The World Bank
       MG-Electricity Sec Operations & Governance Improvement Project(ESOGIP) (P151785)




                                                                                              REPORT NO.: RES55796




                                            RESTRUCTURING PAPER

                                                     ON A

                                     PROPOSED PROJECT RESTRUCTURING

                                                         OF
                MG-ELECTRICITY SEC OPERATIONS & GOVERNANCE IMPROVEMENT PROJECT(ESOGIP)
                                        APPROVED ON MARCH 22, 2016
                                                         TO

                                     MINISTRY OF ECONOMY AND FINANCE



ENERGY & EXTRACTIVES

EASTERN AND SOUTHERN AFRICA




                              Regional Vice President:    Victoria Kwakwa
                                    Country Director:     Zviripayi Idah Pswarayi Riddihough
                                    Regional Director:    Wendy E. Hughes
                          Practice Manager/Manager:       Erik Magnus Fernstrom
                                 Task Team Leader(s):     Tsiry Andriantahina, Justin Marie Bienvenu
                                                          Beleoken Sanguen
         The World Bank
         MG-Electricity Sec Operations & Governance Improvement Project(ESOGIP) (P151785)



ABBREVIATIONS AND ACRONYMS

ADER                                         Agence de Développement de l’Electrification Rurale/Rural
                                             Electrification Development Agency
AF                                           Additional Financing
ARELEC                                       Autorité de Regulation de l’Electricité / Electricity Regulation Authority
CMS                                          Commercial Management System
DCC                                          Distribution Control Center
DMS                                          Distribution Management System
EPC                                          Engineering Procurement and Construction
ERP                                          Enterprise Resource Planning
ESMAP                                        Energy Sector Management Assistance Program
ESOGIP                                       Electricity Sector Operations & Governance Improvement Project
FM                                           Financial Management
HV                                           High voltage
IDMS                                         Integrated Distribution Management System
IPF                                          investment project financing
JIRAMA                                       Jiro sy Rano Malagasy / National Electricity Utility
kV                                           Kilovolt
kWh                                          Kilowatt-hour
LCDP                                         Least Cost Power Development Plan
MV                                           Medium voltage
NES                                          National Electrification Strategy
O&M                                          Operation and maintenance
PIU                                          Project Implementation Unit
RAP                                          Resettlement Action Plan
RPP                                          Revenue Protection Program
SCADA                                        Supervisory Control and Data Acquisition
TA                                           Technical assistance
WBG                                          World Bank Group
           The World Bank
           MG-Electricity Sec Operations & Governance Improvement Project(ESOGIP) (P151785)




Note to Task Teams: The following sections are system generated and can only be edited online in the Portal.




BASIC DATA


Product Information

Project ID                                                      Financing Instrument
P151785                                                         Investment Project Financing

Original EA Category                                            Current EA Category
Partial Assessment (B)                                          Partial Assessment (B)

Approval Date                                                   Current Closing Date
22-Mar-2016                                                     30-Jun-2023


Organizations

Borrower                                                        Responsible Agency
Ministry of Economy and Finance



Project Development Objective (PDO)
Original PDO
The Project Development Objective is to improve the operational performance of the national electricity utility (JIRAMA)
and improve the reliability of electricity supply in the project area and, in the event of an eligible crisis or emergency, to
provide immediate and effective response to said eligible crisis or emergency.

OPS_TABLE_PDO_CURRENTPDO
Summary Status of Financing (US$, Millions)
                                                                                         Net
Ln/Cr/Tf                 Approval          Signing Effectiveness          Closing Commitment Disbursed Undisbursed

IDA-62800              14-Jun-2018   05-Oct-2018     29-Apr-2019     30-Jun-2023            40.00       17.33          20.93
IDA-57730             22-Mar-2016    08-Apr-2016 24-Aug-2016         30-Jun-2023            65.00       56.78            8.49
          The World Bank
          MG-Electricity Sec Operations & Governance Improvement Project(ESOGIP) (P151785)


 Policy Waiver(s)

 Does this restructuring trigger the need for any policy waiver(s)?
 No




 Note to Task Teams: End of system generated content, document is editable from here.


 I. PROJECT STATUS AND RATIONALE FOR RESTRUCTURING



1. This paper seeks approval from the Country Director for a Level II restructuring of the Electricity Sector Operations &
Governance Improvement Project (ESOGIP), Credits No. 5773-MG (P151785) and No. 6280-MG (P164318), which will
cancel undisbursed amount.

2. Background: ESOGIP is an Investment Project Financing (IPF) that was approved on March 22, 2016, in the amount
of US$65 million equivalent, and became effective on August 24, 2016. An Additional Financing (AF) in the amount of
US$40 million was approved on June 14, 2018 and became effective on April 29, 2019. The Project’s closing date is June
30, 2023. The Project Development Objective (PDO) is " to improve the operational performance of the national electricity
utility (JIRAMA) and improve the reliability of electricity supply in the project area and, in the event of an eligible crisis or
emergency, to provide immediate and effective response to said eligible crisis or emergency.” ESOGIP consists of five main
components: (a) Improving electricity sector planning and financial sustainability (US$5.98 million); (b) Strengthening
operational performance and governance of JIRAMA (US$ 17.56 million); (c) Investing in enhanced reliability of electricity
(US$78.12 million), (d) Project Management (US$3.34 million); and (e) Contingent Emergency Response Component
(CERC) (US$ 0 million).

3. Project performance to date: Progress towards achieving the PDO is rated Moderately Satisfactory (MS), and
Implementation Progress (IP) is rated MS. Financial Management is currently rated Moderately Unsatisfactory (MU),
Procurement is rated satisfactory. There are no pending audits. The project was restructured on December 22, 2021, and
the project closing date extended from December 31, 2021, to June 30, 2023, after the critical issue related to the audit
on asset management has been resolved, giving more time to complete two activities that are at the heart of the project:
(i) dispatching and control center (ii) transmission line. However, the Client is still facing issues on implementation of these
same remaining activities. Firstly, the SCADA and the acquisition and installation of the transmission line has continued
facing complications during the procurement process. The completion by the closure date of the project has been
reassessed to be not achievable in the frame of this project and the Government decided to cancel this activity. Secondly,
the first three lots of 4 for the transmission line activity has been evaluated to be not all completed by the end of the
project as it depends on the implementation of the RAP which is not planned to be completed this semester. The
Government decided to cancel this activity. Also, based on the conclusion of the evaluation of JIRAMA's performance-
based compensation system conducted by the external auditor, it was concluded that the system implemented by JIRAMA
needs much improvement. This led to the non-continuation of this activity given the timeframe of the project.
Although two major activities will not be finalized before the project's closing date of June 30, 2023, the activities carried
out have improved JIRAMA's operational performance as well as its electricity supply. The PDO has been reached at more
than 90 percent. Indeed, in terms of loss reduction, from 35% (in 2015), the project was able to reach 26.9% (February
         The World Bank
         MG-Electricity Sec Operations & Governance Improvement Project(ESOGIP) (P151785)


2023) out of an initial target of 24%. The number of annual interruptions has been reduced by more than half from 870
interruptions per year (in 2015) to 402 interruptions per year (February 2023) out of a target of 450 interruptions. Also,
the number of direct beneficiaries of the project has been reached at 94 percent with a value of 330,000 out of a target
of 350,000 since the beginning of the project. The project was also an essential support for the improvement of the sector
planning as well as the implementation of tariff reforms. In particular, the project has financed the sector's least-cost
development plan and the tariff studies that led to the new tariffs for residential and industrial customers.

4. Status of implementation: Overall disbursement as of February 28, 2023, is US$74.10 million, which represents 72
percent of the available funds. To date, the four project components have progressed as follows:

        a) Component 1: Improving electricity sector planning and financial sustainability: Strategic assessments were
           completed under this component, (a) Least Cost Development Plan (LCDP) providing the roadmap for the
           development of least cost generation projects and associated transmission networks; (b) National
           Electrification Strategies (NES) defining the technical, institutional, and financial arrangements to scale-up
           sustainable provision of electricity services; (c) development of a tariff study to address sector financial
           viability; (d) strengthening capacity of public agencies responsible for least-cost planning and electrification
           (Ministry of Energy, Electricity Regulation Authority [ARELEC], Rural Electrification Development Agency
           [ADER], and JIRAMA ; (e) provision of technical assistance, capacity building, and consultancy service for the
           development of ten (10) small hydro” to prepare tenders for high-priority small hydropower plants (assessed
           under the ESMAP funded TA). This includes reviewing pre-feasibility works for sites, finance detailed
           engineering, environmental and social studies needed to prepare bankable feasibility studies, and provision
           of transaction support and advisory services required to ensure competitive and transparent procurement
           processes.
        b) Component 2: Strengthening operational performance and governance of JIRAMA: the activities completed
           under component 2 are: (iii)implementation of integrated management and geographic information system
           MATSELAKA; (iv) implementation of the Revenues Protection Program; (v) the preparation of the performance
           improvement program for JIRAMA.
           i.   Implementation of the integrated management and geographic information system for GIS
                management called MATSELAKA : In line with the Governance Improvement Program (GIP), this
                component supported the procurement and installation of the GIS system, which include a Commercial
                Management System (CMS), an Integrated Distribution Management System (IDMS) and an Enterprise
                Resource Planning (ERP) system, to improve the efficiency, transparency and accountability of processes
                and development activities in all business areas. This includes operation and maintenance (O&M) of
                electricity supply assets, customers’ complaint handling, commercial functions, and enterprise resource
                management. The installation and use of the GIS system was complemented with maintenance.
          ii.   RPP (Revenue Protection Program) project: This activity identified in the ESOGIP Initial Financing’s (IF)
                PAD consists of implementing the program for the sustainable reduction of non-technical losses in supply
                (off-meter consumption) through the systematic remote recording and monitoring of consumption of
                large users, as foreseen in the GIP. The initial phase of the RPP included a "high value" segment of about
                8,500 meters, which accounts for 50 percent of total physical sales (kilowatt-hours) in 2014. This segment
                is composed of all 1300 HV/MV customers and the 7200 users connected to LV grids with a monthly
                demand higher than 500 kWh or with doubtful consumption situations. The contract was awarded to ZTE
                as an EPC with the supply, installation, and commissioning of 8500 smart meters. The contract was
                completed in July 2021. As a reminder, 40% of the revenue from electricity activities is generated by
         The World Bank
         MG-Electricity Sec Operations & Governance Improvement Project(ESOGIP) (P151785)


               HV/MV customers. Clear improvements were made in these resources just after the meters were
               commissioned.
          iii. Preparation of the performance improvement program for JIRAMA: The project supported the
               recruitment of JIRAMA's senior management team completed in 2019. This included the Director General,
               deputy CEOs, and Directors (including the Director of Human Resources). Also, the project evaluated the
               Performance-Based Compensation programs implemented internally by JIRAMA. The first bonus
               payments for 2020 and 2021 were carried out by JIRAMA under its own funding. An independent auditor
               recruited at the end of 2021 in charge of the evaluation and the monitoring of the Performance Based
               Compensation program proposed by JIRAMA delivered his report in 2022. The conclusion confirmed that
               the system implemented by JIRAMA needs improvement.
        c) Component 3: Investing in enhanced reliability of electricity
In the component 3 the main completed activity is: Andekaleka screening machine, Reinforcement of the existing 138 /
63kV substation, Rehabilitation and/or improvement of existing distribution networks, the rehabilitation of production
plants auxiliaries.
         iv.    ANDEKALEKA screening machine : The mobile automatic screening machine has been installed at the 96
                MW Andekaleka Hydroelectric Plant. Functional and operational tests were successfully carried out with
                the operating teams during the month of June-July 2021. It should be noted that this installation will solve
                the problems of clogging of the dam’s grid of the power station during the periods of intense rain and
                cyclones leading to the reduction or even the stop of the production of the power station for a few days
                and which leads each time to load shedding at the level of the RIA with minimum losses of 600 KUS$ for
                each occurrence of clogging.
          v.    Reinforcement of the existing 138 / 63kV substation: The two transformers provided by CHINT are in
                operation since October 2022. The connection of the transformers with the grid coming from Andekaleka
                has been successfully performed and the full power from the dam can be absorbed.
         vi.    Rehabilitation and/or improvement of existing distribution networks: 288km of the 300km (representing
                96%) of distribution lines planned to be rehabilitated and constructed under the project are completed as
                of February 28, 2023.


        d) Component 4 - Project Management: All planned arrangements are in place, including the Project
           Implementation Unit (PIU) housed in the Ministry in charge of Energy and JIRAMA are staffed and operational.
5.   Activities to be cancelled:
        e) RIA 90kV looping lines project, substations and 20kV passages in the regions: This activity concerns the
           supply and installation of equipment, reinforcement and extension works of the RIA source substations,
           adaptation of the medium voltage parts to allow the passage in 20 kV in the regions; and the supply and
           installation of equipment and extension works of a part of the Antananarivo interconnected network by the
           construction of two 90 kV lines (with a variant in 63 kV) connecting respectively: the Tana North substation to
           the Ambodivona substation, and the Tana North substation to the Tana South substation. Negotiations
           between JIRAMA and the tenders are completed for the 4 lots of the activity. However only the contract for
           lot 4 has been signed with constructions and installations planned to be finalized by the end of the project.
           The 3 other lots are still in the procurement phase since JIRAMA has changed his organization last quarter
           2022 leading to the lack of the persons in charge of signatures. Also, given the multiple delays in implementing
         The World Bank
         MG-Electricity Sec Operations & Governance Improvement Project(ESOGIP) (P151785)


             the Resettlement of Affected Persons (RAP) and the lack of clear visibility, the cancellation of Lot No. 1, 2 and
             3 relating to work on the 90 kV transmission line is considered.
        f)   Dispatching and BCC project: This activity allows for the centralised management of generation, transmission
             and distribution networks, in particular to reduce energy production costs and intervention times on the
             electricity networks throughout Madagascar. The procurement process for the building was finalized and the
             construction phase has started in September 2022. The structural works of the building show good progress
             and will be finalized by the end of the closing date of the project. Regarding the SCADA system, the project is
             facing procurement delays due to procurement issues. And considering the uncertainties as to the date of
             signature of the contract and the remaining time of the project, the completion of this activity won’t be
             achieved.
        g) Performance-Based Compensation programs: Based on the conclusion of the evaluation of JIRAMA's
           performance-based compensation system conducted by the external auditor, it was concluded that the
           system implemented by JIRAMA needs much improvement. This led to the non-continuation of this activity
           given the timeframe of the project.




 II. DESCRIPTION OF PROPOSED CHANGES


6. Cancellation of non-used credit. SDR 19.8 million non-used credit related to (i) dispatching and control center, (ii)
transmission line, and (iii) performance-based compensation will be cancelled.




 Note to Task Teams: The following sections are system generated and can only be edited online in the Portal.



 III. SUMMARY OF CHANGES

                                                                         Changed                       Not Changed
 Results Framework                                                          ✔
 Components and Cost                                                        ✔
 Cancellations Proposed                                                     ✔
 Reallocation between Disbursement Categories                               ✔
 Disbursement Estimates                                                     ✔
 Implementing Agency                                                                                         ✔
                                       The World Bank
                                       MG-Electricity Sec Operations & Governance Improvement Project(ESOGIP) (P151785)



DDO Status                                                                                                                   ✔
Project's Development Objectives                                                                                             ✔
PBCs                                                                                                                         ✔
Loan Closing Date(s)                                                                                                         ✔
Disbursements Arrangements                                                                                                   ✔
Overall Risk Rating                                                                                                          ✔
Safeguard Policies Triggered                                                                                                 ✔
EA category                                                                                                                  ✔
Legal Covenants                                                                                                              ✔
Institutional Arrangements                                                                                                   ✔
Financial Management                                                                                                         ✔
Procurement                                                                                                                  ✔
Implementation Schedule                                                                                                      ✔
Other Change(s)                                                                                                              ✔
Economic and Financial Analysis                                                                                              ✔
Technical Analysis                                                                                                           ✔
Social Analysis                                                                                                              ✔
Environmental Analysis                                                                                                       ✔


IV. DETAILED CHANGE(S)


OPS_DETAILEDCHANGES_COMPONENTS_TABLE




COMPONENTS
                                                                     Current
Current                                                                                       Proposed                             Proposed
                                                                        Cost         Action
Component Name                                                                                Component Name                     Cost (US$M)
                                                                     (US$M)
Improving electricity sector                                                                  Improving electricity sector
planning and financial                                                  5.98     No Change    planning and financial                    5.98
sustainability                                                                                sustainability
Strengthening operational                                                                     Strengthening operational
performance and governance of                                          17.56        Revised   performance and governance               17.56
JIRAMA                                                                                        of JIRAMA
Investing in enhanced reliability                                                             Investing in enhanced
                                                                       78.12        Revised                                            78.12
of electricity                                                                                reliability of electricity
                                                  The World Bank
                                                  MG-Electricity Sec Operations & Governance Improvement Project(ESOGIP) (P151785)



            Project management                                                      3.34     No Change     Project management                              3.34
                                                                                                           Immediate Response
            Immediate Response Mechanism                                            0.00     No Change                                                     0.00
                                                                                                           Mechanism
            TOTAL                                                                105.00                                                                  105.00



        OPS_DETAILEDCHANGES_CANCELLATIONS_TABLE




        CANCELLATIONS


                                                                                                                      Value                           Reason
                                                                                  Current      Cancellation                             New
          Ln/Cr/Tf                                      Status    Currency                                          Date of                               for
                                                                                  Amount          Amount                              Amount
                                                                                                                Cancellation                     Cancellation
                                                        Disburs                                                                                  UNDISBURSE
          IDA-57730-
                                                        ing&Re     XDR       47,100,000.00    6,300,000.00      28-Apr-2023      40,800,000.00    D BALANCE
          001
                                                        paying                                                                                    AT CLOSING
                                                                                                                                                 UNDISBURSE
          IDA-62800-                                    Disburs
                                                                   XDR       27,900,000.00   13,500,000.00      28-Apr-2023      14,400,000.00    D BALANCE
          001                                           ing
                                                                                                                                                  AT CLOSING
OPS_DETAILEDCHANGES_REALLOCATION _TABLE




          REALLOCATION BETWEEN DISBURSEMENT CATEGORIES

                                                                                                                                          Financing %
                                                   Current Allocation        Actuals + Committed           Proposed Allocation
                                                                                                                                          (Type Total)
                                                                                                                                       Current      Proposed

          IDA-57730-001                                  |   Currency: XDR

         iLap Category Sequence No: 1                                            Current Expenditure Category: GD,WK,NCS,CS,TR & OC Pt 1;4.1

                                                        1,300,000.00                 1,078,591.23                1,300,000.00          100.00            100.00


         iLap Category Sequence No: 2                                            Current Expenditure Category: GD,WK,NCS,CS,TR & OC Pt 2;3;4.2

                                                       44,800,000.00               36,140,606.26                38,500,000.00          100.00            100.00


         iLap Category Sequence No: 3                                            Current Expenditure Category: PPF REFINANCING

                                                        1,000,000.00                  303,498.14                 1,000,000.00


         iLap Category Sequence No: 4                                            Current Expenditure Category: Emergency Expenditures Pt 5
                                         The World Bank
                                         MG-Electricity Sec Operations & Governance Improvement Project(ESOGIP) (P151785)



                                                       0.00                         0.00                          0.00       100.00             100.00


Total                                         47,100,000.00                37,522,695.63               40,800,000.00



IDA-62800-001                                   |   Currency: XDR

iLap Category Sequence No: 1                                            Current Expenditure Category: GD,WK,NCS,CS,TR & OC Pt 1.2&4.1

                                               2,900,000.00                 2,612,309.05                2,900,000.00         100.00             100.00


iLap Category Sequence No: 2                                            Current Expenditure Category: GD,WK,NCS,CS,TR & OC Pt 2.2;3;4.2

                                              22,200,000.00                 6,790,846.88               10,800,000.00         100.00             100.00


iLap Category Sequence No: 3A                                           Current Expenditure Category: GD,WK,NCS,CS,TR & OC Pt 2.2

                                                700,000.00                          0.00                    700,000.00       100.00             100.00


iLap Category Sequence No: 3B                                           Current Expenditure Category: PERFORMANCE BASED INCENTIVE PT 2.2

                                               2,100,000.00                         0.00                          0.00       100.00             100.00


iLap Category Sequence No: 4                                            Current Expenditure Category: IRM

                                                       0.00                         0.00                          0.00       100.00             100.00


Total                                         27,900,000.00                 9,403,155.93               14,400,000.00

OPS_DETAILEDCHANGES_DISBURSEMENT_TABLE




DISBURSEMENT ESTIMATES

Change in Disbursement Estimates
Yes

      Year                                                                                         Current                                 Proposed
      2016                                                                                      255,060.00                                521,035.00

      2017                                                                                    3,821,155.00                            17,157,370.00

      2018                                                                                    5,330,325.00                            15,046,241.00
           The World Bank
           MG-Electricity Sec Operations & Governance Improvement Project(ESOGIP) (P151785)



    2019                                                      13,792,510.00                    9,568,125.00

    2020                                                      27,025,490.00                   11,632,689.00

    2021                                                      37,350,445.00                    5,656,517.00

    2022                                                      17,425,015.00                    2,946,269.00

.
                                 The World Bank
                                 MG-Electricity Sec Operations & Governance Improvement Project(ESOGIP) (P151785)



.
                                                                                          Results framework
                                                                                      COUNTRY: Madagascar
                                                            MG-Electricity Sec Operations & Governance Improvement Project(ESOGIP)

    Project Development Objectives(s)
    The Project Development Objective is to improve the operational performance of the national electricity utility (JIRAMA) and improve the reliability of
    electricity supply in the project area and, in the event of an eligible crisis or emergency, to provide immediate and effective response to said eligible crisis
    or emergency.



    Project Development Objective Indicators by Objectives/ Outcomes
    RESULT_FRAME_TBL_PDO




                                         Indicator Name                    PBC    Baseline                                       End Target


    Reliability of electricity supply in the project area improved

    Total electricity losses per year in the project area (Percentage)           35.00                                          24.00
    Interruptions in electricity service per year in the project area
                                                                                 870.00                                         450.00
    (Number)

    Direct project beneficiaries (Number)                                        0.00                                           350,000.00

                      Female beneficiaries (Percentage)                          0.00                                           50.00

     PDO Table SPACE

    Intermediate Results Indicators by Components
    RESULT_FRAME_TBL_IO




                              Indicator Name              PBC   Baseline                                      Intermediate Targets            End Target

                                                                                            1                           2
    Improving electricity sector planning and financial sustainability
                        The World Bank
                        MG-Electricity Sec Operations & Governance Improvement Project(ESOGIP) (P151785)



RESULT_FRAME_TBL_IO




                      Indicator Name         PBC    Baseline                                               Intermediate Targets                           End Target

                                                                                      1                                    2
Completion of key studies: Least Cost
                                                                                                                                                         LCPDP and Tariff Studies completed
Power Development Plan (LCPDP), Tariff             No
                                                                                                                                                         and published
Study (Text)
Percentage of total sales (kWh) covered
by the Revenue Protection Program                  0.00                                                                                                  40.00
(RPP). (Percentage)
Competitive Bidding process for the
development of one priority small hydro            0.00                                                                                                  1.00
site launched (Number)
Strengthening operational performance and governance of JIRAMA
Percentage of technical positions held by
females that report directly to Directors          5%                                                                                                    Increased by 15%
in JIRAMA (Text)
JIRAMA customer satisfaction survey
undertaken in project area and report on                                                                                  Second Customer Satisfaction   Customer satisfaction survey
                                                   No survey                         First Customer satisfaction survey
customer feedback and how it was                                                                                          Survey                         administered by JIRAMA
addressed by JIRAMA (Text)
Installation of Management Information
                                                                                                                                                         MIS functioning and used for sector
System (MIS) at JIRAMA, and populated              No
                                                                                                                                                         monitoring and reporting
with data (Text)

JIRAMA's Management Improvement                                                                                                                          JIRAMA business plan published,
                                                   MIP adopted by Government, key
Plan (MIP) completed and key                                                                                                                             Director-level and above
                                                   management positions advertised
management positions recruited (Text)                                                                                                                    competitively recruited
Public availability of customer
                                                   No                                                                                                    Yes
satisfaction survey (Yes/No)
Investing in enhanced reliability of electricity
                              The World Bank
                              MG-Electricity Sec Operations & Governance Improvement Project(ESOGIP) (P151785)



RESULT_FRAME_TBL_IO




                          Indicator Name                   PBC    Baseline                         Intermediate Targets    End Target

                                                                                   1                         2
Dispatching Center and Distribution
Control Center constructed and                                   No                                                       Yes
commissioned (Yes/No)
Action: This indicator has been Marked
for Deletion
Transmission lines constructed or
rehabilitated under the project                                  0.00                                                     134.00
(Kilometers)
                  Transmission lines constructed under
                                                                 0.00                                                     34.00
                  the project (Kilometers)

                  Action: This indicator has been
                  Marked for Deletion
                  Transmission lines rehabilitated under
                                                                 0.00                                                     100.00
                  the project (Kilometers)
Distribution lines constructed or
rehabilitated under the project                                  0.00                                                     300.00
(Kilometers)
                  Distribution lines constructed under
                                                                 0.00                                                     165.00
                  the project (Kilometers)
                  Distribution lines rehabilitated under
                                                                 0.00                                                     135.00
                  the project (Kilometers)
Contingent Emergency Response
Time taken for first disbursement of
funds requested by Government for an                             0.00                                                     8.00
eligible emergency or crisis (Weeks)

IO Table SPACE
The World Bank
MG-Electricity Sec Operations & Governance Improvement Project(ESOGIP) (P151785)
       The World Bank
       MG-Electricity Sec Operations & Governance Improvement Project(ESOGIP) (P151785)




Note to Task Teams: End of system generated content, document is editable from here. Please delete this note when
finalizing the document