PROCUREMENT PLAN (Textual Part) Project information: Kiribati South Tarawa Sanitation Project (STSP) – P176478 Project Implementation Agency: Ministry of Infrastructure and Sustainable Energy (MISE) Date of the Procurement Plan: March 15, 2022 Period covered by this Procurement Plan: June 2022 to December 2023 (18 months) Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (Fourth Edition, November 2020) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in 2002 Kiribati Procurement Act, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. a. open advertising of the procurement opportunity at the national level; b. the procurement is open to eligible firms from any country; c. the request for bids/request for proposals document shall require that Bidders/Proposers submitting Bids/Proposals present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights; d. contracts with an appropriate allocation of responsibilities, risks, and liabilities; e. publication of contract award information; f. rights for the Bank to review procurement documentation and activities; g. an effective complaints mechanism; and h. maintenance of records of the Procurement Process. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: “Not Applicable” Procurement of Secondhand Goods as specified under paragraph 5.11 of the Procurement Regulations – “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: is not applicable for those contracts identified in the Procurement Plan tables Works: is not applicable for those contracts identified in the Procurement Plan tables Other Relevant Procurement Information. - Procurement Implementation Guidance (version as of April 2018): Making Procurement Work for Fragile and Small States in the Pacific under World Bank Investment Project Financing following the Procurement Regulations for IPF Borrowers [July 2016, revised in November 2017]. Procurement Plan Fiduciary_Procurement Risk: Substantial. Procurement WB Review Category Threshold CW $2,000,000.00 GO $500,000.00 NC $500,000.00 CS except INDV $500,000.00 CS INDV Only $300,000.00 Packag Project Procuremen Estimated WB review Expected e No. comp. Description Scope t Method Cost US$mil starting date Procurement Category: Works KS1 1 In BBB areas - Sewer service connections RFB 2.23 (1831), salt-water connections (3030), salt- Sewer and Salt-water water drains, sewer connections to schools connections and and health-centers, equipment Equipment - septage collection and transport equipment, sewer and salt-water O&M equipment for PUB 2 Construction of onsite Onsite systems in BBB areas and the RFB 5.15 KS2 sanitation systems villages, including communal toilets Total Works 7.38 Consultant Service 2 Management services Management services of PUB sewerage and QCBS 1.84 KS3 contract salt-water assets 2 Performance based contract for O&M of CQS 0.085 Community toilets community toilets between local council KS4 operations (owner) and service provider (community based organization or other third party) 2 Develop monitoring and evaluation CQS 0.459 procedures for sanitation performance and environmental health, including establishing KS5 M&E development required platforms/databases, documenting roles of PUB, MISE, MELAD, procurement of equipment and training for ongoing monitoring 2 Sector technical training and capacity CQS 0.240 building for construction, operation and Training and Capacity maintenance of sewered and on-site KS5 Building sanitation systems, including procurement of minor goods and tools to carry out maintenance activities of communal toilets 2 Review (i) institutional arrangements in CQS 0.200 sector, (ii) sector capacity, (iii) partnerships with local, national and international partners, (iv) identify recommendations for Institutional KS7 improved coordination, key capacity Assessments building needs, (v) coordinate study tours in response to capacity building needs, and (vi) identify and operationalize post- implementation support mechanisms. 2 Review (i) long-term financing options for CQS 0.030 capital and operational costs, (ii) tariff Financing Framework KS8 structure, and provide recommendations for review long-term sustainable financing/tariff options 2 Assess risks and impacts of sanitation CQS 0.090 Commented [MDC1]: Can KS7, KS8 and KS9 services, including climate impacts, be as one contract? Consultant firm contract and environmental impacts of current practices selection process to be CQS. Risk assessment and KS9 and develop recommendations for further Mitigation mitigation, needs and options for treatment and citywide inclusive sanitation options for unsewered 3B areas. 3 WASH and Community QCBS 1.4 WASH awareness raising, community KS10 Development mobilization activities 4 Implementation Project Implementation Assistance to CQS 0.766 KS11 Assistance support the PMU KS12 4 PMU Individual staffing of the PMU 2.43 Commented [MDC2]: I understand that the budget line intended for hiring individual 4 Ongoing community feedback survey-start, CQS 0.055 consultants to be stationed at the PMU to KS13 Community Feedback mid, end support MISE. Please list/detail out the consultant positions and its estimated service Total Consultant Service 5.165 cost. PROCUREMENT Kiribati : South Tarawa Sanitation Project PLAN General Information Country: Kiribati 2021-10-27 Bank’s Approval Date of the Original Procurement Plan: 2024-04-30 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P176478 GPN Date: Project Name: South Tarawa Sanitation Project Loan / Credit No: IDA / E0240 Ministry of Infrastructure and Sustainable Energy Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned National Procure KI-MISE-383492-CW-RFQ / K 1. Investments for improved ment Document - Request for Quota Single Stage - One E 2024-11-2 S2-1: Construction of Individu IDA / E0240 sanitation access and liquid Post Open - National 1 Envelope proce 1,000,000.00 0.00 Canceled 2024-03-30 2024-05-25 tions nvelope 1 al and Community Toilets in waste management ss (Non Bank-SPD Nanikaai ) GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual KI-MISE-383490-GO-RFQ / Pr Request for Quota Single Stage - One E IDA / E0240 4. Project Management Post Limited 45,000.00 0.00 Canceled 2023-10-06 2023-10-17 2023-12-01 2024-05-29 oject Vehicle tions nvelope KI-MISE-396653-GO-RFQ / Pr Request for Quota Single Stage - One E IDA / E0240 4. Project Management Post Limited 45,000.00 0.00 Signed 2023-12-18 2023-12-15 2024-02-12 2024-01-24 2024-08-10 oject Vehicle tions nvelope NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual KI-MISE-394349-NC-DIR / Ho usehold survey to identify th 3. Community engagement IDA / E0240 Post Direct Selection Direct - National 15,000.00 0.00 Signed 2023-12-04 2023-12-08 2023-12-09 2023-12-08 2024-01-13 2023-12-12 2024-07-11 e Habitation wise demand for and support on site sanitation in South Ta rawa CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual KI-MISE-383496-CS-QCBS / K 2. Operation and Maintenan Quality And Cost- Open - Internationa Under Implement S11 - Project Implementation IDA / E0240 ce, institutional strengthenin Prior 1,000,000.00 0.00 2023-10-15 2023-11-10 2023-11-05 2023-11-21 2023-12-19 2024-02-28 2024-01-16 2024-02-15 2024-03-21 2024-04-25 2025-04-25 Based Selection l ation Assistance Consultant (PIAC) g and sector improvement KI-MISE-383497-CS-QCBS / K 3. Community engagement Quality And Cost- Open - Internationa Under Implement S10 - NGO for Behaviour Cha IDA / E0240 Prior 1,700,000.00 0.00 2023-11-01 2023-11-12 2023-11-22 2023-11-16 2024-01-05 2024-02-15 2024-02-02 2024-03-03 2024-04-07 2024-05-12 2025-05-12 and support Based Selection l ation nge Campaign (BCC) INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 1. Investments for improved KI-MISE-259203-CS-CDS / Pr IDA / E0240 sanitation access and liquid Post Direct Selection Direct 500,000.00 500,000.00 Signed 2021-11-01 2021-10-27 2021-11-13 2021-11-16 2021-11-25 2021-12-29 2022-05-24 oject Management Unit waste management KI-MISE-311215-CS-INDV / S Individual Consult outh Tarawa Sanitation Proje IDA / E0240 4. Project Management Prior Open - National 384,000.00 0.00 Signed 2022-11-30 2022-12-05 2023-01-18 2023-06-07 2023-02-08 2023-06-27 2023-03-15 2023-07-08 2025-03-04 ant Selection ct - Deputy Project Manager DPM (full time) KI-MISE-311216-CS-INDV / S Individual Consult Open - Internationa outh Tarawa Sanitation Proje IDA / E0240 4. Project Management Prior 598,000.00 0.00 Signed 2022-12-17 2022-12-18 2023-02-04 2023-05-28 2023-02-25 2023-06-26 2023-04-01 2023-07-05 2025-03-21 ant Selection l ct - Project Manager KI-MISE-312504-CS-INDV / S Individual Consult IDA / E0240 4. Project Management Post Open - National 252,000.00 0.00 Signed 2022-11-30 2023-04-03 2023-01-18 2023-09-07 2023-02-08 2023-09-07 2023-03-15 2023-09-20 2025-03-04 ocial Safeguards Specialist (f ant Selection ull time) KI-MISE-312505-CS-INDV / C 3. Community engagement Individual Consult ommunity Engagement Speci IDA / E0240 Post Open - National 252,000.00 0.00 Signed 2023-01-15 2023-04-03 2023-03-05 2023-10-02 2023-03-26 2023-10-09 2023-04-30 2023-11-09 2023-05-07 and support ant Selection alist (full time) KI-MISE-312506-CS-INDV / Pr Individual Consult IDA / E0240 4. Project Management Post Open - National 280,000.00 0.00 Signed 2023-01-15 2023-04-03 2023-03-05 2023-10-24 2023-03-26 2023-10-26 2023-04-30 2023-11-08 2025-04-19 oject Accountant (full time) ant Selection KI-MISE-312508-CS-INDV / E Individual Consult IDA / E0240 4. Project Management Prior Open - National 312,000.00 0.00 Terminated 2023-02-15 2023-02-16 2023-04-05 2024-01-19 2023-04-26 2024-02-01 2023-05-31 2024-02-05 2023-11-27 ngineer (full time) ant Selection KI-MISE-312509-CS-INDV / M Individual Consult IDA / E0240 4. Project Management Post Open - National 264,000.00 0.00 Canceled 2023-06-01 2023-06-21 2023-07-20 2023-08-10 2023-09-14 2025-09-03 &E Specialist (full time) ant Selection KI-MISE-312510-CS-INDV / O Individual Consult IDA / E0240 4. Project Management Post Open - National 93,600.00 0.00 Canceled 2023-06-01 2023-06-21 2023-07-20 2023-08-10 2023-09-14 2025-09-03 ffice Assistant (full time) ant Selection KI-MISE-365250-CS-INDV / Pr Individual Consult IDA / E0240 4. Project Management Post Open - National 100,000.00 0.00 Canceled 2023-06-11 2023-07-30 2023-08-20 2023-09-24 2024-03-22 ocurement Officer ant Selection KI-MISE-311217-CS-INDV / S Individual Consult afeguards Manager, Environ IDA / E0240 4. Project Management Post Open - National 288,000.00 0.00 Canceled 2023-01-15 2023-04-03 2023-03-05 2023-03-26 2023-04-30 2025-04-19 ant Selection mental Specialist (full time) Page 1 KI-MISE-383498-CS-INDV / E Individual Consult Under Implement IDA / E0240 4. Project Management Post Open - National 288,000.00 0.00 2023-11-01 2023-11-12 2023-12-20 2024-01-10 2024-02-14 2024-08-12 nvironmental Management S ant Selection ation pecialist KI-MISE-412922-CS-INDV / E Individual Consult Open - Internationa Pending Impleme IDA / E0240 4. Project Management Prior 430,000.00 0.00 2024-03-08 2024-04-26 2024-05-17 2024-06-21 2024-12-18 ngineer (Full Time) ant Selection l ntation KI-MISE-424962-CS-INDV / Di Individual Consult Open - Internationa Pending Impleme rector for Water and Sanitati IDA / E0240 4. Project Management Prior 400,000.00 0.00 2024-04-30 2024-06-18 2024-07-09 2024-08-13 2025-02-09 ant Selection l ntation on Engineering Department Page 2