Procurement Plan A. GENERAL 1. Project Information: - Country: Lao PDR - Borrower/Recipient: Lao PDR - Project Name: Lao Road Sector Project 2 (LRSP 2) – Additional Finance - Project Number: P158504 - Project Implementation Agency: Ministry of Public Works and Transport Department of Finance (DoF) will take overall responsibility for procurement management. Each procurement package will be conducted by Department and DPWT concern including: Department of Roads (DOR), Department of Transport (DOT), Public Works and Transport Research Institute (PTRI), Public Works and Transport Training Institute (PTTI), Department of Personnel (DoP), Department of Inspection (DOI) and Cabinet Office in Ministry of Public Works & Transport (MPWT) and Department of Public Works & Transport (DPWTs) in the provinces. 2. Date of the Procurement Plan: • November 2022 3. Period covered by this Procurement Plan: 30 months (from the effectiveness date) B. PREAMBLE In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (Jul. 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the Public Procurement Law No. 30/NA, dated 2 Nov. 2017 and the Instruction on Implementation Public Procurement Law No. 0477/MOF, dated 13 February 2019, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions: a) The request for bids/request for proposals document shall require that bidders/proposers submitting bids/proposals present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, Bank Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights; b) Information related to award of contract including reasons for rejection of unsuccessful bidders shall be published on the implementing agency websites and/or newspaper of wide circulation. c) All complaints on procurement related matters including complaints arising from procurement under Bank financed Projects whilst using National Procurement Procedures shall be dealt with in accordance with Article 33 of the Procurement Decree. Borrower shall put in place an effective complaint review mechanism for dealing with procurement related complaints and shall disclose the details in all the bidding documents. All complaints shall be recorded by the Borrower in the appropriate tracking and monitoring system, as agreed between the Bank and the Borrower. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. Not Applicable. Procurement of Second-Hand Goods as specified under paragraph 5.11 of the Procurement Regulations - is allowed for those contracts identified in the Procurement Plan tables. Not Applicable. Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). - Goods: is applicable for those contracts identified in the Procurement Plan tables; - Works: is applicable for those contracts identified in the Procurement Plan tables. Sub-project Procurement Plan will be prepared separately each year and sent to the World Bank for information and reference. All activities under sub-projects will be subjected to the World Bank’s post review and will not be posted on the STEP. C. OTHER RELEVANT PROCUREMENT INFORMATION I. Works and Goods and Non-Consultant Services 1.1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Annex II of the Procurement Regulations: Procurement Method Thresholds Prior Review Thresholds Applicable Applicable Category thresholds Remarks thresholds Remarks (in US$ (in US$) equivalent) Works RFB through Open ≥ 2.0 million – Above US$ 10 million - International market approach RFB through ≥ 200,000 < 2.0 Open National – None - million market approach Request for < 200,000 – None - Quotation No threshold; This has not been meet Same as for foreseen at the Direct Selection None requirements of competitive selection project preparation regulations 7.13- stage. 7.15 Goods and Non-Consulting Services RFB through Open ≥ 0.6 million – Above US$ 2 million - International market approach RFB through ≥ 100,000 < 0.6 Open National - None Risk-based approach million market approach Request for < 100,000 None Quotation No threshold; This has not been meet Same as for foreseen at the Direct Selection None requirements of competitive selection project preparation regulations 7.13- stage. 7.15 1.2. Procurement packages for Works, Goods and Non-Consulting Services (prior and post reviews) with method and Time Schedule Ref. Contract (Description) Estimat Procure- Review Expected Comments No. ed Cost ment by Bank Bid USD Method Opening million Date Civil Works CW- Y1 - Performance-Based Total 0.782; PHO- Routine Maintenance of IDA (12%); PBC- Provincial and District RF (65%); 0,094 NCB Post Aug. 2018 01 roads in Phongsaly GoL (23%); province (Bounneua and Completed Bountai Districts) CW- Y1 - Performance-Based Total 1.043; PHO- Routine Maintenance of IDA (12%); PBC- Provincial and District RF (65%); 02 Roads in Phongsaly 0,125 NCB Post Aug. 2018 GoL (23%); province (Khoua, Completed Samphanh and May Districts) CW- Y1 - Performance-Based Total 1.226; OUD- Routine Maintenance of IDA (12%); PBC- provincial and district roads 0,147 NCB Post Aug. 2018 RF (65%); 01 in Oudomxay province (La, GoL (23%); Xay and Namor districts) Completed CW- Y1 - Performance-Based Total 0.894; 0,107 NCB Post Aug. 2018 OUD- Routine Maintenance of IDA (12%); PBC- Provincial and District RF (65%); 02 roads in Oudomxay GoL (23%); province (Nga District) Completed CW- Y1 - Performance-Based Total 0.680; OUD- Routine Maintenance of IDA (12%); PBC- Provincial and District RF (65%); 0,082 NCB Post Aug. 2018 03 Roads in Oudomxay GoL (23%); province (Beng, Houn and Completed Pakbeng Districts) CW- Y1 - Performance-Based Total 0.918; XAY- Routine Maintenance of IDA (12%); PBC- Provincial and District RF (65%); 0,110 NCB Post Aug. 2018 01 Roads in Xayabuly province GoL (23%); (Khob, Xienghone and Completed Hongsa Districts) CW- Y1 - Performance-Based Total 0.612; XAY- Routine Maintenance of IDA (12%); PBC- Provincial and District RF (65%); 0,073 NCB Post Aug. 2018 02 Roads in Xayabuly province GoL (23%); (Xaysathan, Phieng, Paklai Completed and Bortene Districts) CW- Y1 - Performance-Based Total 0.759; HOU- Routine Maintenance of IDA (12%); PBC- Provincial and District RF (65%); 0,091 NCB Post Aug. 2018 01 Roads in Huaphanh GoL (23%); province (Xamnue and Completed Viengxai Districts) CW- Y1 - Performance-Based Total 0.598; HOU- Routine Maintenance of IDA (12%); PBC- Provincial and District RF (65%); 0,072 NCB Post Aug. 2018 02 Roads in Huaphanh GoL (23%); province (Hoamoueng and Completed Viengthong Districts) CW- Y1 - Performance-Based Total 0.466; XIE- Routine Maintenance of IDA (12%); PBC- provincial and district roads 0,056 NCB Post Aug. 2018 RF (65%); 01 in Xiengkhuang province GoL (23%); (Pek and Kham districts) Completed CW- Y1 - Performance-Based Total 0.379; XIE- Routine Maintenance of IDA (12%); PBC- Provincial and District 0,045 NCB Post Aug. 2018 RF (65%); 02 Roads in Xiengkhuang GoL (23%); province (Poukoud District) Completed CW- Y1 - Performance-Based Total 0.531; BOL- Routine Maintenance of IDA (12%); PBC- Provincial and District RF (65%); 01 Roads in Bolikhamxay 0,064 NCB Post Aug. 2018 GoL (23%); province (Paksanh, Completed Thaphabath and Bolikhanh Districts) CW- Y2023-2025 - Performance- IDA (50%); PHO- Based Routine Maintenance RF (27%); PBC- of Provincial and District GoL (23%); 03 roads in Phongsaly January. Bid opening 0,790 NCB Post province (Phongsaly, Yod 2023 March Ou and Bountai Districts) 2023, Bid Evaluation in process CW- Y2023-2025 - Performance- IDA (50%); PHO- Based Routine Maintenance RF (27%); PBC- of Provincial and District GoL (23%); 04 Roads in Phongsaly Bid opening 0,850 NCB Post January 2023 province (Khoua, and May March Districts) 2023, Bid Evaluation in process CW- Y2023-2025 - Performance- IDA (50%); OUD- Based Routine Maintenance RF (27%); PBC- of Provincial and District GoL (23%); RM-04 Roads in Oudomxay Bid opening 0,867 NCB Post January 2023 province (Xay,La,Beng, March Houn and Pakbeng 2023, Bid Districts) Evaluation in process CW- Y2023-2025 - Performance- IDA (50%); OUD- Based Routine Maintenance RF (27%); PBC- of Provincial and District GoL (23%); RM-05 Roads in Oudomxay Bid opening 0,423 NCB Post January 2023 province (Nga District) March 2023, Bid Evaluation in process CW- Y2023-2025 - Performance- IDA (50%); XAY- Based Routine Maintenance RF (27%); PBC- of Provincial and District GoL (23%); 03 Roads in Xayabouly Bid opening 0,600 NCB Post January 2023 province (Khope, March Xienghone Districts) 2023, Bid Evaluation in process CW- Y2023-2025 - Performance- IDA (50%); XAY- Based Routine Maintenance RF (27%); PBC- of Provincial and District GoL (23%); 04 Roads in Xayabouly Bid opening 0,421 NCB Post January 2023 province (Ngern, Hongsa March Districts) 2023, Bid Evaluation in process CW- Y2023-2025 - Performance- IDA (50%); XAY- Based Routine Maintenance RF (27%); PBC- of Provincial and District GoL (23%); 05 Roads in Xayabouly Bid opening 0,340 NCB Post January 2023 province (Xayabouly, March Xaysathan, Phieng 2023, Bid Districts) Evaluation in process CW- Y2023-2025 - Performance- IDA (50%); XAY- Based Routine Maintenance RF (27%); PBC- of Provincial and District GoL (23%); 06 Roads in Xayabouly Bid opening 0,592 NCB Post January 2023 province (Paklai, Kenthao, March Boten, THongmixay 2023, Bid Districts) Evaluation in process CW- Y2023-2025 - Performance- IDA (50%); HOU- Based Routine Maintenance 0,848 NCB Post Jan. 2023 RF (27%); of Provincial and District GoL (23%); PBC- Roads in Houaphan Bid opening 03 province (Xamnuea, Xamtai March and Kouan Districts) 2023, Bid Evaluation in process CW- Y2023-2025 - Performance- IDA (50%); HOU- Based Routine Maintenance RF (27%); PBC- of Provincial and District GoL (23%); 04 Roads in Houaphan Bid opening 0,773 NCB Post Jan. 2023 province (Houamuang, March Xone, Hiem and Xamnuea 2023, Bid Districts) Evaluation in process CW- Y2023-2025 - Performance- IDA (50%); XIE- Based Routine Maintenance RF (27%); PBC- of provincial and district GoL (23%); 03 roads in Xiengkhuang Bid opening 1,059 NCB Post Jan. 2023 province (Pek and March Phoukoud districts) 2023, Bid Evaluation in process CW- Y2023-2025 - Performance- IDA (50%); XIE- Based Routine Maintenance RF (27%); PBC- of Provincial and District GoL (23%); 04 Roads in Xiengkhuang Bid opening 0,713 NCB Post Jan. 2023 province (Paek, Khoun and March Kham District) 2023, Bid Evaluation in process CW- Y2023-2025 - Performance- IDA (50%); BOL- Based Routine Maintenance RF (27%); PBC- of Provincial and District GoL (23%); 02 Roads in Bolikhamxay January. Bid opening 1,439 NCB Post province (Paksanh, 2023 March Thaphabath ,Bolikhanh,Kha 2023, Bid mkeut and Viengthong Evaluation Districts) in process Periodic Maintenance and Spot Improvement CW- Climate resilient IDA PHO- maintenance of Road No. Completed 1,412 NCB Post Apr. 2019 01- 1201 LOT 1 CW- Climate resilient IDA PHO- maintenance of Road No. Completed 1,623 NCB Post Apr. 2019 01- 1201 LOT 2 CW- Climate resilient IDA; OUD- maintenance of Road No. 1,813 NCB Post May 2018 Completed 01 1851 CW- Climate resilient IDA OUD- maintenance of Road No. 1,649 NCB Post May 2018 Completed 02 1804 CW- Climate resilient IDA XAY- maintenance of Road No. 1,194 NCB Post May 2018 Completed 01 3613 CW- Climate resilient IDA XAY- maintenance of Road No. 1,990 NCB Post May 2018 Completed 02 3602 CW- Climate resilient IDA; BOL- maintenance of Road No. 1,157 NCB Post May 2018 Completed 01 5154 CW- Climate resilient NDF; HOU- maintenance of Road No. 1,453 Dec. 2018 Completed 01 3222 CW- Climate resilient NDF; HOU- maintenance of Road No. 1,420 Dec. 2018 Completed 02 3249 CW- Climate resilient NDF; XIE-01 maintenance of Road No. 0,608 Dec. 2018 Completed 4041 CW- Climate resilient NDF; XIE-02 maintenance of Road No. 1,803 Dec. 2018 Completed 3907 CW- Climate resilient NDF; XIE-03 maintenance of Road No. 0,771 Dec. 2018 Completed 3904 CW- Climate resilient EIB; PHO- maintenance of Road No. Completed 1,167 Jan. 2020 02/ Lot 1229 1 CW- Climate resilient EIB; PHO- maintenance of Road No. Completed 1,281 Jan. 2020 02/ Lot 1229 2 CW- Nam Le Bridge/Road No. EIB; PHO- 1229 Completed 0,841 NCB- 03 CW- Climate resilient EIB; OUD- maintenance of Road No. 0,888 Aug. 2020 Completed 03 1862 CW- Climate resilient EIB; OUD- maintenance of Road No. 1,143 Aug. 2020 Completed 04 1875 CW- Climate resilient EIB; XAY- maintenance of Road No. Completed 0,858 May 2020 03/Lot 3822 1 CW- Climate resilient EIB; XAY- maintenance of Road No. Completed 1,296 May 2020 03/Lot 3822 2 CW- Climate resilient EIB; XAY- maintenance of Road No. 1,656 May 2020 Completed 04 3604 CW- Climate resilient EIB; HOU- maintenance of Road No. 1,251 Dec. 2020 Completed 03 3205 CW- Climate resilient EIB; HOU- maintenance of Road No. 1,318 Jul. 2020 Completed 04 3209 CW- Climate resilient EIB; HOU- maintenance of Road No. 0,771 Jul. 2020 Completed 05 3249 CW- Climate resilient EIB; XIE-04 maintenance of Road No. 2,329 May 2020 Completed 3903 CW- Climate resilient EIB; BOL- maintenance of Road No. 0,954 Aug. 2020 Completed 02 5103 CW- Climate resilient EIB; BOL- maintenance of Road No. 0,664 Aug. 2020 Completed 03 5107 CW- Climate resilient EIB; BOL- maintenance of Road No. 1,276 Aug. 2020 Completed 04 5102 CW- Climate resilient EIB; BOL- maintenance of Road No. 1,057 Aug. 2020 Completed 04 5102 CW- Climate resilient EIB, PHO- maintenance of Road No. contract 1,980 NCB Post Sep. 2021 NCB- 1203 signing 04 process. CW- Climate resilient EIB, OUD- maintenance of Road No. contract 1,628 NCB Post Sep. 2021 NCB- 1857 signed in 05 April 2023 CW- Climate resilient EIB, XAY- maintenance of Road No. contract NCB- 3634 0,856 NCB Post Sep. 2021 signed in 05 August 2022 CW- Climate resilient EIB, XAY- maintenance of Road No. contract NCB- 3609 0,567 NCB Post Sep. 2021 signed in 06 August 2022 CW- Climate resilient EIB, HOU- maintenance of Road No. contract 0,913 NCB Post Sep. 2021 NCB- 3223 signed in 06 June 2022 CW- Climate resilient EIB, HOU- maintenance of Road No. contract 0,157 NCB Post Sep. 2021 NCB- 3222 signed in 06 June 2022 CW- Climate resilient EIB, HOU- maintenance of Road No. contract 0,157 NCB Post Sep. 2021 NCB- 3249 signed in 06 June 2022. CW- Climate resilient EIB, XIE- maintenance of Road No. contract 0,291 NCB Post Sep. 2021 NCB- 3907 signed in 05 April 2023. CW- Climate resilient EIB, XIE- maintenance of Road No. contract 0,047 NCB Post Sep. 2021 NCB- 3907 signed in 05 April 2023. CW- Climate resilient EIB, XIE- maintenance of Road No. contract 0,066 NCB Post Sep. 2021 NCB- 4041 signed in 05 April 2023. CW- Climate resilient NDF, XIE- maintenance of Road No. contract 0,562 NCB Post Sep. 2021 NCB- 3904 signed in 06 April 2023. CW- Climate resilient EIB, BOL- maintenance of Road No. contract NCB- 5161 1,294 NCB Post Sep. 2021 signed in 05 March 2023. Tropical Storm Son-Tinh Emergency Repair and Disaster Recovery ATP01 Emergency maintenance IDA; -2019- and disaster recovery for Completed 0,360 NCB Post Mar. 2019 EM22- NR18A – roads – Lot 1 NR03 ATP01 Emergency maintenance IDA; -2019- and disaster recovery for Competed 0,418 NCB Post Mar. 2019 EM22- NR18A – roads – Lot 2 NR04 Improvement and maintenance of NR13S AF-W- Improvement and IDA ($17m) PACKA Maintenance of NR13S – RF ($3.5m) RFB GE1- Section (length 40 km) May 2020 Completed 20,500 (Internatio Prior OPBRC from km 71 to km 111 Mar. 2021 nal) 001/20 including bridges 20 AF-W- Improvement and EIB 01 Maintenance of NR13S - RFB ($22.19m) Section from KM 111 to 28,130 (Internatio Prior RF KM190 nal) ($5.94m) Completed AF-W- Improvement and AIIB 01 Maintenance of NR13S - RFB ($23.67m) Section from KM 190 to 29,690 (Internatio Prior RF KM268 nal) ($6.02m) Completed AF-W- Improvement and EIB 01 Maintenance of NR13S - RFB ($19.98m) Section from KM268 to 24,980 (Internatio Prior RF KM346 nal) ($5.00m) Completed Works W- Office refurbishment for IDA; DPC- installing VC system 0,005 RFG Post Jul. 2020 Completed 01 Goods G-12 24 off-road bikes and 37 IDA; city bikes for DoR and Completed; DPWT 0,170 NCB Post May 2018 KP Co., Ltd; NCX Co., Ltd G-04 Testing equipment for DoI IDA; Completed; 0,034 Shopping Post May 2018 DDP Chaleunxap Co., Ltd G-11 Computers Server IDA; equipment for Network 0,355 NCB Post Sep. 2019 Completed Development for ICT CS Intellect (Lao) Limited G-13 Equipment and supplies for IDA; Road Safety Campaign Completed; 0,098 Shopping Post May 2018 NSV Computer Co., Ltd G-14 Equipment for back up IDA; procurement information Completed; and for DPWT - Phongsaly VOA Office 0,024 Shopping Post Aug. 2018 Automation Import- Export Co., Ltd G-16 4 vehicles for supervision IDA; 0,180 NCB Post Jul. 2019 team Completed G-17 1 SUV for financial IDA; management and 1 car for 0,095 Shopping Post Oct. 2019 Completed project management team G-18 Equipment for DoF, DPC IDA; 0,045 Shopping Post Nov. 2019 and DoP Completed G-19 7 Motorcycles for financial IDA; 0,014 Shopping Post Nov. 2019 management Completed G-21 Vehicle for implementation IDA; 0,050 Shopping Post Mar. 2020 of Safeguards works Completed G-22 IDA; VC equipment for DPC 0,020 Shopping Post Jul. 2020 Completed G-23 Equipment and tools for IDA; 0,026 Shopping Post Nov. 2020 EDPD Completed G-24 Office equipment for road IDA; safety (computers, laptops 0,050 Shopping Post Nov. 2020 completed and printers) C2-33 Drones (9sets) for PTRI IDA; 0,036 RFQ Post Completed C2-34 VC Equipment's (8sets) for IDA; 0,030 RFQ Post PTRI Completed AF-G- Rescue equipment 15boats RFB IDA; 0,200 Post Apr. 2020 01 (National) completed AF-G- 4 Vehicles RFB IDA, 0,180 Post Apr. 2020 02 (National) completed AF-G- Office equipment for NR13 IDA; 0,024 Shopping Post Apr. 2021 03 PMU and DoI Completed IT Equipment for IDA, AF-G- Permanent Secretary Office completed 0,020 Shopping Post Dec. 2021 04 and Department of Personal AF-G- Office Equipment for DPC IDA; 0,040 Shopping Post Dec. 2021 05 Completed Road Safety Public IDA; AF-G- Awareness Campaign Year 0,020 Shopping Post Dec. 2021 Completed 06 2022 Non-consulting service NC2- Server and internet rental IDA; 0.050 SSS Post Nov. 2020 01 at LANIC Completed Total of Civil Works and Goods 160,785 Notes: - RFQ: Request for Quotations - RFB: Request for Bids II. Selection of Consultants 2.1 Prior Review Threshold: Selection decisions subject to Prior Review by the Bank as stated in Annex II of the Procurement Regulations: Procurement Method Thresholds Prior Review Thresholds Applicable Applicable Category thresholds Remarks thresholds Remarks (in US$ (in US$, millions) equivalent) Methods for consulting services QCBS, QBS, FBS, are specified in LCS (Using the most ≥ 300,000 paragraph 7.3 to ≥ 1.0 million Risk-based approach appropriate market 7.12, Section VII of approach) the Procurement Regulations. CQS (Open or limited competition QCBS, QBS, FBS, through national or LCS) can be applied international market < 300,000 for contracts with None approach, specified value under in the PP and agreed $300,000 with the Bank. No threshold; meet This has not been Same as for Direct Selection of requirements of foreseen at the None competitive firms regulations 7.13- project preparation selection 7.15 stage. Essential individual assignments will be defined in the ≥ 300,000 and for Procurement Plan the positions as Individual N/A depending on agreed with the specified in the PP Risk-based approach Consultants nature of services Bank and in line with agreed with the regulations 7.34- Bank 7.39 using the most appropriate market approach 2.2 Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than US$ 200,000 equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 7.1, Section VII of the Procurement Regulations. 2.3 Consultancy Assignments with Selection Methods and Time Schedule Ref. Description of Estimate Selectio Review by Expected Comment No. Assignment d Cost n Bank Proposals US$ Method Submission million Date Component 1: Climate Resilience Road maintenance Ref. Description of Estimate Selectio Review by Expected Comment No. Assignment d Cost n Bank Proposals US$ Method Submission million Date C1-01 TA for design and NDF; supervision for Completed; 3,000 QCBS Prior Apr. 2017 provincial and district SweRoad roads C1-02 Consulting Services IDA; for Detailed Competitive Engineering Design under C2-01 (DED) of Improvement 0,650 SSS Post Jun. 2019 below and Maintenance of Completed; NR13 South from KM LTEC 70 to KM 346 AF-C1-01 Construction EIB; Supervision for NR13S completed 4,000 QCBS Prior Feb. 2020 improvement and LASA; maintenance Component 2: Institutional Strengthening C2-01 TA for climate resilient NDF; road asset Completed; management and Sweco preparation of Climate Resilience 2,700 QCBS Prior Apr. 2017 Maintenance and Preservation Program for the National Road Network C2-02 Transport Sector IDA; Policy advisor Completed; 0,250 IC Prior May 2018 Mr. Andrew Clive Southern C2-03 Planning Framework IDA; Development Completed; 0,100 IC Post Aug. 2017 Consultant Mr. Hiromi Osada C2-04 Internal Control IDA; Advisor Completed; Mr 0,100 IC Post Jul.2017 Nitiphone Savanvongtho ng C2-05 Quality Assurance IDA; Advisor Completed; 0,100 IC Post Jul. 2017 Mr. Sisamay Inthivong C2-07 Financial Management IDA; Consultant – Northern Completed; Ms. 0,100 IC Post Jul.2017 Phetlamngeun Phommachan h C2-09 Financial Management IDA; Consultant – Southern 0,100 IC Post Jul.2017 Completed; Mr. Lock Lasy C2-11 Environment and IDA; Social Consultant 0,065 IC Post Jul. 2018 Completed; (Local) Ref. Description of Estimate Selectio Review by Expected Comment No. Assignment d Cost n Bank Proposals US$ Method Submission million Date Ms. Khamsy Chansamai C2-13 Human Resource IDA; Development Completed; 0,080 IC Post Jun. 2018 Consultant Mr. Voravate Chonlasin C2-14 Technical assistant to IDA; NSCT (Road Safety Completed; 0,100 IC Post Jul. 2017 Audit Strategy and Mr. Martine Action Plan) Small C2-15 Road safety audit IDA; manual development Completed; 0,200 IC Prior Jul. 2017 Mr. Phillip Jordan C2-20 Local firm for Social IDA; and Environment Completed; 0,290 CQS Prior Apr. 2017 surveys for NR13; Lao Consulting Group C2-21 International IDA; Environment Continuation; Consultant for NR13 0,076 SSS Post Apr. 2017 Completed; Mr. Nicholas Skinner C2-22 Planning Analyst IDA; Completed; 0,150 IC Post Aug. 2017 Mr. Vivath Sovaly C2-23 International IDA; Consultant for MPWT's Completed; IRAM Database, e- Aapo Kuusela Archive and Website 0,080 IC Post Dec. 2018 Needs Assessment, ToR Design and Implementation Supervision C2-28 Consulting Firm for IDA; Upgrading IRAM Completed; software at MPWT the association of 0,298 CQS Post Sep. 2019 Sirway (Sweden) and LCG (Lao PDR, Sub- Consultant) C2-29 Consulting Firm for IDA; MPWT Website Completed; CS 0,033 CQS Post Sep. 2019 upgrade Intellect (Lao) Limited C2-30 Consulting Firm for IDA; Development of e- Completed; CS 0,221 CQS Post Sep. 2019 Archive System for Intellect (Lao) MPWT Limited C2-31 National Financial IDA; 0,080 IC Post May 2020 Management Completed Ref. Description of Estimate Selectio Review by Expected Comment No. Assignment d Cost n Bank Proposals US$ Method Submission million Date Specialist to Support DoF C2-32 National Safeguard IDA; Contract Coordinator Signed, 0,065 IC Post Souktaly Vannavongsy AF-C2-01 Senior Environment IDA; 0,040 IC Post May 2020 and Social Consultant Completed AF-C2-02 Junior Environment IDA; 0,060 IC Post May 2020 and Social Consultant Completed AF-C2-03 Transport sector IDA; Contract policy adviser Signed, Mr. 0,122 IC Post Apr. 2021 Santi Sayakoumma nne AF-C2-04 Planning framework IDA; development 0,130 IC Post Apr. 2021 Completed consultant AF-C2-05 Planning Analyst IDA; 0,060 IC Post Jul. 2021 Completed AF-C2-07 National Financial IDA; Contract Consultant for NR13S Signed; Ms. 0,070 IC Post Apr. 2021 Somkhane Kettavong AF-C2-08 Administration IDA; Contract Consultant Signed; Ms. 0,036 IC Post Jun. 2021 Deuanlavanh Chanthavongi AF-C2-09 Financial internal IDA; inspection consultant 0,099 DS Post Jun. 2021 Completed Local Consultant AF-C2-10 Contract management consultant for road IDA; 0,084 IC Post Jul. 2021 improvement and Completed maintenance AF-C2-11 Road Improvement IDA; Contract and maintenance for signed, Mr. engineer for 0,060 IC Post Jul. 2021 Anousith Bolikhamxay Province Vongphachan h AF-C2-12 Road Improvement IDA; Contract and maintenance for signed, Mr. engineer for 0,060 IC Post Jul. 2021 Bounchanh Houaphan Province Somchanmavo ng AF-C2-13 Road Improvement IDA; Contract and maintenance for signed, Mr. 0,060 IC Post Jul. 2021 engineer for Khamla Phongsaly Province Phimmasone AF-C2-14 Road Improvement IDA; Contract and maintenance for signed, Mr. 0,060 IC Post Jul. 2021 engineer for Xayabuly Keoviengsith Province Sibounma AF-C2-15 International IDA; Contract 0,060 DS Post Environmental Risk Signed, Mr. Ref. Description of Estimate Selectio Review by Expected Comment No. Assignment d Cost n Bank Proposals US$ Method Submission million Date Management Victoriano Consultant for PTRI Macasaquit AF-C2-16 National IDA; Contract Environmental Risk Signed; Ms. 0,100 DS Post Management Khamsy Consultant for PTRI Chansamai AF-C2-17 Social Risk IDA; Contract Management 0,050 DS Post Signed, Mr. Consultant Lilao Bouapao AF-C2-18 Community IDA; Contract Engagement Signed, Mr. Consultant for PTRI 0,025 DS Post Sonedalinh Phoumvongxa y AF-C2-19 Field Survey IDA; Contract Consultant for PTRI Signed, Mr. 0,025 DS Post Santi Sayakoumma nne AF-C2- Consulting Services 20 for Overloading IDA; under 0,250 CQS Post Sep. 2022 Control Study and negotiation Action Plan AF-C2- National Financial 21 Management 0,018 DS Post Nov 2022 Cancelled Consultant to support DPF Component 3: Project management C3-02 Financial Auditor IDA; Completed; 0,200 CQS Post Jul. 2017 Ernst & Young Lao Co. Ltd C3-03 Technical Auditor IDA; Mr. Zoran 0,300 IC Prior Dec. 2017 Veselinovic; Resigned C3-04 International; Mr. IDA; Contract Mohammad Abdullah 0,300 IC Prior Jun. 2017 is terminated Sadeque C3-06 Procurement IDA; Consultant (National) Completed; 0,150 IC Post Jul. 2017 Mr. Chittachone Volasay C3-05 National Coordination IDA; Advisor Continuation; 0,105 SSS Post Jul.2017 Completed; Mr. Khamkhai Phearkeo C3-08 Procurement IDA; Specialist Completed; 0,250 IC Prior Jul. 2018 Mr. Marian Nenita Ref. Description of Estimate Selectio Review by Expected Comment No. Assignment d Cost n Bank Proposals US$ Method Submission million Date C3-09 Technical Auditor IDA; Completed; 0,300 IC Prior Apr. 2019 Mr. Benjamin O Olobo AF-C3-02 National procurement IDA; Contract Consultant Signed Mr. 0,070 IC Post Jun. 2020 Sengphet Thanongsakd AF-C3-03 National Coordination IDA; Advisor Continuation; 0,165 SSS Post Completed; Mr. Khamkhai Phearkeo AF-C3-04 International IDA; Procurement 0,100 DS Post Sep. 2020 Completed Mr. Consultant Marian Nenita AF-C3-05 International Project IDA; Contract Implementation Signed, Mr. 0,050 IC/DS Post Feb. 2022 Support Consultant Victoriano Macasaquit AF-C3-06 Financial Auditor ( IDA; Contract FY2023, 2024 and 0,060 DS Post Nov. 2022 signing 2025) process AF-C3-07 Technical Auditor to IDA; Contract support DOI 0,100 DS Post Dec. 2022 signing process Total Consulting Services 16,457 Grand Total 177,242 Notes: - IC : Individual Consultant - DS: Direct Selection - CQS: Consultant’s Qualifications Based Selection - QCBS: Quality and Cost-Based Selection * Although these packages are subject to procurement Post Review, the World Bank will do prior technical review or the technical proposals evaluation reports and draft negotiated contracts. To select project financial audit, project implementing agencies shall send their RFPs to all three qualified firms namely PwC, KPMG and EY; that are acceptable audit firms for Bank financed projects in the Lao PDR. Means advertising and EOI for this package is not required. PROCUREMENT Lao People's Democratic Republic : Lao Road Sector Project 2 (LRSP2) PLAN General Information Country: Lao People's Democratic Republic Bank’s Approval Date of the Original Procurement Plan: 2017-03-02 2024-03-05 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P158504 GPN Date: 2017-03-01 Project Name: Lao Road Sector Project 2 (LRSP2) Loan / Credit No: IDA / 59200, IDA / 65150 Ministry of Public Works and Transport Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned CW-PHO-01 LOT 2 / Climate Component 1: Climate Resili Single Stage - One E 2020-01-1 IDA / 59200 Post Request for Bids Open - National 995,200.00 0.00 Canceled 2018-04-05 2018-03-26 2018-04-10 2018-05-22 2018-06-04 2018-06-21 2018-07-26 Resilient Maintenance of Roa ent Road Maintenance nvelope 7 d No. 1201 CW-PHO-01 LOT 1 / Climate Component 1: Climate Resili Single Stage - One E 2020-01-1 IDA / 59200 Post Request for Bids Open - National 1,533,249.00 0.00 Canceled 2018-04-05 2018-03-26 2018-04-10 2018-05-22 2018-06-04 2018-06-21 2018-07-26 Resilient Maintenance of Roa ent Road Maintenance nvelope 7 d No. 1201 CW-OUD-01 / Climate Resilie Component 1: Climate Resili Single Stage - One E 1,227,397.9 2020-01-1 IDA / 59200 Post Request for Bids Open - National 1,813,051.00 Signed 2018-04-05 2018-03-26 2018-04-10 2018-05-22 2018-06-04 2018-06-21 2018-06-04 2018-07-26 2019-06-18 nt Maintenance of Road No. ent Road Maintenance nvelope 2 7 1851 CW-OUD-02 / Climate Resilie Component 1: Climate Resili Single Stage - One E 1,634,810.6 2020-01-1 IDA / 59200 Post Request for Bids Open - National 1,649,127.00 Signed 2018-04-05 2018-06-04 2018-04-10 2018-05-22 2018-06-04 2018-06-21 2018-06-04 2018-07-26 2019-03-13 nt Maintenance of Road No. ent Road Maintenance nvelope 4 7 1804 CW-XAY-01 / Climate Resilie Component 1: Climate Resili Single Stage - One E 1,131,393.2 2020-01-1 IDA / 59200 Post Request for Bids Open - National 1,194,132.00 Signed 2018-04-05 2018-03-26 2018-04-10 2018-05-22 2018-06-04 2018-06-21 2018-06-04 2018-07-26 2019-02-23 nt Maintenance of Road No. ent Road Maintenance nvelope 1 7 3613 CW-XAY-02 / Climate Resilie Component 1: Climate Resili Single Stage - One E 1,759,098.9 2020-01-1 IDA / 59200 Post Request for Bids Open - National 1,990,000.00 Signed 2018-04-05 2018-06-04 2018-04-10 2018-05-22 2018-06-04 2018-06-21 2018-03-28 2018-07-26 2019-02-23 nt Maintenance of Road No. ent Road Maintenance nvelope 4 7 3602 CW-BOL-01 / Climate Resilie Component 1: Climate Resili Single Stage - One E 2020-01-1 IDA / 59200 Post Request for Bids Open - National 1,156,835.00 830,327.44 Signed 2018-04-05 2018-03-26 2018-04-10 2018-05-22 2018-06-04 2018-06-21 2018-06-04 2018-07-26 2018-12-11 nt Maintenance of Road No. ent Road Maintenance nvelope 7 5154 CW-PHO-PBC-01 / Y1 - Perfor mance-Based Routine Mainte Component 1: Climate Resili Single Stage - One E 2021-10-0 nance of Provincial and Distri IDA / 59200 Post Request for Bids Open - National 782,360.00 728,114.54 Signed 2018-07-02 2018-06-25 2018-07-07 2018-08-18 2018-10-29 2018-09-17 2019-04-02 2018-10-22 2019-07-23 ent Road Maintenance nvelope 6 ct roads in Phongsaly provinc e (Bounneuar and Bountai Di stricts) CW-PHO-PBC-02 / Y1 - Perfor mance-Based Routine Mainte Component 1: Climate Resili Single Stage - One E 1,051,297.9 2021-10-0 nance of Provincial and Distri IDA / 59200 Post Request for Bids Open - National 1,043,179.00 Signed 2018-07-02 2018-08-27 2018-07-07 2018-08-18 2018-10-29 2018-09-17 2019-04-02 2018-10-22 2019-07-19 ent Road Maintenance nvelope 9 6 ct Roads in Phongsaly provin ce (Khoua, Samphanh and M ay Districts) CW-OUD-PBC-01 / Y1 - Perfor mance-Based Routine Mainte Component 1: Climate Resili Single Stage - One E 1,011,503.6 2021-10-0 nance of provincial and distri IDA / 59200 Post Request for Bids Open - National 1,225,783.00 Signed 2018-07-02 2018-06-23 2018-07-07 2018-08-18 2018-10-29 2018-09-17 2018-10-29 2018-10-22 2019-06-14 ent Road Maintenance nvelope 8 6 ct roads in Oudomxay provin ce (La, Xay and Namor distric ts) CW-OUD-PBC-02 / Y1 - Perfor mance-Based Routine Mainte Component 1: Climate Resili Single Stage - One E 2021-10-0 IDA / 59200 Post Request for Bids Open - National 894,207.00 654,573.97 Signed 2018-07-02 2018-06-25 2018-07-07 2018-08-18 2018-10-29 2018-09-17 2018-10-29 2018-10-22 2019-06-19 nance of Provincial and Distri ent Road Maintenance nvelope 6 ct roads in Oudomxay provin ce (Nga District) CW-OUD-PBC-03 / Y1 - Perfor mance-Based Routine Mainte Component 1: Climate Resili Single Stage - One E 2021-10-0 nance of Provincial and Distri IDA / 59200 Post Request for Bids Open - National 679,591.00 542,894.65 Signed 2018-07-02 2018-06-25 2018-07-07 2018-08-18 2018-10-29 2018-09-17 2018-10-29 2018-10-22 2019-06-14 ent Road Maintenance nvelope 6 ct Roads in Oudomxay provin ce (Beng, Houn and Pakbeng Districts) CW-XAY-PBC-01 / Y1 - Perfor mance-Based Routine Mainte Component 1: Climate Resili Single Stage - One E 2021-10-0 nance of Provincial and Distri IDA / 59200 Post Request for Bids Open - National 918,028.00 912,183.23 Signed 2018-07-02 2018-10-29 2018-07-07 2018-08-18 2018-10-29 2018-09-17 2018-10-29 2018-10-22 2019-07-18 ent Road Maintenance nvelope 6 ct Roads in Xayabuly provinc e (Khob, Xienghone and Hon gsa Districts) CW-XAY-PBC-02 / Y1 - Perfor mance-Based Routine Mainte Component 1: Climate Resili Single Stage - One E 2021-10-0 nance of Provincial and Distri IDA / 59200 Post Request for Bids Open - National 611,816.00 900,961.42 Signed 2018-07-02 2019-08-19 2018-07-07 2018-08-18 2019-10-09 2018-09-17 2019-10-09 2018-10-22 2020-05-19 ent Road Maintenance nvelope 6 ct Roads in Xayabuly provinc e (Xaysathan, Phieng, Paklai and Bortene Districts) CW-HOU-PBC-01 / Y1 - Perfor mance-Based Routine Mainte Component 1: Climate Resili Single Stage - One E 1,007,307.7 2021-10-0 nance of Provincial and Distri IDA / 59200 Post Request for Bids Open - National 759,216.00 Signed 2018-07-02 2018-10-29 2018-07-07 2018-08-18 2018-10-29 2018-09-17 2018-10-29 2018-10-22 2019-07-18 ent Road Maintenance nvelope 7 6 ct Roads in Huaphanh provin ce (Xamnue and Viengxai Dis tricts) CW-HOU-PBC-02 / Y1 - Perfor mance-Based Routine Mainte Component 1: Climate Resili Single Stage - One E 2021-10-0 nance of Provincial and Distri IDA / 59200 Post Request for Bids Open - National 598,088.00 789,789.18 Signed 2018-07-02 2018-10-29 2018-07-07 2018-08-18 2018-10-29 2018-09-17 2018-10-29 2018-10-22 2018-11-06 ent Road Maintenance nvelope 6 ct Roads in Huaphanh provin ce (Hoamoueng and Viength ong Districts) CW-XIE-PBC-01 / Y1 - Perfor mance-Based Routine Mainte Component 1: Climate Resili Single Stage - One E 2021-10-0 nance of provincial and distri IDA / 59200 Post Request for Bids Open - National 465,704.00 551,043.95 Signed 2018-07-02 2018-09-05 2018-07-07 2018-08-18 2018-10-29 2018-09-17 2019-04-24 2018-10-22 2019-07-23 ent Road Maintenance nvelope 6 ct roads in Xiengkhuang prov ince (Pek and Kham districts) CW-XIE-PBC-02 / Y1 - Perfor mance-Based Routine Mainte Component 1: Climate Resili Single Stage - One E 2021-10-0 IDA / 59200 Post Request for Bids Open - National 378,763.00 548,667.71 Signed 2018-07-02 2018-09-05 2018-07-07 2018-08-18 2018-10-29 2018-09-17 2018-10-29 2018-10-22 2019-07-23 nance of Provincial and Distri ent Road Maintenance nvelope 6 ct Roads in Xiengkhuang pro vince (Poukoud District) CW-BOL-PBC-01 / Y1 - Perfor mance-Based Routine Mainte Component 1: Climate Resili Single Stage - One E 2021-10-0 nance of Provincial and Distri IDA / 59200 Post Request for Bids Open - National 531,249.00 397,981.39 Signed 2018-07-02 2018-06-25 2018-07-07 2018-08-18 2018-10-29 2018-09-17 2018-10-29 2018-10-22 2019-07-07 ent Road Maintenance nvelope 6 ct Roads in Bolikhamxay pro vince (Paksane, Thaphabath and Bolikhane Districts) Page 1 ATP01-2019-EM22-NR03 / E Component 1: Climate Resili Single Stage - One E 2020-05-2 mergency maintenance and IDA / 59200 Post Request for Bids Open - National 360,000.00 0.00 Canceled 2019-03-04 2019-03-04 2019-03-09 2019-03-24 2019-03-21 2019-04-23 2019-05-28 ent Road Maintenance nvelope 7 disaster recovery for NR18A - roads - Lot 1 ATP01-2019-EM22-NR04 / E Component 1: Climate Resili Single Stage - One E 2020-05-2 mergency maintenance and IDA / 59200 Post Request for Bids Open - National 418,000.00 0.00 Canceled 2019-03-04 2019-03-21 2019-03-09 2019-03-24 2019-03-21 2019-04-23 2019-05-28 ent Road Maintenance nvelope 7 disaster recovery for NR18A - roads - Lot 2 ATP01-2019-EM22-NR01 / E mergency maintenance and Component 1: Climate Resili Single Stage - One E 2020-05-2 IDA / 59200 Post Request for Bids Open - National 1,097,000.00 0.00 Canceled 2019-03-04 2019-03-09 2019-03-24 2019-04-23 2019-05-28 disaster recovery for NR18A - ent Road Maintenance nvelope 7 bailey bridges - Lot 1 ATP01-2019-EM22-NR02 / E mergency maintenance and Component 1: Climate Resili Single Stage - One E 2020-05-2 IDA / 59200 Post Request for Bids Open - National 1,058,000.00 0.00 Canceled 2019-03-04 2019-03-09 2019-03-24 2019-04-23 2019-05-28 disaster recovery for NR18A - ent Road Maintenance nvelope 7 bailey bridges - Lot 2 CW-PHO-01-LOT 1 / Climate Component 1: Climate Resili Single Stage - One E 1,233,928.8 2020-12-2 IDA / 59200 Post Request for Bids Open - National 1,412,000.00 Signed 2019-03-11 2019-03-11 2019-03-16 2019-04-27 2019-04-30 2019-05-27 2019-08-06 2019-07-01 2020-03-14 resilient maintenance of Roa ent Road Maintenance nvelope 4 2 d No. 1201 CW-PHO-01-LOT 2 / Climate Component 1: Climate Resili Single Stage - One E 1,297,476.3 2020-12-2 IDA / 59200 Post Request for Bids Open - National 1,623,000.00 Signed 2019-03-11 2019-03-08 2019-03-16 2019-04-27 2019-04-30 2019-05-27 2019-04-30 2019-07-01 2020-04-26 resilient maintenance of Roa ent Road Maintenance nvelope 5 2 d No. 1201 AF-W-PACKAGE1-OPBRC 001 /2020 / Improvement and Mai Component 1: Climate Resili Open - Internationa Single Stage - Two E 20,500,000.0 17,531,013. 2030-12-2 ntenance of NR13S – Section IDA / 65150 Prior Request for Bids Signed 2020-04-10 2020-04-09 2020-04-15 2020-04-16 2020-08-03 2020-07-24 2020-10-16 2021-01-20 2020-12-25 2021-03-18 ent Road Maintenance l nvelope 0 00 4 (length 40 km) from km 71 t o km 111 including bridges W-DPC-01 / Office refurbish Component 3: Project Manag Request for Quota Single Stage - One E 2021-03-1 IDA / 59200 Post Open - National 5,000.00 4,046.86 Signed 2020-07-22 2020-09-16 2020-11-10 ment for installing VC system ement tions nvelope 5 CW-PHO-PBC-03 / Y2023-20 National Procure 25 - Performance-Based Rout ment Document - Component 1: Climate Resili Single Stage - One E 2023-09-2 ine Maintenance of Provincial IDA / 65150 Post Request for Bids Open - National 1 Envelope proce 790,000.00 0.00 Canceled 2022-12-02 2023-01-31 2022-12-07 2023-01-18 2023-03-30 2023-02-17 2023-03-24 ent Road Maintenance nvelope 0 and District roads in Phongsa ss (Non Bank-SPD ly province (Phongsaly, Yod ) Ou and Bountai Districts) CW-PHO-PBC-04 / Y2023-20 National Procure 25 - Performance-Based Rout ment Document - Component 1: Climate Resili Single Stage - One E 2023-09-2 ine Maintenance of Provincial IDA / 65150 Post Request for Bids Open - National 1 Envelope proce 850,000.00 0.00 Canceled 2022-12-02 2023-01-31 2022-12-07 2023-01-18 2023-03-30 2023-02-17 2023-03-24 ent Road Maintenance nvelope 0 and District Roads in Phongs ss (Non Bank-SPD aly province (Khoua, and Ma ) y Districts) CW-OUD-PBC-RM-04 / Y2023 National Procure -2025 - Performance-Based R ment Document - outine Maintenance of Provin Component 1: Climate Resili Single Stage - One E 2023-09-2 IDA / 65150 Post Request for Bids Open - National 1 Envelope proce 867,000.00 0.00 Canceled 2022-12-02 2023-01-31 2022-12-07 2023-01-18 2023-03-16 2023-02-17 2023-03-24 cial and District Roads in Oud ent Road Maintenance nvelope 0 ss (Non Bank-SPD omxay province (Xay,La,Ben ) g, Houn and Pakbeng District s) CW-OUD-PBC-RM-05 / Y2023 National Procure -2025 - Performance-Based R ment Document - Component 1: Climate Resili Single Stage - One E 2023-09-2 outine Maintenance of Provin IDA / 65150 Post Request for Bids Open - National 1 Envelope proce 423,000.00 0.00 Canceled 2022-12-02 2023-01-31 2022-12-07 2023-01-18 2023-03-16 2023-02-17 2023-03-24 ent Road Maintenance nvelope 0 cial and District Roads in Oud ss (Non Bank-SPD omxay province (Nga District ) ) CW-XAY-PBC-03 / Y2023-202 National Procure 5 - Performance-Based Routi ment Document - Component 1: Climate Resili Single Stage - One E 2023-09-2 ne Maintenance of Provincial IDA / 65150 Post Request for Bids Open - National 1 Envelope proce 600,000.00 0.00 Signed 2022-12-02 2023-01-31 2022-12-07 2023-01-18 2023-03-23 2023-02-17 2023-06-30 2023-03-24 ent Road Maintenance nvelope 0 and District Roads in Xayabo ss (Non Bank-SPD uly province (Khope, Xiengho ) ne Districts) CW-XAY-PBC-04 / Y2023-202 National Procure 5 - Performance-Based Routi ment Document - Component 1: Climate Resili Single Stage - One E 2023-09-2 ne Maintenance of Provincial IDA / 65150 Post Request for Bids Open - National 1 Envelope proce 421,000.00 0.00 Signed 2022-12-02 2023-01-31 2022-12-07 2023-01-18 2023-03-23 2023-02-17 2023-06-30 2023-03-24 ent Road Maintenance nvelope 0 and District Roads in Xayabo ss (Non Bank-SPD uly province (Ngern, Hongsa ) Districts) CW-XAY-PBC-05 / Y2023-202 National Procure 5 - Performance-Based Routi ment Document - Component 1: Climate Resili Single Stage - One E 2023-09-2 ne Maintenance of Provincial IDA / 65150 Post Request for Bids Open - National 1 Envelope proce 340,000.00 0.00 Signed 2022-12-02 2023-01-31 2022-12-07 2023-01-18 2023-03-23 2023-02-17 2023-06-30 2023-03-24 ent Road Maintenance nvelope 0 and District Roads in Xayabo ss (Non Bank-SPD uly province (Xayabouly, Xa ) ysathan, Phieng Districts) CW-XAY-PBC-06 / Y2023-202 National Procure 5 - Performance-Based Routi ment Document - ne Maintenance of Provincial Component 1: Climate Resili Single Stage - One E 2023-09-2 IDA / 65150 Post Request for Bids Open - National 1 Envelope proce 592,000.00 0.00 Signed 2022-12-02 2023-01-31 2022-12-07 2023-01-18 2023-03-23 2023-02-17 2023-06-30 2023-03-24 and District Roads in Xayabo ent Road Maintenance nvelope 0 ss (Non Bank-SPD uly province (Paklai, Kentha ) o, Boten, THongmixay Distric ts) CW-HOU-PBC-03 / Y2023-20 National Procure 25 - Performance-Based Rout ment Document - Component 1: Climate Resili Single Stage - One E 2023-09-2 ine Maintenance of Provincial IDA / 65150 Post Request for Bids Open - National 1 Envelope proce 848,000.00 0.00 Signed 2022-12-02 2023-01-31 2022-12-07 2023-01-18 2023-03-16 2023-02-17 2023-04-21 2023-03-24 2023-10-02 ent Road Maintenance nvelope 0 and District Roads in Houaph ss (Non Bank-SPD an province (Xamnuea, Xamt ) ai and Kouan Districts) CW-HOU-PBC-04 / Y2023-20 National Procure 25 - Performance-Based Rout ment Document - ine Maintenance of Provincial Component 1: Climate Resili Single Stage - One E 2023-09-2 IDA / 65150 Post Request for Bids Open - National 1 Envelope proce 773,000.00 0.00 Signed 2022-12-02 2023-01-31 2022-12-07 2023-01-18 2023-03-16 2023-02-17 2023-04-21 2023-03-24 2023-10-03 and District Roads in Houaph ent Road Maintenance nvelope 0 ss (Non Bank-SPD an province (Houamuang, Xo ) ne, Hiem and Xamnuea Distri cts) CW-XIE-PBC-03 / Y2023-202 National Procure 5 - Performance-Based Routi ment Document - Component 1: Climate Resili Single Stage - One E 2023-09-2 ne Maintenance of provincial IDA / 65150 Post Request for Bids Open - National 1 Envelope proce 1,059,000.00 0.00 Signed 2022-12-02 2023-01-31 2022-12-07 2023-01-18 2023-03-16 2023-02-17 2023-04-11 2023-03-24 2023-08-01 ent Road Maintenance nvelope 0 and district roads in Xiengkh ss (Non Bank-SPD uang province (Pek and Phou ) koud districts) CW-XIE-PBC-04 / Y2023-202 National Procure 5 - Performance-Based Routi ment Document - Component 1: Climate Resili Single Stage - One E 2023-09-2 ne Maintenance of Provincial IDA / 65150 Post Request for Bids Open - National 1 Envelope proce 713,000.00 0.00 Signed 2022-12-02 2023-01-31 2022-12-07 2023-01-18 2023-03-16 2023-02-17 2023-04-11 2023-03-24 2023-08-01 ent Road Maintenance nvelope 0 and District Roads in Xiengkh ss (Non Bank-SPD uang province (Paek, Khoun ) and Kham District) Page 2 CW-BOL-PBC-02 / Y2023-202 National Procure 5 - Performance-Based Routi ment Document - ne Maintenance of Provincial Component 1: Climate Resili Single Stage - One E 2023-09-2 IDA / 65150 Post Request for Bids Open - National 1 Envelope proce 1,439,000.00 0.00 Signed 2022-12-02 2023-01-31 2022-12-07 2023-01-18 2023-03-16 2023-02-17 2023-05-26 2023-03-24 2023-09-20 and District Roads in Bolikha ent Road Maintenance nvelope 0 ss (Non Bank-SPD mxay province (Paksanh, Tha ) phabath ,Bolikhanh,Khamkeu t and Viengthong Districts) CW-PHO-PBC-05 / Y2 - Y2024 -2025 - Performance-Based R outine Maintenance of Provin Component 1: Climate Resili Single Stage - One E Other (with field f Under Imple 2025-03-2 IDA / 65150 Post Request for Bids Open - National 1,093,000.00 0.00 2024-06-02 2024-01-10 2024-06-07 2024-07-19 2024-08-18 2024-09-22 cial and District roads in Pho ent Road Maintenance nvelope or explanation) mentation 1 ngsaly province (Phongsaly, Yod Ou, Bountai, Khoua and May Districts) CW-OUD-PBC-RM-06 / Y2 - Y 2024-2025 - Performance-Ba sed Routine Maintenance of Component 1: Climate Resili Single Stage - One E Other (with field f Under Imple 2025-03-2 IDA / 65150 Post Request for Bids Open - National 925,000.00 0.00 2024-06-02 2024-01-15 2024-06-07 2024-07-19 2024-02-29 2024-08-18 2024-09-22 Provincial and District Roads ent Road Maintenance nvelope or explanation) mentation 1 in Oudomxay province (Xay,L a,Beng, Houn, Pakbeng and Nga District) GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual G-02 / Fifty (50) motorbikes f Component 2: Institutional S Single Stage - One E IDA / 59200 Post Request for Bids Open - National 200,000.00 0.00 Canceled 2017-05-02 2017-05-07 2017-06-18 2017-07-18 2017-08-22 2018-02-18 or DoR and DPWT trengthening nvelope G-03 / Motorbikes (10 for Do Component 2: Institutional S Request for Quota Single Stage - One E IDA / 59200 Post Open - National 42,000.00 0.00 Canceled 2017-05-02 2017-05-23 2017-11-19 I and 18 for DoF) trengthening tions nvelope G-05 / 1st batch – office equi Component 2: Institutional S Request for Quota Single Stage - One E IDA / 59200 Post Open - National 94,000.00 0.00 Canceled 2017-05-06 2017-07-01 2017-12-28 pment for DoI, DoP and PTTI trengthening tions nvelope G-06 / 2nd batch - office equ Component 3: Project Manag Request for Quota Single Stage - One E IDA / 59200 Post Open - National 80,000.00 0.00 Canceled 2017-07-08 2017-09-02 2018-03-01 ipment for DPC ement tions nvelope G-07 / 3rd batch - office equi Component 2: Institutional S Request for Quota Single Stage - One E IDA / 59200 Post Open - National 73,000.00 0.00 Canceled 2017-07-08 2017-09-02 2018-03-01 pment for DoF trengthening tions nvelope G-09 / E&S monitoring tools/ Component 2: Institutional S Request for Quota Single Stage - One E IDA / 59200 Post Open - National 15,000.00 0.00 Canceled 2017-05-06 2017-07-01 2017-12-28 equipment and facilities for P trengthening tions nvelope TRI G-08 / Computers Server eq Component 2: Institutional S Single Stage - One E uipment for Network Develop IDA / 59200 Post Request for Bids Open - National 140,000.00 0.00 Canceled 2017-05-02 2017-05-07 2017-06-18 2017-07-18 2017-08-22 2018-02-18 trengthening nvelope ment for ICT G-10 / Fifty (50) off-road mot Component 2: Institutional S Request for Quota Single Stage - One E IDA / 59200 Post Open - National 180,000.00 0.00 Canceled 2017-07-15 2017-09-09 2018-03-08 orbikes for DoR and DPWT trengthening tions nvelope G-12 / 24 off-road bikes and Component 2: Institutional S Single Stage - One E IDA / 59200 Post Request for Bids Open - National 170,000.00 129,491.14 Completed 2018-01-05 2018-03-27 2018-01-10 2018-02-21 2018-05-10 2018-03-23 2018-07-09 2018-04-27 2018-08-25 2018-10-24 2019-01-13 37 city bikes for DoR and DP trengthening nvelope WT G-04 / Testing equipment for Component 2: Institutional S Request for Quota Single Stage - One E IDA / 59200 Post Open - National 34,000.00 32,287.35 Completed 2018-05-12 2018-07-07 2018-09-30 2019-01-03 2019-02-07 DoI trengthening tions nvelope G-13 / Equipment supplies fo Component 2: Institutional S Request for Quota Single Stage - One E IDA / 59200 Post Open - National 97,500.00 64,181.09 Completed 2018-04-28 2018-06-23 2018-10-14 2018-12-20 2019-04-04 r Road Safety Campaign trengthening tions nvelope G-15 / Equipment for DPWT - Component 2: Institutional S Request for Quota Single Stage - One E IDA / 59200 Post Open - National 6,000.00 0.00 Canceled 2018-08-04 2018-09-29 2019-03-28 Phongsaly trengthening tions nvelope G-14 / Equipment for back u Component 2: Institutional S Request for Quota Single Stage - One E p procurement information a IDA / 59200 Post Open - National 24,000.00 19,932.73 Completed 2018-07-30 2018-09-24 2018-10-29 2019-03-23 2019-01-08 trengthening tions nvelope nd for DPWT - Phongsaly G-16 / 4 vehicles for supervi Component 2: Institutional S Single Stage - One E IDA / 59200 Post Request for Bids Open - National 180,000.00 155,621.51 Signed 2019-05-30 2019-06-06 2019-06-04 2019-07-16 2019-07-12 2019-08-15 2019-08-14 2019-09-19 2019-10-07 2020-03-17 sion team trengthening nvelope G-17 / 1 SUV for financial ma Component 2: Institutional S Request for Quota Single Stage - One E nagement and 1 car for proje IDA / 59200 Post Open - National 95,000.00 84,671.43 Signed 2019-09-21 2019-11-16 2019-10-21 2020-05-14 trengthening tions nvelope ct management team G-11 / Procurement of IT Equ Component 2: Institutional S Single Stage - One E IDA / 59200 Post Request for Bids Open - National 355,401.00 284,366.92 Signed 2019-08-25 2019-11-04 2019-08-30 2019-10-11 2019-12-24 2019-11-10 2020-02-28 2019-12-15 2020-05-03 2020-06-12 ipment for MPWT Infrastructu trengthening nvelope re System G-18 / Equipment for DoF, D Component 2: Institutional S Request for Quota Single Stage - One E IDA / 59200 Post Open - National 45,000.00 44,030.69 Signed 2019-10-25 2019-12-20 2020-10-28 2020-06-17 PC and DoP trengthening tions nvelope G-19 / 7 Motorcycles for fina Component 2: Institutional S Request for Quota Single Stage - One E IDA / 59200 Post Open - National 14,000.00 13,695.20 Signed 2019-10-25 2019-12-20 2020-09-30 2020-06-17 ncial management trengthening tions nvelope G-20 / UXO clearance/survey Component 2: Institutional S Request for Quota Single Stage - One E IDA / 59200 Post Open - National 60,000.00 0.00 Canceled 2019-10-25 2019-12-20 2020-06-17 equipment trengthening tions nvelope G-21 / Vehicle for implement Component 2: Institutional S Request for Quota Single Stage - One E IDA / 59200 Post Open - National 50,000.00 50,400.00 Signed 2020-03-04 2020-04-29 2020-06-22 2020-10-26 ation of Safeguards works trengthening tions nvelope AF-G-02 / 4 vehicles for proj Component 2: Institutional S Single Stage - One E IDA / 65150 Post Request for Bids Open - National 180,000.00 177,200.00 Signed 2020-04-20 2020-03-24 2020-04-25 2020-06-06 2020-05-15 2020-07-06 2020-05-15 2020-08-10 2020-06-19 2021-02-06 ect management team trengthening nvelope AF-G-01 / Rescue equipment Component 2: Institutional S Single Stage - One E IDA / 65150 Post Request for Bids Open - National 200,000.00 150,052.69 Signed 2020-04-20 2020-03-24 2020-04-25 2020-06-06 2020-05-15 2020-07-06 2020-05-15 2020-08-10 2020-06-19 2021-02-06 15 boats trengthening nvelope G-22 / VC equipment for DP Component 3: Project Manag Request for Quota Single Stage - One E IDA / 59200 Post Open - National 20,000.00 16,990.00 Signed 2020-07-22 2020-09-16 2020-11-10 2021-03-15 C ement tions nvelope G-23 / Equipment and tools f Component 2: Institutional S Request for Quota Single Stage - One E IDA / 59200 Post Open - National 25,700.00 45,613.00 Signed 2020-09-09 2020-11-04 2021-04-12 2021-05-03 or EDPD trengthening tions nvelope G-24 / Office equipment for r Component 2: Institutional S Request for Quota Single Stage - One E oad safety (computers, lapto IDA / 59200 Post Open - National 50,000.00 49,901.00 Signed 2020-11-10 2021-01-05 2021-03-25 2021-07-04 trengthening tions nvelope ps and printers) Page 3 AF-G-03 / Office equipment f Component 2: Institutional S Request for Quota Single Stage - One E IDA / 65150 Post Open - National 24,000.00 24,332.00 Signed 2021-04-14 2021-06-09 2021-11-20 2021-12-06 or NR13 PMU and DoI trengthening tions nvelope C2-34 / VC Equipment's (8se Component 2: Institutional S Request for Quota Single Stage - One E IDA / 65150 Post Limited 50,000.00 34,658.00 Signed 2021-07-19 2021-09-16 2021-09-13 2021-12-02 2022-03-12 ts) for PTRI trengthening tions nvelope C2-33 / Drones (9sets) for PT Component 2: Institutional S Request for Quota Single Stage - One E IDA / 65150 Post Limited 36,000.00 44,711.00 Signed 2021-07-18 2021-09-16 2021-09-12 2021-12-02 2022-03-11 RI trengthening tions nvelope G-25 / Office Equipment for Component 3: Project Manag Request for Quota Single Stage - One E IDA / 59200 Post Limited 40,000.00 0.00 Canceled 2022-01-05 2022-03-02 2022-08-29 DPC ement tions nvelope AF-G-04 / IT Equipment for P Component 2: Institutional S Request for Quota Single Stage - One E ermanent Secretary Office an IDA / 65150 Post Limited 20,000.00 19,902.00 Signed 2022-01-29 2022-01-11 2022-03-26 2022-04-12 2022-09-22 trengthening tions nvelope d Department of Personal AF-G-05 / Office equipment f Component 4: Contingent E Single Stage - One E IDA / 65150 Post Request for Bids Limited 40,000.00 39,936.92 Signed 2022-01-14 2022-03-01 2022-01-19 2022-03-01 2022-03-02 2022-03-15 2022-04-01 2022-03-18 2022-05-06 2022-04-20 2022-11-02 or DPC mergency Response nvelope AF-G-06 / Road Safety Public Component 2: Institutional S Single Stage - One E Awareness Campaign during IDA / 65150 Post Request for Bids Limited 20,000.00 19,998.00 Signed 2022-03-30 2022-03-28 2022-04-04 2022-03-28 2022-05-16 2022-04-08 2022-06-15 2022-04-19 2022-07-20 2022-05-03 2023-01-16 trengthening nvelope Lao New Year 2022 NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NC2-01 / Server and internet Component 2: Institutional S IDA / 59200 Post Direct Selection 50,000.00 0.00 Signed 2020-10-20 2020-10-19 2020-10-30 2022-03-23 2020-12-31 2022-12-03 2023-12-29 rental at LANIC trengthening CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual C2-10 / TA for IRAM for local Component 2: Institutional S Quality And Cost- Open - Internationa IDA / 59200 Prior 750,000.00 0.00 Canceled 2017-03-20 2017-04-03 2017-04-10 2017-04-11 2017-05-24 2017-09-14 2017-06-21 2017-10-16 2017-07-21 2017-11-30 2017-08-25 2018-03-27 2017-09-29 2018-09-29 roads, E-Archive, and Web-sit trengthening Based Selection l e C2-18 / Local firm for Social Component 2: Institutional S Consultant Qualifi IDA / 59200 Prior Open - National 290,000.00 0.00 Canceled 2017-03-20 2017-04-10 2017-05-24 2017-06-23 2017-07-28 2018-01-24 and Environment surveys for trengthening cation Selection NR13 C2-20 / Local firm for Social Component 2: Institutional S Consultant Qualifi IDA / 59200 Prior Open - National 290,000.00 335,956.75 Signed 2015-10-30 2015-11-20 2016-01-03 2016-02-02 2017-04-02 2016-03-08 2017-04-26 2016-09-04 and Environment surveys for trengthening cation Selection NR13 Component 3: Project Manag Consultant Qualifi C3-02 / Financial auditor IDA / 59200 Post Open - National 200,000.00 61,108.00 Signed 2017-07-10 2017-05-17 2017-07-31 2017-09-13 2017-10-17 2017-10-13 2017-11-08 2017-11-17 2018-01-22 2018-05-16 ement cation Selection C2-24 / Consulting Services f Component 2: Institutional S Consultant Qualifi Open - Internationa or Road Transport Efficiency f IDA / 59200 Post 240,000.00 0.00 Canceled 2019-03-15 2019-05-09 2019-04-05 2019-05-23 2019-05-19 2019-06-18 2019-07-23 2020-01-19 trengthening cation Selection l ocusing on Logistics and Ove rloading Control C2-28 / Consulting Firm for U Component 2: Institutional S Consultant Qualifi Open - Internationa IDA / 59200 Post 298,000.00 294,930.00 Signed 2019-08-20 2019-08-20 2019-09-10 2019-09-13 2019-10-24 2019-12-10 2019-11-23 2020-03-23 2019-12-28 2020-05-16 2020-12-31 pgrading IRAM software at M trengthening cation Selection l PWT C2-29 / Consulting Firm for f Component 2: Institutional S Consultant Qualifi Open - Internationa IDA / 59200 Post 33,000.00 31,471.00 Signed 2019-08-20 2019-08-20 2019-09-10 2019-09-13 2019-10-24 2019-12-10 2019-11-23 2020-03-13 2019-12-28 2020-05-13 2020-06-30 or MPWT Website upgrade trengthening cation Selection l C2-30 / Consulting Firm for Component 2: Institutional S Consultant Qualifi Open - Internationa Development of e-Archive Sy IDA / 59200 Post 221,000.00 209,000.00 Signed 2019-08-20 2019-08-20 2019-09-10 2019-09-13 2019-10-24 2019-12-10 2019-11-23 2020-03-13 2019-12-28 2020-05-13 2020-07-31 trengthening cation Selection l stem for MPWT AF-C2-20 / Consulting Servic Component 2: Institutional S Consultant Qualifi Open - Internationa es for Overloading Control St IDA / 65150 Post 250,000.00 0.00 Signed 2022-09-01 2022-09-24 2022-09-22 2022-11-18 2022-11-05 2023-01-27 2022-12-05 2023-06-29 2023-01-09 2023-07-06 2023-07-08 trengthening cation Selection l udy and Action Plan AF-C2-25 / Consulting Servic e for Detailed Feasibility, Tec Component 2: Institutional S Quality And Cost- Open - Internationa Under Implement IDA / 65150 Post 800,000.00 0.00 2024-02-01 2023-09-06 2024-02-22 2023-09-14 2024-04-06 2023-12-07 2024-05-04 2024-01-23 2024-06-03 2024-07-08 2024-08-12 2025-08-12 hnical, Environment and Soci trengthening Based Selection l ation al Assessment Studies of CR RCIP INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual C3-04 / Procurement Consult Component 3: Project Manag Individual Consult IDA / 59200 Prior Open 300,000.00 239,120.00 Signed 2017-03-06 2017-03-06 2017-04-24 2017-08-04 2017-05-15 2017-08-22 2017-06-19 2017-09-13 2017-12-16 ant ement ant Selection C2-14 / Technical assistant t Component 2: Institutional S Individual Consult IDA / 59200 Post Open 100,000.00 118,860.00 Signed 2017-06-01 2017-10-20 2017-07-20 2018-02-07 2017-08-10 2018-03-23 2017-09-14 2018-06-02 2018-03-13 o NSCT trengthening ant Selection C2-17 / International Environ Component 2: Institutional S Individual Consult IDA / 59200 Post Open 76,000.00 0.00 Canceled 2017-03-20 2017-05-08 2017-05-29 2017-07-03 2017-12-30 ment Consultant for NR13 trengthening ant Selection C2-02 / Transport Sector Poli Component 2: Institutional S Individual Consult IDA / 59200 Prior Open 250,000.00 263,000.00 Signed 2017-07-21 2018-03-07 2017-09-08 2018-08-04 2017-09-29 2018-09-17 2017-11-03 2018-10-15 2018-05-02 cy advisor trengthening ant Selection C2-03 / Planning Framework Component 2: Institutional S Individual Consult IDA / 59200 Post Open 100,000.00 186,150.00 Signed 2017-07-21 2017-10-19 2017-09-08 2018-06-08 2017-09-29 2018-07-03 2017-11-03 2018-08-28 2018-05-02 Development Consultant trengthening ant Selection C2-04 / Internal Control Advi Component 2: Institutional S Individual Consult IDA / 59200 Post Open 100,000.00 81,200.00 Signed 2017-07-03 2017-10-06 2017-08-21 2018-01-05 2017-09-11 2018-01-08 2017-10-16 2018-03-02 2018-04-14 sor trengthening ant Selection C2-05 / Quality Assurance A Component 2: Institutional S Individual Consult IDA / 59200 Post Open 100,000.00 83,600.00 Signed 2017-07-03 2017-10-06 2017-08-21 2018-01-05 2017-09-11 2018-01-08 2017-10-16 2018-03-02 2018-04-14 dvisor trengthening ant Selection C2-07 / Financial manageme Component 2: Institutional S Individual Consult IDA / 59200 Post Open 100,000.00 78,800.00 Signed 2017-06-30 2017-06-22 2017-08-18 2017-11-08 2017-09-08 2017-11-08 2017-10-13 2018-02-11 2018-04-11 nt Consultant (N) trengthening ant Selection Page 4 C2-08 / Financial manageme Component 2: Institutional S Individual Consult IDA / 59200 Post Open 100,000.00 0.00 Canceled 2017-06-30 2017-06-22 2017-08-18 2017-11-08 2017-09-08 2017-10-13 2018-04-11 nt Consultant (C) trengthening ant Selection C2-09 / Financial manageme Component 2: Institutional S Individual Consult IDA / 59200 Post Open 100,000.00 78,800.00 Signed 2017-06-30 2017-06-22 2017-08-18 2017-11-08 2017-09-08 2017-11-08 2017-10-13 2018-02-06 2018-04-11 nt Consultant (S) trengthening ant Selection C2-15 / Road safety audit m Component 2: Institutional S Individual Consult IDA / 59200 Prior Open 200,000.00 108,800.00 Signed 2017-07-10 2017-09-21 2017-08-28 2018-02-08 2017-09-18 2018-04-12 2017-10-23 2018-06-01 2018-04-21 anual development trengthening ant Selection C2-19 / International Environ Component 2: Institutional S Individual Consult IDA / 59200 Post Open 76,000.00 0.00 Canceled 2015-10-30 2015-12-18 2016-01-08 2016-02-12 2016-08-10 ment Consultant for NR13 trengthening ant Selection C2-21 / International Environ Component 2: Institutional S IDA / 59200 Post Direct Selection Direct 76,000.00 75,630.00 Completed 2017-07-10 2017-07-20 2017-04-18 2017-09-23 2017-04-23 2018-03-22 2018-07-04 ment Consultant for NR13 trengthening Component 2: Institutional S Individual Consult C2-22 / Planning Analyst IDA / 59200 Post Open 150,000.00 82,560.00 Signed 2017-07-21 2017-10-19 2017-09-08 2018-06-08 2017-09-29 2018-06-22 2017-11-03 2018-08-15 2018-05-02 trengthening ant Selection Component 3: Project Manag Individual Consult C3-01 / Project Coordinator IDA / 59200 Post Open 300,000.00 0.00 Canceled 2017-03-31 2017-05-19 2017-06-09 2017-07-14 2018-01-10 ement ant Selection Component 3: Project Manag Individual Consult C3-03 / Technical Auditor IDA / 59200 Prior Open 300,000.00 298,050.00 Signed 2017-12-08 2018-02-25 2018-01-26 2018-07-16 2018-02-16 2018-09-30 2018-03-23 2018-10-22 2018-09-19 ement ant Selection C3-05 / National Coordinatio Component 3: Project Manag IDA / 59200 Post Direct Selection Direct 105,000.00 52,500.00 Signed 2017-06-02 2017-06-02 2017-06-12 2017-08-04 2017-08-16 2017-09-22 2018-02-12 n Advisor ement C3-06 / Procurement Consult Component 3: Project Manag Individual Consult IDA / 59200 Post Open 150,000.00 66,800.00 Signed 2017-08-15 2017-06-15 2017-10-03 2017-11-08 2017-10-24 2017-11-08 2017-11-28 2018-01-26 2018-05-27 ant (National) ement ant Selection C2-16 / Traffic safety campai Component 2: Institutional S Individual Consult IDA / 59200 Post Open 150,000.00 0.00 Canceled 2017-07-10 2017-08-28 2017-09-18 2017-10-23 2018-04-21 gn consultant trengthening ant Selection C2-13 / Human Resources D Component 2: Institutional S Individual Consult IDA / 59200 Post Open 80,000.00 79,760.00 Signed 2018-06-04 2018-05-04 2018-07-23 2018-07-27 2018-08-13 2018-07-31 2018-09-17 2018-10-06 2019-03-16 evelopment Consultant trengthening ant Selection C3-07 / Procurement Special Component 3: Project Manag Individual Consult IDA / 59200 Prior Open 250,000.00 0.00 Canceled 2018-06-28 2018-07-10 2018-08-16 2018-09-06 2018-10-11 2019-10-06 ist ement ant Selection C2-12 / Environment and So Component 2: Institutional S Individual Consult IDA / 59200 Post Open 30,000.00 0.00 Canceled 2019-10-01 2019-11-19 2019-12-10 2020-01-14 2020-07-12 cial Consultant (International trengthening ant Selection ) C2-11 / Environment and So Component 2: Institutional S Individual Consult IDA / 59200 Post Open 65,000.00 64,750.00 Signed 2018-07-02 2018-06-27 2018-08-20 2018-12-07 2018-09-10 2018-12-11 2018-10-15 2019-02-16 2019-04-13 cial Consultant (Local) trengthening ant Selection C3-08 / Procurement Special Component 3: Project Manag Individual Consult IDA / 59200 Prior Limited 250,000.00 353,710.00 Signed 2018-07-13 2018-07-16 2018-07-18 2018-07-27 2018-08-08 2018-09-03 2018-09-12 2018-10-16 2019-03-11 ist ement ant Selection C2-23 / International Consult ant for MPWT's IRAM Databas Component 2: Institutional S Individual Consult e, e-Archive and Website Nee IDA / 59200 Post Open 80,000.00 38,940.00 Signed 2018-11-30 2019-01-18 2019-01-25 2019-02-08 2019-02-15 2019-03-15 2019-03-08 2019-09-11 trengthening ant Selection ds Assessment, ToR Design a nd Implementation Supervisi on Component 3: Project Manag Individual Consult C3-09 / Technical Auditor IDA / 59200 Prior Open 300,000.00 225,575.00 Signed 2019-04-04 2019-04-08 2019-05-23 2019-06-25 2019-06-13 2019-07-26 2019-07-18 2019-09-13 2022-08-31 ement ant Selection C2-06 / Consultant for evalu Component 2: Institutional S Individual Consult IDA / 59200 Post Open 90,000.00 0.00 Canceled 2019-09-16 2019-11-04 2019-11-25 2019-12-30 2020-06-27 ation of FMS trengthening ant Selection C2-25 / Road Improvement a Component 2: Institutional S Individual Consult IDA / 59200 Post Open 72,000.00 0.00 Canceled 2019-05-30 2019-05-24 2019-07-18 2019-08-08 2019-09-12 2022-02-28 nd Maintenance Consultant 1 trengthening ant Selection C2-26 / Road Improvement a Component 2: Institutional S Individual Consult IDA / 59200 Post Open 72,000.00 0.00 Canceled 2019-05-30 2019-05-24 2019-07-18 2019-08-08 2019-09-12 2022-02-28 nd Maintenance Consultant 2 trengthening ant Selection C2-27 / Consulting Services f or Detailed Engineering Desi Component 1: Climate Resili gn (DED) of Improvement an IDA / 59200 Post Direct Selection Direct 650,000.00 0.00 Canceled 2019-05-30 2019-05-24 2019-06-09 2019-08-13 2022-01-29 ent Road Maintenance d Maintenance of NR13 Sout h from KM 70 to KM 345+500 C1-02 / Consulting Services f or Detailed Engineering Desi Component 1: Climate Resili IDA / 59200 Post Direct Selection Direct 650,000.00 0.00 Signed 2019-08-05 2019-08-05 2019-08-15 2019-08-06 2019-10-19 2019-10-17 2020-04-16 gn (DED) of Improvement an ent Road Maintenance d Maintenance of NR13 Sout h from KM 71 to KM 346 C2-31 / National Financial M Component 2: Institutional S Individual Consult IDA / 59200 Post Open 80,000.00 52,800.00 Signed 2020-02-21 2020-02-13 2020-04-10 2020-10-05 2020-05-01 2020-11-16 2020-06-05 2020-12-10 2022-06-05 anagement Specialist to Sup trengthening ant Selection port DoF AF-C3-01 / National Procure Component 3: Project Manag Individual Consult IDA / 65150 Post Open 70,000.00 0.00 Canceled 2020-02-21 2020-02-13 2020-04-10 2020-05-01 2020-06-05 2022-06-05 ment Specialist to Support D ement ant Selection oF AF-C2-01 / Senior Environme Component 2: Institutional S Individual Consult IDA / 65150 Post Open 40,000.00 48,000.00 Signed 2020-04-27 2020-06-12 2020-06-15 2020-09-25 2020-07-06 2020-09-29 2020-08-10 2020-11-10 2021-08-09 nt and Social Consultant trengthening ant Selection AF-C2-02 / Junior Environme Component 2: Institutional S Individual Consult IDA / 65150 Post Open 60,000.00 67,200.00 Signed 2020-04-27 2020-06-12 2020-06-15 2020-09-25 2020-07-06 2020-09-29 2020-08-10 2020-11-10 2022-08-09 nt and Social Consultant trengthening ant Selection AF-C2-03 / Transport Sector Component 2: Institutional S IDA / 65150 Post Direct Selection Direct 122,000.00 122,000.00 Signed 2021-01-29 2021-03-02 2021-02-08 2021-04-21 2021-04-14 2021-07-18 2023-04-14 Policy Adviser trengthening AF-C2-04 / Planning Framew Component 2: Institutional S IDA / 65150 Post Direct Selection Direct 130,000.00 109,530.00 Signed 2021-01-29 2021-02-22 2021-02-08 2021-04-21 2021-04-14 2021-07-15 2022-04-14 ork Development Consultant trengthening Component 2: Institutional S Individual Consult AF-C2-05 / Planning Analyst IDA / 65150 Post Open 60,000.00 35,685.00 Signed 2021-01-29 2021-02-22 2021-03-19 2021-03-18 2021-04-09 2021-06-15 2021-05-14 2021-08-15 2022-05-14 trengthening ant Selection AF-C2-06 / Project Lifecycle Component 2: Institutional S Individual Consult Management and Monitoring IDA / 65150 Post Open 60,000.00 0.00 Canceled 2021-01-29 2021-03-19 2021-04-09 2021-05-14 2022-11-05 trengthening ant Selection Platform Development Consu ltant AF-C2-07 / National Financial Component 2: Institutional S Individual Consult IDA / 65150 Post Limited 70,000.00 33,600.00 Signed 2021-02-15 2021-02-16 2021-02-20 2021-12-30 2021-03-13 2022-01-11 2021-04-17 2022-02-05 2021-10-14 Management Consultant for trengthening ant Selection NR13S Page 5 AF-C2-08 / Administration Co Component 2: Institutional S Individual Consult IDA / 65150 Post Open 36,000.00 12,000.00 Signed 2021-02-18 2021-02-26 2021-04-08 2021-07-12 2021-04-29 2021-07-14 2021-06-03 2021-09-05 2021-11-30 nsultant trengthening ant Selection AF-C2-09 / Financial Internal Component 2: Institutional S IDA / 65150 Post Direct Selection Direct 99,000.00 92,250.00 Signed 2021-04-09 2021-04-02 2021-04-19 2021-04-20 2021-06-23 2021-07-15 2023-12-25 Inspection Consultant (Local trengthening Consultant) AF-C2-10 / Contract Manage Component 2: Institutional S Individual Consult ment Consultant for Road Im IDA / 65150 Post Open 84,000.00 79,500.00 Signed 2021-04-09 2021-04-06 2021-05-28 2021-04-20 2021-06-18 2021-09-23 2021-07-23 2021-10-24 2023-07-23 trengthening ant Selection provement and Maintenance AF-C2-11 / Road Improveme Component 2: Institutional S Individual Consult nt and Maintenance Engineer IDA / 65150 Post Open 60,000.00 62,700.00 Signed 2021-04-08 2021-04-06 2021-05-27 2021-04-20 2021-06-17 2021-09-23 2021-07-22 2021-10-24 2023-07-22 trengthening ant Selection for Bolikhamxay Province AF-C2-12 / Road Improveme Component 2: Institutional S Individual Consult nt and Maintenance Engineer IDA / 65150 Post Open 60,000.00 62,700.00 Signed 2021-04-09 2021-04-06 2021-05-28 2021-04-20 2021-06-18 2021-09-23 2021-07-23 2021-10-24 2023-07-23 trengthening ant Selection for Houaphan Province AF-C2-13 / Road Improveme Component 2: Institutional S Individual Consult nt and Maintenance Engineer IDA / 65150 Post Open 60,000.00 62,700.00 Signed 2021-04-09 2021-04-06 2021-05-28 2021-04-20 2021-06-18 2021-09-23 2021-07-23 2021-10-24 2023-07-23 trengthening ant Selection for Phongsaly Province AF-C2-14 / Road Improveme Component 2: Institutional S Individual Consult nt and Maintenance Engineer IDA / 65150 Post Open 60,000.00 62,700.00 Signed 2021-04-09 2021-04-06 2021-05-28 2021-04-20 2021-06-18 2021-09-23 2021-07-23 2021-10-24 2023-07-23 trengthening ant Selection for Xayabuly Province AF-C3-02 / National Procure Component 3: Project Manag Individual Consult IDA / 65150 Post Open 70,000.00 92,928.00 Terminated 2021-05-16 2021-05-11 2021-07-04 2021-09-21 2021-07-25 2021-09-24 2021-08-29 2021-10-19 2022-02-25 ment Consultant for supporti ement ant Selection ng DoF C2-32 / NATIONAL SAFEGUA Component 2: Institutional S Individual Consult IDA / 59200 Post Limited 64,800.00 55,200.00 Signed 2021-06-07 2022-03-28 2021-06-12 2022-03-30 2021-07-03 2022-05-11 2021-08-07 2022-06-26 2022-02-03 RD COORDINATOR FOR PTRI trengthening ant Selection C2-35 / Consultant for prepa Component 2: Institutional S ring training curriculum and IDA / 59200 Post Direct Selection Direct 30,000.00 0.00 Canceled 2021-07-12 2021-07-22 2021-09-25 2022-03-24 trengthening action researches for PTRI AF-C2-15 / International Envi Component 2: Institutional S ronmental Risk Management IDA / 65150 Post Direct Selection Direct 60,000.00 32,160.00 Signed 2021-07-05 2021-07-12 2021-07-15 2021-07-12 2021-09-18 2021-08-16 2022-03-17 trengthening Consultant for PTRI AF-C2-16 / National Environ Component 2: Institutional S mental Risk Management Co IDA / 65150 Post Direct Selection Direct 100,000.00 56,980.00 Signed 2021-07-07 2021-07-06 2021-07-17 2021-09-29 2021-09-20 2021-06-15 2022-03-19 trengthening nsultant for PTRI AF-C2-17 / Social Risk Mana Component 2: Institutional S IDA / 65150 Post Direct Selection Direct 50,000.00 46,200.00 Signed 2021-07-07 2021-07-06 2021-07-17 2021-07-12 2021-09-20 2021-08-16 2022-03-19 gement Consultant trengthening AF-C2-18 / Community Enga Component 2: Institutional S IDA / 65150 Post Direct Selection Direct 25,000.00 24,000.00 Signed 2021-07-07 2021-07-06 2021-07-17 2021-07-14 2021-09-20 2021-08-16 2022-03-19 gement Consultant for PTRI trengthening AF-C2-19 / Field Survey Cons Component 2: Institutional S IDA / 65150 Post Direct Selection Direct 25,000.00 24,000.00 Signed 2021-07-07 2021-07-14 2021-07-17 2021-07-12 2021-09-20 2021-08-16 2022-03-19 ultant for PTRI trengthening AF-C3-03 / National Coordina Component 3: Project Manag Individual Consult IDA / 65150 Post Direct 165,000.00 162,000.00 Signed 2021-10-14 2021-09-29 2021-10-24 2021-09-29 2021-11-14 2021-09-30 2021-12-19 2021-10-19 2022-06-17 tion Advisor ement ant Selection AF-C3-05 / International Impl Component 3: Project Manag Individual Consult IDA / 65150 Post Direct 50,000.00 46,568.00 Signed 2022-02-04 2022-02-07 2022-02-14 2022-02-08 2022-03-07 2022-02-09 2022-04-11 2022-03-08 2022-10-08 ementation Support Consulta ement ant Selection nt AF-C3-06 / Financial Auditor Component 3: Project Manag IDA / 65150 Post Direct Selection Direct - National 60,000.00 0.00 Signed 2023-03-01 2023-01-18 2023-03-11 2023-02-13 2023-05-15 2023-12-07 2023-11-11 ( FY2023, 2024 and 2025) ement Component 3: Project Manag Individual Consult AF-C3-07 / Technical Auditor IDA / 65150 Post Direct - National 100,000.00 0.00 Signed 2023-02-01 2023-01-16 2023-02-11 2023-01-27 2023-03-04 2023-04-24 2023-04-08 2023-05-03 2023-10-05 ement ant Selection AF0-C2-21 / National Financi Component 3: Project Manag Individual Consult IDA / 65150 Post Direct - National 18,000.00 0.00 Canceled 2023-01-02 2023-01-12 2023-02-02 2023-03-09 2023-09-05 al Management Consultant ement ant Selection AF-C2-22 / National Environ Component 2: Institutional S Individual Consult mental and Social Safeguard IDA / 65150 Post Direct - National 87,500.00 0.00 Signed 2023-08-28 2023-07-03 2023-09-07 2023-07-14 2023-09-28 2023-08-20 2023-11-02 2023-09-30 2024-04-30 trengthening ant Selection s Consultant (NESSC) AF-C2-23 / National Social St Component 2: Institutional S Individual Consult IDA / 65150 Post Direct - National 18,000.00 0.00 Signed 2023-08-28 2023-07-03 2023-09-07 2023-07-14 2023-09-28 2023-08-15 2023-11-02 2023-09-28 2024-04-30 andard Consultant (NSSC) trengthening ant Selection AF-C3-08 / Junior Procureme Component 3: Project Manag Individual Consult IDA / 65150 Post Open - National 60,000.00 0.00 Signed 2023-09-25 2023-07-07 2023-11-13 2023-08-21 2023-12-04 2023-08-29 2024-01-08 2023-09-23 2024-07-06 nt Officer ement ant Selection AF-C2-21 / International Envi Component 2: Institutional S Individual Consult Direct - Internation ronmental and Social Standa IDA / 65150 Post 40,500.00 0.00 Signed 2023-07-30 2023-07-20 2023-08-09 2023-08-02 2023-08-30 2023-08-28 2023-10-04 2023-09-28 2024-04-01 trengthening ant Selection al rd Consultant (IESSC) AF-C2-24 / Environmental an Component 2: Institutional S Individual Consult d Social Management Consul IDA / 65150 Post Direct - National 42,000.00 0.00 Signed 2023-12-01 2023-09-05 2023-12-11 2023-09-12 2024-01-01 2023-09-18 2024-02-05 2023-10-13 2024-08-03 trengthening ant Selection tant (ESMC) AF-C2-26 / Internal Control A Component 2: Institutional S Individual Consult IDA / 65150 Post Direct - National 58,000.00 0.00 Under Review 2024-02-25 2024-02-26 2024-03-06 2024-03-27 2024-05-01 2024-10-28 dvisor trengthening ant Selection AF-C2-28 / Contract Manage Component 2: Institutional S Individual Consult Pending Impleme ment Consultant (CMC) to su IDA / 65150 Post Open - National 78,000.00 0.00 2024-03-08 2024-04-26 2024-05-17 2024-06-21 2024-12-18 trengthening ant Selection ntation pport DOR-MPWT Page 6