STRATEGIC IRRIGATION MODERNIZATION AND URGENT REHABILITATION PROJECT (SIMURP) Summary Procurement Plan Version No.: 1.1 Date: March 16, 2022 I. General Information 1. Project information: a. Country: Indonesia b. Borrower: Ministry of Finance, Republic of Indonesia c. Project Name: Strategic Irrigation Modernization and Urgent Rehabilitation Project (SIMURP) d. Loan No.: IBRD LOAN L0060A; and AIIB LOAN 8891-ID e. Applicable Procurement Procedures: World Bank Procurement and Consultant Guidelines of January 2011, Revised July 2014 f. The Executing Agency: Directorate Irrigation and Lowlands, Directorate General of Water Resources (DGWR), Ministry Public Works and Housing (MPWH) (i) Central Project Management Unit (CPMU): Directorate of Water Resources Development, DGWR, MPWH (ii) Central Project Implementing Unit (CPIU): Directorate Irrigation and Lowland, DGWR, MPWH (CPIU IRWA) (iii) National Project Implementing Unit (NPIU): • Directorate of Operations and Maintenance Directorate General of Natural Resources, MPWH (NPIU OP-PSDA), • Directorate General of Regional Development (SUPD I and SUPD II) Ministry of Home Affairs (NPIU Bangda) • Ministry of Agriculture's Extension and Agricultural Human Resources Development Agency Agriculture (NPIU Agriculture) (iv) Project Implementing Units (PIUs): DGWR’s River Basin Organizations (Balai Besar/Balai Wilayah Sunga, B/BWS) of Brantas, Citarum, Serayu Opak, Sumatera VIII, Sumatera II, Nusa Tenggara I 2. Bank’s No Objection Date of the Procurement Plan: a. Original : May 22, 2018 b. Last version : September 12, 2021 c. This version : March 16, 2022 3. Date of General Procurement Notice: May 7, 2020 4. Period covered by this procurement plan: May 22, 2018 – Project Closing Date (June 30, 2024) II. Types of Contract, Bank’s Review Requirements and Applied Methods A. Works, Goods and Non-Consulting Services 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Procurement Guidelines: Ref. Procureme Bank’s Review Procurement Method No. nt Method Requirement 1. International Competitive ≥ $25 million Threshold Each contract shall Bidding (Works) be subject to Bank’s prior review. 2. National Competitive < $25 million Each contract ≥ Bidding (Works) $10 million equivalent shall be subject to Bank’s prior review. All other contracts 3. Shopping for Works < $200k subject No post prior to review review. (only post review). 4. International Competitive ≥$2 million Each contract ≥ $2 Bidding (Goods) million equivalent shall be subject to Bank’s prior review. All other contracts subject to post 5. National Competitive review. <$2 million Each contract ≥ $2 Bidding (Goods) million equivalent shall be subject to Bank’s prior review. All other contracts subject to post 6. Shopping for Goods <100k review. No prior review (only post review). 7. International Competitive ≥$10 million Each contract shall Bidding (Non-Consultant be subject to Bank’s Service) prior review. 8. National Competitive <$10 million Each contract ≥ $2 Bidding (Non-Consultant million equivalent Service) shall be subject to Bank’s prior review. All other contracts subject to post 9. Shopping for Non- <$100k review. No prior review Consulting Services (only post review). 10. Direct Contracting Subject to ≥ $2million and paragraph justification shall be 3.7 of the provided when Procurement submit procurement Guidelines plan. 1. Pre-qualification: Prequalification is not used instead post qualification shall be followed for all national competitive bidding under the project. 2. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: As specified in the Project Operations Manual (POM) 3. Reference to (if any) Project Operational/Procurement Manual: Project Operations Manual of SIMURP 4. Any Other Special Procurement Arrangements: -NA- 5. Summary of the Procurement Packages 1 2 3 4 5 Ref. Description Review Estimate Number No. by Bank d of Cost Package (US$ s mil.) ICB A. 1. Works Prior - - 2. Goods and Supply Prior 2.5 1 &Installation 3. Non-consulting Services Prior - - B. NCB 1. Works Prior 165 11 2. Works Post 82 17 3. Goods and Supply & Prior - - Installation 4. Goods and Supply & Post - - Installation 5. Non-consulting Services Prior - - 6. Non-consulting Services Post 0.2 3 C. Shopping 1. Works Post 2. Goods Post 0.18 7 3. Non-consulting Services Post 0.32 5 D. Direct Contracting 1. Works Post - - 2. Goods Post 0.56 1 3. Non-consulting Services Post 0.28 2 Total (All methods and Review 250,85 44 Requirements) B. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to prior review by Bank as stated in Appendix 1 to the Consultant Guidelines: Ref. Selection Selection Method Bank’s Prior Review No. Method Threshold Requirement 1. QCBS and all Applied to all Each contract equal to other methods, estimated value. No or above $1,000,000 including QBS, threshold. equivalent shall be FBS and LCS subject to Bank’s prior (Firms) review. All other contracts subject to post review. (Prior review from technical perspective of only the draft TOR 2. CQS (Firms) Only for estimated and No draft prior cost (only review contract value < $ estimate). post review). 300,000 as per paragraph 3.7 of the 3. Single Source Consultant No selection Guidelines. method Each contract equal to Selection of threshold. Subject to or above $1,000,000 Firms justification for Singe equivalent shall be Source Selection of subject to Bank’s prior firms as per para. 3.9 review. All other and 3.10 of the contracts subject to Consultant Guidelines. post review. (Prior review from technical perspective of only the draft TOR, Justification for use of Single Source Selection method and draft cost estimate, shall be sent for the Bank’s prior approval as part of the procurement plan). Ref. Selection Selection Method Bank’s Prior Review No. Method Threshold Requirement 4. Competitive No threshold. No prior review (only Selection of post review), unless Individual contract is equal to or Consultants above $300,000. (comparison of at least 3 CVs) (Prior review from technical perspective of only the draft TOR. In addition, the Bank’s prior review and no objection shall be also obtained for the exceptional deviations from the normal competitive selection procedure of individual consultants subject to the Bank’s expost- 5. Single Source No Threshold. No prior review in (only review listed Selection of post review), paragraph 5.4unless (a)-(c) of Individual Subject to justification the Consultant to or contract is equal Consultants for single source of above $300,000. Guidelines). individuals as per para. 5.4 of the (Prior review from Consultant Guidelines technical perspective of only the draft TOR, Justification for use of Single Source Selection method together with CV of the recommended candidate and draft cost estimate, shall be sent for the Bank’s 2. Short list comprising entirely of national consultants prior approval : Short as part of the procurement list of consultants for services (firms), estimated to cost less than US$ 400,000 equivalent per contract, may plan).comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: N/A 4. Summary of Consultancy Assignments 1 2 3 4 5 Ref. Description Review Estimate Number No. by Bank d of Cost Package (US$ s mil.) A. Consulting Firm 1. QCBS and all other Prior 64.7 9 methods 2. QCBS and all other Post 0.56 1 methods 3. CQS Post 0.26 2 4. Single-Source Post/Prior - - Sub-total (All methods and Review 65.52 12 Requirements) B. Individual Consultant 1. Competitive Selection Prior - - 2. Single-Source Prior - - 3. Competitive Selection Post 0.89 141) 4. Single-Source Post 0.38 3 Sub-total (All methods and Review 1.27 17 Requirements) 1) limited approach PROCUREMENT Indonesia : Strategic Irrigation Modernization and Urgent Rehabilitation Project PLAN General Information Country: Indonesia 2020-04-26 Bank’s Approval Date of the Original Procurement Plan: 2023-05-13 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P157585 GPN Date: 2020-05-07 Project Name: Strategic Irrigation Modernization and Urgent Rehabilitation Project Loan / Credit No: COFN / C1530, IBRD / 88910 Directorate of Irrigation and Lowland Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Component A: Urgent Rehab ID-DIL-169597-CW-RFB / Reh Single Stage - One E 2023-01-1 COFN / C1530 ilitation of Irrigation and Drai Prior Request for Bids Open - National 6,819,556.00 0.00 Canceled 2020-04-22 2020-05-06 2020-06-12 2020-08-13 2020-10-28 abilitation of DI. Pamukkulu nvelope 6 nage System Component B: Strategic Mod ID-DIL-169608-CW-RFB / Mo Single Stage - One E 24,296,296.0 20,891,218. 2022-07-1 COFN / C1530 ernization of Irrigation and D Prior Request for Bids Open - National Signed 2020-04-22 2020-04-27 2020-04-28 2020-05-28 2020-07-16 2020-06-27 2020-09-24 2020-07-27 2020-11-12 dernization of SS. Macan Cs. nvelope 0 54 7 rainage System ID-DIL-169615-CW-RFB / Mo Component B: Strategic Mod Single Stage - One E 16,888,889.0 12,941,040. 2022-07-1 dernization of SS. Pamanuka COFN / C1530 ernization of Irrigation and D Prior Request for Bids Open - National Signed 2020-04-22 2020-04-29 2020-04-24 2020-05-28 2020-07-16 2020-06-27 2020-10-01 2020-07-27 2020-11-12 nvelope 0 42 7 n Cs rainage System Component A: Urgent Rehab ID-DIL-169616-CW-RFB / Reh Single Stage - One E 2,565,037.8 2022-04-2 COFN / C1530 ilitation of Irrigation and Drai Post Request for Bids Open - National 3,874,074.00 Signed 2020-04-22 2020-04-27 2020-05-06 2020-06-12 2020-07-13 2020-07-12 2020-10-07 2020-08-23 2020-10-16 abilitation of DI Jurang Batu nvelope 0 5 nage System Component A: Urgent Rehab ID-DIL-169617-CW-RFB / Reh Single Stage - One E 6,802,374.1 Under Revie 2022-08-0 COFN / C1530 ilitation of Irrigation and Drai Prior Request for Bids Open - National 9,826,667.00 2020-04-22 2020-04-29 2020-05-06 2020-06-12 2020-08-25 2020-07-12 2020-10-21 2020-08-18 2020-12-02 abilitation of DI. Talang nvelope 7 w 8 nage System ID-DIL-169619-CW-RFB / Reh Component A: Urgent Rehab Single Stage - One E 5,653,027.6 2023-04-0 abilitation of DIR Karang Agu COFN / C1530 ilitation of Irrigation and Drai Prior Request for Bids Open - National 8,380,921.00 Signed 2020-04-22 2020-04-29 2020-05-06 2020-06-12 2020-07-20 2020-07-12 2020-09-27 2020-08-18 2020-11-06 nvelope 8 5 ng Hilir Phase I nage System Component A: Urgent Rehab ID-DIL-173265-CW-RFB / Reh Single Stage - One E 4,783,522.1 2020-08-2 COFN / C1530 ilitation of Irrigation and Drai Prior Request for Bids Open - National 6,819,556.00 Signed 2019-11-08 2020-05-13 2019-11-13 2019-12-25 2019-11-27 2020-01-24 2020-05-19 2020-02-28 2020-06-29 abilitation of DI. Pamukkulu nvelope 1 6 nage System Component A: Urgent Rehab ID-DIL-173287-CW-RFB / Reh Single Stage - One E 3,737,218.5 2022-03-0 COFN / C1530 ilitation of Irrigation and Drai Prior Request for Bids Open - National 5,466,444.00 Signed 2020-05-13 2020-05-18 2020-05-20 2020-06-26 2020-08-24 2020-07-10 2020-11-04 2020-08-24 2020-11-24 abilitasi DI. Kedung Putri nvelope 6 7 nage System Component A: Urgent Rehab ID-DIL-173293-CW-RFB / Reh Single Stage - One E 2,128,030.7 2021-10-0 COFN / C1530 ilitation of Irrigation and Drai Post Request for Bids Open - National 2,986,726.00 Completed 2020-05-13 2020-06-19 2020-05-20 2020-06-26 2020-07-03 2020-07-10 2020-08-11 2020-08-14 2020-09-08 abilitasi Bendung Cikeusik nvelope 7 8 nage System ID-DIL-197310-CW-RFB / Reh Component A: Urgent Rehab Single Stage - One E 1,915,354.6 2021-12-0 abilitasi Jaringan irigasi DI. S IBRD / 88910 ilitation of Irrigation and Drai Post Request for Bids Open - National 2,091,260.00 Signed 2020-10-02 2020-10-20 2020-10-04 2020-11-08 2020-11-20 2020-11-22 2020-12-17 2020-12-08 2021-04-30 nvelope 4 8 ei Ular (Ramonia) Kab. Deli S nage System erdang ID-DIL-197311-CW-RFB / Reh Component A: Urgent Rehab Single Stage - One E 10,670,867.0 2021-07-2 abilitasi Jaringan Irigasi DI. S IBRD / 88910 ilitation of Irrigation and Drai Prior Request for Bids Open - National 0.00 Canceled 2020-10-02 2020-10-06 2020-10-07 2020-11-18 2020-12-01 2020-12-18 2021-02-08 2021-01-22 nvelope 0 1 ei Ular (Perbaungan) Kab. Se nage System rdang Bedagai ID-DIL-209965-CW-RFB / Reh Component A: Urgent Rehab Single Stage - One E 10,108,928.0 2022-10-2 abilitasi Jaringan Irigasi DI. Ci IBRD / 88910 ilitation of Irrigation and Drai Prior Request for Bids Open - National 0.00 Canceled 2020-12-17 2021-01-06 2020-12-22 2021-01-22 2021-02-22 2021-02-05 2021-03-07 nvelope 0 8 keusik nage System ID-DIL-221353-CW-RFB / No Component B: Strategic Mod Regret Measures Daerah Irig Single Stage - One E 1,627,118.6 2023-01-0 IBRD / 88910 ernization of Irrigation and D Post Request for Bids Open - National 2,058,541.00 Signed 2021-02-24 2021-03-12 2021-03-08 2021-04-08 2021-04-13 2021-04-22 2021-05-07 2021-05-13 2021-05-25 asi Jatiluhur (Rehabilitasi Tala nvelope 0 3 rainage System ng BTT. 11 A Saluran Tarum Timur) National Procure ID-DIL-233935-CW-RFB / RE Component A: Urgent Rehab ment Document - Single Stage - One E 10,553,488.0 8,321,735.1 Under Revie 2023-08-1 HABILITASI IRIGASI D.I. SEI U IBRD / 88910 ilitation of Irrigation and Drai Prior Request for Bids Open - National 1 Envelope proce 2021-05-10 2021-05-17 2021-05-18 2021-06-20 2021-06-24 2021-07-20 2022-01-01 2021-08-29 2022-03-21 nvelope 0 7 w 9 LAR (PERBAUNGAN) KAB. SE nage System ss (Non Bank-SPD RDANG BEDAGAI ) National Procure ID-DIL-238192-CW-RFB / Pro Component A: Urgent Rehab ment Document - Single Stage - One E 1,267,284.5 2022-04-1 curement of Rehabilitation T COFN / C1530 ilitation of Irrigation and Drai Post Request for Bids Open - National 1 Envelope proce 1,750,000.00 Signed 2021-06-30 2021-06-07 2021-07-05 2021-08-16 2021-08-27 2021-09-15 2021-09-29 2021-10-20 2021-11-15 nvelope 4 8 ertiary Canal of DI. Kedung P nage System ss (Non Bank-SPD utri (Phase 1) ) National Procure ID-DIL-238572-CW-RFB / Reh Component A: Urgent Rehab ment Document - Single Stage - One E 2022-04-1 abilitation Tertiary Canal of D COFN / C1530 ilitation of Irrigation and Drai Post Request for Bids Open - National 1 Envelope proce 1,225,000.00 854,458.98 Signed 2021-06-30 2021-12-20 2021-07-05 2021-08-16 2022-01-05 2021-09-15 2022-02-17 2021-10-20 2022-03-11 nvelope 8 I. Jurang Batu (Phase 1) nage System ss (Non Bank-SPD ) ID-DIL-240456-CW-RFB / Rev Component A: Urgent Rehab Single Stage - One E Other (with field f 5,697,566.9 2022-05-1 italization of DI Kedung Putri COFN / C1530 ilitation of Irrigation and Drai Post Request for Bids Open - National 6,901,550.00 Signed 2021-07-31 2021-07-22 2021-08-05 2021-09-16 2021-08-27 2021-10-16 2021-09-29 2021-11-20 2021-11-18 nvelope or explanation) 1 9 (Lanjutan) nage System ID-DIL-240458-CW-RFB / Reh Component A: Urgent Rehab Single Stage - One E Other (with field f 1,452,672.0 2022-05-1 abilitation of DI. Talang (lanju COFN / C1530 ilitation of Irrigation and Drai Post Request for Bids Open - National 1,795,400.00 Signed 2021-07-31 2021-09-02 2021-08-05 2021-09-16 2021-09-30 2021-10-16 2021-11-24 2021-11-20 2021-12-06 nvelope or explanation) 0 9 tan) nage System ID-DIL-240460-CW-RFB / Reh Component A: Urgent Rehab Single Stage - One E Other (with field f 2,608,637.5 2022-05-1 abilitation Tertiary Canal of D COFN / C1530 ilitation of Irrigation and Drai Post Request for Bids Open - National 2,915,000.00 Signed 2021-07-31 2021-09-01 2021-08-05 2021-09-16 2021-09-24 2021-10-16 2021-11-24 2021-11-20 2021-12-13 nvelope or explanation) 9 9 I. Talang (Phase 1) nage System ID-DIL-240462-CW-RFB / Reh Component A: Urgent Rehab Single Stage - One E Other (with field f 6,927,857.7 2022-05-1 abilitation and Upgrading of COFN / C1530 ilitation of Irrigation and Drai Post Request for Bids Open - National 8,170,000.00 Signed 2021-07-31 2021-09-24 2021-08-05 2021-09-16 2021-10-26 2021-10-16 2021-12-16 2021-11-20 2021-12-30 nvelope or explanation) 9 9 DIR. Katingan I (Phase 1) nage System ID-DIL-240465-CW-RFB / Civi Component B: Strategic Mod l Works for (ETC) SS Salamda Single Stage - One E Other (with field f 24,190,000.0 18,811,698. 2022-05-1 COFN / C1530 ernization of Irrigation and D Prior Request for Bids Open - National Signed 2021-07-31 2021-07-29 2021-08-05 2021-09-16 2021-09-23 2021-10-16 2022-03-15 2021-11-20 2022-06-03 rma Kiri Cs, SS Gadung Cs, , nvelope or explanation) 0 26 9 rainage System SS. Pawelutan CS National Procure ID-DIL-240466-CW-RFB / Civi Component B: Strategic Mod ment Document - l Works for (ETC) SS Kamojin Single Stage - One E 21,515,000.0 16,517,650. 2022-05-1 COFN / C1530 ernization of Irrigation and D Prior Request for Bids Open - National 1 Envelope proce Signed 2021-07-31 2021-07-29 2021-08-05 2021-09-16 2021-09-23 2021-10-16 2022-03-15 2021-11-20 2022-06-09 g Cs, SS. Telar, SS. Barugbug nvelope 0 13 9 rainage System ss (Non Bank-SPD Cs, SS. Tapen Cs, SI. Tarum T ) imur Page 1 National Procure ID-DIL-242280-CW-RFB / Reh Component A: Urgent Rehab ment Document - Single Stage - One E 8,938,946.9 2023-06-1 abilitasi jaringan Irigasi DI. Ci IBRD / 88910 ilitation of Irrigation and Drai Prior Request for Bids Open - National 1 Envelope proce 9,763,038.00 Signed 2021-07-09 2021-07-14 2021-07-12 2021-08-16 2021-08-12 2021-09-15 2021-12-01 2021-10-19 2021-12-27 nvelope 7 1 keusik nage System ss (Non Bank-SPD ) ID-DIL-249647-CW-RFB / Reh Component A: Urgent Rehab Single Stage - One E Other (with field f 20,709,100.0 17,187,020. Under Revie 2022-06-2 abilitation and Modernization COFN / C1530 ilitation of Irrigation and Drai Prior Request for Bids Open - National 2021-09-01 2021-09-29 2021-09-06 2021-10-18 2021-12-09 2021-11-17 2022-01-25 2021-12-22 2022-03-31 nvelope or explanation) 0 06 w 0 DI. Glapan Timur nage System Component A: Urgent Rehab ID-DIL-249650-CW-RFB / Reh Single Stage - One E Other (with field f 7,111,589.8 2022-08-2 COFN / C1530 ilitation of Irrigation and Drai Post Request for Bids Open - National 9,497,000.00 Signed 2021-11-01 2022-01-10 2021-11-06 2021-12-18 2022-02-02 2022-01-17 2022-02-17 2022-02-21 2022-06-02 abilitation of DI. Jengkelok nvelope or explanation) 5 0 nage System ID-DIL-249651-CW-RFB / Reh Component A: Urgent Rehab Single Stage - One E Other (with field f 4,956,134.1 2022-07-2 abilitation and Improvement COFN / C1530 ilitation of Irrigation and Drai Post Request for Bids Open - National 5,174,000.00 Signed 2021-10-01 2021-09-13 2021-10-06 2021-11-17 2021-10-07 2021-12-17 2021-10-28 2022-01-21 2021-12-31 nvelope or explanation) 2 0 DI. Ameroro nage System ID-DIL-249655-CW-RFB / Reh Component A: Urgent Rehab Single Stage - One E Other (with field f 17,063,000.0 15,885,583. 2022-06-2 abilitation of Wadaslintang B COFN / C1530 ilitation of Irrigation and Drai Prior Request for Bids Open - National Signed 2021-09-01 2021-10-08 2021-09-06 2021-10-18 2021-11-18 2021-11-17 2021-12-10 2021-12-22 2022-01-14 nvelope or explanation) 0 72 0 arat Main Canal DI. Wadaslint nage System ang Component A: Urgent Rehab ID-DIL-249656-CW-RFB / Reh Single Stage - One E Other (with field f 2022-06-2 COFN / C1530 ilitation of Irrigation and Drai Post Request for Bids Open - National 5,280,000.00 0.00 Canceled 2021-09-01 2021-09-20 2021-09-06 2021-10-18 2021-11-17 2021-12-22 abilitation DI. Mbay Kanan nvelope or explanation) 0 nage System ID-DIL-249657-CW-RFB / Reh Component A: Urgent Rehab Single Stage - One E Other (with field f 6,513,378.0 2022-06-2 abilitation and Modernization COFN / C1530 ilitation of Irrigation and Drai Post Request for Bids Open - National 7,867,000.00 Signed 2021-09-01 2021-11-29 2021-09-06 2021-10-18 2021-12-27 2021-11-17 2022-03-04 2021-12-22 2022-05-15 nvelope or explanation) 6 0 DI. Saddang, Sub-unit Langn nage System ga Component A: Urgent Rehab ID-DIL-249658-CW-RFB / Rev Single Stage - One E Other (with field f 8,438,331.2 2022-08-2 COFN / C1530 ilitation of Irrigation and Drai Post Request for Bids Open - National 9,511,000.00 Signed 2021-11-01 2022-01-18 2021-11-06 2021-12-18 2022-02-22 2022-01-17 2022-01-26 2022-02-21 2022-05-25 italization DI. Sempor nvelope or explanation) 4 0 nage System ID-DIL-263523-CW-RFB / Reh Component A: Urgent Rehab Single Stage - One E Other (with field f 3,749,379.2 2024-02-1 abilitation Mbay Kanan Irrigat COFN / C1530 ilitation of Irrigation and Drai Post Request for Bids Open - National 5,280,000.00 Signed 2021-11-21 2021-11-18 2021-11-26 2021-12-19 2021-12-20 2021-12-24 2022-02-03 2022-01-16 2022-02-28 nvelope or explanation) 8 5 ion Scheme nage System ID-DIL-240461-CW-RFB / Reh Component A: Urgent Rehab Single Stage - One E Other (with field f 2022-05-1 abilitation Tertiary Canal of D IBRD / 88910 ilitation of Irrigation and Drai Post Request for Bids Open - National 1,063,000.00 0.00 Canceled 2021-07-31 2021-09-20 2021-08-05 2021-09-16 2021-10-13 2021-10-16 2021-11-20 nvelope or explanation) 9 I. Pamukkulu-Kab. Takalar (P nage System hase 1) ID-DIL-291170-CW-RFB / Reh Component A: Urgent Rehab abilitasi Jaringan Irigasi Tersi Single Stage - One E Other (with field f 2023-02-0 COFN / C1530 ilitation of Irrigation and Drai Post Request for Bids Open - National 1,063,000.00 802,035.46 Signed 2022-05-09 2022-05-18 2022-05-14 2022-06-04 2022-06-09 2022-07-04 2022-07-15 2022-08-08 2022-08-07 er DI. Pamukkulu Kabupaten nvelope or explanation) 4 nage System Takalar Tahap I (SIMURP) Component A: Urgent Rehab ID-DIL-303117-CW-RFB / Reh Single Stage - One E Other (with field f 2023-10-2 COFN / C1530 ilitation of Irrigation and Drai Post Request for Bids Open - National 1,553,874.00 0.00 Canceled 2022-07-24 2022-08-05 2022-07-29 2022-08-19 2022-09-18 2022-10-23 abilitasi Bendung DI.Sei Ular nvelope or explanation) 3 nage System ID-DIL-303128-CW-RFB / Reh Component A: Urgent Rehab abilitasi dan Peningkatan Jari Single Stage - One E Other (with field f 2023-04-2 COFN / C1530 ilitation of Irrigation and Drai Post Request for Bids Open - National 2,393,755.00 0.00 Signed 2022-07-24 2022-08-05 2022-07-29 2022-08-19 2022-08-29 2022-09-18 2022-10-04 2022-10-23 ngan D.I.R Karang Agung Hili nvelope or explanation) 1 nage System r Tahap II Sumatera Selatan Kab. Banyu Asin ID-DIL-303130-CW-RFB / Rev Component A: Urgent Rehab italisasi Jaringan Primer dan s Single Stage - One E Other (with field f 5,291,305.0 2023-10-2 COFN / C1530 ilitation of Irrigation and Drai Post Request for Bids Open - National 7,671,857.00 Signed 2022-07-24 2022-07-18 2022-07-29 2022-08-19 2022-08-15 2022-09-18 2022-09-17 2022-10-23 2022-10-02 ekunder D.I. Cipancuh Jawa B nvelope or explanation) 0 3 nage System arat Kab. Indramayu ID-DIL-303131-CW-RFB / Rev Component A: Urgent Rehab Single Stage - One E Other (with field f 2023-11-0 italisasi Jaringan Tersier D.I. COFN / C1530 ilitation of Irrigation and Drai Post Request for Bids Open - National 2,256,429.00 0.00 Signed 2022-08-07 2022-08-29 2022-08-12 2022-09-02 2022-09-26 2022-10-02 2022-11-15 2022-11-06 nvelope or explanation) 6 Cipancuh Jawa Barat Kab. Ind nage System ramayu ID-DIL-303132-CW-RFB / Rev Component A: Urgent Rehab Single Stage - One E Other (with field f 8,543,885.4 2023-10-2 italization of Banjarcahyana J COFN / C1530 ilitation of Irrigation and Drai Post Request for Bids Open - National 9,644,286.00 Signed 2022-07-24 2022-07-14 2022-07-29 2022-08-19 2022-08-08 2022-09-18 2022-08-22 2022-10-23 2022-09-22 nvelope or explanation) 1 3 awa Tengah Kab. Banjarnega nage System ra ID-DIL-303133-CW-RFB / Reh Component A: Urgent Rehab abilitasi Jaringan Irigasi DI po Single Stage - One E Other (with field f 2023-10-2 COFN / C1530 ilitation of Irrigation and Drai Post Request for Bids Open - National 7,701,786.00 0.00 Signed 2022-07-24 2022-07-15 2022-07-29 2022-08-19 2022-09-19 2022-09-18 2022-09-21 2022-10-23 ndok waluh Kab. Jember Jawa nvelope or explanation) 3 nage System Timur Kab. Jember ID-DIL-303134-CW-RFB / Da Component A: Urgent Rehab erah irigasi DI pondok waluh Single Stage - One E Other (with field f 2023-10-2 COFN / C1530 ilitation of Irrigation and Drai Post Request for Bids Open - National 2,593,929.00 0.00 Signed 2022-07-24 2022-07-20 2022-07-29 2022-08-19 2022-08-16 2022-09-18 2022-10-26 2022-10-23 (SIMURP) yang dibangun (jari nvelope or explanation) 3 nage System ngan tersier) Jawa Timur ID-DIL-303135-CW-RFB / Rev Component A: Urgent Rehab Single Stage - One E Other (with field f 2023-10-2 italisasi Jaringan Primer DI Jur COFN / C1530 ilitation of Irrigation and Drai Post Request for Bids Open - National 6,743,571.00 0.00 Signed 2022-07-21 2022-07-26 2022-07-26 2022-08-16 2022-08-19 2022-09-15 2022-07-21 2022-10-20 nvelope or explanation) 0 ang Sate Hilir nage System ID-DIL-303137-CW-RFB / Rev Component A: Urgent Rehab Single Stage - One E Other (with field f 2022-11-0 italisasi Jaringan Tersier DI Ju COFN / C1530 ilitation of Irrigation and Drai Post Request for Bids Open - National 2,299,643.00 0.00 Signed 2022-07-31 2022-08-29 2022-08-05 2022-08-26 2022-08-22 2022-09-25 2022-10-10 2022-10-30 nvelope or explanation) 2 rang Sate Hilir nage System ID-DIL-303138-CW-RFB / Reh Component A: Urgent Rehab Single Stage - One E Other (with field f 2023-10-2 abilitasi /Revitalisasi High Le COFN / C1530 ilitation of Irrigation and Drai Post Request for Bids Open - National 5,000,000.00 0.00 Signed 2022-07-24 2022-07-22 2022-07-29 2022-08-19 2022-08-19 2022-09-18 2022-09-20 2022-10-23 nvelope or explanation) 3 vel Diversion (HLD) - Paket 1 nage System (Jangkok-BJS6) ID-DIL-303139-CW-RFB / Reh Component A: Urgent Rehab Single Stage - One E Other (with field f 2023-10-2 abilitasi /Revitalisasi High Le COFN / C1530 ilitation of Irrigation and Drai Post Request for Bids Open - National 5,000,000.00 0.00 Signed 2022-07-24 2022-07-22 2022-07-29 2022-08-19 2022-08-19 2022-09-18 2022-09-20 2022-10-23 nvelope or explanation) 3 vel Diversion (HLD) - Paket 2 nage System (BJS6-BJS17) ID-DIL-303140-CW-RFB / Reh Component A: Urgent Rehab Single Stage - One E Other (with field f 2023-10-2 abilitasi Tingkat Lanjut Jaring COFN / C1530 ilitation of Irrigation and Drai Post Request for Bids Open - National 2,689,571.00 0.00 Canceled 2022-07-24 2022-07-15 2022-07-29 2022-08-19 2022-08-15 2022-09-18 2022-10-23 nvelope or explanation) 3 an Primer DI. Pamukulu Taha nage System p2 ID-DIL-303141-CW-RFB / Reh Component A: Urgent Rehab Single Stage - One E Other (with field f 2023-10-2 abilitasi Jaringan Primer DI Sa COFN / C1530 ilitation of Irrigation and Drai Post Request for Bids Open - National 6,891,429.00 0.00 Signed 2022-07-24 2022-07-25 2022-07-29 2022-08-19 2022-08-26 2022-09-18 2022-08-26 2022-10-23 nvelope or explanation) 3 nrego nage System National Procure ID-DIL-303142-CW-RFB / Rev Component A: Urgent Rehab ment Document - Single Stage - One E 2022-11-2 italisasi Jaringan Tersier DI S COFN / C1530 ilitation of Irrigation and Drai Post Request for Bids Open - National 1 Envelope proce 1,582,857.00 0.00 Signed 2022-07-24 2022-08-12 2022-07-29 2022-08-19 2022-09-08 2022-09-18 2022-09-30 2022-10-23 nvelope 8 anrego nage System ss (Non Bank-SPD ) ID-DIL-303143-CW-RFB / Reh Component A: Urgent Rehab Single Stage - One E Other (with field f 2023-10-2 abilitasi dan Peningkatan Jari COFN / C1530 ilitation of Irrigation and Drai Post Request for Bids Open - National 2,693,592.00 0.00 Signed 2022-07-24 2022-08-12 2022-07-29 2022-08-19 2022-09-05 2022-09-18 2022-10-06 2022-10-23 nvelope or explanation) 3 ngan DIR Katingan Tahap II nage System Page 2 ID-DIL-303144-CW-RFB / Rev Component A: Urgent Rehab italisasi Jaringan Tersier DI Ci Single Stage - One E Other (with field f 2023-10-2 COFN / C1530 ilitation of Irrigation and Drai Post Request for Bids Open - National 2,000,000.00 0.00 Signed 2022-07-24 2022-08-16 2022-07-29 2022-08-19 2022-09-07 2022-09-18 2022-10-04 2022-10-23 keusik (SIMURP) Kab. Cirebon nvelope or explanation) 3 nage System Jawa Barat Kab. Cirebon ID-DIL-303145-CW-RFB / Reh abilitasi, Peningkatan dan Mo Component B: Strategic Mod Single Stage - One E Other (with field f 17,998,643.0 Under Imple 2022-12-1 dernisasi Jaringan Irigasi SS. COFN / C1530 ernization of Irrigation and D Prior Request for Bids Open - National 0.00 2022-07-24 2022-08-22 2022-07-29 2022-08-19 2022-10-13 2022-10-03 2023-01-16 2022-11-07 nvelope or explanation) 0 mentation 3 Kandang Haur Cs, SS. Eretan rainage System Cs. Jawa Barat Kab. Indramay u ID-DIL-303146-CW-RFB / Reh Component B: Strategic Mod abilitasi Peningkatan dan Mo Single Stage - One E Other (with field f 14,139,571.0 Under Imple 2023-11-0 IBRD / 88910 ernization of Irrigation and D Prior Request for Bids Open - National 0.00 2022-07-24 2022-08-10 2022-07-29 2022-08-19 2022-10-13 2022-10-03 2023-01-26 2022-11-07 dernisasi Jaringan Irigasi SS. nvelope or explanation) 0 mentation 7 rainage System Anjatan Cs, SS. Sukra Cs Jaw a Barat Kab. Indramayu ID-DIL-303149-CW-RFB / Reh abilitasi, Peningkatan dan Mo Component B: Strategic Mod dernisasi Jaringan Irigasi SS J Single Stage - One E Other (with field f 13,846,464.0 Under Imple 2023-11-1 COFN / C1530 ernization of Irrigation and D Prior Request for Bids Open - National 0.00 2022-07-31 2022-08-26 2022-08-05 2022-08-26 2022-10-21 2022-10-10 2023-01-27 2022-11-14 engkol Cs, SS. Pengkolan Cs, nvelope or explanation) 0 mentation 4 rainage System SS. Sukamandi Cs, SS. Beres Cs Jawa Barat Kab. Subang ID-DIL-303151-CW-RFB / Reh abilitasi Peningkatan dan Mo Component B: Strategic Mod Single Stage - One E Other (with field f 2023-10-3 dernisasi Jaringan Irigasi SS K COFN / C1530 ernization of Irrigation and D Post Request for Bids Open - National 5,974,000.00 0.00 Signed 2022-07-31 2022-10-09 2022-08-05 2022-08-26 2022-11-15 2022-09-25 2023-01-02 2022-10-30 nvelope or explanation) 0 amurang CS, SS. Rancabang rainage System o CS, SI. Karang Toman, Jawa Barat Kab. Subang ID-DIL-307721-CW-RFB / Reh Component A: Urgent Rehab abilitasi Jaringan Irigasi DI. S Single Stage - One E Other (with field f 2024-01-0 COFN / C1530 ilitation of Irrigation and Drai Post Request for Bids Open - National 3,426,242.86 0.00 Canceled 2022-08-11 2022-08-30 2022-08-16 2022-09-06 2022-10-06 2022-11-10 ei Ular (Pulau Gambar, Sumb nvelope or explanation) 4 nage System er Rejo Baru, Timbang Deli) ID-DIL-307725-CW-RFB / Reh Component A: Urgent Rehab Single Stage - One E Other (with field f 2023-12-2 abilitasi Jaringan irigasi DI. S COFN / C1530 ilitation of Irrigation and Drai Post Request for Bids Open - National 8,942,285.71 0.00 Signed 2022-08-21 2022-10-26 2022-08-26 2022-08-28 2022-11-16 2022-09-27 2022-12-06 2022-11-01 nvelope or explanation) 6 ei Ular ( Buluh, Sumber Rejo) nage System ID-DIL-307728-CW-RFB / Reh Component A: Urgent Rehab Single Stage - One E Other (with field f Under Imple 2024-01-1 abilitasi Jaringan Tersier DI S COFN / C1530 ilitation of Irrigation and Drai Post Request for Bids Open - National 4,464,285.71 0.00 2022-08-21 2022-09-22 2022-08-26 2022-09-16 2022-10-16 2022-11-20 nvelope or explanation) mentation 4 ei Ular nage System ID-DIL-307729-CW-RFB / Civi l Work for (NTC) SS. Lamaya Component B: Strategic Mod Single Stage - One E Other (with field f Under Imple 2024-01-1 Barat : Rehabilitasi, Peningka COFN / C1530 ernization of Irrigation and D Post Request for Bids Open - National 5,012,529.00 0.00 2022-08-21 2022-10-10 2022-08-26 2022-09-16 2022-11-15 2022-10-16 2022-11-20 nvelope or explanation) mentation 4 tan dan Modernisasi Jaringan rainage System Irigasi SS Lamaya Barat Cs ID-DIL-307735-CW-RFB / Reh Component B: Strategic Mod abilitasi Saluran induk Tarum Single Stage - One E Other (with field f 14,285,714.2 Under Imple 2023-01-0 COFN / C1530 ernization of Irrigation and D Prior Request for Bids Open - National 0.00 2022-08-21 2022-10-17 2022-08-26 2022-09-16 2022-11-22 2022-10-16 2023-02-01 2022-11-20 Utara (Bendung Leuweung S nvelope or explanation) 9 mentation 1 rainage System eureuh - B.Tub 26) ID-DIL-307738-CW-RFB / Reh Component B: Strategic Mod Single Stage - One E Other (with field f 10,857,142.0 Under Imple 2024-01-1 abilitasi Saluran induk Tarum COFN / C1530 ernization of Irrigation and D Prior Request for Bids Open - National 0.00 2022-08-21 2022-10-16 2022-08-26 2022-09-16 2022-11-22 2022-10-16 2023-01-11 2022-11-20 nvelope or explanation) 0 mentation 4 Utara (Bendung Walahar - B. rainage System Tut 14) ID-DIL-307739-CW-RFB / Non Regret Measures Daerah Irig Component B: Strategic Mod asi Jatiluhur (Salamdarma Sip Single Stage - One E Other (with field f Under Imple 2024-01-1 COFN / C1530 ernization of Irrigation and D Post Request for Bids Open - National 9,788,000.00 0.00 2022-08-21 2022-10-25 2022-08-26 2022-09-16 2022-11-22 2022-10-16 2022-11-20 hon and Desilting Basin, Mac nvelope or explanation) mentation 4 rainage System an Desilting Basin, Barugbug Weir, Cigadug Weir Upgrade and Deflector) Component A: Urgent Rehab ID-DIL-307742-CW-RFB / Reh Single Stage - One E Other (with field f 2024-01-1 COFN / C1530 ilitation of Irrigation and Drai Post Request for Bids Open - National 5,357,142.00 0.00 Signed 2022-08-21 2022-10-04 2022-08-26 2022-09-16 2022-10-27 2022-10-16 2022-11-16 2022-11-20 abilitation DI Tabo-Tabo nvelope or explanation) 4 nage System National Procure ID-DIL-316429-CW-RFB / Reh Component B: Strategic Mod ment Document - Single Stage - One E Under Imple 2024-02-1 abilitasi Jaringan Irigasi Tersi COFN / C1530 ernization of Irrigation and D Post Request for Bids Open - National 1 Envelope proce 4,781,573.00 0.00 2022-09-25 2022-12-26 2022-09-30 2022-10-21 2022-11-20 2022-12-25 nvelope mentation 8 er SS. Pamanukan Cs DI. Jatil rainage System ss (Non Bank-SPD uhur ) National Procure ID-DIL-316430-CW-RFB / Reh Component B: Strategic Mod ment Document - abilitasi Jaringan Irigasi Tersi Single Stage - One E Under Imple 2024-02-1 COFN / C1530 ernization of Irrigation and D Post Request for Bids Open - National 1 Envelope proce 4,828,618.00 0.00 2022-09-25 2022-12-26 2022-09-30 2022-10-21 2023-01-25 2022-11-20 2022-12-25 er SS. Gadung Cs, SS. Salam nvelope mentation 8 rainage System ss (Non Bank-SPD darma Cs DI Jatiluhur ) National Procure ID-DIL-316432-CW-RFB / Reh Component B: Strategic Mod ment Document - Single Stage - One E Under Imple 2024-02-1 abilitasi Jaringan Irigasi Tersi COFN / C1530 ernization of Irrigation and D Post Request for Bids Open - National 1 Envelope proce 3,648,507.00 0.00 2022-09-25 2022-12-26 2022-09-30 2022-10-21 2022-11-20 2022-12-25 nvelope mentation 8 er SS. Macan Cs DI Jatiluhur rainage System ss (Non Bank-SPD ) ID-DIL-316434-CW-RFB / Reh Component B: Strategic Mod Single Stage - One E Other (with field f Under Imple 2024-02-1 abilitasi Jaringan Irigasi Tersi COFN / C1530 ernization of Irrigation and D Post Request for Bids Open - National 1,641,068.00 0.00 2022-09-25 2022-12-26 2022-09-30 2022-10-21 2023-01-25 2022-11-20 2022-12-25 nvelope or explanation) mentation 8 err SS. Pawelutan Cs DI Jatilu rainage System hur National Procure ID-DIL-317964-CW-RFB / Reh Component A: Urgent Rehab ment Document - Single Stage - One E 2024-02-2 abilitasi Tingkat Lanjut Jaring COFN / C1530 ilitation of Irrigation and Drai Post Request for Bids Open - National 1 Envelope proce 2,689,571.00 0.00 Signed 2022-10-02 2022-10-04 2022-10-07 2022-10-28 2022-10-27 2022-11-27 2022-11-16 2023-01-01 nvelope 5 an Primer DI. Pamukulu Taha nage System ss (Non Bank-SPD p2 ) ID-DIL-335116-CW-RFB / Reh Component A: Urgent Rehab Single Stage - One E Other (with field f Pending Imp 2024-03-0 abilitasi dan Peningkatan Jari COFN / C1530 ilitation of Irrigation and Drai Post Request for Bids Open - National 3,535,714.00 0.00 2023-01-22 2023-01-27 2023-03-10 2023-04-09 2023-05-14 nvelope or explanation) lementation 9 ngan DIR Katingan Tahap III nage System Component A: Urgent Rehab ID-DIL-335157-CW-RFB / Reh Single Stage - One E Other (with field f 2024-02-0 COFN / C1530 ilitation of Irrigation and Drai Post Request for Bids Open - National 1,553,874.00 0.00 Signed 2023-01-09 2022-12-23 2023-01-14 2023-02-04 2023-01-13 2023-03-06 2023-02-01 2023-04-10 abilitasi Bendung DI.Sei Ular nvelope or explanation) 4 nage System ID-DIL-335158-CW-RFB / Reh Component A: Urgent Rehab abilitasi Jaringan Irigasi DI. S Single Stage - One E Other (with field f 2024-02-0 COFN / C1530 ilitation of Irrigation and Drai Post Request for Bids Open - National 3,426,242.86 0.00 Signed 2023-01-09 2022-12-23 2023-01-14 2023-02-04 2023-01-13 2023-03-06 2023-02-01 2023-04-10 ei Ular (Pulau Gambar, Sumb nvelope or explanation) 4 nage System er Rejo Baru, Timbang Deli) ID-DIL-361489-CW-RFB / Reh Component A: Urgent Rehab abilitasi/Revitalisasi High Lev Single Stage - One E Other (with field f Pending Imp 2024-04-2 COFN / C1530 ilitation of Irrigation and Drai Post Request for Bids Open - National 6,139,190.00 0.00 2023-05-12 2023-05-17 2023-06-28 2023-07-28 2023-09-01 el Diversion (HLD) - Paket 3 ( nvelope or explanation) lementation 8 nage System BJS17-BJS24 dan BJB19-BJB2 7) GOODS Page 3 Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ID-DIL-CS-A / TA DED & Supe Component A: Urgent Rehab Quality And Cost- Open - Internationa rvision of Component A SIMU IBRD / 88910 ilitation of Irrigation and Drai Prior 24,532,200.00 19,926,997.10 Signed 2019-10-03 2020-09-16 2019-10-24 2020-08-18 2020-12-19 2020-10-02 2021-02-22 2020-10-08 2021-11-04 2020-10-20 2021-12-14 2020-10-30 2022-02-04 2024-03-31 Based Selection l RP nage System ID-DIL-CS-B / TA DED & Supe Component B: Strategic Mod Quality And Cost- Open - Internationa rvision of Component B SIMU IBRD / 88910 ernization of Irrigation and D Prior 15,223,786.00 13,283,351.29 Signed 2019-10-03 2020-09-16 2019-10-24 2020-08-18 2020-12-16 2020-10-02 2021-02-22 2020-10-08 2021-08-04 2020-10-20 2021-10-17 2020-10-31 2022-02-04 2024-03-31 Based Selection l RP rainage System ID-DIL-204654-CS-QCBS / Te Component C: Project Mana Quality And Cost- Open - Internationa chnical Assistance Study of L IBRD / 88910 Prior 5,479,000.00 0.00 Canceled 2020-12-09 2020-12-29 2020-12-09 2021-01-28 2021-02-28 2021-03-22 2021-04-27 2021-05-05 2023-05-05 gement Based Selection l owland Development and Pe at Restoration ID-DIL-253705-CS-QCBS / TA Component C: Project Mana Quality And Cost- Open - Internationa Study of Lowland Developme IBRD / 88910 Prior 5,643,496.00 0.00 Signed 2021-09-16 2021-09-29 2021-09-17 2021-10-06 2021-10-15 2022-03-02 2022-01-19 2022-05-10 2022-02-02 2022-09-07 2022-02-15 2022-12-08 2022-03-15 2023-05-03 2024-02-13 gement Based Selection l nt and Peat Restoration INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ID-DIL-CS-INDPAMUKULU / In Component C: Project Mana Individual Consult Pending Impleme dividual Consultant Bridging IBRD / 88910 Post Direct 6,428.57 0.00 2020-07-01 2020-07-11 2020-07-16 2020-08-18 2020-11-18 gement ant Selection ntation Supervision Page 4