Procurement Plan Credit No: 55080 XK Project ID: P143055 Projec Kosovo Energy Efficiency and Renewable Energy Project t (KEEREP) Name: I. General Agreed date of procurement Plan Origin May 14, 2014 al: Revise October 31, d 2019 Date of General Procurement Notice: Published on UNDB online on February 3, 2015 II. Goods and Works 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement - January 2011 Procurement Procurement Method Prior Review Method Threshold (USD) Threshold (USD) 1 ICB (Goods) ≥ 1,000,000 All above $ 1.5 million 2 NCB (Goods) ≤ 1,000,000 Packages 3 ICB (Works) ≥ 2,000,000 Each contract above $5 Packages million 4 NCB (Works) ≤ 2,000,000 Packages 5 Shopping ≤ 100,000 in accordance (Goods) with 3.5 of the Procurement Guidelines 6 Shopping ≤ 200,000 in accordance (Works) with 3.5 of the Procurement Guidelines 7 Direct In accordance with Contracting paragraph 3.7 of the (Goods and Procurement Guidelines Works) Note: For each Direct Contract (for goods and works) the PIU should provide justification to the Bank according to the procurement guidelines, and such contracts will be included in the procurement plan only after the Bank's clearance. III. Selection of Consultants 1. Prior Review Threshold: Selection Decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants - January 2011 Selection Selection Method Prior Review Method Threshold (USD) Threshold (USD) 1 Quality and ≥ 300,000 ≥ 500,000 Cost Based Selection (QCBS)* 2 Fixed Budget In accordance with ≥ 500,000 Selection (FBS) paragraph 3.5 of the Consultants Guidelines 3 Least Cost In accordance with ≥ 500,000 Selection (LCS) paragraph 3.6 of the Consultants Guidelines 4 Consultants' In accordance with Qualification paragraph 3.7 of the Selection Consultant's Guidelines (CQS) 5 Single Source In accordance with Selection paragraphs 3.8 thru.3.11 of (SSS) (Firms) the Consultants Guidelines 6 Individual In accordance with Section ≥ 200,000 Consultants V of the Consultants (IC) Guidelines 7 Single Source In accordance with Selection paragraph 5.6 of the (SSS) Consultants Guidelines (Individuals) *All ToRs for Consulting Contracts will be reviewed Note: For each single source contract (for firms and individuals) the PIU should provide justification to the Bank according to the consultant’s guidelines, and such contracts will be included in the procurement plan only after the Bank's clearance. 2. Short list comprising entirely of national consultant: Short list of consultants for services, estimated to cost less than USD 300,000 equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultants Guidelines. PROCUREMENT Kosovo : Kosovo Energy Efficiency and Renewable Energy Project PLAN General Information Country: Kosovo 2020-10-14 Bank’s Approval Date of the Original Procurement Plan: 2024-03-19 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P143055 GPN Date: Project Name: Kosovo Energy Efficiency and Renewable Energy Project Loan / Credit No: TF / B1487, IDA / 55080 Kosovo Energy Efficiency Fund Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned KEEF/1A2/W/2021 / Renovati Energy efficiency and renew Open - Internationa Single Stage - One E 2022-09-2 on of Buildings - Package 2, Y TF / B1487 able energy investments in Prior Request for Bids 5,002,500.00 0.00 Canceled 2021-06-01 2021-06-06 2021-07-18 2021-08-17 2021-09-21 l nvelope 1 ear 2021 public buildings KEEF/1A3/W/2021 / Renovati Energy efficiency and renew Open - Internationa Single Stage - One E 2022-10-2 on of Buildings - Package 3, Y TF / B1487 able energy investments in Post Request for Bids 1,437,500.00 0.00 Signed 2021-07-09 2022-10-07 2021-07-14 2022-10-07 2021-08-25 2022-11-23 2021-09-24 2022-12-09 2021-10-29 2023-02-10 l nvelope 9 ear 2022 public buildings Request for Bids - KEEF/1A1/W/2020 / Renovati Energy efficiency and renew Open - Internationa Single Stage - One E Small Works SPD Under Imple 2023-01-1 on of Buildings - Package 1, TF / B1487 able energy investments in Prior Request for Bids 9,200,000.00 0.00 2021-10-05 2021-10-04 2021-10-10 2021-10-05 2021-11-21 2021-11-19 2021-12-21 2022-01-20 2022-01-18 l nvelope (1 envelope proce mentation 8 Year 2020 public buildings ss) Request for Bids - KEEF/1A2/W/2021 R / Renov Energy efficiency and renew Open - Internationa Single Stage - One E Small Works SPD 2022-12-3 ation of Buildings - Package 2 TF / B1487 able energy investments in Post Request for Bids 4,025,000.00 0.00 Signed 2021-11-17 2021-11-18 2021-11-22 2021-11-18 2022-01-03 2021-12-31 2022-02-02 2022-02-04 2022-02-28 2022-03-04 l nvelope (1 envelope proce 1 , the Year 2021 public buildings ss) Request for Bids - RFB NO: KEEF/1A4/W/2023 / Energy efficiency and renew Single Stage - One E Small Works SPD 2023-11-1 Implementation of EE Measur TF / B1487 able energy investments in Post Request for Bids Open - National 1,918,922.62 0.00 Signed 2023-02-24 2023-03-06 2023-03-01 2023-03-27 2023-03-27 2023-04-07 2023-04-14 2023-05-02 2023-05-25 nvelope (1 envelope proce 8 es for 16 Sub-Projects (LOT 1 public buildings ss) and LOT 2) GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual KEEF/RFQ/1.3.1/2024 / IT Eq Project implementation supp Request for Quota Single Stage - One E IDA / 55080 Post Open - National 13,800.00 0.00 Signed 2024-01-16 2024-02-01 2024-01-31 2024-02-21 uipment Supply ort tions nvelope RFQ NO: KEEF/RFQ/1.3.2/20 Project implementation supp Request for Quota Single Stage - One E Under Imple IDA / 55080 Post Open - National 30,300.00 0.00 2024-02-23 2024-03-11 2024-04-01 24 / Work Equipment Supply ort tions nvelope mentation RFQ NO: KEEF/RFQ/1.3.3/20 24 / Procurement procedure: Project implementation supp Request for Quota Single Stage - One E Pending Impl IDA / 55080 Post Open - National 48,886.66 0.00 2024-02-29 2024-03-14 2024-03-14 Office Furniture Supply ort tions nvelope ementation RFQ No: KEEF/RFQ/1.3.3/202 4 RFQ NO: KEEF/RFQ/1.3.4/20 Project implementation supp Request for Quota Single Stage - One E Pending Impl 24 / The purchase of Account IDA / 55080 Post Limited - National 2,800.00 0.00 2024-03-20 2024-03-29 2024-04-10 ort tions nvelope ementation ing Software RFQ NO: KEEF/RFQ/1.3.4/202 4 NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual KEEF/1C2.1/CQ/2020/LOT 1 / Energy audits/Technical desi Energy efficiency and renew Consultant Qualifi gn/bidding Documents/Super TF / B1487 able energy investments in Post Open - National 281,659.00 295,019.77 Signed 2020-09-25 2020-09-25 2020-09-25 2020-09-25 2020-11-12 2020-09-25 2020-11-30 2020-09-25 2021-01-16 2020-09-25 cation Selection vision/DLP for Package 1, Yea public buildings r 2020- LOT 1, building (21 s ubprojects-buildings) KEEF/1C2.1/CQ/2020/LOT 2 / Energy audits/Technical desi Energy efficiency and renew gn/bidding Documents/Super Consultant Qualifi TF / B1487 able energy investments in Post Open - National 228,010.00 0.00 Signed 2020-09-25 2020-09-25 2020-09-25 2020-09-25 2020-11-12 2020-09-25 2020-11-12 2020-09-25 2021-01-01 2020-09-25 vision/DLP for Package 1, Yea cation Selection public buildings r 2020- LOT 2, building (17 s ubprojects: 14 buildings and 3 public lighting) KEEF/1C2.1/CQ/2020/LOT 3 / Energy audits/Technical desi Energy efficiency and renew Consultant Qualifi gn/bidding Documents/Super TF / B1487 able energy investments in Post Open - National 187,773.00 0.00 Signed 2020-09-25 2020-09-25 2020-09-25 2020-09-25 2020-11-12 2020-09-25 2020-12-30 2020-09-25 2020-12-30 2020-09-25 cation Selection vision/DLP for Package 1, Yea public buildings r 2020- LOT 3, building (17 s ubprojects -14 buildings) KEEF/1C2.1/CQ/2020/LOT 4 / Energy efficiency and renew Consultant Qualifi Technical design/bidding Doc TF / B1487 able energy investments in Post Open - National 23,000.00 0.00 Signed 2020-09-25 2020-09-25 2020-09-25 2020-09-25 2020-11-12 2020-09-25 2020-12-30 2020-09-25 2020-12-30 2020-09-25 cation Selection uments/Supervision-LOT 4, fo public buildings r PV subprojects KEEF/1C6/CQ/2022 / Policy r Policy and regulatory suppor Consultant Qualifi eviews and future business p TF / B1487 t for renewable energy and Post Open - National 63,250.00 0.00 Canceled 2022-02-22 2022-03-15 2022-04-28 2022-05-28 2022-07-02 2022-12-29 cation Selection lanning energy efficiency KEEF/2.11/CQ/2021 / Accoun ting firm for assesing KEEF n eeds and develop FM policy ( Project implementation supp Consultant Qualifi TF / B1487 Post Open - National 69,000.00 0.00 Signed 2020-11-16 2020-12-09 2020-12-07 2021-01-20 2021-04-28 2021-02-19 2021-06-30 2021-03-26 2021-06-30 2021-09-22 accounting methodology, fin ort cation Selection ancial reporting procedure, i nternal/external audit policy, etc) Page 1 KEEF/1C3.1/CQ/2021/LOT 1 / Energy efficiency and renew Energy audits/Technical desi Consultant Qualifi TF / B1487 able energy investments in Post Open - National 195,870.00 185,554.60 Signed 2020-10-20 2020-11-20 2020-11-10 2020-12-24 2021-02-01 2021-01-23 2021-02-12 2021-02-27 2021-03-25 2022-12-30 gn/bidding Documents/Super cation Selection public buildings vision/DLP for Package 2, Yea r 2021-LOT1 KEEF/1C3.2/CQ/2021/LOT 2 / Energy efficiency and renew Energy audits/Technical desi Consultant Qualifi TF / B1487 able energy investments in Post Open - National 195,870.00 0.00 Signed 2020-10-20 2020-11-20 2020-11-10 2020-12-24 2021-02-01 2021-01-23 2021-03-15 2021-02-27 2021-03-15 2022-12-30 gn/bidding Documents/Super cation Selection public buildings vision/DLP for Package 2, Yea r 2021-LOT2 KEEF/1C1/CQ/2020 / Awaren Energy efficiency and renew Consultant Qualifi ess raising and marketing for TF / B1487 able energy investments in Post Open - National 28,750.00 0.00 Signed 2020-10-16 2022-06-27 2020-10-16 2020-10-16 2020-07-03 2020-10-16 2020-10-15 2020-10-16 2020-10-18 2020-10-16 cation Selection pipeline development public buildings KEEF/1C4.1/CQ/2021 / Energ Energy efficiency and renew y audits/Technical design/bid Consultant Qualifi TF / B1487 able energy investments in Post Open - National 112,569.00 0.00 Canceled 2020-12-16 2021-01-06 2021-02-19 2021-03-21 2021-04-25 2022-12-30 ding Documents/Supervision/ cation Selection public buildings DLP for Package 3, Year 2022 NR. REF: KEEF/1C17/CQ/202 Project implementation supp Consultant Qualifi TF / B1487 Post Open - National 11,500.00 0.00 Signed 2023-02-23 2023-02-28 2023-03-09 2023-03-29 2023-04-25 2023-04-05 2023-05-11 2023-04-10 2023-05-17 2023-05-31 3 / Audit Services of Financial ort cation Selection Statements REF. NO: KEEF/1C5.1/CQ/202 3 LOT1 / Consulting Compan Energy efficiency and renew Consultant Qualifi y for Development of detaile TF / B1487 able energy investments in Post Open - National 82,800.00 0.00 Under Review 2023-09-26 2023-09-28 2023-10-03 2023-10-13 2023-10-17 2023-10-18 2023-12-31 cation Selection d energy audit reports, Detail public buildings ed Designs, Technical Specifi cation REF. NO: KEEF/1C5.2/CQ/202 3 LOT2 / Consulting Compan Energy efficiency and renew Consultant Qualifi y for Development of detaile TF / B1487 able energy investments in Post Open - National 69,000.00 0.00 Under Review 2023-09-26 2023-09-28 2023-10-03 2023-10-13 2023-10-17 2023-10-18 2023-12-31 cation Selection d energy audit reports, Detail public buildings ed Designs, Technical Specifi cation REF. NO: KEEF/1C5.3/CQ/202 3 LOT3 / Consulting Compan Energy efficiency and renew Consultant Qualifi y for Development of detaile TF / B1487 able energy investments in Post Open - National 82,800.00 0.00 Under Review 2023-09-26 2023-09-28 2023-10-03 2023-10-13 2023-10-17 2023-10-18 2023-12-31 cation Selection d energy audit reports, Detail public buildings ed Designs, Technical Specifi cation INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Energy efficiency and renew KEEF/1C5/IC/2021 / M&V, Mo Individual Consult TF / B1487 able energy investments in Post Open 115,000.00 0.00 Canceled 2021-05-03 2021-06-21 2021-07-12 2021-08-16 2022-02-12 nitoring and evaluation ant Selection public buildings KEEF (PROCUREMENT OFFIC Project implementation supp Individual Consult TF / B1487 Post Open 39,744.00 0.00 Signed 2020-10-08 2020-02-13 2020-10-08 2020-04-14 2020-10-08 2020-07-15 2020-10-08 2023-07-15 2020-10-08 ER) / Procurement Specialist ort ant Selection KEEF SENIOR TECHNICAL AD Project implementation supp Individual Consult VISOR 1 / Mechanical Engine TF / B1487 Post Open 45,540.00 0.00 Signed 2020-10-16 2022-11-01 2020-10-16 2022-12-08 2020-10-16 2022-12-02 2020-10-16 2020-10-16 ort ant Selection er - (Senior Technical Adviso r 1) KEEF SENIOR TECHNICAL AD Project implementation supp Individual Consult VISOR 2 (CIVIL / KEEF Senior TF / B1487 Post Open 39,744.00 42,219.49 Signed 2020-10-08 2020-02-11 2020-10-08 2020-05-18 2020-10-08 2020-07-15 2020-10-08 2020-07-25 2020-10-08 ort ant Selection Technical Advisor 2 (Civil Eng ineer / Architect) KEEF/2.6/IC/2021 / Internatio Project implementation supp Individual Consult TF / B1487 Post Open 20,700.00 0.00 Canceled 2021-04-06 2021-05-25 2021-06-15 2021-07-20 2022-01-16 nal Technical Advisor ort ant Selection KEEF/2.13/IC/2021 / Senior T Project implementation supp Individual Consult TF / B1487 Post Open 19,587.00 0.00 Signed 2021-09-10 2022-10-31 2021-09-10 2021-11-24 2021-09-10 2021-12-06 2021-09-10 2022-12-30 echnical Advisor (Engineer) ort ant Selection KEEF/2.14/IC/2022 / Assignm Project implementation supp Individual Consult ent Title: Senior Technical Ad TF / B1487 Post Open - National 18,468.00 0.00 Signed 2022-11-29 2022-11-29 2022-12-27 2023-02-27 2022-12-29 2023-02-27 2022-12-29 2023-03-01 2023-12-30 ort ant Selection visor (Environmental and soc ial specialist) KEEF/2.15/IC/2022 / Senior T Project implementation supp Individual Consult TF / B1487 Post Open - National 18,468.00 0.00 Signed 2022-11-29 2022-11-29 2022-12-27 2023-02-22 2022-12-29 2023-03-20 2022-12-30 2023-03-20 2023-12-31 echnical Advisor (Mechanical ort ant Selection Engineer) KEEF/2.16/IC/2023 / Senior T Project implementation supp Pending Impleme IDA / 55080 Post Direct Selection Direct - National 8,500.00 0.00 2023-07-05 2023-07-10 2023-07-17 2023-12-31 echnical Advisor (Engineer) ort ntation KEEF/2.17/IC/2023 / Senior T Project implementation supp Pending Impleme IDA / 55080 Post Direct Selection Direct - National 8,500.00 0.00 2023-07-05 2023-07-10 2023-07-17 2023-12-31 echnical Advisor (Engineer) ort ntation REF. NO: KEEF/2.14.1/IC/202 3 / Senior Technical Advisor ( Environmental and social spe cialist) Project implementation supp Individual Consult IDA / 55080 Post Direct - National 4,025.00 0.00 Signed 2023-12-20 2023-12-26 2023-12-26 2023-12-29 2023-12-27 2024-01-29 2023-12-28 2024-01-09 2024-04-30 Ref. no: KEEF/2.14.1/IC/2023. ort ant Selection This position will be part-time for four months, and after th e completion of the project, t he position can be transferre d to regular staff at KEEF! Page 2