PROCUREMENT PLAN (Textual Part) Project information: Rwanda, Nile Cooperation for Climate Resilience P- 172848 Project Implementation agency: Nile Equatorial Strategic Action Plan (NELSAP) Date of the Procurement Plan: April 19, 2021 Period covered by this Procurement Plan: April 2021–April 2022 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in Nile Basin Procurement and Disposal Manual (for NELSAP, NILE-SEC & ENTRO), such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. When other own procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. Not Applicable. Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables Not Applicable. Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Not Applicable. Goods: [is not applicable/is applicable for those contracts identified in the Procurement Plan tables]; Works: [is not applicable/is applicable for those contracts identified in the Procurement Plan tables] PROCUREMENT Eastern and Southern Africa : Nile Cooperation for Climate Resilience PLAN General Information Country: Eastern and Southern Africa 2021-06-28 Bank’s Approval Date of the Original Procurement Plan: 2024-04-15 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P172848 GPN Date: 2021-06-30 Project Name: Nile Cooperation for Climate Resilience Loan / Credit No: TF / B4716 Eastern Nile Technical Regional Office Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned ET-ENTRO-335323-CW-RFB / Request for Bids - Component 3: Improving Me Office Refurbishment(Interna Single Stage - One E Small Works SPD 2023-11-0 TF / B4716 chanisms for Cooperation in Post Request for Bids Open - National 60,000.00 0.00 Signed 2023-01-19 2023-02-06 2023-01-24 2023-02-07 2023-03-07 2022-02-20 2023-04-06 2023-03-08 2023-05-11 2023-04-24 l Painting, Ceiling and Roofin nvelope (1 envelope proce 7 the Eastern Nile g, and Carpet Work) ss) Request for Quota ET-ENTRO-237391-CW-RFQ / Component 3: Improving Me Request for Quota Single Stage - One E tions - Small Work 2022-05-1 Office upgrading (Minor Civil TF / B4716 chanisms for Cooperation in Post Open - National 60,000.00 0.00 Canceled 2021-09-18 2022-10-24 2021-11-13 tions nvelope s (Emergency) SP 2 Works for Office Refurbishme the Eastern Nile D -Competitive nt) GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ET-ENTRO-263453-GO-RFQ / Component 3: Improving Me Request for Quota Single Stage - One E Under Imple Procurement of Professional TF / B4716 chanisms for Cooperation in Post Limited 3,000.00 0.00 2021-12-31 2022-02-25 2022-04-26 tions nvelope mentation Camera for Internship the Eastern Nile ET-ENTRO-237876-GO-RFB / Procurement of IT Equipment as a package under three Lot Component 3: Improving Me Open - Internationa Single Stage - One E s (Lot I: Server and Storage s TF / B4716 chanisms for Cooperation in Post Request for Bids 345,500.00 0.00 Signed 2021-09-30 2022-01-21 2021-10-05 2024-01-11 2021-11-16 2022-02-28 2021-12-16 2023-03-10 2022-01-20 2022-05-21 2022-07-19 l nvelope erver, Lot II: Hi end Desktop, the Eastern Nile and Laptop & Lot III: Scanner s/Digitizers/Plotters and also Power backup ET-ENTRO-338666-GO-RFB / Component 3: Improving Me Request for Quota Single Stage - One E Procurement of Power Backu TF / B4716 chanisms for Cooperation in Post Open - National 180,000.00 0.00 Signed 2023-03-03 2023-03-03 2023-04-28 2023-06-03 2023-10-25 tions nvelope p(Integrated Mini Data Cente the Eastern Nile r) Component 3: Improving Me ET-ENTRO-338673-GO-RFQ / Request for Quota Single Stage - One E TF / B4716 chanisms for Cooperation in Post Open - National 60,000.00 0.00 Signed 2023-02-25 2023-03-07 2023-04-22 2023-06-06 2023-10-19 Backup Storage Server tions nvelope the Eastern Nile ET-ENTRO-237876-GO-RFB-2 022 / Procurement of IT Equi pment as a package under th Component 3: Improving Me Open - Internationa Single Stage - One E Pending Impl ree Lots (Lot I: Server and St TF / B4716 chanisms for Cooperation in Post Request for Bids 345,500.00 0.00 2022-01-21 2022-01-26 2022-03-09 2022-04-08 2022-05-13 2022-11-09 l nvelope ementation orage server, Lot II: Hi end D the Eastern Nile esktop, and Laptop & Lot III: Scanners/Digitizers/Plotters a nd also Power backup ET-ENTRO-237866-GO-RFQ / Component 3: Improving Me Request for Quota Single Stage - One E LAN/WAN/routers/switches - f TF / B4716 chanisms for Cooperation in Post Limited 79,000.00 0.00 Canceled 2021-10-23 2021-12-18 2022-06-16 tions nvelope or upgrading ENTRO IT unit the Eastern Nile ET-ENTRO-237511-GO-RFQ / Component 3: Improving Me Videoconferencing facility an Request for Quota Single Stage - One E TF / B4716 chanisms for Cooperation in Post Open - National 85,000.00 0.00 Canceled 2021-10-30 2021-12-25 2022-06-23 d Touchscreens/Touch Tables tions nvelope the Eastern Nile /Decision Theater - ENTRO ET-ENTRO-416590-GO-RFQ / Procurement of IT EQT LOT I - (AIO Color printer 2 , APC Symmetra PX Battery, A Component 3: Improving Me C AUX & Portable Video Conf Single Stage - One E Pending Impl TF / B4716 chanisms for Cooperation in Post Request for Bids Open - National 135,000.00 0.00 2024-04-22 2024-04-29 2024-07-08 2024-08-07 2024-09-11 2025-03-10 erence) nvelope ementation the Eastern Nile LOT II-(Tablet, KVM: Dell 16-p ort switch Bundle, I/O Module Dell Unity XT 480, APC Symm etra PX - System Power Suppl y & Intelligence Module) NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 3: Improving Me ET-ENTRO-237404-NC-RFQ / Request for Quota Open - Internationa Single Stage - One E Pending Impl TF / B4716 chanisms for Cooperation in Post 100,000.00 0.00 2021-11-27 2022-01-22 2022-07-21 Cloud Services tions l nvelope ementation the Eastern Nile ET-ENTRO-263443-NC-RFQ / Component 3: Improving Me Procurement of Software lice Request for Quota Single Stage - One E TF / B4716 chanisms for Cooperation in Post Limited 10,200.00 0.00 Canceled 2021-12-20 2022-02-14 2022-04-15 nses (Office productivity: Offi tions nvelope the Eastern Nile ce, MS Teams, anti-virus, ado be) – ENTRO CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ET-ENTRO-237319-CS-QCBS / WP1:” Survey and Data Coll Component 3: Improving Me Quality And Cost- Open - Internationa ection” for preparation of Flo TF / B4716 chanisms for Cooperation in Post 220,000.00 0.00 Signed 2021-08-16 2022-05-23 2021-09-06 2022-07-08 2021-10-20 2022-09-13 2021-11-17 2022-11-07 2021-12-17 2022-11-23 2022-01-21 2022-12-08 2022-02-25 2023-01-18 2022-06-25 Based Selection l od modeling and Strengtheni the Eastern Nile ng FFEW in EN region Page 1 ET-ENTRO-237337-CS-QCBS / WP 3:” Support in Establishi ng Flood Community Awaren Component 3: Improving Me Quality And Cost- Open - Internationa Under Implement ess and Preparedness” of Ea TF / B4716 chanisms for Cooperation in Post 308,000.00 0.00 2021-09-20 2021-07-28 2021-10-11 2023-02-15 2021-11-24 2023-08-31 2021-12-22 2023-11-20 2022-01-21 2022-02-25 2022-04-01 2023-01-26 Based Selection l ation stern Nile community & capa the Eastern Nile city building (developing floo d management strategies & f lood preparedness) ET-ENTRO-237340-CS-QCBS / Drought forecast and dashb Component 3: Improving Me Quality And Cost- Open - Internationa oard development for deliver TF / B4716 chanisms for Cooperation in Post 220,000.00 0.00 Signed 2021-08-02 2023-01-11 2021-08-23 2023-02-01 2021-10-06 2023-05-11 2021-11-03 2023-07-14 2021-12-03 2023-07-28 2022-01-07 2023-08-03 2022-02-11 2023-09-26 2022-12-08 Based Selection l ing drought forecast to end u the Eastern Nile ser for entire Nile basin ET-ENTRO-232928-CS-QCBS / Consultancy service for Basi Component 3: Improving Me Quality And Cost- Open - Internationa n wide for development of re TF / B4716 chanisms for Cooperation in Post 800,000.00 796,746.01 Signed 2021-08-15 2021-07-28 2021-09-05 2021-10-08 2021-10-19 2022-01-20 2021-12-15 2022-03-21 2022-01-14 2022-04-15 2022-02-18 2022-05-10 2022-03-25 2022-07-12 2023-09-21 Based Selection l ference framework and imple the Eastern Nile mentation strategy for dam s afety management ET-ENTRO-237321-CS-QCBS Component 3: Improving Me / WP 2: " Enhancement of the Quality And Cost- Open - Internationa TF / B4716 chanisms for Cooperation in Post 396,000.00 0.00 Signed 2021-08-23 2021-07-28 2021-09-13 2022-12-16 2021-10-27 2023-01-23 2021-11-24 2023-03-22 2021-12-24 2023-05-30 2022-01-28 2023-06-30 2022-03-04 2023-07-20 2022-12-29 EN-FFEWS and Flood Risk Ma Based Selection l the Eastern Nile pping” in EN region ET-ENTRO-383356-CS-QCBS Component 3: Improving Me / Development of WRP Tools Quality And Cost- Open - Internationa Under Implement TF / B4716 chanisms for Cooperation in Post 284,000.00 0.00 2023-10-02 2023-10-04 2023-10-23 2023-10-30 2023-12-06 2024-01-05 2024-01-03 2024-02-02 2024-03-08 2024-04-12 2025-07-11 and Models development, pa Based Selection l ation the Eastern Nile ckaging and developing Infor mation Service ET-ENTRO-416579-CS-QCBS Component 3: Improving Me / Consultancy service for Wat Quality And Cost- Open - Internationa Under Implement TF / B4716 chanisms for Cooperation in Post 240,000.00 0.00 2024-04-01 2024-04-01 2024-04-22 2024-06-05 2024-07-03 2024-08-02 2024-09-06 2024-10-11 2025-04-29 er Smart Irrigation Implemen Based Selection l ation the Eastern Nile tation in the Nile Basin INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ET-ENTRO-232933-CS-INDV / Enhance the technical and in Component 3: Improving Me Individual Consult stitutional capacity of dams t TF / B4716 chanisms for Cooperation in Post Open 110,000.00 0.00 Signed 2021-08-08 2021-07-28 2021-10-09 2023-12-04 2021-10-30 2023-12-12 2021-12-18 2022-06-16 ant Selection hrough on job trainings and e the Eastern Nile nsure safe design) (Team Le ader) ET-ENTRO-232934-CS-INDV / Enhance the technical and in Component 3: Improving Me stitutional capacity of dams t Individual Consult TF / B4716 chanisms for Cooperation in Post Open 103,000.00 0.00 Signed 2021-08-02 2021-07-28 2021-09-20 2023-04-04 2021-10-11 2023-12-11 2021-11-15 2022-05-14 hrough on job trainings and e ant Selection the Eastern Nile nsure safe design, constructi on and operation of dams in t he basin)/Institutional Special ist/ ET-ENTRO-232935-CS-INDV / Enhance the technical and in stitutional capacity of dams t Component 3: Improving Me Individual Consult hrough on job trainings and e TF / B4716 chanisms for Cooperation in Post Open 56,000.00 0.00 Signed 2021-08-02 2021-07-28 2021-09-27 2023-03-15 2021-10-18 2023-12-11 2021-12-08 2022-06-06 ant Selection nsure safe design, constructi the Eastern Nile on and operation of dams in t he basin)/Dam expert, for Mo dule development ET-ENTRO-232936-CS-INDV / Component 3: Improving Me Individual Consult Pending Impleme Developing/brand corporate TF / B4716 chanisms for Cooperation in Post Open 50,000.00 0.00 2021-09-20 2021-11-08 2021-11-29 2022-01-03 2022-07-02 ant Selection ntation communication products the Eastern Nile ET-ENTRO-232947-CS-INDV / Component 3: Improving Me Preparation of training mater Individual Consult TF / B4716 chanisms for Cooperation in Post Open 54,000.00 0.00 Signed 2021-09-15 2022-10-10 2021-11-03 2022-11-25 2021-11-24 2022-12-05 2021-12-29 2022-12-27 2022-06-27 ials and Conducting media tr ant Selection the Eastern Nile aining workshops (sub region al & regional) ET-ENTRO-232984-CS-INDV / Need and Gap assessment fo Component 3: Improving Me Individual Consult r Drought forecasting system TF / B4716 chanisms for Cooperation in Post Open 30,000.00 27,226.00 Signed 2021-08-02 2022-03-09 2021-09-20 2022-05-16 2021-10-11 2022-05-31 2021-11-15 2022-06-20 2022-05-14 ant Selection & up scaling to cover NEL reg the Eastern Nile ion and project TOR prepara tion ET-ENTRO-233000-CS-INDV / Component 3: Improving Me Individual Consult Internship Guideline preparat TF / B4716 chanisms for Cooperation in Post Open 30,000.00 19,240.00 Signed 2021-08-02 2022-03-07 2021-09-20 2022-05-23 2021-10-11 2022-06-06 2021-11-15 2022-06-20 2022-05-14 ant Selection ion the Eastern Nile ET-ENTRO-237348-CS-INDV / Individual Consultant to provi Component 3: Improving Me de training on Risk-Informed Individual Consult TF / B4716 chanisms for Cooperation in Post Open 33,000.00 33,000.00 Signed 2021-06-28 2021-07-28 2021-08-16 2021-11-18 2021-09-06 2022-03-15 2021-10-11 2022-04-03 2022-04-09 Decision Making (RIDM), Instr ant Selection the Eastern Nile umentation, surveillance and maintenance(Dam Safety Ex pert 1) ET-ENTRO-237351-CS-INDV / Individual Consultant to prov Component 3: Improving Me ide training on Risk-Informed Individual Consult TF / B4716 chanisms for Cooperation in Post Limited 33,000.00 26,500.00 Signed 2021-06-15 2021-07-28 2021-06-20 2021-11-22 2021-07-11 2022-02-01 2021-08-15 2022-02-06 2022-02-11 Decision Making (RIDM), Instr ant Selection the Eastern Nile umentation, surveillance and maintenance(Dam Safety Ex pert 2) ET-ENTRO-237353-CS-INDV / Individual Consultant to provi Component 3: Improving Me de training on Risk-Informed Individual Consult TF / B4716 chanisms for Cooperation in Post Limited 33,000.00 27,400.00 Signed 2021-07-27 2021-07-28 2021-08-01 2021-11-28 2021-08-22 2022-02-01 2021-09-26 2022-02-06 2022-03-25 Decision Making (RIDM), Instr ant Selection the Eastern Nile umentation, surveillance and maintenance(Dam Safety Ex pert 3) ET-ENTRO-237369-CS-INDV / Component 3: Improving Me Individual Consult Water Resources Planning Ex TF / B4716 chanisms for Cooperation in Post Open 216,000.00 60,000.00 Signed 2021-06-15 2021-06-29 2021-08-03 2021-11-21 2021-08-24 2021-12-13 2021-09-28 2021-12-18 2024-08-19 ant Selection pert(Project Staff) the Eastern Nile ET-ENTRO-237374-CS-INDV / Component 3: Improving Me Individual Consult Water Resources Modeller(Pr TF / B4716 chanisms for Cooperation in Post Open 180,000.00 0.00 Signed 2021-06-21 2023-06-22 2021-08-09 2023-10-26 2021-08-30 2023-11-26 2021-10-04 2023-11-12 2024-08-25 ant Selection oject Staff) the Eastern Nile ET-ENTRO-237383-CS-INDV / Component 3: Improving Me Individual Consult Internship Supervisor (Projec TF / B4716 chanisms for Cooperation in Post Open 120,000.00 37,000.00 Signed 2021-06-30 2021-06-29 2021-08-18 2021-11-18 2021-09-08 2021-12-13 2021-10-13 2021-12-18 2024-09-03 ant Selection t Staff) the Eastern Nile Page 2 ET-ENTRO-237386-CS-INDV / Component 3: Improving Me Individual Consult Procurement Officer (Project TF / B4716 chanisms for Cooperation in Post Open 120,000.00 0.00 Canceled 2021-07-12 2021-08-17 2021-08-30 2021-09-20 2021-10-25 2024-09-15 ant Selection Staff) the Eastern Nile ET-ENTRO-242852-CS-INDV / Component 3: Improving Me Individual Consult GIS and Remote Sensing Exp TF / B4716 chanisms for Cooperation in Post Open 90,000.00 0.00 Signed 2021-10-15 2023-01-26 2021-12-03 2023-09-14 2021-12-24 2023-09-20 2022-01-28 2023-10-10 2022-12-24 ant Selection ert( Project Contracted Staff) the Eastern Nile ET-ENTRO-260322-CS-INDV / Component 3: Improving Me Individual Consult Procurement Officer(Project TF / B4716 chanisms for Cooperation in Prior Open 120,000.00 0.00 Canceled 2021-10-28 2021-12-16 2022-01-06 2022-02-10 2025-03-08 ant Selection Staff) the Eastern Nile ET-ENTRO-237378-CS-INDV / Component 3: Improving Me Individual Consult GIS & Remote Sensing Exper TF / B4716 chanisms for Cooperation in Post Open 90,000.00 0.00 Canceled 2021-09-20 2021-11-08 2021-11-29 2022-01-03 2024-11-24 ant Selection t(Project Staff) the Eastern Nile ENTRO-CS-INDV-237386-202 Component 3: Improving Me Individual Consult Under Implement 1 / Procurement Officer(Proje TF / B4716 chanisms for Cooperation in Prior Open 120,000.00 0.00 2021-08-15 2021-12-14 2021-10-03 2023-07-09 2021-10-24 2021-11-28 2025-11-30 ant Selection ation ct Staff) the Eastern Nile ET-ENTRO-300664-CS-INDV / Component 3: Improving Me Individual Consult Internship Program Coordinat TF / B4716 chanisms for Cooperation in Post Open 99,000.00 0.00 Signed 2022-07-15 2022-06-23 2022-09-02 2022-09-16 2022-09-23 2022-09-20 2022-10-28 2022-09-28 2025-06-30 ant Selection or/Water Resource Engineer( the Eastern Nile Project Staff) ET-ENTRO-317172-CS-INDV / Component 3: Improving Me Individual Consult Open - Internationa Need and Gap assessment of TF / B4716 chanisms for Cooperation in Post 30,000.00 0.00 Signed 2022-10-07 2022-11-02 2022-11-25 2023-01-03 2022-12-16 2023-01-24 2023-01-20 2023-02-02 2023-07-19 ant Selection l WR Tools and Models the Eastern Nile ET-ENTRO-322653-CS-INDV / Component 3: Improving Me Individual Consult Direct - Internation EUMETSAT GEONETCast Inst TF / B4716 chanisms for Cooperation in Post 10,000.00 0.00 Signed 2022-10-31 2022-11-02 2022-11-10 2022-12-05 2022-12-01 2023-01-20 2023-01-05 2023-01-31 2023-02-04 ant Selection al allation at ENTRO the Eastern Nile ET-ENTRO-322664-CS-INDV / Component 3: Improving Me Upgrading ENTRO-DSpace V6 Individual Consult TF / B4716 chanisms for Cooperation in Post Direct - National 5,000.00 0.00 Signed 2022-11-14 2022-11-16 2022-11-24 2023-08-09 2022-12-15 2023-09-08 2023-01-19 2023-09-14 2023-03-20 to V7 to improve ENTRO Libr ant Selection the Eastern Nile ary resources and Services ET-ENTRO-362903-CS-INDV / Component 3: Improving Me Individual Consult Under Implement Dam Safety Consultant(Short TF / B4716 chanisms for Cooperation in Prior Limited 15,000.00 0.00 2023-06-07 2023-06-20 2023-06-12 2023-06-15 2023-07-03 2023-10-01 ant Selection ation Term Consultant) the Eastern Nile ET-ENTRO-378566-CS-INDV / Prepare materials and Condu Component 3: Improving Me Individual Consult Under Implement ct gender training workshops TF / B4716 chanisms for Cooperation in Post Limited 10,000.00 0.00 2023-09-01 2023-09-01 2023-09-06 2023-09-27 2023-11-01 2023-12-16 ant Selection ation for ENTRO Staff and EN coun the Eastern Nile tries (regional) (ENTRO) ET-ENTRO-378567-CS-INDV / Prepare materials and Condu Component 3: Improving Me Individual Consult Open - Internationa Under Implement ct media training workshops TF / B4716 chanisms for Cooperation in Post 10,000.00 0.00 2023-10-02 2023-10-06 2023-11-20 2023-12-11 2024-01-15 2024-03-15 ant Selection l ation (sub-regional, regional level), the Eastern Nile including field visit for reporti ng opportunity (ENTRO) Component 3: Improving Me ET-ENTRO-383361-CS-INDV / Individual Consult Open - Internationa Pending Impleme TF / B4716 chanisms for Cooperation in Post 108,000.00 0.00 2023-11-12 2023-12-31 2024-01-21 2024-02-25 2025-11-06 Project Officer (Project Staff) ant Selection l ntation the Eastern Nile ET-ENTRO-322659-CS-INDV / Component 3: Improving Me Replicating the FFEW at ENT Individual Consult Direct - Internation TF / B4716 chanisms for Cooperation in Post 6,000.00 0.00 Canceled 2022-10-31 2022-11-02 2022-11-10 2022-12-01 2023-01-05 2023-02-04 RO Server from Cloud and Di ant Selection al the Eastern Nile splay forecasts in IKP ET-ENTRO-242849-CS-INDV / Component 3: Improving Me Individual Consult Water Resource Modeler(Proj TF / B4716 chanisms for Cooperation in Post Open 180,000.00 0.00 Canceled 2021-10-03 2021-08-17 2021-12-03 2021-12-24 2022-01-21 2025-01-20 ant Selection ect Staff) the Eastern Nile Page 3