PROCUREMENT PLAN (Textual Part) Project information: P169125 Local Economic Resilience Project Project Implementation agency: National Direction of Public Works Date of the Procurement Plan: January 21, 2022 Period covered by this Procurement Plan: January 2022 – June 2023 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. PROCUREMENT El Salvador : El Salvador Local Economic Resilience Project PLAN General Information Country: El Salvador 2022-01-21 Bank’s Approval Date of the Original Procurement Plan: 2022-09-20 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P169125 GPN Date: 2022-01-21 Project Name: El Salvador Local Economic Resilience Project Loan / Credit No: IBRD / 89480 National Directorate of Municipal Works Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual DOM-BM-SDO-BIENES-01/20 22 / ADQUISICIÓN DE EQUIPO Component 3: Institutional S Solicitud de oferta Open - Internationa Single Stage - One E DE COMPUTO PARA EL FORT IBRD / 89480 trengthening and Capacity B Posterior 1,061,015.00 0.00 En ejecución 2022-08-10 2022-08-16 2022-08-15 2022-09-26 2022-10-26 2022-11-30 2023-04-29 s l nvelope ALECIMIENTO DE LA DGCG D uilding EL MINISTERIO DE HACIENDA DOM-BM-SDC-04/2022 / ADQ Component 3: Institutional S Solicitud de cotiza Single Stage - One E Ejecución pe UISICION DE SEIS (6) TABLET IBRD / 89480 trengthening and Capacity B Posterior Open - National 7,505.00 0.00 2022-08-20 2022-10-15 2023-03-14 ciones nvelope ndiente S PARA LA DGCG uilding DOM-BM-SDC-02/2022 / SUM INISTRO E INSTALACIÓN DE S Component 3: Institutional S Solicitud de cotiza Single Stage - One E Ejecución pe OFTWARE LICENCIA DE AUTO IBRD / 89480 trengthening and Capacity B Posterior Open - National 20,000.00 0.00 2022-08-14 2022-10-09 2023-01-07 ciones nvelope ndiente CAD LT 2022 PARA 3 AÑOS, I uilding NSTALADO EN OCHO (8) EQU IPOS DE LA DGCG DOM-BM-SDC-03/2022 / SUM INISTRO E INSTALACIÓN DE S Component 3: Institutional S Solicitud de cotiza Single Stage - One E Ejecución pe OFTWARE PLANTILLA PREMIU IBRD / 89480 trengthening and Capacity B Posterior Open - National 5,000.00 0.00 2022-08-15 2022-10-10 2022-10-16 ciones nvelope ndiente M PARA AULA DE CAPACITACI uilding ÓN VIRTUAL MOODLE PARA LA DGCG DOM-BM-SDC-05/2022 / ADQ Component 3: Institutional S Solicitud de cotiza Single Stage - One E Ejecución pe UISICION DE DOS (2) PROYEC IBRD / 89480 trengthening and Capacity B Posterior Open - National 3,300.00 0.00 2022-08-20 2022-10-15 2022-12-14 ciones nvelope ndiente TOR DE CAÑÓN PARA LA DG uilding CG DOM-BM-SDC-06/2022 / ADQ Component 3: Institutional S UISICION DE CINCO (5) SWIT Solicitud de cotiza Single Stage - One E Ejecución pe IBRD / 89480 trengthening and Capacity B Posterior Open - National 8,250.00 0.00 2022-08-20 2022-10-15 2022-12-14 CH DE COMUNICACIÓN ADMI ciones nvelope ndiente uilding NISTRABLE PARA LA DGCG DOM-BM-SDC-10/2022 / ADQ Component 3: Institutional S UISICION DE DOS (2) MONITO Solicitud de cotiza Single Stage - One E Ejecución pe IBRD / 89480 trengthening and Capacity B Posterior Open - National 5,500.00 0.00 2022-08-25 2022-10-20 2022-12-19 RES SMART DE 60 A 70 PULG ciones nvelope ndiente uilding ADAS PARA LA DGCG DOM-BM-SDC-11/2022 / ADQ Component 3: Institutional S USICION DE UNA MESA EJECU Solicitud de cotiza Single Stage - One E Ejecución pe IBRD / 89480 trengthening and Capacity B Posterior Open - National 1,650.00 0.00 2022-08-13 2022-10-08 2022-10-14 TIVA DE REUNIONES PARA 12 ciones nvelope ndiente uilding PERSONAS PARA LA DGCG DOM-BM-SDC-12/2022 / EQU Component 3: Institutional S Solicitud de cotiza Single Stage - One E Ejecución pe IPO DE UN EQUIPO DE VIDEO IBRD / 89480 trengthening and Capacity B Posterior Open - National 5,500.00 0.00 2022-08-20 2022-10-15 2022-12-14 ciones nvelope ndiente CONFERENCIA PARA LA DGC uilding G DOM-BM-SDC-13/2022 / ADQ Component 3: Institutional S Solicitud de cotiza Single Stage - One E Ejecución pe USICION DE UN EQUIPO WIFI IBRD / 89480 trengthening and Capacity B Posterior Open - National 1,100.00 0.00 2022-08-20 2022-10-15 2022-12-14 ciones nvelope ndiente PARA LA DGCG uilding NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual DOM-BM-SBCC-01/2022 / CO Component 5: Project mana Selección basada NSULTORIA PARA VERIFICACI IBRD / 89480 Posterior Open - National 225,000.00 0.00 En ejecución 2022-04-02 2022-05-09 2022-04-27 2022-05-18 2022-05-07 2022-07-15 2022-05-24 2022-05-30 2022-06-17 2022-07-09 2022-09-15 gement and implementation en calidad y costo ÓN DE METAS MUNICIPALES DOM-BM-SBCC-02/2022 / SE Component 3: Institutional S Selección basada Open - Internationa RVICIOS DE CONTABILIDAD P IBRD / 89480 trengthening and Capacity B Posterior 600,000.00 0.00 Cancelado 2022-06-15 2022-06-15 2022-07-06 2022-08-19 2022-09-16 2022-10-16 2022-11-20 2022-12-25 2023-06-30 en calidad y costo l ARA ACTUALIZAR CIERRES C uilding ONTABLES DOM-BM-SCC-04/2022 / CON SULTORÍA PARA CAPACITAR AL PERSONAL DE LA DGCG E N EL MANEJO DE LOS EQUIPO Component 3: Institutional S Selección basada S Y LA ELABORACIÓN DE VID Ejecución pendien IBRD / 89480 trengthening and Capacity B Posterior en calificaciones d Open - National 10,000.00 0.00 2022-09-01 2022-09-22 2022-11-05 2022-12-05 2023-01-09 2023-04-09 EOS Y MATERIAL DIDÁCTICO te uilding e consultores CON HERRAMIENTAS MULTIM EDIA PARA FORTALECER CO MPETENCIAS Y CAPACIDADES DEL PERSONAL DE LAS AREA S FINANCIERAS DE LOS GOBI ERNOS LO Page 1 DOM-BM-SCC-05/2022 / Serv icios de Consultoría para la A Component 3: Institutional S Selección basada Ejecución pendien ctualización de Información y IBRD / 89480 trengthening and Capacity B Posterior en calificaciones d Open - National 23,325.00 0.00 2022-10-03 2022-10-24 2022-12-07 2023-01-06 2023-02-10 2023-08-09 te Cierres Contables de los Mun uilding e consultores icipios del Departamento de Ahuachapán DOM-BM-SCC-06/2022 / Serv icios de Consultoría para la A Component 3: Institutional S Selección basada Ejecución pendien ctualización de Información y IBRD / 89480 trengthening and Capacity B Posterior en calificaciones d Open - National 31,600.00 0.00 2022-10-03 2022-10-24 2022-12-07 2023-01-06 2023-02-10 2023-08-09 te Cierres Contables de los Mun uilding e consultores icipios del Departamento de Santa Ana DOM-BM-SCC-07/2022 / Serv icios de Consultoría para la A Component 3: Institutional S Selección basada Ejecución pendien ctualización de Información y IBRD / 89480 trengthening and Capacity B Posterior en calificaciones d Open - National 23,700.00 0.00 2022-10-03 2022-10-24 2022-12-07 2023-01-06 2023-02-10 2023-08-09 te Cierres Contables de los Mun uilding e consultores icipios del Departamento de Sonsonate DOM-BM-SCC-08/2022 / Serv icios de Consultoría para la A Component 3: Institutional S Selección basada Ejecución pendien ctualización de Información y IBRD / 89480 trengthening and Capacity B Posterior en calificaciones d Open - National 119,620.00 0.00 2022-10-03 2022-10-24 2022-12-07 2023-01-06 2023-02-10 2023-08-09 te Cierres Contables de los Mun uilding e consultores icipios del Departamento de Chalatenango DOM-BM-SCC-09/2022 / Serv icios de Consultoría para la A Component 3: Institutional S Selección basada Ejecución pendien ctualización de Información y IBRD / 89480 trengthening and Capacity B Posterior en calificaciones d Open - National 54,920.00 0.00 2022-10-03 2022-10-24 2022-12-07 2023-01-06 2023-02-10 2023-08-09 te Cierres Contables de los Mun uilding e consultores icipios del Departamento de La Libertad DOM-BM-SCC-10/2022 / Serv icios de Consultoría para la A Component 3: Institutional S Selección basada Ejecución pendien ctualización de Información y IBRD / 89480 trengthening and Capacity B Posterior en calificaciones d Open - National 85,760.00 0.00 2022-10-03 2022-10-24 2022-12-07 2023-01-06 2023-02-10 2023-08-09 te Cierres Contables de los Mun uilding e consultores icipios del Departamento de San Salvador DOM-BM-SCC-11/2022 / Serv icios de Consultoría para la A Component 3: Institutional S Selección basada Ejecución pendien ctualización de Información y IBRD / 89480 trengthening and Capacity B Posterior en calificaciones d Open - National 22,570.00 0.00 2022-10-03 2022-10-24 2022-12-07 2023-01-06 2023-02-10 2023-08-09 te Cierres Contables de los Mun uilding e consultores icipios del Departamento de Cuscatlán DOM-BM-SCC-12/2022 / Serv icios de Consultoría para la A Component 3: Institutional S Selección basada Ejecución pendien ctualización de Información y IBRD / 89480 trengthening and Capacity B Posterior en calificaciones d Open - National 42,130.00 0.00 2022-10-03 2022-10-24 2022-12-07 2023-01-06 2023-02-10 2023-08-09 te Cierres Contables de los Mun uilding e consultores icipios del Departamento de La Paz DOM-BM-SCC-13/2022 / Serv icios de Consultoría para la A Component 3: Institutional S Selección basada Ejecución pendien ctualización de Información y IBRD / 89480 trengthening and Capacity B Posterior en calificaciones d Open - National 34,610.00 0.00 2022-10-03 2022-10-24 2022-12-07 2023-01-06 2023-02-10 2023-08-09 te Cierres Contables de los Mun uilding e consultores icipios del Departamento de Cabañas DOM-BM-SCC-14/2022 / Serv icios de Consultoría para la A Component 3: Institutional S Selección basada Ejecución pendien ctualización de Información y IBRD / 89480 trengthening and Capacity B Posterior en calificaciones d Open - National 18,060.00 0.00 2022-10-03 2022-10-24 2022-12-07 2023-01-06 2023-02-10 2023-08-09 te Cierres Contables de los Mun uilding e consultores icipios del Departamento de San Vicente DOM-BM-SCC-15/2022 / Serv icios de Consultoría para la A Component 3: Institutional S Selección basada Ejecución pendien ctualización de Información y IBRD / 89480 trengthening and Capacity B Posterior en calificaciones d Open - National 37,240.00 0.00 2022-10-03 2022-10-24 2022-12-07 2023-01-06 2023-02-10 2023-08-09 te Cierres Contables de los Mun uilding e consultores icipios del Departamento de Usulután DOM-BM-SCC-16/2022 / Serv icios de Consultoría para la A Component 3: Institutional S Selección basada Ejecución pendien ctualización de Información y IBRD / 89480 trengthening and Capacity B Posterior en calificaciones d Open - National 16,930.00 0.00 2022-10-03 2022-10-24 2022-12-07 2023-01-06 2023-02-10 2023-08-09 te Cierres Contables de los Mun uilding e consultores icipios del Departamento de San Miguel DOM-BM-SCC-17/2022 / Serv icios de Consultoría para la A Component 3: Institutional S Selección basada Ejecución pendien ctualización de Información y IBRD / 89480 trengthening and Capacity B Posterior en calificaciones d Open - National 53,795.00 0.00 2022-10-03 2022-10-24 2022-12-07 2023-01-06 2023-02-10 2023-08-09 te Cierres Contables de los Mun uilding e consultores icipios del Departamento de Morazán DOM-BM-SCC-18/2022 / Serv icios de Consultoría para la A Component 3: Institutional S Selección basada Ejecución pendien ctualización de Información y IBRD / 89480 trengthening and Capacity B Posterior en calificaciones d Open - National 35,740.00 0.00 2022-10-03 2022-10-24 2022-12-07 2023-01-06 2023-02-10 2023-08-09 te Cierres Contables de los Mun uilding e consultores icipios del Departamento de La Unión DOM-BM-SCC-19/2022 / Dise Selección basada ño e implementación de plat Component 5: Project mana Ejecución pendien IBRD / 89480 Posterior en calificaciones d Open - National 250,000.00 0.00 2023-02-01 2023-02-22 2023-04-07 2023-05-07 2023-06-11 2023-12-22 aforma digital de transparen gement and implementation te e consultores cia y participación ciudadana DOM-BM-SCC-20/2033 / Eval Selección basada uación y monitoreo de imple Component 5: Project mana Ejecución pendien IBRD / 89480 Posterior en calificaciones d Open - National 30,000.00 0.00 2024-03-01 2024-03-22 2024-05-05 2024-06-04 2024-07-09 2024-10-07 mentación de plataforma digi gement and implementation te e consultores tal de transparencia y partici pación ciudadana DOM-BM-SCC-22/2033 / Elab oración de Carpetas Técnicas de Tipología Centros de com Component 3: Institutional S Selección basada Ejecución pendien ercialización locales municip IBRD / 89480 trengthening and Capacity B Posterior en calificaciones d Open - National 97,775.00 0.00 2022-09-28 2022-10-19 2022-12-02 2023-01-01 2023-02-05 2023-05-06 te ales y mercados de producto uilding e consultores res, centros comerciales, cen tros de alimentación (Compo nente 1) DOM-BM-SCC-23/2033 / Elab oración de Carpetas Técnicas Component 3: Institutional S Selección basada de Tipología Infraestructura p Ejecución pendien IBRD / 89480 trengthening and Capacity B Posterior en calificaciones d Open - National 108,905.00 0.00 2022-09-28 2022-10-19 2022-12-02 2023-01-01 2023-02-05 2023-05-06 ara la prestación de servicios te uilding e consultores turísticos municipales y para la promoción del desarrollo a rtesanal. (Componente1) DOM-BM-SCC-24/2033 / Elab oración de Carpetas Técnicas Component 3: Institutional S Selección basada Ejecución pendien de Tipología Infraestructura v IBRD / 89480 trengthening and Capacity B Posterior en calificaciones d Open - National 111,750.00 0.00 2022-09-28 2022-10-19 2022-12-02 2023-01-01 2023-02-05 2023-05-06 te ial, puentes vehiculares y pe uilding e consultores atonales. (Componente1) Page 2 DOM-BM-SCC-25/2022 / Elab Component 3: Institutional S Selección basada oración de Carpetas Técnicas Ejecución pendien IBRD / 89480 trengthening and Capacity B Posterior en calificaciones d Open - National 49,800.00 0.00 2022-09-28 2022-10-19 2022-12-02 2023-01-01 2023-02-05 2023-05-06 de Tipología Obras de protec te uilding e consultores ción y mitigación de riesgos y otras tipologías. DOM-BM-SCC-26/2022 / Elab Component 3: Institutional S Selección basada Ejecución pendien oración de Carpetas Técnicas IBRD / 89480 trengthening and Capacity B Posterior en calificaciones d Open - National 36,225.00 0.00 2022-09-28 2022-10-19 2022-12-02 2023-01-01 2023-02-05 2023-05-06 te de Tipología Redes de electri uilding e consultores ficación. DOM-BM-SCC-27/2022 / ELA Component 3: Institutional S Selección basada BORACION DE CARPETAS TE Ejecución pendien IBRD / 89480 trengthening and Capacity B Posterior en calificaciones d Open - National 50,325.00 0.00 2022-09-28 2022-10-19 2022-12-02 2023-01-01 2023-01-31 2023-01-31 CNICAS DE TIPOLOGIA SISTE te uilding e consultores MAS DE AGUA Y SANEAMIENT O COMPONENTE 1 DOM-BM-SCC-42/2022 / Elab Component 2: Competitive f Selección basada Ejecución pendien oración de Carpeta Técnica p IBRD / 89480 und for high-impact investm Posterior en calificaciones d Open - National 150,000.00 0.00 2023-01-31 2023-02-21 2023-04-06 2023-05-06 2023-06-10 2023-09-18 te ara Subproyecto Calle Comp ents on regional economic d e consultores onente 2. evelopment INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CI-02 / Coordinador del Proy Component 5: Project mana IBRD / 89480 Posterior Individual Open 144,000.00 48,000.00 Firmado 2022-02-01 2022-01-27 2022-02-21 2022-03-15 2022-02-23 2022-03-15 2022-02-28 2022-03-22 2024-12-31 ecto UEP gement and implementation CI-03 / Coordinador Especiali Component 5: Project mana IBRD / 89480 Previa Individual Open 115,200.00 38,400.00 Firmado 2022-02-01 2022-01-24 2022-02-21 2022-03-17 2022-02-23 2022-03-24 2022-02-28 2022-04-01 2024-12-31 sta de Adquisiciones gement and implementation CI-22 / Especialista en Monit Component 5: Project mana IBRD / 89480 Posterior Individual Open 79,200.00 26,400.00 Firmado 2022-02-01 2022-01-25 2022-02-21 2022-03-16 2022-02-23 2022-03-18 2022-02-28 2022-04-01 2024-12-31 oreo y Evaluación gement and implementation CI-19 / Especialista Ambient Component 5: Project mana IBRD / 89480 Posterior Individual Open 79,200.00 26,400.00 Firmado 2022-02-01 2022-01-23 2022-02-21 2022-03-16 2022-02-23 2022-03-18 2022-02-28 2022-03-22 2024-12-31 al y Riesgo de Desastres gement and implementation CI-04 / Especialista en Adqui Component 5: Project mana IBRD / 89480 Previa Individual Open 79,200.00 26,400.00 Firmado 2022-02-01 2022-01-24 2022-02-21 2022-03-18 2022-02-23 2022-03-24 2022-02-28 2022-04-01 2024-12-31 siciones 1 gement and implementation CI-26 / ESPECIALISTA EN ING Component 5: Project mana IBRD / 89480 Posterior Individual Open 79,200.00 26,400.00 Firmado 2022-02-01 2022-01-25 2022-02-21 2022-03-16 2022-02-23 2022-03-21 2022-02-28 2022-03-25 2024-12-31 ENIERIA CIVIL gement and implementation CI-13 / ASISTENTE ADMINIST Component 5: Project mana IBRD / 89480 Posterior Individual Open 54,000.00 18,000.00 Firmado 2022-02-01 2022-01-25 2022-02-21 2022-03-04 2022-02-23 2022-03-14 2022-02-28 2022-03-22 2024-12-31 RATIVA gement and implementation Component 5: Project mana CI-41 / ANALISTA DE DATOS IBRD / 89480 Posterior Individual Open 79,200.00 26,400.00 Firmado 2022-02-01 2022-01-25 2022-02-21 2022-05-20 2022-02-23 2022-05-23 2022-02-28 2022-06-01 2024-12-31 gement and implementation DOM-BM-CI-15/2022 / ESPEC Component 5: Project mana IBRD / 89480 Posterior Individual Open 79,200.00 0.00 En ejecución 2022-05-31 2022-05-23 2022-06-27 2022-08-09 2022-06-29 2022-08-09 2022-07-14 2024-12-31 IALISTA EN GESTION FINANC gement and implementation IERA UEP DOM-BM-CI-12/2022 / ASIST Component 5: Project mana IBRD / 89480 Previa Individual Open 8,500.00 0.00 Cancelado 2022-05-16 2022-06-01 2022-07-04 2022-07-25 2022-08-29 2024-12-31 ENTE DE ADQUISICIONES UE gement and implementation P-BM DOM-BM-CI-45/2022 / ESPEC Component 5: Project mana IBRD / 89480 Previa Individual Open 26,400.00 0.00 En ejecución 2022-05-16 2022-05-24 2022-07-04 2022-09-07 2022-07-25 2022-09-15 2022-08-29 2024-12-31 IALISTA EN ADQUISICIONES II gement and implementation CI-18 / Especialista Gestión Component 5: Project mana IBRD / 89480 Posterior Individual Open 79,200.00 0.00 Cancelado 2022-02-01 2022-01-23 2022-02-21 2022-02-23 2022-02-28 2024-12-31 Social 1 gement and implementation CI-14 / Especialista Financier Component 5: Project mana IBRD / 89480 Posterior Individual Open 79,200.00 0.00 Cancelado 2022-02-01 2022-01-25 2022-02-21 2022-02-23 2022-03-17 2024-12-31 o gement and implementation CI-05 / Especialista en Adqui Component 5: Project mana IBRD / 89480 Posterior Individual Open 79,200.00 0.00 Cancelado 2022-02-01 2022-01-24 2022-02-21 2022-03-18 2022-02-23 2022-03-24 2022-02-28 2024-12-31 siciones 2 gement and implementation DOM-BM-CI-09/2022 / CONS Component 5: Project mana ULTORIA INDIVIDUAL PARA A IBRD / 89480 Previa Individual Open 54,000.00 0.00 En ejecución 2022-06-15 2022-06-16 2022-08-03 2022-08-24 2022-09-28 2024-12-31 gement and implementation SISTENTE DE ADQUISICIONES DOM-BM-CI-44/2022 / ESPEC Component 5: Project mana Ejecución pendien IBRD / 89480 Posterior Individual Open - National 38,400.00 0.00 2022-08-08 2022-09-26 2022-10-17 2022-11-21 2023-11-21 IALISTA EN COMUNICACIONE gement and implementation te S DOM-BM-CI-27/2022 / ESPEC Component 5: Project mana Ejecución pendien IBRD / 89480 Posterior Individual Open - National 26,400.00 0.00 2022-08-08 2022-09-26 2022-10-17 2022-11-21 2023-11-21 IALISTA EN INGENIERÍA CIVIL gement and implementation te 2 DOM-BM-CI-37/2022 / TÉCNI Component 5: Project mana IBRD / 89480 Posterior Individual Open - National 20,400.00 0.00 En ejecución 2022-08-08 2022-09-26 2022-10-17 2022-11-21 2023-11-21 CO EN GESTION SOCIAL 1 gement and implementation DOM-BM-CI-38/2022 / TÉCNI Component 5: Project mana Ejecución pendien IBRD / 89480 Posterior Individual Open - National 20,400.00 0.00 2022-08-08 2022-09-26 2022-10-17 2022-11-21 2023-11-21 CO EN GESTION SOCIAL 2 gement and implementation te DOM-BM-CI-35/2022 / TÉCNI Component 5: Project mana IBRD / 89480 Posterior Individual Open - National 20,400.00 0.00 En ejecución 2022-08-08 2022-09-19 2022-09-26 2022-10-17 2022-11-21 2023-11-21 CO EN GESTION AMBIENTAL gement and implementation 1 DOM-BM-CI-36/2022 / TÉCNI Component 5: Project mana IBRD / 89480 Posterior Individual Open - National 20,400.00 0.00 En ejecución 2022-08-08 2022-09-19 2022-09-26 2022-10-17 2022-11-21 2023-11-21 CO EN GESTION AMBIENTAL gement and implementation 2 DOM-BM-CI-07/2022 / TECNI Component 5: Project mana IBRD / 89480 Posterior Individual Open 61,200.00 0.00 Cancelado 2022-05-31 2022-05-23 2022-07-19 2022-08-13 2022-08-09 2022-09-13 2024-12-31 CO CONTABLE UEP gement and implementation DOM-BM-CI-08/2022 / TECNI Component 5: Project mana IBRD / 89480 Posterior Individual Open 61,200.00 0.00 Cancelado 2022-04-25 2022-05-23 2022-05-27 2022-08-12 2022-05-31 2022-06-13 2024-12-31 CO DE TESORERIA UEP gement and implementation DOM-BM-CI-01/2022 / Especi Component 5: Project mana IBRD / 89480 Posterior Individual Open 79,200.00 0.00 Cancelado 2022-04-25 2022-05-13 2022-05-27 2022-08-23 2022-05-31 2022-06-13 2024-12-31 alista Legal 1 gement and implementation DOM-BM-CI-46/2022 / Especi Component 5: Project mana Ejecución pendien IBRD / 89480 Posterior Individual Open - National 79,200.00 0.00 2022-10-03 2022-11-21 2022-12-12 2023-01-16 2024-12-31 alista Legal 1 gement and implementation te DOM-BM-CI-47/2022 / Técnic Component 5: Project mana Ejecución pendien IBRD / 89480 Posterior Individual Open - National 64,800.00 0.00 2022-10-03 2022-11-21 2022-12-12 2023-01-16 2024-12-31 o Contable para la UEP gement and implementation te Page 3 DOM-BM-CI-48/2022 / Técnic Component 5: Project mana Ejecución pendien IBRD / 89480 Posterior Individual Open - National 64,800.00 0.00 2022-10-31 2022-12-19 2023-01-09 2023-02-13 2024-12-31 o de Tesorería UEP gement and implementation te DOM-BM-CI-49/2022 / Técnic Component 5: Project mana Ejecución pendien IBRD / 89480 Posterior Individual Open - National 64,800.00 0.00 2022-10-03 2022-11-21 2022-12-12 2023-01-16 2025-02-01 o de Presupuesto UEP gement and implementation te DOM-BM-CI-50/2022 / Especi Component 5: Project mana Ejecución pendien IBRD / 89480 Posterior Individual Open - National 79,200.00 0.00 2022-10-03 2022-11-21 2022-12-12 2023-01-16 2024-12-31 alista en Desarrollo Económic gement and implementation te o Local DOM-BM-CI-51/2022 / Especi Component 5: Project mana Ejecución pendien IBRD / 89480 Posterior Individual Open - National 79,200.00 0.00 2022-10-03 2022-11-21 2022-12-12 2023-01-16 2024-12-31 alista en Ingeniería Civil 1 gement and implementation te DOM-BM-CI-52/2022 / Especi Component 5: Project mana Ejecución pendien IBRD / 89480 Posterior Individual Open - National 79,200.00 0.00 2022-10-03 2022-11-21 2022-12-12 2023-01-16 2024-12-31 alista en Ingeniería Civil 3 gement and implementation te DOM-BM-CI-53/2022 / Especi Component 5: Project mana Ejecución pendien alista en Ingeniería Civil 4 (Es IBRD / 89480 Posterior Individual Open - National 79,200.00 0.00 2022-10-03 2022-11-21 2022-12-12 2023-01-16 2024-12-31 gement and implementation te pecialidad Estructuras) DOM-BM-CI-54/2022 / Especi Component 5: Project mana Ejecución pendien alista en Ingeniería Civil 5 (Es IBRD / 89480 Posterior Individual Open - National 79,200.00 0.00 2022-10-03 2022-11-21 2022-12-12 2023-01-16 2024-12-31 gement and implementation te pecialidad Hidrología) DOM-BM-CI-55/2025 / Especi Component 5: Project mana Ejecución pendien IBRD / 89480 Posterior Individual Open - National 79,200.00 0.00 2022-10-03 2022-11-21 2022-12-12 2023-01-16 2024-12-31 alista en Ingeniería Eléctrica gement and implementation te 1 DOM-BM-CI-56/2024 / Técnic Component 5: Project mana Ejecución pendien IBRD / 89480 Posterior Individual Open - National 61,200.00 0.00 2022-10-03 2022-11-21 2022-12-12 2023-01-16 2024-12-31 o en Gestión Ambiental 3 gement and implementation te DOM-BM-CI-57/2025 / Técnic Component 5: Project mana Ejecución pendien IBRD / 89480 Posterior Individual Open - National 61,200.00 0.00 2022-10-03 2022-11-21 2022-12-12 2023-01-16 2024-12-31 o en Gestión Ambiental 4 gement and implementation te DOM-BM-CI-58/2024 / Técnic Component 5: Project mana Ejecución pendien IBRD / 89480 Posterior Individual Open - National 61,200.00 0.00 2022-10-03 2022-11-21 2022-12-12 2023-01-16 2024-12-31 o en Gestión Social 3 gement and implementation te DOM-BM-CI-59/2025 / Técnic Component 5: Project mana Ejecución pendien IBRD / 89480 Posterior Individual Open - National 61,200.00 0.00 2022-10-03 2022-11-21 2022-12-12 2023-01-16 2024-12-31 o en Gestión Social 4 gement and implementation te Page 4