The World Bank
       Central Highlands Connectivity Improvement Project (P159238)




                                                                                                REPORT NO.: RES56449




                                             RESTRUCTURING PAPER

                                                      ON A

                                      PROPOSED PROJECT RESTRUCTURING

                                                          OF
                           CENTRAL HIGHLANDS CONNECTIVITY IMPROVEMENT PROJECT
                                          APPROVED ON JUNE 22, 2017
                                                          TO

                                        SOCIALIST REPUBLIC OF VIET NAM



TRANSPORT

EAST ASIA AND PACIFIC




                               Regional Vice President:    Manuela V. Ferro
                                     Country Director:     Mariam J. Sherman
                                     Regional Director:    Sudeshna Ghosh Banerjee
                           Practice Manager/Manager:       Benedictus Eijbergen
                                  Task Team Leader(s):     Chi Kien Nguyen, Leslie Nii Odartey Mills
       The World Bank
       Central Highlands Connectivity Improvement Project (P159238)



ABBREVIATIONS AND ACRONYMS

GoV             Government of Viet Nam
IDA             International Development Association
MOT             Ministry Of Transport
ODA             Overseas Development Assistance
PDO             Project Development Objective
PMU2            Project Management Unit No.2
SDR             Special Drawing Rights
XDR             Currency Code for Special Drawing Rights
           The World Bank
           Central Highlands Connectivity Improvement Project (P159238)




BASIC DATA


Product Information

Project ID                                                     Financing Instrument
P159238                                                        Investment Project Financing

Original EA Category                                           Current EA Category
Partial Assessment (B)                                         Partial Assessment (B)

Approval Date                                                  Current Closing Date
22-Jun-2017                                                    31-Dec-2024


Organizations

Borrower                                                       Responsible Agency
Socialist Republic of Viet Nam



Project Development Objective (PDO)
Original PDO
To improve the connectivity, safety and climate-resilience of the National Highway 19.
OPS_TABLE_PDO_CURRENTPDO
Summary Status of Financing (US$, Millions)
                                                                                         Net
Ln/Cr/Tf                  Approval        Signing Effectiveness           Closing Commitment Disbursed Undisbursed

IDA-61080              22-Jun-2017 27-Dec-2017 22-May-2018 31-Dec-2024                   140.50   94.66      42.90
IDA-61090              22-Jun-2017 27-Dec-2017 22-May-2018 31-Dec-2024                     9.50      0        9.23

Policy Waiver(s)

Does this restructuring trigger the need for any policy waiver(s)?
No
            The World Bank
            Central Highlands Connectivity Improvement Project (P159238)




    I. PROJECT STATUS AND RATIONALE FOR RESTRUCTURING

     1. This restructuring paper seeks the approval of a Level 2 restructuring of the Central Highlands Connectivity
        Improvement Project (P159238). The restructuring proposes to partially cancel an amount equivalent to SDR
        14,981,764 of the IDA Credit No. 6108 & IDA Credit No. 6109 based on estimated project savings.

     2. The proposed restructuring does not change the Project Development Objective (PDO). No new activities are
        proposed outside the scope of the Financing Agreement, and no changes to the Results Framework are proposed.
        The environmental and social (E&S) safeguards classification remains “Category B”, and there are no changes to
        the safeguards policies triggered. The proposed restructuring is in response to the Ministry of Finance’s (MOF)
        letter to the IDA, dated April 25, 2024 received by the IDA on May 2, 2024. This proposed cancellation would be
        the second restructuring of the project.

A. Project Background

     3. The IDA’s Board of Executive Directors approved the financing for the Central Highlands Connectivity Improvement
        Project (CHCIP) on June 22, 2017, with financing comprised of two credits from the International Development
        Association (IDA Credit No. 6108 & IDA Credit No. 6109), totaling SDR 109.4 million (US$150 million equivalent).1
        The Financing Agreement for CHCIP was declared effective on May 22, 2018 with an original closing date of June
        30, 2023 which was retroactively extended to December 31, 2024 on August 2, 2023. The extension accommodated
        delays in accessing counterpart funding.

     4. The project development objective (PDO) is to improve the connectivity, safety, and climate-resilience of the
        National Highway 19. CHCIP comprises two components:

              (i) Component 1: Road Improvements (estimated cost of US$145 million, IDA: US$141.3 million). This
              component supports the physical improvement of three sections of National Highway (NH) 19 including
              pavement rehabilitation, widening of the road with paved shoulders, widening of lanes and features for the
              safe sharing of the road by users, including through the addition of dedicated motorcycle lanes, and
              reinforcement of slopes, to improve road connectivity, safety and to ensure sustainability of road assets.

              (ii) Component 2: Implementation Support (estimated costs of US$8.7 million, IDA: US$8.7 million). This
              component provides technical support for Project implementation, including detailed engineering design,
              construction supervision, financial audits, environmental and social management, and monitoring and
              evaluation.

B. Summary of Project Status



1   The project financing includes SDR 102,500,000 under IDA Credit 6108 and SDR 6,900,000 under IDA Credit 6109.
      The World Bank
      Central Highlands Connectivity Improvement Project (P159238)


5. CHCIP is currently rated Moderately Satisfactory for both Development Objective and Project Implementation.
   progress towards achievement of PDO and overall implementation progress is currently Moderately Satisfactory.
   The safeguards rating is Moderately Satisfactory, and overall risk is Moderate. The status of project components is
   as follows:

6. Component 1: Road Improvements. Progress of Civil Works (CWs) - The project consists of eight civil works
   contracts of which, as of end-March 2024, four contracts CW 3, 5, 6 and 7 have been completed. The remaining
   four contracts, CW 1, 2 and 4A, 4B, are under implementation at different pace of works ranging from 59 to 94
   percent. Contracts CW 2, 4A and 4B are scheduled to be completed no later than end-June 2024; and the least
   advanced contract CW1, is rescheduled to be completed or prior to project closing, subject to the resolution of
   outstanding land acquisition issues by end-May 2024.

        i. Delays in land acquisition and compensation: 37 affected households in Tay Son district of Binh Dinh
        province have not been compensated, and relocation of utilities are yet to be completed, further delaying the
        remaining land acquisition and resettlement. The delays in handing over the sites continue to impact civil works
        implementation under contract CW1. MOT and Project Management Unit No.2 (PMU2) are working with the
        local authorities to finalize the updated compensation plan, pay compensation to the remaining households,
        shift the powerlines and hand over the sites to the contractor no later than end-May 2024. An assessment on
        the timeframe to complete the civil works contract for CW1 will be conducted following the current deadline.

        ii. Component 2: Implementation Support: The external financial auditor and independent environmental and
        social safeguards monitoring consultant have been maintaining satisfactory performance. The construction
        supervision consultants (CSC) have deployed all technical staff, a key position of a geotechnical engineer to
        support implementation of the technically highly challenging slope works at the An Khe pass since March 2023
        is still unfilled. PMU2 and the CSC are collaborating to ensure the hiring of the technical experts.

7. Fiduciary and E&S Summary. The project is in compliance with all legal covenants and fiduciary and E&S
   requirements.

8. Disbursement and savings. As of April 30, 2024, the project has disbursed US$ 94.7 million from the IDA Credit
   IDA-6108 (64.5 percent) and IDA Credit IDA-6109 (0.0 percent). Based on MOT/PMU2’s current estimates, there
   are project savings in the amount of approximately US$20.5 million. The savings are a result of: (i) procurement
   savings; (ii) favorable changes in the exchange rate from USD to VND; and (iii) unused contingencies.

9. Procurement, Financial Management (FM) and M&E. The procurement performance rating remains Moderately
   Satisfactory with completion of procurement of all civil works. The performance rating for FM and counterpart
   funding are rated Satisfactory.

10. Environmental and Social Safeguards. The project’s overall safeguards rating is currently Moderately Satisfactory.
    As part of the proposed restructuring, no additional Safeguards policies are triggered, and there will be no change
    to the current “Category B” safeguards classification.
         The World Bank
         Central Highlands Connectivity Improvement Project (P159238)


  11. Project management is rated moderately satisfactory due to pending land acquisition issues. The Monitoring and
      Evaluation rating remains Moderately Satisfactory due to delay in recruitment of consultant to perform the iRAP
      rating for PDO indicator 3.

  12. The overall risk rating is moderate due to environment and social issues.

C. Rationale for Project Restructuring

  13. The project’s financing will not be fully utilized by the closing date of December 31, 2024. The Ministry of Finance,
      in its letter dated April 25, 2024, has requested a cancellation of SDR 14,981,764. This amount is expected to be
      recommitted to finance other project(s) in Viet Nam before the current project closing date.


II. DESCRIPTION OF PROPOSED CHANGES

  14. The proposed changes include: (a) partial cancelation of SDR 14,981,764 from Credits IDA-6108 and IDA-6109; and
      (b) revisions to the disbursement estimates to reflect the partial cancellation. Table 1 summarizes the values of the
      credits in SDR, the amounts to be cancelled through this Level 2 Restructuring.

                                                  Table 1. Financing Summary

                                                  Amount of Credit Allocation              Cancellation Amount
                                                            (SDR)                                  (SDR)
                      Category
                                                    Portion A       Portion B          Portion A             Portion B
                                                    IDA-6108        IDA-6109           IDA-6108              IDA-6109
         (1)    Goods, works, non-consulting       90,100,000       6,900,000          8,081,764            6,900,000
        services, and consulting services under
        the Project

         (2)    Resettlement Compensation          12,400,00             0                 0                    0
        required for Part 1 of the Project

                                                  102,500,000       6,900,000          8,081,764            6,900,000
        TOTAL AMOUNT
                                                          109,400,000                           14,981,764

  15. Disbursement Schedule. The disbursement schedule has been adjusted to reflect the reduced financing after the
      partial cancellation and is shown in Section IV. Detailed Changes below.
        The World Bank
        Central Highlands Connectivity Improvement Project (P159238)



III. SUMMARY OF CHANGES

                                                                 Changed   Not Changed
Components and Cost                                                    ✔
Cancellations Proposed                                                 ✔
Reallocation between Disbursement Categories                           ✔
Disbursement Estimates                                                 ✔
Implementing Agency                                                            ✔
DDO Status                                                                     ✔
Project's Development Objectives                                               ✔
Results Framework                                                              ✔
Loan Closing Date(s)                                                           ✔
Disbursements Arrangements                                                     ✔
Overall Risk Rating                                                            ✔
Safeguard Policies Triggered                                                   ✔
EA category                                                                    ✔
Legal Covenants                                                                ✔
Institutional Arrangements                                                     ✔
Financial Management                                                           ✔
Procurement                                                                    ✔
Implementation Schedule                                                        ✔
Other Change(s)                                                                ✔
Economic and Financial Analysis                                                ✔
Technical Analysis                                                             ✔
Social Analysis                                                                ✔
Environmental Analysis                                                         ✔


IV. DETAILED CHANGE(S)
                                                  The World Bank
                                                  Central Highlands Connectivity Improvement Project (P159238)


          OPS_DETAILEDCHANGES_COMPONENTS_TABLE




          COMPONENTS
                                                                                 Current
          Current                                                                                             Proposed                                Proposed
                                                                                    Cost             Action
          Component Name                                                                                      Component Name                        Cost (US$M)
                                                                                 (US$M)
            Road Improvements                                                     145.00         Revised      Road Improvements                             124.50

            Implementation Support                                                   8.70     No Change       Implementation Support                          8.70

            TOTAL                                                                 153.70                                                                    133.20



        OPS_DETAILEDCHANGES_CANCELLATIONS_TABLE




        CANCELLATIONS


                                                                                                                        Value                            Reason
                                                                                   Current      Cancellation                               New
          Ln/Cr/Tf                                      Status     Currency                                           Date of                                for
                                                                                   Amount          Amount                                Amount
                                                                                                                  Cancellation                      Cancellation
                                                                                                                                                    BORROWER'
                                                        Disburs                                                                                      S REQUEST
          IDA-61080-                                                          102,500,000.0
                                                        ing&Re     XDR                         8,081,764.00       25-Apr-2024       94,418,236.00           FOR
          001                                                                             0
                                                        paying                                                                                        COUNTRY
                                                                                                                                                       REASONS
                                                                                                                                                    BORROWER'
                                                                                                                                                     S REQUEST
          IDA-61090-                                    Effectiv
                                                                   XDR         6,900,000.00    6,900,000.00       25-Apr-2024                0.00           FOR
          001                                           e
                                                                                                                                                      COUNTRY
                                                                                                                                                       REASONS
OPS_DETAILEDCHANGES_REALLOCATION _TABLE




          REALLOCATION BETWEEN DISBURSEMENT CATEGORIES

                                                                                                                                             Financing %
                                                   Current Allocation         Actuals + Committed             Proposed Allocation
                                                                                                                                             (Type Total)
                                                                                                                                          Current      Proposed

          IDA-61080-001                                  |   Currency: XDR

         iLap Category Sequence No: 1                                             Current Expenditure Category: GDS, CW, Non CS, CS

                                                       90,100,000.00                 55,145,101.99                 82,018,236.00          100.00            100.00


         iLap Category Sequence No: 2                                             Current Expenditure Category: Resetlmt compensation P1
                                             The World Bank
                                             Central Highlands Connectivity Improvement Project (P159238)



                                                  12,400,000.00                  8,914,697.52               12,400,000.00        100.00            100.00


    Total                                        102,500,000.00                 64,059,799.51                94,418,236.00



    IDA-61090-001                                   |   Currency: XDR

    iLap Category Sequence No: 1                                             Current Expenditure Category: GDS, CW, Non CS, CS

                                                   6,900,000.00                          0.00                         0.00       100.00                   0


    Total                                          6,900,000.00                          0.00                         0.00

    OPS_DETAILEDCHANGES_DISBURSEMENT_TABLE




    DISBURSEMENT ESTIMATES

    Change in Disbursement Estimates
    Yes

          Year                                                                                          Current                               Proposed
          2018                                                                                     6,040,000.00                                    0.00

          2019                                                                                    28,550,000.00                                    0.00

          2020                                                                                    43,180,000.00                                    0.00

          2021                                                                                    35,260,000.00                            3,897,000.00

          2022                                                                                    26,550,000.00                           36,040,000.00

          2023                                                                                    10,420,000.00                           26,514,000.00

          2024                                                                                              0.00                          40,000,000.00

          2025                                                                                              0.00                          23,006,650.00

.