PROCUREMENT PLAN (Textual Part) Project information: Tunisia - Tunisia-Italy Interconnector TA - P164625 Project Implementation agency: STEG and Elmed Etudes Date of the Procurement Plan: November 6, 2019 Period covered by this Procurement Plan: November 6, 2019 to April 5, 2021 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in Public procurement decree (Décret n° 2014- 1039 du 13 mars 2014, portant réglementation des marchés publics, amendee par le decret No. 2018-416 du 11 Mai 2018)), such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. “Not Applicable” Procurement of Second-Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables: Not Applicable. Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: is not applicable; Works: is not applicable Other Relevant Procurement Information. Not applicable. PROCUREMENT Tunisia : Tunisia-Italy Power Interconnector - Project Preparation TA PLAN General Information Country: Tunisia 2019-11-19 Bank’s Approval Date of the Original Procurement Plan: 2024-04-29 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P164625 GPN Date: 2019-11-25 Project Name: Tunisia-Italy Power Interconnector - Project Preparation TA Loan / Credit No: TF / A6789 ELMED Etudes Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IT-ELMED-136448-NC-RFP / T Sélection fondée s Open - Internationa errestrial Feasibilty Studies f TF / A6789 Preparation Studies A posteriori ur la qualité et le 625,000.00 0.00 Annulé 2019-11-28 2020-06-12 2019-12-19 2020-02-13 2020-03-26 2020-04-25 2020-05-30 2020-07-04 2021-07-04 l or Italy-Tunisia Interconnecto coût r IT-ELMED-136454-CS-QCBS / Sélection fondée s Open - Internationa Enviromental & Social Study TF / A6789 Preparation Studies A posteriori ur la qualité et le 500,000.00 545,745.45 Signé 2019-11-28 2020-07-08 2019-12-19 2020-07-22 2020-02-13 2020-10-16 2020-03-26 2020-12-23 2020-04-25 2021-02-08 2020-05-30 2021-06-10 2020-07-04 2021-07-03 2021-12-31 l and resettlement plan coût IT-ELMED-136444-NC-RFP / Sélection fondée s Open - Internationa Marine Feasibility Studies for TF / A6789 Preparation Studies A priori ur la qualité et le 8,625,000.00 8,210,211.23 Signé 2019-11-13 2020-01-07 2019-12-04 2020-01-13 2020-01-29 2020-07-30 2020-03-11 2020-09-17 2020-04-10 2020-11-11 2020-05-15 2021-05-06 2020-06-19 2021-04-20 2021-12-18 l Italy-tunisia Interconnector coût IT-ELMED-183280-CS-QCBS / Sélection fondée s Open - Internationa Terrestrial Feasibilty Studies TF / A6789 Preparation Studies A priori ur la qualité et le 1,600,000.00 846,797.60 Signé 2020-07-09 2020-07-17 2020-07-24 2020-08-19 2020-10-20 2021-03-19 2020-11-23 2021-05-07 2020-12-22 2021-06-21 2021-02-08 2021-08-18 2021-03-12 2021-09-11 2022-01-03 l for Italy-Tunisia Interconnect coût or IT-ELMED-200978-CS-QCBS / Sélection fondée s Open - Internationa Transaction Advisory for Tuni TF / A6789 Transaction Advisory A priori ur la qualité et le 1,909,000.00 0.00 Annulé 2020-11-13 2020-12-04 2021-01-24 2021-02-28 2021-03-30 2021-05-04 2021-06-08 2021-12-15 l sia-Italy Interconnector coût IT-ELMED-136452-CS-QCBS / Sélection fondée s Open - Internationa Financial Model for Italy-Tuni TF / A6789 Preparation Studies A posteriori ur la qualité et le 138,000.00 0.00 Annulé 2020-09-16 2020-10-07 2020-11-13 2020-12-18 2021-01-17 2021-02-21 2021-03-28 2021-12-31 l sia Interconnector coût IT-ELMED-252946-CS-CQS / Sélection fondée s Project Management Service External Financial Auditing S TF / A6789 A posteriori ur les qualification Open - National 32,500.00 29,283.31 Signé 2021-11-08 2022-01-10 2021-11-29 2022-01-12 2022-03-16 2022-02-11 2022-05-10 2022-03-18 2022-05-14 2022-09-14 s ervice s des consultants INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Sélection de cons IT-ELMED-282515-CS-CDS / Project Management Service En cours d'exécut TF / A6789 A posteriori ultants par entent Direct 7,000.00 0.00 2022-03-09 2022-05-19 2022-03-19 2022-05-23 2022-12-31 Accounting & Fiscal Services s ion e directe IT-ELMED-389028-CS-CDS / Sélection de cons Étude environnementale et s Project Management Service En attente d'exéc TF / A6789 A posteriori ultants par entent Direct - National 145,200.00 0.00 2024-04-26 2024-04-26 2024-05-10 2024-10-21 ociale et plan d'action de réi s ution e directe nstallation du poste THT/HT d e Grombalia2 IT-ELMED-389024-CS-CDS / Sélection de cons Appui technique pour l'évalu Project Management Service Direct - Internation En attente d'exéc TF / A6789 A posteriori ultants par entent 250,000.00 0.00 2024-04-30 2024-05-06 2024-05-27 2024-12-23 ation des offres relatives au s al ution e directe Projet d’Interconnexion électr ique Tunisie-Italie Page 1