PROCUREMENT PLAN (Textual Part) Project information: Mozambique FOOD SYSTEMS RESILIENCE PROGRAM FOR EASTERN AND SOUTHERN AFRICA (FSRP), P177816 Project Implementation agency: Ministry of Agriculture and Rural Development Date of the Procurement Plan: 17 March, 2023 Period covered by this Procurement Plan: 12 (twelve) months for PPA only Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in “Regulamento de Contratação de Empreitada de Obras Públicas, Fornecimento de Bens e Prestação de Serviços ao Estado” of the Republic of Mozambique of March 8, 2016 (“the Regulation”), as per Decree No. 5/2016), such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. All requirements under 5.4 from a) to h) of the Procurement Regulations. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: Is not applicable. Works: Is not applicable. Other Relevant Procurement Information. Not applicable PROCUREMENT Eastern and Southern Africa : Food Systems Resilience Program for Eastern and Southern Africa (Phase 3) FSRP PLAN General Information Country: Eastern and Southern Africa 2023-08-07 Bank’s Approval Date of the Original Procurement Plan: 2024-04-29 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P177816 GPN Date: 2023-08-15 Project Name: Food Systems Resilience Program for Eastern and Southern Africa (Phase 3) FSRP Loan / Credit No: IDA / E1850 Ministry of Agriculture and Irrigation Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SO-MOAI-375957-GO-RFB / P Single Stage - One E rocurement for Vehicles MoAI IDA / E1850 C6 Project Management Prior Request for Bids Open - National 500,000.00 0.00 Signed 2023-08-16 2023-08-24 2023-08-21 2023-08-24 2023-10-02 2023-09-23 2023-11-01 2023-11-03 2023-12-06 2023-11-06 2024-06-03 nvelope and MoLFR FGS SO-MOAI-375958-GO-RFB / P rocurement of Office Equipm Single Stage - One E IDA / E1850 C6 Project Management Prior Request for Bids Open - National 200,000.00 0.00 Signed 2023-08-16 2023-08-24 2023-08-21 2023-08-28 2023-10-02 2023-09-28 2023-11-01 2024-01-28 2023-12-06 2024-01-30 2024-06-03 ent for NPCU, MoAI, and MoL nvelope FR FGS for the FSRP Project SO-MOAI-376118-GO-RFB / P rocurement of Office Furnitur Single Stage - One E IDA / E1850 C6 Project Management Prior Request for Bids Open - National 200,000.00 0.00 Signed 2023-08-16 2023-08-24 2023-08-21 2023-08-24 2023-10-02 2023-09-23 2023-11-01 2023-11-07 2023-12-06 2023-11-10 2024-06-03 e for NPCU, MoAI, and MoLFR nvelope FGS for the FSRP Project C2 Supporting the Sustainab SO-MOAI-415683-GO-RFB / P le Development of Natural R Single Stage - One E Under Imple rocurement for MoLFR FGS L IDA / E1850 Prior Request for Bids Open - National 300,000.00 0.00 2024-03-21 2024-04-20 2024-04-21 2024-04-26 2024-05-31 2024-11-27 esources for Resilient Agricu nvelope mentation aboratory Equipments ltural Landscapes SO-MOAI-418421-GO-RFB / P C5 Contingency Emergency rocurement of hand farm tool Single Stage - One E Under Imple IDA / E1850 Response Component (CERC Prior Request for Bids Open - National 400,000.00 0.00 2024-03-30 2024-04-13 2024-04-18 2024-04-25 2024-05-05 2024-09-02 s for irrigation for HirShabelle nvelope mentation ) State of Somalia SO-MOAI-418422-GO-RFB / P C5 Contingency Emergency Single Stage - One E Under Imple rocurement of hand farm tool IDA / E1850 Response Component (CERC Prior Request for Bids Open - National 400,000.00 0.00 2024-03-30 2024-04-13 2024-04-18 2024-04-23 2024-05-03 2024-08-31 nvelope mentation s for irrigation for Southwest ) State of Somalia SO-MOAI-418423-GO-RFB / P C5 Contingency Emergency Single Stage - One E Under Imple rocurement of hand farm tool IDA / E1850 Response Component (CERC Prior Request for Bids Open - National 400,000.00 0.00 2024-03-30 2024-04-13 2024-04-18 2024-04-25 2024-05-05 2024-09-02 nvelope mentation s for irrigation for Jubbaland ) State of Somalia SO-MOAI-418403-GO-RFB / P C5 Contingency Emergency rocurement of Irrigation Seed Open - Internationa Single Stage - One E Under Imple IDA / E1850 Response Component (CERC Prior Request for Bids 2,000,000.00 0.00 2024-04-02 2024-04-24 2024-04-16 2024-04-26 2024-04-21 2024-04-26 2024-05-17 2024-09-14 s for Southwest (Maize, Sesa l nvelope mentation ) me, Cowpeas, Vegetable See ds) SO-MOAI-418408-GO-RFB / P C5 Contingency Emergency rocurement of Irrigation Seed Open - Internationa Single Stage - One E Under Imple IDA / E1850 Response Component (CERC Prior Request for Bids 2,000,000.00 0.00 2024-04-02 2024-04-24 2024-04-16 2024-04-26 2024-04-21 2024-04-26 2024-05-17 2024-09-14 s for Hirshabelle (Maize, Sesa l nvelope mentation ) me, Cowpeas, Vegetable See ds) SO-MOAI-418410-GO-RFB / P C5 Contingency Emergency rocurement of Irrigation Seed Open - Internationa Single Stage - One E Under Imple IDA / E1850 Response Component (CERC Prior Request for Bids 2,000,000.00 0.00 2024-04-02 2024-04-19 2024-04-16 2024-04-22 2024-04-21 2024-04-26 2024-05-17 2024-09-14 s for Jubaland (Maize, Sesam l nvelope mentation ) e, Cowpeas, Vegetable Seeds ) SO-MOAI-418413-GO-RFB / P C5 Contingency Emergency rocurement of Procurement o Open - Internationa Single Stage - One E Under Imple IDA / E1850 Response Component (CERC Prior Request for Bids 1,800,000.00 0.00 2024-04-02 2024-04-16 2024-04-21 2024-04-26 2024-05-17 2024-09-14 f Agricultural/Livestock fodde l nvelope mentation ) r Tractor for 20 complete (inc luding trailer) SO-MOAI-415483-GO-RFB / P C5 Contingency Emergency Open - Internationa Single Stage - One E Under Imple rocurement of 3,014 No Vete IDA / E1850 Response Component (CERC Prior Request for Bids 3,000,000.00 0.00 2024-04-02 2024-04-16 2024-04-21 2024-04-26 2024-05-17 2024-09-14 l nvelope mentation rinary Kits for MoLFR FGS an ) d FMS SO-MOAI-423216-GO-RFB / P C5 Contingency Emergency Open - Internationa Single Stage - One E Pending Impl rocurement of Rain-fed Seed IDA / E1850 Response Component (CERC Prior Request for Bids 750,000.00 0.00 2024-04-25 2024-05-09 2024-05-14 2024-05-19 2024-06-05 2024-10-03 l nvelope ementation s for Southwest (Sorghum, C ) owpeas, maize) SO-MOAI-423218-GO-RFB / P C5 Contingency Emergency Open - Internationa Single Stage - One E Pending Impl rocurement of Rain-fed Seed IDA / E1850 Response Component (CERC Prior Request for Bids 750,000.00 0.00 2024-04-25 2024-05-09 2024-05-14 2024-05-19 2024-05-27 2024-09-24 l nvelope ementation s for Hirshabelle (Sorghum, C ) owpeas, maize) SO-MOAI-423219-GO-RFB / P C5 Contingency Emergency Open - Internationa Single Stage - One E Pending Impl rocurement of Rain-fed Seed IDA / E1850 Response Component (CERC Prior Request for Bids 750,000.00 0.00 2024-04-25 2024-05-09 2024-05-14 2024-05-19 2024-06-05 2024-10-03 l nvelope ementation s for Jubaland (Sorghum, Cow ) peas, maize) SO-MOAI-423220-GO-RFB / P C5 Contingency Emergency Open - Internationa Single Stage - One E Pending Impl rocurement of Rain-fed Seed IDA / E1850 Response Component (CERC Prior Request for Bids 750,000.00 0.00 2024-04-25 2024-05-09 2024-05-14 2024-05-19 2024-06-05 2024-10-03 l nvelope ementation s for Galmudug (Sorghum, C ) owpeas, maize). SO-MOAI-423221-GO-RFB / P C5 Contingency Emergency rocurement of hand farm tool Single Stage - One E Pending Impl IDA / E1850 Response Component (CERC Prior Request for Bids Open - National 300,000.00 0.00 2024-04-25 2024-05-09 2024-05-14 2024-05-19 2024-06-05 2024-10-03 s for rain-fed agriculture in S nvelope ementation ) outhwest and Jubbaland Stat e SO-MOAI-423222-GO-RFB / P C5 Contingency Emergency rocurement of hand farm tool Single Stage - One E Pending Impl IDA / E1850 Response Component (CERC Prior Request for Bids Open - National 300,000.00 0.00 2024-04-25 2024-05-09 2024-05-14 2024-05-19 2024-06-05 2024-10-03 s for rain-fed agriculture in Hi nvelope ementation ) rShabelle and Galmudug Page 1 SO-MOAI-423223-GO-RFB / P C5 Contingency Emergency rocurement of 120No Water Open - Internationa Single Stage - One E Pending Impl IDA / E1850 Response Component (CERC Prior Request for Bids 600,000.00 0.00 2024-04-25 2024-05-09 2024-05-14 2024-05-19 2024-06-09 2024-12-06 Pumps for three riverine stat l nvelope ementation ) es of Southwest, HirShabelle and Jubbaland NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SO-MOAI-376865-NC-RFQ / Office Rent for National Proje Request for Quota Single Stage - One E IDA / E1850 C6 Project Management Prior Limited 98,000.00 0.00 Signed 2023-08-30 2023-09-06 2023-10-25 2023-10-28 2024-10-19 ct Coordination Unit (NPCU) o tions nvelope f FSRP Project Somalia SO-MOAI-418456-NC-DIR / Pr C5 Contingency Emergency ovision of Emergency live-sa Direct - Internation Under Revie IDA / E1850 Response Component (CERC Prior Direct Selection 4,200,000.00 0.00 2024-03-31 2024-04-10 2024-05-08 2025-05-03 ving Food and non-food kits f al w ) or for Agro-pastoral and Past oral in Somalia CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SO-MOAI-416742-CS-QCBS / C4 Promoting a Greater Foc Quality And Cost- Open - Internationa Pending Impleme FSRP Project Baseline Study f IDA / E1850 us on Food Systems Resilien Prior 600,000.00 0.00 2024-03-27 2024-04-17 2024-05-22 2024-05-29 2024-06-08 2024-06-29 2024-07-20 2025-07-15 Based Selection l ntation or FGS and FMS ce in National and Regional Policymaking SO-MOAI-416743-CS-QCBS / National Environmental Impa Quality And Cost- Open - Internationa Pending Impleme IDA / E1850 C6 Project Management Prior 700,000.00 0.00 2024-03-27 2024-04-17 2024-05-22 2024-05-29 2024-06-08 2024-06-29 2024-07-20 2025-07-15 ct Assessment and Rangelan Based Selection l ntation d Management for FGS and F MS INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SO-MOAI-374819-CS-INDV / Individual Consult IDA / E1850 C6 Project Management Prior Open - National 96,000.00 0.00 Signed 2023-08-13 2023-08-08 2023-10-01 2024-01-06 2023-10-22 2024-01-18 2023-11-26 2024-01-27 2024-11-20 National Project Coordinator ant Selection SO-MOAI-375949-CS-INDV / Individual Consult Under Implement IDA / E1850 C6 Project Management Prior Open - National 75,000.00 0.00 2023-08-14 2023-08-21 2023-10-02 2023-10-23 2023-11-27 2024-11-21 National Procurement Special ant Selection ation ist SO-MOAI-375950-CS-INDV / Individual Consult Under Implement IDA / E1850 C6 Project Management Prior Open - National 75,000.00 0.00 2023-08-14 2023-08-08 2023-10-02 2023-10-23 2023-11-27 2024-11-21 National Financial Specialist ant Selection ation SO-MOAI-375951-CS-INDV / Individual Consult Under Implement IDA / E1850 C6 Project Management Prior Open - National 75,000.00 0.00 2023-08-14 2023-08-08 2023-10-02 2023-10-23 2023-11-27 2024-11-21 National GBV Specialist ant Selection ation SO-MOAI-375952-CS-INDV / Individual Consult Under Implement IDA / E1850 C6 Project Management Prior Open - National 60,000.00 0.00 2023-08-14 2023-08-08 2023-10-02 2023-10-23 2023-11-27 2024-11-21 National M&E Specialist ant Selection ation SO-MOAI-375953-CS-INDV / Individual Consult Under Implement National Environmental Safe IDA / E1850 C6 Project Management Prior Open - National 60,000.00 0.00 2023-08-14 2023-08-08 2023-10-02 2023-10-23 2023-11-27 2024-11-21 ant Selection ation guards Specialist SO-MOAI-375954-CS-INDV / Individual Consult Under Implement IDA / E1850 C6 Project Management Prior Open - National 60,000.00 0.00 2023-08-14 2023-08-08 2023-10-02 2023-10-23 2023-11-27 2024-11-21 National Security Specialist ant Selection ation SO-MOAI-375955-CS-INDV / Individual Consult Under Implement IDA / E1850 C6 Project Management Prior Open - National 60,000.00 0.00 2023-08-14 2023-08-08 2023-10-02 2023-10-23 2023-11-27 2024-11-21 National Social Safeguard Sp ant Selection ation ecialist SO-MOAI-375956-CS-INDV / Individual Consult Under Implement IDA / E1850 C6 Project Management Prior Open - National 60,000.00 0.00 2023-08-14 2023-08-08 2023-10-02 2023-10-23 2023-11-27 2024-11-21 National Internal Auditor ant Selection ation SO-MOAI-375981-CS-INDV / Individual Consult Under Implement IDA / E1850 C6 Project Management Prior Open - National 60,000.00 0.00 2023-08-14 2023-08-08 2023-10-02 2023-10-23 2023-11-27 2024-11-21 National Communication Spe ant Selection ation cialist SO-MOAI-379640-CS-INDV / Individual Consult IDA / E1850 C6 Project Management Prior Open - National 54,600.00 0.00 Under Review 2023-09-10 2023-10-26 2023-10-29 2023-11-19 2023-12-24 2024-12-18 SWS FSRP Project Coordinato ant Selection r SO-MOAI-379643-CS-INDV / Individual Consult Under Implement IDA / E1850 C6 Project Management Prior Open - National 44,280.00 0.00 2023-09-10 2023-11-06 2023-10-29 2023-11-19 2023-12-24 2024-12-18 SWS FSRP Financial Specialis ant Selection ation t SO-MOAI-379644-CS-INDV / Individual Consult IDA / E1850 C6 Project Management Prior Open - National 44,280.00 0.00 Under Review 2023-09-10 2023-10-11 2023-10-29 2023-11-19 2023-12-24 2024-12-18 SWS FSRP Procurement Spec ant Selection ialist SO-MOAI-379646-CS-INDV / Individual Consult Under Implement IDA / E1850 C6 Project Management Prior Open - National 44,280.00 0.00 2023-09-10 2023-11-01 2023-10-29 2023-11-19 2023-12-24 2024-12-18 SWS FSRP M&E Specialist ant Selection ation SO-MOAI-379647-CS-INDV / Individual Consult Under Implement SWS FSRP Social Safeguard a IDA / E1850 C6 Project Management Prior Open - National 44,280.00 0.00 2023-09-10 2023-11-01 2023-10-29 2023-11-19 2023-12-24 2024-12-18 ant Selection ation nd Community Specialist SO-MOAI-379648-CS-INDV / Individual Consult Under Implement IDA / E1850 C6 Project Management Prior Open - National 44,280.00 0.00 2023-09-10 2023-11-01 2023-10-29 2023-11-19 2023-12-24 2024-12-18 SWS FSRP Environmental Sp ant Selection ation ecialist SO-MOAI-379649-CS-INDV / J Individual Consult Under Implement IDA / E1850 C6 Project Management Prior Open - National 54,600.00 0.00 2023-09-10 2023-11-21 2023-10-29 2023-11-19 2023-12-24 2024-12-18 ubbaland FSRP Project Coordi ant Selection ation nator SO-MOAI-379650-CS-INDV / J Individual Consult IDA / E1850 C6 Project Management Prior Open - National 44,280.00 0.00 Under Review 2023-09-10 2023-11-27 2023-10-29 2023-11-19 2023-12-24 2024-12-18 ubbaland FSRP Procurement ant Selection Specialist SO-MOAI-379652-CS-INDV / J Individual Consult Under Implement IDA / E1850 C6 Project Management Prior Open - National 44,280.00 0.00 2023-09-10 2024-02-26 2023-10-29 2023-11-19 2023-12-24 2024-12-18 ubbaland FSRP Financial Spe ant Selection ation cialist Page 2 SO-MOAI-379653-CS-INDV / J Individual Consult Under Implement IDA / E1850 C6 Project Management Prior Open - National 44,280.00 0.00 2023-09-10 2023-11-21 2023-10-29 2023-11-19 2023-12-24 2024-12-18 ubbaland FSRP M&E Specialis ant Selection ation t SO-MOAI-379656-CS-INDV / J Individual Consult Under Implement ubbaland FSRP Social Safegu IDA / E1850 C6 Project Management Prior Open - National 44,280.00 0.00 2023-09-10 2023-11-20 2023-10-29 2023-11-19 2023-12-24 2024-12-18 ant Selection ation ard and Community Specialis t SO-MOAI-379658-CS-INDV / J Individual Consult Under Implement ubbaland FSRP Environmenta IDA / E1850 C6 Project Management Prior Open - National 44,280.00 0.00 2023-09-10 2023-11-21 2023-10-29 2023-11-19 2023-12-24 2024-12-18 ant Selection ation l Specialist SO-MOAI-379661-CS-INDV / Individual Consult IDA / E1850 C6 Project Management Prior Open - National 54,600.00 0.00 Under Review 2023-09-10 2023-11-20 2023-10-29 2023-11-19 2023-12-24 2024-12-18 HSS FSRP Project Coordinator ant Selection SO-MOAI-379663-CS-INDV / Individual Consult Under Implement IDA / E1850 C6 Project Management Prior Open - National 44,280.00 0.00 2023-09-10 2024-02-26 2023-10-29 2023-11-19 2023-12-24 2024-12-18 HSS FSRP Financial Specialist ant Selection ation SO-MOAI-379667-CS-INDV / Individual Consult Under Implement IDA / E1850 C6 Project Management Prior Open - National 44,280.00 0.00 2023-09-10 2023-11-26 2023-10-29 2023-11-19 2023-12-24 2024-12-18 HSS FSRP Procurement Speci ant Selection ation alist SO-MOAI-379671-CS-INDV / Individual Consult Under Implement IDA / E1850 C6 Project Management Prior Open - National 44,280.00 0.00 2023-09-10 2023-11-20 2023-10-29 2023-11-19 2023-12-24 2024-12-18 HSS FRSP M&E Specialist ant Selection ation SO-MOAI-379672-CS-INDV / Individual Consult Under Implement HSS FSRP Social Safeguard a IDA / E1850 C6 Project Management Prior Open - National 44,280.00 0.00 2023-09-10 2023-11-20 2023-10-29 2023-11-19 2023-12-24 2024-12-18 ant Selection ation nd Community Specialist SO-MOAI-379673-CS-INDV / Individual Consult Under Implement IDA / E1850 C6 Project Management Prior Open - National 44,280.00 0.00 2023-09-10 2023-11-20 2023-10-29 2023-11-19 2023-12-24 2024-12-18 HSS FSRP Environmental Spe ant Selection ation cialist SO-MOAI-379675-CS-INDV / Individual Consult Under Implement IDA / E1850 C6 Project Management Prior Open - National 54,600.00 0.00 2023-09-10 2023-11-20 2023-10-29 2023-11-19 2023-12-24 2024-12-18 GS FSRP Project Coordinator ant Selection ation SO-MOAI-379680-CS-INDV / Individual Consult Under Implement IDA / E1850 C6 Project Management Prior Open - National 44,280.00 0.00 2023-09-10 2024-02-26 2023-10-29 2023-11-19 2023-12-24 2024-12-18 GS FSRP Procurement Specia ant Selection ation list SO-MOAI-379684-CS-INDV / Individual Consult Under Implement IDA / E1850 C6 Project Management Prior Open - National 44,280.00 0.00 2023-09-10 2024-02-26 2023-10-29 2023-11-19 2023-12-24 2024-12-18 GS FSRP Financial Specialist ant Selection ation SO-MOAI-379694-CS-INDV / Individual Consult Under Implement GS FSRP Social Safeguard an IDA / E1850 C6 Project Management Prior Open - National 44,280.00 0.00 2023-09-10 2023-11-20 2023-10-29 2023-11-19 2023-12-24 2024-12-18 ant Selection ation d Community Specialist SO-MOAI-379698-CS-INDV / Individual Consult Under Implement IDA / E1850 C6 Project Management Prior Open - National 44,280.00 0.00 2023-09-10 2023-11-20 2023-10-29 2023-11-19 2023-12-24 2024-12-18 GS FRSP Environmental Spec ant Selection ation ialist SO-MOAI-379705-CS-INDV / Individual Consult Under Implement S-FSRP MoLFR-FGS National L IDA / E1850 C6 Project Management Prior Open - National 60,120.00 0.00 2023-09-10 2023-11-02 2023-10-29 2023-11-19 2023-12-24 2024-12-18 ant Selection ation ivestock Specialist SO-MOAI-379706-CS-INDV / Individual Consult Under Implement S-FSRP MoLFR-FGS National IDA / E1850 C6 Project Management Prior Open - National 60,120.00 0.00 2023-09-10 2023-10-31 2023-10-29 2023-11-19 2023-12-24 2024-12-18 ant Selection ation Range Management Specialis t SO-MOAI-418442-CS-CDS / T echnical Assistance for infras C5 Contingency Emergency Direct - Internation Pending Impleme tructure assessment, Design/ IDA / E1850 Response Component (CERC Prior Direct Selection 1,800,000.00 0.00 2024-03-30 2024-04-27 2024-06-01 2025-05-27 al ntation BoQ, ESMP/ESIA, Monitoring, ) supervision, CERAP MIS Dash board and TPM Page 3