Procurement Plan I. General 1. Project Information: Nigeria: Ibadan Urban Flood Management Project 2. Bank’s approval Date of the Procurement Plan: May 2014 3. Period covered by this procurement plan: 18 months II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement Procurement Method Method Prior Review Threshold Threshold USD 1. ICB (Goods and Non- Equal to and All consulting services) above 5,000,000 2. NCB (Goods and Non- Below 5,000,000 Equal to or Consulting Services) above USD700,000 3. Shopping (Goods) Below 100,000 None Shopping (Vehicles) - Below 500,000 None Quotations shall be from 1st line vehicle distributors 4. ICB (Works) Above 20,000,000 All 5. NCB (Works) Below 20,000,000 Equal to or above USD5,000,000 6. Shopping (Works) Below 200,000 None 2. Summary of the Procurement Packages planned during the first 18 months after project effectiveness 3. Procurement Packages with Methods and Time Schedule 1 2 3 4 5 6 7 Re Description Estimat Procure Domes Revie Comme f. ed ment tic w nts No Cost Method Prefer by . US$ ence Bank million (yes/n (Prior o) / Post) 00 Urban 17.4 ICB No Prior 1 Drainage Infrastructure Improvement at priority sites 00 Eleyele Dam 3.5 NCB No Prior This will 2 Safety Works be prior reviewed because of the sensitive nature of the package. III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Method Prior Review Threshold (USD) Threshold (USD) 1. Competitive Methods Equal to or above All (Firms); QCBS, QBS, LCS, 300,000 FCS 2. Consultant Qualification Below 300,000 None 3. Single Source Selection N/A All (Firms & Individual) 4. Individual N/A Above 100,000 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than US$300,000 equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 Ref. Description of Estimat Selecti Review Comments No. Assignment ed on by Bank Cost Metho (Prior / US$ d Post) 001 Engineering designs 2.0 QCBS Prior and construction supervision for works at priority sites 002 Engineering design 0.5 SSS Prior Due to the and construction unsafe supervision for condition of Eleyele dam safety the dam, works single source selection will be used to fast track the design and the bidding process for the works. 003 Ibadan integrated 3.5 QCBS Prior flood risk management master plan 004 Ibadan integrated 1.5 QCBS Prior physical master plan 005 Ibadan solid waste 1.5 QCBS Prior management master plan 006 Project management 4.0 QCBS Prior consultancy in support of PIU in areas of fiduciary, safeguards and technical 007 Preparation of ESIA 0.15 CQS Post 008 Preparation of RAP 0.15 CQS Post PROCUREMENT Nigeria : Ibadan Urban Flood Management Project PLAN General Information Country: Nigeria 2017-04-07 Bank’s Approval Date of the Original Procurement Plan: 2024-04-25 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P130840 GPN Date: Project Name: Ibadan Urban Flood Management Project Loan / Credit No: IDA / 55100 IBADAN FLOOD MANAGEMENT PROJECT Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned NG-IUFMP-11114-CW-RFB / E Component 2: Flood Risk Re Open - Internationa Single Stage - One E 12,000,000.0 10,811,401. 2018-01-2 IDA / 55100 Prior Request for Bids Signed 2017-01-31 2017-04-09 2017-04-09 2017-04-11 2017-05-21 2017-06-06 2017-06-20 2018-02-20 2017-07-25 2018-03-22 leyele Dam Safety Works duction l nvelope 0 17 1 NG-IUFMP-11148-CW-RFB / R Component 3: Project Admin Single Stage - One E Pending Imp 2018-06-1 enovation of Project Office Ac IDA / 55100 Post Request for Bids Open - National 620,000.00 0.00 2017-02-02 2017-02-07 2017-04-06 2017-05-06 2017-06-10 istration and Management nvelope lementation 0 comodation NG-IUFMP-11154-CW-RFB / C Component 2: Flood Risk Re Open - Internationa Single Stage - One E 21,000,000.0 17,794,267. 2018-02-1 onstruction Works at Ten (10 IDA / 55100 Prior Request for Bids Signed 2017-04-28 2017-06-27 2017-05-03 2017-07-14 2017-06-14 2017-07-14 2018-04-23 2017-08-18 2018-06-02 duction l nvelope 0 50 4 ) + Two (2) + One (1) Priority Sites NG-IUFMP-11125-CW-RFB / C Component 1: Flood Risk Ide Single Stage - One E Pending Imp 2018-05-2 onstruction Works for Extend IDA / 55100 ntification, Prevention and P Post Request for Bids Open - National 5,600,000.00 0.00 2017-08-08 2017-08-13 2017-09-24 2017-10-24 2017-11-28 nvelope lementation 7 ed Roads at 4 Priority Sites reparedness NG-IUFMP-11110-CW-RFQ / Component 1: Flood Risk Ide Request for Quota Single Stage - One E Pending Imp 2017-10-2 IDA / 55100 Post Open - National 1,000,000.00 0.00 2017-03-06 2017-05-01 Dredging of Rivers and Strea ntification, Prevention and P tions nvelope lementation 8 ms reparedness NG-IUFMP-11153-CW-RFB / C onstruction Works at Second Component 2: Flood Risk Re Open - Internationa Single Stage - One E 30,000,000.0 2018-07-2 IDA / 55100 Prior Request for Bids 0.00 Canceled 2017-10-04 2017-10-09 2017-11-20 2017-12-20 2018-01-24 pool of Priority Sites as Identi duction l nvelope 0 3 fied by Drainage Managemen t NG-IUFMP-11155-CW-RFB / Component 1: Flood Risk Ide Single Stage - One E Pending Imp 2017-07-3 Urban Drainage Infrastructur IDA / 55100 ntification, Prevention and P Post Request for Bids Open - National 4,900,000.00 0.00 2015-04-20 2015-04-25 2015-06-06 2015-07-06 2015-08-10 nvelope lementation 1 e Improvements at four (4) P reparedness riority Sites NG-IUFMP-64349-CW-RFB / C onstruction Works at First po Component 2: Flood Risk Re Open - Internationa Single Stage - One E 40,000,000.0 29,744,501. 2019-02-2 IDA / 55100 Prior Request for Bids Signed 2018-05-05 2018-12-18 2018-05-10 2019-01-23 2018-06-21 2019-03-20 2018-07-21 2020-04-01 2018-08-25 2020-06-10 ol of Priority Sites as Identifie duction l nvelope 0 34 1 d by Drainage Master Plan NG-IUFMP-70359-CW-RFQ / Component 2: Flood Risk Re Request for Quota Single Stage - One E Pending Imp 2018-11-2 Dredging of Rivers/Streams a IDA / 55100 Post Open - National 1,700,000.00 0.00 2018-04-04 2018-05-30 duction tions nvelope lementation 6 nd Clearing of Blocked Drains NG-IUFMP-70333-CW-RFQ / Component 2: Flood Risk Re Request for Quota Single Stage - One E Pending Imp 2018-10-2 Rehabilitation of Consultant's IDA / 55100 Post Open - National 30,000.00 0.00 2018-03-06 2018-05-01 duction tions nvelope lementation 8 Office at Eleyele Dam Site NG-IUFMP-100563-CW-RFB / Component 2: Flood Risk Re Single Stage - One E Pending Imp 2020-01-1 2019 Dredging of Rivers/Stre IDA / 55100 Post Request for Bids Open - National 1,000,000.00 0.00 2019-03-30 2019-04-04 2019-05-16 2019-06-15 2019-07-20 duction nvelope lementation 6 ams and Clearing of Blocked Drains NG-IUFMP-100565-CW-RFQ / Component 3: Project Admin Request for Quota Single Stage - One E Pending Imp 2019-10-1 Rehabilitation of BPP&DC Offi IDA / 55100 Post Open - National 140,000.00 0.00 2019-02-20 2019-04-17 istration and Management tions nvelope lementation 4 ce Complex (Master Plan Imp lementation) NG-IUFMP-100294-CW-RFQ / Component 3: Project Admin Request for Quota Single Stage - One E Pending Imp 2019-09-2 IDA / 55100 Post Open - National 50,000.00 0.00 2019-02-02 2019-03-30 Additional Works at IUFMP Pr istration and Management tions nvelope lementation 6 oject Office NG-IUFMP-156339-CW-RFB / Construction Works at Third Component 2: Flood Risk Re Open - Internationa Single Stage - One E 83,000,000.0 2021-01-1 & Fourth Pool of Long Term I IDA / 55100 Prior Request for Bids 0.00 Signed 2020-04-01 2020-08-01 2020-04-06 2020-08-06 2020-05-18 2020-10-02 2020-06-17 2022-10-09 2020-07-22 2022-11-01 duction l nvelope 0 8 nvestment as Identified by D rainage Master Plan (Lots 3a &b, 4a&b) NG-IUFMP-156363-CW-RFB / Component 2: Flood Risk Re Single Stage - One E Pending Imp 2020-11-1 2020 Dredging of Rivers/Stre IDA / 55100 Post Request for Bids Open - National 1,500,000.00 0.00 2020-02-01 2020-02-06 2020-03-19 2020-04-18 2020-05-23 duction nvelope lementation 9 ams and Clearing of Blocked Drains NG-IUFMP-156358-CW-RFB / Component 2: Flood Risk Re Single Stage - One E Pending Imp 2021-01-0 Rehabilitation & Construction IDA / 55100 Post Request for Bids Open - National 5,000,000.00 0.00 2020-03-15 2020-03-20 2020-05-01 2020-05-31 2020-07-05 duction nvelope lementation 1 of Appurtenant Structures of Agodi Lake NG-IUFMP-230356-CW-RFQ / Request for Quota Component 1: Flood Risk Ide Rehabilitation of Office Acco Request for Quota Single Stage - One E tions - Small Work Pending Imp 2021-12-1 IDA / 55100 ntification, Prevention and P Post Open - National 120,000.00 0.00 2021-04-25 2021-06-20 mmodation for EWS at Minist tions nvelope s (Emergency) SP lementation 7 reparedness ry of Environment & Natural D -Competitive Resources Request for Bids - NG-IUFMP-230353-CW-RFB / Component 2: Flood Risk Re Single Stage - One E Works (without pr Under Imple 2022-02-1 2021 Dredging of Rivers/Stre IDA / 55100 Post Request for Bids Open - National 1,000,000.00 0.00 2021-04-27 2021-03-11 2021-05-02 2021-06-13 2021-06-03 2021-07-13 2021-06-22 2021-08-17 duction nvelope equalification) SP mentation 3 ams and Clearing of Blocked D Drains Request for Bids - NG-IUFMP-230341-CW-RFB / Component 2: Flood Risk Re Single Stage - One E Works (without pr 13,500,000.0 2022-08-2 Extension Works on thirteen IDA / 55100 Post Request for Bids Open - National 0.00 Canceled 2021-11-10 2021-11-15 2021-12-27 2022-01-26 2022-03-02 duction nvelope equalification) SP 0 9 (13) Priority Sites D Request for Quota NG-IUFMP-263795-CW-DIR / tions - Small Work Component 2: Flood Risk Re 2,759,355.8 2022-06-3 Construction of De-scoped H IDA / 55100 Post Direct Selection Direct s (Emergency) SP 2,138,750.00 Signed 2021-11-22 2021-10-22 2021-11-27 2021-10-28 2022-01-01 2022-01-05 duction 8 0 ydraulic Structures under PLT D -Non Competiti 1 - 1a ve Request for Quota NG-IUFMP-263806-CW-DIR / tions - Small Work Component 2: Flood Risk Re 1,536,780.0 2022-06-3 Construction of De-scoped H IDA / 55100 Post Direct Selection Direct s (Emergency) SP 970,500.00 Signed 2021-11-22 2021-10-22 2021-11-27 2021-10-28 2022-01-01 2021-12-25 duction 7 0 ydraulic Structures under PLT D -Non Competiti 1 - 1b ve Request for Quota NG-IUFMP-263808-CW-DIR / tions - Small Work Component 2: Flood Risk Re 1,501,332.0 2022-06-3 Construction of De-scoped H IDA / 55100 Post Direct Selection Direct s (Emergency) SP 1,043,200.00 Signed 2021-11-22 2021-10-22 2021-11-27 2021-10-28 2022-01-01 2021-12-25 duction 3 0 ydraulic Structures under PLT D -Non Competiti 1 - 1c ve Page 1 Request for Quota NG-IUFMP-263810-CW-DIR / tions - Small Work Component 2: Flood Risk Re 2,229,715.4 2022-06-3 Construction of De-scoped H IDA / 55100 Post Direct Selection Direct s (Emergency) SP 1,569,820.00 Signed 2021-11-22 2021-10-22 2021-11-27 2021-10-28 2022-01-01 2021-12-25 duction 2 0 ydraulic Structures under PLT D -Non Competiti 1 - 2a ve NG-IUFMP-295036-CW-RFB / Request for Bids - 2022 Dredging/Desilting of s Component 2: Flood Risk Re Single Stage - One E Small Works SPD Pending Imp 2023-03-1 IDA / 55100 Post Request for Bids Open - National 1,000,000.00 0.00 2022-05-22 2022-05-27 2022-07-08 2022-08-07 2022-09-11 elected Rivers, Streams and duction nvelope (1 envelope proce lementation 0 Drains in Ibadan City of Oyo ss) State. NG-IUFMP-299001-CW-RFB / Request for Bids - Channelization of Agodi, Oro Component 2: Flood Risk Re Open - Internationa Single Stage - One E Works (without pr 16,000,000.0 13,746,397. 2023-04-0 IDA / 55100 Prior Request for Bids Signed 2022-06-16 2022-06-20 2022-06-21 2022-06-27 2022-08-02 2022-07-28 2022-09-01 2022-08-24 2022-10-06 2022-09-16 gun, Kudeti, and Ogbere Nort duction l nvelope equalification) SP 0 87 4 h Rivers for Flood Control in I D badan City of Oyo State NG-IUFMP-323657-CW-RFB / Request for Bids - Chennalization of Ogbere So Component 2: Flood Risk Re Single Stage - One E Works (without pr 2023-08-2 IDA / 55100 Prior Request for Bids Open - National 5,415,000.00 0.00 Signed 2022-11-10 2023-02-10 2022-11-15 2022-12-27 2022-11-29 2023-01-26 2024-03-12 2023-03-02 2023-05-31 uth River for Flood Control in duction nvelope equalification) SP 9 Ibadan City of Oyo State D NG-IUFMP-325461-CW-RFQ / Request for Quota Construction of Two (2) Major Component 2: Flood Risk Re Request for Quota Single Stage - One E tions - Small Work Under Imple 2023-07-0 IDA / 55100 Post Open - National 1,076,208.00 0.00 2022-11-13 2023-01-08 Hydraulic Structures (ID 73 & duction tions nvelope s (Emergency) SP mentation 7 ID 125A) Under PLTI–1 D -Competitive Request for Quota NG-IUFMP-391840-CW-RFQ / tions - Small Work Component 2: Flood Risk Re Under Imple 2024-06-1 Completion of Defect Works ( IDA / 55100 Post Direct Selection Direct - National s (Emergency) SP 200,000.00 0.00 2023-11-08 2023-09-18 2023-11-13 2023-09-25 2023-12-18 duction mentation 5 IDs 6T, 132, 125A) and EWS/ D -Non Competiti OYSEMA Building ve Request for Quota NG-IUFMP-396081-CW-DIR / tions - Small Work Component 2: Flood Risk Re Direct - Internation 22,000,000.0 2024-07-0 Completion of Upper Ona Riv IDA / 55100 Prior Direct Selection s (Emergency) SP 0.00 Signed 2023-12-01 2023-12-09 2023-12-06 2023-12-25 2024-01-10 2024-02-02 duction al 0 8 er Channel (formerly Lot 3A) D -Non Competiti and Bridge 1185 ve Request for Quota NG-IUFMP-392172-CW-DIR / Component 2: Flood Risk Re tions - Small Work 2024-06-1 Completion of ID 76 (PLTI 1: IDA / 55100 Post Direct Selection Direct - National 1,500,000.00 0.00 Canceled 2023-11-08 2023-09-12 2023-11-13 2023-09-25 2023-12-18 duction s (Emergency) SP 5 De-Scoped) D -Non Competiti ve NG-IUFMP-325185-CW-RFQ / Request for Quota Component 2: Flood Risk Re Request for Quota Single Stage - One E 2023-07-1 Electrification of Early Warnin IDA / 55100 Post Open - National tions (Non Bank-S 64,500.00 0.00 Canceled 2022-11-16 2023-01-11 duction tions nvelope 0 g System Building & Other A PD) dditional Works GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NG-IUFMP-11105-GO-RFQ / C Component 1: Flood Risk Ide Request for Quota Single Stage - One E Pending Impl IDA / 55100 Post Open - National 16,000.00 0.00 2017-03-12 2017-05-07 2017-11-03 omputers and Office Equipm ntification, Prevention and P tions nvelope ementation ent reparedness NG-IUFMP-11160-GO-RFQ / E lectronic Contract Manageme Component 3: Project Admin Request for Quota Single Stage - One E Pending Impl IDA / 55100 Post Open - National 10,000.00 0.00 2017-04-17 2017-06-12 2017-12-09 nt Software (Supply, Installati istration and Management tions nvelope ementation on and Training) NG-IUFMP-11151-GO-RFQ / Component 3: Project Admin Request for Quota Single Stage - One E Pending Impl IDA / 55100 Post Open - National 16,000.00 0.00 2017-03-19 2017-05-14 2017-11-10 Office Furniture istration and Management tions nvelope ementation NG-IUFMP-11116-GO-RFQ / F Component 1: Flood Risk Ide abrication of Complaint Boxe Request for Quota Single Stage - One E Pending Impl IDA / 55100 ntification, Prevention and P Post Open - National 2,000.00 0.00 2017-05-22 2017-07-17 2018-01-13 s (40 No.) for Grievance Redr tions nvelope ementation reparedness ess Mechanism (GRM) NG-IUFMP-11129-GO-RFQ / P Component 3: Project Admin Request for Quota Single Stage - One E Pending Impl rinting of Project Documents IDA / 55100 Post Open - National 2,000.00 0.00 2017-03-06 2017-05-01 2017-10-28 istration and Management tions nvelope ementation - (Accounting/Procurement D ocuments) NG-IUFMP-22114-GO-RFQ / P Component 3: Project Admin Request for Quota Single Stage - One E Pending Impl rocurement of 4x4WD Pick-U IDA / 55100 Post Limited 60,000.00 0.00 2017-08-27 2017-10-22 2018-04-20 istration and Management tions nvelope ementation p Van for State Mediation Ce ntre NG-IUFMP-22118-GO-RFQ / P Component 3: Project Admin Request for Quota Single Stage - One E Pending Impl rocurement of Office Equipm IDA / 55100 Post Limited 5,000.00 0.00 2017-08-28 2017-10-23 2018-04-21 istration and Management tions nvelope ementation ent in Support of State Media tion Centre NG-IUFMP-22123-GO-RFQ / P Component 2: Flood Risk Re Request for Quota Single Stage - One E Pending Impl rocurement of Material for Fl IDA / 55100 Post Limited 3,800.00 0.00 2017-09-05 2017-10-31 2018-04-29 duction tions nvelope ementation ood Emergency Response NG-IUFMP-22126-GO-RFQ / P Component 1: Flood Risk Ide Request for Quota Single Stage - One E Pending Impl rinting of Notepad with Beha IDA / 55100 ntification, Prevention and P Post Limited 12,000.00 0.00 2017-08-14 2017-10-09 2018-04-07 tions nvelope ementation vioral Change Messages reparedness NG-IUFMP-22128-GO-RFQ / P Component 1: Flood Risk Ide rocurement of Award and Sa Request for Quota Single Stage - One E Pending Impl IDA / 55100 ntification, Prevention and P Post Limited 1,600.00 0.00 2017-08-28 2017-10-23 2018-04-21 nitation Material for Operatio tions nvelope ementation reparedness n Keep Ibadan Clean and Flo od Free (OKIC&FF) NG-IUFMP-70341-GO-RFQ / P rocurement of 3 Nos 4x4WD Pick-Up, one (2) Cars and on Component 2: Flood Risk Re Request for Quota Single Stage - One E Pending Impl IDA / 55100 Post Open - National 200,000.00 0.00 2018-02-25 2018-04-22 2018-10-19 e (1) Mini Jeep for supervisio duction tions nvelope ementation n of construction works at Thi rteen (13) Priority Sites and E leyele Dam Rehabilitation NG-IUFMP-70348-GO-RFQ / S upply and Installation of slott Component 3: Project Admin Request for Quota Single Stage - One E Pending Impl IDA / 55100 Post Open - National 16,500.00 0.00 2018-06-20 2018-08-15 2019-02-11 ed Angle Racks for Archiving istration and Management tions nvelope ementation Procurement Documents NG-IUFMP-91416-GO-RFQ / P Component 3: Project Admin Request for Quota Single Stage - One E Pending Impl IDA / 55100 Post Open - National 92,000.00 0.00 2018-12-18 2019-02-12 2019-08-11 rocurement of Office Furnitur istration and Management tions nvelope ementation e & Fittings NG-IUFMP-100562-GO-RFQ / Component 1: Flood Risk Ide Design and Production of IUF Request for Quota Single Stage - One E Pending Impl IDA / 55100 ntification, Prevention and P Post Open - National 50,000.00 0.00 2019-10-06 2019-12-01 2020-05-29 MP Calendars and Branded S tions nvelope ementation reparedness ouvenirs for Project Stakehol ders Page 2 NG-IUFMP-100567-GO-RFQ / Procurement of additional Off Component 3: Project Admin Request for Quota Single Stage - One E Pending Impl ice Furniture and Fittings for I IDA / 55100 Post Limited 50,000.00 0.00 2019-02-15 2019-04-12 2019-10-09 istration and Management tions nvelope ementation UFMP Project Office (Cabinet s, Tables & Chairs, Reading L amps, etc) NG-IUFMP-100692-GO-RFQ / Procurement of Laptops and Component 3: Project Admin Request for Quota Single Stage - One E Pending Impl Desktop Computers, Photoco IDA / 55100 Post Open - National 75,000.00 0.00 2019-02-16 2019-04-13 2019-10-10 istration and Management tions nvelope ementation piers Machine, Multipurpose Printers (A0, A1 & A3) UPS, e tc NG-IUFMP-104691-GO-RFQ / Design and Printing of IUFMP Component 1: Flood Risk Ide Request for Quota Single Stage - One E Pending Impl Quarterly Newsletter, Comm IDA / 55100 ntification, Prevention and P Post Open - National 22,500.00 0.00 2019-03-30 2019-05-25 2019-11-21 tions nvelope ementation unity GRM Operations Manua reparedness l and other Awareness Materi als. NG-IUFMP-121992-GO-RFQ / Component 3: Project Admin Request for Quota Single Stage - One E Pending Impl Procurement of Geographic I IDA / 55100 Post Open - National 250,000.00 0.00 2019-07-15 2019-09-09 2020-03-07 istration and Management tions nvelope ementation nformation System (GIS) Equi pment NG-IUFMP-156369-GO-RFQ / Procurement & Installation of 10KVA Hybrid (Solar/Grid) Po wer Backup to cover IUFMP O Component 3: Project Admin Request for Quota Single Stage - One E Pending Impl IDA / 55100 Post Open - National 30,000.00 0.00 2020-02-15 2020-04-11 2020-10-08 ffice Complex, Internet/Data istration and Management tions nvelope ementation Security Hardware & Softwar e and Provision of 4G LTE Int ernet Connectivity at 11 Zon al UREMEC Offices NG-IUFMP-156362-GO-RFQ / Procurement of one (1) Multi Component 3: Project Admin Request for Quota Single Stage - One E Pending Impl IDA / 55100 Post Open - National 15,000.00 0.00 2020-02-15 2020-04-11 2020-10-08 purpose Network Printer and istration and Management tions nvelope ementation two (2) other Network Printer s/Copier NG-IUFMP-121987-GO-RFQ / Provision of Internet and Info Component 3: Project Admin Request for Quota Single Stage - One E Under Imple IDA / 55100 Post Open - National 125,000.00 0.00 2019-07-14 2019-09-08 2020-03-06 rmation Technology Infrastru istration and Management tions nvelope mentation cture in IUFMP Project Office NG-IUFMP-199032-GO-RFB / Procurement and Installation Component 2: Flood Risk Re Open - Internationa Single Stage - One E Under Imple of Flood Early Warning and R IDA / 55100 Prior Request for Bids 2,000,000.00 0.00 2020-10-09 2021-02-10 2020-10-14 2021-04-07 2020-11-25 2021-05-25 2020-12-25 2022-01-13 2021-01-29 2021-07-28 duction l nvelope mentation esponse System Equipment i n Strategic locations in Ibada n NG-IUFMP-230434-GO-RFQ / Procurement and Installation Component 3: Project Admin Request for Quota Single Stage - One E Pending Impl IDA / 55100 Post Open - National 50,000.00 0.00 2021-05-08 2021-07-03 2021-12-30 of Flood Warning Post in the istration and Management tions nvelope ementation Flood Plain Areas in Ibadan Ci ty NG-IUFMP-230454-GO-RFQ / Supply and Installation of fift Component 3: Project Admin Request for Quota Single Stage - One E Under Imple een (15) Laptop Computers f IDA / 55100 Post Open - National 15,000.00 0.00 2021-07-23 2021-09-17 2022-03-16 istration and Management tions nvelope mentation or PIU Staff and one (1) Multi purpose Photocopying Machi ne NG-IUFMP-156485-GO-RFB / Procurement of 6 Nos. 4X4W Component 3: Project Admin Single Stage - One E Pending Impl D Pick-up Monitoring Vehicle IDA / 55100 Post Request for Bids Open - National 250,000.00 0.00 2020-02-16 2020-02-21 2020-04-03 2020-05-03 2020-06-07 2020-12-04 istration and Management nvelope ementation s for Contract Supervision of Pool of Works on LTI as identi fied by Drainage Master Plan NG-IUFMP-336633-GO-RFQ / Component 2: Flood Risk Re Request for Quota Single Stage - One E Under Imple Procurement of Two (2) Nos IDA / 55100 Post Open - National 20,000.00 0.00 2023-01-27 2023-03-24 2023-09-20 duction tions nvelope mentation Drones and Accessories NG-IUFMP-391842-GO-DIR / Component 1: Flood Risk Ide Direct - Internation Under Imple Completion of Outstanding E IDA / 55100 ntification, Prevention and P Post Direct Selection 500,000.00 0.00 2023-11-07 2023-08-24 2023-11-12 2023-09-06 2023-12-17 2024-06-14 al mentation WS Equipment Supplies reparedness NG-IUFMP-325158-GO-DIR / Component 2: Flood Risk Re Direct - Internation Supply and Installation of Ou IDA / 55100 Post Direct Selection 1,367,405.26 0.00 Canceled 2022-11-08 2022-11-13 2022-12-18 2023-06-16 duction al tstanding Early Warning Syst em Equipment NG-IUFMP-420802-GO-RFB / Component 2: Flood Risk Re Single Stage - One E Pending Impl SWWMP Quick Win - Procure IDA / 55100 Post Request for Bids Limited - National 550,000.00 0.00 2024-04-24 2024-04-24 2024-07-03 2024-08-02 2024-09-06 2026-02-28 duction nvelope ementation ment of Machinery NG-IUFMP-424298-GO-RFQ / Procurement of Cloud Serve Component 2: Flood Risk Re Request for Quota Single Stage - One E Pending Impl IDA / 55100 Post Limited - National 160,000.00 0.00 2024-04-25 2024-04-25 2024-04-25 & Subscription Renewal (Earl duction tions nvelope ementation y Warning Systems) NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NG-IUFMP-22132-NC-RFQ / R Component 1: Flood Risk Ide Request for Quota Single Stage - One E Pending Impl adio Drama Production and B IDA / 55100 ntification, Prevention and P Post Limited 12,000.00 0.00 2017-08-13 2017-10-08 2018-04-06 tions nvelope ementation roadcast (Season/Quarter- 13 reparedness Episodes) NG-IUFMP-336645-NC-RFP / Component 3: Project Admin Request for Propo Single Stage - One E Retreat for Project Team (Te IDA / 55100 Post Open - National 35,000.00 0.00 Canceled 2023-01-22 2023-02-23 2023-01-27 2023-03-10 2023-04-09 2023-05-14 2023-11-10 istration and Management sals nvelope am Bonding) CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NG-IUFMP-11115-CS-QCBS / Component 2: Flood Risk Re Quality And Cost- Open - Internationa Pending Impleme IDA / 55100 Post 1,500,000.00 0.00 2014-04-28 2014-05-19 2014-07-02 2014-07-30 2014-08-29 2014-10-03 2014-11-07 2017-07-14 Ibadan City Urban Master Pla duction Based Selection l ntation n Page 3 NG-IUFMP-11118-CS-QCBS / Component 2: Flood Risk Re Quality And Cost- Open - Internationa Ibadan Solid Waste Manage IDA / 55100 Prior 1,500,000.00 0.00 Canceled 2014-05-05 2014-05-26 2014-07-09 2014-08-06 2014-09-05 2014-10-10 2017-05-04 2017-04-20 2018-04-20 duction Based Selection l ment Master Plan NG-IUFMP-11126-CS-QCBS / Component 2: Flood Risk Re Quality And Cost- Open - Internationa Under Implement Ibadan Integrated Flood Risk IDA / 55100 Prior 3,500,000.00 0.00 2014-04-21 2014-05-12 2014-06-25 2017-04-07 2014-07-23 2016-03-29 2014-08-22 2017-04-07 2014-09-26 2017-04-07 2017-04-20 2021-04-20 duction Based Selection l ation Management and Drainage M aster Plan NG-IUFMP-11156-CS-QBS / P reparation and Supervision of Component 2: Flood Risk Re Quality Based Sel Open - Internationa Pending Impleme Implementation of Safeguar IDA / 55100 Post 2,500,000.00 0.00 2017-02-27 2017-04-28 2017-06-11 2017-07-09 2017-08-08 2017-09-07 2017-10-12 2018-10-12 duction ection l ntation d Instrument for Pool of Priori ty Sites as Identified in the D rainage Masterplan NG-IUFMP-11161-CS-QCBS / Engineering design and const Component 2: Flood Risk Re Quality And Cost- Open - Internationa IDA / 55100 Prior 1,876,000.00 0.00 Canceled 2015-04-01 2015-04-22 2015-06-05 2015-07-03 2015-08-02 2015-09-06 2015-10-11 2020-04-01 ruction supervision for works duction Based Selection l at 10 +2 priority sites NG-IUFMP-11147-CS-QCBS / Component 2: Flood Risk Re Quality And Cost- Open - Internationa Development of Flood Early IDA / 55100 Prior 7,000,000.00 0.00 Canceled 2016-08-12 2016-09-02 2017-05-12 2017-12-19 2017-06-09 2018-03-05 2017-07-09 2017-08-13 2017-09-17 2018-09-17 duction Based Selection l Warning and Response Syste m NG-IUFMP-11145-CS-QCBS / Component 1: Flood Risk Ide Quality And Cost- Open - Internationa Pending Impleme IDA / 55100 Post 250,000.00 0.00 2016-03-11 2016-04-01 2017-04-25 2017-05-23 2017-06-22 2017-07-27 2017-08-31 2018-08-31 Project Baseline Survey ntification, Prevention and P Based Selection l ntation reparedness NG-IUFMP-11149-CS-CQS / C Component 1: Flood Risk Ide Consultant Qualifi Pending Impleme reation and Hosting of GIS En IDA / 55100 ntification, Prevention and P Post Open - National 45,000.00 0.00 2015-02-08 2015-02-08 2015-02-08 2015-02-08 2017-03-15 2017-09-11 cation Selection ntation abled Portal reparedness NG-IUFMP-11137-CS-CQS / E Component 2: Flood Risk Re Consultant Qualifi Open - Internationa Pending Impleme IDA / 55100 Post 100,000.00 0.00 2015-03-23 2015-04-13 2015-05-27 2015-06-26 2015-07-31 2017-02-27 SIA for Eleyele Dam Rehabilit duction cation Selection l ntation ation NG-IUFMP-11106-CS-CQS / P Component 2: Flood Risk Re Consultant Qualifi Open - Internationa Pending Impleme reparation of ESIAs, ESMP's a IDA / 55100 Post 280,000.00 0.00 2015-03-26 2015-04-16 2015-05-30 2015-06-29 2015-08-03 2017-04-28 duction cation Selection l ntation nd RAP for ten (10) priority si tes NG-IUFMP-11159-CS-QCBS / Component 1: Flood Risk Ide Project Monitoring and Evalu Quality And Cost- Open - Internationa Pending Impleme IDA / 55100 ntification, Prevention and P Post 250,000.00 0.00 2016-03-14 2016-04-04 2016-05-18 2016-06-15 2016-07-15 2016-08-19 2017-05-16 2018-05-16 ation (M&E) Management Inf Based Selection l ntation reparedness ormation System (MIS) NG-IUFMP-11123-CS-CQS / D Component 1: Flood Risk Ide Consultant Qualifi Pending Impleme esign and Construction Super IDA / 55100 ntification, Prevention and P Post Open - National 50,000.00 0.00 2015-12-04 2015-12-25 2016-02-07 2016-03-08 2016-04-12 2017-05-30 cation Selection ntation vision of New Project Office reparedness NG-IUFMP-11146-CS-CQS / E Component 1: Flood Risk Ide ngineering design and constr Consultant Qualifi Pending Impleme IDA / 55100 ntification, Prevention and P Post Open - National 120,000.00 0.00 2017-02-14 2017-03-07 2017-04-20 2017-05-20 2017-06-24 2017-12-21 uction supervision for Extend cation Selection ntation reparedness ed Roads at 4 Priority Sites NG-IUFMP-70346-CS-CQS / E Component 3: Project Admin Consultant Qualifi Pending Impleme IDA / 55100 Post Open - National 9,000.00 0.00 2018-02-10 2018-03-03 2018-04-16 2018-05-16 2018-06-20 2018-12-17 ngagement of External Audit istration and Management cation Selection ntation or (PFMU) NG-IUFMP-70327-CS-CQS / D evelopment and deployment Component 3: Project Admin Consultant Qualifi Pending Impleme IDA / 55100 Post Open - National 100,000.00 0.00 2018-02-01 2018-02-22 2018-04-07 2018-05-07 2018-06-11 2018-12-08 of Data Digitization and Archi istration and Management cation Selection ntation ve Management NG-IUFMP-70361-CS-QCBS / Component 1: Flood Risk Ide Quality And Cost- Open - Internationa Development of Early Warnin IDA / 55100 ntification, Prevention and P Prior 7,000,000.00 2,281,408.75 Signed 2018-05-25 2018-06-15 2018-07-29 2018-08-26 2018-09-25 2018-10-30 2018-11-21 2018-12-04 2019-01-21 2019-12-04 Based Selection l g and Response Systems reparedness NG-IUFMP-91443-CS-CQS / C Component 3: Project Admin Consultant Qualifi Under Implement onsultancy Service to Undert IDA / 55100 Post Open - National 200,000.00 0.00 2018-12-24 2019-02-27 2019-01-14 2019-02-27 2019-03-29 2019-05-03 2019-10-30 istration and Management cation Selection ation ake Mid-Term Review Assess ment NG-IUFMP-100558-CS-CQS / Engagement of Consultant fo Component 1: Flood Risk Ide r the Preparation of Safeguar Consultant Qualifi Pending Impleme IDA / 55100 ntification, Prevention and P Post Open - National 492,000.00 0.00 2019-02-04 2019-02-25 2019-04-10 2019-05-10 2019-06-14 2019-12-11 ds Instruments (ESMP, ESIA cation Selection ntation reparedness & RAP) for the Second Pool of Long Term Investment as ide ntified by Drainage Master Pl an NG-IUFMP-100555-CS-CQS / Engagement of Consultant fo r the Conduct of 3rd Party En Component 2: Flood Risk Re Consultant Qualifi Under Implement IDA / 55100 Post Open - National 150,000.00 0.00 2019-01-28 2019-05-16 2019-02-18 2019-04-03 2019-05-03 2019-06-07 2019-12-04 vironmental and Social Moni duction cation Selection ation toring for ongoing Projects (C onstruction Works at 13 Sites , 4 Priority Sites and Eleyele Dam) NG-IUFMP-100564-CS-CQS / Consultancy Services for Stra Component 1: Flood Risk Ide Consultant Qualifi Pending Impleme tegic Communication Activiti IDA / 55100 ntification, Prevention and P Post Open - National 250,000.00 0.00 2019-02-05 2019-02-26 2019-04-11 2019-05-11 2019-06-15 2019-12-12 cation Selection ntation es (Essay Competition, Docu reparedness mentary, Jingles, Drama, Adv ertisments etc) NG-IUFMP-100699-CS-CQS / Selection of Witness Non-Gov Component 3: Project Admin Consultant Qualifi Pending Impleme IDA / 55100 Post Open - National 50,000.00 0.00 2019-02-28 2019-03-21 2019-05-04 2019-06-03 2019-07-08 2020-01-04 ernmental Organization (NG istration and Management cation Selection ntation O) for RAP Implementation NG-IUFMP-100702-CS-CQS / Selection of Consultant to Co Component 3: Project Admin Consultant Qualifi Pending Impleme IDA / 55100 Post Open - National 120,000.00 0.00 2019-09-09 2019-09-30 2019-11-13 2019-12-13 2020-01-17 2020-07-15 nduct Beneficiary Impact Ass istration and Management cation Selection ntation essment and Satisfaction Sur vey NG-IUFMP-100718-CS-CQS / 2019 Retreat on Visioning an Component 3: Project Admin Consultant Qualifi Pending Impleme IDA / 55100 Post Open - National 45,000.00 0.00 2019-02-25 2019-03-18 2019-05-01 2019-05-31 2019-07-05 2020-01-01 d Acculturation for PIU memb istration and Management cation Selection ntation ers and Other Stakeholders NG-IUFMP-104668-CS-CQS / Consultancy Service for the S Component 2: Flood Risk Re Consultant Qualifi Pending Impleme upervision of 2019 Dredging IDA / 55100 Post Open - National 26,000.00 0.00 2019-03-18 2019-04-08 2019-05-22 2019-06-21 2019-07-26 2020-01-22 duction cation Selection ntation of Selected River/Streams an d Desilting of Drains in Ibada n City. NG-IUFMP-104678-CS-QCBS / Consultancy Service for Con Component 2: Flood Risk Re Quality And Cost- Pending Impleme IDA / 55100 Post Open - National 750,000.00 0.00 2019-03-18 2019-04-08 2019-05-22 2019-06-19 2019-07-19 2019-08-23 2019-09-27 2020-09-26 struction Supervision of Work duction Based Selection ntation s at Second Pool of Long Ter m Investment. Page 4 NG-IUFMP-104667-CS-CQS / Component 2: Flood Risk Re Consultant Qualifi Consultancy Service for Dam IDA / 55100 Post Open - National 100,000.00 0.00 Canceled 2019-03-15 2019-04-05 2019-05-19 2019-06-18 2019-07-23 2020-01-19 duction cation Selection Safety Assessment of Awba a nd IITA Dams. NG-IUFMP-156356-CS-CQS / Consultancy Services for the Component 2: Flood Risk Re Consultant Qualifi Pending Impleme Supervision of 2020 Dredgin IDA / 55100 Post Open - National 50,000.00 0.00 2020-02-18 2020-03-10 2020-04-23 2020-05-23 2020-06-27 2020-12-24 duction cation Selection ntation g of Selected Rivers/Streams and Desilting of Drains in Iba dan City NG-IUFMP-156424-CS-CQS / Consultancy Service for Desi gn and Implementation of Int Component 2: Flood Risk Re Consultant Qualifi Pending Impleme egrated Standard Operating IDA / 55100 Post Open - National 25,000.00 0.00 2020-06-15 2020-07-06 2020-08-19 2020-09-18 2020-10-23 2021-04-21 duction cation Selection ntation Procedures (SOP) including T raining and Drilling during rai ny season for Early Warning Systems for MDAs NG-IUFMP-156364-CS-CQS / Consultancy Service for Prep Component 1: Flood Risk Ide Consultant Qualifi Pending Impleme aration of Safeguards Instru IDA / 55100 ntification, Prevention and P Post Open - National 150,000.00 0.00 2020-01-20 2020-02-10 2020-03-25 2020-04-24 2020-05-29 2020-11-25 cation Selection ntation ments (ESIAs/ESMPs/RAPs) fo reparedness r Priority Solid Waste Manage ment Assests NG-IUFMP-156425-CS-QCBS / Support for Economic Activi ties with Public Private Partn Component 2: Flood Risk Re Quality And Cost- Open - Internationa IDA / 55100 Prior 5,000,000.00 0.00 Canceled 2020-03-05 2021-11-01 2020-03-26 2020-05-09 2020-06-06 2020-07-06 2020-08-10 2020-09-14 2021-09-14 ership (PPP) Initiative around duction Based Selection l Pool of Investments including Assest Management Inventor y/Plan NG-IUFMP-156430-CS-CQS / Component 2: Flood Risk Re Consultant Qualifi Pending Impleme Bathymetry Survey & Design IDA / 55100 Post Open - National 80,000.00 0.00 2020-02-10 2020-03-02 2020-04-15 2020-05-15 2020-06-19 2020-12-16 duction cation Selection ntation of Agodi Lake Rehabilitation NG-IUFMP-156368-CS-CQS / Preparation of Safeguards Ins truments (ESMPs, ESIAs & RA Component 1: Flood Risk Ide Least Cost Selecti Under Implement P) for the Construction Works IDA / 55100 ntification, Prevention and P Post Open - National 400,000.00 0.00 2020-02-04 2020-03-17 2020-02-25 2020-04-09 2020-04-28 2020-05-07 2020-06-06 2020-07-11 2020-08-15 2021-02-11 on ation at Second and Third pool of P reparedness riority Sites as Identified by D rainage Management (Lot 3 & 4) NG-IUFMP-104666-CS-CQS / Consultancy Service for Bath Component 2: Flood Risk Re Consultant Qualifi Under Implement ymetric Survey and Dam Saf IDA / 55100 Post Open - National 230,000.00 0.00 2019-03-15 2019-06-11 2019-04-05 2019-05-19 2019-06-18 2019-07-23 2020-01-19 duction cation Selection ation ety Assessment for Eleyele D am, Awba Dam and IITA Dam NG-IUFMP-162546-CS-QCBS Component 1: Flood Risk Ide / Preparation of Solid Waste Quality And Cost- Open - Internationa Under Implement IDA / 55100 ntification, Prevention and P Prior 1,000,000.00 0.00 2020-03-11 2020-03-06 2020-04-01 2020-04-03 2020-05-15 2021-08-17 2020-06-12 2021-06-04 2020-07-12 2021-11-01 2020-08-16 2022-03-31 2020-09-20 2021-09-20 Master Plan including detaile Based Selection l ation reparedness d Engineering Design of reco mmended Infrastructure NG-IUFMP-100287-CS-INDV / Engagement of Consultant fo Component 3: Project Admin Consultant Qualifi Pending Impleme r the Mapping Services for G IDA / 55100 Post Open - National 120,000.00 0.00 2020-06-12 2020-07-03 2020-08-16 2020-09-15 2020-10-20 2021-04-18 istration and Management cation Selection ntation ender-Based Violence and De velopment of Referral Direct ory & Protocol NG-IUFMP-104674-CS-QCBS / Consultancy Service for Con Component 2: Flood Risk Re Quality And Cost- IDA / 55100 Prior 4,050,467.18 3,663,165.21 Signed 2019-03-08 2020-08-27 2019-03-29 2019-05-12 2019-06-09 2019-07-09 2019-08-13 2020-09-25 2019-09-17 2020-10-13 2020-09-16 struction Supervision of Work duction Based Selection s at First Pool of Long Term I nvestment. NG-IUFMP-211438-CS-CQS / Consultancy Services for Un Component 1: Flood Risk Ide manned Aerial Vehicle (UAV) Consultant Qualifi Pending Impleme IDA / 55100 ntification, Prevention and P Post Open - National 100,000.00 0.00 2020-12-24 2021-01-14 2021-02-27 2021-03-29 2021-05-03 2021-10-30 Based Monitoring & Evaluatio cation Selection ntation reparedness n, Training and Flood Damag e Assessment Mapping of Are as in Ibadan City NG-IUFMP-230367-CS-LCS / Component 2: Flood Risk Re Least Cost Selecti Under Implement Consultancy Service for the S IDA / 55100 Post Open - National 165,000.00 0.00 2021-04-27 2021-04-21 2021-05-18 2021-07-01 2021-07-29 2021-08-28 2021-10-02 2021-11-06 2022-05-05 duction on ation upervision of Agodi Lake Reh abilitation NG-IUFMP-230390-CS-CQS / Consultancy Service for the P Component 1: Flood Risk Ide Consultant Qualifi Pending Impleme reparation of Safeguards Inst IDA / 55100 ntification, Prevention and P Post Open - National 100,000.00 0.00 2021-04-27 2021-05-18 2021-07-01 2021-07-31 2021-09-04 2022-03-03 cation Selection ntation ruments for the Extension W reparedness orks at thirteen (13) Priority Sites NG-IUFMP-230429-CS-CQS / Component 1: Flood Risk Ide Consultancy Service for the P Consultant Qualifi Under Implement IDA / 55100 ntification, Prevention and P Post Open - National 15,000.00 0.00 2021-05-03 2021-09-20 2021-05-24 2021-07-07 2021-08-06 2021-09-10 2022-03-09 reparation of Emergency Pre cation Selection ation reparedness paredness Plan (EPP) for Eley ele Dam Safety NG-IUFMP-230402-CS-CQS / Component 3: Project Admin Consultant Qualifi Consultancy Service for Deve IDA / 55100 Post Open - National 75,000.00 113,437.68 Signed 2021-04-26 2022-02-02 2021-05-17 2021-06-30 2021-04-20 2021-07-30 2021-11-26 2021-09-03 2022-03-05 2022-03-02 istration and Management cation Selection lopment of Asset Manageme nt Plan NG-IUFMP-260149-CS-LCS / Component 1: Flood Risk Ide Consultancy Service for the P Least Cost Selecti Pending Impleme IDA / 55100 ntification, Prevention and P Post Open - National 35,000.00 0.00 2021-10-29 2021-11-19 2022-01-02 2022-01-30 2022-03-01 2022-04-05 2022-05-10 2022-11-06 reparation of ESIA for Agodi L on ntation reparedness ake Rehabilitation NG-IUFMP-100559-CS-CQS / Engagement of Consultant fo Component 3: Project Admin Consultant Qualifi Under Implement r the Implementation of RAPs IDA / 55100 Post Open - National 150,000.00 0.00 2021-11-15 2022-01-19 2021-12-06 2022-01-19 2022-02-21 2022-02-18 2022-03-14 2022-03-25 2022-09-21 istration and Management cation Selection ation for the Second Pools of LTIs a s identified by Drainage Mast er Plan (Lot 3 & 4) NG-IUFMP-230368-CS-CQS / Component 1: Flood Risk Ide Consultancy Service for the P Consultant Qualifi IDA / 55100 ntification, Prevention and P Post Open - National 10,000.00 0.00 Canceled 2021-04-26 2021-05-17 2021-06-30 2021-07-30 2021-09-03 2022-03-02 reparation of ESIA for Agodi L cation Selection reparedness ake Rehabilitation NG-IUFMP-299007-CS-CQS / Consultancy Service for Cons truction Supervision for Pool Component 2: Flood Risk Re Consultant Qualifi Under Implement IDA / 55100 Post Open - National 250,000.00 0.00 2022-06-14 2022-06-24 2022-07-05 2022-08-18 2022-09-17 2022-10-22 2023-04-20 of Works (PLTI-1: Lot 2) and duction cation Selection ation De-scoped Major Hydraulic St ructures in Ibadan City of Oy o State Page 5 NG-IUFMP-299012-CS-QCBS / Consultancy Service for Con Component 2: Flood Risk Re Quality And Cost- Open - Internationa struction Supervision for Cha IDA / 55100 Prior 1,287,520.15 0.00 Signed 2022-06-14 2022-07-08 2022-07-05 2022-07-11 2022-08-18 2022-09-21 2022-09-15 2022-10-21 2022-10-15 2022-11-24 2022-11-19 2023-01-20 2022-12-24 2023-07-26 2023-12-24 duction Based Selection l nnelization Works (PLTI-1: Lo t 1) and Sencon Pools of Wor ks (PLTI - 2) NG-IUFMP-333648-CS-CQS / Component 3: Project Admin Consultant Qualifi IDA / 55100 Post Open - National 50,000.00 0.00 Signed 2022-12-27 2023-01-17 2023-01-17 2023-03-02 2023-04-11 2023-04-01 2023-07-25 2023-05-06 2023-07-24 2023-11-02 Consultancy Service for Tech istration and Management cation Selection nical Audit NG-IUFMP-345670-CS-CQS / Component 3: Project Admin Consultant Qualifi Retreat for Project Team (Te IDA / 55100 Post Open - National 35,000.00 0.00 Under Review 2023-02-24 2023-01-31 2023-03-17 2023-04-30 2023-05-30 2023-07-04 2023-12-31 istration and Management cation Selection am Bonding) NG-IUFMP-420810-CS-CQS / Component 2: Flood Risk Re Consultant Qualifi Pending Impleme SWWMP - Technical Assistanc IDA / 55100 Post Open - National 20,000.00 0.00 2024-04-07 2024-04-28 2024-06-11 2024-07-11 2024-08-15 2025-02-11 duction cation Selection ntation e for Implementation NG-IUFMP-423762-CS-CQS / Consultant Service for Prepar Component 2: Flood Risk Re Consultant Qualifi Open - Internationa Pending Impleme IDA / 55100 Post 200,000.00 0.00 2024-04-24 2024-05-15 2024-06-28 2024-07-28 2024-09-01 2025-02-28 ation of Flood Resilience Stra duction cation Selection l ntation tegy for the City of Ibadan NG-IUFMP-423775-CS-CQS / Component 2: Flood Risk Re Consultant Qualifi Pending Impleme Consultancy Service for the P IDA / 55100 Post Open - National 70,000.00 0.00 2024-04-24 2024-05-15 2024-06-28 2024-07-28 2024-09-01 2025-02-28 duction cation Selection ntation reparation of Impact Evaluati on Report (IER) NG-IUFMP-424290-CS-CQS / Component 2: Flood Risk Re Consultant Qualifi Open - Internationa Pending Impleme Completion of Outstanding D IDA / 55100 Post 170,000.00 0.00 2024-04-25 2024-05-16 2024-06-29 2024-07-29 2024-09-02 2025-03-01 duction cation Selection l ntation eliverables on SWMMP INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NG-IUFMP-11108-CS-CDS / E ngineering design and constr Component 2: Flood Risk Re Pending Impleme IDA / 55100 Post Direct Selection Direct 500,000.00 0.00 2014-09-29 2014-09-29 2014-10-20 2017-08-31 uction supervision for Eleyele duction ntation Dam Safety Works NG-IUFMP-11124-CS-INDV / Component 1: Flood Risk Ide Individual Consult Pending Impleme Stakeholders Engagement Pl IDA / 55100 ntification, Prevention and P Post Open 75,000.00 0.00 2015-04-22 2015-04-22 2015-04-22 2016-07-22 2017-01-18 ant Selection ntation an for Fourteen (14) Priority reparedness Sites NG-IUFMP-11157-CS-INDV / Component 1: Flood Risk Ide Preparation of Safeguard Inst Individual Consult Pending Impleme IDA / 55100 ntification, Prevention and P Post Open 32,000.00 0.00 2017-03-14 2017-05-02 2017-05-23 2017-06-27 2017-12-24 rument (ESMP) for the Exten ant Selection ntation reparedness ded Roads at 4 Priority Sites NG-IUFMP-11112-CS-INDV / Component 1: Flood Risk Ide Individual Consult Pending Impleme Baseline Survey for Cummuni IDA / 55100 ntification, Prevention and P Post Open 75,000.00 0.00 2017-03-06 2017-04-24 2017-05-15 2017-06-19 2017-12-16 ant Selection ntation cation Strategy reparedness NG-IUFMP-70352-CS-INDV / Component 1: Flood Risk Ide Individual Consult Pending Impleme Preparation of ESMP & RAP fo IDA / 55100 ntification, Prevention and P Post Open 65,000.00 0.00 2018-02-10 2018-03-31 2018-04-21 2018-05-26 2018-11-22 ant Selection ntation r Extended Roads at Four (4) reparedness Priority Sites NG-IUFMP-91421-CS-INDV / Component 3: Project Admin Individual Consult Under Implement Engagement of Monitoring a IDA / 55100 Post Open 75,000.00 0.00 2018-12-13 2019-01-29 2019-01-31 2019-02-21 2019-03-28 2019-09-24 istration and Management ant Selection ation nd Evaluation Consultant NG-IUFMP-91434-CS-INDV / Component 3: Project Admin Individual Consult Under Implement Engagement of Procurement IDA / 55100 Post Open 75,000.00 0.00 2018-12-13 2019-01-29 2019-01-31 2020-11-30 2019-02-21 2021-09-01 2019-03-28 2019-09-24 istration and Management ant Selection ation Consultant NG-IUFMP-91435-CS-INDV / Component 3: Project Admin Individual Consult Under Implement IDA / 55100 Post Open 75,000.00 0.00 2018-12-13 2019-01-29 2019-01-31 2019-02-21 2019-03-28 2019-09-24 Engagement of Hydraulic Co istration and Management ant Selection ation nsultant NG-IUFMP-91436-CS-INDV / Component 3: Project Admin Individual Consult Under Implement Engagement of Information T IDA / 55100 Post Open 75,000.00 0.00 2018-12-13 2019-01-29 2019-01-31 2019-02-21 2019-03-28 2019-09-24 istration and Management ant Selection ation echnology (IT) Consultant NG-IUFMP-91440-CS-INDV / Component 3: Project Admin Individual Consult Under Implement Engagement of Geographic I IDA / 55100 Post Open 75,000.00 0.00 2018-12-13 2019-01-29 2019-01-31 2019-02-21 2019-03-28 2019-09-24 istration and Management ant Selection ation nformation System (GIS) Con sultant NG-IUFMP-100552-CS-INDV / Component 2: Flood Risk Re Individual Consult Pending Impleme Re-Engagement of Dam Pane IDA / 55100 Post Open 83,000.00 0.00 2019-02-15 2019-04-05 2019-04-26 2019-05-31 2019-11-27 duction ant Selection ntation l of Experts for Eleyele Dam Supervision NG-IUFMP-100550-CS-INDV / Engagement of Consultant fo Component 2: Flood Risk Re Individual Consult Pending Impleme r the Preparation of Safeguar IDA / 55100 Post Open 65,500.00 0.00 2019-02-11 2019-04-01 2019-04-22 2019-05-27 2019-11-23 duction ant Selection ntation ds Instruments for 2019 Dred ging of Rivers/Streams and C learing of Blocked Drains NG-IUFMP-100297-CS-INDV / Engagement of Consultant to Component 3: Project Admin Individual Consult Pending Impleme IDA / 55100 Post Open 30,000.00 0.00 2019-09-01 2019-10-20 2019-11-10 2019-12-15 2020-06-12 conduct RAP Completion Aud istration and Management ant Selection ntation it and RAP Endline M&E stud y for 13 Priority Sites NG-IUFMP-100289-CS-INDV / Component 1: Flood Risk Ide Engagement of Consultant fo Individual Consult Pending Impleme IDA / 55100 ntification, Prevention and P Post Open 50,000.00 0.00 2019-02-14 2019-04-04 2019-04-25 2019-05-30 2019-11-26 r the Update of Stakeholders ant Selection ntation reparedness Engagement Plan NG-IUFMP-100547-CS-INDV / Engagement of Consultant fo Component 3: Project Admin Individual Consult r the Deployment of Multi-Ch IDA / 55100 Post Open 82,000.00 0.00 Under Review 2019-03-11 2024-01-12 2019-04-29 2019-05-20 2019-06-24 2019-12-21 istration and Management ant Selection annel Grievance Managemen t Suite (MCGMS) including tol l-free hotline NG-IUFMP-100566-CS-INDV / Procurement and Setting Up of Licensed Microsoft Project Component 3: Project Admin Individual Consult Pending Impleme IDA / 55100 Post Open 20,000.00 0.00 2019-03-25 2019-05-13 2019-06-03 2019-07-08 2020-01-04 (Professional) Software, Prim istration and Management ant Selection ntation avera 6 Project Management Softaware and Training of PI U members. Page 6 NG-IUFMP-103399-CS-INDV / Engagement of 3 Nos Individ Component 3: Project Admin Individual Consult Pending Impleme ual Consultants (2 Nos Civil E IDA / 55100 Post Direct 5,000.00 0.00 2019-03-04 2019-03-14 2019-04-04 2019-05-09 2019-11-05 istration and Management ant Selection ntation ngineers + 1 No Safeguard) f or Evaluation of 1st Pool of L ong Term Investment NG-IUFMP-154208-CS-CDS / Component 3: Project Admin Under Implement Engagement of Engr. S.A. Ad IDA / 55100 Post Direct Selection Direct 35,000.00 0.00 2020-01-21 2020-02-05 2020-01-31 2020-04-05 2020-10-02 istration and Management ation eniji (Hydraulic Expert) NG-IUFMP-156354-CS-INDV / Engagement of Urban Enviro Component 3: Project Admin Individual Consult Under Implement IDA / 55100 Post Open 61,000.00 0.00 2020-02-10 2020-02-27 2020-03-30 2020-04-20 2020-05-25 2020-11-21 nment and Solid Waste Mana istration and Management ant Selection ation gement Expert (supporting M oE&NR) NG-IUFMP-156360-CS-INDV / Component 3: Project Admin Individual Consult Pending Impleme Engagement of Environment IDA / 55100 Post Open 61,000.00 0.00 2020-02-10 2020-03-30 2020-04-20 2020-05-25 2020-11-21 istration and Management ant Selection ntation al Councellor (supporting Mo E&NR) NG-IUFMP-156367-CS-INDV / Component 3: Project Admin Individual Consult Pending Impleme Engagement of Environment IDA / 55100 Post Open 61,000.00 0.00 2020-02-10 2020-03-30 2020-04-20 2020-05-25 2020-11-21 istration and Management ant Selection ntation al Legal Adviser (supporting MoE&NR) NG-IUFMP-179866-CS-CDS / Component 2: Flood Risk Re Construction Supervision of E IDA / 55100 Prior Direct Selection Direct 190,434.74 728,505.31 Signed 2020-06-12 2020-06-22 2020-08-26 2020-09-15 2021-02-22 duction leyele Rehabilitation and Inta ke Works: NG-IUFMP-199036-CS-CDS / Short Term Consultancy on V Component 3: Project Admin Individual Consult Pending Impleme aluation of Building and Affec IDA / 55100 Post Direct 12,000.00 0.00 2020-11-25 2020-12-05 2020-12-26 2021-01-30 2021-04-30 istration and Management ant Selection ntation ted Structures in Targeted Sit es on LTIs on Drainage Maste rPlan for Ibadan City NG-IUFMP-206339-CS-CDS / Consultancy Service for the Component 2: Flood Risk Re Under Implement IDA / 55100 Prior Direct Selection Direct 24,630.00 0.00 2021-01-17 2021-01-27 2021-04-02 2021-09-29 Design and Construction Sup duction ation ervision of Thirteen (13) Prior ity Sites NG-IUFMP-230397-CS-INDV / Consultancy Service for the S Component 2: Flood Risk Re Individual Consult Pending Impleme upervision of 2021 Dredging IDA / 55100 Post Open 26,500.00 0.00 2021-04-27 2021-06-15 2021-07-06 2021-08-10 2022-02-06 duction ant Selection ntation of Rivers.Streams and Desilti ng of Drains in Ibadan City NG-IUFMP-243640-CS-INDV / Component 3: Project Admin Individual Consult Under Implement Engagement of Individual Co IDA / 55100 Post Open 350.00 0.00 2021-07-16 2021-02-04 2021-09-03 2021-09-24 2021-10-29 2022-04-27 istration and Management ant Selection ation nsultant (Environmental Safe guards Expert) NG-IUFMP-100277-CS-INDV / Engagement of Consultant to Component 2: Flood Risk Re Individual Consult IDA / 55100 Post Open 22,000.00 0.00 Canceled 2019-01-31 2019-03-21 2019-04-11 2019-05-16 2019-11-12 undertake the Supply, Install duction ant Selection ation, Licensing and Training on ODK Software NG-IUFMP-230374-CS-INDV / Component 3: Project Admin Individual Consult Engagement of Individual Co IDA / 55100 Post Open 35,000.00 0.00 Under Review 2021-04-26 2021-01-06 2021-06-14 2021-07-05 2021-08-09 2022-02-05 istration and Management ant Selection nsultant (Social Safeguards E xpert) NG-IUFMP-230388-CS-INDV / Component 3: Project Admin Individual Consult Under Implement Engagement of Project Coord IDA / 55100 Post Open 65,000.00 0.00 2021-04-26 2021-03-18 2021-06-14 2021-09-03 2021-07-05 2021-08-09 2022-02-05 istration and Management ant Selection ation inator (Consultant) for IUFMP NG-IUFMP-260155-CS-INDV / Component 3: Project Admin Individual Consult Under Implement Engagement of Contract Man IDA / 55100 Post Open 35,000.00 0.00 2021-11-01 2022-01-03 2021-12-20 2022-01-10 2022-02-14 2022-08-13 istration and Management ant Selection ation agement Consultant NG-IUFMP-260156-CS-INDV / Component 3: Project Admin Individual Consult Under Implement Engagement of Quantity Sur IDA / 55100 Post Open 35,000.00 0.00 2021-11-01 2022-01-03 2021-12-20 2022-01-10 2022-02-14 2022-08-13 istration and Management ant Selection ation veyor (Consultant) NG-IUFMP-260157-CS-INDV / Component 3: Project Admin Individual Consult Under Implement IDA / 55100 Post Open 35,000.00 0.00 2021-11-01 2022-01-03 2021-12-20 2022-01-10 2022-02-14 2022-08-13 Engagement of Hydraulic Co istration and Management ant Selection ation nsultant NG-IUFMP-230360-CS-CDS / Component 1: Flood Risk Ide Consultancy Service for Desi Pending Impleme IDA / 55100 ntification, Prevention and P Post Direct Selection Direct 550,000.00 0.00 2021-11-10 2021-11-20 2022-01-24 2022-07-23 gn and Supervision of Extens ntation reparedness ion Works on thirteen (13) Pri ority Sites NG-IUFMP-295029-CS-CDS / Component 3: Project Admin Under Implement Engagement of Environment IDA / 55100 Post Direct Selection Direct 35,000.00 0.00 2022-05-15 2022-05-05 2022-05-25 2022-07-29 2023-01-25 istration and Management ation al Safeguards Consultant NG-IUFMP-325111-CS-INDV / Component 3: Project Admin Individual Consult Under Implement Engagement of Procurement IDA / 55100 Post Open - National 35,000.00 0.00 2022-11-07 2022-11-07 2022-12-26 2022-12-09 2023-01-16 2023-02-20 2023-08-19 istration and Management ant Selection ation Consultant NG-IUFMP-325157-CS-CDS / Re-engagement of Consultan Component 1: Flood Risk Ide Direct - Internation Under Implement cy Service for Flood Forecast IDA / 55100 ntification, Prevention and P Post Direct Selection 984,963.45 0.00 2022-11-08 2022-11-08 2022-11-18 2023-01-22 2023-07-21 al ation and Warning Services and Im reparedness plementation Support NG-IUFMP-325160-CS-CDS / Component 3: Project Admin Under Implement Re-engagement of Witness N IDA / 55100 Post Direct Selection Direct - National 49,661.15 0.00 2022-11-10 2022-10-10 2022-11-20 2022-11-09 2023-01-24 2023-07-23 istration and Management ation GO for RAP Implementation NG-IUFMP-325165-CS-CDS / Component 1: Flood Risk Ide Under Implement Re-engagement of Consultan IDA / 55100 ntification, Prevention and P Post Direct Selection Direct - National 41,726.67 0.00 2022-11-10 2022-11-07 2022-11-20 2023-01-24 2023-07-23 ation cy Service for RAP Implemen reparedness tation NG-IUFMP-333644-CS-INDV / Component 3: Project Admin Individual Consult Under Implement Engagement of Project Mana IDA / 55100 Post Open - National 35,000.00 0.00 2022-12-27 2023-02-10 2023-02-14 2023-03-07 2023-04-11 2023-10-08 istration and Management ant Selection ation gement Expert (PME) NG-IUFMP-341991-CS-INDV / Component 3: Project Admin Individual Consult Under Implement IDA / 55100 Post Open - National 25,000.00 0.00 2023-02-14 2023-02-10 2023-04-04 2023-04-25 2023-05-30 2023-11-26 Engagement of Hydraulic Co istration and Management ant Selection ation nsultant NG-IUFMP-341994-CS-INDV / Component 3: Project Admin Individual Consult Under Implement Engagement of Two (2) Nos. IDA / 55100 Post Open - National 50,000.00 0.00 2023-02-14 2023-02-10 2023-04-04 2023-03-28 2023-04-25 2023-04-28 2023-05-30 2023-11-26 istration and Management ant Selection ation Project Engineers Page 7 NG-IUFMP-376252-CS-CDS / Consultancy Service for Impl Component 3: Project Admin Under Implement IDA / 55100 Post Direct Selection Direct - National 100,000.00 0.00 2023-08-13 2023-08-18 2023-08-23 2023-08-18 2023-10-27 2024-04-24 ementation of Third Party En istration and Management ation vironmental and Social Monit oring (TPM-ES) NG-IUFMP-339575-CS-CDS / Consultancy Service for Ident Component 2: Flood Risk Re IDA / 55100 Post Direct Selection Direct - National 50,000.00 0.00 Canceled 2023-02-06 2023-02-13 2023-02-16 2023-04-22 2023-10-19 ification and Treatment of Ha duction zardous Waste Management NG-IUFMP-423768-CS-INDV / SWMMP Quick Win - Consulta Component 2: Flood Risk Re Individual Consult Pending Impleme IDA / 55100 Post Limited - National 20,000.00 0.00 2024-04-24 2024-04-29 2024-05-20 2024-06-24 2024-12-21 ncy Service for ESMP Prepara duction ant Selection ntation tion for Awotan Dump Site NG-IUFMP-423776-CS-INDV / Component 2: Flood Risk Re Individual Consult Pending Impleme Consultancy Service for Prep IDA / 55100 Post Direct - National 60,000.00 0.00 2024-04-24 2024-05-04 2024-05-25 2024-06-29 2024-12-26 duction ant Selection ntation aration of Project Completion Report (PCR) Page 8