Procurement Plan for Shared Infrastructure for Solar Parks Project I. General 1. Project information: Country : India Borrower : Republic of India Project Name : Shared Infrastructure for solar Parks Project Loan No. : Project Implementing : IREDA, RUMSL Agency (PIA), etc. 2. Bank’s approval Date of the procurement Plan Original : March 9, 2017 3. Date of General Procurement Notice: February 9, 2017 4. Period covered by this procurement plan: First 18 months II. Goods and Works and non-consulting services 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement. World Bank review of procurement: The World Bank will prior review (thresholds are based on “Substantial” rating, will be modified if risk rating is changed after assessment by Bank during the project implementation) the following contracts: a) Works including turnkey Supply & Installation of Plant and Equipment and PPP: All contracts more than US$ 10 million equivalent b) Goods, Information Technology and Non-consulting Services: All contracts more than US$ 2 million equivalent First contract issued by implementing agency [IA] will be subject to prior review irrespective of their value. In addition, the justifications for all contracts to be issued on the basis of LIB, single-source or direct contracting will be subject to prior review. The above thresholds are for the initial 18 months implementation period; based on the procurement performance of the project these thresholds may be subsequently modified by Bank. In case of Post Review contracts, the inputs of Bank on Technical Specifications will be obtained by project. The procurement plan will be subsequently updated annually (or at any other time if required) and will reflect any change in prior review thresholds. The World Bank will carry out an annual ex-post procurement review of the procurement falling below the prior review thresholds provided above. To avoid any doubts, the Bank may conduct at any time Independent Procurement Reviews (IPRs) of all the contracts financed under the loan. Domestic preference is allowed only for Procurement of Goods and Information Technology and not for procurement of Works. Categor Method Threshold Method of Procurement y (US$ Equivalent) Works International Competitive Bidding > 40,000,000 (ICB) National Competitive Bidding Up to 40,000,000 (with (NCB) NCB conditions) Shopping Up to 100,000 As per paragraph 3.7 of Direct Contracting (DC) Guidelines Public-Private Partnership (PPP) As per paragraph 3.14 of for Works Guidelines As per paragraph 3.9 of Force Account Guidelines As per paragraph 3.6 of Framework Agreement (FA) Guidelines Goods International Competitive Bidding > 3,000,000 and non- (ICB) consultan Limited International Bidding (LIB) wherever agreed by Bank t services National Competitive Bidding Up to 3,000,000 (with NCB (NCS) (NCB) conditions) Shopping Up to 100,000 Direct Contracting (DC) As per paragraph 3.7 of Guidelines Public-Private Partnership (PPP) As per paragraph 3.14 of Services Guidelines Force Account (only for NCS) As per paragraph 3.9 of Guidelines Framework Agreement (FA)1 As per paragraph 3.6 of Guidelines Procurement from United Nations As per paragraph 3.10 of (UN) Agencies Guidelines 1/ DGS&D rate contracts may be used as framework agreement (FA) subject to the conditions mentioned under NCB conditions 2. Prequalification. Pre-qualification is not envisaged for any package under the Project. 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: Not Applicable 4. Reference to (if any) Project Implementation Plan: Not Applicable 5. Retroactive Financing : The project will be seeking retroactive financing, not exceeding US$ 20 million for financing expenditures incurred , in respect of payments for project-related work during project preparation, on or after May 1, 2016. This includes payments to consultants for various preparatory studies, Procurement of goods and works under the project, training and exposure visits (under technical assistance part) and eligible expenditure incurred prior to loan signing. 6. NCB Condition: National competition for the procurement of goods and works according to the established thresholds will be conducted in accordance with paragraphs 3.3 & 3.4 of Section III of the Guidelines and the following provisions: a) Only the model bidding documents for NCB agreed with the GoI Task Force (and as amended from time to time), shall be used for bidding; b) Invitations to bid shall be advertised in at least one widely circulated national daily newspaper (or on a widely used website or electronic portal with free national and international access along with an abridged version of the said advertisement published in a widely circulated national daily inter-alia giving the website/electronic portal details from which the details of the invitation to bid can be downloaded), at least 30 days prior to the deadline for the submission of bids; c) No special preference will be accorded to any bidder either for price or for other terms and conditions when competing with foreign bidders, state-owned enterprises, small-scale enterprises or enterprises from any given State; d) Except with the prior concurrence of the Bank, there shall be no negotiation of price with the bidders, even with the lowest evaluated bidder; e) Extension of bid validity shall not be allowed with reference to Contracts subject to Bank prior review without the prior concurrence of the Bank (i) for the first request for extension if it is longer than four weeks; and (ii) for all subsequent requests for extension irrespective of the period (such concurrence will be considered by Bank only in cases of Force Majeure and circumstances beyond the control of the Purchaser/Employer); f) Re-bidding shall not be carried out with reference to contracts subject to Bank prior review without the prior concurrence of the Bank. The system of rejecting bids outside a pre-determined margin or "bracket" of prices shall not be used in the project; g) Rate contracts entered into by Directorate General of Supplies and Disposals (DGS&D) will not be acceptable as a substitute for NCB procedures unless agreed with the Bank on case to case basis. Such contracts will be acceptable however for any procurement under the Shopping procedures; h) Use of DGS&D rate contracts as Framework Agreement must be reflected in the procurement plan agreed by the Bank for particular goods. Before issuing the purchasing order, the Bank will have to advise the government on carrying out a price analysis on the specific good that is intended to be purchased. If after this due diligence the borrower concludes [and Bank agrees] that the DGS&D rate contract is not suitable, then the borrower will have to proceed using NCB or shopping depending on the value. To meet the Bank's requirements for right to audit and F&C, these clauses may be included in the Purchase Orders [in case the purchasers are directly placing the purchase orders to DGS&D rate contract holders]. On the other hand, if indent is placed through DGS&D, the Purchaser has the option to sign a separate undertaking with DGS&D rate contract holder, where Bank’s right to audit and F&C clauses could be mentioned. i) Two or three envelope system will not be used (except when using e- procurement system assessed and agreed by the Bank). 7. Procurement Packages with Methods and Time Schedule as per Table A [attached below] III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: a) Consultancy Services for selection of firms : All contracts more than US$ 1.0 million equivalent; b) Consultancy services for selection of individuals: All contracts above US$ 0.3 million. c) First contract issued by implementing agency [IA] will be subject to prior review irrespective of their value. In addition, the justifications for all contracts to be issued on the basis of single-source or direct contracting will be subject to prior review. The above thresholds are for the initial 18- month implementation period; based on the procurement performance of the project these thresholds may be subsequently modified by Bank. In case of Post Review contracts, the inputs of Bank on TORs will be obtained by project. The procurement plan will be subsequently updated annually (or at any other time if required) and will reflect any change in prior review thresholds. The World Bank will carry out an annual ex-post procurement review of the procurement falling below the prior review thresholds provided above. To avoid any doubts, the Bank may conduct at any time Independent Procurement Reviews (IPRs) of all the contracts financed under the loan. Selection Method Method Threshold (USD) Consultants’ Selection Based on Consultants’ Up to 300,000 Services Qualifications (CQS)/Least-Cost Selection (LCS) Single-Source Selection (SSS) As per paragraphs 3.9-3.11 of Guidelines Individuals As per Section V of Guidelines Particular Types of Consultants As per paragraphs 3.15-3.21 of Guidelines Quality- and Cost-Based Selection (QCBS)/ for all other cases Quality-Based Selection (QBS)/ Selection under a Fixed Budget (FBS) (i) International shortlist > 800,000 (ii) Shortlist may comprise national Up to 800,000 consultants only 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than US $ 800,000 equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: First consultancy selection shall be prior reviewed irrespective of threshold. Refer to sl. No. 4 under Section-II of the procurement plan 4. Consultancy Assignments with Selection Methods and Time Schedule as per Table A [attached below] Table A Procurement Plan of Project Implementing State/Agency (RUMSL) Procurement Plan period: (for first 18 months of the project) (Note : The procurement plan will be revised during the course of implementation of the project, based on Project needs) Rewa Solar Park: Mandsaur Solar Park: PROCUREMENT India : Shared Infrastructure for Solar Parks Project PLAN General Information Country: India 2017-06-29 Bank’s Approval Date of the Original Procurement Plan: 2024-04-18 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P154283 GPN Date: 2017-02-09 Project Name: Shared Infrastructure for Solar Parks Project Loan / Credit No: IBRD / 87370, TF / A4639 Rewa Ultra Mega Solar Limited Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned IN-RUMSL-19473-CW-RFB / C Component 1: Shared Infrast ontract for construction of 33 ructure for Solar Parks (esti Single Stage - One E 13,853,575.4 2017-06-2 /220 kV pooling substation al IBRD / 87370 mated total project cost: US Prior Request for Bids Open - National 0.00 Canceled 2017-06-29 2017-06-29 2017-06-29 2017-06-29 2017-06-29 2016-07-13 2017-06-29 2017-06-29 2017-06-29 nvelope 8 9 ong with 220 kV DCDS trans $198 million of which IBRD L mission line oan: US$75 million and CTF Loan: US$23 million) IN-RUMSL-19520-CW-RFB / C Component 1: Shared Infrast ontractor to construct 33/220 ructure for Solar Parks (esti Single Stage - One E 13,853,575.4 9,227,020.5 2017-12-2 kV pooling substation along IBRD / 87370 mated total project cost: US Prior Request for Bids Open - National Signed 2017-06-29 2017-06-30 2017-06-29 2017-06-30 2017-06-29 2016-07-08 2017-06-29 2017-06-30 2017-06-29 2016-09-28 nvelope 8 1 6 with 220 kV DCDS transmiss $198 million of which IBRD L ion line oan: US$75 million and CTF Loan: US$23 million) Component 1: Shared Infrast IN-RUMSL-19620-CW-RFB / C ructure for Solar Parks (esti ontract for supply of three 33 Single Stage - One E 1,700,717.6 2017-12-2 IBRD / 87370 mated total project cost: US Post Request for Bids Open - National 2,484,928.08 Completed 2017-06-30 2016-06-03 2017-06-30 2017-06-30 2016-06-28 2017-06-30 2016-07-13 2017-06-30 2016-10-01 /220 kV, 100 MVA step up tra nvelope 3 7 $198 million of which IBRD L nsformer. oan: US$75 million and CTF Loan: US$23 million) Component 1: Shared Infrast IN-RUMSL-19621-CW-RFB / C ructure for Solar Parks (esti ontract for supply of nine 33/ Single Stage - One E 5,438,951.1 2017-12-2 IBRD / 87370 mated total project cost: US Post Request for Bids Open - National 7,115,924.28 Completed 2017-06-30 2016-05-23 2017-06-30 2017-06-30 2016-07-08 2017-06-30 2016-07-15 2017-06-30 2016-12-07 220 kV, 100 MVA step up tra nvelope 2 7 $198 million of which IBRD L nsformer. oan: US$75 million and CTF Loan: US$23 million) IN-RUMSL-19622-CW-RFB / C ontract to design, manufactu Component 1: Shared Infrast re, test, deliver, install, comp ructure for Solar Parks (esti lete and commission certain f mated total project cost: US Single Stage - One E 3,530,227.4 2017-12-2 IBRD / 87370 Prior Request for Bids Open - National 5,139,098.95 Signed 2017-06-30 2017-06-30 2017-06-30 2017-06-30 2017-06-30 2016-07-08 2017-06-30 2017-06-30 2017-06-30 2016-12-26 acilities, viz. 33/220 kV pooli $198 million of which IBRD L nvelope 2 7 ng substation consisting inst oan: US$75 million and CTF allation of 3X100 MVA transf Loan: US$23 million) ormers at Rewa along with 2 20 kV DCDS transmission lin e IN-RUMSL-19623-CW-RFB / C ontract to design, manufactu Component 1: Shared Infrast re, test, deliver, install, comp ructure for Solar Parks (esti lete and commission certain f mated total project cost: US Single Stage - One E 3,300,101.3 2017-12-2 IBRD / 87370 Prior Request for Bids Open - National 4,831,180.48 Signed 2017-06-30 2017-06-30 2017-06-30 2017-06-30 2017-06-30 2016-07-08 2017-06-30 2017-06-30 2017-06-30 2016-12-26 acilities, viz. 33/220 kV pooli $198 million of which IBRD L nvelope 6 7 ng substation consisting inst oan: US$75 million and CTF allation of 3X100 MVA transf Loan: US$23 million) ormers, Rewa along with 220 kV DCDS transmission line IN-RUMSL-19624-CW-RFB / C ontract to design, manufactu Component 1: Shared Infrast re, test, deliver, install, comp ructure for Solar Parks (esti lete and commission certain f mated total project cost: US Single Stage - One E 3,689,253.5 2017-12-2 IBRD / 87370 Prior Request for Bids Open - National 5,348,837.24 Signed 2017-06-30 2017-06-30 2017-06-30 2017-06-30 2017-06-30 2016-07-08 2017-06-30 2017-06-30 2017-06-30 2016-12-26 acilities, viz. 33/220 kV pooli $198 million of which IBRD L nvelope 1 7 ng substation consisting inst oan: US$75 million and CTF allation of 3X100 MVA transf Loan: US$23 million) ormers, Rewa along with 220 kV DCDS transmission line IN-RUMSL-188629-CW-RFB / Development of Nine 33/222 Component 1: Shared Infrast 0 kV substations for 1500 M ructure for Solar Parks (esti W Solar parks in Madhya Pra mated total project cost: US Single Stage - Two E 25,400,000.0 2022-05-3 IBRD / 87370 Prior Request for Bids Open - National 0.00 Canceled 2020-08-17 2020-08-19 2020-10-03 2020-10-24 2020-11-07 desh - two substations for 55 $198 million of which IBRD L nvelope 0 1 0 MW Agar Solar Park, three oan: US$75 million and CTF substations for 450 MW Shaj Loan: US$23 million) apur Solar Park, and three su bstations for 500 MW Neemu ch Solar Park IN-RUMSL-190687-CW-RFB / Component 1: Shared Infrast Contract for supply of fourtee ructure for Solar Parks (esti n 33/220 kV 110 MVA and thr mated total project cost: US Single Stage - Two E 14,000,000.0 13,748,532. 2022-04-0 ee 33/220 kV 50 MVA step-u IBRD / 87370 Prior Request for Bids Open - National Signed 2020-09-07 2021-01-06 2020-09-09 2021-01-22 2020-10-24 2021-06-16 2020-11-07 2021-08-20 2020-11-21 2021-12-04 $198 million of which IBRD L nvelope 0 45 5 p transformers for 550 MW A oan: US$75 million and CTF gar Solar Park, 450 MW Shaja Loan: US$23 million) pur Solar Park, and 500 MW Neemuch Solar Park IN-RUMSL-190742-CW-RFB / Component 1: Shared Infrast Contract for construction of t ructure for Solar Parks (esti Single Stage - Two E 10,000,000.0 5,606,165.7 2022-04-0 ransmission lines from eight IBRD / 87370 mated total project cost: US Prior Request for Bids Open - National Signed 2020-09-07 2021-01-18 2020-09-09 2021-02-11 2020-10-24 2021-06-17 2020-11-07 2021-08-11 2020-11-21 2021-11-04 nvelope 0 7 5 33/220kV substations to ISTS $198 million of which IBRD L substations for Agar, Shajapu oan: US$75 million and CTF r and Neemuch Solar Park Loan: US$23 million) IN-RUMSL-191683-CW-RFB / Development of Eight 33/222 Component 1: Shared Infrast 0 kV substations for 1500 M ructure for Solar Parks (esti W Solar parks in Madhya Pra mated total project cost: US Single Stage - Two E 25,400,000.0 25,031,632. 2022-06-1 IBRD / 87370 Prior Request for Bids Open - National Signed 2020-09-10 2020-12-23 2020-09-12 2021-01-28 2020-10-27 2021-07-08 2020-11-17 2021-08-18 2020-12-01 2021-10-26 desh - two substations for 55 $198 million of which IBRD L nvelope 0 02 4 0 MW Agar Solar Park, three oan: US$75 million and CTF substations for 450 MW Shaj Loan: US$23 million) apur Solar Park, and three su bstations for 500 MW Neemu ch Solar Park GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IN-RUMSL-19552-GO-RFB / C Component 1: Shared Infrast ontract for supply of nine 33/ ructure for Solar Parks (esti Single Stage - One E 220 kV, 100 MVA step up tra IBRD / 87370 mated total project cost: US Post Request for Bids Open - National 7,115,924.28 0.00 Canceled 2017-06-29 2017-06-29 2017-06-29 2017-06-29 2017-06-29 2017-12-26 nvelope nsformer for 750 MW of Rew $198 million of which IBRD L a Project oan: US$75 million and CTF Loan: US$23 million) Page 1 Component 1: Shared Infrast IN-RUMSL-19554-GO-RFB / C ructure for Solar Parks (esti ontract for supply of three 33 Single Stage - One E IBRD / 87370 mated total project cost: US Post Request for Bids Open - National 2,484,928.08 0.00 Canceled 2017-06-29 2017-06-29 2017-06-29 2017-06-29 2017-06-29 2017-12-26 /220 kV, 100 MVA transforme nvelope $198 million of which IBRD L r for Mandsaur Solar Project oan: US$75 million and CTF Loan: US$23 million) NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IN-RUMSL-121568-CS-LCS / Component 2 - Technical As Survey for Identification of av sistance (Estimated Cost: US Least Cost Selecti TF / A4639 Post Open - National 43,000.00 0.00 Canceled 2019-08-12 2019-12-26 2019-08-12 2020-01-15 2019-08-26 2020-01-23 2019-09-23 2019-10-07 2019-10-16 2019-10-30 2020-03-28 ailable ravine land for solar p $2 million of which CTF Gran on roject in 3 selected districts o t:US$2 million) f the state IN-RUMSL-121569-CS-LCS / Component 2 - Technical As Least Cost Selecti Base line survey of Land in S TF / A4639 sistance (Estimated Cost: US Post Open - National 43,000.00 0.00 Canceled 2019-08-12 2019-12-26 2019-08-12 2020-01-15 2019-08-29 2020-01-23 2019-09-26 2019-10-10 2019-10-17 2019-10-31 2020-03-29 on agar district for new solar pro $2 million of which CTF Gran jects/parks t:US$2 million) IN-RUMSL-121572-CS-QCBS Component 2 - Technical As / Preparing a Business Plan fo sistance (Estimated Cost: US Quality And Cost- TF / A4639 Post Open - National 43,000.00 152,725.18 Terminated 2019-08-12 2019-12-26 2019-08-12 2020-01-15 2019-08-14 2020-01-23 2019-09-13 2020-06-22 2019-09-27 2020-07-16 2019-10-04 2020-07-16 2019-10-18 2021-01-16 2020-04-15 r RUMSL and Institutional Ca $2 million of which CTF Gran Based Selection pacity Building of RUMSL t:US$2 million) IN-RUMSL-121574-CS-QCBS Component 2 - Technical As / Planning publicity, communi sistance (Estimated Cost: US Quality And Cost- cation strategies and media TF / A4639 Post Open - National 200,000.00 0.00 Canceled 2019-08-12 2019-12-15 2019-08-12 2020-01-15 2019-08-16 2020-01-23 2019-09-20 2019-10-04 2019-10-14 2019-10-30 2021-10-29 $2 million of which CTF Gran Based Selection plan for RUMSL's existing, on t:US$2 million) going and future project IN-RUMSL-121576-CS-QCBS Component 2 - Technical As Quality And Cost- / Management System for m TF / A4639 sistance (Estimated Cost: US Post Open - National 200,000.00 0.00 Canceled 2019-08-12 2019-12-26 2019-08-12 2019-08-20 2019-09-19 2019-10-03 2019-10-10 2019-10-24 2020-03-12 Based Selection anaging large solar parks an $2 million of which CTF Gran d projects t:US$2 million) IN-RUMSL-125718-CS-LCS / Component 2 - Technical As Refurbishment of existing RU sistance (Estimated Cost: US Least Cost Selecti TF / A4639 Post Open - National 36,000.00 15,264.40 Signed 2019-08-12 2019-12-15 2019-08-12 2020-01-15 2019-08-19 2020-01-23 2019-09-17 2020-06-22 2019-10-01 2020-07-16 2019-10-12 2020-09-01 2019-10-24 2020-10-08 2020-03-22 MSL website to make it dyna $2 million of which CTF Gran on mic and more user friendly t:US$2 million) IN-RUMSL-126037-CS-LCS / Component 2 - Technical As Power system assessment an sistance (Estimated Cost: US Least Cost Selecti TF / A4639 Post Open - National 28,570.00 0.00 Canceled 2019-08-12 2019-08-12 2019-08-27 2019-09-25 2019-10-09 2019-10-17 2019-10-31 2020-02-28 d planning for renewable ene $2 million of which CTF Gran on rgy integration in MP t:US$2 million) IN-RUMSL-182192-CS-QCBS / Environment and Social Bas Component 2 - Technical As eline Survey for Identification sistance (Estimated Cost: US Quality And Cost- TF / A4639 Post Open - National 71,000.00 0.00 Canceled 2020-07-14 2020-11-16 2020-07-14 2020-08-13 2020-08-13 2020-08-20 2020-08-27 2020-09-10 2021-02-07 of Land for Proposed Solar Pa $2 million of which CTF Gran Based Selection rk in Cluster – 1. Morena, 2. C t:US$2 million) hattarpur, District in Madhya Pradesh IN-RUMSL-182192-CS-QCBS- 2 / Environment and Social B Component 2 - Technical As aseline Survey for Identificati sistance (Estimated Cost: US Quality And Cost- Under Implement TF / A4639 Post Open - National 71,000.00 0.00 2021-01-28 2021-01-22 2021-01-28 2021-01-30 2021-01-22 2021-02-24 2021-02-23 2021-03-03 2021-03-04 2021-03-11 2021-03-28 2021-08-15 on of Land for Proposed Solar $2 million of which CTF Gran Based Selection ation Park in Cluster – 1. Morena, 2 t:US$2 million) . Chattarpur, District in Madh ya Pradesh IN-RUMSL-275866-CS-QCBS Component 2 - Technical As / Direct RFP: Evaluate feasibil sistance (Estimated Cost: US Quality And Cost- TF / A4639 Post Open - National 200,000.00 472,368.25 Signed 2022-05-27 2022-05-27 2022-05-27 2022-05-27 2022-05-27 2022-06-24 2022-06-23 2022-07-04 2022-07-25 2022-07-25 2022-07-29 2022-08-29 2022-09-12 2023-04-26 ity of developing floating sola $2 million of which CTF Gran Based Selection r park at selected three dams t:US$2 million) /reservoirs IN-RUMSL-381542-CS-QCBS / RUMSL is Selecting a Firm f or Design, Development and Component 2 - Technical As Maintenance of integrated W sistance (Estimated Cost: US Quality And Cost- Pending Impleme ebsite and Project Registratio TF / A4639 Post Open - National 80,000.00 0.00 2023-09-13 2023-09-13 2023-09-13 2023-10-03 2023-10-08 2023-10-18 2023-10-28 2024-04-25 $2 million of which CTF Gran Based Selection ntation n Portal for New & Renewabl t:US$2 million) e Energy Department (NRED) , GoMP and revamping of We bsites of MP Urja Vikas Niga m Limited (MPUVNL) and Re wa Ultra IN-RUMSL-395269-CS-QCBS Component 2 - Technical As / Selection of a Firm for cons sistance (Estimated Cost: US Quality And Cost- Under Implement ultancy services for Develop TF / A4639 Post Open - National 80,000.00 0.00 2023-11-28 2023-09-30 2023-11-28 2023-12-19 2023-12-24 2023-12-29 2024-01-05 2024-01-30 2024-05-29 $2 million of which CTF Gran Based Selection ation ment of Environment, Social t:US$2 million) and Governance (ESG) Strate gy. IN-RUMSL-396782-CS-QCBS / Selection of Consultant to u Component 2 - Technical As ndertake ‘End-term Evaluatio sistance (Estimated Cost: US Quality And Cost- Pending Impleme n of the Environmental Mana TF / A4639 Post Open - National 20,000.00 0.00 2023-12-07 2023-12-07 2023-12-07 2023-12-28 2024-01-04 2024-01-11 2024-01-21 2024-05-20 $2 million of which CTF Gran Based Selection ntation gement and R&R component t:US$2 million) s of the 750 MW Solar Power Project, Rewa District, Madhy a Pradesh INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IN-RUMSL-129224-CS-INDV / Component 2 - Technical As Hiring of safeguards experts sistance (Estimated Cost: US Individual Consult to monitor and report on safe TF / A4639 Post Open 28,600.00 0.00 Canceled 2019-09-05 2019-10-24 2019-11-14 2019-12-19 2020-06-16 $2 million of which CTF Gran ant Selection guards/ESMP implementation t:US$2 million) at various solar parks (ongoi ng and pipeline) Page 2 IN-RUMSL-216493-CS-INDV / Component 2 - Technical As Hiring of Environment Expert sistance (Estimated Cost: US Individual Consult for implementation of the En TF / A4639 Post Open 46,285.00 0.00 Canceled 2021-01-28 2021-02-24 2021-03-03 2021-03-17 2024-03-16 $2 million of which CTF Gran ant Selection vironmental Safeguards for t:US$2 million) World Bank funded solar par k projects. IN-RUMSL-217011-CS-INDV / Component 2 - Technical As Hiring of Social Expert for im sistance (Estimated Cost: US Individual Consult plementation of the Social S TF / A4639 Post Open 46,285.00 0.00 Canceled 2021-02-01 2021-02-26 2021-03-03 2021-03-17 2024-03-16 $2 million of which CTF Gran ant Selection afeguards for World Bank fun t:US$2 million) ded solar park projects. Component 2 - Technical As IN-RUMSL-225984-CS-INDV / Individual Consult Pending Impleme TF / A4639 sistance (Estimated Cost: US Post Open 64,285.00 0.00 2021-03-23 2021-04-21 2021-04-28 2021-05-15 2024-05-14 Hiring of Environment Expert ant Selection ntation $2 million of which CTF Gran t:US$2 million) Component 2 - Technical As IN-RUMSL-225994-CS-INDV / Individual Consult Pending Impleme TF / A4639 sistance (Estimated Cost: US Post Open 64,285.00 0.00 2021-03-23 2021-04-21 2021-04-28 2021-05-15 2024-05-14 Hiring of Social expert ant Selection ntation $2 million of which CTF Gran t:US$2 million) IN-RUMSL-419901-CS-CDS / Component 2 - Technical As Hiring of consultants for draft sistance (Estimated Cost: US Pending Impleme IBRD / 87370 Post Direct Selection Direct - National 99,000.00 0.00 2024-04-08 2024-04-14 2024-04-24 2024-06-23 ing Energy Transition Roadm $2 million of which CTF Gran ntation ap for Madhya Pradesh. t:US$2 million) IN-RUMSL-420967-CS-CDS / Comprehensive GIS-based So lar Monitoring System would Component 2 - Technical As help in - Real Time Tracking, sistance (Estimated Cost: US Pending Impleme IBRD / 87370 Post Direct Selection Direct - National 50,000.00 0.00 2024-04-12 2024-04-16 2024-05-06 2025-05-06 Progress Monitoring, Data Int $2 million of which CTF Gran ntation egration, Monitoring using Ti t:US$2 million) me-series Satellite Imagery, and On Demand Monitoring u sing Drone Technology. Page 3