PROCUREMENT PLAN (Textual Part) Project information: NIGER Rural Mobility and Connectivity P164498 Project Implementation agency: PGRC-DU Date of the Procurement Plan: 28 JANUARY 2018 Period covered by this Procurement Plan: 1/1/2018-12/31/2018 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in [insert appropriate references to the national procurement legislation], such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. List only the applicable conditions required to ensure consistency with paragraph 5.4 of the Procurement Regulations. If no conditions apply, delete the phrase “and the following conditions”. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. Otherwise state “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables Otherwise state “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Specify for each Goods: [is not applicable/is applicable for those contracts identified in the Procurement Plan tables]; Works: [is not applicable/is applicable for those contracts identified in the Procurement Plan tables] Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations is Applicable. [Include this sentence only if the Bank has formally agreed to provide the Borrower with HEIS. Otherwise delete] Other Relevant Procurement Information. Provide any other relevant procurement information such as procedures for CDD components, Procurement in Situations of Urgent Need of Assistance or Capacity Constraints etc. PROCUREMENT Niger : Rural Mobility and Connectivity Project PLAN General Information Country: Niger 2018-02-13 Bank’s Approval Date of the Original Procurement Plan: 2023-03-28 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P164498 GPN Date: 2018-02-01 Project Name: Rural Mobility and Connectivity Project Loan / Credit No: / , IDA / V1420, IDA / 63850 Niger Rural Mobility and Connectivity Executing Agency(ies): WORKS Activity Reference No. / Procureme Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH Ri Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method nt Docume ount (US$ and Recommendation Signed Contract o. h cess (Y/N) sk atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion nt Type ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NE-PADEZA-102388-CW-RFB Improvement of rural transp Open - Internationa Single Stage - One E 8,869,849.4 2021-01-2 / Travaux d'aménagement de IDA / 63850 A posteriori Appel d'offres Signé 2019-04-04 2019-04-03 2019-04-09 2019-04-16 2019-05-21 2019-06-10 2019-06-20 2019-09-10 2019-07-25 2020-03-17 ort infrastructure l nvelope 6 0 175,96 km de routes revêtue s 1ère phase NE-PMRC-142596-CW-RFB / Travaux d’aménagement de pistes rurales existantes dan Improvement of rural transp Open - Internationa Single Stage - One E 5,742,583.6 2021-07-2 IDA / 63850 A posteriori Appel d'offres Signé 2019-12-08 2019-11-18 2019-12-13 2019-11-18 2020-01-24 2019-12-31 2020-02-23 2020-03-25 2020-03-29 2020-07-16 s les Régions de Dosso, Taho ort infrastructure l nvelope 5 2 ua et Maradi Deuxième Tranc he (142,457 km) de la Premi ère phase NE-PMRC-153373-CW-RFB / Travaux d'aménagement con Improvement of rural transp Single Stage - One E 2020-09-1 nexes villageois pour la 1ère IDA / 63850 A posteriori Appel d'offres Open - National 0.00 Annulé 2020-01-20 2020-01-25 2020-02-24 2020-03-09 2020-04-13 ort infrastructure nvelope 0 phase des travaux d'infrastru ctures routières du PMRC Demande de NE-PADEZA-349271-GO-RFB cotations (DT / Fourniture et pose de 24 la Improvement of rural transp Single Stage - One E En attente d 2023-08-0 IDA / 63850 A posteriori Demande de prix Limited PM ne prove 0.00 2023-04-19 2023-06-03 mpadaires solaires dans 6 vil ort infrastructure nvelope 'exécution 2 nant pas de l lages de la région de Dosso a Banque) NE-PADEZA-350795-CW-RFQ Demande de / Réalisation et équipement d cotations (DT Improvement of rural transp Single Stage - One E En attente d 2023-08-0 e 2 forages équipés de poste IDA / 63850 A posteriori Demande de prix Limited PM ne prove 0.00 2023-04-29 2023-06-06 ort infrastructure nvelope 'exécution 5 s d'eau autonomes solaires ( nant pas de l 1 Guidan Oumarou,1 Garin G a Banque) ao ) Demande de NE-PADEZA-350800-CW-RFQ cotations (DT / Fourniture et pose de 16 la Improvement of rural transp Single Stage - One E En attente d 2023-08-0 IDA / 63850 A posteriori Demande de prix Limited PM ne prove 0.00 2023-04-19 2023-06-03 mpadaires solaires dans 4 vil ort infrastructure nvelope 'exécution 2 nant pas de l lages de la région de Maradi a Banque) Demande de NE-PADEZA-350801-CW-RFQ cotations (DT / Fourniture et pose de 24 la Improvement of rural transp Single Stage - One E En attente d 2023-08-0 IDA / 63850 A posteriori Demande de prix Limited PM ne prove 0.00 2023-04-19 2023-06-03 mpadaires solaires dans 6 vil ort infrastructure nvelope 'exécution 2 nant pas de l lages de la région de Tahoua a Banque) NE-PADEZA-350804-CW-RFQ Demande de / Construction 2 murs de clôt cotations (DT Improvement of rural transp Single Stage - One E En attente d 2023-08-1 ure et 2 blocs de latrines dan IDA / 63850 A posteriori Demande de prix Limited PM ne prove 0.00 2023-04-25 2023-06-13 ort infrastructure nvelope 'exécution 2 s les villages de Dogonkiria e nant pas de l t Gaouna dans le cadre des tr a Banque) avaux connexes NE-PADEZA-350809-CW-RFQ Demande de / Réalisation et équipement d cotations (DT Improvement of rural transp Single Stage - One E En attente d 2023-08-2 e 2 forages équipés de poste IDA / 63850 A posteriori Demande de prix Limited PM ne prove 0.00 2023-04-29 2023-06-24 ort infrastructure nvelope 'exécution 3 s d'eau autonomes solaires ( nant pas de l 1 ASKIA ,1 Garin Gado Chawe a Banque) ye,) NE-PADEZA-351191-CW-RFQ Demande de / Construction 2 murs de clôt cotations (DT ure et 2 blocs de latrines dan Improvement of rural transp Single Stage - One E En attente d 2023-06-2 IDA / 63850 A posteriori Demande de prix Limited PM ne prove 0.00 2023-04-10 2023-05-18 s les villages de Toudoun Ga ort infrastructure nvelope 'exécution 7 nant pas de l o et de Makera Doubalma d a Banque) ans le cadre des travaux con nexe GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NE-PADEZA-52759-GO-RFQ / Fourniture et installation de Operational support for the Single Stage - One E En attente d' IDA / V1420 A posteriori Demande de prix Limited 0.00 2018-03-20 2018-05-15 2018-11-11 matériels informatiques, logi Project nvelope exécution ciels et accessoires NE-PADEZA-106735-GO-RFQ / Acquisition et installation d' Operational support for the Single Stage - One E En attente d' IDA / V1420 A posteriori Demande de prix Limited 0.00 2019-03-28 2019-05-23 2019-06-22 une licence TOMPRO incluant Project nvelope exécution le paramétrage et la formatio n des utilisateurs NE-PMRC-133863-GO-RFQ / Operational support for the Single Stage - One E Acquisition des mobiliers de IDA / 63850 A posteriori Demande de prix Limited 33,733.78 Signé 2019-10-05 2019-11-13 2019-11-16 2019-12-17 2020-01-15 Project nvelope bureau et équipements infor matiques NE-PMRC-133971-GO-RFQ / Operational support for the Single Stage - One E Acquisition d'un groupe élect IDA / 63850 A posteriori Demande de prix Limited 30,396.61 Signé 2019-10-05 2019-11-13 2019-11-30 2020-01-14 2019-12-06 Project nvelope rogène pour l'UCP NE-PMRC-133984-GO-RFQ / Operational support for the Single Stage - One E Aquisition d'un vehicule Pick IDA / 63850 A posteriori Demande de prix Limited 47,791.96 Signé 2019-10-05 2019-11-13 2019-11-30 2019-12-13 2020-02-28 Project nvelope Up pour l'UCP NE-PMRC-159705-GO-RFQ / Operational support for the Single Stage - One E Acquisition d'une Station Wa IDA / 63850 A posteriori Demande de prix Limited 97,693.76 Signé 2020-03-07 2020-04-23 2020-05-02 2020-05-04 2020-07-01 Project nvelope gon V8 pour UCP/PMRC NE-PADEZA-185850-GO-RFQ / Acquisition d'un véhicule Pi Operational support for the Single Stage - One E IDA / 63850 A posteriori Demande de prix Limited 49,673.90 Signé 2020-08-22 2020-10-09 2020-10-17 2020-12-01 2021-01-15 ck Up au profit du Bureau Na Project nvelope tional des Evaluations Enviro nnementales Page 1 NE-PMRC-230019-GO-RFQ / Operational support for the Single Stage - One E Acquisition d'un véhicule Pick IDA / 63850 A posteriori Demande de prix Limited 45,558.01 Signé 2021-05-16 2021-07-07 2021-06-20 2021-08-17 2021-08-19 Project nvelope Up pour l'UCP NE-PMRC-153380-GO-RFQ / Acquisition des petits matéri Single Stage - One E IDA / 63850 Rural road maintenance A posteriori Demande de prix Limited 0.00 Annulé 2020-01-25 2020-03-17 2020-06-15 els d'entretien pour la 1ère p nvelope hase des travaux d'infrastruc tures routières du PMRC NE-PMRC-282246-GO-RFB / Improvement of rural transp Single Stage - One E En attente d' Fourniture et pose des lampa IDA / 63850 A posteriori Appel d'offres Open - National 0.00 2022-12-26 2022-12-31 2023-01-30 2023-02-14 2023-03-14 2023-05-13 ort infrastructure nvelope exécution daires dans le cadre des trav aux connexes NE-PADEZA-349282-GO-RFQ / Acquisition des petits matér iels d'entretien pour la 1ère p Single Stage - One E En attente d' hase des travaux d'infrastruc IDA / 63850 Rural road maintenance A posteriori Demande de prix Limited 0.00 2023-04-22 2023-06-17 2023-08-16 nvelope exécution tures routières du PMRC pour les 2 tronçons de Guidan Rou mdji-Guidan Sory et Moullé-D ankano NE-PADEZA-350805-GO-RFQ / Acquisition des petits matér iels d'entretien pour la 1ère p Single Stage - One E En attente d' hase des travaux d'infrastruc IDA / 63850 Rural road maintenance A posteriori Demande de prix Limited 0.00 2023-04-22 2023-06-17 2023-08-16 nvelope exécution tures routières du PMRC pour les 2 tronçons de Tasha Dag na-Lougou et Bagagi-Soucou coutane NE-PADEZA-350806-GO-RFQ / Acquisition des petits matér iels d'entretien pour la 1ère p Single Stage - One E En attente d' hase des travaux d'infrastruc IDA / 63850 Rural road maintenance A posteriori Demande de prix Limited 0.00 2023-04-22 2023-06-17 2023-08-16 nvelope exécution tures routières du PMRC pour les 2 tronçons de Kiota-Koulb ou et Harikanassou- Louloudj é NE-PADEZA-350807-GO-RFQ / Acquisition des petits matér iels d'entretien pour la 1ère p Single Stage - One E En attente d' IDA / 63850 Rural road maintenance A posteriori Demande de prix Limited 0.00 2023-04-22 2023-06-17 2023-08-16 hase des travaux d'infrastruc nvelope exécution tures routières du PMRC pour le tronçon de Kouran Mota - Dangoma NE-PADEZA-350808-GO-RFQ / Acquisition des petits matér iels d'entretien pour la 1ère p Single Stage - One E En attente d' IDA / 63850 Rural road maintenance A posteriori Demande de prix Limited 0.00 2023-04-22 2023-06-17 2023-08-16 hase des travaux d'infrastruc nvelope exécution tures routières du PMRC pour les 2 tronçons de Tsaouna-In kikaram et Ichirifan-Bagaré NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NE-PADEZA-47196-CS-QCBS / Etudes techniques (APS, AP Sélection fondée s Open - Internationa En cours d'exame D et DAO) pour la réalisation / A posteriori ur la qualité et le 0.00 2018-02-01 2018-02-14 2018-02-22 2018-04-07 2018-05-05 2018-06-04 2018-07-09 2018-08-13 2019-08-13 l n de 300 km de pistes dans les coût Région de Dosso, Tahoua et Maradi NE-PADEZA-47198-CS-CQS / Elaboration cadre de gestion environnementale et sociale Sélection fondée s (CGES), du cadre de politique En cours d'exame / A posteriori ur les qualification Open - National 0.00 2018-02-01 2018-02-14 2018-02-22 2018-04-07 2018-05-07 2018-06-11 2018-12-08 de réinstallation des populati n s des consultants ons (CPRP), de l'étude d'impa ct environnemental et social (EIES) et du Plan d'action de réinstallation (PAR) NE-PADEZA-106555-CS-QCB S / Firme pour le suivi et le c Sélection fondée s Improvement of rural transp Open - Internationa ontrôle des travaux d'aména IDA / 63850 A posteriori ur la qualité et le 450,068.06 Signé 2019-04-15 2019-04-12 2019-05-06 2019-05-23 2019-06-19 2019-07-03 2019-07-17 2020-03-09 2019-08-16 2020-03-09 2019-09-20 2020-04-16 2019-10-25 2020-07-13 2021-04-17 ort infrastructure l gement des routes rurales po coût ur la 1ère tranche de la 1ère phase. NE-PADEZA-114723-CS-CDS / Sélection de l'ONG spécialis Sélection fondée s Open - Internationa ée pour fournir des services IDA / 63850 Rural road maintenance A priori ur la qualité et le 591,278.29 Signé 2019-06-03 2019-06-15 2019-06-24 2019-07-18 2019-07-15 2019-11-04 2019-07-20 2019-12-13 2019-08-03 2019-12-31 2019-08-22 2020-05-15 2019-09-26 2020-06-03 2023-09-05 l multisectoriels de prévention coût et de réponse à la Violence B asée sur le Genre NE-PADEZA-116888-CS-LCS Operational support for the Sélection au moin / Audit financier et comptabl IDA / 63850 A posteriori Open - National 27,253.35 Signé 2019-06-17 2019-07-09 2019-07-08 2019-08-23 2019-07-29 2019-10-17 2019-08-03 2019-12-10 2019-08-10 2019-12-13 2019-08-29 2020-01-20 2019-10-03 2020-05-27 2020-01-31 Project dre coût e des trois premiers exercice s+PPA NE-PADEZA-139190-CS-CQS / Recrutement d'une ONG po Sélection fondée s ur la sensibilisation des popul Improvement of rural transp En cours d'exécut IDA / 63850 A posteriori ur les qualification Open - National 0.00 2019-09-30 2020-03-02 2019-10-21 2020-12-17 2019-12-04 2021-03-08 2020-01-03 2021-05-12 2020-02-07 2021-07-31 ations des villages traversés ort infrastructure ion s des consultants par les tronçons de la 1ère tr anche du PMRC dans le cadr e de la sécurité routière NE-PMRC-142588-CS-QCBS / Contrôle et surveillance des t Sélection fondée s ravaux d’aménagement de pi Improvement of rural transp Open - Internationa IDA / 63850 A posteriori ur la qualité et le 328,954.76 Signé 2019-11-01 2019-11-03 2019-11-16 2019-12-14 2019-12-24 2019-12-18 2020-03-17 2020-01-01 2020-03-26 2020-01-20 2020-04-30 2020-02-24 2020-07-13 2021-06-18 stes rurales existantes dans l ort infrastructure l coût es régions de Dosso, Tahoua et Maradi, première phase – deuxième tranche du PMRC NE-PMRC-153384-CS-CQS / Recrutement d'une ONG pou Sélection fondée s Improvement of rural transp r la sécurité routière dans les IDA / 63850 A posteriori ur les qualification Open - National 291,320.14 Signé 2020-01-20 2020-07-29 2020-02-10 2020-12-17 2020-03-18 2021-03-08 2020-04-01 2021-05-12 2020-05-06 2021-06-04 2021-10-28 ort infrastructure cadre de la 2ème tranche, 1 s des consultants ère phase des travaux Page 2 NE-PMRC-153370-CS-CQS / Recrutement d'un consultan Sélection fondée s t firme pour les études techni Improvement of rural transp En cours d'exécut IDA / 63850 A posteriori ur les qualification Open - National 0.00 2020-01-20 2023-01-08 2020-02-03 2020-02-24 2020-02-25 2020-03-11 2020-11-06 ques et contrôle des travaux ort infrastructure ion s des consultants d'aménagement connexes vil lageois 1ère phase des trava ux NE-PMRC-153377-CS-QCBS / Sélection fondée s Etudes Techniques pour la 2è Improvement of rural transp Open - Internationa IDA / 63850 A posteriori ur la qualité et le 220,131.21 Signé 2020-06-14 2020-06-22 2020-07-05 2020-08-27 2020-07-19 2020-12-08 2020-08-02 2021-03-09 2020-09-01 2021-09-07 2020-09-22 2022-01-10 2020-10-27 2022-02-23 2021-01-10 me phase des travaux d'infra ort infrastructure l coût structures routières du PMRC NE-PMRC-159715-CS-CQS / Audit de Sécurité Routière du Sélection fondée s Improvement of rural transp corridor dont diagnostic socia IDA / 63850 A posteriori ur les qualification Open - National 0.00 Annulé 2020-03-02 2020-03-23 2020-04-20 2020-05-20 2020-06-17 2020-08-16 ort infrastructure ux économique et comporte s des consultants mental des accidents sur le c orridor (Régional) NE-PMRC-159702-CS-CQS / E tude pour la mise en place d' Sélection fondée s Improvement of rural transp un système d'information int IDA / 63850 A posteriori ur les qualification Open - National 0.00 Annulé 2020-03-16 2020-04-06 2020-04-20 2020-05-04 2020-06-01 2020-07-31 ort infrastructure elligent pour le Projet Corrido s des consultants r Régional Lomé - Ouaga - Ni amey NE-PMRC-139184-CS-QCBS / Sélection fondée s Mise à jour de l’APD, étude é Improvement of rural transp Open - Internationa IDA / 63850 A posteriori ur la qualité et le 0.00 Annulé 2019-10-21 2019-11-12 2019-11-04 2019-11-25 2019-12-25 2020-01-01 2020-01-22 2020-02-19 2020-08-17 conomique et DAO pour tous ort infrastructure l coût les tronçons (y compris la se ction manquante) NE-PMRC-145319-CS-QCBS / Etudes concernant la Réhabil Sélection fondée s Improvement of rural transp Open - Internationa itation et l’Entretien du Corri IDA / 63850 A posteriori ur la qualité et le 0.00 Annulé 2019-11-18 2019-11-16 2019-12-02 2019-11-22 2019-12-23 2020-01-22 2020-01-29 2020-02-19 2020-03-18 2020-09-14 ort infrastructure l dor Transsaharien (RN 11 No coût rd) entre Agadez et Zinder NE-PMRC-158223-CS-QCBS / Elaboration d’un plan de dév eloppement socio-économiqu Sélection fondée s Improvement of rural transp Open - Internationa e autour de la section Nigérie IDA / 63850 A posteriori ur la qualité et le 0.00 Annulé 2020-03-31 2020-01-21 2020-04-14 2020-05-05 2020-06-04 2020-06-11 2020-07-02 2020-07-30 2021-04-26 ort infrastructure l nne dans le cadre du projet c coût orridor Trans-saharien sur la route RN 11 Nord entre Tano ut-Tiguidit NE-PMRC-145286-CS-CQS / E Sélection fondée s Improvement of rural transp tudes EIES pour la route Tan IDA / 63850 A posteriori ur les qualification Open - National 0.00 Annulé 2019-11-25 2020-01-10 2019-12-09 2020-01-15 2020-01-29 2020-02-26 2020-03-27 ort infrastructure out - Tiguidit s des consultants NE-PMRC-159721-CS-QCBS / Sélection fondée s Improvement of rural transp Open - Internationa Etude d'évaluation sécuritair IDA / 63850 A posteriori ur la qualité et le 0.00 Annulé 2020-04-20 2020-05-11 2020-06-08 2020-07-06 2020-07-20 2020-08-17 2020-09-21 2020-11-20 ort infrastructure l e du corridor coût NE-PMRC-241538-CS-INDV / Audit environnemental et soc Sélection fondée s ial des carrières ouvertes et Improvement of rural transp En cours d'exécut IDA / 63850 A posteriori ur les qualification Open - National 0.00 2021-11-01 2021-10-25 2021-11-22 2021-11-29 2021-12-13 2022-02-22 2021-12-27 2022-03-31 2022-01-31 2022-03-02 ou exploitées dans le cadre d ort infrastructure ion s des consultants es travaux de la 1ère tranche et la 2ème tranche du PMRC NE-PMRC-260013-CS-CQS / Audit environnemental et soc Sélection fondée s Operational support for the ial des travaux de constructi IDA / 63850 A posteriori ur les qualification Open - National 40,662.87 Signé 2021-12-13 2021-12-02 2022-01-03 2022-02-02 2022-02-01 2022-05-04 2022-02-16 2022-06-23 2022-03-23 2022-07-14 2022-05-07 Project on et réhabilitation des route s des consultants s rurales de la 1ère phase du PMRC NE-PMRC-260594-CS-CQS / Sélection fondée s Operational support for the Audit Technique de la 1ere p IDA / 63850 A posteriori ur les qualification Open - National 78,562.84 Signé 2021-12-13 2021-11-29 2022-01-03 2022-02-02 2022-02-01 2022-04-20 2022-02-16 2022-08-25 2022-03-23 2022-09-15 2022-05-07 Project hase des travaux du PMRC s des consultants NE-PMRC-159695-CS-CQS / E tudes techniques des aména Sélection fondée s Improvement of rural transp gements sociaux et commun IDA / 63850 A posteriori ur les qualification Open - National 0.00 Annulé 2020-04-20 2020-05-11 2020-05-25 2020-05-26 2020-06-23 2020-08-22 ort infrastructure autaires pour le Projet Corrid s des consultants or Régional Lomé - Ouaga - N iamey NE-PMRC-159713-CS-QCBS / Etudes techniques, de l’amé Sélection fondée s nagement des routes en terr Improvement of rural transp Open - Internationa IDA / 63850 A posteriori ur la qualité et le 0.00 Annulé 2020-03-16 2020-07-16 2020-04-06 2020-04-27 2020-05-27 2020-06-10 2020-07-08 2020-08-12 2021-01-09 es connexes au corridor (174 ort infrastructure l coût km) pour le Projet Corridor R égional Lomé - Ouaga - Niam ey NE-PADEZA-352482-CS-QCB S / Etudes et contrôle des tra Sélection fondée s Improvement of rural transp En cours d'exécut vaux de renforcement des ou IDA / 63850 A posteriori ur la qualité et le Open - National 0.00 2023-04-10 2023-03-28 2023-05-01 2023-06-14 2023-07-12 2023-08-11 2023-09-15 2023-10-20 2024-10-19 ort infrastructure ion vrages de drainage des route coût s de la 1ère phase du PMRC NE-PADEZA-351371-CS-QCB Sélection fondée s S / Audits Comptables et Fina Operational support for the En attente d'exéc IDA / 63850 A posteriori ur la qualité et le Open - National 0.00 2023-08-15 2023-09-05 2023-10-19 2023-11-16 2023-12-16 2024-01-20 2024-02-24 2024-03-04 nciers du PMRC pour les Exer Project ution coût cices 2023, 2024 et 2025 NE-PADEZA-352470-CS-QCB S / Recrutement d'un cabinet Sélection fondée s Improvement of rural transp Open - Internationa En attente d'exéc -Firme pour le contrôle des tr IDA / 63850 A posteriori ur la qualité et le 0.00 2023-04-20 2023-05-11 2023-06-24 2023-07-22 2023-08-21 2023-09-25 2023-10-30 2024-10-29 ort infrastructure l ution avaux de la deuxième phase coût du PMRC dans les régions de Dosso et Tillaberi NE-PADEZA-353030-CS-QCB S / Recrutement d'un cabinet Sélection fondée s Improvement of rural transp Open - Internationa En attente d'exéc -Firme pour le contrôle des tr IDA / 63850 A posteriori ur la qualité et le 0.00 2023-05-08 2023-05-29 2023-07-12 2023-08-09 2023-09-08 2023-10-13 2023-11-17 2024-11-16 ort infrastructure l ution avaux de la deuxième phase coût du PMRC dans les régions de Maradi et de Zinder NE-PADEZA-353035-CS-QCB S / Recrutement d'un cabinet Sélection fondée s Improvement of rural transp Open - Internationa En attente d'exéc -Firme pour le contrôle des tr IDA / 63850 A posteriori ur la qualité et le 0.00 2023-04-20 2023-05-11 2023-06-24 2023-07-22 2023-08-21 2023-09-25 2023-10-30 2024-10-29 ort infrastructure l ution avaux de la deuxième phase coût du PMRC dans la région de T ahoua INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Actual Amount Invitation to Identifie Draft Negotiated Cont Component Review Type Method Contract Type Process Status Teams of Reference Signed Contract Contract Completion Description o. h (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 3 NE-PADEZA-52871-CS-CDS / Sélection de cons Operational support for the Acquisition d'une licence TO IDA / V1420 A priori ultants par entent Direct 0.00 Annulé 2018-06-13 2018-06-23 2018-08-27 2019-02-23 Project MPRO, paramétrage et forma e directe tion NE-PADEZA-52887-CS-INDV / Operational support for the Révision du manuel de procé IDA / V1420 A priori Individuel Limited 0.00 Annulé 2018-03-26 2018-08-27 2018-03-31 2018-04-21 2018-05-26 2018-11-22 Project dures administratives et fina ncière NE-PADEZA-52890-CS-INDV / Operational support for the Recrutement Coordonnateur IDA / V1420 A priori Individuel Open 0.00 Annulé 2018-03-12 2018-07-25 2018-04-30 2018-05-21 2018-06-25 2018-12-22 Project National du Projet NE-PADEZA-52899-CS-INDV / Operational support for the Recrutement Responsable ad IDA / V1420 A priori Individuel Open 0.00 Annulé 2018-03-12 2018-04-30 2018-05-21 2018-06-25 2018-12-22 Project ministratif et Financier du Pr ojet NE-PADEZA-52904-CS-INDV / Operational support for the Recrutement du Spécialiste e IDA / V1420 A priori Individuel Open 0.00 Annulé 2018-03-12 2018-04-30 2018-05-21 2018-06-25 2018-12-22 Project n Passation de Marchés NE-PADEZA-52905-CS-INDV / Operational support for the Recrutement Spécialiste en S IDA / V1420 A priori Individuel Open 0.00 Annulé 2018-03-12 2018-04-30 2018-05-21 2018-06-25 2018-12-22 Project uivi Evaluation NE-PADEZA-52908-CS-INDV / Operational support for the Recrutement Comptable Prin IDA / V1420 A priori Individuel Open 0.00 Annulé 2018-03-12 2018-04-30 2018-05-21 2018-06-25 2018-12-22 Project cipal du Projet NE-PADEZA-106725-CS-CDS Sélection de cons / Elaboration de 7 Plan d'Acti Improvement of rural transp IDA / V1420 A posteriori ultants par entent Direct 23,261.49 Signé 2019-03-28 2019-04-05 2019-04-07 2019-06-01 2019-05-19 2019-08-13 2019-06-18 on de Réinstallation (PAR) de ort infrastructure e directe s routes non revêtues de la 1 ère phase NE-PMRC-133958-CS-INDV / Elaboration des Plans d'Actio Improvement of rural transp IDA / 63850 A posteriori Individuel Limited 35,543.46 Signé 2019-09-30 2019-11-22 2019-10-05 2020-01-14 2019-10-26 2020-04-23 2019-11-30 2020-05-08 2020-01-29 n de Reinstallation complet p ort infrastructure our la route Tanout - Tiguidit NE-PMRC-133961-CS-INDV / Élaboration d'un cadre de ge Improvement of rural transp IDA / 63850 A posteriori Individuel Limited 52,492.00 Signé 2019-09-30 2019-11-09 2019-10-05 2020-01-14 2019-10-26 2020-04-22 2019-11-30 2020-05-07 2020-01-29 stion environnementale et so ort infrastructure ciale (CGES) pour la route Ta nout - Tiguidit NE-PMRC-133981-CS-INDV / Elaboration du Cadre de la P Improvement of rural transp IDA / 63850 A posteriori Individuel Limited 23,744.94 Signé 2019-09-30 2019-11-22 2019-10-05 2021-01-13 2019-10-26 2020-04-23 2019-11-30 2020-05-07 2020-01-29 olitique de Reinstallation po ort infrastructure ur la route Tanout - Tiguidit NE-PMRC-133867-CS-INDV / Elaboration du plan d’engage Improvement of rural transp IDA / 63850 A posteriori Individuel Limited 46,200.00 Signé 2019-09-30 2019-11-22 2019-10-05 2020-02-04 2019-10-26 2020-04-23 2019-11-30 2020-04-22 2020-01-29 ment environnemental et soc ort infrastructure ial pour la route Tanout - Tig uidit NE-PMRC-134033-CS-INDV / Élaboration du plan d’engage Improvement of rural transp ment des parties prenantes e IDA / 63850 A posteriori Individuel Limited 25,127.59 Signé 2019-09-30 2019-11-22 2019-10-05 2020-01-13 2019-10-26 2020-04-23 2019-11-30 2020-05-11 2020-01-29 ort infrastructure t de diffusion de l’information pour la route Tanout - Tiguid it NE-PMRC-134040-CS-INDV / Elaboration d'un cadre de ge Improvement of rural transp IDA / 63850 A posteriori Individuel Limited 35,383.93 Signé 2019-09-30 2019-11-22 2019-10-05 2020-01-13 2019-10-26 2020-04-23 2019-11-30 2020-05-11 2020-01-29 stion des ressources culturell ort infrastructure es physiques (Tanout - Tiguid it) NE-PMRC-134032-CS-INDV / Elaboration d'un plan pour e Improvement of rural transp IDA / 63850 A posteriori Individuel Limited 36,106.88 Signé 2019-09-30 2020-03-27 2019-10-05 2020-04-29 2019-10-26 2020-05-12 2019-11-30 2020-05-29 2020-01-29 mplois et conditions de travai ort infrastructure l (Tanout - Tiguidit) NE-PMRC-133866-CS-INDV / Improvement of rural transp En cours d'exécut Elaboration d'un plan pour la IDA / 63850 A posteriori Individuel Limited 0.00 2019-09-30 2020-03-27 2019-10-05 2019-10-26 2019-11-30 2020-01-29 ort infrastructure ion prévention de la pollution (Ta nout - Tiguidit) NE-PMRC-133973-CS-INDV / Improvement of rural transp Elaboration d'un plan pour la IDA / 63850 A posteriori Individuel Limited 30,374.77 Signé 2019-09-30 2020-03-27 2019-10-05 2020-01-14 2019-10-26 2020-05-15 2019-11-30 2020-06-01 2020-01-29 ort infrastructure santé et sécurité des commu nautés NE-PMRC-134041-CS-INDV / Improvement of rural transp En cours d'exécut Elaboration d'un plan pour l'h IDA / 63850 A posteriori Individuel Limited 0.00 2019-09-30 2020-03-27 2019-10-05 2019-10-26 2019-11-30 2020-01-29 ort infrastructure ion éritage culturel (Tanout - Tig uidit) NE-PMRC-134035-CS-INDV / Recrutement d'un consultant Operational support for the IDA / 63850 A posteriori Individuel Limited 22,360.87 Signé 2019-09-30 2019-11-12 2019-10-05 2019-12-27 2019-10-26 2020-11-03 2019-11-30 2020-11-17 2019-12-30 pour l'élaboration d'un plan d Project e communication NE-PMRC-134073-CS-INDV / Recrutement d'un consultant Improvement of rural transp pour l'élaboration d'un plan s IDA / 63850 A posteriori Individuel Limited 35,314.89 Signé 2019-09-30 2020-03-27 2019-10-05 2020-01-14 2019-10-26 2020-05-19 2019-11-30 2020-06-08 2020-01-29 ort infrastructure ur la biodiversité et ressourc es naturelles (Tanout - Tiguid it) NE-PMRC-134629-CS-INDV / Élaboration d'un plan de gest Improvement of rural transp IDA / 63850 A posteriori Individuel Limited 16,086.02 Signé 2019-09-30 2019-11-09 2019-10-05 2020-01-14 2019-10-26 2020-04-22 2019-11-30 2020-05-07 2019-12-30 ion des pestes et pesticides p ort infrastructure our la route Tanout - Tiguidit NE-PMRC-158214-CS-CDS / E tudes concernant la Réhabilit Sélection de cons Improvement of rural transp En cours d'exécut ation et l’Entretien du Corrid IDA / 63850 A posteriori ultants par entent Direct 0.00 2020-02-11 2019-11-16 2020-02-21 2020-04-19 2020-10-16 ort infrastructure ion or Transaharien (RN 11 Nord) e directe entre Agadez et Zinder NE-PMRC-159719-CS-INDV / Evaluation du système de for Improvement of rural transp mation et d'examen du perm IDA / 63850 A posteriori Individuel Limited 23,710.41 Signé 2020-03-10 2020-03-13 2020-03-15 2020-08-12 2020-04-05 2021-05-24 2020-05-03 2021-06-04 2020-07-02 ort infrastructure is de conduire pour le Projet Corridor Régional Lomé - Oua ga - Niamey Page 4 NE-PMRC-162194-CS-INDV / Recrutement d'un Assistant e Operational support for the IDA / 63850 A posteriori Individuel Limited 19,375.64 Signé 2020-03-17 2020-04-12 2020-03-22 2021-11-19 2020-04-12 2021-11-09 2020-05-17 2021-12-10 2021-05-17 n Passation des Marchés pou Project r le compte du PMRC NE-PMRC-177981-CS-INDV / Improvement of rural transp En cours d'exécut Etudes EIES pour la 2ème Ph IDA / 63850 A posteriori Individuel Limited 0.00 2020-06-14 2021-04-19 2020-06-19 2021-12-13 2020-07-03 2022-08-10 2020-07-31 2020-08-30 ort infrastructure ion ase des travaux du PMRC NE-PADEZA-177984-CS-INDV / Elaboration des Plans d'Acti Improvement of rural transp En cours d'exécut IDA / 63850 A posteriori Individuel Limited 0.00 2020-06-14 2021-04-14 2020-06-19 2021-08-26 2020-06-20 2022-08-10 2020-07-18 2020-09-01 on de Reinstallation complet ort infrastructure ion pour la 2ème Phase des trav aux du PMRC NE-PMRC-162200-CS-CDS / Sélection de cons Operational support for the Recrutement d'un assistant C IDA / 63850 A posteriori ultants par entent Direct 1,246.58 Signé 2020-06-14 2019-09-19 2020-06-24 2019-09-23 2020-07-29 2019-11-01 2021-07-29 Project omptable pour le compte du e directe PMRC NE-PMRC-183469-CS-INDV / Elaboration CGES pour le Proj Improvement of rural transp IDA / 63850 A posteriori Individuel Limited 54,893.43 Signé 2020-07-30 2020-07-30 2020-08-04 2020-09-21 2020-08-25 2020-11-09 2020-09-29 2020-11-20 2020-10-29 et Corridor Régional Lomé - ort infrastructure Ouaga - Niamey NE-PMRC-183473-CS-INDV / Improvement of rural transp Elaboration CPRP pour le Proj IDA / 63850 A posteriori Individuel Limited 40,267.88 Signé 2020-07-30 2020-07-30 2020-08-04 2020-09-21 2020-08-25 2020-11-09 2020-09-29 2020-11-20 2020-10-29 ort infrastructure et Corridor Régional Lomé - Ouaga - Niamey NE-PMRC-183729-CS-INDV / Improvement of rural transp Etude d'évaluation sécuritair IDA / 63850 A posteriori Individuel Limited 23,010.91 Signé 2020-07-30 2020-07-27 2020-08-04 2020-10-13 2020-08-25 2021-03-25 2020-09-22 2021-04-08 2020-11-21 ort infrastructure e du corridor LON NE-PMRC-134039-CS-INDV / Enquête pour l’identification Improvement of rural transp IDA / 63850 A posteriori Individuel Limited 0.00 Annulé 2019-09-30 2020-01-21 2019-10-05 2019-10-26 2019-11-30 2020-01-29 des activités économiques su ort infrastructure r le corridor (Tanout - Tiguidit ) NE-PMRC-194906-CS-INDV / Evaluation des risques et de l Improvement of rural transp a résilience ainsi que des bes IDA / 63850 A posteriori Individuel Limited 8,712.52 Signé 2020-09-30 2020-10-10 2020-10-05 2021-02-03 2020-10-20 2021-03-25 2020-11-04 2021-04-20 2020-11-24 ort infrastructure oins en genre des communau tés le long de l'axe Zinder - A gadez NE-PMRC-210989-CS-INDV / Audit de la mise en œuvre de Improvement of rural transp En cours d'exécut s plans d’actions de Réinstall IDA / 63850 A posteriori Individuel Open 0.00 2021-01-01 2021-01-12 2021-02-19 2021-05-19 2021-03-12 2021-04-02 2021-05-02 ort infrastructure ion ation de la première phase d u Projet de Mobilité Rurale et de Connectivite (PMRC) NE-PMRC-210990-CS-INDV / Improvement of rural transp En cours d'exécut IDA / 63850 A posteriori Individuel Open 0.00 2021-02-01 2021-03-01 2021-03-22 2021-07-29 2021-04-12 2021-09-23 2021-05-03 2021-06-07 Réalisation d'une Cartograp ort infrastructure ion hie VBG NE-PMRC-225056-CS-INDV / Recrutement d’un consultant Operational support for the En cours d'exécut IDA / 63850 A posteriori Individuel Limited 0.00 2021-04-01 2021-04-08 2021-04-06 2021-06-15 2021-04-27 2021-06-21 2021-05-16 2021-08-14 expert en digitalisation pour Project ion appuyer le projet dans l’utilis ation de l’outil KOBO NE-PMRC-233090-CS-INDV / Operational support for the Recrutement d'un Coordonna IDA / 63850 A posteriori Individuel Open 3,525.54 Signé 2021-06-01 2018-06-09 2021-07-05 2018-08-28 2021-07-26 2018-09-05 2021-08-30 2018-10-01 2022-08-30 Project teur National du PMRC NE-PMRC-233092-CS-INDV / Operational support for the Recrutement d'un Spécialiste IDA / 63850 A posteriori Individuel Open 2,578.76 Signé 2021-06-01 2018-06-09 2021-07-05 2018-09-25 2021-07-26 2018-10-08 2021-08-30 2019-02-01 2022-08-30 Project en Passation des Marchés du PMRC NE-PMRC-258222-CS-INDV / Evaluation de risques sécurit Improvement of rural transp IDA / 63850 A posteriori Individuel Limited 28,788.45 Signé 2021-11-01 2021-10-26 2021-11-06 2022-02-21 2021-11-27 2022-04-11 2022-01-01 2022-07-08 2022-01-31 aires dans la zone d’interven ort infrastructure tion de la 2ème phase du PM RC NE-PMRC-258235-CS-INDV / Operational support for the Elaboration du plan de gestio IDA / 63850 A posteriori Individuel Limited 28,899.21 Signé 2021-11-01 2021-10-26 2021-11-06 2021-11-25 2021-11-20 2022-04-05 2021-12-18 2022-08-02 2022-01-27 Project n de la sécurité pour le PACN EN NE-PMRC-262136-CS-INDV / Operational support for the En attente d'exéc IDA / 63850 A priori Individuel Direct 0.00 2021-12-13 2021-12-20 2021-12-27 2022-01-17 2023-01-17 Spécialiste en Sauvegarde So Project ution ciale NE-PMRC-262140-CS-INDV / Operational support for the En cours d'exécut IDA / 63850 A priori Individuel Direct 0.00 2021-12-13 2022-03-10 2021-12-20 2022-04-11 2021-12-27 2022-01-17 2023-01-17 Spécialiste en Passation des Project ion Marchés NE-PMRC-262141-CS-INDV / Operational support for the En attente d'exéc IDA / 63850 A priori Individuel Direct 0.00 2021-12-13 2021-12-20 2021-12-27 2022-01-17 2023-01-17 Spécialiste en Suivi - Evaluati Project ution on NE-PMRC-274002-CS-INDV / Recrutement d'un consultant Operational support for the En cours d'exécut IDA / 63850 A posteriori Individuel Open 0.00 2022-02-01 2022-01-25 2022-02-25 2022-04-19 2022-03-02 2022-05-30 2022-03-21 2022-04-20 individuel pour l'évaluation à Project ion mi - parcours du PMRC NE-PMRC-280059-CS-INDV / Consultant Individuel pour ré aliser l’Audit de la mise en œ Operational support for the uvre du Plan d’Action de l'O IDA / 63850 A posteriori Individuel Open 14,971.98 Signé 2022-03-14 2022-03-10 2022-04-16 2022-06-14 2022-04-23 2022-06-21 2022-05-28 2022-06-30 2022-06-27 Project NG VBG portant sur la préve ntion et réponse contre l’Expl oitation et l’Abus Sexuel, ain si que le Harcèlement Sexuel (EAS/HS) NE-PMRC-233080-CS-INDV / Recrutement d'un Comptable Operational support for the IDA / 63850 A posteriori Individuel Open 0.00 Annulé 2021-06-01 2021-10-14 2021-07-05 2021-07-26 2021-08-14 2021-12-12 du Projet Corridor Economiqu Project e Régional LON NE-PMRC-233077-CS-INDV / Recrutement d'un Spécialiste Operational support for the en Sauvegarde Environneme IDA / 63850 A posteriori Individuel Open 0.00 Annulé 2021-06-01 2021-07-29 2021-07-05 2021-07-26 2021-08-14 2021-12-12 Project ntale du Projet Corridor Econ omique Régional LON NE-PMRC-240473-CS-INDV / Operational support for the Recrutement d'un auditeur in IDA / 63850 A posteriori Individuel Open 0.00 Annulé 2021-08-02 2021-07-29 2021-09-05 2021-09-12 2021-10-03 2022-10-03 Project terne du projet LON Page 5 NE-PMRC-233070-CS-INDV / Recrutement d'un Responsab Operational support for the IDA / 63850 A posteriori Individuel Open 0.00 Annulé 2021-06-01 2021-07-29 2021-07-05 2021-07-26 2021-08-14 2021-12-12 le Administratif et Financier d Project u Projet Corridor Economique LON NE-PMRC-233079-CS-INDV / Recrutement d'un Spécialiste Operational support for the IDA / 63850 A posteriori Individuel Open 0.00 Annulé 2021-06-01 2021-07-29 2021-07-05 2021-07-26 2021-08-14 2021-12-12 en VBG du Projet Corridor Ec Project onomique Régional LON NE-PMRC-233078-CS-INDV / Recrutement d'un Spécialiste Operational support for the IDA / 63850 A posteriori Individuel Open 0.00 Annulé 2021-06-01 2021-07-29 2021-07-05 2021-07-26 2021-08-14 2021-12-12 en Sauvegarde Sociale du Pr Project ojet Corridor Economique Ré gional LON NE-PADEZA-233072-CS-INDV / Recrutement d'un Spécialist Operational support for the IDA / 63850 A posteriori Individuel Open 0.00 Annulé 2021-06-01 2021-07-29 2021-07-05 2021-07-26 2021-08-14 2021-12-12 e en Passation des Marchés d Project u Projet Corridor Economique LON NE-PMRC-233083-CS-INDV / Recrutement d'un Assistant Operational support for the IDA / 63850 A posteriori Individuel Open 0.00 Annulé 2021-06-01 2021-07-05 2021-07-26 2021-08-14 2021-12-12 Comptable du Projet Corridor Project Economique Régional LON NE-PMRC-183467-CS-INDV / Elaboration EIES pour les Rou Improvement of rural transp IDA / 63850 A posteriori Individuel Limited 0.00 Annulé 2020-07-30 2020-08-04 2020-08-25 2020-09-29 2020-10-29 tes Rurales dans le cadre du ort infrastructure Projet Corridor Régional Lom é - Ouaga - Niamey NE-PMRC-183460-CS-INDV / Elaboration PAR pour les Rou Improvement of rural transp IDA / 63850 A posteriori Individuel Limited 0.00 Annulé 2020-07-30 2020-08-04 2020-08-25 2020-09-29 2020-11-13 tes Rurales dans le cadre du ort infrastructure Projet Corridor Régional Lom é - Ouaga - Niamey NE-PMRC-258234-CS-INDV / Operational support for the Recrutement d'un Coordonna IDA / 63850 A posteriori Individuel Open 0.00 Annulé 2021-10-25 2021-11-11 2021-11-18 2021-12-02 2021-12-21 2022-12-21 Project teur National NE-PMRC-258217-CS-INDV / Operational support for the Recrutement d'un (e) Compt IDA / 63850 A posteriori Individuel Direct 0.00 Annulé 2021-10-25 2021-11-26 2021-11-04 2021-11-11 2021-12-02 2022-12-02 Project able pour le compte PACNEN NE-PMRC-233087-CS-INDV / Operational support for the Recrutement d'un Responsab IDA / 63850 A posteriori Individuel Open 0.00 Annulé 2021-06-01 2018-02-19 2021-07-05 2021-07-26 2021-08-30 2022-08-30 Project le Administratif et Financier d u PMRC NE-PMRC-233100-CS-INDV / Recrutement du Spécialiste S Operational support for the IDA / 63850 A posteriori Individuel Open 0.00 Annulé 2021-07-01 2018-02-19 2021-08-04 2021-08-25 2021-09-29 2022-09-29 auvegarde Environnementale Project (SSE) du Projet NE-PMRC-233099-CS-INDV / Operational support for the Recrutement Spécialiste en S IDA / 63850 A posteriori Individuel Open 0.00 Annulé 2021-07-01 2018-02-19 2021-08-04 2021-08-25 2021-09-29 2022-09-29 Project auvegardes Sociales (SSS) d u Projet NE-PMRC-233097-CS-INDV / Operational support for the Recrutement d'un comptable IDA / 63850 A posteriori Individuel Open 0.00 Annulé 2021-06-01 2018-06-09 2021-07-05 2021-07-26 2021-08-30 2022-08-30 Project principal du PMRC NE-PMRC-233098-CS-INDV / Operational support for the Recrutement d'un Spécialiste IDA / 63850 A posteriori Individuel Open 0.00 Annulé 2021-06-01 2018-06-09 2021-07-05 2021-07-26 2021-08-30 2022-08-30 Project en Suivi Evaluation du PMRC NE-PMRC-199131-CS-INDV / Operational support for the Recrutement d'un Spécialiste IDA / 63850 A posteriori Individuel Open 0.00 Annulé 2020-12-01 2021-03-25 2021-01-03 2021-03-25 2021-01-24 2021-02-21 2022-02-21 Project en Genre NE-PADEZA-52901-CS-INDV / Recrutement du Spécialiste S Operational support for the IDA / V1420 A posteriori Individuel Open 0.00 Annulé 2018-03-12 2018-04-30 2018-05-21 2018-06-25 2018-12-22 auvegarde Environnementale Project (SSE) du Projet NE-PADEZA-56376-CS-INDV / Operational support for the Recrutement Spécialiste en S IDA / V1420 A posteriori Individuel Open 0.00 Annulé 2018-03-28 2018-05-16 2018-06-06 2018-07-11 2019-01-07 Project auvegardes Sociales (SSS) d u Projet NE-PMRC-258230-CS-INDV / Operational support for the Assistant spécialiste en sauv IDA / 63850 A posteriori Individuel Limited 0.00 Annulé 2021-11-01 2021-10-25 2021-11-06 2021-11-20 2021-12-11 2022-12-11 Project egardes environnementales pour le PMRC NE-PMRC-262137-CS-INDV / Operational support for the IDA / 63850 A posteriori Individuel Direct 0.00 Annulé 2021-12-13 2021-12-20 2021-12-27 2022-01-17 2023-01-17 Comptable Principal Project NE-PMRC-262135-CS-INDV / Operational support for the Spécialiste en Sauvegarde En IDA / 63850 A posteriori Individuel Direct 0.00 Annulé 2021-12-13 2021-12-20 2021-12-27 2022-01-17 2023-01-17 Project vironnementale NE-PMRC-262131-CS-INDV / Operational support for the IDA / 63850 A posteriori Individuel Direct 0.00 Annulé 2021-12-13 2021-12-20 2021-12-27 2022-01-17 2023-01-17 Responsable Administratif et Project Financier NE-PMRC-258232-CS-INDV / Operational support for the Assistant spécialiste en sauv IDA / 63850 A posteriori Individuel Limited 0.00 Annulé 2021-11-01 2021-10-25 2021-11-06 2021-11-20 2021-12-11 2022-12-11 Project egardes sociales pour le PMR C NE-PMRC-258233-CS-INDV / Operational support for the IDA / 63850 A posteriori Individuel Open 0.00 Annulé 2021-11-01 2021-11-06 2021-12-05 2021-12-26 2022-01-30 2023-01-30 Spécialiste Infrastructures po Project ur le PMRC NE-PADEZA-350810-CS-INDV / Recrutement d'un Consulta Operational support for the En attente d'exéc IDA / 63850 A posteriori Individuel Direct - National 0.00 2023-04-03 2023-04-13 2023-05-04 2023-06-08 2023-12-05 nt en vue de l'Assistance Tec Project ution hnique à l'UCP des projets P MRC er PACNEN NE-PADEZA-351375-CS-CDS Sélection de cons Operational support for the En attente d'exéc / Audit comptable et financie IDA / 63850 A posteriori ultants par entent Direct - National 0.00 2023-04-10 2023-04-20 2023-06-24 2023-12-21 Project ution r de l’exercice 2022 du PMRC e directe Page 6