The World Bank Central Highlands Connectivity Improvement Project (P159238) REPORT NO.: RES56449 RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING OF CENTRAL HIGHLANDS CONNECTIVITY IMPROVEMENT PROJECT APPROVED ON JUNE 22, 2017 TO SOCIALIST REPUBLIC OF VIET NAM TRANSPORT EAST ASIA AND PACIFIC Regional Vice President: Manuela V. Ferro Country Director: Mariam J. Sherman Regional Director: Sudeshna Ghosh Banerjee Practice Manager/Manager: Benedictus Eijbergen Task Team Leader(s): Chi Kien Nguyen, Leslie Nii Odartey Mills The World Bank Central Highlands Connectivity Improvement Project (P159238) ABBREVIATIONS AND ACRONYMS GoV Government of Viet Nam IDA International Development Association MOT Ministry Of Transport ODA Overseas Development Assistance PDO Project Development Objective PMU2 Project Management Unit No.2 SDR Special Drawing Rights XDR Currency Code for Special Drawing Rights The World Bank Central Highlands Connectivity Improvement Project (P159238) BASIC DATA Product Information Project ID Financing Instrument P159238 Investment Project Financing Original EA Category Current EA Category Partial Assessment (B) Partial Assessment (B) Approval Date Current Closing Date 22-Jun-2017 31-Dec-2024 Organizations Borrower Responsible Agency Socialist Republic of Viet Nam Project Development Objective (PDO) Original PDO To improve the connectivity, safety and climate-resilience of the National Highway 19. OPS_TABLE_PDO_CURRENTPDO Summary Status of Financing (US$, Millions) Net Ln/Cr/Tf Approval Signing Effectiveness Closing Commitment Disbursed Undisbursed IDA-61080 22-Jun-2017 27-Dec-2017 22-May-2018 31-Dec-2024 140.50 94.66 42.90 IDA-61090 22-Jun-2017 27-Dec-2017 22-May-2018 31-Dec-2024 9.50 0 9.23 Policy Waiver(s) Does this restructuring trigger the need for any policy waiver(s)? No The World Bank Central Highlands Connectivity Improvement Project (P159238) I. PROJECT STATUS AND RATIONALE FOR RESTRUCTURING 1. This restructuring paper seeks the approval of a Level 2 restructuring of the Central Highlands Connectivity Improvement Project (P159238). The restructuring proposes to partially cancel an amount equivalent to SDR 14,981,764 of the IDA Credit No. 6108 & IDA Credit No. 6109 based on estimated project savings. 2. The proposed restructuring does not change the Project Development Objective (PDO). No new activities are proposed outside the scope of the Financing Agreement, and no changes to the Results Framework are proposed. The environmental and social (E&S) safeguards classification remains “Category B”, and there are no changes to the safeguards policies triggered. The proposed restructuring is in response to the Ministry of Finance’s (MOF) letter to the IDA, dated April 25, 2024 received by the IDA on May 2, 2024. This proposed cancellation would be the second restructuring of the project. A. Project Background 3. The IDA’s Board of Executive Directors approved the financing for the Central Highlands Connectivity Improvement Project (CHCIP) on June 22, 2017, with financing comprised of two credits from the International Development Association (IDA Credit No. 6108 & IDA Credit No. 6109), totaling SDR 109.4 million (US$150 million equivalent).1 The Financing Agreement for CHCIP was declared effective on May 22, 2018 with an original closing date of June 30, 2023 which was retroactively extended to December 31, 2024 on August 2, 2023. The extension accommodated delays in accessing counterpart funding. 4. The project development objective (PDO) is to improve the connectivity, safety, and climate-resilience of the National Highway 19. CHCIP comprises two components: (i) Component 1: Road Improvements (estimated cost of US$145 million, IDA: US$141.3 million). This component supports the physical improvement of three sections of National Highway (NH) 19 including pavement rehabilitation, widening of the road with paved shoulders, widening of lanes and features for the safe sharing of the road by users, including through the addition of dedicated motorcycle lanes, and reinforcement of slopes, to improve road connectivity, safety and to ensure sustainability of road assets. (ii) Component 2: Implementation Support (estimated costs of US$8.7 million, IDA: US$8.7 million). This component provides technical support for Project implementation, including detailed engineering design, construction supervision, financial audits, environmental and social management, and monitoring and evaluation. B. Summary of Project Status 1 The project financing includes SDR 102,500,000 under IDA Credit 6108 and SDR 6,900,000 under IDA Credit 6109. The World Bank Central Highlands Connectivity Improvement Project (P159238) 5. CHCIP is currently rated Moderately Satisfactory for both Development Objective and Project Implementation. progress towards achievement of PDO and overall implementation progress is currently Moderately Satisfactory. The safeguards rating is Moderately Satisfactory, and overall risk is Moderate. The status of project components is as follows: 6. Component 1: Road Improvements. Progress of Civil Works (CWs) - The project consists of eight civil works contracts of which, as of end-March 2024, four contracts CW 3, 5, 6 and 7 have been completed. The remaining four contracts, CW 1, 2 and 4A, 4B, are under implementation at different pace of works ranging from 59 to 94 percent. Contracts CW 2, 4A and 4B are scheduled to be completed no later than end-June 2024; and the least advanced contract CW1, is rescheduled to be completed or prior to project closing, subject to the resolution of outstanding land acquisition issues by end-May 2024. i. Delays in land acquisition and compensation: 37 affected households in Tay Son district of Binh Dinh province have not been compensated, and relocation of utilities are yet to be completed, further delaying the remaining land acquisition and resettlement. The delays in handing over the sites continue to impact civil works implementation under contract CW1. MOT and Project Management Unit No.2 (PMU2) are working with the local authorities to finalize the updated compensation plan, pay compensation to the remaining households, shift the powerlines and hand over the sites to the contractor no later than end-May 2024. An assessment on the timeframe to complete the civil works contract for CW1 will be conducted following the current deadline. ii. Component 2: Implementation Support: The external financial auditor and independent environmental and social safeguards monitoring consultant have been maintaining satisfactory performance. The construction supervision consultants (CSC) have deployed all technical staff, a key position of a geotechnical engineer to support implementation of the technically highly challenging slope works at the An Khe pass since March 2023 is still unfilled. PMU2 and the CSC are collaborating to ensure the hiring of the technical experts. 7. Fiduciary and E&S Summary. The project is in compliance with all legal covenants and fiduciary and E&S requirements. 8. Disbursement and savings. As of April 30, 2024, the project has disbursed US$ 94.7 million from the IDA Credit IDA-6108 (64.5 percent) and IDA Credit IDA-6109 (0.0 percent). Based on MOT/PMU2’s current estimates, there are project savings in the amount of approximately US$20.5 million. The savings are a result of: (i) procurement savings; (ii) favorable changes in the exchange rate from USD to VND; and (iii) unused contingencies. 9. Procurement, Financial Management (FM) and M&E. The procurement performance rating remains Moderately Satisfactory with completion of procurement of all civil works. The performance rating for FM and counterpart funding are rated Satisfactory. 10. Environmental and Social Safeguards. The project’s overall safeguards rating is currently Moderately Satisfactory. As part of the proposed restructuring, no additional Safeguards policies are triggered, and there will be no change to the current “Category B” safeguards classification. The World Bank Central Highlands Connectivity Improvement Project (P159238) 11. Project management is rated moderately satisfactory due to pending land acquisition issues. The Monitoring and Evaluation rating remains Moderately Satisfactory due to delay in recruitment of consultant to perform the iRAP rating for PDO indicator 3. 12. The overall risk rating is moderate due to environment and social issues. C. Rationale for Project Restructuring 13. The project’s financing will not be fully utilized by the closing date of December 31, 2024. The Ministry of Finance, in its letter dated April 25, 2024, has requested a cancellation of SDR 14,981,764. This amount is expected to be recommitted to finance other project(s) in Viet Nam before the current project closing date. II. DESCRIPTION OF PROPOSED CHANGES 14. The proposed changes include: (a) partial cancelation of SDR 14,981,764 from Credits IDA-6108 and IDA-6109; and (b) revisions to the disbursement estimates to reflect the partial cancellation. Table 1 summarizes the values of the credits in SDR, the amounts to be cancelled through this Level 2 Restructuring. Table 1. Financing Summary Amount of Credit Allocation Cancellation Amount (SDR) (SDR) Category Portion A Portion B Portion A Portion B IDA-6108 IDA-6109 IDA-6108 IDA-6109 (1) Goods, works, non-consulting 90,100,000 6,900,000 8,081,764 6,900,000 services, and consulting services under the Project (2) Resettlement Compensation 12,400,00 0 0 0 required for Part 1 of the Project 102,500,000 6,900,000 8,081,764 6,900,000 TOTAL AMOUNT 109,400,000 14,981,764 15. Disbursement Schedule. The disbursement schedule has been adjusted to reflect the reduced financing after the partial cancellation and is shown in Section IV. Detailed Changes below. The World Bank Central Highlands Connectivity Improvement Project (P159238) III. SUMMARY OF CHANGES Changed Not Changed Components and Cost ✔ Cancellations Proposed ✔ Reallocation between Disbursement Categories ✔ Disbursement Estimates ✔ Implementing Agency ✔ DDO Status ✔ Project's Development Objectives ✔ Results Framework ✔ Loan Closing Date(s) ✔ Disbursements Arrangements ✔ Overall Risk Rating ✔ Safeguard Policies Triggered ✔ EA category ✔ Legal Covenants ✔ Institutional Arrangements ✔ Financial Management ✔ Procurement ✔ Implementation Schedule ✔ Other Change(s) ✔ Economic and Financial Analysis ✔ Technical Analysis ✔ Social Analysis ✔ Environmental Analysis ✔ IV. DETAILED CHANGE(S) The World Bank Central Highlands Connectivity Improvement Project (P159238) OPS_DETAILEDCHANGES_COMPONENTS_TABLE COMPONENTS Current Current Proposed Proposed Cost Action Component Name Component Name Cost (US$M) (US$M) Road Improvements 145.00 Revised Road Improvements 124.50 Implementation Support 8.70 No Change Implementation Support 8.70 TOTAL 153.70 133.20 OPS_DETAILEDCHANGES_CANCELLATIONS_TABLE CANCELLATIONS Value Reason Current Cancellation New Ln/Cr/Tf Status Currency Date of for Amount Amount Amount Cancellation Cancellation BORROWER' Disburs S REQUEST IDA-61080- 102,500,000.0 ing&Re XDR 8,081,764.00 25-Apr-2024 94,418,236.00 FOR 001 0 paying COUNTRY REASONS BORROWER' S REQUEST IDA-61090- Effectiv XDR 6,900,000.00 6,900,000.00 25-Apr-2024 0.00 FOR 001 e COUNTRY REASONS OPS_DETAILEDCHANGES_REALLOCATION _TABLE REALLOCATION BETWEEN DISBURSEMENT CATEGORIES Financing % Current Allocation Actuals + Committed Proposed Allocation (Type Total) Current Proposed IDA-61080-001 | Currency: XDR iLap Category Sequence No: 1 Current Expenditure Category: GDS, CW, Non CS, CS 90,100,000.00 55,145,101.99 82,018,236.00 100.00 100.00 iLap Category Sequence No: 2 Current Expenditure Category: Resetlmt compensation P1 The World Bank Central Highlands Connectivity Improvement Project (P159238) 12,400,000.00 8,914,697.52 12,400,000.00 100.00 100.00 Total 102,500,000.00 64,059,799.51 94,418,236.00 IDA-61090-001 | Currency: XDR iLap Category Sequence No: 1 Current Expenditure Category: GDS, CW, Non CS, CS 6,900,000.00 0.00 0.00 100.00 0 Total 6,900,000.00 0.00 0.00 OPS_DETAILEDCHANGES_DISBURSEMENT_TABLE DISBURSEMENT ESTIMATES Change in Disbursement Estimates Yes Year Current Proposed 2018 6,040,000.00 0.00 2019 28,550,000.00 0.00 2020 43,180,000.00 0.00 2021 35,260,000.00 3,897,000.00 2022 26,550,000.00 36,040,000.00 2023 10,420,000.00 26,514,000.00 2024 0.00 40,000,000.00 2025 0.00 23,006,650.00 .