PROCUREMENT PLAN (Textual Part) Project information: [country] [Project name] [P-number] Project Implementation agency: [insert legal name] Date of the Procurement Plan: [insert date] Period covered by this Procurement Plan: [insert from – to period] Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in [insert appropriate references to the national procurement legislation], such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. List only the applicable conditions required to ensure consistency with paragraph 5.4 of the Procurement Regulations. If no conditions apply, delete the phrase “and the following conditions”. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. Otherwise state “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables Otherwise state “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Specify for each Goods: [is not applicable/is applicable for those contracts identified in the Procurement Plan tables]; Works: [is not applicable/is applicable for those contracts identified in the Procurement Plan tables] Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations is Applicable. [Include this sentence only if the Bank has formally agreed to provide the Borrower with HEIS. Otherwise delete] Other Relevant Procurement Information. Provide any other relevant procurement information such as procedures for CDD components, Procurement in Situations of Urgent Need of Assistance or Capacity Constraints etc. PROCUREMENT Western and Central Africa : OMVG Interconnection Project PLAN General Information Country: Western and Central Africa 2016-11-30 Bank’s Approval Date of the Original Procurement Plan: 2023-05-16 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P146830 GPN Date: Project Name: OMVG Interconnection Project Loan / Credit No: IDA / 56590, IDA / 56600, IDA / 56620, IDA / 56610 The Gambia River Basin Development Organization Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Component 1: Extension of ICB/NR L6 / L6 Tanaff Soma Open - Internationa Single Stage - One E 26,200,000.0 20,115,691. 2018-06-2 IDA / 56590 WAPP transmission network A priori Appel d'offres Signé 2015-01-10 2015-03-28 2016-05-31 2015-01-15 2016-10-17 2016-11-25 2016-12-22 2016-12-30 2017-03-08 Birkilane l nvelope 0 58 3 – OMVG Interconnection Component 1: Extension of ICB/NRL7 / L7 Soma - Brikam Open - Internationa Single Stage - One E 40,640,000.0 27,996,573. 2017-06-2 IDA / 56590 WAPP transmission network A priori Appel d'offres Signé 2015-12-15 2016-06-24 2016-10-17 2016-11-25 2016-12-22 2016-12-30 2017-03-09 a l nvelope 0 57 8 – OMVG Interconnection ICB/NRL5 / L5 - Boké - Saltin Component 1: Extension of Open - Internationa Single Stage - One E 73,660,000.0 54,772,293. 2018-06-2 ho - Bambadinca - Mansoa - IDA / 56600 WAPP transmission network A priori Appel d'offres Signé 2016-05-31 2016-08-16 2016-08-16 2016-06-05 2016-10-17 2016-11-25 2016-12-22 2016-12-30 2017-03-09 l nvelope 0 33 3 Tanaff & Mansoa - Bissau – OMVG Interconnection ICB/NRP3 / P3 POSTES BISSA Component 1: Extension of Open - Internationa Single Stage - One E 22,610,000.0 18,468,503. 2018-06-2 U, MANSOA, BAMBADINCA ET IDA / 56620 WAPP transmission network A priori Appel d'offres Signé 2015-12-15 2016-09-04 2016-09-04 2016-06-24 2016-10-17 2016-11-25 2016-12-22 2016-12-30 2017-03-10 l nvelope 0 12 3 SALTHINO – OMVG Interconnection 002/OMVG/PE-OMVG/UGP/S N/02/2019 / Recrutement d'u n opérateur pour de la mise Component 1: Extension of Single Stage - Two E 2019-12-2 en œuvre des activités de re IDA / 56620 WAPP transmission network A posteriori Appel d'offres Open - National 270,000.00 0.00 Annulé 2019-04-19 2019-10-30 2019-04-24 2019-05-22 2019-09-11 2019-06-12 2019-06-26 nvelope 3 boisement, de mise en défen – OMVG Interconnection s et de régénération naturell e des forêts du projet énergi e OMVG au Sénégal 002/OMVG/PE-OMVG/UGP/02 /2019 / MITIGATION OF THE NEGATIVE IMPACTS OF THE C ONSTRUCTION OF SUBSTATI Component 1: Extension of Single Stage - One E 2020-02-0 ONS AND THE INTERCONNEC IDA / 56620 WAPP transmission network A posteriori Appel d'offres Limited 910,000.00 713,875.41 Signé 2019-11-11 2019-11-01 2019-11-16 2019-07-30 2019-12-14 2019-09-11 2019-12-21 2019-11-04 2020-01-04 2020-01-21 nvelope 3 TION LINE OF THE OMVG ENE – OMVG Interconnection RGY PROJECT ON FOREST CO VERS THROUGH REFORESTA TION AND RESTORATION IN S ENEGAL, THE GAMBIA, GUINE A AND GUINEE BISSAU SN-OMVG-293758-CW-DIR / Component 1: Extension of Passation de marc Autre (avec cham 3,727,380.0 2022-12-2 Travaux d’extension du post IDA / 56590 WAPP transmission network A posteriori Direct 3,600,000.00 Signé 2022-05-09 2022-05-26 2022-05-14 2022-05-25 2022-06-23 2022-09-04 hé de gré à gré p d'explication) 0 0 e de Brikama – OMVG Interconnection GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CF20-001 / Acquisition of IT Component 1: Extension of Single Stage - One E En cours d'ex Goods for the Complaints Ma IDA / 56590 WAPP transmission network A posteriori Demande de prix Limited 30,000.00 0.00 2020-01-26 2020-01-21 2020-02-23 2020-03-01 nvelope écution nagement Mechanism Progra – OMVG Interconnection mme SENEGAL MGP CNS CLCS RF Q001/2021 / SENEGAL CNS C Component 1: Extension of LCS Laptop Computers for SE Single Stage - One E IDA / 56620 WAPP transmission network A posteriori Demande de prix Limited 12,000.00 11,189.21 Signé 2021-03-26 2021-03-15 2021-04-08 2021-03-26 2021-04-18 NEGAL CNS and CLCS for acti nvelope – OMVG Interconnection ve participation in the Compl aint Management Mechanism Activity SN-OMVG-241725-GO-RFQ / Laptop Computers for Guinea Component 1: Extension of Single Stage - One E En attente d' CNS and CLCS for active part IDA / 56600 WAPP transmission network A posteriori Demande de prix Limited 12,000.00 0.00 2021-07-03 2021-08-28 2022-02-24 nvelope exécution icipation in the Complaint Ma – OMVG Interconnection nagement Mechanism Activit y SN-OMVG-241728-GO-RFQ / Laptop Computers for GAMBI Component 1: Extension of Single Stage - One E En attente d' A CNS and CLCS for active pa IDA / 56590 WAPP transmission network A posteriori Demande de prix Limited 7,500.00 0.00 2021-07-03 2021-08-28 2022-02-24 nvelope exécution rticipation in the Complaint M – OMVG Interconnection anagement Mechanism Activi ty SN-OMVG-241729-GO-RFQ / Laptop Computers for Guinea Component 1: Extension of Single Stage - One E En attente d' Bissau CNS and CLCS for acti IDA / 56610 WAPP transmission network A posteriori Demande de prix Limited 7,500.00 0.00 2021-07-03 2021-08-28 2022-02-24 nvelope exécution ve participation in the Compl – OMVG Interconnection aint Management Mechanism Activity NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 008/OMVG/PE-OMVG/UGP/12 -2020 / Services d’opérateur Component 2: Technical Assi Open - Internationa Single Stage - Two E IDA / 56590 A priori Appel d'offres 60,000,000.00 0.00 Annulé 2020-12-23 2021-02-03 2021-03-10 2021-03-10 2020-12-28 2021-03-23 2021-05-19 2021-08-01 2021-09-05 2023-02-27 O&M pour la Gestion et l’Expl stance to OMVG l nvelope oitation du Réseau d’intercon nexion de l’OMVG 009/O&M/OMVG/PE-OMVG/U GP/01-2021 / Opérateur Tem Component 2: Technical Assi Passation de marc IDA / 56620 A priori Direct 2,000,000.00 3,245,662.59 Signé 2021-01-27 2021-02-01 2021-02-01 2021-02-16 2021-03-22 2022-03-01 2021-09-18 poraire d’Exploitation et de M stance to OMVG hé de gré à gré aintenance du Réseau d’Inter connexion de l’OMVG Page 1 SN-OMVG-295456-NC-RFP / Services d’Opérateur O&M p Component 1: Extension of Demande de prop Open - Internationa Single Stage - Two E En cours d'ex our la Gestion, l’Exploitation IDA / 56590 WAPP transmission network A priori 60,000,000.00 0.00 2022-05-17 2022-06-27 2022-05-22 2022-10-19 2022-07-03 2022-09-15 2022-10-20 2023-04-18 ositions l nvelope écution et la Maintenance du Réseau – OMVG Interconnection d’interconnexion de l’OMVG CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 01CS / Assistance Technique Component 2: Technical Assi Sélection fondée s Open - Internationa En cours d'exame IDA / 56590 A priori 12,400,000.00 0.00 2015-04-29 2015-05-13 2015-06-26 2015-07-24 2015-08-23 2015-10-19 2015-12-10 2020-08-09 a la Maitrise d'Ouvrage ATM stance to OMVG ur la qualité et le l n O coût 03/CS / Etude technico-com Component 2: Technical Assi Sélection fondée s Open - Internationa IDA / 56590 A priori 500,000.00 0.00 Annulé 2017-01-23 2017-02-13 2017-03-13 2017-04-24 2017-05-08 2017-06-12 2017-07-17 2018-07-17 merciale de la fibre optique stance to OMVG ur la qualité et le l coût 005/OMVG/PE-OMVG/UGP/09 -2017 / Etude du Projet d'acc Component 1: Extension of Sélection fondée s ès à l'énergie électrique à pa Open - Internationa IDA / 56590 WAPP transmission network A priori ur la qualité et le 600,000.00 505,533.23 Signé 2017-09-15 2017-09-19 2017-09-15 2017-09-19 2017-10-24 2017-11-20 2017-11-21 2018-02-19 2017-12-05 2018-03-05 2018-01-16 2018-04-05 2018-02-06 2018-04-09 2018-08-05 rtir des sous stations des proj l – OMVG Interconnection coût ets régionaux OMVG et OMV S dans les pays du Sénégal, Guinée, Guinée Bissau, Gam bie 007/OMVG/PE-OMVG/UGP/S Component 1: Extension of Sélection fondée s N/10-2017 / Opérateur de se Open - Internationa IDA / 56620 WAPP transmission network A posteriori ur les qualification 410,000.00 0.00 Annulé 2017-09-29 2017-09-29 2017-10-20 2017-10-27 2017-11-11 2018-05-10 nsibilisation et d'indemnisati l – OMVG Interconnection s des consultants on pour le Sénégal 008/OMVG/PE-OMVG/UGP/G Component 1: Extension of Sélection fondée s Open - Internationa N/10-2017 / Opérateur de se IDA / 56600 WAPP transmission network A posteriori ur les qualification 360,000.00 0.00 Annulé 2017-09-29 2017-09-29 2017-10-20 2017-10-27 2017-11-11 2018-05-10 l nsibilisation et d'indemnisati – OMVG Interconnection s des consultants on pour la Guinée 010/OMVG/PE-OMVG/UGP/G Component 1: Extension of Sélection fondée s W/10-2017 / Opérateur de se Open - Internationa IDA / 56610 WAPP transmission network A posteriori ur les qualification 130,000.00 0.00 Annulé 2017-09-29 2017-09-29 2017-10-20 2017-10-27 2017-11-11 2018-05-10 nsibilisation et d'indemnisati l – OMVG Interconnection s des consultants on pour la Guinée-Bissau 009/OMVG/PE-OMVG/UGP/G Component 1: Extension of Sélection fondée s Open - Internationa M/10-2017 / Opérateur de se IDA / 56590 WAPP transmission network A posteriori ur les qualification 100,000.00 0.00 Annulé 2017-09-29 2017-09-29 2017-10-20 2017-10-27 2017-11-11 2018-05-10 l nsibilisation et d'indemnisati – OMVG Interconnection s des consultants on pour la Gambie 004/OMVG/PE-OMVG/UGP/08 -2017 / Quatre opérateurs de Component 1: Extension of Sélection fondée s Open - Internationa sensibilisation et d'indemnisa IDA / 56590 WAPP transmission network A priori 980,000.00 0.00 Annulé 2017-08-30 2017-09-21 2017-09-05 2017-09-22 2017-10-10 2017-10-19 2017-10-30 2017-11-03 2018-05-02 ur la qualité l tion pour le Sénégal, la Gam – OMVG Interconnection bie, la Guinée et la Guinée-Bi ssau 006/OMVG/PE-OMVG/UGP/ES /10-2017 / Etude cadre envir Component 1: Extension of Sélection fondée s onnementale et sociale dans Open - Internationa IDA / 56590 WAPP transmission network A posteriori ur les qualification 400,000.00 0.00 Annulé 2017-10-16 2017-11-06 2017-12-11 2018-01-17 2018-02-14 2018-08-13 le cadre des travaux d'exten l – OMVG Interconnection s des consultants sion des réseaux MT/BT depu is les postes sources de l'OM VG 007/OMVG/PE-OMVG/UGP/S N/2017 / Opérateur des inde Component 1: Extension of Sélection fondée s mnisations et charge informa IDA / 56620 WAPP transmission network A posteriori ur les qualification Open - National 410,000.00 294,938.20 Signé 2017-07-19 2017-08-17 2017-08-09 2017-09-22 2017-10-06 2017-10-22 2017-11-01 2017-11-26 2017-11-14 2018-05-25 tion, Sensibilisation et comm – OMVG Interconnection s des consultants unication pour Senegal Comp osante Interconnexion 008/OMVG/PE-OMVG/UGP/G N/2017 / Sélection de consult ants pour les services de : O Component 1: Extension of Sélection fondée s perateur des Indemnisations IDA / 56620 WAPP transmission network A posteriori ur les qualification Open - National 360,000.00 302,119.00 Signé 2017-07-19 2017-08-17 2017-08-09 2017-09-22 2017-10-06 2017-10-22 2017-11-14 2017-11-26 2017-11-14 2018-05-25 et Charge Information, Sensi – OMVG Interconnection s des consultants bilisation et Communication Pour Guinea - Composante In terconnexion 009/OMVG/PE-OMVG/UGP/G M/2017 / Sélection de consult ants pour les services de : O Component 1: Extension of Sélection fondée s perateur des Indemnisations IDA / 56620 WAPP transmission network A posteriori ur les qualification Open - National 100,000.00 115,871.39 Signé 2017-07-19 2017-06-27 2017-08-09 2017-09-22 2017-10-23 2017-10-22 2018-05-14 2017-11-26 2018-07-18 2018-05-25 et Charge Information, Sensi – OMVG Interconnection s des consultants bilisation et Communication pour Gambie - Composante I nterconnexion 010/OMVG/PE-OMVG/UGP/G W/2017 / Sélection de consul tants pour les services de : O Component 1: Extension of Sélection fondée s perateur des Indemnisations IDA / 56620 WAPP transmission network A posteriori ur les qualification Open - National 130,000.00 194,866.00 Signé 2017-07-19 2017-08-17 2017-08-09 2017-09-22 2017-10-30 2017-10-22 2018-04-12 2017-11-26 2018-05-14 2018-05-25 et Charge Information, Sensi – OMVG Interconnection s des consultants bilisation et Communication pour Guinea Bissau - Compos ante Interconnexion 003/OMVG/PE-OMVG/UGP/04 /2019 / L'ETUDE DE FAISABILI TE DANS LA COMMERCIALISA Component 1: Extension of Sélection fondée s Open - Internationa TION DE CAPACITE EXCEDEN IDA / 56590 WAPP transmission network A posteriori ur la qualité et le 500,000.00 298,809.28 Signé 2019-04-12 2019-04-08 2019-05-03 2019-05-15 2019-06-16 2020-08-12 2019-07-14 2020-09-22 2019-08-13 2020-11-23 2019-09-17 2020-12-03 2019-10-22 2021-02-15 2020-10-21 l TAIRE DU CABLE DE GARDE – OMVG Interconnection coût A FIBRE OPTIQUE (CGFO) DU RESEAU DE L'INTERCONNEXI ON 225 kV DE L'OMVG 007/OMVG/PE-OMVG/HC/UG P/08-2020 / Recrutement d’u n consultant chargé du renfo rcement des capacités des C Component 1: Extension of Sélection fondée s NS et des CLCS pour la mise IDA / 56590 WAPP transmission network A posteriori ur les qualification Open - National 50,000.00 182,559.76 Signé 2020-08-17 2020-08-13 2020-08-24 2020-08-31 2020-09-07 2020-10-15 2020-09-14 2021-03-04 2020-10-05 2021-02-22 2021-01-03 en œuvre des activités de pr – OMVG Interconnection s des consultants évention et de réponse aux V iolences Basées sur le Genre (VBG), y compris l’exploitatio n et les abus sexuels (EAS) e t le harcèlem 009/OMVG/PE-OMVG/UGP/02 -2021 / AUDIT SOCIAL ET FIN Component 1: Extension of Sélection fondée s ANCIER - PLANS D’ACTION D IDA / 56610 WAPP transmission network A posteriori ur les qualification Open - National 50,000.00 75,942.37 Signé 2021-02-21 2021-02-19 2021-02-28 2021-03-14 2021-04-29 2021-03-21 2021-04-29 2021-04-11 2021-05-06 2021-05-11 E RÉINSTALLATION DE LA LIG – OMVG Interconnection s des consultants NE DE TRANSMISSION ÉLECT RIQUE ET DES POSTES ÉLECT RIQUES DE LA GUINÉE BISSA U Page 2 SN-OMVG-273217-CS-QCBS / FEASIBILITY STUDIES FOR 22 5 KV SOMA(THE GAMBIA) TO Component 1: Extension of Sélection fondée s Open - Internationa En cours d'exécut TAMBA KUNDA(SENEGAL)WIT IDA / 56590 WAPP transmission network A priori ur la qualité et le 1,200,000.00 0.00 2022-01-24 2022-01-18 2022-02-14 2022-01-19 2022-03-30 2022-09-12 2022-04-27 2022-09-21 2022-05-27 2022-11-24 2022-07-01 2022-08-05 2022-11-03 l ion H SUBSTATION IN BASSE(THE – OMVG Interconnection coût GAMBIA & BRIKAMA(THE GA MBIA TO ZIGUANCHOR(SENE GAL) SN-OMVG-315966-CS-CQS / RECRUTEMENT D’UN CONSU LTANT (FIRME) POUR L’ELAB ORATION DES PLANS DE GES Component 1: Extension of Sélection fondée s TION DE LA BIODIVERSITE SP Open - Internationa En cours d'exécut IDA / 56600 WAPP transmission network A posteriori ur les qualification 200,000.00 0.00 2022-09-19 2023-02-28 2022-10-04 2023-05-16 2022-11-02 2022-11-17 2022-12-22 2023-02-20 ECIFIQUES AUX SITES IDENTI l ion – OMVG Interconnection s des consultants FIES POUR LA MISE EN ŒUVR E DES MESURES DE COMPEN SATION DANS LE CADRE DE L A PROTECTION DES CHIMPAN ZES D’AFRIQUE DE L’OUEST ET DE LEUR INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 2: Technical Assi 02/CS / Auditeur Interne IDA / 56620 A priori Individuel Open 250,000.00 0.00 Annulé 2016-12-21 2017-01-29 2017-02-08 2017-03-15 2018-03-15 stance to OMVG 004/OMVG/PE-OMVG/UGP/G W/12-2017 / POUR LE RECRU TEMENT D'UN CONSULTANT I Component 1: Extension of NDIVIDUEL CHARGE DE LA R IDA / 56610 WAPP transmission network A posteriori Individuel Open 50,000.00 0.00 Annulé 2017-12-11 2017-12-20 2018-01-29 2018-02-19 2018-03-26 2018-09-22 EALISATION DU CADRE DE G – OMVG Interconnection ESTION ENVIRONNEMENTALE ET SOCIALE (CGES-PCGES) D U PROJET REGIONAL D'ACCES A L'ELECTRICITE EN GUINEE BISSAU 011/OMVG/PE-OMVG/UGP/G W/12-2017 / POUR LE RECRU TEMENT D'UN CONSULTANT I Component 1: Extension of NDIVIDUEL CHARGE DE LA R IDA / 56610 WAPP transmission network A posteriori Individuel Open 50,000.00 0.00 Annulé 2017-12-11 2017-12-20 2018-01-29 2018-02-19 2018-03-26 2018-09-22 EALISATION DU CADRE DE P – OMVG Interconnection OLITIQUE DE REINSTALLATIO N (CPRP) DU PROJET REGIONAL D'ACC ES A L'ELECTRICITE EN GUIN EE BISSAU 001/OMVG/PE-OMVG/UGP/06 -2018 / The study will evaluat e the potential impacts of the OMVG Interconnection on We Component 1: Extension of Sélection de cons st African Chimpanzees and t IDA / 56600 WAPP transmission network A posteriori ultants par entent Direct 25,000.00 67,732.58 Signé 2018-06-18 2018-07-07 2018-06-28 2018-07-18 2018-07-26 2018-11-05 2018-10-04 o provide recommendations – OMVG Interconnection e directe The Specialist is expected to possess a degree in zoology, ecology with 10 years experi ence in the field of conservat ion 005/OMVG/PE-OMVG/UGP/10 -2019 / L’audit social concern e la vérification de toutes les indemnisations mises en plac Component 1: Extension of e au niveau du poste de Labé IDA / 56600 WAPP transmission network A posteriori Individuel Limited 45,000.00 0.00 Annulé 2019-12-02 2019-12-07 2019-12-21 2020-01-11 2020-01-14 avant la mise en œuvre du P – OMVG Interconnection AR Postes Guinée, par rappor t au contenu du PAR validé p ar les PTFs L’audit social a pour objectif de comparer les m 006/OMVG/PE-OMVG/UGP/11 -2019 / POUR LE RECRUTEME NT D’UNE CONSULTANT CHA Component 1: Extension of Sélection de cons RGEE DE LA MISE EN ŒUVRE IDA / 56620 WAPP transmission network A posteriori ultants par entent Direct 230,000.00 249,299.45 Signé 2019-12-05 2019-12-12 2019-12-08 2019-12-12 2019-12-20 2020-01-16 2020-06-17 DES MESURES DE PROTECTI – OMVG Interconnection e directe ON DES POPULATIONS DE CH IMPANZES DANS LA ZONE D’I NFLUENCE DE LA LIGNE D’IN TERCONNEXION 005/OMVG/PE-OMVG/UGP/03 -2020 / Recrutement d’un co nsultant chargé du renforce ment des capacités des CNS Component 1: Extension of et des CLCS pour la mise en IDA / 56590 WAPP transmission network A posteriori Individuel Open 30,000.00 0.00 Annulé 2020-03-30 2020-06-23 2020-05-18 2020-06-08 2020-07-13 2020-10-11 œuvre des activités de préve – OMVG Interconnection ntion et de réponse aux Viole nces Basées sur le Genre (VB G), y compris l’exploitation et les abus sexuels (EAS) et le h arcèlem SN-OMVG-361960-CS-INDV / RECRUTEMENT D'UN GESTIO NNAIRE DE BASE DE DONNÉE Component 1: Extension of Open - Internationa En attente d'exéc S POUR AMÉLIORER LA BASE IDA / 56610 WAPP transmission network A posteriori Individuel 15,000.00 0.00 2023-05-16 2023-05-29 2023-06-01 2023-06-14 2023-09-12 l ution DE DONNÉES DES PERSONNE – OMVG Interconnection S AFFECTÉES PAR LE PROJET (PAP) DU PROJET ENERGIE O MVG Page 3