Appendix to Annex 3 Procurement Plan I. General 1. Project Information Country : India Borrower : Government of India Project Name : National Hydrology Project Loan Credit No. : 2. Bank’s Approval Date of the Procurement Plan : 3. Date of General Procurement Notice : 4. Period Covered by this procurement plan : 18 months II. Goods, Works, and Non-Consulting Services Thresholds for Method of Procurement for procurement of goods, works and non- consulting services Procurement of Goods, Information technology and non consultancy services: Method of Procurement Thresholds for Methods International Competitive Bidding (ICB) > US Dollars 3 million Limited Competitive Bidding (LIB) Must meet the requirements as per Para 3.2 of the Procurement Guidelines, and with prior agreement in PP with the Bank National Competitive Bidding (NCB) > USD 100,000 and up to USD 3 million Shopping Up to USD 100,000 (INR 6.5 m) Direct Must meet the requirements as per Para 3.7 of the Procurement Guidelines, and with prior agreement in PP with the Bank Framework Agreement Must meet the requirements as per Para 3.6 of the Procurement Guidelines, and with prior agreement in PP with the Bank Procurement of Works: Method of Procurement Thresholds for Methods International Competitive Bidding (ICB) > US Dollars 40 million National Competitive Bidding (NCB) > USD 100,000 and up to USD 40 million Comparison of three quotations / Up to USD 100,000 (INR 6.5 m) Shopping Force Account Must meet the requirements as per Para 3.9 of the Procurement Guidelines, and with prior agreement in PP with the Bank Prior Review Thresholds: The following would be subject to Prior review of the Bank regardless of the Method of selection: (a) Works: First procurement under the project irrespective of value and all procurements estimated to cost more than USD 10 million (b) Goods: First procurement under the project irrespective of value and all procurements estimated to cost more than USD 2 million; and The Prior Review Thresholds will be reviewed and updated during the implementation of the project, and modified based on the risk assessment. 1. In the case of contracts subject to prior review, Project Implementing Entity shall seek the Bank’s no objection before granting/agreeing to (a) an extension of the stipulated time for performance of a contract that either increases the contract price or has an impact on the planned completion of the project; (b) any substantial modification of the scope of works, goods, non-consulting services or consulting services, other significant changes to the terms and conditions of such that the contract,; (c) any variation order or amendment (except in cases of extreme urgency) which singly or combined with all variation orders or amendments previously issued, increase the original contract amount by more than 15 percent; or (d) the proposed termination of the contract.. A copy of all amendments to the contract shall be furnished to the Bank for its record. 2. Prequalification Not Applicable Domestic Preference: The provision of domestic preference is applicable in the evaluation of Goods only. 3. Reference to Procurement Manual The procurement manual for the project is presently under preparation. SBDs agreed between the Project and Bank will be used for all works, goods, and non consultancy procurements. 4. Any Other Special Procurement Arrangements The National bidding method for procurement and goods and works according to the above value thresholds will be conducted in accordance with paragraphs 3.3 and 3.4 of the Bank’s Procurement Guidelines and the following provisions: (a) Only the model bidding documents for NCB agreed with the GOI task force (and as amended for time to time) shall be used for bidding. (b)Invitations to bid shall be advertised in at least one widely circulated national daily newspaper (or on a widely used website or electronic portal with free national and international access along with an abridged version of the said advertisement published in a widely circulated national daily, among others, giving the website/electronic portal details from which the details of the invitation to bid can be downloaded) at least 30 days before the deadline for the submission of bids. (c) No special preferences will be accorded to any bidder either for price or for other terms and conditions when competing with foreign bidders, state- owned enterprises, small-scale enterprises, or enterprises from any given state. (d)Extension of bid validity shall not be allowed with reference to contracts subject to Bank prior review without the prior concurrence of the Bank (i) for the first request for extension if it is longer than four weeks and (ii) for all subsequent requests for extension irrespective of the period (such concurrence will be considered by the Bank only in cases of force majeure and circumstances beyond the control of the purchaser/employer). (e) Rebidding shall not be carried out with reference to contracts subject to Bank prior review without the prior concurrence of the Bank. The system of rejecting bids outside a predetermined margin or ‘bracket’ of prices shall not be used in the project. (f) Rate contracts entered into by the DGS&D will not be acceptable as a substitute for NCB procedures unless incorporation of right to audit and fraud corruption clauses. DGS&D contracts will be acceptable, however, for any procurement under the shopping procedures. (g)Two or three envelope system will not be used (except when using the e- procurement system assessed and agreed by the Bank). (h)No negotiations are conducted even with the lowest evaluated responsive bidders. 5. The bid evaluation will be carried out according to the agreed timeline in the Procurement Activity Schedule. III. Selection of Consultants 1. Methods and Prior Review Threshold Procurement methods of procurement of Consultants' Services (Firms) Method of Procurement Thresholds for Methods Quality and Cost Based Selection (QCBS) Quality Based Selection (QBS) Must meet the requirements as per Para 3..2 to 3.4 of the Consultant Guidelines Selection based on a Fixed Budget Must meet the requirements as per (FBS) Para 3.5 of the Consultant Guidelines, Selection Based on Least Cost Basis Must meet the requirements as per (LCS) Para 3.6 of the Consultant Guidelines, Selection based on Consultant’s Estimated not to exceed USD Qualification (CQ) 300,000, and must meet the requirements as per Para 3.7 of the Consultant Guidelines. Single Source Selection (SSS) Must meet the requirements as per Para 3.8 to 3.11 of the Consultant Guidelines, and with prior agreement in PP with the Bank. Procurement methods for Selection of Individual Consultants (IC) Method of Procurement Thresholds for Methods Competitive Selection Must meet the requirements of Section V, Para 5.1 to 5.5 of the Consultant Guidelines. Single Source Selection (SSS) Must meet the requirements of Section V, Para 5.6 of the Consultant Guidelines and with prior agreement in PP with the Bank *Shall meet the requirements as stated in Consultant Guidelines Prior Review Thresholds: (a). Consulting Firm: First procurement under the project irrespective of value and all procurements estimated to cost more than USD 1 million. (b). Individual Consultant: all procurements estimated to cost more than USD 0.3 million Terms of Reference (ToR) for all consultant contracts shall be furnished to the Bank for its prior review and No Objection. Note: The Prior Review Thresholds will be reviewed during the implementation of the project and modified. 1. In the case of contracts subject to prior review, before agreeing to: (a) an extension of the stipulated time for performance of a contract; (b) any substantial modification of the scope of services, substitutions of key experts, or other significant changes to the terms and conditions of the contract; or (c) the proposed termination of the contract, the Borrower shall seek the Bank’s no objection. A copy of all amendments to the contract shall be furnished to the Bank for its record. 2. Short List comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than USD 800,000 equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. The Request for Expression of Interest for consultancy services estimated to cost above USD 300,000 equivalent per contract for firms shall be advertised in UNDB online and World Bank external Website and in accordance with other provisions of Para 2.5 of the Consultant Guidelines 4. Any other Special Selection Arrangements: [including advance procurement and retroactive financing, if applicable] I. Implementing Agency Capacity Building Activities with Time Schedule No Expected Outcome/Activity Description Estimated Date Duration ASCI training on Procurement Procedures arranged for Executive, Assistant Engineers 1. 2 weeks Continuous who are responsible for Procurement – multiple trainings Contract management training – multiple 2. 2 weeks Continuous trainings Customized training on Procurement Procedures arranged for Executive, Assistant 3. 1 week Continuous Engineers who are responsible for Procurement – multiple trainings PROCUREMENT India : National Hydrology Project PLAN General Information Country: India 2017-11-09 Bank’s Approval Date of the Original Procurement Plan: 2023-04-01 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P152698 GPN Date: 2022-06-17 Project Name: National Hydrology Project Loan / Credit No: IBRD / 87250 National Institute of Hydrology, Roorkee Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned NHP-2018-2019-NIH-193022 Water Resources Monitoring Request for Quota Single Stage - One E Pending Imp 2019-05-0 -CW-NCB-SE / Construction of IBRD / 87250 Post Limited 61,538.46 0.00 2018-09-15 2018-11-10 System tions nvelope lementation 9 Regional Centre NHP-2019-2020-NIH-795511 Water Resources Operations Request for Quota Single Stage - One E 2020-02-2 IBRD / 87250 Post Limited 7,692.31 3,166.20 Completed 2019-07-06 2019-08-16 2019-08-31 2019-10-23 / Piezometer Development (1 and Planning System tions nvelope 7 2 nos.) NHP-2019-2020-NIH-211316 Water Resources Operations Request for Quota Single Stage - One E 2020-01-3 IBRD / 87250 Post Limited 3,076.92 1,282.39 Completed 2019-06-09 2020-02-07 2019-08-04 2020-02-28 / Piezometer Development and Planning System tions nvelope 1 IN-NIH ROORKEE-182047-C Water Resources Operations Request for Quota Single Stage - One E Pending Imp 2021-03-0 IBRD / 87250 Post Limited 3,846.15 0.00 2020-07-13 2020-09-07 W-RFQ / Piezometer Develop and Planning System tions nvelope lementation 6 ment IN-NIH ROORKEE-252756-C Request for Quota W-RFQ / River Cross-Section Water Resources Operations Request for Quota Single Stage - One E 2022-05-1 IBRD / 87250 Post Limited tions (Non Bank-S 15,385.00 8,900.15 Signed 2021-09-25 2021-09-20 2021-11-20 2021-12-23 Survey of River Gandak betw and Planning System tions nvelope 9 PD) een Dumariaghat to Hajipur ( 80 cross-sections) GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IN-NIH ROORKEE-16148-GO- RFB / Desktop Computers (20 Institutional Capacity Enhan Request for Quota Single Stage - One E IBRD / 87250 Post Limited 77,000.00 20,128.30 Completed 2017-10-03 2017-10-27 2017-11-28 2018-04-24 2018-03-15 2018-04-24 ), Workstation (1), Digital Pho cement tions nvelope tocopier (1), Blade Server (2) , Projector (1) IN-NIH ROORKEE-30957-GO- RFB / Gas Chromatograph Ma Institutional Capacity Enhan Single Stage - Two E Under Imple IBRD / 87250 Post Request for Bids Open - National 276,923.00 0.00 2017-10-27 2017-11-27 2017-11-01 2017-12-13 2018-02-25 2018-04-01 2018-09-28 ss Spectrometer 01, Dedicat cement nvelope mentation ed Auto Titrator 01, TOC Anal yser 01 IN-NIH ROORKEE-30965-GO- RFB / Element Analyser (Dual Carbon C 13 Isotope analyser Institutional Capacity Enhan Single Stage - Two E Under Imple IBRD / 87250 Post Request for Bids Open - National 215,385.00 0.00 2017-10-27 2017-11-28 2017-11-01 2017-12-13 2018-02-25 2018-04-01 2018-09-28 ) 01, Tritium Enrichment unit cement nvelope mentation 01, Normal Scintillation Coun ter 01, Liquid Nitrogen Plant 01. IN-NIH ROORKEE-61685-GO- Institutional Capacity Enhan Single Stage - Two E Pending Impl IBRD / 87250 Post Request for Bids Open - National 149,300.00 0.00 2018-05-31 2018-05-31 2018-07-12 2018-09-24 2018-10-29 2019-03-22 RFB / TRIPLE QUADRUPOLE G cement nvelope ementation C-MS IN-NIH ROORKEE-65126-GO- Institutional Capacity Enhan Request for Quota Single Stage - One E Pending Impl IBRD / 87250 Post Open - National 7,000.00 0.00 2018-06-16 2018-08-11 2019-02-07 RFQ / Laptop (6 nos.) cement tions nvelope ementation NHP-2018-2019-NIH-107727 Institutional Capacity Enhan Request for Quota Single Stage - One E Pending Impl IBRD / 87250 Post Limited 3,076.92 0.00 2018-10-06 2018-12-01 2019-05-30 -GO-SH-QU / Copier / photoco cement tions nvelope ementation pier NHP-2018-2019-NIH-888075 Institutional Capacity Enhan Request for Quota Single Stage - One E Pending Impl IBRD / 87250 Post Limited 3,846.15 0.00 2018-10-06 2018-12-01 2019-05-30 -GO-SH-QU / Plotter/Printer cement tions nvelope ementation NHP-2018-2019-NIH-989202 Water Resources Monitoring Request for Quota Single Stage - One E Pending Impl IBRD / 87250 Post Open - National 10,769.23 0.00 2018-10-06 2018-12-01 2019-05-30 -GO-SH-QU / Server System tions nvelope ementation NHP-2018-2019-NIH-204542 Water Resources Operations Request for Quota Single Stage - One E Pending Impl IBRD / 87250 Post Open - National 4,615.38 0.00 2018-10-06 2018-12-01 2019-05-30 -GO-SH-QU / WorkStations and Planning System tions nvelope ementation NHP-2018-2019-NIH-108835 Institutional Capacity Enhan Request for Quota Single Stage - One E Pending Impl -GO-SH-QU / Travel Stationer IBRD / 87250 Post Limited 38,461.54 0.00 2018-07-06 2018-08-31 2019-02-27 cement tions nvelope ementation y and Computer Consumable s , Misc NHP-2018-2019-NIH-880926 Water Resources Operations Request for Quota Single Stage - One E Pending Impl IBRD / 87250 Post Limited 1,538.46 0.00 2018-08-20 2018-10-15 2019-04-13 -GO-SH-QU / Radiocarbon Da and Planning System tions nvelope ementation ting Line NHP-2018-2019-NIH-934679 Water Resources Operations Request for Quota Single Stage - One E Pending Impl IBRD / 87250 Post Limited 2,307.69 0.00 2018-09-04 2018-10-30 2019-04-28 -GO-SH-QU / Syringe Pump and Planning System tions nvelope ementation NHP-2018-2019-NIH-241231 Water Resources Operations Request for Quota Single Stage - One E Pending Impl IBRD / 87250 Post Limited 1,076.92 0.00 2018-04-10 2018-06-05 2018-12-02 -GO-SH-QU / Laptop and Planning System tions nvelope ementation NHP-2018-2019-NIH-190238 Water Resources Operations Request for Quota Single Stage - One E Pending Impl -GO-DC-DC / GeoChemist Wo IBRD / 87250 Post Limited 10,769.23 0.00 2018-09-04 2018-10-30 2019-04-28 and Planning System tions nvelope ementation rk Bench Software NHP-2018-2019-NIH-724684 Water Resources Operations Request for Quota Single Stage - One E Pending Impl IBRD / 87250 Post Open - National 4,615.38 0.00 2019-01-04 2019-03-01 2019-08-28 -GO-DC-DC / VMOD FLEX Soft and Planning System tions nvelope ementation ware NHP-2018-2019-NIH-731166 Water Resources Operations Request for Quota Single Stage - One E IBRD / 87250 Post Limited 923.08 815.88 Completed 2018-07-20 2019-02-15 2018-09-14 2019-03-27 2019-03-13 2019-04-29 -GO-SH-QU / Laptop and Planning System tions nvelope NHP-2018-2019-NIH-538584 Water Resources Operations Request for Quota Single Stage - One E Pending Impl IBRD / 87250 Post Limited 461.54 0.00 2018-08-04 2018-09-29 2019-03-28 -GO-SH-QU / Camera and Planning System tions nvelope ementation NHP-2018-2019-NIH-825174 Water Resources Operations Request for Quota Single Stage - One E Pending Impl IBRD / 87250 Post Limited 1,230.77 0.00 2018-08-04 2018-09-29 2019-03-28 -GO-SH-QU / Handheld GPS and Planning System tions nvelope ementation Page 1 NHP-2018-2019-NIH-637041 Water Resources Operations Pending Impl IBRD / 87250 Post Direct Selection Direct 7,692.31 0.00 2018-08-30 2018-09-04 2018-10-09 2019-04-07 -GO-DC-DC / WQ Software and Planning System ementation NHP-2018-2019-NIH-335053 Water Resources Operations Request for Quota Single Stage - One E Pending Impl IBRD / 87250 Post Limited 1,538.46 0.00 2018-08-20 2018-10-15 2019-04-13 -GO-SH-QU / Portable pH & E and Planning System tions nvelope ementation C Meter NHP-2018-2019-NIH-452255 Water Resources Operations Request for Quota Single Stage - One E Pending Impl IBRD / 87250 Post Open - National 5,769.23 0.00 2018-07-20 2018-09-14 2019-03-13 -GO-SH-QU / Laptop and Planning System tions nvelope ementation NHP-2018-2019-NIH-197101 Water Resources Operations Request for Quota Single Stage - One E IBRD / 87250 Post Limited 5,846.15 928.88 Completed 2018-07-20 2019-02-19 2018-09-14 2019-02-28 2019-03-13 2019-06-04 -GO-SH-QU / Desktop and Planning System tions nvelope NHP-2018-2019-NIH-853608 Water Resources Operations Request for Quota Single Stage - One E IBRD / 87250 Post Limited 692.31 263.03 Completed 2018-08-20 2019-02-19 2018-10-15 2019-03-11 2019-04-13 2019-04-30 -GO-SH-QU / Printers and Planning System tions nvelope NHP-2018-2019-NIH-371795 Water Resources Operations Request for Quota Single Stage - One E Pending Impl IBRD / 87250 Post Limited 615.38 0.00 2018-08-04 2018-09-29 2019-03-28 -GO-SH-QU / Water Level Met and Planning System tions nvelope ementation er NHP-2018-2019-NIH-538573 Water Resources Operations Request for Quota Single Stage - One E Pending Impl IBRD / 87250 Post Limited 692.31 0.00 2018-08-20 2018-10-15 2019-04-13 -GO-SH-QU / Camera and Planning System tions nvelope ementation NHP-2018-2019-NIH-803917 Water Resources Operations Request for Quota Single Stage - One E Pending Impl IBRD / 87250 Post Open - National 7,692.31 0.00 2018-08-20 2018-10-15 2019-04-13 -GO-DC-DC / Softwares and Planning System tions nvelope ementation NHP-2018-2019-NIH-934561 Water Resources Operations Request for Quota Single Stage - One E Pending Impl IBRD / 87250 Post Limited 1,230.77 0.00 2018-08-04 2018-09-29 2019-03-28 -GO-SH-QU / Portable pH & E and Planning System tions nvelope ementation C Meter NHP-2018-2019-NIH-172815 Water Resources Operations Request for Quota Single Stage - One E IBRD / 87250 Post Limited 769.23 647.91 Completed 2018-08-04 2020-01-17 2018-09-29 2020-02-26 2019-03-28 2020-10-13 -GO-SH-QU / Digital Burette and Planning System tions nvelope NHP-2018-2019-NIH-518596 Water Resources Operations Request for Quota Single Stage - One E IBRD / 87250 Post Limited 3,076.92 914.65 Completed 2018-09-04 2018-12-11 2018-10-30 2019-01-28 2019-04-28 2020-08-11 -GO-SH-QU / Flame Photomet and Planning System tions nvelope er NHP-2018-2019-NIH-225835 Water Resources Operations Request for Quota Single Stage - One E Pending Impl -GO-SH-QU / Cut Throat Flum IBRD / 87250 Post Limited 3,076.92 0.00 2018-09-20 2018-11-15 2019-05-14 and Planning System tions nvelope ementation e / V-Notch NHP-2018-2019-NIH-335077 Water Resources Operations Request for Quota Single Stage - One E Pending Impl -GO-SH-QU / Desktop Workst IBRD / 87250 Post Limited 10,000.00 0.00 2018-08-04 2018-09-29 2019-03-28 and Planning System tions nvelope ementation ation, Laptop Workstation, D esktop-5nos. NHP-2018-2019-NIH-477025 Water Resources Operations Request for Quota Single Stage - One E Pending Impl IBRD / 87250 Post Limited 769.23 0.00 2018-08-04 2018-09-29 2019-03-28 -GO-SH-QU / Handheld GPS and Planning System tions nvelope ementation NHP-2018-2019-NIH-685156 Water Resources Operations Request for Quota Single Stage - One E Pending Impl IBRD / 87250 Post Limited 538.46 0.00 2018-08-04 2018-09-29 2019-03-28 -GO-SH-QU / Camera and Planning System tions nvelope ementation NHP-2018-2019-NIH-469053 Water Resources Operations Request for Quota Single Stage - One E Pending Impl IBRD / 87250 Post Limited 2,307.69 0.00 2018-08-04 2018-09-29 2019-03-28 -GO-SH-QU / Mini Disk Infiltro and Planning System tions nvelope ementation meter NHP-2018-2019-NIH-108582 Water Resources Operations Request for Quota Single Stage - One E Pending Impl -GO-SH-QU / Portable Soil & IBRD / 87250 Post Limited 3,076.92 0.00 2018-08-20 2018-10-15 2019-04-13 and Planning System tions nvelope ementation Water Testing Kit NHP-2018-2019-NIH-170551 Institutional Capacity Enhan Request for Quota Single Stage - One E Pending Impl -CS-SSS-SSS / Development o IBRD / 87250 Post Limited 23,076.92 0.00 2018-08-04 2018-09-29 2019-03-28 cement tions nvelope ementation f Advanced Courses NHP-2018-2019-NIH-503451 Water Resources Operations Single Stage - Two E IBRD / 87250 Post Request for Bids Open - National 7,692.31 2,215.25 Completed 2018-04-01 2018-11-15 2018-04-06 2018-05-18 2018-12-18 2018-07-31 2019-03-06 2018-09-04 2019-03-28 2019-03-03 2019-06-24 -GO-NCB-DE / EC Probes for S and Planning System nvelope alinity NHP-2018-2019-NIH-236582 Water Resources Monitoring Single Stage - Two E -GO-NCB-DE / Auto Titrator P IBRD / 87250 Post Request for Bids Open - National 61,538.46 55,238.75 Completed 2018-06-20 2019-01-02 2018-06-25 2018-08-06 2019-02-05 2018-10-19 2019-08-01 2018-11-23 2019-08-22 2019-05-22 2019-12-23 System nvelope otentiometeric NHP-2018-2019-NIH-825129 Water Resources Monitoring Single Stage - Two E IBRD / 87250 Post Request for Bids Open - National 61,538.46 57,228.30 Signed 2018-06-22 2018-06-21 2018-06-27 2018-08-08 2018-08-03 2018-10-21 2018-10-05 2018-11-25 2018-10-25 2019-05-24 2019-09-06 -GO-NCB-DE / TOC Analyzer System nvelope NHP-2018-2019-NIH-864594 Water Resources Monitoring Single Stage - Two E -GO-NCB-DE / Normal Scintill IBRD / 87250 Post Request for Bids Open - National 30,769.23 36,825.16 Completed 2018-06-26 2018-06-28 2018-07-01 2018-08-12 2018-08-08 2018-10-25 2018-11-14 2018-11-29 2018-11-22 2019-05-28 2019-03-15 System nvelope ation Counter NHP-2018-2019-NIH-931387 Water Resources Monitoring Single Stage - Two E -GO-NCB-DE / CHNS Analyser IBRD / 87250 Post Request for Bids Open - National 55,384.62 51,711.36 Completed 2018-04-01 2018-05-08 2018-04-06 2018-05-18 2018-07-02 2018-07-31 2018-09-24 2018-09-04 2018-09-26 2019-03-03 2019-03-29 System nvelope with Biomass Converter NHP-2018-2019-NIH-541114 Water Resources Monitoring Single Stage - Two E IBRD / 87250 Post Request for Bids Open - National 76,923.08 68,105.66 Completed 2018-05-01 2018-05-11 2018-05-06 2018-06-17 2018-06-29 2018-08-30 2018-09-14 2018-10-04 2018-09-26 2019-04-02 2019-07-11 -GO-NCB-DE / Element Analy System nvelope ser NHP-2018-2019-NIH-310418 Institutional Capacity Enhan Single Stage - One E Pending Impl IBRD / 87250 Post Request for Bids Open - National 15,384.62 0.00 2018-10-01 2018-10-06 2018-11-17 2018-12-17 2019-01-21 2019-07-20 -GO-NCB-DE / Furniture and F cement nvelope ementation urnishings NHP-2018-2019-NIH-604606 Water Resources Operations Single Stage - Two E Pending Impl IBRD / 87250 Post Request for Bids Open - National 7,692.31 0.00 2018-08-15 2018-08-20 2018-10-01 2018-12-14 2019-01-18 2019-07-17 -GO-NCB-DE / Data Logger (T and Planning System nvelope ementation LC) NHP-2018-2019-NIH-119698 Water Resources Operations Single Stage - Two E -GO-NCB-DE / Automatic WL IBRD / 87250 Post Request for Bids Open - National 10,769.23 6,690.61 Completed 2018-04-01 2018-02-20 2018-04-06 2018-05-18 2018-03-08 2018-07-31 2018-07-03 2018-09-04 2018-07-19 2019-03-03 2019-03-27 and Planning System nvelope Recorder & Conductivity Log ger NHP-2018-2019-NIH-741431 Water Resources Operations Single Stage - Two E -GO-NCB-DE / Multi-Paramete IBRD / 87250 Post Request for Bids Open - National 9,230.77 6,763.26 Completed 2018-04-01 2018-02-12 2018-04-06 2018-05-18 2018-03-06 2018-07-31 2018-06-07 2018-09-04 2018-06-27 2019-03-03 2018-12-12 and Planning System nvelope r Ion Analyser NHP-2018-2019-NIH-908192 Water Resources Operations Single Stage - Two E Pending Impl IBRD / 87250 Post Request for Bids Open - National 9,230.77 0.00 2018-08-15 2018-08-20 2018-10-01 2018-12-14 2019-01-18 2019-07-17 -GO-NCB-DE / Soil Monitoring and Planning System nvelope ementation Probes NHP-2018-2019-NIH-166446 Water Resources Operations Single Stage - Two E Pending Impl IBRD / 87250 Post Request for Bids Open - National 5,384.62 0.00 2018-08-15 2018-08-20 2018-10-01 2018-12-14 2019-01-18 2019-07-17 -GO-NCB-DE / Aquameter and Planning System nvelope ementation NHP-2018-2019-NIH-320919 Water Resources Operations Pending Impl -GO-DC-DC / Satellite, Meteor IBRD / 87250 Post Direct Selection Direct 6,153.85 0.00 2018-07-15 2018-07-20 2018-08-24 2019-02-20 and Planning System ementation ological & Geological Data NHP-2018-2019-NIH-371269 Water Resources Operations Single Stage - Two E Pending Impl IBRD / 87250 Post Request for Bids Open - National 3,384.62 0.00 2018-08-30 2018-09-04 2018-10-16 2018-12-29 2019-02-02 2019-08-01 -GO-NCB-DE / Handheld GPS and Planning System nvelope ementation Page 2 NHP-2018-2019-NIH-161213 Water Resources Operations Pending Impl IBRD / 87250 Post Direct Selection Direct 16,923.08 0.00 2018-07-15 2018-07-20 2018-08-24 2019-02-20 -GO-DC-DC / Satellite Data and Planning System ementation NHP-2018-2019-NIH-444196 Water Resources Operations Single Stage - One E Pending Impl IBRD / 87250 Post Request for Bids Open - National 7,615.38 0.00 2018-07-30 2018-08-04 2018-09-15 2018-10-15 2018-11-19 2019-05-18 -GO-NCB-DE / Rain Gauges and Planning System nvelope ementation NHP-2018-2019-NIH-247027 Water Resources Operations Single Stage - Two E IBRD / 87250 Post Request for Bids Open - National 10,769.23 4,203.03 Completed 2018-08-30 2020-02-07 2018-09-04 2018-10-16 2020-03-13 2018-12-29 2020-07-31 2019-02-02 2020-08-19 2019-08-01 2020-12-09 -GO-NCB-DE / UV Spectropho and Planning System nvelope tometer NHP-2018-2019-NIH-664627 Water Resources Operations Single Stage - Two E -GO-NCB-DE / Water Purificat IBRD / 87250 Post Request for Bids Open - National 7,692.31 3,523.75 Completed 2018-08-30 2020-02-07 2018-09-04 2018-10-16 2020-03-13 2018-12-29 2020-07-31 2019-02-02 2020-08-11 2019-08-01 2020-12-18 and Planning System nvelope ion System NHP-2018-2019-NIH-898480 Water Resources Operations Single Stage - Two E Pending Impl IBRD / 87250 Post Request for Bids Open - National 7,692.31 0.00 2018-09-15 2018-09-20 2018-11-01 2019-01-14 2019-02-18 2019-08-17 -GO-NCB-DE / Soil Moisture P and Planning System nvelope ementation robe NHP-2018-2019-NIH-610130 Water Resources Monitoring Single Stage - Two E Pending Impl IBRD / 87250 Post Request for Bids Open - National 15,384.62 0.00 2018-04-01 2018-04-06 2018-05-18 2018-07-31 2018-09-04 2019-03-03 -GO-NCB-DE / Air Pycnometer System nvelope ementation NHP-2018-2019-NIH-378613 Water Resources Operations Single Stage - Two E Under Imple IBRD / 87250 Post Request for Bids Open - National 10,000.00 0.00 2018-07-15 2019-01-22 2018-07-20 2018-08-31 2019-02-19 2018-11-13 2018-12-18 2019-06-16 -GO-NCB-DE / Tension Infiltro and Planning System nvelope mentation meter NHP-2018-2019-NIH-428585 Water Resources Operations Request for Quota Single Stage - One E Pending Impl IBRD / 87250 Post Limited 6,850.00 0.00 2018-08-20 2018-10-15 2019-04-13 -GO-DC-DC / Visual MODFLO and Planning System tions nvelope ementation W NHP-2018-2019-NIH-522571 Water Resources Operations Pending Impl IBRD / 87250 Post Direct Selection Direct 6,153.85 0.00 2018-07-30 2018-08-04 2018-09-08 2019-03-07 -GO-DC-DC / Soil Data and Planning System ementation IN-NIH ROORKEE-72911-GO- Water Resources Operations Request for Quota Single Stage - One E Pending Impl IBRD / 87250 Post Open - National 21,550.00 0.00 2018-09-22 2018-11-17 2019-05-16 RFQ / ArcGIS Software and Planning System tions nvelope ementation NHP-2018-2019-NIH-716566 Water Resources Monitoring Open - Internationa Single Stage - Two E IBRD / 87250 Post Request for Bids 153,846.15 0.00 Canceled 2018-07-30 2018-10-09 2018-08-04 2018-10-09 2018-09-15 2018-11-28 2019-01-02 2019-07-01 -GO-ICB-DE / Triple Quadrupo System l nvelope le GC-MS NHP-2018-2019-NIH-437156 Water Resources Monitoring Single Stage - Two E IBRD / 87250 Post Request for Bids Open - National 36,923.08 21,900.77 Completed 2018-04-23 2018-05-01 2018-04-28 2018-06-09 2018-06-20 2018-08-22 2018-09-18 2018-09-26 2018-10-05 2019-03-25 2020-01-16 -GO-NCB-DE / Microwave dig System nvelope ester IN-NIH ROORKEE-92629-GO- Water Resources Operations Pending Impl DIR / ArcGIS Desktop Advanc IBRD / 87250 Post Direct Selection Direct 27,500.00 0.00 2018-12-31 2019-01-05 2019-02-09 2019-08-08 and Planning System ementation ed software NHP-2018-2019-NIH-716566 Water Resources Monitoring Open - Internationa Single Stage - Two E -GO-ICB-DE-2 / Triple Quadru IBRD / 87250 Post Request for Bids 153,846.15 0.00 Canceled 2019-01-07 2019-01-23 2019-01-12 2019-01-23 2019-02-23 2019-03-07 2019-05-08 2019-06-12 2019-12-09 System l nvelope pole GC-MS NHP-2018-2019-NIH-896867 Water Resources Monitoring Single Stage - Two E IBRD / 87250 Post Request for Bids Open - National 30,769.23 0.00 Canceled 2018-01-23 2018-01-28 2018-03-11 2018-05-24 2018-06-28 2018-12-25 -GO-NCB-DE / Liquid Nitrogen System nvelope Plant NHP-2018-2019-NIH-279015 Water Resources Monitoring Single Stage - Two E -GO-NCB-DE / Ion Chromotog IBRD / 87250 Post Request for Bids Open - National 36,153.85 0.00 Canceled 2018-09-01 2019-01-11 2018-09-06 2018-10-18 2019-02-19 2018-12-31 2019-02-04 2019-08-03 System nvelope raphm, Water Purification Sy stem NHP-2018-2019-NIH-384746 Water Resources Operations Single Stage - Two E IBRD / 87250 Post Request for Bids Open - National 5,538.46 0.00 Canceled 2018-07-30 2018-08-04 2018-09-15 2018-11-28 2019-01-02 2019-07-01 -GO-NCB-DE / WQ Equipment and Planning System nvelope s NHP-2018-2019-NIH-432805 -GO-NCB-DE / Multi-Probe Me Water Resources Operations Single Stage - Two E IBRD / 87250 Post Request for Bids Open - National 8,846.15 0.00 Canceled 2018-07-15 2019-02-05 2018-07-20 2019-02-05 2018-08-31 2019-03-07 2018-11-13 2018-12-18 2019-06-16 ter, Magnetic Stirrer, Digital and Planning System nvelope Titrator, Weighing Balance, D eep Lab Freezer NHP-2019-2020-NIH-505150 Water Resources Monitoring Request for Quota Single Stage - One E Pending Impl IBRD / 87250 Post Limited 7,692.31 0.00 2019-06-06 2019-08-01 2020-01-28 / Computers/Laptops System tions nvelope ementation NHP-2019-2020-NIH-458687 Water Resources Monitoring Request for Quota Single Stage - One E Pending Impl IBRD / 87250 Post Limited 6,153.85 0.00 2019-06-06 2019-08-01 2020-01-28 / Plotter/Printer System tions nvelope ementation NHP-2019-2020-NIH-629383 Water Resources Monitoring Request for Quota Single Stage - One E Pending Impl IBRD / 87250 Post Limited 1,538.46 0.00 2019-06-06 2019-08-01 2020-01-28 / UPS System System tions nvelope ementation NHP-2019-2020-NIH-875368 Water Resources Informatio Request for Quota Single Stage - One E Pending Impl IBRD / 87250 Post Limited 1,538.46 0.00 2019-06-06 2019-08-01 2020-01-28 / Storage and Backup Device n Systems tions nvelope ementation s NHP-2019-2020-NIH-977382 Water Resources Monitoring Request for Quota Single Stage - One E IBRD / 87250 Post Limited 6,153.85 4,840.74 Completed 2019-06-06 2020-09-15 2019-08-01 2020-09-15 2020-01-28 2021-01-06 / Workstation System tions nvelope NHP-2019-2020-NIH-631330 Water Resources Monitoring Single Stage - Two E Pending Impl IBRD / 87250 Post Request for Bids Open - National 80,769.23 0.00 2019-04-01 2019-04-06 2019-05-18 2019-07-31 2019-09-04 2020-03-02 / Ion Chromotograph System nvelope ementation NHP-2019-2020-NIH-239999 Water Resources Informatio IBRD / 87250 Post Direct Selection Direct 6,923.08 6,050.86 Completed 2019-07-15 2019-08-16 2019-07-20 2019-09-06 2019-08-24 2019-12-18 2020-02-20 2020-03-18 / Water Purification System n Systems NHP-2019-2020-NIH-198141 Water Resources Operations Request for Quota Single Stage - One E IBRD / 87250 Post Limited 1,076.92 945.81 Completed 2019-07-06 2019-06-12 2019-08-31 2019-06-12 2020-02-27 2019-07-05 / Desktop PC and Planning System tions nvelope NHP-2019-2020-NIH-970905 Water Resources Operations Request for Quota Single Stage - One E IBRD / 87250 Post Limited 3,076.92 1,278.47 Completed 2019-07-06 2019-07-23 2019-08-31 2019-11-27 2020-02-27 2020-02-26 / pH Meter, EC Meter and Planning System tions nvelope NHP-2019-2020-NIH-683061 Water Resources Operations Request for Quota Single Stage - One E / Water Temperature Profiler, IBRD / 87250 Post Limited 1,538.46 1,122.59 Completed 2019-06-20 2019-07-08 2019-08-15 2019-11-25 2020-02-11 2019-12-10 and Planning System tions nvelope Water Level Indicator NHP-2019-2020-NIH-351582 / Autoclave (1 no.), COD Prob e (1 no.), Double Refractrom Water Resources Operations Request for Quota Single Stage - One E Pending Impl eter (1 no.), Double Distillatio IBRD / 87250 Post Limited 5,538.46 0.00 2019-07-06 2019-08-31 2020-02-27 and Planning System tions nvelope ementation n Unit (1 no.), DO Probe (1 n o.), Push Point Piezometer (1 no.), Mufflw Furnace (1 no.), Oven (1 no.), Deep Freezer ( 1 no.) NHP-2019-2020-NIH-565487 / Hot Air Oven (1 no.), Handh Water Resources Operations Request for Quota Single Stage - One E eld Salinity Refractrometer (2 IBRD / 87250 Post Limited 4,615.38 1,769.00 Completed 2019-07-06 2019-10-31 2019-08-31 2020-05-26 2020-02-27 2020-08-11 and Planning System tions nvelope nos.), Flame Photometer (1 n o.), Portable DO Meter (1 no.) Page 3 NHP-2019-2020-NIH-497998 Water Resources Operations Request for Quota Single Stage - One E IBRD / 87250 Post Limited 5,384.62 3,020.00 Completed 2019-07-06 2019-10-22 2019-08-31 2019-12-18 2020-02-27 2020-03-18 / Earth Resistivity Meter and Planning System tions nvelope NHP-2019-2020-NIH-910157 Water Resources Operations Pending Impl IBRD / 87250 Post Direct Selection Direct 3,076.92 0.00 2019-07-15 2019-07-20 2019-08-24 2020-02-20 / Visual Modflow Pro Software and Planning System ementation NHP-2019-2020-NIH-166238 Water Resources Operations Request for Quota Single Stage - One E Pending Impl IBRD / 87250 Post Limited 9,230.77 0.00 2019-07-06 2019-08-31 2020-02-27 / SPSS Software and Planning System tions nvelope ementation NHP-2019-2020-NIH-784087 Water Resources Operations Request for Quota Single Stage - One E IBRD / 87250 Post Limited 1,538.46 935.87 Completed 2019-07-06 2020-02-03 2019-08-31 2020-05-29 2020-02-27 2020-09-03 / Lab Deep Freezer and Planning System tions nvelope NHP-2019-2020-NIH-876926 Water Resources Operations Request for Quota Single Stage - One E Pending Impl IBRD / 87250 Post Limited 4,615.38 0.00 2019-07-06 2019-08-31 2020-02-27 / ERDAS Software Upgradatio and Planning System tions nvelope ementation n NHP-2019-2020-NIH-524026 Water Resources Operations Request for Quota Single Stage - One E Pending Impl / Data logger (Temp., Conduc IBRD / 87250 Post Limited 16,153.85 0.00 2019-07-06 2019-08-31 2020-02-27 and Planning System tions nvelope ementation tivity & Depth), GW Level Re corders NHP-2019-2020-NIH-301959 Water Resources Operations Request for Quota Single Stage - One E Pending Impl IBRD / 87250 Post Limited 1,538.46 0.00 2019-06-06 2019-08-01 2020-01-28 / Portable EC, pH, Temp. Met and Planning System tions nvelope ementation ers NHP-2019-2020-NIH-128064 Water Resources Operations Request for Quota Single Stage - One E IBRD / 87250 Post Limited 3,076.92 2,488.40 Completed 2019-07-06 2019-01-11 2019-08-31 2019-02-21 2020-02-27 2019-03-29 / Glass Chromatography Colu and Planning System tions nvelope mns NHP-2019-2020-NIH-934154 Water Resources Operations Request for Quota Single Stage - One E IBRD / 87250 Post Limited 6,769.23 3,193.60 Completed 2019-06-22 2019-09-14 2019-08-17 2019-09-14 2020-02-13 2020-01-08 / Desktop PCs and Planning System tions nvelope NHP-2019-2020-NIH-750628 Water Resources Operations Request for Quota Single Stage - One E IBRD / 87250 Post Limited 14,769.23 4,859.36 Completed 2019-07-06 2020-09-15 2019-08-31 2020-09-15 2020-02-27 2021-01-06 / Desktop Workstations and Planning System tions nvelope NHP-2019-2020-NIH-658142 Water Resources Operations Request for Quota Single Stage - One E IBRD / 87250 Post Limited 9,230.77 7,528.68 Completed 2019-07-06 2019-11-20 2019-08-31 2020-06-24 2020-02-27 2020-09-03 / Data Loggers and Planning System tions nvelope NHP-2019-2020-NIH-717328 Water Resources Operations Request for Quota Single Stage - One E IBRD / 87250 Post Limited 3,846.15 3,419.51 Completed 2019-07-06 2020-01-31 2019-08-31 2020-06-15 2020-02-27 2020-09-09 / Multi Probe Meter for Water and Planning System tions nvelope Testing NHP-2019-2020-NIH-760014 Water Resources Operations Request for Quota Single Stage - One E IBRD / 87250 Post Limited 6,153.85 3,288.20 Completed 2019-06-23 2019-07-25 2019-08-18 2019-12-18 2020-02-14 2020-05-05 / Lab Scale Column Setup and Planning System tions nvelope NHP-2019-2020-NIH-145089 Water Resources Operations Request for Quota Single Stage - One E Pending Impl / GW Extraction Unit (Submer IBRD / 87250 Post Limited 2,307.69 0.00 2019-07-06 2019-08-31 2020-02-27 and Planning System tions nvelope ementation sible Pump, Generator, etc.) NHP-2019-2020-NIH-351213 Water Resources Operations Request for Quota Single Stage - One E IBRD / 87250 Post Limited 3,538.46 1,811.99 Completed 2019-07-06 2019-07-19 2019-08-31 2019-12-30 2020-02-27 2020-03-18 / Raingauges (5 nos.) and Planning System tions nvelope NHP-2019-2020-NIH-829043 Water Resources Operations IBRD / 87250 Post Direct Selection Direct 9,230.77 6,449.94 Completed 2019-07-15 2019-11-08 2019-07-20 2019-12-11 2019-08-24 2020-05-08 2020-02-20 2020-06-09 / Hydrus 3D Professional and Planning System NHP-2019-2020-NIH-961106 Water Resources Operations IBRD / 87250 Post Direct Selection Direct 12,307.69 7,546.43 Completed 2019-08-01 2019-11-08 2019-08-06 2019-12-10 2019-09-10 2020-05-08 2020-03-08 2020-06-09 / GMS Premium Latest Versio and Planning System n NHP-2019-2020-NIH-572446 Water Resources Operations Pending Impl IBRD / 87250 Post Direct Selection Direct 6,153.85 0.00 2019-09-01 2019-09-06 2019-10-11 2020-04-08 / Visual Modflow Flex and Planning System ementation NHP-2019-2020-NIH-658179 Water Resources Operations Request for Quota Single Stage - One E Pending Impl IBRD / 87250 Post Limited 3,076.92 0.00 2019-07-06 2019-08-31 2020-02-27 / Cooling Cabinet with Stabili and Planning System tions nvelope ementation zer for Lab NHP-2019-2020-NIH-816989 Water Resources Operations Request for Quota Single Stage - One E Pending Impl IBRD / 87250 Post Limited 13,846.15 0.00 2019-07-06 2019-08-31 2020-02-27 / Multiparameter Water Testi and Planning System tions nvelope ementation ng Probe NHP-2019-2020-NIH-734421 Water Resources Operations Request for Quota Single Stage - One E Pending Impl / Suction Lysimeter/ Pore Wat IBRD / 87250 Post Limited 1,076.92 0.00 2019-07-06 2019-08-31 2020-02-27 and Planning System tions nvelope ementation er Sampling NHP-2019-2020-NIH-877838 Water Resources Operations Request for Quota Single Stage - One E Pending Impl / Soil Moisture Meter with Dat IBRD / 87250 Post Limited 12,307.69 0.00 2019-07-06 2019-08-31 2020-02-27 and Planning System tions nvelope ementation a Logger (with 5 sensors) NHP-2019-2020-NIH-491385 Water Resources Operations Request for Quota Single Stage - One E Pending Impl IBRD / 87250 Post Limited 15,384.62 0.00 2019-07-06 2019-08-31 2020-02-27 / Digital Water Level Recorde and Planning System tions nvelope ementation rs (DWLR) NHP-2019-2020-NIH-950007 Water Resources Operations Request for Quota Single Stage - One E Pending Impl IBRD / 87250 Post Limited 6,923.08 0.00 2019-07-06 2019-08-31 2020-02-27 / Electronic Balance and Planning System tions nvelope ementation NHP-2019-2020-NIH-258627 Water Resources Operations IBRD / 87250 Post Direct Selection Direct 923.08 695.00 Completed 2019-07-15 2020-05-13 2019-07-20 2020-05-18 2019-08-24 2020-09-07 2020-02-20 2020-09-24 / XLSTAT Premium software and Planning System NHP-2019-2020-NIH-459903 Water Resources Operations Pending Impl IBRD / 87250 Post Direct Selection Direct 923.08 0.00 2019-07-15 2019-07-20 2019-08-24 2020-02-20 / Easy Fit software and Planning System ementation NHP-2019-2020-NIH-811947 Water Resources Operations Request for Quota Single Stage - One E IBRD / 87250 Post Limited 538.46 376.96 Completed 2019-07-06 2019-09-30 2019-08-31 2019-10-05 2020-02-27 2019-11-15 / Camera and Planning System tions nvelope NHP-2019-2020-NIH-837552 Water Resources Operations Request for Quota Single Stage - One E / Soil Moisture Profile Probe IBRD / 87250 Post Limited 7,692.31 5,780.83 Completed 2019-07-06 2019-07-29 2019-08-31 2019-09-17 2020-02-27 2019-11-26 and Planning System tions nvelope with Moisture Meter NHP-2019-2020-NIH-319115 Water Resources Operations Request for Quota Single Stage - One E / Desktop Computer (2 nos.), IBRD / 87250 Post Limited 3,461.54 1,655.42 Completed 2019-06-20 2020-01-21 2019-08-15 2020-02-24 2020-02-11 2020-04-20 and Planning System tions nvelope Laptop (1 no.), Printer (1 no.) NHP-2019-2020-NIH-600812 Water Resources Operations Request for Quota Single Stage - One E IBRD / 87250 Post Limited 3,846.15 3,077.52 Completed 2019-07-06 2019-08-05 2019-08-31 2019-10-17 2020-02-27 2020-02-10 / Weighing Balance (1 no.) and Planning System tions nvelope NHP-2019-2020-NIH-857197 Water Resources Operations Pending Impl IBRD / 87250 Post Direct Selection Direct 307.69 0.00 2019-07-01 2019-07-06 2019-08-10 2020-02-06 / Books and Planning System ementation NHP-2019-2020-NIH-346350 / Toposheets/Satellite Data/M Water Resources Operations Pending Impl IBRD / 87250 Post Direct Selection Direct 33,076.92 0.00 2019-07-15 2019-07-20 2019-08-24 2020-02-20 eteorological Data/Geological and Planning System ementation Data/Soil Data Page 4 IN-NIH ROORKEE-152603-GO Water Resources Operations -DIR / GeoChemist Work Ben IBRD / 87250 Post Direct Selection Direct 10,769.23 8,999.00 Completed 2020-03-15 2019-09-26 2020-03-20 2020-04-28 2020-04-24 2020-06-11 2020-10-21 2020-06-11 and Planning System ch Software IN-NIH ROORKEE-152604-GO Water Resources Operations Pending Impl -DIR / Visual Modflow Flex So IBRD / 87250 Post Direct Selection Direct 9,230.77 0.00 2020-03-15 2020-03-20 2020-04-24 2020-10-21 and Planning System ementation ftware (2 nos.) IN-NIH ROORKEE-152605-GO Water Resources Operations Pending Impl IBRD / 87250 Post Direct Selection Direct 1,076.92 0.00 2020-03-15 2020-03-20 2020-04-24 2020-10-21 -DIR / Surfer Software and Planning System ementation IN-NIH ROORKEE-152606-GO Water Resources Operations Pending Impl IBRD / 87250 Post Direct Selection Direct 2,692.31 0.00 2020-03-15 2020-03-20 2020-04-24 2020-10-21 -DIR / Visual HELP Software and Planning System ementation IN-NIH ROORKEE-152609-GO Water Resources Operations Request for Quota Single Stage - One E -RFQ / Temp. Level Conductiv IBRD / 87250 Post Limited 6,153.85 3,140.93 Signed 2020-03-20 2020-10-06 2020-05-15 2021-01-29 2020-11-11 and Planning System tions nvelope ity (TLC) Meter IN-NIH ROORKEE-152610-GO Water Resources Operations Request for Quota Single Stage - One E Pending Impl IBRD / 87250 Post Limited 1,230.77 0.00 2020-03-20 2020-05-15 2020-11-11 -RFQ / Laptop and Planning System tions nvelope ementation IN-NIH ROORKEE-152611-GO Water Resources Operations Request for Quota Single Stage - One E Pending Impl IBRD / 87250 Post Limited 1,538.46 0.00 2020-03-13 2020-05-08 2020-11-04 -RFQ / Desktop PC; Colour La and Planning System tions nvelope ementation ser Printer IN-NIH ROORKEE-152612-GO Water Resources Operations Request for Quota Single Stage - One E IBRD / 87250 Post Limited 1,923.08 1,587.31 Completed 2020-03-17 2020-06-10 2020-05-12 2020-06-10 2020-11-08 2020-07-17 -RFQ / Desktop PC; Colour La and Planning System tions nvelope ser Printer IN-NIH ROORKEE-152613-GO Water Resources Operations Request for Quota Single Stage - One E IBRD / 87250 Post Limited 2,307.69 1,148.67 Completed 2020-04-12 2020-06-23 2020-06-07 2020-07-07 2020-12-04 2020-09-09 -RFQ / Desktop PC; Colour La and Planning System tions nvelope ser Printer IN-NIH ROORKEE-152916-GO Water Resources Monitoring Open - Internationa Single Stage - Two E -RFB / Triple Quadrupole Gas IBRD / 87250 Post Request for Bids 153,846.15 137,997.88 Signed 2020-01-19 2020-05-26 2020-03-08 2020-05-27 2020-04-19 2020-07-17 2020-07-02 2020-10-09 2020-08-06 2020-10-19 2021-02-02 System l nvelope -Chromatograph Mass Spectr ophotometer IN-NIH ROORKEE-170210-GO Water Resources Operations Request for Quota Single Stage - One E Pending Impl IBRD / 87250 Post Limited 4,615.38 0.00 2020-03-22 2020-05-17 2020-11-13 -RFQ / Desktop Workstation and Planning System tions nvelope ementation IN-NIH ROORKEE-501428-GO Water Resources Operations Pending Impl IBRD / 87250 Post Direct Selection Direct 384.62 0.00 2020-03-17 2020-03-22 2020-04-26 2020-10-23 -DIR / Hydrus 3D Standard and Planning System ementation IN-NIH ROORKEE-953662-GO Water Resources Monitoring Request for Quota Single Stage - One E IBRD / 87250 Post Limited 923.08 602.45 Completed 2020-03-22 2020-01-03 2020-05-17 2020-01-03 2020-11-13 2020-02-11 -RFQ / Projector System tions nvelope IN-NIH ROORKEE-477459-GO Water Resources Operations Pending Impl -DIR / Hydrogeoanalyst & Vis IBRD / 87250 Post Direct Selection Direct 1,769.23 0.00 2020-03-17 2020-03-22 2020-04-26 2020-10-23 and Planning System ementation ual Modflow Flex Professional IN-NIH ROORKEE-182039-GO Water Resources Operations Request for Quota Single Stage - One E IBRD / 87250 Post Limited 1,385.00 1,079.48 Completed 2020-07-06 2020-08-20 2020-08-31 2020-08-20 2021-02-27 2020-11-19 -RFQ / Laptop (1 no.) and Planning System tions nvelope IN-NIH ROORKEE-182041-GO Water Resources Operations Request for Quota Single Stage - One E IBRD / 87250 Post Limited 2,307.69 1,075.02 Completed 2020-07-10 2020-09-15 2020-09-04 2020-09-15 2021-03-03 2021-02-11 -RFQ / Laptop Workstation and Planning System tions nvelope IN-NIH ROORKEE-182043-GO Water Resources Operations Request for Quota Single Stage - One E IBRD / 87250 Post Limited 769.23 770.82 Completed 2020-07-05 2020-09-07 2020-08-30 2021-01-29 2021-02-26 2021-03-08 -RFQ / Suction Lysimeter and Planning System tions nvelope IN-NIH ROORKEE-182045-GO Water Resources Operations Request for Quota Single Stage - One E Pending Impl -RFQ / Cooling Cabinet Refrig IBRD / 87250 Post Limited 2,769.23 0.00 2020-07-06 2020-08-31 2021-02-27 and Planning System tions nvelope ementation erator for Laboratory IN-NIH ROORKEE-182046-GO Water Resources Monitoring Single Stage - Two E Under Imple IBRD / 87250 Post Request for Bids Open - National 138,461.54 0.00 2020-07-06 2021-02-25 2020-07-11 2020-09-02 2020-08-22 2021-03-26 2020-11-04 2021-09-22 2020-12-09 2021-06-07 -RFB / FTIR Microscope System nvelope mentation IN-NIH ROORKEE-182048-GO Water Resources Operations Request for Quota Single Stage - One E -RFQ / Soil Moisture Meter wit IBRD / 87250 Post Limited 12,307.69 2,924.81 Completed 2020-07-13 2020-09-17 2020-09-07 2021-01-29 2021-03-06 2021-08-11 and Planning System tions nvelope h Datalogger (2 nos.) IN-NIH ROORKEE-182051-GO Water Resources Operations Request for Quota Single Stage - One E Pending Impl IBRD / 87250 Post Limited 3,846.15 0.00 2020-07-10 2020-09-04 2021-03-03 -RFQ / Raingauges (6 nos.) and Planning System tions nvelope ementation IN-NIH ROORKEE-182053-GO Water Resources Operations Request for Quota Single Stage - One E IBRD / 87250 Post Limited 10,769.23 3,421.89 Completed 2020-07-19 2020-09-23 2020-09-13 2021-01-29 2021-03-12 2021-06-09 -RFQ / Multiparameter Sonde and Planning System tions nvelope (2 nos.) IN-NIH ROORKEE-182033-GO Water Resources Operations IBRD / 87250 Post Direct Selection Direct 2,307.69 1,808.80 Completed 2020-07-15 2020-07-07 2020-07-20 2020-07-13 2020-08-24 2020-08-24 2021-02-20 2020-11-09 -DIR / AquaChem Software and Planning System IN-NIH ROORKEE-182035-GO Water Resources Operations -DIR / Watershed Modelling S IBRD / 87250 Post Direct Selection Direct 8,461.54 3,460.00 Completed 2020-07-15 2020-06-19 2020-07-20 2020-07-03 2020-08-24 2020-08-24 2021-02-20 2020-11-06 and Planning System ystem (Premium) Software IN-NIH ROORKEE-189421-GO Water Resources Operations IBRD / 87250 Post Direct Selection Direct 6,153.85 5,383.33 Completed 2020-08-30 2020-08-06 2020-09-04 2020-08-21 2020-10-09 2020-09-21 2021-04-07 2020-11-23 -DIR / Rockworks Software (0 and Planning System 1 No.) IN-NIH ROORKEE-189422-GO Water Resources Operations IBRD / 87250 Post Direct Selection Direct 3,846.15 3,230.00 Completed 2020-08-30 2020-03-11 2020-09-04 2020-07-21 2020-10-09 2020-09-17 2021-04-07 2020-11-11 -DIR / HYDRUS 3D Software ( and Planning System 01 No.) IN-NIH ROORKEE-189423-GO Water Resources Operations -DIR / Visual MODFLOW Flex IBRD / 87250 Post Direct Selection Direct 21,538.46 15,932.10 Completed 2020-08-30 2020-08-28 2020-09-04 2020-09-07 2020-10-09 2021-01-21 2021-04-07 2021-02-25 and Planning System Premium Software (03 Nos.) IN-NIH ROORKEE-189428-GO Water Resources Operations Request for Quota Single Stage - One E IBRD / 87250 Post Limited 923.08 741.45 Completed 2020-09-04 2020-07-08 2020-10-30 2020-07-08 2021-04-28 2020-09-04 -RFQ / Colour Laser Printer (0 and Planning System tions nvelope 1 No.) IN-NIH ROORKEE-189429-GO Water Resources Operations Request for Quota Single Stage - One E Pending Impl -RFQ / Digital Water Level Re IBRD / 87250 Post Limited 15,384.62 0.00 2020-09-04 2020-10-30 2021-04-28 and Planning System tions nvelope ementation corder for GW Level Monitori ng (10 nos.) IN-NIH ROORKEE-206167-GO Institutional Capacity Enhan Request for Quota Single Stage - One E IBRD / 87250 Post Limited 6,153.85 5,147.75 Completed 2020-12-06 2017-03-21 2021-01-31 2017-06-21 2021-07-30 2017-08-21 -RFQ / Furniture Items cement tions nvelope Page 5 IN-NIH ROORKEE-252750-GO -DIR / ArcGIS Enterprise Adva nced (4 Core) 10.8 with Porta Water Resources Monitoring l for ArcGIS Jump Start Packa IBRD / 87250 Post Direct Selection Direct 140,180.00 108,676.30 Signed 2021-09-20 2021-08-03 2021-09-25 2021-10-04 2021-10-30 2021-12-27 2022-04-28 System ge (1 no.); ArcGIS Desktop A dvanced 10.8 (1 no.); ArcGIS Desktop Extension-Spatial An alyst 10.8 (1 no.) IN-NIH ROORKEE-252758-GO Water Resources Operations Request for Quota Single Stage - One E IBRD / 87250 Post Limited 6,000.00 4,345.29 Completed 2021-09-25 2021-08-13 2021-11-20 2021-08-13 2022-05-19 2022-01-12 -RFQ / Workstation (1 no.) and Planning System tions nvelope IN-NIH ROORKEE-252765-GO Institutional Capacity Enhan Request for Quota Single Stage - One E IBRD / 87250 Post Limited 2,615.00 1,872.44 Completed 2021-09-20 2021-08-13 2021-11-15 2021-08-13 2022-05-14 2021-09-20 -RFQ / Computer Hardware cement tions nvelope IN-NIH ROORKEE-273999-GO Water Resources Operations Request for Quota Single Stage - One E IBRD / 87250 Post Limited 1,107.69 753.83 Signed 2022-02-06 2022-03-23 2022-04-03 2022-03-23 2022-09-30 -RFQ / Desktop PC (01 No.) and Planning System tions nvelope IN-NIH ROORKEE-274001-GO -RFQ / Tower Server (01 No.); Institutional Capacity Enhan Request for Quota Single Stage - One E IBRD / 87250 Post Limited 35,400.00 19,983.32 Signed 2022-02-06 2022-02-21 2022-04-03 2022-07-08 2022-09-30 Windows Server Data Centre cement tions nvelope (01 No.); Desktop Computer with UPS (01 No.) IN-NIH ROORKEE-282707-GO Institutional Capacity Enhan Request for Quota Single Stage - One E Pending Impl IBRD / 87250 Post Limited 6,164.38 0.00 2022-03-19 2022-05-14 2022-11-10 -RFQ / Furniture Items cement tions nvelope ementation IN-NIH ROORKEE-321036-GO -RFB / Procurement of Fourie Water Resources Monitoring Single Stage - Two E Under Imple IBRD / 87250 Post Request for Bids Open - National 164,383.56 0.00 2022-11-01 2023-03-20 2022-11-06 2023-03-20 2022-12-18 2023-03-02 2023-04-06 2023-10-03 r Transform Infra Spectrosco System nvelope mentation py (FTIR Microscope) IN-NIH ROORKEE-352330-GO Water Resources Monitoring Open - Internationa Single Stage - Two E Pending Impl -RFB / Procurement of Dual I IBRD / 87250 Post Request for Bids 479,452.05 0.00 2023-04-07 2023-04-12 2023-05-24 2023-08-06 2023-09-10 2024-03-08 System l nvelope ementation nlet Isotope Ratio Mass Spect rometer (1 No.) IN-NIH ROORKEE-353749-GO Institutional Capacity Enhan Request for Quota Single Stage - One E Pending Impl -RFQ / Procurement of Works IBRD / 87250 Post Limited 6,849.32 0.00 2023-04-05 2023-05-31 2023-11-27 cement tions nvelope ementation tation (1 No.) NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NHP-2018-2019-NIH-476036 Water Resources Operations -NC-DC-DC / Social Survey fo IBRD / 87250 Post Direct Selection Direct 5,384.62 4,717.20 Completed 2018-10-15 2018-10-15 2018-10-20 2018-10-25 2018-11-24 2019-04-01 2019-05-23 2020-01-31 and Planning System r Salinity Impact Assessment NHP-2019-2020-NIH-766282 Water Resources Operations Request for Quota Single Stage - One E Pending Impl / Outsourcing Cost for Water IBRD / 87250 Post Limited 2,307.69 0.00 2019-07-06 2019-08-31 2020-02-27 and Planning System tions nvelope ementation Quality Sample Analysis IN-NIH ROORKEE-182037-NC Water Resources Operations Request for Quota Single Stage - One E -RFQ / Outsourcing for Devel IBRD / 87250 Post Limited 7,692.31 4,281.08 Signed 2020-07-06 2021-03-25 2020-08-31 2021-09-16 2021-02-27 and Planning System tions nvelope opment of Web-based/Mobile Application IN-NIH ROORKEE-182040-C Water Resources Operations Request for Quota Single Stage - One E Pending Impl IBRD / 87250 Post Limited 3,846.15 0.00 2020-07-24 2020-09-18 2021-03-17 W-RFQ / Geophysical Survey and Planning System tions nvelope ementation CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IN-NIH ROORKEE-152616-CS -FBS / Consultancy for Devel Water Resources Operations Fixed Budget Sele Under Implement opment of web-based dynam IBRD / 87250 Post Open - National 15,384.62 0.00 2020-03-15 2020-08-24 2020-04-05 2020-05-19 2020-06-16 2020-07-16 2020-08-20 2020-09-24 2021-09-24 and Planning System ction ation ic IT Framework for Evaluatio n of performance of projects INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IN-NIH ROORKEE-64834-CS- CDS / Decision Support Syste m (Planning & Management). It is continuation of the earlie Institutional Capacity Enhan Under Implement r DSS(P) developed under th IBRD / 87250 Post Direct Selection Direct 690,000.00 0.00 2018-07-16 2018-07-26 2018-09-29 2019-03-28 cement ation e HP-II. It is basically require d to strengthen the earlier D SS(P) and provide simpler int erface for increased and wid er applicability by IAs. NHP-2018-2019-NIH-622791 -CS-SSS-SSS / DSS for River B Water Resources Operations IBRD / 87250 Post Direct Selection Direct 615,384.62 552,999.68 Signed 2018-10-15 2018-10-15 2018-10-25 2019-02-01 2018-12-29 2019-07-18 2019-06-27 asins (Ravi, Nagvali, Periyar, and Planning System Pennar, & Bhadar) NHP-2019-2020-NIH-472675 Water Resources Operations Pending Impleme / Super Resolution Modelling IBRD / 87250 Post Direct Selection Direct 2,307.69 0.00 2019-07-01 2019-07-11 2019-09-14 2020-03-12 and Planning System ntation of Satellite Data IN-NIH ROORKEE-182049-CS Water Resources Operations Pending Impleme -CDS / Outsourcing GIS Base IBRD / 87250 Post Direct Selection Direct 6,153.85 0.00 2020-07-19 2020-07-29 2020-10-02 2021-03-31 and Planning System ntation d Desertification IN-NIH ROORKEE-202967-CS -CDS / Hiring of Consultant fo Water Resources Operations Under Implement r Hydro-geological Investigati IBRD / 87250 Post Direct Selection Direct 6,692.31 0.00 2020-11-15 2020-02-19 2020-11-25 2021-01-29 2021-07-28 and Planning System ation on for identification of possibl e recharge area (springshed) of selected springs Page 6