REPUBLIC OF MALAWI Ministry of Water and Blantyre Water Board Blantyre City Council Sanitation 18-MONTHS PROCUREMENT PLAN FOR MALAWI WATER AND SANITATION PROJECT-1 (MWSP-1)- P174954 NOVEMBER 2022 1|Page General Project information Country Malawi Project Name Malawi Water and Sanitation Project (MWSP)-1 Project ID P178954 Project Implementation Blantyre Water Board (BWB) Agency 30th December 2022 Date of the Procurement Plan January 2023 to June 2024 Period covered by this Procurement Plan I. Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (November 2020) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. II. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. III. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. 1|Page When the Borrower uses its own national open competitive procurement arrangements as set forth in the Public Procurement and Disposal of Public Assets Act, 2017 of the Republic of Malawi, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations as follows:  Provision of “set-asides” contracts for small enterprises shall not be applied.  Criteria such as environmental aspect, extent of local content, technology transfer, and managerial, scientific & operational skills development shall not be used in the evaluation of bids unless specifically agreed by the Bank on case to case basis.  Procurement Documents include sufficient provisions, as agreed with the Bank, to adequately mitigate against environmental and social (including SEA/SH), risks and impacts; When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations. In accordance with paragraph 5.3 of the Procurement Regulations, the request for bids/request for proposals document shall require that Bidders/Proposers submitting Bids/Proposals present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights. The form of the Letter of Acceptance is attached in Appendix 1. IV. Prequalification. Not expected for the works/goods packages in the procurement plan. V. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. Not Applicable VI. Procurement of Second-Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables. Not Applicable. VII. Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). (a) Goods: Not Applicable for those contracts identified in the Procurement Plan tables. (b) Works: Not Applicable for those contracts identified in the Procurement Plan tables. 2|Page VIII. Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations: If requested by the Recipient, the World Bank will provide procurement hands-on expanded implementation support (HEIS) to help expedite preparation of bidding documents. IX. Other Relevant Procurement Information: - (a) Proposed Procedures for CDD Components: Not Applicable (b) Reference to (if any) Project Operational/Procurement Manual: Blantyre Water Board (BWB) will develop a Procurement Manual which will be part of the Project Implementation Manual (PIM) to elaborate procurement arrangements under the proposed Project. The Procurement Plan will also form part of the PIM. X. Procurement Approach and Prior Review Thresholds: Based on the overall procurement risk rating of “Substantial”, the thresholds for the Bank’s prior review and procurement method threshold are provided in the table below: Prior-review Thresholds for Procurement Methods Thresholds Procureme Substanti Works Goods, IT & Non-Consulting Shortlist of National nt al Services Consultants Type Risk ($`000) Works 10,000 Open Request Request Internatio for for Engineerin Open Open nal or Quotatio Open Quotatio Consultin g& Nation Nation ICB n or Internatio n or g Constructi al or al or ($'000 National nal or ICB National Services on NCB NCB Shoppin ($'000) Shoppin ($'000) Supervisio ($'000) ($'000) g g n ($'000) ($'000) ($'000) Goods, IT 2,000 & Non- Consulting ≧ < ≦ ≧ < ≦ < ≦ Services Consultant 1,000 s (Firms) Individual 300 7,000 7,000 200 1,000 1,000 100 200 300 Consultant s 3|Page XI. Procurement Packages/Plan with Procurement Arrangements and Time Schedule: as per the table below: A. Works 1 2 3 4 5 6 7 8 9 10 Ref Contract Description Estimated Procureme Selectio Prequalificati Domestic Bank Expected Expected No. Cost in US $ nt n on (yes/no) Preference Oversig bid Contract Approach/ Method (yes/no) ht opening Signature date Date Competitio n 1 Rehabilitation and upgrading of Mudi WTP 12,500,000.0 Open RFB No No Prior 06-Mar-24 10-May-24 and repairs to the Mudi 0 International Dam 2 Distribution Network 21,900,000.0 Open Upgrading Works for RFB No No Prior 20-Mar-24 24-May-24 0 International Blantyre 3 Priority Transmission 15,900,000.0 Open Network Upgrades for RFB No No Prior 20-Mar-24 24-May-24 0 International Blantyre 4 Extension of pipeline to unserved peri-urban areas Open 2,000,000.00 RFB No No Post 03-Apr-24 07-Jun-24 and Construction of smart National water Kiosks 5 Priority sewerage network 13,400,000.0 Open RFB No No Prior 06-Mar-24 10-May-24 upgrades for Blantyre 0 International 6 Construction of Recycling Open Plant and an Engineered 8,300,000.00 RFB No No Prior1 17-Apr-24 21-Jun-24 International Land Fill 1 The SEA/SH Rating is High hence Prior Review although the estimated cost is less than USD10,000,000 4|Page 1 2 3 4 5 6 7 8 9 10 Ref Contract Description Estimated Procureme Selectio Prequalificati Domestic Bank Expected Expected No. Cost in US $ nt n on (yes/no) Preference Oversig bid Contract Approach/ Method (yes/no) ht opening Signature date Date Competitio n 7 Construction of public Open toilets in Primary Schools, 2,000,000.00 RFB No No Post 06-Mar-24 10-May-24 National Markets and Clinics 8 Upgrading of PIU and PST Open 300,000.00 RFB No No Post 06-Mar-24 10-May-24 offices National B. Goods and Non-Consulting Services 1 2 3 4 5 6 7 8 9 10 Ref. No. Contract Estimated Market Selection Prequalifica Domestic Review Expected Expected Description Cost Approach Method tion Preference by Bank bid opening Contract US$ (yes/no) (yes/no) (Prior / date Signature Post) Date 1. Supply and Delivery of Open Project Supervision and 1,300,000.00 Internatio RFB No No Post 10-Apr-23 14-Jun-23 Operational vehicles nal 2. Supply and Delivery of Open new water connection 3,600,000.00 Internatio RFB No No Prior 10-Apr-23 14-Jun-23 materials nal 3. Procurement of various goods, furniture and Open- 450,000.00 RFB No No Post 10-Apr-23 14-Jun-23 equipment for BWB, BCC National the sector Ministry 5|Page C. Consultancy Services 1 2 3 4 5 6 7 8 9 Ref. Contract Estimated Market Approach Selection Shortlisting Review Expected Expected No. Description Cost Method (Yes/No) by Bank proposal Contract US$ (Prior / opening Signature Post) date Date 1. Consultancy Services for detailed design Open-International QCBS Yes Prior 22-March- and construction supervision of Blantyre 3,800,000.00 24-Jun-23 23 water supply network upgrades 2. Consultancy services for Dam Safety Open-International QCBS Yes Post Assessment and construction 750,000.00 22-Mar-23 24-Jun-23 supervision of Priority Dam Repairs for Mudi Dam 3. Consultancy services for detailed Open-International QCBS Yes Prior designs and construction supervision of 1,500,000.00 22-Mar-23 24-Jun-23 priority sanitation investments 4. Consultancy services for detailed Open-International QCBS Yes Post designs and construction supervision of 250,000.00 22-Mar-23 24-Jun-23 public sanitation facilities, PIU & PST Offices 5. Consultancy services for detailed Open-International QCBS Yes Prior designs and construction supervision of 1,500,000.00 05-Apr-23 08-Jul-23 a Recycling plant and an engineered landfill 6. Consultancy services for Development Open-International QCBS Yes Post of national water supply and sanitation investment plan for urban and rural and 300,000.00 05-Apr-23 08-Jul-23 formulation of Performance Based Financing agreement 7. Consultancy services for development of Open-National QCBS Yes Post 200,000.00 05-Apr-23 08-Jul-23 Water and Sanitation Act – proposal 8. Technical Assistance on Safeguards Open-International QCBS Yes Post Instruments for priority water supply and 600,000.00 19-Apr-23 22-Jul-23 sanitation investments 9. Consultancy services for sanitation Open-International QCBS Yes Post marketing 400,000.00 19-Apr-23 22-Jul-23 10. Consultancy Services for conduction of Open-International QCBS Yes Prior Feasibility study and detailed design for 2,000,000.00 04-Dec-23 07-Mar-24 Mulanje and Mombezi Dam 11. Consultancy Service for baseline study Open-National QCBS Yes Post 22-March- 200,000.00 24-Jun-23 for Blantyre Water Board 23 6|Page RFQ – Request form Quotation; RFB – Request form Bids; CQS- Consultant’s Based Qualifications; INDV - Individual Consultant Selection and DS– Direct Selection. 7|Page Appendix 1 Letter of Acceptance of the World Bank’s Anti-Corruption Guidelines and Sanctions Framework Date: 2 Invitation of Bids/Proposals No.__________ To: ___________________________________________________________________________ We, along with our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not) consultants and personnel, acknowledge and agree to abide by the World Bank’s policy regarding Fraud and Corruption (corrupt, fraudulent, collusive, coercive, and obstructive practices), as set out and defined in the World Bank’s Anti-Corruption Guidelines2 in connection with the procurement and execution of the contract (in case of award), including any amendments thereto. We declare and warrant that we, along our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not), consultants and personnel, , are not subject to, and are not controlled by any entity or individual that is subject to, a temporary suspension, early temporary suspension, or debarment imposed by a member of the World Bank Group, including, inter alia, a cross-debarment imposed by the World Bank Group as agreed with other international financial institutions (including multilateral development banks), or through the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement. Further, we are not ineligible under the laws or official regulations of [Insert name of Employer as per bidding document] or pursuant to a decision of the United Nations Security Council. We confirm our understanding of the consequences of not complying with the World Bank’s Anti-Corruption Guidelines, which may include the following: a. rejection of our Proposal/Bid for award of contract; b. in the case of award, termination of the contract, without prejudice to any other remedy for breach of contract; and c. sanctions, pursuant to the Bank’s Anti-Corruption Guidelines and in accordance with its prevailing sanctions policies and procedures as set forth in the Bank’s Sanctions Framework. This may include a public declaration of ineligibility, either indefinitely or for a stated period of time, (i) to be awarded or otherwise benefit from a Bank-financed contract, financially or 2Guidelines on Preventing and Combating Fraud and Corruption in Projects Financed by International Bank for Reconstruction and Development Loans and the International Development Agency Credits and Grants, dated October 15, 2006, and revised in January 2011 and July 2016, as they may be revised from time to time. 1|Page in any other manner;3 (ii) to be a nominated4 sub-contractor, consultant, manufacturer or supplier, or service provider of an otherwise eligible firm being awarded a Bank-financed contract; and (iii) to receive the proceeds of any loan made by the Bank or otherwise to participate further in the preparation or implementation of any Bank-financed project. We understand that we may be declared ineligible as set out above upon: a. completion of World Bank Group sanctions proceedings according to its prevailing sanctions procedures; b. cross-debarment as agreed with other international financial institutions (including multilateral development banks); c. the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement; or d. temporary suspension or early temporary suspension in connection with an ongoing World Bank Group sanctions proceeding. For avoidance of doubt, the foregoing effects of ineligibility do not extend to a sanctioned firm’s or individual’s execution of its ongoing Bank-financed contracts (or its ongoing sub-agreements under such contracts) that are not the subject of a material modification, as determined by the Bank. We shall permit, and shall cause our sub-contractors, sub-consultants, agents (whether declared or not), personnel, consultants, service providers or suppliers, to permit the Bank to inspect5 all accounts, records, and other documents relating to the procurement process and/or contract execution (in the case of award), and to have them audited by auditors appointed by the Bank. We agree to preserve all accounts, records, and other documents (whether in hard copy or electronic format) related to the procurement and execution of the contract. Name of the Bidder/Consultant: 3 For the avoidance of doubt, a sanctioned party’s ineligibility to be awarded a contract shall include, without limitation, (i) applying for pre-qualification, expressing interest in a consultancy, and bidding, either directly or as a nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider, in respect of such contract, and (ii) entering into an addendum or amendment introducing a material modification to any existing contract. 4 A nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider (different names are used depending on the particular bidding document) is one which has been: (i) included by the bidder in its pre-qualification application or bid because it brings specific and critical experience and know-how that allow the bidder to meet the qualification requirements for the particular bid; or (ii) appointed by the Borrower. 5 Inspections in this context are usually investigative (i.e., forensic) in nature: they involve fact-finding activities undertaken by the Bank or persons appointed by the Bank to address specific matters related to investigations/audits, such as evaluating the veracity of an allegation of possible Fraud and Corruption, through the appropriate mechanisms. Such activity includes but is not limited to accessing and examining a firm's or individual's financial records and information, and making copies thereof as relevant; accessing and examining any other documents, data, and information (whether in hard copy or electronic format) deemed relevant for the investigation/audit, and making copies thereof as relevant; interviewing staff and other relevant individuals; performing physical inspections and site visits; and obtaining third-party verification of information. 2|Page Name of the person duly authorized to sign the Bid/Proposal on behalf of the Bidder/Consultant: Title of the person signing the Letter: 3|Page PROCUREMENT Malawi : Water and Sanitation Project - I PLAN General Information Country: Malawi 2023-02-28 Bank’s Approval Date of the Original Procurement Plan: 2023-04-20 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P178954 GPN Date: 2023-02-28 Project Name: Water and Sanitation Project - I Loan / Credit No: / , IDA / E1590 Blantyre Water Board Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Request for Bids - MW-BWB-340251-CW-RFB / Single Stage - One E Works (without pr Pending Imp 2023-11-2 Construction of Smart kiosks / Water Supply Improvements Post Request for Bids Open - National 1,575,000.00 0.00 2023-03-02 2023-03-09 2023-04-08 2023-05-08 2023-05-29 nvelope equalification) SP lementation 5 and Public Sanitation Faciliti D es Request for Bids - MW-BWB-340265-CW-RFB / Works – Roads (O Priority Sanitation Investme Single Stage - One E Pending Imp 2023-12-0 Construction of Concrete acc / Post Request for Bids Open - National utput and Perform 882,000.00 0.00 2023-03-15 2023-03-22 2023-04-21 2023-05-21 2023-06-11 nts nvelope lementation 8 ess road to Mzedi Dumpsite ance Based Road Access Road Contracts) SPD GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MW-BWB-340108-GO-RFB / Supply and Delivery of Water Institutional Capacity Streng Open - Internationa Single Stage - One E Pending Impl / Post Request for Bids 1,400,000.00 0.00 2023-02-24 2023-03-03 2023-04-23 2023-05-23 2023-06-20 2023-08-19 Bowsers, Refuse Skip Handle thening l nvelope ementation r, Mobile Waste Transfer Veh icles and Motorcycles MW-BWB-340122-GO-RFB / Supply and Delivery of Water Single Stage - One E Pending Impl / Water Supply Improvements Post Request for Bids Open - National 752,200.00 0.00 2023-02-28 2023-03-07 2023-04-06 2023-05-06 2023-05-27 2023-06-26 Treatment Chemicals, Person nvelope ementation al Protective Equipment and Associated Tools MW-BWB-350920-GO-RFB / Single Stage - One E Pending Impl Supply and delivery of Post-p IDA / E1590 Water Supply Improvements Post Request for Bids Open - National 555,000.00 0.00 2023-05-22 2023-06-05 2023-07-22 2023-08-16 2023-09-13 2023-12-12 nvelope ementation aid Water Meters, Pipes and Fittings MW-BWB-350927-GO-RFB / Institutional Capacity Streng Single Stage - One E Pending Impl IDA / E1590 Post Request for Bids Open - National 340,000.00 0.00 2023-05-15 2023-05-25 2023-06-26 2023-07-21 2023-08-11 2023-11-09 Supply and Delivery of Office thening nvelope ementation Furniture MW-BWB-357183-GO-RFB / Institutional Capacity Streng Single Stage - One E Pending Impl IDA / E1590 Post Request for Bids Open - National 280,000.00 0.00 2023-05-15 2023-05-25 2023-06-26 2023-07-21 2023-08-11 2023-11-09 Supply and Delivery of ICT Eq thening nvelope ementation uipment NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MW-BWB-340269-NC-RFB / P Priority Sanitation Investme Request for Quota Single Stage - One E Pending Impl / Post Open - National 17,800.00 0.00 2023-06-05 2023-07-02 2023-07-23 rovision of Fumigation Servic nts tions nvelope ementation es CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MW-BWB-333054-CS-QCBS / Consultancy Services for det Quality And Cost- Open - Internationa Under Implement ailed design and construction / Water Supply Improvements Prior 3,800,000.00 0.00 2023-02-23 2023-03-10 2023-03-05 2023-04-03 2023-04-11 2023-06-01 2023-06-15 2023-07-27 2023-08-24 2027-06-04 Based Selection l ation supervision of Blantyre water supply network upgrades MW-BWB-333131-CS-QCBS / Consultancy Services for Dev Quality And Cost- Open - Internationa Under Implement elopment of Dam Safety Man / Water Supply Improvements Post 750,000.00 0.00 2023-03-09 2023-04-20 2023-03-19 2023-04-25 2023-06-15 2023-07-01 2023-08-12 2023-09-09 2028-03-16 Based Selection l ation agement Plan (DSMP) and De tailed Design for Rehabilitati on Works of Mudi Dam MW-BWB-333134-CS-QCBS / Consultancy services for deta Priority Sanitation Investme Quality And Cost- Open - Internationa Under Implement / Prior 1,500,000.00 0.00 2023-03-09 2023-03-14 2023-03-19 2023-04-04 2023-04-25 2023-06-15 2023-06-29 2023-08-10 2023-09-07 2027-06-18 iled designs and construction nts Based Selection l ation supervision of priority sanitat ion investments MW-BWB-333142-CS-QCBS / Consultancy services for deta Priority Sanitation Investme Quality And Cost- Open - Internationa iled designs and construction / Prior 1,500,000.00 0.00 Under Review 2023-02-23 2023-03-05 2023-04-11 2023-06-01 2023-06-15 2023-07-27 2023-08-24 2027-06-04 nts Based Selection l supervision of a Recycling pl ant and an engineered landfil l MW-BWB-333153-CS-QCBS / Consultancy services for Dev elopment of national water s Institutional Capacity Streng Quality And Cost- Open - Internationa Under Implement / Post 300,000.00 0.00 2023-04-07 2023-03-04 2023-04-17 2023-05-19 2023-07-09 2023-07-25 2023-08-31 2023-09-28 2024-07-09 upply and sanitation investm thening Based Selection l ation ent plan for urban and rural and formulation of Performan ce Based Financing agreeme nt MW-BWB-335962-CS-QCBS / Consultancy services for dev Institutional Capacity Streng Quality And Cost- Under Implement / Post Open - National 200,000.00 0.00 2023-03-24 2023-03-04 2023-04-03 2023-05-03 2023-06-02 2023-06-18 2023-07-25 2023-08-13 2024-04-09 elopment of Sanitation and H thening Based Selection ation ygiene Bill and Regulations – proposal MW-BWB-333179-CS-QCBS / Priority Sanitation Investme Quality And Cost- Open - Internationa Under Implement Consultancy services for sani / Post 400,000.00 0.00 2023-04-07 2023-04-17 2023-04-17 2023-05-19 2023-07-09 2023-07-25 2023-08-31 2023-09-28 2026-03-16 nts Based Selection l ation tation marketing Page 1 MW-BWB-333207-CS-QCBS / Consultancy Services for Fea Quality And Cost- Open - Internationa Under Implement / Water Supply Improvements Prior 2,000,000.00 0.00 2023-10-11 2023-10-21 2023-11-27 2024-01-21 2024-02-04 2024-03-17 2024-04-14 2025-10-06 sibility study and detailed de Based Selection l ation sign for Mulanje and Mombez i Dams. MW-BWB-333213-CS-QCBS / Institutional Capacity Streng Quality And Cost- Under Implement Consultancy Services for Bas / Post Open - National 150,000.00 0.00 2023-03-15 2023-03-04 2023-03-25 2023-04-24 2023-05-24 2023-06-09 2023-07-16 2023-08-04 2024-01-01 thening Based Selection ation eline Survey MW-BWB-335972-CS-QCBS / Consultancy Services for Envi Priority Sanitation Investme Quality And Cost- Under Implement / Post Open - National 200,000.00 0.00 2023-03-15 2023-03-04 2023-03-25 2023-04-24 2023-05-24 2023-06-09 2023-07-16 2023-08-04 2023-12-02 ronmental and Social Impact nts Based Selection ation Assessment (ESIA) for Sanita tion Improvements MW-BWB-337737-CS-QCBS / Consultancy Service for Envir Quality And Cost- Under Implement / Water Supply Improvements Post Open - National 200,000.00 0.00 2023-03-15 2023-03-04 2023-03-25 2023-04-24 2023-05-24 2023-06-09 2023-07-16 2023-08-04 2023-12-02 onment and Social Impact As Based Selection ation sessment for Water Supply I mprovements MW-BWB-345276-CS-QCBS / Consultancy services for Com Quality And Cost- Open - Internationa Under Implement / Water Supply Improvements Post 360,000.00 0.00 2023-03-14 2023-03-04 2023-03-24 2023-04-20 2023-05-04 2023-05-18 2023-06-24 2023-07-13 2024-01-09 munication and Citizen enga Based Selection l ation gement on Cholera response activities MW-BWB-350889-CS-QCBS / Institutional Capacity Streng Quality And Cost- Open - Internationa Pending Impleme Consultancy Services for an I IDA / E1590 Post 400,000.00 0.00 2023-05-02 2023-05-16 2023-07-02 2023-08-18 2023-09-12 2023-10-11 2023-11-08 2025-10-28 thening Based Selection l ntation ndependent Verification Age nt MW-BWB-333140-CS-QCBS / Consultancy services for deta Technical Assistance and Pro Quality And Cost- Open - Internationa iled designs and construction / Post 250,000.00 0.00 Canceled 2023-03-02 2023-04-17 2023-03-12 2023-04-13 2023-06-03 2023-06-19 2023-07-26 2023-08-23 2025-08-12 ject Management Support Based Selection l supervision of public sanitati on facilities, PIU & PST Office s MW-BWB-357904-CS-QCBS / Consultancy services for deta Technical Assistance and Pro Quality And Cost- Pending Impleme iled designs and construction IDA / E1590 Post Open - National 250,000.00 0.00 2023-04-28 2023-05-08 2023-06-24 2023-07-26 2023-08-20 2023-09-18 2023-10-09 2026-09-23 ject Management Support Based Selection ntation supervision of public sanitati on facilities, PIU & PST Office s INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MW-BWB-353684-CS-INDV / Technical Assistance and Pro Individual Consult Pending Impleme Consultancy Services for Soci IDA / E1590 Prior Open - National 100,000.00 0.00 2022-12-24 2023-02-07 2023-02-21 2023-03-14 2025-03-03 ject Management Support ant Selection ntation al Development Specialist Page 2