PROCUREMENT PLAN (Textual Part) Project information: West Africa Coastal Areas Resilience Investment Project II Implementation agency: CPCU (Central Projects Coordination Unit) - Ministry of Agriculture Date of the Procurement Plan: January 10, 2022 Period covered by this Procurement Plan: January 10, 2022 – December 9, 2022 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. “Not Applicable” Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: is not applicable for those contracts identified in the Procurement Plan tables; Works: is not applicable for those contracts identified in the Procurement Plan tables Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations is Applicable. “Not Applicable” Other Relevant Procurement Information. None PROCUREMENT Western and Central Africa : West Africa Coastal Areas Resilience Investment Project 2 PLAN General Information Country: Western and Central Africa 2022-03-12 Bank’s Approval Date of the Original Procurement Plan: 2024-03-18 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P175525 GPN Date: 2022-06-27 Project Name: West Africa Coastal Areas Resilience Investment Project 2 Loan / Credit No: IDA / V4120, IDA / V4040, IDA / E1410 Institute of Biodiversity and Protected Areas Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GW-IBAP-394904-CW-RFQ / Implementa Component 4 : National Coor Solicitação de Cot Single Stage - One E Outro (campo par 2024-06-0 Aménagement des bureaux IDA / E1410 Posterior Limited 50,000.00 0.00 ção Pendent 2024-02-13 2024-04-09 dination ações nvelope a explicação) 8 du siège de l'UGP (IBAP) e GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GW-IBAP-391978-GO-DIR / F ourniture, installation, param Em fase de I Component 4 : National Coor étrage du logiciel de gestion IDA / E1410 Posterior Aquisição Direta Direct - National 45,000.00 0.00 mplementaç 2023-11-24 2023-11-24 2023-12-01 2023-11-29 2024-01-08 2025-01-02 dination financière HIPROJET, et form ão ation de l’équipe du projet à son utilisation GW-IBAP-391993-GO-DIR / F Em fase de I ourniture, montage, installati Component 4 : National Coor IDA / E1410 Posterior Aquisição Direta Direct - National 60,000.00 0.00 mplementaç 2023-11-24 2023-11-24 2023-12-01 2023-11-29 2024-01-08 2024-02-07 on et paramétrage des d’équ dination ão ipements informatiques pour l'UGP-WACA-ResIP II GW-IBAP-392192-GO-DIR / A cquisitions de matériel roula nts en 3 lots : - Deux (2) vehicules pour le p Component 2: Strengthening Em fase de I rojet. IDA / E1410 the Policy and Institutional F Posterior Aquisição Direta Direct - National 510,000.00 0.00 mplementaç 2023-11-24 2023-11-24 2023-11-29 2023-12-05 2024-01-03 2024-03-03 - Trois (3) vehicules et 20 mo ramework ão tos pour les parcs. - Cinq (5) vehicules, soit 1 po ur chaque institution (AAAC, I BAP HQ, INA/GPC, IGA et FBG ). GW-IBAP-392246-GO-DIR / F Em fase de I Component 4 : National Coor ourniture et montage des mo IDA / E1410 Posterior Aquisição Direta Direct - National 30,000.00 0.00 mplementaç 2023-11-30 2023-12-28 2023-12-05 2024-01-16 2024-01-09 2024-02-08 dination biliers de bureau pour l’UGP ão GW-IBAP-392250-GO-RFQ / Component 4 : National Coor Solicitação de Cot Single Stage - One E Implementaç Acquisition de fourniture et c IDA / E1410 Posterior Limited 40,000.00 0.00 2023-11-28 2023-12-29 2024-01-13 dination ações nvelope ão Pendente onsommables de bureau pou r l’UGP GW-IBAP-392394-GO-RFB / A cquisitions d'équipements inf Component 3: Strengthening ormatiques (ordinateurs, GPS Solicitação de Ofe Single Stage - One E Implementaç IDA / E1410 National Physical and Social Posterior Open - National 180,000.00 0.00 2024-06-12 2024-06-17 2024-07-29 2024-08-28 2024-10-02 2024-12-01 , tablettes,, projecteurs, syst rtas nvelope ão Pendente Investments èmes de cinéma, appareils p hotos et drones) pour les siè ges des 6 AMPs GW-IBAP-273599-GO-RFQ / Component 4: National Coor Solicitação de Cot Single Stage - One E Acquisition de matériel infor IDA / V4120 Posterior Limited 10,000.00 0.00 Cancelado 2022-12-28 2023-02-22 2023-08-21 dination ações nvelope matique et bureautique pour le projet GW-IBAP-404243-GO-RFQ / F Component 2: Strengthening ourniture, montage et config Solicitação de Cot Single Stage - One E Implementaç IDA / E1410 the Policy and Institutional F Posterior Limited 84,000.00 0.00 2024-02-20 2024-04-16 2024-05-26 uration d'équipements infor ações nvelope ão Pendente ramework matiques pour AAAC, IBAP (S IG) et INA/GPC GW-IBAP-392270-GO-RFQ / Acquisition d’équipements in Component 2: Strengthening Solicitação de Cot Single Stage - One E formatiques pour l'AAAC (ord IDA / E1410 the Policy and Institutional F Posterior Limited 30,000.00 0.00 Cancelado 2023-12-20 2024-01-20 2024-02-19 ações nvelope inateurs, système de vidéo-c ramework onférence, imprimantes, sca nners etc...) GW-IBAP-392271-GO-RFQ / Component 2: Strengthening Acquisition d’équipements p Solicitação de Cot Single Stage - One E IDA / E1410 the Policy and Institutional F Posterior Limited 50,000.00 0.00 Cancelado 2024-01-03 2024-02-03 2024-03-19 our l'IBAP (SIG, informatique, ações nvelope ramework vidéo conférence, etc.) GW-IBAP-404291-GO-RFQ / F ourniture, montage et config uration d'équipments divers Component 2: Strengthening pour IBAP, Fondation BioGuin Solicitação de Cot Single Stage - One E Implementaç IDA / E1410 the Policy and Institutional F Posterior Limited 92,200.00 0.00 2024-03-12 2024-05-07 2024-06-26 é (FBG) et AAAC (panneaux s ações nvelope ão Pendente ramework olaires, équipements de suivi sur terrain, GPS, Drone, Appa reil Photo, Tablet etc..) pour l e suivi des activités GW-IBAP-392272-GO-RFQ / Component 2: Strengthening Acquisition d’équipements p Solicitação de Cot Single Stage - One E IDA / E1410 the Policy and Institutional F Posterior Limited 45,000.00 0.00 Cancelado 2024-01-30 2024-03-01 2024-04-15 our l'IBAP (groupe électrogèn ações nvelope ramework e, panneaux solaire, etc.) GW-IBAP-392458-GO-RFQ / Component 4 : National Coor Solicitação de Cot Single Stage - One E Acquisition d’équipements d IDA / E1410 Posterior Limited 12,200.00 0.00 Cancelado 2024-01-02 2024-02-02 2024-03-03 dination ações nvelope e suivi sur terrain pour la ''Fu ndação BioGuiné'' GW-IBAP-392476-GO-RFQ / Component 4 : National Coor Solicitação de Cot Single Stage - One E Acquisition de Groupe électro IDA / E1410 Posterior Limited 15,000.00 0.00 Cancelado 2024-03-20 2024-04-20 2024-05-20 dination ações nvelope gène (alternative courant éle ctrique) Page 1 GW-IBAP-405917-GO-RFQ / F ourniture, montage, installati on et configuration d'équipe Component 2: Strengthening Solicitação de Cot Single Stage - One E Implementaç ments informtatiques et de c IDA / E1410 the Policy and Institutional F Posterior Limited 46,100.00 0.00 2024-03-26 2024-05-21 2024-06-20 ações nvelope ão Pendente ommunication pour la Fondat ramework ion BioGuiné (FBG) et l'Inspe ction Générale de l'Environne ment (IGA) GW-IBAP-392467-GO-RFQ / Acquisition d’équipements d Component 4 : National Coor Solicitação de Cot Single Stage - One E IDA / E1410 Posterior Limited 3,500.00 0.00 Cancelado 2023-12-27 2024-01-27 2024-02-26 e communication pour la ''Fu dination ações nvelope ndação BioGuiné'' GW-IBAP-406098-GO-RFQ / F Component 2: Strengthening ourniture d'équipements de Solicitação de Cot Single Stage - One E Implementaç IDA / E1410 the Policy and Institutional F Posterior Limited 49,000.00 0.00 2024-04-03 2024-05-04 2024-06-03 protection individuelle et de t ações nvelope ão Pendente ramework errain pour le personnel d'IB AP et de l'AAAC GW-IBAP-392378-GO-RFQ / Component 3: Strengthening Acquisition d'équipements (b Solicitação de Cot Single Stage - One E IDA / E1410 National Physical and Social Posterior Limited 45,000.00 0.00 Cancelado 2024-02-20 2024-03-22 2024-04-12 ottes, capes de pluies, etc.) p ações nvelope Investments our les gardes et techniciens de l'IBAP NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GW-IBAP-391850-CS-CQS / S élection d’un cabinet pour la réalisation de l'étude techniq ue (APD) et DAO pour la cons Component 3: Strengthening Seleção Baseada Em fase de Imple truction du bâtiment siège d IDA / V4120 National Physical and Social Posterior nas Qualificações Open - National 150,000.00 0.00 2023-12-07 2024-01-29 2023-12-28 2024-02-02 2024-02-10 2024-03-11 2024-04-15 2025-02-09 mentação e l'AAAC et de l'INA, et du mi Investments dos Consultores cro laboratoire de référence environnemental, ainsi que l' extension du siège de l'IBAP et suivi des travaux GW-IBAP-392487-CS-CQS / S élection d’un cabinet pour l’a nalyse du cadre légal existan t et recommandation d’améli Component 2: Strengthening Seleção Baseada oration pour la réinstallation IDA / V4120 the Policy and Institutional F Posterior nas Qualificações Open - National 170,000.00 0.00 Cancelado 2024-06-27 2024-07-18 2024-08-31 2024-09-30 2024-11-04 2025-02-02 volontaire, l’évaluation envir ramework dos Consultores onnementale et sociale strat égique, la loi sur les évaluati ons environnementales, et se s décrets d’applicat GW-IBAP-392587-CS-CQS / S Component 2: Strengthening Seleção Baseada élection d’un cabinet pour l’é Implementação P IDA / V4120 the Policy and Institutional F Posterior nas Qualificações Open - National 150,000.00 0.00 2024-06-21 2024-07-12 2024-08-25 2024-09-24 2024-10-29 2024-12-28 tude de la Faisabilité du syst endente ramework dos Consultores ème d'observation du littoral GW-IBAP-392593-CS-CQS / A Component 2: Strengthening Seleção Baseada Implementação P udit financier annuel -UK (Ins IDA / V4120 the Policy and Institutional F Posterior nas Qualificações Open - National 90,000.00 0.00 2023-12-22 2024-01-12 2024-02-25 2024-03-26 2024-04-30 2024-05-30 endente titutionnel) - ''Fundação BioG ramework dos Consultores uiné'' GW-IBAP-392606-CS-CQS / S Component 2: Strengthening Seleção Baseada élection d’un cabinet de Serv Implementação P IDA / V4120 the Policy and Institutional F Posterior nas Qualificações Limited 87,500.00 0.00 2024-08-22 2024-09-05 2024-10-05 2024-11-09 2027-12-29 ices de Company Secretariat endente ramework dos Consultores annuel + Conseils juridiques en UK (15j par an) GW-IBAP-393239-CS-CQS / S élection d’un cabinet pour l’a nalyse des systèmes de ress ources humaines et mise en Component 2: Strengthening Seleção Baseada Implementação P place de système efficace (IN IDA / V4120 the Policy and Institutional F Posterior nas Qualificações Open - National 110,000.00 0.00 2024-04-18 2024-04-25 2024-06-03 2024-07-01 2024-07-18 2024-09-16 endente A, AAAC, IBAP et FBG) et Dia ramework dos Consultores gnostic des besoins (humains et équipements) pour les inst itutions. Y préparation d'un p olitique de RH. GW-IBAP-393254-CS-CQS / S élection d’un consultant pour l’analyse du cadre existant, P Component 2: Strengthening Seleção Baseada réparation du projet pour act Implementação P IDA / E1410 the Policy and Institutional F Posterior nas Qualificações Open - National 150,000.00 0.00 2024-11-01 2024-11-08 2024-12-16 2025-01-15 2025-02-01 2025-07-31 ualisation de la loi sur les Air endente ramework dos Consultores es Protégées, de la loi sur les espèces (faune et flore) men acées, des lois sur mangrove , forets communautaires, aut res... GW-IBAP-392992-CS-QCBS / Component 2: Strengthening Seleção Baseada Préparation et Mise en œuvr Implementação P IDA / E1410 the Policy and Institutional F Posterior na Qualidade e Cu Open - National 300,000.00 0.00 2024-09-05 2024-09-26 2024-11-09 2024-12-07 2025-01-06 2025-02-10 2025-03-17 2026-03-17 e des stratégies/plans de co endente ramework sto mmunication des différents b énéficiaires du projet GW-IBAP-393008-CS-CQS / S élection d’un cabinet pour le s analyses des options pour r Component 2: Strengthening Seleção Baseada enforcer le CBADP "Communi IDA / V4120 the Policy and Institutional F Posterior nas Qualificações Open - National 150,000.00 0.00 Cancelado 2024-04-11 2024-05-02 2024-06-15 2024-07-15 2024-08-19 2024-11-17 ty-Based Avoided Déforestati ramework dos Consultores on Project - Blue Carbon" me chanisms Plan d'action pour combattre la déforestation GW-IBAP-404583-CS-CQS / D éveloppement des accords d e partage des bénéfices pour Component 2: Strengthening Seleção Baseada le CBADP - projet REDD+ de Em fase de Imple IDA / E1410 the Policy and Institutional F Posterior nas Qualificações Open - National 130,000.00 0.00 2024-04-18 2024-05-09 2024-06-22 2024-07-22 2024-08-26 2025-02-22 déforestation évitée à base c mentação ramework dos Consultores ommunautaire Guinée-Bissau , et intégration de l'évaluatio n de l'impact social et sur la biodiversité Page 2 GW-IBAP-413823-CS-CQS / . Analyse du cadre existant, Pr éparation du projet pour actu Component 2: Strengthening Seleção Baseada alisation du décret sur la réin Implementação P IDA / E1410 the Policy and Institutional F Posterior nas Qualificações Open - National 150,000.00 0.00 2024-08-28 2024-09-18 2024-11-01 2024-12-01 2025-01-05 2025-07-04 stallation involontaire et sur endente ramework dos Consultores l'évaluation environnemental e et sociale stratégique et la loi sur les évaluations enviro nnementales et ses décrets d 'application. INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GW-IBAP-273610-CS-INDV / Component 4: National Coor IDA / V4120 Posterior Individual Open 43,000.00 0.00 Cancelado 2022-02-28 2022-06-02 2022-04-18 2022-05-09 2022-06-13 2023-06-12 Sélection d'un expert techniq dination ue GW-IBAP-273612-CS-INDV / Component 4: National Coor IDA / V4120 Posterior Individual Open 51,000.00 0.00 Cancelado 2022-02-28 2022-04-25 2022-04-18 2022-05-09 2022-06-13 2023-06-12 Sélection d'un Coordonnateu dination r GW-IBAP-273614-CS-INDV / Component 4: National Coor Em fase de Imple Sélection d'un spécialiste en IDA / V4120 Posterior Individual Open 36,500.00 0.00 2022-02-28 2022-04-25 2022-04-18 2022-05-09 2022-06-13 2023-06-12 dination mentação passation des marchés GW-IBAP-273616-CS-INDV / Component 4: National Coor Em fase de Imple Sélection d'un spécialiste en IDA / V4120 Posterior Individual Open 36,500.00 0.00 2022-02-28 2022-04-25 2022-04-18 2022-05-09 2022-06-13 2023-06-12 dination mentação gestion financière GW-IBAP-273622-CS-INDV / Component 4: National Coor Em fase de Imple Sélection d'un expert en sau IDA / V4120 Posterior Individual Open 36,500.00 0.00 2022-02-28 2023-08-02 2022-04-18 2022-05-09 2022-06-13 2023-06-12 dination mentação vegardes environnementales GW-IBAP-273619-CS-INDV / Component 4: National Coor Open - Internationa IDA / V4120 Posterior Individual 20,000.00 0.00 Cancelado 2022-09-15 2022-09-05 2022-11-03 2022-11-24 2022-12-29 2023-06-27 Spécialiste en suivi-évaluatio dination l n GW-IBAP-273624-CS-INDV / Component 4: National Coor Open - Internationa IDA / V4120 Posterior Individual 36,500.00 0.00 Cancelado 2022-09-15 2023-08-02 2022-11-03 2022-11-24 2022-12-29 2023-12-28 Spécialiste en sauvegardes s dination l ociales GW-IBAP-273643-CS-CQS / P reparação dos documentos d Component 4: National Coor Seleção Direta de Direct - Internation Implementação P IDA / V4120 Posterior 270,000.00 0.00 2022-09-12 2022-09-22 2022-11-26 2023-05-25 e gestão dos riscos ambienta dination Consultores al endente is e sociais do projeto GW-IBAP-273615-CS-INDV / Component 4: National Coor Préparation du manuel de mi IDA / V4040 Posterior Individual Limited 15,000.00 0.00 Cancelado 2022-10-31 2022-11-05 2022-11-26 2022-12-31 2023-06-29 dination se en œuvre du projet. GW-IBAP-273618-CS-INDV / Component 4: National Coor Direct - Internation Implementação P Préparation de la stratégie d IDA / V4120 Posterior Individual 15,000.00 0.00 2022-10-03 2022-10-13 2022-11-03 2022-12-08 2023-06-06 dination al endente e passation des marchés du projet GW-IBAP-385274-CS-INDV / Sélection d'un(e) Consultant( Component 4 : National Coor Em fase de Imple IDA / V4120 Posterior Individual Open - National 36,500.00 0.00 2023-10-03 2023-10-03 2023-11-03 2023-12-04 2023-11-06 2023-11-10 2024-11-09 e) Spécialiste en Communica dination mentação tion pour le projet WACA-ResI P II GW-IBAP-385280-CS-INDV / Sélection d'un(e) Consultant( Component 4 : National Coor Em fase de Imple IDA / V4120 Posterior Individual Open - National 36,500.00 0.00 2023-10-03 2023-10-03 2023-11-03 2023-11-06 2023-11-10 2024-11-09 e) Spécialiste en Suivi-Évalua dination mentação tion pour le projet WACA ResI P II GW-IBAP-273632-CS-INDV / Component 4 : National Coor Em fase de Imple Sélection d'un(e) Consultant( IDA / V4120 Posterior Individual Open - National 36,500.00 0.00 2022-09-30 2023-10-03 2022-11-18 2022-12-09 2023-01-13 2024-01-12 dination mentação e) en Audit Interne pour le pr ojet WACA-ResIP II GW-IBAP-390583-CS-INDV / Sélection d'un(e) Consultant( Component 4 : National Coor Em fase de Imple IDA / V4120 Posterior Individual Open - National 48,000.00 0.00 2023-11-01 2023-10-24 2023-12-08 2023-12-11 2023-12-15 2024-12-14 e) pour le poste de Coordonn dination mentação ateur/Coordonnatrice du proj et WACA-ResIP II GW-IBAP-390724-CS-INDV / Sélection d'un(e) Consultant( Component 4 : National Coor Em fase de Imple e) pour le poste de Spécialist IDA / V4120 Posterior Individual Open - National 36,500.00 0.00 2023-11-01 2023-10-31 2023-12-08 2023-12-11 2023-12-15 2024-12-14 dination mentação e en Sauvegarde Sociale du projet WACA-ResIP II GB GW-IBAP-390790-CS-INDV / Sélection d'un(e) Consultant( Component 4 : National Coor Em fase de Imple e) pour le poste d'Expert(e) T IDA / V4120 Posterior Individual Open - National 36,500.00 0.00 2023-11-07 2023-10-31 2023-12-14 2023-12-18 2023-12-22 2024-12-21 dination mentação echnique - Responsable des Opérations du WACA-ResIP II GB GW-IBAP-392481-CS-INDV / Sélection d’un(e) consultant( Component 2: Strengthening Em fase de Imple e) pour la préparation du pla IDA / E1410 the Policy and Institutional F Posterior Individual Limited 60,000.00 0.00 2024-03-14 2024-01-23 2024-03-19 2024-04-09 2024-05-14 2024-07-13 mentação n stratégique pour l'Autorité ramework d'Évaluation Environnementa le Compétente (AAAC) GW-IBAP-392483-CS-INDV / Sélection d’un(e) consultant( Component 2: Strengthening e) pour le développement de Implementação P IDA / E1410 the Policy and Institutional F Posterior Individual Limited 30,000.00 0.00 2024-02-22 2024-02-27 2024-03-19 2024-04-23 2024-06-22 s manuels de procédures ad endente ramework ministratives de l'Autorité d'É valuation Environnementale Compétente (AAAC). GW-IBAP-392581-CS-INDV / Sélection d’un(e) consultant( e) pour la réalisation de l'EIE Component 3: Strengthening Implementação P S pour la construction du bâti IDA / E1410 National Physical and Social Posterior Individual Limited 40,000.00 0.00 2024-01-04 2024-01-09 2024-02-06 2024-03-05 2024-04-19 endente ment siège de l'AAAC et de l'I Investments NA et du micro laboratoire de référence environnemental, et extension du siège de l'IB AP Page 3 GW-IBAP-392640-CS-INDV / Sélection d’un consultant po ur la préparation du Cadre de sauvegarde environnemental Component 2: Strengthening Implementação P e et sociale, genre et risques IDA / E1410 the Policy and Institutional F Posterior Individual Limited 60,000.00 0.00 2024-02-28 2024-03-04 2024-04-01 2024-04-29 2024-06-13 endente pour la FBG, y compris pour l ramework es sous-projets sociaux, avec guides de mise en œuvre (y compris le mécanisme de ge stion des plaintes) (FBG) GW-IBAP-393214-CS-INDV / Component 2: Strengthening Sélection d’un(e) consultant( Implementação P IDA / E1410 the Policy and Institutional F Posterior Individual Limited 25,000.00 0.00 2024-02-01 2024-02-05 2024-03-04 2024-03-22 2024-05-06 e) pour la mise à jour de la st endente ramework ratégie d'écotourisme (2024- 2038) GW-IBAP-393170-CS-CDS / S élection d’un consultant pou Component 2: Strengthening Seleção Direta de Implementação P r la révision de la stratégie n IDA / E1410 the Policy and Institutional F Posterior Direct - National 55,000.00 0.00 2024-03-04 2024-03-11 2024-04-05 2024-06-04 Consultores endente ationale de biodiversité et de ramework s Aires protégés et plan d'act ion et évaluation. GW-IBAP-273611-CS-INDV / Préparation du plan pour le p Component 4: National Coor Open - Internationa IDA / V4120 Posterior Individual 30,000.00 0.00 Cancelado 2022-08-31 2023-07-20 2022-10-19 2022-11-09 2022-12-14 2023-06-12 artage de bénéfice, et mécan dination l isme de gestion des plaintes associé GW-IBAP-273617-CS-INDV / Component 4: National Coor Préparation de la stratégie d IDA / V4120 Posterior Individual Limited 15,000.00 0.00 Cancelado 2022-09-15 2022-09-20 2022-10-11 2022-11-15 2023-05-14 dination e suivi et d'évaluation (manu el) GW-IBAP-399437-CS-INDV / Sélection d’un consultant po ur la réalisation de l'EIES pou Component 3: Strengthening Implementação P r la construction du bâtiment IDA / E1410 National Physical and Social Posterior Individual Limited 40,000.00 0.00 2024-01-25 2024-01-30 2024-02-20 2024-03-10 2024-05-09 endente siège de l'AAAC et de l'INA et Investments du micro laboratoire de référ ence environnemental, et ext ension du siège de l'IBAP GW-IBAP-393151-CS-CDS / S élection d’un Consultant pour l'élaboration du Manuel de pr Component 2: Strengthening Seleção Direta de océdure du projet, révision, a IDA / E1410 the Policy and Institutional F Posterior Direct - National 60,000.00 0.00 Cancelado 2024-02-16 2024-02-26 2024-05-01 2024-06-30 Consultores tualisation et adaptation du ramework manuel de procédures d'IBAP aux procédures de la Banque Mondiale GW-IBAP-393123-CS-INDV / Component 4 : National Coor Sélection d’un(e) consultant( IDA / E1410 Posterior Individual Limited 30,000.00 0.00 Cancelado 2023-11-27 2023-11-30 2023-12-28 2024-01-07 2024-02-06 dination e) pour l’élaboration du Manu el du projet GW-IBAP-393001-CS-INDV / Sélection d’un consultant po Component 2: Strengthening ur le développement du mod IDA / E1410 the Policy and Institutional F Posterior Individual Limited 80,000.00 0.00 Cancelado 2023-12-29 2024-01-03 2024-01-31 2024-02-28 2024-04-13 èle de partage de bénéfice p ramework our le projet carbone (CBADP ) avec le SBIA approach + tra ining GW-IBAP-411524-CS-CDS / S élection par entente directe Component 4 : National Coor Seleção Direta de Em fase de Imple IDA / E1410 Posterior Direct - National 41,380.00 0.00 2024-03-04 2024-03-04 2024-03-13 2024-04-17 2025-04-17 d'une consultante pour le po dination Consultores mentação ste de Spécialiste en Suivi-év aluation. GW-IBAP-413502-CS-CDS / S eleção de um consultor para Component 2: Strengthening analisar e atualizar os projet Seleção Direta de Implementação P IDA / E1410 the Policy and Institutional F Posterior Direct - National 20,000.00 0.00 2024-03-11 2024-03-20 2024-05-17 2024-06-16 os de decretos sobre taxação Consultores endente ramework e acreditação de gabinetes d e estudos em matéria de ava liação ambiental GW-IBAP-413824-CS-CDS / S élection d’un Consultant pour l'élaboration du Manuel de pr Component 2: Strengthening océdure du projet, révision, a Seleção Direta de Implementação P IDA / E1410 the Policy and Institutional F Posterior Direct - National 60,000.00 0.00 2024-04-04 2024-04-25 2024-06-07 2024-08-19 tualisation et adaptation du Consultores endente ramework manuel de procédures d'IBAP aux procédures de la Banque Mondiale, et l'actualisation d u Manuel de procédures de l a FBG. Page 4