PROCUREMENT PLAN (Textual Part) Project information: BRAZIL - São Paulo Aricanduva BRT Corridor (P169140) Project Implementation agencies: Secretaria Municipal de Mobilidade e Transportes and Secretaria Municipal de Infraestrutura Urbana e Obras Date of the Procurement Plan: December 1, 2020 Period covered by this Procurement Plan: 2021-2022 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in Law 8,666/93 and Law 10,520/02such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. 1) Use of the sample bidding documents agreed with by the Bank for e-auction under Law 10,520/02 and 2) Procedures for Concorrencia (open competition), Tomada de Preços (limited competition) and Convite (Request for Quotation and Shopping) may be used provided that the Letter of Acceptance of Anticorruption Guidelines and Sanctions Regime Letter is signed and that the following points are discussed and included in the PPSD and/or the Procurement Plan: a. The option prohibiting joint ventures shall not to be exercised; b. The requirement of certificate of operation for foreign firms shall only apply to foreign firms that are already established in the Brazil; c. The correction of price through clarification shall only apply with respect to misquoted taxes; d. Rejection of bids due to the application of maximum price shall only apply if the PPSD and/or the Procurement Plan confirm that contract price reference is acceptable to the Bank; e. In admeasurement contracts, rejection of bids for exceeding maximum unit price shall only apply for items individually weighing more than 10% of the total price; and f. The forms and conditions of contract of Bank’s SPDs shall be used for Works contracts. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: “Not Applicable”; Works: “Not Applicable” Other Relevant Procurement Information. “Not Applicable” PROCUREMENT Brazil : São Paulo Aricanduva Bus Rapid Transit Corridor PLAN General Information Country: Brazil 2023-05-17 Bank’s Approval Date of the Original Procurement Plan: 2023-05-17 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P169140 GPN Date: Project Name: São Paulo Aricanduva Bus Rapid Transit Corridor Loan / Credit No: IBRD / 90810 Office of the Controller General of the Municipality of Sao Paulo Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BR-CGM-SP-354845-NC-DIR / Project management and ca Implementaç Curso COSO ICIF 2013 - Curs IBRD / 90810 pacity building on transport Posterior Aquisição Direta Direct - National 4,192.20 0.00 2024-07-15 2024-07-30 2024-09-13 2024-12-31 ão Pendente o sobre avaliação de riscos n planning and policies os controles. BR-CGM-SP-354856-NC-RFP / Project management and ca Sistema de Auditoria 2/2 - De Solicitação de Pro Single Stage - Two E Implementaç IBRD / 90810 pacity building on transport Prévia Open - National 104,132.31 0.00 2023-11-15 2024-02-28 2024-03-29 2023-11-30 2024-05-20 2024-09-07 2026-01-15 senvolvimento, Internalizaçã postas nvelope ão Pendente planning and policies o e Manutenção de Sistema de Auditoria BR-CGM-SP-357463-NC-DIR / Contratação de licença doAut Development of a high-quali Implementaç oCAD: software CAD 2D e 3D IBRD / 90810 ty BRT system on the Arican Posterior Aquisição Direta Direct - National 1,604.42 0.00 2023-06-01 2023-07-01 2023-07-27 2023-12-31 ão Pendente - ferramentas de projeto duva Corridor 1 licença por 1 ano BR-CGM-SP-357466-NC-DIR / Contratação de licença doAut Development of a high-quali Implementaç oCAD: software CAD 2D e 3D IBRD / 90810 ty BRT system on the Arican Posterior Aquisição Direta Direct - National 4,813.25 0.00 2024-01-06 2024-02-05 2024-03-02 2024-12-31 ão Pendente - ferramentas de projeto duva Corridor 1 licença por 3 anos BR-CGM-SP-357467-NC-DIR / Development of a high-quali Implementaç Aquisição de licença Project IBRD / 90810 ty BRT system on the Arican Posterior Aquisição Direta Direct - National 1,796.66 0.00 2023-06-01 2023-07-01 2023-07-27 2023-12-31 ão Pendente Professional 2021 - compra ú duva Corridor nica BR-CGM-SP-357472-NC-DIR / Development of a high-quali Contratação de licença de So Implementaç IBRD / 90810 ty BRT system on the Arican Posterior Aquisição Direta Direct - National 4,990.72 0.00 2023-05-06 2023-06-05 2023-07-01 2023-12-31 ftware estatístico - Minitab lic ão Pendente duva Corridor ença Licença para 3 anos BR-CGM-SP-357475-NC-DIR / COSO ICIF 2013 - Taxa de Ad Development of a high-quali Implementaç esão/Restabelecimento - Tax IBRD / 90810 ty BRT system on the Arican Posterior Aquisição Direta Direct - National 349.35 0.00 2024-07-15 2024-08-14 2024-09-09 2024-12-31 ão Pendente a de adesão ao IIA brasil par duva Corridor a a realização do Curso COS O ICIF 2013 BR-CGM-SP-357477-NC-DIR / COSO ERM 2017 - Taxa de ad Development of a high-quali Implementaç esão/Restabelecimento - Tax IBRD / 90810 ty BRT system on the Arican Posterior Aquisição Direta Direct - National 499.07 0.00 2024-02-15 2024-03-16 2024-04-11 2024-07-31 ão Pendente a de adesão ao IIA brasil par duva Corridor a a realização do Curso COS O ERM 2017 BR-CGM-SP-357479-NC-DIR / COSO ERM 2017 - Curso sobr e Gestão de Risco Organizaci Development of a high-quali Implementaç onais. A previsão para os cur IBRD / 90810 ty BRT system on the Arican Posterior Aquisição Direta Direct - National 5,988.86 0.00 2024-02-15 2024-03-16 2024-04-11 2024-07-31 ão Pendente sos está no período de um an duva Corridor o pois dependemos da abert ura das inscrições para os ref eridos curso. BR-CGM-SP-357481-NC-DIR / Development of a high-quali IIA AudiTI - Taxa de Adesão/R Implementaç IBRD / 90810 ty BRT system on the Arican Posterior Aquisição Direta Direct - National 299.04 0.00 2024-07-01 2024-07-31 2024-08-26 2024-10-31 estabelecimento - xa de ades ão Pendente duva Corridor ão ao IIA brasil para a realiza ção do Curso AudiTI BR-CGM-SP-357483-NC-DIR / IIA AudiTI - Curso (TI) - Curso sobre avaliação de risco e co Development of a high-quali Implementaç ntroles de TI. A previsão para IBRD / 90810 ty BRT system on the Arican Posterior Aquisição Direta Direct - National 3,114.21 0.00 2023-07-01 2023-07-31 2023-08-26 2023-10-31 ão Pendente os cursos está no período de duva Corridor um ano pois dependemos da abertura das inscrições para os referidos curso. BR-CGM-SP-357485-NC-DIR / IIA AUDI EOP1 - Taxa de Ades Development of a high-quali Implementaç ão/Restabelecimento - Taxa IBRD / 90810 ty BRT system on the Arican Posterior Aquisição Direta Direct - National 748.61 0.00 2024-02-15 2024-03-16 2024-04-11 2024-07-31 ão Pendente de adesão ao IIA brasil para duva Corridor a realização do CursoAUDI E OP 1 BR-CGM-SP-357487-NC-DIR / IIA AUDI EOP1 - Curso (Audito ria Pública-Interna) - Curso d Development of a high-quali e capacitação em conceitos, Implementaç IBRD / 90810 ty BRT system on the Arican Posterior Aquisição Direta Direct - National 7,486.08 0.00 2024-02-15 2024-03-16 2024-04-11 2024-07-31 procedimentos, técnicas e m ão Pendente duva Corridor etodologias necessárias para o desempenho das responsa bilidades na auditoria interna governamental . Page 1 BR-CGM-SP-357489-NC-DIR / AUDI EOP2 - Taxa de Adesão/ Development of a high-quali Implementaç Restabelecimento - Taxa de IBRD / 90810 ty BRT system on the Arican Posterior Aquisição Direta Direct - National 748.61 0.00 2024-02-15 2024-03-16 2024-04-11 2024-07-31 ão Pendente adesão ao IIA brasil para a re duva Corridor alização do CursoAUDI EOP 2 BR-CGM-SP-357491-NC-DIR / IIA AUDI EOP2 - Curso - Curso de capacitação em conceitos sobre riscos, transparência e Development of a high-quali Implementaç governança, além de abordar IBRD / 90810 ty BRT system on the Arican Posterior Aquisição Direta Direct - National 7,486.08 0.00 2024-02-15 2024-03-16 2024-04-11 2024-07-31 ão Pendente o planejamento estratégico e duva Corridor garantia de qualidade da aud itoria interna e técnicas para a execução de auditoria inter na baseadas em riscos BR-CGM-SP-357494-NC-DIR / Development of a high-quali CIA I - Taxa de Adesão/Resta Implementaç IBRD / 90810 ty BRT system on the Arican Posterior Aquisição Direta Direct - National 99.81 0.00 2023-10-05 2023-11-04 2023-11-30 2023-12-31 belecimento - Taxa de adesã ão Pendente duva Corridor o ao IIA brasil para a realizaç ão do Curso CIA I BR-CGM-SP-357496-NC-DIR / Development of a high-quali CIA I - Taxa de Habilitação - T Implementaç IBRD / 90810 ty BRT system on the Arican Posterior Aquisição Direta Direct - National 159.70 0.00 2023-10-05 2023-11-04 2023-11-30 2023-12-31 axa de adesão ao IIA brasil p ão Pendente duva Corridor ara a realização do Curso e E xame CIA I BR-CGM-SP-357500-NC-DIR / Development of a high-quali Implementaç CIA I - Certificação - Certifica IBRD / 90810 ty BRT system on the Arican Posterior Aquisição Direta Direct - National 435.19 0.00 2023-10-05 2023-11-04 2023-11-30 2023-12-31 ão Pendente ção para a realização do Curs duva Corridor o e Exame CIA I BR-CGM-SP-357502-NC-DIR / CIA I - Curso - Curso de capa citação dos auditores com o objetivo de preparar o profiss Development of a high-quali Implementaç ional de Auditoria Interna par IBRD / 90810 ty BRT system on the Arican Posterior Aquisição Direta Direct - National 1,397.40 0.00 2023-10-05 2023-11-04 2023-11-30 2023-12-31 ão Pendente a a realização do Exame CIA duva Corridor - Parte 1 conferindo ganhos d e qualidade, tanto ao profissi onal, quanto para as Atividad es de Auditoria . BR-CGM-SP-357508-NC-DIR / Development of a high-quali CIA II - Taxa de Adesão/Resta Implementaç IBRD / 90810 ty BRT system on the Arican Posterior Aquisição Direta Direct - National 79.85 0.00 2024-02-15 2024-03-16 2024-04-11 2024-07-31 belecimento - Taxa de adesã ão Pendente duva Corridor o ao IIA brasil para a realizaç ão do Curso CIA II BR-CGM-SP-357510-NC-DIR / Development of a high-quali CIA II - Taxa de Habilitação - Implementaç IBRD / 90810 ty BRT system on the Arican Posterior Aquisição Direta Direct - National 159.70 0.00 2024-02-15 2024-03-16 2024-04-11 2024-07-31 Taxa de adesão ao IIA brasil ão Pendente duva Corridor para a realização do Curso e Exame CIA II BR-CGM-SP-357521-NC-DIR / Development of a high-quali CIA II - Certificação - Certifica Implementaç IBRD / 90810 ty BRT system on the Arican Posterior Aquisição Direta Direct - National 383.29 0.00 2024-02-15 2024-03-16 2024-04-11 2024-07-31 ção para a realização do Curs ão Pendente duva Corridor o e Exame CIA II BR-CGM-SP-357522-NC-DIR / CIA II - Curso - urso de capaci tação dos auditores com o ob jetivo de preparar o profissio Development of a high-quali Implementaç nal de Auditoria Interna para IBRD / 90810 ty BRT system on the Arican Posterior Aquisição Direta Direct - National 1,477.25 0.00 2024-02-15 2024-03-16 2024-04-11 2024-07-31 ão Pendente a realização do Exame CIA - duva Corridor Parte 2 conferindo ganhos de qualidade, tanto ao profissio nal, quanto para as Atividade s de Auditoria. BR-CGM-SP-357523-NC-DIR / Development of a high-quali CIA III - Taxa de Adesão/Rest Implementaç IBRD / 90810 ty BRT system on the Arican Posterior Aquisição Direta Direct - National 79.85 0.00 2025-02-15 2025-03-17 2025-04-12 2025-07-31 abelecimento - Taxa de ades ão Pendente duva Corridor ão ao IIA brasil para a realiza ção do Curso CIA II BR-CGM-SP-357524-NC-DIR / Development of a high-quali CIA III - Taxa de Habilitação - Implementaç IBRD / 90810 ty BRT system on the Arican Posterior Aquisição Direta Direct - National 159.70 0.00 2025-02-15 2025-03-17 2025-04-12 2025-07-31 Taxa de adesão ao IIA brasil ão Pendente duva Corridor para a realização do Curso e Exame CIA II BR-CGM-SP-357525-NC-DIR / Development of a high-quali CIA III - Certificação - Certific Implementaç IBRD / 90810 ty BRT system on the Arican Posterior Aquisição Direta Direct - National 383.29 0.00 2025-02-15 2025-03-17 2025-04-12 2025-07-31 ação para a realização do Cu ão Pendente duva Corridor rso e Exame CIA II BR-CGM-SP-357527-NC-DIR / CIA III - Curso - Curso de cap acitação dos auditores com o objetivo de preparar o profiss Development of a high-quali Implementaç ional de Auditoria Interna par IBRD / 90810 ty BRT system on the Arican Posterior Aquisição Direta Direct - National 1,557.10 0.00 2025-02-15 2025-03-17 2025-04-12 2025-07-31 ão Pendente a a realização do Exame CIA duva Corridor - Parte 3 conferindo ganhos d e qualidade, tanto ao profissi onal, quanto para as Atividad es de Auditoria. BR-CGM-SP-357528-NC-DIR / Elaboração de Planilhas Orça mentárias - Curso de capacit Development of a high-quali ação de elaboração de Planil Implementaç IBRD / 90810 ty BRT system on the Arican Posterior Aquisição Direta Direct - National 3,593.32 0.00 2024-07-15 2024-08-14 2024-09-09 2024-12-31 has orçamentárias, com apre ão Pendente duva Corridor sentação das boas práticas e dos principais erros cometido s durante a fase de orçament ação de obras. BR-CGM-SP-357529-NC-DIR / BIM para projetos e Obras de Infraestrutura – Módulo 1 - C urso sobre a metodologia BI Development of a high-quali Implementaç M para capacitar os auditore IBRD / 90810 ty BRT system on the Arican Posterior Aquisição Direta Direct - National 1,397.40 0.00 2024-07-15 2024-08-14 2024-09-09 2024-12-31 ão Pendente s de Obras e Serviços de Eng duva Corridor enharia na nova metodologia . A previsão para os cursos e stá no período de um ano poi s dependemos da abertura. BR-CGM-SP-357530-NC-DIR / Gestão de Obras Públicas - A Development of a high-quali previsão para os cursos está Implementaç IBRD / 90810 ty BRT system on the Arican Posterior Aquisição Direta Direct - National 4,791.09 0.00 2023-05-07 2023-06-06 2023-07-02 2023-12-31 no período de um ano pois d ão Pendente duva Corridor ependemos da abertura das i nscrições para os referidos c urso. Page 2 BR-CGM-SP-357531-NC-DIR / Curso Pavimentos Asfálticos - Development of a high-quali A previsão para os cursos est Implementaç IBRD / 90810 ty BRT system on the Arican Posterior Aquisição Direta Direct - National 598.89 0.00 2024-01-03 2024-02-02 2024-02-28 2024-07-31 á no período de um ano pois ão Pendente duva Corridor dependemos da abertura das inscrições para os referidos c urso. BR-CGM-SP-357532-NC-DIR / Curso preparatório para: Insp etor I – Inspeção de Estrutura s de Concreto Segundo ABNT Development of a high-quali Implementaç NBR 16230:2013 (Voltado pa IBRD / 90810 ty BRT system on the Arican Posterior Aquisição Direta Direct - National 998.14 0.00 2024-01-03 2024-02-02 2024-02-28 2025-01-07 ão Pendente ra OAE) - A previsão para os duva Corridor cursos está no período de u m ano pois dependemos da a bertura das inscrições para o s referidos curso. BR-CGM-SP-357533-NC-DIR / Curso preparatório para: Insp etor II – Inspeção de Estrutur as de Concreto Segundo ABN Development of a high-quali Implementaç T NBR 16230:2013 (Voltado IBRD / 90810 ty BRT system on the Arican Posterior Aquisição Direta Direct - National 998.14 0.00 2024-07-15 2024-08-14 2024-09-09 2024-12-31 ão Pendente para OAE) - A previsão para duva Corridor os cursos está no período de um ano pois dependemos da abertura das inscrições para os referidos curso. BR-CGM-SP-357534-NC-DIR / Auditoria Financeira aplicada Development of a high-quali ao setor público - A previsão Implementaç IBRD / 90810 ty BRT system on the Arican Posterior Aquisição Direta Direct - National 1,996.29 0.00 2023-08-01 2023-08-31 2023-09-26 2023-12-31 para os cursos está no períod ão Pendente duva Corridor o de um ano pois dependem os da abertura das inscrições para os referidos curso. BR-CGM-SP-357535-NC-DIR / Avaliação de Pares do IA-CM Development of a high-quali - (despesas de viagem) - Des Implementaç IBRD / 90810 ty BRT system on the Arican Posterior Aquisição Direta Direct - National 1,996.29 0.00 2024-01-15 2024-02-14 2024-03-11 2024-12-31 pesas para que seja realizad ão Pendente duva Corridor a a avaliação para obtenção do certificado nível 2 do IA-C M CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 3