PROCUREMENT PLAN Version 2.1 – Date: September 1, 2021 PROGRAM TO ACCELERATE AGRARIAN REFORM (ONE MAP PROJECT) A. Project information: Country: Indonesia Borrower: Republic of Indonesia Project ID: P160661 Financing Agreement IBRD Loan 8897-ID Number: Project Implementation Agency(ies): PMU: Ministry of Agrarian and Spatial Planning (ATR/BPN) PIU: Geospatial Information Agency (BIG) B. Key Dates: 1. Procurement Plan: a. Version 1.0 (for June 4, 2018 negotiation) Bank’s Approval to this June 4, 2018 version: Period covered by this June 4, 2018 – December 31, version: 2023 b. Version 1.9 (previous July 22, 2021 version) Bank’s Approval to this July 29, 2021 version: Period covered by this June 4, 2018 – December 31, version: 2023 c. Version 2.0 (this version) September 1, 2021 Bank’s Approval to this September 8, 2021 version: Period covered by this June 4, 2018 – December 31, version: 2023 d. [next version, if any] [to be updated] 2. General Procurement April 2019 Notice: C. Preamble All Procurement under the Project shall be carried out in accordance with the World Bank’s Procurement Regulations for IPF Borrowers of July 2016, revised November 2017, and the provisions of the Procurement Plan and Project Operations Manual and shall take precedence over any national procurement regulations. In accordance with paragraph 5.9 of the Procurement Regulations, the Bank’s online procurement planning and tracking tools i.e. Systematic Tracking and Exchanges in Procurement (STEP) will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. D. Key Provisions The following conditions apply to all procurement activities in this Procurement Plan. The Bank’s procurement prior review thresholds: The identified procurement risk under this Project is ‘Substantial’. Accordingly, all contracts listed in the Procurement Plan that are at or above the thresholds set out below are subject to the Bank’s prior review. All other contracts are subject to the Bank’s ex-post review. Table 1. Applied Prior Review Threshold Type of procurement Procurement Prior Review Thresholds (US$ millions) Works (including turnkey, supply & installation of 10 plant and equipment, and PPP) Goods, Information Technology and Non- 2 consulting Services Consultants: Firms 1 Consultants: Individuals 0.3 The Bank’s approved selection methods thresholds: The following selection method thresholds shall apply for procurement of goods & information technology, non-consulting services and consulting services of each identified activity. Table 2. Applied Approved Selection Method Threshold Type of procurement and Approved Selection Method Thresholds Approved Selection (US$ millions) Method National International Works (including turnkey, supply & installation of plant and equipment, and PPP) (i) Request for Request for at or above $0.2 and at or above $25 Bids (RFB) less than $25 (ii) Request for Quotations less than $0.2 N/A (RFQ) (iii) Direct Selection On exceptional basis On exceptional basis if justified as per if justified as per paragraph 6.8, 6.9 paragraph 6.8, 6.9 and 6.10 of the and 6.10 of the Procurement Procurement Regulations Regulations Goods, Information Technology and Non-consulting services a. For Goods and Information Technology: (i) Request for Request for at or above $0.1 and at or above $2 Bids (RFB) less than $2 (ii) Request for Quotations less than $0.1 N/A (RFQ) (iii) Direct Selection On exceptional basis On exceptional basis if justified as per if justified as per paragraph 6.8, 6.9 paragraph 6.8, 6.9 Type of procurement and Approved Selection Method Thresholds Approved Selection (US$ millions) Method National International and 6.10 of the and 6.10 of the Procurement Procurement Regulations Regulations b. For Non-consulting Services: (i) Request for Request for at or above $0.1 and at or above $10 Bids (RFB) less than $10 (ii) Request for Quotations less than $0.1 N/A (RFQ) (iii) Direct Selection On exceptional basis On exceptional basis if justified as per if justified as per paragraph 6.8, 6.9 paragraph 6.8, 6.9 and 6.10 of the and 6.10 of the Procurement Procurement Regulations Regulations Consultants: firms a. For Selection of Consulting Firms (i) Quality Cost Based Shortlist of firms for at or above $0.4 Selection (QCBS), Fixed contracts below $0.4 Budget Based Selection may comprise (FBS), Least Cost Based entirely national Selection (LCS) and firms Quality Based Selection (QBS) (ii) Consultant’s less than $0.3 N/A Qualifications Based Selection (CQS) (iii) Direct Selection On exceptional basis On exceptional basis if justified as per if justified as per paragraph 7.13, 7.14 paragraph 7.13, 7.14 and 7.15 of the and 7.15 of the Procurement Procurement Regulations Regulations b. For Selection of Individual Consultants (i) Open Competitive All, no monetary All, no monetary Selection of Individual threshold threshold Consultants and Limited Competitive Selection of Individual Consultants Type of procurement and Approved Selection Method Thresholds Approved Selection (US$ millions) Method National International (ii) Direct Selection of On exceptional basis On exceptional basis Individual Consultants if justified as per if justified as per paragraph 7.39 of paragraph 7.39 of the Procurement the Procurement Regulations Regulations Standard Procurement Documents (SPD): The Bank’s SPD shall be used when approaching the international market (specifically for international competitive procurement and those contracts shall be as specified in the Procurement Plan tables in STEP. Use of National Procurement Procedures: In accordance with paragraphs 5.3 of the Procurement Regulations, when approaching the national market all contracts to be procured through open national competitive procurement will follow the GoI’s procurement regulation. The procedures applicable to the procurement of goods and non-consulting services awarded on the basis of open national competitive procurement shall be those of the Tender method as set forth in the Peraturan Presiden No. 16/2018 and its subsequent amendment Peraturan Presiden No. 12/2021) provided that such arrangements continue to meet requirements set forth under paragraph 5.4 of these Regulations and the following conditions: 1. The procurement is open to eligible firms from any country. There shall not any restriction to the bidders’ participation including mandatory requirement to form in joint venture; 2. Any gaps between National Procurement Procedures and the Procurement Regulations will be addressed and incorporated in the harmonized bidding documents acceptable by the Bank. Use of National e-Procurement System (SPSE): Unless informed otherwise by the Bank in writing, SPSE e-procurement system may be used only for procurement of works, goods and non-consulting services under Request for Bids (RFB) method through national open competitive procurement method, applying the harmonized model bidding documents for national open competitive procurement agreed by the Bank. For selection of consulting services through QCBS method, only the modified SPSE (termed by LKPP as SPSE-“ICB”) may be used applying the Bank’s Standard Request for Proposal (RFP) document. The Bank has further accepted GOI’s proposal for use of SPSE-ICB for selection of consulting services through CQS method applying a modified Bank’s Standard RFP. Two consulting services activities (contracts) under other Bank-financed project are being performed as pilot use of SPSE-ICB for CQS method to ensure that the system is working as intended. Since at the present time LKPP has not yet developed the modified SPSE for procurement of goods, works and non-consulting services under international open Competitive method, nor for selection of consulting services under QBS, LCS, FBS, and individual consultant selection methods, therefore procurement of all contract packages under these methods shall be carried out through non- electronic process with manual issuance of specific procurement notice (request for expression of interest or invitation for bids/proposals and receipt of bids/proposals), until such time that the modified SPSE has been completed by LKPP and assessed by the Bank to be acceptable. If the Bank determines the modified SPSE to be acceptable for use under the above- mentioned remaining procurement methods, the Bank will confirm through the Bank’s written no objection to LKPP and will also notify in writing to PMU/PIU. Use of National e-Catalogue System. Based on the Bank’s assessment of the national e-catalogue system, the Bank allows the Project Implementing Units (PIUs) under World Bank financed projects to use the national e- catalogue for procurement of small value of goods in lieu of the Request for Quotations (RFQ) method specified in these Regulations within the parameters as below: a) For Goods (other than medicines) with estimated cost not more than USD 15,000 equivalent per contract. PIUs may use the national e-catalogue for procuring such items of goods within the above-specified threshold, if such goods are required under the project and specified in the Procurement Plan approved by the Bank. b) Goods (other than medicines) with estimated cost greater than USD 15,000 but less than USD 100,000 equivalent per contract. PIUs may use the national e-catalogue for procuring such items of goods if such goods are required under the project subject to fulfilling the following additional procedural requirement as below: PMU and PIU shall carry out a secondary procurement process through mini competition, by comparing the prices of similar goods offered by at least three different suppliers which available in the national e-catalogue and then selecting the Supplier with the lowest evaluated price on the basis of “as delivered" price at final destination (i.e., including inland transportation, insurance, applicable taxes and any other incidental charges for the delivery of the required quantity of goods at final destination). E. Other Relevant Procurement Information • Project Operations Manual (POM) shall set out the operating procedures for procurement and contract implementation matters under the Project written in Bahasa, which shall be consistent with the procedures and rules specified under the Bank’s Procurement Regulations. In case of any difference of interpretation between the POM and the Bank’s Procurement Regulations, the later shall prevail; • PMU and PIU may use its own forms of contract for goods/non-consulting services procured under Request for Quotations (RFQ) method when approaching to national market, acceptable to the Bank; • Advance procurement may be applied under the project and shall be valid by signing of the Loan Agreement. PMU and PIU may commence the procurement process prior to issuance of the DIPA for any anticipated activity to be procured under the Project, while signing of the contract shall be subject to issuance of the DIPA of the respective activity. All contracts shall not be designed as single-year contract, and therefore procurement process shall continue throughout multiple calendar years without limitation of contract period up to end of the GoI’s fiscal year; • Regardless of the Bank’s review requirement (prior or post), the Bank may review technical aspects of procurement documents and other non- procurement matters (terms of reference, statement of works, technical specifications, environmental documents, cost estimate, etc.) related to the procurement activity in question, if needed; • The Bank will continue to provide guidance and support to the PMU and PIU for procurement processing through the STEP. • Project Implementation Support Personnel shall not be included in this Procurement Plan. Their selection and hiring procedures shall continue to apply the GoI’s selection and hiring procedures as further defined in the POM. The Procurement Plan is a living document and can be revised if there are any changes during the implementation of the project. PROCUREMENT Indonesia : Program to Accelerate Agrarian Reform (One Map Project) PLAN General Information Country: Indonesia 2019-05-03 Bank’s Approval Date of the Original Procurement Plan: 2024-03-14 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P160661 GPN Date: Project Name: Program to Accelerate Agrarian Reform (One Map Project) Loan / Credit No: IBRD / 88970 Geospatial Information Agency Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Geospatial Data Infrastructu CW-PPIG-BIG-1 / Data Center Single Stage - One E Under Imple 2021-05-2 IBRD / 88970 re for Environmental and Na Post Request for Bids Open - National 1,337,516.00 0.00 2020-09-01 2020-12-21 2020-09-06 2020-10-18 2021-01-27 2020-11-17 2021-02-22 2020-12-22 Room Expansion nvelope mentation 1 tural Resource Management GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ID-BIG-109929-GO-RFQ / Pro Geospatial Data Infrastructu Request for Quota Single Stage - One E Under Imple curement of GNSS Data Proc IBRD / 88970 re for Environmental and Na Post Limited 71,429.00 0.00 2019-05-07 2019-06-26 2019-06-14 2019-10-12 tions nvelope mentation essing Infrastructure tural Resource Management ID-BIG-110538-GO-RFB / Pro Geospatial Data Infrastructu Single Stage - One E Under Imple curement of software and Ha IBRD / 88970 re for Environmental and Na Post Request for Bids Open - National 754,329.00 0.00 2019-05-17 2019-07-26 2020-01-22 nvelope mentation rdware for Orthorectification tural Resource Management GO-PPIG-BIG-5 / Software Pr Geospatial Data Infrastructu Single Stage - One E Under Imple ocurement for Orthorectificat IBRD / 88970 re for Environmental and Na Post Request for Bids Open - National 691,549.00 0.00 2020-07-01 2020-09-07 2020-07-06 2020-08-17 2020-10-09 2020-09-16 2020-10-16 2020-10-21 2021-01-19 nvelope mentation ion (PPRT) tural Resource Management GO-PPIG-BIG-6 / Hardware Pr Geospatial Data Infrastructu Request for Quota Single Stage - One E Under Imple ocurement for Orthorektificat IBRD / 88970 re for Environmental and Na Post Open - National 44,366.00 0.00 2020-07-06 2020-08-31 2020-11-14 tions nvelope mentation ion (PPRT) tural Resource Management Geospatial Data Infrastructu GO-PPIG-BIG-7 / Rejuvenatio Single Stage - One E IBRD / 88970 re for Environmental and Na Post Request for Bids Open - National 500,000.00 419,901.48 Signed 2020-07-01 2020-09-11 2020-07-06 2020-08-17 2020-10-13 2020-09-16 2020-10-20 2020-10-21 2020-11-15 2021-02-18 n of Network Core Switch nvelope tural Resource Management GO-PPRT-BIG-10 / Procurem Geospatial Data Infrastructu ent of Image Server and Ima Single Stage - One E Under Imple IBRD / 88970 re for Environmental and Na Post Request for Bids Open - National 278,838.00 0.00 2020-07-01 2020-10-12 2020-07-06 2020-08-17 2020-11-14 2020-09-16 2020-11-25 2020-10-21 2020-12-05 ge Analysis Package to Supp nvelope mentation tural Resource Management ort Orthorectification GO-PJKGG-BIG-1 / Procureme Geospatial Data Infrastructu Single Stage - One E Under Imple nt of Pillars, Equipment, and I IBRD / 88970 re for Environmental and Na Post Request for Bids Open - National 1,334,777.00 0.00 2020-05-18 2020-09-23 2020-05-23 2020-07-04 2020-10-24 2020-08-03 2020-11-19 2020-09-07 2021-01-25 nvelope mentation nstallation of CORS Station tural Resource Management GO-PJKGG-BIG-3 / Procureme Geospatial Data Infrastructu Request for Quota Single Stage - One E Under Imple nt of InaCORS Data Processin IBRD / 88970 re for Environmental and Na Post Limited 98,592.00 0.00 2020-04-06 2020-09-04 2020-06-01 2020-08-30 tions nvelope mentation g Storage tural Resource Management Geospatial Data Infrastructu GO-PPIG-BIG-8 / Purchasing Single Stage - One E IBRD / 88970 re for Environmental and Na Post Request for Bids Open - National 352,113.00 331,774.85 Signed 2020-07-01 2020-09-13 2020-07-06 2020-08-17 2020-10-13 2020-09-16 2020-10-20 2020-10-21 2020-11-15 2021-02-18 of IPS and IDS Devices nvelope tural Resource Management ID-BIG-357052-GO-RFB / Sca Geospatial Data Infrastructu Single Stage - One E Pending Impl le Up of Phase III DC Facility, IBRD / 88970 re for Environmental and Na Post Request for Bids Open - National 1,993,333.00 0.00 2023-04-17 2023-04-22 2023-06-03 2023-07-03 2023-08-07 2024-02-03 nvelope ementation GSCC and NOC Command Ce tural Resource Management nter Rooms ID-BIG-357053-GO-RFB / Ser Geospatial Data Infrastructu Single Stage - One E Under Imple ver, Storage, Network and Co IBRD / 88970 re for Environmental and Na Post Request for Bids Open - National 1,480,000.00 0.00 2023-04-17 2023-04-18 2023-04-22 2023-06-03 2023-05-11 2023-07-03 2023-06-15 2023-08-07 2024-02-03 nvelope mentation mmand Center Devices and tural Resource Management NOC Geospatial Data Infrastructu ID-BIG-388435-GO-RFB / Equ Single Stage - One E Under Imple IBRD / 88970 re for Environmental and Na Post Request for Bids Open - National 567,470.00 0.00 2023-08-25 2023-10-03 2023-08-30 2023-10-11 2023-10-20 2023-11-10 2023-10-27 2023-12-15 2024-06-12 ipment of HPC GXL FY 2023 nvelope mentation tural Resource Management ID-BIG-414760-GO-RFB / Pro Geospatial Data Infrastructu curement of High Performanc Single Stage - One E Pending Impl IBRD / 88970 re for Environmental and Na Post Request for Bids Open - National 830,000.00 0.00 2024-03-08 2024-03-08 2024-05-17 2024-06-16 2024-07-21 2026-01-12 e Computing (HPC) Data Cen nvelope ementation tural Resource Management tre Expansion Stage III FY 20 24 NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ID-BIG-110540-NC-RFB / GCP measurement for orthorectifi Geospatial Data Infrastructu Single Stage - One E Under Imple cation Lot-1 : Kalimantan (W IBRD / 88970 re for Environmental and Na Post Request for Bids Open - National 374,824.00 0.00 2019-05-15 2019-06-17 2019-05-20 2019-06-10 2019-07-16 2019-06-24 2019-07-24 2019-07-15 2019-11-19 nvelope mentation est, Central, East & South Kal tural Resource Management imantan) Lot-2: Sumatera (Ja mbi, Riau, South Sumatera) NCS-PPRT-BIG-1 / Provision o Geospatial Data Infrastructu f Control Point Density Data F Single Stage - One E Under Imple IBRD / 88970 re for Environmental and Na Post Request for Bids Open - National 168,393.00 0.00 2020-06-12 2020-06-12 2020-06-17 2020-07-29 2020-07-14 2020-08-28 2020-08-04 2020-10-02 2020-12-31 or Orthorectification in Provin nvelope mentation tural Resource Management ce of lot-1 (Kalimantan) and lot-2 (Sumatera) ID-BIG-388438-NC-RFB / Mai Geospatial Data Infrastructu Single Stage - One E Under Imple ntenance of Pixel Factory Sof IBRD / 88970 re for Environmental and Na Post Request for Bids Open - National 243,223.00 0.00 2023-07-25 2023-09-07 2023-07-30 2023-09-10 2023-09-26 2023-10-10 2023-10-03 2023-11-14 2024-05-12 nvelope mentation twares FY 2023 tural Resource Management ID-BIG-388436-NC-RFB / Mai Geospatial Data Infrastructu Single Stage - One E Under Imple ntenance of Catalyst Enterpri IBRD / 88970 re for Environmental and Na Post Request for Bids Open - National 92,883.00 0.00 2023-08-09 2023-09-18 2023-08-14 2023-09-25 2023-10-09 2023-10-25 2023-10-17 2023-11-29 2024-05-27 nvelope mentation se (GXL) Softwares FY 2023 tural Resource Management Page 1 CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ID-BIG-110547-CS-QCBS / Co Geospatial Data Infrastructu nsultancy Services for Prepar Quality And Cost- Under Implement IBRD / 88970 re for Environmental and Na Post Open - National 389,750.00 0.00 2019-06-10 2019-09-17 2019-06-12 2019-07-17 2019-10-11 2019-08-07 2019-11-09 2019-08-21 2021-11-15 2019-08-31 2019-09-21 2022-10-12 ation of Technical design and Based Selection ation tural Resource Management Post Management of CORS ID-BIG-110541-CS-QCBS / Co Geospatial Data Infrastructu Quality And Cost- Pending Impleme nsultancy Services for Prepar IBRD / 88970 re for Environmental and Na Post Open - National 100,000.00 0.00 2019-05-15 2019-05-17 2019-06-21 2019-07-01 2019-07-15 2019-07-29 2019-08-19 2020-02-15 Based Selection ntation ation and design of NSDI Port tural Resource Management al ID-BIG-110542-CS-QCBS / Co Geospatial Data Infrastructu Quality And Cost- Pending Impleme nsultancy Services for Prepar IBRD / 88970 re for Environmental and Na Post Open - National 100,000.00 0.00 2019-05-15 2019-05-17 2019-06-21 2019-07-12 2019-07-26 2019-08-05 2019-08-26 2020-08-25 Based Selection ntation ation and design of NSDI Dat tural Resource Management a Center Geospatial Data Infrastructu ID-BIG-199565-CS-QCBS / N Quality And Cost- Under Implement IBRD / 88970 re for Environmental and Na Post Open - National 307,394.00 0.00 2020-07-10 2020-10-13 2020-07-31 2020-09-13 2020-10-11 2020-11-10 2020-12-15 2021-01-19 2022-01-19 SDI System Development Based Selection ation tural Resource Management Geospatial Data Infrastructu ID-BIG-221570-CS-CQS / NS Consultant Qualifi Under Implement IBRD / 88970 re for Environmental and Na Post Limited 238,000.00 0.00 2021-03-01 2021-07-30 2021-03-15 2021-09-28 2021-04-14 2021-05-19 2022-05-19 DI System Development cation Selection ation tural Resource Management ID-BIG-110544-CS-QCBS / Co Geospatial Data Infrastructu Quality And Cost- nsultant Supervision of GCP IBRD / 88970 re for Environmental and Na Post Open - National 210,847.00 0.00 Canceled 2019-05-15 2019-05-17 2019-06-21 2019-07-12 2019-07-26 2019-08-05 2019-08-26 2020-02-22 Based Selection measurement for orthorectifi tural Resource Management cation INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ID-BIG-357058-CS-INDV / HS Geospatial Data Infrastructu Individual Consult Under Implement E Expert For DC Facillity Acti IBRD / 88970 re for Environmental and Na Post Open - National 6,600.00 0.00 2023-04-17 2023-08-21 2023-06-05 2023-06-26 2023-07-31 2024-01-27 ant Selection ation vity Phase III tural Resource Management ID-BIG-357059-CS-INDV / Ex Geospatial Data Infrastructu Individual Consult Under Implement pert Data Center For DC Facil IBRD / 88970 re for Environmental and Na Post Open - National 6,600.00 0.00 2023-04-17 2023-08-21 2023-06-05 2023-06-26 2023-07-31 2024-01-27 ant Selection ation ity Activity Phase III tural Resource Management ID-BIG-357061-CS-INDV / Ex Geospatial Data Infrastructu Individual Consult Under Implement pert Electrical System For DC IBRD / 88970 re for Environmental and Na Post Open - National 6,600.00 0.00 2023-04-17 2023-08-21 2023-06-05 2023-06-26 2023-07-31 2024-01-27 ant Selection ation Facility Phase III tural Resource Management Page 2