PROCUREMENT PLAN (Textual Part) Project information: Eastern Recovery Project (P145196) Project Implementation agency: FSRDC Date of the Procurement Plan: February 2018 Period covered by this Procurement Plan: January 2018 – December 2018 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016 and revised November 2017) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the Borrower’s Public Procurement Law No 10/010 of April 27, 2010 (PPL) and the Manual of Procedures of the PPL as per Borrower’s Decree No 10/22 of June 2, 2010, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. (a) Standard Bidding Documents: All standard bidding documents to be used for the Project under NCB shall be found acceptable to the World Bank before their use during the implementation of Project; (b) Eligibility: Eligibility of bidders and acceptability of their goods and services shall not be based on their nationality and/or their origin; and association with a national firm shall not be a condition for participation in a bidding process. Therefore, except for the ineligibility situations referred to in paragraphs 1.10(a) (i) and 1.10(a) (ii) of the Procurement Guidelines, the eligibility of bidders must be based solely on their qualification, experience and capacity to carry out the contract related to the specific bidding process; (c) Advertising and Bid Preparation Time: Bidding opportunities shall be advertised at least in a national newspaper of wide circulation and on the website of the Recipient’s Procurement Regulator (Autorité de Régulation des Marchés Publics) and bidders should be given at least 30 days from the date of invitation to bid or the date of availability of the bidding documents, whichever is later; (d) Criteria for Qualification of Bidders: Qualification criteria shall only concern the bidder’s capability and resources to perform the contract taking into account objective and measurable factors. Such criteria for qualification of bidders shall be clearly specified in the bidding documents; (e) Bid Evaluation and Contract Award: A contract shall be awarded to the substantially responsive and lowest evaluated bidder provided that such bidder meets the qualification criteria specified in the bidding documents. No scoring system shall be allowed for the evaluation of bids, and no “blanket” limitation to the number of lots which can be awarded to a bidder shall apply. The criteria for bid evaluation and the contract award conditions shall be clearly specified in the bidding documents; (f) Preferences: No preference shall be given to domestic/regional bidders; to domestically/regionally manufactured goods; and to bidders forming a joint venture with a national firm or proposing national sub-contractors or carrying out economic activities in the territory of the Recipient; (g) Publication of Contract Award: Information on all contract awards shall be published in at least a national newspaper of wide circulation or in the Recipient’s Procurement Regulator (Autorité de Régulation des Marchés Publics) web-site; (h) Fraud and Corruption: In accordance with the Procurement Guidelines, each bidding document and contract shall include provisions stating the World Bank’s policy to sanction firms or individuals found to have engaged in fraud and corruption as set forth in the Procurement Guidelines; (i) Inspection and Audit Rights: In accordance with the Procurement Guidelines, each bidding document and contract shall include provisions stating the World Bank’s policy with respect to inspection and audit of accounts, records and other documents relating to the bid submission and contract performance; (j) Requirement for administrative documents and/or tax clearance certificate: The bidding documents shall not require foreign bidders to produce any administrative or tax related certificates prior to confirmation of awarding a contract; and (k) Modifications of a Signed Contract: Any change in the contract amount which, singly or combined with all previous changes, increases the original contract amount by fifteen (15) percent or more must be done through an amendment to the signed contract instead of signing a new contract. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables. “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: is applicable for those contracts identified in the Procurement Plan tables; Other Relevant Procurement Information. “Not Applicable” PROCUREMENT Congo, Democratic Republic of : DRC Eastern Recovery Project PLAN General Information Country: Congo, Democratic Republic of 2021-05-04 Bank’s Approval Date of the Original Procurement Plan: Revised Plan Date(s): (comma delineated, leave blank2023-04-24 if none) Project ID: P145196 GPN Date: Project Name: DRC Eastern Recovery Project Loan / Credit No: IDA / 66650 Social Fund DRC, Ituri Antenna Executing Agency(ies): WORKS Activity Reference No. / Procurement Estimated Actual A Bid Evaluation Repor Loan / Credit N Market Approac Procurement Pr Prequalification High SEA/SH Process S Draft Pre-qualificatio Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission Contract Comple Description Component Review Type Method Document Typ Amount (U mount (U t and Recommendati Signed Contract o. h ocess (Y/N) Risk tatus n Documents ation Report ent / Justification Notice / Invitation s Issued / Opening / Minutes tion e S$) S$) on for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Demande de cota ZR-FSRDC-232889-CW-RFQ / 1. Support to Community Re Single Stage - One tions (DTPM ne pr En attente 2022-02-2 IDA / 66650 A posteriori Demande de prix Limited 150,000.00 0.00 2021-07-05 2021-08-30 Construction de l’EP TSHIBAL silience Envelope ovenant pas de la d'exécution 6 A Banque) Demande de cota ZR-FSRDC-232892-CW-RFQ / 1. Support to Community Re Single Stage - One tions (DTPM ne pr En attente 2022-02-2 IDA / 66650 A posteriori Demande de prix Limited 150,000.00 0.00 2021-07-05 2021-08-30 Construction de l’EP CENTRA silience Envelope ovenant pas de la d'exécution 6 L Banque) Demande de cota ZR-FSRDC-232897-CW-RFQ / 1. Support to Community Re Single Stage - One tions (DTPM ne pr En attente 2022-02-2 IDA / 66650 A posteriori Demande de prix Limited 150,000.00 0.00 2021-07-05 2021-08-30 Construction de l’EP TUBADI silience Envelope ovenant pas de la d'exécution 6 Banque) Demande de cota ZR-FSRDC-236160-CW-RFQ / 1. Support to Community Re Single Stage - One tions (DTPM ne pr 2021-08-1 Travaux de construction de l' IDA / 66650 A posteriori Demande de prix Open - National 135,778.25 135,778.25 Achevé 2020-12-17 2021-02-11 2020-11-30 silience Envelope ovenant pas de la 0 EP 2 LUNGANDU/KANANGA ( Banque) 001) Demande de cota ZR-FSRDC-236049-CW-RFQ / 1. Support to Community Re Single Stage - One tions (DTPM ne pr 2021-08-1 Travaux de construction de l' IDA / 66650 A posteriori Demande de prix Limited 138,055.95 138,055.95 Signé 2020-12-20 2020-11-12 2021-02-14 2020-11-30 silience Envelope ovenant pas de la 3 EP NGIDILAYI/KANANGA (002 Banque) ) Demande de cota ZR-FSRDC-236413-CW-RFQ / 1. Support to Community Re Single Stage - One tions (DTPM ne pr 2021-08-1 Travaux de construction de l' IDA / 66650 A posteriori Demande de prix Open - National 130,112.45 137,704.22 Signé 2020-12-22 2021-02-16 2020-11-30 silience Envelope ovenant pas de la 5 EP ARC-EN-CIEL/KANANGA (0 Banque) 03) Demande de cota ZR-FSRDC-236358-CW-RFQ / 1. Support to Community Re Single Stage - One tions (DTPM ne pr 2021-08-0 Travaux de construction de l' IDA / 66650 A posteriori Demande de prix Open - National 121,136.49 121,136.47 Signé 2020-12-15 2021-02-09 2020-11-30 silience Envelope ovenant pas de la 8 E.P 1 LUMUMBA/KANANGA (0 Banque) 04) Demande de cota ZR-FSRDC-236162-CW-RFQ / 1. Support to Community Re Single Stage - One tions (DTPM ne pr 2021-08-1 Travaux de construction de l' IDA / 66650 A posteriori Demande de prix Open - National 136,988.22 136,988.22 Signé 2020-12-19 2021-02-13 2020-11-30 silience Envelope ovenant pas de la 2 EP MUINDIDI/KANANGA (005) Banque) Demande de cota ZR-FSRDC-236343-CW-RFQ / 1. Support to Community Re Single Stage - One tions (DTPM ne pr 2021-08-0 Travaux de construction de l' IDA / 66650 A posteriori Demande de prix Open - National 137,705.22 130,112.45 Signé 2020-12-11 2021-02-05 2020-11-30 silience Envelope ovenant pas de la 4 EP 2 MUKOLESHI/KANANGA ( Banque) 006) Demande de cota ZR-FSRDC-236054-CW-RFQ / 1. Support to Community Re Single Stage - One tions (DTPM ne pr 2021-08-0 Travaux de construction de l' IDA / 66650 A posteriori Demande de prix Limited 128,633.00 128,632.96 Achevé 2020-12-13 2020-11-18 2021-02-07 2020-11-30 silience Envelope ovenant pas de la 6 EP KAPAJIKA/KANANGA (007) Banque) Demande de cota ZR-FSRDC-236394-CW-RFQ / 1. Support to Community Re Single Stage - One tions (DTPM ne pr 2021-08-0 Travaux de construction de l' IDA / 66650 A posteriori Demande de prix Open - National 139,531.03 139,895.53 Achevé 2020-12-13 2021-02-07 2020-11-30 silience Envelope ovenant pas de la 6 E.P KANDIKU/KANANGA (008) Banque) Demande de cota ZR-FSRDC-236360-CW-RFQ / 1. Support to Community Re Single Stage - One tions (DTPM ne pr 2021-08-1 Travaux de construction de l' IDA / 66650 A posteriori Demande de prix Open - National 138,488.22 138,488.22 Signé 2020-12-24 2021-02-18 2020-11-30 silience Envelope ovenant pas de la 7 EP MUFIMISHI/KANANGA (009 Banque) ) Demande de cota ZR-FSRDC-236163-CW-RFQ / 1. Support to Community Re Single Stage - One tions (DTPM ne pr 2021-08-1 Travaux de construction de l' IDA / 66650 A posteriori Demande de prix Open - National 128,651.09 128,651.09 Signé 2020-12-22 2021-02-16 2020-12-07 silience Envelope ovenant pas de la 5 EP MUDIDIKE/KANANGA (010 Banque) ) Demande de cota ZR-FSRDC-236084-CW-RFQ / 1. Support to Community Re Single Stage - One tions (DTPM ne pr 2021-08-1 Travaux de construction de l' IDA / 66650 A posteriori Demande de prix Limited 136,814.03 136,814.03 Signé 2020-12-21 2020-11-23 2021-02-15 2020-12-07 silience Envelope ovenant pas de la 4 EP NGANZA/KANANGA (011) Banque) Demande de cota ZR-FSRDC-236410-CW-RFQ / 2. Livelihoods and Employm Single Stage - One tions (DTPM ne pr 2021-08-1 Travaux de construction de l' IDA / 66650 A posteriori Demande de prix Open - National 135,632.00 135,632.00 Signé 2020-12-26 2021-02-20 2020-12-07 ent Generation Envelope ovenant pas de la 9 EP TSHINSAMBI/KANANGA (0 Banque) 12) Demande de cota ZR-FSRDC-236395-CW-RFQ / 1. Support to Community Re Single Stage - One tions (DTPM ne pr 2021-08-1 Travaux de construction de l' IDA / 66650 A posteriori Demande de prix Open - National 127,655.00 127,655.24 Signé 2020-12-22 2021-02-16 2020-12-07 silience Envelope ovenant pas de la 5 E.P DIKU/KANANGA (013) Banque) Demande de cota ZR-FSRDC-236542-CW-RFQ / 1. Support to Community Re Single Stage - One tions (DTPM ne pr 2021-08-1 Travaux de construction de l' IDA / 66650 A posteriori Demande de prix Open - National 132,095.59 132,095.59 Signé 2020-12-23 2021-02-17 2020-12-07 silience Envelope ovenant pas de la 6 EP TOSALISANAI/KANANGA (0 Banque) 14) Demande de cota ZR-FSRDC-236396-CW-RFQ / 1. Support to Community Re Single Stage - One tions (DTPM ne pr 2021-08-1 Travaux de construction de l' IDA / 66650 A posteriori Demande de prix Open - National 127,526.39 138,724.34 Signé 2020-12-18 2021-02-12 2020-12-07 silience Envelope ovenant pas de la 1 EP DISANKA/KANANGA (015) Banque) Demande de cota ZR-FSRDC-236141-CW-RFQ / 1. Support to Community Re Single Stage - One tions (DTPM ne pr 2021-08-1 Travaux de construction de l' IDA / 66650 A posteriori Demande de prix Open - National 141,423.00 141,423.19 Signé 2020-12-26 2021-02-20 2020-12-07 silience Envelope ovenant pas de la 9 EP Mgr BAKAFUA/KANANGA ( Banque) 016) Demande de cota ZR-FSRDC-236283-CW-RFQ / 1. Support to Community Re Single Stage - One tions (DTPM ne pr 2021-08-1 Travaux de construction de l' IDA / 66650 A posteriori Demande de prix Open - National 141,423.00 141,423.19 Signé 2020-12-26 2021-02-20 2020-12-07 silience Envelope ovenant pas de la 9 E.P TSHIBASHI/KANANGA (01 Banque) 7) Demande de cota ZR-FSRDC-236354-CW-RFQ / 1. Support to Community Re Single Stage - One tions (DTPM ne pr 2021-08-1 Travaux de construction de l' IDA / 66650 A posteriori Demande de prix Open - National 131,171.95 132,171.95 Signé 2020-12-26 2021-02-20 2020-12-07 silience Envelope ovenant pas de la 9 EP BUSHALA BUAMBA/KANAN Banque) GA (018) Demande de cota ZR-FSRDC-236521-CW-RFQ / 1. Support to Community Re Single Stage - One tions (DTPM ne pr 2021-08-1 Travaux de construction de l' IDA / 66650 A posteriori Demande de prix Open - National 128,306.16 128,306.16 Signé 2020-12-23 2021-02-17 2020-12-14 silience Envelope ovenant pas de la 6 EP NDESHA LUSAMBO/KANA Banque) NGA (019) Demande de cota ZR-FSRDC-236284-CW-RFQ / 1. Support to Community Re Single Stage - One tions (DTPM ne pr 2021-08-1 Travaux de construction de l' IDA / 66650 A posteriori Demande de prix Open - National 132,871.00 132,870.99 Signé 2020-12-23 2021-02-17 2020-12-14 silience Envelope ovenant pas de la 6 E.P BAOLONGO/KANANGA (0 Banque) 20) Demande de cota ZR-FSRDC-236507-CW-RFQ / 1. Support to Community Re Single Stage - One tions (DTPM ne pr 2021-08-1 Travaux de construction de l' IDA / 66650 A posteriori Demande de prix Open - National 128,246.00 128,245.70 Signé 2020-12-23 2021-02-17 2020-12-14 silience Envelope ovenant pas de la 6 EP TSHISUMBU/KANANGA (02 Banque) 1) Demande de cota ZR-FSRDC-236085-CW-RFQ / 1. Support to Community Re Single Stage - One tions (DTPM ne pr En cours d' 2021-08-1 Travaux de construction de l' IDA / 66650 A posteriori Demande de prix Limited 128,434.31 0.00 2020-12-26 2021-02-20 silience Envelope ovenant pas de la exécution 9 EP DIKU DIETU/KANANGA (02 Banque) 2) Demande de cota ZR-FSRDC-236508-CW-RFQ / 1. Support to Community Re Single Stage - One tions (DTPM ne pr 2021-08-2 Travaux de construction de l' IDA / 66650 A posteriori Demande de prix Open - National 132,127.21 132,127.21 Signé 2020-12-27 2021-02-21 2020-12-14 silience Envelope ovenant pas de la 0 EP DIAKAJA/KANANGA (023) Banque) Demande de cota ZR-FSRDC-236286-CW-RFQ / 1. Support to Community Re Single Stage - One tions (DTPM ne pr 2021-08-1 Travaux de construction de l' IDA / 66650 A posteriori Demande de prix Open - National 126,551.11 126,551.11 Signé 2020-12-22 2021-02-16 2020-12-14 silience Envelope ovenant pas de la 5 E.P TUYA KUMPALA/KANANG Banque) A (024) Demande de cota ZR-FSRDC-236156-CW-RFQ / 1. Support to Community Re Single Stage - One tions (DTPM ne pr 2021-08-1 Travaux de construction de l' IDA / 66650 A posteriori Demande de prix Open - National 134,597.49 134,597.49 Signé 2020-12-23 2021-02-17 2020-12-14 silience Envelope ovenant pas de la 6 EP SANKAYI/KANANGA (025) Banque) Demande de cota ZR-FSRDC-236361-CW-RFQ / 1. Support to Community Re Single Stage - One tions (DTPM ne pr En attente 2021-08-2 Travaux de construction EP D IDA / 66650 A posteriori Demande de prix Open - National 135,000.00 0.00 2021-01-05 2021-03-02 silience Envelope ovenant pas de la d'exécution 9 ikongayi 2/Kananga Banque) ZR-FSRDC-239808-CW-RFQ / Demande de cota Construction de l'EP BISHIYA/ 1. Support to Community Re Single Stage - One tions (DTPM ne pr En attente 2022-03-0 Village KALUMBA MANDE/Gro IDA / 66650 A posteriori Demande de prix Limited 125,000.00 0.00 2021-07-14 2021-09-08 silience Envelope ovenant pas de la d'exécution 7 upement BENA NGOYI/KALU Banque) MBA/Secteur DIBANDA_KC ZR-FSRDC-239813-CW-RFQ / Demande de cota Construction de l'EP MUAKAJI 1. Support to Community Re Single Stage - One tions (DTPM ne pr En attente 2022-03-1 /Village TSHIMANGA NFUMA/ IDA / 66650 A posteriori Demande de prix Limited 125,000.00 0.00 2021-07-17 2021-09-11 silience Envelope ovenant pas de la d'exécution 0 Groupement BENA KABIYE/ T Banque) SHIKELE/Secteur DIBANDA_K C ZR-FSRDC-239818-CW-RFQ / Demande de cota Construction de l'EP1 DIBAN 1. Support to Community Re Single Stage - One tions (DTPM ne pr 1,250,000.0 En attente 2022-03-1 DA/Village BUNKONDE/Group IDA / 66650 A posteriori Demande de prix Limited 0.00 2021-07-19 2021-09-13 silience Envelope ovenant pas de la 0 d'exécution 2 ement BENE KALUBI/ BAKUA Banque) NDOLO/Secteur DIBANDA_KC Page 1 ZR-FSRDC-239821-CW-RFQ / Demande de cota Construction de l'EP EP NDIB 1. Support to Community Re Single Stage - One tions (DTPM ne pr En attente 2022-03-1 U KALAMBA/Village TSHILOL IDA / 66650 A posteriori Demande de prix Limited 125,000.00 0.00 2021-07-20 2021-09-14 silience Envelope ovenant pas de la d'exécution 3 O/Groupement BAKUA NDAY Banque) E/Secteur KASANGIDI_KC ZR-FSRDC-239825-CW-RFQ / Demande de cota Construction de l'EP LUAJA/Vi 1. Support to Community Re Single Stage - One tions (DTPM ne pr En attente 2022-03-1 IDA / 66650 A posteriori Demande de prix Limited 125,000.00 0.00 2021-07-18 2021-09-12 llage BENA NGANA/Groupem silience Envelope ovenant pas de la d'exécution 1 ent BENA NGALA/Secteur KA Banque) SANGIDI_KC ZR-FSRDC-239830-CW-RFQ / Demande de cota Construction de l'EP3 LUKUL 1. Support to Community Re Single Stage - One tions (DTPM ne pr En attente 2022-03-1 IDA / 66650 A posteriori Demande de prix Limited 125,000.00 0.00 2021-07-24 2021-09-18 A/Village BENA NKENU/Group silience Envelope ovenant pas de la d'exécution 7 ement BENA NKENU/Secteur Banque) KASANGIDI_KC ZR-FSRDC-239832-CW-RFQ / Demande de cota Construction de l'EP1 BASAN 1. Support to Community Re Single Stage - One tions (DTPM ne pr En attente 2022-03-1 IDA / 66650 A posteriori Demande de prix Limited 125,000.00 0.00 2021-07-25 2021-09-19 GA/Village KAULU/Groupeme silience Envelope ovenant pas de la d'exécution 8 nt KAULU MIKELE/Secteur KA Banque) SANGIDI_KC ZR-FSRDC-239833-CW-RFQ / Demande de cota Construction de l'EP NTUADIJI 1. Support to Community Re Single Stage - One tions (DTPM ne pr En attente 2022-03-1 LU/Village BAKUA TSHILUND IDA / 66650 A posteriori Demande de prix Limited 125,000.00 0.00 2021-07-25 2021-09-19 silience Envelope ovenant pas de la d'exécution 8 U /NFUAMBA/Groupement BA Banque) KUA TSHILUNDU/ NFUAMBA/S ecteur KASANGIDI_KC ZR-FSRDC-239835-CW-RFQ / Demande de cota Construction de l'EP MAMBAS 1. Support to Community Re Single Stage - One tions (DTPM ne pr En attente 2022-03-1 AKO/Village TSHINEMA BENA IDA / 66650 A posteriori Demande de prix Limited 125,000.00 0.00 2021-07-26 2021-09-20 silience Envelope ovenant pas de la d'exécution 9 MUABA/Groupement BENA M Banque) UAMBA/Secteur KASANGIDI_K C ZR-FSRDC-239837-CW-RFQ / Demande de cota Construction de l'EP TSHIMAK 1. Support to Community Re Single Stage - One tions (DTPM ne pr En attente 2022-03-2 AKA/Village MUPOYI/Groupe IDA / 66650 A posteriori Demande de prix Limited 125,000.00 0.00 2021-07-27 2021-09-21 silience Envelope ovenant pas de la d'exécution 0 ment BAKUA NKATE (MUPOYI Banque) )/Secteur KASANGIDI_KC Demande de cota ZR-FSRDC-239867-CW-RFQ / Single Stage - One tions (DTPM ne pr En attente 2022-02-2 Extension Bureaux de l'Anten IDA / 66650 4. Project Management A posteriori Demande de prix Limited 184,000.00 0.00 2021-07-05 2021-08-30 Envelope ovenant pas de la d'exécution 6 ne_Kananga Banque) ZR-FSRDC-243751-CW-RFQ / Demande de cota Construction de sept (7) écol 1. Support to Community Re Single Stage - One tions (DTPM ne pr 1,050,000.0 En attente 2022-04-1 IDA / 66650 A posteriori Demande de prix Limited 0.00 2021-08-17 2021-10-12 es dans le Secteur de KASAN silience Envelope ovenant pas de la 0 d'exécution 0 GIDI en 7 lots distincts Banque) ZR-FSRDC-264810-GO-RFQ / (2): Construction de quatre ( 4) centres de santé dans le s Demande de cota ecteurs Secteurs de Dibataie 1. Support to Community Re Single Stage - One tions (DTPM ne pr En attente 2022-11-1 et Kamuandu / Kasaï Central IDA / 66650 A posteriori Demande de prix Limited 500,000.00 0.00 2022-03-20 2022-05-15 silience Envelope ovenant pas de la d'exécution 1 subdivisés en 4 lots: Banque) - Lot 1 : CS Ngalampata, - Lot 2: CS Bena Kazadi, - Lot 3: CS Kankuku, - Lot 4: CS Mutefu ZR-FSRDC-264813-CW-RFQ / (3): Construction de cinq (5) écoles primaires dans le Sect Demande de cota eurs de Dibataie / Kasaï Cent 1. Support to Community Re Single Stage - One tions (DTPM ne pr En attente 2022-11-1 ral subdivisées en 5 lots : - - IDA / 66650 A posteriori Demande de prix Limited 625,000.00 0.00 2022-03-20 2022-05-15 silience Envelope ovenant pas de la d'exécution 1 Lot 1: EP Ntenda, Banque) - Lot 2: EP Milayi, - Lot 3: EP Lutambi, - Lot 4: EP Mofuayi, - Lot 5: Bena Kazadi ZR-FSRDC-264814-CW-RFQ / (4): Construction de quatre ( 4) écoles primaires dans le S Demande de cota ecteurs de Dibataie / Kasaï C 1. Support to Community Re Single Stage - One tions (DTPM ne pr En attente 2022-11-1 entral subdivisées en 4 lots : IDA / 66650 A posteriori Demande de prix Limited 500,000.00 0.00 2022-03-20 2022-05-15 silience Envelope ovenant pas de la d'exécution 1 - Lot 1: EP Mbondo, Banque) - Lot 2: EP Lusambi, - Lot 3: EP Tudiku, - Lot 4: EP Sankayi ZR-FSRDC-264815-CW-RFQ / (5): Construction de quatre ( 4) écoles primaires dans le S Demande de cota ecteurs de Dibataie et Kamu 1. Support to Community Re Single Stage - One tions (DTPM ne pr En attente 2022-11-1 andu / Kasaï Central subdivis IDA / 66650 A posteriori Demande de prix Limited 500,000.00 0.00 2022-03-21 2022-05-16 silience Envelope ovenant pas de la d'exécution 2 ées en 4 lots : Banque) - Lot 1: EP Kapiku, - Lot 2: Mpunga, - Lot 3: EP Tudilame, - Lot 4: EP Kafudu ZR-FSRDC-264818-CW-RFQ / (6): Construction de de quatr e (4) écoles primaires dans le Demande de cota s Secteurs de Dibataie et Ka 1. Support to Community Re Single Stage - One tions (DTPM ne pr En attente 2022-11-1 muandu / Kasaï Central subdi IDA / 66650 A posteriori Demande de prix Limited 500,000.00 0.00 2022-03-20 2022-05-15 silience Envelope ovenant pas de la d'exécution 1 visées en 4 lots : Banque) - Lot 1: EP Kabonge, - lot 2: EP Kanuamayi, - Lot 3 : EP Dibatayi, - Lot 4: EP Tshitokololo ZR-FSRDC-264819-CW-RFQ / (7): Quatre (4) forages méca niques dans les Secteurs de Demande de cota Dibataie et Kamuandu / Kasa 1. Support to Community Re Single Stage - One tions (DTPM ne pr En attente 2022-11-1 ï Central subdivisées en 4 lot IDA / 66650 A posteriori Demande de prix Limited 500,000.00 0.00 2022-03-20 2022-05-15 silience Envelope ovenant pas de la d'exécution 1 s: Banque) - Lot 1: Kabeya lumbu, - Lot 2: Ntambwe Tshintanku, - Lot 3: Bena Nsamba - Lot 4: Mbulungu ZR-FSRDC-264805-CW-RFQ / (1): Construction de 4 centre s de santé Secteur de Dibatai Demande de cota e / Kasaï Central subdivisés e 1. Support to Community Re Single Stage - One tions (DTPM ne pr En attente 2022-11-2 IDA / 66650 A posteriori Demande de prix Limited 500,000.00 0.00 2022-04-05 2022-05-31 n 4 lots : silience Envelope ovenant pas de la d'exécution 7 - Lot 1: CS Nkufulu, Banque) - Lot 2: CS Ntambue Kayemb e, - Lot 3: CS Kamuina Nsapo, - Lot 4: CS Kasende ZR-FSRDC-274708-CW-RFQ / (6) Construction des IDB aux quartiers (LEMBABO, MUZI-P Demande de cota ELA, 1. Support to Community Re Single Stage - One tions (DTPM ne pr En cours d' 2023-02-2 IDA / 66650 A posteriori Demande de prix Limited 650,000.00 0.00 2022-07-05 2022-08-30 SUKISA, KINDIA et SIMBILIAB silience Envelope ovenant pas de la exécution 6 O)-Lot 1: E.P MUDJUMBE EPAI Banque) NETO- Lot 2: E.P 1 BUNIA- Lot 3: E.P SUKISA - Lot 4: E.P MW ANGA- Lot 5: E.P EP NYAKEZI _ ITURI ZR-FSRDC-274709-CW-RFQ / (7) Construction des IDB aux quartiers (BEMBEY, LUMUMB Demande de cota A, RWAMBUZI-BENI, SALONG 1. Support to Community Re Single Stage - One tions (DTPM ne pr En cours d' 2023-02-2 O et dans le groupement BA IDA / 66650 A posteriori Demande de prix Limited 650,000.00 0.00 2022-07-05 2022-08-30 silience Envelope ovenant pas de la exécution 6 BUCHUKA) - Lot .1: E.P INGA Banque) NIZI- Lot 2: E.P.1 MURONGO- Lot .3: E.P SIMBILYABO- Lot 4 : E.P 4 NYAKASANZA- Lot 5: E P. BUNDIKASA_ ITURI ZR-FSRDC-274712-CW-RFQ / (8) Construction IDB quartier s (BIGO, HOHO, OPAS, KASEG Demande de cota WA et DELE) Lot 1 : Centre d 1. Support to Community Re Single Stage - One tions (DTPM ne pr En cours d' 2023-02-2 IDA / 66650 A posteriori Demande de prix Limited 650,000.00 0.00 2022-07-05 2022-08-30 e santé BIGO - Lot .2 : Centre silience Envelope ovenant pas de la exécution 6 de santé HOHO- Lot .3 : Cent Banque) re de santé OPAS- Lot .4 : Ce ntre de santé KASEGWA- Lot 5: Centre de santé de _ ITUR I ZR-FSRDC-274713-CW-RFQ / (9) Construction des IDB aux quartiers (TSERE, LENGABO, Demande de cota BABULABA, BEDU EZEKERE e 1. Support to Community Re Single Stage - One tions (DTPM ne pr En cours d' 2023-02-2 IDA / 66650 A posteriori Demande de prix Limited 650,000.00 0.00 2022-07-05 2022-08-30 t SALONGO) Lot 1: EP. MAKI silience Envelope ovenant pas de la exécution 6 MBUDHA-Lot .2: EP. MBUNYA Banque) -Lot 3: EP.2 OLENYAMA-Lot.4: EP.BUY SABUNI-Lot 5: Centre de santé SALONGO_ ITURI ZR-FSRDC-274715-CW-RFQ / (10) Construction des IDB au x quartiers (NDIBA-KODU, LU Demande de cota VANGIRE, RWAMBUZI-FICHA 1. Support to Community Re Single Stage - One tions (DTPM ne pr En cours d' 2023-02-2 IDA / 66650 A posteriori Demande de prix Limited 520,000.00 0.00 2022-07-05 2022-08-30 NA et NGEZI) -Lot 1 : Centre silience Envelope ovenant pas de la exécution 6 de santé NDIBE-Lot.2 : Centr Banque) e de santé KATOTO-Lot : 2 Fo rages à RWAMBUZI-FICHANA- Lot.4 : 4 Forages à NGEZI- IT URI Page 2 ZR-FSRDC-275582-CW-RFQ / (11) Construction des IDB au x quartiers (NYAKASANZA I, Demande de cota NYAKASANZA II et SAIO) 1. Support to Community Re Single Stage - One tions (DTPM ne pr En attente 2023-02-2 Lot1: 1 Forages dans le quart IDA / 66650 A posteriori Demande de prix Limited 390,000.00 0.00 2022-07-05 2022-08-30 silience Envelope ovenant pas de la d'exécution 6 ier NYAKASANZA I -Lot 2: 2 F Banque) orages dans le quartier NYAK ASANZA II-Lot 2 Forage dans le quartier SAIO- V_BUNIA_IT URI ZR-FSRDC-275584-CW-RFQ / (12) Construction des IDB au x quartiers (RWANGOLE, YAM Demande de cota BI-YAYA et BANKOKO) 1. Support to Community Re Single Stage - One tions (DTPM ne pr En attente 2023-02-2 Lot 1: 1 Forages dans le quar IDA / 66650 A posteriori Demande de prix Limited 390,000.00 0.00 2022-07-05 2022-08-30 silience Envelope ovenant pas de la d'exécution 6 tier RWANGOLE;-Lot 2: 3 For Banque) ages dans le quartier YAMBI- YAYA -Lot 3: 4 Forages dans le qua rtier BANKOKO_ V_BUNIA_ IT URI ZR-FSRDC ITURI-319845-CW -RFQ / Construction de 4 EP, 1 CS et 5 BCLD dans le territ oire de Mahagi, en 5 lots ; - EP SII et 1 BCLD (Gp Ngote) Demande de cota - EP Rabu et 1 BCLD (Gp Niok 1. Support to Community Re Single Stage - One tions (DTPM ne pr En attente 2023-08-1 IDA / 66650 A posteriori Demande de prix Limited 700,000.00 0.00 2022-12-17 2023-02-11 a) silience Envelope ovenant pas de la d'exécution 0 - EP Lero et 1 BCLD (Gp Djup Banque) anyalengi) - EP Simbi-Lari et 1 BCLD (Gp Rhona) - CS Alla-Wimoo et 1 BCLD (G p Paker) ZR-FSRDC ITURI-319848-CW -RFQ / Construction de 5 fora ges et 5 BCLD dans la ville d Demande de cota e Mahagi, en 5 lots: 1. Support to Community Re Single Stage - One tions (DTPM ne pr En attente 2023-08-1 - 1 Forage et 1 BCLD (Q. Ang IDA / 66650 A posteriori Demande de prix Limited 700,000.00 0.00 2022-12-17 2023-02-11 silience Envelope ovenant pas de la d'exécution 0 wel) ; Banque) - 1 Forage et 1 BCLD (Q. Lac Allu) ; - 1 Forage et 1 BCLD (Q. Jum ba); - 1 Forage et 1 BCLD (Q. Ma ZR-FSRDC ITURI-319852-CW mba) -RFQ / Construction - 1 Forage et 1 BCLD de fora 5 Riha (Q. 1) et 5 BCLD dans le territoi ges re et les Q. de Mahagi, en 5 l Demande de cota ots : 1. Support to Community Re Single Stage - One tions (DTPM ne pr En attente 2023-08-1 IDA / 66650 A posteriori Demande de prix Limited 700,000.00 0.00 2022-12-17 2023-02-11 - 1 Forage et 1 BCLD (Q. Drii) silience Envelope ovenant pas de la d'exécution 0 ; Banque) - 1 Forage et 1 BCLD (Q. Mah agi); - 1 Forage et 1 BCLD (Q. Adu Centre); - 1 Forage et 1 BCLD (G. Pam ZR-FSRDC ITURI-319868-CW itu) -RFQ / Construction - 1 Forage et 1 BCLD Forage, 1(G.Akar a)EP, 1 CS et 5 BCLD dans le 3 T. et les Q de Mahagi, en 5 lo Demande de cota ts: 1. Support to Community Re Single Stage - One tions (DTPM ne pr En attente 2023-08-1 IDA / 66650 A posteriori Demande de prix Limited 700,000.00 0.00 2022-12-17 2023-02-11 - 1 Forage et 1 BCLD (Q. Ga silience Envelope ovenant pas de la d'exécution 0 mba) Banque) - EP Uriko et 1 BCLD (Q. Ridh a 2) - EP Agape et 1 BCLD (Q. Nju ra) - EP Kiangani et 1 BCLD (Q. ZR-FSRDC ITURI-319876-CW Madipoyi) -RFQ / Construction - CS Guna et 1 BCLD de EP, 3 Paro (G. de mbo) 2 CS et 5 BCLD dans le T. et les Q. de Mahagi, en 5 lots : Demande de cota - EP Ajoba et 1 BCLD (G. Gos 1. Support to Community Re Single Stage - One tions (DTPM ne pr En attente 2023-08-1 IDA / 66650 A posteriori Demande de prix Limited 700,000.00 0.00 2022-12-17 2023-02-11 si); silience Envelope ovenant pas de la d'exécution 0 - EP Alingongo et 1 BCLD (G. Banque) Pakwo) - EP Catholiki et 1 BCLD (G. U moyo) - CS Pono Avar et 1 BCLD (G. Palara Pono) - CS Adu et 1 BCLD (Q. A ZR-FSRDC ITURI-319885-CW -RFQ / Construction de 4 EP, de 1 forage et de 5 BCLD dan s le territoire de Mahagi, en 5 Demande de cota lots : 1. Support to Community Re Single Stage - One tions (DTPM ne pr En attente 2023-08-1 IDA / 66650 A posteriori Demande de prix Limited 700,000.00 0.00 2022-12-17 2023-02-11 - EP Cana Both et 1 BCLD (G. silience Envelope ovenant pas de la d'exécution 0 Alur) Banque) - EP Muke et 1 BCLD (G. Sabo ) - EP Jalbonyo et 1 BCLD (G. P agassa) - EP Wi et 1 BCLD (G. Agba) -ZR-FSRDC 1 Forage et ITURI-319886-CW 1 BCLD (G. Urii) -RFQ / Construction de 2 EP, de 2 forages, de 1 CS et de 5 BCLD dans le T. de Mahagi, e Demande de cota n 5 lots : 1. Support to Community Re Single Stage - One tions (DTPM ne pr En attente 2023-08-1 IDA / 66650 A posteriori Demande de prix Limited 700,000.00 0.00 2022-12-17 2023-02-11 - EP Aterlemba et 1 BCLD (G. silience Envelope ovenant pas de la d'exécution 0 Kusu) Banque) - EP Aupa et 1 BCLD (G. Aupa ) - 1 Forage et 1 BCLD (G. Nda ma) - 1 Forage et 1 BCLD (Q. Angi ZR-FSRDC ITURI-319895-CW raju) -RFQ - 1 CS Construction / Agatara de 2 EP, et 1 BCLD (Ko c L 1 forage, de 1 CS et de 4 de BCLD dans le territoire de Ma Demande de cota hagi, en 4 lots: : 1. Support to Community Re Single Stage - One tions (DTPM ne pr En attente 2023-08-1 - EP Undhee et 1 BCLD (G. An IDA / 66650 A posteriori Demande de prix Limited 560,000.00 0.00 2022-12-17 2023-02-11 silience Envelope ovenant pas de la d'exécution 0 gu'uza Paiem) Banque) - 1 Forage et 1 BCLD (G. Ang u'uza Pajulu) - EP Dzangali et 1 BCLD (G. S hari) - CS Mahagi et 1 BCLD (G. Ju pasonge) ZR-FSRDC ITURI-319904-CW -RFQ / Construction de 5 EP e t de 5 BCLD dans le T. d’Irum u, en 5 lots : - EP Muzora et 1 BCLD (G. Ba Demande de cota biase) 1. Support to Community Re Single Stage - One tions (DTPM ne pr En attente 2023-08-1 IDA / 66650 A posteriori Demande de prix Limited 700,000.00 0.00 2022-12-17 2023-02-11 - EP 1 Kasenyi et 1 BCLD (G. silience Envelope ovenant pas de la d'exécution 0 Bangungu) Banque) - EP Kabona et 1 BCLD (G. Bo loma) - EP Bukiringi et 1 BCLD (G. B ukiringi) - EP Kyaireta et 1 BCLD (G. B oga Centre) ZR-FSRDC ITURI-319908-CW -RFQ / Construction de 1 EP, de 1 forage et de 2 BCLD dan Demande de cota s le territoire d’Irumu, en 2 lo 1. Support to Community Re Single Stage - One tions (DTPM ne pr En attente 2023-08-1 IDA / 66650 A posteriori Demande de prix Limited 280,000.00 0.00 2022-12-17 2023-02-11 ts : silience Envelope ovenant pas de la d'exécution 0 - Lot 1: EP Kiangela et 1 BCL Banque) D (G. Rubingo) ; - Lot 2: 1 Forage et 1BCLD (G . Beiziha) ZR-FSRDC ITURI-319910-CW -RFQ / Construction de 2 EP e Demande de cota t 2 BCLD dans le territoire de 1. Support to Community Re Single Stage - One tions (DTPM ne pr En attente 2023-08-1 Djugu, en 2 lots : IDA / 66650 A posteriori Demande de prix Limited 280,000.00 0.00 2022-12-17 2023-02-11 silience Envelope ovenant pas de la d'exécution 0 - Lot 1: EP Balikodra et 1 BCL Banque) D (G. Lingo) ; - Lot 2: EP Zubulu et 1 BCLD (G. Tchomia) GOODS Activity Reference No. / Bid Evaluation Repor Loan / Credit N Market Approac Procurement Pr Prequalification Estimated Am Actual Amount Process St Draft Pre-qualificatio Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission Description Component Review Type Method t and Recommendati Signed Contract Contract Completion o. h ocess (Y/N) ount (US$) (US$) atus n Documents ation Report ent / Justification Notice / Invitation s Issued / Opening / Minutes on for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ZR-FSRDC-232724-GO-RFQ / Acquisition des outillages (Pe 2. Livelihoods and Employm Single Stage - One En attente d' tits matériels) dans le cadre IDA / 66650 A posteriori Demande de prix Limited 30,000.00 0.00 2021-09-05 2021-10-31 2022-04-29 ent Generation Envelope exécution de mise en œuvre des chanti ers Thimo/cash for work à Ka nanga (Kit d’urgence) ZR-FSRDC-232732-GO-RFQ / Acquisition des équipements de protection individuelle (EP 2. Livelihoods and Employm Single Stage - One En attente d' IDA / 66650 A posteriori Demande de prix Limited 50,000.00 0.00 2021-09-05 2021-10-31 2022-04-29 I) dans le cadre de mise en ent Generation Envelope exécution œuvre des chantiers Thimo/c ash for work à Kananga (vag ue 1) Page 3 ZR-FSRDC-232737-GO-RFQ / Acquisition des outillages (Pe 2. Livelihoods and Employm Single Stage - One En attente d' tits matériels) dans le cadre IDA / 66650 A posteriori Demande de prix Limited 270,000.00 0.00 2021-09-05 2021-10-31 2022-04-29 ent Generation Envelope exécution de mise en œuvre des chanti ers Thimo/cash for work à Ka nanga (vague 1) en 9 lots ZR-FSRDC-232772-GO-RFQ / Fourniture de la connexion In Single Stage - One En attente d' IDA / 66650 4. Project Management A posteriori Demande de prix Limited 20,000.00 0.00 2021-06-13 2021-08-08 2022-02-04 ternet et Interphones en fave Envelope exécution ur du projet STEP II ZR-FSRDC-232775-GO-RFQ / Single Stage - One Achat 11 Tablettes enquêteu IDA / 66650 4. Project Management A posteriori Demande de prix Limited 3,300.00 1,760.00 Signé 2021-06-06 2021-05-26 2021-08-01 2021-06-18 2022-01-28 Envelope rs TSHIMBULU ET DIBAYA CE NTRE ZR-FSRDC-232780-GO-RFQ / Acquisition des outillages (Pe 2. Livelihoods and Employm Single Stage - One En attente d' tits matériels) dans le cadre IDA / 66650 A posteriori Demande de prix Limited 30,000.00 0.00 2021-10-05 2021-11-30 2022-05-29 ent Generation Envelope exécution de mise en œuvre des chanti ers Thimo/cash for work à TS HIMBULU ZR-FSRDC-232781-GO-RFQ / Acquisition des équipements 2. Livelihoods and Employm Single Stage - One En attente d' de protection individuelle (EP IDA / 66650 A posteriori Demande de prix Limited 30,000.00 0.00 2021-10-05 2021-11-30 2022-05-29 ent Generation Envelope exécution I) dans le cadre de mise en œuvre des chantiers Thimo/c ash for work à TSHIMBULU ZR-FSRDC-232794-GO-RFQ / Acquisition des outillages (Pe 2. Livelihoods and Employm Single Stage - One En attente d' tits matériels) dans le cadre IDA / 66650 A posteriori Demande de prix Limited 35,000.00 0.00 2021-10-05 2021-11-30 2022-05-29 ent Generation Envelope exécution de mise en œuvre des chanti ers Thimo/cash for work à DI BAYA ZR-FSRDC-232805-GO-RFQ / Acquisition des équipements 2. Livelihoods and Employm Single Stage - One En attente d' de protection individuelle (EP IDA / 66650 A posteriori Demande de prix Limited 35,000.00 0.00 2021-10-05 2021-11-30 2022-05-29 ent Generation Envelope exécution I) dans le cadre de mise en œuvre des chantiers Thimo/c ash for work à DIBAYA ZR-FSRDC-232898-GO-RFQ / 1. Support to Community Re Single Stage - One En attente d' Fourniture des mobiliers pour IDA / 66650 A posteriori Demande de prix Limited 75,000.00 0.00 2021-08-04 2021-09-29 2022-03-28 silience Envelope exécution les 5 EP de Tshibulu ( 5 lots) ZR-FSRDC-232899-GO-RFQ / 1. Support to Community Re Single Stage - One En attente d' Fourniture des mobiliers pour IDA / 66650 A posteriori Demande de prix Limited 90,000.00 0.00 2021-08-04 2021-09-29 2022-03-28 silience Envelope exécution les 6 EP de DIBAYA ( 6 lots) ZR-FSRDC-232764-GO-RFQ / Acquisition des outillages (Pe 2. Livelihoods and Employm Single Stage - One En attente d' tits matériels) dans le cadre IDA / 66650 A posteriori Demande de prix Limited 100,000.00 0.00 2021-09-05 2021-10-31 2022-04-29 ent Generation Envelope exécution de mise en œuvre des chanti ers Thimo/cash for work à Ka nanga (vague 3) en 9 lots ZR-FSRDC-232755-GO-RFQ / Acquisition des équipements de protection individuelle (EP 2. Livelihoods and Employm Single Stage - One En attente d' IDA / 66650 A posteriori Demande de prix Limited 100,000.00 0.00 2021-09-05 2021-10-31 2022-04-29 I) dans le cadre de mise en ent Generation Envelope exécution œuvre des chantiers Thimo/c ash for work à Kananga (vag ue 3) en 9 lots ZR-FSRDC-236168-GO-RFQ / Fourniture d'équipements /m 2. Livelihoods and Employm Single Stage - One En attente d' IDA / 66650 A posteriori Demande de prix Limited 12,600.00 0.00 2021-02-05 2021-04-02 2021-09-29 obilier scolaire l'EP 2 LUNGA ent Generation Envelope exécution NDU/KANANGA (001) ZR-FSRDC-236139-GO-RFQ / Fourniture d'équipements /m 2. Livelihoods and Employm Single Stage - One En attente d' IDA / 66650 A posteriori Demande de prix Limited 12,600.00 0.00 2021-02-05 2021-04-02 2021-09-29 obilier scoalire l'EP NGIDILAYI ent Generation Envelope exécution /KANANGA (002) ZR-FSRDC-236101-GO-RFQ / Fourniture d'équipements /m 2. Livelihoods and Employm Single Stage - One En attente d' IDA / 66650 A posteriori Demande de prix Limited 12,600.00 0.00 2021-02-05 2021-04-02 2021-09-29 obilier scoalire l'EP ARC-EN-C ent Generation Envelope exécution IEL/KANANGA (003) ZR-FSRDC-236158-GO-RFQ / Fourniture d'équipements /m 2. Livelihoods and Employm Single Stage - One En attente d' IDA / 66650 A posteriori Demande de prix Limited 12,600.00 0.00 2021-02-05 2021-04-02 2021-09-29 obilier scoalire l'E.P 1 LUMUM ent Generation Envelope exécution BA/KANANGA (004) ZR-FSRDC-236105-GO-RFQ / Fourniture d'équipements /m 2. Livelihoods and Employm Single Stage - One En attente d' IDA / 66650 A posteriori Demande de prix Limited 12,600.00 0.00 2021-02-05 2021-04-02 2021-09-29 obilier scoalire l'EP MUINDIDI/ ent Generation Envelope exécution KANANGA (005) ZR-FSRDC-236043-GO-RFQ / Fourniture d'équipements /m 1. Support to Community Re Single Stage - One En attente d' IDA / 66650 A posteriori Demande de prix Limited 12,600.00 0.00 2021-02-05 2021-04-02 2021-09-29 obilier scoalire l'EP 2 MUKOL silience Envelope exécution ESHI/KANANGA (006) ZR-FSRDC-236387-GO-RFQ / Fourniture d'équipements /m 1. Support to Community Re Single Stage - One En attente d' IDA / 66650 A posteriori Demande de prix Limited 12,600.00 0.00 2021-02-05 2021-04-02 2021-09-29 obilier scolaire l'EP KAPAJIKA/ silience Envelope exécution KANANGA (007) ZR-FSRDC-236042-GO-RFQ / Fourniture d'équipements /m 1. Support to Community Re Single Stage - One En attente d' IDA / 66650 A posteriori Demande de prix Limited 12,600.00 0.00 2021-02-05 2021-04-02 2021-09-29 obilier scolaire l'E.P KANDIKU silience Envelope exécution /KANANGA (008) ZR-FSRDC-236151-GO-RFQ / Fourniture d'équipements /m 2. Livelihoods and Employm Single Stage - One En attente d' IDA / 66650 A posteriori Demande de prix Limited 12,600.00 0.00 2021-02-05 2021-04-02 2021-09-29 obilier scolaire l'EP MUFIMISH ent Generation Envelope exécution I/KANANGA (009) ZR-FSRDC-236408-GO-RFQ / Fourniture d'équipements /m 1. Support to Community Re Single Stage - One En attente d' IDA / 66650 A posteriori Demande de prix Limited 12,600.00 0.00 2021-02-05 2021-04-02 2021-09-29 obilier scoalire l'EP MUDIDIKE silience Envelope exécution /KANANGA (010) ZR-FSRDC-236051-GO-RFQ / Fourniture d'équipements /m 1. Support to Community Re Single Stage - One En attente d' IDA / 66650 A posteriori Demande de prix Limited 12,600.00 0.00 2021-02-05 2021-04-02 2021-09-29 obilier scoalire l'EP NGANZA/ silience Envelope exécution KANANGA (011) ZR-FSRDC-236170-GO-RFQ / Fourniture d'équipements /m 2. Livelihoods and Employm Single Stage - One En attente d' IDA / 66650 A posteriori Demande de prix Limited 12,495.00 0.00 2021-02-05 2021-04-02 2021-09-29 obilier scoalire l'EP TSHINSA ent Generation Envelope exécution MBI/KANANGA (012) ZR-FSRDC-236276-GO-RFQ / 2. Livelihoods and Employm Single Stage - One En attente d' Fourniture d'équipements /m IDA / 66650 A posteriori Demande de prix Limited 12,600.00 0.00 2021-02-05 2021-04-02 2021-09-29 ent Generation Envelope exécution obilier scoalire l'E.P DIKU/KA NANGA (013) ZR-FSRDC-236140-GO-RFQ / Fourniture d'équipements /m 2. Livelihoods and Employm Single Stage - One En attente d' IDA / 66650 A posteriori Demande de prix Limited 12,600.00 0.00 2021-02-05 2021-04-02 2021-09-29 obilier scoalire l'EP TOSALISA ent Generation Envelope exécution NAI/KANANGA (014) ZR-FSRDC-236107-GO-RFQ / Fourniture d'équipements /m 2. Livelihoods and Employm Single Stage - One En attente d' IDA / 66650 A posteriori Demande de prix Limited 12,600.00 0.00 2021-02-05 2021-04-02 2021-09-29 obilier scoalire l'EP DISANKA/ ent Generation Envelope exécution KANANGA (015) ZR-FSRDC-236281-GO-RFQ / Fourniture d'équipements /m 2. Livelihoods and Employm Single Stage - One En attente d' IDA / 66650 A posteriori Demande de prix Limited 12,600.00 0.00 2021-02-05 2021-04-02 2021-09-29 obilier scoalire l'EP Mgr BAKA ent Generation Envelope exécution FUA/KANANGA (016) ZR-FSRDC-236391-GO-RFQ / Fourniture d'équipements /m 1. Support to Community Re Single Stage - One En attente d' IDA / 66650 A posteriori Demande de prix Limited 12,600.00 0.00 2021-02-05 2021-04-02 2021-09-29 obilier scoalire l'E.P TSHIBAS silience Envelope exécution HI/KANANGA (017) ZR-FSRDC-236503-GO-RFQ / Fourniture d'équipements /m 1. Support to Community Re Single Stage - One En attente d' IDA / 66650 A posteriori Demande de prix Limited 12,075.00 0.00 2021-02-05 2021-04-02 2021-09-29 obilier scoalire l'EP BUSHALA silience Envelope exécution BUAMBA/KANANGA (018) ZR-FSRDC-236050-GO-RFQ / Fourniture d'équipements /m 1. Support to Community Re Single Stage - One En attente d' IDA / 66650 A posteriori Demande de prix Limited 12,600.00 0.00 2021-02-05 2021-04-02 2021-09-29 obilier scoalire l'EP NDESHA L silience Envelope exécution USAMBO/KANANGA (019) Page 4 ZR-FSRDC-236501-GO-RFQ / Fourniture d'équipements /m 1. Support to Community Re Single Stage - One En attente d' IDA / 66650 A posteriori Demande de prix Limited 12,579.00 0.00 2021-02-05 2021-04-02 2021-09-29 obilier scoalire l'E.P BAOLON silience Envelope exécution GO/KANANGA (020) ZR-FSRDC-236047-GO-RFQ / Fourniture d'équipements /m 1. Support to Community Re Single Stage - One En attente d' IDA / 66650 A posteriori Demande de prix Limited 12,600.00 0.00 2021-02-05 2021-04-02 2021-09-29 obilier scoalire l'EP TSHISUM silience Envelope exécution BU/KANANGA (021) ZR-FSRDC-236389-GO-RFQ / Fourniture d'équipements /m 1. Support to Community Re Single Stage - One En attente d' IDA / 66650 A posteriori Demande de prix Limited 12,600.00 0.00 2021-02-05 2021-04-02 2021-09-29 obilier scoalire l'EP DIKU DIET silience Envelope exécution U/KANANGA (022) ZR-FSRDC-236048-GO-RFQ / 1. Support to Community Re Single Stage - One En attente d' Fourniture d'équipements /m IDA / 66650 A posteriori Demande de prix Limited 12,600.00 0.00 2021-02-05 2021-04-02 2021-09-29 silience Envelope exécution obilier scoalire l'EP DIAKAJA/K ANANGA (023) ZR-FSRDC-236058-GO-RFQ / Fourniture d'équipements /m 1. Support to Community Re Single Stage - One En attente d' IDA / 66650 A posteriori Demande de prix Limited 12,600.00 0.00 2021-02-05 2021-04-02 2021-09-29 obilier scoalire l'E.P TUYA KU silience Envelope exécution MPALA/KANANGA (024) ZR-FSRDC-236393-GO-RFQ / Fourniture d'équipements /m 1. Support to Community Re Single Stage - One En attente d' IDA / 66650 A posteriori Demande de prix Limited 12,600.00 0.00 2021-02-05 2021-04-02 2021-09-29 obilier scoalire l'EP SANKAYI/ silience Envelope exécution KANANGA (025) ZR-FSRDC-236153-GO-RFQ / 2. Livelihoods and Employm Single Stage - One En attente d' Fourniture d'équipements /m IDA / 66650 A posteriori Demande de prix Limited 12,285.00 0.00 2021-02-05 2021-04-02 2021-09-29 ent Generation Envelope exécution obilier scolaire EP Dikongayi 2/KANANGA ZR-FSRDC-236081-GO-RFQ / Fourniture de la limonite dan 2. Livelihoods and Employm Single Stage - One En attente d' IDA / 66650 A posteriori Demande de prix Limited 46,200.00 0.00 2021-04-18 2021-06-13 2021-12-10 s les 27 Sous projets de la vill ent Generation Envelope exécution e de Kananga en Lot unique / KNGA MOF-REF-75 / Acquisition de s EPI complémentaires dans l 2. Livelihoods and Employm Single Stage - One En attente d' e cadre de la mise en œuvre IDA / 66650 A posteriori Demande de prix Limited 3,167.50 0.00 2021-04-18 2021-06-13 2021-12-10 ent Generation Envelope exécution de 5 chantiers de THIMO « ca sh for work » à Kananga / K NGA ZR-FSRDC-236147-GO-RFQ / Acquisition des EPI complém 2. Livelihoods and Employm Single Stage - One En attente d' entaires dans le cadre de la IDA / 66650 A posteriori Demande de prix Limited 3,816.00 0.00 2021-03-16 2021-05-11 2021-11-07 ent Generation Envelope exécution mise en œuvre de 6 chantier s de THIMO « cash for work » à Kananga / KNGA ZR-FSRDC-236320-GO-RFQ / Acquisition des EPI complém 2. Livelihoods and Employm Single Stage - One En attente d' entaires dans le cadre de la IDA / 66650 A posteriori Demande de prix Limited 5,625.00 0.00 2021-03-16 2021-05-11 2021-11-07 ent Generation Envelope exécution mise en œuvre de 6 chantier s de THIMO « cash for work » à Kananga / KNGA ZR-FSRDC-236516-GO-RFQ / Acquisition des EPI dans le ca 2. Livelihoods and Employm Single Stage - One En attente d' dre de la mise en œuvre de 9 IDA / 66650 A posteriori Demande de prix Limited 4,269.00 0.00 2021-03-16 2021-05-11 2021-11-07 ent Generation Envelope exécution chantiers de THIMO « cash fo r work » 0 Kanaga/KNGA ZR-FSRDC-236551-GO-RFQ / Single Stage - One En attente d' Acquisition de trois véhicules IDA / 66650 4. Project Management A posteriori Demande de prix Limited 146,950.00 0.00 2021-03-02 2021-04-27 2021-10-24 Envelope exécution automobiles 4x4 pour le proj et STEP II ZR-FSRDC-239840-GO-RFQ / Fourniture d'équipements/m 1. Support to Community Re Single Stage - One En attente d' obiliers scolaires pour l'EP BI IDA / 66650 A posteriori Demande de prix Limited 39,000.00 0.00 2021-09-06 2021-11-01 2022-04-30 silience Envelope exécution SHIYA, l'EP MUAKAJI et l'EP1 DIBANDA du secteur de DIBA NDA_KC ZR-FSRDC-239842-GO-RFQ / Fourniture d'équipements/m 1. Support to Community Re Single Stage - One En attente d' obiliers scolaires pour l'EP N IDA / 66650 A posteriori Demande de prix Limited 39,000.00 0.00 2021-09-05 2021-10-31 2022-04-29 silience Envelope exécution DIBU KALAMBA, l'EP LUAJA et l'EP LUKULA du secteur de K ASANGIDI_KC ZR-FSRDC-239843-GO-RFQ / Fourniture d'équipements/m obiliers scolaires pour l'EP1 B 1. Support to Community Re Single Stage - One En attente d' IDA / 66650 A posteriori Demande de prix Limited 52,000.00 0.00 2021-09-05 2021-10-31 2022-04-29 ASANGA, l'EP NTUADIJILU, l'E silience Envelope exécution P MAMBASAKO et l'EP TSHIM AKAKA du secteur KASANGIDI _KC ZR-FSRDC-243750-GO-RFQ / Fourniture des mobiliers pour 1. Support to Community Re Single Stage - One En attente d' IDA / 66650 A posteriori Demande de prix Limited 45,000.00 0.00 2021-08-14 2021-10-09 2022-04-07 les EP BISHIYA, EP MUAKAJI e silience Envelope exécution t EP1 DIBANDA dans le secte ur de DIBANDA ZR-FSRDC-243758-GO-RFQ / Fourniture des mobiliers pour les EP NDIBU KALAMBA, EP L 1. Support to Community Re Single Stage - One En attente d' IDA / 66650 A posteriori Demande de prix Limited 105,000.00 0.00 2021-08-21 2021-10-16 2022-04-14 UAJA, EP3 LUKULA, EP1 BAS silience Envelope exécution ANGA, EP NTUADIJILU, EP MA MBASAKO et EP TSHIMAKAKA dans le secteur de KASANGID I ZR-FSRDC-244020-GO-RFQ / Acquisition des Fournitures e 1. Support to Community Re Single Stage - One En attente d' t Equipements médicaux pou IDA / 66650 A posteriori Demande de prix Limited 20,000.00 0.00 2021-08-21 2021-10-16 2022-04-14 silience Envelope exécution r l’Hôpital Général du quartie r de LUKONGA de la ville de Kananga ZR-FSRDC-244050-GO-RFQ / Achat Kit de recrutement des bénéficiaires THIMO de l’ante nne de Kananga/Dibaya et K 2. Livelihoods and Employm Single Stage - One En attente d' IDA / 66650 A posteriori Demande de prix Limited 30,000.00 0.00 2021-08-21 2021-10-16 2022-04-14 ananga/Tshimbulu (tables, ch ent Generation Envelope exécution aises, agrafeuses ciseaux, bâ ches seau en plastique, rame papiers, cartouches, bande d e sécurité….) ZR-FSRDC-244054-GO-RFQ / Fourniture de la limonite pou r les Chantiers THIMO de la vi lle de Kananga et des Cités d 2. Livelihoods and Employm Single Stage - One En attente d' IDA / 66650 A posteriori Demande de prix Limited 100,000.00 0.00 2021-08-21 2021-10-16 2022-04-14 e Tshimbulu et Dibaya, ent Generation Envelope exécution Lot1 : 27 chantiers de Kanan ga et Lot 2 : 11 chantiers de Tshim bulu et Dibaya ZR-FSRDC-244077-GO-RFQ / Achat des Kits Médicaux pour 2. Livelihoods and Employm Single Stage - One En attente d' les bénéficiaires THIMO de la IDA / 66650 A posteriori Demande de prix Limited 100,000.00 0.00 2021-08-21 2021-10-16 2022-04-14 ent Generation Envelope exécution ville de Kananga/Phase2 et d es cités de Dibaya et Tshimb ulu ZR-FSRDC-244110-GO-RFQ / Acquisition des équipements Single Stage - One En attente d' de bureaux et matériels infor IDA / 66650 4. Project Management A posteriori Demande de prix Limited 20,000.00 0.00 2021-08-21 2021-10-16 2022-04-14 Envelope exécution matiques pour les bureaux d e Tshimbulu et Dibaya ZR-FSRDC-257629-GO-RFQ / (1): Acquisition des sacs vide 2. Livelihoods and Employm Single Stage - One En attente d' IDA / 66650 A posteriori Demande de prix Limited 46,000.00 0.00 2021-11-20 2022-01-15 2022-07-14 s pour 38 chantiers THIMO d ent Generation Envelope exécution e Tshimbulu, Dibaya et Kana nga phase 2 ZR-FSRDC-257637-GO-RFQ / (2): Fourniture de la limonite 2. Livelihoods and Employm Single Stage - One En attente d' IDA / 66650 A posteriori Demande de prix Limited 150,000.00 0.00 2021-11-20 2022-01-15 2022-07-14 dans les 11 chantiers THIMO ent Generation Envelope exécution de la ville de Tshimbulu et Di baya, en lot unique. ZR-FSRDC-257639-GO-RFQ / (3): Fourniture de la limonite 2. Livelihoods and Employm Single Stage - One En attente d' IDA / 66650 A posteriori Demande de prix Limited 300,000.00 0.00 2021-11-20 2022-01-15 2022-07-14 dans les 27 chantiers THIMO ent Generation Envelope exécution de la ville de Kananga, en lot unique ZR-FSRDC-257640-GO-RFQ / (5): Acquisition des vétivers, pelouse et bambous, fleur po 2. Livelihoods and Employm Single Stage - One En attente d' IDA / 66650 A posteriori Demande de prix Limited 190,000.00 0.00 2021-11-20 2022-01-15 2022-07-14 ur l'embellissement de la vill ent Generation Envelope exécution e pour 38 chantiers THIMO d e Tshimbulu, Dibaya et Kana nga phase 2 Page 5 ZR-FSRDC-264827-GO-RFQ / (12): Acquisition et livraison 1. Support to Community Re Single Stage - One En attente d' des équipements médicaux p IDA / 66650 A posteriori Demande de prix Limited 112,500.00 0.00 2022-03-19 2022-05-14 2022-11-10 silience Envelope exécution our 9 centres de santé dans deux secteurs au Kasaï Centr al ZR-FSRDC-264841-GO-RFQ / Single Stage - One En attente d' (19): Acquisition de mobiliers IDA / 66650 4. Project Management A posteriori Demande de prix Limited 45,000.00 0.00 2022-03-15 2022-05-10 2022-11-06 Envelope exécution de bureau pour la province d u Kasaï Central ZR-FSRDC-264826-GO-RFQ / (11): Acquisition des éqpts sc olaires pr 17 EP dans 2 secte urs au KC, en 4 lots: Lot1:EP Ntenda,Milayi,Lutam bi,Mofuayi,Bena Kazadi 1. Support to Community Re Single Stage - One En attente d' IDA / 66650 A posteriori Demande de prix Limited 212,500.00 0.00 2022-03-23 2022-05-18 2022-11-14 Lot2:EP Mbondo,Lusambi,Tud silience Envelope exécution iku,Sankayi Lot3:EP Kapiku,Mpunga,Tudil ame,Kafudu Lot4:EP Kabonge,Kanuamayi, Dibatayi,Tshitokololo ZR-FSRDC-272205-GO-RFQ / (26):Acq. EPI-chantiers THIM O/Bunia : Lot1:Q/Lembabo,Muzi-pela,Bi go,Kasegwa,Simbiliabo,Bemb 2. Livelihoods and Employm Single Stage - One En cours d'e ey,Ndiba kodu IDA / 66650 A posteriori Demande de prix Limited 260,000.00 0.00 2022-04-04 2022-05-30 2022-11-26 ent Generation Envelope xécution Lot2:Q/Ngezi,Lumumba,Bako ngolo,Yambi yaya,Hoho,Opas ,Bankoko,Dele Lot3:Q/NyakasanzaI et II,Saio ,Rwankole,Kindiya,Salongo,S ukisa,Rwambuzi F.,Rwambuzi B. ZR-FSRDC-272213-GO-RFQ / (27):Acq. outillage-chantiers THIMO/Bunia : Lot1:Q/Lembabo,Muzi-p.,Bigo ,Kasegwa,Simbiliabo,Bembey 2. Livelihoods and Employm Single Stage - One En cours d'e ,Ndiba k. IDA / 66650 A posteriori Demande de prix Limited 260,000.00 0.00 2022-04-04 2022-05-30 2022-11-26 ent Generation Envelope xécution Lot2:Q/Ngezi,Lumumba,Bako ngolo,Yambi y.,Hoho,Opas,Ba nkoko,Dele Lot3:Q/NyakasanzaI et II,Saio ,Rwankole,Kindiya,Salongo,S ukisa,Rwambuzi F.,Rwambuzi B. ZR-FSRDC-274087-GO-RFQ / (26) Acquisition des panneau x (24 grands panneaux indic 2. Livelihoods and Employm Single Stage - One En cours d'e atifs et 480 petits panneaux IDA / 66650 A posteriori Demande de prix Limited 26,712.00 0.00 2022-04-04 2022-05-30 2022-11-26 ent Generation Envelope xécution attention travaux, soit 504 p anneaux) de signalisation de s chantiers de THIMO à Buni a - ITURI ZR-FSRDC-274088-GO-RFQ / (33) Acquisition des fournitur es des bureaux pour les bure aux des chantiers ( installatio 2. Livelihoods and Employm Single Stage - One En cours d'e IDA / 66650 A posteriori Demande de prix Limited 7,200.00 0.00 2022-04-04 2022-05-30 2022-11-26 n des chantiers) dans le cadr ent Generation Envelope xécution e de la mise en oeuvre de ch antier de travaux à haute int ensite de la main d’oeuvre à Bunia_ ITURI ZR-FSRDC-274089-GO-RFQ / (31) Acquisition des 240 kits de lavage des mains pour les beneficaires dans le cadre de 2. Livelihoods and Employm Single Stage - One En cours d'e IDA / 66650 A posteriori Demande de prix Limited 36,000.00 0.00 2022-04-04 2022-05-30 2022-11-26 la mise en œuvre de chantier ent Generation Envelope xécution s de travaux à haute intensit e de la main d’œuvre dans le s 24 quartiers de la ville de B unia _ ITURI ZR-FSRDC-274090-GO-RFQ / (35) Fourniture des matériau x de construction pour la con struction/réhabilitation des p 2. Livelihoods and Employm Single Stage - One En attente d' etits ouvrages (ponts, ponce IDA / 66650 A posteriori Demande de prix Limited 105,000.00 0.00 2022-04-04 2022-05-30 2022-11-26 ent Generation Envelope exécution aux, dalots, buses, passerelle s, etc). Lot 1 : (Quartiers Lembabo, Muzi-pela, Bigo, Kasegwa, Si mbiliabo, Bembey, Ndiba kod u)_ ITURI ZR-FSRDC-274091-GO-RFQ / (36) Fourniture des matériau x de construction pour la con struction/réhabilitation des p 2. Livelihoods and Employm Single Stage - One En attente d' etits ouvrages (ponts, ponce IDA / 66650 A posteriori Demande de prix Limited 120,000.00 0.00 2022-04-04 2022-05-30 2022-11-26 ent Generation Envelope exécution aux, dalots, buses, passerelle s, etc). lot 2 : (Quartiers Ngezi, Lumu mba, Bakongolo, Yambi yaya , Hoho, Opas, Bankoko, Dele) - ITURI ZR-FSRDC-274092-GO-RFQ / (37) Fourniture des matériau x de construction pour la con struction/réhabilitation des p 2. Livelihoods and Employm Single Stage - One En attente d' IDA / 66650 A posteriori Demande de prix Limited 135,000.00 0.00 2022-04-04 2022-05-30 2022-11-26 etits ouvrages (ponts, ponce ent Generation Envelope exécution aux, dalots, buses, passerelle s, etc). lot 3: (Quartiers Nyak asanza I, Nyakasanza II, Saio, Rwankole, Kindiya, Salongo, Sukisa _ ITURI ZR-FSRDC-274105-GO-RFQ / (39) Fourniture de pelouse p our l’embellissement et prote ction des accotements dans l 2. Livelihoods and Employm Single Stage - One En attente d' IDA / 66650 A posteriori Demande de prix Limited 40,000.00 0.00 2022-06-04 2022-07-30 2023-01-26 e cadre des chantiers THIMO ent Generation Envelope exécution à Bunia dans la province de l’ Ituri. Répartit en trois lots. Lot 1 : (Qrts Lembabo,..Lot 2 (Qrts Ngezi,...) Lot3 (Qrts Ny a...)_ ITURI ZR-FSRDC-274106-GO-RFQ / (38) Fourniture des Latérites pour le rechargement des ax 2. Livelihoods and Employm Single Stage - One En attente d' es dans le cadre des chantier IDA / 66650 A posteriori Demande de prix Limited 200,000.00 0.00 2022-06-05 2022-07-31 2023-01-27 ent Generation Envelope exécution s THIMO à Bunia. Répartit en trois lots : Lot 1 : (Qrts Lemb abo...) lot 2 : (Quartiers Ngez i, ...) Lot3 (Qrts Nyakasanza. .. ) _ ITURI ZR-FSRDC-274728-GO-RFQ / (28) Acquisition des kits médi caux d’urgence dans le cadre 2. Livelihoods and Employm Single Stage - One En cours d'e IDA / 66650 A posteriori Demande de prix Limited 24,000.00 0.00 2022-07-05 2022-08-30 2023-02-26 de la mise en œuvre de chan ent Generation Envelope xécution tiers de travaux à haute inte nsité de la main d’œuvre à B unia dans la province de l’Itu ri. ZR-FSRDC-274729-GO-RFQ / (29) Acquisition des fournitur es et kits de recrutement de 2. Livelihoods and Employm Single Stage - One En cours d'e s bénéficiaires dans le cadre IDA / 66650 A posteriori Demande de prix Limited 24,000.00 0.00 2022-07-05 2022-08-30 2023-02-26 ent Generation Envelope xécution de la mise en œuvre des cha ntiers de travaux à haute int ensité de la main d’œuvre à Bunia dans la province de l’It uri ZR-FSRDC-274722-GO-RFQ / (21)Acquisition des Eqpts (Bc s, tabls, chaises, Armrs et au tres) IDB de 5 qrts : (LEMBAB 1. Support to Community Re Single Stage - One En attente d' O, MUZI-PELA, SUKISA, KINDI IDA / 66650 A posteriori Demande de prix Limited 62,500.00 0.00 2022-07-05 2022-08-30 2023-02-26 silience Envelope exécution A et SIMBILIABO)-Lot I.1: E.P EP MUDJUMBE EPAINETO- Lot I.2: E.P 1 BUNIA- Lot I.3: E.P S UKISA - Lot I.4: E.P MWA_ Lot 5 E.P NYAKEZI_ITURI ZR-FSRDC-274724-GO-RFQ / (22) Acquisition ds Eqpts (Bc s, tbls, chaises, Armrs et autr es) IDB de 5 qtrs : BEMBEY, L 1. Support to Community Re Single Stage - One En attente d' UMUMBA, RWAMBUZI-BENI, S IDA / 66650 A posteriori Demande de prix Limited 62,500.00 0.00 2022-07-05 2022-08-30 2023-02-26 silience Envelope exécution ALONGO et dans le groupt B ABUCHUKA,Lot1: E.P INGA NI ZI- Lot2: E.P.1MURONGO- Lot 3: E.P SIMBILYABO,Lot4: E.P4 NYAKASANZA Lot5EP BUNDIK ASA_ ITURI ZR-FSRDC-275599-GO-RFQ / (24) Acquisition des Equipem ents pour les IDB de 5 quarti ers : TSERE, LENGABO BABU 1. Support to Community Re Single Stage - One En attente d' LABA et BEDU EZEKERE et S IDA / 66650 A posteriori Demande de prix Limited 75,000.00 0.00 2022-07-05 2022-08-30 2023-02-26 silience Envelope exécution ALONGO -Lot1: EP. MAKI MBU DHA-Lot2: EP. MBUNYA-Lot 3: EP.2 SOLENYAMA-Lot 4: P.BU Y SABUNI; Lot 5: Centre de s anté SALONGO_ ITURI Page 6 ZR-FSRDC-275603-GO-RFQ / (23) Acquisition des Equipem ents pour les IDB de 5 quarti ers : BIGO, HOHO, OPAS, KAS 1. Support to Community Re Single Stage - One En attente d' IDA / 66650 A posteriori Demande de prix Limited 125,000.00 0.00 2022-07-05 2022-08-30 2023-02-26 EGWA ET DELE -Lot1 : Centre silience Envelope exécution de santé BIGO- Lot2 : centre de santé HOHO- Lot 3 : Centr e de santé OPAS- Lot4;- Lot5: Centre de santé de DELE_ IT URI ZR-FSRDC-274726-GO-RFQ / (25) Acquisition des Equipem ents pour les IDB centre de s 1. Support to Community Re Single Stage - One En attente d' IDA / 66650 A posteriori Demande de prix Limited 50,000.00 0.00 2022-07-05 2022-08-30 2023-02-26 anté de 2 quartiers : NDIBA-K silience Envelope exécution UDU et LUVANGIRA- Lot1 : C entre de santé NDIBE- Lot2 : Centre de santé KATOTO_ IT URI ZR-FSRDC-278111-GO-RFQ / 12 (KC-C2) Acquisition des o utges mise en œuvre des cha ntiers THIMO dans la cité de 2. Livelihoods and Employm Single Stage - One En attente d' Kazumba (21) et Matamba (1 IDA / 66650 A posteriori Demande de prix Limited 370,000.00 0.00 2022-10-05 2022-11-30 2023-05-29 ent Generation Envelope exécution 3),Lot 1 : Matamba (Quartier s Miao, Katoka 1...;lot 2 Kazu mba : (Quartiers du Centre, Ntshintsi nord...;lot 3 Kazum ba: (Quartiers Kapanda...;_KC ZR-FSRDC-278113-GO-RFQ / 13 (KC-C2) Acquisition des ki ts médicaux d’urgence dans l e cadre de la mise en œuvre 2. Livelihoods and Employm Single Stage - One En attente d' IDA / 66650 A posteriori Demande de prix Limited 40,000.00 0.00 2022-10-05 2022-11-30 2023-05-29 de chantiers de travaux à ha ent Generation Envelope exécution ute intensité de la main d’œu vre à Kazumba et Matamba d ans la province du Kasaï-Cen tral (34 chantiers)_ KC ZR-FSRDC-278115-GO-RFQ / 14 (KC-C2) Acquisition des fo urnitures et kits de recrutem ent des bénéficiaires dans le 2. Livelihoods and Employm Single Stage - One En attente d' cadre de la mise en œuvre d IDA / 66650 A posteriori Demande de prix Limited 40,000.00 0.00 2022-10-05 2022-11-30 2023-05-29 ent Generation Envelope exécution es chantiers de travaux à ha ute intensité de la main d’œu vre à Kazumba et Matamba d ans la province du Kasaï-cent ral (34 chantiers)_ KC ZR-FSRDC-278116-GO-RFQ / 15 (KC-C2) Acquisition de 68 panneaux métalliques pr le mécanisme de gestion des pl 2. Livelihoods and Employm Single Stage - One En attente d' aintes ds le cadre de la mise IDA / 66650 A posteriori Demande de prix Limited 17,000.00 0.00 2022-10-05 2022-11-30 2023-05-29 ent Generation Envelope exécution en œuvre de 34 chantiers de travaux à haute intensité de l a main d’œuvre dans les 34 quartiers de la cité de Kazum ba (21) et Matamba (13) _ KC ZR-FSRDC-278119-GO-RFQ / 16 (KC-C2) Acquisition des 3 40 kits de lavage des mains 2. Livelihoods and Employm Single Stage - One En attente d' pour les bénéficiaires dans le IDA / 66650 A posteriori Demande de prix Limited 51,000.00 0.00 2022-10-05 2022-11-30 2023-05-29 ent Generation Envelope exécution cadre de la mise en œuvre d e chantiers de THIMO dans le s 34 quartiers de la cité de K azumba et Matamba _ KC ZR-FSRDC-278120-GO-RFQ / 17 (KC-C2) Acquisition de 71 4 panneaux de signalisation des chantiers dans le cadre d 2. Livelihoods and Employm Single Stage - One En attente d' IDA / 66650 A posteriori Demande de prix Limited 37,842.00 0.00 2022-10-05 2022-11-30 2023-05-29 e la mise en œuvre de chanti ent Generation Envelope exécution ers de travaux à haute intens ité de la main d’œuvre dans l a cité de Kazumba et Matam ba _ KC ZR-FSRDC-278206-GO-RFQ / 18 (KC-C2) Acquisition des fo urnitures des bureaux pour l es bureaux des chantiers (ins 2. Livelihoods and Employm Single Stage - One En attente d' tallation des chantiers) dans l IDA / 66650 A posteriori Demande de prix Limited 10,200.00 0.00 2022-10-05 2022-11-30 2023-05-29 ent Generation Envelope exécution e cadre de la mise en œuvre de chantier de travaux à hau te intensité de la main d’œuv re dans la cité de Kazumba e t Matamba _ KC ZR-FSRDC-278217-GO-RFQ / 20 (KC-C2) Fourniture des mt rx de construction pour la co nstr/réhab des petits ouvrage 2. Livelihoods and Employm Single Stage - One En attente d' IDA / 66650 A posteriori Demande de prix Limited 510,000.00 0.00 2022-10-05 2022-11-30 2023-05-29 s (ponts, ponceaux, dalots...L ent Generation Envelope exécution ot 1 : Matamba (Quartiers Mi ao, Katoka 1...lot 2 Kazumba : (Quartiers du Centre...lot 3 Kazumba: (Q. Kapanda..._ KC ZR-FSRDC-278218-GO-RFQ / 21 (KC-C2) Fourniture des La térites/Limonites pour le rech argement des axes dans le c 2. Livelihoods and Employm Single Stage - One En attente d' IDA / 66650 A posteriori Demande de prix Limited 238,000.00 0.00 2022-10-05 2022-11-30 2023-05-29 adre des chantiers THIMO à K ent Generation Envelope exécution azumba et Matamba. Lot 1 : Matamba (Q Miao,Katoka 1...l ot 2 Kazumba : (Q. du Centre ...lot 3 Kazumba: (Q. Kapand a... _ KC ZR-FSRDC-278219-GO-RFQ / 22 (KC-C2) Fourniture de pels e, de bbous, fleurs, pltes et vetivers pr l’embellissmt et 2. Livelihoods and Employm Single Stage - One En attente d' protection des accts ds le cdr IDA / 66650 A posteriori Demande de prix Limited 102,000.00 0.00 2022-10-05 2022-11-30 2023-05-29 ent Generation Envelope exécution e THIMO ds la cité Kazumba et Matambao Lt 1 : Matamba (Q Miao,Katoka 1...lt 2 Kazu mba : (Q. du Centre...ltt 3 Ka zumba: (Q. Kapanda.._KC ZR-FSRDC-232758-GO-RFQ / Acquisition et Installation de Single Stage - One IDA / 66650 4. Project Management A posteriori Demande de prix Limited 60,000.00 0.00 Annulé 2021-06-13 2021-08-08 2022-02-04 2 Générateurs pour Kasaï Ce Envelope ntral et Nord Ubangi ZR-FSRDC ITURI-303788-GO- RFQ / Acquisition des jouets 2. Livelihoods and Employm Single Stage - One En attente d' IDA / 66650 A posteriori Demande de prix Limited 15,000.00 0.00 2022-09-17 2022-11-12 2023-05-11 pour enfants des crèches mo ent Generation Envelope exécution biles des 21 chantiers thimo d'Aru ZR-FSRDC ITURI-303783-GO- RFQ / Fourniture des produits 2. Livelihoods and Employm Single Stage - One En attente d' IDA / 66650 A posteriori Demande de prix Limited 30,000.00 0.00 2022-09-17 2022-11-12 2023-05-11 d'hygiène pour les crèches m ent Generation Envelope exécution obiles des 21 chantiers thimo d'Aru ZR-FSRDC ITURI-303774-GO- RFQ / Fournitures des équipe 2. Livelihoods and Employm Single Stage - One En attente d' IDA / 66650 A posteriori Demande de prix Limited 20,000.00 0.00 2022-09-17 2022-11-12 2023-05-11 ments et matériels pour les c ent Generation Envelope exécution rèches mobiles des 21 chanti ers thimo d'Aru ZR-FSRDC ITURI-316245-GO- RFQ / Acquisition des EPI dan s le cadre de THIMO dans la ville de Mahagi en Ituri, en 3 lots : 2. Livelihoods and Employm Single Stage - One En attente d' IDA / 66650 A posteriori Demande de prix Limited 150,000.00 0.00 2022-11-19 2023-01-14 2023-07-13 Lot 1 : (Q. Jumba, Lakalu, Ma ent Generation Envelope exécution dipoy, Mahagi et Mamba) ; Lot 2 ; (Q. Adu Centre, Adu M ission, Agwel, Drii et Gamba) Lot 3: (Q. Njura, Ridha I, Ridh a II et Angirajo) ZR-FSRDC ITURI-316247-GO- RFQ / Acquisition des mat. et pts outillages dans le cadre d e THIMO de Mahagi en Ituri, en 3 lots : 2. Livelihoods and Employm Single Stage - One En attente d' IDA / 66650 A posteriori Demande de prix Limited 120,000.00 0.00 2022-11-19 2023-01-14 2023-07-13 Lot 1 : (Q. Jumba, Lakalu, Ma ent Generation Envelope exécution dipoy, Mahagi et Mamba) ; Lot 2 ; (Q. Adu Centre, Adu M ission, Agwel, drii et Gamba) Lot 3: (Q. Njura, Ridha I, Ridh a II et Angirajo ZR-FSRDC ITURI-316249-GO- RFQ / Acquisition des fournit ures et kits de recrutement d 2. Livelihoods and Employm Single Stage - One En attente d' IDA / 66650 A posteriori Demande de prix Limited 21,000.00 0.00 2022-11-19 2023-01-14 2023-07-13 es bénéficiaires dans le cadr ent Generation Envelope exécution e de la mise en œuvre des T HIMO dans la ville de Mahagi en Ituri Page 7 ZR-FSRDC ITURI-316252-GO- RFQ / Acquisition des 62 Pan neaux métalliques pour le Mé 2. Livelihoods and Employm Single Stage - One En attente d' canisme de Gestion des Plain IDA / 66650 A posteriori Demande de prix Limited 9,500.00 0.00 2022-11-19 2023-01-14 2023-07-13 ent Generation Envelope exécution tes dans le cadre de la mise en œuvre des chantiers THIM O et IDBS dans le territoire d e Mahagi en Ituri ZR-FSRDC ITURI-316256-GO- RFQ / Acquisition des fournit ures de bureau pour les bure 2. Livelihoods and Employm Single Stage - One En attente d' aux de chantier (installation IDA / 66650 A posteriori Demande de prix Limited 10,000.00 0.00 2022-11-19 2023-01-14 2023-07-13 ent Generation Envelope exécution des chantiers) dans le cadre de la mise en œuvre de chan tiers THIMO dans la ville de Mahagi en Ituri ZR-FSRDC ITURI-316260-GO- RFQ / Fourniture de latérite p our le rechargement des axe s et fourniture de pelouse, de 2. Livelihoods and Employm Single Stage - One En attente d' bambous, fleurs, plantes pou IDA / 66650 A posteriori Demande de prix Limited 140,000.00 0.00 2022-11-19 2023-01-14 2023-07-13 ent Generation Envelope exécution r l’embellissement et protecti on des accotements dans le cadre de la mise en œuvre d es chantiers THIMO dans la vi lle de Mahagi en Ituri ZR-FSRDC ITURI-316264-GO- RFQ / Acquisition de 294 pan neaux de signalisation des ch 2. Livelihoods and Employm Single Stage - One En attente d' IDA / 66650 A posteriori Demande de prix Limited 15,000.00 0.00 2022-11-19 2023-01-14 2023-07-13 antiers dans cadre de la mise ent Generation Envelope exécution en œuvre des chantiers THIM O dans la ville de Mahagi en I turi ZR-FSRDC ITURI-316267-GO- RFQ / Acquisition des kits mé 2. Livelihoods and Employm Single Stage - One En attente d' dicaux d’urgence dans le cad IDA / 66650 A posteriori Demande de prix Limited 14,000.00 0.00 2022-11-19 2023-01-14 2023-07-13 ent Generation Envelope exécution re de la mise en œuvre de ch antiers THIMO à Mahagi en It uri ZR-FSRDC ITURI-316265-GO- RFQ / Fourniture des mat de construction pour la réhabilit ation des pts ouvrages de TH IMO à Mahagi, en 3 lots: 2. Livelihoods and Employm Single Stage - One En attente d' IDA / 66650 A posteriori Demande de prix Limited 150,000.00 0.00 2022-11-19 2023-01-14 2023-07-13 Lot 1 : Q. Jumba, Lakalu, Mad ent Generation Envelope exécution ipoy, Mahagi et Mamba Lot 2: Q Adu Centre, Adu Mis sion, Agwel, Drii et Gamba Lot 3 : Q. Njura, Ridha I, Ridh a II et Angi ZR-FSRDC ITURI-316255-GO- RFQ / Acquisition de 140 kits 2. Livelihoods and Employm Single Stage - One En attente d' de lavage des mains dans le IDA / 66650 A posteriori Demande de prix Limited 7,000.00 0.00 2022-11-19 2023-01-14 2023-07-13 ent Generation Envelope exécution cadre de la mise en œuvre d es chantiers THIMO dans la vi lle de Mahagi en Ituri ZR-FSRDC ITURI-318669-GO- RFQ / Acquisition des Equipe ments pour les IDB de 6 grou pements du territoire de Mah 1. Support to Community Re Single Stage - One En attente d' IDA / 66650 A posteriori Demande de prix Limited 90,000.00 0.00 2022-11-19 2023-01-14 2023-07-13 agi : G. Ngote, Nioka, Djupan silience Envelope exécution yangi, Rhona, Shari et Aupa Lot 1 : EP SII, Lot 2: EP RABU, Lot 3: EP LERO, Lot 4: EP SIM BI-LARI, Lot 5: EP DZANGALI et Lot 6: EP AUPA ZR-FSRDC ITURI-318672-GO- RFQ / Acquisition des Equipe ments pour les IDB de 2 grou pements du territoire de Mah 1. Support to Community Re Single Stage - One En attente d' agi : G. Pakwo, Gossi et de 3 IDA / 66650 A posteriori Demande de prix Limited 75,000.00 0.00 2022-11-19 2023-01-14 2023-07-13 silience Envelope exécution quartiers de la ville de Maha gi : Ridha 2, Njura et Madipo yi. Lot 1 : EP URIKO, Lot 2: EP A GAPE, Lot 3: EP KIANGANI, Lo t 4: EP AJOBA et Lot 5: EP A ZR-FSRDC ITURI-318673-GO- RFQ / Acquisition des Equipe ments pour les IDB de 6 grou pements du territoire de Mah 1. Support to Community Re Single Stage - One En attente d' agi : G. Umoyo, Alur, Sabu, Ju IDA / 66650 A posteriori Demande de prix Limited 90,000.00 0.00 2022-11-19 2023-01-14 2023-07-13 silience Envelope exécution pagassa, Agba et Kusu. Lot 1 : EP CATHOLIKI, Lot 2: E P CANA BOTH, Lot 3: EP MUK E, Lot 4: EP JALBONYO, Lot 5: EP WI AGBA et Lot 6: EP ATE RLEMBA ZR-FSRDC ITURI-318674-GO- RFQ / Acquisition des Equipe ments pour les IDB de 4 grou pements du territoire d’Irum 1. Support to Community Re Single Stage - One En attente d' IDA / 66650 A posteriori Demande de prix Limited 60,000.00 0.00 2022-11-19 2023-01-14 2023-07-13 u : G. Babiase, Bangungu, Bo silience Envelope exécution loma et Rubingo. Lot 1 : EP MUZORA, Lot 2: EP 1 KASENYI, Lot 3: EP MUZOR A et Lot 4: EP KIANGELA ZR-FSRDC ITURI-318675-GO- RFQ / Acquisition des Equipe ments pour les IDB de 4 grou pements dont 2 du territoire 1. Support to Community Re Single Stage - One En attente d' d’Irumu : G. Bukiringi et Bog IDA / 66650 A posteriori Demande de prix Limited 60,000.00 0.00 2022-11-19 2023-01-14 2023-07-13 silience Envelope exécution a Centre et 2 du territoire de Djugu : G. Lingo et Tchomia. Lot 1 : EP BUKIRINGI, Lot 2: E P KYAIRETA, Lot 3: EP BALIKO DRA et Lot 4: EP ZUBULU ZR-FSRDC ITURI-318676-GO- RFQ / Acquisition des Equipe ments pour les IDB d’un quar tier de Mahagi : Q. Adu Missi 1. Support to Community Re Single Stage - One En attente d' IDA / 66650 A posteriori Demande de prix Limited 75,000.00 0.00 2022-11-19 2023-01-14 2023-07-13 on et 2 groupements du terri silience Envelope exécution toire de Mahagi : G. Koc Lala et Jupasonge. Lot 1 : CS ADU MISSION, Lot 2: CS AGATARA, Lot 3: CS MA HAGI ZR-FSRDC ITURI-318677-GO- RFQ / Acquisition des Equipe ments pour les IDB de 3 grou 1. Support to Community Re Single Stage - One En attente d' pements du territoire de Mah IDA / 66650 A posteriori Demande de prix Limited 75,000.00 0.00 2022-11-19 2023-01-14 2023-07-13 silience Envelope exécution agi : G. Paker, Porombo et Pa laro Pono. Lot 1 : CS ALLA WIMOO, Lot 2 : CS GUNA, Lot 3: CS PONO A VAR ZR-FSRDC ITURI-323681-GO- RFQ / Fourniture des produits 2. Livelihoods and Employm Single Stage - One En attente d' d’hygiène pour les crèches m IDA / 66650 A posteriori Demande de prix Limited 40,000.00 0.00 2022-12-03 2023-01-28 2023-07-27 ent Generation Envelope exécution obiles des 14 chantiers Thim o de la ville de Mahagi ZR-FSRDC ITURI-323680-GO- RFQ / Fourniture des équipe 2. Livelihoods and Employm Single Stage - One En attente d' ments et matériels pour les c IDA / 66650 A posteriori Demande de prix Limited 15,000.00 0.00 2022-12-03 2023-01-28 2023-07-27 ent Generation Envelope exécution rèches mobiles des 14 chanti ers Thimo de la ville de Maha gi ZR-FSRDC ITURI-323682-GO- RFQ / Acquisition des jouets 2. Livelihoods and Employm Single Stage - One En attente d' IDA / 66650 A posteriori Demande de prix Limited 10,000.00 0.00 2022-12-03 2023-01-28 2023-07-27 pour enfants des crèches mo ent Generation Envelope exécution biles des 14 chantiers Thimo de la ville de Mahagi ZR-FSRDC ITURI-355365-GO- RFQ / Acquisition des EPI dan s le cadre de la mise en œuv re des 24 chantiers THIMO d 2. Livelihoods and Employm Single Stage - One En attente d' IDA / 66650 A posteriori Demande de prix Limited 378,000.00 0.00 2023-05-05 2023-06-30 2023-12-27 ans la ville de Bunia. Réparti ent Generation Envelope exécution en trois lots. lot 1: commune de Shari. Lot 2 commune de Mbunya. Lot 3: commune de Nyakasanza ZR-FSRDC ITURI-355366-GO- RFQ / Acquisition des outillag es et petits matériels (compl ément) dans le cadre de la m 2. Livelihoods and Employm Single Stage - One En attente d' ise en œuvre des 24 chantie IDA / 66650 A posteriori Demande de prix Limited 151,200.00 0.00 2023-05-05 2023-06-30 2023-12-27 ent Generation Envelope exécution rs THIMO dans la ville de Bun ia. Réparti en 3 lots. lot 1: co mmune de Shari. Lot 2 comm une de Mbunya. Lot 3: comm une de Nyakasanza Page 8 ZR-FSRDC ITURI-355357-GO- RFQ / Fourniture des Latérite s/Limonites pour le recharge ment des axes dans le cadre 2. Livelihoods and Employm Single Stage - One En attente d' IDA / 66650 A posteriori Demande de prix Limited 192,000.00 0.00 2023-05-05 2023-06-30 2023-12-27 de la mise en oeuvre des cha ent Generation Envelope exécution ntiers THIMO dans la ville de Bunia, répartit en trois lots( l ot 7 : 5 quartiers, lot 2 : 8 qu artiers et lot 3: 9 quartiers) ZR-FSRDC ITURI-356493-GO- RFQ / Fourniture de pelouse, de bambous, fleurs, plantes et vétivers pour l’embellisse 2. Livelihoods and Employm Single Stage - One En attente d' IDA / 66650 A posteriori Demande de prix Limited 48,000.00 0.00 2023-05-05 2023-06-30 2023-12-27 ment et protection des accot ent Generation Envelope exécution ements dans le cadre des ch antiers THIMO à Bunia, repar ti 3 lots( lot1 : 7 quartiers, lot 2: 8 quartiers et lot 3 : 9 quar tiers) . ZR-FSRDC ITURI-356516-GO- RFQ / Acquisition des kits mé 2. Livelihoods and Employm Single Stage - One En attente d' dicaux d’urgence dans le cad IDA / 66650 A posteriori Demande de prix Limited 36,000.00 0.00 2023-05-05 2023-06-30 2023-12-27 ent Generation Envelope exécution re de la mise en oeuvre des c hantiers THIMO dans la ville de Bunia (24 quartiers) ZR-FSRDC ITURI-356509-GO- RFQ / Acquisition des fournit 2. Livelihoods and Employm Single Stage - One En attente d' IDA / 66650 A posteriori Demande de prix Limited 16,800.00 0.00 2023-05-05 2023-06-30 2023-12-27 ures de bureau pour l’installa ent Generation Envelope exécution tion des chantiers THIMO dan s la ville de Bunia ZR-FSRDC ITURI-356519-GO- RFQ / Acquisition des produit s d'hygiène pour les crèches 2. Livelihoods and Employm Single Stage - One En attente d' mobiles de 24 chantiers THI IDA / 66650 A posteriori Demande de prix Limited 24,000.00 0.00 2023-05-05 2023-06-30 2023-12-27 ent Generation Envelope exécution MO dans la ville de Bunia. Ré partit en trois lots. Lot 1: 7 q uartiers, lot 2: 8 quartiers et l ot 3: 9 quartiers ZR-FSRDC ITURI-356514-GO- RFQ / Acquisition des équipe ments et matériels pour les c 2. Livelihoods and Employm Single Stage - One En attente d' rèches mobiles de 24 chantie IDA / 66650 A posteriori Demande de prix Limited 67,200.00 0.00 2023-05-05 2023-06-30 2023-12-27 ent Generation Envelope exécution rs THIMO de la ville de Bunia. Répartit en trois lots. Lot 1: 7 quartiers, lot 2: 8 quartiers et lot 3: 9 quartiers ZR-FSRDC ITURI-356518-GO- RFQ / Acquisition des jouets pour enfants des crèches mo 2. Livelihoods and Employm Single Stage - One En attente d' biles des 24 chantiers THIMO IDA / 66650 A posteriori Demande de prix Limited 36,000.00 0.00 2023-05-05 2023-06-30 2023-12-27 ent Generation Envelope exécution de la ville de Bunia. Répartit en trois lots. Lot 1: 7 quartier s, lot 2: 8 quartiers et lot 3: 9 quartiers ZR-FSRDC ITURI-355354-GO- RFQ / Acquisition de 30 table 2. Livelihoods and Employm Single Stage - One En attente d' ttes pour le recrutement des IDA / 66650 A posteriori Demande de prix Limited 9,000.00 0.00 2023-05-05 2023-06-30 2023-12-27 ent Generation Envelope exécution bénéficiaires THIMO et le sui vi des chantiers de la ville de Bunia NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Repor Loan / Credit N Market Approac Procurement Pr Prequalification Estimated Am Actual Amount Process St Draft Pre-qualificatio Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission Description Component Review Type Method t and Recommendati Signed Contract Contract Completion o. h ocess (Y/N) ount (US$) (US$) atus n Documents ation Report ent / Justification Notice / Invitation s Issued / Opening / Minutes on for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ZR-FSRDC-232738-NC-RFQ / Souscription d’une assurance Single Stage - One En attente d' IDA / 66650 4. Project Management A posteriori Demande de prix Limited 150,000.00 0.00 2021-06-20 2021-08-15 2022-02-11 maladie en faveur du person Envelope exécution nel du STEP2 et leurs ayants droits ZR-FSRDC-232792-NC-RFQ / Single Stage - One En attente d' Services de Paiements Digita IDA / 66650 5. CERC A posteriori Demande de prix Limited 100,000.00 0.00 2021-07-20 2021-09-14 2022-03-13 Envelope exécution ux des Bénéficiaires STEP-KA NANGA ZR-FSRDC-275604-NC-RFQ / (34) Selection des services tr aiteurs pour la formation des 2. Livelihoods and Employm Single Stage - One En cours d'e chfs des chtiers, chfs d’eqps, IDA / 66650 A posteriori Demande de prix Limited 27,000.00 0.00 2022-06-05 2022-07-31 2023-01-27 ent Generation Envelope xécution points PFE et AST dans le cad re de la mise en œuvre de ch antiers THIMO dans les 24 qu artiers de la ville de Bunia_ IT URI ZR-FSRDC-278208-NC-RFQ / 19 (KC-C2) Sélection des ser vices traiteurs pour la format ion des chefs des chantiers ( 2. Livelihoods and Employm Single Stage - One En attente d' 41), chefs d’équipes (374), P IDA / 66650 A posteriori Demande de prix Limited 38,000.00 0.00 2022-10-05 2022-11-30 2023-05-29 ent Generation Envelope exécution FE et sociaux (41) et agents de suivi des terrains (41) dan s le cadre de THIMO_ dans le s 34 quartiers de la cité de K azumba et Matamba_ KC ZR-FSRDC ITURI-315385-NC- RFQ / Recrutement d'un servi ce financier pour les paiemen 2. Livelihoods and Employm Single Stage - One En attente d' IDA / 66650 A posteriori Demande de prix Limited 126,900.00 0.00 2022-11-19 2023-01-14 2023-07-13 ts des bénéficiaires TMI dans ent Generation Envelope exécution la province d'Ituri dans le cad re du Projet STEP 2 dans l'ant enne d'Ituri ZR-FSRDC ITURI-316268-NC- RFQ / Sélection des services t raiteurs devant assurer la res tauration pour la formation d 2. Livelihoods and Employm Single Stage - One En attente d' es chefs d’équipes, chefs des IDA / 66650 A posteriori Demande de prix Limited 25,125.00 0.00 2022-11-19 2023-01-14 2023-07-13 ent Generation Envelope exécution chantiers, PFE et AST dans le cadre de la mise en œuvre d es chantiers thimo à Mahagi en Ituri, subdivisée en 4 lots : Lot 1 : Service traiteur ZR-FSRDC ITURI-355358-NC- RFQ / Recrutement des servi ces traiteur pour la formation des prestataires : Lot 1 Servi 2. Livelihoods and Employm Single Stage - One En attente d' IDA / 66650 A posteriori Demande de prix Limited 22,050.00 0.00 2023-05-05 2023-06-30 2023-12-27 ce traiteur pour la formation ent Generation Envelope exécution des 30 CC.Lot 2: Service trait eur pour formation de 336 C E, lot 3: formation de 30 PFE et lot 4: formation de 30 AST. CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amoun Expression of Interes Short List and Draft R Request for Proposal Opening of Technical Evaluation of Techni Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) t (US$) t Notice equest for Proposals s as Issued Proposals / Minutes cal Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ZR-FSRDC-232808-CS-CQS / Sélection fondée s Recrutement d’un bureau de 1. Support to Community Re En attente d'exéc IDA / 66650 A posteriori ur les qualification Open - National 6,000.00 0.00 2021-08-31 2021-09-21 2021-11-04 2021-12-04 2022-01-08 2022-07-07 contrôle pour la Construction silience ution s des consultants de l’EP Ouelé/ Zabo / ZR-FSRDC-232862-CS-CQS / Sélection fondée s Agence de communication p 2. Livelihoods and Employm En attente d'exéc IDA / 66650 A posteriori ur les qualification Open - National 50,000.00 0.00 2021-07-12 2021-08-02 2021-09-15 2021-10-15 2021-11-19 2022-05-18 our l’élaboration du plan de c ent Generation ution s des consultants ommunication de STEP-CERC ZR-FSRDC-232901-CS-CQS / Sélection fondée s 1. Support to Community Re En cours d'exécut Bureau de contrôle pour l'EP IDA / 66650 A posteriori ur les qualification Open - National 7,500.00 0.00 2021-06-30 2021-06-15 2021-07-21 2021-09-03 2021-10-03 2021-11-07 2022-05-06 silience ion à KABUAYI s des consultants ZR-FSRDC-232902-CS-CQS / Sélection fondée s 1. Support to Community Re En cours d'exécut Recrutrement d'un bureau de IDA / 66650 A posteriori ur les qualification Open - National 7,500.00 0.00 2021-06-30 2021-06-15 2021-07-21 2021-09-03 2021-10-03 2021-11-07 2022-05-06 silience ion contrôle pour l'EP à Central s des consultants ZR-FSRDC-232903-CS-CQS / Sélection fondée s 1. Support to Community Re En cours d'exécut Recrutement d'un bureau de IDA / 66650 A posteriori ur les qualification Open - National 7,500.00 0.00 2021-06-30 2021-06-15 2021-07-21 2021-09-03 2021-10-03 2021-11-07 2022-05-06 silience ion contrôle pour l'EP à LUABA N s des consultants TONDO ZR-FSRDC-232907-CS-CQS / Sélection fondée s 1. Support to Community Re En cours d'exécut Recrutement d'un bureau de IDA / 66650 A posteriori ur les qualification Open - National 7,500.00 0.00 2021-06-30 2021-06-15 2021-07-21 2021-09-03 2021-10-03 2021-11-07 2022-05-06 silience ion contrôle pour l'EP à TUBADI s des consultants ZR-FSRDC-232911-CS-CQS / Sélection fondée s 1. Support to Community Re En cours d'exécut Recrutement d'un bureau de IDA / 66650 A posteriori ur les qualification Open - National 7,500.00 0.00 2021-06-30 2021-06-15 2021-07-21 2021-09-03 2021-10-03 2021-11-07 2022-05-06 silience ion contrôle pour l'EP à THSIBAL s des consultants A Page 9 ZR-FSRDC-232912-CS-CQS / Sélection fondée s 1. Support to Community Re En cours d'exécut Recrutement d'un bureau de IDA / 66650 A posteriori ur les qualification Open - National 7,500.00 0.00 2021-06-30 2021-06-15 2021-07-21 2021-09-03 2021-10-03 2021-11-07 2022-05-06 silience ion contrôle pour l'EP à TSHIMAYI s des consultants ZR-FSRDC-233375-CS-CQS / Recrutement d’une Structure chargée du Renforcement de Sélection fondée s 2. Livelihoods and Employm En cours d'exécut Capacités des Bénéficiaires T IDA / 66650 A posteriori ur les qualification Open - National 50,000.00 0.00 2021-06-30 2021-05-06 2021-07-21 2021-09-03 2021-10-03 2021-11-07 2022-05-06 ent Generation ion HIMO de 1 350 bénéficiaires s des consultants pour les ( Malandi, kamayi, t hsinsambi, Platea, Mpemba) de la ville de Kananga ZR-FSRDC-233377-CS-CQS / Recrutement d’une Structure chargée du Renforcement de Sélection fondée s Capacités des Bénéficiaires T 2. Livelihoods and Employm En cours d'exécut IDA / 66650 A posteriori ur les qualification Open - National 50,000.00 0.00 2021-06-30 2021-05-06 2021-07-21 2021-09-03 2021-10-03 2021-11-07 2022-05-06 HIMO de 1 350 bénéficiaires ent Generation ion s des consultants pour les ( Nsele Nganza -Nor d, Nganza- Sud, Saloneo-Mui mba- lubi-A-Mpata-Sukisa) de la ville de Kananga ZR-FSRDC-233378-CS-CQS / Recrutement d’une Structure chargée du Renforcement de Sélection fondée s 2. Livelihoods and Employm En cours d'exécut Capacités des Bénéficiaires T IDA / 66650 A posteriori ur les qualification Open - National 50,000.00 0.00 2021-06-30 2021-05-06 2021-07-21 2021-09-03 2021-10-03 2021-11-07 2022-05-06 ent Generation ion HIMO de 1 350 bénéficiaires s des consultants pour les ( katokaz- Mpokolo- kelekele- Kapanda- Tukombe ) de la ville de Kananga ZR-FSRDC-233379-CS-CQS / Recrutement d’une Structure chargée du Renforcement de Sélection fondée s 2. Livelihoods and Employm En cours d'exécut Capacités des Bénéficiaires T IDA / 66650 A posteriori ur les qualification Open - National 50,000.00 0.00 2021-06-30 2021-05-06 2021-07-21 2021-09-03 2021-10-03 2021-11-07 2022-05-06 ent Generation ion HIMO de 1 350 bénéficiaires s des consultants pour les ( Ndesma- Thibanda Banda- Kamilabi- Lubuwa- Ka mu pongo) de la ville de Kan anga ZR-FSRDC-233381-CS-CQS / Recrutement d’une Structure chargée du Renforcement de Sélection fondée s Capacités des Bénéficiaires T 2. Livelihoods and Employm En cours d'exécut IDA / 66650 A posteriori ur les qualification Open - National 50,000.00 0.00 2021-06-30 2021-05-06 2021-07-21 2021-09-03 2021-10-03 2021-11-07 2022-05-06 HIMO de 1 350 bénéficiaires ent Generation ion s des consultants pour les ( Mabondo- Itabayi-L umumba-dikongayi- Mulunda - Tshibashi) de la ville de Kan anga ZR-FSRDC-236086-CS-CQS / Sélection fondée s 1. Support to Community Re En attente d'exéc Bureau pour contrôle et Surv IDA / 66650 A posteriori ur les qualification Open - National 3,400.00 0.00 2020-12-30 2021-01-20 2021-03-05 2021-04-04 2021-05-09 2021-11-05 silience ution eillance des travaux de l'EP L s des consultants ungandu/KC MOF-REF-95 / Bureau pour c Sélection fondée s 1. Support to Community Re En attente d'exéc ontrôle et Surveillance des tr IDA / 66650 A posteriori ur les qualification Open - National 5,200.00 0.00 2020-12-30 2021-01-20 2021-03-05 2021-04-04 2021-05-09 2021-11-05 silience ution avaux de l'EP Ngindalalyi/KC s des consultants ZR-FSRDC-236398-CS-CQS / Sélection fondée s 1. Support to Community Re En attente d'exéc Bureau pour contrôle et Surv IDA / 66650 A posteriori ur les qualification Open - National 5,200.00 0.00 2020-12-30 2021-01-20 2021-03-05 2021-04-04 2021-05-09 2021-11-05 silience ution eillance des travaux de l'EPA s des consultants rc En Ciel/KC ZR-FSRDC-236344-CS-CQS / Sélection fondée s Bureau pour contrôle et Surv 1. Support to Community Re En attente d'exéc IDA / 66650 A posteriori ur les qualification Open - National 4,400.00 0.00 2020-12-30 2021-01-20 2021-03-05 2021-04-04 2021-05-09 2021-11-05 eillance des travaux de l'EP L silience ution s des consultants umumba 1/KC ZR-FSRDC-236029-CS-CQS / Sélection fondée s 1. Support to Community Re En attente d'exéc Bureau pour contrôle et Surv IDA / 66650 A posteriori ur les qualification Open - National 5,200.00 0.00 2020-12-30 2021-01-20 2021-03-05 2021-04-04 2021-05-09 2021-11-05 silience ution eillance des travaux de l'EP s des consultants Muindindi/KC ZR-FSRDC-236034-CS-CQS / Sélection fondée s 1. Support to Community Re En attente d'exéc Bureau pour contrôle et Surv IDA / 66650 A posteriori ur les qualification Open - National 5,200.00 0.00 2020-12-30 2021-01-20 2021-03-05 2021-04-04 2021-05-09 2021-11-05 silience ution eillance des travaux de l'EP s des consultants Mukoleshi/KC ZR-FSRDC-236143-CS-CQS / Sélection fondée s 1. Support to Community Re En attente d'exéc Bureau pour contrôle et Surv IDA / 66650 A posteriori ur les qualification Open - National 5,200.00 0.00 2020-12-30 2021-01-20 2021-03-05 2021-04-04 2021-05-09 2021-11-05 silience ution eillance des travaux de l'EP K s des consultants andiku/KC ZR-FSRDC-236399-CS-CQS / Sélection fondée s 1. Support to Community Re En attente d'exéc Bureau pour contrôle et Surv IDA / 66650 A posteriori ur les qualification Open - National 4,600.00 0.00 2020-12-30 2021-01-20 2021-03-05 2021-04-04 2021-05-09 2021-11-05 silience ution eillance des travaux de l'EPA s des consultants Mufumishi/KC ZR-FSRDC-236345-CS-CQS / Sélection fondée s 1. Support to Community Re En attente d'exéc Bureau pour contrôle et Surv IDA / 66650 A posteriori ur les qualification Open - National 5,200.00 0.00 2020-12-30 2021-01-20 2021-03-05 2021-04-04 2021-05-09 2021-11-05 silience ution eillance des travaux de l'EP s des consultants Mudidike/KC ZR-FSRDC-236500-CS-CQS / Sélection fondée s 1. Support to Community Re En attente d'exéc Bureau pour contrôle et Surv IDA / 66650 A posteriori ur les qualification Open - National 3,760.00 0.00 2020-12-30 2021-01-20 2021-03-05 2021-04-04 2021-05-09 2021-11-05 silience ution eillance des travaux de l'EP N s des consultants ganza/KC ZR-FSRDC-236059-CS-CQS / Sélection fondée s 1. Support to Community Re En attente d'exéc Bureau pour contrôle et Surv IDA / 66650 A posteriori ur les qualification Open - National 5,200.00 0.00 2020-12-30 2021-01-20 2021-03-05 2021-04-04 2021-05-09 2021-11-05 silience ution eillance des travaux de l'EP T s des consultants shisambi/KC ZR-FSRDC-236517-CS-CQS / Sélection fondée s 1. Support to Community Re En attente d'exéc Bureau pour contrôle et Surv IDA / 66650 A posteriori ur les qualification Open - National 5,200.00 0.00 2020-12-30 2021-01-20 2021-03-05 2021-04-04 2021-05-09 2021-11-05 silience ution eillance des travaux de l'EP s des consultants Diku/KC MOF-REF-107 / Bureau pour Sélection fondée s 1. Support to Community Re En attente d'exéc contrôle et Surveillance des t IDA / 66650 A posteriori ur les qualification Open - National 4,980.00 0.00 2020-12-30 2021-01-20 2021-03-05 2021-04-04 2021-05-09 2021-11-05 silience ution ravaux de l'EP TOSALISANA/K s des consultants C ZR-FSRDC-236412-CS-CQS / Sélection fondée s 1. Support to Community Re En attente d'exéc Bureau pour contrôle et Surv IDA / 66650 A posteriori ur les qualification Open - National 4,600.00 0.00 2020-12-30 2021-01-20 2021-03-05 2021-04-04 2021-05-09 2021-11-05 silience ution eillance des travaux de l'EP s des consultants Disanka/KC ZR-FSRDC-236543-CS-CQS / Sélection fondée s Bureau pour contrôle et Surv 1. Support to Community Re En attente d'exéc IDA / 66650 A posteriori ur les qualification Open - National 5,200.00 0.00 2020-12-30 2021-01-20 2021-03-05 2021-04-04 2021-05-09 2021-11-05 eillance des travaux de l'EP silience ution s des consultants Mgr Bakafua/KC ZR-FSRDC-236374-CS-CQS / Sélection fondée s Bureau pour contrôle et Surv 2. Livelihoods and Employm En attente d'exéc IDA / 66650 A posteriori ur les qualification Open - National 5,200.00 0.00 2020-12-30 2021-01-20 2021-03-05 2021-04-04 2021-05-09 2021-11-05 eillance des travaux de l'EP B ent Generation ution s des consultants ushala Muamba/KC ZR-FSRDC-236365-CS-CQS / Sélection fondée s 1. Support to Community Re En attente d'exéc Bureau pour contrôle et Surv IDA / 66650 A posteriori ur les qualification Open - National 4,600.00 0.00 2020-12-30 2021-01-20 2021-03-05 2021-04-04 2021-05-09 2021-11-05 silience ution eillance des travaux de l'EP N s des consultants desha/KC ZR-FSRDC-236523-CS-CQS / Sélection fondée s 1. Support to Community Re En attente d'exéc Bureau pour contrôle et Surv IDA / 66650 A posteriori ur les qualification Open - National 3,000.00 0.00 2020-12-30 2021-01-20 2021-03-05 2021-04-04 2021-05-09 2021-11-05 silience ution eillance des travaux de l'EP B s des consultants aolongo/KC ZR-FSRDC-236082-CS-CQS / Sélection fondée s Bureau pour contrôle et Surv 1. Support to Community Re En attente d'exéc IDA / 66650 A posteriori ur les qualification Open - National 4,200.00 0.00 2020-12-30 2021-01-20 2021-03-05 2021-04-04 2021-05-09 2021-11-05 eillance des travaux de l'EP T silience ution s des consultants SHISUMBU/KC ZR-FSRDC-236091-CS-CQS / Sélection fondée s Bureau pour contrôle et Surv 1. Support to Community Re En attente d'exéc IDA / 66650 A posteriori ur les qualification Open - National 4,600.00 0.00 2020-12-30 2021-01-20 2021-03-05 2021-04-04 2021-05-09 2021-11-05 eillance des travaux de l'EP T silience ution s des consultants uya Kumpala/KC ZR-FSRDC-236109-CS-CQS / Sélection fondée s 1. Support to Community Re En attente d'exéc Bureau pour contrôle et Surv IDA / 66650 A posteriori ur les qualification Open - National 3,750.00 0.00 2020-12-30 2021-01-20 2021-03-05 2021-04-04 2021-05-09 2021-11-05 silience ution eillance des travaux de l'EP S s des consultants ANKAYI/KC ZR-FSRDC-236512-CS-CQS / Sélection fondée s 1. Support to Community Re En attente d'exéc Bureau pour contrôle et Surv IDA / 66650 A posteriori ur les qualification Open - National 4,950.00 0.00 2020-12-30 2021-01-20 2021-03-05 2021-04-04 2021-05-09 2021-11-05 silience ution eillance des travaux de l'EP s des consultants DIKONGAYI/KC ZR-FSRDC-191902-CS-CQS / Recrutement d'un consultant Sélection fondée s pour la mise en place et suivi En attente d'exéc IDA / 66650 5. CERC A posteriori ur les qualification Open - National 100,000.00 0.00 2020-09-07 2020-09-28 2020-11-11 2020-12-11 2021-01-15 2021-07-14 de l’auto-enregistrement par ution s des consultants téléphone mobile des person nes éligibles sur le registre d es bénéficiaires. ZR-FSRDC-256194-CS-CQS / Recrutement d’une Structure chargée du Renforcement de Capacités en MEDAC des Bén Sélection fondée s 2. Livelihoods and Employm En cours d'exécut éficiaires THIMO pour la ville IDA / 66650 A posteriori ur les qualification Open - National 25,000.00 0.00 2021-11-30 2021-10-04 2021-12-21 2022-02-03 2022-03-05 2022-04-09 2022-10-06 ent Generation ion de TSHIMBULU repartis en 2 l s des consultants ots de 500 bénéficiaires pou r chaque lot pour les quartier s TSHIABALA, LUBALA, N'SEL E, MITENGU. CF obs- ci-desso us Page 10 ZR-FSRDC-256197-CS-CQS / Recrutement d’une Structure chargée du Renforcement de Capacités en MEDAC des Bén Sélection fondée s 2. Livelihoods and Employm En cours d'exécut éficiaires THIMO pour la ville IDA / 66650 A posteriori ur les qualification Open - National 37,500.00 0.00 2021-11-30 2021-10-04 2021-12-21 2022-02-03 2022-03-05 2022-04-09 2022-10-06 ent Generation ion de DIBAYA repartis en 3 lots s des consultants de 500 bénéficiaires pour ch aque lot pour les quartiers IN GA, MISSION, TUBADI, LUKUL A, CENTRAL, KABUYA: ZR-FSRDC-256199-CS-CQS / Recrutement d’une Structure chargée du Renforcement de Capacités en MEDAC des Bén Sélection fondée s 2. Livelihoods and Employm En cours d'exécut éficiaires THIMO pour la ville IDA / 66650 A posteriori ur les qualification Open - National 175,000.00 0.00 2021-11-30 2021-10-04 2021-12-21 2022-02-03 2022-03-05 2022-04-09 2022-10-06 ent Generation ion de Kananga repartis en 14 lo s des consultants ts de 500 bénéficiaires pour chaque lot pour 28 quartiers de la ville de kananga ci-dess ous les lots repartis: ZR-FSRDC-277785-CS-CQS / Agence de communication p Sélection fondée s En cours d'exécut our pour concevoir et produir IDA / 66650 5. CERC A posteriori ur les qualification Open - National 50,000.00 0.00 2022-06-30 2022-03-07 2022-07-21 2022-09-03 2022-10-03 2022-11-07 2023-05-06 ion e les supports de communica s des consultants tion et de visibilité pour le pr ojet STEP-KIN du FSRDC ZR-FSRDC ITURI-305745-CS- CQS / Recrutement des struc t pour la formation en MEDA C de 2000 bénéficiaires d'Aru Sélection fondée s et d'Ariwara à raison de 500 2. Livelihoods and Employm En attente d'exéc IDA / 66650 A posteriori ur les qualification Open - National 60,000.00 0.00 2022-12-19 2023-01-09 2023-02-22 2023-03-24 2023-04-28 2023-10-25 bénéf par struct et 250 bénéf ent Generation ution s des consultants par quart Lot 1: Q. Route Aba et Esefe Lot 2: Q. Katanga et Rumu Lot 3: Q. Male1 et Male2 Lot 4: Q. Dema 1 et Dema2 ZR-FSRDC ITURI-305746-CS- CQS / Recrutement des struc tures pour la formation en M EDAC de 750 bénéficiaires da Sélection fondée s 2. Livelihoods and Employm En attente d'exéc ns la cité d'Ariwara à raison d IDA / 66650 A posteriori ur les qualification Open - National 22,500.00 0.00 2022-12-19 2023-01-09 2023-02-22 2023-03-24 2023-04-28 2023-10-25 ent Generation ution 'un max de 250 bénéficiaires s des consultants par structure et par quartier Lot 1: Quartier d'Ozua Lot 2: Quartier d'Alikodri Lot 3: Quartier d'Ariwara ZR-FSRDC ITURI-294025-CS- CQS / Recrutement Struct. ch argées de Renforcement des capacités des 2000 bénéf THI MO des quartiers de Bunia en Sélection fondée s 2. Livelihoods and Employm En attente d'exéc MEDAC, subdivisé en 4 lots: IDA / 66650 A posteriori ur les qualification Open - National 60,000.00 0.00 2022-07-18 2022-08-08 2022-09-21 2022-10-21 2022-11-25 2023-05-24 ent Generation ution Lot 1: Q Bigo et Mudzipela s des consultants Lot 2: Q Kasegwa et Bembey Lot 3: Q Rwambuzi Beni et B akongolo Lot 4: Q Rwankole et Kindia ZR-FSRDC ITURI-305747-CS- CQS / Recrut des struct pour la forma en MEDAC de 2500 bénéf d'Ariwara à raison de 5 00 bén par St et 250 bén par Sélection fondée s 2. Livelihoods and Employm En attente d'exéc Qr IDA / 66650 A posteriori ur les qualification Open - National 60,000.00 0.00 2022-12-19 2023-01-09 2023-02-22 2023-03-24 2023-04-28 2023-10-25 ent Generation ution Lot 1: Q. Angarakali1 et Anga s des consultants rakali2 Lot 2: Q. Angarakali3 et Dran zoni Lot 3: Q. Ombayi et Andia Lot 4: Q. Onya1 et Onya2 Lot5: Q Erivu et Malemb ZR-FSRDC ITURI-305748-CS- CQS / Recrutement d'une str ucture pour la formation en Sélection fondée s 2. Livelihoods and Employm MEDAC de 500 bénéficiaires IDA / 66650 A posteriori ur les qualification Open - National 15,000.00 0.00 Annulé 2022-12-19 2023-01-09 2023-02-22 2023-03-24 2023-04-28 2023-10-25 ent Generation de la cité d'Ariwara dans les s des consultants quartiers d'Erivu et Malembe à raison de 250 bénéficiaires par quartier ZR-FSRDC ITURI-294024-CS- CQS / Recrutement de Struct chargées de Renforcement d es capacités des 2000 bénéf THIMO des quartiers de Buni Sélection fondée s 2. Livelihoods and Employm En attente d'exéc a en MEDAC subdivisé en 4 l IDA / 66650 A posteriori ur les qualification Open - National 60,000.00 0.00 2022-08-15 2022-09-05 2022-10-19 2022-11-18 2022-12-23 2023-06-21 ent Generation ution ots: s des consultants Lot 1: Q Rwambuzi Fichama et Ngezi Lot 2: Q Bankoko et Opas Lot 3: Q Lembabo et Ndiba K odu Lot 4: Q Simbiliabo et Saio ZR-FSRDC ITURI-294017-CS- CQS / Recrutement des Struc t chargées de Renforcement des capacités des 2000 béné f THIMO des quartiers de Bun Sélection fondée s 2. Livelihoods and Employm En attente d'exéc ia en MEDAC subdivisé en 4 l IDA / 66650 A posteriori ur les qualification Open - National 60,000.00 0.00 2022-08-15 2022-09-05 2022-10-19 2022-11-18 2022-12-23 2023-06-21 ent Generation ution ots: s des consultants Lot 1: Q Lumumba et Hoho Lot 2: Q Yambi et Dele Lot 3: Q Nyakasanza 1 et Ny akasanza 2 Lot 4: Q Sukisa et Salongo INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Identifie Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amoun Draft Negotiated Con Description Component Review Type Method Process Status Terms of Reference d/Selected Consultan Signed Contract Contract Completion o. h unt (US$) t (US$) tract t Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ZR-FSRDC-232855-CS-INDV / En cours d'exécut IDA / 66650 4. Project Management A posteriori Individuel Open 39,600.00 0.00 2021-06-30 2021-06-01 2021-08-18 2021-09-08 2021-10-13 2022-04-11 Chargé des MESDAC/KC ion ZR-FSRDC-232861-CS-INDV / En cours d'exécut IDA / 66650 4. Project Management A posteriori Individuel Limited 12,020.00 0.00 2021-06-30 2021-06-21 2021-07-05 2021-07-26 2021-08-30 2022-02-26 Caissier/KC ion ZR-FSRDC-232863-CS-INDV / En attente d'exéc IDA / 66650 4. Project Management A posteriori Individuel Limited 12,020.00 0.00 2021-09-30 2021-10-05 2021-10-26 2021-11-30 2022-05-29 Chauffeur 1 des courses/KC ution ZR-FSRDC-232864-CS-INDV / En attente d'exéc IDA / 66650 4. Project Management A posteriori Individuel Limited 12,020.00 0.00 2021-09-30 2021-10-05 2021-10-26 2021-11-30 2022-05-29 Chauffeur 2 des courses/KC ution ZR-FSRDC-232865-CS-INDV / En attente d'exéc IDA / 66650 4. Project Management A posteriori Individuel Limited 12,020.00 0.00 2021-09-30 2021-10-05 2021-10-26 2021-11-30 2022-05-29 Chauffeur 3 des courses/KC ution ZR-FSRDC-236277-CS-INDV / 1. Support to Community Re En attente d'exéc IDA / 66650 A posteriori Individuel Limited 7,200.00 0.00 2020-12-18 2020-12-23 2021-01-13 2021-02-17 2021-08-16 Consultant en appui STIC/KC silience ution ZR-FSRDC-236355-CS-INDV / 1. Support to Community Re En attente d'exéc IDA / 66650 A posteriori Individuel Open 7,200.00 0.00 2020-12-18 2021-02-05 2021-02-26 2021-04-02 2021-09-29 Consultant en appui STIC/KC silience ution ZR-FSRDC-236035-CS-INDV / 1. Support to Community Re En attente d'exéc CI pour contrôle et Surveillan IDA / 66650 A posteriori Individuel Open 4,600.00 0.00 2020-12-30 2021-02-17 2021-03-10 2021-04-14 2021-10-11 silience ution ce des travaux de l'EP Kapaji ka/KC ZR-FSRDC-236161-CS-INDV / 1. Support to Community Re En attente d'exéc CI pour contrôle et Surveillan IDA / 66650 A posteriori Individuel Open 4,600.00 0.00 2020-12-30 2021-02-17 2021-03-10 2021-04-14 2021-10-11 silience ution ce des travaux de l'EP Tshiba shi/KC ZR-FSRDC-236401-CS-INDV / Consultant Individuel pour co 1. Support to Community Re En attente d'exéc IDA / 66650 A posteriori Individuel Open 4,200.00 0.00 2020-12-30 2021-02-17 2021-03-10 2021-04-14 2021-10-11 ntrôle et Surveillance des tra silience ution vaux de l'EP Diku Dietu/KC ZR-FSRDC-236400-CS-INDV / Consultant Individuel pour le 1. Support to Community Re En attente d'exéc IDA / 66650 A posteriori Individuel Open 3,338.00 0.00 2020-12-30 2021-02-17 2021-03-10 2021-04-14 2021-10-11 contrôle et Surveillance des t silience ution ravaux de l'EP DJAKAJA/KC ZR-FSRDC-236092-CS-INDV / Consultants en appui au STHI 2. Livelihoods and Employm En attente d'exéc IDA / 66650 A posteriori Individuel Open 7,500.00 0.00 2020-12-25 2021-02-12 2021-03-05 2021-04-09 2021-10-06 MO pour la supervision des c ent Generation ution hantiers THIMO à Kananga ZR-FSRDC-236094-CS-INDV / Consultants en appui au STHI 2. Livelihoods and Employm En attente d'exéc IDA / 66650 A posteriori Individuel Open 7,500.00 0.00 2020-12-25 2021-02-12 2021-03-05 2021-04-09 2021-10-06 MO pour la supervision des c ent Generation ution hantiers THIMO à Kananga Page 11 ZR-FSRDC-236514-CS-INDV / Consultants en appui au STHI 2. Livelihoods and Employm En attente d'exéc IDA / 66650 A posteriori Individuel Open 7,500.00 0.00 2020-12-25 2021-02-12 2021-03-05 2021-04-09 2021-10-06 MO pour la supervision des c ent Generation ution hantiers THIMO à Kananga ZR-FSRDC-236279-CS-INDV / 2. Livelihoods and Employm En attente d'exéc IDA / 66650 A posteriori Individuel Open 9,000.00 0.00 2020-12-21 2021-02-08 2021-03-01 2021-04-05 2021-10-02 Consultant en appui SSS/KC ent Generation ution ZR-FSRDC-237038-CS-INDV / 1. Support to Community Re En attente d'exéc IDA / 66650 A posteriori Individuel Limited 7,200.00 0.00 2021-04-12 2021-04-17 2021-05-08 2021-06-12 2021-12-09 Consultant en appui STIC/KC silience ution ZR-FSRDC-237039-CS-INDV / 1. Support to Community Re En attente d'exéc IDA / 66650 A posteriori Individuel Limited 7,200.00 0.00 2021-04-12 2021-04-17 2021-05-08 2021-06-12 2021-12-09 Consultant en appui STIC/KC silience ution ZR-FSRDC-237034-CS-INDV / Consultants en appui au STHI 2. Livelihoods and Employm En attente d'exéc IDA / 66650 A posteriori Individuel Limited 7,500.00 0.00 2021-04-12 2021-04-17 2021-05-08 2021-06-12 2021-12-09 MO pour la supervision des c ent Generation ution hantiers THIMO à Kananga ZR-FSRDC-237040-CS-INDV / Consultants en appui au STHI 2. Livelihoods and Employm En attente d'exéc IDA / 66650 A posteriori Individuel Limited 7,500.00 0.00 2021-04-12 2021-04-17 2021-05-08 2021-06-12 2021-12-09 MO pour la supervision des c ent Generation ution hantiers THIMO à Kananga ZR-FSRDC-237037-CS-INDV / Consultants en appui au STHI 2. Livelihoods and Employm En attente d'exéc IDA / 66650 A posteriori Individuel Limited 7,500.00 0.00 2021-04-12 2021-04-17 2021-05-08 2021-06-12 2021-12-09 MO pour la supervision des c ent Generation ution hantiers THIMO à Kananga ZR-FSRDC-237035-CS-INDV / Consultants en appui pour le 1. Support to Community Re En attente d'exéc IDA / 66650 A posteriori Individuel Limited 7,500.00 0.00 2021-04-12 2021-04-17 2021-05-08 2021-06-12 2021-12-09 suivi environnemental et soci silience ution al de kananga ZR-FSRDC-239849-CS-INDV / Recrutement d'un consultant 1. Support to Community Re En attente d'exéc individuel pour le contrôle et IDA / 66650 A posteriori Individuel Limited 4,600.00 0.00 2021-07-21 2021-07-26 2021-08-16 2021-09-20 2022-03-19 silience ution surveillance de l'EP BISHIYA dans le secteur de DIBANDA_ KC ZR-FSRDC-239851-CS-INDV / Recrutement d'un consultant 1. Support to Community Re En attente d'exéc individuel pour le contrôle et IDA / 66650 A posteriori Individuel Limited 4,600.00 0.00 2021-07-20 2021-07-25 2021-08-15 2021-09-19 2022-03-18 silience ution surveillance de l'EP MUAKAJI dans le secteur de DIBANDA_ KC ZR-FSRDC-239852-CS-INDV / Recrutement d'un consultant 1. Support to Community Re En attente d'exéc individuel pour le contrôle et IDA / 66650 A posteriori Individuel Limited 4,600.00 0.00 2021-07-20 2021-07-25 2021-08-15 2021-09-19 2022-03-18 silience ution surveillance de l'EP1 DIBAND A dans le secteur de DIBAND A_KC ZR-FSRDC-239853-CS-INDV / Recrutement d'un consultant 1. Support to Community Re En attente d'exéc individuel pour le contrôle et IDA / 66650 A posteriori Individuel Limited 4,600.00 0.00 2021-07-20 2021-07-25 2021-08-15 2021-09-19 2022-03-18 silience ution surveillance de l'EP NDIBU K ALAMBA dans le secteur de K ASANGIDI_KC ZR-FSRDC-239856-CS-INDV / Recrutement d'un consultant 1. Support to Community Re En attente d'exéc individuel pour le contrôle et IDA / 66650 A posteriori Individuel Limited 4,600.00 0.00 2021-07-21 2021-07-26 2021-08-16 2021-09-20 2022-03-19 silience ution surveillance de l'EP LUAJA da ns le secteur de KASANGIDI_ KC ZR-FSRDC-239857-CS-INDV / Recrutement d'un consultant 1. Support to Community Re En attente d'exéc individuel pour le contrôle et IDA / 66650 A posteriori Individuel Limited 4,500.00 0.00 2021-07-22 2021-07-27 2021-08-17 2021-09-21 2022-03-20 silience ution surveillance de l'EP3 LUKULA dans le secteur de KASANGID I_KC ZR-FSRDC-239858-CS-INDV / Recrutement d'un consultant 1. Support to Community Re En attente d'exéc individuel pour le contrôle et IDA / 66650 A posteriori Individuel Limited 4,600.00 0.00 2021-07-22 2021-07-27 2021-08-17 2021-09-21 2022-03-20 silience ution surveillance de l'EP1 BASANG A dans le secteur de KASANG IDI_KC ZR-FSRDC-239859-CS-INDV / Recrutement d'un consultant 1. Support to Community Re En attente d'exéc individuel pour le contrôle et IDA / 66650 A posteriori Individuel Limited 4,600.00 0.00 2021-07-23 2021-07-28 2021-08-18 2021-09-22 2022-03-21 silience ution surveillance de l'EP NTUADIJI LU dans le secteur de KASAN GIDI_KC ZR-FSRDC-239860-CS-INDV / Recrutement d'un consultant 1. Support to Community Re En attente d'exéc individuel pour le contrôle et IDA / 66650 A posteriori Individuel Limited 4,600.00 0.00 2021-07-26 2021-07-31 2021-08-21 2021-09-25 2022-03-24 silience ution surveillance de l'EP MAMBAS AKO dans le secteur de KASA NGIDI_KC ZR-FSRDC-239861-CS-INDV / Recrutement d'un consultant 1. Support to Community Re En attente d'exéc individuel pour le contrôle et IDA / 66650 A posteriori Individuel Limited 4,600.00 0.00 2021-07-27 2021-08-01 2021-08-22 2021-09-26 2022-03-25 silience ution surveillance de l'EP TSHIMAK AKA dans le secteur de KASA NGIDI_KC ZR-FSRDC-243735-CS-INDV / Recrutement de deux (2) con 1. Support to Community Re En attente d'exéc sultants Ingénieurs en Appui IDA / 66650 A posteriori Individuel Open 100,000.00 0.00 2021-08-14 2021-10-02 2021-10-23 2021-11-27 2022-05-26 silience ution CTIC dans la ville de Kanang a et dans les cités de Dibaya et de Tshimbulu ZR-FSRDC-243745-CS-INDV / Recrutement de trois (3) Con sultant DPO pour le suivi et l 1. Support to Community Re En attente d'exéc IDA / 66650 A posteriori Individuel Open 22,500.00 0.00 2021-08-14 2021-10-02 2021-10-23 2021-11-27 2022-05-26 e contrôle des travaux de co silience ution nstruction des IDB dans le se cteur DIBANDA (EP BISHIYA, EP MUAKAJI et EP1 DIBANDA) ZR-FSRDC-244035-CS-INDV / Recrutement d’un Consultant DPO pour le suivi et le contrô 1. Support to Community Re En attente d'exéc IDA / 66650 A posteriori Individuel Open 6,000.00 0.00 2021-08-16 2021-10-04 2021-10-25 2021-11-29 2022-05-28 le des travaux de réhabilitati silience ution on de l’Hôpital Général du qu artier LUKONGA à Kananga ZR-FSRDC-244127-CS-INDV / Recrutement de deux (2) sup En attente d'exéc IDA / 66650 4. Project Management A posteriori Individuel Limited 18,000.00 0.00 2021-08-16 2021-08-21 2021-09-11 2021-10-16 2022-04-14 erviseurs AST pour le Kasaï C ution entral (Tshimbulu/ Dibaya et Tshimbulu rural) ZR-FSRDC-244222-CS-INDV / En attente d'exéc Recrutement d'un Supervise IDA / 66650 4. Project Management A posteriori Individuel Limited 9,000.00 0.00 2021-08-16 2021-08-21 2021-09-11 2021-10-16 2022-04-14 ution ur AST pour l’Ituri ZR-FSRDC-245019-CS-INDV / Recrutement de vingt sept (2 2. Livelihoods and Employm En attente d'exéc 7) Consultant enquêteurs po IDA / 66650 A posteriori Individuel Open 48,600.00 0.00 2021-08-22 2021-10-10 2021-10-31 2021-12-05 2022-06-03 ent Generation ution ur la collecte des données de mise en œuvre des activités des THIMO et des TIC ZR-FSRDC-253936-CS-INDV / 2. Livelihoods and Employm En attente d'exéc IDA / 66650 A posteriori Individuel Limited 9,000.00 0.00 2021-10-20 2021-10-25 2021-11-15 2021-12-20 2022-06-18 Recrutement de 30 AST pour ent Generation ution les TMI ZR-FSRDC-262031-CS-INDV / (1): Recrutement d'un Assist En attente d'exéc ant en Gestion des Bases des IDA / 66650 4. Project Management A posteriori Individuel Limited 24,000.00 0.00 2021-12-24 2021-12-29 2022-01-19 2022-02-23 2022-08-22 ution données du projet STEP2/Ant enne du Kasaï Central ZR-FSRDC-264821-CS-INDV / (8): Recrutement de 17 cons ultants individuels (DPO) pou 1. Support to Community Re En attente d'exéc IDA / 66650 A posteriori Individuel Limited 95,625.00 0.00 2022-03-16 2022-03-21 2022-04-11 2022-05-16 2022-11-12 r le contrôle et surveillance d silience ution es travaux de construction d es écoles dans deux secteurs au Kasaï Central ZR-FSRDC-264823-CS-INDV / (9): Recrutement de 9 consul tants individuels (DPO) pour l 1. Support to Community Re En attente d'exéc IDA / 66650 A posteriori Individuel Limited 50,625.00 0.00 2022-03-16 2022-03-21 2022-04-11 2022-05-16 2022-11-12 e contrôle et surveillance des silience ution travaux de construction des centres de santé dans deux s ecteurs au Kasaï central Page 12 ZR-FSRDC-264825-CS-INDV / (10): Recrutement de 4 cons ultants individuels (DPO) pou 1. Support to Community Re En attente d'exéc IDA / 66650 A posteriori Individuel Limited 22,500.00 0.00 2022-03-17 2022-03-22 2022-04-12 2022-05-17 2022-11-13 r le contrôle et surveillance d silience ution es travaux de forage mécani que d’eau dans deux secteur s du Kasaï Central ZR-FSRDC-264831-CS-INDV / (16): Recrutement de 17 PFE 1. Support to Community Re En attente d'exéc dans le cadre de la constructi IDA / 66650 A posteriori Individuel Limited 38,250.00 0.00 2022-03-16 2022-03-21 2022-04-11 2022-05-16 2022-11-12 silience ution on des écoles dans les secte urs Dibataie et Kamuandu au Kasaï Central ZR-FSRDC-264834-CS-INDV / (17): Recrutement de 9 PFE d 1. Support to Community Re En attente d'exéc ans le cadre de la constructio IDA / 66650 A posteriori Individuel Limited 20,250.00 0.00 2022-03-18 2022-03-23 2022-04-13 2022-05-18 2022-11-14 silience ution n des centres de santé dans l es secteurs Dibataie et Kamu andu au Kasaï Central ZR-FSRDC-264837-CS-INDV / (18): Recrutement de 4 PFE d 1. Support to Community Re En attente d'exéc ans le cadre des travaux de f IDA / 66650 A posteriori Individuel Limited 9,000.00 0.00 2022-03-16 2022-03-21 2022-04-11 2022-05-16 2022-11-12 silience ution orage mécanique d’eau dans les secteurs Dibataie et Kam uandu au Kasaï Central ZR-FSRDC-264849-CS-INDV / En attente d'exéc (2): Assistant en Gestion de IDA / 66650 4. Project Management A posteriori Individuel Limited 24,600.00 0.00 2021-12-24 2021-12-29 2022-01-19 2022-02-23 2022-08-22 ution Base des Données pour le Ka saï Central ZR-FSRDC-265065-CS-INDV / En attente d'exéc (9): Assistant en Gestion de IDA / 66650 4. Project Management A posteriori Individuel Limited 24,600.00 0.00 2022-01-12 2022-01-17 2022-02-07 2022-03-14 2022-09-10 ution Base des Données de l'Ituri ZR-FSRDC-265069-CS-INDV / En cours d'exécut (10): Assistant du Suivi du Nu IDA / 66650 4. Project Management A posteriori Individuel Limited 24,600.00 0.00 2022-01-12 2022-02-01 2022-01-17 2022-02-07 2022-03-14 2022-09-10 ion méro Vert de l'Ituri ZR-FSRDC-265075-CS-INDV / En attente d'exéc (12): Assistant Administratif IDA / 66650 4. Project Management A posteriori Individuel Limited 24,600.00 0.00 2022-01-12 2022-01-17 2022-02-07 2022-03-14 2022-09-10 ution et Financier de l'Ituri ZR-FSRDC-266685-CS-INDV / (14): Recrutement de 2 AST dans le cadre de la constructi En attente d'exéc IDA / 66650 4. Project Management A posteriori Individuel Limited 4,500.00 0.00 2022-03-21 2022-03-26 2022-04-16 2022-05-21 2022-11-17 on des centres de santé dans ution les secteurs de Dibataie et et Kamuandu au Kasaï Central ZR-FSRDC-266687-CS-INDV / (15): Recrutement d'un AST dans le cadre des travaux de En attente d'exéc IDA / 66650 4. Project Management A posteriori Individuel Limited 2,250.00 0.00 2022-03-15 2022-03-20 2022-04-10 2022-05-15 2022-11-11 forage mécanique d'eau dan ution s les secteurs de Dibataie et et Kamuandu au Kasaï Centr al ZR-FSRDC-267016-CS-INDV / (42): RECRUTEMENT DES 30 2. Livelihoods and Employm En attente d'exéc CONSULTANTS – AGENT DE S IDA / 66650 A posteriori Individuel Limited 27,000.00 0.00 2021-10-10 2021-10-15 2021-11-05 2021-12-10 2022-06-08 ent Generation ution UIVI DE TERRAIN (ENQUETEU RS) POUR LA MISE EN ŒUVR E DE TMI A LEMBO ZR-FSRDC-266682-CS-INDV / (13): Recrutement de 17 AST En attente d'exéc dans le cadre de la constructi IDA / 66650 4. Project Management A posteriori Individuel Limited 15,750.00 0.00 2022-03-10 2022-03-15 2022-04-05 2022-05-10 2022-11-06 ution on des écoles dans les secte urs de Dibataie et et Kamuan du au Kasaï Central ZR-FSRDC-272123-CS-INDV / (16): Recrutement des 6 con 2. Livelihoods and Employm En cours d'exécut sultants Individuels pour la m IDA / 66650 A posteriori Individuel Limited 54,000.00 0.00 2022-03-15 2021-12-28 2022-03-20 2022-04-10 2022-05-15 2022-11-11 ent Generation ion ission de supervision des cha ntiers THIMO dans la ville de Bunia-Ituri ZR-FSRDC-272125-CS-INDV / (17): Recrutement des 24 co 2. Livelihoods and Employm En cours d'exécut nsultants Individuels pour la IDA / 66650 A posteriori Individuel Limited 57,600.00 0.00 2022-03-15 2021-12-28 2022-03-20 2022-04-10 2022-05-15 2022-11-11 ent Generation ion mission de chef de chantier d es THIMO à Bunia-Ituri ZR-FSRDC-272128-CS-INDV / (18): Recrutement des 240 c 2. Livelihoods and Employm En cours d'exécut onsultants Individuels pour la IDA / 66650 A posteriori Individuel Limited 288,000.00 0.00 2022-03-15 2021-12-28 2022-03-20 2022-04-10 2022-05-15 2022-11-11 ent Generation ion mission de chef d’équipe des chantiers THIMO à Bunia-Ituri ZR-FSRDC-272131-CS-INDV / (19): Recrutement des 24 co 2. Livelihoods and Employm En cours d'exécut IDA / 66650 A posteriori Individuel Limited 43,200.00 0.00 2022-03-15 2021-12-28 2022-03-20 2022-04-10 2022-05-15 2022-11-11 nsultants Individuels pour la ent Generation ion mission de PFE des chantiers THIMO à Bunia-Ituri ZR-FSRDC-272669-CS-INDV / (20): Recrutement de 24 con En cours d'exécut sultants individuels pour la m IDA / 66650 4. Project Management A posteriori Individuel Limited 43,200.00 0.00 2022-03-30 2021-12-28 2022-04-04 2022-04-25 2022-05-30 2022-11-26 ion ission des Agent de Suivi de Terrain (AST) de 24 chantiers THIMO à Bunia-Ituri ZR-FSRDC-272673-CS-INDV / (50): Recrutement de 18 con 2. Livelihoods and Employm En attente d'exéc sultants individuels pour la m IDA / 66650 A posteriori Individuel Limited 43,200.00 0.00 2022-03-30 2022-04-04 2022-04-25 2022-05-30 2022-11-26 ent Generation ution ission de chef de chantier de s THIMO à Goma-Nord Kivu ZR-FSRDC-274776-CS-INDV / Recrutement de 30 DPO pour 1. Support to Community Re En cours d'exécut IDA / 66650 A posteriori Individuel Limited 213,750.00 0.00 2022-06-30 2022-02-10 2022-07-05 2022-07-26 2022-08-30 2023-02-26 le contrôle et surveillance de silience ion s travaux des IDB ZR-FSRDC-274720-CS-INDV / (15) Recrutement de 3 Ingéni eurs Superviseurs en Appui a 1. Support to Community Re En cours d'exécut IDA / 66650 A posteriori Individuel Limited 27,000.00 0.00 2022-06-30 2022-02-08 2022-07-05 2022-07-26 2022-08-30 2023-02-26 u CTIC pour les travaux des I silience ion DB (1 superviseur pour 10 ID B) et (1 500 $*6mois pour ch aque superviseur) _ ITURI ZR-FSRDC-278087-CS-INDV / 1 (KC-C2) Recrutement des 8 consultants Individuels pour l 2. Livelihoods and Employm En attente d'exéc IDA / 66650 A posteriori Individuel Limited 72,000.00 0.00 2022-08-31 2022-09-05 2022-09-26 2022-10-31 2023-04-29 a mission de supervision des ent Generation ution chantiers THIMO dans la cité de Kazumba (5) et Matamba (3)_ KC ZR-FSRDC-278089-CS-INDV / 2 (KC-C2) Recrutement des 3 2. Livelihoods and Employm En attente d'exéc 4 consultants Individuels pou IDA / 66650 A posteriori Individuel Limited 81,600.00 0.00 2022-08-31 2022-09-05 2022-09-26 2022-10-31 2023-04-29 ent Generation ution r la mission de chef de chanti er des THIMO à Kazumba (21 ) et Matamba (13)_ KC ZR-FSRDC-278096-CS-INDV / 4 (KC-C2) Recrutement des 3 2. Livelihoods and Employm En attente d'exéc 4 consultants Individuels pou IDA / 66650 A posteriori Individuel Limited 61,200.00 0.00 2022-08-31 2022-09-05 2022-09-26 2022-10-31 2023-04-29 ent Generation ution r la mission de PFE des chant iers THIMO à Kazumba (21) e t Matamba (13)_ KC ZR-FSRDC-278098-CS-INDV / 5 (KC-C4) Recrutement des 3 4 consultants Individuels pou En attente d'exéc IDA / 66650 4. Project Management A posteriori Individuel Limited 61,200.00 0.00 2022-08-31 2022-09-05 2022-09-26 2022-10-31 2023-04-29 r la mission des Agents de su ution ivi de terrain (AST) des chant iers THIMO à Kazumba (21) e t Matamba (13)_ KC ZR-FSRDC-278099-CS-INDV / 6 (KC-C2) Recrutement de de 2. Livelihoods and Employm En attente d'exéc ux consultants superviseurs IDA / 66650 A posteriori Individuel Limited 18,000.00 0.00 2022-09-30 2022-10-05 2022-10-26 2022-11-30 2023-05-29 ent Generation ution des activités de PFE à Kazum ba (1) et Matamba (1)_ KC ZR-FSRDC-278100-CS-INDV / 7 (KC-C4) Recrutement de de En attente d'exéc ux consultants superviseurs IDA / 66650 4. Project Management A posteriori Individuel Limited 18,000.00 0.00 2022-08-31 2022-09-05 2022-09-26 2022-10-31 2023-04-29 ution des activités des AST à Kazu mba (1) et Matamba (1)_ KC ZR-FSRDC-278104-CS-INDV / 8 (KC-C4) Recrutement deux En attente d'exéc consultants points focaux de IDA / 66650 4. Project Management A posteriori Individuel Limited 24,000.00 0.00 2022-08-31 2022-09-05 2022-09-26 2022-10-31 2023-04-29 ution l’équipe de zone des activité s à Kazumba (1) et Matamba (1)_ KC Page 13 ZR-FSRDC-278105-CS-INDV / 9 (KC-C4) Recrutement un co En attente d'exéc nsultant Assistant Administra IDA / 66650 4. Project Management A posteriori Individuel Limited 9,000.00 0.00 2022-09-30 2022-10-05 2022-10-26 2022-11-30 2023-05-29 ution tif de l’équipe de zone des ac tivités à Kazumba et Matamb a_ KC ZR-FSRDC-278107-CS-INDV / 10 (KC-C4) Recrutement d’un En attente d'exéc consultant logisticien de l’éq IDA / 66650 4. Project Management A posteriori Individuel Limited 4,800.00 0.00 2022-08-31 2022-09-05 2022-09-26 2022-10-31 2023-04-29 ution uipe de zone des activités à Kazumba et Matamba_ KC ZR-FSRDC ITURI-303789-CS- INDV / Recrutement d'un Assi En attente d'exéc stant en Passation des March IDA / 66650 4. Project Management A posteriori Individuel Limited 16,200.00 0.00 2022-09-12 2022-09-17 2022-10-08 2022-11-12 2023-05-11 ution és pour le Projet STEP 2 dédi é à l'antenne provinciale d'It uri ZR-FSRDC ITURI-317372-CS- INDV / Recrutement de 4 Con 2. Livelihoods and Employm En attente d'exéc sultants Individuels pour la m IDA / 66650 A posteriori Individuel Limited 36,000.00 0.00 2022-11-14 2022-11-19 2022-12-10 2023-01-14 2023-07-13 ent Generation ution ission de supervision des cha ntiers THIMO dans la ville de Mahagi en Ituri ZR-FSRDC ITURI-317374-CS- INDV / Recrutement de 14 Co 2. Livelihoods and Employm En attente d'exéc nsultants Individuels pour la IDA / 66650 A posteriori Individuel Limited 33,600.00 0.00 2022-11-14 2022-11-19 2022-12-10 2023-01-14 2023-07-13 ent Generation ution mission de chefs des chantie rs THIMO dans la ville de Mah agi en Ituri ZR-FSRDC ITURI-317379-CS- INDV / Recrutement de 140 C 2. Livelihoods and Employm En attente d'exéc onsultants Individuels pour la IDA / 66650 A posteriori Individuel Limited 168,000.00 0.00 2022-11-14 2022-11-19 2022-12-10 2023-01-14 2023-07-13 ent Generation ution mission de chefs d’équipe de s chantiers THIMO dans la vill e de Mahagi en Ituri ZR-FSRDC ITURI-317390-CS- INDV / Recrutement de 62 Co 2. Livelihoods and Employm En attente d'exéc nsultants Individuels pour la IDA / 66650 A posteriori Individuel Limited 137,000.00 0.00 2022-11-14 2022-11-19 2022-12-10 2023-01-14 2023-07-13 ent Generation ution mission de PFE des chantiers THIMO et IDB dans le territoir e de Mahagi en Ituri ZR-FSRDC ITURI-317392-CS- INDV / Recrutement de 27 Co nsultants Individuels pour la En attente d'exéc IDA / 66650 4. Project Management A posteriori Individuel Limited 60,000.00 0.00 2022-11-14 2022-11-19 2022-12-10 2023-01-14 2023-07-13 mission des AST des chantier ution s THIMO, IDB et des TMI dans le territoire de Mahagi en Itur i ZR-FSRDC ITURI-317398-CS- INDV / Recrutement d’un Con En attente d'exéc sultant Superviseur des activi IDA / 66650 4. Project Management A posteriori Individuel Limited 9,000.00 0.00 2022-11-14 2022-11-19 2022-12-10 2023-01-14 2023-07-13 ution tés de PFE Thimo et IDB) dan s le territoire de Mahagi en It uri ZR-FSRDC ITURI-317399-CS- INDV / Recrutement d’un con En attente d'exéc IDA / 66650 4. Project Management A posteriori Individuel Limited 9,000.00 0.00 2022-11-14 2022-11-19 2022-12-10 2023-01-14 2023-07-13 sultant superviseur des activi ution tés des AST dans le territoire de Mahagi en Ituri ZR-FSRDC ITURI-317402-CS- INDV / Recrutement de cinq ( 5) Consultants Ingénieurs en 1. Support to Community Re En attente d'exéc IDA / 66650 A posteriori Individuel Limited 50,000.00 0.00 2022-11-14 2022-11-19 2022-12-10 2023-01-14 2023-07-13 appui au CTIC pour la constru silience ution ction des IDB dans les territoi res de Mahagi, Irumu et Djug u en Ituri ZR-FSRDC ITURI-317403-CS- INDV / Recrutement de quara nte-huit (48) Consultants DP 1. Support to Community Re En attente d'exéc O pour le contrôle et la surve IDA / 66650 A priori Individuel Limited 360,000.00 0.00 2022-11-14 2022-11-19 2022-12-10 2023-01-14 2023-07-13 silience ution illance des travaux d’infrastr uctures communautaires dan s les territoires de Mahagi, Ir umu et Djugu en Ituri ZR-FSRDC ITURI-318657-CS- INDV / Recrutement d’un con En attente d'exéc IDA / 66650 4. Project Management A posteriori Individuel Limited 12,000.00 0.00 2022-11-14 2022-11-19 2022-12-10 2023-01-14 2023-07-13 sultant point focal de l’équip ution e de zone des activités à Ma hagi ZR-FSRDC ITURI-318666-CS- INDV / Recrutement un consu En attente d'exéc IDA / 66650 4. Project Management A posteriori Individuel Limited 9,000.00 0.00 2022-11-14 2022-11-19 2022-12-10 2023-01-14 2023-07-13 ltant Assistant Administratif ution de l’équipe de zone des activ ités à Mahagi ZR-FSRDC ITURI-318667-CS- INDV / Recrutement d’un con En attente d'exéc IDA / 66650 4. Project Management A posteriori Individuel Limited 5,000.00 0.00 2022-11-14 2022-11-19 2022-12-10 2023-01-14 2023-07-13 sultant logisticien de l’équipe ution de zone des activités à Maha gi ZR-FSRDC ITURI-356520-CS- INDV / Recrutement de 6 Con 2. Livelihoods and Employm En attente d'exéc sultants individuels pour la m IDA / 66650 A posteriori Individuel Limited 54,000.00 0.00 2023-04-30 2023-05-05 2023-05-26 2023-06-30 2023-12-27 ent Generation ution ission de supervision des cha ntiers THIMO dans la ville de Bunia. ZR-FSRDC ITURI-356490-CS- INDV / Recrutement de 24 co 2. Livelihoods and Employm En attente d'exéc nsultants Individuels pour la IDA / 66650 A posteriori Individuel Limited 100,800.00 0.00 2023-04-30 2023-05-05 2023-05-26 2023-06-30 2023-12-27 ent Generation ution mission de chef de chantier d es THIMO dans la ville de Bu nia en province de l'Ituri ZR-FSRDC ITURI-356512-CS- INDV / Recrutement de 336 c onsultants Individuels pour la 2. Livelihoods and Employm En attente d'exéc IDA / 66650 A posteriori Individuel Limited 403,200.00 0.00 2023-04-30 2023-05-05 2023-05-26 2023-06-30 2023-12-27 mission de chef d’équipes de ent Generation ution s chantiers THIMO dans la vill e de Bunia en province de l'It uri. ZR-FSRDC ITURI-356508-CS- INDV / Recrutement de 24 co 2. Livelihoods and Employm En attente d'exéc nsultants Individuels pour la IDA / 66650 A posteriori Individuel Limited 72,000.00 0.00 2023-04-30 2023-05-05 2023-05-26 2023-06-30 2023-12-27 ent Generation ution mission de PFES des chantier s THIMO dans la ville de Buni a en province de l'Ituri ZR-FSRDC ITURI-355362-CS- INDV / Recrutement de 24 co nsultants Individuels pour la En attente d'exéc IDA / 66650 4. Project Management A posteriori Individuel Limited 72,000.00 0.00 2023-04-30 2023-05-05 2023-05-26 2023-06-30 2023-12-27 mission des Agents de suivi d ution e terrain (AST) des chantiers THIMO dans la ville de Bunia en province de l'Ituri. ZR-FSRDC ITURI-357403-CS- En attente d'exéc INDV / Recrutement d'un Assi IDA / 66650 4. Project Management A posteriori Individuel Limited 13,300.00 0.00 2023-04-25 2023-04-30 2023-05-21 2023-06-25 2023-12-22 ution stant MEDAC pour l'Antenne de l'Ituri Page 14