PROCUREMENT PLAN (Textual Part) Project information: Democratic Republic Democratic of Congo – Regional Disease Surveillance Systems Enhancement - P167817 Project Implementation agency: UGP PDSS Date of the Procurement Plan: June 2019 Period covered by this Procurement Plan: June 2019 – December 2020 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016 and revised November 2017) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the Borrower’s Public Procurement Law No 10/010 of April 27, 2010 (PPL) and the Manual of Procedures of the PPL as per Borrower’s Decree No 10/22 of June 2, 2010, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. (a) Standard Bidding Documents: All standard bidding documents to be used for the Project under NCB shall be found acceptable to the World Bank before their use during the implementation of Project; (b) Eligibility: Eligibility of bidders and acceptability of their goods and services shall not be based on their nationality and/or their origin; and association with a national firm shall not be a condition for participation in a bidding process. Therefore, except for the ineligibility situations referred to in paragraphs 1.10(a) (i) and 1.10(a) (ii) of the Procurement Guidelines, the eligibility of bidders must be based solely on their qualification, experience and capacity to carry out the contract related to the specific bidding process; (c) Advertising and Bid Preparation Time: Bidding opportunities shall be advertised at least in a national newspaper of wide circulation and on the website of the Recipient’s Procurement Regulator (Autorité de Régulation des Marchés Publics) and bidders should be given at least 30 days from the date of invitation to bid or the date of availability of the bidding documents, whichever is later; (d) Criteria for Qualification of Bidders: Qualification criteria shall only concern the bidder’s capability and resources to perform the contract taking into account objective and measurable factors. Such criteria for qualification of bidders shall be clearly specified in the bidding documents; (e) Bid Evaluation and Contract Award: A contract shall be awarded to the substantially responsive and lowest evaluated bidder provided that such bidder meets the qualification criteria specified in the bidding documents. No scoring system shall be allowed for the evaluation of bids, and no “blanket” limitation to the number of lots which can be awarded to a bidder shall apply. The criteria for bid evaluation and the contract award conditions shall be clearly specified in the bidding documents; (f) Preferences: No preference shall be given to domestic/regional bidders; to domestically/regionally manufactured goods; and to bidders forming a joint venture with a national firm or proposing national sub-contractors or carrying out economic activities in the territory of the Recipient; (g) Publication of Contract Award: Information on all contract awards shall be published in at least a national newspaper of wide circulation or in the Recipient’s Procurement Regulator (Autorité de Régulation des Marchés Publics) web-site; (h) Fraud and Corruption: In accordance with the Procurement Guidelines, each bidding document and contract shall include provisions stating the World Bank’s policy to sanction firms or individuals found to have engaged in fraud and corruption as set forth in the Procurement Guidelines; (i) Inspection and Audit Rights: In accordance with the Procurement Guidelines, each bidding document and contract shall include provisions stating the World Bank’s policy with respect to inspection and audit of accounts, records and other documents relating to the bid submission and contract performance; (j) Requirement for administrative documents and/or tax clearance certificate: The bidding documents shall not require foreign bidders to produce any administrative or tax related certificates prior to confirmation of awarding a contract; and (k) Modifications of a Signed Contract: Any change in the contract amount which, singly or combined with all previous changes, increases the original contract amount by fifteen (15) percent or more must be done through an amendment to the signed contract instead of signing a new contract. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables. “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: is applicable for those contracts identified in the Procurement Plan tables; Other Relevant Procurement Information. “Not Applicable” PROCUREMENT Central Africa : Regional Disease Surveillance Systems Enhancement Project (REDISSE) Phase IV PLAN General Information Country: Central Africa Bank’s Approval Date of the Original Procurement Plan:2019-06-10 2023-04-15 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P167817 GPN Date: 2020-05-18 Project Name: Regional Disease Surveillance Systems Enhancement Project (REDISSE) Phase IV Loan / Credit No: / , IDA / D5160, IDA / 64980, IDA / 64990, IBRD / 90040 RDC-MINISTERE DE LA SANTE PUBLIQUE Executing Agency(ies): WORKS Activity Reference No. / Procurement Estimated Actual A Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Process S Draft Pre-qualificatio Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission Contract Comple Description Component Review Type Method Document Typ Amount (U mount (U and Recommendatio Signed Contract o. h cess (Y/N) isk tatus n Documents ation Report ent / Justification Notice / Invitation s Issued / Opening / Minutes tion e S$) S$) n for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned ZR-DRC-MSP-117854-CW-RF Component 1: Strengthenin Single Stage - One 8,500,000.0 2020-05-3 B / Construction de laboratoi / g Surveillance and Laborato A priori Appel d'offres Open - National 0.00 Annulé 2019-08-12 2019-08-17 2019-09-28 2019-10-28 2019-12-02 Envelope 0 0 res de référence ry Capacity to Rapidly detec t Outbreaks ZR-DRC-MSP-117857-CW-RF Component 1: Strengthenin Single Stage - One 7,000,000.0 2020-06-0 B / Réhabilitation de laborat / g Surveillance and Laborato A priori Appel d'offres Open - National 0.00 Annulé 2019-08-19 2019-08-24 2019-10-05 2019-11-04 2019-12-09 Envelope 0 6 oires dans la zone d'interven ry Capacity to Rapidly detec tion du projet t Outbreaks ZR-DRC-MSP-117888-CW-RF Q / Réhabilitation des locaux Component 3: Public Healt Single Stage - One 2020-04-3 / A posteriori Demande de prix Limited 500,000.00 0.00 Annulé 2019-09-07 2019-11-02 pour abriter les centres médi h Workforce Development Envelope 0 caux (Postes d'inspection Fr ontalières (PIF) ZR-DRC-MSP-184473-CW-RF Component 1: Strengthenin Q / Réhabiliter 18 locaux pou g Surveillance and Laborato Single Stage - One 2021-04-3 IDA / 64980 A posteriori Demande de prix Limited 30,000.00 0.00 Annulé 2020-09-06 2020-11-01 r les soins des animaux et la ry Capacity to Rapidly detec Envelope 0 quarantaine animale t Outbreaks ZR-DRC-MSP-184479-CW-RF Component 1: Strengthenin Single Stage - One 2021-09-2 Q / Réhabiliter le Bureau Nat IDA / D5160 g Surveillance and Laborato A posteriori Demande de prix Limited 39,900.00 0.00 Annulé 2021-01-28 2021-03-25 Envelope 1 ional du PNCPS ry Capacity to Rapidly detec t Outbreaks ZR-DRC-MSP-117872-CW-RF Component 1: Strengthenin B / Construction et équipem g Surveillance and Laborato Single Stage - One 2,000,000.0 2020-06-0 / A posteriori Appel d'offres Open - National 0.00 Annulé 2019-08-21 2019-08-26 2019-10-07 2019-11-06 2019-12-11 ent d'un laboratoire national ry Capacity to Rapidly detec Envelope 0 8 de diagnostic vétérinaire de t Outbreaks niveau 1 ZR-DRC-MSP-200124-CW-RF Component 1: Strengthenin Q / Réhabilitation deux (2) cl g Surveillance and Laborato Single Stage - One 2021-09-0 IDA / 64980 A posteriori Demande de prix Limited 250,000.00 0.00 Annulé 2021-01-10 2021-03-07 iniques des plantes à : Kinsh ry Capacity to Rapidly detec Envelope 3 asa et Lubumbashi. t Outbreaks ZR-DRC-MSP-200136-CW-RF Component 2: Strengthenin Q / Réhabilitation du Bureau g Emergency Planning and Single Stage - One 2021-09-2 National du Programme Nati IDA / D5160 A posteriori Demande de prix Limited 50,000.00 0.00 Annulé 2021-01-27 2021-03-24 Management Capacity to Ra Envelope 0 onal de Communication et Pr pidly respond to Outbreaks omotion de la Santé (PNCPS) à Kinshasa ZR-DRC-MSP-200137-CW-RF Component 4: Institutional Single Stage - One 1,000,000.0 2021-11-1 B / Réhabilitation des Bureau IDA / 64980 Capacity Building, Project M A posteriori Appel d'offres Open - National 0.00 Annulé 2021-01-25 2021-01-30 2021-03-13 2021-04-12 2021-05-17 Envelope 0 3 x du Projet REDISSE anagement, Coordination a nd Advocacy ZR-DRC-MSP-200143-CW-RF Q / Construction des nouvea Component 4: Institutional ux locaux (Bureaux et salles Capacity Building, Project M Single Stage - One 2021-09-2 IDA / 64980 A posteriori Demande de prix Limited 105,000.00 0.00 Annulé 2021-01-30 2021-03-27 des réunions) pour le Point F anagement, Coordination a Envelope 3 ocal Règlement Sanitaire Int nd Advocacy ernational (RSI) du PNHF à Ki nshasa. Document nation ZR-DRC-MSP-238522-CW-RF Component 1: Strengthenin al de passation d Q / Travaux de réhabilitation g Surveillance and Laborato Single Stage - One es marchés - Proc 2,500,000.0 En attente 2022-03-2 IDA / 64980 A posteriori Demande de prix Open - National 0.00 2021-07-28 2021-09-22 du laboratoire provincial de ry Capacity to Rapidly detec Envelope essus à une enve 0 d'exécution 1 Bunia t Outbreaks loppe (DTPM ne p rovenant pas de l a Banque) ZR-DRC-MSP-272385-CW-RF Component 4: Institutional Demande d'offres B / Travaux de réhabilitation Capacity Building, Project M Single Stage - One - DTPM Petits trav En attente 2023-04-1 IDA / 64980 A posteriori Appel d'offres Open - National 700,000.00 0.00 2022-06-27 2022-07-02 2022-08-13 2022-09-12 2022-10-17 des bureaux du PFN, RSI, SE anagement, Coordination a Envelope aux - (Processus d'exécution 5 NES, PNCPS à Kinshasa nd Advocacy à 1 enveloppe) ZR-DRC-MSP-273778-CW-RF Component 1: Strengthenin Demande d'offres B / Travaux de Réhabilitation g Surveillance and Laborato Single Stage - One - DTPM Petits trav En attente 2023-01-0 d’un (1) laboratoire national IDA / 64980 A posteriori Appel d'offres Open - National 900,000.00 0.00 2022-03-23 2022-03-28 2022-05-09 2022-06-08 2022-07-13 ry Capacity to Rapidly detec Envelope aux - (Processus d'exécution 9 de diagnostic vétérinaire: un t Outbreaks à 1 enveloppe) (1) à Kinshasa ; un (1) à Lub umbashi et un (1) à Goma ZR-DRC-MSP-273794-CW-RF Component 2: Strengthenin Q / Travaux de désamiantag g Emergency Planning and Single Stage - One Autre (avec cham En attente 2022-06-1 e dans le cadre de la réhabili IDA / 64980 A posteriori Demande de prix Limited 300,000.00 0.00 2022-02-19 2022-04-16 Management Capacity to Ra Envelope p d'explication) d'exécution 5 tation du dépôt du Ministère pidly respond to Outbreaks de la Santé à Kinshasa ZR-DRC-MSP-200130-CW-RF B / Construction/ Réhabilitati Component 1: Strengthenin on d’un (1) laboratoire natio g Surveillance and Laborato Single Stage - One 3,000,000.0 2022-04-3 nal de diagnostic vétérinaire IDA / D5160 A posteriori Appel d'offres Open - National 0.00 Annulé 2021-07-12 2021-07-17 2021-08-28 2021-09-27 2021-11-01 ry Capacity to Rapidly detec Envelope 0 0 de niveau 1 à Kinshasa ; de t t Outbreaks rois (3) laboratoires vétérina ires à Lubumbashi, Goma, et Bunia ZR-DRC-MSP-200133-CW-RF B / Réhabilitation des locaux pour abriter les centres médi Component 1: Strengthenin caux des Postes d’inspection g Surveillance and Laborato Single Stage - One 2022-05-0 Frontalières (PIF), des centre IDA / 64980 A posteriori Appel d'offres Open - National 900,000.00 0.00 Annulé 2021-07-19 2021-07-24 2021-09-04 2021-10-04 2021-11-08 ry Capacity to Rapidly detec Envelope 7 s des soins des animaux et d t Outbreaks e la quarantaine animale à : Kamako, Kipushi, la petite b arrière (Goma), Ruzizi 1 et 2 (Bukavu), Kavivira, Mahagi ZR-DRC-MSP-184475-CW-RF Component 1: Strengthenin B / Réhabilitation des laborat g Surveillance and Laborato Single Stage - One 9,000,000.0 2021-12-0 IDA / 64980 A posteriori Appel d'offres Open - National 0.00 Annulé 2021-02-19 2021-02-24 2021-04-07 2021-05-07 2021-06-11 oires provinciaux humains et ry Capacity to Rapidly detec Envelope 0 8 des cliniques de plantes t Outbreaks ZR-DRC-MSP-200120-CW-RF Q / Construction / Réhabilitat ion dans les sites sentinelles Component 1: Strengthenin des services de santé animal g Surveillance and Laborato Single Stage - One 2021-11-2 e afin d'assurer une meilleur IDA / 64980 A posteriori Demande de prix Limited 420,000.00 0.00 Annulé 2021-04-07 2021-06-02 ry Capacity to Rapidly detec Envelope 9 e couverture sanitaire des m t Outbreaks aladies zoonotiques dans qu atorze (14) sites sentinelles : Bikoro, Gemena, Buta, Monk oto, Idiofa, Popokabaka, Mw e ZR-DRC-MSP-184472-CW-RF Component 1: Strengthenin Q / Réhabiliter 15 locaux dev g Surveillance and Laborato Single Stage - One 2021-04-2 IDA / 64980 A posteriori Demande de prix Limited 110,000.00 0.00 Annulé 2020-09-01 2020-10-27 ant abriter les centres médic ry Capacity to Rapidly detec Envelope 5 aux aux 15 PoE désignés t Outbreaks ZR-DRC-MSP-184494-CW-RF Q / Construction dans les sit es sentilles 50 bureaux des s Component 1: Strengthenin ervices de santé animale afi g Surveillance and Laborato Single Stage - One 2021-05-0 n d'assurer une meilleure co IDA / D5160 A posteriori Demande de prix Limited 120,000.00 0.00 Annulé 2020-09-13 2020-11-08 ry Capacity to Rapidly detec Envelope 7 ouverture sanitaire des mala t Outbreaks dies zoonotiques Fourniture des mobiliers de bureau en faveur des Coordi nations Locales du PNMLS Ki kwit et Tshikapa) Page 1 Document nation ZR-DRC-MSP-232788-CW-RF al de passation d Component 1: Strengthenin Q / Sélection et Recrutement es marchés - Proc g Surveillance and Laborato Single Stage - One 2022-01-2 d'un consultant Firme charg IDA / 64980 A posteriori Demande de prix Open - National essus à une enve 300,000.00 0.00 Annulé 2021-05-31 2021-07-26 ry Capacity to Rapidly detec Envelope 2 é de la réhabilitation du dép loppe (DTPM ne p t Outbreaks ôt du Ministère de la Santé à rovenant pas de l Kinshasa a Banque) ZR-DRC-MSP-209278-CW-RF Component 1: Strengthenin Q / Réhabilitation d'un bâtim g Surveillance and Laborato Single Stage - One 2021-08-3 ent devant abriter les équipe IDA / 64980 A posteriori Demande de prix Limited 100,000.00 0.00 Annulé 2021-01-06 2021-03-03 ry Capacity to Rapidly detec Envelope 0 ments du laboratoire nationa t Outbreaks l de contrôle qualité des mé dicaments LNCQ LAPHAKI. ZR-DRC-MSP-184496-CW-RF Component 1: Strengthenin Single Stage - One 2021-10-0 Q / Construction d'un bâtime IDA / 64980 g Surveillance and Laborato A posteriori Demande de prix Limited 200,000.00 0.00 Annulé 2021-02-15 2021-04-12 Envelope 9 nt abritant le siège de CDC ry Capacity to Rapidly detec t Outbreaks ZR-DRC-MSP-184495-CW-RF Q / Réhabiliter 80 bureaux d Component 1: Strengthenin es services de santé animale g Surveillance and Laborato Single Stage - One 2021-05-0 IDA / 64980 A posteriori Demande de prix Limited 150,000.00 0.00 Annulé 2020-09-09 2020-11-04 dans les sites sentilles afin d ry Capacity to Rapidly detec Envelope 3 'assurer une meilleure coouv t Outbreaks erture sanitaire des maladie s zoonotiques ZR-DRC-MSP-200137-CW-RF Component 1: Strengthenin B-2 / Réhabiliter 2 modules d g Surveillance and Laborato Single Stage - One Autre (avec cham 1,600,000.0 En cours d' 2023-07-2 u Laboratoire National de Co IDA / D5160 A posteriori Appel d'offres Open - National 0.00 2023-01-16 2023-01-23 2023-01-17 2023-01-28 2023-02-06 2023-02-21 2023-03-24 ry Capacity to Rapidly detec Envelope p d'explication) 0 exécution 2 ntrôle Qualité (LNCQ/ LAPHA t Outbreaks KI) (Microbiologie et Disposit ifs médicaux à Kinshasa). ZR-DRC-MSP-335508-CW-RF Component 4: Institutional B / Réhabilitation / Construct Capacity Building, Project M Single Stage - One Autre (avec cham 1,000,000.0 En cours d' 2024-03-2 IDA / D5160 A posteriori Appel d'offres Open - National 0.00 2023-01-16 2023-01-24 2023-01-17 2023-01-28 2023-03-03 2023-03-18 2023-04-02 ion des Bureaux Siège de l' anagement, Coordination a Envelope p d'explication) 0 exécution 7 UG PDSS à Kinshasa. nd Advocacy ZR-DRC-MSP-339930-CW-DI R / Recrutement par ED de l a firme INOVIE AFRICA Médic Component 1: Strengthenin al Biology Laboratoires pour g Surveillance and Laborato Passation de mar Direct - Internation Autre (avec cham 2,400,000.0 En cours d' 2023-10-1 Réhabilitation, Aménagemen IDA / D5160 A posteriori 0.00 2023-02-28 2023-02-07 2023-03-05 2023-02-20 2023-04-19 ry Capacity to Rapidly detec ché de gré à gré al p d'explication) 0 exécution 6 t, Equipements Médicaux, dé t Outbreaks ploiement de Système tech nique du Personnel pour les 5 Laboratoires des HGR de l a Province du Kwilu en RDC ZR-DRC-MSP-200125-CW-RF B / Construction / Réhabilitat ion des laboratoires provinci Component 1: Strengthenin aux de santé humaine à : Kis g Surveillance and Laborato Open - Internation Single Stage - One 16,500,000. 2022-04-3 IDA / 64980 A priori Appel d'offres 0.00 Annulé 2021-07-12 2021-07-17 2021-08-28 2021-09-27 2021-11-01 angani, Kananga, Mbuji mayi ry Capacity to Rapidly detec al Envelope 00 0 , Bandundu ville et Mbanda t Outbreaks ka ; et des laboratoires des hôpitaux provinciaux à : Kin du, Bukavu, Boende. GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualificatio Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission Description Component Review Type Method and Recommendatio Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus n Documents ation Report ent / Justification Notice / Invitation s Issued / Opening / Minutes n for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ZR-DRC-MSP-117864-GO-RF Component 1: Strengthenin Open - Internation Single Stage - One B / Acquisition de réactifs et / g Surveillance and Laborato A priori Appel d'offres 5,000,000.00 0.00 Annulé 2019-08-27 2019-09-01 2019-10-13 2019-11-12 2019-12-17 2020-06-14 al Envelope de consommables de laborat ry Capacity to Rapidly detec oire t Outbreaks ZR-DRC-MSP-117875-GO-RF Component 1: Strengthenin Open - Internation Single Stage - One B / Acquisition de laboratoire / g Surveillance and Laborato A priori Appel d'offres 1,500,000.00 0.00 Annulé 2019-08-12 2019-08-17 2019-09-28 2019-10-28 2019-12-02 2020-05-30 al Envelope s mobiles pour le compte du ry Capacity to Rapidly detec projet REDISSE t Outbreaks ZR-DRC-MSP-117878-GO-RF Component 4: Institutional B / Acquisition de chaîne de f Capacity Building, Project M Open - Internation Single Stage - One roid (solaire) et matériels de / A priori Appel d'offres 1,500,000.00 0.00 Annulé 2019-07-29 2019-08-03 2019-09-14 2019-10-14 2019-11-18 2020-05-16 anagement, Coordination a al Envelope prélèvement pour le renforc nd Advocacy ement des unités mobile de santé animale ZR-DRC-MSP-184396-GO-RF Component 1: Strengthenin B / Fourniture d’équipement g Surveillance and Laborato Open - Internation Single Stage - One IDA / D5160 A priori Appel d'offres 6,000,000.00 0.00 Annulé 2021-12-17 2021-12-22 2022-02-02 2022-03-04 2022-04-08 2022-10-05 et matériels de laboratoire p ry Capacity to Rapidly detec al Envelope our la santé animale et hum t Outbreaks aine ZR-DRC-MSP-184407-GO-RF Component 1: Strengthenin Single Stage - One B / Acquisitions de laboratoir IDA / D5160 g Surveillance and Laborato A posteriori Appel d'offres Open - National 1,500,000.00 0.00 Annulé 2021-03-19 2021-03-24 2021-05-05 2021-06-04 2021-07-09 2022-01-05 Envelope es mobiles ry Capacity to Rapidly detec t Outbreaks ZR-DRC-MSP-184409-GO-RF Q / Acquisition d’équipement de transmission (postes radi Component 1: Strengthenin o émetteur /récepteur et ant g Surveillance and Laborato Single Stage - One IDA / D5160 A posteriori Demande de prix Limited 500,000.00 0.00 Annulé 2021-10-03 2021-11-28 2022-05-27 ennes, Talkies Walkies), kits ry Capacity to Rapidly detec Envelope de production d’énergie sola t Outbreaks ire, équipement intervention (dosimètre, débitmètre, expl osimètre) ZR-DRC-MSP-184412-GO-RF Component 1: Strengthenin Q / Acquisition des matériels g Surveillance and Laborato Single Stage - One IDA / D5160 A posteriori Demande de prix Limited 500,000.00 0.00 Annulé 2021-10-03 2021-11-28 2022-05-27 de connexion internet en fav ry Capacity to Rapidly detec Envelope eur du Projet (V-SAT et conn t Outbreaks exes) ZR-DRC-MSP-184414-GO-RF Component 1: Strengthenin Q / Achat de moyens de com g Surveillance and Laborato Single Stage - One munication pour la surveillan IDA / D5160 A posteriori Demande de prix Limited 350,000.00 0.00 Annulé 2021-10-03 2021-11-28 2022-05-27 ry Capacity to Rapidly detec Envelope ce au niveau central et provi t Outbreaks nciale (téléphone mobile et GPS) ZR-DRC-MSP-184417-GO-RF Component 1: Strengthenin Q / Acquisition d’équipement g Surveillance and Laborato Single Stage - One IDA / D5160 A posteriori Demande de prix Limited 200,000.00 0.00 Annulé 2021-10-03 2021-11-28 2022-05-27 de communication (Visioconf ry Capacity to Rapidly detec Envelope érence) et interprétation t Outbreaks ZR-DRC-MSP-184421-GO-RF Component 1: Strengthenin Single Stage - One Q / Acquisition d'un serveur IDA / 64980 g Surveillance and Laborato A posteriori Demande de prix Limited 15,000.00 0.00 Annulé 2020-08-04 2020-09-29 2021-03-28 Envelope pour le système de surveilla ry Capacity to Rapidly detec nce électronique t Outbreaks ZR-DRC-MSP-184436-GO-RF Component 1: Strengthenin Q / Acquisition en Kits inform g Surveillance and Laborato Single Stage - One IDA / D5160 A posteriori Demande de prix Limited 225,000.00 0.00 Annulé 2020-09-02 2020-10-28 2021-04-26 atiques et bureautiques les l ry Capacity to Rapidly detec Envelope aboratoires intégrés au rése t Outbreaks au ZR-DRC-MSP-184440-GO-RF Component 1: Strengthenin B / Acquisition d'équipement g Surveillance and Laborato Open - Internation Single Stage - One s des laboratoires intégrés d IDA / D5160 A priori Appel d'offres 2,700,000.00 0.00 Annulé 2020-08-18 2020-08-23 2020-10-04 2020-11-03 2020-12-08 2021-06-06 ry Capacity to Rapidly detec al Envelope u réseau en kits et intrants s t Outbreaks pécifiques de prélèvement d es échantillons ZR-DRC-MSP-184443-GO-RF Component 1: Strengthenin Q / Acquisition d'équipement g Surveillance and Laborato Single Stage - One s des laboratoires intégrés d IDA / D5160 A posteriori Demande de prix Limited 226,380.00 0.00 Annulé 2021-09-02 2021-10-28 2022-04-26 ry Capacity to Rapidly detec Envelope u réseau en matériels, kits e t Outbreaks t intrants spécifiques de stoc kage des échantillons ZR-DRC-MSP-184453-GO-RF Q / Création d'un site Web p Component 1: Strengthenin our renforcer la communicati g Surveillance and Laborato Single Stage - One IDA / 64980 A posteriori Demande de prix Limited 10,000.00 0.00 Annulé 2021-08-02 2021-09-27 2022-03-26 on institutionnelle (communi ry Capacity to Rapidly detec Envelope cation interne et communica t Outbreaks tion externe en créant un sit e Web) Page 2 ZR-DRC-MSP-184454-GO-RF Component 1: Strengthenin Q / Hébergement et gestion g Surveillance and Laborato Single Stage - One du Site WEB en Mettant à jo IDA / 64980 A posteriori Demande de prix Limited 36,000.00 0.00 Annulé 2021-08-02 2021-09-27 2022-03-26 ry Capacity to Rapidly detec Envelope ur périoiquement les inform t Outbreaks ations du PANSS par domain e de RSI ZR-DRC-MSP-184461-GO-RF Component 1: Strengthenin Q / Reprographie du Plan Str g Surveillance and Laborato Single Stage - One IDA / 64980 A posteriori Demande de prix Limited 20,000.00 0.00 Annulé 2020-09-02 2020-10-28 2021-04-26 atégique National Multisecto ry Capacity to Rapidly detec Envelope riel de communication des ri t Outbreaks sques ZR-DRC-MSP-184465-GO-RF Component 1: Strengthenin B / Acquisition des véhicules g Surveillance and Laborato Single Stage - One IDA / D5160 A posteriori Appel d'offres Open - National 800,000.00 0.00 Annulé 2020-08-18 2020-10-13 2021-04-11 de 16 véhicules de type 4x4 ry Capacity to Rapidly detec Envelope pour le compte du projet au t Outbreaks niveau provincial ZR-DRC-MSP-184466-GO-RF Component 1: Strengthenin Single Stage - One Q / Fourniture de cinq (5) mo IDA / D5160 g Surveillance and Laborato A posteriori Demande de prix Limited 32,500.00 0.00 Annulé 2020-08-24 2020-10-19 2021-04-17 Envelope tos de terrain pour le PF RSI ry Capacity to Rapidly detec t Outbreaks ZR-DRC-MSP-184467-GO-RF Component 1: Strengthenin Single Stage - One En attente d' Q / Fourniture d'équipement IDA / 64980 g Surveillance and Laborato A posteriori Demande de prix Limited 38,850.00 0.00 2020-08-15 2020-10-10 2021-04-08 Envelope exécution s, mobiliers et matériels pou ry Capacity to Rapidly detec r le PF RSI t Outbreaks ZR-DRC-MSP-118029-CS-IN Component 4: Institutional DV / Achat de moyens de co Capacity Building, Project M Single Stage - One mmunication pour la surveill / A posteriori Demande de prix Limited 350,000.00 0.00 Annulé 2019-08-17 2019-10-12 2020-04-09 anagement, Coordination a Envelope ance au niveau central et pr nd Advocacy ovinciale (téléphone mobile et GPS) ZR-DRC-MSP-199481-GO-RF Component 1: Strengthenin Q / Fourniture de logiciel de g Surveillance and Laborato Single Stage - One IDA / 64980 A posteriori Demande de prix Limited 30,000.00 0.00 Annulé 2020-12-26 2021-02-20 2021-08-19 suivi des effets indésirables ry Capacity to Rapidly detec Envelope des médicaments et intrants t Outbreaks (pharmaco vigilance). ZR-DRC-MSP-199494-GO-RF B / Fourniture de téléphones cellulaires et crédits de com Component 1: Strengthenin munication pour les province g Surveillance and Laborato Single Stage - One En attente d' s et les zones de santé cible IDA / 64980 A priori Appel d'offres Open - National 2,625,000.00 0.00 2021-01-05 2021-01-10 2021-02-21 2021-03-23 2021-04-27 2021-10-24 ry Capacity to Rapidly detec Envelope exécution s, d’équipements de commu t Outbreaks nication (Visioconférence) et interprétation pour les trois ( 3) secteurs au niveau centra l, de moyens de communicat ion ZR-DRC-MSP-209269-GO-RF Component 1: Strengthenin B / Fourniture de médicame g Surveillance and Laborato Single Stage - One En attente d' IDA / 64980 A posteriori Appel d'offres Open - National 1,800,000.00 0.00 2021-01-11 2021-01-16 2021-02-27 2021-03-29 2021-05-03 2021-10-30 nts génériques et vaccins da ry Capacity to Rapidly detec Envelope exécution ns la santé animale t Outbreaks ZR-DRC-MSP-209274-GO-RF Component 1: Strengthenin Single Stage - One B / Fourniture de réactifs et IDA / 64980 g Surveillance and Laborato A priori Appel d'offres Open - National 2,400,000.00 0.00 Annulé 2021-10-19 2021-10-24 2021-12-05 2022-01-04 2022-02-08 2022-08-07 Envelope consommables de laboratoir ry Capacity to Rapidly detec e. t Outbreaks ZR-DRC-MSP-199826-GO-RF Component 1: Strengthenin Q / Fourniture des tablettes g Surveillance and Laborato Single Stage - One IDA / D5160 A posteriori Demande de prix Limited 80,000.00 0.00 Annulé 2020-12-28 2021-02-22 2021-08-21 pour les points d'entrée et le ry Capacity to Rapidly detec Envelope s zones de santé cibles. t Outbreaks ZR-DRC-MSP-199846-GO-RF Component 1: Strengthenin B / Fourniture d’ambulances g Surveillance and Laborato Single Stage - One IDA / 64980 A posteriori Appel d'offres Open - National 1,080,000.00 0.00 Annulé 2020-12-23 2020-12-28 2021-02-08 2021-03-10 2021-04-14 2021-10-11 médicalisées au niveau des ry Capacity to Rapidly detec Envelope dix-huit (18) points d'entrée. t Outbreaks ZR-DRC-MSP-199851-GO-RF Component 1: Strengthenin Q / Fourniture d'un serveur c g Surveillance and Laborato Single Stage - One entral avec un système d'int IDA / D5160 A posteriori Demande de prix Limited 200,000.00 0.00 Annulé 2020-12-28 2021-02-22 2021-08-21 ry Capacity to Rapidly detec Envelope er opérabilité et interconnec t Outbreaks tivité intra et intersectorielle ZR-DRC-MSP-117861-GO-RF Component 1: Strengthenin B / fourniture d'équipement g Surveillance and Laborato Open - Internation Single Stage - One / A priori Appel d'offres 6,000,000.00 0.00 Annulé 2019-08-20 2019-08-25 2019-10-06 2019-11-05 2019-12-10 2020-06-07 et matériels de laboratoire p ry Capacity to Rapidly detec al Envelope our la santé animale et hum t Outbreaks aine ZR-DRC-MSP-232300-GO-RF Component 1: Strengthenin Q / Fourniture de mobiliers, g Surveillance and Laborato Single Stage - One En attente d' matériels informatiques et él IDA / 64980 A posteriori Demande de prix Open - National 200,000.00 0.00 2021-06-06 2021-08-01 2022-01-28 ry Capacity to Rapidly detec Envelope exécution ectriques pour le dépôt du m t Outbreaks inistère de la santé réhabilit é ZR-DRC-MSP-251700-GO-RF Component 4: Institutional Single Stage - One Q / Acquisition des matériels IDA / D5160 Capacity Building, Project M A posteriori Demande de prix Limited 12,000.00 17,518.75 Signé 2021-10-04 2021-09-09 2021-11-29 2021-09-29 2022-05-28 Envelope informatique pour LAPHAKI anagement, Coordination a nd Advocacy ZR-DRC-MSP-256225-GO-RF Q / Acquisition en urgence d Component 1: Strengthenin es intrants et réactifs de lab g Surveillance and Laborato Single Stage - One oratoire en appui à la Direct IDA / 64980 A posteriori Demande de prix Limited 69,933.00 0.00 Annulé 2021-10-25 2021-12-20 2022-06-18 ry Capacity to Rapidly detec Envelope ion de Surveillance Epidémio t Outbreaks logique pour la riposte contr e l'épidémie de méningite à BANALIA ZR-DRC-MSP-257127-GO-DI R / Contractualisation par en Component 1: Strengthenin tente directe avec la firme P g Surveillance and Laborato Passation de mar HATKIN, pour l'acquisition en IDA / 64980 A posteriori Direct 93,746.80 0.00 Annulé 2021-10-13 2021-10-07 2021-10-18 2021-10-07 2021-11-22 2022-05-21 ry Capacity to Rapidly detec ché de gré à gré urgence des médicaments e t Outbreaks t consommables médicaux p our la riposte contre l'épidé mie de méningite à BANALIA ZR-DRC-MSP-259420-GO-RF Q / Acquisition de 8 motos, d Component 2: Strengthenin ont 4 motos de type DT 125, g Emergency Planning and Single Stage - One et 4 motos de type AG 100, IDA / 64980 A posteriori Demande de prix Limited 45,000.00 42,900.00 Signé 2021-11-16 2021-10-26 2022-01-11 2021-11-19 2022-07-10 Management Capacity to Ra Envelope et 8 casques de protection; pidly respond to Outbreaks et de 2 moteurs Hors-bord, d ont un de 25 CV et un autre de 40 CV, pour l'appui ZR-DRC-MSP-259009-GO-DI R / Contractualisation par en tente directe avec RADIOCO Component 1: Strengthenin M pour l'acquisition de six (6 g Surveillance and Laborato Passation de mar ) appareils radiophoniques, ( IDA / 64980 A posteriori Direct 15,000.00 13,560.00 Signé 2021-11-10 2021-10-21 2021-11-15 2021-10-22 2021-12-20 2021-11-04 2022-06-18 ry Capacity to Rapidly detec ché de gré à gré 6) batteries12 v/ 100 Ah, (6) t Outbreaks Panneau Solaire, et (6) Régu lateur pour l'appui à l'épidé mie de méningite dans la ZS Banalia, Province de la Tsho po Component 2: Strengthenin ZR-DRC-MSP-117868-GO-RF g Emergency Planning and Single Stage - One B / Acquisition d'ambulances IBRD / 90040 A priori Appel d'offres Open - National 2,000,000.00 0.00 Annulé 2019-07-30 2019-08-04 2019-09-15 2019-10-15 2019-11-19 2020-05-17 Management Capacity to Ra Envelope médicalisées pidly respond to Outbreaks ZR-DRC-MSP-272396-GO-RF B / Fourniture et livraison de Component 1: Strengthenin s réactifs et intrants spécifiq g Surveillance and Laborato Single Stage - One En cours d'e IDA / 64980 A posteriori Appel d'offres Open - National 450,000.00 0.00 2022-01-20 2022-06-02 2022-01-25 2022-03-08 2022-04-07 2022-05-12 2022-11-08 ues de détection des épidém ry Capacity to Rapidly detec Envelope xécution ies pour l'Institut National d t Outbreaks es Recherches Biologiques ( INRB) ZR-DRC-MSP-272399-GO-RF Component 1: Strengthenin Single Stage - One En attente d' Q / Acquisition des Fournitur IDA / 64980 g Surveillance and Laborato A posteriori Demande de prix Limited 12,000.00 0.00 2022-02-05 2022-04-02 2022-05-02 Envelope exécution es de bureau et consommab ry Capacity to Rapidly detec les informatiques t Outbreaks Page 3 ZR-DRC-MSP-272400-GO-RF Q / Fourniture matériels de Component 2: Strengthenin manutention pour le dépôt d g Emergency Planning and Single Stage - One En attente d' IDA / 64980 A posteriori Demande de prix Limited 100,000.00 0.00 2022-04-06 2022-06-01 2022-07-01 u Ministère de la santé réha Management Capacity to Ra Envelope exécution bilité / Hôpital général de réf pidly respond to Outbreaks érence de Kinshasa ( HGR) : élévateur, diable, balance, e tc ZR-DRC-MSP-272401-GO-RF Q / Fourniture et montage d Component 2: Strengthenin es mobiliers pour le dépôt d g Emergency Planning and Single Stage - One En attente d' IDA / 64980 A posteriori Demande de prix Limited 100,000.00 0.00 2022-04-06 2022-06-01 2022-07-01 u Ministère de la Santé réha Management Capacity to Ra Envelope exécution bilité / Hôpital Général de Ré pidly respond to Outbreaks férence de Kinshasa (Maman Yemo) ZR-DRC-MSP-272405-GO-RF Q / Fourniture et montage d es mobiliers de bureau pour Component 1: Strengthenin le Service National d'épidém g Surveillance and Laborato Single Stage - One En attente d' io-surveillance (SENES), le P IDA / D5160 A posteriori Demande de prix Limited 75,000.00 0.00 2022-02-06 2022-04-03 2022-05-03 ry Capacity to Rapidly detec Envelope exécution oint Focal National de Règle t Outbreaks mentation Sanitaire internati onal et pour le Programme National de Communication pour la Promotion de la Sant é ZR-DRC-MSP-256226-GO-RF Component 1: Strengthenin Q / Acquisition en urgence d g Surveillance and Laborato Single Stage - One es médicaments et consom IDA / 64980 A posteriori Demande de prix Limited 93,746.80 0.00 Annulé 2021-10-25 2021-12-20 2022-06-18 ry Capacity to Rapidly detec Envelope mables médicaux pour la rip t Outbreaks oste contre l’épidémie de m éningite à Banalia. ZR-DRC-MSP-273136-GO-RF Component 1: Strengthenin Q / Fourniture des matériels g Surveillance and Laborato Single Stage - One En attente d' IDA / D5160 A posteriori Demande de prix Limited 105,000.00 0.00 2022-04-30 2022-06-25 2022-07-25 pour le Système d'informatio ry Capacity to Rapidly detec Envelope exécution ns géographiques (SIG) , Em t Outbreaks a-I et Kobocollect ZR-DRC-MSP-273772-GO-RF Component 1: Strengthenin Q / Sélection d'un Transport g Surveillance and Laborato Single Stage - One En attente d' eur pour l'acheminement de IDA / D5160 A posteriori Demande de prix Limited 100,000.00 0.00 2022-04-04 2022-05-30 2023-05-25 ry Capacity to Rapidly detec Envelope exécution s bulletins épidémiologiques t Outbreaks Mensuels de surveillance de s maladies. ZR-DRC-MSP-199902-GO-DI R / Fourniture d'une centain e (100) motos de terrain pou Component 4: Institutional r le niveau central, provincia Capacity Building, Project M Passation de mar l et opérationnel : Cinq (5) p IDA / D5160 A posteriori Direct 650,000.00 0.00 Annulé 2021-01-11 2021-01-16 2021-02-20 2021-08-19 anagement, Coordination a ché de gré à gré our le Point Focal RSI, Sept ( nd Advocacy 7) motos pour les provinces, seize (16) motos pour les lab oratoires provinciaux, dix-hu it (18) motos pour les poi ZR-DRC-MSP-273790-GO-RF Component 1: Strengthenin B / Fourniture de plus de ce g Surveillance and Laborato Single Stage - One En attente d' nt quarante huit (148 ) moto IDA / 64980 A posteriori Appel d'offres Open - National 962,000.00 0.00 2022-04-04 2022-04-09 2022-05-21 2022-06-20 2022-07-25 2023-01-21 ry Capacity to Rapidly detec Envelope exécution s de terrain pour les laborato t Outbreaks ires provinciaux et pour les sites sentinelles ZR-DRC-MSP-117874-GO-RF Component 4: Institutional Single Stage - One B / Acquisition de 32 véhicul / Capacity Building, Project M A priori Appel d'offres Open - National 1,600,000.00 0.00 Annulé 2019-07-24 2019-07-29 2019-09-09 2019-10-09 2019-11-13 2020-05-11 Envelope es de type 4x4 pour le comp anagement, Coordination a te du projet nd Advocacy ZR-DRC-MSP-257127-GO-DI R-2 / Contractualisation par Component 1: Strengthenin entente directe avec la firme g Surveillance and Laborato Passation de mar En cours d'e IDA / 64980 A posteriori Direct 424,000.00 0.00 2022-03-31 2022-02-18 2022-04-05 2022-02-22 2022-05-10 2022-07-09 PHATKIN, pour acquisition en ry Capacity to Rapidly detec ché de gré à gré xécution urgence des medicaments E t Outbreaks ssentiels aux zones de santé de la Province de l'Equateur ZR-DRC-MSP-291310-GO-RF Q / Acquisition des 3 motos DT + 6casques, 1 véhicule 4 Component 2: Strengthenin x4, tenues chirurgical et autr g Emergency Planning and Single Stage - One En attente d' IDA / D5160 A posteriori Demande de prix Limited 120,000.00 0.00 2022-04-23 2022-05-17 2022-05-31 es petits matériels medicaux Management Capacity to Ra Envelope exécution et non medicaux Assurer la pidly respond to Outbreaks mise la Campagne de vaccin ation contre la maladie à vir us Ébola dans la ville de Mba ndaka avec INRB ZR-DRC-MSP-291314-GO-RF Q / Acquisitions des Mobilier s de bureau, matériels infor Component 1: Strengthenin matiques, Consommables inf g Surveillance and Laborato Single Stage - One En attente d' IDA / D5160 A posteriori Demande de prix Limited 70,000.00 0.00 2022-04-24 2022-06-19 2022-07-19 ormatiques, et autres matéri ry Capacity to Rapidly detec Envelope exécution els pour les Directions du MS t Outbreaks P qui appuient REDISSE IV SENES, DGLM, DSE, INRB, PN HF, DSN et DLS ZR-DRC-MSP-294451-GO-RF Component 1: Strengthenin Q / Acquisition des Mobiliers g Surveillance and Laborato Single Stage - One En cours d'e IDA / D5160 A posteriori Demande de prix Limited 300,000.00 0.00 2022-05-21 2022-06-14 2022-06-28 (armoires, tables, chaises, et ry Capacity to Rapidly detec Envelope xécution c pour équiper le Laboratoire t Outbreaks de Bunia ZR-DRC-MSP-294457-GO-RF Component 1: Strengthenin Q / Acquisition des matériels g Surveillance and Laborato Single Stage - One En cours d'e IDA / D5160 A posteriori Demande de prix Limited 300,000.00 0.00 2022-05-21 2022-06-14 2022-06-28 et outils informatiques pour l ry Capacity to Rapidly detec Envelope xécution e fonctionnement de Laborat t Outbreaks oire de BUNIA ZR-DRC-MSP-294462-GO-RF Q / Fourniture des matériels Component 1: Strengthenin pour le QGIS EMA-I et KOBO g Surveillance and Laborato Single Stage - One En attente d' COLECT pour la Surveillance IDA / D5160 A posteriori Demande de prix Limited 120,000.00 0.00 2022-05-21 2022-06-14 2022-06-28 ry Capacity to Rapidly detec Envelope exécution et Renforcement des capacit t Outbreaks és de laboratoire pour détec ter rapidement les épidémie s (SENES) ZR-DRC-MSP-298180-GO-RF Component 1: Strengthenin B / Acquisitions des Équipem g Surveillance and Laborato Open - Internation Single Stage - One En cours d'e IDA / D5160 A priori Appel d'offres 2,100,000.00 0.00 2022-06-13 2022-08-21 2022-06-18 2022-10-29 2022-07-02 2022-11-10 2022-07-09 2022-07-15 2022-09-13 ents et petits matériels pour ry Capacity to Rapidly detec al Envelope xécution le Laboratoire National de B t Outbreaks unia ZR-DRC-MSP-298181-GO-RF Component 1: Strengthenin B / . Acquisition des Réactifs g Surveillance and Laborato Open - Internation Single Stage - One En cours d'e IDA / D5160 A posteriori Appel d'offres 750,000.00 0.00 2022-06-13 2022-11-14 2022-06-18 2022-11-16 2022-07-02 2022-07-09 2022-07-15 2022-09-13 de laboratoire et divers Cons ry Capacity to Rapidly detec al Envelope xécution ommables de Laboratoire de t Outbreaks Bunia ZR-DRC-MSP-301448-GO-RF Component 2: Strengthenin B / Équiper deux (02) Modul g Emergency Planning and Open - Internation Single Stage - One En attente d' IDA / 64990 A priori Appel d'offres 2,000,000.00 0.00 2022-07-18 2022-07-23 2022-09-06 2022-09-20 2022-10-21 2023-04-19 es (laboratoires de LAPHAKI Management Capacity to Ra al Envelope exécution à Réhabiliter pidly respond to Outbreaks ZR-DRC-MSP-311160-GO-RF Component 1: Strengthenin Q / Acquisition du Logiciel de g Surveillance and Laborato Single Stage - One En cours d'e IDA / D5160 A posteriori Demande de prix Limited 40,000.00 0.00 2022-09-26 2022-10-23 2022-10-26 Laboratoire d'Information Ma ry Capacity to Rapidly detec Envelope xécution nagement System (LIMS) t Outbreaks ZR-DRC-MSP-315473-GO-RF B / Acquisition des réactifs e Component 1: Strengthenin t consommables médicaux p g Surveillance and Laborato Single Stage - One En attente d' IDA / D5160 A posteriori Appel d'offres Open - National 900,000.00 0.00 2022-09-30 2022-10-30 2022-11-04 2022-11-18 2022-12-07 2023-04-06 our les 02 laboratoires du Mi ry Capacity to Rapidly detec Envelope exécution nistère de l’Environnement d t Outbreaks ans les provinces de Kinshas a et du Haut-Katanga ZR-DRC-MSP-315477-GO-RF B / Acquisition des réactifs e Component 1: Strengthenin t consommables médicaux p g Surveillance and Laborato Open - Internation Single Stage - One En attente d' IDA / D5160 A priori Appel d'offres 2,000,000.00 0.00 2022-09-30 2022-11-14 2022-11-19 2022-12-03 2022-12-22 2023-06-20 our les 03 laboratoires vétéri ry Capacity to Rapidly detec al Envelope exécution naires des provinces du Nor t Outbreaks d-Kivu, du Haut-Katanga et d e Kinshasa Page 4 ZR-DRC-MSP-315479-GO-RF B / Acquisition des équipeme Component 1: Strengthenin nts et matériels médicaux p g Surveillance and Laborato Open - Internation Single Stage - One En attente d' IDA / D5160 A priori Appel d'offres 2,000,000.00 0.00 2022-09-30 2022-11-14 2022-11-19 2022-12-03 2022-12-22 2023-06-20 our les 02 laboratoires du Mi ry Capacity to Rapidly detec al Envelope exécution nistère de l’Environnement d t Outbreaks ans les provinces de Kinshas a et du Haut-Katanga ZR-DRC-MSP-273791-GO-RF Component 1: Strengthenin B / Fourniture de 10 véhicul g Surveillance and Laborato Single Stage - One es de type 4x4 dont 8 pour l IDA / 64980 A posteriori Appel d'offres Open - National 503,000.00 0.00 Annulé 2022-02-09 2022-02-14 2022-03-28 2022-04-27 2022-06-01 2022-09-29 ry Capacity to Rapidly detec Envelope es laboratoires provinciaux, t Outbreaks 1 pour l'UGP PDSS et 1 pour INRB ZR-DRC-MSP-320771-GO-RF Component 1: Strengthenin B / Fourniture et Livraison de g Surveillance and Laborato Single Stage - One En attente d' s véhicules de type 4x4 dont IDA / 64980 A posteriori Appel d'offres Open - National 503,000.00 0.00 2022-10-13 2022-10-15 2022-11-14 2022-11-20 2022-12-10 2023-06-08 ry Capacity to Rapidly detec Envelope exécution huit (8) pour les laboratoires t Outbreaks Provinciaux, 1 'un) pour l'UG P PDSS et 1 pour INRB ZR-DRC-MSP-295330-GO-RF Component 1: Strengthenin Q / Acquisition des Mobiliers, g Surveillance and Laborato Single Stage - One En attente d' matériels et outils informatiq IDA / D5160 A posteriori Demande de prix Limited 220,000.00 0.00 2022-05-24 2022-06-25 2022-09-23 ry Capacity to Rapidly detec Envelope exécution ues et autres matériels pour t Outbreaks REDISSE IV / UG PDSS ZR-DRC-MSP-318367-GO-RF Component 1: Strengthenin B / Fourniture et livraison de g Surveillance and Laborato Open - Internation Single Stage - One s véhicules de type 4x4 pour IDA / D5160 A priori Appel d'offres 2,200,000.00 0.00 Annulé 2022-10-05 2022-11-19 2022-11-20 2022-12-04 2023-01-15 2023-07-14 ry Capacity to Rapidly detec al Envelope les ambulances médicalisée t Outbreaks s pour les 18 points d'entrée s PoE ZR-DRC-MSP-324817-GO-RF Component 1: Strengthenin B / Acquisition des Véhicules g Surveillance and Laborato Open - Internation Single Stage - One En cours d'e de Type 4x4 pour les Ambul IDA / D5160 A priori Appel d'offres 2,200,000.00 0.00 2022-11-16 2022-12-31 2023-01-01 2023-01-15 2023-02-26 2023-08-25 ry Capacity to Rapidly detec al Envelope xécution ances Médicalisées pour les t Outbreaks 18 Points d'entées (PoE) ZR-DRC-MSP-117880-GO-RF Component 4: Institutional Single Stage - One B / Acquisition de mobiliers e IBRD / 90040 Capacity Building, Project M A posteriori Appel d'offres Open - National 1,200,000.00 0.00 Annulé 2019-07-25 2019-07-30 2019-09-10 2019-10-10 2019-11-14 2020-05-12 Envelope t équipement informatiques anagement, Coordination a nd Advocacy ZR-DRC-MSP-117871-GO-RF Component 1: Strengthenin B / fourniture de produits de g Surveillance and Laborato Single Stage - One / A priori Appel d'offres Open - National 2,000,000.00 0.00 Annulé 2019-07-25 2019-07-30 2019-09-10 2019-10-10 2019-11-14 2020-05-12 base et consommables pour ry Capacity to Rapidly detec Envelope le laboratoire de clinique vét t Outbreaks érinaire ZR-DRC-MSP-184434-GO-RF B / Acquisition d'équipement Component 1: Strengthenin s pour les laboratoires intégr g Surveillance and Laborato Single Stage - One IDA / D5160 A posteriori Appel d'offres Open - National 1,125,000.00 0.00 Annulé 2020-08-18 2020-08-23 2020-10-04 2020-11-03 2020-12-08 2021-06-06 és du réseau en matériels po ry Capacity to Rapidly detec Envelope ur la détection des maladies t Outbreaks prioritaires dans les secteurs humain et animal ZR-DRC-MSP-184403-GO-RF Component 1: Strengthenin Open - Internation Single Stage - One B / Achat de réactifs et de co IDA / 64980 g Surveillance and Laborato A priori Appel d'offres 5,000,000.00 0.00 Annulé 2021-12-17 2021-12-22 2022-02-02 2022-03-04 2022-04-08 2022-10-05 al Envelope nsommables de laboratoire ry Capacity to Rapidly detec t Outbreaks ZR-DRC-MSP-199501-GO-RF Component 1: Strengthenin Single Stage - One B / Fourniture d'intrants spéc IDA / 64980 g Surveillance and Laborato A posteriori Appel d'offres Open - National 1,800,000.00 0.00 Annulé 2021-01-19 2021-01-24 2021-03-07 2021-04-06 2021-05-11 2021-11-07 Envelope ifiques pour la détection des ry Capacity to Rapidly detec épidémies t Outbreaks ZR-DRC-MSP-272392-GO-RF Component 2: Strengthenin B / Fourniture d’ambulances g Emergency Planning and Open - Internation Single Stage - One IDA / 64990 A priori Appel d'offres 2,000,000.00 0.00 Annulé 2022-01-13 2022-02-03 2022-01-18 2022-03-01 2022-03-31 2022-05-05 2022-11-01 médicalisées de type 4x4 au Management Capacity to Ra al Envelope niveau des dix-huit (18) poin pidly respond to Outbreaks ts d'entrée. ZR-DRC-MSP-199841-GO-RF B / Fourniture en équipemen ts médicaux pour le diagnost Component 1: Strengthenin ic et la prise en charge (sant g Surveillance and Laborato Open - Internation Single Stage - One é publique et animale) pour l IDA / D5160 A priori Appel d'offres 9,686,000.00 0.00 Annulé 2021-12-23 2021-12-28 2022-02-08 2022-03-10 2022-04-14 2022-10-11 ry Capacity to Rapidly detec al Envelope es 18 PoE désignés, d’équip t Outbreaks ements diversément spécifiq ues, de matériels divers pou r les sites sentinelles (Minila b, Centrifugeuse, Microscope ,etc ZR-DRC-MSP-199497-GO-RF Component 1: Strengthenin B / Fourniture en matériels d g Surveillance and Laborato Single Stage - One 'assainissement de base (po IDA / D5160 A posteriori Appel d'offres Open - National 540,000.00 0.00 Annulé 2021-01-05 2021-01-10 2021-02-21 2021-03-23 2021-04-27 2021-10-24 ry Capacity to Rapidly detec Envelope ubelles, décharges, latrines, t Outbreaks points d'eau) pour les 18 Po E désignés. ZR-DRC-MSP-199901-GO-RF B / Fourniture d'un minibus e t de onze (11) véhicules de t Component 4: Institutional ype 4x4 pour toutes les parti Capacity Building, Project M Single Stage - One es prenantes au Projet au ni IDA / D5160 A posteriori Appel d'offres Open - National 610,000.00 0.00 Annulé 2021-01-15 2021-01-20 2021-03-03 2021-04-02 2021-05-07 2021-11-03 anagement, Coordination a Envelope veau central : PDSS (3), DGL nd Advocacy M (1), DLS (1), PNHF (1), PF RSI (1), MiniPE (1), MiniENV ( 1), Laboratoire vétérinaire c entral de Kinshasa (1), comi ZR-DRC-MSP-273785-GO-RF Component 1: Strengthenin B / Fourniture des équipeme g Surveillance and Laborato Single Stage - One IDA / 64980 A posteriori Appel d'offres Open - National 1,250,000.00 0.00 Annulé 2022-05-11 2022-05-16 2022-06-27 2022-07-27 2022-08-31 2023-02-27 nts pour les cinq (5) laborato ry Capacity to Rapidly detec Envelope ires pour les sites de LAPHA t Outbreaks KI réhabilité ZR-DRC-MSP-272394-GO-RF B / Fourniture et installations des équipements des laborat Component 2: Strengthenin oires pour le diagnostic biolo g Emergency Planning and Open - Internation Single Stage - One IDA / 64990 A priori Appel d'offres 5,000,000.00 0.00 Annulé 2022-07-15 2022-07-20 2022-08-31 2022-09-30 2022-11-04 2023-05-03 gique des maladies, y compr Management Capacity to Ra al Envelope is les maladies prioritaires p pidly respond to Outbreaks our la prise en charge (santé publique et animale) pour le s 9 laboratoires des Province s ZR-DRC-MSP-273770-GO-RF Component 2: Strengthenin B / Fournitures des hors Bor g Emergency Planning and Single Stage - One d de 25 CV, Téléphones Mobi IDA / 64980 A posteriori Appel d'offres Open - National 372,500.00 0.00 Annulé 2022-04-11 2022-04-16 2022-05-28 2022-06-27 2022-08-01 2022-10-30 Management Capacity to Ra Envelope les Satellitaires pour les équi pidly respond to Outbreaks pes d'intervention rapides e n moyens logistiques ZR-DRC-MSP-315466-GO-RF B / Acquisition des équipeme Component 1: Strengthenin nts et matériels médicaux p g Surveillance and Laborato Open - Internation Single Stage - One IDA / D5160 A priori Appel d'offres 4,500,000.00 0.00 Annulé 2022-10-03 2022-11-17 2022-12-01 2022-12-15 2023-01-05 2023-05-05 our les 3 laboratoires vétérin ry Capacity to Rapidly detec al Envelope aires des provinces du Nord- t Outbreaks Kivu, du Haut-Katanga et de Kinshasa ZR-DRC-MSP-117877-GO-RF Component 4: Institutional Single Stage - One B / Acquisition de matériels r / Capacity Building, Project M A priori Appel d'offres Open - National 1,500,000.00 0.00 Annulé 2019-07-30 2019-08-04 2019-09-15 2019-10-15 2019-11-19 2020-05-17 Envelope oulants divers ( vélos, canot anagement, Coordination a rapides, moto) nd Advocacy ZR-DRC-MSP-273135-GO-RF B / Acquisition d’équipement s de communication pour les Component 1: Strengthenin trois (3) secteurs pour la sur g Surveillance and Laborato Single Stage - One IDA / 64980 A posteriori Appel d'offres Open - National 500,000.00 0.00 Annulé 2022-04-18 2022-04-23 2022-06-04 2022-07-04 2022-08-08 2022-11-06 veillance ( postes radio émet ry Capacity to Rapidly detec Envelope teur/récepteur et antennes, t Outbreaks Talkies Walkies) kits de prod uction d'énergie solaire, équi pement intervention pour 18 PoE. ZR-DRC-MSP-272395-GO-RF B / Fourniture et installation Component 1: Strengthenin des équipements de laborat g Surveillance and Laborato Single Stage - One oire de Santé Publique de B IDA / 64980 A posteriori Appel d'offres Open - National 1,000,000.00 0.00 Annulé 2022-03-22 2022-03-27 2022-05-08 2022-06-07 2022-07-12 2023-01-08 ry Capacity to Rapidly detec Envelope unia pour le diagnostic biolo t Outbreaks gique des maladies, y compr is les maladies prioritaires p our la prise en charge. Page 5 ZR-DRC-MSP-118023-GO-RF Component 4: Institutional Q / Achat d'équipement (kits Capacity Building, Project M Single Stage - One / A posteriori Demande de prix Open - National 350,000.00 0.00 Annulé 2019-08-26 2019-10-21 2020-04-18 de protection individuelle) p anagement, Coordination a Envelope our Biosécurité et bio sureté nd Advocacy ZR-DRC-MSP-184459-GO-RF Component 1: Strengthenin Q / Regrographie des directi g Surveillance and Laborato Single Stage - One ves et normes de fonctionne IDA / 64980 A posteriori Demande de prix Limited 57,600.00 0.00 Annulé 2021-07-15 2021-09-09 2022-03-08 ry Capacity to Rapidly detec Envelope ment du reseau de laboratoi t Outbreaks res et des textes légaux ZR-DRC-MSP-184418-GO-RF Q / Production et édition des Component 1: Strengthenin outils de gestion pour les ce g Surveillance and Laborato Single Stage - One IDA / D5160 A posteriori Demande de prix Limited 100,000.00 0.00 Annulé 2021-10-03 2021-11-28 2022-05-27 ntres de surveillance animal ry Capacity to Rapidly detec Envelope e et environnementale en (r t Outbreaks egistres et notification, fiche s de notification) ZR-DRC-MSP-184419-GO-RF Component 1: Strengthenin Single Stage - One Q / Acquisition de logiciel de IDA / 64980 g Surveillance and Laborato A posteriori Demande de prix Limited 30,000.00 0.00 Annulé 2021-09-16 2021-11-11 2022-05-10 Envelope suivi de gestion des médica ry Capacity to Rapidly detec ments et intrants t Outbreaks ZR-DRC-MSP-184463-GO-RF Component 1: Strengthenin Q / Production des bulletins g Surveillance and Laborato Single Stage - One épidémiologiques mensuels IDA / 64980 A posteriori Demande de prix Limited 42,000.00 0.00 Annulé 2020-09-05 2020-10-31 2021-04-29 ry Capacity to Rapidly detec Envelope de surveillance des maladies t Outbreaks ( animales et humaines) ZR-DRC-MSP-184464-GO-RF Component 1: Strengthenin Q / Reproduction des suppor g Surveillance and Laborato Single Stage - One ts existants de communicati IDA / 64980 A posteriori Demande de prix Limited 42,000.00 0.00 Annulé 2020-08-08 2020-10-03 2021-04-01 ry Capacity to Rapidly detec Envelope ons (la boite à images, les a t Outbreaks utocollants, les affiches) sur les relais additionnels ZR-DRC-MSP-184462-GO-RF Component 1: Strengthenin Q / Reprographie des modul g Surveillance and Laborato Single Stage - One IDA / 64980 A posteriori Demande de prix Limited 10,000.00 0.00 Annulé 2020-11-03 2020-12-29 2021-06-27 es et guides de formation en ry Capacity to Rapidly detec Envelope communication multisectorie t Outbreaks ls sur les risques ZR-DRC-MSP-199507-GO-RF Q / Fourniture de chaîne de f Component 1: Strengthenin roid (solaire) et matériel de g Surveillance and Laborato Single Stage - One prélèvement pour le renforc IDA / D5160 A posteriori Demande de prix Open - National 320,000.00 0.00 Annulé 2020-12-27 2021-02-14 2021-02-28 ry Capacity to Rapidly detec Envelope ement de quatorze (14) sites t Outbreaks sentinelles des services de s anté animale, et dix-huit (18 ) PoE de santé humaine. ZR-DRC-MSP-199855-GO-RF Component 2: Strengthenin Q / Fourniture de kits de pro g Emergency Planning and Single Stage - One duction d’énergie solaire, éq IDA / D5160 A posteriori Demande de prix Limited 250,000.00 0.00 Annulé 2021-10-20 2021-12-15 2022-06-13 Management Capacity to Ra Envelope uipements intervention (dosi pidly respond to Outbreaks mètre, débitmètre, explosim ètre). ZR-DRC-MSP-117894-GO-RF Component 1: Strengthenin Q / Acquisition des matériels g Surveillance and Laborato Single Stage - One / A posteriori Demande de prix Limited 500,000.00 0.00 Annulé 2019-08-11 2019-10-06 2020-04-03 de connexion internet en fav ry Capacity to Rapidly detec Envelope eur du Projet (V-SAT et conn t Outbreaks exes) ZR-DRC-MSP-184455-GO-RF Component 1: Strengthenin Single Stage - One Q / Connexion Internet aux l IDA / 64980 g Surveillance and Laborato A posteriori Demande de prix Limited 100,800.00 0.00 Annulé 2020-08-15 2020-10-10 2021-04-08 Envelope aboratoires intégrés du rése ry Capacity to Rapidly detec au multisectoriel t Outbreaks ZR-DRC-MSP-273082-GO-RF Component 2: Strengthenin Q / Fourniture de trois (3) ho g Emergency Planning and Single Stage - One rs bords de 25CV et pirogues IDA / D5160 A posteriori Demande de prix Limited 13,500.00 0.00 Annulé 2022-04-23 2022-06-18 2022-12-15 Management Capacity to Ra Envelope pour les sites sentinelles de pidly respond to Outbreaks santé animale : Bikoro, Boen de, Mahagi ZR-DRC-MSP-318353-GO-RF Component 1: Strengthenin Q / Acquisition de deux (02) g Surveillance and Laborato Single Stage - One IDA / D5160 A posteriori Demande de prix Limited 120,000.00 0.00 Annulé 2022-10-03 2022-11-03 2023-03-03 véhicule de type 4x4 pour la ry Capacity to Rapidly detec Envelope mobilité du personnel UG PD t Outbreaks SS ZR-DRC-MSP-184445-GO-RF Component 1: Strengthenin Q / Acquisition d'équipement g Surveillance and Laborato Single Stage - One s des laboratoires intégrés d IDA / D5160 A posteriori Demande de prix Limited 270,000.00 0.00 Annulé 2021-09-02 2021-10-28 2022-04-26 ry Capacity to Rapidly detec Envelope u réseau en matériels/kits et t Outbreaks intrants spécifiques de trans port des échantillons ZR-DRC-MSP-184457-GO-RF Component 1: Strengthenin Single Stage - One Q / Acquisition de matériels r IDA / D5160 g Surveillance and Laborato A posteriori Demande de prix Limited 582,400.00 0.00 Annulé 2021-07-15 2021-09-09 2022-03-08 Envelope oulants spécialisés pour le C ry Capacity to Rapidly detec DC t Outbreaks ZR-DRC-MSP-184413-GO-RF Component 1: Strengthenin Q / Achat d’équipement (kits g Surveillance and Laborato Single Stage - One IDA / D5160 A posteriori Demande de prix Limited 350,000.00 0.00 Annulé 2021-10-03 2021-11-28 2022-05-27 de protection individuelle) p ry Capacity to Rapidly detec Envelope our Biosécurité et bio sureté t Outbreaks ZR-DRC-MSP-199484-GO-RF Q / Reproduction des bulleti ns épidémiologiques mensu Component 1: Strengthenin els de surveillance des mala g Surveillance and Laborato Single Stage - One dies (animales et humaines), IDA / D5160 A posteriori Demande de prix Limited 84,000.00 0.00 Annulé 2021-01-16 2021-03-13 2021-09-09 ry Capacity to Rapidly detec Envelope des supports existants de co t Outbreaks mmunications (la boite à im ages, les autocollants, les aff iches) sur les relais addition nels (secteur de l'enseignem ent, ZR-DRC-MSP-272398-GO-RF Component 1: Strengthenin Q / Fourniture et montage d g Surveillance and Laborato Single Stage - One u matériel informatique pour IDA / 64980 A posteriori Demande de prix Limited 15,000.00 0.00 Annulé 2022-03-15 2022-05-10 2022-06-09 ry Capacity to Rapidly detec Envelope le Point Focal National Règle t Outbreaks mentaire International (PFNR SI) ZR-DRC-MSP-118032-GO-RF Component 4: Institutional Q / Acquisition d'équipement Capacity Building, Project M Single Stage - One / A posteriori Demande de prix Open - National 200,000.00 0.00 Annulé 2019-09-15 2019-11-10 2020-05-08 de communication (Visioconf anagement, Coordination a Envelope érence) et interprétation nd Advocacy ZR-DRC-MSP-184451-GO-RF Component 1: Strengthenin Q / Acquisition de matériels g Surveillance and Laborato Single Stage - One et équipements de travail po IDA / 64980 A posteriori Demande de prix Limited 115,000.00 0.00 Annulé 2020-10-04 2020-11-29 2021-05-28 ry Capacity to Rapidly detec Envelope ur doter les bureaux de servi t Outbreaks ces de santé animale ZR-DRC-MSP-184456-GO-RF Component 1: Strengthenin Q / Services de transport des g Surveillance and Laborato Single Stage - One IDA / 64980 A posteriori Demande de prix Limited 504,000.00 0.00 Annulé 2021-07-19 2021-09-13 2022-03-12 échantillons des lieux de pré ry Capacity to Rapidly detec Envelope lèvements aux lieux d'analys t Outbreaks es ZR-DRC-MSP-199900-GO-RF Q / Fourniture de mobiliers, Component 4: Institutional matériels et biens pour le Bu Capacity Building, Project M Single Stage - One reau de la coordination du Pr IDA / D5160 A posteriori Demande de prix Limited 200,000.00 0.00 Annulé 2021-01-20 2021-03-17 2021-09-13 anagement, Coordination a Envelope ojet, les structures du minist nd Advocacy ère de la santé, du ministrèr e de pêche et élevage, et du ministère de l'environnemen t. ZR-DRC-MSP-199905-GO-RF Q / Fourniture des matériels Component 4: Institutional de connexion internet en fav Capacity Building, Project M Single Stage - One IDA / D5160 A posteriori Demande de prix Limited 300,000.00 0.00 Annulé 2020-12-28 2021-02-22 2021-08-21 eur des structures bénéficiai anagement, Coordination a Envelope res du Projet (Acquisition de nd Advocacy matériel, maintenance, et pa iement de l'abonnement Inte rnet). Page 6 ZR-DRC-MSP-199836-GO-RF Q / Production et édition des Component 1: Strengthenin outils de gestion pour les ce g Surveillance and Laborato Single Stage - One ntres de surveillance animal IDA / D5160 A posteriori Demande de prix Limited 100,000.00 0.00 Annulé 2021-02-02 2021-03-30 2021-09-26 ry Capacity to Rapidly detec Envelope e et environnementale (regis t Outbreaks tres de notification, fiches de notification) dans les zones des provinces cibles. ZR-DRC-MSP-199813-GO-RF Component 1: Strengthenin Q / Fourniture de kits et intra g Surveillance and Laborato Single Stage - One IDA / D5160 A posteriori Demande de prix Limited 270,000.00 0.00 Annulé 2020-12-27 2021-02-21 2021-08-20 nts spécifiques de transport ry Capacity to Rapidly detec Envelope des échantillons. t Outbreaks ZR-DRC-MSP-117890-GO-RF Q / Acquisition d'équipement de transmission (postes radi o émetteur /récepteur et ant Component 3: Public Healt Single Stage - One / A posteriori Demande de prix Limited 500,000.00 0.00 Annulé 2019-09-14 2019-11-09 2020-05-07 ennes, Talkies Walkies), kits h Workforce Development Envelope de production d'énergie sola ire, équipement intervention (dosimètre, débitmètre, expl osimètre,) ZR-DRC-MSP-184427-GO-RF Component 1: Strengthenin Single Stage - One Q / Acquisition des tablettes IDA / D5160 g Surveillance and Laborato A posteriori Demande de prix Limited 80,000.00 0.00 Annulé 2021-09-02 2021-10-28 2022-04-26 Envelope pour les points d'entrée ry Capacity to Rapidly detec t Outbreaks ZR-DRC-MSP-272397-GO-RF Component 1: Strengthenin Q / Fourniture et montage d g Surveillance and Laborato Single Stage - One es mobiliers de bureau pour IDA / 64980 A posteriori Demande de prix Limited 16,600.00 0.00 Annulé 2022-03-06 2022-05-01 2022-05-31 ry Capacity to Rapidly detec Envelope le Point Focal National Règle t Outbreaks mentaire Sanitaire Internatio nal ( PFNRSI) ZR-DRC-MSP-184458-GO-RF Component 1: Strengthenin Q / Acquisition de matériel in g Surveillance and Laborato Single Stage - One IDA / D5160 A posteriori Demande de prix Limited 92,710.00 0.00 Annulé 2021-07-15 2021-09-09 2022-03-08 formatique et de communica ry Capacity to Rapidly detec Envelope tion pour les ministères sect t Outbreaks oriels ZR-DRC-MSP-272402-GO-RF Component 1: Strengthenin Q / Fourniture de matériels i g Surveillance and Laborato Single Stage - One IDA / 64980 A posteriori Demande de prix Limited 30,000.00 0.00 Annulé 2022-04-06 2022-06-01 2022-07-01 nformatiques pour le dépôt ry Capacity to Rapidly detec Envelope du Ministère de la santé réh t Outbreaks abilité / Maman Yemo ZR-DRC-MSP-184428-GO-RF Component 1: Strengthenin Q / Acquisition en équipeme g Surveillance and Laborato Single Stage - One nts médicaux pour le diagno IDA / 64980 A posteriori Demande de prix Limited 486,000.00 0.00 Annulé 2021-09-02 2021-10-28 2022-04-26 ry Capacity to Rapidly detec Envelope stic et la prise en charge (Sa t Outbreaks nté Publique et Animale) pou r les 18 PoE désignés ZR-DRC-MSP-184433-GO-RF Component 1: Strengthenin Q / Acquisition d'équipement g Surveillance and Laborato Single Stage - One IDA / D5160 A posteriori Demande de prix Limited 65,000.00 0.00 Annulé 2021-09-02 2021-10-28 2022-04-26 s en renforcement du labora ry Capacity to Rapidly detec Envelope toire national de contrôle qu t Outbreaks alité LAPHAKI ZR-DRC-MSP-184447-GO-RF Component 1: Strengthenin Q / Acquisition en équipeme g Surveillance and Laborato Single Stage - One nts aux laboratoires intégrés IDA / D5160 A posteriori Demande de prix Limited 168,000.00 0.00 Annulé 2021-09-02 2021-10-28 2022-04-26 ry Capacity to Rapidly detec Envelope au reseau en kits de prélève t Outbreaks ment, stockage et transport d'échantillons ZR-DRC-MSP-200161-GO-RF Q / Fourniture de dix-neuf (1 9) hors bords de 25CV pour l Component 4: Institutional es sites sentinelles de santé Capacity Building, Project M Single Stage - One IDA / 64980 A posteriori Demande de prix Limited 76,000.00 0.00 Annulé 2020-12-28 2021-02-22 2021-08-21 animale : Bikoro, Monkoto, M anagement, Coordination a Envelope angayi, Kalemie, Bunia, Tsha nd Advocacy ngalele et pour les équipes d 'intervention rapide dans les provinces de l'Equateur et d e la Tshuapa. ZR-DRC-MSP-273134-GO-RF Component 1: Strengthenin Q / Fourniture des tablettes g Surveillance and Laborato Single Stage - One IDA / D5160 A posteriori Demande de prix Limited 80,000.00 0.00 Annulé 2022-04-09 2022-06-04 2022-07-04 pour les points d'entrée et le ry Capacity to Rapidly detec Envelope s zones de santé cibles. t Outbreaks ZR-DRC-MSP-184460-GO-RF Component 1: Strengthenin Q / Reprographie du docume g Surveillance and Laborato Single Stage - One IDA / 64980 A posteriori Demande de prix Limited 20,000.00 0.00 Annulé 2020-10-05 2020-11-30 2021-05-29 nt projet de politique de com ry Capacity to Rapidly detec Envelope munication sur les risques t Outbreaks ZR-DRC-MSP-251729-GO-RF Component 1: Strengthenin Q / Acquisition des équipem g Surveillance and Laborato Single Stage - One IDA / 64980 A posteriori Demande de prix Limited 49,800.00 0.00 Annulé 2021-10-04 2021-11-03 2021-11-29 2022-05-28 ents du réseau intrant net a ry Capacity to Rapidly detec Envelope u LNCQ et l'abonnement inte t Outbreaks rnet de LAPHAKI ZR-DRC-MSP-327552-GO-DI R / Contractualisation en Ent Component 4: Institutional ente Directe avec la société Capacity Building, Project M Passation de mar En cours d'e ELITE NETWORKS pour l’Inst IDA / 64980 A posteriori Direct - National 15,000.00 0.00 2022-11-21 2022-11-21 2022-11-26 2022-12-09 2023-06-07 anagement, Coordination a ché de gré à gré xécution allation du Réseau informati nd Advocacy que local et extension Intern et dans le nouveau local abri tant le personnel UG PDSS ZR-DRC-MSP-315483-GO-DI Component 1: Strengthenin R / Contractualisation par ED g Surveillance and Laborato Passation de mar Direct - Internation IDA / 64980 A posteriori 731,000.00 0.00 Annulé 2022-09-27 2022-09-08 2022-10-02 2022-09-22 2022-10-26 2022-12-25 avec la firme CEPHEID pour ry Capacity to Rapidly detec ché de gré à gré al Fourniture d'équipements et t Outbreaks d'intrants GENEXEPRT ZR-DRC-MSP-330515-GO-RF Component 1: Strengthenin Q / Fourniture et livraison d' g Surveillance and Laborato Single Stage - One En attente d' IDA / D5160 A posteriori Demande de prix Limited 60,000.00 0.00 2022-12-27 2023-01-20 2023-04-20 un incinérateur pour le Labo ry Capacity to Rapidly detec Envelope exécution ratoire Provincial de Bunia t Outbreaks ZR-DRC-MSP-327504-GO-DI Component 1: Strengthenin R / Contractualisation par En g Surveillance and Laborato Passation de mar tente Directe avec la Firme IDA / 64980 A posteriori Direct - National 762,350.00 0.00 Annulé 2022-12-27 2022-12-22 2023-01-01 2023-01-14 2023-03-15 ry Capacity to Rapidly detec ché de gré à gré ESSOR EQUIPEMENTS pour F t Outbreaks ourniture d'équipements et d'intrants GENEXPERT ZR-DRC-MSP-339859-GO-RF Component 1: Strengthenin Q / Acquisition des Equipem g Surveillance and Laborato Single Stage - One En attente d' IDA / D5160 A posteriori Demande de prix Limited 300,000.00 0.00 2023-02-26 2023-04-23 2023-08-21 ents et Matériels du Laborat ry Capacity to Rapidly detec Envelope exécution oire de Bactériologie de l'INR t Outbreaks B ZR-DRC-MSP-339869-GO-RF Component 4: Institutional Q / Reproduire des bulletins Capacity Building, Project M Single Stage - One En attente d' IDA / D5160 A posteriori Demande de prix Limited 60,000.00 0.00 2023-02-27 2023-04-24 2023-08-22 d'Information REDISSE IV : In anagement, Coordination a Envelope exécution tervention et Témoignages d nd Advocacy es Bénéficiaires ZR-DRC-MSP-339500-GO-DI Component 1: Strengthenin R / Contractualisation par ED g Surveillance and Laborato Passation de mar En cours d'e avec ESSOR EQUIPEMENTS p IDA / 64980 A posteriori Direct - National 770,200.00 0.00 2023-01-31 2023-01-05 2023-02-05 2023-01-06 2023-02-18 2023-04-19 ry Capacity to Rapidly detec ché de gré à gré xécution our l'Acquisition des Machin t Outbreaks es GeneExpertes du Labo de Bunia ZR-DRC-MSP-341403-GO-RF Component 1: Strengthenin Q / Acquisition des véhicules g Surveillance and Laborato Single Stage - One En attente d' :1 Véhicule de Coordination IDA / D5160 A posteriori Demande de prix Limited 280,000.00 0.00 2023-02-18 2023-04-15 2023-07-14 ry Capacity to Rapidly detec Envelope exécution UG PDSS, 1 véhicule fermé p t Outbreaks our LAPHAKI, 2 véhicules ST AF UG PDSS ZR-DRC-MSP-339816-GO-DI R / Contractualisation par En Component 1: Strengthenin tente Directe avec PRODIMP g Surveillance and Laborato Passation de mar En cours d'e IDA / 64980 A posteriori Direct - National 260,000.00 0.00 2023-02-20 2023-02-07 2023-03-02 2023-02-15 2023-03-20 2023-05-19 EX pour Acquisition de 50 M ry Capacity to Rapidly detec ché de gré à gré xécution otos de terrain pour les EIR a t Outbreaks u niveau Provincial et Labo B unia Page 7 ZR-DRC-MSP-349954-GO-RF Component 4: Institutional Q / Production et Multiplicati Capacity Building, Project M Single Stage - One En attente d' IDA / D5160 A posteriori Demande de prix Limited 60,000.00 0.00 2023-03-25 2023-05-05 2023-07-04 on des supports de Commun anagement, Coordination a Envelope exécution ication des Projets de l'UG P nd Advocacy DSS ZR-DRC-MSP-351438-GO-RF Component 1: Strengthenin Q / Acquisition des Réactifs g Surveillance and Laborato Single Stage - One En attente d' IDA / D5160 A posteriori Demande de prix Limited 150,000.00 0.00 2023-04-10 2023-05-08 2023-11-04 et Consommables du Labora ry Capacity to Rapidly detec Envelope exécution toire Vétérinaire pour la Dét t Outbreaks ection des Epidémies ZR-DRC-MSP-315470-GO-RF B / Acquisition des réactifs e Component 1: Strengthenin t consommables médicaux p g Surveillance and Laborato Open - Internation Single Stage - One our les 7 laboratoires de san IDA / D5160 A priori Appel d'offres 5,250,000.00 0.00 Annulé 2022-10-31 2022-12-15 2022-12-20 2023-01-03 2023-01-22 2023-07-21 ry Capacity to Rapidly detec al Envelope té des provinces du Nord-Kiv t Outbreaks u, Kwilu, Kasaï Central, Kasaï Oriental, Equateur, Tshuapa et Tshopo ZR-DRC-MSP-315461-GO-RF B / Acquisition des équipeme Component 1: Strengthenin nts et matériels médicaux p g Surveillance and Laborato Open - Internation Single Stage - One our les 07 laboratoires de sa IDA / D5160 A priori Appel d'offres 15,000,000.00 0.00 Annulé 2022-10-04 2022-11-18 2022-12-02 2022-12-16 2023-01-06 2023-05-06 ry Capacity to Rapidly detec al Envelope nté publique des provinces: t Outbreaks Nord-Kivu, Kwilu, Kasaï Cent ral, Kasaï Oriental, Equateur, Tshuapa et Tshopo ZR-DRC-MSP-354051-GO-RF B / Assurer la reproduction d Component 1: Strengthenin es bulletins épidémiologique g Surveillance and Laborato Single Stage - One En attente d' s Mensuels de surveillance d IDA / D5160 A posteriori Appel d'offres Open - National 620,175.00 0.00 2023-04-10 2023-04-15 2023-05-05 2023-05-12 2023-06-16 2024-06-10 ry Capacity to Rapidly detec Envelope exécution es maladies (animales, de l'e t Outbreaks nvironnement et humaines) pour les structures d'Appui a u REDISSE IV ZR-DRC-MSP-354053-GO-RF B / Assurer la reproduction d Component 1: Strengthenin u bulletin trimestriel de la lut g Surveillance and Laborato Single Stage - One En attente d' IDA / D5160 A posteriori Appel d'offres Open - National 544,000.00 0.00 2023-04-10 2023-04-15 2023-05-05 2023-05-12 2023-06-16 2024-06-10 te contre la maladie et de la ry Capacity to Rapidly detec Envelope exécution sécurité sanitaire pour les st t Outbreaks ructures du MSP d'appui du REDISSE IV NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualificatio Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission Description Component Review Type Method and Recommendatio Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus n Documents ation Report ent / Justification Notice / Invitation s Issued / Opening / Minutes n for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ZR-DRC-MSP-200146-NC-DI R / "Accords cadre" (en contr Component 1: Strengthenin actualisation) d'avec les com g Surveillance and Laborato Passation de mar IDA / 64980 A posteriori Direct 100,000.00 0.00 Annulé 2021-01-11 2021-01-16 2021-02-20 2021-08-19 pagnies aériennes, agences ry Capacity to Rapidly detec ché de gré à gré de voyage, pour le transport t Outbreaks des échantillons (santé anim ale et santé humaine). ZR-DRC-MSP-200158-NC-RF Component 1: Strengthenin Single Stage - One En attente d' Q / Services spécialisés de tr IDA / 64980 g Surveillance and Laborato A posteriori Demande de prix Limited 250,000.00 0.00 2021-01-16 2021-03-13 2021-09-09 Envelope exécution ansport des échantillons. ry Capacity to Rapidly detec t Outbreaks ZR-DRC-MSP-261328-NC-DI R / Contractualisation par en tente avec l'UNICEF pour la Component 2: Strengthenin réduction des infections ass g Emergency Planning and Passation de mar IDA / 64980 A priori Direct 6,000,000.00 6,000,000.00 Signé 2021-11-30 2021-11-03 2021-12-05 2021-12-06 2022-01-09 2021-12-14 2022-07-08 ociées aux soins de santé et Management Capacity to Ra ché de gré à gré renforcement de la résilienc pidly respond to Outbreaks e communautaire contre la Maladie à Virus Ebola (MVE) et la COVID-19. ZR-DRC-MSP-272388-NC-RF B / Sélection d'un prestataire Component 1: Strengthenin pour la reproduction des bul g Surveillance and Laborato Single Stage - One En attente d' IDA / 64980 A posteriori Appel d'offres Open - National 500,000.00 0.00 2022-01-28 2022-02-02 2022-03-16 2022-04-15 2022-05-20 2023-05-20 letins épidémiologiques men ry Capacity to Rapidly detec Envelope exécution suels de surveillance des ma t Outbreaks ladies et outils SIMAR (anima les et humaines) ZR-DRC-MSP-272389-NC-RF B / Sélection d'un prestataire Component 1: Strengthenin pour la reproduction des out g Surveillance and Laborato Single Stage - One En attente d' IDA / 64980 A posteriori Appel d'offres Open - National 500,000.00 0.00 2022-01-28 2022-02-02 2022-03-16 2022-04-15 2022-05-20 2023-05-20 ils de SMIR (guides techniqu ry Capacity to Rapidly detec Envelope exécution es 3ème édition, Guide des t Outbreaks participants et de facilitateur s) et bulletins épidémiologiq ues ZR-DRC-MSP-272404-NC-DI R / Contractualisation avec l a Compagnie Transport Logi Component 1: Strengthenin stique Traiding TLC pour le t g Surveillance and Laborato Passation de mar En cours d'e IDA / 64980 A posteriori Direct 400,000.00 0.00 2022-03-30 2022-03-07 2022-04-04 2022-03-08 2022-05-09 2023-05-09 ransport des échantillons les ry Capacity to Rapidly detec ché de gré à gré xécution Provinces de: l'Equateur, Kas t Outbreaks ai Central, la Tshopo, le Kwil u, Nord et en Ituri vers Kin shasa pour les analyses ZR-DRC-MSP-295887-NC-RF Q / Location temporaire d'un Component 2: Strengthenin entrepôt pendant 6 mois po g Emergency Planning and Single Stage - One ur le stockage des biens et é IDA / 64980 A posteriori Demande de prix Limited 220,000.00 0.00 Annulé 2022-06-14 2022-06-30 2022-12-27 Management Capacity to Ra Envelope quipement du Ministère de l pidly respond to Outbreaks a Santé actuellement logés dans l’entrepôt de Mama Ye mo en phase de réhabilitatio n ZR-DRC-MSP-300941-NC-DI R / Contractualisation par ED avec UNFPA pour appui des Component 1: Strengthenin projets PDSS, PMNS, REDISS g Surveillance and Laborato Passation de mar IDA / D5160 A priori Direct 20,000,000.00 20,000,000.00 Signé 2022-06-27 2022-07-13 2022-07-02 2022-07-14 2022-08-06 2022-06-23 2023-02-02 E IV et COVID 19 pour atténu ry Capacity to Rapidly detec ché de gré à gré ation et réponses aux risque t Outbreaks s de EAS/HS liés à la mise en Œuvre dans les zones d'inter vention de ces projets ZR-DRC-MSP-305229-NC-DI R / Contractualisation par En tente directe avec CAMESE e Component 1: Strengthenin n vue d'assurer les services g Surveillance and Laborato Passation de mar En cours d'e de Réception, de stockage, d IDA / 64980 A posteriori Direct - National 49,751.00 0.00 2022-07-21 2022-05-27 2022-07-26 2022-07-26 2022-08-30 2023-02-26 ry Capacity to Rapidly detec ché de gré à gré xécution e colisage par formation sani t Outbreaks taire bénéficiaire et distributi on secondaires des medica ments vers 278 formations sanitaires dans les 18 ZS ZR-DRC-MSP-311157-NC-DI R / Contractualisation par ED avec SADCAS ( Southern Afri Component 1: Strengthenin can Development Communit g Surveillance and Laborato Passation de mar En cours d'e y Accréditation Services ) en IDA / D5160 A posteriori Direct - National 100,000.00 0.00 2022-09-05 2022-08-26 2022-09-10 2022-10-15 2023-04-13 ry Capacity to Rapidly detec ché de gré à gré xécution Faveur du Laboratoire Natio t Outbreaks nal de Contrôle Qualité - LAP HAKI à l'Accréditation ISO/IE C 17025:2017 de l'Unité d'A nalyse Physicochimique ZR-DRC-MSP-311158-NC-DI R / Contractualisation par ED HI-TECH détection System ( Component 1: Strengthenin HI-TECH) (HTDS) du Labo N g Surveillance and Laborato Passation de mar En cours d'e ational de Contrôle Qualité - IDA / D5160 A posteriori Direct - National 25,000.00 0.00 2022-09-05 2022-08-26 2022-09-10 2022-10-15 2023-04-13 ry Capacity to Rapidly detec ché de gré à gré xécution LAPHAKI pour qualification O t Outbreaks pérationnelle d'équipements en vue d'Accréditation ISO/IE C 17025 :2017 de l'unité d'a nalyse Physicochimique Page 8 ZR-DRC-MSP-318362-NC-DI R / Contractualisation par En tente Directe avec la Firme Component 1: Strengthenin BOLLORE pour Location tem g Surveillance and Laborato Passation de mar poraire d'un entrepôt penda IDA / D5160 A posteriori Direct - National 220,000.00 0.00 Signé 2022-09-30 2022-09-27 2022-10-05 2022-09-30 2022-10-22 2023-04-20 ry Capacity to Rapidly detec ché de gré à gré nt 6 mois pour le stockage d t Outbreaks es biens et équipement du M SP actuellement logés dans l ’entrepôt de Mama Yemo en phase de Réhabilitation ZR-DRC-MSP-327484-NC-DI R / Contractualisation par En tente Directe avec la Firme Component 1: Strengthenin BILEM IMPRESSIONS pour Re g Surveillance and Laborato Passation de mar En cours d'e produire, l'imprimer les Outil IDA / 64980 A posteriori Direct - National 790,778.00 0.00 2022-11-21 2022-11-18 2022-11-24 2022-11-24 2022-12-09 2023-04-08 ry Capacity to Rapidly detec ché de gré à gré xécution s de Formation et relais com t Outbreaks munautaire dans Six Provinc es cibles: Kasaï Central, Kas aï Oriental, Tshopo, Kwilu, N ord Kivu et Tshuapa. ZR-DRC-MSP-334013-NC-DI R / Contractualisation par En Component 1: Strengthenin tente Directe avec OIM pour g Surveillance and Laborato Passation de mar Direct - Internation le renforcement des capacit IDA / D5160 A priori 21,658,235.00 0.00 Annulé 2022-12-29 2023-01-06 2023-01-03 2023-01-06 2023-01-25 2024-05-19 ry Capacity to Rapidly detec ché de gré à gré al és des 18 Points d'Entrée (P t Outbreaks oE) désignés et sites sentine lles pour appuyer REDISSE I V sous Financement Banque Mondiale. ZR-DRC-MSP-334218-NC-DI R / Contractualisation par En Component 1: Strengthenin tente Directe avec OIM pour g Surveillance and Laborato Passation de mar Direct - Internation le renforcement des capacit IDA / D5160 A priori 21,658,235.00 0.00 Annulé 2022-12-30 2023-01-04 2023-01-23 2024-05-17 ry Capacity to Rapidly detec ché de gré à gré al és des 18 Points d'Entrée (P t Outbreaks oE) désignés et sites sentine lles pour appuyer REDISSE I V sous Financement Banque Mondiale. ZR-DRC-MSP-334013-NC-DI Component 1: Strengthenin R-2 / Contractualisation par g Surveillance and Laborato Passation de mar Direct - Internation Entente Directe avec l'OIM p IDA / D5160 A priori 21,658,235.00 0.00 Signé 2023-01-09 2023-01-10 2023-01-14 2023-01-10 2023-01-31 2024-05-25 ry Capacity to Rapidly detec ché de gré à gré al our le Renforcement des Ca t Outbreaks pacités des 18 Points d'Entré es (POEs) ZR-DRC-MSP-354033-NC-DI R / Contractualisation par ED avec le Groupe INNOVIE po Component 1: Strengthenin ur le Transport et Conservati g Surveillance and Laborato Passation de mar En attente d' IDA / D5160 A posteriori Direct - National 200,000.00 0.00 2023-04-03 2023-04-08 2023-04-27 2023-10-24 on des échantillons Biologiq ry Capacity to Rapidly detec ché de gré à gré exécution ues pour les 5 Labo des HGR t Outbreaks de la Province du Kwilu en R DC pour rapidement détecte r les épidémies CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amoun Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Techni Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) t (US$) Notice equest for Proposals as Issued Proposals / Minutes cal Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ZR-DRC-MSP-184499-CS-QC Component 1: Strengthenin BS / Contractualisation avec Sélection fondée g Surveillance and Laborato une structure spécialisée po IDA / 64980 A priori sur la qualité et le Open - National 5,000,000.00 0.00 Annulé 2020-08-24 2020-09-14 2020-10-28 2020-11-25 2020-12-25 2021-01-29 2021-03-05 2022-03-05 ry Capacity to Rapidly detec ur la gestion logistique et ch coût t Outbreaks aine d’approvisionnement ZR-DRC-MSP-184500-CS-QC Component 1: Strengthenin BS / Contractualisation avec Sélection fondée g Surveillance and Laborato des Centres d’Excellence et IDA / 64980 A priori sur la qualité et le Open - National 1,200,000.00 0.00 Annulé 2021-06-27 2021-07-18 2021-08-31 2021-09-28 2021-10-28 2021-12-02 2022-01-06 2023-01-06 ry Capacity to Rapidly detec de laboratoires pour la fourn coût t Outbreaks iture de service de diagnosti c ZR-DRC-MSP-184517-CS-QC Component 1: Strengthenin Sélection fondée BS / Recrutement d’une firm IDA / 64980 g Surveillance and Laborato A posteriori sur la qualité et le Open - National 150,000.00 0.00 Annulé 2020-08-24 2020-09-14 2020-10-28 2020-11-25 2020-12-25 2021-01-29 2021-03-05 2022-03-05 e pour l’audit financier exter ry Capacity to Rapidly detec coût ne du projet t Outbreaks ZR-DRC-MSP-184542-CS-QC Component 1: Strengthenin Sélection fondée BS / Recrutement d'un consu IDA / 64980 g Surveillance and Laborato A posteriori sur la qualité et le Open - National 350,000.00 0.00 Annulé 2020-08-28 2020-09-18 2020-11-01 2020-11-29 2020-12-29 2021-02-02 2021-03-09 2022-03-09 ltant externe pour le suivi en ry Capacity to Rapidly detec coût vironnemental t Outbreaks ZR-DRC-MSP-118031-CS-CQ Component 1: Strengthenin Sélection fondée S / Recrutement de consulta / g Surveillance and Laborato A posteriori sur les qualificatio Open - National 350,000.00 0.00 Annulé 2019-08-22 2019-09-12 2019-10-26 2019-11-25 2019-12-30 2020-06-27 nt pour faire l'état des lieux ry Capacity to Rapidly detec ns des consultant des laboratoires t Outbreaks s ZR-DRC-MSP-117886-CS-CQ Component 1: Strengthenin Sélection fondée S / Contractualisation avec u g Surveillance and Laborato sur les qualificatio ne structure spécialisée pour / A priori Open - National 900,000.00 0.00 Annulé 2019-08-28 2019-09-18 2019-11-01 2019-12-01 2020-01-05 2020-07-03 ry Capacity to Rapidly detec ns des consultant l'amélioration des systèmes t Outbreaks s de transport des échantillon s ZR-DRC-MSP-118041-CS-QC Component 4: Institutional Sélection fondée BS / Recrutement d'une firm / Capacity Building, Project M A posteriori sur la qualité et le Open - National 150,000.00 0.00 Annulé 2019-09-09 2019-09-30 2019-11-13 2019-12-11 2020-01-10 2020-02-14 2020-03-20 2021-03-20 e pour l'audit financier exter anagement, Coordination a coût ne du projet nd Advocacy ZR-DRC-MSP-118040-CS-CQ Component 1: Strengthenin Sélection fondée S / Recrutement d'une firme g Surveillance and Laborato sur les qualificatio / A posteriori Open - National 150,000.00 0.00 Annulé 2019-08-27 2019-09-17 2019-10-31 2019-11-30 2020-01-04 2020-07-02 pour l'élaboration du Plan St ry Capacity to Rapidly detec ns des consultant ratégique des laboratoires d t Outbreaks s e l'Espace CEEAC ZR-DRC-MSP-118039-CS-CQ Component 1: Strengthenin Sélection fondée S / Recrutement d'un Cabine g Surveillance and Laborato sur les qualificatio t pour élaborer le document / A posteriori Open - National 150,000.00 0.00 Annulé 2019-08-14 2019-09-04 2019-10-18 2019-11-17 2019-12-22 2020-06-19 ry Capacity to Rapidly detec ns des consultant de réglementation du transp t Outbreaks s ort international des échantil lons biologiques ZR-DRC-MSP-118038-CS-CQ Component 1: Strengthenin Sélection fondée S / Recrutement d'un Cabine g Surveillance and Laborato sur les qualificatio t pour l'élaboration d'un plan / A posteriori Open - National 150,000.00 0.00 Annulé 2019-08-05 2019-08-26 2019-10-09 2019-11-08 2019-12-13 2020-06-10 ry Capacity to Rapidly detec ns des consultant stratégique de préparation e t Outbreaks s t de réponse aux épidémies et urgences sanitaires ZR-DRC-MSP-118036-CS-CQ S / Recrutement d'une firme Sélection fondée pour la mise en place d'un s Component 3: Public Healt sur les qualificatio / A posteriori Open - National 150,000.00 0.00 Annulé 2019-08-12 2019-09-02 2019-10-16 2019-11-15 2019-12-20 2020-06-17 ystème d'information qui pre h Workforce Development ns des consultant nd en compte les activités d s e la santé humaine et anima le ZR-DRC-MSP-118035-CS-CQ Sélection fondée S / Recrutement d'une firme Component 3: Public Healt sur les qualificatio / A posteriori Open - National 150,000.00 0.00 Annulé 2019-08-13 2019-09-03 2019-10-17 2019-11-16 2019-12-21 2020-06-18 pour l'élaboration de la strat h Workforce Development ns des consultant égie régionale sur les activit s és transfrontalières ZR-DRC-MSP-209283-CS-CQ Component 1: Strengthenin Sélection fondée S / Sélection et recrutement g Surveillance and Laborato sur les qualificatio d'un consultant firme pour fa IDA / 64980 A posteriori Open - National 350,000.00 0.00 Annulé 2021-01-26 2021-05-19 2021-02-16 2021-04-01 2021-05-01 2021-06-05 2021-12-02 ry Capacity to Rapidly detec ns des consultant ire l’état des lieux (Ingénieur t Outbreaks s Architecte et Bio médical) de s laboratoires. ZR-DRC-MSP-199255-CS-CQ S / Sélection et recrutement Component 1: Strengthenin Sélection fondée d'un Consultant firme pour l g Surveillance and Laborato sur les qualificatio En attente d'exéc a conception, la mise en pla IDA / 64980 A posteriori Open - National 124,500.00 0.00 2020-12-30 2021-01-20 2021-03-05 2021-04-04 2021-05-09 2021-11-05 ry Capacity to Rapidly detec ns des consultant ution ce, et la mise en oeuvre des t Outbreaks s systèmes électroniques de s urveillance inter opérable da ns le cadre de « Une Santé » . Page 9 ZR-DRC-MSP-199256-CS-CQ Component 1: Strengthenin Sélection fondée S / Sélection et recrutement g Surveillance and Laborato sur les qualificatio d’une firme pour l’élaboratio IDA / 64980 A posteriori Open - National 150,000.00 0.00 Annulé 2021-01-05 2021-01-26 2021-03-11 2021-04-10 2021-05-15 2021-11-11 ry Capacity to Rapidly detec ns des consultant n du Plan Stratégique des la t Outbreaks s boratoires de l’Espace CEEA C. ZR-DRC-MSP-199251-CS-CQ S / Sélection et recrutement Component 1: Strengthenin Sélection fondée d'un consultant firme pour l' g Surveillance and Laborato sur les qualificatio accompagnement de (s) lab IDA / 64980 A posteriori Open - National 109,920.00 0.00 Annulé 2021-03-25 2021-04-15 2021-05-29 2021-06-28 2021-08-02 2022-01-29 ry Capacity to Rapidly detec ns des consultant oratoire (s) de la RDC au pro t Outbreaks s cessus d'accréditation et de Système Management de Qu alité (SMQ). ZR-DRC-MSP-199263-CS-CQ S / Sélection et recrutement Sélection fondée d'un consultant firme pour u Component 3: Public Healt sur les qualificatio IDA / 64980 A posteriori Open - National 100,000.00 0.00 Annulé 2021-01-25 2021-02-15 2021-03-31 2021-04-30 2021-06-04 2021-12-01 n Audit organisationnel des s h Workforce Development ns des consultant tructures des trois (3) minist s ères parties prenantes au Pr ojet. ZR-DRC-MSP-199278-CS-CQ S / Sélection d'un cabinet d'a Component 4: Institutional Sélection fondée vocats pour réaliser un état Capacity Building, Project M sur les qualificatio En attente d'exéc des lieux des textes juridiqu IDA / 64980 A posteriori Open - National 100,000.00 0.00 2021-01-11 2021-02-01 2021-03-17 2021-04-16 2021-05-21 2021-11-17 anagement, Coordination a ns des consultant ution es et reglémentaires et élab nd Advocacy s orer les avants projet des te xtes juridiques pour la mise en œuvre du RSI. ZR-DRC-MSP-199469-CS-CQ Component 4: Institutional Sélection fondée S / Sélection et recrutement Capacity Building, Project M sur les qualificatio IDA / 64980 A posteriori Open - National 150,000.00 0.00 Annulé 2020-12-30 2021-01-20 2021-03-05 2021-04-04 2021-05-09 2021-11-05 d’une firme pour l’audit fina anagement, Coordination a ns des consultant ncier externe du projet. nd Advocacy s ZR-DRC-MSP-199474-CS-CQ S / Sélection et recrutement Component 4: Institutional Sélection fondée d'un consultant firme extern Capacity Building, Project M sur les qualificatio IDA / 64980 A posteriori Open - National 350,000.00 0.00 Annulé 2021-01-05 2021-01-26 2021-03-11 2021-04-10 2021-05-15 2021-11-11 e pour le suivi des études en anagement, Coordination a ns des consultant vironnementales et la produ nd Advocacy s ction des différents docume nts. ZR-DRC-MSP-199475-CS-CQ S / Sélection et recrutement Component 4: Institutional Sélection fondée d'une ONG pour la mise en Capacity Building, Project M sur les qualificatio IDA / 64980 A posteriori Open - National 300,000.00 0.00 Annulé 2021-01-05 2021-01-26 2021-03-11 2021-04-10 2021-05-15 2021-11-11 œuvre des activités de prév anagement, Coordination a ns des consultant ention et sensibilisation des nd Advocacy s Violences Basées sur le Genr e ZR-DRC-MSP-199476-CS-CQ S / Sélection et recrutement Component 4: Institutional Sélection fondée d'une ONG chargée de l'éval Capacity Building, Project M sur les qualificatio IDA / 64980 A posteriori Open - National 100,000.00 0.00 Annulé 2021-05-03 2021-05-24 2021-07-07 2021-08-06 2021-09-10 2022-03-09 uation de la mise en œuvre anagement, Coordination a ns des consultant des activités ayant trait aux nd Advocacy s Violences Basées sur le Genr e ZR-DRC-MSP-266799-CS-QC BS / Sélection et Recruteme nt d’un Consultant (Bureau d Component 4: Institutional ’études Architecturales) char Sélection fondée Capacity Building, Project M En cours d'exécut gé des Études techniques et IDA / 64980 A posteriori sur la qualité et le Open - National 100,000.00 0.00 2022-02-24 2022-01-02 2022-03-17 2022-03-23 2022-04-30 2022-04-19 2022-05-28 2022-06-27 2022-08-01 2022-09-05 2023-09-05 anagement, Coordination a ion d'évaluation environnement coût nd Advocacy ale et sociale préliminaire, d u Contrôle et de la Surveillan ce des travaux de constructi on/ réhabilitation des bureau x ZR-DRC-MSP-287280-CS-QC BS / Recrutement "Bureau d’ études, Contrôle et Surveilla Component 1: Strengthenin nce" Chargé des Études Tec Sélection fondée g Surveillance and Laborato En cours d'exécut hniques, Evaluation Environn IDA / 64980 A posteriori sur la qualité et le Open - National 100,000.00 0.00 2022-04-04 2022-03-31 2022-04-18 2022-04-07 2022-06-01 2022-06-29 2022-07-29 2022-09-02 2022-10-07 2023-02-04 ry Capacity to Rapidly detec ion ementale et Sociale, du Cont coût t Outbreaks rôle et de la Surveillance des Travaux de Réhab des Labo de Bactériologie en Charge d e la Surveillance Epidémiolo gique ZR-DRC-MSP-295894-CS-QC BS / Sélection et Recruteme Component 1: Strengthenin nt d'un Consultant firme pou Sélection fondée g Surveillance and Laborato En cours d'exécut r la Conception, la mise en p IDA / 64980 A posteriori sur la qualité et le Open - National 150,000.00 0.00 2022-05-31 2022-06-02 2022-06-14 2022-07-05 2022-07-12 2022-07-13 2022-08-17 2022-09-21 2023-09-21 ry Capacity to Rapidly detec ion lace, et la mise en œuvre de coût t Outbreaks s systèmes électroniques de surveillance inter opérable d ans le cadre de « Une Santé ». ZR-DRC-MSP-295896-CS-CQ Component 4: Institutional Sélection fondée S / Recrutement d'un cabine Capacity Building, Project M sur les qualificatio En cours d'exécut IDA / 64980 A posteriori Open - National 100,000.00 0.00 2022-05-31 2022-05-31 2022-06-14 2022-07-05 2022-07-20 2022-08-24 2023-02-20 t d'avocat pour état des lieu anagement, Coordination a ns des consultant ion x des textes juridiques DGL nd Advocacy s M / PNHF ZR-DRC-MSP-301427-CS-QC BS / Recruter d'un Bureau d' Component 2: Strengthenin Études pour les études Arch Sélection fondée g Emergency Planning and En attente d'exéc itecturales et environnement IDA / D5160 A posteriori sur la qualité et le Open - National 100,000.00 0.00 2022-06-29 2022-07-13 2022-08-19 2022-08-26 2022-09-02 2022-09-10 2022-10-11 2022-12-10 Management Capacity to Ra ution ale en vue de la construction coût pidly respond to Outbreaks du bâtiment du Centre des O pérations des Urgences de S anté Publics ( COUSP) ZR-DRC-MSP-301442-CS-QC BS / Recrutement d'un Cabin Component 1: Strengthenin et / Bureau d'Études pour Ét Sélection fondée g Surveillance and Laborato En cours d'exécut ats des lieux pour la réhabilit IDA / D5160 A posteriori sur la qualité et le Open - National 150,000.00 0.00 2022-06-29 2022-11-01 2022-07-13 2022-08-19 2022-08-26 2022-09-02 2022-09-10 2022-10-11 2022-12-10 ry Capacity to Rapidly detec ion ation deux laboratoires de c coût t Outbreaks ontrôle phytosanitaire et sur veillance environnementale à Kinshasa et Lubumbashi. ZR-DRC-MSP-315480-CS-QC BS / Sélection et recrutemen Component 1: Strengthenin t d'un Consultant Firme pour Sélection fondée g Surveillance and Laborato En cours d'exécut la rationalisation et la mise e IDA / 64980 A posteriori sur la qualité et le Open - National 100,000.00 0.00 2022-09-20 2022-11-07 2022-10-04 2022-10-23 2022-10-28 2022-11-02 2022-11-09 2022-11-21 2022-12-21 ry Capacity to Rapidly detec ion n place d’un cadre réglemen coût t Outbreaks taire et institutionnel de l'Ins titut National de Santé Publi que (INSP) ZR-DRC-MSP-315481-CS-QC BS / Le Recrutement d’un co nsultant firme charge d’élab Component 1: Strengthenin oration de trois rapports d’Et Sélection fondée g Surveillance and Laborato En cours d'exécut udes d’impacts environneme IDA / 64980 A posteriori sur la qualité et le Open - National 250,000.00 0.00 2022-09-20 2022-09-12 2022-10-04 2022-10-23 2022-10-28 2022-11-02 2022-11-09 2022-11-21 2023-01-20 ry Capacity to Rapidly detec ion ntal et social (EIES) distincts coût t Outbreaks pour la construction des labo ratoires provinciaux de sant e publique de Mbandaka, Ka nanga et Mbuji-Mayi du redis se ZR-DRC-MSP-301452-CS-QC BS / Recruter un Cabinet fir me pour Surveillance des Tr Component 1: Strengthenin avaux LAPHAKI, Spécificatio Sélection fondée g Surveillance and Laborato ns techniques des matériels IDA / D5160 A posteriori sur la qualité et le Open - National 300,000.00 0.00 Annulé 2022-07-04 2022-10-12 2022-07-18 2022-08-24 2022-08-31 2022-09-07 2022-09-15 2022-10-16 2022-12-15 ry Capacity to Rapidly detec et équipements, assistance t coût t Outbreaks echnique et renforcement d es capacités du personnel te chnique de 2 laboratoires en cours de réhabilitation avec la USP ZR-DRC-MSP-184529-CS-QC Component 1: Strengthenin BS / Accompagnement de la Sélection fondée g Surveillance and Laborato bo de la RDC au processus d IDA / D5160 A posteriori sur la qualité et le Open - National 109,920.00 0.00 Annulé 2021-03-20 2021-04-10 2021-05-24 2021-06-21 2021-07-21 2021-08-25 2021-09-29 2022-09-29 ry Capacity to Rapidly detec 'accreditation et de Système coût t Outbreaks Management de Qualité (SM Q) Page 10 ZR-DRC-MSP-199261-CS-QC BS / Sélection et recrutemen Component 2: Strengthenin t des Centres d’Excellence e Sélection fondée g Emergency Planning and t de laboratoires pour renfor IDA / 64980 A priori sur la qualité et le Open - National 1,200,000.00 0.00 Annulé 2021-06-29 2021-07-20 2021-09-02 2021-09-30 2021-10-30 2021-12-04 2022-01-08 2023-01-08 Management Capacity to Ra cer les capacités des laborat coût pidly respond to Outbreaks oires nationaux (en santé hu maine et en santé animale) à poser des diagnostics. ZR-DRC-MSP-199276-CS-QC BS / Sélection et recrutemen Component 4: Institutional t du (des) bureau (x) d'étude Sélection fondée Capacity Building, Project M s chargé (s) du contrôle et d IDA / 64980 A posteriori sur la qualité et le Open - National 500,000.00 0.00 Annulé 2020-12-23 2021-02-18 2021-01-13 2022-02-16 2021-02-26 2021-03-26 2021-04-25 2021-05-30 2021-07-04 2022-07-04 anagement, Coordination a e la surveillance des travaux coût nd Advocacy de construction/ réhabilitatio n envisagés dans le cadre d e la mise en œuvre du Projet . ZR-DRC-MSP-199257-CS-QC BS / Sélection et recrutemen Component 1: Strengthenin Sélection fondée t d'une agence de communic g Surveillance and Laborato IDA / 64980 A posteriori sur la qualité et le Open - National 950,000.00 0.00 Annulé 2021-06-29 2021-07-20 2021-09-02 2021-09-30 2021-10-30 2021-12-04 2022-01-08 2023-01-08 ation pour la gestion de l’inf ry Capacity to Rapidly detec coût ormation et le développeme t Outbreaks nt technique (mise en place d’un portail web). ZR-DRC-MSP-301445-CS-QC BS / Recruter un cabinet . fir Component 1: Strengthenin Sélection fondée me pour l'accréditation / cert g Surveillance and Laborato IDA / D5160 A posteriori sur la qualité et le Open - National 100,000.00 0.00 Annulé 2022-07-11 2022-07-25 2022-08-31 2022-09-07 2022-09-14 2022-09-22 2022-10-23 2022-12-22 ification du laboratoire physi ry Capacity to Rapidly detec coût cochimique déjà Réhabilité I t Outbreaks SO / IEC 17025:2017. " ZR-DRC-MSP-199244-CS-QC BS / Sélection et recrutemen Component 1: Strengthenin Sélection fondée t des structures spécialisées g Surveillance and Laborato IDA / 64980 A priori sur la qualité et le Open - National 5,000,000.00 0.00 Annulé 2021-01-26 2021-02-16 2021-04-01 2021-04-29 2021-05-29 2021-07-03 2021-08-07 2022-08-07 en stratégie de gestion logis ry Capacity to Rapidly detec coût tique et chaine d’approvisio t Outbreaks nnement des médicaments, intrants et réactifs de labora toire. ZR-DRC-MSP-184502-CS-QC Component 1: Strengthenin BS / Contractualisation avec Sélection fondée g Surveillance and Laborato une structure spécialisée po IDA / 64980 A posteriori sur la qualité et le Open - National 900,000.00 0.00 Annulé 2021-06-27 2021-07-18 2021-08-31 2021-09-28 2021-10-28 2021-12-02 2022-01-06 2023-01-06 ry Capacity to Rapidly detec ur l’amélioration des systèm coût t Outbreaks es de transport des échantill ons ZR-DRC-MSP-199258-CS-CQ S / Sélection et recrutement Component 2: Strengthenin Sélection fondée d’un consultant firme pour la g Emergency Planning and sur les qualificatio mise en place d’un système IDA / 64980 A posteriori Open - National 150,000.00 0.00 Annulé 2021-01-05 2021-01-26 2021-03-11 2021-04-10 2021-05-15 2021-11-11 Management Capacity to Ra ns des consultant d’information frontalier qui p pidly respond to Outbreaks s rend en compte les activités de la santé humaine et anim ale. ZR-DRC-MSP-199478-CS-CQ Component 4: Institutional Sélection fondée S / Sélection et recrutement Capacity Building, Project M sur les qualificatio d’un consultant firme pour l’ IDA / 64980 A posteriori Open - National 150,000.00 0.00 Annulé 2021-06-01 2021-06-22 2021-08-05 2021-09-04 2021-10-09 2022-04-07 anagement, Coordination a ns des consultant élaboration de la stratégie ré nd Advocacy s gionale sur les activités tran sfrontalières. ZR-DRC-MSP-335515-CS-CQ Component 4: Institutional Sélection fondée S / Recrutement d'un Cabine Capacity Building, Project M sur les qualificatio En cours d'exécut IDA / D5160 A posteriori Limited 25,000.00 0.00 2023-01-19 2023-02-06 2023-02-02 2023-03-04 2023-04-08 2024-04-02 t d'Audit pour Appuyer la Cel anagement, Coordination a ns des consultant ion lule d'Audit de l'UG PDSS po nd Advocacy s ur les 4 Programmes. ZR-DRC-MSP-339884-CS-CQ Component 1: Strengthenin Sélection fondée S / Recrutement d'un consult g Surveillance and Laborato sur les qualificatio En attente d'exéc ant firme pour mise en place IDA / D5160 A posteriori Limited 200,000.00 0.00 2023-02-24 2023-03-10 2023-04-09 2023-05-14 2024-05-08 ry Capacity to Rapidly detec ns des consultant ution du Système de Gestion digit t Outbreaks s ale de l'Entrepôt du MSP, à l' hôpital Mama Yemo ZR-DRC-MSP-339948-CS-CQ S / Réaliser les évaluations e nvironnementales et sociale Component 1: Strengthenin Sélection fondée s préliminaires, études de sa g Surveillance and Laborato sur les qualificatio En cours d'exécut IDA / D5160 A posteriori Limited 150,000.00 0.00 2023-02-15 2023-04-05 2023-02-22 2023-03-04 2023-03-19 2023-04-18 uvegarde environnementale ry Capacity to Rapidly detec ns des consultant ion s et sociales des activités de t Outbreaks s cinq (5) laboratoires des HG R à Kwilu (Recrutement des consultants firme; individuel s) ZR-DRC-MSP-346702-CS-CQ Component 1: Strengthenin Sélection fondée S / Recrutement d'un Consul g Surveillance and Laborato sur les qualificatio En attente d'exéc tant pour Réaliser une Etud IDA / 64980 A posteriori Limited 100,000.00 0.00 2023-03-06 2023-03-20 2023-04-03 2023-05-08 2023-06-13 ry Capacity to Rapidly detec ns des consultant ution e sur la Viabilité et la pérenn t Outbreaks s ité des Laboratoires à Réhab iliter / Construire ZR-DRC-MSP-349986-CS-CQ S / Recrutement d'un cabine Component 1: Strengthenin Sélection fondée t / Firme pour Etudes d'Impa g Surveillance and Laborato sur les qualificatio En cours d'exame IDA / D5160 A posteriori Limited 130,000.00 0.00 2023-03-20 2023-03-20 2023-04-03 2023-04-10 2023-05-08 2023-08-06 ct Environnemental et Social ry Capacity to Rapidly detec ns des consultant n des Travaux de Construction t Outbreaks s des Laboratoires de Santé P ublique de Kwilu et Kisangan i ZR-DRC-MSP-351456-CS-QC BS / Recrutement d'un Cabin Component 1: Strengthenin et Chargé pour la mise en pl Sélection fondée g Surveillance and Laborato En attente d'exéc ace d'un Système d'Opératio IDA / 64980 A posteriori sur la qualité et le Open - National 425,000.00 0.00 2023-03-27 2023-04-10 2023-05-01 2023-05-08 2023-05-09 2023-06-13 2023-07-18 2024-02-13 ry Capacity to Rapidly detec ution nnalisation du Système Elect coût t Outbreaks ronique des Surveillances Int égrée et Interopérable dans « Une Santé ». INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Identifie Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amoun Draft Negotiated Con Description Component Review Type Method Process Status Terms of Reference d/Selected Consultan Signed Contract Contract Completion o. h unt (US$) t (US$) tract t Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ZR-DRC-MSP-117851-CS-CD Component 1: Strengthenin Sélection de cons S / Contractualisation avec l' g Surveillance and Laborato / A priori ultants par entent Direct 20,000,000.00 0.00 Annulé 2019-07-22 2019-08-01 2019-10-05 2020-04-02 UNFPA pour la fourniture de ry Capacity to Rapidly detec e directe médicaments et réactifs t Outbreaks ZR-DRC-MSP-117866-CS-CD Component 2: Strengthenin Sélection de cons S / Contractualisation avec l' g Emergency Planning and / A priori ultants par entent Direct 5,000,000.00 0.00 Annulé 2019-07-24 2019-08-03 2019-10-07 2020-04-04 UNICEF pour la gestion logist Management Capacity to Ra e directe ique et chaine d'approvision pidly respond to Outbreaks nement ZR-DRC-MSP-117882-CS-CD Component 2: Strengthenin Sélection de cons S / Contractualisation avec l' g Emergency Planning and / A priori ultants par entent Direct 1,200,000.00 0.00 Annulé 2019-08-19 2019-08-29 2019-11-02 2020-04-30 INRB pour la fourniture de se Management Capacity to Ra e directe rvice de diagnostic pidly respond to Outbreaks ZR-DRC-MSP-117885-CS-CD Component 2: Strengthenin S / Contractualisation avec Sélection de cons g Emergency Planning and BLUES QUARE pour la gestio / A priori ultants par entent Direct 950,000.00 0.00 Annulé 2019-08-27 2019-09-06 2019-11-10 2020-05-08 Management Capacity to Ra n de l'information et le dével e directe pidly respond to Outbreaks oppement technique (mise e n place d'un portail web) ZR-DRC-MSP-117895-CS-IN Component 4: Institutional DV / Recrutement d'un chef IDA / D5160 Capacity Building, Project M A priori Individuel Open 400,000.00 168,600.00 Signé 2019-08-13 2020-06-18 2019-10-01 2020-08-25 2019-10-22 2020-09-01 2019-11-26 2020-09-01 2020-05-24 de projet anagement, Coordination a nd Advocacy ZR-DRC-MSP-117896-CS-IN Component 4: Institutional DV / Recrutement de deux c / Capacity Building, Project M A priori Individuel Open 400,000.00 0.00 Annulé 2019-08-13 2019-10-01 2019-10-22 2019-11-26 2020-05-24 omptables pour la gestion d anagement, Coordination a u projet nd Advocacy ZR-DRC-MSP-118016-CS-IN Component 4: Institutional DV / Recrutement d'un Assis / Capacity Building, Project M A priori Individuel Open 250,000.00 0.00 Annulé 2019-07-30 2019-09-17 2019-10-08 2019-11-12 2020-05-10 tant Technique en Santé Hu anagement, Coordination a maine nd Advocacy Page 11 ZR-DRC-MSP-118017-CS-IN Component 4: Institutional DV / Recrutement d'un Assis / Capacity Building, Project M A priori Individuel Open 250,000.00 0.00 Annulé 2019-07-30 2019-09-17 2019-10-08 2019-11-12 2020-05-10 tant Technique en Santé ani anagement, Coordination a male nd Advocacy ZR-DRC-MSP-118019-CS-IN Component 4: Institutional DV / Recrutement d'un Assis / Capacity Building, Project M A priori Individuel Open 250,000.00 0.00 Annulé 2019-07-30 2019-09-17 2019-10-08 2019-11-12 2020-05-10 tant Technique en Santé vég anagement, Coordination a étale nd Advocacy ZR-DRC-MSP-118021-CS-IN Component 4: Institutional DV / Recrutement d'un Assis Capacity Building, Project M En attente d'exéc / A priori Individuel Open 250,000.00 0.00 2019-07-30 2019-09-17 2019-10-08 2019-11-12 2020-05-10 tant Technique en sauvegar anagement, Coordination a ution de environnementale et soci nd Advocacy ale ZR-DRC-MSP-184520-CS-IN Component 1: Strengthenin DV / Recrutement de consult g Surveillance and Laborato IDA / D5160 A posteriori Individuel Open 60,000.00 0.00 Annulé 2021-06-16 2021-08-04 2021-08-25 2021-09-29 2022-03-28 ant pour élaborer le Cadre d ry Capacity to Rapidly detec e planification des Peuples A t Outbreaks utochtone ZR-DRC-MSP-184521-CS-IN Component 1: Strengthenin DV / Recrutement de consult g Surveillance and Laborato IDA / D5160 A posteriori Individuel Open 60,000.00 0.00 Annulé 2021-06-16 2021-08-04 2021-08-25 2021-09-29 2022-03-28 ants pour élaborer les plans ry Capacity to Rapidly detec de Gestion Environnemental t Outbreaks e et Sociale ZR-DRC-MSP-184524-CS-IN Component 1: Strengthenin DV / Recrutement de consult g Surveillance and Laborato IDA / D5160 A posteriori Individuel Open 60,000.00 0.00 Annulé 2021-06-16 2021-08-04 2021-08-25 2021-09-29 2022-03-28 ants pour élaborer les plans ry Capacity to Rapidly detec d’engagement des Parties Pr t Outbreaks enantes ZR-DRC-MSP-184526-CS-IN DV / Recruter un Consultant Component 1: Strengthenin international pour la concept g Surveillance and Laborato IDA / D5160 A posteriori Individuel Open 30,000.00 0.00 Annulé 2020-08-10 2020-09-28 2020-10-19 2020-11-23 2021-05-22 ion et la mise en place des s ry Capacity to Rapidly detec ystèmes électroniques de su t Outbreaks rveillance interopérable dan s le cadre de « Une Santé » ZR-DRC-MSP-184532-CS-IN Component 1: Strengthenin DV / Recruter un consultant g Surveillance and Laborato IDA / D5160 A posteriori Individuel Open 13,140.00 0.00 Annulé 2020-08-02 2020-09-20 2020-10-11 2020-11-15 2021-05-14 pour réaliser l'évaluation con ry Capacity to Rapidly detec jointe des risques liés aux PZ t Outbreaks D (Grippe Aviaire) ZR-DRC-MSP-184535-CS-IN DV / Recrutement d'un cons Component 1: Strengthenin ultant national senior pour l' g Surveillance and Laborato IDA / D5160 A posteriori Individuel Open 17,720.00 0.00 Annulé 2020-10-04 2020-11-22 2020-12-13 2021-01-17 2021-07-16 élaboration du plan national ry Capacity to Rapidly detec d'envoi, de réception, de sto t Outbreaks ckage et de déploiement de s moyens médicaux ZR-DRC-MSP-184536-CS-IN DV / Recrutement d'un cons Component 1: Strengthenin ultant national senior pour l' g Surveillance and Laborato IDA / D5160 A posteriori Individuel Open 17,720.00 0.00 Annulé 2020-09-04 2020-10-23 2020-11-13 2020-12-18 2021-06-16 élaboration du plan national ry Capacity to Rapidly detec relatif au déploiement du pe t Outbreaks rsonnel en situation d’urgen ce de santé publique ZR-DRC-MSP-184537-CS-IN Component 1: Strengthenin DV / Recrutement d'un cons g Surveillance and Laborato ultant national pour élaborer IDA / D5160 A posteriori Individuel Open 10,000.00 0.00 Annulé 2020-08-02 2020-09-20 2020-10-11 2020-11-15 2021-05-14 ry Capacity to Rapidly detec le plan Stratégique National t Outbreaks Multisectoriel de communica tion des risques ZR-DRC-MSP-184540-CS-IN Component 1: Strengthenin DV / Recruter un consultant g Surveillance and Laborato IDA / D5160 A posteriori Individuel Open 6,800.00 0.00 Annulé 2020-08-31 2020-10-19 2020-11-09 2020-12-14 2021-06-12 national pour l'utilisation et l ry Capacity to Rapidly detec 'implémentation de l'outil E t Outbreaks MAI ZR-DRC-MSP-199268-CS-IN Component 4: Institutional DV / Sélection et recrutemen IDA / 64980 Capacity Building, Project M A priori Individuel Open 337,500.00 0.00 Annulé 2020-12-23 2021-02-10 2021-03-03 2021-04-07 2021-10-04 t d’un Spécialiste en Santé a anagement, Coordination a nimale nd Advocacy ZR-DRC-MSP-199270-CS-IN Component 4: Institutional En cours d'exécut DV / Sélection et recrutemen IDA / 64980 Capacity Building, Project M A priori Individuel Open 337,500.00 0.00 2020-12-23 2021-06-15 2021-02-10 2021-03-03 2021-04-07 2021-10-04 ion t d’un Spécialiste en Epidémi anagement, Coordination a ologie nd Advocacy ZR-DRC-MSP-199274-CS-IN DV / Sélection et Recruteme nt d'un (1) Ingénieur conseil Component 4: Institutional chargé du contrôle et de la s Capacity Building, Project M IDA / 64980 A posteriori Individuel Open 50,000.00 0.00 Annulé 2020-12-23 2021-02-10 2021-03-03 2021-04-07 2021-10-04 urveillance des travaux de c anagement, Coordination a onstruction/ réhabilitation do nd Advocacy nt le démarrage est envisag é dans le cadre de la mise e n œuvre du Projet pour l'an 2020. ZR-DRC-MSP-209292-CS-IN DV / Sélection et recrutemen Component 4: Institutional t d'un consultant internation Capacity Building, Project M IDA / 64980 A posteriori Individuel Open 30,000.00 0.00 Annulé 2020-12-23 2021-07-07 2021-02-10 2021-03-03 2021-04-07 2021-10-04 al pour l'élaboration des prot anagement, Coordination a ocoles pour la gestion des ur nd Advocacy gences en lien avec MVE, CO VID, Rougéole et Choléra ZR-DRC-MSP-209294-CS-IN DV / Sélection et recrutemen Component 4: Institutional t d'un consultant national po Capacity Building, Project M IDA / 64980 A posteriori Individuel Open 20,000.00 0.00 Annulé 2020-12-23 2021-02-10 2021-03-03 2021-04-07 2021-10-04 ur l'élaboration des protocol anagement, Coordination a es pour la gestion des urgen nd Advocacy ces en lien avec MVE, COVID , Rougéole et Choléra ZR-DRC-MSP-218040-CS-CD S / Contractualisation par en Component 2: Strengthenin Sélection de cons tente directe avec l'OMS pou g Emergency Planning and IDA / 64980 A priori ultants par entent Direct 8,000,000.00 3,451,230.60 Signé 2021-03-17 2021-11-26 2021-03-27 2021-08-12 2021-05-31 2022-01-05 2021-11-27 r l'appui au plan de 90 jours Management Capacity to Ra e directe et renforcement des activité pidly respond to Outbreaks s post Ebola à l'Equateur et Provinces voisines ZR-DRC-MSP-218043-CS-CD S / Contractualisation par en Component 2: Strengthenin Sélection de cons tente directe avec OIM pour g Emergency Planning and IDA / 64980 A priori ultants par entent Direct 2,000,000.00 0.00 Annulé 2021-03-24 2021-04-03 2021-06-07 2021-12-04 l'appui au plan de 90 jours e Management Capacity to Ra e directe t renforcement des activités pidly respond to Outbreaks post Ebola à l'Equateur et Pr ovinces voisines ZR-DRC-MSP-227756-CS-IN DV / Recrutement d'un cons Component 1: Strengthenin ultant chargé d’appuyer le P g Surveillance and Laborato DSS dans l’élaboration du do IDA / 64980 A posteriori Individuel Limited 7,000.00 0.00 Annulé 2021-04-29 2021-04-05 2021-05-04 2021-05-25 2021-06-29 2021-12-26 ry Capacity to Rapidly detec ssier technique et du devis d t Outbreaks es travaux de réaménageme nt de l’Entrepôt Central du M inistère de la Santé ZR-DRC-MSP-232228-CS-CD S / Contractualisation par En tente Directe avec CRESTE B Component 1: Strengthenin ureau d'Etudes chargé de la Sélection de cons g Surveillance and Laborato Validation du Rapport de mis IDA / 64990 A posteriori ultants par entent Direct 200,000.00 258,420.00 Signé 2021-05-27 2021-05-04 2021-06-06 2021-05-10 2021-08-10 2021-05-14 2022-02-06 ry Capacity to Rapidly detec sion de l'Ingénieur Jean-Paul e directe t Outbreaks MAKOMA INRB, Elaboration d u DAO et du Contrôle et Surv eillance des travaux de réha bilitation du Laboratoire de Bunia ZR-DRC-MSP-232790-CS-IN DV / Contractualisation en e Component 1: Strengthenin ntente directe avec Monsieu g Surveillance and Laborato IDA / 64980 A posteriori Individuel Direct 116,200.00 116,200.00 Signé 2021-05-27 2021-05-18 2021-06-06 2020-09-25 2021-06-27 2020-09-28 2021-08-01 2020-10-01 2022-01-28 r AHLEGNAN KOMLAN Victor, ry Capacity to Rapidly detec consultant spécialiste en ges t Outbreaks tion financière en appui au P rojet REDISSE ZR-DRC-MSP-232061-CS-IN Component 1: Strengthenin DV / Contractualisation par e g Surveillance and Laborato IDA / 64980 A posteriori Individuel Direct 53,400.00 53,400.00 Signé 2021-05-27 2021-05-18 2021-06-06 2020-09-21 2021-06-27 2020-09-22 2021-08-01 2020-09-24 2022-01-28 ntente directe avec Monsieu ry Capacity to Rapidly detec r Dimitri MATUTEZULWA LU t Outbreaks BOKOLO Page 12 ZR-DRC-MSP-232064-CS-IN Component 1: Strengthenin DV / Contractualisation par e g Surveillance and Laborato ntente directe avec Monsieu IDA / 64980 A posteriori Individuel Direct 36,822.50 36,822.50 Signé 2021-05-31 2021-05-18 2021-06-10 2021-10-19 2021-07-01 2021-02-03 2021-08-05 2021-02-03 2022-02-01 ry Capacity to Rapidly detec r Camille BAMONEKENE WAS t Outbreaks UKAMA, Comptable en appui au Projet REDISSE IV ZR-DRC-MSP-235192-CS-CD S / Contractualisation par en tente directe (ED) avec la Fir Component 1: Strengthenin me United States Pharmaco Sélection de cons g Surveillance and Laborato peia (USP) pour appuyer l'U IDA / 64980 A posteriori ultants par entent Direct 70,000.00 0.00 Annulé 2021-06-24 2021-06-05 2021-07-04 2021-10-20 2021-09-07 2022-03-06 ry Capacity to Rapidly detec G PDSS dans l'établissement e directe t Outbreaks de l'état des lieux, l'élaborati on du dossier technique et d u devis des travaux de réam énagement des Laboratoires ZR-DRC-MSP-256330-CS-CD S / Contractualisation par en tente directe (ED) avec la Fir Component 1: Strengthenin me United States Pharmaco Sélection de cons g Surveillance and Laborato En cours d'exécut peia (USP) pour appuyer l'U IDA / 64980 A posteriori ultants par entent Direct 434,222.00 0.00 2021-10-20 2021-10-04 2021-10-30 2022-01-03 2022-07-02 ry Capacity to Rapidly detec ion G PDSS dans l'établissement e directe t Outbreaks de l'état des lieux, l'élaborati on du dossier technique et d u devis des travaux de réam énagement des Laboratoires ZR-DRC-MSP-218042-CS-CD S / Contractualisation par en Component 2: Strengthenin Sélection de cons tente avec UNICEF, appui au g Emergency Planning and IDA / 64980 A priori ultants par entent Direct 4,000,000.00 0.00 Annulé 2021-03-23 2021-04-02 2021-06-06 2021-12-03 plan de 90 jours et renforce Management Capacity to Ra e directe ment des activités post Ebol pidly respond to Outbreaks a à l'Equateur et Provinces v oisines ZR-DRC-MSP-263380-CS-IN DV / Recrutement d’un spéci Component 4: Institutional aliste en développement soc Capacity Building, Project M En cours d'exécut IDA / 64980 A posteriori Individuel Limited 57,600.00 0.00 2022-01-20 2021-11-30 2022-01-25 2022-02-15 2022-03-22 2022-09-18 ial appelé à prester pour le P anagement, Coordination a ion rojet de Renforcement des s nd Advocacy ystèmes de surveillance des maladies en Afrique Centrale ZR-DRC-MSP-263706-CS-CD S / Contractualisation par En Component 4: Institutional tente Directe avec Mr Theod Sélection de cons Capacity Building, Project M En cours d'exécut ore KAZADI KASHISHI Consul IDA / 64980 A posteriori ultants par entent Direct 60,000.00 0.00 2022-01-20 2021-12-04 2022-01-30 2022-04-05 2022-10-02 anagement, Coordination a ion tant chargé du Contrôle des e directe nd Advocacy travaux de Désamiantage à Entrepôt Central de Mama Y emo. ZR-DRC-MSP-118014-CS-IN Component 4: Institutional DV / Recrutement d'un Spéci / Capacity Building, Project M A priori Individuel Open 300,000.00 0.00 Annulé 2019-07-30 2021-03-01 2019-09-17 2019-10-08 2019-11-12 2020-05-10 aliste en Passation des Marc anagement, Coordination a hés nd Advocacy ZR-DRC-MSP-228866-CS-CD Component 1: Strengthenin S / Contractualisation par en Sélection de cons g Surveillance and Laborato tente directe avec Monsieur IDA / 64980 A posteriori ultants par entent Direct 147,290.00 0.00 Annulé 2021-04-30 2021-05-10 2021-07-14 2022-01-10 ry Capacity to Rapidly detec Camille BAMONEKENE WASU e directe t Outbreaks KAMA, Comptable en appui a u Projet REDISSE IV ZR-DRC-MSP-235192-CS-CD S-2 / Contractualisation par directe (ED) avec la Firme U Component 1: Strengthenin nited States Pharmacopeia ( Sélection de cons g Surveillance and Laborato En attente d'exéc USP) pour l'entente de souti IDA / 64980 A posteriori ultants par entent Direct 434,222.00 0.00 2022-03-30 2022-04-09 2022-06-13 2022-12-10 ry Capacity to Rapidly detec ution en à l'UG PDSS dans l'établis e directe t Outbreaks sement de l'état des lieux, l' élaboration du dossier techn ique et du devis des travaux de réaménagement des Lab oratoires ZR-DRC-MSP-289453-CS-IN Component 1: Strengthenin DV / Contractualisation par E g Surveillance and Laborato En cours d'exécut ntente Directe avec le Spéci IDA / D5160 A posteriori Individuel Direct 70,000.00 0.00 2022-04-08 2022-04-18 2022-04-21 2022-05-17 2023-05-12 ry Capacity to Rapidly detec ion aliste en Passation des Marc t Outbreaks hés Mr. Adelard KUMBU KUM BU ZR-DRC-MSP-287587-CS-CD S / Contractualisation par ED avec UNFPA pour appui des Component 1: Strengthenin Sélection de cons projets PDSS, PMNS, REDISS g Surveillance and Laborato En cours d'exécut IDA / D5160 A priori ultants par entent Direct 20,000,000.00 0.00 2022-04-11 2022-04-19 2022-04-21 2022-05-30 2022-06-25 2023-12-17 E IV et COVID 19 pour attenu ry Capacity to Rapidly detec ion e directe ation et réponses aux risque t Outbreaks s de EAS/HS liés à la mise en Oeuvre dans les zones d'inte rvention de ces projets ZR-DRC-MSP-273072-CS-CD S / Contractualisation par en tente directe avec UNFPA po Component 2: Strengthenin Sélection de cons ur appuiyer les projets PDSS g Emergency Planning and IDA / 64980 A priori ultants par entent Direct 10,000,000.00 0.00 Annulé 2022-02-24 2022-03-06 2022-05-10 2022-11-06 PMNS REDISSE IV et COVID 1 Management Capacity to Ra e directe 9 financement add.BM par p pidly respond to Outbreaks revention , attenuation aux r isque l'EAS/HS lié à la mise e n oeuvre des Opérations ZR-DRC-MSP-301462-CS-IN Component 1: Strengthenin DV / Contractualisation par E g Surveillance and Laborato En attente d'exéc ntente Directe avec le Spéci IDA / D5160 A posteriori Individuel Direct 64,200.00 0.00 2022-07-01 2022-07-11 2022-07-14 2022-08-09 2023-08-04 ry Capacity to Rapidly detec ution aliste en Suivi Evaluation Mr t Outbreaks MUISHA BAROKI Derrick ZR-DRC-MSP-305224-CS-CD S / Contractualisation par En tente directe avec le consult Component 4: Institutional Sélection de cons ant individuel Mr Bruno BOL Capacity Building, Project M IDA / 64980 A posteriori ultants par entent Direct - National 95,000.00 0.00 Annulé 2022-07-21 2022-07-29 2022-07-31 2022-08-03 2022-10-04 2023-04-02 EKYMO pour la préparation d anagement, Coordination a e directe u plan d'action du peuple au nd Advocacy tochtone dans les zones de s anté de WANGATA, BOLENG E et MBANDAKA ZR-DRC-MSP-309077-CS-IN Component 1: Strengthenin DV / Contractualisation par E g Surveillance and Laborato En cours d'exécut ntente Directe avec le Projec IDA / D5160 A posteriori Individuel Direct - National 90,000.00 0.00 2022-08-22 2022-08-17 2022-09-01 2022-09-22 2022-10-27 2023-10-22 ry Capacity to Rapidly detec ion t Manager de Projet REDISSE t Outbreaks IV Dr Baudouin MAKUMA BO OTO ZR-DRC-MSP-324810-CS-CD S / Contractualisation par En Component 1: Strengthenin tente Directe avec OIM pour Sélection de cons g Surveillance and Laborato Direct - Internation le renforcement des capacit IDA / D5160 A priori ultants par entent 21,677,602.00 0.00 Signé 2022-11-02 2022-11-08 2022-11-12 2022-06-16 2022-12-31 2024-06-23 ry Capacity to Rapidly detec al és des 18 Points d'Entrée (P e directe t Outbreaks oE) désignés et sites sentine lles pour appuyer REDISSE I V sous Financement Banque Mondiale. ZR-DRC-MSP-295886-CS-CD S / Contractualisation en Ent ente Directe (ED) avec l’Org Component 1: Strengthenin anisation Internationale pour Sélection de cons g Surveillance and Laborato les Migrations (OIM) pour le r IDA / D5160 A priori ultants par entent Direct 16,000,000.00 0.00 Annulé 2022-05-30 2022-06-22 2022-06-09 2022-06-16 2022-07-28 2023-07-23 ry Capacity to Rapidly detec enforcement des capacités d e directe t Outbreaks es 18 Points d’Entrée (PoE) d ésignés et sites sentinelles p our appuyer le projet REDISS E IV sous le financement BM ZR-DRC-MSP-263377-CS-IN DV / Recrutement d’un spéci Component 4: Institutional aliste en sauvegarde environ Capacity Building, Project M nementale appelé à prester IDA / 64980 A posteriori Individuel Limited 57,600.00 0.00 Annulé 2022-01-12 2021-11-24 2022-01-17 2022-02-07 2022-03-14 2022-09-10 anagement, Coordination a pour le Projet de Renforcem nd Advocacy ent des systèmes de surveill ance des maladies en Afriqu e Centrale ZR-DRC-MSP-184519-CS-IN Component 1: Strengthenin DV / Recrutement de consult g Surveillance and Laborato IDA / D5160 A posteriori Individuel Open 60,000.00 0.00 Annulé 2021-06-16 2021-08-04 2021-08-25 2021-09-29 2022-03-28 ant pour élaborer le Cadre d ry Capacity to Rapidly detec e Réinsertion des Population t Outbreaks s Page 13 ZR-DRC-MSP-199247-CS-IN DV / Sélection et recrutemen Component 1: Strengthenin t d'un (1) consultant internat g Surveillance and Laborato IDA / 64980 A posteriori Individuel Open 50,000.00 0.00 Annulé 2020-12-24 2021-02-11 2021-03-04 2021-04-08 2021-10-05 ional et deux (2) consultants ry Capacity to Rapidly detec nationaux pour réaliser l'éva t Outbreaks luation conjointe des risques liés aux pandémies zoonotiq ues. ZR-DRC-MSP-199265-CS-IN Component 4: Institutional DV / Sélection et recrutemen IDA / 64980 Capacity Building, Project M A priori Individuel Open 375,000.00 0.00 Annulé 2020-12-23 2020-12-23 2021-02-10 2021-06-22 2021-03-03 2021-04-07 2021-10-04 t d’un Spécialiste en Suivi- E anagement, Coordination a valuation nd Advocacy ZR-DRC-MSP-301456-CS-IN Component 1: Strengthenin DV / Recrutement d'un Cons g Surveillance and Laborato ultant Individuel pour l'Elabo IDA / D5160 A posteriori Individuel Open 70,000.00 0.00 Annulé 2022-07-11 2022-08-06 2022-08-27 2022-09-27 2022-11-26 ry Capacity to Rapidly detec ration du plan en faveur des t Outbreaks populations des peuples aut ochtones (PPA) ZR-DRC-MSP-184533-CS-IN Component 1: Strengthenin DV / Recrutement de 2 cons g Surveillance and Laborato IDA / D5160 A posteriori Individuel Open 20,000.00 0.00 Annulé 2020-08-16 2020-10-04 2020-10-25 2020-11-29 2021-05-28 ultants nationaux pour la for ry Capacity to Rapidly detec mation en biosécurité t Outbreaks ZR-DRC-MSP-263383-CS-IN DV / Contractualisation par E ntente Directe avec Mme AN Component 4: Institutional INA MITULO consultant char Capacity Building, Project M gé de la mise en œuvre du r IDA / 64980 A posteriori Individuel Direct 7,000.00 0.00 Annulé 2022-01-27 2021-11-24 2022-02-06 2022-02-27 2022-04-03 2022-09-30 anagement, Coordination a apport d’évaluation des pert nd Advocacy es économiques des travaux de réhabilitation du laboratoi re médical de référence prov incial de Bunia (Province de l ’Ituri) ZR-DRC-MSP-117897-CS-IN Component 4: Institutional DV / Recrutement d'un respo / Capacity Building, Project M A priori Individuel Open 300,000.00 0.00 Annulé 2019-08-13 2019-10-01 2019-10-22 2019-11-26 2020-05-24 nsable en suivi et évaluation anagement, Coordination a du projet nd Advocacy ZR-DRC-MSP-184531-CS-IN DV / Recruter un consultant Component 1: Strengthenin national pour développer un g Surveillance and Laborato guide standard pour réaliser IDA / D5160 A posteriori Individuel Open 7,870.00 0.00 Annulé 2020-08-20 2021-03-04 2020-10-08 2020-10-29 2020-12-03 2021-06-01 ry Capacity to Rapidly detec un état des lieux des textes j t Outbreaks uridiques et reglémentaires pour la mise en œuvre du RS I (2005) ZR-DRC-MSP-239895-CS-IN DV / Contractualisation par e ntente directe avec Monsieu Component 1: Strengthenin r KAYINDU KALUMBA Jean-Bi g Surveillance and Laborato envenu, consultant chargé d IDA / 64980 A posteriori Individuel Direct 14,000.00 0.00 Annulé 2021-07-22 2021-08-09 2021-08-01 2021-08-22 2021-09-26 2022-03-25 ry Capacity to Rapidly detec e la réalisation d'un plan de t Outbreaks gestion environnementale et sociale (PGES) et d'un plan d 'hygiène, santé et sécurité ( PHSS) des travaux de réhabi litation ZR-DRC-MSP-327472-CS-IN Component 1: Strengthenin DV / Contractualisation par E g Surveillance and Laborato En attente d'exéc IDA / D5160 A posteriori Individuel Direct - National 19,560.00 0.00 2022-11-21 2022-11-29 2022-12-06 2022-12-23 2023-12-18 ntente Directe avec l'Assista ry Capacity to Rapidly detec ution nte Trésorière Madame LIZA t Outbreaks NSIAFUMU FIFA ZR-DRC-MSP-327478-CS-IN Component 1: Strengthenin DV / Contractualisation par E g Surveillance and Laborato Direct - Internation En attente d'exéc IDA / 64980 A posteriori Individuel 120,616.00 0.00 2022-11-21 2022-12-01 2022-12-08 2022-12-25 2023-12-20 ntente Directe avec Monsieu ry Capacity to Rapidly detec al ution r AHLEGNAN KOMLAN, Exper t Outbreaks t en Finances ZR-DRC-MSP-320887-CS-CD S / Contractualisation par ED avec USP pour appuyer l'UG Component 1: Strengthenin PDSS dans la surveillance de Sélection de cons g Surveillance and Laborato Direct - Internation En attente d'exéc s Travaux de Réhabilitation IDA / D5160 A posteriori ultants par entent 300,000.00 0.00 2022-10-17 2022-10-27 2022-12-31 2023-06-29 ry Capacity to Rapidly detec al ution des Labo d'analyses microbi e directe t Outbreaks o et dispositifs médicaux, de l'accompagnement techniqu e ainsi que de la formation d u personnel du LNCQ LAPHA KI ZR-DRC-MSP-335548-CS-IN DV / Recrutement des Consu Component 1: Strengthenin ltants pour Analyse et évalu g Surveillance and Laborato En attente d'exéc IDA / 64980 A posteriori Individuel Limited 30,000.00 0.00 2023-01-31 2023-02-05 2023-02-26 2023-04-02 2023-09-29 ation des documents de Pas ry Capacity to Rapidly detec ution sation des Marchés pour Con t Outbreaks struction des 7 Laboratoires du MSP ZR-DRC-MSP-341423-CS-IN DV / Recrutement d'un Ingén Component 1: Strengthenin ieur en Génie Civil pour trait g Surveillance and Laborato En attente d'exéc IDA / D5160 A posteriori Individuel Limited 30,000.00 0.00 2023-02-13 2023-02-18 2023-03-11 2023-04-15 2023-10-12 ement du Dossier d'Appel d' ry Capacity to Rapidly detec ution Offres et autres documents t Outbreaks pour les Travaux de Constru ction de 7 laboratoires ZR-DRC-MSP-346694-CS-CD S / Contractualisation par En Component 4: Institutional Sélection de cons tente Directe avec Mr Claud Capacity Building, Project M Direct - Internation En cours d'exécut IDA / 64980 A posteriori ultants par entent 126,130.00 0.00 2023-03-06 2023-03-03 2023-03-16 2023-03-20 2023-04-27 2023-10-24 e OGOU, Assistant Techniqu anagement, Coordination a al ion e directe e International en Passation nd Advocacy des Marchés pour Appuyer l' UG PDSS ZR-DRC-MSP-349989-CS-IN DV / Recrutement d'un Cons Component 1: Strengthenin ultant Individuel pour l'Elabo g Surveillance and Laborato En cours d'exécut ration des Plans de Gestion IDA / D5160 A posteriori Individuel Limited 30,000.00 0.00 2023-03-23 2023-03-20 2023-03-28 2023-04-04 2023-05-09 2023-08-07 ry Capacity to Rapidly detec ion Environnementale et Sociale t Outbreaks des Travaux de Réhabilitatio n deV2 Laboratoires Vétérin aire et Environnemental de Kinshasa. ZR-DRC-MSP-349991-CS-IN DV / Recrutement d'un Cons ultant Individuel pour l'Elabo Component 1: Strengthenin ration des Plans de Gestion g Surveillance and Laborato En attente d'exéc Environnementale et Sociale IDA / D5160 A posteriori Individuel Limited 60,000.00 0.00 2023-03-22 2023-03-29 2023-04-05 2023-04-22 2023-07-21 ry Capacity to Rapidly detec ution des Travaux de Réhabilitatio t Outbreaks n de 5 Laboratoires de 4 Hô pitaux Généraux de Référen ce: Bandundu - Ville, Mosang o, Kikwit Nord, Gungu et Idio fa ZR-DRC-MSP-350004-CS-IN Component 4: Institutional DV / Renouvellement du Con Capacity Building, Project M En attente d'exéc trat Pour Mr Adélard KUMBU IDA / D5160 A posteriori Individuel Direct - National 87,360.00 0.00 2023-04-05 2023-04-15 2023-04-18 2023-04-24 2024-04-18 anagement, Coordination a ution KUMBU Spécialiste en Passat nd Advocacy ion des Marchés de REDISSE IV au sein de l'UG - PDSS ZR-DRC-MSP-350188-CS-IN Component 4: Institutional DV / Renouvellement du Con Capacity Building, Project M En attente d'exéc trat pour Mr Derrick BAROKI IDA / D5160 A posteriori Individuel Direct - National 82,500.00 0.00 2023-03-31 2023-04-10 2023-04-17 2023-04-23 2024-04-17 anagement, Coordination a ution Spécialiste en Suivi Evaluati nd Advocacy on REDISSE IV - UG PDSS Page 14