The World Bank                                                                                    Implementation Status & Results Report
            Moldova Emergency COVID-19 Response Project (P173776)



Moldova Emergency COVID-19 Response Project (P173776)


 EUROPE AND CENTRAL ASIA | Moldova | Health, Nutrition & Population Global Practice |
 IBRD/IDA | Investment Project Financing | FY 2020 | Seq No: 9 | ARCHIVED on 18-Apr-2024 | ISR60337 |


 Implementing Agencies: Ministry of Health, Republic of Moldova



 Key Dates


  Key Project Dates

   Bank Approval Date: 24-Apr-2020                                             Effectiveness Date: 28-May-2020
   Planned Mid Term Review Date: 23-Feb-2022                                   Actual Mid-Term Review Date: 23-Feb-2022
   Original Closing Date: 30-Apr-2022                                          Revised Closing Date: 30-Sep-2024
 pdoTable

 Project Development Objectives

  Project Development Objective (from Project Appraisal Document)
  The objectives of the Project are to prevent, detect and respond to the threat posed by the COVID-19 pandemic in Republic of Moldova.

  Has the Project Development Objective been changed since Board Approval of the Project Objective?
  No


 Components Table

 Name
 Emergency COVID-19 Response:(Cost $90.78 M)
 Implementation Management and Monitoring and Evaluation:(Cost $0.60 M)

 Overall Ratings

 Name                                                                        Previous Rating                          Current Rating

 Progress towards achievement of PDO                                         Moderately Satisfactory                 Satisfactory
 Overall Implementation Progress (IP)                                        Moderately Satisfactory                 Moderately Satisfactory
 Overall Risk Rating                                                         Substantial                             Substantial


 Implementation Status and Key Decisions

  Progress toward achieving the Project development objective (PDO) and implementation progress is rated Satisfactory. All four PDO indicators and
  13 of 15 interim results (IR) indicators have already been achieved. IR indicator 14 “Number of public health warehouses built or rehabilitated”, and
  IR 15 “Number of public health centers renovated” are currently on track to be achieved. Both performance-based conditions have been
  accomplished.

  The Project has disbursed a cumulative total of US$ 73.04 million, or 78.9 percent of the Project’s total of US$91.38 million. The closing date for
  Additional Financing 2 of the Project has been extended to September 30, 2024. The Project supported the procurement of laboratory equipment,
  diagnostic supplies, and vehicles to transport diagnostic samples from regions. It has financed personal protective equipment and disinfectants for
  health personnel, ambulances, computer tomography systems, and equipment for intensive care units (ventilators, syringe pumps, pulse oximeters,
  oxygen generators, mobile X-rays, functional beds, etc.). The refurbishment of 10 intensive care units has been completed, and the remaining
  works in the ICU in the Institute of Mother and Child are scheduled for completion in June 2024 11.



4/18/2024                                                                                                                     Page 1 of 10
            The World Bank                                                                                     Implementation Status & Results Report
            Moldova Emergency COVID-19 Response Project (P173776)




 MPA Program Development Objective


 MPA PDO Table
 The Program Development Objective is to prevent, detect and respond to the threat posed by COVID-19 and strengthen national systems for public
 health preparedness

 MPA Table
 Multiphase Programmatic Approach (MPA) Status

 MPA Table Body
 Sustained efforts continue to be made to advance the implementation of the 87 MPA operations. As reported in the past months, the overall level of
 disbursements is being affected by three main reasons: (i) low disbursements in six countries (Bangladesh, Kiribati, Nigeria, Samoa, Solomon
 Islands, and Zambia); (ii) pausing of disbursements in two countries – Afghanistan, and Myanmar; and (iii) processing of refunds to the Project
 accounts, which in the past weeks have increased at this late stage of Project implementation. In addition, (i) a large refund from the UN to the
 Project account of the Myanmar operation was processed in March 2023 due to the inability to implement the Project, and (ii) the amounts of Loans
 and Credits denominated in SDRs, and Euros have been affected because of fluctuations between the SDRs and Euros against the US
 dollar. During the past week, a second large refund was processed under the Trinidad and Tobago operation because of savings realized for
 medical supplies and medicines procured through PAHO.

 As of March 18, 2024, 88 MPA-Projects had been approved with a total commitment of US$4.25 billion. One operation (Guatemala) was cancelled in
 mid-September 2021. Total disbursements as of March 18, 2024, amount to US$3.98 billion or 94% of overall commitments. This amount
 does not include disbursements under MPA-V operations which are reported together with AF-V operations or disbursements under PEF
 grants as commitments do not include PEF Grants. Closing dates for MPA operations have been as follows: (i) ten operations closed by the end
 of CY22, (ii) nine operations closed on June 30, 2023, (iii) thirteen operations closed on December 31, 2023. Twenty-eight operations are scheduled
 to close by June 30, 2024. However, this number is likely to change as extension of closing dates are being processed under some operations.

 As with the Mid Term Review (MTR) issued on March 25, 2023, no individual ICR will be required for COVID-19 MPA operations. Only one
 ICR will be prepared upon completion of the SPRP COVID-19 MPA Program, which closes on December 31, 2025. The Global ICR will be based on
 final ISRs packages prepared by country operations’ teams. A template for the final ISR was issued by OPCS on March 21, 2023. So far, seventeen
 operations have finalized final ISR packages, and some others are under preparation. The overall conclusion of the MPA MTR was that: (i) the
 COVID-19 MPA Program embodied a rapid, innovative approach to new lending for human health response; (ii) the COVID-19 MPA has been
 successful, notwithstanding considerable uncertainty and multiple constraints in the early stages of the pandemic; (iii) the Bank’s emergency
 response was remarkably swift in the most vulnerable countries facing human capital losses and development setbacks; and (iv) notwithstanding the
 challenges, the MPA is on track to achieve its PrDO, “prevent, detect and respond to the threat posed by COVID-19 and strengthen national
 systems for public health preparedness.“

 Seventy-five (75) country Projects or 86 percent of Projects approved have reached 70-100+ percent disbursement (reasons for >100%
 disbursements relate to fluctuations between the Euro and the SDR against the US$). Out of the 75 operations, 66 operations or 87 percent have
 disbursed 90%+ of commitments. Out of the 75 operations, 52 operations or 69 percent are fully disbursed, and 8 operations have
 disbursed 95-99 percent of commitments. There are six operations with disbursements of 65 percent or less. Out of these four operations, one
 operation has disbursed 35 percent (AFW), two operations in EAP have disbursed 48-62 percent and one operation in SAR has disbursed 53
 percent. The operation in AFW has been restructured in the past two weeks to: (i) extend the closing date by four months, (ii) cancel a large
 amount under the parent Project, (iii) reallocate funds under components and activities, and (iv) revise the Results Framework.

 The Projects are benefitting about 3.7 billion people or 50% of the global population. When countries with AF-V operations are counted,
 the Projects are benefitting about 4.1 billion of 51 percent of the global population. This is because some countries that do not have a parent
 Project have AF-V operations. All Projects approved are disbursing. Operations in ECA and MNA are fully disbursed. In other regions,


4/18/2024                                                                                                                     Page 2 of 10
            The World Bank                                                                                        Implementation Status & Results Report
            Moldova Emergency COVID-19 Response Project (P173776)



 disbursements have reached: (i) SAR 96 percent, (ii) LAC 94 percent, (iii) EAP 88 percent, (iv) AFW 85 percent, and (v) AFE 82
 percent. Disbursements for EAP operations are being affected by low disbursements in three country Projects that have disbursed between 48 and
 62 percent. AFE lower disbursements compared to other regions are a result of low disbursements under one operation, which has disbursed 63
 percent. In the case of AFW low overall disbursements are a result of low disbursements under one operation (35 percent). Retroactive Financing
 (RF) represents 20 percent of commitments. SAR has the highest percentage of RF at 37 percent, followed by ECA at 18 percent. Direct Payment
 (DP) disbursements represent 22 percent of commitments. EAP has the highest level of disbursements using DP – 80 percent, followed by AFW at
 38 percent. IDA continues to represent 40 percent while IBRD represents 60 percent of disbursements.

 Streamlined procedures, delegated approvals, coupled with flexible Project design and intensified efforts by counterparts and Bank teams have
 contributed to the progress. Implementation is being guided by Bank teams working in parallel with other health related Projects, including
 Additional Financing operations which have supported vaccine procurement and deployment efforts.



 COVID-19 MPA AF-V

 Considerable progress is being made in the implementation of AF-V operations. As of March 18, 2024, the Bank has approved 117
 operations (including MPA-V operations) to support vaccine procurement and rollout in 78 countries amounting to $8.54 billion. Four operations have
 been approved in the past months including: (i) Senegal AF2 operation for $15 million financed by a Grant from The Global Finance Facility (GFF)
 approved on June 30, 2023; (ii) a Second AF (IDA Grant of $2.50 million) approved on August 31, 2023 for Sao Tome and Principe, (iii) a Grant of
 $3.94 approved for Chad on July 23, 2023; and (iv) Zimbabwe AF2 operation for $15 million financed by a Grant from the GFF approved on
 December 7, 2023. One hundred and twenty-one (121) operations had been approved amounting to $10 billion, but with cancellation of four
 operations and partial cancellations processed in the past months under several operations, commitments today amount to $8.54 billion. The four
 operations cancelled are: (i) Costa Rica loan ($120 million), (ii) Peru loan ($500 million), (iii) Gabon loan ($12 million), which loan agreement lapsed,
 and (iv) Philippines AF2 loan of $300 million. The Afghanistan operation commitment of $113 million was reduced to $60 million. Of the 117
 approved operations: (i) 67 are in Africa – 32 in AFE and 35 in AFW; (ii) 10 in East Asia and the Pacific; (iii) 11 in Europe and Central Asia; (iv) 11 in
 Latin America and the Caribbean; (v) 9 in Middle East and North Africa; and (vi) 9 in South Asia. The 117 operations approved, include 6 operations
 that involved restructuring of parent Projects (Bhutan, Cameroon, North Macedonia, Philippines, and Pakistan) and in the case of Lebanon,
 restructuring of the Health Resilience Project.

 Partial cancellations have been/are being processed under several operations -- Afghanistan, Bangladesh, Belarus, Benin, Cabo Verde, Cameroon,
 Ethiopia, Gabon, Georgia, Lao, Madagascar, Mali, Mozambique, Nepal, Nigeria, Pakistan, Philippines, Papua New Guinea, Sierra Leone, South
 Africa, Sudan, Republic of Congo AF2, and Togo.

 Thirty-two (32) operations are being implemented in Fragile and Conflict-affected situations. IDA represents 45 percent and IBRD 55 percent of
 disbursements. Total disbursements under these Projects as of March 18, 2024, amount to US$6.60 billion or 77 percent of overall
 commitments. Disbursements under MPA-V operations are included in this total while disbursements under the six restructured Projects are
 counted under parent Projects. With less than planned demand for IDA/IBRD funds for vaccine procurement because, inter alia, over supply of
 vaccines from donations from various sources, several Projects have been/are being restructured and more will need to be restructured to reallocate
 funds or partially cancel funds allocated to procurement of COVID-19 vaccines and deployment. Guidance was issued under an Email from Juan
 Pablo Uribe of July 7, 2023, which provided direction for the use of undisbursed funds under COVID-19 operations. HNP is monitoring
 implementation of the guidelines.

 Six (6) operations are fully disbursed (Argentina, El Salvador AF1, Indonesia, Iraq, Sri Lanka AF-V 1, and Ukraine AF-V 3). Sixty-four (64)
 operations or 55 percent of operations approved have disbursed over 70 percent of their commitments. Out of the 64, twenty-nine (29) operations
 have disbursed 90+ percent. One hundred and seven (107) operations or 91 percent of total operations approved are disbursing. EAP has the
 highest percentage of disbursements at 96 percent, followed by ECA at 89 percent, LAC at 88 percent, SAR at 81 percent, MNA at 81 percent, AFE
 at 67 percent, and AFW at 63 percent.



4/18/2024                                                                                                                        Page 3 of 10
            The World Bank                                                                                      Implementation Status & Results Report
            Moldova Emergency COVID-19 Response Project (P173776)



 Retroactive Financing (RF) represents 36 percent of overall commitments. ECA has the highest level of RF at 74 percent, followed by SAR at 68
 percent, LAC at 59 percent, MNA and AFE at 29 percent and AFW at 13 percent. Disbursements to UN agencies represent 23 percent of overall
 disbursements, while Direct Payment represents 17 percent of disbursements.

 As with the COVID-19 MPA operations, streamlined procedures, delegated approval, wide use of Bank Facilitated Procurement (BFP), coupled with
 flexible Project design, and intensified efforts from counterparts and Bank staff have contributed to the rapid design, processing, and implementation
 of the AF-V operations.




  Risks


 Systematic Operations Risk-rating Tool


  Risk Category                                              Rating at Approval               Previous Rating               Current Rating

  Political and Governance                                   Substantial                     Moderate                     Moderate
  Macroeconomic                                              High                            Substantial                  Substantial
  Sector Strategies and Policies                             Moderate                        Moderate                     Moderate
  Technical Design of Project or Program                     Moderate                        Moderate                     Moderate
  Institutional Capacity for Implementation and
                                                             Moderate                        Moderate                     Moderate
  Sustainability
  Fiduciary                                                  Substantial                     Substantial                  Substantial
  Environment and Social                                     Substantial                     Substantial                  Substantial
  Stakeholders                                               Moderate                        Moderate                     Moderate
  Other                                                      Moderate                        Moderate                     Moderate
  Overall                                                    Substantial                     Substantial                  Substantial



  Results


 PDO Indicators by Objectives / Outcomes



   To prevent, detect, and respond to the threat posed by the COVID-19 pandemic

    IN01414803
    ►Number of designated hospitals with fully equipped and functional intensive care units (ICUs). (Number, Custom)

                                       Baseline                     Actual (Previous)            Actual (Current)           End Target

    Value                              0.00                        14.00                         21.00                      19.00

    Date                               24-Apr-2020                 21-Mar-2022                   22-Mar-2024               30-Apr-2023
                                        Overachieved. Out of 21, 18 are equipped and functional, the remaining 3 ICUs are scheduled to become
   Comments:                           functional in April 2024, and works in one additional ICU will be completed in June 2024.

    IN01414804



4/18/2024                                                                                                                     Page 4 of 10
            The World Bank                                                                                  Implementation Status & Results Report
            Moldova Emergency COVID-19 Response Project (P173776)




    ►Percentage of designated hospitals with personal protection equipment and infection control products and supplies (Percentage, Custom)

                                     Baseline                    Actual (Previous)           Actual (Current)           End Target

    Value                            0.00                       90.00                        90.00                      80.00

    Date                             24-Apr-2020                21-Mar-2022                  21-Mar-2022               30-Apr-2023

                                     This indicator was achieved in 2022.
   Comments:

    IN01414805
    ►Number of people tested for coronavirus identification (Number, Custom)

                                     Baseline                    Actual (Previous)           Actual (Current)           End Target

    Value                            8,149.00                   3,062,136.00                 3,062,136.00               250,000.00

    Date                             24-Apr-2020                10-Mar-2022                  10-Mar-2022               30-Apr-2023

                                     This indicator was achieved in 2022.
   Comments:

    IN01414806
    ►Number of Ajutor Social recipients during the emergency period (Number, Custom)

                                     Baseline                    Actual (Previous)           Actual (Current)           End Target

    Value                            47,569.00                  71,802.00                    71,802.00                  65,000.00

    Date                             24-Apr-2020                09-Mar-2021                  09-Mar-2021               30-Apr-2023

                                     This indicator was achieved in 2022.
   Comments:



 Intermediate Results Indicators by Components



   Emergency COVID-19 Response

    IN01414807
    ►Number of ventilators purchased (Number, Custom)

                                     Baseline                    Actual (Previous)           Actual (Current)           End Target

    Value                            0.00                       292.00                       292.00                     292.00

    Date                             24-Apr-2020                21-Mar-2022                  21-Mar-2022               30-Apr-2023

                                     This indicator was achieved in 2022.
   Comments:

    IN01414808
    ►Number of personal protection equipment (PPE) purchased. (Number, Custom)

                                     Baseline                    Actual (Previous)           Actual (Current)           End Target

    Value                            0.00                       500,000.00                   500,000.00                 500,000.00



4/18/2024                                                                                                                 Page 5 of 10
            The World Bank                                                                              Implementation Status & Results Report
            Moldova Emergency COVID-19 Response Project (P173776)




    Date                             24-Apr-2020                  03-Aug-2022             03-Aug-2022              03-Aug-2022

                                     This indicator was achieved in 2022.
   Comments:

   IN01414809
   ►Number of designated laboratories with COVID-19 diagnostic equipment, test kits, and reagents per MoHLSP guidelines. (Number,
   Custom)

                                     Baseline                     Actual (Previous)       Actual (Current)          End Target

    Value                            0.00                         5.00                    5.00                      4.00

    Date                             24-Apr-2020                  21-Mar-2022             21-Mar-2022              30-Apr-2023

                                     This indicator was achieved in 2022.
   Comments:

    IN01414810
    ►Number of activities in National Communications Strategy for COVID-19 implemented (Number, Custom)

                                     Baseline                     Actual (Previous)       Actual (Current)          End Target

    Value                            0.00                         20.00                   20.00                     10.00

    Date                             24-Apr-2020                  11-Aug-2021             11-Aug-2021              30-Apr-2023

                                     This indicator was achieved in 2022.
   Comments:

    IN01414811
    ►Number of Ajutor Social recipients (Number, Custom)

                                     Baseline                     Actual (Previous)       Actual (Current)          End Target

    Value                            47,659.00                    54,231.00               54,231.00                 53,000.00

    Date                             24-Apr-2020                  22-Mar-2021             22-Mar-2021              30-Apr-2023

                                     This indicator was achieved in 2022.
   Comments:

    IN01414812
    ►Budget Allocation for Ajutor Social Program (Text, Custom)

                                     Baseline                     Actual (Previous)       Actual (Current)          End Target

    Value                            MDL 495,461,700              MDL 708,749,800         MDL 708,749,800           MDL 697,361,700

    Date                             24-Apr-2020                  22-Mar-2021             22-Mar-2021              30-Apr-2023

                                     This indicator is expected to be achieved in 2023.
   Comments:

    IN01414813
    ►Average Ajutor Social benefit amount (Text, Custom)

                                     Baseline                     Actual (Previous)       Actual (Current)          End Target

    Value                            MDL 828                      MDL 1079                MDL 1079                  MDL 1099

    Date                             24-Apr-2020                  22-Mar-2021             22-Mar-2021              30-Apr-2023



4/18/2024                                                                                                             Page 6 of 10
            The World Bank                                                                                      Implementation Status & Results Report
            Moldova Emergency COVID-19 Response Project (P173776)



                                       This indicator was achieved in 2022.
   Comments:

   IN01414814
   ►Percentage of hospitals (i) establishing approved citizen engagement platforms (in-facilities or online), (ii) responding to citizen views (in-
   facilities or online), and (iii) reporting (Percentage, Custom)

                                       Baseline                     Actual (Previous)             Actual (Current)           End Target

    Value                              0.00                         0.00                          78.69                      25.00

    Date                               16-Oct-2020                  21-Mar-2022                   21-Mar-2022                30-Apr-2023

                                       This indicator was achieved.
   Comments:

    IN01414815
    ►Review of the VIRAT-VRAF 2.0 or updated tool, completed (Text, Custom)

                                       Baseline                     Actual (Previous)             Actual (Current)           End Target

    Value                              No                           No                            Yes                        Yes

    Date                               15-Feb-2021                  21-Mar-2022                   22-Mar-2024                30-Sep-2024

                                       This indicator was achieved in 2022.
   Comments:

    IN01414816
    ►Percentage of individuals that will accept a safe and effective COVID-19 vaccine: (a) Males; and (b) Females (Text, Custom)

                                       Baseline                     Actual (Previous)             Actual (Current)           End Target
                                       (a) 31%                      (a) 57%                       (a) 57%                    (a) 70%
    Value                              (b) 31%                      (b) 57%                       (b) 57%                    (b) 70%


    Date                               15-Feb-2021                  11-Aug-2021                   11-Aug-2021                30-Apr-2023

    IN01414817
    ►Percentage of applicants that have benefited from the Ajutor Social Program that are: (a) Males; and (b) Females (Text, Custom)

                                       Baseline                     Actual (Previous)             Actual (Current)           End Target
                                       (a) 30%                      (a) 30%                       (a) 30%                    (a) 30%
    Value                              (b) 70%                      (b) 70%                       (b) 70%                    (b) 70%


    Date                               15-Feb-2021                  15-Feb-2021                   15-Feb-2021                30-Apr-2023

    IN01414818
    ►Average monthly benefit received by applicants to the Ajutor Social Program: (a) Males; and (b) Females (Text, Custom)

                                       Baseline                     Actual (Previous)             Actual (Current)           End Target
                                                                                                  (a) MDL 958
                                       (a) MDL 708                  (a) MDL 708                                              (a) MDL 800
                                                                                                  (b) MDL 1924
    Value                              (b) MDL 874                  (b) MDL 874                                              (b) MDL 1000


    Date                               15-Feb-2021                  15-Feb-2021                   30-Nov-2023                30-Apr-2023

                                       This indicator was achieved.
   Comments:

    IN01414819


4/18/2024                                                                                                                      Page 7 of 10
            The World Bank                                                                                    Implementation Status & Results Report
            Moldova Emergency COVID-19 Response Project (P173776)



   ►Percentage of workers associated with the Project who have participated in an information session on the code of conduct (Percentage,
   Custom)

                                       Baseline                    Actual (Previous)            Actual (Current)          End Target

    Value                              0.00                        0.00                         100.00                    100.00

    Date                               15-Feb-2021                 21-Mar-2022                  30-Nov-2023              30-Sep-2024

                                       Achieved. All signed civil works contracts workers were trained
   Comments:

    IN01414820
    ►Number of public health warehouses built or rehabilitated (Number, Custom)

                                       Baseline                    Actual (Previous)            Actual (Current)          End Target

    Value                              0.00                        0.00                         0.00                      3.00

    Date                               03-Aug-2022                 03-Aug-2022                  22-Mar-2024              30-Sep-2024
                                       The construction of one warehouse has been moved to be completed under the Modernization and
                                       Improvement of Rehabilitation Services Project. Two warehouses are in the process of refurbishment, and
   Comments:
                                       two regional public health centers are undergoing renovation.

    IN01414821
    ►Number of public health centers renovated (Number, Custom)

                                       Baseline                    Actual (Previous)            Actual (Current)          End Target

    Value                              0.00                        0.00                         1.00                      6.00

    Date                               03-Aug-2022                 03-Aug-2022                  22-Mar-2024              30-Sep-2024

                                       The renovation of five public health centers is expected to complete by August 2024.
   Comments:



 Performance-Based Conditions




   IN01414822
   ►PBC 1 Supplement budget increasing allocations for the Ajutor Social program by 39% adopted. (Percentage, Outcome, 17,000,000.00,
   0.00%)


                                Baseline                        Actual (Previous)             Actual (Current)             Completed

    Value                       0.00                            39.80                         39.80                        39.00

    Date                        --                              02-Jun-2020                  02-Jun-2020                   --




   IN01414823
    ►PBC 2 Increase of the benefit and the coverage by 10% achieved (Percentage, Outcome, 7,000,000.00, 0.00%)




4/18/2024                                                                                                                     Page 8 of 10
            The World Bank                                                                                      Implementation Status & Results Report
            Moldova Emergency COVID-19 Response Project (P173776)




                                  Baseline                        Actual (Previous)             Actual (Current)              Completed

    Value                         0.00                            34.80                         34.80                         10.00

    Date                          --                              24-Apr-2020                   24-Apr-2020                   --



 Data on Financial Performance


 Disbursements (by loan)

 Project        Loan/Credit/TF    Status       Currency        Original   Revised       Cancelled       Disbursed     Undisbursed              % Disbursed


 P173776        IDA-66320         Closed       USD               57.90      57.90             0.00         62.35              0.00                   100%

 P173776        IDA-68730         Effective    USD               30.00      30.00             0.00         11.27            15.32                     42%

 P173776        TF-B4344          Closed       USD                3.48       3.48             0.00           3.48             0.00                   100%


 Key Dates (by loan)

 Project         Loan/Credit/TF    Status      Approval Date       Signing Date       Effectiveness Date      Orig. Closing Date      Rev. Closing Date

 P173776         IDA-66320         Closed      24-Apr-2020         28-Apr-2020        28-May-2020             30-Apr-2022             31-Mar-2024
 P173776         IDA-68730         Effective   23-Apr-2021         09-Aug-2021        04-Feb-2022             30-Apr-2023             30-Sep-2024
 P173776         TF-B4344          Closed      23-Dec-2020         23-Dec-2020        23-Dec-2020             31-Jan-2021             31-Jan-2021


Cumulative Disbursements




4/18/2024                                                                                                                      Page 9 of 10
            The World Bank                                                                      Implementation Status & Results Report
            Moldova Emergency COVID-19 Response Project (P173776)




  Restructuring History


  Level 2 Approved on 19-Sep-2022 ,Level 2 Approved on 02-Feb-2024


  Related Project(s)

 P174761-Moldova Pandemic Emergency Financing for COVID-19 ,P175816-Moldova Emergency COVID-19 Response Project - Additional
 Financing




4/18/2024                                                                                                    Page 10 of 10