PROCUREMENT PLAN (Textual Part) Project information: Solomon Islands – Tina River Hydropower Development Project (P161319) Project Implementation agency: The Solomon Island Energy Authority – SIEA (in the trade name of the Solomon Power – SP), and the Ministry of Mines, Energy and Rural Electrification Date of the Procurement Plan: May 10, 2017 Period covered by this Procurement Plan: from 2017 to 2023 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. At this stage, no contracts are expected to be procured by approaching the national market. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Not Applicable. Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – Not Applicable. Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works) – not applicable. PROCUREMENT Solomon Islands : Tina River Hydropower Development Project PLAN General Information Country: Solomon Islands 2017-11-21 Bank’s Approval Date of the Original Procurement Plan: 2024-05-08 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P161319 GPN Date: 2017-11-15 Project Name: Tina River Hydropower Development Project Loan / Credit No: TF / A1895, IDA / D2020, TF / A4843 Ministry of Mines, Energy and Rural Electrification Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SB-MMERE-140924-CS-INDV Component 4: Technical Assi Quality And Cost- Open - Internationa IDA / D2020 Prior 2,500,000.00 1,459,878.00 Under Review 2019-10-17 2019-10-30 2019-11-07 2019-10-31 2019-12-21 2019-11-12 2020-01-18 2019-12-23 2020-02-17 2020-01-07 2020-03-23 2020-01-16 2020-04-27 2020-02-14 2021-04-27 / Lenders Technical Advisor stance Based Selection l SB-MMERE-183627-CS-CQS / Component 4: Technical Assi Consultant Qualifi IDA / D2020 Post Limited 54,000.00 0.00 Canceled 2020-07-15 2020-07-29 2020-08-28 2020-10-02 2021-03-31 Technical Advisor stance cation Selection INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SB-MMERE-36062-CS-INDV / Component 4: Technical Assi Individual Consult TF / A1895 Post Direct 18,000.00 18,000.00 Completed 2017-11-09 2017-11-09 2017-11-19 2017-11-19 2017-12-10 2017-12-10 2018-01-14 2017-10-22 2018-07-13 2018-01-07 Project Manager stance ant Selection SB-MMERE-36717-CS-CDS / Component 4: Technical Assi Strategic Advisor, Commerci TF / A1895 Post Direct Selection Direct 24,000.00 24,000.00 Completed 2017-11-14 2017-11-14 2017-11-24 2017-11-24 2018-01-28 2017-11-19 2018-07-27 2018-07-15 stance al and Financial SB-MMERE-47235-CS-CDS / Component 4: Technical Assi TF / A1895 Post Direct Selection Direct 28,800.00 28,800.00 Completed 2018-02-08 2018-02-08 2018-02-08 2018-02-08 2018-02-15 2018-01-19 2018-06-30 2018-07-14 Legal Advisor Contract stance SB-MMERE-48065-CS-CDS / Component 4: Technical Assi Project Manager Contract Jan TF / A1895 Post Direct Selection Direct 36,000.00 36,000.00 Completed 2018-02-08 2019-01-24 2018-02-13 2019-01-29 2018-02-15 2018-02-27 2018-06-30 2018-07-09 stance uary to June 2018 SB-MMERE-48068-CS-CDS / Component 4: Technical Assi Strategic Advisor, Safeguard TF / A1895 Post Direct Selection Direct 63,030.00 63,030.00 Completed 2018-02-08 2018-02-08 2018-02-12 2018-02-12 2018-02-15 2018-01-13 2018-06-30 2018-07-09 stance and stakeholder Engagement Contract SB-MMERE-48074-CS-CDS / Component 4: Technical Assi Technical Advisor Engineerin TF / A1895 Post Direct Selection Direct 37,800.00 37,800.00 Completed 2018-02-08 2018-02-08 2018-02-14 2018-02-14 2018-02-16 2018-02-27 2018-06-30 2018-07-09 stance g Contract January to June 20 18 SB-MMERE-99680-CS-CDS / Component 4: Technical Assi IDA / D2020 Post Direct Selection Direct 16,200.00 22,600.00 Completed 2019-02-18 2019-02-18 2019-02-18 2019-02-18 2019-03-01 2019-03-18 2019-03-31 2019-04-15 Senior Project Advisor stance SB-MMERE-99681-CS-CDS / Component 4: Technical Assi IDA / D2020 Post Direct Selection Direct 13,950.00 358,755.00 Completed 2019-02-08 2019-02-08 2019-02-18 2019-02-18 2019-02-18 2019-03-18 2019-03-31 2020-07-15 Technical Advisor ( Engineeri stance ng) SB-MMERE-99682-CS-CDS / Component 4: Technical Assi IDA / D2020 Post Direct Selection Direct 9,375.00 367,400.00 Signed 2019-02-08 2019-02-08 2019-02-18 2019-02-18 2019-03-18 2019-03-18 2019-03-31 Legal Advisor stance SB-MMERE-99683-CS-CDS / Component 4: Technical Assi Strategic Advisor, Safeguard IDA / D2020 Post Direct Selection Direct 24,550.00 113,425.00 Completed 2019-02-08 2019-02-08 2019-02-18 2019-02-18 2019-03-18 2019-03-18 2019-03-31 2019-04-15 stance and stakeholder Engagement Plan SB-MMERE-110090-CS-INDV / Community Liaison Officer a Component 4: Technical Assi Individual Consult IDA / D2020 Post Open 25,500.00 53,812.30 Completed 2019-04-11 2019-04-11 2019-05-30 2019-09-11 2019-06-20 2019-09-12 2019-07-25 2019-09-27 2020-03-31 2020-08-15 nd Gender Focal Point for Tin stance ant Selection a River Hydro power Project SB-MMERE-110120-CS-INDV / Community Liaison Officer a Component 4: Technical Assi Individual Consult nd Livelihood Restoration Ma IDA / D2020 Post Open 25,538.25 25,832.00 Completed 2019-04-11 2019-04-11 2019-05-30 2019-09-13 2019-06-20 2019-09-14 2019-07-25 2019-09-21 2020-03-31 2020-08-07 stance ant Selection nager for Tina River Hydropo wer Development Project SB-MMERE-110122-CS-INDV Component 4: Technical Assi Individual Consult / Communications Officer for IDA / D2020 Post Open 17,850.00 17,850.00 Completed 2019-04-11 2019-04-11 2019-05-30 2020-10-28 2019-06-20 2020-10-28 2019-07-25 2020-02-20 2020-03-31 2021-02-21 stance ant Selection Tina River Hydropower Devel opment Project Page 1 SB-MMERE-110124-CS-INDV / Environmental & Social Safe Component 4: Technical Assi Individual Consult IDA / D2020 Post Open 23,638.50 23,916.00 Completed 2019-04-11 2019-04-11 2019-05-30 2019-09-11 2019-06-20 2019-09-12 2019-07-25 2019-09-20 2020-03-31 2020-06-06 guard Officer for Tina River H stance ant Selection ydropower Development Proj ect. SB-MMERE-110926-CS-INDV Component 4: Technical Assi Individual Consult / Deputy Project Manager for IDA / D2020 Post Open 68,040.00 75,250.00 Completed 2019-04-17 2019-04-17 2019-06-05 2019-06-26 2019-05-02 2019-07-31 2019-09-29 2020-03-31 2020-05-15 stance ant Selection Tina River Hydropower Devel opment Project SB-MMERE-110929-CS-INDV Component 4: Technical Assi Individual Consult / Project Manager for Tina Riv IDA / D2020 Post Open 221,000.00 0.00 Canceled 2019-04-17 2019-04-17 2019-06-05 2019-06-26 2019-07-31 2020-03-31 stance ant Selection er Hydropower Development Project SB-MMERE-120345-CS-CDS / Component 4: Technical Assi Dam Safety Advisory Panel: IDA / D2020 Post Direct Selection Direct 33,720.00 95,160.00 Signed 2019-06-24 2019-07-19 2019-07-04 2019-10-15 2019-09-07 2019-05-14 2020-05-09 stance Hydropower /Civil Dam Engin eer SB-MMERE-120346-CS-CDS / Component 4: Technical Assi Dam Safety Advisory Panel: E IDA / D2020 Post Direct Selection Direct 20,160.00 88,480.00 Signed 2019-06-24 2019-07-19 2019-07-04 2020-03-23 2019-09-07 2019-05-15 2020-05-09 stance lectro/Merchanical Expert SB-MMERE-120347-CS-CDS / Component 4: Technical Assi Dam Safety Advisory Panel: IDA / D2020 Post Direct Selection Direct 45,920.00 222,360.00 Signed 2019-06-25 2019-07-19 2019-07-05 2019-10-15 2019-09-08 2019-05-15 2020-05-09 stance Getechnical/Geology Expert SB-MMERE-121257-CS-CDS / Component 4: Technical Assi Dam Safety Advisory Panel- IDA / D2020 Post Direct Selection Direct 35,700.00 131,120.00 Signed 2019-06-27 2019-07-19 2019-07-07 2019-10-15 2019-09-10 2019-06-06 2020-05-10 stance Hydraulics/sediment Expert SB-MMERE-121258-CS-CDS / Component 4: Technical Assi Dam Safety Advisory Panel: S IDA / D2020 Post Direct Selection Direct 60,080.00 148,160.00 Signed 2019-06-27 2019-07-19 2019-07-07 2019-10-15 2019-09-10 2019-05-23 2020-05-09 stance eismologist SB-MMERE-121252-CS-CDS / Component 4: Technical Assi Project Implementation Supp IDA / D2020 Post Direct Selection Direct 15,480.00 15,480.00 Completed 2019-06-27 2019-07-29 2019-07-07 2019-07-30 2019-09-10 2019-09-28 2020-03-08 2020-11-19 stance ort Officer SB-MMERE-121249-CS-CDS / Component 4: Technical Assi IDA / D2020 Post Direct Selection Direct 10,320.00 10,320.00 Completed 2019-06-27 2019-07-29 2019-07-07 2019-07-30 2019-09-10 2019-09-28 2020-06-30 2020-11-19 Resource Management Office stance r SB-MMERE-121251-CS-CDS / Component 4: Technical Assi IDA / D2020 Post Direct Selection Direct 17,850.00 17,850.00 Completed 2019-06-27 2019-07-29 2019-07-07 2019-07-30 2019-09-10 2019-09-28 2020-06-30 2021-07-16 Project Accountant stance SB-MMERE-125620-CS-INDV Component 4: Technical Assi Individual Consult IDA / D2020 Post Direct 17,000.00 17,000.00 Completed 2019-07-31 2019-07-31 2019-08-09 2019-08-09 2019-08-30 2019-08-30 2019-09-23 2019-10-09 2019-09-30 2019-10-16 / Management Plan Consulta stance ant Selection nt SB-MMERE-125990-CS-INDV Component 4: Technical Assi Individual Consult IDA / D2020 Post Direct 16,395.90 16,614.90 Completed 2019-08-03 2020-09-09 2019-08-13 2020-09-10 2019-09-03 2020-09-10 2019-10-08 2019-08-02 2020-04-05 / Livelihood Mapping stance ant Selection SB-MMERE-126107-CS-INDV Component 4: Technical Assi Individual Consult IDA / D2020 Post Direct 19,675.08 19,675.08 Completed 2019-08-03 2020-09-24 2019-08-13 2020-09-24 2019-09-03 2020-09-28 2019-10-08 2021-08-05 2020-04-05 / Archaeological Survey stance ant Selection SB-MMERE-126109-CS-INDV Component 4: Technical Assi Individual Consult IDA / D2020 Post Direct 7,870.03 7,870.03 Completed 2019-08-03 2020-02-11 2019-08-13 2020-09-10 2019-09-03 2020-09-10 2019-10-08 2020-09-23 2020-04-05 / Tribal Registry stance ant Selection SB-MMERE-138812-CS-CDS / Component 4: Technical Assi IDA / D2020 Post Direct Selection Direct 17,200.00 17,200.00 Completed 2019-10-07 2019-10-08 2019-10-17 2021-10-12 2019-12-21 2021-02-24 2020-06-18 2021-03-09 Plantation Valuation Consulta stance nt SB-MMERE-138922-CS-INDV Component 4: Technical Assi Individual Consult IDA / D2020 Post Open 73,935.00 328,170.00 Completed 2019-10-08 2020-03-23 2019-11-26 2020-01-05 2019-12-17 2020-04-06 2020-01-21 2019-11-26 2020-07-19 2021-11-11 / Communication Adviser stance ant Selection SB-MMERE-168719-CS-INDV Component 4: Technical Assi Individual Consult / Social - Economic Baseline IDA / D2020 Post Direct 66,000.00 66,000.00 Completed 2020-04-15 2020-04-25 2020-04-25 2021-10-12 2020-05-16 2021-10-11 2020-06-20 2020-06-16 2020-12-17 2020-09-01 stance ant Selection Consultant SB-MMERE-169784-CS-INDV Component 4: Technical Assi Individual Consult / Environment and Social Saf IDA / D2020 Post Open 168,000.00 0.00 Canceled 2020-04-27 2020-04-25 2020-06-15 2020-07-06 2020-08-10 2021-02-06 stance ant Selection e guards Manager SB-MMERE-171321-CS-INDV Component 4: Technical Assi Individual Consult Under Implement / Environmental and Social IDA / D2020 Prior Open 336,000.00 0.00 2020-04-29 2020-05-11 2020-06-17 2020-07-08 2020-08-12 2021-02-08 stance ant Selection ation Safeguard Manager SB-MMERE-179053-CS-INDV / Gender Focal Point and Co Component 4: Technical Assi Individual Consult IDA / D2020 Post Open 44,496.00 57,021.30 Signed 2020-06-17 2020-07-20 2020-08-05 2020-09-02 2020-08-26 2020-09-02 2020-09-30 2020-09-14 2022-09-20 mmunity Liaison Officer for Ti stance ant Selection na River Hydro power Project SB-MMERE-179060-CS-INDV / Environmental & Social Safe Component 4: Technical Assi Individual Consult IDA / D2020 Post Open 44,496.00 44,496.00 Completed 2020-06-17 2020-07-20 2020-08-05 2020-09-02 2020-08-26 2020-09-02 2020-09-30 2020-08-13 2022-09-20 2022-08-12 guard Officer for Tina River H stance ant Selection ydropower Development Proj ect. SB-MMERE-179039-CS-INDV Component 4: Technical Assi Individual Consult IDA / D2020 Post Open 120,000.00 129,000.00 Signed 2020-06-17 2020-06-30 2020-08-05 2020-07-27 2020-08-26 2020-07-27 2020-09-30 2020-08-02 2022-09-20 / Deputy Project Manager stance ant Selection SB-MMERE-179042-CS-INDV Component 4: Technical Assi Individual Consult IDA / D2020 Post Open 48,072.00 47,833.20 Signed 2020-06-25 2020-05-01 2020-08-13 2020-09-04 2020-09-03 2020-09-04 2020-10-08 2020-08-07 2022-09-28 / Community Liaison Officer stance ant Selection SB-MMERE-187773-CS-CDS / Component 4: Technical Assi IDA / D2020 Post Direct Selection Direct 1,500.00 1,500.00 Completed 2020-08-07 2020-08-24 2020-08-17 2021-05-05 2020-10-21 2020-10-08 2021-04-19 2020-10-08 Enumerator 1 stance SB-MMERE-187778-CS-CDS / Component 4: Technical Assi IDA / D2020 Post Direct Selection 1,500.00 1,500.00 Completed 2020-08-07 2020-08-24 2020-08-07 2021-05-05 2020-08-07 2020-09-07 2020-08-07 2020-10-07 Enumerator 2 stance SB-MMERE-187779-CS-CDS / Component 4: Technical Assi IDA / D2020 Post Direct Selection Direct 1,500.00 1,500.00 Completed 2020-08-07 2020-08-24 2020-08-17 2021-05-05 2020-10-21 2020-09-07 2021-04-19 2020-10-07 Enumerator 3 stance SB-MMERE-187805-CS-CDS / Component 4: Technical Assi IDA / D2020 Post Direct Selection Direct 1,500.00 1,500.00 Completed 2020-08-07 2020-08-24 2020-08-17 2021-04-30 2020-10-21 2020-09-07 2021-04-19 2020-10-07 Enumerator 4 stance SB-MMERE-187806-CS-CDS / Component 4: Technical Assi IDA / D2020 Post Direct Selection 1,500.00 1,500.00 Completed 2020-08-07 2020-08-24 2020-08-07 2021-04-30 2020-08-07 2020-09-05 2020-08-07 2020-10-07 Enumerator 5 stance SB-MMERE-187820-CS-CDS / Component 4: Technical Assi IDA / D2020 Post Direct Selection Direct 1,500.00 1,500.00 Completed 2020-08-07 2020-08-24 2020-08-17 2021-04-28 2020-10-21 2020-09-05 2021-04-19 2020-10-05 Enumerator 6 stance Page 2 SB-MMERE-187821-CS-CDS / Component 4: Technical Assi IDA / D2020 Post Direct Selection 1,500.00 1,500.00 Completed 2020-08-07 2020-08-24 2020-08-07 2021-04-29 2020-08-07 2020-09-05 2020-08-07 2020-10-05 Enumerator 7 stance SB-MMERE-187822-CS-CDS / Component 4: Technical Assi IDA / D2020 Post Direct Selection 1,500.00 1,500.00 Completed 2020-08-07 2020-08-24 2020-08-07 2021-03-16 2020-08-07 2020-09-06 2020-08-07 2021-05-05 Enumerator 8 stance SB-MMERE-187823-CS-CDS / Component 4: Technical Assi IDA / D2020 Post Direct Selection Direct 8,200.00 8,200.00 Completed 2020-08-07 2020-08-24 2020-08-17 2021-06-16 2020-10-21 2020-09-06 2021-04-19 2020-10-05 Local Team Leader stance SB-MMERE-191661-CS-INDV Component 4: Technical Assi Individual Consult IDA / D2020 Prior Open 462,000.00 488,000.00 Signed 2020-09-14 2020-09-09 2020-11-02 2021-07-08 2020-11-23 2021-07-15 2020-12-28 2021-07-13 2022-12-18 / Project Manager stance ant Selection SB-MMERE-192165-CS-CDS / Component 4: Technical Assi IDA / D2020 Post Direct Selection Direct 54,000.00 54,000.00 Completed 2020-09-07 2021-06-16 2020-09-17 2022-08-24 2020-11-21 2022-07-10 2021-05-20 2022-09-07 Technical Advisor stance SB-MMERE-195923-CS-INDV Component 4: Technical Assi Individual Consult IDA / D2020 Post Open 17,450.00 17,450.00 Signed 2020-09-25 2021-05-11 2020-11-13 2021-06-16 2020-12-04 2021-06-16 2021-01-08 2020-12-10 2022-12-29 / Project Accountant stance ant Selection SB-MMERE-195924-CS-INDV Component 4: Technical Assi Individual Consult / Project Implementation Sup IDA / D2020 Post Open 15,480.00 15,480.00 Terminated 2020-09-25 2021-05-19 2020-11-13 2021-06-10 2020-12-04 2021-06-10 2021-01-08 2021-03-15 2022-12-29 stance ant Selection port Officer SB-MMERE-195925-CS-INDV Component 4: Technical Assi Individual Consult IDA / D2020 Post Open 10,320.00 10,320.00 Signed 2020-09-25 2020-10-20 2020-11-13 2021-05-13 2020-12-04 2021-05-13 2021-01-08 2020-11-13 2022-12-29 / Resource Management Offic stance ant Selection er SB-MMERE-222250-CS-INDV Component 4: Technical Assi Individual Consult / Communication officer for T IDA / D2020 Post Open 17,850.00 17,850.00 Signed 2021-03-15 2021-03-08 2021-05-03 2021-05-20 2021-05-24 2021-05-31 2021-06-28 2021-06-28 2021-12-25 stance ant Selection ina River Hydropower develo pment Project. SB-MMERE-238620-CS-CDS / Component 4: Technical Assi Under Implement Morris & Sojnocki Chartered IDA / D2020 Post Direct Selection Direct 19,801.00 0.00 2021-06-10 2021-11-10 2021-06-20 2021-08-24 2022-02-20 stance ation Accountants (Audit Fee for 2 020) SB-MMERE-261265-CS-CDS / Component 4: Technical Assi IDA / D2020 Post Direct Selection Direct 76,700.00 76,700.00 Signed 2021-11-05 2021-10-28 2021-11-07 2022-08-10 2021-11-10 2021-11-05 2023-10-01 Communication Advisor stance SB-MMERE-261351-CS-INDV Component 4: Technical Assi Individual Consult IDA / D2020 Prior Direct 367,200.00 367,200.00 Signed 2021-11-04 2021-11-09 2021-11-10 2021-11-13 2021-11-15 2021-11-19 2021-12-01 2021-11-27 2023-12-01 / ES Safeguards Manager (Int stance ant Selection ) SB-MMERE-283275-CS-INDV Component 4: Technical Assi Individual Consult Under Implement / Community Liaison Officer IDA / D2020 Post Open - National 45,000.00 0.00 2022-08-01 2022-08-01 2022-09-19 2022-08-01 2022-10-10 2024-03-18 2022-11-14 2023-05-13 stance ant Selection ation & Gender Focal Point (CLO-G FP) SB-MMERE-305157-CS-INDV / Environmental & Social Safe Component 4: Technical Assi Individual Consult Under Implement IDA / D2020 Post Open - National 44,496.00 0.00 2022-08-01 2022-08-22 2022-09-19 2024-04-23 2022-10-10 2024-04-23 2022-11-14 2023-05-13 guard officer for Tina River H stance ant Selection ation ydropower Development Proj ect. SB-MMERE-340895-CS-INDV Component 4: Technical Assi Individual Consult Open - Internationa Under Implement IDA / D2020 Prior 462,000.00 0.00 2023-02-28 2023-03-27 2023-04-18 2023-07-26 2023-05-09 2024-02-08 2023-06-13 2023-12-10 / Project Manager stance ant Selection l ation SB-MMERE-327454-CS-INDV Component 4: Technical Assi Individual Consult / Community Liaison Officer - IDA / D2020 Post Open - National 47,833.20 0.00 Signed 2023-03-02 2023-08-15 2023-04-20 2023-10-03 2023-05-11 2024-02-12 2023-06-15 2022-11-28 2023-12-12 stance ant Selection Social Monitoring SB-MMERE-250666-CS-INDV Component 4: Technical Assi Individual Consult IDA / D2020 Post Open 51,000.00 0.00 Canceled 2021-08-30 2021-08-30 2021-10-18 2021-11-08 2021-12-13 2022-06-11 / Administration Manager stance ant Selection SB-MMERE-390307-CS-CQS / Component 4: Technical Assi Direct - Internation Under Implement IDA / D2020 Post Direct Selection 177,750.00 0.00 2023-11-23 2024-01-04 2023-12-03 2024-01-25 2024-02-06 2024-08-04 Financial Advisor stance al ation SB-MMERE-420462-CS-INDV Component 4: Technical Assi Individual Consult Under Implement TF / A4843 Post Open - National 120,000.00 0.00 2024-04-18 2024-04-26 2024-06-06 2024-06-27 2024-08-01 2025-01-28 / Deputy Project Manager stance ant Selection ation SB-MMERE-418557-CS-INDV Component 4: Technical Assi Individual Consult Open - Internationa Pending Impleme / Environmental & Social Safe IDA / D2020 Prior 400,000.00 0.00 2024-04-12 2024-05-31 2024-06-21 2024-07-26 2025-01-22 stance ant Selection l ntation guard Manager SB-MMERE-419972-CS-CDS / Component 4: Technical Assi Pending Impleme TF / A4843 Post Direct Selection Direct - National 12,500.00 0.00 2024-04-30 2024-05-10 2024-07-14 2026-03-31 Community Consultant Office stance ntation r Page 3