PROCUREMENT PLAN (Textual Part) Project information: Republic of Marshall Islands Sustainable Energy Development Project P160096 & P163699 Project Implementation agency: PREP2 PMU, Division of International Development Assistance-Ministry of Finance (DIDA-MOF), and SPC-Pacific Community Date of the Procurement Plan: May 10, 2018 Period covered by this Procurement Plan: May 1, 2018 to Nov 30, 2019 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the Procurement Code of 1988, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions: 1. The procurement is open to all eligible firms from any country; 2. The request for bids/request for proposals document shall require the Bidders/Proposers submitting Bids/Proposals present a signed acceptance at the time of bidding, to be incorporated in any resulting signed contracts, confirming application of, and compliance with, the Bank's Anti- Corruption Guidelines, including without limitation the Bank's right to sanction and the Bank's inspection and audit rights; 3. Publication of contract award information; 4. Rights for the Bank to review procurement documentation and activities; and 5. An effective complaints mechanism. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Not Applicable Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations: Not Applicable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Work) Goods: is not applicable; Works: is not applicable. PROCUREMENT Marshall Islands : Pacific Resilience Project II under the Pacific Resilience Program PLAN General Information Country: Marshall Islands 2018-10-21 Bank’s Approval Date of the Original Procurement Plan: 2023-06-02 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P160096 GPN Date: 2018-06-19 Project Name: Pacific Resilience Project II under the Pacific Resilience Program Loan / Credit No: IDA / D1830, IDA / V0410 Project Implementation Unit, PREP II Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned MH-PREP II-PIU-83439-CW-R Component 1: Institutional S Request for Quota Open - Internationa Single Stage - One E 2020-07-1 FB / NDMO Building Refurbish IDA / D1830 trengthening, Early Warning Post 750,000.00 0.00 Canceled 2019-11-23 2020-01-18 tions l nvelope 6 ment and Preparedness MH-PREP II-PIU-81920-CW-R Component 2: Strengthening Request for Propo Open - Internationa 35,312,500.0 2023-10-2 IDA / D1830 Prior Multi Stage 0.00 Canceled 2020-12-31 2021-01-05 2021-03-16 2021-06-28 2021-08-02 FP / Coastal Protection Works Coastal Resilience sals l 0 1 MH-PREP II-PIU-119118-CW- Component 1: Institutional S RFQ / Support for NDMO Stre Open - Internationa Single Stage - One E 2021-06-2 IDA / D1830 trengthening, Early Warning Prior Request for Bids 1,050,000.00 0.00 Canceled 2020-09-06 2020-09-11 2020-10-23 2020-11-22 2020-12-27 ngthening as per NDMO Roa l nvelope 5 and Preparedness dmap including NDMO Refurb ishment Works. MH-PREP II-PIU-252921-GO- Component 1: Institutional S RFQ / Support for NDMO Stre Request for Quota Single Stage - One E Other (with field f Under Imple 2024-02-1 IDA / D1830 trengthening, Early Warning Post Open - National 400,000.00 0.00 2023-06-21 2023-08-16 ngthening as per NDMO Roa tions nvelope or explanation) mentation 2 and Preparedness dmap including NDMO Refurb ishment Works MH-PREP II-PIU-356432-CW- Component 1: Institutional S DIR / Installation and Commis Other (with field f Under Imple 2023-11-1 IDA / D1830 trengthening, Early Warning Prior Direct Selection Direct - National 2,300,000.00 0.00 2023-04-13 2023-04-17 2023-04-18 2023-05-01 2023-05-23 sioning of the Emergency Co or explanation) mentation 9 and Preparedness mmunications Network and A ssociated Trainings Request for Bids - MH-PREP II-PIU-239881-CW- Component 2: Strengthening Open - Internationa Single Stage - Two E 36,987,473.0 2024-02-0 IDA / D1830 Prior Request for Bids Works SPD (after 0.00 Canceled 2021-12-01 2022-05-20 2022-02-16 2022-02-16 2021-12-06 2022-07-13 2022-04-27 2022-07-10 2022-08-14 RFB / Coastal Protection Wor Coastal Resilience l nvelope 0 5 prequalification) ks Request for Bids - MH-PREP II-PIU-364075-CW- Works (without pr Component 2: Strengthening Open - Internationa Single Stage - Two E 60,520,000.0 Pending Imp 2027-11-1 RFB / Coastal Protection Wor IDA / D1830 Prior Request for Bids equalification) SP 0.00 2023-06-27 2023-06-29 2023-10-01 2024-05-15 Coastal Resilience l nvelope 0 lementation 5 ks D - Applying contr actor disqualificia tion GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MH-PREP II-PIU-83438-GO-RF Component 4: Project and Pr Request for Quota Single Stage - One E Q / Office Equipment includin IDA / D1830 Post Open - National 61,000.00 0.00 Canceled 2019-08-05 2019-09-30 2020-03-28 ogram Management tions nvelope g Computers MH-PREP II-PIU-252918-GO- Component 4: Project and Pr Request for Quota Single Stage - One E RFQ / Office Equipment inclu IDA / D1830 Post Open - National 61,000.00 0.00 Signed 2021-10-05 2021-11-03 2021-11-30 2022-05-29 ogram Management tions nvelope ding Computers MH-PREP II-PIU-252920-GO- Component 1: Institutional S RFQ / Supply of IT equipment Request for Quota Single Stage - One E IDA / D1830 trengthening, Early Warning Post Open - National 50,000.00 39,155.87 Signed 2021-10-20 2021-11-11 2021-12-15 2022-07-15 2022-06-13 , outdoor equipment & office tions nvelope and Preparedness furniture under the NDMO Ro admap MH-PREP II-PIU-163821-GO- Component 4: Project and Pr Request for Quota Single Stage - One E IDA / D1830 Post Open - National 40,000.00 0.00 Canceled 2020-05-05 2020-06-30 2020-12-27 RFB / Project Vehicle ogram Management tions nvelope MH-PREP II-PIU-301507-GO- Component 4: Project and Pr Request for Quota Single Stage - One E IDA / D1830 Post Open - National 50,000.00 0.00 Signed 2022-07-20 2023-03-02 2022-09-14 2023-03-13 RFQ / Project Vehicle Resubm ogram Management tions nvelope ission MH-PREP II-PIU-83436-GO-RF Component 1: Institutional S Open - Internationa Single Stage - One E Q / Emergency Communicati IDA / D1830 trengthening, Early Warning Prior Request for Bids 1,100,000.00 0.00 Canceled 2022-01-03 2022-01-08 2022-02-19 2022-03-21 2022-04-25 2022-10-22 l nvelope on Equipment Supply & Com and Preparedness mission MH-PREP II-PIU-347314-GO- Component 1: Institutional S Request for Quota Single Stage - One E RFQ / VHF Emergency Comm IDA / D1830 trengthening, Early Warning Prior Limited 218,400.00 0.00 Signed 2023-03-12 2023-04-17 2023-05-07 2023-06-20 2023-11-03 tions nvelope unications Equipment Supply and Preparedness MH-PREP II-PIU-348605-GO- Component 4: Project and Pr Request for Quota Single Stage - One E Under Imple IDA / D1830 Post Open - National 10,000.00 0.00 2023-03-18 2023-05-13 2023-11-09 RFQ / Supply of Office Furnitu ogram Management tions nvelope mentation re for PIU MH-PREP II-PIU-342614-GO- Component 1: Institutional S Request for Quota Open - Internationa Single Stage - One E RFQ / IT Equipment to Suppo IDA / V0410 trengthening, Early Warning Post 48,700.00 0.00 Signed 2023-03-05 2023-03-27 2023-04-30 2023-10-27 tions l nvelope rt NDMO and Preparedness MH-PREP II-PIU-345824-GO- Component 1: Institutional S Request for Quota Open - Internationa Single Stage - One E RFQ / Non-IT Equipment Sup IDA / V0410 trengthening, Early Warning Post 9,900.00 0.00 Signed 2023-03-17 2023-04-09 2023-05-12 2023-11-08 tions l nvelope port to NDMO and Preparedness MH-PREP II-PIU-355664-GO- Component 1: Institutional S Request for Quota Single Stage - One E Under Imple RFQ / HF Communication Equ IDA / D1830 trengthening, Early Warning Prior Limited 666,550.00 0.00 2023-04-24 2023-04-17 2023-06-19 2023-12-16 tions nvelope mentation ipment for Support to EC Roa and Preparedness dmap MH-PREP II-PIU-361450-GO- Component 1: Institutional S RFQ / Procurement of masts Request for Quota Open - Internationa Single Stage - One E IDA / D1830 trengthening, Early Warning Post 235,000.00 0.00 Signed 2023-05-24 2023-05-17 2023-07-19 2024-01-15 and antennas in support of th tions l nvelope and Preparedness e Emergency Communication s Network NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 1 MH-PREP II-PIU-81923-NC-RF Component 4: Project and Pr Request for Quota Single Stage - One E IDA / D1830 Post Open - National 40,000.00 0.00 Canceled 2019-09-07 2019-11-02 2020-01-31 Q / M and E Satisfaction Surv ogram Management tions nvelope ey MH-PREP II-PIU-81925-NC-RF Component 4: Project and Pr Request for Quota Single Stage - One E IDA / D1830 Post Open - National 150,000.00 26,050.00 Signed 2019-07-05 2019-08-30 2021-10-06 2019-10-29 Q / PIU IT Support ogram Management tions nvelope MH-PREP II-PIU-81924-NC-RF Component 4: Project and Pr Request for Quota Single Stage - One E IDA / D1830 Post Open - National 20,000.00 0.00 Canceled 2019-10-05 2019-11-30 2019-12-30 Q / Translation Services ogram Management tions nvelope MH-PREP II-PIU-81919-NC-RF Component 2: Strengthening Request for Quota Open - Internationa Single Stage - One E IDA / D1830 Post 250,000.00 0.00 Canceled 2020-04-05 2020-05-31 2020-11-27 Q / UXO Removal Services Coastal Resilience tions l nvelope CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MH-PREP II-PIU-83435-CS-QC Component 2: Strengthening Quality And Cost- Open - Internationa BS / Coastal Engineering Desi IDA / D1830 Prior 3,210,000.00 2,897,518.50 Signed 2018-10-30 2019-01-14 2018-11-20 2019-01-30 2019-01-03 2019-11-05 2019-01-31 2020-02-17 2019-03-02 2020-04-06 2019-04-06 2020-09-07 2019-05-11 2020-10-25 2021-04-30 Coastal Resilience Based Selection l gn & Supervision Firm MH-PREP II-PIU-81918-CS-UN Component 1: Institutional S UN Agencies (Dire / Community DRM and Emerg IDA / D1830 trengthening, Early Warning Prior Direct 500,000.00 500,000.00 Signed 2020-01-09 2021-06-06 2021-12-29 ct) ency Communications Traini and Preparedness ng (IOM-UN) Component 1: Institutional S MH-PREP II-PIU-81916-CS-CQ Consultant Qualifi Open - Internationa IDA / D1830 trengthening, Early Warning Post 190,000.00 0.00 Canceled 2018-11-30 2018-12-21 2019-02-03 2018-11-06 2019-03-05 2019-04-09 2019-08-07 S / NDMO Building Design cation Selection l and Preparedness MH-PREP II-PIU-119121-CS-C Component 1: Institutional S Consultant Qualifi Open - Internationa QS / NDMO Structural Analysi IDA / D1830 trengthening, Early Warning Post 190,000.00 0.00 Canceled 2019-06-30 2019-07-21 2019-09-03 2019-10-03 2019-11-07 2020-05-05 cation Selection l s and Refurbishment Design and Preparedness MH-PREP II-PIU-163827-CS-C Component 1: Institutional S Consultant Qualifi QS / NAP Community Consult IDA / D1830 trengthening, Early Warning Prior Limited 500,000.00 0.00 Under Review 2020-05-05 2021-04-11 2020-05-19 2021-09-21 2020-06-18 2022-04-19 2020-07-23 2021-01-19 cation Selection ation and Preparedness MH-PREP II-PIU-110299-CS-C Component 4: Project and Pr Consultant Qualifi IDA / D1830 Post Limited 300,000.00 218,501.11 Signed 2020-04-16 2021-05-31 2020-04-30 2021-09-29 2020-05-30 2022-05-27 2020-07-04 2022-07-26 2020-12-31 QS / Communications and Me ogram Management cation Selection dia Firm MH-PREP II-PIU-217361-CS-Q CBS / Design of New NDMO Component 1: Institutional S Quality And Cost- Open - Internationa Warehouse and Office Accom IDA / D1830 trengthening, Early Warning Prior 550,000.00 0.00 Signed 2021-02-05 2021-09-16 2021-02-26 2021-11-30 2021-04-11 2022-05-01 2021-05-09 2022-06-23 2021-06-08 2022-09-27 2021-07-13 2023-02-12 2021-08-17 2023-03-29 2022-08-17 Based Selection l modation and Structural Anal and Preparedness ysis of the Existing NDMO Bui lding MH-PREP II-PIU-163844-CS-Q Component 1: Institutional S Quality And Cost- Open - Internationa CBS / Vulnerability and Planni IDA / D1830 trengthening, Early Warning Prior 600,000.00 0.00 Canceled 2020-03-17 2020-04-07 2020-05-21 2020-06-18 2020-07-18 2020-08-22 2020-09-26 2021-09-26 Based Selection l ng Consultancy Firm and Preparedness MH-PREP II-PIU-303510-CS-C Component 1: Institutional S Consultant Qualifi Open - Internationa QS / Vulnerability and Planni IDA / D1830 trengthening, Early Warning Prior 500,000.00 0.00 Signed 2022-07-24 2022-07-30 2022-08-14 2022-09-06 2022-09-27 2022-11-09 2022-10-27 2023-04-02 2022-12-01 2023-05-30 cation Selection l ng Consultancy Firm and Preparedness MH-PREP II-PIU-163825-CS-C Component 1: Institutional S Consultant Qualifi Open - Internationa QS / Community Vulnerability IDA / D1830 trengthening, Early Warning Post 250,000.00 0.00 Canceled 2020-05-03 2020-05-24 2020-07-07 2020-08-06 2020-09-10 2021-03-09 cation Selection l Mapping and Training and Preparedness MH-PREP II-PIU-163847-CS-C Component 1: Institutional S Consultant Qualifi Open - Internationa QS / Climate Financing Techn IDA / D1830 trengthening, Early Warning Post 200,000.00 0.00 Canceled 2023-06-01 2023-06-22 2023-08-05 2023-09-04 2023-10-09 2024-04-06 cation Selection l ical Assistance and Preparedness INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MH-PREP II-PIU-81917-CS-CD Component 2: Strengthening S / Coastal Vulnerability Asse IDA / D1830 Prior Direct Selection Direct 500,000.00 592,782.00 Signed 2019-04-04 2019-10-02 2019-04-14 2019-12-10 2019-06-18 2020-03-21 2020-01-10 Coastal Resilience ssment Firm MH-PREP II-PIU-81834-CS-IN Component 1: Institutional S Individual Consult DV / Emergency Communicat IDA / D1830 trengthening, Early Warning Post Open 120,000.00 64,425.00 Terminated 2019-04-30 2019-06-14 2019-06-18 2019-09-19 2019-07-09 2019-11-01 2019-08-13 2019-11-21 2020-06-08 ant Selection ion Specialist and Preparedness MH-PREP II-PIU-81915-CS-CD Component 2: Strengthening IDA / D1830 Prior Direct Selection Direct 50,000.00 0.00 Canceled 2018-11-16 2018-11-26 2019-01-30 2022-11-10 S / Coastal Design Adviser Coastal Resilience Component 1: Institutional S MH-PREP II-PIU-81927-CS-IN Individual Consult IDA / D1830 trengthening, Early Warning Post Open 480,000.00 0.00 Canceled 2018-10-15 2018-12-03 2018-12-24 2019-01-28 2021-01-17 DV / DRM and CCA Adviser ant Selection and Preparedness MH-PREP II-PIU-81928-CS-IN Component 1: Institutional S Individual Consult DV / Disaster and Climate Ris IDA / D1830 trengthening, Early Warning Post Open 202,500.00 0.00 Canceled 2018-10-15 2018-12-03 2018-12-24 2019-01-28 2021-01-17 ant Selection k Governance Adviser and Preparedness MH-PREP II-PIU-81926-CS-IN Component 2: Strengthening Individual Consult IDA / D1830 Post Limited 180,000.00 0.00 Canceled 2018-12-28 2019-01-02 2019-01-23 2019-02-27 2019-08-26 DV / Ebeye Project Represent Coastal Resilience ant Selection ative Component 1: Institutional S MH-PREP II-PIU-109655-CS-I Individual Consult IDA / D1830 trengthening, Early Warning Prior Open 324,000.00 648,000.00 Signed 2018-05-01 2018-01-03 2018-06-19 2018-08-24 2018-07-10 2018-09-27 2018-08-24 2018-10-01 2020-12-31 NDV / DRM&CCA Adviser ant Selection and Preparedness MH-PREP II-PIU-109653-CS-I Component 4: Project and Pr Individual Consult IDA / D1830 Prior Open 720,000.00 790,313.00 Signed 2017-02-14 2016-11-30 2017-03-28 2017-03-24 2017-04-20 2017-05-01 2017-05-01 2017-05-02 2020-05-14 NDV / Project Manager ogram Management ant Selection MH-PREP II-PIU-109656-CS-I Component 2: Strengthening Individual Consult IDA / D1830 Post Open 80,280.00 80,280.00 Completed 2018-04-18 2018-05-31 2018-06-06 2018-05-24 2018-06-27 2018-05-24 2018-07-31 2018-08-04 2020-07-01 2020-01-13 NDV / Ebeye Project Represe Coastal Resilience ant Selection ntative MH-PREP II-PIU-109654-CS-I Component 1: Institutional S Individual Consult NDV / Disaster and Climate R IDA / D1830 trengthening, Early Warning Prior Open 206,750.00 602,200.00 Signed 2018-04-01 2018-02-01 2018-05-20 2019-08-06 2018-06-10 2018-09-14 2018-07-13 2018-09-16 2020-08-31 ant Selection isk Governance Adviser and Preparedness Page 2 MH-PREP II-PIU-81838-CS-IN Component 4: Project and Pr Individual Consult DV / Communications & Medi IDA / D1830 Prior Open 240,000.00 0.00 Canceled 2018-11-30 2019-01-18 2019-02-08 2019-03-15 2021-03-04 ogram Management ant Selection a Specialist MH-PREP II-PIU-110300-CS-I Component 1: Institutional S Individual Consult NDV / Strategic Emergency C IDA / D1830 trengthening, Early Warning Post Open 80,000.00 135,100.00 Signed 2019-07-30 2019-06-14 2019-09-17 2019-09-19 2019-10-08 2019-11-01 2019-11-12 2019-11-25 2020-05-10 2022-07-08 ant Selection ommunications Adviser and Preparedness MH-PREP II-PIU-81832-CS-IN Component 4: Project and Pr Individual Consult IDA / D1830 Post Open 30,000.00 0.00 Canceled 2020-03-01 2020-04-19 2020-05-10 2020-06-14 2020-08-13 DV / Mid-term Reviewer ogram Management ant Selection MH-PREP II-PIU-81841-CS-IN Component 2: Strengthening Individual Consult IDA / D1830 Post Open 150,000.00 0.00 Canceled 2019-09-30 2020-02-18 2019-11-18 2019-12-09 2020-01-13 2020-07-11 DV / Value Engineering Coastal Resilience ant Selection MH-PREP II-PIU-137152-CS-I Component 4: Project and Pr Individual Consult IDA / D1830 Prior Open 480,000.00 13,022.00 Terminated 2020-05-16 2020-02-17 2020-07-04 2020-05-14 2020-07-25 2020-08-02 2020-08-29 2020-08-11 2021-02-25 NDV / Project Manager Post 2 ogram Management ant Selection 020 MH-PREP II-PIU-109652-CS-I Component 2: Strengthening Individual Consult IDA / D1830 Post Open 470,000.00 470,000.00 Signed 2017-10-25 2017-10-31 2017-11-01 2017-11-07 2017-11-19 2017-11-15 2017-12-20 2018-01-10 2020-01-31 NDV / Original Civil Engineeri Coastal Resilience ant Selection ng Advisor MH-PREP II-PIU-160075-CS-C Component 2: Strengthening IDA / D1830 Post Direct Selection Direct 150,000.00 154,975.00 Signed 2020-02-19 2020-03-05 2020-02-24 2020-04-17 2020-04-29 2020-06-21 2021-10-31 DS / Value Engineering Firm Coastal Resilience MH-PREP II-PIU-110298-CS-I Component 4: Project and Pr Individual Consult NDV / Local Communications IDA / D1830 Post Open 230,000.00 112,879.67 Terminated 2020-03-19 2020-05-19 2020-05-07 2020-09-14 2020-05-28 2020-10-15 2020-07-02 2020-11-08 2020-12-29 ogram Management ant Selection and M & E Officer MH-PREP II-PIU-81835-CS-IN Component 2: Strengthening Individual Consult IDA / D1830 Post Open 80,000.00 0.00 Canceled 2020-04-01 2020-05-20 2020-06-10 2020-07-15 2021-07-10 DV / Work Probity Assurance Coastal Resilience ant Selection Provider Component 1: Institutional S MH-PREP II-PIU-163845-CS-I Individual Consult IDA / D1830 trengthening, Early Warning Post Open 100,000.00 0.00 Canceled 2020-05-02 2021-03-23 2020-06-20 2020-07-11 2020-08-15 2021-02-11 NDV / NAP Coordinator ant Selection and Preparedness MH-PREP II-PIU-163848-CS-I Component 1: Institutional S Individual Consult NDV / Donor Coordination Te IDA / D1830 trengthening, Early Warning Prior Open 400,000.00 0.00 Canceled 2020-12-21 2021-02-08 2021-03-01 2021-04-05 2021-10-02 ant Selection chnical Assistance and Preparedness MH-PREP II-PIU-137154-CS-I Component 2: Strengthening Individual Consult NDV / Ebeye Project Represe IDA / D1830 Post Limited 100,000.00 0.00 Canceled 2020-07-01 2020-07-06 2020-07-27 2020-08-31 2021-02-27 Coastal Resilience ant Selection ntative Post 2020 MH-PREP II-PIU-81837-CS-IN Component 4: Project and Pr Individual Consult IDA / D1830 Post Open 180,000.00 0.00 Canceled 2019-07-30 2019-09-23 2019-09-17 2019-10-08 2019-11-12 2023-07-22 DV / Project Officer ogram Management ant Selection MH-PREP II-PIU-135263-CS-I Component 4: Project and Pr Individual Consult IDA / D1830 Post Open 190,000.00 0.00 Canceled 2019-09-27 2019-12-02 2019-11-15 2019-12-06 2020-01-10 2020-07-08 NDV / Implementation Suppo ogram Management ant Selection rt Specialist MH-PREP II-PIU-119120-CS-I Component 1: Institutional S Individual Consult NDV / Civil Engineering Advis IDA / D1830 trengthening, Early Warning Prior Open 470,000.00 0.00 Canceled 2019-08-19 2020-02-10 2019-10-07 2019-10-28 2019-12-02 2020-05-30 ant Selection er and Preparedness MH-PREP II-PIU-165685-CS-I Component 4: Project and Pr Individual Consult IDA / D1830 Post Open 255,000.00 70,000.00 Signed 2020-04-17 2019-12-16 2020-06-05 2020-06-09 2020-06-26 2020-06-09 2020-07-31 2020-06-10 2021-01-27 NDV / Project Officer ogram Management ant Selection MH-PREP II-PIU-165691-CS-I Component 4: Project and Pr Individual Consult IDA / D1830 Post Open 305,000.00 180,000.00 Terminated 2019-12-15 2019-12-01 2020-02-02 2020-01-09 2020-02-23 2020-02-01 2020-03-29 2020-02-15 2020-09-25 NDV / Implementation Suppo ogram Management ant Selection rt Specialist MH-PREP II-PIU-165694-CS-I Component 1: Institutional S Individual Consult NDV / Civil Engineering Advis IDA / D1830 trengthening, Early Warning Prior Open 770,000.00 734,375.00 Signed 2020-03-23 2020-05-06 2020-05-11 2020-04-24 2020-06-01 2020-07-27 2020-07-06 2020-08-05 2021-01-02 ant Selection er and Preparedness MH-PREP II-PIU-163846-CS-I Component 1: Institutional S Individual Consult NDV / Climate Change Adapt IDA / D1830 trengthening, Early Warning Prior Open 300,000.00 303,000.00 Terminated 2020-05-02 2020-05-06 2020-06-20 2020-07-09 2020-07-11 2020-08-11 2020-08-15 2020-08-19 2021-02-11 ant Selection ation Specialist and Preparedness MH-PREP II-PIU-202148-CS-C Component 4: Project and Pr IDA / D1830 Prior Direct Selection Direct 480,000.00 442,000.00 Signed 2020-10-30 2020-11-20 2020-11-03 2020-12-01 2020-11-06 2021-01-12 2022-11-05 DS / PREP II Project Manager ogram Management 2021 MH-PREP II-PIU-205222-CS-C Component 4: Project and Pr DS / Project Management Su IDA / D1830 Prior Direct Selection Direct 86,820.00 82,200.00 Signed 2020-11-20 2020-12-22 2020-11-30 2021-02-09 2020-12-15 2021-03-10 2021-06-13 ogram Management pport Specialist Component 1: Institutional S MH-PREP II-PIU-234808-CS-C IDA / D1830 trengthening, Early Warning Post Direct Selection Direct 100,000.00 83,625.00 Signed 2021-05-22 2021-07-01 2021-06-01 2021-08-23 2021-08-05 2021-09-06 2022-02-01 DS / NAP Coordinator and Preparedness MH-PREP II-PIU-246795-CS-I Component 1: Institutional S Individual Consult NDV / Disaster and Climate R IDA / D1830 trengthening, Early Warning Prior Open 400,000.00 0.00 Signed 2021-08-09 2021-10-11 2021-09-27 2022-03-30 2021-10-18 2022-04-23 2021-11-22 2023-05-21 2022-05-21 ant Selection esilience Donor Coordination and Preparedness Adviser Component 1: Institutional S MH-PREP II-PIU-81836-CS-IN Individual Consult IDA / D1830 trengthening, Early Warning Post Open 60,000.00 0.00 Signed 2019-04-28 2022-06-23 2019-06-16 2023-02-19 2019-07-07 2023-02-19 2019-08-11 2019-11-09 DV / DRM Legislative Drafter ant Selection and Preparedness MH-PREP II-PIU-228529-CS-I Component 1: Institutional S Individual Consult NDV / Donor Coordination Te IDA / D1830 trengthening, Early Warning Prior Direct 400,000.00 0.00 Canceled 2021-04-30 2021-08-16 2021-05-10 2021-05-31 2021-07-05 2022-01-01 ant Selection chnical Assistance and Preparedness MH-PREP II-PIU-257808-CS-I Component 4: Project and Pr Individual Consult NDV / Implementation Suppo IDA / D1830 Post Open 190,000.00 0.00 Signed 2021-10-31 2022-02-03 2021-12-19 2022-11-10 2022-01-09 2022-07-13 2022-02-13 2022-08-12 ogram Management ant Selection rt Specialist 2022 MH-PREP II-PIU-81840-CS-IN Component 2: Strengthening Individual Consult IDA / D1830 Post Open 120,000.00 0.00 Canceled 2019-11-30 2020-01-18 2020-02-08 2020-03-14 2020-09-10 DV / Contracts Disputes Boar Coastal Resilience ant Selection d Member MH-PREP II-PIU-301513-CS-I Component 1: Institutional S NDV / Senior Emergency Co Individual Consult IDA / V0410 trengthening, Early Warning Post Direct 80,000.00 0.00 Signed 2022-07-08 2022-07-14 2022-07-18 2022-08-11 2022-08-08 2022-08-16 2022-09-12 2023-03-11 mmunications Network Com ant Selection and Preparedness missioning Specialist MH-PREP II-PIU-137153-CS-I Component 1: Institutional S Individual Consult NDV / DRM&CCA Adviser pos IDA / D1830 trengthening, Early Warning Prior Open 324,000.00 0.00 Canceled 2021-01-01 2021-02-19 2021-03-12 2021-04-16 2021-10-13 ant Selection t 2020 and Preparedness Page 3 MH-PREP II-PIU-327141-CS-C Component 1: Institutional S Direct - Internation DS / Climate Change Adaptat IDA / D1830 trengthening, Early Warning Post Direct Selection 210,000.00 0.00 Canceled 2022-11-23 2022-12-02 2022-12-03 2022-12-20 2023-02-06 2023-08-05 al ion Specialist 2023 and Preparedness MH-PREP II-PIU-301516-CS-I Component 1: Institutional S NDV / Junior Emergency Com Individual Consult IDA / D1830 trengthening, Early Warning Post Open 50,000.00 0.00 Canceled 2022-10-01 2022-11-19 2022-12-10 2023-01-14 2023-07-13 munications Network Commi ant Selection and Preparedness ssioning Specialist MH-PREP II-PIU-347593-CS-I Component 4: Project and Pr Individual Consult NDV / Communication and M IDA / D1830 Post Open - National 30,000.00 0.00 Canceled 2023-03-07 2023-02-13 2023-04-25 2023-05-02 2023-05-16 2023-06-20 2023-12-17 ogram Management ant Selection onitoring & Evaluations Offic er MH-PREP II-PIU-81831-CS-IN Component 1: Institutional S Individual Consult Open - Internationa DV / Change Management Ad IDA / D1830 trengthening, Early Warning Prior 480,000.00 0.00 Canceled 2018-11-30 2019-01-18 2019-02-08 2019-03-15 2021-03-04 ant Selection l visor and Preparedness MH-PREP II-PIU-327137-CS-C Component 1: Institutional S DS / Disaster and Climate Re Direct - Internation IDA / D1830 trengthening, Early Warning Post Direct Selection 210,000.00 0.00 Canceled 2022-11-23 2022-12-02 2022-12-03 2022-12-19 2023-02-06 2023-08-05 silience Donor Coordination A al and Preparedness dviser (DCR-DCA) 2023 MH-PREP II-PIU-327141-CS-C Component 1: Institutional S Direct - Internation DS-2 / Climate Change Adapt IDA / D1830 trengthening, Early Warning Post Direct Selection 210,000.00 0.00 Signed 2023-03-16 2023-01-17 2023-03-26 2023-01-17 2023-05-30 2023-11-26 al ation Specialist 2023 and Preparedness MH-PREP II-PIU-362384-CS-I Component 4: Project and Pr Individual Consult Under Implement IDA / D1830 Post Open - National 20,000.00 0.00 2023-05-26 2023-05-19 2023-07-14 2023-08-04 2023-09-08 2024-03-06 NDV / Project Officer 2023 ogram Management ant Selection ation MH-PREP II-PIU-362549-CS-I Component 4: Project and Pr Individual Consult Open - Internationa Under Implement IDA / D1830 Post 60,000.00 0.00 2023-05-26 2023-05-19 2023-07-14 2023-08-04 2023-09-08 2024-03-06 NDV / Financial Management ogram Management ant Selection l ation Specialist MH-PREP II-PIU-81839-CS-IN Component 4: Project and Pr Individual Consult Open - Internationa Pending Impleme IDA / D1830 Post 30,000.00 0.00 2023-09-01 2023-10-20 2023-11-10 2023-12-15 2024-06-12 DV / End Term Reviewer ogram Management ant Selection l ntation MH-PREP II-PIU-365763-CS-I Component 1: Institutional S NDV / Junior Emergency Com Individual Consult Open - Internationa Under Implement IDA / D1830 trengthening, Early Warning Post 84,000.00 0.00 2023-06-16 2023-06-20 2023-08-04 2023-08-25 2023-09-29 2024-03-27 munications Network Commi ant Selection l ation and Preparedness ssioning Specialist Page 4 PROCUREMENT PLAN (Textual Part) Project information: [Mongolia] [COVID-19 emergency response and health system preparedness project] [P-173779] Project Implementation agency: [Ministry of Health] Date of the Procurement Plan: [25 March 2020] Period covered by this Procurement Plan: [Apr-Jun 2020] Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” dated July 2016 (Revised in November 2017 and August 2018) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the Law on Public Procurement of Goods, Works and Services, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: Not applicable (most if the Goods are not manufactured in country); Works: Not applicable (no works planned under this Project). Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations is Applicable. Under HIES the Project will receive the bank-facilitated procurement (BFP). BFP activities will include the following: 1. Conduct extensive market engagement and survey to identify available stock of the agreed list of critical medical consumables and equipment needed under this COVID10 response project (attached) in the quantities therein specified; 2. Assist [the Implementing Entity] in (i) negotiating prices, delivery terms, and other contract conditions with identified suppliers; 3. Draft final award letters and/or contracts adapted to specific market conditions, on a fit-for-purpose basis and ensuring consistency with Bank’s procurement framework; 4. Provide additional hands-on support in contracting to outsource logistics. Other HEIS activities are as follows: 5. Draft technical requirements and specifications, as requested by the [Implementing Entity; 6. Assist [the Implementing Entity] in drafting procurement documents; and 7. Provide advice on evaluation procedures, participate as observers during negotiations, by only clarifying matters of the Bank Procurement Regulations. Other Relevant Procurement Information. Given the nature of the Project, the procurement approach shall prioritize fast track emergency procurement for the required goods, works and services that include the following measures: - Direct Contracting and/or Limited Competition with identified manufacturers of equipment; - Use of CQS, RFQ or National Open/Limited Competitive procurement procedures as appropriate and agreed with the Bank in the Procurement Plan. - Considering existing framework agreements with international agencies like UNICEF, WHO, UNOPS and other UN agencies for procurement of medicines, medical supplies and commodity equipment for emergency requirements where the terms offered are more beneficial (such as delivery times); - Increasing advance payments to 40% when supported by an advance payment guarantee; - Waiving the conditions for bid securities and replacing them with Bid Securing Declarations; - Maximizing the use of direct payments to foreign suppliers; - Allowing submission of bids using emails in encrypted files where it is not feasible to receive bids in hardcopy. All procurements under this project will be subject to Post Review (there will be no Prior Review). Thresholds for fast track emergency procurement under the Project are: - Increased threshold for goods for shopping of US$500,000; - Increased threshold for National Procurement of U$1,000,000 and reduced bidding time to 7-14 days; - Use of CQS rather than QCBS for larger contract below (should read ‘above’?) US$500,000. PROCUREMENT Mongolia : MONGOLIA COVID-19 EMERGENCY RESPONSE AND HEALTH SYSTEM PREPAREDNESS PROJECT PLAN General Information Country: Mongolia 2020-04-27 Bank’s Approval Date of the Original Procurement Plan: 2023-06-01 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P173799 GPN Date: 2021-08-03 Project Name: MONGOLIA COVID-19 EMERGENCY RESPONSE AND HEALTH SYSTEM PREPAREDNESS PROJECT Loan / Credit No: IDA / 65940, IBRD / 90820, IDA / 68330 Ministry of Health Executing Agency(ies): WORKS Activity Reference No. / Procureme Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH Ri Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method nt Docume ount (US$ and Recommendation Signed Contract o. h cess (Y/N) sk atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion nt Type ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MN-MOH-212439-CW-UN / B Component 2: Strengthening UN Agencies (Dire 2,057,664.0 2022-01-3 uilding Capacity for COVID-1 IDA / 65940 Health Care Delivery Capacit Prior Direct Signed 2021-01-06 2021-01-15 2021-01-06 2021-01-16 2021-01-16 2021-01-19 ct) 0 1 9 Vaccine Infrastructure y GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MN-MOH-169104-GO-DIR / 2. Component 2: Strengthening IBRD / 90820 Post Direct Selection Direct 0.00 Canceled 2020-04-17 2020-04-22 2020-05-06 2020-06-17 1.6. Oxygen equipment Health Care Delivery Capacit y MN-MOH-169366-GO-DIR / 2. Component 2: Strengthening IBRD / 90820 Post Direct Selection Direct 0.00 Canceled 2020-04-20 2020-04-25 2020-05-09 2020-06-20 1.7. Laboratory equipment a Health Care Delivery Capacit nd tests y MN-MOH-169092-GO-DIR / 2. Component 2: Strengthening 1.1. VENTILATORS, CPAP AN IBRD / 90820 Health Care Delivery Capacit Post Direct Selection Direct 6,864,425.00 Signed 2020-04-17 2020-06-19 2020-04-22 2020-06-22 2020-05-06 2020-08-04 2020-06-17 D ACCESSORIES y MN-MOH-169095-GO-DIR / 2. 1.2. AUTOMATIC SUCTION PU MP, AUTOMATIC SYRINGE PU Component 2: Strengthening MP, EXAMINATION LIGHT, VEI IBRD / 90820 Health Care Delivery Capacit Post Direct Selection Direct 242,956.76 Signed 2020-04-17 2020-06-05 2020-04-22 2020-06-01 2020-05-06 2020-10-15 2020-06-17 N DETECTOR, DIGITAL DISTA y NCE THERMOMETER, LARYNG OSCOPE, HANDHELD VIDEO L ARYNGOSOPE, FINGER TYPE PULSOXIMETER MN-MOH-173769-GO-RFQ / 2 Component 2: Strengthening Request for Quota Single Stage - One E IBRD / 90820 Post Open - National 0.00 Canceled 2020-05-14 2020-05-22 2020-06-19 .1.3. CORPSE REFRIGERATOR Health Care Delivery Capacit tions nvelope S y MN-MOH-173770-GO-RFQ / 2 Component 2: Strengthening Request for Quota Single Stage - One E IBRD / 90820 Post Open - National 0.00 Canceled 2020-05-14 2020-05-21 2020-10-18 .1.4. ECMO MACHINE Health Care Delivery Capacit tions nvelope y MN-MOH-173773-GO-RFQ / 2 Component 2: Strengthening Request for Quota Single Stage - One E IBRD / 90820 Post Open - National 0.00 Canceled 2020-05-14 2020-05-21 2020-06-18 .1.5. CRRT, HEMODIALYSIS E Health Care Delivery Capacit tions nvelope QUIPMENT y MN-MOH-173780-GO-RFQ / 2 Component 2: Strengthening Request for Quota Single Stage - One E IBRD / 90820 Post Open - National 0.00 Canceled 2020-05-14 2020-05-21 2020-06-18 .1.12. REAL TIME PCR EQUIP Health Care Delivery Capacit tions nvelope MENT y MN-MOH-173776-GO-RFQ / 2 Component 2: Strengthening Request for Quota Single Stage - One E .1.8. MULTIFUNCTIONAL HOS IBRD / 90820 Health Care Delivery Capacit Post Open - National 0.00 Canceled 2020-05-14 2020-05-21 2020-06-18 tions nvelope PITAL BEDS y MN-MOH-169371-GO-DIR / 2. Component 2: Strengthening IDA / 65940 Post Direct Selection Direct 0.00 Canceled 2020-08-23 2020-08-30 2020-09-20 2020-10-20 1.a.1. Ventilator accessories Health Care Delivery Capacit y MN-MOH-173777-GO-RFQ / 2 Component 2: Strengthening Request for Quota Single Stage - One E IBRD / 90820 Post Open - National 0.00 Canceled 2020-05-14 2020-05-21 2020-06-18 .1.9. CRITICAL CARE CRASH Health Care Delivery Capacit tions nvelope CARTS y MN-MOH-173777-GO-RFQ-2 / Component 2: Strengthening Request for Quota Single Stage - One E IBRD / 90820 Post Open - National 0.00 Canceled 2020-08-30 2020-09-27 2020-11-08 2.1.9. CRITICAL CARE CRUSH Health Care Delivery Capacit tions nvelope CARTS y MN-MOH-180288-GO-DIR / 2. Component 2: Strengthening IBRD / 90820 Post Direct Selection Direct 707,294.48 Signed 2020-09-28 2020-05-28 2020-10-05 2020-05-28 2020-10-24 2020-08-25 2020-12-05 1.b.1. DIAGNOSTIC EQUIPME Health Care Delivery Capacit NT y MN-MOH-180319-GO-DIR / 2. Component 2: Strengthening IDA / 65940 Post Direct Selection Direct 0.00 Canceled 2020-09-14 2020-09-21 2020-10-10 2020-12-05 1.d.6. NEUROLOGICAL ICU E Health Care Delivery Capacit QUIPMENT y MN-MOH-180308-GO-DIR / 2. Component 2: Strengthening IBRD / 90820 Post Direct Selection Direct 948,815.00 Signed 2020-09-14 2020-12-02 2020-09-25 2020-12-02 2020-10-16 2021-05-29 2020-11-27 1.c.1. MEDICAL EQUIPMENT Health Care Delivery Capacit y MN-MOH-180316-GO-DIR / 2. Component 2: Strengthening IDA / 65940 Post Direct Selection Direct 659,064.00 Signed 2020-09-14 2020-12-01 2020-09-21 2021-01-20 2020-10-10 2021-02-25 2020-12-05 1.d.1. ICU MEDICAL EQUIPME Health Care Delivery Capacit NT y MN-MOH-180321-GO-RFQ / 2 Component 2: Strengthening Request for Quota Single Stage - One E IDA / 65940 Post Open - National 408,195.67 Signed 2020-09-21 2020-10-10 2020-12-12 2020-11-21 .1.d.3. ENDOSCOPY EQUIPME Health Care Delivery Capacit tions nvelope NT y MN-MOH-173778-GO-RFQ / 2 .1.10. REANIMATION EQUIPM Component 2: Strengthening Request for Quota Single Stage - One E ENT (PATIENT MONITORS, DE IBRD / 90820 Health Care Delivery Capacit Post Open - National 0.00 Canceled 2020-05-14 2020-05-21 2020-06-18 tions nvelope FIBRILLATORS, OXYGEN CON y CENTRATOR, ANESTHESIA M ACHINES) MN-MOH-173778-GO-RFQ-2 / 2.1.10. REANIMATION EQUIP Component 2: Strengthening Request for Quota Single Stage - One E MENT (PATIENT MONITOR, D IBRD / 90820 Health Care Delivery Capacit Post Open - National 0.00 Canceled 2020-08-30 2020-09-27 2020-11-08 tions nvelope EFIBRILLATOR, ECG, OXYGEN y CONCENTRATOR, HIGH FLOW OXYGEN DEVICE) MN-MOH-169373-GO-DIR / 2. Component 2: Strengthening IDA / 65940 Post Direct Selection Direct 1,269,370.00 Signed 2020-04-20 2020-10-12 2020-04-25 2020-10-09 2020-05-09 2020-12-03 2020-05-30 2.3. N95 masks, PPE Health Care Delivery Capacit y Page 1 MN-MOH-173775-GO-RFQ / 2 .1.7. LABORATORY EQUIPME Component 2: Strengthening NT (AUTOMATED AUTOCLAVE Request for Quota Single Stage - One E IBRD / 90820 Health Care Delivery Capacit Post Open - National 0.00 Canceled 2020-08-30 2020-09-27 2020-11-26 , CO2 INCUBATOR, BIO-SAFE tions nvelope y TY LEVEL 2 CABINET, BENCH TOP CENTRIFUGE, TABLETOP CENTRIFUGE) MN-MOH-173781-GO-RFQ / 2 Component 2: Strengthening Request for Quota Single Stage - One E IBRD / 90820 Post Open - National 0.00 Canceled 2020-10-12 2020-11-09 2020-12-21 .1.16. ENDOSCOPY DISINFEC Health Care Delivery Capacit tions nvelope TING UNIT y MN-MOH-173774-GO-RFQ / 2 Component 2: Strengthening Request for Quota Single Stage - One E IBRD / 90820 Post Open - National 0.00 Canceled 2020-08-30 2020-09-27 2020-11-08 .1.6. OXYGEN REGULATING E Health Care Delivery Capacit tions nvelope QUIPMENT y MN-MOH-169101-GO-DIR / 2. Component 2: Strengthening 1.14. SPECIFIC LABORATORY IBRD / 90820 Health Care Delivery Capacit Post Direct Selection Direct 0.00 Canceled 2020-08-30 2020-09-04 2020-09-18 2020-11-17 TESTS FOR ZOONOSIS CENTE y R, 25 TYPES MN-MOH-180426-GO-RFQ / 3 Component 3: Implementati Request for Quota Single Stage - One E .5. IT equipment for PIU speci IDA / 65940 on management and Monito Post Limited 19,429.74 Completed 2020-09-06 2020-09-17 2020-10-11 2020-10-01 2020-11-10 2020-12-16 tions nvelope alists ring and Evaluation MN-MOH-169368-GO-DIR / 2. Component 2: Strengthening IBRD / 90820 Post Direct Selection Direct 0.00 Canceled 2020-04-20 2020-04-25 2020-05-09 2020-06-20 1.13. PCR TESTS AND KITS Health Care Delivery Capacit y MN-MOH-173779-GO-RFQ / 2 Component 2: Strengthening .1.11. ISOLATION EQUIPMENT Request for Quota Single Stage - One E IBRD / 90820 Health Care Delivery Capacit Post Open - National 0.00 Canceled 2020-08-30 2020-09-27 2020-11-08 (NEGATIVE PRESSURE ISOLA tions nvelope y TION CHAMBER WITH STRET CHER) MN-MOH-169370-GO-DIR / 2. Component 2: Strengthening 1.15. PCR EXTRACTION KITS IBRD / 90820 Health Care Delivery Capacit Post Direct Selection Direct 0.00 Canceled 2020-08-23 2020-08-30 2020-09-20 2020-11-01 AND SUPPLIES y MN-MOH-169367-GO-DIR / 2. Component 2: Strengthening IDA / 65940 Post Direct Selection Direct 0.00 Canceled 2020-08-23 2020-08-30 2020-09-20 2020-11-01 2.1.8. INFUSION SETS AND S Health Care Delivery Capacit YRINGES y MN-MOH-180318-GO-DIR / 2. Component 2: Strengthening 1.d.5. EMERGENCY AND ICU IDA / 65940 Health Care Delivery Capacit Post Direct Selection Direct 0.00 Canceled 2020-09-14 2020-09-21 2020-10-17 2020-12-12 PREPAREDNESS EQUIPMENT y MN-MOH-180291-GO-DIR / 2. Component 2: Strengthening 1.b.2. SURGICAL AND INTENS IBRD / 90820 Health Care Delivery Capacit Post Direct Selection Direct 0.00 Canceled 2020-09-14 2020-09-21 2020-10-19 2020-11-30 IVE CARE EQUIPMENT y MN-MOH-169369-GO-DIR / 2. Component 2: Strengthening 2.1. INTERFERON ALPHA 2B IBRD / 90820 Health Care Delivery Capacit Post Direct Selection Direct 0.00 Canceled 2020-09-14 2020-09-21 2020-10-12 2020-11-11 NASAL SPRAY y MN-MOH-169102-GO-DIR / 2. Component 2: Strengthening 2.1.2. BACTERIAL LYSATE OM IDA / 65940 Health Care Delivery Capacit Post Direct Selection Direct 0.00 Canceled 2020-09-14 2020-09-21 2020-10-12 2020-11-23 -85 BRONCHOMUNAL y MN-MOH-173782-GO-RFQ / 2 Component 2: Strengthening Request for Quota Single Stage - One E .1.17. OXYGEN CYLINDER FIL IBRD / 90820 Health Care Delivery Capacit Post Open - National 0.00 Canceled 2020-10-05 2020-11-02 2021-01-31 tions nvelope LING SYSTEM, OXYGEN GAS y PLANT COMBINED MN-MOH-188110-GO-RFB / 2 Component 2: Strengthening Single Stage - One E IBRD / 90820 Post Request for Bids Open - National 0.00 Canceled 2020-08-30 2020-09-18 2020-09-13 2020-09-27 2020-10-06 2020-10-11 2020-11-08 2021-01-07 .1.1.2 General medical equip Health Care Delivery Capacit nvelope ment y MN-MOH-173769-GO-RFQ-2 / Component 2: Strengthening Request for Quota Single Stage - One E IBRD / 90820 Post Limited 0.00 Canceled 2020-08-25 2020-10-06 2020-12-05 2.1.3. CORPSE REFRIGERATO Health Care Delivery Capacit tions nvelope RS y MN-MOH-173770-GO-RFQ-2 / Component 2: Strengthening Request for Quota Single Stage - One E IBRD / 90820 Post Limited 0.00 Canceled 2020-08-25 2020-10-06 2020-12-05 2.1.4. ECMO MACHINE Health Care Delivery Capacit tions nvelope y MN-MOH-173773-GO-RFQ-2 / Component 2: Strengthening Request for Quota Single Stage - One E 2.1.5. CRRT, HEMODIALYSIS IBRD / 90820 Health Care Delivery Capacit Post Limited 0.00 Canceled 2020-08-25 2020-10-06 2020-12-05 tions nvelope EQUIPMENT y MN-MOH-173774-GO-RFQ-2 / Component 2: Strengthening Request for Quota Single Stage - One E 2.1.6. OXYGEN REGULATING IBRD / 90820 Health Care Delivery Capacit Post Limited 0.00 Canceled 2020-08-25 2020-10-06 2020-12-05 tions nvelope EQUIPMENT y MN-MOH-173775-GO-RFQ-2 / 2.1.7. LABORATORY EQUIPME Component 2: Strengthening NT (AUTOMATED AUTOCLAVE Request for Quota Single Stage - One E IBRD / 90820 Health Care Delivery Capacit Post Limited 0.00 Canceled 2020-08-25 2020-10-06 2020-12-05 , CO2 INCUBATOR, BIO-SAFE tions nvelope y TY LEVEL 2 CABINET, BENCH TOP CENTRIFUGE, TABLETOP CENTRIFUGE) MN-MOH-173777-GO-RFQ-3 / Component 2: Strengthening Request for Quota Single Stage - One E IBRD / 90820 Post Limited 0.00 Canceled 2020-08-25 2020-10-06 2020-12-05 2.1.9. CRITICAL CARE CRUSH Health Care Delivery Capacit tions nvelope CARTS y MN-MOH-173778-GO-RFQ-3 / Component 2: Strengthening 2.1.10. REANIMATION EQUIP Request for Quota Single Stage - One E IBRD / 90820 Health Care Delivery Capacit Post Limited 0.00 Canceled 2020-08-25 2020-10-06 2020-12-05 MENT (PATIENT MONITOR, D tions nvelope y EFIBRILLATOR, ECG, OXYGEN CONCENTRATOR) MN-MOH-173779-GO-RFQ-2 / Component 2: Strengthening 2.1.11. ISOLATION EQUIPMEN Request for Quota Single Stage - One E IBRD / 90820 Health Care Delivery Capacit Post Limited 0.00 Canceled 2020-08-25 2020-10-06 2020-12-05 T (NEGATIVE PRESSURE ISOL tions nvelope y ATION CHAMBER WITH STRE TCHER) MN-MOH-173780-GO-RFQ-2 / Component 2: Strengthening Request for Quota Single Stage - One E IBRD / 90820 Post Limited 0.00 Canceled 2020-08-25 2020-10-06 2020-12-05 2.1.12. REAL TIME PCR EQUIP Health Care Delivery Capacit tions nvelope MENT y MN-MOH-173781-GO-RFQ-2 / Component 2: Strengthening Request for Quota Single Stage - One E 2.1.16. ENDOSCOPY DISINFE IBRD / 90820 Health Care Delivery Capacit Post Limited 0.00 Canceled 2020-08-25 2020-10-06 2020-12-05 tions nvelope CTING UNIT y MN-MOH-173782-GO-DIR / 2. Component 2: Strengthening 1.17. OXYGEN CYLINDER FILL IBRD / 90820 Health Care Delivery Capacit Post Direct Selection Direct 0.00 Canceled 2020-08-23 2020-08-30 2020-10-11 2020-12-10 ING SYSTEM, OXYGEN GAS P y LANT COMBINED MN-MOH-169372-GO-DIR / 2. Component 2: Strengthening IDA / 65940 Post Direct Selection Direct 0.00 Canceled 2020-08-23 2020-08-30 2020-09-27 2020-10-27 2.2. PPE (EXAMINATION GLO Health Care Delivery Capacit VES) y Page 2 MN-MOH-169371-GO-RFQ / 2 Component 2: Strengthening Request for Quota Single Stage - One E IDA / 65940 Post Open - National 0.00 Canceled 2020-09-18 2020-10-23 2021-01-21 .1.1.1. Ventilator accessories Health Care Delivery Capacit tions nvelope y MN-MOH-173778-GO-RFQ-4 / 2.1.10. REANIMATION EQUIP Component 2: Strengthening Request for Quota Single Stage - One E MENT (PATIENT MONITOR, D IBRD / 90820 Health Care Delivery Capacit Post Open - National 0.00 Canceled 2020-09-18 2020-10-23 2021-01-21 tions nvelope EFIBRILLATOR, ECG, OXYGEN y CONCENTRATOR, HIGH FLOW OXYGEN DEVICE) MN-MOH-173769-GO-RFQ-4 / Component 2: Strengthening Request for Quota Single Stage - One E IBRD / 90820 Post Open - National 104,258.87 Signed 2020-09-18 2020-10-23 2020-10-27 2021-01-21 2.1.3. CORPSE REFRIGERATO Health Care Delivery Capacit tions nvelope RS y MN-MOH-173770-GO-RFQ-3 / Component 2: Strengthening Request for Quota Single Stage - One E IBRD / 90820 Post Open - National 201,169.47 Signed 2020-09-18 2020-10-23 2020-11-07 2021-01-21 2.1.4. ECMO MACHINE Health Care Delivery Capacit tions nvelope y MN-MOH-173773-GO-RFQ-3 / Component 2: Strengthening Request for Quota Single Stage - One E 2.1.5. CRRT, HEMODIALYSIS IBRD / 90820 Health Care Delivery Capacit Post Open - National 459,343.26 Signed 2020-09-18 2020-10-23 2020-11-07 2021-01-21 tions nvelope EQUIPMENT y MN-MOH-173774-GO-RFQ-3 / Component 2: Strengthening Request for Quota Single Stage - One E 2.1.6. OXYGEN REGULATING IBRD / 90820 Health Care Delivery Capacit Post Open - National 25,307.28 Signed 2020-09-18 2020-10-23 2020-12-25 2021-01-21 tions nvelope EQUIPMENT (CYLINDERS, INH y APERS) MN-MOH-173775-GO-RFQ-3 / 2.1.7. LABORATORY EQUIPME Component 2: Strengthening NT (AUTOMATED AUTOCLAVE Request for Quota Single Stage - One E IBRD / 90820 Health Care Delivery Capacit Post Open - National 34,586.59 Completed 2020-09-18 2020-10-23 2020-11-11 2021-01-21 2021-06-29 , CO2 INCUBATOR, BIO-SAFE tions nvelope y TY LEVEL 2 CABINET, BENCH TOP CENTRIFUGE, TABLETOP CENTRIFUGE) MN-MOH-173781-GO-RFQ-3 / Component 2: Strengthening Request for Quota Single Stage - One E 2.1.16. ENDOSCOPY DISINFE IBRD / 90820 Health Care Delivery Capacit Post Open - National 78,547.58 Signed 2020-09-18 2020-10-23 2020-12-09 2021-01-21 tions nvelope CTING UNIT y MN-MOH-173780-GO-RFQ-3 / Component 2: Strengthening Request for Quota Single Stage - One E IBRD / 90820 Post Open - National 171,931.20 Signed 2020-09-18 2020-10-23 2020-11-07 2021-01-21 2.1.12. REAL TIME PCR EQUIP Health Care Delivery Capacit tions nvelope MENT y MN-MOH-169368-GO-RFQ / 2 Component 2: Strengthening Request for Quota Single Stage - One E IBRD / 90820 Post Open - National 0.00 Canceled 2020-09-18 2020-10-23 2021-01-21 .1.13. PCR TESTS AND KITS Health Care Delivery Capacit tions nvelope y MN-MOH-169101-GO-RFQ / 2 Component 2: Strengthening Request for Quota Single Stage - One E .1.14. SPECIFIC LABORATORY IBRD / 90820 Health Care Delivery Capacit Post Open - National 0.00 Canceled 2020-09-18 2020-10-23 2021-01-21 tions nvelope TESTS FOR ZOONOTIC CENTE y R, 25 TYPES MN-MOH-173777-GO-RFQ-4 / Component 2: Strengthening Request for Quota Single Stage - One E IBRD / 90820 Post Open - National 272,884.03 Signed 2020-09-18 2020-10-23 2020-10-29 2021-01-21 2.1.9. CRITICAL CARE CRUSH Health Care Delivery Capacit tions nvelope CARTS y MN-MOH-173779-GO-RFQ-3 / Component 2: Strengthening 2.1.11. ISOLATION EQUIPMEN Request for Quota Single Stage - One E IBRD / 90820 Health Care Delivery Capacit Post Open - National 129,790.51 Signed 2020-09-18 2020-10-23 2020-12-09 2021-01-21 T (NEGATIVE PRESSURE ISOL tions nvelope y ATION CHAMBER WITH STRE TCHER) MN-MOH-173782-GO-RFQ-2 / Component 2: Strengthening Request for Quota Single Stage - One E 2.1.17. OXYGEN CYLINDER FI IBRD / 90820 Health Care Delivery Capacit Post Open - National 360,090.49 Signed 2020-09-18 2020-10-23 2020-12-09 2021-01-21 tions nvelope LLING SYSTEM, OXYGEN GAS y PLANT MN-MOH-169370-GO-RFQ / 2 Component 2: Strengthening Request for Quota Single Stage - One E .1.15. PCR EXTRACTION KITS IBRD / 90820 Health Care Delivery Capacit Post Open - National 0.00 Canceled 2020-09-18 2020-10-23 2021-01-21 tions nvelope AND SUPPLIES y MN-MOH-198939-GO-RFQ / 2 Component 2: Strengthening Request for Quota Single Stage - One E IDA / 65940 Post Open - National 94,166.02 Signed 2020-10-18 2020-11-15 2020-12-12 2020-12-15 .1.d.7. PENDANT SYSTEM Health Care Delivery Capacit tions nvelope y MN-MOH-180318-GO-RFQ / 2 Component 2: Strengthening Request for Quota Single Stage - One E IDA / 65940 Post Open - National 148,921.03 Signed 2020-10-18 2020-11-15 2020-12-12 2020-12-15 .1.d.5. ICU EMERGENCY EQUI Health Care Delivery Capacit tions nvelope PMENT y MN-MOH-180319-GO-RFQ / 2 Component 2: Strengthening Request for Quota Single Stage - One E IDA / 65940 Post Open - National 0.00 Canceled 2020-10-18 2020-11-15 2020-12-15 .1.d.6. ICU HOSPITAL EQUIPM Health Care Delivery Capacit tions nvelope ENT y MN-MOH-198949-GO-RFQ / 2 Component 2: Strengthening Request for Quota Single Stage - One E .1.d.8. IMAGING DIAGNOSTIC IDA / 65940 Health Care Delivery Capacit Post Open - National 52,211.69 Signed 2020-10-18 2020-11-15 2020-12-12 2020-12-15 tions nvelope EQUIPMENT y MN-MOH-201930-GO-DIR / 2. 1.b. ULTRASOUND MACHINES , ECG, PATIENT MONITORS, D Component 2: Strengthening EFIBRILATORS, SYRINGE AND IBRD / 90820 Health Care Delivery Capacit Post Direct Selection Direct 733,605.00 Signed 2020-10-28 2020-10-09 2020-11-11 2020-10-20 2020-12-16 2020-11-25 2021-01-27 INFUSION PUMPS, OXYGEN C y ONCENTRATOR, HEMATOLOG Y AND BLOOD ANALYZERS, NEONATAL CPAP MN-MOH-180298-GO-RFQ / 2 Component 2: Strengthening Request for Quota Single Stage - One E IBRD / 90820 Post Open - National 197,321.48 Signed 2020-11-05 2020-12-10 2021-01-19 2021-02-08 .1.b.6. ULTRASOUND 3D/4D Health Care Delivery Capacit tions nvelope MACHINE y MN-MOH-180293-GO-DIR / 2. Component 2: Strengthening IBRD / 90820 Post Direct Selection Direct 0.00 Canceled 2020-06-22 2020-06-29 2020-07-18 2020-09-12 1.b.4. LABORATORY EQUIPME Health Care Delivery Capacit NT y MN-MOH-201965-GO-RFQ / 2 Component 2: Strengthening Request for Quota Single Stage - One E .1.b. GYNECOLOGY AND OBS IBRD / 90820 Health Care Delivery Capacit Post Open - National 77,644.41 Signed 2020-11-23 2020-12-28 2021-06-16 2021-02-26 tions nvelope TETRICS INSTRUMENTS SET y MN-MOH-201974-GO-RFQ / 2 Component 2: Strengthening Request for Quota Single Stage - One E .1.b. WASHING, EXTRACTING IBRD / 90820 Health Care Delivery Capacit Post Open - National 0.00 Canceled 2020-11-23 2020-12-28 2021-02-26 tions nvelope EQUIPMENT y MN-MOH-212442-GO-DIR / C Component 2: Strengthening OVID-19 ANTIGEN TESTS @$ IBRD / 90820 Health Care Delivery Capacit Post Direct Selection Direct 0.00 Canceled 2021-01-22 2021-01-29 2021-02-19 2021-04-20 4.95 PER UNIT (INCLUSIVE OF y FREIGHT COST) MN-MOH-201966-GO-RFQ / 2 Component 2: Strengthening Request for Quota Single Stage - One E IBRD / 90820 Post Open - National 303,359.67 Signed 2021-01-27 2021-03-03 2021-05-25 2021-05-02 .1.b. ENDOSCOPY, LAPARASC Health Care Delivery Capacit tions nvelope OPY y MN-MOH-213325-GO-RFQ / 2 Component 2: Strengthening Request for Quota Single Stage - One E IBRD / 90820 Post Open - National 25,313.29 Completed 2021-01-27 2021-03-03 2021-05-28 2021-05-02 2022-08-21 .1.b. Low temperature steriliz Health Care Delivery Capacit tions nvelope er y Page 3 MN-MOH-180291-GO-RFQ / 2 Component 2: Strengthening .1.b. STATIONERY XRAY MAC Request for Quota Single Stage - One E IBRD / 90820 Health Care Delivery Capacit Post Open - National 323,763.66 Signed 2021-01-27 2021-03-03 2021-01-29 2021-05-02 HINE, FLUOROGRAPHY UNIT, tions nvelope y XRAY PACS VIEWER MN-MOH-201925-GO-DIR / 2. Component 2: Strengthening 1.b. COMPUTER TOMOGRAPH IBRD / 90820 Health Care Delivery Capacit Post Direct Selection Direct 0.00 Canceled 2020-10-28 2020-11-11 2020-12-16 2021-01-27 Y MACHINE, 64 SLICES y MN-MOH-201925-GO-RFB / 2 Component 2: Strengthening Single Stage - One E IBRD / 90820 Post Request for Bids Open - National 667,479.51 Signed 2021-01-20 2021-01-13 2021-01-27 2021-02-10 2021-02-02 2021-02-24 2021-02-10 2021-03-10 2021-02-24 2021-09-06 .1.b Computer tomography Health Care Delivery Capacit nvelope 64 slice y MN-MOH-201967-GO-RFQ / 2 Component 2: Strengthening Request for Quota Single Stage - One E IBRD / 90820 Post Open - National 42,530.29 Signed 2021-01-27 2021-03-03 2021-02-24 2021-05-02 .1.b. Cardiotocography, Fetal Health Care Delivery Capacit tions nvelope Doppler y MN-MOH-201968-GO-RFQ / 2 Component 2: Strengthening Request for Quota Single Stage - One E IBRD / 90820 Post Open - National 159,748.69 Signed 2021-01-27 2021-03-03 2021-02-24 2021-05-02 .1.b. ANAESTHESIA EQUIPME Health Care Delivery Capacit tions nvelope NT y MN-MOH-180299-GO-RFQ / 2 Component 2: Strengthening Request for Quota Single Stage - One E IDA / 65940 Post Open - National 140,337.96 Signed 2021-01-27 2021-02-22 2021-02-24 2021-04-05 .1.b.7. PATHOLOGICAL EQUIP Health Care Delivery Capacit tions nvelope MENT y MN-MOH-201975-GO-RFQ / 2 Component 2: Strengthening Request for Quota Single Stage - One E .1.b. Delivery bed and nursin IBRD / 90820 Health Care Delivery Capacit Post Open - National 199,528.92 Signed 2021-01-27 2021-03-03 2021-02-24 2021-05-02 tions nvelope g equipment y MN-MOH-213362-GO-RFQ / 2 Component 2: Strengthening Request for Quota Single Stage - One E IBRD / 90820 Post Open - National 8,716.95 Signed 2021-01-27 2021-03-03 2021-02-24 2021-04-17 .1.b Blood analyzer, automati Health Care Delivery Capacit tions nvelope c y MN-MOH-180301-GO-RFQ / 2 Component 2: Strengthening Request for Quota Single Stage - One E Under Imple IDA / 65940 Post Open - National 0.00 2020-06-29 2020-08-01 2020-09-12 .1.b.8. COMPUTER, SERVER H Health Care Delivery Capacit tions nvelope mentation ARDWARE y MN-MOH-180302-GO-RFQ / 2 Component 2: Strengthening Request for Quota Single Stage - One E IDA / 65940 Post Open - National 46,620.21 Signed 2020-06-29 2020-07-18 2020-12-11 2020-08-29 .1.b.9. HOSPITAL KITCHEN EQ Health Care Delivery Capacit tions nvelope UIPMENT y MN-MOH-201974-GO-DIR / 2. Component 2: Strengthening IBRD / 90820 Post Direct Selection Direct 129,993.91 Signed 2020-12-09 2020-11-21 2020-12-14 2020-11-18 2021-01-02 2020-12-24 2021-02-01 1.b. WASHING, CLEANING EQ Health Care Delivery Capacit UIPMENT y MN-MOH-201878-GO-RFQ / 2 Component 2: Strengthening Request for Quota Single Stage - One E IBRD / 90820 Post Open - National 0.00 Canceled 2021-01-27 2021-03-03 2021-04-02 .1.b. HOSPITAL ARCHIVING E Health Care Delivery Capacit tions nvelope QUIPMENT y MN-MOH-201977-GO-RFQ / 2 Component 2: Strengthening Request for Quota Single Stage - One E IBRD / 90820 Post Open - National 24,811.09 Signed 2021-01-27 2021-03-03 2021-05-25 2021-04-17 .1.b. MEDICAL MEASURING E Health Care Delivery Capacit tions nvelope QUIPMENT y MN-MOH-180295-GO-RFQ / 2 Component 2: Strengthening Request for Quota Single Stage - One E .1.b.5. STERILIZATION AND W IBRD / 90820 Health Care Delivery Capacit Post Open - National 133,098.96 Signed 2020-06-29 2020-07-18 2021-01-29 2020-08-29 tions nvelope ASHING EQUIPMENT y MN-MOH-180293-GO-RFQ / 2 Component 2: Strengthening Request for Quota Single Stage - One E IBRD / 90820 Post Open - National 318,621.66 Signed 2020-11-06 2020-12-11 2021-01-29 2021-02-09 .1.b. LABORATORY EQUIPME Health Care Delivery Capacit tions nvelope NT y MN-MOH-180294-GO-RFQ / 2 Component 2: Strengthening Request for Quota Single Stage - One E IBRD / 90820 Post Open - National 0.00 Canceled 2021-01-27 2021-02-15 2021-03-29 .1.b.3. REHABILITATION EQUI Health Care Delivery Capacit tions nvelope PMENT y MN-MOH-201970-GO-RFQ / 2 Component 2: Strengthening Request for Quota Single Stage - One E IBRD / 90820 Post Open - National 42,764.63 Signed 2021-01-27 2021-03-03 2021-05-25 2021-05-02 .1.b. NEONATAL CARE EQUIP Health Care Delivery Capacit tions nvelope MENT y MN-MOH-201972-GO-RFQ / 2 Component 2: Strengthening Request for Quota Single Stage - One E .1.b. ELECTROSURGICAL UNI IBRD / 90820 Health Care Delivery Capacit Post Open - National 47,611.65 Signed 2021-01-27 2021-03-03 2021-05-25 2021-05-02 tions nvelope TS, AUTOMATIC SUCTION PU y MPS MN-MOH-201880-GO-RFQ / 2 Component 2: Strengthening Request for Quota Single Stage - One E .1.b. Electroencephalogram, IBRD / 90820 Health Care Delivery Capacit Post Open - National 34,109.04 Signed 2021-01-27 2021-03-03 2021-05-25 2021-04-02 tions nvelope holter monitor, spirometer y MN-MOH-201933-GO-RFQ / 2 Component 2: Strengthening Request for Quota Single Stage - One E .1.b. Neonatal phototherapy, IBRD / 90820 Health Care Delivery Capacit Post Open - National 0.00 Canceled 2021-01-27 2021-03-03 2021-04-14 tions nvelope warmer, incubator, y MN-MOH-201877-GO-RFQ / 2 Component 2: Strengthening Request for Quota Single Stage - One E IBRD / 90820 Post Open - National 229,267.77 Signed 2020-11-23 2020-12-28 2020-12-17 2021-02-11 .1.b. HOSPITAL OFFICE FURNI Health Care Delivery Capacit tions nvelope TURE y MN-MOH-201978-GO-RFQ / 2 Component 2: Strengthening Request for Quota Single Stage - One E Pending Impl IBRD / 90820 Post Open - National 0.00 2021-01-27 2021-03-03 2021-05-02 .1.a. Vaccine Syringe, safety Health Care Delivery Capacit tions nvelope ementation box y MN-MOH-216269-GO-UN / D ue to emergency case, vacci Component 2: Strengthening ne cold chain equipment will UN Agencies (Dire IBRD / 90820 Health Care Delivery Capacit Prior Direct 2,900,000.00 Signed 2021-01-27 2021-02-06 2021-02-01 2021-02-07 2021-03-08 2021-02-13 2021-09-04 supply directly from UNICEF s ct) y hopping list. Therefore, UNIC EF would be WB direct contra cter. MN-MOH-180320-GO-RFQ / 2 Component 2: Strengthening Request for Quota Single Stage - One E IDA / 65940 Post Open - National 221,181.57 Completed 2021-03-04 2021-03-23 2021-02-15 2021-05-04 2021-04-28 .1.d.2. EMERGENCY EQUIPME Health Care Delivery Capacit tions nvelope NT y MN-MOH-180322-GO-RFQ / 2 Component 2: Strengthening Request for Quota Single Stage - One E IDA / 65940 Post Open - National 110,559.24 Signed 2021-03-04 2021-03-23 2021-02-11 2021-05-04 .1.d.6. NEUROLOGICAL ICU E Health Care Delivery Capacit tions nvelope QUIPMENT y MN-MOH-180304-GO-RFQ / 2 Component 2: Strengthening .1.c.2. Aquapheresis apparat Request for Quota Single Stage - One E Under Imple IDA / 65940 Health Care Delivery Capacit Post Open - National 0.00 2021-03-17 2021-04-10 2021-05-22 us, CRRT, Hemodialisys wate tions nvelope mentation y r apparatus, Double water di stiller MN-MOH-180306-GO-RFQ / 2 Component 2: Strengthening Request for Quota Single Stage - One E .1.c.23. Surgical microscope, IDA / 65940 Health Care Delivery Capacit Post Open - National 227,704.03 Completed 2021-03-17 2021-04-05 2021-07-26 2021-05-17 2021-12-31 tions nvelope Viterctomy, phacomachine y MN-MOH-169369-GO-RFQ / 2 Component 2: Strengthening Request for Quota Single Stage - One E IDA / 65940 Post Open - National 414,940.00 Signed 2021-03-17 2021-04-26 2021-06-16 2021-07-25 .1.c.3 Endoscopic ultrasound Health Care Delivery Capacit tions nvelope set y MN-MOH-169102-GO-RFQ / 2 Component 2: Strengthening Request for Quota Single Stage - One E IDA / 65940 Post Open - National 0.00 Canceled 2021-03-17 2021-04-28 2021-07-27 .1.c.4. Laboratory equipment Health Care Delivery Capacit tions nvelope y MN-MOH-169367-GO-RFQ / 2 Component 2: Strengthening Request for Quota Single Stage - One E Pending Impl .1.c.6 Nursing examination e IDA / 65940 Health Care Delivery Capacit Post Open - National 0.00 2021-03-23 2021-05-04 2021-08-02 tions nvelope ementation quipment y Page 4 MN-MOH-169372-GO-RFQ / 2 Component 2: Strengthening Request for Quota Single Stage - One E IDA / 65940 Post Open - National 0.00 Canceled 2021-03-23 2021-05-04 2021-08-02 .1.c.7. Bipap, CPAP, high flow Health Care Delivery Capacit tions nvelope y MN-MOH-221838-GO-RFQ / 2 Component 2: Strengthening Request for Quota Single Stage - One E IDA / 65940 Post Open - National 0.00 Canceled 2021-04-04 2021-06-07 2021-08-06 .1.c.9. Post operation care ap Health Care Delivery Capacit tions nvelope pliances y MN-MOH-221841-GO-RFQ / 2 Component 2: Strengthening Request for Quota Single Stage - One E .1.c.11. Endoscopy diagnosti IDA / 65940 Health Care Delivery Capacit Post Open - National 108,391.41 Signed 2021-03-29 2021-05-18 2021-06-16 2021-07-17 tions nvelope c set with accessories y MN-M0H-221844-GO-RFQ / 2 Component 2: Strengthening Request for Quota Single Stage - One E Under Imple IDA / 65940 Post Open - National 0.00 2021-04-06 2021-06-13 2021-08-12 .1.c.12. Surgery equipment Health Care Delivery Capacit tions nvelope mentation y MN-MOH-221845-GO-RFQ / 2 Component 2: Strengthening Request for Quota Single Stage - One E IDA / 65940 Post Open - National 57,863.62 Signed 2021-04-02 2021-06-04 2021-04-16 2021-08-03 .1.c.13. Patient monitoring s Health Care Delivery Capacit tions nvelope ystem y MN-MOH-221847-GO-RFQ / 2 Component 2: Strengthening Request for Quota Single Stage - One E Pending Impl IDA / 65940 Post Open - National 0.00 2021-04-06 2021-06-13 2021-06-19 .1.c.14. Ultrasound diagnosti Health Care Delivery Capacit tions nvelope ementation c unit y MN-M0H-221849-GO-RFQ / 2 Component 2: Strengthening Request for Quota Single Stage - One E Pending Impl IDA / 65940 Post Open - National 0.00 2021-04-04 2021-06-13 2021-06-19 .1.c.15. Neuromonitoring equ Health Care Delivery Capacit tions nvelope ementation ipment y MN-MOH-221853-GO-RFQ / 2 Component 2: Strengthening Request for Quota Single Stage - One E IDA / 65940 Post Open - National 115,354.63 Signed 2021-03-28 2021-06-06 2021-07-23 2021-08-05 .1.c.17. ENT diagnostic unit Health Care Delivery Capacit tions nvelope y MN-MOH-221855-GO-RFQ / 2 Component 2: Strengthening Request for Quota Single Stage - One E Pending Impl IDA / 65940 Post Open - National 0.00 2021-04-05 2021-06-14 2021-08-13 .1.c.18. Ankle arthroscopic su Health Care Delivery Capacit tions nvelope ementation rgery set y MN-MOOH-221858-GO-RFQ / Component 2: Strengthening Request for Quota Single Stage - One E Pending Impl 2.1.c.19. Tissue cassette writ IDA / 65940 Health Care Delivery Capacit Post Open - National 0.00 2021-04-05 2021-06-14 2021-07-29 tions nvelope ementation er and Histology equipment y MN-MOH-221859-GO-RFQ / 2 Component 2: Strengthening Request for Quota Single Stage - One E Pending Impl IDA / 65940 Post Open - National 0.00 2021-04-05 2021-06-14 2021-08-13 .1.c.20. Drug packing equipm Health Care Delivery Capacit tions nvelope ementation ent y MN-MOH-221860-GO-RFQ / 2 Component 2: Strengthening Request for Quota Single Stage - One E Pending Impl .1.c.21. Medical equipment t IDA / 65940 Health Care Delivery Capacit Post Open - National 0.00 2021-04-13 2021-06-22 2021-08-21 tions nvelope ementation esting devices y MN-MOH-221861-GO-RFQ / 2 Component 2: Strengthening Request for Quota Single Stage - One E Pending Impl IDA / 65940 Post Open - National 0.00 2021-04-21 2021-06-30 2021-12-27 .1.c.22. Ambulance car Health Care Delivery Capacit tions nvelope ementation y MN-MOH-180310-GO-DIR / B Component 2: Strengthening IDA / 65940 Post Direct Selection Direct 78,540.00 Signed 2020-06-29 2020-11-25 2020-07-06 2020-11-27 2020-07-25 2020-12-24 2020-09-19 FP contract... patient bed Health Care Delivery Capacit y MN-MOH-221850-GO-RFQ / 2 Component 2: Strengthening Single Stage - One E Under Imple IDA / 65940 Post Request for Bids Open - National 0.00 2021-03-31 2021-05-12 2021-04-05 2021-05-17 2021-06-16 2021-07-21 2021-09-19 .1.c.16. Surgery set Health Care Delivery Capacit nvelope mentation y MN-M0H-221840-GO-RFQ / 2 Component 2: Strengthening Request for Quota Single Stage - One E .1.c.10. Endoscopy washer, s IDA / 65940 Health Care Delivery Capacit Post Open - National 24,603.92 Signed 2021-03-30 2021-06-01 2021-04-16 2021-07-31 tions nvelope terilization case y MN-MOH-181224-GO-RFQ / 2 Component 2: Strengthening Request for Quota Single Stage - One E Pending Impl IDA / 65940 Post Open - National 0.00 2021-03-30 2021-06-01 2021-07-31 .1.c.8. Physio and therapy de Health Care Delivery Capacit tions nvelope ementation vices y MN-MOH-169371-GO-RFQ-2 / Component 2: Strengthening Request for Quota Single Stage - One E IBRD / 90820 Post Open - National 135,230.63 Signed 2021-03-18 2021-04-22 2021-05-25 2021-07-21 2.1.1.1. Ventilator accessorie Health Care Delivery Capacit tions nvelope s y MN-MOH-188110-GO-RFB-2 / Component 2: Strengthening 2.1.1.2 General medical equi IBRD / 90820 Health Care Delivery Capacit Post Request for Bids 468,161.62 Signed 2021-03-11 2021-02-09 2021-03-18 2021-04-01 2021-03-12 2021-04-22 2021-05-03 2021-05-06 2021-05-25 2021-08-04 pment (re-announcement) y MN-MOH-169102-GO-RFQ-2 / Component 2: Strengthening Request for Quota Single Stage - One E Pending Impl IDA / 65940 Post Open - National 0.00 2021-05-08 2021-06-19 2021-09-17 2.1.c.4. Laboratory equipmen Health Care Delivery Capacit tions nvelope ementation t y MN-MOH-169372-GO-RFQ-2 / 2.1.c.7. Teaching hospital BiPap machine Component 2: Strengthening Request for Quota Single Stage - One E Pending Impl Mini ventilator /CPAP/ IDA / 65940 Health Care Delivery Capacit Post Open - National 0.00 2021-05-24 2021-07-05 2021-10-03 tions nvelope ementation Mechanical Ventilator for MRI y system High flow nasal canula MN-MOH-235531-GO-DIR / R Component 2: Strengthening T-PCR and RNA Extraction Kit IBRD / 90820 Health Care Delivery Capacit Post Direct Selection Direct 0.00 Canceled 2021-05-21 2021-05-21 2021-05-28 2021-06-18 2021-08-17 For COVID -19 Control and Pr y evention MN-MOH-236935-GO-DIR / 2. Component 2: Strengthening 1.a.RT-PCR and Extraction kit IBRD / 90820 Health Care Delivery Capacit Post Direct Selection Direct 264,199.32 Completed 2021-05-28 2021-05-28 2021-05-31 2021-05-28 2021-06-15 2021-06-04 2021-07-15 2021-06-11 s for COVID-19 Control and P y revention MN-MOH-236938-GO-DIR / 2. Component 2: Strengthening 1.a. RT-PCR test kits for COVI IBRD / 90820 Health Care Delivery Capacit Post Direct Selection Direct 120,305.05 Signed 2021-05-28 2021-05-27 2021-05-31 2021-05-28 2021-06-15 2021-06-04 2021-07-20 D-19 Control and Prevention y MN-MOH-180427-GO-RFQ / 3 Component 3: Implementati Request for Quota Single Stage - One E .6. Furniture for PIU specialist IDA / 65940 on management and Monito Post Limited 0.00 Canceled 2020-08-30 2020-10-04 2020-11-03 tions nvelope s ring and Evaluation MN-MOH-247241-GO-RFQ / 1 Component 1: Emergency C Request for Quota Single Stage - One E Pending Impl .2.1.B.5. COVID19 VACCINE E IDA / 68330 OVID-19 Prevention and Res Post Open - National 0.00 2021-08-31 2021-10-10 2022-01-31 tions nvelope ementation FFICIENCY STUDY EQUIPMEN ponse T AND SUPPLIES MN-MOH-180294-GO-RFQ-2 / Component 2: Strengthening Request for Quota Single Stage - One E IBRD / 90820 Post Open - National 44,122.16 Signed 2021-08-18 2021-09-29 2021-09-26 2021-11-28 2.1.b.3.Rehabilitation equipm Health Care Delivery Capacit tions nvelope ent y MN-MOH-201878-GO-RFQ-2 / Component 2: Strengthening Request for Quota Single Stage - One E IBRD / 90820 Post Open - National 0.00 Canceled 2021-08-18 2021-09-29 2021-11-28 2.1.b.Hospital archiving equi Health Care Delivery Capacit tions nvelope pment y MN-MOH-253569-GO-RFQ / 2 Component 2: Strengthening Request for Quota Single Stage - One E IDA / 68330 Post Open - National 162,106.56 Signed 2021-09-27 2021-10-25 2021-11-06 2021-12-24 .2.3.2. PULSE OXIMETERS, FI Health Care Delivery Capacit tions nvelope NGER TIP y MN-MOH-262038-GO-DIR / 2. Component 2: Strengthening 2.2.1. COVID-19 VACCINES (2 IDA / 68330 Health Care Delivery Capacit Prior Direct Selection Direct 4,500,000.00 Completed 2021-11-08 2021-11-25 2021-11-15 2021-12-21 2021-12-14 2021-03-19 2022-01-13 2022-06-02 ND CONTRACT) y Page 5 MN-MOH-239597-GO-DIR / 2. Component 2: Strengthening IDA / 68330 Prior Direct Selection Direct 26,000,000.00 Completed 2021-06-15 2021-11-25 2021-06-22 2021-12-21 2021-09-15 2022-03-19 2021-10-15 2022-06-02 2.2.1. COVID-19 VACCINES Health Care Delivery Capacit y MN-MOH-331981-GO-DIR / C Component 2: Strengthening Direct - Internation Under Imple IDA / 68330 Prior Direct Selection 0.00 2022-12-18 2023-05-05 2022-12-19 2022-12-21 2022-12-22 OVID-19 VACCINES Health Care Delivery Capacit al mentation y MN-MOH-332103-GO-RFQ / P Component 2: Strengthening Request for Quota Single Stage - One E ackage 1 - Continuous renal r IDA / 68330 Health Care Delivery Capacit Post Open - National 0.00 Signed 2022-12-20 2022-12-20 2023-02-24 2023-07-04 tions nvelope eplacement therapy y MN-MOH-332108-GO-RFQ / P Component 2: Strengthening Request for Quota Single Stage - One E ackage 7 - Diagnostic and tr IDA / 68330 Health Care Delivery Capacit Post Open - National 0.00 Signed 2022-12-20 2022-12-19 2023-02-24 2023-07-04 tions nvelope eatment equipment y MN-MOH-332110-GO-RFQ / P Component 2: Strengthening Request for Quota Single Stage - One E Pending Impl IBRD / 90820 Post Open - National 0.00 2022-12-16 2023-01-19 2023-02-28 2023-07-08 ackage 8 - Rehabilitation equ Health Care Delivery Capacit tions nvelope ementation ipment y MN-MOH-332112-GO-RFQ / P Component 2: Strengthening Request for Quota Single Stage - One E IBRD / 90820 Post Open - National 0.00 Signed 2022-12-20 2022-12-20 2023-02-24 2023-07-04 ackage 9 - Surgery hand tool Health Care Delivery Capacit tions nvelope set y MN-MOH-332116-GO-RFQ / P Component 2: Strengthening Request for Quota Single Stage - One E IBRD / 90820 Post Open - National 0.00 Signed 2022-12-20 2023-02-24 2023-07-04 ackage 10 - Surgical equipm Health Care Delivery Capacit tions nvelope ent y MN-MOH-332117-GO-RFQ / P Component 2: Strengthening Request for Quota Single Stage - One E ackage 11 - Biomedical equip IBRD / 90820 Health Care Delivery Capacit Post Open - National 0.00 Signed 2022-12-20 2022-12-20 2023-02-24 2023-07-04 tions nvelope ment inspection analyzator y MN-MOH-332121-GO-RFQ / P Component 2: Strengthening Request for Quota Single Stage - One E IBRD / 90820 Post Open - National 0.00 Signed 2022-12-20 2022-12-20 2023-02-24 2023-07-04 ackage 13 - Endoscope set Health Care Delivery Capacit tions nvelope y MN-MOH-332125-GO-RFQ / P Component 2: Strengthening Request for Quota Single Stage - One E IBRD / 90820 Post Open - National 0.00 Signed 2022-12-20 2022-12-20 2023-02-24 2023-07-04 ackage 14 - Radiology equip Health Care Delivery Capacit tions nvelope ment y G01 / Package 9. Neonatal tr Component 2: Strengthening Request for Quota Single Stage - One E IDA / 68330 Post Open - National 0.00 Signed 2023-01-31 2023-03-16 2023-08-03 eatment equipment Health Care Delivery Capacit tions nvelope y G02 / Package 23. Archiving Component 2: Strengthening Request for Quota Single Stage - One E IDA / 68330 Post Open - National 0.00 Signed 2023-01-31 2023-03-16 2023-08-03 shelves Health Care Delivery Capacit tions nvelope y G03 / Package 6. Stretcher, Component 2: Strengthening Request for Quota Single Stage - One E IDA / 68330 Post Open - National 0.00 Signed 2023-01-31 2023-03-16 2023-08-03 Therapeutic normothermic sy Health Care Delivery Capacit tions nvelope stem y G05 / Package 3 - Laborator Component 2: Strengthening Request for Quota Single Stage - One E IDA / 68330 Post Open - National 0.00 Signed 2023-01-31 2023-03-16 2023-08-03 y equipment Health Care Delivery Capacit tions nvelope y G06 / Package 4 - Pathology Component 2: Strengthening Request for Quota Single Stage - One E IDA / 68330 Post Open - National 0.00 Signed 2023-01-31 2023-03-16 2023-08-03 equipment Health Care Delivery Capacit tions nvelope y G07 / Package 15 - Anestesi Component 2: Strengthening Request for Quota Single Stage - One E IDA / 68330 Post Open - National 0.00 Signed 2023-01-31 2023-03-16 2023-08-03 a surgical equipment Health Care Delivery Capacit tions nvelope y G08 / Package 16 - IT equip Component 2: Strengthening Request for Quota Single Stage - One E IDA / 68330 Post Open - National 0.00 Signed 2023-01-31 2023-03-16 2023-08-03 ment Health Care Delivery Capacit tions nvelope y G09 / Autoclave for sterilizat Component 2: Strengthening Single Stage - One E IDA / 68330 Post Request for Bids Open - National 0.00 Signed 2023-01-18 2022-12-27 2023-01-18 2023-02-03 2023-02-03 2023-03-05 2023-04-03 2023-04-09 2023-08-17 ion of medical waste Health Care Delivery Capacit nvelope y MN-MOH-332105-GO-RFQ / P Component 2: Strengthening Request for Quota Single Stage - One E ackage 5 - Automatic tablet / IDA / 68330 Health Care Delivery Capacit Post Open - National 0.00 Canceled 2022-12-20 2022-12-20 2023-02-24 2023-07-04 tions nvelope capsule machine y MN-MOH-332107-GO-RFQ / P Component 2: Strengthening Request for Quota Single Stage - One E IDA / 68330 Post Open - National 0.00 Canceled 2022-12-20 2022-12-20 2023-02-24 2023-07-04 ackage 6 - Neurology equip Health Care Delivery Capacit tions nvelope ment y G04 / Package 2 - Intensive Component 2: Strengthening Request for Quota Single Stage - One E IDA / 68330 Post Open - National 0.00 Canceled 2023-01-31 2023-03-16 2023-08-03 care equipment Health Care Delivery Capacit tions nvelope y G10 / Supply and Delivery of Component 2: Strengthening Request for Quota Single Stage - One E Under Imple IDA / 68330 Post Open - National 0.00 2023-04-20 2023-06-20 2024-01-26 ambulance cars Health Care Delivery Capacit tions nvelope mentation y G11 / Package 5 - Automatic Component 2: Strengthening Request for Quota Single Stage - One E Under Imple IDA / 68330 Post Open - National 0.00 2023-04-20 2023-06-17 2023-10-15 tablet / capsule machine Health Care Delivery Capacit tions nvelope mentation y G12 / Package 6 - Neurolog Component 2: Strengthening Request for Quota Single Stage - One E Under Imple IDA / 68330 Post Open - National 0.00 2023-04-20 2023-06-17 2023-09-20 y equipment Health Care Delivery Capacit tions nvelope mentation y G13 / Package 2 - Intensive Component 2: Strengthening Request for Quota Single Stage - One E Under Imple IDA / 68330 Post Open - National 0.00 2023-04-20 2023-07-01 2023-07-12 care equipment Health Care Delivery Capacit tions nvelope mentation y NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MN-MOH-208524-NC-DIR / 2. Component 2: Strengthening Customs Clearance and Local IDA / 65940 Health Care Delivery Capacit Post Direct Selection Direct 82,089.59 Signed 2020-12-10 2020-11-18 2020-12-13 2020-12-18 2020-12-22 2020-12-25 2021-12-22 Freight Forwarding Services y CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 3: Implementati MN-MOH-180428-CS-CQS / 3 Consultant Qualifi Pending Impleme IDA / 65940 on management and Monito Post Open - National 0.00 2020-09-28 2020-10-05 2020-10-19 2020-10-19 2020-11-02 2020-12-02 .7. Project baseline survey cation Selection ntation ring and Evaluation MN-MOH-181206-CS-CQS / 1 .1.3. Prepare and publish the Component 1: Emergency C Consultant Qualifi Information, Education, and IDA / 65940 OVID-19 Prevention and Res Post Limited 0.00 Canceled 2020-09-27 2020-10-04 2020-10-11 2020-10-23 2020-11-22 cation Selection Communication (IEC) materia ponse ls, TV promo, and info graphi c content Page 6 MN-MOH-181213-CS-CQS / 1 .1.8. Compose song and vide Component 1: Emergency C o movie against the COVID-1 Consultant Qualifi IDA / 65940 OVID-19 Prevention and Res Post Limited 0.00 Canceled 2020-09-28 2020-10-05 2020-10-12 2020-10-26 2020-11-25 9 infection under the "Let us cation Selection ponse prevent infection together!" slogan and broadcast widely MN-MOH-181218-CS-CQS / 1 .1.16. Produce a video conte Component 1: Emergency C Consultant Qualifi nt to support social morale in IDA / 65940 OVID-19 Prevention and Res Post Limited 0.00 Canceled 2020-09-13 2020-09-20 2020-09-27 2020-10-09 2020-11-08 cation Selection cooperation with Mongolian S ponse tate Academic Drama Theate r MN-MOH-181210-CS-CQS / 1 Component 1: Emergency C .1.7. Prepare educational TV Consultant Qualifi IDA / 65940 OVID-19 Prevention and Res Post Limited 0.00 Canceled 2020-10-04 2020-10-11 2020-10-18 2020-10-30 2020-11-29 programme with scientific an cation Selection ponse d cognitive content MN-MOH-181211-CS-CQS / 1 Component 1: Emergency C Consultant Qualifi .1.9. Produce a documentary IDA / 65940 OVID-19 Prevention and Res Post Limited 0.00 Canceled 2020-10-04 2020-10-11 2020-10-18 2020-10-30 2020-11-29 cation Selection film on COVID-19 infection ponse MN-MOH-181220-CS-CQS / 1 Component 1: Emergency C .2.3. Conduct the coronaviru Consultant Qualifi IDA / 65940 OVID-19 Prevention and Res Post Limited 0.00 Canceled 2020-09-13 2020-09-20 2020-09-27 2020-10-09 2020-11-08 s infection survey (CIS) recor cation Selection ponse ds and incident monitoring re search MN-MOH-181222-CS-CQS / 1 Component 1: Emergency C .2.4. Develop mathematical Consultant Qualifi IDA / 65940 OVID-19 Prevention and Res Post Limited 0.00 Canceled 2020-09-27 2020-10-04 2020-10-11 2020-10-23 2020-11-22 modelling of the coronavirus cation Selection ponse infection, influenza, and seas onal influenza MN-MOH-181204-CS-CQS / 1 Component 1: Emergency C .1.2. Develop and implement Consultant Qualifi IDA / 65940 OVID-19 Prevention and Res Post Limited 0.00 Canceled 2020-09-07 2020-09-14 2020-09-21 2020-10-03 2020-11-02 the communications strategy cation Selection ponse during the coronavirus outbr eak MN-MOH-181215-CS-CQS / 1 Component 1: Emergency C Consultant Qualifi .1.11. Produce TV talk show s IDA / 65940 OVID-19 Prevention and Res Post Limited 0.00 Canceled 2020-09-27 2020-10-04 2020-10-11 2020-10-23 2020-11-22 cation Selection eries dedicated to youth ponse MN-MOH-181216-CS-CQS / 1 Component 1: Emergency C Consultant Qualifi .1.12. Obtain COVID-19 dedic IDA / 65940 OVID-19 Prevention and Res Post Limited 0.00 Canceled 2020-09-13 2020-09-20 2020-09-27 2020-10-09 2020-11-08 cation Selection ated air-time on TV channel ponse MN-MOH-181208-CS-CQS / 1 Component 1: Emergency C .1.5. Develop and distribute t Consultant Qualifi IDA / 65940 OVID-19 Prevention and Res Post Limited 0.00 Canceled 2020-09-28 2020-10-05 2020-10-12 2020-10-24 2020-11-23 he Information, Education, an cation Selection ponse d Communication (IEC) mate rials MN-MOH-181203-CS-CQS / 1 Component 1: Emergency C Consultant Qualifi .1.17. Produce song and vide IDA / 65940 OVID-19 Prevention and Res Post Limited 0.00 Canceled 2020-09-28 2020-10-05 2020-10-12 2020-10-24 2020-11-23 cation Selection o clip to promote work of doc ponse tors MN-MOH-181209-CS-CQS / 1 Component 1: Emergency C Consultant Qualifi .1.6. Disseminate information IDA / 65940 OVID-19 Prevention and Res Post Limited 0.00 Canceled 2020-09-28 2020-10-05 2020-10-12 2020-10-26 2020-11-25 cation Selection via public media outlets and ponse social media MN-MOH-181217-CS-CQS / 1 Component 1: Emergency C Consultant Qualifi .1.13. Place banner on the ho IDA / 65940 OVID-19 Prevention and Res Post Limited 0.00 Canceled 2020-09-07 2020-09-14 2020-09-21 2020-10-05 2020-11-04 cation Selection me page of the cable TVs ponse INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Actual Amount Invitation to Identifie Draft Negotiated Cont Component Review Type Method Contract Type Process Status Teams of Reference Signed Contract Contract Completion Description o. h (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MN-MOH-168717-CS-INDV / Component 3: Implementati Individual Consult 3.1. Medical Equipment Speci IDA / 65940 on management and Monito Post Direct 22,294.66 Signed 2020-04-20 2020-05-19 2020-04-30 2020-06-03 2020-05-03 2020-08-05 2020-05-10 2020-08-06 2022-05-31 ant Selection alist/Engineer ring and Evaluation MN-MOH-168720-CS-INDV / Component 3: Implementati Individual Consult 3.2. Risk Communication and IDA / 65940 on management and Monito Post Direct 0.00 Canceled 2020-04-20 2020-05-19 2020-04-30 2020-06-03 2020-05-03 2020-05-10 2022-05-31 ant Selection Community Involvement Spe ring and Evaluation cialist Component 3: Implementati MN-MOH-168721-CS-INDV / Individual Consult IDA / 65940 on management and Monito Post Direct 0.00 Canceled 2020-04-20 2020-05-19 2020-04-30 2020-06-03 2020-05-03 2020-05-10 2022-05-31 3.3. Procurement Specialist ant Selection ring and Evaluation MN-MOH-168722-CS-INDV / Component 3: Implementati Individual Consult 3.4. Environmental and Occu IDA / 65940 on management and Monito Post Direct 0.00 Canceled 2020-04-20 2020-05-19 2020-04-30 2020-06-03 2020-05-03 2020-05-10 2022-05-31 ant Selection pational Health Specialist ring and Evaluation MN-MOH-185586-CS-INDV / Component 3: Implementati Individual Consult 3.2. Risk Communication and IDA / 65940 on management and Monito Post Open 0.00 Canceled 2020-08-06 2020-05-29 2020-09-03 2020-09-17 2020-10-01 2022-05-31 ant Selection Community Involvement Spe ring and Evaluation cialist Component 3: Implementati MN-MOH-185589-CS-INDV / Individual Consult IDA / 65940 on management and Monito Post Open 0.00 Canceled 2020-08-06 2020-05-23 2020-09-03 2020-09-17 2020-10-01 2022-05-31 3.3. Procurement Specialist ant Selection ring and Evaluation MN-MOH-185590-CS-INDV / Component 3: Implementati Individual Consult 3.4. Environmental and Occu IDA / 65940 on management and Monito Post Open 18,924.22 Signed 2020-08-06 2020-06-03 2020-09-03 2020-10-05 2020-09-17 2021-03-01 2020-10-01 2021-02-06 2022-05-31 ant Selection pational Health Specialist ring and Evaluation MN-MOH-185586-CS-INDV-2 Component 3: Implementati Individual Consult / 3.2. Risk Communication an IDA / 65940 on management and Monito Post Open 33,491.81 Completed 2020-10-16 2020-05-29 2020-11-13 2020-12-14 2020-11-20 2021-03-09 2020-12-01 2021-10-08 2022-10-31 2022-01-01 ant Selection d Community Involvement S ring and Evaluation pecialist Component 3: Implementati MN-MOH-185589-CS-INDV-2 Individual Consult IDA / 65940 on management and Monito Post 0.00 Canceled 2020-10-20 2020-05-26 2020-11-17 2020-11-24 2020-12-08 2022-10-31 / 3.3. Procurement specialist ant Selection ring and Evaluation Component 3: Implementati MN-MOH-218295-CS-CDS / 3 IDA / 65940 on management and Monito Prior Direct Selection Direct 0.00 Canceled 2021-02-10 2021-02-09 2021-02-20 2021-04-26 2021-10-23 .3. Procurement Specialist ring and Evaluation Component 3: Implementati MN-MOH-218862-CS-INDV / Individual Consult IDA / 65940 on management and Monito Prior Direct 14,642.68 Completed 2021-02-10 2021-02-10 2021-02-20 2021-02-11 2021-03-13 2021-03-30 2021-04-17 2021-08-25 2021-10-14 2022-01-01 3.3 Procurement specialist ant Selection ring and Evaluation Page 7 MN-MOH-232717-CS-INDV / Component 3: Implementati Individual Consult 3.6.Monitoring and Evaluatio IDA / 68330 on management and Monito Post Open 7,318.65 Completed 2021-05-17 2021-05-11 2021-06-19 2021-06-02 2021-06-26 2021-06-02 2021-07-17 2021-09-09 2023-03-31 2022-01-12 ant Selection n Specialist ring and Evaluation MN-MOH-232716-CS-INDV / Component 3: Implementati Individual Consult 3.5. Contract management s IDA / 68330 on management and Monito Post Open 7,824.72 Completed 2021-05-17 2021-05-11 2021-06-19 2021-06-07 2021-06-26 2021-05-28 2021-07-17 2021-06-08 2023-03-31 2021-12-01 ant Selection pecialist (local consultant) ring and Evaluation Component 3: Implementati MN-MOH-232722-CS-INDV / Individual Consult IDA / 68330 on management and Monito Post Open 0.00 Canceled 2021-05-17 2021-05-11 2021-06-19 2021-06-26 2021-07-17 2023-03-31 3.7. Vaccine Specialist ant Selection ring and Evaluation MN-MOH-180421-CS-CDS / 1 .3.13. Organize on-job traini Component 1: Emergency C ng among the traditional me IDA / 65940 OVID-19 Prevention and Res Post Direct Selection Direct 0.00 Canceled 2020-10-05 2020-10-12 2020-11-07 2020-12-05 dicine doctors, on epidemiolo ponse gy prevention and monitorin g measures MN-MOH-180424-CS-CDS / 1 .3.21. Organize clinical waste Component 1: Emergency C management specifically, bo IDA / 65940 OVID-19 Prevention and Res Post Direct Selection Direct 0.00 Canceled 2020-10-05 2020-10-12 2020-11-07 2020-12-05 dy transportation, storage, a ponse nd sanitation, and cremation training MN-MOH-180423-CS-CDS / 1 .3.15. Organize training on e Component 1: Emergency C arly detection of the complic IDA / 65940 OVID-19 Prevention and Res Post Direct Selection Direct 0.00 Canceled 2020-10-05 2020-10-12 2020-11-07 2020-12-05 ations of coronavirus infectio ponse n and mandatory treatment procedures for doctors of int ernal medicine MN-MOH-180422-CS-CDS / 1 .3.14. Strengthen laboratory operations and services capa Component 1: Emergency C bility by developing the bio- IDA / 65940 OVID-19 Prevention and Res Post Direct Selection Direct 0.00 Canceled 2020-10-05 2020-10-12 2020-11-07 2020-12-05 hazardous material and bio s ponse ubstances transportation reg ulation, on job training of CO VID-19 virus analysis, develo p manuals for specimen colle ction MN-MOH-247236-CS-CDS / 1 Component 1: Emergency C .1.1.A.1. COVID19 PREVENTI Under Implement IDA / 65940 OVID-19 Prevention and Res Post Direct Selection Direct 0.00 2021-08-13 2021-07-06 2021-08-27 2021-09-24 2022-12-17 ON AND TRANING ACTIVITIES ation ponse BY NATIONAL CENTER FOR P UBLIC HEALTH MN-MOH-247238-CS-CDS / 1 Component 1: Emergency C .2.2.A.3. COVID19 PREVENTI Under Implement IDA / 65940 OVID-19 Prevention and Res Post Direct Selection Direct 0.00 2021-08-09 2021-05-31 2021-08-23 2021-09-13 2022-12-31 ON TRANING ACTIVITIES BY C ation ponse ENTER FOR HEALTH DEVELO PMENT MN-MOH-247239-CS-CDS / 1 Component 1: Emergency C .2.1.B.5. COVID19 VACCINE E Under Implement IDA / 68330 OVID-19 Prevention and Res Post Direct Selection Direct 0.00 2021-08-09 2021-07-24 2021-08-30 2021-10-04 2022-07-31 FFICIENCY STUDY BY MONGO ation ponse LIAN NATIONAL UNIVERSITY OF MEDICAL SCIENCES MN-MOH-232722-CS-INDV-2 Component 1: Emergency C Individual Consult / 1.1.1.B.15. PUBLIC HEALTH IDA / 68330 OVID-19 Prevention and Res Post Open 0.00 Canceled 2021-09-22 2021-09-21 2021-10-18 2021-10-23 2021-11-06 2022-11-06 ant Selection LOCAL CONSULTANT ponse MN-MOH-254589-CS-INDV / Component 1: Emergency C Individual Consult 1.3.3.A.3. FACILITY HEALTH A IDA / 65940 OVID-19 Prevention and Res Post Open 14,030.11 Signed 2021-09-22 2021-09-22 2021-10-25 2022-05-05 2021-10-30 2022-05-05 2021-11-13 2022-05-25 2022-11-13 ant Selection ND SAFETY LOCAL CONSULT ponse ANT MN-MOH-272427-CS-INDV / Component 1: Emergency C Individual Consult IDA / 65940 Post Direct 0.00 Canceled 2022-01-10 2022-02-11 2022-01-16 2022-01-19 2022-02-11 2022-08-10 1.1.1.B.15. Public health loca OVID-19 Prevention and Res ant Selection l consultant ponse Component 3: Implementati MN-MOH-272428-CS-INDV / Individual Consult IDA / 65940 on management and Monito Prior Open 0.00 Canceled 2022-01-17 2022-03-07 2022-03-28 2022-05-02 2022-10-29 procurement specialist ant Selection ring and Evaluation Component 3: Implementati MN-MOH-272668-CS-INDV / Individual Consult IDA / 65940 on management and Monito Prior Limited 0.00 Canceled 2022-01-17 2022-01-17 2022-01-22 2022-01-21 2022-02-12 2022-02-06 2022-03-19 2022-09-15 procurement specialist ant Selection ring and Evaluation MN-MOH-272670-CS-INDV / Component 3: Implementati Individual Consult Monitoring and Evaluation Sp IDA / 65940 on management and Monito Post Open 9,775.72 Terminated 2022-01-29 2022-01-04 2022-02-14 2022-01-21 2022-02-15 2022-03-18 2022-03-16 2022-03-28 2023-04-30 ant Selection ecialist ring and Evaluation Component 3: Implementati MN-MOH-272671-CS-INDV / Individual Consult IDA / 65940 on management and Monito Post Open 9,877.93 Terminated 2022-01-29 2022-01-04 2022-02-14 2022-01-21 2022-02-15 2022-01-01 2022-03-16 2022-04-30 2023-04-30 Project Assistant ant Selection ring and Evaluation MN-MOH-272672-CS-INDV / Component 3: Implementati Individual Consult Risk Communication and Co IDA / 65940 on management and Monito Post Open 10,248.84 Terminated 2022-01-29 2022-01-04 2022-02-14 2022-01-21 2022-02-15 2022-02-01 2022-03-16 2022-04-30 2023-04-30 ant Selection mmunity Engagement Specia ring and Evaluation list MN-MOH-272674-CS-INDV / Component 3: Implementati Individual Consult Financial Management Speci IDA / 65940 on management and Monito Prior Open 0.00 Canceled 2022-03-28 2022-04-06 2022-04-14 2022-04-15 2022-04-18 2022-10-15 ant Selection alist ring and Evaluation MN-MOH-292429-CS-INDV / Component 1: Emergency C Individual Consult Project Coordinator for Comp IDA / 68330 OVID-19 Prevention and Res Post Open 10,317.12 Terminated 2022-04-28 2022-04-28 2022-05-18 2022-06-08 2022-05-23 2022-06-08 2022-05-30 2022-06-22 2023-02-24 ant Selection onent 1 / National Training S ponse pecialist MN-MOH-292853-CS-INDV / Component 1: Emergency C Individual Consult IDA / 68330 Post Open 0.00 Canceled 2022-04-28 2022-05-05 2022-05-18 2022-06-27 2022-05-20 2022-05-24 2023-02-18 PUBLIC HEALTH LOCAL CONS OVID-19 Prevention and Res ant Selection ULTANT ponse MN-MOH-294627-CS-INDV / Component 3: Implementati Individual Consult Financial Management Speci IDA / 65940 on management and Monito Post Open 0.00 Signed 2022-05-11 2022-05-11 2022-06-03 2022-06-17 2022-06-06 2022-06-17 2022-06-10 2023-03-31 ant Selection alist ring and Evaluation Component 3: Implementati MN-MOH-272669-CS-INDV / Individual Consult IDA / 65940 on management and Monito Post Direct 0.00 Canceled 2022-01-29 2022-02-07 2022-02-13 2021-11-25 2022-02-14 2022-02-16 2023-04-30 Project Coordinator ant Selection ring and Evaluation MN-MOH-288910-CS-INDV / Component 2: Strengthening Individual Consult NATIONAL MEDICAL EQUIPME IDA / 65940 Health Care Delivery Capacit Post Open 0.00 Canceled 2022-04-15 2022-04-15 2022-05-03 2022-05-05 2022-05-07 2023-01-17 ant Selection NT SPECIALIST/ENGINEERING y CONSULTANT Component 3: Implementati MN-MOH-272673-CS-INDV / Individual Consult IDA / 65940 on management and Monito Post Open 0.00 Canceled 2022-03-22 2022-03-23 2022-04-09 2022-05-31 2022-04-10 2022-04-14 2022-10-11 Procurement Specialist ant Selection ring and Evaluation Page 8 MN-MOH-313589-CS-INDV / Component 1: Emergency C Individual Consult Project Coordinator for Comp IDA / 68330 OVID-19 Prevention and Res Post Open - National 11,467.88 Signed 2022-09-02 2022-09-01 2022-09-15 2022-09-01 2022-09-15 2022-09-02 2022-09-15 2022-09-06 2023-03-31 ant Selection onent 1 / National Training S ponse pecialist MN-MOH-288910-CS-INDV-2 Component 2: Strengthening Individual Consult / National Medical Equipment IDA / 68330 Health Care Delivery Capacit Post Open - National 10,820.64 Signed 2022-09-02 2022-09-01 2022-09-17 2022-09-02 2022-09-18 2022-09-02 2022-09-19 2022-09-15 2023-03-31 ant Selection Specialist / Engineering Cons y ultant MN-MOH-315239-CS-CDS / C REATING AN ENABLING ENVI Component 1: Emergency C RONMENT FOR ONE HEALTH Pending Impleme IDA / 68330 OVID-19 Prevention and Res Post Direct Selection Direct - National 0.00 2022-09-11 2022-09-13 2022-09-18 2023-08-14 CONCEPT IN MONGOLIA SING ntation ponse LE SOURCE CONTRACT WITH NATIONAL CENTER FOR ZOO NOTIC DISEASES Component 3: Implementati MN-MOH-317985-CS-INDV / Individual Consult Under Implement IDA / 68330 on management and Monito Post Open - National 0.00 2022-09-27 2022-10-10 2022-10-15 2022-10-17 2022-10-19 2023-03-31 Project Driver / Courier ant Selection ation ring and Evaluation MN-MOH-325523-CS-INDV / Component 1: Emergency C RISK COMMUNICATION AND Individual Consult Under Implement IBRD / 90820 OVID-19 Prevention and Res Post Open - National 0.00 2022-11-08 2022-12-26 2022-11-28 2022-11-30 2022-12-04 2023-12-31 COMMUNITY ENGAGEMENT S ant Selection ation ponse PECIALIST OF THE PROJECT I MPLEMENTATION UNIT MN-MOH-332130-CS-INDV / Component 3: Implementati Individual Consult Under Implement NATIONAL MONITORING AND IBRD / 90820 on management and Monito Post Open - National 0.00 2022-12-20 2022-12-20 2023-01-23 2023-01-26 2023-01-26 2023-09-10 ant Selection ation EVALUATION CONSULTANT ring and Evaluation MN-MOH-333001-CS-INDV / Component 3: Implementati Individual Consult PIU Monitoring and Evaluatio IBRD / 90820 on management and Monito Post Open - National 0.00 Canceled 2022-12-21 2023-01-20 2023-01-25 2023-01-27 2023-12-31 ant Selection n Specsialist ring and Evaluation CS02 / CREATING AN ENABLI Component 1: Emergency C NG ENVIRONMENT FOR ONE IDA / 68330 OVID-19 Prevention and Res Post Direct Selection Direct - National 0.00 Under Review 2023-05-31 2023-05-24 2023-06-02 2023-06-06 2023-12-31 HEALTH CONCEPT IN MONGO ponse LIA CS03 / IMPROVING HEALTHC Component 1: Emergency C Under Implement IDA / 68330 Post Direct Selection Direct - National 0.00 2023-05-31 2023-05-24 2023-06-04 2023-06-13 2024-02-08 ARE WASTE MANAGEMENT OVID-19 Prevention and Res ation ponse Page 9 PROCUREMENT PLAN (Textual Part) Project information: Ethiopia, Desert Locust Response Project, P173702 Project Implementation agency: Ministry of Agriculture, Ethiopia Date of the Procurement Plan: April 6, 2012 Period covered by this Procurement Plan: April 2020 to March 2021 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016, revised November 2017 and August 2018) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the Procurement Directives of the Federal and Regional Governments of Ethiopia, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. For national open competitive procurement the following requirement apply: a. open advertising of the procurement opportunity at the national level; b. the procurement is open to eligible firms from any country; c. the request for bids/request for proposals document shall require that Bidders/Proposers submitting Bids/Proposals present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights; d. Procurement Documents include provisions, as agreed with the Bank, intended to adequately mitigate against environmental, social (including sexual exploitation and abuse and gender-based violence), health and safety (“ESHS”) risks and impacts; e. contracts with an appropriate allocation of responsibilities, risks, and liabilities; f. publication of contract award information; g. rights for the Bank to review procurement documentation and activities; h. an effective complaints mechanism; and i. maintenance of records of the Procurement Process. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. Not Applicable Procurement of Secondhand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables Not Applicable For national open competitive procurement the following requirement apply: a. open advertising of the procurement opportunity at the national level; b. the procurement is open to eligible firms from any country; c. the request for bids/request for proposals document shall require that Bidders/Proposers submitting Bids/Proposals present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights; d. Procurement Documents include provisions, as agreed with the Bank, intended to adequately mitigate against environmental, social (including sexual exploitation and abuse and gender-based violence), health and safety (“ESHS”) risks and impacts; e. contracts with an appropriate allocation of responsibilities, risks, and liabilities; f. publication of contract award information; g. rights for the Bank to review procurement documentation and activities; h. an effective complaints mechanism; and i. maintenance of records of the Procurement Process. cable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Not Applicable Goods: [is not applicable/is applicable for those contracts identified in the Procurement Plan tables]; Works: [is not applicable/is applicable for those contracts identified in the Procurement Plan tables] Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations is Applicable. Other Relevant Procurement Information. Since the project is an emergency response project the provisions of Procurement in Situations of Urgent Need of Assistance shall apply. PROCUREMENT Eastern and Southern Africa : Emergency Locust Response Program PLAN General Information Country: Eastern and Southern Africa 2022-10-20 Bank’s Approval Date of the Original Procurement Plan: 2023-06-01 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P173702 GPN Date: 2020-12-03 Project Name: Emergency Locust Response Program Loan / Credit No: IDA / 66480 Isiolo County Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned KE-ISIOLO COUNTY-320739- Request for Quota CW-RFQ / Rehabilitation of La Livelihoods Protection and R Request for Quota Single Stage - One E Pending Imp 2023-02-1 IDA / 66480 Post Limited tions (Non Bank-S 82,680.00 0.00 2022-10-21 2022-11-18 ffe Borehole at Sericho Ward. ehabilitation tions nvelope lementation 6 PD) GPS coordinates: N0489997, E0155618 GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual KE-ISIOLO COUNTY-325132- GO-RFQ / Procurement of em ergency livestock supplemen Livelihoods Protection and R Request for Quota Single Stage - One E Pending Impl tary feeds in Sericho Ward, I IDA / 66480 Post Limited 87,053.90 0.00 2022-11-21 2022-12-16 2023-03-16 ehabilitation tions nvelope ementation siolo County. Coordinates: Latitude 1.12942 N 1*7'45.92 4 longitude 39.11108 E 38*6'3 KE-ISIOLO COUNTY-03/2022/ 9.894 2023-GO-RFQ / Procurement of Assorted certified Livelihoods Protection and R Pending Impl IDA / 66480 Post Direct Selection Direct - National 36,710.72 0.00 2023-05-18 2023-05-23 2023-06-13 2023-09-11 Seeds for farmers - County w ehabilitation ementation ide- Garbatulla, Merti and Isiolo s ub Counties. NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual KE-ISIOLO COUNTY-325126- GO-RFQ / Water trucking serv Livelihoods Protection and R Request for Quota Single Stage - One E Pending Impl IDA / 66480 Post Limited 81,766.14 0.00 2022-11-21 2022-12-23 2023-03-23 ices to alleviate human and li ehabilitation tions nvelope ementation vestock suffering as a result of drought. CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 1 Cher Marc, Nous avons examiné le projet de plan de passation des marchés pour le projet susmentionné, soumis à la Banque le 2019/09/01. Sur la base des informations fournies, la Banque n'a pas d'objection à ce que les activités marquées «cleared» dans le plan de passation des marchés (PPM). Après la publication du PPM, vous pouvez commencer la mise en œuvre de ces activités. Les PPMs traités par le système seront automatiquement publiés sur le site Web externe de la Banque mondiale dès réception de la déclaration de non-objection de la Banque et seront archivés sous le numéro de version indiqué ci-dessus. Bien cordialement + merci pour vos efforts, Jan Friedrich Kappen Spécialiste Principal en Energie PROCUREMENT Madagascar : Madagascar - Least-Cost Electricity Access Development Project - LEAD PLAN General Information Country: Madagascar 2019-11-07 Bank’s Approval Date of the Original Procurement Plan: 2023-06-02 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P163870 GPN Date: Project Name: Madagascar - Least-Cost Electricity Access Development Project - LEAD Loan / Credit No: IDA / 63730 JIRAMA LEAD Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MG-JIRAMA LEAD-241233-G O-RFB / V0121C Densification des réseaux de distribution - Open - Internationa Single Stage - One E IDA / 63730 Grid Electrification Post Request for Bids 1,000,000.00 0.00 Signed 2021-06-28 2021-07-27 2021-07-03 2021-09-09 2021-08-14 2021-09-10 2021-09-13 2022-01-27 2021-10-18 2022-02-15 Fourniture des équipements l nvelope pour l’installation de 5000 br anchements sociaux (sans le s compteurs) MG-JIRAMA LEAD-241294-G O-RFB / V0321C Densification Open - Internationa Single Stage - One E et extension des réseaux de IDA / 63730 Grid Electrification Post Request for Bids 800,000.00 0.00 Canceled 2021-06-28 2021-08-19 2021-07-03 2021-08-19 2021-08-14 2021-10-04 2021-09-13 2022-02-08 2021-10-18 2022-02-15 l nvelope distribution : Fourniture maté riel de sécurité, appareil de mesure et outillage MG-JIRAMA LEAD-241299-G Single Stage - One E O-RFB / V0421C Fourniture d IDA / 63730 Grid Electrification Post Request for Bids Open - National 200,000.00 259,803.16 Signed 2021-06-28 2021-08-19 2021-07-03 2021-08-19 2021-08-14 2021-09-20 2021-09-13 2022-01-28 2021-10-18 2022-03-22 2022-02-15 nvelope e matériels informatiques MG-JIRAMA LEAD-244494-G O-RFQ / I0121A - Fournitures Technical Assistance and Pro Request for Quota Single Stage - One E IDA / 63730 Post Open - National 20,000.00 0.00 Signed 2021-07-24 2021-08-20 2021-09-18 2022-03-17 d'équipements informatiques ject Implementation Support tions nvelope pour l'unité de gestion du pro jet MG-JIRAMA LEAD-170532-G O-DIR / I0120C - Achat de 07 Technical Assistance and Pro licences du logiciel Power Fa IDA / 63730 Post Direct Selection Direct 20,000.00 0.00 Canceled 2020-06-02 2020-09-01 2020-06-07 2019-09-23 2020-07-12 2021-01-08 ject Implementation Support ctory avec contrat de mainte nance inclu pour une durée d e 03 ans MG-JIRAMA LEAD-244507-G O-RFB / A0121C - Fourniture de matériels roulants réparti e en 5 lots: Lot n°1: 20 Véhicules pick up Technical Assistance and Pro Open - Internationa Single Stage - One E IDA / 63730 Prior Request for Bids 2,800,000.00 0.00 Canceled 2021-09-14 2021-09-19 2021-10-31 2021-11-21 2021-12-26 2022-06-24 4x4 double cabine; ject Implementation Support l nvelope Lot n°2: 40 Camionnettes H D65 4X2 (plateau ridelle); Lot n°3: 5 Camions grues; Lot n°4: 2 Camions Plateaux ; Lot n°5: 7 Camions Nacelles, MG-JIRAMA LEAD-241292-G O-RFB / D0322C - Fourniture Open - Internationa Single Stage - One E IDA / 63730 Grid Electrification Post Request for Bids 1,840,000.00 1,556,789.98 Signed 2022-03-14 2022-03-24 2022-03-15 2022-04-05 2022-04-29 2022-05-16 2022-05-11 2022-05-16 2022-06-10 2022-08-05 2023-01-06 des kits de matériels pour 20 l nvelope 000 branchements sociaux MG-JIRAMA LEAD-283165-G O-RFB / D0222C - Fourniture Open - Internationa Single Stage - One E de 195 000 compteurs prép IDA / 63730 Grid Electrification Prior Request for Bids 6,640,000.00 0.00 Signed 2022-03-16 2022-06-21 2022-03-17 2022-07-18 2022-05-02 2022-09-01 2022-05-14 2023-01-12 2022-06-13 2022-12-10 l nvelope aiement et équipements de t est du laboratoire (en 2 lots) MG-JIRAMA LEAD-283176-G O-RFB / A0121C - Fourniture des moyens roulants en 4 lot Open - Internationa Single Stage - One E IDA / 63730 Grid Electrification Prior Request for Bids 2,500,000.00 0.00 Signed 2022-03-17 2022-06-24 2022-03-18 2022-07-18 2022-05-02 2022-08-23 2022-05-14 2023-01-12 2022-06-17 2023-06-02 2022-12-14 2023-06-02 s : 13 Véhicules 4x4 cabines, l nvelope 50 Camionnettes, 6 camions grues et 5 Camions plateaux MG-JIRAMA LEAD-283181-G Open - Internationa Single Stage - One E O-RFB / D0822C - Fourniture IDA / 63730 Grid Electrification Post Request for Bids 1,650,000.00 0.00 Signed 2022-03-18 2022-03-31 2022-03-19 2022-04-06 2022-05-03 2022-05-23 2022-05-11 2022-07-07 2022-06-13 2023-02-08 l nvelope des matériels de réseau élect rique MG-JIRAMA LEAD-241307-G O-RFB / D0122C (EPC) - Four Open - Internationa Single Stage - One E niture et installation en 6 Lot IDA / 63730 Grid Electrification Prior Request for Bids 20,060,000.00 0.00 Signed 2021-07-26 2022-07-06 2021-07-31 2023-01-10 2021-09-11 2022-10-27 2021-10-11 2023-02-21 2021-11-15 2023-06-01 2022-05-14 l nvelope s des kits de matériels pour 170 000 branchements socia ux en deux tranches MG-JIRAMA LEAD-283321-G O-RFB / D0722C (EPC) - Four niture et installation en 6 Lot Open - Internationa Single Stage - One E IDA / 63730 Grid Electrification Prior Request for Bids 23,200,000.00 0.00 Signed 2022-03-24 2022-07-06 2022-03-25 2022-07-24 2022-05-09 2022-10-28 2022-05-24 2023-04-02 2022-06-28 2023-06-23 2023-02-23 s des matériels de réseaux é l nvelope lectriques, poteaux et access oires pour 400 activités d'ext ension MG-JIRAMA LEAD-287326-G Under Imple O-DIR / D1322C FOURNITURE IDA / 63730 Grid Electrification Post Direct Selection Direct 700,000.00 0.00 2022-04-01 2022-06-03 2022-04-16 2022-06-05 2022-10-03 mentation DE 5000 COMPTEURS COMM UNICANTS MG-JIRAMA LEAD-283291-G Single Stage - One E Under Imple O-RFB / D0522C - Fourniture IDA / 63730 Grid Electrification Post Request for Bids Open - National 180,000.00 0.00 2022-03-23 2022-04-26 2022-03-24 2022-05-06 2022-03-28 2022-06-10 2022-04-09 2022-05-14 2022-11-10 nvelope mentation des matériaux de constructio n en 8 Lots MG-JIRAMA LEAD-283289-G Single Stage - One E O-RFB / D0422C - Fourniture IDA / 63730 Grid Electrification Post Request for Bids Open - National 630,000.00 0.00 Canceled 2022-03-21 2022-04-21 2022-03-22 2022-04-27 2022-05-06 2022-06-14 2022-05-18 2022-06-21 2022-12-18 nvelope de 5094 poteaux béton en u n seul Lot Page 1 MG-JIRAMA LEAD-305932-G O-RFB / D0522C - Fourniture Single Stage - One E Under Imple IDA / 63730 Grid Electrification Post Request for Bids Open - National 180,000.00 0.00 2022-08-09 2022-08-25 2022-08-14 2022-09-02 2022-09-28 2022-10-14 2022-10-10 2022-11-01 2023-04-30 des matériaux de constructio nvelope mentation n en 8 Lots (Relance) MG-JIRAMA LEAD-305937-G Request for Quota Single Stage - One E Pending Impl O-RFQ / P0122C - Services de IDA / 63730 Grid Electrification Post Open - National 1,000.00 0.00 2022-08-14 2022-10-09 2023-04-07 tions nvelope ementation 20 impressions de plans au f ormat A0 MG-JIRAMA LEAD-319194-G Single Stage - One E Under Imple O-RFB / D0422C - Fourniture IDA / 63730 Grid Electrification Post Request for Bids Open - National 1,900,000.00 0.00 2022-04-15 2022-04-26 2022-04-20 2022-10-16 2022-06-01 2022-06-14 2022-07-01 2022-10-17 2022-08-05 2023-02-01 nvelope mentation de 5094 poteaux béton en u n seul Lot MG-JIRAMA LEAD-340594-G O-RFB / D0922C Fourniture d Open - Internationa Single Stage - One E Pending Impl e 5000 Compteurs intelligent IDA / 63730 Grid Electrification Post Request for Bids 1,950,000.00 0.00 2023-04-03 2023-04-12 2023-05-27 2023-06-26 2023-07-31 2024-01-27 l nvelope ementation s et Acquisition et Mise en Se rvice d'une plateforme pour t ous Compteurs Intelligents MG-JIRAMA LEAD-350802-G O-RFB / D0123C Fourniture, I nstallation et mise en service Open - Internationa Single Stage - One E Pending Impl IDA / 63730 Grid Electrification Post Request for Bids 1,950,000.00 0.00 2023-06-21 2023-06-26 2023-08-07 2023-08-28 2023-10-02 2024-04-19 de raccordement électrique d l nvelope ementation es CSB et Centres Hospitalier s à partir des réseaux de la JI RAMA MG-JIRAMA LEAD-365709-G O-RFB / A0123C Acquisition d Single Stage - One E Pending Impl IDA / 63730 Grid Electrification Post Request for Bids Open - National 300,000.00 0.00 2023-06-14 2023-06-19 2023-07-31 2023-08-30 2023-10-04 2024-01-02 es moyens roulants : 2 voitur nvelope ementation es 4 x 4 et 50 motos MG-JIRAMA LEAD-365773-G O-RFB / V0123C Acquisition d Single Stage - One E Pending Impl IDA / 63730 Grid Electrification Post Request for Bids Open - National 150,000.00 0.00 2023-06-21 2023-06-26 2023-07-26 2023-08-10 2023-09-09 2023-11-08 es équipements informatique nvelope ementation s ordinateurs et imprimantes MG-JIRAMA LEAD-366144-G O-RFQ / V0223C ACQUISITIO Request for Quota Single Stage - One E Pending Impl IDA / 63730 Grid Electrification Post Open - National 50,000.00 0.00 2023-06-24 2023-09-10 2023-11-09 N DES MATERIELS DE BUREA tions nvelope ementation UX POUR LE SERVICE BU MG-JIRAMA LEAD-365712-G Single Stage - One E Pending Impl O-RFB / D0223C Acquisition d IDA / 63730 Grid Electrification Post Request for Bids Open - National 300,000.00 0.00 2023-06-14 2023-06-19 2023-07-31 2023-08-30 2023-10-04 2024-01-02 nvelope ementation es équipements de sécurité e t outillages NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MG-JIRAMA LEAD-283295-NC Request for Quota Single Stage - One E -RFQ / D0622C - Recrutemen IDA / 63730 Grid Electrification Post Open - National 70,000.00 0.00 Canceled 2022-03-15 2022-04-19 2022-05-09 2023-01-04 tions nvelope t de main d’œuvre temporair e en 8 Lots MG-JIRAMA LEAD-305925-NC -RFQ / D0622C - Recrutemen Request for Quota Single Stage - One E Under Imple IDA / 63730 Grid Electrification Post Open - National 120,000.00 0.00 2022-07-30 2022-09-02 2022-09-14 2023-05-12 t de main d’œuvre temporair tions nvelope mentation e en 8 Lots (Relance) MG-JIRAMA LEAD-318061-NC -DIR / SERVICE DE MIGRATIO Technical Assistance and Pro Direct - Internation Under Imple IDA / 63730 Post Direct Selection 10,000.00 0.00 2022-09-26 2022-09-28 2022-10-01 2022-09-28 2022-10-08 2022-10-22 N DE LA PLATEFORME ZTE A ject Implementation Support al mentation LA NOUVELLE ARCHITECTUR E SIG/SIG JIRAMA MG-JIRAMA LEAD-356618-NC -RFQ / X0423C Location d'un Pending Impl IDA / 63730 Grid Electrification Post Direct Selection Direct - National 75,000.00 0.00 2023-06-14 2023-06-19 2023-07-01 2024-07-31 bureau et équipement de bur ementation eau pour le PIÙ PAGOSE et L EAD JIRAMA CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MG-JIRAMA LEAD-140248-CS -INDV / ASSISTANCE A LA MA Technical Assistance and Pro Quality And Cost- Open - Internationa IDA / 63730 Prior 4,000,000.00 4,794,525.54 Signed 2019-10-14 2019-11-11 2019-10-15 2019-12-04 2019-10-31 2020-06-03 2019-12-16 2020-08-14 2019-12-24 2020-10-01 2020-01-08 2021-02-14 2020-01-28 2021-03-16 2022-01-27 ITRISE D'OUVRAGE (Etude, C ject Implementation Support Based Selection l ontrôle et Supervision) (X011 9C) MG-JIRAMA LEAD-208711-CS -QCBS / ÉTUDES ENVIRONNE Technical Assistance and Pro Quality And Cost- Open - Internationa MENTALES ET SOCIALES REQ IDA / 63730 Post 220,000.00 224,274.66 Signed 2020-12-17 2020-12-16 2020-12-24 2021-05-21 2021-01-28 2021-06-22 2021-02-25 2021-07-22 2021-03-11 2021-08-09 2021-03-25 2021-08-26 2021-04-22 2021-10-14 2021-10-19 ject Implementation Support Based Selection l UISES POUR LES ACTIVITÉS D E LA SOUS- COMPOSANTE 1b DU PROJET MG-JIRAMA LEAD-232195-CS Consultant Qualifi -CQS / Service d'un Consulta IDA / 63730 Grid Electrification Post Limited 100,000.00 436,000.00 Signed 2021-04-29 2021-05-19 2021-05-13 2021-06-24 2021-06-12 2022-02-03 2021-07-17 2022-02-23 2021-12-24 cation Selection nt pour Compteur en cascad e V0121C MG-JIRAMA LEAD-298026-CS -CQS / X0122C - OPTIMA BUS INESS & BRANCHEMENTS MO Technical Assistance and Pro Consultant Qualifi Under Implement IDA / 63730 Post Limited 239,000.00 0.00 2022-06-09 2022-08-25 2022-06-16 2022-07-16 2022-08-13 2023-01-21 RA : Recrutement d’une Age ject Implementation Support cation Selection ation nce de communication pour l a mise en œuvre du Plan de Communication MG-JIRAMA LEAD-350822-CS Technical Assistance and Pro Consultant Qualifi Open - Internationa Pending Impleme -CQS / X0123C Service de Co IDA / 63730 Post 100,000.00 0.00 2023-03-24 2023-04-14 2023-05-13 2023-05-28 2023-06-21 2023-08-20 ject Implementation Support cation Selection l ntation nsultants pour l'Audit de MAT SELAKA (JdE) MG-JIRAMA LEAD-366138-CS -CQS / X0523C CABINET DE P ROFESSIONNEL DES COMPTA BLES CHARGE D'ASSURER LA Consultant Qualifi Pending Impleme IDA / 63730 Grid Electrification Post Open - National 350,000.00 0.00 2023-06-21 2023-07-12 2023-08-02 2023-08-09 2023-08-23 2024-09-19 GESTION FINANCIERE cation Selection ntation POUR LES PROJETS PAGOSE ET LEAD JUSQU'A LA CLOTUR E DES PROJETS Page 2 INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MG-JIRAMA LEAD-182997-CS -CDS / SERVICE DE CONSULT ANT INDIVIDUEL POUR ASSIS Technical Assistance and Pro Individual Consult IDA / 63730 Post Limited 15,000.00 0.00 Canceled 2020-08-07 2020-08-12 2020-09-02 2020-10-07 2021-04-05 TER LA DIRECTION GÉNÉRAL ject Implementation Support ant Selection E DE LA JIRAMA POUR LES FO NCTIONS AU POSTE DU CONT RÔLEUR DE GESTION 1 MG-JIRAMA LEAD-182998-CS -CDS / SERVICE DE CONSULT ANT INDIVIDUEL POUR ASSIS Technical Assistance and Pro Individual Consult IDA / 63730 Post Limited 15,000.00 0.00 Canceled 2020-08-07 2020-08-12 2020-09-02 2020-10-07 2021-04-05 TER LA DIRECTION GÉNÉRAL ject Implementation Support ant Selection E DE LA JIRAMA POUR LES FO NCTIONS AU POSTE DU CONT RÔLEUR DE GESTION 2 MG-JIRAMA LEAD-246789-CS -INDV / X0321C - Recruteme Technical Assistance and Pro Individual Consult nt d'un Spécialiste en Gestio IDA / 63730 Post Open 17,500.00 16,677.23 Signed 2021-09-24 2021-10-18 2021-10-28 2022-01-28 2021-11-04 2022-05-17 2021-11-26 2022-05-31 2022-11-26 ject Implementation Support ant Selection n Financière pour appuyer l'é quipe de l'AGEX de la JIRAMA MG-JIRAMA LEAD-258678-CS -INDV / X0521C - Recruteme Technical Assistance and Pro Individual Consult Under Implement nt d'un Responsable de la Pa IDA / 63730 Prior Direct 17,000.00 0.00 2021-10-19 2021-10-21 2021-10-25 2021-11-17 2022-05-16 ject Implementation Support ant Selection ation ssation des Marchés pour le projet LEAD et PAGOSE MG-JIRAMA LEAD-295777-CS -INDV / Consultant individuel Technical Assistance and Pro Individual Consult Under Implement IDA / 63730 Post Direct 12,000.00 0.00 2022-05-23 2022-03-26 2022-06-02 2022-06-23 2022-07-28 2023-07-28 Comptable de Projets PAGOS ject Implementation Support ant Selection ation E et LEAD au sein de l'AGEX de la JIRAMA MG-JIRAMA LEAD-276238-CS -INDV / Coordonnateur de Pro Technical Assistance and Pro Individual Consult IDA / 63730 Post Direct 30,200.00 0.00 Canceled 2022-02-09 2022-02-11 2022-02-13 2022-02-20 2023-02-20 jets PAGOSE et LEAD au sein ject Implementation Support ant Selection de l'AGEX de la JIRAMA MG-JIRAMA LEAD-307906-CS -INDV / X0322C - Service de Technical Assistance and Pro Individual Consult Under Implement IDA / 63730 Post Direct - National 12,750.00 0.00 2022-08-09 2022-08-09 2022-08-19 2022-09-09 2022-10-14 2023-04-12 Consultant Individuel pour la ject Implementation Support ant Selection ation Coordination des Projets PAG OSE et LEAD MG-JIRAMA LEAD-304435-CS Technical Assistance and Pro Individual Consult Under Implement -INDV / X0422C - Recruteme IDA / 63730 Post Open - National 8,000.00 0.00 2022-08-09 2022-08-18 2022-09-27 2022-10-18 2022-11-22 2024-06-28 ject Implementation Support ant Selection ation nt d'un assistant en passatio n de marché MG-JIRAMA LEAD-304440-CS -INDV / X0522C - Recruteme Technical Assistance and Pro Individual Consult Under Implement IDA / 63730 Post Open - National 17,000.00 0.00 2022-08-09 2022-08-25 2022-09-27 2022-10-18 2022-11-22 2024-06-28 nt d'un consultant Responsa ject Implementation Support ant Selection ation ble de Passation de Marchés MG-JIRAMA LEAD-340591-CS -INDV / X0622C Service de C Technical Assistance and Pro Individual Consult Pending Impleme IDA / 63730 Post Direct - National 40,000.00 0.00 2023-02-10 2023-02-14 2023-02-17 2023-02-28 2024-07-01 onsultant individuel Coordon ject Implementation Support ant Selection ntation nateur de Projets PAGOSE et LEAD MG-JIRAMA LEAD-350775-CS -CDS / X0323C Service de Co Technical Assistance and Pro Pending Impleme nsultant individuel pour Com IDA / 63730 Post Direct Selection Direct - National 17,000.00 0.00 2023-03-20 2023-03-21 2023-03-22 2024-06-30 ject Implementation Support ntation ptable des projets PAGOSE et LEAD au sein de l'AGEX JIRA MA de ces projets MG-JIRAMA LEAD-367136-CS -INDV / X0623C SERVICE DE Individual Consult IDA / 63730 Grid Electrification Prior Open - National 15,000.00 0.00 Under Review 2023-06-30 2023-08-12 2023-08-19 2023-09-09 2024-07-31 CONSULTANT INDIVIDUEL D' ant Selection ASSISTANT EN PASSATION D E MARCHE Page 3 SUMMARY O F PROCUREMENT PLAN Project Preparation Advancement (PPA) Project information: Harmonizing and Improving Statistics in West Africa Project -P169265 Project Implementation agency: Liberia Institute of Statistics and Geo- Information Services (LISGIS) Date of the Procurement Plan: February 3, 2020 Period covered by this Procurement Plan: 3rd February to 31st July 2020 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 1, 2016), revised in November 2017, and August 2018 (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the Public Procurement and Concessions Act, 2010 of the Republic of Liberia, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations. In accordance with paragraph 5.3 of the Procurement Regulations, the request for bids/request for proposals document shall require that Bidders/Proposers submitting Bids/Proposals present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights. The form of the Letter of Acceptance is attached in Appendix 1. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. Not Applicable Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables. Not Applicable. Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: Not Applicable for those contracts identified in the Procurement Plan tables; Works: Not Applicable for those contracts identified in the Procurement Plan tables. Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations: Not Applicable. Other Relevant Procurement Information: - (a). Prior Procurement Arrangements: The Procurement Arrangements as indicated in the below table and within the thresholds indicated in the below tables will be used. The thresholds for the Bank’s prior review requirements are also provided in the table below: Table: Thresholds*, Procurement Arrangements, and Prior Review (The table below depicts the Thresholds and Procurement Methods to be used under the Regional Project for Statistics Thresholds*, Procurement Methods, and Prior Review Contract (C) Value Expenditure Procurement Contracts Subject to No Threshold* [eq. Category Method Prior Review /[eq. US$] USD] All contracts at or above USD Open Competition 5,000,000 are subject to International Market 1 Works C ≥ 5,000,000 Approach and Direct international advertising and the use of the Bank’s SPDs (or other Contracting documents agreed with the Contract (C) Value Expenditure Procurement Contracts Subject to No Threshold* [eq. Category Method Prior Review /[eq. US$] USD] Bank). Open Competition National Market 200,000 < C < 5,000,000 None Approach C ≤ 200,000 RfQ None All contracts at or above USD Open Competition 500,000 are subject to International Market international advertising and the C ≥ 500,000 Approach and Direct use of the Bank’s SPDs (or other Goods, IT and Contracting documents agreed with the 2 non-consulting Bank). services Open Competition 100,000 < C < 500,000 National Market None Approach C ≤ 100,000 RfQ None All contracts at or above USD 100,000 are subject to for international advertising and the C < 100,000 Consulting Services use of the Bank’s SPDs (or other National documents agreed with the shortlist for Bank). 3 selection of All contracts at or above USD consultant firms for 200,000 are subject to Engineering and international advertising and the C ≤ 200,000 Construction use of the Bank’s SPDs (or other Supervision documents agreed with the Bank). Selection of All values ≥ 100,000 4 Individual All Approaches consultants Training, This line activity is not subject to Workshops, Based on approved Procurement Review However, 5 Study Tours All Values Annual Work Plan & each of the activities will be Budgets (AWPB) by TTL cleared with the TTL prior to its implementation. (Special procurement arrangements like direct contracting, use of SOEs, UN Agencies, third party monitors, local NGOs, Force Account, servants needs, results based arrangements. It is not expected that there will be need for prequalification in the procurement arrangements under this Regional Project *These thresholds are for the purposes of the initial procurement plan for the PPA and for first 18 months. The thresholds will be revised periodically based on re- assessment of risks. All contracts not subject to prior review will be post-reviewed. Prequalification. Not expected for the packages of works/goods packages in the procurement plan. Proposed Procedures for CDD Components: Not Applicable Reference to (if any) Project Operational/Procurement Manual: The LISGIS Project Management Team will prepare Procurement manuals. The Procurement Plan will also form part of the Project Implementation Manual. Any Other Special Procurement Arrangements: None Procurement Packages/PLAN with Procurement Arrangements and Time Schedule: as per the Table below: b) PROCUREMENT PLAN Works There are no works under the Project Preparation Advance Goods and Non-Consulting Services 1 2 3 4 5 6 7 8 9 Ref. Contract Estimated Procurement Prequ Nation Revie Expecte Expecte Comment No. (Description) Cost Method alifica al w d bid d s US$ tion Prefer by opening Contrac (yes/n ence Bank date t o) (yes/n (Prior Signatu o) / Post) re Date 1 Procurement of 4 12,100 laptops, 3 No. all- in-1 printers, Limited, RFQ No No Post 28 Feb 4 Mar office desks, a 20 20 projector, metal filing cabinet, and stationery and supplies for project management Consultancy Services 1 2 3 4 5 6 7 8 9 Ref. Description of Estimate Selection Review Expecte Expected Expected Comments No. Assignment d Method/ by Bank d date Contract Completi Cost in Arrangem (Prior / of Signatur on US$ ent Post) proposal e Date submissi Date on 1. Recruitment of a Consultant to draft and validate 10,000 INDV Post 16 Mar 10 Apr 23 Apr ToR to be curricula of the 20 20 20 submitted to IDA Statistics degree & for Review and No CEST Program at Objection. the UL 2. Recruitment of a ToR, performance Financial evaluation, draft Management contract and Officer for Project DS Prior 10 Feb 21 Feb 31 Aug minutes of Management 20 20 20 contract negotiation to be submitted to IDA for Review and No 15,600 Objection. 3. ToR, performance evaluation, draft Recruitment of a contract and Procurement DS Prior 10 Feb 21 Feb 31 Aug minutes of Specialist for 20 20 20 contract Project 18,000 negotiation to be Management submitted to IDA for Review and No Objection. Training and Workshop (Training & Workshop activities are subject to TTL clearance). Estimat Estimated Expected Ref. Training, workshop and ed Cost Duration Training/workshop No. study tours in (Days) Date (US$) Conduct of validation 54,000 workshop and TOT for the GP Feb. 20 to March 1. on the design of 13 2020 questionnaires and enumeration training manual Workshop for cartographic 150,000 Feb. 24 to March 2. field staff training 16 2020 Workshop for enumeration 113,900 3. mapping training April 15, 2020 Study Tours to regional 32,000 countries for first-hand experience on regional March to April 4. harmonization of data 2020 collection, management and communication Workshops on current 50,000 administrative data across 5. April to July 2020 MACs and LISGIS regional offices Workshop to strengthen and 35,000 6. develop institutional capacity April to July 2020 of NSO Workshops for steering 40,000 7. committee on Administrative April to July 2020 Data Workshop for Project 10,000 Steering/Technical 8. Committees for annual work February 2020 plan preparation, review and validation GENERAL NOTES 1. Training and capacity building: Training workshops (including training material and support), conference attendance and study tours, will be carried out based on approved annual training and allied activities plan by the TTL. The beneficiaries, after the training, will be requested to submit a brief report indicating what skills have been acquired and how these skills will contribute to enhance their performance and contribute to the attainment of the Project’s development objective. 2. Operational Costs: These are expenditures incurred by the Recipient to finance: (i) communication technology (including, without limitation, internet and telephone; (ii) per diem and travel expenses of the operational staff performing their responsibilities under the Project; (iii) fuel and vehicle maintenance; (iv) maintenance of equipment; (v) photocopies and publications; (viii) bank commissions; and (ix) utilities and office supplies as defined in the FA. Appendix 1 Letter of Acceptance of the World Bank’s Anti-Corruption Guidelines and Sanctions Framework Date: Invitation of Bids/Proposals No.__________ To: ___________________________________________________________________________ We, along with our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not) consultants and personnel, acknowledge and agree to abide by the World Bank’s policy regarding Fraud and Corruption (corrupt, fraudulent, collusive, coercive, and obstructive practices), as set out and defined in the World Bank’s Anti-Corruption Guidelines1 in connection with the procurement and execution of the contract (in case of award), including any amendments thereto. We declare and warrant that we, along our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not), consultants and personnel, , are not subject to, and are not controlled by any entity or individual that is subject to, a temporary suspension, early temporary suspension, or debarment imposed by a member of the World Bank Group, including, inter alia, a cross-debarment imposed by the World Bank Group as agreed with other international financial institutions (including multilateral development banks), or through the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement. Further, we are not ineligible under the laws or official regulations of [Insert name of Employer as per bidding document] or pursuant to a decision of the United Nations Security Council. We confirm our understanding of the consequences of not complying with the World Bank’s Anti-Corruption Guidelines, which may include the following: a. rejection of our Proposal/Bid for award of contract; 1Guidelines on Preventing and Combating Fraud and Corruption in Projects Financed by International Bank for Reconstruction and Development Loans and the International Development Agency Credits and Grants, dated October 15, 2006, and revised in January 2011 and July 2016, as they may be revised from time to time. b. in the case of award, termination of the contract, without prejudice to any other remedy for breach of contract; and c. sanctions, pursuant to the Bank’s Anti-corruption Guidelines and in accordance with its prevailing sanctions policies and procedures as set forth in the Bank’s Sanctions Framework. This may include a public declaration of ineligibility, either indefinitely or for a stated period of time, (i) to be awarded or otherwise benefit from a Bank-financed contract, financially or in any other manner;2 (ii) to be a nominated3 sub-contractor, consultant, manufacturer or supplier, or service provider of an otherwise eligible firm being awarded a Bank-financed contract; and (iii) to receive the proceeds of any loan made by the Bank or otherwise to participate further in the preparation or implementation of any Bank-financed project. We understand that we may be declared ineligible as set out above upon: a. completion of World Bank Group sanctions proceedings according to its prevailing sanctions procedures; b. cross-debarment as agreed with other international financial institutions (including multilateral development banks); c. the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement; or d. temporary suspension or early temporary suspension in connection with an ongoing World Bank Group sanctions proceeding. For avoidance of doubt, the foregoing effects of ineligibility do not extend to a sanctioned firm’s or individual’s execution of its ongoing Bank-financed contracts (or its ongoing sub-agreements under such contracts) that are not the subject of a material modification, as determined by the Bank. We shall permit, and shall cause our sub-contractors, sub-consultants, agents (whether declared or not), personnel, consultants, service providers or suppliers, to 2 For the avoidance of doubt, a sanctioned party’s ineligibility to be awarded a contract shall include, without limitation, (i) applying for pre-qualification, expressing interest in a consultancy, and bidding, either directly or as a nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider, in respect of such contract, and (ii) entering into an addendum or amendment introducing a material modification to any existing contract. 3 A nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider (different names are used depending on the particular bidding document) is one which has been: (i) included by the bidder in its pre-qualification application or bid because it brings specific and critical experience and know-how that allow the bidder to meet the qualification requirements for the particular bid; or (ii) appointed by the Borrower. permit the Bank to inspect4 all accounts, records, and other documents relating to the procurement process and/or contract execution (in the case of award), and to have them audited by auditors appointed by the Bank. We agree to preserve all accounts, records, and other documents (whether in hard copy or electronic format) related to the procurement and execution of the contract. Name of the Bidder/Consultant: Name of the person duly authorized to sign the Bid/Proposal on behalf of the Bidder/Consultant: Title of the person signing the Letter: 4 Inspections in this context are usually investigative (i.e., forensic) in nature: they involve fact-finding activities undertaken by the Bank or persons appointed by the Bank to address specific matters related to investigations/audits, such as evaluating the veracity of an allegation of possible Fraud and Corruption, through the appropriate mechanisms. Such activity includes but is not limited to accessing and examining a firm's or individual's financial records and information, and making copies thereof as relevant; accessing and examining any other documents, data, and information (whether in hard copy or electronic format) deemed relevant for the investigation/audit, and making copies thereof as relevant; interviewing staff and other relevant individuals; performing physical inspections and site visits; and obtaining third-party verification of information. PROCUREMENT Western and Central Africa : Harmonizing and Improving Statistics in West Africa PLAN General Information Country: Western and Central Africa 2021-02-15 Bank’s Approval Date of the Original Procurement Plan: 2023-06-07 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P169265 GPN Date: 2021-05-19 Project Name: Harmonizing and Improving Statistics in West Africa Loan / Credit No: IDA / 65750, IDA / 65770 National Institute of Statistics - Cote d'Ivoire Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Regional component: Harmo CI-INS COTE D'IVOIRE-21420 nization, Data Collection, Qu 7-CW-RFB / Câblage réseau ( Single Stage - One E 2021-11-1 IDA / 65750 ality Improvement, Dissemin Post Request for Bids Open - National 268,000.00 0.00 Canceled 2021-01-25 2021-01-30 2021-03-13 2021-04-12 2021-05-17 câblage informatique, couran nvelope 3 ation and Use of Core Social t ondulé et revêtement mur) and Economic Statistics CI-INS COTE D'IVOIRE-21419 Regional component: Harmo National Procure 9-CW-RFQ / Travaux et amén nization, Data Collection, Qu ment Document - agement (Acquisition et insta Request for Quota Single Stage - One E 2022-12-0 IDA / 65750 ality Improvement, Dissemin Post Limited 1 Envelope proce 110,000.00 0.00 Canceled 2022-04-11 2022-06-06 llation de Split, Revêtement tions nvelope 3 ation and Use of Core Social ss (Non Bank-SPD murs, cloisonnement, extensi and Economic Statistics ) on du câblage électrique et r éseau, travaux divers...) CI-INS COTE D'IVOIRE-27353 Country-Specific Component Request for Quota 9-CW-RFQ / Travaux de réha : Improving and modernizing Request for Quota Single Stage - One E Under Imple 2022-10-2 IDA / 65770 Post Limited tions (Non Bank-S 100,000.00 0.00 2022-07-05 2022-08-30 bilitation et d'aménagement physical and statistical infra tions nvelope mentation 9 PD) du bâtiment siège de l'UCP structure CI-INS COTE D'IVOIRE-27354 Country-Specific Component Request for Quota 0-CW-RFQ / Travaux de réha : Improving and modernizing Request for Quota Single Stage - One E Pending Imp 2022-10-1 IDA / 65770 Post Limited tions (Non Bank-S 100,000.00 0.00 2022-08-09 2022-10-04 bilitation et d'aménagement physical and statistical infra tions nvelope lementation 0 PD) du bâtiment pour le Centre d structure e cartographie CI-INS COTE D'IVOIRE-30845 Country-Specific Component Request for Quota 1-CW-RFQ / Travaux de clois : Improving and modernizing Request for Quota Single Stage - One E tions - Small Work Pending Imp 2022-12-2 IDA / 65770 Post Limited 180,000.00 0.00 2022-09-19 2022-11-14 onnement et d'aménagemen physical and statistical infra tions nvelope s (Emergency) SP lementation 9 t des nouveaux bureaux de l' structure D -Competitive INS CI-INS COTE D'IVOIRE-30845 3-CW-RFQ / Travaux de fourn Country-Specific Component Request for Quota iture et installation de bâtim : Improving and modernizing Request for Quota Single Stage - One E tions - Small Work Pending Imp 2022-11-2 ent préfabriqués pour le site IDA / 65770 Post Limited 180,000.00 0.00 2022-09-17 2022-10-07 physical and statistical infra tions nvelope s (Emergency) SP lementation 1 de relocalisation de l'INS (infi structure D -Competitive rmerie, local imprimerie et lo cal de maintenance informati que etc.) CI-INS COTE D'IVOIRE-30845 Request for Quota 6-CW-RFQ / Travaux d'install Project Management and Mo Request for Quota Single Stage - One E Pending Imp 2022-12-2 IDA / 65770 Post Limited tions (Non Bank-S 110,000.00 0.00 2022-09-18 2022-11-13 ation de bureau en préfabriq nitoring and Evaluation tions nvelope lementation 8 PD) ués dans les locaux de l'UCP- PHAS CI-INS COTE D'IVOIRE-35012 Country-Specific Component 1-CW-RFQ / Travaux de mise Request for Quota : Improving and modernizing Request for Quota Single Stage - One E Pending Imp 2023-12-3 en place de bâtiments préfab IDA / 65770 Post Limited tions (Non Bank-S 190,000.00 0.00 2023-05-09 2023-07-04 physical and statistical infra tions nvelope lementation 1 riqués et aménagement du c PD) structure entre d’appel de l’INS CI-INS COTE D'IVOIRE-35198 Regional component: Harmo Request for Quota 6-CW-RFQ / Travaux d'aména nization, Data Collection, Qu Request for Quota Single Stage - One E tions - Small Work Pending Imp 2023-12-1 gement des bureaux du Rece IDA / 65770 ality Improvement, Dissemin Post Limited 150,000.00 0.00 2023-04-25 2023-06-20 tions nvelope s (Emergency) SP lementation 7 nsement Général des Entrepr ation and Use of Core Social D -Competitive ises et Etablissements de Côt and Economic Statistics e d'Ivoire (RGEE-CI) GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CI-INS COTE D'IVOIRE-27353 5-GO-RFQ / Fourniture et inst Project Management and Mo Request for Quota Single Stage - One E Under Imple allation d'équipements infor IDA / 65770 Post Limited 90,000.00 0.00 2022-02-07 2022-06-10 2022-04-04 2022-10-01 nitoring and Evaluation tions nvelope mentation matiques (Ordinateurs, serve urs, imprimantes etc.) pour l' UCP-PHAS CI-INS COTE D'IVOIRE-27353 Country-Specific Component 6-GO-RFQ / Fourniture et inst : Improving and modernizing Request for Quota Single Stage - One E Pending Impl allation de matériels de bure IDA / 65770 Post Limited 90,000.00 0.00 2022-03-01 2022-04-26 2022-10-23 physical and statistical infra tions nvelope ementation au (Copieurs, vidéos projecte structure urs etc.) pour l'UCP et le cent re de cartographie CI-INS COTE D'IVOIRE-27354 Country-Specific Component 4-GO-RFQ / Fourniture et inst : Improving and modernizing Request for Quota Single Stage - One E Pending Impl allation d'un système de visi IDA / 65770 Post Limited 30,000.00 0.00 2022-03-28 2022-05-23 2022-11-19 physical and statistical infra tions nvelope ementation oconférence pour l'UCP-PHAS structure et le centre de cartographie CI-INS COTE D'IVOIRE-27354 5-GO-RFQ / Fourniture et inst Project Management and Mo Request for Quota Single Stage - One E Pending Impl IDA / 65770 Post Limited 30,000.00 0.00 2022-04-18 2022-06-13 2022-12-10 allation de GPS pour les véhi nitoring and Evaluation tions nvelope ementation cules acquis dans le cadre du Projet PHAS CI-INS COTE D'IVOIRE-21423 Regional component: Harmo 2-GO-RFQ / Acquisition d’ouv nization, Data Collection, Qu Request for Quota Single Stage - One E Under Imple rages pour renouveler le fon IDA / 65750 ality Improvement, Dissemin Post Limited 12,000.00 0.00 2022-04-06 2022-06-01 2022-11-28 tions nvelope mentation ds documentaire de la bibliot ation and Use of Core Social hèque de l’ENSEA and Economic Statistics CI-INS COTE D'IVOIRE-27353 3-GO-RFQ / Acquisition de Fo Project Management and Mo Request for Quota Single Stage - One E Pending Impl urnitures de bureau (rame, ki IDA / 65770 Post Limited 60,000.00 0.00 2022-04-05 2022-05-31 2023-05-31 nitoring and Evaluation tions nvelope ementation ts, stylo…) pour l'UCP et dive rs ateliers et enquêtes Page 1 CI-INS COTE D'IVOIRE-27352 Country-Specific Component 1-GO-RFQ / Fourniture et inst : Improving and modernizing Request for Quota Single Stage - One E Pending Impl allation de matériels informat IDA / 65770 Post Limited 75,000.00 0.00 2022-04-17 2022-06-12 2022-07-27 physical and statistical infra tions nvelope ementation iques pour le fonctionnement structure du centre de cartographie CI-INS COTE D'IVOIRE-27352 Country-Specific Component Request for Quota Single Stage - One E Pending Impl 2-GO-RFQ / Fourniture et inst IDA / 65770 : Improving and modernizing Post Limited 70,000.00 0.00 2022-03-29 2022-05-24 2022-06-23 tions nvelope ementation allation de mobiliers de bure physical and statistical infra au pour l'UCP structure CI-INS COTE D'IVOIRE-21421 Regional component: Harmo 1-GO-RFB / Acquisition de LO nization, Data Collection, Qu Single Stage - One E GICIELS (VISUAL BASIC 2019 IDA / 65750 ality Improvement, Dissemin Post Request for Bids Open - National 783,484.00 0.00 Canceled 2021-02-25 2021-03-02 2021-04-13 2021-05-13 2021-06-17 2021-12-14 nvelope Entreprise, MS SQLSERVER 2 ation and Use of Core Social 019, STATA 16/PM 32, IBM SP and Economic Statistics SS 26 et anti virus) Regional component: Harmo CI-INS COTE D'IVOIRE-21423 nization, Data Collection, Qu 0-GO-RFQ / Acquisition de Ph Request for Quota Single Stage - One E IDA / 65750 ality Improvement, Dissemin Post Limited 49,000.00 0.00 Canceled 2021-01-27 2021-03-24 2021-09-20 otocopieurs de grande capaci tions nvelope ation and Use of Core Social té and Economic Statistics CI-INS COTE D'IVOIRE-21422 Regional component: Harmo 7-GO-RFB / Acquisition d’équi nization, Data Collection, Qu Single Stage - One E pements (serveurs physiques IDA / 65750 ality Improvement, Dissemin Post Request for Bids Open - National 221,930.00 0.00 Canceled 2021-02-22 2021-02-27 2021-04-10 2021-05-10 2021-06-14 2021-12-11 nvelope , disques de sauvegardes, ap ation and Use of Core Social plications, etc.) and Economic Statistics Regional component: Harmo CI-INS COTE D'IVOIRE-21421 nization, Data Collection, Qu 3-GO-RFB / Acquisition de mo Single Stage - One E IDA / 65750 ality Improvement, Dissemin Post Request for Bids Open - National 279,800.00 0.00 Canceled 2021-02-18 2021-02-23 2021-04-06 2021-05-06 2021-06-10 2021-12-07 biliers de bureau pour l'Unité nvelope ation and Use of Core Social de Coordination du Projet and Economic Statistics CI-INS COTE D'IVOIRE-21422 Regional component: Harmo 2-GO-RFB / Acquisition de Fo nization, Data Collection, Qu Single Stage - One E urnitures de bureau (rame, ki IDA / 65750 ality Improvement, Dissemin Post Request for Bids Open - National 139,326.00 0.00 Canceled 2021-02-26 2021-03-03 2021-04-14 2021-05-14 2021-06-18 2021-12-15 nvelope ts, stylo…), pour le fonctionn ation and Use of Core Social ement de l'UCP et la collecte and Economic Statistics des données Regional component: Harmo CI-INS COTE D'IVOIRE-21422 nization, Data Collection, Qu 4-GO-RFB / Acquisition de co Single Stage - One E IDA / 65750 ality Improvement, Dissemin Post Request for Bids Open - National 189,502.00 0.00 Canceled 2021-02-24 2021-03-01 2021-04-12 2021-05-12 2021-06-16 2021-12-13 nsommables informatiques ( nvelope ation and Use of Core Social encre, cartouches, etc…) and Economic Statistics CI-INS COTE D'IVOIRE-27351 Project Management and Mo Request for Quota Single Stage - One E Under Imple 8-GO-RFQ / Acquisition de tro IDA / 65770 Post Limited 190,000.00 0.00 2022-05-31 2022-09-06 2022-07-15 2022-08-14 nitoring and Evaluation tions nvelope mentation is (03) Véhicules pour les bes oins de l'UCP CI-INS COTE D'IVOIRE-27352 9-GO-RFB / Fourniture et inst allation de Matériels Informat Country-Specific Component iques, logiciels, consommabl : Improving and modernizing Single Stage - One E Under Imple IDA / 65770 Post Request for Bids Open - National 500,000.00 0.00 2022-05-25 2023-04-28 2022-05-30 2023-05-05 2022-07-11 2022-08-10 2022-09-14 2023-09-14 es et matériels de bureau po physical and statistical infra nvelope mentation ur la réalisation des enquête structure s (Indice d'Accessibilité, refo nte du site web, enquête prix , ENSEA, enquête marge de t ransport) CI-INS COTE D'IVOIRE-27352 5-GO-DIR / Acquisition de Car burant pour la mise en œuvr Project Management and Mo Request for Quota Single Stage - One E IDA / 65770 Post Limited 90,000.00 0.00 Canceled 2022-04-11 2022-06-06 2022-12-03 e des activités du projet (car nitoring and Evaluation tions nvelope burant pour les véhicules de l 'UCP, pour les enquêtes enqu êtes et ateliers) CI-INS COTE D'IVOIRE-29236 Country-Specific Component 4-GO-DIR / Acquisition de car : Improving and modernizing Pending Impl burant pour les véhicules de l IDA / 65770 Post Direct Selection Direct 120,000.00 0.00 2022-05-18 2022-05-23 2022-06-27 2023-06-27 physical and statistical infra ementation 'UCP et pour les ateliers et e structure nquêtes dans le cadre de la mise en œuvre du Projet CI-INS COTE D'IVOIRE-21422 Regional component: Harmo 9-GO-RFB / Acquisition d'ond nization, Data Collection, Qu Single Stage - One E uleurs pour les Directions rég IDA / 65750 ality Improvement, Dissemin Post Request for Bids Open - National 148,400.00 0.00 Canceled 2021-02-26 2021-03-03 2021-04-14 2021-05-14 2021-06-18 2021-12-15 nvelope ionales et le centre de cartog ation and Use of Core Social raphie (20 onduleurs de 6 KV and Economic Statistics A et 1 onduleur de 30 KVA) CI-INS COTE D'IVOIRE-21423 3-GO-RFB / Acquisition de ser Regional component: Harmo veurs de calcul statistique, li nization, Data Collection, Qu Single Stage - One E cences, logiciels service clou IDA / 65750 ality Improvement, Dissemin Post Request for Bids Open - National 255,000.00 0.00 Canceled 2021-03-10 2021-03-15 2021-04-26 2021-05-26 2021-06-30 2021-12-27 nvelope d et équipements informatiq ation and Use of Core Social ues pour améliorer les capaci and Economic Statistics tés de calcul des étudiants et des chercheurs pour l'ENSEA CI-INS COTE D'IVOIRE-24506 Regional component: Harmo 5-GO-RFQ / ACHAT DE FOUR nization, Data Collection, Qu NITURES DE BUREAUX (Kits d Request for Quota Single Stage - One E IDA / 65750 ality Improvement, Dissemin Post Limited 157.00 0.00 Canceled 2021-08-01 2021-09-26 2022-03-25 e formation (cahier 200 page tions nvelope ation and Use of Core Social s, stylo, crayon, gomme, che and Economic Statistics mise cartonnée) et Carton de rames)/EHCVM-NSU Regional component: Harmo CI-INS COTE D'IVOIRE-24508 nization, Data Collection, Qu 5-GO-RFQ / Achat de carbura Request for Quota Single Stage - One E IDA / 65750 ality Improvement, Dissemin Post Limited 3,500.00 0.00 Canceled 2021-08-02 2021-09-27 2022-03-26 nt (Coordonnateur, Equipe te tions nvelope ation and Use of Core Social chnique) /EHCVM-NSU and Economic Statistics Regional component: Harmo CI-INS COTE D'IVOIRE-21423 nization, Data Collection, Qu 1-GO-RFQ / Acquisition de sc Request for Quota Single Stage - One E IDA / 65750 ality Improvement, Dissemin Post Limited 40,000.00 0.00 Canceled 2022-03-28 2022-05-23 2022-11-19 anner professionnel A0 pour l tions nvelope ation and Use of Core Social e Centre de cartographie and Economic Statistics Regional component: Harmo CI-INS COTE D'IVOIRE-24507 nization, Data Collection, Qu 3-GO-RFQ / Achat de cartouc Request for Quota Single Stage - One E IDA / 65750 ality Improvement, Dissemin Post Limited 160.00 0.00 Canceled 2021-08-02 2021-09-27 2022-03-26 he d'encre pour imprimante / tions nvelope ation and Use of Core Social EHCVM NSU and Economic Statistics CI-INS COTE D'IVOIRE-27353 Country-Specific Component 2-GO-RFB / Acquisition de 30 : Improving and modernizing Open - Internationa Single Stage - One E véhicules pour la réalisation IDA / 65770 Post Request for Bids 1,800,000.00 0.00 Signed 2022-06-30 2022-07-07 2022-07-05 2022-11-19 2022-08-16 2022-08-23 2022-09-15 2022-09-06 2022-10-20 2023-04-18 physical and statistical infra l nvelope des enquêtes et recensemen structure ts dans le cadre du Projet Page 2 CI-INS COTE D'IVOIRE-21422 Regional component: Harmo 5-GO-RFQ / Achat de produits nization, Data Collection, Qu Request for Quota Single Stage - One E pharmaceutiques (kits pour l IDA / 65750 ality Improvement, Dissemin Post Limited 11,658.00 0.00 Canceled 2022-04-11 2022-06-06 2022-12-03 tions nvelope es agents de collecte sur le t ation and Use of Core Social errain) and Economic Statistics CI-INS COTE D'IVOIRE-27353 1-GO-RFQ / Fourniture et inst Project Management and Mo Request for Quota Single Stage - One E Pending Impl allation d'un système de vidé IDA / 65770 Post Limited 20,000.00 0.00 2022-07-04 2022-08-29 2022-11-27 nitoring and Evaluation tions nvelope ementation osurveillance et de sécurité p our les locaux de l'UCP-PHAS CI-INS COTE D'IVOIRE-24507 Regional component: Harmo 8-GO-RFQ / Achat de KITS sa nization, Data Collection, Qu nitaires (paquet de gants, Ge Request for Quota Single Stage - One E IDA / 65750 ality Improvement, Dissemin Post Limited 675.00 0.00 Canceled 2021-08-02 2021-09-27 2022-03-26 l hydroalcoolique flacon (30 tions nvelope ation and Use of Core Social ml + 450ml + 30ml), Paquet and Economic Statistics de 50 Cache-nez )/EHCVM-NS U CI-INS COTE D'IVOIRE-24507 5-GO-RFQ / Acquisition de m Regional component: Harmo atériels de terrain ( Pèse alim nization, Data Collection, Qu ent, Peson électronique (affic Request for Quota Single Stage - One E IDA / 65750 ality Improvement, Dissemin Post Limited 5,470.00 0.00 Canceled 2021-08-02 2021-09-27 2022-03-26 hage numérique), Toile de co tions nvelope ation and Use of Core Social uleur blanche (4 mètres), Pile and Economic Statistics s pour pèse aliment, Imperm éables, Imperméables, Sac à dos, chargeur portable)/EHC VM-NSU Regional component: Harmo CI-INS COTE D'IVOIRE-24508 nization, Data Collection, Qu 9-GO-RFQ / Achat de produits Request for Quota Single Stage - One E IDA / 65750 ality Improvement, Dissemin Post Limited 540.00 0.00 Canceled 2021-08-02 2021-09-27 2022-03-26 pharmaceutiques dans le cad tions nvelope ation and Use of Core Social re des EHCVM-NSU and Economic Statistics CI-INS COTE D'IVOIRE-27352 Country-Specific Component 3-GO-RFQ / Fourniture et inst : Improving and modernizing Request for Quota Single Stage - One E Pending Impl IDA / 65770 Post Limited 75,000.00 0.00 2022-07-05 2022-08-30 2022-09-29 allation de mobiliers de bure physical and statistical infra tions nvelope ementation au pour le centre de cartogra structure phie CI-INS COTE D'IVOIRE-27353 Country-Specific Component 7-GO-RFQ / Acquisition de co : Improving and modernizing Request for Quota Single Stage - One E Under Imple nsommables informatiques ( IDA / 65770 Post Limited 60,000.00 0.00 2022-08-01 2022-08-05 2022-09-26 2023-03-25 physical and statistical infra tions nvelope mentation encre, toners etc.) pour le fo structure nctionnement de l'UCP et le c entre de cartographie CI-INS COTE D'IVOIRE-27352 7-GO-RFQ / Acquisition d'équi Country-Specific Component pements techniques, de com : Improving and modernizing Request for Quota Single Stage - One E Pending Impl munication et petit électrom IDA / 65770 Post Limited 50,000.00 0.00 2022-07-04 2022-08-29 2022-10-08 physical and statistical infra tions nvelope ementation énager (coffres-forts, télévise structure urs, téléphones portables, réf rigérateurs, machines à café, relieuses) pour l'UCP CI-INS COTE D'IVOIRE-29806 0-GO-DIR / Acquisition d'un lo Project Management and Mo Pending Impl IDA / 65770 Post Direct Selection Direct 30,000.00 0.00 2022-07-15 2022-07-20 2022-08-24 2023-02-20 giciel de gestion comptable e nitoring and Evaluation ementation t financière (TOMPRO) pour l' UCP-PHAS CI-INS COTE D'IVOIRE-30846 2-GO-RFQ / Fourniture et inst Country-Specific Component allation d'enseigne lumineus : Improving and modernizing Request for Quota Single Stage - One E Pending Impl IDA / 65770 Post Limited 30,000.00 0.00 2022-09-18 2022-11-13 2022-12-13 e, panneau directionnels et s physical and statistical infra tions nvelope ementation ystème de signalétique pour structure les bâtiments et bureaux du Projet CI-INS COTE D'IVOIRE-30846 6-GO-RFQ / Fourniture d'impr Country-Specific Component imés et gadgets promotionne : Improving and modernizing Request for Quota Single Stage - One E Pending Impl ls pour l'unité de coordinatio IDA / 65770 Post Limited 50,000.00 0.00 2022-09-17 2022-11-12 2022-11-22 physical and statistical infra tions nvelope ementation n du projet et la mise en œuv structure re des activités du projet (blo c-notes, tee-shirt, kakémono s, agenda etc.) CI-INS COTE D'IVOIRE-30846 Country-Specific Component 8-GO-RFQ / Acquisition de cin : Improving and modernizing Request for Quota Single Stage - One E Pending Impl quante-six (56) ordinateurs p IDA / 65770 Post Limited 90,000.00 0.00 2022-09-11 2022-11-06 2022-12-21 physical and statistical infra tions nvelope ementation ortables pour les 56 jeunes p structure rofessionnels recrutés dans l e cadre du PHAS CI-INS COTE D'IVOIRE-30847 0-GO-RFQ / Acquisition de m Country-Specific Component atériels informatiques compl : Improving and modernizing Request for Quota Single Stage - One E Pending Impl IDA / 65770 Post Limited 90,000.00 0.00 2022-09-13 2022-11-08 2022-12-23 émentaires pour le centre d'i physical and statistical infra tions nvelope ementation nnovation cartographique, ce structure ntre ce calcul et le centre d'a nalyse économique CI-INS COTE D'IVOIRE-32347 Country-Specific Component 7-GO-DIR / Acquisition d'un lo : Improving and modernizing Pending Impl IDA / 65770 Post Direct Selection Direct - National 40,000.00 0.00 2023-01-31 2023-02-05 2023-03-12 2023-09-08 giciel de type ARCGIS pour l'I physical and statistical infra ementation nstitut National de la Statisti structure que CI-INS COTE D'IVOIRE-32347 Country-Specific Component 9-GO-RFB / Fourniture et Mis : Improving and modernizing Single Stage - One E Under Imple IDA / 65770 Post Request for Bids Open - National 200,000.00 0.00 2023-01-31 2023-01-11 2023-02-05 2023-02-10 2023-03-19 2023-02-23 2023-04-18 2023-03-24 2023-05-23 2023-11-19 e en service d'un centre d'ap physical and statistical infra nvelope mentation pel pour l'Institut National de structure s Statistiques CI-INS COTE D'IVOIRE-33226 Country-Specific Component 2-GO-RFQ / Fourniture de logi : Improving and modernizing Request for Quota Single Stage - One E Pending Impl IDA / 65770 Post Limited 60,000.00 0.00 2023-03-05 2023-04-30 2023-10-27 ciel prioritaire (STATA, SPSS, physical and statistical infra tions nvelope ementation EVIEWS, …) pour l'INS et le structure Centre de Cartographie CI-INS COTE D'IVOIRE-33254 3-GO-RFQ / Acquisition de m Country-Specific Component obiliers de bureau pour l'opér : Improving and modernizing Request for Quota Single Stage - One E Pending Impl IDA / 65770 Post Limited 80,000.00 0.00 2023-09-05 2023-10-31 2024-04-28 ationnalisation du Conseil Na physical and statistical infra tions nvelope ementation tional de la Statistique (CNSt structure at) et l'Autorité Nationale de l a Statistique Publique (ANSP) CI-INS COTE D'IVOIRE-33255 Country-Specific Component 0-GO-RFQ / Acquisition de se : Improving and modernizing Request for Quota Single Stage - One E Pending Impl IDA / 65770 Post Limited 47,000.00 0.00 2023-02-06 2023-04-03 2023-09-30 pt (07) drones + Batterie de physical and statistical infra tions nvelope ementation rechange pour le centre de c structure artographie Page 3 CI-INS COTE D'IVOIRE-33255 Country-Specific Component 1-GO-RFQ / Fourniture de ma : Improving and modernizing Request for Quota Single Stage - One E Pending Impl tériels et mise en place de sa IDA / 65770 Post Limited 90,000.00 0.00 2023-05-01 2023-06-26 2023-12-23 physical and statistical infra tions nvelope ementation lles multimédia dans les dire structure ctions régionales de l'INS CI-INS COTE D'IVOIRE-33255 Country-Specific Component 3-GO-RFB / Acquisition de 67 : Improving and modernizing Single Stage - One E Pending Impl 0 engins à deux roues et cas IDA / 65770 Post Request for Bids Open - National 504,000.00 0.00 2023-03-29 2023-04-03 2023-05-15 2023-06-14 2023-07-19 2024-01-15 physical and statistical infra nvelope ementation ques en appui aux activités d structure e recensement agricole CI-INS COTE D'IVOIRE-33255 Country-Specific Component 7-GO-RFQ / Travaux d'aména : Improving and modernizing Request for Quota Single Stage - One E Pending Impl gement intérieur des locaux IDA / 65770 Post Limited 190,000.00 0.00 2023-01-29 2023-03-26 2023-09-22 physical and statistical infra tions nvelope ementation de l'UC-PHAS (aménagement structure salles de réunion, bureaux, s alles de conférence) etc. CI-INS COTE D'IVOIRE-33257 Country-Specific Component 5-GO-RFQ / Acquisition de Mo : Improving and modernizing Request for Quota Single Stage - One E Pending Impl IDA / 65770 Post Limited 90,000.00 0.00 2023-03-05 2023-04-30 2023-10-27 biliers de Bureau complémen physical and statistical infra tions nvelope ementation taires pour l'UC-PHAS structure CI-INS COTE D'IVOIRE-33252 Country-Specific Component Request for Quota Single Stage - One E Pending Impl 4-GO-RFQ / Acquisition de de IDA / 65770 : Improving and modernizing Post Limited 200,000.00 0.00 2023-05-22 2023-07-17 2024-01-13 tions nvelope ementation ux (02) cars pour l'INS physical and statistical infra structure CI-INS COTE D'IVOIRE-35003 Country-Specific Component 3-GO-RFQ / Acquisition de m : Improving and modernizing Request for Quota Single Stage - One E Pending Impl IDA / 65770 Post Limited 90,000.00 0.00 2023-05-03 2023-06-28 2023-12-25 obiliers de bureau (tables, fa physical and statistical infra tions nvelope ementation uteuils etc.) pour le centre d’ structure appels de l’INS CI-INS COTE D'IVOIRE-35014 Country-Specific Component 3-GO-RFQ / Acquisition de Ma : Improving and modernizing Request for Quota Single Stage - One E Pending Impl tériels Informatiques en souti IDA / 65770 Post Limited 90,000.00 0.00 2023-04-11 2023-06-06 2023-12-03 physical and statistical infra tions nvelope ementation en aux activités de l’Institut structure National de la Statistique (IN S) CI-INS COTE D'IVOIRE-35014 Country-Specific Component 6-GO-RFQ / Achats de matéri : Improving and modernizing Request for Quota Single Stage - One E Pending Impl IDA / 65770 Post Limited 200,000.00 0.00 2023-05-09 2023-07-04 2023-12-31 els roulants (120) Motos et c physical and statistical infra tions nvelope ementation asques pour le corps des age structure nts enquêteurs CI-INS COTE D'IVOIRE-35014 7-GO-RFQ / Acquisition d'équi Country-Specific Component pements techniques (Tables l : Improving and modernizing Request for Quota Single Stage - One E Pending Impl IDA / 65770 Post Limited 75,000.00 0.00 2023-05-03 2023-06-28 2023-12-25 umineuses, loupes etc.) pour physical and statistical infra tions nvelope ementation la cartothèque physique de l’ structure Institut National de la Statisti que (INS) CI-INS COTE D'IVOIRE-35014 Country-Specific Component 8-GO-RFQ / Acquisition de dix : Improving and modernizing Request for Quota Single Stage - One E Pending Impl IDA / 65770 Post Limited 480,000.00 0.00 2023-04-30 2023-06-25 2023-12-22 (10) véhicules pour la mise e physical and statistical infra tions nvelope ementation n œuvre du recensement agr structure icole CI-INS COTE D'IVOIRE-35014 Country-Specific Component 9-GO-RFQ / Acquisition de m : Improving and modernizing Request for Quota Single Stage - One E Pending Impl IDA / 65770 Post Limited 90,000.00 0.00 2023-06-05 2023-07-31 2024-01-27 atériels informatiques pour le physical and statistical infra tions nvelope ementation recensement agricole structure CI-INS COTE D'IVOIRE-35015 Country-Specific Component 2-GO-RFQ / Acquisition de m : Improving and modernizing Request for Quota Single Stage - One E Pending Impl obiliers de bureau pour les n IDA / 65770 Post Limited 90,000.00 0.00 2023-05-03 2023-06-28 2023-12-25 physical and statistical infra tions nvelope ementation ouveaux bureaux de l’Institut structure National de la Statistique (IN S) NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CI-INS COTE D'IVOIRE-27350 Country-Specific Component 7-NC-RFQ / Recrutement d'un : Improving and modernizing Request for Quota Single Stage - One E Pending Impl IDA / 65770 Post Limited 50,000.00 0.00 2022-02-05 2022-04-02 2023-04-02 Prestaire pour le gardiennag physical and statistical infra tions nvelope ementation e des locaux du Projet et du structure centre de cartographie CI-INS COTE D'IVOIRE-27351 1-NC-RFQ / Recrutement d'un Country-Specific Component Prestataire pour la fourniture : Improving and modernizing Request for Quota Single Stage - One E Pending Impl de police d'assurances malad IDA / 65770 Post Limited 80,000.00 0.00 2022-03-13 2022-05-08 2023-05-08 physical and statistical infra tions nvelope ementation ie, individuelle accident tous structure risques véhicules et Multirisq ue professionnelle pour les v éhicules et les bâtiments du projet CI-INS COTE D'IVOIRE-21456 Regional component: Harmo 3-NC-RFQ / Recrutement d'un nization, Data Collection, Qu Request for Quota Single Stage - One E Pending Impl prestataire pour l'entretien d IDA / 65750 ality Improvement, Dissemin Post Limited 40,000.00 0.00 2022-04-03 2022-05-29 2022-11-25 tions nvelope ementation es locaux de l'UCP PHAS et d ation and Use of Core Social u centre de cartographie and Economic Statistics Regional component: Harmo CI-INS COTE D'IVOIRE-21451 nization, Data Collection, Qu 0-NC-RFQ / Confection Kaké Request for Quota Single Stage - One E IDA / 65750 ality Improvement, Dissemin Post Limited 20,088.00 0.00 Canceled 2021-03-20 2021-05-15 2021-11-11 mono, Location diverses, Ser tions nvelope ation and Use of Core Social vice divers and Economic Statistics CI-INS COTE D'IVOIRE-24527 Regional component: Harmo 2-NC-RFQ / ONNEXION INTER nization, Data Collection, Qu Request for Quota Single Stage - One E NET (formation agents, sortie IDA / 65750 ality Improvement, Dissemin Post Limited 888.00 0.00 Canceled 2021-08-02 2021-09-27 2022-03-26 tions nvelope terrain, coordonnateur, super ation and Use of Core Social viseur, Headquater et collect and Economic Statistics e)/EHCVM-NSU CI-INS COTE D'IVOIRE-24527 Regional component: Harmo 3-NC-RFQ / REPRODUCTION nization, Data Collection, Qu Request for Quota Single Stage - One E DES OUTILS DE FORMATION ( IDA / 65750 ality Improvement, Dissemin Post Limited 891.00 0.00 Canceled 2021-08-02 2021-09-27 2022-03-26 tions nvelope questionnaire, manuel, librair ation and Use of Core Social ie photo, etc.) et Badges /EH and Economic Statistics CVM NSU Page 4 CI-INS COTE D'IVOIRE-21457 Regional component: Harmo 5-NC-RFQ / Reprographie des nization, Data Collection, Qu Request for Quota Single Stage - One E documents des projets (RECE IDA / 65750 ality Improvement, Dissemin Post Limited 52,000.00 0.00 Canceled 2022-04-25 2022-06-20 2022-12-17 tions nvelope NSEMENT, REPERTOIRE, EAI, ation and Use of Core Social IHPC, IPS) and Economic Statistics CI-INS COTE D'IVOIRE-21457 Regional component: Harmo 8-NC-RFQ / Reprographie des nization, Data Collection, Qu Request for Quota Single Stage - One E documents des projets (ANN IDA / 65750 ality Improvement, Dissemin Post Limited 12,460.00 0.00 Canceled 2022-04-05 2022-05-31 2022-11-27 tions nvelope UAIRE, REEA, ENQUETE PRO ation and Use of Core Social DUCTION ET PRIX) and Economic Statistics Regional component: Harmo CI-INS COTE D'IVOIRE-21446 nization, Data Collection, Qu Request for Quota Single Stage - One E 8-NC-RFQ / Réparation de vé IDA / 65750 ality Improvement, Dissemin Post Limited 99,920.00 0.00 Canceled 2021-04-04 2021-05-30 2021-11-26 tions nvelope hicules ation and Use of Core Social and Economic Statistics Regional component: Harmo CI-INS COTE D'IVOIRE-24526 nization, Data Collection, Qu 9-NC-RFQ / LOCATION DE SA Request for Quota Single Stage - One E IDA / 65750 ality Improvement, Dissemin Post Limited 800.00 0.00 Canceled 2021-08-02 2021-09-27 2022-03-26 LLE DE FORMATION AGENTS/ tions nvelope ation and Use of Core Social EHCVM -NSU and Economic Statistics CI-INS COTE D'IVOIRE-24527 Regional component: Harmo 0-NC-RFQ / FRAIS DE COMMU nization, Data Collection, Qu Request for Quota Single Stage - One E NICATION (coordonnateur, éq IDA / 65750 ality Improvement, Dissemin Post Limited 560.00 0.00 Canceled 2021-07-28 2021-09-22 2022-03-21 tions nvelope uipes technique et collecte / ation and Use of Core Social EHCVM-NSU and Economic Statistics Regional component: Harmo CI-INS COTE D'IVOIRE-21446 nization, Data Collection, Qu Request for Quota Single Stage - One E 2-NC-RFQ / Location motos p IDA / 65750 ality Improvement, Dissemin Post Limited 16,800.00 0.00 Canceled 2021-01-30 2021-03-27 2021-09-23 tions nvelope our la collecte sur le terrain ation and Use of Core Social and Economic Statistics CI-INS COTE D'IVOIRE-21456 Regional component: Harmo 6-NC-RFQ / Reprographie des nization, Data Collection, Qu documents des projets (PAAS Request for Quota Single Stage - One E IDA / 65750 ality Improvement, Dissemin Post Limited 6,726.00 0.00 Canceled 2022-03-28 2022-05-23 2022-11-19 , RAAS, PLATEFORME, REFON tions nvelope ation and Use of Core Social TE, ETUDE SNDS, RENFORCE and Economic Statistics MENT DE SITE PRODUCTION UTILISATEURS) Regional component: Harmo CI-INS COTE D'IVOIRE-21456 nization, Data Collection, Qu Request for Quota Single Stage - One E 9-NC-RFQ / Reprographie des IDA / 65750 ality Improvement, Dissemin Post Limited 8,126.00 0.00 Canceled 2022-04-24 2022-06-19 2022-12-16 tions nvelope documents ENSESI ation and Use of Core Social and Economic Statistics Regional component: Harmo CI-INS COTE D'IVOIRE-21447 nization, Data Collection, Qu 8-NC-RFQ / Acquisition de car IDA / 65750 ality Improvement, Dissemin Post Direct Selection Direct 40,000.00 0.00 Canceled 2021-01-28 2021-02-02 2021-03-09 2021-09-05 tes (traitement et production ation and Use of Core Social ) / CNTIG and Economic Statistics Regional component: Harmo CI-INS COTE D'IVOIRE-21453 nization, Data Collection, Qu 7-NC-DIR / Service autorisati IDA / 65750 ality Improvement, Dissemin Post Direct Selection Direct 65,000.00 0.00 Canceled 2022-03-30 2022-04-04 2022-05-09 2022-11-05 on de collecte de données gé ation and Use of Core Social ospatiales (ANAC) and Economic Statistics CI-INS COTE D'IVOIRE-21446 Regional component: Harmo 9-NC-RFQ / Recrutement d'un nization, Data Collection, Qu Request for Quota Single Stage - One E Pending Impl prestataire pour l'assurances IDA / 65750 ality Improvement, Dissemin Post Limited 72,000.00 0.00 2022-06-06 2022-08-01 2023-01-28 tions nvelope ementation des trente (30) véhicules pou ation and Use of Core Social r les enquêtes et recenseme and Economic Statistics nts dans le cadre du projet Regional component: Harmo CI-INS COTE D'IVOIRE-21450 nization, Data Collection, Qu 8-NC-RFQ / Acquisition d'un S Request for Quota Single Stage - One E IDA / 65750 ality Improvement, Dissemin Post Limited 6,000.00 0.00 Canceled 2022-04-19 2022-06-14 2022-12-11 ervice de VIDEO SURVEILLAN tions nvelope ation and Use of Core Social CE and Economic Statistics CI-INS COTE D'IVOIRE-21457 Regional component: Harmo 1-NC-RFQ / Reprographie des nization, Data Collection, Qu Request for Quota Single Stage - One E documents des projets (C. CA IDA / 65750 ality Improvement, Dissemin Post Limited 1,500.00 0.00 Canceled 2022-04-23 2022-06-18 2022-12-15 tions nvelope RTO-CALL CENTER -UGP-REF ation and Use of Core Social ORME 1&2-CNStat) and Economic Statistics CI-INS COTE D'IVOIRE-27350 9-NC-RFQ / Recrutement d'un Country-Specific Component prestataire pour le câblage r : Improving and modernizing Request for Quota Single Stage - One E Under Imple IDA / 65770 Post Limited 50,000.00 0.00 2022-06-21 2022-07-20 2022-08-16 2022-09-30 éseau informatique, téléphon physical and statistical infra tions nvelope mentation ique, internet et pose de com structure binés téléphoniques des loca ux de l'UCP-PHAS CI-INS COTE D'IVOIRE-21457 Regional component: Harmo 3-NC-RFQ / Reprographie des nization, Data Collection, Qu Request for Quota Single Stage - One E documents des projets (LIAS IDA / 65750 ality Improvement, Dissemin Post Limited 8,490.00 0.00 Canceled 2022-05-01 2022-06-26 2022-12-23 tions nvelope SE, CR, CEA, SANTE, ICF, CE, ation and Use of Core Social MARGE) and Economic Statistics Regional component: Harmo CI-INS COTE D'IVOIRE-21456 nization, Data Collection, Qu Request for Quota Single Stage - One E 8-NC-RFQ / Reprographie des IDA / 65750 ality Improvement, Dissemin Post Limited 7,257.00 0.00 Canceled 2022-03-22 2022-05-17 2022-11-13 tions nvelope documents RGPH 2020 ation and Use of Core Social and Economic Statistics CI-INS COTE D'IVOIRE-21447 0-NC-RFQ / Recrutement d'un prestataire pour la fourniture Regional component: Harmo de police d'Assurances dom nization, Data Collection, Qu Request for Quota Single Stage - One E Pending Impl mage des agents de collecte IDA / 65750 ality Improvement, Dissemin Post Limited 26,627.00 0.00 2022-06-20 2022-08-15 2023-02-11 tions nvelope ementation dans le cadre des recenseme ation and Use of Core Social nts et enquêtes financés par and Economic Statistics le PHAS (recensement génér al des entreprises, enquête e mploi, recensements agricole s) CI-INS COTE D'IVOIRE-27350 4-NC-RFB / Recrutement d'un Country-Specific Component prestataire pour la location d : Improving and modernizing Request for Quota Single Stage - One E Under Imple e véhicules en appoint dans l IDA / 65770 Post Limited 30,000.00 0.00 2022-06-11 2022-06-15 2022-07-23 2023-01-19 physical and statistical infra tions nvelope mentation e cadre des enquêtes et inter structure ventions du projet (enquête pilote pour le recensement g énéral des entreprises). Page 5 Regional component: Harmo CI-INS COTE D'IVOIRE-24526 nization, Data Collection, Qu 7-NC-RFQ / Location de véhic Request for Quota Single Stage - One E IDA / 65750 ality Improvement, Dissemin Post Limited 7,200.00 0.00 Canceled 2021-08-02 2021-09-27 2022-03-26 ules de type 4x4 - Mission de tions nvelope ation and Use of Core Social supervision /EHCVM-NSU and Economic Statistics CI-INS COTE D'IVOIRE-27350 5-NC-RFQ / Recrutement d'un Country-Specific Component prestataire pour le câblage r : Improving and modernizing Request for Quota Single Stage - One E Pending Impl IDA / 65770 Post Limited 80,000.00 0.00 2022-09-26 2022-11-21 2023-01-05 éseau téléphonique, internet physical and statistical infra tions nvelope ementation et pose de combinés télépho structure niques des locaux du centre de cartographie CI-INS COTE D'IVOIRE-30974 Country-Specific Component 0-NC-RFQ / Recrutement d'un : Improving and modernizing Pending Impl prestataire pour les services IDA / 65770 Post Direct Selection Direct - National 20,000.00 0.00 2022-09-05 2022-09-10 2022-10-15 2023-04-13 physical and statistical infra ementation de gardiennage des locaux d structure u centre de cartographie CI-INS COTE D'IVOIRE-30974 Country-Specific Component 4-NC-DIR / Recrutement d'un : Improving and modernizing Request for Quota Single Stage - One E Pending Impl IDA / 65770 Post Limited 18,000.00 0.00 2022-12-05 2023-01-30 2023-07-29 prestataire pour l'entretien d physical and statistical infra tions nvelope ementation es locaux du centre de carto structure graphie CI-INS COTE D'IVOIRE-32364 Country-Specific Component 6-NC-DIR / Recrutement d'un : Improving and modernizing Pending Impl prestataire pour l'entretien d IDA / 65770 Post Direct Selection Direct - National 200,000.00 0.00 2022-12-01 2022-12-06 2023-01-10 2023-07-09 physical and statistical infra ementation es véhicules acquis par le Pro structure jet pour les enquêtes CI-INS COTE D'IVOIRE-33252 6-NC-RFQ / Recrutement d'un Project Management and Mo Request for Quota Single Stage - One E Pending Impl Prestataire pour la gestion de IDA / 65770 Post Limited 20,000.00 0.00 2023-02-13 2023-04-10 2023-10-07 nitoring and Evaluation tions nvelope ementation s transfert mobile money des agents dans le cadre des acti vités du Projet CI-INS COTE D'IVOIRE-33257 Country-Specific Component 4-NC-RFQ / Recrutement d'un : Improving and modernizing Request for Quota Single Stage - One E Pending Impl IDA / 65770 Post Limited 60,000.00 0.00 2023-04-05 2023-05-31 2023-11-27 prestataire pour la mise en pl physical and statistical infra tions nvelope ementation ace d'un système d'archivag structure e électronique CI-INS COTE D'IVOIRE-32365 Country-Specific Component 1-NC-DIR / Recrutement d'un : Improving and modernizing Request for Quota Single Stage - One E Pending Impl IDA / 65770 Post Limited 30,000.00 0.00 2023-04-08 2023-06-03 2023-11-30 Prestataire pour l'entretien d physical and statistical infra tions nvelope ementation es copieurs de l'UCP structure CI-INS COTE D'IVOIRE-35010 4-NC-RFQ / Recrutement d'un Country-Specific Component prestataire pour le Câblage r : Improving and modernizing Request for Quota Single Stage - One E Pending Impl IDA / 65770 Post Limited 90,000.00 0.00 2023-05-03 2023-06-28 2023-12-25 éseau, informatique et téléph physical and statistical infra tions nvelope ementation onique pour le centre d’appel structure de l’Institut National de la St atistique (INS) CI-INS COTE D'IVOIRE-35011 Country-Specific Component 1-NC-RFQ / Recrutement d’u : Improving and modernizing Request for Quota Single Stage - One E Pending Impl n Prestataire pour l’entretien IDA / 65770 Post Limited 30,000.00 0.00 2023-05-09 2023-07-04 2023-12-31 physical and statistical infra tions nvelope ementation des locaux des trois (03) Cen structure tres (Cartographie, Appel et CAE) CI-INS COTE D'IVOIRE-35015 Country-Specific Component 0-NC-DIR / Convention avec l’ : Improving and modernizing Pending Impl Institut National de la Statisti IDA / 65770 Prior Direct Selection Direct - National 2,000,000.00 0.00 2023-05-02 2023-05-07 2023-06-11 2023-12-08 physical and statistical infra ementation que (INS) pour la mise en œu structure vre de l’enquête Budget Con sommation CI-INS COTE D'IVOIRE-35015 Country-Specific Component 3-NC-RFQ / Recrutement d'un : Improving and modernizing Pending Impl IDA / 65770 Post Direct Selection Direct - National 30,000.00 0.00 2023-04-14 2023-04-19 2023-05-24 2023-11-20 Prestataire pour l'entretien d physical and statistical infra ementation es locaux de l’UC PHAS structure CI-INS COTE D'IVOIRE-35028 Country-Specific Component 3-NC-RFQ / Recrutement d’u : Improving and modernizing Request for Quota Single Stage - One E Pending Impl n prestataire pour l’impressio IDA / 65770 Post Limited 30,000.00 0.00 2023-05-06 2023-07-01 2023-12-28 physical and statistical infra tions nvelope ementation n des documents et rapports structure dans le cadre des activités d u Projet CI-INS COTE D'IVOIRE-35029 Regional component: Harmo 1-NC-DIR / Convention avec l’ nization, Data Collection, Qu Pending Impl Institut National de la Statisti IDA / 65770 ality Improvement, Dissemin Post Direct Selection Direct - National 1,000,000.00 0.00 2023-04-27 2023-05-02 2023-06-06 2023-12-03 ementation que (INS) pour la mise en œ ation and Use of Core Social uvre de l’enquête emploi and Economic Statistics CI-INS COTE D'IVOIRE-35015 1-NC-DIR / Convention avec l’ Country-Specific Component Institut National de la Statisti : Improving and modernizing Pending Impl IDA / 65770 Prior Direct Selection Direct - National 4,000,000.00 0.00 2023-06-06 2023-06-11 2023-07-16 2024-07-15 que (INS) pour la mise en œu physical and statistical infra ementation vre du Recensement Général structure des entreprises et établissem ents de côte d’Ivoire (RGEECI ) CI-INS COTE D'IVOIRE-35013 Regional component: Harmo 8-NC-DIR / Convention avec l’ nization, Data Collection, Qu Pending Impl INS pour la mise en place du IDA / 65770 ality Improvement, Dissemin Prior Direct Selection Direct - National 3,000,000.00 0.00 2023-06-01 2023-06-06 2023-07-11 2024-01-07 ementation corps des agents enquêteurs ation and Use of Core Social sur une durée de deux ans et and Economic Statistics demi CI-INS COTE D'IVOIRE-35014 Country-Specific Component 1-NC-DIR / Recrutement d’un : Improving and modernizing Request for Quota Single Stage - One E Pending Impl IDA / 65770 Post Limited 30,000.00 0.00 2023-05-30 2023-07-25 2024-01-21 Prestataire pour le gardienna physical and statistical infra tions nvelope ementation ge des locaux de l’UCP structure CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CI-INS COTE D'IVOIRE-21458 3-CS-QCBS / Recrutement d'u Regional component: Harmo ne firme de Consultants pour nization, Data Collection, Qu Consultant Qualifi Under Implement le renforcement des capacité IDA / 65750 ality Improvement, Dissemin Post Limited 100,000.00 0.00 2021-03-15 2022-05-17 2021-03-29 2021-04-28 2021-06-02 2021-11-29 cation Selection ation s des techniciens (Formation ation and Use of Core Social en Big Data et tout autre for and Economic Statistics mation technique compléme ntaire) Page 6 CI-INS COTE D'IVOIRE-21461 Regional component: Harmo 3-CS-QCBS / Recrutement d'u nization, Data Collection, Qu Consultant Qualifi Pending Impleme n cabinet pour l'installation e IDA / 65750 ality Improvement, Dissemin Post Limited 35,000.00 0.00 2021-02-05 2021-02-19 2021-03-21 2021-04-25 2021-10-22 cation Selection ntation t la maintenance d'une appli ation and Use of Core Social cation pour le Call Center and Economic Statistics CI-INS COTE D'IVOIRE-21487 Regional component: Harmo 1-CS-CQS / Recrutement d’un nization, Data Collection, Qu Quality And Cost- Open - Internationa e firme pour accompagner la IDA / 65750 ality Improvement, Dissemin Post 72,000.00 0.00 Under Review 2021-03-15 2022-02-08 2021-04-05 2021-05-19 2021-06-16 2021-07-16 2021-08-20 2021-09-24 2022-09-24 Based Selection l mise en œuvre de la formati ation and Use of Core Social on à distance and Economic Statistics CI-INS COTE D'IVOIRE-27349 0-CS-QCBS / Recrutement d'u Country-Specific Component ne firme pour l'audit des fond : Improving and modernizing Quality And Cost- Pending Impleme IDA / 65770 Post Open - National 50,000.00 0.00 2022-02-01 2022-02-22 2022-03-18 2022-04-15 2022-05-15 2022-06-19 2022-07-24 2022-10-22 s de la Banque Mondiale dan physical and statistical infra Based Selection ntation s le cadre du Recensement G structure énéral de la Population et de l'Habitat (RGPH) CI-INS COTE D'IVOIRE-27349 Country-Specific Component 8-CS-QCBS / Recrutement d'u : Improving and modernizing Quality And Cost- Open - Internationa Under Implement IDA / 65770 Post 150,000.00 0.00 2022-02-16 2022-03-09 2022-03-09 2022-04-06 2022-04-22 2022-05-20 2022-06-19 2022-07-24 2022-08-28 2023-08-28 n cabinet pour la mise en pla physical and statistical infra Based Selection l ation ce d'un modèle macro écono structure métrique CI-INS COTE D'IVOIRE-21487 Regional component: Harmo 0-CS-QCBS / Recrutement d’ nization, Data Collection, Qu une firme chargée d’accomp Quality And Cost- Under Implement IDA / 65750 ality Improvement, Dissemin Post Open - National 70,000.00 0.00 2022-04-07 2022-05-17 2022-04-28 2022-06-27 2022-06-11 2022-07-09 2022-08-08 2022-09-12 2022-10-17 2023-10-17 agner l’ENSEA dans le dévelo Based Selection ation ation and Use of Core Social ppement de certificats profes and Economic Statistics sionnels dans le cadre de la f ormation continue Regional component: Harmo CI-INS COTE D'IVOIRE-21460 nization, Data Collection, Qu 6-CS-QCBS / Recrutement Ca Least Cost Selecti Pending Impleme IDA / 65750 ality Improvement, Dissemin Post Open - National 10,000.00 0.00 2022-03-30 2022-04-20 2022-06-03 2022-07-01 2022-07-31 2022-09-04 2022-10-09 2023-04-07 binet d'Audit des comptes de on ntation ation and Use of Core Social gestion du Projet and Economic Statistics CI-INS COTE D'IVOIRE-21488 Regional component: Harmo 9-CS-CQS / Recrutement d’un nization, Data Collection, Qu Consultant Qualifi Cabinet de consultants pour l IDA / 65750 ality Improvement, Dissemin Post Limited 10,300.00 0.00 Canceled 2021-06-30 2021-07-14 2021-08-13 2021-09-17 2022-03-16 cation Selection a réalisation de l'Enquête Sol ation and Use of Core Social de opinions Immobiliers and Economic Statistics CI-INS COTE D'IVOIRE-21458 Regional component: Harmo 6-CS-QCBS / Recrutement d'u nization, Data Collection, Qu Consultant Qualifi n Cabinet de conception de s IDA / 65750 ality Improvement, Dissemin Post Limited 40,000.00 0.00 Canceled 2021-02-12 2021-02-26 2021-03-28 2021-05-02 2021-10-29 cation Selection ite dans le cadre de la refont ation and Use of Core Social e du site internet de l'INS and Economic Statistics CI-INS COTE D'IVOIRE-21461 Regional component: Harmo 2-CS-QCBS / Recrutement d'u nization, Data Collection, Qu Consultant Qualifi n cabinet pour la réalisation IDA / 65750 ality Improvement, Dissemin Post Limited 35,000.00 0.00 Canceled 2022-04-27 2022-05-11 2022-06-10 2022-07-15 2023-01-11 cation Selection de la 2ème étude spécifique ation and Use of Core Social sur les réformes institutionne and Economic Statistics lles de l'INS CI-INS COTE D'IVOIRE-21461 7-CS-QCBS / Assistance cons Regional component: Harmo eil d'un opérateur (Faire l’étu nization, Data Collection, Qu Consultant Qualifi de par l’inventaire des conne IDA / 65750 ality Improvement, Dissemin Post Limited 10,000.00 0.00 Canceled 2022-03-31 2022-04-14 2022-05-14 2022-06-18 2022-12-15 cation Selection xions Internet et des équipe ation and Use of Core Social ments informatiques d’interc and Economic Statistics onnexion existant pour les sit es à interconnecter) CI-INS COTE D'IVOIRE-21461 Regional component: Harmo 1-CS-QCBS / Recrutement d'u nization, Data Collection, Qu Consultant Qualifi n cabinet pour la réalisation IDA / 65750 ality Improvement, Dissemin Post Limited 35,000.00 0.00 Canceled 2022-04-06 2022-04-20 2022-05-20 2022-06-24 2022-12-21 cation Selection de la 1ère étude spécifique s ation and Use of Core Social ur les réformes institutionnell and Economic Statistics es de l'INS CI-INS COTE D'IVOIRE-21458 Regional component: Harmo 7-CS-QCBS / Recrutement d'u nization, Data Collection, Qu Consultant Qualifi n cabinet pour la réalisation IDA / 65750 ality Improvement, Dissemin Post Limited 35,000.00 0.00 Canceled 2022-04-28 2022-05-12 2022-06-11 2022-07-16 2023-01-12 cation Selection de l'étude sur la SNDS 2017- ation and Use of Core Social 2021 and Economic Statistics CI-INS COTE D'IVOIRE-21488 Regional component: Harmo 6-CS-CQS / Recrutement d’un nization, Data Collection, Qu Consultant Qualifi Cabinet de consultants pour l IDA / 65750 ality Improvement, Dissemin Post Limited 10,300.00 0.00 Canceled 2022-02-24 2022-03-10 2022-04-09 2022-05-14 2022-11-10 cation Selection a réalisation de l'Enquête Sol ation and Use of Core Social de opinions Transport and Economic Statistics CI-INS COTE D'IVOIRE-21460 Regional component: Harmo 9-CS-QCBS / Recrutement d'u nization, Data Collection, Qu Consultant Qualifi n Cabinet pour l'élaboration IDA / 65750 ality Improvement, Dissemin Post Limited 30,000.00 0.00 Canceled 2021-02-10 2021-02-24 2021-03-26 2021-04-30 2021-10-27 cation Selection du Manuel de procédures du ation and Use of Core Social Projet and Economic Statistics CI-INS COTE D'IVOIRE-30975 6-CS-QCBS / Recrutement d'u Country-Specific Component ne firme pour la mise en plac : Improving and modernizing Quality And Cost- Open - Internationa IDA / 65770 Post 150,000.00 0.00 Under Review 2022-09-28 2022-10-18 2022-10-19 2022-12-02 2022-12-30 2023-01-29 2023-03-05 2023-04-09 2024-04-08 e d’un modèle de prévisions physical and statistical infra Based Selection l macroéconomiques trimestri structure elles (macrotrim) pour la côt e d’ivoire CI-INS COTE D'IVOIRE-32271 Country-Specific Component 2-CS-CQS / Recrutement d’un : Improving and modernizing Consultant Qualifi Under Implement e firme pour un accompagne IDA / 65770 Post Open - National 75,000.00 0.00 2022-11-30 2023-01-31 2022-12-21 2023-05-05 2023-02-03 2023-03-05 2023-04-09 2023-10-06 physical and statistical infra cation Selection ation ment technique dans le cadr structure e de la mise en place du cent re d’appels CI-INS COTE D'IVOIRE-30215 4-CS-QCBS / Recrutement d'u ne firme pour la Mise en plac Country-Specific Component e d’un modèle d’équilibre gé : Improving and modernizing Quality And Cost- Open - Internationa IDA / 65770 Post 100,000.00 0.00 Under Review 2022-11-30 2023-04-05 2022-12-21 2023-02-03 2023-03-03 2023-04-02 2023-05-07 2023-06-11 2024-06-10 néral calculable statique et d physical and statistical infra Based Selection l ynamique (MEGC) et d’un mo structure dèle d’équilibre général stoc hastique dynamique (DGSE) pour la Côte d’ivoire CI-INS COTE D'IVOIRE-33225 Country-Specific Component 6-CS-QBS / Recrutement d'un : Improving and modernizing Quality Based Sel Open - Internationa Pending Impleme IDA / 65770 Post 158,000.00 0.00 2023-02-02 2023-02-23 2023-04-08 2023-05-06 2023-06-05 2023-07-05 2023-08-09 2024-08-08 cabinet pour la mise en place physical and statistical infra ection l ntation d'un modèle d'équilibre géné structure ral calculable Page 7 CI-INS COTE D'IVOIRE-33225 Country-Specific Component 7-CS-QBS / Recrutement d'un : Improving and modernizing Quality Based Sel Open - Internationa e firme pour la mise en place IDA / 65770 Post 103,000.00 0.00 Under Review 2023-03-01 2023-04-05 2023-03-22 2023-05-05 2023-06-02 2023-07-02 2023-08-01 2023-09-05 2024-09-04 physical and statistical infra ection l d'un modèle DSGE (Dynamic structure Stochastic General Equilibriu m) INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Regional component: Harmo CI-INS COTE D'IVOIRE-21459 nization, Data Collection, Qu 3-CS-INDV / Recrutement Sp Individual Consult Under Implement IDA / 65750 ality Improvement, Dissemin Post Open 48,000.00 0.00 2021-02-03 2021-03-29 2021-03-24 2021-09-03 2021-04-14 2021-05-19 2021-11-15 écialiste en Passation de Mar ant Selection ation ation and Use of Core Social chés du Projet and Economic Statistics CI-INS COTE D'IVOIRE-21461 Regional component: Harmo 5-CS-INDV / Recrutement d’u nization, Data Collection, Qu n consultant chargé de l’ani Individual Consult Under Implement IDA / 65750 ality Improvement, Dissemin Post Open 10,000.00 0.00 2021-03-15 2022-05-17 2021-05-03 2021-05-24 2021-06-28 2021-12-25 mation du pôle de recherche ant Selection ation ation and Use of Core Social et de développement des co and Economic Statistics mpétences en statistique et r essources numériques Regional component: Harmo CI-INS COTE D'IVOIRE-21488 nization, Data Collection, Qu 4-CS-INDV / Recrutement d'u Individual Consult Under Implement IDA / 65750 ality Improvement, Dissemin Post Limited 15,744.00 0.00 2021-05-14 2022-03-23 2021-05-19 2021-06-09 2021-07-14 2022-01-10 n consultant Formateur en te ant Selection ation ation and Use of Core Social chnique de Prévision and Economic Statistics Regional component: Harmo CI-INS COTE D'IVOIRE-21489 nization, Data Collection, Qu 0-CS-INDV / Recrutement d'u Individual Consult Pending Impleme IDA / 65750 ality Improvement, Dissemin Post Limited 40,000.00 0.00 2021-03-15 2021-03-20 2021-04-10 2021-05-15 2021-11-11 n consultant dans le cadre de ant Selection ntation ation and Use of Core Social l'activité IPS ICA and Economic Statistics CI-INS COTE D'IVOIRE-21490 Regional component: Harmo 2-CS-INDV / Recrutement d'u nization, Data Collection, Qu Individual Consult Pending Impleme n Expert pour la production d IDA / 65750 ality Improvement, Dissemin Post Limited 8,800.00 0.00 2021-03-15 2021-03-20 2021-04-10 2021-05-15 2021-11-11 ant Selection ntation es Statistiques du Commerce ation and Use of Core Social Extérieur and Economic Statistics Regional component: Harmo CI-INS COTE D'IVOIRE-22840 nization, Data Collection, Qu Individual Consult 2-CS-INDV / Recrutement du IDA / 65750 ality Improvement, Dissemin Post Open 72,000.00 3,085.31 Signed 2021-04-17 2021-05-27 2021-06-05 2021-09-01 2021-06-26 2021-10-08 2021-07-31 2021-11-06 2022-01-27 ant Selection Coordonnateur du Projet ation and Use of Core Social and Economic Statistics Regional component: Harmo CI-INS COTE D'IVOIRE-22840 nization, Data Collection, Qu 5-CS-INDV / Recrutement du Individual Consult IDA / 65750 ality Improvement, Dissemin Post Open 48,000.00 0.00 Under Review 2021-04-12 2021-05-27 2021-05-31 2022-01-14 2021-06-21 2021-07-26 2022-01-22 Spécialiste en gestion financi ant Selection ation and Use of Core Social ère et décaissement (RAF) and Economic Statistics CI-INS COTE D'IVOIRE-26140 3-CS-CDS / Convention avec l ’INS relative au recrutement Regional component: Harmo du personnel de collecte et d nization, Data Collection, Qu ’un opérateur de paiement m IDA / 65750 ality Improvement, Dissemin Prior Direct Selection Direct 12,216,000.00 0.00 Canceled 2021-11-05 2021-11-15 2022-01-19 2022-07-18 obile pour le paiement des p ation and Use of Core Social erdiems du personnel de coll and Economic Statistics ecte dans le cadre du Recens ement Général de la Populati on et de l’Habitat 2021-10-21 (RGPH 2021) CI-INS COTE D'IVOIRE-26235 9-CS-CDS / Convention avec l ’INS relative au recrutement Regional component: Harmo du personnel de collecte et d nization, Data Collection, Qu ’un opérateur de paiement m IDA / 65750 ality Improvement, Dissemin Prior Direct Selection Direct 16,483,740.00 0.00 Under Review 2021-11-10 2021-11-12 2021-11-20 2021-11-15 2022-01-24 2022-07-23 obile pour le paiement des p ation and Use of Core Social erdiems du personnel de coll and Economic Statistics ecte dans le cadre du recens ement Général de la Populati on et de l’Habitat 2021-10-21 (RGPH 2021) CI-INS COTE D'IVOIRE-27334 Country-Specific Component Individual Consult Under Implement 6-CS-INDV / Recruter 20 Adjo IDA / 65770 : Improving and modernizing Post Open 25,000.00 0.00 2022-02-07 2022-05-12 2022-03-08 2022-03-18 2022-04-04 2023-04-04 ant Selection ation ints Techniques de la Statisti physical and statistical infra que structure CI-INS COTE D'IVOIRE-27334 Country-Specific Component Individual Consult Under Implement 7-CS-INDV / Recrutement de IDA / 65770 : Improving and modernizing Post Open 36,000.00 0.00 2022-02-07 2022-05-12 2022-03-13 2022-03-14 2022-04-03 2023-04-03 ant Selection ation trois (03) géomaticiens physical and statistical infra structure CI-INS COTE D'IVOIRE-27349 Country-Specific Component 2-CS-INDV / recrutement d'u : Improving and modernizing Individual Consult Under Implement n consultant international sta IDA / 65770 Post Open 30,000.00 0.00 2022-02-17 2022-11-07 2022-04-07 2022-04-28 2022-06-02 2022-08-31 physical and statistical infra ant Selection ation tisticien agricole spécialisé e structure n sondage et analyse de don nées CI-INS COTE D'IVOIRE-27349 4-CS-INDV / Recrutement d’u Country-Specific Component n consultant individuel pour l : Improving and modernizing Individual Consult Under Implement IDA / 65770 Post Open 50,000.00 0.00 2022-02-10 2022-05-17 2022-03-31 2022-04-21 2022-05-26 2022-08-24 ’élaboration des textes juridi physical and statistical infra ant Selection ation ques associes a la création d’ structure une fondation liée a l’ENSEA CI-INS COTE D'IVOIRE-27349 Country-Specific Component 6-CS-INDV / Recrutement d'u : Improving and modernizing Individual Consult Pending Impleme n Consultant Individuel pour l IDA / 65770 Post Open 36,000.00 0.00 2022-02-10 2022-03-31 2022-04-21 2022-05-26 2022-08-24 physical and statistical infra ant Selection ntation 'élaboration d'un nouveau dé structure cret sur le fonctionnement d e l'ENSEA CI-INS COTE D'IVOIRE-27355 5-CS-INDV / Recrutement d’u Project Management and Mo Individual Consult Under Implement n consultant pour les études IDA / 65770 Post Limited 10,000.00 0.00 2022-02-01 2022-02-21 2022-02-06 2022-02-27 2022-04-03 2022-04-18 nitoring and Evaluation ant Selection ation de réhabilitation/configuratio n des bureaux du Projet et d u centre de cartographie CI-INS COTE D'IVOIRE-21485 Regional component: Harmo 5-CS-INDV / Recrutement de nization, Data Collection, Qu Individual Consult Under Implement quinze (15) Ingénieurs Statist IDA / 65750 ality Improvement, Dissemin Post Open 267,505.00 0.00 2022-04-06 2022-05-12 2022-05-25 2022-06-15 2022-07-20 2023-01-16 ant Selection ation iciens Economistes pour le re ation and Use of Core Social nforcement des capacités tec and Economic Statistics hnique de l'INS Page 8 Regional component: Harmo CI-INS COTE D'IVOIRE-21460 nization, Data Collection, Qu 8-CS-INDV / Recrutement Co Individual Consult IDA / 65750 ality Improvement, Dissemin Post Limited 14,400.00 0.00 Canceled 2021-02-08 2021-02-13 2021-03-06 2021-04-10 2021-10-07 nducteur de véhicule adminis ant Selection ation and Use of Core Social tratif du Projet and Economic Statistics Regional component: Harmo CI-INS COTE D'IVOIRE-21460 nization, Data Collection, Qu Individual Consult 7-CS-INDV / Recrutement Ag IDA / 65750 ality Improvement, Dissemin Post Limited 16,800.00 0.00 Canceled 2021-02-08 2021-02-13 2021-03-06 2021-04-10 2021-10-07 ant Selection ent de liaison du Projet ation and Use of Core Social and Economic Statistics Regional component: Harmo CI-INS COTE D'IVOIRE-21459 nization, Data Collection, Qu Individual Consult 8-CS-INDV / Recrutement Log IDA / 65750 ality Improvement, Dissemin Post Open 24,000.00 0.00 Canceled 2021-02-05 2021-03-26 2021-04-16 2021-05-21 2021-11-17 ant Selection isticien du Projet ation and Use of Core Social and Economic Statistics CI-INS COTE D'IVOIRE-21489 Regional component: Harmo 2-CS-CDS / Mise en place d'u nization, Data Collection, Qu n Système d'Information Géo IDA / 65750 ality Improvement, Dissemin Post Direct Selection Direct 200,000.00 0.00 Canceled 2021-01-29 2021-02-08 2021-04-14 2021-10-11 graphique pour le recenseme ation and Use of Core Social nt des entreprises (CNTIG) and Economic Statistics Regional component: Harmo CI-INS COTE D'IVOIRE-21459 nization, Data Collection, Qu Individual Consult 9-CS-INDV / Recrutement Ass IDA / 65750 ality Improvement, Dissemin Post Open 24,000.00 0.00 Canceled 2021-02-05 2021-03-26 2021-04-16 2021-05-21 2021-11-17 ant Selection istante de Direction du Projet ation and Use of Core Social and Economic Statistics Regional component: Harmo CI-INS COTE D'IVOIRE-22840 nization, Data Collection, Qu 6-CS-INDV / Recrutement du Individual Consult IDA / 65750 ality Improvement, Dissemin Post Open 48,000.00 0.00 Canceled 2021-04-12 2021-05-27 2021-05-31 2021-06-21 2021-07-26 2022-01-22 Spécialiste en Suivi Evaluatio ant Selection ation and Use of Core Social n du Projet and Economic Statistics Regional component: Harmo CI-INS COTE D'IVOIRE-21488 nization, Data Collection, Qu 3-CS-INDV / Recrutement d’u Individual Consult IDA / 65750 ality Improvement, Dissemin Post Limited 16,000.00 0.00 Canceled 2021-03-15 2021-03-20 2021-04-10 2021-05-15 2021-11-11 n consultant Formation Conjo ant Selection ation and Use of Core Social ncture and Economic Statistics Regional component: Harmo CI-INS COTE D'IVOIRE-21489 nization, Data Collection, Qu 7-CS-INDV / Recrutement d'e Individual Consult IDA / 65750 ality Improvement, Dissemin Post Limited 16,000.00 0.00 Canceled 2021-02-19 2021-02-24 2021-03-17 2021-04-21 2021-10-18 xpert-comptable auprès d'un ant Selection ation and Use of Core Social cabinet comptable and Economic Statistics CI-INS COTE D'IVOIRE-21489 Regional component: Harmo 6-CS-INDV / Recrutement de nization, Data Collection, Qu Individual Consult ux (02) experts informaticien IDA / 65750 ality Improvement, Dissemin Post Limited 56,330.00 0.00 Canceled 2021-01-29 2021-02-03 2021-02-24 2021-03-31 2021-09-27 ant Selection s pour les travaux de liasses ation and Use of Core Social auprès d'un cabinet informati and Economic Statistics que CI-INS COTE D'IVOIRE-21489 Regional component: Harmo 8-CS-INDV / Recrutement de nization, Data Collection, Qu Individual Consult consultants pour la productio IDA / 65750 ality Improvement, Dissemin Post Limited 26,000.00 0.00 Canceled 2021-04-19 2021-04-24 2021-05-15 2021-06-19 2021-12-16 ant Selection n des comptes satellites de l ation and Use of Core Social a Santé and Economic Statistics Regional component: Harmo CI-INS COTE D'IVOIRE-21459 nization, Data Collection, Qu Individual Consult 7-CS-INDV / Recrutement Co IDA / 65750 ality Improvement, Dissemin Post Open 24,000.00 0.00 Canceled 2021-02-04 2021-03-25 2021-04-15 2021-05-20 2021-11-16 ant Selection mptable du Projet ation and Use of Core Social and Economic Statistics CI-INS COTE D'IVOIRE-21490 Regional component: Harmo 1-CS-INDV / Recrutement de nization, Data Collection, Qu Individual Consult Consultants pour la productio IDA / 65750 ality Improvement, Dissemin Post Limited 16,000.00 0.00 Canceled 2021-06-18 2021-06-23 2021-07-14 2021-08-18 2022-02-14 ant Selection n des comptes Economiques ation and Use of Core Social de l'agriculture and Economic Statistics CI-INS COTE D'IVOIRE-21490 Regional component: Harmo 3-CS-INDV / Recrutement d'u nization, Data Collection, Qu Individual Consult n Informaticien programmeur IDA / 65750 ality Improvement, Dissemin Post Limited 10,000.00 0.00 Canceled 2021-03-25 2021-03-30 2021-04-20 2021-05-25 2021-11-21 ant Selection pour la production des statist ation and Use of Core Social iques du Commerce Extérieu and Economic Statistics r Regional component: Harmo CI-INS COTE D'IVOIRE-21490 nization, Data Collection, Qu 4-CS-INDV / Recrutement d'u Individual Consult IDA / 65750 ality Improvement, Dissemin Post Limited 35,000.00 0.00 Canceled 2021-02-15 2021-02-20 2021-03-13 2021-04-17 2021-10-14 n consultant à long terme en ant Selection ation and Use of Core Social Comptabilité National and Economic Statistics Regional component: Harmo CI-INS COTE D'IVOIRE-21490 nization, Data Collection, Qu 5-CS-INDV / Recrutement d’u Individual Consult IDA / 65750 ality Improvement, Dissemin Post Limited 35,000.00 0.00 Canceled 2021-02-15 2021-02-20 2021-03-13 2021-04-17 2021-10-14 n consultant à long terme en ant Selection ation and Use of Core Social Statistique d'Entreprises and Economic Statistics CI-INS COTE D'IVOIRE-21460 Regional component: Harmo 1-CS-INDV / Recrutement d'u nization, Data Collection, Qu Individual Consult n Consultant Expertise équip IDA / 65750 ality Improvement, Dissemin Post Limited 12,000.00 0.00 Canceled 2021-02-15 2021-02-20 2021-03-13 2021-04-17 2021-10-14 ant Selection e technique pour l'indice d'ac ation and Use of Core Social cessibilité and Economic Statistics CI-INS COTE D'IVOIRE-21460 Regional component: Harmo 5-CS-INDV / Recrutement d'u nization, Data Collection, Qu Individual Consult n Consultant en organisation IDA / 65750 ality Improvement, Dissemin Post Open 12,000.00 0.00 Canceled 2021-02-08 2021-03-29 2021-04-19 2021-05-24 2021-11-20 ant Selection statistique dans le cadre de l ation and Use of Core Social a refonte du site internet de l and Economic Statistics 'INS Regional component: Harmo CI-INS COTE D'IVOIRE-21487 nization, Data Collection, Qu 3-CS-CQS / Recrutement de c Individual Consult IDA / 65750 ality Improvement, Dissemin Post Limited 4,000.00 0.00 Canceled 2022-04-05 2022-04-10 2022-05-01 2022-06-05 2022-12-02 onsultant Enquête Producteu ant Selection ation and Use of Core Social r de l'agriculture and Economic Statistics CI-INS COTE D'IVOIRE-27349 Country-Specific Component 1-CS-INDV / Recrutement d’u : Improving and modernizing Individual Consult n consultant international inf IDA / 65770 Post Open 30,000.00 0.00 Canceled 2022-02-08 2022-03-29 2022-04-19 2022-05-24 2022-08-22 physical and statistical infra ant Selection ormaticien spécialisé en trait structure ement informatique des rece nsements et enquêtes Page 9 CI-INS COTE D'IVOIRE-21486 Regional component: Harmo 5-CS-INDV / Recrutement d'u nization, Data Collection, Qu Individual Consult Pending Impleme n Webmaster pour le centre IDA / 65750 ality Improvement, Dissemin Post Open 36,000.00 0.00 2022-07-28 2022-09-15 2022-10-06 2022-11-10 2023-05-09 ant Selection ntation de traitement des travaux ca ation and Use of Core Social rtographiques et la refonte d and Economic Statistics u site internet de l'INS CI-INS COTE D'IVOIRE-21460 Regional component: Harmo 4-CS-INDV / Recrutement d'u nization, Data Collection, Qu Individual Consult n Webmaster dans le cadre d IDA / 65750 ality Improvement, Dissemin Post Open 5,000.00 0.00 Canceled 2021-02-08 2021-03-29 2021-04-19 2021-05-24 2021-11-20 ant Selection e la refonte du site internet d ation and Use of Core Social e l'INS and Economic Statistics CI-INS COTE D'IVOIRE-21460 Regional component: Harmo 3-CS-INDV / Recrutement d'u nization, Data Collection, Qu Individual Consult n Webmaster pour le centre IDA / 65750 ality Improvement, Dissemin Post Limited 16,800.00 0.00 Canceled 2022-05-30 2022-06-04 2022-06-25 2022-07-30 2023-01-26 ant Selection de traitement des travaux ca ation and Use of Core Social rtographiques and Economic Statistics CI-INS COTE D'IVOIRE-21486 Regional component: Harmo 3-CS-INDV / Recrutement de nization, Data Collection, Qu Individual Consult douze (12) Adjoints Techniqu IDA / 65750 ality Improvement, Dissemin Post Open 250,734.00 0.00 Canceled 2022-03-31 2022-05-19 2022-06-09 2022-07-14 2023-01-10 ant Selection es des statistiques pour le re ation and Use of Core Social nforcement des capacités tec and Economic Statistics hniques de l'INS CI-INS COTE D'IVOIRE-21486 Regional component: Harmo 2-CS-INDV / Recrutement de nization, Data Collection, Qu Individual Consult dix (10) ingénieurs des trava IDA / 65750 ality Improvement, Dissemin Post Open 260,539.00 0.00 Canceled 2021-02-11 2021-04-01 2021-04-22 2021-05-27 2021-11-23 ant Selection ux statistiques pour le renfor ation and Use of Core Social cement des capacités techni and Economic Statistics ques de l'INS CI-INS COTE D'IVOIRE-29798 Regional component: Harmo 4-CS-INDV / RECRUTEMENT D nization, Data Collection, Qu Individual Consult E SEIZE (16) INGENIEURS DE IDA / 65770 ality Improvement, Dissemin Post Open 300,000.00 0.00 Under Review 2022-07-20 2022-06-16 2022-09-07 2022-09-28 2022-11-02 2023-05-01 ant Selection S TRAVAUX STATISTIQUES (IT ation and Use of Core Social S), and Economic Statistics CI-INS COTE D'IVOIRE-29798 5-CS-INDV / RECRUTEMENT D Country-Specific Component E 02 INGENIEURS INFORMATI : Improving and modernizing Individual Consult Under Implement IDA / 65770 Post Open 48,000.00 0.00 2022-07-15 2022-06-16 2022-09-02 2022-09-23 2022-10-28 2023-04-26 CIENS (DEVELOPPEUR D’APP physical and statistical infra ant Selection ation LICATIONS ET WEBMASTER) structure dans le cadre du programme des jeunes professionnels CI-INS COTE D'IVOIRE-29806 2-CS-CDS / Recrutement d'un Cabinet d'audit comptable et Project Management and Mo IDA / 65770 Post Direct Selection Direct 10,000.00 0.00 Under Review 2022-06-21 2022-06-15 2022-07-01 2022-09-04 2023-03-03 financier pour la réalisation d nitoring and Evaluation e l'audit comptable et financi er de l'exercice 2021 du PHA S CI-INS COTE D'IVOIRE-30850 4-CS-INDV / Recrutement d'u Country-Specific Component n consultant pour l'élaboratio : Improving and modernizing Individual Consult Under Implement n des plans d'aménagements IDA / 65770 Post Limited 25,000.00 0.00 2022-09-09 2022-12-19 2022-09-14 2022-09-19 2022-10-31 2023-04-29 physical and statistical infra ant Selection ation et la supervision des travaux structure d'aménagement des nouvea ux bâtiments de l'INS et du c entre de cartographie CI-INS COTE D'IVOIRE-32272 2-CS-INDV / Recrutement d'u Country-Specific Component n consultant individuel pour l' : Improving and modernizing Individual Consult Pending Impleme IDA / 65770 Post Limited 20,000.00 0.00 2022-11-30 2022-12-05 2022-12-26 2023-01-30 2023-07-29 élaboration des cahiers de ch physical and statistical infra ant Selection ntation arges et la maitrise d'œuvre structure des travaux d'aménagement des différents centres CI-INS COTE D'IVOIRE-30847 4-CS-INDV / Recrutement de Country-Specific Component deux (02) Consultants superv : Improving and modernizing Individual Consult Under Implement IDA / 65770 Post Open - National 48,000.00 0.00 2022-11-30 2022-12-28 2023-01-18 2023-02-08 2023-03-15 2023-09-11 iseurs pour la mise en place physical and statistical infra ant Selection ation des centres d'appel, centre d structure 'innovation cartographique et centre de calcul CI-INS COTE D'IVOIRE-30851 8-CS-INDV / Recrutement d’u Country-Specific Component n Consultant pour l'Actualisat : Improving and modernizing Individual Consult Pending Impleme ion des analyses approfondie IDA / 65770 Post Limited 10,000.00 0.00 2022-12-02 2022-12-07 2022-12-28 2023-02-01 2023-07-31 physical and statistical infra ant Selection ntation s de l’EHCVM 2018 et de la D structure ynamique de la pauvreté ent re 1993 et 2018 en Côte d’Iv oire CI-INS COTE D'IVOIRE-30849 Country-Specific Component 1-CS-INDV / Recrutement de : Improving and modernizing Individual Consult Under Implement deux (02) consultants cartoth IDA / 65770 Post Limited 40,000.00 0.00 2022-12-01 2022-12-28 2022-12-06 2022-12-27 2023-01-31 2023-07-30 physical and statistical infra ant Selection ation écaires pour la mise en place structure du centre de cartographie CI-INS COTE D'IVOIRE-30850 Country-Specific Component 1-CS-INDV / Recrutement de : Improving and modernizing Individual Consult Under Implement quarante (40) téléopérateurs IDA / 65770 Post Open - National 180,000.00 0.00 2023-01-31 2022-12-28 2023-03-21 2023-04-11 2023-05-16 2023-11-12 physical and statistical infra ant Selection ation pour la mise en place et le fo structure nctionnement du centre d'ap pel CI-INS COTE D'IVOIRE-32364 Country-Specific Component 8-CS-INDV / Recrutement de : Improving and modernizing Individual Consult Under Implement quinze (15) consultants lecte IDA / 65770 Post Open - National 50,000.00 0.00 2023-01-31 2022-12-27 2023-03-21 2023-04-11 2023-05-16 2023-11-12 physical and statistical infra ant Selection ation urs pour la relecture et la vali structure dation des rapports d’analys e CI-INS COTE D'IVOIRE-30847 5-CS-INDV / Recrutement d'u Country-Specific Component n Consultant Ingénieur en rés : Improving and modernizing Individual Consult Pending Impleme eau, sécurité et système d'in IDA / 65770 Post Open - National 36,000.00 0.00 2023-01-31 2023-03-21 2023-04-11 2023-05-16 2023-11-12 physical and statistical infra ant Selection ntation formation pour la mise en pla structure ce et l'opérationnalisation du centre d'appel pour la collect e des données de l'INS CI-INS COTE D'IVOIRE-30849 6-CS-INDV / Recrutement d'u Country-Specific Component n Consultant expert en sécuri : Improving and modernizing Individual Consult IDA / 65770 Post Open - National 30,000.00 0.00 Under Review 2023-01-31 2023-06-20 2023-03-21 2023-04-11 2023-05-16 2023-11-12 té et réseau pour la mise en physical and statistical infra ant Selection place des centres d'appel, de structure calcul et d'innovation cartogr aphique CI-INS COTE D'IVOIRE-30849 Country-Specific Component 8-CS-INDV / Recrutement d'u : Improving and modernizing Individual Consult Under Implement IDA / 65770 Post Open - National 36,000.00 0.00 2023-01-19 2022-12-28 2023-03-09 2023-03-30 2023-05-04 2023-10-31 n Consultant Project Manage physical and statistical infra ant Selection ation ment Officer pour l'INS structure Page 10 CI-INS COTE D'IVOIRE-30851 Country-Specific Component 3-CS-CDS / Actualisation des : Improving and modernizing Pending Impleme IDA / 65770 Post Direct Selection Direct - National 20,000.00 0.00 2022-11-30 2022-12-10 2023-02-13 2023-08-12 analyses approfondies de l’E physical and statistical infra ntation HCVM 2018 par l’équipe de r structure echerche de l’ENSEA CI-INS COTE D'IVOIRE-30849 4-CS-INDV / Recrutement d'u Country-Specific Component n Consultant Chargé des opé : Improving and modernizing Individual Consult Under Implement IDA / 65770 Post Open - National 24,000.00 0.00 2023-01-31 2022-12-28 2023-03-21 2023-04-11 2023-05-16 2023-11-12 rations pour le centre d'innov physical and statistical infra ant Selection ation ation cartographique, d'analy structure se économique et du centre de calcul CI-INS COTE D'IVOIRE-32270 Country-Specific Component 9-CS-CDS / FORMATION DES : Improving and modernizing Under Implement IDA / 65770 Post Direct Selection Direct - National 45,000.00 0.00 2023-01-31 2023-01-20 2023-02-10 2023-04-16 2023-10-13 TELE OPERATEURS AUX TEC physical and statistical infra ation HNIQUES DE COLLECTE DE D structure ONNEES CI-INS COTE D'IVOIRE-32364 9-CS-INDV / Recrutement de Country-Specific Component quinze (15) consultants analy : Improving and modernizing Individual Consult Under Implement IDA / 65770 Post Open - National 180,000.00 0.00 2023-01-31 2022-12-27 2023-03-21 2023-04-11 2023-05-16 2023-11-12 stes pour la relecture et la va physical and statistical infra ant Selection ation lidation des rapports d’analy structure se thématique du Recensem ent de la Population 2021 CI-INS COTE D'IVOIRE-33224 Country-Specific Component 6-CS-INDV / Recrutement d'u : Improving and modernizing Individual Consult Open - Internationa Pending Impleme n Consultant pour la mise en IDA / 65770 Post 30,000.00 0.00 2023-01-31 2023-03-21 2023-04-11 2023-05-16 2023-11-12 physical and statistical infra ant Selection l ntation place d'un dispositif de collec structure te de données sur l'emploi CI-INS COTE D'IVOIRE-33225 Country-Specific Component 1-CS-INDV / Recrutement d’u : Improving and modernizing Individual Consult Under Implement n consultant individuel infor IDA / 65770 Post Open - National 40,000.00 0.00 2023-01-31 2022-12-27 2023-03-21 2023-04-11 2023-05-16 2023-11-12 physical and statistical infra ant Selection ation maticien spécialisé en traite structure ment informatique des recen sements et enquêtes CI-INS COTE D'IVOIRE-33225 Country-Specific Component 2-CS-INDV / Recrutement d’u : Improving and modernizing Individual Consult Pending Impleme n consultant individuel en ap IDA / 65770 Post Open - National 35,000.00 0.00 2023-03-01 2023-04-19 2023-05-10 2023-06-14 2023-12-11 physical and statistical infra ant Selection ntation pui au Calcul des Indices des structure valeurs unitaires (IVU) et des termes de l’échange (TE) CI-INS COTE D'IVOIRE-33225 Country-Specific Component 9-CS-INDV / Recrutement d'u : Improving and modernizing Individual Consult Pending Impleme IDA / 65770 Post Limited 12,000.00 0.00 2023-03-28 2023-04-02 2023-04-23 2023-05-28 2023-11-24 n Consultant formateur en Te physical and statistical infra ant Selection ntation chniques d'Analyses conjonct structure urelles CI-INS COTE D'IVOIRE-33226 Country-Specific Component 3-CS-INDV / Recrutement d'u : Improving and modernizing Individual Consult Pending Impleme IDA / 65770 Post Limited 10,000.00 0.00 2023-02-28 2023-03-05 2023-03-26 2023-04-30 2023-10-27 n agent d'anonymisation et l physical and statistical infra ant Selection ntation abellisation des données structure CI-INS COTE D'IVOIRE-33226 Country-Specific Component 5-CS-INDV / Recrutement d'u : Improving and modernizing Individual Consult Pending Impleme n consultant individuel pour IDA / 65770 Post Limited 15,000.00 0.00 2023-02-22 2023-02-27 2023-03-20 2023-04-24 2023-10-21 physical and statistical infra ant Selection ntation élaboreration d'un Projet de structure Décret portant tarification de s produits statistiques CI-INS COTE D'IVOIRE-33226 6-CS-INDV / Recrutement d'u Country-Specific Component n consultant individuel pour : Improving and modernizing Individual Consult Pending Impleme élaboreration d'un Projet de IDA / 65770 Post Limited 15,000.00 0.00 2023-02-28 2023-03-05 2023-03-26 2023-04-30 2023-10-27 physical and statistical infra ant Selection ntation décret fixant les modalités d structure e communication des fichiers administratifs aux administra tions du SSN CI-INS COTE D'IVOIRE-33226 7-CS-INDV / Recrutement d'u Country-Specific Component n consultant individuel pour l' : Improving and modernizing Individual Consult Pending Impleme élaboraration d'un Projet de IDA / 65770 Post Limited 15,000.00 0.00 2023-03-30 2023-04-04 2023-04-25 2023-05-30 2023-11-26 physical and statistical infra ant Selection ntation Décret fixant les modalités d’ structure attribution du visa pour les e nquêtes et recensements eff ectués par les organes du SS N CI-INS COTE D'IVOIRE-33226 9-CS-INDV / Recrutement de Country-Specific Component dix (10) Ingénieurs statisticie : Improving and modernizing Individual Consult Under Implement IDA / 65770 Post Open - National 142,000.00 0.00 2023-07-31 2023-01-06 2023-09-18 2023-10-09 2023-11-13 2024-05-11 ns économistes dans le cadre physical and statistical infra ant Selection ation de la seconde cohorte du pro structure gramme des jeunes professio nnels CI-INS COTE D'IVOIRE-33227 1-CS-INDV / Recrutement de Country-Specific Component dix (10) Ingénieurs des Trava : Improving and modernizing Individual Consult Under Implement IDA / 65770 Post Open - National 200,000.00 0.00 2023-07-31 2023-01-06 2023-09-18 2023-10-09 2023-11-13 2024-05-11 ux Statistiques (ITS) dans le physical and statistical infra ant Selection ation cadre de la seconde cohorte structure du programme des jeunes pr ofessionnels CI-INS COTE D'IVOIRE-33227 2-CS-INDV / Recrutement de Country-Specific Component quatorze adjoint technique d : Improving and modernizing Individual Consult Under Implement IDA / 65770 Post Open - National 142,000.00 0.00 2023-07-31 2023-01-06 2023-09-18 2023-10-09 2023-11-13 2024-05-11 e la statistique dans le cadre physical and statistical infra ant Selection ation de la seconde cohorte du pro structure gramme des jeunes professio nnels CI-INS COTE D'IVOIRE-33253 Country-Specific Component 0-CS-INDV / Recrutement d'u : Improving and modernizing Individual Consult Pending Impleme IDA / 65770 Post Limited 10,000.00 0.00 2023-02-28 2023-03-05 2023-03-26 2023-04-30 2023-10-27 n Consultant en appui à la pr physical and statistical infra ant Selection ntation oduction des comptes sectori structure els et satellites CI-INS COTE D'IVOIRE-33253 Country-Specific Component 3-CS-INDV / Recrutement d'u : Improving and modernizing Individual Consult Pending Impleme n Consultant Programmeur e IDA / 65770 Post Open - National 15,000.00 0.00 2023-02-28 2023-04-18 2023-05-09 2023-06-13 2023-12-10 physical and statistical infra ant Selection ntation n appui aux activités d'exten structure sion et d'amélioration des co mptes nationaux annuels CI-INS COTE D'IVOIRE-33741 Country-Specific Component 3-CS-INDV / RECRUTEMENT D : Improving and modernizing Individual Consult ES TRENTE-TROIS ANALYSTE IDA / 65770 Post Open - National 165,000.00 0.00 Under Review 2023-03-01 2023-02-20 2023-04-19 2023-05-10 2023-06-14 2023-12-11 physical and statistical infra ant Selection S (CONSULTANTS) POUR LA structure REALISATION DES MONOGRA PHIES REGIONALES Page 11 CI-INS COTE D'IVOIRE-33254 Country-Specific Component 6-CS-INDV / Recrutement d'u : Improving and modernizing Individual Consult Pending Impleme n consultant juriste pour la c IDA / 65770 Post Open - National 27,000.00 0.00 2023-05-31 2023-07-19 2023-08-09 2023-09-13 2024-03-11 physical and statistical infra ant Selection ntation onsolidation de la loi de 2013 structure et de la loi modifiée de 2020 relatives au SSN CI-INS COTE D'IVOIRE-33226 Country-Specific Component 0-CS-INDV / Recrutement de : Improving and modernizing Individual Consult Under Implement IDA / 65770 Post Open - National 61,000.00 0.00 2023-03-15 2023-03-10 2023-05-03 2023-05-24 2023-06-28 2023-12-25 trois consultants data scienti physical and statistical infra ant Selection ation st au profit de l'INS structure CI-INS COTE D'IVOIRE-33255 5-GO-RFQ / Recrutement de Country-Specific Component deux (2) consultants pour l’él : Improving and modernizing Individual Consult Pending Impleme aboration des feuilles de mis IDA / 65770 Post Open - National 31,000.00 0.00 2023-04-06 2023-05-25 2023-06-15 2023-07-20 2024-01-16 physical and statistical infra ant Selection ntation e en place du Système d’Info structure rmation Statistique (SIS) de d eux (2) Services Statistiques Ministériels (SSM) CI-INS COTE D'IVOIRE-33227 Country-Specific Component 3-CS-INDV / Recrutement de : Improving and modernizing Individual Consult Pending Impleme trois (03) démographes dans IDA / 65770 Post Open - National 66,000.00 0.00 2023-07-31 2023-09-18 2023-10-09 2023-11-13 2024-05-11 physical and statistical infra ant Selection ntation le cadre de la seconde cohort structure e du programme des jeunes professionnels CI-INS COTE D'IVOIRE-33254 Country-Specific Component 8-CS-INDV / Recrutement de : Improving and modernizing Individual Consult Pending Impleme deux (02) consultants pour l' IDA / 65770 Post Open - National 29,000.00 0.00 2023-04-13 2023-06-01 2023-06-22 2023-07-27 2024-01-23 physical and statistical infra ant Selection ntation animation d’un laboratoire d’ structure Innovation numérique en Sta tistique Appliquée CI-INS COTE D'IVOIRE-34926 Country-Specific Component 1-CS-INDV / Recrutement d'u : Improving and modernizing Individual Consult Under Implement n Ingénieur Informaticien spé IDA / 65770 Post Limited 20,000.00 0.00 2023-06-01 2023-06-22 2023-06-06 2023-06-27 2023-08-01 2024-01-28 physical and statistical infra ant Selection ation cialiste en réseau, sécurité et structure système d’information CI-INS COTE D'IVOIRE-35891 Regional component: Harmo 3-CS-CDS / Formation du cor nization, Data Collection, Qu Pending Impleme ps des agents enquêteurs au IDA / 65770 ality Improvement, Dissemin Post Direct Selection Direct - National 45,000.00 0.00 2023-06-01 2023-06-11 2023-08-15 2024-02-11 ntation x techniques de collecte de d ation and Use of Core Social onnées par l'ENSEA and Economic Statistics Page 12 18-MONTH PROCUREMENT PLAN Project information: Nigeria Rural Access And Agricultural Marketing Project (RAAMP) - P163353 Project Implementation Agencies: Federal Ministry of Agriculture and Rural Development and State Project Implementation Units (SPIUs) Date of the Procurement Plan: September 18, 2019 Period covered by this Procurement Plan: February 2019 to July 2020 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the Nigeria Public Procurement Act 2007, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. Not Applicable Procurement of Second-Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables. Not Applicable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: [15% is applicable for those contracts identified in the Procurement Plan tables]; Works: [ 7.5% is applicable for those contracts identified in the Procurement Plan tables] I. Threshold for Prior Review – Goods, Works, Non-Consulting Services and Consulting Services Prior-review Thresholds Thresholds for Procurement Methods High Substanti Moderate Low Risk Goods, IT & Non-Consulting Shortlist of National Procurement Type Risk al Risk Risk Works ($'000) ($'000) ($'000) ($'000) Services Consultants Request Request Engineering Open for for Open Open Open Consultin & Quotatio Quotatio 10,0 15,0 20,0 Internatio National internatio National g Constructio Works n or n or 5,000 00 00 00 nal or ICB or NCB National nal or ICB or NCB National Services n ($'000) ($'000) ($'000) ($'000) ($'000) Supervision Shopping Shopping ($'000) ($'000) ($'000) Goods, IT & Non- 2,0 4,0 6,0 Consulting Services 1,500 00 00 00 ≧ < ≦ ≧ < ≦ < ≦ Consultants 1,0 2,0 4,0 20,0 20,0 5,0 5,0 1 3 5 200 (Firms) 500 00 00 00 00 00 00 00 00 00 00 Post Review: All contracts not subject to prior review shall be subject to post review. Summary of the procurement packages for Goods, Works and Non-Consulting Services (Planned for the first 18 months after project effectiveness): Selecti Market on Evaluation Approa Review Metho Options Expected ch Prequal- Domestic Expected by Estimat d (Most date of Sr. Contract (Open- ification Preferenc date of Bank ed Cost (RFP, Advantageou bid/ No Description Nation (Yes/ e Contract (Prior/ (US$) RFB, s Bid, BAFO, proposal al/ No) (Yes/No) Signature Post) RFQ, Rated Criteria opening Limited DS etc.) etc.) etc.) Procurement of Air Conditioners 2 Limited Lowest March. 1 Post 24,600 RFQ No No Feb. 2020 Horse power Evaluated Cost 2020 (Split Unit) (Goods) Procurement of Steel File cabinets, Lowest March. 2 Spiral Binding Post 12,600 Limited RFQ Evaluated Cost No No Feb. 2020 2020 Machines and Consumables (Goods) Procurement of External hard disk + software packages Lowest March. 3 (licensed MS Post 12,300 Limited RFQ Evaluated Cost No No 2020 April. 2020 Office, Autocads, Antivirus, Converter etc) (Goods) Procurement of Laptops and Lowest March. 4 Post 100,000 Limited RFQ No No May. 2020 Tablets Evaluated Cost 2020 (Goods) Procurement Lowest March. 5 Post 22,400 Limited RFQ No No April. 2020 of Evaluated Cost 2020 Photocopying Machines (Goods) Medium Sized Lowest March. 6 Refrigerators Post 10,800 Limited RFQ Evaluated Cost No No 2020 April. 2020 (Goods) Procurement of Safety Equipment (Boots, Lowest 7 Post 39,000 Limited RFQ No No June. 2020 July, 2020 Helmets, Evaluated Cost Reflective Jackets etc.) (Goods) Construction Measuring Manual Wheel Lowest August. 8 Post 6,500 Limited RFQ No No July 2020 (Surveyor’s Evaluated Cost 2020 Wheel) (Goods) Roads Maintenance Equipment for Community based road maintenance (30 Nos tipping tricycles and other Open- 1,235,0 Lowest 9 equipment Post Nationa RFB No No Sept. 2020 Dec. 2020 00 Evaluated Cost such roads l signs and; cutlasses, wheelbarrows, hand rammer, digger, helmet, watering cans, reflective jacket, long shovel, nose cover, boots etc) (Goods) Procurement of Office Equipment, Printers, Open- Digital Lowest August. 10 Post 420,000 Nationa RFB No No June. 2020 Cameras & Evaluated Cost 2020 l Sundry Communicatio n devices (Goods) Purchase of Open- Project 2,940,0 Lowest March. 11 Prior Nationa RFB No No May. 2020 Vehicles 00 Evaluated Cost 2020 l (Goods) Server, Network System and other Open- Lowest equipment & Post 150,000 Nationa RFB Evaluated Cost No No Feb. 2020 May. 2020 accessories for l NiRTIMS and CosMos (Goods) Design and Construction of 200km of Rural Roads Open- 134,000 Rated Criteria (13 Prior Interna RFP No No Jun. 2020 Dec. 2020 ,000.00 and Cost Contracts of tional US$10.3 Million each) (Works) Construction/E stablishment Open – of Agro- 2,000,0 Lowest March. Post Nationa RFB No No July. 2021 Logistics 00 Evaluated Cost 2021 l centers/hubs at strategic locations (Multiple contracts) (Works) Construction /Rehabilitation of 10 Nos. Rural Bridges Open- 8,000,0 Lowest March. & Large Post Nationa RFB No No July. 2022 00 Evaluated Cost 2021 culverts (US$ l 0.6 M each Package) (Works) Local Community Group (LCG) and micro- enterprises maintenance Open- 14,000, Lowest of pilot roads Post Nationa RFB No No April. 2020 June.2020 000 Evaluated Cost (Multiple l Contracts in 13 States - US$ 0.002/year) (Works) II. Summary of the procurement packages for Consulting Services -Planned for the first 18 months after project effectiveness): Selection Market Method Review Approach Expected Expected Estimate (QCBS, Shortlisti Sr. by Bank (Open - date of bid/ date of Contract Description d Cost FBS, ng No (Prior/ International proposal Contract (US$) LCBS, (Yes/ No) Post) / National/ opening Signature QBS, CQS, etc.) DS etc.) Offshore & Onshore training and Workshops for Open- March. 1 the 13 states (Multiple Post 5,200,000 CQS No May. 2020 National 2020 contracts not to exceed US$ 0.1 M) (Consultancy) Consultancy Services for Detailed assessment, preliminary engineering design, ESIA, Procurement Support for Rural roads and Bridges; Road and 25,390,00 Open- 2 Bridge Supervision Prior QCBS Yes June. 2020 Nov. 2020 0 International Consultancy; Assessment of project security risk and mitigation (Multiple contracts spread in different locations) (Consultancy) Consultancy Services for design, procurement and supervision for Agro- Open- 3 logistics centers (Multiple Post 6,500,000 QCBS Yes Sep. 2020 Dec. 2020 International contracts spread in different locations) (Consultancy) Consultancy Services for the establishment of state Open- March. August. 4 road fund, and Post 5,665,000 QCBS Yes National 2020 2020 establishment of state rural access roads administration (Multiple contracts at 13 states) (Consultancy) Consultancy services on the development and operationalization of the Nigeria Rural Transport Infrastructure Management System (NiRTIMS) for sustainable road asset; Planning and Open- 5 Post 5,860,000 QCBS Yes Feb. 2020 July. 2020 implementation of the National routine maintenance system, spot improvement, periodic maintenance for rural roads. (Multiple contracts at 13 states) (Consultancy) Technical assistance consultancy services for the provision of technical advice (TA) to enhance the performance of agro- logistics centers (to ensure effective utilization of the facilities at the agro- Open- National March. 6 logistics centers); Post 4,975,000 QCBS Yes July. 2020 provision of TA and 2020 implements to farm level post-harvest agro-logistics activities and enhance the engagement of women and unemployed youth. (Multiple contracts at 13 states) (Consultancy) Consultancy services support for coordination of Open- 7 Post 2,442,000 CQS No Feb. 2020 April. 2020 project implementation at National Federal and State Levels (Multiple contracts at 13 states) (Consultancy) Consultancy services on Impact Evaluation, Baseline Data Collection, Comprehensive Technical Audit, Consultancy support for the development and Open- March. 8 operationalization of the Post 5,325,000 QCBS Yes July.2020 National 2020 smartphone-based construction site monitoring system (CoSMoS) (Multiple contracts at 13 states) (Consultancy) Consultancy support for the development and monitoring of Grievance Redress Mechanism and Gender-Based Violence; Development of road safety manual and training Open- 9 Post 1,843,000 CQS No April.2020 June. 2020 at the state level; National establishment/strengtheni ng the state traffic management agencies; road safety audit. (Multiple contracts at 13 states) (Consultancy) Appendix 1 Letter of Acceptance of the World Bank’s Anti-Corruption Guidelines and Sanctions Framework Date: Invitation of Bids/Proposals No.__________ To: ___________________________________________________________________________ We, along with our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not) consultants and personnel, acknowledge and agree to abide by the World Bank’s policy regarding Fraud and Corruption (corrupt, fraudulent, collusive, coercive, and obstructive practices), as set out and defined in the World Bank’s Anti-Corruption Guidelines1 in connection with the procurement and execution of the contract (in case of award), including any amendments thereto. We declare and warrant that we, along our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not), consultants and personnel, , are not subject to, and are not controlled by any entity or individual that is subject to, a temporary suspension, early temporary suspension, or debarment imposed by a member of the World Bank Group, including, inter alia, a cross-debarment imposed by the World Bank Group as agreed with other international financial institutions (including multilateral development banks), or through the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement. Further, we are not ineligible under the laws or official regulations of [Insert name of Employer as per bidding document] or pursuant to a decision of the United Nations Security Council. We confirm our understanding of the consequences of not complying with the World Bank’s Anti-Corruption Guidelines, which may include the following: a. rejection of our Proposal/Bid for award of contract; b. in the case of award, termination of the contract, without prejudice to any other remedy for breach of contract; and c. sanctions, pursuant to the Bank’s Anti-corruption Guidelines and in accordance with its prevailing sanctions policies and procedures as set forth in the Bank’s Sanctions Framework. This may include a 1Guidelineson Preventing and Combating Fraud and Corruption in Projects Financed by International Bank for Reconstruction and Development Loans and the International Development Agency Credits and Grants, dated October 15, 2006, and revised in January 2011 and July 2016, as they may be revised from time to time. public declaration of ineligibility, either indefinitely or for a stated period of time, (i) to be awarded or otherwise benefit from a Bank-financed contract, financially or in any other manner;2 (ii) to be a nominated3 sub-contractor, consultant, manufacturer or supplier, or service provider of an otherwise eligible firm being awarded a Bank-financed contract; and (iii) to receive the proceeds of any loan made by the Bank or otherwise to participate further in the preparation or implementation of any Bank-financed project. We understand that we may be declared ineligible as set out above upon: a. completion of World Bank Group sanctions proceedings according to its prevailing sanctions procedures; b. cross-debarment as agreed with other international financial institutions (including multilateral development banks); c. the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement; or d. temporary suspension or early temporary suspension in connection with an ongoing World Bank Group sanctions proceeding. For avoidance of doubt, the foregoing effects of ineligibility do not extend to a sanctioned firm’s or individual’s execution of its ongoing Bank-financed contracts (or its ongoing sub-agreements under such contracts) that are not the subject of a material modification, as determined by the Bank. We shall permit, and shall cause our sub-contractors, sub-consultants, agents (whether declared or not), personnel, consultants, service providers or suppliers, to permit the Bank to inspect4 all accounts, records, 2 For the avoidance of doubt, a sanctioned party’s ineligibility to be awarded a contract shall include, without limitation, (i) applying for pre-qualification, expressing interest in a consultancy, and bidding, either directly or as a nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider, in respect of such contract, and (ii) entering into an addendum or amendment introducing a material modification to any existing contract. 3 A nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider (different names are used depending on the particular bidding document) is one which has been: (i) included by the bidder in its pre-qualification application or bid because it brings specific and critical experience and know-how that allow the bidder to meet the qualification requirements for the particular bid; or (ii) appointed by the Borrower. 4 Inspections in this context are usually investigative (i.e., forensic) in nature: they involve fact-finding activities undertaken by the Bank or persons appointed by the Bank to address specific matters related to investigations/audits, such as evaluating the veracity of an allegation of possible Fraud and Corruption, through the appropriate mechanisms. Such activity includes but is not and other documents relating to the procurement process and/or contract execution (in the case of award), and to have them audited by auditors appointed by the Bank. We agree to preserve all accounts, records, and other documents (whether in hard copy or electronic format) related to the procurement and execution of the contract. Name of the Bidder/Consultant: Name of the person duly authorized to sign the Bid/Proposal on behalf of the Bidder/Consultant: Title of the person signing the Letter: limited to accessing and examining a firm's or individual's financial records and information, and making copies thereof as relevant; accessing and examining any other documents, data, and information (whether in hard copy or electronic format) deemed relevant for the investigation/audit, and making copies thereof as relevant; interviewing staff and other relevant individuals; performing physical inspections and site visits; and obtaining third-party verification of information. PROCUREMENT Nigeria : Nigeria Rural Access and Agricultural Marketing Project PLAN General Information Country: Nigeria 2023-02-10 Bank’s Approval Date of the Original Procurement Plan: 2023-06-03 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P163353 GPN Date: Project Name: Nigeria Rural Access and Agricultural Marketing Project Loan / Credit No: IDA / 65190 Ekiti RAAMP Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Request for Bids - NG-EKITI RAAMP-331057-CW Component B. Asset Manage Single Stage - One E Small Works SPD Pending Imp 2024-06-2 -RFB / Construction of 40KM IDA / 65190 ment, Agro-logistics Perform Post Request for Bids Open - National 6,400,000.00 0.00 2023-09-06 2023-09-11 2023-10-23 2023-11-22 2023-12-27 nvelope (1 envelope proce lementation 4 Rural Roads Upgrading ance Enhancement and Sect ss) or Reform NG-EKITI RAAMP-331060-CW Component B. Asset Manage Request for Bids - -RFB / Construction of 100 Li ment, Agro-logistics Perform Single Stage - One E Small Works SPD Pending Imp 2024-06-2 IDA / 65190 Post Request for Bids Open - National 1,200,000.00 0.00 2023-09-05 2023-09-10 2023-10-22 2023-11-21 2023-12-26 near meters cross Drainage ance Enhancement and Sect nvelope (1 envelope proce lementation 3 Structures(Culverts/Bridges) or Reform ss) on rural Roads Request for Bids - NG-EKITI RAAMP-336060-CW Component B. Asset Manage Single Stage - One E Small Works SPD Pending Imp 2024-05-0 -RFB / Physical improvement IDA / 65190 ment, Agro-logistics Perform Post Request for Bids Open - National 2,000,000.00 0.00 2023-07-21 2023-07-26 2023-09-06 2023-10-06 2023-11-10 nvelope (1 envelope proce lementation 8 of Agro logistics centres ance Enhancement and Sect ss) or Reform Request for Bids - NG-EKITI RAAMP-331058-CW Component B. Asset Manage Single Stage - One E Small Works SPD Pending Imp 2024-07-0 -RFB / Construction of Backl IDA / 65190 ment, Agro-logistics Perform Post Request for Bids Open - National 4,000,000.00 0.00 2023-09-13 2023-09-23 2023-11-04 2023-12-04 2024-01-08 nvelope (1 envelope proce lementation 6 og Maintenance/rehabilitatio ance Enhancement and Sect ss) n of Roads or Reform NG-EKITI RAAMP-331059-CW Request for Bids - -RFB / Spot Improvement of Component A. Improvement Single Stage - One E Small Works SPD Pending Imp 2024-06-2 Rural Roads and Constructio IDA / 65190 of Rural Access and Trading Post Request for Bids Open - National 7,875,000.00 0.00 2023-09-05 2023-09-10 2023-10-22 2023-11-21 2023-12-26 nvelope (1 envelope proce lementation 3 n of linear meters Cross Drai Infrastructure ss) nage Structures on Rural Roa ds GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NG-EKITI RAAMP-331062-GO Component B. Asset Manage Request for Quota Single Stage - One E Pending Impl -RFQ / Procurement of 2Nos IDA / 65190 ment, Agro-logistics Perform Post Limited 170,000.00 0.00 2023-02-27 2023-04-24 2023-10-21 tions nvelope ementation Operating Project Vehicle ance Enhancement and Sect or Reform NG-EKITI RAAMP-331084-GO -RFQ / Procurement of Lapto ps, Desktops, Printers/Fax, U Component C. Institutional D Request for Quota Single Stage - One E Under Imple PS and peripherals, Heavy du IDA / 65190 evelopment, Project Manage Post Limited 80,000.00 0.00 2023-01-30 2023-03-27 2023-09-23 tions nvelope mentation ty photocopiers,scanners, pr ment and Risk Mitigation ojectors,internet installation, Video Camera, photo Printer, consumables etc NG-EKITI RAAMP-331151-GO Component C. Institutional D Request for Quota Single Stage - One E Pending Impl -RFQ / Procurement of a 30K IDA / 65190 evelopment, Project Manage Post Limited 40,000.00 0.00 2023-04-08 2023-06-03 2023-11-30 tions nvelope ementation VA Generator ment and Risk Mitigation NG-EKITI RAAMP-331245-GO Component C. Institutional D Request for Quota Single Stage - One E Pending Impl -RFQ / Procurement of Data C IDA / 65190 evelopment, Project Manage Post Limited 10,000.00 0.00 2023-03-11 2023-05-06 2023-11-02 tions nvelope ementation ollection Gadgets for NIRTIM ment and Risk Mitigation S and CoSMos NG-EKITI RAAMP-332720-GO -RFQ / Procurement of Safeg uard equipment(PPEs, First ai Component C. Institutional D Request for Quota Single Stage - One E Pending Impl d kits, Environmental Monitor IDA / 65190 evelopment, Project Manage Post Limited 20,000.00 0.00 2023-03-13 2023-05-08 2023-11-04 tions nvelope ementation ing and tracking Equipment, i ment and Risk Mitigation n-situ air quality kits, noise m eter, Ph meter, Caution tapes , Measuring tapes etc NG-EKITI RAAMP-331080-GO -RFQ / Procurement of Office Component C. Institutional D Request for Quota Single Stage - One E Pending Impl Furniture and Equipment, Shr IDA / 65190 evelopment, Project Manage Post Limited 50,000.00 0.00 2023-03-01 2023-04-26 2023-10-23 tions nvelope ementation edder Machines, Licence Soft ment and Risk Mitigation ware and Official Website NG-EKITI RAAMP-366086-GO Component C. Institutional D Request for Quota Single Stage - One E Pending Impl -RFQ / Procurement of Promo IDA / 65190 evelopment, Project Manage Post Limited 20,000.00 0.00 2023-07-28 2023-09-22 2024-03-20 tions nvelope ementation tional Materials ment and Risk Mitigation NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NG-EKITI RAAMP-330902-CS- CQS / Consultancy Services f Component B. Asset Manage or design and Supervision of ment, Agro-logistics Perform Consultant Qualifi Under Implement IDA / 65190 Post Open - National 300,000.00 0.00 2023-03-06 2023-03-22 2023-03-27 2023-05-10 2023-06-09 2023-07-14 2024-01-10 Rural Roads Spot Improveme ance Enhancement and Sect cation Selection ation nt and Construction of Linea or Reform r meters Cross Drainage Stru ctures on Rural Roads Page 1 NG-EKITI RAAMP-330921-CS- QCBS / Consultancy Service f Component A. Improvement Quality And Cost- Under Implement or Design and Supervision of IDA / 65190 of Rural Access and Trading Post Open - National 400,000.00 0.00 2023-02-13 2023-03-22 2023-03-06 2023-04-19 2023-05-17 2023-06-16 2023-07-21 2023-08-25 2024-08-24 Based Selection ation 2-3Nos Agro-Logistics centre Infrastructure s Physical improvement NG-EKITI RAAMP-330811-CS- Component A. Improvement QCBS / Consultancy service f Quality And Cost- Open - Internationa Under Implement IDA / 65190 of Rural Access and Trading Post 450,000.00 0.00 2023-01-30 2023-03-22 2023-02-20 2023-04-05 2023-05-03 2023-06-02 2023-07-07 2023-08-11 2024-08-10 or the design and Supervisio Based Selection l ation Infrastructure n of Road upgrading NG-EKITI RAAMP-336058-CS- Component B. Asset Manage CQS / Consultancy Service fo ment, Agro-logistics Perform Consultant Qualifi Under Implement IDA / 65190 Post Open - National 300,000.00 0.00 2023-04-17 2023-03-22 2023-05-08 2023-04-27 2023-06-21 2023-07-21 2023-08-25 2024-02-21 r Design and Supervision of ance Enhancement and Sect cation Selection ation Rural Roads Backlog Mainten or Reform ance/Rehabilitation INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NG-EKITI RAAMP-331054-CS- Component C. Institutional D Individual Consult Under Implement INDV / Consultancy Service f IDA / 65190 evelopment, Project Manage Post Limited 20,000.00 0.00 2023-02-13 2023-03-08 2023-02-18 2023-03-11 2023-04-15 2024-04-14 ant Selection ation or the engagement of a Secu ment and Risk Mitigation rity Specialist NG-EKITI RAAMP-331055-CS- Component C. Institutional D INDV / Consultancy Services f Individual Consult Pending Impleme IDA / 65190 evelopment, Project Manage Post Limited 20,000.00 0.00 2023-06-14 2023-06-19 2023-07-10 2023-08-14 2024-02-10 or the Engagement of a Geog ant Selection ntation ment and Risk Mitigation raphic Information System S pecialist NG-EKITI RAAMP-331053-CS- Component C. Institutional D INDV / Consultancy Services f Individual Consult Under Implement IDA / 65190 evelopment, Project Manage Post Limited 20,000.00 0.00 2023-04-04 2023-04-09 2023-04-30 2023-06-04 2024-05-13 or the Engagement of an Infr ant Selection ation ment and Risk Mitigation astructure Engineering Speci alist NG-EKITI RAAMP-361869-CS- Component C. Institutional D INDV / Consultancy Service f Individual Consult Under Implement IDA / 65190 evelopment, Project Manage Post Limited 20,000.00 0.00 2023-06-19 2023-06-24 2023-07-15 2023-08-19 2024-02-15 or the Engagement of a Tec ant Selection ation ment and Risk Mitigation hnical Assistance(TA) for Envi ronmental Safeguard NG-EKITI RAAMP-366291-CS- Component C. Institutional D INDV / Consultancy Service f Individual Consult Pending Impleme IDA / 65190 evelopment, Project Manage Post Limited 20,000.00 0.00 2023-07-28 2023-08-02 2023-08-23 2023-09-27 2024-03-25 or the Engagement of a Proc ant Selection ntation ment and Risk Mitigation urement (TA)Specialist NG-EKITI RAAMP-366466-CS- Component C. Institutional D INDV / Consultancy Service f Individual Consult Pending Impleme IDA / 65190 evelopment, Project Manage Post Limited 20,000.00 0.00 2023-08-03 2023-08-08 2023-08-29 2023-10-03 2024-03-31 or the Engagement of a Soci ant Selection ntation ment and Risk Mitigation al Safeguard (TA)Specialist NG-EKITI RAAMP-331056-CS- Component C. Institutional D Individual Consult Pending Impleme INDV / Consultancy Services f IDA / 65190 evelopment, Project Manage Post Limited 20,000.00 0.00 2023-10-19 2023-10-24 2023-11-14 2023-12-19 2024-06-16 ant Selection ntation or the engagement of a Data ment and Risk Mitigation Entry Specialist Page 2 PROCUREMENT PLAN (Textual Part) Project information: Country: Bolivia Project name: Bolivia Urban Resilience Project P-number: P165861 Project Implementation Agencies: Municipality of Santa Cruz (GAMSC) and Municipality of La Paz (GAMLP) Date of the Procurement Plan: September 09, 2021 Period covered by this Procurement Plan: 18 months Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers”, dated July 2016, revised November 2017 and August 2018” (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures acceptable for the Bank by the may be used. When the Borrower uses its own national open competitive procurement arrangements, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. a. open advertising of the procurement opportunity at the national level; b. the procurement is open to eligible firms from any country; c. the request for bids/request for proposals document shall require that Bidders/Proposers submitting Bids/Proposals present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti- Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights; d. contracts with an appropriate allocation of responsibilities, risks, and liabilities; e. publication of contract award information; f. rights for the Bank to review procurement documentation and activities; g. an effective complaints mechanism; and h. maintenance of records of the Procurement Process. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. Not Applicable. Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations: Not Applicable. Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works): Not Applicable. Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations may be Applicable. Other Relevant Procurement Information. Procurement activities will be undertaken by GAMSC for Part 1 and 3.1; and by the GAMLP for Parts 2 and 3.2. Procurement of Goods, Works and Non-Consulting Services. According the Project Procurement Strategy for Development (PPSD), the open international competitive bidding approach should be applied when the Procurement Plan establishes it, while for small contracts the open national competitive bidding approach is supported by the availability of bidders in the local market. For Works and Gods the Borrower is able to specify detailed requirements to which bidders respond by offering bids; the Request for Bids or the Request for Quotations would be the selection methods for these contracts. Procurement of Consulting Services. Technical Assistance, designs, supervision services, and other studies: Considering that these will be small and medium magnitude contracts, the suitable market approach would be an open competition in the international or national market or direct market approach, while the Quality-Cost- Based Selection or Direct Selection (when a sole firm with needed capabilities is identified and justified) would be the selection methods. Project implementation support personnel. Individuals contracted to support project implementation (project staff), other than individual consulting positions identified in the Legal Agreement, may be selected by the Borrower according to their personnel hiring procedures for such activities, as reviewed and found acceptable by the Bank and described in the POMs. Individual consultants. Individual consultants will be selected for an assignment for which: (i) a team of experts is not required; (ii) no additional office support is required; and (iii) the experience and qualifications of the individual are of paramount requirement. The evaluation shall be based on the relevant qualifications and experience of the individual consultant in accordance with provision of paragraphs 7.34 to 7.39 of the Procurement Regulations. PROCUREMENT Bolivia : Bolivia Urban Resilience PLAN General Information Country: Bolivia 2021-09-09 Bank’s Approval Date of the Original Procurement Plan: 2023-06-02 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P165861 GPN Date: 2021-08-12 Project Name: Bolivia Urban Resilience Loan / Credit No: IDA / 65170 Municipal Autonomous Government of Santa Cruz Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned SMOP LPI 001 2021 / Obras Request for Bids - de construccion del canal em Resilient Infrastructure and Open - Internationa Single Stage - One E Small Works SPD 22,188,412.0 2024-10-0 isario 8vo Anillo suroeste y m IDA / 65170 Urban Upgrading in Santa Cr Prior Request for Bids 0.00 Canceled 2021-11-15 2021-11-20 2022-01-04 2022-02-03 2022-03-10 l nvelope (1 envelope proce 0 3 ejoramiento del espacio publi uz ss) co. Incluye salvaguardas soci ales y ambientales SMOP LPI 002-2022 / Constr Request for Bids - Resilient Infrastructure and ucción Canal Emisario 8vo An Open - Internationa Single Stage - One E Small Works SPD 23,294,667.3 2025-01-0 IDA / 65170 Urban Upgrading in Santa Cr Prior Request for Bids 0.00 Signed 2022-02-14 2022-04-08 2022-02-19 2022-06-03 2022-04-05 2022-06-13 2022-05-05 2022-10-13 2022-06-09 illo Sur Oeste y Mejoramiento l nvelope (1 envelope proce 4 2 uz de Espacio Público ss) National Procure SMOP UT COT 001/2022 / Ma ment Document - Request for Quota Single Stage - One E Under Imple 2022-12-2 ntenimiento de Espacio Públi IDA / 65170 Project Management Post Open - National 1 Envelope proce 120,000.00 0.00 2022-09-27 2022-11-22 tions nvelope mentation 2 co con Urbanismo Táctico en ss (Non Bank-SPD la Zona Central ) SES COT 001 2022 / Obras d Resilient Infrastructure and Request for Quota Request for Quota Single Stage - One E 2022-10-1 e Regeneracion Urbana. Pilot IDA / 65170 Urban Upgrading in Santa Cr Post Open - National tions (Non Bank-S 120,000.00 0.00 Canceled 2022-02-20 2022-04-17 tions nvelope 4 o de Urbanismo Tactico uz PD) GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual DPI COT 003 2021 / Utiles d Request for Quota Single Stage - One E IDA / 65170 Project Management Post Open - National 10,000.00 0.00 Canceled 2021-10-23 2021-12-18 2022-02-01 e escritorio tions nvelope DPI COT 002 2021 / Adquisic Request for Quota Single Stage - One E IDA / 65170 Project Management Post Open - National 16,961.00 0.00 Canceled 2021-10-23 2021-12-18 2022-02-01 ión de Muebles y Enseres tions nvelope DPI COT 001 2021 / Adquisci on de equipos de computacio Request for Quota Single Stage - One E IDA / 65170 Project Management Post Open - National 45,950.00 0.00 Canceled 2021-10-23 2021-12-23 2022-02-06 n, scanner, fotocopiadora, im tions nvelope presoras y proyectores DPI COT 002 2022 / Adquisic ión de: Computadoras de esc ritorio, Impresora de plotter, Single Stage - One E IDA / 65170 Project Management Post Request for Bids Open - National 82,492.71 0.00 Completed 2022-06-10 2022-07-13 2022-06-25 2022-07-13 2022-07-16 2022-08-11 2022-08-03 2022-08-29 2022-09-29 2022-10-29 2022-11-22 Computadoras portátiles, Pro nvelope yector multimedia, fotocopia doras, Impresoras de inyecci ón de tinta. DPI COT 001 2022 / Adquisic Request for Quota Single Stage - One E IDA / 65170 Project Management Post Open - National 32,912.39 0.00 Completed 2022-07-22 2022-09-22 2022-11-06 2022-12-12 ión de Equipos de Oficina y M tions nvelope uebles DPI COT 006 2021 / Adquisi Resilient Infrastructure and Request for Quota Single Stage - One E IDA / 65170 Post Open - National 10,500.00 0.00 Canceled 2021-11-27 2022-01-22 2022-03-08 cion de 1 Dron Urban Upgrading in Santa Cr tions nvelope uz DPI COT 004 2021 / Adquisic ion de Equipos de comunicac Request for Quota Single Stage - One E IDA / 65170 Project Management Post Open - National 2,620.00 0.00 Canceled 2021-10-30 2021-12-25 2022-02-08 ión, GPS, distanciador, radios tions nvelope walkie talkie, telefonos inala mbricos DPI SDO BS 001 2022 / Adqu isicion de Equipos de comuni Single Stage - One E IDA / 65170 Project Management Post Request for Bids Open - National 51,841.11 0.00 Completed 2022-08-15 2022-10-11 2022-08-30 2022-09-20 2022-11-10 2022-10-08 2022-11-06 2022-11-07 2022-12-07 2023-02-10 cación, Mobile phones, Digita nvelope l cameras, Televisions y Audi o visual technology DPI SDO BS 002 2022 / Adqu Single Stage - One E isiciones de Dos Vehiculos, u IDA / 65170 Project Management Post Request for Bids Open - National 66,427.76 0.00 Canceled 2022-09-05 2022-09-10 2022-10-01 2022-10-19 2022-11-17 2022-12-17 nvelope na camioneta y una camione ta DPI LPN 001 2021 / Adquisic Single Stage - One E ion de 2 Vehiculos 1 Vagonet IDA / 65170 Project Management Post Request for Bids Open - National 75,802.00 0.00 Canceled 2021-11-01 2021-11-06 2021-12-04 2022-01-03 2022-02-07 2022-03-24 nvelope a 4x4 y 1 Camioneta 4x4 DPI COT 003 2022 / Calzado Request for Quota Single Stage - One E IDA / 65170 Project Management Post Open - National 7,653.00 0.00 Canceled 2022-02-06 2022-04-08 2022-05-23 s tions nvelope DPI COT 002 2022 / Prendas Request for Quota Single Stage - One E IDA / 65170 Project Management Post Open - National 12,755.00 0.00 Canceled 2022-02-06 2022-04-03 2022-05-18 de vestir tions nvelope DPI-SD-001 / Adquisicion de Under Imple IDA / 65170 Project Management Post Direct Selection Direct - National 7,200.00 0.00 2022-12-19 2022-12-16 2022-12-24 2023-05-09 2023-01-28 2023-02-27 un Software Contable mentation DPI COT 003 2022 / ADQUISI Request for Quota Single Stage - One E IDA / 65170 Project Management Post Open - National 9,397.00 0.00 Canceled 2022-09-17 2022-11-12 2022-12-12 CIÓN DE UTILES DE ESCRITO tions nvelope RIO Y PAPEL DPI SDO BS 003 / Adquisició Single Stage - One E Pending Impl IDA / 65170 Project Management Post Request for Bids Open - National 182,653.00 0.00 2023-06-07 2023-06-12 2023-07-24 2023-08-23 2023-09-27 2023-11-26 n de (4) Cuatro Vehículos livi nvelope ementation anos DPI COT 005 / Adquisición d Request for Quota Single Stage - One E Pending Impl IDA / 65170 Project Management Post Open - National 19,000.00 0.00 2023-04-14 2023-06-22 2023-07-07 e Útiles de Escritorio y Papel tions nvelope ementation DPI COT 004 / Adquisición D Request for Quota Single Stage - One E Pending Impl e Prendas De Vestir y Calzad IDA / 65170 Project Management Post Open - National 4,500.00 0.00 2023-10-07 2023-12-16 2023-12-31 tions nvelope ementation os de seguridad Page 1 NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual DPI COT 005 2021 / Seguro Request for Quota Single Stage - One E IDA / 65170 Project Management Post Open - National 3,207.00 0.00 Canceled 2021-11-20 2022-01-15 2025-06-30 automotor tions nvelope DPI COT 001 2022 / Publicid Request for Quota Single Stage - One E IDA / 65170 Project Management Post Open - National 14,577.00 0.00 Canceled 2022-02-06 2022-04-03 2025-06-30 ad tions nvelope CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SMOP CONS 002 2021 / Serv Resilient Infrastructure and icios Consultoria especializad Quality And Cost- IDA / 65170 Urban Upgrading in Santa Cr Post Open - National 174,710.00 0.00 Canceled 2021-11-15 2021-12-06 2022-01-19 2022-02-16 2022-03-18 2022-04-22 2022-05-27 2024-09-30 a fiscalizacion de obras Sec. Based Selection uz Mcpal. Obras Publicas SMOP CONS 001 2021 / Serv icios Consultoría especializad a en Supervisión de las Obra Resilient Infrastructure and Quality And Cost- Open - Internationa s Civiles Ambientales y Social IDA / 65170 Urban Upgrading in Santa Cr Post 926,023.00 0.00 Canceled 2021-11-01 2021-11-11 2021-11-22 2022-01-05 2022-02-19 2022-03-21 2022-04-25 2022-05-30 2024-10-17 Based Selection l es. uz Obras de Construcción del Ca nal Emisario 8vo. Anillo sur-o este y mejoramiento del esp acio público SMOP LPI 001-2022 / Servici os Consultoría especializada para Supervisión de las Obra Resilient Infrastructure and Quality And Cost- Open - Internationa s Civiles, Ambientales y Soci IDA / 65170 Urban Upgrading in Santa Cr Post 722,568.75 0.00 Signed 2022-02-08 2022-02-10 2022-03-01 2022-03-28 2022-04-14 2022-06-06 2022-05-12 2022-07-20 2022-06-11 2022-08-31 2022-07-16 2022-09-30 2022-08-20 2023-08-20 Based Selection l ales. Construcción del Canal uz Emisario 8vo. Anillo sur-oeste y mejoramiento del espacio p úblico DPI CP 002 2022 / Consultorí a por producto para la elabor ación a diseño final del estud Quality And Cost- IDA / 65170 Project Management Post Open - National 150,000.00 0.00 Canceled 2022-09-26 2022-12-13 2022-10-17 2022-11-30 2022-12-28 2023-01-27 2023-03-03 2023-04-07 2024-04-06 io de Diseño Técnico de Prein Based Selection versión del proyecto Constru cción de Obra de Regeneraci ón Urbana Zona Central DPI CP 001 2022 / Consultorí a por producto para la elabor ación del Plan Integral de Ma Quality And Cost- Open - Internationa nejo de Parques Urbanos - PE IDA / 65170 Project Management Post 200,000.00 0.00 Canceled 2022-08-31 2022-12-13 2022-09-21 2022-11-04 2022-12-16 2023-01-15 2023-02-19 2023-03-26 2024-03-25 Based Selection l M: Proyecto del Parque Lineal Ecológico Metropolitano de S anta Cruz y su Plan Integral d e Manejo SMTT CP 001-2022 / Consult oría para la elaboración del P Quality And Cost- Open - Internationa Under Implement lan Maestro de Transporte N IDA / 65170 Project Management Post 500,000.00 0.00 2022-09-28 2022-12-29 2022-10-19 2023-01-24 2022-11-19 2023-03-30 2022-12-30 2023-05-25 2023-01-20 2023-02-24 2023-03-31 2024-03-30 Based Selection l ation o Motorizado y Proyecto de la Red de Ciclovías Ecológicas, Sustentables y Resilientes DPI SCC 001 / Consultoría pa Consultant Qualifi Under Implement ra el diseño e implementació IDA / 65170 Project Management Post Limited 58,000.00 0.00 2022-11-30 2022-12-01 2022-12-14 2022-12-21 2023-01-13 2023-02-11 2023-05-12 cation Selection ation n de Estrategia Comunicacio nal DPI CONS 002 / Consultoria para la Elaboracion del Plan I Quality And Cost- Open - Internationa Under Implement ntegral de Manejo de Parque IDA / 65170 Project Management Post 200,000.00 0.00 2023-01-10 2023-01-18 2023-01-31 2023-02-24 2023-03-16 2023-04-30 2023-05-30 2023-07-04 2023-08-08 2024-08-02 Based Selection l ation s Urbanos - PEM, Direccion d e Planificacion Integral, SEMP LAD DPI CONS 004 / Servicio de c onsultoría para auditoría fina nciera por el periodo compre Least Cost Selecti Under Implement ndido entre el 10 de marzo al IDA / 65170 Project Management Post Open - National 100,000.00 0.00 2023-03-27 2023-03-27 2023-03-27 2023-04-04 2023-05-17 2023-06-06 2023-07-10 2023-08-10 2024-02-26 on ation 31 de diciembre del 2021; 1º de enero al 31 de diciembre de 2022 y 1º de enero al 31 de diciembre de 2023 DPI CONS 001 2022 / Audito Least Cost Selecti IDA / 65170 Project Management Post Open - National 100,000.00 0.00 Canceled 2022-12-15 2022-09-12 2023-01-05 2023-02-18 2023-03-18 2023-04-17 2023-05-22 2023-06-26 2023-12-23 ria Externa Gestiones 2021 - on 2022 DPI CONS 003 / Consultoria para la Elaboracion de diseño final de Estudio Diseño Técni Quality And Cost- co de Preinversión del proyec IDA / 65170 Project Management Post Open - National 150,000.00 0.00 Under Review 2023-06-02 2023-06-27 2023-06-23 2023-08-06 2023-09-17 2023-10-17 2023-11-21 2023-12-26 2024-03-25 Based Selection to Construccion de la Obra R egeneracion Urbana Zona Ce ntral, Direccion de Planificaci on Integral, SEMPLAD INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual DPI CI 001 2021 / Especialist Individual Consult IDA / 65170 Project Management Post Open 116,790.00 0.00 Canceled 2021-10-01 2021-09-15 2021-11-19 2021-12-10 2022-01-14 2025-06-30 a Social ant Selection DPI CI 002 2021 / Especialist Individual Consult IDA / 65170 Project Management Post Open 116,790.00 0.00 Canceled 2021-10-01 2021-09-15 2021-11-19 2021-12-10 2022-01-14 2025-06-30 a Ambiental ant Selection DPI CI 003 2021 / Especialist Individual Consult IDA / 65170 Project Management Post Open 116,790.00 0.00 Canceled 2021-10-01 2021-09-15 2021-11-19 2021-12-10 2022-01-14 2025-06-30 a en Monitoreo ant Selection DPI CI 004 2021 / Especialist Individual Consult IDA / 65170 Project Management Post Open 116,790.00 0.00 Canceled 2021-10-01 2021-09-15 2021-11-19 2021-12-10 2022-01-14 2025-06-30 a Financiero ant Selection DPI CI 005 2021 / Especialist Individual Consult IDA / 65170 Project Management Prior Open 116,790.00 0.00 Canceled 2021-10-01 2021-09-20 2021-11-19 2021-12-10 2022-01-14 2025-06-30 a en Adquisiciones ant Selection Page 2 DPI CI 006 2021 / Especialist Individual Consult IDA / 65170 Project Management Post Open 116,790.00 0.00 Canceled 2021-10-01 2021-09-15 2021-11-19 2021-12-10 2022-01-14 2025-06-30 a Legal ant Selection DPI CI 007 2021 / Especialist Individual Consult IDA / 65170 Project Management Post Open 116,790.00 0.00 Canceled 2021-10-01 2021-09-15 2021-11-19 2021-12-10 2022-01-14 2025-06-30 a Comunicador ant Selection DPI CI 008 2021 / Especialist Individual Consult IDA / 65170 Project Management Post Open 116,790.00 0.00 Canceled 2021-10-01 2021-09-15 2021-11-19 2021-12-10 2022-01-14 2025-06-30 a Infraestructura Resiliente ant Selection DPI CI 009 2021 / Profesiona Individual Consult IDA / 65170 Project Management Post Open 63,289.00 0.00 Canceled 2021-10-01 2021-09-15 2021-11-19 2021-12-10 2022-01-14 2025-06-30 l A Asistente Administrativo ant Selection Individual Consult DPI CI 010 2021 / Chofer A IDA / 65170 Project Management Post Open 37,854.00 0.00 Canceled 2021-10-01 2021-09-15 2021-11-19 2021-12-10 2022-01-14 2025-06-30 ant Selection DPI CI 001 2022 / Profesiona Individual Consult IDA / 65170 Project Management Post Open 63,289.00 0.00 Canceled 2022-02-01 2022-03-22 2022-04-12 2022-05-17 2025-06-30 l A Contador Auditor Analista ant Selection Contable DPI CI 002 2022 / Profesiona Individual Consult IDA / 65170 Project Management Post Open 63,289.00 0.00 Canceled 2022-02-01 2022-03-22 2022-04-12 2022-05-17 2025-06-30 l A Analista Presupuestario ant Selection DPI CI 003 2022 / Profesiona Individual Consult IDA / 65170 Project Management Prior Open 63,289.00 0.00 Canceled 2022-02-01 2022-03-22 2022-04-12 2022-05-17 2025-06-30 l A Analista en Adquisiciones ant Selection 1 DPI CI 004 2022 / Profesiona Individual Consult IDA / 65170 Project Management Post Open 57,149.00 0.00 Canceled 2022-02-01 2022-03-22 2022-04-12 2022-05-17 2025-06-30 l B Asistente Legal ant Selection DPI CI 005 2022 / Asistente Individual Consult IDA / 65170 Project Management Post Open 51,464.00 0.00 Canceled 2022-02-01 2022-03-22 2022-04-12 2022-05-17 2025-06-30 A en Archivo ant Selection Individual Consult DPI CI 006 2022 / Chofer A IDA / 65170 Project Management Post Open 37,854.00 0.00 Canceled 2022-02-01 2022-03-22 2022-04-12 2022-05-17 2025-06-30 ant Selection SMOP CI 001-2022 / Fiscal d Resilient Infrastructure and Individual Consult e Obra para el canal emisario IDA / 65170 Urban Upgrading in Santa Cr Post Open 45,450.44 0.00 Signed 2022-02-08 2022-10-24 2022-03-29 2022-10-26 2022-04-19 2022-11-30 2022-05-24 2022-11-20 ant Selection 8vo. Anillo sur-oeste uz SMOP CI 002-2022 / Fiscal A Resilient Infrastructure and Individual Consult mbiental para el canal emisa IDA / 65170 Urban Upgrading in Santa Cr Post Open 45,450.44 0.00 Signed 2022-02-08 2022-10-24 2022-03-29 2022-10-26 2022-04-19 2022-11-09 2022-05-24 2022-11-20 ant Selection rio 8vo. Anillo sur-oeste uz SMOP CI 003-2022 / Fiscal S Resilient Infrastructure and Individual Consult ocial para el canal emisario 8 IDA / 65170 Urban Upgrading in Santa Cr Post Open 45,450.44 0.00 Signed 2022-02-08 2022-10-24 2022-03-29 2022-10-26 2022-04-19 2022-11-30 2022-05-24 2022-11-20 ant Selection vo. Anillo sur-oeste uz DPI CI 008-2022 / Consultor Individual Consult de línea Especialista en Infra IDA / 65170 Project Management Post Open 116,790.00 16,573.91 Signed 2022-02-11 2022-02-11 2022-04-01 2022-04-01 2022-04-22 2022-04-04 2022-05-27 2022-04-15 2025-11-10 ant Selection estructura Resiliente DPI CI 005-2022 / Consultor Individual Consult IDA / 65170 Project Management Prior Open 116,790.00 0.00 Signed 2022-02-11 2022-02-14 2022-04-01 2022-03-13 2022-04-22 2022-12-09 2022-05-27 2025-11-10 de línea Especialista en Adqu ant Selection isiciones DPI CI 001-2022 / Consultor Individual Consult de línea Especialista en Salva IDA / 65170 Project Management Post Open 116,790.00 16,573.91 Signed 2022-02-11 2022-02-11 2022-04-01 2022-04-01 2022-04-22 2022-04-04 2022-05-27 2022-04-24 2025-11-10 ant Selection guarda Social DPI CI 004-2022 / Consultor Individual Consult IDA / 65170 Project Management Post Open 116,790.00 16,549.83 Signed 2022-02-11 2022-02-11 2022-04-01 2022-04-01 2022-04-22 2022-04-04 2022-05-27 2022-04-24 2025-11-10 de línea Especialista Financie ant Selection ro DPI CI 007-2022 / Consultor Individual Consult IDA / 65170 Project Management Post Open 116,790.00 16,573.91 Completed 2022-02-11 2022-02-11 2022-04-01 2022-04-01 2022-04-22 2022-04-04 2022-05-27 2022-04-24 2025-11-10 2023-01-14 de línea Especialista Comuni ant Selection cador DPI CI 006-2022 / Consultor Individual Consult IDA / 65170 Project Management Post Open 116,790.00 16,573.91 Signed 2022-02-11 2022-02-11 2022-04-01 2022-04-01 2022-04-22 2022-04-04 2022-05-27 2022-04-24 2025-11-10 de línea Especialista Legal ant Selection DPI CI 003-2022 / Consultor Individual Consult IDA / 65170 Project Management Post Open 116,790.00 16,549.83 Signed 2022-02-11 2022-02-11 2022-04-01 2022-04-01 2022-04-22 2022-04-04 2022-05-27 2022-04-24 2025-11-10 de línea Especialista en Moni ant Selection toreo DPI CI 014-2022 / Consultor Individual Consult Under Implement IDA / 65170 Project Management Post Open 37,854.00 0.00 2022-02-11 2023-06-08 2022-06-17 2022-07-08 2022-08-12 2026-01-26 de línea Chofer A ant Selection ation DPI CI 002-2022 / Consultor Individual Consult de línea Especialista en Salva IDA / 65170 Project Management Post Open 116,790.00 16,549.83 Signed 2022-02-11 2022-02-11 2022-04-01 2022-04-01 2022-04-22 2022-04-04 2022-05-27 2022-04-24 2025-11-10 ant Selection guarda Ambiental DPI CI 009-2022 / Consultor Individual Consult de línea Profesional A – Asist IDA / 65170 Project Management Post Open 63,288.00 8,994.49 Signed 2022-02-11 2022-02-11 2022-04-01 2022-04-01 2022-04-22 2022-04-04 2022-05-27 2022-04-24 2025-11-10 ant Selection ente Administrativo DPI CI 010-2022 / Consultor Individual Consult IDA / 65170 Project Management Post Open 63,288.00 8,968.37 Signed 2022-02-11 2022-02-11 2022-04-01 2022-04-01 2022-04-22 2022-04-04 2022-05-27 2022-04-24 2025-07-10 de línea Profesional A - Analis ant Selection ta Contable DPI CI 011-2022 / Consultor Individual Consult de línea Profesional A - Analis IDA / 65170 Project Management Post Open 63,288.00 8,981.41 Completed 2022-02-11 2022-02-11 2022-04-01 2022-04-01 2022-04-22 2022-04-04 2022-05-27 2022-04-24 2025-07-10 2022-09-08 ant Selection ta Presupuestario DPI CI 012-2022 / Consultor Individual Consult de línea Profesional A - Analis IDA / 65170 Project Management Post Open 63,288.00 8,968.37 Completed 2022-02-11 2022-02-11 2022-04-01 2022-04-01 2022-04-22 2022-04-07 2022-05-27 2022-04-24 2025-07-10 ant Selection ta de Procesos de Adquisicio nes DPI CI 013-2022 / Consultor Individual Consult IDA / 65170 Project Management Post Open 57,149.00 8,110.08 Signed 2022-02-11 2022-02-11 2022-04-01 2022-04-01 2022-04-22 2022-04-05 2022-05-27 2022-04-24 2025-07-10 de línea Profesional B – Técni ant Selection co Legal SES CI 002 2022 / Consultor Resilient Infrastructure and especialista Fiscal de Obras d Individual Consult IDA / 65170 Urban Upgrading in Santa Cr Post Open 10,700.00 0.00 Canceled 2022-02-07 2022-03-28 2022-04-18 2022-05-23 2022-11-19 e Regeneracion Urbana. Pilot ant Selection uz o de Urbanismo Tactico SMOP UT CI 002-2022 / Cons ultor de linea Fiscal de Obra Individual Consult Under Implement IDA / 65170 Project Management Post Open - National 6,060.06 0.00 2022-09-22 2023-05-10 2022-11-05 2022-11-26 2022-12-27 2023-06-25 para el Mantenimiento de Es ant Selection ation pacio Público con Urbanismo Táctico Zona Central Page 3 SMOP UT CI 001-2022 / Cons ultor de linea Supervisor de o Individual Consult Under Implement bra para el Mantenimiento d IDA / 65170 Project Management Post Open - National 6,060.06 0.00 2022-09-22 2023-05-10 2022-11-05 2022-11-26 2022-12-27 2023-06-25 ant Selection ation e Espacio Público con Urbani smo Táctico Zona Central SES CI 001 2022 / Consultor especialista Supervisor de la Individual Consult IDA / 65170 Project Management Post Open 10,700.00 0.00 Canceled 2022-02-07 2022-03-28 2022-04-18 2022-05-23 2022-11-19 Obras de Regeneracion Urba ant Selection na. Piloto de Urbanismo Tacti co SMOP UT CP 001-2022 / Con sultor por producto para la cr eación de trabajos de pintura Under Implement IDA / 65170 Project Management Post Direct Selection Direct - National 9,475.22 0.00 2022-09-22 2022-10-10 2022-10-02 2023-05-31 2022-12-06 2023-03-06 mural para el Mantenimiento ation de Espacio Público con Urban ismo Táctico Zona Central pa ra la Pascana de la Recova SMOP UT CP 002 2022 / Con sultor por producto para la cr eación de trabajos de pintura Under Implement IDA / 65170 Project Management Post Direct Selection Direct - National 2,478.13 0.00 2022-09-22 2022-08-19 2022-10-02 2023-05-31 2022-12-06 2023-03-06 mural para el Mantenimiento ation de Espacio Público con Urban ismo Táctico Zona Central pa ra la Zona Hospitalaria SMOP UT CP 003 2022 / Con sultor por producto para la cr eación de trabajos de pintura Under Implement IDA / 65170 Project Management Post Direct Selection Direct - National 947.52 0.00 2022-09-01 2023-05-10 2022-09-11 2023-05-31 2022-11-15 2023-05-14 mural para el Mantenimiento ation de Espacio Público con Urban ismo Táctico Zona Central pa ra el Rincon de la Cruz DPI CI 015 / Consultor de Lin Individual Consult Under Implement IDA / 65170 Project Management Post Open - National 31,645.00 0.00 2023-04-10 2023-05-19 2023-05-23 2023-06-13 2023-07-08 2025-06-13 ea Profesional A - Analista Pr ant Selection ation esupuestario DPI CI 016 / Consultor de Lin Individual Consult Under Implement ea Profesional A - Analista de IDA / 65170 Project Management Post Open - National 31,645.00 0.00 2023-04-10 2023-05-19 2023-05-23 2023-06-13 2023-07-08 2025-06-13 ant Selection ation Procesos de Adquisiciones DPI CI 018 / Consultor de Lin Individual Consult Under Implement ea Profesional B - Personal d IDA / 65170 Project Management Post Open - National 28,575.00 0.00 2023-04-10 2023-05-19 2023-05-24 2023-06-07 2023-07-08 2025-06-13 ant Selection ation e Apoyo - Archivo DPI CI 017 / Consultor de Lin Resilient Infrastructure and Individual Consult IDA / 65170 Post Open - National 58,395.00 0.00 Under Review 2023-06-15 2023-06-27 2023-07-29 2023-08-12 2023-09-12 2025-06-30 ea Especialista Comunicador Urban Upgrading in Santa Cr ant Selection uz DPI CI 019 / Consultor de lín Individual Consult IDA / 65170 Project Management Post Open - National 58,395.00 0.00 Under Review 2023-06-15 2023-06-07 2023-07-28 2023-08-18 2023-09-12 2025-06-30 ea Especialista Legal ant Selection Page 4 PROCUREMENT PLAN Project information: Lebanon – Emergency Social Safety Net Project – P173367 Project Implementation agency: Presidency of Council of Ministers Date of the Procurement Plan: August 18th, 2021 Period covered by this Procurement Plan: August 2021 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international and national competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: is not applicable for those contracts identified in the Procurement Plan tables; Works: is not applicable for those contracts identified in the Procurement Plan tables. PROCUREMENT Lebanon : LEBANON EMERGENCY CRISIS AND COVID-19 RESPONSE SOCIAL SAFETY NET PROJECT PLAN General Information Country: Lebanon 2021-08-19 Bank’s Approval Date of the Original Procurement Plan: 2023-06-05 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P173367 GPN Date: 2021-10-28 Project Name: LEBANON EMERGENCY CRISIS AND COVID-19 RESPONSE SOCIAL SAFETY NET PROJECT Loan / Credit No: IBRD / 91980 Presidency of the Council of Ministers Executing Agency(ies): WORKS Activity Reference No. / Procureme Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH Ri Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method nt Docume ount (US$ and Recommendation Signed Contract o. h cess (Y/N) sk atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion nt Type ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual LB-PCM-277681-GO-RFQ / Pr ovision and Installation of Ha Enhanced Social Safety Nets Request for Quota Single Stage - One E IBRD / 91980 Post Open - National 0.00 Signed 2022-02-16 2022-04-13 2022-10-10 rdware for ID Cards Departm Program Delivery tions nvelope ent for the Ministry of Interior and Municipalities LB-PCM-292749-GO-RFQ / Pr ovision and Installation of Ha Enhanced Social Safety Nets Request for Quota Single Stage - One E IBRD / 91980 Post Open - National 0.00 Signed 2022-05-03 2022-06-28 2022-12-25 rdware and Software for the Program Delivery tions nvelope Ministry of Education and Hig her Education LB-PCM-292755-GO-RFQ / Pr Enhanced Social Safety Nets Request for Quota Single Stage - One E ovision and Installation of IT IBRD / 91980 Post Open - National 0.00 Completed 2022-05-03 2022-06-28 2022-12-25 2022-08-12 Program Delivery tions nvelope equipment for the Central Ma nagement Unit LB-PCM-364780-GO-RFQ / Pr Enhanced Social Safety Nets Request for Quota Single Stage - One E Under Imple ovision and Installation of IT IBRD / 91980 Post Open - National 0.00 2023-06-11 2023-08-06 2024-02-02 Program Delivery tions nvelope mentation equipment for the Ministry of Social Affairs NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual LB-PCM-248944-NC-DIR / Ver Enhanced Social Safety Nets IBRD / 91980 Prior Direct Selection Direct 3,787,416.00 Signed 2021-08-18 2021-08-23 2021-08-23 2021-08-30 2021-09-27 2021-12-16 2022-03-26 ification of Household Program Delivery LB-PCM-259665-NC-DIR / Pro Provision of Cash Transfer fo vision of cash transfer for ho IBRD / 91980 Prior Direct Selection Direct 241,491,025.00 Signed 2021-10-25 2021-11-11 2021-10-30 2021-11-29 2021-12-04 2022-03-21 2022-06-02 r Basic Income Support me basic income support and students at risk CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual LB-PCM-251364-CS-QCBS / T Enhanced Social Safety Nets Quality And Cost- Open - Internationa IBRD / 91980 Prior 0.00 Canceled 2021-09-01 2021-09-05 2021-09-22 2021-11-05 2021-12-03 2022-01-02 2022-02-06 2022-03-13 2023-03-13 hird Party Monitoring Agent Program Delivery Based Selection l LB-PCM-259792-CS-CQS / Th Enhanced Social Safety Nets Consultant Qualifi Open - Internationa IBRD / 91980 Prior 0.00 Canceled 2021-10-26 2021-10-26 2021-11-16 2021-11-11 2021-12-30 2022-02-22 2022-01-29 2022-03-05 2022-09-01 ird Party Monitoring Agent (T Program Delivery cation Selection l PMA) LB-PCM-309236-CS-CQS / Ex ternal Auditor for Lebanon E Enhanced Social Safety Nets Consultant Qualifi Under Implement IBRD / 91980 Post Open - National 0.00 2022-10-04 2022-11-01 2022-10-25 2022-12-16 2022-12-08 2023-01-07 2023-02-11 2023-08-10 mergency Crisis and COVID-1 Program Delivery cation Selection ation 9 Response Social Safety Net Project LB-PCM-295749-CS-QCBS / T Enhanced Social Safety Nets Quality And Cost- Open - Internationa Under Implement IBRD / 91980 Prior 0.00 2021-09-01 2022-12-07 2021-09-22 2021-11-05 2023-03-27 2021-12-03 2022-01-02 2022-02-06 2022-03-13 2023-03-13 hird-Party Monitoring Agent Program Delivery Based Selection l ation INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Actual Amount Invitation to Identifie Draft Negotiated Cont Component Review Type Method Contract Type Process Status Teams of Reference Signed Contract Contract Completion Description o. h (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual LB-PCM-251006-CS-CDS / Ad Enhanced Social Safety Nets Under Implement ministration and Operation of IBRD / 91980 Post Direct Selection Direct 0.00 2021-08-30 2021-09-03 2021-09-09 2021-11-13 2022-05-12 Program Delivery ation Ration Card Call Center LB-PCM-251004-CS-CDS / De Enhanced Social Safety Nets velopment and Management IBRD / 91980 Prior Direct Selection Direct 783,010.00 Signed 2021-08-30 2021-10-17 2021-09-09 2021-10-20 2021-11-13 2021-12-11 2022-05-12 Program Delivery of Intake and Registration Pla tform Enhanced Social Safety Nets IC001 / Procurement Officer IBRD / 91980 Post Direct Selection Direct 36,600.00 Signed 2021-10-25 2021-10-25 2021-10-25 2021-10-25 2021-10-25 2021-11-04 2022-10-31 Program Delivery Enhanced Social Safety Nets Individual Consult IC002 / Financial Officer IBRD / 91980 Post Open 36,000.00 Signed 2021-11-26 2021-11-29 2022-01-14 2022-03-07 2022-02-04 2022-03-07 2022-03-11 2022-03-20 2022-09-07 Program Delivery ant Selection IC005 / MOSA ESSN Coordin Enhanced Social Safety Nets Individual Consult IBRD / 91980 Post Open 0.00 Canceled 2022-01-07 2022-02-25 2022-03-18 2022-04-22 2022-10-19 ator Program Delivery ant Selection LB-PCM-270451-CS-CDS / Pr Enhanced Social Safety Nets IBRD / 91980 Post Direct Selection Direct 107,637.60 Signed 2022-01-07 2021-12-21 2022-01-17 2021-12-22 2022-03-23 2022-04-22 2022-09-19 ovision of Information Securit Program Delivery y Services Enhanced Social Safety Nets Individual Consult IC004 / Project Director IBRD / 91980 Post Direct 48,000.00 Signed 2021-12-22 2021-11-30 2022-01-01 2021-11-30 2022-01-22 2021-12-01 2022-02-26 2021-12-13 2022-08-25 Program Delivery ant Selection Page 1 IC003 / Social Safeguards Of Enhanced Social Safety Nets Individual Consult IBRD / 91980 Post Open 30,000.00 Signed 2021-12-22 2022-01-10 2022-02-09 2022-03-04 2022-03-02 2022-03-07 2022-04-06 2022-03-20 2022-10-03 ficer-Full time Program Delivery ant Selection IC006 / Monitoring and Evalu Enhanced Social Safety Nets Individual Consult Under Implement IBRD / 91980 Post Open 0.00 2022-01-19 2022-01-19 2022-03-09 2022-03-30 2022-05-04 2022-10-31 ation Officer Program Delivery ant Selection ation IC007 / Focal Point/Monitorin Enhanced Social Safety Nets Individual Consult g and Evaluation Officer-Mini IBRD / 91980 Post Open 0.00 Canceled 2022-04-14 2022-04-27 2022-06-02 2022-06-23 2022-07-28 2023-01-24 Program Delivery ant Selection stry of Education and Higher Education IC008 / Focal Point/Monitorin g and Evaluation Officer und Enhanced Social Safety Nets Individual Consult IBRD / 91980 Post Limited 0.00 Signed 2022-10-04 2022-08-19 2022-10-09 2022-09-21 2022-10-30 2022-10-03 2022-12-04 2023-06-02 er the Ministry of Education a Program Delivery ant Selection nd Higher Education IC010 / Junior Software Deve Enhanced Social Safety Nets Individual Consult Pending Impleme loper-The Ministry of Educati IBRD / 91980 Post Limited 0.00 2022-10-04 2022-10-09 2022-10-30 2022-12-04 2023-06-02 Program Delivery ant Selection ntation on and Higher Education IC009 / Senior Software Dev Enhanced Social Safety Nets Individual Consult eloper-The Ministry of Educat IBRD / 91980 Post Limited 0.00 Canceled 2022-10-04 2022-10-09 2022-10-30 2022-12-04 2023-06-02 Program Delivery ant Selection ion and Higher Education IC012 / Senior Software Dev Contingent Emergency Resp Individual Consult Under Implement eloper for the Ministry of Edu IBRD / 91980 Post Open - National 0.00 2022-11-09 2022-11-17 2022-12-28 2023-01-18 2023-02-22 2023-08-21 onse Component (CERC) ant Selection ation cation and Higher Education IC011 / Database Admin-The Enhanced Social Safety Nets Individual Consult Under Implement Ministry of Education and Hig IBRD / 91980 Post Open - National 0.00 2022-11-17 2022-11-21 2023-01-05 2023-01-26 2023-03-02 2023-08-29 Program Delivery ant Selection ation her Education IC013 / ESSN Coordinator-Mi Contingent Emergency Resp Individual Consult IBRD / 91980 Post Limited 0.00 Signed 2022-11-17 2022-12-07 2022-11-22 2023-03-20 2022-12-13 2023-04-12 2023-01-17 2023-07-16 nistry of Social Affairs onse Component (CERC) ant Selection IC014 / MOSA Communicatio Enhanced Social Safety Nets Individual Consult IBRD / 91980 Post Direct - National 0.00 Signed 2022-12-07 2022-12-09 2022-12-17 2022-12-15 2023-01-07 2022-12-15 2023-02-11 2023-08-10 ns Officer Program Delivery ant Selection Page 2 Plan de Passation de marchés I. Généralités 1. L'information sur le projet : Pays : Madagascar ; Emprunteur : République de Madagascar ; Nom de projet : Deuxième Projet de Gouvernance des Pêches et de Croissance Partagée du Sud-ouest de l’Océan Indien (SWIOFish2) Numéro du Crédit : P153370 Agence d’exécution du Projet : 2. Date d’approbation du Plan de passation de marchés par la Banque : 01 Février 2018 ; Révision : 09 Août 2018 ; 3. Date de notification du Plan Général de Passation de marchés : - ; 4. Période couverte par le Plan de Passation de marchés : Année 2018 II. Biens et Travaux et Services hors consultants 1. Seuil de Revue préalable : Les décisions de passation de marchés sujet aux revues préalables de la Banque comme indiqué dans le paragraphe 3.1 de l'Annexe II du Règlement de Passation des Marchés pour les Emprunteurs sollicitant le Financement de Projets d’Investissement (Juillet 2016) et sur la base de l'évaluation de la capacité de l'agence d’exécution : Méthode de Passation de Seuil de revue Commentaires marchés à priori 1. AOI – Ouvert ou Restreint (Biens) 2 000 000 Les montants 2. AON (Biens) 2 000 000 estimatifs des 3. AOI (Travaux) 10 000 000 marchés prévus 4. AON (Travaux) 10 000 000 sont au-dessous 5. AOI (Services) 2 000 000 des seuils. 6. UN -UNOPS (Biens) 2 000 000 Niveau de risque : 7. ED (Biens/Travaux) 2 000 000 « SUBSTANTIEL » 2. Pré-qualification (selon les dispositions des paragraphes 6.19 à 6.24 de la Section VI du Règlement de Passation des Marchés pour les Emprunteurs sollicitant le Financement de Projets d’Investissement (Juillet 2016)) : Non Applicable. 3. Procédures proposées pour les composantes CDD (selon le paragraphe. 6.52 et 6.53 de la Section VI du Règlement de Passation des Marchés pour les Emprunteurs sollicitant le Financement de Projets d’Investissement (Juillet 2016)) : Non Applicable 4. Référence (s’il y en a) au Manuel d’exécution du projet / Manuel de Passation de marchés : Non Applicable 5. Tout autre arrangement spécial en passation de marchés : Non Applicable. 6. Allotissement de fournitures avec méthodes et calendrier : [Enumérer d’abord les allotissements qui nécessitent la revue préalable de la Banque, ensuite les autres allotissements] 1 2 3 4 5 6 7 8 9 Réf. Description Contrat Coût Approche/Méth Pré- Préféren Revue de la Date Commentair No estimatif ode de qualificati ce Banque (à prévue es sélection on national priori / à d’ouverture Oui / Non e posteriori) des Oui / Non soumission s MG- Matériels roulants (46Voitures : PM 1DSP – 2CEDP – 3SG – 3DGRHP 3 070 000 UNOPS Non Non Oui 01/07/2018 01/1 – 3RGPDD – 4ASH – 1USTA – 8 5CSP – 22 DRRHP – 2UGP) MG- PM Matériels roulants (20motos ; Non Non 59 000 UNOPS Non 01/07/2018 02/1 2USTA – 16UGL – 2UGP) 8 Matériels et équipement Informatiques (48 Ordinateurs de bureau – 45 Ordinateurs portables – 27 Onduleurs – Non Non Non MG- 4Stabilisateurs – 29Imprimantes PM AON/UNOP multifonctions – 52 Imprimantes 433 910 30/09/2018 03/1 S laser noir – 11Imprimantes laser 8 couleur – 29Photocopieuses – 10Vidéoprojecteurs – 10Appareils photo – 11GPS – 1Caméra – 32 Tablettes MG- PM Matériels et mobiliers de bureau Non Non Non 162 200 AON 30/09/2018 04/1 : 1DCI – 2USTA –8 UGL - 1UGP 8 MG- Commented [JM1]: 29 170 dans PPM d’aout PM Fournitures et articles de Non Non Non Commented [u2R2]: Omission de la ligne 47 170 DC 01/12/2018 05/1 bureau 4.1.3.2.1 de l’UGP d’un montant de 18.000USD 8 sur le PTBA 2018 MG- PM Non Non Non Consommables informatiques 73 170 DC 30/09/2018 06/1 8 MG- Kits d'équipements pour les PM enquêteurs (sac de couchage, Non Non Non 17 500 DC 15/10/2018 07/1 tente, torche, bottes, 8 imperméable) MG- Non Non Non Achat téléphone mobile pour la PM collecte de données au niveau 5 250 DC 01/12/2018 08/1 national 8 MG- Non Non Non Matériels d'échantillonnage PM (Blouse, gant, balance, pied a 1 000 DC 30/09/2018 09/1 coulisse…) 8 MG- Non Non Non Acquisition et installation d’un PM logiciel de suivi automatique 150 000 AON 01/12/2018 10/1 des captures (ERS); 8 MG- Non Non Non Dotation et moyens PM d'équipement pour les 48 000 DC 30/10/2018 11/1 membres du CSC 8 MG- Non Non Non PM Matériels de l'électrification 9 000 DC 30/10/2018 12/1 hors grille 8 MG- Non Non Non PM Equipements et outils de pêche 120 000 AON 01/10/2018 13/1 8 MG- Non Non Non Commented [JM3]: 115 000 dans PPM d’aout Outillage d'entretien d'engin et PM Commented [u4R4]: Après vérification du d'embarcation de pêche pour 60 000 AON 01/12/2018 14/1 PTBA Ligne 3.2.1.1.32 : il est prévu :12 lots à usage communautaire 8 5.000USD l’unité Appui à la mise à disposition Non Non Non MG- des équipements de base pour PM la sécurité des pêcheurs et de 165 000 AON 01/12/2018 15/1 leurs embarcations en mer 8 (gilet, miroir… pour la période transitoire) MG- Non Non Non PM Outils de valorisation 80 000 DC 01/12/2018 16/1 8 MG- Petits matériels de valorisation 80 000 DC Non Non Non 01/12/2018 PM 17/1 8 MG- Non Non Non Commented [JM5]: Combien de boites sont PM prévues ? Achat boites à plaintes 3 950 DC 30/09/2018 18/1 Commented [u6R6]: 79 boites à plaintes 8 suivant la ligne 3.2.3.4.4 du PTBA 2018 MG- Non Non Non PM Outillage pour les pépinières et 19 000 DC 01/12/2018 19/1 les reboisements (brouette,….) 8 MG- Non Non Non Renforcement de l'unité de PM gestion communautaire en 10 000 DC 01/12/2018 20/1 biens et équipements 8 MG- Acquisition, installation et test Non Non Non PM des biens et équipements 240 000 AON 01/12/2018 21/1 relatifs aux technologies hors 8 grille MG- Non Non Non PM Petit outillage et fournitures 417 DC 30/10/2018 22/1 d’atelier (unité) 8 MG- Non Non Non Construction des bureaux des 2 PM PIE de l'ASH en province : 60 000 DC 30/09/2018 23/1 Antsiranana et Morondava 8 Carénages du navire de Non Non Non MG- surveillance «Atsantsa », PM remplacement des appareils de 181 000 AON 30/08/2018 24/1 navigation/accessoires et pièces 8 de rechanges des moteurs auxiliaires MG- Non Non Non PM Carénage du navire de 76 000 DC 30/10/2018 25/1 surveillance "Telonify" 8 MG- Non Non Non PM Constructions pour les six (06) 420 000 AON 30/09/2018 26/1 DRRHP et huit (08) CIRRHP 8 MG- Non Non Non PM Construction de petits 350 000 AON 30/11/2018 27/1 débarcadères type ponton 8 Installation d'unités de Non Non Non fabriques de glace/chambres MG- froides fonctionnant avec des PM énergies renouvelables et 320 000 AON 30/11/2018 28/1 respectant l’environnement 8 pour maintenir la chaine de froid des produits halieutiques dès leur débarquement MG- Non Non Non PM Construction d'infrastructures 360 000 AON 01/12/2018 29/1 communautaires /communales 8 MG- Non Non Non Infrastructures d'électrification PM hors grille dans les 1 250 000 AON 01/12/2018 30/1 communautés pilotes 8 MG- Non Non Non PM Construction de bureau de 60 000 DC 30/07/2018 31/1 l'UGP centrale 8 7.858.197 TOTAL Biens – Equipements et Travaux III. Sélection de consultants 1. Seuil de Revue Préalable : Décisions de sélection sujet à la revue préalable de la Banque comme indiqué dans le paragraphe 3 de l'Annexe II du Règlement de Passation des Marchés pour les Emprunteurs sollicitant le Financement de Projets d’Investissement (Juillet 2016) : Méthode de sélection Seuil de Commentaires revue à priori 1. Méthode compétitive (firmes) 1 000 000 Les montants 2. Entente directe (firmes) 1 000 000 estimatifs des 3. Méthode compétitive (Consultant individuel) 300 000 contrats prévus sont 4. Entente directe (Consultant individuel) 300 000 au-dessous des seuils. Niveau de risque : « SUBSTANTIEL » 2. Liste restreinte composée entièrement de consultants nationaux : Liste restreinte de consultants pour prestations de services, estimés à moins de USD 150 000 par contrat, peut comporter entièrement des consultants nationaux selon les dispositions du paragraphe 7.25 de l'Annexe II du Règlement de Passation des Marchés pour les Emprunteurs sollicitant le Financement de Projets d’Investissement (Juillet 2016). 3. Tout autre arrangement spécial de Sélection de consultants : Non applicable 4. Tâches de consultation avec des méthodes de sélection et calendrier Réf. Description des missions Coût Approche/Méthode de Revue de la Date prévue Commentaires No. estimatif sélection Banque (à de priori / à soumission posteriori) des propositions Etude et analyse diagnostiques des MG-PM stratégies du secteur et des anciens 75 000 CI NON 01/05/2018 32/18 plans directeurs et élaboration du nouveau plan directeur Mise à jour de la Stratégie Nationale de MG-PM l’Aquaculture (Consultant national + 30 000 CI NON 30/08/2018 33/18 Réunions (1 consultation, 1 validation) Etude sur les procédures MG-PM administratives régissant l’accès aux 70 000 CI NON 30/07/2018 34/18 ressources et examen des options et recommandations (6 outils de gestion) Elaboration de la stratégie d'adaptation MG-PM du secteur pêche face au changement 10 000 CI NON 01/09/2018 35/18 climatique Amélioration de la base de données pour la déclaration des produits de la Commented [JM8]: Est-ce que l augmentation MG-PM pêche régionale (Base de données- 10 000 CI NON 30/08/2018 de 35 000 à 58 500 justifié par l’ajout de la 36/18 Tableau de bord-Système d'Information partie CFTP non prévue au PPM d’aout. Pêche : basé sur le Web, consultant) Commented [u9R9]: Faisant suite aux Amélioration de la base de données instructions de l’Equipe PPM de la BM, on a MG-PM pour les pêcheries industrielles 10 000 CI NON 30/09/2018 regroupée les études techniques et les études 37/18 Impacts pour l’OEPA régional et central – CFTP (consultant) Etude technique et étude d'impact et Enceinte Fénerive Est suivant les lignes du PTBA suivantes ; 2.1.2.3.6 – 2.1.2.3.7 – 2.1.2.5.2 environnemental et social de Etude groupée – 2.1.2.5.3 – 2.3.2.1.1 – 2.3.2.2.1.2 – 3.2.1.1.3 et MG-PM l'extension ou construction du bureau MG-PM 38-39-40- 3.2.1.1.4 58 500 SFQC NON 30/10/2018 92/18 régional et central de l’OEPA, de 41-55-56-62- réhabilitation du CFTP , Clôture de 63/18 Commented [JM7]: Est-ce que les études techniquesenv. Pour l’enceinte de la DRRHP de l’enceinte DRRHP Fenerive Fenerive ne pourrait pas être plutôt ajouter à la PA65 ? Réf. Description des missions Coût Approche/Méthode de Revue de la Date prévue Commentaires No. estimatif sélection Banque (à de priori / à soumission posteriori) des propositions Elaboration stratégie nationale de MG-PM recherches halieutiques (1 Consultant 50 000 CI NON 30/07/2018 42/18 international et 3 consultants nationaux) MG-PM Etude sur les mesures de gestion des 30 000 CI NON 30/07/2018 43/18 poulpes Avis scientifique pour la gestion des MG-PM pêcheries de langoustes, dans les sites 30 000 CI NON 30/07/2018 44/18 prioritaires Développement des points de référence MG-PM opérationnels pour la gestion de la 75 000 CI NON 30/07/2018 45/18 pêche crevettière Révision du système de suivi de la MG-PM pêche crevettière traditionnelle (PCT) 86 000 SFQC NON 30/07/2018 46/18 et élargissement à toutes les zones de pêche MG-PM Révision par les pairs des modèles 86 000 SFQC NON 30/07/2018 47/18 d'évaluation des stocks de crevettes Étude technique sur la stratégie de NON Commented [JM10]: 60 000 dans le PPM MG-PM surveillance et sur le fonctionnement 15 000 SFQC 30/07/2018 d’aout 49/18 du CSP Commented [u11R11]: Après vérification du Frais d'équipage durant les travaux de NON PTBA 2018 ligne 2.2.2.1.1, pour 2018 on a prévu MG-PM carénages (vivres+ indemnités + 25 000 CI 01/08/2018 01 étude pour 15.000USD le coût unitaire 50/18 carburants) MG-PM Assistance technique pour le suivi des 26 000 CI NON 30/09/2018 51/18 travaux de carénage de l'Atsantsa MG-PM NON Rédaction d’un plan national de lutte 52/18 52 000 CI 30/07/2018 contre la pêche INN Extension de l’ERS vers la flotte NON MG-PM nationale (Etude / subvention/ cout 50 000 CI 30/10/2018 53/18 interne CSP) Réf. Description des missions Coût Approche/Méthode de Revue de la Date prévue Commentaires No. estimatif sélection Banque (à de priori / à soumission posteriori) des propositions Etude et élaboration de mécanisme NON MG-PM structurel de plateforme de cogestion 50 000 CI 30/07/2018 54/18 des filières prioritaires (crabes, poulpes, langoustes, holothuries, crevettes) Études techniques et études d’impact SFQC NON Commented [JM13]: 50 000 dans le PPM environnemental et social pour la Etude groupée d’aout PA 65 Construction des Bureaux de six (06) 70 000 30/07/2018 MG-PM 57-58-85– Commented [u14R14]: Cette ligne regroupe DRRHP et neuf (09) CirRHP et d’un local 86/18 les études MG-PM 57-58-85 et 85 du PPM d’Août, pour bureau de l’UGP réf PTBA 2018 : 2.3.2.1.3 – 2.3.2.1.4 – 4.1.4.1.1 Etude sur l'identification des 180 000 SFQC NON et 4.1.4.1.2 bénéficiaires, du montant et des Commented [u12]: Après vérification PTBA modalités de transfert financier et sur Etude groupée 2018 lignes 2.3.2.1.3 et 2.3.2.1.4 c’est 08 MG-PM la détermination du montant minimal MG-PM 59-18 et 93/18 30/04/2018 de filet social pour les pêcheurs/acteurs MG-PM 60-18 filières affectés par les mesures de gestion MG-PM Recensement et identification des 20 000 CI NON 30/05/2018 61/18 bénéficiaires chaque année Etude sur l'amélioration des SFQC NON MG-PM embarcations existantes à partir des 270 000 01/11/2018 64/18 matériaux locaux bon marché et existants pour chaque ZUP Etude sur l'identification de techniques NON MG-PM modernes de pêche et de fabrication 60 000 SFQC 30/07/2018 65/18 d'engins de pêche adaptés pour chaque ZUP Prestataire formateur en construction 30 000 CI NON MG-PM et entretien des embarcations de pêche 30/11/2018 66/18 (par an) Prestataire formateur en construction 30 000 CI NON MG-PM et entretien des engins de pêche (par 30/08/2018 67/18 an) Réf. Description des missions Coût Approche/Méthode de Revue de la Date prévue Commentaires No. estimatif sélection Banque (à de priori / à soumission posteriori) des propositions Etude sur le circuit de 90 000 SFQC NON MG-PM commercialisation des produits des 30/03/2018 68/18 pêches par ZUP MG-PM ""Etude sur les accidents en mer de la 90 000 SFQC NON 30/04/2018 69/18 pêche à petite échelle""" ""Développement du système de SFQC NON MG-PM valorisation des produits halieutiques 60 000 30/03/2018 70/18 adaptées pour chaque ZUP""" " Étude de marché pour les produits de SFQC MG-PM pêche valorisés dans chaque région 90 000 NON 30/04/2018 71/18 ultra prioritaire (1 étude par région)" MG-PM Prestataire formateur en technique de CI NON 75 000 30/03/2018 72/18 valorisation (par an) MG-PM Prestataire formateur en technique CI NON 25 000 28/02/2018 73/18 commerciale (par an) MG-PM "Analyse des besoins en activités SFQC NON 74/18 alternatives adaptées pour chaque ZUP 210 000 30/05/2018 (exécutée par AGEX)" Evaluation des impacts socio- SFQC NON MG-PM économiques de la mise pratique des 90 000 30/09/2018 75/18 activités alternatives MG-PM Elaboration des Plans d'Action aux 60 000 CI NON 28/02/2018 76/18 restrictions de Ressources (PARAR) Détermination des outils financiers de NON PA40 gestion des revenus issus des filières et 60 000 CI activités alternatives MG – PM Cabinet d’étude ou d’une ONG pour 600 000 SFQC NON 117/18 assurer les missions de l’AGEX (PAP 01/06/2018 MELAKY) Réf. Description des missions Coût Approche/Méthode de Revue de la Date prévue Commentaires No. estimatif sélection Banque (à de priori / à soumission posteriori) des propositions MG – PM Cabinet d’étude ou d’une ONG pour 600 000 SFQC NON 117/18 assurer les missions de l’AGEX (PAP 01/06/2018 BATAN) MG – PM Cabinet d’étude ou d’une ONG pour 600 000 SFQC NON 117/18 assurer les missions de l’AGEX (PAP 01/06/2018 Baie d’Antongil) Elaboration de plan de formation des CI NON élus et acteurs communaux MG-PM (Fokontany, Mairie,…) pour la gestion 18 000 01/06/2018 77/18 et la pérennisation des infrastructures de pêches et communautaires MG-PM Elaboration du plan stratégique de CI NON 80 000 30/01/2018 78/18 développement local (PCD et PLD) Etat de lieux des petites infrastructures CI NON MG-PM de pêches et identifications des besoins 79/18 60 000 01/04/2018 des communautés cibles en petites infrastructures de pêche Etude de faisabilité technique des NON constructions d'infrastructures de pêche (APS & APD) (33 débarcadères, 8 MG-PM marchés couverts, 70 salles réunion et 550 000 SFQC 01/08/2018 80/18 hangars d'entretien des embarcations, 28 fabriques de glace) MG-PM Etude d'impact environnemental et 275 000 SFQC NON 01/08/2018 81/18 social Préparation du plan local NON Ligne d’activité à Commented [JM15]: Pas de montant? MG-PM d'électrification communautaire : étude CI 01/03/2018 retirer dans ce Commented [u16R16]: Omission de montant 82/18 et rapports PPM dans le PTBA réf 3.3.3.1.3 – Après consultation Gestion et mise en œuvre : évaluation NON de RC3, le type de coût CS est changé en OP car MG-PM cette activité fait partie d’objet de convention de la mise en place de l'électrification 15 000 CI 01/12/2018 83/18 avec l’ADER. De ce fait, cette ligne ne fera plus hors grille partie des études dans le PPM 2018 Réf. Description des missions Coût Approche/Méthode de Revue de la Date prévue Commentaires No. estimatif sélection Banque (à de priori / à soumission posteriori) des propositions MG-PM Gestion et mise en œuvre : Suivi 40 000 CI NON 15/10/2018 84/18 évaluation des bases de données MG-PM Enquête de situation de référence des SFQC NON 50 000 30/07/2018 87/18 bénéficiaires MG-PM Audit externe des comptes du Projet 15 000 SMC NON 01/12/2018 88/18 MG-PM Elaboration d'une stratégie du plan de CI NON 10 000 30/09/2018 89/18 communication du projet SWIOFish2 MG-PM Mise en place du site internet du projet CI NON 2 000 30/09/2018 90/18 SWIOFish2 MG-PM CI NON Assistance technique - maintenance 500 30/09/2018 91/18 TOTAL Consultances 5.264.000 IV. Activités de renforcement de capacités de l’Agence d’exécution avec calendrier 1. Dans cette section, les activités de renforcement de capacité acceptées (quelques articles pourraient être des recommandations de CPAR) sont énumérées avec le calendrier No. Résultats escomptés / Description Coût Durée Date de Commentaire de l’activité estimatif estimative début s (jours) MG-FO Ateliers nationaux pour la 12.000 01-18 validation des textes d'application avec CRDA MG-FO Formation SLC (technique de 18.000 02-18 négociation, leadership etc.) MG-FO Tenir un atelier national relatif à 7.500 03-18 la communication de la nouvelle loi portant Code de la Pêche et de l'Aquaculture à Madagascar MG-FO Atelier national de préparation de 3.000 02 04-18 l'élaboration du nouveau plan directeur MG-FO Atelier national de validation du 6.000 01 05-18 plan directeur MG-FO Visite d'échange d'expérience en 40.000 06-18 matière de technique de production et d'exploitation aquacole marine (ex: grouper sp, algue marine, crabe) MG-FO Formation provinciale sur 27.000 07-18 nouvelles procédures de marquage, de délivrance des cartes pêcheurs et mareyeurs MG-FO Formation des cadres supérieurs 123.000 08-18 (6+6) dans la collecte des données et statistiques de pêche (formation FAO/ISSEA) MG-FO Formation des 10 enquêteurs en 2.000 09-18 méthodologie de collecte de données par téléphone mobile pour les 2 ZUP (DIANA et Analanjirofo; soit 5 enquêteurs/région) MG-FO Formation de 05 cadres 25.000 10-18 supérieurs dans l'analyse des données MG-FO Formation de 05 cadres 25.000 11-18 supérieurs en IT MG-FO Participation à des réunions et 10.000 12-18 ateliers régionaux per diem et hôtel et frais d'avion MG-FO Renforcement des 13-18 capacités des personnels 15.000 techniques de l'OEPA (économie des ressources naturelles et économie des pêches) MG-FO Ateliers régionaux sur la 36.000 14-18 stratégie nationale (pour les 6 ex- provinces) MG-FO Atelier national sur la stratégie 3.000 15-18 nationale MG-FO Formations et voyages d’échange 100.000 16-18 d’expérience et de la bonne pratique (renforcement des capacités, Ateliers de restitution et de validation des travaux de consultance, coûts des voyages, frais de participations, indemnités…) MG-FO Renforcement de capacité des 50.250 17-18 agents chercheurs (formations extérieures) MG-FO Participation à des forums de 52.500 18-18 recherche MG-FO Formation de l'équipe (média, 15.000 19-18 audio-visuel, design, PAO, site web, prog. éducatifs) MG-FO Renforcement de capacité des 5.000 20-18 membres du bureau de coordination pêche environnement (environnement pêche et mer) MG-FO Organisation des réunions 46.000 21-18 semestrielles MG-FO Formation en QMS d’une Autorité 14.300 22-18 Compétente par formateur international pour renforcement de capacités en Audit interne d’une Autorité compétente (Maitrise des documents et des enregistrements) MG-FO Formation en Informatique & 23-18 Base de données : Avec 24.000 formateur national : Informatique (bureautique et programmation) / Utilisation & gestion de base de données MG-FO Linguistique : Avec formateur 15.140 24-18 national : Anglais / Chinois MG-FO Formation en Aquaculture : Avec 22.640 25-18 formateur international : Technique d’élevage et gestion de risque / Méthode de contrôle appliquée dans divers système d’aquaculture (Diana 3 personnes; Melaky 7; Central 2) MG-FO Formation en système de 26-18 Biosécurité : Avec formateur 22.640 international : Biosécurité appliquée aux animaux aquatiques (Diana 3 personnes; Melaky 7; Central 2) MG-FO Formation en Système de 22.640 27-18 management de la QHSE Sanitaire : Avec formateur international : Hygiène et pré requis au niveau des établissements / Normes ISO sur la sécurité sanitaire des aliments / HACCP / Evaluation & analyse des risques MG-FO Formation en Gestion des crises : 28-18 Avec formateur international : 22.640 RASFF MG-FO Formation en Système de 20.200 29-18 certification : Avec formateur international : TRACES MG-FO Formation en Accord International 22.640 30-18 : Avec formateur international : Accord SPS&OMC MG-FO Formation en Science & 22.640 31-18 Technologie : Avec formateur international : Microbiologie des aliments et de l’eau / Toxicologie appliquées aux produits de la mer / Science & Technologie des aliments MG-FO Formation en Technique 2.830 32-18 d’analyse : Avec formateur national : Technique d’analyse de détection des maladies aquatiques MG-FO Formatio 22.640 33-18 n en Technique d’analyse et Technique d’échantillonnage : Avec formateur international MG-FO Formation en Administration : 34-18 Avec formateur national : 15.64 Formation en officier de police 0 judiciaire MG-FO Formation en Administration : 2.840 35-18 Avec formateur national : Procédures Banque Mondiale (Passation de marché, suivi- évaluation MG-FO Formation en QMS d’une Autorité 24.000 36-18 Compétente : Avec formateur international : Structuration et management Qualité d’une Autorité Compétente (ISO 17020) MG-FO Formation en Aquaculture : Avec 37-18 formateur international : 40.000 Aquaculture & environnement MG-FO Formation en Contrôles officiels : 38-18 Avec formateur international : 32.000 Echange d’expérience par jumelage régionale MG-FO Formation en Système de 39-18 management de la QHSE 8.000 Sanitaire : Avec formateur international : Audit de laboratoire selon ISO 17025 MG-FO Formation en Technique 8000 40-18 d’analyse : Avec formateur international : Technique d’analyse officielle MG-FO Formation en Technique 41-18 d’analyse : Avec formateur 8.000 international : Métrologie MG-FO Participation aux réunions et 134.000 42-18 groupes de travail CTOI et ORP MG-FO Réunion nationale (50 personnes 43-18 de 2 jours) de concertation sur la 6.000 pêche aux requins, oiseaux de mer, tortues MG-FO Participation aux réunions 100.500 44-18 régionales pour les termes minimaux des accords de pêche MG-FO Réunions de consultation 6.000 45-18 nationales sur la préparation des Mesures de conservation et de gestion (pour 6 réunions par an) MG- Formation sur l'identification des 8.500 FO46-18 espèces thonières et les techniques d'échantillonnage au débarquement MG-FO Formation sur la gestion des 8.500 47-18 données MG-FO Atelier de validation de nouveaux 75.000 48-18 PAP MG-FO Visite d'échange et d'expérience 31.000 49-18 sur l'utilisation du logiciel ERS MG-FO Formation du personnel à 60.600 50-18 l’utilisation et à l’exploitation de cet outil. MG-FO Renforcement de capacité et 51-18 formation des membres des CSC 24.000 MG-FO Ateliers de lancement régionaux 30.000 52-18 sur les plateformes de cogestion (crabes, poulpes, langoustes, holothuries, crevettes) dans les régions MG-FO Formations et remise à niveau au 112.500 53-18 niveau national des cadres MG-FO Formations et remise à niveau 100.000 54-18 des cadres à l'extérieur MG-FO Atelier de restitution de l'étude 55-18 sur l'identification des 20.000 bénéficiaires, du montant et des modalités de transfert financier et du filet social MG-FO Ateliers de validation des 3.000 56-18 référentiels (diplôme, certificat, attestation) MG-FO Formation des techniques 60.000 57-18 modernes de pêche MG-FO Formation en construction 60.000 58-18 et entretien d'engin de pêche MG-FO Formation sur les techniques 60.000 59-18 commerciales des produits des pêches MG-FO Atelier de restitution de l'étude 20.000 60-18 sur l'accidentologie MG-FO Visite d'échange dans le cadre de 90.000 61-18 la sécurité en mer et de la professionnalisation (Philippine, …) MG-FO Ateliers de validation régionale 62-18 (03) et nationale (01) de l'étude 16.000 diagnostic des techniques de valorisation MG-FO Voyage de partage d’expérience 63-18 dans les régions ou pays voisins, 90.000 où la formation et l’appui en valorisation ont été effectives et ont apporté des effets positifs MG-FO Formation des personnes dans la 64-18 communauté de pêcheurs (pêcheurs, femmes de pêcheur, jeunes sans emploi) en 72.000 techniques de valorisation (15 personnes formées par village) MG-FO Formation des acteurs pratiquant 72.000 65-18 les techniques de valorisation sur la gestion des activités commerciales, la prospection des marchés, les techniques de négociation et le marketing et conditionnement MG-FO Voyages d’échange d’expérience 16.000 66-18 pour les acteurs formés et ayant pratiqué la commercialisation au niveau d’un district littoral accompagnés des agents de la CirRHP/DRRHP/MRHP (1 par année par district) (50 acteurs par voyage) MG-FO Ateliers de restitution régionaux 67-18 et des ateliers de validation 24.000 nationale de l'étude diagnostic des besoins en activités alternatives MG-FO Voyages d’échange d’expérience 45.000 68-18 dans des pays semblables à Madagascar pour les bénéficiaires (Afrique australe, régions de la COI et en Asie) MG-FO Prestation à la formation des 50.000 69-18 cibles en activités alternatives MG-FO Formation des techniciens de 9.000 70-18 l’Administration (DRRHP et CirRHP) et l’UGL sur les techniques et le système de suivi de ces techniques (par région) MG-FO Formation des pêcheurs, femmes 480.000 15 71-18 de pêcheurs et jeunes dans les villages de pêcheurs en techniques de production appropriées pour chaque type d’activité alternative choisi (15j*8000) MG-FO Formation des pêcheurs, femmes 05 72-18 de pêcheurs et jeunes sans 100.000 emploi en techniques d’aquaculture (5 jours) MG-FO Formation et d'échange 90.000 73-18 d'expérience à l'étranger dans le cadre de l'aquaculture (algoculture, pisciculture, crabiculture,…) MG-FO Formation des acteurs pratiquant 80.000 04 74-18 les activités alternatives sur la gestion des activités commerciales, la prospection des marchés, les techniques de négociation et le marketing et conditionnement (4 jours) MG-FO Visites de la vitrine/ ferme école 72.000 75-18 pour les acteurs formés MG-FO Orientation des pêcheurs dans la 1.600 02 76-18 valorisation de leur biodiversité et les former en guide touristique MG-FO Sélection et formation des PF au 12.000 77-18 fonctionnement du MDGP MG-FO Ateliers de validation régionale 16.000 78-18 (03) et nationale (01) MG-FO Visite d’échange d’expérience 32.000 79-18 nationale (1 voyage par an par district) MG-FO Voyage de partage d’expérience 45.000 80-18 à l’étranger (01 voyage par an) MG-FO Séminaire/atelier international 70.000 81-18 (02 voyages par an) MG-FO Formation de courte durée à 45.000 82-18 l’étranger (01 voyage par an) MG-FO Réunions de sensibilisation et de 192.000 03 83-18 formation en éducation financière des petits pêcheurs et aquaculteurs à petite échelle (200 villages de pêcheurs) MG-FO Réunions de sensibilisation pour 64.000 01 84-18 la constitution en organisation appropriée des bénéficiaires du projet (200 villages de pêcheurs) MG-FO Promotion des services financiers 48.000 85-18 adéquats et adaptés à chaque zone d’intervention à travers des sensibilisations MG-FO Renforcement de capacité des 150.000 86-18 cadres et élus au niveau local MG-FO Renforcement de capacité des 9.000 87-18 UGL MG-FO Ateliers régionaux (03) et national 16.000 88-18 de validation MG-FO Atelier de réception locale de 4.000 89-18 l’infrastructure construite MG-FO Partage d'expérience à l'étranger 45.000 90-18 (2 missions par an) dans le cadre de la gestion communautaire des infrastructures de pêche MG-FO Formation des groupements de 8.000 91-18 pêcheurs pour être dans des comités de gestion et formation sur la gestion des infrastructures MG-FO Formation des groupements de 36.000 92-18 pêcheurs pour être dans des comités de gestion et formation sur la gestion des infrastructures MG-FO Formation des communautés 55.800 93-18 pilote sur les procédures réglementaires dans le cadre de l'électrification hors grille MG-FO Formation des communautés 90.000 94-18 pilotes à l'usage et à la gestion de l'électrification hors grille MG-FO Engagement communautaire 75.000 95-18 (IEC) dans le cadre de l'électrification hors grille MG-FO Gestion et mise en œuvre : 27.900 96-18 diffusion de connaissances MG-FO Participation à des ateliers de 10.000 97-18 partage MG-FO Formation modulaire spécifique 20.250 98-18 (langues, communication, informatique, …) MG-FO Formation modulaire (Gestion de 120.000 99-18 projet, suivi et évaluation, sauvegarde environnementale, techniques de négociations, SIG, …) MG-FO Formation de l'équipe (média, 37.500 100-18 audio-visuel, design, PAO, site web, prog. éducatifs) MG-FO Formation sur les procédures de 22.500 101-18 la Banque mondiale MG-FO Organisation des ateliers 17.000 102-18 MG-FO Formation relative à l'utilisation 11.400 103-18 de logiciel SE MG-FO Renforcement de capacité des 104-18 UGL sur le SE 7.500 MG-FO Atelier participatif de Suivi 105-18 Evaluation avec UGP- UGL- 3.000 MRHP-AGEX TOTAL Renforcement de capacité 4.396.730 PROCUREMENT Southern Africa : Second South West Indian Ocean Fisheries Governance and Shared Growth Project - Madagascar PLAN General Information Country: Southern Africa Bank’s Approval Date of the Original Procurement Plan: 2017-04-06 Revised Plan Date(s): (comma delineated, leave blank 2023-06-05 if none) Project ID: P153370 GPN Date: Project Name: Second South West Indian Ocean Fisheries Governance and Shared Growth Project - Madagascar Loan / Credit No: IDA / Q9790, IDA / 59870, IDA / D1720, IDA / V0500, TF / A4588 MINISTRY OF HALIEUTIC RESSOURCES AND FISHERIES Executing Agency(ies): WORKS Activity Reference No. / Procurement Estimated Actual A Bid Evaluation Repor Loan / Credit Market Approa Procurement Pr Prequalificatio High SEA/SH Process Draft Pre-qualificatio Prequalification Eval Draft Bidding Docu Specific Procuremen Bidding Documents Proposal Submission Contract Compl Description Component Review Type Method Document Ty Amount ( mount (U t and Recommendati Signed Contract No. ch ocess n (Y/N) Risk Status n Documents uation Report ment / Justification t Notice / Invitation as Issued / Opening / Minutes etion pe US$) S$) on for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned MG-MRHP-28163-CW-RFB// Component 2. Strengthenin Open - Internation Single Stage - Two 2017-09-3 2017-10-2 2017-12-0 2018-02-2 2018-04-0 2018-10- MG-PM-11 / Carénages du n IDA / D1720 g capacities for priority fish Post Request for Bids 76,000.00 0.00 Canceled al Envelope 0 1 5 4 7 04 avire de surveillance «Teloni eries management fy », MG-MRHP-28164-CW-RFB// Component 3. Strengthenin MG-PM-12 / Construction d'i g capacities for engaging in Single Stage - Two 2017-11-3 2017-12-2 2018-02-0 2018-04-2 2018-06-0 2018-12- IDA / 59870 Post Request for Bids Open - National 200,000.00 0.00 Canceled nfrastructures communautai alternative fishing practices Envelope 0 1 4 6 7 04 res /communales and livelihoods activities MG-MRHP-28634-CW-RFB// MG-PM-105 / Carénages du Component 2. Strengthenin navire de surveillance «Atsa Open - Internation Single Stage - Two 2018-02-2 2019-01-2 2018-03-1 2018-04-2 2018-08-0 2018-09-1 2019-03- IDA / D1720 g capacities for priority fish Post Request for Bids 181,000.00 0.00 Canceled ntsa », remplacement des a al Envelope 8 8 4 8 2 3 12 eries management ppareils de navigation/accés soires et pièces de rechange s desmoteurs auxiliaires Component 3. Strengthenin MG-MRHP-28642-CW-RFB// g capacities for engaging in Single Stage - Two 2018-06-2 2018-07-1 2018-08-2 2018-11-1 2018-12-2 2019-06- MG-PM-107 / Rehabilitation IDA / 59870 Post Request for Bids Open - National 50,000.00 0.00 Canceled alternative fishing practices Envelope 9 3 7 6 8 26 du CFTP Nosy be and livelihoods activities MG-MRHP-28648-CW-RFB// Component 3. Strengthenin MG-PM-110 / Infrastructures g capacities for engaging in Single Stage - One 1,250,000.0 2018-04-3 2018-05-1 2018-06-2 2018-09-2 2019-03- IDA / V0500 Post Request for Bids Open - National 0.00 Canceled d'électrification hors grille d alternative fishing practices Envelope 0 0 4 5 0 19 ans les communautés pilote and livelihoods activities s MG-MRHP-100097-CW-RFQ Component 2. Strengthenin Request for Quot Single Stage - One 2019-02-1 2018-07-2 2019-04-1 2018-09-1 2019-10- / Carénages du navire de su IDA / D1720 g capacities for priority fish Post Limited 76,000.00 101,079.93 Completed ations Envelope 7 3 4 7 11 rveillance «Telonify » eries management MG-MRHP-28432-CW-RFB// Component 2. Strengthenin Open - Internation Single Stage - Two 2019-07-0 2019-07-1 2019-08-2 2019-11-1 2019-12-3 2020-06- MG-PM-101 / Extension ou c IDA / 59870 g capacities for priority fish Post Request for Bids 60,000.00 0.00 Canceled al Envelope 1 5 9 8 0 27 onstruction du bureau régio eries management nal OEPA : 03 MG-MRHP-28436-CW-RFB// Component 2. Strengthenin Open - Internation Single Stage - Two 2019-07-1 2019-07-2 2019-09-1 2019-12-0 2020-01-1 2020-07- MG-PM-102 / Construction d IDA / 59870 g capacities for priority fish Post Request for Bids 40,000.00 0.00 Canceled al Envelope 5 9 2 2 3 11 u bâtiment central de l'OEPA eries management : 01 MG-MRHP-28438-CW-RFB// Component 2. Strengthenin Open - Internation Single Stage - Two 2019-07-0 2019-07-1 2019-08-2 2019-11-1 2019-12-3 2020-06- MG-PM-103 / Mise en place IDA / 59870 g capacities for priority fish Post Request for Bids 100,000.00 0.00 Canceled al Envelope 1 5 9 8 0 27 d'infrastructure pour centre eries management de recherche CEDP MG-MRHP-119316-CW-RFB / Component 2. Strengthenin Construction bureaux USTA Single Stage - One 2019-08-0 2019-08-0 2019-09-1 2019-10-1 2019-11-2 2020-05- IDA / 59870 g capacities for priority fish Post Request for Bids Open - National 46,000.00 0.00 Canceled au niveau des antennes (Ma Envelope 1 6 7 7 1 19 eries management hajanga et Toamasina) : 02 MG-MRHP-96947-CW-RFQ B IS / Carénages du navire de Component 2. Strengthenin surveillance «Atsantsa », re Request for Quot Single Stage - One 2019-07-0 2019-02-1 2019-09-2 2019-07-1 2020-03- IDA / D1720 g capacities for priority fish Post Limited 350,000.00 309,641.94 Completed mplacement des appareils d ations Envelope 7 1 6 2 24 eries management e navigation/accessoires et pièces de rechanges des mo teurs auxiliaires MG-MRHP-119317-CW-RFB / Component 2. Strengthenin Single Stage - One 2019-07-1 2019-07-2 2019-08-3 2019-09-3 2019-11-0 2020-05- Constructions pour les six (0 IDA / 59870 g capacities for priority fish Post Request for Bids Open - National 420,000.00 0.00 Canceled Envelope 5 0 1 0 4 02 6) DRRHP et huit (08) CIRR eries management HP MG-MRHP-28643-CW-RFB// Component 3. Strengthenin MG-PM-108 / Construction d g capacities for engaging in Single Stage - Two 2019-08-0 2019-08-1 2019-09-2 2019-12-1 2020-01-3 2020-07- IDA / 59870 Post Request for Bids Open - National 350,000.00 0.00 Canceled e petites débarcadères type alternative fishing practices Envelope 1 5 9 9 0 28 ponton and livelihoods activities MG-MRHP-119318-CW-RFB / Travaux de construction et d Component 2. Strengthenin Single Stage - One 2019-07-1 2019-06-1 2019-07-2 2019-08-3 2019-07-2 2020-02-2 2020-06-0 2020-03-2 2020-08-2 2021-08- e la réhabilitation de l’ancie IDA / 59870 g capacities for priority fish Post Request for Bids Open - National 130,900.00 126,080.50 Signed Envelope 5 8 0 1 3 2 9 8 0 25 n bureau-logement du DRRH eries management P Analanjorofo – Region Anal anjorofo MG-MRHP-119318BIS1-CW- Component 2. Strengthenin RFB / Travaux de constructio Single Stage - One 2019-07-1 2019-06-1 2019-07-2 2019-08-3 2019-07-2 2020-02-2 2020-06-0 2020-03-2 2020-07-0 2021-08- IDA / 59870 g capacities for priority fish Post Request for Bids Open - National 58,400.00 89,364.09 Signed n d'un nouveau bureau-loge Envelope 5 8 0 1 4 2 9 8 4 25 eries management ment du DRRHP Anosy - Rég ion Anosy MG-MRHP-119318BIS2-CW- Component 2. Strengthenin RFB / Travaux de réhabilitati Single Stage - One 2019-07-1 2019-06-1 2019-07-2 2019-08-3 2019-07-2 2020-02-2 2020-06-0 2020-03-2 2020-06-2 2021-08- IDA / 59870 g capacities for priority fish Post Request for Bids Open - National 62,700.00 95,221.17 Signed on du bureau de la CIRRHP Envelope 5 8 0 1 4 2 9 8 4 25 eries management Maroantsetra- District Maroa ntsetra MG-MRHP-119318BIS4-CW- Component 2. Strengthenin RFB / Travaux de constructio Single Stage - One 2019-07-1 2019-06-1 2019-07-2 2019-08-3 2019-07-2 2020-02-2 2020-06-1 2020-03-2 2020-08-1 2021-08- IDA / 59870 g capacities for priority fish Post Request for Bids Open - National 58,600.00 43,216.11 Signed n d'un nouveau bureau-loge Envelope 5 8 0 1 5 2 2 8 8 25 eries management ment ASH Morondava - Régi on Menabe MG-MRHP-28640-CW-RFB// Component 2. Strengthenin Single Stage - Two 2018-06-1 2018-06-2 2018-08-1 2018-11-0 2018-12-1 2019-06- MG-PM-106 / Constructions IDA / 59870 g capacities for priority fish Post Request for Bids Open - National 180,000.00 0.00 Canceled Envelope 5 9 3 2 4 12 pour les six ( 06) DRRHP et eries management huit (08 )CIRRHP MG-MRHP-170956-CW-DIR / Component 2. Strengthenin 2020-05-0 2020-06-1 2020-05-2 2020-06-1 2020-07-1 2020-09-2 2021-12- Travaux de construction du IDA / 59870 g capacities for priority fish Post Direct Selection Direct 76,500.00 95,680.97 Signed 8 1 2 2 0 2 07 DRRHP Androy - Région And eries management roy MG-MRHP-170965-CW-DIR / Component 2. Strengthenin Travaux de réhabilitation du 2020-05-0 2020-06-1 2020-05-2 2020-06-1 2020-07-1 2021-03-1 2021-12- IDA / 59870 g capacities for priority fish Post Direct Selection Direct 71,000.00 71,774.44 Signed bureau-logement du DRRHP 8 1 2 2 7 8 14 eries management Melaky - Région Melaky MG-MRHP-119318BIS5-CW- Component 2. Strengthenin RFB / Travaux de réhabilitati Single Stage - One 2019-07-1 2019-06-1 2019-07-2 2019-08-3 2019-07-2 2020-02-2 2020-03-2 2021-08- IDA / 59870 g capacities for priority fish Post Request for Bids Open - National 71,000.00 0.00 Canceled on du bureau-logement du Envelope 5 8 0 1 6 2 8 25 eries management DRRHP Melaky - Région Mel aky MG-MRHP-119318BIS3-CW- Component 2. Strengthenin Single Stage - One 2019-07-1 2019-06-1 2019-07-2 2019-08-3 2019-07-2 2020-02-2 2020-03-2 2021-08- RFB / Travaux de constructio IDA / 59870 g capacities for priority fish Post Request for Bids Open - National 76,500.00 0.00 Canceled Envelope 5 8 0 1 5 2 8 25 n du DRRHP Androy - Région eries management Androy MG-MRHP-28165-CW-RFB-B Component 4. Project mana Single Stage - One Terminate 2019-06-1 2019-06-1 2019-07-0 2019-08-1 2019-07-2 2019-09-1 2019-12-1 2019-10-2 2020-01-1 2021-03- IS // MG-PM-13 / Constructio IDA / 59870 Post Request for Bids Open - National 90,375.00 74,306.94 gement and coordination Envelope d 7 7 8 9 3 8 7 3 8 21 n de bureau de l'UGP central e MG-MRHP-28165-CW-RFB// Component 4. Project mana Single Stage - Two 2019-07-0 2019-06-1 2019-07-2 2019-07-1 2019-09-0 2019-07-2 2019-11-2 2020-01-0 2020-07- MG-PM-13 / Construction de IDA / 59870 Post Request for Bids Open - National 60,000.00 0.00 Canceled gement and coordination Envelope 1 7 2 8 5 3 5 6 04 bureau de l'UGP centrale MG-MRHP-203600-CW-RFB / Travaux de construction d'u Component 2. Strengthenin Single Stage - One 2020-11-2 2020-12-0 2020-12-1 2020-12-1 2021-01-0 2021-01-0 2021-02-0 2021-03-3 2021-03-1 2021-05-1 2021-07- n bureau de Circonscription IDA / 59870 g capacities for priority fish Post Request for Bids Open - National 61,500.00 59,640.48 Signed Envelope 0 9 0 2 9 8 8 0 5 5 13 de l'Agriculture, de l'Elevage eries management et de la Pêche ( CirAEP) à A mbanja MG-MRHP-96947-CW-RFQ / Carénage du navire de surv Component 2. Strengthenin eillance "Atsantsa", remplac Request for Quot Single Stage - One 2019-03-0 2019-02-1 2019-05-2 2019-11- IDA / D1720 g capacities for priority fish Post Limited 181,000.00 0.00 Canceled ement des appareils de navi ations Envelope 8 1 8 24 eries management gation/ accessoires et pièce s de rechanges des moteurs auxiliaires. MG-MRHP-256406-CW-RFB / Request for Bids TRAVAUX DE CONSTRUCTIO Component 2. Strengthenin Single Stage - One - Works French C 2021-11-1 2021-12-0 2021-11-2 2021-12-0 2021-12-2 2022-01-0 2022-01-2 2022-01-2 2022-02-2 2022-03-1 2022-07- N D’UN BATIMENT ADMINIST IDA / 59870 g capacities for priority fish Post Request for Bids Open - National 178,400.00 163,531.57 Signed Envelope ivil Law (French) 6 1 1 7 1 7 0 4 4 4 24 RATIF ASH TOLIARA - District eries management SPD Toliara Région ATSIMO AND REFANA MG-MRHP-262336-CW-RFQ Request for Quot Component 4. Project mana Request for Quot Single Stage - One Under Impl 2021-12-2 2023-01-1 2022-02-2 2022-08- / Construction de bureau de IDA / 59870 Post Open - National ations (Non Bank 90,375.00 0.00 gement and coordination ations Envelope ementation 0 0 1 20 l'UGP centrale (Relance) -SPD) MG-MRHP-119319-CW-RFB / Installation d'unités de fabri ques de glace/chambres froi Component 3. Strengthenin Request for Bids des fonctionnant avec des é g capacities for engaging in Single Stage - One - Works French C 2022-03-0 2022-03-0 2022-04-0 2022-05-0 2022-06-1 2022-12- IDA / 59870 Post Request for Bids Open - National 320,000.00 0.00 Canceled nergies renouvelables et res alternative fishing practices Envelope ivil Law (French) 2 7 6 6 0 07 pectant l’environnement po and livelihoods activities SPD ur maintenir la chaîne de fro id des produits halieutiques dès leur débarquement : 04 MG-MRHP-119321-CW-RFB / Construction de hangars ave c des matériaux locaux pour Component 3. Strengthenin entretenir les moteurs, les e g capacities for engaging in Single Stage - One 2021-08-0 2021-08-1 2021-09-2 2021-10-2 2021-11-2 2022-05- IDA / 59870 Post Request for Bids Open - National 240,000.00 0.00 Canceled mbarcations et des engins d alternative fishing practices Envelope 6 1 2 2 6 25 e pêche autorisés et d'une b and livelihoods activities ase de réunion, sensibilisati on et de structuration des ut ilisateurs petites infrastructu res de pêche : 08 MG-MRHP-28645-CW-RFB// Component 3. Strengthenin Request for Bids Pending Im MG-PM-109 / Construction d' g capacities for engaging in Single Stage - Two - Small Works SP 2022-08-0 2022-08-1 2022-09-2 2022-12-1 2023-01-3 2023-07- IDA / 59870 Post Request for Bids Open - National 600,000.00 0.00 plementati infrastructures communauta alternative fishing practices Envelope D (1 envelope pr 1 5 9 9 0 29 on ires /communales : 60 and livelihoods activities ocess) MG-MRHP-119320-CW-RFB / Component 3. Strengthenin Request for Bids Pending Im Construction de marchés co g capacities for engaging in Single Stage - One - Small Works SP 2022-05-0 2022-05-0 2022-06-1 2022-07-1 2022-08-2 2023-02- IDA / 59870 Post Request for Bids Open - National 300,000.00 0.00 plementati uverts aux produits halieutiq alternative fishing practices Envelope D (1 envelope pr 3 8 9 9 3 19 on ues : 10 and livelihoods activities ocess) MG-MRHP-119324-CW-RFB / Component 3. Strengthenin Request for Bids Pending Im Infrastructures d'électrificati g capacities for engaging in Single Stage - One - Small Works SP 2022-04-3 2022-05-0 2022-06-1 2022-07-1 2022-08-2 2023-02- TF / A4588 Post Request for Bids Open - National 300,000.00 0.00 plementati on hors grille dans les comm alternative fishing practices Envelope D (1 envelope pr 0 5 6 6 0 16 on unautés pilotes : 10 and livelihoods activities ocess) MG-MRHP-28632-CW-RFB// Component 2. Strengthenin MG-PM-104 / Construction d Single Stage - Two 2019-07-0 2019-07-1 2019-08-2 2019-12-0 2020-01-1 2020-07- IDA / 59870 g capacities for priority fish Post Request for Bids Open - National 60,000.00 0.00 Canceled es bureaux des 2 PIE de l'AS Envelope 1 5 9 3 4 12 eries management H en province : Antsiranana et Morondava Request for Bids MG-MRHP-127603-CW-RFB / Component 2. Strengthenin Pending Im Single Stage - One - Small Works SP 2022-07-0 2022-07-2 2022-09-0 2022-10-0 2022-11-0 2023-05- Construction du siège de l'A IDA / 59870 g capacities for priority fish Post Request for Bids Open - National 60,000.00 0.00 plementati Envelope D (1 envelope pr 1 2 2 2 6 05 SH centrale sis à Antananari eries management on ocess) vo Page 1 MG-MRHP-292931-CW-RFB / Construction des bâtiments Component 3. Strengthenin Request for Bids du kiosque de pré-électrifica g capacities for engaging in Single Stage - One - Small Works SP Under Impl 2022-05-1 2022-05-1 2022-05-1 2022-05-1 2022-06-1 2022-06-2 2022-07-1 2022-07-1 2022-08-2 2022-12- IDA / 59870 Post Request for Bids Open - National 347,450.00 0.00 tion et du «Complexe-pêche alternative fishing practices Envelope D (1 envelope pr ementation 2 2 7 6 6 0 6 5 0 18 » dans les villages de Fontsi and livelihoods activities ocess) maro et Rantohely, Région A nalanjirofo répartis en 2 lots MG-MRHP-296929-CW-RFB / Constructions des Bureaux a dministratifs de l’Autorité Sa Request for Bids nitaire Halieutique (ASH) da Component 2. Strengthenin Single Stage - One - Works French C Under Impl 2022-06-1 2022-06-1 2022-06-2 2022-06-2 2022-07-2 2022-08-1 2022-09-2 2023-02- ns la Région Vatovavy Fitovi IDA / 59870 g capacities for priority fish Post Request for Bids Open - National 362,500.00 0.00 Envelope ivil Law (French) ementation 5 7 0 0 0 9 3 20 nany, District Manakara, Co eries management SPD mmune Manakara, Village M angarivotra et au District de Mananjary, Commune Mana njary, Village Marofinaritra ( 2 Lots) MG-MRHP-297986-CW-RFB / TRAVAUX DE CONSTRUCTIO Component 3. Strengthenin Request for Bids N DES BATIMENTS DU KIOS g capacities for engaging in Single Stage - One - Works French C 2,745,000.0 Under Impl 2022-06-1 2022-10-0 2022-06-2 2022-10-1 2022-07-2 2022-08-2 2022-09-2 2023-02- QUE DE PRE-ELECTRIFICATI IDA / 59870 Post Request for Bids Open - National 0.00 alternative fishing practices Envelope ivil Law (French) 0 ementation 6 7 1 0 1 0 4 21 ON ET DU « COMPLEXE-PEC and livelihoods activities SPD HE » DANS LE DISTRICT D’A MBILOBE, ET DANS LE DISTR ICT DE NOSY BE REPARTIS E N HUIT (08) LOTS MG-MRHP-307513-CW-RFB- Component 3. Strengthenin Request for Bids BIS / Travaux de constructio Pending Im g capacities for engaging in Single Stage - One - Works French C 2022-09-2 2022-10-0 2022-11-0 2022-12-0 2023-01-0 2023-05- n du bâtiment de Kiosque et IDA / 59870 Post Request for Bids Open - National 558,200.00 0.00 plementati alternative fishing practices Envelope ivil Law (French) 9 4 3 3 7 07 du complexe pêche Aniribe on and livelihoods activities SPD Mananara-Nord et Antoraka Maroantsetra répartis en 2 l ots MG-MRHP-320141-CW-RFB / Construction de Bâtiment ab Component 3. Strengthenin Request for Bids ritant la machine à glace rep g capacities for engaging in Single Stage - One - Works French C Under Impl 2022-10-2 2022-11-3 2022-10-2 2022-12-0 2022-11-2 2022-12-2 2023-01-2 2023-05- artis en 5 Lots dans les villa IDA / 59870 Post Request for Bids Open - National 601,000.00 0.00 alternative fishing practices Envelope ivil Law (French) ementation 1 0 6 6 5 5 9 29 ges d’Antanambao Mandrisy and livelihoods activities SPD , Hoalampano, Tampolo, Fah ambahy, Itanjona dans le dis trict de Mananara nord) MG-MRHP-320162-CW-RFB / TRAVAUX DE CONSTRUCTIO Component 3. Strengthenin Request for Bids N DES BATIMENTS DU KIOS g capacities for engaging in Single Stage - One - Works French C Under Impl 2022-10-2 2022-11-2 2022-10-2 2022-12-0 2022-11-2 2022-12-2 2023-01-2 2023-05- IDA / 59870 Post Request for Bids Open - National 852,900.00 0.00 QUE DE PRE-ELECTRIFICATI alternative fishing practices Envelope ivil Law (French) ementation 1 8 6 9 5 5 9 29 ON ET DU « COMPLEXE-PEC and livelihoods activities SPD HE » DANS LE DISTRICT D’A MBANJA REPARTIS EN TROIS (03) LOTS MG-MRHP-320156-CW-RFB / Travaux de construction des Component 3. Strengthenin Request for Bids bâtiments du kiosque de pré g capacities for engaging in Single Stage - One - Works French C Under Impl 2022-10-2 2022-10-2 2022-10-2 2022-10-3 2022-11-2 2022-11-2 2022-12-2 2023-01-2 2023-06- -électrification et du « Comp IDA / 59870 Post Request for Bids Open - National 622,000.00 0.00 alternative fishing practices Envelope ivil Law (French) ementation 1 7 6 1 5 8 5 9 28 lexe-pêche » dans les villag and livelihoods activities SPD es d'Ambalahonko et Ampas imandoro district de Maintir ano repartis en 2 lots MG-MRHP-320151-CW-RFB / Request for Bids CONSTRUCTIONS DES BURE Component 2. Strengthenin Pending Im Single Stage - One - Works French C 2022-10-2 2022-10-2 2022-11-2 2022-12-2 2023-01-2 2023-05- AUX ADMINISTRATIFS DE L'A IDA / 59870 g capacities for priority fish Post Request for Bids Open - National 975,000.00 0.00 plementati Envelope ivil Law (French) 1 6 5 5 9 29 SH ET DE DESP (Ex-OEPA) A eries management on SPD NTANANARIVO repartis en 2 Lots MG-MRHP-332561-CW-RFB / Travaux de construction des Request for Bids Bureaux de la circonscriptio Component 2. Strengthenin Pending Im Single Stage - One - Works French C 2023-01-1 2023-01-1 2023-02-1 2023-03-1 2023-04-2 2023-08- n en charge de la pèche et d IDA / 59870 g capacities for priority fish Post Request for Bids Open - National 708,427.00 0.00 plementati Envelope ivil Law (French) 0 5 4 6 0 18 e l’économie bleu et l’anten eries management on SPD ne du centre de la surveillan ce des pêches à Maintirano, Région Melaky MG-MRHP-337958-CW-RFB / Component 3. Strengthenin Request for Bids Construction de Bâtiment ab g capacities for engaging in Single Stage - One - Small Works SP Under Impl 2023-01-2 2023-02-0 2023-02-0 2023-02-0 2023-03-0 2023-03-1 2023-03-2 2023-07- ritant la chambre froide dan IDA / 59870 Post Request for Bids Open - National 410,000.00 0.00 alternative fishing practices Envelope D (1 envelope pr ementation 7 3 1 6 3 3 3 21 s le village de RANTABE dan and livelihoods activities ocess) s le district de MAROANTSET RA, Région ANALANJIROFO MG-MRHP-337965-CW-RFB / Component 3. Strengthenin Request for Bids CONSTRUCTION DES DEUX ( Pending Im g capacities for engaging in Single Stage - One - Works French C 2023-01-3 2023-02-0 2023-03-0 2023-03-1 2023-03-2 2023-07- 02) MARCHES COUVERTS D IDA / 59870 Post Request for Bids Open - National 250,000.00 0.00 plementati alternative fishing practices Envelope ivil Law (French) 1 5 7 7 5 23 ANS LE DISTRICT DE MANAN on and livelihoods activities SPD ARA NORD REPARTIE EN DE UX (02) LOTS Request for Bids MG-MRHP-262336-BIS-CW- Component 4. Project mana Single Stage - One - Works French C Under Impl 2023-01-2 2023-01-1 2023-02-0 2023-02-0 2023-03-0 2023-03-1 2023-03-2 2023-07- RFQ / Construction de burea IDA / 59870 Post Request for Bids Open - National 90,375.00 0.00 gement and coordination Envelope ivil Law (French) ementation 9 0 3 8 5 5 3 21 u de l’UGP centrale (Relance SPD ) MG-MRHP-340927-CW-RFB / Travaux de construction des Component 3. Strengthenin Request for Bids bâtiments du kiosque de pré Pending Im g capacities for engaging in Single Stage - One - Works French C 2023-02-1 2023-02-1 2023-03-2 2023-04-1 2023-04-2 2023-08- électrification et du "Comple IDA / 59870 Post Request for Bids Open - National 222,300.00 0.00 plementati alternative fishing practices Envelope ivil Law (French) 4 9 1 1 8 26 xe pêche" dans le village d' on and livelihoods activities SPD Andranonabo, Commune Anj iabe ambony, District d'Amb ilobe (RELANCE) MG-MRHP-344175-CW-RFB / Request for Bids Travaux de construction des Component 2. Strengthenin Single Stage - One - Small Works SP 1,352,000.0 Under Impl 2023-02-2 2023-03-1 2023-03-0 2023-03-1 2023-03-3 2023-04-1 2023-04-1 2023-08- bâtiments Administratifs du IDA / 59870 g capacities for priority fish Post Request for Bids Open - National 0.00 Envelope D (1 envelope pr 0 ementation 4 1 1 5 1 0 4 12 MPEB dans les régions de D eries management ocess) IANA- MELAKY- ANOSY repar tie en 04 lots MG-MRHP-344184-CW-RFB / Request for Bids Travaux de construction des Component 2. Strengthenin Single Stage - One - Works French C Under Impl 2023-02-2 2023-03-1 2023-03-0 2023-04-1 2023-03-3 2023-04-1 2023-04-1 2023-08- bâtiments Administratifs du IDA / 59870 g capacities for priority fish Post Request for Bids Open - National 620,000.00 0.00 Envelope ivil Law (French) ementation 4 1 1 1 1 0 4 12 MPEB dans les régions de B eries management SPD OENY et ATSIMO ANTSINANA NA repartie en 02 lots MG-MRHP-344311-CW-DIR / Travaux additionnels de con Component 2. Strengthenin Request for Quot Pending Im struction du bureau, de Han 2023-04-0 2023-04-2 2023-05-0 2023-08- TF / A4588 g capacities for priority fish Post Direct Selection Direct - National ations (Non Bank 230,000.00 0.00 plementati gar pour la vedette de la bri 7 7 3 31 eries management -SPD) on gade du CSP Analanjirofo, et mise en place d’un point d’eau autonome par Entrepr ise FITALIA Request for Bids MG-MRHP-127600-CW-RFB / Component 2. Strengthenin Pending Im Single Stage - One - Small Works SP 2023-05-0 2023-05-0 2023-06-0 2023-06-2 2023-07-1 2023-09- Renforcement du CDA - Con IDA / 59870 g capacities for priority fish Post Request for Bids Open - National 36,850.00 0.00 plementati Envelope D (1 envelope pr 2 7 6 7 1 29 struction puits et réhabilitati eries management on ocess) on clôture CDA MG-MRHP-337960-CW-RFB / Travaux de construction des Component 3. Strengthenin Request for Bids bâtiments abritant la machi g capacities for engaging in Single Stage - One - Small Works SP Under Impl 2023-05-0 2023-05-0 2023-05-0 2023-05-0 2023-06-0 2023-06-1 2023-07-0 2023-09- ne à glace dans les villages IDA / 59870 Post Request for Bids Open - National 357,400.00 0.00 alternative fishing practices Envelope D (1 envelope pr ementation 3 3 3 9 2 6 7 29 de Maintimbato, Mahasoa, A and livelihoods activities ocess) mbodipaka, Masindrano da ns le district de Maroantsetr a repartis en 4 lots MG-MRHP-337959-CW-RFB / Component 3. Strengthenin Request for Bids Travaux de construction des g capacities for engaging in Single Stage - One - Works French C Under Impl 2023-04-2 2023-04-2 2023-04-2 2023-05-2 2023-05-2 2023-06-1 2023-07-1 2023-09- bâtiments abritant la machi IDA / 59870 Post Request for Bids Open - National 198,000.00 0.00 alternative fishing practices Envelope ivil Law (French) ementation 9 8 9 2 9 2 0 29 ne à glace et magasin de st and livelihoods activities SPD ockage dans le district de N osy be répartis en 2 lots GOODS Activity Reference No. / Bid Evaluation Repor Loan / Credit Market Approa Procurement Pr Prequalificatio Estimated A Actual Amoun Process St Draft Pre-qualificatio Prequalification Eval Draft Bidding Docu Specific Procuremen Bidding Documents Proposal Submission Description Component Review Type Method t and Recommendati Signed Contract Contract Completion No. ch ocess n (Y/N) mount (US$) t (US$) atus n Documents uation Report ment / Justification t Notice / Invitation as Issued / Opening / Minutes on for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MG-MRHP-28121-GO-UN// M Component 2. Strengthenin UN Agencies (Dir 2017-09-3 2017-10-2 2017-12-2 2018-06-2 G-PM-01 / Matériels et équip IDA / 59870 g capacities for priority fish Post Direct 315,310.00 0.00 Canceled ect) 0 1 3 1 ements informatiques et bur eries management eautiques MG-MRHP-28129-GO-RFB// Component 2. Strengthenin MG-PM-02 / Kits d'équipeme Open - Internation Single Stage - Two 2017-10-1 2017-11-0 2017-12-1 2018-03-0 2018-04-1 2018-10-1 IDA / D1720 g capacities for priority fish Post Request for Bids 17,500.00 0.00 Canceled nts pour les enquêteurs (sa al Envelope 5 5 7 8 9 6 eries management c de couchage, tente, torche , bottes, impermeable) MG-MRHP-28136-GO-UN//M Component 2. Strengthenin UN Agencies (Dir Pending Imp 2017-09-3 2017-10-2 2017-12-2 2018-06-2 G-PM-03 / Acquisition de Vé IDA / 59870 g capacities for priority fish Post Direct 1,830,000.00 0.00 ect) lementation 0 1 3 1 hicule eries management MG-MRHP-28157-GO-RFB// Component 2. Strengthenin Open - Internation Single Stage - Two 2017-10-3 2017-11-2 2018-01-0 2018-03-2 2018-05-0 2018-11-0 MG-PM-05 / Acquisition de fo IDA / 59870 g capacities for priority fish Post Request for Bids 29,170.00 0.00 Canceled al Envelope 0 0 4 6 7 3 urnitures et articles de bure eries management au MG-MRHP-28158-GO-UN//M Component 2. Strengthenin UN Agencies (Dir Pending Imp 2017-09-3 2017-10-2 2017-12-2 2018-06-2 G-PM-06 / Acquisition de Mot IDA / 59870 g capacities for priority fish Post Direct 59,000.00 0.00 ect) lementation 0 1 3 1 o eries management MG-MRHP-28159-GO-UN//M Component 2. Strengthenin UN Agencies (Dir 2017-10-1 2017-11-0 2018-01-0 2018-07-0 G-PM-07 / Acquisition de Dro IDA / D1720 g capacities for priority fish Post Direct 5,000.00 0.00 Canceled ect) 6 6 8 7 ne pour surveillance et contr eries management ôle MG-MRHP-28160-GO-RFB// Component 2. Strengthenin Open - Internation Single Stage - Two 2017-10-3 2017-11-2 2018-01-0 2018-03-2 2018-05-0 2018-11-0 MG-PM-08 / Acquisition de M IDA / 59870 g capacities for priority fish Post Request for Bids 120,000.00 0.00 Canceled al Envelope 0 0 4 6 7 3 atériels et Mobiliers de bure eries management au MG-MRHP-28161-GO-RFB// MG-PM-09 / Appui à la mise Component 3. Strengthenin à disposition des équipemen g capacities for engaging in Open - Internation Single Stage - Two 2017-11-1 2017-12-0 2018-01-2 2018-04-1 2018-05-2 2018-11-1 IDA / 59870 Post Request for Bids 65,000.00 0.00 Canceled ts de base pour la sécurité d alternative fishing practices al Envelope 5 6 0 1 3 9 es pêcheurs et de leurs emb and livelihoods activities arcations en mer (gilet, miro ir... pour la période transitoir e) MG-MRHP-28162-GO-RFB// Component 2. Strengthenin Single Stage - One 2017-11-1 2017-12-0 2018-01-2 2018-02-1 2018-04-0 2018-09-2 MG-PM-10 / Acquisition de C IDA / 59870 g capacities for priority fish Post Request for Bids Open - National 25,170.00 0.00 Canceled Envelope 5 6 0 9 2 9 onsommables informatiques eries management (Lot) MG-MRHP-28397-GO-RFB// Component 2. Strengthenin MG-MP-89 / Acquisition et in Open - Internation Single Stage - Two 2018-06-1 2018-06-2 2018-08-1 2018-11-0 2018-12-1 2019-06-1 IDA / D1720 g capacities for priority fish Post Request for Bids 150,000.00 0.00 Canceled stallation d'un logiciel de sui al Envelope 5 9 3 2 4 2 eries management vi automatique des captures (ERS) MG-MRHP-28401-GO-RFB// Component 3. Strengthenin MG-PM-90 / Matériels de bur g capacities for engaging in Open - Internation Single Stage - Two 2018-06-1 2018-06-2 2018-08-1 2018-11-0 2018-12-1 2019-06-1 eau du CFTP (06 lots compo IDA / 59870 Post Request for Bids 6,000.00 0.00 Canceled alternative fishing practices al Envelope 5 9 3 2 4 2 sés de table de bureau, chai and livelihoods activities se de bureau, chaise visiteu se et armoire ) MG-MRHP-28406-GO-RFB// MG-PM-93 / Acquisition des Component 3. Strengthenin équipements de base pour l g capacities for engaging in Open - Internation Single Stage - Two 2018-01-3 2018-02-1 2018-03-3 2018-06-1 2018-07-3 2019-01-2 IDA / 59870 Post Request for Bids 100,000.00 0.00 Canceled a sécurité des pêcheurs et d alternative fishing practices al Envelope 0 3 0 9 1 7 e leurs embarcations en mer and livelihoods activities (gilet, miroir... pour la périod e transitoire) MG-MRHP-28415-GO-RFB// Component 3. Strengthenin MG-PM-96 / Acquisition d'out g capacities for engaging in Single Stage - Two 2018-03-3 2018-04-1 2018-05-2 2018-08-1 2018-09-2 2019-03-2 IDA / 59870 Post Request for Bids Open - National 19,000.00 0.00 Canceled illage pour les pépinières et alternative fishing practices Envelope 0 3 8 7 8 7 les reboisements (brouette,. and livelihoods activities ...) Page 2 MG-MRHP-28431-GO-RFB// MG-PM-100 / Acquisition de Component 3. Strengthenin mobiliers de bureau pour Ge g capacities for engaging in Single Stage - Two 2018-05-1 2018-05-2 2018-07-1 2018-10-0 2018-11-1 2019-05-1 stion et mise en œuvre : (0 IDA / V0500 Post Request for Bids Open - National 40,000.00 0.00 Canceled alternative fishing practices Envelope 5 9 3 2 3 2 3 lots composés de 01 table and livelihoods activities de bureau, 01 chaise de bur eau, 02 chaises visiteurs et 01 armoire de rangement se mi vitré ) MG-MRHP-23399-GO-UN / A Component 2. Strengthenin UN Agencies (Dir 2017-08-1 2017-09-0 2017-11-0 2018-05-0 chat de lot de Matériel infor IDA / Q9790 g capacities for priority fish Post Direct 201,660.00 0.00 Canceled ect) 5 5 7 6 matique (Année 2017) eries management Component 3. Strengthenin MG-MRHP-85764-GO-RFQ // g capacities for engaging in Request for Quot Single Stage - One 2018-12-1 2019-04-1 2019-10-1 MG-PM 18/18 / Achat de 79 IDA / 59870 Post Limited 3,950.00 0.00 Canceled alternative fishing practices ations Envelope 5 4 1 boites à plaintes and livelihoods activities MG-MRHP-28404-GO-RFB// Component 3. Strengthenin MG-PM-91 / Acquisition d'éq g capacities for engaging in Open - Internation Single Stage - Two 2019-07-1 2019-07-3 2019-09-1 2019-12-0 2020-01-1 2020-07-1 IDA / 59870 Post Request for Bids 320,000.00 0.00 Canceled uipements et outils de pêch alternative fishing practices al Envelope 6 0 3 3 4 2 e and livelihoods activities MG-MRHP-28405-GO-RFB// Component 3. Strengthenin MG-PM-92 / Acquisition d'out g capacities for engaging in Open - Internation Single Stage - Two 2019-07-0 2019-07-1 2019-08-2 2019-11-1 2019-12-3 2020-06-2 IDA / 59870 Post Request for Bids 185,000.00 0.00 Canceled illage d'entretien d'engin et alternative fishing practices al Envelope 1 5 9 8 0 7 d'embarcation de pêche pou and livelihoods activities r usage communautaire MG-MRHP-119305-GO-RFQ / Component 3. Strengthenin Appui à l'acquisition de mat g capacities for engaging in Request for Quot Single Stage - One 2019-07-0 2019-08-3 2020-02-2 IDA / 59870 Post Limited 100,000.00 0.00 Canceled ériels de sécurité aux pêche alternative fishing practices ations Envelope 6 1 7 urs et communauté de pêch and livelihoods activities eurs : 2000 Component 3. Strengthenin MG-MRHP-28410-GO-RFB// g capacities for engaging in Open - Internation Single Stage - Two 2018-05-1 2018-05-2 2018-07-1 2018-10-0 2018-11-1 2019-05-1 MG-PM-94 / Acquisition d'out IDA / 59870 Post Request for Bids 80,000.00 0.00 Canceled alternative fishing practices al Envelope 5 9 3 2 3 2 ils de valorisation and livelihoods activities MG-MRHP-28411-GO-RFB// Component 3. Strengthenin MG-PM-95 / Acquisition des g capacities for engaging in Open - Internation Single Stage - Two 2019-07-0 2019-07-1 2019-08-2 2019-11-1 2019-12-3 2020-06-2 IDA / 59870 Post Request for Bids 80,000.00 0.00 Canceled petits matériels de valorisati alternative fishing practices al Envelope 1 5 9 8 0 7 on and livelihoods activities Component 3. Strengthenin MG-MRHP-119309-GO-RFQ / g capacities for engaging in Request for Quot Single Stage - One 2019-06-2 2019-08-1 2019-07-1 2020-02-1 2019-08-1 IDA / 59870 Post Open - National 5,250.00 7,885.75 Completed Achat boites à plaintes : 105 alternative fishing practices ations Envelope 3 8 6 4 4 and livelihoods activities Component 3. Strengthenin MG-MRHP-119311-GO-RFQ / g capacities for engaging in Request for Quot Single Stage - One 2019-07-2 2019-10-0 2019-09-1 2020-01-1 2020-03-1 2020-02-0 Achat puce et téléphone por IDA / 59870 Post Limited 5,250.00 11,213.00 Completed alternative fishing practices ations Envelope 0 9 4 1 2 1 table : 105 and livelihoods activities MG-MRHP-28121-GO-UN// M Component 2. Strengthenin Request for Prop Single Stage - One 2019-07-3 2019-09-1 2019-08-2 2019-10-0 2019-10-0 2019-11-0 2019-11-0 2020-04-1 2019-12-1 2020-06-1 2020-06-1 2020-09-2 G-PM-01-2 / Matériels inform IDA / 59870 g capacities for priority fish Post Open - National 156,370.00 141,053.48 Completed osals Envelope 1 4 1 9 2 8 1 5 3 0 0 8 atiques 2019 eries management MG-MRHP-86177-GO-RFQ// Component 2. Strengthenin MG-PM 08/18 / Achat téléph Request for Quot Single Stage - One 2019-08-2 2019-07-2 2020-01-0 2019-09-0 2020-07-0 2019-09-2 IDA / V0500 g capacities for priority fish Post Limited 10,500.00 10,073.72 Completed one mobile pour la collecte ations Envelope 4 4 6 4 4 5 eries management de données au niveau natio nal MG-MRHP-28160-GO-RFB// Component 2. Strengthenin Request for Quot Single Stage - One 2019-07-2 2019-08-2 2019-09-1 2019-09-0 2020-03-1 2019-09-1 MG-PM-08-2 / Matériels et m IDA / 59870 g capacities for priority fish Post Limited 33,200.00 19,057.68 Completed ations Envelope 0 9 4 5 2 0 obiliers de bureau 2019 eries management MG-MRHP-28161-GO-RFB// MG-PM-09-2 / Appui à la mis Component 3. Strengthenin e à disposition des équipem g capacities for engaging in Single Stage - One 2019-07-1 2019-09-1 2019-07-2 2019-10-0 2019-08-3 2019-11-0 2019-09-3 2019-11-0 2020-05-0 ents de base pour la sécurit IDA / 59870 Post Request for Bids Open - National 330,000.00 0.00 Canceled alternative fishing practices Envelope 5 6 0 9 1 8 0 4 2 é des pêcheurs et de leurs e and livelihoods activities mbarcations en mer (gilet, miroir… pour la période tran sitoire) : 3300 MG-MRHP-28161 BIS-GO-RF Component 3. Strengthenin B // MG-PM-09-2 / Acquisitio g capacities for engaging in Single Stage - One 2019-12-2 2019-12-3 2019-12-2 2019-12-3 2020-01-2 2020-01-3 2020-02-1 2020-04-0 2020-03-0 2020-04-2 2020-06-0 n de 3300 kits de sécurité e IDA / 59870 Post Request for Bids Open - National 330,000.00 106,992.01 Signed alternative fishing practices Envelope 0 1 7 1 6 1 6 7 4 8 2 n mer pour les petits pêcheu and livelihoods activities rs (gilet, miroir… pour la pér iode transitoire) MG-MRHP-160447-GO-RFQ / Component 2. Strengthenin Fourniture des plaques d'im Request for Quot Single Stage - One 2020-03-1 2020-08-2 2020-04-1 2020-11-0 2020-05-1 2020-12-1 IDA / 59870 g capacities for priority fish Post Limited 100,000.00 18,218.09 Completed matriculations des pirogues ations Envelope 1 5 5 4 5 8 eries management (lot unique et indivisible) MG-MRHP-161268-GO-RFQ / Component 2. Strengthenin Request for Quot Single Stage - One 2020-02-2 2020-02-1 2020-03-0 2020-03-0 2020-03-1 Fourniture des carnets d'exp IDA / 59870 g capacities for priority fish Post Limited 8,400.00 8,166.14 Signed ations Envelope 7 8 6 5 3 édition des produits halieuti eries management ques MG-MRHP-127597-GO-RFQ / Component 2. Strengthenin Request for Quot Single Stage - One Pending Imp 2020-09-1 2020-12-1 2021-06-0 200 équipements et outils d IDA / 59870 g capacities for priority fish Post Limited 40,000.00 0.00 ations Envelope lementation 1 1 9 e pêches eries management MG-MRHP-119304-GO-RFQ / Component 2. Strengthenin Request for Quot Single Stage - One Pending Imp 2020-08-0 2020-09-2 2021-03-2 Matériels de l'électrification IDA / 59870 g capacities for priority fish Post Limited 9,000.00 0.00 ations Envelope lementation 4 9 8 hors grille : 03 eries management MG-MRHP-119300BIS-GO-R Component 2. Strengthenin Request for Quot Single Stage - One Pending Imp 2019-06-0 2019-08-2 2020-02-2 FQ / Acquisition d'une Vedet TF / A4588 g capacities for priority fish Post Limited 100,000.00 0.00 ations Envelope lementation 8 6 2 te pour appui CSP eries management Component 3. Strengthenin MG-MRHP-85764 BIS-GO-RF g capacities for engaging in Request for Quot Single Stage - One 2020-05-1 2020-05-0 2020-07-0 2020-06-1 2020-08-0 Q / Achat de 155 boites à pl IDA / 59870 Post Limited 12,000.00 11,910.86 Signed alternative fishing practices ations Envelope 3 8 8 0 7 aintes pour l'exercice 2020 and livelihoods activities MG-MRHP-174399-GO-RFQ / Component 3. Strengthenin Acquisition de 160 téléphon g capacities for engaging in Request for Quot Single Stage - One Under Imple 2020-05-3 2020-06-0 2020-07-2 2020-08-2 IDA / 59870 Post Limited 15,000.00 0.00 es mobiles pour le Mécanis alternative fishing practices ations Envelope mentation 1 3 6 5 me De Gestion des Plaintes and livelihoods activities (MDGP) / Exercice 2020 MG-MRHP-119314-GO-RFQ / Component 3. Strengthenin Achat de vedette pour la mi g capacities for engaging in Request for Quot Single Stage - One 2020-07-2 2020-09-1 2021-03-1 IDA / 59870 Post Limited 80,000.00 0.00 Canceled se en œuvre des activités d alternative fishing practices ations Envelope 0 4 3 ans la région Melaky :1 and livelihoods activities MG-MRHP-119300-GO-RFB / Acquisition de Cinq (05) Ved ettes pour CSP réparties en deux (02) lots: Component 2. Strengthenin - Lot 01: Acquisition de 03 V Single Stage - One 2020-04-1 2020-04-2 2020-06-0 2020-07-0 2020-08-0 2021-02-0 TF / A4588 g capacities for priority fish Post Request for Bids Open - National 321,500.00 0.00 Canceled edettes pour appuyer le CSP Envelope 5 0 1 1 5 1 eries management pour les nouvelles antennes au niveau des ZUP; - Lot 02: Acquisition de 02 v edettes rapides semi-rigides pour patrouilleurs MG-MRHP-119300BIS1-GO- RFB / Acquisition des vedett es réparties en 02 Lots : Component 2. Strengthenin Single Stage - One Under Imple 2020-06-1 2020-06-1 2020-06-1 2020-06-1 2020-07-1 2020-08-1 2020-09-1 2020-12-1 • Lot1 : 07 vedettes coque IDA / 59870 g capacities for priority fish Post Request for Bids Open - National 551,500.00 0.00 Envelope mentation 5 2 6 9 6 5 9 8 s rigides ; eries management • Lot2 : 02 vedettes rapid es semi-rigides. MG-MRHP-28415-GO-RFB // Component 3. Strengthenin MG-PM-96 BIS / Outillage po g capacities for engaging in Request for Quot Single Stage - One 2020-04-2 2020-06-1 2020-12-1 IDA / 59870 Post Limited 19,000.00 0.00 Canceled ur les pépinières et les reboi alternative fishing practices ations Envelope 0 5 2 sements (brouette,….) : 19 and livelihoods activities MG-MRHP-14629-GO-RFQ// Component 2. Strengthenin Request for Quot Single Stage - One 2020-09-2 2021-03-2 2020-11-1 2021-04-1 2020-12-1 PA 2 / PA2: Acquisition d'un l IDA / Q9790 g capacities for priority fish Post Limited 11,000.00 4,352.99 Signed ations Envelope 9 6 7 6 7 ot de matériels de formation eries management et d'enquête MG-MRHP-119240-GO-RFB / Component 2. Strengthenin Renforcement du Centre de Single Stage - Two 2020-07-3 2020-08-0 2020-09-1 2020-11-2 2021-01-0 2021-07-0 IDA / 59870 g capacities for priority fish Post Request for Bids Open - National 580,000.00 0.00 Canceled Développement de l'Aquacul Envelope 0 4 5 8 2 1 eries management ture (CDA) -Equipement der echerche MG-MRHP-188316-GO-RFB / Component 3. Strengthenin Fourniture et livraison de 11 g capacities for engaging in Open - Internation Single Stage - One 2020-08-1 2020-08-2 2020-08-1 2020-08-2 2020-09-2 2020-10-2 2020-10-1 2020-11-1 2020-11-1 2021-01-1 2021-01-1 IDA / 59870 Post Request for Bids 1,170,000.00 432,020.22 Signed .700 lots d'équipements de alternative fishing practices al Envelope 4 6 5 6 9 0 4 3 1 9 0 base pour la sécurité en mer and livelihoods activities MG-MRHP-192172-GO-RFQ / Achat de 15.000 Caches bou Component 4. Project mana Request for Quot Single Stage - One 2020-09-2 2020-11-1 2021-05-1 IDA / 59870 Post Limited 11,500.00 0.00 Canceled che avec logo SWIOFish2 po gement and coordination ations Envelope 2 7 6 ur les trois (03) UGL's et l'U GP du projet SWIOFish2 MG-MRHP-119300 RELANCE -GO-RFB / Acquisition des ve Component 2. Strengthenin Single Stage - One Under Imple 2021-01-1 2021-02-1 2021-01-2 2021-02-1 2021-03-0 2021-03-2 2021-04-0 2021-05-1 2021-11-0 dettes réparties en 02 Lots : IDA / 59870 g capacities for priority fish Post Request for Bids Limited 551,500.00 0.00 Envelope mentation 9 5 4 6 7 2 6 1 7 • Lot1 : 07 vedettes coques eries management rigides ; • Lot2 : 02 vedettes rapides semi-rigides. MG-MRHP-218714-GO-RFB / Component 2. Strengthenin Single Stage - One 2021-03-0 2021-03-3 2021-03-0 2021-04-0 2021-04-0 2021-05-0 2021-05-0 2021-07-1 2021-06-0 2021-11-0 2021-08-2 Acquisition des matériels inf IDA / 59870 g capacities for priority fish Post Request for Bids Open - National 316,100.00 402,663.35 Signed Envelope 1 0 6 6 5 3 5 6 9 6 3 ormatiques 2020 et 2021 eries management MG-MRHP-119306-GO-RFQ / Component 3. Strengthenin Appui en biens et équipeme g capacities for engaging in Request for Quot Single Stage - One Pending Imp 2021-03-1 2021-05-0 2021-11-0 nts des groupements formel IDA / 59870 Post Limited 6,400.00 0.00 alternative fishing practices ations Envelope lementation 4 9 5 s: 32/ répartis en 2 Lots: Lot and livelihoods activities 1: Glacières; Lot 2: Couteau x MG-MRHP-203606-GO-RFQ / Component 2. Strengthenin Request for Quot Single Stage - One 2021-03-2 2021-05-2 2021-04-2 2021-07-1 2021-05-0 Acquisitions des téléphones IDA / 59870 g capacities for priority fish Post Open - National 19,200.00 17,632.53 Completed ations Envelope 0 9 0 3 1 mobiles pour l'UGP- SRPA et eries management RPA MG-MRHP-222323-GO-RFQ / Component 2. Strengthenin Acquisition d'une vedette et Request for Quot Single Stage - One Pending Imp 2021-04-0 2021-06-2 2021-09-0 IDA / 59870 g capacities for priority fish Post Limited 45,000.00 0.00 des autres équipements pou ations Envelope lementation 5 3 6 eries management r la prospections de nouvell e zone de pêche MG-MRHP-216847-GO-RFB / Component 3. Strengthenin Achat, installation et mainte g capacities for engaging in Open - Internation Single Stage - One 2021-04-1 2021-03-3 2021-04-2 2021-03-3 2021-06-0 2021-05-1 2021-06-2 2021-09-1 2021-07-3 2021-10-2 2022-01-2 IDA / 59870 Post Request for Bids 1,615,000.00 1,541,854.13 Signed nance d'équipements photo alternative fishing practices al Envelope 5 0 0 1 4 7 5 3 0 3 6 voltaïque pour 20 kiosques and livelihoods activities multiservices MG-MRHP-224078-GO-RFB / Component 3. Strengthenin Achat, installation et mainte g capacities for engaging in Open - Internation Single Stage - One 2021-04-1 2021-03-3 2021-04-2 2021-03-3 2021-06-0 2021-05-1 2021-07-0 2021-07-1 2021-08-0 2021-10-1 2022-02-0 IDA / 59870 Post Request for Bids 990,300.00 873,533.21 Signed nance d'équipements frigorif alternative fishing practices al Envelope 5 0 0 1 4 8 4 2 8 6 4 iques et de glace pour 20 ki and livelihoods activities osques multiservices MG-MRHP-227238-GO-RFB / Component 3. Strengthenin Fourniture et livraison des é g capacities for engaging in Open - Internation Single Stage - One 2021-05-1 2021-05-1 2021-05-2 2021-05-1 2021-07-0 2021-07-1 2021-07-3 2021-11-3 2021-09-0 2022-01-1 2022-03-0 IDA / 59870 Post Request for Bids 1,200,000.00 780,301.00 Signed quipements de base pour la alternative fishing practices al Envelope 5 7 0 8 1 9 1 0 4 7 3 sécurité en mer pour l'anné and livelihoods activities e 2021 et 2022 MG-MRHP-231608-GO-RFB / Component 2. Strengthenin Open - Internation Single Stage - One 2021-05-1 2022-05-1 2021-05-1 2022-05-1 2021-06-3 2022-06-3 2021-07-3 2022-09-1 2021-09-0 2022-03-0 Matériels et équipements po IDA / V0500 g capacities for priority fish Post Request for Bids 680,000.00 0.00 Signed al Envelope 4 0 9 6 0 0 0 3 3 2 ur laboratoire CEDP-CDA et eries management USTA Page 3 MG-MRHP-119240 BIS-GO-R Component 2. Strengthenin FB / Renforcement du Centr Single Stage - One 2021-03-2 2021-03-3 2021-04-3 2021-05-3 2021-07-0 2021-10-0 IDA / 59870 g capacities for priority fish Post Request for Bids Open - National 580,000.00 0.00 Canceled e de Développement de l'Aq Envelope 6 1 0 0 4 2 eries management uaculture (CDA) -Equipemen t de recherche MG-MRHP-28156-GO-UN//-M Component 2. Strengthenin UN Agencies (Dir 2020-11-0 2020-11-2 2021-01-2 2021-07-2 G-PM-04 / Matériels et équip IDA / 59870 g capacities for priority fish Post Direct 50,000.00 0.00 Canceled ect) 2 3 5 4 ements pour laboratoire CE eries management DP MG-MRHP-232523-GO-RFQ / Component 2. Strengthenin Request for Quot Single Stage - One Pending Imp 2021-05-2 2021-07-2 2021-10-0 Acquisition d'une vedette fri IDA / 59870 g capacities for priority fish Post Limited 73,000.00 0.00 ations Envelope lementation 5 0 3 gorifique CDPHM eries management MG-MRHP-231602-GO-RFQ / Component 2. Strengthenin Request for Quot Single Stage - One Pending Imp 2021-05-2 2021-07-2 2022-01-1 Acquisition de Drones pour IDA / D1720 g capacities for priority fish Post Limited 26,000.00 0.00 ations Envelope lementation 5 0 6 CSC, formation et service ap eries management rès vente MG-MRHP-232525-GO-RFQ / Component 2. Strengthenin Acquisition des matériels ro Request for Quot Single Stage - One Pending Imp 2021-05-2 2021-07-2 2021-10-1 IDA / 59870 g capacities for priority fish Post Open - National 86,000.00 0.00 ulants ( 02 camions Frigorifi ations Envelope lementation 6 1 9 eries management ques de capacité 5 tonnes) pour les sites du CDPHM MG-MRHP-232534-GO-RFQ / Component 4. Project mana Request for Quot Single Stage - One 2021-05-2 2021-12-0 2021-07-2 2022-03-1 2022-01-1 Acquisition et installation d' IDA / Q9790 Post Open - National 50,000.00 20,955.96 Signed gement and coordination ations Envelope 5 9 0 2 6 un logiciel de suivi évaluatio n MG-MRHP-119295-GO-RFQ / Component 2. Strengthenin Request for Quot Single Stage - One 2021-03-1 2021-05-1 2021-11-0 Achat de Lot d'équipements IDA / 59870 g capacities for priority fish Post Limited 10,000.00 0.00 Canceled ations Envelope 5 0 6 pour laboratoire USTA eries management MG-MRHP-119300 RELANCE Component 2. Strengthenin LOT2-GO-RFB / Acquisition d Single Stage - One 2021-11-3 2021-12-1 2021-12-0 2021-12-2 2021-12-3 2022-03-1 2022-01-3 2022-03-0 2022-06-0 TF / A4588 g capacities for priority fish Post Request for Bids Open - National 170,000.00 0.00 Canceled e 02 vedettes rapides semi-r Envelope 0 7 1 1 1 0 0 6 4 eries management igides pour CSP (Relance Lot 2) MG-MRHP-262317-GO-RFQ / Component 2. Strengthenin Acquisition des matériels inf Request for Quot Single Stage - One 2021-12-0 2021-12-0 2022-01-3 2022-04-3 IDA / 59870 g capacities for priority fish Post Open - National 93,600.00 0.00 Canceled ormatiques 2020 et 2021 (re ations Envelope 5 9 0 0 eries management lance lot 8: tablettes) MG-MRHP-284470-GO-RFQ / Component 2. Strengthenin Single Stage - One Under Imple 2022-04-1 2022-05-0 2022-04-2 2022-05-3 2022-06-0 2022-07-0 2022-08-0 2023-02-0 Acquisition mobiliers de bur IDA / 59870 g capacities for priority fish Post Request for Bids Open - National 427,553.00 0.00 Envelope mentation 5 6 0 0 1 1 5 1 eau pour les bureaux admini eries management stratifs 2022-2023 Component 3. Strengthenin MG-MRHP-28421-GO-RFB// g capacities for engaging in Single Stage - One Pending Imp 2020-09-1 2020-09-2 2020-11-0 2020-12-0 2021-01-0 2021-07-0 MG-PM-99 / Acquisition des IDA / V0500 Post Request for Bids Open - National 500,000.00 0.00 alternative fishing practices Envelope lementation 7 2 3 3 7 6 kits de panneaux solaires and livelihoods activities MG-MRHP-119315-GO-RFQ / Component 3. Strengthenin Renforcement de l'unité de g capacities for engaging in Request for Quot Single Stage - One Pending Imp 2022-05-0 2022-06-3 2022-12-2 IDA / 59870 Post Limited 55,000.00 0.00 gestion communautaire en b alternative fishing practices ations Envelope lementation 5 0 7 iens et équipements : 22 and livelihoods activities MG-MRHP-289660-GO-RFQ / Component 3. Strengthenin Équipements et outils de for g capacities for engaging in Request for Quot Single Stage - One Pending Imp 2022-04-2 2022-06-1 2022-12-1 IDA / 59870 Post Open - National 100,000.00 0.00 mation de technique de pêc alternative fishing practices ations Envelope lementation 3 8 5 he: palangre and livelihoods activities MG-MRHP-289646-GO-RFQ / Component 3. Strengthenin Equipement pour la commer g capacities for engaging in Request for Quot Single Stage - One Pending Imp 2022-04-2 2022-06-1 2022-12-1 IDA / 59870 Post Open - National 40,000.00 0.00 cialisation des produits de p alternative fishing practices ations Envelope lementation 1 6 3 êche and livelihoods activities MG-MRHP-231589-GO-RFQ / Component 2. Strengthenin Acquisition de 20 tablettes Request for Quot Single Stage - One Pending Imp 2022-07-0 2022-08-3 2022-10-3 IDA / V0500 g capacities for priority fish Post Open - National 37,000.00 0.00 marinisées pour le Centre d ations Envelope lementation 6 1 0 eries management e Surveillance de Pêche MG-MRHP-119303-GO-RFQ / Component 2. Strengthenin Request for Quot Single Stage - One Pending Imp 2022-11-0 2023-01-0 2023-06-3 Dotation et moyens d'équip TF / A4588 g capacities for priority fish Post Limited 48,000.00 0.00 ations Envelope lementation 6 1 0 ement pour les membres du eries management CSC : 24 MG-MRHP-119300_2ÈME RE Component 2. Strengthenin LANCE LOT2-GO-RFB / Acqui Open - Internation Single Stage - One Under Imple 2022-05-3 2022-05-2 2022-06-0 2022-05-2 2022-07-1 2022-07-1 2022-08-0 2022-09-1 2022-12-1 TF / A4588 g capacities for priority fish Post Request for Bids 170,000.00 0.00 sition de 02 vedettes rapide al Envelope mentation 0 3 4 5 9 1 9 3 2 eries management s semi-rigides pour CSP MG-MRHP-262317-GO-RFQ- 2ÈME RELANCE / ACQUISITI Component 2. Strengthenin ON DES TABLETTES POUR C Request for Quot Single Stage - One Pending Imp 2022-06-0 2022-07-1 2022-09-1 IDA / 59870 g capacities for priority fish Post Open - National 100,000.00 0.00 ENTRE DE SURVEILLANCE D ations Envelope lementation 4 6 4 eries management E PÊCHE, STATISTIQUE ET 1 3 RÉGIONS CÔTIÈRES DE L’U GP SWIOFISH2 MG-MRHP-296825-GO-RFQ / Component 2. Strengthenin Acquisition des smartphones Request for Quot Single Stage - One 2022-06-1 2022-10-2 2022-08-0 2022-09-0 TF / A4588 g capacities for priority fish Post Open - National 30,000.00 0.00 Signed pour la collecte des données ations Envelope 3 7 8 7 eries management pour le Service d'Etude MPE B MG-MRHP-119299-GO-RFQ / Matériels d'échantillonnages Component 2. Strengthenin Request for Quot Single Stage - One Under Imple 2022-06-2 2023-04-1 2022-08-1 2022-08-2 pour Services d'Etudes (Ex- TF / A4588 g capacities for priority fish Post Open - National 40,000.00 0.00 ations Envelope mentation 1 2 6 2 USTA) et Enquêteurs pour St eries management atistique et Kit d'Inspection pour CSP MG-MRHP-256429-GO-RFQ / Component 2. Strengthenin Request for Quot Single Stage - One 2021-10-2 2021-12-0 2021-12-1 2022-01-1 Acquisition de 20 VTT pour l TF / A4588 g capacities for priority fish Post Open - National 6,000.00 0.00 Canceled ations Envelope 3 9 8 7 es antennes USTA eries management MG-MRHP-307043-GO-RFB / Fourniture, Installation, Mise en service et Maintenance d Component 3. Strengthenin e vingt-six (26) infrastructur g capacities for engaging in Open - Internation Single Stage - One Under Imple 2022-09-2 2022-10-3 2022-10-0 2022-10-3 2022-11-1 2022-12-1 2023-01-1 2023-07-1 IDA / 59870 Post Request for Bids 1,100,000.00 0.00 es frigorifiques dans les loca alternative fishing practices al Envelope mentation 9 1 4 1 5 5 9 8 lités de pêcheurs dans les Z and livelihoods activities ones Ultra Prioritaires (ZUP) sur deux (02) régions de MA DAGASCAR : ANALANJIROFO - DIANA MG-MRHP-307036-GO-RFB / Fourniture, Installation, Mise en service et Maintenance d Component 3. Strengthenin e vingt-six (26) infrastructur g capacities for engaging in Open - Internation Single Stage - One Under Imple 2022-09-2 2022-10-2 2022-10-0 2022-10-3 2022-11-1 2022-12-1 2022-12-1 2023-01-1 2023-07-1 IDA / 59870 Post Request for Bids 1,800,000.00 0.00 es énergétiques dans les loc alternative fishing practices al Envelope mentation 9 7 4 1 5 4 5 9 8 alités de pêcheurs dans les and livelihoods activities Zones Ultra Prioritaires (ZUP ) sur deux (02) régions de M ADAGASCAR : ANALANJIROF O - DIANA MG-MRHP-329768-GO-RFQ / Component 3. Strengthenin Acquisition matériels de co g capacities for engaging in Request for Quot Single Stage - One Pending Imp 2022-12-1 2023-02-0 2023-08-0 IDA / 59870 Post Open - National 5,000.00 0.00 mmunication de la météo m alternative fishing practices ations Envelope lementation 5 9 8 arine: Panneau SAP - Téléph and livelihoods activities one solaire - radio VHF MG-MRHP-329336-GO-RFB / Outil et équipement de valor Component 3. Strengthenin isation et commercialisation g capacities for engaging in Single Stage - One Under Imple 2023-01-1 2023-02-0 2023-01-1 2023-02-0 2023-02-1 2023-03-1 2023-04-2 2023-07-1 IDA / 59870 Post Request for Bids Open - National 500,000.00 0.00 compose de 400 bicyclette à alternative fishing practices Envelope mentation 0 3 5 8 4 6 0 9 grande roue, 250 Glacière 5 and livelihoods activities 0litres et 150 bac ajouré 70li tre MG-MRHP-256423-GO-DIR / Component 2. Strengthenin 2022-05-0 2022-05-1 2022-06-1 2022-10-1 Acquisition de 33 motos 5 TF / A4588 g capacities for priority fish Post Direct Selection Direct 70,000.00 0.00 Canceled 6 1 5 3 motos eries management MG-MRHP-332050-GO-RFB / Acquisition des matériels ro Component 2. Strengthenin Single Stage - One Under Imple 2023-01-1 2023-02-0 2023-01-1 2023-02-0 2023-02-1 2023-03-0 2023-04-1 2023-07-1 ulants répartis en 2 Lots: IDA / 59870 g capacities for priority fish Post Request for Bids Open - National 495,000.00 0.00 Envelope mentation 0 3 5 6 4 7 1 0 • Lot 01: 05 véhicules 4*4 eries management • Lot 02: 45 motos MG-MRHP-338246-GO-RFB / Component 2. Strengthenin Open - Internation Single Stage - One Under Imple 2023-02-0 2023-02-1 2023-02-0 2023-02-1 2023-03-1 2023-03-1 2023-03-1 2023-05-2 2023-03-2 2023-07-2 Acquisition de matériels info IDA / 59870 g capacities for priority fish Post Request for Bids 490,000.00 0.00 al Envelope mentation 3 0 8 3 0 3 5 5 5 3 rmatiques 2022 et 2023 eries management MG-MRHP-331442-GO-RFB / La fourniture, Livraison, Inst allation et Mise en service d Component 3. Strengthenin e 200 lampadaires solaires g capacities for engaging in Single Stage - One Under Imple 2023-01-1 2023-02-1 2023-01-1 2023-02-1 2023-02-1 2023-03-0 2023-03-1 2023-08-0 IDA / 59870 Post Request for Bids Open - National 140,000.00 0.00 dans les localités des Zones alternative fishing practices Envelope mentation 0 1 5 3 4 1 1 8 Ultra Prioritaires des pêcheu and livelihoods activities rs dans (03) trois Régions à Madagascar : MELAKY - DIA NA - ANALANJIROFO MG-MRHP-338964-GO-DIR / Component 3. Strengthenin Equipement et d'outils de pê g capacities for engaging in Under Imple 2023-01-3 2023-02-2 2023-02-0 2023-02-2 2023-02-2 2023-07-2 che: 20.000 kits composés d IDA / 59870 Post Direct Selection Direct - National 436,800.00 0.00 alternative fishing practices mentation 1 4 5 4 4 4 e palmes réglable, masque and livelihoods activities de plongé, tuba et sac de tr ansport MG-MRHP-338245-GO-RFB / Component 3. Strengthenin Outils de valorisation compo g capacities for engaging in Single Stage - One Under Imple 2023-02-0 2023-02-1 2023-02-0 2023-02-1 2023-03-1 2023-03-1 2023-03-1 2023-03-2 2023-03-2 2023-04-0 IDA / 59870 Post Request for Bids Open - National 650,000.00 0.00 sé de 325 broyeurs à disque alternative fishing practices Envelope mentation 3 0 8 3 0 3 5 8 5 3 , à percussion et de 125 pell and livelihoods activities etiseur à pédale MG-MRHP-338984-GO-RFB / La fourniture, Livraison, Inst allation et Mise en service d Component 3. Strengthenin e 20 kits de congélateurs sol g capacities for engaging in Single Stage - One Under Imple 2023-01-3 2023-02-1 2023-02-0 2023-02-1 2023-03-0 2023-03-1 2023-03-2 2023-08-2 IDA / 59870 Post Request for Bids Open - National 50,000.00 0.00 aires dans les localités des Z alternative fishing practices Envelope mentation 1 1 2 3 4 4 9 6 ones Ultra Prioritaires des p and livelihoods activities êcheurs dans (03) trois Régi ons à Madagascar , Region MELAKY - DIANA - ANALANJI ROFO MG-MRHP-346374-GO-RFQ / Component 3. Strengthenin Acquisition de 500 téléphon g capacities for engaging in Request for Quot Single Stage - One Pending Imp 2023-03-1 2023-04-3 2023-06-2 IDA / 59870 Post Open - National 100,000.00 0.00 es solaires et 300 radios VH alternative fishing practices ations Envelope lementation 9 0 9 F and livelihoods activities MG-MRHP-346378-GO-DIR / Fourniture et installation, Fo rmation des points focaux et Component 3. Strengthenin accompagnement pour la mi g capacities for engaging in Under Imple 2023-03-1 2023-03-1 2023-03-1 2023-03-1 2023-04-1 2023-08-1 IDA / 59870 Post Direct Selection Direct - National 1,975,000.00 0.00 se en service de 3000 pann alternative fishing practices mentation 4 4 9 4 6 4 eaux agrometeorologique d and livelihoods activities e type MITAO FORECAST (pa nneaux SAP) dans les 14 rég ions côtières de Madagascar MG-MRHP-355024-GO-RFB / Component 3. Strengthenin Acquisition d'équipements p g capacities for engaging in Open - Internation Single Stage - One Pending Imp 2023-05-1 2023-05-2 2023-07-0 2023-07-1 2023-07-2 2023-09-2 our la mise en œuvre de l'Ac IDA / 59870 Post Request for Bids 1,920,000.00 0.00 alternative fishing practices al Envelope lementation 6 1 5 5 7 9 tivité Génératrice des Reven and livelihoods activities us ( AGR) pour les pêcheurs. Component 3. Strengthenin MG-MRHP-361766-GO-DIR / g capacities for engaging in Pending Imp 2023-05-1 2023-05-2 2023-06-1 2023-08-2 Acquisition des divers matér IDA / 59870 Post Direct Selection Direct - National 900,000.00 0.00 alternative fishing practices lementation 8 8 2 6 iels de pêches and livelihoods activities MG-MRHP-362169-GO-RFB / Component 3. Strengthenin Acquisition et installation de g capacities for engaging in Single Stage - One Pending Imp 2023-05-2 2023-05-3 2023-06-2 2023-07-0 2023-07-1 2023-09-0 s matériels et équipements IDA / 59870 Post Request for Bids Open - National 290,000.00 0.00 alternative fishing practices Envelope lementation 5 0 9 4 1 9 pour le fonctionnement des i and livelihoods activities nfrastructures construites Page 4 MG-MRHP-362172-GO-RFB / Component 3. Strengthenin Renforcement de l'unité de g capacities for engaging in Single Stage - One Pending Imp 2023-05-2 2023-05-3 2023-06-2 2023-07-0 2023-07-1 2023-09-0 IDA / 59870 Post Request for Bids Open - National 300,000.00 0.00 gestion communautaire en b alternative fishing practices Envelope lementation 5 0 9 4 1 9 iens et équipements; and livelihoods activities NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Repor Loan / Credit Market Approa Procurement Pr Prequalificatio Estimated A Actual Amoun Process St Draft Pre-qualificatio Prequalification Eval Draft Bidding Docu Specific Procuremen Bidding Documents Proposal Submission Description Component Review Type Method t and Recommendati Signed Contract Contract Completion No. ch ocess n (Y/N) mount (US$) t (US$) atus n Documents uation Report ment / Justification t Notice / Invitation as Issued / Opening / Minutes on for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MG-MRHP-151759-NC-RFB / Component 2. Strengthenin Open - Internation Single Stage - One 2020-01-0 2020-01-2 2020-01-1 2020-01-2 2020-02-2 2020-03-1 2020-02-2 2020-06-1 2020-03-2 2020-11-2 2020-05-2 Analyse PC de l'eau de traite IDA / 59870 g capacities for priority fish Post Request for Bids 110,000.00 186,954.22 Signed al Envelope 6 9 1 9 5 6 6 5 2 6 1 ment ou de production (lot eries management N°1) MG-MRHP-151759BIS1-NC- Component 2. Strengthenin RFQ / Analyses officielles po Request for Quot Single Stage - One Pending Imp 2019-08-1 2019-10-2 2019-12-2 IDA / 59870 g capacities for priority fish Post Limited 100,000.00 0.00 ur le compte de l'Autorité Sa ations Envelope lementation 0 8 7 eries management nitaire Halieutique (ASH) rép artie en 9 Lots MG-MRHP-192432-NC-RFB / Analyses officielles relatives au contrôle de la qualité phy sico-chimique des eaux de tr Component 2. Strengthenin Open - Internation Single Stage - One Under Imple 2020-09-2 2021-10-1 2020-09-2 2021-10-1 2020-11-1 2021-12-0 2020-12-0 2021-01-0 2021-04-0 aitement et de production et IDA / 59870 g capacities for priority fish Post Request for Bids 309,750.00 0.00 al Envelope mentation 2 3 7 3 1 7 2 2 2 des résidus chimiques et co eries management ntaminants dans les produit s de la pêche et d’aquacultu re, conformément aux plans de surveillance nationaux 2 02 MG-MRHP-192435-NC-DIR / Analyses officielles relatives à la Recherche de Vibrio pot Component 2. Strengthenin entiellement entéropathogè Pending Imp 2020-09-2 2020-09-2 2020-11-2 2021-02-2 IDA / 59870 g capacities for priority fish Post Direct Selection Direct 7,860.00 0.00 nes dans les produits de la p lementation 2 7 5 3 eries management êche et d’aquaculture (crust acées : crabes et crevettes), conformément aux plans de surveillance nationaux 2020 MG-MRHP-196025-NC-DIR / Component 2. Strengthenin Diagnostic des maladies des Pending Imp 2020-10-0 2020-10-3 2020-11-2 2020-12-1 IDA / 59870 g capacities for priority fish Post Direct Selection Direct 47,000.00 0.00 crustacés dans le cadre de l lementation 9 0 6 1 eries management a réalisation du Plan de Surv eillance 2020 MG-MRHP-231600-NC-DIR / Component 2. Strengthenin Acquisition et installation d' Under Imple 2021-05-2 2021-05-2 2021-07-1 2022-07-1 IDA / V0500 g capacities for priority fish Post Direct Selection Direct 37,000.00 0.00 équipement des deux Patro mentation 0 5 4 4 eries management uilleurs (Atsantsa et Telonify )   à bord des navires MG-MRHP-231592-NC-DIR / Extension de l’application d Component 2. Strengthenin 2021-05-2 2021-05-2 2021-05-2 2021-06-1 2021-07-1 2021-10-2 2022-07-1 u système ERS du Centre de IDA / V0500 g capacities for priority fish Post Direct Selection Direct 36,600.00 47,559.62 Signed 0 7 5 4 4 2 4 Surveillance des Pêches de eries management Madagascar aux navires nati onaux et étrangers hors-UE MG-MRHP-289369-NC-DIR / Analyse officielle en laborat Component 2. Strengthenin oire de dosage des substan Under Imple 2022-04-1 2022-04-2 2022-04-1 2022-04-2 2022-05-2 2022-11-1 IDA / 59870 g capacities for priority fish Post Direct Selection Direct 30,000.00 0.00 ces interdites et résidus mé mentation 2 1 7 5 2 8 eries management dicamenteux et de dosage de résidus de pes ticides MG-MRHP-295994-NC-RFQ / ACHEMINEMENT DES PRELE VEMENTS DE PRODUITS DE LA PECHE POUR ANALYSES Component 2. Strengthenin OFFICIELLES DANS LE CADR Request for Quot Single Stage - One Pending Imp 2022-05-3 2022-07-2 2023-01-2 IDA / 59870 g capacities for priority fish Post Open - National 51,000.00 0.00 E DE LA REALISATION DES P ations Envelope lementation 0 5 1 eries management LANS DE SURVEILLANCE SA NITAIRES 2020 & 2021 DE L’ AUTORITE SANITAIRE HALIE UTIQUE JUSQU’AUX LABORA TOIRES ACCREDITES INTERN ATIONAUX RETENUS. Component 3. Strengthenin MG-MRHP-REG2022-NC-RFQ g capacities for engaging in Request for Quot Single Stage - One 2022-05-3 2022-05-3 2022-06-0 2022-06-0 2022-06-2 / Dédouanement de 20000 k IDA / 59870 Post Limited 100,000.00 93,478.02 Signed alternative fishing practices ations Envelope 1 1 6 8 1 it de sécurté en mer and livelihoods activities MG-MRHP-296834-NC-RFP / Firme pour la réparation des Component 2. Strengthenin Request for Quot Single Stage - One Pending Imp 2022-06-2 2022-08-1 2023-02-1 imprimantes photocopieurs, IDA / 59870 g capacities for priority fish Post Open - National 20,000.00 0.00 ations Envelope lementation 1 6 2 scanners, dupli copieurs,mat eries management ériels informatique et électr onique MG-MRHP-REG2020-NC-RFQ Component 4. Project mana Request for Quot Single Stage - One 2020-11-0 2020-11-0 2020-11-1 2020-11-2 2021-11-1 / Hébergement mail professi IDA / 59870 Post Limited 13,800.00 13,793.14 Signed gement and coordination ations Envelope 6 6 9 0 9 onnel du projet SWIOFish2 MG-MRHP-308415-NC-RFQ / Prestation de service en Age Component 2. Strengthenin Request for Quot Single Stage - One Pending Imp 2022-11-0 2022-12-3 2023-06-2 nce de Voyage ( Billet d'avio IDA / 59870 g capacities for priority fish Post Open - National 100,000.00 0.00 ations Envelope lementation 5 1 9 n) pour les voyages à l'étran eries management ger - Contrat Cadre Multi at tributaire de 12 mois- MG-MRHP-337984-NC-DIR / Component 2. Strengthenin Direct - Internatio Pending Imp 2023-01-2 2023-02-0 2023-03-0 2023-05-3 Support et Maintenance de l IDA / D1720 g capacities for priority fish Post Direct Selection 50,000.00 0.00 nal lementation 7 1 2 1 'application THEMIS-VMS pa eries management r CLS CONSULTING FIRMS Activity Reference No. / Short List and Draft Combined Evaluatio Loan / Credit Market Approa Contract Type Estimated Am Actual Amou Process Statu Expression of Interes Request for Proposal Opening of Technical Evaluation of Techni Description Component Review Type Method Terms of Reference Request for Proposal n Report and Draft N Signed Contract Contract Completion No. ch ount (US$) nt (US$) s t Notice s as Issued Proposals / Minutes cal Proposal s egotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MG-MRHP-14498-CS-QCBS// PA-13 / PA 13: Mise à jour de Component 2. Strengthenin Quality And Cost- Open - Internation 2017-05-3 2017-07-2 2017-09-1 2017-09-1 2017-09-2 2017-10-2 2018-10-2 la Stratégie d'aquaculture et IDA / Q9790 g capacities for priority fish Post 75,000.00 0.00 Canceled 2017-05-16 Based Selection al 0 8 1 3 2 0 0 élaboration de plan de dével eries management oppement des 03 filières aq uaculture MG-MRHP-14951-CS-LCS//P A65 / PA 65: Etudes techniq ues : - Clôture de l'enceinte DRRH Component 2. Strengthenin P Fénérive Least Cost Select Open - Internation 2017-12-1 2017-05-3 2017-07-2 2018-03-1 2017-08-2 2018-04-1 2017-08-2 2018-04-2 2017-09-1 2018-05-0 2017-10-0 2018-07-0 2018-04-0 2019-07-2 IDA / Q9790 g capacities for priority fish Post 35,000.00 25,756.66 Completed 2017-05-17 - Construction des Bureaux ion al 9 1 2 9 1 7 8 4 1 7 9 3 7 4 eries management de 06 DRRHP - Extension de l'ASH à Antsir anana et Morondava - Construction local pour bur eau UGP MG-MRHP-23760-CS-QCBS// MG-PM-117 / Recrutement d' Component 3. Strengthenin un Cabinet d'étude ou d'une g capacities for engaging in Quality And Cost- 2017-10-3 2017-10-0 2018-08-2 2017-12-1 2018-09-1 2018-01-0 2019-02-0 2018-02-0 2019-07-0 2018-03-2 2019-08-1 2018-05-0 2019-09-2 2020-04-3 ONG pour assurer les missio IDA / Q9790 Prior Open - National 600,000.00 677,965.07 Signed 2017-09-14 alternative fishing practices Based Selection 0 5 9 0 8 7 7 6 8 0 6 1 4 0 ns de l'AGEX pour l'appui à l and livelihoods activities a mise en œuvre du Plan d'A ménagement des Pêcheries de la Baie d'Antongil MG-MRHP-27282-CS-QCBS// Component 2. Strengthenin Quality And Cost- Open - Internation 2017-09-2 2017-11-2 2017-12-2 2017-08-0 2018-01-2 2018-02-2 2018-04-0 2019-04-0 PA61 / Appui à la mise en pl IDA / Q9790 g capacities for priority fish Prior 500,000.00 0.00 Canceled 2017-09-07 Based Selection al 8 6 4 4 3 7 3 3 ace des outils d'aménageme eries management nt des pêches MG-MRHP-28166-CS-QCBS// Component 2. Strengthenin Quality And Cost- Open - Internation 2018-01-0 2018-03-1 2018-04-0 2018-05-2 2018-07-0 2018-08-1 2019-08-1 MG-PM-14 / Recueil et analy IDA / D1720 g capacities for priority fish Post 25,000.00 0.00 Canceled 2017-12-15 Based Selection al 5 2 9 4 5 6 6 se des informations de base eries management avant-projet MG-MRHP-28168-CS-QCBS// Component 2. Strengthenin MG-PM-16 / Collecte des don Quality And Cost- Open - Internation Pending Implem 2018-01-0 2018-03-1 2018-04-0 2018-05-2 2018-07-0 2018-08-1 2019-08-1 IDA / D1720 g capacities for priority fish Post 20,000.00 0.00 2017-12-15 nées au niveau des régions Based Selection al entation 5 2 9 4 5 6 6 eries management prioritaires (Artfish) MG-MRHP-28170-CS-CQS// MG-PM-18 / Identification de s besoins en formation et él Component 2. Strengthenin Consultant Qualif Open - Internation 2018-01-1 2018-03-1 2018-04-1 2018-05-3 2018-11-2 aboration du plan de formati IDA / 59870 g capacities for priority fish Post 20,000.00 0.00 Canceled 2017-12-22 ication Selection al 2 9 8 0 6 on des agents de l'administr eries management ation (y compris Inventaire et contact des centres de fo rmation locaux et extérieurs ) MG-MRHP-28171-CS-CQS// MG-PM-19 / Etude sur l'ident ification et recensement des Component 3. Strengthenin bénéficiaires chaque année, g capacities for engaging in Consultant Qualif Open - Internation 2017-10-2 2017-12-0 2018-02-1 2019-05-3 2018-03-2 2019-09-0 2018-05-0 2019-09-1 2018-11-0 2020-11-0 IDA / 59870 Post 200,000.00 159,792.61 Completed 2017-11-15 du montant et des modalité alternative fishing practices ication Selection al 4 6 0 1 7 6 8 8 4 2 s de transfert financier, du and livelihoods activities montant minimal de filet soc ial pour les pêcheurs/acteur s filières affectés par les me sures de gestion MG-MRHP-28174-CS-CQS// Component 3. Strengthenin MG-PM-22 / Étude sur le circ g capacities for engaging in Consultant Qualif Open - Internation 2019-06-1 2017-12-2 2018-02-2 2018-04-1 2018-05-2 2018-11-1 IDA / 59870 Post 90,000.00 0.00 Canceled 2017-11-30 uit de commercialisation des alternative fishing practices ication Selection al 7 1 5 1 3 9 produits des pêches and livelihoods activities MG-MRHP-28175-CS-CQS// MG-PM-23 / Étude et enquêt e sur l'état des lieux des acc Component 3. Strengthenin idents en mer de la petite p g capacities for engaging in Consultant Qualif Open - Internation 2019-02-2 2017-12-2 2018-02-2 2019-02-2 2018-04-1 2019-06-1 2018-05-2 2019-06-1 2018-11-1 êche et aux éventuelles mes IDA / 59870 Post 120,000.00 50,244.29 Signed 2017-11-30 alternative fishing practices ication Selection al 6 1 5 6 1 4 3 4 9 ures déjà prises/analyse de and livelihoods activities s accidentologies/aspect inst itutionnel sur les responsabil ités de la petite pêche/ à titr e provisoire proposer les éq uipements MG-MRHP-28319-CS-QCBS// Component 3. Strengthenin MG-PM-25 / Diagnostic des b g capacities for engaging in Quality And Cost- Open - Internation 2019-03-1 2018-01-0 2018-03-1 2018-04-0 2018-05-2 2018-07-0 2018-08-1 2019-08-1 esoins en activités alternativ IDA / 59870 Post 150,000.00 0.00 Canceled 2017-12-15 alternative fishing practices Based Selection al 5 5 2 9 4 5 6 6 es adaptées pour chaque ré and livelihoods activities gion ultra prioritaire (exécut ée par AGEX) MG-MRHP-28322-CS-QCBS// Component 3. Strengthenin MG-PM-27 / Détermination d g capacities for engaging in Quality And Cost- Open - Internation 2017-01-2 2017-11-2 2018-01-2 2017-09-0 2018-02-2 2017-10-1 2018-04-0 2017-10-1 2018-05-2 2018-08-0 2018-07-0 2018-09-2 2019-07-0 2019-07-2 IDA / 59870 Post 60,000.00 66,260.37 Completed 2017-10-30 es outils financiers d'appui a alternative fishing practices Based Selection al 4 0 5 6 2 0 8 0 0 8 1 5 1 3 ux filières et activités altern and livelihoods activities atives MG-MRHP-28323-CS-CQS// Component 3. Strengthenin MG-PM-28 / Étude sur l'amél g capacities for engaging in Consultant Qualif Open - Internation 2017-11-0 2018-01-1 2018-02-2 2018-04-0 2018-10-0 IDA / 59870 Post 60,000.00 0.00 Canceled 2017-10-16 ioration des conditions de vi alternative fishing practices ication Selection al 6 1 5 8 5 e sociale des communautés and livelihoods activities de pêcheur MG-MRHP-28330-CS-QCBS// MG-PM-31 / État de lieux des Component 3. Strengthenin petites infrastructures de pê g capacities for engaging in Quality And Cost- Open - Internation 2019-04-0 2017-11-2 2019-04-1 2018-01-2 2019-06-0 2018-02-2 2019-07-1 2018-04-0 2019-07-1 2018-05-2 2019-09-1 2018-07-0 2019-10-1 2019-07-0 2020-11-0 IDA / 59870 Post 120,000.00 113,351.50 Completed 2017-10-30 ches et les besoins des com alternative fishing practices Based Selection al 4 0 5 5 6 2 7 8 8 0 3 1 0 1 3 munautés cibles en petites i and livelihoods activities nfrastructures de pêche et c ommunautaires MG-MRHP-28333-CS-QCBS// Component 3. Strengthenin MG-PM-32 / Étude des besoi g capacities for engaging in Quality And Cost- Open - Internation 2017-11-2 2018-01-2 2018-02-2 2018-04-0 2018-05-2 2018-07-0 2019-07-0 IDA / 59870 Post 200,000.00 0.00 Canceled 2017-10-30 ns communautaires (une ét alternative fishing practices Based Selection al 0 5 2 8 0 1 1 ude par district) and livelihoods activities Page 5 MG-MRHP-28336-CS-CQS// Component 3. Strengthenin MG-PM-33 / Préparation du p g capacities for engaging in Consultant Qualif Open - Internation 2017-11-2 2018-01-2 2018-03-1 2018-04-2 2018-10-1 IDA / 59870 Post 60,000.00 0.00 Canceled 2017-10-30 lan local d'électrification co alternative fishing practices ication Selection al 0 5 1 2 9 mmunautaire : étude et rap and livelihoods activities ports MG-MRHP-28342-CS-CQS// MG-PM-39 / Études techniqu Component 4. Project mana Consultant Qualif 2017-11-2 2018-01-2 2018-03-1 2018-04-2 2018-10-1 IDA / 59870 Post Open - National 13,500.00 0.00 Canceled 2017-10-30 es pour la construction d'un gement and coordination ication Selection 0 5 1 2 9 local pour bureau UGP MG-MRHP-28343-CS-LCS//M G-PM-40 / Études d'impacts Component 4. Project mana Least Cost Select Open - Internation 2018-01-0 2018-03-1 2018-04-0 2018-05-0 2018-06-2 2018-08-0 2019-01-2 IDA / 59870 Post 10,000.00 0.00 Canceled 2017-12-15 environnementales et social gement and coordination ion al 5 2 9 9 0 1 8 es pour la construction d'un local pour bureau UGP MG-MRHP-27288-CS-QCBS// Component 2. Strengthenin PA62 / Appui à la mise en œ Quality And Cost- Open - Internation 2016-09-0 2017-09-2 2017-11-1 2017-06-0 2017-12-0 2017-07-1 2018-01-0 2017-08-0 2018-02-1 2017-10-2 2018-03-1 2018-05-0 2019-03-1 2019-07-1 IDA / Q9790 g capacities for priority fish Post 255,000.00 234,182.87 Completed 2017-09-07 uvre du plan d'amélioration Based Selection al 6 8 1 6 9 7 8 4 2 0 9 2 9 6 eries management de la pêcherie crevettière MG-MRHP-28654-CS-CQS// MG-PM-113 / Mise à jour de l Component 2. Strengthenin Consultant Qualif 2018-02-2 2018-04-2 2018-06-1 2018-07-2 2019-01-2 a Stratégie Nationale de l'Aq IDA / 59870 g capacities for priority fish Post Open - National 30,000.00 0.00 Canceled 2018-02-01 ication Selection 2 9 3 5 1 uaculture (Consultant natio eries management nal + Réunions (1 consultati on, 1 validation) MG-MRHP-28656-CS-CQS// MG-PM-114 / Étude sur les p Component 2. Strengthenin rocédures administratives ré Consultant Qualif 2018-02-2 2018-04-2 2018-06-1 2018-07-2 2019-01-1 IDA / 59870 g capacities for priority fish Post Open - National 50,000.00 0.00 Canceled 2018-01-30 gissant l'accès aux ressourc ication Selection 0 7 1 3 9 eries management es et examen des options et recommandations (6 outils d e gestion) MG-MRHP-28657-CS-CQS// Component 2. Strengthenin MG-PM-115 / Diagnostic du Consultant Qualif 2018-06-2 2018-08-2 2018-10-1 2018-11-2 2019-05-2 IDA / 59870 g capacities for priority fish Post Open - National 30,000.00 0.00 Canceled 2018-06-01 secteur dans le domaine fin ication Selection 2 7 1 2 1 eries management ancier local, régional, intern ational MG-MRHP-28659-CS-CQS// Component 2. Strengthenin MG-PM-116 / Élaboration de Consultant Qualif 2018-02-2 2018-04-2 2018-05-2 2018-07-0 2019-01-0 IDA / 59870 g capacities for priority fish Post Open - National 10,000.00 0.00 Canceled 2018-01-30 la stratégie d'adaptation du ication Selection 0 7 7 8 4 eries management secteur pêche face au chan gement climatique MG-MRHP-28661-CS-CQS// Component 2. Strengthenin Consultant Qualif 2018-06-2 2018-08-2 2018-09-2 2018-11-0 2019-05-0 MG-PM-118 / Recueil et anal IDA / D1720 g capacities for priority fish Post Open - National 30,000.00 0.00 Canceled 2018-06-01 ication Selection 2 7 6 7 6 yse des informations de bas eries management e avant-projet MG-MRHP-28663-CS-CQS// MG-PM-119 / Développemen Component 2. Strengthenin t et mise en œuvre du systè Consultant Qualif 2018-04-2 2018-06-0 2018-07-0 2018-08-1 2019-02-0 IDA / D1720 g capacities for priority fish Post Open - National 5,000.00 0.00 Canceled 2018-04-02 me de collecte de données p ication Selection 3 6 6 0 6 eries management our les pêcheries traditionne lles, y compris une stratégie d'échantillonnage approprié e MG-MRHP-28665-CS-CQS// Component 2. Strengthenin MG-PM-120 / Collecte des do Consultant Qualif 2018-03-2 2018-05-0 2018-06-0 2018-07-0 2019-01-0 IDA / D1720 g capacities for priority fish Post Open - National 35,000.00 0.00 Canceled 2018-03-01 nnées au niveau des régions ication Selection 2 5 4 9 5 eries management prioritaires (Artfish) MG-MRHP-28668-CS-CQS// Component 2. Strengthenin Consultant Qualif 2018-02-2 2018-04-0 2018-05-0 2018-06-1 2018-12-0 MG-PM-121 / Mise à jour de l IDA / D1720 g capacities for priority fish Post Open - National 50,000.00 0.00 Canceled 2018-02-01 ication Selection 2 7 7 1 8 'Enquête Cadre Nationale eries management MG-MRHP-28669-CS-CQS// Component 2. Strengthenin MG-PM-122 / Développemen Consultant Qualif 2018-03-0 2018-04-2 2018-05-2 2018-06-2 2018-12-2 IDA / D1720 g capacities for priority fish Post Open - National 30,000.00 0.00 Canceled 2018-02-15 t et mise en œuvre de la col ication Selection 8 1 1 5 2 eries management lecte de données pour les pr oduits post-capture MG-MRHP-28679-CS-CQS// Component 2. Strengthenin MG-PM-126 / Développemen Consultant Qualif 2018-09-2 2018-11-0 2018-12-0 2019-01-1 2019-07-1 IDA / D1720 g capacities for priority fish Post Open - National 10,000.00 0.00 Canceled 2018-09-03 t d'un système d'information ication Selection 4 7 7 1 0 eries management halieutique modulaire MG-MRHP-28682-CS-CQS// Component 2. Strengthenin Consultant Qualif 2018-05-2 2018-07-0 2018-08-0 2018-09-0 2019-03-0 MG-PM-127 / Suivi du systè IDA / D1720 g capacities for priority fish Post Open - National 10,000.00 0.00 Canceled 2018-04-30 ication Selection 1 4 3 7 6 me d'information halieutiqu eries management e modulaire MG-MRHP-28686-CS-CQS// Component 2. Strengthenin MG-PM-129 / Étude d'impact Consultant Qualif 2018-06-0 2018-07-1 2018-08-1 2018-09-2 2019-03-2 IDA / 59870 g capacities for priority fish Post Open - National 66,000.00 0.00 Canceled 2018-05-15 environnemental et social d ication Selection 5 9 8 2 1 eries management e l'extension ou de la constr uction MG-MRHP-28687-CS-QCBS// Component 2. Strengthenin Quality And Cost- Open - Internation 2018-04-0 2018-06-1 2018-07-0 2018-08-0 2018-09-1 2018-10-3 2019-10-3 MG-PM-130 / Élaboration str IDA / 59870 g capacities for priority fish Post 50,000.00 0.00 Canceled 2018-03-15 Based Selection al 5 0 8 7 8 0 0 atégie nationale de recherch eries management es halieutiques MG-MRHP-28690-CS-CQS// Component 2. Strengthenin Consultant Qualif Open - Internation 2018-07-0 2018-08-1 2018-09-1 2018-10-2 2019-04-2 MG-PM-134 / Etude sur les IDA / 59870 g capacities for priority fish Post 30,000.00 0.00 Canceled 2018-06-15 ication Selection al 6 9 8 3 1 mesures de gestion des pou eries management lpes MG-MRHP-28691-CS-QCBS// Component 2. Strengthenin MG-PM-135 / Avis scientifiqu Quality And Cost- Open - Internation 2018-07-2 2018-09-2 2018-10-2 2018-11-2 2019-01-0 2019-02-0 2020-02-0 IDA / 59870 g capacities for priority fish Post 30,000.00 0.00 Canceled 2018-06-29 e pour la gestion des pêcher Based Selection al 0 4 2 1 2 6 6 eries management ies de langoustes, dans les sites prioritaires MG-MRHP-28693-CS-QCBS// MG-PM-137 / Révision du sys Component 2. Strengthenin Quality And Cost- Open - Internation 2018-02-0 2018-04-1 2018-05-1 2018-06-0 2018-07-2 2018-08-2 2019-08-2 tème de suivi de la pêche cr IDA / 59870 g capacities for priority fish Post 75,000.00 0.00 Canceled 2018-01-15 Based Selection al 5 2 0 9 1 5 5 evettière traditionnelle (PCT eries management ) et élargissement à toutes l es zones de pêche MG-MRHP-28694-CS-CQS// Component 2. Strengthenin MG-PM-138 / Révision par le Consultant Qualif Open - Internation 2018-02-2 2018-04-0 2018-05-0 2018-06-1 2018-12-0 IDA / 59870 g capacities for priority fish Post 75,000.00 0.00 Canceled 2018-02-01 s pairs des modèles d'évalu ication Selection al 2 7 7 1 8 eries management ation des stock de crevettes MG-MRHP-28695-CS-CQS// Component 2. Strengthenin MG-PM-139 / Etat des lieux e Consultant Qualif Open - Internation 2018-06-2 2018-08-0 2018-09-0 2018-10-0 2019-04-0 IDA / 59870 g capacities for priority fish Post 10,000.00 0.00 Canceled 2018-05-30 t évaluation des besoins du ication Selection al 0 3 2 7 5 eries management Ministère en moyens et équi pements MG-MRHP-28703-CS-QCBS// MG-PM-145 / Élaboration du Component 2. Strengthenin Quality And Cost- 2018-02-2 2018-04-2 2018-05-1 2018-07-0 2018-08-0 2018-09-1 2019-09-1 plan d'action national sur les IDA / 59870 g capacities for priority fish Post Open - National 60,000.00 0.00 Canceled 2018-01-30 Based Selection 0 0 8 2 6 0 0 requins, les oiseaux de mer, eries management les tortues mrines, (résolutio n CTOI) MG-MRHP-28706-CS-QCBS// Component 2. Strengthenin Quality And Cost- 2018-10-0 2018-12-1 2019-01-1 2019-02-2 2019-03-3 2019-05-0 2020-05-0 MG-PM-149 / Étude sur l'am IDA / 59870 g capacities for priority fish Post Open - National 20,000.00 0.00 Canceled 2018-09-17 Based Selection 8 3 0 4 1 5 4 élioration du protocole stand eries management ard de pêche MG-MRHP-28707-CS-CQS// MG-PM-150 / Étude sur l'éval Component 2. Strengthenin Consultant Qualif 2018-10-0 2018-11-2 2018-12-2 2019-01-2 2019-07-2 uation des impacts des diffé IDA / 59870 g capacities for priority fish Post Open - National 30,000.00 0.00 Canceled 2018-09-17 ication Selection 8 1 1 5 4 rents engins (palangres, filet eries management s, ...) sur les espèces menac ées (requins, tortues, ...) MG-MRHP-28709-CS-CQS// Component 2. Strengthenin MG-PM-128 / Étude techniqu Consultant Qualif 2018-03-0 2018-04-2 2018-05-2 2018-06-2 2018-12-2 IDA / 59870 g capacities for priority fish Post Open - National 67,500.00 0.00 Canceled 2018-02-15 e de l'extension ou construc ication Selection 8 1 1 5 2 eries management tion du bureau régional MG-MRHP-28713-CS-QCBS// Component 2. Strengthenin MG-PM-155 / Études techniq Quality And Cost- 2018-02-2 2018-04-2 2018-05-2 2018-07-0 2018-08-2 2018-10-0 2019-10-0 IDA / D1720 g capacities for priority fish Post Open - National 60,000.00 0.00 Canceled 2018-01-30 ues sur la stratégie de surve Based Selection 0 7 5 9 0 1 1 eries management illance et sur le fonctionnem ent du CSP MG-MRHP-28728-CS-CQS// Component 2. Strengthenin Consultant Qualif Open - Internation 2018-02-2 2018-04-2 2018-06-1 2018-07-2 2019-01-1 MG-PM-156 / Rédaction d'un IDA / 59870 g capacities for priority fish Post 15,000.00 0.00 Canceled 2018-01-30 ication Selection al 0 7 1 3 9 plan national de lutte contre eries management la pêche INN MG-MRHP-28732-CS-CQS// MG-PM-158 / Etude et élabor Component 2. Strengthenin ation de mécanisme structur Consultant Qualif Open - Internation 2018-02-2 2018-04-1 2018-05-1 2018-06-2 2018-12-2 IDA / 59870 g capacities for priority fish Post 50,000.00 0.00 Canceled 2018-01-30 el de plateforme de cogestio ication Selection al 0 2 2 3 0 eries management n des filières prioritaires (cra bes, poulpes, langoustes, ho lothuries, crevettes) MG-MRHP-28733-CS-QCBS// Component 2. Strengthenin Quality And Cost- 2018-03-0 2018-05-1 2018-06-1 2018-07-2 2018-09-0 2018-10-1 2019-10-1 MG-PM-163 / Suivi-évaluatio IDA / 59870 g capacities for priority fish Post Open - National 10,000.00 0.00 Canceled 2018-02-15 Based Selection 8 3 0 5 5 7 7 n des formations et recyclag eries management es réalisés MG-MRHP-28747-CS-QCBS// Component 3. Strengthenin MG-PM-172 / Mise en place g capacities for engaging in Quality And Cost- Open - Internation 2018-08-2 2018-10-2 2018-11-2 2019-01-0 2019-02-1 2019-03-3 2020-03-3 IDA / 59870 Post 25,000.00 0.00 Canceled 2018-07-30 d'une règlementation de bas alternative fishing practices Based Selection al 0 5 2 6 7 1 0 e concernant la sécurité en and livelihoods activities mer de la petite pêche MG-MRHP-28748-CS-QCBS// Component 3. Strengthenin MG-PM-173 / " Étude de mar g capacities for engaging in Quality And Cost- Open - Internation 2018-04-2 2018-06-2 2018-07-2 2018-09-0 2018-10-1 2018-11-2 2019-11-2 ché pour les produits de pêc IDA / 59870 Post 90,000.00 0.00 Canceled 2018-03-30 alternative fishing practices Based Selection al 0 5 3 6 8 9 9 he valorisés dans chaque ré and livelihoods activities gion ultra prioritaire " MG-MRHP-28763-CS-QCBS// Component 3. Strengthenin MG-PM-185 / Gestion et mis g capacities for engaging in Quality And Cost- Open - Internation 2018-11-2 2019-01-1 2019-02-1 2019-04-0 2019-05-0 2019-06-1 2020-06-0 IDA / V0500 Post 40,000.00 0.00 Canceled 2018-10-30 e en œuvre : Suivi évaluatio alternative fishing practices Based Selection al 0 8 5 1 6 0 9 n des bases de données and livelihoods activities MG-MRHP-28766-CS-LCS//M Component 4. Project mana Least Cost Select Open - Internation 2018-02-2 2018-04-0 2018-05-0 2018-06-0 2018-07-0 2018-08-1 2019-02-0 G-PM-189 / Audit externe de IDA / 59870 Post 15,000.00 0.00 Canceled 2018-01-30 gement and coordination ion al 0 5 3 2 7 1 7 s comptes du Projet MG-MRHP-14953-CS-LCS//P Component 2. Strengthenin Least Cost Select Open - Internation 2018-03-2 2018-05-1 2018-05-2 2018-05-2 2018-06-1 2018-07-1 2019-01-1 A67 / PA 67: Recensement d IDA / Q9790 g capacities for priority fish Post 75,000.00 0.00 Canceled 2018-03-15 ion al 9 3 0 7 7 5 1 es données au niveau des ré eries management gions prioritaires MG-MRHP-14945-CS-CQS//P Component 2. Strengthenin Consultant Qualif Open - Internation 2018-01-0 2018-03-1 2018-04-2 2018-06-0 2018-12-0 A 15 / PA 15: Recueillir et an IDA / Q9790 g capacities for priority fish Post 75,000.00 0.00 Canceled 2017-12-15 ication Selection al 5 2 6 7 4 alyser des informations de b eries management ase avant-projet MG-MRHP-86202-CS-QCBS// PA61 / Recrutement d'une fi Component 2. Strengthenin Quality And Cost- Open - Internation 2016-09-2 2018-12-2 2019-02-1 2017-06-0 2019-03-2 2017-07-1 2019-04-1 2017-08-0 2019-06-1 2018-07-0 2019-08-1 2018-10-1 2020-08-1 rme afin d'appuyer la mise e IDA / 59870 g capacities for priority fish Post 262,000.00 317,899.36 Terminated 2018-11-20 Based Selection al 0 0 8 6 0 7 9 4 8 5 7 2 6 n place d'outils d'aménage eries management ment des pêcheries à Mada gascar MG-MRHP-86206-CS-LCS//M Component 4. Project mana Least Cost Select Open - Internation 2019-02-0 2018-12-3 2019-03-1 2019-02-1 2019-04-2 2019-03-1 2019-06-1 2019-03-2 2019-08-2 2019-03-2 2019-11-1 2019-04-1 2020-05-0 2021-04-2 G-PM 88/18 / Audit externe IDA / 59870 Post 45,000.00 14,382.71 Completed 2018-11-30 gement and coordination ion al 5 0 5 5 9 5 3 1 7 6 0 6 8 1 des comptes du Projet 2018- 2019-2020 MG-MRHP-119249-CS-QCBS Component 3. Strengthenin / Etude technique et étude d g capacities for engaging in Quality And Cost- 2019-08-0 2019-10-3 2019-12-1 2020-01-1 2020-03-2 2020-06-1 2021-06-1 IDA / 59870 Post Open - National 20,000.00 0.00 Canceled 2019-07-03 'Impact Environnemental Ré alternative fishing practices Based Selection 2 1 5 4 9 2 2 habilitation du CFPT and livelihoods activities MG-MRHP-28674-CS-QCBS// MG-PM-125 / Développemen Component 2. Strengthenin Quality And Cost- 2019-08-2 2019-11-1 2019-12-1 2020-01-1 2020-03-1 2020-05-1 2021-05-1 t de la base de données pou IDA / 59870 g capacities for priority fish Post Open - National 46,000.00 0.00 Canceled 2019-07-30 Based Selection 9 2 2 1 1 0 0 r la pêche traditionnelle MA eries management RITIME et CONTINENTALE (c onsultant) Page 6 MG-MRHP-28755-CS-QCBS// MG-PM-177 / Élaboration de Component 3. Strengthenin s Plans d'Action aux restricti g capacities for engaging in Quality And Cost- Open - Internation 2019-08-2 2019-09-0 2019-08-3 2019-11-0 2020-01-2 2019-12-0 2020-02-2 2019-12-3 2020-04-0 2020-02-0 2020-04-1 2020-03-1 2021-02-0 2021-03-1 IDA / 59870 Post 270,000.00 408,313.76 Signed 2019-08-15 ons de Ressources (PARAR)/ alternative fishing practices Based Selection al 2 5 0 3 9 1 8 1 7 4 3 0 6 0 Diagnostic des besoins en a and livelihoods activities ctivités alternatives adaptée s à chaque région ultra prior itaire (AGR) MG-MRHP-105669-CS-QCBS Component 3. Strengthenin / Recrutement d'agence de g capacities for engaging in Quality And Cost- 2019-02-0 2019-09-2 2019-11-0 2019-05-0 2019-12-0 2019-06-1 2020-01-0 2019-06-1 2020-02-0 2019-06-2 2020-03-1 2019-07-1 2021-03-1 2019-09-1 communication pour la conc IDA / 59870 Post Open - National 33,750.00 21,553.74 Completed 2019-09-02 alternative fishing practices Based Selection 7 3 6 2 4 2 3 2 7 1 3 6 3 7 eption et production des sup and livelihoods activities ports de communications rel atifs au MDGP MG-MRHP-28174-CS-QCBS / Etude sur le circuit de comm Component 3. Strengthenin ercialisation des produits de g capacities for engaging in Quality And Cost- Open - Internation 2019-06-1 2019-09-2 2019-11-0 2019-10-0 2019-12-0 2019-11-1 2020-01-0 2020-01-1 2020-02-0 2020-02-0 2020-03-1 2020-06-0 2021-03-1 2021-05-1 IDA / 59870 Post 130,000.00 100,145.61 Completed 2019-09-02 s pêches frais et identificatio alternative fishing practices Based Selection al 8 3 6 9 4 1 3 3 7 3 3 6 3 3 n des techniques de transfor and livelihoods activities mation adaptées pour chaqu e ZUP MG-MRHP-19124-CS-QCBS PA48 / Etablissement de la S Component 4. Project mana Quality And Cost- Open - Internation 2017-08-0 2017-07-1 2017-09-0 2017-08-3 2017-09-2 2017-10-2 2017-12-0 2018-01-0 2019-01-0 ituation de référence du Cad IDA / Q9790 Post 75,000.00 0.00 Canceled 2017-06-27 gement and coordination Based Selection al 1 8 6 1 8 8 2 6 6 re de résultats et développe ment d'un système de gesti on de projet MG-MRHP-28701-CS-QCBS// Component 2. Strengthenin MG-PM-144 / Étude pour la d Quality And Cost- 2018-05-0 2018-07-0 2018-08-0 2018-09-1 2018-10-2 2018-11-2 2019-11-2 IDA / 59870 g capacities for priority fish Post Open - National 10,000.00 0.00 Canceled 2018-04-16 éfinition des termes de référ Based Selection 7 5 2 6 1 5 5 eries management ences du Service de Gestion de la Pêche Thonière MG-MRHP-28759-CS-QCBS// Component 3. Strengthenin MG-PM-182 / Préparation du g capacities for engaging in Quality And Cost- Open - Internation 2018-04-2 2018-06-1 2018-07-1 2018-08-3 2018-10-0 2018-11-0 2019-11-0 IDA / V0500 Post 251,100.00 0.00 Canceled 2018-03-30 plan local d'électrification co alternative fishing practices Based Selection al 0 8 6 0 4 8 8 mmunautaire : prestations i and livelihoods activities nternationales MG-MRHP-28753-CS-QCBS// Component 3. Strengthenin MG-PM-176 / Évaluation des g capacities for engaging in Quality And Cost- Open - Internation 2018-10-0 2018-12-0 2018-12-3 2019-01-3 2019-03-0 2019-04-1 2020-04-0 IDA / 59870 Post 90,000.00 0.00 Canceled 2018-09-14 impacts socio-économiques alternative fishing practices Based Selection al 5 3 1 0 6 0 9 de la mise pratique des acti and livelihoods activities vités alternatives MG-MRHP-28741-CS-QCBS// Component 3. Strengthenin MG-PM-168 / Étude sur l'ide g capacities for engaging in Quality And Cost- Open - Internation 2019-11-1 2020-01-2 2021-04-2 2021-06-1 2021-08-1 2021-09-2 2022-09-2 ntification de techniques mo IDA / 59870 Post 100,000.00 0.00 Canceled 2019-09-30 alternative fishing practices Based Selection al 4 8 8 2 1 2 2 dernes de pêche et de fabric and livelihoods activities ation d'engins de pêche ada ptés pour chaque ZUP MG-MRHP-14947-CS-QCBS// PA63 / PA 63: Elaboration de Component 2. Strengthenin Quality And Cost- Open - Internation 2017-05-3 2017-07-2 2017-08-0 2017-08-1 2017-09-0 2017-09-3 2018-09-3 s plans d'action nationaux s IDA / Q9790 g capacities for priority fish Prior 60,000.00 0.00 Canceled 2017-05-17 Based Selection al 1 9 5 2 2 0 0 ur les requins, les oiseaux d eries management e mer et les tortues marines (résolutions CTOI) MG-MRHP-28746-CS-QCBS// MG-PM-171 / Identification d e matériels de sécurité adap Component 3. Strengthenin tés aux différentes catégorie g capacities for engaging in Quality And Cost- Open - Internation 2018-04-2 2018-06-2 2018-07-2 2018-09-0 2018-10-1 2018-11-2 2019-11-2 IDA / 59870 Post 180,000.00 0.00 Canceled 2018-03-30 s d'embarcation et de navig alternative fishing practices Based Selection al 0 5 3 6 8 9 9 ation, stratégie de mis à dis and livelihoods activities position des équipements, d' organisation de secours et l a diffusion des informations météorologiques MG-MRHP-28761-CS-QCBS// Component 3. Strengthenin MG-PM-183 / Préparation du g capacities for engaging in Quality And Cost- Open - Internation 2018-04-0 2018-06-0 2018-07-0 2018-08-1 2018-09-1 2018-10-2 2019-10-2 IDA / V0500 Post 33,800.00 0.00 Canceled 2018-03-15 plan local d'électrification co alternative fishing practices Based Selection al 5 3 1 5 9 4 4 mmunautaire : prestations n and livelihoods activities ationales MG-MRHP-127605-CS-CQS / Component 2. Strengthenin Consultant Qualif Open - Internation 2019-10-0 2019-12-0 2020-01-0 2020-02-2 2020-08-2 Etude sur les accidents en IDA / 59870 g capacities for priority fish Post 90,000.00 0.00 Canceled 2019-09-06 ication Selection al 6 5 4 4 2 mer de la pêche à petite éch eries management elle MG-MRHP-28697-CS-CQS// MG-PM-140 / Étude sur l'ada Component 2. Strengthenin Consultant Qualif Open - Internation 2018-05-2 2018-07-0 2018-08-0 2018-09-0 2019-03-0 ptation des missions et attri IDA / 59870 g capacities for priority fish Post 10,000.00 0.00 Canceled 2018-04-30 ication Selection al 1 4 3 7 6 butions du MRHP par rappor eries management t au défi du développement rural MG-MRHP-23763-CS-QCBS// MG-PM-117 / Recrutement d' Component 3. Strengthenin un Cabinet d'étude ou d'une g capacities for engaging in Quality And Cost- 2017-10-3 2017-10-0 2017-12-0 2017-12-1 2018-09-1 2018-01-0 2019-02-0 2018-02-0 2018-03-2 2018-05-0 2020-04-3 ONG pour assurer les missio IDA / Q9790 Prior Open - National 600,000.00 0.00 Canceled 2017-09-14 alternative fishing practices Based Selection 0 5 1 0 8 7 7 6 0 1 0 ns de l'AGEX pour l'appui à l and livelihoods activities a mise en œuvre du Plan d'A ménagement Concerté des Pêcheries de la Région Mela ky MG-MRHP-23508-CS-QCBS// MG-MP-117 / Recrutement d e Cabinet d'étude ou d'une Component 3. Strengthenin ONG pour assurer les missio g capacities for engaging in Quality And Cost- 2017-10-3 2017-10-0 2018-08-2 2017-12-1 2018-09-1 2018-01-0 2019-02-0 2018-02-0 2019-09-0 2018-03-2 2018-05-0 2020-04-3 ns de l'AGEX pour l'appui à l IDA / Q9790 Prior Open - National 600,000.00 0.00 Canceled 2017-09-14 alternative fishing practices Based Selection 0 5 9 0 8 7 7 6 5 0 1 0 a mise en œuvre du Plan d'A and livelihoods activities ménagement des Pêcheries des Baies d'Ampasindava, d e Tsimipaika, d'Ambaro, et l' archipel de Nosy Be (BATAN ) MG-MRHP-23508-CS-BQS / Recrutement d'une agence Component 3. Strengthenin d'exécution pour l'appui à la g capacities for engaging in Quality Based Sel 2020-01-0 2017-10-0 2020-01-0 2017-11-1 2020-01-2 2017-12-1 2019-02-0 2018-01-1 2020-02-1 2018-02-1 2020-04-1 2018-03-2 2020-05-0 2019-03-2 mise en œuvre du Plan d'Am IDA / Q9790 Prior Open - National 1,600,000.00 1,517,925.94 Signed 2017-09-14 alternative fishing practices ection 7 5 9 8 3 6 7 5 1 4 4 1 9 1 énagement des Pêcheries d and livelihoods activities es Baies d'Ampasindava, de Tsimipaika, d'Ambaro, et l « archipel de Nosy Be (BATAN ) MG-MRHP-23763-CS-BQS / Component 3. Strengthenin Recrutement d'une agence g capacities for engaging in Quality Based Sel 2019-12-1 2017-10-0 2020-01-0 2017-11-1 2020-01-2 2017-12-1 2019-02-0 2018-01-1 2020-02-1 2018-02-1 2020-05-2 2018-03-2 2020-06-1 2021-03-2 d'exécution pour l'appui à la IDA / Q9790 Prior Open - National 900,000.00 647,158.90 Signed 2017-09-14 alternative fishing practices ection 8 5 9 8 3 6 7 5 1 4 0 1 6 0 mise en œuvre du Plan d'Am and livelihoods activities énagement Concerté des Pê cheries de la Région Melaky MG-MRHP-150365-CS-CQS / RECRUTEMENT D'UN CONSU LTANT NATIONAL POUR LE R ENFORCEMENT DE CAPACIT Component 2. Strengthenin Consultant Qualif Under Implemen 2020-03-1 2019-12-3 2020-09-1 2020-01-2 2020-03-0 2020-03-2 2020-05-2 E DU PERSONNEL DE L’AUT IDA / 59870 g capacities for priority fish Post Open - National 15,140.00 0.00 2019-12-24 ication Selection tation 1 1 4 8 8 2 1 ORITE SANITAIRE HALIEUTIQ eries management UE PAR UNE FORMATION EN LINGUISTIQUE (ANGLAIS / CHINOIS) AU NIV EAU NATIONAL (2.1.7.2.04) MG-MRHP-28740BIS-CS-QC BS // MG-PM-167 / Etude sur Component 3. Strengthenin l'amélioration des embarcati g capacities for engaging in Quality And Cost- Under Implemen 2020-02-2 2020-03-0 2020-03-1 2020-04-1 2020-05-1 2020-06-0 2020-07-0 2020-07-1 2021-03-2 IDA / 59870 Post Open - National 90,000.00 0.00 2020-02-25 ons existantes à partir des alternative fishing practices Based Selection tation 7 3 8 6 6 6 4 8 5 matériaux locaux bon march and livelihoods activities é et existants pour chaque Z UP (3.2.1.1.12) MG-MRHP-28740-CS-QCBS// Component 3. Strengthenin MG-PM-167 / Étude sur l'am g capacities for engaging in Quality And Cost- Open - Internation 2019-08-1 2018-05-2 2019-08-1 2018-07-2 2018-08-2 2018-10-0 2018-11-1 2018-12-3 2019-12-3 élioration des embarcations IDA / 59870 Post 60,000.00 0.00 Canceled 2018-04-30 alternative fishing practices Based Selection al 1 1 9 6 3 7 8 0 0 existantes à partir des maté and livelihoods activities riaux locaux bon marché et existants MG-MRHP-86203BIS-CS-QC BS / Recrutement d'une Fir me pour Appui à la Mise à jo ur de la Stratégie Nationale Component 2. Strengthenin Quality And Cost- Under Implemen 2020-02-2 2020-03-0 2020-03-0 2020-04-1 2020-05-1 2020-06-0 2020-07-1 2020-07-2 2020-12-1 pour le Développement de l’ IDA / 59870 g capacities for priority fish Post Open - National 50,000.00 0.00 2020-02-28 Based Selection tation 5 6 7 9 9 9 4 8 5 Aquaculture à Madagascar ( eries management SNDAM) et Elaboration des P lans de Développement des trois (3) filières « d’algocultu re, d’holothuriculture et de c rabicultu MG-MRHP-119284-CS-QCBS / Recrutement d'un BE pour Etudes techniques, étude d’i Component 3. Strengthenin mpact environnemental et s g capacities for engaging in Quality And Cost- Open - Internation 2020-03-1 2020-03-2 2020-03-1 2020-05-1 2020-06-1 2020-06-0 2020-07-1 2020-06-3 2020-08-1 2020-08-0 2020-11-0 2020-08-2 2021-03-1 2022-03-2 ocial et contrôle et surveilla TF / A4588 Post 44,000.00 56,927.90 Signed 2020-03-06 alternative fishing practices Based Selection al 0 7 8 0 6 9 6 0 3 4 5 5 8 8 nce des travaux pour la con and livelihoods activities struction des bâtiments du k iosque de pré-électrification et du « Complexe-pêche » d ans 2 villages à Mananara N ord MG-MRHP-86203-CS-QCBS// PA13 / Mise à jour de la Stra Component 2. Strengthenin Quality And Cost- Open - Internation 2020-02-0 2019-08-3 2019-11-1 2019-12-2 2020-02-1 2020-04-1 2020-06-1 2021-06-1 tégie Nationale de l’Aquacul IDA / 59870 g capacities for priority fish Post 30,000.00 0.00 Canceled 2019-07-31 Based Selection al 4 0 3 8 1 1 0 0 ture (Consultant national + eries management Réunions (1 consultation, 1 validation) MG-MRHP-14952-CS-LCS//P A66 / PA 66: Etudes d'Impac t environnemental et Socail : - Clôture de l'enceinte DRRH Component 2. Strengthenin Consultant Qualif Open - Internation 2017-07-1 2017-08-3 2017-09-3 2017-11-0 2018-05-0 P Fénérive IDA / Q9790 g capacities for priority fish Post 35,000.00 0.00 Canceled 2017-06-27 ication Selection al 8 1 0 4 3 - Construction des Bureaux eries management de 06 DRRHP - Extension de l'ASH à Antsir anana et Morondava - Construction local pour bur eau UGP MG-MRHP-168222-CS-QCBS / Recrutement d'un BE pour la réalisation des études tec Component 2. Strengthenin Quality And Cost- Under Implemen 2020-04-1 2020-05-0 2020-04-2 2020-06-2 2020-07-1 2020-08-1 2020-09-2 2020-10-2 2021-05-3 hniques- du PGES et du cont IDA / 59870 g capacities for priority fish Post Open - National 20,000.00 0.00 2020-04-17 Based Selection tation 5 8 7 1 9 8 2 7 0 rôle et surveillance des cons eries management tructions des bureaux admin istratifs de l'ASH à Manakara et Mananjary MG-MRHP-168223-CS-QCBS / Recrutement d'un BE pour la réalisation des études tec Component 2. Strengthenin Quality And Cost- Under Implemen 2020-04-1 2020-05-0 2020-04-2 2020-06-2 2020-08-1 2020-07-1 2020-09-1 2020-08-1 2020-12-1 2020-09-2 2021-10-2 2020-10-2 2021-05-3 hniques- du PGES et du cont IDA / 59870 g capacities for priority fish Post Open - National 20,000.00 0.00 2020-04-17 Based Selection tation 5 8 7 1 7 9 7 8 6 2 5 7 0 rôle et surveillance des cons eries management tructions des bureaux admin istratifs de l'ASH-OEPA à An tananarivo MG-MRHP-168224-CS-QCBS / Recrutement d'un BE pour la réalisation des études tec Component 2. Strengthenin Quality And Cost- Under Implemen 2020-04-1 2020-05-0 2020-04-2 2020-06-2 2020-07-1 2020-08-1 2020-09-2 2020-10-2 2021-05-3 hniques- du PGES et du cont IDA / 59870 g capacities for priority fish Post Open - National 20,000.00 0.00 2020-04-17 Based Selection tation 5 8 7 1 9 8 2 7 0 rôle et surveillance des cons eries management tructions des bureaux admin istratifs de l'ASH-USTA-SRPA à Majunga MG-MRHP-168226-CS-QCBS / Recrutement d'un BE pour Component 2. Strengthenin la réalisation des études tec Quality And Cost- 2020-04-1 2020-05-0 2020-04-2 2020-06-2 2020-08-2 2020-07-1 2020-09-2 2020-08-1 2020-12-1 2020-09-2 2021-02-0 2020-10-2 2021-03-1 2021-05-3 IDA / 59870 g capacities for priority fish Post Open - National 10,000.00 15,378.80 Signed 2020-04-17 hniques- du PGES et du cont Based Selection 5 8 7 1 0 9 8 8 8 2 1 7 8 0 eries management rôle et surveillance des cons tructions des bureaux admin istratifs de l'ASH à Toliara MG-MRHP-168227-CS-QCBS / Recrutement d'un BE pour Component 2. Strengthenin la réalisation des études tec Quality And Cost- 2020-04-1 2020-05-0 2020-04-2 2020-06-2 2020-08-1 2020-07-1 2020-09-1 2020-08-1 2021-02-1 2020-09-2 2021-06-2 2020-10-2 2021-09-3 2021-05-3 IDA / 59870 g capacities for priority fish Post Open - National 10,000.00 25,713.74 Signed 2020-04-17 hniques- du PGES et du cont Based Selection 5 8 7 1 4 9 4 8 6 2 3 7 0 0 eries management rôle et surveillance des cons tructions des bureaux admin istratifs de l'ASH à Fort-Dau phin Page 7 MG-MRHP-168225-CS-QCBS / Recrutement d'un BE pour la réalisation des études tec Component 2. Strengthenin Quality And Cost- Under Implemen 2020-04-1 2020-05-0 2020-04-2 2020-06-2 2020-07-1 2020-08-1 2020-09-2 2020-10-2 2021-05-3 hniques- du PGES et du cont IDA / 59870 g capacities for priority fish Post Open - National 30,000.00 0.00 2020-04-17 Based Selection tation 5 8 7 1 9 8 2 7 0 rôle et surveillance des cons eries management tructions des bureaux admin istratifs de l'ASH-SRPA-OEPA à Diégo Suarez MG-MRHP-169196-CS-QCBS / RECRUTEMENT D’UNE FIRM E EN CHARGE DE L’ELABOR Component 3. Strengthenin ATION DES PCD ET PDF DE g capacities for engaging in Quality And Cost- 2020-05-0 2020-05-2 2020-05-1 2020-07-0 2020-10-2 2020-08-0 2020-12-0 2020-08-3 2021-04-2 2020-10-0 2021-06-0 2020-11-0 2021-09-0 2021-09-0 S COMMUNES POUR LES 3 Z IDA / 59870 Post Open - National 300,000.00 157,999.04 Signed 2020-04-30 alternative fishing practices Based Selection 4 1 6 4 0 1 2 1 6 5 2 9 9 5 UPs ET REPARTIE EN TROIS and livelihoods activities LOTS: Lot 1: ZUP BA, Lot 2: ZUP BATAN Lot 3: ZUP MELAKY MG-MRHP-170094-CS-CQS / Recrutement d’un consultan Component 2. Strengthenin Consultant Qualif 2020-05-1 2020-05-2 2020-05-1 2020-06-2 2021-05-1 2020-07-2 2021-12-1 2020-08-2 2022-02-0 2021-02-2 t chargé de la traduction et IDA / 59870 g capacities for priority fish Post Open - National 20,000.00 74,211.00 Signed 2020-04-30 ication Selection 4 1 6 5 9 5 6 9 5 5 de la synthèse des documen eries management ts du français et anglais au malagasy officiel MG-MRHP-170870-CS-QCBS / Recrutement d'une firme p Component 2. Strengthenin Quality And Cost- Under Implemen 2020-05-0 2020-05-2 2020-05-1 2020-07-0 2020-08-0 2020-09-0 2020-10-0 2020-11-1 2022-02-1 our l’élaboration du Plan d’A IDA / 59870 g capacities for priority fish Post Open - National 75,000.00 0.00 2020-05-04 Based Selection tation 4 5 6 8 5 4 9 3 1 ménagement des Pêcheries eries management de la Région ATSIMO ATSINA NANA MG-MRHP-174365-CS-QCBS / Recrutement d'un Institut de Recherche ou d'une Firm Component 2. Strengthenin Quality And Cost- 2020-05-2 2020-06-1 2020-06-0 2020-07-3 2020-10-2 2020-08-2 2020-12-0 2020-09-2 2021-01-2 2020-10-3 2021-03-0 2020-12-0 2021-04-1 2022-02-2 e pour appuyer le Centre d’ IDA / 59870 g capacities for priority fish Post Open - National 75,000.00 338,974.11 Signed 2020-05-26 Based Selection 0 6 6 0 0 7 2 6 9 1 4 5 5 8 Etude et de Développement eries management des Pêches (CEDP) dans l’ét ude des stocks Halieutiques (Cinq filières Prioritaires) MG-MRHP-181840-CS-QCBS Component 3. Strengthenin / RECRUTEMENT D’UNE FIRM g capacities for engaging in Quality And Cost- Under Implemen 2020-06-3 2020-07-1 2020-07-1 2020-08-1 2020-09-1 2020-10-0 2020-11-1 2020-12-1 2021-12-1 E POUR LA FORMATION DES IDA / 59870 Post Open - National 50,000.00 0.00 2020-07-02 alternative fishing practices Based Selection tation 0 2 6 6 5 6 0 5 5 GROUPEMENTS DE PÊCHEU and livelihoods activities RS SUR LES TECHNIQUES C OMMERCIALES MG-MRHP-182950-CS-CQS / Recrutement d'agence de co Component 3. Strengthenin mmunication pour la concep g capacities for engaging in Consultant Qualif 2020-08-1 2020-08-0 2020-08-2 2020-09-1 2021-10-0 2020-10-1 2022-03-3 2020-11-2 2022-04-1 2021-05-2 tion et production des suppo IDA / 59870 Post Open - National 25,000.00 61,842.50 Signed 2020-07-14 alternative fishing practices ication Selection 3 4 6 7 5 7 0 1 4 0 rts de communications relati and livelihoods activities fs au MDGP 2020 et pour la mise en oeuvre du plan de c ommunication du projet SWI Ofish2 MG-MRHP-181871-CS-QCBS / Recrutement d’ONG pour l a conservation et la restaura Component 3. Strengthenin tion des forêts de mangrove g capacities for engaging in Quality And Cost- 2020-10-0 2020-07-3 2020-10-2 2020-09-1 2021-05-2 2020-10-1 2022-01-1 2020-11-0 2022-04-0 2020-12-0 2022-10-1 2020-12-2 2021-12-2 IDA / 59870 Prior Open - National 3,000,000.00 0.00 Signed 2020-07-21 , et la protection de récifs co alternative fishing practices Based Selection 7 1 1 3 5 3 3 3 7 8 3 9 9 ralliens et d’herbiers marins and livelihoods activities dans des zones riches en ha bitats naturels côtiers et ma rins de Madagascar, répartis en 6 Lots MG-MRHP-183755-CS-QCBS / Recrutement d'une firme p our la réalisation d’une enqu Component 4. Project mana Quality And Cost- 2020-07-2 2020-08-0 2020-08-0 2020-09-1 2020-10-1 2020-10-1 2020-11-1 2020-11-0 2020-12-0 2020-12-0 2021-02-1 2020-12-2 2021-03-3 2021-03-1 IDA / 59870 Post Open - National 75,000.00 79,586.86 Signed 2020-07-17 ête de satisfaction des béné gement and coordination Based Selection 2 7 7 1 3 1 3 1 3 6 5 0 1 0 ficiaires du projet et les me mbres de la communauté de s pêcheurs MG-MRHP-28698-CS-CQS// Component 2. Strengthenin Consultant Qualif 2020-07-2 2020-09-0 2020-10-0 2020-11-0 2021-05-0 MG-PM-141 / Assistant techn IDA / 59870 g capacities for priority fish Post Open - National 24,000.00 0.00 Canceled 2020-06-30 ication Selection 1 3 3 7 6 ique pour UGP eries management MG-MRHP-183758-CS-QCBS Component 2. Strengthenin / Recrutement d'une firme p Quality And Cost- 2020-09-0 2020-09-1 2020-09-1 2020-10-2 2020-11-2 2020-11-2 2021-01-1 2020-12-1 2021-02-0 2021-01-1 2021-03-0 2021-02-2 2021-04-3 2021-10-1 IDA / 59870 g capacities for priority fish Post Open - National 75,000.00 86,424.70 Signed 2020-08-27 our étudier la mise en place Based Selection 1 7 0 2 7 1 1 2 2 6 9 0 0 8 eries management des ZEA pêche et aquacultu re MG-MRHP-28689-CS-CQS// MG-PM-133 / Appui du centr Component 2. Strengthenin Consultant Qualif Open - Internation 2020-08-3 2020-11-1 2020-12-2 2021-03-1 2021-09-0 e de recherche par deux (02 IDA / 59870 g capacities for priority fish Post 150,000.00 0.00 Canceled 2020-07-31 ication Selection al 0 3 8 3 9 ) experts internationaux pou eries management r les évaluations de stocks d e 5 filières prioritaires MG-MRHP-190077-CS-CQS / Recrutement d'un cabinet d' Component 2. Strengthenin Consultant Qualif 2020-09-1 2020-09-2 2020-09-2 2020-11-0 2021-03-1 2020-12-0 2021-05-1 2021-01-0 2022-05-1 2021-03-0 étude pour effectuer une ét IDA / 59870 g capacities for priority fish Post Open - National 20,000.00 50,426.00 Signed 2020-08-31 ication Selection 1 1 3 4 1 4 4 8 1 9 ude de faisabilité de l'éclose eries management rie en holothuries à Ambanj a MG-MRHP-28671-CS-QCBS// MG-PM-123 / Amélioration d e la base de données pour l Component 2. Strengthenin Quality And Cost- 2018-01-2 2018-03-3 2018-04-2 2018-05-2 2018-07-0 2018-08-1 2019-08-1 a déclaration des produits d IDA / D1720 g capacities for priority fish Post Open - National 20,000.00 0.00 Canceled 2018-01-02 Based Selection 3 0 7 7 8 9 9 e la pêche régionale (Base d eries management e données-Tableau de bord- Système d'Information Pêch e :basé sur le Web, consulta nt) MG-MRHP-198557-CS-QCBS / Recrutement des BE pour Component 3. Strengthenin réaliser les études techniqu g capacities for engaging in Quality And Cost- 2020-10-1 2020-11-0 2020-12-2 2021-04-0 2021-01-1 2021-11-0 2021-02-1 2021-05-1 2021-03-2 2021-07-1 2021-04-2 2021-11-0 2021-11-2 es et EIES de la construction TF / A4588 Post Open - National 130,000.00 108,278.08 Signed 2020-10-16 alternative fishing practices Based Selection 9 6 0 1 9 3 8 4 5 6 9 5 5 des bâtiments de pré-électri and livelihoods activities fication hors grille et comple xe pêche au niveau BATAN et Aniribe (BA) répartis en 4 Lots MG-MRHP-199272-CS-CQS / Recrutement d'un BE études Component 2. Strengthenin Consultant Qualif Under Implemen 2020-10-1 2020-11-0 2020-12-1 2021-03-1 2021-01-1 2021-02-1 2021-09-0 techniques- EIES et contrôle IDA / 59870 g capacities for priority fish Post Open - National 20,000.00 0.00 2020-10-19 ication Selection tation 9 9 3 1 2 6 4 et surveillance des travaux eries management à la mise en place d'écloseri e_Ambanja MG-MRHP-203599-CS-CQS / Recrutement d’une firme po ur la conception et le dévelo ppement de site web pour l’ Component 2. Strengthenin Consultant Qualif 2020-11-2 2020-12-1 2020-11-2 2021-01-1 2021-03-2 2021-02-1 2021-06-0 2021-03-2 2021-09-2 2021-05-1 Observatoire Economique d IDA / Q9790 g capacities for priority fish Post Open - National 45,000.00 76,667.73 Signed 2020-11-20 ication Selection 1 1 6 5 3 4 8 1 5 0 e la Pêche et de l’Aquacultur eries management e (OEPA), pour le Centre d’E tudes et de Développement des Pêches (CEDP) et pour l’ Unité Statistique Thonière d’ Antsiran MG-MRHP-208296-CS-CQS / Recrutement d'un BE études techniques, EIES et C&S des Component 3. Strengthenin travaux pour la construction g capacities for engaging in Consultant Qualif 2021-01-1 2021-01-1 2021-01-1 2021-02-1 2021-03-2 2021-03-1 2021-06-1 2021-04-2 2021-09-1 2021-11-1 TF / A4588 Post Open - National 20,000.00 36,890.00 Signed 2020-12-21 des bâtiments du kiosque d alternative fishing practices ication Selection 2 1 9 4 6 6 0 0 4 6 e pré-électrification et du « and livelihoods activities Complexe-pêche » dans les villages d’Ambalahonko et A mpasimandroro district de M aintirano MG-MRHP-208303-CS-QCBS / Recrutement des BE pour r Component 3. Strengthenin éaliser les études technique g capacities for engaging in Quality And Cost- 2021-01-1 2021-01-1 2021-01-1 2021-02-2 2021-03-3 2021-03-2 2021-04-3 2021-04-2 2021-05-2 2021-05-3 2021-07-1 2021-07-0 2022-09-2 2022-01-3 IDA / 59870 Post Open - National 180,000.00 146,654.22 Signed 2020-12-21 s, PGES et et contrôle et sur alternative fishing practices Based Selection 2 1 9 4 1 6 0 5 5 0 9 4 2 0 veillance des travaux de con and livelihoods activities struction des petites infrast ructures de pêches répartis en 6 lots MG-MRHP-208305-CS-CQS / Component 2. Strengthenin Recrutement d'un BE pour l Consultant Qualif 2021-01-1 2021-01-1 2021-01-1 2021-02-2 2021-03-2 2021-03-2 2021-06-1 2021-04-3 2021-09-2 2021-09-2 IDA / 59870 g capacities for priority fish Post Open - National 20,000.00 25,708.56 Signed 2020-12-21 e contrôle et surveillance de ication Selection 2 1 9 4 3 6 0 0 8 7 eries management s travaux des DRAEP à Andr oy, Anosy MG-MRHP-208306-CS-CQS / Component 2. Strengthenin Recrutement d'un BE pour l Consultant Qualif 2021-01-1 2021-01-1 2021-01-1 2021-02-2 2021-03-2 2021-03-2 2021-10-0 2021-04-3 2021-10-2 2021-09-2 IDA / 59870 g capacities for priority fish Post Open - National 8,000.00 15,062.89 Signed 2020-12-21 e contrôle et la surveillance ication Selection 2 1 9 4 3 6 4 0 1 7 eries management des travaux du DRAEP à Mai ntirano MG-MRHP-214299-CS-QCBS / Recrutement d’une firme p Component 2. Strengthenin Quality And Cost- 2021-01-2 2021-02-1 2021-02-0 2021-03-0 2021-03-3 2021-03-3 2021-04-3 2021-04-2 2021-05-1 2021-05-2 2021-06-0 2021-06-3 2021-09-1 2022-09-2 our l’élaboration du Plan d’A IDA / 59870 g capacities for priority fish Post Open - National 100,000.00 137,749.52 Signed 2021-01-29 Based Selection 8 3 4 1 0 1 0 1 4 6 7 0 4 3 ménagement des Pêcheries eries management (PAP) de la Région ANDROY MG-MRHP-216848-CS-CQS / Recrutement d'un BE pour ET, élaboration du PGES et C Component 3. Strengthenin &S relative à la construction g capacities for engaging in Consultant Qualif Under Implemen 2021-02-2 2021-03-1 2021-03-0 2021-04-1 2021-05-1 2021-06-1 2022-02-0 IDA / 59870 Post Open - National 33,000.00 0.00 2021-02-17 du bureau de la Circonscripti alternative fishing practices ication Selection tation 4 0 9 3 3 7 2 on en charge de la pêche et and livelihoods activities de l’Aquaculture et l’l’anten ne du Centre de Surveillanc e des Pêches (CSP) à Maintir ano MG-MRHP-218699-CS-CQS / Component 2. Strengthenin Recrutement d’une firme po Consultant Qualif Under Implemen 2021-02-2 2021-03-0 2021-03-0 2021-04-2 2021-05-2 2021-06-2 2021-10-2 IDA / 59870 g capacities for priority fish Post Open - National 30,000.00 0.00 2021-02-15 ur Etude des impacts du CO ication Selection tation 3 8 2 1 1 5 3 eries management VID19 sur la pêche à Madag ascar MG-MRHP-222309-CS-CQS / Recrutement d'une firme po Component 2. Strengthenin Consultant Qualif 2021-03-1 2021-03-3 2021-03-2 2021-05-1 2021-04-2 2021-06-1 2021-05-2 2021-07-1 2021-09-1 2021-09-0 ur réaliser un diagnostic inst IDA / 59870 g capacities for priority fish Post Open - National 20,000.00 13,920.80 Signed 2021-03-17 ication Selection 4 1 6 4 1 3 8 8 4 1 itutionnel et organisationnel eries management de la mise en oeuvre du proj et SWIOFish2 MG-MRHP-222313-CS-QCBS / Recrutement d’une firme e n charge de l’identification d Component 3. Strengthenin es plans de pérennisation in g capacities for engaging in Quality And Cost- Under Implemen 2022-01-1 2021-04-0 2022-01-1 2021-05-2 2022-03-1 2021-06-2 2022-05-0 2021-07-2 2022-05-2 2021-08-2 2022-06-0 2021-09-2 2022-01-2 IDA / 59870 Post Open - National 90,000.00 0.00 2021-03-24 cluant un plan de gestion et alternative fishing practices Based Selection tation 2 7 7 1 7 0 3 0 4 4 3 8 6 un plan d’affaire des petites and livelihoods activities infrastructures de pêche et complexes pêches dans les zones ultra prioritaires BATA N, BA et MELAKY MG-MRHP-224627-CS-CQS / Component 2. Strengthenin Recrutement firme pour pro Consultant Qualif Under Implemen 2021-03-3 2021-04-2 2021-04-1 2021-06-0 2021-07-0 2021-08-0 2022-02-0 IDA / 59870 g capacities for priority fish Post Open - National 115,000.00 0.00 2021-03-30 spection nouvelles zones de ication Selection tation 0 0 5 3 3 7 3 eries management pêche langoustes MG-MRHP-223841-CS-CQS / Cabinet pour le recrutement Component 2. Strengthenin Consultant Qualif 2021-05-0 2021-04-2 2021-06-0 2021-09-2 2021-07-0 2021-12-2 2021-08-0 2022-03-2 2021-10-0 de 75 enquêteurs pour le dé IDA / Q9790 g capacities for priority fish Post Open - National 40,000.00 23,150.53 Signed 2021-03-31 ication Selection 1 1 4 9 4 3 8 2 7 ploiement d'OPENARTFISH d eries management ans 5 régions côtières MG-MRHP-222316-CS-QCBS Component 2. Strengthenin / Recrutement d'une firme p Quality And Cost- Under Implemen 2021-04-2 2021-06-0 2021-07-0 2021-08-0 2021-09-0 2021-10-1 2022-04-1 IDA / 59870 g capacities for priority fish Prior Open - National 1,250,000.00 0.00 2021-03-31 our l'Appui au développeme Based Selection tation 1 4 4 3 7 2 0 eries management nt de l’économie bleue à Ma dagascar MG-MRHP-227234-CS-CQS / Recrutement d'une firme po Component 2. Strengthenin Consultant Qualif Under Implemen 2021-04-0 2021-04-2 2021-06-1 2021-07-1 2021-08-1 2022-02-1 ur la mise à jour de la straté IDA / 59870 g capacities for priority fish Post Open - National 30,000.00 0.00 2021-04-07 ication Selection tation 9 8 1 1 5 1 gie Nationale de la Bonne G eries management ouvernance de la Pêche Mar itime MG-MRHP-229422-CS-QCBS Component 2. Strengthenin Quality And Cost- Under Implemen 2021-05-1 2021-05-2 2021-10-1 2021-06-2 2022-03-0 2021-07-2 2022-04-1 2021-08-1 2022-05-3 2021-09-2 2022-07-2 2021-10-2 2023-01-2 / Recrutement des firmes po IDA / 59870 g capacities for priority fish Post Open - National 700,000.00 0.00 2021-05-14 Based Selection tation 8 9 4 8 2 8 1 8 0 2 0 7 0 ur l'élaboration des PAP régi eries management onaux Page 8 MG-MRHP-28730-CS-CQS// Component 2. Strengthenin Consultant Qualif Open - Internation 2021-07-2 2021-09-0 2021-10-0 2021-11-0 2022-05-0 MG-PM-157 / Étude pour l'ex IDA / 59870 g capacities for priority fish Post 50,000.00 0.00 Canceled 2021-07-01 ication Selection al 2 4 4 8 7 tension de l'ERS vers la flott eries management e nationale MG-MRHP-231603-CS-CQS / Recrutement d'une firme po Component 2. Strengthenin Consultant Qualif Under Implemen 2021-06-0 2021-06-0 2021-10-1 2021-07-1 2022-01-0 2021-08-1 2022-05-0 2021-09-2 2021-12-2 ur réaliser une étude diagno IDA / 59870 g capacities for priority fish Post Open - National 20,000.00 0.00 2021-05-14 ication Selection tation 9 4 4 8 7 7 2 1 0 stique des besoins en renfor eries management cement des capacités DGPA et UGP SWIOFish2 MG-MRHP-231604-CS-LCS / Component 4. Project mana Least Cost Select 2021-06-1 2021-07-2 2021-08-2 2021-09-2 2021-10-2 2021-11-2 2022-01-2 Recrutement d'audit pour le IDA / Q9790 Post Open - National 32,500.00 0.00 Canceled 2021-05-20 gement and coordination ion 0 4 1 0 5 9 8 Centre de Surveillance de P êche MG-MRHP-232532-CS-LCS / Recrutement d'un cabinet d' Component 4. Project mana Least Cost Select 2021-07-1 2021-06-1 2021-07-2 2021-09-2 2021-08-2 2021-10-2 2021-09-2 2021-11-1 2021-10-2 2022-01-2 2021-11-2 2022-02-2 2023-09-2 IDA / 59870 Post Open - National 50,000.00 20,442.04 Signed 2021-05-20 audit externe des comptes d gement and coordination ion 5 0 4 3 1 5 0 2 5 6 9 4 9 u Projet 2021-2022 et 2023 MG-MRHP-236858-CS-CQS / Component 2. Strengthenin Recrutement d'un BE pour l Consultant Qualif Under Implemen 2021-08-0 2021-07-1 2021-10-1 2021-08-2 2021-11-2 2021-09-2 2022-05-3 2021-10-3 2022-04-2 TF / A4588 g capacities for priority fish Post Open - National 30,000.00 0.00 2021-06-30 es études technique et contr ication Selection tation 6 4 4 7 6 6 1 1 9 eries management ôle et surveillance du Burea u CSP à Toliara MG-MRHP-239019-CS-CQS / Recrutement d'un BE ET- PG Component 2. Strengthenin ES et C&S relative à la con Consultant Qualif Under Implemen 2021-08-0 2021-07-1 2021-10-1 2021-08-1 2021-09-1 2021-10-2 2022-06-0 IDA / 59870 g capacities for priority fish Post Open - National 37,000.00 0.00 2021-06-30 struction du bureau de la Cir ication Selection tation 6 4 4 7 6 1 8 eries management conscription en charge de la pêche et de l’Aquaculture à Besalampy. MG-MRHP-28755BIS-CS-QC BS // MG-PM-177 / Élaboratio Component 3. Strengthenin n des plans d'action aux rest g capacities for engaging in Quality And Cost- 2019-08-3 2020-01-2 2020-02-2 2020-04-0 2020-04-1 2021-02-0 2021-10-0 rictions de ressources (PARA IDA / 59870 Post Open - National 875,300.00 0.00 Canceled 2019-08-22 alternative fishing practices Based Selection 0 9 8 7 3 9 7 R) / Diagnostic des besoins and livelihoods activities en activités alternatives ada ptées à chaque région ultra prioritaire (AGR) MG-MRHP-150349-CS-CQS / Recrutement de consultant national pour assurer le renf Component 2. Strengthenin orcement de capacité des a Consultant Qualif Pending Implem 2022-01-1 2022-02-0 2022-03-2 2022-04-0 2022-04-2 IDA / 59870 g capacities for priority fish Post Open - National 1,500.00 0.00 2022-01-04 gents de l’administration de ication Selection entation 1 8 0 3 4 eries management s pêches et des responsable s des textes administratifs e n leadership et Gestion axés sur les résultats (2.1.1.1.04) MG-MRHP-14959-CS-CQS / Component 3. Strengthenin Mise en place d’une règleme g capacities for engaging in Consultant Qualif Open - Internation 2021-11-1 2022-01-2 2022-03-1 2022-05-1 2022-11-0 IDA / 59870 Post 60,000.00 0.00 Canceled 2021-09-30 ntation de base concernant l alternative fishing practices ication Selection al 4 8 4 3 9 a sécurité en mer de la petit and livelihoods activities e pêche MG-MRHP-263393-CS-CQS / Recrutement des BE pour ré Component 3. Strengthenin aliser les études techniques, g capacities for engaging in Consultant Qualif 2021-12-1 2021-12-1 2021-12-2 2022-01-2 2022-03-1 2022-02-2 2022-06-0 2022-04-0 2022-07-2 2022-09-2 IDA / 59870 Post Open - National 77,000.00 98,415.82 Signed 2021-11-23 PGES et contrôle et surveilla alternative fishing practices ication Selection 5 4 1 7 7 6 9 2 0 9 nce des travaux de construc and livelihoods activities tion des petites infrastructur es de pêches (relance lot 1 et 5) MG-MRHP-264080-CS-CQS / Recrutement des BE pour é Component 3. Strengthenin tudes techniques, PGES et C g capacities for engaging in Consultant Qualif 2021-12-1 2021-12-2 2021-12-2 2022-01-2 2022-03-1 2022-02-2 2022-06-0 2022-03-3 2022-07-2 2022-10-1 IDA / 59870 Post Open - National 84,000.00 111,436.73 Signed 2021-11-30 ontrôle et surveillance des tr alternative fishing practices ication Selection 5 1 1 4 7 3 9 0 0 6 avaux de construction des b and livelihoods activities âtiments abritant les chamb res froide repartis en 3 lots MG-MRHP-288108-CS-CQS / Component 2. Strengthenin Mise à jour l’enquête cadre Consultant Qualif Under Implemen 2022-04-1 2022-05-0 2022-05-0 2022-06-1 2022-08-0 2022-07-1 2022-11-1 2022-08-1 2023-02-1 IDA / 59870 g capacities for priority fish Post Open - National 100,000.00 0.00 2022-04-11 nationale 2012-2013 sur la ication Selection tation 8 2 3 5 5 5 8 9 5 eries management petite pêche maritime et la pêche continentale MG-MRHP-232529-CS-QCBS Component 2. Strengthenin / Recrutement d'une firme p Quality And Cost- Open - Internation 2022-01-2 2021-06-1 2021-07-2 2021-08-2 2021-09-2 2021-10-2 2021-11-2 2022-11-2 IDA / 59870 g capacities for priority fish Prior 2,000,000.00 0.00 Canceled 2021-05-20 our le développement de la Based Selection al 3 0 4 1 0 5 9 9 eries management planification spatiale mariti me PSM à Madagascar MG-MRHP-232529 BIS-CS-Q CBS / Recrutement d'une fir Component 2. Strengthenin Quality And Cost- Open - Internation Under Implemen 2022-04-2 2022-05-1 2022-04-2 2022-06-2 2022-07-2 2022-08-2 2022-09-2 2022-10-3 2023-10-3 me pour le développement IDA / 59870 g capacities for priority fish Post 600,000.00 0.00 2022-04-20 Based Selection al tation 5 1 8 4 2 1 5 0 0 de la planification spatiale eries management maritime PSM à Madagascar MG-MRHP-239018-CS-CQS / Recrutement d’une firme po Component 2. Strengthenin ur élaborer et mettre à jour l Consultant Qualif 2021-10-1 2021-10-0 2021-12-2 2021-11-1 2021-12-1 2021-12-2 2022-05-0 IDA / 59870 g capacities for priority fish Post Open - National 56,000.00 0.00 Canceled 2021-09-22 es textes d’application de la ication Selection 9 6 1 0 0 4 3 eries management nouvelle loi portant Code de la Pêche et de l'Aquaculture à Madagascar MG-MRHP-28757-CS-QCBS// Component 3. Strengthenin MG-PM-179 / Étude de faisa g capacities for engaging in Quality And Cost- Open - Internation 2021-10-3 2022-01-1 2022-02-2 2022-04-1 2022-06-1 2022-08-1 2023-08-1 bilité technique des constru IDA / 59870 Post 795,000.00 0.00 Canceled 2021-10-01 alternative fishing practices Based Selection al 1 4 8 4 3 2 2 ctions d'infrastructures de p and livelihoods activities êche(APS & APD) (33 débarc adères, 8 marchés couverts) MG-MRHP-252969-CS-CQS / Component 3. Strengthenin Recrutement d'une firme po g capacities for engaging in Consultant Qualif 2021-10-1 2021-11-1 2021-12-1 2022-01-0 2022-12-2 IDA / 59870 Post Open - National 100,000.00 0.00 Canceled 2021-09-30 ur la promotion de transfert alternative fishing practices ication Selection 4 8 8 1 7 financier pour les 03 ZUP. and livelihoods activities MG-MRHP-218708-CS-QCBS Component 3. Strengthenin / Recrutement d’une firme g capacities for engaging in Quality And Cost- Pending Implem 2022-05-1 2022-06-1 2022-07-1 2022-08-0 2022-09-1 2022-10-1 2023-02-1 en charge de l’élaboration d’ IDA / 59870 Post Open - National 100,000.00 0.00 2022-05-10 alternative fishing practices Based Selection entation 5 9 9 9 3 8 5 un plan de formation/renforc and livelihoods activities ement de capacités des élus et des acteurs MG-MRHP-198566-CS-QCBS / Recrutement des BE pour é Component 3. Strengthenin tudes techniques- PGES et c g capacities for engaging in Quality And Cost- 2020-11-1 2020-12-2 2021-01-2 2021-02-2 2021-04-0 2021-05-0 2021-12-0 IDA / 59870 Post Open - National 240,000.00 0.00 Canceled 2020-10-23 ontrôle et surveillance des tr alternative fishing practices Based Selection 3 7 6 5 1 6 2 avaux des petites infrastruct and livelihoods activities ures de pêches pour les 3 Z ups répartis en 8 Lots. MG-MRHP-239018-CS-CQS- 2 / Recrutement d'une firme Component 2. Strengthenin pour élaborer et mettre à jo Consultant Qualif Under Implemen 2022-05-1 2022-05-0 2022-05-1 2022-06-0 2022-07-0 2022-07-2 2022-11-2 IDA / 59870 g capacities for priority fish Post Open - National 56,000.00 0.00 2022-04-18 ur les textes d'application d ication Selection tation 0 2 6 6 6 0 7 eries management e la nouvelle loi portant Cod e de la Pêche et de l'Aquacu lture à Madagascar. MG-MRHP-14951-CS-QCBS / PA 65: Etudes techniques : - Clôture de l'enceinte DRRHP Component 2. Strengthenin Fénérive - Construction des Quality And Cost- 2019-08-1 2019-09-2 2019-10-2 2019-11-2 2019-12-3 2020-02-0 2021-02-0 IDA / Q9790 g capacities for priority fish Post Open - National 35,000.00 0.00 Canceled 2019-07-26 Bureaux de 06 DRRHP - Exte Based Selection 6 9 7 6 1 4 3 eries management nsion de l'ASH à Antsiranana et Morondava - Construction local pour bureau UGP et 0 8 CirRHP (APS/APD) MG-MRHP-285789-CS-CQS / Recrutement d'une firme po Component 2. Strengthenin Consultant Qualif 2022-04-1 2022-06-0 2022-07-0 2022-08-0 2023-02-0 ur mettre à jour l’enquête c IDA / 59870 g capacities for priority fish Post Open - National 100,000.00 0.00 Canceled 2022-03-28 ication Selection 8 1 1 5 1 adre nationale 2012-2013 s eries management ur la petite pêche maritime et la pêche continentale MG-MRHP-150366-CS-CQS / RECRUTEMENT D'UN CONSU Component 2. Strengthenin LTANT NATIONAL POUR LA F Consultant Qualif 2021-07-3 2021-08-2 2021-10-0 2021-10-2 2021-12-1 IDA / 59870 g capacities for priority fish Post Open - National 15,000.00 0.00 Canceled 2021-07-23 ORMATION ET RENFORCEME ication Selection 0 7 6 0 9 eries management NT DE CAPACITE DE L’EQUIP E EN COMMUNICATION (2.1. 4.1.05) MG-MRHP-150361-CS-CQS / RECRUTEMENT D'UN CONSU LTANT NATIONAL POUR LE R Component 2. Strengthenin ENFORCEMENT DE CAPACIT Consultant Qualif Pending Implem 2022-11-0 2022-12-0 2023-01-1 2023-01-2 2023-03-3 IDA / 59870 g capacities for priority fish Post Open - National 8,000.00 0.00 2022-11-01 E DU PERSONNEL DE L’AUT ication Selection entation 8 6 5 9 0 eries management ORITE SANITAIRE HALIEUTIQ UE EN INFORMATIQUE (BUR EAUTIQUE ET PROGRAMMAT ION) AU NIVEAU NATIONAL ( 2.1.7.2.02) MG-MRHP-298214-CS-CQS / Recrutement d’une firme ch Component 3. Strengthenin argée de l’appui à la promot g capacities for engaging in Consultant Qualif Under Implemen 2022-06-1 2022-07-1 2022-08-1 2022-09-1 2022-10-0 2023-09-2 IDA / 59870 Post Open - National 70,000.00 0.00 2022-06-30 ion des produits halieutique alternative fishing practices ication Selection tation 5 4 8 7 1 6 s valorisés au niveau des ZU and livelihoods activities P sur le marché national/inte rnational MG-MRHP-304395-CS-CQS / Recrutement d’une firme po Component 3. Strengthenin ur l’étude de faisabilité de m g capacities for engaging in Consultant Qualif Under Implemen 2022-07-2 2022-08-1 2022-10-0 2022-11-0 2022-12-0 2023-03-0 IDA / 59870 Post Open - National 60,000.00 0.00 2022-07-29 ise en place d’unités de pro alternative fishing practices ication Selection tation 2 9 2 1 6 6 duction artisanale de conser and livelihoods activities ves de sardines à BATAN et BA MG-MRHP-304402-CS-QCBS Component 2. Strengthenin / Recrutement d'une firme p Quality And Cost- Open - Internation Under Implemen 2022-08-0 2022-08-1 2022-08-2 2022-10-0 2022-10-3 2022-11-2 2023-01-0 2023-02-0 2023-08-0 IDA / 59870 g capacities for priority fish Post 205,000.00 0.00 2022-07-29 our la lise en place des outil Based Selection al tation 3 9 2 2 0 9 3 7 6 eries management s d'aménagement des pêch eries à Madagascar MG-MRHP-307091-CS-CQS / Component 2. Strengthenin Evaluation des emplois direc Consultant Qualif Under Implemen 2022-09-1 2022-09-0 2022-10-0 2022-10-1 2022-11-1 2022-12-2 2023-06-1 IDA / 59870 g capacities for priority fish Post Open - National 20,000.00 0.00 2022-08-12 ts et indirects issus de la pet ication Selection tation 5 2 7 6 5 0 8 eries management ite pêche au niveau des 03 ZUP du Projet MG-MRHP-307110-CS-CQS / Elaboration de Cartographie Component 2. Strengthenin Consultant Qualif Under Implemen 2022-09-1 2022-09-0 2022-10-3 2022-10-1 2022-11-1 2022-12-2 2023-06-1 détaillée pour le développe IDA / 59870 g capacities for priority fish Post Open - National 150,000.00 0.00 2022-08-12 ication Selection tation 5 2 1 6 5 0 8 ment de l’holothuriculture, l eries management a crabiculture, l’algoculture et l’aquaculture continental e. MG-MRHP-307200-CS-CQS / Recrutement d’une firme po Component 2. Strengthenin Consultant Qualif Under Implemen 2022-09-1 2022-08-3 2022-10-2 2022-10-0 2022-11-0 2022-12-0 2023-06-1 ur la mise en place d’un site IDA / 59870 g capacities for priority fish Post Open - National 20,000.00 0.00 2022-08-09 ication Selection tation 5 0 7 4 3 8 6 web dynamique du Ministèr eries management e de la Pêche et de l’Écono mie Bleue MG-MRHP-306851-CS-CQS / Etude technique, l'élaboratio Component 2. Strengthenin Consultant Qualif Under Implemen 2022-11-2 2022-10-2 2022-12-1 2022-12-0 2023-01-0 2023-02-0 2023-08-0 n du PGES , contrôle et surv IDA / 59870 g capacities for priority fish Post Open - National 60,000.00 0.00 2022-09-29 ication Selection tation 4 0 5 3 2 6 5 eillance des travaux de cons eries management truction de l'antenne CDPH M à Besalampy MG-MRHP-306857-CS-CQS / Component 3. Strengthenin Etude techniques élaboratio g capacities for engaging in Consultant Qualif Under Implemen 2022-11-2 2022-10-1 2022-12-1 2022-12-0 2023-01-0 2023-02-0 2023-08-0 n PGES et Contrôle & surveil IDA / 59870 Post Open - National 35,000.00 0.00 2022-09-28 alternative fishing practices ication Selection tation 4 9 6 2 1 5 4 lance de la Construction déb and livelihoods activities arcadère à Ankazomborona MG-MRHP-320120-CS-CQS / Component 3. Strengthenin Recrutement d'une associati g capacities for engaging in Consultant Qualif Under Implemen 2022-10-2 2022-10-2 2022-10-3 2022-11-1 2022-12-0 2022-12-1 2023-09-2 on pour l’étude et la mise en IDA / 59870 Post Open - National 40,000.00 0.00 2022-10-21 alternative fishing practices ication Selection tation 7 2 1 9 3 7 9 place d’habitats artificiels d and livelihoods activities ans quatre zones côtières Page 9 MG-MRHP-320122-CS-CQS / Recrutement d'une firme po Component 2. Strengthenin Consultant Qualif Under Implemen 2022-10-2 2022-11-0 2022-12-0 2022-12-0 2023-01-0 2023-01-2 2023-05-2 ur l'élaboration de la Politiqu IDA / 59870 g capacities for priority fish Post Open - National 75,000.00 0.00 2022-10-21 ication Selection tation 5 4 6 9 8 9 9 e Nationale intégrée de la G eries management ouvernance de l'Océan à Ma dagascar MG-MRHP-355022-CS-CQS / Component 3. Strengthenin Recrutement d’une ONG po g capacities for engaging in Consultant Qualif Under Implemen 2023-05-0 2023-04-2 2023-05-2 2023-05-1 2023-05-2 2023-05-3 2023-08-2 IDA / 59870 Post Open - National 250,000.00 0.00 2023-04-09 ur la mise en œuvre des Acti alternative fishing practices ication Selection tation 9 4 3 9 4 1 9 vités Alternatives (PARAR/A and livelihoods activities GR) MG-MRHP-239021-CS-CQS / Component 4. Project mana Consultant Qualif Under Implemen 2023-05-2 2023-05-2 2023-05-2 2023-06-0 2023-07-0 2023-07-2 2023-09-2 Recrutement firme pour l'év IDA / 59870 Post Open - National 75,000.00 0.00 2023-05-10 gement and coordination ication Selection tation 3 4 5 7 7 1 9 aluation finale du projet SWI OFish2 MG-MRHP-239020-CS-CQS / Component 2. Strengthenin Recrutement d'une firme po Consultant Qualif Under Implemen 2023-05-0 2023-05-2 2023-05-2 2023-06-2 2023-07-1 2023-07-2 2023-09-2 IDA / 59870 g capacities for priority fish Post Open - National 25,000.00 0.00 2023-05-10 ur l'élaboration de manuel d ication Selection tation 9 4 2 8 2 6 4 eries management e l'audit interne du MPEB MG-MRHP-362176-CS-CQS / Renforcement de capacité d Component 3. Strengthenin u comité de gestion des infr g capacities for engaging in Consultant Qualif Under Implemen 2023-06-1 2023-07-2 2023-08-0 2023-08-1 2023-09-1 IDA / 59870 Post Open - National 270,000.00 0.00 2023-05-26 astructures sur la gestion de alternative fishing practices ication Selection tation 6 1 5 5 4 s infrastructures et appui à l' and livelihoods activities opérationnalisation des petit es infrastructures; Component 3. Strengthenin MG-MRHP-363621-CS-CQS / g capacities for engaging in Consultant Qualif Under Implemen 2023-06-0 2023-06-1 2023-06-1 2023-06-2 2023-07-1 2023-07-2 2023-09-1 Formation sur la fabrication IDA / 59870 Post Open - National 30,000.00 0.00 2023-05-30 alternative fishing practices ication Selection tation 6 4 4 4 4 1 9 des pirogues and livelihoods activities MG-MRHP-4770-CS-CQS / C onception d'un système de c Component 2. Strengthenin Consultant Qualif Open - Internation 2017-02-2 2017-04-0 2017-05-0 2017-06-1 2017-12-0 ollecte de données pour les IDA / Q9790 g capacities for priority fish Post 10,000.00 0.00 Canceled 2017-02-01 ication Selection al 2 7 7 1 8 pêcheries traditionnelles, y eries management compris une stratégie d'éch antillonnage appropriée MG-MRHP-4769-CS-CQS / Mi Component 2. Strengthenin se à jour de la Stratégie d'a Consultant Qualif Open - Internation 2017-02-2 2017-04-0 2017-05-0 2017-06-1 2017-12-0 IDA / Q9790 g capacities for priority fish Post 75,000.00 0.00 Canceled 2017-02-01 quaculture et élaboration de ication Selection al 2 7 7 1 8 eries management plan de développement des 03 filières aquaculture INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Identifie Loan / Credit Market Approa Contract Type Estimated Am Actual Amou Process Statu Draft Negotiated Co Description Component Review Type Method Terms of Reference d/Selected Consulta Signed Contract Contract Completion No. ch ount (US$) nt (US$) s ntract nt Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MG-MRHP-23395-CS-INDV// PA75 / Recrutement d'un (0 Component 4. Project mana Individual Consul 2017-08-0 2017-09-2 2017-09-2 2017-10-1 2017-10-0 2017-11-2 2017-10-0 2018-05-2 2019-04-0 1) Spécialiste en Passation d IDA / Q9790 Post Open 15,600.00 15,412.69 Completed 2017-08-02 gement and coordination tant Selection 3 0 1 1 2 2 3 1 1 es Marchés en appui à l'équi pe de passation des marché s de l'UGP SWIOFish2. MG-MRHP-28176-CS-INDV// MG-PM-24 / Diagnostic des t echniques de valorisation pr Component 3. Strengthenin atiquées à Madagascar et le g capacities for engaging in Individual Consul 2018-02-1 2018-03-1 2018-04-1 2018-10-0 IDA / 59870 Post Open 30,000.00 0.00 Canceled 2017-11-30 s bonnes pratique en Afriqu alternative fishing practices tant Selection 8 8 0 7 e et identifier les besoins en and livelihoods activities technique de valorisation de s produits halieutiques de ch aque région ultra prioritaire MG-MRHP-28321-CS-INDV// Component 3. Strengthenin MG-PM-26 / Évaluation du ni g capacities for engaging in Individual Consul 2018-01-1 2018-01-3 2018-03-1 2018-09-1 IDA / D1720 Post Open 90,000.00 0.00 Canceled 2017-10-30 veau de vulnérabilité des m alternative fishing practices tant Selection 0 1 4 0 énages bénéficiaires and livelihoods activities MG-MRHP-28328-CS-INDV// Component 3. Strengthenin MG-PM-30 / Élaboration du p g capacities for engaging in Individual Consul 2018-01-2 2018-02-1 2018-03-2 2018-09-2 IDA / 59870 Post Open 10,500.00 0.00 Canceled 2017-10-30 lan stratégique de développ alternative fishing practices tant Selection 5 5 9 5 ement local (PCD et PLD) and livelihoods activities MG-MRHP-28338-CS-INDV// Component 4. Project mana Individual Consul 2017-12-2 2018-01-1 2018-02-2 2018-08-2 MG-PM-35 / Assistants coord IDA / 59870 Post Open 20,800.00 0.00 Canceled 2017-10-16 gement and coordination tant Selection 0 0 1 0 inateurs locaux UGL MG-MRHP-28344-CS-INDV// MG-PM-41 / Élaboration d'un Component 4. Project mana Individual Consul 2018-02-2 2018-03-1 2018-04-2 2018-10-2 IDA / 59870 Post Open 10,000.00 0.00 Canceled 2017-12-15 e stratégie du plan de comm gement and coordination tant Selection 5 8 9 6 unication du projet SWIOFis h2 MG-MRHP-28345-CS-INDV// Component 4. Project mana Individual Consul 2018-01-2 2018-02-1 2018-03-3 2018-09-2 MG-PM-42 / Mise en place d IDA / 59870 Post Open 2,000.00 0.00 Canceled 2017-11-15 gement and coordination tant Selection 6 6 0 6 u site internet du projet SWI OFish2 MG-MRHP-28346-CS-INDV// Component 4. Project mana Individual Consul 2018-02-1 2018-03-1 2018-04-2 2018-10-1 MG-PM-43 / Mission de couv IDA / 59870 Post Open 1,000.00 0.00 Canceled 2017-12-15 gement and coordination tant Selection 8 1 2 9 erture des autres activités d e communication MG-MRHP-27289-CS-INDV// Component 2. Strengthenin PA27 / Évaluation et dévelop Individual Consul 2015-09-0 2017-10-2 2017-11-1 2016-11-0 2017-12-2 2017-11-1 2018-06-1 2018-08-3 IDA / Q9790 g capacities for priority fish Post Open 50,000.00 35,963.63 Completed 2017-09-07 pement de la recherche hali tant Selection 9 6 6 1 1 4 9 0 eries management eutique (pour les 5 filières p rioritaires MG-MRHP-28651-CS-INDV// Component 2. Strengthenin Individual Consul 2018-09-0 2018-09-2 2018-11-0 2019-05-0 MG-PM-111 / Assistance Tec IDA / 59870 g capacities for priority fish Post Open 10,000.00 0.00 Canceled 2018-07-02 tant Selection 5 6 7 6 hnique juridique pour le SLC eries management MG-MRHP-28653-CS-INDV// MG-PM-112 / Étude et analy Component 2. Strengthenin se diagnostiques des stratég Individual Consul 2018-04-0 2018-04-2 2018-06-0 2018-12-0 IDA / 59870 g capacities for priority fish Post Open 30,000.00 0.00 Canceled 2018-01-30 ies du secteur et des ancien tant Selection 5 6 7 4 eries management s plans directeurs et élabora tion du nouveau plan directe ur MG-MRHP-28692-CS-INDV// Component 2. Strengthenin MG-PM-136 / Développemen Individual Consul 2018-05-0 2018-05-2 2018-06-3 2018-12-2 IDA / 59870 g capacities for priority fish Post Open 30,000.00 0.00 Canceled 2018-03-01 t des points de référence op tant Selection 5 6 0 7 eries management érationnels pour la gestion d e la pêche crevettière MG-MRHP-28704-CS-INDV// Component 2. Strengthenin Individual Consul 2018-08-0 2018-08-2 2018-09-3 2019-03-2 MG-PM-148 / Audit techniqu IDA / 59870 g capacities for priority fish Post Open 30,000.00 0.00 Canceled 2018-06-01 tant Selection 5 6 0 9 e et financier de la pêche au eries management x thons MG-MRHP-28744-CS-INDV// Component 3. Strengthenin MG-PM-169 / Prestataire for g capacities for engaging in Individual Consul 2019-01-0 2019-01-2 2019-03-0 2019-08-2 IDA / 59870 Post Open 30,000.00 0.00 Canceled 2018-11-01 mateur en construction et e alternative fishing practices tant Selection 5 6 2 9 ntretien des embarcations and livelihoods activities MG-MRHP-28751-CS-INDV// Component 3. Strengthenin MG-PM-174 / Prestataire for g capacities for engaging in Individual Consul 2018-08-1 2018-09-0 2018-10-1 2019-04-1 IDA / 59870 Post Open 75,000.00 0.00 Canceled 2018-06-15 mateur en technique de val alternative fishing practices tant Selection 9 9 4 2 orisation and livelihoods activities MG-MRHP-28752-CS-INDV// Component 3. Strengthenin MG-PM-175 / Prestataire for g capacities for engaging in Individual Consul 2018-09-1 2018-10-0 2018-11-1 2019-05-1 IDA / 59870 Post Open 25,000.00 0.00 Canceled 2018-06-29 mateur en technique comm alternative fishing practices tant Selection 7 8 2 1 erciale and livelihoods activities MG-MRHP-28758-CS-INDV// MG-PM-181 / Étude d'impact Component 3. Strengthenin environnemental et social d g capacities for engaging in Individual Consul 2018-07-1 2018-08-0 2018-09-1 2019-03-1 IDA / 59870 Post Open 90,000.00 0.00 Canceled 2018-05-30 es constructions d'infrastruc alternative fishing practices tant Selection 8 8 2 1 tures de pêche(APS & APD) ( and livelihoods activities 33 débarcadères, 8 marchés couverts) MG-MRHP-28762-CS-INDV// Component 3. Strengthenin MG-PM-184 / Gestion et mis g capacities for engaging in Individual Consul 2018-07-1 2018-08-0 2018-09-1 2019-03-1 IDA / V0500 Post Open 15,000.00 0.00 Canceled 2018-05-30 e en œuvre : évaluation de l alternative fishing practices tant Selection 8 8 2 1 a mise en place de l'électrifi and livelihoods activities cation hors grille MG-MRHP-28765-CS-INDV// Component 4. Project mana Individual Consul 2018-11-1 2018-12-1 2019-01-1 2019-07-1 MG-PM-188 / Responsable P IDA / 59870 Post Open 7,800.00 0.00 Canceled 2018-10-01 gement and coordination tant Selection 9 0 4 3 assation de marché MG-MRHP-28769-CS-INDV// MG-PM-191 / Mission de cou Component 4. Project mana Individual Consul 2018-04-1 2018-05-1 2018-06-1 2018-12-1 IDA / 59870 Post Open 1,000.00 0.00 Canceled 2018-03-01 verture des autres activités gement and coordination tant Selection 9 0 4 1 de communication MG-MRHP-28770-CS-INDV// Component 4. Project mana Individual Consul 2018-04-1 2018-05-0 2018-06-1 2018-12-1 MG-PM-192 / Réalisation du IDA / 59870 Post Open 8,000.00 0.00 Canceled 2018-02-28 gement and coordination tant Selection 8 9 3 0 Bulletin trimestriel SWIOFish 2 MG-MRHP-14956-CS-INDV// 70 / PA 70: Etude sur l'adapt Component 2. Strengthenin Individual Consul 2018-02-1 2018-02-2 2018-04-0 2018-10-0 ation des missions et attribu IDA / Q9790 g capacities for priority fish Post Open 15,000.00 0.00 Canceled 2017-11-30 tant Selection 0 4 7 4 tions du MRHP par rapport a eries management ux défis du développement r ural MG-MRHP-14959-CS-INDV// Component 3. Strengthenin PA71 / PA 71: Mise en place g capacities for engaging in Individual Consul 2018-07-2 2018-08-0 2018-09-2 2019-03-1 IDA / Q9790 Post Open 1,000.00 0.00 Canceled 2018-05-31 d'une règlementation de bas alternative fishing practices tant Selection 6 9 0 9 e concernant la sécurité en and livelihoods activities mer de la petite pêche MG-MRHP-14955-CS-INDV// Component 2. Strengthenin 69 / PA 69: Elaboration du S Individual Consul 2018-06-2 2018-07-1 2018-08-1 2019-02-1 IDA / Q9790 g capacities for priority fish Post Open 8,000.00 0.00 Canceled 2018-05-15 chéma d'aménagement aqu tant Selection 6 0 4 0 eries management acole national (algues, crab es, holothurie etc) MG-MRHP-14954-CS-INDV// PA68 / PA 68: Conception d' Component 2. Strengthenin Individual Consul 2018-02-0 2018-02-1 2018-03-2 2018-09-2 un système de collecte de d IDA / Q9790 g capacities for priority fish Post Open 10,000.00 0.00 Canceled 2017-12-30 tant Selection 3 7 4 0 onnées pour les pêcheries tr eries management aditionnelles, y compris une stratégie MG-MRHP-14497-CS-INDV// PA-42 / PA 42: Etude sur les Component 2. Strengthenin Individual Consul 2017-07-0 2017-07-1 2017-08-1 2018-02-1 FFOM et mesures nécessaire IDA / Q9790 g capacities for priority fish Post Open 25,000.00 0.00 Canceled 2017-05-29 tant Selection 3 0 4 0 s pour le développement de eries management la pêche nationale et attirer la flotte étrangère MG-MRHP-14950-CS-INDV// PA64 / PA 64: Etude sur les Component 2. Strengthenin besoins en formation, en Eq Individual Consul 2017-07-0 2017-07-1 2017-08-0 2018-02-0 IDA / Q9790 g capacities for priority fish Prior Open 20,000.00 0.00 Canceled 2017-05-29 uipements et immobiliers de tant Selection 3 0 7 3 eries management l'Administration (Central et DRRHP) Plans de formation et d'investissement MG-MRHP-14948-CS-INDV// Component 2. Strengthenin PA21 / PA 21: Etude de faisa Individual Consul 2018-06-2 2018-07-0 2018-07-3 2019-01-2 IDA / Q9790 g capacities for priority fish Post Open 20,000.00 0.00 Canceled 2018-05-15 bilité du projet d'Ecole Natio tant Selection 6 3 1 7 eries management nale Halieutique, les besoins en formation Page 10 MG-MRHP-28167-CS-QCBS// MG-PM-15 / Développement Component 2. Strengthenin et mise en œuvre du systèm Individual Consul 2018-03-1 2018-04-0 2018-05-1 2018-11-1 IDA / D1720 g capacities for priority fish Post Open 5,000.00 0.00 Canceled 2017-12-15 e de collecte de données po tant Selection 2 2 4 0 eries management ur les pêcheries traditionnell es, y compris une stratégie d'échantillonnage approprié e MG-MRHP-28339-CS-CQS// Component 4. Project mana Individual Consul 2017-08-2 2017-12-0 2018-01-2 2017-12-2 2018-01-2 2018-02-0 2018-02-1 2018-07-3 MG-PM-37 / Recrutement d'u IDA / 59870 Post Open 4,000.00 23,250.53 Signed 2017-10-19 gement and coordination tant Selection 4 7 3 8 3 1 7 1 n Chef Comptable MG-MRHP-28711-CS-QCBS// MG-PM-153 / Étude de prosp Component 2. Strengthenin Individual Consul 2018-12-0 2018-12-2 2019-02-0 2019-08-0 ection des lieux d'implantati IDA / 59870 g capacities for priority fish Post Open 1,500.00 0.00 Canceled 2018-10-01 tant Selection 5 6 6 5 on des deux antennes regio eries management nales de l'USTA (Majunga, T amatave) MG-MRHP-28712-CS-QCBS// Component 2. Strengthenin Individual Consul 2019-02-1 2019-03-0 2019-04-1 2019-10-0 MG-PM-154 / Étude de mise IDA / 59870 g capacities for priority fish Post Open 1,500.00 0.00 Canceled 2018-12-03 tant Selection 3 6 0 7 en place des antennes régio eries management nales MG-MRHP-33990-CS-INDV// Component 2. Strengthenin Individual Consul 2018-01-2 2018-02-1 2018-03-2 2018-09-2 MG-PM 68 / Assistance tech IDA / D1720 g capacities for priority fish Post Open 26,000.00 0.00 Canceled 2017-11-02 tant Selection 1 1 5 1 nique pour le suivi des trava eries management ux de carénage MG-MRHP-86203-CS-INDV// Component 2. Strengthenin Individual Consul 2019-01-3 2019-03-0 2019-04-2 2019-07-0 2020-01-0 PA13 / Mise à jour de la Stra IDA / 59870 g capacities for priority fish Post Open 30,000.00 0.00 Canceled 2018-11-22 tant Selection 1 7 1 5 1 tégie Nationale de l'Aquacul eries management ture MG-MRHP-86204-CS-INDV / Component 2. Strengthenin Recrutement d'un consultan Individual Consul 2018-12-1 2019-03-1 2019-02-2 2019-04-1 2019-02-2 2019-06-2 2018-12-2 2019-12-2 2020-04-0 IDA / D1720 g capacities for priority fish Post Open 55,000.00 39,810.58 Completed 2018-11-26 t pour convertir OPENARTFIS tant Selection 7 1 6 0 6 4 6 1 2 eries management H dans une base de donnée s basée sur le We MG-MRHP-86205-CS-INDV// Component 2. Strengthenin MG-PM 51/18 / Assistance te Individual Consul 2018-08-1 2019-03-0 2018-10-2 2019-04-0 2018-11-0 2019-06-2 2018-11-1 2019-12-1 IDA / D1720 g capacities for priority fish Post Open 26,000.00 24,252.91 Signed 2018-11-22 chnique pour le suivi des tra tant Selection 0 7 3 6 8 0 3 7 eries management vaux de carénage de l'Atsan tsa MG-MRHP-105669-CS-INDV Component 3. Strengthenin / Recrutement d'agence de g capacities for engaging in Individual Consul 2019-03-2 2019-04-2 2019-04-3 2019-05-2 2019-11-2 communication pour la conc IDA / 59870 Post Open 5,625.00 0.00 Canceled 2019-03-12 alternative fishing practices tant Selection 0 3 0 8 4 eption et production des sup and livelihoods activities ports de communications rel atifs au MDGP MG-MRHP-119243-CS-INDV / Assistance technique pour Component 2. Strengthenin Individual Consul 2019-08-0 2019-11-2 2020-01-1 2020-03-2 2020-09-2 la coordination génerale des IDA / 59870 g capacities for priority fish Post Open 15,000.00 0.00 Canceled 2019-08-15 tant Selection 9 8 2 7 3 activités durant l'élaboration eries management du PAP Atsimo Atsinanana MG-MRHP-119244-CS-INDV / Etude sur l'analyse de prob Component 2. Strengthenin Individual Consul 2019-08-0 2020-01-2 2020-01-1 2020-03-1 2020-02-2 2020-05-1 2020-03-0 2020-11-0 lématiques liées à la pratiqu IDA / D1720 g capacities for priority fish Post Open 20,000.00 10,846.29 Signed 2019-10-15 tant Selection 2 8 7 3 1 2 9 8 e courante des sennes de pl eries management age dans la Baie d’ Antongil MG-MRHP-119261-CS-INDV Component 3. Strengthenin / Prestataire formateur en c g capacities for engaging in Individual Consul 2019-12-2 2020-01-2 2020-03-2 2020-09-2 IDA / 59870 Post Open 30,000.00 0.00 Canceled 2019-09-15 onstruction et entretien des alternative fishing practices tant Selection 9 8 8 4 engins de pêche and livelihoods activities Component 3. Strengthenin MG-MRHP-119286-CS-INDV g capacities for engaging in Individual Consul 2019-12-1 2020-01-1 2020-03-2 2020-09-2 / Consultance et appui à la c IDA / 59870 Post Open 45,900.00 0.00 Canceled 2019-08-30 alternative fishing practices tant Selection 3 2 7 3 omposante 3 and livelihoods activities MG-MRHP-119288-CS-INDV Component 4. Project mana Individual Consul 2019-08-2 2019-10-2 2019-10-2 2019-11-2 2019-11-1 2020-01-1 2019-11-2 2020-07-1 / Consultance et appui à la IDA / 59870 Post Open 15,300.00 11,155.20 Terminated 2019-07-31 gement and coordination tant Selection 8 9 2 8 2 8 6 6 composante 4 MG-MRHP-119289-CS-CDS / Component 4. Project mana 2019-07-2 2019-08-1 2019-08-0 2019-11-1 2019-08-1 2020-05-1 IDA / 59870 Post Direct Selection Direct 20,400.00 32,788.66 Signed 2019-07-15 Responsable Administratif et gement and coordination 9 9 8 7 6 5 Financier MG-MRHP-119291-CS-INDV Component 4. Project mana Individual Consul Under Implemen 2019-10-1 2019-10-2 2019-11-2 2020-01-1 2020-07-1 IDA / 59870 Post Open 4,200.00 0.00 2019-07-31 / Personnel d'appui : Secréta gement and coordination tant Selection tation 0 9 8 8 6 ire MG-MRHP-28341-CS-CQS// Component 4. Project mana Individual Consul 2017-08-2 2019-09-0 2018-01-2 2019-09-2 2018-01-2 2019-10-2 2018-03-0 2020-04-2 MG-PM-38 / Recrutement de IDA / 59870 Post Open 24,000.00 47,399.30 Signed 2019-07-15 gement and coordination tant Selection 4 2 2 3 3 8 6 5 deux (02) Comptables MG-MRHP-119292-CS-INDV Component 4. Project mana Individual Consul Pending Implem 2019-07-2 2019-08-1 2019-09-1 2020-03-1 / Personnel d'appui (Femme IDA / 59870 Post Limited 1,320.00 0.00 2019-07-15 gement and coordination tant Selection entation 0 0 4 2 de ménage et gardien) MG-MRHP-119293-CS-INDV Component 4. Project mana Individual Consul Pending Implem 2019-07-2 2019-08-1 2019-09-1 2020-03-1 IDA / 59870 Post Limited 25,200.00 0.00 2019-07-15 / Personnel d'appui : Chauffe gement and coordination tant Selection entation 0 0 4 2 ur MG-MRHP-28673-CS-INDV// Component 2. Strengthenin MG-PM-124 / Amélioration d Individual Consul 2019-09-0 2019-09-2 2019-10-3 2020-04-2 IDA / D1720 g capacities for priority fish Post Open 15,000.00 0.00 Canceled 2019-07-01 e la base de données pour l tant Selection 4 5 0 7 eries management es pêcheries industrielles MG-MRHP-23395-CS-INDV// SPM / Frais de personnel du projet : recrutement d'un (0 Component 4. Project mana Individual Consul 2019-08-0 2019-09-1 2019-10-0 2019-10-0 2019-10-1 2019-11-0 2019-10-2 2020-05-0 IDA / 59870 Post Open 88,400.00 14,322.53 Signed 2019-07-26 1) Spécialiste en Passation d gement and coordination tant Selection 1 3 4 4 5 8 1 6 es Marchés en appui à l'équi pe de passation des marché s de l'UGP SWIOFish2. MG-MRHP-119243BIS-CS-IN DV / Recrutement d’un cons ultant individuel pour l’assis Component 2. Strengthenin Individual Consul 2019-08-2 2019-12-1 2019-10-2 2020-01-2 2019-11-2 2020-04-1 2019-12-0 2020-10-0 tance technique de l’Admini IDA / 59870 g capacities for priority fish Post Open 35,000.00 89,509.64 Signed 2019-08-15 tant Selection 2 3 2 7 7 1 2 8 stration en charge de la Pêc eries management he et de l’Aquaculture et de l’UGP du Projet SWIOFish2 d ans le cadre de la Cogestion MG-MRHP-123343-CS-INDV / Développer la base de don nées intégrée des pêches de Component 2. Strengthenin Madagascar et le registre de Individual Consul 2019-08-2 2019-11-0 2019-10-2 2019-11-2 2020-02-1 2020-01-0 2020-02-2 2020-07-0 IDA / D1720 g capacities for priority fish Post Open 50,000.00 38,851.99 Signed 2019-09-02 s pêcheurs et embarcations tant Selection 2 6 2 7 9 8 0 6 eries management dans une base de donnée b asé sur le Web (lignes des é tudes regroupées: 2.1.2.1.1 3 - 2.1.2.1.13.1 - 2.1.2.1.13. 2) MG-MRHP-28764-CS-INDV// Component 4. Project mana Individual Consul 2018-11-1 2018-12-1 2019-01-1 2019-07-1 MG-PM-187 / Assistants coor IDA / 59870 Post Open 62,400.00 0.00 Canceled 2018-10-01 gement and coordination tant Selection 9 0 4 3 dinateurs locaux UGL MG-MRHP-28735-CS-INDV// Component 3. Strengthenin MG-PM-164 / Recensement g capacities for engaging in Individual Consul 2018-05-0 2018-05-2 2018-06-2 2018-12-2 IDA / 59870 Post Open 20,000.00 0.00 Canceled 2018-02-28 et identification des bénéfici alternative fishing practices tant Selection 4 5 9 6 aires chaque année and livelihoods activities MG-MRHP-127608-CS-INDV Component 4. Project mana Individual Consul 2019-12-2 2020-01-2 2020-03-1 2020-09-0 IDA / 59870 Post Open 1,500.00 0.00 Canceled 2019-09-23 / Assistance technique - mai gement and coordination tant Selection 2 1 2 8 ntenance MG-MRHP-28926-CS-INDV// Component 4. Project mana Individual Consul 2018-03-2 2018-04-1 2018-05-1 2018-11-1 MG-PM-17 / Évaluation seme IDA / 59870 Post Open 3,500.00 0.00 Canceled 2018-01-15 gement and coordination tant Selection 1 1 6 2 strielle du projet MG-MRHP-127606-CS-INDV Component 2. Strengthenin Individual Consul 2019-12-1 2020-01-1 2020-03-0 2020-09-0 / Etude diagnostic sur la pêc IDA / 59870 g capacities for priority fish Post Open 20,000.00 0.00 Canceled 2019-09-18 tant Selection 7 6 7 3 herie crevettière à Madagas eries management car MG-MRHP-141087-CS-INDV Component 4. Project mana Individual Consul 2019-10-2 2019-11-2 2019-12-1 2019-11-2 2019-12-1 2019-11-2 2019-12-1 2022-11-2 / Recrutement d’un Chef Co IDA / 59870 Post Open 39,000.00 22,844.93 Signed 2019-10-31 gement and coordination tant Selection 8 1 1 3 3 7 9 6 mptable (CC) au sein de l’U GP MG-MRHP-141088-CS-INDV Component 4. Project mana Individual Consul 2019-10-2 2019-11-2 2019-12-0 2019-11-2 2019-12-1 2019-11-2 2019-12-1 2022-11-2 IDA / 59870 Post Open 24,000.00 17,668.00 Terminated 2019-10-31 / Recrutement d'un comptab gement and coordination tant Selection 8 1 9 3 3 7 8 6 le MG-MRHP-146229-CS-INDV / Recrutement d’un consulta Component 2. Strengthenin nt national pour animer l’ate Individual Consul 2019-10-1 2019-11-2 2019-10-2 2019-12-0 2019-11-1 2019-12-2 2019-12-0 2020-01-0 IDA / 59870 g capacities for priority fish Post Limited 2,800.00 2,496.64 Signed 2019-11-21 lier national relatif à la com tant Selection 4 6 3 1 3 2 5 5 eries management munication de la nouvelle loi portant Code de la Pêche et de l'Aquaculture à Madagas car MG-MRHP-146231-CS-INDV / Recrutement d’un Assistan t Technique pour les constru Component 4. Project mana Individual Consul 2019-12-0 2019-12-1 2020-01-1 2019-12-2 2020-01-2 2019-12-2 2020-01-2 2022-12-2 IDA / 59870 Post Open 25,000.00 25,491.34 Signed 2019-11-21 ctions et réhabilitations d’ in gement and coordination tant Selection 6 5 7 5 4 9 5 8 frastructures de pêche, com munautaires et administrati ves MG-MRHP-119287-CS-CDS / Component 4. Project mana 2019-10-2 2020-02-1 2020-08-0 Contrôle et surveillance de l IDA / 59870 Post Direct Selection Direct 12,000.00 0.00 Canceled 2019-08-30 gement and coordination 9 1 9 a construction de bureau de l'UGP centrale MG-MRHP-149046-CS-CDS / RECRUTEMENT DE CONSULT ANT NATIONAL POUR ASSUR Component 2. Strengthenin 2019-12-2 2020-01-0 2020-05-1 2020-01-2 2020-09-0 2020-02-0 ER LE RENFORCEMENT DE C IDA / 59870 g capacities for priority fish Post Direct Selection Direct 6,290.00 7,739.85 Signed 2019-12-30 6 5 4 0 5 4 APACITES DES BIOLOGISTES eries management DU CDA DANS LE DOMAINE DE L’AQUACULTURE MARINE ET DULCAQUICOLE (2.1.1.3. 03) MG-MRHP-160293-CS-INDV / Recrutement d'un consulta Component 2. Strengthenin Individual Consul 2020-02-2 2020-03-3 2020-06-1 2020-04-0 2020-09-1 2020-04-2 2020-11-2 2020-08-1 nt pour l'élaboration de proc IDA / 59870 g capacities for priority fish Post Open 15,000.00 86,190.00 Signed 2020-02-27 tant Selection 5 0 8 9 5 3 6 1 édure de délivrance des cart eries management es pêcheurs et d'immatricul ation des pirogues MG-MRHP-160452-CS-INDV Component 2. Strengthenin / Recrutement d’un Assistan Individual Consul 2020-03-0 2020-04-1 2020-07-0 2020-05-1 2020-08-1 2020-05-2 2020-08-1 2022-05-2 IDA / D1720 g capacities for priority fish Post Open 85,000.00 15,207.52 Signed 2020-03-10 t technique pour l’ Appui au tant Selection 6 9 1 0 7 4 9 4 eries management renforcement des capacités opérationnelles du CSP MG-MRHP-160443-CS-CDS / Component 2. Strengthenin Recrutement d'Institut de Fo Under Implemen 2020-03-0 2020-03-1 2020-04-1 2020-04-2 IDA / 59870 g capacities for priority fish Post Direct Selection Direct 3,000.00 0.00 2020-03-09 rmation en technique d'anal tation 1 9 7 7 eries management yse de détection de maladie aquatique MG-MRHP-161605-CS-INDV / Recrutement d'un consulta Component 4. Project mana Individual Consul 2020-03-0 2020-04-2 2020-05-2 2020-05-1 2020-06-2 2020-05-2 2020-06-2 2020-09-2 nt individuel pour la réalisati IDA / 59870 Post Open 100,000.00 34,272.29 Signed 2020-03-13 gement and coordination tant Selection 2 7 6 1 2 5 4 2 on de l’évaluation à mi-parc ours des objectifs du projet SWIOFish2 MG-MRHP-161625-CS-CDS / Component 2. Strengthenin Recrutement d'un BE pour l 2020-03-2 2020-03-2 2020-05-2 2020-05-3 2020-11-0 2021-10-2 IDA / 59870 g capacities for priority fish Post Direct Selection Direct 12,600.00 22,582.18 Signed 2020-03-16 e contrôle et la surveillance 0 6 6 0 6 7 eries management des travaux du CIRAEP Mar oantsetra Page 11 MG-MRHP-159186-CS-CDS / Component 3. Strengthenin Recrutement d'une Associati g capacities for engaging in 2020-04-1 2020-04-1 2020-05-1 2020-05-0 2020-08-1 2021-10-3 on/ONG pour la promotion d IDA / 59870 Post Direct Selection Direct 90,000.00 90,332.42 Signed 2020-03-31 alternative fishing practices 6 0 5 1 9 1 e l'approche Groupe d'Eparg and livelihoods activities ne Communautaire (GEC) Zo ne BATAN (3.2.5.1.02.1) MG-MRHP-165352-CS-CDS / Component 3. Strengthenin Recrutement d'une Associati g capacities for engaging in 2020-04-1 2020-04-1 2020-09-1 2020-05-0 2021-01-1 2021-11-0 on / ONG pour la promotion IDA / 59870 Post Direct Selection Direct 90,000.00 80,997.01 Signed 2020-04-01 alternative fishing practices 6 1 8 2 4 1 de l'approche Groupe d'Epar and livelihoods activities gne Communautaire (GEC) Zone MELAKY (3.2.5.1.02.1) MG-MRHP-165351-CS-CDS / Component 3. Strengthenin Recrutement d'une Associati g capacities for engaging in 2020-04-1 2020-04-2 2020-07-2 2020-05-1 2020-10-0 2021-11-1 on / ONG pour la promotion IDA / 59870 Post Direct Selection Direct 90,000.00 75,162.11 Signed 2020-04-10 alternative fishing practices 6 0 4 1 9 0 de l'approche Groupe d'Epar and livelihoods activities gne Communautaire (GEC) Zone BA (3.2.5.1.02.1) MG-MRHP-167265-CS-CDS / Acquisition et maintenance Component 4. Project mana 2020-04-0 2020-04-2 2020-04-1 2020-06-2 2020-05-1 2020-12-2 d'un Logiciel Informatisé de IDA / 59870 Post Direct Selection Direct 50,000.00 40,829.47 Signed 2020-04-10 gement and coordination 7 0 6 4 2 1 Gestion Administrative, Com ptable, Budgétaire et Financ ière pour le Projet SWIOFish 2 MG-MRHP-119242-CS-INDV Component 2. Strengthenin / Elaboration du plan de dév Individual Consul 2019-11-1 2019-12-1 2020-02-1 2020-08-1 IDA / 59870 g capacities for priority fish Post Open 20,000.00 0.00 Canceled 2019-08-01 eloppement des 3 filières aq tant Selection 4 4 2 0 eries management uaculture (algue,holothurie, crabe) MG-MRHP-149438-CS-INDV / Recrutement d'un Consulta nt individuel pour la facilitati Component 2. Strengthenin on des ateliers de sensibilisa Individual Consul 2020-04-1 2020-06-2 2020-05-2 2020-07-0 2020-09-0 2020-07-1 2020-10-0 2020-09-1 IDA / 59870 g capacities for priority fish Post Limited 3,000.00 8,439.82 Signed 2020-06-19 tion régionale au niveau des tant Selection 6 5 7 2 8 6 8 4 eries management 13 régions côtières, relatifs à la communication de la no uvelle loi portant Code de la Pêche et de l'Aquaculture à Madagascar MG-MRHP-119286-CS-INDV- 2 / Recrutement d’un Consul Component 3. Strengthenin tant individuel pour l’appui t g capacities for engaging in Individual Consul 2020-04-2 2020-06-0 2020-07-2 2020-06-2 2020-08-1 2020-07-0 2020-08-2 2021-07-0 TF / A4588 Post Open 85,000.00 26,683.05 Signed 2020-04-24 echnique à la mise en œuvr alternative fishing practices tant Selection 1 6 4 0 4 4 7 4 e de l’électrification hors gril and livelihoods activities le dans le cadre du projet S WIOFish2 MG-MRHP-28756-CS-INDV// Component 3. Strengthenin MG-PM-178 / Élaboration du g capacities for engaging in Individual Consul 2019-11-0 2019-12-1 2020-01-2 2020-03-2 2020-09-2 IDA / 59870 Post Open 300,000.00 0.00 Canceled 2019-08-30 plan stratégique de dévelop alternative fishing practices tant Selection 5 3 7 7 3 pement local (PCD et PLD) and livelihoods activities MG-MRHP-170896-CS-INDV / Recrutement d'un Consulta Component 2. Strengthenin Individual Consul Under Implemen 2020-05-2 2020-07-0 2020-07-2 2020-09-0 2021-09-0 nt pour la mise en place de IDA / D1720 g capacities for priority fish Post Open 30,000.00 0.00 2020-05-04 tant Selection tation 4 8 9 9 9 Base Des Données et la con eries management ception d'un logiciel de colle cte de données_OEPA MG-MRHP-119288BIS-CS-IN DV / Recrutement d'un resp Component 4. Project mana Individual Consul 2019-08-2 2020-03-2 2020-03-2 2020-04-1 2020-04-1 2020-04-2 2020-04-1 2021-04-2 IDA / 59870 Post 15,000.00 13,822.38 Signed 2019-08-19 onsable en communication gement and coordination tant Selection 8 0 0 7 7 0 8 0 2 de l'UGP SWIOfish2 MG-MRHP-170881-CS-INDV Component 2. Strengthenin / Recrutement d’un consulta Individual Consul 2020-05-1 2020-06-2 2020-09-1 2020-07-1 2020-10-0 2020-08-1 2020-10-2 2021-08-1 IDA / 59870 g capacities for priority fish Post Open 15,000.00 13,828.32 Signed 2020-05-04 nt individuel spécialiste de l tant Selection 3 2 6 3 9 7 0 7 eries management a petite pêche au sein de l’U GP du Projet SWIOFish2 MG-MRHP-170887-CS-INDV / Recrutement d’un consulta Component 3. Strengthenin nt individuel spécialiste du d g capacities for engaging in Individual Consul Under Implemen 2020-05-1 2020-07-0 2020-07-2 2020-08-2 2021-08-2 IDA / 59870 Post Open 15,000.00 0.00 2020-05-15 éveloppement des chaines d alternative fishing practices tant Selection tation 4 3 4 8 8 e valeur de la petite pêche a and livelihoods activities u sein de l’UGP du Projet SW IOFish2 MG-MRHP-173507-CS-INDV Component 2. Strengthenin / Recrutement de consultant Individual Consul Under Implemen 2020-05-1 2020-06-2 2020-06-2 2020-07-1 2020-07-2 IDA / 59870 g capacities for priority fish Post Open 15,000.00 0.00 2020-05-20 Individuel pour la formation tant Selection tation 4 2 9 9 9 eries management en technique d'approche et animation rurale MG-MRHP-173508-CS-INDV Component 2. Strengthenin / Recrutement de consultant Individual Consul Under Implemen 2020-05-1 2020-07-1 2020-08-0 2020-09-0 2020-09-1 IDA / 59870 g capacities for priority fish Post Open 15,000.00 0.00 2020-05-20 Individuel pour formation en tant Selection tation 4 7 7 5 5 eries management technique de négociation et leadership MG-MRHP-119245 BIS1-CS- CDS / Recrutement d'un BE Component 2. Strengthenin pour le Contrôle et surveilla 2019-07-2 2019-08-1 2019-08-1 2019-11-1 2020-03-1 2021-04-1 IDA / 59870 g capacities for priority fish Post Direct Selection Direct 56,000.00 51,918.79 Signed 2019-07-24 nce des travaux de construc 4 4 4 2 8 0 eries management tion de l'UGP SWIOFish2 Nan isana, DRRHP Analanjirojo et ASH Morondava MG-MRHP-119245-CS-CDS / Component 2. Strengthenin Contrôle et surveillance des 2019-07-2 2019-10-1 2019-08-1 2020-01-1 2020-07-1 IDA / 59870 g capacities for priority fish Post Direct Selection Direct 84,000.00 0.00 Canceled 2019-08-01 travaux de constructions po 4 5 4 3 1 eries management ur les six (06) DRRHP et h uit (08) CIRRHP MG-MRHP-172004-CS-INDV / Recrutement d’un consulta Component 2. Strengthenin nt individuel pour l’appui tec Individual Consul 2020-05-2 2020-07-1 2020-08-0 2020-08-0 2020-09-0 2020-09-0 2020-10-0 2023-09-0 IDA / 59870 g capacities for priority fish Post Open 50,000.00 13,512.58 Terminated 2020-05-26 hnique à la mise en œuvre d tant Selection 0 4 7 4 1 8 9 8 eries management es activités d’aquaculture d ans le cadre du projet SWIO Fish2 MG-MRHP-28341 BIS 2-CS-I Component 4. Project mana Individual Consul 2019-02-1 2019-03-1 2019-03-0 2019-03-2 2019-03-0 2019-03-3 2019-03-1 2020-03-2 NDV / Recrutement d'un Co IDA / 59870 Post Open 12,000.00 9,065.16 Terminated 2019-02-18 gement and coordination tant Selection 8 2 6 2 7 0 2 9 mptable remplaçant en 201 9 MG-MRHP-179481-CS-INDV Component 3. Strengthenin / Recrutement d’un formate g capacities for engaging in Individual Consul Under Implemen 2020-06-1 2020-07-3 2020-08-2 2020-09-0 2020-11-3 IDA / 59870 Post Open 50,000.00 0.00 2020-06-18 ur sur la technique de pêche alternative fishing practices tant Selection tation 9 0 0 1 0 moderne and livelihoods activities MG-MRHP-179501-CS-INDV Component 2. Strengthenin / RECRUTEMENT D’UN CONS Individual Consul Under Implemen 2020-07-0 2020-08-0 2020-08-2 2020-09-1 2021-03-1 IDA / 59870 g capacities for priority fish Post Open 10,000.00 0.00 2020-06-19 ULTANT SPÉCIALISTE EN SYS tant Selection tation 7 7 8 1 0 eries management TEME D’INFORMATION GEO GRAPHIQUE (SIG) MG-MRHP-179518-CS-CDS / Recrutement d'une firme po Component 2. Strengthenin 2020-06-2 2020-07-0 2020-07-2 2020-07-2 2020-10-0 2020-08-0 2020-10-2 ur assurer le renforcement d IDA / 59870 g capacities for priority fish Post Direct Selection Direct 10,000.00 23,550.98 Completed 2020-06-22 4 9 2 4 2 8 4 es capacités des agents de l eries management a DGPA à l'IHSM en algocult ure et holothuriculture MG-MRHP-182966-CS-INDV Component 2. Strengthenin / Recrutement d'un consulta Individual Consul Under Implemen 2020-07-2 2020-09-0 2020-09-2 2020-10-3 2023-10-3 IDA / 59870 g capacities for priority fish Post Open 23,400.00 0.00 2020-07-17 nt INDIVIDUEL pour Respons tant Selection tation 2 4 5 0 0 eries management able Local de la composante 2 à Nosy be MG-MRHP-182961-CS-INDV Component 2. Strengthenin / Recrutement d'un consulta Individual Consul 2020-07-2 2020-09-0 2020-10-0 2020-09-2 2020-10-1 2020-10-3 2020-10-2 2023-10-3 IDA / 59870 g capacities for priority fish Post Open 23,400.00 6,449.18 Signed 2020-07-17 nt individuel pour Responsa tant Selection 2 4 7 5 3 0 0 0 eries management ble Local de la composante 2 à Maintirano MG-MRHP-105671-CS-INDV Component 3. Strengthenin / Mise en place, Formation, g capacities for engaging in Individual Consul 2019-03-2 2019-05-1 2019-05-2 2019-07-0 2019-12-2 IDA / 59870 Post Open 60,000.00 0.00 Canceled 2019-03-12 Maintenance et Entretien du alternative fishing practices tant Selection 0 4 8 2 9 système en ligne ou platefor and livelihoods activities me MG-MRHP-119245 BIS2-CS- CDS / Recrutement d'un BE Component 2. Strengthenin 2019-07-2 2020-10-2 2019-08-1 2021-01-2 2021-05-1 2022-06-2 pour le Contrôle et surveilla IDA / 59870 g capacities for priority fish Post Direct Selection Direct 34,500.00 13,383.27 Signed 2020-10-05 4 6 4 4 5 3 nce des travaux de construc eries management tion des CIRRHP Ambanja, A mbilobe, MG-MRHP-119248-CS-INDV Component 2. Strengthenin Individual Consul 2019-11-0 2019-10-1 2019-11-1 2020-01-2 2020-07-2 / Consultance et appui à la IDA / 59870 g capacities for priority fish Post Open 30,600.00 0.00 Canceled 2019-07-01 tant Selection 5 4 3 7 5 composante 2 eries management MG-MRHP-119241-CS-INDV / Assistance juridique pour a Component 2. Strengthenin Individual Consul 2019-08-1 2019-10-3 2019-11-2 2020-01-2 2020-07-2 ppuyer à l’homologation du IDA / 59870 g capacities for priority fish Post Open 10,000.00 0.00 Canceled 2019-08-01 tant Selection 9 0 9 8 6 Dinabe régissant la gestion l eries management ocale des pêcheries au nive au de la Baie d'Antongil MG-MRHP-148888-CS-INDV / Recrutement d’un consulta nt national pour assurer le r Component 2. Strengthenin enforcement de capacité de Individual Consul Pending Implem 2020-09-3 2020-10-0 2020-10-1 2020-10-3 IDA / 59870 g capacities for priority fish Post Limited 1,000.00 0.00 2020-09-24 s agents de l’administration tant Selection entation 0 7 7 1 eries management des pêches et des responsa bles des textes administratif s en technique d'approche e t d’animation rurale (2.1.1.1 .04) MG-MRHP-189680-CS-INDV / Recrutement d'un (e) secré Component 4. Project mana Individual Consul 2020-10-0 2020-10-1 2020-10-2 2023-10-2 IDA / 59870 Post Open 15,000.00 0.00 Canceled 2020-09-15 taire en passation des marc gement and coordination tant Selection 9 9 3 3 hés du projet SWIOFish2 MG-MRHP-160194-CS-INDV / Recrutement d'un assistan Component 4. Project mana Individual Consul 2020-02-2 2020-03-2 2020-04-0 2020-04-0 2023-04-0 IDA / 59870 Post Open 20,000.00 0.00 Canceled 2020-02-27 t en passation des marchés gement and coordination tant Selection 5 2 1 5 5 de l'UGP-SWIOFish2 MG-MRHP-197771-CS-INDV / Recrutement d'un Consulta Component 4. Project mana Individual Consul 2020-10-2 2020-11-1 2021-01-3 2020-11-2 2021-02-0 2020-12-0 2021-02-2 2023-09-0 IDA / 59870 Post Open 21,000.00 6,389.81 Signed 2020-10-13 nt individuel Assistant en Pa gement and coordination tant Selection 0 6 0 2 1 3 7 3 ssation des Marchés de l'UG P SWIOFish2 MG-MRHP-197821-CS-INDV / Recrutement d'un Consulta Component 4. Project mana Individual Consul 2020-10-1 2020-10-2 2021-05-0 2020-11-0 2021-05-0 2020-11-2 2021-05-1 2023-09-2 IDA / 59870 Post Limited 11,900.00 3,071.04 Signed 2020-10-13 nt individuel Secrétaire de la gement and coordination tant Selection 3 3 5 6 7 2 1 1 Passation des Marchés de l' UGP SWIOFish2 MG-MRHP-197817-CS-INDV / Recrutement d'un Consulta Component 4. Project mana Individual Consul 2020-11-1 2020-11-1 2021-03-0 2020-11-2 2021-03-0 2020-12-0 2021-03-0 2023-09-0 IDA / 59870 Post Open 21,000.00 11,362.85 Signed 2020-10-13 nt individuel Gestionnaire de gement and coordination tant Selection 6 6 2 2 4 5 9 5 contrats de l'UGP SWIOFish2 MG-MRHP-203594-CS-INDV Component 2. Strengthenin / Recrutement d'un consulta Individual Consul Under Implemen 2020-11-2 2021-01-0 2021-01-2 2021-02-0 2024-02-0 IDA / 59870 g capacities for priority fish Post Open 23,400.00 0.00 2020-11-20 nt individuel pour Responsa tant Selection tation 1 1 2 5 5 eries management ble Local de la composante 2 à Mananara Nord MG-MRHP-203595-CS-INDV Component 2. Strengthenin / Recrutement d'un consulta Individual Consul Under Implemen 2020-11-2 2021-01-0 2021-01-2 2021-02-0 2024-02-0 IDA / 59870 g capacities for priority fish Post Open 23,400.00 0.00 2020-11-20 nt individuel pour Responsa tant Selection tation 1 1 2 5 5 eries management ble Local de la composante 2 à Maroantsetra MG-MRHP-203596-CS-INDV Component 3. Strengthenin / Recrutement d'un consulta g capacities for engaging in Individual Consul 2020-11-2 2020-11-2 2021-01-1 2020-12-1 2021-01-1 2021-01-2 2021-01-2 2023-09-2 IDA / 59870 Post Limited 23,400.00 6,449.18 Signed 2020-11-20 nt individuel pour Responsa alternative fishing practices tant Selection 1 5 4 6 5 0 1 3 ble Local de la Composante and livelihoods activities 3 à Maintirano Page 12 MG-MRHP-203597-CS-INDV Component 3. Strengthenin / Recrutement des consultan g capacities for engaging in Individual Consul Under Implemen 2020-11-2 2021-01-0 2021-01-2 2021-02-1 2023-09-2 ts individuels pour Responsa IDA / 59870 Post Open 46,800.00 0.00 2020-11-20 alternative fishing practices tant Selection tation 1 1 2 2 3 ble Local de la Composante and livelihoods activities 3 à Maroantsetra et Nosy Be MG-MRHP-28348-CS-INDV/ Component 4. Project mana Individual Consul Pending Implem 2021-08-0 2021-08-2 2021-10-0 2022-04-0 MG-PM-44 / Réalisation du B IDA / 59870 Post Open 8,000.00 0.00 2021-06-03 gement and coordination tant Selection entation 7 8 9 7 ulletin trimestriel SWIOFish2 MG-MRHP-223821-CS-CDS / Recrutement d'un BE pour ET, PGES, C&S de travaux d e construction de la clôture Component 2. Strengthenin 2021-03-1 2021-03-2 2021-03-2 2021-05-3 2021-09-2 2021-07-2 de l’enceinte et mise en pla IDA / 59870 g capacities for priority fish Post Direct Selection Direct 40,000.00 15,938.40 Signed 2021-03-16 4 6 6 0 8 9 ce d’un point d’eau autono eries management me du bureau de la CirAEP Maroantsetra, construction du Hangar et bureau de la brigade CSP Analanjirofo MG-MRHP-223828-CS-INDV / Recrutement d’un troisièm Component 4. Project mana Individual Consul Under Implemen 2021-03-2 2021-04-2 2021-04-2 2021-04-2 2023-09-2 IDA / 59870 Post Open 15,600.00 0.00 2021-03-30 e Comptable pour l’Unité de gement and coordination tant Selection tation 6 0 2 6 9 Gestion du Projet SWIOFish2 MG-MRHP-227230-CS-INDV Component 4. Project mana Individual Consul 2021-04-0 2021-05-2 2021-09-1 2021-06-1 2021-11-1 2021-07-2 2021-11-2 2021-10-1 / Recrutement d'un SIGiste a IDA / 59870 Post Open 15,000.00 15,563.24 Signed 2021-04-07 gement and coordination tant Selection 9 6 0 6 9 1 7 9 u niveau de l'UGP SWIOFish 2 MG-MRHP-229415-CS-CDS / Recrutement d'un responsa Component 4. Project mana Under Implemen 2021-05-2 2021-04-2 2021-05-1 2023-09-2 IDA / 59870 Post Direct Selection 52,600.00 0.00 2021-04-22 ble en passation des marché gement and coordination tation 3 8 5 9 s du projet SWIOFish2 MG-MRHP-229418-CS-INDV / Recrutement d'un Consulta Component 4. Project mana Individual Consul 2021-10-2 2021-04-2 2022-03-0 2021-05-0 2022-03-1 2021-05-1 2022-03-2 2023-09-2 IDA / 59870 Post Limited 52,000.00 7,736.16 Signed 2021-04-22 nt individuel Gestionnaire de gement and coordination tant Selection 0 9 8 6 1 5 3 9 contrats de l'UGP SWIOFish2 (2021) MG-MRHP-161616-CS-CDS / Recrutement d'un BE pour l Component 2. Strengthenin 2020-03-2 2020-03-2 2020-05-2 2020-05-2 2021-10-2 e contrôle et surveillance de IDA / 59870 g capacities for priority fish Post Direct Selection Direct 41,500.00 0.00 Canceled 2020-03-12 0 2 6 6 3 s travaux des DRAEP à Andr eries management oy, Anosy et Atsimo Atsinan ana MG-MRHP-161621-CS-CDS / Recrutement d'un BE pour l Component 2. Strengthenin 2020-03-2 2020-03-2 2020-05-2 2020-05-2 2021-10-2 e contrôle et la surveillance IDA / 59870 g capacities for priority fish Post Direct Selection Direct 51,000.00 0.00 Canceled 2020-03-13 0 3 6 7 4 des travaux du DRAEP et CI eries management RAEP à Maintirano, des CIRA EP à Besalampy et à Masoar ivo MG-MRHP-231606-CS-INDV / Recrutement consultant in Component 2. Strengthenin Individual Consul 2021-05-0 2021-07-0 2021-06-2 2021-07-2 2021-10-0 2021-09-0 2021-11-0 2022-09-0 dividuel pour développemen IDA / D1720 g capacities for priority fish Post Open 15,000.00 47,116.80 Signed 2021-05-20 tant Selection 7 8 3 9 8 2 5 2 t de Base des Donnés du Ce eries management ntre de Surveillance Pêche ( CSP) MG-MRHP-236864-CS-INDV / Recrutement d’un Consulta nt individuel pour effectuer Component 2. Strengthenin Individual Consul Under Implemen 2021-08-0 2021-08-1 2021-09-0 2021-10-1 2021-12-1 la mise à jour du Plan d’Acti TF / A4588 g capacities for priority fish Post Open 100,000.00 0.00 2021-06-30 tant Selection tation 6 8 8 3 2 on National de lutte contre l eries management a pêche Illicite Non Déclarée et Non Réglementée (PAN IN N) de Madagascar MG-MRHP-119285-CS-CDS / Component 3. Strengthenin Contrôles et surveillances d g capacities for engaging in 2022-01-2 2022-05-1 2022-11-1 IDA / 59870 Post Direct Selection Direct 60,000.00 0.00 Canceled 2021-11-30 es infrastructures d'électrific alternative fishing practices 9 4 0 ation hors grille dans les co and livelihoods activities mmunautés pilotes MG-MRHP-119281-CS-CDS / Component 2. Strengthenin Contrôle et surveillance des 2021-06-2 2021-10-2 2022-04-2 IDA / 59870 g capacities for priority fish Post Direct Selection Direct 60,000.00 0.00 Canceled 2021-04-30 constructions de marchés co 9 7 5 eries management uverts aux produits halieutiq ues Component 3. Strengthenin MG-MRHP-252968-CS-INDV g capacities for engaging in Individual Consul 2021-10-1 2021-11-3 2021-10-2 2021-12-2 2021-11-0 2022-01-2 2021-11-1 2023-01-2 / Recrutement d’un Assistan IDA / 59870 Post Open 15,000.00 6,796.71 Signed 2021-10-11 alternative fishing practices tant Selection 2 0 2 1 3 5 7 5 t Technique Foncier and livelihoods activities MG-MRHP-256410-CS-INDV Component 4. Project mana Individual Consul 2021-12-2 2021-11-0 2022-02-2 2021-11-1 2022-03-0 2021-11-2 2022-03-0 2023-09-2 / Recrutement d'un comptab IDA / 59870 Post Open 24,000.00 8,042.13 Signed 2021-10-18 gement and coordination tant Selection 0 8 5 5 1 4 8 9 le 2021 (Remplacement co mptable 2) MG-MRHP-285250-CS-CDS / Component 2. Strengthenin Analyse des problématiques Under Implemen 2022-04-1 2022-04-1 2022-06-0 2022-06-1 2022-12-1 IDA / 59870 g capacities for priority fish Post Direct Selection Direct 20,000.00 0.00 2022-04-05 liées à l’utilisation des senn tation 5 5 2 9 6 eries management es de plage dans la baie d’A ntongil MG-MRHP-289654-CS-INDV / Responsable Local de la Co Component 3. Strengthenin mposante 3 (RLC3) « Appui g capacities for engaging in Individual Consul Pending Implem 2022-05-3 2022-06-2 2022-07-1 2025-02-1 à l’adhésion des populations IDA / 59870 Post Open 22,000.00 0.00 2022-04-18 alternative fishing practices tant Selection entation 0 0 1 8 cibles à la gestion durable d and livelihoods activities es pêcheries cibles/Promotio n des activités alternatives » dans les Districts de Maro antsetra MG-MRHP-252785-CS-INDV / Recrutement d'un Respons Component 4. Project mana Individual Consul 2021-09-1 2021-10-1 2021-10-2 2021-11-0 2023-09-3 IDA / 59870 Post Open 32,400.00 0.00 Canceled 2021-09-23 able Administratif et Financi gement and coordination tant Selection 5 3 3 6 0 er pour le Projet SWIOFish2 ( 2021) MG-MRHP-119282-CS-CDS / Contrôle et surveillance des constructions de hangars av Component 3. Strengthenin ec des materiaux locaux po g capacities for engaging in 2022-01-1 2022-05-1 2022-11-0 ur entretenir les moteurs, le IDA / 59870 Post Direct Selection Direct 48,000.00 0.00 Canceled 2021-11-12 alternative fishing practices 1 1 7 s embarcations et des engin and livelihoods activities s de pêche autorisés et d'un e base de réunion, sensibilis ation et de structuration des utilisateurs petites infrastru MG-MRHP-119283-CS-CDS / Component 3. Strengthenin Contrôles et surveillances d g capacities for engaging in 2022-01-1 2022-04-2 2022-10-2 IDA / 59870 Post Direct Selection Direct 120,000.00 0.00 Canceled 2021-11-12 es constructions d'infrastruc alternative fishing practices 1 6 3 tures communautaires /com and livelihoods activities munales MG-MRHP-119280-CS-CDS / Component 3. Strengthenin Contrôle et surveillance des g capacities for engaging in 2022-01-2 2022-04-2 2022-10-2 IDA / 59870 Post Direct Selection Direct 70,000.00 0.00 Canceled 2021-11-12 constructions de petites déb alternative fishing practices 6 6 3 arcadères type ponton and livelihoods activities MG-MRHP-28325-CS-INDV// Component 3. Strengthenin MG-PM-29 / Élaboration de p g capacities for engaging in Individual Consul 2022-11-1 2022-12-1 2023-02-1 2023-08-1 IDA / 59870 Post Open 30,000.00 0.00 Canceled 2022-09-02 lan de formation des cadres alternative fishing practices tant Selection 7 7 5 4 et élus au niveau local and livelihoods activities MG-MRHP-189660-CS-INDV / Recrutement d'un consulta Component 2. Strengthenin nt individuel pour le renforc Individual Consul Pending Implem 2022-08-0 2022-08-2 2022-09-1 2022-09-2 IDA / 59870 g capacities for priority fish Post Open 4,000.00 0.00 2022-07-01 ement de capacités de l'équ tant Selection entation 6 7 0 2 eries management ipe du service personnel du secteur pêche et aquacultur e en gestion des ressources humaines MG-MRHP-190572-CS-INDV / Recrutement d'un consulta nt individuel pour le renforc Component 2. Strengthenin ement de capacités des age Individual Consul Pending Implem 2022-10-0 2022-10-2 2022-11-1 2022-12-0 IDA / 59870 g capacities for priority fish Post Open 4,000.00 0.00 2022-09-01 nts de l'administration en dé tant Selection entation 7 8 1 8 eries management veloppement d'application web sous HTML, CSS et Java Script et pratique de dévelo ppement en WEBDEV MG-MRHP-292939-CS-INDV / Assistant Technique 2 pour Component 4. Project mana Individual Consul Under Implemen 2022-06-1 2022-06-0 2022-06-1 2022-06-1 2025-06-1 les constructions et réhabilit IDA / 59870 Post Open 25,000.00 0.00 2022-05-09 gement and coordination tant Selection tation 0 2 2 6 5 ations d'infrastructures de p êche, communautaires et ad ministratives MG-MRHP-280897-CS-CDS / Mise à jour des études techn iques relatives à la construct ion du bureau administratif Component 2. Strengthenin Under Implemen 2022-06-0 2022-05-1 2022-06-0 2022-07-2 2023-01-1 de l’UGP SWIOFish2 Nanisan IDA / 59870 g capacities for priority fish Post Direct Selection Direct 26,000.00 0.00 2022-05-06 tation 2 6 8 0 6 a et Contrôle et surveillance eries management de la construction du nouve au bureau logement et de la réhabilitation du bureau log ement existant Farafangana MG-MRHP-297266-CS-INDV / Recrutement d'un consulta Component 2. Strengthenin nt pour la création d'un site Individual Consul 2022-07-1 2022-08-0 2022-09-1 2022-08-2 2022-10-0 2022-09-0 2022-12-0 IDA / 59870 g capacities for priority fish Post Open 15,000.00 0.00 Signed 2022-06-10 web de design et de base de tant Selection 3 5 2 6 7 9 8 eries management données pour la gestion des autorisations et des licences des pêches MG-MRHP-298184-CS-INDV Component 4. Project mana Individual Consul Under Implemen 2022-06-2 2022-08-0 2022-08-2 2022-09-2 2023-09-2 / Recrutement d'un comptab IDA / 59870 Post Open 24,000.00 0.00 2022-06-16 gement and coordination tant Selection tation 4 4 5 9 9 le 3 remplaçant MG-MRHP-298211-CS-CDS / Recrutement d’une organisa tion non-gouvernementale p Component 3. Strengthenin our la promotion des groupe g capacities for engaging in Under Implemen 2022-06-1 2022-06-2 2022-07-1 2023-07-1 s d’épargne communautaire IDA / 59870 Post Direct Selection Direct 90,000.00 0.00 2022-06-17 alternative fishing practices tation 0 7 8 8 (GEC) au niveau des district and livelihoods activities s de Farafangana et Vangain drano - regions Atsimo Atsin anana et des districts d’Amb ovombe, Tsihombe et Beloh a - région And MG-MRHP-296823-CS-INDV / Recrutement d'un Assista Component 4. Project mana Individual Consul 2022-08-1 2023-02-1 IDA / 59870 Post Open 25,000.00 0.00 Canceled nt Technique national au Mi gement and coordination tant Selection 7 3 nistère de la Pêche et de l'E conomie Bleue (MPEB) MG-MRHP-296823-CS-INDV_ 2 / Recrutement d'un Assist Component 4. Project mana Individual Consul 2022-06-2 2022-08-1 2022-07-1 2022-09-0 2022-07-1 2022-10-1 2022-08-0 2023-04-1 IDA / 59870 Post Open 25,000.00 7,215.66 Signed 2022-06-30 ant Technique national au M gement and coordination tant Selection 9 8 3 8 9 3 2 1 inistère de la Pêche et de l'E conomie Bleue (MPEB) MG-MRHP-303933-CS-CDS / Recrutement d'un formateur Component 3. Strengthenin relatif au renforcement de c g capacities for engaging in Direct - Internatio Under Implemen 2022-07-2 2022-08-0 2022-10-0 2023-08-0 IDA / 59870 Post Direct Selection 500,000.00 0.00 2022-07-22 apacité sur les techniques d alternative fishing practices nal tation 1 1 5 1 e fumage des produits halie and livelihoods activities utiques et construction de fu moirs FTT MG-MRHP-231604-CS-INDV / Recrutement d’un Consulta Component 2. Strengthenin nt Individuel pour effectuer Individual Consul 2022-07-2 2022-09-0 2022-10-1 2022-09-3 2022-11-1 2022-11-0 2023-09-2 TF / A4588 g capacities for priority fish Post Open - National 32,500.00 0.00 Signed 2022-07-22 un Audit des activités de Sur tant Selection 2 9 8 0 0 4 9 eries management veillance, réalisées par le Ce ntre de Surveillance des Pêc hes (CSP) de Madagascar. Page 13 MG-MRHP-304398-CS-CDS / Recrutement d'un consultan Component 2. Strengthenin Under Implemen 2022-07-2 2022-08-0 2022-07-2 2022-10-0 2023-09-2 t pour la modification tablea TF / A4588 g capacities for priority fish Post Direct Selection Direct - National 20,000.00 0.00 2022-07-22 tation 1 1 5 5 9 u de bord et création de mo eries management dules dans le SIP et OPENAR TFISH MG-MRHP-308538-CS-CDS / Renouvellement des contrat Component 3. Strengthenin s de prestation des organisa g capacities for engaging in 2022-09-2 2022-08-2 2022-09-2 2022-11-0 2023-05-0 tions non-gouvernementales IDA / 59870 Post Direct Selection Direct - National 180,000.00 0.00 Signed 2022-08-19 alternative fishing practices 7 9 9 2 1 pour la promotion des group and livelihoods activities es d’épargne communautair e (GEC) au niveau des ZUP MELAKY et BAIE d’ANTONGIL MG-MRHP-308722-CS-CDS / Renouvellement des contrat Component 3. Strengthenin s de prestation des organisa g capacities for engaging in Under Implemen 2022-09-2 2022-08-2 2022-09-2 2022-10-3 2023-04-2 IDA / 59870 Post Direct Selection Direct - National 90,000.00 0.00 2022-08-17 tions non-gouvernementales alternative fishing practices tation 7 7 9 1 9 pour la promotion des group and livelihoods activities es d’épargne communautair e (GEC) au niveau des ZUP BATAN MG-MRHP-320114-CS-INDV Component 3. Strengthenin / Recrutement d'un Assistan g capacities for engaging in Individual Consul 2022-10-2 2022-11-0 2023-01-1 2022-11-1 2023-01-1 2022-12-1 2023-08-1 IDA / 59870 Post Open - National 20,000.00 0.00 Signed 2022-10-14 t spécialiste sauvegarde env alternative fishing practices tant Selection 4 9 1 0 3 4 6 ironnemental et social and livelihoods activities MG-MRHP-334021-CS-INDV Component 4. Project mana Individual Consul Under Implemen 2023-01-3 2023-02-1 2023-02-2 2023-03-1 2023-09-2 IDA / 59870 Post Open - National 16,000.00 0.00 2023-01-10 / Recrutement d'un 4ème co gement and coordination tant Selection tation 0 2 6 2 9 mptable MG-MRHP-336492-CS-INDV Component 4. Project mana Individual Consul Under Implemen 2023-01-3 2023-02-2 2023-03-1 2023-04-0 2023-09-2 / Recrutement d'un Chef Co IDA / 59870 Post Open - National 8,000.00 0.00 2023-01-30 gement and coordination tant Selection tation 0 5 1 1 9 mptable (CC) au sein de l'U GP 2023 MG-MRHP-336490-CS-CDS / Recrutement d'un Responsa Component 4. Project mana 2023-02-1 2023-02-2 2023-02-2 2023-03-0 2023-10-1 IDA / 59870 Post Direct Selection Direct - National 15,000.00 0.00 Signed 2023-02-15 ble Administratif et Financie gement and coordination 7 0 4 3 5 r au sein de l'UGP 2023 MG-MRHP-299084-CS-INDV / Recrutement d'un Assista Component 4. Project mana Individual Consul 2022-06-2 2022-08-1 2022-09-0 2022-10-1 2023-04-1 nt Technique international IDA / 59870 Post Open 35,000.00 0.00 Canceled 2022-06-30 gement and coordination tant Selection 9 8 8 3 1 au Ministère de la Pêche et de l'Economie Bleue (MPEB) MG-MRHP-5189-CS-INDV / E Component 2. Strengthenin tude sur l'adaptation des mi Individual Consul 2017-04-0 2017-04-2 2017-05-3 2017-11-2 IDA / Q9790 g capacities for priority fish Post Open 15,000.00 0.00 Canceled 2017-02-15 ssions et attributions du MR tant Selection 5 6 1 7 eries management HP par rapport aux défis du développement rural Page 14 LESOTHO COMPETITIVENESS AND FINANCIAL INCLUSION (CAFI) PROJECT Project Procurement Strategy Development (PPSD) (Short form of PPSD) Implementing Agency: Ministry of Trade & Industry MARCH 2022 1|Page Common Abbreviations and Defined Terms This Section explains the common terms and abbreviations used in this Document. Defined terms are written using capital letters. Abbreviation / Full terminology / definition term ASYCUDA A computerised customs management system which covers most foreign Trade procedures Bank IBRD and/or IDA (whether acting on its account or in its capacity as administrator of trust funds provided by other donors). Borrower A borrower or recipient of Investment Project Financing (IPF) and any other entity involved in the implementation of a project financed by IPF, in this case, the GoL. Complaint A procurement-related complaint as described in Paragraphs 3.26 to 3.31 and Annex III, Procurement- related Complaints of the Procurement Regulations. ESRI Company that provides GIS systems in Africa and around the globe (Environmental Systems Research Institute) EXPERIAN Credit Scoring system and Credit Infrastructure system Goods A category of procurement that includes commodities, raw material, machinery, equipment, vehicles, Plant, and related services such as transportation, insurance, installation, commissioning, training, and initial maintenance, G2B Government to Business Initial Selection The shortlisting process is used prior to inviting (IS) requests for Proposals in the procurement of Goods, Works, or Non-consulting Services. Investment The Bank’s financing of investment Projects that aim Project to promote poverty reduction and sustainable Financing (IPF) development. IPF supports Projects with defined development objectives, activities, and results, and disburses the proceeds of Bank financing against specific eligible expenditures. LERIMA Lesotho Electronic Registry Interest of Moveable Assets Non--consulting Services, which are not Consulting Services. Non- Services: consulting Services are normally bid and contracted on the basis of performance of measurable outputs, and for which performance standards can be clearly identified and consistently applied. Examples include drilling, aerial photography, satellite imagery, mapping, and similar operations. 2|Page Abbreviation / Full terminology / definition term SWOT (Strengths, Weaknesses, Opportunity and Threats) is an analysis tool for supporting assessment of each of these factors. PARADIGM A company that deals with Moveable Asset Registry Prequalification The shortlisting process can be, used prior to inviting requests for Bids in the procurement of Goods, Works or Non-Consulting Services. Procurement Procurement approach is the overall design of “fit Approach for purpose” procurement to award contracts that deliver the Project Development Objectives and Value for Money. This includes Procurement Arrangements, procurement risk management, contract strategy, market engagement, requirements drafting and contract management (where appropriate). Procurement Procurement arrangements are the combination of Arrangements Selection Methods and Market Approaches. Procurement The Borrower’s Procurement Plan for IPF Projects, as Plan referred to in Paragraphs 4.4 and 4.5 of the Procurement Regulations, and incorporated by reference in the Legal Agreement. Procurement The process that starts with the identification of a Process need and continues through planning, preparation of specifications/ requirements, budget considerations, selection, contract award, and contract management. It ends on the last day of the warranty period. Procurement The “World Bank Procurement Regulations for IPF Regulations Borrowers”. Project A Project-level strategy document, prepared by the Procurement Borrower, that describes how procurement in IPF Strategy for operations will support the development objectives Development of the Project and deliver Value for Money (VFM). (PPSD) UNCTAD United Nations Conference on Trade and Development 3|Page Table of Contents CHAPTER 1 ...........................................................................................................5 1.0 PROJECT OVERVIEW ...............................................................................5 1.1 Project Description ................................................................................6 1.2 Project Development Objectives .........................................................8 1.3 Results Indicators ..................................................................................8 1.4 High Level Statement of Requirement ...............................................9 CHAPTER 2 ...........................................................................................................9 2.0 OVERVIEW OF COUNTRY, BORROWER AND MARKET PLACE .9 2.1 Operational Context ..............................................................................9 2.2 Assessment of Borrower Capability and Project Implementation Unit (PIU) ........................................................................................................15 2.3 Project Procurement Structure .........................................................19 2.4 Market Analysis ....................................................................................20 CHAPTER 3 .........................................................................................................23 3.0 PROJECT PROCUREMENT RISK ANALYSIS .........................................23 CHAPTER 4 .........................................................................................................29 4.0 STAKEHOLDER ANALYSIS ...................................................................29 CHAPTER 5 .........................................................................................................31 5.0 PROCUREMENT OBJECTIVES ...............................................................31 CHAPTER 6 .........................................................................................................32 6.0 PROCUREMENT APPROACH OPTIONS AND RECOMMENDATIONS .32 CHAPTER 7 .........................................................................................................39 7.0 SUMMARY OF PPSD TO SUPPORT THE PREPARATION OF THE PAD BY THE BANK ..................................................................................................39 CHAPTER 8 .........................................................................................................40 8.0 PROCUREMENT PLAN FOR THE FIRST 18 MONTHS .........................40 4|Page CHAPTER 1 1.0 PROJECT OVERVIEW Competitiveness and Financial Inclusion (CAFI), aims to provide more opportunities for women in the private sector through the following interventions: (i) focusing on women owned MSMEs for rapid disbursements during shocks. Women-owned MSMEs are particularly vulnerable to climatic shocks and require targeted support. Research in Lesotho has shown that shocks disproportionately increase the work burden of women, who, in addition to being more likely to be self-employed or employed in the informal sector, are also tasked with walking long distances to collect water for their families in droughts, growing/providing food, covering educational costs/needs, and generally sustaining the family. In rural areas, men are more likely to leave their villages in search of alternate income sources, thereby giving women the full burden of family caretaking. Thus, when climatic shocks occur, a loss of income for the self-employed women can have large and catastrophic effects on families and communities, emphasizing the need for rapid support to women-owned MSMEs; (ii) focusing on women-owned start-ups and women-owned MSMEs to assist them in launching businesses, adopting new digital technologies, and improving managerial practices. This supports gender transformation within the MSME space. The proposed project has adopted a selective approach by targeting interventions that link closely to business expansion and resilience and job creation, specifically those related to supporting entrepreneurship, MSMEs, and high potential value chains. The proposed interventions are targeted at increasing financial inclusion and resilience as well as strengthening the support for MSMEs and entrepreneurship along the high potential value chains. Under increasing financial inclusion and resilience, the proposed interventions focus on strengthening the delivery of G2B services, increasing access to finance for MSMEs with a focus on ensuring the 5|Page inclusion of women- owned MSMEs and enhancing the resilience of the business sector from climate and other shocks. Support for MSMEs and entrepreneurship is focused on enhancing the scope and quality of business support services, access to early-stage finance and improving the overall competitiveness and climate resilience of horticulture and export manufacturing value chains. Based on the experience of the PSCED and PSCEDII projects, institutional, legal, and regulatory reforms pertaining to access to finance, investment policy and business environment reforms, while critical for overall competitiveness, have proven challenging and unnecessarily prolonged. These reforms will be supported through a parallel technical advisory support program. The project interventions proposed therefore target market and coordination failures through direct support to entrepreneurs and firms while leveraging private sector service delivery capacity to augment limited public sector capacity. Although the tourism value chain has not been explicitly targeted, entrepreneurs and existing MSMEs in the sector will be able to fully benefit from the project interventions. Country: Kingdom of Lesotho Full Project Competitiveness and Financial Inclusion Project Name: Total Finance 55,000,000. ($): Project ID P175783 Number: 1.1 Project Description The purpose of this project is to increase access to business support services and financial products targeted at MSMEs and entrepreneurs, especially women and youth. The project has three components that will support the Government’s efforts to expand the private sector in Lesotho. 6|Page • Component 1 will enhance financial inclusion by strengthening the delivery of efficient and reliable government-to-business (G2B) digital services to facilitate the establishment and operation of new businesses and reduce the time and cost of regulatory compliance which in turn will enhance access to finance and the competitiveness of MSMEs. It will also provide support for firms to be more resilient to shocks from climate, pandemics, and other natural disasters. The component will include activities that support (i) optimizing the outcomes of investments in G2B digital systems and processes made under the PSCEDII project, to strengthen inter-operability, efficiency, and impactful service delivery for businesses, particularly those receiving support under Component 2, (ii) improving financial access through upgrading the security and reliability of credit infrastructure and expanding access to digital financial services, and (iii) instruments to expand financial resilience for businesses to cope with disasters and other shocks to the economy. These instruments will be particularly beneficial to the private sector. The component will finance technical assistance, goods, training and capacity building programs, and recurrent expenditures, including operating costs. • Component 2 aims to strengthen the nascent entrepreneurial ecosystem and access to early-stage finance for startups and youth owned businesses, support the digitization of MSMEs, and facilitate private investment in high-potential value-chains including encourage upgrading of skills and adoption of sustainable production practices by businesses to enhance productivity and green growth. The component will include activities that support (i) establishing an Entrepreneurship Hub and Seed Financing Facility to increase the quality and scope of integrated startup business support services and increase access to early-stage financing, (ii) scaling the current Lesotho Enterprise Assistance Program (LEAP) focusing on supporting MSMEs to adopt digital technologies that allow them to transact in the digital economy and upgrade their capabilities, and (iii) facilitating investment into productive value chains that are linked to 7|Page local MSMEs. The component will finance technical assistance, goods, training, recurring expenditures including operating costs, grants, and investments in a “seed financing facility.” • Component 3 will provide support for the management and implementation of project-associated activities. Activities to be financed include salaries of project management unit (PMU) staff/consultants in areas of project management, project coordination, fiduciary specialists (e.g., procurement, financial management), monitoring and evaluation (M&E) specialist, a dedicated environment, and social safeguards (E&S) specialist, project communication, and citizen engagement. This component will also cover modest office equipment and independent audits and learning/training for the PMU and beneficiary agencies, through the official closing date of the project. It is expected that all consultant terms of reference (TORs) will clearly stipulate knowledge transfer and hands on training to ministry staff. Special attention will be devoted to promoting equal participation of women in all decision- making bodies under the project and contributing to tackling barriers in recruitment, retention, and promotion. 1.2 Project Development Objectives The project development objective (PDO) is to increase access to business support services and financial products targeted at MSMEs and entrepreneurs, especially women and youth. The proposed project supports results in two areas: (i) Improving financial inclusion and resilience through improvements in government to business services, government supported financial products that increase MSME creation, growth, and resilience to climatic and other shocks; and 8|Page (ii) Direct support for entrepreneurship and MSMEs to increase start-up creation and growth and the capabilities of MSMEs to grow and participate in the value chains of high potential export industries. 1.3 Results Indicators The project’s achievement of the PDO will be measured via the following key results indicators: 1. Number of enterprises benefitting from private sector initiatives of the program (Of which are women-owned, of which are youth-owned); 2. Value of financing (seed funding, grants, partial credit guarantee, MSME resilience funds) accessed by enterprises through the program (Of which are women-owned); 3. Percentage of enterprises supported by the program with increased revenue (Of which are women-owned, of which are youth-owned); and 4. Percentage of enterprises supported by the program with increased employment (Of which are women-owned, of which are youth-owned. 9|Page There are also indicative intermediate indicators which will be used to measure the performance of the project, and these are: • Firms benefiting from private sector initiatives (CRI, Number) (Of which are women-owned, and of which are youth-owned). • Percent change in the number of enterprises accessing supported G2B systems; • Number of key G2B systems upgraded with the support from the program; • Percentage of women-owned enterprises recorded as being creditworthy in the credit bureau; • Number of additional enterprises covered by the partial credit guarantee (PCG) scheme; • Number of MSMEs registered for coverage in MSME Resilience Fund database; • Number of startups and innovative SMEs supported through entrepreneurship hub support programs; • Number of startups and innovative SMEs supported through entrepreneurship hub support programs of which are women-owned; • Number of enterprises accessing early-stage finance; • Number of entrepreneurship hub and LEAP program supported enterprises that adopted new digital technologies; • Number of LEAP fund supported enterprises with 25% or greater increase in revenues one year after grant support; and • Number of supported enterprises in targeted value chains with increased value of exports. 1.4 High Level Statement of Requirement The implementation of the Competitiveness and Financial Inclusion Project requires procurement of consulting and non-consulting services, goods, and works under the project components. Consulting services will be needed to provide capacity building and technical advisory services as well as 10 | P a g e management assistance to both PMU and beneficiary agencies. Procurement of consulting services will be needed to enhance G2B digital services to more effectively serve MSMEs, access to financial services, strengthening the resilience of MSMEs to Climatic Disasters and shock scaling-up support for Entrepreneurship and MSME’s and expanding SME participation in high potential value chains. Procurement of works will be needed to support the refurbishment of Mahobong Incubation Hub as well as partitioning of PMU office. Procurement of goods will be needed to provide ICT equipment to support implementation of Component 1 system upgrades including the business registration and licensing system at OBFC, the LRA customs system, the MCC construction permitting system to mention a few. Table 1 below provides a summary of the estimated costs of procurement package per component, works, good and consulting services included. 11 | P a g e TABLE 1: Proposed Procurement Contract Summary PROCURMENT PLAN FOR SELECTION OF CONSULTANCY SERVICES JUSTIFICATIONS FOR THE PROPOSED SELECTION DESCRIPTION ESTIMAT PROPOSED METHOD COMPON OF THE ED COST SELECTION ENT ASSIGNMENT ($) METHOD COMPONENT 1: ENHANCING G2B DIGITAL SERVICES AND STRENGTHENING PRIVATE SECTOR RESILIENCE Sub-Component 1.1 - Enhancing Government to Business Digital Services UNCTAD is uniquely and exceptionally qualified to upgrade business registration and licensing system at OBFC as it was originally developed by them. It is also the case that the tasks represent a natural continuation of previous work carried out by a consultant, where continuity in the technical approach, experience Upgrade of the acquired, and continued professional liability of the same business Consultant may make continuation with the initial registration and Consultant preferable to a new competition. The licensing system 880 Direct Selection performance of UNCTAD has been satisfactory in the 1.1.1 at OBFC 000.00 (UNCTAD) previous assignment(s); UNCTAD is uniquely and exceptionally qualified to upgrade LRA customs system as it was originally designed and developed by them. Upgrade of the It is also the case that the tasks represent a natural LRA customs continuation of previous work carried out by a consultant, system, based on Direct Selection where continuity in the technical approach, experience UNCTAD`s (UNCTAD)ASYC acquired, and continued professional liability of the same ASYCUDA World 1 000 UDA World Consultant may make continuation with the initial 1.1.2 System 000.00 System Consultant preferable to a new competition. The 1|Page PROCURMENT PLAN FOR SELECTION OF CONSULTANCY SERVICES JUSTIFICATIONS FOR THE PROPOSED SELECTION DESCRIPTION ESTIMAT PROPOSED METHOD COMPON OF THE ED COST SELECTION ENT ASSIGNMENT ($) METHOD performance of UNCTAD has been satisfactory in the previous assignment(s); Only ESRI is qualified and has experience of exceptional worth for the upgrade of the LAA land registry system as they designed and developed the system. It is also the case that the system is proprietary where continuity in the technical approach, experience acquired, and continued professional liability of the same Consultant may make direct selection of the system developer Upgrade of the Consultant preferable to a new competition. The LAA land registry 1 000 Direct Selection performance of ESRI has been satisfactory in the previous 1.1.3 system 000.00 (ESRI) assignment(s); Design and Appropriate method for medium and high complexity development of assignment. Competitive approach is required to achieve the G2B quality and value for money interoperability 1 600 QCBS - 1.1.4 framework 000.00 International Design and The method is appropriate as this is a large firm consultant development of a assignment with cost above $ 300 000.00. Competitive G2B payment 1 500 QCBS - approach is required to achieve quality and value for money 1.1.5 gateway 000.00 International 5 980 000.00 Sub-Component 1.2 - Improving Access to Financial Services Upgrade of the Only EXPERIAN is qualified and has experience of credit exceptional worth for the upgrade of the credit infrastructure infrastructure system as they designed and developed the system. The system that 200 Direct Selection task represents a natural continuation of previous work 1.2.1 facilitates access 000.00 (EXPERIAN) carried out by a consultant, where continuity in the technical 2|Page PROCURMENT PLAN FOR SELECTION OF CONSULTANCY SERVICES JUSTIFICATIONS FOR THE PROPOSED SELECTION DESCRIPTION ESTIMAT PROPOSED METHOD COMPON OF THE ED COST SELECTION ENT ASSIGNMENT ($) METHOD to business approach, experience acquired, and continued professional financing liability of the same consultant may make continuation with the initial consultant preferable to a new competition The performance of EXPERIAN has been satisfactory in the previous assignments Only EXPERIAN is qualified and has experience of exceptional worth for the development of the credit scoring system as they designed the system. The task represents a natural continuation of previous work carried out by a consultant, where continuity in the technical approach, Development of experience acquired, and continued professional liability of credit scoring the same consultant may make continuation with the initial system to consultant preferable to a new competition The performance enhance the of EXPERIAN has been satisfactory in the previous utility of credit 600 Direct Selection assignments 1.2.2 reporting 000.00 (EXPERIAN) Only Paradigm is qualified and has experience of exceptional worth for the upgrade of the LERIMA movable asset registry as they designed and developed the system. The task represents a natural continuation of previous work carried out by a consultant, where continuity in the technical approach, experience acquired, and continued professional liability of the same consultant may make continuation with the initial consultant preferable to a new competition. The Upgrade of performance of LERIMA has been satisfactory in the previous LERIMA movable 200 Direct Selection assignments 1.2.3 asset registry 000.00 (Paradigm) Development of Appropriate method for medium and high complexity New financial 500 QCBS - assignment. Competitive approach is required to achieve 1.2.4 products to 000.00 International quality and value for money 3|Page PROCURMENT PLAN FOR SELECTION OF CONSULTANCY SERVICES JUSTIFICATIONS FOR THE PROPOSED SELECTION DESCRIPTION ESTIMAT PROPOSED METHOD COMPON OF THE ED COST SELECTION ENT ASSIGNMENT ($) METHOD promote market innovation Capacity building This is a small assignment of which preparing and evaluating of financial competitive proposals is not justified institutions and MSME`s to utilise asset-based 1.2.5 lending 50 000.00 CQS- National TA to Postbank This is a small assignment of which preparing and evaluating for development competitive proposals is not justified of business case for agricultural value chain finance, including market assessment and financing 150 CQS- 1.2.6 methodology 000.00 International Design and This is a small assignment of which preparing and evaluating implementation competitive proposals is not justified of a management information system (MIS) to support value- 200 CQS- 1.2.7 chain financing 000.00 International Review and This is a low value assignment with less than six months improve governance, institutional and 1.2.8 operational 50 000.00 IC- National 4|Page PROCURMENT PLAN FOR SELECTION OF CONSULTANCY SERVICES JUSTIFICATIONS FOR THE PROPOSED SELECTION DESCRIPTION ESTIMAT PROPOSED METHOD COMPON OF THE ED COST SELECTION ENT ASSIGNMENT ($) METHOD features of the L- PCG Develop a This is a small assignment of which preparing and evaluating business case competitive proposals is not justified and financial model for portfolio 150 CQS- 1.2.9 guarantees 000.00 International Design and Appropriate method for large firm consultant assignment implement the over US$ 300 000.00. Competitive approach is required to portfolio achieve quality and value for money guarantee scheme including development of supporting documentation 2,000 QCBS- 1.2.10 and systems 000.00 International 100 This is a small assignment of which preparing and evaluating 1.2.11 Capacity building 000.00 CQS-National competitive proposals is not justified 2 800 000.00 Sub-Component 1.3 – Strengthening the Resilience of MSMEs to Climatic Shocks TA on disaster Appropriate method for such high value and complex risk financing assignment. Competitive approach is required to achieve including drafting quality and value for money of National Disaster Risk Finance Policy for 750 QCBS- 1.3.1 MoF 000.00 International 5|Page PROCURMENT PLAN FOR SELECTION OF CONSULTANCY SERVICES JUSTIFICATIONS FOR THE PROPOSED SELECTION DESCRIPTION ESTIMAT PROPOSED METHOD COMPON OF THE ED COST SELECTION ENT ASSIGNMENT ($) METHOD Design and Appropriate method for less complex assignments. This is a development a small assignment of which preparing and evaluating database for competitive proposals is not justified informal MSMEs and integrate the database into the existing business 300 QCBS- 1.3.2 registry 000.00 International TA on design and Appropriate method for less complex assignments. This is a procurement of small assignment of which preparing and evaluating sovereign competitive proposals is not justified insurance backstop and co- financing of insurance 150 CQS- 1.3.3 premiums 000.00 International Draft regulations This is a low value assignment with less than six months to govern the duration operational activities of the existing MoF Contingency 1.3.4 Fund 75 000.00 IC - National 1,275, 000.00 COMPONENT 2: SCALING SUPPORT FOR ENTREPRENEURSHIP AND MSMES Sub-Component 2.1 - Establishing an Entrepreneurship Hub and Seed Financing Facility 6|Page PROCURMENT PLAN FOR SELECTION OF CONSULTANCY SERVICES JUSTIFICATIONS FOR THE PROPOSED SELECTION DESCRIPTION ESTIMAT PROPOSED METHOD COMPON OF THE ED COST SELECTION ENT ASSIGNMENT ($) METHOD Procure a private Appropriate method for high value and complex assignment. operator to Competitive approach is required to achieve quality and support the value for money establishment of a sustainable Entrepreneurship Hub within the Tourism Information Craft 500 QCBS- 2.1.1 Centre 000.00 International Design and Appropriate method for less complex assignments. development of Preparing and evaluating competitive proposals is not an incubation 150 CQS- justified 2.1.2 support program 000.00 International Facilitate the This is a low value assignment with less than six months integration of the duration Lesotho Start-up Community within a wider regional Entrepreneurship 2.1.3 ecosystem 50 000.00 IC- National Procure a private Appropriate method for less complex assignments. operator to Preparing and evaluating competitive proposals is not establish and justified manage a seed financing facility and an associated acceleration 250 CQS- 2.1.4 program 000.00 International 7|Page PROCURMENT PLAN FOR SELECTION OF CONSULTANCY SERVICES JUSTIFICATIONS FOR THE PROPOSED SELECTION DESCRIPTION ESTIMAT PROPOSED METHOD COMPON OF THE ED COST SELECTION ENT ASSIGNMENT ($) METHOD 950 000.00 Sub-Component 2.2 - Scaling Up of the Lesotho Enterprise Assistance Program Procure private Appropriate method for less complex assignments. sector service Preparing and evaluating competitive proposals is not providers to justified augment the delivery capacity 300 2.2.1 of LEAP PMU 000.00 QCBS-National Sub-Component 2.3 - Expanding SME Participation in High Potential Value Chains TA to set up a QCBS Appropriate method for high value and complex assignment. Horticulture 350 International Competitive approach is required to achieve quality and 2.3.1 Incubation Hub 000.00 Selection value for money PROCURMENT PLAN TEMPLATE FOR SELECTION OF GOODS JUSTIFICATION S FOR THE ESTIMATED PROPOSED COMPON COST ($) PROCUREMENT SELECTION ENT DESCRIPTION OF THE ASSIGNMENT METHOD METHOD COMPONENT 1: ENHANCING G2B DIGITAL SERVICES AND STRENGTHENING PRIVATE SECTOR RESILIENCE Sub-Component 1.1 - Enhancing Government to Business Digital Services 8|Page PROCURMENT PLAN TEMPLATE FOR SELECTION OF GOODS JUSTIFICATION S FOR THE ESTIMATED PROPOSED COMPON COST ($) PROCUREMENT SELECTION ENT DESCRIPTION OF THE ASSIGNMENT METHOD METHOD Efficient method for procuring limited quantities of readily ICT equipment for upgrade of the business Request For available off-the- 1.1.1 registration and licensing system at OBFC 70 000.00 Quotations shelf goods Medium value and local availability. The user will be able to specify detailed requirements to which bidders may respond in offering bids. ICT equipment for Upgrade of the LRA customs Value for money system, based on UNCTAD`s ASYCUDA World National will also be 1.1.2 System 150 000.00 Competitive Bidding achieved. Efficient method for procuring limited quantities ICT equipment for Upgrade of the LAA land registry of readily system and the MCC construction permitting Request For available off-the- 1.1.3 system 100 000.00 Quotations shelf goods Medium value and local availability. National The user will be 1.1.4 ICT equipment for G2B interoperability 200 000.00 Competitive Bidding able to specify 9|Page PROCURMENT PLAN TEMPLATE FOR SELECTION OF GOODS JUSTIFICATION S FOR THE ESTIMATED PROPOSED COMPON COST ($) PROCUREMENT SELECTION ENT DESCRIPTION OF THE ASSIGNMENT METHOD METHOD detailed requirements to which bidders may respond in offering bids. Value for money will also be achieved. 520 000.00 Sub-Component 1.2 - Improving Access to Financial Services Efficient method for procuring limited quantities ICT equipment for upgrade of the credit of readily infrastructure system that facilitates access to Request for available off-the- 1.2.1 business financing 100 000.00 Quotations shelf goods Efficient method for procuring limited quantities ICT equipment for upgrade of LERIMA movable of readily assets and integration of data from motor vehicle Request for available off-the- 1.2.3 and company registries 100 000.00 Quotations shelf goods Efficient method for procuring limited quantities of readily ICT equipment to support implementation of MIS Request for available off-the- 1.2.4 for Lesotho Post bank value-chain financing 100 000.00 Quotations shelf goods 10 | P a g e PROCURMENT PLAN TEMPLATE FOR SELECTION OF GOODS JUSTIFICATION S FOR THE ESTIMATED PROPOSED COMPON COST ($) PROCUREMENT SELECTION ENT DESCRIPTION OF THE ASSIGNMENT METHOD METHOD Efficient method for procuring limited quantities of readily Request for available off-the- 1.2.5 ICT equipment to support L-PCG 100 000.00 Quotations shelf goods 400 000.00 Sub-Component 1.3 – Strengthening the Resilience of MSMEs to Climatic Shocks COMPONENT 2: SCALING SUPPORT FOR ENTREPRENEURSHIP AND MSMES Sub-Component 2.1 - Establishing an Entrepreneurship Hub and Seed Financing Facility Medium value and local availability. The user will be able to specify detailed requirements to which bidders may respond in offering bids. Value for money Procure equipment and furniture for the National will also be 2.1.1 Entrepreneurship Hub 300 000.00 Competitive Bidding achieved. Sub-Component 2.2 - Scaling Up of the Lesotho Enterprise Assistance Program Efficient method for procuring Request for limited quantities Procure ICT equipment and furniture 70 000.00 Quotations of readily 11 | P a g e PROCURMENT PLAN TEMPLATE FOR SELECTION OF GOODS JUSTIFICATION S FOR THE ESTIMATED PROPOSED COMPON COST ($) PROCUREMENT SELECTION ENT DESCRIPTION OF THE ASSIGNMENT METHOD METHOD available off-the- shelf goods Sub-Component 2.3 - Expanding SME Participation in High Potential Value Chains Medium value and local availability. The user will be able to specify detailed requirements to which bidders may respond in offering bids. Value for money Procure ICT equipment and furniture for National will also be 2.3.1 Horticulture Incubation Hub 300 000.00 Competitive Bidding achieved. COMPONENT 3: PROJECT MANAGEMENT IMPLEMENTATION SUPPORT Efficient method for procuring limited quantities of readily Request for available off-the- 3.1.1 ICT equipment and furniture for PMU 100 000.00 Quotations shelf goods Medium value and local availability. The user will be National able to specify 3.1.2 Procure vehicles for PMU and Vehicle 150 000.00 Competitive Bidding detailed 12 | P a g e PROCURMENT PLAN TEMPLATE FOR SELECTION OF GOODS JUSTIFICATION S FOR THE ESTIMATED PROPOSED COMPON COST ($) PROCUREMENT SELECTION ENT DESCRIPTION OF THE ASSIGNMENT METHOD METHOD requirements to which bidders may respond in offering bids. Value for money will also be achieved. PROCURMENT PLAN TEMPLATE FOR SELECTION OF WORKS COMPON ESTIMATED PROCUREMENT ENT DESCRIPTION OF THE ASSIGNMENT COST ($) METHOD Sub-Component 2.3 - Expanding SME Participation in high Potential Value Chain Medium value and local availability. The user will be able to specify detailed requirements to which bidders may respond in offering bids. Value for money National will also be 2.3.1 Refurbishment of the Horticulture Incubation Hub 250 000.00 Competitive Bidding achieved. COMPONENT 3: PROJECT MANAGEMENT IMPLEMENTATION SUPPORT 13 | P a g e PROCURMENT PLAN TEMPLATE FOR SELECTION OF GOODS JUSTIFICATION S FOR THE ESTIMATED PROPOSED COMPON COST ($) PROCUREMENT SELECTION ENT DESCRIPTION OF THE ASSIGNMENT METHOD METHOD Efficient method for procuring limited quantities of readily Request for available off-the- 3.1.1 Partitioning of New PMU office space 50 000.00 Quotations shelf goods 14 | P a g e CHAPTER 2 2.0 OVERVIEW OF COUNTRY, BORROWER AND MARKET PLACE 2.1 Operational Context This section provides an overview of the context in which the project will be implemented and the conditions under which the procurement process will take place. It is essentially based on a simplified Governance, Economic, Sustainability and Technological (GEST analysis as suggested in the procurement guidance: Project Procurement Strategy for Development Short Form Guidance (World Bank:2017). 2.1.1 Governance Aspects Lesotho’s private sector is largely concentrated in two sectors – mining and textiles/apparel manufacturing – and economic diversification has proven challenging due to a lack of competitiveness. The two sectors account for 84 percent of all formal sector employment and over two-thirds of all exports. Both sectors have experienced challenges in recent years. Textile and apparel exports have been declining due to competitiveness challenges and Kenya has overtaken Lesotho as the leading apparel exporter to the United States under the African Growth and Opportunity Act (AGOA). Total employment in the export manufacturing sector dropped from a peak of 43,500 in February 2020 to a low of 31,000 in April 2020 before rebounding to 39,000 in September 2020.1 It was reported that an additional 6,000 workers had been laid off in 2021. Job losses in the textile/manufacturing sector have had a significant impact on women and on widening gender gaps in labour market outcomes in Lesotho. Women comprise 80 percent of the approximately 40,000 textile workers in Lesotho and an increasing 1 LNDC survey of 64 firms in eight industrial estates, November 2020; most of these factory workers are women 15 | P a g e proportion of those who migrate to South Africa for jobs in the textile industry.2 The pandemic has exposed the underlying challenges that are stifling the export competitiveness of the manufacturing sector as well as exposing the vulnerable position of women workers in the sector, who suffer from occupation segregation across the entire spectrum of labour market opportunities occupying lower-skilled jobs compared to men, even in sectors such as manufacturing where they predominate. Lesotho’s mining sector is entirely dependent on diamond exports which have faced declining demand in recent years. Lesotho’s business environment is still weak despite recent reforms, with political instability, tax rates and practices of the informal sector emerging as the top three constraints for firms. The Second National Strategic Development Plan (NSPD II) (2019-2023) identified an “uncompetitive business environment” as one of the key binding constraints on the growth of private enterprises, adversely affecting both FDI and local micro, small, and medium enterprises (MSMEs). Recent reforms include new legislation for business registration and licensing and secured lending as well as starting adoption of digital systems and procedures in trade facilitation, land administration, and construction permits, all supported under the World Bank’s Second Private Sector Competitiveness and Economic Diversification Project (PSCED2), which closes in June 2022. However, weak regulations and inadequate institutional capacity hinder the effective implementation of these reforms necessary for meaningful impact. Lesotho’s ranking in the Global Competitiveness Index dropped from 123 to 131 out of 141 countries (from 2014 to 2019), and the Logistics Performance Index ranking also dropped from 133 to 139. In the most recent Enterprise Survey, the top constraints faced by firms are (in order of severity): (i) political instability, (ii) tax rates, (iii) practices of the informal sector, (iv) access to finance, (v) crime, (vi) theft and disorder, (vii) access to land, (viii) electricity (power supply), (ix) corruption (x) tax administration, and (xi) customs and trade 2 Botea, Compernolle, and Chakravarty 2018 16 | P a g e regulations.3 These challenges have manifested in different ways. For example, insolvency takes 2.6 years with a recovery rate of 28 cents per dollar compared to 2 years and 43 cents of recovery for the rest of the SACU region4 and the onerous licensing regulations have left local wool and mohair farmers with just one broker through whom they can sell their production. 3 World Bank Enterprise Survey, 2016 4 IMF Data 17 | P a g e 2.1.2 Economic Aspects Despite being a lower-middle income country, Lesotho experiences persistently high levels of unemployment, informality, inequality, and poverty, which have been further exacerbated by the Covid-19 pandemic. GDP growth has steadily worsened over the past decade, from a peak of 6.3 percent in 2012 to -11.1 percent in 2020, resulting in a 12 percent decline in GDP per capita from 2016 to 2020 Lesotho’s poor economic performance has been the result of compounding factors including declining revenues from the Southern African Customs Union (SACU)5, recurrent climate related shocks that have drained fiscal resources6, a high public sector wage bill that has inhibited spending on development objectives, and contraction of key economic sectors (manufacturing and tourism) due to the Covid-19 pandemic. Unemployment is at 22.5 percent7, and while the poverty rate in Lesotho fell from 56.6% to 49.7% between 2002 and 2017, economic vulnerability persists with more than 75% of the population either poor or vulnerable to poverty, driven in large part by exposure to climatic shocks. Declines in remittances due to Covid-19 related border restrictions have further exacerbated poverty. Although income and other measures of inequality have fallen, Lesotho remains one of the most unequal countries in the world.8 Overall, Lesotho’s economic and social development is not commensurate with the country’s lower- middle-income-status.9 The public sector has a disproportionate role in the economy, crowding out private participation and resulting in a weak and largely informal private sector. The government has been the main driver of economic activity, with public spending accounting for 60 percent of GDP and with public sector 5 SACU revenues fell from 30% of GDP in FY2012/13 to 17.7% of GDP in FY2017/18 and are expected to decline further to 15.2% of GDP in FY 2019/20. 6 The average annual cost of disaster response is estimated at US$19.3 million, or 1.6 percent of the total budget expenditure in the 2019/20 fiscal year. 7 22.5 percent unemployment (strict definition) or 38.3 percent (expanded definition) in 2019. Systematic Country Diagnostic. World Bank (Forthcoming) 8 Lesotho Poverty Assessment. World Bank (2019). 9 IMF Article IV Consultation (2019) 18 | P a g e investment levels averaging around 29 percent of GDP since 2010, both figures amongst the highest in the world. The government’s contribution to GDP now far exceeds that of the textile and apparel industry, which is the largest private sector industry in Lesotho. Lesotho’s public sector wage bill (as a percentage of GDP) is one of the highest in the world and has crowded out private sector employment. Public sector workers earn an average monthly salary that is approximately seven times higher than the minimum wage of a skilled worker in the textile sector.10 The recent Mid-Term Budget Review projects the compensation of employees to account for 45.9 percent of total government expenditures for 2020/21. Core inflation, which excludes the CPI suppliers with extreme price changes, however, decelerated from 4.2 percent in June 2021 to 3.9 percent in July 2021. The decline was broad-based but major contributors were food and non-alcoholic beverages, transport, housing, water, electricity, gas and other fuels and alcohol and tobacco components. The disinflation during the review period reflected declining international food prices due to better cereal production from the United States and Argentina and cancelled grain import orders from China. In addition, the exchange rate appreciation of South African Rand against the US. Dollar contributed to falling domestic prices, amid favourable harvest conditions, domestic availability of grain and limited food import demand. (Central Bank of Lesotho Monthly Economic Review (July 2021). 2.1.3 Sustainability Aspects Sustainable procurement is a process which incorporates sustainability considerations throughout the procurement process in order to achieve optimal value for money in delivering development objectives. (Sustainable Procurement an introduction for practitioners to sustainable procurement in World Bank IPF projects November 2016). The United Nations Environment Programme (UNEP) defines Sustainable Public Procurement 10 Lesotho Poverty Assessment. World Bank (2019) 19 | P a g e (SPP) as “a process whereby organisations meet their needs for goods, services, works and utilities in a way that achieves value for money on a whole life basis in terms of generating benefits not only to the organisation, but also to society and the economy, whilst minimising damage to the environment” (United Nations Environment Programme, 2015). The project is supporting broad reforms on financial inclusion and the private sector. Such efforts are meant to strengthen access to finance, create jobs, and support export-led growth. Sustainability will be supported through three main avenues, system-level interventions, infrastructure development, and skills development/capacity building. a) System-level Interventions will Promote Structural Reform. System-level interventions include investments to enhance the interoperability of government IT systems that facilitate private sector activity, implementation of a government payment gateway to support G2B digital payments, investments to strengthen credit infrastructure, and the establishment of a private sector window within the contingency fund and procurement of sovereign insurance (which will be co-financed on a sliding basis, so the cost is increasingly transferred to the budget over the life of the project). b) Establishment of Infrastructure: The project will support the establishment of a sustainable entrepreneurship hub, seed financing facility, infrastructure for the horticulture incubator program. This infrastructure will exceed the life of the project, enabling activities to continue. c) Technical Assistance will Build Skills Amongst the Workforce and Government Capacity. Technical assistance will be provided to the Government to address deficiencies and build interoperability and strengthen disaster risk financing. For the workforce, skills development initiatives will build technical, supervisory and management capacity in high potential sectors and capacity of MSMEs 20 | P a g e and entrepreneurs. Building capacity at the government level will enable line ministries and agencies to continue project activities after the completion of the project. Skills development is intended to equip the workforce with the skills required at the labour market, thereby enabling them to find employment. 2.1.4 Technological Aspects Digital transformation can foster economic growth, reduce poverty, increase productivity and create jobs. However, its potential in underutilised in Lesotho. Whereas good progress has been made in improving digital infrastructure, adoption and use of digital technology is lagging. Around two thirds of the population are not regularly using the internet, pointing to a wide digital divide. As a result, the ability of the government to take advantage of the internet connectivity and digital channels of service delivery for COVID-19response is limited. Adoption and use of digital technology should be accelerated to meet the needs under the pandemic, but also for long-term recovery and development. In 2018, approximately two-thirds of the population were not using the internet regularly even though 97 percent of the population was covered by a 3G network and 72 percent by the 4G network signal. Lesotho ranked 133 on the 2017 ITU ICT Development Index, behind South Africa (92), Botswana (105) and Namibia (118). This ranking was driven by limited use of, and demand placed on the extensive broadband infrastructure. Digital public platforms such as digital ID systems and digital financial services are key for improving efficiency, quality and inclusiveness of the public and private services. Though several G2B services have been developed and adopted with success, the government may need to consider adopting more coordinated and strategic approach towards advancing digital government. Investments in technology may need to be put on shared interoperable infrastructure and services that can be leveraged across various government entities. Legal and regulatory gaps especially concerning cybersecurity, electronic transactions and e-commerce should be fixed. A road map for adopting electronic payments across all government services 21 | P a g e should be developed and the digital financial services market further enhanced. Lesotho is characterised with private sector that makes limited use of digital technologies. In the private sector, digital technology can change the way economies of scale are achieved, particularly through e-commerce and digital payments. The digital economy may provide the better matching of buyers and sellers in a competitive marketplace. The digital economy offers potential for enhanced service delivery in the public sector, but the Lesotho government’s efforts in this field appear fragmented and slow moving. Improved digital infrastructure can only achieve the desired transformational impact if combined with a capable public sector, investments in digital skills and literacy, increased access to digital financial services, and ramped up support for digital start-ups and existing businesses. Though Lesotho is characterised with weak business environment induced by weak government regulations and policies and inadequate institutional capacity to support implementation of reforms that curtail the weak environment, the success of the PSECDP II in implementing reforms supporting private sector development is an indication of the willingness of the country to eliminate these constraints and enhance its rating. The environment within which the CAFI project will be implement is deemed favourable and pose no potential risk that may affect the efficiency and the effectiveness of the project implementation. As mentioned above, the low level of inflation and stable exchange rate will support efficient procurement of both goods and services that would create value for money. Nevertheless, the project encompasses enormous digital transformation that may call for project implementing agencies to prepare accurate technical specifications to ensure relevant purchase of equipment and technology to meet the project development objectives. “World Bank. 2020. Lesotho Digital Economy Diagnostic. World Bank, Washington, DC. © World Bank. https://openknowledge.worldbank.org/handle/10986/33881 License: CC BY 3.0 IGO.” 22 | P a g e 2.2 Assessment of Borrower Capability and Project Implementation Unit (PIU) The Project governance is an “oversight function that is aligned with the organization's governance model and encompasses the project life cycle,” this is according to A Guide to the Project Management Body of Knowledge (PMBOK® Guide) – Fifth Edition (Project Management Institute, 2013, p. 34). There are two critical elements in this statement that need to be emphasised: • Alignment with organization's governance: There needs to be an understanding of the project's environment to ensure that there is a right fit with the established Project's governance. This alignment is a crucial factor and has been considered when defining (1) the project governance framework, (2) roles and responsibilities and (3) stakeholder engagement and communication. The project governance structure is similar to the one used in the implementation of PSCEDP II, which has proven to be effective. The PSCEDP II structure has maintained constant flow of information from the Project Management Unit to all key stakeholders. The proposal is therefore to adopt a strengthened version of the PSCEDP II governance structure (to match the project size) as it ensures that all key stakeholders that are critical for the successful implementation of the project are represented; The Department of Planning under the Ministry of Trade and Industry (MTI) will remain the implementing agency for the CAFI project as MTI already has extensive experience in implementing WB-financed projects. Critical to the governance structure are the following: a) Project Steering Committee 23 | P a g e The Steering Committee will provide advice, ensures delivery of the project outputs and the achievement of project outcomes. The committee is responsible for policy decisions to support the project approvals and implementations, review project progress and facilitates for implementation by the PIUs. The steering committee helps to steer the project through from start to completion. The committee: • Reports to the stakeholders. • Consists of representatives of key Stakeholder Ministries (Trade and Industry, Finance, Development Planning, Agriculture and Food Security, Tourism, Environment and Culture etc.), relevant State- Owned Enterprises (Lesotho National Development Corporation, Basotho Enterprise Development Corporation and Lesotho Tourism Development Corporation), Maseru City Council and critical regulators (Central Bank of Lesotho, Land Administration Authority and Lesotho Revenue Authority); • Reports to GoL (Ministry of Finance, Ministry of Trade and Industry and others) and WB on project implementation status; • Coordinate other ministries around project implementation; • The Principal Secretary of the Ministry of Trade and Industry shall chair the Steering Committee; and • The Steering Committee receives reports from the Project Manager. b) Client/Contracting Authorities • The contracting authority is the Ministry of Trade and Industry. • Signs all contracts with private entities to implement the project (works, services, goods); • Authorise payments to all private entities that have been contracted. • Report to GoL (Ministry of Finance and others) and WB on project implementation status; and • Coordinate other ministries around project implementation. 24 | P a g e c) Project Management Unit (PMU)/ Project Implementation Unit • As the frontline actor, PIU plans, executes, monitors, administers and manages the project representing the project implementing agency (MTI); • Reporting to the Ministry of Trade and Industry and Stakeholder in the format agreed with the Ministry of Development Planning; • Establish financial accounting and control systems and ensure accurate and timely report submissions and funds flow from WB and onwards to the implementing agencies. Financial status and forecast, disbursements; • Procurement and contracting of private entities; • All contracts management (works, services, goods); • Supervise, coordinate and monitor the work of PIUs for implementation of project activities; and • Contribute to institutional analysis if necessary and requested. c) Project Manager (PM) The Project Manager is responsible for the day-to-day implementation of the project through performing the following: • Reporting to MTI and the Steering Committee; • Financial status and forecast, disbursements; • Procurement and contracting of private entities; • Manage Human Resources of the Project; • Oversee contracts negotiations; • Manage the assets of the project; • All contracts management (works, services, goods); • Physical monitoring of works (technical, E&S etc…); and • All other duties as stipulated in the Terms of Reference. A further assessment of the Procurement Capability within the Ministry of Trade and Industry (PMU) has been done. The Ministry through the PMU/PIU 25 | P a g e has over the past fifteen years successfully implemented similar projects including: a) The First Private Sector Competitiveness and Economic Diversification Project (PSCEDP I) b) The Second Private Competitiveness and Economic Diversification Project (PSCEDP II) and c) PSCEDP II - Additional Financing (on-going). Procurement Risk Assessment: The procurement risk assessment has taken into considerations the Strengths, Weaknesses, Opportunities and Threats of the operational context of the implementing agencies. The project will be implemented by the same Project Management Unit (PMU) that is currently implementing the World Bank financed Second Private Sector Competitiveness and Economic Diversification Project (PSCEDP II) under MTI. The PSCEDP II PMU has a good track record of many years and has established project implementation capacity as well as working relationships with key agencies and Ministries across the Government. The PSCEDP II is ending in June 2022 thereby allowing the PMU to be available and ready for CAFI project implementation from the outset of the project. The PMU will be responsible for all fiduciary aspects of the project including FM and procurement activities. The MTI and its PMU, having prior experience of working on PSCED and PSCED II projects, are expected to implement the project smoothly. However, the fact that there will be more project beneficiaries under each component and subcomponent, could pose coordination risk due to the complexity of the project. Based on the existing procurement capacity within the MTI/PMU and taking into consideration one additional Procurement Officer to be recruited by the Project the procurement risk is rated Moderate. This rating has also considered the fact that the current project does not have any IPF component involving complex or high value contracts. It is also expected that all the procurement activities envisaged under the new project (CAFI) will be simple and small value contracts. Taking all these circumstances into consideration, the four major capacity limitations or risks identified at the moment are: (i) lack of prior experience of implementing IPF procurement procedures; (ii) coordination challenge as implementation of components and subcomponents involve many beneficiaries; (ii) Implementation capacity 26 | P a g e gap within the different beneficiaries and (iii) lack of practices on good contracts implementation management. 2.3 Project Procurement Unit Structure The Procurement Unit within the Project Management Unit (PMU) is staffed with qualified procurement professionals i.e. The Procurement Manager holds MSc Degree in Supply Chain Management with more than ten (10) years’ experience in procurement, while the Procurement Officer has bachelor’s degree in economics with seven years’ experience. TABLE 2: PIU Procurement Staff Supply Chain Staff Experience working on Bank Position Qualificati Experienc financed Projects ons e procurement Procurem MSc in Over 10 The Procurement Manager has ent Supply years’ held a senior procurement Manager Chain, BA experience management positions since Degree in in 2017. She managed and Business procureme administered procurement Administrati nt. services under the Lesotho on, government’s capital projects Chartered and donor funded projects Institute of including AfDB and World Bank Procuremen supported projects. t and Supply (Professiona l Diploma Level 6) Procurem BA Over 7 The Procurement Officer has over ent Economics years’ 7 years’ experience working on Officer and experience GoL capital projects that are Chartered in supported by development Institute of procureme partners including AfDB and the Procuremen nt. World Bank. In addition, the t and Supply officer has worked as a (Diploma, Procurement Officer for the level 4) World Bank financed PSCEDP since 2021. 27 | P a g e 2.4 Market Analysis The objective of market research and analysis is to develop a good understanding of the market sectors that have been identified as having the potential to bid for the goods, services, and/or works required by the Project. This is to ensure the eventual Procurement Approach maximizes the likelihood of the right suppliers participating, and the right supplier being selected thereby minimizing failed procurement processes due to no bids, or the wrong types of bids. Supplier Preferencing identifies the approaches suppliers use based on their segmentation of customers. The table below provides a view of a supplier’s likely approach to the project in each category. 28 | P a g e TABLE 3: Supplier Preferencing Model SUPPLIER PREFERENCING MODEL Relative Supply value of Account positioning Compon the Attractiven ent Description of the assignment Business ess COMPONENT 1: ENHANCING G2B DIGITAL SERVICES AND STRENGTHENING PRIVATE SECTOR RESILIENCE ($20.25 MILLION) Sub-Component 1.1: Enhancing Government to Business Digital Services ($ 6.5 million) 1.1.1 Upgrade of the business registration and licensing system at OBFC High High core Upgrade of the LRA customs system, based on UNCTAD`s ASYCUDA core 1.1.2 World System High High Upgrade of the LAA land registry system and the MCC construction core 1.1.3 permitting system High High 1.1.4 Design and development of the G2B interoperability framework Low High Developmental 1.1.5 Design and development of a G2B payment gateway Low High Developmental Sub-Component 1.2: Improving Access to Financial Services ($ 3.0 million) Upgrade of the credit infrastructure system that facilitates access to Developmental 1.2.1 business financing low High Development of credit scoring system to enhance the utility of credit Core 1.2.2 reporting High High 1.2.3 Upgrade of LERIMA movable asset registry High High Core 1.2.4 Development of New financial products to promote market innovation Low High Developmental Capacity building of financial institutions and MSME`s to utilise asset- Core 1.2.5 based lending High High TA to Postbank for development of business case for agricultural value Core chain finance, including market assessment and financing 1.2.6 methodology High High Design and implementation of a management information system (MIS) Developmental 1.2.7 to support value-chain financing Low High 29 | P a g e Review and improve governance, institutional and operational features Core 1.2.8 of the L-PCG High High 1.2.9 Develop a business case and financial model for portfolio guarantees High High Core Design and implement the portfolio guarantee scheme including Core 1.2.10 development of supporting documentation and systems High High 1.2.11 Capacity building High High Core Sub-Component 1.3 – Strengthening the Resilience of MSMEs to Climatic Shocks ($ 10.75 million ) TA on disaster risk financing including drafting of National Disaster Risk Core 1.3.1 Finance Policy for MoF High High Design and development a database for informal MSMEs and integrate Developmental 1.3.2 the database into the existing business registry Low High TA on design and procurement of sovereign insurance backstop and Developmental 1.3.3 co-financing of insurance premiums Low High Draft regulations to govern the operational activities of the existing Core 1.3.4 MoF Contingency Fund High High COMPONENT 2: SCALING SUPPORT FOR ENTREPRENEURSHIP AND MSMES ($ 29.5 MILLION) Sub-Component 2.1 - Establishing an Entrepreneurship Hub and Seed Financing Facility (12.5 million) Procure a private operator to support the establishment of a Core sustainable Entrepreneurship Hub within the Tourism Information Craft 2.1.1 Centre High High 2.1.2 Design and development of an incubation support program High High Core Facilitate the integration of the Lesotho Start-up Community within a Core 2.1.3 wider regional Entrepreneurship ecosystem High High Procure a private operator to establish and manage a seed financing Core 2.1.4 facility and an associated acceleration program High High Sub-Component 2.2 - Scaling Up of the Lesotho Enterprise Assistance Program ($ 5.0 million) Procure private sector service providers to augment the delivery Developmental 2.2.1 capacity of LEAP PMU Low High Sub-Component 2.3 - Expanding SME Participation in high potential Value Chains ($ 12 million) 2.3.1 TA to set up a Horticulture Incubation Hub Low High Developmental 30 | P a g e Summary of Procurement Market Analysis for the Project: Considering the local, Regional, and international market situations and the nature and value of the procurement activities under this project, the market risk is low and favourable. Conducting further detail market research for other innovative market approaches and selection methods is not proportional. Therefore, the default selection methods are fit-for-purpose as indicated in table 6, Chapter 6 of this PPSD. 31 | P a g e 32 | P a g e CHAPTER 3 3.0 PROJECT PROCUREMENT RISK ANALYSIS TABLE 4: Project Procurement implementation capacity (MoTI) Risk Analysis Risk Probability Impact Risk Rating Description of Mitigation of Measure occurrence (Major, (High, (Very likely, minor, Substantial, likely, unlikely, negligible, or Moderate, Low or not not or Not applicable) applicable) Applicable) 1. Accountability for Procurement Unlikely Major Moderate (2) Prepare and adopt a Project Decisions Procurement Manual (PPM), that identifies lines of responsibilities. 2. Internal Manuals and Clarity of Unlikely Minor Moderate (3) Develop a project the Procurement Process procurement manual that is comprehensive and easy to follow and should be accessible to all procurement staff. 3. Record Keeping & Document All procurement documents Management Systems Unlikely Minor Moderate (2) will be kept in procurement office with contract register manual and should be accessible to all procurement staff. 4. Procurement Planning Likely Major High (4) Prepare and adopt a project operation manual (POM), including a chapter on procurement comprising of 33 | P a g e Risk Probability Impact Risk Rating Description of Mitigation of Measure occurrence (Major, (High, (Very likely, minor, Substantial, likely, unlikely, negligible, or Moderate, Low or not not or Not applicable) applicable) Applicable) clear rules, step by step procedures and responsibility, timeline requirements for procurement activities. All Procurement assignment should be uploaded in STEP. 5. Bidding documents, qualification/ Likely Minor Substantial (3) Follow Bank’s Procurement shortlisting/ evaluation criteria templates. Standard bidding documents, evaluation forms and evaluation criteria should be availed and provided in the bidding document. 6. Staffing Unlikely Major Moderate (2) Recruitment of qualified and experienced staff and require staff involved in procurement to declare their interest and sign a declaration form. 7. Advertisement, Pre-bid/proposal Unlikely Minor Moderate (2) Ensure that all adverts, pre Conference and Bid/Proposal bid/proposal conference and Submission bid/proposal submissions should follow the banks procurement procedures and regulations. 34 | P a g e Risk Probability Impact Risk Rating Description of Mitigation of Measure occurrence (Major, (High, (Very likely, minor, Substantial, likely, unlikely, negligible, or Moderate, Low or not not or Not applicable) applicable) Applicable) 8. Evaluation and Award of contract Unlikely Major Moderate (2) Recruit qualified technical evaluation team and follow the bank`s procurement procedure. 9. Review of Procurement Decisions Unlikely Major Moderate (2) Establish a procurement and Resolution of Complaints complaint handling mechanism consistent with the Government Procurement Rules and Regulations and in line with the World Bank`s requirements. 10. Contract Management and Likely Minor Substantial (3) Develop a contract Administration management strategy and contract management plan 11. Procurement Oversight Unlikely Major Moderate (2) Procurement audits should be carried out regularly. 12. Procurement functional Unit Unlikely Major Moderate (2) Recruit qualified performance procurement staff with experience in implementation of World Bank financed project procurement. Overall Project Procurement Risk 28/12 =2.3 ~~ (2) = Moderate rating 35 | P a g e Note: The risk ratings in fourth column of the above table are determined using the following formulation: Probability of Impact Risk Rating Occurrence Likely or Equal Major High Likelihood Likely or Equal Minor Substantial Likelihood Likely or Equal Negligible Moderate Likelihood Unlikely Major Moderate Unlikely Minor Moderate Unlikely Negligible Low Not applicable Not Applicable Not Applicable 36 | P a g e Procurement Risk Mitigation Measures: The MTI will have overall responsibility of procurement under the project. Based on the above preliminary procurement implementation risks identification, the mitigation measures may also include: (i) provision of reorientation/training to the PMU on Bank’s procurement procedures and contract management, including use of STEP platform; (ii) putting in place simple, but efficient, procurement and contract management mechanism (tracking system);(iii) Develop Project Operational Manual/Project Procurement Strategy for Development (PPSD) that would assist the practitioners on procurement routines and (iv) strengthen the PMU based on the needs of the new project. More frequent World Bank implementation support missions with the aim of providing closer support and monitoring the performance of PMU and its Procurement team’s performance would also add value. Record Keeping: All records pertaining to award of tenders, including bid notification, register pertaining to sale and receipt of bids, bid opening minutes, bid evaluation reports and all correspondence pertaining to bid evaluation, communication sent to/with the World Bank in the process, bid securities, and approval of invitation/evaluation of bids by the management would be retained by the Procurement Unit and also uploaded in the STEP for Post ante review and independent procurement audit, as necessary. Operational Context, SWOT Analysis: According to CIPS (2012) Strengths, weaknesses, opportunities, and threats (SWOT) analysis is a technique of corporate appraisal, used to assess the internal resources of an organisation (or function or project) to cope with and/or capitalise on factors in the external environment in which it operates. This tool will be used to assess the PMU’s capability. A summary of the strengths, weaknesses, opportunities, and threats regarding the capacity of the PMU is presented as follows: 37 | P a g e 38 | P a g e STRENGTHS The Project Management Unit (PMU) has extensive experience in executing projects funded by the World Bank and the African Development Bank (AfDB) and has both tangible and non-tangible resources to execute projects. The unit already has some human capital with relevant skills set to execute the project and the Project Manager has successfully managed the PSCEDP I and PSCEDP II and PSCEDP II – Additional Financing. The Project Manager is supported by an experienced competent fiduciary management team that has more than 10 years’ experience. The project also has experience in stakeholder and private sector engagements and administration of matching grants. The PMU already has office space, furniture and ICT equipment which are in good condition to start the new project. The responsible Ministry also has prior operational experience in implementation of World Bank financed projects. WEAKNESSES The procurement staff lacks operational capacity to administer procurement of multiple packages at the same time in a timely manner. The operational capacity is limited by under-staffing of the Procurement Unit. OPPORTUNITIES The Project has tools and systems in place that enables procurement to be carried out effectively, efficiently, and economically. All procurements under the project will be carried out in accordance with the World Bank’s Procurement Regulations for Investment Project Financing Recipient’s- Procurement in investment Project Financing Goods, Works, Non-Consulting and Consulting services. The project will also be subject to the guidelines on preventing and combating fraud and corruption in projects Financed by IBRD Loans and IDA Credit and grants. The Systematic Tracking Exchange Procurement (STEP) system will be used to track all procurement planning, execution, and contract management. The PMU will also recruit additional procurement staff to strengthen the capacity of the Procurement Unit. 39 | P a g e THREATS The main threat is political instability, which may hider implementation of important policies and regulations. The governing coalition remains fragile with considerable risk of frequent change in administration during project implementation. Political instability can also deter new international investors and experienced service providers. Limited availability of service providers can in turn delay procurement processes and may lead to selection of inexperienced consultants. Strength: Weakness 5. PIU’s Prior experience of similar • Limited manpower/staff projects implementation for increased works 6. Well-functioning PMU having • Lack of experience on necessary facilities and complex contracts motivated team procurement and 7. Availability of tested and well- contracts implementation functioning working procedures management and well-defined responsibility • Lack of business matrix performance standard Opportunities Threats • Technical support and training • Political instability opportunities from the • Weak local/national Development partners (world market Bank & others). • Application and use of good practice standard procurement documents of the development partners (World Bank) including use of STEP for tracking procurement transactions. 40 | P a g e • Availability of providers in the region, like SA. Key Risks Identified from operational context and agency capacity: i. MoTI-PIU institutional performance capacity limitations. ii. Inadequate local market. iii. Political instability and weak macro-economic performance 41 | P a g e CHAPTER 4 4.0 STAKEHOLDER ANALYSIS The table below presents analysis of key stakeholders responsible for implementation of various components of the project towards achievement of the Project Development Objective: TABLE 5: Stakeholder Analysis STAKEHOLDER MANAGEMENT PLAN Interest in Stakeholder Name the Stakeholder Objectives from the Stake Holder Management Project11 Procurement Approach R A C I World Bank - - - Y • To ensure that project procurement in C compliance with procurement objectives. Consult and Keep informed and comply Ministry of Trade and Y Y Y Y • MTI is the implementing agency MTI is responsible and accountable Industry and should be consulted and informed Maseru City Council - - Y Y • Project Implementing agency for upgrade MCC is consulted and informed of the construction permitting system Basotho Enterprise - - Y Y • Stakeholder in the implementation of BEDCO is consulted and informed Development Corporation subcomponent 2.1 and 2.2 of the project. (BEDCO) 11 Responsible, Accountable, Consulted, Informed 42 | P a g e STAKEHOLDER MANAGEMENT PLAN Interest in Stakeholder Name the Stakeholder Objectives from the Stake Holder Management Project11 Procurement Approach R A C I Lesotho Revenue - - Y Y • Stakeholder in the implementation of LRA is consulted and informed Authority (LRA) subcomponent 1.1 and 1.2 and 1.3 of the projects. One Stop Business - - Y Y • Stakeholder in the implementation of OBFC is consulted and informed Facilitation Centre (OBFC) subcomponent 1.1. Ministry of Small Business - - Y Y • Stakeholder in the implementation of MSBDC is consulted and informed Development and subcomponent 1.3, 2.1 and 2.2 of the Cooperatives project. Prime Minister’s Delivery - - Y Y • Stakeholder in the implementation of PMDU is consulted and informed Unit (PMDU) component 3 Ministry of Labour and - - Y Y • Stakeholder in the implementation of MoLE is consulted and informed Employment subcomponent 2.3. Ministry of Public Works - - Y Y • Stakeholder in the implementation of MPW is consulted and informed subcomponent 2.3. Ministry of Transport - - Y Y • Stakeholder in the implementation of MoT is consulted and informed subcomponent 2.3. Lesotho National - - Y Y • Stakeholder in the implementation of LNDC is consulted and informed Development Corporation subcomponent 2.3. (LNDC) Central Bank of Lesotho - - Y Y Stakeholder in the implementation of CBL is consulted and informed (CBL) subcomponent 1.2 and 1.3 of the project. National University of - - Y Y • Stakeholder in the implementation of MUL is consulted and informed Lesotho (NUL) subcomponent 2.3. 43 | P a g e CHAPTER 5 5.0 PROCUREMENT OBJECTIVES Based on the Strategic Analysis, Risk Assessment and Stakeholder Analysis, the five key Procurement Objectives that if achieved, would help support the delivery of the Project Development Objective are as follows: • Packaging based on market analysis to aim for an average of 8 bidders’ participation in each bid. • Foster competition to enhance achievement of VfM by familiarizing the vendors with the SBDs for international approach to market through vendor conferences and pre-bid meetings and site visits, and suitably modifying and customizing the bidding documents and conditions such as qualification requirements and application of bid securities with the objectives receiving competitive bid prices which are within approximately 15% of client’s cost estimate. • Implementation of works and services in time to ensure that 95 percent of bids are awarded without extending bid validity and that rebid in not more than 5 percent cases, for all procurements. • Awarding contracts to qualified, experienced, capable bidders so that 90 percent of contracts are executed within original allotted time; and • Contracts are completed with not more than 15 percent cost overruns by carrying out robust design at bidding stage. 44 | P a g e CHAPTER 6 6.0 PROCUREMENT APPROACH OPTIONS AND RECOMMENDATIONS This procurement strategy/approach is designed based on the project requirements, technical solutions, and market information, institutional capacity and experience of the Ministry of trade and Industry (MoTI). The Market approach and selection method proposed for each package has taken into considerations values, complexities, local market capacity and institutional experiences of MoTI to achieve better Value for Money (VfM) while supporting the project achievement of objectives its objectives. The project has no high value and complex contract packages as such. However, the PPSD has focused on separate packages for consultancy services and works using both international and national approach to markets with the objectives of fostering competitions to enable the PIU get best of what the market can offer. For certain unique packages, where open competition may not be the best-fit approach, Direct Selection (DS) has been proposed with clear justifications on why DS is found to be fit-for-purpose as against the default open competitive market approaches. The following activities are proposed for Direct Selection market approach for the reasons as indicated in the below table: Package/contract Reason why non-competitive market approach is Name of Proposed appropriate and departing from the preferred and supplier/consultant default competitive methods 45 | P a g e Consultancy Services for UNCTAD is uniquely and exceptionally qualified to upgrade UNCTAD is an eligible design and upgrade of the business registration and licensing system at OBFC as it firm under Bank’s business registration and was originally developed by them. It is also the case that financed projects. It is a the tasks represent a natural continuation of previous UN Agency based in East licensing system at OBFC work carried out by a consultant, where continuity in the and Southern Africa; technical approach, experience acquired, and continued professional liability of the same Consultant may make continuation with the initial Consultant preferable to a new competition. The performance of UNCTAD has been satisfactory in the previous assignment(s); Consultancy Services for design UNCTAD is uniquely and exceptionally qualified to upgrade UNCTAD is an eligible LRA customs system as it was originally designed and and upgrading of the LRA customs firm under Bank’s developed by them. The task represents a natural system, based on UNCTAD`s continuation of previous work carried out by a consultant, financed projects. It is a where continuity in the technical approach, experience ASYCUDA World System UN Agency based in East acquired, and continued professional liability of the same consultant may make continuation with the initial and Southern Africa; consultant preferable to a new competition The performance of UNCTAD has been satisfactory in the previous assignments Consultancy Service for Design Only ESRI is qualified and has experience of exceptional ESRI is an eligible firm worth for the upgrade of the LAA land registry system as and upgrading of the LAA land they designed and developed the system. The task under Bank’s financed registry system represents a natural continuation of previous work carried projects. It out by a consultant, where continuity in the technical approach, experience acquired, and continued professional is a South African liability of the same consultant may make continuation with company based in the initial consultant preferable to a new competition The 46 | P a g e performance of esri has been satisfactory in the previous Midrand 1685, Cnr New assignments Road. Consultancy Services for Only EXPERIAN is qualified and has experience of EXPERIAN is an eligible exceptional worth for the upgrade of the credit Design and upgrading of the infrastructure system as they designed and developed the firm under bank’s credit infrastructure system system. The task represents a natural continuation of financed projects. It is a previous work carried out by a consultant, where continuity that facilitates access to in the technical approach, experience acquired, and South African company continued professional liability of the same consultant may based in Stellenbosch, business financing make continuation with the initial consultant preferable to a new competition The performance of EXPERIAN has been Experian House, 3 satisfactory in the previous assignments Neutron Avenue, Techno PARK. Consultancy Services for Only Paradigm is qualified and has experience of PARADIGM is an eligible exceptional worth for the upgrade of the LERIMA movable Design and Upgrading of asset registry as they designed and developed the system. firm under bank’s LERIMA movable asset registry The task represents a natural continuation of previous work financed projects. It is a carried out by a consultant, where continuity in the technical approach, experience acquired, and continued company based in United professional liability of the same consultant may make States, New York. continuation with the initial consultant preferable to a new competition The performance of PARADIGM has been satisfactory in the previous assignments For works packages where designs have been completed and the client’s requirements are well defined, the selection methods would be RFB or RFQs, based on the package’s values. For works where there are conceptual designs and innovation can be introduced by the providers, the selection method will be RFP. The RFP method will also be used 47 | P a g e for selection of consultants. The selection method for supply and installation of software and hardware, as schedules of requirements and specifications are precisely defined by the ministry, the selection method will be RFBs. The table below presents the project market approach and procurement methods for consultancy services, procurement of goods and works. TABLE 6: Procurement Approach and Recommendation PROCURMENT PLAN FOR SELECTION OF CONSULTANCY SERVICES DESCRIPTION OF PROCURE CONTRA JUSTIFICATION FOR THE ESTIMATED COMPON THE MARKET MENT CT RECOMMENDED SELECTION COST ($) ENT ASSIGNMENT APPROACH METHOD TYPE METHOD COMPONENT 1 : ENHANCING G2B DIGITAL SERVICES AND STRENGTHENING PRIVATE SECTOR RESILIENCE Sub-Component 1.1 - Enhancing Government to Business Digital Services Upgrade of the UNCTAD is a UN Agency based in East business and Southern Africa; It is uniquely and 1.1.1 registration and 800 000.00 Direct exceptionally qualified to upgrade 48 | P a g e licensing system DS Lump business registration and licensing at OBFC Sum system at OBFC as it was originally developed by them. Upgrade of the UNCTAD is a UN Agency based in East LRA customs and Southern Africa. It is uniquely and system, based on DS exceptionally qualified to upgrade UNCTAD`s Lump LRA customs system as it was ASYCUDA World Sum originally designed and developed by 1.1.2 System 1 000 000.00 Direct them. ESRI is a South African company based in Midrand 1685, Cnr New DS Lump Road. It is qualified and has Sum experience of exceptional worth for Upgrade of the the upgrade of the LAA land registry LAA land registry system as they designed and 1.1.3 system 1 000 000.00 Direct developed the system. Design and Appropriate method for high value development of QCBS Lump and complex assignment. the G2B Sum Competitive approach is required to interoperability achieve quality and value for money 1.1.4 framework 1 600 000.00 International Appropriate method for high value and complex assignment. Design and Competitive approach is required to development of a QCBS achieve quality and value for money G2B payment Lump 1.1.5 gateway 1 500 000.00 International Sum 5 980 000.00 Sub-Component 1.2 - Improving Access to Financial Services Upgrade of the Lump credit Sum EXPERIAN is a South African company infrastructure based in Stellenbosch, Experian 1.2.1 system that 200 000.00 Direct DS House, 3 Neutron Avenue, Techno 49 | P a g e facilitates access PARK. It is qualified and has to business experience of exceptional worth for financing the upgrade of the credit infrastructure system as they designed and developed the system. Lump EXPERIAN is a South African company Sum based in Stellenbosch, Experian House, 3 Neutron Avenue, Techno PARK. It is qualified and has Development of DS experience of exceptional worth for credit scoring the development of the credit scoring system to enhance system as they designed the system the utility of credit 1.2.2 reporting 600 000.00 Direct Lump Paradigm is a company based in Sum United States, New York. It is qualified and has experience of exceptional worth for the upgrade of the LERIMA DS movable asset registry as they Upgrade of LERIMA designed and developed the system movable asset 1.2.3 registry 200 000.00 Direct Development of Lump Appropriate method for high value New financial Sum and complex assignment. products to Competitive approach is required to promote market achieve quality and value for money 1.2.4 innovation 500 000.00 International QCBS Capacity building Schedule Appropriate method for less of financial of complex assignments. Preparing and institutions and CQS Rates/Ti evaluating competitive proposals is MSME`s to utilise me- not justified asset-based Based 1.2.5 lending 50 000.00 National 50 | P a g e TA to Postbank for Schedule Appropriate method for less complex development of of assignments. Preparing and business case for Rates/Ti evaluating competitive proposals is agricultural value me- not justified chain finance, Based including market assessment and CQS financing 1.2.6 methodology 150 000.00 International Design and Lump Appropriate method for less complex implementation of Sum assignments. Preparing and a management evaluating competitive proposals is information not justified system (MIS) to support value- CQS 1.2.7 chain financing 200 000.00 International Review and Lump Low value assignment with a duration improve Sum less than six months governance, institutional and operational IC features of the L- 1.2.8 PCG 50 000.00 National Develop a Lump Appropriate method for less complex business case and Sum assignments. Preparing and financial model for evaluating competitive proposals is portfolio CQS not justified 1.2.9 guarantees 150 000.00 International Design and Lump Appropriate method for high value implement the QCBS Sum and complex assignment. portfolio Competitive approach is required to guarantee scheme achieve quality and value for money including development of 1.2.10 supporting 2,000,000.00 International 51 | P a g e documentation and systems Schedule Appropriate method for less complex of assignments. Preparing and CQS Rates/Ti evaluating competitive proposals is me- not justified 1.2.11 Capacity building 100 000.00 National Based 2 800 000.00 Sub-Component 1.3 – Strengthening the Resilience of MSMEs to Climatic Shocks TA on disaster risk Lump Appropriate method for high value financing including Sum and complex assignment. drafting of Competitive approach is required to National Disaster achieve quality and value for money Risk Finance Policy QCBS 1.3.1 for MoF 750 000.00 International Design and Lump Appropriate method for less complex development a Sum assignments. Preparing and database for evaluating competitive proposals is informal MSMEs not justified and integrate the database into the existing business QCBS 1.3.2 registry 300 000.00 International TA on design and Lump Appropriate method for less complex procurement of Sum assignments. Preparing and sovereign evaluating competitive proposals is insurance not justified backstop and co- financing of CQS insurance 1.3.3 premiums 150 000.00 International Draft regulations Lump Low value assignment with a duration 1.3.4 to govern the 75 000.00 National Sum less than six months 52 | P a g e operational activities of the IC existing MoF Contingency Fund 1 275 000.00 COMPONENT 2: SCALING SUPPORT FOR ENTREPRENEURSHIP AND MSMES ($ 29.5 MILLION) Sub-Component 2.1 - Establishing an Entrepreneurship Hub and Seed Financing Facility Procure a private Schedule Appropriate method for high value operator to of and complex assignment. support the Rates/Ti Competitive approach is required to establishment of a me- achieve quality and value for money sustainable Based Entrepreneurship Hub within the Tourism QCBS Information Craft 2.1.1 Centre 500 000.00 International Design and Lump Appropriate method for less complex development of an Sum assignments. Preparing and incubation support evaluating competitive proposals is 2.1.2 program 150 000.00 International CQS not justified Facilitate the Schedule Low value assignment with a duration integration of the of less than six months Lesotho Start-up Rates/Ti Community within me- a wider regional Based Entrepreneurship 2.1.3 ecosystem 50 000.00 National IC Procure a private Schedule Appropriate method for less complex operator to of assignments. Preparing and 2.1.4 establish and 250 000.00 International Rates/Ti 53 | P a g e manage a seed me- evaluating competitive proposals is financing facility CQS Based not justified and an associated acceleration program 950 000.00 Sub-Component 2.2 - Scaling Up of the Lesotho Enterprise Assistance Program Procure private Schedule Appropriate method for less complex sector service of assignments. Preparing and providers to Rates/Ti evaluating competitive proposals is augment the me- not justified delivery capacity QCBS Based 2.2.1 of LEAP PMU 300 000.00 International Sub-Component 2.3 - Expanding SME Participation in high potential Value Chains Lump Appropriate method for high value Sum and complex assignment. TA to set up a Competitive approach is required to Horticulture achieve quality and value for money 2.3.1 Incubation Hub 350 000.00 International QCBS 54 | P a g e PROCURMENT PLAN TEMPLATE FOR SELECTION OF GOODS CONTRA JUSTIFICATION CT TYPE S FOR THE ESTIMATED PROCUREM RECOMMENDE COST ($) COMPON ENT D SELECTION ENT DESCRIPTION OF THE ASSIGNMENT METHOD METHOD COMPONENT 1: ENHANCING G2B DIGITAL SERVICES AND STRENGTHENING PRIVATE SECTOR RESILIENCE Sub-Component 1.1 Enhancing Government to Business Digital Services Conforman Efficient method ce for procuring /Traditional limited quantities ICT equipment for upgrade of the business Request For of readily available 1.1.1 registration and licensing system at OBFC 70 000.00 Quotations off-the-shelf goods Conforman Medium value and ce local availability. /Traditional The user will be able to specify detailed requirements to which bidders may respond in offering ICT equipment for Upgrade of the LRA customs National bids. Value for system, based on UNCTAD`s ASYCUDA World Competitive money will also be 1.1.2 System 150 000.00 Bidding achieved. Conforman Efficient method ce for procuring /Traditional limited quantities ICT equipment for Upgrade of the LAA land Request For of readily available 1.1.3 registry system. 100 000.00 Quotations off-the-shelf goods 55 | P a g e Conforman Medium value and ce local availability. /Traditional The user will be able to specify detailed requirements to which bidders may respond in offering National bids. Value for Competitive money will also be 1.1.4 ICT equipment for G2B interoperability 200 000.00 Bidding achieved. 520 000.00 Sub-Component 1.2 - Improving Access to Financial Services Conforman Efficient method ce for procuring ICT equipment for upgrade of the credit /Traditional limited quantities infrastructure system that facilitates access to Request for of readily available 1.2.1 business financing 100 000.00 Quotations off-the-shelf goods Conforman Efficient method ce for procuring ICT equipment for upgrade of LERIMA movable /Traditional limited quantities assets and integration of data from motor Request for of readily available 1.2.3 vehicle and company registries 100 000.00 Quotations off-the-shelf goods Conforman Efficient method ce for procuring ICT equipment to support implementation of /Traditional limited quantities MIS for Lesotho Post bank value-chain Request for of readily available 1.2.6 financing 100 000.00 Quotations off-the-shelf goods Conforman Efficient method ce for procuring /Traditional limited quantities Request for of readily available 1.2.7 ICT equipment to support L-PCG 100 000.00 Quotations off-the-shelf goods 400 000.00 56 | P a g e Sub-Component 1.3 – Strengthening the Resilience of MSMEs to Climatic Shocks COMPONENT 2: SCALING SUPPORT FOR ENTREPRENEURSHIP AND MSMES Sub-Component 2.1 - Establishing an Entrepreneurship Hub and Seed Financing Facility Conforman Medium value and ce local availability. /Traditional The user will be able to specify detailed requirements to which bidders may respond in offering National bids. Value for Procure equipment and furniture for the Competitive money will also be 2.1.1 Entrepreneurship Hub 300 000.00 Bidding achieved. Sub-Component 2.2 - Scaling Up of the Lesotho Enterprise Assistance Program Conforman Medium value and ce local availability. /Traditional The user will be able to specify detailed requirements to which bidders may respond in offering bids. Value for Request for money will also be Procure ICT equipment and furniture 70 000.00 Quotations achieved. Sub-Component 2.3 - Expanding SME Participation in high Potential Value Chains Conforman Medium value and ce local availability. National /Traditional The user will be Procure ICT equipment and furniture for Competitive able to specify 2.3.1 Horticulture Incubation Hub 300 000.00 Bidding detailed 57 | P a g e requirements to which bidders may respond in offering bids. Value for money will also be achieved. COMPONENT 3: PROJECT MANAGEMENT IMPLEMENTATION SUPPORT Conforman Efficient method ce for procuring /Traditional limited quantities Request for of readily available 3.1.1 ICT equipment and furniture for PMU 100 000.00 Quotations off-the-shelf goods Conforman Medium value and ce local availability. /Traditional The user will be able to specify detailed requirements to which bidders may respond in offering National bids. Value for Competitive money will also be 3.1.2 Procure vehicles for PMU and Vehicle 150 000.00 Bidding achieved. PROCURMENT PLAN TEMPLATE FOR SELECTION OF WORKS Estimated Procuremen Component Description of the assignment Cost ($) t Method Sub-Component 2.3 - Expanding SME Participation in high Potential Value Chain Conforman Medium value and National ce local availability. Refurbishment of the Horticulture Competitive /Traditional The user will be 2.3.1 Incubation Hub 250 000.00 Bidding able to specify 58 | P a g e detailed requirements to which bidders may respond in offering bids. Value for money will also be achieved. COMPONENT 3: PROJECT MANAGEMENT IMPLEMENTATION SUPPORT Conforman Efficient method ce for procuring /Traditional limited quantities Request for of readily available 3.1.1 Partitioning of New PMU office space 50 000.00 Quotations off-the-shelf goods 59 | P a g e CHAPTER 7 7.0 SUMMARY OF PPSD TO SUPPORT THE PREPARATION OF THE PAD BY THE BANK The recommended procurement approach, which is expected to inform the Project Appraisal Document (PAD) is stated in the summary above. The rationale for this approach is primarily based on packaging that is suitable for each procurement package. 60 | P a g e CHAPTER 8 8.0 PROCUREMENT PLAN FOR THE FIRST 18 MONTHS TABLE 8: Procurement Plan for Goods, Works & Non-Consultancy Services 1 2 3 4 5 6 7 8 9 10 11 Expected Expected Expected Expected Expected contract contract Contract Estimat Procurem Prequalif (Prio Bid Bid- contract commence completio Ref. No. Descriptio ed Cost ent ication r/ Floating Opening award ment date n date n (US$’00 Method (yes/no) Post Date Date date 0) ) COMPONENT 1: ENHANCING G2B DIGITAL SERVICES AND STRENGTHENING PRIVATE SECTOR RESILIENCE ($20.25 MILLION) Sub-Component 1.1 - Enhancing Government to Business Digital Services ($520 000.00) CAF/WB/GO/2 ICT 70 RfQ NO Post 5 Jan 23 15 Feb 23 29 March 1 April 23 17 May 23 7 equipment 23 for upgrade of the business registration and licensing system at OBFC CAF/WB/GO/2 ICT 150 NCB NO Post 10 Aug 23 15 Sept 23 29 Sept 23 2 Oct 23 17 Nov 23 8 equipment 61 | P a g e for Upgrade of the LRA customs system, based on UNCTAD`s ASYCUDA World System CAF/WB/GO/2 ICT 100 RFQ NO Post 6 Oct 22 6 Nov 22 18 Nov 22 25 Nov 22 6 Jan 23 9 equipment for Upgrade of the LAA land registry system and the MCC constructio n permitting system CAF/WB/GO/3 ICT 200 NCB NO Post 10 Aug 23 15 Sept 23 29 Sept 23 2 Oct 23 17 Nov 23 0 equipment for G2B interoperabi lity Sub-Component 1.2 Improving Access to Financial Services CAF/WB/GO/ ICT 100 RfQ NO Post 10 Aug 23 15 Sept 23 29 Sept 23 2 Oct 23 17 Nov 23 31 equipment for upgrade 62 | P a g e of the credit infrastructur e system that facilitates access to business financing CAF/WB/GO/ ICT 100 RfQ NO Post 10 Aug 23 15 Sept 23 29 Sept 23 2 Oct 23 17 Nov 23 32 equipment for upgrade of LERIMA movable assets and integration of data from motor vehicle and company registries CAF/WB/GO/ ICT 100 RfQ NO Post 10 Aug 23 15 Sept 23 29 Sept 23 2 Oct 23 17 Nov 23 33 equipment to support implementati on of MIS for Lesotho Post bank value- chain financing CAF/WB/GO/ ICT 100 RfQ NO Post 10 Aug 23 15 Sept 23 29 Sept 23 2 Oct 23 17 Nov 23 34 equipment 63 | P a g e to support L- PCG Sub-Component 2.1 - Establishing an Entrepreneurship Hub and Seed Financing Facility CAF/WB/GO/ Procure 300 NCB NO Post 11 Aug 22 15 Sept 22 29 Sept 22 2 Oct 22 17 Nov 22 35 equipment and furniture for the Entrepreneu rship Hub Sub-Component 2.2 - Scaling Up of the Lesotho Enterprise Assistance Program CAF/WB/GO/ Procure ICT 70 RfQ NO Post 3 Feb 23 2 March 16 March 31 March 23 12 May 23 36 equipment 23 23 and furniture Sub-Component 2.3 - Expanding SME Participation in high Potential Value Chains Procure ICT 300 NCB NO Post 10 Aug 23 15 Sept 29 Sept 23 2 Oct 23 17 Nov 23 CAF/WB/GO/ equipment 23 37 and furniture for Horticulture Incubation Hub COMPONENT 3: PROJECT MANAGEMENT IMPLEMENTATION SUPPORT CAF/WB/GO/ ICT 100 RfQ NO Post 10 Oct 23 15 Nov 23 29 Nov 23 2 Dec 23 17 Dec 23 38 Equipment and furniture for PMU CAF/WB/GO/ Procure 150 NCB NO Post 10 Jun 23 15 July 23 2 Aug 23 2 Aug 23 15 Sept 23 39 vehicles for PMU and Vehicle 64 | P a g e PROCUREMENT PLAN FOR SELECTION OF WORKS Sub-Component 2.3 - Expanding SME Participation in high Potential Value Chain CAF/WB/WS/ Refurbishme 250 NCB NO Post 10 Aug 23 15 Sept 2 Oct 23 2 Oct 23 17 Nov 23 40 nt of the 23 Horticulture Incubation Hub COMPONENT 3: PROJECT MANAGEMENT IMPLEMENTATION SUPPORT CAF/WB/WS/ Partitioning 50 RfQ NO Post 10 July 23 15 Aug 23 2 Aug 23 2 Aug 23 17 Aug 23 41 of New PMU office space PROCURMENT PLAN FOR CONSULTING SERVICES Expected Expected Expect Expected Expected assignment contract Contract Estimat Procurem Prior Review ed Technical Assignme commence completio Ref. No. Description ed Cost ent Shortlisti by REoI Proposal nt award ment date n date (US$’00 Method ng Financi (SPN s date 0) yes/no) ng date) Opening Agency date (Prior / Post) COMPONENT 1: ENHANCING G2B DIGITAL SERVICES AND STRENGTHENING PRIVATE SECTOR RESILIENCE ($20.25 MILLION) Sub-Component 1.1 - Enhancing Government to Business Digital Services ($520 000.00) CAF/WB/CS/0 Upgrade of 800 Direct NO Prior - 1 Nov 22 Nov 29 Nov 2022 31 May 1 the business 2022 2022 2023 Registration and Licensing system at OBFC 65 | P a g e CAF/WB/CS/0 Upgrade of 1 000 Direct NO Prior - 1 Nov 22 Nov 29 Nov 2022 31 May 2 the LRA 2022 022 2023 customs system, based on UNCTAD`s ASYCUDA World System CAF/WB/CS/0 Upgrade of 1 000 Direct NO Prior - 1 Nov 22 Nov 29 Nov 2022 31 May 3 the LAA land 2022 022 2023 registry system CAF/WB/CS/0 Design and 1 600 QCBS Yes Prior 9 Jan 2023 6 Feb 23 27 Feb 28 Feb 23 31 August 4 development 2023 2023 of G2B interoperabil ity Sub-Component 1.2- Improving Access to Financial Services CAF/WB/CS/0 Upgrade of 200 Direct NO Post - 1 Nov 22 Nov 22 Nov 2022 31 May 5 the credit 2022 2022 2023 infrastructure system that facilitates access to business financing CAF/WB/CS/0 Development 600 QCBS Yes Prior 9 Jan 2023 6 Feb 27 Feb 28 Feb 2023 31 Aug 6 of credit 2023 2023 2023 scoring system to 66 | P a g e enhance the utility of credit reporting CAF/WB/CS/0 Upgrade of 200 Direct - Post 1 Nov 22 Nov 22 Nov 29 Nov 2022 31 May 7 LERIMA 2022 2022 2022 2023 movable assets and integration of data from motor vehicle and company registries CAF/WB/CS/0 Capacity 50 IC Yes Post 9 Jan 23 6 Feb 23 27 Feb 23 28 Feb 23 31 Aug 8 Building of 2023 financial institutions and MSME`s to utilise asset-based lending CAF/WB/CS/0 TA to Post 150 CQS Yes Post 9 Jan 23 6 Feb 23 27 Feb 23 28 Feb 23 31 Aug 9 Bank for 2023 development of business case for agricultural value chain finance, including market assessment 67 | P a g e and financing methodology CAF/WB/CS/1 Design and 200 CQS Yes Post 23 Jan 20 Feb 13 March 20 March 29 Sept 0 implementati 2023 2023 2023 2023 2023 on of a management information system (MIS) to support value-chain financing CAF/WB/CS/1 Review and 50 IC Yes Post 23 Jan 20 Feb 13 March 20 March 29 Sept 1 improve 2023 2023 2023 2023 2023 governance, institutional and operational features of the L-PCG CAF/WB/CS/1 Develop a 150 CQS Yes Post 23 Jan 20 Feb 13 March 20 March 20 March 2 business 2023 2023 2023 2023 2023 case and financial model for portfolio guarantees CAF/WB/CS/1 Design and 2000 QCBS Yes Prior 23 Jan 20 Feb 13 March 20 March 20 March 3 implement 2023 2023 2023 2023 2023 the portfolio guarantee scheme including development of supporting documentati 68 | P a g e on and systems CAF/WB/CS/1 Capacity 100 CQS Yes Post 23 Jan 20 Feb 13 March 20 March 20 March 4 Building 2023 2023 2023 2023 2023 Sub-Component 1.3: Strengthening the Resilience of MSMEs to Climatic Shocks CAF/WB/CS/1 TA on 750 QCBS Yes Prior 23 Jan 20 Feb 13 Mar 20 Mar 29 Sept 5 disaster risk 2023 2023 2023 2023 financing including drafting of National Disaster Risk Finance Policy for MoF CAF/WB/CS/1 Design and 300 QCBS Yes Post 23 Jan 20 Feb 13 Mar 20 Mar 2023 29 Sept 6 development 2023 2023 2023 2023 of a database for informal MSMEs and integrate the database into the existing business registry CAF/WB/CS/1 TA on design 150 CQS Yes Post 23 Jan 20 Feb 13 Mar 20 Mar 2023 29 Sept 7 and 2023 2023 2023 2023 procurement of sovereign insurance backstop and co- 69 | P a g e financing of insurance premiums CAF/WB/CS/1 Draft 75 CQS Yes Post 23 Jan 20 Feb 13 Mar 20 Mar 29 Sept 8 regulations 2023 2023 2023 2023 to govern the operational activities of the existing MoF Contingency Fund Sub-Component 2.1- Establishing an Entrepreneurship Hub and Seed Financing Facility CAF/WB/CS/1 Procure a 500 QCBS Yes Prior 9 Jan 3 Feb 27 Feb 28 Feb 2023 31 Aug 23 9 private 2023 2023 2023 Sector operator to support establishmen t of a sustainable entrepreneur ship Hub within the Tourism Information centre CAF/WB/CS/2 Design and 150 CQS Yes Post 23 Jan 20 Feb 13 Mar 20 Mar 29 Sept 0 development 2023 2023 2023 2023 of an incubation support program 70 | P a g e CAF/WB/CS/2 Facilitate the 50 IC Yes Post 23 Jan 20 Feb 13 Mar 20 Mar 29 Sept 1 integration of 2023 2023 2023 2023 the Lesotho Start-up Community within a wider regional Entrepreneur ship ecosystem CAF/WB/CS/2 Procure a 250 CQS Yes Post 9 Jan 3 Feb 27 Feb 28 Feb 2023 31 Aug 23 2 private 2023 2023 2023 operator to establish and manage a seed financing facility and an associated acceleration program Procure a 300 QCBS Yes Post 9 Jan 2023 6 Feb 27 Feb 28 Feb 2023 31 May CAF/WB/CS/2 private 2023 2023 2023 3 sector service provider to augment the delivery capacity of LEAP PMU Sub-Component 2.3-Expanding SME Participation in High Potential Value Chains 71 | P a g e CAF/WB/CS/2 TA to set a 350 CQBS Yes Post 10 Oct 23 15 Nov 23 29 Nov 23 2 Dec 23 17 Dec 23 4 Horticulture Incubation Hub 9. Contract Management Plan (CMP) As the project at hand (CAFI) doesn’t involve any high value and complex contract, the Contract Management Plan (CMP) being outlined below may not need to be applied fully. However, the basic ones that would help the CMU manage its contracts (Works, Goods, Non-Consultancy Services or Consultancy services) with better efficiency to achieve its intended objectives may be adopted. The primary objective of any CMP is achievement of designed quality, agreed delivery timelines and perform within the contract ceiling amount. Assuring sustainability objectives in terms of environmental, social, and economic compliance are also sustainability dimension to be achieved through appropriate and proportional CMP. The Key contract management tools are all around establishing clear communication lines and having defined roles and responsibilities in the contract implementations. Each contractual parties defined accountability and Decision-making process must be communicated to the other party. The below templates may be used as found fit to each contract context. Sample Contract Management Plan 1.CONTACTS, ROLES AND RESPONSIBILITIES Roles and Organization Name and Title Contact Information (email, tel, address) Responsibilities PE Contract Manager Contractor Contractor’s representative: Consultant Engineer 72 | P a g e 2.COMMUNICATION AND REPORTING PROCEDURE Communication Procedures Communication Objective Format Frequency Audience Owner Type Contractual Notices Descriptions Objective Contract Frequency/ From to Reference Timing Contractor’s documents Descriptions Objective Contract Reference 73 | P a g e Reporting Requirement and Procedure No. Contract Ref. Due date/ Recipients Responsibilities Required Action Clause frequency [Progress [Monthly] Report] [ESHS Progress [Monthly] reports] [ESHS [immediately after immediate occurrence of event reports] Test results Issues Escalation Procedure Nature of Level of Responsible Response Type of issue Issue review body time Low or Routine Medium High Critical 3.KEY CONTRACTUAL PROVISIONS 74 | P a g e No. Description Contract Responsible Remark Risks reference 1. Care and Procuring 2 copies issued Supply of Entity to contractor Documents 2. Delayed Procuring Time extension Drawings or Entity cost compensation Instructions 3. Right of Access Procuring Give right of to the Site Entity access within time stated in data sheet. 4. 4.CONTRACTUAL MILESTONES AND DELIVERABLES Contract Start End Activity / Milestone Responsible Remark Reference date date Submit work Contractor schedule Foundation work for Contractor Critical path section… Complete structure Contractor for … Pilot testing for … 5.KEY PERFORMANCE INDICATORS (to MEASURE PERFORMANCE AND OUTCOMES) No. Deliverable KPI Performance Test Verification Remark target 1. 2. 3. 75 | P a g e 6.UNDERPERFORMANCE/DEFAULT CONTRACTUAL ACTIONS No. Description of Responsible Applicable Actions Remark underperformance contractual to be provision/s taken 1. 2. 3. 7.CHANGE MANAGEMENT PROCESS No. Change Type of Responsible Required Review/ Contract Status initiated change Action Approval Amendment by Process Requirement 1. Procuring Change in Procuring Inform Entity authority of Entity Contractor the of any Engineer change 2. Procuring Change in Engineer Entity scope of work 3. 8.INSURANCE Contract Amount / Information Required Required Expiry No Type of Insurance Ref. Limit of Date date liability 1. 2. 3. 9.GUARANTEES AND SECURITIES 76 | P a g e Type of Contrac Amount / Expir Information Required Require No Guarantee / t Ref. Limit of y d Date Security liability date 1. [Advance Payment Guarantee] 2. [Performance Security] 3. [ESHS Performance Security] 4. [Retention Guarantee] 77 | P a g e 10.PAYMENT PLAN /PROCEDURES N Type of Whe Documents Required Process Verification Approvals o Payment n/ time process . freq uenc y 1 Advance Once Advance payment . payment Guarantee 2 Interim Ever Interim payment . payments y certificates, timesheets, mont proof of incurred h expenditure, shipping documents etc. 3 Interest Dela . payments yed pay ment s 4 Price - . adjustme nt 5 Claims/ As Contractors . Compens need ation ed 6 Final . Payment 11.RECORDS MANAGMENT No. Type of Record Owner Responsible Action Remark required 1. [Contract documents and any amendments/] 78 | P a g e No. Type of Record Owner Responsible Action Remark required 2. Insurance details 3. [change orders] 4. [notices] 5. [Payment Documents, including documents on application of price adjustment if any] 6. Minutes of contract related meetings 7. [Progress Reports] 8. [immediate Reports on ESHS, if applicable] 9. [Test Results] 10. [Guarantees, warranty/defect liability and Securities] 11. Documents related to any suspension or termination 12.KEY STAKEHOLDERS ENGAGEMENT PLAN No. Stakeholder Format Frequency Remark 1. 2. 3. 13.CONTRACT CLOSURE PROCEDURES No. Activity Responsible Remark 1. 2. 3. 14.PRICE ADJUSTMENT PROCEDURES 79 | P a g e No. Activity Responsible Remark 1. e.g., verification of indices 2. 3. 15.INTERFACE MANAGEMENT No. Activity Responsible Remark 1. 2. 3. 80 | P a g e PROCUREMENT Lesotho : Lesotho Competitiveness and Financial Inclusion Project PLAN General Information Country: Lesotho 2022-10-06 Bank’s Approval Date of the Original Procurement Plan: 2023-06-07 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P175783 GPN Date: Project Name: Lesotho Competitiveness and Financial Inclusion Project Loan / Credit No: IDA / 71690 Ministry of Trade and Industry Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Request for Quota LS-MTI-369383-CW-RFQ / Re Scaling Support for Entrepre Request for Quota Single Stage - One E tions - Small Work Pending Imp 2024-03-2 furbishment of Horticulture I IDA / 71690 Post Limited 130,000.00 0.00 2023-08-05 2023-09-30 neurship and MSMEs tions nvelope s (Emergency) SP lementation 8 ncubation Hub D -Competitive GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual LS-MTI-334917-GO-RFQ / Su Project Management and Im Request for Quota Single Stage - One E pply and Delivery of Three (3 IDA / 71690 Post Limited 20,000.00 0.00 Canceled 2023-01-11 2023-01-04 2023-03-08 2023-09-04 plementation Support tions nvelope ) colour printers for Project M anagement Unit LS-MTI-347213-GO-RFQ / Su Project Management and Im Request for Quota Single Stage - One E pply and delivery of 3 colour IDA / 71690 Post Limited 11,000.00 0.00 Canceled 2023-03-08 2023-05-03 2023-10-30 plementation Support tions nvelope printers for the project mana gement unit NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual LS-MTI-344493-NC-DIR / Eng agement of Comnet (PTY)Ltd Project Management and Im IDA / 71690 Post Direct Selection Direct - National 13,000.00 0.00 Signed 2023-02-21 2023-02-01 2023-02-26 2023-02-01 2023-04-02 2023-09-29 for provision of ICT equipmen plementation Support t maintenance and repair LS-MTI-344436-NC-RFQ / Pro vision of Office Space for Ent Scaling Support for Entrepre Single Stage - One E IDA / 71690 Post Request for Bids Limited 204,564.00 0.00 Canceled 2023-03-07 2023-03-12 2023-04-23 2023-05-23 2023-06-27 2023-12-24 repreneurship Hub and Seed neurship and MSMEs nvelope Financing Facility for 3 years LS-MTI-353680-NC-RFQ / Pro vision of office space for the Scaling Support for Entrepre Request for Quota Single Stage - One E IDA / 71690 Post Limited 137,000.00 0.00 Signed 2023-04-03 2023-02-06 2023-05-29 2023-11-25 Entrepreneurship Hub and Se neurship and MSMEs tions nvelope ed Financing Facility for 24 M onths LS-MTI-355099-NC-DIR / Pro vision of Lesotho National Sin Enhancing Financial Inclusio Direct - Internation IDA / 71690 Post Direct Selection 83,000.00 0.00 Signed 2023-04-06 2023-04-11 2023-04-21 2023-04-11 2023-06-02 2023-11-29 gle Window (LNSW) Cloud Ho n and Resilience of MSMEs al sting Services for 12 Months CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual LS-MTI-326389-CS-CQS / Eng Project Management and Im Consultant Qualifi Under Implement agement of a Communicatio IDA / 71690 Post Open - National 30,000.00 0.00 2022-11-14 2022-11-01 2022-12-05 2022-11-23 2023-01-18 2023-03-01 2023-02-17 2023-03-24 2023-09-20 plementation Support cation Selection ation ns Firm to support CAFI LS-MTI-327844-CS-CQS / Des Scaling Support for Entrepre Consultant Qualifi Under Implement IDA / 71690 Post Open - National 50,000.00 0.00 2022-11-22 2023-01-03 2022-12-13 2023-01-20 2023-01-26 2023-03-01 2023-02-25 2023-04-01 2023-09-28 ign and Development of LEAP neurship and MSMEs cation Selection ation Website LS-MTI-327989-CS-CQS / De Enhancing Financial Inclusio Consultant Qualifi Open - Internationa velopment of New Financial P IDA / 71690 Post 80,000.00 0.00 Canceled 2022-11-23 2022-12-14 2023-01-27 2023-02-26 2023-04-02 2023-09-29 n and Resilience of MSMEs cation Selection l roducts for Post Bank LS-MTI-327991-CS-CQS / Str Enhancing Financial Inclusio Consultant Qualifi Open - Internationa engthening the Credit Infrast IDA / 71690 Post 100,000.00 0.00 Canceled 2022-11-23 2022-12-01 2022-12-14 2023-01-12 2023-01-27 2023-02-26 2023-04-02 2023-09-29 n and Resilience of MSMEs cation Selection l ructure System for Central B ank LS-MTI-327996-CS-CQS / Eng Scaling Support for Entrepre Consultant Qualifi agement of Technical Adviso IDA / 71690 Post Limited 100,000.00 0.00 Canceled 2022-11-30 2022-12-01 2022-12-14 2023-01-13 2023-02-17 2023-08-16 neurship and MSMEs cation Selection r for MTI/BDT re-organization INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual LS-MTI-317459-CS-CDS / Pro vision of Consultancy service Scaling Support for Entrepre Direct - Internation Under Implement s by ILO "Lesotho Textiles an IDA / 71690 Prior Direct Selection 4,300,000.00 0.00 2022-09-23 2022-11-08 2022-10-03 2022-12-07 2023-06-05 neurship and MSMEs al ation d clothing Global Value Chain Technical Assistance Progra m LS-MTI-319844-CS-INDV / Co Scaling Support for Entrepre Individual Consult Open - Internationa nsultancy for Entrepreneursh IDA / 71690 Post 240,000.00 0.00 Signed 2022-10-06 2022-10-12 2022-11-24 2023-02-01 2022-12-15 2023-01-31 2023-01-19 2023-07-18 neurship and MSMEs ant Selection l ip Hub Manager for 24 month s Page 1 LS-MTI-319846-CS-CDS / Eng Project Management and Im agement of a Project Manage IDA / 71690 Post Direct Selection Direct - National 698,489.63 0.00 Signed 2022-10-17 2022-11-01 2022-10-27 2022-11-01 2022-12-31 2023-06-29 plementation Support r for the CAFI Project for a Pe riod of 6 years LS-MTI-319870-CS-CDS / Eng Project Management and Im agement of the Finance Man IDA / 71690 Post Direct Selection Direct - National 396,742.55 0.00 Signed 2022-10-17 2022-11-01 2022-10-27 2022-11-01 2022-12-31 2023-06-29 plementation Support ager for 6 years LS-MTI-319914-CS-CDS / Eng Project Management and Im agement of the Project Accou IDA / 71690 Post Direct Selection Direct - National 194,535.04 0.00 Signed 2022-10-17 2022-11-01 2022-10-27 2022-11-01 2022-12-31 2023-06-29 plementation Support ntant for 6 years LS-MTI-319862-CS-CDS / Eng Project Management and Im agement of the Deputy Proje IDA / 71690 Post Direct Selection Direct - National 457,658.37 0.00 Signed 2022-10-17 2022-11-01 2022-10-27 2022-11-01 2022-12-31 2023-06-29 plementation Support ct Manager for 6 years LS-MTI-319940-CS-CDS / Eng Project Management and Im agement of the Procurement IDA / 71690 Post Direct Selection Direct - National 32,982.39 0.00 Signed 2022-10-17 2022-11-01 2022-10-27 2022-11-01 2022-12-31 2023-06-29 plementation Support Officer for 12 Months LS-MTI-319942-CS-CDS / Eng Project Management and Im agement of the Receptionist/ IDA / 71690 Post Direct Selection Direct - National 21,433.28 0.00 Signed 2022-10-17 2022-11-01 2022-10-27 2022-11-01 2022-12-31 2023-06-29 plementation Support IT Support for 12 Months LS-MTI-319881-CS-CDS / Eng Project Management and Im agement of the Entrepreneur IDA / 71690 Post Direct Selection Direct - National 320,662.11 0.00 Signed 2022-10-17 2022-11-01 2022-10-27 2022-11-01 2022-12-31 2023-06-29 plementation Support ship Manager for the period o f 6 years LS-MTI-319921-CS-CDS / Eng Project Management and Im agement of the Office Assista IDA / 71690 Post Direct Selection Direct - National 37,410.61 0.00 Signed 2022-10-17 2022-11-01 2022-10-27 2022-11-01 2022-12-31 2023-06-29 plementation Support nt for 6 years LS-MTI-319951-CS-CDS / Eng Project Management and Im agement of the Project Accou IDA / 71690 Post Direct Selection Direct - National 32,982.39 0.00 Signed 2022-10-17 2022-11-01 2022-10-27 2022-11-01 2022-12-31 2023-06-29 plementation Support ntant for 12 Months LS-MTI-319937-CS-CDS / Eng Project Management and Im agement of the Administrativ IDA / 71690 Post Direct Selection Direct - National 33,087.41 0.00 Signed 2022-10-17 2022-11-01 2022-10-27 2022-11-01 2022-12-31 2023-06-29 plementation Support e Secretary for 12 Months LS-MTI-319890-CS-CDS / Eng Project Management and Im agement of the Procurement IDA / 71690 Post Direct Selection Direct - National 48,862.00 0.00 Signed 2022-10-17 2022-11-01 2022-10-27 2022-11-01 2022-12-31 2023-06-29 plementation Support Manager for 1 year LS-MTI-319947-CS-CDS / Eng Project Management and Im agement of the LEAP Officer f IDA / 71690 Post Direct Selection Direct - National 30,539.25 0.00 Signed 2022-10-17 2022-11-01 2022-10-27 2022-11-01 2022-12-31 2023-06-29 plementation Support or 12 Months LS-MTI-319948-CS-CDS / Eng Project Management and Im agement of the Project Drive IDA / 71690 Post Direct Selection Direct - National 53,443.69 0.00 Signed 2022-10-17 2022-11-01 2022-10-27 2022-11-01 2022-12-31 2023-06-29 plementation Support r for 6 years LS-MTI-326558-CS-INDV / En Project Management and Im Individual Consult Under Implement gagement of the LEAP Officer IDA / 71690 Post Open - National 30,539.25 0.00 2022-11-15 2022-11-22 2023-01-03 2023-01-24 2023-02-28 2023-08-27 plementation Support ant Selection ation 2 for the Project for 1 year LS-MTI-326560-CS-INDV / En gagement of the Monitoring Project Management and Im Individual Consult IDA / 71690 Post Open - National 55,000.00 0.00 Canceled 2022-11-15 2022-11-22 2023-01-03 2023-01-24 2023-02-28 2023-08-27 and Evaluation Specialist for plementation Support ant Selection CAFI Project for 1 year LS-MTI-326562-CS-INDV / En gagement of the Social and E Project Management and Im Individual Consult IDA / 71690 Post Open - National 55,000.00 0.00 Signed 2022-11-15 2022-11-22 2023-01-03 2023-01-13 2023-01-24 2023-01-31 2023-02-28 2023-08-27 nvironmental Safeguards Spe plementation Support ant Selection cialist for CAFI Project for 1 y ear LS-MTI-326566-CS-INDV / En Project Management and Im Individual Consult gagement of Deputy Project IDA / 71690 Post Open - National 76,000.00 0.00 Signed 2022-11-15 2022-11-22 2023-01-03 2023-01-27 2023-01-24 2023-01-23 2023-02-28 2023-08-27 plementation Support ant Selection Manager Operations for CAFI Project for 1 year LS-MTI-326568-CS-INDV / En Project Management and Im Individual Consult gagement of the Executive A IDA / 71690 Post Open - National 33,087.41 0.00 Canceled 2022-11-15 2022-11-22 2023-01-03 2023-01-31 2023-01-24 2023-02-28 2023-08-27 plementation Support ant Selection ssistant for CAFI Project for 1 year LS-MTI-326594-CS-INDV / En Enhancing Financial Inclusio Individual Consult gagement of MSME Resilienc IDA / 71690 Post Open - National 52,000.00 0.00 Canceled 2022-11-15 2022-11-22 2023-01-03 2023-03-10 2023-01-24 2023-03-15 2023-02-28 2023-08-27 n and Resilience of MSMEs ant Selection e Coordinator for 1 year LS-MTI-327692-CS-INDV / En Enhancing Financial Inclusio Individual Consult Open - Internationa gagement of Trade Facilitatio IDA / 71690 Post 100,000.00 0.00 Signed 2022-11-22 2023-01-03 2023-01-10 2023-01-18 2023-01-31 2023-01-23 2023-03-07 2023-09-03 n and Resilience of MSMEs ant Selection l n Expert for 18 Months LS-MTI-330598-CS-INDV / En Scaling Support for Entrepre Individual Consult gagement of the Horticulture IDA / 71690 Post Open - National 52,000.00 0.00 Signed 2022-12-07 2022-12-01 2023-01-25 2023-03-16 2023-02-15 2023-03-15 2023-03-22 2023-09-18 neurship and MSMEs ant Selection Coordinator for a period of 1 2 Months LS-MTI-330602-CS-INDV / En Scaling Support for Entrepre Individual Consult Under Implement gagement of Incubation Hub IDA / 71690 Post Open - National 52,000.00 0.00 2022-12-07 2022-12-01 2023-01-25 2023-02-15 2023-03-22 2023-09-18 neurship and MSMEs ant Selection ation Manager for 12 Months LS-MTI-331150-CS-CDS / Eng agement of Horticulture Infra Scaling Support for Entrepre IDA / 71690 Post Direct Selection Direct - National 7,000.00 0.00 Signed 2022-12-12 2022-12-01 2022-12-22 2023-01-02 2023-02-25 2023-08-24 structure Technician 2 for a p neurship and MSMEs eriod of 12 Months. LS-MTI-331153-CS-CDS / Eng Scaling Support for Entrepre agement of Horticulture Infra IDA / 71690 Post Direct Selection Direct - National 7,000.00 0.00 Signed 2022-12-12 2022-12-01 2022-12-22 2023-01-02 2023-02-25 2023-08-24 neurship and MSMEs structure Technician 1 for 12 Months LS-MTI-331168-CS-CDS / Eng Scaling Support for Entrepre agement of Horticulture Tech IDA / 71690 Post Direct Selection Direct - National 32,000.00 0.00 Signed 2022-12-12 2023-01-03 2022-12-22 2023-01-02 2023-02-25 2023-08-24 neurship and MSMEs nical Field Manager for 12 Mo nths LS-MTI-331185-CS-CDS / Eng Scaling Support for Entrepre agement of the Horticulture IDA / 71690 Post Direct Selection Direct - National 50,000.00 0.00 Canceled 2022-12-12 2022-12-01 2022-12-22 2023-02-25 2023-08-24 neurship and MSMEs Field Technical Advisor for 12 Months Page 2 LS-MTI-334909-CS-INDV / En Scaling Support for Entrepre Individual Consult gagement of Horticulture Tec IDA / 71690 Post Open - National 28,000.00 0.00 Signed 2023-01-12 2023-01-09 2023-03-02 2023-03-01 2023-03-23 2023-03-15 2023-04-27 2023-10-24 neurship and MSMEs ant Selection hnical Advisor for 12 Months LS-MTI-344470-CS-CDS / Inst Project Management and Im Direct - Internation allation of Financial Manage IDA / 71690 Post Direct Selection 40,000.00 0.00 Signed 2023-02-21 2023-02-01 2023-03-03 2023-01-31 2023-05-07 2023-11-03 plementation Support al ment System, TOMPRO LS-MTI-356459-CS-INDV / En Project Management and Im Individual Consult Under Implement gagement of MSME Resilienc IDA / 71690 Post Open - National 45,000.00 0.00 2023-04-17 2023-04-12 2023-06-05 2023-06-26 2023-07-31 2024-01-27 plementation Support ant Selection ation e Coordinator for 12 months LS-MTI-360353-CS-CDS / Eng Scaling Support for Entrepre Direct - Internation agement of Textile and Appa IDA / 71690 Post Direct Selection 150,000.00 0.00 Signed 2023-05-08 2023-05-05 2023-05-18 2023-05-09 2023-07-22 2024-01-18 neurship and MSMEs al rel Senior Advisor for 24 Mon ths LS-MTI-364387-CS-INDV / En gagement of Senior Expert to Enhancing Financial Inclusio Individual Consult Open - Internationa Under Implement IDA / 71690 Post 100,000.00 0.00 2023-06-06 2023-06-09 2023-07-25 2023-08-15 2023-09-19 2024-03-17 review and reform Credit Gu n and Resilience of MSMEs ant Selection l ation arantee Scheme for 45 days LS-MTI-366101-CS-INDV / En gagement of Deputy Progra Scaling Support for Entrepre Individual Consult Under Implement mme Manager-Entrepreneurs IDA / 71690 Post Open - National 94,000.00 0.00 2023-06-30 2023-06-09 2023-08-18 2023-09-08 2023-10-13 2024-04-10 neurship and MSMEs ant Selection ation hip Hub and Seed Financing Facility for a period of 24 Mo nths LS-MTI-366106-CS-INDV / En gagement of the Grants Adm Scaling Support for Entrepre Individual Consult Under Implement inistrator for Entrepreneurshi IDA / 71690 Post Open - National 40,000.00 0.00 2023-06-30 2023-06-09 2023-08-18 2023-09-08 2023-10-13 2024-04-10 neurship and MSMEs ant Selection ation p Hub and Seed Financing Fa cility for a period of 24 Month s LS-MTI-366112-CS-INDV / En gagement of the Executive A Scaling Support for Entrepre Individual Consult Under Implement ssistant for Entrepreneurship IDA / 71690 Post Open - National 40,000.00 0.00 2023-06-30 2023-06-09 2023-08-18 2023-09-08 2023-10-13 2024-04-10 neurship and MSMEs ant Selection ation Hub and Seed Financing Facil ity for a period of 24 Months LS-MTI-366363-CS-INDV / En gagement of the Financial Se Enhancing Financial Inclusio Individual Consult Open - Internationa Under Implement IDA / 71690 Post 45,000.00 0.00 2023-06-30 2023-06-13 2023-08-18 2023-09-08 2023-10-13 2024-04-10 ctor Specialist for Strengthen n and Resilience of MSMEs ant Selection l ation ing the Credit Infrastructure System for 12 Weeks LS-MTI-367031-CS-INDV / En gagement of a legal Consulta Enhancing Financial Inclusio Individual Consult Under Implement nt for Central Bank to suppor IDA / 71690 Post Open - National 40,000.00 0.00 2023-06-30 2023-06-15 2023-08-18 2023-09-08 2023-10-13 2024-04-10 n and Resilience of MSMEs ant Selection ation t the strengthening of the Cr edit Infrastructure System for 12 weeks Page 3 18-MONTH PROCUREMENT PLAN Project information: Nigeria Rural Access And Agricultural Marketing Project (RAAMP) - P163353 Project Implementation Agencies: Federal Ministry of Agriculture and Rural Development and State Project Implementation Units (SPIUs) Date of the Procurement Plan: September 18, 2019 Period covered by this Procurement Plan: February 2019 to July 2020 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the Nigeria Public Procurement Act 2007, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. Not Applicable Procurement of Second-Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables. Not Applicable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: [15% is applicable for those contracts identified in the Procurement Plan tables]; Works: [ 7.5% is applicable for those contracts identified in the Procurement Plan tables] I. Threshold for Prior Review – Goods, Works, Non-Consulting Services and Consulting Services Prior-review Thresholds Thresholds for Procurement Methods High Substanti Moderate Low Risk Goods, IT & Non-Consulting Shortlist of National Procurement Type Risk al Risk Risk Works ($'000) ($'000) ($'000) ($'000) Services Consultants Request Request Engineering Open for for Open Open Open Consultin & Quotatio Quotatio 10,0 15,0 20,0 Internatio National internatio National g Constructio Works n or n or 5,000 00 00 00 nal or ICB or NCB National nal or ICB or NCB National Services n ($'000) ($'000) ($'000) ($'000) ($'000) Supervision Shopping Shopping ($'000) ($'000) ($'000) Goods, IT & Non- 2,0 4,0 6,0 Consulting Services 1,500 00 00 00 ≧ < ≦ ≧ < ≦ < ≦ Consultants 1,0 2,0 4,0 20,0 20,0 5,0 5,0 1 3 5 200 (Firms) 500 00 00 00 00 00 00 00 00 00 00 Post Review: All contracts not subject to prior review shall be subject to post review. Summary of the procurement packages for Goods, Works and Non-Consulting Services (Planned for the first 18 months after project effectiveness): Selecti Market on Evaluation Approa Review Metho Options Expected ch Prequal- Domestic Expected by Estimat d (Most date of Sr. Contract (Open- ification Preferenc date of Bank ed Cost (RFP, Advantageou bid/ No Description Nation (Yes/ e Contract (Prior/ (US$) RFB, s Bid, BAFO, proposal al/ No) (Yes/No) Signature Post) RFQ, Rated Criteria opening Limited DS etc.) etc.) etc.) Procurement of Air Conditioners 2 Limited Lowest March. 1 Post 24,600 RFQ No No Feb. 2020 Horse power Evaluated Cost 2020 (Split Unit) (Goods) Procurement of Steel File cabinets, Lowest March. 2 Spiral Binding Post 12,600 Limited RFQ Evaluated Cost No No Feb. 2020 2020 Machines and Consumables (Goods) Procurement of External hard disk + software packages Lowest March. 3 (licensed MS Post 12,300 Limited RFQ Evaluated Cost No No 2020 April. 2020 Office, Autocads, Antivirus, Converter etc) (Goods) Procurement of Laptops and Lowest March. 4 Post 100,000 Limited RFQ No No May. 2020 Tablets Evaluated Cost 2020 (Goods) Procurement Lowest March. 5 Post 22,400 Limited RFQ No No April. 2020 of Evaluated Cost 2020 Photocopying Machines (Goods) Medium Sized Lowest March. 6 Refrigerators Post 10,800 Limited RFQ Evaluated Cost No No 2020 April. 2020 (Goods) Procurement of Safety Equipment (Boots, Lowest 7 Post 39,000 Limited RFQ No No June. 2020 July, 2020 Helmets, Evaluated Cost Reflective Jackets etc.) (Goods) Construction Measuring Manual Wheel Lowest August. 8 Post 6,500 Limited RFQ No No July 2020 (Surveyor’s Evaluated Cost 2020 Wheel) (Goods) Roads Maintenance Equipment for Community based road maintenance (30 Nos tipping tricycles and other Open- 1,235,0 Lowest 9 equipment Post Nationa RFB No No Sept. 2020 Dec. 2020 00 Evaluated Cost such roads l signs and; cutlasses, wheelbarrows, hand rammer, digger, helmet, watering cans, reflective jacket, long shovel, nose cover, boots etc) (Goods) Procurement of Office Equipment, Printers, Open- Digital Lowest August. 10 Post 420,000 Nationa RFB No No June. 2020 Cameras & Evaluated Cost 2020 l Sundry Communicatio n devices (Goods) Purchase of Open- Project 2,940,0 Lowest March. 11 Prior Nationa RFB No No May. 2020 Vehicles 00 Evaluated Cost 2020 l (Goods) Server, Network System and other Open- Lowest equipment & Post 150,000 Nationa RFB Evaluated Cost No No Feb. 2020 May. 2020 accessories for l NiRTIMS and CosMos (Goods) Design and Construction of 200km of Rural Roads Open- 134,000 Rated Criteria (13 Prior Interna RFP No No Jun. 2020 Dec. 2020 ,000.00 and Cost Contracts of tional US$10.3 Million each) (Works) Construction/E stablishment Open – of Agro- 2,000,0 Lowest March. Post Nationa RFB No No July. 2021 Logistics 00 Evaluated Cost 2021 l centers/hubs at strategic locations (Multiple contracts) (Works) Construction /Rehabilitation of 10 Nos. Rural Bridges Open- 8,000,0 Lowest March. & Large Post Nationa RFB No No July. 2022 00 Evaluated Cost 2021 culverts (US$ l 0.6 M each Package) (Works) Local Community Group (LCG) and micro- enterprises maintenance Open- 14,000, Lowest of pilot roads Post Nationa RFB No No April. 2020 June.2020 000 Evaluated Cost (Multiple l Contracts in 13 States - US$ 0.002/year) (Works) II. Summary of the procurement packages for Consulting Services -Planned for the first 18 months after project effectiveness): Selection Market Method Review Approach Expected Expected Estimate (QCBS, Shortlisti Sr. by Bank (Open - date of bid/ date of Contract Description d Cost FBS, ng No (Prior/ International proposal Contract (US$) LCBS, (Yes/ No) Post) / National/ opening Signature QBS, CQS, etc.) DS etc.) Offshore & Onshore training and Workshops for Open- March. 1 the 13 states (Multiple Post 5,200,000 CQS No May. 2020 National 2020 contracts not to exceed US$ 0.1 M) (Consultancy) Consultancy Services for Detailed assessment, preliminary engineering design, ESIA, Procurement Support for Rural roads and Bridges; Road and 25,390,00 Open- 2 Bridge Supervision Prior QCBS Yes June. 2020 Nov. 2020 0 International Consultancy; Assessment of project security risk and mitigation (Multiple contracts spread in different locations) (Consultancy) Consultancy Services for design, procurement and supervision for Agro- Open- 3 logistics centers (Multiple Post 6,500,000 QCBS Yes Sep. 2020 Dec. 2020 International contracts spread in different locations) (Consultancy) Consultancy Services for the establishment of state Open- March. August. 4 road fund, and Post 5,665,000 QCBS Yes National 2020 2020 establishment of state rural access roads administration (Multiple contracts at 13 states) (Consultancy) Consultancy services on the development and operationalization of the Nigeria Rural Transport Infrastructure Management System (NiRTIMS) for sustainable road asset; Planning and Open- 5 Post 5,860,000 QCBS Yes Feb. 2020 July. 2020 implementation of the National routine maintenance system, spot improvement, periodic maintenance for rural roads. (Multiple contracts at 13 states) (Consultancy) Technical assistance consultancy services for the provision of technical advice (TA) to enhance the performance of agro- logistics centers (to ensure effective utilization of the facilities at the agro- Open- National March. 6 logistics centers); Post 4,975,000 QCBS Yes July. 2020 provision of TA and 2020 implements to farm level post-harvest agro-logistics activities and enhance the engagement of women and unemployed youth. (Multiple contracts at 13 states) (Consultancy) Consultancy services support for coordination of Open- 7 Post 2,442,000 CQS No Feb. 2020 April. 2020 project implementation at National Federal and State Levels (Multiple contracts at 13 states) (Consultancy) Consultancy services on Impact Evaluation, Baseline Data Collection, Comprehensive Technical Audit, Consultancy support for the development and Open- March. 8 operationalization of the Post 5,325,000 QCBS Yes July.2020 National 2020 smartphone-based construction site monitoring system (CoSMoS) (Multiple contracts at 13 states) (Consultancy) Consultancy support for the development and monitoring of Grievance Redress Mechanism and Gender-Based Violence; Development of road safety manual and training Open- 9 Post 1,843,000 CQS No April.2020 June. 2020 at the state level; National establishment/strengtheni ng the state traffic management agencies; road safety audit. (Multiple contracts at 13 states) (Consultancy) Appendix 1 Letter of Acceptance of the World Bank’s Anti-Corruption Guidelines and Sanctions Framework Date: Invitation of Bids/Proposals No.__________ To: ___________________________________________________________________________ We, along with our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not) consultants and personnel, acknowledge and agree to abide by the World Bank’s policy regarding Fraud and Corruption (corrupt, fraudulent, collusive, coercive, and obstructive practices), as set out and defined in the World Bank’s Anti-Corruption Guidelines1 in connection with the procurement and execution of the contract (in case of award), including any amendments thereto. We declare and warrant that we, along our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not), consultants and personnel, , are not subject to, and are not controlled by any entity or individual that is subject to, a temporary suspension, early temporary suspension, or debarment imposed by a member of the World Bank Group, including, inter alia, a cross-debarment imposed by the World Bank Group as agreed with other international financial institutions (including multilateral development banks), or through the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement. Further, we are not ineligible under the laws or official regulations of [Insert name of Employer as per bidding document] or pursuant to a decision of the United Nations Security Council. We confirm our understanding of the consequences of not complying with the World Bank’s Anti-Corruption Guidelines, which may include the following: a. rejection of our Proposal/Bid for award of contract; b. in the case of award, termination of the contract, without prejudice to any other remedy for breach of contract; and c. sanctions, pursuant to the Bank’s Anti-corruption Guidelines and in accordance with its prevailing sanctions policies and procedures as set forth in the Bank’s Sanctions Framework. This may include a 1Guidelineson Preventing and Combating Fraud and Corruption in Projects Financed by International Bank for Reconstruction and Development Loans and the International Development Agency Credits and Grants, dated October 15, 2006, and revised in January 2011 and July 2016, as they may be revised from time to time. public declaration of ineligibility, either indefinitely or for a stated period of time, (i) to be awarded or otherwise benefit from a Bank-financed contract, financially or in any other manner;2 (ii) to be a nominated3 sub-contractor, consultant, manufacturer or supplier, or service provider of an otherwise eligible firm being awarded a Bank-financed contract; and (iii) to receive the proceeds of any loan made by the Bank or otherwise to participate further in the preparation or implementation of any Bank-financed project. We understand that we may be declared ineligible as set out above upon: a. completion of World Bank Group sanctions proceedings according to its prevailing sanctions procedures; b. cross-debarment as agreed with other international financial institutions (including multilateral development banks); c. the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement; or d. temporary suspension or early temporary suspension in connection with an ongoing World Bank Group sanctions proceeding. For avoidance of doubt, the foregoing effects of ineligibility do not extend to a sanctioned firm’s or individual’s execution of its ongoing Bank-financed contracts (or its ongoing sub-agreements under such contracts) that are not the subject of a material modification, as determined by the Bank. We shall permit, and shall cause our sub-contractors, sub-consultants, agents (whether declared or not), personnel, consultants, service providers or suppliers, to permit the Bank to inspect4 all accounts, records, 2 For the avoidance of doubt, a sanctioned party’s ineligibility to be awarded a contract shall include, without limitation, (i) applying for pre-qualification, expressing interest in a consultancy, and bidding, either directly or as a nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider, in respect of such contract, and (ii) entering into an addendum or amendment introducing a material modification to any existing contract. 3 A nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider (different names are used depending on the particular bidding document) is one which has been: (i) included by the bidder in its pre-qualification application or bid because it brings specific and critical experience and know-how that allow the bidder to meet the qualification requirements for the particular bid; or (ii) appointed by the Borrower. 4 Inspections in this context are usually investigative (i.e., forensic) in nature: they involve fact-finding activities undertaken by the Bank or persons appointed by the Bank to address specific matters related to investigations/audits, such as evaluating the veracity of an allegation of possible Fraud and Corruption, through the appropriate mechanisms. Such activity includes but is not and other documents relating to the procurement process and/or contract execution (in the case of award), and to have them audited by auditors appointed by the Bank. We agree to preserve all accounts, records, and other documents (whether in hard copy or electronic format) related to the procurement and execution of the contract. Name of the Bidder/Consultant: Name of the person duly authorized to sign the Bid/Proposal on behalf of the Bidder/Consultant: Title of the person signing the Letter: limited to accessing and examining a firm's or individual's financial records and information, and making copies thereof as relevant; accessing and examining any other documents, data, and information (whether in hard copy or electronic format) deemed relevant for the investigation/audit, and making copies thereof as relevant; interviewing staff and other relevant individuals; performing physical inspections and site visits; and obtaining third-party verification of information. PROCUREMENT Nigeria : Nigeria Rural Access and Agricultural Marketing Project PLAN General Information Country: Nigeria 2021-04-23 Bank’s Approval Date of the Original Procurement Plan: 2023-06-03 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P163353 GPN Date: Project Name: Nigeria Rural Access and Agricultural Marketing Project Loan / Credit No: IDA / 65190 AKWA IBOM RAAMP Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned NG-AKWA IBOM RAAMP-230 Request for Bids - Component A. Improvement 755-CW-RFB / Construction o Single Stage - One E Small Works SPD Pending Imp 2024-04-1 IDA / 65190 of Rural Access and Trading Post Request for Bids Open - National 900,000.00 0.00 2022-09-28 2022-10-03 2022-11-14 2022-12-14 2023-01-18 f 100 meters Cross - Drainag nvelope (1 envelope proce lementation 2 Infrastructure e Structures (Culverts/Bridge ss) s) on Rural Roads Request for Bids - NG-AKWA IBOM RAAMP-280 Component A. Improvement Single Stage - One E Small Works SPD Under Imple 2023-06-3 436-CW-RFB / Upgrading/ Co IDA / 65190 of Rural Access and Trading Post Request for Bids Open - National 600,000.00 0.00 2022-07-04 2022-10-25 2022-07-25 2022-12-16 2022-07-27 2022-11-22 2022-08-26 2022-09-23 nvelope (1 envelope proce mentation 0 nstruction of 11km of priority Infrastructure ss) pilot Road NG-AKWA IBOM RAAMP-280 Request for Bids - Component A. Improvement 438-CW-RFB / Physical impro Single Stage - One E Small Works SPD Pending Imp 2024-06-2 IDA / 65190 of Rural Access and Trading Post Request for Bids Open - National 1,000,000.00 0.00 2022-09-19 2022-10-10 2022-10-12 2022-11-11 2022-12-09 vement of about 2 nos. Agro- nvelope (1 envelope proce lementation 6 Infrastructure logistics Centers (ALCs) ss) Request for Bids - NG-AKWA IBOM RAAMP-230 Component B. Asset Manage Single Stage - One E Small Works SPD Pending Imp 2024-01-0 747-CW-RFB / Spot Improve IDA / 65190 ment, Agro-logistics Perform Post Request for Bids Open - National 5,000,000.00 0.00 2022-07-26 2022-08-16 2022-08-18 2022-09-08 2022-10-13 nvelope (1 envelope proce lementation 6 ment of about 225 km Rural ance Enhancement and Sect ss) Roads or Reform Request for Bids - NG-AKWA IBOM RAAMP-280 Component A. Improvement Single Stage - One E Small Works SPD Pending Imp 2024-06-1 431-CW-RFB / Rural Roads up IDA / 65190 of Rural Access and Trading Post Request for Bids Open - National 2,000,000.00 0.00 2022-09-29 2022-10-20 2022-10-22 2022-11-21 2022-12-19 nvelope (1 envelope proce lementation 1 grading of about 40km Infrastructure ss) Request for Bids - NG-AKWA IBOM RAAMP-230 Component B. Asset Manage Single Stage - One E Small Works SPD Pending Imp 2024-04-0 673-CW-RFB / Backlog Maint IDA / 65190 ment, Agro-logistics Perform Post Request for Bids Open - National 2,500,000.00 0.00 2022-09-27 2022-10-02 2022-11-13 2022-12-13 2023-01-10 nvelope (1 envelope proce lementation 4 enance/Rehabilitation of 100 ance Enhancement and Sect ss) km Rural Roads or Reform GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NG-AKWA IBOM RAAMP-230 Component C. Institutional D Request for Quota Single Stage - One E Pending Impl 299-GO-RFQ / Purchase of off IDA / 65190 evelopment, Project Manage Post Limited 50,000.00 0.00 2022-06-07 2022-07-12 2022-08-11 tions nvelope ementation ice furniture and equipment ment and Risk Mitigation NG-AKWA IBOM RAAMP-230 Component C. Institutional D Request for Quota Single Stage - One E Under Imple 389-GO-RFQ / Purchase of 1 IDA / 65190 evelopment, Project Manage Post Limited 33,000.00 0.00 2022-05-23 2022-08-30 2022-06-27 2022-07-27 tions nvelope mentation no. 30 KVA Generators ment and Risk Mitigation NG-AKWA IBOM RAAMP-230 Component C. Institutional D Request for Quota Single Stage - One E Pending Impl 590-GO-RFQ / Purchase of pr IDA / 65190 evelopment, Project Manage Post Limited 50,000.00 0.00 2022-06-27 2022-08-01 2022-08-31 tions nvelope ementation omotional materials (Flip Cha ment and Risk Mitigation rt, Memo etc.) NG-AKWA IBOM RAAMP-230 Component C. Institutional D Request for Quota Single Stage - One E Pending Impl 280-GO-RFQ / Purchase of 2n IDA / 65190 evelopment, Project Manage Post Limited 150,000.00 0.00 2022-06-13 2022-07-25 2022-08-24 tions nvelope ementation os. of operating project vehic ment and Risk Mitigation les NG-AKWA IBOM RAAMP-230 339-GO-RFQ / Purchase of 15 nos. laptops, 10nos, Desktop Component C. Institutional D Request for Quota Single Stage - One E Pending Impl s, 10nos Printers/Fax, 2Nos H IDA / 65190 evelopment, Project Manage Post Limited 80,000.00 0.00 2022-06-20 2022-07-25 2022-08-24 tions nvelope ementation eavy Duty Photocopiers 10No ment and Risk Mitigation s Scanners, 1 nos Projector, I nternet Installation, Air Condi tioners, and Consumables NG-AKWA IBOM RAAMP-230 409-GO-RFQ / Purchase of Sa feguard equipment (PPEs, fir Component C. Institutional D st aid kits, environmental mo Request for Quota Single Stage - One E Pending Impl IDA / 65190 evelopment, Project Manage Post Limited 80,000.00 0.00 2022-07-02 2022-08-13 2022-09-12 nitoring and tracking equipm tions nvelope ementation ment and Risk Mitigation ent including in-situ air qualit y kits, noise meter, PH meter , caution tapes, measuring ta pes, camera, GPS etc.) NG-AKWA IBOM RAAMP-230 Component C. Institutional D Request for Quota Single Stage - One E Pending Impl 391-GO-RFQ / Purchase of da IDA / 65190 evelopment, Project Manage Post Limited 10,000.00 0.00 2022-04-08 2022-05-20 2022-07-04 tions nvelope ementation ta Collection Gadgets (6Nos) ment and Risk Mitigation AKS/RAAMP/RFQ/O1/23 / Pro Component C. Institutional D Request for Quota Single Stage - One E Pending Impl curement of office stationerie IDA / 65190 evelopment, Project Manage Post Limited 10,000.00 0.00 2023-07-17 2023-08-24 2023-09-07 tions nvelope ementation s and Consumables for AKS R ment and Risk Mitigation AAMP NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 1 NG-AKWA IBOM RAAMP-280 293-CS-QCBS / Consultancy S Component A. Improvement ervices for Design and Super Quality And Cost- Open - Internationa Under Implement IDA / 65190 of Rural Access and Trading Post 430,000.00 0.00 2022-03-09 2022-06-09 2022-04-08 2022-08-17 2022-05-06 2022-10-06 2022-06-03 2022-11-17 2022-07-03 2022-12-15 2022-08-07 2022-09-11 2024-11-29 vision of 160 km Rural Road Based Selection l ation Infrastructure Upgrading (Design & Build; N on-Design & Build contracts) NG-AKWA IBOM RAAMP-230 440-CS-CQS / Consultancy se rvices for Design and Supervi Component B. Asset Manage sion of Backlog Maintenance, ment, Agro-logistics Perform Consultant Qualifi IDA / 65190 Post Open - National 365,000.00 0.00 Canceled 2021-05-10 2021-05-17 2021-06-23 2021-07-07 2021-08-04 2023-12-22 Spot Improvement, Performa ance Enhancement and Sect cation Selection nce Based Maintenance Cont or Reform ract (PBMC) and Cross-draina ge Structures (bridges/ culve rts) in Akwa Ibom State NG-AKWA IBOM RAAMP-280 Component A. Improvement 333-CS-CQS / Consultancy se Consultant Qualifi Under Implement IDA / 65190 of Rural Access and Trading Post Open - National 120,000.00 0.00 2022-03-20 2022-03-08 2022-04-10 2022-05-19 2022-05-08 2022-08-09 2022-06-07 2022-09-07 2022-07-12 2023-05-08 rvices for the Design review cation Selection ation Infrastructure and Supervision of 11 Km of priority Pilot road NG-AKWA IBOM RAAMP-280 337-CS-QCBS / Consultancy S Component A. Improvement Quality And Cost- Open - Internationa Under Implement ervices for Design and Super IDA / 65190 of Rural Access and Trading Post 395,000.00 0.00 2022-03-20 2022-03-09 2022-04-19 2022-12-24 2022-06-14 2023-02-03 2022-06-28 2022-07-19 2022-08-09 2022-09-06 2024-11-14 Based Selection l ation vision of physical improveme Infrastructure nt of 5 to 6 nos. Agro-logistic s Centers (ALCs) NG-AKWA IBOM RAAMP-230 412-CS-CQS / Consultancy Se Component A. Improvement rvices for Design and Supervi Consultant Qualifi IDA / 65190 of Rural Access and Trading Post Open - National 350,000.00 0.00 Canceled 2021-09-06 2021-09-13 2021-10-20 2021-11-03 2021-12-01 2024-06-18 sion of Rural Road Upgrading cation Selection Infrastructure (Design & Build) and Improve ment of Agro-Logistics Hubs ( ALHs) in Akwa Ibom State. NG-AKWA IBOM RAAMP-282 Component B. Asset Manage 705-CS-CQS / Consultancy Se ment, Agro-logistics Perform Consultant Qualifi Under Implement rvices for Design and Supervi IDA / 65190 Post Open - National 180,000.00 0.00 2022-03-20 2022-06-09 2022-04-10 2022-06-08 2022-05-15 2022-08-31 2022-05-29 2022-10-13 2022-06-26 2023-06-21 ance Enhancement and Sect cation Selection ation sion of Backlog maintenance/ or Reform Réhabilitation of roads (125K M) NG-AKWA IBOM RAAMP-282 708-CS-CQS / Consultancy Se Component B. Asset Manage rvices for Design and Supervi ment, Agro-logistics Perform Consultant Qualifi Under Implement IDA / 65190 Post Open - National 200,000.00 0.00 2022-03-28 2022-03-08 2022-04-18 2022-06-08 2022-05-23 2022-08-30 2022-06-06 2022-10-21 2022-07-04 2023-06-29 sion of Spot Improvement (3 ance Enhancement and Sect cation Selection ation 00KM) and construction of 50 or Reform linear meter Cross-drainage s tructures (bridges/culverts) NG-AKWA IBOM RAAMP-280 320-CS-CQS / Consultancy se rvices for Design and Supervi Component B. Asset Manage sion of Backlog Maintenance/ ment, Agro-logistics Perform Consultant Qualifi IDA / 65190 Post Open - National 212,000.00 0.00 Canceled 2022-03-01 2022-03-22 2022-04-19 2022-05-03 2022-05-31 2023-05-26 Rehabilitation (125km), Spot ance Enhancement and Sect cation Selection Improvement (300km), and c or Reform onstruction of 50 linear mete r Cross-drainage Structures ( bridges/culverts) AKS/RAAMP/ESMP/CQS/01/2 3 / Consultancy Services for preparation of ESMP for Rural Component C. Institutional D Consultant Qualifi Pending Impleme Roads (Upgrading of Rural Ro IDA / 65190 evelopment, Project Manage Post Limited 120,000.00 0.00 2023-07-12 2023-07-26 2023-08-16 2023-09-11 2024-09-10 cation Selection ntation ads, Spot Improvement, Cros ment and Risk Mitigation s-drainage structure, and Ba cklog Maintenance/Rehabilita tion) for AKS RAAMP AKS/RAAMP/RAP/CQS/02/23 / Consultancy Services for pre Component C. Institutional D paration of RAP for Rural Roa Consultant Qualifi Pending Impleme IDA / 65190 evelopment, Project Manage Post Limited 120,000.00 0.00 2023-07-12 2023-07-26 2023-08-16 2023-09-11 2024-09-10 ds (Upgrading of Rural Roads cation Selection ntation ment and Risk Mitigation , Spot Improvement, Cross-dr ainage structure, and Backlo g Maintenance/Rehabilitation ) INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NG-AKWA IBOM RAAMP-280 Component C. Institutional D 394-CS-INDV / Consultancy S Individual Consult IDA / 65190 evelopment, Project Manage Post Limited 30,000.00 0.00 Signed 2022-03-07 2022-04-05 2022-03-28 2022-06-14 2022-04-04 2022-07-25 2022-04-18 2023-04-13 ervices for the engagement o ant Selection ment and Risk Mitigation f TA on Security Specialist NG-AKWA IBOM RAAMP-230 Component C. Institutional D Individual Consult 466-CS-INDV / Engagement o IDA / 65190 evelopment, Project Manage Post Limited 40,000.00 0.00 Canceled 2022-06-08 2022-06-29 2022-07-13 2022-08-03 2023-08-03 ant Selection f Technical Assistant (Gender ment and Risk Mitigation Based Violent) NG-AKWA IBOM RAAMP-230 Component C. Institutional D Individual Consult 504-CS-INDV / Engagement o IDA / 65190 evelopment, Project Manage Post Limited 30,000.00 0.00 Canceled 2022-06-16 2022-07-07 2022-07-21 2022-08-11 2023-08-11 ant Selection f Technical Assistant (Social ment and Risk Mitigation Safeguard) NG-AKWA IBOM RAAMP-230 Component C. Institutional D 522-CS-INDV / Engagement o Individual Consult IDA / 65190 evelopment, Project Manage Post Limited 30,000.00 0.00 Canceled 2022-06-23 2022-07-14 2022-07-28 2022-08-18 2023-08-18 f Technical Assistant (Environ ant Selection ment and Risk Mitigation mental Safeguard) NG-AKWA IBOM RAAMP-230 Component C. Institutional D Individual Consult 533-CS-INDV / Engagement o IDA / 65190 evelopment, Project Manage Post Limited 30,000.00 0.00 Canceled 2022-06-30 2022-07-21 2022-08-04 2022-08-25 2023-08-25 ant Selection f Technical Assistant (Procure ment and Risk Mitigation ment) NG-AKWA IBOM RAAMP-230 Component C. Institutional D Individual Consult Under Implement 538-CS-INDV / Engagement o IDA / 65190 evelopment, Project Manage Post Limited 30,000.00 0.00 2022-07-08 2022-05-25 2022-07-29 2022-05-10 2022-08-12 2022-07-12 2022-09-02 2023-09-02 ant Selection ation f Technical Assistant (Infrastr ment and Risk Mitigation ucture) NG-AKWA IBOM RAAMP-280 406-CS-INDV / Consultancy S Component C. Institutional D Individual Consult Under Implement ervices for engagement of Te IDA / 65190 evelopment, Project Manage Post Open 25,000.00 0.00 2022-07-18 2021-06-25 2022-08-22 2021-08-13 2022-08-29 2021-08-16 2022-09-12 2023-09-12 ant Selection ation chnical Assistant (TA) for Dat ment and Risk Mitigation a Entry Specialist (DES) NG-AKWA IBOM RAAMP-280 398-CS-INDV / Consultancy S Component C. Institutional D Individual Consult Under Implement ervices for engagement of TA IDA / 65190 evelopment, Project Manage Post Limited 25,000.00 0.00 2022-07-26 2021-06-25 2022-08-02 2021-07-16 2022-08-16 2022-09-06 2023-09-01 ant Selection ation for Geographic Information S ment and Risk Mitigation ystem (GIS) Specialist Page 2 NG-AKWA IBOM RAAMP-313 481-CS-CDS / CONSULTANCY SERVICE FOR UPDATING OF E NVIRONMENTAL AND SOCIAL Component C. Institutional D Under Implement MANAGEMENT PLAN (ESMP) F IDA / 65190 evelopment, Project Manage Post Direct Selection Direct - National 30,000.00 0.00 2022-09-12 2022-09-15 2022-09-26 2022-10-31 2023-04-29 ation OR 11KM OWOT UTA – NUNG ment and Risk Mitigation OKU EKERE – AFAHA UDOE E YOP – EDEOBOM UTUAT MAR KET JUNCTION ROAD IN NSIT IBOM & IBESIKPO ASUTAN IN AKWA STATE NG-AKWA IBOM RAAMP-313 511-CS-CDS / CONSULTANCY SERVICES FOR UPDATING OF RESETTLEMENT ACTION PLA Component C. Institutional D Under Implement N (RAP) FOR 11KM OWOT UT IDA / 65190 evelopment, Project Manage Post Direct Selection Direct - National 30,000.00 0.00 2022-09-19 2022-09-15 2022-10-03 2022-11-07 2023-05-06 ation A – NUNG OKU EKERE – AFAH ment and Risk Mitigation A UDOE EYOP – EDEOBOM UT UAT MARKET JUNCTION ROA D IN NSIT IBOM & IBESIKPO A SUTAN IN AKWA STATE NG-AKWA IBOM RAAMP-313 965-CS-CDS / CONSULTANCY SERVICE FOR THE PREPARATI ON OF ENVIRONMENTAL AND Component C. Institutional D Under Implement SOCIAL MANAGEMENT PLAN ( IDA / 65190 evelopment, Project Manage Post Direct Selection Direct - National 30,000.00 0.00 2022-09-21 2022-09-15 2022-10-05 2022-11-09 2023-05-08 ation ESMP) FOR 11.127KM NSIE – ment and Risk Mitigation UTINE – OTIEKE OFFI – URUTI NG AKS-RAAMP PILOT ROAD I N OKOBO LGA AS PART OF P RIORITY ROADS IN AKWA IBO M. NG-AKWA IBOM RAAMP-313 968-CS-CDS / CONSULTANCY SERVICES FOR THE PREPARA Component C. Institutional D TION OF RESETTLEMENT ACT Under Implement IDA / 65190 evelopment, Project Manage Post Direct Selection Direct - National 30,000.00 0.00 2022-09-26 2022-09-15 2022-10-10 2022-11-14 2023-05-13 ION PLAN (RAP) FOR 11.127K ation ment and Risk Mitigation M NSIE – UTINE – OTIEKE OFF I – URUTING AKS-RAAMP PILO T ROAD IN OKOBO LGA AS PA RT OF PRIORITY ROADS IN AK WA IBOM. NG-AKWA IBOM RAAMP-322 Component C. Institutional D Individual Consult Under Implement 098-CS-INDV / ENGAGEMENT IDA / 65190 evelopment, Project Manage Prior Limited 40,000.00 0.00 2022-10-31 2022-11-01 2022-11-14 2023-02-28 2022-11-28 2023-06-01 2022-12-12 2024-12-01 ant Selection ation OF PROCUREMENT SPECIALIS ment and Risk Mitigation T NG-AKWA IBOM RAAMP-350 642-CS-INDV / Consultancy S ervice for the Preparation of Environmental and Social Ma Component C. Institutional D Individual Consult Pending Impleme nagement Plan (ESMP) and R IDA / 65190 evelopment, Project Manage Post Limited 25,000.00 0.00 2023-04-05 2023-04-19 2023-05-03 2023-05-24 2024-05-23 ant Selection ntation AP For 11.127km Nsie – Utine ment and Risk Mitigation – Otieke Offi – Uruting Aks-RA AMP Pilot Road in Okobo LGA s as Part of Priority Roads in Akwa Ibom State. NG-AKWA IBOM RAAMP-347 Component C. Institutional D Individual Consult 731-CS-INDV / Engagement o IDA / 65190 evelopment, Project Manage Post Limited 30,000.00 0.00 Canceled 2023-03-15 2023-04-18 2023-04-05 2023-04-19 2023-05-10 2024-05-09 ant Selection f Technical Assistant (Social ment and Risk Mitigation Safeguard) NG-AKWA IBOM RAAMP-347 Component C. Institutional D 741-CS-INDV / Engagement o Individual Consult IDA / 65190 evelopment, Project Manage Post Limited 30,000.00 0.00 Canceled 2023-03-26 2023-03-20 2023-04-16 2023-04-30 2023-05-21 2024-05-20 f Technical Assistant (Environ ant Selection ment and Risk Mitigation mental Safeguard) NG-AKWA IBOM RAAMP-347 Component C. Institutional D 738-CS-INDV / Engagement o Individual Consult IDA / 65190 evelopment, Project Manage Post Limited 30,000.00 0.00 Canceled 2023-03-20 2023-04-10 2023-04-24 2023-05-15 2024-05-14 f Technical Assistant (Environ ant Selection ment and Risk Mitigation mental Safeguard) AKS/RAAMP/ES/INDV/01/23 / Component C. Institutional D Consultancy Service for the E Individual Consult Pending Impleme IDA / 65190 evelopment, Project Manage Post Limited 30,000.00 0.00 2023-08-01 2023-08-15 2023-08-29 2023-10-03 2024-03-01 ngagement of TA Environme ant Selection ntation ment and Risk Mitigation nt to support SPIU NG-AKWA IBOM RAAMP-350 636-CS-INDV / Consultancy S ervice for updating of Enviro nmental and Social Manage Component C. Institutional D Individual Consult Pending Impleme ment Plan (ESMP) and RAP fo IDA / 65190 evelopment, Project Manage Post Limited 25,000.00 0.00 2023-03-27 2023-04-10 2023-04-24 2023-05-22 2024-05-21 ant Selection ntation r 11km Owot Uta – Nung Oku ment and Risk Mitigation Ekere – Afaha Udoe Eyop – E de obom Utuat Market Juncti on Road in Nsit Ibom & Ibesik po Asutan LGAs in Akwa Stat e AKS/RAAMP/SS/INDV/02/23 / Component C. Institutional D Consultancy Services for Eng Individual Consult Pending Impleme IDA / 65190 evelopment, Project Manage Post Limited 30,000.00 0.00 2023-07-13 2023-07-27 2023-08-10 2023-08-31 2024-01-28 agement of TA Social Safegu ant Selection ntation ment and Risk Mitigation ard to support SPIU Page 3 PROCUREMENT PLAN Project information: ENHANCING WATERWAY CONNECTIVITY AND WATER SERVICE PROVISION IN COLOMBIA’S PLAN PAZCIFICO Region Project P156880 Project Implementation agency: 1. NATIONAL UNIT FOR THE MANAGEMENT OF DISASTER RISK / UNIDAD NACIONAL DE GESTION DEL RIESGO DE DESASTRES Date of the Procurement Plan: 10/22/2019 Period covered by this Procurement Plan: 10/22/2019 – 12/15/2023 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the documents previously approved with the Bank will be used. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: Is not applicable; Works: Is not applicable PROCUREMENT Colombia : Enhancing Waterway Connectivity and Water Service Provision in Colombia’s Plan Pazcifico PLAN General Information Country: Colombia Bank’s Approval Date of the Original Procurement Plan: 2019-12-12 Revised Plan Date(s): (comma delineated, leave blank if2023-06-05 none) Project ID: P156880 GPN Date: 2019-12-09 Project Name: Enhancing Waterway Connectivity and Water Service Provision in Colombia’s Plan Pazcifico Loan / Credit No: IBRD / 87980 National Unit for the Management of Disaster Risk Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned PTSP-BIRF8798-003 / Constr Improving Water Supply and Single Stage - One E 2020-10-3 ucción acueducto Francisco P IBRD / 87980 Sanitation Services in partici Post Request for Bids Open - National 3,967,526.00 0.00 Canceled 2020-01-13 2020-01-18 2020-02-29 2020-03-30 2020-05-04 nvelope 1 izarro pating municipalities Improving Water Supply and PTSP-BIRF8798-005 / Constr Single Stage - One E 2020-11-1 IBRD / 87980 Sanitation Services in partici Post Request for Bids Open - National 4,046,127.00 0.00 Canceled 2020-01-27 2020-02-01 2020-03-14 2020-04-13 2020-05-18 ucción acueducto Timbiquí nvelope 4 pating municipalities PTSP-BIRF8798-006 / Constr Improving Water Supply and Single Stage - One E 2020-11-0 ucción alcantarillado municip IBRD / 87980 Sanitation Services in partici Post Request for Bids Open - National 3,760,945.00 0.00 Canceled 2020-01-20 2020-01-25 2020-03-07 2020-04-06 2020-05-11 nvelope 7 io seleccionado pating municipalities PTSP-BIRF8798-007 / Mante nimiento de las instalaciones Improving Waterway Transp Single Stage - One E 2020-11-1 portuarias y equipos de Seña IBRD / 87980 ort in participating municipal Post Request for Bids Open - National 962,000.00 0.00 Canceled 2020-01-27 2020-02-01 2020-03-14 2020-04-13 2020-05-18 nvelope 4 lización y Seguridad durante ities el periodo de ejecución de la s obras PTSP-BIRF8798-0060 / Const Improving Waterway Transp Single Stage - One E 2021-07-1 rucción del muelle y terminal IBRD / 87980 ort in participating municipal Post Request for Bids Open - National 1,336,814.00 0.00 Canceled 2020-08-15 2020-08-28 2020-08-20 2020-09-18 2020-10-15 2020-10-06 2020-11-21 nvelope 9 portuario del municipio de La ities Tola (Nariño) National Procure PTSP-BIRF8798-090 / Constr Improving Waterway Transp ment Document - Single Stage - One E Pending Imp 2023-08-1 ucción del muelle y terminal IBRD / 87980 ort in participating municipal Post Request for Bids Open - National 1 Envelope proce 1,700,000.00 0.00 2022-09-28 2022-10-03 2022-11-14 2022-12-14 2023-01-18 nvelope lementation 8 portuario No. 1 ities ss (Non Bank-SPD ) National Procure PTSP-BIRF8798-091 / Constr Improving Waterway Transp ment Document - Single Stage - One E Pending Imp 2023-10-2 ucción del muelle y terminal IBRD / 87980 ort in participating municipal Post Request for Bids Open - National 1 Envelope proce 1,700,000.00 0.00 2022-11-03 2022-11-08 2022-12-20 2023-01-19 2023-02-23 nvelope lementation 3 portuario No. 2 ities ss (Non Bank-SPD ) National Procure PTSP-BIRF8798-092 / Constr Improving Waterway Transp ment Document - Single Stage - One E Pending Imp 2023-12-1 ucción del muelle y terminal IBRD / 87980 ort in participating municipal Post Request for Bids Open - National 1 Envelope proce 1,700,000.00 0.00 2022-12-22 2022-12-27 2023-02-07 2023-03-09 2023-04-13 nvelope lementation 1 portuario No. 3 ities ss (Non Bank-SPD ) National Procure PTSP-BIRF8798-094 / Constr Improving Waterway Transp ment Document - Single Stage - One E Pending Imp 2023-12-0 ucción del muelle y terminal IBRD / 87980 ort in participating municipal Post Request for Bids Open - National 1 Envelope proce 1,700,000.00 0.00 2022-12-15 2022-12-20 2023-01-31 2023-03-02 2023-04-06 nvelope lementation 4 portuario No. 4 ities ss (Non Bank-SPD ) National Procure PTSP-BIRF8798-095 / Constr Improving Waterway Transp ment Document - Single Stage - One E Pending Imp 2023-12-0 ucción del muelle y terminal IBRD / 87980 ort in participating municipal Post Request for Bids Open - National 1 Envelope proce 1,700,000.00 0.00 2022-12-12 2022-12-17 2023-01-28 2023-02-27 2023-04-03 nvelope lementation 1 portuario No. 5 ities ss (Non Bank-SPD ) National Procure PTSP-BIRF8798-096 / Constr Improving Waterway Transp ment Document - Single Stage - One E Pending Imp 2023-12-2 ucción del muelle y terminal IBRD / 87980 ort in participating municipal Post Request for Bids Open - National 1 Envelope proce 1,700,000.00 0.00 2023-01-05 2023-01-10 2023-02-21 2023-03-23 2023-04-27 nvelope lementation 5 portuario No. 6 ities ss (Non Bank-SPD ) National Procure PTSP-BIRF8798-098 / Obras Improving Water Supply and ment Document - Single Stage - One E Pending Imp 2023-05-2 de optimización del acueduct IBRD / 87980 Sanitation Services in partici Post Request for Bids Open - National 1 Envelope proce 2,900,000.00 0.00 2022-02-02 2022-02-07 2022-03-21 2022-04-20 2022-05-25 nvelope lementation 5 o de Timbiquí pating municipalities ss (Non Bank-SPD ) National Procure PTSP-BIRF8798-099 / Obras Improving Water Supply and ment Document - Single Stage - One E Pending Imp 2023-07-0 de optimización del acueduct IBRD / 87980 Sanitation Services in partici Post Request for Bids Open - National 1 Envelope proce 2,900,000.00 0.00 2022-03-17 2022-03-22 2022-05-03 2022-06-02 2022-07-07 nvelope lementation 7 o de Francisco Pizarro pating municipalities ss (Non Bank-SPD ) National Procure Improving Water Supply and ment Document - PTSP-BIRF8798-100 / Obra al Single Stage - One E Pending Imp 2024-06-1 IBRD / 87980 Sanitation Services in partici Post Request for Bids Open - National 1 Envelope proce 3,200,000.00 0.00 2022-10-21 2022-10-26 2022-12-07 2023-01-06 2023-02-10 cantarillado de Timbiquí nvelope lementation 0 pating municipalities ss (Non Bank-SPD ) National Procure PTSP-BIRF8798-101 / Obra al Improving Water Supply and ment Document - Single Stage - One E Pending Imp 2024-06-1 cantarillado de Francisco Piza IBRD / 87980 Sanitation Services in partici Post Request for Bids Open - National 1 Envelope proce 3,200,000.00 0.00 2022-10-21 2022-10-26 2022-12-07 2023-01-06 2023-02-10 nvelope lementation 0 rro pating municipalities ss (Non Bank-SPD ) PTSP-BIRF-8798-125 / Optimi zación y ampliación del siste ma de acueducto de la cabec Improving Water Supply and Request for Quota Request for Quota Single Stage - One E Under Imple 2023-07-0 era urbana del municipio de IBRD / 87980 Sanitation Services in partici Post Open - National tions (Non Bank-S 1,031,264.00 0.00 2022-11-12 2023-01-07 tions nvelope mentation 6 Timbiquí Departamento del C pating municipalities PD) auca: Obras en la captación, aducción, tratamiento y alma cenamiento de agua potable. PTSP-BIRF-8798-130 / Optimi zación y ampliación del siste Improving Water Supply and ma de acueducto de la cabec Request for Quota Single Stage - One E Other (with field f Under Imple 2023-07-0 IBRD / 87980 Sanitation Services in partici Post Open - National 1,755,560.00 0.00 2022-11-15 2023-01-10 era urbana del municipio de tions nvelope or explanation) mentation 9 pating municipalities Timbiquí Departamento del C auca: Obras en la red de dist ribución. National Procure PTSP-BIRF8798-088 / Constr Improving Waterway Transp ment Document - Single Stage - One E 2023-09-0 ucción del muelle y terminal IBRD / 87980 ort in participating municipal Post Request for Bids Open - National 1 Envelope proce 2,761,617.00 0.00 Canceled 2022-08-15 2022-12-06 2022-08-20 2022-10-01 2023-01-26 2022-10-31 2022-12-05 nvelope 1 portuario del municipio de La ities ss (Non Bank-SPD Tola (Nariño) ) PTSP-BIRF8798-140 / Constr Improving Waterway Transp Single Stage - One E Other (with field f Pending Imp 2024-01-1 ucción del muelle y terminal IBRD / 87980 ort in participating municipal Post Request for Bids Open - National 2,761,618.84 0.00 2023-03-29 2023-04-03 2023-05-15 2023-06-14 2023-07-19 nvelope or explanation) lementation 5 portuario del municipio de La ities Tola (Nariño). GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 1 Capacity Building and Institu PTSP-BIRF8798-0052 / Adqui tional Strengthening for wat Request for Quota Single Stage - One E rir motobombas y accesorios IBRD / 87980 erway transport operators a Post Open - National 198,804.00 187,812.81 Signed 2020-07-13 2020-09-07 2020-11-15 2020-10-07 tions nvelope hidráulicos nd water supply and sanitati on service providers in parti cipating municipalities Capacity Building and Institu PTSP-BIRF8798-0053 / Adqui tional Strengthening for wat Request for Quota Single Stage - One E rir tanques para almacenami IBRD / 87980 erway transport operators a Post Open - National 246,330.00 19,321.73 Signed 2020-07-13 2020-09-07 2020-11-21 2020-10-07 tions nvelope ento de agua nd water supply and sanitati on service providers in parti cipating municipalities Capacity Building and Institu PTSP-BIRF8798-0056 / Adqui tional Strengthening for wat Request for Quota Single Stage - One E rir filtros purificadores de ag IBRD / 87980 erway transport operators a Post Open - National 100,274.00 51,899.67 Signed 2020-07-13 2020-09-07 2020-11-12 2020-10-22 tions nvelope ua nd water supply and sanitati on service providers in parti cipating municipalities Capacity Building and Institu PTSP-BIRF8798-0054 / Adqui tional Strengthening for wat Request for Quota Single Stage - One E rir plantas de tratamiento de IBRD / 87980 erway transport operators a Post Open - National 140,278.00 120,485.00 Signed 2020-07-13 2020-09-07 2020-10-31 2020-11-06 tions nvelope agua potable portátiles nd water supply and sanitati on service providers in parti cipating municipalities NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PTSP-BIRF8798-117 / Prestar los servicios logísticos integr Capacity Building and Institu ales para la correcta ejecució tional Strengthening for wat n del Convenio de Cooperaci erway transport operators a Request for Quota Single Stage - One E Under Imple IBRD / 87980 Post Open - National 166,050.00 0.00 2022-08-27 2022-10-22 2023-05-20 ón No. 57833-PTSP-017-2022 nd water supply and sanitati tions nvelope mentation suscrito entre la Dirección Ge on service providers in parti neral Marítima (MDN – DIMAR cipating municipalities ), el Servicio Nacional de Apr endizaje (SENA) y el FTSP. CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PTSP-BIRF8798-010 / Interve Improving Waterway Transp ntoría de la Ejecución de Obr Quality And Cost- Open - Internationa IBRD / 87980 ort in participating municipal Post 1,326,080.00 0.00 Canceled 2020-01-27 2020-02-17 2020-04-01 2020-04-29 2020-05-29 2020-07-03 2020-08-07 2021-08-07 as de muelles, Obras de Señ Based Selection l ities alización y Seguridad en Nav egación PTSP-BIRF8798-011 / Imple Project Management and En Consultant Qualifi mentación del plan de inform IBRD / 87980 vironmental and Social Mana Post Open - National 100,000.00 0.00 Canceled 2020-02-03 2020-02-24 2020-04-08 2020-05-08 2020-06-12 2020-12-09 cation Selection ación, comunicación y partici gement pación PTSP-BIRF8798-012 / Actuali Improving Water Supply and Consultant Qualifi zacion de estudios Acueduct IBRD / 87980 Sanitation Services in partici Post Open - National 74,600.00 0.00 Canceled 2020-01-27 2020-02-17 2020-04-01 2020-05-01 2020-06-05 2020-12-02 cation Selection o Francisco Pizarro pating municipalities PTSP-BIRF8798-014 / Interve Improving Water Supply and Least Cost Selecti ntoria Obras Alcantarillado Fr IBRD / 87980 Sanitation Services in partici Post Open - National 275,138.00 0.00 Canceled 2020-01-13 2020-02-03 2020-03-18 2020-04-15 2020-05-15 2020-06-19 2020-07-24 2021-01-20 on ancisco Pizarro pating municipalities PTSP-BIRF8798-015 / Actuali Improving Water Supply and Least Cost Selecti zacion de estudios Alcantarill IBRD / 87980 Sanitation Services in partici Post Open - National 275,138.00 0.00 Canceled 2020-01-20 2020-02-10 2020-03-25 2020-04-22 2020-05-22 2020-06-26 2020-07-31 2021-01-27 on ado Francisco Pizarro pating municipalities PTSP-BIRF8798-017 / Interve Improving Water Supply and Least Cost Selecti ntoría obras Acueducto Timbi IBRD / 87980 Sanitation Services in partici Post Open - National 323,690.00 0.00 Canceled 2020-01-20 2020-02-10 2020-03-25 2020-04-22 2020-05-22 2020-06-26 2020-07-31 2021-01-27 on quí pating municipalities PTSP-BIRF8798-018 / Actuali Improving Water Supply and Least Cost Selecti zacion de estudios Alcantarill IBRD / 87980 Sanitation Services in partici Post Open - National 302,814.00 0.00 Canceled 2020-01-20 2020-02-10 2020-03-25 2020-04-22 2020-05-22 2020-06-26 2020-07-31 2021-01-27 on ado Timbiquí pating municipalities PTSP-BIRF8798-019 / Interve Improving Water Supply and Least Cost Selecti ntoría obras Alcantarillado Ti IBRD / 87980 Sanitation Services in partici Post Open - National 275,285.00 0.00 Canceled 2020-01-27 2020-02-17 2020-04-01 2020-04-29 2020-05-29 2020-07-03 2020-08-07 2021-02-03 on mbiquí pating municipalities Capacity Building and Institu tional Strengthening for wat PTSP-BIRF8798-020 / Fortale Quality And Cost- Open - Internationa IBRD / 87980 erway transport operators a Post 700,000.00 0.00 Canceled 2020-02-17 2020-03-09 2020-04-22 2020-05-20 2020-06-19 2020-07-24 2020-08-28 2021-08-28 cimiento institucional Based Selection l nd water supply and sanitati on service providers in parti cipating municipalities PTSP-BIRF8798-021 / Actuali Capacity Building and Institu zacion de planes maestros d tional Strengthening for wat Quality And Cost- Open - Internationa e acueducto para Olaya Herr IBRD / 87980 erway transport operators a Post 900,000.00 0.00 Canceled 2020-02-24 2020-03-16 2020-04-29 2020-05-27 2020-06-26 2020-07-31 2020-09-04 2021-09-04 Based Selection l era, La Tola, Mosquera, Franc nd water supply and sanitati isco Pizarro, Lopez de Micay on service providers in parti and Santa Barbara de Iscuan cipating municipalities de PTSP-BIRF8798-022 / Interve Improving Water Supply and Consultant Qualifi ntoría Actualizacion de estudi IBRD / 87980 Sanitation Services in partici Post Open - National 5,425.00 0.00 Canceled 2020-01-27 2020-02-17 2020-04-01 2020-05-01 2020-06-05 2020-12-02 cation Selection os Acueducto Francisco Pizar pating municipalities ro PTSP-BIRF8798-023 / Interve Improving Water Supply and Consultant Qualifi ntoría Actualizacion de estudi IBRD / 87980 Sanitation Services in partici Post Open - National 8,447.00 0.00 Canceled 2020-01-20 2020-02-10 2020-03-25 2020-04-24 2020-05-29 2020-11-25 cation Selection os Acueducto Timbiquí pating municipalities PTSP-BIRF8798-024 / Interve Improving Water Supply and Consultant Qualifi ntoría Actualizacion de estudi IBRD / 87980 Sanitation Services in partici Post Open - National 22,011.00 0.00 Canceled 2020-02-03 2020-02-24 2020-04-08 2020-05-08 2020-06-12 2020-12-09 cation Selection os Alcantarillado Francisco pi pating municipalities zarro PTSP-BIRF8798-025 / Interve Improving Water Supply and Consultant Qualifi ntoría Actualizacion de estudi IBRD / 87980 Sanitation Services in partici Post Open - National 24,225.00 0.00 Canceled 2020-02-10 2020-03-02 2020-04-15 2020-05-15 2020-06-19 2020-12-16 cation Selection os Alcantarillado Timbiquí pating municipalities PTSP-BIRF8798-026 / Evalua Project Management and En Quality And Cost- IBRD / 87980 Post Open - National 174,000.00 0.00 Canceled 2021-02-22 2021-03-15 2021-04-28 2021-05-26 2021-06-25 2021-07-30 2021-09-03 2022-09-03 ción de medio término y final vironmental and Social Mana Based Selection gement Page 2 PTSP-BIRF8798-008 / Estudio Improving Waterway Transp Quality And Cost- Open - Internationa s y Diseños definitivos para l IBRD / 87980 ort in participating municipal Prior 1,169,532.00 925,315.06 Signed 2020-05-19 2020-06-15 2020-06-09 2020-07-08 2020-07-08 2020-09-21 2020-08-05 2020-11-20 2020-08-20 2021-01-29 2020-09-24 2021-06-01 2020-10-18 2021-10-09 2021-10-18 Based Selection l os muelles y señalización ities PTSP-BIRF8798-009 / Interve Improving Waterway Transp Consultant Qualifi ntoría de Estudios de muelles IBRD / 87980 ort in participating municipal Post Open - National 350,763.00 0.00 Canceled 2020-05-19 2020-06-24 2020-06-09 2020-07-23 2020-08-22 2020-10-05 2021-10-05 cation Selection y estudios de señalización ities PTSP-BIRF8798-0009 / Interv Improving Waterway Transp Quality And Cost- entoría de Estudios y Diseños IBRD / 87980 ort in participating municipal Post Open - National 350,763.00 191,593.71 Signed 2020-07-07 2020-07-06 2020-07-28 2020-09-10 2020-09-10 2020-10-08 2020-11-09 2020-11-07 2021-01-29 2020-12-12 2021-02-22 2021-01-16 2021-10-09 2022-01-16 Based Selection de Muelles y señalización ities PTSP-BIRF8798-0058 / Interv entoría técnica, administrativ Improving Waterway Transp a, financiera, legal, ambienta Quality And Cost- IBRD / 87980 ort in participating municipal Post Open - National 230,726.00 0.00 Canceled 2020-07-21 2020-07-18 2020-08-11 2020-09-24 2020-10-22 2020-11-21 2020-12-26 2021-01-30 2021-10-27 l y social de la construcción d Based Selection ities el muelle y terminal portuari o en el municipio de La Tola ( Nariño) PTSP-BIRF8798-0059 / Cons ultoría para la estructuración Capacity Building and Institu del modelo de administració tional Strengthening for wat n, operación y mantenimient erway transport operators a Consultant Qualifi IBRD / 87980 Post Open - National 101,414.00 71,457.54 Signed 2020-07-21 2020-07-18 2020-08-11 2020-09-24 2020-10-06 2020-10-24 2022-01-18 2020-11-28 2022-01-19 2021-05-27 o de los terminales portuario nd water supply and sanitati cation Selection s fluviales de los municipios on service providers in parti del Pacífico sur de Colombia, cipating municipalities con aplicación piloto en el m unicipio de La Tola (Nariño). PTSP-BIRF8798-0057 / Actua Improving Water Supply and lización, ajuste y complemen Consultant Qualifi IBRD / 87980 Sanitation Services in partici Post Open - National 100,013.00 129,170.81 Signed 2020-09-30 2020-10-21 2020-10-15 2020-11-22 2021-02-16 2020-12-07 2021-06-10 2021-01-11 2021-06-11 2021-07-10 tación de los estudios y diseñ cation Selection pating municipalities os acueducto Francisco Pizar ro PTSP-BIRF8798-072 / CONSU LTORÍA PARA LA ELABORACI ÓN DE LOS ESTUDIOS Y DISE Improving Water Supply and Consultant Qualifi Under Implement ÑOS DEL SISTEMA DE ALCAN IBRD / 87980 Sanitation Services in partici Post Open - National 172,700.00 0.00 2021-03-24 2021-05-06 2021-04-08 2021-05-16 2021-05-31 2021-07-05 2022-03-02 cation Selection ation TARILLADO DE LA CABECERA pating municipalities URBANA DEL MUNICIPIO DE T IMBIQUÍ, DEPARTAMENTO DE L CAUCA PTSP-BIRF8798-073 / CONSU LTORÍA PARA LA ELABORACI ÓN DE LOS ESTUDIOS Y DISE Improving Water Supply and Consultant Qualifi Under Implement ÑOS DEL SISTEMA DE ALCAN IBRD / 87980 Sanitation Services in partici Post Open - National 184,250.00 0.00 2021-03-24 2021-05-20 2021-04-08 2021-05-16 2021-05-31 2021-07-05 2022-03-02 cation Selection ation TARILLADO DE LA CABECERA pating municipalities URBANA DEL MUNICIPIO DE F RANCISCO PIZARRO, DEPART AMENTO DE NARIÑO PTSP-BIRF8798-074 / PREST AR LOS SERVICIOS DE INTER VENTORÍA (SUPERVISIÓN) TÉ CNICA, ADMINISTRATIVA, FIN Improving Water Supply and ANCIERA, LEGAL, AMBIENTAL Quality And Cost- IBRD / 87980 Sanitation Services in partici Post Open - National 93,030.00 0.00 Canceled 2021-03-24 2021-04-14 2021-05-18 2021-05-23 2021-06-07 2021-06-22 2021-07-18 2022-04-22 Y SOCIAL PARA LOS ESTUDIO Based Selection pating municipalities S Y DISEÑOS DE LOS SISTEM AS DE ALCANTARILLADO DE LOS MUNICIPIOS DE TIMBIQUÍ , DEPARTAMENTO DEL CAUC A, Y FRANCISCO PIZARRO, D PTSP-BIRF8798-078 / Prestar los servicios de interventoría (supervisión) técnica, admini Improving Water Supply and strativa, financiera, legal, am Quality And Cost- IBRD / 87980 Sanitation Services in partici Post Open - National 46,512.00 0.00 Canceled 2021-05-13 2021-06-03 2021-07-07 2021-07-12 2021-07-27 2021-08-11 2021-09-06 2022-06-11 biental y social para los estu Based Selection pating municipalities dios y diseños del sistema de alcantarillado en los municipi os del pacifico sur de los dep artamentos de cauca y nariñ o. PTSP-BIRF8798-080 / PREST AR LOS SERVICIOS DE INTER VENTORÍA (SUPERVISIÓN) TÉ CNICA, ADMINISTRATIVA, FIN Improving Water Supply and ANCIERA, LEGAL, AMBIENTAL Consultant Qualifi Under Implement IBRD / 87980 Sanitation Services in partici Post Open - National 60,550.00 0.00 2021-05-25 2021-06-09 2021-06-09 2021-07-19 2021-10-01 2021-08-03 2021-10-28 2021-09-01 2022-05-29 Y SOCIAL PARA LOS ESTUDIO cation Selection ation pating municipalities S Y DISEÑOS DE LOS SISTEM AS DE ALCANTARILLADO DE LOS MUNICIPIOS DE TIMBIQUÍ , DTO DEL CAUCA, Y FRANCIS CO PIZARRO DTO NARIÑO. PTSP-BIRF8798-082 / PREST AR LOS SERVICIOS DE INTER VENTORÍA (SUPERVISIÓN) TÉ CNICA, ADMINISTRATIVA, FIN Improving Water Supply and ANCIERA, LEGAL, AMBIENTAL Quality And Cost- Open - Internationa Under Implement IBRD / 87980 Sanitation Services in partici Prior 1,640,447.00 0.00 2021-07-12 2021-10-04 2021-07-16 2021-12-07 2021-08-14 2022-04-06 2021-09-27 2022-06-17 2021-10-12 2022-09-16 2021-11-16 2023-04-21 2021-12-10 2023-12-15 , SOCIAL Y DE SEGURIDAD Y Based Selection l ation pating municipalities SALUD EN EL TRABAJO PARA LOS ESTUDIOS, DISEÑOS Y O BRAS DE LOS SISTEMAS DE A CUEDUCTO Y ALCANTARILLA DO EN LOS MUNICIPIOS DEL PTSP-BIRF8798-089 / Interve ntoría técnica, administrativa Improving Waterway Transp , financiera, legal, ambiental Quality And Cost- Open - Internationa Under Implement IBRD / 87980 ort in participating municipal Post 430,000.00 0.00 2022-03-16 2022-04-23 2022-04-06 2022-05-20 2022-06-17 2022-07-17 2022-08-21 2022-09-25 2023-07-25 y social de la construcción de Based Selection l ation ities l muelle y terminal portuario en el municipio de La Tola (N ariño) PTSP-BIRF8798-093 / Interve ntoría técnica, administrativa Improving Waterway Transp Quality And Cost- Open - Internationa Pending Impleme , financiera, legal, ambiental IBRD / 87980 ort in participating municipal Post 950,000.00 0.00 2022-10-12 2022-11-02 2022-12-16 2023-01-13 2023-02-12 2023-03-19 2023-04-23 2024-02-23 Based Selection l ntation y social de la construcción de ities l muelle y terminal portuario 1, 2 y 3 PTSP-BIRF8798-097 / Interve ntoría técnica, administrativa Improving Waterway Transp Quality And Cost- Open - Internationa Pending Impleme , financiera, legal, ambiental IBRD / 87980 ort in participating municipal Post 950,000.00 0.00 2023-01-05 2023-01-26 2023-03-11 2023-04-08 2023-05-08 2023-06-12 2023-07-17 2024-05-17 Based Selection l ntation y social de la construcción de ities l muelle y terminal portuario 4, 5 y 6 PTSP-BIRF8798-102 / Estruct Capacity Building and Institu uración del esquema de pres tional Strengthening for wat Quality And Cost- tación de los servicios públic IBRD / 87980 erway transport operators a Post Open - National 380,000.00 0.00 Canceled 2022-03-17 2022-04-07 2022-05-21 2022-06-18 2022-07-18 2022-08-22 2022-09-26 2023-07-26 Based Selection os de acueducto, alcantarilla nd water supply and sanitati do \ aseo en Timbiquí on service providers in parti cipating municipalities Page 3 PTSP-BIRF8798-111 / ESTRU Capacity Building and Institu CTURACIÓN DEL ESQUEMA D tional Strengthening for wat E PRESTACIÓN DE LOS SERVI erway transport operators a Consultant Qualifi Under Implement CIOS PÚBLICOS DE ACUEDUC IBRD / 87980 Post Open - National 285,000.00 0.00 2022-04-27 2022-08-01 2022-05-18 2022-07-01 2022-07-31 2022-09-04 2023-07-01 nd water supply and sanitati cation Selection ation TO, ALCANTARILLADO Y ASE on service providers in parti O EN EL MUNICIPIO DE TIMBI cipating municipalities QUÍ, DEPARTAMENTO DEL CA UCA PTSP-BIRF8798-119 / INTERV ENTORÍA integral técnica, ad ministrativa, financiera, cont Capacity Building and Institu able, ambiental, social y juríd tional Strengthening for wat ica a la consultoría que tiene erway transport operators a Consultant Qualifi Pending Impleme IBRD / 87980 Post Open - National 61,786.00 0.00 2022-08-30 2022-09-19 2022-10-17 2022-11-16 2022-12-21 2023-06-19 como nd water supply and sanitati cation Selection ntation objeto la “ESTRUCTURACIÓN on service providers in parti DEL ESQUEMA DE PRESTACI cipating municipalities ÓN DE LOS SERVICIOS PÚBLI COS DE ACUEDUCTO, ALCAN TARILLADO Y ASEO TIMBIQUI " PTSP-BIRF- 8798-133 / Interv entoría técnica, administrativ a, financiera, legal, ambienta Improving Waterway Transp l y social de los estudios y dis Quality And Cost- Open - Internationa Pending Impleme IBRD / 87980 ort in participating municipal Post 114,205.00 0.00 2023-01-27 2023-02-06 2023-03-22 2023-04-19 2023-05-19 2023-06-23 2023-07-28 2024-07-27 eños finales para la construc Based Selection l ntation ities ción, rehabilitación y mejora miento de la infraestructura de muelles e instalaciones po rtuarias; y para la implement ación de la INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PTSP-BIRF8798-001 / Líder d Project Management and En Individual Consult IBRD / 87980 Post Open 23,598.00 18,126.11 Signed 2019-11-25 2020-01-02 2019-12-04 2021-01-08 2019-12-05 2021-01-28 2019-12-15 2020-02-08 2020-04-13 e Conectividad de Transporte vironmental and Social Mana ant Selection gement PTSP-BIRF8798-028 / Especi Project Management and En Individual Consult IBRD / 87980 Post Limited 17,032.00 0.00 Canceled 2020-01-27 2020-01-28 2020-02-01 2020-02-08 2020-03-07 2020-07-05 alista Ambiental vironmental and Social Mana ant Selection gement PTSP-BIRF8798-029 / Enlace Project Management and En Individual Consult IBRD / 87980 Post Open 7,759.00 0.00 Canceled 2020-01-27 2020-01-28 2020-03-16 2020-03-23 2020-04-20 2020-08-18 Social de Conectividad de Tr vironmental and Social Mana ant Selection ansporte gement PTSP-BIRF8798-030 / Enlace Project Management and En Individual Consult IBRD / 87980 Post Open 7,759.00 0.00 Canceled 2020-01-27 2020-01-28 2020-03-16 2020-03-23 2020-04-20 2020-08-18 Social de Conectividad de Tr vironmental and Social Mana ant Selection ansporte gement PTSP-BIRF8798-031 / Apoyo Project Management and En Técnico del Componente de Individual Consult IBRD / 87980 vironmental and Social Mana Post Limited 7,759.00 0.00 Canceled 2020-01-31 2020-01-31 2020-02-05 2020-02-15 2020-03-06 2020-07-04 Conectividad de Transporte y ant Selection gement Provisión de Agua PTSP-BIRF8798-032 / Apoyo Project Management and En Técnico del Componente de Individual Consult IBRD / 87980 vironmental and Social Mana Post Limited 7,759.00 0.00 Canceled 2020-01-31 2020-01-31 2020-02-05 2020-02-15 2020-03-10 2020-07-08 Conectividad de Transporte y ant Selection gement Provisión de Agua PTSP-BIRF8798-033 / Especi Project Management and En Individual Consult IBRD / 87980 Post Limited 17,032.00 10,993.59 Signed 2020-01-31 2020-01-31 2020-02-05 2020-02-05 2020-02-15 2020-02-14 2020-03-10 2020-05-27 2020-07-08 alista de Conectividad de Tra vironmental and Social Mana ant Selection nsporte gement PTSP-BIRF8798-034 / Viabiliz Project Management and En Individual Consult IBRD / 87980 Post Limited 17,032.00 10,993.59 Signed 2020-01-31 2020-01-31 2020-02-05 2020-03-16 2020-02-15 2020-04-15 2020-03-10 2020-05-27 2020-07-08 ador de Proyectos ante INVIA vironmental and Social Mana ant Selection S gement PTSP-BIRF8798-035 / Especi Project Management and En alista en Agua y Saneamient Individual Consult IBRD / 87980 vironmental and Social Mana Post Direct 17,302.00 39,247.38 Signed 2020-02-26 2020-03-11 2020-03-04 2020-03-23 2020-03-09 2020-07-16 2020-03-19 2020-07-22 2020-07-17 o Básico - Recontratación JAI ant Selection gement RO ALBERTO PÉREZ GÓMEZ PTSP-BIRF8798-036 / Directo Project Management and En ra Ejecutiva / Coordinadora d Individual Consult IBRD / 87980 vironmental and Social Mana Post Direct 17,596.00 67,107.66 Signed 2020-02-26 2020-02-26 2020-03-07 2020-03-06 2020-03-12 2020-03-10 2020-03-22 2020-03-19 2021-03-21 el Proyecto FTSP - Recontrata ant Selection gement ción LUZ AMANDA PULIDO PTSP-BIRF8798-037 / Líder A Project Management and En Individual Consult mbiental - Recontratación RU IBRD / 87980 vironmental and Social Mana Post Limited 15,009.00 57,644.82 Signed 2020-02-27 2020-03-11 2020-03-03 2020-03-16 2020-03-08 2020-03-12 2020-03-18 2020-03-19 2021-03-17 ant Selection TH ALEJANDRA CATACOLI JIM gement ENEZ PTSP-BIRF8798-038 / Líder Fi Project Management and En Individual Consult nanciera - Recontratación CL IBRD / 87980 vironmental and Social Mana Post Direct 15,009.00 57,242.20 Signed 2020-02-26 2020-02-26 2020-03-07 2020-03-06 2020-03-12 2020-03-16 2020-03-22 2020-03-19 2021-03-21 ant Selection AUDIA AGUDELO SEDANO gement PTSP-BIRF8798-039 / Líder d Project Management and En Individual Consult e Adquisiciones - Recontrata IBRD / 87980 vironmental and Social Mana Post Direct 15,009.00 57,242.20 Signed 2020-02-26 2020-02-26 2020-03-07 2020-03-05 2020-03-12 2020-03-11 2020-03-22 2020-03-19 2021-03-21 ant Selection ción ELKIN ADOLFO PINILLA C gement AÑÓN PTSP-BIRF8798-040 / Líder d Project Management and En Individual Consult e Seguridad - Recontratación IBRD / 87980 vironmental and Social Mana Post Direct 15,009.00 57,242.09 Signed 2020-02-26 2022-03-11 2020-03-07 2020-03-06 2020-03-12 2020-03-11 2020-03-22 2020-03-22 2021-03-21 ant Selection WILSON LAVERDE FLÓREZ gement PTSP-BIRF8798-041 / Especi Project Management and En Individual Consult alista Financiera - Recontrata IBRD / 87980 vironmental and Social Mana Post Direct 11,355.00 43,304.24 Signed 2020-02-26 2020-02-26 2020-03-07 2020-03-10 2020-03-12 2020-03-12 2020-03-22 2020-03-19 2021-03-21 ant Selection ción SANDRA LORENA PEÑA gement PTSP-BIRF8798-042 / Líder C Project Management and En omponente Agua y Saneamie Individual Consult IBRD / 87980 vironmental and Social Mana Post Direct 37,523.00 57,644.82 Signed 2020-03-24 2020-04-01 2020-04-03 2020-04-07 2020-04-08 2020-04-01 2020-04-18 2020-04-07 2021-04-18 nto Básico - Recontratación F ant Selection gement ABIOLA IGUARAN ARAUJO PTSP-BIRF8798-043 / Líder S Project Management and En Individual Consult ocial - Recontratación KELLY IBRD / 87980 vironmental and Social Mana Post Direct 15,009.00 57,666.59 Signed 2020-04-06 2020-04-06 2020-04-16 2020-04-06 2020-04-21 2020-04-10 2020-05-01 2020-04-24 2021-04-30 ant Selection LORENA RUIZ GARCIA gement PTSP-BIRF8798-044 / Especi Project Management and En alista de Adquisiciones BM - Individual Consult IBRD / 87980 vironmental and Social Mana Post Direct 56,773.00 43,625.30 Signed 2020-04-16 2020-02-14 2020-04-26 2020-04-10 2020-05-01 2020-04-15 2020-05-11 2020-05-05 2021-05-10 Recontratación JOHN MAURIC ant Selection gement IO OTALVARO CORTES PTSP-BIRF8798-045 / Actuali zación, Ajustes y Complemen Improving Water Supply and Pending Impleme to de los Diseños para la Opti IBRD / 87980 Sanitation Services in partici Post Direct Selection Direct 69,865.00 0.00 2020-05-07 2020-05-17 2020-06-06 2020-09-19 ntation mización y Ampliación del Ac pating municipalities ueducto del Municipio de Tim biquí - Cauca Page 4 PTSP-BIRF8798-046 / Especi Project Management and En Individual Consult IBRD / 87980 Post Limited 11,355.00 0.00 Canceled 2020-05-07 2020-05-07 2020-05-12 2020-06-02 2020-07-07 2021-01-03 alista de Planeación y Segui vironmental and Social Mana ant Selection miento gement PTSP-BIRF8798-047 / Líder d Project Management and En Individual Consult e Conectividad - Recontrataci IBRD / 87980 vironmental and Social Mana Post Direct 75,046.00 57,644.82 Signed 2020-05-14 2020-06-12 2020-05-24 2020-05-22 2020-05-29 2020-06-04 2020-06-08 2020-06-09 2021-06-07 ant Selection ón DIEGO FERNANDO DUQUE gement BASTIDAS PTSP-BIRF8798-052 / Líder d Project Management and En Individual Consult Pending Impleme IBRD / 87980 Post Limited 15,009.00 0.00 2020-06-24 2020-07-04 2020-07-09 2020-07-19 2021-07-18 e Planeación y Seguimiento vironmental and Social Mana ant Selection ntation gement PTSP-BIRF8798-048 / Interve ntoría de Estudios y Diseños Improving Water Supply and Individual Consult Acueducto y Alcantarillado d IBRD / 87980 Sanitation Services in partici Post Direct 13,932.00 12,466.75 Signed 2020-06-12 2020-07-09 2020-06-22 2020-07-15 2020-07-02 2020-07-27 2020-07-17 2020-08-27 2021-07-16 ant Selection e Timbiquí y Francisco Pizarr pating municipalities o - Director de Interventoría PTSP-BIRF8798-049 / Interve ntoría de Estudios y Diseños Improving Water Supply and Individual Consult Acueducto y Alcantarillado d IBRD / 87980 Sanitation Services in partici Post Direct 4,917.00 4,509.25 Signed 2020-06-12 2020-07-09 2020-06-22 2020-07-15 2020-07-02 2020-07-27 2020-07-17 2020-08-27 2021-07-16 ant Selection e Timbiquí y Francisco Pizarr pating municipalities o - Especialista Electromecán ico PTSP-BIRF8798-050 / Interve ntoría de Estudios y Diseños Improving Water Supply and Individual Consult Acueducto y Alcantarillado d IBRD / 87980 Sanitation Services in partici Post Direct 8,072.00 7,294.38 Signed 2020-06-12 2020-07-09 2020-06-22 2020-07-15 2020-07-02 2020-07-27 2020-07-17 2020-08-27 2021-07-16 ant Selection e Timbiquí y Francisco Pizarr pating municipalities o - Especialista Estructural PTSP-BIRF8798-051 / interve ntoría de Estudios y Diseños Improving Water Supply and Individual Consult Acueducto y Alcantarillado d IBRD / 87980 Sanitation Services in partici Post Direct 5,818.00 5,263.20 Signed 2020-06-04 2020-07-09 2020-06-14 2020-07-15 2020-06-24 2020-07-24 2020-07-09 2020-08-27 2021-07-08 ant Selection e Timbiquí y Francisco Pizarr pating municipalities o - Especialista Geotécnia PTSP-BIRF8798-061 / AUDIT ORÍA DE LOS ESTADOS FINA NCIEROS DE PROPÓSITO ESP Project Management and En ECIAL Y ASEGURAMIENTO RA IBRD / 87980 vironmental and Social Mana Post Direct Selection Direct 10,200.00 20,172.50 Signed 2020-10-19 2020-11-05 2020-11-08 2020-11-19 2021-01-08 2021-02-20 2021-07-07 ZONABLE SOBRE LOS PROCE gement SOS DE ADQUISICIONES DEL PROYECTO/PROGRAMA FINA NCIADO POR EL BID Y EL BAN CO MUNDIAL A TRAVÉS DE P RÉSTAMOS PTSP-BIRF8798-062 / Directo Project Management and En ra Ejecutiva / Coordinadora d Individual Consult IBRD / 87980 vironmental and Social Mana Post Direct 12,900.00 62,078.79 Signed 2021-02-26 2021-03-15 2021-03-08 2021-03-15 2021-03-13 2021-03-13 2021-03-18 2021-03-19 2022-03-17 el Proyecto FTSP - Recontrata ant Selection gement ción LUZ AMANDA PULIDO PTSP-BIRF8798-063 / Líder C Project Management and En omponente Agua y Saneamie Individual Consult IBRD / 87980 vironmental and Social Mana Post Direct 27,500.00 52,952.63 Signed 2021-03-01 2021-03-15 2021-03-11 2021-03-15 2021-03-16 2021-03-16 2021-04-08 2021-04-09 2022-04-07 nto Básico - Recontratación F ant Selection gement ABIOLA IGUARAN ARAUJO PTSP-BIRF8798-064 / Líder d Project Management and En Individual Consult e Adquisiciones - Recontrata IBRD / 87980 vironmental and Social Mana Post Direct 11,000.00 52,952.63 Signed 2021-02-26 2021-03-15 2021-03-08 2021-03-15 2021-03-13 2021-03-16 2021-03-18 2021-03-19 2022-03-17 ant Selection ción ELKIN ADOLFO PINILLA C gement AÑÓN PTSP-BIRF8798-065 / Líder Fi Project Management and En Individual Consult nanciera - Recontratación CL IBRD / 87980 vironmental and Social Mana Post Direct 11,000.00 52,952.63 Signed 2021-02-26 2021-03-15 2021-03-08 2021-03-15 2021-03-13 2021-03-13 2021-03-18 2021-03-19 2022-03-17 ant Selection AUDIA AGUDELO SEDANO gement PTSP-BIRF8798-066 / Líder S Project Management and En Individual Consult ocial - Recontratación KELLY IBRD / 87980 vironmental and Social Mana Post Direct 11,000.00 52,952.63 Signed 2021-03-19 2021-03-15 2021-03-29 2021-03-29 2021-04-03 2021-04-03 2021-04-23 2021-04-24 2022-04-22 ant Selection LORENA RUIZ GARCIA gement PTSP-BIRF8798-067 / Líder d Project Management and En Individual Consult e Seguridad - Recontratación IBRD / 87980 vironmental and Social Mana Post Direct 11,000.00 52,952.63 Signed 2021-02-26 2021-03-15 2021-03-08 2021-03-18 2021-03-13 2021-03-18 2021-03-22 2021-03-24 2022-03-21 ant Selection WILSON LAVERDE FLÓREZ gement PTSP-BIRF8798-068 / Contra tación Líder Ambiental para l a ejecución y cumplimiento d Project Management and En e los Marcos de Gestión Ambi IBRD / 87980 vironmental and Social Mana Post Direct Selection Direct 5,496.00 26,476.31 Signed 2021-03-08 2021-03-15 2021-03-09 2021-03-15 2021-03-22 2021-03-24 2021-09-21 ental adoptados para la ejec gement ución del Fondo para el desar rollo del Plan Todos Somos P AZcífico - Fernando Rey PTSP-BIRF8649-070 / Especi Project Management and En Individual Consult alista Financiera - Recontrata IBRD / 87980 vironmental and Social Mana Post Direct 8,315.00 40,059.14 Signed 2021-03-08 2021-03-15 2021-03-09 2021-03-15 2021-03-14 2021-03-16 2021-03-18 2021-03-19 2022-03-17 ant Selection ción Sandra Lorena Peña gement PTSP-BIRF8649-069 / Especi Project Management and En alista de Adquisiciones - Cont IBRD / 87980 vironmental and Social Mana Post Direct Selection Direct 20,079.00 40,059.14 Signed 2021-03-08 2021-03-15 2021-03-09 2021-03-15 2021-03-15 2021-03-17 2022-03-14 ratación Tulio José Fuentes gement PTSP-BIRF8649-071 / Especi alista de Planeación y Segui miento. - Brindar apoyo profe Project Management and En Individual Consult sional en la gestión de planifi IBRD / 87980 vironmental and Social Mana Post Open 10,394.00 18,200.98 Signed 2021-03-11 2021-03-15 2021-03-16 2021-03-22 2021-03-17 2021-03-18 2021-03-25 2021-03-27 2021-09-24 ant Selection cación, monitoreo y seguimie gement nto a las actividades del Fon do para el Desarrollo del Plan Todos Somos Pazcífico. PTSP-BIRF8798-075 / Contra tación Líder Fortalecimiento I nstitucional para Liderar la i Project Management and En mplementación y ejecución d IBRD / 87980 vironmental and Social Mana Post Direct Selection Direct 5,496.00 0.00 Canceled 2021-04-14 2021-04-19 2021-05-17 2021-11-16 e los componentes de Capaci gement dad y Fortalecimiento Institu cional de Agua y Saneamient o Básico - Jorge Silva PTSP-BIRF8798-076 / Contra tación Líder Fortalecimiento I nstitucional para Liderar la i Project Management and En mplementación y ejecución d Individual Consult IBRD / 87980 vironmental and Social Mana Post Direct 5,496.00 26,476.31 Signed 2021-04-15 2021-04-19 2021-04-22 2021-04-22 2021-04-23 2021-04-23 2021-05-17 2021-05-12 2021-11-16 e los componentes de Capaci ant Selection gement dad y Fortalecimiento Institu cional de Agua y Saneamient o Básico para el desarrollo de l Plan Todos Somos PAZcífico - Jorge Silva. PTSP-BIRF8798-077 / Especi Project Management and En alista de Adquisiciones - Rec Individual Consult IBRD / 87980 vironmental and Social Mana Post Direct 8,315.00 40,059.14 Signed 2021-04-22 2021-04-26 2021-04-24 2021-04-26 2021-04-26 2021-04-26 2021-05-04 2021-05-07 2022-05-03 ontratación JOHN MAURICIO ant Selection gement OTÁLVARO CORTÉS Page 5 PTSP-BIRF8798-079 / Líder d Project Management and En Individual Consult e Conectividad - Recontrataci IBRD / 87980 vironmental and Social Mana Post Direct 54,958.00 52,952.63 Signed 2021-05-18 2021-05-26 2021-05-20 2021-05-26 2021-05-24 2021-05-24 2021-06-08 2021-06-09 2022-06-07 ant Selection ón DIEGO FERNANDO DUQUE gement BASTIDAS PTSP-BIRF8798-081 / Líder d Project Management and En Individual Consult e Planeación y Seguimiento IBRD / 87980 vironmental and Social Mana Post Direct 10,992.00 52,952.63 Signed 2021-06-09 2021-06-10 2021-06-19 2021-06-19 2021-06-24 2021-06-24 2021-06-30 2021-07-01 2022-06-29 ant Selection - Recontratación Joan Natalie gement Garzón PTSP-BIRF8798-083 / AUDIT ORÍA DE LOS ESTADOS FINA NCIEROS DE PROPÓSITO ESP ECIAL Y ASEGURAMIENTO Project Management and En RAZONABLE SOBRE LOS PRO IBRD / 87980 vironmental and Social Mana Post Direct Selection Direct 21,808.00 19,036.57 Signed 2021-09-06 2021-09-15 2021-09-26 2021-10-04 2021-12-23 2022-02-01 2022-06-21 CESOS DE ADQUISICIONES D gement EL PROYECTO/PROGRAMA FI NANCIADO POR EL BID Y EL B ANCO MUNDIAL A TRAVÉS DE PRÉSTAMOS PTSP-BIRF8798-084 / Líder A Project Management and En Individual Consult mbiental FTSP - Recontrataci IBRD / 87980 vironmental and Social Mana Post Direct 5,935.00 26,476.31 Signed 2021-09-09 2021-09-09 2021-09-09 2021-09-09 2021-09-20 2021-09-20 2021-09-23 2021-09-24 2022-03-22 ant Selection ón Fernando Rey gement PTSP-BIRF8798-085 / Especi Project Management and En alista de Planeación y Segui Individual Consult IBRD / 87980 vironmental and Social Mana Post Direct 22,425.00 40,059.14 Signed 2021-09-09 2021-09-09 2021-09-17 2021-09-17 2021-09-17 2021-09-17 2021-09-27 2021-09-29 2022-09-26 miento FTSP - Recontratación ant Selection gement Natalia García Medina Capacity Building and Institu PTSP-BIRF8798-086 / Líder d tional Strengthening for wat e Fortalecimiento Institucion Individual Consult IBRD / 87980 erway transport operators a Post Direct 11,870.00 52,952.63 Signed 2021-10-19 2021-10-20 2021-10-19 2021-10-20 2021-10-26 2021-10-26 2021-11-11 2021-11-12 2022-11-10 al - Recontratación Jorge Ern ant Selection nd water supply and sanitati esto Silva on service providers in parti cipating municipalities PTSP-BIRF8798-087 / Líder S Project Management and En Individual Consult IBRD / 87980 Post Open 14,837.00 24,066.33 Signed 2021-10-27 2021-10-27 2021-11-30 2022-02-22 2021-12-03 2022-02-25 2021-12-22 2022-04-10 2022-06-19 ocial FTSP vironmental and Social Mana ant Selection gement PTSP-BIRF8798-103 / Realiza r la evaluación de medio tér mino del proyecto “Mejora de Project Management and En la Conectividad y de la Provis Individual Consult Under Implement IBRD / 87980 vironmental and Social Mana Post Limited 12,545.00 0.00 2022-03-10 2022-03-01 2022-03-15 2022-04-05 2022-05-10 2022-08-11 ión de Agua en el Marco del ant Selection ation gement Plan PAZcífico” en cumplimie nto de las condiciones establ ecidas en el Contrato de Prés tamo BIRF N° 8798-CO. PTSP-BIRF8798-104 / Recont Improving Water Supply and Individual Consult ratación Líder de Agua BM - F IBRD / 87980 Sanitation Services in partici Post Direct 31,342.00 57,727.68 Signed 2022-03-04 2022-03-04 2022-03-14 2022-03-04 2022-03-19 2022-03-09 2022-04-08 2022-04-10 2023-04-07 ant Selection abiola del Rosario Iguarán pating municipalities PTSP-BIRF8798-106 / Recont Project Management and En Individual Consult ratación Líder de Adquisicion IBRD / 87980 vironmental and Social Mana Post Direct 12,537.00 52,952.63 Signed 2022-03-04 2022-03-04 2022-03-14 2022-03-14 2022-03-14 2022-03-14 2022-03-18 2022-03-28 2023-03-17 ant Selection es - Élkin Pinilla gement PTSP-BIRF8798-107 / Recont Project Management and En Individual Consult ratación Líder Financiera - Cl IBRD / 87980 vironmental and Social Mana Post Direct 12,537.00 52,952.63 Signed 2022-03-04 2022-03-04 2022-03-14 2022-03-14 2022-03-16 2022-03-16 2022-03-18 2022-03-19 2023-03-17 ant Selection audia Agudelo gement PTSP-BIRF8798-108 / Recont Project Management and En Individual Consult IBRD / 87980 Post Direct 6,269.00 26,476.31 Signed 2022-03-04 2022-03-04 2022-03-09 2022-03-09 2022-03-15 2022-03-15 2022-03-23 2022-03-24 2022-09-22 ratación Líder Ambiental - Fe vironmental and Social Mana ant Selection rnando Rey gement PTSP-BIRF8798-110 / Recont Project Management and En Individual Consult Under Implement ratación Especialista Financie IBRD / 87980 vironmental and Social Mana Post Direct 9,484.00 0.00 2022-03-04 2022-03-04 2022-03-05 2022-03-10 2022-03-18 2023-03-17 ant Selection ation ra - Sandra Lorena Peña gement PTSP-BIRF8798-105 / Recont Project Management and En Individual Consult ratación Directora Ejecutiva- IBRD / 87980 vironmental and Social Mana Post Direct 14,698.00 62,078.79 Signed 2022-03-04 2022-03-04 2022-03-14 2022-03-14 2022-03-15 2022-03-14 2022-03-18 2022-03-19 2023-03-17 ant Selection Coordinadora General - Luz A gement manda Pulido PTSP-BIRF8798-109 / Recont Project Management and En Individual Consult ratación Especialista de Adqu IBRD / 87980 vironmental and Social Mana Post Direct 23,711.00 43,671.56 Signed 2022-03-10 2022-03-04 2022-03-20 2022-03-20 2022-03-20 2022-03-07 2022-03-26 2022-03-17 2023-03-25 ant Selection isiciones - Tulio José Fuentes gement PTSP-BIRF8798-112 / Recont Project Management and En Individual Consult Under Implement ratación Líder de Seguridad - IBRD / 87980 vironmental and Social Mana Post Direct 5,935.00 0.00 2022-04-26 2022-05-05 2022-05-02 2022-05-02 2022-05-04 2022-05-05 2022-11-04 ant Selection ation Wilson Laverde gement PTSP-BIRF8798-113 / Liderar los procesos de adquisicione s que adelanta la Unidad Nac ional para la Gestión del Ries Project Management and En Individual Consult Under Implement go de Desastres como entida IBRD / 87980 vironmental and Social Mana Post Limited 11,870.00 0.00 2022-05-23 2022-05-23 2022-05-28 2022-06-15 2022-06-02 2022-06-17 2023-06-16 ant Selection ation d ejecutora del Fondo para el gement Desarrollo del Plan Todos So mos PAZcífico, según las Polí ticas, normas y regulaciones del BID y Banco M. PTSP-BIRF8798-114 / Liderar la planificación, estructuració Capacity Building and Institu n, seguimiento y gestión de l tional Strengthening for wat os proyectos de Conectividad erway transport operators a Individual Consult Under Implement de Transporte que hagan par IBRD / 87980 Post Direct 60,000.00 0.00 2022-05-27 2022-05-26 2022-05-29 2022-06-02 2022-06-07 2023-06-06 nd water supply and sanitati ant Selection ation te del préstamo BIRF 8798 - on service providers in parti CO, ejecutado por la Unidad cipating municipalities Nacional para la Gestión del Riesgo de Desastres como en tidad ejecutora. PTSP-BIRF8798-115 / Liderar la planificación, monitoreo, s eguimiento y gestión de los p réstamos del BID y el Banco Project Management and En Individual Consult Pending Impleme Mundial, ejecutados por la U IBRD / 87980 vironmental and Social Mana Post Direct 11,870.00 0.00 2022-06-16 2022-06-17 2022-06-24 2022-06-29 2023-06-29 ant Selection ntation nidad Nacional para la Gestió gement n del Riesgo de Desastres co mo entidad ejecutora del Fon do para el Desarrollo del Plan Todos Somos Pazc PTSP-BIRF8798-116 / Brindar apoyo profesional como Espe cialista de Adquisiciones en l Project Management and En os procesos que adelanta la Individual Consult Under Implement IBRD / 87980 vironmental and Social Mana Post Limited 20,979.00 0.00 2022-07-11 2022-07-19 2022-07-16 2022-08-06 2022-09-10 2023-03-09 Unidad Nacional para la Gesti ant Selection ation gement ón del Riesgo de Desastres c omo entidad ejecutora del Fo ndo para el Desarrollo del Pla n Todos Somos PAZcífico. Page 6 PTSP-BIRF8798-118 / Especi Project Management and En alista de Planeación y Segui Individual Consult Pending Impleme IBRD / 87980 vironmental and Social Mana Post Direct - National 20,979.00 0.00 2022-08-30 2022-08-30 2022-09-28 2022-09-28 2023-09-27 miento FTSP - Recontratación ant Selection ntation gement Natalia García Medina PTSP-BIRF8798-120 / Liderar la planificación, seguimiento y gestión ambiental de los pr oyectos que se adelanten en Project Management and En Individual Consult Pending Impleme el marco de los prestamos de IBRD / 87980 vironmental and Social Mana Post Direct - National 5,546.00 0.00 2022-09-19 2022-09-29 2022-10-20 2022-10-28 2023-04-26 ant Selection ntation l BIRF y el Banco Mundial, eje gement cutados por la Unidad Nacion al para la Gestión del Riesgo Desastres como entidad ejec utora del Fondo. PTSP-BIRF8798-121 / Coordi nar la implementación y sup ervisión de los préstamos del Project Management and En BID y el Banco Mundial, ejecu Individual Consult IBRD / 87980 vironmental and Social Mana Post Open - National 13,004.00 0.00 Canceled 2022-09-23 2022-09-19 2022-10-15 2022-10-17 2022-11-21 2023-05-20 tados por la Unidad Nacional ant Selection gement para la Gestión del Riesgo de Desastres como entidad ejec utora del Fondo para el Desa rrollo del Plan Todos Somos P AZcífico PTSP-BIRF-8798-122 / Presta r los servicios jurídicos como especialista para los proceso s de adquisiciones del Fondo Project Management and En Individual Consult Pending Impleme para el Desarrollo del Plan To IBRD / 87980 vironmental and Social Mana Post Open - National 8,392.00 0.00 2022-10-03 2022-11-21 2022-12-12 2023-01-16 2023-07-15 ant Selection ntation dos Somos PAZcífico que ade gement lanta como entidad ejecutora la Uni-dad Nacional para la G estión del Riesgo de Desastr es, en el marco d PTSP-BIRF-8798-123 / AUDIT ORÍA DE LOS ESTADOS FINA NCIEROS DE PROPÓSITO ESP Project Management and En ECIAL Y ASEGURAMIENTO RA Pending Impleme IBRD / 87980 vironmental and Social Mana Post Direct Selection Direct - National 21,217.00 0.00 2022-10-10 2022-10-16 2023-01-09 2023-05-09 ZONABLE SOBRE LOS PROCE ntation gement SOS DE ADQUISICIONES DEL PROYECTO/PROGRAMA FINA NCIADO POR EL BID Y EL BAN CO MUNDIAL A TRAVÉS DE P RÉSTAMOS PTSP-BIRF-8798-124 / Coordi nar la implementación y sup ervisión de los préstamos del Project Management and En BID y el Banco Mundial, ejecu Individual Consult Under Implement IBRD / 87980 vironmental and Social Mana Post Limited 13,004.00 0.00 2022-10-10 2022-10-07 2022-10-15 2022-09-27 2022-11-05 2022-12-10 2023-06-08 tados por la Unidad Nacional ant Selection ation gement para la Gestión del Riesgo de Desastres como entidad ejec utora del Fondo para el Desa rrollo del Plan Todos Somos P AZcífico PTSP-BIRF-8798-126 / Lidera r el componente social de los proyectos que se generen en el marco de los préstamos de Project Management and En Individual Consult Pending Impleme l Banco Mundial ejecutados p IBRD / 87980 vironmental and Social Mana Post Direct - National 5,826.00 0.00 2022-11-07 2022-11-17 2022-12-08 2023-01-12 2023-07-11 ant Selection ntation or la Unidad Nacional para la gement Gestión del Riesgo de Desast res como entidad ejecutora d el Fondo para el Desarrollo d el Plan Todos Somos PTSP-BIRF-8798-127 / Lidera r la planificación, estructurac Capacity Building and Institu ión, seguimiento y gestión de tional Strengthening for wat los proyectos de Capacidad y erway transport operators a Individual Consult Pending Impleme Fortalecimiento Institucional IBRD / 87980 Post Direct - National 2,773.00 0.00 2022-11-11 2022-11-16 2022-12-07 2023-01-11 2023-07-10 nd water supply and sanitati ant Selection ntation que hagan parte de los prést on service providers in parti amos del BID y el Banco Mun cipating municipalities dial, ejecutados por la Unida d Nacional para la Gestión de l Riesgo de Desa PTSP-BIRF-8798-128 / Lidera r los procesos de adquisicion es que adelanta la Unidad Na cional para la Gestión del Rie Project Management and En Individual Consult Under Implement sgo de Desastres como entid IBRD / 87980 vironmental and Social Mana Post Open - National 11,092.00 0.00 2022-11-11 2022-09-15 2022-12-20 2022-11-23 2023-01-10 2022-12-19 2023-02-14 2023-08-13 ant Selection ation ad ejecutora del Fondo para gement el Desarrollo del Plan Todos Somos PAZcífico, según las P olíticas, normas y regulacion es del BID y el Banc PTSP-BIRF-8798-129 / Lidera r las actividades relacionad as con protocolos y herrami Project Management and En entas de seguridad, para miti Pending Impleme IBRD / 87980 vironmental and Social Mana Post Direct Selection Direct - National 2,773.00 0.00 2022-11-08 2022-11-16 2023-01-20 2023-07-19 gar las posibles amenazas o ntation gement riesgos en la ejecución de los proyectos que se desarrollan en el marco de los préstamos del BID y el Banco Mundial, q ue ejecuta la PTSP-BIRF-8798-131 / Brinda r apoyo profesional como esp ecialista de planeación, moni toreo, seguimiento y gestión Project Management and En Individual Consult Pending Impleme de los préstamos del Banco IBRD / 87980 vironmental and Social Mana Post Direct - National 23,731.00 0.00 2023-01-27 2023-02-01 2023-02-22 2023-03-29 2023-09-25 ant Selection ntation Mundial, ejecutados por la U gement nidad Nacional para la Gestió n del Riesgo de Desastres co mo entidad ejecutora del Fon do para el Desarrollo d PTSP-BIRF8798-132 / Liderar la planificación, seguimiento y gestión ambiental de los pr oyectos que se adelanten en Project Management and En Pending Impleme el marco de los préstamos de IBRD / 87980 vironmental and Social Mana Post Direct Selection Direct - National 12,548.00 0.00 2023-01-27 2023-02-01 2023-04-07 2023-10-04 ntation l BID y el Banco Mundial, ejec gement utados por la Unidad Naciona l para la Gestión del Riesgo d e Desastres como entidad ej ecutora del Fondo PTSP-BIRF-8798-134 / Realiz ar apoyo como profesional es pecializado en los procesos c ontractuales y relaciones jurí Project Management and En Individual Consult Pending Impleme dico negociales del Fondo pa IBRD / 87980 vironmental and Social Mana Post Limited 9,493.00 0.00 2023-02-06 2023-02-11 2023-03-04 2023-04-08 2023-10-05 ant Selection ntation ra el Desarrollo del Plan Todo gement s Somos PAZcífico - FTSP, cu ya entidad ejecutora es la Un idad Nacional para la Gestión del Riesgo de Des Page 7 PTSP-BIRF-8798-135 / TDR E specialista Financiera en la g estión presupuestal y financi era de los préstamos del BID Project Management and En Individual Consult Pending Impleme y el Banco Mundial, ejecutad IBRD / 87980 vironmental and Social Mana Post Direct - National 9,493.00 0.00 2023-03-13 2023-03-22 2023-04-12 2023-05-17 2023-11-13 ant Selection ntation os por la Unidad Nacional par gement a la Gestión del Riesgo de De sastres como entidad ejecuto ra del Fondo para el Desarrol lo del Plan Todos S PTSP-BIRF-8798-136 / Lidera r la gestión presupuestal y fi nanciera de los préstamos de Project Management and En l BID y el Banco Mundial, ejec Individual Consult Pending Impleme IBRD / 87980 vironmental and Social Mana Post Direct - National 12,548.00 0.00 2023-03-13 2023-03-22 2023-04-12 2023-05-17 2023-11-13 utados por la Unidad Naciona ant Selection ntation gement l para la Gestión del Riesgo d e Desastres como entidad ej ecutora del Fondo para el De sarrollo del Plan Todos Somo s PAZcífico. PTSP-BIRF-8798-137 / Lidera r las actividades relacionadas con protocolos y herramienta s de seguridad, para mitigar l Project Management and En as posibles amenazas o riesg IBRD / 87980 vironmental and Social Mana Post Direct Selection Direct - National 12,548.00 0.00 Under Review 2023-03-13 2023-03-23 2023-03-22 2023-05-26 2023-11-22 os en la ejecución de los proy gement ectos que se desarrollan en e l marco de los préstamos del BID y el Banco Mundial, que ejecuta la Unida PTSP-BIRF-8798-139 / Lidera r la planificación, estructurac ión, seguimiento y gestión de los proyectos de Capacidad y Improving Waterway Transp Individual Consult Pending Impleme Fortalecimiento Institucional IBRD / 87980 ort in participating municipal Post Direct - National 12,548.00 0.00 2023-03-13 2023-03-22 2023-04-12 2023-05-17 2023-11-13 ant Selection ntation que hagan parte de los prést ities amos del BID y el Banco Mun dial, ejecutados por la Unida d Nacional para la Gestión de l Riesgo de Desa PTSP-BIRF-8798-141 / Presta r los servicios juridicos como especialista al Ordenador del Gasto, en los procesos de ad Project Management and En Individual Consult Pending Impleme quisiciones, así como en las IBRD / 87980 vironmental and Social Mana Post Direct - National 7,977.00 0.00 2023-04-11 2023-04-21 2023-05-12 2023-06-16 2023-12-13 ant Selection ntation actividades inherentes a la ej gement ecución de los proyectos que se desarrollan en el marco d e los prestamos del BID y el Banco Mundial.. PTSP-BIRF-8798-142 / Lidera r la planificación,estructuraci ón, seguimiento y gestión de los proyectos de Agua y Sane Improving Water Supply and Individual Consult Pending Impleme amiento Básico que hagan p IBRD / 87980 Sanitation Services in partici Post Direct - National 15,684.00 0.00 2023-04-11 2023-04-21 2023-05-12 2023-06-16 2023-12-13 ant Selection ntation arte de los préstamos del Ba pating municipalities nco Mundial 8649 CO y 8798 CO, ejecutados por la Unidad Nacional para la Gestión del Riesgo de Desastres. PTSP-BIRF-8798-143 / Lidera r el componente social de los proyectos que se generen en el marco de los préstamos de Project Management and En Individual Consult Under Implement l Banco Mundial ejecutados p IBRD / 87980 vironmental and Social Mana Post Limited 31,370.00 0.00 2023-05-05 2023-05-11 2023-05-10 2023-05-31 2023-07-05 2024-01-01 ant Selection ation or la Unidad Nacional para la gement Gestión del Riesgo de Desast res como entidad ejecutora d el Fondo para el Desarrollo d el Plan Todos Somos PTSP-BIRF-8798-138 / Lidera r el componente social de los proyectos que se generen en el marco de los préstamos de Project Management and En Individual Consult l Banco Mundial ejecutados p IBRD / 87980 vironmental and Social Mana Post Limited 15,685.00 0.00 Canceled 2023-03-13 2023-04-04 2023-03-17 2023-04-07 2023-05-12 2023-11-08 ant Selection or la Unidad Nacional para la gement Gestión del Riesgo de Desast res como entidad ejecutora d el Fondo para el Desarrollo d el Plan Todos Somos PTSP-BIRF-8798-145 / Lidera r la planificación, monitoreo, seguimiento y gestión de los Project Management and En préstamos del BID y el Banco Individual Consult Under Implement IBRD / 87980 vironmental and Social Mana Post Direct - National 12,548.00 0.00 2023-05-26 2023-05-25 2023-06-05 2023-06-26 2023-07-31 2024-01-27 Mundial, ejecutados por la U ant Selection ation gement nidad Nacional para la Gestió n del Riesgo de Desastres co mo entidad ejecutora del FTS P. NATALIE GARZON PSTP-BIRF-8798-146 / Brinda r acompañamiento técnico pr ofesional ambiental en la ges Project Management and En tión de los Planes de Manejo Individual Consult IBRD / 87980 vironmental and Social Mana Post Limited 5,307.00 0.00 Under Review 2023-05-26 2023-05-25 2023-05-31 2023-06-21 2023-07-26 2024-01-22 Ambiental y Estudios de Imp ant Selection gement acto Ambiental de los proyec tos que se desarrollen en el marco del PTSP, que adelant a como entidad ejecutora la UNGRD PTSP-BIRF-8798-147 / Lidera r la planificación, estructurac ión, seguimiento y gestión de Improving Waterway Transp Individual Consult Under Implement los proyectos de Conectivida IBRD / 87980 ort in participating municipal Post Direct - National 31,370.00 0.00 2023-05-26 2023-05-30 2023-06-05 2023-06-26 2023-07-31 2024-01-27 ant Selection ation d de Transporte que hagan p ities arte del préstamo BIRF 8798 - CO, ejecutado por la UNGR D como entidad ejecutora del FTSP PTSP-BIRF-8798-148 / Brinda r apoyo profesional como Esp ecialista de Adquisiciones del préstamo 8798-CO en los pro Project Management and En Individual Consult Under Implement cesos que adelanta la Unidad IBRD / 87980 vironmental and Social Mana Prior Limited 47,463.00 0.00 2023-05-26 2023-06-07 2023-05-31 2023-06-21 2023-07-26 2024-01-22 ant Selection ation Nacional para la Gestión del gement Riesgo de Desastres como en tidad ejecutora del Fondo par a el Desarrollo del Plan Todos Somos PAZcífico. Page 8 PTSP-BIRF-8798-149 / Presta r los servicios de acompaña miento integral y exclusivo al Ordenador del Gasto del FTS Project Management and En Individual Consult Pending Impleme P, en las actividades inherent IBRD / 87980 vironmental and Social Mana Post Limited 11,866.00 0.00 2023-06-02 2023-06-07 2023-06-28 2023-08-02 2024-01-29 ant Selection ntation es a la ejecución de los proye gement ctos que se desarrollan en el marco de los préstamos del BID y el Banco Mundial, que ejecuta la UNGRD. PTSP-BIRF-8798-150 / Coordi nar y dirigir la implementació n y supervisión de los présta mos del BID y el Banco Mund Project Management and En Individual Consult Pending Impleme ial, ejecutados por la Unidad IBRD / 87980 vironmental and Social Mana Post Direct - National 8,581.00 0.00 2023-06-02 2023-06-12 2023-07-03 2023-08-07 2024-02-03 ant Selection ntation Nacional para la Gestión del gement Riesgo de Desastres como en tidad ejecutora del Fondo par a el Desarrollo del Plan Todos Somos PAZcífico. PTSP-BIRF-8798-152 / LÍDER Improving Water Supply and COMPONENTE AGUA Y SANE Individual Consult Pending Impleme IBRD / 87980 Sanitation Services in partici Post Open - National 62,739.00 0.00 2023-06-09 2023-07-28 2023-08-18 2023-09-22 2024-03-20 AMIENTO BÁSICO (FRANCISC ant Selection ntation pating municipalities O PZARRO - TIMBIQUI) PTSP-BIRF-8798-153 / Brinda r apoyo profesional como Esp ecialista de Adquisiciones del préstamo 8798-CO en los pro Project Management and En Individual Consult Pending Impleme cesos que adelanta la Unidad IBRD / 87980 vironmental and Social Mana Post Open - National 47,463.00 0.00 2023-06-13 2023-08-01 2023-08-22 2023-09-26 2024-03-24 ant Selection ntation Nacional para la Gestión del gement Riesgo de Desastres como en tidad ejecutora del Fondo par a el Desarrollo del Plan Todos Somos PAZcífico. Page 9 PROCUREMENT PLAN General 1. Project Information a. Country: Federal Republic of Somalia b. Project Name: Improving Healthcare Services in Somalia ("Damal Caafimaad") Project c. Project Number: P172031 d. Total Finance: USD 100 million 2. Project Implementation Agency: Ministry of Health 3. Date of Project Plan: May, 2021 4. Period Covered by this Procurement: June 2021- May 2022 I. Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016 revised November 2017, August 2018 and November 2020 and ) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. II. Bank’s Standard Procurement Document: The Bank’s standard Procurement Documents shall be used for all contracts subject to international competitive procurement and those contracts as specified into Procurement Plan tables in STEP III. National Procurement Arrangements: Not applicable IV. Prequalification: Not applicable V. Leased Assets: Not Applicable VI. Procurement of Second-hand Goods: Not Applicable VII. Domestic Preference: Not Applicable VIII. Hands on Expanded Implementation Support (HEIS): Not applicable 1 IX. Other Relevant Procurement Information: Not Applicable X. Thresholds for Procurement Approaches and Method (US millions) Based on the risks identified above, the following procurement arrangements are proposed: a) Approach to Market: Based on previous experience and available local market, the following threshold will be used of open national/international and RFQ bidding (all figures in million USD) Table 1.2: Thresholds for procurement approaches and methods Procurement Methods (US millions)–Goods, Works, and Non- Consulting Services Open Open Request for Direct Category Internatio National Quotation Selection nal (RfQ) Works ≥ 5.0 <5.0 ≤ 0.2 All Values Goods, IT, and non- ≥ 0.5 <0.5 ≤ 0.1 All Values consultin g services Thresholds for Procurement Approaches and Methods (US, millions) – Consulting Services Category Short List of National Consultants Consulting Engineering and Services Construction Supervision Consultants (Firms) ≤ 0.1 ≤ 0.2 Individual Consultants n.a. n.a. Direct Selection Consultants (Firms) All Values All Values Individual Consultants All Values All Values 2 XI. Table Packages for Goods, Works and Non-Consulting Services (At Negotiations – to be entered in STEP) S.N Contract Title, Description Estimat Revi Market Selec Evaluation Expect Date of o and Category ed Cost ew Approach tion Options (BAFO ed date contrac (US$) by (Open- Meth Rated Criteria of t award Ban National/ od etc.) bid/pro k Limited (RFP, posal etc.) RFB, openin RFQ g GOODS G1 FGS HMIS office 20,000 Prior Limited RFQ Most 27-Sep- 31-Oct- electronics/equipment advantageous Bid 21 21 G2 FMS HMIS office 40,000 Prior Limited RFQ Most 27-Oct- 30-Nov- electronics/equipment advantageous Bid 21 21 G3 HMIS reporting forms, printing 40,000 Prior Limited RFQ Most 26-Jan- 01-Mar- costs advantageous Bid 22 22 Sub-total 1 60,000 S.N Contract Title, Description and Estimate Revi Market Metho Expect Date of o Category d Cost ew Approach d ed date contract (US$) by (Open- (QCBS, of award Bank National/ LCBCS, bid/pro Limited etc.) QBS, posal DS openin g CONSULTANCY SERVICES C1 PCIU Senior Project Coordinator 91,680 Prior Open INDV 28-Jun- 01-Aug- International 21 21 C2 PCIU Legal Advisor (Part-time) 40,000 Prior Open National INDV 28-Jun- 01-Aug- 21 21 1 S.N Contract Title, Description and Estimate Revi Market Metho Expect Date of o Category d Cost ew Approach d ed date contract (US$) by (Open- (QCBS, of award Bank National/ LCBCS, bid/pro Limited etc.) QBS, posal DS openin g C3 PCIU Security Advisor 80,000 Prior Open INDV 28-Jun- 01-Aug- International 21 21 C4 PCIU Communications Specialist 43,488 Prior Open National INDV 28-Jun- 01-Aug- 21 21 C5 PCIU Environmental Specialist 43,488 Prior Open National INDV 28-Jun- 01-Aug- 21 21 C6 PCIU Procurement Specialist 100,000 Prior Open INDV 26-Feb- 01-Apr-22 International 22 C7 PCIU PFM Specialist 100,000 Prior Open INDV 26-Feb- 01-Apr-22 International 22 C8 PCIU GBV Specialist 43,488 Prior Open National INDV 19-Jul- 22-Aug- 21 21 C9 PCIU Social Specialist 52,800 Prior Open National INDV 28-Jun- 01-Aug- 21 21 C10 PMT Project Manager (PL) 48,000 Prior Open National INDV 19-Aug- 22-Sep- 21 21 C11 PMT Environmental Specialist (PL) 16,000 Prior Open National INDV 19-Aug- 22-Sep- 21 21 C12 PMT Social/ GBV Specialist (PL) 32,000 Prior Open National INDV 19-Aug- 22-Sep- 21 21 C13 PMT Project Manager (SWS) 48,000 Prior Open National INDV 19-Aug- 22-Sep- 21 21 C14 PMT Environmental Specialist (SWS) 16,000 Prior Open National INDV 19-Aug- 22-Sep- 21 21 2 S.N Contract Title, Description and Estimate Revi Market Metho Expect Date of o Category d Cost ew Approach d ed date contract (US$) by (Open- (QCBS, of award Bank National/ LCBCS, bid/pro Limited etc.) QBS, posal DS openin g C15 PMT Social/ GBV Specialist (SWS) 32,000 Prior Open National INDV 19-Aug- 22-Sep- 21 21 C16 PMT Project Manager (HSS) 48,000 Prior Open National INDV 19-Aug- 22-Sep- 21 21 C17 PMT Environmental Specialist (HSS) 16,000 Prior Open National INDV 19-Aug- 22-Sep- 21 21 C18 PMT Social/ GBV Specialist (HSS) 32,000 Prior Open National INDV 19-Aug- 22-Sep- 21 21 C19 PMT Project Manager (GAL) 48,000 Prior Open National INDV 19-Aug- 22-Sep- 21 21 C20 PMT Project Manager (JUB) 48,000 Prior Open National INDV 19-Aug- 22-Sep- 21 21 C21 FGS MoH HMIS specialist 43,488 Prior Open National INDV 18-Sep- 22-Oct-21 21 C22 FMS MoH HMIS specialist (PL) 32,000 Prior Open National INDV 19-Oct- 22-Nov- 21 21 C23 FMS MoH HMIS specialist (SWS) 24,000 Prior Open National INDV 19-Oct- 22-Nov- 21 21 C24 FMS MoH HMIS specialist (HSS) 24,000 Prior Open National INDV 19-Oct- 22-Nov- 21 21 C25 FMS MoH HMIS specialist (GAL) 24,000 Prior Open National INDV 19-Oct- 22-Nov- 21 21 C26 FMS MoH HMIS specialist (JUB) 24,000 Prior Open National INDV 19-Oct- 22-Nov- 21 21 3 S.N Contract Title, Description and Estimate Revi Market Metho Expect Date of o Category d Cost ew Approach d ed date contract (US$) by (Open- (QCBS, of award Bank National/ LCBCS, bid/pro Limited etc.) QBS, posal DS openin g C27 HMIS TA (firm) 400,000 Prior Open QCBS 28-Nov- 01-Jan-22 International 21 C28 PCIU Contract management specialist 43,488 Prior Open National INDV 28-Jun- 01-Aug- (3no.) 21 21 C29 PCIU M&E specialist 43,488 Prior Open National INDV 28-Jun- 01-Aug- 21 21 C30 HMIS expert in the HMIS Unit 43,488 Prior Open National INDV 18-Sep- 22-Oct-21 21 C31 Contract management TA (firm) 100,000 Prior Open QCBS 19-Oct- 22-Nov- International 21 21 C32 Regional-level health staff in 5 regions 16,000 Prior Open National INDV 19-Oct- 22-Nov- (5no.) 21 21 C33 Health financing/RMET specialist 43,488 Prior Open National INDV 19-Aug- 22-Sep- 21 21 C34 Public Private Partnerships (PPP) 43,488 Prior Open National INDV 19-Oct- 22-Nov- Specialist 21 21 C35 Security Assessment (Firm) 300,000 Prior Open QCBS 19-Aug- 22-Sep- International 21 21 C36 Third-party monitoring contract 1,250,000 Prior Open QCBS 15-Aug- 15-Sep- International 21 21 C37 Service delivery contract (Nugaal, PL) 4,000,000 Prior Open QCBS 15-Aug- 15-Sep- International 21 21 C38 Service delivery contract (Bay, SWS) 4,000,000 Prior Open QCBS 15-Aug- 15-Sep- International 21 21 4 S.N Contract Title, Description and Estimate Revi Market Metho Expect Date of o Category d Cost ew Approach d ed date contract (US$) by (Open- (QCBS, of award Bank National/ LCBCS,bid/pro Limited etc.) QBS, posal DS openin g C39 Service delivery contract (Bakool, SWS) 4,000,000 Prior Open QCBS 15-Aug- 15-Sep- International 21 21 C40 Service delivery contract (Hiraan, 4,000,000 Prior Open QCBS 15-Aug- 15-Sep- Hirshabelle) International 21 21 C41 Service delivery contract (M.Shabelle, 1,500,000 Prior Open QCBS 15-Aug- 15-Sep- Hirshabelle)* International 21 21 Sub-Total 2 20,933,8 72 GRAND TOTAL 20,993,8 72 5 PROCUREMENT Somalia : Improving Healthcare Services in Somalia Project (“Damal Caafimaad”) PLAN General Information Country: Somalia 2021-06-30 Bank’s Approval Date of the Original Procurement Plan: 2023-06-06 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P172031 GPN Date: 2021-09-30 Project Name: Improving Healthcare Services in Somalia Project (“Damal Caafimaad”) Loan / Credit No: / , IDA / D8620, TF / B5820 Federal Government of Somalia Ministry of Health Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SO-MOH-FGS-043-GO-RFQ / Component 3: Project mana Request for Quota Single Stage - One E Under Imple Procurement of Office Equip IDA / D8620 gement, knowledge manage Prior Limited 35,000.00 0.00 2023-01-07 2023-06-14 2023-02-16 2023-04-17 tions nvelope mentation ment for the PCIU ment and learning SO-MOH-FGS-0058-GO-RFQ / Component 3: Project mana Request for Quota Single Stage - One E Under Revie Damal Caafimaad - Office Fur IDA / D8620 gement, knowledge manage Prior Limited 49,000.00 0.00 2023-06-18 2023-07-28 2024-01-24 tions nvelope w niture for PCIU ment and learning NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 1: Expanding th SO-MOH-FGS-036-NC-DIR / P e coverage of high-impact h rovision of Security Risk Asse IDA / D8620 Prior Direct Selection Direct 500,000.00 0.00 Canceled 2021-11-01 2021-11-06 2021-12-21 2022-12-21 ealth and nutrition services i ssment Services n select geographic areas SO-MOH-FGS-043-NC-RFB / Component 1: Expanding th Delivering the Essential Pack e coverage of high-impact h Open - Internationa Single Stage - One E Under Imple IDA / D8620 Prior Request for Bids 12,000,000.00 0.00 2022-12-23 2022-12-30 2022-12-28 2023-01-06 2023-02-08 2023-02-12 2023-03-10 2023-05-27 2023-04-14 2025-04-13 age of Health Services in Nug ealth and nutrition services i l nvelope mentation al Region - Puntland State of n select geographic areas Somalia SO-MOH-FGS-044-NC-RFB / Component 1: Expanding th Delivery of Essential Package e coverage of high-impact h Open - Internationa Single Stage - One E Under Imple IDA / D8620 Prior Request for Bids 12,000,000.00 0.00 2022-12-23 2022-12-30 2022-12-28 2023-01-18 2023-02-08 2023-02-20 2023-03-10 2023-05-27 2023-04-14 2025-04-13 of Health Services in Hiiraan ealth and nutrition services i l nvelope mentation Region - Hirshabelle State of n select geographic areas Somalia SO-MOH-FGS-045-NC-RFB / Component 1: Expanding th Delivery of Essential Package e coverage of high-impact h Open - Internationa Single Stage - One E Under Imple IDA / D8620 Prior Request for Bids 4,500,000.00 0.00 2022-12-23 2022-12-30 2022-12-28 2023-01-16 2023-02-08 2023-02-18 2023-03-10 2023-05-27 2023-04-14 2025-04-13 of Health Services in Middle ealth and nutrition services i l nvelope mentation Shabelle Region - Hirshabelle n select geographic areas State of Somalia SO-MOH-FGS-046-NC-RFB / Component 1: Expanding th Delivery of Essential Package e coverage of high-impact h Open - Internationa Single Stage - One E IDA / D8620 Prior Request for Bids 12,000,000.00 0.00 Canceled 2022-12-23 2022-12-30 2022-12-28 2023-01-06 2023-02-08 2023-02-12 2023-03-10 2023-04-14 2025-04-13 of Health Services in Bay Reg ealth and nutrition services i l nvelope ion - South West State of So n select geographic areas malia SO-MOH-FGS-047-NC-RFB / Component 1: Expanding th Delivery of Essential Package e coverage of high-impact h Open - Internationa Single Stage - One E IDA / D8620 Prior Request for Bids 12,000,000.00 0.00 Canceled 2022-12-23 2022-12-30 2022-12-28 2023-01-06 2023-02-08 2023-02-12 2023-03-10 2023-04-14 2025-04-13 of Health Services in Bakool ealth and nutrition services i l nvelope Region - South West State of n select geographic areas Somalia SO-MOH-FGS-0054-NC-RFB / Component 1: Expanding th Delivery of Essential Package e coverage of high-impact h Single Stage - One E Under Imple IDA / D8620 Prior Request for Bids Limited 15,000,000.00 0.00 2023-06-02 2023-06-12 2023-06-18 2023-06-15 2023-06-21 2023-07-06 2023-07-25 2025-05-30 of Health Services in Bay Reg ealth and nutrition services i nvelope mentation ion n select geographic areas SO-MOH-FGS-0055-NC-RFB / Component 1: Expanding th Delivery of Essential Package e coverage of high-impact h Single Stage - One E Under Imple IDA / D8620 Prior Request for Bids Limited 15,000,000.00 0.00 2023-06-02 2023-06-12 2023-06-18 2023-06-15 2023-06-20 2023-07-05 2023-07-24 2025-05-30 of Health Services in Bakool ealth and nutrition services i nvelope mentation Region n select geographic areas CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 1: Expanding th SO-MOH-FGS-014-CS-QCBS / e coverage of high-impact h Quality And Cost- Open - Internationa Under Implement Provision of Third Party Monit IDA / D8620 Prior 5,000,000.00 0.00 2021-09-28 2022-02-09 2021-10-08 2022-03-14 2021-10-27 2023-06-14 2021-11-24 2021-11-29 2021-12-14 2022-01-04 2023-01-04 ealth and nutrition services i Based Selection l ation oring Services n select geographic areas Component 1: Expanding th SO-MOH-FGS-013-CS-QCBS / e coverage of high-impact h Quality And Cost- Open - Internationa Provision of Security Assess IDA / D8620 Prior 500,000.00 0.00 Canceled 2021-09-28 2021-10-08 2021-10-27 2021-11-24 2021-11-29 2021-12-14 2022-01-04 2023-01-04 ealth and nutrition services i Based Selection l ment Services n select geographic areas Component 1: Expanding th SO-MOH-FGS-017-CS-QCBS / e coverage of high-impact h Quality And Cost- Open - Internationa Service delivery contract (Ba IDA / D8620 Prior 12,000,000.00 0.00 Canceled 2021-10-01 2022-02-09 2021-10-11 2021-10-31 2021-11-28 2021-12-03 2021-12-18 2022-01-08 2025-01-07 ealth and nutrition services i Based Selection l kool, South West State) n select geographic areas Component 1: Expanding th SO-MOH-FGS-015-CS-QCBS / e coverage of high-impact h Quality And Cost- Open - Internationa Service delivery contract (Nu IDA / D8620 Prior 12,000,000.00 0.00 Canceled 2021-10-01 2022-02-22 2021-10-11 2022-03-10 2021-10-31 2021-11-28 2021-12-03 2021-12-18 2022-01-08 2025-01-07 ealth and nutrition services i Based Selection l gaal, Puntland) n select geographic areas Page 1 Component 1: Expanding th SO-MOH-FGS-018-CS-QCBS / e coverage of high-impact h Quality And Cost- Open - Internationa Service delivery contract (Hir IDA / D8620 Prior 12,000,000.00 0.00 Canceled 2021-10-01 2022-02-22 2021-10-11 2022-03-10 2021-10-31 2021-11-28 2021-12-03 2021-12-18 2022-01-08 2025-01-07 ealth and nutrition services i Based Selection l aan, Hirshabelle) n select geographic areas Component 1: Expanding th SO-MOH-FGS-016-CS-QCBS / e coverage of high-impact h Quality And Cost- Open - Internationa Service delivery contract (Ba IDA / D8620 Prior 12,000,000.00 0.00 Canceled 2021-10-01 2022-02-22 2021-10-11 2022-03-10 2021-10-31 2021-11-28 2021-12-03 2021-12-18 2022-01-08 2025-01-07 ealth and nutrition services i Based Selection l y, South West State) n select geographic areas Component 1: Expanding th SO-MOH-FGS-019-CS-QCBS / e coverage of high-impact h Quality And Cost- Open - Internationa Service delivery contract (M. IDA / D8620 Prior 4,500,000.00 0.00 Canceled 2021-10-01 2022-02-22 2021-10-11 2022-03-10 2021-10-31 2021-11-28 2021-12-03 2021-12-18 2022-01-08 2025-01-07 ealth and nutrition services i Based Selection l Shabelle, Hirshabelle) n select geographic areas INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 3: Project mana SO-MOH-FGS-0002-CS-INDV Individual Consult / gement, knowledge manage Prior Open 40,000.00 0.00 Signed 2021-07-01 2021-07-27 2021-08-19 2021-10-31 2021-09-09 2021-12-13 2021-10-14 2022-10-13 / PCIU Legal Advisor ant Selection ment and learning SO-MOH-FGS-0004-CS-INDV Component 3: Project mana Individual Consult / PIU Communications Specia IDA / D8620 gement, knowledge manage Prior Open 43,488.00 51,000.00 Signed 2021-07-10 2021-07-16 2021-08-28 2021-12-21 2021-09-18 2022-02-09 2021-10-23 2022-02-24 2022-10-22 ant Selection list ment and learning SO-MOH-FGS-0008-CS-INDV Component 3: Project mana Individual Consult / PCIU Contract Management IDA / D8620 gement, knowledge manage Prior Open 43,488.00 49,920.00 Signed 2021-07-10 2021-07-16 2021-08-28 2021-11-03 2021-09-18 2021-12-09 2021-10-23 2021-12-28 2022-10-22 ant Selection Specialist no. 01 ment and learning Component 3: Project mana SO-MOH-FGS-0010-CS-INDV Individual Consult IDA / D8620 gement, knowledge manage Prior Open 43,488.00 49,920.00 Signed 2021-07-10 2021-07-16 2021-08-28 2021-12-21 2021-09-18 2022-01-14 2021-10-23 2022-01-28 2022-10-22 / PCIU- HMIS Specialist ant Selection ment and learning SO-MOH-FGS-0011-CS-INDV Component 3: Project mana Individual Consult / PCIU- Contract Management IDA / D8620 gement, knowledge manage Prior Open 43,488.00 49,920.00 Signed 2021-07-10 2021-07-16 2021-08-28 2021-12-09 2021-09-18 2021-12-24 2021-10-23 2022-01-11 2022-10-22 ant Selection Specialist No. 2 ment and learning Component 3: Project mana SO-MOH-FGS-0009-CS-INDV Individual Consult IDA / D8620 gement, knowledge manage Prior Open 43,488.00 49,920.00 Signed 2021-07-10 2021-07-16 2021-08-28 2021-11-20 2021-09-18 2021-12-09 2021-10-23 2021-12-28 2022-10-22 / PCIU M&E Specialist ant Selection ment and learning Component 3: Project mana SO-MOH-FGS-0003-CS-INDV Individual Consult IDA / D8620 gement, knowledge manage Prior Open 80,000.00 54,360.00 Signed 2021-07-10 2021-07-16 2021-08-28 2021-10-31 2021-09-18 2021-12-08 2021-10-23 2021-12-28 2022-10-22 / PCIU Security Advisor ant Selection ment and learning SO-MOH-FGS-0001-CS-INDV Component 3: Project mana Individual Consult / PCIU Senior Programme Co IDA / D8620 gement, knowledge manage Prior Open 91,680.00 93,980.00 Signed 2021-07-10 2021-07-16 2021-08-28 2021-10-20 2021-09-18 2021-12-06 2021-10-23 2022-01-01 2022-10-22 ant Selection ordinator ment and learning SO-MOH-FGS-0007-CS-INDV Component 3: Project mana Individual Consult / PCIU Social Safeguards Spe IDA / D8620 gement, knowledge manage Prior Open 52,800.00 51,000.00 Signed 2021-07-10 2021-07-16 2021-08-28 2021-11-03 2021-09-18 2021-12-08 2021-10-23 2021-12-28 2022-10-22 ant Selection cialist ment and learning SO-MOH-FGS-0005-CS-INDV Component 3: Project mana Individual Consult / PCIU Environmental Safegu IDA / D8620 gement, knowledge manage Prior Open 43,488.00 49,920.00 Signed 2021-07-10 2021-07-16 2021-08-28 2021-11-18 2021-09-18 2021-12-21 2021-10-23 2021-12-28 2022-10-22 ant Selection ards Specialist ment and learning Component 3: Project mana SO-MOH-FGS-0006-CS-INDV Individual Consult IDA / D8620 gement, knowledge manage Prior Open 43,488.00 51,000.00 Signed 2021-07-10 2021-07-21 2021-08-28 2021-11-02 2021-09-18 2021-12-07 2021-10-23 2021-12-28 2022-10-22 / PCIU- GBV Specialist ant Selection ment and learning SO-MOH-FGS-0012-CS-INDV Component 3: Project mana Individual Consult / PCIU- Contract Management IDA / D8620 gement, knowledge manage Prior Open 43,488.00 49,920.00 Signed 2021-07-10 2021-07-16 2021-08-28 2021-12-07 2021-09-18 2021-12-24 2021-10-23 2022-01-11 2022-10-22 ant Selection Specialist No. 3 ment and learning SO-MOH-FGS-020-CS-INDV / Component 3: Project mana Individual Consult Under Implement PMT Project Manager (Puntla IDA / D8620 gement, knowledge manage Prior Open 48,000.00 0.00 2021-09-21 2021-11-04 2021-10-17 2022-09-06 2021-10-31 2022-10-18 2021-11-24 2022-11-23 ant Selection ation nd) ment and learning SO-MOH-FGS-022-CS-INDV / Component 3: Project mana Individual Consult Under Implement PMT Social/ GBV Specialist ( IDA / D8620 gement, knowledge manage Prior Open 32,000.00 0.00 2021-09-21 2021-10-05 2021-10-17 2022-09-06 2021-10-31 2022-12-22 2021-11-24 2022-11-23 ant Selection ation Puntland) ment and learning SO-MOH-FGS-024-CS-INDV / Component 3: Project mana Individual Consult Under Implement PMT Project Manager (South IDA / D8620 gement, knowledge manage Prior Open 48,000.00 0.00 2021-09-21 2021-11-04 2021-10-17 2022-11-26 2021-10-31 2022-12-30 2021-11-24 2022-11-23 ant Selection ation West State) ment and learning SO-MOH-FGS-026-CS-INDV / Component 3: Project mana Individual Consult Under Implement PMT Social/ GBV Specialist ( IDA / D8620 gement, knowledge manage Prior Open 32,000.00 0.00 2021-09-21 2021-10-05 2021-10-17 2022-10-17 2021-10-31 2022-12-22 2021-11-24 2022-11-23 ant Selection ation South West State) ment and learning SO-MOH-FGS-028-CS-INDV / Component 3: Project mana Individual Consult Under Implement PMT Project Manager (Hirsha IDA / D8620 gement, knowledge manage Prior Open 48,000.00 0.00 2021-09-21 2021-11-04 2021-10-17 2022-08-23 2021-10-31 2022-10-18 2021-11-24 2022-11-23 ant Selection ation belle) ment and learning SO-MOH-FGS-030-CS-INDV / Component 3: Project mana Individual Consult Under Implement PMT Social/ GBV Specialist ( IDA / D8620 gement, knowledge manage Prior Open 32,000.00 0.00 2021-09-21 2021-10-05 2021-10-17 2022-10-06 2021-10-31 2022-10-28 2021-11-24 2022-11-23 ant Selection ation Hirshabelle) ment and learning SO-MOH-FGS-032-CS-INDV / Component 3: Project mana Individual Consult Under Implement PMT Project Manager (Galmu IDA / D8620 gement, knowledge manage Prior Open 48,000.00 0.00 2021-09-21 2021-11-04 2021-10-17 2022-07-31 2021-10-31 2022-10-18 2021-11-24 2022-11-23 ant Selection ation dug) ment and learning SO-MOH-FGS-034-CS-INDV / Component 3: Project mana Individual Consult Under Implement PMT Project Manager (Jubbal IDA / D8620 gement, knowledge manage Prior Open 48,000.00 0.00 2021-09-21 2021-11-04 2021-10-17 2022-09-06 2021-10-31 2022-10-18 2021-11-24 2022-11-23 ant Selection ation and) ment and learning SO-MOH-FGS-021-CS-INDV / Component 3: Project mana Individual Consult Under Implement PMT Environmental Specialist IDA / D8620 gement, knowledge manage Prior Open 32,000.00 0.00 2021-09-21 2021-10-05 2021-10-17 2022-09-06 2021-10-31 2022-10-18 2021-11-24 2022-11-23 ant Selection ation (Puntland) ment and learning SO-MOH-FGS-031-CS-INDV / Component 2: Strengthening Individual Consult Under Implement FMS MoH HMIS specialist (Hir IDA / D8620 Government’s stewardship t Prior Open 24,000.00 0.00 2021-09-27 2022-01-06 2021-10-23 2022-10-02 2021-11-06 2022-10-28 2021-11-30 2022-11-29 ant Selection ation shabelle) o enhance service delivery Page 2 SO-MOH-FGS-029-CS-INDV / Component 3: Project mana Individual Consult PMT Environmental Specialist IDA / D8620 gement, knowledge manage Prior Open 32,000.00 0.00 Signed 2021-09-21 2021-10-05 2021-10-17 2022-10-02 2021-10-31 2022-11-15 2021-11-24 2022-11-23 ant Selection (Hirshabelle) ment and learning SO-MOH-FGS-023-CS-INDV / Component 2: Strengthening Individual Consult Under Implement FMS MoH HMIS specialist (Pu IDA / D8620 Government’s stewardship t Prior Open 32,000.00 0.00 2021-09-27 2022-01-06 2021-10-23 2022-09-06 2021-11-06 2022-12-22 2021-11-30 2022-11-29 ant Selection ation ntland) o enhance service delivery SO-MOH-FGS-027-CS-INDV / Component 2: Strengthening Individual Consult Under Implement FMS MoH HMIS specialist (So IDA / D8620 Government’s stewardship t Prior Open 24,000.00 0.00 2021-09-27 2022-01-06 2021-10-23 2022-11-24 2021-11-06 2022-12-24 2021-11-30 2022-11-29 ant Selection ation uth West State) o enhance service delivery SO-MOH-FGS-025-CS-INDV / Component 3: Project mana Individual Consult PMT Environmental Specialist IDA / D8620 gement, knowledge manage Prior Open 32,000.00 0.00 Canceled 2021-09-24 2021-10-05 2021-10-20 2022-11-23 2021-11-03 2021-11-27 2022-11-26 ant Selection (South West State) ment and learning SO-MOH-FGS-033-CS-INDV / Component 2: Strengthening Individual Consult Under Implement FMS MoH HMIS specialist (Gal IDA / D8620 Government’s stewardship t Prior Open 24,000.00 0.00 2021-09-27 2022-01-06 2021-10-23 2022-07-31 2021-11-06 2022-10-18 2021-11-30 2022-11-29 ant Selection ation mudug) o enhance service delivery SO-MOH-FGS-035-CS-INDV / Component 2: Strengthening Individual Consult Under Implement FMS MoH HMIS specialist (Jub IDA / D8620 Government’s stewardship t Prior Open 24,000.00 0.00 2021-09-27 2022-01-06 2021-10-23 2022-10-02 2021-11-06 2022-10-29 2021-11-30 2022-11-29 ant Selection ation baland) o enhance service delivery SO-MOH-FGS-037-CS-INDV / Component 2: Strengthening Individual Consult FGS Health Financing Special IDA / D8620 Government’s stewardship t Prior Open 43,488.00 49,920.00 Signed 2021-11-05 2021-11-04 2021-12-24 2022-06-30 2022-01-14 2022-08-01 2022-02-18 2022-08-16 2023-02-17 ant Selection ist o enhance service delivery Component 1: Expanding th SO-MOH-FGS-037-CS-CDS / P e coverage of high-impact h rovision of Security Risk Asse IDA / D8620 Prior Direct Selection Direct 900,000.00 927,000.00 Signed 2021-11-30 2021-12-06 2021-12-10 2022-01-11 2022-02-13 2022-08-23 2022-08-12 ealth and nutrition services i ssment Services n select geographic areas SO-MOH-FGS-038-CS-INDV / Component 3: Project mana Individual Consult Under Implement Senior Contract Management IDA / D8620 gement, knowledge manage Prior Open 182,000.00 0.00 2022-07-04 2022-08-31 2022-08-22 2022-09-01 2022-10-06 2023-10-05 ant Selection ation Technical Advisor ment and learning SO-MOH-FGS-0040-CS-INDV Component 3: Project mana Individual Consult / Procurement Specialist No. IDA / D8620 gement, knowledge manage Prior Open - National 51,000.00 0.00 Canceled 2022-09-08 2022-10-27 2022-11-17 2022-12-22 2023-12-22 ant Selection 2 ment and learning SO-MOH-FGS-039-CS-INDV / Component 2: Strengthening Individual Consult Under Implement Health Financing Specialist N IDA / D8620 Government’s stewardship t Prior Direct - National 51,000.00 0.00 2022-09-07 2022-12-30 2022-09-17 2023-01-10 2022-09-27 2023-01-12 2022-10-28 2023-10-28 ant Selection ation o. 2 o enhance service delivery SO-MOH-FGS-041-CS-INDV / Component 3: Project mana Individual Consult Direct - Internation Under Implement Public Financial Management IDA / D8620 gement, knowledge manage Prior 190,000.00 0.00 2022-11-25 2022-12-04 2022-12-07 2022-12-21 2022-12-12 2022-12-27 2022-12-31 2023-12-31 ant Selection al ation (PFM) Specialist ment and learning Component 2: Strengthening SO-MOH-FGS-042-CS-INDV / Individual Consult Direct - Internation Under Implement IDA / D8620 Government’s stewardship t Prior 190,000.00 0.00 2022-11-25 2022-12-06 2022-12-06 2022-12-19 2022-12-11 2023-01-05 2022-12-31 2023-12-31 Procurement Specialist ant Selection al ation o enhance service delivery Component 2: Strengthening SO-MOH-FGS-048-CS-INDV / Individual Consult Under Implement TF / B5820 Government’s stewardship t Prior Limited 51,000.00 0.00 2023-01-18 2023-02-10 2023-01-23 2023-04-02 2023-02-13 2023-06-08 2023-03-20 2024-03-19 HMIS-ICT Specialist ant Selection ation o enhance service delivery SO-MOH-FGS-050-CS-INDV / Component 3: Project mana Individual Consult PMT Environmental Specialist IDA / D8620 gement, knowledge manage Prior Open - National 46,200.00 0.00 Under Review 2023-04-05 2023-05-08 2023-05-14 2023-06-04 2023-07-02 2024-07-01 ant Selection -South West State- (Readvert ment and learning ised) SO-MOH-FGS-051-CS-INDV / Component 2: Strengthening Individual Consult Under Implement Public Private Partnership Sp IDA / D8620 Government’s stewardship t Prior Open - National 55,000.00 0.00 2023-04-05 2023-06-08 2023-05-14 2023-06-04 2023-07-09 2024-07-08 ant Selection ation ecialist o enhance service delivery SO-MOH-FGS-049-CS-INDV / Component 2: Strengthening Individual Consult Open - Internationa Under Implement HMIS International Consultan TF / B5820 Government’s stewardship t Prior 190,000.00 0.00 2023-04-05 2023-05-24 2023-06-14 2023-07-19 2024-07-18 ant Selection l ation t o enhance service delivery Component 3: Project mana SO-MOH-FGS-052-CS-INDV / Individual Consult Under Implement IDA / D8620 gement, knowledge manage Prior Open - National 52,200.00 0.00 2023-06-05 2023-06-06 2023-07-14 2023-08-04 2023-09-08 2024-09-07 PMT Project Manager (BRA) ant Selection ation ment and learning Component 3: Project mana SO-MOH-FGS-053-CS-INDV / Individual Consult Under Implement IDA / D8620 gement, knowledge manage Prior Open - National 46,000.00 0.00 2023-06-05 2023-06-06 2023-07-14 2023-08-04 2023-09-08 2024-09-07 PMT HMIS Specialist (BRA) ant Selection ation ment and learning Component 3: Project mana SO-MOH-FGS-0056-CS-INDV Individual Consult Open - Internationa Under Implement IDA / D8620 gement, knowledge manage Prior 190,000.00 0.00 2023-06-02 2023-06-12 2023-07-11 2023-07-21 2023-08-09 2024-08-08 / Procurement Specialist ant Selection l ation ment and learning SO-MOH-FGS-0057-CS-INDV Component 3: Project mana Individual Consult Under Implement / PCIU Social Safeguard Speci IDA / D8620 gement, knowledge manage Prior Open - National 54,000.00 0.00 2023-06-02 2023-06-06 2023-07-11 2023-07-21 2023-08-09 2024-08-08 ant Selection ation alist ment and learning Page 3 PROCUREMENT PLAN (Textual Part) Project information: Papua New Guinea (PNG), PNG COVID-19 Emergency Response Project, P-173834 Project Implementation agency: National Department of Health (NDoH) Date of the Procurement Plan: April 3, 2020 Period covered by this Procurement Plan: April 3 2020 – to April 2, 2021 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016, revised November 2017 and August 2018) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: Not Applicable. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Not Applicable Procurement of Second-Hand Goods as specified under paragraph 5.11 of the Procurement Regulations: Not Applicable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: Not Applicable; Works: Not Applicable PROCUREMENT Papua New Guinea : Papua New Guinea COVID-19 Emergency Response Project PLAN General Information Country: Papua New Guinea 2020-04-14 Bank’s Approval Date of the Original Procurement Plan: 2023-06-06 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P173834 GPN Date: 2020-04-21 Project Name: Papua New Guinea COVID-19 Emergency Response Project Loan / Credit No: / , IDA / 66140, IDA / 67850 National Department of Health Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PG-NDOH-168433-GO-RFQ / Managing Implementation a Request for Quota Single Stage - One E / Post Limited 10,000.00 0.00 Canceled 2020-05-02 2020-05-27 2020-11-23 IT Equipment for the PCU nd Monitoring & Evaluation tions nvelope PG-NDOH-168430-GO-UN / D irect Selection of UNOPS for " delivery of outputs", includin Health Systems Strengtheni UN Agencies (Dire g but not limited to: modular IDA / 66140 Post Direct 10,490,139.00 10,490,139.00 Signed 2020-04-17 2020-04-13 2020-04-22 2020-04-16 2020-05-07 2020-04-25 2023-04-30 ng ct) isolation facilities, medical eq uipment and other medical c onsumables, and specimen tr ansportation PG-NDOH-338787-GO-RFQ / Managing Implementation a Request for Quota Single Stage - One E IDA / 67850 Post Limited 7,000.00 0.00 Canceled 2023-02-08 2023-04-05 2023-10-02 Laptops nd Monitoring & Evaluation tions nvelope NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PG-NDOH-168432-NC-UN / D irect Selection UNICEF for "d elivery of outputs", including Preparedness for COVID-19 UN Agencies (Dire but not limited to: delivering IDA / 66140 Post Direct 8,233,861.00 8,294,910.77 Signed 2020-04-17 2020-04-13 2020-04-22 2020-04-17 2020-05-06 2020-05-01 2023-04-09 Containment and Mitigation ct) diagnostic as well as social b ehavioral change communica tions training (inc related logi stics), and some goods (such as PPE). CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PG-NDOH-168421-CS-INDV / Managing Implementation a Individual Consult Financial Management Speci / Post Limited 216,000.00 0.00 Canceled 2020-05-04 2020-06-18 2020-05-09 2020-05-30 2020-06-19 2023-04-30 nd Monitoring & Evaluation ant Selection alist (part time) PG-NDOH-168424-CS-INDV / Managing Implementation a Individual Consult Monitoring & Evaluation Spec / Post Limited 180,000.00 0.00 Canceled 2020-05-04 2020-05-09 2020-05-30 2020-06-19 2023-04-30 nd Monitoring & Evaluation ant Selection ialist (part time) PG-NDOH-168425-CS-INDV / Managing Implementation a Individual Consult International Procurement Sp IDA / 66140 Post Direct 180,000.00 123,885.00 Completed 2020-04-24 2020-06-26 2020-05-04 2020-06-29 2020-05-14 2020-06-29 2020-05-24 2020-10-26 2023-04-30 nd Monitoring & Evaluation ant Selection ecialist (part time) PG-NDOH-168426-CS-INDV / Managing Implementation a Individual Consult International Environmental IDA / 66140 Post Limited 120,000.00 120,064.60 Completed 2020-05-15 2020-04-17 2020-05-20 2020-04-21 2020-06-10 2020-06-01 2020-06-30 2021-06-09 2023-04-15 nd Monitoring & Evaluation ant Selection and Social Safeguards Specia list (part time) PG-NDOH-168423-CS-INDV / Managing Implementation a Individual Consult Environmental Safeguard Sp IDA / 66140 Post Limited 180,000.00 0.00 Canceled 2020-05-04 2020-05-09 2020-05-30 2020-06-19 2023-04-30 nd Monitoring & Evaluation ant Selection ecialist (part time) PG-NDOH-176430-CS-INDV / Environmental, Social, Health Managing Implementation a Individual Consult IDA / 66140 Post Limited 180,000.00 114,961.45 Completed 2020-06-09 2020-06-01 2020-06-14 2020-06-16 2020-07-05 2020-07-17 2020-08-09 2020-06-29 2022-05-31 , Safety and Community Eng nd Monitoring & Evaluation ant Selection agement Specialist PG-NDOH-193728-CS-INDV / Managing Implementation a Individual Consult IDA / 66140 Post Open 200,000.00 299,689.60 Signed 2020-09-14 2020-09-20 2020-10-17 2022-02-17 2020-10-22 2022-03-07 2020-11-01 2022-05-10 2022-11-01 2023-05-03 Deputy Project Coordinator nd Monitoring & Evaluation ant Selection PG-NDOH-303681-CS-INDV / Managing Implementation a Individual Consult Direct - Internation IDA / 66140 Post 80,000.00 0.00 Canceled 2022-07-18 2022-07-28 2022-08-18 2022-08-28 2023-04-30 Financial Management Speci nd Monitoring & Evaluation ant Selection al alist PG-NDOH-308745-CS-INDV / Managing Implementation a Individual Consult IDA / 66140 Post Limited 36,000.00 0.00 Completed 2022-08-17 2022-08-23 2022-08-27 2022-10-26 2022-09-06 2023-01-10 2022-09-16 2023-05-05 Environmental Assessment S nd Monitoring & Evaluation ant Selection pecialist PG-NDOH-365532-CS-CDS / I Managing Implementation a Direct - Internation Under Implement IDA / 66140 Post Direct Selection 219,126.41 0.00 2023-06-07 2023-06-08 2023-06-17 2023-08-21 2024-02-17 nternational Procurement Sp nd Monitoring & Evaluation al ation ecialist Page 1 PG-NDOH-366185-CS-INDV / Managing Implementation a Individual Consult Under Implement Environmental, Social, and H IDA / 66140 Post Direct - National 70,000.00 0.00 2023-06-16 2023-06-17 2023-06-26 2023-07-17 2023-08-21 2024-10-31 nd Monitoring & Evaluation ant Selection ation ealth and Safety (ESHS) Spec ialist PG-NDOH-367257-CS-INDV / Managing Implementation a Individual Consult Direct - Internation Under Implement IDA / 66140 Prior 737,710.55 0.00 2023-06-23 2023-06-22 2023-07-03 2023-06-26 2023-07-23 2023-06-28 2023-08-11 2024-10-31 Project Coordinator nd Monitoring & Evaluation ant Selection al ation Page 2 TOGO PLAN DE PASSATION DES MARCHES SI PROJET : PROJET D’AMELIORATION DE LA QUALITE ET DE L’EQUITE DE L’EDUCATION DE BASE(PAQEEB) No d’identification du projet [P172674] PLAN DE PASSATION DE MARCHES SIMPLIFIE VERSION N° 1 I. GENERAL 1. Informations sur le Projet Emprunteur : République Togolaise Ministère : Ministère des enseignements primaire, Responsable secondaire, technique et de l’artisanat Nom du Projet : PROJET D’AMELIORATION DE LA QUALITE ET DE L’EQUITE DE L’EDUCATION DE BASE Identification : P172674 IDA N° Accord de Crédit/Accord de Don No… Structure chargée Unité de coordination du projet de la mise en œuvre du projet 2. Date d’approbation par la Banque du plan de passation de marchés : 3. Date de publication de l’Avis Général de Passation des Marchés : [A insérer plus tard 4. Période couverte par la Plan de Passation des Marchés : [A insérer dès à présent]…………… 5. Evaluation de risque par P-RAMS (Procurement Risk Assessment and Management System) : Substantiel Préambule Conformément au paragraphe 5.9 du “Règlement de Passation des Marchés pour les Emprunteurs sollicitant le Financement de Projets d’Investissement (FPI)” (Novembre 2020) (“Règlement de Passation des Marchés”), le Système 2 électronique de la Banque de suivi systématique des transactions de marchés publics (STEP) sera utilisé pour préparer, valider et actualiser les plans de passation des marchés et effectuer toutes les transactions liées à la passation des marchés du projet. Ce texte ainsi que les tableaux du plan de passation des marchés présents dans STEP constituent le plan de passation des marchés du projet. Les conditions suivantes s'appliquent à toutes les activités de passation de marchés du plan de passation de marchés. Les autres éléments du plan de passation des marchés tels que requis au paragraphe 4.4 du Règlement de passation des marchés sont énoncés dans STEP. Les Dossiers types de passation des marchés publics de la Banque devront être utilisés pour tous les contrats soumis à la concurrence internationale, ainsi que pour tous les autres contrats soumis à cette obligation telle que spécifiée dans les tableaux du plan de passation des marchés de STEP. Procédures nationales de passation des marchés : En accord avec le paragraphe 5.3 du Règlement de passation des marchés, dans le cas où la procédure de passation des marchés se fera au niveau national (telle que spécifiée dans les tableaux du plan de passation des marchés inclus dans STEP), les procédures nationales de passation des marchés du pays considéré pourront être utilisées.  Si l’Emprunteur utilise ses propres procédures d’appel d’offres national ouvert telles qu’énoncées dans la loi No 2009-013 du 30 juin 2009 relative aux Marchés Publics et Délégation de Service Public, le Décret Nº 2009-277/PR du 11 novembre 2009 portant Code des Marchés Publics et Délégation de Service Public, et les textes d’application y afférents, ces arrangements sont soumis aux dispositions du paragraphe 5.4 du Règlement de passation des marchés et aux conditions suivantes : • Le dossier d’appel d’offres/à propositions oblige le Soumissionnaire/les proposants présentant une Offre/Proposition à déposer un agrément signé, qui sera joint à tout contrat éventuel, pour confirmer qu’il applique et respecte les Directives de la Banque pour la lutte contre la corruption, y compris sans limitation, le droit de la Banque de sanctionner et les droits de la Banque pour l’inspection et l’audit ; • Le droit de la Banque d’examiner le dossier et les activités de passation des marchés. 3  Lorsque l’Emprunteur utilise d’autres procédures que l’appel d’offres national ouvert, ces procédures devront être en accord avec les dispositions du paragraphe 5.5 du Règlement de passation des marchés. Crédit-bail tel que spécifié au paragraphe 5.10 du Règlement de Passation des marchés : Le crédit-bail peut être utilisé pour les contrats indiqués comme tel dans le Plan de passation des marchés. « Sans objet » Achat de biens d’occasion tel que spécifié au paragraphe 5.11 du Règlement de Passation des Marchés est autorisé pour les contrats indiqués comme tel dans le Plan de passation des marchés. « Sans objet » Préférence nationale telle que spécifiée au paragraphe 5.51 du Règlement de Passation des Marchés (Fournitures et Travaux). L’Assistance directe à la mise en œuvre (sigle HEIS en anglais) tel que précisée aux paragraphes 3.10 et 3.11 du Règlement de Passation des marchés ne s’applique pas. Seuils pour approches et méthodes de passation des marchés – Travaux, Fournitures, et Services non-consultant ; Approches et méthode de passation des marchés (US$) Catégorie Ouverte Ouverte Demande de Internationale Nationale cotation (DC) (AOI) (AON) Travaux ≥ 5 000 000 <5 000 000 ≤ 200 000 Fournitures et Services ≥ 500 000 <500 000 ≤ 100 000 non-consultant 4 II. TRAVAUX, FOURNITURES ET SERVICES AUTRES QUE LES SERVICES DE CONSULTANTS 1. Dispositions relatives aux seuils de revue préalable : Seuils requis pour les décisions de marchés soumis à la revue préalable de la Banque, tel que prévu dans les paragraphes 3.5 à 3.8 de la Section III, et de l’Annexe II du Règlement de Passation des Marchés pour les Emprunteurs sollicitant le Financement de Projets d’Investissement (FPI), en date de Novembre 2020. Montants estimatifs des contrats en Catégories de marchés Observations millions de dollars américains Travaux (incluant clé à main, Fourniture et Installation, et les >= 10 Partenariat Public - Privé -PPP) Biens, Système d’Information et de Services autres que les Services >= 2 intellectuels Travaux (incluant clé à main, Fourniture et Installation, et les >= 10 Les justifications de Contrats à Partenariat Public - l’entente directe passer par Privé -PPP) devront être jointes entente Biens, Système et approuvées avec directe d’Information et de PPM Services autres que >= 2 les Services intellectuels 2. Pré qualification : Sans objet. 3. Dispositions spéciales sur les marchés : Concernant les acquisitions de véhicules et de carburant, en fonction des circonstances et des besoins spécifiques du pays, le seuil pour la consultation de fournisseurs pourrait être porté à la contre- valeur d’USD 500,000 (en prenant soin de consulter tous les principaux concessionnaires de marque ou distributeurs de produits pétroliers). Liste des marchés avec les méthodes de passation et les dates de mise en œuvre : Travaux 1 2 3 4 5 6 7 8 9 Revue de Méthode Date de Comment Ref. la Re Coût de lanceme aires/Fin Com Approche du Banque f. Description estimatif passatio nt de la de pos marché (a priori/a N° (US$) n des procédu prestatio ante posteriori marchés re ns ) Activités à l’étape projet Coût total en US$ 6 Fournitures et services autres que les services de consultants 1 2 3 4 5 6 7 8 9 Revue de Métho la Date de Ref. de de Commenta Coût Banque lancemen Ref. Com passati Approche du ires/Fin de Description estimatif (a t de la N° posa on des marché prestation (US$) priori/a procédur nte march s posterior e és i) Activités à l’étape projet Coût total en US$ III. SÉLECTION DES CONSULTANTS 1. Dispositions relatives aux seuils de revue préalable des marchés Décisions de sélection sujette à la revue préalable de la Banque comme indiqué dans Seuils requis pour les décisions de marchés soumis à la revue préalable de la Banque, tel que prévu dans les paragraphes 3.5 à 3.8 de la Section III, et de l’Annexe II du Règlement de Passation des Marchés pour les Emprunteurs sollicitant le Financement de Projets d’Investissement (FPI), en date de Novembre 2020. Seuils de revue a priori Méthode de Montants estimatifs des sélection/Catégories Observations contrats en millions de de marchés dollars américains Méthode compétitive/Firmes de >= 1 consultants Entente Les justifications pour directe/firmes de >= 1 l’entente directe consultants devront être jointes et 7 Entente approuvées avec le directe/Consultants >= 0.3 PPM individuel Méthode Compétitive (Comparaison de CVs) >= 0.3 / Consultants individuels 2. Liste restreinte composée entièrement de firmes nationales : La liste restreinte de consultants pour les prestations d’études d’ingénierie, de contrôle et de surveillance estimées à moins de 300,000 US$ par contrat, et pour tout autre type de prestations, estimées à moins de 100 000 US$ par contrat, peut comporter entièrement de consultants nationaux en conformité avec les dispositions des Règlement de Passation des marchés., et l’Emprunteur ne procède pas à une publication dans UNDB. 3. Autre arrangement spécial de Sélection de consultants : Le seuil pour l’utilisation de la méthode de sélection de consultant fondée sur les qualifications des consultant est déterminé au cas par cas en tenant compte de la nature et de la complexité de la mission ; cependant, ce seuil ne devrait pas dépasser la contre-valeur de USD 300,000 sauf dans des cas exceptionnels telles des situations d’urgence en conformité au Règlement de Passation des marchés. Marchés de Services de Consultants 1. 2. 3. 4. 5. 6. 7. 8. 9. Revue de la Date de Ref Ref. Coût Méthode Banque lancemen Commentaires Approche . Composa Description des missions estimatif de (a t de la /Fin de du marché N° nte (US$) sélection priori/a procédur prestations posterio e ri) Activités à l’étape projet Coût total en US$ Lexique des Sigles et Abréviations PPM : Plan de Passation des Marchés AOI : Appel d’Offres International AON : Appel d’Offres National DC : Demande de Cotations SQC Sélection fondée sur les Qualifications des : Consultants SMC : Sélection au Moindre Coût CI : Consultant Individuel ED : Sélection Directe ou Entente Directe A Revue a posteriori : posteriori A Priori : Revue a priori PPM : Plan de Passation des Marchés DNCMP Direction Nationale de Contrôle des : Marchés Publics ARMP : Autorité de Régulation des Marchés Publics PROCUREMENT Togo : Togo, Improving Quality and Equity of Basic Education Project PLAN General Information Country: Togo 2022-04-12 Bank’s Approval Date of the Original Procurement Plan: 2023-06-04 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P172674 GPN Date: 2022-03-20 Project Name: Togo, Improving Quality and Equity of Basic Education Project Loan / Credit No: IDA / D9010, TF / B6287 Project Coordination Unit - PAQEEB Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned TG-PCU-PAQEEB-356614-CW Component 1: Improving Qu Request for Quota -RFQ / Travaux de réfection d Request for Quota Single Stage - One E Pending Imp 2023-10-3 IDA / D9010 ality of Teaching and Learni Post Limited tions (Non Bank-S 313,540.00 0.00 2023-05-30 2023-08-01 es Ecoles Normales de Forma tions nvelope lementation 0 ng PD) tion des Professeurs d’Ecoles (ENFPE) de Notsè TG-PCU-PAQEEB-348838-CW National Procure -RFB / Travaux de réfection d Component 1: Improving Qu ment Document - Request for Quota Single Stage - One E Pending Imp 2023-11-0 es Ecoles Normales de Forma IDA / D9010 ality of Teaching and Learni Post Limited 1 Envelope proce 335,195.00 0.00 2023-05-30 2023-08-08 tions nvelope lementation 6 tion des Professeurs d’Ecoles ng ss (Non Bank-SPD (ENFPE) de Dapaong et de M ) ango TG-PCU-PAQEEB-356605-CW Component 1: Improving Qu Request for Quota -RFQ / Travaux de réfection d Request for Quota Single Stage - One E Pending Imp 2023-08-1 IDA / D9010 ality of Teaching and Learni Post Limited tions (Non Bank-S 248,450.00 0.00 2023-05-30 2023-08-01 es Ecoles Normales de Forma tions nvelope lementation 0 ng PD) tion des Professeurs d’Ecoles (ENFPE) d'Adéta TG-PCU-PAQEEB-356608-CW Component 1: Improving Qu Request for Quota -RFQ / Travaux de réfection d Request for Quota Single Stage - One E Pending Imp 2023-10-3 IDA / D9010 ality of Teaching and Learni Post Limited tions (Non Bank-S 257,770.00 0.00 2023-05-30 2023-08-01 es Ecoles Normales de Forma tions nvelope lementation 0 ng PD) tion des Professeurs d’Ecoles (ENFPE) de Tabligbo TG-PCU-PAQEEB-356613-CW -RFQ / Travaux de réfection d Component 1: Improving Qu Request for Quota Request for Quota Single Stage - One E Pending Imp 2023-10-3 es Ecoles Normales de Forma IDA / D9010 ality of Teaching and Learni Post Limited tions (Non Bank-S 252,895.00 0.00 2023-05-30 2023-08-01 tions nvelope lementation 0 tion des Professeurs d’Ecoles ng PD) (ENFPE) de Sotouboua GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TG-PCU-PAQEEB-285558-GO -RFB / Acquisition de tablette Component 3: Strengthening s pour les DRE, inspections (i Single Stage - One E IDA / D9010 system management and re Post Request for Bids Open - National 340,000.00 0.00 Signed 2022-06-15 2022-06-20 2022-06-20 2022-07-20 2022-07-19 2022-09-03 2022-09-13 2022-10-15 2023-01-13 nspecteurs, conseillers, char nvelope silience gés de statistique) et aux ca dres des directions centrales et de l'UCP-PAQEEB TG-PCU-PAQEEB-285564-GO -RFB / Acquisition de matériel Component 3: Strengthening Single Stage - One E informatique (vidéo projecte IDA / D9010 system management and re Post Request for Bids Open - National 180,000.00 0.00 Signed 2022-06-15 2022-07-27 2022-06-20 2022-07-20 2022-08-26 2022-09-03 2022-10-05 2023-04-23 2023-07-22 nvelope ur, PC portable) aux inspectio silience ns et DRE, cellule genre, et a ux directions centrales TG-PCU-PAQEEB-285546-GO -RFQ / Acquisition de matérie Component 3: Strengthening Single Stage - One E ls informatiques pour la mise IDA / D9010 system management and re Post Request for Bids Open - National 400,000.00 0.00 Signed 2022-06-15 2022-08-04 2022-06-20 2022-07-20 2022-12-05 2022-09-03 2023-02-15 2022-10-08 2023-02-05 nvelope en place d'une plateforme d' silience enseignement en ligne TG-PCU-PAQEEB-296639-GO -RFQ / Acquisition d'équipem ents (MICROPHONE FILAIRE, Component 2: Improve equit LECTEUR DVD EXTERNE, ÉCO able access to basic educati Request for Quota Single Stage - One E UTEURS INTRA-AURICULAIRE IDA / D9010 Post Limited 40,000.00 0.00 Canceled 2022-06-20 2022-07-29 2022-08-23 2022-11-21 on (primary and lower-secon tions nvelope S, MICRO SANS FIL, KIT ACCE dary) SSOIRES POUR MICROPHONE S, etc.…) pour la salle de pro duction de la plateforme d'en seignement en ligne TG-PCU-PAQEEB-296770-GO -RFQ / Acquisition du matérie Component 1: Improving Qu Request for Quota Single Stage - One E l informatique pour le compt IDA / D9010 ality of Teaching and Learni Post Limited 80,000.00 0.00 Signed 2022-06-15 2022-09-19 2022-08-18 2022-11-16 tions nvelope e de l’INSE, l’ENS d’Atakpam ng é et la Fast de l’Université de Kara TG-PCU-PAQEEB-285554-GO Component 3: Strengthening Open - Internationa Single Stage - One E -RFB / Acquisition de 24 véhi IDA / D9010 system management and re Post Request for Bids 1,056,000.00 0.00 Signed 2022-09-15 2022-10-21 2022-09-20 2022-10-21 2022-11-01 2022-12-01 2022-12-01 2023-02-13 2023-01-31 2023-05-01 l nvelope cules PICKUP pour les inspect silience ions TG-PCU-PAQEEB-328197-GO -RFB / Acquisition d'équipem ents (MICROPHONE FILAIRE, Component 2: Improve equit LECTEUR DVD EXTERNE, ÉCO able access to basic educati Single Stage - One E Under Imple UTEURS INTRA-AURICULAIRE IDA / D9010 Post Request for Bids Open - National 160,000.00 0.00 2022-12-15 2022-12-20 2022-12-20 2023-01-19 2023-01-23 2023-02-27 2023-03-08 on (primary and lower-secon nvelope mentation S, MICRO SANS FIL, KIT ACCE dary) SSOIRES POUR MICROPHONE S, etc.…) pour la salle de pro duction de la plateforme d'en seignement en ligne TG-PCU-PAQEEB-348484-GO -RFB / Acquisition de tablette s pour le personnel d'encadr Component 1: Improving Qu Open - Internationa Single Stage - One E Pending Impl ement, les élèves professeur IDA / D9010 ality of Teaching and Learni Post Request for Bids 1,279,990.00 0.00 2023-03-27 2023-04-03 2023-05-15 2023-06-14 2023-07-26 2023-10-24 l nvelope ementation s d'écoles et les élèves du pri ng maire pour la phase pilote de la numérisation des apprenti ssages au primaire Page 1 TG-PCU-PAQEEB-348501-GO -RFB / Acquisition de matériel s informatiques pour les élèv Component 1: Improving Qu Open - Internationa Single Stage - One E Under Imple es inspecteurs et les conseill IDA / D9010 ality of Teaching and Learni Post Request for Bids 564,560.00 0.00 2023-04-05 2023-05-26 2023-04-12 2023-05-26 2023-05-24 2023-06-23 2023-08-04 2023-08-13 l nvelope mentation ers pédagogiques, pour la Dir ng ection de l'Enseignement Sec ondaire Général (DESG), pou r le CNDP-TICE et l'ENEAS. TG-PCU-PAQEEB-307487-GO Component 3: Strengthening -RFQ / Acquisition d'un véhic Request for Quota Single Stage - One E IDA / D9010 system management and re Post Limited 50,000.00 0.00 Canceled 2022-12-10 2023-01-12 2023-02-12 2023-04-13 ule station wagon pour l'Unit tions nvelope silience é de Coordination du Projet TG-PCU-PAQEEB-353825-GO -RFQ / Acquisition de deux vé Component 3: Strengthening hicules station wagon pour l' Request for Quota Single Stage - One E Under Imple IDA / D9010 system management and re Post Limited 100,000.00 0.00 2023-05-25 2023-06-06 2023-08-03 2023-09-02 unité de coordination du proj tions nvelope mentation silience et et de la Direction de la Pla nification de statistiques et d e suivi-évaluation TG-PCU-PAQEEB-353828-GO Component 2: Improve equit -RFQ / Acquisition et installati able access to basic educati Request for Quota Single Stage - One E Pending Impl IDA / D9010 Post Limited 60,000.00 0.00 2023-05-30 2023-08-15 2023-10-14 on de dispositifs de visioconf on (primary and lower-secon tions nvelope ementation érence dans les 6 ENFPE et l dary) a DPIP TG-PCU-PAQEEB-354335-GO Component 1: Improving Qu Request for Quota Single Stage - One E -RFQ / Acquisition de matérie IDA / D9010 ality of Teaching and Learni Post Limited 17,500.00 0.00 Canceled 2023-04-25 2023-06-20 2023-07-20 tions nvelope l de géométrie au profit des ng ENFPE TG-PCU-PAQEEB-363225-GO -RFB / Acquisition et distribut Component 1: Improving Qu Open - Internationa Single Stage - One E Pending Impl ion des manuels et guides sc TF / B6287 ality of Teaching and Learni Prior Request for Bids 5,000,000.00 0.00 2023-06-05 2023-06-10 2023-07-22 2023-08-21 2023-10-02 2023-12-31 l nvelope ementation olaires pour les préscolaires ng section 1 et 2, et des cours p réparatoires 1 et 2 TG-PCU-PAQEEB-367783-GO Component 1: Improving Qu Request for Quota Single Stage - One E Pending Impl -RFQ / Acquisition de matérie IDA / D9010 ality of Teaching and Learni Post Limited 17,500.00 0.00 2023-07-05 2023-09-06 2024-01-04 tions nvelope ementation l de géométrie au profit des ng ENFPE NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TG-PCU-PAQEEB-285027-NC- Component 1: Improving Qu Request for Quota Single Stage - One E Pending Impl RFQ / Reproduction des guid TF / B6287 ality of Teaching and Learni Post Limited 17,000.00 0.00 2022-05-30 2022-08-17 2022-10-16 tions nvelope ementation es de cours pour la formation ng des enseignants TG-PCU-PAQEEB-285496-NC- Component 3: Strengthening Request for Quota Single Stage - One E Under Imple RFQ / Reproduction des guid IDA / D9010 system management and re Post Limited 50,000.00 0.00 2022-07-25 2022-07-18 2022-09-19 2023-03-18 tions nvelope mentation es illustrés pour les formatio silience ns FGB TG-PCU-PAQEEB-285005-NC- Component 1: Improving Qu RFQ / Impression des module Request for Quota Single Stage - One E IDA / D9010 ality of Teaching and Learni Post Limited 40,000.00 0.00 Canceled 2022-05-21 2022-07-29 2022-08-08 2022-10-07 s de formation en français et tions nvelope ng en mathématiques du CE2 TG-PCU-PAQEEB-285050-NC- RFQ / Impression du guide si Component 1: Improving Qu mplifié/circulaire de gestion Request for Quota Single Stage - One E IDA / D9010 ality of Teaching and Learni Post Limited 39,500.00 0.00 Signed 2022-07-05 2022-09-01 2022-09-29 2022-11-28 de la subvention et des regis tions nvelope ng tres de gestion aux inspectio ns (IEPP/IESG) et aux DRE po ur le suivi-accompagnement TG-PCU-PAQEEB-285058-NC- RFQ / Reproduction des regis Component 1: Improving Qu Request for Quota Single Stage - One E tres de la tenue de la compt IDA / D9010 ality of Teaching and Learni Post Limited 13,600.00 0.00 Signed 2022-06-25 2022-09-01 2022-09-19 2022-11-18 tions nvelope abilité aux COGEPs /COGERE ng S et aux inspections/DRE TG-PCU-PAQEEB-285547-NC- Component 3: Strengthening RFQ / Assurance maladie-indi Request for Quota Single Stage - One E IDA / D9010 system management and re Post Limited 50,000.00 0.00 Signed 2022-09-20 2022-09-27 2022-11-29 2023-11-29 viduel accident et décès UCP tions nvelope silience -PAQEEB pour une période d e deux (02) ans TG-PCU-PAQEEB-285414-NC- DIR / Acquisition d'un module Component 3: Strengthening supplémentaire de schoolfee IDA / D9010 system management and re Post Direct Selection Direct - National 30,000.00 0.00 Signed 2022-10-18 2022-08-26 2022-10-23 2022-09-05 2022-12-27 2023-03-27 s pour la gestion des dotatio silience ns aux écoles et formation d es chefs sections finance des inspections TG-PCU-PAQEEB-328196-NC- Component 1: Improving Qu RFB / Impression des module Single Stage - One E Under Imple IDA / D9010 ality of Teaching and Learni Post Request for Bids Open - National 160,000.00 0.00 2022-12-15 2022-12-27 2022-12-20 2023-01-19 2023-01-26 2023-03-05 2023-04-09 2023-06-08 s de formation en français et nvelope mentation ng en mathématiques du CE2 TG-PCU-PAQEEB-329090-NC- RFQ / Reproduction et distrib ution des manuels scolaires a ux élèves de préscolaires sec Component 1: Improving Qu Request for Quota Single Stage - One E Under Imple tion 1 et 2, et des cours prép IDA / D9010 ality of Teaching and Learni Prior Limited 5,000,000.00 0.00 2023-01-15 2023-01-13 2023-03-12 2023-04-26 tions nvelope mentation aratoires 1 et 2 en deux lots : ng Lot 1 : préscolaires section 1 et préscolaires 2, Lot 2 : CP1 et CP2 TG-PCU-PAQEEB-348855-NC- RFB / Impression des plans d étaillés de cours pour les ens eignants volontaires, des mo Component 1: Improving Qu Single Stage - One E dules de formation sur l'éval TF / B6287 ality of Teaching and Learni Post Request for Bids Open - National 120,000.00 0.00 Canceled 2023-07-25 2023-07-30 2023-08-29 2023-09-28 2023-11-09 2024-01-08 nvelope uation en APC, reproduction ng des guides de cours pour la f ormation des enseignants et Impression du manuel sur la santé scolaire (SH). TG-PCU-PAQEEB-348503-NC- RFB / Assurances tous risque Component 3: Strengthening Request for Quota Single Stage - One E Under Imple s pour les 24 véhicules pick-u IDA / D9010 system management and re Post Limited 84,000.00 0.00 2023-04-25 2023-05-16 2023-06-27 2024-06-21 tions nvelope mentation p pour les inspections pour u silience ne durée d'une année. Page 2 TG-PCU-PAQEEB-368706-NC- RFQ / Impression des plans d Component 1: Improving Qu Request for Quota Single Stage - One E Pending Impl étaillés de cours pour les ens IDA / D9010 ality of Teaching and Learni Post Limited 60,000.00 0.00 2023-07-18 2023-09-19 2023-11-18 tions nvelope ementation eignants volontaires et des ng modules de formation sur l'é valuation en APC. CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TG-PCU-PAQEEB-285037-CS- Component 1: Improving Qu QCBS / Recrutement d'un édi Quality And Cost- Open - Internationa IDA / D9010 ality of Teaching and Learni Post 300,000.00 0.00 Signed 2022-04-15 2022-06-15 2022-05-06 2022-07-27 2022-06-12 2022-10-25 2022-07-27 2022-11-23 2022-09-10 2022-12-19 2022-10-24 2023-02-14 2022-11-28 2023-05-27 teur pour l'édition des manu Based Selection l ng els et guides du CM1 TG-PCU-PAQEEB-285500-CS- Component 3: Strengthening Quality And Cost- Open - Internationa QCBS / Recrutement d'un Ag IDA / D9010 system management and re Post 400,000.00 0.00 Signed 2022-04-04 2022-07-06 2022-04-18 2022-07-11 2022-05-25 2022-10-19 2022-07-09 2022-11-22 2022-08-23 2022-12-16 2022-09-27 2023-03-30 2022-11-08 2026-10-08 Based Selection l ent Vérificateur Indépendant silience TG-PCU-PAQEEB-285503-CS- Component 3: Strengthening LCS / Recrutement de l'Audit Least Cost Selecti IDA / D9010 system management and re Post Open - National 90,000.00 0.00 Signed 2022-04-15 2022-05-17 2022-05-06 2022-06-12 2022-09-13 2022-07-12 2022-10-12 2022-08-11 2022-11-07 2022-09-08 2022-11-23 2022-10-20 2025-10-19 eur Externe pour les exercice on silience s 2022,2023 et 2024 TG-PCU-PAQEEB-285045-CS- Component 1: Improving Qu CQS / Recrutement d'un édit Consultant Qualifi Open - Internationa IDA / D9010 ality of Teaching and Learni Post 200,000.00 0.00 Signed 2022-06-20 2022-08-10 2022-07-11 2022-08-22 2022-08-28 2022-11-02 2022-09-27 2023-01-05 2022-11-01 2023-04-30 eur pour l'édition des manue cation Selection l ng ls de technologie ( 6ème, 5è me, 4ème, 3ème) TG-PCU-PAQEEB-348826-CS- CQS / Recrutement d'un cons Component 3: Strengthening ultant pour la réalisation de l' Consultant Qualifi Open - Internationa Pending Impleme IDA / D9010 system management and re Post 100,000.00 0.00 2023-05-25 2023-06-08 2023-07-22 2023-08-21 2023-10-02 2023-12-01 enquête sur la transition des cation Selection l ntation silience jeunes diplômés de l'enseign ement supérieur et des EFFP vers la vie active TG-PCU-PAQEEB-348827-CS- Component 3: Strengthening CQS / Recrutement d'un cabi Consultant Qualifi IDA / D9010 system management and re Post Open - National 90,000.00 0.00 Under Review 2023-04-20 2023-04-25 2023-05-04 2023-06-17 2023-07-17 2023-08-28 2023-10-27 net pour l'évaluation des acq cation Selection silience uis scolaires EGMA et EGRA TG-PCU-PAQEEB-348824-CS- Component 3: Strengthening Quality And Cost- Open - Internationa CQS / Recrutement d'un cabi IDA / D9010 system management and re Post 260,000.00 0.00 Canceled 2023-05-15 2023-06-05 2023-07-19 2023-07-23 2023-08-22 2023-10-03 2023-11-14 2023-12-14 Based Selection l net pour la réalisation de l'en silience quête SDI TG-PCU-PAQEEB-361288-CS- CDS / Recrutement d'un cabi Component 3: Strengthening net en formation en gestion Consultant Qualifi Open - Internationa Pending Impleme IDA / D9010 system management and re Post 100,000.00 0.00 2023-06-30 2023-07-14 2023-08-18 2023-09-08 2023-10-13 2024-10-07 a la base (FGB) pour appuyer cation Selection l ntation silience la DPSSE dans la mise en œu vre de l’approche communau taire INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TG-PCU-PAQEEB-285070-CS- INDV / Recrutement d'un con sultant pour faire l'Etat des li Component 2: Improve equit eux et identification des beso able access to basic educati Individual Consult ins en ressources humaines TF / B6287 Post Open 20,000.00 0.00 Signed 2022-07-20 2022-06-15 2022-09-07 2022-09-26 2022-09-10 2022-10-19 2022-10-22 2022-12-21 on (primary and lower-secon ant Selection et équipement pour le bon fo dary) nctionnement de la cellule ge nre et élaborer une stratégie nationale d’intégration du ge nre dans la planification TG-PCU-PAQEEB-285497-CS- CDS / Recrutement d'un cons ultant par entente directe po Component 3: Strengthening ur la poursuite de l'élaboratio IDA / D9010 system management and re Post Direct Selection Direct 35,600.00 0.00 Signed 2022-09-20 2022-07-20 2022-10-02 2022-07-20 2022-12-06 2023-01-20 n du document de politique n silience ationale d'offre de service d'i nformation et d'orientation s colaires et professionnelles. TG-PCU-PAQEEB-285083-CS- Component 2: Improve equit CDS / Sélection par entente d able access to basic educati IDA / D9010 Post Direct Selection Direct 280,000.00 0.00 Signed 2022-05-20 2022-07-20 2022-05-30 2022-07-20 2022-08-10 2022-11-08 ire de l'IIPE pour l' opérationn on (primary and lower-secon alisation du système de la ca dary) rte scolaire TG-PCU-PAQEEB-285402-CS- CDS / Recrutement d'un cons ultant individuel pour l'élabor Component 3: Strengthening Individual Consult ation du schéma directeur su IDA / D9010 system management and re Post Open 22,000.00 0.00 Signed 2022-06-30 2022-07-13 2022-08-18 2022-10-05 2022-09-17 2022-10-26 2022-10-22 2022-12-21 ant Selection r la mise en œuvre de la for silience mation initiale et continue de les acteurs du système éduc atif TG-PCU-PAQEEB-285412-CS- CDS / Recrutement d'un cons ultant national (coache) pour Component 3: Strengthening Individual Consult accompagner l'équipe des dé IDA / D9010 system management and re Post Open 18,000.00 0.00 Signed 2022-06-15 2022-07-13 2022-08-03 2022-09-15 2022-09-02 2022-10-21 2022-10-07 2023-04-05 ant Selection veloppeurs d'une plateforme silience unique de gestion des notes des élèves de tous les établis sements scolaires TG-PCU-PAQEEB-285409-CS- CDS / Recrutement d'un cons Component 3: Strengthening ultant StatEduc expert SIGE IDA / D9010 system management and re Post Direct Selection Direct - National 40,000.00 0.00 Signed 2022-09-15 2022-09-26 2022-09-25 2022-09-26 2022-11-29 2023-02-27 par entente directe pour l'op silience timisation du du Système d'I nformation de Gestion de l'E ducation (SIGE) TG-PCU-PAQEEB-285020-CS- Component 1: Improving Qu INDV / Recrutement d'un con Individual Consult TF / B6287 ality of Teaching and Learni Post Open 40,000.00 0.00 Canceled 2022-04-15 2022-06-03 2022-07-03 2022-08-07 2022-11-05 sultant pour la mise en œuvr ant Selection ng e de l'outil TEACH Page 3 TG-PCU-PAQEEB-285031-CS- Component 1: Improving Qu INDV / Recrutement d'un con Individual Consult TF / B6287 ality of Teaching and Learni Post Open 30,000.00 0.00 Canceled 2022-05-10 2022-06-28 2022-07-28 2022-09-01 2022-10-31 sultant individuel pour l'élab ant Selection ng oration de la politique des m anuels scolaires TG-PCU-PAQEEB-307500-CS- CDS / Recrutement d'un cabi Component 1: Improving Qu Direct - Internation net par entente directe pour l TF / B6287 ality of Teaching and Learni Post Direct Selection 30,000.00 0.00 Signed 2022-09-15 2022-10-05 2022-09-25 2022-10-07 2022-11-29 2023-01-28 al 'élaboration de la politique d ng es manuels scolaires TG-PCU-PAQEEB-307562-CS- INDV / Recrutement d'un con sultant individuel internation Component 3: Strengthening Individual Consult Open - Internationa Under Implement al en formation en gestion a l IDA / D9010 system management and re Post 50,000.00 0.00 2022-12-05 2022-12-26 2023-01-23 2023-02-22 2023-03-29 2023-06-27 ant Selection l ation a base (FGB) pour appuyer la silience DPSSE dans la mise en œuvr e de l’approche communauta ire TG-PCU-PAQEEB-328193-CS- INDV / Recrutement d'un con Component 3: Strengthening sultant individuel national en Individual Consult Under Implement IDA / D9010 system management and re Post Open - National 50,000.00 0.00 2022-12-15 2022-12-26 2023-02-02 2023-03-04 2023-04-08 2023-10-05 formation en gestion a la bas ant Selection ation silience e (FGB) pour appuyer la DPS SE dans la mise en œuvre de l’approche communautaire TG-PCU-PAQEEB-348831-CS- INDV / Recrutement d'un con Component 3: Strengthening Individual Consult sultant individuel pour la nu IDA / D9010 system management and re Post Open - National 50,000.00 0.00 Under Review 2023-05-25 2023-04-25 2023-07-13 2023-08-03 2023-09-14 2023-10-14 ant Selection mérisation des nouveaux out silience ils de gestion : ETP, IRRP, TIS E, MAGEV, CC TG-PCU-PAQEEB-348841-CS- INDV / Recrutement d'un con Component 1: Improving Qu sultant en ingénierie pédago Individual Consult TF / B6287 ality of Teaching and Learni Post Open - National 16,000.00 0.00 Under Review 2023-05-25 2023-06-16 2023-07-13 2023-08-03 2023-09-14 2023-11-13 gique auprès de la DRH de la ant Selection ng DESG et de la DEPP dans le c adre de la reforme curriculair e TG-PCU-PAQEEB-296779-CS- INDV / Recrutement d’un con Component 3: Strengthening sultant individuel pour la mis Individual Consult IDA / D9010 system management and re Post Open 40,000.00 0.00 Canceled 2022-07-15 2022-07-25 2022-09-02 2022-10-13 2022-10-02 2022-11-06 2023-02-04 e en œuvre des recommanda ant Selection silience tions du rapport de l’évaluati on du pilotage sectoriel de l’ éducation au Togo TG-PCU-PAQEEB-354394-CS- INDV / Recrutement d’un con Component 3: Strengthening Individual Consult sultant pour la formation des IDA / D9010 system management and re Post Direct - National 4,250.00 0.00 Canceled 2023-04-17 2023-04-27 2023-05-18 2023-06-22 2023-07-02 ant Selection cadres de l’ENEAS sur les mé silience thodes quantitatives des don nées TG-PCU-PAQEEB-354341-CS- INDV / Recrutement d’un con Component 3: Strengthening sultant pour la formation des Individual Consult Direct - Internation IDA / D9010 system management and re Post 7,000.00 0.00 Canceled 2023-04-13 2023-04-23 2023-05-14 2023-06-18 2023-06-28 cadres de l’ENEAS sur le pilot ant Selection al silience age et gestion des évaluation s à large échelle internationa le et nationale. TG-PCU-PAQEEB-285499-CS- INDV / Recrutement d'un con Component 3: Strengthening Individual Consult sultant individuel pour le Dia IDA / D9010 system management and re Post Open 30,000.00 0.00 Canceled 2022-06-15 2022-07-19 2022-08-03 2022-09-02 2022-10-14 2022-12-13 ant Selection gnostic institutionnel du syst silience ème national d'évaluation de s apprentissages (SNEA) TG-PCU-PAQEEB-285498-CS- Component 3: Strengthening CDS / Recrutement d'un cons Individual Consult IDA / D9010 system management and re Post Open 30,000.00 0.00 Canceled 2022-06-10 2022-07-29 2022-08-28 2022-10-02 2023-03-31 ultant individuel en ingénieri ant Selection silience e pédagogique auprès de la DF et de la DEPP TG-PCU-PAQEEB-285504-CS- INDV / Recrutement d'un con Component 3: Strengthening sultant pour l'Etude de faisab Individual Consult IDA / D9010 system management and re Post Open 30,000.00 0.00 Canceled 2022-05-30 2022-08-03 2022-08-24 2022-10-05 2022-12-04 ilité pour usage de l'instrume ant Selection silience nt PPP en Education pour la c onstruction d'infrastructures scolaires TG-PCU-PAQEEB-367785-CS- INDV / Recrutement d'un con Component 3: Strengthening sultant individuel pour appuy Individual Consult Pending Impleme IDA / D9010 system management and re Post Open - National 36,000.00 0.00 2023-06-30 2023-08-09 2023-09-08 2023-10-13 2023-12-12 er l'équipe nationale d'évalua ant Selection ntation silience tion des acquis scolaires (EN EAS) pour la réalisation de l'e nquête SDI TG-PCU-PAQEEB-367787-CS- INDV / Recrutement d'un con Component 3: Strengthening sultant individuel pour appuy Individual Consult Pending Impleme IDA / D9010 system management and re Post Open - National 30,000.00 0.00 2023-06-30 2023-08-09 2023-09-08 2023-10-13 2023-12-12 er l'équipe nationale d'évalua ant Selection ntation silience tion des acquis scolaires (EN EAS) pour l'évaluation des ac quis scolaires EGMA et EGRA TG-PCU-PAQEEB-368690-CS- CDS / Recrutement de L’ONG Component 2: Improve equit PLAN INTERNATIONAL TOGO able access to basic educati Pending Impleme pour appuyer la cellule genre TF / B6287 Post Direct Selection Direct - National 24,000.00 0.00 2023-07-10 2023-07-20 2023-09-23 2024-09-17 on (primary and lower-secon ntation dans la réalisation des activit dary) és de promotion de la scolari sation des filles dans le cadre de la mise en œuvre du PAQ EEB Page 4 PROCUREMENT PLAN (Textual Part) Project information: Accelerating and Strengthening Skills for Economic Transformation Project) (ASSET), P167506 Project Implementation agency: Directorate of Technical Education (DTE), Technical and Madrasah Education Division (TMED), Ministry of Education (MoE) Date of the Procurement Plan: March 23, 2022 Period covered by this Procurement Plan: March 2022 to March 2025 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (dated July 2016, revised November 2017, August 2018 and November 2020) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the People’s Republic of Bangladesh (Public Procurement Act 2006 - PPA, 1st amendment to PPA (2009) and the Public Procurement Rules 2008, as amended in August 2009) , such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions : a) e-GP system of the country for national competitive bidding (NCB) shall be followed using Standard/Model Procurement documents satisfactory to the Bank b) Post bidding negotiations shall not be allowed with the lowest evaluated or any other bidder; c) Bids should be submitted and opened in public in one location immediately after the deadline for submission; d) Lottery in award of contracts shall not be allowed; e) Bidders’ qualification/experience requirement shall be mandatory f) Bids shall not be invited or rejected on the basis of percentage above or below the estimated cost. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Specify for each Goods: is applicable for those contracts identified in the Procurement Plan tables; Other Relevant Procurement Information. Procurement Responsibility: Bangladesh Bureau of Statistics (BBS) is the implementing agency (IA) who will be responsible for all procurements. Procurement Threshold Bank-financed all contracts at or above the thresholds set out in the below table 1 are subject to the Bank’s procurement prior review. Table 1: Procurement Prior Review Thresholds (US$ millions) High Substant Modera Low Type of procurement risk ial risk te risk risk Works (including turnkey, supply & installation of plant and equipment, 5 10 15 20 and PPP) Goods, information technology and 1.5 2 4 6 non-consulting services Consultants: firms 0.5 1 2 4 Consultants: individuals 0.2 0.3 0.4 0.5 Irrespective of the contract value, the following procurement activities are subject to the Bank’s procurement prior review: a. procurement processes involving contract negotiations as, described in paragraphs 6.34-36 of Section VI of the Procurement Regulation for Borrowers; b. competitive dialogue; c. sustainable procurement; and d. best and final offer. The determination of whether a contract meets the procurement prior review threshold is based on the estimated value of the contract, including all taxes and duties payable under the contract. PROCUREMENT Bangladesh : Accelerating and Strengthening Skills for Economic Transformation PLAN General Information Country: Bangladesh 2022-04-03 Bank’s Approval Date of the Original Procurement Plan: 2023-06-04 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P167506 GPN Date: 2022-04-18 Project Name: Accelerating and Strengthening Skills for Economic Transformation Loan / Credit No: IDA / 68740 Technical and Madrasah Education Division Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned National Procure Component 3: Capacity Dev ment Document - BD-TMED-317150-CW-RFB / elopment, Project Managem Single Stage - One E Under Imple 2023-11-0 IDA / 68740 Post Request for Bids Open - National 1 Envelope proce 174,400.00 0.00 2023-02-28 2023-03-23 2023-03-21 2023-03-27 2023-05-02 2023-04-18 2023-07-01 2023-08-05 Office refurbishment of DTE ent, Social Marketing and M nvelope mentation 3 ss (Non Bank-SPD onitoring & Evaluation ) GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BD-TMED-286889-GO-RFB / Component 3: Capacity Dev Procurement of Desktop Com elopment, Project Managem Single Stage - One E IDA / 68740 Post Request for Bids Open - National 66,176.47 0.00 Signed 2022-04-05 2022-05-24 2022-04-10 2022-05-22 2022-06-13 2022-06-21 2022-07-03 2022-07-26 2023-01-22 puter, UPS, Laptop Computer ent, Social Marketing and M nvelope , Photocopier, Printer,Scanne onitoring & Evaluation r, DSLR Camera,etc BD-TMED-317151-GO-RFB / Component 1: Transforming Establishment of Internet & T Formal Skills Development f Single Stage - One E Pending Impl IDA / 68740 Post Request for Bids Open - National 17,450.00 0.00 2022-10-10 2022-10-25 2022-11-04 2022-12-04 2023-01-08 2023-07-07 elecom Network of the Projec or Future of Work, Inclusiven nvelope ementation t Office ess, and Resilience BD-TMED-317152-GO-RFB / Component 3: Capacity Dev Supply & installation of Offic elopment, Project Managem Single Stage - One E IDA / 68740 Post Request for Bids Open - National 16,280.00 0.00 Signed 2022-10-10 2022-11-30 2022-10-15 2022-11-26 2022-12-15 2022-12-26 2023-01-08 2023-01-30 2023-03-01 e Equipment (Photocopier, Pr ent, Social Marketing and M nvelope inter & Scanner) onitoring & Evaluation Component 3: Capacity Dev BD-TMED-317153-GO-RFB / elopment, Project Managem Single Stage - One E Pending Impl Supply and installation of PA IDA / 68740 Post Request for Bids Open - National 11,630.00 0.00 2022-10-11 2022-10-16 2022-11-27 2022-12-27 2023-01-31 2023-03-02 ent, Social Marketing and M nvelope ementation and multimedia system onitoring & Evaluation G2B / Supply and Installatio Component 3: Capacity Dev n of Laptop, Intercom System elopment, Project Managem Single Stage - One E Under Imple IDA / 68740 Post Request for Bids Open - National 32,500.00 0.00 2023-05-21 2023-06-12 2023-05-26 2023-06-12 2023-06-16 2023-07-31 2023-09-04 2023-12-03 and LAN for PMU including all ent, Social Marketing and M nvelope mentation accessories onitoring & Evaluation Component 3: Capacity Dev G5A / Supply of Furniture an elopment, Project Managem Single Stage - One E Pending Impl IDA / 68740 Post Request for Bids Open - National 232,550.00 0.00 2023-05-21 2023-05-26 2023-06-16 2023-07-31 2023-09-04 2024-01-02 d Fixtures for PMU office ent, Social Marketing and M nvelope ementation onitoring & Evaluation Component 3: Capacity Dev G11A / Supply of Computer elopment, Project Managem Request for Quota Single Stage - One E Under Imple IDA / 68740 Post Open - National 2,325.00 0.00 2023-05-26 2023-06-19 2023-06-22 2023-07-13 Consumables ent, Social Marketing and M tions nvelope mentation onitoring & Evaluation Component 3: Capacity Dev G15A / Supply of Stationarie elopment, Project Managem Request for Quota Single Stage - One E Pending Impl IDA / 68740 Post Open - National 1,400.00 0.00 2023-06-02 2023-06-29 2023-07-20 s for PMU office ent, Social Marketing and M tions nvelope ementation onitoring & Evaluation G57 / Supply of Materials for Component 1: Transforming Seminar, Workshops and Con Formal Skills Development f Single Stage - One E Pending Impl IDA / 68740 Post Request for Bids Open - National 232,550.00 0.00 2023-05-28 2023-06-02 2023-06-30 2023-07-30 2023-09-10 2025-09-09 ferences under framework co or Future of Work, Inclusiven nvelope ementation ntract ess, and Resilience G59 / Supply of Project Mana Component 3: Capacity Dev gement Information System elopment, Project Managem Single Stage - One E Under Imple IDA / 68740 Post Request for Bids Open - National 286,000.00 0.00 2023-05-28 2023-05-18 2023-06-02 2023-05-21 2023-06-04 2023-06-21 2023-08-03 2023-09-07 2023-12-06 Software with 04 year opera ent, Social Marketing and M nvelope mentation tional and maintenance supp onitoring & Evaluation ort Component 3: Capacity Dev BD-TMED-286891-GO-RFB / elopment, Project Managem Single Stage - One E Supply of Accounts and other IDA / 68740 Post Request for Bids Open - National 12,941.18 0.00 Canceled 2022-05-03 2022-05-08 2022-06-19 2022-07-19 2022-08-23 2023-02-19 ent, Social Marketing and M nvelope Software onitoring & Evaluation Component 3: Capacity Dev BD-TMED-286890-GO-RFB / elopment, Project Managem Single Stage - One E IDA / 68740 Post Request for Bids Open - National 35,294.12 0.00 Canceled 2022-04-12 2022-04-17 2022-05-29 2022-06-28 2022-08-02 2023-01-29 Supply of furniture for PMU ent, Social Marketing and M nvelope onitoring & Evaluation NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 1: Transforming NCS1A / Selection of Event Formal Skills Development f Single Stage - One E Pending Impl Management firm for Semina IDA / 68740 Post Request for Bids Open - National 55,800.00 0.00 2023-05-28 2023-06-02 2023-06-30 2023-08-29 2023-10-03 2024-03-31 or Future of Work, Inclusiven nvelope ementation rs and Workshops ess, and Resilience CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 1 BD-TMED-286611-CS-QCBS / Selection of firm/ institution f Component 1: Transforming or organizing seminars and w Formal Skills Development f Quality And Cost- orkshops for TTIs (1), Partner IDA / 68740 Post Open - National 228,235.29 0.00 Canceled 2022-04-03 2022-04-24 2022-06-07 2022-07-05 2022-08-04 2022-09-08 2022-10-13 2023-10-13 or Future of Work, Inclusiven Based Selection organizations (1), RPL for em ess, and Resilience ployers and workers (2) and DTE (1), project launching ce remony (1) BD-TMED-286628-CS-QCBS / Component 3: Capacity Dev Selection of Consultant for R elopment, Project Managem Quality And Cost- apid Assessment and follow- IDA / 68740 Post Open - National 117,647.06 0.00 Canceled 2022-04-20 2022-05-11 2022-06-24 2022-07-22 2022-08-21 2022-09-25 2022-10-30 2023-10-30 ent, Social Marketing and M Based Selection up on Diploma Students by D onitoring & Evaluation TE (1), Demand and Gap Ana lysis by BTEB (1) Component 3: Capacity Dev BD-TMED-286635-CS-QCBS / elopment, Project Managem Quality And Cost- Survey and Studies by BMET IDA / 68740 Post Open - National 235,294.12 0.00 Canceled 2022-04-27 2022-05-18 2022-07-01 2022-07-29 2022-08-28 2022-10-02 2022-11-06 2023-11-06 ent, Social Marketing and M Based Selection (2), NSDA (1), DTE (1) onitoring & Evaluation BD-TMED-286641-CS-FBS / S Component 3: Capacity Dev election of Consultant for TV elopment, Project Managem Fixed Budget Sele Pending Impleme IDA / 68740 Post Open - National 29,411.76 0.00 2022-04-10 2022-05-01 2022-06-14 2022-07-12 2022-08-11 2022-09-15 2022-10-20 2023-10-20 C production (1), Radio Ad pr ent, Social Marketing and M ction ntation oduction (2) onitoring & Evaluation BD-TMED-286888-CS-QCBS / Component 3: Capacity Dev Selection of Consulting Firm f elopment, Project Managem Quality And Cost- IDA / 68740 Post Open - National 174,117.65 0.00 Canceled 2022-04-24 2022-05-15 2022-06-28 2022-07-26 2022-08-25 2022-09-29 2022-11-03 2023-11-03 or Competency Standard Dev ent, Social Marketing and M Based Selection elopment for BTEB (12), BME onitoring & Evaluation T (40), S51 / Selection of Consultant for Demand and Gap Analysi Component 3: Capacity Dev s under BTEB: Analyzing the elopment, Project Managem Consultant Qualifi Skills and Competency Gaps IDA / 68740 Post Open - National 58,000.00 0.00 Under Review 2023-03-01 2023-03-23 2023-03-22 2023-05-05 2023-06-23 2023-08-04 2024-01-31 ent, Social Marketing and M cation Selection of the Selected Diploma in En onitoring & Evaluation gineering Courses Running U nder the Bangladesh Technic al Education Board S55A / Selection of Consulta nt for Survey and Studies un Component 3: Capacity Dev der BTEB on Analyzing Weak elopment, Project Managem Quality And Cost- IDA / 68740 Post Open - National 93,000.00 0.00 Under Review 2023-03-01 2023-03-23 2023-03-22 2023-05-05 2023-06-30 2023-07-30 2023-09-03 2023-10-15 2024-04-12 nesses, Prospects, and Effect ent, Social Marketing and M Based Selection iveness of Industrial Attachm onitoring & Evaluation ent of Diploma in Engineerin g Courses Running S59A / Selection of Consultin Component 3: Capacity Dev g firm for Surveys and Studie elopment, Project Managem Consultant Qualifi IDA / 68740 Post Open - National 58,000.00 0.00 Under Review 2023-03-07 2023-03-23 2023-03-28 2023-05-11 2023-06-22 2023-08-03 2024-01-30 s under NSDA (Sector: Creati ent, Social Marketing and M cation Selection ve Media) onitoring & Evaluation INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 3: Capacity Dev BD-TMED-286652-CS-INDV / elopment, Project Managem Individual Consult Selection of Financial Manag IDA / 68740 Prior Open 352,941.18 0.00 Signed 2022-04-03 2022-04-18 2022-05-22 2022-09-21 2022-06-12 2022-10-24 2022-07-17 2023-01-13 ent, Social Marketing and M ant Selection ement Specialist (1) onitoring & Evaluation Component 3: Capacity Dev BD-TMED-286655-CS-INDV / elopment, Project Managem Individual Consult Selection of Junior Financial IDA / 68740 Post Open 197,647.06 0.00 Signed 2022-04-03 2022-04-16 2022-05-22 2023-02-23 2022-06-12 2023-02-23 2022-07-17 2023-01-13 ent, Social Marketing and M ant Selection Management Specialist (1) onitoring & Evaluation Component 3: Capacity Dev BD-TMED-286658-CS-INDV / elopment, Project Managem Individual Consult Selection of Procurement Spe IDA / 68740 Prior Open 364,705.88 0.00 Signed 2022-04-04 2022-04-17 2022-05-23 2022-09-21 2022-06-13 2022-10-27 2022-07-18 2023-01-14 ent, Social Marketing and M ant Selection cialist (1) onitoring & Evaluation Component 3: Capacity Dev BD-TMED-286660-CS-INDV / elopment, Project Managem Individual Consult Selection of Junior Procureme IDA / 68740 Prior Open 218,823.53 0.00 Signed 2022-04-04 2022-04-20 2022-05-23 2023-02-23 2022-06-13 2023-03-28 2022-07-18 2023-05-02 2023-01-14 ent, Social Marketing and M ant Selection nt Specialist (1) onitoring & Evaluation Component 3: Capacity Dev BD-TMED-286661-CS-INDV / elopment, Project Managem Individual Consult Selection of IDG Managemen IDA / 68740 Prior Open 317,647.06 0.00 Signed 2022-04-04 2022-04-20 2022-05-23 2022-09-21 2022-06-13 2022-10-25 2022-07-18 2023-01-14 ent, Social Marketing and M ant Selection t Specialist (1) onitoring & Evaluation Component 3: Capacity Dev BD-TMED-286883-CS-INDV / elopment, Project Managem Individual Consult Selection of ICT and MIS Spec IDA / 68740 Prior Open 282,352.94 0.00 Signed 2022-04-04 2022-04-20 2022-05-23 2022-09-21 2022-06-13 2022-10-25 2022-07-18 2023-01-14 ent, Social Marketing and M ant Selection ialist (1) onitoring & Evaluation Component 3: Capacity Dev BD-TMED-286885-CS-INDV / elopment, Project Managem Individual Consult Under Implement Selection of E&S safeguard S IDA / 68740 Prior Open 235,294.12 0.00 2022-04-28 2022-08-07 2022-06-16 2022-07-07 2022-08-11 2023-02-07 ent, Social Marketing and M ant Selection ation pecialist (1) onitoring & Evaluation BD-TMED-316744-CS-INDV / Component 3: Capacity Dev Selection of TVET & Industry elopment, Project Managem Individual Consult Under Implement IDA / 68740 Prior Open - National 310,000.00 0.00 2022-09-27 2022-11-07 2022-11-15 2022-12-06 2023-01-10 2025-01-09 Development Management S ent, Social Marketing and M ant Selection ation pecialist onitoring & Evaluation Component 3: Capacity Dev BD-TMED-286886-CS-INDV / elopment, Project Managem Individual Consult Pending Impleme Selection of Short Term Tech IDA / 68740 Prior Open - National 350,000.00 0.00 2022-09-27 2022-11-15 2022-12-06 2023-01-10 2023-07-09 ent, Social Marketing and M ant Selection ntation nical Specialist onitoring & Evaluation Component 3: Capacity Dev BD-TMED-317145-CS-INDV / elopment, Project Managem Individual Consult Selection of Monitoring & Eva IDA / 68740 Prior Open - National 590,000.00 0.00 Under Review 2022-09-30 2022-11-07 2022-11-18 2022-12-09 2023-01-13 2025-01-12 ent, Social Marketing and M ant Selection luation Specialist onitoring & Evaluation Component 3: Capacity Dev BD-TMED-317147-CS-INDV / elopment, Project Managem Individual Consult Selection of Skills Training Sp IDA / 68740 Prior Open - National 310,000.00 0.00 Under Review 2022-10-05 2022-11-07 2022-11-23 2022-12-14 2023-01-18 2025-01-07 ent, Social Marketing and M ant Selection ecialist onitoring & Evaluation Component 3: Capacity Dev BD-TMED-317148-CS-INDV / elopment, Project Managem Individual Consult Under Implement Selection of Communication IDA / 68740 Prior Open - National 310,000.00 0.00 2022-10-05 2022-11-07 2022-11-23 2022-12-14 2023-01-18 2025-01-17 ent, Social Marketing and M ant Selection ation Speciaist onitoring & Evaluation Page 2 Component 3: Capacity Dev S39B / Selection of IDG Spec elopment, Project Managem Individual Consult IDA / 68740 Post Limited 34,800.00 0.00 Under Review 2023-06-08 2023-06-06 2023-06-13 2023-07-04 2023-08-15 2024-02-11 ialist (Health) ent, Social Marketing and M ant Selection onitoring & Evaluation Page 3 PROCUREMENT PLAN (Textual Part) Project information: Mozambique – Mozambique: Access to Finance & Economic Opportunities Project – P178658 Project Implementation agency: Ministry of Economy and Finance Date of the Procurement Plan: March 20, 2023 Period covered by this Procurement Plan: from March 22, 2023 to August 31, 2024 (18 months) Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in Decree 79/ 2022 of 30th December 2022 (in replacement of Decree 5/2016), such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Not Applicable. Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations: Not Applicable. Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: is not applicable; Works: is not applicable. PROCUREMENT Mozambique : Access to Finance & Economic Opportunities Project – Mais Oportunidades PLAN General Information Country: Mozambique 2023-03-22 Bank’s Approval Date of the Original Procurement Plan: 2023-06-04 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P178658 GPN Date: Project Name: Access to Finance & Economic Opportunities Project – Mais Oportunidades Loan / Credit No: / , IDA / 72780 Ministry of Economy and Finance - DNT Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MZ-MEF-DNT-350986-CS-IND Component 1. Promote acce Individual Consult Open - Internationa Under Implement V / Credit Guarantee Fund M / ss and usage of financial ser Post 200,000.00 0.00 2023-03-31 2023-03-22 2023-06-12 2023-07-03 2023-08-21 2028-08-19 ant Selection l ation anager vices for MSMEs MZ-MEF-DNT-351009-CS-IND Component 1. Promote acce Individual Consult Under Implement V / Risk and Compliance Man / ss and usage of financial ser Post Open - National 150,000.00 0.00 2023-04-14 2023-03-23 2023-07-06 2023-08-05 2023-09-23 2026-09-22 ant Selection ation ager vices for MSMEs MZ-MEF-DNT-351014-CS-IND Component 1. Promote acce Individual Consult Under Implement V / Credit Risk and Operation / ss and usage of financial ser Post Open - National 120,000.00 0.00 2023-04-21 2023-03-23 2023-07-13 2023-08-12 2023-09-30 2026-09-29 ant Selection ation s Manager vices for MSMEs MZ-MEF-DNT-364905-CS-IND Component 3. Project mana Individual Consult Pending Impleme IDA / 72780 Post Open - National 86,400.00 0.00 2023-07-20 2023-10-21 2023-11-25 2024-01-20 2026-01-19 V / Financial Services Speciali gement ant Selection ntation st Component 1. Promote acce MZ-MEF-DNT-364907-CS-IND Individual Consult Pending Impleme IDA / 72780 ss and usage of financial ser Post Open - National 120,000.00 0.00 2023-07-21 2023-10-22 2023-11-21 2024-01-09 2026-01-08 V / Line of Credit Manager ant Selection ntation vices for MSMEs MZ-MEF-DNT-364920-CS-IND Component 3. Project mana Individual Consult Pending Impleme IDA / 72780 Prior Open - National 64,800.00 0.00 2023-07-31 2023-11-01 2023-12-06 2024-01-24 2026-01-23 V / Procurement Consultant gement ant Selection ntation MZ-MEF-DNT-364908-CS-IND Component 1. Promote acce V / Individual consulting servi Individual Consult Pending Impleme IDA / 72780 ss and usage of financial ser Post Open - National 120,000.00 0.00 2023-07-31 2023-11-01 2023-12-01 2024-01-19 2026-01-18 ces for Financial Inclusion Pro ant Selection ntation vices for MSMEs gramme Manager (micro-savi ngs) MZ-MEF-DNT-364917-CS-IND V / Individual consulting servi Component 3. Project mana Individual Consult IDA / 72780 Post Open - National 75,600.00 0.00 Under Review 2023-08-30 2023-12-11 2024-01-10 2024-02-28 2026-02-27 ces for Social Specialist with gement ant Selection health and safety experience MZ-MEF-DNT-364910-CS-IND V / Individual consulting servi Component 3. Project mana Individual Consult Pending Impleme IDA / 72780 Post Open - National 75,600.00 0.00 2023-08-18 2023-11-19 2023-12-19 2024-02-06 2026-02-05 ces for Social Specialist with gement ant Selection ntation experience in resettlement Page 1 PROCUREMENT PLAN (Textual Part) Project information: [country]Congo Democratic Republic, EMERGENCY EQUITY AND SYSTEM STRENGTHENING IN EDUCATION PROJECT [Project name] [P-number] Project Implementation agency: [insert legal name] Date of the Procurement Plan: [insert date] Period covered by this Procurement Plan: [insert from – to period] Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in [insert appropriate references to the national procurement legislation], such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. List only the applicable conditions required to ensure consistency with paragraph 5.4 of the Procurement Regulations. If no conditions apply, delete the phrase “and the following conditions”. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. Otherwise state “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables Otherwise state “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Specify for each Goods: [is not applicable/is applicable for those contracts identified in the Procurement Plan tables]; Works: [is not applicable/is applicable for those contracts identified in the Procurement Plan tables] Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations is Applicable. [Include this sentence only if the Bank has formally agreed to provide the Borrower with HEIS. Otherwise delete] Other Relevant Procurement Information. Provide any other relevant procurement information such as procedures for CDD components, Procurement in Situations of Urgent Need of Assistance or Capacity Constraints etc. PROCUREMENT Congo, Democratic Republic of : DR Congo Emergency Equity and System Strengthening in Education PLAN General Information Country: Congo, Democratic Republic of 2020-08-11 Bank’s Approval Date of the Original Procurement Plan: 2023-06-04 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P172341 GPN Date: Project Name: DR Congo Emergency Equity and System Strengthening in Education Loan / Credit No: IDA / 66920 Permanent Secretariat for Support and Coordination of the Education Sector Executing Agency(ies): WORKS Activity Reference No. / Procureme Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH Ri Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method nt Docume ount (US$ and Recommendation Signed Contract o. h cess (Y/N) sk atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion nt Type ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ZR-SPACE-214168-CW-RFQ / Travaux d'aménagement des Component 3: Strengthening Request for Quota Single Stage - One E 2021-04-2 IDA / 66920 Post Limited 52,613.00 Signed 2021-01-22 2021-01-05 2021-03-10 2021-02-19 bureaux pour l'Equipe de Coo Systems for Results tions nvelope 4 rdination du Projet (ECP) du P rojet PERSE Request for ZR-SPACE-272628-CW-RFQ / Quotations - TRAVAUX D'AMENAGEMENT Component 3: Strengthening Request for Quota Single Stage - One E Small Works 2022-09-0 IDA / 66920 Post Limited 0.00 Signed 2022-01-16 2022-08-18 2022-03-13 DE 6 CONTAINERS EN BUREA Systems for Results tions nvelope (Emergency) 9 UX POUR LE PROJET PERSE SPD -Compet itive Request for ZR-SPACE-296497-CW-RFQ / Quotations - Travaux d'aménagement des Component 3: Strengthening Request for Quota Single Stage - One E Small Works 2023-01-2 IDA / 66920 Post Limited 0.00 Signed 2022-06-06 2022-08-18 2022-08-01 douze (12) bureaux en faveu Systems for Results tions nvelope (Emergency) 8 r des Directions d'appui MEP SPD -Compet ST itive GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ZR-SPACE-209748-GO-RFQ / Component 3: Strengthening Request for Quota Single Stage - One E Fourniture des supports de c IDA / 66920 Post Limited 69,950.00 Signed 2020-12-15 2020-12-04 2021-01-28 2021-01-21 2021-02-27 Systems for Results tions nvelope ommunication pour le PERSE ZR-SPACE-209751-GO-RFQ / Fourniture et installation des Component 3: Strengthening Request for Quota Single Stage - One E IDA / 66920 Post Limited 45,800.00 Completed 2020-12-15 2020-12-04 2021-01-10 2021-01-21 2021-02-09 2021-04-01 équipements vidéo conféren Systems for Results tions nvelope ce pour l'UCP PERSE ZR-SPACE-209756-GO-RFQ / Component 3: Strengthening Request for Quota Single Stage - One E Acquisition de deux véhicule IDA / 66920 Post Limited 94,450.00 Completed 2020-12-15 2020-12-15 2021-01-05 2021-03-24 2021-02-04 2021-09-17 Systems for Results tions nvelope s utilitaires pour l'UCP PERSE ZR-SPACE-229255-GO-RFQ / ACQUISITION MOBILIER DE B Component 3: Strengthening Request for Quota Single Stage - One E IDA / 66920 Post Limited 94,415.00 Completed 2021-04-19 2021-04-15 2021-06-14 2021-05-11 2021-12-11 UREAU POUR L'EQUIPE DE C Systems for Results tions nvelope OORDINATION (ECP) DU PROJ ET PERSE A KINSHASA ZR-SPACE-229266-GO-RFQ / ACQUISITION EQUIPEMENTS I Component 3: Strengthening Request for Quota Single Stage - One E NFORMATIQUES POUR L'EQU IDA / 66920 Post Limited 94,060.00 Completed 2021-04-19 2021-04-15 2021-06-14 2021-05-11 2021-12-11 2021-06-25 Systems for Results tions nvelope IPE DE COORDINATION DU P ROJET PERSE A KINSHASA ZR-SPACE-237602-GO-RFQ / ACQUISITION DES FOURNITU RES DE BUREAU ET CONSOM Component 3: Strengthening Request for Quota Single Stage - One E MABLES INFORMATIQUES PO IDA / 66920 Post Limited 52,533.83 Completed 2021-06-06 2021-07-26 2021-08-01 2021-08-14 2022-01-28 Systems for Results tions nvelope UR L'EQUIPE DE COORDINATI ON DU PROJET (ECP) PERSE P OUR 3 MOIS ( JUILLET -AOUT- SEPTEMBRE 2021) ZR-SPACE-248721-GO-RFP / Component 3: Strengthening Request for Quota Single Stage - One E Impression du code de bonne IDA / 66920 Post Limited 103,550.00 Completed 2021-09-19 2021-08-23 2021-11-07 2021-09-14 2022-02-05 2022-01-15 Systems for Results tions nvelope conduite (Acte d'engagemen t) ZR-SPACE-252528-GO-RFB / Component 3: Strengthening Single Stage - One E Under Imple ACQUISITION DE 11 VEHICUL IDA / 66920 Post Request for Bids Open - National 0.00 2021-09-08 2021-11-01 2021-09-13 2021-10-25 2021-11-24 2021-12-29 2022-06-27 Systems for Results nvelope mentation ES DE TERRAIN POUR LE PRO JET PERSE ZR-SPACE-256454-GO-RFQ / ACQUISITION DE MOBILIER D E BUREAU POUR L'EQUIPE DE Component 3: Strengthening Request for Quota Single Stage - One E COORDINATION DU PROJET P IDA / 66920 Post Limited 60,600.00 Completed 2021-10-09 2021-09-27 2021-12-04 2021-10-23 2022-06-02 2021-12-05 Systems for Results tions nvelope ERSE (ECP EN PROVINCE : KA NANGA, MBUJI-MAYI, TSHIKAP A, KABINDA, MATADI, BANDU NDU VILLE ZR-SPACE-259196-GO-RFQ / Component 3: Strengthening Request for Quota Single Stage - One E FOURNITURE DES SUPPORTS IDA / 66920 Post Limited 98,550.00 Completed 2021-10-26 2021-10-21 2021-12-21 2021-12-16 2022-06-19 2022-02-15 Systems for Results tions nvelope DE COMMUNICATION POUR L E PROJET PERSE ZR-SPACE-261260-GO-RFB / Component 3: Strengthening Single Stage - One E IMPRESSION DU CODE DE BO IDA / 66920 Post Request for Bids Open - National 0.00 Completed 2021-11-02 2022-03-30 2021-11-07 2021-12-19 2022-05-03 2022-01-18 2022-06-10 2022-02-22 2022-08-21 2022-11-03 Systems for Results nvelope NNE CONDUITE ZR-SPACE-272906-GO-RFQ / ACQUISITION D'UN SYSTEME Component 3: Strengthening Request for Quota Single Stage - One E Pending Impl ELECTRONIQUE DE POINTAG IDA / 66920 Post Limited 0.00 2022-01-18 2022-03-15 2022-09-11 Systems for Results tions nvelope ementation E DE PRESENCE DU PERSON NEL DU PROJET PERSE ZR-SPACE-272911-GO-RFQ / ACQUISITION DES FOURNITU Component 3: Strengthening Request for Quota Single Stage - One E IDA / 66920 Post Limited 0.00 Signed 2022-01-18 2022-04-08 2022-03-15 2022-09-11 RES DE BUREAU ET PETITS M Systems for Results tions nvelope ATERIELS POUR LE PROJET PE RSE ZR-SPACE-272912-GO-RFQ / ACQUISITION DES CONSOMM Component 3: Strengthening Request for Quota Single Stage - One E IDA / 66920 Post Limited 0.00 Signed 2022-01-18 2022-04-08 2022-03-15 2022-09-11 ABLES INFORMATIQUES POU Systems for Results tions nvelope R LE PROJET PERSE Page 1 ZR-SPACE-272914-GO-RFQ / ACQUISITION DU MATERIEL E Component 3: Strengthening Request for Quota Single Stage - One E Pending Impl T LOCATION D'UNE BANDE P IDA / 66920 Post Limited 0.00 2022-01-18 2022-03-15 2022-09-11 Systems for Results tions nvelope ementation ASSANTE POUR L'ABONNEME NT INTERNET DES BUREAUX DU PROJET PERSE ZR-SPACE-256601-GO-RFQ / ACQUISITION ET INSTALLATI Component 3: Strengthening Request for Quota Single Stage - One E ON D'UN GROUPE ELECTROG IDA / 66920 Post Limited 34,200.00 Completed 2021-10-10 2021-10-06 2021-12-05 2021-10-26 2022-06-03 2021-11-02 Systems for Results tions nvelope ENE DE 100 KVA POUR LE PR OJET PERSE A KINSHASA ZR-SPACE-296501-GO-RFQ / Acquisition d'Ordinateurs por tables (Laptops), imprimante Component 3: Strengthening Request for Quota Single Stage - One E IDA / 66920 Post Limited 0.00 Completed 2022-06-14 2022-06-01 2022-08-09 2023-02-05 s en couleurs et les Rétroproj Systems for Results tions nvelope ecteurs vidéo en faveur des Directions d'appui du MEPST ZR-SPACE-296503-GO-RFQ / Acquisition des mobiliers et c Component 3: Strengthening Request for Quota Single Stage - One E Pending Impl IDA / 66920 Post Limited 0.00 2022-06-19 2022-08-14 2023-02-10 limatisation des bureaux des Systems for Results tions nvelope ementation Directions d'appui du MEPST ZR-SPACE-300083-GO-RFB / ACQUISITION DES MOTOS AU Component 3: Strengthening Single Stage - One E IDA / 66920 Post Request for Bids Open - National 0.00 Signed 2022-09-16 2022-08-19 2022-09-21 2022-11-02 2022-09-22 2022-12-02 2022-10-14 2023-01-06 2023-07-05 PROFIT DES SOUS-DIVISIONS Systems for Results nvelope PROVINCIALES CIBLEES PAR LE PERSE ZR-SPACE-300092-GO-RFB / ACQUISITION DE CANOTS RA Component 3: Strengthening Single Stage - One E Pending Impl IDA / 66920 Post Request for Bids Open - National 0.00 2022-08-22 2022-08-27 2022-10-08 2022-11-07 2022-12-12 2023-06-10 PIDES AU PROFIT DES 2 SOU Systems for Results nvelope ementation S DIVISIONS LACUTSRES ZR-SPACE-300098-GO-RFB / ACQUISITION DES KITS INFOR Component 3: Strengthening Single Stage - One E MATIQUES (LAP TOP ET IMPR IDA / 66920 Post Request for Bids Open - National 0.00 Signed 2022-09-15 2022-08-18 2022-09-20 2022-11-01 2022-09-20 2022-12-01 2022-10-12 2023-01-05 2023-07-04 Systems for Results nvelope OMANTES) AU PROFIT DES DI VISIONS PROVINCIALES CIBL EES PAR LE PERSE ZR-SPACE-305596-GO-RFB / ACQUISITION DE MATERIEL I Component 3: Strengthening Open - Internationa Single Stage - One E Under Imple IDA / 66920 Prior Request for Bids 0.00 2022-08-16 2022-10-20 2022-08-21 2022-11-23 2022-10-02 2023-01-10 2022-11-01 2022-12-06 2023-06-04 NFORMATIQUE POUR LES DIF Systems for Results l nvelope mentation FERENTES DIRECTIONS DU M EPST ZR-SPACE-305616-GO-RFQ / PRODUCTION DES SUPPORTS Component 3: Strengthening Request for Quota Single Stage - One E Under Imple IDA / 66920 Post Limited 0.00 2022-07-27 2022-10-13 2022-09-21 2023-03-20 DE FIN D'ANNEE (AGENDAS, Systems for Results tions nvelope mentation CALENDRIERS ET AUTRES GA DGET) ZR-SPACE-305621-GO-RFQ / PRODUCTION DES SUPPORTS Component 3: Strengthening Request for Quota Single Stage - One E IDA / 66920 Post Limited 0.00 Completed 2022-07-27 2022-08-18 2022-09-21 2023-03-20 2023-02-27 DE VULGARISATION DU NUM Systems for Results tions nvelope ERO VERT 178 ZR-SPACE-305623-GO-RFQ / PRODUCTION DES FEUILLETS Component 3: Strengthening Request for Quota Single Stage - One E IDA / 66920 Post Limited 0.00 Signed 2022-08-31 2022-09-22 2022-10-26 2023-04-24 DE SENSIBIISATION SUR LE M Systems for Results tions nvelope ECANISME DE GESTION DES PLAINTES ZR-SPACE-305626-GO-RFQ / IMPRESSION DES SUPPORTS Component 3: Strengthening Request for Quota Single Stage - One E IDA / 66920 Post Limited 0.00 Signed 2022-08-29 2022-08-18 2022-10-24 2023-04-22 DE VISIBILITE DU PROJET/RE Systems for Results tions nvelope NOUVELLEMENT STOCK ZR-SPACE-305631-GO-RFQ / Component 3: Strengthening Request for Quota Single Stage - One E Pending Impl PRODUCTION ET MULTIPLICA IDA / 66920 Post Limited 0.00 2022-07-27 2022-09-21 2023-03-20 Systems for Results tions nvelope ementation TION DES MODULES DE FOR MATION ZR-SPACE-305634-GO-RFQ / Component 3: Strengthening Request for Quota Single Stage - One E PRODUCTION DES SUPPORTS IDA / 66920 Post Limited 0.00 Completed 2022-08-20 2022-09-13 2022-10-11 2023-04-09 2022-11-07 Systems for Results tions nvelope DE SENSIBILISATION DIFORE ZR-SPACE-305636-GO-RFQ / Component 3: Strengthening Request for Quota Single Stage - One E Pending Impl IMPRESSION DU MODULE MG IDA / 66920 Post Limited 0.00 2022-07-27 2022-09-21 2023-03-20 Systems for Results tions nvelope ementation P EN 15 000 EXEMPLAIRES (I LD4) ZR-SPACE-305637-GO-RFQ / IMPRESSION DU MANUEL DE Component 3: Strengthening Request for Quota Single Stage - One E Pending Impl IDA / 66920 Post Limited 0.00 2022-07-27 2022-09-21 2023-03-20 PROCEDURE DE GESTION DE Systems for Results tions nvelope ementation S FRAIS DE FONCTIONNEMEN T ZR-SPACE-305638-GO-RFQ / Component 3: Strengthening Request for Quota Single Stage - One E Pending Impl IMPRESSION DE MANUEL DE IDA / 66920 Post Limited 0.00 2022-07-27 2022-09-21 2023-03-20 Systems for Results tions nvelope ementation FORMATION DE COGES ZR-SPACE-305640-GO-RFQ / Component 3: Strengthening Request for Quota Single Stage - One E Pending Impl IDA / 66920 Post Limited 0.00 2022-07-27 2022-09-21 2023-03-20 IMPRESSION BUDGET CITOYE Systems for Results tions nvelope ementation N ZR-SPACE-329759-GO-RFQ / ACQUISITION DE 10 GROUPE Component 3: Strengthening Request for Quota Single Stage - One E Pending Impl S ELECTROGENES POUR LES IDA / 66920 Post Limited 0.00 2022-12-17 2023-02-11 2023-08-10 Systems for Results tions nvelope ementation BUREAUX PERSE EN PROVIN CES (10KVA), FRAIS D'INSTAL LATION ET ACCESSOIRES ZR-SPACE-358640-GO-DIR / Contractualisation avec la fir me GMSP-COM pour l'acquisit Component 3: Strengthening Under Imple IDA / 66920 Post Direct Selection Direct - National 0.00 2023-04-26 2023-04-25 2023-05-01 2023-04-24 2023-06-05 2023-12-02 ion des cartes SIM VPN et forf Systems for Results mentation ait connexion pour la collecte des données dans les 10 Pro vinces ciblées par le PERSE ZR-SPACE-358644-GO-DIR / Contractualisation avec la fir Component 3: Strengthening Under Imple me LIFT TECH COMPANY pou IDA / 66920 Post Direct Selection Direct - National 0.00 2023-04-26 2023-04-25 2023-05-01 2023-04-24 2023-06-05 2023-12-02 Systems for Results mentation r l'acquisition de 1000 Tablet tes pour la collecte des donn ées scolaires 2022-2023 NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Page 2 Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ZR-SPACE-227692-NC-DIR / Acquisition du logiciel TOMPR Component 3: Strengthening Pending Impl IDA / 66920 Post Direct Selection Direct 0.00 2021-09-14 2021-09-19 2021-10-24 2021-11-23 O pour la gestion comptable Systems for Results ementation du projet PERSE : TOMATE ZR-SPACE-272910-NC-RFB / RECRUTEMENT D'UN PRESTA TAIRE EN QUALITE D'UNE AG Component 3: Strengthening Single Stage - One E Pending Impl IDA / 66920 Post Request for Bids Open - National 0.00 2022-01-13 2022-01-18 2022-03-01 2022-03-31 2022-05-05 2022-11-01 ENCE DE VOYAGE POUR L'AC Systems for Results nvelope ementation QUISITION DES TITRES DE VO YAGE AINSI QUE LES FORMAL ITES Y RELATIVES ZR-SPACE-272913-NC-RFQ / RECRUTEMENT D'UN CABINE T EN CHARGE DE L'ENTRETIE Component 3: Strengthening Request for Quota Single Stage - One E Pending Impl IDA / 66920 Post Limited 0.00 2022-01-18 2022-03-15 2022-09-11 N ET MAINTENANCE DU MAT Systems for Results tions nvelope ementation ERIEL INFORMATIQUE, PLOM BERIE ET CLIMATISATION PO UR LE PROJET PERSE ZR-SPACE-305975-NC-RFQ / Contrat avec un assureur ma Component 3: Strengthening Request for Quota Single Stage - One E Pending Impl IDA / 66920 Post Limited 0.00 2022-07-30 2022-09-24 2023-03-23 ladie pour la prise en charge Systems for Results tions nvelope ementation des soins médicaux des mem bres de l'ECP PERSE ZR-SPACE-314511-NC-RFQ / RECRUTEMENT D'UNE SOCIE Component 3: Strengthening Request for Quota Single Stage - One E Pending Impl IDA / 66920 Post Limited 0.00 2022-09-25 2022-11-20 2023-05-19 TE DE GARDIENNAGE POUR L Systems for Results tions nvelope ementation ES BUREAUX DU PERSE A KIN SHASA ZR-SPACE-326748-NC-RFQ / Component 3: Strengthening Request for Quota Single Stage - One E Pending Impl PRODUCTION D'UN FILM DE S IDA / 66920 Post Limited 0.00 2022-11-30 2023-01-25 2023-07-24 Systems for Results tions nvelope ementation ENSIBILISATION AUX VBG/EA S/HS ET MGP CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ZR-SPACE-187618-CS-CQS / Component 3: Strengthening Consultant Qualifi Pending Impleme Sélection de la firme pour la IDA / 66920 Post Open - National 0.00 2021-02-09 2021-03-02 2021-04-15 2021-05-15 2021-06-19 2023-06-09 Systems for Results cation Selection ntation revue du Plan de Travail Ann uel (PTA) ZR-SPACE-191896-CS-CQS / Sélection du Cabinet pour le Component 3: Strengthening Consultant Qualifi IDA / 66920 Post Open - National 96,825.08 Completed 2020-09-15 2020-09-28 2020-10-06 2020-11-03 2020-11-02 2020-11-10 2020-12-09 2020-12-01 2021-01-14 2021-01-30 2021-10-15 recrutement du personnel clé Systems for Results cation Selection de l'équipe de gestion du pro jet ZR-SPACE-198450-CS-CQS / Sélection du Cabinet Firme l' Component 3: Strengthening Consultant Qualifi Audit externe du Programme IDA / 66920 Post Limited 106,350.00 Signed 2020-10-08 2020-10-06 2020-10-22 2020-11-02 2020-10-29 2020-11-12 2020-11-19 2020-11-19 2020-12-19 Systems for Results cation Selection des Dépenses Eligibles (EEP) au 30 novembre 2020 ZR-SPACE-187535-CS-UN / S élection de l'Agence des Nati Component 3: Strengthening UN Agencies (Dire ons Unies pour la mise en œ IDA / 66920 Prior Direct 15,000,000.00 Signed 2020-11-03 2021-01-12 2020-11-10 Systems for Results ct) uvre du programme pilote " é coles sécurisées et inclusives " : UNFPA ZR-SPACE-221809-CS-QCBS / Cabinet d'Assistance Techni Component 3: Strengthening Quality And Cost- Open - Internationa Under Implement que pour appuyer la mise en IDA / 66920 Post 0.00 2021-03-05 2021-03-23 2021-03-19 2021-06-25 2021-04-16 2021-05-14 2021-05-28 2021-06-25 2021-07-30 2022-07-30 Systems for Results Based Selection l ation oeuvre de l'ILD 5 et les activ ités de la Composante 3.2 lié es au MGP et l'EC ZR-SPACE-223392-CS-QCBS / Sélection du Cabinet d'assis tance technique chargé d'ap Component 3: Strengthening Quality And Cost- Open - Internationa Under Implement IDA / 66920 Post 0.00 2021-03-10 2021-03-23 2021-03-31 2021-06-25 2021-04-28 2021-05-26 2021-06-25 2021-07-30 2021-09-03 2022-09-03 puyer les activités liées aux I Systems for Results Based Selection l ation LD 2,3,6 et 7 et de renforcer les Directions responsables d e ces ILD ZR-SPACE-221808-CS-QCBS / Sélection du Cabinet / ONG d'Assistance technique pour Component 3: Strengthening Consultant Qualifi Open - Internationa Under Implement appuyer les activités suivant IDA / 66920 Post 0.00 2021-03-22 2021-03-29 2021-04-12 2021-04-08 2021-05-26 2021-06-19 2021-06-09 2021-11-10 2021-07-14 2022-01-10 Systems for Results cation Selection l ation es de la Composante 3.1: ren forcer le SIGE et entreprendr e une revue fonctionnelle de la DIGE. ZR-SPACE-226130-CS-QBS / Sélection du Cabinet / ONG d Component 3: Strengthening Quality Based Sel Open - Internationa Under Implement 'Assistance technique pour le IDA / 66920 Post 0.00 2021-04-01 2021-04-01 2021-04-22 2021-04-07 2021-06-05 2021-07-07 2021-07-03 2021-08-02 2021-09-01 2021-10-06 2022-10-06 Systems for Results ection l ation s activités de Communication ( y compris vis-à-vis du MGP) ZR-SPACE-241434-CS-QCBS / Sélection d'un Cabinet pour la formation, sensibilisation e Component 3: Strengthening Quality And Cost- Open - Internationa Under Implement IDA / 66920 Post 0.00 2021-06-29 2021-08-05 2021-07-20 2021-08-09 2021-08-17 2021-09-14 2021-09-15 2021-10-13 2021-11-17 2023-11-07 t suivi sur les Violences Basé Systems for Results Based Selection l ation es sur le Genre (VBG) au nive au des Points Focaux MGP/ P ERSE ZR-SPACE-187608-CS-QCBS / Sélection des firmes pour la Component 3: Strengthening Quality And Cost- Open - Internationa réalisation des reformes du s IDA / 66920 Prior 0.00 Canceled 2020-08-31 2020-09-21 2020-11-04 2020-12-02 2021-01-01 2021-02-05 2021-03-12 2023-03-02 Systems for Results Based Selection l ystème d'enseignement prim aire et l'amélioration de la go uvernance ZR-SPACE-241554-CS-QCBS / Sélection du Consultant Fir me chargé (i) de la Vérificati Component 3: Strengthening Quality And Cost- Under Implement on des indicateurs Liés au Dé IDA / 66920 Post Open - National 0.00 2021-06-29 2021-08-02 2021-07-20 2021-08-09 2021-08-04 2021-09-01 2021-09-15 2021-10-13 2021-11-10 2022-11-10 Systems for Results Based Selection ation caissements, (ii) de l'audit de s Dépenses Eligibles au Progr amme (DEP) et (iii) de l'audit financier des comptes du pro jet ZR-SPACE-187612-CS-QCBS / Sélection de la firme pour la vérification des Indicateurs Li Component 3: Strengthening Quality And Cost- Open - Internationa IDA / 66920 Prior 0.00 Canceled 2020-09-10 2020-10-01 2020-11-14 2020-12-12 2021-01-11 2021-02-15 2021-03-22 2024-03-21 és aux Décaissements ( ILD) Systems for Results Based Selection l et de l'Audit externe du Progr amme des Dépenses Eligible s (EEP) et du SECOPE Page 3 ZR-SPACE-221810-CS-QCBS / Un Cabinet d'Assistance Tec Component 3: Strengthening Quality And Cost- Open - Internationa IDA / 66920 Post 0.00 Canceled 2021-03-05 2021-04-01 2021-03-19 2021-04-08 2021-04-16 2021-05-14 2021-05-28 2021-06-25 2021-07-23 2022-07-23 hnique pour le suivi par des t Systems for Results Based Selection l iers des autres assistances te chniques ZR-SPACE-246958-CS-CQS / Component 3: Strengthening Consultant Qualifi Under Implement ASSISTANCE TECHNIQUE PO IDA / 66920 Post Open - National 0.00 2021-08-12 2021-08-05 2021-08-26 2021-10-09 2021-10-23 2021-11-27 2022-05-26 Systems for Results cation Selection ation UR L'EVALUATION SOCIALE D U PROJET PERSE ZR-SPACE-296511-CS-QCBS / Recrutement d'un Consulta nt cabinet en soutien de la C Component 1: Enabling Free Quality And Cost- Open - Internationa Pending Impleme omposante 1 (LDs2&3), de la IDA / 66920 Prior 0.00 2022-06-06 2022-06-27 2022-08-10 2022-09-07 2022-10-07 2022-11-11 2022-12-16 2023-12-16 Access for All Based Selection l ntation Composante 2 5ILDs 6&7) et de la Composante 3.1 (Elabo ration et contrôle du budget ) pour le Projet PERSE ZR-SPACE-296505-CS-CQS / Recrutement d'un Consultant Cabinet chargé d'Assistance Technique en soutien à la for Component 3: Strengthening Consultant Qualifi Under Implement mation des COGES, à la Com IDA / 66920 Prior Limited 0.00 2022-06-02 2022-07-25 2022-06-16 2022-07-16 2022-08-20 2023-02-16 Systems for Results cation Selection ation posante3.2 (Engagement des Citoyens et Mécanisme de G estion des Plaintes) et de la Composante 3.1 (Elaboration et contrôle du budget) ZR-SPACE-305078-CS-QCBS / Recrutement d'un consultan t Cabinet d'Assistance Techni que chargé d'appuyer, dans l Component 3: Strengthening Quality And Cost- Under Implement IDA / 66920 Prior Open - National 0.00 2022-08-05 2022-08-26 2022-10-09 2022-11-06 2022-12-06 2023-01-10 2023-02-14 2024-02-14 e cadre du projet PERSE, la r Systems for Results Based Selection ation ationalisation des écoles, bur eaux gestionnaires et service s du MEPST ainsi que du proc essus de leur création ZR-SPACE-305103-CS-QCBS / Recrutement d'un Consulta nt Cabinet d'Assistance Tech nique chargé d'appuyer le M Component 3: Strengthening Quality And Cost- Under Implement IDA / 66920 Prior Open - National 0.00 2022-08-08 2022-08-29 2022-10-12 2022-11-09 2022-12-09 2023-01-13 2023-02-17 2024-02-17 EPST dans la mise en place d Systems for Results Based Selection ation 'un nouveau système de recr utement, transparent, objecti f et basé sur l'équité, d'ensei gnants et Directeurs d'école primaire ZR-SPACE-307961-CS-QCBS / RECRUTEMENT D'UN CABIN Component 3: Strengthening Quality And Cost- Under Implement ET D'AUDIT COMPTABLE ET F IDA / 66920 Post Open - National 0.00 2022-09-05 2022-12-15 2022-09-26 2022-11-09 2022-12-07 2023-01-06 2023-02-10 2023-03-17 2024-03-16 Systems for Results Based Selection ation INANCIER DU PERSE, EXERCI CES 2022,2023 ET 2024 ZR-SPACE-326745-CS-CQS / RECRUTEMENT D’UN CONSU LTANT (FIRME) CHARGE (I) D E L’ELABORATION DU RAPPO Component 3: Strengthening Consultant Qualifi Under Implement IDA / 66920 Post Open - National 0.00 2022-11-21 2023-02-14 2022-12-12 2023-01-25 2023-02-24 2023-03-31 2023-09-27 RT DE CERTIFICATION DE L’A Systems for Results cation Selection ation TTEINTE DE L’INDICATEUR LI E AU DECAISSEMENT (ILD) ET (II) DE L’AUDIT DES DEPENSE S ELIGIBLES AU PROGRAMME (DEP) ZR-SPACE-359741-CS-QCBS / RECRUTEMENT D'UN CONS ULTANT (FIRME) CHARGE (I) DE L'ELABORATION DU RAPP Component 3: Strengthening Quality And Cost- Pending Impleme IDA / 66920 Post Open - National 0.00 2023-05-08 2023-05-29 2023-07-12 2023-08-09 2023-09-08 2023-10-13 2023-11-17 2024-11-16 ORT DE CERTIFICATION DE L' Systems for Results Based Selection ntation ATTEINTE DE L'INDICATEUR L IE AU DECAISSEMENT (ILD) E T (II) DE L'AUDIT DES DEPEN SES ELIGIBLES AU PROGRAM ME (DEP) ZR-SPACE-359742-CS-QCBS / Sélection du Prestataire Tier s chargé du suivi des activité Component 3: Strengthening Quality And Cost- IDA / 66920 Post Open - National 0.00 Under Review 2023-05-15 2023-06-05 2023-06-05 2023-07-19 2023-08-16 2023-09-15 2023-10-20 2023-11-24 2024-11-23 s de renforcement des capaci Systems for Results Based Selection tés dans le cadre de la mise en oeuvre du projet PERSE INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Actual Amount Invitation to Identifie Draft Negotiated Cont Component Review Type Method Contract Type Process Status Teams of Reference Signed Contract Contract Completion Description o. h (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ZR-SPACE-187600-CS-INDV / Component 3: Strengthening Individual Consult Under Implement Sélection des consultants ( 2) IDA / 66920 Post Open 0.00 2020-09-07 2020-09-28 2020-10-26 2021-08-11 2020-11-16 2021-08-16 2020-12-21 2022-12-11 Systems for Results ant Selection ation chargés du suivi de l'engage ment citoyen ZR-SPACE-187601-CS-INDV / Sélection des consultants nat ionaux ( 10) au niveau provin Component 3: Strengthening Individual Consult Under Implement IDA / 66920 Post Open 0.00 2020-09-15 2020-09-17 2020-11-03 2020-11-24 2020-12-29 2022-12-19 cial pour la supervision, le so Systems for Results ant Selection ation utien et le suivi des reformes du projet : plusieurs petits m archés ZR-SPACE-187573-CS-INDV / Sélection du spécialiste resp Component 3: Strengthening Individual Consult onsable pour appuyer le renf IDA / 66920 Post Open 0.00 Signed 2020-09-10 2020-09-28 2020-10-29 2021-08-11 2020-11-19 2021-08-16 2020-12-24 2022-12-14 Systems for Results ant Selection orcement des réseaux d'écol es et Bureaux gestionnaires ZR-SPACE-187592-CS-INDV / Component 3: Strengthening Individual Consult Sélection du Spécialiste char IDA / 66920 Post Open 0.00 Signed 2020-09-14 2020-09-28 2020-11-02 2021-06-23 2020-11-23 2021-08-15 2020-12-28 2022-12-18 Systems for Results ant Selection gé du suivi-évaluation du pro jet ZR-SPACE-187590-CS-INDV / Component 3: Strengthening Individual Consult Under Implement Sélection du Spécialiste en s IDA / 66920 Post Open 0.00 2020-09-15 2020-09-30 2020-11-03 2020-11-24 2020-12-29 2022-12-19 Systems for Results ant Selection ation auvegardes sociales ZR-SPACE-187548-CS-INDV / Component 3: Strengthening Individual Consult Sélection du Coordonnateur IDA / 66920 Post Open 0.00 Signed 2020-09-14 2020-09-17 2020-11-02 2021-06-07 2020-11-16 2021-08-12 2020-12-14 2022-12-04 Systems for Results ant Selection adjoint du projet PERSE ZR-SPACE-187555-CS-INDV / Sélection d'un Consultant int Component 3: Strengthening Individual Consult Under Implement ernational pour appuyer les s IDA / 66920 Post Open 0.00 2020-09-10 2020-09-28 2020-10-29 2020-11-12 2020-12-17 2021-02-27 Systems for Results ant Selection ation ystèmes d'information et de paiement des salaires Page 4 ZR-SPACE-187561-CS-INDV / Sélection du spécialiste resp Component 3: Strengthening Individual Consult Under Implement IDA / 66920 Post Open 0.00 2020-09-13 2021-02-05 2020-11-01 2020-11-22 2020-12-27 2022-12-17 onsable pour le recrutement Systems for Results ant Selection ation basé sur le mérite ZR-SPACE-187576-CS-INDV / Sélection d'un Consultant int Component 3: Strengthening Individual Consult Pending Impleme IDA / 66920 Post Open 0.00 2020-09-17 2020-11-05 2020-11-19 2020-12-24 2022-12-14 ernational pour la gestion fin Systems for Results ant Selection ntation ancière du projet ZR-SPACE-187579-CS-INDV / Sélection du Consultant natio Component 3: Strengthening Individual Consult Under Implement IDA / 66920 Post Open 0.00 2020-09-15 2020-09-15 2020-11-03 2020-11-24 2020-12-29 2022-12-19 nal spécialiste en gestion fin Systems for Results ant Selection ation ancière du projet ZR-SPACE-187580-CS-INDV / Component 3: Strengthening Individual Consult Under Implement Sélection du Spécialiste en P IDA / 66920 Post Open 0.00 2020-09-10 2021-01-26 2020-10-29 2020-11-12 2020-12-17 2022-12-07 Systems for Results ant Selection ation assation des marchés ZR-SPACE-187582-CS-INDV / Component 3: Strengthening Individual Consult Sélection du Spécialiste char IDA / 66920 Post Open 0.00 Signed 2020-09-15 2020-09-28 2020-11-03 2021-08-11 2020-11-24 2021-08-16 2020-12-29 2022-12-19 Systems for Results ant Selection gé des sauvegardes environn ementales ZR-SPACE-187575-CS-INDV / Sélection du spécialiste resp Component 3: Strengthening Individual Consult IDA / 66920 Post Open 0.00 Signed 2020-09-14 2020-12-17 2020-11-02 2022-08-11 2020-11-23 2021-08-16 2020-12-28 2022-12-18 onsable pour appuyer la gest Systems for Results ant Selection ion des finances publiques ZR-SPACE-187620-CS-CDS / Component 3: Strengthening Sélection du Coordonnateur IDA / 66920 Post Direct Selection Direct 7,500.00 Signed 2020-09-10 2020-10-16 2020-09-20 2021-01-03 2020-11-01 2021-01-09 2022-10-22 Systems for Results du Projet : Prof Valère MUNS YA ZR-SPACE-209760-CS-CDS / Component 3: Strengthening Sélection chargée de Passati IDA / 66920 Post Direct Selection Direct 7,500.00 Signed 2020-12-14 2021-02-10 2020-12-18 2020-12-30 2020-12-29 2021-01-06 2021-06-27 Systems for Results on des Marchés : Fleur SHWE KA ZR-SPACE-216049-CS-CDS / Sélection du Consultant Spéc Component 3: Strengthening IDA / 66920 Post Direct Selection Direct 27,000.00 Signed 2021-01-26 2021-02-10 2021-02-05 2020-12-30 2021-02-26 2021-01-06 2021-08-25 ialiste en Communication de Systems for Results l'ECP PERSE: Mme BIBICHE M ODJAKA ZR-SPACE-216061-CS-CDS / Component 3: Strengthening Sélection du Spécialiste en V IDA / 66920 Post Direct Selection Direct 36,000.00 Signed 2021-01-26 2021-02-10 2021-02-05 2020-12-30 2021-03-05 2021-01-06 2021-09-01 Systems for Results BG : Jeanine Gabrielle NGUN GU ZR-SPACE-221812-CS-CDS / Sélection du Consultant Princ ipal ( avec son équipe de 4 e Component 3: Strengthening xperts) pour la conduite des IDA / 66920 Post Direct Selection Direct 93,500.00 Completed 2021-03-08 2021-03-10 2021-03-18 2021-03-15 2021-04-08 2021-03-30 2021-07-07 2021-10-15 Systems for Results opérations de géolocalisation des écoles primaires dans le cadre du PERSE : Roger VIBIL A ZR-SPACE-221817-CS-INDV / Component 3: Strengthening Individual Consult Under Implement Assistant ponctuel logisticien IDA / 66920 Post Direct 0.00 2021-02-25 2021-02-26 2021-03-07 2021-03-12 2021-03-22 2021-06-20 Systems for Results ant Selection ation : ARLY MANGELELE BOKOMB E ZR-SPACE-223393-CS-INDV / Consultant Architecte chargé de mener les études pour la r Component 3: Strengthening Individual Consult Under Implement IDA / 66920 Post Limited 0.00 2021-03-10 2021-01-20 2021-03-15 2021-04-05 2021-05-03 2021-08-01 éhabilitation des bureaux du Systems for Results ant Selection ation SPACE qui serviront des bure aux définitifs pour le projet P ERSE ZR-SPACE-223394-CS-INDV / Component 3: Strengthening Individual Consult Under Implement Sélection du Comptable pour IDA / 66920 Post Open 0.00 2021-03-10 2021-03-23 2021-04-28 2021-05-19 2021-06-23 2021-12-20 Systems for Results ant Selection ation le projet PERSE ZR-SPACE-221823-CS-CDS / Recrutement du Prestataire p Component 3: Strengthening IDA / 66920 Post Direct Selection Direct 830,726.00 Signed 2021-03-21 2021-03-03 2021-03-31 2021-03-25 2021-04-29 2021-07-08 2021-10-26 our le Développement de l'ap Systems for Results plication ALLO ECOLE : INFOS ET ZR-SPACE-231137-CS-INDV / RENOUVELLEMENT CONTRAT Component 3: Strengthening Individual Consult CHARGEE DE PASSATION DE IDA / 66920 Post Direct 0.00 Signed 2021-04-22 2021-03-20 2021-05-02 2021-03-26 2021-05-23 2021-03-30 2021-06-27 2022-06-27 Systems for Results ant Selection S MARCHES MADAME FLEUR SHWEKA (12 MOIS) ZR-SPACE-234473-CS-INDV / Sélection du Consultant char gé de l'élaboration du Plan d Component 3: Strengthening Individual Consult Under Implement e Gestion Environnemental e IDA / 66920 Post Limited 0.00 2021-06-30 2021-08-05 2021-07-05 2021-07-19 2021-08-09 2021-10-08 Systems for Results ant Selection ation t Social Générique (PGES) po ur le projet PERSE ( Le volet Social étant prépondérant da ns le cadre de ce marché) ZR-SPACE-241555-CS-INDV / Renouvellement du Contrat d Component 3: Strengthening Individual Consult Under Implement IDA / 66920 Post Direct 0.00 2021-06-27 2021-05-27 2021-07-07 2021-07-14 2021-07-28 2022-07-28 e la Chargée de logistique- A Systems for Results ant Selection ation RLLY MANGELELE ( pour 12 mois) ZR-SPACE-187591-CS-INDV / Sélection du Spécialiste dans Component 3: Strengthening Individual Consult IDA / 66920 Post Open 0.00 Canceled 2020-09-09 2020-10-28 2020-11-18 2020-12-23 2022-12-13 la gestion des Violences Basé Systems for Results ant Selection es sur le Genre ( VBG) ZR-SPACE-248688-CS-INDV / Component 3: Strengthening Individual Consult Under Implement Sélection spécialiste en plani IDA / 66920 Post Open 0.00 2021-08-17 2020-09-17 2021-10-05 2021-10-26 2021-11-30 2022-11-30 Systems for Results ant Selection ation fication et vérification du proj et PERSE ZR-SPACE-248700-CS-INDV / Component 3: Strengthening Individual Consult Sélection Expert en communi IDA / 66920 Post Open 0.00 Signed 2021-08-17 2021-08-17 2021-10-05 2021-07-23 2021-10-26 2021-07-23 2021-11-30 2022-05-29 Systems for Results ant Selection cation Projet PERSE ZR-SPACE-249050-CS-INDV / Sélection d'un Spécialiste de Component 3: Strengthening Individual Consult Under Implement IDA / 66920 Post Limited 0.00 2021-09-14 2020-11-26 2021-09-19 2021-10-03 2021-10-24 2022-10-24 s Systèmes d’information de Systems for Results ant Selection ation gestion de l’éducation et du paiement (SIGEP) Page 5 ZR-SPACE-241557-CS-CDS / Sélection du Prestataire Tiers chargé du suivi des activités Component 3: Strengthening Pending Impleme IDA / 66920 Post Direct Selection Direct 0.00 2021-09-14 2021-09-24 2021-11-12 2022-11-12 de renforcement des capacit Systems for Results ntation és dans le cadre de la mise e n oeuvre du projet PERSE : O NG CORDAID ZR-SPACE-231135-CS-INDV / RENOUVELLEMENT CONTRAT Component 3: Strengthening Individual Consult Under Implement SPECIALISTE EN VIOLENCES IDA / 66920 Post Direct 0.00 2021-06-30 2021-03-01 2021-07-10 2021-07-31 2021-09-04 2023-08-25 Systems for Results ant Selection ation BASEES SUR LE GENRE : MA DAME JEANINE NGUNGU KWA TE (12 MOIS) ZR-SPACE-261331-CS-INDV / Component 3: Strengthening Individual Consult Under Implement SELECTION CAISSIER(RE) PO IDA / 66920 Post Open 0.00 2021-11-03 2022-02-10 2021-12-22 2022-01-12 2022-02-16 2022-08-15 Systems for Results ant Selection ation UR LE PROJET PERSE ZR-SPACE-261334-CS-INDV / Component 3: Strengthening Individual Consult Under Implement SELECTION D'UN(E) ASSISTA IDA / 66920 Post Open 0.00 2021-11-03 2022-02-10 2021-12-22 2022-01-12 2022-02-16 2022-08-15 Systems for Results ant Selection ation NT(E) ADMINISTRATIF POUR L E PROJET PERSE ZR-SPACE-261338-CS-INDV / SELECTION D'UN(E) ASSISTA Component 3: Strengthening Individual Consult Under Implement IDA / 66920 Post Open 0.00 2021-11-03 2022-02-10 2021-12-22 2022-01-12 2022-02-16 2022-08-15 NT(E) AU PROGRAMME POUR Systems for Results ant Selection ation LE PROJET PERSE ZR-SPACE-262236-CS-INDV / SELECTION DES CHAUFFEUR Component 3: Strengthening Individual Consult Under Implement IDA / 66920 Post Limited 0.00 2021-11-16 2022-02-10 2021-11-21 2021-12-12 2022-01-16 2022-07-15 S POUR LE PROJET PERSE A K Systems for Results ant Selection ation INSHASA (5 CONTRATS POUR 12 MOIS) ZR-SPACE-272626-CS-INDV / RECRUTEMENT D'UN CONSUL Component 3: Strengthening Individual Consult Pending Impleme TANT INDIVIDUEL EN QUALIT IDA / 66920 Post Open 0.00 2022-01-11 2022-03-01 2022-03-22 2022-04-26 2022-10-23 Systems for Results ant Selection ntation E DE SUPERVISEUR PROVINCI AL BASE A KINSHASA ZR-SPACE-262238-CS-INDV / SELECTION DES ASSISTANTS Component 3: Strengthening Individual Consult Under Implement ADMINISTRATIFS ET FINANCI IDA / 66920 Post Open 0.00 2021-11-16 2022-03-09 2022-01-04 2022-01-25 2022-03-01 2022-08-28 Systems for Results ant Selection ation ERS (10 CONTRATS) POUR LE PROJET PERSE EN PROVINCE (12 MOIS) ZR-SPACE-284618-CS-CDS / CONTRACTUALISATION AVEC LE CABINET PriceWatherHous eCoopers POUR LA VERIFICA TION DES INDICATEURS LIES Component 3: Strengthening Under Implement IDA / 66920 Prior Direct Selection Direct 0.00 2022-03-15 2022-03-18 2022-03-25 2022-03-19 2022-05-29 2022-11-25 AUX DECAISSEMENTS (ILD) E Systems for Results ation T L'AUDIT DES DEPENSES ELI GIBLES AU PROGRAMME (DE P) DANS LES PROVINCES DU KWILU, KONGO CENTRAL, KI NSHASA, LOMAMI, KASAÏ ORI ENTAL ZR-SPACE-284619-CS-CDS / CONTRACTUALISATION AVEC LE CABINET MGI STRONG NK V POUR L'AUDIT FINANCIER Component 3: Strengthening Under Implement DES COMPTES DU PROJET PO IDA / 66920 Post Direct Selection Direct 0.00 2022-03-15 2022-03-18 2022-03-25 2022-03-21 2022-05-29 2022-11-25 Systems for Results ation UR LES 3 EXERCICES SUIVAN TS: (1) JUIN 2020 AU 31 DEC EMBRE 2020; (2) 01 JANVIER 2021 AU 31 DECEMBRE 2021 ; (3) 01 JANVIER 22 AU 31 DE CEMBRE 2022 ZR-SPACE-284617-CS-CDS / CONTRACTUALISATION AVEC LE CABINET COFIMA POUR LA VERIFICATION DES INDICATE Component 3: Strengthening Under Implement URS LIES AUX DECAISSEMEN IDA / 66920 Prior Direct Selection Direct 0.00 2022-03-15 2022-03-18 2022-03-25 2022-03-19 2022-05-29 2022-11-25 Systems for Results ation TS (ILD) ET L'AUDIT DES DEP ENSES ELIGIBLES AU PROGR AMME (DEP) DANS LES PROVI NCES DU NORD-KIVU, SUD-KI VU, ITURI, KASAÏ, kASAÏ CENT RAL ZR-SPACE-286586-CS-CDS / RENOUVELLEMENT CONTRAT Component 3: Strengthening Under Implement CHARGEE DE PASSATION DE IDA / 66920 Post Direct Selection Direct 0.00 2022-05-20 2022-03-28 2022-05-30 2022-08-03 2023-01-30 Systems for Results ation S MARCHES DU PROJET PERS E MADAME FLEUR SHWEKA ( 12 MOIS) ZR-SPACE-295474-CS-INDV / Recrutement d'un Consultant individuel pour l'accompagne ment de la cellule du Projet d Component 3: Strengthening Individual Consult Under Implement ans l'évaluation et coordinati IDA / 66920 Post Limited 0.00 2022-05-20 2022-07-20 2022-05-25 2022-06-15 2022-07-20 2023-01-16 Systems for Results ant Selection ation on des travaux réalisés par le s cabinets chargés de l'audit des Dépenses DEP et du cont rôle des indicateurs de réalis ation ILD/RLD ZR-SPACE-300402-CS-INDV / RECRUTEMENT D'UN ASSIST Component 3: Strengthening Individual Consult Under Implement IDA / 66920 Post Limited 0.00 2022-09-09 2022-08-31 2022-09-14 2022-10-05 2022-11-09 2023-05-08 ANT TECHNIQUE PROVINCIAL Systems for Results ant Selection ation BASE A KINSHASA ZR-SPACE-303555-CS-CDS / CONSULTANT PONCTUEL PO Component 3: Strengthening Under Implement UR UN APPUI TECHNIIQUE A L IDA / 66920 Post Direct Selection Direct - National 0.00 2022-08-11 2022-07-29 2022-08-21 2022-10-25 2023-04-23 Systems for Results ation A PASSATION DES MARCHES DU PROJET PERSE ( Mr LAURE NT TSHIMBIYE) ZR-SPACE-304959-CS-CDS / Renouvellement du contrat d Component 3: Strengthening Under Implement IDA / 66920 Post Direct Selection Direct - National 0.00 2022-07-19 2022-07-28 2022-07-29 2022-10-02 2023-03-31 e la chargée de la logistique Systems for Results ation (Madame Arlly MANGELELE) pour 12 mois ZR-SPACE-304955-CS-INDV / Recrutement de 10 chauffeur Component 3: Strengthening Individual Consult Pending Impleme IDA / 66920 Post Limited 0.00 2022-07-19 2022-07-24 2022-08-14 2022-09-18 2023-03-17 s pour les véhicules des ante Systems for Results ant Selection ntation nnes provinciales du Projet ZR-SPACE-300117-CS-INDV / Component 3: Strengthening Individual Consult Under Implement RECRUTEMENT DU SPECIALIS IDA / 66920 Post Limited 0.00 2022-08-26 2022-09-13 2022-08-31 2022-09-21 2022-10-26 2023-04-24 Systems for Results ant Selection ation TE PROVINCIAL POUR LE NOR D-KIVU Page 6 ZR-SPACE-314053-CS-INDV / RECRUTEMENT D’UN(E) ASSI STANT(E) SPECIALISTE EN VI Component 3: Strengthening Individual Consult Under Implement IDA / 66920 Post Limited 0.00 2022-09-19 2022-12-20 2022-09-24 2022-10-15 2022-11-19 2023-05-18 OLENCES BASEES SUR LE GE Systems for Results ant Selection ation NRE AU SEIN DE L’EQUIPE DE CO ORDINATION DU PROJET ZR-SPACE-326740-CS-CDS / CONTRACTUALISATION AVEC LE CABINET PWC POUR LA MI SSION D'AUDIT DES DEPENS Component 3: Strengthening Pending Impleme ES ELIGIBLES AU PROGRAMM IDA / 66920 Post Direct Selection Direct - National 0.00 2022-11-21 2022-12-01 2023-02-04 2023-08-03 Systems for Results ntation E (DEP) POUR LA PERIODE A LLANT DU 1ER JANVIER AU 3 1 DECEMBRE 2022 ET VERIFI CATION DE L'INDICATEUR LIE AU DECAISSEMENT (ILD 5.2) ZR-SPACE-326743-CS-CDS / CONTRACTUALISATION AVEC LE CABINET COFIMA POUR LA MISSION D'AUDIT DES DEPE Component 3: Strengthening Pending Impleme NSES ELIGIBLES AU PROGRA IDA / 66920 Post Direct Selection Direct - National 0.00 2022-11-21 2022-12-01 2023-02-04 2023-08-03 Systems for Results ntation MME (DEP) POUR LA PERIOD E ALLANT DU 1ER JANVIER A U 31 DECEMBRE 2022 ET VE RIFICATION DE L'INDICATEUR LIE AU DECAISSEMENT (ILD 5 .2) ZR-SPACE-327666-CS-INDV / RECRUTEMENT D'UN ASSIST Component 3: Strengthening Individual Consult Under Implement IDA / 66920 Post Limited 0.00 2022-11-28 2022-12-20 2022-12-03 2022-12-24 2023-01-28 2023-07-27 ANT ADMINISTRATIF ET FINA Systems for Results ant Selection ation NCIER POUR LE KONGO CENT RAL ZR-SPACE-336148-CS-INDV / Component 3: Strengthening Individual Consult Under Implement RECRUTEMENT DU COORDO IDA / 66920 Post Open - National 0.00 2023-02-01 2023-02-22 2023-03-22 2023-04-12 2023-05-17 2023-11-13 Systems for Results ant Selection ation NNATEUR ADJOINT DU PERSE ZR-SPACE-343004-CS-CDS / CONTRACTUALISATION AVEC Component 3: Strengthening Pending Impleme IDA / 66920 Post Direct Selection Direct - National 0.00 2023-02-28 2023-03-10 2023-05-14 2023-11-10 LA FIRME INFOSET POUR L'E Systems for Results ntation XTENSION DU CENTRE D'APP EL ALLO-ECOLE Page 7 PROCUREMENT PLAN (Textual Part) Project information: Sao Tome and Principe - WACA Resilience Investment Project - P162337 Project Implementation agency: Ministry of Public Works and Natural Resources, Directorate General of Environment Date of the Procurement Plan: July 2017 Period covered by this Procurement Plan: July 1st 2017 to June 30th, 2018 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in Regulamento de Licitação e Contratações Publicas such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables: Not Applicable Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables: Not Applicable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: is not applicable for those contracts identified in the Procurement Plan tables; Works: is not applicable for those contracts identified in the Procurement Plan tables Other Relevant Procurement Information.: Not Applicable PROCUREMENT Western and Central Africa : West Africa Coastal Areas Resilience Investment Project PLAN General Information Country: Western and Central Africa 2018-02-19 Bank’s Approval Date of the Original Procurement Plan: 2023-06-06 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P162337 GPN Date: 2017-12-29 Project Name: West Africa Coastal Areas Resilience Investment Project Loan / Credit No: IDA / V1150, IDA / D2860, IDA / 62130, TF / A7130, TF / A7131 Ministry of Environnement/Directorate of Environment Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned 39 / Aménagement de burea Component 4: National Coor Single Stage - One E 2019-02-2 ux pour l’unité de gestion du IDA / V1150 Post Request for Bids Open - National 90,000.00 81,133.59 Terminated 2018-05-07 2018-04-06 2018-05-12 2018-06-23 2018-05-07 2018-07-23 2018-05-26 2018-08-27 2018-08-29 dination nvelope 3 projet WACA 59 / Travaux d'aménagemen t du R+1 des bureaux pour l' UGP, Construction du mur de séparation, d'un parking pour Component 4: National Coor Single Stage - One E 2020-04-1 IDA / D2860 Post Request for Bids Open - National 190,000.00 0.00 Canceled 2019-06-27 2019-07-02 2019-08-13 2019-09-12 2019-10-17 10 voitures, un poste d'héber dination nvelope 4 gement (des compteurs et d u groupe électrogène) et am énagement de la cour (aires de circulation et jardin) 85 / Travaux d’aménagemen t de la cour du Ministère de l' Component 2: Strengthening Request for Quota Single Stage - One E 2021-01-1 environnement, du développ IDA / D2860 the Policy and Institutional F Post Limited 105,000.00 126,079.40 Signed 2020-05-19 2020-04-24 2020-07-14 2020-08-29 tions nvelope 0 ement durable et de la prote ramework ction de la nature - en un (01 ) lot 114 / Travaux de constructio n de la clôture de la direction Component 4: National Coor Request for Quota Single Stage - One E 2020-12-0 IDA / D2860 Post Open - National 70,000.00 55,047.27 Signed 2020-07-14 2020-09-08 2022-02-19 régionale des forestiers de la dination tions nvelope 8 réserve de Togodo Nord à AT AKPAME 88 / Travaux d'aménagemen Component 4: National Coor Request for Quota Single Stage - One E 2021-03-0 t du R+1 des bureaux pour l' IDA / D2860 Post Limited 152,728.00 0.00 Signed 2020-07-12 2020-07-16 2020-09-06 dination tions nvelope 5 UGP WACA ResIP, en lot uniq ue 104 / Travaux de protection Component 3: Strengthening d’urgence de la côte par la te 2021-02-1 IDA / D2860 National Physical and Social Post Direct Selection Direct 909,090.90 899,211.65 Signed 2020-07-08 2020-07-03 2020-07-13 2020-08-19 2020-08-17 2020-09-18 chnique de juxtaposition de p 3 Investments uits en fûs granulitique. TG-WACA TOGO-204668-CW Component 3: Strengthening Request for Quota Single Stage - One E 2021-04-1 -RFQ / Construction de deux ( TF / A7131 National Physical and Social Post Limited 30,000.00 0.00 Canceled 2021-01-20 2021-03-18 tions nvelope 7 02) bâtiments à TOGODO Investments TG-WACA TOGO-204671-CW Component 3: Strengthening -RFQ / Travaux de constructi Request for Quota Single Stage - One E 2021-09-1 TF / A7130 National Physical and Social Post Limited 60,000.00 0.00 Canceled 2021-01-25 2021-03-22 on de deux (02) étangs et de tions nvelope 8 Investments deux (02) forages à TOGODO 92 / Travaux de construction Component 2: Strengthening Request for Quota Single Stage - One E 2021-02-2 IDA / D2860 Post Limited 106,000.00 0.00 Canceled 2020-07-01 2020-08-26 du siège de l'ANGE the Policy and Institutional F tions nvelope 2 ramework TG-WACA TOGO-239069-CW National Procure -RFQ / Travaux d'aménagem Component 2: Strengthening ment Document - ent (réhabilitation) de la salle Request for Quota Single Stage - One E 2022-02-1 IDA / D2860 the Policy and Institutional F Post Limited 1 Envelope proce 30,000.00 0.00 Signed 2021-09-20 2022-04-26 2021-11-15 de vidéo conférence du progr tions nvelope 3 ramework ss (Non Bank-SPD amme de licence en océano ) graphie de l'université de Kar a TG-WACA TOGO-239044-CW National Procure -RFB / TRAVAUX DE CONSTR Component 3: Strengthening ment Document - Single Stage - One E 2022-07-2 UCTION DES UNITES DE TRA IDA / D2860 National Physical and Social Post Request for Bids Open - National 1 Envelope proce 937,389.00 653,009.74 Signed 2021-10-15 2021-08-09 2021-10-20 2021-11-19 2021-11-02 2021-12-19 2021-11-13 2022-01-23 2022-03-29 nvelope 2 NSFORMATIONS DANS LES A Investments ss (Non Bank-SPD GR PILOTES EN SEPT (07) LO ) TS TG-WACA TOGO-255574-CW -RFB / TRAVAUX DE CONSTR UCTION ET DE REHABILITATI National Procure ON DE CABINES DE TOILETT Component 3: Strengthening ment Document - Single Stage - One E 2022-06-0 ES EQUIPES DE DISPOSITIFS IDA / D2860 National Physical and Social Post Request for Bids Open - National 1 Envelope proce 177,273.00 192,765.13 Signed 2021-10-29 2021-08-09 2021-11-03 2021-12-03 2021-11-03 2022-01-02 2021-11-14 2022-02-06 2022-05-07 nvelope 6 DE LAVE-MAIN DANS LES EC Investments ss (Non Bank-SPD OLES, ET DE CONSTRUCTION ) DE TOILETTES ECOSAN DANS LES MENAGES DE LA COMMU NE DES LACS 1( en 04 lots) TG-WACA TOGO-222964-CW National Procure -RFQ / renforcement (travaux Component 3: Strengthening ment Document - Request for Quota Single Stage - One E 2022-07-2 de réhabilitation) du poste se IDA / D2860 National Physical and Social Post Open - National 1 Envelope proce 109,000.00 0.00 Canceled 2021-11-02 2022-01-25 tions nvelope 4 cours d'urgence (PSR) du cor Investments ss (Non Bank-SPD ps des sapeurs - pompiers de ) la Région de Lomé Nord TG-WACA TOGO-239057-CW National Procure -RFB / construction de trois ( Component 2: Strengthening ment Document - 03) postes de relais forestier Single Stage - One E 2022-06-0 TF / A7130 the Policy and Institutional F Post Request for Bids Open - National 1 Envelope proce 90,000.00 0.00 Canceled 2021-10-25 2021-10-30 2021-11-29 2021-12-29 2022-02-02 s équipés de panneaux solair nvelope 2 ramework ss (Non Bank-SPD es et de forages à motricité h ) umaine dans le complexe d’a ires protégées de Togodo. Request for Bids - TG-WACA TOGO-239048-CW Component 2: Strengthening Single Stage - One E Small Works SPD 2022-07-0 -RFB / Réhabilitation de la br TF / A7130 the Policy and Institutional F Post Request for Bids Open - National 100,000.00 0.00 Canceled 2021-10-29 2021-11-03 2021-12-03 2022-01-02 2022-02-06 nvelope (1 envelope proce 6 igade de Togodo Nord ramework ss) National Procure TG-WACA TOGO-255877-CW Component 3: Strengthening ment Document - Request for Quota Single Stage - One E 2022-07-2 -RFQ / Réhabilitation de la bri TF / A7130 National Physical and Social Post Limited 1 Envelope proce 100,000.00 105,469.51 Signed 2021-12-05 2021-11-10 2022-01-30 2022-04-16 tions nvelope 9 gade de Togodo Nord Investments ss (Non Bank-SPD ) TG-WACA TOGO-255863-CW National Procure -RFQ / renforcement (travaux Component 3: Strengthening ment Document - Request for Quota Single Stage - One E 2022-05-1 de réhabilitation) du poste se IDA / D2860 National Physical and Social Post Limited 1 Envelope proce 109,000.00 93,880.49 Signed 2021-11-20 2021-11-10 2022-01-15 2022-04-16 tions nvelope 5 cours d'urgence (PSR) du cor Investments ss (Non Bank-SPD ps des sapeurs - pompiers de ) la Région de Lomé Nord Page 1 TG-WACA TOGO-255873-CW National Procure -RFQ / construction de trois ( Component 3: Strengthening ment Document - Request for Quota Single Stage - One E Under Imple 2022-07-1 03) postes de relais forestier TF / A7130 National Physical and Social Post Limited 1 Envelope proce 90,000.00 0.00 2021-11-24 2022-04-14 2022-01-19 tions nvelope mentation 8 s équipés de panneaux solair Investments ss (Non Bank-SPD es dans le complexe d’aires ) protégées de Togodo. TG-WACA TOGO-238677-CW National Procure -RFB / Construction de toilett Component 3: Strengthening ment Document - Single Stage - One E 2022-03-1 e dans les ménages (12 lots) IDA / D2860 National Physical and Social Post Request for Bids Open - National 1 Envelope proce 177,273.00 0.00 Canceled 2021-08-03 2021-08-08 2021-09-07 2021-10-07 2021-11-11 nvelope 1 et dans les écoles en six (06) Investments ss (Non Bank-SPD lots soit en 18 lots au total ) TG-WACA TOGO-204666-CW Component 3: Strengthening Single Stage - One E 2021-08-1 -RFB / Réhabilitation de 90 k TF / A7130 National Physical and Social Post Request for Bids Open - National 210,606.00 0.00 Canceled 2021-01-06 2021-01-11 2021-02-10 2021-03-12 2021-04-16 nvelope 4 m de piste, 7 ponceaux et 15 Investments radiers à Togodo National Procure TG-WACA TOGO-276081-CW ment Document - Component 4: National Coor Request for Quota Single Stage - One E Under Imple 2023-03-0 -RFQ / Aménagement de la c IDA / D2860 Post Limited 1 Envelope proce 54,546.00 0.00 2022-07-11 2022-07-18 2022-09-05 dination tions nvelope mentation 4 our et d'un parking de l'UGP ss (Non Bank-SPD WACA ResIP ) TG-WACA TOGO-238692-CW National Procure -RFB / Construction de forage Component 3: Strengthening ment Document - (dans les préfectures de Yoto Single Stage - One E 2023-04-0 IDA / D2860 National Physical and Social Post Request for Bids Open - National 1 Envelope proce 231,090.00 0.00 Signed 2022-08-31 2021-08-18 2022-09-05 2022-10-05 2022-04-21 2022-11-04 2022-09-02 2022-12-09 , Bas-Mono, Lacs, Vo, Avé, Zi nvelope 8 Investments ss (Non Bank-SPD o et Golfe) pour les sous-proj ) ets communautaire en cinq ( 05) lots TG-WACA TOGO-262261-CW Component 3: Strengthening Request for Quota -RFQ / construction et équipe Request for Quota Single Stage - One E Pending Imp 2022-11-2 TF / A7130 National Physical and Social Post Limited tions (Non Bank-S 20,000.00 0.00 2022-08-29 2022-10-24 ment de trois forages dans le tions nvelope lementation 3 Investments PD) complexe forestier de Togod o TG-WACA TOGO-290356-CW -RFQ / TRAVAUX DE CURAGE Component 3: Strengthening Request for Quota Request for Quota Single Stage - One E Pending Imp 2023-05-2 DE LA MARE A TOMETY KOND TF / A7130 National Physical and Social Post Limited tions (Non Bank-S 128,000.00 0.00 2022-10-05 2022-11-30 tions nvelope lementation 9 JI ET DE CONSTRUCTION DE Investments PD) DEUX 02 ETANGS DANS LA F ORET TG-WACA TOGO-290370-CW Request for Quota Component 4: National Coor Request for Quota Single Stage - One E Pending Imp 2023-05-2 -RFQ / Travaux d'extension R IDA / D2860 Post Limited tions (Non Bank-S 150,000.00 0.00 2022-10-03 2022-11-28 dination tions nvelope lementation 7 +2 du Bâtiment de la Coordi PD) nation nationale TG-WACA TOGO-265124-CW Request for Bids - Component 3: Strengthening -RFB / Réhabilitation de pist Single Stage - One E Works French Civi 2023-06-1 TF / A7130 National Physical and Social Post Request for Bids Open - National 1,145,500.00 0.00 Signed 2022-08-24 2022-08-29 2022-08-29 2022-10-10 2022-09-21 2022-11-09 2022-10-07 2022-12-14 e, construction de ponceaux nvelope l Law (French) SP 2 Investments et radiers à Togodo D TG-WACA TOGO-306588-CW Component 3: Strengthening Request for Quota Request for Quota Single Stage - One E 2023-03-3 -RFQ / Construction de la Brig IDA / D2860 National Physical and Social Post Limited tions (Non Bank-S 120,000.00 0.00 Signed 2022-10-05 2022-10-11 2022-11-30 tions nvelope 0 ades Forestières de Togodo S Investments PD) ud TG-WACA TOGO-313426-CW Request for Bids - -RFB / TRAVAUX DE CURAGE Component 3: Strengthening Open - Internationa Single Stage - One E Works (without pr Under Imple 2023-04-1 MÉCANIQUE ET DE RESTAUR IDA / 62130 National Physical and Social Post Request for Bids 7,289,738.00 0.00 2022-11-30 2022-10-24 2022-12-05 2022-11-07 2023-01-16 2022-12-22 2023-02-15 2023-03-02 2023-03-23 l nvelope equalification) SP mentation 9 ATION DES ECOSYSTEMES A Investments D SSOCIES DU CHENAL DE GBA GA TG-WACA TOGO-313517-CW Component 3: Strengthening Request for Quota Request for Quota Single Stage - One E Under Imple 2023-06-2 -DIR / TRAVAUX DE RÉHABILI IDA / 62130 National Physical and Social Post Limited tions (Non Bank-S 72,000.00 0.00 2022-11-02 2022-09-27 2022-12-28 tions nvelope mentation 6 TATION DE L'EPP AGBODRAF Investments PD) O National Procure TG-WACA TOGO-276078-CW Component 2: Strengthening ment Document - Request for Quota Single Stage - One E Under Imple 2023-02-0 -RFB / construction de la dire TF / A7130 the Policy and Institutional F Post Limited 1 Envelope proce 145,455.00 0.00 2022-06-13 2022-08-08 tions nvelope mentation 4 ctions préfectorale de Vo ramework ss (Non Bank-SPD ) TG-WACA TOGO-355573-CW -RFQ / achèvement des trava Request for Quota Component 4: National Coor Request for Quota Single Stage - One E Pending Imp 2024-01-2 ux de clôture de la direction r IDA / D2860 Post Limited tions (Non Bank-S 60,000.00 0.00 2023-06-04 2023-07-30 dination tions nvelope lementation 6 égionale de l'environnement PD) et des ressources forestières plateaux TG-WACA TOGO-355341-CW Component 3: Strengthening Request for Quota -RFQ / PRÉPARATION DU SOL Request for Quota Single Stage - One E Under Imple 2023-08-2 TF / A7130 National Physical and Social Post Limited tions (Non Bank-S 150,000.00 0.00 2023-05-29 2023-07-24 ET LABOUR MÉCANIQUE POU tions nvelope mentation 3 Investments PD) R LE REBOISEMENT PAR L'OD EF ET LA MAIRIE Vo3 Request for Quota TG-WACA TOGO-364034-CW Component 3: Strengthening Request for Quota Single Stage - One E tions - Small Work Pending Imp 2023-11-2 -RFQ / ENLÈVEMENT DE FUTS IDA / 62130 National Physical and Social Post Limited 126,000.00 0.00 2023-08-05 2023-09-30 tions nvelope s (Emergency) SP lementation 9 EN BÉTON NON ARME A ADIS Investments D -Competitive SEM GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 35 / Acquisition de matériels Component 4: National Coor Request for Quota Single Stage - One E IDA / V1150 Post Limited 15,000.00 0.00 Canceled 2018-05-13 2018-07-08 2019-01-04 informatiques dination tions nvelope 37 / Acquisition du mobilier Component 4: National Coor Request for Quota Single Stage - One E IDA / V1150 Post Limited 25,000.00 23,847.22 Signed 2018-07-17 2018-09-03 2018-09-11 2018-10-25 2019-03-10 de bureau pour la coordinatio dination tions nvelope n du projet 34 / Achat de fournitures de bureau, matériels de bureau et matériels d'entretien de b ureau en 03 lots. Component 4: National Coor Request for Quota Single Stage - One E Lot 1 fournitures de bureau ( IDA / V1150 Post Limited 10,000.00 7,637.09 Signed 2018-02-03 2018-02-16 2018-03-31 2018-08-08 2018-09-27 dination tions nvelope papiers rames, bics,..) Lot 2 matériels de bureau (re liure) et Lot 3 matériels d'entretien d e bureau (gel désinfectant, ... ). 35 BIS / Acquisition de fourni tures informatiques et de ma tériels informatiques en 02 lo ts : Lot 1 fournitures informat Component 4: National Coor Request for Quota Single Stage - One E IDA / V1150 Post Limited 27,000.00 26,469.61 Signed 2018-01-09 2018-01-11 2018-03-06 2018-08-08 2018-09-02 iques (cartouches d'encre, an dination tions nvelope tivirus, disques durs) et Lot 2 matériels informatiques (or dinateurs de bureau, ordinat eurs portables, scanners ..) Page 2 41BIS / Le matériel roulant s era composé comme suit : Lo t 1: 2 pick-up 4x4 double cab Component 4: National Coor Request for Quota Single Stage - One E IDA / D2860 Post Limited 294,000.00 113,114.60 Signed 2019-04-20 2019-10-10 2019-06-15 2020-05-27 2019-12-12 ine tropicalisés pour les missi dination tions nvelope ons de terrain, Lot2: 01 stati on wagon , Lot3: 01 mini bus. 65 / Acquisition de matériel r Component 4: National Coor Request for Quota Single Stage - One E oulant (moto) pour les 7 CPD TF / A7130 Post Limited 40,000.00 0.00 Canceled 2019-07-01 2019-08-26 2020-02-22 dination tions nvelope D et le coursier de l'UGP 66 / Acquisition de GPS pour Component 4: National Coor Request for Quota Single Stage - One E les CPDD (07) et l'unité de ge TF / A7130 Post Limited 20,000.00 0.00 Signed 2019-07-02 2019-09-10 2019-08-27 2020-02-23 dination tions nvelope stion du projet (5) soit au tot al 12 GPS 58 / Acquisition de matériel et fourniture informatique po ur le projet (Ordinateur burea u +portable en poste de trav, Component 4: National Coor Request for Quota Single Stage - One E IDA / D2860 Post Limited 50,000.00 0.00 Canceled 2019-06-16 2019-08-11 2020-02-07 copieur, imprimante couleur, dination tions nvelope blanc noir, clé USB multi copi eur, disque dure, vidéo proje cteur, onduleurs, modem pou r connexion Wifi, camera... 74 / Acquisition de 2 véhicul Component 2: Strengthening Request for Quota Single Stage - One E es de terrain pour l'Agence N IDA / D2860 the Policy and Institutional F Post Limited 85,000.00 0.00 Canceled 2019-06-26 2019-08-21 2020-02-17 tions nvelope ationale de Gestion de l'Envir ramework onnement 98 / Production des supports Component 4: National Coor Request for Quota Single Stage - One E IDA / D2860 Post Open - National 36,364.00 16,660.05 Signed 2020-04-14 2020-06-09 2021-05-15 2020-12-06 de communications - un lot dination tions nvelope 83 / Acquisition de matériel et fourniture informatique, et Component 2: Strengthening matériels bureautique pour l Single Stage - One E IDA / D2860 the Policy and Institutional F Post Request for Bids Open - National 473,091.00 229,876.88 Signed 2020-06-25 2020-07-23 2020-06-30 2020-08-11 2020-09-25 2020-09-10 2020-10-26 2020-10-15 2021-04-24 2021-01-15 es CPDD, l'ANGE,Direction de nvelope ramework l'Environnement, Economie B leue et l'UGP WACA - Lot uni que 107 / Acquisition de matériel Component 2: Strengthening UN Agencies (Dire s roulants pour le Haut Conse IDA / D2860 the Policy and Institutional F Post Direct 232,727.00 0.00 Canceled 2020-06-02 2020-06-07 2020-07-12 2020-09-30 ct) il pour la Mer, l’ANGE et l’UG ramework P WACA ResIP 84BIS / Acquisition de matéri Component 2: Strengthening UN Agencies (Dire els roulants (engins TP) pour IDA / D2860 the Policy and Institutional F Post Direct 531,000.00 0.00 Canceled 2020-06-02 2020-06-07 2020-07-12 2020-11-12 ct) la Mairie d’Aného – lot uniqu ramework e 81 / Acquisition de matériels Component 2: Strengthening Request for Quota Single Stage - One E roulants pour le développem IDA / D2860 the Policy and Institutional F Post Limited 187,272.73 0.00 Canceled 2020-04-13 2020-06-08 2020-12-05 tions nvelope ent de l'économie bleue et l' ramework ANGE - 02 Lots 109 / Acquisition de trois (03 Component 4: National Coor Request for Quota Single Stage - One E ) téléphones portables pour l’ IDA / D2860 Post Limited 2,190.00 3,558.26 Signed 2020-08-16 2020-09-08 2020-10-11 2020-09-15 2020-10-27 dination tions nvelope UGP WACA ResIP 118 / Acquisition de mobilier Component 2: Strengthening Request for Quota Single Stage - One E de bureau pour l'ANGE et l'Ec IDA / D2860 the Policy and Institutional F Post Limited 36,364.00 6,936.87 Signed 2020-10-05 2021-05-18 2020-11-30 2022-02-01 2021-01-28 tions nvelope onomie Bleue ramework 120 / Acquisition de technol ogie des systèmes aériens sa Component 2: Strengthening ns pilotes (drone, logiciels, d Request for Quota Single Stage - One E IDA / D2860 the Policy and Institutional F Post Limited 70,000.00 0.00 Signed 2020-10-05 2021-06-28 2020-11-30 2021-03-01 e matériel et fourniture infor tions nvelope ramework matiques, Formations) pour l a production d'une cartograp hie 2D et 3D de gestion de la côte TG-WACA TOGO-211741-GO- Component 2: Strengthening UN / Acquisition de matériel r UN Agencies (Dire IDA / D2860 the Policy and Institutional F Post Direct 836,049.00 1,310,421.00 Signed 2020-10-15 2020-06-02 2020-10-16 2020-11-25 2020-11-22 2020-12-12 2021-02-20 oulant pour la coordination e ct) ramework t les partenaires TG-WACA TOGO-222191-GO- RFQ / Achat de véhicule Stati Component 2: Strengthening Request for Quota Single Stage - One E on WAGON pour le Ministère IDA / 62130 the Policy and Institutional F Post Limited 60,000.00 52,272.60 Signed 2021-05-25 2021-06-11 2021-07-20 2022-02-01 2021-08-19 tions nvelope de la Protection côtière, de la ramework Pêche et de l'Economie Mariti me TG-WACA TOGO-223503-GO- Component 2: Strengthening RFQ / Equipements de suivi e Request for Quota Single Stage - One E TF / A7130 the Policy and Institutional F Post Limited 18,182.00 0.00 Signed 2021-07-05 2022-04-28 2021-08-30 2021-09-29 t surveillance pour les comm tions nvelope ramework unautés locales (30 tablettes ) TG-WACA TOGO-232179-GO- RFQ / Acquisition de matériel pour la vidéoconférence pour Component 4: National Coor Request for Quota Single Stage - One E IDA / 62130 Post Limited 97,273.00 35,295.12 Signed 2021-07-20 2021-06-29 2021-09-14 2022-03-29 2021-10-14 la salle de réunion de l'UGP (l dination tions nvelope ot1) et pour la faculté de géo graphie de l'université de Kar a (lot2) TG-WACA TOGO-249718-GO- RFQ / ACQUISITION DE MOBIL Component 4: National Coor Request for Quota Single Stage - One E IDA / D2860 Post Limited 50,000.00 42,374.50 Signed 2021-10-05 2021-09-07 2021-11-30 2022-02-01 2021-12-30 IER DE BUREAU POUR L'UNIT dination tions nvelope E DE COORDINATION NATION ALE TG-WACA TOGO-223620-GO- RFQ / acquisition de matériel Component 2: Strengthening Single Stage - One E Under Imple et équipement de laboratoire IDA / D2860 the Policy and Institutional F Post Request for Bids Open - National 110,000.00 0.00 2021-11-15 2021-10-01 2021-11-20 2021-12-20 2021-11-16 2022-01-19 2021-12-29 2022-02-23 2022-05-24 nvelope mentation pour les départements de gé ramework ographie des universités de L omé et Kara TG-WACA TOGO-265102-GO- Component 4: National Coor Request for Quota Single Stage - One E Under Imple RFQ / Fourniture et installatio IDA / D2860 Post Limited 54,000.00 0.00 2022-06-01 2022-02-25 2022-07-27 2023-01-23 dination tions nvelope mentation n de groupe électrogène TG-WACA TOGO-276063-GO- Component 3: Strengthening RFB / Acquisition et installati Open - Internationa Single Stage - One E Pending Impl IDA / D2860 National Physical and Social Post Request for Bids 650,000.00 0.00 2022-09-30 2022-10-05 2022-11-16 2022-12-16 2023-01-20 2023-07-19 on d'un centre de contrôle et l nvelope ementation Investments d'une station météorologique marine TG-WACA TOGO-276061-GO- Component 3: Strengthening Request for Quota Single Stage - One E Pending Impl RFQ / Acquisition de matériel IDA / D2860 National Physical and Social Post Limited 100,000.00 0.00 2022-06-28 2022-08-31 2023-02-27 tions nvelope ementation de collecte des données par l Investments es institutions Page 3 TG-WACA TOGO-260437-GO- RFB / FOURNITURE ET INSTAL LATION DE MINI CENTRALES SOLAIRES AVEC RESEAU ELE Component 3: Strengthening CTRIQUE, DE PLATEFORMES Single Stage - One E TF / A7130 National Physical and Social Post Request for Bids Open - National 218,000.00 0.00 Signed 2022-07-28 2022-01-31 2022-08-02 2022-09-01 2022-04-20 2022-10-01 2022-08-12 2022-11-05 2023-03-05 MULTIFONCTIONNELLES ALIM nvelope Investments ENTEES PAR LA CENTRALE S OLAIRE ET DES KITS DE LAMP ADAIRES AUTONOMES EN 04 LOTS DANS 04 LOCALITES (A damé, Afito, Godjinmé et Nya massiva) TG-WACA TOGO-223532-GO- RFQ / Acquisition d'équipeme nt pour la mise en place d'un Component 2: Strengthening e base de données de gestio Request for Quota Single Stage - One E IDA / D2860 the Policy and Institutional F Post Limited 95,454.00 0.00 Signed 2022-10-05 2022-04-26 2022-11-30 2023-02-28 n des ouvrages côtiers (serve tions nvelope ramework ur, ordinateurs portables, dis que durs externe, appareil p hoto professionnel, etc...) et des ordinateurs portables TG-WACA TOGO-292672-GO- RFQ / Acquisition d'équipeme nts complémentaires de prod Component 2: Strengthening Request for Quota Single Stage - One E Pending Impl uction des plants et d'expéri TF / A7130 the Policy and Institutional F Post Limited 54,000.00 0.00 2022-09-05 2022-10-31 2022-11-30 tions nvelope ementation mentation pour le centre se ramework mencier de Davié (Ombrière, Humidi-mètre ,PH-mètre, Mél angeur de terreau) TG-WACA TOGO-292843-GO- Component 3: Strengthening Request for Quota Single Stage - One E Under Imple RFQ / Achat d'un porte-char IDA / D2860 National Physical and Social Post Limited 70,000.00 0.00 2022-07-25 2022-06-08 2022-09-19 2023-03-18 tions nvelope mentation pour la commune Lacs1 Investments TG-WACA TOGO-306594-GO- Component 2: Strengthening Single Stage - One E Pending Impl RFB / Acquisition des équipe IDA / D2860 the Policy and Institutional F Post Request for Bids Open - National 360,000.00 0.00 2022-09-30 2022-10-05 2022-11-04 2022-12-04 2023-01-08 2023-01-20 nvelope ementation ments du studio (Météo médi ramework a) TG-WACA TOGO-313510-GO- Component 3: Strengthening RFQ / Fourniture et pose de p Request for Quota Single Stage - One E IDA / 62130 National Physical and Social Post Limited 18,000.00 0.00 Signed 2022-11-05 2022-08-24 2022-12-31 2023-06-29 anneaux de signalisation sur tions nvelope Investments les sites de travaux de prote ction côtière TG-WACA TOGO-326628-GO- RFQ / Acquisition des équipe Component 3: Strengthening ments de maraichage (Bande Request for Quota Single Stage - One E Pending Impl TF / A7130 National Physical and Social Post Limited 130,000.00 0.00 2022-12-20 2023-02-14 2023-08-13 s perforées, motopompe et a tions nvelope ementation Investments ccessoires, Pulvérisateur élec trique rechargeable etc..) TG-WACA TOGO-313451-GO- Component 3: Strengthening Request for Quota Single Stage - One E Pending Impl RFQ / ACHAT DE TRACTEUR P IDA / D2860 National Physical and Social Post Limited 40,000.00 0.00 2023-02-20 2023-04-17 2023-10-14 tions nvelope ementation OUR LA COMMUNE LAC 1 Investments TG-WACA TOGO-308000-GO- Component 2: Strengthening Request for Quota Single Stage - One E Under Imple TF / A7130 Post Limited 150,000.00 0.00 2023-02-20 2023-02-22 2023-04-17 2023-10-14 RFQ / Acquisition d'un camio the Policy and Institutional F tions nvelope mentation n fourgon ramework TG-WACA TOGO-346896-GO- Component 3: Strengthening RFB / Acquisition des équipe Single Stage - One E Under Imple IDA / D2860 National Physical and Social Post Request for Bids Open - National 566,273.00 0.00 2023-04-24 2023-05-16 2023-04-29 2023-05-29 2023-06-28 2023-08-02 2024-02-28 ments de transformation en nvelope mentation Investments sept (07) lots pour les 7 AGR TG-WACA TOGO-355426-GO- Component 3: Strengthening RFQ / acquisition de plants p Request for Quota Single Stage - One E Pending Impl TF / A7130 National Physical and Social Post Limited 140,000.00 0.00 2023-05-20 2023-07-15 2024-01-11 our le reboisement par ODEF tions nvelope ementation Investments et les mairies des préfecture s des Lacs et Vo 97 / Réalisation des films do Component 4: National Coor Request for Quota Single Stage - One E IDA / D2860 Post Open - National 27,909.00 0.00 Canceled 2020-05-27 2020-07-22 2021-01-18 cumentaires dination tions nvelope 93 / Fournitures de bureau p Component 4: National Coor Request for Quota Single Stage - One E our l'UGP ( Accord cadre attri TF / A7130 Post Open 20,000.00 0.00 Canceled 2020-04-20 2020-06-15 2020-12-12 dination tions nvelope bution par article) TG-WACA TOGO-223544-GO- Component 2: Strengthening RFQ / Edition et vulgarisation Request for Quota Single Stage - One E IDA / D2860 the Policy and Institutional F Post Limited 5,544.00 0.00 Canceled 2021-05-31 2021-07-26 2021-08-25 du guide d'intégration de l'éc tions nvelope ramework onomie bleu dans les docum ents de planification TG-WACA TOGO-234936-GO- Component 2: Strengthening Request for Quota Single Stage - One E TF / A7130 Post Limited 5,000.00 0.00 Canceled 2021-08-04 2021-09-29 2021-11-28 RFQ / achat de deux (02) dro the Policy and Institutional F tions nvelope nes ramework TG-WACA TOGO-365276-GO- Component 3: Strengthening RFQ / Acquisition de plants p Request for Quota Single Stage - One E Pending Impl TF / A7130 National Physical and Social Post Limited 50,000.00 0.00 2023-08-05 2023-09-30 2024-03-28 our l'ODEF (Tectona grandis, tions nvelope ementation Investments Gmelina arborea, Khaya sene galensis etc..) TG-WACA TOGO-365279-GO- Component 3: Strengthening Request for Quota Single Stage - One E Pending Impl RFQ / acquisition de plants p TF / A7130 National Physical and Social Post Limited 6,000.00 0.00 2023-08-05 2023-09-30 2024-03-28 tions nvelope ementation our la commune des Lacs 1 Investments TG-WACA TOGO-365283-GO- RFQ / achat de plants pour la Component 3: Strengthening Request for Quota Single Stage - One E Pending Impl commune Lacs 2 (Khaya sen TF / A7130 National Physical and Social Post Limited 5,900.00 0.00 2023-08-05 2023-09-30 2024-03-28 tions nvelope ementation egalensis, Sena ciamea Gmel Investments ina arborea et autres essenc es naturelles) TG-WACA TOGO-365292-GO- Component 3: Strengthening Request for Quota Single Stage - One E Pending Impl RFQ / Acquisition de plants p TF / A7130 National Physical and Social Post Limited 6,200.00 0.00 2023-08-13 2023-10-08 2024-04-05 tions nvelope ementation our la mairie Lacs 3 Investments TG-WACA TOGO-365294-GO- RFQ / achat de plants pour la Component 3: Strengthening Request for Quota Single Stage - One E Pending Impl mairie Vo 1 (Khaya senegale TF / A7130 National Physical and Social Post Limited 18,000.00 0.00 2023-08-09 2023-10-04 2024-04-01 tions nvelope ementation nsis, Sena ciamea Gmelina ar Investments borea et autres essences nat urelles) TG-WACA TOGO-365296-GO- Component 3: Strengthening Request for Quota Single Stage - One E Pending Impl RFQ / acquisition de plants p TF / A7130 National Physical and Social Post Limited 17,000.00 0.00 2023-08-13 2023-10-08 2024-04-05 tions nvelope ementation our la mairie Vo 3 Investments TG-WACA TOGO-365299-GO- Component 3: Strengthening Request for Quota Single Stage - One E Pending Impl RFQ / achat de plants pour la TF / A7130 National Physical and Social Post Limited 6,000.00 0.00 2023-08-13 2023-10-08 2024-04-05 tions nvelope ementation mairie Vo 2 Investments Page 4 NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 36 / Edition du plan d'investi ssement et du document d'a Component 4: National Coor Request for Quota Single Stage - One E IDA / V1150 Post Limited 18,000.00 20,365.63 Signed 2018-02-21 2018-02-16 2018-04-18 2018-08-01 2018-10-15 nalyse du cadre juridique inst dination tions nvelope itutionnel de gestion intégrée du littoral 38 / Paramétrage du logiciel Component 4: National Coor de gestion financière du PGIC IDA / V1150 Post Direct Selection Direct 13,000.00 12,538.87 Signed 2018-07-05 2018-11-14 2018-07-10 2018-11-14 2018-08-14 2019-08-29 2019-02-10 dination T pour le projet WACA 52 / Recrutement d'un servic Component 4: National Coor Request for Quota Single Stage - One E IDA / D2860 Post Limited 4,000.00 0.00 Signed 2019-06-29 2020-06-08 2019-08-24 2020-02-20 e d'entretien dination tions nvelope 77 / Police d'assurance pour Component 4: National Coor Request for Quota Single Stage - One E le personnel recruté par le pr IDA / D2860 Post Limited 20,000.00 12,512.77 Signed 2019-11-25 2019-09-10 2020-01-20 2020-04-08 2020-07-18 dination tions nvelope ojet WACA ResIP 17 BIS / Mise en place d'un s ystème informatisé de suivi d Component 4: National Coor Single Stage - One E IDA / D2860 Post Request for Bids Open - National 40,000.00 0.00 Canceled 2019-02-20 2019-05-08 2019-02-25 2019-04-08 2019-05-08 2019-06-12 2019-12-09 u projet (acquisition, installat dination nvelope ion et formation des utilisate urs) 119 / Service de gardiennag Component 4: National Coor Request for Quota Single Stage - One E IDA / D2860 Post Limited 8,182.00 8,602.22 Signed 2020-08-17 2020-09-09 2020-10-12 2021-04-24 2021-10-09 e des bureaux de l'UGP dination tions nvelope TG-WACA TOGO-364035-NC- Component 4: National Coor Request for Quota Single Stage - One E Pending Impl RFQ / Entretien et maintenan IDA / D2860 Post Limited 24,000.00 0.00 2023-09-04 2023-10-30 2023-12-05 dination tions nvelope ementation ce de climatiseur CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 14 / Etude de faisabilité tech Component 3: Strengthening Quality And Cost- Open - Internationa nique de la protection côtière IDA / V1150 National Physical and Social Prior 2,000,000.00 0.00 Canceled 2018-02-06 2018-02-27 2018-04-12 2018-05-10 2018-06-09 2018-07-14 2018-08-18 2019-08-18 Based Selection l du segment transfrontalier B Investments énin-Togo 15 / Etude d'Impact Environ Component 2: Strengthening nemental et Social (EIES) de l Quality And Cost- Open - Internationa IDA / V1150 the Policy and Institutional F Post 320,000.00 0.00 Canceled 2018-02-08 2018-03-01 2018-04-14 2018-05-12 2018-06-11 2018-07-16 2018-08-20 2019-08-20 a protection côtière du segm Based Selection l ramework ent transfrontalier Bénin-Tog o 19 / Etude d'Impact Environ nemental et Social (EIES) pou Component 2: Strengthening Consultant Qualifi r le curage mécanique du ch IDA / V1150 the Policy and Institutional F Post Open - National 200,000.00 0.00 Canceled 2018-09-25 2018-10-16 2018-11-29 2018-12-29 2019-02-02 2019-08-01 cation Selection enal Gbaga et de restauratio ramework n de ces écosystèmes associ és 46 / Evaluation du coût de la Component 2: Strengthening dégradation historique de la Consultant Qualifi IDA / D2860 the Policy and Institutional F Post Open - National 130,000.00 149,746.25 Signed 2019-01-17 2019-05-22 2019-02-07 2019-07-08 2019-03-23 2019-11-28 2019-04-22 2020-12-22 2019-05-27 2021-04-24 2019-11-23 côte y compris la vulnérabilit cation Selection ramework é des communautés côtières 42BIS / Etude de faisabilité t echnique de l'installation d'u Component 3: Strengthening Quality And Cost- Open - Internationa ne vanne au niveau du pont IDA / D2860 National Physical and Social Prior 650,000.00 0.00 Canceled 2019-03-05 2019-03-26 2019-05-09 2019-06-06 2019-07-06 2019-08-10 2019-09-14 2020-09-13 Based Selection l de la lagune d'Aného et l'étu Investments de hydrodynamique du systè me fluvio-lagunaire 43 / Etude approfondie de fa Component 3: Strengthening Quality And Cost- Open - Internationa isabilité du traitement des bo IDA / 62130 National Physical and Social Prior 600,000.00 0.00 Canceled 2019-03-12 2019-04-02 2019-05-16 2019-06-13 2019-07-13 2019-08-17 2019-09-21 2020-09-20 Based Selection l ues de phosphates rejetées e Investments n mer 44 / Elaboration du plan spat Component 4: National Coor Quality And Cost- Open - Internationa IDA / D2860 Post 250,000.00 0.00 Canceled 2019-02-11 2019-03-04 2019-04-17 2019-05-15 2019-06-14 2019-07-19 2019-08-23 2020-08-22 ial marin et côtier dination Based Selection l 45 / Evaluation du capital na Component 2: Strengthening Quality And Cost- Open - Internationa IDA / D2860 Post 300,000.00 0.00 Canceled 2019-02-12 2019-03-05 2019-04-18 2019-05-16 2019-06-15 2019-07-20 2019-08-24 2020-08-23 turel de la zone côtière the Policy and Institutional F Based Selection l ramework 49 / Audits financiers et com Component 4: National Coor Least Cost Selecti ptables du projet - exercices IDA / D2860 Post Open - National 45,000.00 24,687.83 Signed 2019-02-11 2019-04-18 2019-03-04 2019-07-08 2019-04-17 2019-10-10 2019-05-15 2020-02-06 2019-06-14 2020-03-11 2019-07-19 2020-05-19 2019-08-23 2020-06-30 2020-02-19 dination on 2017, 2018 et 2019 3 BIS / Etudes de faisabilité t echniques de dragage et de Component 3: Strengthening stabilisation des berges de la Quality And Cost- Open - Internationa IDA / D2860 National Physical and Social Post 250,000.00 1,061,119.41 Signed 2018-10-04 2018-05-18 2018-10-25 2018-12-08 2019-08-28 2019-01-05 2019-10-10 2019-02-04 2019-10-25 2019-03-11 2019-12-13 2019-04-15 2020-08-27 2020-04-14 lagune et du lac Togo, et pou Based Selection l Investments r la Construction et le curage de caniveau, de bassin d'ora ge, de retenue d'eau 48 / Etude d'Impact Environ nemental et Social (EIES) pou Component 3: Strengthening Consultant Qualifi r le curage mécanique du ch TF / A7130 National Physical and Social Post Open - National 100,000.00 0.00 Canceled 2018-12-28 2019-01-03 2019-01-18 2019-03-03 2019-04-02 2019-05-07 2019-11-03 cation Selection enal Gbaga et de restauratio Investments n de ces écosystèmes associ és 47B / Etude de faisabilité tec Component 3: Strengthening hnique pour le curage mécan Quality And Cost- Open - Internationa TF / A7130 National Physical and Social Prior 600,000.00 554,086.35 Signed 2019-04-26 2019-04-18 2019-05-17 2019-07-23 2019-06-30 2020-10-17 2019-07-28 2020-10-26 2019-08-27 2021-01-14 2019-10-01 2021-04-13 2019-11-05 2021-06-19 2020-11-04 ique du chenal de Gbaga et d Based Selection l Investments e la restauration de ces écos ystèmes associés 47 / Etude de faisabilité tech Component 3: Strengthening nique du curage mécanique Quality And Cost- Open - Internationa TF / A7130 National Physical and Social Post 300,000.00 0.00 Canceled 2018-12-28 2019-01-03 2019-01-18 2019-03-03 2019-03-31 2019-04-30 2019-06-04 2019-07-09 2020-07-08 du chenal Gbaga et de resta Based Selection l Investments uration de ces écosystèmes associés 48B / Etude d'Impact Enviro nnemental et Social (EIES) po Component 3: Strengthening Consultant Qualifi Open - Internationa Under Implement ur le curage mécanique du c TF / A7130 National Physical and Social Post 200,000.00 0.00 2019-04-26 2019-04-17 2019-05-17 2019-06-30 2019-08-13 2019-07-30 2021-02-26 2019-09-03 2020-03-01 cation Selection l ation henal Gbaga et de restaurati Investments on de ces écosystèmes assoc iés Page 5 40 / Surveillance et contrôle Component 4: National Coor Consultant Qualifi des travaux d'aménagement IDA / V1150 Post Open - National 18,000.00 0.00 Canceled 2018-07-11 2018-08-01 2018-09-14 2018-10-14 2018-11-18 2019-05-17 dination cation Selection des bureaux du Projet WACA 62 / Élaboration du plan d'a Component 3: Strengthening ménagement participatif et d Consultant Qualifi Open - Internationa TF / A7130 National Physical and Social Post 140,000.00 154,345.80 Signed 2019-08-28 2020-01-07 2019-09-18 2020-06-26 2019-11-01 2020-10-26 2019-12-01 2021-02-09 2020-01-05 2021-04-24 2020-07-03 es outils de gestion de la forê cation Selection l Investments t communautaire d'Avévé  63 / Elaboration du plan d'a Component 3: Strengthening ménagement participatif et d Consultant Qualifi Open - Internationa TF / A7130 National Physical and Social Post 150,000.00 154,345.80 Signed 2019-08-28 2020-01-07 2019-09-18 2020-06-26 2019-11-01 2020-10-15 2019-12-01 2021-02-09 2020-01-05 2021-04-24 2020-07-03 es outils de gestion de la forê cation Selection l Investments t communautaire de Kodjo-G ati 60 / Recrutement d'une stru cture ( centre de formation) Component 3: Strengthening pour la formation et l'accomp Consultant Qualifi TF / A7130 National Physical and Social Post Open - National 55,000.00 244,722.82 Signed 2019-08-28 2019-08-21 2019-09-18 2019-11-01 2020-05-05 2019-12-01 2020-06-10 2020-01-05 2021-06-04 2020-07-03 agnement des acteurs comm cation Selection Investments unautaires sur les bonnes pr atiques en gestion durable d es terres. 82 / Etude sur la situation de s plantes envahissantes, des Component 3: Strengthening Consultant Qualifi Open - Internationa modèles de gestion et de val TF / A7130 National Physical and Social Post 80,000.00 0.00 Signed 2019-12-30 2020-03-30 2020-01-20 2022-04-28 2020-03-04 2022-10-20 2020-04-03 2022-11-28 2020-05-08 2020-11-04 cation Selection l orisation dans la sous-région Investments et les applications possibles dans la zone du projet 40 C / Surveillance et contrôl e des travaux d'aménageme nt du R + 1 des bureaux de l' Component 4: National Coor Consultant Qualifi UGP, Construction du mur de IDA / D2860 Post Open - National 20,000.00 0.00 Canceled 2019-08-28 2019-09-18 2019-11-01 2019-12-01 2020-01-05 2020-07-03 dination cation Selection séparation, d'un parking pour 10 voitures, d'un poste d'ach at et d'un aménagement de cour. 105 / Recrutement d'un cabi net pour l'actualisation de l'é tude de faisabilité technique Component 3: Strengthening du projet d'assainissement d Quality And Cost- Open - Internationa IDA / D2860 National Physical and Social Post 120,000.00 111,390.00 Signed 2020-06-30 2020-09-16 2020-07-21 2021-01-20 2020-09-03 2021-04-15 2020-10-01 2021-07-02 2020-10-31 2021-07-28 2020-12-05 2021-08-19 2021-01-09 2022-02-01 2022-01-09 es eaux usées à la plage de L Based Selection l Investments omé, réhabilitation du réseau embryonnaire d'assainissem ent collectif des eaux usées de la ville de Lomé au Togo 121 / Recrutement d'un cabi net pour le contrôle et surveil Component 3: Strengthening lance des travaux d’urgence Consultant Qualifi IDA / D2860 National Physical and Social Post Limited 910.00 90,871.35 Signed 2020-08-07 2020-08-09 2020-08-21 2020-08-25 2020-09-20 2020-11-10 2020-10-25 2021-02-02 2021-02-24 de protection contre l’érosion cation Selection Investments côtière des habitations vulné rables sur le littoral togolais allant de Gbodjomé à Agbodr afo. TG-WACA TOGO-223531-CS- CQS / Etude de faisabilité te Component 2: Strengthening Consultant Qualifi chnique pour la création et l' IDA / D2860 the Policy and Institutional F Post Open - National 92,000.00 0.00 Canceled 2021-06-30 2021-07-21 2021-09-03 2021-10-03 2021-11-07 2022-05-06 cation Selection opérationnalisation de l'obse ramework rvatoire national sur le littora l 78 / Assistance technique et Component 2: Strengthening Consultant Qualifi TF / A7130 Post Open - National 220,982.00 0.00 Canceled 2020-01-14 2020-01-15 2020-02-04 2020-03-19 2020-04-18 2020-05-23 2020-11-19 contrôle des activités commu the Policy and Institutional F cation Selection nautaires ramework 113 / Etude d'avant projet d étaillé (APD) pour la construc Component 4: National Coor Consultant Qualifi tion de la nouvelle direction r IDA / D2860 Post Open - National 40,000.00 0.00 Canceled 2020-07-27 2020-08-17 2020-09-30 2020-10-30 2020-12-04 2021-06-02 dination cation Selection égionale des forestiers de la réserve de faune de Togodo Nord à Atakpamé TG-WACA TOGO-276324-CS- Component 4: National Coor Least Cost Selecti Pending Impleme LCS / audit externe 2023 et IDA / D2860 Post Open - National 20,000.00 0.00 2022-08-16 2022-09-06 2022-10-20 2022-11-17 2022-12-17 2023-01-21 2023-02-25 2023-03-27 dination on ntation clôture du projet TG-WACA TOGO-276160-CS- Component 3: Strengthening QBS / Informatisation du syst Consultant Qualifi Open - Internationa Pending Impleme TF / A7130 National Physical and Social Post 100,000.00 0.00 2022-09-30 2022-10-21 2022-12-04 2023-01-03 2023-02-07 2023-08-06 ème de suivi-évaluation du M cation Selection l ntation Investments ERF: Extension du logiciel Ru che au ministère TG-WACA TOGO-276156-CS- Component 2: Strengthening QBS / Recrutement d'un cabi Consultant Qualifi Open - Internationa TF / A7130 the Policy and Institutional F Post 100,000.00 0.00 Signed 2022-07-29 2022-05-11 2022-08-19 2022-07-27 2022-10-02 2022-09-15 2022-11-01 2022-11-02 2022-12-06 2023-06-04 net pour la formation des ag cation Selection l ramework ents du MEMPPC sur la prote ction côtière TG-WACA TOGO-224375-CS- Component 3: Strengthening CDS / Etude de faisabilité tec Quality And Cost- Open - Internationa Under Implement IDA / 62130 National Physical and Social Post 380,000.00 0.00 2022-09-28 2023-03-14 2022-10-19 2022-12-02 2022-06-06 2022-12-30 2022-06-17 2023-01-29 2022-06-02 2023-03-05 2022-06-20 2023-04-09 2024-04-08 hnique de la mise en place d' Based Selection l ation Investments un bypass au port autonome de Lomé TG-WACA TOGO-276177-CS- Component 3: Strengthening QBS / Mise en valeur de quat Quality And Cost- Open - Internationa Under Implement IDA / 62130 National Physical and Social Post 363,637.00 0.00 2022-09-30 2023-05-01 2022-10-21 2023-05-04 2022-12-04 2023-01-01 2023-01-31 2023-03-07 2023-04-11 2024-04-10 re zones prioritaires du Sché Based Selection l ation Investments ma d’aménagement du Littor al (SDAL) TG-WACA TOGO-222420-CS- CQS / Elaboration de la carte Component 2: Strengthening Consultant Qualifi de vulnérabilité de la côte to TF / A7130 the Policy and Institutional F Post Open - National 54,545.00 0.00 Canceled 2022-08-24 2022-09-14 2022-10-28 2022-11-27 2023-01-01 2023-04-01 cation Selection golaise face aux menaces de ramework pollution par les hydrocarbur es (ABC) TG-WACA TOGO-308002-CS- CQS / Elaboration de la carte Component 2: Strengthening Consultant Qualifi Open - Internationa Under Implement de vulnérabilité de la côte to TF / A7130 the Policy and Institutional F Post 100,000.00 0.00 2022-10-20 2023-01-24 2022-11-10 2023-03-24 2022-12-24 2023-01-23 2023-02-27 2023-08-26 cation Selection l ation golaise face aux menaces de ramework pollution par les hydrocarbur es (ABC) TG-WACA TOGO-313433-CS- Component 3: Strengthening CQS / CONTRÔLE DES TRAVA Consultant Qualifi Open - Internationa Under Implement IDA / 62130 National Physical and Social Post 990,000.00 0.00 2022-10-20 2022-09-29 2022-11-10 2022-12-13 2022-12-24 2023-01-23 2023-02-27 2023-12-24 UX DE CURAGE MÉCANIQUE cation Selection l ation Investments DU CHENAL DE GBAGA TG-WACA TOGO-339841-CS- Component 2: Strengthening Quality And Cost- CQS / Étude architecturale de IDA / D2860 the Policy and Institutional F Post Open - National 120,000.00 0.00 Under Review 2023-04-24 2023-05-15 2023-06-28 2023-07-26 2023-08-25 2023-09-29 2023-11-03 2024-11-02 Based Selection la construction du siège de l' ramework ANGE Page 6 TG-WACA TOGO-276163-CS- QBS / Appui à la mise en œu Component 3: Strengthening vre du plan d'investissement Consultant Qualifi Open - Internationa IDA / D2860 National Physical and Social Post 100,000.00 0.00 Canceled 2022-09-30 2022-10-21 2022-12-04 2023-01-03 2023-02-07 2023-08-06 des CDN 2030 du Togo pour l cation Selection l Investments 'élaboration d'une stratégie d e développement sobre en c arbone et résilience au CC TG-WACA TOGO-223546-CS- Component 2: Strengthening Consultant Qualifi CQS / Elaboration du plan sp IDA / D2860 the Policy and Institutional F Post Open - National 32,000.00 0.00 Canceled 2022-09-26 2022-10-17 2022-11-30 2022-12-30 2023-02-03 2023-06-03 cation Selection atial marin et côtier ramework INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 1 / Elaboration du Cadre de Component 2: Strengthening Individual Consult Gestion Environnementale et IDA / V1150 the Policy and Institutional F Post Limited 27,500.00 23,893.15 Signed 2017-07-18 2017-06-22 2017-07-23 2017-09-07 2018-01-29 2017-09-28 2018-03-05 2017-11-29 2018-07-17 ant Selection Sociale (CGES) ramework 2 / Elaboration du Cadre de Component 2: Strengthening Individual Consult IDA / V1150 Post Limited 24,000.00 20,223.92 Signed 2017-06-22 2017-06-22 2017-08-24 2017-09-07 2017-09-29 2017-09-29 2017-11-29 2017-11-29 2018-01-12 Politique de Réinstallation (C the Policy and Institutional F ant Selection PR) ramework 4 / Etude d'impact environne Component 2: Strengthening mental et social des dragage Individual Consult IDA / V1150 the Policy and Institutional F Post Limited 18,000.00 0.00 Signed 2017-11-12 2017-11-12 2018-01-27 2018-01-22 2018-02-17 2018-05-31 2018-03-24 2018-04-24 s et de la construction des ou ant Selection ramework vrages de lutte contre les ino ndations 13 / Elaboration de la straté Component 4: National Coor IDA / V1150 Post Direct Selection Direct 14,000.00 13,130.33 Signed 2017-12-12 2017-12-12 2017-12-22 2017-12-22 2018-02-09 2018-08-29 2018-03-29 gie de passation des marché dination s (PPSD) 6 / Recrutement d'un spécial Component 4: National Coor Individual Consult IDA / V1150 Post Open 24,000.00 0.00 Canceled 2018-02-06 2018-03-27 2018-04-17 2018-05-22 2018-11-18 iste en passation des marché dination ant Selection s 8 / Recrutement d'un spécial Component 4: National Coor Individual Consult IDA / V1150 Post Open 24,000.00 0.00 Canceled 2018-02-06 2018-03-27 2018-04-17 2018-05-22 2018-11-18 iste en suivi-évaluation dination ant Selection 9 / Recrutement d'un spécial Component 4: National Coor Individual Consult IDA / V1150 Post Open 24,000.00 0.00 Canceled 2018-02-06 2018-03-27 2018-04-17 2018-05-22 2018-11-18 iste en sauvegarde sociale dination ant Selection 10 / Recrutement d'un spéci Component 4: National Coor Individual Consult IDA / V1150 Post Open 24,000.00 0.00 Canceled 2018-02-20 2018-04-10 2018-05-01 2018-06-05 2018-12-02 aliste en communication dination ant Selection 9 BIS / Recrutement d'un sp Component 4: National Coor Individual Consult IDA / V1150 Post Open 24,000.00 0.00 Signed 2018-04-26 2018-05-18 2018-06-14 2019-01-25 2018-07-05 2019-05-14 2018-08-09 2019-02-05 écialiste en sauvegarde socia dination ant Selection le 10 BIS / Recrutement d'un s Component 4: National Coor Individual Consult IDA / V1150 Post Open 24,000.00 0.00 Signed 2018-06-03 2018-02-18 2018-07-22 2019-04-11 2018-08-12 2019-05-20 2018-09-16 2019-03-15 pécialiste en communication dination ant Selection 7 / Recrutement d'un ingéni Component 4: National Coor Individual Consult IDA / V1150 Post Open 28,000.00 0.00 Signed 2018-05-17 2018-08-13 2018-07-05 2018-07-26 2019-04-15 2018-08-30 2019-02-26 eur génie civil (génie côtier) dination ant Selection 27 / Recrutement d'un audit Component 4: National Coor Individual Consult IDA / V1150 Post Open 24,000.00 0.00 Signed 2018-05-24 2019-02-03 2018-07-12 2019-06-25 2018-08-02 2022-02-22 2018-09-06 2019-03-05 eur interne du projet dination ant Selection 11 / Recrutement de secréta Component 4: National Coor Individual Consult IDA / V1150 Post Open 12,000.00 0.00 Canceled 2018-02-20 2018-04-10 2018-05-01 2018-06-05 2018-12-02 ire caissière dination ant Selection 7 / Recrutement d'un ingéni Component 4: National Coor Individual Consult IDA / V1150 Post Open 24,000.00 0.00 Canceled 2018-02-06 2018-03-27 2018-04-17 2018-05-22 2018-11-18 eur génie civil (génie côtier) dination ant Selection 3 / Réalisation d'études tech Component 3: Strengthening Individual Consult niques d'ouvrages de lutte co IDA / V1150 National Physical and Social Post Limited 53,000.00 0.00 Canceled 2017-11-08 2017-11-13 2018-03-26 2018-04-30 2018-10-27 ant Selection ntre les inondations Investments 12 / Recrutement d'un Assist Component 4: National Coor Individual Consult IDA / V1150 Post Limited 30,000.00 0.00 Canceled 2017-11-08 2017-11-13 2017-12-04 2018-01-08 2018-07-07 ant technique au projet dination ant Selection 25 / Recrutement d'un assist Component 4: National Coor Individual Consult IDA / V1150 Post Open 10,000.00 0.00 Canceled 2018-04-26 2018-06-14 2018-07-05 2018-08-09 2019-02-05 ant en passation des marché dination ant Selection s 24 BIS / Recrutement d'un s Component 4: National Coor Individual Consult IDA / D2860 Post Open 24,000.00 0.00 Signed 2018-08-29 2018-09-18 2018-11-02 2018-11-23 2019-02-25 2018-12-28 2019-06-26 pécialiste en gestion financiè dination ant Selection re 24 / Recrutement d'un assist Component 4: National Coor Individual Consult IDA / V1150 Post Open 10,000.00 0.00 Canceled 2018-08-29 2018-10-31 2018-11-21 2018-12-26 2019-06-24 ant au spécialiste en gestion dination ant Selection financière 6 BIS / Recrutement d'un sp Component 4: National Coor Individual Consult IDA / D2860 Post Open 24,000.00 37,051.31 Signed 2018-08-27 2018-10-31 2019-02-15 2018-11-21 2019-08-19 2018-12-26 2019-08-09 2019-06-24 écialiste en passation des ma dination ant Selection rchés 69 / Actualisation des manu Component 2: Strengthening Individual Consult IDA / D2860 Post Open 13,000.00 13,023.07 Signed 2019-06-17 2019-06-07 2019-08-05 2020-11-17 2019-08-26 2020-11-23 2019-09-30 2021-04-24 2020-03-28 els de procédure de l'ANGE the Policy and Institutional F ant Selection ramework 67 / Élaboration du plan de d éveloppement des Ressource Component 2: Strengthening Individual Consult s Humaines du Ministère de l' TF / A7130 the Policy and Institutional F Post Open 15,000.00 0.00 Canceled 2019-06-19 2019-06-17 2019-08-07 2019-08-28 2019-10-02 2020-03-30 ant Selection Environnement, du Développ ramework ement Durable et de la Prote ction de la Nature 64 / Appui à l'analyse institu tionnelle du Ministère de l'En vironnement, du Développe Component 2: Strengthening Individual Consult ment Durable et de la Protec TF / A7130 the Policy and Institutional F Post Open 15,000.00 16,668.25 Signed 2019-06-19 2019-06-07 2019-08-07 2020-11-17 2019-08-28 2020-11-23 2019-10-02 2021-04-24 2020-03-30 ant Selection tion de la Nature relative à la ramework mise en œuvre des conventio ns internationales signées pa r le Togo Component 3: Strengthening 68 / Élaboration du cadre fo Individual Consult TF / A7130 National Physical and Social Post Open 24,000.00 18,403.19 Signed 2019-06-17 2019-06-07 2019-08-05 2019-11-04 2019-08-26 2019-02-07 2019-09-30 2020-08-18 2020-03-28 nctionnel (procédural) ant Selection Investments Page 7 40B / Surveillance contrôle d es Travaux d'aménagement du R+1 des bureaux pour l'U GP, Construction du mur de s Component 4: National Coor Individual Consult IDA / V1150 Post Open 9,000.00 0.00 Canceled 2019-06-20 2019-08-08 2019-08-29 2019-10-03 2020-03-31 éparation, d'un parking pour dination ant Selection 10 voitures, un poste d'héber gement (des compteurs et d u groupe électrogène) et am énagement de la cour 61 / Élaboration des textes d Component 2: Strengthening Individual Consult IDA / D2860 Post Open 20,000.00 22,801.19 Signed 2019-06-20 2019-06-07 2019-08-08 2020-12-18 2019-08-29 2021-01-04 2019-10-03 2021-04-24 2020-03-31 'application de la loi sur le litt the Policy and Institutional F ant Selection oral ramework 53 / Recrutement d'un (01) c Component 4: National Coor Individual Consult IDA / D2860 Post Open 3,500.00 4,603.46 Signed 2019-06-26 2019-08-21 2019-08-14 2020-05-13 2019-09-04 2020-09-03 2019-10-09 2020-09-22 2020-04-06 oursier dination ant Selection 55 / Recrutement de deux (2 Component 4: National Coor Individual Consult IDA / D2860 Post Open 9,000.00 20,845.12 Signed 2019-07-12 2019-08-21 2019-08-30 2020-06-02 2019-09-20 2020-07-15 2019-10-25 2020-09-22 2020-04-22 ) chauffeurs de permis catég dination ant Selection orie B 54 / Recrutement d'un (01) c Component 4: National Coor Individual Consult IDA / D2860 Post Open 5,500.00 0.00 Canceled 2019-08-22 2019-08-21 2019-10-10 2019-10-31 2019-12-05 2020-06-02 hauffeur de permis catégorie dination ant Selection C 75 / Recrutement d'un Coord Component 4: National Coor Individual Consult IDA / D2860 Post Open 33,000.00 40,385.61 Signed 2019-08-19 2019-08-20 2019-10-07 2020-03-04 2019-10-28 2020-03-11 2019-12-02 2020-05-27 2020-05-30 onnateur du projet WACA Re dination ant Selection sIP 75BIS / Recrutement de coor Component 4: National Coor Individual Consult IDA / D2860 Post Open 33,000.00 40,486.37 Signed 2019-11-20 2019-11-08 2019-12-23 2020-03-13 2020-01-06 2020-03-25 2020-02-10 2020-05-27 2020-08-08 donnateur pour le projet WA dination ant Selection CA ResIP 91 / Recrutement d'un secré Component 4: National Coor Individual Consult taire administratif pour l'UGP IDA / D2860 Post Open 12,000.00 694.31 Signed 2020-04-09 2020-07-30 2020-05-28 2021-03-15 2020-06-18 2021-05-10 2020-07-23 2021-06-16 2021-01-19 dination ant Selection WACAResIP 89 / Recrutement de consult ant individuel environnement Component 2: Strengthening aliste pour le contrôles des tr Individual Consult TF / A7130 the Policy and Institutional F Post Open 11,136.00 0.00 Canceled 2020-04-15 2020-06-03 2020-06-24 2020-07-29 2021-01-25 avaux d'aménagement de la ant Selection ramework cour du MEDDPN et des bure aux de l'UGP (RDC et R+1) 20 / Recrutement d'un spéci Component 4: National Coor Individual Consult IDA / V1150 Post Open 24,000.00 0.00 Canceled 2018-06-03 2018-07-22 2019-06-25 2018-08-12 2018-09-16 2019-03-15 aliste en développement insti dination ant Selection tutionnel 111 / Recrutement d'un exp Component 4: National Coor Individual Consult ert en passation de marché p IDA / D2860 Post Open 28,500.00 34,987.56 Signed 2020-05-29 2020-05-25 2020-07-17 2020-07-23 2020-08-07 2020-10-02 2020-09-11 2020-11-21 2021-09-10 dination ant Selection our le projet WACA ResIP 115 / Recrutement d'un audi Component 4: National Coor Individual Consult IDA / D2860 Post Open 17,455.00 0.00 Canceled 2020-06-03 2020-07-22 2020-08-12 2020-09-16 2021-11-30 teur interne pour le projet W dination ant Selection ACA ResIP 101 / Recrutement de consul tant individuel génie électro Component 2: Strengthening mécanique pour le contrôle d Individual Consult IDA / D2860 the Policy and Institutional F Post Open 6,200.00 15,039.77 Signed 2020-07-10 2020-06-16 2020-08-28 2020-09-23 2020-09-18 2021-03-24 2020-10-23 2021-04-24 2021-06-23 es travaux d'aménagement d ant Selection ramework u cadre de travail de l'ANGE et du bâtiment R+1 de l'UGP WACA ResiP 90 / Recrutement d’un secré taire pour la passation de ma Component 4: National Coor Individual Consult IDA / D2860 Post Open 12,000.00 11,146.14 Signed 2020-06-30 2020-08-11 2020-08-18 2021-03-15 2020-09-08 2021-05-10 2020-10-13 2021-06-16 2021-04-11 rché et la gestion financière dination ant Selection du projet WACA ResIP 117 / Recrutement d'un spéc Component 4: National Coor Individual Consult ialiste en communication pou IDA / D2860 Post Open 24,000.00 0.00 Canceled 2020-08-12 2020-09-30 2020-10-21 2020-11-25 2021-11-24 dination ant Selection r le projet WACA ResIP 122 / Mise en place d'un sys Component 2: Strengthening tème automatisé de gestion Individual Consult TF / A7130 the Policy and Institutional F Post Open 15,000.00 30,789.27 Signed 2020-09-30 2021-03-29 2020-11-18 2021-06-28 2020-12-09 2021-08-19 2021-01-13 2021-10-15 2021-04-12 des ressources humaines et f ant Selection ramework inancières du MEDDPN TG-WACA TOGO-204714-CS- Component 3: Strengthening INDV / élaboration d'un plan Individual Consult TF / A7130 National Physical and Social Post Limited 20,000.00 25,170.94 Signed 2021-01-28 2020-12-30 2021-02-12 2021-02-04 2021-03-05 2021-06-17 2021-04-09 2021-08-04 2021-05-09 d'aménagement et de gestio ant Selection Investments n de la forêt classée d'Assév é 99 / Recrutement d'un consu ltant pour la réalisation d'un Component 3: Strengthening Individual Consult plan d'action de réinstallatio IDA / D2860 National Physical and Social Post Open 22,000.00 0.00 Canceled 2020-04-10 2020-05-29 2020-06-19 2020-07-24 2021-01-20 ant Selection n du dragage et stabilisation Investments des berges de la lagune et d u lac Togo 95 / Recrutement d'un consu Component 3: Strengthening ltant pour la realisation d'un Individual Consult TF / A7130 National Physical and Social Post Open 9,091.00 0.00 Canceled 2020-04-09 2020-04-14 2020-05-28 2020-06-18 2020-07-23 2021-01-19 plan d'action de réinstallatio ant Selection Investments n du complexe d'aires protég ées de TOGODO 102 / Recrutement de consul tant individuel environnemen Component 2: Strengthening Individual Consult taliste pour le contrôle des tr IDA / D2860 the Policy and Institutional F Post Open 2,727.00 0.00 Canceled 2020-04-09 2020-05-28 2020-06-18 2020-07-23 2021-01-19 ant Selection avaux d'aménagement du ca ramework dre de travail de l'ANGE 94 / Recrutement de consult ant individuel génie civil pour Component 2: Strengthening Individual Consult le contrôle des travaux IDA / D2860 the Policy and Institutional F Post Open 4,136.00 0.00 Canceled 2020-06-30 2020-08-18 2020-09-08 2020-10-13 2021-05-12 ant Selection d'aménagement du cadre de ramework travail de l'ANGE 86 / Recrutement de consult ant individuel génie civil pour Component 2: Strengthening Individual Consult le contrôles des travaux d'a TF / A7130 the Policy and Institutional F Post Open 18,182.00 0.00 Canceled 2020-04-15 2020-06-03 2020-06-24 2020-07-29 2021-01-25 ant Selection ménagement de la cour du ramework MEDDPN et des bureaux de l' UGP (RDC et R+1) 80 / Etude d'impact environn Component 3: Strengthening Individual Consult ementale et sociale du compl TF / A7130 National Physical and Social Post Open 18,182.00 0.00 Canceled 2020-03-19 2020-03-30 2020-05-07 2020-05-28 2020-07-02 2020-12-29 ant Selection exe d'aires protégées de TO Investments GODO TG-WACA TOGO-222909-CS- Component 4: National Coor Individual Consult INDV / Elaboration du rapport IDA / D2860 Post Open 46,000.00 35,376.04 Signed 2021-04-15 2021-03-29 2021-06-03 2021-08-04 2021-06-24 2021-08-16 2021-07-29 2021-09-30 2021-08-28 dination ant Selection d'évaluation à mi-parcours Page 8 TG-WACA TOGO-222896-CS- Component 4: National Coor Individual Consult INDV / SELECTION D’UN EXPE IDA / D2860 Post Open 38,000.00 123.63 Signed 2021-06-18 2021-06-01 2021-08-06 2021-09-03 2021-08-27 2021-09-03 2021-10-01 2022-03-29 2022-10-01 dination ant Selection RT OCEANOGRAPHE – LITTOR ALISTE TG-WACA TOGO-222891-CS- Component 2: Strengthening Individual Consult INDV / Elaboration du plan sp IDA / D2860 the Policy and Institutional F Post Open 32,000.00 0.00 Canceled 2021-05-20 2021-07-08 2021-07-29 2021-09-02 2021-10-02 ant Selection atial marin et côtier ramework 51 / Appui à la mise en place Component 2: Strengthening Individual Consult IDA / D2860 Post Open 30,000.00 0.00 Canceled 2019-02-04 2019-06-05 2019-03-25 2019-04-15 2019-05-20 2019-11-16 du MRV de la zone côtière the Policy and Institutional F ant Selection ramework TG-WACA TOGO-238696-CS- INDV / Recrutement d'un spé Component 4: National Coor Individual Consult IDA / D2860 Post Open 27,000.00 0.00 Under Review 2021-07-14 2021-06-07 2021-09-01 2021-09-22 2021-10-27 2022-10-22 cialiste en développement de dination ant Selection s sous-projet communautaire et AGR pilote TG-WACA TOGO-240809-CS- INDV / RECRUTEMENT D’UN Component 4: National Coor Individual Consult IDA / D2860 Post Limited 17,455.00 16,663.49 Signed 2021-07-30 2021-06-02 2021-08-04 2021-06-10 2021-08-25 2021-08-12 2021-09-29 2021-10-09 2021-11-04 ASSISTANT A LA MISE EN ŒU dination ant Selection VRE DES ACTIVITES GENERA TRICES DE REVENUS TG-WACA TOGO-240217-CS- INDV / ELABORATION DU PLA Component 3: Strengthening N D’ACTION POUR LA RESTRI Individual Consult TF / A7130 National Physical and Social Post Open 54,545.00 40,571.91 Signed 2021-09-30 2021-08-06 2021-11-18 2022-03-15 2021-12-09 2022-04-22 2022-01-13 2022-06-16 2022-04-13 CTION D’ACCES AUX RESSOU ant Selection Investments RCES DES ECOSYSTEMES FO RESTIERS DE LA ZONE LITTO RALE DU TOGO 87 / Recrutement de consult ant individuel génie electro- Component 2: Strengthening mécanique pour le contrôles Individual Consult TF / A7130 the Policy and Institutional F Post Open 18,182.00 0.00 Canceled 2020-04-15 2020-06-03 2020-06-24 2020-07-29 2021-01-25 des travaux d'aménagement ant Selection ramework de la cour du MEDDPN et de s bureaux de l'UGP (RDC et R +1) TG-WACA TOGO-260449-CS- INDV / recrutement d'un cons Component 3: Strengthening ultant individuel pour l'appui Individual Consult TF / A7130 National Physical and Social Post Open 35,000.00 0.00 Under Review 2022-08-23 2022-03-17 2022-10-11 2022-11-01 2022-12-06 2023-06-04 à l’aménagement des périmè ant Selection Investments tres maraichers de 04 sous p rojets communautaires TG-WACA TOGO-260444-CS- INDV / IDENTIFICATION, ELAB ORATION DES SPECIFICATION Component 3: Strengthening Individual Consult Pending Impleme S TECHNIQUES ET DETERMIN TF / A7130 National Physical and Social Post Open 27,000.00 0.00 2022-07-26 2022-08-31 2022-09-21 2022-10-26 2022-11-25 ant Selection ntation ATION DES COÛTS DES EQUI Investments PEMENTS POUR LE DEVELOP PEMENT DES FILIERES AGRIC OLES TG-WACA TOGO-222416-CS- Component 2: Strengthening Individual Consult Under Implement INDV / Etude pour la mise en IDA / D2860 the Policy and Institutional F Post Open 30,000.00 0.00 2022-08-24 2022-01-26 2022-10-13 2022-11-03 2022-12-08 2023-01-07 ant Selection ation place du MRV de la zone côti ramework ère TG-WACA TOGO-299627-CS- Component 2: Strengthening Individual Consult INDV / RÉALISATION D’UNE IDA / D2860 the Policy and Institutional F Post Open 45,000.00 0.00 Signed 2022-07-27 2022-06-06 2022-09-14 2022-10-12 2022-10-05 2022-12-23 2022-11-09 2023-05-08 ant Selection WEB CARTOGRAPHIE DU PRO ramework JET WACA ResIP TG-WACA TOGO-306645-CS- Component 3: Strengthening CDS / Actualisation de l'étud Direct - Internation IDA / 62130 National Physical and Social Post Direct Selection 110,000.00 0.00 Signed 2022-09-30 2022-09-13 2022-10-10 2022-09-14 2022-12-05 2023-02-03 e de faisabilité technique de l al Investments a protection côtière: tronçon Agbodrafo-Gbodjomé TG-WACA TOGO-306628-CS- CDS / Actualisation de l'étud Component 3: Strengthening Direct - Internation e d'impact environnemental IDA / 62130 National Physical and Social Post Direct Selection 120,000.00 0.00 Signed 2022-09-30 2022-09-28 2022-10-10 2022-09-12 2022-12-05 2023-03-05 al et social du tronçon Agbodraf Investments o-Gbodjomé et élaboration d u PAR TG-WACA TOGO-332877-CS- INDV / ELABORATION DE L’A DDENDUM AU PLAN D’ACTIO Component 3: Strengthening NS DE RÉINSTALLATION (PAR Individual Consult Pending Impleme IDA / 62130 National Physical and Social Post Limited 30,000.00 0.00 2023-01-24 2023-01-29 2023-02-19 2023-03-26 2023-09-22 ) DES PERSONNES AFFECTÉE ant Selection ntation Investments S DANS LE CADRE DES TRAV AUX DE PROTECTION DU SEG MENT DE CÔTE SITUE ENTRE AGBODRAFO ET ANEHO TG-WACA TOGO-223541-CS- INDV / Actualisation du plan Component 2: Strengthening Individual Consult d’action pour le développem IDA / D2860 the Policy and Institutional F Post Open - National 27,273.00 0.00 Signed 2021-05-28 2022-05-09 2021-07-16 2022-12-23 2021-08-06 2022-12-23 2021-09-10 2021-10-10 ant Selection ent et l’adaptation aux chang ramework ements climatiques du littora l togolais TG-WACA TOGO-346060-CS- Component 2: Strengthening INDV / REALISATION DE L'ET Individual Consult Under Implement TF / A7130 the Policy and Institutional F Post Open - National 13,000.00 0.00 2023-05-30 2023-05-02 2023-07-18 2023-08-08 2023-09-12 2024-03-10 UDE DE SATISFACTION DES B ant Selection ation ramework ENEFICAIRES DU PROJET WA CA ResIP TG-WACA TOGO-355432-CS- Component 3: Strengthening INDV / élaboration d'une stra Individual Consult Under Implement IDA / D2860 National Physical and Social Post Open - National 60,000.00 0.00 2023-05-15 2022-10-10 2023-07-03 2023-07-24 2023-08-28 2024-02-24 tégie de développement sobr ant Selection ation Investments e en carbone et résilience au CC TG-WACA TOGO-356038-CS- Component 3: Strengthening INDV / Réalisation de l'EIES si Individual Consult Pending Impleme IDA / 62130 National Physical and Social Post Limited 30,000.00 0.00 2023-05-30 2023-06-04 2023-06-25 2023-07-30 2024-01-26 mplifié des activités du sous ant Selection ntation Investments projet d'AGR pilote noix de C oco 50 / Etude pour la mise en pl ace du système national d'inf Component 2: Strengthening ormations côtières (Définitio Individual Consult IDA / D2860 the Policy and Institutional F Post Open 70,000.00 0.00 Canceled 2019-04-02 2019-06-05 2019-05-21 2019-06-11 2019-07-16 2020-01-12 n et harmonisation des stand ant Selection ramework ards de collecte, traitement e t diffusion de données pour l' observatoire) 106 / Recrutement d'un cons ultant pour la réalisation de l' EIES du projet d'assainissem Component 3: Strengthening Individual Consult ent des eaux usées à la plag IDA / D2860 National Physical and Social Post Open 50,000.00 0.00 Canceled 2020-06-02 2020-11-11 2020-07-21 2020-08-11 2020-09-15 2021-01-15 ant Selection e de Lomé, réhabilitation du r Investments éseau embryonnaire d'assain issement collectif des eaux u sées de la ville de Lomé-Tog o Page 9 TG-WACA TOGO-276167-CS- Component 2: Strengthening INDV / Appui à la révision de Individual Consult IDA / D2860 the Policy and Institutional F Post Open 20,000.00 0.00 Canceled 2022-07-15 2022-09-02 2022-09-23 2022-10-28 2023-04-26 la loi cadre sur l'environnem ant Selection ramework ent et l'élaboration de ses te xtes d'application Page 10 PROCUREMENT PLAN (Textual Part) Project information: Caribbean Region, Caribbean Digital Transformation Program, P171528 Project Implementation agency: Organisation of Eastern Caribbean States (OECS) Date of the Procurement Plan: November 11, 2020. Period covered by this Procurement Plan: The whole project life. Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: The implementing agency is not a national state; hence, there is not a national market and there are no national procurement regulations. This notwithstanding, the implementing agency’s procurement procedures (OECS Procurement Manual Revised June 2016) were found acceptable to the Bank and therefore they may be applied for the Procurement of Works, Goods and Non-consulting Services below the mandatory thresholds for international competition (as specified in the Procurement Plan tables in STEP). These procurements should be in accordance with paragraph 5.3, 5.4 and 5.5 of the Procurement Regulations.. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: not applicable Procurement of Second-Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – not applicable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: not applicable; Works: not applicable Other Relevant Procurement Information: The Implementing Agency will proceed with advance contracting in the amount of not exceeding SDR1,180,000.- (US$1.600,000.- equivalent) in accordance with the provisions of paragraph 5.1 – 5.2 of the Procurement Regulations. PROCUREMENT Caribbean : Caribbean Digital Transformation Project PLAN General Information Country: Caribbean 2021-03-24 Bank’s Approval Date of the Original Procurement Plan: 2023-06-05 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P171528 GPN Date: 2021-10-11 Project Name: Caribbean Digital Transformation Project Loan / Credit No: IDA / 66820 Department of Public Service Executing Agency(ies): WORKS Activity Reference No. / Procureme Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH Ri Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method nt Docume ount (US$ and Recommendation Signed Contract o. h cess (Y/N) sk atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion nt Type ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SLU_CARDTP_W_RFQ_1 / Sit Digital Government Infrastru Other (with fi e preparation and civil works Request for Quota Single Stage - One E 2022-12-1 IDA / 66820 cture, Platforms and Service Post Open - National eld for expla 0.00 Canceled 2022-07-20 2022-09-14 for foundation of the 40ft con tions nvelope 3 s nation) tainer to establish a Containe rized Datacenter. GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SLU_CARDTP_G_RFB_10 / Te Digital Skills and Technology Open - Internationa Single Stage - One E Pending Impl chnology Adoption and Innov IDA / 66820 Post Request for Bids 0.00 2023-02-02 2023-02-07 2023-03-21 2023-04-20 2023-05-25 2023-11-21 Adoption l nvelope ementation ation (Balance) SLU_CARDTP_G_RFB_8 / Bulk disbursements digitization to support the upgrading of fina Digital Government Infrastru Open - Internationa Single Stage - One E Pending Impl ncial infrastructure (payment IDA / 66820 cture, Platforms and Service Post Request for Bids 0.00 2022-12-15 2022-12-20 2023-01-31 2023-03-02 2023-04-06 2023-10-03 l nvelope ementation settlement), operational cons s iderations, policy modificatio ns, and monitoring and evalu ation SLU_CARDTP_G_RFB_3 / Proc urement of digital devices an Digital Government Infrastru d associated digital content t Open - Internationa Single Stage - One E IDA / 66820 cture, Platforms and Service Post Request for Bids 0.00 Canceled 2021-10-25 2021-10-11 2021-10-28 2021-11-27 2021-12-27 2022-01-16 2022-04-16 o access among Grade 6 and l nvelope s Form 1 for remote learning b y students, SALCC & Civil Se rvants SLU_CARDTP_G_RFB_3R / Pr ocurement of digital devices Digital Government Infrastru and associated digital conten Single Stage - One E IDA / 66820 cture, Platforms and Service Post Request for Bids Open - National 1,843,845.32 Signed 2021-10-11 2021-10-16 2021-11-27 2021-11-10 2021-12-27 2022-01-17 2022-03-27 2022-03-31 2022-06-25 t to access among Grade 6 a nvelope s nd Form 1 for remote learnin g by students, SALCC & Civil Servant SLU_CARDTP_G_RFB_5 / Sup Digital Enabling Environmen Open - Internationa Single Stage - One E ply and Installation of Cybers IDA / 66820 Post Request for Bids 0.00 Canceled 2022-06-30 2022-07-05 2022-08-16 2022-09-15 2022-10-20 2023-04-18 t l nvelope ecurity System SLU_CARDTP_G_RFB_1 / Pha se 1: Supply, Refurbishment and Retrofitting of a 40ft con tainer to establish a Containe Digital Government Infrastru Open - Internationa Single Stage - One E Pending Impl rized Datacenter to host a Di IDA / 66820 cture, Platforms and Service Post Request for Bids 0.00 2023-04-15 2023-04-20 2023-06-01 2023-07-01 2023-08-05 2024-02-01 l nvelope ementation giGov Platform, through a Tu s rnkey solution. Phase 2: Supply and Installat ion of Equipment to establish a Containerized Datacenter SLU_CARDTP_G_RFQ_7 / Upg Digital Skills and Technology Request for Quota Open - Internationa Single Stage - One E Under Imple rading of approximately 20 C IDA / 66820 Post 0.00 2022-12-20 2023-02-08 2023-03-29 2023-07-27 Adoption tions l nvelope mentation lassrooms to smart classroo ms SLU_CARDTP_G_RFB_4 / Soft Digital Skills and Technology Open - Internationa Single Stage - One E Pending Impl ware Development Platform t IDA / 66820 Post Request for Bids 0.00 2023-09-15 2023-09-20 2023-10-20 2023-11-19 2023-12-24 2024-06-21 Adoption l nvelope ementation o facilitate Virtual Learning SLU_CARDTP_G_RFB_7 / Sup Digital Government Infrastru Open - Internationa Single Stage - One E Pending Impl ply and Installation of Health IDA / 66820 cture, Platforms and Service Post Request for Bids 0.00 2023-09-19 2023-09-24 2023-11-05 2023-12-05 2024-01-09 2024-07-07 l nvelope ementation Surveillance and Tracking Sy s stem LC-DPS-326309-GO-RFB / Su Digital Skills and Technology Open - Internationa Single Stage - One E Pending Impl pply and Installation of SALC IDA / 66820 Post Request for Bids 0.00 2022-12-16 2022-12-21 2023-02-01 2023-03-03 2023-04-07 2023-10-04 Adoption l nvelope ementation C Innovation Lab SLU_CARDTP_G_RFB_12 / Di Digital Government Infrastru gital infrastructure strengthe Open - Internationa Single Stage - One E IDA / 66820 cture, Platforms and Service Prior Request for Bids 0.00 Canceled 2022-09-02 2022-09-07 2022-10-19 2022-11-18 2022-12-23 2023-06-21 ning and Continuity of Gover l nvelope s nment Operations (Balance) SLU_CARDTP_G_RFB_6 / Cyb Digital Enabling Environmen Open - Internationa Single Stage - One E ersecurity, Data Protection a IDA / 66820 Post Request for Bids 0.00 Canceled 2022-06-30 2022-07-05 2022-08-16 2022-09-15 2022-10-20 2023-04-18 t l nvelope nd Privacy (Balance) LC-DPS-326899-GO-RFB / Pr Digital Government Infrastru Open - Internationa Single Stage - One E Pending Impl ocurement of an e-Land Regi IDA / 66820 cture, Platforms and Service Post Request for Bids 0.00 2023-06-13 2023-06-18 2023-07-30 2023-08-29 2023-10-03 2024-03-31 l nvelope ementation stry System s LC-DPS-336825-GO-DIR / Pur chase of Microsoft Office 201 Digital Government Infrastru 6 for installation on the four IDA / 66820 cture, Platforms and Service Post Direct Selection Direct - National 0.00 Canceled 2023-01-31 2023-05-24 2023-02-05 2023-02-10 2023-03-12 2023-09-08 hundred and Fifty (450) Lapt s ops purchased for Public Ser vants LC-DPS-365681-GO-RFQ / Pu rchase of Microsoft Office 20 Digital Government Infrastru Request for Quota Single Stage - One E Under Imple 21 for installation on the four IDA / 66820 cture, Platforms and Service Post Limited 0.00 2023-04-25 2023-06-20 2023-09-18 tions nvelope mentation hundred and Fifty (450) Lapt s ops purchased for Public Ser vants NON CONSULTING SERVICES Page 1 Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SLU_CARDTP_G_RFB_9 / Ref Digital Skills and Technology Open - Internationa Single Stage - One E Pending Impl IDA / 66820 Post Request for Bids 0.00 2023-11-17 2023-11-22 2024-01-03 2024-02-02 2024-03-08 2024-09-04 urbishment of co-working sp Adoption l nvelope ementation ace SLU_CARDTP_G_RFQ_6 / Adv ertising Support for the Roll-o Digital Skills and Technology Request for Quota Single Stage - One E IDA / 66820 Post Open - National 0.00 Canceled 2022-03-02 2022-04-27 2022-06-26 ut of the IT Adoption and Pro Adoption tions nvelope ductivity measurement tool f or SME's CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SLU_CARDTP_CS_RFQ_8 / Se Digital Government Infrastru Consultant Qualifi Open - Internationa Pending Impleme ctor-specific Digital Transfor IDA / 66820 cture, Platforms and Service Post 0.00 2022-12-01 2022-12-22 2023-02-04 2023-03-06 2023-04-10 2023-10-07 cation Selection l ntation mation Strategy s SLU_CARDTP_C_IC_13 / Deliv Digital Skills and Technology Quality And Cost- Open - Internationa Pending Impleme IDA / 66820 Prior 0.00 2023-02-07 2023-02-28 2023-04-13 2023-05-11 2023-06-10 2023-07-15 2023-08-19 2024-08-18 ery of Workforce-Ready Digit Adoption Based Selection l ntation al Skills LC-DPS-326299-CS-QCBS / C onsultancy Services for the E Digital Enabling Environmen Quality And Cost- Open - Internationa Pending Impleme IDA / 66820 Prior 0.00 2023-01-09 2023-01-30 2023-03-15 2023-04-12 2023-05-12 2023-06-16 2023-07-21 2024-07-20 stablishment of a National CE t Based Selection l ntation RT and Supporting Systems LC-DPS-326303-CS-CQS / Co Digital Government Infrastru nsultancy Services for the de Consultant Qualifi Open - Internationa Pending Impleme IDA / 66820 cture, Platforms and Service Post 0.00 2023-01-09 2023-01-30 2023-03-15 2023-04-14 2023-05-19 2023-11-15 velopment of Standards for t cation Selection l ntation s he Government of Saint Luci a LC-DPS-326307-CS-CQS / Im Digital Government Infrastru Consultant Qualifi Open - Internationa Pending Impleme plementation of Open Data P IDA / 66820 cture, Platforms and Service Post 0.00 2023-01-22 2023-02-12 2023-03-28 2023-04-27 2023-06-01 2023-11-28 cation Selection l ntation rogramme s SLU_CARDTP_C_IC_16 / Digit Digital Government Infrastru al Government strategy, stan Quality And Cost- Open - Internationa IDA / 66820 cture, Platforms and Service Post 0.00 Canceled 2022-11-15 2022-12-06 2023-01-19 2023-02-16 2023-03-18 2023-04-22 2023-05-27 2024-05-26 dards, business continuity an Based Selection l s d protocols (Balance) SLU_CARDTP_C_IC_12 / Supp ort for an internship/apprenti ceship program to facilitate j Digital Skills and Technology Quality And Cost- Open - Internationa ob placements of participant IDA / 66820 Post 0.00 Canceled 2022-11-15 2022-12-06 2023-01-19 2023-02-16 2023-03-18 2023-04-22 2023-05-27 2023-11-23 Adoption Based Selection l s of the digital skills program s (under Subcomponent 3.1) including provision of Interns hip Stipends for participants LC-DPS-337263-CS-CQS / Co Digital Government Infrastru nsultancy for undertaking an Consultant Qualifi Under Implement IDA / 66820 cture, Platforms and Service Post Open - National 0.00 2023-02-06 2023-02-01 2023-02-27 2023-04-12 2023-05-12 2023-06-16 2023-09-14 d Inventory of Computer Equi cation Selection ation s pment for the Government o f Saint Lucia LC-DPS-337889-CS-QCBS / C Project Implementation Sup Quality And Cost- Open - Internationa onsultancy Services for Imple IDA / 66820 Post 0.00 Canceled 2023-02-24 2023-03-17 2023-04-30 2023-05-28 2023-06-27 2023-08-01 2023-09-05 2024-09-04 port Based Selection l mentation and Technical Sup port LC-DPS-326302-CS-CQS / Co Digital Government Infrastru nsultancy for the developme Consultant Qualifi Open - Internationa Pending Impleme IDA / 66820 cture, Platforms and Service Post 0.00 2023-03-31 2023-04-21 2023-06-04 2023-07-04 2023-08-08 2024-02-04 nt of the Business Continuity cation Selection l ntation s and Cloud Infrastructure for t he GOSL LC-DPS-345278-CS-CQS / Co nsultancy Services for the De Digital Government Infrastru Consultant Qualifi Open - Internationa Under Implement velopment of the National Br IDA / 66820 cture, Platforms and Service Post 0.00 2023-03-08 2023-06-05 2023-04-10 2023-05-24 2023-07-24 2023-08-18 2024-02-24 cation Selection l ation oadband Policy, Strategy & A s ction Plan for the Government of Saint Lucia LC-DPS-346401-CS-QCBS / C onsultancy Services for the S Digital Government Infrastru upport with the Development Quality And Cost- Open - Internationa Under Implement IDA / 66820 cture, Platforms and Service Post 0.00 2023-06-02 2023-04-17 2023-06-23 2023-05-15 2023-08-06 2023-09-03 2023-10-03 2023-11-07 2023-12-12 2025-06-12 of Technical Requirements a Based Selection l ation s nd Implementation of the e-L and Registry Information Sys tem LC-DPS-362369-CS-QCBS / C onsultancy Services for an Im Project Implementation Sup Quality And Cost- Open - Internationa Under Implement plementation Support & Tech IDA / 66820 Post 0.00 2023-05-26 2023-06-06 2023-06-16 2023-07-30 2023-08-27 2023-09-26 2023-10-31 2023-12-05 2026-06-08 port Based Selection l ation nical Advisory Firm for the Pr oject Implementation Unit INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Actual Amount Invitation to Identifie Draft Negotiated Cont Component Review Type Method Contract Type Process Status Teams of Reference Signed Contract Contract Completion Description o. h (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SLU_CARDTP_G_RFB_11 / Su pport for development of an I Digital Skills and Technology Individual Consult Pending Impleme IDA / 66820 Post Open 0.00 2022-12-15 2023-02-02 2023-02-23 2023-03-30 2023-09-26 T adoption and productivity Adoption ant Selection ntation measurement tool for SMEs ( Balance years 2-5) SLU_CARDTP_C_IC-1 / Drafti ng of Legislation for Digital P ayments, Digital Identificatio Digital Enabling Environmen Individual Consult Pending Impleme IDA / 66820 Post Open 0.00 2022-09-23 2022-11-11 2022-12-02 2023-01-06 2023-09-23 n, as well as amending existi t ant Selection ntation ng Finance Act to include Thi rd Party Transactions for Tra de Facilitation LC-DPS-208504-CS-INDV / Pr Project Implementation Sup Individual Consult IDA / 66820 Post Open 0.00 Canceled 2021-03-24 2021-09-27 2021-04-08 2021-04-13 2021-04-23 2026-04-22 ocurement Specialist port ant Selection LC-DPS-208502-CS-INDV / Pr Project Implementation Sup Individual Consult IDA / 66820 Post Open 0.00 Canceled 2021-03-22 2020-08-21 2021-04-06 2021-04-11 2021-04-21 2026-04-20 oject Manager port ant Selection LC-DPS-208501-CS-INDV / Pr Project Implementation Sup Individual Consult IDA / 66820 Post Open 0.00 Canceled 2021-03-22 2020-09-24 2021-05-10 2021-05-31 2021-07-05 2022-01-01 oject Manager port ant Selection Page 2 LC-DPS-208503-CS-INDV / Pr Project Implementation Sup Individual Consult IDA / 66820 Post Open 0.00 Canceled 2021-03-24 2020-08-21 2021-05-12 2021-06-02 2021-07-07 2022-01-03 ocurement Specialist port ant Selection SLU_CARDTP_C_IC_18 / Fina Project Implementation Sup Individual Consult IDA / 66820 Post Open 108,000.00 Signed 2022-03-13 2022-03-21 2022-04-21 2022-06-08 2022-05-12 2022-06-09 2022-05-31 2022-06-25 2025-05-30 nce Officer port ant Selection SLU_CARDTP_C_IC_2 / Techn Digital Government Infrastru ical Consultant to support th Individual Consult IDA / 66820 cture, Platforms and Service Post Open 0.00 Canceled 2022-05-27 2022-06-29 2022-07-20 2022-08-24 2022-09-24 e development of the TOR fo ant Selection s r the Broadband Policy and S trategy SLU_CARDTP_C_IC_4 / Techn ical Consultant to support th Digital Government Infrastru Individual Consult e development of the TOR fo IDA / 66820 cture, Platforms and Service Post Open 0.00 Canceled 2022-07-29 2022-08-31 2022-09-21 2022-10-26 2022-11-26 ant Selection r the Development of a Conti s nuity Plan for the GOSL LC-DPS-326059-CS-INDV / A Project Implementation Sup Individual Consult IDA / 66820 Post Open - National 0.00 Canceled 2022-11-27 2022-12-05 2023-01-05 2023-01-26 2023-03-02 2026-03-01 dministrative Assistant port ant Selection LC-DPS-326060-CS-INDV / Tr Project Implementation Sup Individual Consult Open - Internationa IDA / 66820 Post 0.00 Signed 2022-12-01 2022-12-05 2023-01-09 2023-04-25 2023-01-30 2023-04-26 2023-03-06 2026-03-05 aining Officer port ant Selection l LC-DPS-326062-CS-INDV / E Project Implementation Sup Individual Consult Under Implement IDA / 66820 Post Open - National 0.00 2023-01-03 2023-02-13 2023-02-11 2023-03-04 2023-04-08 2023-10-05 nvironmental and Social Offic port ant Selection ation er LC-DPS-326298-CS-INDV / R Digital Government Infrastru Individual Consult Open - Internationa Pending Impleme eclassification and Job Evalua IDA / 66820 cture, Platforms and Service Post 0.00 2023-01-23 2023-03-03 2023-03-24 2023-04-28 2023-10-25 ant Selection l ntation tion of ICT Positions within G s OSL SLU_CARDTP_C_IC_14 / Deve Digital Enabling Environmen Individual Consult lopment of CERT National CE IDA / 66820 Post Open 0.00 Canceled 2022-03-31 2022-05-19 2022-06-09 2022-07-14 2023-01-10 t ant Selection RT Roadmap SLU_CARDTP_C_IC_15 / Supp ort for CERT human capacity Digital Enabling Environmen Individual Consult IDA / 66820 Prior Open 0.00 Canceled 2022-04-01 2022-05-20 2022-06-10 2022-07-15 2023-01-11 including support for hiring of t ant Selection CERT manager and analysts; SLU_CARDTP_CS_RFQ_7 / Su Digital Enabling Environmen Individual Consult pport for Development of Nat IDA / 66820 Prior Open 0.00 Canceled 2022-09-16 2022-11-04 2022-11-25 2022-12-30 2023-06-28 t ant Selection ional Cybersecurity Capabilit y LC-DPS-326300-CS-INDV / C Digital Government Infrastru onsultancy Services for the D Individual Consult Open - Internationa IDA / 66820 cture, Platforms and Service Post 0.00 Canceled 2022-12-01 2023-01-19 2023-02-09 2023-03-16 2023-09-12 evelopment of the Broadban ant Selection l s d Policy and Strategy SLU_CARDTP_C_IC_5 / Consu Digital Government Infrastru ltancy Services for the Devel Individual Consult IDA / 66820 cture, Platforms and Service Post Open 0.00 Canceled 2022-03-01 2022-04-19 2022-05-10 2022-06-14 2022-12-26 opment of a Business Contin ant Selection s uity Plan for the GOSL SLU_CARDTP_C_IC_6 / Consu ltancy Services for the Prepar ation of Detailed Specificatio ns for Turnkey Solution for a Digital Government Infrastru Individual Consult containerized Datacenter to IDA / 66820 cture, Platforms and Service Post Open 0.00 Canceled 2021-10-20 2021-12-27 2021-12-08 2021-12-29 2022-02-02 2022-04-23 ant Selection host the DigiGov platform an s d associated data and servic es, and backup centralized G overnment data hosted by th e GITS and Govt Depts LC-DPS-326304-CS-INDV / C onsultancy Services for the P Digital Government Infrastru Individual Consult Open - Internationa Under Implement reparation of Detailed Specifi IDA / 66820 cture, Platforms and Service Post 0.00 2022-12-29 2023-01-24 2023-02-16 2023-03-09 2023-04-13 2023-10-10 ant Selection l ation cations for Turnkey Solution f s or a containerized Datacente r SLU_CARDTP_C_IC_9 / Procur ement of Teacher Training of Digital Skills and Technology Individual Consult digital devices and associate IDA / 66820 Post Open 0.00 Canceled 2022-06-24 2022-08-12 2022-09-02 2022-10-07 2023-02-04 Adoption ant Selection d digital content to access a mong vulnerable groups and remote learning by students LC-DPS-326308-CS-INDV / C Digital Skills and Technology Individual Consult Under Implement onsultancy to M&E Services f IDA / 66820 Post Open - National 0.00 2023-01-23 2023-04-06 2023-03-13 2023-04-03 2023-05-08 2023-11-04 Adoption ant Selection ation or Training Activities SLU_CARDTP_C_IC_8 / Delive ry of Training in accordance with Training Plan to support Digital Government Infrastru Individual Consult Open - Internationa Pending Impleme technical capacity developm IDA / 66820 cture, Platforms and Service Post 0.00 2023-03-30 2023-05-18 2023-06-08 2023-07-13 2023-11-20 ant Selection l ntation ent of GITS and Public Sector s Modernization Unit, CARDTP PIU Staff, ICT staff and other s as relevant SLU_CARDTP_C_IC_3 / Consu Digital Government Infrastru ltancy Services for the Devel Individual Consult IDA / 66820 cture, Platforms and Service Post Open 0.00 Canceled 2022-03-15 2021-12-27 2022-05-03 2022-05-24 2022-06-28 2023-01-09 opment of the Broadband Pol ant Selection s icy and Strategy SLU_CARDTP_C_IC_17 / Proje Project Implementation Sup Individual Consult IDA / 66820 Prior Open 0.00 Canceled 2022-09-15 2022-11-03 2022-11-24 2022-12-29 2026-06-12 ct Implementation Support port ant Selection SLU_CARDTP_C_IC_10 / Train ing Programme - Enhancing Business Productivity as part Digital Skills and Technology Individual Consult IDA / 66820 Post Open 0.00 Canceled 2022-06-24 2022-08-12 2022-09-02 2022-10-07 2022-12-21 of Protool Capacity Building A Adoption ant Selection pproach (3 Cohorts of 20 per sons per session over a 5 da y training period each) SLU_CARDTP_C_IC_7 / Under take Training and Awareness Assessment and prepare Trai Digital Government Infrastru Individual Consult ning Plan to support technica IDA / 66820 cture, Platforms and Service Post Open 0.00 Canceled 2022-08-25 2022-04-25 2022-10-13 2022-11-03 2022-12-08 2023-02-26 ant Selection l capacity development of GI s TS and Public Sector Moderni zation Unit, CARDTP PIU Staff , ICT staff and others as rele vant SLU_CARDTP_C_IC_11 / Capa Digital Government Infrastru Individual Consult city building of public sector I IDA / 66820 cture, Platforms and Service Prior Open 0.00 Canceled 2022-07-17 2022-09-04 2022-09-25 2022-10-30 2023-04-28 ant Selection T professionals and civil serv s ants Page 3 LC-DPS-208506-CS-INDV / Pr Project Implementation Sup Individual Consult IDA / 66820 Post Open - National 0.00 Signed 2021-04-19 2021-06-07 2021-02-16 2021-06-28 2021-04-14 2021-08-02 2022-01-29 ocurement Specialist port ant Selection LC-DPS-208505-CS-INDV / Pr Project Implementation Sup Individual Consult Open - Internationa IDA / 66820 Post 0.00 Signed 2021-04-19 2021-06-07 2021-02-16 2021-06-28 2021-04-14 2021-08-02 2022-01-29 oject Coordinator port ant Selection l LC-DPS-326635-CS-CDS / Su Digital Skills and Technology IDA / 66820 Post Direct Selection Direct - National 0.00 Canceled 2022-12-01 2022-12-05 2022-12-11 2023-02-14 2023-08-13 pport for Pro-Tool TrainingPro Adoption gramme Page 4 PROCUREMENT PLAN General 1. Project Information a. Country: Federal Republic of Somalia b. Project Name: Somalia Crisis Recovery Project c. Project Number: P173315 d. Total Finance: USD 137.5 Million 2. Project Implementation Agency: Ministry of Finance, FGS 3. Date of Project Plan: July 2020 4. Period Covered by this Procurement: July-2020 I. Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016 revised November 2017 and August 2018) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. II. Bank’s Standard Procurement Document: The Bank’s standard Procurement Documents shall be used for all contracts subject to international competitive procurement and those contracts as specified into Procurement Plan tables in STEP III. National Procurement Arrangements: Not applicable IV. Prequalification: Not applicable V. Leased Assets: Not Applicable VI. Procurement of Second hand Goods: Not Applicable VII. Domestic Preference: Not Applicable 1 VIII. Hands on Expanded Implementation Support (HEIS): Not Applicable IX. Other Relevant Procurement Information: Not Applicable X. Thresholds for Procurement Approaches and Method (US$ millions) Procurement Methods (US$ millions)–Goods, Works, and Non- Consulting Services Category Open Open Request for International National Quotation (RfQ) Works ≥ 5.0 <5.0 ≤ 0.2 Goods, IT, and non- ≥ 0.5 <0.5 ≤ 0.1 consulting services Thresholds for Procurement Approaches and Methods (US$, millions) – Consulting Services Category Short List of National Consultants Consulting Engineering and Services Construction Supervision Consultants (Firms) ≤ 0.1 ≤ 0.2 Individual Consultants n.a. n.a. 2 Consulting Services Re Contract Estimated Review Market Selecti Shortli Expected Expected f Description Cost (US$) by Bank Approach on sting Date of Date of No (Prior/Po (Open- Metho (Yes/N Bid Contract . st) National/ d o) Proposal Signatur Limited (QCBS Opening e etc.) , LCBCS , QBS, DS Social Development 70,200.00 July 16, C1 Prior Limited INDV N/A July 11, 2020 Specialist 2020 Agreement for Delivery of Outputs: Provision of Desert Locust Control, Emergency Support to 10,000,000. Direct Un July 16, C2 affected 00 Prior N/A July 9, 2020 Contracting Agency 2020 communities, and Re- establish the Desert Locust Surveillance and Control System. 10,070,20 Total 0.00 3 4 PROCUREMENT Somalia : Somalia Crisis Recovery Project PLAN General Information Country: Somalia 2020-07-09 Bank’s Approval Date of the Original Procurement Plan: 2023-06-05 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P173315 GPN Date: Project Name: Somalia Crisis Recovery Project Loan / Credit No: IDA / D6300, IDA / D8730 Federal Government of Somalia Ministry of Finance Executing Agency(ies): WORKS Activity Reference No. / Procureme Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH Ri Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method nt Docume ount (US$ and Recommendation Signed Contract o. h cess (Y/N) sk atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion nt Type ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SO-MOF-188762-CW-RFB / R ehabilitation and Reconstruct Component 2: Medium-Ter Open - Internationa Single Stage - One E Pending Imp 2021-12-1 IDA / D6300 Prior Request for Bids 0.00 2021-02-28 2021-03-05 2021-04-16 2021-05-16 2021-06-20 ion in Open River Breakages m Flood Recovery l nvelope lementation 7 along Jubba and Shabelle bas in SO-MOF-188768-CW-RFB / R Component 2: Medium-Ter Open - Internationa Single Stage - One E Pending Imp 2021-12-1 ehabilitation of flood relief ca IDA / D6300 Prior Request for Bids 0.00 2021-02-28 2021-03-05 2021-04-16 2021-05-16 2021-06-20 m Flood Recovery l nvelope lementation 7 nals of shabelle and Jubba Ri vers SO-MOF-228020-CW-RFQ / R ehabilitation of River Embank Component 2: Medium-Ter Request for Quota Single Stage - One E 2021-12-0 ments (7 Sites) in Beledweyn IDA / D6300 Prior Limited 198,109.19 Signed 2021-04-14 2021-05-10 2021-06-09 2021-05-21 m Flood Recovery tions nvelope 6 District – Somalia (Lot-1) SO-MOF-228024-CW-RFQ / R EHABILITATION OF BELEDWE Component 2: Medium-Ter Request for Quota Single Stage - One E 2021-12-0 YNE/BUNDOWEY N/KAWANKA IDA / D6300 Prior Limited 164,868.31 Signed 2021-04-14 2021-04-26 2021-06-09 2021-04-30 m Flood Recovery tions nvelope 6 /BUULADA RIVER EMBANKME NT IN BELEDWEYN DISTRICT – SOMALIA (Lot-2) SO-MOF-228026-CW-RFQ / R EHABILITATION OF BELEDWE Component 2: Medium-Ter Request for Quota Single Stage - One E 2021-12-0 YNE/XAWO IDA / D6300 Prior Limited 90,134.76 Signed 2021-04-14 2021-04-29 2021-06-09 2021-05-06 m Flood Recovery tions nvelope 6 TAKO/HORSEED RIVER EMBA NKMENT IN BELEDWEYN DIST RICT – SOMALIA (Lot-3) SO-MOF-229815-CW-RFQ / B Request for ATCH-2 (Beledwyne): REHABI Quotations - LITATION BELEDWEYN/ BULO Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2021-12-2 -KAHIN B-1 (RIGHT) AND BAL IDA / D6300 Prior Limited 159,147.00 Signed 2021-05-05 2021-05-17 2021-06-30 2021-05-21 m Flood Recovery tions nvelope (Emergency) 7 ADWEYN/BULO-KAHIN A-1 (RI SPD -Compet GHT) RIVER EMBANKMENT IN itive BELEDWEYN DISTRICT – SOM ALIA (C4) SO-MOF-229841-CW-RFQ / B Request for ATCH-2 (Beledwyne): REHABI Quotations - LITATION OF CEELKA TOWFIQ Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2021-12-2 (BEERTA HUSEEN DHEERE) A IDA / D6300 Prior Limited 62,680.00 Signed 2021-05-03 2021-05-17 2021-06-28 2021-05-21 m Flood Recovery tions nvelope (Emergency) 5 ND HELO KILIYO TO HOODLE SPD -Compet Y RIVER EMBANKMENT IN BE itive LEDWEYN DISTRICT – SOMALI A (C5) SO-MOF-229843-CW-RFQ / B atch-2 (Beledwyne): REHABIL Request for ITATION OF BELEDWEYN/DHA Quotations - RKEYNTA 1, BELEDWEYN/DH Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2021-12-2 IDA / D6300 Prior Limited 181,262.94 Signed 2021-05-03 2021-05-17 2021-06-28 2021-05-21 ARKEYNTA 2, BELEDWEYN/S m Flood Recovery tions nvelope (Emergency) 5 HINIILE 1, AND BALADWEYN/ SPD -Compet SHINIILE 2 RIVER EMBANKME itive NT IN BELEDWEYN DISTRICT – SOMALIA (C7) SO-MOF-229844-CW-RFQ / B atch-2 (Beledwyn): REHABILI Request for TATION OF BELEDWEYNE/ DO Quotations - OLOGAAL (BEERTA CIILOW) Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2021-12-2 IDA / D6300 Prior Limited 239,419.76 Signed 2021-05-03 2021-05-17 2021-06-28 2021-05-21 (LEFT), BELEDWEYNE/XUBEE m Flood Recovery tions nvelope (Emergency) 5 Y 2, BELEDWEYNE/ XUBEEY 3 SPD -Compet AND BEBELEDWEYNE/XUBEE itive Y 4 RIVER EMBANKMENT IN B ELEDWEYN DISTRICT – SOMA LIA (C8) SO-MOF-229845-CW-RFQ / B Request for atch-2 (Beledwyn): REHABILI Quotations - TATION OF BELEDWEYNE/XU Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2021-12-2 IDA / D6300 Prior Limited 155,960.80 Signed 2021-05-03 2021-06-06 2021-06-28 2021-06-11 BEEY 6 AND BELEDWEYNE / m Flood Recovery tions nvelope (Emergency) 5 XUBEEY 8 RIVER EMBANKME SPD -Compet NT IN BELEDWEYN DISTRICT itive – SOMALIA (C9) SO-MOF-229846-CW-RFQ / B atch-2 (Beledwyn): REHABILI TATION OF DAMALAW/XURIY Request for E1, / SIIGAALOW/ KALIAGA Y Quotations - UUSUF A, BELEDWEYNE/ SIIG Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2021-12-2 IDA / D6300 Prior Limited 172,386.28 Signed 2021-05-03 2021-06-06 2021-06-28 2021-06-11 AALOW / KALIAGA YUUSUF B, m Flood Recovery tions nvelope (Emergency) 5 BELEDWEYN/BEERATA MOHA SPD -Compet MED SALAAD 1, AND BELED itive WEYN/BEERATA MOHAMED S ALAAD 2 RIVER EMBANKMEN T IN BELEDWEYN DISTRICT –( C10) SO-MOF-229847-CW-RFQ / B atch-2 (Beledwyn): REHABILI TATION OF BELEDWEYNE/CE Request for ELKA TAWFIIQ/ BEERTA HUSE Quotations - EN DHEERE1, BELEDWEYNE/ Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2021-12-2 IDA / D6300 Prior Limited 153,159.44 Signed 2021-05-03 2021-06-06 2021-06-28 2021-06-11 LAANTA HILAAC/KALIGA ABDI m Flood Recovery tions nvelope (Emergency) 5 GARAAD, BELEDWEYNE/ BER SPD -Compet DAHA/RADERKA/HILO BARDO itive 1AND BELEDWEYNE/ BERDA HA/RADERKA/HILO BARDO 2 RIVER EMBANKMENT ( C11) SO-MOF-229848-CW-RFQ / B Request for atch-2 (Beledwyn): REHABILI Quotations - TATION OF BLEDWEYNE/HAA Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2021-12-2 WOTAKOBALADWEYN-4 (LEF IDA / D6300 Prior Limited 152,241.50 Signed 2021-05-03 2021-06-06 2021-06-28 2021-06-11 m Flood Recovery tions nvelope (Emergency) 5 T) AND BELEDWEYNE/BILIS D SPD -Compet IID 2 RIVER EMBANKMENT IN itive BELEDWEYN DISTRICT – SOM ALIA (C12) Page 1 SO-MOF-229849-CW-RFQ / B Request for atch-2 (Beledwyn): REHABILI Quotations - TATION OF BELEDWEYN/ QO Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2021-12-2 OQANE, BELELDWAYN/XAWO IDA / D6300 Prior Limited 161,580.00 Signed 2021-05-03 2021-06-06 2021-06-28 2021-06-11 m Flood Recovery tions nvelope (Emergency) 5 TAKO, /BELEDWEYN/BILISDII SPD -Compet D 1 RIVER EMBANKMENT IN B itive ELEDWEYN DISTRICT – SOMA LIA (C13) Request for SO-MOF-229852-CW-RFQ / B Quotations - atch-1 (Jowhar): Rehabilitatio Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2022-01-2 IDA / D6300 Prior Limited 170,543.80 Signed 2021-06-05 2021-05-10 2021-07-31 2021-05-19 n of River Embankments (Jow m Flood Recovery tions nvelope (Emergency) 7 har/Magadley 2) - C2 SPD -Compet itive Request for SO-MOF-229853-CW-RFQ / B Quotations - atch-1 (Jowhar): Rehabilitatio Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2022-01-2 IDA / D6300 Prior Limited 150,315.00 Signed 2021-06-05 2021-05-10 2021-07-31 2021-05-19 n of River Embankments (Jow m Flood Recovery tions nvelope (Emergency) 7 har/gafaay 1) - C3 SPD -Compet itive Request for SO-MOF-229857-CW-RFQ / B Quotations - atch-1 (Jowhar): Rehabilitatio Component 2: Medium-Ter Request for Quota Single Stage - One E 2022-01-2 IDA / D6300 Prior Limited Small Works 96,958.00 Signed 2021-06-05 2021-05-10 2021-07-31 2021-05-19 n of River Embankments (Jow m Flood Recovery tions nvelope 7 (Emergency) har/Sabuun) - C7 SPD -Compet itive Request for SO-MOF-229860-CW-RFQ / B Quotations - atch-1 (Jowhar): Rehabilitatio Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2022-01-2 IDA / D6300 Prior Limited 140,354.00 Signed 2021-06-05 2021-05-10 2021-07-31 2021-05-19 n of River Embankments (Jow m Flood Recovery tions nvelope (Emergency) 7 har/Buulo haji) - C10 SPD -Compet itive SO-MOF-229842-CW-RFQ / B Request for ATCH-2 (Beledwyne): REHABI Quotations - LITATION OF BALADWEYN/BU Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2022-01-0 ULO KAHIN 2, BALADWEYN /B IDA / D6300 Prior Limited 198,329.46 Signed 2021-05-15 2021-06-07 2021-07-10 2021-06-18 m Flood Recovery tions nvelope (Emergency) 6 UULO KAHIN 3 AND BALADW SPD -Compet EYN/BUULO KAHIN 4RIVER E itive MBANKMENT IN BELEDWEYN DISTRICT – SOMALIA (C6) Request for SO-MOF-229854-CW-RFQ / B Quotations - atch-1 (Jowhar): Rehabilitatio Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2022-01-0 IDA / D6300 Prior Limited 162,610.60 Signed 2021-05-16 2021-06-14 2021-07-11 2021-06-18 n of River Embankments (Jow m Flood Recovery tions nvelope (Emergency) 7 har/gafaay 2) - C4 SPD -Compet itive Request for SO-MOF-229856-CW-RFQ / B Quotations - atch-1 (Jowhar): Rehabilitatio Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2022-01-0 IDA / D6300 Prior Limited 172,125.85 Signed 2021-05-15 2021-06-14 2021-07-10 2021-06-20 n of River Embankments (Jow m Flood Recovery tions nvelope (Emergency) 6 har/Geedo Barkan 2 & Buulo SPD -Compet Ahmed) C6 itive Request for SO-MOF-229855-CW-RFQ / B Quotations - atch-1 (Jowhar): Rehabilitatio Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2022-01-0 IDA / D6300 Prior Limited 185,812.00 Signed 2021-05-16 2021-06-14 2021-07-11 2021-06-20 n of River Embankments (Jow m Flood Recovery tions nvelope (Emergency) 7 har/Geedo Barkan 1) - C5 SPD -Compet itive Request for B SO-MOF-235315-CW-RFB / S ids - Small W Component 5: Contingent Single Stage - One E 2022-05-1 upply and Installation of Sola IDA / D6300 Prior Request for Bids Open - National orks SPD (1 e 0.00 Canceled 2021-07-31 2021-08-05 2021-09-16 2021-10-16 2021-11-20 Emergency Response nvelope 9 r panels to hospitals (Martini nvelope proc & Banadir) ess) Request for SO-MOF-229850-CW-RFQ / B Quotations - atch-2 (Beledwyn): REHABILI Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2021-12-2 TATION OF BELEDWEYN/HOO IDA / D6300 Prior Limited 0.00 Canceled 2021-05-03 2021-06-28 m Flood Recovery tions nvelope (Emergency) 5 DLEY RIVER EMBANKMENT IN SPD -Compet BELEDWEYN DISTRICT – SOM itive ALIA (C4) Request for SO-MOF-238412-CW-RFQ / B Quotations - ardhere: Rehabilitation of Riv Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works Under Imple 2022-02-2 IDA / D6300 Prior Limited 0.00 2021-07-05 2021-10-19 2021-08-30 er Embankments Shimbiro ea m Flood Recovery tions nvelope (Emergency) mentation 6 st, Baardhere District – Soma SPD -Compet lia (C1) itive Request for SO-MOF-238415-CW-RFQ / B Quotations - aardhere: Rehabilitation of Ri Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2022-02-2 IDA / D6300 Prior Limited 156,525.00 Signed 2021-07-05 2021-10-27 2021-08-30 2022-03-08 ver Embankments Bandar 2, m Flood Recovery tions nvelope (Emergency) 6 Baardhere District – Somalia SPD -Compet (C2) itive Request for SO-MOF-238416-CW-RFQ / B Quotations - aardhere: Rehabilitation of Ri Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2022-02-2 IDA / D6300 Prior Limited 151,605.00 Signed 2021-07-05 2021-10-27 2021-08-30 2022-03-08 ver Embankments Bandar 3, m Flood Recovery tions nvelope (Emergency) 6 Baardhere District – Somalia SPD -Compet (C3) itive Request for SO-MOF-238417-CW-RFQ / B Quotations - aardhere: Rehabilitation of Ri Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works Under Imple 2022-02-2 ver Embankments Hilo banee IDA / D6300 Prior Limited 0.00 2021-07-05 2021-10-19 2021-08-30 m Flood Recovery tions nvelope (Emergency) mentation 6 d 1 and Hilo baneed 2, Baard SPD -Compet here District – Somalia (C4) itive Request for SO-MOF-238418-CW-RFQ / B Quotations - aardhere: Rehabilitation of Ri Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2022-02-2 IDA / D6300 Prior Limited 152,534.20 Signed 2021-07-05 2021-10-19 2021-08-30 2022-03-08 ver Embankments Hilo banee m Flood Recovery tions nvelope (Emergency) 6 d 3, Baardhere District – Som SPD -Compet alia (C5) itive Request for SO-MOF-238419-CW-RFQ / B Quotations - aardhere: Rehabilitation of Ri Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2022-02-2 IDA / D6300 Prior Limited 177,395.00 Signed 2021-07-05 2021-10-27 2021-08-30 2022-03-08 ver Embankments Hilo banee m Flood Recovery tions nvelope (Emergency) 6 d 6, Baardhere District – Som SPD -Compet alia (C6) itive Request for SO-MOF-238421-CW-RFQ / B Quotations - aardhere: Rehabilitation of Ri Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2022-02-2 ver Embankments Bandar 1, IDA / D6300 Prior Limited 136,540.00 Signed 2021-07-05 2021-10-27 2021-08-30 2022-03-08 m Flood Recovery tions nvelope (Emergency) 6 Bulo cesan 1 and Bulo-cesan SPD -Compet 2, Baardhere District – Somal itive ia (C7) Request for SO-MOF-235264-CW-RFQ / A Quotations - fgoye: Rehabilitation of River Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2022-02-2 IDA / D6300 Post Limited 0.00 Canceled 2021-07-05 2021-08-30 Embankments Daaf bari 1 in m Flood Recovery tions nvelope (Emergency) 6 Agooye District – Somalia (C1 SPD -Compet 1) itive Request for SO-MOF-235233-CW-RFQ / A Quotations - fgoye: Rehabilitation of River Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2022-03-0 IDA / D6300 Post Limited 0.00 Canceled 2021-07-15 2021-09-09 Embankments (3 Sites) in Af m Flood Recovery tions nvelope (Emergency) 8 goye district – Somalia (C1) SPD -Compet itive Request for SO-MOF-235235-CW-RFQ / A Quotations - fgoye: Rehabilitation of River Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2022-03-0 IDA / D6300 Post Limited 0.00 Canceled 2021-07-15 2021-09-09 Embankments Beerta Kuwayt m Flood Recovery tions nvelope (Emergency) 8 1 in Afgoye District – Somalia SPD -Compet (C2) itive Page 2 Request for SO-MOF-235267-CW-RFQ / A Quotations - fgoye: Rehabilitation of River Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2022-02-2 Embankments Ceelka cartan/ IDA / D6300 Post Limited 0.00 Canceled 2021-07-05 2021-08-30 m Flood Recovery tions nvelope (Emergency) 6 farta baabaa hasan1 in Afgoo SPD -Compet ye District – Somalia (C13) itive Request for SO-MOF-235272-CW-RFQ / A Quotations - fgoye: Rehabilitation of River Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2022-02-2 IDA / D6300 Post Limited 0.00 Canceled 2021-07-05 2021-08-30 Embankments Raqayle 1 in A m Flood Recovery tions nvelope (Emergency) 6 fgooye District – Somalia (C1 SPD -Compet 5) itive Request for SO-MOF-235278-CW-RFQ / A Quotations - fgoye: Rehabilitation of River Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2022-02-2 IDA / D6300 Post Limited 0.00 Canceled 2021-07-05 2021-08-30 Embankments Damalay1 in A m Flood Recovery tions nvelope (Emergency) 6 fgooye District – Somalia (C1 SPD -Compet 7) itive Request for SO-MOF-235281-CW-RFQ / A Quotations - fgoye: Rehabilitation of River Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2022-02-2 IDA / D6300 Post Limited 0.00 Canceled 2021-07-05 2021-08-30 Embankments Dhagax tuurk m Flood Recovery tions nvelope (Emergency) 6 a 1 in Afgooye District – Som SPD -Compet alia (C19) itive Request for SO-MOF-235283-CW-RFQ / A Quotations - fgoye: Rehabilitation of River Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2022-02-2 IDA / D6300 Post Limited 0.00 Canceled 2021-07-05 2021-08-30 Embankments Baalguri in Af m Flood Recovery tions nvelope (Emergency) 6 gooye District – Somalia (C21 SPD -Compet ) itive Request for SO-MOF-235284-CW-RFQ / A Quotations - fgoye: Rehabilitation of River Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2022-02-2 IDA / D6300 Post Limited 0.00 Canceled 2021-07-05 2021-08-30 Embankments Beerta imaara m Flood Recovery tions nvelope (Emergency) 6 adka 1 in Afgooye District – S SPD -Compet omalia (C22) itive Request for SO-MOF-235288-CW-RFQ / A Quotations - fgoye: Rehabilitation of River Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2022-02-2 IDA / D6300 Post Limited 0.00 Canceled 2021-07-05 2021-08-30 Embankment (1 Site) in Afgo m Flood Recovery tions nvelope (Emergency) 6 ye District – Somalia (C24) SPD -Compet itive SO-MOF-238422-CW-RFQ / D ollow: Procurement of: Qansa Request for xlay,Qansaxlay/Beerta Aadan Quotations - Modoobe 1, Qansaxlay/Beert Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2022-03-2 IDA / D6300 Post Limited 0.00 Canceled 2021-08-05 2021-09-30 a Aadan Modoobe 2, Dollow/ m Flood Recovery tions nvelope (Emergency) 9 Qansaxlay/Beerta osman Abd SPD -Compet ikadir1, Dollow/ Qansaxlay/B itive eerta osman Abdikadir2. In J ubba-land Somalia (C1) Request for SO-MOF-238426-CW-RFQ / D Quotations - ollow: Procurement of Lot2 i Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2022-03-2 n Dollow/ Cambaha/ Dhuma IDA / D6300 Post Limited 0.00 Canceled 2021-08-05 2021-09-30 m Flood Recovery tions nvelope (Emergency) 9 dhumay1/ Dhumadhumay2 D SPD -Compet huudhhumy 3 of Jubaland - S itive omalia (C2) SO-MOF-238428-CW-RFQ / D Request for ollow: Procurement of: [Five Quotations - villages Dollow/Una/Beerta Z Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2022-03-2 IDA / D6300 Post Limited 0.00 Canceled 2021-08-05 2021-09-30 akaria Abdirashid1, Dollow/U m Flood Recovery tions nvelope (Emergency) 9 na/Beerta Zakaria Abdirashid SPD -Compet 2 district Jubaland state of So itive malia. (C3) Request for SO-MOF-238430-CW-RFQ / D Quotations - ollow: Procurement of: Five v Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2022-03-2 illages in Dollow/Una/Hilo, Un IDA / D6300 Post Limited 0.00 Canceled 2021-08-05 2021-09-30 m Flood Recovery tions nvelope (Emergency) 9 a/Beerta Abdi dool and Una/B SPD -Compet eerta Abdikawi mohamed (C itive 4) Request for SO-MOF-238431-CW-RFQ / D Quotations - ollow: Procurement of: Dollo Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2022-03-2 IDA / D6300 Post Limited 0.00 Canceled 2021-08-05 2021-09-30 w/Suul Guduud/Abdiyo Abdi m Flood Recovery tions nvelope (Emergency) 9 Baale, Suul Guduud/mohame SPD -Compet d Abdullahi (C5) itive Request for SO-MOF-238432-CW-RFQ / D Quotations - ollow: Procurement of: [Suulg Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2022-03-2 udud/Ali sharif , Quracleey/K IDA / D6300 Post Limited 0.00 Canceled 2021-08-05 2021-09-30 m Flood Recovery tions nvelope (Emergency) 9 eli Dahir, Suulgudud/Adam Ib SPD -Compet rahim] in Dollow Juba land So itive malia. (C6) SO-MOF-257503-CW-RFB / Jo Request for B whar Batch 2 Works: Rehabili ids - Small W tation of River Embankment Component 2: Medium-Ter Single Stage - One E 2022-08-1 IDA / D6300 Prior Request for Bids Open - National orks SPD (1 e 0.00 Canceled 2021-10-30 2021-11-04 2021-12-16 2022-01-15 2022-02-19 at Magadley 1, Muriyaale, Gu m Flood Recovery nvelope 8 nvelope proc maray and Mareeray 1 (3 LO ess) TS) in Jowhar, Hirshabelle Sta te. Request for SO-MOF-255371-CW-RFQ / A Quotations - fgoye: Rehabilitation of River Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2022-08-1 Embankment at Beerta Kuwa IDA / D6300 Prior Limited 0.00 Signed 2021-12-20 2022-03-24 2022-02-14 m Flood Recovery tions nvelope (Emergency) 3 yt 2 site in Afgoye District, Lo SPD -Compet wer Shabelle Region - (C6) itive Request for SO-MOF-255309-CW-RFQ / A Quotations - fgoye: Rehabilitation of River Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2022-06-1 Embankments at Aytiro 1 an IDA / D6300 Post Limited 0.00 Canceled 2021-10-21 2021-12-16 m Flood Recovery tions nvelope (Emergency) 4 d Dhagaxtuurka 2 sites in Af SPD -Compet goye District, Lower Shabelle itive Region - (C1) Request for SO-MOF-255347-CW-RFQ / A Quotations - fgooye: Rehabilitation of Rive Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2022-06-1 r Embankment at Baalguri 2 IDA / D6300 Post Limited 0.00 Canceled 2021-10-21 2021-12-16 m Flood Recovery tions nvelope (Emergency) 4 site in Afgoye District, Lower SPD -Compet Shabelle Region - (C2) itive Request for SO-MOF-255357-CW-RFQ / A Quotations - fgoye: Rehabilitation of River Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2022-06-1 Embankment and Canal Intak IDA / D6300 Post Limited 0.00 Canceled 2021-10-19 2021-12-14 m Flood Recovery tions nvelope (Emergency) 2 e at Beerta Imaaraadka 1 in SPD -Compet Afgoye District, Lower Shabel itive le Region - (C3) SO-MOF-255367-CW-RFQ / A Request for fgoye: Rehabilitation of River Quotations - Embankment & Canal Intake Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2022-06-1 IDA / D6300 Post Limited 0.00 Canceled 2021-10-21 2021-12-16 Chamber at Beerta Imaaraad m Flood Recovery tions nvelope (Emergency) 4 ka 2 site in Afgoye District, L SPD -Compet ower Shabelle Region - (C4) itive Page 3 Request for SO-MOF-255369-CW-RFQ / A Quotations - fgoye: Rehabilitation of River Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2022-08-1 Embankment at Beerta Kuwa IDA / D6300 Prior Limited 0.00 Signed 2021-12-20 2022-03-24 2022-02-14 m Flood Recovery tions nvelope (Emergency) 3 yt 1 site in Afgoye District, Lo SPD -Compet wer Shabelle Region - (C5) itive Request for SO-MOF-255372-CW-RFQ / A Quotations - fgoye: Rehabilitation of River Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2022-08-1 Embankment at Beerta Kuwa IDA / D6300 Prior Limited 0.00 Signed 2021-12-20 2022-03-24 2022-02-14 m Flood Recovery tions nvelope (Emergency) 3 yt 3 site in Afgoye District, Lo SPD -Compet wer Shabelle Region - (C7) itive Request for SO-MOF-255373-CW-RFQ / A Quotations - fgoye: Rehabilitation of River Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2022-08-1 Embankment at Beerta Kuwa IDA / D6300 Prior Limited 0.00 Signed 2021-12-20 2022-03-24 2022-02-14 m Flood Recovery tions nvelope (Emergency) 3 yt 4 in Afgoye District, Lower SPD -Compet Shabelle Region - (C8) itive Request for SO-MOF-255374-CW-RFQ / A Quotations - fgoye: Rehabilitation of River Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2022-08-1 Embankment at Beerta Kuwa IDA / D6300 Prior Limited 0.00 Signed 2021-12-20 2022-03-24 2022-02-14 m Flood Recovery tions nvelope (Emergency) 3 yt 5 in Afgoye District, Lower SPD -Compet Shabelle Region - (C9) itive Request for SO-MOF-255375-CW-RFQ / A Quotations - fgoye: Rehabilitation of River Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2022-08-1 Embankment at Beerta Kuwa IDA / D6300 Prior Limited 0.00 Signed 2021-12-20 2022-03-24 2022-02-14 m Flood Recovery tions nvelope (Emergency) 3 yt 6 in Afgoye District, Lower SPD -Compet Shabelle Region - (C10) itive Request for B SO-MOF-262209-CW-RFB / R ids - Small W ehabilitation of River Embank Component 2: Medium-Ter Single Stage - One E 2022-10-0 IDA / D6300 Prior Request for Bids Open - National orks SPD (1 e 0.00 Canceled 2021-12-15 2022-05-26 2021-12-20 2022-06-05 2022-01-31 2022-07-31 2022-03-02 2022-04-06 ments at Dhagaxtuurka 2 an m Flood Recovery nvelope 3 nvelope proc d Aytiro 1 (2 Sites) in Afgoye ess) District, SWS State Request for SO-MOF-262214-CW-RFQ / A Quotations - fgoye: Rehabilitation of River Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2022-08-1 IDA / D6300 Prior Limited 0.00 Signed 2021-12-20 2022-03-24 2022-02-14 Embankment at Baalguri 2 si m Flood Recovery tions nvelope (Emergency) 3 te in Afgoye District, Lower S SPD -Compet habelle Region (C2) itive Request for SO-MOF-262215-CW-RFQ / A Quotations - fgoye: Rehabilitation of River Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2022-08-1 Embankment at Beerta Imaa IDA / D6300 Prior Limited 0.00 Signed 2021-12-20 2022-03-24 2022-02-14 m Flood Recovery tions nvelope (Emergency) 3 raakda 1 in Afgoye District, L SPD -Compet ower Shabelle Region (C3) itive Request for SO-MOF-262216-CW-RFQ / A Quotations - fgoye: Rehabilitation of River Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2022-08-1 Embankment at Beerta Imaa IDA / D6300 Prior Limited 0.00 Signed 2021-12-20 2022-03-24 2022-02-14 m Flood Recovery tions nvelope (Emergency) 3 raadka 2 in Afgoye District, L SPD -Compet ower Shabelle Region (C4) itive Request for SO-MOF-257752-CW-RFQ / D Quotations - ollow: Rehabilitation of River Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2022-06-2 IDA / D6300 Post Limited 0.00 Canceled 2021-11-04 2021-12-30 Embankment at Qansaxlay Si m Flood Recovery tions nvelope (Emergency) 8 te In Dollow District, Gedo Re SPD -Compet gion (Lot 1) itive Request for B SO-MOF-262226-CW-RFB / R ids - Small W ehabilitation of River Embank Component 2: Medium-Ter Single Stage - One E 2022-10-0 IDA / D6300 Prior Request for Bids Open - National orks SPD (1 e 0.00 Canceled 2021-12-15 2022-05-26 2021-12-20 2022-06-05 2022-01-31 2022-03-02 2022-04-06 ment (five sites) in Dollow Di m Flood Recovery nvelope 3 nvelope proc strict, Gedo Region - (2 Lots) ess) SO-MOF-257753-CW-RFQ / D Request for ollow: Rehabilitation of River Quotations - Embankment at Qansaxlay ( Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works Under Imple 2022-08-1 IDA / D6300 Prior Limited 0.00 2021-12-20 2022-03-07 2022-02-14 Beerta Aden madobe1,2 and m Flood Recovery tions nvelope (Emergency) mentation 3 Beerta osman Abdikadir1,2) i SPD -Compet n Dollow District, Gedo Regio itive n (C2) SO-MOF-257760-CW-RFQ / D Request for ollow: Rehabiliation of River Quotations - Embankment at Buulo Qaloo Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2022-08-1 IDA / D6300 Prior Limited 0.00 Signed 2021-12-20 2022-03-07 2022-02-14 2023-05-11 c (Mohamed Qase 1,2,3 and m Flood Recovery tions nvelope (Emergency) 3 Dollow/Iskudaraha Ahmed Ali SPD -Compet Qeyr) in Dollow District, Ged itive o Region (C9) Request for SO-MOF-257758-CW-RFQ / D Quotations - ollow: Rehabilitation of River Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2022-08-1 Embankment at Sulguduud ( IDA / D6300 Prior Limited 0.00 Signed 2021-12-20 2022-03-07 2022-02-14 2023-05-11 m Flood Recovery tions nvelope (Emergency) 3 Ali Sharif, Adan Ibrahim, Abdi SPD -Compet rashid, and Hassan) in Dollo itive w District, Gedo Region - (C7 ) Request for SO-MOF-257759-CW-RFQ / D Quotations - ollow: Rehabilitation of River Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2022-06-2 IDA / D6300 Post Limited 0.00 Canceled 2021-11-04 2021-12-30 Embankment at Sulguduud N m Flood Recovery tions nvelope (Emergency) 8 asteh in Dollow District, Gedo SPD -Compet Region (Lot 8) itive Request for B SO-MOF-257755-CW-RFB / R ids - Small W ehbilitation of River embank Component 2: Medium-Ter Single Stage - One E 2022-09-1 IDA / D6300 Prior Request for Bids Open - National orks SPD (1 e 0.00 Canceled 2021-11-30 2022-05-26 2021-12-05 2022-06-05 2022-01-16 2022-02-15 2022-03-22 ment (5 sites) in Dollow distri m Flood Recovery nvelope 8 nvelope proc ct, Jubaland (2 Lots) ess) Request for B SO-MOF-257754-CW-RFB / R ids - Small W ehabilitation of River Embank Component 2: Medium-Ter Single Stage - One E 2022-09-1 IDA / D6300 Prior Request for Bids Open - National orks SPD (1 e 0.00 Canceled 2021-11-30 2022-06-06 2021-12-05 2022-06-10 2022-01-16 2022-02-15 2022-03-22 ments (4 sites) in Dollow Dist m Flood Recovery nvelope 8 nvelope proc rict, Jubaland State (2 Lots) ess) Request for SO-MOF-256788-CW-RFQ / L Quotations - uuq: Rehabilitation of River E Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works Under Imple 2022-08-1 IDA / D6300 Prior Limited 0.00 2021-12-20 2022-03-24 2022-02-14 mbankment at Boyle farm 1 i m Flood Recovery tions nvelope (Emergency) mentation 3 n Luuq District, Gedo Region SPD -Compet - (C1) itive Request for SO-MOF-256790-CW-RFQ / L Quotations - uuq: Rehabilitation of River E Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2022-06-2 IDA / D6300 Post Limited 0.00 Canceled 2021-10-30 2021-12-25 mbankment at Bacaad Weyn m Flood Recovery tions nvelope (Emergency) 3 1&2 in Luuq District, Gedo Re SPD -Compet gion - (C2) itive Request for SO-MOF-256791-CW-RFQ / L Quotations - uuq: Rehabilitation of River E Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2022-08-1 IDA / D6300 Prior Limited 0.00 Signed 2021-12-20 2022-03-24 2022-02-14 2023-03-21 mbankment at Bacaadlay Far m Flood Recovery tions nvelope (Emergency) 3 m 3 in Luuq District, Gedo Re SPD -Compet gion - (C3) itive Page 4 Request for SO-MOF-256792-CW-RFQ / L Quotations - uuq: Rehabilitation of River E Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2022-08-1 IDA / D6300 Prior Limited 0.00 Canceled 2021-12-20 2022-02-14 mbankment at Bacaadlay Far m Flood Recovery tions nvelope (Emergency) 3 m 4 in Luuq District, Gedo Re SPD -Compet gion - (C4) itive SO-MOF-255593-CW-RFQ / K Request for ismayo: Rehabilitation of Riv Quotations - er Embankments at Goobwey Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2022-06-1 n (Farta school ka, Fargeelee IDA / D6300 Post Limited 0.00 Canceled 2021-10-21 2021-12-16 m Flood Recovery tions nvelope (Emergency) 4 y, Farta Garoonka and Masha SPD -Compet qo 1 & 2) and Qamqam (Maq itive ara'as 1, 2 & 3) in Kismayo T own, Jubba-land state - (C1) Request for SO-MOF-262246-CW-RFQ / K Quotations - ismayo: Rehabilitation of Riv Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2022-08-1 IDA / D6300 Prior Limited 0.00 Signed 2021-12-20 2022-03-07 2022-02-14 er Embankment In Kismayo T m Flood Recovery tions nvelope (Emergency) 3 own, Jubaland State (C1) SPD -Compet itive Request for SO-MOF-255595-CW-RFQ / K Quotations - ismayo: Rehabilitation of Riv Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2022-06-1 er Embankment at Yoontoow IDA / D6300 Post Limited 0.00 Canceled 2021-10-21 2021-12-16 m Flood Recovery tions nvelope (Emergency) 4 (Mayakondo & Shubiiro sites) SPD -Compet in Kismayo town, Jubba-land itive state (C2) Request for SO-MOF-262247-CW-RFQ / K Quotations - ismayo: Rehabilitation of Riv Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2022-08-1 IDA / D6300 Prior Limited 0.00 Signed 2021-12-20 2022-03-07 2022-02-14 er Embankment in Kismayo T m Flood Recovery tions nvelope (Emergency) 3 own, Jubaland State (C2) SPD -Compet itive Request for SO-MOF-238433-CW-RFQ / D Quotations - ollaw: Procurement of: [Five Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2022-03-2 villages in dollaw Suulgudud/ IDA / D6300 Post Limited 0.00 Canceled 2021-08-05 2021-09-30 m Flood Recovery tions nvelope (Emergency) 9 Ali sharif, Quracleey/Keli Dahi SPD -Compet r district Jubaland state of So itive malia. (C7) SO-MOF-235230-CW-RFQ / B Request for atch-3 (Beledwyn): Rehabilita Quotations - tion of Masonry Retaining Wa Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2022-03-0 ll (in Hilo Bardo, Horseed, Bal IDA / D6300 Post Limited 0.00 Canceled 2021-07-15 2021-09-09 m Flood Recovery tions nvelope (Emergency) 8 adweyn 1, Ibrahim Farm & D SPD -Compet onsubagle 5 Villages)for Floo itive d Protection in Beledweyn Di strict – Somalia (C15) Request for SO-MOF-235875-CW-RFQ / R Quotations - ehabilitation of Beledweyn/H Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2022-03-1 IDA / D6300 Post Limited 0.00 Canceled 2021-07-20 2021-09-14 oodley River Embankment in m Flood Recovery tions nvelope (Emergency) 3 Beledweyn District – Somalia SPD -Compet (C14). itive SO-MOF-266544-CW-RFB / R Request for B ehabilitation of River Embank ids - Small W Component 2: Medium-Ter Single Stage - One E 2023-01-1 ment at Magadley 1, Muriyaa IDA / D6300 Prior Request for Bids Open - National orks SPD (1 e 0.00 Canceled 2022-03-31 2022-05-26 2022-04-05 2022-06-05 2022-05-17 2022-08-06 2022-06-16 2022-07-21 m Flood Recovery nvelope 7 le, nvelope proc Gumaray and Mareeray 1 (3 ess) LOTS) in Jowhar, Hirshabelle State Request for B SO-MOF-262257-CW-RFB / R ids - Small W Component 2: Medium-Ter Open - Internationa Single Stage - One E 2023-01-1 ehabilitation of Far Libaax Ro IDA / D6300 Prior Request for Bids orks SPD (1 e 0.00 Canceled 2022-03-31 2022-05-26 2022-04-05 2022-06-05 2022-05-17 2022-07-07 2022-06-16 2022-07-21 m Flood Recovery l nvelope 7 ad (phase-I) in Beledwayne, nvelope proc Hirshabelle State ess) SO-MOF-262258-CW-RFB / L Request for B ot 1: Rehabilitation of Habala ids - Small W Component 2: Medium-Ter Single Stage - One E 2023-01-1 Adey MCH in Bardhere Distric IDA / D6300 Prior Request for Bids Open - National orks SPD (1 e 0.00 Canceled 2022-03-31 2022-05-26 2022-04-05 2022-06-05 2022-05-17 2022-06-16 2022-07-21 m Flood Recovery nvelope 7 t nvelope proc Lot 2: Rehabilitation of Horse ess) ed Health Facility in Berdere District SO-MOF-262259-CW-RFB / L Request for B ot 1: Rehabilitation of Sigaalo ids - Small W w MCH in Beldewyne District Component 2: Medium-Ter Single Stage - One E 2023-01-1 IDA / D6300 Prior Request for Bids Open - National orks SPD (1 e 0.00 Canceled 2022-03-31 2022-05-26 2022-04-05 2022-06-05 2022-05-17 2022-07-05 2022-06-16 2022-07-21 Lot 2: Rehabilitation of Haaw m Flood Recovery nvelope 7 nvelope proc o Taako Health Facility in Bal ess) edweyn District Request for B SO-MOF-276917-CW-RFB / R ids - Small W ehabilitation of 5 sites ( Kalu Component 2: Medium-Ter Single Stage - One E Under Imple 2022-12-0 IDA / D6300 Prior Request for Bids Open - National orks SPD (1 e 0.00 2022-02-20 2022-03-14 2022-02-25 2022-03-16 2022-04-08 2022-03-26 2022-05-08 2022-04-26 2022-06-12 undi 1 &2, Garaash and Moky m Flood Recovery nvelope mentation 9 nvelope proc o 1& 3) in Jowhar District ess) Request for SO-MOF-277130-CW-RFQ / C Component 5: Contingent Request for Quota Single Stage - One E Quotations ( Pending Imp 2022-11-2 onstruction of two rooms to h IDA / D6300 Prior Limited 0.00 2022-04-05 2022-05-31 Emergency Response tions nvelope Non Bank-SP lementation 7 ouse Oxygen plants in Baido D) a and Kismayo Request for SO-MOF-295717-CW-RFQ / R Component 5: Contingent Request for Quota Single Stage - One E Quotations ( Pending Imp 2023-03-0 ehabilitation of a medical wa IDA / D6300 Prior Limited 0.00 2022-07-08 2022-09-02 Emergency Response tions nvelope Non Bank-SP lementation 1 rehouse for the State of Jubal D) and Request for SO-MOF-295721-CW-RFQ / R Component 5: Contingent Request for Quota Single Stage - One E Quotations ( Pending Imp 2023-03-0 ehabilitation of a medical wa IDA / D6300 Prior Limited 0.00 2022-07-08 2022-09-02 Emergency Response tions nvelope Non Bank-SP lementation 1 rehouse for the State of Sout D) hwest Request for SO-MOF-295723-CW-RFQ / R Component 5: Contingent Request for Quota Single Stage - One E Quotations ( Pending Imp 2023-03-0 ehabilitation of a medical wa IDA / D6300 Prior Limited 0.00 2022-07-09 2022-09-03 Emergency Response tions nvelope Non Bank-SP lementation 2 rehouse for the State of Gal D) mudug Request for SO-MOF-295724-CW-RFQ / R Component 5: Contingent Request for Quota Single Stage - One E Quotations ( Pending Imp 2023-03-0 ehabilitation of a medical wa IDA / D6300 Prior Limited 0.00 2022-07-09 2022-09-03 Emergency Response tions nvelope Non Bank-SP lementation 2 rehouse for the State of Hirsh D) abelle Request for SO-MOF-295727-CW-RFQ / R Component 5: Contingent Request for Quota Single Stage - One E Quotations ( Pending Imp 2023-03-2 ehabilitation of Medical Natio IDA / D6300 Prior Limited 0.00 2022-08-05 2022-09-30 Emergency Response tions nvelope Non Bank-SP lementation 9 nal warehouse in Mogadishu D) SO-MOF-295726-CW-RFQ / R Request for ehabilitation of Medical ware Component 5: Contingent Request for Quota Single Stage - One E Quotations ( Pending Imp 2023-03-2 IDA / D6300 Prior Limited 0.00 2022-08-05 2022-09-30 house for Banadir regional ad Emergency Response tions nvelope Non Bank-SP lementation 9 ministration (BRA) D) Request for SO-MOF-295719-CW-RFQ / R Component 5: Contingent Request for Quota Single Stage - One E Quotations ( Pending Imp 2023-03-2 ehabilitation of Medical ware IDA / D6300 Prior Limited 0.00 2022-08-05 2022-09-30 Emergency Response tions nvelope Non Bank-SP lementation 9 house in Puntland State D) Request for B SO-MOF-307801-CW-RFB / R ids - Small W Component 2: Medium-Ter Single Stage - One E Under Imple 2023-06-1 ehabilitation of river embank IDA / D6300 Prior Request for Bids Open - National orks SPD (1 e 0.00 2022-08-31 2022-08-25 2022-09-05 2022-09-02 2022-10-17 2022-09-29 2022-11-16 2022-12-15 2022-12-21 m Flood Recovery nvelope mentation 9 ment (3 sites) in Luuq district nvelope proc , Jubaland State ess) Page 5 Request for B SO-MOF-307802-CW-RFB / R ids - Small W Component 2: Medium-Ter Open - Internationa Single Stage - One E Under Imple 2023-06-1 ehabilitation of Belethawa's IDA / D6300 Prior Request for Bids orks SPD (1 e 0.00 2022-08-31 2022-09-13 2022-09-05 2022-09-14 2022-10-17 2022-10-17 2022-11-16 2023-02-14 2022-12-21 m Flood Recovery l nvelope mentation 9 Dolow (2.9Km) and Elwaq (1. nvelope proc 9Km) Roads ess) Request for B SO-MOF-307803-CW-RFB / R ids - Small W ehabilitation of Hudur Main R Component 2: Medium-Ter Open - Internationa Single Stage - One E 2023-06-1 IDA / D6300 Prior Request for Bids orks SPD (1 e 0.00 Canceled 2022-08-31 2022-09-05 2022-10-17 2022-11-16 2022-12-21 oad (2.5 kilometers) and Blim m Flood Recovery l nvelope 9 nvelope proc aqasi Road (3.9 kilometers) i ess) n Hudur Request for B SO-MOF-316762-CW-RFB / R ids - Small W ehabilitation of Hudur Main R Component 2: Medium-Ter Open - Internationa Single Stage - One E Under Imple 2023-07-1 IDA / D6300 Prior Request for Bids orks SPD (1 e 0.00 2022-09-30 2022-10-04 2022-10-05 2022-11-16 2022-11-16 2022-12-17 2022-12-16 2023-03-07 2023-01-20 oad (2.5Km) and Blimaqasi R m Flood Recovery l nvelope mentation 9 nvelope proc oad (3.9Km) in Hudur district ess) , South West State Request for B SO-MOF-316766-CW-RFB / R ids - Small W ehabilitation of Dhulu Ale (3. Component 2: Medium-Ter Open - Internationa Single Stage - One E Under Imple 2023-07-1 IDA / D6300 Prior Request for Bids orks SPD (1 e 0.00 2022-09-30 2022-11-08 2022-10-05 2022-11-15 2022-11-16 2022-12-20 2022-12-16 2023-05-23 2023-01-20 5Km), Dolow (1.25Km) and B m Flood Recovery l nvelope mentation 9 nvelope proc oiya Road (4.0Km) in Luuq, Ju ess) baland State SO-MOF-316767-CW-RFB / R Request for B e-construction of Kulmis Mat ids - Small W Component 2: Medium-Ter Open - Internationa Single Stage - One E Under Imple 2023-08-0 ernal and Child Health (MCH) IDA / D6300 Prior Request for Bids orks SPD (1 e 0.00 2022-10-15 2022-11-08 2022-10-20 2022-11-15 2022-12-01 2022-12-19 2022-12-31 2023-01-31 2023-02-04 m Flood Recovery l nvelope mentation 3 Facility in Jowhar District -Hir nvelope proc shabelle State, Somalia. ess) SO-MOF-316794-CW-RFB / R Request for B e-construction of Shidley Mat Component 3: Longer-Ter ids - Small W Open - Internationa Single Stage - One E Under Imple 2023-08-0 ernal and Child Health (MCH) IDA / D6300 m Disaster Risk Preparednes Prior Request for Bids orks SPD (1 e 0.00 2022-10-15 2022-11-08 2022-10-20 2022-11-15 2022-12-01 2022-12-15 2022-12-31 2023-03-14 2023-02-04 l nvelope mentation 3 Facility in Hudur District - So s nvelope proc uth West State, Somalia. ess) Request for B SO-MOF-319819-CW-RFB / R ids - Small W ehabilitation of Far Libaax Ro Component 2: Medium-Ter Single Stage - One E Under Imple 2023-08-1 IDA / D6300 Prior Request for Bids Limited orks SPD (1 e 0.00 2022-10-31 2022-11-15 2022-11-05 2023-01-17 2022-12-17 2022-11-26 2023-01-16 2023-01-31 2023-02-20 ad (2 km) in Beledweyne, Hir m Flood Recovery nvelope mentation 9 nvelope proc shabelle State of Somalia ess) SO-MOF-319822-CW-RFB / R Request for B e-Construction of Habala Ade ids - Small W y Maternal and Child Health ( Component 2: Medium-Ter Single Stage - One E Under Imple 2023-09-1 IDA / D6300 Prior Request for Bids Limited orks SPD (1 e 0.00 2022-11-30 2022-11-15 2022-12-05 2022-12-21 2023-01-16 2022-11-27 2023-02-15 2023-03-06 2023-03-22 MCH) Facility and Re-Constru m Flood Recovery nvelope mentation 8 nvelope proc ction Horseed Healthcare Fac ess) ility, Bardere District, Jubbala nd State, Somalia SO-MOF-319827-CW-RFB / R Request for B e-construction of Sigaalow M ids - Small W aternal and Child Health (MC Component 2: Medium-Ter Single Stage - One E Under Imple 2023-08-1 IDA / D6300 Prior Request for Bids Limited orks SPD (1 e 0.00 2022-10-31 2022-11-15 2022-11-05 2022-12-21 2022-12-17 2022-11-27 2023-01-16 2023-03-06 2023-02-20 H) Facility and Haawa Taako m Flood Recovery nvelope mentation 9 nvelope proc Healthcare (HF) Facility in Be ess) ledweyne District, Hirshabell e State SO-MOF-319829-CW-RFB / R Request for B ehabilitation of river embank ids - Small W Component 2: Medium-Ter Single Stage - One E Under Imple 2023-08-1 ments at Dhagaxtuurka 2 (21 IDA / D6300 Prior Request for Bids Limited orks SPD (1 e 0.00 2022-10-31 2022-11-15 2022-11-05 2022-12-14 2022-12-17 2022-11-24 2023-01-16 2023-02-07 2023-02-20 m Flood Recovery nvelope mentation 9 0m) and Aytiro 1 (200m) Site nvelope proc s in Afgoye District, Southwe ess) st State of Somalia. SO-MOF-319831-CW-RFB / R ehabilitation of river embank ment in Dollow District, cover Request for B ing the following sites: ids - Small W Component 2: Medium-Ter Single Stage - One E Under Imple 2023-09-1 IDA / D6300 Prior Request for Bids Limited orks SPD (1 e 0.00 2022-11-30 2022-11-16 2022-12-05 2022-12-14 2023-01-16 2022-11-23 2023-02-15 2023-03-06 2023-03-22 - Lot-1: Dollow/Una (Qansa m Flood Recovery nvelope mentation 8 nvelope proc xlay (276m). ess) - Lot-2: Dollow/Una/ (Beert a Zakaria Abdirashid1 & 2 (2 05.5m) SO-MOF-319832-CW-RFB / R ehabilitation of river embank ment in Dollow District, cover Request for B ing the following sites: ids - Small W Component 2: Medium-Ter Single Stage - One E Under Imple 2023-09-1 IDA / D6300 Prior Request for Bids Limited orks SPD (1 e 0.00 2022-11-30 2022-11-15 2022-12-05 2022-12-21 2023-01-16 2022-11-23 2023-02-15 2023-03-06 2023-03-22 - LOT 1: Dollow/Sulguduud m Flood Recovery nvelope mentation 8 nvelope proc (Mudeey Ali 1,2&3 (349m) an ess) d; - LOT 2: Dollow Sulguduud/ Nasteh (196m) SO-MOF-319835-CW-RFB / R ehabilitation of river embank ment in Dollow District, cover Request for B ing the following two sites: ids - Small W Component 2: Medium-Ter Single Stage - One E Under Imple 2023-09-1 - Lot-1: Dollow/Una (Beerta IDA / D6300 m Flood Recovery Prior Request for Bids Limited nvelope orks SPD (1 e 0.00 mentation 2022-11-30 2022-11-15 2022-12-05 2022-12-21 2023-01-16 2022-11-23 2023-02-15 2023-01-31 2023-03-22 8 Abdikawi Mohamed, Beerta A nvelope proc bdi dool, and Hillo (360.2m) ess) and; - Lot-2: Doolaw/Sulguduud (Husein Ibrahim 1&2 (466m) SO-MOF-319837-CW-RFB / R ehabilitation of river embank ment sites in Jowhar District, Hirshabelle State of Somalia, Request for B consisting of the following 3 l ids - Small W Component 2: Medium-Ter Single Stage - One E Under Imple 2023-09-1 ots IDA / D6300 Prior Request for Bids Limited orks SPD (1 e 0.00 2022-11-30 2022-11-15 2022-12-05 2022-12-21 2023-01-16 2022-11-24 2023-02-15 2023-03-06 2023-03-22 m Flood Recovery nvelope mentation 8 nvelope proc Lot 1 - Jowhar/Magadley 1 (3 ess) 30m) Lot 2 - Jowhar/Muryaale & Gu mareey (460m) Lot 3- Jowhar/Mareerey 1 & Mareerey 2 (450m) Request for B SO-MOF-262240-CW-RFB / R ids - Small W ehabilitation of River Embank Component 2: Medium-Ter Single Stage - One E 2022-11-1 IDA / D6300 Post Request for Bids Open - National orks SPD (1 e 0.00 Canceled 2022-01-31 2022-02-05 2022-03-19 2022-04-18 2022-05-23 ment Bacaadlay Farm 1, 2 & m Flood Recovery nvelope 9 nvelope proc 4 in Luuq District, Gedo Regi ess) on. Request for B SO-MOF-328327-CW-RFB / R ids - Small W Component 2: Medium-Ter Open - Internationa Single Stage - One E Under Imple 2023-09-1 e-habilitation of Imbresso Ro IDA / D6300 Prior Request for Bids orks SPD (1 e 0.00 2022-12-01 2022-12-14 2022-12-06 2023-01-11 2023-01-17 2023-02-07 2023-02-16 2023-05-31 2023-03-23 m Flood Recovery l nvelope mentation 9 ad (8.4Km) in Barawe, South nvelope proc West State ess) SO-MOF-328329-CW-RFB / R Request for B e-construction of Malkariyey ids - Small W Component 2: Medium-Ter Single Stage - One E Under Imple 2023-09-2 Maternal and Child Health (M IDA / D6300 Prior Request for Bids Open - National orks SPD (1 e 0.00 2022-12-05 2022-12-14 2022-12-10 2023-01-11 2023-01-21 2023-02-06 2023-02-20 2023-04-26 2023-03-27 m Flood Recovery nvelope mentation 3 CH) Facility Belet Hawo Distri nvelope proc ct Jubbaland State, Somalia ess) Page 6 Request for B SO-MOF-328797-CW-RFB / R ids - Small W e-construction of Bulobarde Component 2: Medium-Ter Open - Internationa Single Stage - One E Under Imple 2023-10-0 IDA / D6300 Prior Request for Bids orks SPD (1 e 0.00 2022-12-20 2023-01-11 2022-12-25 2023-01-17 2023-02-05 2023-02-22 2023-03-07 2023-04-20 2023-04-11 Cholera Unit Healthcare Facil m Flood Recovery l nvelope mentation 8 nvelope proc ity in Bulobarde District Hirsh ess) abelle State, Somalia Request for B SO-MOF-333065-CW-RFB / R ids - Small W e-construction of Barawe TB Component 2: Medium-Ter Open - Internationa Single Stage - One E Under Imple 2023-10-1 IDA / D6300 Prior Request for Bids orks SPD (1 e 0.00 2022-12-31 2023-01-11 2023-01-05 2023-01-17 2023-02-16 2023-02-16 2023-03-18 2023-04-20 2023-04-22 Unit Healthcare Facility, in Ba m Flood Recovery l nvelope mentation 9 nvelope proc rawe District, South West Sta ess) te, Somalia. Request for B SO-MOF-331714-CW-RFB / R ids - Small W e-construction of Barawe TB Component 2: Medium-Ter Open - Internationa Single Stage - One E 2023-10-1 IDA / D6300 Post Request for Bids orks SPD (1 e 0.00 Canceled 2022-12-31 2023-01-05 2023-02-16 2023-03-18 2023-04-22 Unit Healthcare Facility, Bara m Flood Recovery l nvelope 9 nvelope proc we District, South West State ess) , Somalia. Request for SO-MOF-352047-CW-RFQ / R Quotations - ehabilitation of river embank Component 2: Medium-Ter Request for Quota Single Stage - One E Under Imple 2023-12-2 IDA / D8730 Prior Limited Small Works 0.00 2023-05-05 2023-05-03 2023-06-30 ment site (Moyko 3) in Jowha m Flood Recovery tions nvelope mentation 7 (Emergency) r District. SPD -Compet itive Request for B SO-MOF-358679-CW-RFB / R ids - Small W ehabilitation of Two Canals ( Component 2: Medium-Ter Open - Internationa Single Stage - One E Under Revie 2024-03-1 IDA / D8730 Prior Request for Bids orks SPD (1 e 0.00 2023-05-31 2023-06-28 2023-06-05 2023-07-17 2023-08-16 2023-09-20 Xanshoore and Aslubta) in Jo m Flood Recovery l nvelope w 8 nvelope proc whar District, Hirshabelle Sta ess) te of Somalia GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SO-MOF-214333-GO-RFQ / Pr Component 4: Project Manag Request for Quota Single Stage - One E IDA / D6300 Prior Limited 84,861.70 Signed 2021-04-05 2021-07-14 2021-05-31 2021-07-25 2021-11-27 ocurement of 2 Vehicle for PI ement tions nvelope U SO-MOF-214334-GO-RFQ / Fi Component 4: Project Manag Request for Quota Single Stage - One E Under Imple IDA / D6300 Prior Limited 0.00 2021-04-05 2021-04-26 2021-05-31 2021-11-27 ttings and furniture for PIU Of ement tions nvelope mentation fice SO-MOF-230645-GO-RFQ / Pr Component 4: Project Manag Request for Quota Single Stage - One E Under Imple ocurement of IT equipment f IDA / D6300 Prior Limited 0.00 2021-05-06 2021-07-12 2021-07-01 2021-12-28 ement tions nvelope mentation or PIU Office SO-MOF-235305-GO-RFB / Pr ocurement of Locally made cl Component 5: Contingent Single Stage - One E Pending Impl IDA / D6300 Prior Request for Bids Open - National 0.00 2021-06-30 2021-07-05 2021-08-16 2021-09-15 2021-10-20 2022-04-18 oth face masks for the gener Emergency Response nvelope ementation al public (schools, mosques, etc) SO-MOF-235307-GO-RFB / Pr Component 5: Contingent Single Stage - One E Pending Impl ocure Hygiene supplies (Clor IDA / D6300 Prior Request for Bids Open - National 0.00 2021-06-30 2021-07-05 2021-08-16 2021-09-15 2021-10-20 2022-04-18 Emergency Response nvelope ementation ox, soaps, disinfectants, han d sanitizers etc) SO-MOF-235309-GO-DIR / Pr ocurement, commissioning a Component 5: Contingent nd installation of two oxygen IDA / D6300 Prior Direct Selection Direct 0.00 Canceled 2021-06-30 2021-07-05 2021-08-09 2022-02-05 Emergency Response plants for Southwest and Jub aland States of Somalia SO-MOF-235310-GO-RFB / Pr ocurement of Continuous su Component 5: Contingent Single Stage - One E Pending Impl IDA / D6300 Prior Request for Bids Open - National 0.00 2021-06-30 2021-07-05 2021-08-16 2021-09-15 2021-10-20 2022-04-18 pply of oxygen to hospitals to Emergency Response nvelope ementation be used for Covid-19 patients SO-MOF-233802-GO-RFQ / B atch-2 (Beledwyn): REHABILI Component 2: Medium-Ter Request for Quota Single Stage - One E TATION OF BELEDWEYN/HOO IDA / D6300 Prior Limited 0.00 Canceled 2021-05-16 2021-07-11 2022-01-07 m Flood Recovery tions nvelope DLEY RIVER EMBANKMENT IN BELEDWEYN DISTRICT – SOM ALIA (C14) SO-MOF-238495-GO-RFQ / Pr ocurement, commissioning a Component 5: Contingent Open - Internationa Single Stage - One E Pending Impl IDA / D6300 Prior Request for Bids 0.00 2021-07-15 2021-07-20 2021-08-31 2021-09-30 2021-11-04 2022-05-03 nd installation of One oxygen Emergency Response l nvelope ementation plant for Banadir SO-MOF-242309-GO-RFB / Pr ocurement, commissioning a Component 5: Contingent Open - Internationa Single Stage - One E Pending Impl IDA / D6300 Prior Request for Bids 0.00 2021-07-20 2021-07-25 2021-09-05 2021-10-05 2021-11-09 2022-05-08 nd installation of 2 oxygen pl Emergency Response l nvelope ementation ants for Southwest and Jubal and States of Somalia SO-MOF-247166-GO-RFB / S upply, delivery, installation, c ommissioning and maintenan Component 5: Contingent Single Stage - One E Pending Impl IDA / D6300 Prior Request for Bids Open - National 0.00 2021-08-15 2021-08-20 2021-10-01 2021-10-31 2021-12-05 2022-06-03 ce of solar systems to Martini Emergency Response nvelope ementation Hospital, Banadir Hospital, N ational Laboratory and Minist ry of Health SO-MOF-273751-GO-RFQ / P Component 4: Project Manag Request for Quota Single Stage - One E Under Imple urchase of IT equipment for S IDA / D6300 Prior Limited 0.00 2022-04-05 2022-03-03 2022-05-31 2022-11-27 ement tions nvelope mentation tate project teams (3 Lots) SO-MOF-273756-GO-RFQ / P Component 4: Project Manag Request for Quota Single Stage - One E Under Imple urchase of office furniture for IDA / D6300 Prior Limited 0.00 2022-04-05 2022-03-03 2022-05-31 2022-11-27 ement tions nvelope mentation State project teams (3 Lots) SO-MOF-235291-GO-RFQ / Pr ocurement of Medical grade Component 5: Contingent Request for Quota Single Stage - One E IDA / D6300 Post Limited 0.00 Canceled 2021-07-20 2021-09-14 2022-03-13 masks for health care worker Emergency Response tions nvelope s at hospitals and health facil ities SO-MOF-235311-GO-RFB / Pr ocurement of Essential Covid Component 5: Contingent Open - Internationa Single Stage - One E Pending Impl IDA / D6300 Prior Request for Bids 0.00 2022-03-31 2022-04-05 2022-05-17 2022-06-16 2022-07-21 2023-01-17 -19 medicines and kits, labor Emergency Response l nvelope ementation atory reagents and other ess entials countrywide SO-MOF-295728-GO-RFQ / Pr Component 5: Contingent Request for Quota Single Stage - One E Pending Impl ocurement of a vehicle for th IDA / D6300 Prior Limited 0.00 2022-07-09 2022-09-03 2023-03-02 Emergency Response tions nvelope ementation e FMOH to transport Medical Supplies. SO-MOF-304013-GO-RFB / Pr ocurement and installation of Component 5: Contingent Open - Internationa Single Stage - One E Pending Impl additional solar panels (comp IDA / D8730 Prior Request for Bids 0.00 2022-08-31 2022-09-05 2022-10-17 2022-11-16 2022-12-21 2023-06-19 Emergency Response l nvelope ementation lete with spare parts) at the COVID-19 Health Facilities in Mogadishu and FMS Page 7 SO-MOF-304000-GO-RFB / Pr Component 5: Contingent Open - Internationa Single Stage - One E Under Imple ocurement of Lab & medical IDA / D8730 Prior Request for Bids 0.00 2022-08-31 2022-09-05 2022-10-17 2022-11-16 2022-12-21 2023-06-19 Emergency Response l nvelope mentation equipment for Federal & FMS Health Ministries SO-MOF-328332-GO-DIR / Pr Component 3: Longer-Ter ocurement of Hydrological an Direct - Internation Under Revie IDA / D6300 m Disaster Risk Preparednes Prior Direct Selection 0.00 2022-12-10 2022-12-29 2022-12-15 2023-04-14 2023-01-19 2023-07-18 d hydraulic modeling and Flo al w s od Early Warning System soft ware package SO-MOF-346330-GO-RFQ / Pr Component 4: Project Manag Request for Quota Single Stage - One E Under Imple ocurement of office furniture IDA / D6300 Prior Limited 0.00 2023-04-05 2023-05-15 2023-05-31 2023-11-27 ement tions nvelope mentation for Hirshabelle and Jubaland SPT offices SO-MOF-357130-GO-RFB / Pr Component 6: Anticipatory a Open - Internationa Single Stage - One E Under Imple ocurement of Refrigerated tr IDA / D6300 nd Recovery Support for Add Prior Request for Bids 0.00 2023-06-30 2023-05-15 2023-07-05 2023-05-23 2023-08-16 2023-09-15 2023-10-20 2024-04-17 l nvelope mentation ucks for fishing associations ressing Food Insecurity SO-MOF-357133-GO-RFB / Pr Component 6: Anticipatory a Open - Internationa Single Stage - One E Under Imple ocurement of Mobile refriger IDA / D6300 nd Recovery Support for Add Prior Request for Bids 0.00 2023-06-30 2023-05-17 2023-07-05 2023-05-19 2023-08-16 2023-09-15 2023-10-20 2024-04-17 l nvelope mentation ated fish kiosks ressing Food Insecurity SO-MOF-359405-GO-RFQ / Pr Component 3: Longer-Ter Request for Quota Single Stage - One E Pending Impl ocurement of Office Furniture IDA / D8730 m Disaster Risk Preparednes Prior Limited 0.00 2023-06-05 2023-07-31 2024-01-27 tions nvelope ementation and Equipment for NEOC s SO-MOF-359413-GO-RFB / Pr Component 3: Longer-Ter Single Stage - One E Pending Impl IDA / D8730 Prior Request for Bids Open - National 0.00 2023-05-31 2023-06-05 2023-07-17 2023-08-16 2023-09-20 2024-03-18 ocurement of Vehicles for NE m Disaster Risk Preparednes nvelope ementation OC s NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SO-MOF-174236-NC-UN / Agr eement for Delivery of Outpu ts: Provision of Desert Locust Component 1: Immediate UN Agencies (Dire Control, Emergency Support IDA / D6300 Basic Services and Livelihoo Prior Direct 41,156,567.00 Signed 2020-07-09 2020-07-10 2020-07-14 2020-07-10 2020-08-18 2020-07-28 2021-02-14 ct) to affected communities, and d Support Re-establish the Desert Locu st Surveillance and Control S ystem. SO-MOF-190204-NC-DIR / No n-consulting Service contract with the INGO- Building Resil Component 1: Immediate ience Communities in Somali IDA / D6300 Basic Services and Livelihoo Prior Direct Selection Direct 14,142,000.00 Signed 2020-12-31 2020-10-28 2021-01-05 2021-02-24 2021-02-09 2022-01-24 2021-08-08 a (BRC for the implementatio d Support n of Immediate basic service s and livelihood support for e arly recovery SO-MOF-217511-NC-UN / AG REEMENT FOR DELIVERY OF Component 5: Contingent UN Agencies (Dire OUTPUTS WITH UNICEF: SOM IDA / D6300 Prior Direct 0.00 Canceled 2021-03-15 2021-03-20 2021-04-24 2021-10-21 Emergency Response ct) ALIA COVID-19 OUTBREAK RE SPONSE UNDER SOMALIA CRI SIS RESPONSE SO-MOF-223676-NC-UN / AG REEMENT FOR DELIVERY OF Component 5: Contingent UN Agencies (Dire IDA / D6300 Prior Direct 871,500.00 Signed 2021-04-30 2021-04-07 2021-05-05 2021-04-12 2021-06-09 2021-08-01 2021-12-06 OUTPUTS WITH IOM- SOMALI Emergency Response ct) A COVID-19 RESPONSE UNDE R SCRP SO-MOF-223678-NC-UN / AG REEMENT FOR DELIVERY OF Component 5: Contingent UN Agencies (Dire IDA / D6300 Prior Direct 8,175,120.00 Signed 2021-04-30 2021-04-07 2021-05-05 2021-04-12 2021-06-09 2021-04-25 2021-12-06 OUTPUTS WITH WHO - SOMA Emergency Response ct) LIA COVID-19 RESPONSE UN DER SCRP PROJECT SO-MOF-223679-NC-DIR / Ag reement with SomRep consor Component 1: Immediate tia for the provision of Early IDA / D6300 Basic Services and Livelihoo Prior Direct Selection Direct 10,681,000.00 Signed 2021-04-30 2021-04-12 2021-05-05 2021-04-29 2021-06-09 2022-06-30 2021-12-06 Recovery Support to The Floo d Support d Affected Communities in Hi rshabelle, Jubaland And Sout hwest SO-MOF-223686-NC-DIR / Ag reement with NEXUS Consort Component 1: Immediate ia for the provision of early r IDA / D6300 Basic Services and Livelihoo Prior Direct Selection Direct 0.00 Canceled 2021-05-31 2021-08-05 2021-06-05 2021-07-10 2022-01-06 ecovery Support to The Flood d Support Affected Communities in Hirs habelle, Jubaland And South west States of Somalia SO-MOF-226047-NC-UN / AG REEMENT FOR DELIVERY OF Component 5: Contingent UN Agencies (Dire OUTPUTS WITH UNICEF: SOM IDA / D6300 Prior Direct 4,416,509.11 Signed 2021-03-31 2021-03-23 2021-04-05 2021-04-01 2021-05-10 2021-04-13 2021-11-06 Emergency Response ct) ALIA COVID-19 OUTBREAK RE SPONSE UNDER SOMALIA CRI SIS RESPONSE SO-MOF-328356-NC-DIR / Str Component 3: Longer-Ter engthening medical emergen Direct - Internation Under Imple IDA / D8730 m Disaster Risk Preparednes Prior Direct Selection 0.00 2022-12-01 2023-01-02 2022-12-06 2023-02-27 2023-01-10 2023-07-09 cy services including intensiv al mentation s e care units for Federal & Sta te referral hospitals SO-MOF-333084-NC-DIR / Ca Component 3: Longer-Ter Direct - Internation Under Imple pacity Building of Somalia Se IDA / D8730 m Disaster Risk Preparednes Prior Direct Selection 0.00 2023-02-28 2023-04-14 2023-03-05 2023-05-17 2023-04-09 2023-10-06 al mentation ed Systems Recovery Initiati s ve (SSRI) CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SO-MOF-183832-CS-CDS / Te chnical assistance agency for Component 4: Project Manag UN Agencies (Dire IDA / D6300 Prior Direct 4,437,254.00 Signed 2020-08-28 2020-09-15 2022-08-28 the provision of Project Mana ement ct) gement Support SO-MOF-187653-CS-QCBS / Component 4: Project Manag Least Cost Selecti Open - Internationa SCRP Project Audit and Indep IDA / D6300 Prior 406,932.40 Signed 2020-10-31 2020-11-05 2020-11-21 2020-11-19 2021-01-04 2021-02-24 2021-02-01 2021-04-03 2021-03-03 2021-06-28 2021-04-07 2021-09-30 2021-05-12 2021-11-17 2021-11-08 ement on l endent Verification Agent IVA Page 8 SO-MOF-188776-CS-UN / De Component 2: Medium-Ter UN Agencies (Dire velopment of Designs & Supe IDA / D6300 Prior Direct 0.00 Canceled 2020-11-09 2021-05-08 m Flood Recovery ct) rvision of Construction Works SO-MOF-318290-CS-QCBS / Component 3: Longer-Ter Consultancy service to stren Quality And Cost- Under Implement IDA / D6300 m Disaster Risk Preparednes Prior Open - National 0.00 2022-11-30 2022-11-28 2022-12-21 2022-12-14 2023-02-03 2023-05-04 2023-03-03 2023-04-02 2023-05-07 2023-06-11 2024-06-10 gthen Hydromet service diss Based Selection ation s emination and community en gagement SO-MOF-328349-CS-FBS / Co Component 3: Longer-Ter Fixed Budget Sele nsultancy Service for Strengt IDA / D6300 m Disaster Risk Preparednes Prior Open - National 0.00 Under Review 2022-12-10 2022-12-14 2022-12-31 2023-03-09 2023-02-13 2023-03-13 2023-04-12 2023-05-17 2023-06-21 2024-06-20 ction hening Hydro-Met and Hazar s d Monitoring SO-MOF-328353-CS-FBS / Co Component 3: Longer-Ter nsultancy Service to Strength Fixed Budget Sele IDA / D6300 m Disaster Risk Preparednes Prior Open - National 0.00 Under Review 2022-12-10 2022-12-14 2022-12-31 2023-01-11 2023-02-13 2023-03-13 2023-04-12 2023-05-17 2023-06-21 2024-06-20 en Hydromet Service Dissemi ction s nation and Community Enga gement SO-MOF-333116-CS-CQS / C onsultancy Services for the d Component 3: Longer-Ter evelopment of a Basin Diagn Quality And Cost- Open - Internationa IDA / D8730 m Disaster Risk Preparednes Prior 0.00 Under Review 2023-03-31 2023-03-13 2023-04-21 2023-04-14 2023-06-04 2023-07-02 2023-08-01 2023-09-05 2023-10-10 2024-10-09 ostic and a Strategic Action P Based Selection l s lan for the Juba Basin, Somali a, and preparation of prioritiz ed action projects SO-MOF-346332-CS-LCS / Pr Component 3: Longer-Ter ovision of Consulting Service Consultant Qualifi IDA / D6300 m Disaster Risk Preparednes Prior Limited 0.00 Canceled 2023-03-31 2023-03-15 2023-04-14 2023-05-14 2023-06-18 2023-12-15 s for Mogadishu's Water Secu cation Selection s rity Diagnostic Study SO-MOF-347690-CS-QCBS / Component 6: Anticipatory a Consulting Service - Capacity Quality And Cost- Open - Internationa Under Implement IDA / D8730 nd Recovery Support for Add Prior 0.00 2023-03-31 2023-05-19 2023-04-21 2023-05-31 2023-06-04 2023-07-02 2023-08-01 2023-09-05 2023-10-10 2024-10-09 Assessment of Federal and S Based Selection l ation ressing Food Insecurity tate level Ministries of Agricu lture and Irrigation SO-MOF-348357-CS-CQS / P Component 3: Longer-Ter ublic Private Engagement (PP Consultant Qualifi Pending Impleme IDA / D6300 m Disaster Risk Preparednes Prior Limited 0.00 2023-03-31 2023-04-14 2023-05-14 2023-06-18 2023-12-15 E) to strengthen Hydro-mete cation Selection ntation s orological services SO-MOF-352038-CS-CQS / C Component 3: Longer-Ter onsulting Services - Assessm Consultant Qualifi Under Implement IDA / D8730 m Disaster Risk Preparednes Prior Limited 0.00 2023-04-30 2023-05-14 2023-06-13 2023-07-18 2024-01-14 ent & Delivery of Design & C cation Selection ation s ost Estimation for Eight Regi onal Hospitals SO-MOF-358654-CS-CQS / T Component 3: Longer-Ter echnical assistance to suppor Consultant Qualifi Under Implement IDA / D8730 m Disaster Risk Preparednes Prior Limited 0.00 2023-05-31 2023-05-16 2023-06-14 2023-07-14 2023-08-18 2024-02-14 t Mogadishu's Water Security cation Selection ation s Diagnostic Study SO-MOF-358661-CS-QCBS / Component 3: Longer-Ter Provision of Consulting Servic Quality And Cost- Pending Impleme IDA / D8730 m Disaster Risk Preparednes Prior Open - National 0.00 2023-07-31 2023-08-21 2023-10-04 2023-11-01 2023-12-01 2024-01-05 2024-02-09 2025-02-08 es for Mogadishu's Water Sec Based Selection ntation s urity Diagnostic Study INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Actual Amount Invitation to Identifie Draft Negotiated Cont Component Review Type Method Contract Type Process Status Teams of Reference Signed Contract Contract Completion Description o. h (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SO-MOF-183841-CS-INDV / H Component 5: Contingent Individual Consult ealth/COVID19 Response Faci IDA / D6300 Prior Limited 120,000.00 Signed 2020-08-20 2020-08-19 2020-08-27 2020-12-12 2020-09-01 2021-01-07 2020-09-04 2021-01-18 2021-06-01 Emergency Response ant Selection litation Consultant SO-MOF-186983-CS-CDS / Fo Component 3: Longer-Ter recasting, Aid Tracking Syste IDA / D6300 m Disaster Risk Preparednes Prior Direct Selection Direct 769,060.00 Signed 2020-08-31 2020-11-16 2020-09-10 2020-12-19 2020-11-14 2021-03-29 2021-05-13 m & Needs Assessment to Int s egrate COVID-19 Country Wi de efforts SO-MOF-184256-CS-INDV / R Component 4: Project Manag Individual Consult IDA / D6300 Prior Limited 227,880.00 Signed 2020-08-17 2020-09-03 2020-08-22 2020-10-07 2020-09-12 2020-10-09 2020-10-17 2020-10-11 2021-04-15 ecovery Planning Specialist ement ant Selection SO-MOF-183833-CS-QCBS / Component 4: Project Manag Security Risk Management C IDA / D6300 Prior Direct Selection Direct 1,581,419.71 Signed 2020-10-31 2020-09-04 2020-11-10 2020-09-23 2021-01-14 2021-01-09 2021-07-13 ement onsulting Services SO-MOF-183838-CS-INDV / Component 4: Project Manag Individual Consult IDA / D6300 Prior Direct 140,400.00 Completed 2020-08-15 2020-09-03 2020-08-25 2020-09-09 2020-09-15 2020-09-17 2020-10-20 2020-09-24 2021-04-18 2021-12-17 Monitoring & Evaluation Spec ement ant Selection ialist SO-MOF-183836-CS-INDV / F Component 4: Project Manag Individual Consult IDA / D6300 Prior Direct 213,780.00 Signed 2020-08-15 2020-09-04 2020-08-25 2020-09-09 2020-09-15 2020-09-17 2020-10-20 2020-09-27 2021-04-18 inancial Management Special ement ant Selection ist SO-MOF-183837-CS-INDV / P Component 4: Project Manag Individual Consult IDA / D6300 Prior Direct 213,780.00 Signed 2020-08-15 2020-09-03 2020-08-20 2020-09-09 2020-09-10 2020-09-17 2020-10-15 2020-09-27 2021-04-13 roject Engineer ement ant Selection SO-MOF-183834-CS-CDS / Pr Component 4: Project Manag Individual Consult IDA / D6300 Prior Direct 334,440.00 Terminated 2020-08-15 2020-09-03 2020-08-25 2020-09-01 2020-09-15 2020-09-17 2020-10-20 2020-09-27 2021-04-18 oject Coordinator ement ant Selection SO-MOF-183835-CS-INDV / P Component 4: Project Manag Individual Consult IDA / D6300 Prior Direct 222,420.00 Signed 2020-08-15 2020-09-04 2020-08-25 2020-09-09 2020-09-15 2020-09-17 2020-10-20 2020-09-27 2021-04-18 rocurement Specialist ement ant Selection SO-MOF-183839-CS-INDV / E Component 4: Project Manag Individual Consult IDA / D6300 Prior Direct 70,200.00 Signed 2020-08-15 2020-09-03 2020-08-25 2020-09-09 2020-09-15 2020-09-17 2020-10-20 2020-09-25 2021-04-18 nvironmental Safeguard Spe ement ant Selection cialist SO-MOF-183157-CS-INDV / S Component 4: Project Manag Individual Consult IDA / D6300 Prior Limited 0.00 Canceled 2020-07-09 2020-07-09 2020-07-14 2020-08-04 2020-09-08 2021-03-07 ocial Development Specialist ement ant Selection SO-MOF-187526-CS-INDV / S Component 4: Project Manag Individual Consult IDA / D6300 Prior Limited 0.00 Canceled 2020-08-15 2020-08-20 2020-09-10 2020-10-15 2021-04-13 ocial Development Specialist ement ant Selection SO-MOF-190535-CS-INDV / S Component 4: Project Manag Individual Consult IDA / D6300 Prior Limited 140,400.00 Signed 2020-10-31 2020-10-05 2020-11-05 2020-12-09 2020-11-26 2020-12-15 2020-12-31 2020-12-20 2021-06-29 takeholder Engagement Spec ement ant Selection ialist SO-MOF-190539-CS-INDV / P Component 4: Project Manag Individual Consult IDA / D6300 Prior Limited 65,035.00 Terminated 2020-10-31 2020-10-05 2020-11-05 2021-02-25 2020-11-26 2021-03-01 2020-12-31 2021-03-02 2021-06-29 roject Administrative Officer ement ant Selection Page 9 SO-MOF-190541-CS-INDV / T Component 4: Project Manag Individual Consult IDA / D6300 Prior Limited 105,600.00 Signed 2020-12-31 2020-11-05 2021-01-05 2020-11-16 2021-01-26 2020-11-20 2021-03-02 2020-12-07 2021-08-29 oll-free Hotline Operator (GR ement ant Selection M) SO-MOF-190545-CS-INDV / P Component 4: Project Manag Individual Consult IDA / D6300 Prior Limited 52,800.00 Completed 2020-11-30 2020-10-05 2020-12-05 2021-03-22 2020-12-26 2021-04-21 2021-01-30 2021-05-19 2021-07-29 2022-05-19 roject Security Officer ement ant Selection SO-MOF-190709-CS-INDV / S Component 4: Project Manag Individual Consult IDA / D6300 Prior Limited 229,320.00 Signed 2020-08-31 2020-10-05 2020-09-05 2020-08-18 2020-09-26 2020-10-08 2020-10-31 2020-09-05 2021-04-29 ocial Development Specialist ement ant Selection SO-MOF-196562-CS-INDV / E Component 4: Project Manag Individual Consult nvironmental Safeguard Offic IDA / D6300 Prior Open 0.00 Signed 2020-11-15 2020-11-16 2021-01-03 2022-03-03 2021-01-24 2022-03-14 2021-02-28 2023-03-21 2021-08-27 ement ant Selection er, Hirshabelle State Project Team SO-MOF-196565-CS-INDV / E Component 4: Project Manag Individual Consult nvironmental Safeguard Offic IDA / D6300 Prior Open 82,200.00 Signed 2020-12-15 2020-11-16 2021-02-02 2021-05-17 2021-02-23 2021-06-07 2021-03-30 2021-06-08 2021-09-26 ement ant Selection er, Southwest State Project T eam SO-MOF-196570-CS-INDV / P Component 4: Project Manag Individual Consult IDA / D6300 Prior Open 82,200.00 Signed 2020-11-15 2020-11-16 2021-01-03 2021-05-17 2021-01-24 2021-06-06 2021-02-28 2021-06-08 2021-08-27 roject Engineer, Southwest St ement ant Selection ate SO-MOF-196571-CS-INDV / P Component 4: Project Manag Individual Consult IDA / D6300 Prior Open 40,320.00 Signed 2020-12-15 2020-11-16 2021-02-02 2022-01-09 2021-02-23 2022-01-19 2021-03-30 2022-02-06 2021-09-26 roject Engineer, Hirshabelle S ement ant Selection tate SO-MOF-196572-CS-INDV / P Component 4: Project Manag Individual Consult IDA / D6300 Prior Open 102,120.00 Signed 2020-11-15 2020-11-16 2021-01-03 2021-05-19 2021-01-24 2021-06-06 2021-02-28 2021-06-08 2021-08-27 roject Coordinator, Southwes ement ant Selection t SPT SO-MOF-196574-CS-INDV / P Component 4: Project Manag Individual Consult IDA / D6300 Prior Open 49,920.00 Signed 2020-12-15 2020-11-16 2021-02-02 2022-01-09 2021-02-23 2022-01-19 2021-03-30 2022-02-06 2021-09-26 roject Coordinator, Hirshabell ement ant Selection e SPT SO-MOF-197348-CS-INDV / G Component 4: Project Manag Individual Consult IDA / D6300 Prior Limited 105,600.00 Signed 2020-10-31 2020-11-16 2020-11-05 2021-02-07 2020-11-26 2021-02-12 2020-12-31 2021-02-16 2021-06-29 BV Officer ement ant Selection SO-MOF-196560-CS-INDV / E Component 4: Project Manag Individual Consult nvironmental Safeguard Offic IDA / D6300 Prior Open 0.00 Canceled 2020-12-31 2020-11-25 2021-02-18 2021-03-11 2021-04-15 2021-10-12 ement ant Selection er, Jubalad SPT SO-MOF-196555-CS-INDV / P Component 4: Project Manag Individual Consult IDA / D6300 Prior Open 0.00 Signed 2020-12-31 2020-11-25 2021-02-18 2022-03-17 2021-03-11 2022-03-23 2021-04-15 2023-04-15 2021-10-12 roject Coordinator, Jubaland ement ant Selection State SPT SO-MOF-196556-CS-INDV / P Component 4: Project Manag Individual Consult IDA / D6300 Prior Open 0.00 Signed 2020-12-31 2020-11-25 2021-02-18 2022-03-17 2021-03-11 2022-03-23 2021-04-15 2023-04-16 2021-10-12 roject Engineer, Jubaland SPT ement ant Selection SO-MOF-196568-CS-INDV / A Component 4: Project Manag Individual Consult dministration & Finance Offic IDA / D6300 Prior Open 82,200.00 Signed 2020-12-15 2020-11-25 2021-02-02 2021-05-17 2021-02-23 2021-06-06 2021-03-30 2021-06-08 2021-09-26 ement ant Selection er, Southwest SPT SO-MOF-196567-CS-INDV / A Component 4: Project Manag Individual Consult dministration & Finance Offic IDA / D6300 Prior Open 40,320.00 Signed 2020-12-31 2020-11-30 2021-02-18 2022-01-09 2021-03-11 2022-01-19 2021-04-15 2022-02-06 2021-10-12 ement ant Selection er, Hirshabelle SPT SO-MOF-196558-CS-INDV / A Component 4: Project Manag Individual Consult dministration & Finance Offic IDA / D6300 Prior Open 0.00 Canceled 2020-12-31 2020-11-30 2021-02-18 2021-03-11 2021-04-15 2021-10-12 ement ant Selection er, Jubaland SPT SO-MOF-210970-CS-INDV / Component 3: Longer-Ter Individual Consult IDA / D6300 Prior Limited 140,400.00 Signed 2021-01-31 2021-02-10 2021-02-05 2021-03-04 2021-02-26 2021-03-17 2021-04-02 2021-03-30 2021-09-29 MOH Senior Coordinator for S m Disaster Risk Preparednes ant Selection CRP Project s SO-MOF-214330-CS-INDV / F Component 3: Longer-Ter Individual Consult IDA / D6300 Prior Limited 118,560.00 Signed 2021-02-28 2021-02-09 2021-03-05 2021-05-10 2021-03-26 2021-06-06 2021-04-30 2021-03-21 2021-10-27 inancial Specialist, MOH m Disaster Risk Preparednes ant Selection s SO-MOF-214331-CS-INDV / Component 3: Longer-Ter Individual Consult IDA / D6300 Prior Limited 77,400.00 Signed 2021-03-01 2021-03-15 2021-03-06 2021-03-04 2021-03-27 2021-03-18 2021-05-01 2021-03-24 2021-10-28 MOH Communication Officer m Disaster Risk Preparednes ant Selection s SO-MOF-210968-CS-INDV / Component 5: Contingent Individual Consult MOH COVID-19 RESPONSE & IDA / D6300 Prior Limited 139,617.75 Signed 2021-03-31 2021-03-15 2021-04-05 2021-03-04 2021-04-26 2021-03-18 2021-05-31 2021-03-21 2021-11-27 Emergency Response ant Selection RECOVERY COORDINATOR SO-MOF-217509-CS-INDV / S Component 4: Project Manag Individual Consult IDA / D6300 Prior Direct 164,040.00 Signed 2021-04-30 2021-04-16 2021-05-10 2021-05-17 2021-05-31 2021-06-07 2021-07-05 2021-06-08 2022-01-01 CRP Operations Manager ement ant Selection SO-MOF-190538-CS-INDV / C Component 4: Project Manag Individual Consult IDA / D6300 Prior Limited 0.00 Canceled 2020-10-31 2020-10-05 2020-11-05 2020-11-26 2020-12-31 2021-06-29 ommunication Specialist ement ant Selection SO-MOF-229866-CS-INDV / P Component 4: Project Manag Individual Consult Under Implement IDA / D6300 Prior Open 0.00 2021-04-30 2021-05-21 2021-06-18 2021-07-09 2021-08-13 2022-02-09 IU Communications Specialist ement ant Selection ation SO-MOF-239607-CS-CDS / A GREEMENT FOR DELIVERY OF Component 4: Project Manag IDA / D6300 Prior Direct Selection Direct 0.00 Canceled 2021-07-01 2021-07-11 2021-09-14 2022-03-13 OUTPUTS WITH UNOPS: TECH ement NICAL STUDIES & DESIGN SO-MOF-188776-CS-UN-2 / P Component 2: Medium-Ter Under Implement rovision of Design and Super IDA / D6300 Prior Direct Selection Direct 0.00 2021-08-15 2021-08-25 2021-10-29 2022-04-27 m Flood Recovery ation vision of Flood and Irrigation System with FAO SO-MOF-256503-CS-INDV / E Component 4: Project Manag Individual Consult Under Implement IDA / D6300 Prior Open 0.00 2021-10-20 2021-10-22 2021-12-08 2022-03-24 2021-12-29 2022-03-29 2022-02-02 2022-08-01 nvironmental Safeguard Spe ement ant Selection ation cialist SO-MOF-260028-CS-CDS / Pr ovision of Technical Studies a Component 4: Project Manag Under Implement IDA / D6300 Prior Direct Selection Direct 0.00 2021-11-05 2022-01-20 2021-11-15 2022-01-19 2022-07-18 nd Design Services as part of ement ation the Somalia Crisis Recovery Project SO-MOF-273757-CS-INDV / Component 4: Project Manag Individual Consult IDA / D6300 Prior Open 0.00 Signed 2022-02-28 2022-02-07 2022-04-18 2022-06-07 2022-05-09 2022-06-13 2022-06-13 2023-06-09 2022-12-10 Monitoring and Evaluation Sp ement ant Selection ecialist SO-MOF-277118-CS-CDS / Te Component 3: Longer-Ter chnical Advisor for National E Under Implement IDA / D6300 m Disaster Risk Preparednes Prior Direct Selection Direct 0.00 2022-03-31 2022-03-30 2022-04-10 2022-04-13 2022-06-14 2022-12-11 mergency Operation Centre ( ation s NEOC), Office of the Prime Mi nster SO-MOF-277127-CS-CDS / C Component 3: Longer-Ter ommunication Consultant, N IDA / D6300 m Disaster Risk Preparednes Prior Direct Selection Direct 0.00 Signed 2022-03-31 2022-03-30 2022-04-10 2022-04-13 2022-06-14 2022-12-11 ational Emergency Operation s Centre (NEOC) - Office of the Prime Minster Page 10 SO-MOF-276900-CS-CDS / C Component 5: Contingent Under Implement ERC Coordinator for Banadir IDA / D6300 Prior Direct Selection Direct 0.00 2022-03-31 2022-04-05 2022-04-10 2022-04-13 2022-06-14 2022-12-11 Emergency Response ation Regional Administration (BRA ) SO-MOF-276905-CS-CDS / C Component 5: Contingent Under Implement ERC Finance Specialist for Ba IDA / D6300 Prior Direct Selection Direct 0.00 2022-03-31 2022-04-05 2022-04-10 2022-04-13 2022-06-14 2022-12-11 Emergency Response ation ndir Regional Administration SO-MOF-307794-CS-INDV / P Component 4: Project Manag Individual Consult Under Implement IDA / D6300 Prior Limited 0.00 2022-08-31 2022-08-25 2022-09-05 2022-12-06 2022-09-26 2023-02-22 2022-10-31 2023-04-29 roject Security Officer ement ant Selection ation SO-MOF-307795-CS-INDV / P Component 4: Project Manag Individual Consult Under Implement IDA / D6300 Prior Open - National 0.00 2022-08-31 2022-08-25 2022-10-19 2023-02-25 2022-11-09 2023-05-11 2022-12-14 2023-06-12 roject Admin Officer ement ant Selection ation SO-MOF-307796-CS-INDV / E Component 4: Project Manag Individual Consult Under Implement nvironmental and Social Safe IDA / D6300 Prior Open - National 0.00 2022-08-31 2022-09-19 2022-10-19 2023-04-27 2022-11-09 2023-05-11 2022-12-14 2023-06-12 ement ant Selection ation guard Officer, Jubaland SPT SO-MOF-307798-CS-INDV / Component 4: Project Manag Individual Consult Under Implement Monitoring and evaluation off IDA / D6300 Prior Open - National 0.00 2022-08-31 2022-09-26 2022-10-19 2023-02-15 2022-11-09 2023-05-11 2022-12-14 2023-06-12 ement ant Selection ation icer, Jubaland SPT SO-MOF-316799-CS-CDS / C Component 4: Project Manag Under Implement ontract Management and Pro IDA / D6300 Prior Direct Selection Direct - National 0.00 2022-11-30 2022-10-12 2022-12-10 2022-10-22 2023-02-13 2023-08-12 ement ation curement Specialist, PIU SO-MOF-322581-CS-INDV / D Component 3: Longer-Ter rought Management Advisor Individual Consult Under Implement IDA / D6300 m Disaster Risk Preparednes Prior Limited 0.00 2022-10-31 2022-11-08 2022-11-05 2023-01-25 2022-11-26 2023-03-13 2022-12-31 2023-06-29 for the office of Somalia spec ant Selection ation s ial envoy for drought respons e SO-MOF-322582-CS-INDV / R esource Mobilization and Don Component 3: Longer-Ter Individual Consult Under Implement or Relations Advisor for the o IDA / D6300 m Disaster Risk Preparednes Prior Limited 0.00 2022-10-31 2022-11-08 2022-11-05 2023-01-25 2022-11-26 2023-03-07 2022-12-31 2023-06-29 ant Selection ation ffice of Somalia’s special env s oy for drought response SO-MOF-328720-CS-INDV / P Component 4: Project Manag Individual Consult Under Implement IDA / D8730 Prior Limited 0.00 2022-12-10 2022-12-14 2022-12-15 2023-03-01 2023-01-05 2023-06-14 2023-02-09 2023-08-08 rocurement officer, PIU ement ant Selection ation SO-MOF-328721-CS-INDV / F Component 4: Project Manag Individual Consult Under Implement IDA / D8730 Prior Limited 0.00 2022-12-10 2022-12-14 2022-12-15 2023-03-01 2023-01-05 2023-06-12 2023-02-09 2023-08-08 inance Officer, PIU ement ant Selection ation SO-MOF-333068-CS-INDV / P Component 4: Project Manag Individual Consult Under Implement IDA / D8730 Prior Limited 0.00 2022-12-31 2023-01-17 2023-01-05 2023-01-26 2023-03-02 2023-08-29 IU Communication Officer ement ant Selection ation SO-MOF-333073-CS-INDV / A Component 3: Longer-Ter Individual Consult Under Implement IDA / D8730 Prior Open - National 0.00 2022-12-31 2023-02-18 2023-03-11 2023-04-15 2023-10-12 nesthetics/Intensivist Consult m Disaster Risk Preparednes ant Selection ation ant s SO-MOF-333077-CS-INDV / B Component 3: Longer-Ter Individual Consult Under Implement lood Bank Technologist for R IDA / D8730 m Disaster Risk Preparednes Prior Open - National 0.00 2022-12-31 2023-02-18 2023-03-11 2023-04-15 2023-10-12 ant Selection ation egional Referral Hospitals s SO-MOF-333079-CS-INDV / E Component 3: Longer-Ter Individual Consult Under Implement IDA / D8730 Prior Open - National 0.00 2022-12-31 2023-02-18 2023-03-11 2023-04-15 2023-10-12 mergency Medicine Consulta m Disaster Risk Preparednes ant Selection ation nt s SO-MOF-333082-CS-INDV / Component 3: Longer-Ter Individual Consult Under Implement Medical Laboratory Consulta IDA / D8730 m Disaster Risk Preparednes Prior Open - National 0.00 2022-12-31 2023-02-18 2023-03-11 2023-04-15 2023-10-12 ant Selection ation nt for Regional Referral Hospi s tals SO-MOF-331702-CS-INDV / C Component 4: Project Manag Individual Consult IDA / D8730 Post Limited 0.00 Canceled 2022-12-29 2023-01-03 2023-01-24 2023-02-28 2023-08-27 ommunication Officer, PIU ement ant Selection SO-MOF-333083-CS-INDV / I Component 3: Longer-Ter Individual Consult ntegration and Organizationa IDA / D8730 m Disaster Risk Preparednes Post Open - National 0.00 Canceled 2022-12-31 2023-02-13 2023-02-18 2023-03-11 2023-04-15 2023-10-12 ant Selection l Development Consultant for s NEOC/SODMA SO-MOF-344251-CS-INDV / F Component 4: Project Manag Individual Consult Under Implement IDA / D6300 Prior Direct - National 0.00 2023-02-25 2023-03-10 2023-03-07 2023-03-14 2023-03-28 2023-03-20 2023-05-02 2023-10-29 inancial Management Special ement ant Selection ation ist SO-MOF-344255-CS-INDV / I Component 3: Longer-Ter Individual Consult Under Implement ntegration and Organizationa IDA / D8730 m Disaster Risk Preparednes Prior Limited 0.00 2023-02-28 2023-04-10 2023-03-05 2023-03-26 2023-04-30 2023-10-27 ant Selection ation l Consultant for NEOC/SODM s A SO-MOF-350971-CS-CDS / C ONSULTING SERVICES TO SU Component 4: Project Manag Direct - Internation IDA / D6300 Prior Direct Selection 0.00 Under Review 2023-04-30 2023-06-08 2023-05-10 2023-06-17 2023-07-14 2024-01-10 PPORT THE SCRP PROJECT WI ement al TH SECURITY RISK MANAGEM ENT SO-MOF-357102-CS-INDV / E Component 3: Longer-Ter Individual Consult Under Implement mergency Medicine Consulta IDA / D6300 m Disaster Risk Preparednes Prior Limited 0.00 2023-05-31 2023-05-11 2023-06-05 2023-06-26 2023-07-31 2024-01-27 ant Selection ation nt – Banadir Hospital, Benadi s r Region SO-MOF-357104-CS-INDV / E Component 3: Longer-Ter Individual Consult Under Implement mergency Medicine Consulta IDA / D6300 m Disaster Risk Preparednes Prior Limited 0.00 2023-05-31 2023-05-11 2023-06-05 2023-06-26 2023-07-31 2024-01-27 ant Selection ation nt – Martini Hospital, Benadir s Region SO-MOF-357112-CS-INDV / E Component 3: Longer-Ter Individual Consult Under Implement mergency Medicine Consulta IDA / D6300 m Disaster Risk Preparednes Prior Limited 0.00 2023-05-31 2023-05-17 2023-06-05 2023-06-26 2023-07-31 2024-01-27 ant Selection ation nt – Hirshabelle State of Som s alia SO-MOF-357113-CS-INDV / E Component 3: Longer-Ter Individual Consult Under Implement mergency Medicine Consulta IDA / D6300 m Disaster Risk Preparednes Prior Limited 0.00 2023-06-30 2023-05-17 2023-07-05 2023-07-26 2023-08-30 2024-02-26 ant Selection ation nt – Jubbaland State of Somal s ia SO-MOF-357115-CS-INDV / E Component 3: Longer-Ter Individual Consult Under Implement mergency Medicine Consulta IDA / D6300 m Disaster Risk Preparednes Prior Limited 0.00 2023-05-31 2023-05-17 2023-06-05 2023-06-26 2023-07-31 2024-01-27 ant Selection ation nt – Government of Somalila s nd SO-MOF-357116-CS-INDV / E Component 3: Longer-Ter Individual Consult Under Implement mergency Medicine Consulta IDA / D6300 m Disaster Risk Preparednes Prior Limited 0.00 2023-06-30 2023-05-17 2023-07-05 2023-07-26 2023-08-30 2024-02-26 ant Selection ation nt – Galmudug State of Soma s lia SO-MOF-357117-CS-INDV / E Component 3: Longer-Ter Individual Consult Under Implement mergency Medicine Consulta IDA / D6300 m Disaster Risk Preparednes Prior Limited 0.00 2023-06-30 2023-05-17 2023-07-05 2023-07-26 2023-08-30 2024-02-26 ant Selection ation nt - Southwest State of Soma s lia Page 11 SO-MOF-357119-CS-INDV / E Component 3: Longer-Ter Individual Consult Under Implement mergency Medicine Consulta IDA / D6300 m Disaster Risk Preparednes Prior Limited 0.00 2023-07-31 2023-05-17 2023-08-05 2023-08-26 2023-09-30 2024-03-28 ant Selection ation nt – Puntland State of Somali s a SO-MOF-328359-CS-INDV / S Component 3: Longer-Ter Individual Consult enior Health Emergency Prep IDA / D8730 m Disaster Risk Preparednes Post Direct - National 0.00 Canceled 2022-12-10 2023-01-17 2022-12-20 2023-01-10 2023-02-14 2023-08-13 ant Selection aredness & Response Adviso s r SO-MOF-357121-CS-INDV / S Component 3: Longer-Ter Individual Consult Under Implement enior Health emergency prep IDA / D6300 m Disaster Risk Preparednes Prior Open - National 0.00 2023-06-30 2023-05-15 2023-08-18 2023-09-08 2023-10-13 2024-04-10 ant Selection ation aredness and Response Advi s sor SO-MOF-357128-CS-INDV / S Component 3: Longer-Ter enior Medical Technical Advis Individual Consult IDA / D6300 m Disaster Risk Preparednes Prior Open - National 0.00 Under Review 2023-05-31 2023-05-15 2023-07-19 2023-08-09 2023-09-13 2024-03-11 or for the Ministry of Health ant Selection s & Human Services SO-MOF-362318-CS-INDV / V Component 3: Longer-Ter Individual Consult Under Implement IDA / D6300 Prior Limited 0.00 2023-06-30 2023-07-05 2023-07-26 2023-08-30 2024-02-26 ector Control Advisor m Disaster Risk Preparednes ant Selection ation s SO-MOF-362320-CS-INDV / A Component 3: Longer-Ter Individual Consult Under Implement IDA / D6300 Prior Limited 0.00 2023-06-30 2023-07-05 2023-07-26 2023-08-30 2024-02-26 nimal Health Advisor m Disaster Risk Preparednes ant Selection ation s SO-MOF-362323-CS-INDV / F Component 3: Longer-Ter Individual Consult Under Implement ield Coordinator, Vector contr IDA / D6300 m Disaster Risk Preparednes Prior Limited 0.00 2023-06-30 2023-07-05 2023-07-26 2023-08-30 2024-02-26 ant Selection ation ol for Southwest State s SO-MOF-362418-CS-INDV / F Component 3: Longer-Ter Individual Consult Under Implement ield Coordinator, vector contr IDA / D6300 m Disaster Risk Preparednes Prior Limited 0.00 2023-06-30 2023-07-05 2023-07-26 2023-08-30 2024-02-26 ant Selection ation ol in Jubaland State s SO-MOF-362421-CS-INDV / F Component 3: Longer-Ter Individual Consult Under Implement ield Coordinator, vector contr IDA / D6300 m Disaster Risk Preparednes Prior Limited 0.00 2023-07-31 2023-08-05 2023-08-26 2023-09-30 2024-03-28 ant Selection ation ol in Hirshabelle State s SO-MOF-362428-CS-INDV / C Component 3: Longer-Ter Individual Consult IDA / D6300 Prior Open - National 0.00 Under Review 2023-06-20 2023-08-08 2023-08-29 2023-10-03 2024-03-31 apacity building specialist, N m Disaster Risk Preparednes ant Selection EOC s SO-MOF-362432-CS-INDV / I Component 3: Longer-Ter Individual Consult nformation management spe IDA / D6300 m Disaster Risk Preparednes Prior Open - National 0.00 Under Review 2023-06-20 2023-08-08 2023-08-29 2023-10-03 2024-03-31 ant Selection cialist, NEOC s SO-MOF-362434-CS-INDV / N Component 3: Longer-Ter Individual Consult IDA / D6300 Prior Open - National 0.00 Under Review 2023-06-20 2023-08-08 2023-08-29 2023-10-03 2024-03-31 EOC Coordinator m Disaster Risk Preparednes ant Selection s SO-MOF-362438-CS-INDV / N Component 3: Longer-Ter Individual Consult IDA / D6300 Prior Open - National 0.00 Under Review 2023-06-20 2023-08-08 2023-08-29 2023-10-03 2024-03-31 EOC Deputy Coordinator m Disaster Risk Preparednes ant Selection s SO-MOF-362440-CS-INDV / D Component 3: Longer-Ter Individual Consult Pending Impleme isaster Risk Management (DR IDA / D6300 m Disaster Risk Preparednes Prior Open - National 0.00 2023-06-20 2023-08-08 2023-08-29 2023-10-03 2024-03-31 ant Selection ntation M) specialist s SO-MOF-366795-CS-INDV / O Component 3: Longer-Ter Individual Consult IDA / D6300 Prior Open - National 0.00 Under Review 2023-06-20 2023-08-08 2023-08-29 2023-10-03 2024-03-31 perations Manager, NEOC m Disaster Risk Preparednes ant Selection s SO-MOF-366797-CS-INDV / P Component 3: Longer-Ter Individual Consult IDA / D6300 Prior Open - National 0.00 Under Review 2023-06-20 2023-08-08 2023-08-29 2023-10-03 2024-03-31 olicy & Planning Advisor, NE m Disaster Risk Preparednes ant Selection OC s SO-MOF-366804-CS-INDV / P Component 3: Longer-Ter Individual Consult IDA / D6300 Prior Open - National 0.00 Under Review 2023-06-20 2023-08-08 2023-08-29 2023-10-03 2024-03-31 rocurement & Logistics Office m Disaster Risk Preparednes ant Selection r, NEOC s SO-MOF-366805-CS-INDV / Li Component 3: Longer-Ter Individual Consult IDA / D6300 Prior Open - National 0.00 Under Review 2023-06-21 2023-08-09 2023-08-30 2023-10-04 2024-04-01 aison Officer, NEOC m Disaster Risk Preparednes ant Selection s SO-MOF-366806-CS-INDV / P Component 3: Longer-Ter Individual Consult IDA / D6300 Prior Open - National 0.00 Under Review 2023-06-20 2023-08-08 2023-08-29 2023-10-03 2024-03-31 lanning Officer, NEOC m Disaster Risk Preparednes ant Selection s SO-MOF-366808-CS-INDV / E Component 4: Project Manag Individual Consult nvironmental & Safeguard Sp IDA / D8730 Prior Open - National 0.00 Under Review 2023-06-20 2023-08-08 2023-08-29 2023-10-03 2024-03-31 ement ant Selection ecialist, PIU Page 12 REPUBLIQUE DE CENTRAFRIQUE Projet d’Amélioration des Services d’Eau et d’Electricité (PASEEL) P162245 « Numéro du crédit ou du Don » PLAN SIMPLIFIE DE PASSATION DES MARCHES (VERSION 15 JUILLET 2017) Information sur le Projet : République Centrafricaine - Projet Eau & Energie – P162245 Agence d’exécution du Projet : Sous – traitant Coordination du Projet Transit et Transit en zone CEMAC Date du plan de passation des marchés : 16 Mai 2017 Période couverte par ce plan de passation des marchés : Juin 2017 à Mai 2018 I. PRÉAMBULE Conformément au paragraphe 5.9 du “Règlement de Passation des Marchés pour les Emprunteurs sollicitant le Financement de Projets d’Investissement (FPI)” (Juillet 2016) (“Règlement de Passation des Marchés”) le Système électronique de la Banque de suivi systématique des transactions de marchés publics (STEP) sera utilisé pour préparer, valider et actualiser les plans de passation des marchés et effectuer toutes les transactions liées à la passation des marchés du projet. Ce texte ainsi que les tableaux du plan de passation des marchés présents dans STEP constituent le plan de passation des marchés du projet. Les conditions suivantes s'appliquent à toutes les activités de passation de marchés du plan de passation de marchés. Les autres éléments du plan de passation des marchés tels que requis au paragraphe 4.4 du Règlement de passation des marchés sont énoncés dans STEP. Les Dossiers types de passation des marchés publics de la Banque devront être utilisés pour tous les contrats soumis à la concurrence internationale, ainsi que pour tous les autres contrats soumis à cette obligation telle que spécifiée dans les tableaux du plan de passation des marchés de STEP. Procédures nationales de passation des marchés : En accord avec le paragraphe 5.3 du Règlement de passation des marchés, dans le cas où la procédure de passation des marché se fera au niveau national (telle que spécifiée dans les tableaux du plan de passation des marchés inclus de STEP), les procédures nationales de passation des marchés du pays considéré pourront être utilisées. Page 1 of 11 Si l’Emprunteur utilise ses propres procédures d’appel d’offres national ouvert telles qu’énoncées par la Loi n°08.017 portant Code des Marchés Publics et Délégations de Service Publics en République Centrafricaine, ces arrangements sont soumis aux dispositions du paragraphe 5.4 du Règlement de passation des marchés. Lorsque l’Emprunteur utilise d’autres procédures que l’appel d’offres national ouvert, ces procédures devront être en accord avec les dispositions du paragraphe 5.5 du Règlement de passation des marchés. Crédit-bail tel que spécifié au paragraphe 5.10 du Règlement de Passation des marchés : Le crédit-bail peut être utilisé pour les contrats indiqués comme tel dans le Plan de passation des marchés : « Sans objet » Achat de biens d’occasion tel que spécifié au paragraphe 5.11 du Règlement de Passation des Marchés est autorisé pour les contrats indiqués comme tel dans le Plan de passation des marchés : « Sans objet » Préférence nationale telle que spécifiée au paragraphe 5.51 du Règlement de Passation des Marchés (Fournitures et Travaux). Fournitures : ne s’applique pas pour les contrats indiqués dans les tableaux du Plan de passation des marchés. Travaux ne s’applique pas pour les contrats indiqués dans les tableaux du Plan de passation des marchés. Autres informations pertinentes sur la passation des marchés Indiquer toute autre information pertinente relative aux procédures de passation, telle que par exemple l’utilisation de procédures de participation communautaire au développement (CDD), de l’utilisation de procédures pour un besoin urgent d’assistance ou de faible capacité, etc. Page 2 of 11 II. TRAVAUX, FOURNITURES ET SERVICES NON INTELLECTUELS 1. Dispositions relatives aux seuils de revue préalable : Seuils requis pour les décisions de marchés soumis au contrôle de la passation des marchés, tel que prévu dans l’annexe II du "Règlement de Passation des pour les Emprunteurs sollicitant de la Banque mondiale le Financement de Projets d’Investissement (FPI)’’. Méthodes de Seuils de Examen par la Catégorie passation Option de marchés revue en Banque des marchés USD ≥ Tous les contrats Appel Internationale 5.000.000 d’Offres < Le premier Nationale Travaux 5.000.000 contrat Demande de Aucun Internationale/Nati cotations <200.000 onale (DC) ≥ Tous les contrats Fournitures Appel Internationale 500.000 et services d’Offres < Le premier autres que Nationale 500.000 contrat services de Demande de Internationale/Nati Aucun consultant <100.000 cotations onale 2. Seuils pour les méthodes de passation des marchés : Les seuils de passation des marchés se présentent comme suit au vu des conditions du marché : TRAVAUX (US$ équivalent) FOURNITURES (US$ équivalent) Demande Demande Appel d’offres de Appel d’offres de Cotations Cotations Internatio National International/Na Internatio National International/Nat nal tional nal ional < ≥ ≥ <500.00 5.000.00 < 200,000 < 100,000 5,000.000 500.000 0 0 3. Référence (s’il y en a) au Manuel d’exécution du projet/Manuel de Passation des Marchés : Manuel des Procédures Administrative, Financière et Comptable. 4. Autres arrangements spécifiques pour la passation des marchés : Concernant les acquisitions de véhicules et de carburant, en fonction des circonstances et des besoins spécifiques du pays, le seuil pour la consultation de fournisseurs pourrait être porté à la contre-valeur de USD 500,000 (en prenant soin de consulter tous les principaux concessionnaires de marque ou distributeurs de produits pétroliers) ; Page 3 of 11 5. Autres modalités nationales de passation des marchés : En conformité avec le paragraphe 5.5 du "Règlement de Passation des pour les Emprunteurs sollicitant de la Banque mondiale le Financement de Projets d’Investissement (FPI)’’, les autres modalités nationales de passation des marchés (autres que sous forme d’appel d’offres/a propositions national ouvert) qui pourraient être appliquées par l’Emprunteur (appel d’offres limite/restreint, demande de prix/consultation des fournisseurs, entente directe) doivent être conformes avec les Principes Fondamentaux de passation des marchés de la Banque et garantir que les Directives de lutte contre la corruption, son cadre de sanctions et les recours contractuels vises dans l’Accord Juridique s’appliquent. Page 4 of 11 6. Liste des marchés avec les méthodes de passation et les dates de mise en œuvre Fournitures, Travaux et Services autres que services de consultants 1 2 3 4 5 6 7 8 9 Date Pré Revue de Comment Ré Méthode Préférenc prévue Coût qualific la Banque aires / Fin f. passatio e de Description estimatif ation (à priori / de No n des nationale l’ouvertu (US$) (oui/no à prestation . marchés (oui/non) re des n) posteriori) s offres Acquisition du matériel informatique pour assistant comptable, assistant en passation des A 1 50,000 DC NON NON 31/10/17 marchés, expert suivi- posteriori évaluation, expert technique, et expert environnemental et social Frais de fonctionnement et de 2 logistique jusqu’à la 50,000 DC NON NON A posteriori 31/10/17 mise en œuvre du Projet Page 5 of 11 Coût total en US$ 100,000 Page 6 of 11 III. SÉLECTION DES CONSULTANTS 1. Dispositions relatives aux seuils de revue préalable des marchés : Décisions de sélection sujet au contrôle de la passation des marchés, tel que prévu dans l’annexe II du "Règlement de Passation des pour les Emprunteurs sollicitant le Financement de Projets d’Investissement (FPI)’’. Seuils Méthodes de de Examen par Catégorie sélection revue la Banque en USD SFQC ; SFQ ; ≥ Tous les Services de SBCD ; SMC ; CQ 200.000 contrats Consultant (firmes) ≥ Tous les SED 100.000 contrats ≥ Tous les SED Consultants 100.000 contrats Individuels Comparaison de ≥ Tous les CVs) 200.000 contrats 2. Liste restreinte composée entièrement de firmes nationales: La liste restreinte de consultants pour les prestations d’études d’ingénierie, de contrôle et de surveillance estimées à moins de 200,000 US$ par contrat, et pour tout autre type de prestations, estimées à moins de 100 000 US$ par contrat, peut comporter entièrement de consultants nationaux selon les dispositions du paragraphe 7.25 du "Règlement de Passation des pour les Emprunteurs sollicitant de la Banque mondiale le Financement de Projets d’Investissement (FPI)’’. 3. Autres arrangements spécifiques pour la Sélection de consultants : Le seuil pour l’utilisation de la méthode de sélection de consultant fondée sur les qualifications des consultants est déterminé au cas par cas en tenant compte de la nature et de la complexité de la mission; cependant, ce seuil ne devrait pas dépasser la contre-valeur de USD 300,000 sauf dans des cas exceptionnels prévus au paragraphe 7.12 du "Règlement de Passation des pour les Emprunteurs sollicitant de la Banque mondiale le Financement de Projets d’Investissement (FPI) ". Page 7 of 11 4. Liste des Consultations, avec les méthodes de sélection et le calendrier de mise œuvre 1 2 3 4 5 6 7 Revue Date de la Coût Méthod prévue de Ref Banque Commentaires/ estimatif e de soumissio . Description des Missions (à priori Fin de ($EU) 1$ = sélectio n des No. /à prestations 600 FCFA n propositio posterio ns ri) Etude détaillée des travaux hydrauliques devant être 1 250,000 QC A priori 15/10/17 réalisées à Bangui et Berberati (SODECA) + contrôle des travaux Audit énergétique des A 2 infrastructures hydrauliques de la 50,000 CI 31/10/17 posteriori SODECA Le bureau d’études CONCEPT SA a été recruté par le Ministère dans le cadre du projet BADEA pour réaliser Etudes APS, APD et DAO pour les les études à travaux hydrauliques à réaliser 3 200,000 ED A priori 31/10/17 Bambari. Il est dans Bambari + contrôle des proposé de faire un travaux avenant au contrat de ce BE qui intervient déjà à Bambari pour un projet complémentaire. Page 8 of 11 1 2 3 4 5 6 7 Revue Date de la Coût Méthod prévue de Ref Banque Commentaires/ estimatif e de soumissio . Description des Missions (à priori Fin de ($EU) 1$ = sélectio n des No. /à prestations 600 FCFA n propositio posterio ns ri) Réalisation d’un Plan de Sécurité A 4 60,000 CI 15/10/17 du barrage de Boali posteriori Réalisation du Manuel A 5 30,000 CI 15/10/17 d’exécution du projet posteriori Réalisation des Etudes d’Impact Environnementales et Sociales (EIES), y compris les Plans de A 6 150,000 QC 31/10/17 Gestion Environnemental et posteriori Social (PGES), et les PARs – Eau et Energie, à Bambari Réalisation des Etudes d’Impact Environnementales et Sociales (EIES), y compris les Plans de A 7 130,000 QC 31/10/17 Gestion Environnemental et posteriori Social (PGES), et les PARs – Eau et Energie, à Berberati Réalisation des Etudes d’Impact Environnementales et Sociales (EIES), y compris les Plans de 8 210,000 QC A priori 31/10/17 Gestion Environnemental et Social (PGES), et les PARs – Eau et Energie à Bangui Page 9 of 11 1 2 3 4 5 6 7 Revue Date de la Coût Méthod prévue de Ref Banque Commentaires/ estimatif e de soumissio . Description des Missions (à priori Fin de ($EU) 1$ = sélectio n des No. /à prestations 600 FCFA n propositio posterio ns ri) Diagnostic opérationnel et APS des installations de génération et distribution de l’ENERCA dans six 9 230,000 QC A priori 15/11/17 villes secondaires (Berberati, Ndélé, Bria, Kaga-Bandoro, Bangassou et Sibut) Diagnostic opérationnel, APS + A 10 niveau APD/DAO et contrôle des 100,000 QC 31/10/17 posteriori travaux à Bambari, volet énergie Diagnostic opérationnel/Etat des A 11 lieux des installations de 100,000 CI 30/10/17 posteriori distribution de l’ENERCA à Bangui A 12 Elaboration du PPSD 30,000 CI 15/10/17 posteriori A 13 Audit financier du PPSD 20,000 QC 31/01/18 posteriori Recrutement d’un Assistant 14 20,000 CI A priori 15/10/17 comptable Assistant en passation des 15 20,000 CI A priori 15/10/17 marchés 16 Expert en suivi-évaluation 20,000 CI A priori 15/10/17 17 Expert environnement 20,000 CI A priori 15/10/17 Page 10 of 11 1 2 3 4 5 6 7 Revue Date de la Coût Méthod prévue de Ref Banque Commentaires/ estimatif e de soumissio . Description des Missions (à priori Fin de ($EU) 1$ = sélectio n des No. /à prestations 600 FCFA n propositio posterio ns ri) 18 Expert en développement Social 20,000 CI A priori 15/10/17 19 Expert technique énergie 20,000 CI A priori 15/10/17 20 Expert technique eau 20,000 CI A priori 15/10/17 Coût total en US$ 1,700,000 Lexique des Sigles et Abréviations AO : Appel d’Offres Ouvert SMC : Sélection au Moindre Coût DC : Demande de Cotations CI : Consultant Individuel SFQC : Sélection Fondée sur la Qualité et le Coût A posteriori : Revue à posteriori SFQ : Sélection Fondée sur la Qualité A Priori : Revue à priori QC : Sélection fondée sur les Qualifications des PPM : Plan de Passation des Marchés Consultants SED : Sélection par Entente Directe Page 11 of 11 PROCUREMENT Central African Republic : Water and Electricity Upgrading Project PLAN General Information Country: Central African Republic 2017-11-10 Bank’s Approval Date of the Original Procurement Plan: 2023-06-07 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P162245 GPN Date: Project Name: Water and Electricity Upgrading Project Loan / Credit No: IDA / D2690, / , IDA / V1340 Water and Electricity Upgrading Project Executing Agency(ies): WORKS Activity Reference No. / Procureme Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH Ri Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method nt Docume ount (US$ and Recommendation Signed Contract o. h cess (Y/N) sk atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion nt Type ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PASEEL/045/CW/RFB/19 / Be rberati AEP-Travaux de réhab Single Stage - One E 1,703,778.0 2020-05-1 ilitation des infrastructures d IDA / D2690 Water Supply Infrastructure Post Request for Bids Open - National Signed 2019-07-25 2019-10-23 2019-07-30 2019-10-23 2019-09-10 2019-11-22 2019-10-10 2020-03-02 2019-11-14 2020-06-08 nvelope 9 2 es infrastructures d'alimenta tion en eau dans la ville de B erberati PASEEL/053/CW/RFB/19 / Ea u Bangui-Travaux de réhabili Single Stage - One E 2020-08-3 IDA / D2690 Water Supply Infrastructure Post Request for Bids Open - National 0.00 Canceled 2019-11-13 2019-11-18 2019-12-30 2020-01-29 2020-03-04 tation des infrastructures d'al nvelope 1 imentation en eau potable de la ville de Bangui. PASEEL/056/CW/RFB/19 / Re bobinage-Travaux de rebobin Single Stage - One E 1,343,699.6 2020-09-0 IDA / D2690 Energy Infrastructure Post Request for Bids Open - National Signed 2019-11-18 2019-12-19 2019-11-23 2020-01-04 2020-03-05 2020-02-03 2020-03-06 2020-03-09 2020-10-24 age des alternateurs des Gro nvelope 9 5 upes G2, G3, G4 et G5 de Bo ali 1 PASEEL/052/CW/RFB / Eau B ambari-Travaux de réhabilita Single Stage - One E 2,028,639.2 2020-09-0 IDA / D2690 Water Supply Infrastructure Post Request for Bids Open - National Signed 2019-11-22 2020-01-15 2019-11-27 2020-01-08 2020-02-17 2020-02-07 2020-03-25 2020-03-13 2020-08-30 tion des infrastructures d'ali nvelope 3 9 mentation en eau potable de la ville de Bambari PASEEL/054/CW/RFB/19 / En ergie de 2 villes-Travaux de r Single Stage - One E 1,939,143.7 2020-09-2 éhabilitation et d'amélioratio IDA / D2690 Energy Infrastructure Prior Request for Bids Open - National Signed 2019-12-03 2020-01-22 2019-12-08 2020-02-06 2020-01-19 2020-04-03 2020-02-18 2020-06-15 2020-03-24 2020-08-27 nvelope 5 0 n de l'alimentation en électri cité dans les villes de Bamba ri et Berberati PASEEL/065/CW/RFB/20 / Ce ntrales hybrides-Construction Open - Internationa Single Stage - One E 2,365,433.3 2021-05-0 des ouvrages de production IDA / D2690 Energy Infrastructure Post Request for Bids Signed 2020-07-15 2020-07-13 2020-07-20 2020-07-24 2020-08-31 2020-09-18 2020-09-30 2020-10-26 2020-11-04 2021-04-11 l nvelope 5 3 de centrales hybrides (solaire PV-Diesel) dans les villes de Bambari et Berberati. PASEEL/078/CW/RFQ/21 / Dé Other (with fi molition Bambari-Travaux de Technical Support to Water Request for Quota Single Stage - One E 2022-05-1 2021-10 IDA / D2690 Post Limited eld for expla 5,691.55 Completed 2021-09-25 2021-09-02 2021-11-20 2021-10-07 démolition et de nettoyage d and Energy Sectors tions nvelope 9 -17 nation) u site de l'ENERCA à Bambari . PASEEL/079/CW/RFQ/21 / Dé Other (with fi molition Berberati-Travaux d Technical Support to Water Request for Quota Single Stage - One E 2022-05-1 2021-11 IDA / D2690 Post Limited eld for expla 19,878.23 Completed 2021-09-21 2021-09-02 2021-11-16 2021-10-08 e démolition, abattage d'arbr and Energy Sectors tions nvelope 5 -05 nation) es et nettoyage du site de l'E NERCA à Berberati. Request for PASEEL/0097/CW/DIR/23 / R Quotations - éalisation de forages-Travau Technical Support to Water Small Works Under Imple 2023-11-2 x de réalisation et d'équipem IDA / D2690 Post Direct Selection Direct - National 0.00 2023-04-18 2023-05-09 2023-04-23 2023-05-10 2023-05-28 and Energy Sectors (Emergency) mentation 4 ents de 2 forages y compris SPD -Non Co un forage témoin à Berberati. mpetitive PASEEL/097/CW/RFQ/22 / Ré alisation de forages-Travaux Other (with fi Technical Support to Water Request for Quota Single Stage - One E 2023-06-0 de réalisation et d'équipeme IDA / D2690 Post Limited eld for expla 0.00 Canceled 2022-10-10 2022-12-05 and Energy Sectors tions nvelope 3 nts de 2 forages y compris u nation) n forage témoin à Berberati. GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CF- PASEEL-38235-GO-RFQ / Acquisition du matériel infor matique pour les experts (Pa Technical Support to Water Request for Quota Single Stage - One E IDA / D2690 Post Limited 30,074.23 Completed 2017-12-31 2018-06-29 2018-02-25 2019-03-23 2018-08-24 2019-04-30 ssation des Marchés, Compta and Energy Sectors tions nvelope ble, Suivi-évaluation et exper t environnemental et social) PASEEL-20-IND-18 / Acquisiti on des moyens roulants - Ac Technical Support to Water Request for Quota Single Stage - One E hat des véhicules (2 double c IDA / D2690 Post Limited 190,572.56 Completed 2018-04-30 2018-04-20 2018-06-25 2018-05-29 2018-12-22 2018-07-24 and Energy Sectors tions nvelope abine, une berline) et 10 mot os pour la supervision des a ctivités du Projet PASEEL/O21/FOUR/DC/18 / C Request for Quota Single Stage - One E arburant-Acquisition de carb IDA / D2690 Water Supply Infrastructure Post Limited 101,955.32 Completed 2018-08-20 2019-07-15 2018-10-15 2019-03-16 2019-04-13 2020-11-21 tions nvelope urant pour la SODECA PASEEL/O23/FOUR/AOI/18 / Branchements sociaux-Acqui Open - Internationa Single Stage - One E IDA / D2690 Water Supply Infrastructure Post Request for Bids 1,180,710.11 Completed 2018-12-07 2020-02-03 2018-12-12 2019-01-23 2019-03-21 2019-02-22 2019-05-16 2019-03-29 2020-07-28 2019-09-25 2021-07-02 sition d'équipements d'exten l nvelope sion et de branchements soci aux pour la SODECA. PASEEL/22/FOUR/DC/18 / Pro duits chimiques-Acquisition d Request for Quota Single Stage - One E IDA / D2690 Water Supply Infrastructure Post Open - National 0.00 Canceled 2019-01-19 2019-03-16 2019-09-12 e consommables (produits ch tions nvelope imiques) pour la SODECA PASEEL/033/FOUR/CF/18 / D étection fuite-Acquisition d'é Request for Quota Single Stage - One E IDA / D2690 Water Supply Infrastructure Post Limited 23,148.34 Completed 2019-02-04 2021-04-01 2019-04-01 2021-10-12 2019-09-28 2022-07-20 quipements de détection de f tions nvelope uite sur le réseau de distribut ion de la SODECA Page 1 PASEEL/O22/FOUR/AON/18 / Single Stage - One E Produits chimiques-Acquisitio IDA / D2690 Water Supply Infrastructure Post Request for Bids Open - National 0.00 Canceled 2018-11-29 2018-12-04 2019-01-15 2019-02-14 2019-03-21 2019-09-17 nvelope n de consommables pour la S ODECA PASEEL/035/FOUR/DC/18 / El Request for Quota Single Stage - One E ectropompes - Fourniture d'é IDA / D2690 Water Supply Infrastructure Post Limited 0.00 Canceled 2019-01-12 2019-03-09 2019-09-05 tions nvelope lectropompes à la SODECA PASEEL/038/FOUR/DIR/19 / E lectropompes de captage: Fo Contingent Emergency Resp IDA / D2690 Post Direct Selection Direct 473,708.04 Signed 2019-05-16 2019-09-07 2019-05-21 2019-09-07 2019-06-25 2019-07-16 2019-12-22 urniture d'électropompes de onse captage d'eau brute à la SOD ECA PASEEL/040/FOUR/DIR/19 / E lectropompes de refoulement Contingent Emergency Resp - Fourniture et installation d' IDA / D2690 Post Direct Selection Direct 203,227.14 Signed 2019-05-16 2019-11-19 2019-05-21 2019-11-25 2019-06-25 2019-10-18 2019-12-22 onse électropompes de refouleme nt d'eau vers les réservoirs R 2, R3 et R4 à la SODECA. PASEEL/022/FOUR/RFB/19 / Single Stage - One E Produits chimiques - Fournitu IDA / D2690 Water Supply Infrastructure Post Request for Bids Open - National 201,207.87 Completed 2019-05-27 2019-07-25 2019-06-01 2019-07-13 2019-09-03 2019-08-12 2020-02-27 2019-09-16 2019-10-20 2020-03-14 2020-01-20 nvelope re de produits chimiques à la SODECA PASEEL/19/GO/RFB/19 / Bloc Single Stage - One E de réserve-Acquisition de Tra IDA / D2690 Energy Infrastructure Post Request for Bids Open - National 85,523.75 Completed 2019-11-05 2019-11-21 2019-11-10 2019-12-16 2019-12-22 2019-12-20 2020-01-21 2020-01-03 2020-02-25 2020-04-09 2020-08-23 2020-10-23 nvelope nsformateurs de Puissance PASEEL/055/GO/RFQ/19 / Tra Request for Quota Open - Internationa Single Stage - One E nsformateur-Acquisition de tr IDA / D2690 Energy Infrastructure Post 0.00 Canceled 2019-11-05 2019-12-31 2020-06-28 tions l nvelope ansformateurs de courant. PASEEL/057/GO/RFQ/19 / Pet its outillages-Acquisition de p Request for Quota Single Stage - One E Under Imple IDA / D2690 Water Supply Infrastructure Post Limited 0.00 2019-11-18 2019-11-20 2020-01-13 2020-07-11 etits outillages pour les instal tions nvelope mentation lations des électropompes fo urnies à la SODECA. PASEEL/058/GO/DIR/19 / Mat ériels informatiques-Acquisiti Technical Support to Water on de matériels informatique IDA / D2690 Post Direct Selection Direct 43,017.59 Completed 2019-10-31 2021-01-20 2019-11-05 2021-04-06 2019-12-10 2021-05-06 2020-06-07 2021-06-01 and Energy Sectors s pour certains cadres Minist ériels acteurs du Projet PASSEEL/049/GO/RFB/19 / C ompteurs-Acquisition de com pteurs à prépaiement et com Open - Internationa Single Stage - One E IDA / D2690 Energy Infrastructure Prior Request for Bids 872,468.94 Completed 2019-11-26 2020-01-06 2019-12-01 2020-01-16 2020-01-12 2020-03-31 2020-02-11 2020-05-15 2020-03-17 2020-06-13 2020-09-13 2021-12-05 municants pour l'amélioratio l nvelope n des performances commer ciales de l'ENERCA à BANGUI PASEEL/50/GO/RFB/19 / Rem Single Stage - One E placement cellules-Acquisitio IDA / D2690 Energy Infrastructure Prior Request for Bids Open - National 318,725.00 Completed 2019-11-29 2019-12-27 2019-12-04 2020-04-22 2020-01-15 2020-03-06 2020-02-14 2020-04-27 2020-03-20 2020-07-10 2020-09-16 2021-05-15 nvelope n des équipements de postes HTA/BT PASEEL/059/GO/RFQ/19 / Elé ments armoires-Fournitures Request for Quota Single Stage - One E Under Imple des éléments d'armoires de c IDA / D2690 Water Supply Infrastructure Post Limited 0.00 2020-01-04 2020-02-20 2020-02-29 2020-08-27 tions nvelope mentation ommande des électropompe s de refoulement d'eau. PASEEL/067/GO/DIR/21 / Acq uisition du logiciel de gestion Technical Support to Water IDA / D2690 Post Direct Selection Direct 17,742.81 Signed 2021-02-01 2021-04-27 2021-02-06 2021-04-30 2021-03-13 2021-06-26 2021-09-09 financière TOM2PRO et la for and Energy Sectors mation des utilisateurs. PASEEL/71/GO/DIR/21 / Carb urant ENERCA-Acquisition de Technical Support to Water IDA / D2690 Post Direct Selection Direct 0.00 Canceled 2021-04-30 2021-05-05 2021-06-09 2021-12-06 carburant et mise à dispositi and Energy Sectors on de l'ENERCA et certains H ôpitaux PASEEL/072/GO/RFQ/21 / Ma tériels branchements-Acquisi Request for Quota Single Stage - One E tion de matériels informatiqu IDA / D2690 Water Supply Infrastructure Post Limited 7,637.28 Completed 2021-06-01 2021-06-01 2021-07-27 2021-08-18 2022-01-23 2021-09-08 tions nvelope es et équipements de collect e pour la mise en œuvre des branchements sociaux. PASEEL/074/GO/RFQ/21 / Eq uipements branchements-Ac Request for Quota Single Stage - One E quisition d'outillage et d'équi IDA / D2690 Water Supply Infrastructure Post Limited 7,852.30 Completed 2021-05-31 2021-05-31 2021-07-26 2021-08-18 2022-01-22 2021-08-28 tions nvelope pements de chantier pour la mise en œuvre des branche ments sociaux PASEEL/075/GO/RFB/21 / Vé hicules branchements sociau Single Stage - One E x-Acquisitions de matériels r IDA / D2690 Water Supply Infrastructure Post Request for Bids Open - National 98,006.81 Completed 2021-05-31 2021-06-03 2021-06-05 2021-06-17 2021-07-17 2021-07-21 2021-08-16 2021-07-23 2021-09-20 2021-09-01 2022-03-19 2021-10-15 nvelope oulants pour la mise en œuvr e des branchements sociaux. PASEEL/077/GO/RFB/21 / Tra Single Stage - One E nsfo Courant-Acquisition de t IDA / D2690 Energy Infrastructure Post Request for Bids Open - National 140,919.92 Signed 2021-09-21 2021-09-20 2021-09-26 2021-09-23 2021-11-07 2021-10-26 2021-12-07 2021-11-24 2022-01-11 2022-02-08 2022-07-10 nvelope ransformateurs de courant à l'ENERCA. PASEEL/082/GO/RFQ/21 / Br anchements sociaux-Acquisit Request for Quota Single Stage - One E IDA / D2690 Water Supply Infrastructure Post Limited 12,815.41 Completed 2021-10-16 2021-10-11 2021-12-11 2021-11-25 2022-06-09 2021-12-22 ion de supports de communic tions nvelope ation pour les activités de br anchements sociaux. PASEEL/085/RFQ/21 / Fournit Technical Support to Water Request for Quota Single Stage - One E ure bureau-Acquisition de fou IDA / D2690 Post Limited 8,726.29 Completed 2021-10-17 2022-01-25 2021-12-12 2022-03-22 2022-06-10 2022-04-30 and Energy Sectors tions nvelope rnitures de bureaux PASEE/086/GO/RFQ/21 / Bra nchements électriques-Achat Technical Support to Water Request for Quota Single Stage - One E de matériels de branchement IDA / V1340 Post Limited 67,212.76 Completed 2021-12-22 2021-12-22 2022-02-16 2022-03-22 2022-08-15 2022-06-23 and Energy Sectors tions nvelope s électriques à Bambari et Be rberati par l'ENERCA. PASEEL/080/GO/RFB/21 / Gr oupe 1250 KVA-Acquisition e Technical Support to Water Single Stage - One E t installation d'un groupe éle IDA / D2690 Post Request for Bids Open - National 0.00 Canceled 2021-09-20 2021-09-17 2021-09-25 2021-09-21 2021-11-06 2021-11-18 2021-12-06 2022-01-10 2022-07-09 and Energy Sectors nvelope ctrogène de 1250 KVA à la st ation de traitement de la SO DECA à Bangui. Page 2 PASEEL/087/GO/CDS/21 / GA LATE-Mise à jour du logiciel d Technical Support to Water IDA / V1340 Post Direct Selection Direct 0.00 Signed 2021-12-27 2021-12-22 2022-01-01 2023-03-16 2022-02-05 2022-08-04 e gestion (GALATE) de la clie and Energy Sectors ntèle de la SODECA. PASEEL/088/GO/RFQ/21 / Gr Technical Support to Water Single Stage - One E oupe 650 kva-Achat d'un gro IDA / V1340 Post Request for Bids Open - National 109,580.00 Signed 2021-12-27 2021-12-21 2022-01-01 2021-12-23 2022-02-12 2022-01-28 2022-03-14 2022-02-07 2022-04-18 2022-03-22 2022-10-15 and Energy Sectors nvelope upe électrogène de 650 KVA à la SODECA. PASEEL/092/GO/DIR/22 / Gro upe SODECA-Acquisition d'un Technical Support to Water IDA / D2690 Post Direct Selection Direct - National 48,771.52 Completed 2022-07-14 2022-07-19 2022-07-19 2022-07-19 2022-08-23 2022-07-20 2023-02-19 2022-07-27 groupe électrogène de 100 K and Energy Sectors VA à la SODECA, Agence de BERBERATI PASEEL/091/GO/RFQ/22 / Ac quisition de matériels et équi Technical Support to Water Single Stage - One E pements pour la mise en plac IDA / D2690 Post Request for Bids Open - National 0.00 Canceled 2022-03-14 2022-03-21 2022-03-19 2022-03-22 2022-04-30 2022-05-30 2022-07-04 2022-12-31 and Energy Sectors nvelope e du Système d'Information Géographique (SIG) de la SO DECA. PASEEL/093/GO/RFQ/22 / Ma tériels SIG-Acquisition de mat Technical Support to Water Single Stage - One E Under Imple ériels et équipements pour la IDA / D2690 Post Request for Bids Open - National 0.00 2022-09-27 2022-09-27 2022-10-02 2022-10-11 2022-11-13 2022-12-13 2023-01-17 2023-07-16 and Energy Sectors nvelope mentation mise en place du Système d'I nformation Géographique (SI G) de la SODECA. PASEEL/090/GO/RFQ/22 / Ac quisition de matériels et équi Technical Support to Water Request for Quota Single Stage - One E IDA / D2690 Post Open - National 0.00 Signed 2022-03-12 2022-05-07 2022-11-03 pements pour la mise à jour and Energy Sectors tions nvelope du progiciel GALATE de la SO DECA. PASEEL/098/GO/RFQ/22 / Co mpteurs eau-Acquisition de 5 Technical Support to Water Request for Quota Single Stage - One E IDA / D2690 Post Limited 0.00 Canceled 2022-10-08 2022-12-03 2023-06-01 00 compteurs d'eau en maté and Energy Sectors tions nvelope riau plastic pour la SODECA. PASEEL/099/GO/DIR/22 / Tub es Galva-Acquisition de 600 t Technical Support to Water IDA / D2690 Post Direct Selection Direct - National 0.00 Completed 2022-09-26 2022-10-10 2022-10-01 2022-10-18 2022-11-05 2023-05-04 2022-12-31 ubes Galva de 6 mètres linéa and Energy Sectors ires y compris les coudes. PASEEL/095/GO/CDS/22 / Vé hicules distribution-Acquisitio n de matériels roulants pour l Technical Support to Water IDA / D2690 Post Direct Selection Direct - National 0.00 Signed 2022-10-17 2022-10-10 2022-10-23 2022-10-21 2022-11-27 2023-05-26 a mise en œuvre de la distrib and Energy Sectors ution d'électricité dans les vil les de Bambari et Berberati PASEEL/100/GO/RFQ/22 / Div ers outillages-Acquisition de Technical Support to Water Request for Quota Single Stage - One E divers outillages pour les acti IDA / D2690 Post Limited 0.00 Completed 2022-12-03 2022-12-06 2023-01-28 2023-07-27 2023-01-16 and Energy Sectors tions nvelope vités de branchements socia ux de la SODECA à Bambari et Berberati. PASEEL/0101/GO/RFQ/22 / M atériels informatiques-Acquis ition de matériels et équipem Technical Support to Water Request for Quota Single Stage - One E IDA / D2690 Post Limited 0.00 Canceled 2022-12-04 2023-01-29 2023-07-28 ents informatiques pour les a and Energy Sectors tions nvelope ctivités de branchements soc iaux de la SODECA à Bambari et Berberati. PASEEL/102/GO/RFQ/22 / Co mpteurs eau-Acquisition de 2 Technical Support to Water Request for Quota Single Stage - One E IDA / D2690 Post Limited 0.00 Completed 2022-12-05 2022-12-07 2023-01-30 2023-07-29 2023-02-05 500 compteurs d'eau en mat and Energy Sectors tions nvelope ériau plastic pour la SODECA PASEEL/104/GO/DIR/22 / Mat ériels roulants - Acquisition d e 2 véhicules pour les branch IDA / D2690 Water Supply Infrastructure Post Direct Selection Direct - National 0.00 Signed 2022-12-15 2022-12-13 2022-12-20 2022-12-13 2023-01-24 2023-07-23 ements sociaux et 2 motos p our appuyer les service régio naux Eau-Energie à Bambari et Berberati. PASEEL/105/GO/RFQ/22 / Sor ties HTA - Acquisition de mat ériels pour la reprise des sort Request for Quota Single Stage - One E ies HTA des départs du résea IDA / D2690 Energy Infrastructure Post Open - National 0.00 Signed 2022-12-21 2023-02-15 2023-08-14 tions nvelope u de Berberati et lampadaire s solaires pour l'éclairage de sécurité au pourtour des cha mps solaires à Bambari et Be rberati PASEEL/107/GO/RFQ/22 / Ac quisition ordinateurs - Acquis ition de 8 ordinateurs et 4 im Technical Support to Water Request for Quota Single Stage - One E IDA / D2690 Post Open - National 0.00 Signed 2022-12-17 2023-02-11 2023-08-10 primantes pour appuyer les d and Energy Sectors tions nvelope irections régionales Eau/Ener gie de Bambari et Berberati p our les collectes de données PASEEL/103/GO/RFQ/22 / Ré paration conduite - Acquisitio Single Stage - One E n des matériels pour la répar IDA / D2690 Water Supply Infrastructure Post Request for Bids Limited 0.00 Signed 2022-12-19 2022-12-26 2022-12-24 2023-01-06 2023-02-04 2023-02-06 2023-03-06 2023-02-16 2023-04-10 2023-10-07 nvelope ation des conduites de distrib ution d'eau à Bambari. PASEEL/106/GO/RFQ/22 / Ma tériels branchements - Acqui Single Stage - One E sition de complément de mat IDA / D2690 Energy Infrastructure Post Request for Bids Limited 0.00 Signed 2022-12-19 2022-12-26 2022-12-24 2023-01-06 2023-02-04 2023-02-06 2023-03-06 2023-02-16 2023-04-10 2023-10-07 nvelope ériels de branchements pour Bangui, Bambari et Berberati . PASEEL/0108/GO/DIR/22 / Ac quisition et pose de matériels et équipements de plomberie Technical Support to Water IDA / D2690 Post Direct Selection Direct - National 0.00 Signed 2022-12-19 2022-12-14 2022-12-24 2022-12-14 2023-01-28 2023-07-27 pour le renforcement du syst and Energy Sectors ème d'alimentation en eau d es sanitaires des locaux de l' UGP. PASEEL/101/GO/DIR/22 / Mat ériels informatiques - Acquisi tion de matériels et équipem Technical Support to Water IDA / D2690 Post Direct Selection Direct - National 0.00 Completed 2022-12-26 2022-12-26 2022-12-31 2022-12-26 2023-02-04 2023-08-03 2023-02-01 ents informatiques pour les a and Energy Sectors ctivités de branchements soc iaux de la SODECA à Bambari et Berberati. Page 3 PASEEL/110/GO/CDS/23 / Ca rbure centres SODECA - Acqu Pending Impl IDA / D2690 Water Supply Infrastructure Post Direct Selection Direct - National 0.00 2023-02-23 2023-02-28 2023-04-04 2023-10-01 isition de carburant pour les ementation centres de Berberati et Bamb ari de la SODECA PASEEL/109/GO/RFQ/23 / Ma tériels extensions - Acquisitio Request for Quota Single Stage - One E IDA / D2690 Water Supply Infrastructure Post Limited 0.00 Signed 2023-03-29 2023-03-24 2023-05-24 2023-11-20 n de matériels d'extension et tions nvelope de raccordement des Bornes Fontaines PASEEL/111/GO/CDS/23 / Co nsommables SODECA provin IDA / D2690 Water Supply Infrastructure Post Direct Selection Direct - National 0.00 Canceled 2023-02-21 2023-02-26 2023-04-02 2023-09-29 ces - Acquisition des consom mables pour SODECA Berber ati et Bambari NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PASEEL/114/NC/DIR/23 / SO DECA Bambari-Achemineme Technical Support to Water Under Imple nt de matériels de réparation IDA / D2690 Post Direct Selection Direct - National 0.00 2023-04-24 2023-05-11 2023-04-29 2023-05-10 2023-06-03 2023-11-30 and Energy Sectors mentation des conduites de distribution d’eau au centre d’exploitatio n de SODECA de Bambari PASEEL/115/NC/DIR/23 / Mat ériels KBF-Acheminement de matériels d’extension et de r Technical Support to Water Pending Impl IDA / D2690 Post Direct Selection Direct - National 0.00 2023-05-09 2023-05-14 2023-06-18 2023-12-15 accordements des bornes fon and Energy Sectors ementation taines sur le réseau de distri bution de la SODECA à Bamb ari. CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CS-REF-6 / Réalisation des Et udes d'Impact Environnemen tal et Social (EIES), y compris Technical Support to Water Consultant Qualifi Open - Internationa les Plans de Gestion Environn / Post 0.00 Canceled 2017-11-30 2017-12-21 2018-02-03 2018-03-05 2018-04-09 2018-10-06 and Energy Sectors cation Selection l ementale et Sociale (PGES) e t les Plans d'Action de Réinst allation du Projet Eau et Ener gie à Bambari CS-REF-7 / Réalisation des Et udes d'Impact Environnemen tal et Social (EIES) y compris Technical Support to Water Consultant Qualifi Open - Internationa / Post 0.00 Canceled 2017-11-30 2017-12-21 2018-02-03 2018-03-05 2018-04-09 2018-10-06 les Plans de Gestion Environn and Energy Sectors cation Selection l ementale et Sociale (PGES) e t les PARS du Projet eau et é nergie dans la ville de Berber ati CS-REF-8 / Réalisation des EI Technical Support to Water Consultant Qualifi Open - Internationa Under Implement ES, PGES et PARS - Eau et En IDA / D2690 Prior 0.00 2017-11-30 2017-12-21 2018-01-29 2018-02-03 2018-03-27 2018-03-05 2018-04-09 2018-10-06 and Energy Sectors cation Selection l ation ergie à Bangui CS-REF-9 / Diagnostic opérat ionnel APS des installations d e génération et distribution d Consultant Qualifi Open - Internationa / Energy Infrastructure Post 0.00 Canceled 2018-01-05 2018-01-26 2018-03-11 2018-04-10 2018-05-15 2018-11-11 e l'ENERCA dans six villes se cation Selection l condaires ( Ndele, Bria, Kaga -Bandoro, Bangassou et Sibu t) CS-REF-10 / Diagnostic opér ationnel APS, APD et DAO ain Consultant Qualifi Open - Internationa / Energy Infrastructure Post 0.00 Signed 2018-01-10 2018-07-24 2018-01-31 2018-08-02 2018-03-16 2018-11-28 2018-04-15 2019-03-13 2018-05-20 2018-11-16 si que contrôle des travaux à cation Selection l Bambari et Berberati, volet é nergie CS-REF-12 / Audit financier e Technical Support to Water Least Cost Selecti Open - Internationa IDA / V1340 Prior 0.00 Canceled 2018-01-25 2018-02-15 2018-03-31 2018-04-28 2018-05-28 2018-07-02 2018-08-06 2019-02-02 xterne du PPA and Energy Sectors on l PASEEL/02/CS/QC/18 / Bang ui-Berberati étude hydro/ Co Consultant Qualifi Open - Internationa IDA / D2690 Water Supply Infrastructure Prior 548,339.01 Signed 2017-12-20 2018-07-18 2018-01-10 2018-02-23 2018-11-02 2018-03-25 2018-11-27 2018-04-29 2018-12-13 2018-10-26 nsultant pour étude détaillée cation Selection l et contrôle des travaux hydr auliques. CS-REF-2 / Recrutement d'u n consultant pour étude déta Consultant Qualifi Open - Internationa illée des travaux hydraulique / Water Supply Infrastructure Prior 0.00 Canceled 2017-12-20 2018-01-10 2018-02-14 2018-02-23 2018-03-25 2018-04-29 2018-10-26 cation Selection l s devant être réalisées à Ban gui et Berberati et contrôle d es travaux PASEEL/O24/CS/QC/18 / Etud es Bambari/Berberati-Recrut ement d'un Consultant/Firme chargé de la réalisation des é Consultant Qualifi Open - Internationa tudes APS, APD, élaboration IDA / D2690 Energy Infrastructure Prior 0.00 Canceled 2018-08-22 2018-09-12 2018-10-26 2018-11-25 2018-12-30 2019-06-28 cation Selection l du DAO, surveillance et contr ôle des travaux de réhabilitat ion et d'amélioration de l'ali mentation en électricité à Ba mbari et Berberati PASEEL/28/CS/QC/18 / EIES - Technical Support to Water Consultant Qualifi Open - Internationa Berberati: EIES-PGES-PAR du IDA / V1340 Post 95,061.24 Signed 2018-01-15 2018-10-12 2018-02-05 2018-03-21 2018-04-13 2018-04-20 2018-07-23 2018-05-25 2018-07-24 2018-11-21 and Energy Sectors cation Selection l PASEEL pour la ville de Berbe rati. PASEEL/29/SC/QC/18 / EIES Technical Support to Water Consultant Qualifi Open - Internationa BAMBARI-EIES-PGES-PAR du IDA / V1340 Post 112,148.82 Signed 2018-01-15 2018-10-12 2018-02-05 2018-03-21 2018-04-13 2018-04-20 2018-07-19 2018-05-25 2018-07-29 2018-11-21 and Energy Sectors cation Selection l PASEEL pour la ville de BAMB ARI. PASEEL/032/CS/SFQC/18 / Et udes dans 6 villes-Recruteme nt d'un consultant/Firme pou Technical Support to Water Quality And Cost- Open - Internationa r la réalisation des études te IDA / D2690 Prior 593,295.00 Signed 2019-02-20 2019-01-23 2019-03-13 2019-04-17 2019-04-26 2020-03-19 2019-05-24 2020-07-21 2019-06-23 2020-10-21 2019-07-28 2021-06-29 2019-09-01 2021-07-13 2020-08-31 and Energy Sectors Based Selection l chniques de faisabilité et Ava nt-Projet Sommaire, volet ea u et énergie dans six (6) ville s secondaires de la RCA. Page 4 PASEEL/035/CS/QC/19 / Elect Quality Based Sel Open - Internationa rification rurale-Politique d'él IDA / D2690 Energy Infrastructure Post 0.00 Canceled 2019-03-15 2019-04-05 2021-06-01 2019-05-19 2019-06-16 2019-07-16 2019-08-15 2019-09-19 2020-09-18 ection l ectrification rurale et plan d'i nvestissement PASEEL/036/CS/SFQC/19 / Pl an Directeur-Recrutement d' un Consultant/Firme pour l'él Quality And Cost- Open - Internationa aboration d'un Plan Directeur IDA / D2690 Energy Infrastructure Post 519,397.52 Signed 2019-03-11 2019-03-20 2019-04-01 2019-05-15 2019-10-01 2019-06-12 2020-05-15 2019-07-12 2020-05-20 2019-08-16 2020-05-20 2019-09-20 2020-11-14 2020-09-19 Based Selection l et d'un Programme d'Investis sement pour l'électrification nationale de la République C entrafricaine CS-REF-012 / Audit-externe- Recrutement d'un Auditeur e Technical Support to Water Quality And Cost- Open - Internationa IDA / D2690 Prior 0.00 Canceled 2019-03-18 2020-11-12 2019-04-08 2019-05-22 2019-06-19 2019-07-19 2019-08-23 2019-09-27 2020-09-26 xterne pour réaliser l'audit d and Energy Sectors Based Selection l es comptes financiers du Proj et CS-REF-0012 / Audit externe -Recrutement d'un Auditeur Technical Support to Water Quality Based Sel Open - Internationa Under Implement IDA / D2690 Prior 0.00 2019-04-03 2019-03-29 2019-04-24 2019-06-07 2019-04-15 2019-07-05 2019-05-20 2019-08-04 2022-09-11 2019-09-03 2019-10-08 2020-10-07 externe pour réaliser l'audit and Energy Sectors ection l ation des comptes financiers du pr ojet PASEEL/047/CS/QC/19 / Mise Technical Support to Water Consultant Qualifi à jour-Mise à jour de la straté IDA / D2690 Post Open - National 138,401.96 Signed 2019-07-31 2019-09-13 2019-08-21 2019-09-17 2019-10-04 2021-07-13 2019-11-03 2021-09-15 2019-12-08 2021-09-29 2020-06-05 and Energy Sectors cation Selection gie du secteur énergétique PASEEL/048/CS/QCBS/19 / A udit externe 19 - Recrutemen t d'un Consultant/Firme pour Technical Support to Water Quality And Cost- Open - Internationa Under Implement IDA / D2690 Prior 0.00 2019-11-15 2019-12-16 2019-12-06 2020-03-19 2020-01-19 2020-02-16 2020-03-17 2020-04-21 2020-05-26 2021-05-26 la réalisation de l'audit financ and Energy Sectors Based Selection l ation ier et comptable du PASEEL e t PURACEL pour l'exercice 20 19, 2020 et 2021 PASEEL/069/SC/QC/21 / Recr utement d'un Consultant/Fir Technical Support to Water Consultant Qualifi me pour appui aux activités IDA / D2690 Post Limited 22,029.03 Signed 2021-03-25 2021-05-14 2021-04-08 2021-06-01 2021-05-08 2021-08-17 2021-06-12 2021-08-27 2021-12-09 and Energy Sectors cation Selection de communication relatives a ux branchements sociaux. PASEEL/062/CS/QCBS/20 / A udit ENERCA SODECA-Audit fi nancier et comptable de l'EN Technical Support to Water Quality And Cost- Open - Internationa IDA / D2690 Prior 0.00 Canceled 2020-03-09 2020-11-19 2020-03-30 2020-11-23 2020-05-13 2020-06-10 2020-07-10 2020-08-14 2020-09-18 2021-09-18 ERCA et de la SODECA et les and Energy Sectors Based Selection l évaluations indépendantes d es exercices 2016, 2017 et 2 018. PASEEL/00062/CS/LCS/20 / A udit ENERCA SODECA-Audit fi nancier et comptable de l'EN Least Cost Selecti Open - Internationa IDA / D2690 Energy Infrastructure Post 97,306.09 Signed 2020-11-19 2020-11-19 2020-12-10 2021-01-23 2021-02-19 2021-02-20 2021-04-09 2021-03-22 2021-05-03 2021-04-26 2021-05-05 2021-05-31 2021-05-07 2021-11-27 ERCA et de la SODECA et les on l évaluations indépendantes d es exercices 2016, 2017 et 2 018. PASEEL/046/CS/SFQC/19 / C ode d'électrification-Révision Technical Support to Water Quality And Cost- IDA / D2690 Post Open - National 0.00 Canceled 2019-08-02 2019-09-07 2019-08-23 2019-10-06 2019-11-03 2019-12-03 2020-01-07 2020-02-11 2021-02-10 du Code d'électrification et r and Energy Sectors Based Selection édaction des décrets d'applic ation. PASEEL/031/CS/SFQC/18 / As sistance Technique-Recrute Technical Support to Water Quality And Cost- Open - Internationa IDA / D2690 Post 0.00 Canceled 2019-02-15 2019-03-08 2019-04-21 2019-05-19 2019-06-18 2019-07-23 2019-08-27 2020-08-26 ment d'un consultant/Firme p and Energy Sectors Based Selection l our l'Assistance Technique à la SODECA INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Actual Amount Invitation to Identifie Draft Negotiated Cont Component Review Type Method Contract Type Process Status Teams of Reference Signed Contract Contract Completion Description o. h (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CS-REF-1 / Recrutement d'u n consultant chargé de l'élab Technical Support to Water IDA / D2690 Prior Direct Selection Direct 0.00 Under Review 2017-09-30 2018-01-23 2017-10-19 2017-10-04 2017-10-25 2017-11-24 oration du PPSD des Projets P and Energy Sectors ASEEL et PURACEL CS-REF-3 / Recrutement d'u n consultant pour études APS , APD et DAO des travaux hy / Water Supply Infrastructure Prior Direct Selection Direct 0.00 Canceled 2017-12-10 2017-12-20 2018-04-20 2018-02-23 2018-08-22 drauliques à réaliser et contr ôle des travaux dans la ville de Bambari CS-REF-15 / Recrutement d' Technical Support to Water Individual Consult Under Implement IDA / V1340 Post Open 0.00 2018-01-31 2020-09-10 2018-03-21 2018-04-11 2018-05-16 2018-11-12 un Expert en Suivi-évaluation and Energy Sectors ant Selection ation SGF-PASEEL-CS-INDV-16 / S Technical Support to Water Individual Consult GF - Recrutement d'un compt IDA / D2690 Prior Limited 0.00 Canceled 2017-11-10 2017-11-15 2017-12-06 2018-01-10 2018-07-09 and Energy Sectors ant Selection able du Projet PASEEL PASEEL-CS-INDV-15 / EPM-P Technical Support to Water Individual Consult ASEEL-Recrutement d'un Exp IDA / D2690 Prior Limited 3,160.64 Signed 2017-11-12 2017-11-17 2017-12-08 2018-05-05 2018-01-12 2018-05-14 2018-07-11 and Energy Sectors ant Selection ert en Passation des Marchés CS-REF-13 / Recrutement d' Technical Support to Water Individual Consult un comptable, responsable d IDA / V1340 Prior Limited 1,535.77 Signed 2018-01-25 2018-01-30 2018-02-20 2018-03-21 2018-03-27 2018-04-06 2018-09-23 and Energy Sectors ant Selection e gestion fiduciaire du projet PASEEL-18-IND-18 / Expert E nvironnement-Recrutement d Technical Support to Water Individual Consult IDA / D2690 Post Limited 1,714.06 Signed 2018-05-15 2017-10-04 2018-05-20 2020-10-27 2018-06-10 2018-04-13 2018-07-15 2019-04-18 2019-01-11 'un consultant, expert en sau and Energy Sectors ant Selection vegarde environnementale d u Projet PASEEL. PASEEL-19-IND-18 / Expert s ociale - Recrutement d'un co Technical Support to Water Individual Consult IDA / D2690 Post Limited 0.00 Canceled 2018-05-10 2018-05-15 2018-06-05 2018-07-10 2019-01-06 nsultant individuel, expert en and Energy Sectors ant Selection sauvegarde sociale du Projet PASEEL/O25/CS/IND/18 / Rés ilience Boali-Recrutement d'u n consultant chargé de la réd Individual Consult action des spécifications tech IDA / D2690 Energy Infrastructure Post Open 141,700.48 Signed 2018-09-05 2020-02-15 2018-10-24 2019-03-05 2018-11-14 2020-03-07 2018-12-19 2019-03-22 2019-06-17 ant Selection niques pour la fourniture et i nstallation des équipements de la sous-composante "Résil ience de Boali". Page 5 PASEEL/O26/CS/IND/18 / Co mpteurs prépaiement-Recrut ement d'un consultant charg é de la rédaction des spécific Individual Consult IDA / D2690 Energy Infrastructure Post Open 32,300.00 Signed 2018-09-13 2018-08-28 2018-11-01 2019-03-12 2018-11-22 2019-03-20 2018-12-27 2019-03-22 2019-06-25 ations techniques des compt ant Selection eurs à prépaiement et comm uniquant pour l'amélioration des performances commerci ales de l'ENERCA à Bangui. PASEEL/030/CS/IND/18 / Aud it énergétique-Recrutement d'un consultant individuel po Individual Consult IDA / D2690 Water Supply Infrastructure Post Open 54,236.70 Signed 2018-11-15 2018-08-28 2019-01-03 2019-09-02 2019-01-24 2019-09-02 2019-02-28 2019-10-23 2019-08-27 ur la réalisation de l'audit én ant Selection ergétique des infrastructures hydrauliques de la SODECA. PASEEL-0019-IND-18 / Exper Technical Support to Water Individual Consult t Social-Recrutement d'un Ex IDA / D2690 Post Open 16,477.67 Signed 2018-06-03 2020-02-28 2018-07-22 2018-08-06 2018-08-12 2018-09-25 2018-09-16 2018-12-04 2019-03-15 and Energy Sectors ant Selection pert en sauvegardes sociales PASEEL/034/CS/CDS/18 / Par amétrage Tompro-Recrutem Technical Support to Water Individual Consult IDA / D2690 Post Direct 23,580.49 Completed 2018-11-19 2018-12-19 2018-11-29 2019-04-11 2018-12-20 2019-04-16 2019-01-24 2019-04-17 2019-07-23 2019-05-27 ent d'un consultant individue and Energy Sectors ant Selection l pour le paramétrage des pr ojets sur Tompro. CS-REF-11 / Diagnostic opér ationnel/Etat des lieux des in Individual Consult IDA / D2690 Energy Infrastructure Post Open 0.00 Canceled 2019-02-28 2019-04-18 2019-05-09 2019-06-13 2019-12-10 stallations de distribution de ant Selection l'ENERCA à Bangui CS-REF-5 / Etude de réalisati Individual Consult on d'un plan de sécurité du b IDA / D2690 Energy Infrastructure Post Limited 80,150.00 Signed 2019-03-15 2019-02-08 2019-03-20 2019-03-15 2019-04-10 2019-05-02 2020-07-03 2019-05-11 2020-12-30 ant Selection arrage de Boali PASEEL/037/SC/SED/19 / Co ntrat Comptable-Renouvelle Technical Support to Water IDA / D2690 Prior Direct Selection Direct 1,712.76 Signed 2019-04-16 2019-05-08 2019-04-26 2019-06-30 2019-05-10 2019-12-27 ment de contrat du Comptabl and Energy Sectors e du PASEEL et du PURACEL PASEEL/043/CS/ED/19 / Reno uvellement du contrat de l'Ex Technical Support to Water IDA / D2690 Post Direct Selection Direct 38.22 Signed 2019-05-15 2019-05-29 2019-05-25 2019-05-29 2019-07-29 2019-06-09 2020-01-25 pert en Passation des Marché and Energy Sectors s des Projets PASEEL et PURA CEL PASEEL/044/CS/INDV/19 / SI G-Recrutement d'un consulta nt individuel chargé de réalis Technical Support to Water Individual Consult IDA / D2690 Post Open 45,387.60 Signed 2019-06-13 2021-08-27 2019-08-01 2021-11-22 2019-08-22 2021-12-13 2019-09-26 2021-12-28 2020-03-24 er les études pour la mise en and Energy Sectors ant Selection place d'u système d'informati on géographique de la SODE CA PASEEL/060/CS/INDV/19 / Ex pert Social-Renouvellement d Technical Support to Water IDA / D2690 Post Direct Selection Direct 19,825.08 Signed 2019-12-30 2020-01-07 2020-01-09 2020-01-17 2020-03-14 2020-01-17 2020-09-10 u contrat de l'Expert en Sauv and Energy Sectors egardes Sociales PASEEL/061/CS/INDV/19 / Ex pert environnement-Renouve Technical Support to Water IDA / D2690 Post Direct Selection Direct 28,071.11 Signed 2020-01-08 2020-01-16 2020-01-18 2020-02-28 2020-03-23 2020-05-06 2020-09-19 llement du contrat de l'Exper and Energy Sectors t en Sauvegardes Environne mentales PASEEL/063/CS/INDV/20 / Co Technical Support to Water mptable-Renouvellement du IDA / D2690 Post Direct Selection Direct 1,871.30 Signed 2020-03-10 2020-04-17 2020-03-20 2020-04-22 2020-05-24 2020-04-30 2020-11-20 and Energy Sectors contrat du Comptable PASEE L/PURACEL PASSEL/064/CS/INDV/20 / SP M Renouvellement-Renouvell Technical Support to Water IDA / D2690 Post Direct Selection Direct 0.00 Signed 2020-06-15 2020-06-29 2020-06-25 2020-05-29 2020-08-29 2021-02-25 ement du contrat du Spéciali and Energy Sectors ste en Passation des Marchés PASEEL/066/CS/IND/20 / Soci Technical Support to Water Individual Consult al-Renouvellement du Contra IDA / D2690 Post Direct 29,047.36 Signed 2020-09-30 2020-09-16 2020-10-10 2020-09-04 2020-10-31 2020-12-04 2020-12-05 2020-12-10 2021-06-03 and Energy Sectors ant Selection t de l'Expert en Sauvegardes Sociales PASEEL/067/CS/INDV/20 / Re lecture-Recrutement d'un Co Technical Support to Water Individual Consult nsultant individuel chargé de IDA / D2690 Post Direct 0.00 Canceled 2020-10-21 2020-10-22 2020-10-31 2020-11-21 2020-12-26 2021-06-24 and Energy Sectors ant Selection la relecture et finalisation de s rapports EIES des villes de Bambari et Berberati. PASEEL/068/CS/INDV/21 / Av Technical Support to Water Individual Consult enant 3-Renouvellement du IDA / D2690 Post Direct 30,595.49 Signed 2021-02-16 2021-04-01 2021-02-26 2021-05-27 2021-03-19 2021-06-09 2021-04-23 2021-06-19 2021-10-20 and Energy Sectors ant Selection Contrat du Comptable du PA SEEL/PURACEL PASEEL/069/CS/INDV/21 / Av enant 2- renouvellement du Technical Support to Water Individual Consult IDA / D2690 Post Direct 28,410.10 Signed 2021-02-18 2021-03-01 2021-02-28 2021-05-27 2021-03-21 2021-06-10 2021-04-25 2021-06-19 2021-10-22 Contrat de l'Expert en Sauve and Energy Sectors ant Selection gardes Environnementales. PASEEL/073/CS/DIR/21 / Ave nant3 SPM-Renouvellement d Technical Support to Water IDA / D2690 Post Direct Selection Direct 43,158.96 Signed 2021-05-31 2021-06-14 2021-06-10 2021-06-07 2021-08-14 2021-06-10 2022-02-10 u contrat du Spécialiste en P and Energy Sectors assation des Marchés second du PURACEL/PASEEL PASEEL/076/CS/INDV/21 / Ev aluation mi parcours-Recrute ment d'un Consultant Individ Technical Support to Water Individual Consult IDA / D2690 Post Limited 42,814.85 Signed 2021-06-21 2021-05-28 2021-06-26 2021-08-06 2021-07-17 2021-09-06 2021-08-21 2021-09-08 2022-02-17 uel chargé de l'évaluation à and Energy Sectors ant Selection mi parcours du Projet d'Améli oration des Services d'Eau et d'Electricité (PASEEL). PASEEL/081/CS/INDV/21 / Co ntrat SGF-Renouvellement du Technical Support to Water contrat n°0266/20/MTPER/DI IDA / D2690 Post Direct Selection Direct 138,375.90 Signed 2021-09-20 2021-08-19 2021-09-30 2021-09-07 2021-12-04 2021-10-30 2022-06-02 and Energy Sectors RCAB/CUGP/PASEEL-PURACE L, Prestations de Spécialiste en Gestion Financière PASEEL/083/CS/CDS/21 / Exp ert Energie-Renouvellement du contrat n°0217/18/MTPER/ Technical Support to Water IDA / D2690 Post Direct Selection Direct 197,521.30 Signed 2021-11-22 2020-11-30 2021-12-02 2021-12-07 2022-02-05 2022-01-20 2022-08-04 DIRCAB/CUG/PASEEL-PURACE and Energy Sectors L, prestations d'Expert en En ergie (NERGUIDIMA Mathurin ) Page 6 PASEEL/084/CS/CDS/21 / Exp ert Social-Renouvellement du contrat n°0192/18/MTPER/DI Technical Support to Water IDA / D2690 Post Direct Selection Direct 28,318.56 Signed 2021-11-19 2020-09-23 2021-11-29 2021-11-24 2022-02-02 2022-02-24 2022-08-01 RCAB/CUG -/PASEEL–PURACE and Energy Sectors L, prestation d'Expert en sau vegardes sociales du PASEEL /PURACEL PASEEL/089/CS/INDV/21 / Re vue code-Révision du code d' Technical Support to Water Individual Consult IDA / V1340 Post Open 0.00 Signed 2021-12-27 2021-12-21 2022-02-14 2022-03-07 2022-03-07 2022-12-14 2022-04-11 2022-10-08 électricité et rédaction des d and Energy Sectors ant Selection écrets d'application. PASEEL/094/SC/INDV/22 / Co ntrôle Bambari-Recrutement par entente pour la surveillan Technical Support to Water IDA / D2690 Post Direct Selection Direct - National 0.00 Signed 2022-09-27 2022-10-14 2022-10-07 2022-10-18 2022-12-11 2023-06-09 ce et contrôle des travaux de and Energy Sectors réhabilitation des infrastruct ures d’alimentation en eau p otable de la ville de Bambari. PASEEL/95/SC/INDV/22 / Con trôle Berberati-Recrutement par entente directe d'un cons Technical Support to Water ultant individuel pour la supe IDA / D2690 Post Direct Selection Direct - National 0.00 Signed 2022-09-30 2022-10-14 2022-10-10 2022-10-18 2022-12-14 2023-06-12 and Energy Sectors rvision et contrôle des travau x de Réhabilitation des infras tructures d’alimentation en e au potable de la ville de Berb erati. CS-REF-03 / MOC AEP Bamb ari-Recrutement d'un consult ant pour études APS, APD et Direct - Internation IDA / D2690 Water Supply Infrastructure Post Direct Selection 0.00 Signed 2017-12-10 2018-04-24 2017-12-20 2018-04-20 2018-02-23 2018-08-22 DAO des travaux hydraulique al s à réaliser et contrôle des tr avaux dans la ville de Bamba ri PASEEL/CS/CDS/22 / Concep tion 2 forages-Recrutement d 'un consultant individuel char Technical Support to Water Direct - Internation IDA / D2690 Post Direct Selection 0.00 Signed 2022-11-28 2022-11-24 2022-12-08 2022-11-29 2023-02-11 2023-08-10 gé de réaliser les études et c and Energy Sectors al onception de deux forages p our le compte de la SODECA à Beberati. PASEEL/112/CS/CDS/23 / Au dit technique-Recrutement d’ un Consultant Individuel char gé de l’Audit de l’exécution d Technical Support to Water Direct - Internation Under Implement u marché des Travaux de réh IDA / D2690 Post Direct Selection 0.00 2023-04-17 2023-04-10 2023-04-27 2023-07-01 2023-12-28 and Energy Sectors al ation abilitation, de construction et d’équipement des infrastruct ures d’eau potable dans la vil le de BAMBARI confiés à l’Ent reprise SK BATIMENT. PASEEL/0113/CS/CDS/23 / A udit SK-Recrutement d’un Co nsultant Individuel chargé de l’Audit de l’exécution des ma Technical Support to Water Direct - Internation Under Implement rchés de Travaux de réhabilit IDA / D2690 Post Direct Selection 0.00 2023-04-17 2023-04-10 2023-04-27 2023-07-01 2023-12-28 and Energy Sectors al ation ation, de construction et d’éq uipement des infrastructures d’eau potable dans la ville de BERBERATI confiés à l’Entrep rise SK BATIMENT. Page 7 Plan de Passation des marchés du Projet d’Appui aux Communautés dépendantes de la Forêt (DGM-DRC) P149049 (TF0A0924). I. Général 1. Date d’élaboration : 8 février 2016 2. Date d’approbation par la Banque du Plan de Passation des Marches : 8 février 2016 - Version négociée 3. Date de l’Avis Général de Passation des marchés: 4. Période couverte par ce Plan : Janvier à Décembre 2016 5. Risque passation des marchés : Substantiel II. Biens et Travaux et services autres que ceux de consultants. 1. Seuil de revue préalable: au-dessus duquel le processus de passation des marchés fait l’objet d’une revue préalable de la Banque mondiale tel que décrit dans l’annexe 1 des Directives pour l’acquisition de biens et de services autres que ceux de consultants. Nature des Méthode de passation Valeur seuil Contrats soumis à dépenses de marchés du marché examen préalable de $EU l’IDA 1. Travaux Entente directe Tout montant Tout contrat supérieur ou égal à US$ 100 000 Demande de cotation – < 200.000 Aucun comparaison d’au moins 3 offres 2. AON ˂1 000.000 Tout contrat supérieur ou Fournitures égal à US$500 000 et services Consultation de < 100.000 Aucun assimilés Fournisseurs Entente directe Tout montant Tout contrat supérieur ou égal à US$ 100 000 N.B. : Toutes les justifications du recours à l’entente directe incluant le montant estimé du contrat sont à soumettre à la revue préalable de la Banque. 2. Liste globale des contrats d’équipement devant être financés sur le don de préparation et le projet. Date Réf. Cout Méthode Préfére prévue Commentai Description Revue No. estimés$ de nce pour res 1 Passatio nationa (Prior / l’ouvertur n des le Post) e des marchés (oui/no offres n) Acquisition de cinq 1 motos de brousse 12.000 CF Non Post 15/06/16 et 32 vélos Service informatique de configuration de 2 15/05/16 logiciels 5,000 CF Non Post spécialisés de comptabilité Assurance du 3 matériel roulant 15/06/16 2,000 ED Non Post (pour 3 ans) Contrat ouvert – tarif Impression et préférentiels duplication des négociés documents du 4 20,000 1/12/16 pour les projet, du Code AC Non Post prestations Forestier et des attendues décrets durant l’année CF= Consultations de Fournisseurs AC = Accord Cadre III. Sélection de Consultants 1. Seuil de revue préalable: au-dessus duquel le processus de sélection fait l’objet d’une revue préalable de la Banque mondiale tel que décrit dans l’annexe 1 des Directives pour la sélection et l’emploi de consultants. Nature de Méthode de Valeur seuil du Contrats soumis à examen dépenses passation de contrat préalable marchés $EU Consultan ≥ 200.000 Tout contrat supérieur ou ts égal à US$ 500 000 Firmes < 200.000 Aucun QC Tout montant Tout contrat supérieur ou égal à US$ 100 000 Entente directe 2 Consultan Tout montant Tout contrat supérieur ou ts Consultant égal à Individuel individuel 200 000 US$ s Entente directe Tout montant Tout contrat supérieur ou égal à US$ 100 000 Tous les TDRs, quelle que soit la valeur du contrat, sont soumis à examen préalable. Toutes les justifications du recours à l’entente directe incluant le montant estimé du contrat sont soumis à l’examen préalable de la Banque. QC = Qualifications du Consultant 2. Listes restreintes comprenant uniquement des candidats nationaux: Les listes restreintes pour les contrats de consultants estimées à un coût inférieur à $100,000 pour les services ordinaires et $200,000 pour les contrats de supervision peuvent être entièrement composées de consultants nationaux, suivant les dispositions du Paragraphe 2.7 des Directives pour l’emploi des Consultants. 1 2 3 4 5 6 7 8 Examen Date Ref. Description Montant Préalable prévue Date Commentaires No. Méthod estimé ou à pour prévue e de ($.US) postériori l’ouvertu pour sélectio par la re des attributio n Banque offres n Opérateur spécialisé Pour les 3 pour le suivi des premières plaintes, 1 ED 200,000 Priori 15/07/16 15/08/16 années – consultation Composante 3b - permanente des REPALEF communautés Réalisation pour 2 chaque APAC de la 1 seule sélection cartographie avec 5 lots de QC 225,000 Post 15/08/16 15/09/16 participative, du 45,000 USD – plan de gestion et du Composante 2b PARAR Opérateur spécialisé Pour 3 ans – 3 QC 45,000 Post 1/03/16 1/04/16 sur la question des Composante 1a – 3 droits fonciers des PA Etudes pour dégager des options susceptibles de 4 renseigner la CI 5,000 Post 15/08/16 15/09/16 Composante 1a réforme foncière sur l'accès des PA à la terre Opérateur spécialisé pour créer des Pour 3 ans - 5 lobbies pour QC 45,000 Post 1/03/16 1/04/16 Composante 1a l'adoption de la loi sur les PA Opérateur spécialisé pour l'appui à la gestion Pour 3 ans - 6 QC 45,000 Post 1/03/16 1/04/16 communautaire de Composante 1a l'affectation des terres (APAC) Opérateurs pour Les lots seront l'alphabétisation des définis après le PACL impliqués dans diagnostic la gestion du projet institutionnel et les former à la initial pour 7 QC 40,000 Post 15/08/16 15/09/16 gestion et à la petite identifier les comptabilité (tenue opérateurs du livre de caisse, locaux et les gestion des entrées besoins - et des sorties, etc) Composante 1b Consultant appui Conservation Communautaire 8 CI 5,000 Post 15/2/16 10/03/16 pour le bilan des expériences existantes Contrat 3 ans 9 Expert Sauvegardes CI 70,000 Post 15/07/16 15/08/16 renouvelable - Composante 3a Appui pour la finalisation - Rédaction du Manuel 10 CI 5,000 Post 1/03/16 1/04/16 pour la mise en de mise en œuvre vigueur - Composante 3a Pour 3 ans - 11 Auditeur externe SMC 45,000 Post 15/07/16 15/08/16 Composante 3a En vue de la Expert technique revue à mi- 12 CI 30,000 Post 15/11/16 15/12/16 indépendant parcours - Composante 3b 4 5 PROCUREMENT Congo, Democratic Republic of : Forest Dependent Communities Support Project PLAN General Information Country: Congo, Democratic Republic of 2018-09-19 Bank’s Approval Date of the Original Procurement Plan: 2023-06-07 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P149049 GPN Date: Project Name: Forest Dependent Communities Support Project Loan / Credit No: TF / A0924, TF / A5550 CARITAS CONGO Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ZR-CARITAS-125539-GO-RF Component 3 - Increase the Q / 40 téléphones (+4) Andro capacity to implement the IP Request for Quota Single Stage - One E TF / A0924 Post Limited 15,600.00 6,783.00 Signed 2019-08-05 2019-10-29 2019-09-30 2020-03-14 2020-03-28 id pour le suivi des indicateur LC development activities a tions nvelope s avec KOBO. nd consolidate feedback NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ZR-CARITAS-83598-NC-RFQ / Contrat - Cadre avec Imprim Component 1 - Reinforce the eurs (plusieurs lots) pour mo participation of the IPLC in fo Request for Quota Single Stage - One E Pending Impl TF / A0924 Post Limited 60,000.00 0.00 2018-11-05 2018-12-31 2019-06-29 dules d'alphabétisation , cod rest and land management tions nvelope ementation e forestier, textes sur le fonci processes related to REDD+ er (40000 documents de taill es diverses) ZR-CARITAS-122739-CS-CDS Component 1 - Reinforce the / Transport et distribution de participation of the IPLC in fo Request for Quota Single Stage - One E Pending Impl s modules dans les territoires TF / A0924 Post Limited 8,000.00 0.00 2019-07-31 2019-09-25 2020-03-23 rest and land management tions nvelope ementation avec AEN ( consultations de processes related to REDD+ trois transporteurs pour dem ande des prixà ZR-CARITAS-83603-NC-RFQ / Component 1 - Reinforce the Transport des documents po participation of the IPLC in fo Request for Quota Single Stage - One E TF / A0924 Post Limited 3,000.00 0.00 Canceled 2018-11-05 2018-12-31 2019-06-29 ur Kisangani, Mbujimayi, Go rest and land management tions nvelope ma, Kanange, Inongo et Mba processes related to REDD+ ndaka ZR-CARITAS-175242-NC-RFQ / Sélection d'un prestataire p Component 2 - Support com Request for Quota Single Stage - One E our la reproduction des docu TF / A0924 munity-based sustainable fo Post Limited 12,750.00 0.00 Canceled 2020-07-25 2020-09-19 2021-03-18 tions nvelope ments sur le foncier, foresteri rest and land management e communautaire et amenag ement du territoire CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 3 - Increase the ZR-CARITAS-66039-CS-CDS / capacity to implement the IP Consultant Qualifi Recrutement point focal INO TF / A0924 Post Open - National 18,000.00 0.00 Signed 2018-09-13 2018-09-13 2018-09-18 2023-06-01 2018-10-07 2023-06-05 2018-10-17 2023-06-09 2018-10-27 2019-04-25 LC development activities a cation Selection NGO nd consolidate feedback ZR-CARITAS-241037-CS-QCB Component 3 - Increase the S / Recrutement d'un Cabinet capacity to implement the IP Consultant Qualifi TF / A0924 Post Open - National 6,000.00 8,260.00 Signed 2021-07-14 2021-07-15 2021-07-17 2021-09-10 2021-07-24 2021-07-27 2021-07-29 2021-07-30 2021-08-08 2021-08-11 2021-09-07 d'Audit pour Auditer les Etats LC development activities a cation Selection financiers du Projet DGM exe nd consolidate feedback rcice 2020 ZR-CARITAS-49120-CS-CDS / Component 3 - Increase the CAUDITEC - Recrutement d'u capacity to implement the IP Quality And Cost- n Auditeur externe pour la c TF / A0924 Post Open - National 40,000.00 0.00 Canceled 2018-10-31 2018-10-31 2018-11-21 2019-01-04 2019-02-01 2019-03-03 2019-04-07 2019-05-12 2020-05-11 LC development activities a Based Selection ertification des comptes de l nd consolidate feedback a DGM pour les comptables 2 016, 2017 et 2018 ZR-CARITAS-280030-CS-QCB Component 3 - Increase the S / Recrutement d'un auditeu capacity to implement the IP Quality And Cost- r externe pour la reddition de TF / A0924 Post Open - National 40,000.00 0.00 Signed 2022-03-07 2023-06-12 2022-03-28 2023-06-22 2022-05-11 2023-06-20 2022-06-08 2023-06-20 2022-07-08 2023-06-20 2022-08-12 2023-06-20 2022-09-16 2023-09-16 LC development activities a Based Selection s comptes du projet DGM exe nd consolidate feedback rcices 2016, 2017 et 2018 INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 3 - Increase the ZR-CARITAS-66157-CS-CDS / capacity to implement the IP Individual Consult TF / A0924 Post Open 22,500.00 0.00 Canceled 2018-10-31 2019-10-01 2018-12-19 2019-01-09 2019-02-13 2019-08-12 PF Sauvegardes KISANGANI LC development activities a ant Selection nd consolidate feedback Component 3 - Increase the ZR-CARITAS-66158-CS-CDS / capacity to implement the IP Individual Consult TF / A0924 Post Open 9,000.00 0.00 Signed 2018-10-31 2019-10-01 2018-12-19 2023-06-05 2019-01-09 2023-06-07 2019-02-13 2019-08-12 PF Sauvegardes GOMA LC development activities a ant Selection nd consolidate feedback Component 3 - Increase the ZR-CARITAS-66159CS-CDS / capacity to implement the IP Individual Consult Under Implement TF / A0924 Post Open 13,500.00 0.00 2018-10-31 2018-10-31 2018-12-19 2019-01-09 2019-02-13 2019-08-12 PF Sauvegardes KANANGA LC development activities a ant Selection ation nd consolidate feedback Page 1 Component 3 - Increase the ZR-CARITAS-66159-CS-CDS / capacity to implement the IP Individual Consult TF / A0924 Post Open 22,500.00 0.00 Signed 2018-10-31 2019-10-01 2018-12-19 2023-06-04 2019-01-09 2023-06-06 2019-02-13 2019-08-12 PF Sauvegardes MBUJIMAYI LC development activities a ant Selection nd consolidate feedback Component 3 - Increase the ZR-CARITAS-83607-CS-INDV capacity to implement the IP Individual Consult Under Implement TF / A0924 Post Open 72,000.00 0.00 2018-10-25 2018-10-25 2018-12-13 2019-01-03 2019-02-07 2019-08-06 / Expert Sauvegardes LC development activities a ant Selection ation nd consolidate feedback Component 3 - Increase the ZR-CARITAS-66156-CS-CDS / capacity to implement the IP Individual Consult TF / A0924 Post Open 18,000.00 0.00 Canceled 2018-10-31 2018-12-19 2019-01-09 2019-02-13 2019-08-12 PF sauvegardes INONGO LC development activities a ant Selection nd consolidate feedback ZR-CARITAS-122805-CS-CDS Component 1 - Reinforce the / Salaire expert sauvegarde e participation of the IPLC in fo Individual Consult nv. et sociale et mission suivi TF / A0924 Post Limited 126,000.00 0.00 Canceled 2019-08-08 2019-08-13 2019-09-03 2019-10-08 2020-04-05 rest and land management ant Selection sauvegarde (respect des cad processes related to REDD+ res de gestion environnemen tale et sociale ZR-CARITAS-62547-CS-CDS / Component 1 - Reinforce the Contractualisation avec Carit participation of the IPLC in fo as BUKAVU sur l'Alphabétisat TF / A0924 Post Direct Selection Direct 6,000.00 6,000.00 Signed 2020-06-22 2020-07-24 2020-07-02 2020-08-03 2020-09-05 2020-08-14 2021-03-04 rest and land management ion Dio BUKAVU, Territoire de processes related to REDD+ KALEHE . Component 1 - Reinforce the ZR-CARITAS-49616-CS-CDS / participation of the IPLC in fo Alphabétisation Dio KANANG TF / A0924 Post Direct Selection Direct 6,000.00 6,000.00 Signed 2019-07-16 2020-07-24 2019-07-26 2020-08-03 2019-09-29 2020-08-25 2020-03-27 rest and land management A, Territoire de DIMBELENGE processes related to REDD+ ZR-CARITAS-62538-CS-CDS / Component 1 - Reinforce the Contractualisation avec Carit participation of the IPLC in fo as diocese de MWEKA pour l' TF / A0924 Post Direct Selection Direct 6,000.00 6,000.00 Signed 2020-06-22 2020-07-24 2020-07-02 2020-08-03 2020-09-05 2020-08-21 2021-03-04 rest and land management éducation de base et l'alphab processes related to REDD+ étisation territoire MWEKA ZR-CARITAS-62540-CS-CDS / Component 1 - Reinforce the Contractualisation avec Carit participation of the IPLC in fo as diocese d'INONGO, territoi TF / A0924 Post Direct Selection Direct 18,000.00 18,000.00 Signed 2020-06-25 2020-07-24 2020-07-05 2020-08-06 2020-09-08 2020-08-11 2021-03-07 rest and land management re de KIRI, OSWE et INONGO processes related to REDD+ pour l'éducation de base et l' alphabétisation . ZR-CARITAS-62543-CS-CDS / Component 1 - Reinforce the Contractualisation avec Carit participation of the IPLC in fo as diocese d'ISANGI, territoir TF / A0924 Post Direct Selection Direct 12,000.00 12,000.00 Signed 2020-07-20 2020-07-24 2020-07-30 2020-07-27 2020-10-03 2020-08-11 2021-04-01 rest and land management e de YAHUMA et OPALA pour processes related to REDD+ l'éducation de base et l'alpha bétisation ZR-CARITAS-62546-CS-CDS / Component 1 - Reinforce the Contractualisation avec Carit participation of the IPLC in fo TF / A0924 Post Direct Selection Direct 6,000.00 6,000.00 Signed 2020-07-31 2020-07-24 2020-08-10 2020-08-06 2020-10-14 2020-08-12 2021-04-12 as diocese de MBANDAKA BI rest and land management KORO, territoire de BIKORO processes related to REDD+ Component 1 - Reinforce the ZR-CARITAS-83577-CS-CDS / participation of the IPLC in fo Alphabétisation Dio WAMBA - TF / A0924 Post Direct Selection Direct 12,000.00 12,000.00 Signed 2020-06-26 2020-07-24 2020-07-06 2020-08-03 2020-09-09 2020-08-11 2021-03-08 rest and land management MAMBASA ET BAFWASENDE processes related to REDD+ ZR-CARITAS-175241-CS-CDS Component 3 - Increase the / Renouvelement de contrat capacity to implement the IP avec REPALEF avec les opéra TF / A0924 Post Direct Selection Direct 120,950.00 0.00 Signed 2020-07-27 2016-07-01 2020-08-06 2016-07-11 2020-10-10 2021-04-08 LC development activities a teurs pour le suivi de satifact nd consolidate feedback ion et gestion des plainte 20 20 2022 ZR-CARITAS-62460-CS-CDS / Component 1 - Reinforce the Contractualisation avec Carit participation of the IPLC in fo as diocese de KABINDA pour TF / A0924 Post Direct Selection Direct 18,000.00 18,000.00 Signed 2020-06-17 2021-03-17 2020-06-27 2020-07-27 2020-09-15 2020-08-21 2021-03-14 rest and land management l'alphabétisation , Territoire K processes related to REDD+ ABINDA, LUBAO et LUSAMBO ZR-CARITAS-185697-CS-CDS / Contractualisation avec l'O NG FONDATION NSELALA pou Component 2 - Support com r valorisation des initiatives l TF / A0924 munity-based sustainable fo Post Direct Selection Direct 61,000.00 61,000.00 Signed 2020-08-10 2021-03-18 2020-08-20 2020-08-24 2020-09-15 2020-11-11 2021-03-14 ocales des plantations d'arbr rest and land management es dans le secteur entre LUK ENI - LOKORO , Territoire de 0shwe ZR-CARITAS-185700-CS-CDS / Contractualisation avec l'O Component 2 - Support com NG EQUIPE MIKA pour la valo TF / A0924 munity-based sustainable fo Post Direct Selection Direct 61,000.00 66,077.00 Signed 2020-08-10 2021-03-18 2020-08-20 2020-08-24 2020-09-15 2020-11-03 2021-03-14 risation des initiatives locales rest and land management des plantations d'arbres dans le secteur de Penzwa, Territo ire de Kiri ZR-CARITAS-175248-CS-CDS / Renouvelement de contrat Component 1 - Reinforce the avec LINAPYCO pour la Colle participation of the IPLC in fo Under Implement TF / A0924 Post Direct Selection Direct 120,000.00 0.00 2020-07-13 2020-07-13 2020-07-23 2020-07-23 2020-09-26 2021-03-25 cte des données sur les terre rest and land management ation s des PA pour la reconnaissa processes related to REDD+ nce légale et la sécurisation des terres ZR-CARITAS-62535-CS-CDS / Contractualisation avec Carit Component 1 - Reinforce the as diocese de MUJIMAYI , terri participation of the IPLC in fo toire de LUPATAPATA Les Les TF / A0924 Post Direct Selection Direct 6,000.00 6,000.00 Signed 2020-06-29 2021-03-17 2020-07-09 2020-07-27 2020-09-15 2020-08-21 2021-03-14 rest and land management justificatifs techniques ( note processes related to REDD+ s méthodologiques et cv des alphabétiseurs vous parviend rons par mail. ZR-CARITAS-185701-CS-CDS / Contractualisation avec le C entre National d'appui au Dé veloppement et à la participa Component 2 - Support com tion populaire (CENEDEP) po TF / A0924 munity-based sustainable fo Post Direct Selection Direct 66,000.00 0.00 Canceled 2020-08-10 2020-08-20 2020-09-15 2021-03-14 ur l'amélioration des capacit rest and land management és de 280 ménages PA et CO LO à planter et entretenir les arbres de la forêt MOBOKON DA secteur INONGO ZR-CARITAS-62464-CS-CDS / Component 1 - Reinforce the Contractualisation avec Carit participation of the IPLC in fo as diocese de KOLE pour l'éd TF / A0924 Post Direct Selection Direct 6,000.00 6,000.00 Signed 2020-09-21 2021-03-16 2020-10-01 2020-07-27 2021-11-22 2020-08-21 2022-02-20 rest and land management ucation de base et l'alphabéti processes related to REDD+ sation des PA et COLO Territo ire de DEKESE Page 2 ZR-CARITAS-189907-CS-CDS Component 1 - Reinforce the / Contractualisation avec l'O participation of the IPLC in fo NG CENADEP pour l'élevage TF / A0924 Post Direct Selection Direct 65,000.00 65,416.00 Signed 2020-09-21 2021-03-18 2020-10-01 2020-08-26 2020-12-05 2020-11-06 2021-06-03 rest and land management des porcs à MOMBOKONDA, processes related to REDD+ dans le Territoire d’INONGO ZR-CARITAS-185690-CS-CDS / Contractualisation avec l'O NG Programme d'intégration Component 1 - Reinforce the et du développement des pe participation of the IPLC in fo uples pygmées (PIDP) pour l' TF / A0924 Post Direct Selection Direct 6,000.00 0.00 Signed 2020-09-15 2020-09-08 2020-09-25 2021-09-18 2020-10-21 2021-04-19 rest and land management éducation de base et l'alphab processes related to REDD+ étisation aux peuples autoch tones (PA ) et aux communa utés locales (COLO) pour le T erritoire de Walikale. ZR-CARITAS-62537-CS-CDS / Component 1 - Reinforce the Contractualisation avec Carit participation of the IPLC in fo TF / A0924 Post Direct Selection Direct 6,000.00 6,000.00 Signed 2020-09-15 2021-03-17 2020-09-25 2020-07-27 2020-12-09 2020-08-21 2021-06-07 as de KISANGANI pour l'éduc rest and land management ation de base et l'alphabétisa processes related to REDD+ tion ZR-CARITAS-62539-CS-CDS / Component 1 - Reinforce the Contractualisation avec Carit participation of the IPLC in fo as diocese de TSHUMBE pour TF / A0924 Post Direct Selection Direct 6,000.00 6,000.00 Signed 2020-09-15 2020-07-10 2020-09-25 2020-07-27 2020-10-28 2020-08-21 2021-04-26 rest and land management l'éducation de base et l'alpha processes related to REDD+ bétisation Territoire de LUBE FU ZR-CARITAS-154570-CS-CDS Component 2 - Support com / Contractualisation avec AN TF / A0924 munity-based sustainable fo Post Direct Selection Direct 80,000.00 0.00 Canceled 2020-07-21 2020-07-31 2020-10-04 2021-04-02 APAC pour l'organisation de r rest and land management éunions avec les peules auto chtones ZR-CARITAS-175245-CS-CDS / Avenant avec ANAPAC pour Component 2 - Support com suivi des dossiers de deman TF / A0924 munity-based sustainable fo Post Direct Selection Direct 12,000.00 0.00 Canceled 2020-07-27 2020-08-06 2020-10-10 2021-04-08 de auprès du Ministère de l'e rest and land management nvironnement et du Gouvern ement ZR-CARITAS-175244-CS-CDS / Renouvellement contrat AN APAC pour organiser des ass Component 2 - Support com emblées communautaires et TF / A0924 munity-based sustainable fo Post Direct Selection Direct 285,000.00 0.00 Canceled 2020-07-21 2020-07-21 2020-07-31 2020-07-31 2020-10-04 2021-04-02 réunions consultatives, d'ide rest and land management ntification, prospection des si tes à : Walikale, Bikoro et fin alisation dossier Mweka, Kiri et Mambasa ZR-CARITAS-196411-CS-CDS Component 1 - Reinforce the / Contractualisation avec DG participation of the IPLC in fo PA pour Suivi des loi au Parle TF / A0924 Post Direct Selection Direct 25,500.00 0.00 Signed 2020-09-28 2020-09-28 2020-10-08 2020-09-08 2020-12-12 2021-06-10 rest and land management ment et lutte contre la discri processes related to REDD+ mination pour les PA ZR-CARITAS-62578-CS-CDS / DIPED: Opérateur pour acco mpagner les communautés d Component 2 - Support com e Walikale dans l'identificatio TF / A0924 munity-based sustainable fo Post Direct Selection Direct 5,800.00 0.00 Canceled 2018-05-14 2018-05-24 2018-07-28 2019-01-24 n des idées des microprojets rest and land management et des Opérateurs locaux d'a ppui aux communautés -Com posante 2.a.1 - Consultant ZR-CARITAS-62576-CS-CDS / UEFA: Opérateur pour accom pagner les communautés de Component 2 - Support com Kalehe dans l'identification d TF / A0924 munity-based sustainable fo Post Direct Selection Direct 5,800.00 0.00 Canceled 2018-05-14 2018-05-24 2018-07-28 2019-01-24 es idées des microprojets et rest and land management des Opérateurs locaux d'app ui aux communautés -Compo sante 2.a.1 - Consultant ZR-CARITAS-49316-CS-CDS / CAIF- Opérateur pour accom Component 2 - Support com pagner les communautés (m TF / A0924 munity-based sustainable fo Post Direct Selection Direct 9,900.00 0.00 Canceled 2018-03-01 2018-03-11 2018-05-15 2018-11-11 icroprojets et des Opérateurs rest and land management locaux d'appui aux communa utés Lubao et Lubefu ZR-CARITAS-62579-CS-CDS / FECOFA: Opérateur pour acc ompagner les communautés Component 2 - Support com de Kabinda et Lusambo dans TF / A0924 munity-based sustainable fo Post Direct Selection Direct 9,900.00 0.00 Canceled 2018-05-14 2018-05-24 2018-07-28 2019-01-24 l'identification des idées des rest and land management microprojets et des Opérateu rs locaux d'appui aux commu nautés -Composante 2.a.1 - Consultant ZR-CARITAS-62575-CS-CDS / GTF: Opérateur pour accomp agner les communautés de Y Component 2 - Support com ahuma et Opala dans l'identif TF / A0924 munity-based sustainable fo Post Direct Selection Direct 9,800.00 0.00 Canceled 2018-05-14 2018-05-24 2018-07-28 2019-01-24 ication des idées des micropr rest and land management ojets et des Opérateurs locau x d'appui aux communautés -Composante 2.a.1 - Consult ant ZR-CARITAS-62572-CS-CDS / EPAP/RDC: Opérateur pour a ccompagner les communaut Component 2 - Support com és de Lupatapata et Dimbele TF / A0924 munity-based sustainable fo Post Direct Selection Direct 9,350.00 0.00 Canceled 2018-05-14 2018-05-24 2018-07-28 2019-01-24 nge dans l'identification des i rest and land management dées des microprojets et des Opérateurs locaux d'appui au x communautés -Composant e 2.a.1 - Consultant ZR-CARITAS-62582-CS-CDS / APSVR:Opérateur pour acco mpagner les communautés d Component 2 - Support com e Mweka et Dekese dans l'id TF / A0924 munity-based sustainable fo Post Direct Selection Direct 9,700.00 0.00 Canceled 2018-05-14 2019-10-30 2018-05-24 2018-07-28 2019-01-24 entification des idées des mi rest and land management croprojets et des Opérateurs locaux d'appui aux communa utés -Composante 2.a.1 - Co nsultant ZR-CARITAS-62581-CS-CDS / OCEAN: Opérateur pour acco mpagner les communautés d Component 2 - Support com e Banalia, Bafwasende et Ma TF / A0924 munity-based sustainable fo Post Direct Selection Direct 12,950.00 0.00 Canceled 2018-05-14 2018-05-24 2018-07-28 2019-01-24 mbasa dans l'identification d rest and land management es idées des microprojets et des Opérateurs locaux d'app ui aux communautés -Compo sante 2.a.1 - Consultant Page 3 ZR-CARITAS-49123-CS-CDS / Consultant Kasongo Kabusa Component 2 - Support com Raphael, chargé d'identificati TF / A0924 munity-based sustainable fo Post Direct Selection Direct 8,000.00 0.00 Canceled 2018-02-05 2018-02-15 2018-04-21 2018-10-18 on des expériences de mise rest and land management en œuvre des microprojets c ommunautaires ZR-CARITAS-125538-CS-CDS Component 1 - Reinforce the / Contrat REPEQ identificatio participation of the IPLC in fo TF / A0924 Post Direct Selection Direct 10,000.00 0.00 Canceled 2019-08-31 2019-09-10 2019-11-14 2020-05-12 n des besoins en renforceme rest and land management nt des capacités processes related to REDD+ ZR-CARITAS-62580-CS-CDS / DIPY: Opérateur pour accom pagner les communautés d'I Component 2 - Support com nongo et Oshwe dans l'identi TF / A0924 munity-based sustainable fo Post Direct Selection Direct 9,800.00 0.00 Canceled 2018-05-14 2018-05-24 2018-07-28 2019-01-24 fication des idées des microp rest and land management rojets et des Opérateurs loca ux d'appui aux communautés -Composante 2.a.1 - Consult ant ZR-CARITAS-49610-CS-CDS / -CIDB: Opérateur d'identificat Component 2 - Support com ion des micros projets et ON TF / A0924 munity-based sustainable fo Post Direct Selection Direct 9,600.00 0.00 Canceled 2018-03-01 2018-03-11 2018-05-15 2018-11-11 G locales ( Bikoro et Kiri) AN rest and land management O obtenu 25/09/2017 Component 1 - Reinforce the ZR-CARITAS-122741-CS-CDS participation of the IPLC in fo Individual Consult / Evaluation à mis parcours s TF / A0924 Post Limited 17,500.00 0.00 Canceled 2019-08-10 2019-08-15 2019-09-05 2019-10-10 2020-04-07 rest and land management ant Selection uivi processes related to REDD+ ZR-CARITAS-253078-CS-CDS / Renouvellement de contrat Component 1 - Reinforce the avec Caritas diocésaine de M participation of the IPLC in fo TF / A0924 Post Direct Selection Direct 6,000.00 0.00 Under Review 2021-12-08 2020-09-08 2021-12-18 2022-02-21 2022-06-21 BANDAKA pour l'éducation d rest and land management e base et l'alphabétisation, T processes related to REDD+ erritoire de BIKORO composa nte 1b ZR-CARITAS-253085-CS-CDS / Renouvellement avec ANAP AC pour appui à l'élaboration des cartes des droits et d'aff Component 2 - Support com ectation des terres, plans de TF / A0924 munity-based sustainable fo Post Direct Selection Direct 113,500.00 0.00 Canceled 2021-12-08 2021-12-08 2021-12-18 2021-12-18 2022-02-21 2022-06-21 sondage, Dépôt des dossiers rest and land management de demande de CFCL, Enquê te de vacance des terres, Ob tention de CFCL à Mweka, Bi ko, Walikale. composante 2b ZR-CARITAS-253091-CS-CDS Component 3 - Increase the / Renouvellement de Contrat capacity to implement the IP avec REPALEF pour le suivi d TF / A0924 Post Direct Selection Direct 40,500.00 0.00 Signed 2021-12-08 2021-12-08 2021-12-18 2021-12-18 2022-02-21 2022-06-21 LC development activities a e satisfaction et gestion des nd consolidate feedback plaintes. composante 3b ZR-CARITAS-253093-CS-CDS / Renouvellement de contrat Component 1 - Reinforce the avec (CENADEP) pour l'améli participation of the IPLC in fo oration des capacités de 280 TF / A0924 Post Direct Selection Direct 38,045.00 0.00 Signed 2021-12-08 2022-02-28 2021-12-18 2022-03-10 2022-02-21 2022-06-21 rest and land management ménages PA et COLO à plant processes related to REDD+ er et entretenir les arbres de la forêt MOBOKONDA secteur INONGO. composante 2a ZR-CARITAS-253094-CS-CDS / Renouvellement contrat av ec l'ONG ADGRN pour le pro Component 2 - Support com jet de plantation d’arbres su TF / A0924 munity-based sustainable fo Post Direct Selection Direct 71,250.00 73,773.50 Signed 2021-12-08 2021-12-06 2021-12-18 2022-01-31 2022-02-21 2022-01-25 2022-03-05 r 45 ha et de promotion de l’ rest and land management élevage et de l'apiculture da ns les villages de Milela, Toko meka et Tshintu mwanza, Te rritoire de Lupatapata. comp osante 2a ZR-CARITAS-253072-CS-CDS / Renouvellement contrat Ca ritas diocésaine Kabinda po Component 1 - Reinforce the ur le projet d'appui à la prote participation of the IPLC in fo ction du forestière par l'agro TF / A0924 Post Direct Selection Direct 73,960.00 0.00 Signed 2021-12-08 2022-01-14 2021-12-18 2022-01-31 2022-03-08 2022-07-06 rest and land management foresterie et en faveur des p processes related to REDD+ euples autochtones pour les villages de Tulimbi, Ebaala et Kashoko, Territoire de Kabind a composante 2a ZR-CARITAS-253097-CS-CDS / Renouvellement de contrat Component 2 - Support com avec l'ONG SPFA pour le proj TF / A0924 munity-based sustainable fo Post Direct Selection Direct 22,680.00 0.00 Signed 2021-09-30 2021-09-30 2021-10-10 2021-10-10 2021-12-14 2022-04-13 et d'appui à l'agroforesterie e rest and land management t à la pisciculture dans les vill ages Moboyo, Mboli et Iyand a, dans le Territoire de Bikor o ZR-CARITAS-253098-CS-CDS / Renouvellement contrat UE Component 2 - Support com FA projet d'amélioration des TF / A0924 munity-based sustainable fo Post Direct Selection Direct 48,760.00 0.00 Signed 2021-12-08 2021-07-01 2021-12-18 2023-01-01 2022-02-21 2022-06-21 écosystèmes forestiers avec l rest and land management a plantation d'arbres de 17 g roupements du Territoire de Kalehe, composante 2b ZR-CARITAS-253067-CS-CDS / Renouvellement de contrat Component 1 - Reinforce the avec Caritas diocésaine Kisa participation of the IPLC in fo ngani pour donner l'Educatio TF / A0924 Post Direct Selection Direct 3,000.00 0.00 Canceled 2021-12-08 2021-12-08 2021-12-18 2022-03-03 2022-07-01 rest and land management n de base et alphabétisation processes related to REDD+ aux PA et Communautés loca les Territoire BANALIA comp osante 1b ZR-CARITAS-253086-CS-CDS / Renouvellement de contrat avec l'ONG FONDATION NSEL Component 2 - Support com ALA pour valorisation des init TF / A0924 munity-based sustainable fo Post Direct Selection Direct 30,761.00 0.00 Signed 2021-12-08 2021-12-08 2021-12-18 2022-02-07 2022-01-13 2022-05-13 iatives locales des plantation rest and land management s d'arbres dans le secteur en tre LUKENI - LOKORO, Territoi re de 0shwe. composante 2a ZR-CARITAS-253090-CS-CDS / Renouvellement de Contrat Component 1 - Reinforce the avec LINAPYCO pour la Colle participation of the IPLC in fo TF / A0924 Post Direct Selection Direct 61,790.00 0.00 Signed 2021-12-08 2021-12-08 2021-12-18 2021-12-18 2022-02-21 2022-06-21 cte des données sur les terre rest and land management s des PA pour la reconnaissa processes related to REDD+ nce légale et la sécurisation des terres. composante 1a Page 4 ZR-CARITAS-253096-CS-CDS / Renouvellement Contrat av ec l'ONG Programme d'intég Component 1 - Reinforce the ration et du développement participation of the IPLC in fo des peuples pygmées (PIDP) TF / A0924 Post Direct Selection Direct 42,300.00 0.00 Signed 2021-12-08 2016-07-01 2021-12-18 2022-12-09 2022-02-21 2022-06-21 rest and land management pour le projet d'amélioration processes related to REDD+ des capacités de production agropastorale des ménages autochtones pygmées dans l e Territoire de Walikale. com pos 2a ZR-CARITAS-253099-CS-CDS / Renouvellement contrat DG Component 1 - Reinforce the PA pour soutien à la finalisati participation of the IPLC in fo on de 4 concessions : Bondo, TF / A0924 Post Direct Selection Direct 106,636.00 0.00 Signed 2021-09-30 2017-07-17 2021-10-10 2017-07-27 2021-12-14 2022-04-13 rest and land management Kombe, Mitshia, Tongonwena processes related to REDD+ forestières des communauté s locales de TSHIEFU / Territo ire de Dimbelenge. composa nte 2b ZR-CARITAS-253095-CS-CDS / Contractualisation avec CA RITAS Kabinda pour le pro d Component 2 - Support com 'appui à la protection du cou TF / A0924 munity-based sustainable fo Post Direct Selection Direct 71,359.00 0.00 Signed 2022-01-27 2022-01-27 2022-02-06 2022-02-18 2022-04-12 2022-08-10 ver forestier par l'agroforeste rest and land management rie, la porciculture et la picic ulture en faveur des peuples autochtones des villages d'E baala et Kangulube, Territoir e de Lubao. c 2a ZR-CARITAS-253087-CS-CDS / Renouvellement de contrat avec l'ONG EQUIPE MIKA pou Component 2 - Support com r la valorisation des initiative TF / A0924 munity-based sustainable fo Post Direct Selection Direct 12,500.00 0.00 Signed 2021-12-08 2021-12-08 2021-12-18 2021-12-18 2022-01-13 2022-05-13 s locales des plantations d'ar rest and land management bres dans le secteur de Penz wa, Territoire de Kiri. compos ante 2a ZR-CARITAS-280706-CS-CDS / CAIF- Opérateur pour acco Component 2 - Support com mpagner les communautés ( TF / A0924 munity-based sustainable fo Post Direct Selection Direct 9,800.00 0.00 Signed 2022-04-10 2022-04-10 2022-04-20 2022-04-20 2022-06-24 2022-12-21 microprojets et des Opérateu rest and land management rs locaux d'appui aux commu nautés Lubao et Lubefu ZR-CARITAS-280677-CS-CDS / EPAP/RDC: Opérateur pour accompagner les communau Component 2 - Support com tés de Lupatapata et Dimbel TF / A0924 munity-based sustainable fo Post Direct Selection Direct 9,800.00 0.00 Signed 2022-04-10 2022-04-10 2022-04-20 2022-04-20 2022-06-24 2022-12-21 enge dans l'identification des rest and land management idées des microprojets et des Opérateurs locaux d'appui au x communautés -Composant e 2.a.1 - Consultant ZR-CARITAS-280720-CS-CDS / Recrutement d'un opérateu r spécialisé, chargé d'organis er des assemblées communa Component 2 - Support com utaires et d'accompagner les TF / A0924 munity-based sustainable fo Post Direct Selection Direct 80,000.00 0.00 Canceled 2022-04-10 2022-04-20 2022-06-24 2022-12-21 PA et communautés locales d rest and land management ans le processus de la reconn aissance formelle de leur con cession forestière et de leurs aires de conservation ZR-CARITAS-280674-CS-CDS / APSVR: Opérateur pour acc ompagner les communautés Component 2 - Support com de Mweka et Dekese dans l'i TF / A0924 munity-based sustainable fo Post Direct Selection Direct 9,800.00 0.00 Signed 2022-04-10 2022-04-10 2022-04-20 2022-04-20 2022-06-24 2022-12-21 dentification des idées des m rest and land management icroprojets et des Opérateurs locaux d'appui aux communa utés -Composante 2.a.1 - Co nsultant ZR-CARITAS-280683-CS-CDS / OCEAN: Opérateur pour acc ompagner les communautés Component 2 - Support com de Banalia, Bafwasende et M TF / A0924 munity-based sustainable fo Post Direct Selection Direct 12,950.00 0.00 Signed 2022-04-10 2022-04-10 2022-04-20 2022-04-20 2022-06-24 2022-12-21 ambasa dans l'identification rest and land management des idées des microprojets et des Opérateurs locaux d'app ui aux communautés -Compo sante 2.a.1 - Consultant ZR-CARITAS-280711-CS-CDS / DIPY: Opérateur pour acco mpagner les communautés d Component 2 - Support com 'Inongo et Oshwe dans l'ident TF / A0924 munity-based sustainable fo Post Direct Selection Direct 9,800.00 0.00 Signed 2022-04-10 2022-04-10 2022-04-20 2022-04-20 2022-06-24 2022-12-21 ification des idées des micro rest and land management projets et des Opérateurs loc aux d'appui aux communaut és -Composante 2.a.1 – Cons ultant ZR-CARITAS-281043-CS-CDS / Avenant avec ANAPAC pour Component 2 - Support com suivi des dossiers de demand TF / A0924 munity-based sustainable fo Post Direct Selection Direct 27,000.00 0.00 Signed 2022-04-10 2022-04-10 2022-04-20 2022-12-07 2022-06-24 2022-12-21 e auprès du Ministère de l'en rest and land management vironnement et du Gouverne ment ZR-CARITAS-280020-CS-CDS Component 2 - Support com / Identification des idées des TF / A0924 munity-based sustainable fo Post Direct Selection Direct 5,800.00 0.00 Signed 2022-04-10 2022-04-10 2022-04-20 2022-04-20 2022-06-24 2022-12-21 micro-projets dans le territoir rest and land management e de Walikale ZR-CARITAS-280023-CS-CDS / UEFA: Opérateur pour acco mpagner les communautés d Component 2 - Support com e Kalehe dans l'identification TF / A0924 munity-based sustainable fo Post Direct Selection Direct 5,800.00 0.00 Signed 2022-04-10 2022-04-10 2022-04-20 2022-04-20 2022-06-10 2022-12-07 des idées des microprojets et rest and land management des Opérateurs locaux d'app ui aux communautés -Compo sante 2.a.1 - Consultant ZR-CARITAS-280659-CS-CDS / FECOFA: Opérateur pour ac compagner les communauté Component 2 - Support com s de Kabinda et Lusambo à l'i TF / A0924 munity-based sustainable fo Post Direct Selection Direct 9,800.00 0.00 Signed 2022-04-10 2022-04-20 2022-04-20 2022-10-12 2022-06-24 2022-12-21 dentification des idées des m rest and land management icroprojets et des Opérateurs locaux d'appui aux communa utés -Composante 2.a.1 - Co nsultant ZR-CARITAS-280688-CS-CDS / Contrat REPEQ renforcemen Component 1 - Reinforce the t des capacités dans le cadre participation of the IPLC in fo TF / A0924 Post Direct Selection Direct 5,000.00 0.00 Signed 2022-04-10 2023-04-10 2022-04-20 2023-06-18 2022-06-24 2022-12-21 du plan d’action pour le déve rest and land management loppement et la promotion d processes related to REDD+ es droits des peuples autocht ones en RDC Page 5 Component 1 - Reinforce the ZR-CARITAS-280724-CS-CDS participation of the IPLC in fo / Evaluation externe à mi-par TF / A0924 Post Direct Selection Direct 20,000.00 0.00 Signed 2022-04-10 2023-06-12 2022-04-20 2023-06-18 2022-06-24 2022-12-21 rest and land management cours du projet PACDF processes related to REDD+ ZR-CARITAS-286914-CS-CDS / GTF: Opérateur pour accom pagner les communautés de Component 2 - Support com Yahuma et Opala dans l'ident Under Implement TF / A0924 munity-based sustainable fo Post Direct Selection Direct 9,800.00 0.00 2022-04-10 2023-06-12 2022-04-20 2023-06-18 2022-06-24 2022-12-21 ification des idées des micro ation rest and land management projets et des Opérateurs loc aux d'appui aux communaut és -Composante 2.a.1 – Cons ultant Component 1 - Reinforce the ZR-CARITAS-279788-CS-CQS participation of the IPLC in fo / Contractualisation avec le c TF / A0924 Post Direct Selection Direct 30,000.00 0.00 Canceled 2022-04-10 2022-04-20 2022-06-24 2022-12-21 rest and land management onsultant DGPA processes related to REDD+ ZR-CARITAS-281039-CS-CDS / ANAPAC: accompagner les PA et les COLO dans le proce ssus de la reconnaissance for Component 2 - Support com melle de leurs concessions fo TF / A0924 munity-based sustainable fo Post Direct Selection Direct 250,000.00 0.00 Signed 2022-05-20 2022-05-20 2022-05-30 2022-05-30 2022-08-03 2023-01-30 restières et des aires de cons rest and land management ervation et patrimoine autoc htone et communautaires da ns les sites de Walikale, Bikor o, Kiri, Mambasa et Mweka ZR-CARITAS-280041-CS-CDS / FECOFA: Opérateur pour ac compagner les communauté Component 2 - Support com s de Kabinda et Lusambo dan TF / A0924 munity-based sustainable fo Post Direct Selection Direct 9,800.00 0.00 Canceled 2022-04-10 2022-04-10 2022-04-20 2022-06-24 2022-12-21 s l'identification des idées de rest and land management s microprojets et des Opérat eurs locaux d'appui aux com munautés -Composante 2.a.1 - Consultant ZR-CARITAS-281031-CS-CDS / Renouvèlement de contrat Component 1 - Reinforce the avec LINAPYCO pour la Collec participation of the IPLC in fo TF / A0924 Post Direct Selection Direct 120,000.00 0.00 Canceled 2022-04-10 2022-04-20 2022-06-24 2022-12-21 te des données sur les terres rest and land management des PA pour la reconnaissanc processes related to REDD+ e légale et la sécurisation de s terres ZR-CARITAS-253083-CS-CDS / Renouvellement de contrat Component 1 - Reinforce the avec Caritas diocésaine de M participation of the IPLC in fo TF / A0924 Post Direct Selection Direct 6,000.00 0.00 Canceled 2021-12-08 2020-09-08 2021-12-18 2022-02-21 2022-06-21 WEKA pour l'éducation de ba rest and land management se et l'alphabétisation, Territ processes related to REDD+ oire MWEKA composante 1b ZR-CARITAS-300093-CS-CQS / POINT FOCAL: Suivi rapproc Component 2 - Support com Individual Consult Under Implement hé environnemental et social TF / A0924 munity-based sustainable fo Post Direct 3,000.00 0.00 2022-06-30 2022-10-11 2022-07-10 2022-07-31 2022-09-04 2023-03-03 ant Selection ation des activités des microprojet rest and land management s dans le territoire de Walikal e ZR-CARITAS-300099-CS-CQS / POINT FOCAL: Suivi rapproc Component 2 - Support com Individual Consult hé environnemental et social TF / A0924 munity-based sustainable fo Post Direct 3,000.00 0.00 Canceled 2022-06-30 2022-10-11 2022-07-10 2022-07-31 2022-09-04 2023-03-03 ant Selection des activités des microprojet rest and land management s dans le territoire de Kahele ZR-CARITAS-300107-CS-CQS / POINT FOCAL: Suivi rapproc hé environnemental et social Component 2 - Support com Individual Consult Under Implement des activités à Mbuji-Mayi da TF / A0924 munity-based sustainable fo Post Direct 9,000.00 0.00 2022-06-30 2022-10-11 2022-07-10 2022-07-31 2022-09-04 2023-03-03 ant Selection ation ns les territoires de Lupatapa rest and land management ta (Tshintumuanza, Tokomek a et Milela), Kabinda (Ebala - Tulimbi) et Lubao (Kangulube ) ZR-CARITAS-319901-CS-CDS Component 3 - Increase the / ADDEC: Recrutement d'une capacity to implement the IP ONG d'appui à la mise en œu TF / A5550 Post Direct Selection Direct - National 99,373.50 0.00 Signed 2022-10-11 2022-10-11 2022-10-21 2022-10-21 2022-12-25 2023-06-23 LC development activities a vre de microprojet à Kabala, nd consolidate feedback dans le territoire de Dimbele nge ZR-CARITAS-319916-CS-CDS / UNION POUR LE DEVELOPPE MENT DES MINORITES EKON Component 2 - Support com DA: Recrutement d'une ONG TF / A5550 munity-based sustainable fo Post Direct Selection Direct - National 108,749.00 0.00 Signed 2022-10-11 2022-10-11 2022-10-21 2022-10-22 2022-12-25 2023-06-23 d'appui à la mise en œuvre d rest and land management e microprojet à MPANGOLA, dans le territoire de LUSAMB O ZR-CARITAS-319961-CS-CDS / FODI: Recrutement d'une O Component 2 - Support com NG d'appui à la mise en œuv TF / A5550 munity-based sustainable fo Post Direct Selection Direct - National 104,749.00 0.00 Signed 2022-10-11 2022-10-11 2022-10-20 2022-10-21 2022-12-24 2023-06-22 re de microprojet dans le vill rest and land management age d'Itunga, territoire de Lu befu ZR-CARITAS-319986-CS-CDS / PCF: Recrutement d'une ON Component 1 - Reinforce the G d'appui à la mise en œuvre participation of the IPLC in fo TF / A5550 Post Direct Selection Direct - National 96,509.50 0.00 Signed 2022-10-11 2022-10-11 2022-10-21 2022-10-21 2022-12-25 2023-06-23 de microprojet à MANGBAUT rest and land management U, KILONDE, et BANANA GITE processes related to REDD+ dans le territoire de MAMBAS A ZR-CARITAS-319996-CS-CDS / CARITAS KABINDA: Recrute Component 2 - Support com ment d'une structure d'appui TF / A5550 munity-based sustainable fo Post Direct Selection Direct - National 72,509.00 0.00 Canceled 2022-10-11 2022-10-11 2022-10-21 2022-12-25 2023-06-23 à la mise en œuvre de micro rest and land management projet à TSHINTU MWANZA, MILELA et TOKOMEKA dans le territoire de LUPATAPATA ZR-CARITAS-320000-CS-CDS / ACODELPY: Recrutement d' Component 2 - Support com une ONG d'appui à la mise e TF / A5550 munity-based sustainable fo Post Direct Selection Direct - National 99,948.50 0.00 Signed 2022-10-11 2022-10-11 2022-10-21 2022-10-11 2022-12-25 2023-06-23 n œuvre de microprojet à BI rest and land management MELI, dans le territoire de BA FWASENDE Page 6 ZR-CARITAS-300080-CS-CDS / LIMA: Promotion des initiati ves de restauration de la forê t, développement des alterna Component 2 - Support com tives économiques compensa TF / A0924 munity-based sustainable fo Post Direct Selection Direct - National 111,383.50 0.00 Signed 2022-10-11 2022-10-11 2022-10-21 2022-10-21 2022-12-25 2023-06-23 toires aux efforts de la forêt rest and land management et contribution à la cohésion sociale entre les PA et les CO LO à Bomili dans le territoire de Bafwasende. Com 2a ZR-CARITAS-300070-CS-CDS / CARITAS ISANGI: Contributi on à la réduction de la pressi on sur la forêt par l'améliorat Component 2 - Support com ion de la production, commer TF / A0924 munity-based sustainable fo Post Direct Selection Direct - National 116,220.00 0.00 Signed 2022-10-11 2022-10-11 2022-10-21 2022-12-12 2022-12-25 2023-06-23 cialisation du riz, du manioc, rest and land management du miel et l'artisanat en fave ur des PA et des COLO à Yalo nde et Yasamola dans le terri toire de Yahuma. C 2a ZR-CARITAS-300059-CS-CDS / CARITAS ISANGI: Contributi on à la restauration de la for Component 2 - Support com êt, la croissance économique TF / A0924 munity-based sustainable fo Post Direct Selection Direct - National 83,056.00 0.00 Signed 2022-10-11 2022-10-11 2022-10-21 2022-10-21 2022-12-25 2023-06-23 de 150 ménages cibles et en rest and land management même temps à l'encouragem ent de la cohésion sociale de s PA et CL à Lieke Lesole dan s le territoire d'Opala. Compo sante 2a ZR-CARITAS-300115-CS-CDS / LIMA: Promotion des initiati ves de restauration de la forê t, développement des alterna Component 2 - Support com tives économiques compensa TF / A0924 munity-based sustainable fo Post Direct Selection Direct - National 111,383.50 0.00 Canceled 2022-10-11 2022-10-21 2022-12-25 2023-06-23 toires aux efforts de la forêt rest and land management et contribution à la cohésion sociale entre les PA et les CO LO à Bangbo dans le territoir e de Banalia. Comp 2a ZR-CARITAS-280716-CS-CDS / Consultant Kasongo Kabusa Component 2 - Support com Individual Consult Raphael, Chargé d’identificat TF / A0924 munity-based sustainable fo Post Direct - National 8,000.00 0.00 Signed 2022-10-11 2022-10-11 2022-10-21 2022-10-22 2022-11-11 2022-11-11 2022-12-16 2023-06-14 ant Selection ion des expériences de mise rest and land management en œuvre des microprojets c ommunautaires ZR-CARITAS-320534-CS-CDS / CARITAS KOLE: Recrutemen Component 2 - Support com t d'une ONG d'appui à la mis TF / A5550 munity-based sustainable fo Post Direct Selection Direct - National 99,603.00 0.00 Signed 2022-10-12 2022-11-21 2022-10-22 2022-12-01 2022-12-26 2023-06-24 e en œuvre de microprojet à rest and land management ITUNGA dans le territoire de DEKESE. Comp 2a ZR-CARITAS-320537-CS-CDS / CEDAP: Recrutement d'une ONG locale pour la mise en œuvre du projet de restaurat Component 2 - Support com ion de la foret d'Itungampen TF / A5550 munity-based sustainable fo Post Direct Selection Direct - National 105,094.00 0.00 Signed 2022-10-12 2022-11-21 2022-10-22 2022-12-01 2022-12-26 2023-06-24 de à travers la plantation d'a rest and land management rbres et le développement de s alternatives économiques pour lutter contre la dégrada tion de la foret. Comp 2a ZR-CARITAS-320542-CS-IND V / POINT FOCAL: Recruteme Component 2 - Support com nt d'un consultant pour le sui Individual Consult TF / A5550 munity-based sustainable fo Post Direct - National 5,200.00 0.00 Signed 2022-10-12 2022-11-21 2022-10-22 2022-12-01 2022-11-12 2022-12-22 2022-12-17 2023-06-15 vi environnemental et social ant Selection rest and land management dans les territoires de BAFW ASENDE, YAHUMA, OPALA et BANALIA ZR-CARITAS-320547-CS-IND V / POINT FOCAL: Recruteme Component 2 - Support com Individual Consult nt d'un consultant pour le sui TF / A5550 munity-based sustainable fo Post Direct - National 1,000.00 0.00 Signed 2022-10-11 2022-11-21 2022-10-21 2022-11-26 2022-11-11 2022-12-17 2022-12-16 2023-06-14 ant Selection vi environnemental et social rest and land management dans le territoire de MAMBAS A ZR-CARITAS-320549-CS-IND V / POINT FOCAL: Recruteme Component 2 - Support com Individual Consult nt d'un consultant pour le sui TF / A5550 munity-based sustainable fo Post Direct - National 4,200.00 0.00 Signed 2022-10-12 2022-11-21 2022-10-22 2022-12-01 2022-11-12 2022-12-22 2022-12-17 2023-06-15 ant Selection vi environnemental et social rest and land management dans les territoires de MWEK A, DEKESE et DIMBELENGE ZR-CARITAS-320552-CS-IND V / POINT FOCAL: Recruteme Component 2 - Support com Individual Consult nt d'un consultant pour le sui TF / A5550 munity-based sustainable fo Post Direct - National 3,400.00 0.00 Signed 2022-10-12 2022-11-21 2022-10-22 2022-12-01 2022-11-12 2022-12-22 2022-12-17 2023-06-15 ant Selection vi environnemental et social rest and land management dans les territoires de LUSAM BO ET LUBEFU ZR-CARITAS-253070-CS-CDS / Renouvellement contrat Car Component 1 - Reinforce the itas Mbujimayi pour donner l' participation of the IPLC in fo TF / A0924 Post Direct Selection Direct 5,400.00 0.00 Canceled 2021-12-08 2021-07-08 2021-12-18 2022-02-24 2022-06-24 éducation de base et alphab rest and land management étisation aux PA et communa processes related to REDD+ utés locales territoire de LUP ATAPATA composante 1b ZR-CARITAS-253063-CS-CDS / Renouvellement contrat av Component 1 - Reinforce the ec Caritas diocèse Kananga p participation of the IPLC in fo TF / A0924 Post Direct Selection Direct 6,000.00 0.00 Canceled 2021-12-08 2021-12-08 2021-12-18 2022-02-21 2022-06-21 our l'Education de base des P rest and land management A et communautés locales Te processes related to REDD+ rritoire de Dimbelenge comp 1b ZR-CARITAS-253084-CS-CDS Component 1 - Reinforce the / Renouvellement contrat av participation of the IPLC in fo ec Caritas diocésaine de WA TF / A0924 Post Direct Selection Direct 12,000.00 0.00 Canceled 2021-12-08 2021-12-08 2021-12-18 2022-02-21 2022-06-21 rest and land management MBA Alphabétisation Dio WA processes related to REDD+ MBA - MAMBASA ET BAFWAS ENDE composante 1b ZR-CARITAS-253082-CS-CDS Component 1 - Reinforce the / Renouvellement de contrat participation of the IPLC in fo avec Caritas BUKAVU sur l'Al TF / A0924 Post Direct Selection Direct 6,000.00 0.00 Canceled 2021-12-08 2020-09-08 2021-12-18 2020-09-22 2022-02-21 2022-06-21 rest and land management phabétisation Dio BUKAVU, T processes related to REDD+ erritoire de KALEHE composa nte 1b ZR-CARITAS-253089-CS-CDS Component 1 - Reinforce the / Renouvellement de Contrat participation of the IPLC in fo avec DGPA pour Suivi des loi TF / A0924 Post Direct Selection Direct 30,000.00 0.00 Canceled 2021-12-08 2020-09-08 2021-12-18 2022-02-21 2022-06-21 rest and land management au Parlement et lutte contre l processes related to REDD+ a discrimination pour les PA. composante 1a Page 7 ZR-CARITAS-280035-CS-CDS / CAIF- Opérateur pour acco Component 2 - Support com mpagner les communautés à TF / A0924 munity-based sustainable fo Post Direct Selection Direct 9,900.00 0.00 Canceled 2022-04-10 2022-04-20 2022-06-24 2022-12-21 l’identification des micro-proj rest and land management ets pour les territoires de Lub ao et Lubefu ZR-CARITAS-253092-CS-CDS / Renouvellement de Contrat avec l'ONG Programme d'inté Component 1 - Reinforce the gration et du développement participation of the IPLC in fo des peuples pygmées (PIDP) TF / A0924 Post Direct Selection Direct 6,000.00 0.00 Canceled 2021-12-08 2020-09-08 2021-12-18 2022-01-13 2022-05-13 rest and land management pour l'éducation de base et l' processes related to REDD+ alphabétisation aux peuples autochtones (PA ) et aux com munautés locales (COLO) po ur le Territoire de Walikale. c 1b ZR-CARITAS-253073-CS-CDS / Renouvellement de contrat Component 1 - Reinforce the avec Caritas diocésaine de d participation of the IPLC in fo TF / A0924 Post Direct Selection Direct 6,000.00 0.00 Canceled 2021-12-08 2021-12-08 2021-12-18 2022-05-31 2022-09-28 e KOLE pour l'éducation de b rest and land management ase et l'alphabétisation des P processes related to REDD+ A et COLO Territoire de DEKE SE composante 1b ZR-CARITAS-253088-CS-CDS / Renouvellement de contrat Component 1 - Reinforce the avec Caritas diocèse d'ISANG participation of the IPLC in fo TF / A0924 Post Direct Selection Direct 12,000.00 0.00 Canceled 2021-12-08 2021-12-27 2021-12-18 2022-01-15 2022-02-21 2022-06-21 I, territoire de YAHUMA et OP rest and land management ALA pour l'éducation de bas processes related to REDD+ e et l'alphabétisation. compo sante 1b ZR-CARITAS-280699-CS-CDS / Identification des idées des Component 2 - Support com microprojets et des organisat TF / A0924 munity-based sustainable fo Post Direct Selection Direct 5,900.00 0.00 Canceled 2022-04-10 2022-04-20 2022-06-24 2022-12-21 ions et site d'implémentation rest and land management du microprojet à Walikale ZR-CARITAS-253081-CS-CDS / Renouvellement de contrat Component 1 - Reinforce the avec Caritas diocésaine de K participation of the IPLC in fo TF / A0924 Post Direct Selection Direct 18,000.00 0.00 Canceled 2021-12-08 2021-12-08 2021-12-18 2022-03-08 2022-07-06 ABINDA pour l'alphabétisatio rest and land management n , Territoire KABINDA, LUBA processes related to REDD+ O et LUSAMBO composante 1 b ZR-CARITAS-294564-CS-CQS Component 3 - Increase the / Recrutement d'un auditeur capacity to implement the IP Individual Consult externe pour la révision du m TF / A0924 Post Direct 3,000.00 0.00 Canceled 2022-06-24 2022-10-11 2022-07-04 2022-07-25 2022-08-29 2023-02-25 LC development activities a ant Selection anuel des procédures admini nd consolidate feedback stratives et financières du pr ojet PACDF ZR-CARITAS-242600-CS-IND Component 3 - Increase the V / Recrutement d'un consult capacity to implement the IP Individual Consult ant individuel pour la révisio TF / A0924 Post Limited 4,000.00 0.00 Canceled 2021-07-30 2021-08-04 2021-08-25 2021-09-29 2021-11-13 LC development activities a ant Selection n du manuel des procédures nd consolidate feedback administratives et financière s du projet PCDF ZR-CARITAS-362380-CS-CDS Component 3 - Increase the / Recrutement d'un Consulta capacity to implement the IP Individual Consult Direct - Internation nt International pour l'évalua TF / A0924 Post 10,000.00 0.00 Canceled 2023-05-30 2023-05-30 2023-06-09 2023-06-04 2023-06-30 2023-08-04 2024-01-31 LC development activities a ant Selection al tion final et la rédaction du r nd consolidate feedback apport d'achèvement du pro jet ZR-CARITAS-362377-CS-CDS Component 3 - Increase the / Recrutement d'un Consulta capacity to implement the IP Individual Consult nt National pour l'appui à l'év TF / A0924 Post Direct - National 10,000.00 0.00 Signed 2023-05-30 2023-05-30 2023-06-09 2023-06-04 2023-06-30 2023-06-25 2023-08-04 2024-01-31 LC development activities a ant Selection aluation finale et à la rédacti nd consolidate feedback on du rapport d'achèvement du projet ZR-CARITAS-253079-CS-CDS / Renouvellement de contrat Component 1 - Reinforce the avec Caritas diocésaine d'IN participation of the IPLC in fo TF / A0924 Post Direct Selection Direct 18,000.00 0.00 Canceled 2021-12-08 2020-09-08 2021-12-18 2022-02-21 2022-06-21 ONGO, territoire de KIRI, OS rest and land management WE et INONGO pour l'éducat processes related to REDD+ ion de base et l'alphabétisati on. composante 1b ZR-CARITAS-253068-CS-CDS / Renouvellement contrat av Component 1 - Reinforce the ec Caritas diocésaine TSHUM participation of the IPLC in fo TF / A0924 Post Direct Selection Direct 6,000.00 0.00 Canceled 2021-12-08 2021-12-08 2021-12-18 2022-01-20 2022-05-20 BE pour Education de Base et rest and land management Alphabétisation aux PA et co processes related to REDD+ mmunautés locales territoire de LUBEFU composante 1b ZR-CARITAS-365668-CS-CDS / CIDB: Identification des idée Component 2 - Support com s des microprojets communa TF / A0924 munity-based sustainable fo Post Direct Selection Direct - National 9,800.00 0.00 Signed 2023-06-06 2023-06-12 2023-06-16 2023-06-18 2023-08-20 2024-02-16 utaires et des opérateurs loc rest and land management aux d'appui aux communaut és à Bikoro-Kiri ZR-CARITAS-365674-NC-DIR / OSAPY: Appuyer l'élaboratio n des cartes des terroirs com Component 1 - Reinforce the munautaires et des plans d'a participation of the IPLC in fo Under Implement TF / A0924 Post Direct Selection Direct - National 150,000.00 0.00 2023-06-12 2023-06-25 2023-06-22 2023-06-29 2023-08-26 2024-02-22 ménagement et de gestion si rest and land management ation mplifiée des concessions fore processes related to REDD+ stières des COLO et des aires de patrimoine ou aires de co nservation des PA et des COL O Page 8 PROCUREMENT PLAN (Textual Part) Project information: Sindh Flood Emergency Rehabilitation Project (P179981) Project Implementation agency(ies): (i) Sindh Planning & Development Department (ii) Sindh Irrigation Department Date of the Procurement Plan: December 2022 Period covered by this Procurement Plan: June 30 2024 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” November 2020 (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in public procurement rules such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions: 1) The eligibility of bidders shall be as defined under Section III of the Procurement Regulations. Accordingly, no bidder or potential bidder shall be declared ineligible for contracts financed by the Bank for reasons other than those provided in Section III of the Procurement Regulations. 2) For national open competitive procurement, only the model procurement documents acceptable to the World Bank, shall be used. 3) The request for bids/request for proposals document shall require that Bidders/Proposers submitting Bids/Proposals present a signed acceptance (in the form attached) at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights. 4) Procurement Documents include provisions, as agreed with the Bank, intended to adequately mitigate against environmental, social (including sexual exploitation and abuse and gender-based violence), health and safety (“ESHS”) risks and impacts 5) Access to procurement opportunities shall not be restricted to firms that have pre-registered and/or paid a registration fee. 6) No preference of any kind shall be given to national bidders in the bidding process. 7) Procurement methods that use two-envelope process and rated criteria shall be subject to Bank’s prior concurrence When other national procurement arrangements (other than national open competitive procurement) are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is not allowed Letter of Acceptance of the World Bank’s Anticorruption Guidelines and Sanctions Framework1 Date: Invitation of Bids/Proposals No.__________ To: ___________________________________________________________________________ We, along with our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not) consultants and personnel, acknowledge and agree to abide by the World Bank’s policy regarding Fraud and Corruption (corrupt, fraudulent, collusive, coercive, and obstructive practices), as set out and defined in the World Bank’s Anti-Corruption Guidelines2 in connection with the procurement and execution of the contract (in case of award), including any amendments thereto. We declare and warrant that we, along our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not), consultants and personnel, are not subject to, and are not controlled by any entity or individual that is subject to, a temporary suspension, early temporary suspension, or debarment imposed by a member of the World Bank Group, including, inter alia, a cross-debarment imposed by the World Bank Group as agreed with other international financial institutions (including multilateral development banks), or through the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement. Further, we are not ineligible under the laws or official regulations of [Insert name of Employer as per bidding document] or pursuant to a decision of the United Nations Security Council. We confirm our understanding of the consequences of not complying with the World Bank’s Anti-Corruption Guidelines, which may include the following: a. rejection of our Proposal/Bid for award of contract; 1[Drafting note: This document shall be signed by bidders/proposers/consultants and submitted as part of their bids/proposals. In addition, this document shall be signed by the winning bidder/consultant and incorporated as part of the contract.] 2Guidelines on Preventing and Combating Fraud and Corruption in Projects Financed by International Bank for Reconstruction and Development Loans and the International Development Agency Credits and Grants, dated October 15, 2006, and revised in January 2011 and July 2016, as they may be revised from time to time. b. in the case of award, termination of the contract, without prejudice to any other remedy for breach of contract; and c. sanctions, pursuant to the Bank’s Anti-Corruption Guidelines and in accordance with its prevailing sanctions policies and procedures as set forth in the Bank’s Sanctions Framework. This may include a public declaration of ineligibility, either indefinitely or for a stated period of time, (i) to be awarded or otherwise benefit from a Bank-financed contract, financially or in any other manner;3 (ii) to be a nominated4 sub-contractor, sub-consultant, consultant, manufacturer or supplier, or service provider of an otherwise eligible firm being awarded a Bank-financed contract; and (iii) to receive the proceeds of any loan made by the Bank or otherwise to participate further in the preparation or implementation of any Bank- financed project. We understand that we may be declared ineligible as set out above upon: a. completion of World Bank Group sanctions proceedings according to its prevailing sanctions procedures; b. cross-debarment as agreed with other international financial institutions (including multilateral development banks); c. the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement; or d. temporary suspension or early temporary suspension in connection with an ongoing World Bank Group sanctions proceeding. For avoidance of doubt, the foregoing effects of ineligibility do not extend to a sanctioned firm’s or individual’s execution of its ongoing Bank-financed contracts (or its ongoing sub-agreements under such contracts) that are not the subject of a material modification, as determined by the Bank. We shall permit, and shall cause our sub-contractors, sub-consultants, agents (whether declared or not), personnel, consultants, service providers or suppliers, to permit the Bank to inspect5 all accounts, records, and other documents relating to 3 For the avoidance of doubt, a sanctioned party’s ineligibility to be awarded a contract shall include, without limitation, (i) applying for pre-qualification or initial selection), expressing interest in a consultancy, and bidding, either directly or as a nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider, in respect of such contract, and (ii) entering into an addendum or amendment introducing a material modification to any existing contract. 4A nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider (different names are used depending on the bidding document) is one which has been: (i) included by the bidder in its pre-qualification or initial selection application or bid because it brings specific and critical experience and know-how that allow the bidder to meet the qualification requirements for the particular bid; or (ii) appointed by the Borrower. 5Inspections in this context are usually investigative (i.e., forensic) in nature: they involve fact- finding activities undertaken by the Bank or persons appointed by the Bank to address specific the procurement process and/or contract execution (in the case of award), and to have them audited by auditors appointed by the Bank. We agree to preserve all accounts, records, and other documents (whether in hard copy or electronic format) related to the procurement and execution of the contract. Name of the Bidder/Proposer/Consultant: Name of the person duly authorized to sign the Bid/Proposal on behalf of the Bidder/Proposer/ Consultant: Title of the person signing the Letter: matters related to investigations/audits, such as evaluating the veracity of an allegation of possible Fraud and Corruption, through the appropriate mechanisms. Such activity includes but is not limited to accessing and examining a firm's or individual's financial records and information, and making copies thereof as relevant; accessing and examining any other documents, data, and information (whether in hard copy or electronic format) deemed relevant for the investigation/audit, and making copies thereof as relevant; interviewing staff and other relevant individuals; performing physical inspections and site visits; and obtaining third-party verification of information. PROCUREMENT Pakistan : Sindh Flood Emergency Rehabilitation Project PLAN General Information Country: Pakistan 2023-01-17 Bank’s Approval Date of the Original Procurement Plan: 2023-06-01 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P179981 GPN Date: 2023-01-19 Project Name: Sindh Flood Emergency Rehabilitation Project Loan / Credit No: IDA / 72500 Province of Sindh Irrigation Department Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned PK-POSID-336211-CW-RFB / Rehabilitation/ Construction Single Stage - One E Other (with field f Under Imple 2024-03-1 IDA / 72500 Infrastructure Rehabilitation Post Request for Bids Open - National 5,681,818.00 0.00 2023-01-13 2022-12-19 2023-01-13 2023-01-24 2023-02-23 2023-03-13 of Additional Outfall Regulato nvelope or explanation) mentation 1 r Along Ochitto Outfall Drain and Leading Channel. PK-POSID-336212-CW-RFB / Single Stage - One E Other (with field f Pending Imp 2024-03-1 Rehabilitation of Main East Br IDA / 72500 Infrastructure Rehabilitation Post Request for Bids Open - National 1,006,738.00 0.00 2023-01-13 2023-01-13 2023-01-24 2023-02-23 2023-03-13 nvelope or explanation) lementation 1 anch Nawabshah. PK-POSID-336213-CW-RFB / Single Stage - One E Other (with field f Under Imple 2024-03-1 Rehabilitation of Shikarpur Br IDA / 72500 Infrastructure Rehabilitation Post Request for Bids Open - National 258,748.00 0.00 2023-01-13 2022-12-19 2023-01-13 2023-01-24 2023-02-23 2023-03-13 nvelope or explanation) mentation 1 . Drain system. PK-POSID-336214-CW-RFB / Rehabilitation of Pharho Esca Single Stage - One E Other (with field f Under Imple 2024-03-1 pe from RD 0+000 to 30+00 IDA / 72500 Infrastructure Rehabilitation Post Request for Bids Open - National 139,273.00 0.00 2023-01-13 2022-12-19 2023-01-13 2023-01-24 2023-02-23 2023-03-13 nvelope or explanation) mentation 1 0 Both Sides in KhairpurGam bo Sub Division of Nasir Divis ion. PK-POSID-336215-CW-RFB / Raising and Rehabilitation (E arthwork) along Oderolal Esc Single Stage - One E Other (with field f Under Imple 2024-03-1 ape from RD 0+000 to 71+0 IDA / 72500 Infrastructure Rehabilitation Post Request for Bids Open - National 2,250,000.00 0.00 2023-01-13 2022-12-19 2023-01-13 2023-01-24 2023-02-23 2023-03-13 nvelope or explanation) mentation 1 00 NIP Side i/c installation of new gates to increase capaci ty of water to enable escape discharge in Indus River. PK-POSID-336216-CW-RFB / Single Stage - One E Other (with field f 2024-03-1 IDA / 72500 Infrastructure Rehabilitation Post Request for Bids Open - National 652,658.00 0.00 Canceled 2023-01-13 2023-01-13 2023-01-24 2023-02-23 2023-03-13 Rehabilitation of Karampur Ri nvelope or explanation) 1 ng Bund. PK-POSID-336217-CW-RFB / Single Stage - One E Other (with field f Under Imple 2024-03-1 IDA / 72500 Infrastructure Rehabilitation Post Request for Bids Open - National 1,590,120.00 0.00 2023-01-13 2022-12-19 2023-01-13 2023-01-24 2023-02-23 2023-03-13 Rehabilitation of Suprio Bund nvelope or explanation) mentation 1 . PK-POSID-336218-CW-RFB / Package No. 1 Lot No. 1 Floo d Detention Dam Lat-01 (DD/ Single Stage - One E Other (with field f 2024-03-1 W-L01 along LatNai). IDA / 72500 Infrastructure Rehabilitation Post Request for Bids Open - National 7,586,543.00 0.00 Signed 2023-01-13 2022-12-26 2023-01-13 2023-01-25 2023-01-31 2023-01-31 2023-03-02 2023-02-20 2023-03-20 nvelope or explanation) 8 Lot No.2 Floo d Detention Dam Lat-02 (DD/ W-L02 along LatNai). PK-POSID-336219-CW-RFB / Package No. 2 Lot No. 1 Floo d Detention Dam Lat-03 (DD/ Single Stage - One E Other (with field f 2024-03-1 W-L03 along LatNai). IDA / 72500 Infrastructure Rehabilitation Post Request for Bids Open - National 7,919,065.00 0.00 Signed 2023-01-13 2022-12-26 2023-01-13 2023-01-25 2023-01-31 2023-01-31 2023-03-02 2023-02-20 2023-03-20 nvelope or explanation) 8 Lot No. 2 Flo od Detention Dam Lat-04 (D D/W-L04 along LatNai). PK-POSID-336220-CW-RFB / Single Stage - One E Other (with field f 2024-03-1 Package No.3 Flood Detentio IDA / 72500 Infrastructure Rehabilitation Post Request for Bids Open - National 4,597,684.00 0.00 Signed 2023-01-13 2022-12-26 2023-01-13 2023-01-25 2023-01-31 2023-01-31 2023-03-02 2023-02-20 2023-03-20 nvelope or explanation) 8 n Dam Mole-02 (DD/W-M2 al ong Mole Nai). PK-POSID-336221-CW-RFB / Package No. 4 Lot No. 1 Floo d Detention Dam Mole-03 (D Single Stage - One E Other (with field f 2024-03-1 D/W-M3 along Mole Nai). IDA / 72500 Infrastructure Rehabilitation Post Request for Bids Open - National 7,993,696.00 0.00 Signed 2023-01-13 2022-12-26 2023-01-13 2023-01-25 2023-01-31 2023-01-31 2023-03-02 2023-03-07 2023-03-20 nvelope or explanation) 8 Lot No. 2 Floo d Detention Dam Mole-04 (D D/W-M4 along Mole Nai). PK-POSID-336223-CW-RFB / Package No. 5 Lot No. 1 Floo d Detention Dam Mole-05 (D Single Stage - One E Other (with field f 2024-03-1 D/W-M5 along Mole Nai). IDA / 72500 Infrastructure Rehabilitation Post Request for Bids Open - National 8,779,468.00 0.00 Signed 2023-01-14 2022-12-26 2023-01-14 2023-01-25 2023-01-31 2023-01-31 2023-03-02 2023-02-20 2023-03-20 nvelope or explanation) 8 Lot No. 2 Floo d Detention Dam Mole-06 (D D/W-M6 along Mole Nai). PK-POSID-336225-CW-RFB / Package No. 6 Lot No.1 Floo d Detention Dam Mole-07 (D Single Stage - One E Other (with field f 2024-03-1 D/W-M7 along Mole Nai). IDA / 72500 Infrastructure Rehabilitation Post Request for Bids Open - National 7,608,233.00 0.00 Signed 2023-01-14 2022-12-26 2023-01-14 2023-01-25 2023-01-31 2023-01-31 2023-03-02 2023-03-07 2023-03-20 nvelope or explanation) 8 Lot No. 2 Flo od Detention Dam Mole -08 ( DD/W-M8 along Mole Nai). PK-POSID-336067-CW-DIR / Other (with field f 2023-04-2 Rehabilitation OF Manchar C IDA / 72500 Infrastructure Rehabilitation Post Direct Selection Direct - National 4,251,592.00 0.00 Signed 2023-01-13 2022-10-21 2023-01-13 2022-10-24 2023-01-21 or explanation) 1 ONTAINING BUND (RD 0+000 TO 27+000 ). PK-POSID-336093-CW-DIR / Other (with field f 2023-04-2 REHABILITATION OF DANISTA IDA / 72500 Infrastructure Rehabilitation Post Direct Selection Direct - National 3,682,097.00 0.00 Signed 2023-01-13 2022-11-14 2023-01-13 2022-11-15 2023-01-21 or explanation) 1 R CANAL (RD 0+000 TO 27+ 440). PK-POSID-336083-CW-DIR / Other (with field f 2023-04-2 REHABILITATION OF DHORO IDA / 72500 Infrastructure Rehabilitation Post Direct Selection Direct - National 2,427,760.00 0.00 Signed 2023-01-13 2022-10-21 2023-01-13 2022-10-24 2023-01-21 or explanation) 1 PURAN RD 176+400 to 210+ 000. PK-POSID-336069-CW-DIR / REHABILITATION OF MANCHA Other (with field f 2023-04-2 IDA / 72500 Infrastructure Rehabilitation Post Direct Selection Direct - National 4,483,243.00 0.00 Signed 2023-01-13 2022-10-21 2023-01-13 2022-10-24 2023-01-21 R CONTAINING BUND (RD 54 or explanation) 1 +000 TO 77+000 ). Page 1 PK-POSID-336074-CW-DIR / Other (with field f 2023-04-2 Rehabilitation of FP Bund (RD IDA / 72500 Infrastructure Rehabilitation Post Direct Selection Direct - National 4,543,288.00 0.00 Signed 2023-01-13 2022-10-28 2023-01-13 2022-10-31 2023-01-21 or explanation) 1 380+000 to RD 445+000). PK-POSID-336077-CW-DIR / Rehabilitation of FP Bund (RD Other (with field f 2023-04-2 IDA / 72500 Infrastructure Rehabilitation Post Direct Selection Direct - National 4,748,317.00 0.00 Signed 2023-01-13 2022-10-28 2023-01-13 2022-10-31 2023-01-21 490+000 to RD 502+000 & R or explanation) 1 D 263+000 to RD 220+000). PK-POSID-336079-CW-DIR / Other (with field f 2023-04-2 Rehabilitation of FP Bund (RD IDA / 72500 Infrastructure Rehabilitation Post Direct Selection Direct - National 4,492,892.00 0.00 Signed 2023-01-13 2022-10-28 2023-01-13 2022-10-31 2023-01-21 or explanation) 1 220+000 to RD 169+000). PK-POSID-336085-CW-DIR / REHABILITATION OF DHORO Other (with field f 2023-04-2 IDA / 72500 Infrastructure Rehabilitation Post Direct Selection Direct - National 4,318,122.00 0.00 Signed 2023-01-13 2022-10-21 2023-01-13 2022-10-24 2023-01-21 PURAN RD 210+000 TO 222 or explanation) 1 +130 AND MAIN DRAIN RD 2 12+300 TO 217+600. PK-POSID-336075-CW-DIR / Other (with field f 2023-04-2 Rehabilitation of FP Bund (RD IDA / 72500 Infrastructure Rehabilitation Post Direct Selection Direct - National 4,604,680.00 0.00 Signed 2023-01-13 2022-10-21 2023-01-13 2022-10-24 2023-01-21 or explanation) 1 445+000 to RD 490+000). PK-POSID-335890-CW-DIR / Other (with field f 2023-02-1 Plugging and Strengthening IDA / 72500 Infrastructure Rehabilitation Post Direct Selection Direct - National 635,481.00 0.00 Signed 2023-01-12 2022-09-26 2023-01-12 2022-09-28 2023-01-20 or explanation) 9 of Breach along Saifullah Ma gsi Branch. PK-POSID-335912-CW-DIR / Other (with field f 2023-02-1 Plugging, Strengthening Rest IDA / 72500 Infrastructure Rehabilitation Post Direct Selection Direct - National 930,558.00 0.00 Signed 2023-01-12 2022-10-05 2023-01-12 2022-10-07 2023-01-20 or explanation) 9 oration and Rehabilitation of Dhamrah Wah. PK-POSID-335914-CW-DIR / Replacement / Supply and In stallation of Motor Pump (10 Other (with field f 2023-04-2 IDA / 72500 Infrastructure Rehabilitation Post Direct Selection Direct - National 1,074,545.00 0.00 Signed 2023-01-12 2022-10-05 2023-01-12 2022-10-07 2023-01-20 0 H.P) Including All Accessori or explanation) 0 es Along Ghaar, Shahmeer, Mehar, Mashori, K.N.Shah, Mi ro Khan and Agani Pumping Stations. PK-POSID-335916-CW-DIR / Plugging and Strengthening Other (with field f 2023-02-1 IDA / 72500 Infrastructure Rehabilitation Post Direct Selection Direct - National 977,477.00 0.00 Signed 2023-01-12 2022-10-14 2023-01-12 2022-10-17 2023-01-20 of Breach along Main Nara V or explanation) 9 alley (MNV) Drain at RD 280. PK-POSID-335928-CW-DIR / Other (with field f Under Imple 2023-02-1 Closing of cuts alog Rohri Mai IDA / 72500 Infrastructure Rehabilitation Post Direct Selection Direct - National 469,559.00 0.00 2023-01-12 2022-10-14 2023-01-12 2022-10-17 2023-01-20 or explanation) mentation 9 n Canal, Moro Division. PK-POSID-335933-CW-DIR / Plugging And Strengthening Other (with field f 2023-02-1 IDA / 72500 Infrastructure Rehabilitation Post Direct Selection Direct - National 1,022,523.00 0.00 Signed 2023-01-12 2022-10-28 2023-01-12 2022-10-31 2023-01-20 Of Relief Cut Along Johi Branc or explanation) 9 h Along Rd 80 To Rd 86 And Rd 95 To Rd 98. PK-POSID-335862-CW-DIR / Other (with field f 2023-02-1 Plugging and Strengthening IDA / 72500 Infrastructure Rehabilitation Post Direct Selection Direct - National 226,695.00 0.00 Signed 2023-01-12 2022-09-26 2023-01-12 2022-09-28 2023-01-20 or explanation) 9 of Breach along FP Bund alon g 169+000. PK-POSID-335917-CW-DIR / Plugging and Strengthening Other (with field f 2023-02-1 IDA / 72500 Infrastructure Rehabilitation Post Direct Selection Direct - National 309,602.00 0.00 Signed 2023-01-12 2022-10-14 2023-01-12 2022-10-17 2023-01-20 of Breach along Main Nara V or explanation) 9 alley (MNV) Drain at RD 330. PK-POSID-335893-CW-DIR / Plugging and Strengthening Other (with field f 2023-02-1 IDA / 72500 Infrastructure Rehabilitation Post Direct Selection Direct - National 407,933.00 0.00 Signed 2023-01-12 2022-10-05 2023-01-12 2022-10-07 2023-01-20 of Breaches / Cuts Along Gha or explanation) 9 r Main Drain & Leading Chan nel. PK-POSID-335905-CW-DIR / Other (with field f 2023-02-1 Plugging and Strengthening IDA / 72500 Infrastructure Rehabilitation Post Direct Selection Direct - National 782,058.00 0.00 Signed 2023-01-12 2022-10-05 2023-01-12 2022-10-07 2023-01-20 or explanation) 9 of Breaches / Cuts Along Miro Khan Main Drain. PK-POSID-335919-CW-DIR / Plugging, Strengthening and Other (with field f 2023-02-1 IDA / 72500 Infrastructure Rehabilitation Post Direct Selection Direct - National 346,364.00 0.00 Signed 2023-01-12 2022-10-14 2023-01-12 2022-10-17 2023-01-20 Stone Pitching of Breach alon or explanation) 9 g Superio Bund RD 12. PK-POSID-335920-CW-DIR / Plugging, Strengthening and Other (with field f 2023-02-1 IDA / 72500 Infrastructure Rehabilitation Post Direct Selection Direct - National 249,294.00 0.00 Signed 2023-01-12 2022-10-14 2023-01-12 2022-10-17 2023-01-20 Stone Pitching of Breach alon or explanation) 9 g Superio Bund RD 28. PK-POSID-336089-CW-DIR / REMODELING AND REHABILIT Other (with field f 2023-04-2 IDA / 72500 Infrastructure Rehabilitation Post Direct Selection Direct - National 6,486,130.00 0.00 Signed 2023-01-13 2022-10-28 2023-01-13 2022-10-31 2023-01-21 ATION OF ARAL HEAD REGUL or explanation) 1 ATOR (MC RD 0+000). PK-POSID-336087-CW-DIR / REHABILITATION OF OUTFALL Other (with field f 2023-04-2 IDA / 72500 Infrastructure Rehabilitation Post Direct Selection Direct - National 2,482,485.00 0.00 Signed 2023-01-13 2022-10-21 2023-01-13 2022-10-24 2023-01-21 STRUCTURE AT RD 210+000 or explanation) 1 OF DHORO PURAN. PK-POSID-336070-CW-DIR / REHABILITATION OF MANCHA Other (with field f 2023-04-2 IDA / 72500 Infrastructure Rehabilitation Post Direct Selection Direct - National 4,542,517.00 0.00 Signed 2023-01-13 2022-10-21 2023-01-13 2022-10-24 2023-01-21 R CONTAINING BUND (RD 77 or explanation) 1 +000 TO 100+000). PK-POSID-336071-CW-DIR / Other (with field f 2023-04-2 Rehabilitation of FP Bund (RD IDA / 72500 Infrastructure Rehabilitation Post Direct Selection Direct - National 4,475,187.00 0.00 Signed 2023-01-13 2022-10-21 2023-01-13 2022-10-24 2023-01-21 or explanation) 1 160+000 to RD 210+000). PK-POSID-335923-CW-DIR / Plugging, Strengthening and Other (with field f 2023-02-1 IDA / 72500 Infrastructure Rehabilitation Post Direct Selection Direct - National 60,393.00 0.00 Signed 2023-01-12 2022-10-14 2023-01-12 2022-10-17 2023-01-20 Stone Pitching of Breach alon or explanation) 9 g Superio Bund RD 42. PK-POSID-336091-CW-DIR / Other (with field f 2023-04-2 REHABILITATION OF LEFT AR IDA / 72500 Infrastructure Rehabilitation Post Direct Selection Direct - National 3,156,718.00 0.00 Signed 2023-01-13 2022-10-28 2023-01-13 2022-10-31 2023-01-21 or explanation) 1 AL BUND RD 0+000 TO RD 1 9+000. PK-POSID-335931-CW-DIR / Other (with field f 2023-02-1 Repair of Rain Damages of S IDA / 72500 Infrastructure Rehabilitation Post Direct Selection Direct - National 1,397,355.00 0.00 Signed 2023-01-12 2022-10-14 2023-01-12 2022-10-17 2023-01-20 or explanation) 9 mall Dams Under Small Dam s Organization. Page 2 PK-POSID-335855-CW-DIR / Plugging, Strengthening & St Other (with field f 2023-02-1 IDA / 72500 Infrastructure Rehabilitation Post Direct Selection Direct - National 219,056.00 0.00 Signed 2023-01-12 2022-09-26 2023-01-12 2022-09-28 2023-01-20 one Pitching of Relief Cut Lar or explanation) 9 kana Sehwan Bund along Mil e 95/6. PK-POSID-336080-CW-DIR / Other (with field f 2023-04-2 REHABILITATION OF DHORO IDA / 72500 Infrastructure Rehabilitation Post Direct Selection Direct - National 3,250,317.00 0.00 Signed 2023-01-13 2022-10-21 2023-01-13 2022-10-24 2023-01-21 or explanation) 1 PURAN RD 110+000 TO 143 +330. PK-POSID-335851-CW-DIR / Plugging and Strengthening Other (with field f 2023-02-1 IDA / 72500 Infrastructure Rehabilitation Post Direct Selection Direct - National 1,249,943.00 0.00 Signed 2023-01-12 2022-09-26 2023-01-12 2022-09-28 2023-01-20 of Relief Cut along Manchar or explanation) 9 Containing Bund at RD 52+0 00. PK-POSID-335854-CW-DIR / Plugging and Strengthening Other (with field f 2023-02-1 IDA / 72500 Infrastructure Rehabilitation Post Direct Selection Direct - National 1,133,842.00 0.00 Signed 2023-01-12 2022-09-26 2023-01-12 2022-09-28 2023-01-20 of Breach along Main Nara V or explanation) 9 aley (MNV) Drain at RD 8+06 8. PK-POSID-335887-CW-DIR / Other (with field f 2023-02-1 Plugging and Strengthening IDA / 72500 Infrastructure Rehabilitation Post Direct Selection Direct - National 180,708.00 0.00 Signed 2023-01-12 2022-09-26 2023-01-12 2022-09-28 2023-01-20 or explanation) 9 of Breach along FP Bund alon g RD 476+000. PK-POSID-336081-CW-DIR / Other (with field f 2023-04-2 REHABILITATION OF DHORO IDA / 72500 Infrastructure Rehabilitation Post Direct Selection Direct - National 3,491,000.00 0.00 Signed 2023-01-13 2022-10-21 2023-01-13 2022-10-24 2023-01-21 or explanation) 1 PURAN RD 143+330 TO 176 +400. PK-POSID-335925-CW-DIR / Plugging, Strengthening and Other (with field f 2023-02-1 IDA / 72500 Infrastructure Rehabilitation Post Direct Selection Direct - National 189,836.00 0.00 Signed 2023-01-12 2022-10-14 2023-01-12 2022-10-17 2023-01-20 Stone Pitching of Breach alon or explanation) 9 g Superio Bund RD 52. PK-POSID-335929-CW-DIR / Other (with field f 2023-02-1 Repair of Rain Damages Sma IDA / 72500 Infrastructure Rehabilitation Post Direct Selection Direct - National 1,912,465.00 0.00 Signed 2023-01-12 2022-10-14 2023-01-12 2022-10-17 2023-01-20 or explanation) 9 ll Dams Under Sindh Resilien ce Project (SRP). PK-POSID-335898-CW-DIR / Plugging and Strengthening Other (with field f 2023-02-1 IDA / 72500 Infrastructure Rehabilitation Post Direct Selection Direct - National 493,189.00 0.00 Signed 2023-01-12 2022-10-05 2023-01-12 2022-10-07 2023-01-20 of Breaches Along K.N Shah or explanation) 9 Main Drain & Leading Chann el. PK-POSID-335927-CW-DIR / Plugging, Strengthening and Other (with field f 2023-02-1 IDA / 72500 Infrastructure Rehabilitation Post Direct Selection Direct - National 44,676.00 0.00 Signed 2023-01-12 2022-10-14 2023-01-12 2022-10-17 2023-01-20 Stone Pitching of Breach alon or explanation) 9 g Superio Bund RD 82. PK-POSID-335858-CW-DIR / Plugging, Strengthening & St Other (with field f 2023-02-1 IDA / 72500 Infrastructure Rehabilitation Post Direct Selection Direct - National 906,846.00 0.00 Signed 2023-01-12 2022-10-05 2023-01-12 2022-10-07 2023-01-20 one Pitching of Relief Cut Lar or explanation) 9 kana Sehwan Bund along Mil e 97/2. PK-POSID-335873-CW-DIR / Other (with field f 2023-02-1 Plugging and Strengthening IDA / 72500 Infrastructure Rehabilitation Post Direct Selection Direct - National 1,452,498.00 0.00 Signed 2023-01-12 2022-09-26 2023-01-12 2022-09-28 2023-01-20 or explanation) 9 of Breach along FP Bund alon g RD 340+000. PK-POSID-335915-CW-DIR / Plugging and Strengthening Other (with field f 2023-02-1 IDA / 72500 Infrastructure Rehabilitation Post Direct Selection Direct - National 802,253.00 0.00 Signed 2023-01-12 2022-10-14 2023-01-12 2022-10-17 2023-01-20 of Breach along Main Nara V or explanation) 9 alley (MNV) Drain at RD 210. PK-POSID-335821-CW-DIR / Plugging and Strengthening Other (with field f 2023-02-1 IDA / 72500 Infrastructure Rehabilitation Post Direct Selection Direct - National 1,135,696.00 0.00 Signed 2023-01-12 2022-09-26 2023-01-12 2022-09-28 2023-01-20 of Relief Cut along Manchar or explanation) 9 Containing Bund at RD 14+0 00. PK-POSID-335903-CW-DIR / Plugging and Strengthening Other (with field f 2023-02-1 IDA / 72500 Infrastructure Rehabilitation Post Direct Selection Direct - National 385,539.00 0.00 Signed 2023-01-12 2022-10-05 2023-01-12 2022-10-07 2023-01-20 of Breaches / Cuts Along Sha or explanation) 9 hdad Kot Branch Drain. PK-POSID-336068-CW-DIR / REHABILITATION OF MANCHA Other (with field f 2023-04-2 IDA / 72500 Infrastructure Rehabilitation Post Direct Selection Direct - National 4,538,878.00 0.00 Signed 2023-01-13 2022-10-21 2023-01-13 2022-10-24 2023-01-21 R CONTAINING BUND (RD 27 or explanation) 1 +000 TO 54+000 ). PK-POSID-336072-CW-DIR / Other (with field f 2023-04-2 Rehabilitation of FP Bund (RD IDA / 72500 Infrastructure Rehabilitation Post Direct Selection Direct - National 4,524,135.00 0.00 Signed 2023-01-13 2022-10-28 2023-01-13 2022-10-31 2023-01-21 or explanation) 1 325+000 to RD 380+000). PK-POSID-336094-CW-DIR / Other (with field f 2023-04-2 REHABILITATION OF DANISTA IDA / 72500 Infrastructure Rehabilitation Post Direct Selection Direct - National 3,633,010.00 0.00 Signed 2023-01-13 2022-11-14 2023-01-13 2022-11-15 2023-01-21 or explanation) 1 R CANAL (RD 27+440 TO 56 +434). PK-POSID-335860-CW-DIR / Plugging, Strengthening & St Other (with field f 2023-02-1 IDA / 72500 Infrastructure Rehabilitation Post Direct Selection Direct - National 2,231,284.00 0.00 Signed 2023-01-12 2022-09-26 2023-01-12 2022-09-28 2023-01-20 one Pitching of Relief Cut Lar or explanation) 9 kana Sehwan Bund along Mil e 99/3. PK-POSID-335909-CW-DIR / Other (with field f 2023-02-1 Plugging and Strengthening IDA / 72500 Infrastructure Rehabilitation Post Direct Selection Direct - National 2,075,286.00 0.00 Signed 2023-01-12 2022-10-05 2023-01-12 2022-10-07 2023-01-20 or explanation) 9 of Breach Along F.P Bund Rd 432. PK-POSID-335932-CW-DIR / Repair of Gaj Diversion Bund Other (with field f 2023-02-1 ledge and stone apron from IDA / 72500 Infrastructure Rehabilitation Post Direct Selection Direct - National 1,342,347.00 0.00 Signed 2023-01-12 2022-10-14 2023-01-12 2022-10-17 2023-01-20 or explanation) 9 RD 3-11, Repair of Gaj Divers ion Bund stone apron from R D 15-32.5. PK-POSID-335867-CW-DIR / Other (with field f 2023-02-1 Plugging and Strengthening IDA / 72500 Infrastructure Rehabilitation Post Direct Selection Direct - National 552,124.00 0.00 Signed 2023-01-12 2022-09-26 2023-01-12 2022-09-28 2023-01-20 or explanation) 9 of Breach along FP Bund alon g RD 215+000. PK-POSID-335853-CW-DIR / Plugging and Strengthening Other (with field f 2023-02-1 IDA / 72500 Infrastructure Rehabilitation Post Direct Selection Direct - National 1,361,326.00 0.00 Signed 2023-01-12 2022-09-26 2023-01-12 2022-09-28 2023-01-20 of Breach along Main Nara V or explanation) 9 aley (MNV) Drain at RD 2+31 8. PK-POSID-335908-CW-DIR / Other (with field f 2023-02-1 Plugging and Strengthening IDA / 72500 Infrastructure Rehabilitation Post Direct Selection Direct - National 1,747,581.00 0.00 Signed 2023-01-12 2022-10-05 2023-01-12 2022-10-07 2023-01-20 or explanation) 9 of Breaches Along Indus Link Drain. Page 3 PK-POSID-336092-CW-DIR / REMODELING AND REHABILIT Other (with field f 2023-04-2 IDA / 72500 Infrastructure Rehabilitation Post Direct Selection Direct - National 3,469,384.00 0.00 Signed 2023-01-13 2022-11-14 2023-01-13 2022-11-15 2023-01-21 ATION OF ARAL WAH (RD 1+ or explanation) 1 250 TO RD 0+000 & RD 0+0 00 TO 14+000). PK-POSID-336095-CW-DIR / Remodeling and Rehabilitatio Other (with field f 2023-04-2 n of Danister Tail Regulator a IDA / 72500 Infrastructure Rehabilitation Post Direct Selection Direct - National 2,745,403.00 0.00 Signed 2023-01-13 2022-11-14 2023-01-13 2022-11-15 2023-01-21 or explanation) 1 nd Regulator for 10 Phats (Mi nors) Danister Canal (Civil W orks). PK-POSID-343948-CW-DIR / Other (with field f 2023-05-2 Rehabilitation Of Old Water IDA / 72500 Infrastructure Rehabilitation Post Direct Selection Direct - National 173,193.00 0.00 Signed 2023-02-20 2022-12-07 2023-02-20 2022-12-09 2023-02-28 or explanation) 9 Way In Desert Area Of Khairp ur. Request for Quota PK-POSID-341482-CW-RFQ / Request for Quota Single Stage - One E tions - Small Work Under Imple 2023-12-1 Rehabilitation of Talpur Wad IDA / 72500 Infrastructure Rehabilitation Post Limited 530,161.00 0.00 2023-02-24 2023-03-17 tions nvelope s (Emergency) SP mentation 2 a Pumping Station And Water D -Competitive Carrier Drain. PK-POSID-341480-CW-RFQ / Request for Quota Rehabilitation of Syphon at A Request for Quota Single Stage - One E tions - Small Work Under Imple 2023-12-1 IDA / 72500 Infrastructure Rehabilitation Post Limited 294,021.00 0.00 2023-02-24 2023-03-17 li Bahar Branch And Rehabilit tions nvelope s (Emergency) SP mentation 2 ation of Syphon at Kubri Mino D -Competitive r. Request for Quota PK-POSID-341483-CW-RFQ / Request for Quota Single Stage - One E tions - Small Work Under Imple 2023-12-1 Rehabilitation of G & F Pumpi IDA / 72500 Infrastructure Rehabilitation Post Limited 752,713.00 0.00 2023-02-24 2023-03-17 tions nvelope s (Emergency) SP mentation 2 ng Station. D -Competitive Request for Quota PK-POSID-341485-CW-RFQ / Request for Quota Single Stage - One E tions - Small Work Under Imple 2023-12-1 Rehabilitation of Karampur Ri IDA / 72500 Infrastructure Rehabilitation Post Limited 527,885.00 0.00 2023-02-24 2023-03-17 tions nvelope s (Emergency) SP mentation 2 ng Bund. D -Competitive PK-POSID-335901-CW-DIR / Other (with field f 2023-02-1 IDA / 72500 Infrastructure Rehabilitation Post Direct Selection Direct - National 337,811.00 0.00 Signed 2023-01-12 2022-10-05 2023-01-12 2022-10-07 2023-01-20 Rehabilitation Of Mehar Main or explanation) 9 Drain. PK-POSID-348241-CW-DIR / Rehabilitation of F.P Bund (R Other (with field f 2023-12-1 IDA / 72500 Infrastructure Rehabilitation Post Direct Selection Direct - National 4,507,304.00 0.00 Signed 2023-03-09 2022-12-07 2023-03-09 2022-12-09 2023-03-17 D 0+000 to RD 20+000 & RD or explanation) 2 75+000 to RD 160+000). PK-POSID-348243-CW-DIR / Other (with field f 2023-12-1 Rehabilitation of F.P Bund (R IDA / 72500 Infrastructure Rehabilitation Post Direct Selection Direct - National 4,533,536.00 0.00 Signed 2023-03-09 2022-12-07 2023-03-09 2022-12-09 2023-03-17 or explanation) 2 D 210+000 to RD 265+000). PK-POSID-348244-CW-DIR / Other (with field f 2023-12-1 Rehabilitation of F.P Bund (R IDA / 72500 Infrastructure Rehabilitation Post Direct Selection Direct - National 4,506,334.00 0.00 Signed 2023-03-09 2022-12-07 2023-03-09 2022-12-09 2023-03-17 or explanation) 2 D 265+000 to RD 325+000). PK-POSID-348246-CW-DIR / Rehabilitation of Gates in Ara Other (with field f 2023-12-1 IDA / 72500 Infrastructure Rehabilitation Post Direct Selection Direct - National 3,361,791.00 0.00 Signed 2023-03-09 2022-12-07 2023-03-09 2022-12-09 2023-03-17 l Head Regulator, Dainster Ta or explanation) 2 il Regulator and 10 Phats (Mi nors) Regulators. PK-POSID-348248-CW-DIR / Rehabilitation of Retaining W Other (with field f 2023-12-1 IDA / 72500 Infrastructure Rehabilitation Post Direct Selection Direct - National 4,976,266.00 0.00 Signed 2023-03-09 2022-12-07 2023-03-09 2022-12-09 2023-03-17 all (3 RDs) along Danistar Ca or explanation) 2 nal (Bubak/Miani Town). PK-POSID-348251-CW-DIR / Other (with field f 2023-12-1 Rehabilitation of Irrigation W IDA / 72500 Infrastructure Rehabilitation Post Direct Selection Direct - National 3,348,712.00 0.00 Signed 2023-03-09 2022-12-07 2023-03-09 2022-12-09 2023-03-17 or explanation) 2 orks on Johi Branch. PK-POSID-348254-CW-DIR / Remodeling of Shaheed Bena Other (with field f 2023-12-1 IDA / 72500 Infrastructure Rehabilitation Post Direct Selection Direct - National 5,891,955.00 0.00 Signed 2023-03-09 2022-12-07 2023-03-09 2022-12-09 2023-03-17 zirabad Stormwater Drain (R or explanation) 2 D 0+000 to 16+556). PK-POSID-348257-CW-DIR / Remodeling of Shaheed Bena Other (with field f 2023-12-1 IDA / 72500 Infrastructure Rehabilitation Post Direct Selection Direct - National 5,558,022.00 0.00 Signed 2023-03-09 2022-12-07 2023-03-09 2022-12-09 2023-03-17 zirabad Stormwater Drain (R or explanation) 2 D 13+320+ to RD 26+223). PK-POSID-356470-CW-DIR / Construction of new T-head S pur along Ruk loop bund mile 0/0+200, 04 Nos. Stone Stud Other (with field f 10,393,757.0 2024-01-2 s, providing stone pitching, st IDA / 72500 Infrastructure Rehabilitation Prior Direct Selection Direct - National 0.00 Signed 2023-04-14 2023-04-17 2023-04-14 2023-04-26 2023-04-27 2023-06-09 or explanation) 0 2 one apron along Rukh loop b und mile 0/0 to 0/5 and Ghu mra loop bund mile 4/6 & pro viding stone pitching and apr on at remaining portions. PK-POSID-356505-CW-DIR / Rehabilitation/Re-Constructio Other (with field f 2024-01-2 IDA / 72500 Infrastructure Rehabilitation Post Direct Selection Direct - National 1,957,566.00 0.00 Signed 2023-04-14 2023-04-14 2023-04-14 2023-04-14 2023-04-27 n of Regulator Mile 44th of D or explanation) 2 esert Canal. Damaged during floods 2022. GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PK-POSID-353032-GO-RFQ / Project Management and Op Request for Quota Single Stage - One E IDA / 72500 Post Limited 107,410.00 0.00 Signed 2023-04-03 2023-04-03 2023-04-25 2023-10-22 Procurement of Vehicles. erational Costs tions nvelope PK-POSID-364645-GO-RFQ / Project Management and Op Request for Quota Single Stage - One E Under Imple Procurement of IT Equipment IDA / 72500 Post Limited 14,000.00 0.00 2023-06-01 2023-06-02 2023-06-08 2023-07-08 erational Costs tions nvelope mentation for Office use. NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Page 4 Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PK-POSID-342908-CS-QCBS / Institutional Strengthening f Forensic Analysis of 2022 Flo Quality And Cost- Open - Internationa IDA / 72500 or Resilience and Technical Prior 1,500,000.00 0.00 Under Review 2023-02-16 2023-02-20 2023-04-06 2023-05-11 2023-06-10 2023-06-27 2023-07-07 2024-07-06 ods and Mitigation Options o Based Selection l Assistance n the Right Bank of Indus. PK-POSID-364945-CS-CQS / Project Management and Op Consultant Qualifi Under Implement IDA / 72500 Post Limited 75,000.00 0.00 2023-06-02 2023-06-08 2023-06-12 2023-06-19 2023-06-26 2026-06-25 The Hiring of Internal Audit Fi erational Costs cation Selection ation rm. PK-POSID-364947-CS-CQS / Environmental and Social Saf Project Management and Op Consultant Qualifi eguard Management Implem IDA / 72500 Post Limited 100,000.00 0.00 Under Review 2023-06-02 2023-06-08 2023-06-12 2023-06-19 2023-06-26 2024-03-22 erational Costs cation Selection entation and Monitoring Of R ehabilitation of Dhoro Puran Works. PK-POSID-366420-CS-QCBS / Institutional Strengthening f Hiring of Consultancy Service Quality And Cost- Open - Internationa Pending Impleme IDA / 72500 or Resilience and Technical Prior 1,200,000.00 0.00 2023-06-12 2023-06-19 2023-08-18 2023-09-15 2023-09-29 2023-11-03 2023-12-01 2024-11-30 s for Designing Flood Detenti Based Selection l ntation Assistance on Weirs and Flood Affected Embankments. INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PK-POSID-344014-CS-CDS / Institutional Strengthening f Development & Integration o Direct - Internation IDA / 72500 or Resilience and Technical Post Direct Selection 949,373.00 0.00 Signed 2023-02-20 2023-03-05 2023-03-01 2023-03-15 2023-04-04 2024-04-02 f Kirthar Model and Operatio al Assistance ns & Maintenance of Data Ce nter. PK-POSID-346415-CS-INDV / Project Management and Op Individual Consult The Hiring of Project Director IDA / 72500 Post Open - National 101,533.00 0.00 Signed 2023-03-01 2023-03-17 2023-03-29 2023-06-02 2023-04-03 2023-06-02 2023-04-12 2025-04-09 erational Costs ant Selection (Market Based). PK-POSID-349520-CS-INDV / Project Management and Op Individual Consult The Hiring of Gender Speciali IDA / 72500 Post Open - National 12,915.00 0.00 Signed 2023-03-14 2022-11-20 2023-04-06 2022-12-16 2023-04-07 2022-12-26 2023-04-13 2024-04-11 erational Costs ant Selection st for SFERP. PK-POSID-349526-CS-INDV / Project Management and Op Individual Consult The Hiring of Environment Co IDA / 72500 Post Open - National 12,915.00 0.00 Signed 2023-03-14 2022-11-20 2023-04-06 2022-12-16 2023-04-07 2022-12-26 2023-04-13 2024-04-11 erational Costs ant Selection nsultant for SFERP. PK-POSID-349551-CS-INDV / Project Management and Op Individual Consult The Hiring of Social Safeguar IDA / 72500 Post Open - National 12,915.00 0.00 Signed 2023-03-14 2022-11-20 2023-04-06 2022-12-16 2023-04-07 2022-12-26 2023-04-13 2024-04-11 erational Costs ant Selection d Consultant for SFERP. Page 5 18 MONTHS PROCUREMENT PLAN- (FINES) I. General 1.Project information Country: Malawi Project Name: Financial Inclusion and Entrepreneurship Scaling (FINES) Project ID: P168577 2.Project Implementation Agency: Reserve Bank of Malawi 3.Date of the Procurement Plan: January 2020 4.Period covered by this Procurement Plan: March 2020 to December 2021 II. Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016 Revised November 2017 and August 2018) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. III. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. IV. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the Public Procurement and Disposal of Public Assets Act, 2017 of the Republic of Malawi, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations. In accordance with paragraph 5.3 of the Procurement Regulations, the request for bids/request for proposals document shall require that Bidders/Proposers submitting Bids/Proposals present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit Page 1 of 8 rights. The form of the Letter of Acceptance is attached in Appendix 1. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. Not Applicable Procurement of Second-Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables. Not Applicable. Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: Not Applicable for those contracts identified in the Procurement Plan tables; Works: Not Applicable for those contracts identified in the Procurement Plan tables. Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations: Not Applicable. Other Relevant Procurement Information: - (a) Procurement Approach and Prior Review Thresholds: The Procurement Arrangements as indicated in the below table will be used. The thresholds for the Bank’s prior review requirements are also provided in the table: Prior-review Thresholds for Procurement Methods Thresholds Procurem Substanti Works Goods, IT & Non-Consulting Shortlist of National ent al Services Consultants Type Risk ($`000) Works 10,000 Open Request Request Internatio for Engineerin Open Open for nal or Quotatio Open g& Nation Nationa Quotatio Consulting n or internatio Constructio al or l or n or Services ICB National nal or ICB n NCB NCB National ($'000) ($'000 Shoppin ($'000) Supervision ($'000) ($'000) Shopping g ($'000) ($'000) ($'000) Goods, IT 2,000 & Non- Consulting ≧ < ≦ ≧ < ≦ < ≦ Services Consultan 1,000 ts (Firms) 7,000 7,000 200 1,000 1,000 100 200 300 Individual 300 Consultan ts Page 2 of 8 *These prior review thresholds are for the purposes of the initial procurement plan for the first 18 months. The thresholds will be revised periodically based on re-assessment of risks. All contracts not subject to prior review will be post-reviewed. Prequalification. Not expected for the works/goods packages in the procurement plan. Proposed Procedures for CDD Components: Not Applicable Reference to (if any) Project Operational/Procurement Manual: The Ministry of Agriculture Irrigation and Water Development team will prepare Procurement manuals. The Procurement Plan will also form part of the Project Implementation Manual. Any Other Special Procurement Arrangements: None Page 3 of 8 Procurement Packages/Plan with Procurement Arrangements and Time Schedule: as per the table below: b) PROCUREMENT PLAN Works 1 2 3 4 5 6 7 8 9 Ref. Contract Estimated Procurement Prequalifica Domestic Review Expected bid Expected Comme No. Method/ tion Preferen opening date Contract nts (Description) Cost Arrangement (yes/no) ce by Bank Signature (yes/no) Date US$ million (Prior / Post) 1. Minor works for 200,000.00 Open, National, Post No Post September 11, October maintenance of PIU offices RFB 2020 16, 2020 Goods and Non-Consulting Services 1 2 3 4 5 6 7 8 9 Ref. Contract Estimated Procurement Prequalific Domestic Review Expected bid Expected Comme No. (Description) Cost Method/ ation Preferenc by Bank opening date Contract nts US$ million Arrangement (yes/no) e (Prior / Signature (yes/no) Post) Date 1. Procurement of 8 motor 550,000.00 Open National, Post No Post Sept 11, 2020 Nov 16, 2020 vehicles RFB 2. Procurement of office 500,000.00 Open National, Post No Post August 07, 2020 August 31, furniture, ICT equipment RFB 2020 and system upgrades 3. Procurement of an ICT 300,000.00 Open National, Post No Post February 15, March 30, system for proper stress RFB 2021 2021 testing by the Reserve Bank’s Supervision Department 4. Procurement of a 150,000.00 Open National, Post No Post February 15, March 30, surveillance system for the RFB 2021 2021 securities market 5. Procurement of an 100,000.00 Open National, Post No Post February 15, March 30, integrated risk RFB 2021 2021 management system for Deposit Insurance Scheme (DIS) Page 4 of 8 Consultancy Services 1 2 3 4 5 6 7 8 Ref. No. Description of Assignment Estimated Selection Review Expected date Expected Comment Cost Method/ by Bank of proposal Contract s US$ Arrangement (Prior / submission Signature Post) Date IDA 1. Consulting services to carry out annual external 150,000.00 Open National LCS Post August 30, 2021 Sept 20, 2021 audits 2. Consulting services to carry out Baseline surveys 200,000.00 Open International Post September 11, October 16, 2020 QCBS 2020 3. Consulting services to collect and consolidate data 200,000.00 Open International Post February 15, March 30, 2021 on MSMEs on a national level to support the creation QCBS 2021 of a national database on MSMEs 4. Consulting services to Develop legal, regulatory and 200,000.00 Open International Post February 15, March 30, 2021 supervision frameworks for consumer protection; QCBS 2021 and digital finance products 5. Consulting service to support MAIIC 100,000 Open, National Post September 11, October 16, 2020 QCBS 2020 6. Consulting service to support RBM administration of 100,000 Open, National Post February 15, March 30, 2021 LOCs to PFIs, and provide support for onboarding of QCBS 2021 MFIs to the MFI Hub 7. Consulting service to support capacity building at 100,000 Open, National Post February 15, March 30, 2021 the Malawi Registration Bureau CQS 2021 8. Consulting service to conduct BDS Service activities 1,000,000 Open, International Prior September 11, October 16, 2020 QCBS 2020 9. Consulting Service to support and build capacity at 200,000 Open International Post September 11, October 16, 2020 SMEDI QCBS 2020 10. Consulting service to support improvement of 150,000 Open, National Post September 11, October 16, 2020 policy, legal and regulatory environment at the RBM, QCBS 2020 MoITT, and MoFEPD. 11. Hiring of Procurement Specialist 392,000.00 Open National Prior Review 12. Hiring of a Financial Management Specialist 392,000.00 Open National Prior Review 13. Environmental and Social Risk Management 300,000.00 Open National Prior Specialist Review 14. Hiring of M&E Specialist 250,000.00 Open National Post Review Page 5 of 8 Appendix 1 Letter of Acceptance of the World Bank’s Anti-Corruption Guidelines and Sanctions Framework Date: Invitation of Bids/Proposals No.__________ To: ___________________________________________________________________________ We, along with our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not) consultants and personnel, acknowledge and agree to abide by the World Bank’s policy regarding Fraud and Corruption (corrupt, fraudulent, collusive, coercive, and obstructive practices), as set out and defined in the World Bank’s Anti-Corruption Guidelines1 in connection with the procurement and execution of the contract (in case of award), including any amendments thereto. We declare and warrant that we, along our sub-contractors, sub- consultants, service providers, suppliers, agents (whether declared or not), consultants and personnel, , are not subject to, and are not controlled by any entity or individual that is subject to, a temporary suspension, early temporary suspension, or debarment imposed by a member of the World Bank Group, including, inter alia, a cross- debarment imposed by the World Bank Group as agreed with other international financial institutions (including multilateral development banks), or through the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement. Further, we are not ineligible under the laws or official regulations of [Insert name of Employer as per bidding document] or pursuant to a decision of the United Nations Security Council. We confirm our understanding of the consequences of not complying with the World Bank’s Anti-Corruption Guidelines, which may include the following: a. rejection of our Proposal/Bid for award of contract; b. in the case of award, termination of the contract, without prejudice to any other remedy for breach of contract; and c. sanctions, pursuant to the Bank’s Anti-Corruption Guidelines and in accordance with its prevailing sanctions policies and procedures as set forth in the Bank’s Sanctions Framework. This may include a public declaration of ineligibility, either indefinitely or for a stated period of time, (i) to be awarded or otherwise benefit from a Bank-financed contract, financially or in any other manner;2 (ii) 1Guidelines on Preventing and Combating Fraud and Corruption in Projects Financed by International Bank for Reconstruction and Development Loans and the International Development Agency Credits and Grants, dated October 15, 2006, and revised in January 2011 and July 2016, as they may be revised from time to time. 2 For the avoidance of doubt, a sanctioned party’s ineligibility to be awarded a contract shall include, Page 6 of 8 to be a nominated3 sub-contractor, consultant, manufacturer or supplier, or service provider of an otherwise eligible firm being awarded a Bank-financed contract; and (iii) to receive the proceeds of any loan made by the Bank or otherwise to participate further in the preparation or implementation of any Bank-financed project. We understand that we may be declared ineligible as set out above upon: a. completion of World Bank Group sanctions proceedings according to its prevailing sanctions procedures; b. cross-debarment as agreed with other international financial institutions (including multilateral development banks); c. the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement; or d. temporary suspension or early temporary suspension in connection with an ongoing World Bank Group sanctions proceeding. For avoidance of doubt, the foregoing effects of ineligibility do not extend to a sanctioned firm’s or individual’s execution of its ongoing Bank-financed contracts (or its ongoing sub-agreements under such contracts) that are not the subject of a material modification, as determined by the Bank. We shall permit, and shall cause our sub-contractors, sub-consultants, agents (whether declared or not), personnel, consultants, service providers or suppliers, to permit the Bank to inspect4 all accounts, records, and other documents relating to the procurement process and/or contract execution (in the case of award), and to have them audited by auditors appointed by the Bank. We agree to preserve all accounts, records, and other documents (whether in hard copy or electronic format) related to the procurement and execution of the contract. Name of the Bidder/Consultant: without limitation, (i) applying for pre-qualification, expressing interest in a consultancy, and bidding, either directly or as a nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider, in respect of such contract, and (ii) entering into an addendum or amendment introducing a material modification to any existing contract. 3 A nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider (different names are used depending on the particular bidding document) is one which has been: (i) included by the bidder in its pre-qualification application or bid because it brings specific and critical experience and know-how that allow the bidder to meet the qualification requirements for the particular bid; or (ii) appointed by the Borrower. 4 Inspections in this context are usually investigative (i.e., forensic) in nature: they involve fact-finding activities undertaken by the Bank or persons appointed by the Bank to address specific matters related to investigations/audits, such as evaluating the veracity of an allegation of possible Fraud and Corruption, through the appropriate mechanisms. Such activity includes but is not limited to accessing and examining a firm's or individual's financial records and information, and making copies thereof as relevant; accessing and examining any other documents, data, and information (whether in hard copy or electronic format) deemed relevant for the investigation/audit, and making copies thereof as relevant; interviewing staff and other relevant individuals; performing physical inspections and site visits; and obtaining third-party verification of information. Page 7 of 8 Name of the person duly authorized to sign the Bid/Proposal on behalf of the Bidder/Consultant: Title of the person signing the Letter: Page 8 of 8 PROCUREMENT Malawi : Financial Inclusion and Entrepreneurship Scaling Project PLAN General Information Country: Malawi 2020-12-14 Bank’s Approval Date of the Original Procurement Plan: 2023-06-01 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P168577 GPN Date: 2022-08-25 Project Name: Financial Inclusion and Entrepreneurship Scaling Project Loan / Credit No: IDA / 67460 Reserve Bank of Malawi Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MW-RBM-223957-GO-DIR / PI U Accounting Software Packa Project Implementation Sup IDA / 67460 Post Direct Selection Direct 60,000.00 60,250.00 Signed 2021-03-22 2021-09-01 2021-03-27 2021-09-01 2021-05-11 2021-09-07 2025-09-30 ge- Licences, support & main port tenance, Installation MW-RBM-223977-GO-RFB / P Enhancing the Enabling Envi rocurement for improving of ronment for Supporting the IDA / 67460 Post Request for Bids 350,000.00 0.00 Canceled 2021-04-09 2021-04-14 2021-05-26 2021-06-25 2021-07-30 2025-10-18 a surveillance system for the Financial Inclusion and Grow securities market to ensure th of Entrepreneurs orderly markets, MW-RBM-223956-GO-RFB / P Project Implementation Sup IDA / 67460 Post Request for Bids 600,000.00 564,693.80 Signed 2021-05-21 2021-07-08 2021-05-26 2021-08-06 2021-07-07 2021-09-09 2021-08-06 2021-10-07 2021-09-10 2022-07-04 2025-11-29 rocurement of 9 motor vehicl port es MW-RBM-223965-GO-RFB / P Project Implementation Sup Single Stage - One E IDA / 67460 Post Request for Bids Open - National 350,000.00 0.00 Canceled 2021-07-11 2021-07-16 2021-08-27 2021-09-26 2021-10-31 2025-09-30 rocurement of ICT equipment port nvelope MW-RBM-223961-GO-RFB / P Liquidity Enhancement for M Open - Internationa Single Stage - One E rocurement Integrated Mana IDA / 67460 Post Request for Bids 1,230,000.00 0.00 Canceled 2021-07-25 2021-07-30 2021-09-10 2021-10-10 2021-11-14 2025-09-30 SMEs l nvelope gement Information System f or MAIIC MW-RBM-223972-GO-DIR / P Enhancing the Enabling Envi rocurement of enhancement ronment for Supporting the IDA / 67460 Prior Direct Selection Direct 1,500,000.00 0.00 Canceled 2021-05-28 2021-06-02 2021-07-17 2025-12-06 software on National Switch t Financial Inclusion and Grow o support Electronic payment th of Entrepreneurs s MW-RBM-236762-GO-DIR / PI U Accounting Software Packa Project Implementation Sup IDA / 67460 Post Direct Selection Direct 60,000.00 0.00 Canceled 2021-06-22 2021-06-24 2021-06-27 2021-08-19 2021-08-01 2025-09-25 ge- Licenses, Support and Ma port intenance Installation RBM/FINES/002/GO / Procure Project Implementation Sup Request for Quota Single Stage - One E IDA / 67460 Post Limited 3,800.00 3,431.62 Completed 2021-04-12 2021-04-12 2021-04-28 2021-04-29 2021-05-13 2021-05-14 ment of Office desks port tions nvelope RBM/FINES/003/GO / Procure Project Implementation Sup Request for Quota Single Stage - One E IDA / 67460 Post Limited 5,000.00 2,107.14 Completed 2021-04-12 2021-04-12 2021-04-28 2021-04-29 2021-05-13 2021-05-14 ment of Office chairs port tions nvelope RBM/FINES/004/GO / Procure Project Implementation Sup Request for Quota Single Stage - One E IDA / 67460 Post Limited 1,700.00 1,050.00 Completed 2021-03-11 2021-03-11 2021-04-18 2021-04-29 2021-05-28 2021-05-14 ment of Projector and Screen port tions nvelope RBM/FINES/005/GO / Procure Project Implementation Sup Request for Quota Single Stage - One E IDA / 67460 Post Limited 18,000.00 18,256.98 Completed 2021-02-09 2021-02-09 2021-04-28 2021-04-29 2021-05-13 2021-05-14 ment of Color Photo Copier port tions nvelope RBM/FINES/006/GO / Procure Project Implementation Sup Request for Quota Single Stage - One E IDA / 67460 Post Limited 4,000.00 2,355.87 Completed 2021-04-19 2021-04-19 2021-04-28 2021-05-15 2021-05-10 2021-05-15 ment of Mobile Phones port tions nvelope RBM/FINES/007/GO / Procure Project Implementation Sup Request for Quota Single Stage - One E IDA / 67460 Post Limited 4,000.00 3,000.00 Completed 2021-04-09 2021-04-09 2021-04-28 2021-04-29 2021-05-13 2021-05-14 ment of Filling Cabinet port tions nvelope RBM/FINES/008/GO / Procure Project Implementation Sup Request for Quota Single Stage - One E IDA / 67460 Post Limited 2,000.00 706.76 Completed 2021-02-17 2021-02-17 2021-04-28 2021-04-29 2021-05-13 2021-04-29 ment of Binding Machine port tions nvelope RBM/FINES/009/GO / Procure Project Implementation Sup Request for Quota Single Stage - One E IDA / 67460 Post Limited 44,000.00 32,061.26 Completed 2020-12-28 2020-12-28 2021-04-28 2021-04-29 2021-05-10 2021-05-11 ment of Laptops port tions nvelope RBM/FINES/010/GO / Procure Project Implementation Sup Request for Quota Single Stage - One E IDA / 67460 Post Limited 1,200.00 1,022.86 Completed 2021-04-23 2021-04-23 2021-04-28 2021-04-29 2021-05-13 2021-05-14 ment of Bar Fridge port tions nvelope MW-RBM-250746-GO-RFP / P rocurement of an Integrated Liquidity Enhancement for M Request for Propo Open - Internationa Management Information Sys IDA / 67460 Post 1,230,000.00 0.00 Canceled 2021-09-03 2021-11-19 2021-11-19 2021-09-08 2022-01-28 2022-07-02 2022-08-06 2024-01-28 SMEs sals l tem for Malawi Agricultural a nd Industrial Investment Cor poration Plc (MAIIC) MW-RBM-223955-GO-RFB / P Project Implementation Sup Single Stage - One E IDA / 67460 Post Request for Bids Open - National 200,000.00 0.00 Canceled 2021-06-18 2021-06-23 2021-08-04 2021-09-03 2021-10-08 2025-09-25 rocurement of office furnitur port nvelope e MW-RBM-223981-GO-RFB / P Project Implementation Sup Single Stage - One E IDA / 67460 Post Request for Bids Open - National 50,000.00 0.00 Canceled 2021-06-22 2021-06-27 2021-08-08 2021-09-07 2021-10-12 2025-09-25 rocurement -system upgrade port nvelope s MW-RBM-264980-GO-RFQ / Liquidity Enhancement for M Request for Quota Single Stage - One E Supply and delivery of ICT Eq IDA / 67460 Post Limited 34,000.00 87,050.45 Completed 2022-01-01 2022-01-12 2022-02-26 2022-02-19 2022-04-27 2022-04-30 SMEs tions nvelope uipment for MoF and MoI (dat abase) MW-RBM-265216-GO-RFQ / Project Implementation Sup Request for Quota Single Stage - One E Supply and delivery of 2022 IDA / 67460 Post Limited 4,000.00 1,926.45 Signed 2022-01-01 2021-12-07 2022-02-19 2022-01-07 2022-04-20 port tions nvelope calendars, diaries and busine ss cards MW-RBM-265219-GO-DIR / D Enhancing the Enabling Envi esign, supply and delivery of ronment for Supporting the IDA / 67460 Post Direct Selection Direct 30,000.00 39,028.36 Signed 2021-12-20 2021-12-06 2021-12-25 2021-12-06 2022-02-05 2021-12-30 2022-08-04 5000 ATM debit cards for MFI Financial Inclusion and Grow Hub th of Entrepreneurs Page 1 MW-RBM-267217-GO-RFQ / Project Implementation Sup Request for Quota Single Stage - One E IDA / 67460 Post Limited 28,000.00 30,622.25 Completed 2021-12-18 2021-12-22 2022-02-12 2022-01-11 2022-08-11 2022-01-15 Server port tions nvelope MW-RBM-278501-GO-RFB / Design, Supply, Installation a nd Commissioning of Integrat Liquidity Enhancement for M Open - Internationa Single Stage - One E IDA / 67460 Post Request for Bids 1,230,000.00 0.00 Signed 2022-02-28 2022-02-15 2022-03-05 2022-02-17 2022-04-16 2022-04-14 2022-05-16 2022-06-08 2022-06-20 2025-07-31 ed Management System for SMEs l nvelope Malawi Agricultural and Indus trial Investment Corporation (MAIIC) MW-RBM-289686-GO-RFQ / Enhancing the Enabling Envi Supply and delivery of ICT Eq ronment for Supporting the Request for Quota Single Stage - One E IDA / 67460 Post Limited 70,000.00 61,456.90 Completed 2022-05-14 2022-04-19 2022-07-09 2022-06-10 2022-09-07 2022-07-14 uipment for MFI Hub and Dep Financial Inclusion and Grow tions nvelope artment of Registrar General th of Entrepreneurs MW-RBM-236760-GO-RFB / S Enhancing the Enabling Envi upply, Installation and Comm ronment for Supporting the Single Stage - One E issioning of an Automated M IDA / 67460 Post Request for Bids Open - National 350,000.00 0.00 Signed 2022-05-27 2022-06-09 2022-06-01 2022-06-10 2022-07-13 2022-08-04 2022-08-12 2022-09-30 2022-09-16 2023-03-15 Financial Inclusion and Grow nvelope arket Trading Surveillance Sy th of Entrepreneurs stem for Reserve Bank of Mal awi MW-RBM-298572-GO-RFQ / Enhancing the Enabling Envi Design and printing of broch ronment for Supporting the Request for Quota Single Stage - One E IDA / 67460 Post Limited 8,000.00 0.00 Signed 2022-07-30 2022-07-07 2022-09-24 2023-03-23 ures and flyers for Pension A Financial Inclusion and Grow tions nvelope wareness th of Entrepreneurs MW-RBM-303991-GO-RFQ / Project Implementation Sup Request for Quota Single Stage - One E Supply and delivery of One ( IDA / 67460 Post Limited 100,000.00 0.00 Signed 2022-09-24 2022-08-03 2022-11-19 2023-05-18 port tions nvelope 1) Station Wagon SUV MW-RBM-318976-GO-RFB / S upply and Delivery of Procur Scaling Entrepreneurship an Single Stage - One E IDA / 67460 Post Request for Bids Open - National 200,000.00 0.00 Signed 2022-12-01 2022-10-28 2022-12-06 2022-10-31 2023-01-17 2022-11-10 2023-02-16 2022-12-09 2023-03-23 2023-05-22 ement of ICT Equipment for S d Building Firm Capabilities nvelope MEDI Head Office and Region al Offices. MW-RBM-322622-GO-DIR / S Enhancing the Enabling Envi upply, Installation and Comm ronment for Supporting the Direct - Internation Under Imple IDA / 67460 Post Direct Selection 1,500,000.00 0.00 2022-12-01 2022-10-24 2022-12-06 2022-11-01 2023-01-24 2023-04-24 issioning of National E-paym Financial Inclusion and Grow al mentation ent Gateway th of Entrepreneurs MW-RBM-318969-GO-RFB / S Enhancing the Enabling Envi upply, Installation and Comm ronment for Supporting the Single Stage - One E issioning of a Mobile Trading IDA / 67460 Post Request for Bids Open - National 200,000.00 0.00 Canceled 2023-01-02 2022-11-18 2023-01-16 2022-11-18 2023-02-27 2023-01-10 2023-03-29 2023-01-18 2023-05-19 2023-11-15 Financial Inclusion and Grow nvelope Platform for the Malawi Stock th of Entrepreneurs Exchange Automated Tradin g System. MW-RBM-325735-GO-RFQ / P rinting and delivery of 500 co Scaling Entrepreneurship an Request for Quota Single Stage - One E IDA / 67460 Post Limited 5,000.00 0.00 Signed 2023-01-16 2022-11-18 2023-03-27 2023-05-26 pies of MSME policy documen d Building Firm Capabilities tions nvelope t for Ministry of Trade and In dustry MW-RBM-332182-GO-RFQ / Enhancing the Enabling Envi Supply and delivery of Tablet ronment for Supporting the Request for Quota Single Stage - One E IDA / 67460 Post Limited 20,000.00 0.00 Signed 2023-03-20 2023-02-27 2023-06-29 2023-12-26 s for Complaints Handling an Financial Inclusion and Grow tions nvelope d Financial literacy. th of Entrepreneurs MW-RBM-358971-GO-RFQ / Enhancing the Enabling Envi Designing, supply and deliver ronment for Supporting the Request for Quota Single Stage - One E Under Imple y of IEC materials (Roll up ba IDA / 67460 Post Limited 20,000.00 0.00 2023-06-19 2023-05-26 2023-08-07 2023-10-06 Financial Inclusion and Grow tions nvelope mentation nners, Golf shirts, Caps, Clot th of Entrepreneurs h, Billboards, Backdrop bann er, Brochures) MW-RBM-364667-GO-DIR / D Project Implementation Sup Pending Impl esigning and printing of bran IDA / 67460 Post Direct Selection Direct - National 9,205.00 0.00 2023-08-31 2023-09-05 2023-10-10 2024-04-07 port ementation ded cloth wrapper for FInES P roject MW-RBM-364671-GO-RFQ / P Enhancing the Enabling Envi rocurement of ICT Equipment ronment for Supporting the Request for Quota Single Stage - One E Under Imple (1Desktop and 2 scanner/pri IDA / 67460 Post Limited 5,714.00 0.00 2023-09-04 2023-10-30 2023-12-29 Financial Inclusion and Grow tions nvelope mentation nters) for Pension and Financ th of Entrepreneurs ial Sector Policy Division, Min istry of Finance MW-RBM-366379-GO-RFQ / Enhancing the Enabling Envi Supply, installation and confi ronment for Supporting the Request for Quota Single Stage - One E Pending Impl guration of network firewall d IDA / 67460 Post Limited 20,000.00 0.00 2023-08-28 2023-10-26 2024-01-24 Financial Inclusion and Grow tions nvelope ementation evice for IFMIS interface with th of Entrepreneurs Natswitch on e-payment gate way NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MW-RBM-265206-NC-RFQ / Project Implementation Sup Request for Quota Single Stage - One E Migration of email platform t IDA / 67460 Post Limited 5,000.00 25,000.00 Signed 2021-12-25 2021-12-06 2022-02-12 2022-02-11 2022-04-13 port tions nvelope o Microsoft 365 MW-RBM-298557-NC-RFQ / P Enhancing the Enabling Envi roduction of FInES and Pensi ronment for Supporting the Request for Quota Single Stage - One E IDA / 67460 Post Limited 45,000.00 0.00 Signed 2022-09-24 2022-08-03 2022-11-19 2023-01-18 on Awareness Materials (Jingl Financial Inclusion and Grow tions nvelope es and Comedies) th of Entrepreneurs MW-RBM-303998-NC-RFQ / Project Implementation Sup Request for Quota Single Stage - One E IDA / 67460 Post Limited 1,000.00 633.26 Signed 2022-10-01 2022-08-03 2022-11-26 2022-08-25 2023-01-25 Design of FInES Project logo port tions nvelope MW-RBM-358976-NC-RFQ / P Enhancing the Enabling Envi roduction and airing of anima ronment for Supporting the Request for Quota Single Stage - One E Under Imple IDA / 67460 Post Limited 10,000.00 0.00 2023-07-03 2023-05-19 2023-08-28 2024-02-24 ted videos, video documenta Financial Inclusion and Grow tions nvelope mentation ries, radio and video jingles a th of Entrepreneurs nd adverts MW-RBM-358985-NC-DIR / S Enhancing the Enabling Envi upply and installation of toll-f ronment for Supporting the Under Imple IDA / 67460 Post Direct Selection Direct - National 7,000.00 0.00 2023-06-12 2023-06-09 2023-06-26 2023-06-19 2023-08-14 2024-02-10 ree lines for Financial Consu Financial Inclusion and Grow mentation mer Complaints Handling th of Entrepreneurs MW-RBM-364664-NC-RFQ / P Enhancing the Enabling Envi roduction and airing of TV an ronment for Supporting the Request for Quota Single Stage - One E Under Imple IDA / 67460 Post Limited 7,725.00 0.00 2023-08-14 2023-06-02 2023-10-09 2023-11-08 d Radio messages on launch Financial Inclusion and Grow tions nvelope mentation of Incubation by Malawi Stoc th of Entrepreneurs k Exchange Page 2 CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MW-RBM-223959-CS-QCBS / Consultancy and advisory ser Liquidity Enhancement for M Quality And Cost- Open - Internationa vices to support managemen IDA / 67460 Post 470,000.00 0.00 Canceled 2021-05-28 2021-06-18 2021-08-01 2021-08-29 2021-09-28 2021-11-02 2021-12-07 2025-11-12 SMEs Based Selection l t in capital raising and projec t preparation for MAIIC. MW-RBM-253006-CS-LCS / C Liquidity Enhancement for M Least Cost Selecti Open - Internationa onsultancy services to suppo IDA / 67460 Post 170,000.00 0.00 Canceled 2021-10-04 2021-10-25 2021-12-08 2022-01-05 2022-02-04 2022-03-11 2022-04-15 2025-09-25 SMEs on l rt management in project pre paration MW-RBM-256859-CS-CQS / C onsulting Services to identify Liquidity Enhancement for M Consultant Qualifi innovative firms with projects IDA / 67460 Post Open - National 166,666.67 0.00 Canceled 2021-10-25 2021-10-11 2021-11-08 2021-10-13 2021-12-22 2022-01-21 2022-02-25 2024-12-31 SMEs cation Selection that can access concessional loans from MAIIC Package 2 MW-RBM-256870-CS-CQS / C onsulting Services to identify Project Implementation Sup Consultant Qualifi innovative firms with projects IDA / 67460 Post Open - National 166,666.67 0.00 Canceled 2021-10-25 2021-10-11 2021-11-08 2021-10-13 2021-12-22 2022-01-21 2022-02-25 2024-12-31 port cation Selection that can access concessional loans from MAIIC Package 1 MW-RBM-256867-CS-CQS / C onsulting Services to identify Liquidity Enhancement for M Consultant Qualifi innovative firms with projects IDA / 67460 Post Open - National 166,666.67 0.00 Canceled 2021-10-25 2021-10-11 2021-11-08 2021-10-13 2021-12-22 2022-01-21 2022-02-25 2024-12-31 SMEs cation Selection that can access concessional loans from MAIIC Package 3 MW-RBM-256872-CS-CQS / C onsulting Services to identify Liquidity Enhancement for M Consultant Qualifi innovative firms with projects IDA / 67460 Post Open - National 166,666.67 0.00 Canceled 2021-10-25 2021-10-11 2021-11-08 2021-10-13 2021-12-22 2022-01-21 2022-02-25 2024-12-31 SMEs cation Selection that can access concessional loans from MAIIC Package 4 MW-RBM-256875-CS-CQS / C onsulting Services to identify Liquidity Enhancement for M Consultant Qualifi innovative firms with projects IDA / 67460 Post Open - National 166,666.67 0.00 Canceled 2021-10-25 2021-10-11 2021-11-08 2021-10-13 2021-12-22 2022-01-21 2022-02-25 2024-12-31 SMEs cation Selection that can access concessional loans from MAIIC Package 5 MW-RBM-256863-CS-CQS / C onsulting Services to identify Liquidity Enhancement for M Consultant Qualifi innovative firms with projects IDA / 67460 Post Open - National 166,666.67 0.00 Canceled 2021-10-25 2021-10-11 2021-11-08 2021-10-13 2021-12-22 2022-01-21 2022-02-25 2024-12-31 SMEs cation Selection that can access concessional loans from MAIIC Package 6 MW-RBM-259352-CS-CQS / C onsultancy Service for Trans Liquidity Enhancement for M Consultant Qualifi IDA / 67460 Post Open - National 100,000.00 0.00 Canceled 2021-11-01 2021-10-27 2021-11-22 2021-10-28 2022-01-05 2021-11-30 2022-02-04 2022-03-11 2025-09-25 action Advisory Services for SMEs cation Selection Capital Raising for MAIIC Pac kage 1 MW-RBM-259279-CS-CQS / C onsultancy Service for Trans Liquidity Enhancement for M Consultant Qualifi IDA / 67460 Post Open - National 100,000.00 247,250.00 Signed 2021-11-01 2021-10-27 2021-11-22 2021-10-28 2022-01-05 2021-11-30 2022-02-04 2022-02-15 2022-03-11 2022-04-30 2025-09-25 action Advisory Services for SMEs cation Selection Capital Raising for MAIIC Pac kage 3 MW-RBM-259367-CS-CQS / C Project Implementation Sup Consultant Qualifi onsultancy services for Exter IDA / 67460 Post Open - National 45,000.00 23,985.62 Signed 2021-11-01 2021-10-28 2021-11-22 2021-11-23 2022-01-05 2022-01-06 2022-02-04 2022-02-02 2022-03-11 2022-03-01 2025-09-25 port cation Selection nal Audit Review for PIU MW-RBM-259365-CS-CQS / C Liquidity Enhancement for M Consultant Qualifi onsultancy services for Legal IDA / 67460 Post Open - National 50,000.00 0.00 Canceled 2021-11-01 2021-11-23 2021-11-22 2022-01-11 2022-01-05 2022-02-04 2022-03-11 2025-09-25 SMEs cation Selection Services in respect of MAIIC's Capital raising MW-RBM-259363-CS-CQS / C onsultancy Services on the d Project Implementation Sup Consultant Qualifi IDA / 67460 Post Open - National 180,000.00 99,892.39 Signed 2021-11-01 2021-12-16 2021-11-22 2022-02-28 2022-01-05 2022-04-01 2022-02-04 2022-05-05 2022-03-11 2022-08-01 2025-09-25 evelopment of the Project Ma port cation Selection nagement Information Syste m MW-RBM-259364-CS-CQS / C Project Implementation Sup Consultant Qualifi onsultancy services for Basel IDA / 67460 Post Open - National 200,000.00 227,505.10 Signed 2021-11-01 2022-01-19 2021-11-22 2022-01-28 2022-01-05 2022-03-04 2022-02-04 2022-03-30 2022-03-11 2022-04-30 2025-09-25 port cation Selection ine Survey MW-RBM-253010-CS-QCBS / Liquidity Enhancement for M Quality And Cost- Open - Internationa Consultancy services to sup IDA / 67460 Post 250,000.00 0.00 Canceled 2021-10-04 2021-10-25 2021-12-08 2022-01-05 2022-02-04 2022-03-11 2022-04-15 2025-09-25 SMEs Based Selection l port management in capital r aising MW-RBM-223948-CS-CQS / C onsulting service for Biller an Liquidity Enhancement for M Consultant Qualifi d Card System Intergration a IDA / 67460 Post Open - National 176,000.00 0.00 Canceled 2021-05-28 2021-06-18 2021-08-01 2021-08-31 2021-10-05 2025-12-06 SMEs cation Selection nd capacity building to suppo rt onboarding of MFIs to the MFI Hub MW-RBM-240966-CS-QCBS / Technical Assistance in busin ess development and suppor Scaling Entrepreneurship an Quality And Cost- Open - Internationa t services to entrepreneurs t IDA / 67460 Prior 3,500,000.00 0.00 Canceled 2021-06-25 2021-08-10 2021-07-16 2021-08-29 2021-09-26 2021-10-26 2021-11-30 2022-01-04 2025-01-03 d Building Firm Capabilities Based Selection l o develop the right business models, skills, networks, and to access financial services a nd markets. MW-RBM-264974-CS-QCBS / Consultancy Services for Pro vision of Business Developm Scaling Entrepreneurship an Quality And Cost- Open - Internationa IDA / 67460 Prior 3,000,000.00 0.00 Canceled 2021-12-27 2022-01-17 2022-03-02 2022-04-01 2022-05-01 2022-06-05 2022-07-10 2025-07-09 ent Services to deliver capaci d Building Firm Capabilities Based Selection l ty building training program t o firms defined under subco mponent 2.1 MW-RBM-265225-CS-CQS / P Enhancing the Enabling Envi rovision of consultancy servic ronment for Supporting the Consultant Qualifi IDA / 67460 Post Open - National 20,000.00 22,067.37 Completed 2021-12-20 2021-12-07 2022-01-10 2021-12-16 2022-02-23 2022-01-21 2022-03-25 2022-03-08 2022-04-29 2022-04-22 2022-05-29 2022-10-07 es to conduct systems audit f Financial Inclusion and Grow cation Selection or MFI Hub th of Entrepreneurs MW-RBM-270547-CS-CQS / C ONSULTING SERVICES TO IDE Liquidity Enhancement for M Consultant Qualifi NTIFY INNOVATIVE FIRMS WI IDA / 67460 Post Open - National 166,666.67 118,423.37 Signed 2021-12-26 2022-01-05 2022-01-09 2022-01-10 2022-02-22 2022-02-09 2022-03-24 2022-03-10 2022-04-28 2022-05-21 2025-03-03 SMEs cation Selection TH PROJECTS THAT CAN ACC ESS CONCESSIONAL LOANS F ROM MAIIC PACKAGE 1 Page 3 MW-RBM-256872-CS-CQS-2 / CONSULTING SERVICES TO I Liquidity Enhancement for M Consultant Qualifi DENTIFY INNOVATIVE FIRMS IDA / 67460 Post Open - National 166,666.67 130,809.55 Signed 2021-12-26 2022-01-05 2022-01-09 2022-01-10 2022-02-22 2022-02-09 2022-03-24 2022-03-10 2022-04-28 2022-05-21 2025-03-03 SMEs cation Selection WITH PROJECTS THAT CAN A CCESS CONCESSIONAL LOAN S FROM MAIIC PACKAGE 2 MW-RBM-270552-CS-CQS / C ONSULTING SERVICES TO IDE Liquidity Enhancement for M Consultant Qualifi NTIFY INNOVATIVE FIRMS WI IDA / 67460 Post Open - National 166,666.67 130,809.55 Signed 2021-12-26 2022-01-05 2022-01-09 2022-01-10 2022-02-22 2022-02-09 2022-03-24 2022-03-10 2022-04-28 2022-05-21 2025-03-03 SMEs cation Selection TH PROJECTS THAT CAN ACC ESS CONCESSIONAL LOANS F ROM MAIIC PACKAGE 3 MW-RBM-270553-CS-CQS / C ONSULTING SERVICES TO IDE Liquidity Enhancement for M Consultant Qualifi NTIFY INNOVATIVE FIRMS WI IDA / 67460 Post Open - National 166,666.67 130,809.55 Signed 2021-12-26 2022-01-05 2022-01-09 2022-01-10 2022-02-22 2022-02-09 2022-03-24 2022-03-10 2022-04-28 2022-05-21 2025-03-03 SMEs cation Selection TH PROJECTS THAT CAN ACC ESS CONCESSIONAL LOANS F ROM MAIIC PACKAGE 4 MW-RBM-270557-CS-CQS / C ONSULTING SERVICES TO IDE Liquidity Enhancement for M Consultant Qualifi NTIFY INNOVATIVE FIRMS WI IDA / 67460 Post Open - National 166,666.67 0.00 Signed 2021-12-26 2022-01-05 2022-01-09 2022-01-10 2022-02-22 2022-04-27 2022-03-24 2022-10-07 2022-04-28 2025-03-03 SMEs cation Selection TH PROJECTS THAT CAN ACC ESS CONCESSIONAL LOANS F ROM MAIIC PACKAGE 5 MW-RBM-270558-CS-CQS / C ONSULTING SERVICES TO IDE Project Implementation Sup Consultant Qualifi NTIFY INNOVATIVE FIRMS WI IDA / 67460 Post Open - National 166,666.67 130,809.55 Signed 2021-12-26 2022-01-05 2022-01-09 2022-01-10 2022-02-22 2022-02-09 2022-03-24 2022-03-10 2022-04-28 2022-05-21 2025-03-03 port cation Selection TH PROJECTS THAT CAN ACC ESS CONCESSIONAL LOANS F ROM MAIIC PACKAGE 6 MW-RBM-272572-CS-QCBS / Consultancy Services for Pro vision of Business Developm Scaling Entrepreneurship an Quality And Cost- Open - Internationa IDA / 67460 Prior 3,300,000.00 0.00 Signed 2022-02-14 2022-01-27 2022-03-07 2022-02-04 2022-04-20 2022-05-16 2022-05-20 2022-06-30 2022-06-19 2022-08-24 2022-07-24 2022-10-20 2022-08-28 2025-08-29 ent Services to deliver capaci d Building Firm Capabilities Based Selection l ty building training program t o firms defined under subco mponent 2.1 MW-RBM-272889-CS-CQS / C onsultancy Services to Establ ish a Baseline for Capacity B Scaling Entrepreneurship an Consultant Qualifi Open - Internationa uilding and Access to Financi IDA / 67460 Post 200,000.00 0.00 Signed 2022-02-14 2022-02-08 2022-03-07 2022-02-17 2022-04-20 2022-04-01 2022-05-20 2022-05-05 2022-06-24 2022-11-21 d Building Firm Capabilities cation Selection l al Services for Small and Med ium Enterprises (SMEs) Partic ipating in Firm Capability Trai ning Under Sub-Component 2 .1 MW-RBM-303996-CS-CQS / C Enhancing the Enabling Envi onsultancy to conduct follow- ronment for Supporting the Consultant Qualifi IDA / 67460 Post Open - National 130,000.00 0.00 Signed 2022-09-30 2022-08-24 2022-10-21 2022-09-11 2022-12-04 2022-10-31 2023-01-03 2022-11-28 2023-02-07 2023-07-07 up household survey on Mala Financial Inclusion and Grow cation Selection wi financial capability and Co th of Entrepreneurs nsumer Protection MW-RBM-313226-CS-CQS / P rovision of Consulting service s to design, develop and com mission a user-friendly and r Project Implementation Sup Consultant Qualifi IDA / 67460 Post Open - National 8,000.00 0.00 Signed 2022-11-14 2022-09-16 2022-12-05 2023-01-18 2022-10-20 2023-02-17 2023-03-28 2023-03-24 2023-06-22 esponsive Content Managem port cation Selection ent System (CMS) or website which shall provide a platfor m to all stakeholders to easil y access all material on FInE S Project MW-RBM-259365-CS-CQS-2 / CONSULTANCY SERVICES FO R PROVISION OF LEGAL SERV Liquidity Enhancement for M Consultant Qualifi ICES IN RESPECT OF MALAWI IDA / 67460 Post Open - National 50,000.00 0.00 Canceled 2022-03-28 2022-05-12 2022-04-18 2022-05-17 2022-06-01 2022-07-09 2022-07-01 2022-08-05 2023-02-01 SMEs cation Selection AGRICULTURAL AND INDUST RIAL INVESTMENT CORPORA TION PLC (MAIIC) CAPITAL RA ISING MW-RBM-324785-CS-CQS / C onsulting Services to Provide Capacity Building Programm Scaling Entrepreneurship an Consultant Qualifi e for SMEDI Staff in Financial IDA / 67460 Post Open - National 50,000.00 0.00 Signed 2022-12-26 2022-12-02 2023-01-16 2022-12-06 2023-03-08 2023-01-10 2023-04-07 2023-02-03 2023-05-18 2023-08-16 d Building Firm Capabilities cation Selection and Business Advisory Servic es and Programme Design fo r Micro, Small and Medium E nterprises MW-RBM-327297-CS-CQS / C onsulting Services to identify innovative firms with projects Liquidity Enhancement for M Consultant Qualifi IDA / 67460 Post Open - National 190,000.00 0.00 Signed 2023-01-23 2022-11-23 2023-02-13 2022-12-16 2023-03-29 2023-02-07 2023-04-28 2023-03-19 2023-06-02 2025-07-31 that can access concessional SMEs cation Selection loans from MAIIC (Business in cubators, hubs and accelerat ors) Package 1 MW-RBM-327298-CS-CQS / C onsulting Services to identify innovative firms with projects Liquidity Enhancement for M Consultant Qualifi IDA / 67460 Post Open - National 190,000.00 0.00 Signed 2023-01-23 2022-11-23 2023-02-13 2022-12-16 2023-03-29 2023-02-07 2023-04-28 2023-03-28 2023-06-02 2025-07-31 that can access concessional SMEs cation Selection loans from MAIIC (Business in cubators, hubs and accelerat ors) Package 2 MW-RBM-327299-CS-CQS / C onsulting Services to identify innovative firms with projects Liquidity Enhancement for M Consultant Qualifi IDA / 67460 Post Open - National 190,000.00 0.00 Canceled 2023-01-31 2022-11-23 2023-02-21 2022-12-16 2023-04-06 2023-02-07 2023-05-06 2023-06-10 2025-08-08 that can access concessional SMEs cation Selection loans from MAIIC (Business in cubators, hubs and accelerat ors) Package 3 MW-RBM-327300-CS-CQS / C onsulting Services to identify innovative firms with projects Liquidity Enhancement for M Consultant Qualifi IDA / 67460 Post Open - National 190,000.00 0.00 Canceled 2023-01-23 2022-11-23 2023-02-13 2022-12-16 2023-03-29 2023-02-07 2023-04-28 2023-06-02 2025-07-31 that can access concessional SMEs cation Selection loans from MAIIC (Business in cubators, hubs and accelerat ors) Package 4 MW-RBM-259354-CS-CQS / C onsultancy Service for Trans Liquidity Enhancement for M Consultant Qualifi IDA / 67460 Post Open - National 100,000.00 0.00 Canceled 2021-11-01 2021-10-27 2021-11-22 2021-10-28 2022-01-05 2021-11-30 2022-02-04 2022-03-11 2025-09-25 action Advisory Services for SMEs cation Selection Capital Raising for MAIIC Pac kage 2 INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 4 MW-RBM-209099-CS-INDV / Project Implementation Sup Individual Consult IDA / 67460 Prior Open 392,000.00 60,832.03 Terminated 2020-12-14 2020-12-17 2021-02-09 2021-05-20 2021-02-23 2021-08-23 2021-03-16 2021-06-22 2025-09-30 Procurement Specialist port ant Selection MW-RBM-209097-CS-INDV / Project Implementation Sup Individual Consult IDA / 67460 Prior Open 392,000.00 116,541.90 Signed 2020-12-14 2021-01-07 2021-02-09 2021-05-25 2021-02-23 2021-08-22 2021-03-16 2021-06-11 2025-09-30 Financial Management Speci port ant Selection alist MW-RBM-209089-CS-INDV / Project Implementation Sup Individual Consult Environmental and Social Ris IDA / 67460 Prior Open 392,000.00 88,958.02 Terminated 2020-12-14 2021-01-06 2021-02-09 2021-05-25 2021-02-23 2021-09-09 2021-03-16 2021-06-18 2025-09-30 port ant Selection k Management Specialist MW-RBM-216945-CS-INDV / Project Implementation Sup Individual Consult IDA / 67460 Post Open 250,000.00 4,576.64 Terminated 2021-02-28 2021-02-02 2021-04-18 2021-06-01 2021-05-09 2021-06-02 2021-06-13 2021-07-13 2025-09-30 Monitoring and Evaluation Sp port ant Selection ecialist MW-RBM-223978-CS-INDV / Hiring of Micro Small &Mediu Project Implementation Sup Individual Consult IDA / 67460 Post Open 250,000.00 43,847.68 Signed 2021-03-22 2021-03-29 2021-05-10 2021-07-27 2021-05-31 2021-09-01 2021-07-05 2021-09-03 2025-09-30 m Enterprises (Business Dev port ant Selection elopment) Specialist MW-RBM-223963-CS-INDV / Project Implementation Sup Individual Consult IDA / 67460 Post Open 250,000.00 67,306.89 Terminated 2021-03-22 2021-03-29 2021-05-10 2021-06-25 2021-05-31 2021-09-01 2021-07-05 2021-09-03 2025-09-30 Hiring of Financial Sector Spe port ant Selection cialist MW-RBM-241105-CS-INDV / Consultancy Services to scop e the status of SMEDI, identif Scaling Entrepreneurship an Individual Consult IDA / 67460 Post Open 14,060.00 0.00 Canceled 2021-06-25 2021-06-27 2021-08-13 2021-09-03 2021-10-08 2022-01-06 y its capacity development n d Building Firm Capabilities ant Selection eeds and recommend priority capacity development action s MW-RBM-241101-CS-INDV / Project Implementation Sup Individual Consult Hiring of a Business Develop IDA / 67460 Post Open 250,000.00 0.00 Canceled 2021-06-25 2021-06-28 2021-08-13 2021-09-03 2021-10-08 2022-04-06 port ant Selection ment Services Specialist MW-RBM-251839-CS-INDV / Consultant to scope the statu Scaling Entrepreneurship an Individual Consult s of SMEDI, identify its capaci IDA / 67460 Post Open 30,000.00 28,104.45 Completed 2021-09-03 2021-08-09 2021-10-22 2021-12-06 2021-11-12 2021-12-07 2021-12-17 2021-12-21 2022-06-15 d Building Firm Capabilities ant Selection ty development needs and re commend priority capacity d evelopment actions MW-RBM-258339-CS-INDV / Project Implementation Sup Individual Consult IDA / 67460 Prior Open 250,000.00 61,502.76 Signed 2021-10-18 2021-11-07 2021-12-06 2022-01-25 2021-12-27 2022-02-10 2022-01-31 2022-02-13 2025-09-25 Financial Sector Specialist port ant Selection MW-RBM-209099-CS-INDV.. / Project Implementation Sup Individual Consult IDA / 67460 Prior Open 392,000.00 60,501.37 Signed 2020-12-15 2021-11-17 2021-02-02 2021-08-27 2021-10-22 2022-01-19 2021-11-07 2021-12-18 2025-09-25 Procurement Specialist port ant Selection MW-RBM-209099-CS-INDV. / Project Implementation Sup Individual Consult IDA / 67460 Post Open 392,000.00 0.00 Canceled 2020-12-15 2020-12-15 2021-10-10 2021-10-31 2021-12-05 2025-09-25 Procurement Specialist port ant Selection MW-RBM-264972-CS-INDV / Enhancing the Enabling Envi Consultancy to review activiti ronment for Supporting the Individual Consult IDA / 67460 Post Open 14,458.00 15,000.00 Signed 2021-12-20 2021-12-07 2022-01-28 2022-02-09 2022-02-11 2022-03-11 2022-03-18 2022-04-09 2022-04-17 es planned for the developm Financial Inclusion and Grow ant Selection ent of payment gateway in M th of Entrepreneurs alawi MW-RBM-265208-CS-INDV / Consultancy Services to supp ort National Economic Empo Liquidity Enhancement for M Individual Consult IDA / 67460 Post Open 100,000.00 41,828.93 Completed 2021-12-27 2021-12-06 2022-02-14 2022-01-21 2022-03-07 2022-03-10 2022-04-11 2022-04-04 2022-06-10 werment Fund (NEEF) to stre SMEs ant Selection ngthen their credit portfolio management systems and pr ocedures MW-RBM-209089-CS-INDV. / Project Implementation Sup Individual Consult Environmental and Social Ris IDA / 67460 Prior Open 392,000.00 61,502.76 Signed 2021-12-13 2021-01-06 2022-01-31 2022-01-05 2022-02-21 2022-02-10 2022-03-28 2022-03-12 2025-09-25 port ant Selection k Management Specialist MW-RBM-272092-CS-INDV / Project Implementation Sup Individual Consult Financial Services Developm IDA / 67460 Post Open 250,000.00 60,527.57 Signed 2022-01-31 2022-01-10 2022-03-21 2022-03-01 2022-04-11 2022-03-07 2022-05-16 2022-04-02 2025-09-30 port ant Selection ent Specialist MW-RBM-272077-CS-INDV / Enhancing the Enabling Envi Consultancy to develop a Nat ronment for Supporting the Individual Consult IDA / 67460 Post Open 168,000.00 0.00 Canceled 2022-02-07 2022-01-13 2022-03-28 2022-04-18 2022-05-23 2022-09-20 ional Database for Micro, Sm Financial Inclusion and Grow ant Selection all and Medium Enterprises ( th of Entrepreneurs MSMEs) MW-RBM-272561-CS-INDV / Consultancy to develop a Co Project Implementation Sup Individual Consult mmunication Strategy for the IDA / 67460 Post Open 15,000.00 26,989.25 Signed 2022-02-07 2022-01-13 2022-03-28 2022-02-18 2022-04-18 2022-03-09 2022-05-23 2022-04-22 2022-07-22 port ant Selection Financial Inclusion and Entre preneurship Scaling (FInES) P roject MW-RBM-216945-CS-INDV.. / Project Implementation Sup Individual Consult IDA / 67460 Prior Open 392,000.00 52,077.89 Signed 2022-03-01 2022-02-23 2022-04-19 2022-01-31 2022-05-10 2022-03-11 2022-06-14 2022-03-27 2025-09-25 Monitoring and Evaluation Sp port ant Selection ecialist MW-RBM-278507-CS-INDV / Enhancing the Enabling Envi Consultancy to design a Nati ronment for Supporting the Individual Consult IDA / 67460 Post Open 30,000.00 24,277.56 Signed 2022-02-28 2022-02-17 2022-04-18 2022-04-01 2022-05-09 2022-05-05 2022-06-13 2022-07-28 2022-08-12 onal Database for Micro, Sma Financial Inclusion and Grow ant Selection ll and Medium Enterprises ( th of Entrepreneurs MSMEs) in Malawi MW-RBM-313225-CS-INDV / Project Implementation Sup Individual Consult IDA / 67460 Post Open - National 55,000.00 0.00 Signed 2022-11-07 2022-09-07 2022-12-26 2022-11-22 2023-01-16 2022-12-23 2023-02-20 2024-12-31 Communication Officer for FI port ant Selection nES Project MW-RBM-313237-CS-INDV / Consultancy Services to Iden tify, propose action plan and Liquidity Enhancement for M Individual Consult IDA / 67460 Post Limited 50,000.00 0.00 Signed 2022-11-14 2022-09-22 2022-11-19 2022-09-30 2022-12-10 2022-11-04 2023-01-14 2023-03-10 train financial institutions in i SMEs ant Selection ncreasing access to finance t o MSMEs and farmer coopera tives MW-RBM-313243-CS-INDV / Enhancing the Enabling Envi Consultancy Services for Aut ronment for Supporting the Individual Consult Open - Internationa omation and Enhancement of IDA / 67460 Post 100,000.00 0.00 Canceled 2022-11-30 2022-09-07 2023-01-18 2023-02-08 2023-03-15 2024-03-31 Financial Inclusion and Grow ant Selection l the Complaints Handling and th of Entrepreneurs Management Information Sys tem MW-RBM-313241-CS-INDV / Consultancy Services for Cap acity Building Program for S Scaling Entrepreneurship an Individual Consult IDA / 67460 Post Limited 50,000.00 0.00 Canceled 2022-12-12 2022-09-16 2022-12-17 2022-09-27 2023-01-07 2022-11-01 2023-02-11 2023-03-04 MEDI Staff in Entrepreneurshi d Building Firm Capabilities ant Selection p Development, Business Dia gnostics and Advisory; and C urriculum Development Page 5 MW-RBM-318989-CS-INDV / Enhancing the Enabling Envi Consultancy Services to Stud ronment for Supporting the Individual Consult IDA / 67460 Post Open - National 26,956.00 0.00 Signed 2022-12-19 2022-10-07 2023-02-06 2022-11-22 2023-02-27 2022-11-25 2023-04-03 2023-07-02 y the Cost of Financial Servic Financial Inclusion and Grow ant Selection es in Malawi th of Entrepreneurs MW-RBM-313243-CS-INDV. / Enhancing the Enabling Envi Consultancy Services for Aut ronment for Supporting the Individual Consult Open - Internationa omation and Enhancement of IDA / 67460 Post 100,000.00 0.00 Signed 2022-11-30 2022-10-13 2023-01-18 2022-12-15 2023-02-08 2022-12-19 2023-03-15 2024-03-31 Financial Inclusion and Grow ant Selection l the Complaints Handling and th of Entrepreneurs Management Information Sys tem MW-RBM-313246-CS-INDV / Enhancing the Enabling Envi Consultancy Services for Dev ronment for Supporting the Individual Consult Open - Internationa elopment of a Directive on Fi IDA / 67460 Post 93,000.00 0.00 Canceled 2022-12-05 2022-09-07 2023-01-23 2023-02-13 2023-03-20 2023-09-16 Financial Inclusion and Grow ant Selection l nancial Consumer Protection th of Entrepreneurs for Users of Digital Financial Services MW-RBM-327295-CS-INDV / Consultancy for Capacity Buil ding Programme for SMEDI S Scaling Entrepreneurship an Individual Consult IDA / 67460 Post Open - National 50,000.00 0.00 Signed 2023-01-02 2022-11-23 2023-03-01 2023-01-18 2023-03-22 2023-01-20 2023-04-26 2023-07-25 taff in Entrepreneurship Deve d Building Firm Capabilities ant Selection lopment, Business Diagnostic s and Advisory; and Curriculu m Development MW-RBM-332176-CS-CDS / P rovision of External Audit Ser Project Implementation Sup IDA / 67460 Post Direct Selection Direct - National 45,000.00 0.00 Signed 2023-02-13 2023-01-17 2023-03-29 2023-01-20 2023-06-02 2023-12-31 vices for FInES Project for the port year ended 2022 MW-RBM-364181-CS-INDV / Consultancy Services for dev elopment of Online Training Scaling Entrepreneurship an Individual Consult Under Implement IDA / 67460 Post Open - National 49,547.00 0.00 2023-07-28 2023-06-02 2023-09-15 2023-10-06 2023-11-10 2024-03-09 and Marketing Portals, Mobil d Building Firm Capabilities ant Selection ation e and USSD Applications for s upport of Micro, Small and M edium Enterprises Page 6 PROCUREMENT PLAN (Textual Part) Project information: Greater Accra Resilient Integrated Development (GARID) Project- [P-164330] Project Implementation agency: Ministry of Works and Housing Date of the Procurement Plan: March 28, 2018 Period covered by this Procurement Plan: January to December, 2018 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in [Ghana Public Procurement Act 663, amended with Act 914 ], such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. List only the applicable conditions required to ensure consistency with paragraph 5.4 of the Procurement Regulations. If no conditions apply, delete the phrase “and the following conditions”. a. Open advertising of the procurement opportunity at the national level; b. The procurement is open to eligible firms from any country; c. The request for bids/request for proposals document shall require that Bidders/Proposers submitting Bids/Proposals present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti- Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights; d. Contracts with an appropriate allocation of responsibilities, risks, and liabilities; e. Publication of contract award information; f. Rights for the Bank to review procurement documentation and activities; g. An effective complaints mechanism; and h. Maintenance of records of the Procurement Process. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. N/A Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables N/A Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: is applicable for those contracts identified in the Procurement Plan tables]; Works: is applicable for those contracts identified in the Procurement Plan tables] Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations is Applicable. Other Relevant Procurement Information. . PROCUREMENT Ghana : Greater Accra Resilient and Integrated Development Project PLAN General Information Country: Ghana 2019-02-27 Bank’s Approval Date of the Original Procurement Plan: 2023-06-01 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P164330 GPN Date: Project Name: Greater Accra Resilient and Integrated Development Project Loan / Credit No: IDA / V1450, IDA / 64100 Ministry of Local Government Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 3: Participatory GH-MLG-RESILIANCE-159390 Upgrading of Targeted Flood Request for Quota Single Stage - One E -GO-RFQ / Procurement of 2N IDA / 64100 Post Limited 46,000.00 0.00 Canceled 2020-03-01 2020-04-26 2020-07-25 Prone Low-income Communi tions nvelope o. Vehicles ties and Local Government S upport GH-MLG-RESILIANCE-159389 Component 3: Participatory -GO-RFQ / Procurement of 2N Upgrading of Targeted Flood Request for Quota Single Stage - One E IDA / 64100 Post Limited 3,000.00 9,487.78 Signed 2020-08-15 2020-09-07 2020-10-10 2021-02-25 2021-01-08 o Laptops, 1 No Printers, inte Prone Low-income Communi tions nvelope rnet modem, External Hard D ties and Local Government S rives upport GH-MLG-RESILIANCE-159392 Component 3: Participatory -GO-RFQ / Procurement of off Upgrading of Targeted Flood Request for Quota Single Stage - One E IDA / 64100 Post Limited 1,200.00 0.00 Canceled 2020-03-01 2020-09-07 2020-04-26 2020-07-25 ice furniture - 1 Desk and 1 s Prone Low-income Communi tions nvelope wivel chair ties and Local Government S upport GH-MLG-RESILIANCE-220955 Component 3: Participatory -GO-RFQ / Procure 3 No. Lapt Upgrading of Targeted Flood Request for Quota Single Stage - One E IDA / 64100 Post Limited 8,000.00 6,779.26 Completed 2021-06-26 2021-08-04 2021-08-21 2021-08-25 2021-09-20 2021-11-10 ops, Printer, Scanner and Ext Prone Low-income Communi tions nvelope ernal Hard Drive ties and Local Government S upport GH-MLG-RESILIANCE-220965 Component 3: Participatory -GO-RFQ / Procure office Tabl Upgrading of Targeted Flood Request for Quota Single Stage - One E IDA / 64100 Post Limited 4,200.00 2,623.85 Completed 2021-06-26 2021-08-24 2021-08-21 2021-09-09 2021-09-20 2021-11-10 e, Swivel Chair and File Cabin Prone Low-income Communi tions nvelope et ties and Local Government S upport Component 3: Participatory GH-MLG-RESILIANCE-282273 Upgrading of Targeted Flood Request for Quota Single Stage - One E -GO-RFQ / Procurement of 3N IDA / 64100 Post Limited 8,000.00 0.00 Signed 2022-05-28 2022-06-21 2022-07-23 2022-08-27 Prone Low-income Communi tions nvelope o. Laptops and a Printer ties and Local Government S upport GH-MLG-RESILIANCE-347032 Component 3: Participatory -GO-RFB / Procure Multipurpo Upgrading of Targeted Flood se Drones for the Physical Pla Single Stage - One E Under Imple IDA / 64100 Prone Low-income Communi Post Request for Bids Open - National 665,000.00 0.00 2023-05-15 2023-05-25 2023-05-20 2023-05-30 2023-06-19 2023-07-10 2023-08-07 2023-11-05 nning Departments of GARID nvelope mentation ties and Local Government S MMAs, LUSPA Headquarters a upport nd Greater Accra Regional Co ordinating Council (GARCC) GH-MLG-RESILIANCE-159391 -GO-RFQ / Printing of 200 cop Component 3: Participatory ies of O&M Manuals, 30 copie Upgrading of Targeted Flood Request for Quota Single Stage - One E Pending Impl s of Participating Agreement IDA / 64100 Prone Low-income Communi Post Limited 21,500.00 0.00 2023-06-18 2023-08-13 2023-09-12 tions nvelope ementation Document for Participating M ties and Local Government S MAs & Partners and 250 copi upport es of ICMC Management Fra mework and Guidelines. Component 3: Participatory GH-MLG-RESILIANCE-347029 Upgrading of Targeted Flood Request for Quota Single Stage - One E Pending Impl -GO-RFQ / Procure 2No. Proje IDA / 64100 Post Limited 3,000.00 0.00 2023-05-20 2023-07-15 2023-09-09 Prone Low-income Communi tions nvelope ementation ctors and 2No. Laptops ties and Local Government S upport NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GH-MLG-RESILIANCE-103417 Component 3: Participatory -CS-QCBS / Flood utility asses Upgrading of Targeted Flood Quality And Cost- IDA / V1450 Post Open - National 194,250.00 0.00 Canceled 2021-03-18 2021-04-08 2021-05-22 2021-06-19 2021-07-19 2021-08-23 2021-09-27 2023-09-27 sment and Support for JDPA/ Prone Low-income Communi Based Selection B LI development, sensitizati ties and Local Government S on, capacity building upport GH-MLG-RESILIANCE-182102 Component 3: Participatory -CS-QCBS / Consultancy Servi Upgrading of Targeted Flood Quality And Cost- ces for the Establishment an IDA / 64100 Prone Low-income Communi Post Open - National 120,000.00 118,000.00 Signed 2020-08-25 2021-02-15 2020-09-15 2020-10-29 2021-09-14 2020-11-26 2021-10-22 2020-12-26 2021-11-23 2021-01-30 2021-12-14 2021-03-06 2022-03-31 2022-03-06 Based Selection d Operationalisation of the In ties and Local Government S ter-jurisdictional Coordinatio upport n Management Framework GH-MLG-RESILIANCE-159398 Component 3: Participatory -CS-LCS / Preparation of O & Upgrading of Targeted Flood Least Cost Selecti M Plan and Manuals, Implem IDA / 64100 Prone Low-income Communi Post Open - National 80,000.00 170,000.00 Signed 2020-04-15 2020-12-10 2020-05-06 2020-06-19 2021-06-22 2020-07-17 2021-07-22 2020-08-16 2021-10-13 2020-09-20 2021-10-28 2020-10-25 2021-12-27 2021-04-23 on entation Guidelines for delive ties and Local Government S ry of O & M Grants to GARID upport MAs GH-MLG-RESILIANCE-198806 Component 3: Participatory -CS-QCBS / Consultancy Servi Upgrading of Targeted Flood Quality And Cost- Open - Internationa ces for the Preparation of Joi IDA / 64100 Prone Low-income Communi Prior 2,100,000.00 0.00 Canceled 2020-11-06 2021-03-18 2020-11-27 2021-07-16 2021-01-10 2022-01-04 2021-02-07 2022-02-15 2021-03-09 2021-04-13 2021-05-18 2023-05-08 Based Selection l nt Basin Management Plan fo ties and Local Government S r the Odaw Drainage Basin. upport Page 1 GH-MLG-RESILIANCE-182100 Component 3: Participatory -CS-QCBS / Consultancy Servi Upgrading of Targeted Flood Quality And Cost- Open - Internationa Under Implement IDA / 64100 Prior 1,400,000.00 0.00 2021-04-22 2021-05-13 2021-06-26 2021-07-24 2021-08-23 2021-09-27 2021-11-01 2022-11-01 ces for the Preparation of Ge Prone Low-income Communi Based Selection l ation ospatial Asset Management P ties and Local Government S lan. upport GH-MLG-RESILIANCE-292975 Component 3: Participatory -CS-FBS / Consultancy Servic Upgrading of Targeted Flood Fixed Budget Sele Under Implement IDA / 64100 Post Open - National 200,000.00 0.00 2022-05-19 2022-05-26 2022-06-09 2022-08-15 2022-07-14 2022-11-09 2022-08-13 2023-01-05 2022-08-27 2023-01-25 2022-10-01 2022-10-22 2023-10-22 es for the Preparation of Geo Prone Low-income Communi ction ation spatial Management Assets P ties and Local Government S latform upport GH-MLG-RESILIANCE-325992 Component 3: Participatory -CS-QCBS / Consultancy Servi Upgrading of Targeted Flood Quality And Cost- Open - Internationa Pending Impleme IDA / 64100 Prior 1,000,000.00 0.00 2023-06-07 2023-06-28 2023-08-11 2023-09-08 2023-10-08 2023-11-12 2023-12-17 2024-07-25 ces for the Development of a Prone Low-income Communi Based Selection l ntation n Integrated Odaw Basin Man ties and Local Government S agement Plan upport INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GH-MLG-RESILIANCE-159394 Component 3: Participatory -CS-INDV / Consultancy Servi Upgrading of Targeted Flood Individual Consult ces for the Preparation of Joi IDA / 64100 Prone Low-income Communi Post Open 50,000.00 0.00 Canceled 2020-08-20 2020-10-01 2020-10-08 2020-10-29 2020-12-03 2021-06-01 ant Selection nt Basin Management Plan fo ties and Local Government S r the Odaw Drainage Basin. upport Page 2 Procurement Plan I. General 1. Project Information Country : Kenya Recipient : Republic of Kenya Project Name : National Agriculture and Rural Inclusive Growth Loan Credit No. : IDA 59000 2. Date of General Procurement Notice : 9th February 2018 3. Period Covered by this procurement plan : 18 months II. Goods, Works, and Non-Consulting Services 1. Thresholds for the Method of Procurement: Method of Procurement Thresholds for Method (US$ equivalent) Open International (Goods) Equal to or more than 3 million Open National ( Goods) – Open < $3 million Tender as per PPDA 2015 RFQ (Goods) Less than 20,000 or as stipulated in Kenya Procurement Regulations 2017 Open International (Works) Equal to or more than 15 million Open National (Works) - Open Less than 15 million Tender as per PPDA 2015 RFQ (works) Less than 20,000 or as stipulated in Kenya Procurement Regulations 2017 Method of Procurement Thresholds for Method (US$ equivalent) Open International (Non-consulting Equal to or More than 3 million Services) Open National (Non-consulting Less than 3 million Services) - Open Tender as per PPDA 2015 Direct Contracting No threshold; meet requirements of Bank’s Procurement Regulations Prior Review: The details of the Procurement review / oversight are defined in the Annex II of the Regulations for borrowers. The following would be subject to Prior review of the Bank regardless of the Method of selection (Project Procurement Risk Rating is “High”): (a) Goods, information technology and Non-consulting Services: First procurement under the project irrespective of value and all procurements estimated to cost more than USD 1.5 million (b) Works (including turnkey, supply & installation of plant and equipment and PPP); First procurement under the project irrespective of value and all procurements estimated to cost more than USD 5 million and The prior review thresholds will be reviewed during the implementation of the project and modified, based on the risk assessment. 2. For contracts subject to prior review, the Borrower shall seek the Bank’s no objection before agreeing to: a. an extension of the stipulated time for execution of a contract that has an impact on the planned completion of the project; b. any material modification of the scope of the Works, Goods, Non- consulting services or Consulting Services, or other significant changes to the terms and conditions of the contract; c. any variation order or contract amendment (except in cases of extreme urgency), including due to extension of time, that singly or combined with all previous variation orders or amendments, increases the original contract amount by more than 15% (fifteen percent); or d. the proposed termination of the contract. The Borrower / IA shall provide a copy of all amendments to the contract to the Bank for its records. 3. Prequalification Not Applicable Domestic Preference. The provision of domestic preference shall be applied in the procurement of goods following international market approach in accordance with Annex VI of the Regulations. Domestic preference shall not apply in the procurement of works. 4. Reference to Standard Procurement Documents Bank’s Standard RFB Goods and RFP Consulting Services dated July 2016 will be used as a base and incorporating suitable modifications and the same would be agreed with the Bank subject international competition. 5. Any Other Special Procurement Arrangements A. Procurement approach under CDD Approach by Communities: Applicable if stipulated in the PAD. B. When approaching the national market, as agreed in the Procurement Plan, the Open Tender procedure of Public Procurement and Asset Disposal Act 2015 and Regulations 2017 may be used. The specific Requirements for national open competitive procurement include the following: a. open advertising of the procurement opportunity at the national level; b. the procurement is open to eligible firms from any country; c. the request for bids/request for proposals document shall require that Bidders/Proposers submitting Bids/Proposals present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights; d. contracts with an appropriate allocation of responsibilities, risks, and liabilities; e. publication of contract award information; f. rights for the Bank to review procurement documentation and activities; g. an effective complaints mechanism; and h. maintenance of records of the Procurement Process. Other national procurement arrangements (other than national open competitive procurement), that may be applied by the Borrower (such as limited/restricted competitive bidding, request for quotations/shopping, direct contracting), shall be consistent with the Bank’s Core Procurement Principles and ensure that the Bank’s Anti-Corruption Guidelines and Sanctions Framework and contractual remedies set out in its Legal Agreement apply. In all cases, the national procurement procedures to be used shall give due attention to quality aspects. 6. The bid evaluation will be carried out according to the agreed timeline in the Procurement Activity Schedule. III. Selection of Consultants 1. Methods and Prior Review Threshold Selection methods of procurement of Consultants' Services (Firms): The Approved Selection Methods as reflected in the Section VII of the procurement regulations Method of Procurement Thresholds for Methods Quality and Cost Based As per requirements of para 7.3 of the Selection (QCBS) Regulations Quality Based Selection As per requirements of para 7.8 to 7.10 (QBS) of the Regulations Selection based on a Fixed As per requirements of para 7.4 and 7.5 of the Budget (FBS) Regulations Selection Based on Least As per requirements of para 7.6 and 7.7 of the Cost Basis (LCS) Regulations Selection based on As per requirements of para 7.11 and 7.12 of Consultant’s Qualification the Regulations (CQ) Direct Must meet the requirements of Para 7.13 to 7.15 of the Regulations, and with prior agreement in PP with the Bank. The short list may consist of all National consultants in case the estimated cost is less than USD 300,000 Procurement methods for Selection of Individual Consultants (IC): The Approved Selection Methods as reflected in the Section VII of the procurement regulations Method of Procurement Thresholds for Methods Open Competitive As per requirements of para 7.36 and 7.37 of Selection the Regulations Limited Competitive As per requirements of para 7.38 of the Selection Regulations Direct Must meet the requirements of Para 7.39 of the Regulations, and with prior agreement in PP with the Bank *Shall meet the requirements as stated in Regulations Prior Review Thresholds: The details of the Procurement review / oversight are defined in the Annex II of the Regulations for borrowers. The following would be subject to Prior review of the Bank regardless of the Method of selection: (a). Consulting Firm: First procurement under the project irrespective of value and all procurements estimated to cost more than USD 0.5 million. (b). Individual Consultant: all procurements estimated to cost more than USD 0.2 million Terms of Reference (ToR) for all consultant contracts shall be furnished to the Bank for its prior review and No Objection. PROCUREMENT Kenya : National Agricultural and Rural Inclusive Growth Project PLAN General Information Country: Kenya 2019-10-04 Bank’s Approval Date of the Original Procurement Plan: 2023-06-05 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P153349 GPN Date: 2018-02-09 Project Name: National Agricultural and Rural Inclusive Growth Project Loan / Credit No: IDA / 59000 Migori County Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned KE-MIGORI COUNTY-138559- Project Coordination and Ma Single Stage - One E 34,565,500.0 Pending Imp 2020-08-0 IDA / 59000 Prior Request for Bids Open - National 0.00 2019-10-16 2019-10-21 2019-12-02 2020-01-01 2020-02-05 CW-RFB / Good for the grant i nagement nvelope 0 lementation 3 ssuance KE-MIGORI COUNTY-154147- CW-RFB / CONSTRUCTION W ORKS FOR LOWER KUJA IRRI Supporting County Communi Single Stage - One E Pending Imp 2020-07-0 IDA / 59000 Post Request for Bids Open - National 700,000.00 0.00 2020-01-17 2020-01-22 2020-03-04 2020-04-03 2020-05-08 GATION DEVELOPMENT PROJ ty-Led Development nvelope lementation 7 ECT BLOCK 2.1 UNDER MULTI COMMUNITY PROJECT; COMP ONENT 3 KE-MIGORI COUNTY-218291- CW-RFB / GIRIBE LANDSCAPE RESTORATION AND EARTH D Supporting County Communi Single Stage - One E Under Imple 2021-08-3 AM REHABILITATION. THIS WI IDA / 59000 Post Request for Bids Open - National 355,868.00 0.00 2021-02-10 2022-12-15 2021-02-15 2021-03-29 2021-05-03 2021-04-28 2021-06-02 ty-Led Development nvelope mentation 1 LL CREATE SUSTAINABLE AG RICULTURAL PRODUCTION A ND AVAILABILITY OF WATER FOR COMMUNITY USE. KE-MIGORI COUNTY-221343- CW-RFB / SIABAI LANDSCAPE RESTORATION AND EARTH D AM REHABILITATION PROJECT Supporting County Communi Single Stage - One E Under Imple 2021-09-1 WILL CREATE SUSTAINABLE IDA / 59000 Post Request for Bids Open - National 399,912.03 0.00 2021-02-25 2021-03-12 2021-03-02 2021-04-13 2021-05-03 2021-05-13 2021-06-17 ty-Led Development nvelope mentation 5 AGRICULTURAL PRODUCTION AND AVAILABILITY OF WATER FOR COMMUNITY USE THROU GH CLIMATE SMART AGRICUL TURE TECHNOLOGIES. KE-MIGORI COUNTY-148815- Project Coordination and Ma Request for Quota Single Stage - One E 2020-08-0 IDA / 59000 Post Limited 13,000.00 22,595.43 Completed 2019-12-12 2018-05-30 2020-02-06 2018-06-30 CW-RFQ / CPCU OFFICE REFU nagement tions nvelope 4 RBISHMENT KE-MIGORI COUNTY-230006- Request for Bids - CW-RFB / ROKERE/ KOMAKAR Supporting County Communi Single Stage - One E Works (without pr Under Imple 2022-02-1 IDA / 59000 Post Request for Bids Open - National 322,026.20 0.00 2021-04-20 2021-04-28 2021-07-06 2021-05-27 2021-07-06 2021-04-28 2021-04-25 2022-12-08 2021-09-14 2021-05-19 2021-10-14 2021-11-18 A LANDSCAPE RESTORATION ty-Led Development nvelope equalification) SP mentation 6 AND EARTH DAM REHABILITA D TION PROJECT KE-MIGORI COUNTY-230011- Request for Bids - CW-RFB / THE OTATI LANDSC Supporting County Communi Single Stage - One E Works (without pr Under Imple 2022-02-1 IDA / 59000 Post Request for Bids Open - National 423,909.95 0.00 2021-04-20 2021-04-30 2021-07-06 2021-05-27 2021-07-06 2021-04-28 2021-04-25 2021-09-14 2021-05-19 2021-10-14 2021-05-27 2021-11-18 APE RESTORATION AND EAR ty-Led Development nvelope equalification) SP mentation 6 TH DAM REHABILITATION PR D OJECT KE-MIGORI COUNTY-138553- Project Coordination and Ma Single Stage - One E 13,333,333.0 2020-08-1 CW-RFB / Refurbishment of N IDA / 59000 Prior Request for Bids Open - National 0.00 Canceled 2019-10-30 2019-11-04 2019-12-16 2020-01-15 2020-02-19 nagement nvelope 0 7 ARIGP offices GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual KE-MIGORI COUNTY-138546- Project Coordination and Ma Single Stage - One E GO-RFB / Motor cycle procure IDA / 59000 Post Request for Bids Open - National 100,000.00 769.82 Completed 2019-10-03 2019-10-04 2019-10-08 2019-10-04 2019-11-19 2019-10-04 2019-12-19 2019-10-04 2020-01-23 2019-10-04 2020-02-22 2020-09-10 nagement nvelope ment for 20 ward officers. KE-MIGORI COUNTY-148812- Project Coordination and Ma Request for Quota Single Stage - One E Pending Impl GO-RFQ / PURCHASE OF OFFI IDA / 59000 Post Limited 10,000.00 0.00 2019-12-12 2020-02-06 2020-08-04 nagement tions nvelope ementation CE CABINETS FOR CDDCs KE-MIGORI COUNTY-148814- Project Coordination and Ma Request for Quota Single Stage - One E Under Imple GO-RFQ / PURCHASE OF OFFI IDA / 59000 Post Limited 10,360.00 0.00 2019-12-12 2018-05-30 2020-02-06 2020-08-04 nagement tions nvelope mentation CE FURNITURE FOR CPCU KE-MIGORI COUNTY-148820- GO-RFQ / PROCUREMENT OF Supporting County Communi Request for Quota Single Stage - One E IDA / 59000 Post Limited 41,456.00 30,773.47 Completed 2020-01-22 2020-06-05 2020-03-18 2020-06-27 2020-05-17 2020-09-26 SOIL TESTING AND WATER C ty-Led Development tions nvelope ONSERVATION TOOLS KE-MIGORI COUNTY-191573- GO-RFQ / SUPPLY DELIVERY AND INSTALLATION OF IP BA Project Coordination and Ma Request for Quota Single Stage - One E SED TELECONFERENCING SY IDA / 59000 Post Limited 85,000.00 58,380.64 Completed 2020-09-14 2020-10-30 2020-11-11 2020-11-27 2020-12-11 2021-02-26 nagement tions nvelope STEM, FIRE WALL AND NETW ORK ROUTER AND INSTALL I NTERNET CONNECTION IN T HE CPCU OFFICES IN MIGORI COUNTY KE-MIGORI COUNTY-363774- GO-RFQ / PROCUREMENT OF Supporting Community-Driv Request for Quota Single Stage - One E Pending Impl IDA / 59000 Post Limited 23,741.10 0.00 2023-06-14 2023-08-09 2023-11-07 CDDCs AND FPOs SACCOs C en Development tions nvelope ementation OMPUTERS AND PRINTERS NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Page 1 Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual KE-MIGORI COUNTY-164389- CS-CQS / PROVISION OF CON SULTANCY SERVICES ON PRI Supporting Community-Driv Consultant Qualifi Under Implement IDA / 59000 Post Open - National 50,000.00 0.00 2020-03-16 2020-09-10 2020-04-06 2022-12-05 2020-05-20 2020-07-24 2020-06-19 2021-03-01 2020-07-24 2021-08-28 MARY PRODUCTION (TIMPS), en Development cation Selection ation VALUE ADDITION AND LINKA GE TO MARKET IN APICULTUR E VALUE CHAIN KE-MIGORI COUNTY-164403- CS-CQS / PROVISION OF CON SULTANCY SERVICES ON PRI Supporting Community-Driv Consultant Qualifi Under Implement IDA / 59000 Post Open - National 50,000.00 0.00 2020-03-16 2020-09-10 2020-04-06 2022-12-06 2020-05-20 2020-07-24 2020-06-19 2021-03-01 2020-07-24 2021-08-28 MARY PRODUCTION (TIMPS), en Development cation Selection ation VALUE ADDITION AND LINKA GE TO MARKET IN LOCAL CHI CKEN VALUE CHAIN KE-MIGORI COUNTY-164414- CS-CQS / PROVISION OF CON SULTANCY SERVICES ON PRI Supporting Community-Driv Consultant Qualifi Under Implement IDA / 59000 Post Open - National 50,000.00 0.00 2020-03-16 2020-09-10 2020-04-06 2022-12-06 2020-05-20 2021-02-18 2020-06-19 2021-03-01 2020-07-24 2021-08-28 MARY PRODUCTION (TIMPS), en Development cation Selection ation VALUE ADDITION AND LINKA GE TO MARKET IN SWEET PO TATOES VALUE CHAIN KE-MIGORI COUNTY-164420- CS-CQS / PROVISION OF CON SULTANCY SERVICES ON PRI Supporting Community-Driv Consultant Qualifi Under Implement IDA / 59000 Post Open - National 50,000.00 0.00 2020-03-16 2020-09-10 2020-04-06 2022-12-06 2020-05-20 2020-07-24 2020-06-19 2021-03-01 2020-07-24 2021-08-28 MARY PRODUCTION (TIMPS), en Development cation Selection ation VALUE ADDITION AND LINKA GE TO MARKET IN DAIRY CO W MILK VALUE CHAIN INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 2 PROCUREMENT PLAN (Textual Part) Project information: Pakistan Punjab Rural Sustainable Water Supply and Sanitation Project (P169071) Project Implementation agency: Local Government Department Date of the Procurement Plan: April 15, 2022 Period covered by this Procurement Plan: April 2022- December 2025 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016, Revised November 2017 and August 2018) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in Public Procurement Rules 2004 Revised 2020, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions: 1) The eligibility of bidders shall be as defined under Section III of the Procurement Regulations. Accordingly, no bidder or potential bidder shall be declared ineligible for contracts financed by the Bank for reasons other than those provided in Section III of the Procurement Regulations. 2) For national open competitive procurement, only the model procurement documents acceptable to the World Bank, shall be used. 3) The request for bids/request for proposals document shall require that Bidders/Proposers submitting Bids/Proposals present a signed acceptance (in the form attached) at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights. 4) Procurement Documents include provisions, as agreed with the Bank, intended to adequately mitigate against environmental, social (including sexual exploitation and abuse and gender-based violence), health and safety (“ESHS”) risks and impacts 5) Access to procurement opportunities shall not be restricted to firms that have pre-registered and/or paid a registration fee. 6) No preference of any kind shall be given to national bidders in the bidding process. 7) Procurement methods that use two-envelope process and rated criteria shall be subject to Bank’s prior concurrence When other national procurement arrangements (other than national open competitive procurement) are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Letter of Acceptance of the World Bank’s Anticorruption Guidelines and Sanctions Framework1 Date: Invitation of Bids/Proposals No.__________ To: ___________________________________________________________________________ We, along with our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not) consultants and personnel, acknowledge and agree to abide by the World Bank’s policy regarding Fraud and Corruption (corrupt, fraudulent, collusive, coercive, and obstructive practices), as set out and defined in the World Bank’s Anti-Corruption Guidelines2 in connection with the procurement and execution of the contract (in case of award), including any amendments thereto. We declare and warrant that we, along our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not), consultants and personnel, are not subject to, and are not controlled by any entity or individual that is subject to, a temporary suspension, early temporary suspension, or debarment imposed by a member of the World Bank Group, including, inter alia, a cross-debarment imposed by the World Bank Group as agreed with other international financial institutions (including multilateral development banks), or through the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement. Further, we are not ineligible under the laws or official regulations of [Insert name of Employer as per bidding document] or pursuant to a decision of the United Nations Security Council. We confirm our understanding of the consequences of not complying with the World Bank’s Anti-Corruption Guidelines, which may include the following: a. rejection of our Proposal/Bid for award of contract; 1[Drafting note: This document shall be signed by bidders/proposers/consultants and submitted as part of their bids/proposals. In addition, this document shall be signed by the winning bidder/consultant and incorporated as part of the contract.] 2Guidelines on Preventing and Combating Fraud and Corruption in Projects Financed by International Bank for Reconstruction and Development Loans and the International Development Agency Credits and Grants, dated October 15, 2006, and revised in January 2011 and July 2016, as they may be revised from time to time. b. in the case of award, termination of the contract, without prejudice to any other remedy for breach of contract; and c. sanctions, pursuant to the Bank’s Anti-Corruption Guidelines and in accordance with its prevailing sanctions policies and procedures as set forth in the Bank’s Sanctions Framework. This may include a public declaration of ineligibility, either indefinitely or for a stated period of time, (i) to be awarded or otherwise benefit from a Bank-financed contract, financially or in any other manner;3 (ii) to be a nominated4 sub-contractor, sub-consultant, consultant, manufacturer or supplier, or service provider of an otherwise eligible firm being awarded a Bank-financed contract; and (iii) to receive the proceeds of any loan made by the Bank or otherwise to participate further in the preparation or implementation of any Bank- financed project. We understand that we may be declared ineligible as set out above upon: a. completion of World Bank Group sanctions proceedings according to its prevailing sanctions procedures; b. cross-debarment as agreed with other international financial institutions (including multilateral development banks); c. the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement; or d. temporary suspension or early temporary suspension in connection with an ongoing World Bank Group sanctions proceeding. For avoidance of doubt, the foregoing effects of ineligibility do not extend to a sanctioned firm’s or individual’s execution of its ongoing Bank-financed contracts (or its ongoing sub-agreements under such contracts) that are not the subject of a material modification, as determined by the Bank. We shall permit, and shall cause our sub-contractors, sub-consultants, agents (whether declared or not), personnel, consultants, service providers or suppliers, to permit the Bank to inspect5 all accounts, records, and other documents relating to 3 For the avoidance of doubt, a sanctioned party’s ineligibility to be awarded a contract shall include, without limitation, (i) applying for pre-qualification or initial selection), expressing interest in a consultancy, and bidding, either directly or as a nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider, in respect of such contract, and (ii) entering into an addendum or amendment introducing a material modification to any existing contract. 4A nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider (different names are used depending on the bidding document) is one which has been: (i) included by the bidder in its pre-qualification or initial selection application or bid because it brings specific and critical experience and know-how that allow the bidder to meet the qualification requirements for the particular bid; or (ii) appointed by the Borrower. 5Inspections in this context are usually investigative (i.e., forensic) in nature: they involve fact- finding activities undertaken by the Bank or persons appointed by the Bank to address specific the procurement process and/or contract execution (in the case of award), and to have them audited by auditors appointed by the Bank. We agree to preserve all accounts, records, and other documents (whether in hard copy or electronic format) related to the procurement and execution of the contract. Name of the Bidder/Proposer/Consultant: Name of the person duly authorized to sign the Bid/Proposal on behalf of the Bidder/Proposer/ Consultant: Title of the person signing the Letter: matters related to investigations/audits, such as evaluating the veracity of an allegation of possible Fraud and Corruption, through the appropriate mechanisms. Such activity includes but is not limited to accessing and examining a firm's or individual's financial records and information, and making copies thereof as relevant; accessing and examining any other documents, data, and information (whether in hard copy or electronic format) deemed relevant for the investigation/audit, and making copies thereof as relevant; interviewing staff and other relevant individuals; performing physical inspections and site visits; and obtaining third-party verification of information. PROCUREMENT Pakistan : Punjab Rural Sustainable Water Supply and Sanitation Project PLAN General Information Country: Pakistan 2022-04-15 Bank’s Approval Date of the Original Procurement Plan: 2023-06-03 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P169071 GPN Date: 2021-04-22 Project Name: Punjab Rural Sustainable Water Supply and Sanitation Project Loan / Credit No: IBRD / 92670, IDA / 69250 Local Government and Community Development Department, Government of Punjab Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned National Procure PK-LG& CD-289259-CW-RFB ment Document - Water Supply and Sanitation Single Stage - One E Pending Imp 2024-10-1 / Pilot Scheme Provision of W IBRD / 92670 Post Request for Bids Open - National 1 Envelope proce 2,000,000.00 0.00 2023-01-02 2023-01-07 2023-02-18 2023-03-20 2023-04-24 Infrastructure Development nvelope lementation 5 ater supply & Sanitation (Nor ss (Non Bank-SPD th) / W ) National Procure PK-LG& CD-289261-CW-RFB ment Document - Water Supply and Sanitation Single Stage - One E Pending Imp 2024-10-1 / Pilot Scheme Provision of W IBRD / 92670 Post Request for Bids Open - National 1 Envelope proce 2,000,000.00 0.00 2023-01-05 2023-01-10 2023-02-21 2023-03-23 2023-04-27 Infrastructure Development nvelope lementation 8 ater supply & Sanitation (Cen ss (Non Bank-SPD tral) / W ) National Procure PK-LG& CD-289264-CW-RFB ment Document - Water Supply and Sanitation Single Stage - One E Pending Imp 2024-10-1 / Pilot Scheme Provision of W IBRD / 92670 Post Request for Bids Open - National 1 Envelope proce 2,000,000.00 0.00 2023-01-06 2023-01-11 2023-02-22 2023-03-24 2023-04-28 Infrastructure Development nvelope lementation 9 ater Supply & Sanitation (Sou ss (Non Bank-SPD th ) / W ) Request for Quota PK-LG& CD-315561-GO-RFQ Water Supply and Sanitation Request for Quota Single Stage - One E tions - Small Work Pending Imp 2023-05-1 / Rehabilitation of Water Sup IBRD / 92670 Post Open - National 330,000.00 0.00 2022-10-05 2022-11-14 Infrastructure Development tions nvelope s (Emergency) SP lementation 3 ply Schemes D -Competitive National Procure PK-LG& CD-349521-CW-RFB ment Document - Water Supply and Sanitation Single Stage - One E Under Imple 2024-03-2 / Procurement of Civil Works IDA / 69250 Post Request for Bids Open - National 1 Envelope proce 3,200,000.00 0.00 2023-03-20 2023-04-03 2023-03-24 2023-04-03 2023-04-14 2023-05-02 2023-04-24 2023-05-26 Infrastructure Development nvelope mentation 1 of Priority Villages Central-I ( ss (Non Bank-SPD Tehsil Bhowana) ) National Procure PK-LG& CD-349557-CW-RFB ment Document - Water Supply and Sanitation Single Stage - One E Under Imple 2024-03-2 / Procurement of Civil Works IDA / 69250 Post Request for Bids Open - National 1 Envelope proce 1,800,000.00 0.00 2023-03-20 2023-04-03 2023-03-24 2023-04-03 2023-04-14 2023-05-02 2023-04-24 2023-05-26 Infrastructure Development nvelope mentation 1 of Priority Villages Central-II ( ss (Non Bank-SPD Tehsil Pakpattan) ) National Procure PK-LG& CD-349583-CW-RFB ment Document - / Procurement of Civil Works Water Supply and Sanitation Single Stage - One E Under Imple 2024-03-2 IDA / 69250 Post Request for Bids Open - National 1 Envelope proce 1,100,000.00 0.00 2023-03-20 2023-04-03 2023-03-24 2023-04-03 2023-04-14 2023-05-02 2023-04-24 2023-05-26 of Priority Villages South-I (T Infrastructure Development nvelope mentation 1 ss (Non Bank-SPD ehsil Bahawalnagar) ) National Procure PK-LG& CD-349597-CW-RFB ment Document - / Procurement of Civil Works Water Supply and Sanitation Single Stage - One E Under Imple 2024-03-2 IDA / 69250 Post Request for Bids Open - National 1 Envelope proce 1,000,000.00 0.00 2023-03-20 2023-04-03 2023-03-24 2023-04-03 2023-04-14 2023-05-02 2023-04-24 2023-05-26 of Priority Villages South-I (T Infrastructure Development nvelope mentation 1 ss (Non Bank-SPD ehsil Khairpur Tamewali) ) National Procure PK-LG& CD-349608-CW-RFB ment Document - / Procurement of Civil Works Water Supply and Sanitation Single Stage - One E Under Imple 2024-03-2 IDA / 69250 Post Request for Bids Open - National 1 Envelope proce 1,200,000.00 0.00 2023-03-20 2023-04-03 2023-03-24 2023-04-03 2023-04-14 2023-05-02 2023-04-24 2023-05-26 of Priority Villages South-II (T Infrastructure Development nvelope mentation 1 ss (Non Bank-SPD ehsil Kahror Pakka) ) National Procure PK-LG& CD-349614-CW-RFB ment Document - Water Supply and Sanitation Single Stage - One E 2024-03-2 / Procurement of Civil Works IDA / 69250 Post Request for Bids Open - National 1 Envelope proce 1,700,000.00 0.00 Canceled 2023-03-20 2023-04-03 2023-03-24 2023-04-03 2023-04-14 2023-05-02 2023-04-24 2023-05-26 Infrastructure Development nvelope 1 of Priority Villages South-III (T ss (Non Bank-SPD ehsil Liaqatpur) ) National Procure PK-LG& CD-349619-CW-RFB ment Document - / Procurement of Civil Works Water Supply and Sanitation Single Stage - One E Under Imple 2024-03-2 IDA / 69250 Post Request for Bids Open - National 1 Envelope proce 2,500,000.00 0.00 2023-03-20 2023-04-03 2023-03-24 2023-04-03 2023-04-14 2023-05-02 2023-04-24 2023-05-26 of Priority Villages North (Teh Infrastructure Development nvelope mentation 1 ss (Non Bank-SPD sil Kallar Kahar and Kot Momi ) n) National Procure PK-LG& CD-359416-CW-RFB ment Document - Water Supply and Sanitation Single Stage - One E Under Imple 2024-05-0 / Procurement of Civil Works IDA / 69250 Post Request for Bids Open - National 1 Envelope proce 3,300,000.00 0.00 2023-05-04 2023-05-07 2023-05-08 2023-05-08 2023-05-29 2023-05-30 2023-06-08 2023-07-10 Infrastructure Development nvelope mentation 5 of Priority Villages (Tehsil Bh ss (Non Bank-SPD awana 02) ) National Procure PK-LG& CD-359417-CW-RFB ment Document - Water Supply and Sanitation Single Stage - One E Under Imple 2024-05-0 / Procurement of Civil Works IDA / 69250 Post Request for Bids Open - National 1 Envelope proce 3,600,000.00 0.00 2023-05-04 2023-05-04 2023-05-08 2023-05-08 2023-05-29 2023-05-30 2023-06-08 2023-07-10 Infrastructure Development nvelope mentation 5 of Priority Villages (Khairpur ss (Non Bank-SPD Tamewali 02) ) National Procure PK-LG& CD-359419-CW-RFB ment Document - Water Supply and Sanitation Single Stage - One E Under Imple 2024-05-0 / Procurement of Civil Works IDA / 69250 Post Request for Bids Open - National 1 Envelope proce 4,200,000.00 0.00 2023-05-04 2023-05-04 2023-05-08 2023-05-08 2023-05-29 2023-05-30 2023-06-08 2023-07-10 Infrastructure Development nvelope mentation 5 of Priority Villages (Tehsil Ka ss (Non Bank-SPD hror Pakka 02) ) National Procure PK-LG& CD-359420-CW-RFB ment Document - Water Supply and Sanitation Single Stage - One E Under Imple 2024-05-0 / Procurement of Civil Works IDA / 69250 Post Request for Bids Open - National 1 Envelope proce 7,600,000.00 0.00 2023-05-04 2023-05-04 2023-05-08 2023-05-08 2023-05-29 2023-05-30 2023-06-08 2023-07-10 Infrastructure Development nvelope mentation 5 of Priority Villages (Tehsil Lia ss (Non Bank-SPD quatpur 02) ) National Procure PK-LG& CD-359421-CW-RFB ment Document - Water Supply and Sanitation Single Stage - One E Under Imple 2024-05-0 / Procurement of Civil Works IDA / 69250 Post Request for Bids Open - National 1 Envelope proce 5,200,000.00 0.00 2023-05-04 2023-05-04 2023-05-08 2023-05-08 2023-05-29 2023-05-30 2023-06-08 2023-07-10 Infrastructure Development nvelope mentation 5 of Priority Villages (Tehsil Kot ss (Non Bank-SPD Momin 02) ) National Procure PK-LG& CD-366683-CW-RFB ment Document - Water Supply and Sanitation Single Stage - One E Under Imple 2024-06-2 / Procurement of Civil Works, IDA / 69250 Post Request for Bids Open - National 1 Envelope proce 1,250,000.00 0.00 2023-06-14 2023-06-15 2023-06-18 2023-06-20 2023-07-09 2023-07-19 2023-08-30 Infrastructure Development nvelope mentation 5 Central-I, Tehsil Ahmedpur Si ss (Non Bank-SPD al (APS-01) ) National Procure PK-LG& CD-366693-CW-RFB ment Document - Water Supply and Sanitation Single Stage - One E Under Imple 2024-06-2 / Procurement of Civil Works, IDA / 69250 Post Request for Bids Open - National 1 Envelope proce 1,510,000.00 0.00 2023-06-14 2023-06-15 2023-06-18 2023-06-20 2023-07-09 2023-07-19 2023-08-30 Infrastructure Development nvelope mentation 5 Central-I, Tehsil Ahmedpur Si ss (Non Bank-SPD al (APS-02) ) National Procure PK-LG& CD-366694-CW-RFB ment Document - Water Supply and Sanitation Single Stage - One E 2024-06-2 / Procurement of Civil Works, IDA / 69250 Post Request for Bids Open - National 1 Envelope proce 2,050,000.00 0.00 Canceled 2023-06-14 2023-06-18 2023-07-09 2023-07-19 2023-08-30 Infrastructure Development nvelope 5 South-III, Tehsil Rojhan (ROJ- ss (Non Bank-SPD 01) ) National Procure PK-LG& CD-366695-CW-RFB ment Document - Water Supply and Sanitation Single Stage - One E 2024-06-2 / Procurement of Civil Works, IDA / 69250 Post Request for Bids Open - National 1 Envelope proce 600,000.00 0.00 Canceled 2023-06-14 2023-06-18 2023-07-09 2023-07-19 2023-08-30 Infrastructure Development nvelope 5 South-III, Tehsil Rojhan (ROJ- ss (Non Bank-SPD 02) ) National Procure PK-LG& CD-366696-CW-RFB ment Document - Water Supply and Sanitation Single Stage - One E Under Imple 2024-06-2 / Procurement of Civil Works, IDA / 69250 Post Request for Bids Open - National 1 Envelope proce 960,000.00 0.00 2023-06-14 2023-06-15 2023-06-18 2023-06-18 2023-07-09 2023-07-19 2023-08-30 Infrastructure Development nvelope mentation 5 South-III, Tehsil Rojhan (ROJ- ss (Non Bank-SPD 03) ) National Procure PK-LG& CD-366697-CW-RFB ment Document - Water Supply and Sanitation Single Stage - One E Pending Imp 2024-06-2 / Procurement of Civil Works, IDA / 69250 Post Request for Bids Open - National 1 Envelope proce 1,360,000.00 0.00 2023-06-14 2023-06-18 2023-07-09 2023-07-19 2023-08-30 Infrastructure Development nvelope lementation 5 South-III, Tehsil Liaquatpur (L ss (Non Bank-SPD QR-01) ) Page 1 National Procure PK-LG& CD-366698-CW-RFB ment Document - Water Supply and Sanitation Single Stage - One E Pending Imp 2024-06-2 / Procurement of Civil Works, IDA / 69250 Post Request for Bids Open - National 1 Envelope proce 1,500,000.00 0.00 2023-06-14 2023-06-18 2023-07-09 2023-07-19 2023-08-30 Infrastructure Development nvelope lementation 5 South-I, Tehsil Bahawalnagar ss (Non Bank-SPD (BWN-02) ) National Procure PK-LG& CD-366699-CW-RFB ment Document - Water Supply and Sanitation Single Stage - One E Pending Imp 2024-06-2 / Procurement of Civil Works, IDA / 69250 Post Request for Bids Open - National 1 Envelope proce 1,050,000.00 0.00 2023-06-14 2023-06-18 2023-07-09 2023-07-19 2023-08-30 Infrastructure Development nvelope lementation 5 South-I, Tehsil Bahawalnagar ss (Non Bank-SPD (BWN-03) ) National Procure PK-LG& CD-366701-CW-RFB ment Document - Water Supply and Sanitation Single Stage - One E Pending Imp 2024-06-2 / Procurement of Civil Works, IDA / 69250 Post Request for Bids Open - National 1 Envelope proce 1,750,000.00 0.00 2023-06-14 2023-06-18 2023-07-09 2023-07-19 2023-08-30 Infrastructure Development nvelope lementation 5 South-I, Tehsil Bahawalnagar ss (Non Bank-SPD (BWN-04) ) National Procure PK-LG& CD-366702-CW-RFB ment Document - Water Supply and Sanitation Single Stage - One E Pending Imp 2024-06-2 / Procurement of Civil Works, IDA / 69250 Post Request for Bids Open - National 1 Envelope proce 2,200,000.00 0.00 2023-06-14 2023-06-18 2023-07-09 2023-07-19 2023-08-30 Infrastructure Development nvelope lementation 5 South-I, Tehsil Bahawalnagar ss (Non Bank-SPD (BWN-05) ) National Procure PK-LG& CD-366704-CW-RFB ment Document - Water Supply and Sanitation Single Stage - One E Under Imple 2024-06-2 / Procurement of Civil Works, IDA / 69250 Post Request for Bids Open - National 1 Envelope proce 1,600,000.00 0.00 2023-06-14 2023-06-15 2023-06-18 2023-06-18 2023-07-09 2023-07-19 2023-08-30 Infrastructure Development nvelope mentation 5 South-II, Tehsil Shujaabad (SJ ss (Non Bank-SPD D-01) ) National Procure PK-LG& CD-366706-CW-RFB ment Document - Water Supply and Sanitation Single Stage - One E Under Imple 2024-06-2 / Procurement of Civil Works, IDA / 69250 Post Request for Bids Open - National 1 Envelope proce 1,700,000.00 0.00 2023-06-14 2023-06-15 2023-06-18 2023-06-18 2023-07-09 2023-07-19 2023-08-30 Infrastructure Development nvelope mentation 5 South-II, Tehsil Shujaabad (SJ ss (Non Bank-SPD D-02) ) National Procure PK-LG& CD-366707-CW-RFB ment Document - Water Supply and Sanitation Single Stage - One E Under Imple 2024-06-2 / Procurement of Civil Works, IDA / 69250 Post Request for Bids Open - National 1 Envelope proce 1,900,000.00 0.00 2023-06-14 2023-06-15 2023-06-18 2023-06-18 2023-07-09 2023-07-19 2023-08-30 Infrastructure Development nvelope mentation 5 South-II, Tehsil Shujaabad (SJ ss (Non Bank-SPD D-03) ) National Procure PK-LG& CD-366708-CW-RFB ment Document - Water Supply and Sanitation Single Stage - One E Under Imple 2024-06-2 / Procurement of Civil Works, IDA / 69250 Post Request for Bids Open - National 1 Envelope proce 1,350,000.00 0.00 2023-06-14 2023-06-15 2023-06-18 2023-06-18 2023-07-09 2023-07-19 2023-08-30 Infrastructure Development nvelope mentation 5 South-II, Tehsil Shujaabad (SJ ss (Non Bank-SPD D-04) ) National Procure PK-LG& CD-366711-CW-RFB ment Document - Water Supply and Sanitation Single Stage - One E Pending Imp 2024-06-2 / Procurement of Civil Works, IDA / 69250 Post Request for Bids Open - National 1 Envelope proce 750,000.00 0.00 2023-06-14 2023-06-18 2023-07-09 2023-07-19 2023-08-30 Infrastructure Development nvelope lementation 5 North, Tehsil Noorpur Thal (N ss (Non Bank-SPD PT-01) ) National Procure PK-LG& CD-366713-CW-RFB ment Document - Water Supply and Sanitation Single Stage - One E Under Imple 2024-06-2 / Procurement of Civil Works, IDA / 69250 Post Request for Bids Open - National 1 Envelope proce 2,850,000.00 0.00 2023-06-14 2023-06-15 2023-06-18 2023-06-18 2023-07-09 2023-07-19 2023-08-30 Infrastructure Development nvelope mentation 5 North, Tehsil Isa Khel (ISK-01 ss (Non Bank-SPD ) ) National Procure PK-LG& CD-366715-CW-RFB ment Document - Water Supply and Sanitation Single Stage - One E Under Imple 2024-06-2 / Procurement of Civil Works, IDA / 69250 Post Request for Bids Open - National 1 Envelope proce 2,150,000.00 0.00 2023-06-14 2023-06-15 2023-06-18 2023-06-18 2023-07-09 2023-07-19 2023-08-30 Infrastructure Development nvelope mentation 5 North, Tehsil Isa Khel (ISK-02 ss (Non Bank-SPD ) ) National Procure PK-LG& CD-366716-CW-RFB ment Document - Water Supply and Sanitation Single Stage - One E Under Imple 2024-06-2 / Procurement of Civil Works, IDA / 69250 Post Request for Bids Open - National 1 Envelope proce 2,250,000.00 0.00 2023-06-14 2023-06-15 2023-06-18 2023-06-18 2023-07-09 2023-07-19 2023-08-30 Infrastructure Development nvelope mentation 5 North, Tehsil Isa Khel (ISK-03 ss (Non Bank-SPD ) ) National Procure PK-LG& CD-366717-CW-RFB ment Document - Water Supply and Sanitation Single Stage - One E Under Imple 2024-06-2 / Procurement of Civil Works, IDA / 69250 Post Request for Bids Open - National 1 Envelope proce 1,900,000.00 0.00 2023-06-14 2023-06-15 2023-06-18 2023-06-18 2023-07-09 2023-07-19 2023-08-30 Infrastructure Development nvelope mentation 5 Central-II, Tehsil Pakpattan (P ss (Non Bank-SPD KN-02) ) National Procure PK-LG& CD-366718-CW-RFB ment Document - Water Supply and Sanitation Single Stage - One E Under Imple 2024-06-2 / Procurement of Civil Works, IDA / 69250 Post Request for Bids Open - National 1 Envelope proce 1,500,000.00 0.00 2023-06-14 2023-06-15 2023-06-18 2023-06-18 2023-07-09 2023-07-19 2023-08-30 Infrastructure Development nvelope mentation 5 Central-II, Tehsil Pakpattan (P ss (Non Bank-SPD KN-03) ) National Procure PK-LG& CD-366719-CW-RFB ment Document - Water Supply and Sanitation Single Stage - One E Under Imple 2024-06-2 / Procurement of Civil Works, IDA / 69250 Post Request for Bids Open - National 1 Envelope proce 1,200,000.00 0.00 2023-06-14 2023-06-15 2023-06-18 2023-06-18 2023-07-09 2023-07-19 2023-08-30 Infrastructure Development nvelope mentation 5 Central-II, Tehsil Pakpattan (P ss (Non Bank-SPD KN-04) ) National Procure PK-LG& CD-366720-CW-RFB ment Document - Water Supply and Sanitation Single Stage - One E Under Imple 2024-06-2 / Procurement of Civil Works, IDA / 69250 Post Request for Bids Open - National 1 Envelope proce 1,650,000.00 0.00 2023-06-14 2023-06-15 2023-06-18 2023-06-18 2023-07-09 2023-07-19 2023-08-30 Infrastructure Development nvelope mentation 5 Central-II, Tehsil Pakpattan (P ss (Non Bank-SPD KN-05) ) National Procure PK-LG& CD-366721-CW-RFB ment Document - Water Supply and Sanitation Single Stage - One E Under Imple 2024-06-2 / Procurement of Civil Works, IDA / 69250 Post Request for Bids Open - National 1 Envelope proce 700,000.00 0.00 2023-06-14 2023-06-15 2023-06-18 2023-06-18 2023-07-09 2023-07-19 2023-08-30 Infrastructure Development nvelope mentation 5 Central-II, Tehsil Pakpattan (P ss (Non Bank-SPD KN-06) ) National Procure PK-LG& CD-366916-CW-RFB ment Document - Water Supply and Sanitation Single Stage - One E Under Imple 2024-06-2 / Procurement of Civil Works, IDA / 69250 Post Request for Bids Open - National 1 Envelope proce 950,000.00 0.00 2023-06-15 2023-06-15 2023-06-19 2023-06-18 2023-07-10 2023-07-20 2023-08-31 Infrastructure Development nvelope mentation 6 South-III, Tehsil Rojhan (ROJ- ss (Non Bank-SPD 02) ) National Procure PK-LG& CD-366917-CW-RFB ment Document - Water Supply and Sanitation Single Stage - One E Under Imple 2024-06-2 / Procurement of Civil Works, IDA / 69250 Post Request for Bids Open - National 1 Envelope proce 2,860,000.00 0.00 2023-06-15 2023-06-15 2023-06-19 2023-06-18 2023-07-10 2023-07-20 2023-08-31 Infrastructure Development nvelope mentation 6 South-III, Tehsil Rojhan (ROJ- ss (Non Bank-SPD 01) ) GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PK-LG& CD-289353-GO-RFQ Request for Quota Single Stage - One E Pending Impl IBRD / 92670 Project Management Post Open - National 80,000.00 0.00 2022-05-07 2022-06-11 2022-09-09 / Procurement of Office Equip tions nvelope ementation ment/G PK-LG& CD-289354-GO-RFQ Request for Quota Single Stage - One E Pending Impl IBRD / 92670 Project Management Post Open - National 100,000.00 0.00 2022-05-09 2022-06-09 2022-08-08 / Procurement of Office Furni tions nvelope ementation ture /G PK-LG& CD-289355-GO-RFQ Request for Quota Single Stage - One E Pending Impl IBRD / 92670 Project Management Post Open - National 400,000.00 0.00 2022-05-13 2022-06-17 2022-12-14 / Procurement of Operational tions nvelope ementation Vehicles PK-LG& CD-289352-GO-RFB Single Stage - One E Pending Impl IBRD / 92670 Project Management Post Request for Bids Open - National 200,000.00 0.00 2022-04-29 2022-05-04 2022-05-25 2022-05-30 2022-06-13 2022-09-11 / Procurement of IT Equipme nvelope ementation nt /G PK-LG& CD-315566-GO-RFQ Service Delivery Improveme Request for Quota Single Stage - One E IBRD / 92670 Post Open - National 12,100.00 0.00 Signed 2022-09-24 2023-05-23 2022-10-09 2022-11-08 / Package-V: Chlorine Tablets nt tions nvelope PK-LG& CD-315555-GO-RFQ Service Delivery Improveme Request for Quota Single Stage - One E / Procurement of double cabi IDA / 69250 Post Open - National 110,000.00 0.00 Signed 2022-09-24 2023-05-24 2022-10-08 2022-12-07 nt tions nvelope n 4x4 vehicles PK-LG& CD-315558-GO-RFQ Service Delivery Improveme Request for Quota Single Stage - One E Pending Impl IDA / 69250 Post Open - National 85,000.00 0.00 2022-09-26 2022-10-10 2022-11-24 / Procurement of Equipment nt tions nvelope ementation Page 2 PK-LG& CD-316170-GO-DIR / Service Delivery Improveme Under Imple IDA / 69250 Post Direct Selection Direct - National 1,450,000.00 0.00 2022-09-16 2022-11-01 2022-09-21 2022-11-10 2022-09-30 2023-01-28 Procurement of Heavy Machi nt mentation nery PK-LG& CD-316171-GO-RFQ Water Supply and Sanitation Request for Quota Single Stage - One E Pending Impl / Procurement of Water Filtra IDA / 69250 Prior Open - National 2,100,000.00 0.00 2022-09-24 2022-10-09 2022-12-08 Infrastructure Development tions nvelope ementation tion Systems PK-LG& CD-316174-GO-RFQ Service Delivery Improveme Request for Quota Single Stage - One E IDA / 69250 Post Open - National 90,000.00 0.00 Signed 2022-09-27 2023-05-23 2022-10-10 2022-10-11 / Procurement of Generators nt tions nvelope PK-LG& CD-289345-GO-RFB / Design, Supply and Installat Single Stage - One E Under Imple IBRD / 92670 Project Management Prior Request for Bids Open - National 3,000,000.00 0.00 2022-09-15 2022-09-20 2022-11-01 2022-12-01 2023-01-05 2024-06-28 ion of Enterprise Resource Pl nvelope mentation anning [ERP] and Manageme nt Information System PK-LG& CD-317580-GO-RFQ / Procurement of Goods for R Request for Quota Single Stage - One E Under Imple IDA / 69250 Project Management Post Open - National 96,000.00 0.00 2022-10-29 2022-11-28 2023-03-28 enovation of PRSC Head Offic tions nvelope mentation e and Miscellaneous Item PK-LG& CD-325075-GO-RFQ Request for Quota Single Stage - One E Under Imple / procurement of Office Furni IDA / 69250 Project Management Post Open - National 85,000.00 0.00 2022-11-15 2023-05-27 2022-12-07 2023-02-05 tions nvelope mentation ture for PRMSC Tehsil Offices PK-LG& CD-325076-GO-RFQ Request for Quota Single Stage - One E Under Imple / Procurement of General Offi IDA / 69250 Project Management Post Open - National 50,000.00 0.00 2022-11-17 2023-05-27 2022-12-14 2023-01-13 tions nvelope mentation ce Equipment PK-LG& CD-325074-GO-RFQ Request for Quota Single Stage - One E Pending Impl / Procurement of Printing and IDA / 69250 Project Management Post Open - National 85,000.00 0.00 2022-11-17 2022-12-15 2022-12-24 tions nvelope ementation Miscellaneous IT Equipment PK-LG& CD-315548-GO-DIR / Service Delivery Improveme Under Imple IDA / 69250 Post Direct Selection Direct - National 1,100,000.00 0.00 2022-09-14 2022-11-01 2022-09-19 2022-11-10 2022-10-05 2022-11-19 Procurement of Sucker & Jett nt mentation er Unit PK-LG& CD-331360-GO-RFB / Procurement of Laptops & D Single Stage - One E IDA / 69250 Project Management Post Request for Bids Open - National 210,000.00 0.00 Signed 2022-12-13 2023-01-23 2022-12-16 2023-05-23 2023-01-13 2023-02-20 2023-01-14 2023-03-16 2023-02-05 2023-08-04 esktops for PRMSC Head Offi nvelope ce & Tehsil Offices PK-LG& CD-300945-GO-RFQ Request for Quota Single Stage - One E Under Imple / Office Fixtures & Portable In IBRD / 92670 Project Management Post Open - National 60,000.00 0.00 2022-06-24 2022-06-28 2022-06-30 tions nvelope mentation stallations and Miscellaneous office Items PK-LG& CD-351779-GO-RFQ Request for Quota Single Stage - One E Under Imple / Installation of Monitoring an IDA / 69250 Project Management Post Open - National 60,000.00 0.00 2023-04-06 2023-04-12 2023-05-21 2023-06-20 tions nvelope mentation d Vehicle Tracking System PK-LG& CD-359711-GO-RFB / Installation, Commissioning Water Supply and Sanitation Single Stage - One E Pending Impl and Testing for Solarization o IDA / 69250 Post Request for Bids Open - National 1,000,000.00 0.00 2023-05-10 2023-05-12 2023-06-02 2023-06-07 2023-07-03 2023-10-31 Infrastructure Development nvelope ementation f Water Supply and Sewerag e Schemes under PRSWSSP P hase-I (70 Villages) PK-LG& CD-362800-GO-RFB / Installation, Commissioning Water Supply and Sanitation Single Stage - One E Pending Impl and Testing for Solarization o IDA / 69250 Post Request for Bids Open - National 1,800,000.00 0.00 2023-05-22 2023-05-27 2023-06-17 2023-06-22 2023-07-18 2023-11-15 Infrastructure Development nvelope ementation f Water Supply and Sewerag e Schemes under PRSWSSP P hase-I (70 Villages) Part-II NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PK-LG& CD-332020-NC-DIR / Service Delivery Improveme Under Imple Water & Waste Water Quality IDA / 69250 Prior Direct Selection Direct - National 3,000,000.00 0.00 2023-03-15 2023-02-24 2023-03-20 2023-04-07 2023-04-24 2028-04-22 nt mentation Monitoring PK-LG& CD-289231-NC-RFB / Procurement of the Services Behavior Change and Capaci Single Stage - One E of Implementation Partners f IBRD / 92670 Prior Request for Bids Open - National 3,500,000.00 0.00 Canceled 2022-12-02 2022-12-07 2023-01-18 2023-02-17 2023-03-24 2028-06-30 ty Development nvelope or Behavioral Change Comm unications & Capacity Buildin g (South)/NCS PK-LG& CD-289205-NC-RFB / Procurement of the Services Behavior Change and Capaci Single Stage - One E of Implementation Partners f IBRD / 92670 Prior Request for Bids Open - National 3,500,000.00 0.00 Canceled 2022-12-02 2022-12-07 2023-01-18 2023-02-17 2023-03-24 2023-10-02 ty Development nvelope or Behavioural Change Com munications & Capacity Build ing (Central)/NCS PK-LG& CD-289107-NC-RFB / Procurement of the Services Behavior Change and Capaci Single Stage - One E of Implementation Partners f IBRD / 92670 Prior Request for Bids Open - National 3,500,000.00 0.00 Canceled 2022-12-02 2022-12-07 2023-01-18 2023-02-17 2023-03-24 2028-06-30 ty Development nvelope or Behavioural Change Com munications & Capacity Build ing (North)/NCS PK-LG& CD-316926-NC-RFB / Behavior Change and Capaci Single Stage - One E Under Imple Behavior Change and Capaci IBRD / 92670 Prior Request for Bids Open - National 3,500,000.00 0.00 2022-12-26 2023-02-26 2022-12-31 2023-03-02 2023-02-05 2023-04-07 2023-02-20 2023-05-16 2023-03-20 2025-03-19 ty Development nvelope mentation ty Development Program PK-LG& CD-332746-NC-RFB / Procurement of the Services Behavior Change and Capaci Single Stage - One E Pending Impl of Implementation Partners f IDA / 69250 Prior Request for Bids Open - National 9,000,000.00 0.00 2023-07-20 2023-07-25 2023-09-05 2023-10-05 2023-11-09 2026-11-13 ty Development nvelope ementation or Behavioral Change Comm unications & Capacity Buildin g (Multiple Lots) PK-LG& CD-332015-NC-RFB / Single Stage - One E Impact Evaluation of PRSWSS IDA / 69250 Project Management Post Request for Bids Open - National 1,200,000.00 0.00 Canceled 2023-01-26 2023-01-31 2023-02-28 2023-03-15 2023-04-06 2025-05-25 nvelope P (Baseline and Midline) CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 3 PK-LG& CD-289348-CS-QCBS Water Supply and Sanitation Quality And Cost- Pending Impleme / TPV (TPV (baseline, midline IBRD / 92670 Prior Open - National 1,500,000.00 0.00 2022-09-30 2022-10-21 2022-12-04 2023-01-01 2023-01-31 2023-03-07 2023-04-11 2028-06-30 Infrastructure Development Based Selection ntation and end line)/CS PK-LG& CD-289968-CS-CQS / Water Supply and Sanitation Consultant Qualifi Pilot Services for Engineering IBRD / 92670 Post Open - National 300,000.00 0.00 Signed 2022-04-25 2022-06-27 2022-05-16 2023-05-24 2022-06-06 2022-08-12 2022-06-13 2022-09-23 2022-07-11 2023-04-07 Infrastructure Development cation Selection , Design and Supervision Sou th PK-LG& CD-289097-CS-CQS / Water Supply and Sanitation Consultant Qualifi Pilot Services for Engineering IBRD / 92670 Post Open - National 300,000.00 0.00 Signed 2022-04-26 2022-06-27 2022-05-17 2023-05-23 2022-06-07 2022-08-01 2022-07-07 2022-10-24 2022-08-11 2023-05-08 Infrastructure Development cation Selection , Design and Supervision Cen tral /CS PK-LG& CD-289966-CS-CQS / Water Supply and Sanitation Consultant Qualifi Pilot Services for Engineering IBRD / 92670 Post Open - National 300,000.00 0.00 Signed 2022-04-18 2022-06-27 2022-05-09 2023-05-23 2022-05-30 2022-08-12 2022-06-29 2022-09-23 2022-08-03 2023-04-30 Infrastructure Development cation Selection , Design and Supervision Nor th/CS PK-LG& CD-292584-CS-CQS / Water Supply and Sanitation Consultant Qualifi Pilot Services for Engineering IBRD / 92670 Post Open - National 300,000.00 0.00 Signed 2022-05-10 2022-06-27 2022-05-31 2023-05-23 2022-06-21 2022-08-12 2022-07-21 2022-09-23 2022-08-11 2023-05-08 Infrastructure Development cation Selection , Design and Supervision Nor th- A/CS PK-LG& CD-292585-CS-CQS / Water Supply and Sanitation Consultant Qualifi Pilot Services for Engineering IBRD / 92670 Post Open - National 300,000.00 0.00 Signed 2022-05-11 2022-06-27 2022-06-01 2023-05-23 2022-06-22 2022-08-12 2022-07-22 2022-09-23 2022-08-12 2023-05-09 Infrastructure Development cation Selection , Design and Supervision Cen tral - A /CS PK-LG& CD-292587-CS-CQS / Water Supply and Sanitation Consultant Qualifi Pilot Services for Engineering IBRD / 92670 Post Open - National 300,000.00 0.00 Signed 2022-05-12 2022-06-27 2022-06-02 2023-05-23 2022-06-23 2022-08-01 2022-07-23 2022-09-23 2022-08-13 2023-05-10 Infrastructure Development cation Selection , Design and Supervision Sou th-A /CS PK-LG& CD-289349-CS-QCBS Quality And Cost- IBRD / 92670 Project Management Prior Open - National 1,000,000.00 0.00 Canceled 2022-07-05 2022-07-26 2022-09-08 2022-10-06 2022-11-05 2022-12-10 2023-01-14 2028-06-30 / Internal Audit Firm/CS Based Selection PK-LG& CD-289099-CS-CQS / Procurement of Services for Water Supply and Sanitation Consultant Qualifi IBRD / 92670 Post Open - National 300,000.00 0.00 Canceled 2022-05-06 2022-05-27 2022-06-17 2022-06-24 2022-07-08 2023-01-04 Development of Punjab BCC Infrastructure Development cation Selection WASH Strategy PK-LG& CD-333387-CS-QCBS Quality And Cost- IDA / 69250 Project Management Post Open - National 400,000.00 0.00 Canceled 2026-03-12 2026-04-02 2026-05-16 2026-06-13 2026-07-13 2026-08-17 2026-09-21 2027-09-21 / Impact Evaluation Firm/ End Based Selection line PK-LG& CD-334176-CS-CQS / Water Supply and Sanitation Consultant Qualifi Procurement for hiring of Fir IDA / 69250 Post Open - National 250,000.00 0.00 Signed 2023-01-04 2023-01-09 2023-01-19 2023-02-27 2023-02-02 2023-03-30 2023-02-09 2023-04-12 2023-02-23 2024-02-23 Infrastructure Development cation Selection m for Tariff Appraisal Study f or PRSWSSP PK-LG& CD-346557-CS-CQS / Consultant Qualifi Consultancy Services for Co IDA / 69250 Project Management Post Open - National 100,000.00 0.00 Under Review 2023-03-07 2023-06-22 2023-03-28 2023-04-11 2023-05-11 2023-05-25 2024-05-24 cation Selection mmunication/PR/Marketing of PRSWSSP PK-LG& CD-289246-CS-QCBS Water Supply and Sanitation Quality And Cost- Under Implement / Services for Engineering, D IBRD / 92670 Prior Open - National 3,500,000.00 0.00 2023-04-14 2023-05-16 2023-05-05 2023-06-17 2023-05-27 2023-06-24 2023-07-09 2023-07-31 2023-08-22 2028-08-25 Infrastructure Development Based Selection ation esign and Supervision North / CS PK-LG& CD-289251-CS-QCBS Water Supply and Sanitation Quality And Cost- Under Implement / Services for Engineering, D IBRD / 92670 Prior Open - National 3,750,000.00 0.00 2023-04-14 2023-05-16 2023-05-05 2023-06-17 2023-05-27 2023-06-24 2023-07-09 2023-07-31 2023-08-22 2028-08-23 Infrastructure Development Based Selection ation esign and Supervision Centra l /CS PK-LG& CD-289253-CS-QCBS Water Supply and Sanitation Quality And Cost- Under Implement / Services for Engineering, D IBRD / 92670 Prior Open - National 3,000,000.00 0.00 2023-04-14 2023-05-16 2023-05-05 2023-06-17 2023-05-27 2023-06-24 2023-07-09 2023-07-31 2023-08-22 2028-08-21 Infrastructure Development Based Selection ation esign and Supervision South- I /CS PK-LG& CD-353899-CS-QCBS Water Supply and Sanitation Quality And Cost- Under Implement / Services for Engineering, D IBRD / 92670 Prior Open - National 3,500,000.00 0.00 2023-04-14 2023-05-16 2023-05-05 2023-06-17 2023-05-27 2023-06-24 2023-07-09 2023-07-31 2023-08-22 2028-08-25 Infrastructure Development Based Selection ation esign and Supervision South- II /CS PK-LG& CD-353901-CS-QCBS Water Supply and Sanitation Quality And Cost- Under Implement / Services for Engineering, D IBRD / 92670 Prior Open - National 3,500,000.00 0.00 2023-04-14 2023-05-16 2023-05-05 2023-06-17 2023-05-27 2023-06-24 2023-07-09 2023-07-31 2023-08-22 2028-08-25 Infrastructure Development Based Selection ation esign and Supervision South- III /CS PK-LG& CD-359704-CS-LCS / Least Cost Selecti Consultancy Services for Imp IDA / 69250 Project Management Prior Open - National 3,600,000.00 0.00 Canceled 2023-05-10 2023-05-19 2023-05-31 2023-05-26 2023-06-17 2023-07-15 2023-07-22 2023-08-03 2023-08-31 2028-01-17 on act Evaluation of PRSWSSP PK-LG& CD-364852-CS-QCBS Quality And Cost- Under Implement IDA / 69250 Project Management Prior Open - National 3,600,000.00 0.00 2023-06-06 2023-06-09 2023-06-27 2023-06-24 2023-07-14 2023-08-11 2023-08-21 2023-09-05 2023-09-29 2028-02-15 / Impact Evaluation of PRSWS Based Selection ation SP INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PK-LG& CD-316922-CS-INDV Individual Consult IDA / 69250 Project Management Post Open - National 30,000.00 0.00 Under Review 2022-09-26 2022-09-15 2022-10-22 2022-10-29 2022-11-08 2023-11-08 / MIS System Architect ant Selection PK-LG& CD-316924-CS-INDV Individual Consult IDA / 69250 Project Management Post Open - National 25,000.00 0.00 Under Review 2022-09-27 2022-09-15 2022-10-23 2022-10-28 2022-11-07 2023-11-07 / Principal Technology Adviso ant Selection r (ERP) PK-LG& CD-289361-CS-INDV Individual Consult IBRD / 92670 Project Management Post Open 250,000.00 0.00 Canceled 2022-05-03 2022-06-07 2022-06-14 2022-06-21 2028-06-30 / Safeguard Specialist /IC ant Selection PK-LG& CD-289357-CS-INDV / Procurement Specialist /IC/ Individual Consult IBRD / 92670 Project Management Post Open 250,000.00 0.00 Canceled 2022-04-30 2022-06-04 2022-06-11 2022-06-18 2028-06-30 Sr. Procurement & Contract S ant Selection pecialist PK-LG& CD-325078-CS-INDV Individual Consult / Individual Consultant for Ba IDA / 69250 Project Management Post Open - National 20,000.00 0.00 Canceled 2022-11-16 2022-11-30 2022-12-28 2023-01-05 2023-07-04 ant Selection seline, Midline and Endline S urvey PK-LG& CD-289359-CS-INDV Individual Consult IBRD / 92670 Project Management Post Open 250,000.00 0.00 Canceled 2022-07-07 2022-08-11 2022-08-18 2022-08-25 2028-06-30 / M& E Specialist/IC ant Selection PK-LG& CD-289356-CS-INDV Individual Consult IBRD / 92670 Project Management Prior Open 300,000.00 0.00 Canceled 2022-04-30 2022-06-04 2022-06-11 2022-06-18 2028-06-30 / Project Coordinator /IC ant Selection PK-LG& CD-289360-CS-INDV Individual Consult IBRD / 92670 Project Management Post Open 250,000.00 0.00 Canceled 2022-05-10 2022-06-14 2022-06-21 2022-06-28 2028-06-30 / Environmental specialist/IC ant Selection Page 4 PK-LG& CD-289358-CS-INDV Individual Consult IBRD / 92670 Project Management Post Open 250,000.00 0.00 Canceled 2022-05-03 2022-06-07 2022-06-14 2022-06-21 2028-06-30 / Financial Management Spec ant Selection ialist /IC PK-LG& CD-332736-CS-INDV Individual Consult IDA / 69250 Project Management Post Limited 13,000.00 0.00 Signed 2022-12-23 2023-04-03 2022-12-24 2023-03-20 2022-12-26 2023-04-10 2023-01-14 2023-04-14 / Procurement Specialist ant Selection PK-LG& CD-332737-CS-INDV Individual Consult Pending Impleme IDA / 69250 Project Management Post Limited 12,000.00 0.00 2022-12-23 2022-12-25 2022-12-28 2023-01-07 2023-04-07 / Contract Management Spec ant Selection ntation ialist PK-LG& CD-332740-CS-INDV Individual Consult IDA / 69250 Project Management Post Limited 20,000.00 0.00 Signed 2022-12-25 2023-03-27 2022-12-27 2023-03-01 2023-01-17 2023-03-31 2023-02-21 2023-08-20 / Legal Expert ant Selection PK-LG& CD-362799-CS-INDV Water Supply and Sanitation Individual Consult Under Implement / Engineering Design Review IDA / 69250 Post Limited 10,000.00 0.00 2023-05-22 2023-06-20 2023-05-25 2023-05-30 2023-06-09 2023-10-07 Infrastructure Development ant Selection ation Consultant for 200 Villages Page 5 Sample Procurement Plan (Text in italic font is meant for instruction to staff and should be deleted in the final version of the PP) (This is only a sample with the minimum content that is required to be included in the PAD. The detailed procurement plan is still mandatory for disclosure on the Bank’s website in accordance with the guidelines. The initial procurement plan will cover the first 18 months of the project and then updated annually or earlier as necessary). I. General 1. Bank’s approval Date of the procurement Plan [Original: December 2007]: Revision 15 of Updated Procurement Plan, June 2010] 2. Date of General Procurement Notice: Dec 24, 2006 3. Period covered by this procurement plan: The procurement period of project covered from year June 2010 to December 2012 II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: [Thresholds for applicable procurement methods (not limited to the list below) will be determined by the Procurement Specialist /Procurement Accredited Staff based on the assessment of the implementing agency’s capacity.] Procurement Method Prior Review Comments Threshold US$ 1. ICB and LIB (Goods) Above US$ 500,000 All 2. NCB (Goods) Above US$ 100,000 First contract 3. ICB (Works) Above US$ 15 million All 4. NCB (Works) Above US$ 5 million All 5. (Non-Consultant Services) Below US$ 100,000 First contract [Add other methods if necessary] 2. Prequalification. Bidders for _Not applicable_ shall be prequalified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines. July 9, 2010 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: [Refer to the relevant CDD project implementation document approved by the Bank or delete if not applicable] 4. Reference to (if any) Project Operational/Procurement Manual: Project Implementation Manual for World Bank Loan Project XYZ 04/01/2010 issued by 5. Any Other Special Procurement Arrangements: [including advance procurement and retroactive financing, if applicable] 5 ICB works packages will be financed under retroactive financing 6. Summary of the Procurement Packages planned during the first 18 months after project effectiveness ( including those that are subject to retroactive financing and advanced procurement) [List the Packages which require Bank’s prior review first and then the other packages] 1 2 3 4 5 6 7 Ref. Descripti Estimat Packages Dome Review Comme No. on ed stic by Bank nts Cost Prefe (Prior / US$ rence Post) million (yes/ no) Summary 82 5 No Prior of the ICB (Works) Summary 43.77 15 No Prior of the ICB (Goods) Summary 64.53 18 No Post 1st of the NCB contrac (Works) t for Prior Review Summary 1.86 4 No Post 1st of the NCB contrac (Goods) t for Prior Review Summary 0.45 1 No Prior of the ICB (Non- Consultant Services) July 9, 2010 III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Comments Threshold 1. Competitive Methods (Firms) Above US$ 100,000 2. Single Source (Firms) All 3. Individual Above US$ 50,000 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_300,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: [including advance procurement and retroactive financing, if applicable or delete if not applicable] 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 Ref. No. Description Estimat Package Review Comment of ed s by Bank s Assignmen Cost (Prior / t US$ Post) million Summary 4.17 7 Prior of number of contracts that will be let under QCBS Summary 0.83 1 Prior CQS of number of contracts that will be let under other July 9, 2010 methods July 9, 2010 PROCUREMENT Tanzania : Citizen-Centric Judicial Modernization and Justice Service Delivery PLAN General Information Country: Tanzania 2016-08-05 Bank’s Approval Date of the Original Procurement Plan: 2023-06-02 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P155759 GPN Date: 2022-06-09 Project Name: Citizen-Centric Judicial Modernization and Justice Service Delivery Loan / Credit No: IDA / 57780, IDA / 70580 Judiciary of Tanzania Executing Agency(ies): WORKS Activity Reference No. / Procureme Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH Ri Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method nt Docume ount (US$ and Recommendation Signed Contract o. h cess (Y/N) sk atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion nt Type ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TZ-JUDICIARY TZ-18206-CW- Component 2: Skills Develop DIR / Construction of training 2018-03-0 2020-01 IDA / 57780 ment, Inspection and Perfor Prior Direct Selection Direct 35,175.53 Completed 2017-07-14 2017-06-29 2017-07-19 2017-08-22 2017-09-06 2017-08-24 room at Kisutu Residence Ma 5 -22 mance Management gistrate Court location in Dar es Salaam TZ-JUDICIARY TZ-118965-C W-RFB / Construction of Integ rated Justice Centers (IJCs) in Component 3: Access to Just Open - Internationa Single Stage - One E 22,309,086. 2020-04-1 IDA / 57780 Prior Request for Bids Signed 2019-06-28 2019-07-31 2019-07-03 2019-08-01 2019-08-14 2019-09-20 2019-09-13 2019-12-04 2019-10-18 2020-01-11 Six Selected Locations of Mw ice and Public Trust l nvelope 76 5 anza, Morogoro, Arusha, Dod oma and Dar es Salaam-Six L ots TZ-JUDICIARY TZ-211158-C W-RFB / Construction of Subo Component 3: Access to Just Single Stage - One E 7,950,439.8 2021-09-0 IDA / 57780 Prior Request for Bids Open - National Signed 2020-12-28 2021-02-04 2021-01-04 2021-02-11 2021-02-08 2021-03-23 2021-02-28 2021-08-24 2021-04-04 2021-09-11 rdinate Courts in twenty five( ice and Public Trust nvelope 1 1 25) Selected Locations aroun d Tanzania. TZ-JUDICIARY TZ-364564-C Request for B W-RFB / Construction of Integ ids - Small W Component 3: Access to Just Open - Internationa Single Stage - One E Under Revie 2024-06-1 rated Justice Centers (IJCs) in IDA / 70580 Prior Request for Bids orks SPD (1 e 0.00 2023-06-06 2023-06-11 2023-07-23 2023-08-22 2023-09-12 ice and Public Trust l nvelope w 3 Four Selected Locations of Si nvelope proc ngida, Simiyu, Geita and Pem ess) ba-Four Lots TZ-JUDICIARY TZ-364566-C Request for B W-RFB / Construction of Integ ids - Small W Component 3: Access to Just Open - Internationa Single Stage - One E Under Revie 2024-06-1 rated Justice Centers (IJCs) in IDA / 70580 Prior Request for Bids orks SPD (1 e 0.00 2023-06-06 2023-06-11 2023-07-23 2023-08-22 2023-09-12 ice and Public Trust l nvelope w 3 Five Selected Locations of Ka nvelope proc tavi, Songwe, Njombe, Mtwar ess) a and Songea-Five Lots TZ-JUDICIARY TZ-364568-C Request for B W-RFB / Construction of Integ ids - Small W Component 3: Access to Just Open - Internationa Single Stage - One E Under Revie 2024-06-1 rated Justice Centers (IJCs) in IDA / 70580 Prior Request for Bids orks SPD (1 e 0.00 2023-06-06 2023-06-11 2023-07-23 2023-08-22 2023-09-12 ice and Public Trust l nvelope w 3 Five Selected Locations of Pw nvelope proc ani, Tanga, Moshi, Manyara a ess) nd Lindi-Five Lots TZ-JUDICIARY TZ-9217-CW-D IR / Construction of ten (10) c Component 3: Access to Just 2017-11-1 ourthouses for subordinate c IDA / 57780 Prior Direct Selection Direct 0.00 Canceled 2017-04-10 2017-04-15 2017-05-20 ice and Public Trust 6 ourts Primary Court and Trai ning room at Kisutu RMs Cou rt. GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TZ-JUDICIARY TZ-4371-GO-R Component 1: Governance, Request for Quota Single Stage - One E FQ / Design, Editing and Print IDA / 57780 Organization and Systems D Post Limited 40,909.50 Completed 2016-12-18 2016-12-05 2017-02-12 2017-01-24 2017-08-11 2017-02-08 tions nvelope ing of Strategic plan, Brochur evelopment es TZ-JUDICIARY TZ-9220-GO-R Component 1: Governance, Single Stage - One E FB / Supply of IT Equipment f IDA / 57780 Organization and Systems D Prior Request for Bids Open - National 0.00 Canceled 2017-07-15 2017-07-20 2017-08-31 2017-09-30 2017-11-04 2018-05-03 nvelope or registries & DJSIE evelopment TZ-JUDICIARY TZ-30083-GO- Component 2: Skills Develop RFQ / Procurement of office f Request for Quota Single Stage - One E IDA / 57780 ment, Inspection and Perfor Post Limited 32,612.45 Completed 2017-09-30 2017-10-04 2017-11-05 2017-11-25 2018-05-04 2018-01-23 acilities for training center at tions nvelope mance Management Kisutu Resident Magistrate C ourt-Dar es salaam TZ-JUDICIARY TZ-30400-GO- RFQ / Procurement of office v Component 2: Skills Develop Request for Quota Single Stage - One E ideo conference facilities for IDA / 57780 ment, Inspection and Perfor Post Limited 83,134.05 Completed 2017-10-03 2017-10-05 2017-11-28 2017-10-31 2018-05-27 2018-04-16 tions nvelope training center at Kisutu resi mance Management dent magistrate court-Dar es salaam. TZ-JUDICIARY TZ-30103-GO- Component 2: Skills Develop RFQ / Procurement of IT equi Request for Quota Single Stage - One E IDA / 57780 ment, Inspection and Perfor Post Limited 77,394.71 Completed 2017-10-04 2017-10-12 2017-11-09 2017-11-14 2018-05-08 2018-05-16 pment for training center at tions nvelope mance Management Kisutu Resident Magistrate C ourt- Dar es Salaam. TZ-JUDICIARY TZ-37777-GO- RFQ / Supply, Installation and Component 1: Governance, Commissioning of Furniture, Request for Quota Single Stage - One E IDA / 57780 Organization and Systems D Post Limited 91,246.04 Completed 2017-11-27 2017-11-28 2018-01-08 2018-01-19 2018-02-05 2018-04-06 LAN, CCTV camera and Bio-m tions nvelope evelopment etric Door Access System for Retooling of Judiciary Deliver y Unit Office. TZ-JUDICIARY TZ-40300-GO- RFB / Supply, Installation, Te Component 1: Governance, st and Commissioning of Vid Single Stage - One E IDA / 57780 Organization and Systems D Post Request for Bids Open - National 594,512.13 Completed 2017-12-21 2018-01-11 2017-12-26 2018-01-25 2018-02-09 2018-02-24 2018-03-21 2018-03-31 2018-05-15 2018-09-27 2019-06-18 eo Conferencing facilities, Au nvelope evelopment dio Visual and Recording equ ipment at four selected Court s TZ-JUDICIARY TZ-64942-GO- Component 1: Governance, Request for Quota Single Stage - One E RFQ / Procurement of ICT eq IDA / 57780 Organization and Systems D Post Limited 95,937.33 Completed 2018-06-16 2018-06-14 2018-08-11 2018-08-07 2019-02-07 2018-09-21 tions nvelope uipment for new directorates evelopment TZ-JUDICIARY TZ-64971-GO- Component 1: Governance, Request for Quota Single Stage - One E RFQ / Procurement of furnitur IDA / 57780 Organization and Systems D Post Limited 71,421.54 Completed 2018-06-16 2018-06-14 2018-08-11 2018-07-17 2019-02-07 2018-11-23 tions nvelope e for new directorates evelopment Page 1 TZ-JUDICIARY TZ-67572-GO- Component 3: Access to Just Single Stage - One E RFB / Procurement of furnitur IDA / 57780 Prior Request for Bids Open - National 1,785,846.11 Completed 2018-07-25 2019-01-09 2018-07-30 2019-01-29 2018-09-10 2019-02-28 2018-10-10 2019-05-15 2018-11-14 2019-07-02 2019-05-13 2023-02-18 ice and Public Trust nvelope e for eighteen (18) new court buildings. TZ-JUDICIARY TZ-87170-GO- Component 2: Skills Develop UN Agencies (Dire UN / Procurement of 57 moto IDA / 57780 ment, Inspection and Perfor Prior Direct 1,701,529.79 Completed 2018-11-30 2018-12-05 2019-01-16 2019-01-28 2019-07-15 2019-06-30 ct) r vehicles mance Management TZ-JUDICIARY TZ-62259-GO- Component 2: Skills Develop Open - Internationa Single Stage - One E RFB / Procurement of 57 mot IDA / 57780 ment, Inspection and Perfor Prior Request for Bids 0.00 Canceled 2018-06-01 2018-06-06 2018-07-18 2018-08-17 2018-09-21 2019-03-20 l nvelope or vehicles mance Management TZ-JUDICIARY TZ-91934-GO- RFB / Supply, Installation, Te sting and Commissioning of L Component 3: Access to Just Single Stage - One E ocal Area Network and other IDA / 57780 Post Request for Bids Open - National 592,972.08 Completed 2018-12-28 2019-04-25 2019-01-02 2019-01-30 2019-07-12 2019-03-01 2019-08-19 2019-04-05 2019-11-20 2019-10-02 2020-07-26 ice and Public Trust nvelope ICT equipment for Moderniza tion of ICT Infrastructure to T wenty Three (23) New Court s Buildings. TZ-JUDICIARY TZ-107689-GO -DIR / SUPPLY AND INSTALLA TION OF NETWORK/FIBER CO Component 1: Governance, NNECTIVITY AND PROVISION IDA / 57780 Organization and Systems D Prior Direct Selection Direct 1,814,257.31 Signed 2019-04-01 2019-04-24 2019-04-06 2019-05-22 2019-05-11 2019-07-29 2019-11-07 OF DATA AND INTERNET SER evelopment VICES TO HIGH COURTS, REG IONAL MAGISTRATES AND DI STRICT COURTS BUILDINGS C OUNTRYWIDE. TZ-JUDICIARY TZ-110239-GO Component 2: Skills Develop -RFQ / PROCUREMENT OF PR Request for Quota Single Stage - One E IDA / 57780 ment, Inspection and Perfor Post Limited 42,683.08 Completed 2019-04-20 2019-05-02 2019-06-15 2019-06-17 2019-12-12 2019-10-28 OTECTIVE ACCESSORIES FOR tions nvelope mance Management THE 57 PROCURED MOTOR V EHICLES. TZ-JUDICIARY TZ-113691-GO Component 1: Governance, -RFB / Procurement of Gadge Single Stage - One E IDA / 57780 Organization and Systems D Post Request for Bids Open - National 219,227.79 Completed 2019-05-10 2019-05-10 2019-05-15 2019-06-26 2019-06-14 2019-07-26 2019-07-23 2019-08-30 2019-08-02 2020-02-26 2020-01-30 ts (POS) for utilization of GeP nvelope evelopment G government system TZ-JUDICIARY TZ-118395-GO Component 1: Governance, -RFQ / Procurement of Stand Request for Quota Single Stage - One E IDA / 57780 Organization and Systems D Post Limited 26,526.32 Completed 2019-06-26 2019-06-20 2019-08-21 2019-09-24 2020-02-17 2020-01-19 by Generator for High Court- tions nvelope evelopment Commercial Division TZ-JUDICIARY TZ-120930-GO Component 2: Skills Develop -RFQ / Procurement of ICT eq Request for Quota Single Stage - One E IDA / 57780 ment, Inspection and Perfor Post Limited 22,480.99 Completed 2019-07-06 2019-07-22 2019-08-31 2019-08-30 2020-02-27 2019-10-31 uipment and furniture for Co tions nvelope mance Management urt brokers and advocate sec tion TZ-JUDICIARY TZ-144324-GO Component 3: Access to Just Request for Quota Single Stage - One E -RFQ / PROCUREMENT OF ICT IDA / 57780 Post Limited 8,221.98 Completed 2019-11-19 2019-12-06 2020-01-14 2020-04-01 2020-07-12 2020-06-25 ice and Public Trust tions nvelope EQUIPMENT FOR LEGAL AID UNIT - MOCLA TZ-JUDICIARY TZ-159885-GO Component 1: Governance, -UN / Procurement of ICT equ UN Agencies (Dire IDA / 57780 Organization and Systems D Prior Direct 1,370,192.72 Completed 2020-02-25 2020-05-18 2020-03-01 2020-05-19 2020-04-19 2020-05-16 2020-10-16 2020-10-13 pment for registries, Court of ct) evelopment Appeal and centres. TZ-JUDICIARY TZ-168252-GO Component 1: Governance, -DIR / Supply of ICT equipme IDA / 57780 Organization and Systems D Post Direct Selection Direct 268,181.31 Completed 2020-04-15 2020-04-15 2020-04-17 2020-04-15 2020-04-20 2020-04-18 2020-04-25 2021-05-09 nt to facilitate e-court service evelopment s as a response measures ag ainst COVID-19 TZ-JUDICIARY TZ-178077-GO -RFB / Procurement of furnitu Component 3: Access to Just Single Stage - One E re for six Integrated Justice C IDA / 57780 Prior Request for Bids Open - National 3,069,984.39 Completed 2020-06-26 2020-06-29 2020-07-01 2020-06-30 2020-08-12 2020-07-28 2020-09-11 2020-08-20 2020-10-16 2020-10-28 2021-04-14 2021-12-18 ice and Public Trust nvelope enters located in Mwanza, Ar usha,Morogoro,Dodoma, Tem eke and Kinondoni. TZ-JUDICIARY TZ-180768-GO -RFB / SUPPLY, INSTALLATIO N AND CONFIGURATION OF Component 1: Governance, Single Stage - One E MICROSOFT OFFICE PROFESS IDA / 57780 Organization and Systems D Post Request for Bids Open - National 650,286.94 Completed 2020-06-26 2020-07-16 2020-07-01 2020-07-17 2020-07-22 2020-08-03 2020-07-29 2020-09-01 2020-08-10 2020-11-21 2020-09-07 2020-12-24 nvelope IONAL 2019 FOR 1388 LAPTO evelopment PS AND 14 DESKTOPS FOR M AGISTRATES AND COURT OF APPEAL REGISTRIES TZ-JUDICIARY TZ-180771-GO -RFQ / PROCUREMENT OF SC Component 3: Access to Just Request for Quota Single Stage - One E ANNERS FOR TWO INTERGRA IDA / 57780 Post Limited 27,451.65 Completed 2020-08-04 2020-06-25 2020-09-13 2020-12-05 2020-09-22 2021-05-20 ice and Public Trust tions nvelope TED JUSTICE CENTRES (IJCS) LOCATED IN MOROGORO AN D TEMEKE DAR ES SALAAM. TZ-JUDICIARY TZ-180773-GO -UN / PROCUREMENT OF ICT Component 3: Access to Just UN Agencies (Dire EQUIPMENT FOR TWO INTER IDA / 57780 Post Direct 27,451.65 Completed 2020-07-01 2020-07-21 2020-07-06 2020-07-22 2020-08-10 2020-12-05 2020-12-08 2021-09-15 ice and Public Trust ct) GRATED JUSTICE CENTRES (IJ CS) LOCATED IN MOROGORO AND TEMEKE DAR ES SALAA M. TZ-JUDICIARY TZ-182131-GO Component 1: Governance, -RFQ / Supply and Installation Request for Quota Single Stage - One E IDA / 57780 Organization and Systems D Post Limited 4,764.07 Completed 2020-07-03 2020-07-08 2020-07-10 2020-08-23 2021-01-06 2020-10-27 of plumbing materials and fit tions nvelope evelopment tings at new JDU Offices-Haki House TZ-JUDICIARY TZ-182133-GO Component 1: Governance, -RFQ / Supply and Installation Request for Quota Single Stage - One E IDA / 57780 Organization and Systems D Post Limited 7,534.44 Completed 2020-07-02 2020-07-08 2020-07-10 2020-08-29 2021-01-06 2020-09-01 of LAN,CCTV, security door s tions nvelope evelopment ystem and telephones at JDU offices-Haki House TZ-JUDICIARY TZ-182134-GO -RFQ / Supply and installation Component 1: Governance, of office partitioning material Request for Quota Single Stage - One E IDA / 57780 Organization and Systems D Post Limited 51,159.33 Completed 2020-07-02 2020-07-09 2020-07-10 2020-10-03 2021-01-06 2021-01-26 s and dismantal , packing an tions nvelope evelopment d re-instllation of Office facilit ies from Rita tower and PPF T ower to HAKI House. TZ-JUDICIARY TZ-182136-GO Component 1: Governance, Request for Quota Single Stage - One E -RFQ / Supply and Installation IDA / 57780 Organization and Systems D Post Limited 9,799.74 Completed 2020-07-02 2020-07-08 2020-07-10 2020-08-20 2021-01-06 2020-12-01 tions nvelope of Air Conditions at JDU Offic evelopment es -Haki House TZ-JUDICIARY TZ-188551-GO -RFQ / Supply, Installation, te Component 3: Access to Just Request for Quota Single Stage - One E sting and comissioning of LA IDA / 57780 Post Limited 23,461.52 Completed 2020-08-26 2020-08-23 2020-10-02 2020-11-17 2020-12-01 2021-04-15 ice and Public Trust tions nvelope N at Office of Attorney Gene ral in Dar es Salaam and Dod oma. Page 2 TZ-JUDICIARY TZ-211164-GO Component 1: Governance, Request for Quota Single Stage - One E -RFQ / Procurement of ICT Fa IDA / 57780 Organization and Systems D Post Limited 21,195.18 Completed 2021-01-02 2020-12-31 2021-02-03 2021-03-18 2021-04-04 2021-06-25 tions nvelope cilities for Kigamboni " Paper evelopment less Court" TZ-JUDICIARY TZ-221783-GO -RFB / Procurement of ICT eq Component 3: Access to Just Single Stage - One E uipment for Six Integrated Ju IDA / 57780 Post Request for Bids Open - National 560,528.31 Completed 2021-03-01 2021-08-04 2021-03-06 2021-08-04 2021-04-05 2021-08-27 2021-04-30 2020-08-30 2021-05-24 2021-09-22 2021-09-21 2021-12-08 ice and Public Trust nvelope stice Centers(IJCs) in Arusha, Mwanza, Dodoma, Morogoro, Kinondoni, and Temeke. TZ-JUDICIARY TZ-260890-GO -RFB / Procurement of furnitu re for eighteen(18) Subordin ate Courts located at Kaliua, Component 3: Access to Just Single Stage - One E IDA / 57780 Post Request for Bids Open - National 0.00 Canceled 2021-11-12 2021-11-29 2021-11-17 2021-11-29 2021-12-15 2021-12-20 2021-12-29 2021-12-27 2022-01-12 2022-05-12 Uvinza, Buhigwe, Kakonko, B ice and Public Trust nvelope utiama, Rorya, Itilima, Buseg a, Songwe, Tanganyika, Mbo gwe, Nyang’wale , Kyerwa, M isenyi, Gairo, Mvomero, Kilo mbero and Mkinga. TZ-JUDICIARY TZ-260892-GO -RFB / Supply, Installation, Te st and Commissioning of ICT equipment for eighteen(18) S Component 3: Access to Just Single Stage - One E ubordinate Courts located at IDA / 57780 Post Request for Bids Open - National 659,497.68 Completed 2021-11-12 2021-11-29 2021-11-17 2021-11-29 2021-12-15 2021-12-20 2021-12-29 2021-12-20 2022-01-12 2022-03-12 2022-05-12 2022-10-19 ice and Public Trust nvelope Kaliua, Uvinza, Buhigwe, Kak onko, Butiama, Rorya, Itilima , Busega, Songwe, Tanganyik a, Mbogwe, Nyang’wale , Kye rwa, Misenyi, Gairo, Mvomer o, Kilom TZ-JUDICIARY TZ-271298-GO -RFB / PROCUREMENT OF FU RNITURE FOR EIGHTEEN(18) SUBORDINATE COURTS LOCA TED AT KALIUA, UVINZA, BUH Component 3: Access to Just Single Stage - One E IDA / 57780 Post Request for Bids Open - National 1,257,889.98 Signed 2022-01-03 2022-01-05 2022-01-05 2022-01-05 2022-01-26 2022-01-26 2022-02-02 2022-02-07 2022-02-16 2022-05-07 2022-05-17 IGWE, KAKONKO, BUTIAMA, R ice and Public Trust nvelope ORYA, ITILIMA, BUSEGA, SON GWE, TANGANYIKA, MBOGW E, NYANG’WALE , KYERWA, M ISENYI, GAIRO, MVOMERO, KI LOMBERO AND MKINGA-(RE ADVERTISED) TZ-JUDICIARY TZ-293025-GO Component 3: Access to Just Single Stage - One E -RFB / Procurement of ICT eq IDA / 57780 Post Request for Bids Open - National 0.00 Canceled 2022-05-04 2022-05-09 2022-06-06 2022-06-16 2022-06-30 2022-08-29 ice and Public Trust nvelope uipment for Judiciary Media C enter TZ-JUDICIARY TZ-295320-GO Component 1: Governance, -DIR / Procurement of 18 Mot Under Imple IDA / 57780 Organization and Systems D Post Direct Selection Direct 0.00 2022-05-27 2022-08-03 2022-06-01 2022-08-03 2022-06-29 2022-12-01 or vehicles to support IJCs an mentation evelopment d project operations. TZ-JUDICIARY TZ-295322-GO Component 3: Access to Just Single Stage - One E -RFB / Procurement of ICT eq IDA / 57780 Post Request for Bids Limited 393,494.83 Completed 2022-05-16 2022-05-09 2022-05-17 2022-05-10 2022-05-31 2022-05-21 2022-06-02 2022-06-02 2022-06-11 2022-06-24 2022-06-25 2022-12-11 ice and Public Trust nvelope uipment for Judiciary Media C enter TZ-JUDICIARY TZ-320431-GO Component 1: Governance, -RFQ / Procurement of Archiv Request for Quota Single Stage - One E Under Imple IDA / 57780 Organization and Systems D Post Limited 0.00 2022-10-29 2022-12-29 2022-12-24 2023-06-22 e Boxes, File Cover and Stati tions nvelope mentation evelopment onery for Decongestion Exerc ise TZ-JUDICIARY TZ-320580-GO Component 1: Governance, -DIR / PROCUREMENT OF 83 Direct - Internation IDA / 57780 Organization and Systems D Prior Direct Selection 0.00 Signed 2022-11-30 2023-01-24 2022-12-05 2023-02-01 2023-01-09 2023-03-24 2023-07-08 MOTOR VEHICLES TO SUPPO al evelopment RT THE JUDICIAL REFORM AG ENDA TZ-JUDICIARY TZ-322583-GO -RFB / PROCUREMENT OF ICT Component 1: Governance, Single Stage - One E Under Imple EQUIPMENT FOR THE ATTOR IDA / 57780 Organization and Systems D Post Request for Bids Open - National 0.00 2022-11-11 2022-11-28 2022-11-16 2022-12-22 2022-12-19 2022-12-29 2023-01-23 2023-01-31 2023-05-31 nvelope mentation NEY GENERAL'S OFFICE & DI evelopment GITIZATION OF COURT RECO RDS. TZ-JUDICIARY TZ-320428-GO Component 3: Access to Just Single Stage - One E Under Imple -RFB / Procurement of Six Mo IDA / 57780 Prior Request for Bids Open - National 0.00 2022-11-11 2023-02-03 2022-11-16 2023-02-08 2022-12-22 2023-03-31 2022-12-27 2023-06-01 2023-01-15 2023-11-11 ice and Public Trust nvelope mentation bile Court Vehicles TZ-JUDICIARY TZ-330899-GO -RFB / Supply, installation, te Component 1: Governance, Single Stage - One E Under Imple st, configuration and Commis IDA / 70580 Organization and Systems D Post Request for Bids Open - National 0.00 2023-01-06 2023-01-30 2023-01-16 2023-01-31 2023-02-21 2023-03-10 2023-03-07 2023-03-25 2023-03-28 2023-07-26 nvelope mentation sioning of audio virtual recor evelopment ding equipment for eight IJCs and three high court centers. TZ-JUDICIARY TZ-338611-GO -RFB / Supply, installation , c Component 1: Governance, Single Stage - One E Under Imple onfiguration, testing and com IDA / 70580 Organization and Systems D Post Request for Bids Open - National 0.00 2023-02-10 2023-02-15 2023-02-15 2023-02-15 2023-03-23 2023-03-16 2023-04-22 2023-03-17 2023-05-27 2023-08-25 nvelope mentation missioning of ICT equipment evelopment for establishment of Judiciary Virtual Situation Room. TZ-JUDICIARY TZ-340099-GO -RFB / Procurement of heavy Component 1: Governance, Single Stage - One E Under Imple duty scanners and other ICT IDA / 70580 Organization and Systems D Post Request for Bids Open - National 0.00 2023-03-08 2023-02-08 2023-03-17 2023-02-08 2023-04-22 2023-03-02 2023-05-22 2023-03-06 2023-06-26 2023-09-24 nvelope mentation equipment for digitization of evelopment court records and supporting JDU's procurement functions. TZ-JUDICIARY TZ-347075-GO -RFB / Supply, Installation, te sting, and commissioning of Component 3: Access to Just Single Stage - One E Under Imple Video Conferencing facilities IDA / 70580 Post Request for Bids Open - National 0.00 2023-03-14 2023-04-14 2023-03-19 2023-04-14 2023-04-30 2023-05-15 2023-05-30 2023-05-24 2023-07-04 2023-10-02 ice and Public Trust nvelope mentation for Prisons and other ICT facil ities to capacitate the estate management unit of the Judi ciary of Tanzania. TZ-JUDICIARY TZ-359592-GO Component 1: Governance, Request for Quota Single Stage - One E Under Imple -RFQ / Supply of protective a IDA / 57780 Organization and Systems D Post Limited 0.00 2023-05-15 2023-05-09 2023-06-15 2023-07-15 tions nvelope mentation ccessories for 18 motor vehic evelopment les. TZ-JUDICIARY TZ-364570-GO Component 1: Governance, -RFQ / Procurement of ICT eq Request for Quota Single Stage - One E Under Imple IDA / 70580 Organization and Systems D Post Limited 0.00 2023-06-11 2023-08-06 2024-02-02 uipment to support the imple tions nvelope mentation evelopment mentation and oversight of t he project. TZ-JUDICIARY TZ-9233-GO-R Component 2: Skills Develop FQ / Procurement of Furnitur Request for Quota Single Stage - One E IDA / 57780 ment, Inspection and Perfor Post Limited 58,108.56 Completed 2017-07-03 2017-11-10 2017-08-28 2017-12-14 2018-02-24 2018-04-05 e for training rooms at High tions nvelope mance Management Court DSM & Kisutu RMs Cou rt Page 3 TZ-JUDICIARY TZ-9227-GO-R FB / Supply, installation and c Component 1: Governance, Single Stage - One E ommission of Video Conferen IDA / 57780 Organization and Systems D Prior Request for Bids Open - National 0.00 Canceled 2017-05-22 2017-09-11 2017-05-27 2017-07-08 2017-08-07 2017-09-11 2018-03-10 nvelope cing Equipment, audio visual evelopment and recording equipment for four selected courts. TZ-JUDICIARY TZ-9218-GO-R Component 3: Access to Just Single Stage - One E FB / Supply of Two (2) Mobile IDA / 57780 Prior Request for Bids Open - National 415,669.47 Completed 2017-04-13 2017-10-09 2017-04-18 2017-05-30 2017-11-15 2017-06-29 2017-12-22 2017-08-03 2018-01-19 2018-01-30 2019-02-01 ice and Public Trust nvelope Courts Van TZ-JUDICIARY TZ-9356-GO-R Component 1: Governance, FB / Procurement of IT hardw Single Stage - One E IDA / 57780 Organization and Systems D Post Request for Bids Open - National 235,523.50 Completed 2017-03-09 2017-01-26 2017-03-14 2017-04-25 2017-02-16 2017-05-25 2017-04-22 2017-06-29 2017-03-23 2017-12-26 2017-09-15 are and general software for nvelope evelopment Integrated Justice Centre at Mbeya. TZ-JUDICIARY TZ-585-GO-RF Component 1: Governance, Request for Quota Single Stage - One E Q / Supply of office consuma IDA / 57780 Organization and Systems D Post Limited 27,167.14 Completed 2016-08-17 2016-08-17 2016-10-12 2016-10-07 2017-04-10 2016-11-08 tions nvelope bles evelopment TZ-JUDICIARY TZ-9382-GO-R Component 3: Access to Just Request for Quota Single Stage - One E FQ / Supply of Documentary IDA / 57780 Post Limited 11,233.54 Completed 2017-03-21 2017-02-02 2017-05-16 2017-01-28 2017-11-12 2017-05-02 ice and Public Trust tions nvelope about information on Judiciar y constructions. TZ-JUDICIARY TZ-9361-GO-R FB / Procurement of furniture Component 3: Access to Just Single Stage - One E IDA / 57780 Post Request for Bids Open - National 0.00 Canceled 2017-06-13 2017-06-18 2017-07-30 2017-08-29 2017-10-03 2018-04-01 for registries & Mbeya Integr ice and Public Trust nvelope ated Justice Centre. TZ-JUDICIARY TZ-9237-GO-R Component 1: Governance, FB / Procurement of training I Single Stage - One E IDA / 57780 Organization and Systems D Post Request for Bids Open - National 0.00 Canceled 2017-03-28 2017-04-02 2017-05-14 2017-06-13 2017-07-18 2018-01-14 T facilities for High Court DS nvelope evelopment M & Kisutu RMs Court. TZ-JUDICIARY TZ-9364-GO-R Component 1: Governance, FQ / Procurement of IT hardw Request for Quota Single Stage - One E IDA / 57780 Organization and Systems D Post Limited 78,159.26 Completed 2017-03-20 2017-03-22 2017-05-15 2017-05-04 2017-11-11 2017-06-30 are and general software for tions nvelope evelopment a medium size Integrated Jus tice Centre at Kibaha TZ-JUDICIARY TZ-9239-GO-R FB / Procurement of standb Component 3: Access to Just Single Stage - One E IDA / 57780 Post Request for Bids Open - National 133,805.01 Completed 2017-04-28 2017-08-02 2017-05-03 2017-06-14 2017-09-19 2017-07-14 2017-10-03 2017-08-18 2017-11-23 2018-02-14 2018-06-19 y generators for High Court ice and Public Trust nvelope DSM, JDU & Kisutu RMs Court TZ-JUDICIARY TZ-9222-GO-R Component 1: Governance, Single Stage - One E FB / Installation and partition IDA / 57780 Organization and Systems D Prior Request for Bids Open - National 0.00 Canceled 2017-04-26 2017-05-01 2017-06-12 2017-07-12 2017-08-16 2018-02-12 nvelope of pre fabrication storage for evelopment selected courts. TZ-JUDICIARY TZ-9389-GO-R Component 1: Governance, FB / Supply of LAN materials, Single Stage - One E IDA / 57780 Organization and Systems D Prior Request for Bids Open - National 0.00 Canceled 2017-11-08 2017-11-13 2017-12-25 2018-01-24 2018-02-28 2018-08-27 installation and commission i nvelope evelopment n High courts, Resident and d istrict courts. NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TZ-JUDICIARY TZ-39836-NC- RFB / Provision of Service for Component 3: Access to Just Single Stage - One E Design, Editing and Printing IDA / 57780 Prior Request for Bids Open - National 0.00 Canceled 2017-12-15 2017-12-08 2017-12-20 2018-01-17 2018-01-15 2018-02-16 2018-03-05 2018-03-23 2018-09-19 ice and Public Trust nvelope of Various Legal Documents under Framework Contract. TZ-JUDICIARY TZ-52317-NC- RFQ / Provision of event man Component 3: Access to Just Request for Quota Single Stage - One E IDA / 57780 Post Limited 93,400.36 Completed 2018-03-13 2018-03-23 2018-05-08 2018-05-02 2018-11-04 2018-06-11 agement, documentary and li ice and Public Trust tions nvelope ve coverage services for law week. TZ-JUDICIARY TZ-55449-NC- RFQ / Production of awarenes Component 3: Access to Just Request for Quota Single Stage - One E IDA / 57780 Post Limited 53,002.21 Completed 2018-04-01 2018-03-19 2018-05-27 2018-05-03 2018-11-23 2018-05-18 s program of ongoing judiciar ice and Public Trust tions nvelope y reforms to the public. TZ-JUDICIARY TZ-67402-NC- RFQ / Provision of event man Component 3: Access to Just Request for Quota Single Stage - One E agement service and printing IDA / 57780 Post Limited 19,723.02 Completed 2018-06-25 2018-06-22 2018-07-07 2018-07-13 2019-01-03 2018-07-23 ice and Public Trust tions nvelope of various exhibition material s for sabasaba 2018. TZ-JUDICIARY TZ-91933-NC- RFQ / Provision of Event Man Component 3: Access to Just Request for Quota Single Stage - One E IDA / 57780 Post Limited 97,646.03 Completed 2018-12-22 2019-01-03 2019-01-27 2019-01-29 2019-07-26 2019-03-28 agement and Printing Service ice and Public Trust tions nvelope s for Law Week 2019. TZ-JUDICIARY TZ-122947-NC -RFQ / Provision of event ma Component 3: Access to Just Request for Quota Single Stage - One E IDA / 57780 Post Limited 23,220.09 Completed 2019-07-21 2019-06-03 2019-08-10 2019-06-25 2019-08-24 2019-12-03 nagement service and printin ice and Public Trust tions nvelope g of various exhibition materi als TZ-JUDICIARY TZ-146943-NC -RFQ / Provision of printing s Component 2: Skills Develop Request for Quota Single Stage - One E ervice for guideline manuals IDA / 57780 ment, Inspection and Perfor Post Limited 12,051.60 Completed 2019-12-13 2019-12-02 2020-02-07 2020-01-28 2020-08-05 2020-03-14 tions nvelope for Judicial Ethics Committee, mance Management Judiciary training policy and t raining programs. TZ-JUDICIARY TZ-151993-NC -RFQ / Provision of Event Man Component 3: Access to Just Request for Quota Single Stage - One E agement: Hiring of Tents, Ch IDA / 57780 Post Limited 82,237.59 Completed 2020-01-15 2019-12-06 2020-03-11 2020-01-28 2020-09-07 2020-03-18 ice and Public Trust tions nvelope airs, Tables, Mobile Toilet an d Printing Services for Law W eek 2020 TZ-JUDICIARY TZ-159179-NC -RFB / ONLINE PUBLICATION OF COURT DECISIONS (REPO Component 1: Governance, Single Stage - One E RTED AND UNREPORTED LA IDA / 57780 Organization and Systems D Post Request for Bids Open - National 335,025.26 Completed 2020-02-23 2020-02-18 2020-02-28 2020-03-16 2020-04-10 2020-04-16 2020-05-10 2020-04-26 2020-06-14 2020-06-07 2020-12-11 2022-04-30 nvelope W REPORTS), PRINTING OF L evelopment AW REPORTS AND INDEX OF LEGISLATION AND SUB LEGIS LATION FROM THE YEAR 196 1-2020 Page 4 TZ-JUDICIARY TZ-180775-NC Component 1: Governance, -RFQ / PROCUREMENT OF SE Request for Quota Single Stage - One E IDA / 57780 Organization and Systems D Post Limited 98,517.15 Completed 2020-07-08 2020-07-08 2020-08-10 2020-09-23 2020-11-08 2021-03-20 RVICE FOR EDITING, DESIGN tions nvelope evelopment AND PRINTING OF VARIOUS J UDICIARY DOCUMENTS. TZ-JUDICIARY TZ-298032-NC -RFQ / Provision of Non-Cons Component 3: Access to Just Request for Quota Single Stage - One E IDA / 57780 Post Limited 16,353.54 Signed 2022-06-10 2022-06-05 2022-07-08 2022-07-15 2022-07-22 ultancy service-Filming and d ice and Public Trust tions nvelope eveloping documentaries abo ut project activities TZ-JUDICIARY TZ-325875-NC -RFQ / PROVISION OF EVENT S MANAGEMENT SERVICES (H IRING TENTS, TABLE, CHAIRS , GENERATORS, PA SYSTEM, Component 3: Access to Just Request for Quota Single Stage - One E Under Imple IDA / 70580 Post Limited 0.00 2022-11-23 2022-11-28 2022-12-21 2023-02-19 CARPET,MOBILE TOILET, DEC ice and Public Trust tions nvelope mentation ORATION, EXHIBITION BOOT H, MARQUEE, AND SUPPLY O F PROMOTIONAL MATERIALS) FOR OPENING CEREMONY AN D 6 DAYS LAW WEEK 2023 TZ-JUDICIARY TZ-9393-NC-R Component 3: Access to Just Request for Quota Single Stage - One E FQ / Printing and supply of m IDA / 57780 Post Limited 80,911.34 Completed 2017-03-14 2017-01-02 2017-05-09 2017-01-28 2017-11-05 2017-03-28 ice and Public Trust tions nvelope aterials for Law week. TZ-JUDICIARY TZ-9397-NC-R FQ / Draw printing and fixing Component 3: Access to Just Request for Quota Single Stage - One E IDA / 57780 Post Limited 0.00 Canceled 2017-03-28 2017-05-23 2017-11-19 of Signs / display boards for s ice and Public Trust tions nvelope elected court buildings. TZ-JUDICIARY TZ-9395-NC-R Component 3: Access to Just Request for Quota Single Stage - One E FQ / Design and printing of Ju IDA / 57780 Post Limited 63,673.97 Completed 2017-03-14 2016-12-28 2017-05-09 2017-01-24 2017-11-05 2017-03-23 ice and Public Trust tions nvelope diciary Calendar and diaries TZ-JUDICIARY TZ-9392-NC-R Component 3: Access to Just Single Stage - One E FB / Printing of different mat IDA / 57780 Prior Request for Bids Open - National 0.00 Canceled 2017-04-28 2017-12-08 2017-05-03 2017-06-14 2017-07-14 2017-08-18 2018-02-14 ice and Public Trust nvelope erials( Framework Contract) CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TZ-JUDICIARY TZ-9448-CS-Q CBS / Consultancy for design Component 1: Governance, Quality And Cost- and supervision of LAN instal IDA / 57780 Organization and Systems D Prior Open - National 0.00 Canceled 2017-04-25 2017-10-09 2017-05-16 2017-12-08 2017-06-29 2018-02-26 2017-07-27 2018-03-30 2017-08-26 2018-05-21 2017-09-30 2017-11-04 2018-11-04 Based Selection lation in Selected High Court, evelopment Resident and District Courts TZ-JUDICIARY TZ-44715-CS- QCBS / CONSULTANCY SERVI CES FOR FEASIBILITY STUDY/I Component 1: Governance, Quality And Cost- Open - Internationa MPLEMENTATION PLAN/PROC IDA / 57780 Organization and Systems D Prior 513,542.79 Completed 2018-01-26 2018-02-16 2018-01-22 2018-04-01 2018-03-29 2018-04-29 2018-04-30 2018-05-29 2018-07-06 2018-07-03 2018-10-03 2018-08-07 2018-11-29 2019-08-07 2021-03-05 Based Selection l UREMENT, DEVELOPMENT AN evelopment D IMPLEMENTATION SUPPOR T FOR E-JUDICIARY SERVICES FOR THE JUDICIARY OF TANZ ANIA TZ-JUDICIARY TZ-50144-CS- QCBS / Consultancy Services to (I) Update Design (Redesig n) of Existing Drawings (Phas Component 3: Access to Just Quality And Cost- Open - Internationa e 1) and (Ii) Supervise the Co IDA / 57780 Prior 452,799.20 Signed 2018-02-26 2018-03-18 2018-03-19 2018-03-27 2018-05-02 2018-06-18 2018-05-30 2018-07-27 2018-06-29 2018-10-03 2018-08-03 2018-11-27 2018-09-07 2018-12-16 2019-09-07 ice and Public Trust Based Selection l nstruction Work for the Propo sed Integrated Justice Centre (IJC) Court Buildings which wi ll be Built in Six Selected Loc ations of Mwanza, Morogoro TZ-JUDICIARY TZ-50194-CS- QCBS / Consultancy Services to (I) Update Design (Redesig n) of Existing Drawings (Phas Component 3: Access to Just Quality And Cost- Open - Internationa IDA / 57780 Prior 0.00 Canceled 2018-02-26 2018-03-18 2018-03-19 2018-04-12 2018-05-02 2018-06-18 2018-05-30 2018-06-29 2018-08-03 2018-09-07 2019-09-07 e 1) and (Ii) Supervise the Co ice and Public Trust Based Selection l nstruction Work for Small Co urthouses which will be Built in at least 10 Selected Locati ons in Tanzania (Phase 2) TZ-JUDICIARY TZ-113326-CS -QCBS / Consultancy Services to (I) Update Design (Redesig n) of Existing Drawings (Phas Component 3: Access to Just Quality And Cost- Open - Internationa IDA / 57780 Prior 310,611.59 Signed 2019-05-08 2019-07-27 2019-05-22 2019-07-31 2019-07-05 2019-12-28 2019-08-02 2020-01-10 2019-08-16 2020-02-18 2019-09-06 2020-03-13 2019-09-23 2020-04-01 2020-09-22 e 1) and (II) Supervise the Co ice and Public Trust Based Selection l nstruction Work for Small Co urthouses which will be Buil t in at Least 27 Selected Loca tions in Tanzania (Phase 2). TZ-JUDICIARY TZ-291807-CS -CQS / CONSULTANCY SERVI CES FOR PREPARATION OF A N ENVIRONMENTAL AND SOC IAL IMPACT ASSESSMENT FO Component 3: Access to Just Consultant Qualifi IDA / 57780 Post Open - National 295,190.27 Signed 2022-04-26 2022-04-24 2022-05-10 2022-05-19 2022-05-25 2022-07-01 2022-06-24 2022-07-25 2022-07-15 2022-08-06 2022-10-13 R THE PROPOSED CONSTRUC ice and Public Trust cation Selection TION PROJECTS IN TANZANIA MAINLAND UNDER THE CITIZ EN-CENTRIC JUDICIAL MODER NIZATION AND JUSTICE SERVI CE DELIVERY PROJECT.(AF) TZ-JUDICIARY TZ-320375-CS -QCBS / Consultancy Services to (I) Update the Design (Red esign) of Existing Drawings, Component 3: Access to Just Quality And Cost- Open - Internationa Under Implement and; (II) Supervise the Constr IDA / 57780 Post 0.00 2022-10-21 2022-10-20 2022-11-04 2022-11-30 2022-11-14 2023-02-09 2022-12-20 2023-03-24 2022-12-25 2023-03-31 2023-01-04 2023-06-26 2023-01-23 2025-03-13 ice and Public Trust Based Selection l ation uction Work for the Proposed Small Courthouses which will be Built in at Least Eleven (1 1) Selected Locations in Tanz ania. 1st Package TZ-JUDICIARY TZ-320379-CS -QCBS / Consultancy Services to (I) Update the Design (Red esign) of Existing Drawings, Component 3: Access to Just Quality And Cost- Open - Internationa Under Implement and; (II) Supervise the Constr IDA / 57780 Post 0.00 2022-10-21 2022-10-20 2022-11-04 2022-11-30 2022-11-14 2023-01-18 2022-12-20 2023-03-24 2022-12-25 2023-03-31 2023-01-04 2023-06-26 2023-01-23 2025-03-13 ice and Public Trust Based Selection l ation uction Work for the Proposed Small Courthouses which will be Built in at least nine (09) Selected Locations in Tanzani a. 2nd Package Page 5 TZ-JUDICIARY TZ-320381-CS -QCBS / Consultancy Services to (I) Update the Design (Red esign) of Existing Drawings, Component 3: Access to Just Quality And Cost- Open - Internationa Under Implement and; (II) Supervise the Constr IDA / 57780 Post 0.00 2022-10-21 2022-10-20 2022-11-04 2022-11-29 2022-11-14 2023-02-09 2022-12-20 2023-03-24 2022-12-25 2023-03-31 2023-01-04 2023-06-21 2023-01-23 2025-03-13 ice and Public Trust Based Selection l ation uction Work for the Proposed Small Courthouses which will be Built in at least nine (09) Selected Locations in Tanzani a. 3rd Package TZ-JUDICIARY TZ-320383-CS -QCBS / Consultancy Services to (I) Update the Design (Red esign) of Existing Drawings, Component 3: Access to Just Quality And Cost- Open - Internationa Under Implement and; (II) Supervise the Constr IDA / 57780 Post 0.00 2022-10-21 2022-10-20 2022-11-04 2022-11-29 2022-11-14 2023-02-09 2022-12-20 2023-03-24 2022-12-25 2023-03-31 2023-01-04 2023-06-19 2023-01-23 2025-03-13 ice and Public Trust Based Selection l ation uction Work for the Proposed Small Courthouses which will be Built in at Least eleven (1 1) Selected Locations in Tanz ania. 4th Package TZ-JUDICIARY TZ-320388-CS -QCBS / Consultancy Services to (I) Update the Design (Red esign) of Existing Drawings, Component 3: Access to Just Quality And Cost- Under Implement IDA / 57780 Post Open - National 0.00 2022-10-21 2022-10-20 2022-11-04 2022-11-29 2022-11-14 2023-02-09 2022-12-20 2023-03-24 2022-12-25 2023-03-31 2023-01-04 2023-06-19 2023-01-23 2025-03-13 and; (II) Supervise the Constr ice and Public Trust Based Selection ation uction Work for the Proposed Small Courthouses which will be Built in at least four (4) Se lected Locations in Tanzania. 5th Package TZ-JUDICIARY TZ-320391-CS -QCBS / Consultancy Services to (I) Update the Design (Red esign) of Existing Drawings, Component 3: Access to Just Quality And Cost- Open - Internationa Under Implement IDA / 57780 Post 0.00 2022-10-21 2022-10-20 2022-11-04 2022-11-30 2022-11-14 2023-02-09 2022-12-20 2023-03-24 2022-12-25 2023-03-31 2023-01-04 2023-06-19 2023-01-23 2025-03-13 and; (II) Supervise the Constr ice and Public Trust Based Selection l ation uction Work for the Proposed Small Courthouses which will be Built in at least six (6) Sel ected Locations in Tanzania. 6th Package TZ-JUDICIARY TZ-320393-CS -QCBS / Consultancy Services to (I) Update the Design (Red esign) of Existing Drawings, Component 3: Access to Just Quality And Cost- Open - Internationa Under Implement IDA / 57780 Post 0.00 2022-10-21 2022-10-20 2022-11-04 2022-11-29 2022-11-14 2023-02-09 2022-12-20 2023-03-24 2022-12-25 2023-03-31 2023-01-04 2023-01-23 2025-03-13 and; (II) Supervise the Constr ice and Public Trust Based Selection l ation uction Work for the Proposed Small Courthouses which will be Built in at Least ten (10) S elected Locations in Tanzania . 7th Package TZ-JUDICIARY TZ-320396-CS -QCBS / Consultancy Service for Supervision of Constructi on Work for the Proposed Int Component 3: Access to Just Quality And Cost- Open - Internationa Under Implement IDA / 57780 Post 0.00 2022-10-21 2022-10-20 2022-11-04 2022-11-29 2022-11-14 2023-02-08 2022-12-20 2023-03-24 2022-12-25 2023-03-31 2023-01-04 2023-01-23 2025-05-12 egrated Justice Centre (IJC) C ice and Public Trust Based Selection l ation ourt Buildings which will be b uilt in four (4) Selected regio ns of Singida, Geita, Simiyu a nd Manyara. 1st Package. TZ-JUDICIARY TZ-320398-CS -QCBS / Consultancy Service for Supervision of Constructi on Work for the Proposed Int Component 3: Access to Just Quality And Cost- Open - Internationa Under Implement IDA / 57780 Post 0.00 2022-10-21 2022-10-20 2022-11-04 2022-11-29 2022-11-14 2023-02-09 2022-12-20 2023-03-24 2022-12-25 2023-03-31 2023-01-04 2023-01-23 2025-05-12 egrated Justice Centre (IJC) C ice and Public Trust Based Selection l ation ourt Buildings which will be b uilt in three (3) Selected regi ons of Katavi, Songwe, and N jombe. 3rd Package. TZ-JUDICIARY TZ-320400-CS -QCBS / Consultancy Service for Supervision of Constructi Component 3: Access to Just Quality And Cost- Open - Internationa Under Implement on Work for the Proposed Int IDA / 57780 Post 0.00 2022-10-21 2022-10-20 2022-11-04 2022-11-29 2022-11-14 2023-02-09 2022-12-20 2023-03-24 2022-12-25 2023-03-31 2023-01-04 2023-01-23 2025-05-12 ice and Public Trust Based Selection l ation egrated Justice Centre (IJC) C ourt Buildings which will be b uilt in Two (2) Selected regio ns of Lindi and Pwani. 2nd Pa ckage TZ-JUDICIARY TZ-365265-CS -QCBS / Consultancy services Component 1: Governance, Quality And Cost- for conducting impact assess IDA / 70580 Organization and Systems D Post Open - National 0.00 Under Review 2023-06-23 2023-07-14 2023-07-28 2023-09-02 2023-09-09 2023-09-30 2023-10-21 2024-02-18 Based Selection ments on simplified laws and evelopment rules of procedure. TZ-JUDICIARY TZ-9183-CS-C QS / Consultancy service to c onduct environmental and so Component 3: Access to Just Consultant Qualifi IDA / 57780 Post Open - National 110,103.09 Completed 2017-03-08 2016-09-06 2017-03-29 2017-05-12 2016-10-25 2017-06-11 2017-02-09 2017-07-16 2017-03-10 2018-01-12 2018-04-27 cial impact assessments for t ice and Public Trust cation Selection he Citizen-Centric Judicial Mo dernization and Justice Servic e Delivery Project. TZ-JUDICIARY TZ-9399-CS-C Component 2: Skills Develop QS / Consultancy service to D Consultant Qualifi IDA / 57780 ment, Inspection and Perfor Post Open - National 0.00 Canceled 2017-07-17 2017-08-07 2017-09-20 2017-10-20 2017-11-24 2018-05-23 evelop continuous training pr cation Selection mance Management ogram and facilitate legal trai ning TZ-JUDICIARY TZ-9438-CS-Q Component 1: Governance, CBS / Consultancy Services t Quality And Cost- IDA / 57780 Organization and Systems D Prior Open - National 0.00 Canceled 2017-05-10 2017-05-31 2017-07-14 2017-08-11 2017-09-10 2017-10-15 2017-11-19 2018-11-19 o design and introduce E-jud Based Selection evelopment gment, e-payment & E- notifi cation TZ-JUDICIARY TZ-9420-CS-Q Component 1: Governance, Quality And Cost- CBS / Consultancy service to IDA / 57780 Organization and Systems D Post Open - National 100,710.87 Completed 2017-04-19 2016-03-30 2017-05-10 2017-06-23 2016-12-23 2017-07-21 2017-01-30 2017-08-20 2017-03-30 2017-09-24 2017-05-04 2017-10-29 2017-06-08 2018-10-29 2019-01-31 Based Selection undertake Court mapping co evelopment untry wide INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Actual Amount Invitation to Identifie Draft Negotiated Cont Component Review Type Method Contract Type Process Status Teams of Reference Signed Contract Contract Completion Description o. h (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TZ-JUDICIARY TZ-25713-CS-I Component 1: Governance, Individual Consult NDV / Procurement Specialist IDA / 57780 Organization and Systems D Post Limited 179,040.00 Completed 2017-08-28 2017-08-28 2017-09-02 2017-08-31 2017-09-23 2017-09-06 2017-10-28 2017-09-26 2018-04-26 2020-05-20 ant Selection to support Project team evelopment TZ-JUDICIARY TZ-42554-CS-I NDV / Provision of consultanc Component 3: Access to Just Individual Consult IDA / 57780 Post Limited 67,200.00 Completed 2018-01-15 2017-11-21 2018-01-20 2018-01-23 2018-02-10 2018-02-12 2018-03-17 2018-03-29 2018-09-13 2019-03-28 y for Information and Commu ice and Public Trust ant Selection nication services Page 6 TZ-JUDICIARY TZ-42596-CS-I Component 1: Governance, NDV / Consultancy services f Individual Consult IDA / 57780 Organization and Systems D Post Limited 68,100.00 Completed 2018-01-18 2017-11-21 2018-01-23 2018-01-18 2018-02-13 2018-02-12 2018-03-20 2018-05-07 2018-09-16 2019-06-26 or preparation of Human Res ant Selection evelopment ource planning guideline for J udiciary of Tanzania. TZ-JUDICIARY TZ-42602-CS-I NDV / Provision of consultanc y services for development o Component 3: Access to Just Individual Consult IDA / 57780 Post Limited 31,581.00 Terminated 2018-01-15 2017-12-30 2018-01-20 2018-01-21 2018-02-10 2018-02-15 2018-03-17 2018-05-07 2018-09-13 f database systems for judge ice and Public Trust ant Selection ment, Advocates and Court B rokers and database for proje ct M & E tools based on BRN. TZ-JUDICIARY TZ-9406-CS-C DS / Consultancy service for supervision of the constructio Component 3: Access to Just IDA / 57780 Prior Direct Selection Direct 0.00 Canceled 2017-04-02 2017-04-12 2017-06-16 2017-12-13 n of ten (10) courthouses for ice and Public Trust subordinate court Primary Co urt and training room at Kisu tu RMs Court. TZ-JUDICIARY TZ-54811-CS-I Component 1: Governance, NDV / Individual Consultancy Individual Consult IDA / 57780 Organization and Systems D Post Limited 22,980.00 Completed 2018-03-26 2018-03-26 2018-03-31 2018-07-02 2018-04-21 2018-08-21 2018-05-26 2018-11-07 2018-11-22 2019-10-04 service for establishment an ant Selection evelopment d development of a compute rized e-Library system TZ-JUDICIARY TZ-138788-CS -INDV / CLERK OF WORKS (Co Ws) FOR SUPERVISION OF CO Component 3: Access to Just Individual Consult IDA / 57780 Post Open 66,998.08 Completed 2019-10-21 2019-10-22 2019-11-16 2020-01-17 2019-11-23 2020-01-17 2019-12-21 2020-01-25 2020-06-18 2022-03-01 NSTRUCTION OF INTEGRATE ice and Public Trust ant Selection D JUSTICE CENTRE (IJC) IN M WANZA, Plot 768 Block. A at North Buswelu. TZ-JUDICIARY TZ-140323-CS -INDV / CLERK OF WORKS (Co Ws) FOR SUPERVISION OF CO Component 3: Access to Just Individual Consult IDA / 57780 Post Open 31,688.28 Completed 2019-10-21 2019-10-22 2019-11-16 2020-01-17 2019-11-23 2020-01-17 2020-01-04 2020-01-25 2020-07-02 2021-02-15 NSTRUCTION OF INTEGRATE ice and Public Trust ant Selection D JUSTICE CENTRE (IJC) IN M OROGORO,, Plot 430 Block. G at Kihonda. TZ-JUDICIARY TZ-140325-CS -INDV / CLERK OF WORKS (Co Ws) FOR SUPERVISION OF CO Component 3: Access to Just Individual Consult IDA / 57780 Post Open 47,647.74 Completed 2019-10-21 2019-10-22 2019-11-16 2020-01-17 2019-11-23 2020-01-17 2019-12-07 2020-01-25 2020-06-04 2021-09-01 NSTRUCTION OF INTEGRATE ice and Public Trust ant Selection D JUSTICE CENTRE (IJC) IN AR USHA, Plot No 123. Block I Sit uated at Corridor I in Arusha City. TZ-JUDICIARY TZ-140327-CS -INDV / CLERK OF WORKS (Co Ws) FOR SUPERVISION OF CO Component 3: Access to Just Individual Consult IDA / 57780 Post Open 46,979.73 Completed 2019-10-21 2019-10-22 2019-11-16 2020-01-17 2019-11-23 2020-01-17 2019-12-21 2020-01-25 2020-06-18 2021-09-01 NSTRUCTION OF INTEGRATE ice and Public Trust ant Selection D JUSTICE CENTRE (IJC) IN D ODOMA, Plot No. 4 Block C at NCC Link. TZ-JUDICIARY TZ-140332-CS -INDV / CLERK OF WORKS (Co Ws) FOR SUPERVISION OF CO Component 3: Access to Just Individual Consult IDA / 57780 Post Open 53,505.92 Completed 2019-10-21 2019-10-22 2019-11-16 2020-01-17 2019-11-23 2020-02-06 2019-12-07 2020-01-25 2020-06-04 2021-07-31 NSTRUCTION OF INTEGRATE ice and Public Trust ant Selection D JUSTICE CENTRE (IJC) in DA R ES SALAAM, Plot No. 38 Blo ck No. 20 at Kinondoni Munic ipal. TZ-JUDICIARY TZ-140334-CS -INDV / CLERK OF WORKS (Co Ws) FOR SUPERVISION OF CO Component 3: Access to Just Individual Consult IDA / 57780 Post Open 48,306.60 Signed 2019-10-21 2019-10-22 2019-11-16 2020-01-17 2019-11-23 2020-01-17 2019-12-07 2020-01-25 2020-06-04 NSTRUCTION OF INTEGRATE ice and Public Trust ant Selection D JUSTICE CENTRE (IJC) IN DA R ES SALAAM, Plot No 2025 B lock D at Temeke. TZ-JUDICIARY TZ-152928-CS -INDV / INDIVIDUAL EXPERT T Component 1: Governance, O CONDUCT AN ECONOMIC A Individual Consult IDA / 57780 Organization and Systems D Post Limited 8,182.54 Completed 2020-01-24 2020-02-11 2020-01-29 2020-02-12 2020-02-19 2020-02-14 2020-03-25 2020-03-04 2020-09-21 2021-01-01 NALYSIS OF CITIZEN-CENTRIC ant Selection evelopment JUDICIAL MODERNIZATION A ND JUSTICE SERVICE DELIVE RY PROJECT TZ-JUDICIARY TZ-291818-CS Component 1: Governance, -INDV / Procurement and Con Individual Consult IDA / 57780 Organization and Systems D Prior Open 67,925.09 Signed 2022-04-26 2022-05-06 2022-05-22 2022-07-09 2022-05-27 2022-08-26 2022-06-13 2022-09-02 2023-06-08 tract Management Expert to ant Selection evelopment support the project team. TZ-JUDICIARY TZ-294037-CS -INDV / INDIVIDUAL CONSULT Component 1: Governance, ANT (CIVIL ENGINEER) FOR T Individual Consult IDA / 57780 Organization and Systems D Post Limited 30,875.04 Signed 2022-05-13 2022-05-15 2022-05-18 2022-06-27 2022-06-08 2022-08-24 2022-06-29 2022-09-05 2023-06-29 HE CITIZEN-CENTRIC JUDICIA ant Selection evelopment L MODERNIZATION AND JUST ICE SERVICE DELIVERY PROJE CT. TZ-JUDICIARY TZ-295323-CS -CDS / CONSULTANCY SERVI CE TO UPDATE THE DESIGN ( Component 3: Access to Just Under Implement IDA / 57780 Post Direct Selection Direct 0.00 2022-05-20 2022-05-30 2022-06-08 2022-08-25 2022-06-22 2022-08-23 REDESIGN) OF EXISTING DRA ice and Public Trust ation WINGS FOR THE PROPOSED 12 INTEGRATED JUSTICE CEN TRE (IJCs). TZ-JUDICIARY TZ-306644-CS -CDS / Consultancy service t Component 3: Access to Just Under Implement IDA / 57780 Post Direct Selection Direct - National 0.00 2022-07-31 2022-08-01 2022-08-19 2022-08-17 2022-08-31 2023-02-27 o conduct court users’ satisfa ice and Public Trust ation ction survey 2022 TZ-JUDICIARY TZ-364600-CS -INDV / Individual Consultant- Component 3: Access to Just Individual Consult Pending Impleme Clerk of Works (CoWs) for su IDA / 70580 Post Open - National 0.00 2023-06-11 2023-07-30 2023-08-20 2023-09-10 2024-09-09 ice and Public Trust ant Selection ntation pervision of construction of I ntegrated Justice Centre (IJC) in Songea. TZ-JUDICIARY TZ-364607-CS -INDV / Individual Consultant- Component 3: Access to Just Individual Consult Pending Impleme Clerk of Works (CoWs) for su IDA / 70580 Post Open - National 0.00 2023-06-11 2023-07-30 2023-08-20 2023-09-10 2024-09-09 ice and Public Trust ant Selection ntation pervision of construction of I ntegrated Justice Centre (IJC) in Lindi. TZ-JUDICIARY TZ-364593-CS -INDV / Individual Consultant- Component 3: Access to Just Individual Consult Pending Impleme Clerk of Works (CoWs) for su IDA / 70580 Post Open - National 0.00 2023-06-11 2023-07-30 2023-08-20 2023-09-10 2024-09-09 ice and Public Trust ant Selection ntation pervision of construction of i ntegrated justice centre (IJC) in Njombe. Page 7 TZ-JUDICIARY TZ-364576-CS -INDV / Individual Consultant- Component 3: Access to Just Individual Consult Pending Impleme Clerk of Works (CoWs) for su IDA / 70580 Post Open - National 0.00 2023-06-11 2023-07-30 2023-08-20 2023-09-10 2024-09-09 ice and Public Trust ant Selection ntation pervision of construction of i ntegrated justice centre (IJC) in Simiyu TZ-JUDICIARY TZ-364587-CS -INDV / Individual Consultant- Component 3: Access to Just Individual Consult Pending Impleme Clerk of Works (CoWs) for su IDA / 70580 Post Open - National 0.00 2023-06-11 2023-07-30 2023-08-20 2023-09-10 2024-09-09 ice and Public Trust ant Selection ntation pervision of construction of I ntegrated Justice Centre (IJC) in Katavi TZ-JUDICIARY TZ-364590-CS -INDV / Individual Consultant- Component 3: Access to Just Individual Consult Pending Impleme Clerk of Works (CoWs) for su IDA / 70580 Post Open - National 0.00 2023-06-11 2023-07-30 2023-08-20 2023-09-10 2024-09-09 ice and Public Trust ant Selection ntation pervision of construction of t he Integrated Justice Centre ( IJC) in Songwe TZ-JUDICIARY TZ-364605-CS -INDV / Individual Consultant- Component 3: Access to Just Individual Consult Pending Impleme Clerk of Works (CoWs) for su IDA / 70580 Post Open - National 0.00 2023-06-11 2023-07-30 2023-08-20 2023-09-10 2024-09-09 ice and Public Trust ant Selection ntation pervision of construction of t he Integrated Justice Centre ( IJC) in Moshi. TZ-JUDICIARY TZ-364583-CS -INDV / Individual Consultant- Component 3: Access to Just Individual Consult Pending Impleme Clerk of Works (CoWs) for su IDA / 70580 Post Open - National 0.00 2023-06-11 2023-07-30 2023-08-20 2023-09-10 2024-09-09 ice and Public Trust ant Selection ntation pervision of construction of i ntegrated justice centre (IJC) in Pemba. TZ-JUDICIARY TZ-364597-CS -INDV / Individual Consultant- Component 3: Access to Just Individual Consult Pending Impleme Clerk of Works (CoWs) for su IDA / 70580 Post Open - National 0.00 2023-06-11 2023-07-30 2023-08-20 2023-09-10 2024-09-09 ice and Public Trust ant Selection ntation pervision of construction of I ntegrated Justice Centre (IJC) in Mtwara TZ-JUDICIARY TZ-364602-CS -INDV / Individual Consultant- Component 3: Access to Just Individual Consult Pending Impleme Clerk of Works (CoWs) for su IDA / 70580 Post Open - National 0.00 2023-06-11 2023-07-30 2023-08-20 2023-09-10 2024-09-09 ice and Public Trust ant Selection ntation pervision of construction of I ntegrated Justice Centre (IJC) in Pwani. TZ-JUDICIARY TZ-364604-CS -INDV / Individual Consultant- Component 3: Access to Just Individual Consult Pending Impleme Clerk of Works (CoWs) for su IDA / 70580 Post Open - National 0.00 2023-06-11 2023-07-30 2023-08-20 2023-09-10 2024-09-09 ice and Public Trust ant Selection ntation pervision of construction of I ntegrated Justice Centre (IJC) in Tanga. TZ-JUDICIARY TZ-364581-CS -INDV / Individual Consultant- Component 3: Access to Just Individual Consult Pending Impleme Clerk of Works (CoWs) for su IDA / 70580 Post Open - National 0.00 2023-06-11 2023-07-30 2023-08-20 2023-09-10 2024-09-09 ice and Public Trust ant Selection ntation pervision of construction of I ntegrated Justice Centre (IJC) in Geita. TZ-JUDICIARY TZ-364606-CS -INDV / Individual Consultant- Component 3: Access to Just Individual Consult Pending Impleme Clerk of Works (CoWs) for su IDA / 70580 Post Open - National 0.00 2023-06-11 2023-07-30 2023-08-20 2023-09-10 2024-09-09 ice and Public Trust ant Selection ntation pervision of construction of t he Integrated Justice Centre ( IJC) in Manyara. TZ-JUDICIARY TZ-364574-CS -INDV / Individual Consultant- Component 3: Access to Just Individual Consult Clerk of Works (CoWs) for su IDA / 70580 Post Open - National 0.00 Under Review 2023-06-11 2023-07-30 2023-08-20 2023-09-10 2024-09-09 ice and Public Trust ant Selection pervision of construction of i ntegrated justice centre (IJC) in Singida TZ-JUDICIARY TZ-9441-CS-IN DV / Consultancy to review ju Component 3: Access to Just Individual Consult IDA / 57780 Post Open 0.00 Canceled 2017-04-24 2017-06-12 2017-07-03 2017-08-07 2018-02-03 stice chain, identify gaps in t ice and Public Trust ant Selection erms of policy, strategy, refo rm or performance TZ-JUDICIARY TZ-9445-CS-IN Component 3: Access to Just Individual Consult DV / Consultancy to prepare IDA / 57780 Post Open 0.00 Canceled 2017-04-24 2017-06-12 2017-07-03 2017-08-07 2018-02-03 ice and Public Trust ant Selection special program on legal aid with MoCLA TZ-JUDICIARY TZ-9410-CS-C Component 3: Access to Just DS / Consultancy service for IDA / 57780 Post Direct Selection Direct 121,856.63 Completed 2017-03-29 2019-01-18 2017-04-08 2019-04-17 2017-06-12 2019-06-27 2017-12-09 2019-09-27 ice and Public Trust Court User Survey. TZ-JUDICIARY TZ-9433-CS-IN Component 1: Governance, Individual Consult DV / Procurement of IT Speci IDA / 57780 Organization and Systems D Post Open 0.00 Canceled 2017-04-17 2017-06-05 2017-06-26 2017-07-31 2018-01-27 ant Selection alist to support Project team evelopment TZ-JUDICIARY TZ-9422-CS-IN Component 1: Governance, Individual Consult DV / Procurement Specialist t IDA / 57780 Organization and Systems D Post Open 0.00 Canceled 2017-03-09 2017-02-02 2017-04-27 2017-05-11 2017-05-18 2017-06-22 2017-12-19 ant Selection o Support Project Team evelopment TZ-JUDICIARY TZ-9431-CS-IN DV / Consultancy service to s Component 3: Access to Just Individual Consult IDA / 57780 Post Open 0.00 Canceled 2017-05-12 2017-06-30 2017-07-21 2017-08-25 2018-02-21 upport the development of A ice and Public Trust ant Selection DR and backlog reduction pr ogram TZ-JUDICIARY TZ-9440-CS-IN DV / Consultancy Services to Component 3: Access to Just Individual Consult IDA / 57780 Post Open 0.00 Canceled 2017-07-18 2017-09-05 2017-09-26 2017-10-31 2018-04-29 introduce Online interactive c ice and Public Trust ant Selection omplaints platform Page 8 PROCUREMENT PLAN (Textual Part) Project information: Burundi - Great Lakes Trade Facilitation and Integration Project] (P174814) Project Implementation agency: Burundi-Ministry of Finance, Budget and Privatization Date of the Procurement Plan: November 8, 2021 Period covered by this Procurement Plan: December 2017 – December 2021 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the country procurement handbook, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. - The request for bids/request for proposals document shall require that Bidders/Proposers submitting Bids/Proposals present a signed acceptance at the time of bidding to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights. - Rights for the Bank to review procurement documentation and activities. - An effective complaints mechanism. - Maintenance of records of the Procurement Process When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables: Not Applicable Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables : Not Applicable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: is Not Applicable Works: is not Applicable PROCUREMENT Eastern and Southern Africa : Great Lakes Trade Facilitation and Integration Project PLAN General Information Country: Eastern and Southern Africa 2018-07-23 Bank’s Approval Date of the Original Procurement Plan: 2023-06-04 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P174814 GPN Date: Project Name: Great Lakes Trade Facilitation and Integration Project Loan / Credit No: IDA / V1000, IDA / V3250, IDA / V0960, IDA / V3940, IDA / E0700, IDA / E0710 Burundi-Ministry of Finance, Budget and Privatization Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned BI-BI-MOF-71885-CW-DIR / A Component 1. Improving Poli Under Imple 2019-01-1 dduction d'eau au poste front IDA / V1000 cy and Regulatory Environm Prior Direct Selection Direct 28,600.00 0.00 2018-07-27 2018-08-01 2018-09-18 mentation 7 ière de Gatumba (Interventio ent for cross border trade n rapide) BI-BI-MOF-71888-CW-RFQ / Improving core trade infrastr Aménagement des Latrines e Request for Quota Single Stage - One E 2019-01-0 IDA / V1000 ucture and facilities in the b Post Limited 11,000.00 10,186.24 Completed 2018-08-11 2018-08-10 2018-10-02 2018-09-06 t douches au port de Rumon tions nvelope 4 order areas ge (Intervention urgente) GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BI-BI-MOF-170418-GO-RFQ / Implementation support, Co Request for Quota Single Stage - One E Acquisition des équipements IDA / V3250 mmunication, Monitoring, an Post Limited 50,000.00 16,881.67 Signed 2020-07-25 2022-02-22 2020-09-19 2022-01-25 2020-10-30 tions nvelope de bureau (mobilier et photo d Evaluation copieuse) BI-BI-MOF-170426-GO-RFQ / Implementation support, Co Request for Quota Single Stage - One E Acquisition du matériel infor IDA / V3250 mmunication, Monitoring, an Post Limited 30,000.00 42,446.89 Completed 2020-07-12 2020-10-12 2020-08-28 2021-01-20 2020-10-09 2021-06-08 tions nvelope matique pour l'UGP d Evaluation BI-BI-MOF-170423-GO-RFB / Implementation support, Co Acquisition de Trois véhicules Single Stage - One E IDA / V3250 mmunication, Monitoring, an Post Request for Bids Open - National 250,000.00 0.00 Canceled 2020-07-15 2020-07-20 2020-08-31 2020-09-15 2020-10-09 2020-12-01 (One station wagon 4*4 et de nvelope d Evaluation ux camionnettes) BI-BI-MOF-319184-GO-RFB / Component 4: Supporting Im Single Stage - One E Pending Impl Acquisition des équipements IDA / E0700 plementation and Monitoring Post Request for Bids Open - National 50,000.00 0.00 2022-12-15 2022-12-20 2023-01-31 2023-03-02 2023-04-06 2023-06-15 nvelope ementation mobiliers pour l'UGP and Evaluation BI-BI-MOF-319187-GO-RFB / Component 4: Supporting Im Single Stage - One E Pending Impl Acquisition du matériel infor IDA / E0700 plementation and Monitoring Post Request for Bids Open - National 100,000.00 0.00 2022-12-15 2022-12-20 2023-01-31 2023-03-02 2023-04-06 2023-06-30 nvelope ementation matique pour l'UGP and Evaluation BI-BI-MOF-319182-GO-RFB / Component 4: Supporting Im Acquisition de 4 véhicules (1 Single Stage - One E IDA / E0700 plementation and Monitoring Post Request for Bids Open - National 350,000.00 0.00 Canceled 2022-11-15 2022-11-20 2023-01-01 2023-01-20 2023-02-17 2023-04-21 jeep station wagon ou équiva nvelope and Evaluation lent + 3 pick up) BI-BI-MOF-355350-GO-DIR / Acquisition de 4 véhicules (1 Component 4: Supporting Im Direct - Internation Under Imple station wagon 4X4 et 3 cami IDA / E0700 plementation and Monitoring Post Direct Selection 300,000.00 0.00 2023-04-21 2023-06-02 2023-05-02 2023-03-25 2023-05-23 2023-11-19 al mentation onnettes double cabine 4X4) and Evaluation auprès de l'agence des Natio ns Unies UNOPS BI-BI-MOF-357226-GO-RFB / Component 4: Supporting Im Open - Internationa Single Stage - One E Pending Impl Acquisition d'un système de IDA / E0700 plementation and Monitoring Post Request for Bids 60,000.00 0.00 2023-04-28 2023-05-03 2023-06-14 2023-06-21 2023-07-26 2023-10-27 l nvelope ementation vidéoconférence and Evaluation BI-BI-MOF-360294-GO-RFB / Component 4: Supporting Im Single Stage - One E Pending Impl Acquisition de 14 batteries d' IDA / E0700 plementation and Monitoring Post Request for Bids Open - National 20,000.00 0.00 2023-05-19 2023-05-24 2023-07-05 2023-08-04 2023-09-08 2023-12-15 nvelope ementation un système de back-up élect and Evaluation rique BI-BI-MOF-367786-GO-RFQ / Component 4: Supporting Im Request for Quota Single Stage - One E Pending Impl Acquisition du mobilier de bu IDA / E0700 plementation and Monitoring Post Limited 10,000.00 0.00 2023-07-05 2023-08-16 2023-10-20 tions nvelope ementation reau and Evaluation BI-BI-MOF-367788-GO-RFQ / Component 4: Supporting Im Request for Quota Single Stage - One E Pending Impl Acquisition du matériel infor IDA / E0700 plementation and Monitoring Post Limited 15,000.00 0.00 2023-07-10 2023-08-21 2023-10-27 tions nvelope ementation matique pour l'UGP and Evaluation BI-BI-MOF-367790-GO-RFQ / Component 4: Supporting Im Request for Quota Single Stage - One E Pending Impl Acquisition des climatiseurs IDA / E0700 plementation and Monitoring Post Limited 18,000.00 0.00 2023-07-16 2023-08-25 2023-11-30 tions nvelope ementation de remplacement and Evaluation NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual DMI/010/PFCGL-II/2018 / Con Improving core trade infrastr ception détaillée nécessaire Quality And Cost- Open - Internationa IDA / V1000 ucture and facilities in the b Post 200,000.00 187,605.23 Completed 2018-04-20 2018-04-16 2018-06-15 2018-09-13 2018-07-22 2018-07-05 2018-08-23 2018-09-28 2018-09-15 2018-10-05 2018-10-20 2018-10-23 2018-11-10 2018-02-15 2019-02-11 2019-11-06 pour le site du projet de cons Based Selection l order areas truction du Port de Rumonge BI-BI-MOF-65618-CS-QCBS / Improving core trade infrastr Conception détaillée nécessa Quality And Cost- Open - Internationa IDA / V1000 ucture and facilities in the b Post 200,000.00 0.00 Canceled 2018-07-05 2018-07-26 2018-08-31 2018-10-03 2018-10-19 2018-11-16 2018-12-07 2019-02-07 ire pour les sites du poste fro Based Selection l order areas ntalier et du marché frontalie r de Gatumba Page 1 BI-BI-MOF-65723-CS-QCBS / Improving core trade infrastr Conception des infrastructur Quality And Cost- IDA / V1000 ucture and facilities in the b Post Open - National 60,000.00 0.00 Canceled 2018-07-15 2018-08-10 2018-09-10 2018-10-15 2018-10-31 2018-11-21 2018-12-05 2019-03-05 es provisoires aux postes fro Based Selection order areas ntaliers de Gatumba et au po rt de Rumonge BI-BI-MOF-71876-CS-QCBS / Improving core trade infrastr Conception détaillée nécessa Quality And Cost- Open - Internationa IDA / V1000 ucture and facilities in the b Post 80,000.00 118,150.00 Completed 2018-08-20 2018-11-19 2018-09-10 2018-11-20 2018-10-15 2019-01-24 2018-11-27 2019-01-15 2018-12-14 2019-01-25 2019-01-18 2019-04-15 2019-02-22 2020-08-20 2019-05-27 2021-07-05 ire pour les sites du poste fro Based Selection l order areas ntière de Gatumba BI-BI-MOF-71879-CS-QCBS / Improving core trade infrastr Quality And Cost- Conception détaillée nécessa IDA / V1000 ucture and facilities in the b Post Open - National 43,130.00 8,504.99 Completed 2018-08-23 2018-09-07 2018-09-13 2018-09-12 2018-10-19 2018-11-08 2018-11-23 2019-01-15 2018-12-10 2019-10-28 2019-01-14 2019-10-28 2019-02-11 2019-03-20 2019-05-13 2020-04-22 Based Selection ire pour le marché frontalier order areas de Gatumba BI-BI-MOF-96822-CS-LCS / A Implementation support, Co udit comptable et financier d Least Cost Selecti Open - Internationa IDA / V1000 mmunication, Monitoring, an Post 25,000.00 13,684.46 Completed 2019-01-28 2019-02-22 2019-02-18 2019-05-20 2019-04-03 2019-10-30 2019-05-01 2019-10-30 2019-05-31 2019-10-30 2019-07-05 2022-02-19 2019-08-09 2019-11-19 2020-02-05 2019-12-06 u PFCGL-II de la période allan on l d Evaluation t du 07/08/2017 au 30/06/20 19 BI-BI-MOF-102626-CS-QCBS / Recrutement d'une firme de Improving core trade infrastr consultants pour le contrôle Quality And Cost- Open - Internationa IDA / V1000 ucture and facilities in the b Post 100,000.00 0.00 Canceled 2019-03-14 2019-04-04 2019-05-17 2019-07-04 2019-07-19 2019-08-16 2019-10-08 2020-10-07 et la surveillance des travaux Based Selection l order areas de construction du port de R umonge et provision de servi ces connexes BI-BI-MOF-203512-CS-CQS / Recrutement d'un bureau en charge de l'élaboration de l'é Improving core trade infrastr tude technique pour l'aména Consultant Qualifi Open - Internationa IDA / V3250 ucture and facilities in the b Post 80,000.00 0.00 Canceled 2020-12-01 2020-12-08 2021-01-14 2021-01-29 2021-02-11 2021-05-11 gement et le bitumage de la cation Selection l order areas RP 108: RN4(PK 14 + 8)/Gatu mba-Vuggizo/Frontière RDC ( 8km)+Etude d'Impact Enviro nnemental et Social (EIES) BI-BI-MOF-203525-CS-CQS / Improving core trade infrastr Etude de faisabilité sur les ch Consultant Qualifi Open - Internationa IDA / V3250 ucture and facilities in the b Post 200,000.00 0.00 Canceled 2020-12-15 2020-12-22 2021-02-04 2021-02-18 2021-03-04 2021-05-19 aînes de valeur des produits cation Selection l order areas agricoles, de pêche et de frui ts BI-BI-MOF-203488-CS-CQS / Etude pour la construction du Improving core trade infrastr marché transfrontalier de Ru Consultant Qualifi IDA / V3250 ucture and facilities in the b Post 50,000.00 0.00 Canceled 2020-11-27 2020-12-10 2021-01-23 2021-02-10 2021-03-17 2021-05-25 monge (incluant l'étude de re cation Selection order areas ntabilité et Etude d'Impact E nironnemental et Social (EIES )) BI-BI-MOF-204468-CS-QCBS / Recrutement d'un cabinet p Implementation of policy an our la réalisation de l'audit o d procedural reforms and ca pérationnel des administratio Quality And Cost- Open - Internationa IDA / V3250 pacity building to facilitate c Post 150,000.00 0.00 Canceled 2020-12-21 2021-01-04 2021-02-03 2021-03-11 2021-03-30 2021-05-04 2021-05-31 2021-10-14 ns des services des frontière Based Selection l ross-border trade in goods a s: étude sur l'efficacité et l'ef nd servic es ficience institutionnelle des a dministrations des services d es frontières BI-BI-MOF-207626-CS-CQS / Component 1. Improving Poli Etude pour la constructiondu Consultant Qualifi Pending Impleme IDA / V3250 cy and Regulatory Environm Post Open - National 40,000.00 0.00 2021-03-08 2021-03-15 2021-04-28 2021-05-28 2021-06-11 2021-09-30 marché transfrontalier de Ru cation Selection ntation ent for cross border trade monge incluant l'étude de re ntabilité BI-BI-MOF-207711-CS-CQS / Etude technique pour l'amén Component 1. Improving Poli Consultant Qualifi Open - Internationa Under Implement agement et le bitumage de l IDA / V3250 cy and Regulatory Environm Post 55,000.00 0.00 2020-12-09 2021-01-27 2020-12-14 2021-02-15 2021-01-20 2022-02-21 2021-02-05 2021-02-15 2021-05-28 cation Selection l ation a RP 108: RN4 (PK14 + 8)Gat ent for cross border trade umba-Vugizo/frontière BI-BI-MOF-207744-CS-CQS / Recrutement d'un cabinet po Implementation of policy an ur la réalisation de l'audit op d procedural reforms and ca érationnel des administration Consultant Qualifi Open - Internationa IDA / V3250 pacity building to facilitate c Post 150,000.00 108,130.00 Signed 2021-01-15 2020-12-21 2021-01-29 2021-03-15 2021-03-14 2022-02-17 2021-04-13 2022-02-17 2021-05-04 2021-12-03 2021-10-31 s des services des frontières cation Selection l ross-border trade in goods a : étude sur l'efficacité et l'effi nd servic es cience institutionnelle des ad ministrations des services de s frontières BI-BI-MOF-207751-CS-CQS / Improving core trade infrastr Etude de faisabilité sur les ch Consultant Qualifi Open - Internationa IDA / V3250 ucture and facilities in the b Post 200,000.00 0.00 Canceled 2020-12-15 2020-12-21 2020-12-22 2021-01-26 2021-02-04 2022-02-18 2021-03-06 2021-03-19 2021-06-18 aînes de valeurs des produits cation Selection l order areas agricoles, de pêche et de frui ts BI-BI-MOF-221288-CS-LCS / Implementation support, Co Audit comptable et financier Least Cost Selecti Open - Internationa IDA / V0960 mmunication, Monitoring, an Post 20,000.00 6,074.00 Completed 2021-03-02 2021-03-01 2021-03-23 2021-05-10 2021-05-06 2022-02-15 2021-06-03 2022-02-15 2021-07-03 2022-02-21 2021-08-07 2022-02-21 2021-10-15 2021-12-07 2021-12-15 2021-12-25 du projet pour la période alla on l d Evaluation nt du 01/07/2020 au 30/06/2 021 BI-BI-MOF-290037-CS-QCBS Component 3: Supporting Co / Recrutement d'un coonsulta Quality And Cost- Open - Internationa Under Implement IDA / V3250 mmercialization of Selected Post 200,000.00 0.00 2022-04-14 2022-04-13 2022-04-20 2022-07-12 2022-05-20 2023-03-22 2022-06-17 2022-07-11 2022-08-15 2022-09-19 2022-12-30 nt chargé de l'étude de l"état Based Selection l ation Cross-border Value Chains des lieux des chaînes de vale ur de l'agribusiness BI-BI-MOF-303406-CS-QCBS / Recrutement d'un consultan Component 3: Supporting Co t chargé de l'élaboration du Quality And Cost- Open - Internationa IDA / V3940 mmercialization of Selected Post 100,000.00 0.00 Canceled 2022-08-19 2022-10-04 2022-09-09 2022-10-23 2022-11-20 2022-12-20 2023-01-24 2023-02-28 2023-04-26 manuel de gestion des subve Based Selection l Cross-border Value Chains ntions aux associations et co opératives des commerçants dans le cadre du PFCIGL BI-BI-MOF-319236-CS-QCBS / Recrutement d'un bureau p our l'élaboration d'une étude Component 2: Improving Cor Quality And Cost- Open - Internationa Under Implement IDA / E0700 Post 200,000.00 0.00 2022-11-02 2023-01-13 2022-11-09 2023-04-07 2022-12-23 2023-01-20 2023-02-10 2023-03-03 2023-03-31 2023-07-14 technique pour l'aménageme e Trade Infrastructure Based Selection l ation nt et modernisation des infra structures du poste frontière de Vugizo-Kiliba BI-BI-MOF-207635-CS-CQS / Component 1. Improving Poli Etude pour l'aménagement e Consultant Qualifi Open - Internationa IDA / V3250 cy and Regulatory Environm Post 40,000.00 0.00 Canceled 2020-12-11 2020-12-22 2020-12-18 2021-01-26 2021-01-22 2021-02-21 2021-03-05 2021-05-17 t la modernisation du poste-f cation Selection l ent for cross border trade rontière Vugizo-Kiliba Page 2 BI-BI-MOF-203504-CS-CQS / Recrutement d'un bureau ch argé de l'élaboration de l'étu Improving core trade infrastr Consultant Qualifi de pour l'aménagement et m IDA / V3250 ucture and facilities in the b Post Open - National 60,000.00 0.00 Canceled 2020-11-18 2020-11-25 2021-01-08 2021-02-07 2021-02-19 2021-04-26 cation Selection odernisation poste-frontière order areas Vugizo-Kiliba + Etude d'Imp act Environnemental et Socia l (EIES) BI-BI-MOF-335979-CS-QCBS / Recrutement d'un bureau d' un bureau pour la réalisation Component 2: Improving Cor Quality And Cost- Open - Internationa Under Implement de la réalisation d'une étude IDA / E0700 Post 100,000.00 0.00 2023-01-20 2023-04-04 2023-01-25 2023-06-05 2023-02-17 2023-04-03 2023-04-14 2023-05-12 2023-06-09 2023-09-15 e Trade Infrastructure Based Selection l ation de rentabilité économique et l'adaptation de l'étude techni que pour la construction du marché transfrontalier de Ga tumba BI-BI-MOF-335987-CS-QCBS / Recrutement d'un bureau p Component 2: Improving Cor Quality And Cost- Open - Internationa Under Implement our la surveillance/contrôle d IDA / E0700 Post 700,000.00 0.00 2023-01-20 2023-01-18 2023-01-27 2023-04-05 2023-02-17 2023-04-04 2023-04-14 2023-05-05 2023-05-29 2024-05-28 e Trade Infrastructure Based Selection l ation es travaux de construction d u poste frontière de Gatumb a-Kavimvira BI-BI-MOF-335989-CS-QCBS / Recrutement d'un bureau p our la surveillance/contrôle d Component 2: Improving Cor Quality And Cost- Open - Internationa Under Implement es travaux de construction d IDA / E0700 Post 1,800,000.00 0.00 2023-01-24 2023-01-19 2023-01-31 2023-02-23 2023-02-21 2023-04-05 2023-04-19 2023-05-05 2023-05-31 2026-05-29 e Trade Infrastructure Based Selection l ation u port de Rumonge et provisi on de services connexes y co mpris l'actualisation des étud es techniques BI-BI-MOF-338261-CS-QCBS / Recrutement d'un bureau c hargé de l'élaboration de l'ét Component 2: Improving Cor Quality And Cost- Open - Internationa Under Implement IDA / E0710 Post 200,000.00 0.00 2023-02-15 2023-01-25 2023-02-21 2023-03-30 2023-03-30 2023-05-10 2023-05-26 2023-06-30 2023-07-21 2023-10-30 ude technique d'aménageme e Trade Infrastructure Based Selection l ation nt et de bitumage de la RP 1 08: RN 4/Gatumba - Vugizo/fr ontière RDC (8 km) BI-BI-MOF-338268-CS-QCBS / Recrutement d'une firme ch Component 3: Supporting Co Quality And Cost- Open - Internationa Under Implement argée de la gestion du méca IDA / E0700 mmercialization of Selected Post 300,000.00 0.00 2023-02-20 2023-03-13 2023-02-27 2023-03-30 2023-04-05 2023-05-12 2023-05-26 2023-06-30 2023-07-21 2025-07-18 Based Selection l ation nisme de subventions aus as Cross-border Value Chains sociations et coopératives de commerçants BI-BI-MOF-357217-CS-QCBS / Recrutement d'un bureau d' Component 2: Improving Cor Quality And Cost- Open - Internationa Under Implement étude pour l'aménagement e IDA / E0700 Post 400,000.00 0.00 2023-04-24 2023-04-26 2023-04-26 2023-06-12 2023-06-02 2023-07-07 2023-07-28 2023-08-25 2023-09-22 2023-12-29 e Trade Infrastructure Based Selection l ation t modernisation des postes fr ontières de Buganda et Mpar ambo BI-BI-MOF-362749-CS-QCBS / Recrutement d'une ONG po Component 4: Supporting Im Quality And Cost- Open - Internationa Under Implement ur la mise en oeuvre des PAR IDA / E0700 plementation and Monitoring Post 100,000.00 0.00 2023-05-31 2023-05-29 2023-06-07 2023-07-14 2023-08-11 2023-08-25 2023-09-22 2023-10-20 2024-06-28 Based Selection l ation du port de Rumonge et du po and Evaluation ste frontière de Gatumba BI-BI-MOF-365295-CS-QCBS / Recrutement d'un bureau c hargé de l'étude d'aménage Component 2: Improving Cor Quality And Cost- Open - Internationa IDA / E0700 Post 200,000.00 0.00 Under Review 2023-06-12 2023-06-19 2023-06-20 2023-08-03 2023-08-31 2023-09-22 2023-10-20 2023-11-17 2024-02-28 ment et de bitumage des voi e Trade Infrastructure Based Selection l es d'accès aux postes frontiè res de Buganda et Mparamb o BI-BI-MOF-367793-CS-LCS / Component 4: Supporting Im Least Cost Selecti Recrutement d'un cabinet d' IDA / E0700 plementation and Monitoring Post Open - National 15,000.00 0.00 Under Review 2023-06-30 2023-06-27 2023-07-10 2023-08-16 2023-08-23 2023-09-08 2023-09-29 2023-10-27 2024-10-26 on audit interne du projet and Evaluation INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual DMI/002/PFCGL-II/2017 / Ela boration du Cadre de Politiqu e des Peuples Autochtones ( Improving core trade infrastr Individual Consult Pending Impleme CPPA), du Plan en faveur des IDA / V1000 ucture and facilities in the b Post Open 30,000.00 0.00 2017-12-11 2018-01-20 2018-02-06 2018-02-09 2018-03-18 ant Selection ntation populations autochtones (PP order areas A) du Cadre de Politique de R éinstallation (CPR) pour les a ctivitésdu Projet GLTFP BI-BI-MOF-65639-CS-INDV / Improving core trade infrastr Individual Consult IDA / V1000 Post Open 50,000.00 0.00 Canceled 2018-07-27 2018-09-05 2018-09-19 2018-10-04 2018-12-18 Etude sur la logistique et le tr ucture and facilities in the b ant Selection ansport order areas BI-BI-MOF-65645-CS-INDV / Implementation of policy an Enquête auprès des commer d procedural reforms and ca Individual Consult çants des associations profes IDA / V1000 pacity building to facilitate c Post Open 60,000.00 0.00 Canceled 2018-08-05 2018-09-12 2018-09-26 2018-10-10 2019-01-10 ant Selection sionnelles et évaluation des ross-border trade in goods a besoins pour le renforcement nd servic es des capacités BI-BI-MOF-71086-CS-INDV / Implementation support, Co Individual Consult Pending Impleme Consultant Expert en Sauveg IDA / V1000 mmunication, Monitoring, an Post Open 40,800.00 0.00 2018-07-24 2018-10-28 2018-11-20 2018-11-23 2019-05-19 ant Selection ntation ardes Environnementales et d Evaluation Sociales BI-BI-MOF-71104-CS-INDV / Improving core trade infrastr Elaboration du Cadre de Gest Individual Consult Pending Impleme IDA / V1000 ucture and facilities in the b Post Open 16,210.00 0.00 2018-07-24 2018-08-31 2018-09-24 2018-09-25 2018-11-01 ion Environnementale et Soci ant Selection ntation order areas ale (CGES) du Projet GLTFP DMI/006/PFCGL-II/2018 / Con Implementation support, Co Individual Consult Pending Impleme sultant Responsable en Suivi- IDA / V1000 mmunication, Monitoring, an Post Open 40,800.00 0.00 2018-07-24 2018-09-16 2018-12-02 2018-12-03 2019-12-02 ant Selection ntation Evaluation d Evaluation DMI/004/PFCGL-II/2018 / Con Implementation support, Co Individual Consult Under Implement sultant Expert en Facilitation IDA / V1000 mmunication, Monitoring, an Post Open 40,800.00 0.00 2018-01-26 2018-01-25 2018-05-25 2018-05-25 2018-05-28 2019-05-27 ant Selection ation du Commerce d Evaluation BI-BI-MOF-65604-CS-INDV / Implementation support, Co Individual Consult Pending Impleme Consultant Responsable Adm IDA / V1000 mmunication, Monitoring, an Post Open 40,800.00 0.00 2018-06-07 2018-07-10 2018-07-17 2018-07-23 2019-07-22 ant Selection ntation inistratif et Financier d Evaluation DMI/003/PFCGL-II/2018 / Con Implementation support, Co Individual Consult sultant Coordinateur du proje IDA / V1000 mmunication, Monitoring, an Post Open 48,000.00 0.00 Under Review 2018-01-26 2018-01-19 2018-05-10 2018-05-10 2018-05-14 2019-05-13 ant Selection t d Evaluation Page 3 DMI/007/PFCGL-II/2018 / Con Implementation support, Co Individual Consult Pending Impleme sultant Responsable Passatio IDA / V1000 mmunication, Monitoring, an Post Open 40,800.00 0.00 2018-01-26 2018-05-25 2018-05-28 2018-05-28 2019-05-27 ant Selection ntation n des Marchés d Evaluation Implementation support, Co DMI/009/PFCGL-II/2018 / Con Individual Consult IDA / V1000 mmunication, Monitoring, an Post Open 24,000.00 0.00 Under Review 2018-01-26 2018-06-08 2018-06-05 2018-06-07 2018-07-01 2019-06-30 sultant Comptable du projet ant Selection d Evaluation BI-BI-MOF-65720-CS-INDV / Implementation of policy an Enumérateurs et Superviseur d procedural reforms and ca Individual Consult Under Implement s pour l'enquête de base et p IDA / V1000 pacity building to facilitate c Post Open 16,631.00 0.00 2018-06-27 2018-11-05 2018-08-06 2018-08-20 2018-08-31 2018-10-31 ant Selection ation our la collecte des données s ross-border trade in goods a ur le commerce transfrontali nd servic es er BI-BI-MOF-170399-CS-INDV / Recrutement d'un consultant Improving service delivery b Individual Consult pour réaliser l'identification e IDA / V3250 y agencies at the border/por Post Open 30,000.00 43,617.38 Completed 2020-08-25 2020-11-05 2020-10-13 2022-02-21 2020-11-03 2022-02-21 2020-12-08 2021-01-13 2021-02-13 2021-04-24 ant Selection t la cartographie des associat t and citizen engagement ions des commerçants transf rontaliers BI-BI-MOF-170412-CS-INDV / Implementation support, Co Recrutement d'un consultant Individual Consult Pending Impleme IDA / V3250 mmunication, Monitoring, an Post Open 20,000.00 0.00 2020-07-31 2020-09-18 2020-10-09 2020-11-13 2021-01-22 en charge de l'élaboration d' ant Selection ntation d Evaluation une stratégie de communicat ion du projet BI-BI-MOF-182061-CS-INDV / Implementation support, Co Individual Consult Under Implement Conception et réalisation du IDA / V3250 mmunication, Monitoring, an Post Open 20,000.00 0.00 2020-08-24 2023-02-21 2020-10-12 2020-11-02 2020-12-07 2021-01-29 ant Selection ation site web PFCGL-II d Evaluation BI-BI-MOF-182703-CS-CDS / Implementation support, Co Audit comptable et financier IDA / V3250 mmunication, Monitoring, an Post Direct Selection Direct 20,000.00 10,844.85 Completed 2020-08-04 2020-07-15 2020-08-14 2020-08-11 2020-10-09 2020-11-03 2020-11-30 2020-12-29 du projet (exercice de juillet d Evaluation 2019 à juin 2020) BI-BI-MOF-203519-CS-INDV / Improving core trade infrastr Individual Consult Recrutement d'un consultant IDA / V3250 ucture and facilities in the b Post Open 20,000.00 0.00 Canceled 2020-11-17 2020-12-29 2021-01-12 2021-02-09 2021-03-15 ant Selection pour la mise à jour du CGES order areas et du CPR BI-BI-MOF-207798-CS-INDV / Component 1. Improving Poli Individual Consult Under Implement Recrutement d'un expert en i IDA / V3250 cy and Regulatory Environm Post Open 40,000.00 0.00 2020-12-09 2020-12-18 2021-01-20 2022-01-06 2021-02-03 2022-01-11 2021-02-08 2022-01-31 ant Selection ation nfrastructures ent for cross border trade BI-BI-MOF-207950-CS-CDS / Entente Directe avec le Cons Improving core trade infrastr ultant Dr NIYONKURU Charles IDA / V3250 ucture and facilities in the b Post Direct Selection Direct 15,000.00 0.00 Canceled 2020-12-10 2020-12-14 2020-12-24 2021-01-29 pour l'Elaboration du CGES + order areas Plan de Gestion des Pestes et Pesticides (PGPP) BI-BI-MOF-207964-CS-CDS / Entente Directe avec le Cons ultant CIMPAYE Joachim pour Improving core trade infrastr la Mise à jour des rapports d'I IDA / V3250 ucture and facilities in the b Post Direct Selection Direct 10,000.00 0.00 Canceled 2020-12-12 2020-12-22 2021-01-06 2021-02-15 mpact Environnemental et S order areas ocial (EIES) pour la constructi on du Port de Rumonge et la construction du marché de G atumba BI-BI-MOF-207970-CS-CDS / Entente Directe avec le Cons Improving core trade infrastr ultant Dr MISAGO Aloispour l IDA / V3250 ucture and facilities in the b Post Direct Selection Direct 10,000.00 0.00 Canceled 2020-12-18 2020-12-28 2021-01-13 2021-02-19 a Préparation du Plan dActio order areas n de Réinstallation (PAR) des Personnes affectées pour la c onstruction du Port de Rumo nge BI-BI-MOF-225823-CS-CDS / Entente Directe avec Monsie ur NDIKUMANA Denis pour l'a Improving core trade infrastr ctualisation/mise à jour des E IDA / V0960 ucture and facilities in the b Post Direct Selection Direct 10,000.00 9,834.66 Completed 2021-03-24 2021-03-24 2021-03-26 2021-03-25 2021-04-02 2021-03-31 2021-05-03 2021-10-20 IES du sous-projet de constru order areas ction du port de Rumonge et celui de construction du mar ché transfrontalier de Gatum ba BI-BI-MOF-239602-CS-CDS / Implementation support, Co Entente Directe avec le bure IDA / V0960 mmunication, Monitoring, an Post Direct Selection Direct 79,400.00 70,447.09 Signed 2021-06-22 2021-06-17 2021-07-02 2022-02-15 2021-07-30 2021-10-06 2022-01-14 au GETA pour pour l'élaborat d Evaluation ion du CGES du PFCIGL BI-BI-MOF-207962-CS-CDS / Entente Directe avec le Cons ultant BARAKAMFITIYE Tharci Improving core trade infrastr sse pour l'Elaboration du Cad IDA / V3250 ucture and facilities in the b Post Direct Selection Direct 15,000.00 0.00 Canceled 2020-12-11 2020-12-21 2021-01-12 2021-02-16 re de Politique de Réinstallati order areas on (CPR) + Cadre de Planifica tion en faveur des Peuples A utochtones (CPPA) BI-BI-MOF-246029-CS-CDS / Implementation support, Co Entente directe avec Madam IDA / V0960 mmunication, Monitoring, an Post Direct Selection Direct 26,000.00 33,246.84 Signed 2021-07-30 2021-07-28 2021-08-09 2021-09-03 2021-10-13 2021-05-12 2021-11-01 e Clotilde NIZIGAMA, Coordo d Evaluation nnateur du projet pour l'Actu alisation du contrat BI-BI-MOF-246032-CS-CDS / Entente directe avec Mr BAT Implementation support, Co UNGWANAYO Léonidas, Resp IDA / V0960 mmunication, Monitoring, an Post Direct Selection Direct 21,600.00 30,476.27 Signed 2021-07-30 2021-07-29 2021-08-09 2021-09-02 2021-10-13 2021-07-27 2022-04-30 onsable Administratif et Fina d Evaluation ncier pour l'Actualisation du contrat BI-BI-MOF-246034-CS-CDS / Entente directe avec Monsie Implementation support, Co ur Cyprien BARAMBONERANY IDA / V0960 mmunication, Monitoring, an Post Direct Selection Direct 24,700.00 27,710.10 Signed 2021-07-30 2021-07-29 2021-08-09 2021-09-02 2021-10-13 2021-05-29 2022-04-30 E, Responsable de la Passati d Evaluation on des Marchés pour l'actuali sation du contrat BI-BI-MOF-246037-CS-CDS / Entente directe avec Mr BIRE Implementation support, Co HANISENGE Adophe, Expert IDA / V0960 mmunication, Monitoring, an Post Direct Selection Direct 24,800.00 30,224.40 Signed 2021-07-30 2021-07-29 2021-08-09 2021-09-03 2021-10-13 2021-05-29 2022-04-30 en Facilitation du Commerce d Evaluation et Secteur Privé pour l'actuali sation du contrat BI-BI-MOF-246040-CS-CDS / Entente directe avec Madam Implementation support, Co e KABURA Marie Rose, Respo IDA / V0960 mmunication, Monitoring, an Post Direct Selection Direct 19,800.00 27,705.70 Signed 2021-07-30 2021-07-29 2021-08-09 2021-09-03 2021-10-13 2021-07-21 2022-04-30 nsable des Sauvegardes envi d Evaluation ronnementales pour l'actuali sation du contrat BI-BI-MOF-246044-CS-CDS / Implementation support, Co Entente directe avec Mr Césa IDA / V0960 mmunication, Monitoring, an Post Direct Selection Direct 19,800.00 27,705.70 Signed 2021-07-30 2021-07-29 2021-08-09 2021-09-02 2021-10-13 2021-06-08 2022-04-30 r Abel MAYELE pour l'actualis d Evaluation ation du contrat Page 4 BI-BI-MOF-246046-CS-CDS / Implementation support, Co Entente directe avec Madam IDA / V0960 mmunication, Monitoring, an Post Direct Selection Direct 17,700.00 16,623.42 Signed 2021-07-30 2021-07-28 2021-08-09 2021-09-03 2021-10-13 2021-07-01 2022-04-30 e NIYOKINDI Consolée pour l' d Evaluation actualisation du contrat BI-BI-MOF-253433-CS-INDV / Implementation support, Co Individual Consult Réalisation d'une enquête de IDA / V0960 mmunication, Monitoring, an Post Open 45,000.00 41,703.71 Signed 2021-09-17 2021-09-17 2021-10-29 2022-02-15 2021-11-05 2022-02-15 2021-11-16 2021-12-16 2022-05-15 ant Selection base dans la zone du PFCIGL d Evaluation BI-BI-MOF-257902-CS-INDV / Entente Directe avec Monsie ur Denis NDIKUMANA pour l'É Component 2: Improving Cor Individual Consult laboration du PAR pour la co IDA / V3250 Post Direct 12,000.00 14,557.51 Signed 2021-10-25 2021-11-22 2021-11-04 2022-02-01 2021-11-15 2022-02-01 2021-11-21 2021-12-14 2021-12-31 e Trade Infrastructure ant Selection nstruction du port de Rumon ge et l’actualisation du PAR p our le poste frontière de Gat umba BI-BI-MOF-262743-CS-CDS / Entente Directe avec la firme CHEMAS pour l'élaboration d Component 2: Improving Cor e l'EIES/PGES et du PAR de la IDA / V3250 Post Direct Selection Direct 420,000.00 0.00 Canceled 2021-11-15 2021-11-19 2022-01-14 2022-02-28 e Trade Infrastructure RN3, projet pilote TNM, du Bo ulevard NDADAYE et du Cont ournement Ouest de Bujumb ura pour le PRT BI-BI-MOF-262749-CS-CDS / Entente Directe avec la firme CHEMAS pour l'assistance te chnique en sauvegardes envi Component 2: Improving Cor ronnementales et sociales et IDA / V3250 Post Direct Selection Direct 300,000.00 0.00 Canceled 2021-11-15 2021-11-21 2022-01-05 2022-03-15 e Trade Infrastructure la préparation des dossiers d u Cadre Environnemental et Social pour PRT et le contrô le qualité des documents de sauvegarde du PFCIGL BI-BI-MOF-303392-CS-CDS / Entente Directe avec Mr NIVY Component 4: Supporting Im Under Implement INTIZO Scarie pour l'élaborati IDA / V3940 plementation and Monitoring Post Direct Selection Direct 50,000.00 0.00 2022-07-13 2022-08-11 2022-07-23 2022-10-18 2022-08-30 2022-10-29 ation on des manuels de procédur and Evaluation es et d'execution du Projet BI-BI-MOF-303396-CS-INDV / Component 2: Improving Cor Individual Consult Pending Impleme Etude de rentabilité du marc IDA / V3940 Post Open 50,000.00 0.00 2022-08-15 2022-10-03 2022-10-24 2022-11-28 2023-01-27 e Trade Infrastructure ant Selection ntation hé transfrontalier de Gatumb a BI-BI-MOF-303470-CS-INDV / Component 4: Supporting Im Individual Consult Under Implement Recrutement d'un spécialiste IDA / V3940 plementation and Monitoring Post Open 3,500.00 0.00 2022-07-29 2022-08-24 2022-09-16 2022-10-07 2022-11-11 2023-02-10 ant Selection ation en communication and Evaluation BI-BI-MOF-303472-CS-INDV / Component 4: Supporting Im Individual Consult Under Implement Recrutement d'un spécialiste IDA / V3940 plementation and Monitoring Post Open 4,000.00 0.00 2022-08-04 2022-09-12 2022-09-22 2022-10-13 2022-11-17 2023-02-16 ant Selection ation en VBG and Evaluation BI-BI-MOF-303474-CS-INDV / Component 4: Supporting Im Individual Consult Under Implement Recrutement d'un spécialiste IDA / V3940 plementation and Monitoring Post Open 4,000.00 0.00 2022-08-10 2022-09-06 2022-09-28 2022-10-19 2022-11-23 2023-02-22 ant Selection ation en Développement social and Evaluation BI-BI-MOF-304400-CS-INDV / Actualisation de l'étude d'im Component 4: Supporting Im pact environnemental et soci Individual Consult Under Implement IDA / V3250 plementation and Monitoring Post Open - National 15,000.00 0.00 2022-07-19 2022-08-09 2022-09-06 2022-09-27 2022-11-01 2022-12-06 al (EIES) pour la construction ant Selection ation and Evaluation et modernisation du poste fr ontière de Gatumba-Kavimvir a BI-BI-MOF-312567-CS-CDS / Component 4: Supporting Im Entente Directe avec le cabin Direct - Internation Under Implement IDA / V3250 plementation and Monitoring Post Direct Selection 15,000.00 0.00 2022-09-06 2022-09-19 2022-09-16 2022-10-14 2022-11-11 2022-12-15 et pour l'audit comptable et f al ation and Evaluation inancier exercice de juillet 20 21 à juin 2022 BI-BI-MOF-319230-CS-INDV / Recrutement d'un Consultant pour l'élaboration d'une étud Component 1. Improving Poli e sur les natures et causes d Individual Consult Pending Impleme IDA / E0700 cy and Regulatory Environm Post Open - National 30,000.00 0.00 2022-12-15 2023-02-02 2023-02-23 2023-03-16 2023-05-30 es conflits entre les administr ant Selection ntation ent for cross border trade ations des frontières et les co mmerçants, entre les service s ou entre les commerçants au niveau des frontières ciblé es du projet BI-BI-MOF-319247-CS-INDV / Réalisation de l'Etude d'Impa ct Environnemental et Social Component 2: Improving Cor Individual Consult Pending Impleme IDA / E0700 Post Open - National 25,000.00 0.00 2023-04-20 2023-06-08 2023-06-22 2023-07-13 2023-09-22 (EIES) des travaux d'aménag e Trade Infrastructure ant Selection ntation ement et modernisation des i nfrastructures du poste fronti ère de Vugizo-Kiliba BI-BI-MOF-319248-CS-INDV / Recrutement d'un consultant pour la préparation du plan d Component 2: Improving Cor Individual Consult Pending Impleme 'action de réinstallation des t IDA / E0700 Post Open - National 30,000.00 0.00 2023-04-27 2023-06-08 2023-06-22 2023-07-13 2023-09-29 e Trade Infrastructure ant Selection ntation ravaux d'aménagement et m odernisation des infrastructur es du poste frontière de Vugi zo-Kiliba BI-BI-MOF-335993-CS-INDV / Component 4: Supporting Im Individual Consult Under Implement Recrutement d'un assistant e IDA / E0700 plementation and Monitoring Post Open - National 36,000.00 0.00 2023-01-18 2023-01-19 2023-02-15 2023-03-08 2023-03-30 2024-03-29 ant Selection ation n passation des marchés and Evaluation BI-BI-MOF-335996-CS-INDV / Component 4: Supporting Im Individual Consult Under Implement Recrutement d'un assistant c IDA / E0700 plementation and Monitoring Post Open - National 36,000.00 0.00 2023-01-26 2023-01-30 2023-03-01 2023-03-15 2023-04-05 2024-04-04 ant Selection ation omptable and Evaluation BI-BI-MOF-344280-CS-QCBS Component 4: Supporting Im / Recrutement d'un bureau p Individual Consult Open - Internationa IDA / E0700 plementation and Monitoring Post 100,000.00 0.00 Canceled 2023-03-31 2023-04-03 2023-05-03 2023-05-24 2023-06-21 2023-09-29 our effectuer un audit techni ant Selection l and Evaluation que du Bureau Burundais de Normalisation (BBN) BI-BI-MOF-353142-CS-INDV / Recrutement d'un consultant Component 2: Improving Cor Individual Consult Under Implement individuel pour la conception IDA / E0700 Post Open - National 20,000.00 0.00 2023-03-31 2023-04-03 2023-05-03 2023-05-17 2023-06-16 2023-08-16 e Trade Infrastructure ant Selection ation des infrastructures provisoire s aux postes frontières de Bu ganda et Mparambo Page 5 BI-BI-MOF-360296-CS-CDS / Entente Directe avec le cabin Component 4: Supporting Im Direct - Internation Under Implement et ABC pour l'audit comptabl IDA / E0700 plementation and Monitoring Post Direct Selection 15,000.00 0.00 2023-05-12 2023-05-20 2023-05-22 2023-05-29 2023-07-26 2023-11-15 al ation e et financier de l'exercice de and Evaluation juillet 2022 à juin 2023 BI-BI-MOF-364126-CS-INDV / RECRUTEMENT D'UN CONSUL TANT CHARGE D'EFFECTUER Component 3: Supporting Co UN AUDIT TECHNIQUE ET INS Individual Consult Open - Internationa IDA / E0700 mmercialization of Selected Post 100,000.00 0.00 Under Review 2023-06-05 2023-06-05 2023-07-17 2023-07-31 2023-09-04 2023-11-17 TITUTIONNEL DU BUREAU BU ant Selection l Cross-border Value Chains RUNDAIS DE NORMALISATIO N ET CONTROLE DE LA QUALI TE (BBN) EN MATIERE DE CE RTIFICATION BI-BI-MOF-365300-CS-INDV / Component 4: Supporting Im Recrutement d'un consultant Individual Consult Pending Impleme IDA / E0700 plementation and Monitoring Post Open - National 25,000.00 0.00 2023-07-20 2023-08-31 2023-09-14 2023-10-19 2023-12-15 pour l'élaboration du plan de ant Selection ntation and Evaluation gestion de la biodiversité Page 6 Procurement Plan I. General 1. Project Information Country : Kenya Recipient : Republic of Kenya Project Name : National Agriculture and Rural Inclusive Growth Loan Credit No. : IDA 59000 2. Date of General Procurement Notice : 9th February 2018 3. Period Covered by this procurement plan : 18 months II. Goods, Works, and Non-Consulting Services 1. Thresholds for the Method of Procurement: Method of Procurement Thresholds for Method (US$ equivalent) Open International (Goods) Equal to or more than 3 million Open National ( Goods) – Open < $3 million Tender as per PPDA 2015 RFQ (Goods) Less than 20,000 or as stipulated in Kenya Procurement Regulations 2017 Open International (Works) Equal to or more than 15 million Open National (Works) - Open Less than 15 million Tender as per PPDA 2015 RFQ (works) Less than 20,000 or as stipulated in Kenya Procurement Regulations 2017 Method of Procurement Thresholds for Method (US$ equivalent) Open International (Non-consulting Equal to or More than 3 million Services) Open National (Non-consulting Less than 3 million Services) - Open Tender as per PPDA 2015 Direct Contracting No threshold; meet requirements of Bank’s Procurement Regulations Prior Review: The details of the Procurement review / oversight are defined in the Annex II of the Regulations for borrowers. The following would be subject to Prior review of the Bank regardless of the Method of selection (Project Procurement Risk Rating is “High”): (a) Goods, information technology and Non-consulting Services: First procurement under the project irrespective of value and all procurements estimated to cost more than USD 1.5 million (b) Works (including turnkey, supply & installation of plant and equipment and PPP); First procurement under the project irrespective of value and all procurements estimated to cost more than USD 5 million and The prior review thresholds will be reviewed during the implementation of the project and modified, based on the risk assessment. 2. For contracts subject to prior review, the Borrower shall seek the Bank’s no objection before agreeing to: a. an extension of the stipulated time for execution of a contract that has an impact on the planned completion of the project; b. any material modification of the scope of the Works, Goods, Non- consulting services or Consulting Services, or other significant changes to the terms and conditions of the contract; c. any variation order or contract amendment (except in cases of extreme urgency), including due to extension of time, that singly or combined with all previous variation orders or amendments, increases the original contract amount by more than 15% (fifteen percent); or d. the proposed termination of the contract. The Borrower / IA shall provide a copy of all amendments to the contract to the Bank for its records. 3. Prequalification Not Applicable Domestic Preference. The provision of domestic preference shall be applied in the procurement of goods following international market approach in accordance with Annex VI of the Regulations. Domestic preference shall not apply in the procurement of works. 4. Reference to Standard Procurement Documents Bank’s Standard RFB Goods and RFP Consulting Services dated July 2016 will be used as a base and incorporating suitable modifications and the same would be agreed with the Bank subject international competition. 5. Any Other Special Procurement Arrangements A. Procurement approach under CDD Approach by Communities: Applicable if stipulated in the PAD. B. When approaching the national market, as agreed in the Procurement Plan, the Open Tender procedure of Public Procurement and Asset Disposal Act 2015 and Regulations 2017 may be used. The specific Requirements for national open competitive procurement include the following: a. open advertising of the procurement opportunity at the national level; b. the procurement is open to eligible firms from any country; c. the request for bids/request for proposals document shall require that Bidders/Proposers submitting Bids/Proposals present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights; d. contracts with an appropriate allocation of responsibilities, risks, and liabilities; e. publication of contract award information; f. rights for the Bank to review procurement documentation and activities; g. an effective complaints mechanism; and h. maintenance of records of the Procurement Process. Other national procurement arrangements (other than national open competitive procurement), that may be applied by the Borrower (such as limited/restricted competitive bidding, request for quotations/shopping, direct contracting), shall be consistent with the Bank’s Core Procurement Principles and ensure that the Bank’s Anti-Corruption Guidelines and Sanctions Framework and contractual remedies set out in its Legal Agreement apply. In all cases, the national procurement procedures to be used shall give due attention to quality aspects. 6. The bid evaluation will be carried out according to the agreed timeline in the Procurement Activity Schedule. III. Selection of Consultants 1. Methods and Prior Review Threshold Selection methods of procurement of Consultants' Services (Firms): The Approved Selection Methods as reflected in the Section VII of the procurement regulations Method of Procurement Thresholds for Methods Quality and Cost Based As per requirements of para 7.3 of the Selection (QCBS) Regulations Quality Based Selection As per requirements of para 7.8 to 7.10 (QBS) of the Regulations Selection based on a Fixed As per requirements of para 7.4 and 7.5 of the Budget (FBS) Regulations Selection Based on Least As per requirements of para 7.6 and 7.7 of the Cost Basis (LCS) Regulations Selection based on As per requirements of para 7.11 and 7.12 of Consultant’s Qualification the Regulations (CQ) Direct Must meet the requirements of Para 7.13 to 7.15 of the Regulations, and with prior agreement in PP with the Bank. The short list may consist of all National consultants in case the estimated cost is less than USD 300,000 Procurement methods for Selection of Individual Consultants (IC): The Approved Selection Methods as reflected in the Section VII of the procurement regulations Method of Procurement Thresholds for Methods Open Competitive As per requirements of para 7.36 and 7.37 of Selection the Regulations Limited Competitive As per requirements of para 7.38 of the Selection Regulations Direct Must meet the requirements of Para 7.39 of the Regulations, and with prior agreement in PP with the Bank *Shall meet the requirements as stated in Regulations Prior Review Thresholds: The details of the Procurement review / oversight are defined in the Annex II of the Regulations for borrowers. The following would be subject to Prior review of the Bank regardless of the Method of selection: (a). Consulting Firm: First procurement under the project irrespective of value and all procurements estimated to cost more than USD 0.5 million. (b). Individual Consultant: all procurements estimated to cost more than USD 0.2 million Terms of Reference (ToR) for all consultant contracts shall be furnished to the Bank for its prior review and No Objection. PROCUREMENT Kenya : National Agricultural and Rural Inclusive Growth Project PLAN General Information Country: Kenya 2019-10-04 Bank’s Approval Date of the Original Procurement Plan: 2023-06-05 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P153349 GPN Date: 2018-02-09 Project Name: National Agricultural and Rural Inclusive Growth Project Loan / Credit No: IDA / 59000 Kisii County Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned KE-KISII COUNTY-140174-CW Project Coordination and Ma Request for Quota Single Stage - One E 2020-06-1 -RFQ / renovation works at A IDA / 59000 Post Limited 14,041.42 14,190.45 Completed 2019-10-19 2019-11-08 2019-12-14 2019-12-05 nagement tions nvelope 1 TC NARIGP offices KE-KISII COUNTY-167455-CW Supporting County Communi Single Stage - One E 2021-03-1 -RFB / proposed construction IDA / 59000 Post Request for Bids Open - National 1,000,000.00 850,110.00 Completed 2020-04-21 2020-04-28 2020-04-28 2020-09-15 2020-05-01 2020-09-15 2020-05-06 2020-06-05 2020-05-16 2020-07-18 ty-Led Development nvelope 2 of nyamache banana market KE-KISII COUNTY-216089-CW -RFQ / proposed construction Supporting County Communi Request for Quota Single Stage - One E 2021-06-0 IDA / 59000 Post Limited 57,504.25 0.00 Signed 2021-02-13 2022-07-01 2021-03-09 of watershed hotspot activiti ty-Led Development tions nvelope 7 es in Nyamesocho KE-KISII COUNTY-216087-CW Supporting County Communi Request for Quota Single Stage - One E 2021-06-0 -RFQ / proposed construction IDA / 59000 Post Limited 64,596.77 0.00 Signed 2021-02-13 2022-07-08 2021-03-05 ty-Led Development tions nvelope 3 of watershed hotspot activiti es in Nyakani KE-KISII COUNTY-320530-CW Request for Bids - Strengthening Producer Org -RFB / Proposed Construction Single Stage - One E Small Works SPD 2023-06-3 IDA / 59000 anizations and Value Chain Post Request for Bids Open - National 370,278.54 0.00 Signed 2022-10-11 2022-10-17 2022-10-21 2022-12-15 2022-11-20 2022-11-11 2022-12-04 2022-11-18 2023-01-01 of Magena Vegetable Aggreg nvelope (1 envelope proce 0 Development ation & Marketing Centre ss) KE-KISII COUNTY-320531-CW Request for Bids - Strengthening Producer Org -RFB / Proposed Construction Single Stage - One E Small Works SPD 2023-06-3 IDA / 59000 anizations and Value Chain Post Request for Bids Open - National 370,278.54 0.00 Signed 2022-10-11 2022-10-17 2022-10-21 2022-12-15 2022-11-20 2022-11-11 2022-12-04 2022-11-18 2023-01-01 of Marani Vegetable Aggrega nvelope (1 envelope proce 0 Development tion & Marketing Centre ss) GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual KE-KISII COUNTY-138534-GO Supporting County Communi Single Stage - One E IDA / 59000 Post Request for Bids Open - National 100,000.00 6,254.81 Completed 2019-10-03 2019-10-04 2019-10-05 2019-10-04 2019-11-04 2019-10-04 2019-11-18 2019-10-04 2019-12-23 2019-10-04 2020-01-22 2019-10-04 -RFB / procurement of motor ty-Led Development nvelope cycles KE-KISII COUNTY-144916-GO Project Coordination and Ma Request for Quota Single Stage - One E -RFQ / purchase of 20 cabine IDA / 59000 Post Limited 7,350.00 2,579.61 Completed 2019-12-25 2020-04-14 2020-01-16 2020-04-25 2020-01-31 2020-05-13 nagement tions nvelope ts for cddc and 1 executive t able for cessco KE-KISII COUNTY-144917-GO Supporting Community-Driv Request for Quota Single Stage - One E -RFQ / Agricultural Materials, IDA / 59000 Post Limited 40,220.00 37,067.28 Completed 2020-01-01 2020-06-03 2020-01-23 2020-07-01 2020-02-07 2020-12-24 en Development tions nvelope Supplies and Small Equipme nt KE-KISII COUNTY-148933-GO Project Coordination and Ma Request for Quota Single Stage - One E IDA / 59000 Post Limited 10,000.00 7,376.67 Completed 2019-12-25 2020-04-20 2020-01-16 2020-05-01 2020-01-31 2020-06-20 -RFQ / Purchase of laptops nagement tions nvelope KE-KISII COUNTY-167453-GO Project Coordination and Ma Request for Quota Single Stage - One E IDA / 59000 Post Limited 80,000.00 73,364.06 Completed 2020-04-28 2020-06-05 2020-05-17 2020-06-20 2020-06-16 2020-07-17 -RFB / purchase of motorcycl nagement tions nvelope es KE-KISII COUNTY-169149-GO -RFQ / procurement of install Project Coordination and Ma Request for Quota Single Stage - One E IDA / 59000 Post Limited 63,000.00 69,555.28 Completed 2020-04-26 2020-05-05 2020-05-18 2020-05-15 2020-06-17 2020-08-21 ation and commissioning of I nagement tions nvelope P based audio-visual teleconf erence system KE-KISII COUNTY-173312-GO -RFQ / Supply and Installation Project Coordination and Ma Request for Quota Single Stage - One E IDA / 59000 Post Limited 13,000.00 69,555.28 Completed 2020-05-15 2020-05-05 2020-05-30 2020-05-15 2020-06-29 2020-08-21 of Video Conferencing Equip nagement tions nvelope ment (IP network connectivit y, firewall and router) KE-KISII COUNTY-206421-GO Supporting County Communi Request for Quota Single Stage - One E IDA / 59000 Post Limited 1,318.00 12,223.77 Completed 2020-12-05 2020-12-16 2020-12-19 2021-01-07 2021-01-18 2021-01-26 -RFQ / purchase of farm tools ty-Led Development tions nvelope KE-KISII COUNTY-206426-GO Supporting County Communi Request for Quota Single Stage - One E IDA / 59000 Post Limited 36,360.00 16,351.23 Completed 2020-12-05 2020-12-16 2020-12-19 2020-12-30 2021-01-18 2021-02-03 -RFQ / purchase of agricultur ty-Led Development tions nvelope al items KE-KISII COUNTY-206430-GO Supporting County Communi Request for Quota Single Stage - One E -RFQ / procurement of publis IDA / 59000 Post Limited 4,000.00 3,594.18 Completed 2020-12-05 2020-12-16 2020-12-19 2020-12-29 2021-01-18 2021-04-27 ty-Led Development tions nvelope hing and printing materials KE-KISII COUNTY-206438-GO Supporting County Communi Request for Quota Single Stage - One E IDA / 59000 Post Limited 4,000.00 3,639.74 Completed 2020-12-05 2020-12-16 2020-12-19 2020-12-30 2021-01-18 2021-01-16 -RFQ / purchase of phones ty-Led Development tions nvelope KE-KISII COUNTY-206429-GO Supporting County Communi Request for Quota Single Stage - One E IDA / 59000 Post Limited 825.00 767.44 Completed 2021-01-31 2020-12-16 2021-02-14 2020-12-31 2021-03-16 2021-01-29 -RFQ / purchase of roadshow ty-Led Development tions nvelope items KE-KISII COUNTY-276686-GO Project Coordination and Ma Request for Quota Single Stage - One E -RFQ / Purchase of smart pho IDA / 59000 Post Limited 2,000.00 0.00 Signed 2022-02-24 2022-07-01 2022-03-20 2022-04-19 nagement tions nvelope nes for County A.I service pro viders KE-KISII COUNTY-276688-GO Project Coordination and Ma Request for Quota Single Stage - One E IDA / 59000 Post Limited 300.00 0.00 Signed 2022-02-24 2022-07-01 2022-03-20 2022-04-19 -RFQ / Purchase of speakers nagement tions nvelope KE-KISII COUNTY-276690-GO Project Coordination and Ma Request for Quota Single Stage - One E IDA / 59000 Post Limited 2,228.00 0.00 Signed 2022-02-24 2022-06-08 2022-03-20 2022-04-19 -RFQ / Purchase of stickers a nagement tions nvelope nd reflectors Page 1 KE-KISII COUNTY-276692-GO -RFQ / procurement of Web-b Project Coordination and Ma Request for Quota Single Stage - One E ased Dashboard and Analytic IDA / 59000 Post Limited 8,000.00 0.00 Signed 2022-02-24 2022-07-14 2022-03-20 2022-04-19 nagement tions nvelope s Application plus Android Da ta Collection Application KE-KISII COUNTY-276697-GO Project Coordination and Ma Request for Quota Single Stage - One E -RFQ / procurement of Specia IDA / 59000 Post Limited 3,654.00 0.00 Signed 2022-02-24 2022-07-01 2022-03-20 2022-04-19 nagement tions nvelope lly designed Android Tablet KE-KISII COUNTY-276699-GO Project Coordination and Ma Request for Quota Single Stage - One E -RFQ / procurement of Smart IDA / 59000 Post Limited 6,786.00 0.00 Signed 2022-02-24 2022-07-01 2022-03-20 2022-04-19 nagement tions nvelope Digital Projector with Android OS KE-KISII COUNTY-276700-GO Project Coordination and Ma Request for Quota Single Stage - One E IDA / 59000 Post Limited 2,955.00 0.00 Signed 2022-02-24 2022-07-01 2022-03-20 2022-04-19 -RFQ / procurement of Ruka nagement tions nvelope device KE-KISII COUNTY-276703-GO Project Coordination and Ma Request for Quota Single Stage - One E -RFQ / procurement of Agripr IDA / 59000 Post Limited 9,396.00 0.00 Signed 2022-02-24 2022-07-01 2022-03-20 2022-04-19 nagement tions nvelope eneurs Digital platform Licen se KE-KISII COUNTY-276708-GO Project Coordination and Ma Request for Quota Single Stage - One E -RFQ / procurement of EQUIP IDA / 59000 Post Limited 12,000.00 0.00 Signed 2022-02-24 2022-06-08 2022-03-20 2022-04-19 nagement tions nvelope MENT & LINCENSING KE-KISII COUNTY-363805-GO -RFQ / Procurement of 3no d Supporting County Communi Request for Quota Single Stage - One E Under Imple IDA / 59000 Post Open - National 3,254.00 0.00 2023-06-02 2023-06-23 2023-07-23 esktop computers,backup an ty-Led Development tions nvelope mentation d printers for 3 saccos KE-KISII COUNTY-363826-GO Supporting Community-Driv Request for Quota Single Stage - One E Under Imple -RFQ / Procurement of Hass A IDA / 59000 Post Open - National 8,586.00 0.00 2023-06-05 2023-07-02 2023-08-01 en Development tions nvelope mentation vocado Seedlings KE-KISII COUNTY-363820-GO Project Coordination and Ma Under Imple -DIR / Procurement of soil dig IDA / 59000 Post Direct Selection Direct - National 7,549.00 0.00 2023-06-14 2023-06-13 2023-06-17 2023-06-12 2023-07-04 2023-08-03 nagement mentation ital testing kit (soil pal) NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual KE-KISII COUNTY-171191-CS Supporting Community-Driv Consultant Qualifi -CQS / service provider for ba IDA / 59000 Post Open - National 50,000.00 23,154.47 Completed 2020-05-12 2020-08-17 2020-05-19 2020-06-09 2020-08-21 2020-06-12 2021-01-14 2020-06-26 2021-01-19 2021-12-28 2022-01-05 en Development cation Selection nana value chain KE-KISII COUNTY-171198-CS Supporting Community-Driv Consultant Qualifi -CQS / service provider for da IDA / 59000 Post Open - National 50,000.00 23,145.91 Completed 2020-05-12 2020-08-17 2020-05-19 2020-06-09 2020-08-21 2020-06-12 2021-01-10 2020-06-26 2021-01-19 2021-12-28 2022-01-05 en Development cation Selection iry (cow) value chain KE-KISII COUNTY-171199-CS Supporting Community-Driv Consultant Qualifi -CQS / service provider for lo IDA / 59000 Post Open - National 50,000.00 23,073.65 Completed 2020-05-12 2020-08-17 2020-05-19 2020-06-09 2020-08-21 2020-06-12 2021-01-10 2020-06-26 2021-01-19 2021-12-28 2022-01-05 en Development cation Selection cal vegetable value chain KE-KISII COUNTY-171200-CS Supporting Community-Driv Consultant Qualifi -CQS / service provider for ch IDA / 59000 Post Open - National 50,000.00 23,158.88 Completed 2020-05-12 2020-08-17 2020-05-19 2020-06-09 2020-08-21 2020-06-12 2021-01-10 2020-06-26 2021-01-19 2021-12-28 2022-01-05 en Development cation Selection icken value chain INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual KE-KISII COUNTY-276269-CS -INDV / Procurement of consu Supporting Community-Driv Individual Consult IDA / 59000 Post Limited 26,408.45 0.00 Canceled 2022-02-02 2022-02-07 2022-02-28 2022-04-04 2022-10-01 ltancy services to support FI en Development ant Selection MG in selected Saccos Page 2 Sample Procurement Plan (Text in italic font is meant for instruction to staff and should be deleted in the final version of the PP) (This is only a sample with the minimum content that is required to be included in the PAD. The detailed procurement plan is still mandatory for disclosure on the Bank’s website in accordance with the guidelines. The initial procurement plan will cover the first 18 months of the project and then updated annually or earlier as necessary). I. General 1. Bank’s approval Date of the procurement Plan [Original: December 2007]: Revision 15 of Updated Procurement Plan, June 2010] 2. Date of General Procurement Notice: Dec 24, 2006 3. Period covered by this procurement plan: The procurement period of project covered from year June 2010 to December 2012 II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: [Thresholds for applicable procurement methods (not limited to the list below) will be determined by the Procurement Specialist /Procurement Accredited Staff based on the assessment of the implementing agency’s capacity.] Procurement Method Prior Review Comments Threshold US$ 1. ICB and LIB (Goods) Above US$ 500,000 All 2. NCB (Goods) Above US$ 100,000 First contract 3. ICB (Works) Above US$ 15 million All 4. NCB (Works) Above US$ 5 million All 5. (Non-Consultant Services) Below US$ 100,000 First contract [Add other methods if necessary] 2. Prequalification. Bidders for _Not applicable_ shall be prequalified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines. July 9, 2010 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: [Refer to the relevant CDD project implementation document approved by the Bank or delete if not applicable] 4. Reference to (if any) Project Operational/Procurement Manual: Project Implementation Manual for World Bank Loan Project XYZ 04/01/2010 issued by 5. Any Other Special Procurement Arrangements: [including advance procurement and retroactive financing, if applicable] 5 ICB works packages will be financed under retroactive financing 6. Summary of the Procurement Packages planned during the first 18 months after project effectiveness ( including those that are subject to retroactive financing and advanced procurement) [List the Packages which require Bank’s prior review first and then the other packages] 1 2 3 4 5 6 7 Ref. Descripti Estimat Packages Dome Review Comme No. on ed stic by Bank nts Cost Prefe (Prior / US$ rence Post) million (yes/ no) Summary 82 5 No Prior of the ICB (Works) Summary 43.77 15 No Prior of the ICB (Goods) Summary 64.53 18 No Post 1st of the NCB contrac (Works) t for Prior Review Summary 1.86 4 No Post 1st of the NCB contrac (Goods) t for Prior Review Summary 0.45 1 No Prior of the ICB (Non- Consultant Services) July 9, 2010 III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Comments Threshold 1. Competitive Methods (Firms) Above US$ 100,000 2. Single Source (Firms) All 3. Individual Above US$ 50,000 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_300,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: [including advance procurement and retroactive financing, if applicable or delete if not applicable] 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 Ref. No. Description Estimat Package Review Comment of ed s by Bank s Assignmen Cost (Prior / t US$ Post) million Summary 4.17 7 Prior of number of contracts that will be let under QCBS Summary 0.83 1 Prior CQS of number of contracts that will be let under other July 9, 2010 methods July 9, 2010 PROCUREMENT Tanzania : Citizen-Centric Judicial Modernization and Justice Service Delivery PLAN General Information Country: Tanzania 2016-08-05 Bank’s Approval Date of the Original Procurement Plan: 2023-06-06 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P155759 GPN Date: 2022-06-09 Project Name: Citizen-Centric Judicial Modernization and Justice Service Delivery Loan / Credit No: IDA / 57780, IDA / 70580 Judiciary of Tanzania Executing Agency(ies): WORKS Activity Reference No. / Procureme Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH Ri Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method nt Docume ount (US$ and Recommendation Signed Contract o. h cess (Y/N) sk atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion nt Type ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TZ-JUDICIARY TZ-18206-CW- Component 2: Skills Develop DIR / Construction of training 2018-03-0 2020-01 IDA / 57780 ment, Inspection and Perfor Prior Direct Selection Direct 35,175.53 Completed 2017-07-14 2017-06-29 2017-07-19 2017-08-22 2017-09-06 2017-08-24 room at Kisutu Residence Ma 5 -22 mance Management gistrate Court location in Dar es Salaam TZ-JUDICIARY TZ-118965-C W-RFB / Construction of Integ rated Justice Centers (IJCs) in Component 3: Access to Just Open - Internationa Single Stage - One E 22,309,086. 2020-04-1 IDA / 57780 Prior Request for Bids Signed 2019-06-28 2019-07-31 2019-07-03 2019-08-01 2019-08-14 2019-09-20 2019-09-13 2019-12-04 2019-10-18 2020-01-11 Six Selected Locations of Mw ice and Public Trust l nvelope 76 5 anza, Morogoro, Arusha, Dod oma and Dar es Salaam-Six L ots TZ-JUDICIARY TZ-211158-C W-RFB / Construction of Subo Component 3: Access to Just Single Stage - One E 7,950,439.8 2021-09-0 IDA / 57780 Prior Request for Bids Open - National Signed 2020-12-28 2021-02-04 2021-01-04 2021-02-11 2021-02-08 2021-03-23 2021-02-28 2021-08-24 2021-04-04 2021-09-11 rdinate Courts in twenty five( ice and Public Trust nvelope 1 1 25) Selected Locations aroun d Tanzania. TZ-JUDICIARY TZ-364564-C Request for B W-RFB / Construction of Integ ids - Small W Component 3: Access to Just Open - Internationa Single Stage - One E Under Revie 2024-06-1 rated Justice Centers (IJCs) in IDA / 70580 Prior Request for Bids orks SPD (1 e 0.00 2023-06-06 2023-06-11 2023-07-23 2023-08-22 2023-09-12 ice and Public Trust l nvelope w 3 Four Selected Locations of Si nvelope proc ngida, Simiyu, Geita and Pem ess) ba-Four Lots TZ-JUDICIARY TZ-364566-C Request for B W-RFB / Construction of Integ ids - Small W Component 3: Access to Just Open - Internationa Single Stage - One E Under Revie 2024-06-1 rated Justice Centers (IJCs) in IDA / 70580 Prior Request for Bids orks SPD (1 e 0.00 2023-06-06 2023-06-11 2023-07-23 2023-08-22 2023-09-12 ice and Public Trust l nvelope w 3 Five Selected Locations of Ka nvelope proc tavi, Songwe, Njombe, Mtwar ess) a and Songea-Five Lots TZ-JUDICIARY TZ-364568-C Request for B W-RFB / Construction of Integ ids - Small W Component 3: Access to Just Open - Internationa Single Stage - One E Under Revie 2024-06-1 rated Justice Centers (IJCs) in IDA / 70580 Prior Request for Bids orks SPD (1 e 0.00 2023-06-06 2023-06-11 2023-07-23 2023-08-22 2023-09-12 ice and Public Trust l nvelope w 3 Five Selected Locations of Pw nvelope proc ani, Tanga, Moshi, Manyara a ess) nd Lindi-Five Lots TZ-JUDICIARY TZ-9217-CW-D IR / Construction of ten (10) c Component 3: Access to Just 2017-11-1 ourthouses for subordinate c IDA / 57780 Prior Direct Selection Direct 0.00 Canceled 2017-04-10 2017-04-15 2017-05-20 ice and Public Trust 6 ourts Primary Court and Trai ning room at Kisutu RMs Cou rt. GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TZ-JUDICIARY TZ-4371-GO-R Component 1: Governance, Request for Quota Single Stage - One E FQ / Design, Editing and Print IDA / 57780 Organization and Systems D Post Limited 40,909.50 Completed 2016-12-18 2016-12-05 2017-02-12 2017-01-24 2017-08-11 2017-02-08 tions nvelope ing of Strategic plan, Brochur evelopment es TZ-JUDICIARY TZ-9220-GO-R Component 1: Governance, Single Stage - One E FB / Supply of IT Equipment f IDA / 57780 Organization and Systems D Prior Request for Bids Open - National 0.00 Canceled 2017-07-15 2017-07-20 2017-08-31 2017-09-30 2017-11-04 2018-05-03 nvelope or registries & DJSIE evelopment TZ-JUDICIARY TZ-30083-GO- Component 2: Skills Develop RFQ / Procurement of office f Request for Quota Single Stage - One E IDA / 57780 ment, Inspection and Perfor Post Limited 32,612.45 Completed 2017-09-30 2017-10-04 2017-11-05 2017-11-25 2018-05-04 2018-01-23 acilities for training center at tions nvelope mance Management Kisutu Resident Magistrate C ourt-Dar es salaam TZ-JUDICIARY TZ-30400-GO- RFQ / Procurement of office v Component 2: Skills Develop Request for Quota Single Stage - One E ideo conference facilities for IDA / 57780 ment, Inspection and Perfor Post Limited 83,134.05 Completed 2017-10-03 2017-10-05 2017-11-28 2017-10-31 2018-05-27 2018-04-16 tions nvelope training center at Kisutu resi mance Management dent magistrate court-Dar es salaam. TZ-JUDICIARY TZ-30103-GO- Component 2: Skills Develop RFQ / Procurement of IT equi Request for Quota Single Stage - One E IDA / 57780 ment, Inspection and Perfor Post Limited 77,394.71 Completed 2017-10-04 2017-10-12 2017-11-09 2017-11-14 2018-05-08 2018-05-16 pment for training center at tions nvelope mance Management Kisutu Resident Magistrate C ourt- Dar es Salaam. TZ-JUDICIARY TZ-37777-GO- RFQ / Supply, Installation and Component 1: Governance, Commissioning of Furniture, Request for Quota Single Stage - One E IDA / 57780 Organization and Systems D Post Limited 91,246.04 Completed 2017-11-27 2017-11-28 2018-01-08 2018-01-19 2018-02-05 2018-04-06 LAN, CCTV camera and Bio-m tions nvelope evelopment etric Door Access System for Retooling of Judiciary Deliver y Unit Office. TZ-JUDICIARY TZ-40300-GO- RFB / Supply, Installation, Te Component 1: Governance, st and Commissioning of Vid Single Stage - One E IDA / 57780 Organization and Systems D Post Request for Bids Open - National 594,512.13 Completed 2017-12-21 2018-01-11 2017-12-26 2018-01-25 2018-02-09 2018-02-24 2018-03-21 2018-03-31 2018-05-15 2018-09-27 2019-06-18 eo Conferencing facilities, Au nvelope evelopment dio Visual and Recording equ ipment at four selected Court s TZ-JUDICIARY TZ-64942-GO- Component 1: Governance, Request for Quota Single Stage - One E RFQ / Procurement of ICT eq IDA / 57780 Organization and Systems D Post Limited 95,937.33 Completed 2018-06-16 2018-06-14 2018-08-11 2018-08-07 2019-02-07 2018-09-21 tions nvelope uipment for new directorates evelopment TZ-JUDICIARY TZ-64971-GO- Component 1: Governance, Request for Quota Single Stage - One E RFQ / Procurement of furnitur IDA / 57780 Organization and Systems D Post Limited 71,421.54 Completed 2018-06-16 2018-06-14 2018-08-11 2018-07-17 2019-02-07 2018-11-23 tions nvelope e for new directorates evelopment Page 1 TZ-JUDICIARY TZ-67572-GO- Component 3: Access to Just Single Stage - One E RFB / Procurement of furnitur IDA / 57780 Prior Request for Bids Open - National 1,785,846.11 Completed 2018-07-25 2019-01-09 2018-07-30 2019-01-29 2018-09-10 2019-02-28 2018-10-10 2019-05-15 2018-11-14 2019-07-02 2019-05-13 2023-02-18 ice and Public Trust nvelope e for eighteen (18) new court buildings. TZ-JUDICIARY TZ-87170-GO- Component 2: Skills Develop UN Agencies (Dire UN / Procurement of 57 moto IDA / 57780 ment, Inspection and Perfor Prior Direct 1,701,529.79 Completed 2018-11-30 2018-12-05 2019-01-16 2019-01-28 2019-07-15 2019-06-30 ct) r vehicles mance Management TZ-JUDICIARY TZ-62259-GO- Component 2: Skills Develop Open - Internationa Single Stage - One E RFB / Procurement of 57 mot IDA / 57780 ment, Inspection and Perfor Prior Request for Bids 0.00 Canceled 2018-06-01 2018-06-06 2018-07-18 2018-08-17 2018-09-21 2019-03-20 l nvelope or vehicles mance Management TZ-JUDICIARY TZ-91934-GO- RFB / Supply, Installation, Te sting and Commissioning of L Component 3: Access to Just Single Stage - One E ocal Area Network and other IDA / 57780 Post Request for Bids Open - National 592,972.08 Completed 2018-12-28 2019-04-25 2019-01-02 2019-01-30 2019-07-12 2019-03-01 2019-08-19 2019-04-05 2019-11-20 2019-10-02 2020-07-26 ice and Public Trust nvelope ICT equipment for Moderniza tion of ICT Infrastructure to T wenty Three (23) New Court s Buildings. TZ-JUDICIARY TZ-107689-GO -DIR / SUPPLY AND INSTALLA TION OF NETWORK/FIBER CO Component 1: Governance, NNECTIVITY AND PROVISION IDA / 57780 Organization and Systems D Prior Direct Selection Direct 1,814,257.31 Signed 2019-04-01 2019-04-24 2019-04-06 2019-05-22 2019-05-11 2019-07-29 2019-11-07 OF DATA AND INTERNET SER evelopment VICES TO HIGH COURTS, REG IONAL MAGISTRATES AND DI STRICT COURTS BUILDINGS C OUNTRYWIDE. TZ-JUDICIARY TZ-110239-GO Component 2: Skills Develop -RFQ / PROCUREMENT OF PR Request for Quota Single Stage - One E IDA / 57780 ment, Inspection and Perfor Post Limited 42,683.08 Completed 2019-04-20 2019-05-02 2019-06-15 2019-06-17 2019-12-12 2019-10-28 OTECTIVE ACCESSORIES FOR tions nvelope mance Management THE 57 PROCURED MOTOR V EHICLES. TZ-JUDICIARY TZ-113691-GO Component 1: Governance, -RFB / Procurement of Gadge Single Stage - One E IDA / 57780 Organization and Systems D Post Request for Bids Open - National 219,227.79 Completed 2019-05-10 2019-05-10 2019-05-15 2019-06-26 2019-06-14 2019-07-26 2019-07-23 2019-08-30 2019-08-02 2020-02-26 2020-01-30 ts (POS) for utilization of GeP nvelope evelopment G government system TZ-JUDICIARY TZ-118395-GO Component 1: Governance, -RFQ / Procurement of Stand Request for Quota Single Stage - One E IDA / 57780 Organization and Systems D Post Limited 26,526.32 Completed 2019-06-26 2019-06-20 2019-08-21 2019-09-24 2020-02-17 2020-01-19 by Generator for High Court- tions nvelope evelopment Commercial Division TZ-JUDICIARY TZ-120930-GO Component 2: Skills Develop -RFQ / Procurement of ICT eq Request for Quota Single Stage - One E IDA / 57780 ment, Inspection and Perfor Post Limited 22,480.99 Completed 2019-07-06 2019-07-22 2019-08-31 2019-08-30 2020-02-27 2019-10-31 uipment and furniture for Co tions nvelope mance Management urt brokers and advocate sec tion TZ-JUDICIARY TZ-144324-GO Component 3: Access to Just Request for Quota Single Stage - One E -RFQ / PROCUREMENT OF ICT IDA / 57780 Post Limited 8,221.98 Completed 2019-11-19 2019-12-06 2020-01-14 2020-04-01 2020-07-12 2020-06-25 ice and Public Trust tions nvelope EQUIPMENT FOR LEGAL AID UNIT - MOCLA TZ-JUDICIARY TZ-159885-GO Component 1: Governance, -UN / Procurement of ICT equ UN Agencies (Dire IDA / 57780 Organization and Systems D Prior Direct 1,370,192.72 Completed 2020-02-25 2020-05-18 2020-03-01 2020-05-19 2020-04-19 2020-05-16 2020-10-16 2020-10-13 pment for registries, Court of ct) evelopment Appeal and centres. TZ-JUDICIARY TZ-168252-GO Component 1: Governance, -DIR / Supply of ICT equipme IDA / 57780 Organization and Systems D Post Direct Selection Direct 268,181.31 Completed 2020-04-15 2020-04-15 2020-04-17 2020-04-15 2020-04-20 2020-04-18 2020-04-25 2021-05-09 nt to facilitate e-court service evelopment s as a response measures ag ainst COVID-19 TZ-JUDICIARY TZ-178077-GO -RFB / Procurement of furnitu Component 3: Access to Just Single Stage - One E re for six Integrated Justice C IDA / 57780 Prior Request for Bids Open - National 3,069,984.39 Completed 2020-06-26 2020-06-29 2020-07-01 2020-06-30 2020-08-12 2020-07-28 2020-09-11 2020-08-20 2020-10-16 2020-10-28 2021-04-14 2021-12-18 ice and Public Trust nvelope enters located in Mwanza, Ar usha,Morogoro,Dodoma, Tem eke and Kinondoni. TZ-JUDICIARY TZ-180768-GO -RFB / SUPPLY, INSTALLATIO N AND CONFIGURATION OF Component 1: Governance, Single Stage - One E MICROSOFT OFFICE PROFESS IDA / 57780 Organization and Systems D Post Request for Bids Open - National 650,286.94 Completed 2020-06-26 2020-07-16 2020-07-01 2020-07-17 2020-07-22 2020-08-03 2020-07-29 2020-09-01 2020-08-10 2020-11-21 2020-09-07 2020-12-24 nvelope IONAL 2019 FOR 1388 LAPTO evelopment PS AND 14 DESKTOPS FOR M AGISTRATES AND COURT OF APPEAL REGISTRIES TZ-JUDICIARY TZ-180771-GO -RFQ / PROCUREMENT OF SC Component 3: Access to Just Request for Quota Single Stage - One E ANNERS FOR TWO INTERGRA IDA / 57780 Post Limited 27,451.65 Completed 2020-08-04 2020-06-25 2020-09-13 2020-12-05 2020-09-22 2021-05-20 ice and Public Trust tions nvelope TED JUSTICE CENTRES (IJCS) LOCATED IN MOROGORO AN D TEMEKE DAR ES SALAAM. TZ-JUDICIARY TZ-180773-GO -UN / PROCUREMENT OF ICT Component 3: Access to Just UN Agencies (Dire EQUIPMENT FOR TWO INTER IDA / 57780 Post Direct 27,451.65 Completed 2020-07-01 2020-07-21 2020-07-06 2020-07-22 2020-08-10 2020-12-05 2020-12-08 2021-09-15 ice and Public Trust ct) GRATED JUSTICE CENTRES (IJ CS) LOCATED IN MOROGORO AND TEMEKE DAR ES SALAA M. TZ-JUDICIARY TZ-182131-GO Component 1: Governance, -RFQ / Supply and Installation Request for Quota Single Stage - One E IDA / 57780 Organization and Systems D Post Limited 4,764.07 Completed 2020-07-03 2020-07-08 2020-07-10 2020-08-23 2021-01-06 2020-10-27 of plumbing materials and fit tions nvelope evelopment tings at new JDU Offices-Haki House TZ-JUDICIARY TZ-182133-GO Component 1: Governance, -RFQ / Supply and Installation Request for Quota Single Stage - One E IDA / 57780 Organization and Systems D Post Limited 7,534.44 Completed 2020-07-02 2020-07-08 2020-07-10 2020-08-29 2021-01-06 2020-09-01 of LAN,CCTV, security door s tions nvelope evelopment ystem and telephones at JDU offices-Haki House TZ-JUDICIARY TZ-182134-GO -RFQ / Supply and installation Component 1: Governance, of office partitioning material Request for Quota Single Stage - One E IDA / 57780 Organization and Systems D Post Limited 51,159.33 Completed 2020-07-02 2020-07-09 2020-07-10 2020-10-03 2021-01-06 2021-01-26 s and dismantal , packing an tions nvelope evelopment d re-instllation of Office facilit ies from Rita tower and PPF T ower to HAKI House. TZ-JUDICIARY TZ-182136-GO Component 1: Governance, Request for Quota Single Stage - One E -RFQ / Supply and Installation IDA / 57780 Organization and Systems D Post Limited 9,799.74 Completed 2020-07-02 2020-07-08 2020-07-10 2020-08-20 2021-01-06 2020-12-01 tions nvelope of Air Conditions at JDU Offic evelopment es -Haki House TZ-JUDICIARY TZ-188551-GO -RFQ / Supply, Installation, te Component 3: Access to Just Request for Quota Single Stage - One E sting and comissioning of LA IDA / 57780 Post Limited 23,461.52 Completed 2020-08-26 2020-08-23 2020-10-02 2020-11-17 2020-12-01 2021-04-15 ice and Public Trust tions nvelope N at Office of Attorney Gene ral in Dar es Salaam and Dod oma. Page 2 TZ-JUDICIARY TZ-211164-GO Component 1: Governance, Request for Quota Single Stage - One E -RFQ / Procurement of ICT Fa IDA / 57780 Organization and Systems D Post Limited 21,195.18 Completed 2021-01-02 2020-12-31 2021-02-03 2021-03-18 2021-04-04 2021-06-25 tions nvelope cilities for Kigamboni " Paper evelopment less Court" TZ-JUDICIARY TZ-221783-GO -RFB / Procurement of ICT eq Component 3: Access to Just Single Stage - One E uipment for Six Integrated Ju IDA / 57780 Post Request for Bids Open - National 560,528.31 Completed 2021-03-01 2021-08-04 2021-03-06 2021-08-04 2021-04-05 2021-08-27 2021-04-30 2020-08-30 2021-05-24 2021-09-22 2021-09-21 2021-12-08 ice and Public Trust nvelope stice Centers(IJCs) in Arusha, Mwanza, Dodoma, Morogoro, Kinondoni, and Temeke. TZ-JUDICIARY TZ-260890-GO -RFB / Procurement of furnitu re for eighteen(18) Subordin ate Courts located at Kaliua, Component 3: Access to Just Single Stage - One E IDA / 57780 Post Request for Bids Open - National 0.00 Canceled 2021-11-12 2021-11-29 2021-11-17 2021-11-29 2021-12-15 2021-12-20 2021-12-29 2021-12-27 2022-01-12 2022-05-12 Uvinza, Buhigwe, Kakonko, B ice and Public Trust nvelope utiama, Rorya, Itilima, Buseg a, Songwe, Tanganyika, Mbo gwe, Nyang’wale , Kyerwa, M isenyi, Gairo, Mvomero, Kilo mbero and Mkinga. TZ-JUDICIARY TZ-260892-GO -RFB / Supply, Installation, Te st and Commissioning of ICT equipment for eighteen(18) S Component 3: Access to Just Single Stage - One E ubordinate Courts located at IDA / 57780 Post Request for Bids Open - National 659,497.68 Completed 2021-11-12 2021-11-29 2021-11-17 2021-11-29 2021-12-15 2021-12-20 2021-12-29 2021-12-20 2022-01-12 2022-03-12 2022-05-12 2022-10-19 ice and Public Trust nvelope Kaliua, Uvinza, Buhigwe, Kak onko, Butiama, Rorya, Itilima , Busega, Songwe, Tanganyik a, Mbogwe, Nyang’wale , Kye rwa, Misenyi, Gairo, Mvomer o, Kilom TZ-JUDICIARY TZ-271298-GO -RFB / PROCUREMENT OF FU RNITURE FOR EIGHTEEN(18) SUBORDINATE COURTS LOCA TED AT KALIUA, UVINZA, BUH Component 3: Access to Just Single Stage - One E IDA / 57780 Post Request for Bids Open - National 1,257,889.98 Signed 2022-01-03 2022-01-05 2022-01-05 2022-01-05 2022-01-26 2022-01-26 2022-02-02 2022-02-07 2022-02-16 2022-05-07 2022-05-17 IGWE, KAKONKO, BUTIAMA, R ice and Public Trust nvelope ORYA, ITILIMA, BUSEGA, SON GWE, TANGANYIKA, MBOGW E, NYANG’WALE , KYERWA, M ISENYI, GAIRO, MVOMERO, KI LOMBERO AND MKINGA-(RE ADVERTISED) TZ-JUDICIARY TZ-293025-GO Component 3: Access to Just Single Stage - One E -RFB / Procurement of ICT eq IDA / 57780 Post Request for Bids Open - National 0.00 Canceled 2022-05-04 2022-05-09 2022-06-06 2022-06-16 2022-06-30 2022-08-29 ice and Public Trust nvelope uipment for Judiciary Media C enter TZ-JUDICIARY TZ-295320-GO Component 1: Governance, -DIR / Procurement of 18 Mot Under Imple IDA / 57780 Organization and Systems D Post Direct Selection Direct 0.00 2022-05-27 2022-08-03 2022-06-01 2022-08-03 2022-06-29 2022-12-01 or vehicles to support IJCs an mentation evelopment d project operations. TZ-JUDICIARY TZ-295322-GO Component 3: Access to Just Single Stage - One E -RFB / Procurement of ICT eq IDA / 57780 Post Request for Bids Limited 393,494.83 Completed 2022-05-16 2022-05-09 2022-05-17 2022-05-10 2022-05-31 2022-05-21 2022-06-02 2022-06-02 2022-06-11 2022-06-24 2022-06-25 2022-12-11 ice and Public Trust nvelope uipment for Judiciary Media C enter TZ-JUDICIARY TZ-320431-GO Component 1: Governance, -RFQ / Procurement of Archiv Request for Quota Single Stage - One E Under Imple IDA / 57780 Organization and Systems D Post Limited 0.00 2022-10-29 2022-12-29 2022-12-24 2023-06-22 e Boxes, File Cover and Stati tions nvelope mentation evelopment onery for Decongestion Exerc ise TZ-JUDICIARY TZ-320580-GO Component 1: Governance, -DIR / PROCUREMENT OF 83 Direct - Internation IDA / 57780 Organization and Systems D Prior Direct Selection 0.00 Signed 2022-11-30 2023-01-24 2022-12-05 2023-02-01 2023-01-09 2023-03-24 2023-07-08 MOTOR VEHICLES TO SUPPO al evelopment RT THE JUDICIAL REFORM AG ENDA TZ-JUDICIARY TZ-322583-GO -RFB / PROCUREMENT OF ICT Component 1: Governance, Single Stage - One E Under Imple EQUIPMENT FOR THE ATTOR IDA / 57780 Organization and Systems D Post Request for Bids Open - National 0.00 2022-11-11 2022-11-28 2022-11-16 2022-12-22 2022-12-19 2022-12-29 2023-01-23 2023-01-31 2023-05-31 nvelope mentation NEY GENERAL'S OFFICE & DI evelopment GITIZATION OF COURT RECO RDS. TZ-JUDICIARY TZ-320428-GO Component 3: Access to Just Single Stage - One E Under Imple -RFB / Procurement of Six Mo IDA / 57780 Prior Request for Bids Open - National 0.00 2022-11-11 2023-02-03 2022-11-16 2023-02-08 2022-12-22 2023-03-31 2022-12-27 2023-06-01 2023-01-15 2023-11-11 ice and Public Trust nvelope mentation bile Court Vehicles TZ-JUDICIARY TZ-330899-GO -RFB / Supply, installation, te Component 1: Governance, Single Stage - One E Under Imple st, configuration and Commis IDA / 70580 Organization and Systems D Post Request for Bids Open - National 0.00 2023-01-06 2023-01-30 2023-01-16 2023-01-31 2023-02-21 2023-03-10 2023-03-07 2023-03-25 2023-03-28 2023-07-26 nvelope mentation sioning of audio virtual recor evelopment ding equipment for eight IJCs and three high court centers. TZ-JUDICIARY TZ-338611-GO -RFB / Supply, installation , c Component 1: Governance, Single Stage - One E Under Imple onfiguration, testing and com IDA / 70580 Organization and Systems D Post Request for Bids Open - National 0.00 2023-02-10 2023-02-15 2023-02-15 2023-02-15 2023-03-23 2023-03-16 2023-04-22 2023-03-17 2023-05-27 2023-08-25 nvelope mentation missioning of ICT equipment evelopment for establishment of Judiciary Virtual Situation Room. TZ-JUDICIARY TZ-340099-GO -RFB / Procurement of heavy Component 1: Governance, Single Stage - One E Under Imple duty scanners and other ICT IDA / 70580 Organization and Systems D Post Request for Bids Open - National 0.00 2023-03-08 2023-02-08 2023-03-17 2023-02-08 2023-04-22 2023-03-02 2023-05-22 2023-03-06 2023-06-26 2023-09-24 nvelope mentation equipment for digitization of evelopment court records and supporting JDU's procurement functions. TZ-JUDICIARY TZ-347075-GO -RFB / Supply, Installation, te sting, and commissioning of Component 3: Access to Just Single Stage - One E Under Imple Video Conferencing facilities IDA / 70580 Post Request for Bids Open - National 0.00 2023-03-14 2023-04-14 2023-03-19 2023-04-14 2023-04-30 2023-05-15 2023-05-30 2023-05-24 2023-07-04 2023-10-02 ice and Public Trust nvelope mentation for Prisons and other ICT facil ities to capacitate the estate management unit of the Judi ciary of Tanzania. TZ-JUDICIARY TZ-359592-GO Component 1: Governance, Request for Quota Single Stage - One E Under Imple -RFQ / Supply of protective a IDA / 57780 Organization and Systems D Post Limited 0.00 2023-05-15 2023-05-09 2023-06-15 2023-07-15 tions nvelope mentation ccessories for 18 motor vehic evelopment les. TZ-JUDICIARY TZ-364570-GO Component 1: Governance, -RFQ / Procurement of ICT eq Request for Quota Single Stage - One E Under Imple IDA / 70580 Organization and Systems D Post Limited 0.00 2023-06-11 2023-08-06 2024-02-02 uipment to support the imple tions nvelope mentation evelopment mentation and oversight of t he project. TZ-JUDICIARY TZ-9233-GO-R Component 2: Skills Develop FQ / Procurement of Furnitur Request for Quota Single Stage - One E IDA / 57780 ment, Inspection and Perfor Post Limited 58,108.56 Completed 2017-07-03 2017-11-10 2017-08-28 2017-12-14 2018-02-24 2018-04-05 e for training rooms at High tions nvelope mance Management Court DSM & Kisutu RMs Cou rt Page 3 TZ-JUDICIARY TZ-9227-GO-R FB / Supply, installation and c Component 1: Governance, Single Stage - One E ommission of Video Conferen IDA / 57780 Organization and Systems D Prior Request for Bids Open - National 0.00 Canceled 2017-05-22 2017-09-11 2017-05-27 2017-07-08 2017-08-07 2017-09-11 2018-03-10 nvelope cing Equipment, audio visual evelopment and recording equipment for four selected courts. TZ-JUDICIARY TZ-9218-GO-R Component 3: Access to Just Single Stage - One E FB / Supply of Two (2) Mobile IDA / 57780 Prior Request for Bids Open - National 415,669.47 Completed 2017-04-13 2017-10-09 2017-04-18 2017-05-30 2017-11-15 2017-06-29 2017-12-22 2017-08-03 2018-01-19 2018-01-30 2019-02-01 ice and Public Trust nvelope Courts Van TZ-JUDICIARY TZ-9356-GO-R Component 1: Governance, FB / Procurement of IT hardw Single Stage - One E IDA / 57780 Organization and Systems D Post Request for Bids Open - National 235,523.50 Completed 2017-03-09 2017-01-26 2017-03-14 2017-04-25 2017-02-16 2017-05-25 2017-04-22 2017-06-29 2017-03-23 2017-12-26 2017-09-15 are and general software for nvelope evelopment Integrated Justice Centre at Mbeya. TZ-JUDICIARY TZ-585-GO-RF Component 1: Governance, Request for Quota Single Stage - One E Q / Supply of office consuma IDA / 57780 Organization and Systems D Post Limited 27,167.14 Completed 2016-08-17 2016-08-17 2016-10-12 2016-10-07 2017-04-10 2016-11-08 tions nvelope bles evelopment TZ-JUDICIARY TZ-9382-GO-R Component 3: Access to Just Request for Quota Single Stage - One E FQ / Supply of Documentary IDA / 57780 Post Limited 11,233.54 Completed 2017-03-21 2017-02-02 2017-05-16 2017-01-28 2017-11-12 2017-05-02 ice and Public Trust tions nvelope about information on Judiciar y constructions. TZ-JUDICIARY TZ-9361-GO-R FB / Procurement of furniture Component 3: Access to Just Single Stage - One E IDA / 57780 Post Request for Bids Open - National 0.00 Canceled 2017-06-13 2017-06-18 2017-07-30 2017-08-29 2017-10-03 2018-04-01 for registries & Mbeya Integr ice and Public Trust nvelope ated Justice Centre. TZ-JUDICIARY TZ-9237-GO-R Component 1: Governance, FB / Procurement of training I Single Stage - One E IDA / 57780 Organization and Systems D Post Request for Bids Open - National 0.00 Canceled 2017-03-28 2017-04-02 2017-05-14 2017-06-13 2017-07-18 2018-01-14 T facilities for High Court DS nvelope evelopment M & Kisutu RMs Court. TZ-JUDICIARY TZ-9364-GO-R Component 1: Governance, FQ / Procurement of IT hardw Request for Quota Single Stage - One E IDA / 57780 Organization and Systems D Post Limited 78,159.26 Completed 2017-03-20 2017-03-22 2017-05-15 2017-05-04 2017-11-11 2017-06-30 are and general software for tions nvelope evelopment a medium size Integrated Jus tice Centre at Kibaha TZ-JUDICIARY TZ-9239-GO-R FB / Procurement of standb Component 3: Access to Just Single Stage - One E IDA / 57780 Post Request for Bids Open - National 133,805.01 Completed 2017-04-28 2017-08-02 2017-05-03 2017-06-14 2017-09-19 2017-07-14 2017-10-03 2017-08-18 2017-11-23 2018-02-14 2018-06-19 y generators for High Court ice and Public Trust nvelope DSM, JDU & Kisutu RMs Court TZ-JUDICIARY TZ-9222-GO-R Component 1: Governance, Single Stage - One E FB / Installation and partition IDA / 57780 Organization and Systems D Prior Request for Bids Open - National 0.00 Canceled 2017-04-26 2017-05-01 2017-06-12 2017-07-12 2017-08-16 2018-02-12 nvelope of pre fabrication storage for evelopment selected courts. TZ-JUDICIARY TZ-9389-GO-R Component 1: Governance, FB / Supply of LAN materials, Single Stage - One E IDA / 57780 Organization and Systems D Prior Request for Bids Open - National 0.00 Canceled 2017-11-08 2017-11-13 2017-12-25 2018-01-24 2018-02-28 2018-08-27 installation and commission i nvelope evelopment n High courts, Resident and d istrict courts. NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TZ-JUDICIARY TZ-39836-NC- RFB / Provision of Service for Component 3: Access to Just Single Stage - One E Design, Editing and Printing IDA / 57780 Prior Request for Bids Open - National 0.00 Canceled 2017-12-15 2017-12-08 2017-12-20 2018-01-17 2018-01-15 2018-02-16 2018-03-05 2018-03-23 2018-09-19 ice and Public Trust nvelope of Various Legal Documents under Framework Contract. TZ-JUDICIARY TZ-52317-NC- RFQ / Provision of event man Component 3: Access to Just Request for Quota Single Stage - One E IDA / 57780 Post Limited 93,400.36 Completed 2018-03-13 2018-03-23 2018-05-08 2018-05-02 2018-11-04 2018-06-11 agement, documentary and li ice and Public Trust tions nvelope ve coverage services for law week. TZ-JUDICIARY TZ-55449-NC- RFQ / Production of awarenes Component 3: Access to Just Request for Quota Single Stage - One E IDA / 57780 Post Limited 53,002.21 Completed 2018-04-01 2018-03-19 2018-05-27 2018-05-03 2018-11-23 2018-05-18 s program of ongoing judiciar ice and Public Trust tions nvelope y reforms to the public. TZ-JUDICIARY TZ-67402-NC- RFQ / Provision of event man Component 3: Access to Just Request for Quota Single Stage - One E agement service and printing IDA / 57780 Post Limited 19,723.02 Completed 2018-06-25 2018-06-22 2018-07-07 2018-07-13 2019-01-03 2018-07-23 ice and Public Trust tions nvelope of various exhibition material s for sabasaba 2018. TZ-JUDICIARY TZ-91933-NC- RFQ / Provision of Event Man Component 3: Access to Just Request for Quota Single Stage - One E IDA / 57780 Post Limited 97,646.03 Completed 2018-12-22 2019-01-03 2019-01-27 2019-01-29 2019-07-26 2019-03-28 agement and Printing Service ice and Public Trust tions nvelope s for Law Week 2019. TZ-JUDICIARY TZ-122947-NC -RFQ / Provision of event ma Component 3: Access to Just Request for Quota Single Stage - One E IDA / 57780 Post Limited 23,220.09 Completed 2019-07-21 2019-06-03 2019-08-10 2019-06-25 2019-08-24 2019-12-03 nagement service and printin ice and Public Trust tions nvelope g of various exhibition materi als TZ-JUDICIARY TZ-146943-NC -RFQ / Provision of printing s Component 2: Skills Develop Request for Quota Single Stage - One E ervice for guideline manuals IDA / 57780 ment, Inspection and Perfor Post Limited 12,051.60 Completed 2019-12-13 2019-12-02 2020-02-07 2020-01-28 2020-08-05 2020-03-14 tions nvelope for Judicial Ethics Committee, mance Management Judiciary training policy and t raining programs. TZ-JUDICIARY TZ-151993-NC -RFQ / Provision of Event Man Component 3: Access to Just Request for Quota Single Stage - One E agement: Hiring of Tents, Ch IDA / 57780 Post Limited 82,237.59 Completed 2020-01-15 2019-12-06 2020-03-11 2020-01-28 2020-09-07 2020-03-18 ice and Public Trust tions nvelope airs, Tables, Mobile Toilet an d Printing Services for Law W eek 2020 TZ-JUDICIARY TZ-159179-NC -RFB / ONLINE PUBLICATION OF COURT DECISIONS (REPO Component 1: Governance, Single Stage - One E RTED AND UNREPORTED LA IDA / 57780 Organization and Systems D Post Request for Bids Open - National 335,025.26 Completed 2020-02-23 2020-02-18 2020-02-28 2020-03-16 2020-04-10 2020-04-16 2020-05-10 2020-04-26 2020-06-14 2020-06-07 2020-12-11 2022-04-30 nvelope W REPORTS), PRINTING OF L evelopment AW REPORTS AND INDEX OF LEGISLATION AND SUB LEGIS LATION FROM THE YEAR 196 1-2020 Page 4 TZ-JUDICIARY TZ-180775-NC Component 1: Governance, -RFQ / PROCUREMENT OF SE Request for Quota Single Stage - One E IDA / 57780 Organization and Systems D Post Limited 98,517.15 Completed 2020-07-08 2020-07-08 2020-08-10 2020-09-23 2020-11-08 2021-03-20 RVICE FOR EDITING, DESIGN tions nvelope evelopment AND PRINTING OF VARIOUS J UDICIARY DOCUMENTS. TZ-JUDICIARY TZ-298032-NC -RFQ / Provision of Non-Cons Component 3: Access to Just Request for Quota Single Stage - One E IDA / 57780 Post Limited 16,353.54 Signed 2022-06-10 2022-06-05 2022-07-08 2022-07-15 2022-07-22 ultancy service-Filming and d ice and Public Trust tions nvelope eveloping documentaries abo ut project activities TZ-JUDICIARY TZ-325875-NC -RFQ / PROVISION OF EVENT S MANAGEMENT SERVICES (H IRING TENTS, TABLE, CHAIRS , GENERATORS, PA SYSTEM, Component 3: Access to Just Request for Quota Single Stage - One E Under Imple IDA / 70580 Post Limited 0.00 2022-11-23 2022-11-28 2022-12-21 2023-02-19 CARPET,MOBILE TOILET, DEC ice and Public Trust tions nvelope mentation ORATION, EXHIBITION BOOT H, MARQUEE, AND SUPPLY O F PROMOTIONAL MATERIALS) FOR OPENING CEREMONY AN D 6 DAYS LAW WEEK 2023 TZ-JUDICIARY TZ-9393-NC-R Component 3: Access to Just Request for Quota Single Stage - One E FQ / Printing and supply of m IDA / 57780 Post Limited 80,911.34 Completed 2017-03-14 2017-01-02 2017-05-09 2017-01-28 2017-11-05 2017-03-28 ice and Public Trust tions nvelope aterials for Law week. TZ-JUDICIARY TZ-9397-NC-R FQ / Draw printing and fixing Component 3: Access to Just Request for Quota Single Stage - One E IDA / 57780 Post Limited 0.00 Canceled 2017-03-28 2017-05-23 2017-11-19 of Signs / display boards for s ice and Public Trust tions nvelope elected court buildings. TZ-JUDICIARY TZ-9395-NC-R Component 3: Access to Just Request for Quota Single Stage - One E FQ / Design and printing of Ju IDA / 57780 Post Limited 63,673.97 Completed 2017-03-14 2016-12-28 2017-05-09 2017-01-24 2017-11-05 2017-03-23 ice and Public Trust tions nvelope diciary Calendar and diaries TZ-JUDICIARY TZ-9392-NC-R Component 3: Access to Just Single Stage - One E FB / Printing of different mat IDA / 57780 Prior Request for Bids Open - National 0.00 Canceled 2017-04-28 2017-12-08 2017-05-03 2017-06-14 2017-07-14 2017-08-18 2018-02-14 ice and Public Trust nvelope erials( Framework Contract) CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TZ-JUDICIARY TZ-9448-CS-Q CBS / Consultancy for design Component 1: Governance, Quality And Cost- and supervision of LAN instal IDA / 57780 Organization and Systems D Prior Open - National 0.00 Canceled 2017-04-25 2017-10-09 2017-05-16 2017-12-08 2017-06-29 2018-02-26 2017-07-27 2018-03-30 2017-08-26 2018-05-21 2017-09-30 2017-11-04 2018-11-04 Based Selection lation in Selected High Court, evelopment Resident and District Courts TZ-JUDICIARY TZ-44715-CS- QCBS / CONSULTANCY SERVI CES FOR FEASIBILITY STUDY/I Component 1: Governance, Quality And Cost- Open - Internationa MPLEMENTATION PLAN/PROC IDA / 57780 Organization and Systems D Prior 513,542.79 Completed 2018-01-26 2018-02-16 2018-01-22 2018-04-01 2018-03-29 2018-04-29 2018-04-30 2018-05-29 2018-07-06 2018-07-03 2018-10-03 2018-08-07 2018-11-29 2019-08-07 2021-03-05 Based Selection l UREMENT, DEVELOPMENT AN evelopment D IMPLEMENTATION SUPPOR T FOR E-JUDICIARY SERVICES FOR THE JUDICIARY OF TANZ ANIA TZ-JUDICIARY TZ-50144-CS- QCBS / Consultancy Services to (I) Update Design (Redesig n) of Existing Drawings (Phas Component 3: Access to Just Quality And Cost- Open - Internationa e 1) and (Ii) Supervise the Co IDA / 57780 Prior 452,799.20 Signed 2018-02-26 2018-03-18 2018-03-19 2018-03-27 2018-05-02 2018-06-18 2018-05-30 2018-07-27 2018-06-29 2018-10-03 2018-08-03 2018-11-27 2018-09-07 2018-12-16 2019-09-07 ice and Public Trust Based Selection l nstruction Work for the Propo sed Integrated Justice Centre (IJC) Court Buildings which wi ll be Built in Six Selected Loc ations of Mwanza, Morogoro TZ-JUDICIARY TZ-50194-CS- QCBS / Consultancy Services to (I) Update Design (Redesig n) of Existing Drawings (Phas Component 3: Access to Just Quality And Cost- Open - Internationa IDA / 57780 Prior 0.00 Canceled 2018-02-26 2018-03-18 2018-03-19 2018-04-12 2018-05-02 2018-06-18 2018-05-30 2018-06-29 2018-08-03 2018-09-07 2019-09-07 e 1) and (Ii) Supervise the Co ice and Public Trust Based Selection l nstruction Work for Small Co urthouses which will be Built in at least 10 Selected Locati ons in Tanzania (Phase 2) TZ-JUDICIARY TZ-113326-CS -QCBS / Consultancy Services to (I) Update Design (Redesig n) of Existing Drawings (Phas Component 3: Access to Just Quality And Cost- Open - Internationa IDA / 57780 Prior 310,611.59 Signed 2019-05-08 2019-07-27 2019-05-22 2019-07-31 2019-07-05 2019-12-28 2019-08-02 2020-01-10 2019-08-16 2020-02-18 2019-09-06 2020-03-13 2019-09-23 2020-04-01 2020-09-22 e 1) and (II) Supervise the Co ice and Public Trust Based Selection l nstruction Work for Small Co urthouses which will be Buil t in at Least 27 Selected Loca tions in Tanzania (Phase 2). TZ-JUDICIARY TZ-291807-CS -CQS / CONSULTANCY SERVI CES FOR PREPARATION OF A N ENVIRONMENTAL AND SOC IAL IMPACT ASSESSMENT FO Component 3: Access to Just Consultant Qualifi IDA / 57780 Post Open - National 295,190.27 Signed 2022-04-26 2022-04-24 2022-05-10 2022-05-19 2022-05-25 2022-07-01 2022-06-24 2022-07-25 2022-07-15 2022-08-06 2022-10-13 R THE PROPOSED CONSTRUC ice and Public Trust cation Selection TION PROJECTS IN TANZANIA MAINLAND UNDER THE CITIZ EN-CENTRIC JUDICIAL MODER NIZATION AND JUSTICE SERVI CE DELIVERY PROJECT.(AF) TZ-JUDICIARY TZ-320375-CS -QCBS / Consultancy Services to (I) Update the Design (Red esign) of Existing Drawings, Component 3: Access to Just Quality And Cost- Open - Internationa Under Implement and; (II) Supervise the Constr IDA / 57780 Post 0.00 2022-10-21 2022-10-20 2022-11-04 2022-11-30 2022-11-14 2023-02-09 2022-12-20 2023-03-24 2022-12-25 2023-03-31 2023-01-04 2023-06-26 2023-01-23 2025-03-13 ice and Public Trust Based Selection l ation uction Work for the Proposed Small Courthouses which will be Built in at Least Eleven (1 1) Selected Locations in Tanz ania. 1st Package TZ-JUDICIARY TZ-320379-CS -QCBS / Consultancy Services to (I) Update the Design (Red esign) of Existing Drawings, Component 3: Access to Just Quality And Cost- Open - Internationa Under Implement and; (II) Supervise the Constr IDA / 57780 Post 0.00 2022-10-21 2022-10-20 2022-11-04 2022-11-30 2022-11-14 2023-01-18 2022-12-20 2023-03-24 2022-12-25 2023-03-31 2023-01-04 2023-06-26 2023-01-23 2025-03-13 ice and Public Trust Based Selection l ation uction Work for the Proposed Small Courthouses which will be Built in at least nine (09) Selected Locations in Tanzani a. 2nd Package Page 5 TZ-JUDICIARY TZ-320381-CS -QCBS / Consultancy Services to (I) Update the Design (Red esign) of Existing Drawings, Component 3: Access to Just Quality And Cost- Open - Internationa Under Implement and; (II) Supervise the Constr IDA / 57780 Post 0.00 2022-10-21 2022-10-20 2022-11-04 2022-11-29 2022-11-14 2023-02-09 2022-12-20 2023-03-24 2022-12-25 2023-03-31 2023-01-04 2023-06-21 2023-01-23 2025-03-13 ice and Public Trust Based Selection l ation uction Work for the Proposed Small Courthouses which will be Built in at least nine (09) Selected Locations in Tanzani a. 3rd Package TZ-JUDICIARY TZ-320383-CS -QCBS / Consultancy Services to (I) Update the Design (Red esign) of Existing Drawings, Component 3: Access to Just Quality And Cost- Open - Internationa Under Implement and; (II) Supervise the Constr IDA / 57780 Post 0.00 2022-10-21 2022-10-20 2022-11-04 2022-11-29 2022-11-14 2023-02-09 2022-12-20 2023-03-24 2022-12-25 2023-03-31 2023-01-04 2023-06-19 2023-01-23 2025-03-13 ice and Public Trust Based Selection l ation uction Work for the Proposed Small Courthouses which will be Built in at Least eleven (1 1) Selected Locations in Tanz ania. 4th Package TZ-JUDICIARY TZ-320388-CS -QCBS / Consultancy Services to (I) Update the Design (Red esign) of Existing Drawings, Component 3: Access to Just Quality And Cost- Under Implement IDA / 57780 Post Open - National 0.00 2022-10-21 2022-10-20 2022-11-04 2022-11-29 2022-11-14 2023-02-09 2022-12-20 2023-03-24 2022-12-25 2023-03-31 2023-01-04 2023-06-19 2023-01-23 2025-03-13 and; (II) Supervise the Constr ice and Public Trust Based Selection ation uction Work for the Proposed Small Courthouses which will be Built in at least four (4) Se lected Locations in Tanzania. 5th Package TZ-JUDICIARY TZ-320391-CS -QCBS / Consultancy Services to (I) Update the Design (Red esign) of Existing Drawings, Component 3: Access to Just Quality And Cost- Open - Internationa Under Implement IDA / 57780 Post 0.00 2022-10-21 2022-10-20 2022-11-04 2022-11-30 2022-11-14 2023-02-09 2022-12-20 2023-03-24 2022-12-25 2023-03-31 2023-01-04 2023-06-19 2023-01-23 2025-03-13 and; (II) Supervise the Constr ice and Public Trust Based Selection l ation uction Work for the Proposed Small Courthouses which will be Built in at least six (6) Sel ected Locations in Tanzania. 6th Package TZ-JUDICIARY TZ-320393-CS -QCBS / Consultancy Services to (I) Update the Design (Red esign) of Existing Drawings, Component 3: Access to Just Quality And Cost- Open - Internationa Under Implement IDA / 57780 Post 0.00 2022-10-21 2022-10-20 2022-11-04 2022-11-29 2022-11-14 2023-02-09 2022-12-20 2023-03-24 2022-12-25 2023-03-31 2023-01-04 2023-01-23 2025-03-13 and; (II) Supervise the Constr ice and Public Trust Based Selection l ation uction Work for the Proposed Small Courthouses which will be Built in at Least ten (10) S elected Locations in Tanzania . 7th Package TZ-JUDICIARY TZ-320396-CS -QCBS / Consultancy Service for Supervision of Constructi on Work for the Proposed Int Component 3: Access to Just Quality And Cost- Open - Internationa Under Implement IDA / 57780 Post 0.00 2022-10-21 2022-10-20 2022-11-04 2022-11-29 2022-11-14 2023-02-08 2022-12-20 2023-03-24 2022-12-25 2023-03-31 2023-01-04 2023-01-23 2025-05-12 egrated Justice Centre (IJC) C ice and Public Trust Based Selection l ation ourt Buildings which will be b uilt in four (4) Selected regio ns of Singida, Geita, Simiyu a nd Manyara. 1st Package. TZ-JUDICIARY TZ-320398-CS -QCBS / Consultancy Service for Supervision of Constructi on Work for the Proposed Int Component 3: Access to Just Quality And Cost- Open - Internationa Under Implement IDA / 57780 Post 0.00 2022-10-21 2022-10-20 2022-11-04 2022-11-29 2022-11-14 2023-02-09 2022-12-20 2023-03-24 2022-12-25 2023-03-31 2023-01-04 2023-01-23 2025-05-12 egrated Justice Centre (IJC) C ice and Public Trust Based Selection l ation ourt Buildings which will be b uilt in three (3) Selected regi ons of Katavi, Songwe, and N jombe. 3rd Package. TZ-JUDICIARY TZ-320400-CS -QCBS / Consultancy Service for Supervision of Constructi Component 3: Access to Just Quality And Cost- Open - Internationa Under Implement on Work for the Proposed Int IDA / 57780 Post 0.00 2022-10-21 2022-10-20 2022-11-04 2022-11-29 2022-11-14 2023-02-09 2022-12-20 2023-03-24 2022-12-25 2023-03-31 2023-01-04 2023-01-23 2025-05-12 ice and Public Trust Based Selection l ation egrated Justice Centre (IJC) C ourt Buildings which will be b uilt in Two (2) Selected regio ns of Lindi and Pwani. 2nd Pa ckage TZ-JUDICIARY TZ-365265-CS -QCBS / Consultancy services Component 1: Governance, Quality And Cost- for conducting impact assess IDA / 70580 Organization and Systems D Post Open - National 0.00 Under Review 2023-06-23 2023-07-14 2023-07-28 2023-09-02 2023-09-09 2023-09-30 2023-10-21 2024-02-18 Based Selection ments on simplified laws and evelopment rules of procedure. TZ-JUDICIARY TZ-9183-CS-C QS / Consultancy service to c onduct environmental and so Component 3: Access to Just Consultant Qualifi IDA / 57780 Post Open - National 110,103.09 Completed 2017-03-08 2016-09-06 2017-03-29 2017-05-12 2016-10-25 2017-06-11 2017-02-09 2017-07-16 2017-03-10 2018-01-12 2018-04-27 cial impact assessments for t ice and Public Trust cation Selection he Citizen-Centric Judicial Mo dernization and Justice Servic e Delivery Project. TZ-JUDICIARY TZ-9399-CS-C Component 2: Skills Develop QS / Consultancy service to D Consultant Qualifi IDA / 57780 ment, Inspection and Perfor Post Open - National 0.00 Canceled 2017-07-17 2017-08-07 2017-09-20 2017-10-20 2017-11-24 2018-05-23 evelop continuous training pr cation Selection mance Management ogram and facilitate legal trai ning TZ-JUDICIARY TZ-9438-CS-Q Component 1: Governance, CBS / Consultancy Services t Quality And Cost- IDA / 57780 Organization and Systems D Prior Open - National 0.00 Canceled 2017-05-10 2017-05-31 2017-07-14 2017-08-11 2017-09-10 2017-10-15 2017-11-19 2018-11-19 o design and introduce E-jud Based Selection evelopment gment, e-payment & E- notifi cation TZ-JUDICIARY TZ-9420-CS-Q Component 1: Governance, Quality And Cost- CBS / Consultancy service to IDA / 57780 Organization and Systems D Post Open - National 100,710.87 Completed 2017-04-19 2016-03-30 2017-05-10 2017-06-23 2016-12-23 2017-07-21 2017-01-30 2017-08-20 2017-03-30 2017-09-24 2017-05-04 2017-10-29 2017-06-08 2018-10-29 2019-01-31 Based Selection undertake Court mapping co evelopment untry wide INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Actual Amount Invitation to Identifie Draft Negotiated Cont Component Review Type Method Contract Type Process Status Teams of Reference Signed Contract Contract Completion Description o. h (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TZ-JUDICIARY TZ-25713-CS-I Component 1: Governance, Individual Consult NDV / Procurement Specialist IDA / 57780 Organization and Systems D Post Limited 179,040.00 Completed 2017-08-28 2017-08-28 2017-09-02 2017-08-31 2017-09-23 2017-09-06 2017-10-28 2017-09-26 2018-04-26 2020-05-20 ant Selection to support Project team evelopment TZ-JUDICIARY TZ-42554-CS-I NDV / Provision of consultanc Component 3: Access to Just Individual Consult IDA / 57780 Post Limited 67,200.00 Completed 2018-01-15 2017-11-21 2018-01-20 2018-01-23 2018-02-10 2018-02-12 2018-03-17 2018-03-29 2018-09-13 2019-03-28 y for Information and Commu ice and Public Trust ant Selection nication services Page 6 TZ-JUDICIARY TZ-42596-CS-I Component 1: Governance, NDV / Consultancy services f Individual Consult IDA / 57780 Organization and Systems D Post Limited 68,100.00 Completed 2018-01-18 2017-11-21 2018-01-23 2018-01-18 2018-02-13 2018-02-12 2018-03-20 2018-05-07 2018-09-16 2019-06-26 or preparation of Human Res ant Selection evelopment ource planning guideline for J udiciary of Tanzania. TZ-JUDICIARY TZ-42602-CS-I NDV / Provision of consultanc y services for development o Component 3: Access to Just Individual Consult IDA / 57780 Post Limited 31,581.00 Terminated 2018-01-15 2017-12-30 2018-01-20 2018-01-21 2018-02-10 2018-02-15 2018-03-17 2018-05-07 2018-09-13 f database systems for judge ice and Public Trust ant Selection ment, Advocates and Court B rokers and database for proje ct M & E tools based on BRN. TZ-JUDICIARY TZ-9406-CS-C DS / Consultancy service for supervision of the constructio Component 3: Access to Just IDA / 57780 Prior Direct Selection Direct 0.00 Canceled 2017-04-02 2017-04-12 2017-06-16 2017-12-13 n of ten (10) courthouses for ice and Public Trust subordinate court Primary Co urt and training room at Kisu tu RMs Court. TZ-JUDICIARY TZ-54811-CS-I Component 1: Governance, NDV / Individual Consultancy Individual Consult IDA / 57780 Organization and Systems D Post Limited 22,980.00 Completed 2018-03-26 2018-03-26 2018-03-31 2018-07-02 2018-04-21 2018-08-21 2018-05-26 2018-11-07 2018-11-22 2019-10-04 service for establishment an ant Selection evelopment d development of a compute rized e-Library system TZ-JUDICIARY TZ-138788-CS -INDV / CLERK OF WORKS (Co Ws) FOR SUPERVISION OF CO Component 3: Access to Just Individual Consult IDA / 57780 Post Open 66,998.08 Completed 2019-10-21 2019-10-22 2019-11-16 2020-01-17 2019-11-23 2020-01-17 2019-12-21 2020-01-25 2020-06-18 2022-03-01 NSTRUCTION OF INTEGRATE ice and Public Trust ant Selection D JUSTICE CENTRE (IJC) IN M WANZA, Plot 768 Block. A at North Buswelu. TZ-JUDICIARY TZ-140323-CS -INDV / CLERK OF WORKS (Co Ws) FOR SUPERVISION OF CO Component 3: Access to Just Individual Consult IDA / 57780 Post Open 31,688.28 Completed 2019-10-21 2019-10-22 2019-11-16 2020-01-17 2019-11-23 2020-01-17 2020-01-04 2020-01-25 2020-07-02 2021-02-15 NSTRUCTION OF INTEGRATE ice and Public Trust ant Selection D JUSTICE CENTRE (IJC) IN M OROGORO,, Plot 430 Block. G at Kihonda. TZ-JUDICIARY TZ-140325-CS -INDV / CLERK OF WORKS (Co Ws) FOR SUPERVISION OF CO Component 3: Access to Just Individual Consult IDA / 57780 Post Open 47,647.74 Completed 2019-10-21 2019-10-22 2019-11-16 2020-01-17 2019-11-23 2020-01-17 2019-12-07 2020-01-25 2020-06-04 2021-09-01 NSTRUCTION OF INTEGRATE ice and Public Trust ant Selection D JUSTICE CENTRE (IJC) IN AR USHA, Plot No 123. Block I Sit uated at Corridor I in Arusha City. TZ-JUDICIARY TZ-140327-CS -INDV / CLERK OF WORKS (Co Ws) FOR SUPERVISION OF CO Component 3: Access to Just Individual Consult IDA / 57780 Post Open 46,979.73 Completed 2019-10-21 2019-10-22 2019-11-16 2020-01-17 2019-11-23 2020-01-17 2019-12-21 2020-01-25 2020-06-18 2021-09-01 NSTRUCTION OF INTEGRATE ice and Public Trust ant Selection D JUSTICE CENTRE (IJC) IN D ODOMA, Plot No. 4 Block C at NCC Link. TZ-JUDICIARY TZ-140332-CS -INDV / CLERK OF WORKS (Co Ws) FOR SUPERVISION OF CO Component 3: Access to Just Individual Consult IDA / 57780 Post Open 53,505.92 Completed 2019-10-21 2019-10-22 2019-11-16 2020-01-17 2019-11-23 2020-02-06 2019-12-07 2020-01-25 2020-06-04 2021-07-31 NSTRUCTION OF INTEGRATE ice and Public Trust ant Selection D JUSTICE CENTRE (IJC) in DA R ES SALAAM, Plot No. 38 Blo ck No. 20 at Kinondoni Munic ipal. TZ-JUDICIARY TZ-140334-CS -INDV / CLERK OF WORKS (Co Ws) FOR SUPERVISION OF CO Component 3: Access to Just Individual Consult IDA / 57780 Post Open 48,306.60 Signed 2019-10-21 2019-10-22 2019-11-16 2020-01-17 2019-11-23 2020-01-17 2019-12-07 2020-01-25 2020-06-04 NSTRUCTION OF INTEGRATE ice and Public Trust ant Selection D JUSTICE CENTRE (IJC) IN DA R ES SALAAM, Plot No 2025 B lock D at Temeke. TZ-JUDICIARY TZ-152928-CS -INDV / INDIVIDUAL EXPERT T Component 1: Governance, O CONDUCT AN ECONOMIC A Individual Consult IDA / 57780 Organization and Systems D Post Limited 8,182.54 Completed 2020-01-24 2020-02-11 2020-01-29 2020-02-12 2020-02-19 2020-02-14 2020-03-25 2020-03-04 2020-09-21 2021-01-01 NALYSIS OF CITIZEN-CENTRIC ant Selection evelopment JUDICIAL MODERNIZATION A ND JUSTICE SERVICE DELIVE RY PROJECT TZ-JUDICIARY TZ-291818-CS Component 1: Governance, -INDV / Procurement and Con Individual Consult IDA / 57780 Organization and Systems D Prior Open 67,925.09 Signed 2022-04-26 2022-05-06 2022-05-22 2022-07-09 2022-05-27 2022-08-26 2022-06-13 2022-09-02 2023-06-08 tract Management Expert to ant Selection evelopment support the project team. TZ-JUDICIARY TZ-294037-CS -INDV / INDIVIDUAL CONSULT Component 1: Governance, ANT (CIVIL ENGINEER) FOR T Individual Consult IDA / 57780 Organization and Systems D Post Limited 30,875.04 Signed 2022-05-13 2022-05-15 2022-05-18 2022-06-27 2022-06-08 2022-08-24 2022-06-29 2022-09-05 2023-06-29 HE CITIZEN-CENTRIC JUDICIA ant Selection evelopment L MODERNIZATION AND JUST ICE SERVICE DELIVERY PROJE CT. TZ-JUDICIARY TZ-295323-CS -CDS / CONSULTANCY SERVI CE TO UPDATE THE DESIGN ( Component 3: Access to Just Under Implement IDA / 57780 Post Direct Selection Direct 0.00 2022-05-20 2022-05-30 2022-06-08 2022-08-25 2022-06-22 2022-08-23 REDESIGN) OF EXISTING DRA ice and Public Trust ation WINGS FOR THE PROPOSED 12 INTEGRATED JUSTICE CEN TRE (IJCs). TZ-JUDICIARY TZ-306644-CS -CDS / Consultancy service t Component 3: Access to Just Under Implement IDA / 57780 Post Direct Selection Direct - National 0.00 2022-07-31 2022-08-01 2022-08-19 2022-08-17 2022-08-31 2023-02-27 o conduct court users’ satisfa ice and Public Trust ation ction survey 2022 TZ-JUDICIARY TZ-364600-CS -INDV / Individual Consultant- Component 3: Access to Just Individual Consult Pending Impleme Clerk of Works (CoWs) for su IDA / 70580 Post Open - National 0.00 2023-06-11 2023-07-30 2023-08-20 2023-09-10 2024-09-09 ice and Public Trust ant Selection ntation pervision of construction of I ntegrated Justice Centre (IJC) in Songea. TZ-JUDICIARY TZ-364607-CS -INDV / Individual Consultant- Component 3: Access to Just Individual Consult Pending Impleme Clerk of Works (CoWs) for su IDA / 70580 Post Open - National 0.00 2023-06-11 2023-07-30 2023-08-20 2023-09-10 2024-09-09 ice and Public Trust ant Selection ntation pervision of construction of I ntegrated Justice Centre (IJC) in Lindi. TZ-JUDICIARY TZ-364593-CS -INDV / Individual Consultant- Component 3: Access to Just Individual Consult Pending Impleme Clerk of Works (CoWs) for su IDA / 70580 Post Open - National 0.00 2023-06-11 2023-07-30 2023-08-20 2023-09-10 2024-09-09 ice and Public Trust ant Selection ntation pervision of construction of i ntegrated justice centre (IJC) in Njombe. Page 7 TZ-JUDICIARY TZ-364576-CS -INDV / Individual Consultant- Component 3: Access to Just Individual Consult Pending Impleme Clerk of Works (CoWs) for su IDA / 70580 Post Open - National 0.00 2023-06-11 2023-07-30 2023-08-20 2023-09-10 2024-09-09 ice and Public Trust ant Selection ntation pervision of construction of i ntegrated justice centre (IJC) in Simiyu TZ-JUDICIARY TZ-364587-CS -INDV / Individual Consultant- Component 3: Access to Just Individual Consult Pending Impleme Clerk of Works (CoWs) for su IDA / 70580 Post Open - National 0.00 2023-06-11 2023-07-30 2023-08-20 2023-09-10 2024-09-09 ice and Public Trust ant Selection ntation pervision of construction of I ntegrated Justice Centre (IJC) in Katavi TZ-JUDICIARY TZ-364590-CS -INDV / Individual Consultant- Component 3: Access to Just Individual Consult Pending Impleme Clerk of Works (CoWs) for su IDA / 70580 Post Open - National 0.00 2023-06-11 2023-07-30 2023-08-20 2023-09-10 2024-09-09 ice and Public Trust ant Selection ntation pervision of construction of t he Integrated Justice Centre ( IJC) in Songwe TZ-JUDICIARY TZ-364605-CS -INDV / Individual Consultant- Component 3: Access to Just Individual Consult Pending Impleme Clerk of Works (CoWs) for su IDA / 70580 Post Open - National 0.00 2023-06-11 2023-07-30 2023-08-20 2023-09-10 2024-09-09 ice and Public Trust ant Selection ntation pervision of construction of t he Integrated Justice Centre ( IJC) in Moshi. TZ-JUDICIARY TZ-364583-CS -INDV / Individual Consultant- Component 3: Access to Just Individual Consult Pending Impleme Clerk of Works (CoWs) for su IDA / 70580 Post Open - National 0.00 2023-06-11 2023-07-30 2023-08-20 2023-09-10 2024-09-09 ice and Public Trust ant Selection ntation pervision of construction of i ntegrated justice centre (IJC) in Pemba. TZ-JUDICIARY TZ-364597-CS -INDV / Individual Consultant- Component 3: Access to Just Individual Consult Pending Impleme Clerk of Works (CoWs) for su IDA / 70580 Post Open - National 0.00 2023-06-11 2023-07-30 2023-08-20 2023-09-10 2024-09-09 ice and Public Trust ant Selection ntation pervision of construction of I ntegrated Justice Centre (IJC) in Mtwara TZ-JUDICIARY TZ-364602-CS -INDV / Individual Consultant- Component 3: Access to Just Individual Consult Pending Impleme Clerk of Works (CoWs) for su IDA / 70580 Post Open - National 0.00 2023-06-11 2023-07-30 2023-08-20 2023-09-10 2024-09-09 ice and Public Trust ant Selection ntation pervision of construction of I ntegrated Justice Centre (IJC) in Pwani. TZ-JUDICIARY TZ-364604-CS -INDV / Individual Consultant- Component 3: Access to Just Individual Consult Pending Impleme Clerk of Works (CoWs) for su IDA / 70580 Post Open - National 0.00 2023-06-11 2023-07-30 2023-08-20 2023-09-10 2024-09-09 ice and Public Trust ant Selection ntation pervision of construction of I ntegrated Justice Centre (IJC) in Tanga. TZ-JUDICIARY TZ-364581-CS -INDV / Individual Consultant- Component 3: Access to Just Individual Consult Pending Impleme Clerk of Works (CoWs) for su IDA / 70580 Post Open - National 0.00 2023-06-11 2023-07-30 2023-08-20 2023-09-10 2024-09-09 ice and Public Trust ant Selection ntation pervision of construction of I ntegrated Justice Centre (IJC) in Geita. TZ-JUDICIARY TZ-364606-CS -INDV / Individual Consultant- Component 3: Access to Just Individual Consult Pending Impleme Clerk of Works (CoWs) for su IDA / 70580 Post Open - National 0.00 2023-06-11 2023-07-30 2023-08-20 2023-09-10 2024-09-09 ice and Public Trust ant Selection ntation pervision of construction of t he Integrated Justice Centre ( IJC) in Manyara. TZ-JUDICIARY TZ-364574-CS -INDV / Individual Consultant- Component 3: Access to Just Individual Consult Clerk of Works (CoWs) for su IDA / 70580 Post Open - National 0.00 Under Review 2023-06-11 2023-07-30 2023-08-20 2023-09-10 2024-09-09 ice and Public Trust ant Selection pervision of construction of i ntegrated justice centre (IJC) in Singida TZ-JUDICIARY TZ-9441-CS-IN DV / Consultancy to review ju Component 3: Access to Just Individual Consult IDA / 57780 Post Open 0.00 Canceled 2017-04-24 2017-06-12 2017-07-03 2017-08-07 2018-02-03 stice chain, identify gaps in t ice and Public Trust ant Selection erms of policy, strategy, refo rm or performance TZ-JUDICIARY TZ-9445-CS-IN Component 3: Access to Just Individual Consult DV / Consultancy to prepare IDA / 57780 Post Open 0.00 Canceled 2017-04-24 2017-06-12 2017-07-03 2017-08-07 2018-02-03 ice and Public Trust ant Selection special program on legal aid with MoCLA TZ-JUDICIARY TZ-9410-CS-C Component 3: Access to Just DS / Consultancy service for IDA / 57780 Post Direct Selection Direct 121,856.63 Completed 2017-03-29 2019-01-18 2017-04-08 2019-04-17 2017-06-12 2019-06-27 2017-12-09 2019-09-27 ice and Public Trust Court User Survey. TZ-JUDICIARY TZ-9433-CS-IN Component 1: Governance, Individual Consult DV / Procurement of IT Speci IDA / 57780 Organization and Systems D Post Open 0.00 Canceled 2017-04-17 2017-06-05 2017-06-26 2017-07-31 2018-01-27 ant Selection alist to support Project team evelopment TZ-JUDICIARY TZ-9422-CS-IN Component 1: Governance, Individual Consult DV / Procurement Specialist t IDA / 57780 Organization and Systems D Post Open 0.00 Canceled 2017-03-09 2017-02-02 2017-04-27 2017-05-11 2017-05-18 2017-06-22 2017-12-19 ant Selection o Support Project Team evelopment TZ-JUDICIARY TZ-9431-CS-IN DV / Consultancy service to s Component 3: Access to Just Individual Consult IDA / 57780 Post Open 0.00 Canceled 2017-05-12 2017-06-30 2017-07-21 2017-08-25 2018-02-21 upport the development of A ice and Public Trust ant Selection DR and backlog reduction pr ogram TZ-JUDICIARY TZ-9440-CS-IN DV / Consultancy Services to Component 3: Access to Just Individual Consult IDA / 57780 Post Open 0.00 Canceled 2017-07-18 2017-09-05 2017-09-26 2017-10-31 2018-04-29 introduce Online interactive c ice and Public Trust ant Selection omplaints platform Page 8 PROCUREMENT PLAN (Textual Part) Project information: Proyecto de Respuesta de El Salvador ante el COVID 19 - P173872 Project Implementation agency: Ministerio de Salud Date of the Procurement Plan: 27 de Enero de 2021 Period covered by this Procurement Plan: Enero 2021 – Diciembre 2021 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. PROCUREMENT El Salvador : El Salvador COVID-19 Emergency Response Project PLAN General Information Country: El Salvador 2021-06-10 Bank’s Approval Date of the Original Procurement Plan: 2023-06-02 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P173872 GPN Date: 2022-01-24 Project Name: El Salvador COVID-19 Emergency Response Project Loan / Credit No: IBRD / 91000, IBRD / 92290, IBRD / 94290 Health Ministry Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned RECOVID-4-RFB-GO / Equipo, Component 1: Emergency C Open - Internationa Single Stage - One E 2022-02-1 cristalería, insumos y mobilia IBRD / 91000 OVID-19 response to preven Post Request for Bids 914,805.00 0.00 Canceled 2021-03-22 2021-04-15 2021-05-31 2021-07-20 2021-08-19 l nvelope 5 rio para Laboratorio de Biolo tion, detection and treatmen gía Molecular t  RECOVID-63-RFQ-CW / Adec Component 1: Emergency C uación de infraestructura par Request for Quota OVID-19 response to preven Request for Quota Single Stage - One E 2022-09-2 a la sustitución del sistema d IBRD / 92290 Post Open - National tions (Non Bank-S 52,830.00 0.00 Signed 2022-04-18 2022-05-26 2022-06-27 tion, detection and treatmen tions nvelope 5 e generación de vapor Hospit PD) t  al Nueva Concepción, Chalat enango RECOVID-53-RFB-CW / Remo delación y readecuación de o Component 1: Emergency C Request for Bids - bras eléctricas y electromecá OVID-19 response to preven Single Stage - One E Small Works SPD Pending Imp 2023-04-2 nicas de las instalaciones del IBRD / 92290 Post Request for Bids Open - National 3,900,000.00 0.00 2022-04-12 2022-04-15 2022-05-15 2022-06-14 2022-07-19 tion, detection and treatmen nvelope (1 envelope proce lementation 5 Almacén Regional de Salud d t  ss) el área Metropolitana de San Salvador en el Centro Nacion al de Biológicos RECOVID-138-RFB-CW / Ade Component 1: Emergency C Request for Bids - cuación de Infraestructura pa OVID-19 response to preven Single Stage - One E Small Works SPD Under Imple 2023-06-2 IBRD / 92290 Post Request for Bids Open - National 186,040.00 0.00 2022-10-31 2023-01-25 2022-11-05 2023-03-08 2022-11-25 2023-03-07 2022-12-15 2023-05-18 2022-12-29 ra la Instalación de Cuarto Frí tion, detection and treatmen nvelope (1 envelope proce mentation 7 o de la Región Paracentral de t  ss) Salud del MINSAL RECOVID-96-RFB-CW / Remo delación y readecuación de o Component 1: Emergency C Request for Bids - bras eléctricas y electromecá OVID-19 response to preven Open - Internationa Single Stage - One E Works (without pr 2023-11-1 nicas de las instalaciones del IBRD / 92290 Post Request for Bids 3,650,000.00 0.00 Canceled 2022-10-28 2022-11-02 2022-12-02 2022-12-30 2023-02-03 tion, detection and treatmen l nvelope equalification) SP 0 Almacén Regional de Salud d t  D el Área Metropolitana de San Salvador en el Centro Nacion al de Biológicos. RECOVID-147-DIR-CW / Rem odelación y readecuación de Component 1: Emergency C obras eléctricas y electromec OVID-19 response to preven Other (with field f Under Imple 2023-11-0 ánicas de las instalaciones d IBRD / 92290 Post Direct Selection Direct - National 3,650,000.00 0.00 2022-12-09 2022-12-13 2022-12-14 2023-01-09 2023-01-12 tion, detection and treatmen or explanation) mentation 8 el Almacén Regional de Salu t  d del Área Metropolitana de San Salvador en el Centro Na cional de Biológicos. RECOVID-159-RFB-CW / Rea Component 1: Emergency C decuación y Ampliación Unid OVID-19 response to preven Single Stage - One E Other (with field f 2023-12-0 IBRD / 92290 Post Request for Bids Open - National 833,267.69 0.00 Canceled 2023-01-20 2023-03-23 2023-01-25 2023-03-23 2023-02-24 2023-03-16 2023-04-11 ad de Pediatría Hospital Naci tion, detection and treatmen nvelope or explanation) 7 onal Zacamil, Dr. Juan José F t  ernández RECOVID-175-RFB-CW / Rea Component 1: Emergency C Request for Bids - decuación y Ampliación Unid OVID-19 response to preven Single Stage - One E Small Works SPD Under Imple 2024-05-0 IBRD / 92290 Post Request for Bids Open - National 1,100,000.00 0.00 2023-06-02 2023-06-21 2023-06-07 2023-06-22 2023-07-07 2023-08-06 2023-09-04 ad de Pediatría Hospital Naci tion, detection and treatmen nvelope (1 envelope proce mentation 1 onal Zacamil, Dr. Juan José F t  ss) ernández RECOVID-178-RFB-CW / Amp Component 1: Emergency C Request for Bids - liación de las áreas de Labor OVID-19 response to preven Single Stage - One E Small Works SPD Pending Imp 2024-01-2 atorios Clínicos de las Unidad IBRD / 92290 Post Request for Bids Open - National 150,000.00 0.00 2023-06-16 2023-06-21 2023-07-21 2023-08-18 2023-09-22 tion, detection and treatmen nvelope (1 envelope proce lementation 0 es de Salud de Dulce Nombre t  ss) de María, Chalatenango y Ciu dad Barrios, San Miguel RECOVID-183-RFB-CW / Mejo Component 1: Emergency C Request for Bids - ras de la Unidad de Salud de OVID-19 response to preven Single Stage - One E Small Works SPD Pending Imp 2024-04-1 El Triunfo, Usulután a través IBRD / 92290 Post Request for Bids Open - National 235,000.00 0.00 2023-08-07 2023-08-12 2023-08-15 2023-09-14 2023-10-19 tion, detection and treatmen nvelope (1 envelope proce lementation 6 de la implementación del áre t  ss) a de Laboratorio Clínico. GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual RECOVID-1-RFB-GO / Sumini Component 1: Emergency C stro, instalación y puesta en OVID-19 response to preven Open - Internationa Single Stage - One E marcha de equipos de unida IBRD / 91000 Prior Request for Bids 7,131,425.00 0.00 Signed 2021-08-23 2021-12-15 2021-09-13 2021-12-20 2021-10-28 2022-03-15 2021-11-27 2023-01-13 2022-01-25 2022-07-24 tion, detection and treatmen l nvelope d de radiología e imágenes di t  agnósticas para el Hospital N acional El Salvador. RECOVID-10-RFQ-GO / Equip Component 1: Emergency C os de seguridad ocupacional OVID-19 response to preven Request for Quota Single Stage - One E Pending Impl IBRD / 91000 Post Open - National 22,400.00 0.00 2021-09-17 2021-11-28 2022-02-26 para personal elaborando en tion, detection and treatmen tions nvelope ementation áreas de riesgo del Hospital t  El Salvador RECOVID-5-RFQ-GO / Equipo Component 1: Emergency C Request for Quota Single Stage - One E y mobiliario clínico para Hosp IBRD / 91000 OVID-19 response to preven Post Open - National 62,625.00 0.00 Canceled 2021-10-27 2022-01-26 2022-04-26 tions nvelope ital El Salvador tion, detection and treatmen t  Component 1: Emergency C RECOVID-6-RFQ-GO / Mobilia Request for Quota Single Stage - One E IBRD / 91000 OVID-19 response to preven Post Open - National 138,750.00 0.00 Canceled 2021-10-12 2022-01-12 2022-04-12 rio para Hospital El Salvador tions nvelope tion, detection and treatmen t  RECOVID-27-RFQ-GO / Insu Component 2. Project Manag Request for Quota Single Stage - One E mos informáticos para funcio IBRD / 91000 Post Open - National 1,659.00 1,232.88 Signed 2021-08-06 2021-09-27 2021-10-12 2021-10-12 ement and Monitoring tions nvelope namiento de la UGP RECOVID-11-RFQ-GO / Equip Component 1: Emergency C Request for Quota Single Stage - One E o informático y mobiliario par IBRD / 91000 OVID-19 response to preven Post Open - National 8,000.00 8,556.51 Signed 2021-08-16 2021-10-05 2021-11-17 2021-11-19 tions nvelope a ejecución del proyecto tion, detection and treatmen t  Page 1 RECOVID-7-RFQ-GO / Equipo Component 1: Emergency C s para el fortalecimiento de e OVID-19 response to preven Request for Quota Single Stage - One E Pending Impl spacio de almacén para insu IBRD / 91000 Post Open - National 25,000.00 0.00 2022-01-25 2022-04-14 2022-05-29 tion, detection and treatmen tions nvelope ementation mos y medicamentos dentro t  del Hospital El Salvador RECOVID-8-RFQ-GO / Equipo Component 1: Emergency C s para el fortalecimiento de e OVID-19 response to preven Request for Quota Single Stage - One E Pending Impl IBRD / 91000 Post Open - National 30,000.00 0.00 2022-01-17 2022-04-04 2022-07-03 spacio de almacenamiento d tion, detection and treatmen tions nvelope ementation e desechos bioinfecciosos t  RECOVID-9-RFQ-GO / Mobilia Component 1: Emergency C Request for Quota Single Stage - One E Pending Impl rio para las áreas de socializa IBRD / 91000 OVID-19 response to preven Post Open - National 25,000.00 0.00 2021-11-04 2022-01-11 2022-02-25 tions nvelope ementation ción y alimentación del perso tion, detection and treatmen nal t  RECOVID-3-RFB-GO / Sumini Component 1: Emergency C stro, instalación y puesta en f OVID-19 response to preven Open - Internationa Single Stage - One E uncionamiento de equipos pa IBRD / 91000 Prior Request for Bids 2,442,500.00 1,296,504.90 Signed 2021-08-23 2021-12-15 2021-09-13 2021-12-20 2021-10-28 2022-03-03 2021-11-27 2022-06-15 2022-01-08 2022-09-03 2022-07-07 tion, detection and treatmen l nvelope ra la central de esterilización t  del Hospital Nacional El Salva dor RECOVID-2-RFB-GO / Sumini Component 1: Emergency C stro, instalación y puesta en f OVID-19 response to preven Open - Internationa Single Stage - One E Under Imple uncionamiento de equipos de IBRD / 91000 Prior Request for Bids 2,535,000.00 0.00 2021-08-23 2022-03-10 2021-09-13 2022-03-17 2021-10-28 2022-05-30 2021-11-27 2022-10-25 2022-01-25 2022-07-24 tion, detection and treatmen l nvelope mentation la sala de angiógrafo y quiróf t  ano general del Hospital Naci onal El Salvador RECOVID-32-DIR-GO / Adqui Component 1: Emergency C sición de medicamentos (Toc IBRD / 91000 OVID-19 response to preven Post Direct Selection Direct 1,216,656.00 1,216,656.00 Completed 2020-06-24 2020-06-24 2020-06-26 2020-06-26 2020-06-27 2020-06-28 2020-07-20 2020-07-21 ilizumab) tion, detection and treatmen t  RECOVID-33-DIR-GO / Adqui Component 1: Emergency C sición de oxígeno medicinal lí IBRD / 91000 OVID-19 response to preven Post Direct Selection Direct 99,996.00 99,996.49 Completed 2020-07-31 2020-07-30 2020-07-31 2020-07-31 2020-08-01 2020-08-02 2020-09-04 2020-08-12 quido para el Hospital Nacion tion, detection and treatmen al El Salvador t  RECOVID-34-DIR-GO / Adqui Component 1: Emergency C sición de medicamentos (Toc IBRD / 91000 OVID-19 response to preven Post Direct Selection Direct 1,569,568.00 1,569,568.00 Completed 2020-08-06 2020-08-06 2020-08-06 2020-08-06 2020-08-07 2020-08-08 2020-09-06 2020-08-22 ilizumab) tion, detection and treatmen t  RECOVID-35-DIR-GO / Adqui Component 1: Emergency C sición de reactivos de laborat OVID-19 response to preven orio (set de extracción para IBRD / 91000 Post Direct Selection Direct 1,043,455.00 1,043,455.04 Completed 2020-08-07 2020-08-07 2020-08-12 2020-08-12 2020-08-13 2020-08-14 2020-11-11 2020-09-06 tion, detection and treatmen RNA/DNA viral y set de ampli t  ficación de ácidos nucleicos RECOVID-36-DIR-GO / Adqui Component 1: Emergency C sición de oxígeno medicinal lí IBRD / 91000 OVID-19 response to preven Post Direct Selection Direct 99,996.00 99,996.49 Completed 2020-08-12 2020-08-13 2020-08-12 2020-08-12 2020-08-13 2020-08-14 2020-08-22 2020-08-23 quido para el Hospital Nacion tion, detection and treatmen al El Salvador t  RECOVID-28-RFB-GO / Sumi Component 1: Emergency C nistro, instalación y puesta e OVID-19 response to preven Open - Internationa Single Stage - One E n marcha de equipo de Labor IBRD / 91000 Post Request for Bids 1,172,105.00 0.00 Signed 2022-01-07 2022-03-22 2022-01-14 2022-05-11 2022-02-28 2022-06-24 2022-03-30 2022-12-13 2022-05-04 2022-10-31 tion, detection and treatmen l nvelope atorio de Biología Molecular t  para Hospital Nacional El Sal vador RECOVID-37-RFQ-GO / Equip o informático y audio para el Component 2. Project Manag Request for Quota Single Stage - One E IBRD / 92290 Post Open - National 69,591.00 21,678.30 Signed 2022-01-26 2022-03-24 2022-06-23 2022-06-22 fortalecimiento del área de p ement and Monitoring tions nvelope romoción de la salud. RECOVID-38-RFQ-GO / Adqui Component 2. Project Manag Request for Quota Single Stage - One E sición de mobiliario de oficin IBRD / 92290 Post Open - National 20,670.00 9,596.11 Signed 2022-01-31 2022-03-28 2022-02-24 2022-04-27 ement and Monitoring tions nvelope a para dependencias del MIN SAL y UGPPI RECOVID-39-RFQ-GO / Papel Component 1: Emergency C ería para el fortalecimiento al OVID-19 response to preven Request for Quota Single Stage - One E IBRD / 92290 Post Open - National 7,279.00 5,266.39 Signed 2022-02-01 2022-03-22 2022-05-16 2022-04-21 componente técnico y proces tion, detection and treatmen tions nvelope os en promoción de la salud t  RECOVID-40-RFQ-GO / Mobili Component 1: Emergency C ario para el fortalecimiento al OVID-19 response to preven Request for Quota Single Stage - One E IBRD / 92290 Post Open - National 23,130.00 16,519.00 Signed 2022-01-24 2022-04-07 2022-07-19 2022-06-06 componente técnico y proces tion, detection and treatmen tions nvelope os de promoción de la salud t  RECOVID-49-DIR-GO / Vacun Component 1: Emergency C a contra SARS COV-2 inactiva IBRD / 92290 OVID-19 response to preven Prior Direct Selection Direct 20,000,000.00 0.00 Canceled 2021-04-23 2021-12-22 2021-04-23 2021-12-22 2021-04-26 2021-07-01 da CORONAVAC suspensión i tion, detection and treatmen nyectable t  RECOVID-49-DIR-GO-2 / Vac Component 1: Emergency C una contra SARS COV-2 inact IBRD / 92290 OVID-19 response to preven Post Direct Selection Direct 20,000,000.00 30,000,000.00 Completed 2021-04-23 2021-12-03 2021-04-23 2021-12-10 2021-04-26 2021-03-11 2021-07-01 2021-07-02 ivada CORONAVAC suspensió tion, detection and treatmen n inyectable t  Component 1: Emergency C RECOVID-54-DIR-GO / Equip IBRD / 91000 OVID-19 response to preven Post Direct Selection Direct 1,499,250.00 1,499,250.00 Completed 2020-07-06 2020-07-06 2020-07-07 2020-07-07 2020-07-08 2020-07-09 2020-09-06 2020-09-08 o de alto flujo de oxigeno tion, detection and treatmen t  RECOVID-55-DIR-GO / Adqui Component 1: Emergency C sición de materiales de aseo OVID-19 response to preven personal para Regiones de S IBRD / 91000 Post Direct Selection Direct 102,812.00 115,711.88 Completed 2020-02-01 2020-02-03 2020-02-07 2020-02-07 2020-03-04 2020-03-05 2020-11-09 2020-03-27 tion, detection and treatmen alud y Hospitales Nacionales t  para atender emergencia del Coronavirus. Component 1: Emergency C RECOVID-56-RFB-GO / Insum Single Stage - One E IBRD / 92290 OVID-19 response to preven Post Request for Bids Open - National 200,000.00 181,010.00 Signed 2022-03-31 2022-03-23 2022-04-05 2022-05-05 2022-06-19 2022-05-25 2022-06-08 2022-06-29 2022-07-17 2022-09-27 2022-08-20 os médicos de bioseguridad nvelope tion, detection and treatmen t  RECOVID-57-RFB-GO / Sumi Component 1: Emergency C nistro de emisor Rayos X par OVID-19 response to preven IBRD / 92290 Post Direct Selection Direct 226,050.00 0.00 Canceled 2022-03-04 2022-03-11 2022-04-09 2022-05-09 a equipo de Tomografía para tion, detection and treatmen Hospitales Nacionales. t  RECOVID-61-RFB-GO / Sumi nistro, instalación y puesta e n marcha de sistemas de: ex Component 1: Emergency C tracción de aire y aire acondi OVID-19 response to preven Single Stage - One E IBRD / 92290 Post Request for Bids Open - National 329,509.00 0.00 Canceled 2022-04-04 2022-04-11 2022-05-11 2022-06-10 2022-07-08 2023-01-04 cionado de aplicación especi tion, detection and treatmen nvelope al (100% aire exterior) y recir t  culado, para Hospital Nacion al General Zacamil "Dr. Juan J osé Fernández". Page 2 RECOVID-62-RFB-GO / Sumi Component 1: Emergency C nistro, instalación y puesta e OVID-19 response to preven Single Stage - One E IBRD / 92290 Post Request for Bids Open - National 606,849.00 0.00 Signed 2022-04-11 2022-05-17 2022-04-18 2022-05-17 2022-05-18 2022-06-28 2022-06-17 2022-07-28 2022-07-22 2023-01-18 n marcha de equipo generad tion, detection and treatmen nvelope or de vapor, caldera 100 bhp t  y periféricos. RECOVID-57-DIR-GO / Sumin Component 1: Emergency C istro de emisor Rayos X para IBRD / 92290 OVID-19 response to preven Post Direct Selection Direct 226,050.00 226,050.00 Signed 2022-03-28 2022-03-31 2022-04-04 2022-04-04 2022-04-25 2022-06-11 2022-05-10 equipo de Tomografía para H tion, detection and treatmen ospitales t  RECOVID-65-RFQ-GO / Equip Component 1: Emergency C Request for Quota Single Stage - One E Under Imple o informático y software para IBRD / 92290 OVID-19 response to preven Post Open - National 30,000.00 0.00 2022-04-18 2022-06-06 2022-10-04 tions nvelope mentation el fortalecimiento de Epidemi tion, detection and treatmen ología MINSAL t  RECOVID-66-RFQ-GO / Mater Component 1: Emergency C iales promocionales para ide OVID-19 response to preven Request for Quota Single Stage - One E IBRD / 92290 Post Open - National 10,000.00 0.00 Signed 2022-04-19 2022-06-07 2022-07-07 ntificación del personal de ep tion, detection and treatmen tions nvelope idemiología de campo t  RECOVID-67-RFQ-GO / Aires Component 1: Emergency C Request for Quota Single Stage - One E acondicionados para depend IBRD / 92290 OVID-19 response to preven Post Open - National 36,000.00 0.00 Canceled 2022-05-18 2022-07-13 2022-08-12 tions nvelope encias del MINSAL tion, detection and treatmen t  RECOVID-68-RFQ-GO / Adqui Component 1: Emergency C sición de Mobiliario para el fo OVID-19 response to preven Request for Quota Single Stage - One E IBRD / 92290 Post Open - National 6,711.00 0.00 Signed 2022-05-18 2022-07-06 2022-08-05 rtalecimiento de la Dirección tion, detection and treatmen tions nvelope de Promoción de Salud t  RECOVID-69-RFQ-GO / Adqui Component 2. Project Manag Request for Quota Single Stage - One E sición de equipo de computo IBRD / 92290 Post Open - National 30,000.00 13,565.25 Signed 2022-05-13 2022-06-27 2022-07-21 2022-08-26 ement and Monitoring tions nvelope para ser utilizado en la UGP-P I RECOVID-71-RFW-GO / Insu Component 2. Project Manag Request for Quota Single Stage - One E mos Infromáticos para funcio IBRD / 92290 Post Open - National 2,000.00 0.00 Canceled 2022-05-07 2022-06-14 2022-06-29 ement and Monitoring tions nvelope namiento de UGP RECOVID-72-RFQ-NC / Contr atación de servicios de alime ntación y uso de instalacion Component 2. Project Manag Request for Quota Single Stage - One E IBRD / 92290 Post Open - National 7,400.00 6,880.00 Signed 2022-05-16 2022-07-25 2022-07-29 2023-05-31 es para jornadas de socializa ement and Monitoring tions nvelope ción con partes interesadas, poblaciones vulnerables y for talecimiento y personal de sa lud. RECOVID-73-RFB-GO / Adqui Component 1: Emergency C sición de estantería industrial OVID-19 response to preven Single Stage - One E Pending Impl y equipo de carga para fortal IBRD / 92290 Post Request for Bids Open - National 190,000.00 0.00 2022-05-17 2022-05-23 2022-07-04 2022-08-03 2022-09-07 2023-02-04 tion, detection and treatmen nvelope ementation ecer la cadena de suministro t  s con la mejora del almacén El Paraíso del MINSAL RECOVID-78-RFQ-GO / Adqui sición y Suministro de Insum Component 2. Project Manag Request for Quota Single Stage - One E IBRD / 92290 Post Open - National 59,500.00 0.00 Signed 2022-06-20 2022-09-09 2022-08-18 2022-09-19 os para Establecimientos de ement and Monitoring tions nvelope Salud en el Marco de la Gesti ón Ambiental RECOVID-80-RFB-GO / Comp ra de frigoríficos para fortale Component 1: Emergency C cimiento de la cadena de frío OVID-19 response to preven Open - Internationa Single Stage - One E Under Imple IBRD / 92290 Post Request for Bids 1,200,000.00 0.00 2022-06-24 2023-01-10 2022-08-08 2023-01-18 2022-09-19 2023-03-02 2022-10-19 2023-06-07 2022-11-23 2023-03-23 del MINSAL para el almacena tion, detection and treatmen l nvelope mentation miento adecuado de vacunas t  , con énfasis en la vacuna co ntar la COVID-19 RECOVID-81-DIR-GO / Adqui sición y Suministro de Repue stos como parte del servicio Component 1: Emergency C del mantenimiento preventiv OVID-19 response to preven o y correctivo de equipo de R IBRD / 92290 Post Direct Selection Direct 29,000.00 0.00 Signed 2022-06-24 2022-07-27 2022-07-01 2022-08-10 2022-08-05 2023-01-02 tion, detection and treatmen esonancia Magnética del Hos t  pital Nacional Rosales y de la Fuente de Suministro Eléctric o UPS para el Hospital Nacion al General Neumología RECOVID-82-RFQ-GO / Adqui Component 1: Emergency C sición de Equipo informático OVID-19 response to preven Request for Quota Single Stage - One E Under Imple IBRD / 92290 Post Open - National 54,500.00 0.00 2022-07-20 2022-09-22 2022-12-21 y audio para el fortalecimient tion, detection and treatmen tions nvelope mentation o del área de promoción de l t  a salud. RECOVID-41-RFB-GO / Sumi nistro, instalación y puesta e Component 1: Emergency C n marcha de planta generad OVID-19 response to preven Open - Internationa Single Stage - One E IBRD / 92290 Prior Request for Bids 5,000,000.00 0.00 Canceled 2022-01-31 2022-02-04 2022-03-21 2022-04-20 2022-06-03 2022-11-30 ora de oxígeno médico (PGO tion, detection and treatmen l nvelope M) para el sistema hospitalari t  o del Ministerio de Salud de E l Salvador RECOVID-83-RFB-GO / SUMI NISTRO, INSTALACIÓN Y PUE Component 1: Emergency C STA EN FUNCIONAMIENTO DE OVID-19 response to preven Open - Internationa Single Stage - One E Under Imple IBRD / 92290 Post Request for Bids 867,100.00 0.00 2022-08-08 2022-10-04 2022-08-18 2022-10-05 2022-09-29 2022-11-15 2022-10-28 2023-01-16 2022-12-02 2023-05-01 LAVADORAS TERMODESINFE tion, detection and treatmen l nvelope mentation CTADORAS Y BAÑOS ULTRAS t  ONICOS PARA HOSPITAL NAC IONAL EL SALVADOR. RECOVID-84-RFQ-GO / SUMI Component 1: Emergency C NISTRO, INSTALACIÓN Y PUE OVID-19 response to preven Request for Quota Single Stage - One E STA EN FUNCIONAMIENTO DE IBRD / 92290 Post Open - National 30,000.00 0.00 Signed 2022-08-08 2022-10-03 2023-03-02 tion, detection and treatmen tions nvelope MAQUINAS PARA CORTAR TE t  LA PARA HOSPITAL NACIONA L EL SALVADOR. RECOVID-76-RFB-GO / SUMI Component 1: Emergency C NISTRO, INSTALACIÓN Y PUE OVID-19 response to preven Single Stage - One E STA EN FUNCIONAMIENTO DE IBRD / 92290 Post Request for Bids Open - National 121,500.00 0.00 Signed 2022-06-01 2022-08-29 2022-06-06 2022-10-07 2022-07-18 2022-10-07 2022-08-17 2023-01-18 2022-09-21 2022-12-20 tion, detection and treatmen nvelope EQUIPO DE ENDOSCOPIA PAR t  A EL HOSPITAL NACIONAL RO SALES. RECOVID-87-RFB-GO / SUMI Component 1: Emergency C NISTRO, INSTALACIÓN Y PUE OVID-19 response to preven Open - Internationa Single Stage - One E Under Imple STA EN MARCHA DE EQUIPOS IBRD / 92290 Post Request for Bids 844,000.00 0.00 2022-09-02 2022-12-05 2022-09-19 2023-02-10 2022-10-31 2022-11-30 2023-01-04 2023-07-03 tion, detection and treatmen l nvelope mentation DE RAYOS "X" DIGITALES EN t  HOSPITALES PRIORIZADOS RECOVID-88-DIR-GO / Adqui Component 1: Emergency C sición de Vacuna inactiva par OVID-19 response to preven Direct - Internation IBRD / 94290 Prior Direct Selection 15,600,000.00 35,600,000.00 Completed 2021-03-10 2022-08-15 2021-03-10 2022-08-16 2021-03-10 2021-03-11 2021-05-19 2021-05-20 a la profilaxis del SARS CoV-2 tion, detection and treatmen al SINOVAC original t  Page 3 RECOVID-89-DIR-GO / Adqui Component 1: Emergency C sición de BNT 162, Vacuna A OVID-19 response to preven Direct - Internation RNm dirigida contra SARS Co IBRD / 94290 Prior Direct Selection 29,694,600.00 29,694,600.00 Completed 2021-05-07 2022-08-09 2021-05-07 2022-08-09 2021-05-25 2021-05-20 2022-03-04 2021-12-31 tion, detection and treatmen al V-2 para prevenir la infección t  por COVID-19 en los seres hu manos RECOVID-90-DIR-GO / Adqui Component 1: Emergency C sición de vacuna para SARS- OVID-19 response to preven Direct - Internation IBRD / 94290 Prior Direct Selection 15,000,000.00 15,000,000.00 Completed 2021-05-07 2022-08-15 2021-05-15 2022-08-16 2021-06-17 2021-06-18 2021-07-23 2021-09-12 CoV-2 (VERO CELL) inactivad tion, detection and treatmen al a Vacuna COVID-19 (VERO C t  ELL Inactivada) RECOVID-91-DIR-GO / Vacun Component 1: Emergency C Direct - Internation a contra SARS COV-2 inactiva IBRD / 94290 OVID-19 response to preven Prior Direct Selection 5,000,000.00 35,000,000.00 Completed 2021-04-23 2022-08-09 2021-04-23 2022-08-10 2021-04-26 2021-03-11 2021-07-01 2021-07-08 al da CORONAVAC suspensión i tion, detection and treatmen nyectable t  RECOVID-75-RFB-GO / SUMI NISTRO, INSTALACIÓN Y PUE Component 1: Emergency C STA EN MARCHA DEL SISTEM OVID-19 response to preven Single Stage - One E IBRD / 92290 Post Request for Bids Open - National 48,000.00 0.00 Canceled 2022-06-01 2022-06-06 2022-07-18 2022-08-17 2022-09-21 2023-01-19 A DE AIRE ACONDICIONADO tion, detection and treatmen nvelope Y VENTILACIÓN MECÁNICA, P t  ARA EL LABORATORIO DE PA TOLOGÍA DEL HOSPITAL ROS ALES. RECOVID-92-RFQ-GO / Aires Component 1: Emergency C Request for Quota Single Stage - One E Acondicionados para depend IBRD / 92290 OVID-19 response to preven Post Open - National 9,500.00 0.00 Signed 2022-09-02 2022-11-02 2023-01-01 tions nvelope encias del MINSAL tion, detection and treatmen t  RECOVID-86-RFQ-GO / SUMI Component 1: Emergency C NISTRO, INSTALACIÓN Y PUE OVID-19 response to preven Request for Quota Open - Internationa Single Stage - One E Under Imple STA EN MARCHA DE TOMOG IBRD / 92290 Post 1,350,000.00 0.00 2022-09-26 2022-11-21 2023-05-20 tion, detection and treatmen tions l nvelope mentation RAFO COMPUTARIZADO MUL t  TICORTE PARA EL HOSPITAL NACIONAL DE LA MUJER RECOVID-85-RFQ-GO / SUMI NISTRO, INSTALACIÓN Y PUE STA EN MARCHA DE EQUIPOS Component 1: Emergency C DE UNIDAD DE RADIOLOGÍA OVID-19 response to preven Request for Quota Open - Internationa Single Stage - One E Under Imple IBRD / 92290 Prior 7,501,000.00 0.00 2022-09-26 2023-02-24 2022-11-21 2023-05-20 E IMÁGENES DIAGNÓSTICAS tion, detection and treatmen tions l nvelope mentation PARA EL HOSPITAL NACIONA t  L ROSALES, HOSPITAL NACIO NAL ZACAMIL Y HOSPITAL NA CIONAL SAN RAFAEL RECOVID-95-RFB-GO / Sumi Component 1: Emergency C nistro, Instalación y Puesta e OVID-19 response to preven Single Stage - One E IBRD / 92290 Post Request for Bids Open - National 200,000.00 0.00 Signed 2022-09-30 2022-11-24 2022-10-05 2023-01-30 2022-11-04 2023-01-12 2022-12-02 2023-02-23 2022-12-22 2023-05-21 n funcionamiento de Autocla tion, detection and treatmen nvelope ve para Hospital Nacional Sa t  n Vicente RECOVID-97-RFB-GO / Adqui Component 1: Emergency C sición de estantería industrial OVID-19 response to preven Single Stage - One E Under Imple y equipo de carga para mejor IBRD / 92290 Post Request for Bids Open - National 250,000.00 0.00 2022-10-14 2022-11-28 2022-10-19 2022-12-05 2022-11-18 2023-01-04 2022-12-16 2023-02-03 2023-01-20 2023-06-19 tion, detection and treatmen nvelope mentation ar el almacenamiento en alm t  acén el Paraíso del MINSAL. RECOVID-99-RFB-GO / Sumi Component 1: Emergency C nistro, Instalación y Puesta e OVID-19 response to preven Single Stage - One E Pending Impl IBRD / 92290 Post Request for Bids Open - National 100,000.00 0.00 2022-10-10 2022-10-17 2022-11-28 2022-12-28 2023-02-01 2023-08-30 n marcha de Curato Frío Regi tion, detection and treatmen nvelope ementation ón Central de Salud, Ministeri t  o de Salud RECOVID-100-RFQ-GO / Aire Component 1: Emergency C s Acondicionados Dependenc OVID-19 response to preven Request for Quota Single Stage - One E IBRD / 92290 Post Open - National 26,500.00 0.00 Signed 2022-11-02 2022-12-28 2023-02-11 ias del MINSAL: Dirección de tion, detection and treatmen tions nvelope Inmunizaciones y Centro Nac t  ional de Biológicos RECOVID-101-RFB-GO / Sum inistro, Instalación y Puesta e Component 2. Project Manag Single Stage - One E Under Imple IBRD / 92290 Post Request for Bids Open - National 200,000.00 0.00 2022-10-31 2023-02-07 2022-11-07 2023-02-07 2022-12-19 2023-01-18 2023-02-22 2023-08-21 n Marcha de Paneles Solares ement and Monitoring nvelope mentation para Hospitales Priorizados, Ministerio de Salud RECOVID-DIR-102-GO / ADQ Component 1: Emergency C UISICIÓN DE CARRO PARA CU OVID-19 response to preven RACIONES PARA STABLECIMI IBRD / 94290 Post Direct Selection Direct - National 331,000.00 331,000.00 Signed 2021-01-12 2021-01-12 2021-03-02 2021-03-02 2021-04-06 2021-04-20 2021-10-03 tion, detection and treatmen ENTOS DE SALUD DE APLICA t  CIÓN DE LA VACIUNA CONTR A COVID-19 RECOVID-DIR-103-GO / ADQ Component 1: Emergency C UISICION DE MEDICAMENTOS OVID-19 response to preven IBRD / 94290 Post Direct Selection Direct - National 1,867,320.00 1,867,320.00 Signed 2022-01-19 2021-11-22 2022-02-01 2022-02-01 2022-02-24 2022-03-08 2022-05-25 CASIMIRAB E INDIMIRAB PAR tion, detection and treatmen A EL TRATAMIENTO DE COVI t  D 19 Component 1: Emergency C RECOVID-DIR-104-GO / ADQ IBRD / 94290 OVID-19 response to preven Post Direct Selection Direct - National 9,000.00 9,000.00 Completed 2021-01-11 2021-01-20 2021-02-04 2021-02-04 2021-03-10 2021-03-21 2021-12-31 2021-07-28 UISICIÓN DE EQUIPO MÉDICO tion, detection and treatmen t  RECOVID-DIR-106-GO / ADQ Component 1: Emergency C UISICIÓN DE INSUMOS DE LA OVID-19 response to preven IBRD / 94290 Post Direct Selection Direct - National 1,685,635.84 1,685,635.84 Signed 2021-02-25 2021-03-02 2021-03-04 2021-03-04 2021-03-11 2021-03-16 2021-07-11 BORATORIO (SET DE AMPLIFI tion, detection and treatmen CACIÓN DE ÁCIDOS NUCLEIC t  OS RT-PCR Y PCR) RECOVID-DIR-107-GO / ADQ Component 1: Emergency C UISICIÓN DE INSUMOS MEDIC IBRD / 94290 OVID-19 response to preven Post Direct Selection Direct - National 2,283,600.00 2,283,600.00 Signed 2021-03-05 2021-03-09 2021-03-22 2021-03-22 2021-04-20 2021-04-21 2021-05-31 OS (MASCARILLAS N95) tion, detection and treatmen t  RECOVID-DIR-109-GO / ADQ Component 1: Emergency C UISICIÓN DE MEDICAMENTOS IBRD / 94290 OVID-19 response to preven Post Direct Selection Direct - National 73,730.00 73,730.00 Signed 2021-03-15 2021-03-19 2021-04-08 2021-04-08 2021-04-27 2021-04-28 2021-05-20 (ÁCIDO ACETILSALICILICO) tion, detection and treatmen t  RECOVID-DIR-111-GO / ADQ UISICION DE SUMINISTROS (C Component 1: Emergency C INTAS Y CARTUCHOS PARA I OVID-19 response to preven IBRD / 94290 Post Direct Selection Direct - National 180,540.00 180,540.00 Signed 2021-03-18 2021-04-28 2021-05-19 2021-05-19 2021-06-15 2021-06-16 2021-12-31 MPRESORAS) PARA ESTABLE tion, detection and treatmen CIMIENTOS DE APLICACIÓN D t  E LA VACUNA CONTRA EL SA RS-COVID-II RECOVID-DIR-112-GO / ADQ Component 1: Emergency C UISICIÓN DE SUMINISTROS D OVID-19 response to preven E OFICINA PARA ESTABLECIM IBRD / 94290 Post Direct Selection Direct - National 82,507.00 82,506.29 Signed 2021-03-18 2021-04-20 2021-05-21 2021-05-21 2021-06-25 2021-07-05 2021-12-31 tion, detection and treatmen IENTOS DE APLICACIÓN DE L t  A VACUNA CONTRA EL SARS- COVID-II RECOVID-DIR-114-GO / ADQ Component 1: Emergency C UISICIÓN DE MOBILIARIO (CA OVID-19 response to preven NOPY) PARA ESTABLECIMIEN IBRD / 94290 Post Direct Selection Direct - National 296,510.00 296,510.00 Signed 2021-04-15 2021-04-20 2021-04-29 2021-04-29 2021-05-14 2021-05-15 2021-06-15 tion, detection and treatmen TOS DE APLICACIÓN DE LA V t  ACUNA CONTRA EL SARS-CO VID-II Page 4 RECOVID-DIR-115-GO / ADQ Component 1: Emergency C UISICIÓN DE MEDICAMENTOS OVID-19 response to preven : TOCILIZUMAB 20 MG/ML CO IBRD / 94290 Post Direct Selection Direct - National 1,783,600.00 1,783,600.00 Signed 2021-04-26 2021-04-27 2021-05-20 2021-05-20 2021-07-01 2021-07-02 2021-09-20 tion, detection and treatmen NCENTRADO PARA LIQUIDO P t  ARENTERAL PARA PERFUSIO N FRASCO VIAL 10 ML RECOVID-DIR-117-GO / MEDI Component 1: Emergency C O DE TRANSPORTE UNIVERS OVID-19 response to preven IBRD / 94290 Post Direct Selection Direct - National 177,800.00 177,800.00 Completed 2021-06-11 2021-06-23 2021-06-28 2021-06-28 2021-07-12 2021-07-22 2021-07-15 2021-09-15 AL PARA VIRUS, CON HISOPO tion, detection and treatmen INCORPORADO CAJA (50-100) t  UNIDADES RECOVID-DIR-119-GO / SUMI Component 1: Emergency C NISTRO DE ALGODÓN HIDRO IBRD / 94290 OVID-19 response to preven Post Direct Selection Direct - National 225,990.00 225,990.00 Signed 2021-09-06 2021-09-06 2021-09-28 2021-09-28 2021-11-08 2021-11-20 2021-12-31 FILO ABSORBENTE EN LIBRA tion, detection and treatmen S t  RECOVID-DIR-120-GO / ADQ Component 1: Emergency C UISICIÓN DE INSUMOS MEDIC OVID-19 response to preven IBRD / 94290 Post Direct Selection Direct - National 1,777,174.85 1,777,174.85 Signed 2021-09-16 2021-09-20 2021-09-27 2021-09-27 2021-11-26 2021-12-12 2021-12-31 OS PARA LA DIRECCIÓN NACI tion, detection and treatmen ONAL HOSPITALES t  RECOVID-DIR-121-GO / ADQ Component 1: Emergency C UISICIÓN DE MEDICAMENTOS IBRD / 94290 OVID-19 response to preven Post Direct Selection Direct - National 748,587.53 748,587.61 Signed 2021-09-16 2021-09-21 2021-09-24 2021-09-24 2021-11-24 2021-12-06 2021-12-31 PARA LA DIRECCIÓN NACION tion, detection and treatmen AL HOSPITALES t  RECOVID-DIR-122-GO / ADQ Component 1: Emergency C UISICIÓN DE CASIRIVIMAB E I OVID-19 response to preven MDEVIMAB 120 MG/ML CONC IBRD / 94290 Post Direct Selection Direct - National 1,867,320.00 1,867,320.00 Signed 2021-09-17 2021-09-17 2021-09-19 2021-09-14 2021-09-21 2021-09-26 2021-11-05 tion, detection and treatmen ENTRADO PARA LIQUIDO PAR t  ENTERAL, FRASCO VIAL DE 6 A 20 ML SOLIDO, ORAL RECOVID-DIR-123-GO / ADQ Component 1: Emergency C UISICIÓN DE MEDICAMENTO IBRD / 94290 OVID-19 response to preven Post Direct Selection Direct - National 220,000.00 220,000.00 Signed 2021-10-06 2021-10-18 2021-11-29 2021-11-01 2021-12-01 2021-12-02 2021-12-31 EDOXABAN 60 MG tion, detection and treatmen t  RECOVID-DIR-128-GO / OXIG Component 1: Emergency C ENO MEDICINAL PARA PACIE OVID-19 response to preven IBRD / 94290 Post Direct Selection Direct - National 3,919,020.00 3,919,020.00 Signed 2021-09-16 2021-09-17 2021-09-18 2021-09-18 2021-09-20 2021-09-21 2021-12-31 NTES CON COVID-19 HOSPIT tion, detection and treatmen AL NACIONAL EL SALVADOR t  RECOVID-DIR-132-GO / PRO Component 1: Emergency C DUCCIÓN Y SUMINISTRO DE OVID-19 response to preven IBRD / 94290 Post Direct Selection Direct - National 58,375.80 0.00 Completed 2021-07-17 2021-07-23 2021-07-24 2021-07-24 2021-08-13 2021-09-01 2021-09-10 MOBILIARIO PARA ESTACION tion, detection and treatmen MOVIL DE VACUNACIÓN t  RECOVID-DIR-134-GO / ADQ Component 1: Emergency C UISICION DE ACIDO ASCÓRBI IBRD / 94290 OVID-19 response to preven Post Direct Selection Direct - National 246,035.00 0.00 Completed 2021-11-03 2021-11-12 2021-11-17 2021-11-19 2021-12-23 2022-01-03 2022-05-20 CO PARA KIT COVID 19 (VITA tion, detection and treatmen MINA C) t  RECOVID-135-RFQ-GO / ADQ UISICIÓN DE ARTÍCULOS DE L Component 2. Project Manag Request for Quota Single Stage - One E Under Imple IMPIEZA, ALIMENTACIÓN Y M IBRD / 92290 Post Open - National 2,210.00 0.00 2022-10-19 2022-12-01 2022-12-16 ement and Monitoring tions nvelope mentation ANIPULACIÓN DE ALIMENTOS PARA FUNCIONAMIENTO DE L A UGPPI RECOVID-64-RFB-GO / Sumi Component 1: Emergency C nistro, instalación y puesta e OVID-19 response to preven Single Stage - One E IBRD / 92290 Post Request for Bids Open - National 315,000.00 0.00 Canceled 2022-04-19 2022-06-15 2022-04-26 2022-05-26 2022-07-27 2022-06-25 2022-07-30 2023-02-25 n marcha de cuarto frio Regi tion, detection and treatmen nvelope ón Paracentral de Salud, Mini t  sterio de Salud RECOVID-DIR-140-GO / ADQ Component 1: Emergency C UISICIÓN DE MEDICAMENTOS IBRD / 94290 OVID-19 response to preven Post Direct Selection Direct - National 555,300.00 0.00 Signed 2022-01-07 2022-01-24 2022-02-01 2022-02-01 2022-02-24 2022-12-31 PARA KIT COVID 19 tion, detection and treatmen t  RECOVID-DIR-143-GO / ADQ Component 1: Emergency C UISICION DE MEDICAMENTO IBRD / 94290 OVID-19 response to preven Post Direct Selection Direct - National 666,876.00 0.00 Completed 2021-10-08 2021-10-12 2021-10-18 2021-10-15 2021-11-25 2022-02-25 2022-02-07 PARA KIT COVID 19 tion, detection and treatmen t  RECOVID-DIR-142-GO / ADQ Component 1: Emergency C UISICIÓN DE CUPONES DE C OVID-19 response to preven Single Stage - One E OMBUSTIBLE PARA ABASTECI IBRD / 94290 Post Request for Bids Open - National 90,250.00 0.00 Canceled 2021-04-29 2021-06-02 2021-05-09 2021-07-02 2021-07-12 2021-07-30 2021-12-31 tion, detection and treatmen nvelope MIENTO DE FLOTA DE VEHIC t  ULOS DEL NIVEL SUPERIOR M INSAL RECOVID-DIR-145-GO / ADQ Component 1: Emergency C UISICIÓN DE CUPONES DE C OVID-19 response to preven OMBUSTIBLE PARA ABASTECI IBRD / 94290 Post Direct Selection Direct - National 90,250.00 0.00 Completed 2021-04-29 2021-06-02 2021-07-02 2021-07-02 2021-07-30 2021-12-31 tion, detection and treatmen MIENTO DE FLOTA DE VEHIC t  ULOS DEL NIVEL SUPERIOR M INSAL RECOVID-146-RFQ-GO / Adq uisición de 7 boletos aéreos para la capacitación de siete Component 2. Project Manag Request for Quota Single Stage - One E IBRD / 92290 Post Open - National 10,000.00 0.00 Canceled 2022-11-11 2022-11-16 2022-12-16 profesionales del Laboratorio ement and Monitoring tions nvelope Clínico Nacional de Salud Púb lica en secuenciación genómi ca del SARS-Cov-2. RECOVID-148-DIR-GO / SUMI NISTRO, INSTALACIÓN Y PUE Component 1: Emergency C STA EN FUNCIONAMIENTO DE OVID-19 response to preven Under Imple IBRD / 92290 Post Direct Selection Direct - National 29,000.00 0.00 2022-12-16 2023-01-04 2022-12-21 2023-01-06 2023-01-25 2023-05-25 VIDEO-ENDOSCOPIO Y MONIT tion, detection and treatmen mentation OR A COLOR 19", GRADO MÉ t  DICO PARA EL HOSPITAL NAC IONAL ROSALES. RECOVID-75-RFQ-GO / SUMI NISTRO, INSTALACIÓN Y PUE Component 1: Emergency C STA EN MARCHA DEL SISTEM OVID-19 response to preven Request for Quota Single Stage - One E IBRD / 92290 Post Open - National 48,000.00 0.00 Canceled 2022-08-24 2022-10-26 2023-02-23 A DE AIRE ACONDICIONADO tion, detection and treatmen tions nvelope Y VENTILACIÓN MECÁNICA, P t  ARA EL LABORATORIO DE PA TOLOGÍA DEL HOSPITAL ROS ALES. RECOVID-149-RFQ-GO / SUM INISTRO, INSTALACIÓN Y PUE Component 1: Emergency C STA EN MARCHA DEL SISTEM OVID-19 response to preven Request for Quota Single Stage - One E A DE AIRE ACONDICIONADO IBRD / 92290 Post Open - National 48,000.00 0.00 Canceled 2023-01-18 2023-05-18 2023-03-11 2023-07-09 tion, detection and treatmen tions nvelope Y VENTILACIÓN MECÁNICA, P t  ARA EL LABORATORIO DE PA TOLOGÍA DEL HOSPITAL ROS ALES. RECOVID-156-RFB-GO / Sum inistro, instalación y puesta e Component 1: Emergency C n marcha de Cabinas de bios OVID-19 response to preven Single Stage - One E Under Imple IBRD / 91000 Post Request for Bids Open - National 194,472.55 0.00 2023-01-27 2023-02-13 2023-02-01 2023-02-14 2023-03-03 2023-03-30 2023-03-23 2023-06-20 2023-04-20 2023-10-17 eguridad, Esterilizador y Sist tion, detection and treatmen nvelope mentation ema de ultrapurificación de a t  gua para Hospital Nacional El Salvador. Page 5 RECOVID-157-RFQ-GO / Insu Component 2. Project Manag Request for Quota Single Stage - One E Under Imple mos informáticos para funcio IBRD / 92290 Post Open - National 2,865.00 0.00 2023-01-03 2023-02-20 2023-03-07 ement and Monitoring tions nvelope mentation namiento de la UGP RECOVID-158-RFB-GO / Sum Component 1: Emergency C Single Stage - One E Under Imple inistro de Torre de Video colo IBRD / 91000 OVID-19 response to preven Post Request for Bids Open - National 141,350.00 0.00 2023-01-13 2023-02-13 2023-01-18 2023-02-13 2023-02-17 2023-03-20 2023-04-18 2023-07-17 nvelope mentation noscopia para el Hospital Na tion, detection and treatmen cional Rosales t  RECOVID-161-RFB-GO / Adq Component 1: Emergency C uisición de equipo informátic OVID-19 response to preven Single Stage - One E Pending Impl o para el fortalecimiento de l IBRD / 92290 Post Request for Bids Open - National 133,932.55 0.00 2023-02-15 2023-02-20 2023-03-22 2023-04-21 2023-05-23 2023-09-20 tion, detection and treatmen nvelope ementation a Dirección de Comunicación t  Social e Institucional RECOVID-162-RFQ-GO / Sum Component 1: Emergency C inistro, Instalación y Puesta e OVID-19 response to preven Request for Quota Single Stage - One E Pending Impl IBRD / 92290 Post Open - National 60,000.00 0.00 2023-02-20 2023-04-07 2023-08-05 n Funcionamiento de Baños tion, detection and treatmen tions nvelope ementation Ultrasónicas para HNES. t  RECOVID-163-RFB-GO / Adq Component 1: Emergency C uisición de montacargas para OVID-19 response to preven Single Stage - One E Under Imple IBRD / 92290 Post Request for Bids Open - National 120,250.00 0.00 2023-02-15 2023-03-24 2023-02-20 2023-03-22 2023-04-16 2023-05-21 2023-09-18 mejorar el almacenamiento e tion, detection and treatmen nvelope mentation n almacén el Paraiso del MIN t  SAL. RECOVID-139-RFB-GO / SUM Component 1: Emergency C INISTRO, INSTALACIÓN Y PUE OVID-19 response to preven Single Stage - One E STA EN MARCHA DE CUARTO IBRD / 92290 Post Request for Bids Open - National 139,265.00 0.00 Canceled 2022-10-28 2022-12-13 2022-11-02 2022-12-13 2022-11-25 2022-12-09 2022-12-29 2023-07-27 tion, detection and treatmen nvelope FRIO DE LA REGION PARACE t  NTRAL DE SALUD DEL MINIST ERIO DE SALUD RECOVID-167-RFB-GO / Sum Component 1: Emergency C Single Stage - One E Under Imple inistro, Instalación y Puesta e IBRD / 92290 OVID-19 response to preven Post Request for Bids Open - National 139,265.00 0.00 2023-02-28 2023-03-31 2023-03-05 2023-03-31 2023-04-04 2023-04-24 2023-05-23 2023-11-19 nvelope mentation n Marcha de Cuarto Frío RPS tion, detection and treatmen del MINSAL t  RECOVID-77-RFB-GO / Sumi Component 1: Emergency C nistro de Equipo e Instrumen OVID-19 response to preven Single Stage - One E IBRD / 92290 Post Request for Bids Open - National 170,000.00 0.00 Canceled 2022-08-31 2022-12-08 2022-09-14 2022-12-08 2022-10-15 2022-11-14 2022-12-06 2023-04-05 tal para Unidad de Oftalmolo tion, detection and treatmen nvelope gía de Hospital del Hospital N t  acional Zacamil RECOVID-165-RFQ-GO / Sum Component 1: Emergency C inistro de Equipo para Unidad OVID-19 response to preven Request for Quota Single Stage - One E Under Imple IBRD / 92290 Post Open - National 40,000.00 0.00 2023-03-08 2023-05-18 2023-04-23 2023-08-21 de Oftalmología de Hospital tion, detection and treatmen tions nvelope mentation del Hospital Nacional Zacami t  l RECOVID-166-RFQ-GO / Sum Component 1: Emergency C inistro de Instrumental para OVID-19 response to preven Request for Quota Single Stage - One E Pending Impl IBRD / 92290 Post Open - National 150,000.00 0.00 2023-03-08 2023-04-27 2023-08-25 Unidad de Oftalmología de H tion, detection and treatmen tions nvelope ementation ospital del Hospital Nacional t  Zacamil RECOVID-173-RFQ-GO / Adq Component 1: Emergency C uisición de Equipo Informátic OVID-19 response to preven Request for Quota Single Stage - One E Pending Impl IBRD / 92290 Post Open - National 34,595.68 0.00 2023-05-24 2023-07-15 2023-11-12 o para el fortalecimiento de tion, detection and treatmen tions nvelope ementation Unidad de Promoción Vida Sa t  na y Bienestar RECOVID-1-RFB-GO-BIS / Su Component 1: Emergency C ministro, instalación y puesta OVID-19 response to preven Open - Internationa Single Stage - One E en marcha de equipos de uni IBRD / 91000 Prior Request for Bids 8,349,609.18 0.00 Canceled 2021-08-23 2021-12-20 2022-03-15 2022-06-24 2022-10-24 2023-07-02 tion, detection and treatmen l nvelope dad de radiología e imágenes t  diagnósticas para el Hospital Nacional El Salvador. RECOVID-179-RFQ-GO / Adq Component 1: Emergency C uisición y suministro de equi OVID-19 response to preven Request for Quota Single Stage - One E Pending Impl IBRD / 92290 Post Open - National 32,000.00 0.00 2023-07-05 2023-08-30 2023-11-28 pos de aires acondicionados tion, detection and treatmen tions nvelope ementation en Establecimientos de Salud t  priorizados. RECOVID-181-RFQ-GO / Adq uisición de impresores matric Component 2. Project Manag Request for Quota Single Stage - One E Pending Impl iales, software y accesorios i IBRD / 92290 Post Open - National 34,250.00 0.00 2023-06-28 2023-08-28 2023-11-26 ement and Monitoring tions nvelope ementation nformáticos para el fortaleci miento de la UGGPI y la Paga duría Institucional RECOVID-182-RFB-GO / Sum Component 1: Emergency C inistro, Instalación y Puesta e OVID-19 response to preven Single Stage - One E Pending Impl n Marcha de Equipo generad IBRD / 92290 Post Request for Bids Open - National 275,000.00 0.00 2023-07-14 2023-07-19 2023-08-18 2023-09-18 2023-10-13 2024-02-10 tion, detection and treatmen nvelope ementation or de vapor, caldera 80 VHP t  y periféricos. Hospital Nacion al Zacamil. RECOVID-180-RFQ-GO / Adq Component 1: Emergency C uisición y suministro de piso OVID-19 response to preven Request for Quota Single Stage - One E Pending Impl IBRD / 92290 Post Open - National 70,000.00 0.00 2023-07-05 2023-08-21 2023-11-19 de vinil en áreas de imagenol tion, detection and treatmen tions nvelope ementation ogía de Hospitales Nacionale t  s priorizados. NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual RECOVID-13-RFQ-NC / Contr atación de servicios de agen Component 1: Emergency C cia de publicidad para produ OVID-19 response to preven Request for Quota Single Stage - One E IBRD / 91000 Post Open - National 500,000.00 400,000.00 Signed 2021-09-29 2022-01-10 2022-03-08 2022-07-09 cción y difusión de campañas tion, detection and treatmen tions nvelope de comunicación educativa, t  para el combate de la pande mia contra el COVID-19. RECOVID-16-RFQ-NC / Servic io de rotulación que visibilice Component 1: Emergency C las recomendaciones y medi OVID-19 response to preven Request for Quota Single Stage - One E Pending Impl IBRD / 91000 Post Open - National 35,000.00 0.00 2021-11-11 2022-01-21 2022-03-07 das contenidas en los lineami tion, detection and treatmen tions nvelope ementation entos técnicos para la protec t  ción del personal por la emer gencia del COVID-19 RECOVID-58-RFQ-NC / Servic io de arrendamiento de fotoc Component 2. Project Manag Request for Quota Single Stage - One E IBRD / 92290 Post Open - National 7,000.00 6,999.00 Signed 2022-03-23 2022-04-27 2022-05-15 2023-04-27 opiadora e impresiones para ement and Monitoring tions nvelope apoyar la Gestión de la UGPP I RECOVID-59-RFQ-NC / Servic Component 2. Project Manag Request for Quota Single Stage - One E ios de mantenimiento de equ IBRD / 92290 Post Open - National 15,000.00 4,320.00 Signed 2022-03-23 2022-04-27 2022-06-08 2023-04-27 ement and Monitoring tions nvelope ipos de aíres acondicionados Page 6 RECOVID-15-RFQ-NC / Contr Component 1: Emergency C atación de alimentación y loc OVID-19 response to preven Request for Quota Single Stage - One E al para el desarrollo de consu IBRD / 91000 Post Open - National 15,000.00 0.00 Canceled 2022-01-21 2022-03-30 2022-07-28 tion, detection and treatmen tions nvelope ltas de partes interesadas y t  poblaciones vulnerables RECOVID-DIR-105-NC / SERV Component 1: Emergency C ICIO DE CALL CENTER PARA L IBRD / 94290 OVID-19 response to preven Post Direct Selection Direct - National 418,530.00 418,530.00 Signed 2021-02-02 2021-02-11 2021-02-12 2021-02-12 2021-02-15 2021-02-16 2021-03-05 LAMADAS DE CONTENCIÓN D tion, detection and treatmen E LA PANDEMIA t  RECOVID-DIR-110-NC / SERV ICIO DE ALQUILER DE 40 CA Component 1: Emergency C MIONES FURGON PARA LA DI OVID-19 response to preven STRIBUCION DE SUMINISTRO IBRD / 94290 Post Direct Selection Direct - National 597,645.00 597,645.00 Signed 2021-03-11 2021-04-13 2021-04-16 2021-04-16 2021-05-17 2021-05-18 2021-12-31 tion, detection and treatmen S, TRASLADO DE MOBILIARIO t  Y EQUIPO A LOS DIFERENTES CENTROS DE VACUNACIÓN Y OTROS. RECOVID-DIR-113-NC / SERV Component 1: Emergency C ICIO DE ALIMENTACION A DO OVID-19 response to preven MICILIO EN ZONA METROPOLI IBRD / 94290 Post Direct Selection Direct - National 96,884.24 96,884.24 Signed 2021-04-08 2021-04-09 2021-04-09 2021-04-09 2021-05-21 2021-05-22 2021-08-21 tion, detection and treatmen TANA PARA EL PERSONAL EN t  LOS AUTOSERVICIOS DE VAC UNACION PARA COVID-19 RECOVID-DIR-116-NC / CON Component 1: Emergency C TRATACION DE SERVICIOS D OVID-19 response to preven E SANITIZACION DE UNIDADE IBRD / 94290 Post Direct Selection Direct - National 530,545.04 530,545.04 Signed 2021-04-07 2021-04-19 2021-04-19 2021-04-19 2021-04-30 2021-05-01 2021-12-31 tion, detection and treatmen S DE TRANSPORTE DERIVAD t  OS PARA LA EMERGENCIA PO R COVID-19 RECOVID-DIR-118-NC / SERV ICIO DE ALIMENTACIÓN PARA Component 1: Emergency C EL PERSONAL DE SALUD DE L OVID-19 response to preven IBRD / 94290 Post Direct Selection Direct - National 194,929.00 474,722.08 Signed 2021-04-12 2021-06-16 2021-07-16 2021-07-16 2021-07-27 2021-08-06 2021-10-27 OS AUTOCENTROS DE VACU tion, detection and treatmen NACION Y EL MEGACENTRO t  DE VACUNACION DEL HOSPIT AL EL SALVADOR RECOVID-DIR-124-NC / SERV ICIO DE ALIMENTACIÓN A DO Component 1: Emergency C MICILIO EN ZONA METROPOLI OVID-19 response to preven IBRD / 94290 Post Direct Selection Direct - National 148,918.60 148,918.60 Signed 2021-10-27 2021-11-11 2021-11-01 2021-10-11 2021-12-22 2021-12-23 2022-02-22 TANA, MEGACENTRO DE VAC tion, detection and treatmen UNACION Y CENTRO NACION t  AL DE VACUNACION (CENABI ) RECOVID-DIR-125-NC / SERV Component 1: Emergency C ICIO DE CALL CENTER PARA IBRD / 94290 OVID-19 response to preven Post Direct Selection Direct - National 4,100,000.00 4,100,000.00 Signed 2021-09-03 2021-09-07 2021-09-08 2021-09-08 2021-09-16 2021-09-17 2021-12-31 EL SEM tion, detection and treatmen t  RECOVID-DIR-126-NC / SERV Component 1: Emergency C ICIO DE CALL CENTER PARA OVID-19 response to preven SEGUIMIENTO DE CASOS SOS IBRD / 94290 Post Direct Selection Direct - National 1,064,361.32 1,064,361.22 Signed 2021-11-08 2021-11-10 2021-11-10 2021-11-10 2021-11-12 2021-11-29 2022-02-22 tion, detection and treatmen PECHOSOS Y CONFIRMADOS t  POR COVID-19 A NIVEL NACI ONAL RECOVID-DIR-108-NC / CON Component 1: Emergency C TRATACIÓN DE SERVICIO DE OVID-19 response to preven CALL CENTER DE ATENCIÓN IBRD / 94290 Post Direct Selection Direct - National 1,064,361.32 1,064,361.32 Completed 2021-03-04 2021-03-12 2021-03-22 2021-03-19 2021-03-22 2021-04-01 2021-07-21 2021-09-05 tion, detection and treatmen DE LLAMADAS EN EL MARCO t  DE LA CONTENCIÓN DE LA P ANDEMIA COVID-19 RECOVID-DIR-129-NC / SERV ICIO DE TRANSPORTE PARA Component 1: Emergency C LA DISTRIBUCION DE VACUN OVID-19 response to preven AS, EQUIPO DE VACUNACION IBRD / 94290 Post Direct Selection Direct - National 808,515.00 0.00 Completed 2021-01-05 2021-02-01 2021-02-03 2021-02-03 2021-02-11 2021-12-31 2021-11-07 tion, detection and treatmen , KITS MEDICOS, INSUMOS Y t  PERSONAS A LAS DIFRENTES CENTROS DE VACUNACION Y OTROS PUNTOS GEOGRAFIC OS. RECOVID-DIR-130-NC / SERV Component 1: Emergency C ICIO DE LIMPIEZA DE BIOPRO OVID-19 response to preven TECCIÒN EN LOS ESTABLECI IBRD / 94290 Post Direct Selection Direct - National 1,283,599.32 0.00 Signed 2021-01-03 2021-03-01 2021-03-08 2021-03-08 2021-06-15 2021-12-31 tion, detection and treatmen MIENTOS DE LA RED NACION t  AL DE HOSPITALES DEL MINS AL. RECOVID-DIR-131-NC / SERV ICIO DE TRANSPORTE PARA L Component 1: Emergency C A DISTRIBUCIÓN DE VACUNA OVID-19 response to preven S, EQUIPO DE VACUNACION, IBRD / 94290 Post Direct Selection Direct - National 2,997,144.00 0.00 Signed 2021-05-12 2021-05-17 2021-05-19 2021-05-19 2021-05-31 2021-10-01 tion, detection and treatmen KITS MEDICOS, INSUMOS Y P t  ERSONAS A LOS DIFERENTES CENTROS DE VACUNACION Y OTROS PUNTOS GEOGRAFIC OS. RECOVID-DIR-133-NC / SERV Component 1: Emergency C ICIO DE LIMPIEZA DE BIOPRO IBRD / 94290 OVID-19 response to preven Post Direct Selection Direct - National 778,000.00 0.00 Completed 2021-08-12 2021-08-19 2021-10-22 2021-10-22 2021-12-10 2021-12-31 2022-06-06 TECCION tion, detection and treatmen t  RECOVID-DIR-141-NC / LICE Component 1: Emergency C NCIA DE ALOJAMIENTO EN LA IBRD / 94290 OVID-19 response to preven Post Direct Selection Direct - National 196,892.30 0.00 Completed 2021-01-19 2021-02-02 2021-02-08 2021-02-02 2021-03-03 2022-03-03 2022-06-12 NUBE tion, detection and treatmen t  RECOVID-17-RFQ-NC / Repro Component 1: Emergency C ducción de material educativ OVID-19 response to preven Request for Quota Single Stage - One E o para promover el sistema d IBRD / 91000 Post Open - National 55,000.00 0.00 Canceled 2022-01-19 2022-03-31 2022-06-29 tion, detection and treatmen tions nvelope e quejas y derechos de los us t  uarios de los servicios RECOVID-150-RFQ-NC / Mont aje, Impresión y Reproducció n de Rotafolio Educativo sobr Component 2. Project Manag Request for Quota Single Stage - One E Under Imple IBRD / 92290 Post Open - National 55,000.00 0.00 2023-01-18 2023-03-11 2023-04-25 e la temática de Mecanismo ement and Monitoring tions nvelope mentation de Insatisfacciones, dirigido a la Población Usuaria de los S ervicios de Salud. RECOVID-168-RFQ-NC / Serv icio de arrendamiento de fot Component 2. Project Manag Request for Quota Single Stage - One E Under Imple IBRD / 92290 Post Open - National 10,000.00 0.00 2023-03-01 2023-04-18 2023-12-31 ocopiadora e impresiones pa ement and Monitoring tions nvelope mentation ra apoyar la Gestión de la UG PPI RECOVID-169-RFQ-NC / SER VICIOS DE ALIMENTACION Y USO DE INSTALACIONES EN ZONA METROPOLITANA DE S Component 2. Project Manag Request for Quota Single Stage - One E Under Imple AN SALVADOR, PARA JORNAD IBRD / 92290 Post Open - National 10,000.00 0.00 2023-04-03 2023-05-19 2023-09-30 ement and Monitoring tions nvelope mentation AS DE SOCIALIZACIÓN DE A VANCES Y FORTALECIMIENTO DE RECURSOS HUMANOS EN CUMPLIMIENTO AL MARCO D E GESTIÓN AMBIENTAL Y SO CIAL Page 7 RECOVID-176-RFQ-NC / CON TRATACIÓN DE AGENCIA DE VIAJES PARA EL SERVICIO DE EMISIÓN DE BOLETOS AÉREO S, TARJETAS DE SEGURO DE Component 2. Project Manag Request for Quota Single Stage - One E Pending Impl IBRD / 92290 Post Open - National 12,000.00 0.00 2023-05-29 2023-06-09 2023-06-30 ASISTENCIA AL VIAJERO CON ement and Monitoring tions nvelope ementation COBERTURA INTERNACIONAL , ALOJAMIENTO Y TRASLADO PARA PERSONAL DE LA UNID AD DE GESTIÓN DE PROGRA MAS Y PROYECTOS DE INVER SIÓN EN CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual RECOVID-18-QCBS-CS / Serv icios de consultoría para sup Component 1: Emergency C ervisión externa de conexos OVID-19 response to preven Quality And Cost- IBRD / 91000 Post Open - National 150,000.00 0.00 Canceled 2021-02-08 2021-03-01 2021-03-30 2021-04-27 2021-05-12 2021-05-26 2021-06-09 2022-01-10 relacionados a la adecuación tion, detection and treatmen Based Selection de la infraestructura para la i t  nstalación del equipo de res onancia magnética RECOVID-19-LCS-CS / Audito ría de estados financieros pa ra el periodo del 1 de enero a l 31 de diciembre 2021 del Pr Component 2. Project Manag Least Cost Selecti IBRD / 91000 Post Open - National 20,000.00 20,000.00 Signed 2022-01-13 2022-01-18 2022-01-13 2022-02-21 2022-01-28 2022-03-22 2022-02-02 2022-03-31 2022-02-07 2022-04-07 2022-02-15 2022-04-07 2022-02-28 2022-05-21 2022-05-31 oyecto de “Respuesta de Em ement and Monitoring on ergencia de El salvador ante el COVID-19” financiado por l os Contratos de Préstamo BI RF-9100-SV y BIRF-9229-SV RECOVID-93-CQS-CS / Contr atación de Auditoría de estad os financieros para el periodo del 1 de enero al 31 de dicie Component 2. Project Manag Consultant Qualifi Under Implement mbre 2022 del Proyecto de R IBRD / 92290 Post Open - National 40,000.00 0.00 2022-08-26 2022-10-04 2022-09-16 2022-10-31 2022-11-30 2023-01-04 2023-05-31 ement and Monitoring cation Selection ation espuesta de Emergencia de El salvador ante el COVID-19 ” financiado por los contratos de préstamo 9100-SV, 9229- SV y 9429-SV. RECOVID-20-LCS-CS / Audito Component 1: Emergency C Least Cost Selecti ria de los estados financieros IBRD / 91000 OVID-19 response to preven Post Open - National 23,000.00 0.00 Canceled 2022-10-10 2022-10-10 2022-11-09 2022-12-07 2022-12-21 2023-01-25 2023-02-22 2023-06-30 on correspondientes al año 202 tion, detection and treatmen 2 t  RECOVID-174-CQS-CS / Audi toría de estados financieros p ara el periodo del 1 de enero al 31 de diciembre 2023 del Component 2. Project Manag Consultant Qualifi Under Implement Proyecto de “Respuesta de E IBRD / 92290 Post Open - National 40,000.00 0.00 2023-05-18 2023-06-13 2023-06-08 2023-08-03 2023-09-04 2023-10-10 2024-05-04 ement and Monitoring cation Selection ation mergencia de El salvador ant e el COVID-19” financiado po r los Contratos de Préstamo BIRF-9100-SV, BIRF-9229-SV y BIRF 9429-SV INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual RECOVID-23-INDV-CS / Cons ultoría Individual de Especiali sta Social en Apoyo al cumpli Component 1: Emergency C miento del Marco de Gestión OVID-19 response to preven Individual Consult IBRD / 91000 Post Open 41,600.00 41,600.00 Terminated 2021-08-16 2021-07-27 2021-08-29 2021-09-09 2021-09-01 2021-09-22 2021-10-02 2021-10-11 2023-01-25 Social de los Proyectos ejecu tion, detection and treatmen ant Selection tados en la UGPPI con financi t  amiento BIRF, con énfasis en el Proyecto “Respuesta de El Salvador ante el COVID-19 RECOVID-24-INDV-CS / Cons ultoría Individual de Especiali sta Ambiental en Apoyo al cu Component 1: Emergency C mplimiento del Marco de Ges OVID-19 response to preven Individual Consult IBRD / 91000 Post Open 41,600.00 41,600.00 Signed 2021-08-09 2021-08-26 2021-08-22 2021-10-06 2021-08-25 2021-10-06 2021-09-25 2021-11-04 2023-01-18 tión Ambiental de los Proyect tion, detection and treatmen ant Selection os ejecutados en la UGPPI co t  n financiamiento BIRF, con é nfasis en el Proyecto “Respu esta de El Salvador ante el C OVID-19” RECOVID-29-IND-CS / Servici o de consultoría para la supe Component 1: Emergency C rvisión del proyecto “suminis OVID-19 response to preven Individual Consult Pending Impleme tro, instalación y puesta en f IBRD / 91000 Post Open 17,500.00 0.00 2021-08-31 2021-10-19 2021-11-09 2022-01-04 2022-07-31 tion, detection and treatmen ant Selection ntation uncionamiento de equipos de t  la sala de angiógrafo y quiróf ano general del Hospital Naci onal El Salvador”. RECOVID-30-IND-CS / Servici o de consultoría para la supe Component 1: Emergency C rvisión del proyecto “suminis OVID-19 response to preven Individual Consult Pending Impleme tro, instalación y puesta en f IBRD / 91000 Post Open 17,500.00 0.00 2021-08-31 2021-10-19 2021-11-09 2022-01-04 2022-07-31 tion, detection and treatmen ant Selection ntation uncionamiento de equipos pa t  ra la central de esterilización y equipos del Hospital Nacion al El Salvador”. RECOVID-31-IND-CS / Servici o de consultoría para la supe Component 1: Emergency C rvisión del proyecto “suminis OVID-19 response to preven Individual Consult Pending Impleme tro, instalación y puesta en IBRD / 91000 Post Open 24,000.00 0.00 2021-08-31 2021-10-19 2021-11-09 2022-01-04 2022-07-31 tion, detection and treatmen ant Selection ntation marcha de equipos de unida t  d de radiología e imágenes di agnósticas para el Hospital N acional El Salvador Component 1: Emergency C RECOVID-22-INDV-CS / Espe Individual Consult IBRD / 91000 OVID-19 response to preven Post Open 52,500.00 0.00 Canceled 2021-02-15 2021-02-28 2021-03-03 2021-04-03 2022-12-31 cialista financiero ant Selection tion, detection and treatmen t  RECOVID-21-INDV-CS / Cons Component 1: Emergency C ultor(a) para adquisiciones y OVID-19 response to preven Individual Consult contrataciones del proyecto IBRD / 91000 Prior Open 33,600.00 33,600.00 Signed 2021-08-28 2021-09-07 2021-09-14 2021-09-13 2021-09-17 2021-11-30 2021-10-05 2021-10-11 2022-10-05 tion, detection and treatmen ant Selection de respuesta de El Salvador t  ante el COVID-19, y otros con financiamiento BIRF Page 8 RECOVID -46-INDV-CS / Serv icios de consultoría especiali Component 2. Project Manag Individual Consult Pending Impleme zada de ingeniería mecánica IBRD / 92290 Post Open 33,600.00 0.00 2022-01-07 2022-01-31 2022-02-04 2022-02-15 2023-02-15 ement and Monitoring ant Selection ntation en apoyo a la ejecución de lo s proyectos de infraestructur a RECOVID -47-INDV-CS / Serv icios de consultoría especiali Component 2. Project Manag Individual Consult Pending Impleme zada de ingeniería eléctrica e IBRD / 92290 Post Open 33,600.00 0.00 2022-01-07 2022-01-31 2022-02-04 2022-02-15 2023-02-15 ement and Monitoring ant Selection ntation n apoyo a la ejecución de los proyectos de infraestructura RECOVID -48-INDV-CS / Serv icios de consultoría especiali Component 2. Project Manag Individual Consult Pending Impleme zada de ingeniería hidrosanit IBRD / 92290 Post Open 33,600.00 0.00 2022-01-07 2022-01-31 2022-02-04 2022-02-15 2023-02-15 ement and Monitoring ant Selection ntation aria en apoyo a la ejecución de los proyectos de infraestr uctura RECOVID-42-CDS-CS / Consu ltoría en arquitectura y activi dades de dibujo técnico de in Component 2. Project Manag Individual Consult IBRD / 92290 Post Direct 27,600.00 27,600.00 Signed 2021-12-17 2022-01-03 2022-01-03 2022-01-07 2022-01-06 2022-01-18 2022-01-14 2022-02-07 2023-01-14 fraestructura financiados con ement and Monitoring ant Selection Unidad de Gestión de Progra mas y Proyectos De Inversión – UGPPI RECOVID-45-CDS-CS / Consu ltoría en arquitectura y activi dades de dibujo técnico de in Component 2. Project Manag Individual Consult IBRD / 92290 Post Direct 27,600.00 27,600.00 Signed 2021-12-17 2022-01-03 2022-01-03 2022-01-07 2022-01-06 2022-01-18 2022-01-14 2022-02-07 2023-01-14 fraestructura financiados con ement and Monitoring ant Selection Unidad de Gestión de Progra mas y Proyectos De Inversión – UGPPI RECOVID-43-CDS-CS / Consu ltoría en arquitectura y activi dades de dibujo técnico de in Component 2. Project Manag Individual Consult IBRD / 92290 Post Direct 27,600.00 27,600.00 Signed 2021-12-17 2022-01-03 2022-01-03 2022-01-07 2022-01-06 2022-01-18 2022-01-14 2022-02-07 2023-01-14 fraestructura financiados con ement and Monitoring ant Selection Unidad de Gestión de Progra mas y Proyectos De Inversión – UGPPI RECOVID-44-CDS-CS / Consu ltoría en arquitectura y activi dades de dibujo técnico de in Component 2. Project Manag Individual Consult IBRD / 92290 Post Direct 27,600.00 27,600.00 Signed 2021-12-17 2022-01-03 2022-01-03 2022-01-07 2022-01-06 2022-01-18 2022-01-14 2022-02-07 2023-01-14 fraestructura financiados con ement and Monitoring ant Selection Unidad de Gestión de Progra mas y Proyectos De Inversión – UGPPI RECOVID-50-INDV-CS / Cons ultoría individual para especi alista de adquisiciones y cont Component 2. Project Manag Individual Consult IBRD / 92290 Prior Open 39,200.00 33,600.00 Signed 2022-01-10 2022-03-10 2022-01-20 2022-04-21 2022-01-27 2022-04-25 2022-02-01 2022-05-07 2023-03-31 rataciones del proyecto de re ement and Monitoring ant Selection spuesta de El Salvador ante el COVID-19, y otros con fina nciamiento BIRF RECOVID-51-INDV-CS / Contr atación de consultores para f ormulación de carpetas técni Component 2. Project Manag Individual Consult IBRD / 92290 Post Open 120,000.00 0.00 Signed 2022-02-07 2022-06-13 2022-03-05 2022-09-01 2022-03-18 2022-09-02 2022-04-08 2022-07-07 cas para el mejoramiento del ement and Monitoring ant Selection sistema eléctrico de los hospi tales nacionales priorizados RECOVID-52-INDV-CS / Servi cios de consultoría par avalú Component 2. Project Manag Individual Consult os técnicos de los bienes inm IBRD / 92290 Post Open 100,000.00 75,000.00 Signed 2022-02-14 2022-03-17 2022-03-14 2022-06-07 2022-03-21 2022-06-07 2022-04-12 2022-06-24 2022-06-11 ement and Monitoring ant Selection uebles propiedad del Minister io de Salud en hospitales na cionales priorizados. RECOVID-60-RFQ-CS / Servic Component 2. Project Manag Individual Consult ios de consultoría de especial IBRD / 92290 Prior Open 36,000.00 0.00 Canceled 2022-03-21 2022-03-28 2022-04-18 2022-05-23 2023-05-23 ement and Monitoring ant Selection ista en adquisiciones para ap oyar la UGPPI RECOVID-60-IND-CS / Servici Component 2. Project Manag Individual Consult os de consultoría de especiali IBRD / 92290 Prior Open 36,000.00 33,600.00 Signed 2022-04-04 2022-05-24 2022-04-18 2022-06-13 2022-05-02 2022-06-30 2022-05-13 2022-07-14 2022-12-31 ement and Monitoring ant Selection sta en adquisiciones para ap oyar la UGPPI RECOVID-70-INDV-CS / Servi cios de consultoría para aval Component 2. Project Manag Individual Consult úos técnicos de los bienes in IBRD / 92290 Post Open 100,000.00 0.00 Signed 2022-04-28 2022-06-27 2022-05-30 2022-10-24 2022-06-09 2022-10-25 2022-07-06 2022-11-03 ement and Monitoring ant Selection muebles propiedad del Minist erio de Salud en Hospitales N acionales Priorizados RECOVID-94-CDS-CS / CONS ULTORÍA INDIVIDUAL PARA E SPECIALISTA EN ADQUISICIO Component 2. Project Manag NES Y CONTRATACIONES DEL IBRD / 92290 Post Direct Selection Direct - National 42,000.00 0.00 Signed 2022-09-09 2022-09-12 2022-09-18 2022-09-28 2022-09-30 2023-12-31 ement and Monitoring PROYECTO DE RESPUESTA D E EL SALVADOR ANTE EL CO VID-19, Y OTROS CON FINACI AMIENTO BIRF RECOVID-98-INDV-CS / Cons ultoría Individual de Especiali sta Social en Apoyo al Cumpli miento del Marco de Gestión Component 2. Project Manag Individual Consult Under Implement IBRD / 92290 Post Open - National 39,000.00 0.00 2022-09-16 2022-11-14 2022-09-30 2023-01-09 2022-10-10 2023-01-12 2022-10-24 2023-12-31 Social de los proyectos ejecu ement and Monitoring ant Selection ation tados en la UGPPI con financi amiento BIRF, con énfasis en el Proyecto "Respuesta de El Salvador ante el COVID-19" RECOVID-136-INDV-CS / CO NSULTORÍA INDIVIDUAL PAR A ESPECIALISTA EN ADQUISIC Component 2. Project Manag Individual Consult IONES Y CONTRATACIONES D IBRD / 92290 Prior Open - National 39,200.00 0.00 Canceled 2022-10-14 2022-10-29 2022-11-03 2022-11-17 2023-12-31 ement and Monitoring ant Selection EL PROYECTO DE RESPUESTA DE EL SALVADOR ANTE EL C OVID-19, Y OTROS CON FINA CIAMIENTO BIRF RECOVID-137-INDV-CS / SER VICIO DE CONSULTORÍA PAR Component 2. Project Manag Individual Consult A APOYO JURÍDICO EN UNIDA IBRD / 92290 Prior Open - National 39,200.00 0.00 Canceled 2022-10-14 2022-10-25 2022-10-27 2022-11-03 2022-11-17 2023-12-31 ement and Monitoring ant Selection D DE ADQUISICIONES Y CON TRATACIONES DE LA UGPPI Page 9 RECOVID-144-CDS-CS / CON SULTORÍA INDIVIDUAL PARA ESPECIALISTA EN ADQUISICI Component 2. Project Manag ONES Y CONTRATACIONES D IBRD / 92290 Prior Direct Selection Direct - National 39,200.00 0.00 Signed 2022-10-18 2022-10-21 2022-10-26 2022-11-03 2022-11-10 2023-12-31 ement and Monitoring EL PROYECTO DE RESPUESTA DE EL SALVADOR ANTE EL C OVID-19, Y OTROS CON FINA CIAMIENTO BIRF RECOVID-152-CDS-CS / SER VICIOS DE CONSULTORIA EN ARQUITECTURA Y ACTIVIDAD Component 2. Project Manag ES DE DIBUJO TECNICO DE IN IBRD / 92290 Post Direct Selection Direct - National 25,300.00 0.00 Signed 2022-12-23 2023-01-20 2023-01-09 2023-01-20 2023-01-25 2023-12-31 ement and Monitoring FRAESTRUCTURA FINANCIAD OS CON UNIDAD DE GESTION DE PROGRAMAS Y PROYECTO S DE INVERSION - UGPPI RECOVID-153-CDS-CS / SER VICIOS DE CONSULTORIA EN ARQUITECTURA Y ACTIVIDAD Component 2. Project Manag Under Implement ES DE DIBUJO TECNICO DE IN IBRD / 92290 Post Direct Selection Direct - National 25,300.00 0.00 2022-12-23 2023-01-10 2023-01-09 2023-01-20 2023-01-25 2023-12-31 ement and Monitoring ation FRAESTRUCTURA FINANCIAD OS CON UNIDAD DE GESTION DE PROGRAMAS Y PROYECTO S DE INVERSION - UGPPI RECOVID-154-CDS-CS / SER VICIOS DE CONSULTORIA EN ARQUITECTURA Y ACTIVIDAD Component 2. Project Manag Under Implement ES DE DIBUJO TECNICO DE IN IBRD / 92290 Post Direct Selection Direct - National 25,300.00 0.00 2022-12-23 2023-01-10 2023-01-09 2023-01-20 2023-01-25 2023-12-31 ement and Monitoring ation FRAESTRUCTURA FINANCIAD OS CON UNIDAD DE GESTION DE PROGRAMAS Y PROYECTO S DE INVERSION - UGPPI RECOVID-155-CDS-CS / SER VICIOS DE CONSULTORIA EN ARQUITECTURA Y ACTIVIDAD Component 2. Project Manag ES DE DIBUJO TECNICO DE IN IBRD / 92290 Post Direct Selection Direct - National 25,300.00 0.00 Signed 2022-12-23 2023-01-10 2023-01-09 2023-01-23 2023-01-25 2023-12-31 ement and Monitoring FRAESTRUCTURA FINANCIAD OS CON UNIDAD DE GESTION DE PROGRAMAS Y PROYECTO S DE INVERSION - UGPPI RECOVID-160-CDS-CS / Cons ultoría Individual de Especiali sta Ambiental en Apoyo al cu mplimiento del Marco de Ges Component 2. Project Manag IBRD / 92290 Post Direct Selection Direct - National 26,588.00 0.00 Signed 2023-01-31 2023-02-10 2023-02-10 2023-02-24 2023-02-25 2023-12-31 tión Ambiental de los Proyect ement and Monitoring os ejecutados en la UGPPI co n financiamiento BIRF, con é nfasis en el Proyecto “Respu esta de El Salvador ante el C OVID-19. RECOVID-164-INDV-CS / Ser vicios de Consultoría para Ap Component 2. Project Manag Individual Consult IBRD / 92290 Prior Open - National 28,000.00 0.00 Signed 2023-02-08 2023-02-07 2023-02-20 2023-02-21 2023-02-24 2023-02-23 2023-03-01 2023-12-31 oyo Jurídico en Unidad de Ad ement and Monitoring ant Selection quisiciones y Contartaciones de la UGPPI RECOVID-170-INDV-CS / Con tratación de servicios de con Component 2. Project Manag Individual Consult Pending Impleme sultoría individual para el fort IBRD / 92290 Post Open - National 45,000.00 0.00 2023-03-31 2023-05-04 2023-05-19 2023-06-13 2023-09-11 ement and Monitoring ant Selection ntation alecimiento de la Dirección d e Tecnologías de la Informaci ón y Comunicación RECOVID-171-CDS-CS / Cons ultoría Individual para Especi alista en Adquisiciones y Con Component 2. Project Manag IBRD / 92290 Prior Direct Selection Direct - National 22,774.00 0.00 Signed 2023-03-24 2023-04-13 2023-04-03 2023-04-17 2023-04-27 2023-12-31 tratación del Proyecto de Res ement and Monitoring puesta de El Salvador ante el COVID-19 y otros con financi amiento BIRF RECOVID-172-CDS-CS / Cons ultoría Individual para Especi alista en Adquisiciones y Con Component 2. Project Manag Under Implement IBRD / 92290 Prior Direct Selection Direct - National 16,530.00 0.00 2023-04-14 2023-04-13 2023-05-03 2023-05-15 2023-07-04 2023-12-31 tratación del Proyecto de Res ement and Monitoring ation puesta de El Salvador ante el COVID-19 y otros con financi amiento BIRF RECOVID-184-INDV-CS / Con tratación de Asistente Admini Component 2. Project Manag Individual Consult Pending Impleme IBRD / 92290 Post Open - National 5,000.00 0.00 2023-06-30 2023-07-25 2023-08-07 2023-08-18 2023-12-31 strativo para la coordinación ement and Monitoring ant Selection ntation del Área de Infraestructura y Equipo Page 10 PLAN DE PASSATION DE MARCHÉS Information sur le Projet : Emprunteur/Bénéficiaire République Togolaise Ministère Responsable Nom du Projet Identification P172769 Agence d’exécution du Projet : [A insérer] Date du plan de passation des marchés : [A indiquer] Période couverte par ce plan de passation des marchés : [A indiquer] Date d’approbation par la Banque du plan de passation de marchés : [A indiquer] Date de publication de l’Avis Général de Passation des Marchés : [A indiquer] Evaluation de risque par P-RAMS (Procurement Risk Assessment and Management System) : Elevé Préambule Conformément au paragraphe 5.9 du “Règlement de Passation des Marchés pour les Emprunteurs sollicitant le Financement de Projets d’Investissement (FPI)” (Novembre 2020) (“Règlement de Passation des Marchés”), le Système électronique de la Banque de suivi systématique des transactions de marchés publics (STEP) sera utilisé pour préparer, valider et actualiser les plans de passation des marchés et effectuer toutes les transactions liées à la passation des marchés du projet. Ce texte ainsi que les tableaux du plan de passation des marchés présents dans STEP constituent le plan de passation des marchés du projet. Les conditions suivantes s'appliquent à toutes les activités de passation de marchés du plan de passation de marchés. Les autres éléments du plan de passation des marchés tels que requis au paragraphe 4.4 du Règlement de passation des marchés sont énoncés dans STEP. Les Dossiers types de passation des marchés publics de la Banque devront être utilisés pour tous les contrats soumis à la concurrence internationale, ainsi que pour tous les autres contrats soumis à cette obligation telle que spécifiée dans les tableaux du plan de passation des marchés de STEP. Procédures nationales de passation des marchés : En accord avec le paragraphe 5.3 du Règlement de passation des marchés, dans le cas où la procédure de passation des marchés se fera au niveau national (telle que spécifiée dans les tableaux du plan de passation des marchés inclus dans STEP), les procédures nationales de passation des marchés du pays considéré pourront être utilisées. Si l’Emprunteur utilise ses propres procédures d’appel d’offres national ouvert telles qu’énoncées dans la loi No. 2009-013 du 30 juin 2009 relative aux Marchés Publics et Délégation de Service Public, le Décret Nº 2009-277/PR du 11 novembre 2009 portant Code des Marchés Publics et Délégation de Service Public, et les textes d’application y afférents, ces arrangements sont soumis aux dispositions du paragraphe 5.4 du Règlement de passation des marchés et aux conditions suivantes : - Le dossier d’appel d’offres/à propositions oblige le Soumissionnaire/les proposants présentant une Offre/Proposition à déposer un agrément signé, qui sera joint à tout contrat éventuel, pour confirmer qu’il applique et respecte les Directives de la Banque pour la lutte contre la corruption, y compris sans limitation, le droit de la Banque de sanctionner et les droits de la Banque pour l’inspection e l’audit ; - Le droit de la Banque d’examiner le dossier et les activités de passation des marchés. Lorsque l’Emprunteur utilise d’autres procédures que l’appel d’offres national ouvert, ces procédures devront être en accord avec les dispositions du paragraphe 5.5 du Règlement de passation des marchés. Crédit-bail tel que spécifié au paragraphe 5.10 du Règlement de Passation des marchés : Le crédit-bail peut être utilisé pour les contrats indiqués comme tel dans le Plan de passation des marchés. « Sans objet » Achat de biens d’occasion tel que spécifié au paragraphe 5.11 du Règlement de Passation des Marchés est autorisé pour les contrats indiqués comme tel dans le Plan de passation des marchés. « Sans objet » Préférence nationale telle que spécifiée au paragraphe 5.51 du Règlement de Passation des Marchés (Fournitures et Travaux). Fournitures : ne s’applique pas pour les contrats indiqués dans les tableaux du Plan de passation des marchés Travaux ne s’applique pas pour les contrats indiqués dans les tableaux du Plan de passation des marchés L’Assistance directe à la mise en œuvre (sigle HEIS en anglais) tel que précisée aux paragraphes 3.10 et 3.11 du Règlement de Passation des marchés ne s’applique pas. Autres informations pertinentes sur la passation des marchés : Néant I. TRAVAUX, FOURNITURES ET SERVICES AUTRES QUE LES SERVICES DE CONSULTANTS 1. Dispositions relatives aux seuils de revue préalable : Seuils requis pour les décisions de marchés soumis à la revue préalable de la Banque, tel que prévu dans les paragraphes 3.5 à 3.8 de la Section III, et de l’Annexe II du Règlement de Passation des Marchés pour les Emprunteurs sollicitant le Financement de Projets d’Investissement (FPI), en date de Juillet 2016, révisé en Novembre 2017. Catégories de marchés Montants Observations estimatifs des contrats en millions de dollars américains Travaux (incluant clé à main, Fourniture et Installation, et les >= 5 Partenariat Public - Privé -PPP) Biens, Système d’Information et de Services autres que les >= 1,5 Services intellectuels Contrats à Travaux passer par (incluant clé à >= 5 entente main, directe Fourniture et Les justifications de Installation, et l’entente directe les Partenariat devront être jointes et Public - Privé - approuvées avec PPM PPP) Biens, Système d’Information et de Services >= 1,5 autres que les Services intellectuels 2. Seuils pour les méthodes de passation des marchés : Les seuils de passation des marchés se présentent comme suit au vu des conditions du marché : FOURNITURES ET SERVICES AUTRE QUE LES SERVICES DE CONSULTANTS TRAVAUX (US$ équivalent) (US$ équivalent) AOI AON DC AOI AON DC < < 100.000 ≥5.000.000 <5.000.000 200.00 ≥500.000 <500.000 0 3. Dispositions spéciales sur les marchés : Concernant les acquisitions de véhicules et de carburant, en fonction des circonstances et des besoins spécifiques du pays, le seuil pour la consultation de fournisseurs pourrait être porté à la contre-valeur d’USD 500,000 (en prenant soin de consulter tous les principaux concessionnaires de marque ou distributeurs de produits pétroliers). Liste de Marchés de Travaux, Fournitures, et Services autres que Consultant Date Type Méthode/ Montan de Comme d'Exa Modalité Appro t lance ntaire Réf. DESCRIP men de che de Estimat ment /Fin de No. TION par la passatio march if en de la prestat Banqu n des és US$ procé ions e marchés dure II. SÉLECTION DES CONSULTANTS 1. Dispositions relatives aux seuils de revue préalable des marchés : Décisions de sélection sujette à la revue préalable de la Banque comme indiqué dans Seuils requis pour les décisions de marchés soumis à la revue préalable de la Banque, tel que prévu dans les paragraphes 3.5 à 3.8 de la Section III, et de l’Annexe II du Règlement de Passation des Marchés pour les Emprunteurs sollicitant le Financement de Projets d’Investissement (FPI), en date de Novembre 2020. Méthode de Seuils de revue a priori Observations sélection/Catégories de Montants estimatifs des marchés contrats en millions de dollars américains Méthode compétitive/Firmes de >= 0.5 consultants Entente directe/firmes de Les justifications pour consultants >= 0.5 l’entente directe devront être jointes et approuvées Entente avec le PPM directe/Consultants >= 0.2 individuel Méthode Compétitive >= 0.2 (Comparaison de CVs)/ Consultants individuels 2. Liste restreinte composée entièrement de firmes nationales: La liste restreinte de consultants pour les prestations d’études d’ingénierie, de contrôle et de surveillance estimées à moins de 300,000 US$ par contrat, et pour tout autre type de prestations, estimées à moins de 100 000 US$ par contrat, peut comporter entièrement de consultants nationaux en conformité avec les dispositions des Règlements de Passation des marchés., et l’Emprunteur ne procède pas à une publication dans UNDB 3. Autre arrangement spécial de Sélection de consultants : Le seuil pour l’utilisation de la méthode de sélection de consultant fondée sur les qualifications des consultants est déterminé au cas par cas en tenant compte de la nature et de la complexité de la mission ; cependant, ce seuil ne devrait pas dépasser la contre-valeur de USD 300,000 sauf dans des cas exceptionnels telles des situations d’urgence en conformité au Règlement de Passation des marchés II- Liste de Marchés de Services de Consultants Date Méthod Comm Montan Type de Ré e de entair t d'Exam Approch lancem f. DESCRIPTION passati e/Fin Estimat en par e de ent de No DES MISSIONS on des des if en la Marché la . marché presta US$ Banque procéd s tions ure Lexique des Sigles et Abréviations ARMP Autorité de Régulation des Marchés Publics AOI Appel d’Offres International AON Appel d’Offres National A Revue a posteriori posteriori A Priori Revue a priori CI Consultant Individuel DC Demande de Cotations DNCMP Direction Nationale de Contrôle des Marchés Publics ED Sélection Directe ou Entente Directe PPM Plan de Passation des Marchés SFQ Sélection Fondée sur la Qualité SFQC Sélection Fondée sur la Qualité et le Coût SMC Sélection au Moindre Coût SQC Sélection fondée sur les Qualifications des Consultants PROCUREMENT Western and Central Africa : West Africa Food System Resilience Program (FSRP) PLAN General Information Country: Western and Central Africa 2022-08-09 Bank’s Approval Date of the Original Procurement Plan: 2023-06-01 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P172769 GPN Date: Project Name: West Africa Food System Resilience Program (FSRP) Loan / Credit No: IDA / 69980, IDA / D9250 FOOD SYSTEM RESILIENCE PROGRAM - NIGER Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned National Procure NE-FRSP-NE-306233-CW-RF ment Document - Request for Quota Single Stage - One E 2023-01-3 Q / Travaux d'extension du si IDA / 69980 Project Management Post Limited 1 Envelope proce 121,951.00 0.00 Signed 2022-08-20 2022-09-22 2022-09-12 tions nvelope 0 ège de l’UGP PARIIS pour le c ss (Non Bank-SPD ompte du FSRP ) GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NE-FRSP-NE-306159-GO-RFB Sustainability and adaptive c / Acquisition pour doter le CR Single Stage - One E IDA / 69980 apacity of the food system’s Post Request for Bids Open - National 313,589.00 0.00 Signed 2022-09-05 2022-12-12 2022-09-10 2022-12-13 2022-10-10 2023-01-16 2022-10-25 2023-01-27 2022-11-29 2023-03-29 S et les labos en équipement nvelope productive base s complémentaires clés NE-FRSP-NE-306190-GO-RFB Sustainability and adaptive c Single Stage - One E / Acquisition de semences (A IDA / 69980 apacity of the food system’s Post Request for Bids Open - National 143,728.00 0.00 Completed 2022-08-31 2022-10-07 2022-09-05 2022-10-10 2022-10-05 2022-11-02 2022-10-15 2022-11-23 2022-11-15 2022-12-30 2023-01-21 nvelope ppui en intrants agricoles) productive base NE-FRSP-NE-306228-GO-RFQ Request for Quota Single Stage - One E IDA / 69980 Project Management Post Limited 52,265.00 0.00 Completed 2022-10-25 2023-03-30 2022-11-21 2022-12-31 2023-04-16 / Acquisition de mobilier de b tions nvelope ureau NE-FRSP-NE-306961-GO-RFQ Request for Quota Single Stage - One E / Acquisition de matériel infor IDA / 69980 Project Management Post Limited 52,265.00 38,580.81 Completed 2022-08-15 2022-08-22 2022-08-31 2022-09-09 2022-10-15 2022-09-26 tions nvelope matique pour l'équipe FSRP NE-FRSP-NE-342474-GO-RFQ / Acquisition d'équipements c Digital advisory services for Request for Quota Single Stage - One E Pending Impl omplémentaires et mise en IDA / D9250 agriculture and food crisis pr Post Limited 52,632.00 0.00 2023-06-06 2023-06-14 2023-07-14 tions nvelope ementation marche de la station de réce evention and management ption des données satellitale s de la DGPIA et DGGR NE-FRSP-NE-342493-GO-RFQ Digital advisory services for / Equipement des structures, Request for Quota Single Stage - One E Pending Impl IDA / D9250 agriculture and food crisis pr Post Limited 17,545.00 0.00 2023-06-05 2023-06-13 2023-07-13 renforcement de la cellule gé tions nvelope ementation evention and management omatique par acquisition des drones. NE-FRSP-NE-342526-GO-RFQ / Acquisitions de Kits de com Digital advisory services for Request for Quota Single Stage - One E Pending Impl munication, d'information de IDA / D9250 agriculture and food crisis pr Post Limited 13,000.00 0.00 2023-04-05 2023-04-13 2023-04-30 tions nvelope ementation s impacts potentiels aux agro evention and management pasteurs et décideurs NE-FRSP-NE-342538-GO-RFQ Regional food market integr Request for Quota Single Stage - One E Pending Impl / Equipement des laboratoire IDA / D9250 Post Limited 43,333.00 0.00 2023-03-20 2023-03-28 2023-05-02 ation and trade tions nvelope ementation s (LABOCEL, DGPV, LANA, LT A et LNCCS) NE-FRSP-NE-342565-GO-RFQ Regional food market integr Request for Quota Single Stage - One E Pending Impl / Acquisition de matériel de c IDA / D9250 Post Limited 26,315.00 0.00 2023-04-15 2023-04-25 2023-05-10 ation and trade tions nvelope ementation ollecte des données NE-FRSP-NE-342578-GO-RFB Sustainability and adaptive c Single Stage - One E Under Imple / Appui en intrants des cultur IDA / D9250 apacity of the food system’s Post Request for Bids Open - National 221,053.00 0.00 2023-03-15 2023-03-24 2023-03-20 2023-03-31 2023-04-20 2023-04-27 2023-04-28 2023-05-27 2023-05-22 2023-06-26 nvelope mentation es pluviales (semences et en productive base grais) NE-FRSP-NE-342588-GO-RFB Single Stage - One E Under Imple IDA / D9250 Project Management Post Request for Bids Open - National 390,351.00 0.00 2023-03-15 2023-03-23 2023-03-20 2023-03-23 2023-04-19 2023-04-27 2023-04-28 2023-05-15 2023-05-25 2023-07-29 / Acquisition de matériel roul nvelope mentation ant NE-FRSP-NE-342590-GO-RFQ Request for Quota Single Stage - One E / Acquisition de Motos au pro IDA / D9250 Project Management Post Limited 13,160.00 0.00 Completed 2023-03-13 2023-03-01 2023-03-21 2023-03-31 2023-04-05 tions nvelope fit de l'UCP et les Régions NE-FRSP-NE-342591-GO-RFQ Request for Quota Single Stage - One E / Acquisition de Matériels info IDA / D9250 Project Management Post Limited 26,315.00 0.00 Completed 2023-03-03 2023-03-06 2023-03-10 2023-03-31 2023-04-05 tions nvelope rmatiques au profit de l'UCP NE-FRSP-NE-342499-GO-RFQ Digital advisory services for Request for Quota Single Stage - One E Pending Impl / Achats d'équipements infor IDA / D9250 agriculture and food crisis pr Post Limited 35,088.00 0.00 2023-05-07 2023-05-16 2023-05-31 tions nvelope ementation matiques (Ordinateurs et Tél evention and management éphones) NE-FRSP-NE-306204-GO-RFB / Acquisition de Matériels info Regional food market integr Single Stage - One E Pending Impl IDA / D9250 Post Request for Bids Open - National 122,807.00 0.00 2023-06-12 2023-06-17 2023-07-17 2023-07-27 2023-08-26 2023-10-10 rmatiques pour les structures ation and trade nvelope ementation et partenaires du FSRP NE-FRSP-NE-361809-GO-RFQ Sustainability and adaptive c / Acquisition de semences en Request for Quota Single Stage - One E IDA / D9250 apacity of the food system’s Post Limited 87,000.00 0.00 Completed 2023-05-29 2023-06-01 2023-06-09 2023-06-24 complément de quantités po tions nvelope productive base ur la campagne hivernale 20 23 NE-FRSP-NE-364001-GO-RFB / Fourniture et installation d' Regional food market integr Single Stage - One E Pending Impl un générateur d'azote liquid IDA / D9250 Post Request for Bids Open - National 280,700.00 0.00 2023-06-15 2023-06-22 2023-07-21 2023-07-31 2023-08-31 2023-11-30 ation and trade nvelope ementation e en appui aux unités de con servations de semences ani males NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Page 1 Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NE-FRSP-NE-306238-NC-DIR / Fourniture et installation du IDA / 69980 Project Management Post Direct Selection Direct - National 17,422.00 0.00 Signed 2022-08-30 2022-09-09 2022-09-04 2022-10-07 2022-09-23 2023-09-23 logiciel informatique et comp table TOM2PRO CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NE-FRSP-NE-306060-CS-CQS / Recrutement consultant po Digital advisory services for Consultant Qualifi Pending Impleme ur l'évaluation des capacités IDA / 69980 agriculture and food crisis pr Post Open - National 43,554.00 0.00 2022-08-30 2022-09-20 2022-11-03 2022-12-03 2022-12-30 2023-02-28 cation Selection ntation techniques et les besoins en evention and management formation pour soutenir le PD O du FSRP NE-FRSP-NE-306174-CS-CQS Sustainability and adaptive c Consultant Qualifi / Recrutement des ONGs pou IDA / 69980 apacity of the food system’s Post Open - National 300,000.00 0.00 Signed 2022-08-20 2022-10-10 2022-09-10 2022-10-24 2022-10-24 2022-12-14 2022-11-23 2023-02-20 2022-12-28 2023-12-28 cation Selection r l'Elaboration d'un Plan GIP productive base NE-FRSP-NE-306184-CS-CQS Sustainability and adaptive c / Recrutement consultant po Consultant Qualifi Pending Impleme IDA / 69980 apacity of the food system’s Post Open - National 69,686.00 0.00 2022-08-25 2022-09-15 2022-10-25 2022-11-24 2022-12-16 2023-02-14 ur l’Élaboration des schémas cation Selection ntation productive base d’aménagements de bassin v ersant NE-FRSP-NE-306187-CS-CQS Consultant Qualifi Under Implement / Recrutement Consultant po IDA / 69980 Project Management Post Open - National 36,794.00 0.00 2022-09-05 2022-12-08 2022-09-20 2023-01-26 2022-10-11 2023-05-05 2022-10-26 2022-11-01 2022-12-16 cation Selection ation ur l’Etude de référence NE-FRSP-NE-306235-CS-QCB Quality And Cost- S / Recrutement d’un Consult IDA / 69980 Project Management Post Open - National 8,711.00 0.00 Signed 2022-08-30 2022-09-05 2022-09-20 2022-10-13 2022-10-31 2022-12-22 2022-11-30 2023-01-20 2022-12-09 2023-02-28 2022-12-21 2023-02-28 2023-01-25 2024-01-25 Based Selection ant pour l’Audit annuel du pr ojet NE-FRSP-NE-342601-CS-CQS / Recrutement d'un consultan Sustainability and adaptive c Consultant Qualifi Open - Internationa Pending Impleme t pour les études de faisabilit IDA / D9250 apacity of the food system’s Post 263,160.00 0.00 2023-04-10 2023-04-20 2023-05-30 2023-07-05 2023-07-27 2024-01-23 cation Selection l ntation é technique de l'aménageme productive base nt des petits périmètres irrig ués NE-FRSP-NE-342663-CS-QCB Sustainability and adaptive c S / Recrutement d'un consult Quality And Cost- Open - Internationa Pending Impleme IDA / D9250 apacity of the food system’s Post 352,632.00 0.00 2023-05-05 2023-05-26 2023-07-09 2023-08-06 2023-09-05 2023-10-10 2023-11-14 2024-11-13 ant chargé des étude techniq Based Selection l ntation productive base ues des seuils de correction NE-FRSP-NE-342655-CS-QCB S / Recrutement d'un consult Sustainability and adaptive c ant pour les études de faisab Quality And Cost- Open - Internationa IDA / D9250 apacity of the food system’s Post 307,000.00 0.00 Under Review 2023-04-15 2023-05-20 2023-05-02 2023-06-15 2023-07-17 2023-07-28 2023-08-18 2023-09-22 2023-12-31 ilité technique et contrôle de Based Selection l productive base s travaux d'une petite retenu e d'eau dans la région de Till abéry NE-FRSP-NE-361744-CS-CQS / Recrutement d'ONG pour l'é Sustainability and adaptive c Consultant Qualifi Under Implement laboration d'un Plan GIP (Ges IDA / D9250 apacity of the food system’s Post Limited 300,000.00 0.00 2023-05-22 2023-05-26 2023-06-12 2023-07-12 2023-08-15 2025-08-14 cation Selection ation tion Intégrée du Paysage) da productive base ns la région de Zinder NE-FRSP-NE-361758-CS-CQS / Recrutement d'ONG pour l'é Sustainability and adaptive c Consultant Qualifi Under Implement laboration d'un Plan GIP (Ges IDA / D9250 apacity of the food system’s Post Limited 300,000.00 0.00 2023-05-22 2023-05-26 2023-06-05 2023-07-05 2023-08-15 2025-08-14 cation Selection ation tion Intégrée du Paysage) da productive base ns la région de Tahoua NE-FRSP-NE-361797-CS-CQS Sustainability and adaptive c / Recrutement d'ONG pour l'é Consultant Qualifi Under Implement IDA / D9250 apacity of the food system’s Post Limited 200,000.00 0.00 2023-05-22 2023-05-26 2023-06-05 2023-07-05 2023-08-15 2025-08-14 laboration d'un Plan GIP (Ges cation Selection ation productive base tion Intégrée du Paysage) da ns la région de Diffa NE-FRSP-NE-361801-CS-CQS / Recrutement d'ONG pour l'é Sustainability and adaptive c Consultant Qualifi Under Implement laboration d'un Plan GIP (Ges IDA / D9250 apacity of the food system’s Post Limited 200,000.00 0.00 2023-05-22 2023-05-26 2023-06-05 2023-07-05 2023-08-15 2025-08-14 cation Selection ation tion Intégrée du Paysage) da productive base ns la région de Tillabéry NE-FRSP-NE-361866-CS-QCB S / Recrutement d’un cabinet pour l’étude de faisabilité (AP Sustainability and adaptive c Quality And Cost- Open - Internationa S/APD/EIES/DAO) et le contrôl IDA / D9250 apacity of the food system’s Post 307,000.00 0.00 Under Review 2023-05-22 2023-05-20 2023-06-12 2023-07-24 2023-08-21 2023-08-31 2023-09-08 2023-10-13 2024-10-12 Based Selection l e des travaux d’aménageme productive base nt des bas-fonds (seuils d’ép andage/petits barrages) dans les régions de Tahoua et INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NE-FRSP-NE-306128-CS-IND Digital advisory services for Individual Consult Pending Impleme V / Recrutement consultant p IDA / 69980 agriculture and food crisis pr Post Limited 17,422.00 0.00 2022-08-15 2022-08-22 2022-09-05 2022-09-15 2022-11-14 ant Selection ntation our la mise à jour des param evention and management ètres d’analyse NE-FRSP-NE-306140-CS-IND V / Recrutement consultant p Digital advisory services for our identifier/répertorier les f Individual Consult IDA / 69980 agriculture and food crisis pr Post Limited 52,265.00 0.00 Signed 2022-10-10 2022-12-07 2022-10-31 2023-02-22 2022-11-15 2023-04-25 2022-11-16 2022-12-31 ournisseurs et évaluation des ant Selection evention and management besoins de services hydro m étéo, phyto, et agro météo (I ncluant le secteur privée) NE-FRSP-NE-306156-CS-IND V / Recrutement d'un prestat Digital advisory services for Individual Consult Pending Impleme aire pour l'identification des t IDA / 69980 agriculture and food crisis pr Post Limited 17,422.00 0.00 2022-09-15 2022-09-30 2022-10-12 2022-10-15 2022-11-29 ant Selection ntation ypes de services et des mod evention and management alités d'engagement du sect eur privé NE-FRSP-NE-306516-CS-CDS / Service de consultant pour l IDA / 69980 Project Management Post Direct Selection Direct - National 26,132.00 0.00 Completed 2022-08-15 2022-08-19 2022-08-22 2022-09-20 2022-09-07 2022-10-07 2023-03-23 e recrutement du personnel complémentaire du FSRP Page 2 NE-FRSP-NE-306199-CS-IND V / Recrutement d'un Consult Regional food market integr Individual Consult ant pour l’Identification des a IDA / 69980 Post Limited 10,180.00 0.00 Canceled 2022-09-26 2022-10-10 2022-10-31 2022-11-15 2022-12-30 ation and trade ant Selection cteurs dans les chaines de va leur de Niébé et Oignon NE-FRSP-NE-309010-CS-IND V / Recrutement d'un Consult Regional food market integr Individual Consult IDA / 69980 Post Limited 5,500.00 0.00 Canceled 2022-09-26 2022-10-10 2022-10-31 2022-11-01 2022-12-01 ant pour l’Identification des a ation and trade ant Selection cteurs dans la chaine de vale ur Bétail-viande-lait NE-FRSP-NE-342594-CS-IND V / Recrutement d’un Consult Individual Consult ant pour l' Elaboration d'un g IDA / D9250 Project Management Post Limited 17,545.00 0.00 Under Review 2023-02-20 2023-02-22 2023-02-28 2023-03-10 2023-03-13 2023-05-02 ant Selection uide simplifié de gestion fina ncière pour les partenaires NE-FRSP-NE-342595-CS-IND V / Recrutement d'un consult Sustainability and adaptive c Individual Consult Pending Impleme ant pour l'élaboration d'une c IDA / D9250 apacity of the food system’s Post Limited 17,545.00 0.00 2023-04-03 2023-04-13 2023-04-20 2023-04-21 2023-05-31 ant Selection ntation artographie des groupes vuln productive base érables et constitution des b ases de données NE-FRSP-NE-342596-CS-IND Sustainability and adaptive c V / Recrutement d'un consult Individual Consult Pending Impleme IDA / D9250 apacity of the food system’s Post Limited 26,667.00 0.00 2023-04-01 2023-04-10 2023-04-21 2023-04-25 2023-06-14 ant pour l'élaboration de 3 pl ant Selection ntation productive base ans d’aménagement des zon es humides Page 3 PROCUREMENT PLAN (Textual Part) Project information: Papua New Guinea (PNG), PNG Agriculture Commercialization and Diversification Strategy, P-166222 Project Implementation agency: Department of Agriculture and Livestock (DAL); Cocoa Board (CB); and Coffee Industry Corporation (CIC) Date of the Procurement Plan: February 13, 2020 Period covered by this Procurement Plan: February 2020 – to August 2021 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016, revised November 2017 and August 2018) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the National Procurement Act 2018, No. 12 of 2018, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. National preferences Eligibility: Eligibility to participate in a procurement process for and to be awarded a Bank financed contract shall be as defined under paragraphs 3.21-3.23 of the Procurement Regulations; accordingly, no bidder or potential bidder shall be declared ineligible for contracts financed by the Bank for reasons other than those provided in the said paragraphs. Foreign bidders shall be eligible to participate in bidding under the same conditions as national bidders. No domestic preference shall be granted in bid evaluation on the basis of bidder’s nationality, origin of goods or services, and/or preferential programs. Registration of bidders as Registration of bidders: condition for bidding Registration shall not be used to assess bidders’ qualifications. A foreign bidder shall not be required to register as a condition for submitting its bid, and a foreign bidder recommended for contract award shall be given a reasonable opportunity to register, with the reasonable cooperation of the Recipient, prior to contract signing. Procurement documents Procurement Documents: Templates of procurement documents, including contract forms, acceptable to the Association shall be used for all procurement financed by the Project. Document Fees Bidding Document Fees: A fee for bidding documents if applied must be reasonable and is to be used to offset the actual costs associated with reproduction of large bidding documents and associated plans and drawings. It is not to be used to generate revenue, or to limit or restrict participation in procurement processes. Bidding document fees are not to be charged for the procurement of consulting services (firms and individual), non-consulting services, or goods. Fraud and Corruption Fraud and Corruption: The procurement documents shall require that bidders submitting bids present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights. Negotiations and Cancellation of all bids: cancellation of All bids (or the sole bid if only one bid is procurement process received) shall not be rejected, the procurement process shall not be cancelled, and new bids shall not be solicited without the Bank’s prior written concurrence. Complaints Handling Complaints Review Mechanism: The Recipient shall establish and implement an effective, fair and timely complaints review mechanism allowing bidders to complain and to have their complaints handled in a timely manner. Until an adequate complaints review mechanism (as assessed by the Bank) is established the Bank’s review mechanism as set out in the Procurement Regulations will apply. Contract Award Notice Publication of Contract Award Notice: For purposes of Article 36(5) of the Act, within one month from award, a notice of all procurement contract awards shall include, at a minimum as relevant and applicable for each procurement method (a) the name of each bidder that submitted a bid; (b) bid prices as read out at bid opening; (c) evaluated prices of each bid that was evaluated; (d) the names of bidders whose bids were either rejected as nonresponsive or not meeting qualification criteria, or not evaluated, with the reasons thereof; and (e) the name of the winning bidder, the final total contract price, as well as the duration and a summary of the scope of the contract. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. The above captioned conditions also apply when approaching the international market. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Not Applicable Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations: Not Applicable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: Not Applicable; Works: Not Applicable PROCUREMENT Papua New Guinea : PNG Agriculture Commercialization and Diversification Project PLAN General Information Country: Papua New Guinea 2021-07-23 Bank’s Approval Date of the Original Procurement Plan: 2023-06-04 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P166222 GPN Date: 2020-12-12 Project Name: PNG Agriculture Commercialization and Diversification Project Loan / Credit No: IDA / 64660 Coffee Industry Corporation Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PG-CIC-321953-GO-RFQ / St andard Multi-Function Printer Institutional Capacity Buildin Request for Quota Single Stage - One E Under Imple , Scanner and Photocopier-un IDA / 64660 Post Limited 15,000.00 0.00 2022-12-26 2023-02-13 2023-01-17 2023-01-31 g tions nvelope mentation der component 1 for CIC's Co ffee Research Institute Librar y in Aiyura, EHP. PG-CIC-361661-GO-RFQ / Pu Institutional Capacity Buildin Request for Quota Single Stage - One E Under Imple rchase of Factory Machines-P IDA / 64660 Post Limited 87,000.00 0.00 2023-06-19 2023-06-07 2023-08-14 2024-08-08 g tions nvelope mentation anga, Sub-station (dry coffee mill) NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PG-CIC-236458-CS-INDV / Pr Project Management and Mo Individual Consult IDA / 64660 Prior Open 540,000.00 0.00 Canceled 2021-06-01 2021-07-20 2021-08-10 2021-09-14 2022-03-13 oject Manager, Coffee PMU nitoring and Evaluation ant Selection PG-CIC-236473-CS-INDV / Se Project Management and Mo Individual Consult IDA / 64660 Post Open 276,000.00 95,044.72 Signed 2021-06-01 2021-12-03 2021-07-20 2022-03-01 2021-08-10 2022-02-28 2021-09-14 2022-03-05 2022-03-13 nior Procurement Officer, Cof nitoring and Evaluation ant Selection fee PMU PG-CIC-236469-CS-INDV / M Project Management and Mo Individual Consult onitoring, Evaluation and Sur IDA / 64660 Post Open 220,000.00 92,404.62 Terminated 2021-06-01 2021-12-03 2021-07-20 2022-03-01 2021-08-10 2022-03-01 2021-09-14 2022-03-01 2022-03-13 nitoring and Evaluation ant Selection vey Officer (MESO) PG-CIC-236474-CS-INDV / Pr Individual Consult oductive Partnership Coordin IDA / 64660 Productive Partnerships Prior Open 360,000.00 0.00 Signed 2021-08-05 2022-01-05 2021-09-23 2022-07-28 2021-10-14 2023-03-14 2021-11-18 2023-05-21 2022-05-17 ant Selection ator, Coffee PMU PG-CIC-248926-CS-INDV / En Project Management and Mo Individual Consult IDA / 64660 Post Open 210,000.00 40,636.99 Signed 2021-08-18 2021-12-03 2021-10-06 2022-03-11 2021-10-27 2022-03-14 2021-12-01 2022-03-17 2022-05-30 vironmental and Social Office nitoring and Evaluation ant Selection r PG-CIC-260472-CS-INDV / Pr Project Management and Mo Individual Consult oject Manager, Coffee Project IDA / 64660 Prior Open 424,000.00 0.00 Signed 2021-10-29 2021-11-08 2021-12-17 2022-07-19 2022-01-07 2022-08-17 2022-02-11 2023-05-08 2022-08-10 nitoring and Evaluation ant Selection Management Unit PG-CIC-236468-CS-INDV / Se Project Management and Mo Individual Consult IDA / 64660 Prior Open 326,000.00 0.00 Canceled 2021-08-05 2021-09-23 2021-10-14 2021-11-18 2022-05-17 nior Finance Officer, Coffee P nitoring and Evaluation ant Selection MU PG-CIC-236481-CS-INDV / Se Individual Consult IDA / 64660 Agriculture Feeder Roads Prior Open 377,000.00 0.00 Canceled 2021-08-05 2021-09-23 2021-10-14 2021-11-18 2022-05-17 nior Engineer, Coffee PMU ant Selection PG-CIC-266769-CS-INDV / Co Individual Consult IDA / 64660 Agriculture Feeder Roads Post Open 295,000.00 0.00 Signed 2021-12-10 2022-11-24 2022-01-28 2023-05-22 2022-02-18 2023-06-12 2022-03-25 2025-12-04 ffee PMU Senior Engineer ant Selection PG-CIC-266768-CS-INDV / Se Project Management and Mo Individual Consult IDA / 64660 Post Open 240,000.00 86,607.73 Terminated 2021-12-13 2021-12-07 2022-02-09 2022-03-14 2022-03-02 2022-03-14 2022-04-06 2022-03-15 2025-12-16 nior Finance Officer, Coffee P nitoring and Evaluation ant Selection MU PG-CIC-288418-CS-INDV / M Project Management and Mo Individual Consult onitoring, Evaluation and Sur IDA / 64660 Post Limited 220,000.00 73,308.35 Terminated 2022-04-11 2022-04-07 2022-04-25 2022-04-12 2022-05-09 2022-04-22 2022-06-06 2022-04-21 2023-02-11 nitoring and Evaluation ant Selection vey Officer (MESO) PG-CIC-288419-CS-INDV / Se Project Management and Mo Individual Consult IDA / 64660 Post Limited 240,000.00 116,086.28 Signed 2022-04-11 2022-04-07 2022-04-16 2022-04-11 2022-04-30 2022-04-14 2022-05-28 2022-04-24 2023-02-02 nior Finance Officer, Coffee P nitoring and Evaluation ant Selection MU PG-CIC-289818-CS-INDV / Se Individual Consult IDA / 64660 Productive Partnerships Post Open 167,000.00 0.00 Terminated 2022-05-16 2022-05-16 2022-06-18 2022-09-30 2022-06-28 2022-09-30 2022-07-13 2023-01-09 nior Partnership Officer - East ant Selection ern Zone PG-CIC-289829-CS-INDV / Se Individual Consult IDA / 64660 Productive Partnerships Post Open 167,000.00 0.00 Signed 2022-05-16 2022-05-16 2022-06-14 2022-10-04 2022-06-24 2022-10-04 2022-07-09 2023-01-05 nior Partnership Officer - Wes ant Selection tern Zone Page 1 PG-CIC-290477-CS-INDV / Inf Project Management and Mo Individual Consult ormation Technology & Mana IDA / 64660 Post Open 170,520.00 0.00 Signed 2022-05-16 2022-05-16 2022-06-14 2022-10-27 2022-06-24 2022-10-27 2022-07-20 2023-01-16 nitoring and Evaluation ant Selection gement Information Systems Officer PG-CIC-289832-CS-INDV / Fi Project Management and Mo Individual Consult IDA / 64660 Post Open 97,440.00 0.00 Signed 2022-05-16 2022-05-20 2022-06-14 2022-10-05 2022-06-19 2022-10-05 2022-07-15 2023-01-11 nance and Administration Off nitoring and Evaluation ant Selection icer PG-CIC-307536-CS-INDV / M Project Management and Mo Individual Consult IDA / 64660 Post Open - National 220,000.00 0.00 Signed 2022-08-08 2022-08-15 2022-09-26 2022-11-03 2022-10-17 2022-10-03 2022-11-21 2025-12-25 onitoring, Evaluation and Sur nitoring and Evaluation ant Selection vey Officer PG-CIC-321943-CS-CDS / Co Institutional Capacity Buildin Direct - Internation nsultant-ToT Training for PNG IDA / 64660 Post Direct Selection 6,000.00 0.00 Signed 2022-12-12 2022-10-18 2022-12-27 2023-01-13 2023-02-07 2023-02-12 g al Coffee Extension Manuals PG-CIC-328546-CS-INDV / Pa Individual Consult Under Implement IDA / 64660 Productive Partnerships Post Open - National 91,350.00 0.00 2022-12-12 2022-11-22 2023-01-14 2023-01-19 2023-01-29 2025-01-18 rtnership Officer, Eastern Zo ant Selection ation ne. PG-CIC-328548-CS-INDV / Pa Individual Consult Under Implement IDA / 64660 Productive Partnerships Post Open - National 91,350.00 0.00 2022-12-12 2022-11-22 2023-01-05 2023-01-10 2023-01-29 2025-01-18 rtnership Officer, Western Zo ant Selection ation ne PG-CIC-328557-CS-INDV / Ad Project Management and Mo Individual Consult Under Implement IDA / 64660 Post Limited 42,630.00 0.00 2022-12-12 2022-11-25 2022-12-26 2022-12-31 2023-01-10 2023-03-23 ministration Officer, Western nitoring and Evaluation ant Selection ation Zone PG-CIC-328553-CS-INDV / Fi Project Management and Mo Individual Consult IDA / 64660 Post Open - National 85,260.00 0.00 Canceled 2022-12-12 2023-01-05 2023-01-10 2023-01-20 2025-01-09 nance & Admin Officer-Gorok nitoring and Evaluation ant Selection a PG-CIC-335414-CS-INDV / Fi Project Management and Mo Individual Consult Under Implement nance & Procurement Officer IDA / 64660 Post Open - National 84,877.00 0.00 2023-01-30 2023-01-20 2023-03-04 2023-03-09 2023-03-19 2025-03-18 nitoring and Evaluation ant Selection ation -Goroka/Panga PG-CIC-331087-CS-INDV / M Individual Consult SME Development Officer (Mi IDA / 64660 Productive Partnerships Post Open - National 125,283.00 0.00 Signed 2023-01-23 2023-01-23 2023-02-25 2023-06-16 2023-03-02 2023-06-16 2023-03-12 2025-12-26 ant Selection cro Small Medium Enterprise) PG-CIC-363589-CS-INDV / Se Project Management and Mo Individual Consult Under Implement nior Partnership Officer, East IDA / 64660 Post Limited 167,000.00 0.00 2023-05-30 2023-06-01 2023-06-04 2023-06-25 2023-07-30 2024-01-26 nitoring and Evaluation ant Selection ation ern Zone (Replacement) Page 2 PROCUREMENT PLAN (Textual Part) Project information: Mauritania, Western Africa Regional Digital Integration Program (WARDIP) [P176932] Project Implementation agency: Ministere de la Transition Numerique, de l’Innovation et de la Modernisation de l’Administration (MTNIMA) Date of the Procurement Plan: December 22, 2021 Period covered by this Procurement Plan: December 22, 2021 - November 30, 2022 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in “le décret N° 2020-122 du 06 octobre 2020, modifiant et complétant certaines dispositions du décret N° 2017-126 du 02 novembre 2017, abrogeant et replaçant les dispositions des décrets d’applications de la loi N° 2010-044 du 22 juillet 2010”, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: [is not applicable]; Works: [is not applicable] Other Relevant Procurement Information. PROCUREMENT Western and Central Africa : Western Africa Regional Digital Integration Program SOP1 PLAN General Information Country: Western and Central Africa 2023-06-01 Bank’s Approval Date of the Original Procurement Plan: 2023-06-01 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P176932 GPN Date: Project Name: Western Africa Regional Digital Integration Program SOP1 Loan / Credit No: IDA / V4020 PCU Western Africa Regional Digital Integration Program Executing Agency(ies): WORKS Activity Reference No. / Procureme Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH Ri Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method nt Docume ount (US$ and Recommendation Signed Contract o. h cess (Y/N) sk atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion nt Type ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual WARDIP-F - 016-2023 / Mobil Component 5. Project Manag Request for Quota Single Stage - One E Pending Impl iário de escritório para a Unid IDA / V4020 ement and Implementation Post Open - National 0.00 2023-06-26 2023-08-21 2024-02-17 tions nvelope ementation ade de Gestão Support WARDIP-F - 017-2023 / IT an Component 5. Project Manag Request for Quota Single Stage - One E Pending Impl IDA / V4020 Post Open - National 0.00 2023-06-28 2023-08-23 2024-02-19 d Office Equipment ement and Implementation tions nvelope ementation Support WARDIP-F - 018-2023 / Stati Component 5. Project Manag Request for Quota Single Stage - One E Pending Impl IDA / V4020 Post Open - National 0.00 2023-07-03 2023-08-28 2024-02-24 onary ement and Implementation tions nvelope ementation Support WARDIP-F - 019-2023 / Com Component 5. Project Manag Request for Quota Single Stage - One E Pending Impl munication Devices (telepho IDA / V4020 ement and Implementation Post Open - National 0.00 2023-07-04 2023-08-29 2024-02-25 tions nvelope ementation ne, router, etc) Support NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual WARDIP-C - 006-2023 / Lega Component 1. Enabling envi l analysis of missing /outdate Quality And Cost- Open - Internationa Pending Impleme IDA / V4020 ronment for the establishme Post 0.00 2023-06-30 2023-07-21 2023-09-03 2023-10-01 2023-10-31 2023-12-05 2024-01-09 2025-01-08 d laws and regulations and re Based Selection l ntation nt of a continental SDM commendations for needed r eforms WARDIP-C - 007-2023 / Stud y of the national backbone: F Component 1. Enabling envi easibility (technical, financial Quality And Cost- Open - Internationa Pending Impleme IDA / V4020 ronment for the establishme Post 0.00 2023-06-19 2023-07-10 2023-08-23 2023-09-20 2023-10-20 2023-11-24 2023-12-29 2024-12-28 and governance), preparatio Based Selection l ntation nt of a continental SDM n of tender documents (DAO) , monitoring and evaluation ( M&E). WARDIP-C - 008-2023 / Stud y of (i) redundancy of interna Component 1. Enabling envi tional connectivity, (ii) sale of Quality And Cost- Open - Internationa Pending Impleme IDA / V4020 ronment for the establishme Post 0.00 2023-06-27 2023-07-18 2023-08-31 2023-09-28 2023-10-28 2023-12-02 2024-01-06 2025-01-05 excess capacity to neighbors Based Selection l ntation nt of a continental SDM , (iii) improvement of SCGB g overnance and (iv) improvem ent of FAU management WARDIP-C - 009-2023 / Feasi bility study for establishing a Component 3. Data Market Quality And Cost- Open - Internationa Under Implement n NREN and connecting it to t IDA / V4020 Development and Integratio Post 0.00 2023-07-15 2023-06-20 2023-08-05 2023-06-22 2023-09-18 2023-10-16 2023-11-15 2023-12-20 2024-01-24 2025-01-23 Based Selection l ation he Western and Central Afric n a Research and Education Ne twork (WACREN) WARDIP-C - 010-2023 / Stud y on government needs for a Security Operations Center ( Quality And Cost- Open - Internationa Under Implement SOC), Computer Emergency IDA / V4020 Component 6. CERC Post 0.00 2023-07-14 2023-06-20 2023-08-04 2023-06-22 2023-09-17 2023-10-15 2023-11-14 2023-12-19 2024-01-23 2025-01-22 Based Selection l ation Response Team (CERT) and n ational cloud, including a dat a sharing and infrastructure analysis and DAO WARDIP-C - 011-2023 / Gap analysis on (i) demand for di gital skills in the public and p Component 3. Data Market rivate sectors; (ii) current su Quality And Cost- Open - Internationa Pending Impleme IDA / V4020 Development and Integratio Post 0.00 2023-07-17 2023-08-07 2023-09-20 2023-10-18 2023-11-17 2023-12-22 2024-01-26 2025-01-25 pply of digital skills in the pri Based Selection l ntation n vate sector and public sector ; and (iii) suggestions on how to expand or strengthen exis ting and future programs and courses t WARDIP-C - 012-2023 / Gap analysis of the entrepreneurs Component 4. Online Market Quality And Cost- Open - Internationa hip ecosystem and needs of IDA / V4020 Development and Integratio Post 0.00 Under Review 2023-07-12 2023-06-22 2023-08-02 2023-09-15 2023-10-13 2023-11-12 2023-12-17 2024-01-21 2025-01-20 Based Selection l digital entrepreneurs and rec n ommended actions (DAO) WARDIP-C - 013-2023 / Detai Component 3. Data Market led analysis of digital payme Quality And Cost- Open - Internationa IDA / V4020 Development and Integratio Post 0.00 Under Review 2023-07-30 2023-06-22 2023-08-20 2023-10-03 2023-10-31 2023-11-30 2024-01-04 2024-02-08 2025-02-07 nts and financial digital servi Based Selection l n ces infrastructure WARDIP-C - 014-2023 / Feasi bility study for the developm Component 2. Connectivity Quality And Cost- Open - Internationa ent of an interoperability fra IDA / V4020 Market Development and Int Post 0.00 Under Review 2023-07-31 2023-06-22 2023-08-21 2023-10-04 2023-11-01 2023-12-01 2024-01-05 2024-02-09 2025-02-08 Based Selection l mework and platform, as well egration as digitalization of the main public services and DAO Page 1 WARDIP-C - 015-2023 / Tech nical assistance to the Minist Component 1. Enabling envi ry of Transport and Communi Quality And Cost- Open - Internationa Pending Impleme IDA / V4020 ronment for the establishme Post 0.00 2023-07-24 2023-08-14 2023-09-27 2023-10-25 2023-11-24 2023-12-29 2024-02-02 2025-02-01 cations for the development Based Selection l ntation nt of a continental SDM of human and institutional ca pacity in terms of digital tran sformation. INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Actual Amount Invitation to Identifie Draft Negotiated Cont Component Review Type Method Contract Type Process Status Teams of Reference Signed Contract Contract Completion Description o. h (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 2 PROCUREMENT PLAN (Textual Part) Project information: Republic of Trinidad and Tobago: COVID-19 EMERGENCY RESPONSE PROJECT (P173989) Project Implementation agency: MOH – Ministry of Health Date of the Procurement Plan: June 30th, 2020 Period covered by this Procurement Plan: From July 2020 to December 2021 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the national procurement legislation, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions: The corresponding Procurement Documents must be acceptable to the World Bank. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations and the corresponding Procurement Documents must be acceptable to the World Bank. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: “Not Applicable” Procurement of Second-Hand Goods as specified under paragraph 5.11 of the Procurement Regulations: “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: “Not Applicable”; Works: “Not Applicable” Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations is “Not Applicable” Other Relevant Procurement Information. Since the Project triggers Paragraph 12 of the IPF Policy, which relates to Projects in Situations of Urgent Need of Assistance or Capacity Constraints, the GoRTT and the Bank have agreed that the MOH would directly engage PAHO/WHO to source all PPEs, pharmaceuticals, medical supplies, equipment and vaccines the Project needs to respond the COVID-19 pandemic, given PAHO/WHO’s rapid mobilization on the ground and expertise in responding emergency situations like the current one. When entering into a contract with PAHO/WHO, the MOH will use a standard form of agreement previously negotiated and approved by the Bank. PROCUREMENT Trinidad and Tobago : Republic of Trinidad and Tobago: COVID-19 EMERGENCY RESPONSE PROJECT PLAN General Information Country: Trinidad and Tobago 2021-05-03 Bank’s Approval Date of the Original Procurement Plan: 2023-06-07 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P173989 GPN Date: 2021-05-10 Project Name: Republic of Trinidad and Tobago: COVID-19 EMERGENCY RESPONSE PROJECT Loan / Credit No: IBRD / 91570 Ministry of Health Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TT-MOH-232028-GO-RFB / Pr ocurement/supply of COVID- Emergency Response to CO IBRD / 91570 Prior Direct Selection Direct 11,617,613.85 0.00 Signed 2021-05-16 2021-05-20 2021-05-23 2021-06-01 2021-06-27 2022-06-22 19 related PPEs, pharmaceuti VID-19 cals, medical supplies and eq uipments TT-MOH-343910-GO-RFQ / P Project Management and Mo Request for Quota Single Stage - One E IBRD / 91570 Post Limited 18,680.00 0.00 Signed 2023-02-22 2022-12-28 2023-04-19 2023-10-16 urchasing of ICT Equipment f nitoring tions nvelope or the PIU TT-MOH-348518-GO-DIR / Pu Support to COVID-19 Vaccin Direct - Internation Under Revie IBRD / 91570 Prior Direct Selection 7,500,000.00 0.00 2023-03-09 2023-03-14 2023-04-18 2023-10-15 rchasing of COVID-19 Vaccin ation Campaign al w es TT-MOH-348548-GO-DIR / Pu Support to COVID-19 Vaccin Direct - Internation Under Revie IBRD / 91570 Prior Direct Selection 173,432.00 0.00 2023-03-09 2023-03-14 2023-04-18 2023-10-15 rchasing of COVID-19 vaccin ation Campaign al w es TT-MOH-348554-GO-DIR / Th Project Management and Mo e purchasing of SAGE 50 Acc IBRD / 91570 Post Direct Selection Direct - National 4,412.00 0.00 Signed 2023-03-09 2023-03-17 2023-03-14 2023-03-03 2023-04-18 2023-10-15 nitoring ounting Software for the PIU Team NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TT-MOH-365711-CS-LCS / Fi nancial Audit Services for the COVID 19 Emergency Respo Project Management and Mo Least Cost Selecti Under Implement IBRD / 91570 Post Open - National 60,000.00 0.00 2023-06-06 2023-05-25 2023-06-27 2023-08-10 2023-09-07 2023-10-07 2023-11-11 2023-12-16 2024-06-13 nse Project for the periods M nitoring on ation arch 15, 2021 to September 30, 2023, October 1, 2023 to June 30, 2024. INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TT-MOH-IC-1 / PIU Project Ma Project Management and Mo Individual Consult IBRD / 91570 Post Limited 39,000.00 0.00 Under Review 2021-03-01 2022-08-08 2021-08-28 2022-02-24 2022-04-14 2023-04-14 nager nitoring ant Selection TT-MOH-IC-3 / PIU Financial Project Management and Mo Individual Consult IBRD / 91570 Post Limited 39,000.00 0.00 Under Review 2021-03-01 2022-08-09 2021-08-28 2022-02-24 2022-04-14 2023-04-14 Management Officer nitoring ant Selection TT-MOH-IC-4 / PIU Environm Project Management and Mo Individual Consult IBRD / 91570 Post Limited 39,000.00 0.00 Under Review 2021-03-01 2022-08-09 2021-08-28 2022-02-24 2022-04-14 2023-04-14 ental and Social Specialist nitoring ant Selection TT-MOH-IC-2 / PIU Procurem Project Management and Mo Individual Consult IBRD / 91570 Post Limited 39,000.00 0.00 Under Review 2021-03-01 2022-10-20 2021-08-28 2022-02-24 2022-04-14 2023-04-14 ent Officer nitoring ant Selection Page 1 PROCUREMENT PLAN (Textual Part) Project information: Pakistan Pandemic Response Effectiveness Project (P173796) Project Implementation agency: (i) Ministry of National Health Services, Regulations and Coordination; (ii) National Disaster Management Authority (iii) Benazir Income Support Programme and; (iv) Provincial EPI Cells Date of the Procurement Plan: April 13, 2020 Period covered by this Procurement Plan: April-2020 to June 2021 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016, Revised November 2017 and August 2018) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in Public Procurement Rules 2004, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions: 1) The eligibility of bidders shall be as defined under Section III of the Procurement Regulations. Accordingly, no bidder or potential bidder shall be declared ineligible for contracts financed by the Bank for reasons other than those provided in Section III of the Procurement Regulations. 2) For national open competitive procurement, only the model procurement documents acceptable to the World Bank, shall be used. 3) The request for bids/request for proposals document shall require that Bidders/Proposers submitting Bids/Proposals present a signed acceptance (in the form attached) at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights. 4) Procurement Documents include provisions, as agreed with the Bank, intended to adequately mitigate against environmental, social (including sexual exploitation and abuse and gender-based violence), health and safety (“ESHS”) risks and impacts 5) Access to procurement opportunities shall not be restricted to firms that have pre-registered and/or paid a registration fee. 6) No preference of any kind shall be given to national bidders in the bidding process. When other national procurement arrangements (other than national open competitive procurement) are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations is Applicable. Other Relevant Procurement Information. Procurement in Situations of Urgent Need of Assistance or Capacity Constraints etc. are applicable Letter of Acceptance of the World Bank’s Anticorruption Guidelines and Sanctions Framework1 Date: Invitation of Bids/Proposals No.__________ To: ___________________________________________________________________________ We, along with our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not) consultants and personnel, acknowledge and agree to abide by the World Bank’s policy regarding Fraud and Corruption (corrupt, fraudulent, collusive, coercive, and obstructive practices), as set out and defined in the World Bank’s Anti-Corruption Guidelines2 in connection with the procurement and execution of the contract (in case of award), including any amendments thereto. We declare and warrant that we, along our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not), consultants and personnel, are not subject to, and are not controlled by any entity or individual that is subject to, a temporary suspension, early temporary suspension, or debarment imposed by a member of the World Bank Group, including, inter alia, a cross-debarment imposed by the World Bank Group as agreed with other international financial institutions (including multilateral development banks), or through the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement. Further, we are not ineligible under the laws or official regulations of [Insert name of Employer as per bidding document] or pursuant to a decision of the United Nations Security Council. We confirm our understanding of the consequences of not complying with the World Bank’s Anti-Corruption Guidelines, which may include the following: a. rejection of our Proposal/Bid for award of contract; 1[Drafting note: This document shall be signed by bidders/proposers/consultants and submitted as part of their bids/proposals. In addition, this document shall be signed by the winning bidder/consultant and incorporated as part of the contract.] 2Guidelines on Preventing and Combating Fraud and Corruption in Projects Financed by International Bank for Reconstruction and Development Loans and the International Development Agency Credits and Grants, dated October 15, 2006, and revised in January 2011 and July 2016, as they may be revised from time to time. b. in the case of award, termination of the contract, without prejudice to any other remedy for breach of contract; and c. sanctions, pursuant to the Bank’s Anti-Corruption Guidelines and in accordance with its prevailing sanctions policies and procedures as set forth in the Bank’s Sanctions Framework. This may include a public declaration of ineligibility, either indefinitely or for a stated period of time, (i) to be awarded or otherwise benefit from a Bank-financed contract, financially or in any other manner;3 (ii) to be a nominated4 sub-contractor, sub-consultant, consultant, manufacturer or supplier, or service provider of an otherwise eligible firm being awarded a Bank-financed contract; and (iii) to receive the proceeds of any loan made by the Bank or otherwise to participate further in the preparation or implementation of any Bank- financed project. We understand that we may be declared ineligible as set out above upon: a. completion of World Bank Group sanctions proceedings according to its prevailing sanctions procedures; b. cross-debarment as agreed with other international financial institutions (including multilateral development banks); c. the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement; or d. temporary suspension or early temporary suspension in connection with an ongoing World Bank Group sanctions proceeding. For avoidance of doubt, the foregoing effects of ineligibility do not extend to a sanctioned firm’s or individual’s execution of its ongoing Bank-financed contracts (or its ongoing sub-agreements under such contracts) that are not the subject of a material modification, as determined by the Bank. We shall permit, and shall cause our sub-contractors, sub-consultants, agents (whether declared or not), personnel, consultants, service providers or suppliers, to permit the Bank to inspect5 all accounts, records, and other documents relating to 3 For the avoidance of doubt, a sanctioned party’s ineligibility to be awarded a contract shall include, without limitation, (i) applying for pre-qualification or initial selection), expressing interest in a consultancy, and bidding, either directly or as a nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider, in respect of such contract, and (ii) entering into an addendum or amendment introducing a material modification to any existing contract. 4A nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider (different names are used depending on the bidding document) is one which has been: (i) included by the bidder in its pre-qualification or initial selection application or bid because it brings specific and critical experience and know-how that allow the bidder to meet the qualification requirements for the particular bid; or (ii) appointed by the Borrower. 5Inspections in this context are usually investigative (i.e., forensic) in nature: they involve fact- finding activities undertaken by the Bank or persons appointed by the Bank to address specific the procurement process and/or contract execution (in the case of award), and to have them audited by auditors appointed by the Bank. We agree to preserve all accounts, records, and other documents (whether in hard copy or electronic format) related to the procurement and execution of the contract. Name of the Bidder/Proposer/Consultant: Name of the person duly authorized to sign the Bid/Proposal on behalf of the Bidder/Proposer/ Consultant: Title of the person signing the Letter: matters related to investigations/audits, such as evaluating the veracity of an allegation of possible Fraud and Corruption, through the appropriate mechanisms. Such activity includes but is not limited to accessing and examining a firm's or individual's financial records and information, and making copies thereof as relevant; accessing and examining any other documents, data, and information (whether in hard copy or electronic format) deemed relevant for the investigation/audit, and making copies thereof as relevant; interviewing staff and other relevant individuals; performing physical inspections and site visits; and obtaining third-party verification of information. PROCUREMENT Pakistan : PANDEMIC RESPONSE EFFECTIVENESS IN PAKISTAN PLAN General Information Country: Pakistan 2022-06-20 Bank’s Approval Date of the Original Procurement Plan: 2023-06-07 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P173796 GPN Date: 2020-04-20 Project Name: PANDEMIC RESPONSE EFFECTIVENESS IN PAKISTAN Loan / Credit No: IDA / 65900 Ministry of Federal Education and Professional Training Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PK-MOFEPT-300476-GO-RFB / Procurement of relevant eq uipment for AIOU on lot-wise basis for transmission of DL c hannels. The categories are: Component 2. Mitigation of Open - Internationa Single Stage - One E 1. Earth Station Uplink & Ser IDA / 65900 Post Request for Bids 1,480,000.00 0.00 Canceled 2022-09-19 2023-02-23 2022-09-22 2023-02-26 2022-11-07 2023-03-17 2022-11-21 2022-11-25 2023-05-31 Disruptive Impacts l nvelope ver Development 2. Upgradation of Existing Fa cilities 3. Establishment of Studio 4. Post-Production Assets 3. Up PK-MOFEPT-327308-GO-RFB / Procurement of Handheld D Component 2. Mitigation of Single Stage - One E evices (Chromebooks) for stu IDA / 65900 Prior Request for Bids Open - National 3,250,000.00 0.00 Canceled 2022-12-12 2023-02-13 2022-12-16 2023-02-13 2023-01-17 2023-03-08 2023-01-27 2023-01-31 2023-06-30 Disruptive Impacts nvelope dents and teachers under Dis tance Learning initiatives of MOFEPT. PK-MOFEPT-327311-GO-RFB / Hiring of a firm to provide e Component 2. Mitigation of Single Stage - One E IDA / 65900 Prior Request for Bids Open - National 1,700,000.00 0.00 Canceled 2022-12-05 2023-03-10 2022-12-09 2023-04-03 2023-01-10 2023-04-17 2023-01-20 2023-01-31 2023-06-30 nd-to-end implementation of Disruptive Impacts nvelope "School on Wheels" activity. PK-MOFEPT-330116-GO-RFB / Establishment of 400 Smart Component 3. Implementati Classrooms in selected instit Single Stage - One E Under Imple IDA / 65900 on Management and Monitor Post Request for Bids Open - National 1,250,000.00 0.00 2022-12-16 2023-02-21 2022-12-19 2023-01-18 2023-04-10 2023-01-27 2023-05-08 2023-01-31 2023-06-30 utions of Islamabad Capital T nvelope mentation ing and Evaluation erritory (ICT), Azad, Jammu & Kashmir (AJK) and Gilgit-Balti stan (GB). PK-MOFEPT-330115-GO-RFB / Establishment of Virtual Tea Component 3. Implementati Single Stage - One E cher training platform for tea IDA / 65900 on Management and Monitor Post Request for Bids Open - National 975,000.00 0.00 Canceled 2022-12-15 2022-12-21 2023-01-20 2023-01-27 2023-01-31 2023-06-30 nvelope chers including development ing and Evaluation of a dedicated Mobile App an d Website PK-MOFEPT-332164-GO-DIR / Hiring of "PTCL" for develop ment of a dedicated Mobile A Component 3. Implementati Under Imple pp and Website as an e-learn IDA / 65900 on Management and Monitor Post Direct Selection Direct - National 650,000.00 0.00 2022-12-26 2023-01-20 2022-12-30 2023-03-06 2023-01-13 2023-06-30 mentation ing solution for teachers and ing and Evaluation students including Virtual Te acher training (VTT) platform and LMS. PK-MOFEPT-332166-GO-RFB Component 3. Implementati / Sourcing of Teachers' Traini Single Stage - One E Under Imple IDA / 65900 on Management and Monitor Post Request for Bids Open - National 190,000.00 0.00 2022-12-30 2023-02-16 2023-01-05 2023-01-26 2023-03-07 2023-02-10 2023-02-20 2023-05-31 ng Content for Virtual Teache nvelope mentation ing and Evaluation rs' Training (VTT) module PK-MOFEPT-335516-GO-RFQ Component 4. Contingent E / Refurbishment of Two Existi Request for Quota Single Stage - One E IDA / 65900 mergency Response Compo Post Open - National 65,000.00 0.00 Signed 2023-01-12 2023-02-01 2023-03-10 ng Buses at Federal Director tions nvelope nent ate of Education for Conversi on into Mobile Schools. PK-MOFEPT-344018-GO-RFB / Procurement of Distance Le Component 2. Mitigation of Single Stage - One E IDA / 65900 Prior Request for Bids Open - National 1,806,000.00 0.00 Canceled 2023-02-20 2023-02-23 2023-03-14 2023-03-21 2023-03-27 2023-06-30 arning Content for Grade KG Disruptive Impacts nvelope to Grade 12 under PREP. PK-MOFEPT-349937-GO-RFB / Procurement and Developm Component 2. Mitigation of Single Stage - One E Under Imple IDA / 65900 Prior Request for Bids Open - National 1,806,000.00 0.00 2023-03-17 2023-04-07 2023-03-21 2023-04-09 2023-04-11 2023-04-17 2023-04-21 2023-06-30 ent of Distance Learning Con Disruptive Impacts nvelope mentation tent for Grades KG-12 under PREP. PK-MOFEPT-355504-GO-RFB / Establishment of Television Channels on Turnkey Basis w ith Provisioning and Commiss Component 2. Mitigation of Single Stage - One E IDA / 65900 Prior Request for Bids Open - National 5,000,000.00 0.00 Canceled 2023-04-11 2023-04-17 2023-04-13 2023-04-17 2023-04-28 2023-05-04 2023-05-03 2023-05-08 2023-06-30 ioning of Hardware, Software Disruptive Impacts nvelope and Installation of All the Req uired Equipment, Accessories , Electrical & Access Controls at Allama Iqbal Open Univers ity (AIOU) PK-MOFEPT-362836-GO-DIR / Procurement of Chromeboo Component 2. Mitigation of Direct - Internation IDA / 65900 Prior Direct Selection 2,750,000.00 0.00 Canceled 2023-05-22 2023-05-28 2023-05-23 2023-06-01 2023-05-29 2023-06-30 ks for Supplies at School Lev Disruptive Impacts al el across Pakistan. PK-MOFEPT-366470-GO-RFB Component 4. Contingent E / Procurement of LED Screen Single Stage - One E Under Revie IDA / 65900 mergency Response Compo Prior Request for Bids Limited 2,666,667.00 0.00 2023-06-10 2023-06-13 2023-06-11 2023-06-16 2023-06-19 2023-06-20 2023-06-30 s for Federal Directorate of E nvelope w nent ducation (FDE) Schools PK-MOFEPT-366476-GO-RFB Component 4. Contingent E / Procurement of Laptops (lot Single Stage - One E Under Revie IDA / 65900 mergency Response Compo Prior Request for Bids Limited 3,312,781.00 0.00 2023-06-10 2023-06-13 2023-06-11 2023-06-16 2023-06-19 2023-06-20 2023-06-30 -1), Desktops (lot-2) and Clic nvelope w nent kers(lot-3) for FDE schools. Page 1 NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PK-MOFEPT-326600-NC-RFB / Hiring of a Survey Firm for Component 2. Mitigation of Single Stage - One E IDA / 65900 Post Request for Bids Open - National 264,000.00 0.00 Signed 2022-11-21 2022-11-15 2022-11-21 2022-12-07 2022-12-07 2022-12-12 2023-01-04 2022-12-15 2023-03-31 Administration of Summative Disruptive Impacts nvelope Testing and Surveys in KPK P ublic Schools PK-MOFEPT-329384-NC-DIR / Component 4. Contingent E Engagement with PTV for Tra IDA / 65900 mergency Response Compo Post Direct Selection Direct - National 850,000.00 0.00 Signed 2022-12-01 2022-12-01 2022-12-02 2022-11-30 2022-12-05 2023-06-30 nsmission of "Tele School" nent PK-MOFEPT-344017-NC-RFQ Component 3. Implementati / Hiring of a firm to run a ded Request for Quota Single Stage - One E IDA / 65900 on Management and Monitor Post Open - National 74,600.00 0.00 Signed 2023-02-21 2023-02-28 2023-03-31 icated communication campa tions nvelope ing and Evaluation ign for launch of MoFEPT's Te leschool App. PK-MOFEPT-357389-NC-RFQ Component 3. Implementati Request for Quota Single Stage - One E / Communication & Dissemin IDA / 65900 on Management and Monitor Post Open - National 67,685.00 0.00 Signed 2023-05-02 2023-05-15 2023-06-30 tions nvelope ation Campaign under PREP. ing and Evaluation PK-MOFEPT-363615-NC-RFQ / Hiring of fIrm to provide logi Component 3. Implementati Request for Quota Single Stage - One E Under Imple stics, event management an IDA / 65900 on Management and Monitor Post Open - National 80,000.00 0.00 2023-05-26 2023-06-08 2023-06-30 tions nvelope mentation d communications services f ing and Evaluation or the "National Learning Co nference" CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PK-MOFEPT-325096-CS-CQS / Hiring of firm to supervise s Component 2. Mitigation of Consultant Qualifi ourcing and installation of rel IDA / 65900 Post Open - National 225,000.00 0.00 Signed 2022-11-04 2022-11-04 2022-11-24 2022-12-05 2022-12-15 2022-12-12 2023-01-04 2022-12-17 2023-06-30 Disruptive Impacts cation Selection evant equipment and facilitie s at AIOU for running 04 dedi cated channels. PK-MOFEPT-326076-CS-QCB Component 1. Emergency C S / Communications and Outr Quality And Cost- IDA / 65900 OVID-19 Preparedness and R Prior Open - National 1,650,000.00 0.00 Canceled 2022-11-11 2022-11-16 2022-11-30 2022-12-12 2023-04-06 2023-01-11 2023-03-27 2023-01-20 2023-04-12 2023-01-30 2023-01-31 2023-06-30 each Campaign under Pande Based Selection esponse mic Response Effectiveness P roject (PREP). PK-MOFEPT-326940-CS-CQS / Hiring of Consulting Service Component 3. Implementati Consultant Qualifi s for "Rapid Assessment and IDA / 65900 on Management and Monitor Post Open - National 60,000.00 0.00 Canceled 2022-12-05 2022-12-23 2023-01-06 2023-01-12 2023-01-16 2023-06-30 cation Selection Mapping" to provide learning ing and Evaluation about MoFEPT learning conti nuation activities PK-MOFEPT-326943-CS-QCB S / Procurement and develop Component 2. Mitigation of Quality And Cost- IDA / 65900 Prior Open - National 1,806,000.00 0.00 Canceled 2022-12-05 2022-12-23 2023-01-07 2023-02-07 2023-02-15 2023-02-23 2023-02-26 2023-06-30 ment of distance learning co Disruptive Impacts Based Selection ntent for Grade KG-Grade 12 under PREP. PK-MOFEPT-300484-CS-LCS / Hiring of firm to supervise so Component 2. Mitigation of Least Cost Selecti IDA / 65900 Post Open - National 225,000.00 0.00 Canceled 2022-09-15 2022-09-16 2022-10-06 2022-10-14 2022-10-17 2022-10-17 2022-10-17 2022-10-21 2023-06-30 urcing and installation of rele Disruptive Impacts on vant equipment and facilities at AIOU. INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PK-MOFEPT-316197-CS-CDS / HIRING OF ALLAMA IQBAL O Component 3. Implementati PEN UNIVERSIT (AIOU) FOR S IDA / 65900 on Management and Monitor Post Direct Selection Direct - National 300,000.00 0.00 Signed 2022-09-16 2022-08-17 2022-09-21 2022-08-10 2022-09-27 2023-06-30 USTAINIBILITY OF DISTANCE ing and Evaluation LEARNING INITIATIVES INCLU DING TELE-SCHOOL. PK-MOFEPT-300488-CS-INDV Component 1. Emergency C Individual Consult IDA / 65900 Post Open 66,000.00 0.00 Canceled 2022-06-24 2022-07-01 2022-07-26 2022-07-28 2022-08-01 2023-06-30 / Hiring of "Project Director" OVID-19 Preparedness and R ant Selection esponse PK-MOFEPT-335676-CS-INDV Component 3. Implementati / Hiring of "Project Coordinati Individual Consult Under Implement IDA / 65900 on Management and Monitor Post Open - National 26,500.00 0.00 2023-01-12 2023-01-18 2023-01-27 2023-02-03 2023-01-30 2023-02-07 2023-01-31 2023-06-30 on Consultant" for Program C ant Selection ation ing and Evaluation oordination Unit, M/o FE & PT . Page 2 PROCUREMENT PLAN (Textual Part) Project information: Ethiopia, Desert Locust Response Project, P173702 Project Implementation agency: Ministry of Agriculture, Ethiopia Date of the Procurement Plan: April 6, 2012 Period covered by this Procurement Plan: April 2020 to March 2021 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016, revised November 2017 and August 2018) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the Procurement Directives of the Federal and Regional Governments of Ethiopia, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. For national open competitive procurement the following requirement apply: a. open advertising of the procurement opportunity at the national level; b. the procurement is open to eligible firms from any country; c. the request for bids/request for proposals document shall require that Bidders/Proposers submitting Bids/Proposals present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights; d. Procurement Documents include provisions, as agreed with the Bank, intended to adequately mitigate against environmental, social (including sexual exploitation and abuse and gender-based violence), health and safety (“ESHS”) risks and impacts; e. contracts with an appropriate allocation of responsibilities, risks, and liabilities; f. publication of contract award information; g. rights for the Bank to review procurement documentation and activities; h. an effective complaints mechanism; and i. maintenance of records of the Procurement Process. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. Not Applicable Procurement of Secondhand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables Not Applicable For national open competitive procurement the following requirement apply: a. open advertising of the procurement opportunity at the national level; b. the procurement is open to eligible firms from any country; c. the request for bids/request for proposals document shall require that Bidders/Proposers submitting Bids/Proposals present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights; d. Procurement Documents include provisions, as agreed with the Bank, intended to adequately mitigate against environmental, social (including sexual exploitation and abuse and gender-based violence), health and safety (“ESHS”) risks and impacts; e. contracts with an appropriate allocation of responsibilities, risks, and liabilities; f. publication of contract award information; g. rights for the Bank to review procurement documentation and activities; h. an effective complaints mechanism; and i. maintenance of records of the Procurement Process. cable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Not Applicable Goods: [is not applicable/is applicable for those contracts identified in the Procurement Plan tables]; Works: [is not applicable/is applicable for those contracts identified in the Procurement Plan tables] Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations is Applicable. Other Relevant Procurement Information. Since the project is an emergency response project the provisions of Procurement in Situations of Urgent Need of Assistance shall apply. PROCUREMENT Eastern and Southern Africa : Emergency Locust Response Program PLAN General Information Country: Eastern and Southern Africa 2020-05-11 Bank’s Approval Date of the Original Procurement Plan: 2023-06-07 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P173702 GPN Date: 2020-12-03 Project Name: Emergency Locust Response Program Loan / Credit No: IDA / 66480, IDA / 66510, IDA / D6360 Ministry of Agriculture Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Request for Quota ET-MOA-325738-NC-RFQ / R Surveillance and Control Me Request for Quota Single Stage - One E tions - Small Work Pending Imp 2023-06-0 IDA / 66510 Post Limited 200,000.00 0.00 2023-03-23 2023-04-19 enovation of chemical store asures tions nvelope s (Emergency) SP lementation 3 D -Competitive GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ET-MOA-172079-GO-DIR / Fi Coordination and Early Warn IDA / 66480 Post Direct Selection Direct 450,000.00 1,056,832.73 Completed 2020-05-08 2020-07-10 2020-05-13 2020-05-27 2020-05-27 2020-08-18 2020-06-16 2021-12-25 eld Vehicles (Pickups) ing Preparedness ET-MOA-178452-GO-DIR / A Livelihoods Protection and R mhara feed purchase 318 qtl IDA / 66510 Post Direct Selection Direct 143,100.00 0.00 Canceled 2020-06-15 2020-06-20 2020-07-25 2020-07-30 ehabilitation s from Amhara Seed Enterpri se ET-MOA-184656-GO-DIR / Eq uipment for Desert Locust Re Surveillance and Control Me Under Revie IDA / 66510 Prior Direct Selection Direct 7,800,000.00 0.00 2020-07-19 2020-07-24 2020-08-12 2020-08-27 sponse Project (Knapsacks U asures w LV sprayers, PPE, Vehicle mo unted sprayers) ET-MOA-242623-GO-RFQ / A Livelihoods Protection and R Request for Quota Single Stage - One E Pending Impl IDA / 66510 Post Limited 143,100.00 0.00 2021-07-17 2021-08-14 2021-09-04 mhara Region, Seed for Anim ehabilitation tions nvelope ementation al Feed ET-MOA-248518-GO-RFQ / P Livelihoods Protection and R Request for Quota Single Stage - One E Pending Impl urchase of animal feed seed IDA / 66510 Post Limited 130,000.00 0.00 2021-08-30 2021-10-04 2021-11-03 ehabilitation tions nvelope ementation (Alfalfa and Sudan grass) ET-MOA-184728-GO-DIR / Dr Surveillance and Control Me Pending Impl IDA / 66510 Post Direct Selection Direct 50,000.00 0.00 2022-02-14 2022-02-19 2022-03-15 2022-03-28 ones for survey asures ementation ET-MOA-175937-GO-RFQ / Af Livelihoods Protection and R Pending Impl ar purchase of fertilizer 3088 IDA / 66510 Post Direct Selection Direct 200,720.00 0.00 2022-02-14 2022-02-19 2022-03-26 2022-04-03 ehabilitation ementation Qtl from EARC ET-MOA-175930-GO-RFQ / A mhara procurement of fertiliz Livelihoods Protection and R Pending Impl IDA / 66510 Post Direct Selection Direct 746,200.00 0.00 2022-02-14 2022-02-19 2022-03-26 2022-04-04 er 11480 Qtl from Amhara Se ehabilitation ementation ed Enterprise (ASE) ET-MOA-178443-GO-DIR / 14 Livelihoods Protection and R Pending Impl 35 Qtls of seed from Amhara IDA / 66510 Post Direct Selection Direct 154,980.00 0.00 2022-02-14 2022-02-19 2022-03-26 2022-04-04 ehabilitation ementation Seed Enterprise (ASE) ET-MOA-175925-GO-RFQ / Ti Livelihoods Protection and R Pending Impl gray region procurement of f IDA / 66510 Prior Direct Selection Direct 3,685,240.00 0.00 2022-02-14 2022-02-19 2022-03-26 2022-04-04 ehabilitation ementation ertilizer 56696 Qtls from EAR C ET-MOA-178446-GO-DIR / Or Livelihoods Protection and R Pending Impl omia Seed purchase 2455 Qtl IDA / 66510 Post Direct Selection Direct 265,140.00 0.00 2022-02-14 2022-02-19 2022-03-26 2022-04-01 ehabilitation ementation s from Oromia Seed Enterpris e (OSE) ET-MOA-178447-GO-DIR / SN Livelihoods Protection and R Pending Impl NP seed purchase 304 Qtls fr IDA / 66510 Post Direct Selection Direct 32,832.00 0.00 2022-02-14 2022-02-19 2022-03-26 2022-03-31 ehabilitation ementation om Southern Seed Enterprise (SSE) ET-MOA-178440-GO-DIR / Ti Livelihoods Protection and R Pending Impl gray seed purchase 7087 Qtl IDA / 66510 Post Direct Selection Direct 765,396.00 0.00 2022-02-14 2022-02-19 2022-03-26 2022-09-22 ehabilitation ementation s of Seed from EARC ET-MOA-178448-GO-DIR / Af Livelihoods Protection and R Pending Impl IDA / 66510 Post Direct Selection Direct 41,688.00 0.00 2022-02-14 2022-02-19 2022-03-26 2022-04-03 ar seed purchase 386 Qtls fro ehabilitation ementation m EARC ET-MOA-178449-GO-DIR / So Livelihoods Protection and R mali seed purchase 7,815 Qtl IDA / 66510 Post Direct Selection Direct 844,020.00 600,365.32 Completed 2022-02-14 2020-09-11 2022-02-19 2020-09-17 2022-03-26 2020-10-27 2022-04-05 2021-06-05 ehabilitation s from EARC ET-MOA-178450-GO-DIR / D Livelihoods Protection and R Pending Impl IDA / 66510 Post Direct Selection Direct 20,844.00 0.00 2022-02-14 2022-02-19 2022-03-26 2022-04-01 D seed purchase 193 qtls fro ehabilitation ementation m EARC ET-MOA-178453-GO-DIR / Or Livelihoods Protection and R Pending Impl omia feed seed purchase 160 IDA / 66510 Post Direct Selection Direct 720,000.00 0.00 2022-02-14 2022-02-19 2022-03-26 2022-09-22 ehabilitation ementation 0 qtls from Oromia seed ente rprise ET-MOA-178454-GO-DIR / SN Livelihoods Protection and R Under Imple NP feed seeds purchase 125 IDA / 66510 Post Direct Selection Direct 562,500.00 0.00 2022-02-14 2022-02-19 2022-03-26 2022-04-03 ehabilitation mentation 0 qtls from Southern seed en terprise (SSE) ET-MOA-178456-GO-DIR / Af Livelihoods Protection and R Pending Impl ar feed seeds purchase 2500 IDA / 66510 Post Direct Selection Direct 1,125,000.00 0.00 2022-02-14 2022-02-19 2022-03-26 2022-04-03 ehabilitation ementation qtls from EARC ET-MOA-178467-GO-DIR / So Livelihoods Protection and R Pending Impl IDA / 66510 Post Direct Selection Direct 1,080,000.00 0.00 2022-02-14 2022-02-19 2022-03-26 2022-04-03 mali feed seeds 2400 Qtls fro ehabilitation ementation m EARC ET-MOA-178468-GO-DIR / D Livelihoods Protection and R Pending Impl IDA / 66510 Post Direct Selection Direct 90,000.00 0.00 2022-02-14 2022-02-19 2022-03-26 2022-04-04 D feed seeds 200 qtls from E ehabilitation ementation ARC Page 1 ET-MOA-175934-GO-RFQ / D Livelihoods Protection and R Pending Impl IDA / 66510 Post Direct Selection Direct 100,360.00 0.00 2022-02-14 2022-02-19 2022-03-26 2022-04-04 D purchase of fertilizer 1544 ehabilitation ementation Qtl ET-MOA-175933-GO-RFQ / S Livelihoods Protection and R Under Imple IDA / 66510 Prior Direct Selection Direct 4,063,800.00 0.00 2022-02-11 2022-06-16 2022-02-16 2022-06-29 2022-03-23 2022-04-01 omali purchase of fertilizer 6 ehabilitation mentation 2520 Qtl ET-MOA-277931-GO-RFQ / O Livelihoods Protection and R Request for Quota Single Stage - One E Pending Impl IDA / 66510 Prior Limited 2,782,000.00 0.00 2022-02-21 2022-04-18 2022-05-18 romia purchase of improved ehabilitation tions nvelope ementation seeds ET-MOA-277932-GO-DIR / Or omia- purchase of fertilizers f Livelihoods Protection and R Pending Impl IDA / 66510 Prior Direct Selection Direct 1,737,000.00 0.00 2022-02-16 2022-02-21 2022-03-28 2022-04-27 rom Ethiopian agricultural Bu ehabilitation ementation siness Corporation (EABC) ET-MOA-277933-GO-DIR / Af Livelihoods Protection and R Pending Impl ar- Purchase of fertilizers fro IDA / 66510 Post Direct Selection Direct 363,500.00 0.00 2022-02-15 2022-02-20 2022-03-27 2022-04-17 ehabilitation ementation m Ethiopian Agricultural Busi ness Corporation ET-MOA-277936-GO-RFQ / Af Livelihoods Protection and R Request for Quota Single Stage - One E Pending Impl IDA / 66510 Post Limited 244,500.00 0.00 2022-02-21 2022-04-18 2022-05-18 ar- Purchase of improved see ehabilitation tions nvelope ementation ds ET-MOA-277940-GO-RFQ / S Livelihoods Protection and R Request for Quota Single Stage - One E Pending Impl IDA / 66510 Post Limited 422,000.00 0.00 2022-02-21 2022-04-18 2022-05-09 NNP- Purchase of improved s ehabilitation tions nvelope ementation eeds ET-MOA-277943-GO-RFQ / S Livelihoods Protection and R Request for Quota Single Stage - One E IDA / 66510 Post Limited 687,000.00 0.00 Canceled 2022-02-21 2022-04-18 2022-05-18 omali- Purchase of improved ehabilitation tions nvelope seeds ET-MOA-277951-GO-RFQ / S Livelihoods Protection and R Request for Quota Single Stage - One E Pending Impl IDA / 66510 Post Limited 808,000.00 0.00 2022-02-21 2022-04-18 2022-05-18 omali- purchase of forage se ehabilitation tions nvelope ementation eds ET-MOA-277958-GO-RFQ / Di Livelihoods Protection and R Request for Quota Single Stage - One E Pending Impl IDA / 66510 Post Limited 120,700.00 0.00 2022-02-20 2022-04-17 2022-05-17 redawa- purchase of improve ehabilitation tions nvelope ementation d seeds ET-MOA-277962-GO-DIR / SN NP- purchase of fertilizers fro Livelihoods Protection and R IDA / 66510 Post Direct Selection Direct 608,000.00 0.00 Canceled 2022-02-15 2022-02-20 2022-03-27 2022-04-26 m Ethiopian Agricultural Busi ehabilitation ness Corporation ET-MOA-277964-GO-DIR / So mali- purchase of Fertilizer fr Livelihoods Protection and R Pending Impl IDA / 66510 Post Direct Selection Direct 1,030,000.00 0.00 2022-02-16 2022-02-21 2022-03-28 2022-04-18 om Ethiopian Agricultural Bu ehabilitation ementation siness Corporation ET-MOA-277965-GO-DIR / A mhara- Purchase of fertilizers Livelihoods Protection and R Pending Impl IDA / 66510 Prior Direct Selection Direct 2,810,000.00 0.00 2022-02-16 2022-02-21 2022-03-28 2022-04-27 from Ethiopian Agricultural B ehabilitation ementation usiness Corporation ET-MOA-277969-GO-DIR / Di Livelihoods Protection and R Pending Impl redawa- purchase of fertilizer IDA / 66510 Post Direct Selection Direct 182,300.00 0.00 2022-02-16 2022-02-21 2022-03-28 2022-09-24 ehabilitation ementation s from EABC ET-MOA-277971-GO-DIR / Ha Livelihoods Protection and R Pending Impl IDA / 66510 Post Direct Selection Direct 91,500.00 0.00 2022-02-16 2022-02-21 2022-03-28 2022-04-27 rar purchase of fertilizer from ehabilitation ementation EABC ET-MOA-277974-GO-RFQ / H Livelihoods Protection and R Request for Quota Single Stage - One E Pending Impl IDA / 66510 Post Limited 60,400.00 0.00 2022-02-20 2022-04-17 2022-05-08 arar purchase of improved se ehabilitation tions nvelope ementation eds ET-MOA-286684-GO-DIR / pu Livelihoods Protection and R Pending Impl rchase of improved seeds fro IDA / 66510 Post Direct Selection Direct 687,000.00 0.00 2022-03-25 2022-03-30 2022-04-13 2022-04-28 ehabilitation ementation m Somali Seed Enterprise ET-MOA-308951-GO-RFQ / S Livelihoods Protection and R Single Stage - One E IDA / 66510 Post Request for Bids Open - National 608,000.00 0.00 Canceled 2022-08-18 2022-08-23 2022-09-07 2022-09-22 2022-10-13 2022-10-27 NNP Purchase of seeds ehabilitation nvelope ET-MOA-313528-GO-RFQ / T Livelihoods Protection and R Request for Quota Single Stage - One E Under Imple IDA / 66510 Post Limited 390,000.00 0.00 2022-09-11 2022-08-30 2022-10-09 2022-11-08 eff Seed for SNNP woredas ehabilitation tions nvelope mentation ET-MOA-313530-GO-RFQ / S Livelihoods Protection and R Request for Quota Single Stage - One E Pending Impl IDA / 66510 Post Limited 212,000.00 0.00 2022-09-12 2022-10-10 2022-11-09 weet potato seed ehabilitation tions nvelope ementation ET-MOA-318810-GO-RFQ / U Coordination and Early Warn Request for Quota Single Stage - One E Pending Impl IDA / 66510 Post Limited 90,000.00 0.00 2022-10-08 2022-12-03 2023-01-02 niforms for scouts ing Preparedness tions nvelope ementation ET-MOA-318811-GO-RFQ / la Request for Quota Single Stage - One E Pending Impl IDA / 66510 Project Management Post Limited 17,500.00 0.00 2022-10-09 2022-12-04 2023-01-03 ptop computers tions nvelope ementation ET-MOA-323079-GO-DIR / A Livelihoods Protection and R Pending Impl IDA / 66510 Post Direct Selection Direct - National 260,000.00 0.00 2022-10-28 2022-11-02 2022-12-07 2022-12-21 mhara Fertilizer ehabilitation ementation ET-MOA-323073-GO-RFQ / A Livelihoods Protection and R Request for Quota Single Stage - One E Pending Impl IDA / 66510 Post Limited 1,000,000.00 0.00 2022-10-30 2022-12-25 2023-01-24 mhara wheat improved seed ehabilitation tions nvelope ementation s ET-MOA-323076-GO-RFQ / A Livelihoods Protection and R Request for Quota Single Stage - One E Pending Impl IDA / 66510 Post Limited 380,000.00 0.00 2022-11-01 2022-12-27 2023-01-26 mhara Masho improved seed ehabilitation tions nvelope ementation s ET-MOA-323075-GO-RFQ / A Livelihoods Protection and R Request for Quota Single Stage - One E Pending Impl IDA / 66510 Post Limited 280,000.00 0.00 2022-11-01 2022-12-27 2023-01-26 mhara Sorghum improved se ehabilitation tions nvelope ementation eds ET-MOA-323074-GO-RFQ / A Livelihoods Protection and R Request for Quota Single Stage - One E Pending Impl IDA / 66510 Post Limited 600,000.00 0.00 2022-10-30 2022-12-25 2023-01-24 mhara Teff improved seeds ehabilitation tions nvelope ementation ET-MOA-325985-GO-DIR / Fe Livelihoods Protection and R IDA / 66510 Post Direct Selection Direct - National 490,000.00 0.00 Signed 2022-11-14 2022-10-24 2022-11-19 2022-12-12 2022-12-24 2023-01-23 rtilizer ehabilitation ET-MOA-325961-GO-RFQ / i Livelihoods Protection and R Request for Quota Single Stage - One E Pending Impl IDA / 66510 Post Limited 560,226.00 0.00 2022-11-19 2023-01-14 2023-02-13 mproved wheat seed ehabilitation tions nvelope ementation ET-MOA-325964-GO-RFQ / F Livelihoods Protection and R Request for Quota Single Stage - One E Pending Impl IDA / 66510 Post Limited 94,339.00 0.00 2022-11-19 2023-01-14 2023-02-13 orage seeds ehabilitation tions nvelope ementation ET-MOA-325966-GO-RFQ / Di Livelihoods Protection and R Request for Quota Single Stage - One E Pending Impl IDA / 66510 Post Limited 12,075.00 0.00 2022-11-20 2023-01-15 2023-02-14 redawa Forage seed ehabilitation tions nvelope ementation Page 2 ET-MOA-325982-GO-DIR / Di Livelihoods Protection and R Pending Impl IDA / 66510 Post Direct Selection Direct - National 16,982.00 0.00 2022-11-15 2022-11-20 2022-12-25 2023-01-24 redawa procurement of Fert ehabilitation ementation ilizer ET-MOA-325983-GO-RFQ / Di Livelihoods Protection and R Request for Quota Single Stage - One E Pending Impl IDA / 66510 Post Limited 44,889.00 0.00 2022-11-23 2023-01-18 2023-02-17 redawa procurement of cere ehabilitation tions nvelope ementation als ET-MOA-328808-GO-RFQ / S Livelihoods Protection and R Request for Quota Single Stage - One E Pending Impl IDA / 66510 Post Limited 483,411.00 0.00 2022-12-05 2023-01-23 2023-02-22 omali improved seed (Maize ) ehabilitation tions nvelope ementation ET-MOA-328809-GO-RFQ / s Livelihoods Protection and R Request for Quota Single Stage - One E Pending Impl IDA / 66510 Post Limited 225,236.00 0.00 2022-12-05 2023-01-30 2023-03-01 omali improved forage seed ehabilitation tions nvelope ementation ET-MOA-328817-GO-RFQ / Af Livelihoods Protection and R Request for Quota Single Stage - One E Pending Impl IDA / 66510 Post Limited 135,406.00 0.00 2022-12-04 2023-01-29 2023-02-28 rar procurement of cereals ehabilitation tions nvelope ementation ET-MOA-328823-GO-RFQ / Af Livelihoods Protection and R Request for Quota Single Stage - One E IDA / 66510 Post Limited 94,340.00 0.00 Signed 2022-12-05 2022-12-06 2023-01-30 2023-03-01 ar improved forage seeds ehabilitation tions nvelope ET-MOA-328826-GO-DIR / pr Livelihoods Protection and R Pending Impl IDA / 66510 Post Direct Selection Direct - National 66,037.00 0.00 2022-11-30 2022-12-05 2023-01-09 2023-02-08 ocurement of fertilizer ehabilitation ementation ET-MOA-328842-GO-RFQ / or Livelihoods Protection and R Request for Quota Single Stage - One E Pending Impl IDA / 66510 Post Limited 463,393.00 0.00 2022-12-04 2023-01-29 2023-02-28 omia improved forage seed ehabilitation tions nvelope ementation ET-MOA-328849-GO-DIR / Or Livelihoods Protection and R Pending Impl omia -procurement of Fertili IDA / 66510 Post Direct Selection Direct - National 686,788.00 0.00 2022-11-29 2022-12-04 2023-01-08 2023-02-07 ehabilitation ementation zer (NPS ,UREA) ET-MOA-328854-GO-RFQ / O Livelihoods Protection and R Request for Quota Single Stage - One E Pending Impl IDA / 66510 Post Limited 351,696.00 0.00 2022-12-05 2023-01-30 2023-03-01 romia procurement of impro ehabilitation tions nvelope ementation ved seed ET-MOA-333773-GO-RFQ / H Livelihoods Protection and R Request for Quota Single Stage - One E Pending Impl IDA / 66510 Post Limited 27,158.21 0.00 2023-01-04 2023-03-01 2023-03-31 arari -Forage seeds ehabilitation tions nvelope ementation ET-MOA-333776-GO-DIR / Ha Livelihoods Protection and R Pending Impl IDA / 66510 Post Direct Selection Direct - National 19,622.00 0.00 2022-12-29 2023-01-03 2023-02-07 2023-03-09 rari - procurement of fertilize ehabilitation ementation r ET-MOA-333777-GO-RFQ / H Livelihoods Protection and R Request for Quota Single Stage - One E Pending Impl IDA / 66510 Post Limited 27,164.00 0.00 2023-01-04 2023-03-01 2023-03-31 arari procurement of seeds ehabilitation tions nvelope ementation ET-MOA-333831-GO-RFQ / s Surveillance and Control Me Request for Quota Single Stage - One E Under Imple upply installation of electric b IDA / 66510 Post Limited 48,000.00 0.00 2023-01-04 2023-03-01 2023-03-31 asures tions nvelope mentation oard for data centre ET-MOA-335504-GO-RFQ / E Request for Quota Single Stage - One E quipment for DL Communicat IDA / 66510 Project Management Post Limited 78,200.00 0.00 Signed 2023-01-18 2023-01-18 2023-03-15 2023-04-14 tions nvelope ion (Audio Visual ) ET-MOA-311252-GO-RFB / E Coordination and Early Warn Request for Quota Single Stage - One E quipment for networking and IDA / 66510 Prior Limited 2,000,000.00 0.00 Canceled 2022-09-04 2022-10-16 2022-11-15 ing Preparedness tions nvelope Software management ET-MOA-337956-GO-RFB / E Coordination and Early Warn Open - Internationa Single Stage - One E Under Imple quipment for Networking and IDA / 66510 Prior Request for Bids 2,000,000.00 0.00 2023-01-27 2023-04-04 2023-02-01 2023-04-11 2023-03-15 2023-04-04 2023-04-21 2023-06-20 ing Preparedness l nvelope mentation software Management ET-MOA-175931-GO-RFQ / O Livelihoods Protection and R romia purchase of fertilizer 1 IDA / 66510 Post Direct Selection Direct 1,276,600.00 0.00 Canceled 2022-02-14 2022-02-19 2022-03-26 2022-04-01 ehabilitation 9640 Qtl from Oromia Seed E nterprise (OSE) ET-MOA-175932-GO-RFQ / S Livelihoods Protection and R NNP purchase of fertilizer 24 IDA / 66510 Post Direct Selection Direct 158,080.00 0.00 Canceled 2022-02-14 2022-02-19 2022-03-26 2022-04-05 ehabilitation 32 Qtl from SSE ET-MOA-277955-GO-RFQ / A Livelihoods Protection and R Request for Quota Single Stage - One E IDA / 66510 Prior Limited 1,865,000.00 0.00 Canceled 2022-02-21 2022-04-18 2022-05-18 mhara- purchase of improve ehabilitation tions nvelope d seeds ET-MOA-348001-GO-RFQ / pr Livelihoods Protection and R Request for Quota Single Stage - One E Pending Impl IDA / 66510 Post Limited 160,000.00 0.00 2023-03-17 2023-05-12 2023-05-27 ocurement of Urea fertilizer ehabilitation tions nvelope ementation ET-MOA-349034-GO-RFQ / pr Request for Quota Single Stage - One E Pending Impl IDA / 66510 Project Management Post Limited 99,500.00 0.00 2023-03-21 2023-05-16 2023-06-25 ocurement of office furniture tions nvelope ementation ET-MOA-318812-GO-RFQ / E arth ranger and tableaus soft Surveillance and Control Me Request for Quota Single Stage - One E IDA / 66510 Post Limited 35,000.00 0.00 Canceled 2022-10-15 2022-12-10 2023-01-09 ware for data analysis and fie asures tions nvelope ld operation tracking ET-MOA-328848-GO-RFQ / O Livelihoods Protection and R Request for Quota Single Stage - One E IDA / 66510 Post Limited 100.00 0.00 Canceled 2022-12-05 2023-01-30 2023-03-01 romia improved seed ehabilitation tions nvelope ET-MOA-199303-GO-DIR / 20 Surveillance and Control Me IDA / 66510 Post Direct Selection Direct 700,000.00 0.00 Canceled 2022-02-14 2022-02-19 2022-03-26 2022-05-10 Agricultural sprayer Drones asures ET-MOA-353878-GO-RFQ / R Livelihoods Protection and R Request for Quota Single Stage - One E Pending Impl hodes grass, Panicum grass IDA / 66510 Post Limited 920,000.00 0.00 2023-04-08 2023-05-13 2023-06-27 ehabilitation tions nvelope ementation and Sudan grass seeds ET-MOA-353882-GO-RFQ / L Livelihoods Protection and R Request for Quota Single Stage - One E Pending Impl ukinia, Sesbania, Tree Lucere IDA / 66510 Post Limited 900,000.00 0.00 2023-04-08 2023-05-13 2023-06-27 ehabilitation tions nvelope ementation ne and pigeon pea seeds ET-MOA-364542-GO-RFQ / O Livelihoods Protection and R Pending Impl romia procurement of fertili IDA / 66510 Prior Direct Selection Direct - National 2,094,230.00 0.00 2023-06-05 2023-06-10 2023-07-08 2023-08-07 ehabilitation ementation zer ( urea and UPS) ET-MOA-364548-GO-RFQ / or Livelihoods Protection and R Single Stage - One E Under Imple IDA / 66510 Prior Request for Bids Open - National 2,879,741.00 0.00 2023-06-06 2023-06-11 2023-07-11 2023-07-21 2023-08-18 2023-09-20 omia procurement of improv ehabilitation nvelope mentation ed seed ET-MOA-364555-GO-RFB / A Livelihoods Protection and R Single Stage - One E Pending Impl IDA / 66510 Post Request for Bids Open - National 322,652.00 0.00 2023-06-07 2023-06-12 2023-07-12 2023-07-13 2023-08-04 2023-09-03 mhara procurement of forag ehabilitation nvelope ementation e seed ET-MOA-364601-GO-RFB / S Livelihoods Protection and R Single Stage - One E Pending Impl IDA / 66510 Post Request for Bids Open - National 246,000.00 0.00 2023-06-06 2023-06-11 2023-07-11 2023-07-19 2023-07-28 2023-08-27 NNP procurement of forage s ehabilitation nvelope ementation eeds Page 3 ET-MOA-365284-GO-RFQ / Pr Surveillance and Control Me Request for Quota Single Stage - One E Pending Impl ocurement of tablets for DL d IDA / 66510 Post Limited 30,000.00 0.00 2023-06-12 2023-08-07 2023-09-06 asures tions nvelope ementation ata collection NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ET-MOA-181756-NC-DIR / Le Surveillance and Control Me Under Revie ase of Aircraft sprayer (4 airc IDA / 66510 Prior Direct Selection 5,600,000.00 0.00 2020-07-07 2020-07-12 2020-07-25 2021-01-21 asures w rafts) from Zemen Flights ser vice ET-MOA-199304-NC-DIR / Le Surveillance and Control Me Under Revie IDA / 66510 Prior Direct Selection Direct 4,500,000.00 0.00 2020-10-15 2020-10-20 2020-11-24 2021-02-22 ase of sprayer air crafts asures w ET-MOA-236964-NC-RFQ / C harter service to transport ba Surveillance and Control Me Request for Quota Single Stage - One E IDA / 66510 Post Limited 390,000.00 385,000.00 Completed 2021-06-05 2021-05-25 2021-07-17 2021-05-27 2021-08-06 2021-06-01 ck to South Africa after servic asures tions nvelope e contract of the Helicopters is completed. ET-MOA-237036-NC-RFQ / Tr Livelihoods Protection and R Request for Quota Single Stage - One E Pending Impl ansport contract to deliver th IDA / 66510 Post Limited 150,000.00 0.00 2021-06-05 2021-07-10 2021-08-09 ehabilitation tions nvelope ementation e "improved seeds" for the Ti gray regions. ET-MOA-238897-NC-RFQ / Tr ansport service for 11,584 qu Livelihoods Protection and R Request for Quota Single Stage - One E Pending Impl IDA / 66510 Post Limited 150,000.00 0.00 2021-06-16 2021-07-06 2021-07-21 intals of seed from Mekelle to ehabilitation tions nvelope ementation various woredas in Tigray reg ion ET-MOA-279746-NC-RFQ / le Surveillance and Control Me Request for Quota Single Stage - One E IDA / 66510 Prior Limited 3,000,000.00 0.00 Canceled 2022-03-01 2022-04-26 2022-10-23 ase of DL spray aircrafts asures tions nvelope ET-MOA-199300-NC-DIR / Le Surveillance and Control Me Pending Impl IDA / 66510 Post Direct Selection Direct 315,000.00 0.00 2020-10-19 2020-10-24 2020-11-28 2021-01-12 ase of four sprayer drones asures ementation ET-MOA-289953-NC-DIR / Le Surveillance and Control Me IDA / 66510 Post Direct Selection Direct 1,490,000.00 0.00 Completed 2022-04-15 2022-04-21 2022-04-20 2022-04-21 2022-05-11 2022-09-08 2022-07-22 ase of Sprayer aircraft asures ET-MOA-255670-GO-RFQ / D ocumentation and publicatio Request for Quota Single Stage - One E IDA / 66510 Project Management Post Limited 60,000.00 0.00 Canceled 2022-02-16 2022-04-13 2022-06-12 n service of DL situation in Et tions nvelope hiopia from 2019-2021 ET-MOA-311259-NC-DIR / Thi Direct - Internation IDA / 66510 Project Management Post Direct Selection 1,400,000.00 0.00 Canceled 2022-09-05 2022-09-10 2022-10-08 2023-04-06 rd Party Implementer service al fee ET-MOA-322588-NC-DIR / Se Direct - Internation IDA / D6360 Project Management Prior Direct Selection 2,400,000.00 0.00 Signed 2022-10-26 2022-10-20 2022-10-31 2022-10-24 2022-12-05 2023-11-30 rvice of Third Party Impleme al nter ET-MOA-348005-GO-DIR / Pr Surveillance and Control Me Direct - Internation Pending Impl ocurement of earth range sof IDA / 66510 Post Direct Selection 35,000.00 0.00 2023-03-20 2023-03-25 2023-04-10 2023-05-20 asures al ementation tware license CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ET-MOA-325698-CS-LCS / co Surveillance and Control Me Least Cost Selecti nsultancy service for design IDA / 66510 Post Open - National 90,000.00 0.00 Under Review 2022-12-08 2023-06-27 2022-12-22 2023-01-01 2023-01-29 2023-02-05 2023-02-13 2023-02-23 2023-03-16 asures on and supervise of renovation of chemical store INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ET-MOA-197751-CS-INDV / E Individual Consult mployment of Communicatio IDA / 66510 Project Management Post Open 48,000.00 0.00 Canceled 2020-10-15 2020-11-23 2020-12-08 2021-01-07 2022-01-06 ant Selection n specialist ET-MOA-199298-CS-INDV / E Individual Consult mployment of data manage IDA / 66510 Project Management Post Open 48,000.00 0.00 Canceled 2020-10-16 2020-11-25 2020-12-09 2020-12-28 2021-12-27 ant Selection ment specialist ET-MOA-197753-CS-INDV / E Individual Consult mployment of Pest Managem IDA / 66510 Project Management Post Open 48,000.00 0.00 Canceled 2020-10-14 2020-11-22 2020-12-10 2020-12-30 2021-12-29 ant Selection ent Specialist ET-MOA-197752-CS-INDV / E Individual Consult mployment of Environmental IDA / 66510 Project Management Post Open 48,000.00 0.00 Canceled 2020-10-13 2020-11-22 2020-12-13 2021-01-05 2022-01-04 ant Selection and Social Safeguards Specia list ET-MOA-197750-CS-INDV / E Individual Consult mployment of Monitoring, Ev IDA / 66510 Project Management Post Open 48,000.00 0.00 Canceled 2020-10-18 2020-11-27 2020-12-11 2021-01-06 2022-01-05 ant Selection aluation and Learning (MEAL) specialist ET-MOA-264667-CS-INDV / R Individual Consult Under Implement ecruitment of Pest Managem IDA / 66510 Project Management Post Open 10,000.00 0.00 2021-11-23 2021-06-10 2022-01-11 2022-02-01 2022-03-08 2022-09-04 ant Selection ation ent specialist ET-MOA-264678-CS-INDV / R Individual Consult Under Implement IDA / 66510 Project Management Post Open 10,000.00 0.00 2021-11-26 2021-06-10 2021-12-22 2021-12-29 2022-01-26 2023-01-26 ecruitment of M & E Specialis ant Selection ation t ET-MOA-261441-CS-INDV / E Individual Consult Under Implement mployment of Communicatio IDA / 66510 Project Management Post Open 10,000.00 0.00 2021-11-25 2020-11-05 2021-12-28 2022-01-04 2022-02-08 2023-02-08 ant Selection ation n specialist Page 4 ET-MOA-264675-CS-INDV / r Individual Consult Under Implement ecruitment of Environmental IDA / 66510 Project Management Post Open 10,000.00 0.00 2021-11-25 2021-06-10 2021-12-28 2022-01-18 2022-02-22 2023-02-22 ant Selection ation Safeguard Specialist Page 5 PLAN DE PASSATION DE MARCHÉS Information sur le Projet : Emprunteur/Bénéficiaire République Togolaise Ministère Responsable Nom du Projet Identification P172769 Agence d’exécution du Projet : [A insérer] Date du plan de passation des marchés : [A indiquer] Période couverte par ce plan de passation des marchés : [A indiquer] Date d’approbation par la Banque du plan de passation de marchés : [A indiquer] Date de publication de l’Avis Général de Passation des Marchés : [A indiquer] Evaluation de risque par P-RAMS (Procurement Risk Assessment and Management System) : Elevé Préambule Conformément au paragraphe 5.9 du “Règlement de Passation des Marchés pour les Emprunteurs sollicitant le Financement de Projets d’Investissement (FPI)” (Novembre 2020) (“Règlement de Passation des Marchés”), le Système électronique de la Banque de suivi systématique des transactions de marchés publics (STEP) sera utilisé pour préparer, valider et actualiser les plans de passation des marchés et effectuer toutes les transactions liées à la passation des marchés du projet. Ce texte ainsi que les tableaux du plan de passation des marchés présents dans STEP constituent le plan de passation des marchés du projet. Les conditions suivantes s'appliquent à toutes les activités de passation de marchés du plan de passation de marchés. Les autres éléments du plan de passation des marchés tels que requis au paragraphe 4.4 du Règlement de passation des marchés sont énoncés dans STEP. Les Dossiers types de passation des marchés publics de la Banque devront être utilisés pour tous les contrats soumis à la concurrence internationale, ainsi que pour tous les autres contrats soumis à cette obligation telle que spécifiée dans les tableaux du plan de passation des marchés de STEP. Procédures nationales de passation des marchés : En accord avec le paragraphe 5.3 du Règlement de passation des marchés, dans le cas où la procédure de passation des marchés se fera au niveau national (telle que spécifiée dans les tableaux du plan de passation des marchés inclus dans STEP), les procédures nationales de passation des marchés du pays considéré pourront être utilisées. Si l’Emprunteur utilise ses propres procédures d’appel d’offres national ouvert telles qu’énoncées dans la loi No. 2009-013 du 30 juin 2009 relative aux Marchés Publics et Délégation de Service Public, le Décret Nº 2009-277/PR du 11 novembre 2009 portant Code des Marchés Publics et Délégation de Service Public, et les textes d’application y afférents, ces arrangements sont soumis aux dispositions du paragraphe 5.4 du Règlement de passation des marchés et aux conditions suivantes : - Le dossier d’appel d’offres/à propositions oblige le Soumissionnaire/les proposants présentant une Offre/Proposition à déposer un agrément signé, qui sera joint à tout contrat éventuel, pour confirmer qu’il applique et respecte les Directives de la Banque pour la lutte contre la corruption, y compris sans limitation, le droit de la Banque de sanctionner et les droits de la Banque pour l’inspection e l’audit ; - Le droit de la Banque d’examiner le dossier et les activités de passation des marchés. Lorsque l’Emprunteur utilise d’autres procédures que l’appel d’offres national ouvert, ces procédures devront être en accord avec les dispositions du paragraphe 5.5 du Règlement de passation des marchés. Crédit-bail tel que spécifié au paragraphe 5.10 du Règlement de Passation des marchés : Le crédit-bail peut être utilisé pour les contrats indiqués comme tel dans le Plan de passation des marchés. « Sans objet » Achat de biens d’occasion tel que spécifié au paragraphe 5.11 du Règlement de Passation des Marchés est autorisé pour les contrats indiqués comme tel dans le Plan de passation des marchés. « Sans objet » Préférence nationale telle que spécifiée au paragraphe 5.51 du Règlement de Passation des Marchés (Fournitures et Travaux). Fournitures : ne s’applique pas pour les contrats indiqués dans les tableaux du Plan de passation des marchés Travaux ne s’applique pas pour les contrats indiqués dans les tableaux du Plan de passation des marchés L’Assistance directe à la mise en œuvre (sigle HEIS en anglais) tel que précisée aux paragraphes 3.10 et 3.11 du Règlement de Passation des marchés ne s’applique pas. Autres informations pertinentes sur la passation des marchés : Néant I. TRAVAUX, FOURNITURES ET SERVICES AUTRES QUE LES SERVICES DE CONSULTANTS 1. Dispositions relatives aux seuils de revue préalable : Seuils requis pour les décisions de marchés soumis à la revue préalable de la Banque, tel que prévu dans les paragraphes 3.5 à 3.8 de la Section III, et de l’Annexe II du Règlement de Passation des Marchés pour les Emprunteurs sollicitant le Financement de Projets d’Investissement (FPI), en date de Juillet 2016, révisé en Novembre 2017. Catégories de marchés Montants Observations estimatifs des contrats en millions de dollars américains Travaux (incluant clé à main, Fourniture et Installation, et les >= 5 Partenariat Public - Privé -PPP) Biens, Système d’Information et de Services autres que les >= 1,5 Services intellectuels Contrats à Travaux passer par (incluant clé à >= 5 entente main, directe Fourniture et Les justifications de Installation, et l’entente directe les Partenariat devront être jointes et Public - Privé - approuvées avec PPM PPP) Biens, Système d’Information et de Services >= 1,5 autres que les Services intellectuels 2. Seuils pour les méthodes de passation des marchés : Les seuils de passation des marchés se présentent comme suit au vu des conditions du marché : FOURNITURES ET SERVICES AUTRE QUE LES SERVICES DE CONSULTANTS TRAVAUX (US$ équivalent) (US$ équivalent) AOI AON DC AOI AON DC < < 100.000 ≥5.000.000 <5.000.000 200.00 ≥500.000 <500.000 0 3. Dispositions spéciales sur les marchés : Concernant les acquisitions de véhicules et de carburant, en fonction des circonstances et des besoins spécifiques du pays, le seuil pour la consultation de fournisseurs pourrait être porté à la contre-valeur d’USD 500,000 (en prenant soin de consulter tous les principaux concessionnaires de marque ou distributeurs de produits pétroliers). Liste de Marchés de Travaux, Fournitures, et Services autres que Consultant Date Type Méthode/ Montan de Comme d'Exa Modalité Appro t lance ntaire Réf. DESCRIP men de che de Estimat ment /Fin de No. TION par la passatio march if en de la prestat Banqu n des és US$ procé ions e marchés dure II. SÉLECTION DES CONSULTANTS 1. Dispositions relatives aux seuils de revue préalable des marchés : Décisions de sélection sujette à la revue préalable de la Banque comme indiqué dans Seuils requis pour les décisions de marchés soumis à la revue préalable de la Banque, tel que prévu dans les paragraphes 3.5 à 3.8 de la Section III, et de l’Annexe II du Règlement de Passation des Marchés pour les Emprunteurs sollicitant le Financement de Projets d’Investissement (FPI), en date de Novembre 2020. Méthode de Seuils de revue a priori Observations sélection/Catégories de Montants estimatifs des marchés contrats en millions de dollars américains Méthode compétitive/Firmes de >= 0.5 consultants Entente directe/firmes de Les justifications pour consultants >= 0.5 l’entente directe devront être jointes et approuvées Entente avec le PPM directe/Consultants >= 0.2 individuel Méthode Compétitive >= 0.2 (Comparaison de CVs)/ Consultants individuels 2. Liste restreinte composée entièrement de firmes nationales: La liste restreinte de consultants pour les prestations d’études d’ingénierie, de contrôle et de surveillance estimées à moins de 300,000 US$ par contrat, et pour tout autre type de prestations, estimées à moins de 100 000 US$ par contrat, peut comporter entièrement de consultants nationaux en conformité avec les dispositions des Règlements de Passation des marchés., et l’Emprunteur ne procède pas à une publication dans UNDB 3. Autre arrangement spécial de Sélection de consultants : Le seuil pour l’utilisation de la méthode de sélection de consultant fondée sur les qualifications des consultants est déterminé au cas par cas en tenant compte de la nature et de la complexité de la mission ; cependant, ce seuil ne devrait pas dépasser la contre-valeur de USD 300,000 sauf dans des cas exceptionnels telles des situations d’urgence en conformité au Règlement de Passation des marchés II- Liste de Marchés de Services de Consultants Date Méthod Comm Montan Type de Ré e de entair t d'Exam Approch lancem f. DESCRIPTION passati e/Fin Estimat en par e de ent de No DES MISSIONS on des des if en la Marché la . marché presta US$ Banque procéd s tions ure Lexique des Sigles et Abréviations ARMP Autorité de Régulation des Marchés Publics AOI Appel d’Offres International AON Appel d’Offres National A Revue a posteriori posteriori A Priori Revue a priori CI Consultant Individuel DC Demande de Cotations DNCMP Direction Nationale de Contrôle des Marchés Publics ED Sélection Directe ou Entente Directe PPM Plan de Passation des Marchés SFQ Sélection Fondée sur la Qualité SFQC Sélection Fondée sur la Qualité et le Coût SMC Sélection au Moindre Coût SQC Sélection fondée sur les Qualifications des Consultants PROCUREMENT Western and Central Africa : West Africa Food System Resilience Program (FSRP) PLAN General Information Country: Western and Central Africa 2022-08-08 Bank’s Approval Date of the Original Procurement Plan: 2023-06-01 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P172769 GPN Date: Project Name: West Africa Food System Resilience Program (FSRP) Loan / Credit No: IDA / D9220 COORDINATION OF WEST AFRICA FOOD SYSTEM RESILIENCE PROGRAM (TOGO) Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned National Procure TG-FSRP TOGO-306292-CW- ment Document - Request for Quota Single Stage - One E 2023-02-2 RFQ / Travaux de réhabilitati IDA / D9220 Project Management Post Limited 1 Envelope proce 54,545.00 0.00 Signed 2022-09-04 2022-09-13 2022-10-30 tions nvelope 7 on du bâtiment du projet FSR ss (Non Bank-SPD P-Togo ) National Procure TG-FSRP TOGO-315205-CW- Sustainability and adaptive c ment Document - Single Stage - One E Pending Imp 2023-04-2 RFB / Construction de deux ( IDA / D9220 apacity of the food system’s Post Request for Bids Open - National 1 Envelope proce 109,000.00 0.00 2022-10-18 2022-10-25 2022-11-24 2022-12-24 2023-01-28 nvelope lementation 8 02) serres modernes sur une productive base ss (Non Bank-SPD station de l'ITRA ) TG-FSRP TOGO-337929-CW- RFB / Réalisation des forages Request for Bids - de suivi des ressources en ea Digital advisory services for Single Stage - One E Works (without pr Under Imple 2023-12-1 ux souterraines (piézomètres IDA / D9220 agriculture and food crisis pr Post Request for Bids Open - National 150,182.00 0.00 2023-03-03 2023-04-05 2023-03-13 2023-04-12 2023-05-05 2023-05-12 2023-05-11 2023-06-16 nvelope equalification) SP mentation 3 ) dans les formations aquifèr evention and management D es du socle au profit de la Dir ection des ressources en eau (DRE) TG-FSRP TOGO-337930-CW- RFB / Réhabilitation de sept ( Request for Bids - Sustainability and adaptive c 07) agences de l' institut de Single Stage - One E Works (without pr Pending Imp 2023-11-2 IDA / D9220 apacity of the food system’s Post Request for Bids Open - National 707,000.00 0.00 2023-04-10 2023-04-17 2023-05-17 2023-06-01 2023-06-29 conseil et d'appui technique ( nvelope equalification) SP lementation 6 productive base ICAT) dans les régions de la D Kara, centrale, plateaux et m aritime (Marchés en 4 lots) TG-FSRP TOGO-338947-CW- National Procure RFB / Réhabilitation du local Sustainability and adaptive c ment Document - devant abriter les équipemen Request for Quota Single Stage - One E Pending Imp 2023-09-1 IDA / D9220 apacity of the food system’s Post Open - National 1 Envelope proce 72,727.00 0.00 2023-04-20 2023-06-16 ts de conservation des resso tions nvelope lementation 4 productive base ss (Non Bank-SPD urces génétiques de l'Institut ) togolais de recherche agrono mique (ITRA) TG-FSRP TOGO-337928-CW- RFB / Réhabilitation de onze ( Request for Bids - Digital advisory services for 11) centres et stations agro Single Stage - One E Works (without pr Pending Imp 2023-12-1 IDA / D9220 agriculture and food crisis pr Post Request for Bids Open - National 938,000.00 0.00 2023-04-10 2023-04-25 2023-05-25 2023-06-09 2023-07-14 météorologiques de la directi nvelope equalification) SP lementation 1 evention and management on générale de la météorolog D ie nationale (DGMN) réparti e n quatre (04) lots. TG-FSRP TOGO-351037-CW- Request for Quota RFQ / Réhabilitation de deux Sustainability and adaptive c Request for Quota Single Stage - One E tions - Small Work Under Imple 2023-09-0 (02) agences de l'institut de IDA / D9220 apacity of the food system’s Post Open - National 170,500.00 0.00 2023-04-17 2023-06-06 tions nvelope s (Emergency) SP mentation 4 conseil et d'appui technique ( productive base D -Competitive ICAT) dans la région des sava nes TG-FSRP TOGO-351042-CW- Request for Quota RFQ / Réhabilitation de trois ( Digital advisory services for Request for Quota Single Stage - One E tions - Small Work Pending Imp 2023-09-1 03) agence de l'Agence natio IDA / D9220 agriculture and food crisis pr Post Open - National 302,000.00 0.00 2023-04-17 2023-06-13 tions nvelope s (Emergency) SP lementation 1 nale de la météorologie (ANA evention and management D -Competitive MET) dans la région des sava nes. TG-FSRP TOGO-357134-CW- Request for Quota Sustainability and adaptive c RFQ / Aménagement de la vo Request for Quota Single Stage - One E tions - Small Work Pending Imp 2023-11-0 IDA / D9220 apacity of the food system’s Post Open - National 123,955.00 0.00 2023-06-02 2023-08-03 ix d'accès au complexe avico tions nvelope s (Emergency) SP lementation 1 productive base le de référence d'Avetonou D -Competitive GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TG-FSRP TOGO-305273-GO- Digital advisory services for Request for Quota Single Stage - One E RFQ / Acquisition de GPS au IDA / D9220 agriculture and food crisis pr Post Limited 14,545.00 0.00 Signed 2022-11-13 2022-09-05 2023-01-08 2023-05-08 tions nvelope profit des structures partenai evention and management res TG-FSRP TOGO-305828-GO- Digital advisory services for RFQ / Acquisition et installati Request for Quota Single Stage - One E IDA / D9220 agriculture and food crisis pr Post Limited 18,182.00 0.00 Signed 2022-10-29 2022-09-06 2022-12-24 2023-06-22 on de l'antenne de réception tions nvelope evention and management d'images satellitaires au profi t de la DGMN TG-FSRP TOGO-305833-GO- Digital advisory services for Request for Quota Single Stage - One E Pending Impl RFQ / Acquisition de smart p IDA / D9220 agriculture and food crisis pr Post Limited 12,727.00 0.00 2022-10-03 2022-11-28 2023-02-26 tions nvelope ementation hone pour le FAMEWS evention and management TG-FSRP TOGO-306008-GO- Digital advisory services for Request for Quota Single Stage - One E RFQ / Acquisition des pièges IDA / D9220 agriculture and food crisis pr Post Limited 12,727.00 0.00 Signed 2022-09-03 2022-08-31 2022-10-29 2023-01-27 tions nvelope à pheromone au profit de la evention and management DPV TG-FSRP TOGO-306094-GO- Sustainability and adaptive c RFQ / Acquisition de 2 drones Request for Quota Single Stage - One E IDA / D9220 apacity of the food system’s Post Limited 90,909.00 0.00 Signed 2022-09-03 2022-09-05 2022-10-29 2023-02-26 de phénotypage haut débit e tions nvelope productive base t de traitements phytosanitai res au profit de l'ITRA TG-FSRP TOGO-306286-GO- RFB / Acquisition des instrum Regional food market integr Single Stage - One E ents de mesure de températ IDA / D9220 Post Request for Bids Open - National 109,091.00 0.00 Signed 2022-08-18 2022-10-03 2022-08-23 2022-10-04 2022-11-04 2022-11-03 2022-12-07 2022-12-08 2023-04-07 ation and trade nvelope ure pour le laboratoire de mé trologie au profit de la HAUQ E (ATOMET, COTAG) TG-FSRP TOGO-306297-GO- RFQ / Acquisition des mobilie Request for Quota Single Stage - One E Under Imple IDA / D9220 Project Management Post Limited 36,364.00 0.00 2022-08-23 2022-12-22 2022-10-18 2022-11-17 rs et équipements pour la sal tions nvelope mentation le de reunion de la coordinati on du FSRP Page 1 TG-FSRP TOGO-305701-GO- Digital advisory services for RFQ / Achat de consommable Request for Quota Single Stage - One E Under Imple IDA / D9220 agriculture and food crisis pr Post Limited 18,182.00 0.00 2022-10-30 2022-12-25 2023-03-25 s pour les analyses au labora tions nvelope mentation evention and management toire des semences de Sotou boua TG-FSRP TOGO-306207-GO- Sustainability and adaptive c RFQ / Acquisition de vaccins I Request for Quota Single Stage - One E IDA / D9220 apacity of the food system’s Post Limited 87,273.00 0.00 Signed 2022-09-04 2022-10-19 2022-10-30 2023-01-28 TANEW pour la campagne de tions nvelope productive base vaccination de volailles (1 84 0 000 doses) TG-FSRP TOGO-306014-GO- Digital advisory services for RFQ / Acquisition de véhicule Direct - Internation IDA / D9220 agriculture and food crisis pr Post Direct Selection 872,727.00 0.00 Signed 2022-08-22 2022-10-28 2022-08-27 2022-08-23 2022-10-01 2022-12-30 s au profit des structures par al evention and management tenaires du FSRP - Togo TG-FSRP TOGO-306304-GO- RFQ / Achat de fournitures de Request for Quota Single Stage - One E Under Imple IDA / D9220 Project Management Post Limited 36,364.00 0.00 2022-08-28 2022-10-10 2022-10-16 2022-11-15 bureau et consomables infor tions nvelope mentation matiques au profit du FSRP TG-FSRP TOGO-306009-GO- RFQ / Acquisition de semenc Sustainability and adaptive c Request for Quota Single Stage - One E Under Imple es certifiées de cultures mar IDA / D9220 apacity of the food system’s Post Limited 136,364.00 0.00 2022-09-04 2022-11-02 2022-10-30 2022-12-29 tions nvelope mentation aichères au profit des produc productive base teurs de la région des savane s TG-FSRP TOGO-306015-GO- Digital advisory services for DIR / Acquisition des motos a Direct - Internation IDA / D9220 agriculture and food crisis pr Post Direct Selection 450,000.00 0.00 Signed 2022-08-25 2022-10-28 2022-08-30 2022-08-23 2022-10-04 2023-01-02 u profit des structures parten al evention and management aires du FSRP - Togo TG-FSRP TOGO-306007-GO- RFQ / Acquisition des équipe ments TIC (Serveur, imprima Digital advisory services for nte AO pour l'impression de Request for Quota Single Stage - One E IDA / D9220 agriculture and food crisis pr Post Limited 81,818.00 0.00 Signed 2022-09-04 2022-09-06 2022-10-30 2023-02-27 données sur des formats spé tions nvelope evention and management cifiques, ordinateurs de perfo rmances élevées, écrans inte ractifs) au profit de l'ANPC et de la DSID TG-FSRP TOGO-306331-GO- RFQ / Acquisition et installati Request for Quota Single Stage - One E Under Imple IDA / D9220 Project Management Post Limited 36,364.00 0.00 2022-09-04 2022-09-05 2022-10-23 2022-12-22 on d'un groupe electrogène a tions nvelope mentation u profit de la FSRP TG-FSRP TOGO-306302-GO- RFQ / Acquisiton du matériel Request for Quota Single Stage - One E Under Imple IDA / D9220 Project Management Post Limited 54,545.00 0.00 2022-08-31 2022-11-16 2022-10-26 2023-02-23 informatique au profit de la c tions nvelope mentation oordination du FSRP TG-FSRP TOGO-306288-GO- Regional food market integr Request for Quota Single Stage - One E Under Imple DIR / Acquérir les équipemen IDA / D9220 Post Limited 36,364.00 0.00 2022-09-12 2022-11-15 2022-11-07 2023-03-07 ation and trade tions nvelope mentation ts de métrologie au profit de la HAUQE TG-FSRP TOGO-306016-GO- Digital advisory services for RFB / Acquisition des matérie Single Stage - One E Under Imple IDA / D9220 agriculture and food crisis pr Post Request for Bids Open - National 490,909.00 0.00 2022-08-24 2021-10-05 2022-08-29 2022-09-28 2022-11-08 2022-10-28 2023-01-06 2022-12-02 2023-04-01 ls informatiques au profit de nvelope mentation evention and management s structures partenaires du F SRP - Togo TG-FSRP TOGO-306290-GO- RFQ / Acquisition des kits de Sustainability and adaptive c formation des femmes leader Request for Quota Single Stage - One E IDA / D9220 apacity of the food system’s Post Limited 10,909.00 0.00 Signed 2022-08-30 2022-08-31 2022-10-18 2022-11-17 s et des groupes organisés s tions nvelope productive base ur la transformation des alim ents à hautes valeurs nutritio nnelles TG-FSRP TOGO-306019-GO- DIR / Acquisition de vaccin p Sustainability and adaptive c Direct - Internation our la campagne de vaccinati IDA / D9220 apacity of the food system’s Post Direct Selection 47,273.00 0.00 Signed 2022-08-30 2022-09-08 2022-09-04 2022-08-23 2022-10-09 2023-01-07 al on du petit ruminant (500 00 productive base 0 doses de vaccins PPR) TG-FSRP TOGO-306285-GO- RFQ / Acquisition de matériel s et équipements de producti Sustainability and adaptive c on des essences forrestières Request for Quota Single Stage - One E IDA / D9220 apacity of the food system’s Post Limited 54,545.00 0.00 Signed 2022-09-11 2022-09-22 2022-11-06 2023-02-04 au profit des pépinéristes et tions nvelope productive base des équipements de collecte des produits forestiers non li geux (PFNL) au proft des coo pératives collectrices des PF NL. TG-FSRP TOGO-315078-GO- RFB / Acquisition de tracteurs Sustainability and adaptive c Open - Internationa Single Stage - One E Under Imple avec machines agricoles de IDA / D9220 apacity of the food system’s Post Request for Bids 545,455.00 0.00 2022-10-13 2022-10-17 2022-10-28 2022-10-20 2022-12-12 2022-12-02 2023-01-11 2023-01-16 2023-02-15 2023-06-15 l nvelope mentation motoculteurs et de trieuses c productive base alibreuses au profit de l’ITRA, l’ESA, l’ISMA et l’INFA TG-FSRP TOGO-315173-GO- RFB / Acquisition des équipe Sustainability and adaptive c ments pour l’analyse des rési Open - Internationa Single Stage - One E IDA / D9220 apacity of the food system’s Post Request for Bids 365,000.00 0.00 Signed 2022-10-14 2022-10-24 2022-10-29 2022-10-27 2022-12-13 2022-12-07 2023-01-12 2023-01-18 2023-02-16 2023-05-17 dus de médicaments vétérin l nvelope productive base aires et autres (laboratoire d e microbiologie, physico-chi mie, etc.) pour le compte de l 'ITRA TG-FSRP TOGO-315208-GO- RFB / Acquisition des équipe Sustainability and adaptive c ments des laboratoires de bi Open - Internationa Single Stage - One E IDA / D9220 apacity of the food system’s Post Request for Bids 364,000.00 0.00 Signed 2022-10-20 2022-11-17 2022-11-04 2022-11-17 2022-12-19 2023-01-06 2023-01-18 2023-01-23 2023-02-22 2023-06-22 osécurité, génétiques, entom l nvelope productive base ologie, microbiologie, chimie et phytopathologie au profit de l'ITRA TG-FSRP TOGO-318862-GO- Sustainability and adaptive c RFB / Acquisition des fertilisa Single Stage - One E Under Imple IDA / D9220 apacity of the food system’s Post Request for Bids Open - National 90,000.00 0.00 2022-10-30 2022-11-14 2022-11-06 2022-11-21 2022-12-16 2022-12-21 2022-12-22 2023-01-25 2023-03-26 nts et des biopesticides au pr nvelope mentation productive base ofit des producteurs sur les Z AAP TG-FSRP TOGO-320854-GO- RFB / Acquisition des équipe Sustainability and adaptive c ments de transformation agri Open - Internationa Single Stage - One E Pending Impl IDA / D9220 apacity of the food system’s Post Request for Bids 909,100.00 0.00 2022-11-30 2022-12-21 2023-02-04 2023-03-06 2023-04-17 2023-10-14 cole (décortiqueuses, batteus l nvelope ementation productive base es-vanneuses de riz, décortiq ueuses-vanneuses de soja) d ans la région des savanes Page 2 TG-FSRP TOGO-320879-GO- RFB / Acquisition et installati Digital advisory services for on de dix (10) stations autom Open - Internationa Single Stage - One E Under Imple IDA / D9220 agriculture and food crisis pr Post Request for Bids 636,364.00 0.00 2022-11-10 2022-11-21 2022-11-25 2022-11-21 2023-01-09 2023-02-08 2023-03-16 2023-09-12 atiques avec télétransmissio l nvelope mentation evention and management n de mesures hydrologiques et autres équipements au pr ofit de la DRE TG-FSRP TOGO-320903-GO- RFB / Acquisition des équipe Digital advisory services for Open - Internationa Single Stage - One E ments de réétalonnage (mai IDA / D9220 agriculture and food crisis pr Post Request for Bids 727,273.00 0.00 Signed 2022-11-02 2022-11-14 2022-11-17 2022-11-17 2023-01-01 2023-01-06 2023-01-31 2023-02-15 2023-03-07 2023-08-04 l nvelope ntenance) et autres accessoi evention and management res au profit de la DGMN. TG-FSRP TOGO-318860-GO- Sustainability and adaptive c RFB / Acquisition des outils m Single Stage - One E IDA / D9220 apacity of the food system’s Post Request for Bids Open - National 309,000.00 0.00 Signed 2022-10-30 2022-11-16 2022-11-14 2022-11-29 2022-12-02 2022-12-29 2022-12-22 2023-02-02 2023-03-19 araichers au profit des produ nvelope productive base cteurs sur les ZAAP TG-FSRP TOGO-320892-GO- RFB / Acquisition et installati Digital advisory services for Single Stage - One E on des équipements d’interc IDA / D9220 agriculture and food crisis pr Post Request for Bids Open - National 363,634.00 0.00 Signed 2022-11-22 2022-11-16 2022-12-07 2023-01-06 2022-12-20 2023-02-05 2022-12-30 2023-03-12 2023-07-10 nvelope onnexion des stations et cent evention and management re de contrôle de la DGMN TG-FSRP TOGO-320791-GO- Request for Quota Single Stage - One E RFQ / Acquisition de véhivule IDA / D9220 Project Management Post Limited 237,000.00 0.00 Signed 2022-10-28 2022-11-14 2022-12-01 2023-03-01 tions nvelope s au profit de la coordination du FSRP TG-FSRP TOGO-305934-GO- RFQ / Acquisition et installati on de 10 stations automatiqu Digital advisory services for Request for Quota Single Stage - One E es avec télétransmission de IDA / D9220 agriculture and food crisis pr Post Limited 40,000.00 0.00 Canceled 2022-09-07 2022-11-02 2023-03-02 tions nvelope mesures hydrologiques au pr evention and management ofit de la DRE et des équipe ments de réétalonnage au pr ofit de la DGMN. TG-FSRP TOGO-305702-GO- RFQ / Acquisition des équipe Digital advisory services for Request for Quota Single Stage - One E ments d'interconnexion des s IDA / D9220 agriculture and food crisis pr Post Limited 54,545.00 0.00 Canceled 2022-10-23 2022-12-18 2023-04-17 tions nvelope tations et centre de contrôle evention and management (15 stations et la DGMN: cent re de contrôle) TG-FSRP TOGO-306095-GO- Sustainability and adaptive c RFQ / Acquisition de 5 moiss Request for Quota Single Stage - One E IDA / D9220 apacity of the food system’s Post Limited 31,818.00 0.00 Canceled 2022-09-03 2022-08-31 2022-10-29 2023-02-26 onneuses batteuses au profit tions nvelope productive base des structures partenaires TG-FSRP TOGO-305830-GO- Digital advisory services for RFQ / Acquisition de postes p Request for Quota Single Stage - One E IDA / D9220 agriculture and food crisis pr Post Limited 90,909.00 0.00 Canceled 2022-10-10 2022-08-31 2022-12-05 2023-03-05 luvio classique complets ave tions nvelope evention and management c support au profit de la DGM N TG-FSRP TOGO-306287-GO- DIR / Acquisition des équipe Regional food market integr Direct - Internation ments de contrôle de qualité IDA / D9220 Post Direct Selection 327,273.00 0.00 Canceled 2022-08-29 2022-09-03 2022-10-08 2023-02-05 ation and trade al des produits  (camion étalon) au profit de la HAUQE (ATOM ET, COTAG) TG-FSRP TOGO-337895-GO- RFB / Acquisition de moisson Sustainability and adaptive c Open - Internationa Single Stage - One E Under Imple neuses-batteuses et trieuses IDA / D9220 apacity of the food system’s Post Request for Bids 305,455.00 0.00 2023-02-23 2023-05-12 2023-03-10 2023-04-24 2023-05-24 2023-06-28 2023-10-26 l nvelope mentation calibreuses au profit des stru productive base ctures partenaires du FSRP TG-FSRP TOGO-337896-GO- Sustainability and adaptive c Open - Internationa Single Stage - One E Under Imple RFB / Acquisition des motocu IDA / D9220 apacity of the food system’s Post Request for Bids 418,182.00 0.00 2023-02-24 2023-05-15 2023-03-11 2023-05-17 2023-04-25 2023-05-25 2023-06-29 2023-10-27 l nvelope mentation lteurs au profit des producte productive base urs sur les ZAAP TG-FSRP TOGO-337900-GO- RFB / Acquisition des équipe ments de contrôle de qualité Regional food market integr Open - Internationa Single Stage - One E Under Imple IDA / D9220 Post Request for Bids 545,455.00 0.00 2023-02-26 2023-05-12 2023-03-13 2023-05-17 2023-04-27 2023-05-27 2023-07-01 2023-12-28 des produits  (camion étalon) ation and trade l nvelope mentation au profit de la Haute Autorité pour la Qualité et l'Environne ment (HAUQE) TG-FSRP TOGO-337903-GO- Sustainability and adaptive c RFB / Acquisition des semenc Single Stage - One E Under Imple IDA / D9220 apacity of the food system’s Post Request for Bids Open - National 363,636.00 0.00 2023-02-17 2023-02-14 2023-03-04 2023-03-25 2023-04-20 2023-04-09 2023-05-09 2023-05-08 2023-06-07 es certifiées de riz et de soj nvelope mentation productive base a au profit des producteurs TG-FSRP TOGO-337927-GO- RFQ / Acquisition et installati on de dix (10) sondes électri Digital advisory services for Request for Quota Single Stage - One E Under Imple ques à eau pour mesure du IDA / D9220 agriculture and food crisis pr Post Limited 21,455.00 0.00 2023-04-07 2023-04-06 2023-05-19 2023-07-18 tions nvelope mentation niveau d'eau dans dix (10) pi evention and management ézomètres dans le bassin ver sant de l'Oti au profit de la Di rection des ressources en ea u (DRE) TG-FSRP TOGO-337933-GO- RFQ / Acquisition des logiciel Digital advisory services for Request for Quota Single Stage - One E Pending Impl s (SimClim, BaRatinAGE et lo IDA / D9220 agriculture and food crisis pr Post Limited 61,818.00 0.00 2023-03-04 2023-04-25 2023-06-24 tions nvelope ementation giciel base de données hydro evention and management logique) et la formation à leu r l'utilisation TG-FSRP TOGO-338507-GO- Digital advisory services for RFB / Acquisition et installati Open - Internationa Single Stage - One E Pending Impl IDA / D9220 agriculture and food crisis pr Post Request for Bids 909,091.00 0.00 2023-03-15 2023-04-05 2023-05-20 2023-06-19 2023-07-31 2024-01-27 on de six (06) nouvelles stati l nvelope ementation evention and management ons agrométéorologie au pro fit de la DGMN TG-FSRP TOGO-338974-GO- Sustainability and adaptive c RFB / Mise en place de 05 sy Open - Internationa Single Stage - One E Pending Impl IDA / D9220 apacity of the food system’s Post Request for Bids 545,455.00 0.00 2023-04-28 2023-05-13 2023-06-27 2023-07-27 2023-09-06 2023-12-05 stèmes de micro-irrigation s l nvelope ementation productive base ur les ZAAP à aménager TG-FSRP TOGO-338058-GO- Sustainability and adaptive c RFB / Equipement de la banq Single Stage - One E Under Imple IDA / D9220 apacity of the food system’s Post Request for Bids Open - National 174,545.00 0.00 2023-02-27 2023-03-08 2023-03-09 2023-04-08 2023-05-08 2023-05-25 2023-07-24 ue de gènes de l'Institut togo nvelope mentation productive base lais de recherche agronomiq ue (ITRA) TG-FSRP TOGO-337906-GO- Sustainability and adaptive c Direct - Internation DIR / Acquisition de l'engrais IDA / D9220 apacity of the food system’s Prior Direct Selection 20,000,000.00 0.00 Signed 2023-02-15 2023-02-21 2023-02-17 2023-02-21 2023-03-14 2023-04-13 al NPK15-15-15 en réponse à la productive base crise Page 3 TG-FSRP TOGO-351054-GO- RFQ / Acquisition de divers é Sustainability and adaptive c Request for Quota Single Stage - One E Pending Impl quipements d’élevage dans l IDA / D9220 apacity of the food system’s Post Open - National 50,000.00 0.00 2023-04-27 2023-06-19 2023-08-18 tions nvelope ementation e cadre du programme d'urg productive base ence dans la région des sava nes (PURS) TG-FSRP TOGO-357098-GO- RFB / Achat de couveuses de Sustainability and adaptive c Open - Internationa Single Stage - One E Pending Impl grandes capacités pour le co IDA / D9220 apacity of the food system’s Post Request for Bids 181,818.00 0.00 2023-05-19 2023-06-02 2023-07-17 2023-08-16 2023-09-20 2024-03-18 l nvelope ementation mplexe avicole de référence productive base d'Avetonou pour le compte d e l'ITRA TG-FSRP TOGO-357101-GO- Sustainability and adaptive c RFB / Acquisition et installati Open - Internationa Single Stage - One E Pending Impl IDA / D9220 apacity of the food system’s Post Request for Bids 472,727.00 0.00 2023-05-17 2023-05-31 2023-07-15 2023-08-14 2023-09-18 2023-12-17 on des kits d'irrigation au pr l nvelope ementation productive base ofit des producteurs de la rég ion des savanes TG-FSRP TOGO-358287-GO- Sustainability and adaptive c RFQ / Acquisition des poulets Request for Quota Single Stage - One E Under Imple IDA / D9220 apacity of the food system’s Post Limited 45,455.00 0.00 2023-06-01 2023-06-07 2023-07-20 2023-09-18 reproducteurs SASSO au prof tions nvelope mentation productive base it de l'ITRA (Ferme d'Avetono u) TG-FSRP TOGO-358276-GO- DIR / Acquisition des pièces d Digital advisory services for Direct - Internation Pending Impl e rechange et autres accesso IDA / D9220 agriculture and food crisis pr Post Direct Selection 1,090,909.00 0.00 2023-06-30 2023-07-05 2023-08-23 2024-02-19 al ementation ires pour la remise à niveau evention and management des stations météorologiques de l'ANAMET TG-FSRP TOGO-363533-GO- Sustainability and adaptive c RFB / Achat d'ingrédients pou Single Stage - One E Pending Impl IDA / D9220 apacity of the food system’s Post Request for Bids Open - National 181,818.00 0.00 2023-06-20 2023-07-04 2023-08-03 2023-08-18 2023-09-22 2024-09-21 r alimentation des volailles a nvelope ementation productive base u profit de l'ITRA (AVETONOU ) TG-FSRP TOGO-363538-GO- Sustainability and adaptive c RFB / Acquisition des équipe Open - Internationa Single Stage - One E Pending Impl IDA / D9220 apacity of the food system’s Post Request for Bids 318,181.00 0.00 2023-06-16 2023-06-30 2023-08-14 2023-09-13 2023-10-18 2024-04-15 ment d'analyse bromatologiq l nvelope ementation productive base ue rapide pour le compte de l 'ITRA (AVETONOU) NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TG-FSRP TOGO-306337-GO- Request for Quota Single Stage - One E RFQ / Sélection d'une compa IDA / D9220 Project Management Post Limited 44,545.00 0.00 Signed 2022-08-29 2022-09-06 2022-10-24 2023-10-24 tions nvelope gnie d'assurance pour le pers onnel du projet TG-FSRP TOGO-306339-GO- Request for Quota Single Stage - One E RFQ / Service courant de gar IDA / D9220 Project Management Post Limited 21,818.00 0.00 Signed 2022-08-30 2022-09-06 2022-10-18 2024-10-17 tions nvelope diennage pour le FSRP TG-FSRP TOGO-305834-GO- RFQ / Sélection d’une firme p Digital advisory services for Request for Quota Single Stage - One E Under Imple our l’impression des cartes, d IDA / D9220 agriculture and food crisis pr Post Limited 72,727.00 0.00 2022-08-28 2022-11-08 2022-10-23 2023-10-23 tions nvelope mentation es bulletins d’information et evention and management d’alerte au profit de l’ANPC e t de la DGMN TG-FSRP TOGO-306351-NC- Request for Quota Single Stage - One E RFQ / Service courant d'une s IDA / D9220 Project Management Post Limited 18,182.00 0.00 Signed 2022-08-29 2022-09-05 2022-10-24 2024-10-23 tions nvelope ociété d'entretien pour le FS RP CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TG-FSRP TOGO-305281-CS-L CS / Recrutement d'un audite Least Cost Selecti Under Implement ur externe pour l'audit financ IDA / D9220 Project Management Post Open - National 54,545.00 0.00 2022-08-31 2022-08-12 2022-09-21 2022-11-04 2022-12-02 2023-01-01 2023-02-05 2023-03-12 2023-06-10 on ation ier et comptable du projet FS RP (Exercice 2022, 2023, 202 4) TG-FSRP TOGO-306526-CS-I NDV / Selection d'un consulta Sustainability and adaptive c Quality And Cost- Open - Internationa Pending Impleme nt (cabinet) pour l'élaboratio IDA / D9220 apacity of the food system’s Post 109,091.00 0.00 2022-10-28 2022-11-18 2023-01-01 2023-01-29 2023-02-28 2023-04-04 2023-05-09 2023-08-07 Based Selection l ntation n du draft 1 de l'avant-projet productive base de loi portant régime foncier rural TG-FSRP TOGO-306602-CS-I NDV / Recrutement d'un cons Sustainability and adaptive c ultant pour l'étude environne Consultant Qualifi Pending Impleme IDA / D9220 apacity of the food system’s Post Limited 54,545.00 0.00 2022-09-20 2022-10-04 2022-11-03 2022-12-08 2023-03-08 mentale et sociale en vue de cation Selection ntation productive base l'aménagement de 5 ZAAP (5 00 ha) dans la région des sav anes TG-FSRP TOGO-315162-CS-C QS / Sélection d'un cabinet p Sustainability and adaptive c our l'étude de faisabilité tech Consultant Qualifi Pending Impleme IDA / D9220 apacity of the food system’s Post Limited 154,545.00 0.00 2022-10-25 2022-11-08 2022-12-08 2023-01-12 2023-06-11 nique et environnementale e cation Selection ntation productive base t sociale (APS, APD, EIES, DA O) pour la réhabilitation de 2 00 Km de pistes rurales TG-FSRP TOGO-320868-CS-L CS / Recrutement d’un consu Digital advisory services for Quality And Cost- Under Implement ltant (cabinet) pour la mise e IDA / D9220 agriculture and food crisis pr Post Open - National 36,364.00 0.00 2022-11-14 2022-10-27 2022-12-05 2023-01-18 2023-02-15 2023-03-17 2023-04-21 2023-05-26 2023-11-22 Based Selection ation n place de la base de donnée evention and management s nationales sur les catastrop hes agro climatiques TG-FSRP TOGO-338969-CS-I NDV / Recrutement d'un con sultant/cabinet pour les étud Sustainability and adaptive c Consultant Qualifi Pending Impleme es techniques, environnemen IDA / D9220 apacity of the food system’s Post Limited 90,909.00 0.00 2023-04-20 2023-04-30 2023-05-30 2023-07-05 2024-01-01 cation Selection ntation tales et sociales d'aménage productive base ment et réhabilitation des ret enues d'eau ( APS, APD, EIES ,DAO) Page 4 TG-FSRP TOGO-337941-CS-L CS / Recrutement d'un cabin Sustainability and adaptive c Quality And Cost- Under Implement et pour la surveillance et le c IDA / D9220 apacity of the food system’s Post Open - National 72,727.00 0.00 2023-04-10 2023-03-29 2023-04-24 2023-05-19 2023-06-03 2023-06-10 2023-06-24 2023-07-29 2024-01-25 Based Selection ation ontrôle de l'exécution des tra productive base vaux de réhabilitation de neu f (09) agences de l'ICAT TG-FSRP TOGO-337934-CS-L CS / Recrutement d'un cabin et pour la surveillance et le c ontrôle de l'exécution des tra Digital advisory services for Quality And Cost- Under Implement vaux de réhabilitation des ce IDA / D9220 agriculture and food crisis pr Post Open - National 90,909.00 0.00 2023-04-10 2023-04-10 2023-04-24 2023-05-19 2023-06-03 2023-06-10 2023-06-24 2023-07-25 2024-01-21 Based Selection ation ntres et stations météorologi evention and management ques de l'agence nationale d e la météorologie (ANAMET) dans 14 localités réparties da ns les 5 régions du TOGO TG-FSRP TOGO-357140-CS-Q CBS / Recrutement d'un cabi net pour la surveillance et le Sustainability and adaptive c contrôle de d'exécution des t Quality And Cost- Under Implement IDA / D9220 apacity of the food system’s Post Open - National 63,636.00 0.00 2023-05-08 2023-05-22 2023-06-17 2023-07-09 2023-08-08 2023-08-23 2023-09-14 2023-10-19 2024-04-16 ravaux d'aménagement du c Based Selection ation productive base omplexe avicole de référenc e d'Avetonou ainsi que de l'a ménagement de la voix d'acc ès au complexe TG-FSRP TOGO-363560-CS-Q CBS / Recrutement d'un cons ultant (cabinet) pour la mise Regional food market integr Quality And Cost- Under Implement IDA / D9220 Post Open - National 45,455.00 0.00 2023-06-21 2023-06-02 2023-08-05 2023-09-03 2023-10-01 2023-10-31 2023-12-05 2024-01-09 2024-03-09 en place d'un dispositif de ve ation and trade Based Selection ation ille informatique sur l'offre et la demande de marché au se in du CIFS INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TG-FSRP TOGO-306507-CS-I NDV / Recrutement d'un spéc Regional food market integr Individual Consult Under Implement IDA / D9220 Post Open - National 36,364.00 0.00 2022-09-20 2022-11-08 2022-11-29 2023-01-03 2024-01-03 ialiste en gestion des instrum ation and trade ant Selection ation ents financiers et l'accès au marché TG-FSRP TOGO-306509-CS-I NDV / Recrutement d'un cons Digital advisory services for ultant pour l'élaboration d'un Individual Consult Under Implement IDA / D9220 agriculture and food crisis pr Post Open - National 18,182.00 0.00 2022-10-06 2022-10-12 2022-11-24 2022-12-15 2023-01-19 2023-07-18 e cartographie des acteurs in ant Selection ation evention and management tervenants dans la productio n des données météorologiq ues TG-FSRP TOGO-306515-CS-I NDV / Recrutement d'un cons ultant pour l'élaboration du d Digital advisory services for Individual Consult ocument sur la thématique R IDA / D9220 agriculture and food crisis pr Post Open - National 72,727.00 0.00 Signed 2022-09-15 2022-09-22 2022-11-03 2022-12-16 2022-11-24 2023-03-16 2022-12-29 2023-03-29 ant Selection RC en lien avec la résilience evention and management alimentaire et nutritionelle d ans les instruments de planifi cation du développement TG-FSRP TOGO-306552-CS-I NDV / Recrutement d'un cons ultant pour l'actualisation de s textes législatifs et régleme Regional food market integr Individual Consult IDA / D9220 Post Open - National 18,182.00 0.00 Signed 2022-11-25 2022-09-21 2023-01-13 2023-01-06 2023-02-03 2023-03-13 2023-03-10 2023-04-09 ntaires relatifs au stockage e ation and trade ant Selection t aux échanges commerciaux des produits alimentaires en lien avec les textes commun autaires et internationaux TG-FSRP TOGO-306557-CS-I NDV / Recrutement de chauff Individual Consult Under Implement IDA / D9220 Project Management Post Open - National 20,945.00 0.00 2022-08-22 2022-08-17 2022-10-10 2023-02-24 2022-10-31 2022-12-05 2023-12-05 eurs et de coursier au profit ant Selection ation de la Coordination du FSRP TG-FSRP TOGO-306554-CS-I NDV / Recrutement d'un cons ulant individuel pour le renfo Regional food market integr Individual Consult IDA / D9220 Post Limited 36,364.00 0.00 Signed 2022-09-15 2022-11-10 2022-09-20 2022-12-01 2022-10-11 2023-03-13 2022-11-15 2022-12-15 rcement des capacités des tr ation and trade ant Selection ois filières cibles (Riz, Sodja, Volailes) sur l'accès au marc hé dans le cadre de la ZELEC AF TG-FSRP TOGO-306521-CS-I Sustainability and adaptive c NDV / Recrutement d'un cons Individual Consult IDA / D9220 apacity of the food system’s Post Limited 36,364.00 0.00 Signed 2022-08-25 2022-09-21 2022-08-30 2022-10-21 2022-09-20 2023-04-04 2022-10-25 2022-12-24 utant pour l'élaboration de la ant Selection productive base stratégie de vulgarisation dig itale (e-extension) TG-FSRP TOGO-306513-CS-I NDV / Recrutement d'un cons Digital advisory services for Individual Consult ultant pour la mise en place IDA / D9220 agriculture and food crisis pr Post Open - National 18,182.00 0.00 Canceled 2022-08-30 2022-10-18 2022-11-08 2022-12-13 2023-03-13 ant Selection de la base de données nation evention and management ales sur les catastrophes agr o climatiques TG-FSRP TOGO-338956-CS-I NDV / Recrutement d'un cons utatnt pour le diagnostic des Digital advisory services for possibiltés d' intervention du Individual Consult Pending Impleme IDA / D9220 agriculture and food crisis pr Post Open - National 27,273.00 0.00 2023-03-17 2023-05-11 2023-06-01 2023-07-06 2023-09-04 secteur privé dans la product ant Selection ntation evention and management ion des données y compris l a stratégie de financement d e la production et d'accès au x données TG-FSRP TOGO-338958-CS-I NDV / Recrutement d'un cons Digital advisory services for ultant pour l'inventaire des p Individual Consult Pending Impleme IDA / D9220 agriculture and food crisis pr Post Open - National 18,182.00 0.00 2023-03-20 2023-05-14 2023-06-04 2023-07-09 2023-09-07 arties prenantes, y compris l ant Selection ntation evention and management es acteurs du secteur privée en matières de données et d e services HIA TG-FSRP TOGO-338960-CS-I NDV / Recrutement de consul Digital advisory services for tant pour l'elaboration d'un Individual Consult Under Implement IDA / D9220 agriculture and food crisis pr Post Open - National 14,545.00 0.00 2023-03-15 2023-03-15 2023-05-04 2023-05-25 2023-06-29 2023-08-28 manuel de méthodologie et d ant Selection ation evention and management es outils de collectes des prix des produits animaux et hali eutiques pour le SIM Page 5 TG-FSRP TOGO-338962-CS-I NDV / Recrutement d'un cons ultant pour la formation des Digital advisory services for Individual Consult Pending Impleme acteurs (DGMN, ANPC, DSID, IDA / D9220 agriculture and food crisis pr Post Open - National 36,364.00 0.00 2023-03-22 2023-05-11 2023-06-01 2023-07-06 2023-08-05 ant Selection ntation DPPSE)sur les logiciels de SI evention and management G/Cartographie, de télédétec tion, SimClim, Globalmapper …...) TG-FSRP TOGO-338965-CS-I NDV / Recrutement de consul Digital advisory services for Individual Consult Pending Impleme tant pour l'établissement de l IDA / D9220 agriculture and food crisis pr Post Open - National 72,727.00 0.00 2023-03-24 2023-05-08 2023-05-29 2023-07-03 2023-10-31 ant Selection ntation a cartographie des zones à ri evention and management sques (inondation, vent viole nt, éboulements etc) TG-FSRP TOGO-338967-CS-I NDV / Recrutement de consul Digital advisory services for tant pour la Conception de m Individual Consult Pending Impleme IDA / D9220 agriculture and food crisis pr Post Open - National 27,273.00 0.00 2023-03-30 2023-05-19 2023-06-09 2023-07-14 2023-09-12 odèle simplifie de prévision e ant Selection ntation evention and management t détermination des seuils d’ alerte aux inondations dans l es bassins fluviaux du Togo TG-FSRP TOGO-338968-CS-I NDV / Recrutement d'un cons Digital advisory services for Individual Consult Under Implement ultant pour l'opérationnalisati IDA / D9220 agriculture and food crisis pr Post Open - National 9,091.00 0.00 2023-03-28 2023-04-10 2023-05-17 2023-06-07 2023-07-12 2023-08-11 ant Selection ation on du système informatisé d evention and management e gestion de la traçabilité des semences TG-FSRP TOGO-338971-CS-I NDV / Recrutement d'un cons Regional food market integr Individual Consult Under Implement ultant pour la cartographiqu IDA / D9220 Post Open - National 45,455.00 0.00 2023-04-10 2023-05-23 2023-05-30 2023-06-20 2023-07-25 2023-09-08 ation and trade ant Selection ation e des zones de production bi ologiques et agroécologique à l'echelle nationale TG-FSRP TOGO-338975-CS-I NDV / Recrutement d'un con Digital advisory services for Individual Consult Pending Impleme sultant pour l'étude diagnosti IDA / D9220 agriculture and food crisis pr Post Open - National 18,182.00 0.00 2023-04-04 2023-05-24 2023-06-14 2023-07-15 2023-07-18 ant Selection ntation que, l'élaboration et la valid evention and management ation des textes réglementan t l'accès aux données TG-FSRP TOGO-338979-CS-I NDV / recrutement d'un cons Regional food market integr Individual Consult Open - Internationa Under Implement ultant international pour app IDA / D9220 Post 45,455.00 0.00 2023-03-08 2023-04-10 2023-04-27 2023-05-18 2023-06-22 2023-08-21 ation and trade ant Selection l ation uyer la certification de cents (100) produits agroalimentair es prioritaires togolais TG-FSRP TOGO-357122-CS-I NDV / Mise en place d’un dis Regional food market integr Individual Consult Under Implement IDA / D9220 Post Open - National 45,455.00 0.00 2023-05-08 2023-05-05 2023-06-20 2023-07-11 2023-08-15 2023-10-14 positif de collecte des besoin ation and trade ant Selection ation s en intrants au sein du CIFS TG-FSRP TOGO-357129-CS-I NDV / Recrutement d’un cons ultant pour l’identification, la Sustainability and adaptive c Individual Consult Under Implement caractérisation et la de limita IDA / D9220 apacity of the food system’s Post Open - National 45,455.00 0.00 2023-05-08 2023-05-05 2023-07-05 2023-07-26 2023-08-30 2023-10-29 ant Selection ation tion du paysage d’interventio productive base n pour la mise en œuvre de l’ approche gestion intégrée du paysage TG-FSRP TOGO-357111-CS-I NDV / Recrutement d'un cons ultant pour la mise en place Regional food market integr Individual Consult IDA / D9220 Post Open - National 45,455.00 0.00 Canceled 2023-05-08 2023-07-06 2023-07-27 2023-08-31 2023-10-30 d'un dispositif de veille infor ation and trade ant Selection matique sur l'offre et la dem ande de marché au sein du C IFS Page 6 PROCUREMENT PLAN General 1. Project Information a. Country: Federal Republic of Somalia b. Project Name: Somalia Capacity Advancement, Livelihoods and Entrepreneurship, through Digital Uplift Program (SCALED-UP) c. Project Number: P168115 d. Total Finance: USD 31 Million 2. Project Implementation Agency: Somalia Ministry of Finance 3. Date of Project Plan: January 31, 2019 4. Period Covered by this Procurement: May 2019 – November 2020 I. Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016 revised November 2017 and August 2018) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. II. Bank’s Standard Procurement Document: The Bank’s standard Procurement Documents shall be used for all contracts subject to international competitive procurement and those contracts as specified into Procurement Plan tables in STEP III. National Procurement Arrangements: Not applicable IV. Prequalification: Not applicable V. Leased Assets: Not Applicable VI. Procurement of Second hand Goods: Not Applicable VII. Domestic Preference: Not Applicable 1 VIII. Hands on Expanded Implementation Support (HEIS): Not Applicable IX. Other Relevant Procurement Information: Not Applicable X. Thresholds for Procurement Approaches and Method (US$ millions) Thresholds for Procurement Approaches and Methods (US$ millions)–Goods, Works, and Non-Consulting Services Category Prior Open Open Request for Review Internation National Quotation (US$ al (RfQ) millions) Works All ≥ 5.0 < 5.0 ≤ 0.2 Goods, IT, All ≥ 0.5 < 0.5 ≤ 0.1 and non- consulting services Thresholds for Procurement Approaches and Methods (US$, millions) – Consulting Services Category Prior Review Short List of National (US$, millions) Consultants Consulting Engineering Services and Construction Supervision Consultants all ≤0.1 ≤0.2 (Firms) Individual all N/A N/A Consultants 2 XI. Packages for Goods, Works and Non-Consulting Services (At Negotiations – to be entered in STEP) Pr Revi Procur Selecti eq ew Evaluati ement Dom Market on ual by on Proces estic Expecte Expecte Approac Metho ific Estimate Ban Options s Pref d date of d date of Ref. Contract h (Open- d ati d Cost k (BAFO (Single eren bid/ Contract No Description National/ (RFP, on (US$) (Pri Rated stage- ce proposal Signatur Limited RFB, (Ye or/ Criteria single (Yes opening e etc.) RFQ s/ Post etc.) envelo /No) etc.) No ) pe etc.) ) GOODS Data Center equipment and software including: Singe Open Lowest 30th Security systems and stage 1st Jan, G1 $500,000 Prior Internatio RFQ Evaluate N/A N/A March equipment, Fraud One - 2020 nal d Cost 2020 monitoring and Envelop detection system (NCA) Office Equipment Single (Laptops, Desktops, Lowest Open stage 30/Octob 30/Novem G2 Projector, Printers $160,000 Prior RFB Evaluate N/A N/A National One- er/2019 ber/2019 and accessories) d Cost Envelop (NCA and ID) Singe Lowest Purchase of vehicles Open stage 20/Novem 10/Januar $80,000 Prior RFQ Evaluate N/A N/A G3 (NCA and ID) National One - ber/2019 y/2020 d Cost Envelop 3 Pr Revi Procur Selecti eq ew Evaluati ement Dom Market on ual by on Proces estic Expecte Expecte Approac Metho ific Estimate Ban Options s Pref d date of d date of Ref. Contract h (Open- d ati d Cost k (BAFO (Single eren bid/ Contract No Description National/ (RFP, on (US$) (Pri Rated stage- ce proposal Signatur Limited RFB, (Ye or/ Criteria single (Yes opening e etc.) RFQ s/ Post etc.) envelo /No) etc.) No ) pe etc.) ) Single Office furniture Lowest Stage 30/Januar 30/Februa (Chairs, Tables) $80,000 Prior Limited RFQ Evaluate N/A N/A G4 One- y/2020 ry/2020 (NCA and ID) d Cost Envelop Fixed spectrum monitoring and management Single Lowest equipment, Open Stage 01/Jun/20 01/Jul/201 G5 $120,000 Prior RFB Evaluate N/A N/A Spectrum National One- 19 9 d Cost management and Envelop monitoring system (NCA) Procurement of a suitable software platform to meet the Single CBS regulatory Open- Lowest Stage 01/Januar 01/April/2 G9 reporting and 1,100,000 Prior Internatio RFB Evaluate N/A N/A One- y/2020 020 effective analysis of nal d Cost Envelop financial risks (RegTech) for Central Bank 4 Pr Revi Procur Selecti eq ew Evaluati ement Dom Market on ual by on Proces estic Expecte Expecte Approac Metho ific Estimate Ban Options s Pref d date of d date of Ref. Contract h (Open- d ati d Cost k (BAFO (Single eren bid/ Contract No Description National/ (RFP, on (US$) (Pri Rated stage- ce proposal Signatur Limited RFB, (Ye or/ Criteria single (Yes opening e etc.) RFQ s/ Post etc.) envelo /No) etc.) No ) pe etc.) ) Procurement of a suitable software platform to meet the Financial Reporting Center (FRC) Single Open- Lowest requirements for Stage 01/Januar 01//April/ G10 1,300,000 Prior Internatio RFB Evaluate N/A N/A effective analysis One- y/2019 2020 nal d Cost and investigation of Envelop suspected cases of money laundering or financing of terrorism (FRC) Laptops for the new Single consultants, Office Lowest Stage 1stJanuary 1st March G11 chairs and tables 30,000 Prior Limited RFQ Evaluate N/A N/A One- 2020 2020 (Project Management d Cost Envelop (FRC) $3,370,0 Total Goods 00 WORKS W1 N/A Total Works Non -Consulting Services 5 Pr Revi Procur Selecti eq ew Evaluati ement Dom Market on ual by on Proces estic Expecte Expecte Approac Metho ific Estimate Ban Options s Pref d date of d date of Ref. Contract h (Open- d ati d Cost k (BAFO (Single eren bid/ Contract No Description National/ (RFP, on (US$) (Pri Rated stage- ce proposal Signatur Limited RFB, (Ye or/ Criteria single (Yes opening e etc.) RFQ s/ Post etc.) envelo /No) etc.) No ) pe etc.) ) Total Non- Consultant Service Consulting Services Selecti Market on Review by Approach Shortli Expected Estimate Method Expected Date Contract Bank (Open- sting Date of Bid Ref No. d Cost (QCBS, of Contract Description (Prior/Pos National/ (Yes/N Proposal (US$) LCBCS, Signature t) Limited o) Opening QBS, etc.) DS Individual Consultant for Financial Sector Specialist(Fintech) C1 100,000 Prior Open INDV N/A 01/June/2019 30/July/2019 and focal point of CBS on Scaled-up- to support Central Bank Consultancy services to: i) draft secured Open - C2 300,000 Prior QCBS N/A 15/June/2019 15/August2019 transaction and International credit referencing law that 6 Selecti Market on Review by Approach Shortli Expected Estimate Method Expected Date Contract Bank (Open- sting Date of Bid Ref No. d Cost (QCBS, of Contract Description (Prior/Pos National/ (Yes/N Proposal (US$) LCBCS, Signature t) Limited o) Opening QBS, etc.) DS establishes a modern legal framework enabling efficient intermediation, and ii) draft regulations under a modern FIL, National Payment Systems Law and Insurance Law to support Central Bank Individual AML/CFT expert to support the planned 2021 Mutual Evaluation and Financial C3 Reporting Center 100,000 Prior Open INDV N/A 01/June/2019 30/July/2019 (FRC) organizational development and Focal point to Scaled-Up to support FRC 7 Selecti Market on Review by Approach Shortli Expected Estimate Method Expected Date Contract Bank (Open- sting Date of Bid Ref No. d Cost (QCBS, of Contract Description (Prior/Pos National/ (Yes/N Proposal (US$) LCBCS, Signature t) Limited o) Opening QBS, etc.) DS Policy Advisor- Focal Point MPTT 100,000 C4 Prior Open INDV N/A 30/June 2019 20/August/2019 to Scaled up - NCA Consultancy services to provide ICT Sector Open – 09/Septembe C5 200,000 Prior CQS N/A 26/November2019 Strategy for International r/2019 Women in ICT (MPTT) - NCA Consultancy to provide ICT Sector Open – 09/October/2 30/December/201 C6 Strategy for 200,000 Prior CQS N/A International 019 9 Youth in ICT (MPTT) Consultancy to provide ICT Sector Strategy for Open – 15/Novembe C7 200,000 Prior CQS N/A 10/January/2020 ICT for the International r/2019 disabled (MPTT) - - NCA Consultancy to provide Regulatory Capacity Building 200,000 Open – 25/Novembe C8 Prior CQS N/A 26/January/2020 and Advisory International r/2019 Services on technical aspects including 8 Selecti Market on Review by Approach Shortli Expected Estimate Method Expected Date Contract Bank (Open- sting Date of Bid Ref No. d Cost (QCBS, of Contract Description (Prior/Pos National/ (Yes/N Proposal (US$) LCBCS, Signature t) Limited o) Opening QBS, etc.) DS Spectrum Management including 4G spectrum allocation, and SIM card registry (NCA) Consultancy service to provide logistical, transport and travel support for Open – 15th January C9 public 100,000 Prior CQS N/A 1st March 2020 International 2020 consultations, workshops, seminars, and select meetings (NCA) Consultancy 20th January C10 services for 100,000 Prior Open INDV N/A 10th March 2020 2020 Regulation (NCA) Consultancy C11 services for 100,000 Prior Open INDV N/A 1st Feb 2020 15th March 2020 Licensing (NCA) Consultancy service for 15th Feb C12 100,000 Prior Open INDV N/A 30th March 2020 Interconnection 2020 (NCA) 9 Selecti Market on Review by Approach Shortli Expected Estimate Method Expected Date Contract Bank (Open- sting Date of Bid Ref No. d Cost (QCBS, of Contract Description (Prior/Pos National/ (Yes/N Proposal (US$) LCBCS, Signature t) Limited o) Opening QBS, etc.) DS Consultancy 25th Feb C13 service for Mobile 100,000 Prior Open INDV N/A 10th April 2020 2020 Money (NCA) Consultancy service for SIM 1st March C14 100,000 Prior Open INDV N/A 20th April 2020 card registration 2020 (NCA) Consultancy 10th Sept C15 service for 100,000 Prior Open INDV N/A 10th Nov 2020 2020 Spectrum (NCA) Consultancy 20th March C16 service for 100,000 Prior Open INDV N/A 20th May 2020 2020 Numbering (NCA) Consultancy service for Sector 1st Sept t C17 100,000 Prior Open INDV N/A 1st Nov 2020 Economic Analysis 2020 (NCA) Services of a Senior Resident C18 Regulatory 100,000 Prior Open INDV N/A 01/Oct/2019 30/Nov/2019 Advisor to NCA (ITT) Services of a Licensing C19 60,000 Prior Open INDV N/A 01/Oct/2019 30/Nov/2019 Specialist to NCA (ITT) Services of a C20 60,000 Prior Open INDV N/A 01/Oct/2019 30/Nov/2019 Spectrum 10 Selecti Market on Review by Approach Shortli Expected Estimate Method Expected Date Contract Bank (Open- sting Date of Bid Ref No. d Cost (QCBS, of Contract Description (Prior/Pos National/ (Yes/N Proposal (US$) LCBCS, Signature t) Limited o) Opening QBS, etc.) DS Specialist to NCA (ITT) Services of a C21 Finance Specialist 60,000 Prior Open INDV N/A 01/Oct/2019 30/Nov/2019 to NCA (ITT) Services of an Accounting C22 60,000 Prior Open INDV N/A 01/Oct/2019 30/Nov/2019 Specialist to NCA (ITT) Services of a Pricing and Cyber C23 60,000 Prior Open INDV N/A 01/Oct/2019 30/Nov/2019 Security Specialist to NCA (ITT) Digital Identification System C24 Consultant and 108,000 Prior Open INDV N/A 30/May/2019 01/July/2019 Focal Point for ID to Scaled-up Project Consultancy to support the development of a comprehensive Open – C25 450,000 Prior QCBS N/A 30/May/2019 01/August/2019 legal framework International for the digital ID system, including to address data 11 Selecti Market on Review by Approach Shortli Expected Estimate Method Expected Date Contract Bank (Open- sting Date of Bid Ref No. d Cost (QCBS, of Contract Description (Prior/Pos National/ (Yes/N Proposal (US$) LCBCS, Signature t) Limited o) Opening QBS, etc.) DS protection, privacy, and cybersecurity (Digital ID) Consultancy to provide Advisory Services and Capacity Building on technical aspects of the digital ID system, Open – C26 400,000 Prior QCBS N/A 01/June/2019 30/Aug/2019 incl. database International mgmt., registration, and credential issuance, and authentication (Digital ID) Consultancy to provide Capacity Building and Advisory Services on the Open – C27 operationalization 300,000 Prior QCBS N/A 30/June/2019 30/August2019 International of an ID authority (incl. governance arrangements, organizational structure, 12 Selecti Market on Review by Approach Shortli Expected Estimate Method Expected Date Contract Bank (Open- sting Date of Bid Ref No. d Cost (QCBS, of Contract Description (Prior/Pos National/ (Yes/N Proposal (US$) LCBCS, Signature t) Limited o) Opening QBS, etc.) DS business plan) (ID authority) Consultancy service to provide logistical, transport and travel support for public Open – C28 100,000 Prior CQS N/A 30/June/2019 30/August/2019 consultations, National workshops, seminars, trainings, and meetings (Digital ID) Consultancy to develop Grievance Redressal Mechanisms, Social Management Plan Open – 01/Septembe C29 to address 250,000 Prior CQS N/A 30/October/2019 National r/2019 ongoing risks of exclusion and risk of data protection, and to design Digital ID Outreach Strategy to women and 13 Selecti Market on Review by Approach Shortli Expected Estimate Method Expected Date Contract Bank (Open- sting Date of Bid Ref No. d Cost (QCBS, of Contract Description (Prior/Pos National/ (Yes/N Proposal (US$) LCBCS, Signature t) Limited o) Opening QBS, etc.) DS other vulnerable groups (Digital ID) Consultancy to integrate the use of digital IDs in the financial Open – 15/October2 C30 250,000 Prior CQS N/A 15/December2019 sector, including National 019 for KYC and payment systems (Digital ID) Services of a Project Coordinator to the Open – 20/October/2 20/December/201 C31 ID unit/authority 60,000 Prior INDV N/A National 019 9 (could also be under Comp 2 or 3) Services of a Technical ID Open - 30/Septembe 30/November/201 C32 Solutions 80,000 Prior INDV N/A International r/2019 9 Specialist to the ID unit/authority Services of an ID Information Open - 03/October 03/December/201 C33 Systems 80,000 Prior INDV N/A International /2019 9 Specialist to the ID unit/authority 14 Selecti Market on Review by Approach Shortli Expected Estimate Method Expected Date Contract Bank (Open- sting Date of Bid Ref No. d Cost (QCBS, of Contract Description (Prior/Pos National/ (Yes/N Proposal (US$) LCBCS, Signature t) Limited o) Opening QBS, etc.) DS Services of a Financial Sector Specialist to the Open - 30/Septembe 03/November/201 C34 60,000 Prior INDV N/A ID unit (could also National r/2019 9 be under Comp 2 or 3) Services of a Communications and Grievance Open - 30/Septembe 03/November/201 C35 60,000 Prior INDV N/A Redressal National r/2019 9 Specialist to the ID unit Consultancy service to design and implement Citizen Open – 01/Sep/2019 01/Nov/2019 C36 600,000 Prior QCBS N/A Engagement and International Communications Campaign [Component 2.2] Consultancy service to implement ID Open – 01/Sep/2019 01/Nov 2019 C37 (mass) 2,400,000 Prior QCBS N/A International registration for 1 million residents [Component 2.2] Payment System Open – C38 162,000 Prior INDV 20/Aug/2019 30/October2019 Consultant to International 15 Selecti Market on Review by Approach Shortli Expected Estimate Method Expected Date Contract Bank (Open- sting Date of Bid Ref No. d Cost (QCBS, of Contract Description (Prior/Pos National/ (Yes/N Proposal (US$) LCBCS, Signature t) Limited o) Opening QBS, etc.) DS support interoperability of retail payment systems and mobile money services Individual consultancy services for digital registration Open – C39 100,000 Prior INDV N/A 30/Aug/2019 30/October/2019 services for International business at MoCI and Scaled-Up Focal Point PIU Personnel (PIU) Coordinator, Procurement Direct C40 Specialist and 396,000 Prior DIR N/A 15/May/2019 15/June/2020 Selection Financial Management Specialist) Monitoring Agent Open – 30/October/2 20/December/201 C41 300,000 Prior CQS N/A (PIU) International 019 9 Environmental and Social Open – C42 100,000 Prior INDV N/A 20/June/2019 30/August/2019 Safeguards International Consultant (PIU) 16 Selecti Market on Review by Approach Shortli Expected Estimate Method Expected Date Contract Bank (Open- sting Date of Bid Ref No. d Cost (QCBS, of Contract Description (Prior/Pos National/ (Yes/N Proposal (US$) LCBCS, Signature t) Limited o) Opening QBS, etc.) DS Monitoring and Open – C43 Evaluation 100,000 Prior INDV N/A 30/June/2019 01/August/2019 International Specialist Grievance Open – 30/Novembe C44 Redress Services 100,000 Prior INDV N/A 30/January/2020 International r/2019 Advisor (PIU) Investment Advisor for the Open – 30/October2 28/December/201 C45 100,000 Prior INDV N/A MSME Financing International 019 9 Facility (PIU) 9,256,00 Total Consulting 0 Services 12,626,0 Grand total 00 17 PROCUREMENT Somalia : Somalia Capacity Advancement, Livelihoods and Entrepreneurship, through Digital Uplift Project (SCALED-UP) PLAN General Information Country: Somalia Bank’s Approval Date of the Original Procurement Plan: 2019-04-24 Revised Plan Date(s): (comma delineated, leave blank if 2023-06-07 none) Project ID: P168115 GPN Date: Project Name: Somalia Capacity Advancement, Livelihoods and Entrepreneurship, through Digital Uplift Project (SCALED-UP) Loan / Credit No: IDA / D4330, TF / A9642, IDA / D8430, TF / B5774 Federal Republic of Somalia, Ministry of Finance, Office of the Director General Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SO-MOF-125939-GO-RFQ / IT Project Management and Co Request for Quota Single Stage - One E Under Imple IDA / D4330 Prior Limited 20,000.00 0.00 2019-08-12 2020-01-28 2019-10-07 2020-04-04 Equipment for Gargaara Offic ordination tions nvelope mentation e SO-MOF-125942-GO-RFQ / O Project Management and Co Request for Quota Single Stage - One E Under Imple IDA / D4330 Prior Limited 20,000.00 0.00 2019-08-12 2019-12-12 2019-10-07 2020-04-04 ffice Furniture for Gargaara O ordination tions nvelope mentation ffice SO-MOF-133514-GO-RFQ / O Project Management and Co Request for Quota Single Stage - One E Under Imple TF / A9642 Prior Limited 24,000.00 0.00 2019-09-17 2019-12-12 2019-11-12 2020-05-10 ffice Furniture for FRC ordination tions nvelope mentation SO-MOF-133517-GO-RFQ / IT Project Management and Co Request for Quota Single Stage - One E Under Imple TF / A9642 Prior Limited 34,000.00 0.00 2019-09-16 2019-12-12 2019-11-11 2020-05-09 Equipment for FRC Office ordination tions nvelope mentation SO-MOF-147025-GO-RFQ / M Project Management and Co Request for Quota Single Stage - One E Under Imple IDA / D4330 Prior Limited 16,000.00 0.00 2019-12-01 2019-12-22 2020-01-05 2020-02-04 aterials to renovate Gargaara ordination tions nvelope mentation Office SO-MOF-157419-GO-RFQ / O Request for Quota Single Stage - One E Under Imple TF / A9642 Strengthening Institutions Prior Limited 18,000.00 0.00 2020-02-16 2020-02-28 2020-03-21 2020-05-20 ffice Renovation Materials for tions nvelope mentation FRC SO-MOF-147502-GO-RFQ / M Request for Quota Single Stage - One E TF / A9642 Strengthening Institutions Prior Limited 15,000.00 0.00 Canceled 2019-12-04 2020-01-07 2020-03-07 aterials to renovate FRC Offic tions nvelope e SO-MOF-158312-GO-RFQ / IT Project Management and Co Request for Quota Single Stage - One E Pending Impl TF / A9642 Post Limited 40,000.00 0.00 2020-02-16 2020-03-22 2020-05-21 Equipment for NCA ordination tions nvelope ementation SO-MOF-158311-GO-RFQ / O Project Management and Co Request for Quota Single Stage - One E Pending Impl TF / A9642 Post Limited 30,000.00 0.00 2020-02-18 2020-03-25 2020-05-24 ffice Furniture for NCA ordination tions nvelope ementation SO-MOF-164727-GO-RFQ / O Project Management and Co Request for Quota Single Stage - One E Under Imple TF / A9642 Prior Limited 36,000.00 0.00 2020-03-25 2020-05-13 2020-05-01 2020-06-19 ffice Vehicle for Gargaara ordination tions nvelope mentation SO-MOF-176028-GO-RFQ / O Project Management and Co Request for Quota Single Stage - One E Pending Impl TF / A9642 Post Limited 15,000.00 0.00 2020-06-05 2020-07-12 2020-09-10 ffice Furniture for Switch Con ordination tions nvelope ementation sultants SO-MOF-176029-GO-RFQ / IT Project Management and Co Request for Quota Single Stage - One E Pending Impl Equipment for Switch Project TF / A9642 Post Limited 13,000.00 0.00 2020-06-05 2020-07-12 2020-09-10 ordination tions nvelope ementation Consultants SO-MOF-157412-GO-RFB / D esign, supply, installation, co Open - Internationa Single Stage - One E mmissioning and support of i TF / A9642 Strengthening Institutions Prior Request for Bids 500,000.00 0.00 Canceled 2020-02-13 2020-03-01 2020-02-18 2020-04-24 2020-03-31 2020-04-30 2020-06-04 2020-12-01 l nvelope nformation technology infras tructure ( Hardware and Soft ware) for goAML for FRC SO-MOF-182695-GO-RFB / D esign, supply, installation, co Open - Internationa Single Stage - One E mmissioning and support of i TF / A9642 Strengthening Institutions Prior Request for Bids 500,000.00 533,413.00 Signed 2020-06-30 2020-07-08 2020-07-05 2020-07-09 2020-08-16 2020-08-22 2020-09-15 2020-10-04 2020-10-20 2020-11-15 2021-06-17 l nvelope nformation technology infras tructure ( Hardware and Soft ware) for goAML for FRC SO-MOF-186149-GO-RFQ / O Project Management and Co Request for Quota Single Stage - One E Under Imple TF / A9642 Prior Limited 20,000.00 0.00 2020-07-30 2020-08-07 2020-09-03 2020-09-07 ffice Furniture for State Attor ordination tions nvelope mentation ney General SO-MOF-186151-GO-RFQ / IT Project Management and Co Request for Quota Single Stage - One E Under Imple Equipment for Office of State TF / A9642 Prior Limited 10,000.00 0.00 2020-08-02 2020-08-20 2020-09-01 2020-10-11 ordination tions nvelope mentation Attorney General SO-MOF-194580-GO-DIR / "D esign, Supply, Installation, Co mmissioning and Support for Information Technology Infra structure (ITI) covering Telec TF / A9642 Strengthening Institutions Prior Direct Selection Direct 586,355.28 595,823.09 Signed 2020-09-18 2020-10-01 2020-09-23 2020-10-30 2020-09-28 2021-03-04 2021-03-27 ommunication Networks, Mo dular Data Centers and LAN Network Infrastructure Tender No.SO-MoF-2018-3-G O-RFB i SO-MOF-194583-GO-DIR / D esign, Supply, Installation, Co TF / A9642 Strengthening Institutions Prior Direct Selection Direct 1,016,620.00 1,016,620.00 Signed 2020-09-18 2020-10-01 2020-09-23 2020-11-08 2020-09-27 2021-07-21 2021-03-26 mmissioning and Support for “National Switch of Somalia” (NSS) SO-MOF-194584-GO-DIR / D esign, Supply, Installation, Co mmissioning and Support for TF / A9642 Strengthening Institutions Prior Direct Selection Direct 1,468,677.00 507,323.50 Signed 2020-09-18 2020-10-01 2020-09-23 2020-11-08 2020-09-29 2021-08-27 2021-03-28 an Automated Transfer Syste m + (ATS+) - “Somalia Trans action Automation and Repor ting System” (STARS) SO-MOF-195729-GO-RFQ / G Project Management and Co Request for Quota Single Stage - One E Under Imple TF / A9642 Prior Limited 40,000.00 0.00 2020-09-27 2020-10-04 2020-10-25 2021-04-23 argaara Vehicle ordination tions nvelope mentation Page 1 SO-MOF-205114-GO-RFQ / IC Request for Quota Single Stage - One E T Equipment for Office of Sta TF / A9642 Strengthening Institutions Prior Limited 10,000.00 0.00 Terminated 2020-11-24 2020-12-23 2020-12-29 2021-02-22 2021-02-27 tions nvelope te Attorney General SO-MOF-205304-GO-RFQ / O Request for Quota Single Stage - One E TF / A9642 Strengthening Institutions Prior Limited 52,960.00 96,500.00 Signed 2020-11-25 2021-01-20 2020-12-22 2021-02-24 2021-02-20 ffice Renovation Materials for tions nvelope SPS Office SO-MOF-206419-GO-RFQ / H Request for Quota Single Stage - One E Under Imple ardware requirement for goA TF / A9642 Strengthening Institutions Prior Limited 60,000.00 0.00 2020-12-02 2021-01-02 2021-07-01 tions nvelope mentation ML Infrastructure for FRC SO-MOF-208281-GO-RFQ / IT Request for Quota Single Stage - One E Under Imple TF / A9642 Strengthening Institutions Prior Limited 8,000.00 0.00 2020-12-13 2020-12-14 2021-01-11 2021-03-12 I Network Monitoring Servers tions nvelope mentation for CBS SO-MOF-212376-GO-RFQ / IT Request for Quota Single Stage - One E Under Imple TF / A9642 Strengthening Institutions Prior Limited 29,100.00 0.00 2021-01-13 2021-02-16 2021-04-17 Equipment for Office of Switc tions nvelope mentation h Project. SO-MOF-212381-GO-RFQ / O Request for Quota Single Stage - One E Pending Impl TF / A9642 Strengthening Institutions Prior Limited 15,000.00 0.00 2021-01-13 2021-02-16 2021-04-17 ffice Furniture for Office of S tions nvelope ementation witch Project SO-MOF-215205-GO-DIR / Cl oud hosting, storages and So Request for Quota Single Stage - One E TF / A9642 Strengthening Institutions Prior Limited 90,000.00 86,925.45 Signed 2021-01-31 2021-02-11 2021-03-28 2021-03-02 2021-09-24 ftware Licenses Procurement tions nvelope for the Office of Accountant General SO-MOF-217738-GO-RFQ / IT Request for Quota Single Stage - One E TF / A9642 Strengthening Institutions Prior Limited 50,000.00 52,358.00 Signed 2021-02-11 2021-02-23 2021-03-14 2021-08-03 2021-05-13 Equipment for NCA Office tions nvelope SO-MOF-217739-GO-RFQ / O Request for Quota Single Stage - One E TF / A9642 Strengthening Institutions Prior Limited 40,000.00 46,175.00 Signed 2021-02-13 2021-02-23 2021-03-16 2021-05-05 2021-05-15 ffice Furniture for NCA Office tions nvelope SO-MOF-235209-GO-RFQ / IT Request for Quota Single Stage - One E Equipment for Ministry of Co TF / A9642 Strengthening Institutions Prior Limited 15,000.00 0.00 Terminated 2021-05-29 2021-10-15 2021-07-24 2022-02-28 2022-01-20 tions nvelope mmerce and Industry SO-MOF-235195-GO-RFQ / IT Request for Quota Single Stage - One E Under Imple Equipment for Office of State TF / A9642 Strengthening Institutions Prior Limited 10,000.00 0.00 2021-05-28 2021-06-08 2021-07-23 2022-01-19 tions nvelope mentation Attorney General SO-MOF-239372-GO-RFQ / IT Request for Quota Single Stage - One E Under Imple TF / A9642 Strengthening Institutions Prior Limited 29,000.00 0.00 2021-06-21 2021-06-28 2021-08-16 2022-02-12 Equipment for Switch Compa tions nvelope mentation ny Office SO-MOF-244698-GO-RFB / O Open - Internationa Single Stage - One E racle EBS Development & Su TF / A9642 Strengthening Institutions Prior Request for Bids 400,000.00 395,000.00 Signed 2021-07-26 2021-08-03 2021-07-31 2021-08-04 2021-09-11 2021-09-17 2021-10-11 2021-12-02 2021-11-15 2021-12-15 2022-11-15 l nvelope pport Maintenance for Centra l Bank SO-MOF-244700-GO-RFQ / IC Project Management and Co Request for Quota Single Stage - One E Pending Impl T Equipment for the Project I TF / A9642 Prior Limited 20,000.00 0.00 2021-08-02 2021-09-27 2022-03-26 ordination tions nvelope ementation mplementation Unit SO-MOF-248597-GO-RFQ / V Project Management and Co Request for Quota Single Stage - One E TF / A9642 Prior Limited 50,000.00 45,000.00 Signed 2021-08-25 2021-08-27 2021-10-02 2021-11-14 2022-03-31 ehicle for PIU Office ordination tions nvelope SO-MOF-248598-GO-RFQ / O Project Management and Co Request for Quota Single Stage - One E Pending Impl TF / A9642 Prior Limited 20,000.00 0.00 2021-08-25 2021-10-02 2022-03-31 ffice Furniture of PIU ordination tions nvelope ementation SO-MOF-259560-GO-RFQ / V Enabling Financial and Digit Request for Quota Single Stage - One E ehicle for Gargaara Company IDA / D4330 Prior Limited 50,000.00 40,000.00 Signed 2021-10-30 2021-10-29 2021-12-06 2021-11-18 2022-06-04 al Services tions nvelope Limited Office SO-MOF-261494-GO-RFQ / O Project Management and Co Request for Quota Single Stage - One E Under Imple TF / A9642 Prior Limited 20,000.00 0.00 2021-11-13 2021-11-12 2021-12-16 2022-06-14 ffice Furniture for PIU ordination tions nvelope mentation SO-MOF-261477-GO-RFQ / IC Request for Quota Single Stage - One E T Equipment for PIU Office an TF / A9642 Strengthening Institutions Prior Limited 93,000.00 94,468.00 Signed 2021-11-13 2021-11-12 2021-12-03 2021-12-21 2022-06-01 tions nvelope d for Office of Accountant Ge neral SO-MOF-261945-GO-RFQ / IC Enabling Financial and Digit Request for Quota Single Stage - One E Under Imple T Equipment for Gargaara Co IDA / D4330 Prior Limited 20,000.00 0.00 2021-11-15 2021-12-08 2021-12-23 2022-06-21 al Services tions nvelope mentation mpany Limited SO-MOF-266889-GO-RFQ / O Request for Quota Single Stage - One E Under Imple ffice Furniture for Ministry of TF / A9642 Strengthening Institutions Prior Limited 20,000.00 0.00 2021-12-12 2021-12-09 2022-02-06 2022-08-05 tions nvelope mentation Commerce and Industry SO-MOF-287355-GO-RFQ / IC Enabling Financial and Digit Request for Quota Single Stage - One E Under Imple T Equipment for Gargaara Co IDA / D4330 Prior Limited 20,000.00 0.00 2022-04-09 2022-04-12 2022-05-13 2022-11-09 al Services tions nvelope mentation mpany Limited SO-MOF-294240-GO-RFQ / IC Request for Quota Single Stage - One E Under Imple TF / B5774 Strengthening Institutions Prior Limited 25,000.00 0.00 2022-05-16 2023-03-09 2022-06-19 2022-12-16 T Equipment for FRC tions nvelope mentation SO-MOF-294242-GO-RFQ / O Request for Quota Single Stage - One E Under Imple TF / B5774 Strengthening Institutions Prior Limited 50,000.00 0.00 2022-05-16 2022-07-26 2022-06-19 2022-12-16 ffice Furniture for FRC tions nvelope mentation SO-MOF-299091-GO-RFB / C Under Imple ORE-BANKING TEMENOS T24 TF / B5774 Strengthening Institutions Prior Request for Bids Direct 350,000.00 0.00 2022-06-10 2022-06-21 2022-06-18 2022-06-27 2022-07-29 2023-07-29 mentation UPGRADE FOR CENTRAL BAN K SO-MOF-301667-GO-RFQ / Pr ovision and implementation Request for Quota Single Stage - One E TF / B5774 Strengthening Institutions Prior Limited 100,000.00 0.00 Canceled 2022-07-05 2022-08-15 2022-08-30 2023-02-26 of Splunk Enterprise security tions nvelope system for Central Bank. SO-MOF-343154-GO-RFQ / O Request for Quota Single Stage - One E Pending Impl TF / B5774 Strengthening Institutions Prior Limited 30,000.00 0.00 2023-02-26 2023-04-23 2023-07-02 ffice furniture for Gargaara tions nvelope ementation SO-MOF-345380-GO-RFQ / Pr ovision and implementation Request for Quota Single Stage - One E Under Imple TF / B5774 Strengthening Institutions Prior Limited 100,000.00 0.00 2023-03-05 2023-05-09 2023-04-30 2023-10-27 of Splunk Enterprise security tions nvelope mentation system for Central Bank SO-MOF-360532-GO-RFQ / IC Request for Quota Single Stage - One E Pending Impl TF / B5774 Strengthening Institutions Prior Limited 95,000.00 0.00 2023-05-23 2023-07-18 2023-09-16 T Equipment for NIRA tions nvelope ementation SO-MOF-360537-GO-RFQ / V Project Management and Co Request for Quota Single Stage - One E Under Imple TF / A9642 Prior Limited 60,000.00 0.00 2023-05-31 2023-07-26 2023-09-24 ehicle for PIU ordination tions nvelope mentation Page 2 NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SO-MOF-129803-NC-RFQ / Of Project Management and Co Request for Quota Single Stage - One E IDA / D4330 Prior Limited 44,000.00 205,440.00 Signed 2019-09-14 2020-02-10 2019-11-09 2020-02-23 2019-12-01 fice Rent for Gargaara Comp ordination tions nvelope any SO-MOF-145412-NC-RFQ / C omprehensive Brand Visual I Request for Quota Single Stage - One E Under Imple IDA / D4330 Strengthening Institutions Prior Limited 11,000.00 0.00 2019-11-22 2019-12-12 2019-12-20 2020-02-18 dentity & Development Servi tions nvelope mentation ce for Gargaara Company SO-MOF-176015-GO-RFQ / O Project Management and Co Request for Quota Single Stage - One E Pending Impl TF / A9642 Post Limited 50,000.00 0.00 2020-06-05 2020-07-31 2021-07-31 ffice Rent for Switch Compan ordination tions nvelope ementation y SO-MOF-189485-NC-DIR / Or acle Cloud Infrastructure for TF / A9642 Strengthening Institutions Prior Direct Selection Direct 500,000.00 416,350.00 Signed 2020-08-20 2020-08-25 2020-08-22 2020-10-15 2020-08-29 2020-11-10 2022-08-19 Somalia Stars Project for Cen tral Bank SO-MOF-192239-NC-DIR / T2 TF / A9642 Strengthening Institutions Prior Direct Selection Direct 60,000.00 296,712.50 Signed 2020-09-09 2020-09-16 2020-09-14 2020-10-26 2020-09-19 2020-12-25 2020-11-18 4 Integration to STARS for Ce ntral Bank SO-MOF-198928-NC-RFB / Or Single Stage - One E Under Imple TF / A9642 Strengthening Institutions Prior Request for Bids Limited 400,000.00 0.00 2020-10-12 2020-10-21 2020-10-17 2020-10-28 2020-11-28 2020-12-22 2020-12-10 2021-04-19 2021-01-05 2022-01-05 acle Partner for CBS nvelope mentation SO-MOF-221827-NC-RFQ / in Request for Quota Single Stage - One E TF / A9642 Strengthening Institutions Prior Limited 24,000.00 22,800.00 Signed 2021-03-04 2021-03-08 2021-04-10 2021-05-03 2022-04-10 ternet connection to MoCI tions nvelope SO-MOF-238583-NC-RFB / Or Single Stage - One E acle EBS Development & Sup TF / A9642 Strengthening Institutions Prior Request for Bids Open - National 400,000.00 0.00 Canceled 2021-06-13 2021-06-18 2021-07-30 2021-08-29 2021-10-03 2022-10-03 nvelope port Maintenance for Central Bank SO-MOF-239371-NC-RFQ / Tr anslations of the Radio Frequ Request for Quota Single Stage - One E Under Imple ency Spectrum Policy and th TF / A9642 Strengthening Institutions Prior Limited 30,000.00 0.00 2021-06-21 2021-06-28 2021-08-16 2022-02-12 tions nvelope mentation e Numbering Policy for Minist ry of Communication and Tec hnology SO-MOF-258720-NC-RFQ / Cl oud dedicated server hosting Project Management and Co Request for Quota Single Stage - One E Under Imple TF / A9642 Prior Limited 96,000.00 0.00 2021-10-31 2021-12-07 2022-06-05 and software license for ongo ordination tions nvelope mentation ing activities of Ministry of Fi nance Website SO-MOF-259985-NC-RFB / Or Open - Internationa Single Stage - One E Pending Impl acle Software Update License TF / A9642 Strengthening Institutions Prior Request for Bids 206,000.00 0.00 2021-11-01 2021-11-06 2021-12-18 2022-01-07 2022-01-24 2023-01-24 l nvelope ementation and Support to CBS SO-MOF-259987-NC-RFQ / T Request for Quota Single Stage - One E Under Imple emenos T24 R16 Cloud Base TF / A9642 Strengthening Institutions Prior Limited 50,000.00 0.00 2021-11-06 2021-11-03 2021-12-13 2022-06-11 tions nvelope mentation d Disaster Recover Solution f or CBS SO-MOF-259990-NC-RFQ / T Request for Quota Single Stage - One E Under Imple 24-SFMIS BULK Transactions TF / A9642 Strengthening Institutions Prior Limited 51,000.00 0.00 2021-11-06 2021-11-03 2021-12-14 2022-06-12 tions nvelope mentation Straight Through Processing (STP) for CBS SO-MOF-287352-NC-DIR / Or Under Imple acle Database Enterprise Edit TF / B5774 Strengthening Institutions Prior Direct Selection Direct 200,000.00 0.00 2022-04-01 2022-04-08 2022-04-06 2022-04-25 2022-04-12 2023-04-07 mentation ion - Processor Perpetual Full Use 6 Pieces SO-MOF-291779-NC-RFQ / S ecurity Aspect Regulatory Co Request for Quota Single Stage - One E Pending Impl TF / B5774 Strengthening Institutions Prior Limited 70,000.00 0.00 2022-04-30 2022-06-07 2023-06-07 mpliance for Somali Business tions nvelope ementation Registration and licensing sy stem SO-MOF-291776-NC-RFQ / A Request for Quota Single Stage - One E udit Software for the Central TF / B5774 Strengthening Institutions Post Limited 90,000.00 0.00 Canceled 2022-04-30 2022-05-30 2022-06-07 2023-06-07 tions nvelope Bank of Somalia (CBS) SO-MOF-304504-NC-RFQ / A Request for Quota Single Stage - One E Under Imple TF / B5774 Strengthening Institutions Prior Limited 90,000.00 0.00 2022-07-23 2022-08-15 2022-09-17 2023-03-16 udit Software for Central Ban tions nvelope mentation k SO-MOF-332568-NC-RFQ / S omali Business Registration a Enabling Financial and Digit Request for Quota Single Stage - One E Under Imple TF / B5774 Prior Limited 46,000.00 0.00 2023-01-31 2023-05-15 2023-03-28 2023-09-24 nd licensing system – Securit al Services tions nvelope mentation y Aspect Regulatory Complia nce report. SO-MOF-348481-NC-DIR / Tr Enabling Financial and Digit Under Imple IDA / D4330 Prior Direct Selection Direct - National 35,633.00 0.00 2023-03-09 2023-03-09 2023-03-10 2023-03-10 2023-03-31 2023-04-10 aining for local Bankers -Gaa al Services mentation rgara Co. SO-MOF-353236-NC-DIR / Of Project Management and Co fice Rent for National Identifi IDA / D4330 Prior Direct Selection Direct - National 84,000.00 0.00 Canceled 2023-03-31 2023-04-05 2023-04-05 2023-04-19 2023-05-10 2024-05-09 ordination cation and Registration Auth ority SO-MOF-353364-NC-DIR / Int Under Imple ernet connection to Business TF / A9642 Strengthening Institutions Prior Direct Selection Direct - National 26,400.00 0.00 2023-04-10 2023-04-18 2023-04-15 2023-05-03 2023-05-20 2024-05-19 mentation Registration System for MOCI SO-MOF-362310-NC-DIR / Of Under Imple TF / B5774 Strengthening Institutions Prior Direct Selection Direct - National 173,195.00 0.00 2023-05-20 2023-05-18 2023-05-25 2023-05-21 2023-06-22 2025-06-21 fice Rent for NIRA mentation SO-MOF-362876-NC-RFQ / Of Request for Quota Single Stage - One E Under Revie TF / B5774 Strengthening Institutions Prior Limited 56,000.00 0.00 2023-06-09 2023-08-04 2024-08-03 fice Rent for DPA tions nvelope w CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 3 SO-MOF-113751-CS-CQS / C onsultancy service to prepar e financial sustainability plan Project Management and Co Consultant Qualifi s for each supported agency IDA / D4330 Prior Open - National 250,000.00 0.00 Canceled 2019-05-28 2019-07-10 2019-06-18 2019-07-23 2019-08-01 2019-08-31 2019-10-05 2020-04-02 ordination cation Selection to assist with fiscal planning and sustainability of services delivered & institutional effec tiveness SO-MOF-128029-CS-CQS / C onsultancy Services To Provi Enabling Financial and Digit Consultant Qualifi IDA / D4330 Prior Open - National 200,000.00 102,629.20 Signed 2019-08-22 2019-09-03 2019-09-12 2019-09-11 2019-10-26 2019-12-04 2019-11-25 2020-03-17 2019-12-30 2020-03-20 2020-06-27 de Legal Advisory Services to al Services cation Selection Gargaara Company Limited SO-MOF-134869-CS-QCBS / Enabling Financial and Digit Quality And Cost- Open - Internationa Under Implement TF / A9642 Prior 500,000.00 0.00 2019-09-23 2019-09-25 2019-10-14 2019-10-04 2019-11-15 2019-12-22 2019-11-17 2020-02-24 2019-12-17 2020-05-01 2019-12-24 2020-01-28 2021-01-27 Digital ID Legal Framework S al Services Based Selection l ation upport SO-MOF-135542-CS-QCBS / Technical and Project Manag Enabling Financial and Digit Quality And Cost- Open - Internationa Under Implement TF / A9642 Prior 1,500,000.00 0.00 2019-09-26 2019-09-26 2019-10-17 2019-10-04 2019-11-30 2020-02-18 2019-12-02 2020-01-01 2020-01-09 2020-02-01 2021-01-31 ement Support for Somalia’s al Services Based Selection l ation Digital ID System SO-MOF-139425-CS-CQS / D ESIGN, DEVELOPMENT AND I MPLEMENTATION OF AN ELE CTONIC MANAGEMENT INFOR MATION SYSTEM FOR ACCOU Consultant Qualifi TF / A9642 Strengthening Institutions Prior Open - National 200,000.00 0.00 Canceled 2019-10-14 2019-11-08 2019-11-04 2019-12-15 2019-12-22 2020-01-15 2020-07-13 NTABLE DOCUMENTS (EMIS – cation Selection AD), AN ENTERPRISE ELECTR ONIC OFFICE AND DOCUMEN T MANAGEMENT SYSTEM (EO DMS) AND A CASH MANAGEM ENT SYSTEM/DATABASE FOR THE AG SO-MOF-150489-CS-QCBS / THE DESIGN, DEVELOPMENT AND IMPLEMENTATION OF A N ELECTONIC MANAGEMENT INFORMATION SYSTEM FOR A Quality And Cost- Open - Internationa TF / A9642 Strengthening Institutions Prior 300,000.00 394,546.50 Signed 2019-12-18 2020-01-13 2020-01-08 2020-01-26 2020-02-21 2020-06-03 2020-03-20 2020-07-01 2020-04-19 2020-09-07 2020-05-24 2020-09-23 2020-06-20 2020-09-25 2021-06-20 CCOUNTABLE DOCUMENTS ( Based Selection l EMIS – AD), AN ENTERPRISE ELECTRONIC OFFICE AND DO CUMENT MANAGEMENT SYST EM (EODMS) AND A CASH MA NAGEMENT SYSTEM/DATABA SE FOR THE AG Office SO-MOF-153721-CS-CQS / C onsultancy service to prepar e financial sustainability plan Project Management and Co Consultant Qualifi Open - Internationa s for each supported agency TF / A9642 Prior 250,000.00 73,912.80 Signed 2020-01-30 2020-02-02 2020-02-13 2020-02-02 2020-02-28 2020-08-19 2020-03-04 2020-09-23 2020-03-21 2020-09-25 2020-08-28 ordination cation Selection l to assist with fiscal planning and sustainability of services delivered & institutional effec tiveness SO-MOF-155916-CS-CQS / Gr ievance Redress Mechanisms Consultant Qualifi Open - Internationa TF / A9642 Strengthening Institutions Prior 90,000.00 88,966.25 Signed 2020-01-29 2020-01-28 2020-02-12 2020-02-06 2020-03-05 2020-09-01 2020-03-17 2021-02-03 2020-04-03 2021-03-15 2020-08-07 for the Digital ID System and cation Selection l the MSME Financing Facility SO-MOF-155917-CS-CQS / S ocial Impact Research & Dev Consultant Qualifi Open - Internationa elopment of an Inclusive Outr TF / A9642 Strengthening Institutions Prior 180,000.00 179,604.19 Signed 2020-01-31 2020-01-28 2020-02-14 2020-02-06 2020-03-21 2020-09-01 2020-03-26 2021-02-01 2020-04-12 2021-03-26 2020-12-06 cation Selection l each and Enrollment Strateg y for the Digital ID System SO-MOF-167633-CS-CQS / C onsultancy Services to Provid Consultant Qualifi Open - Internationa TF / A9642 Strengthening Institutions Prior 50,000.00 60,000.00 Signed 2020-04-07 2020-04-22 2020-04-21 2020-05-04 2020-05-22 2020-10-12 2020-05-27 2021-04-30 2020-06-14 2021-05-04 2021-06-14 e Financial Audit Services to cation Selection l Gargaara Company Limited SO-MOF-201605-CS-CQS / D EVELOPMENT OF AN ICT DIGI TAL INCLUSION POLICY AND Consultant Qualifi TF / A9642 Strengthening Institutions Prior Open - National 180,000.00 0.00 Canceled 2020-10-28 2020-11-16 2020-11-18 2020-12-10 2020-12-17 2021-03-23 2020-12-20 2021-01-03 2021-07-02 ACTION PLAN FOR ADVANCIN cation Selection G ACCESS TO ICT SERVICES F OR MARGINALIZED GROUPS FOR MPTT SO-MOF-204670-CS-CQS / C onsulting Services for CBS str Consultant Qualifi ongrooms on Design and Eng TF / A9642 Strengthening Institutions Prior Limited 60,000.00 74,160.00 Signed 2020-11-17 2020-12-01 2020-12-01 2020-12-28 2020-12-11 2021-05-06 2020-12-25 2021-05-28 2021-06-23 cation Selection ineering, Required by CBS St rongrooms & Incineration Fac ilities SO-MOF-205622-CS-CQS / C onsultancy Services to condu Consultant Qualifi Pending Impleme TF / A9642 Strengthening Institutions Post Open - National 90,000.00 0.00 2020-11-23 2020-12-14 2021-01-12 2021-01-17 2021-01-30 2022-01-30 ct Independent third-party as cation Selection ntation sessments of PFIs SO-MOF-205623-CS-CQS / E nterprise Information and Re Consultant Qualifi Pending Impleme TF / A9642 Strengthening Institutions Post Open - National 200,000.00 0.00 2020-11-23 2020-12-14 2021-01-12 2021-01-14 2021-01-28 2022-01-28 source Planning System for G cation Selection ntation argaara Company Limited SO-MOF-215903-CS-CQS / C onsultancy Services to Condu Enabling Financial and Digit Consultant Qualifi Open - Internationa Pending Impleme ct Independent Third-Party A IDA / D4330 Prior 150,000.00 0.00 2021-01-26 2021-02-09 2021-03-12 2021-03-24 2021-04-08 2022-04-08 al Services cation Selection l ntation ssessment of Financial Institu tions under the MSME Financi ng Facility SO-MOF-225550-CS-CQS / C Consultant Qualifi Open - Internationa onsulting Firm to Conduct AM TF / A9642 Strengthening Institutions Prior 60,000.00 0.00 Canceled 2021-03-21 2021-04-11 2021-05-25 2021-06-24 2021-07-29 2022-01-25 cation Selection l L/CFT Technical Compliance Analysis SO-MOF-228105-CS-CQS / C Consultant Qualifi Open - Internationa Under Implement onsulting Firm to Conduct AM TF / A9642 Strengthening Institutions Prior 100,000.00 0.00 2021-04-08 2021-05-03 2021-04-29 2021-05-24 2021-06-12 2021-10-21 2021-07-12 2023-01-15 2021-08-16 2022-02-12 cation Selection l ation L/CFT Technical Compliance Analysis SO-MOF-231332-CS-QCBS / Technical Advisory Services f Quality And Cost- Open - Internationa Under Implement TF / A9642 Strengthening Institutions Prior 500,000.00 0.00 2021-05-24 2021-07-22 2021-06-07 2021-09-15 2021-07-20 2021-12-23 2021-07-23 2022-01-18 2021-08-22 2022-03-01 2021-09-26 2022-10-06 2021-10-31 2022-10-31 or the development of a foun Based Selection l ation dational legal framework for the digital economy SO-MOF-261944-CS-CQS / In Consultant Qualifi dependent Verification Agent IDA / D8430 Strengthening Institutions Prior Open - National 250,000.00 0.00 Under Review 2021-11-10 2021-11-10 2021-11-24 2021-11-16 2021-12-27 2022-05-30 2021-12-30 2022-07-20 2022-01-16 2023-01-16 cation Selection for Central Bank Page 4 SO-MOF-272066-CS-CQS / D EVELOPMENT OF AN ICT DIGI TAL INCLUSION POLICY AND Consultant Qualifi Open - Internationa ACTION PLAN FOR ADVANCIN TF / A9642 Strengthening Institutions Prior 180,000.00 0.00 Canceled 2022-01-09 2022-01-23 2022-02-23 2022-02-27 2022-03-16 2022-09-12 cation Selection l G ACCESS TO ICT SERVICES F OR MARGINALIZED GROUPS FOR MINISTRY OF COMMUNIC ATION AND TECHNOLOGY SO-MOF-273546-CS-CQS / D EVELOPMENT OF AN ICT DIGI Consultant Qualifi Under Implement TAL INCLUSION POLICY AND TF / B5774 Strengthening Institutions Prior Open - National 230,000.00 0.00 2022-01-24 2022-01-31 2022-02-07 2022-02-03 2022-03-12 2023-01-30 2022-03-22 2023-04-28 2022-04-10 2022-10-07 cation Selection ation ACTION PLAN FOR ADVANCIN G ACCESS TO ICT SERVICES F OR MARGINALIZED GROUPS SO-MOF-276315-CS-CQS / C onsultancy to identify the de Enabling Financial and Digit Consultant Qualifi Under Implement IDA / D8430 Prior Open - National 140,000.00 0.00 2022-02-07 2022-02-03 2022-02-28 2022-02-06 2022-04-05 2022-06-21 2022-04-09 2022-09-19 2022-04-27 2022-10-24 mand for Business Developm al Services cation Selection ation ent Services (BDS) by MSMEs in Somalia SO-MOF-299092-CS-CQS / C Consultant Qualifi Under Implement onsultancy Services that pro TF / B5774 Strengthening Institutions Prior Open - National 144,000.00 0.00 2022-06-13 2022-07-26 2022-07-04 2022-08-14 2022-08-17 2023-04-07 2022-09-16 2022-10-21 2023-10-21 cation Selection ation vide IFRSs to Central Bank of Somalia SO-MOF-299099-CS-QCBS / Technical Advisory Services f or the Development of a Nati onal Cybersecurity Policy, Str Quality And Cost- Open - Internationa Under Implement ategy, Governance and Instit TF / B5774 Strengthening Institutions Prior 300,000.00 0.00 2022-06-13 2022-06-16 2022-07-04 2022-07-18 2022-08-17 2022-09-14 2022-10-14 2022-11-18 2022-12-23 2023-12-23 Based Selection l ation utional Structure as well as G uidelines for the Protection of Critical Information Infrastruc ture for Ministry of Communi cation & Technology SO-MOF-128027-CS-CQS / C onsultancy services for indep Enabling Financial and Digit Consultant Qualifi endent third-party assessme IDA / D4330 Post Open - National 250,000.00 0.00 Canceled 2019-08-23 2019-09-03 2019-09-13 2019-09-11 2019-10-27 2019-11-14 2019-11-26 2019-12-31 2020-06-28 al Services cation Selection nt of financial institution accr editation under the MSME Fin ancing Facility SO-MOF-345386-CS-CQS / C onsultancy Service for Techni Consultant Qualifi Open - Internationa TF / A9642 Strengthening Institutions Prior 100,000.00 0.00 Under Review 2023-03-02 2023-03-23 2023-05-06 2023-06-05 2023-07-10 2024-01-06 cal Assistance to Establish a cation Selection l Market Observatory- NCA SO-MOF-360637-CS-CQS / C onsultancy Services to Under Consultant Qualifi Open - Internationa Under Implement TF / B5774 Strengthening Institutions Prior 150,000.00 0.00 2023-05-28 2023-06-15 2023-06-18 2023-08-01 2023-08-31 2023-10-05 2024-01-03 take Assessment for establis cation Selection l ation hing National CERT at NCA SO-MOF-360536-CS-CQS / C onsultancy Services to Provid Enabling Financial and Digit Consultant Qualifi Under Implement IDA / D4330 Prior Limited 30,000.00 0.00 2023-05-21 2023-05-30 2023-06-04 2023-07-04 2023-08-08 2023-11-06 e Financial Audit Services to al Services cation Selection ation Gargaara Company Limited SO-MOF-362870-CS-CQS / D evelopment of DPA Strategic Plan, Budget and Financial S Enabling Financial and Digit Consultant Qualifi Open - Internationa Pending Impleme IDA / D4330 Prior 200,000.00 0.00 2023-06-05 2023-06-26 2023-08-09 2023-09-08 2023-10-13 2024-04-10 ustainability Plan; 5-year HR al Services cation Selection l ntation and Talent Plan; 5-year Capa city Building Plan for or the D PA SO-MOF-362874-CS-CQS / C onsultancy service for Develo Enabling Financial and Digit Consultant Qualifi Open - Internationa Pending Impleme TF / B5774 Prior 150,000.00 0.00 2023-06-05 2023-06-26 2023-08-09 2023-09-08 2023-10-13 2024-04-10 ping a communications strat al Services cation Selection l ntation egy/engagement strategy for DPA INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SO-MOF-111310-CS-INDV / C Project Management and Co Individual Consult IDA / D4330 Prior Open 120,000.00 156,000.00 Signed 2019-04-27 2019-04-25 2019-05-31 2019-07-06 2019-06-15 2019-07-16 2019-07-12 2019-07-16 2020-01-08 hief Executive Officer( Garga ordination ant Selection ara) SO-MOF-113319-CS-INDV / G Project Management and Co Individual Consult IDA / D4330 Prior Open 77,000.00 338,760.00 Signed 2019-05-06 2019-05-06 2019-05-27 2019-07-15 2019-06-04 2019-07-16 2019-06-27 2019-07-17 2019-12-24 argaara Treasurer ordination ant Selection SO-MOF-113749-CS-INDV / E Project Management and Co Individual Consult nvironmental and Social Safe IDA / D4330 Prior Open 100,000.00 199,920.00 Signed 2019-05-28 2019-06-02 2019-07-16 2019-09-10 2019-08-06 2019-09-30 2019-09-10 2019-10-03 2020-09-11 ordination ant Selection guard Consultant SO-MOF-116571-CS-INDV / C Project Management and Co Individual Consult IDA / D4330 Prior Open 70,000.00 0.00 Canceled 2019-05-29 2019-05-31 2019-07-17 2019-08-07 2019-09-11 2020-03-09 ommunication Officer ordination ant Selection SO-MOF-118083-CS-INDV / P Individual Consult olicy Advisor-Ministry of Post IDA / D4330 Strengthening Institutions Prior Open 60,000.00 0.00 Canceled 2019-06-10 2019-07-29 2019-08-19 2019-09-23 2020-03-21 ant Selection and Telecommunication Auth ority SO-MOF-118084-CS-INDV / C Individual Consult IDA / D4330 Strengthening Institutions Prior Open 60,000.00 194,040.00 Signed 2019-06-10 2019-10-08 2019-07-29 2020-05-09 2019-08-19 2020-05-27 2019-09-23 2020-05-30 2020-03-21 yber Security Specialist-NCA ant Selection SO-MOF-118086-CS-INDV / F Individual Consult IDA / D4330 Strengthening Institutions Prior Open 60,000.00 194,040.00 Signed 2019-06-10 2019-06-11 2019-07-29 2019-11-30 2019-08-19 2019-12-10 2019-09-23 2020-01-01 2020-03-21 inance and Accounting Exper ant Selection t-NCA SO-MOF-118091-CS-INDV / S Individual Consult IDA / D4330 Strengthening Institutions Prior Open 60,000.00 194,040.00 Signed 2019-06-10 2019-06-11 2019-07-29 2019-12-02 2019-08-19 2019-12-10 2019-09-23 2020-01-01 2020-03-21 pectrum Management Expert ant Selection -NCA SO-MOF-118092-CS-INDV / T Individual Consult IDA / D4330 Strengthening Institutions Prior Open 60,000.00 220,140.00 Signed 2019-06-10 2019-06-11 2019-07-29 2019-12-01 2019-08-19 2019-12-09 2019-09-23 2020-01-01 2020-03-21 eam Coordinator-NCA ant Selection SO-MOF-118093-CS-INDV / L Individual Consult IDA / D4330 Strengthening Institutions Prior Open 60,000.00 194,040.00 Signed 2019-06-10 2019-06-11 2019-07-29 2019-11-30 2019-08-19 2019-12-10 2019-09-23 2020-01-01 2020-03-21 egal and Regulatory Advisor ant Selection SO-MOF-118658-CS-INDV / P Individual Consult IDA / D4330 Strengthening Institutions Prior Open 60,000.00 72,000.00 Signed 2019-06-17 2019-06-13 2019-08-05 2019-12-02 2019-08-26 2019-12-10 2019-09-30 2019-12-16 2020-03-28 olicy Advisor-MPT ant Selection Page 5 SO-MOF-119553-CS-INDV / I T System Integrator – Integra Enabling Financial and Digit Individual Consult tion of the SFMIS with the CB IDA / D4330 Prior Open 80,000.00 0.00 Canceled 2019-06-20 2019-07-09 2019-07-23 2019-07-30 2019-08-10 2020-04-30 al Services ant Selection S Financial Systems and Oth er external Systems ( Office of Accountant General) SO-MOF-126312-CS-INDV / F Project Management and Co Individual Consult IDA / D4330 Prior Open 72,000.00 177,120.00 Signed 2019-08-11 2019-08-19 2019-09-29 2019-12-01 2019-10-09 2019-12-09 2019-10-24 2019-12-10 2020-08-30 inancial Institutions Analyst ordination ant Selection SO-MOF-132967-CS-INDV / T echnical assistant - Institutio Individual Consult nal development, Administra TF / A9642 Strengthening Institutions Prior Open 70,000.00 0.00 Canceled 2019-09-09 2019-10-28 2019-11-18 2019-12-23 2020-08-31 ant Selection tion and Human resource ma nagement for the Office of Ac countant General SO-MOF-132969-CS-INDV / P Project Management and Co Individual Consult TF / A9642 Prior Direct 125,640.00 230,460.00 Signed 2019-09-09 2019-10-18 2019-09-19 2019-10-17 2019-10-10 2019-11-25 2019-11-14 2019-12-08 2021-08-10 rocurement Specialist-PIU ordination ant Selection SO-MOF-133522-CS-INDV / P Project Management and Co Individual Consult rocurement and Contract Ma TF / A9642 Prior Limited 70,000.00 0.00 Canceled 2019-09-13 2019-09-18 2019-10-09 2019-11-13 2020-09-30 ordination ant Selection nager-Payment System and Regtech SO-MOF-135080-CS-INDV / P Project Management and Co Individual Consult Under Implement rocurement and Contract Ma TF / A9642 Prior Limited 60,000.00 0.00 2019-09-24 2019-09-23 2019-09-29 2019-09-30 2019-10-18 2020-10-15 ordination ant Selection ation nagement Consultant SO-MOF-133524-CS-INDV / O Project Management and Co Individual Consult TF / A9642 Prior Open 60,000.00 0.00 Canceled 2019-09-13 2019-09-23 2019-11-01 2019-11-02 2019-11-10 2020-09-30 perations Officer for SCALED- ordination ant Selection UP SO-MOF-139422-CS-CDS / IT System Integrator – Integrati on of the SFMIS with the CBS TF / A9642 Strengthening Institutions Prior Direct Selection Direct 84,000.00 216,000.00 Signed 2019-10-13 2019-10-14 2019-10-23 2020-03-01 2019-11-09 2020-05-15 2020-10-01 Financial Systems and Other external Systems ( Office of Accountant General) SO-MOF-139423-CS-INDV / N Individual Consult TF / A9642 Strengthening Institutions Prior Open 36,000.00 145,220.00 Signed 2019-10-14 2019-11-06 2019-11-17 2020-03-19 2019-11-22 2021-09-05 2019-12-09 2021-09-20 2020-11-30 CA Focal Point ant Selection SO-MOF-139429-CS-INDV / T echnical assistant - Institutio Individual Consult TF / A9642 Strengthening Institutions Prior Open 60,000.00 0.00 Canceled 2019-10-14 2019-11-08 2019-11-22 2019-12-04 2019-12-21 2020-12-22 nal development, Administra ant Selection tion and Human resource ma nagement SO-MOF-139430-CS-INDV / T Individual Consult echnical assistant – Treasury TF / A9642 Strengthening Institutions Prior Open 60,000.00 0.00 Canceled 2019-10-14 2019-11-08 2019-11-08 2019-11-16 2019-12-04 2020-11-30 ant Selection and Payroll Management SO-MOF-139650-CS-INDV / T Individual Consult TF / A9642 Strengthening Institutions Prior Open 72,000.00 0.00 Canceled 2019-10-15 2019-11-08 2019-11-18 2019-11-23 2019-12-08 2020-11-30 echnical assistant - Cash Man ant Selection agement SO-MOF-139652-CS-INDV / T Individual Consult echnical assistant - Internal c TF / A9642 Strengthening Institutions Prior Open 72,000.00 129,360.00 Signed 2019-10-15 2019-11-08 2019-11-15 2020-06-19 2019-11-20 2020-06-26 2019-12-08 2020-07-23 2020-11-30 ant Selection ontrols and compliance SO-MOF-144735-CS-CDS / Fi Project Management and Co TF / A9642 Prior Direct Selection Direct 80,000.00 230,460.00 Signed 2019-11-12 2019-12-11 2019-11-22 2020-01-15 2019-11-30 2020-02-03 2020-11-28 nancial Management Speciali ordination st- PIU SO-MOF-147501-CS-INDV / A Enabling Financial and Digit Individual Consult Under Implement dministrative Assistant for Di TF / A9642 Prior Open 40,000.00 0.00 2019-11-30 2020-06-22 2019-12-22 2019-12-26 2020-01-12 2020-12-31 al Services ant Selection ation gital ID Task Force SO-MOF-148232-CS-INDV / P Project Management and Co rocurement and Contract Ma TF / A9642 Prior Direct Selection Direct 60,000.00 278,775.00 Signed 2019-12-06 2019-12-04 2019-12-16 2019-12-11 2019-12-27 2020-01-03 2020-12-26 ordination nagement Consultant SO-MOF-148234-CS-CDS / Pr Project Management and Co TF / A9642 Prior Direct Selection Direct 63,000.00 194,040.00 Signed 2019-12-05 2020-01-26 2019-12-15 2020-02-12 2019-12-25 2020-05-16 2020-12-24 icing and Interconnection Ex ordination pert SO-MOF-150482-CS-INDV / T echnical Assistant-Public Sect Individual Consult TF / A9642 Strengthening Institutions Prior Open 60,000.00 194,040.00 Signed 2019-12-18 2020-01-09 2020-01-12 2020-06-19 2020-01-17 2020-06-26 2020-01-26 2020-07-12 2020-12-31 or Accounting and Reporting ant Selection for Office of Accountant Gen eral SO-MOF-132860-CS-INDV / A Enabling Financial and Digit Individual Consult dministrative Assistant for G IDA / D4330 Prior Open 40,000.00 0.00 Canceled 2019-09-09 2019-09-11 2019-10-28 2019-11-18 2019-12-23 2020-08-31 al Services ant Selection argaara Company Limited SO-MOF-154543-CS-INDV / A Project Management and Co Individual Consult TF / A9642 Prior Open 40,000.00 104,940.00 Signed 2020-01-24 2020-01-28 2020-02-16 2020-03-16 2020-02-24 2020-03-30 2020-03-08 2020-04-03 2021-03-08 dministrative Assistant for G ordination ant Selection argaara SO-MOF-155128-CS-INDV / S Individual Consult enior System Analyst for Offi TF / A9642 Strengthening Institutions Prior Open 70,000.00 0.00 Canceled 2020-01-24 2020-01-28 2020-02-19 2020-02-22 2020-03-06 2021-03-06 ant Selection ce of Accountant General SO-MOF-155131-CS-INDV / D Individual Consult atabase Administrator for Off TF / A9642 Strengthening Institutions Prior Open 60,000.00 0.00 Canceled 2020-01-24 2020-01-28 2020-02-22 2020-02-27 2020-03-13 2021-03-13 ant Selection ice of Accountant General SO-MOF-155135-CS-INDV / S Individual Consult ystem Developer for Office of TF / A9642 Strengthening Institutions Prior Open 60,000.00 0.00 Canceled 2020-01-24 2020-01-28 2020-02-10 2020-02-12 2020-02-26 2021-02-25 ant Selection Accountant General SO-MOF-139424-CS-CDS / Li TF / A9642 Strengthening Institutions Prior Direct Selection Direct 84,000.00 0.00 Canceled 2019-10-14 2019-10-14 2019-10-24 2019-11-10 2020-11-01 censing Expert SO-MOF-118090-CS-INDV / P Individual Consult IDA / D4330 Strengthening Institutions Prior Open 60,000.00 0.00 Canceled 2019-06-10 2019-06-11 2019-07-29 2019-08-19 2019-09-23 2020-03-21 ricing and Interconnection Ex ant Selection pert-NCA SO-MOF-118085-CS-INDV / Li Individual Consult IDA / D4330 Strengthening Institutions Prior Open 60,000.00 0.00 Canceled 2019-06-10 2019-06-11 2019-07-29 2019-08-19 2019-09-23 2020-03-21 censing Specialist-NCA ant Selection SO-MOF-155915-CS-CDS / Li TF / A9642 Strengthening Institutions Prior Direct Selection Direct 60,000.00 194,040.00 Signed 2020-01-29 2020-01-28 2020-02-08 2020-02-09 2020-02-17 2020-05-16 2021-02-16 censing Expert SO-MOF-153723-CS-INDV / C Project Management and Co Individual Consult TF / A9642 Prior Open 60,000.00 0.00 Canceled 2020-01-30 2020-02-28 2020-03-05 2020-03-21 2021-03-21 ommunication Specialist ordination ant Selection Page 6 SO-MOF-153788-CS-INDV / Enabling Financial and Digit Individual Consult Under Implement TF / A9642 Prior Open 120,000.00 0.00 2020-01-30 2020-02-23 2020-02-25 2020-03-13 2021-03-13 Managing Project Director- Di al Services ant Selection ation gital ID SO-MOF-157418-CS-INDV / A Individual Consult Under Implement dministration and Finance Co TF / A9642 Strengthening Institutions Prior Limited 60,000.00 0.00 2020-02-13 2020-02-23 2020-02-18 2020-02-22 2020-02-28 2021-02-27 ant Selection ation nsultant for FRC SO-MOF-157417-CS-INDV / R Individual Consult Under Implement TF / A9642 Strengthening Institutions Prior Limited 60,000.00 0.00 2020-02-13 2020-02-23 2020-02-18 2020-02-22 2020-03-06 2021-03-06 egulatory Consultant for FRC ant Selection ation SO-MOF-163669-CS-INDV / F Individual Consult Under Implement TF / A9642 Strengthening Institutions Prior Open 40,000.00 0.00 2020-03-09 2020-04-01 2020-04-08 2020-08-05 2020-04-10 2020-08-19 2020-04-27 2021-04-27 ocal Point-FRC ant Selection ation SO-MOF-167102-CS-INDV / S Individual Consult TF / A9642 Strengthening Institutions Prior Limited 120,000.00 120,000.00 Signed 2020-04-03 2020-04-22 2020-04-08 2020-06-21 2020-04-12 2020-06-26 2020-04-29 2020-07-09 2020-08-27 trategic Advisor for Central B ant Selection ank SO-MOF-167208-CS-INDV / A Individual Consult Under Implement TF / A9642 Strengthening Institutions Prior Limited 60,000.00 0.00 2020-04-04 2020-04-05 2020-04-09 2020-04-12 2020-04-29 2021-04-29 dministration and Finance Co ant Selection ation nsultant SO-MOF-167209-CS-INDV / R Individual Consult Under Implement TF / A9642 Strengthening Institutions Prior Limited 60,000.00 0.00 2020-04-04 2020-04-05 2020-04-09 2020-05-06 2020-04-14 2020-05-28 2020-05-01 2021-05-01 egulatory Expert ant Selection ation SO-MOF-168266-CS-CDS / PI Project Management and Co TF / A9642 Prior Direct Selection Direct 111,480.00 0.00 Canceled 2020-04-13 2020-04-23 2020-04-30 2020-06-05 U Coordinator of SCALED-UP ordination SO-MOF-169310-CS-INDV / P Project Management and Co Individual Consult roject Director-Digital Identifi TF / A9642 Prior Limited 360,000.00 156,000.00 Signed 2020-04-22 2020-04-23 2020-04-27 2020-05-01 2020-05-01 2020-05-17 2020-05-17 2020-05-20 2021-05-17 ordination ant Selection cation Program SO-MOF-169477-CS-INDV / R Individual Consult Under Implement estructuring Project Manager TF / A9642 Strengthening Institutions Prior Open 84,000.00 0.00 2020-04-23 2020-05-01 2020-05-15 2020-05-18 2020-06-03 2021-06-03 ant Selection ation -Central Bank SO-MOF-171854-CS-INDV / L Individual Consult Under Implement egal drafting and translator f TF / A9642 Strengthening Institutions Prior Open 60,000.00 0.00 2020-05-05 2020-06-23 2020-07-14 2020-08-18 2021-08-18 ant Selection ation or office of the Attorney Gen eral SO-MOF-172367-CS-INDV / P roject Consultant Finance an Individual Consult TF / A9642 Strengthening Institutions Prior Limited 48,000.00 118,560.00 Signed 2020-05-11 2020-06-08 2020-05-16 2020-09-01 2020-05-28 2020-09-07 2020-06-14 2020-09-14 2021-06-14 d Administration- Somalia Pa ant Selection yment Switch Project SO-MOF-172370-CS-INDV / P Individual Consult ROJECT CONSULTANT SWITC TF / A9642 Strengthening Institutions Prior Limited 60,000.00 118,560.00 Signed 2020-05-11 2020-06-08 2020-05-16 2020-07-28 2020-05-27 2020-09-01 2020-06-13 2020-09-18 2021-06-13 ant Selection H OPERATIONS SO-MOF-172373-CS-INDV / P ROJECT CONSULTANT, INFOR Individual Consult Under Implement TF / A9642 Strengthening Institutions Prior Limited 72,000.00 0.00 2020-05-12 2020-06-08 2020-05-17 2020-07-28 2020-05-30 2020-09-01 2020-06-16 2021-06-16 MATION TECHNOLOGY-SOMA ant Selection ation LIA PAYMENT SWITCH PROJE CT SO-MOF-176000-CS-CDS / B TF / A9642 Strengthening Institutions Prior Direct Selection Direct 500,000.00 500,510.00 Signed 2020-05-31 2020-06-23 2020-06-10 2020-08-27 2020-07-16 2020-09-17 2023-07-16 usiness Automation Registrat ion PhaseII SO-MOF-178403-CS-INDV / A Individual Consult TF / A9642 Strengthening Institutions Prior Limited 60,000.00 0.00 Canceled 2020-06-10 2020-06-15 2020-06-25 2020-07-12 2021-07-12 dmin/Finance Consultant for ant Selection FRC SO-MOF-175994-CS-INDV / N Individual Consult TF / A9642 Strengthening Institutions Prior Direct 80,000.00 210,000.00 Signed 2020-05-31 2020-09-03 2020-06-10 2020-09-14 2020-07-01 2020-09-23 2020-08-05 2020-10-04 2021-08-05 ational Risk Assessment Coor ant Selection dinator SO-MOF-178462-CS-INDV / S omali Legislative Drafting Ex Enabling Financial and Digit Individual Consult Under Implement TF / A9642 Prior Open 60,000.00 0.00 2020-06-10 2020-06-11 2020-07-09 2020-07-14 2020-07-30 2021-07-30 pert for the Digital ID Project al Services ant Selection ation for Office of State Attorney G eneral SO-MOF-179535-CS-INDV / A Individual Consult Under Implement TF / A9642 Strengthening Institutions Prior Open 60,000.00 0.00 2020-06-15 2020-06-26 2020-07-06 2020-09-01 2020-07-08 2020-10-04 2020-07-23 2021-07-23 dmin/Finance Consultant for ant Selection ation FRC SO-MOF-183387-CS-INDV / C Enabling Financial and Digit Individual Consult Under Implement hief Technology Officer (CTO) TF / A9642 Prior Open 77,400.00 0.00 2020-07-13 2020-07-22 2020-08-05 2020-08-07 2020-08-21 2021-08-21 al Services ant Selection ation for Digital ID Project SO-MOF-183388-CS-INDV / S Enabling Financial and Digit Individual Consult Under Implement enior Network and Security E TF / A9642 Prior Open 77,400.00 0.00 2020-07-13 2020-07-22 2020-08-06 2020-08-09 2020-08-24 2021-08-24 al Services ant Selection ation ngineer - (SNSE) for Digital I D Project SO-MOF-183390-CS-INDV / S Enabling Financial and Digit Individual Consult Under Implement enior Solutions Architect for TF / A9642 Prior Open 77,400.00 0.00 2020-07-13 2020-07-22 2020-08-10 2020-08-13 2020-08-27 2021-08-27 al Services ant Selection ation Digital ID Project SO-MOF-185120-CS-CDS / I Under Implement mplementation Project Mana TF / A9642 Strengthening Institutions Prior Direct Selection Direct 72,000.00 0.00 2020-07-24 2020-07-29 2020-08-03 2020-09-02 2020-08-08 2021-02-04 ation ger- Payment System SO-MOF-187101-CS-INDV / A dvisor - Business Registration Individual Consult TF / A9642 Strengthening Institutions Prior Open 60,000.00 59,280.00 Signed 2020-08-06 2020-09-14 2020-09-01 2021-04-20 2020-09-05 2021-04-26 2020-09-20 2021-05-18 2021-09-20 Services (BRS) Outreach and ant Selection MSME Engagement SO-MOF-187103-CS-INDV / I Individual Consult TF / A9642 Strengthening Institutions Prior Open 60,000.00 118,560.00 Signed 2020-08-07 2020-09-15 2020-09-02 2021-02-11 2020-09-05 2021-02-16 2020-09-21 2021-03-18 2021-09-21 CT Advisor for OSS and ICT In ant Selection frastructure SO-MOF-190091-CS-CDS / Le gal and Regulatory Expert for TF / A9642 Strengthening Institutions Prior Direct Selection Direct 67,770.00 180,720.00 Signed 2020-08-28 2020-09-15 2020-09-07 2020-09-29 2020-09-15 2020-10-06 2021-06-12 Central Bank SO-MOF-190093-CS-CDS / H uman Resource Management TF / A9642 Strengthening Institutions Prior Direct Selection Direct 87,480.00 174,960.00 Signed 2020-08-28 2020-09-15 2020-09-07 2020-09-29 2020-09-18 2020-11-13 2021-09-18 Principal Advisor SO-MOF-190096-CS-CDS / Pr oject Manager- Business Regi TF / A9642 Strengthening Institutions Prior Direct Selection Direct 52,650.00 175,500.00 Signed 2020-08-27 2020-09-18 2020-09-06 2020-09-29 2020-09-20 2020-10-05 2021-06-17 stration Automation SO-MOF-190098-CS-INDV / P Individual Consult TF / A9642 Strengthening Institutions Prior Open 80,000.00 0.00 Signed 2020-08-31 2020-09-07 2020-10-01 2021-09-11 2020-10-04 2021-09-20 2020-10-30 2021-10-30 IU Coordinator for SCALED-U ant Selection P Page 7 SO-MOF-190597-CS-INDV / R Individual Consult TF / A9642 Strengthening Institutions Prior Limited 80,000.00 97,480.00 Signed 2020-08-26 2020-09-07 2020-08-31 2020-10-05 2020-09-03 2020-11-23 2020-09-11 2020-11-23 2020-12-10 estructuring Project Manager ant Selection SO-MOF-193600-CS-INDV / I Individual Consult TF / A9642 Strengthening Institutions Prior Open 60,000.00 190,460.00 Terminated 2020-09-15 2020-09-16 2020-10-11 2020-11-16 2020-10-14 2020-11-25 2020-10-27 2020-11-26 2021-10-27 CT Consultant for Central Ba ant Selection nk SO-MOF-196195-CS-CDS / E Project Management and Co Under Implement TF / A9642 Prior Direct Selection Direct 50,000.00 0.00 2020-09-25 2020-10-05 2020-11-11 2021-05-10 nd SCORE Evaluation Consult ordination ation ant SO-MOF-199766-CS-CDS / Po Under Implement TF / A9642 Strengthening Institutions Prior Direct Selection Direct 40,000.00 0.00 2020-10-16 2020-10-15 2020-10-26 2020-10-21 2020-11-13 2021-05-12 licy Advisor for MPTT ation SO-MOF-199770-CS-INDV / C Individual Consult TF / A9642 Strengthening Institutions Prior Open 72,000.00 204,220.00 Signed 2020-10-17 2020-10-19 2020-11-20 2021-01-21 2020-11-22 2021-02-10 2020-12-07 2021-03-24 2021-12-07 ommunication Consultant ant Selection SO-MOF-201599-CS-CDS / LE GAL EXPERT TO CONDUCT ST AKEHOLDER CONSULTATION S ON FINANCIAL INSTITUTION S BILL, 2020, NATIONAL PAY TF / A9642 Strengthening Institutions Prior Direct Selection Direct 200,000.00 200,000.00 Signed 2020-10-27 2020-11-01 2020-11-06 2020-12-18 2020-11-15 2021-03-02 2021-11-15 MENT SYSTEM BILL, 2020 AN D INSURANCE BILL, 2020 & T O DEVELOP REGULATIONS O N OVERSIGHT OF THE NATIO NAL PAYMENT SYSTEM, REGU LATIONS ON THE OPERATION S OF THE SO-MOF-205624-CS-INDV / I Individual Consult Under Implement T Consultant for Somalia Pay TF / A9642 Strengthening Institutions Prior Open 72,000.00 0.00 2020-11-23 2020-12-14 2020-12-21 2020-12-24 2021-01-06 2022-01-06 ant Selection ation ment Switch Project SO-MOF-206189-CS-INDV / C onsultant to Develop of an e- Individual Consult TF / A9642 Strengthening Institutions Prior Open 90,000.00 90,000.00 Signed 2020-11-26 2020-12-09 2020-12-22 2021-05-29 2020-12-25 2021-06-15 2021-01-08 2021-06-26 2021-07-07 Government Strategy and Im ant Selection plementation Roadmap for M PTT SO-MOF-206191-CS-INDV / C Individual Consult Under Implement onsultant to conduct Human TF / A9642 Strengthening Institutions Prior Open 60,000.00 0.00 2020-11-24 2020-12-01 2020-12-23 2021-03-30 2020-12-26 2021-04-21 2021-01-09 2021-07-08 ant Selection ation Capital Development Frame work for NCA SO-MOF-212383-CS-INDV / L Individual Consult Under Implement egal and Regulatory Expert t TF / A9642 Strengthening Institutions Prior Open 90,000.00 0.00 2021-01-08 2021-02-26 2021-03-02 2021-03-27 2022-03-27 ant Selection ation o Assist the MPTT SO-MOF-212387-CS-INDV / E Individual Consult Under Implement -Government Strategy Imple TF / A9642 Strengthening Institutions Prior Open 90,000.00 0.00 2021-01-08 2021-02-26 2021-03-03 2021-03-16 2022-04-04 ant Selection ation mentation Advisor SO-MOF-212389-CS-INDV / C Individual Consult Under Implement yber-security Policy Impleme TF / A9642 Strengthening Institutions Prior Open 90,000.00 0.00 2021-01-08 2021-02-11 2021-03-04 2021-03-20 2021-05-14 ant Selection ation ntation Advisor SO-MOF-215898-CS-INDV / C onsultant to Provide Pre- Pro curement and Project Imple Enabling Financial and Digit Individual Consult mentation Consultancy Servi IDA / D4330 Prior Open 90,000.00 55,000.00 Signed 2021-01-27 2021-01-28 2021-02-25 2021-05-06 2021-02-28 2021-05-24 2021-03-16 2021-05-27 2022-03-16 al Services ant Selection ces for the GARGAARA Finan cial Management and Reporti ng System and Supporting In frastructure SO-MOF-216261-CS-INDV / C Enabling Financial and Digit Individual Consult hief Executive Officer of Garg IDA / D4330 Prior Open 87,480.00 0.00 Signed 2021-01-28 2021-02-01 2021-03-03 2021-08-28 2021-03-08 2021-09-28 2021-03-22 2022-03-22 al Services ant Selection aara Company SO-MOF-218183-CS-INDV / S Project Management and Co Individual Consult ocial Development Specialist TF / A9642 Prior Open 87,000.00 143,580.00 Under Review 2021-02-09 2021-03-15 2021-03-10 2021-06-16 2021-03-13 2021-06-28 2021-03-28 2021-07-07 2022-03-28 ordination ant Selection for SCALED-UP PIU SO-MOF-218204-CS-INDV / I Individual Consult TF / A9642 Strengthening Institutions Prior Open 72,000.00 73,380.00 Terminated 2021-02-09 2021-02-15 2021-03-06 2021-04-15 2021-03-09 2021-05-05 2021-03-24 2021-05-30 2022-03-24 T Consultant for Switch Proje ant Selection ct SO-MOF-220162-CS-INDV / Project Management and Co Individual Consult Under Implement Monitoring and Evaluation Sp TF / A9642 Prior Open 72,000.00 0.00 2021-02-19 2021-03-08 2021-03-20 2021-03-22 2021-04-06 2022-04-06 ordination ant Selection ation ecialist for SCALED-UP Projec t SO-MOF-227745-CS-INDV / C Individual Consult Under Implement TF / A9642 Strengthening Institutions Prior Open 60,000.00 0.00 2021-04-06 2021-05-01 2021-05-10 2021-11-22 2021-05-13 2021-11-29 2021-05-30 2022-05-30 ommunication Consultant for ant Selection ation MoCI SO-MOF-227746-CS-INDV / B Individual Consult Under Implement usiness Planning and Policy A TF / A9642 Strengthening Institutions Prior Open 60,000.00 0.00 2021-04-06 2021-05-01 2021-05-06 2022-02-03 2021-05-07 2022-02-09 2021-05-22 2022-05-22 ant Selection ation dvisor for MoCI SO-MOF-228108-CS-INDV / Monitoring, Evaluation and L Enabling Financial and Digit Individual Consult IDA / D4330 Prior Open 60,000.00 0.00 Signed 2021-04-12 2021-06-08 2021-05-31 2022-02-17 2021-06-21 2022-03-01 2021-07-26 2023-04-16 2022-07-26 earning (ME&L) Consultant fo al Services ant Selection r Gargaara Company Limited SO-MOF-231333-CS-INDV / E Individual Consult Under Implement TF / A9642 Strengthening Institutions Prior Open 72,000.00 0.00 2021-04-26 2021-07-27 2021-06-14 2021-07-05 2021-08-09 2022-08-09 mbedded Local Legal Advisor ant Selection ation SO-MOF-234389-CS-INDV / A Enabling Financial and Digit Individual Consult IDA / D4330 Prior Open 40,000.00 67,440.00 Terminated 2021-05-14 2021-06-08 2021-06-12 2022-05-17 2021-06-15 2022-05-27 2021-06-30 2022-06-20 2022-06-30 ccountant, Gargaara Compan al Services ant Selection y Limited SO-MOF-234391-CS-INDV / H Enabling Financial and Digit Individual Consult Pending Impleme ead of Finance, Gargaara Co IDA / D4330 Prior Open 60,000.00 0.00 2021-05-14 2021-06-12 2021-06-17 2021-07-03 2022-07-03 al Services ant Selection ntation mpany Limited SO-MOF-234398-CS-INDV / E nvironmental and Social Risk Enabling Financial and Digit Individual Consult IDA / D4330 Prior Open 60,000.00 0.00 Signed 2021-05-14 2021-06-08 2021-06-12 2022-03-03 2021-06-16 2022-03-21 2021-07-01 2023-04-16 2022-07-01 Management Officer, Gargaa al Services ant Selection ra Company Limited SO-MOF-238133-CS-INDV / G Project Management and Co Individual Consult Under Implement TF / A9642 Prior Open 60,000.00 0.00 2021-06-10 2021-07-22 2021-07-14 2021-09-29 2021-08-04 2021-10-13 2021-08-19 2022-08-19 ender Based Violence (GBV) ordination ant Selection ation Advisor Page 8 SO-MOF-244708-CS-INDV / I NTERNATIONAL CONSULTAN T TO CONDUCT A FEASIBILIT Enabling Financial and Digit Individual Consult Y STUDY FOR THE ESTABLISH IDA / D4330 Prior Open 30,000.00 42,000.00 Signed 2021-07-26 2021-07-27 2021-08-29 2022-02-16 2021-09-19 2022-03-01 2021-10-24 2022-03-21 2022-04-22 al Services ant Selection MENT OF A PARTIAL CREDIT GUARANTEE (PCG) SCHEME OR OTHER RISK SHARING ME CHANISM IN SOMALIA SO-MOF-244701-CS-INDV / Project Management and Co Individual Consult TF / A9642 Prior Open 87,000.00 0.00 Signed 2021-07-26 2021-07-26 2021-09-13 2021-10-03 2021-10-04 2021-10-27 2021-11-08 2023-04-24 2022-11-08 Monitoring and Evaluation Of ordination ant Selection ficer SO-MOF-245275-CS-CDS / C onsultancy Services To Provi Enabling Financial and Digit Under Implement IDA / D4330 Prior Direct Selection Direct 150,000.00 0.00 2021-07-27 2021-09-13 2021-08-06 2021-12-14 2021-08-18 2022-08-18 de Legal Advisory Services to al Services ation Gargaara Company Limited SO-MOF-245277-CS-INDV / P Project Management and Co Individual Consult Under Implement roject Assistant for SCALED-U TF / A9642 Prior Open 40,000.00 0.00 2021-07-27 2021-07-27 2021-08-30 2021-10-03 2021-08-31 2021-10-23 2021-09-12 2022-09-12 ordination ant Selection ation P Project PIU SO-MOF-245864-CS-CDS / Po Under Implement licy Advisor and Focal Point o TF / A9642 Strengthening Institutions Prior Direct Selection Direct 60,000.00 0.00 2021-08-02 2021-07-30 2021-08-12 2021-08-23 2021-08-19 2022-08-19 ation f SCALED-UP Project SO-MOF-246212-CS-INDV / e Individual Consult Under Implement -Government Strategy Devel TF / A9642 Strengthening Institutions Prior Open 90,000.00 0.00 2021-07-31 2021-08-16 2021-08-29 2021-11-24 2021-09-02 2021-12-08 2021-09-15 2022-09-15 ant Selection ation opment and Implementation Advisor SO-MOF-248595-CS-INDV / C Project Management and Co Individual Consult Under Implement TF / A9642 Prior Open 60,000.00 0.00 2021-08-20 2021-08-25 2021-09-11 2021-11-03 2021-09-14 2021-11-11 2021-10-01 2022-10-01 ommunication Consultant for ordination ant Selection ation PIU SO-MOF-253392-CS-CDS / C onsultancy service to prepar e financial sustainability plan Project Management and Co Under Implement s for Central Bank and Minist TF / A9642 Prior Direct Selection Direct 170,000.00 0.00 2021-09-17 2021-10-13 2021-10-20 2022-06-27 ordination ation ry of Commerce and Industry to assist with fiscal planning and sustainability of services delivered & institutional effec tiveness SO-MOF-253780-CS-CDS / E Project Management and Co Under Implement nvironmental and Social Safe TF / A9642 Prior Direct Selection Direct 87,000.00 0.00 2021-09-20 2021-09-29 2021-09-30 2021-10-03 2021-10-09 2022-10-09 ordination ation guard Consultant for SCALED -UP PIU SO-MOF-258660-CS-INDV / I Individual Consult Pending Impleme TF / A9642 Strengthening Institutions Prior Open 72,000.00 0.00 2021-10-26 2021-11-26 2021-11-29 2021-12-15 2022-12-15 CT Consultant for Switch Proj ant Selection ntation ect SO-MOF-256363-CS-INDV / I Individual Consult Under Implement TF / A9642 Strengthening Institutions Prior Open 72,000.00 0.00 2021-10-29 2021-11-30 2021-11-24 2021-11-26 2021-12-13 2022-12-13 CT Consultant for SPS project ant Selection ation SO-MOF-266890-CS-INDV / E mbedded Local Legal Advisor Individual Consult Under Implement TF / B5774 Strengthening Institutions Prior Open 60,000.00 0.00 2021-12-08 2021-12-21 2022-01-03 2022-01-05 2022-01-21 2023-01-21 for Ministry of Communicatio ant Selection ation n and Technology SO-MOF-266891-CS-INDV / F Individual Consult Under Implement inance and Administration Co TF / A9642 Strengthening Institutions Prior Open 72,000.00 0.00 2021-12-08 2022-02-14 2022-01-03 2023-02-27 2022-01-06 2023-03-15 2022-01-22 2023-01-22 ant Selection ation nsultant for FRC SO-MOF-266892-CS-INDV / E Individual Consult Under Implement TF / A9642 Strengthening Institutions Prior Open 40,000.00 0.00 2021-12-08 2022-01-06 2022-01-06 2022-04-09 2022-01-09 2022-04-24 2022-01-26 2023-01-26 xecutive Assistant for FRC ant Selection ation SO-MOF-272062-CS-INDV / R Individual Consult Under Implement TF / A9642 Strengthening Institutions Prior Open 90,000.00 0.00 2022-01-10 2022-02-23 2022-02-18 2023-02-28 2022-02-21 2023-03-26 2022-03-09 2023-03-09 egulatory Expert ant Selection ation SO-MOF-272063-CS-CDS / C onsulting Services for CBS str Pending Impleme ongrooms on Design and Eng TF / A9642 Strengthening Institutions Prior Direct Selection Direct 70,000.00 0.00 2022-01-10 2022-01-20 2022-01-29 2022-07-28 ntation ineering, Required by CBS St rongrooms & Incineration Fac ilities SO-MOF-273543-CS-INDV / T echnical Advisor on Cybersec Individual Consult Under Implement TF / B5774 Strengthening Institutions Prior Open 87,000.00 0.00 2022-01-24 2022-02-06 2022-02-22 2022-10-12 2022-03-04 2022-10-31 2022-04-08 2023-04-08 urity for Ministry of Communi ant Selection ation cation and Technology SO-MOF-266895-CS-INDV / I nternational consultant to Co nduct a review of Institutiona Enabling Financial and Digit Individual Consult l Development Plan (IDP) exp TF / B5774 Post Open 100,000.00 0.00 Canceled 2021-12-08 2021-12-21 2022-01-26 2022-01-28 2022-02-16 2022-08-15 al Services ant Selection erience in the SCALED-UP pro ject and identify incentives o ptions to improve IDP owners hip and performance SO-MOF-281989-CS-INDV / C Enabling Financial and Digit Individual Consult Under Implement onsultant to develop Gargaar IDA / D4330 Prior Limited 14,000.00 0.00 2022-03-03 2022-03-21 2022-03-08 2022-03-14 2022-04-18 2022-10-15 al Services ant Selection ation a Company Profile and Annua l Report Writer SO-MOF-287354-CS-INDV / I Individual Consult Under Implement TF / A9642 Strengthening Institutions Prior Open 72,000.00 0.00 2022-04-04 2022-08-22 2022-05-03 2022-05-06 2022-05-23 2023-05-18 CT Consultant for Switch Proj ant Selection ation ect SO-MOF-295539-CS-CDS / Po licy Advisor/SCALED-UP Focal TF / B5774 Strengthening Institutions Prior Direct Selection Direct 100,000.00 0.00 Signed 2022-05-21 2022-06-02 2022-05-31 2022-06-07 2022-08-04 2023-05-30 2023-08-04 point for Ministry of Commun ication and Technology SO-MOF-297512-CS-INDV / P Individual Consult Under Implement TF / B5774 Strengthening Institutions Prior Open 72,000.00 0.00 2022-05-31 2022-08-16 2022-07-19 2022-08-09 2022-09-13 2023-09-13 rocurement Expert for Centra ant Selection ation l Bank SO-MOF-299094-CS-CDS / SF TF / B5774 Strengthening Institutions Prior Direct Selection Direct 96,000.00 0.00 Signed 2022-06-13 2022-06-30 2022-06-23 2022-07-18 2022-08-27 2022-10-02 MIS TA SO-MOF-299095-CS-INDV / E mbedded Advisor for Data Pr Individual Consult TF / B5774 Strengthening Institutions Prior Open 87,000.00 0.00 Under Review 2022-06-13 2022-06-16 2022-08-01 2022-08-22 2022-09-26 2023-09-26 otection (Individual Consulta ant Selection nt) for Ministry of Communic ation and Technology SO-MOF-299596-CS-INDV / I Individual Consult Under Implement TF / B5774 Strengthening Institutions Prior Open 87,000.00 0.00 2022-06-16 2022-07-20 2022-08-04 2022-08-25 2022-09-29 2023-09-29 CT Consultant for Central Ba ant Selection ation nk Page 9 SO-MOF-304330-CS-CDS / C onsultancy Services to Provid Enabling Financial and Digit Under Implement IDA / D8430 Prior Direct Selection Direct - National 30,000.00 0.00 2022-07-18 2022-09-30 2022-07-28 2022-11-01 2022-09-03 2023-03-02 e Financial Audit Services to al Services ation Gargaara Company Limited SO-MOF-304332-CS-CDS / M TF / B5774 Strengthening Institutions Prior Direct Selection Direct - National 120,000.00 0.00 Under Review 2022-07-18 2022-07-25 2022-07-28 2022-07-28 2022-08-26 2023-06-27 2023-08-26 utual Evaluation Coordinator for FRC SO-MOF-304335-CS-CDS / Le gal Advisor for Ministry of Co TF / B5774 Strengthening Institutions Prior Direct Selection Direct - National 60,000.00 0.00 Canceled 2022-07-18 2022-08-14 2022-07-28 2022-10-01 2023-10-01 mmerce and Industry SO-MOF-304503-CS-INDV / I ndividual Consultant Institutional Review and Rest Individual Consult Open - Internationa Under Implement ructuring of the Ministry of C TF / B5774 Strengthening Institutions Prior 100,000.00 0.00 2022-07-18 2022-07-26 2022-09-05 2022-09-26 2022-10-31 2023-04-29 ant Selection l ation ommunications and Technolo gy, as well as development o f a dedicated Ministry 5-year Strategic Plan SO-MOF-304329-CS-INDV / A Enabling Financial and Digit Individual Consult Under Implement ccountant for Gargaara Com IDA / D8430 Prior Limited 70,000.00 0.00 2022-07-27 2022-10-05 2022-08-01 2022-07-28 2022-08-22 2022-10-17 2022-09-26 2023-09-26 al Services ant Selection ation pany Limited SO-MOF-305712-CS-INDV / P Project Management and Co Individual Consult Under Implement rocurement Specialist for PIU TF / A9642 Prior Open - National 80,000.00 0.00 2022-07-25 2022-07-26 2022-08-18 2022-09-22 2022-08-23 2022-10-06 2022-09-16 2023-09-16 ordination ant Selection ation - Ministry of Finance Somalia SO-MOF-319310-CS-CDS / Pr Project Management and Co Direct - Internation ocurement Consultant for PIU TF / A9642 Prior Direct Selection 150,000.00 0.00 Canceled 2022-10-04 2022-10-09 2022-10-31 2023-10-31 ordination al - International SO-MOF-320077-CS-CDS / Pr Project Management and Co Direct - Internation Under Implement ocurement Consultant PIU - I TF / A9642 Prior Direct Selection 150,000.00 0.00 2022-10-06 2022-10-11 2022-10-16 2022-10-13 2022-10-31 2023-10-31 ordination al ation nternational SO-MOF-320415-CS-INDV / R Individual Consult Open - Internationa Pending Impleme eserve Management (RM) an TF / A9642 Strengthening Institutions Prior 96,000.00 0.00 2022-10-13 2022-12-01 2022-12-11 2022-12-31 2023-12-31 ant Selection l ntation d Asset Allocations Consultan t. SO-MOF-323013-CS-INDV / L Individual Consult Open - Internationa Under Implement TF / B5774 Strengthening Institutions Prior 80,000.00 0.00 2023-01-12 2022-12-29 2023-02-16 2023-03-06 2023-04-14 2024-04-13 egal advisor ID ant Selection l ation SO-MOF-325815-CS-INDV / E Individual Consult Open - Internationa TF / B5774 Strengthening Institutions Prior 30,000.00 0.00 Canceled 2023-01-12 2022-12-27 2023-02-24 2023-03-09 2023-03-20 2023-09-16 mbedded Professional Transl ant Selection l ator. SO-MOF-332567-CS-INDV / C Enabling Financial and Digit Individual Consult Open - Internationa Pending Impleme TF / B5774 Prior 80,280.00 0.00 2023-01-24 2023-03-23 2023-04-13 2023-05-18 2023-11-14 ommunication consultant for al Services ant Selection l ntation CBS SO-MOF-340104-CS-INDV / l Enabling Financial and Digit Individual Consult Open - Internationa egal and policy advisor to mi TF / A9642 Prior 60,000.00 0.00 Under Review 2023-02-10 2023-02-13 2023-03-15 2023-03-22 2023-04-12 2024-04-06 al Services ant Selection l nistry of commerce and indu stry SO-MOF-342298-CS-INDV / C Individual Consult Open - Internationa Under Implement TF / A9642 Strengthening Institutions Prior 104,000.00 0.00 2023-02-18 2023-02-13 2023-04-08 2023-04-29 2023-06-03 2024-05-28 ommunication Consultant ant Selection l ation SO-MOF-343936-CS-INDV / S Individual Consult Pending Impleme tatistics Expert for Central Ba TF / A9642 Strengthening Institutions Prior Open - National 90,360.00 0.00 2023-02-22 2023-04-12 2023-05-03 2023-06-07 2024-06-06 ant Selection ntation nk of Somalia SO-MOF-345384-CS-INDV / I Individual Consult Under Implement CT Consultant – Somali Paym TF / B5774 Strengthening Institutions Prior Open - National 70,200.00 0.00 2023-02-28 2023-04-13 2023-04-18 2023-05-09 2023-06-13 2024-06-12 ant Selection ation ent Switch (SPS) SO-MOF-350222-CS-CDS / C onsulting Services for Techni Enabling Financial and Digit Under Implement cal support for an Electronic TF / A9642 Prior Direct Selection Direct - National 119,700.00 0.00 2023-04-03 2023-04-18 2023-04-13 2023-06-29 2023-06-17 2024-06-16 al Services ation Management Information Sy stem for (EMIS – AD) Account ant General office SO-MOF-353257-CS-INDV / s Individual Consult Under Implement TF / B5774 Strengthening Institutions Prior Open - National 91,000.00 0.00 2023-03-30 2023-04-13 2023-05-18 2023-06-08 2023-07-13 2024-07-12 tatistics Expert for CBS ant Selection ation SO-MOF-353293-CS-INDV / F Individual Consult Open - Internationa Under Implement TF / B5774 Strengthening Institutions Prior 90,000.00 0.00 2023-03-30 2023-04-12 2023-05-18 2023-06-08 2023-07-13 2024-07-12 inancial Sector Expert - CBS ant Selection l ation SO-MOF-353315-CS-INDV / O Individual Consult Open - Internationa Under Implement rganization-wide Risk and Co TF / A9642 Strengthening Institutions Prior 102,000.00 0.00 2023-03-30 2023-04-05 2023-05-18 2023-06-08 2023-07-13 2024-07-12 ant Selection l ation mpliance Management Exper t for CBS SO-MOF-353961-CS-INDV / E Individual Consult Under Implement mbedded Professional Transl TF / B5774 Strengthening Institutions Prior Limited 30,000.00 0.00 2023-03-31 2023-04-18 2023-04-05 2023-06-07 2023-04-26 2023-05-31 2023-11-27 ant Selection ation ator for MOCT SO-MOF-360169-CS-INDV / C Individual Consult Pending Impleme TF / B5774 Strengthening Institutions Prior Open - National 76,800.00 0.00 2023-05-10 2023-06-28 2023-07-19 2023-08-23 2024-08-17 ommunications Specialist for ant Selection ntation NIRA SO-MOF-360524-CS-INDV / C Individual Consult Under Implement TF / B5774 Strengthening Institutions Prior Open - National 80,280.00 0.00 2023-05-15 2023-07-03 2023-07-24 2023-08-28 2024-08-22 ybersecurity Specialist for NI ant Selection ation RA SO-MOF-360525-CS-INDV / I Individual Consult Pending Impleme nstitutional Development Ad TF / B5774 Strengthening Institutions Prior Open - National 80,280.00 0.00 2023-05-15 2023-07-03 2023-07-24 2023-08-28 2024-08-22 ant Selection ntation visor for NIRA SO-MOF-360526-CS-INDV / N Individual Consult Pending Impleme TF / B5774 Strengthening Institutions Prior Open - National 80,280.00 0.00 2023-05-15 2023-07-03 2023-07-24 2023-08-28 2024-08-22 etwork Architect consultant f ant Selection ntation or NIRA SO-MOF-360528-CS-INDV / P Individual Consult Pending Impleme TF / B5774 Strengthening Institutions Prior Open - National 80,280.00 0.00 2023-05-15 2023-07-03 2023-07-24 2023-08-28 2024-08-22 olicy and strategy advisor for ant Selection ntation NIRA SO-MOF-360529-CS-INDV / S Individual Consult Pending Impleme oftware Development Special TF / B5774 Strengthening Institutions Prior Open - National 80,280.00 0.00 2023-05-18 2023-07-06 2023-07-27 2023-08-31 2024-08-25 ant Selection ntation ist for NIRA SO-MOF-360530-CS-INDV / S Individual Consult Pending Impleme TF / B5774 Strengthening Institutions Prior Open - National 87,480.00 0.00 2023-05-15 2023-07-03 2023-07-24 2023-08-28 2024-08-22 olutions Architect Advisor for ant Selection ntation NIRA Page 10 SO-MOF-362842-CS-INDV / F Individual Consult Pending Impleme TF / B5774 Strengthening Institutions Prior Open - National 59,280.00 0.00 2023-06-05 2023-07-24 2023-08-14 2023-09-18 2024-09-17 ocal Point and Coordination f ant Selection ntation or DPA SO-MOF-362845-CS-INDV / L Individual Consult Pending Impleme TF / B5774 Strengthening Institutions Prior Open - National 70,200.00 0.00 2023-06-05 2023-07-24 2023-08-14 2023-09-18 2024-09-12 egal Adviser for DPA ant Selection ntation SO-MOF-362846-CS-INDV / D Individual Consult Pending Impleme ata Protection - Technical Ex TF / B5774 Strengthening Institutions Prior Open - National 59,280.00 0.00 2023-05-25 2023-06-20 2023-07-11 2023-08-15 2024-08-09 ant Selection ntation pert for DPA SO-MOF-362869-CS-INDV / F Enabling Financial and Digit Individual Consult Under Implement IDA / D4330 Prior Open - National 59,280.00 0.00 2023-05-30 2023-07-18 2023-08-08 2023-09-12 2024-09-06 inancial Institution Analyst F al Services ant Selection ation or Gargaara Page 11 PROCUREMENT PLAN (Textual Part) Project information: P167958 - COMMUNITY PARTICIPATION IN HOW IS MY SCHOOL DOING PROJECT Project Implementation agency: World Vision Dominicana Date of the Procurement Plan: 03-08-2022 Period covered by this Procurement Plan: during project implementation Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. Not Applicable Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables. Not Applicable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: Not applicable Works: Not applicable PROCUREMENT Dominican Republic : COMMUNITY PARTICIPATION IN HOW IS MY SCHOOL DOING PROJECT PLAN General Information Country: Dominican Republic 2022-03-31 Bank’s Approval Date of the Original Procurement Plan: 2023-06-01 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P167958 GPN Date: 2022-04-26 Project Name: COMMUNITY PARTICIPATION IN HOW IS MY SCHOOL DOING PROJECT Loan / Credit No: TF / B0840 How is my School Doing Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual DO-CVME-258014-GO-RFQ / Monitoring, Evaluation and L Request for Quota Single Stage - One E Adquisición de Softwares (Po TF / B0840 earning, and Project Manage Post Limited 150.00 0.00 Canceled 2022-04-19 2022-06-14 2023-01-18 tions nvelope wer BI, Zoom etc.) ment DO-CVME-258020-GO-RFQ / Monitoring, Evaluation and L Request for Quota Single Stage - One E TF / B0840 Post Open - National 4,500.00 5,207.89 Completed 2022-05-05 2022-07-23 2022-06-30 2022-07-22 2022-12-27 2022-07-27 Adquisición de 3 Laptop. earning, and Project Manage tions nvelope ment DO-CVME-257960-GO-RFQ / Community participation in s Request for Quota Single Stage - One E Adquisición de Accesorios de TF / B0840 chool management through Post Open - National 2,500.00 0.00 Canceled 2022-04-24 2022-06-19 2022-12-16 tions nvelope computadoras y cámara de v CVME ideos para TV DO-CVME-258017-GO-RFQ / Community participation in s Request for Quota Single Stage - One E Adquisición de paquetes de i TF / B0840 chool management through Post Open - National 2,500.00 0.00 Canceled 2022-05-19 2022-07-14 2023-01-10 tions nvelope nternet para 30 Escuelas (rec CVME arga de 2 GB). DO-CVME-258016-GO-RFQ / Community participation in s Request for Quota Single Stage - One E Adquisición de 10 televisores TF / B0840 chool management through Post Open - National 3,000.00 0.00 Canceled 2022-05-05 2022-06-30 2022-12-27 tions nvelope Smart 40 pulgadas. CVME DO-CVME-257998-GO-RFQ / Community participation in s Servicio de impresión de Mat Request for Quota Single Stage - One E TF / B0840 chool management through Post Open - National 2,500.00 2,464.30 Completed 2022-03-30 2022-08-02 2022-05-25 2022-08-13 2022-11-21 2022-08-26 erial didáctico para capacitac tions nvelope CVME iones en 60 escuelas. DO-CVME-258018-GO-RFQ / Solicitud de compra de mater iales de higiene (50 Alcohol d Community participation in s Request for Quota Single Stage - One E e 1500 ml, 50 gel antibacteri TF / B0840 chool management through Post Open - National 3,500.00 0.00 Canceled 2023-04-06 2023-06-01 2023-11-28 tions nvelope al de 10 ml, 500 mascarillas CVME quirúrgicas) para el desarroll o de actividades en comunid ades. DO-CVME-258002-GO-RFQ / Establishing a follow-up mec Servicio de Impresión de Mat hanism between schools and Request for Quota Single Stage - One E TF / B0840 Post Open - National 1,800.00 900.73 Completed 2022-03-30 2022-05-25 2022-05-10 2022-11-21 2022-05-31 eriales de visibilidad Afiches, the Ministry of Education thr tions nvelope Banners y díptico. ough CVME DO-CVME-285846-GO-RFQ / Adquisición de materiales ga Monitoring, Evaluation and L Request for Quota Single Stage - One E stables varios (lapiceros, libr TF / B0840 earning, and Project Manage Post Open - National 700.00 115.67 Completed 2022-04-04 2022-07-20 2022-05-30 2022-05-17 2022-11-26 2022-05-17 tions nvelope etas, folders etc.) para realiz ment ación de talleres en comunid ad educativa. DO-CVME-258024-GO-RFQ / Monitoring, Evaluation and L Request for Quota Single Stage - One E Plataforma (servidores virtua TF / B0840 earning, and Project Manage Post Open - National 16,235.00 0.00 Canceled 2022-04-19 2022-06-14 2022-12-11 tions nvelope les en la nube) ment DO-CVME-285844-GO-RFQ / Adquisición de Artículos pro mocionales Souvenir para las Monitoring, Evaluation and L Request for Quota Single Stage - One E APMAES Para celebración de TF / B0840 earning, and Project Manage Post Open - National 1,200.00 0.00 Canceled 2022-03-30 2022-05-25 2022-11-21 tions nvelope Dia de las APMAE" Polo-Shirt ment para los colaboradores integr antes de la comunidad educa tiva del proyecto. DO-CVME-256484-GO-RFQ / Community participation in s Adquisición de 60 Murales inf Request for Quota Single Stage - One E TF / B0840 chool management through Post Open - National 3,000.00 0.00 Canceled 2022-04-05 2022-05-31 2022-11-27 ormativos para Centros educ tions nvelope CVME ativos, en Vinil adhesivo 20X 24. DO-CVME-257733-GO-RFQ / Community participation in s Servicio de Diseño e impresió Request for Quota Single Stage - One E TF / B0840 chool management through Post Open - National 500.00 0.00 Canceled 2022-04-20 2022-06-15 2022-06-18 n de 60 Impresiones de Scor tions nvelope CVME e Card en Escuelas. DO-CVME-360032-GO-RFQ / Adquisición de materiales ga stables varios (lapiceros, libr Community participation in s etas, folders etc.) para realiz Request for Quota Single Stage - One E TF / B0840 chool management through Post Open - National 1,000.00 0.00 Completed 2023-05-05 2023-06-13 2023-06-20 2023-05-25 ación de talleres en comunid tions nvelope CVME ad educativa y Adquisición d e 4 cajas plásticas para salva guardar las fuentes de verific ación del Proyecto. NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual DO-CVME-257943-NC-RFQ / Establishing a follow-up mec Diagramación y diseño de h hanism between schools and Request for Quota Single Stage - One E TF / B0840 Post Open - National 4,000.00 0.00 Canceled 2022-05-07 2022-07-02 2022-12-29 allazgo en la Evaluación de i the Ministry of Education thr tions nvelope mpacto del proyecto CVME. ough CVME Page 1 DO-CVME-257926-NC-RFQ / Diseño gráficos pedagógico d Community participation in s e los materiales de capacitac Request for Quota Single Stage - One E TF / B0840 chool management through Post Open - National 2,200.00 0.00 Canceled 2022-10-20 2022-12-15 2023-06-13 ión (manuales, brochure, ban tions nvelope CVME ner ect.) Derivados de la gest ión y aprendizaje adaptivo de l proyecto. DO-CVME-258021-NC-RFQ / Community participation in s Request for Quota Single Stage - One E Servicio de producción de Vo TF / B0840 chool management through Post Open - National 2,000.00 0.00 Completed 2022-01-09 2022-07-28 2022-03-06 2022-09-02 2022-09-25 tions nvelope z en off para programa forma CVME tivo. DO-CVME-257954-GO-RFQ / Servicios de alimentos y rent Community participation in s Request for Quota Single Stage - One E a de espacio para realizar Co TF / B0840 chool management through Post Open - National 1,500.00 1,387.91 Completed 2022-04-27 2022-08-08 2022-06-22 2022-08-20 2022-12-19 2022-08-26 tions nvelope nmemoración del Día de la D CVME escentralización a nivel nacio nal, para 50 personas. DO-CVME-258000-GO-RFQ / Servicios de alimentos para r Monitoring, Evaluation and L ealizar "Foro Regional Ciudad Request for Quota Single Stage - One E TF / B0840 earning, and Project Manage Post Open - National 1,500.00 754.90 Completed 2022-04-06 2022-06-01 2022-04-30 2022-11-28 2022-05-07 anía Voz y Acción en Centros tions nvelope ment Educativos" en 28 Centros E ducativos de la zona Metropo litana, para 45 personas. DO-CVME-258028-GO-RFQ / Servicios de alimentos para r Community participation in s ealizar "Foro Regional Ciudad Request for Quota Single Stage - One E TF / B0840 chool management through Post Open - National 1,200.00 1,043.92 Completed 2022-04-10 2022-07-20 2022-06-05 2022-04-29 2022-12-02 2022-04-29 anía Voz y Acción en Centros tions nvelope CVME Educativos" en 24 Centros Ed ucativos de la zona norte, pa ra 40 personas. DO-CVME-258350-NC-RFQ / Community participation in s Servicios de alimentos para r Request for Quota Single Stage - One E TF / B0840 chool management through Post Open - National 500.00 767.42 Completed 2022-04-17 2022-07-22 2022-06-12 2022-05-21 2022-12-09 2022-05-24 ealizar Encuentro con Volunt tions nvelope CVME arios en la zona Metropolitan a, para 35 personas. DO-CVME-270877-NC-RFQ / Servicios de Alquiler de Trans porte privado con el recorrid Community participation in s Request for Quota Single Stage - One E o desde Santiago, La Vega y TF / B0840 chool management through Post Open - National 300.00 0.00 Canceled 2022-03-27 2022-05-22 2022-05-25 tions nvelope Bonao para participantes de CVME "Foro Regional Ciudadanía V oz y Acción en Centros Educa tivos" de la zona norte. DO-CVME-270850-NC-RFQ / Servicios de alimentos para r Community participation in s ealizar 5 talleres en 12 Centr Request for Quota Single Stage - One E TF / B0840 chool management through Post Open - National 2,500.00 988.36 Completed 2022-04-19 2022-06-13 2022-06-14 2022-06-30 2023-01-18 2022-10-08 os Educativos en la Provincia tions nvelope CVME de Santiago para un total de 110 participantes por escuel a. DO-CVME-270875-NC-RFQ / Servicios de alimentos para r Community participation in s Request for Quota Single Stage - One E ealizar talleres Fase 2 CVA e TF / B0840 chool management through Post Open - National 35.54 0.00 Canceled 2022-04-06 2022-06-01 2022-11-28 tions nvelope n los 2 centros educativos en CVME Puerto Plata, zona norte. 5 p articipantes por escuelas. DO-CVME-270826-NC-RFQ / Servicios de alimentos para r Community participation in s Request for Quota Single Stage - One E ealizar 5 talleres en 4 Escuel TF / B0840 chool management through Post Open - National 800.00 250.87 Completed 2022-04-06 2022-06-13 2022-06-01 2022-06-21 2022-11-28 2022-06-21 tions nvelope as en la Villa Altagracia un to CVME tal de 65 participantes por es cuela. DO-CVME-270786-NC-RFQ / Servicios de alimentos para r Community participation in s Request for Quota Single Stage - One E ealizar 6 talleres en 4 Escuel TF / B0840 chool management through Post Open - National 800.00 476.32 Completed 2023-04-09 2022-06-13 2023-06-04 2022-06-30 2023-12-01 2022-10-08 tions nvelope a en Bonao un total de 110 p CVME articipantes por escuela. DO-CVME-270869-NC-RFQ / Servicios de alimentos para r Community participation in s Request for Quota Single Stage - One E ealizar 5 talleres en 2 Escuel TF / B0840 chool management through Post Open - National 350.00 448.97 Completed 2023-04-15 2022-06-13 2023-06-10 2022-06-27 2023-12-07 2022-10-09 tions nvelope a en La Provincia de Puerto P CVME lata un total de 110 participa ntes por escuela. DO-CVME-270852-NC-RFQ / Servicios de alimentos para r Community participation in s ealizar 5 talleres en 6 Centro Request for Quota Single Stage - One E TF / B0840 chool management through Post Open - National 1,000.00 587.29 Completed 2023-04-15 2022-06-13 2023-06-10 2022-06-27 2023-12-07 2022-10-08 s Educativos en la Provincia tions nvelope CVME de La Vega para un total de 110 participantes por escuel a. DO-CVME-270805-NC-RFQ / Servicio de alimentos para re alizar Taller de formación con Community participation in s Request for Quota Single Stage - One E miembros de organismos de TF / B0840 chool management through Post Open - National 1,120.00 0.00 Completed 2022-04-06 2022-12-03 2022-06-01 2022-11-28 2022-12-10 tions nvelope participación escolar de 28 C CVME entros Educativos en el Gran Santo Domingo. 20 participa ntes por cada centro. DO-CVME-270881-NC-RFQ / Servicios de alimentos para r Community participation in s ealizar 4 talleres de la Fase 1 Request for Quota Single Stage - One E TF / B0840 chool management through Post Open - National 3,400.00 0.00 Terminated 2022-04-19 2022-12-03 2022-06-14 2022-12-11 y 2 de CVA en los 28 centros tions nvelope CVME educativos en el Gran Santo Domingo. Un total de 90 part icipantes por escuela. DO-CVME-270837-NC-RFQ / Servicios de alimentos para r Community participation in s ealizar "Foro Regional Ciudad Request for Quota Single Stage - One E TF / B0840 chool management through Post Open - National 700.00 0.00 Completed 2023-04-12 2022-10-26 2023-06-07 2023-12-04 2022-11-05 anía Voz y Acción en Centros tions nvelope CVME Educativos" en 8 Centros Edu cativos de San Cristóbal, par a 20 personas. DO-CVME-270863-NC-RFQ / Servicios de alimentos para r Community participation in s ealizar 5 talleres en 4 Centro Request for Quota Single Stage - One E TF / B0840 chool management through Post Open - National 1,000.00 0.00 Completed 2022-04-06 2022-12-03 2022-06-01 2022-11-28 2022-11-30 s Educativos en la Provincia tions nvelope CVME de San Cristóbal para un tota l de 110 participantes por es cuela. DO-CVME-285916-NC-RFQ / Monitoring, Evaluation and L Servicio de Bordado de las C Request for Quota Single Stage - One E TF / B0840 earning, and Project Manage Post Open - National 80.00 0.00 Canceled 2021-03-25 2021-05-20 2021-11-16 amisas del Proyecto Mi Comu tions nvelope ment nidad Participa en CVME Page 2 DO-CVME-285910-NC-RFQ / Community participation in s Compra de Materiales Educat Request for Quota Single Stage - One E TF / B0840 chool management through Post Open - National 70.00 0.00 Completed 2021-08-25 2021-10-20 2022-04-18 2021-09-05 ivos y gastables para utilizar tions nvelope CVME en encuentro con técnicos re gionales y distritales DO-CVME-285921-NC-RFQ / Servicio de alimentos y renta de local para celebrar la Jorn Community participation in s Request for Quota Single Stage - One E ada de capacitación del equi TF / B0840 chool management through Post Open - National 980.00 0.00 Completed 2021-08-07 2022-10-27 2021-10-02 2022-03-31 2022-11-14 tions nvelope po Vision Mundial, Técnicos R CVME egionales, Distritales y Direct ores de Centros Educativos Z ona Norte. DO-CVME-323688-NC-RFQ / Servicio de adquisición de m Community participation in s aterias educativos y gastable Request for Quota Single Stage - One E TF / B0840 chool management through Post Open - National 1,500.00 0.00 Completed 2022-11-10 2022-11-25 2023-01-05 2023-07-04 2022-12-14 s para desarrollar encuentros tions nvelope CVME formativos con estudiantes, docentes y técnicos del MINE RD. DO-CVME-323689-NC-RFQ / Servicio de alimentos y renta de espacio para la celebració Establishing a follow-up mec n del Congreso Nacional de B hanism between schools and Request for Quota Single Stage - One E TF / B0840 Post Limited 6,000.00 0.00 Completed 2023-03-15 2023-03-01 2023-05-10 2023-11-06 2023-04-04 uenas Practicas de Participac the Ministry of Education thr tions nvelope ión Comunitaria en apoyo a l ough CVME a calidad educativa. Activida d de cierre del Proyecto. 100 personas. DO-CVME-323690-NC-RFQ / Monitoring, Evaluation and L Solicitud de materiales plega Request for Quota Single Stage - One E TF / B0840 earning, and Project Manage Post Open - National 2,500.00 0.00 Completed 2022-11-10 2022-12-09 2023-01-05 2023-07-04 2023-01-28 bles y portátiles para la impl tions nvelope ment ementación del Proyecto en campo. DO-CVME-323700-NC-RFQ / Servicio de alimentos para r Community participation in s Request for Quota Single Stage - One E ealizar jornada formativa con TF / B0840 chool management through Post Open - National 700.00 0.00 Completed 2022-11-10 2022-11-03 2023-01-05 2023-07-04 2022-11-16 tions nvelope Técnicos del MINERD en Sant CVME o Domingo Para 20 personas. Regional 10 DO-CVME-323692-NC-RFQ / Monitoring, Evaluation and L Servicio de impresión de mat Request for Quota Single Stage - One E TF / B0840 earning, and Project Manage Post Open - National 9,850.00 0.00 Completed 2022-11-10 2023-03-21 2023-01-05 2023-07-04 eriales formativos y de visibil tions nvelope ment idad del Proyecto DO-CVME-323691-NC-RFQ / Servicio de alimentos para 2 0 personas, actividad para d Community participation in s Request for Quota Single Stage - One E esarrollar Encuentro de revisi TF / B0840 chool management through Post Open - National 1,200.00 0.00 Completed 2022-11-25 2022-11-25 2023-01-20 2023-07-19 2022-12-10 tions nvelope ón del Protocolo de acción p CVME ara el seguimiento a los orga nismos de Participación Escol ar con Técnicos del MINERD. DO-CVME-323694-NC-RFQ / Community participation in s Servicio de diseño y diagram Request for Quota Single Stage - One E TF / B0840 chool management through Post Open - National 4,300.00 0.00 Canceled 2022-11-25 2023-01-20 2023-07-19 ación de materiales formativ tions nvelope CVME os y de visibilidad del Proyec to DO-CVME-270878-NC-RFQ / Servicios de streaming para Establishing a follow-up mec Zoom y YouTube, Para celebr hanism between schools and Request for Quota Single Stage - One E TF / B0840 Post Open - National 5,000.00 0.00 Canceled 2023-01-06 2023-03-03 2023-08-30 ar el Congreso Nacional de B the Ministry of Education thr tions nvelope uenas Prácticas de Participac ough CVME ión Comunitaria en apoyo a l a calidad educativa. DO-CVME-258004-NC-RFQ / Servicio de alimentos para d Establishing a follow-up mec ar el Entrenamientos colabor hanism between schools and Request for Quota Single Stage - One E TF / B0840 Post Open - National 300.00 0.00 Canceled 2022-05-21 2022-11-07 2022-07-16 2023-01-12 ativos con IDEC y Comité de the Ministry of Education thr tions nvelope Veeduría para establecer vín ough CVME culos entre CVME, Plan Estrat égico y Pacto Educativo . DO-CVME-257730-GO-RFQ / Servicio de alimentos y renta Establishing a follow-up mec de espacio, Congreso Nacion hanism between schools and Request for Quota Single Stage - One E al de Buenas Practicas de Par TF / B0840 Post Open - National 1,500.00 0.00 Completed 2022-11-16 2022-11-04 2023-01-11 2023-07-10 2022-11-30 the Ministry of Education thr tions nvelope ticipación Comunitaria en ap ough CVME oyo a la calidad educativa, e n conmeración del mes de la familia. DO-CVME-285918-NC-RFQ / Monitoring, Evaluation and L Servicio de diseño e impresió Request for Quota Single Stage - One E TF / B0840 earning, and Project Manage Post Open - National 388.00 0.00 Completed 2020-07-11 2020-09-05 2021-03-04 2021-07-18 n 3 Banner tamano 31x80 PU tions nvelope ment LGS. Impresos a full color DO-CVME-285913-NC-RFQ / Establishing a follow-up mec Servicio de impresión de 50 c hanism between schools and Request for Quota Single Stage - One E opias a full color en papel Bo TF / B0840 Post Open - National 645.00 0.00 Completed 2021-05-01 2021-06-26 2021-12-23 2021-05-07 the Ministry of Education thr tions nvelope nd tamano 8/30 x11y encuar ough CVME denacion espiral a manual de encuestadores DO-CVME-257734-NC-RFQ / I Community participation in s Request for Quota Single Stage - One E mplementación de Plataform TF / B0840 chool management through Post Open - National 10,000.00 0.00 Canceled 2022-03-30 2022-07-29 2022-05-25 2022-11-21 tions nvelope a, creación de aula virtual de CVME estudio. DO-CVME-324459-NC-RFQ / I Community participation in s Request for Quota Single Stage - One E mplementación de Plataform TF / B0840 chool management through Post Open - National 20,000.00 0.00 Completed 2022-11-10 2022-12-08 2023-01-05 2023-07-04 2023-03-31 tions nvelope a, creación de aula virtual de CVME estudio. DO-CVME-258015-NC-RFQ / Establishing a follow-up mec Servicios de fotografia y vide hanism between schools and Request for Quota Single Stage - One E os para el Congreso Nacional TF / B0840 Post Open - National 715.00 0.00 Canceled 2022-03-30 2022-05-25 2022-11-21 the Ministry of Education thr tions nvelope de Buenas Practicas de Partic ough CVME ipación Comunitaria en apoy o a la calidad educativa. DO-CVME-285928-NC-RFQ / Community participation in s Servicio de alimentación par Request for Quota Single Stage - One E TF / B0840 chool management through Post Open - National 208.00 0.00 Completed 2021-05-19 2021-07-14 2022-01-10 2021-05-31 a realizar jornadas en centro tions nvelope CVME s educativos zona metropolit ana DO-CVME-285920-NC-RFQ / Community participation in s Servicio de alimentación par Request for Quota Single Stage - One E TF / B0840 chool management through Post Open - National 87.00 0.00 Canceled 2021-05-19 2021-07-14 2022-01-10 a realizar jornadas en centro tions nvelope CVME s educativos zona metropolit ana (Galleta) Page 3 DO-CVME-270866-NC-RFQ / Compra y servicio de bordad Monitoring, Evaluation and L Request for Quota Single Stage - One E o de camisas tipo Columbia, TF / B0840 earning, and Project Manage Post Open - National 2,000.00 0.00 Canceled 2022-04-04 2022-05-30 2022-11-26 tions nvelope mangas largas de colores ne ment gro, blanca y azul, con Logo del proyecto. DO-CVME-323697-NC-RFQ / Servicio de alimentos para r Community participation in s Request for Quota Single Stage - One E ealizar jornada formativa con TF / B0840 chool management through Post Open - National 700.00 0.00 Completed 2022-11-10 2022-12-03 2023-01-05 2023-07-04 2022-11-21 tions nvelope Tecnicos del MINERD en San CVME to Domingo Para 20 personas . Regional 15 DO-CVME-351268-NC-RFQ / Servicio de alimentos para so Establishing a follow-up mec cializar la sistematización de hanism between schools and Request for Quota Single Stage - One E TF / B0840 Post Open - National 700.00 0.00 Completed 2023-04-26 2023-06-30 2023-12-27 buenas prácticas en auditori the Ministry of Education thr tions nvelope a Social en centros educativo ough CVME s del Corredor Duarte. 20 per sonas. DO-CVME-352076-NC-RFQ / I mpresión del INFOGRAFICO 1 7x22 Cartonite 1 Cara. 100 ej Establishing a follow-up mec emplares. Impresión de las S hanism between schools and Request for Quota Single Stage - One E TF / B0840 Post Open - National 3,900.00 0.00 Canceled 2023-03-29 2023-05-24 2023-11-20 core Card de las 60 escuelas the Ministry of Education thr tions nvelope objetivos del Proyecto. A tod ough CVME o color 17X22. Impresión de 60 Murales de visibilidad de l as APMAE para 60 centros ed ucativos. DO-CVME-357699-NC-RFQ / Solicitud de refrigerio para re Community participation in s alizar Jornada formativo en t Request for Quota Single Stage - One E TF / B0840 chool management through Post Open - National 1,000.00 0.00 Completed 2023-05-12 2023-05-10 2023-06-06 2023-06-20 2023-05-14 orno a la metodología Ciudan tions nvelope CVME ía, Voz y Acción con la comu nidad educativa de la escuel a Juan Pablo Pina, San Cristó bal. DO-CVME-359988-NC-RFQ / Encuentro de cierre del Proy ecto en la Zona Norte: Servic Community participation in s io de alimentos y renta de es Request for Quota Single Stage - One E TF / B0840 chool management through Post Open - National 10,000.00 0.00 Completed 2023-05-12 2023-06-13 2023-06-18 pacio para la celebración del tions nvelope CVME cierre del proyecto y las entr egas de las Scoredcard (28x4 ) actividad para un estimado de 112 personas DO-CVME-359989-NC-RFQ / Encuentro de Cierre del Proy ecto en la Zona Metropolitan Community participation in s a: Servicio de alimentos y re Request for Quota Single Stage - One E TF / B0840 chool management through Post Open - National 15,000.00 0.00 Canceled 2023-05-12 2023-06-14 2023-06-19 nta de espacio para la celebr tions nvelope CVME ación del Cierre del Proyecto y las entregas de las Scoredc ard para un estimado de 14 0 personas DO-CVME-360025-GO-RFQ / Community participation in s Request for Quota Single Stage - One E TF / B0840 Post Open - National 10,000.00 0.00 Completed 2023-05-10 2023-06-10 2023-06-20 2023-06-20 Adquisición de Materiales ser chool management through tions nvelope igrafiados CVME DO-CVME-360015-NC-RFQ / I mpresión de Herramientas fo rmativas diseñadas o replica Establishing a follow-up mec das en el Marco del Proyecto hanism between schools and Request for Quota Single Stage - One E Mi Comunidad Participa en C TF / B0840 Post Open - National 21,390.00 0.00 Signed 2023-05-05 2023-05-26 2023-06-20 the Ministry of Education thr tions nvelope omo Va Mi Escuela e impresi ough CVME ón del Informe de la evaluaci ón del Proyecto, realizado en el formato del GPSA y murale s de visibilidad DO-CVME-364457-NC-RFQ / Establishing a follow-up mec Diseño, ilustración y diagram hanism between schools and Request for Quota Single Stage - One E Under Imple TF / B0840 Post Open - National 15,600.00 0.00 2023-06-04 2023-07-30 2024-01-26 ación de los materiales form the Ministry of Education thr tions nvelope mentation ativos y de visibilidad del pro ough CVME yecto. DO-CVME-365429-NC-RFQ / Solicitud de refrigerio para re alizar Encuentros del Cierre d Community participation in s Request for Quota Single Stage - One E Under Imple el Proyecto en Los 60 centros TF / B0840 chool management through Post Open - National 20,000.00 0.00 2023-06-06 2023-06-12 2023-06-12 tions nvelope mentation Educativos: CVME “Ciudadanía Voy y Acción For taleciendo la Participación Es colar y Comunitaria CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual DO-CVME-258023-CS-CQS / Monitoring, Evaluation and L Consultant Qualifi TF / B0840 Post Open - National 9,000.00 0.00 Canceled 2023-04-03 2023-04-24 2023-06-07 2023-07-07 2023-08-11 2024-02-07 Auditoria Externa del proyect earning, and Project Manage cation Selection o. ment DO-CVME-285875-NC-RFQ / Establishing a follow-up mec Servicio de consultoría para l hanism between schools and Quality Based Sel Under Implement TF / B0840 Post Open - National 41,300.00 0.00 2021-04-19 2021-04-19 2021-05-10 2021-06-23 2021-04-14 2021-07-21 2021-04-14 2021-08-20 2021-04-08 2021-09-19 2021-04-16 2021-10-24 2022-10-24 evantamiento de Encuesta e the Ministry of Education thr ection ation n 180 centros educativos ough CVME DO-CVME-285906-CS-QBS / Monitoring, Evaluation and L Contratación de Firma De Au Quality Based Sel TF / B0840 earning, and Project Manage Post Open - National 5,610.00 0.00 Completed 2021-09-21 2021-05-17 2021-10-12 2021-11-25 2021-05-15 2021-12-23 2021-05-17 2022-01-22 2021-05-17 2022-02-21 2021-05-17 2022-03-28 2023-03-28 2022-07-29 ditores Para Visión Mundial In ection ment ternacional y Banco Mundial INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual DO-CVME-257737-NC-RFQ / 2 Facilitadores para Jornada Community participation in s Individual Consult s formativas CVA Miembros d TF / B0840 chool management through Post Open 12,000.00 998.19 Completed 2022-04-01 2022-04-19 2022-05-20 2022-04-26 2022-06-10 2022-04-27 2022-07-15 2022-04-28 2023-01-11 2022-05-08 ant Selection e APMAEs, Técnicos Regional CVME es, Distritales y Directores de Centros Educativos. Page 4 DO-CVME-258398-CS-INDV / Monitoring, Evaluation and L Contratación de servicios de Individual Consult TF / B0840 earning, and Project Manage Post Open 50,342.47 0.00 Completed 2020-02-28 2020-01-20 2020-04-17 2020-02-18 2020-05-08 2020-03-24 2020-06-12 2020-12-09 2023-05-17 Consultoria para la eleboraci ant Selection ment ón de las Evaluaciones inter media y Final. DO-CVME-285869-CS-INDV / Community participation in s Servicio de consultoria para Individual Consult Under Implement TF / B0840 chool management through Post Open 5,478.00 0.00 2021-08-20 2021-04-12 2021-10-08 2021-03-31 2021-10-29 2021-05-05 2021-12-03 2022-06-01 el Desarrollo de capacitacion ant Selection ation CVME es en centros educativos DO-CVME-314908-CS-INDV / Servicio de consultoría indivi Community participation in s dual para facilitar fase 2 de l Individual Consult TF / B0840 chool management through Post Open - National 2,000.00 0.00 Canceled 2022-09-24 2022-10-26 2022-11-12 2022-12-03 2023-01-07 2023-07-06 a metodología ciudadanía, vo ant Selection CVME z y acción (CVA) a trabajar e n la zona norte de Santo Do mingo Este y Distrito Naciona l. DO-CVME-314910-CS-INDV / Desarrollar la fase 2 de CVA en 12 escuelas intervenidas Community participation in s Individual Consult por el Proyecto Mi Comunida TF / B0840 chool management through Post Open - National 3,000.00 0.00 Canceled 2022-09-24 2022-10-26 2022-11-12 2022-12-03 2023-01-07 2023-07-06 ant Selection d Participa en Como Va Mi Es CVME cuela, ubicadas en San Cristó bal, Villa Altagracia y Santo Domingo Oeste. DO-CVME-314911-CS-INDV / Desarrollar la fase 2 de CVA Community participation in s en 14 escuelas intervenidas Individual Consult TF / B0840 chool management through Post Open - National 3,500.00 0.00 Canceled 2022-09-24 2022-10-24 2022-11-12 2022-12-03 2023-01-07 2023-07-06 por el Proyecto Mi Comunida ant Selection CVME d Participa en Como Va Mi Es cuela, ubicadas en Bonao, La Vega, Santiago y Puerto Plat a DO-CVME-258019-CS-INDV / Establishing a follow-up mec Servicios de consultoría siste hanism between schools and Individual Consult TF / B0840 Post Open 15,000.00 0.00 Canceled 2022-07-01 2022-08-19 2022-09-09 2022-10-14 2023-04-12 matización de buenas practic the Ministry of Education thr ant Selection as en auditoria Social en cent ough CVME ros educativos. DO-CVME-357232-CS-CDS / Monitoring, Evaluation and L Under Implement TF / B0840 Post Direct Selection Direct - National 9,000.00 0.00 2023-04-21 2023-05-15 2023-05-01 2023-05-15 2023-07-05 2024-01-01 Auditoria externa del proyect earning, and Project Manage ation o ment DO-CVME-359985-CS-INDV / Servicio de consultoria para l a sistematizacion del proyect Establishing a follow-up mec o Mi Comunidad Participa en hanism between schools and Individual Consult Under Implement Como Va Mi Escuela (Buenas TF / B0840 Post Open - National 18,000.00 0.00 2023-05-05 2023-05-22 2023-05-25 2023-05-30 2023-06-13 2023-06-24 the Ministry of Education thr ant Selection ation Practicas) y Sistematizacion ough CVME y digitalizacion de datos cuali tativos y cuantitativos de 60 centros educativos ubicados en el corredor Duarte DO-CVME-360012-CS-INDV / Diseño de Murales de visibili dad de los Organismos de Pa Establishing a follow-up mec rticipación Escolar (Identifica hanism between schools and Individual Consult TF / B0840 Post Open - National 4,500.00 0.00 Canceled 2023-05-05 2023-06-20 2023-06-28 2023-07-07 2023-07-18 ndo los Roles y las funciones the Ministry of Education thr ant Selection de Cada uno) y Diagramació ough CVME n del Informe de la evaluació n del Proyecto, realizado en el formato del GPSA. DO-CVME-361876-CS-INDV / Servicio de Diseño, ilustració n y diagramación de las de S Establishing a follow-up mec core Card de las evaluacione hanism between schools and Individual Consult s de los estandares educativ TF / B0840 Post Open - National 7,000.00 0.00 Under Review 2023-05-16 2023-05-30 2023-05-23 2023-05-26 2023-05-31 2023-05-31 the Ministry of Education thr ant Selection os realizados durante la impl ough CVME ementacion del proyecto Mi Comunidad Participa en Com o Va Mi Escuela 60 escuelas. Full color 17X22. DO-CVME-362554-CS-INDV / PARA EL DISEÑO, ILUSTRACI Establishing a follow-up mec ÓN Y DIAGRAMACIÓN DE LOS hanism between schools and Individual Consult TF / B0840 Post Open - National 8,600.00 0.00 Canceled 2023-05-19 2023-05-29 2023-05-31 2023-06-09 2023-06-13 MATERIALES FORMATIVOS Y the Ministry of Education thr ant Selection DE VISIBILIDAD DEL PROYEC ough CVME TO MI COMUNIDAD PARTICIP A EN COMO VA MI ESCUELA Page 5 PROCUREMENT PLAN - Textual Part Project information: Sint Maarten Emergency Recovery Project (P167339) Project Implementation Agency: NRPB Date of the Procurement Plan: April 29, 2021 Period covered by this Procurement Plan: From April 2021 to March 2022 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: Shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the National Procurement Legislation such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions: 1. The request for bids/request for proposals document shall require that Bidders/Proposers submitting Bids/Proposals present a signed acceptance at the time of bidding to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights. The Bank’s Anti- Corruption Guidelines and Sanctions Framework shall be incorporated into the national bidding documents by adding a page entitled “Letter of Acceptance of the World Bank’s Anti-Corruption Guidelines and Sanctions Framework”. 2. Contracts with an appropriate allocation of responsibilities, risks, and liabilities between the Borrower and the contractors/suppliers/consultants. 3. Rights for the Bank to review procurement documentation and activities. In accordance with the Procurement Regulations, each bidding document and contract shall include provisions stating the Bank's policy to sanction firms or individuals, found to have engaged in fraud and/or corruption as defined in the Procurement Regulations. In accordance with the Procurement Regulations, each bidding document and contract financed out of the proceeds of the Financing Agreement shall provide that bidders, suppliers, contractors and their subcontractors, agents, personnel, consultants, service providers, or suppliers shall permit the Bank to inspect all accounts, records and other documents relating to the bid submission and performance of the contract and to have said accounts and records audited by auditors appointed by the Bank. Acts intended to materially impede the exercise of the Bank's inspection and audit rights provided for in the Procurement Regulations constitute an obstructive practice as defined in the Regulations. 4. No bids shall be rejected solely because they fall below or exceed the estimated cost. All bids (including in the case when less than two bids are received) shall not be rejected, the procurement process shall not be cancelled, and new bids shall not be solicited without the Bank's prior written concurrence. The Bidding Documents template to be used under “national open competitive procurement arrangements” are subject to prior written concurrence by the Bank. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Not Applicable. Procurement of Second-hand Goods as specified under paragraph 5.11 of the Procurement Regulations: Not Applicable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: not applicable Works: not applicable. Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations is Applicable. Other Relevant Procurement Information. Procurement in Situations of Urgent Need of Assistance or Capacity Constraints. PROCUREMENT PLAN Goods Notification Activity Draft Signed Review Procurement Evaluation of Intention Reference No. / In-Process Component Contract Contract Type Category Options of Award Description: Planned Planned Planned Restoring a community SX-NRPB- learning and 205571-GO-DIR / No cultural Post Goods Direct 2021/01/30 2021/02/13 2021/03/06 ICT Equipment environment, Project Management Consulting Services Draft Signed Negotiated Activity Contract Market Contract Reference No. In-Process Component Review Type Category Approach / Description: Planned Planned SX-NRPB- Restoring a 205590-CS- community CDS / ESS8 Consultant No learning and Post Direct 2021/03/26 2021/04/30 Cultural Services cultural Heritage environment Consultants SX-NRPB- 205594-CS- Rebuilding safe Consultant CDS / School No Prior Direct 2021/04/10 2021/05/15 schools Services and Library designs Individual Consultants Terms of Expression Signed Activity Reference of Interest Contract Reference In- Review Market Component Category No. / Process Type Approach Description: Planned Planned Planned SX-NRPB- 205589-CS- INDV / Consultant No Project Management Post Open 2021/03/04 2021/03/25 2021/06/24 MECYS Services Project Manager SX-NRPB- 205575-CS- Restoring a community INDV / learning and cultural Consultant Technical No Post Open 2021/01/04 2021/01/25 2021/04/26 environment,Project Services Assistant Management Project Engineer SX-NRPB- Restoring a community 205576-CS- learning and cultural Consultant INDV / No Post Open 2021/02/04 2021/02/25 2021/05/27 environment,Project Services Safeguards Management Specialist SX-NRPB- 205592-CS- Restoring a community INDV / Needs Consultant No learning and cultural Post Open 2021/02/04 2021/02/25 2021/05/27 Assessment Services environment for Inclusive Education SX-NRPB- 205415-CS- INDV / FRLP: Local Consultant to Restoring a community work on learning and cultural strategy and Consultant No environment,Strengthening Post Open 2021/01/04 2021/01/18 2021/04/19 Framework Services the Ministry’s Management for SXM Information System Cultural Heritage and other Learning Services SX-NRPB- 205561-CS- Consultant INDV / No Project Management Post Open 2021/01/04 2021/01/25 2021/04/26 Services Procurement Specialist SX-NRPB- 205593-CS- Strengthening the INDV / Consultant No Ministry’s Management Post Open 2021/03/01 2021/03/22 2021/06/21 Development Services Information System MIS framework PROCUREMENT St Maarten : Sint Maarten Emergency Recovery Project I PLAN General Information Country: St Maarten 2018-09-05 Bank’s Approval Date of the Original Procurement Plan: 2023-06-01 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P167339 GPN Date: Project Name: Sint Maarten Emergency Recovery Project I Loan / Credit No: TF / A8079, TF / B5199 National Recovery Program Bureau Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned SX-NRPB-156576-CW-RFB / P Housing Repair and Public B Open - Internationa Single Stage - One E 2020-12-1 ublic Building Repairs: Educa TF / A8079 uildings Repair and Reconstr Prior Request for Bids 5,000,000.00 0.00 Canceled 2020-03-02 2020-03-07 2020-04-18 2020-05-18 2020-06-22 l nvelope 9 tion Facilities uction SX-NRPB-165115-CW-RFB / Housing Repair and Public B Single Stage - One E 2,418,911.5 2021-01-1 TF / A8079 Post Request for Bids Limited 1,000,000.00 Completed 2020-03-25 2020-04-16 2020-03-30 2020-04-16 2020-05-11 2020-05-07 2020-06-10 2020-06-01 2020-07-15 2020-07-10 Rehabilitation of Shelters uildings Repair and Reconstr nvelope 4 1 uction SX-NRPB-181992-CW-RFB / P Housing Repair and Public B Single Stage - One E 1,946,600.0 2021-05-0 TF / A8079 Prior Request for Bids Limited 1,500,000.00 Signed 2020-07-14 2020-08-10 2020-07-19 2020-11-03 2020-08-30 2020-09-11 2020-09-29 2020-11-12 2020-11-03 2021-01-19 riority School Repairs uildings Repair and Reconstr nvelope 0 2 uction SX-NRPB-183349-CW-RFQ / Housing Repair and Public B Request for Quota Single Stage - One E 2021-03-0 SMHDF roof repairs, for retro TF / A8079 uildings Repair and Reconstr Post Limited 236,367.00 236,367.00 Signed 2020-07-13 2020-07-07 2020-09-07 2020-07-08 tions nvelope 6 active finance uction SX-NRPB-202289-CW-RFB / Housing Repair and Public B Open - Internationa Single Stage - One E 7,151,533.0 2021-08-2 Batch 2: Schools and F&A Bui TF / A8079 uildings Repair and Reconstr Post Request for Bids 4,750,000.00 Signed 2020-11-09 2021-04-27 2020-11-14 2021-05-10 2020-12-26 2021-07-06 2021-01-25 2021-10-01 2021-03-01 2021-12-21 l nvelope 0 8 lding Repairs uction SX-NRPB-202300-CW-RFB / Housing Repair and Public B Open - Internationa Single Stage - One E 5,471,564.0 2021-09-0 TF / A8079 Post Request for Bids 6,500,000.00 Signed 2020-11-16 2021-04-01 2020-11-21 2021-04-08 2021-01-02 2021-05-24 2021-02-01 2021-09-17 2021-03-08 2021-12-21 SMHDF Repairs Phase 2 uildings Repair and Reconstr l nvelope 0 4 uction SX-NRPB-202314-CW-RFB / Housing Repair and Public B Open - Internationa Single Stage - One E 2021-10-3 TF / A8079 Post Request for Bids 5,000,000.00 0.00 Canceled 2021-01-11 2021-08-31 2021-01-16 2021-08-31 2021-02-27 2021-11-09 2021-03-29 2022-01-14 2021-05-03 Batch 3: School Repairs uildings Repair and Reconstr l nvelope 0 uction Emergency measures for the SX-NRPB-202332-CW-RFB / Open - Internationa Single Stage - One E 3,779,342.0 2021-12-1 TF / A8079 recovery of disaster first res Post Request for Bids 5,000,000.00 Signed 2021-03-01 2021-08-23 2021-03-06 2021-08-23 2021-04-17 2021-10-05 2021-05-17 2021-11-05 2021-06-21 2022-01-11 GEBE Trenching Batch 1 l nvelope 0 8 ponders and preparedness f acilities SX-NRPB-208747-CW-DIR / Housing Repair and Public B 2021-07-1 Minor Repair Works to Home TF / A8079 uildings Repair and Reconstr Post Direct Selection Direct 27,772.18 28,065.55 Completed 2020-12-09 2020-12-01 2020-12-14 2020-12-01 2021-01-18 2021-01-07 7 s: Aluminum System uction Request for Bids - SX-NRPB-202315-CW-RFB / Housing Repair and Public B Open - Internationa Single Stage - One E Small Works SPD Pending Imp 2022-12-1 TF / A8079 Post Request for Bids 4,500,000.00 0.00 2022-03-01 2022-03-06 2022-04-17 2022-05-17 2022-06-21 Expansion of the EOC Buildin uildings Repair and Reconstr l nvelope (1 envelope proce lementation 8 g uction ss) National Procure SX-NRPB-275606-CW-RFB / Housing Repair and Public B Single Stage - One E ment Document - 2023-02-1 Single Family Home Repairs TF / A8079 uildings Repair and Reconstr Post Request for Bids Open - National 3,000,000.00 0.00 Signed 2022-05-01 2022-06-15 2022-05-06 2022-06-16 2022-06-17 2022-08-10 2022-07-17 2022-09-28 2022-08-21 nvelope 1 Envelope proce 7 PHASE 3 uction ss (Non Bank-SPD ) Request for Bids - Emergency measures for the SX-NRPB-202333-CW-RFB / Open - Internationa Single Stage - One E Small Works SPD Pending Imp 2022-12-1 TF / A8079 recovery of disaster first res Post Request for Bids 5,000,000.00 0.00 2022-03-01 2022-03-06 2022-04-17 2022-05-17 2022-06-21 GEBE Trenching Batch 2 l nvelope (1 envelope proce lementation 8 ponders and preparedness f ss) acilities National Procure SX-NRPB-278379-CW-RFB / P Housing Repair and Public B ment Document - rocurement of Repair and Re Open - Internationa Single Stage - One E 2022-12-0 TF / A8079 uildings Repair and Reconstr Post Request for Bids 1 Envelope proce 5,000,000.00 0.00 Signed 2022-02-14 2022-03-10 2022-02-19 2022-03-10 2022-04-02 2022-05-27 2022-05-02 2022-08-05 2022-06-06 habilitation Works for 13 SXM l nvelope 3 uction ss (Non Bank-SPD schools - relaunch ) Request for Quota SX-NRPB-278660-CW-DIR / Housing Repair and Public B 2022-09-2 TF / A8079 Post Direct Selection Direct tions (Non Bank-S 4,000.00 4,100.45 Signed 2022-02-15 2022-01-27 2022-02-20 2022-02-24 2022-03-27 2022-03-15 MAC High I.T Classroom Relo uildings Repair and Reconstr 3 PD) cation uction Request for Quota AN-NRPB-93655-CW-RFQ / M Housing Repair and Public B Request for Quota Single Stage - One E Under Imple 2020-01-2 TF / A8079 Post Open - National tions (Non Bank-S 500,000.00 0.00 2019-06-06 2019-08-01 inor Repairs to 26 Homes uildings Repair and Reconstr tions nvelope mentation 8 PD) uction Request for Quota AN-NRPB-93655A-CW-RFQ / Housing Repair and Public B Request for Quota Single Stage - One E 2021-01-2 TF / A8079 Post Open - National tions (Non Bank-S 130,000.00 0.00 Signed 2020-06-06 2020-08-01 Minor Repairs to 3 Homes uildings Repair and Reconstr tions nvelope 8 PD) uction Request for Bids - SX-NRPB-357289-CW-RFB / Housing Repair and Public B Open - Internationa Single Stage - One E Small Works SPD Pending Imp 2024-08-1 TF / B5199 Post Request for Bids 4,800,000.00 0.00 2023-04-30 2023-05-05 2023-06-16 2023-07-16 2023-08-20 Renovation of Gyms uildings Repair and Reconstr l nvelope (1 envelope proce lementation 9 uction ss) Request for Bids - SX-NRPB-357290-CW-RFB / Housing Repair and Public B Open - Internationa Single Stage - One E Small Works SPD Pending Imp 2024-08-1 TF / B5199 Post Request for Bids 3,100,000.00 0.00 2023-04-30 2023-05-05 2023-06-16 2023-07-16 2023-08-20 Renovation of Sports facilitie uildings Repair and Reconstr l nvelope (1 envelope proce lementation 9 s uction ss) GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Emergency measures for the SX-NRPB-136740-GO-DIR / Fi TF / A8079 recovery of disaster first res Prior Direct Selection Direct 2,250,000.00 1,938,933.00 Signed 2019-10-01 2020-06-04 2019-10-01 2020-06-18 2019-11-05 2020-02-27 2020-05-03 re Trucks ponders and preparedness f acilities Emergency measures for the SX-NRPB-143339-GO-DIR / S TF / A8079 recovery of disaster first res Prior Direct Selection Direct 15,000.00 15,120.00 Signed 2019-10-29 2020-05-27 2019-11-03 2020-06-15 2019-12-08 2020-01-09 2020-06-05 afety Shoes Fire Department ponders and preparedness f acilities Emergency measures for the SX-NRPB-157539-GO-DIR / D TF / A8079 recovery of disaster first res Post Direct Selection Direct 20,000.00 17,690.00 Signed 2020-02-09 2020-02-04 2020-02-14 2020-03-19 2020-03-20 2020-03-28 2020-09-16 iesel Water Pumps ponders and preparedness f acilities Emergency measures for the SX-NRPB-160723-GO-DIR / A TF / A8079 recovery of disaster first res Post Direct Selection Direct 60,000.00 52,355.72 Signed 2020-02-20 2019-12-11 2020-02-25 2020-03-10 2020-03-31 2020-04-15 2020-09-27 mbulance: Spare Parts ponders and preparedness f acilities SX-NRPB-160730-GO-DIR / F Emergency measures for the D&AD: Additional Radios and TF / A8079 recovery of disaster first res Post Direct Selection Direct 100,000.00 61,381.67 Signed 2020-02-20 2018-06-07 2020-02-25 2020-03-23 2020-03-31 2020-03-24 2020-09-27 Accessories ponders and preparedness f acilities Page 1 Emergency measures for the SX-NRPB-165436-GO-DIR / T TF / A8079 recovery of disaster first res Prior Direct Selection Direct 1,500,000.00 0.00 Canceled 2020-03-19 2020-06-04 2020-03-24 2020-06-18 2020-04-28 2020-10-25 ype II Ambulances ponders and preparedness f acilities Emergency measures for the SX-NRPB-167830-GO-DIR / P TF / A8079 recovery of disaster first res Post Direct Selection Direct 100,000.00 100,213.14 Signed 2020-04-06 2020-03-05 2020-04-06 2020-04-06 2020-05-11 2020-04-22 2020-11-07 roPac Isolation Capsules ponders and preparedness f acilities Emergency measures for the AN-NRPB-76471-GO-RFB / G Open - Internationa Single Stage - One E TF / A8079 recovery of disaster first res Prior Request for Bids 2,385,000.00 1,645,775.00 Signed 2020-05-18 2020-06-18 2020-05-23 2020-09-14 2020-07-04 2020-09-23 2020-08-03 2020-12-10 2020-09-07 2021-02-12 2021-03-06 eneral Vehicles l nvelope ponders and preparedness f acilities Emergency measures for the SX-NRPB-160728-GO-DIR / F TF / A8079 recovery of disaster first res Post Direct Selection Direct 100,000.00 174,753.00 Signed 2020-02-20 2021-05-10 2020-02-25 2021-02-05 2020-03-31 2021-05-26 2020-09-27 D: Spare Parts ponders and preparedness f acilities Emergency measures for the SX-NRPB-160720-GO-DIR / S TF / A8079 recovery of disaster first res Prior Direct Selection Direct 170,000.00 0.00 Canceled 2020-02-20 2020-02-25 2020-03-31 2020-09-27 ubmersible Water Pumps ponders and preparedness f acilities Emergency measures for the SX-NRPB-185662-GO-RFQ / Request for Quota Open - Internationa Single Stage - One E TF / A8079 recovery of disaster first res Post 320,000.00 0.00 Canceled 2020-08-12 2020-10-07 2021-04-05 Crane Trucks (2) tions l nvelope ponders and preparedness f acilities Emergency measures for the SX-NRPB-202313-GO-RFQ / Request for Quota Open - Internationa Single Stage - One E TF / A8079 recovery of disaster first res Post 630,000.00 0.00 Canceled 2020-11-20 2021-03-04 2021-01-15 2021-07-14 Command Vehicles tions l nvelope ponders and preparedness f acilities SX-NRPB-213914-GO-DIR / Si Emergency measures for the nt Maarten Fire Service Repai TF / A8079 recovery of disaster first res Post Direct Selection Direct 15,400.00 21,052.00 Signed 2021-01-15 2021-03-11 2021-01-20 2021-02-05 2021-02-24 2021-04-17 2021-08-23 r Parts 2 : Waziri Export ponders and preparedness f acilities SX-NRPB-213915-GO-DIR / Si Emergency measures for the nt Maarten Fire Service Repai TF / A8079 recovery of disaster first res Post Direct Selection Direct 8,800.00 6,603.47 Signed 2021-01-15 2021-03-11 2021-01-20 2021-02-05 2021-02-24 2021-05-07 2021-08-23 r Parts 3: Saint-Martin Cars ponders and preparedness f acilities Emergency measures for the SX-NRPB-216605-GO-RFQ / T Request for Quota Open - Internationa Single Stage - One E TF / A8079 recovery of disaster first res Post 90,000.00 0.00 Canceled 2021-02-03 2021-06-28 2021-03-31 2021-09-27 hirty Seater Bus (1) tions l nvelope ponders and preparedness f acilities SX-NRPB-218343-GO-DIR / Si Emergency measures for the nt Maarten Fire Service Repai TF / A8079 recovery of disaster first res Post Direct Selection Direct 27,500.00 28,132.52 Signed 2021-02-09 2021-03-11 2021-02-14 2021-02-08 2021-03-21 2021-04-14 2021-09-17 r Parts Package 4: Motorworl ponders and preparedness f d acilities SX-NRPB-218364-GO-DIR / Si Emergency measures for the nt Maarten Fire Service Repai TF / A8079 recovery of disaster first res Post Direct Selection Direct 3,000.00 2,181.54 Signed 2021-02-09 2021-03-11 2021-02-14 2021-02-08 2021-03-21 2021-04-16 2021-09-17 r Parts package 5: Napa Auto ponders and preparedness f Parts SXM acilities SX-NRPB-220199-GO-DIR / T Emergency measures for the ype II Ambulances: Wheeled TF / A8079 recovery of disaster first res Prior Direct Selection Direct 1,500,000.00 1,146,956.00 Signed 2021-02-18 2021-02-18 2021-02-23 2021-02-18 2021-03-30 2021-03-02 2021-09-26 Coach/ REV Group ponders and preparedness f acilities Emergency measures for the SX-NRPB-216373-GO-RFQ / S Request for Quota Open - Internationa Single Stage - One E TF / A8079 recovery of disaster first res Post 215,000.00 0.00 Canceled 2021-02-02 2021-04-12 2021-03-30 2021-09-26 upport Vehicles - Vans tions l nvelope ponders and preparedness f acilities SX-NRPB-221791-GO-DIR / C Emergency measures for the Pending Impl omputer Tablets and Protecti TF / A8079 recovery of disaster first res Post Direct Selection Direct 3,000.00 0.00 2021-02-27 2021-03-04 2021-04-08 2021-10-05 ementation ve Cases: Keijzer Computer S ponders and preparedness f ystems NV acilities Emergency measures for the SX-NRPB-239642-GO-RFQ / Request for Quota Single Stage - One E TF / A8079 recovery of disaster first res Post Limited 215,000.00 124,500.00 Signed 2021-06-22 2021-06-21 2021-08-17 2021-09-17 2022-02-13 Vans II tions nvelope ponders and preparedness f acilities Emergency measures for the SX-NRPB-241317-GO-RFQ / Request for Quota Open - Internationa Single Stage - One E TF / A8079 recovery of disaster first res Post 486,500.00 0.00 Canceled 2021-07-02 2021-07-21 2021-08-27 2022-02-23 Command Vehicles II (7) tions l nvelope ponders and preparedness f acilities Emergency measures for the SX-NRPB-241320-GO-RFQ / Request for Quota Open - Internationa Single Stage - One E TF / A8079 recovery of disaster first res Post 142,500.00 0.00 Canceled 2021-07-02 2021-07-15 2021-08-27 2022-02-23 Command Pick-up Trucks (3) tions l nvelope ponders and preparedness f acilities Emergency measures for the SX-NRPB-202345-GO-RFQ / Request for Quota Single Stage - One E TF / A8079 recovery of disaster first res Post Open - National 35,000.00 0.00 Signed 2020-12-06 2021-01-31 2021-07-30 MDS Goods tions nvelope ponders and preparedness f acilities SX-NRPB-202327-GO-RFQ / Emergency measures for the Request for Quota Open - Internationa Single Stage - One E Pending Impl MDS Automatic Weather Stat TF / A8079 recovery of disaster first res Post 350,000.00 0.00 2022-06-06 2022-08-01 2023-01-28 tions l nvelope ementation ions and Tidal Gauges ponders and preparedness f acilities Emergency measures for the SX-NRPB-275366-GO-DIR / Fi TF / A8079 recovery of disaster first res Post Direct Selection Direct 100,000.00 103,361.00 Signed 2022-02-01 2022-01-26 2022-02-06 2022-03-02 2022-03-13 2022-05-12 2022-09-09 re Suits - Viking ponders and preparedness f acilities SX-NRPB-284636-GO-RFB / F Emergency measures for the Open - Internationa Single Stage - One E Under Imple ire and Ambulance Vehicles ( TF / A8079 recovery of disaster first res Post Request for Bids 108,672.00 0.00 2022-03-21 2022-04-26 2022-03-26 2022-04-27 2022-05-07 2022-05-31 2022-06-06 2022-07-08 2022-07-11 2023-01-07 l nvelope mentation 12) ponders and preparedness f acilities Emergency measures for the SX-NRPB-284650-GO-RFB / V Open - Internationa Single Stage - One E Under Imple TF / A8079 recovery of disaster first res Post Request for Bids 200,000.00 0.00 2022-03-21 2022-07-14 2022-03-26 2022-07-19 2022-05-07 2022-10-04 2022-06-06 2022-11-16 2022-07-11 2023-01-07 ROMI Specialty Trucks l nvelope mentation ponders and preparedness f acilities SX-NRPB-288112-GO-DIR / M Emergency measures for the Pending Impl odular classrooms for tempor TF / A8079 recovery of disaster first res Post Direct Selection Direct 90,000.00 0.00 2022-04-05 2022-04-10 2022-05-15 2022-11-11 ementation ary relocation of classrooms ponders and preparedness f under repair acilities SX-NRPB-300150-GO-DIR / A Emergency measures for the mbulance Vehicle Warning Li TF / A8079 recovery of disaster first res Post Direct Selection Direct 4,000.00 0.00 Completed 2022-06-21 2022-07-01 2022-06-26 2022-07-01 2022-07-31 2023-01-27 2022-11-25 ghts & Siren ponders and preparedness f acilities NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SX-NRPB-160721-NC-DIR / E Housing Repair and Public B mergency Mold Assessment TF / A8079 uildings Repair and Reconstr Post Direct Selection Direct 150,000.00 8,082.00 Signed 2020-02-20 2020-02-21 2020-02-25 2020-02-17 2020-03-31 2020-02-22 2020-09-27 and Remediation Action Plan uction Page 2 SX-NRPB-232003-NC-DIR / R Housing Repair and Public B etroactive Lease Agreement: TF / A8079 uildings Repair and Reconstr Post Direct Selection Direct 4,200.00 5,400.00 Signed 2021-04-30 2021-04-09 2021-05-05 2020-12-04 2021-06-09 2021-05-20 2021-12-06 Simpson Bay Community Cen uction ter SX-NRPB-278661-NC-RFQ / Housing Repair and Public B Request for Quota Single Stage - One E Pending Impl TF / A8079 Post Limited 6,000.00 0.00 2022-02-20 2022-04-17 2022-10-14 Dumpster Rental for 16 Scho uildings Repair and Reconstr tions nvelope ementation ols uction SX-NRPB-278700-NC-RFQ / Housing Repair and Public B Request for Quota Single Stage - One E TF / A8079 Post Limited 100,000.00 0.00 Signed 2022-02-20 2022-05-18 2022-04-17 2022-10-14 Moving Company for 16 Scho uildings Repair and Reconstr tions nvelope ols uction SX-NRPB-278672-NC-DIR / S Housing Repair and Public B ecurity Company Services for TF / A8079 uildings Repair and Reconstr Post Direct Selection Direct 30,000.00 0.00 Signed 2022-02-15 2022-02-11 2022-02-20 2022-02-23 2022-03-27 2022-09-23 MPC School uction SX-NRPB-278674-NC-RFQ / S Housing Repair and Public B Request for Quota Single Stage - One E torage Space/ Container Rent TF / A8079 uildings Repair and Reconstr Post Limited 130,000.00 57,995.00 Signed 2022-02-20 2022-06-13 2022-04-17 2022-08-10 2022-10-14 tions nvelope al for 16 Schools uction SX-NRPB-300184-NC-DIR / A Emergency measures for the mbulance Department Vehicl TF / A8079 recovery of disaster first res Post Direct Selection Direct 1,800.00 0.00 Completed 2022-06-21 2022-07-01 2022-06-26 2022-06-30 2022-07-31 2023-01-27 2022-12-02 e Branding and Striping ponders and preparedness f acilities SX-NRPB-311317-NC-DIR / M Housing Repair and Public B AC High Art Class Transporta TF / A8079 uildings Repair and Reconstr Post Direct Selection Direct - National 32,000.00 0.00 Signed 2022-08-29 2022-08-19 2022-09-03 2022-08-18 2022-10-08 2023-04-06 tion Services uction Emergency measures for the SX-NRPB-312693-NC-DIR / R TF / A8079 recovery of disaster first res Post Direct Selection Direct - National 10,000.00 0.00 Signed 2022-08-31 2022-08-15 2022-09-05 2022-09-07 2022-10-10 2023-04-08 ental for MAC CSE Art Studio ponders and preparedness f acilities SX-NRPB-328192-NC-DIR / S Housing Repair and Public B Pending Impl chools Moving Services Here TF / A8079 uildings Repair and Reconstr Post Direct Selection Direct - National 70,000.00 0.00 2021-02-25 2021-03-02 2021-04-06 2021-10-03 ementation and There Transport B.V uction SX-NRPB-328180-NC-DIR / A Housing Repair and Public B Pending Impl TF / A8079 Post Direct Selection Direct - National 5,000.00 0.00 2022-06-27 2022-07-02 2022-08-06 2023-02-02 rt Class Rental Silvia Carty uildings Repair and Reconstr ementation uction SX-NRPB-328195-NC-DIR / A Institutional Support for Rec Pending Impl dditional Structural Assessm TF / A8079 Post Direct Selection Direct - National 11,000.00 0.00 2021-02-21 2021-02-26 2021-04-02 2021-09-29 onstruction ementation ent and Design of 3 Schools I .C.E SX-NRPB-328194-NC-DIR / A Institutional Support for Rec Pending Impl dditional Structural Design a TF / A8079 Post Direct Selection Direct - National 2,432.00 0.00 2021-05-25 2021-05-30 2021-07-04 2021-12-31 onstruction ementation nd Assessment 3 Schools Pha se Two I.C.E SX-NRPB-328181-NC-DIR / S Housing Repair and Public B Pending Impl chools Security Services Haw TF / A8079 uildings Repair and Reconstr Post Direct Selection Direct - National 15,038.00 0.00 2021-04-28 2021-05-03 2021-06-07 2021-12-04 ementation keye Security Force uction SX-NRPB-328179-NC-DIR / S Housing Repair and Public B Pending Impl chools Transportation Servic TF / A8079 uildings Repair and Reconstr Post Direct Selection Direct - National 4,500.00 0.00 2022-04-01 2022-04-06 2022-05-11 2022-11-07 ementation es Group Transnational Trans uction port Services SX-NRPB-328183-NC-DIR / Fi Emergency measures for the Pending Impl re Dept. Suit Sizing Camille S TF / A8079 recovery of disaster first res Post Direct Selection Direct - National 1,400.00 0.00 2020-10-09 2020-10-14 2020-11-18 2021-05-17 ementation ewing & Boutique ponders and preparedness f acilities SX-NRPB-328182-NC-DIR / Fi Emergency measures for the Under Imple re Dept. Suit Sizing Camille S TF / A8079 recovery of disaster first res Post Direct Selection Direct - National 2,700.00 0.00 2021-09-15 2020-10-09 2021-09-20 2020-10-09 2021-10-25 2022-04-23 mentation ewing & Boutique ponders and preparedness f acilities SX-NRPB-328191-NC-DIR / H Institutional Support for Rec Pending Impl TF / A8079 Post Direct Selection Direct - National 3,901.00 0.00 2021-06-01 2021-06-06 2021-07-11 2022-01-07 ome Assessment I.C.E house onstruction ementation Nr.8 SX-NRPB-328189-NC-DIR / C Institutional Support for Rec Pending Impl ombining Technical Files for TF / A8079 Post Direct Selection Direct - National 1,578.00 0.00 2021-07-07 2021-07-12 2021-08-16 2022-02-12 onstruction ementation Schools RFB 3 I.C.E SX-NRPB-327303-NC-DIR / P Emergency measures for the erforated Vinyl Sides for Amb TF / B5199 recovery of disaster first res Post Direct Selection Direct - National 500.00 0.00 Completed 2022-11-23 2022-11-17 2022-11-28 2022-12-07 2023-01-02 2023-07-01 2023-01-23 ulances ponders and preparedness f acilities SX-NRPB-347195-NC-RFQ / S Housing Repair and Public B Request for Quota Single Stage - One E Under Imple TF / B5199 Post Open - National 96,140.00 0.00 2023-03-18 2023-05-13 2024-08-13 ecurity Services for 13 Schoo uildings Repair and Reconstr tions nvelope mentation ls uction SX-NRPB-347196-NC-DIR / Tr Housing Repair and Public B Pending Impl TF / B5199 Post Direct Selection Direct - National 66,667.00 0.00 2023-03-13 2023-03-18 2023-04-22 2024-03-31 ansportation Services for 13 uildings Repair and Reconstr ementation Schools uction SX-NRPB-347197-NC-DIR / L Housing Repair and Public B ease Agreement with NIPA fo Pending Impl TF / B5199 uildings Repair and Reconstr Post Direct Selection Direct - National 9,943.19 0.00 2023-03-13 2023-03-18 2023-04-22 2023-07-22 r Kitchen & Restaurant faciliti ementation uction es for Sundial School Student s SX-NRPB-347198-NC-DIR / L Housing Repair and Public B ease Agreement with NIA for Pending Impl TF / B5199 uildings Repair and Reconstr Post Direct Selection Direct - National 5,805.00 0.00 2023-03-13 2023-03-18 2023-04-22 2023-07-22 Dance Studio facilities for Su ementation uction ndial School Students CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SX-NRPB-132867-CS-LCS / A Institutional Support for Rec Least Cost Selecti TF / A8079 Prior Open - National 150,000.00 0.00 Canceled 2019-09-05 2019-09-26 2019-11-09 2019-12-07 2020-01-06 2020-02-10 2020-03-16 2020-09-12 udit Services NRPB onstruction on Institutional Support for Rec Least Cost Selecti ERP_C_015 / Audit services TF / A8079 Post Open - National 150,000.00 421,998.00 Signed 2019-09-05 2019-02-13 2019-09-26 2019-09-18 2019-11-09 2019-04-25 2019-12-07 2019-07-11 2020-01-06 2019-07-11 2020-02-10 2019-07-11 2020-03-16 2019-09-29 2020-09-12 onstruction on SX-NRPB-160722-CS-LCS / W Housing Repair and Public B Least Cost Selecti TF / A8079 Post Open - National 25,000.00 59,696.00 Signed 2019-11-06 2020-01-30 2019-11-27 2020-01-10 2020-01-30 2020-02-07 2020-03-25 2020-03-08 2020-03-25 2020-04-12 2020-03-25 2020-05-17 2020-04-24 2020-11-13 orks Verification Audit SMHD uildings Repair and Reconstr on F uction AN-IRC-NRPB-88561-CS-CQS Housing Repair and Public B Consultant Qualifi / SMHDF Technical Assessme TF / A8079 uildings Repair and Reconstr Post Open - National 250,000.00 207,300.00 Completed 2020-10-15 2019-01-03 2020-11-05 2020-11-17 2020-12-19 2019-01-24 2021-01-18 2019-09-27 2021-02-22 2019-10-01 2021-08-21 2020-04-09 cation Selection nt and Design for Phase 2 uction Page 3 AN-IRC-NRPB-109549-CS-QC Housing Repair and Public B Quality And Cost- BS / Technical Assessment Si TF / A8079 uildings Repair and Reconstr Post Open - National 500,000.00 522,461.00 Signed 2020-11-03 2019-07-10 2020-11-24 2021-08-04 2021-01-07 2019-04-22 2021-02-04 2019-04-22 2021-03-06 2019-04-22 2021-04-10 2019-07-11 2021-05-15 2019-07-16 2022-05-15 Based Selection ngle family Home Repairs 2 uction AN-NRPB-76431-CS-CQS / Su pervision Shelter Repairs Mai Institutional Support for Rec Consultant Qualifi n and Recovery Housing Rep TF / A8079 Post Open - National 100,000.00 402,811.88 Signed 2021-05-19 2019-02-11 2021-06-09 2022-03-08 2021-07-23 2019-03-22 2021-08-22 2019-08-12 2021-09-26 2019-08-16 2022-03-25 onstruction cation Selection air and Public Buildings Repai r and Reconstruction SX-NRPB-202330-CS-CQS / E Emergency measures for the Quality And Cost- Open - Internationa Pending Impleme mergency Cell Broadcast Sys TF / A8079 recovery of disaster first res Post 350,000.00 0.00 2022-06-01 2022-06-22 2022-08-05 2022-09-02 2022-10-02 2022-11-06 2022-12-11 2023-12-11 Based Selection l ntation tem ponders and preparedness f acilities SX-NRPB-298818-CS-LCS / N Institutional Support for Rec Least Cost Selecti Open - Internationa TF / A8079 Post 545,000.00 0.00 Signed 2022-06-14 2022-06-29 2022-07-05 2022-08-18 2022-07-05 2022-09-15 2022-08-15 2022-10-15 2022-09-29 2022-11-19 2022-09-29 2022-12-24 2023-06-22 RPB Financial Audit Services onstruction on l SX-NRPB-317497-CS-CQS / S Institutional Support for Rec Consultant Qualifi Open - Internationa TF / B5199 Post 20,000.00 0.00 Canceled 2022-09-23 2022-10-23 2022-11-07 2022-12-09 2023-01-08 2023-03-08 ecurity Assessment onstruction cation Selection l SX-NRPB-338215-CS-QCBS / Emergency measures for the Quality And Cost- Open - Internationa Under Implement Project Management Service TF / B5199 recovery of disaster first res Prior 3,000,000.00 0.00 2023-01-27 2023-04-12 2023-02-17 2023-05-17 2023-04-02 2023-04-30 2023-05-30 2023-07-04 2023-08-08 2024-12-02 Based Selection l ation s for ERP-1 ponders and preparedness f acilities SX-NRPB-352121-CS-CQS / P Housing Repair and Public B Consultant Qualifi Open - Internationa Pending Impleme TF / B5199 Post 150,000.00 0.00 2023-08-06 2023-08-27 2023-10-10 2023-11-09 2023-11-27 2024-11-26 reparation GEBE Investment uildings Repair and Reconstr cation Selection l ntation Plan uction INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SX-NRPB-124802-CS-INDV / Institutional Support for Rec Individual Consult PROJECT COORDINATOR– Sin TF / A8079 Post Open 180,000.00 267,983.36 Signed 2019-07-25 2019-07-25 2019-09-12 2019-10-18 2019-10-03 2019-11-25 2019-11-07 2020-05-30 2020-05-05 onstruction ant Selection t Maarten Digital Governmen t Project SX-NRPB-126135-CS-INDV / Institutional Support for Rec Individual Consult TF / A8079 Prior Open 60,000.00 59,241.98 Signed 2019-08-03 2019-08-07 2019-09-21 2019-11-21 2019-10-12 2020-07-07 2019-11-16 2020-01-17 2020-05-14 Procurement Assistant Consu onstruction ant Selection ltant SX-NRPB-126138-CS-INDV / Institutional Support for Rec Individual Consult TF / A8079 Prior Open 90,000.00 0.00 Canceled 2019-08-03 2019-08-07 2019-09-21 2019-10-12 2019-11-16 2020-05-14 Procurement Specialist Cons onstruction ant Selection ultant SX-NRPB-126137-CS-INDV / Institutional Support for Rec Individual Consult Portfolio and Accounting Offi TF / A8079 Post Open 180,000.00 0.00 Canceled 2019-08-03 2019-08-07 2019-09-21 2019-10-12 2019-11-16 2020-05-14 onstruction ant Selection cer for Small Enterprise Reco very Project SX-NRPB-126665-CS-CDS / I Institutional Support for Rec TF / A8079 Post Direct Selection Direct 14,000.00 12,150.00 Signed 2019-08-12 2019-09-01 2019-08-22 2019-08-08 2019-10-26 2019-09-01 2020-04-23 nterim Financial Managemen onstruction t Officer SX-NRPB-127209-CS-CDS / S Institutional Support for Rec TF / A8079 Post Direct Selection Direct 45,000.00 44,000.00 Signed 2019-08-14 2019-08-09 2019-08-24 2019-08-08 2019-10-28 2019-08-16 2020-04-25 takeholder Engagement Hom onstruction e Repairs SX-NRPB-128034-CS-INDV / J Institutional Support for Rec Individual Consult TF / A8079 Post Open 80,000.00 43,436.52 Terminated 2019-08-20 2019-08-23 2019-10-08 2019-10-18 2019-10-29 2019-11-12 2019-12-03 2019-11-16 2020-05-31 unior Communications Consu onstruction ant Selection ltant SX-NRPB-128036-CS-INDV / Institutional Support for Rec Individual Consult TF / A8079 Post Open 40,000.00 27,000.00 Signed 2019-08-19 2019-08-22 2019-10-07 2019-11-19 2019-10-28 2019-11-26 2019-12-02 2019-11-27 2020-05-30 Financial Management Assist onstruction ant Selection ant SX-NRPB-129158-CS-INDV / Institutional Support for Rec Individual Consult TF / A8079 Post Open 80,000.00 61,699.24 Signed 2019-08-26 2019-08-30 2019-10-14 2019-11-13 2019-11-04 2019-11-18 2019-12-09 2019-11-20 2020-06-06 Executive Assistant onstruction ant Selection SX-NRPB-129299-CS-INDV / J Institutional Support for Rec Individual Consult TF / A8079 Post Open 80,000.00 106,076.17 Signed 2019-08-30 2019-08-30 2019-10-18 2019-11-18 2019-11-08 2020-03-30 2019-12-13 2020-05-30 2020-06-10 r Environmental Safeguards onstruction ant Selection Specialist SX-NRPB-134548-CS-INDV / Institutional Support for Rec Individual Consult TF / A8079 Post Open 25,000.00 0.00 Canceled 2019-09-16 2018-12-10 2019-11-04 2019-11-25 2019-12-30 2020-06-27 Communications Specialist onstruction ant Selection SX-NRPB-144180-CS-CDS / D Emergency measures for the esign Fire Department Renov TF / A8079 recovery of disaster first res Post Direct Selection Direct 100,000.00 0.00 Canceled 2019-11-04 2021-05-03 2019-11-04 2020-01-08 2020-07-06 ation and Expansion ponders and preparedness f acilities SX-NRPB-146192-CS-INDV / Institutional Support for Rec Individual Consult TF / A8079 Post Open 150,000.00 0.00 Canceled 2019-12-12 2019-12-12 2020-02-14 2020-03-06 2020-04-10 2020-10-07 Contract Manager onstruction ant Selection SX-NRPB-153308-CS-INDV / Institutional Support for Rec Individual Consult TF / A8079 Post Open 150,000.00 108,000.00 Signed 2020-01-31 2020-01-24 2020-03-20 2020-06-11 2020-04-10 2020-06-24 2020-05-15 2020-06-25 2020-11-11 Project Manager Education Pr onstruction ant Selection oject SX-NRPB-154610-CS-CDS / Institutional Support for Rec Mission Project Manager Digit TF / A8079 Post Direct Selection Direct 8,000.00 7,250.00 Signed 2020-01-20 2020-01-21 2020-01-20 2019-10-18 2020-01-27 2020-01-24 2020-02-17 onstruction al Government SX-NRPB-155761-CS-INDV / Institutional Support for Rec Individual Consult Project Manager Enterprise R TF / A8079 Post Open 150,000.00 0.00 Canceled 2020-01-24 2020-03-13 2020-04-03 2020-05-08 2020-11-04 onstruction ant Selection ecovery Project SX-NRPB-156570-CS-CDS / P Institutional Support for Rec TF / A8079 Post Direct Selection Direct 320,000.00 0.00 Canceled 2020-01-29 2020-01-29 2020-05-03 2020-10-30 rocurement Consultant Servi onstruction ces SX-NRPB-146438-CS-INDV / Institutional Support for Rec Individual Consult TF / A8079 Prior Open 150,000.00 0.00 Canceled 2019-11-20 2020-01-08 2020-01-29 2020-03-04 2020-08-31 Procurement Specialist Cons onstruction ant Selection ultant 2 SX-NRPB-156572-CS-CDS / P roject Manager ERP-1 Institutional Support for Rec This is a continuation of the c TF / A8079 Post Direct Selection Direct 185,000.00 184,500.00 Signed 2020-01-29 2020-03-10 2020-02-08 2020-03-10 2020-04-13 2020-03-26 2020-10-10 onstruction urrent contract. This contract will go into effect on April 1 - March 31 2021. SX-NRPB-146440-CS-INDV / Institutional Support for Rec Individual Consult TF / A8079 Post Limited 50,000.00 57,975.00 Signed 2019-11-22 2019-11-27 2019-11-27 2020-01-20 2020-02-07 2020-03-09 2020-03-13 2020-03-13 2020-09-09 Activity Manager School Rep onstruction ant Selection airs SX-NRPB-159532-CS-CDS / N Institutional Support for Rec TF / A8079 Prior Direct Selection Direct 200,000.00 49,262.46 Signed 2020-02-13 2021-02-02 2020-02-13 2020-02-13 2020-04-17 2020-02-13 2020-10-14 RPB Legal Services onstruction Page 4 SX-NRPB-161524-CS-CDS / A Institutional Support for Rec Pending Impleme TF / A8079 Post Direct Selection Direct 8,000.00 0.00 2020-02-26 2020-03-07 2020-05-11 2020-11-07 irport Benchmark Study onstruction ntation SX-NRPB-165435-CS-CDS / E Institutional Support for Rec TF / A8079 Post Direct Selection Direct 225,000.00 220,500.00 Signed 2020-03-19 2019-07-09 2020-03-29 2020-03-20 2020-06-02 2020-03-21 2020-11-29 ngineer onstruction SX-NRPB-166957-CS-CDS / P Institutional Support for Rec roject Coordinator Digital Go TF / A8079 Post Direct Selection Direct 16,000.00 40,000.00 Signed 2020-03-30 2019-12-01 2020-04-09 2020-04-02 2020-06-13 2020-04-10 2020-12-10 onstruction vernment INTERIM SX-NRPB-168099-CS-CDS / S Institutional Support for Rec TF / A8079 Post Direct Selection Direct 150,000.00 182,550.00 Signed 2020-04-08 2020-07-31 2020-04-18 2020-04-07 2020-06-22 2020-08-17 2020-12-19 ocial Safeguards Specialist onstruction SX-NRPB-168800-CS-CDS / D Institutional Support for Rec TF / A8079 Post Direct Selection Direct 120,000.00 177,000.00 Signed 2020-04-15 2020-04-14 2020-04-25 2020-05-04 2020-06-29 2020-05-05 2020-12-26 esign Rehabilitation of Shelte onstruction rs SX-NRPB-173096-CS-INDV / J Institutional Support for Rec Individual Consult TF / A8079 Post Open 60,000.00 89,982.21 Signed 2020-05-11 2019-10-01 2020-06-29 2020-05-15 2020-07-20 2020-06-19 2020-08-24 2020-06-23 2021-02-20 r Communication Officer 2 onstruction ant Selection SX-NRPB-167363-CS-CDS / Institutional Support for Rec TF / A8079 Prior Direct Selection Direct 30,000.00 63,000.00 Signed 2020-04-02 2021-01-12 2020-04-12 2020-05-08 2020-06-16 2020-05-08 2020-12-13 MP: Procurement Consultant onstruction SX-NRPB-167376-CS-CDS / S Institutional Support for Rec TF / A8079 Prior Direct Selection Direct 30,000.00 223,500.00 Signed 2020-04-02 2020-07-22 2020-04-12 2020-04-02 2020-06-16 2020-04-24 2020-12-13 I: Procurement Consultant onstruction SX-NRPB-186632-CS-CDS / T Housing Repair and Public B wenty Schools and F&A buildi TF / A8079 uildings Repair and Reconstr Prior Direct Selection Direct 820,600.00 790,190.00 Signed 2020-07-30 2020-08-19 2020-08-09 2020-05-19 2020-10-13 2020-09-01 2021-04-11 ng Design Consulting uction SX-NRPB-186392-CS-CDS / A Housing Repair and Public B sbestos Assessment Consulti TF / A8079 uildings Repair and Reconstr Post Direct Selection Direct 25,000.00 56,950.00 Signed 2020-07-29 2020-07-29 2020-08-08 2020-08-23 2020-10-12 2020-09-19 2021-04-10 ng Services ROBERTO DAVID uction OVICH SX-NRPB-189349-CS-INDV / Institutional Support for Rec Individual Consult TF / A8079 Post Open 85,000.00 0.00 Canceled 2020-08-18 2019-11-14 2020-10-06 2020-10-27 2020-12-01 2021-05-30 HR Consultant onstruction ant Selection SX-NRPB-189691-CS-CDS / L Emergency measures for the and Negotiation for Link 6 Ro TF / A8079 recovery of disaster first res Prior Direct Selection Direct 50,000.00 0.00 Canceled 2020-08-20 2020-08-28 2020-08-30 2020-09-23 2020-11-03 2021-05-02 ad-Hubert Lopez HISMAR NV ponders and preparedness f acilities SX-NRPB-191068-CS-CDS / S Institutional Support for Rec TF / A8079 Prior Direct Selection Direct 125,000.00 501,550.00 Signed 2020-08-28 2021-04-01 2020-09-07 2020-10-20 2020-11-11 2020-10-26 2021-05-10 GS Procurement Service onstruction SX-NRPB-196201-CS-CDS / F Institutional Support for Rec TF / A8079 Post Direct Selection Direct 30,000.00 0.00 Under Review 2020-09-25 2020-10-05 2020-12-09 2021-06-07 MO Consultant Home Based onstruction SX-NRPB-197284-CS-INDV / Institutional Support for Rec Individual Consult TF / A8079 Post Open 180,000.00 181,250.00 Signed 2020-10-01 2020-12-12 2020-11-19 2020-05-18 2020-12-10 2020-06-01 2021-01-14 2021-01-12 2021-07-13 DL - Contract Manager onstruction ant Selection SX-NRPB-198813-CS-INDV / Institutional Support for Rec Individual Consult TF / A8079 Post Open 150,000.00 0.00 Canceled 2020-10-15 2020-11-19 2020-12-03 2020-12-24 2021-01-28 2021-07-27 AR - Contract Manager onstruction ant Selection SX-NRPB-126986-CS-CDS / C Institutional Support for Rec Pending Impleme TF / A8079 Post Direct Selection Direct 85,690.00 0.00 2019-08-16 2019-08-26 2019-10-30 2020-04-27 orporate Governance Lawyer onstruction ntation 1 SX-NRPB-126988-CS-CDS / C Institutional Support for Rec Pending Impleme TF / A8079 Post Direct Selection Direct 61,250.00 0.00 2019-08-16 2019-08-26 2019-10-30 2020-04-27 orporate Governance Legal S onstruction ntation upport 1 SX-NRPB-126989-CS-CDS / C Institutional Support for Rec Pending Impleme TF / A8079 Post Direct Selection Direct 28,500.00 0.00 2019-08-16 2019-08-26 2019-10-30 2020-04-27 orporate Governance Legal S onstruction ntation upport 2 SX-NRPB-126987-CS-CDS / C Institutional Support for Rec Pending Impleme TF / A8079 Post Direct Selection Direct 79,000.00 0.00 2019-08-16 2019-08-26 2019-10-30 2020-04-27 orporate Governance Lawyer onstruction ntation 2 SX-NRPB-199448-CS-CDS / C Institutional Support for Rec TF / A8079 Post Direct Selection Direct 23,750.00 23,684.00 Signed 2020-10-13 2020-11-19 2020-10-23 2020-02-06 2020-12-27 2020-10-29 2021-06-25 ontract Manager (DL) Home onstruction Based SX-NRPB-170435-CS-CDS / I Institutional Support for Rec nterim Environmental Safegu TF / A8079 Post Direct Selection Direct 20,000.00 21,720.00 Signed 2020-04-24 2019-09-02 2020-05-04 2019-11-18 2020-07-08 2020-05-08 2021-01-04 onstruction ards Specialist SX-NRPB-201640-CS-CDS / J Institutional Support for Rec TF / A8079 Prior Direct Selection Direct 95,000.00 189,000.00 Signed 2020-10-26 2020-10-29 2020-11-05 2020-10-29 2021-01-09 2021-01-01 2021-07-08 B: Procurement Coordinator onstruction SX-NRPB-201789-CS-INDV / I Institutional Support for Rec Individual Consult Under Implement TF / A8079 Post Limited 25,000.00 0.00 2020-10-27 2020-10-27 2020-11-01 2020-11-22 2020-12-27 2021-06-25 nsurance Consultant onstruction ant Selection ation SX-NRPB-201788-CS-CDS / U Institutional Support for Rec TF / A8079 Post Direct Selection Direct 155,000.00 163,252.75 Signed 2020-10-27 2020-10-21 2020-11-06 2020-09-16 2021-01-10 2020-11-03 2021-07-09 B: Activity Manager Home Re onstruction pairs SX-NRPB-201795-CS-CDS / B Institutional Support for Rec TF / A8079 Post Direct Selection Direct 200,000.00 125,000.00 Signed 2020-10-27 2020-11-24 2020-11-06 2019-11-01 2021-01-10 2020-12-17 2021-07-09 B: ICT Helpdesk onstruction SX-NRPB-205755-CS-INDV / Institutional Support for Rec Individual Consult TF / A8079 Post Open 50,000.00 50,000.00 Signed 2020-11-24 2020-11-20 2021-01-12 2021-03-04 2021-02-02 2021-03-04 2021-03-09 2021-05-20 2021-09-05 Copywriter onstruction ant Selection SX-NRPB-208921-CS-CDS / Institutional Support for Rec Mold Assessment Consultanc TF / A8079 Post Direct Selection Direct 50,000.00 141,910.00 Signed 2020-12-09 2020-12-07 2020-12-19 2020-12-03 2021-02-22 2021-01-15 2021-08-21 onstruction y: Farmer Environmental Gro up SX-NRPB-214549-CS-CDS / J Institutional Support for Rec TF / A8079 Prior Direct Selection Direct 50,000.00 48,000.00 Signed 2021-01-18 2021-01-28 2021-01-28 2021-01-07 2021-04-03 2021-02-10 2021-09-30 A: Procurement Consultant onstruction SX-NRPB-215465-CS-CDS / A Housing Repair and Public B TF / A8079 Post Direct Selection Direct 200,000.00 218,842.20 Signed 2021-01-21 2021-01-20 2021-01-31 2021-01-21 2021-04-06 2021-02-16 2021-10-03 C: Project Manager Infrastruc uildings Repair and Reconstr ture uction SX-NRPB-211337-CS-CDS / E Institutional Support for Rec TF / A8079 Post Direct Selection Direct 350,000.00 0.00 Canceled 2020-12-23 2021-01-02 2021-03-08 2021-09-04 ngineer onstruction SX-NRPB-231555-CS-INDV / J Emergency measures for the Individual Consult unior Environmental Speciali TF / A8079 recovery of disaster first res Post Open 60,000.00 70,200.00 Signed 2021-04-29 2021-05-18 2021-06-17 2021-09-06 2021-07-08 2021-09-30 2021-08-12 2021-10-01 2022-02-08 ant Selection st ponders and preparedness f acilities Page 5 SX-NRPB-232896-CS-INDV / Institutional Support for Rec Individual Consult TF / A8079 Post Open 15,000.00 43,875.00 Signed 2021-05-03 2021-05-06 2021-06-21 2021-08-13 2021-07-12 2021-08-19 2021-08-16 2021-08-28 2022-02-12 HRM Consultant onstruction ant Selection SX-NRPB-236664-CS-INDV / Institutional Support for Rec Individual Consult TF / A8079 Post Open 30,000.00 20,000.00 Signed 2021-05-28 2021-06-08 2021-07-16 2021-08-05 2021-08-06 2021-09-21 2021-09-10 2021-10-30 2022-03-09 Graphic Design Services onstruction ant Selection SX-NRPB-236668-CS-INDV / Institutional Support for Rec Individual Consult TF / A8079 Post Open 30,000.00 35,000.00 Signed 2021-05-28 2021-06-08 2021-07-16 2021-08-05 2021-08-06 2021-09-21 2021-09-10 2021-11-04 2022-03-09 Video Production Services onstruction ant Selection SX-NRPB-236671-CS-INDV / Institutional Support for Rec Individual Consult TF / A8079 Post Open 30,000.00 30,000.00 Signed 2021-05-28 2021-06-08 2021-07-16 2021-08-05 2021-08-06 2021-09-21 2021-09-10 2021-10-30 2022-03-09 Animation Services onstruction ant Selection SX-NRPB-239247-CS-CDS / S Institutional Support for Rec ocial Safeguards Consultant: TF / A8079 Post Direct Selection Direct 200,000.00 200,000.00 Signed 2021-06-14 2021-06-16 2021-06-24 2021-06-28 2021-08-28 2020-07-13 2022-02-24 onstruction Jo-Ann George SX-NRPB-240330-CS-CDS / Institutional Support for Rec TF / A8079 Post Direct Selection Direct 280,000.00 251,210.00 Signed 2021-06-18 2021-06-28 2021-06-20 2021-06-21 2021-06-23 2021-07-07 2023-05-31 MH: Project Manager EDMP onstruction SX-NRPB-241445-CS-CDS / D Emergency measures for the esign Fire Dept. Renovation a TF / A8079 recovery of disaster first res Post Direct Selection Direct 160,000.00 159,900.00 Signed 2021-06-28 2021-05-21 2021-07-08 2021-05-03 2021-09-11 2021-07-01 2022-03-10 nd Expansion: ICE ponders and preparedness f acilities SX-NRPB-242711-CS-CDS / P Institutional Support for Rec rocurement Coordinator: San TF / A8079 Post Direct Selection Direct 267,000.00 266,640.00 Signed 2021-07-11 2021-07-15 2021-07-21 2021-06-08 2021-09-24 2021-08-03 2022-03-23 onstruction tiago Ibarguen SX-NRPB-246966-CS-INDV / Institutional Support for Rec Individual Consult Under Implement TF / A8079 Prior Open 80,000.00 0.00 2021-09-17 2021-09-21 2021-11-05 2021-11-26 2021-12-31 2022-06-29 NRPB Procurement Assistant onstruction ant Selection ation SX-NRPB-252781-CS-CDS / P Institutional Support for Rec roject Funding Coordinator – TF / A8079 Post Direct Selection Direct 20,000.00 0.00 Canceled 2021-09-12 2021-09-08 2021-09-22 2021-11-26 2022-05-25 onstruction Housing Project SX-NRPB-253548-CS-INDV / Institutional Support for Rec Individual Consult TF / A8079 Post Open 180,000.00 102,600.00 Signed 2021-09-17 2021-09-30 2021-11-05 2021-11-15 2021-11-26 2022-01-12 2021-12-31 2022-01-13 2022-06-29 DGTP Project Manager for DL onstruction ant Selection T SX-NRPB-254305-CS-INDV / Institutional Support for Rec Individual Consult Under Implement TF / A8079 Post Open 90,000.00 0.00 2021-09-24 2021-09-15 2021-11-12 2021-12-03 2022-01-07 2022-07-06 Program Management Assist onstruction ant Selection ation ant SX-NRPB-256482-CS-INDV / Institutional Support for Rec Individual Consult Under Implement TF / A8079 Post Open 90,000.00 0.00 2021-10-07 2021-10-05 2021-11-25 2021-12-16 2022-01-20 2022-07-19 Project Manager - Mental Hea onstruction ant Selection ation lth Project SX-NRPB-257387-CS-INDV / Institutional Support for Rec Individual Consult TF / A8079 Post Open 60,000.00 58,800.00 Signed 2021-10-12 2021-10-08 2021-11-30 2022-01-27 2021-12-21 2022-04-06 2022-01-25 2022-04-07 2022-07-24 Executive Assistant II onstruction ant Selection SX-NRPB-257388-CS-INDV / Institutional Support for Rec Individual Consult TF / A8079 Post Open 180,000.00 163,500.00 Signed 2021-10-12 2021-10-07 2021-11-30 2021-09-20 2021-12-21 2021-10-19 2022-01-25 2021-10-22 2022-07-24 Engineer II onstruction ant Selection SX-NRPB-257389-CS-INDV / Institutional Support for Rec Individual Consult TF / A8079 Post Open 245,000.00 244,000.00 Signed 2021-10-12 2021-10-07 2021-11-30 2021-09-22 2021-12-21 2021-10-12 2022-01-25 2021-11-02 2022-07-24 Contract Manager II onstruction ant Selection SX-NRPB-257455-CS-CDS / E Institutional Support for Rec TF / A8079 Post Direct Selection Direct 20,000.00 31,972.50 Signed 2021-10-12 2021-10-07 2021-10-22 2021-09-20 2021-12-26 2021-10-22 2022-06-24 ngineer II onstruction SX-NRPB-258195-CS-CDS / P Institutional Support for Rec TF / A8079 Prior Direct Selection Direct 40,000.00 82,400.00 Signed 2021-10-15 2021-10-19 2021-10-25 2021-10-20 2021-12-29 2021-11-02 2022-06-27 rocurement Consultant: Paol onstruction o Maculotti SX-NRPB-258246-CS-CDS / P Institutional Support for Rec roject Finance Specialist-Hou TF / A8079 Post Direct Selection Direct 20,000.00 23,240.00 Signed 2021-10-14 2021-10-13 2021-10-24 2021-10-14 2021-12-28 2021-10-15 2022-06-26 onstruction sing Project SX-NRPB-258918-CS-CDS / P Institutional Support for Rec TF / A8079 Post Direct Selection Direct 15,000.00 12,750.00 Signed 2021-10-22 2021-10-27 2021-11-01 2021-10-27 2022-01-05 2021-10-30 2022-07-04 roject Officer - Mental Health onstruction Project SX-NRPB-262565-CS-INDV / Institutional Support for Rec Individual Consult TF / A8079 Post Direct 130,000.00 140,000.00 Signed 2021-11-12 2021-11-08 2021-11-22 2021-10-20 2021-12-13 2021-12-04 2022-01-17 2021-12-13 2022-07-16 Procurement Consultant: Ms. onstruction ant Selection Jackson SX-NRPB-270528-CS-CDS / S Housing Repair and Public B TF / A8079 Post Direct Selection Direct 350,000.00 294,850.00 Signed 2021-12-24 2022-01-17 2022-01-03 2021-12-21 2022-03-09 2022-02-20 2022-09-05 chool Gyms Technical Assess uildings Repair and Reconstr ment uction SX-NRPB-272351-CS-CDS / P Institutional Support for Rec rocurement Consultant - Ho TF / A8079 Post Direct Selection Direct 72,090.00 72,090.00 Signed 2022-01-10 2022-01-14 2022-01-20 2022-01-18 2022-03-26 2022-01-22 2022-09-22 onstruction me Based : Paolo Maculotti SX-NRPB-272355-CS-CDS / P Institutional Support for Rec roject Manager EDMP: East W TF / A8079 Post Direct Selection Direct 165,000.00 174,000.00 Signed 2022-01-10 2022-01-07 2022-01-20 2022-01-05 2022-03-26 2022-02-25 2022-09-22 onstruction est Consultancy BV SX-NRPB-278264-CS-INDV / Institutional Support for Rec Individual Consult TF / A8079 Post Open 250,000.00 295,050.00 Signed 2022-02-14 2022-03-01 2022-04-04 2022-04-18 2022-04-25 2022-05-16 2022-05-30 2022-05-17 2022-11-26 Senior Project Manager ERP1 onstruction ant Selection SX-NRPB-278699-CS-CDS / D Housing Repair and Public B esign of Fire Dept. Renovatio TF / A8079 uildings Repair and Reconstr Post Direct Selection Direct 171,124.00 152,075.25 Signed 2022-02-15 2022-03-24 2022-02-25 2022-03-14 2022-05-01 2022-03-31 2022-10-28 n and Expansion completion uction of deliverables SX-NRPB-281075-CS-CDS / C Institutional Support for Rec TF / A8079 Post Direct Selection Direct 180,000.00 181,250.00 Signed 2022-02-28 2022-03-11 2022-03-10 2022-01-14 2022-05-14 2022-03-31 2022-11-10 ontract Manager - D. Louis onstruction SX-NRPB-282293-CS-INDV / Institutional Support for Rec Individual Consult Under Implement TF / A8079 Post Open 245,000.00 0.00 2022-03-11 2022-03-03 2022-04-29 2022-05-20 2022-06-24 2022-12-21 Social Safeguards Specialist onstruction ant Selection ation SX-NRPB-280013-CS-CDS / E Institutional Support for Rec TF / A8079 Post Direct Selection Direct 125,000.00 112,370.00 Signed 2022-03-08 2022-03-14 2022-03-18 2022-03-04 2022-05-22 2022-03-16 2022-11-18 nvironmental Safeguards Spe onstruction cialist SX-NRPB-286353-CS-INDV / Institutional Support for Rec Individual Consult TF / A8079 Post Direct 52,500.00 150,480.00 Signed 2022-03-28 2022-03-21 2022-04-07 2022-03-23 2022-04-28 2022-03-23 2022-06-02 2022-04-06 2022-11-29 Senior Human Resources Con onstruction ant Selection sultant SX-NRPB-286729-CS-CDS / E Housing Repair and Public B Under Implement SS8 Cultural Heritage Mental TF / A8079 uildings Repair and Reconstr Post Direct Selection Direct 20,000.00 0.00 2022-03-30 2022-04-14 2022-04-09 2022-04-21 2022-06-13 2022-12-10 ation Health Project uction SX-NRPB-287284-CS-INDV / Institutional Support for Rec Individual Consult TF / A8079 Post Direct 105,000.00 103,106.00 Signed 2022-03-31 2022-05-24 2022-04-10 2022-05-31 2022-05-01 2022-05-31 2022-06-05 2022-06-02 2022-12-02 Activity Coordinator Home an onstruction ant Selection d Schools Page 6 SX-NRPB-288109-CS-INDV / Institutional Support for Rec Individual Consult Under Implement TF / A8079 Post Direct 161,712.00 0.00 2022-04-05 2022-05-15 2022-04-15 2022-08-17 2022-05-06 2022-08-17 2022-06-10 2022-12-07 Social Safeguards Consultant onstruction ant Selection ation SX-NRPB-291870-CS-CDS / R Housing Repair and Public B eview of MET building design TF / A8079 uildings Repair and Reconstr Post Direct Selection Direct 7,400.00 6,688.00 Signed 2022-04-28 2022-05-04 2022-05-08 2022-04-13 2022-07-12 2022-05-10 2023-01-08 : Structural Integrity uction SX-NRPB-287287-CS-INDV / Institutional Support for Rec Individual Consult TF / A8079 Post Direct 136,940.00 136,980.00 Signed 2022-05-04 2022-04-26 2022-05-14 2022-04-22 2022-06-04 2022-05-05 2022-07-09 2022-05-06 2023-01-05 Senior Advisor – Project Mana onstruction ant Selection gement SX-NRPB-294730-CS-INDV / Institutional Support for Rec Individual Consult Under Implement Medior Project Manager – Ho TF / A8079 Post Open 162,000.00 0.00 2022-05-17 2022-05-13 2022-07-05 2022-07-26 2022-08-30 2023-02-26 onstruction ant Selection ation using Project SX-NRPB-295647-CS-INDV / Institutional Support for Rec Individual Consult Communication Consultant - TF / A8079 Post Direct 63,250.00 63,000.00 Signed 2022-05-24 2022-05-16 2022-06-03 2022-06-30 2022-06-24 2022-06-30 2022-07-29 2022-07-01 2023-01-25 onstruction ant Selection Copywriter SX-NRPB-298841-CS-INDV / Institutional Support for Rec Individual Consult Communication and Commu TF / A8079 Post Direct 57,000.00 57,000.00 Signed 2022-06-10 2022-06-09 2022-06-20 2022-06-15 2022-07-11 2022-06-15 2022-08-15 2022-06-17 2023-02-11 onstruction ant Selection nity Outreach Consultant SX-NRPB-304252-CS-INDV / Institutional Support for Rec Individual Consult Direct - Internation PROJECT COORDINATOR - INF TF / A8079 Post 229,786.00 229,786.00 Signed 2022-07-21 2022-07-25 2022-07-31 2022-07-26 2022-08-21 2022-07-31 2022-09-25 2022-07-30 2024-03-25 onstruction ant Selection al RASTRUCTURE ERP-1 SX-NRPB-312698-CS-INDV / Institutional Support for Rec Individual Consult Open - Internationa Under Implement Communications and Commu TF / A8079 Post 91,200.00 0.00 2022-08-31 2022-08-25 2022-10-19 2022-11-09 2022-12-14 2023-12-14 onstruction ant Selection l ation nity Outreach Consultant SX-NRPB-314853-CS-INDV / Institutional Support for Rec Individual Consult Open - Internationa Under Implement Project Manager - St. Maarte TF / B5199 Post 270,000.00 0.00 2022-09-16 2022-09-20 2022-11-04 2022-11-25 2022-12-30 2024-06-30 onstruction ant Selection l ation n Wastewater Management P roject SX-NRPB-322083-CS-INDV / I Institutional Support for Rec Individual Consult Direct - Internation TF / B5199 Post 14,500.00 0.00 Signed 2022-10-21 2022-10-25 2022-10-31 2022-10-27 2022-11-21 2022-10-27 2022-12-26 2023-01-31 nterim Project coordinator W onstruction ant Selection al astewater SX-NRPB-325069-CS-INDV / Institutional Support for Rec Individual Consult Direct - Internation TF / B5199 Post 271,140.00 0.00 Signed 2022-11-15 2022-11-03 2022-11-25 2022-11-03 2022-12-16 2022-12-13 2023-01-20 2024-07-21 Head of Procurement - S.I onstruction ant Selection al SX-NRPB-326442-CS-INDV / J Institutional Support for Rec Individual Consult Pending Impleme TF / B5199 Post Open - National 90,000.00 0.00 2022-11-30 2023-01-18 2023-02-08 2023-03-15 2024-09-13 r. M&E Consultant onstruction ant Selection ntation SX-NRPB-326444-CS-INDV / Institutional Support for Rec Individual Consult Direct - Internation Under Implement TF / B5199 Post 160,000.00 0.00 2022-11-28 2022-01-11 2022-12-08 2023-01-12 2022-12-29 2023-01-12 2023-01-16 2024-07-17 Program Advisor onstruction ant Selection al ation SX-NRPB-326641-CS-INDV / Institutional Support for Rec Individual Consult Open - Internationa Under Implement TF / B5199 Post 260,000.00 0.00 2022-11-30 2023-01-11 2023-01-18 2023-02-08 2023-05-08 2024-11-06 Project Manager Housing onstruction ant Selection l ation SX-NRPB-333295-CS-INDV / Institutional Support for Rec Individual Consult Open - Internationa Under Implement TF / B5199 Post 45,000.00 0.00 2022-12-23 2023-01-12 2023-02-10 2023-03-03 2023-04-07 2024-04-06 Financial Management Assist onstruction ant Selection l ation ant SX-NRPB-260433-CS-INDV / Institutional Support for Rec Individual Consult TF / A8079 Post Open 25,000.00 0.00 Canceled 2021-10-29 2021-12-17 2022-01-07 2022-02-11 2022-08-10 Sector Expert - Housing onstruction ant Selection SX-NRPB-342557-CS-INDV / Institutional Support for Rec Individual Consult Open - Internationa Under Implement TF / B5199 Post 110,000.00 0.00 2023-02-17 2023-02-27 2023-04-07 2023-04-28 2023-06-02 2024-06-01 Project Officer ERP-1 onstruction ant Selection l ation SX-NRPB-342572-CS-INDV / Institutional Support for Rec Individual Consult Open - Internationa TF / B5199 Post 100,000.00 0.00 Canceled 2023-02-17 2023-02-27 2023-04-07 2023-04-28 2023-06-02 2024-06-01 Senior Advisor -Housing Proje onstruction ant Selection l ct SX-NRPB-347124-CS-INDV / Institutional Support for Rec Individual Consult Direct - Internation Under Implement TF / B5199 Post 221,000.00 0.00 2023-03-05 2023-03-20 2023-03-15 2023-05-19 2023-04-05 2023-04-12 2023-05-10 2024-09-14 Coordinating Environmental onstruction ant Selection al ation Specialist SX-NRPB-347131-CS-INDV / Institutional Support for Rec Individual Consult Open - Internationa Under Implement TF / B5199 Post 245,000.00 0.00 2023-03-05 2023-03-20 2023-04-23 2023-05-14 2023-06-18 2024-10-31 Social Specialist onstruction ant Selection l ation SX-NRPB-353790-CS-INDV / Institutional Support for Rec Individual Consult Under Implement TF / B5199 Post Direct - National 65,000.00 0.00 2023-04-05 2023-04-26 2023-04-15 2023-05-16 2023-05-06 2023-05-16 2023-06-10 2024-06-09 Executive Assistant Consulta onstruction ant Selection ation nt SX-NRPB-326436-CS-INDV / Institutional Support for Rec Individual Consult Direct - Internation Under Implement TF / B5199 Post 165,000.00 0.00 2022-11-15 2023-05-23 2022-11-25 2022-12-16 2023-06-01 2024-12-31 Engineer ERP-1 - K.W onstruction ant Selection al ation SX-NRPB-363223-CS-INDV / Institutional Support for Rec Individual Consult TF / B5199 Post Direct - National 15,000.00 0.00 Under Review 2023-05-28 2023-05-23 2023-06-07 2023-06-28 2023-08-02 2023-10-02 Energy Specialist onstruction ant Selection SX-NRPB-364424-CS-INDV / Institutional Support for Rec Individual Consult Open - Internationa Under Implement TF / B5199 Post 100,000.00 0.00 2023-06-09 2023-05-31 2023-07-28 2023-08-18 2023-09-22 2024-09-21 Housing Sector Expert onstruction ant Selection l ation SX-NRPB-364743-CS-INDV / Institutional Support for Rec Individual Consult TF / B5199 Prior Direct - National 242,510.00 0.00 Signed 2023-06-01 2023-06-01 2023-06-11 2023-06-02 2023-07-02 2023-06-02 2023-08-06 2024-08-05 Procurement Consultant Ms. J onstruction ant Selection ackson II SX-NRPB-364744-CS-CDS / F Institutional Support for Rec Under Implement acilitator Performance Agree TF / B5199 Post Direct Selection Direct - National 60,000.00 0.00 2023-06-09 2023-06-22 2023-06-19 2023-06-19 2023-08-23 2024-05-22 onstruction ation ment Housing SX-NRPB-368036-CS-INDV / Institutional Support for Rec Individual Consult Direct - Internation Under Implement TF / B5199 Prior 153,900.00 0.00 2023-06-25 2023-06-22 2023-07-05 2023-06-13 2023-07-26 2023-06-26 2023-08-30 2024-08-29 Procurement Consultant Mr. onstruction ant Selection al ation Maculotti II Page 7 Summarized Procurement Plan I. GENERAL Project information: Borrower: CCARDESA Project Name: Agricultural Productivity Program for Southern Africa Project ID No: P164486 Grant No.: Project Implementing Agency: CCARDESA Bank’s approval Date of the Procurement Plan: February 13, 2019 Date of General Procurement Notice: Period covered by this procurement plan: February 13, 2019 to September 2020 II. Goods and Works and Non-Consulting Services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by IDA as stated in Appendix 1 to the Guidelines for Procurement: Thresholds for Procurement Methods and Prior Review Goods, Works and Non- Consulting Services Procurement Approaches and Methods (US$ Prior millions) Review Category Open Open Request for (US$ millions) International National Quotation (RfQ) Works ≥ 15 ≥7 < 0.2 ≤ 0.2 Goods, IT, and non- ≥6 ≥1 < 0.1 ≤ 0.1 consulting services 2. Reference to (if any) Project Operational/Procurement Manual: The Procurement Plan also forms part of the Project Implementation Manual approved on May 2019. 1 3. Procurement Packages with Methods and Time Schedule Procurement of Goods & Non-consulting Services Summary 1 2 3 4 5 6 7 Ref. Description Estimated Packages Domestic Review Comments No. Cost Preference by Bank US$ million (yes/no) (Prior / Post) Summary of the ICB NIL NIL NIL NIL NIL (Works) Summary of the NCB NIL NIL NIL NIL NIL (Works) Summary of the ICB NIL NIL No NIL No major goods (Goods) Summary of the NCB NIL NIL NIL NIL NIL (Goods) Summary of the RfQ 0.03 6 No Post Request for (Goods & Non- Quotations Consulting Services) Summary of the DC 0.2million 2 No Post (Non-consulting services) III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines: Selection and Employment of Consultants: Thresholds for Consultants Selection Methods and Prior Review Thresholds for Consultants Selection Methods and Prior Review for Consulting Services Category Prior Short List of National Consultants (US$ million) 2 Review Consulting Engineering and (US$ Services Construction Supervision millions) Consultants (Firms) ≥4 ≤ 0.3 ≤ 0.3 Individual Consultants ≥ 0.5 NA. NA. 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $ 300,000 equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Guidelines: Selection and Employment of Consultants. 3. Terms of Reference (TOR) for all consultancy contracts as well as all single source selections, irrespective of the contract value, will be subject to prior review. 4. Any Other Special Selection Arrangements: N/A 5. Consultancy Assignments with Selection Methods and Time Procurement of Consulting Services Summary 1 2 3 4 5 6 Ref. No. Description of Estimated Package Review Comments Assignment Cost s by Bank (Prior / US$ million Post) Summary of NIL NIL NIL NIL contracts through CQS 3 Summary of 0.2 million 26 Post Individual Consultants (mostly contracts through peer reviewers) IC 4 PROCUREMENT Eastern and Southern Africa : Agricultural Productivity Program for Southern Africa - Angola & Lesotho PLAN General Information Country: Eastern and Southern Africa 2020-08-27 Bank’s Approval Date of the Original Procurement Plan: 2023-06-02 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P164486 GPN Date: Project Name: Agricultural Productivity Program for Southern Africa - Angola & Lesotho Loan / Credit No: IBRD / 89170 Agronomic Research Institute Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Request for Bids - AO-IIA-188294-CW-RFP / Ref Strengthening the Institution Single Stage - One E Small Works SPD 2023-11-0 urbishment of the PIU Office IBRD / 89170 al and Enabling Environment Post Request for Bids Open - National 200,000.00 0.00 Canceled 2023-01-17 2023-01-22 2023-03-05 2023-04-04 2023-05-09 nvelope (1 envelope proce 5 and three premises in Chiang for Technology Adoption ss) a - Huambo Request for Bids - APPSA/W-001 / Construction Strengthening the Institution Open - Internationa Single Stage - One E Works (without pr Under Imple 2023-11-2 Works of the Cassava Region IBRD / 89170 al and Enabling Environment Post Request for Bids 5,000,000.00 0.00 2023-03-10 2023-04-19 2023-03-15 2023-04-25 2023-04-26 2023-04-27 2023-06-01 l nvelope equalification) SP mentation 8 al Leadership Center in Mala for Technology Adoption D nje. APPSA/W-002 / Fencing at th Strengthening the Institution Request for Quota Single Stage - One E Other (with field f Under Imple 2023-10-1 e Agricultural Experimental S IBRD / 89170 al and Enabling Environment Post Limited 100,000.00 0.00 2023-02-25 2023-05-30 2023-04-22 tions nvelope or explanation) mentation 9 tations of Malanje for Technology Adoption APPSA/W-003 / Fencing at th Strengthening the Institution Request for Quota Single Stage - One E Other (with field f Under Imple 2023-10-2 e Agricultural Experimental S IBRD / 89170 al and Enabling Environment Post Limited 70,000.00 0.00 2023-03-04 2023-05-30 2023-04-29 tions nvelope or explanation) mentation 6 tations of Chianga (Huambo) for Technology Adoption APPSA/W-005 / Fencing at th Strengthening the Institution Request for Quota Single Stage - One E Other (with field f Under Imple 2023-10-2 e Agricultural Experimental S IBRD / 89170 al and Enabling Environment Post Limited 70,000.00 0.00 2023-03-01 2023-05-30 2023-04-26 tions nvelope or explanation) mentation 3 tations of Namibe for Technology Adoption Request for Bids - APPSA/W-006 / Rehabilitatio Strengthening the Institution Single Stage - One E Small Works SPD Under Imple 2023-12-1 n of the Malanje Agricultural IBRD / 89170 al and Enabling Environment Post Request for Bids Open - National 200,000.00 0.00 2023-02-28 2023-04-24 2023-03-05 2023-05-03 2023-04-16 2023-05-16 2023-06-20 nvelope (1 envelope proce mentation 7 Experimental Station for Technology Adoption ss) APPSA/W-008 / Construction Strengthening the Institution Request for Quota Single Stage - One E Other (with field f Pending Imp 2023-10-3 of a Warehouse at the Tomb IBRD / 89170 al and Enabling Environment Post Limited 15,000.00 0.00 2023-03-08 2023-05-03 tions nvelope or explanation) lementation 0 oco Agricultural Experimental for Technology Adoption Field (Zaire) APPSA/W-010 / Rehabilitatio Request for Bids - Strengthening the Institution n of three (3) Buildings of the Single Stage - One E Small Works SPD Under Imple 2023-12-2 IBRD / 89170 al and Enabling Environment Post Request for Bids Open - National 400,000.00 0.00 2023-03-06 2023-04-25 2023-03-11 2023-05-03 2023-04-22 2023-05-22 2023-06-26 Chianga (Huambo) and Buildi nvelope (1 envelope proce mentation 3 for Technology Adoption ng in Largo Cussy ss) APPSA/W-004 / Fencing at th Strengthening the Institution Request for Quota Single Stage - One E Other (with field f Under Imple 2023-12-2 e Agricultural Experimental S IBRD / 89170 al and Enabling Environment Post Limited 40,000.00 0.00 2023-05-01 2023-06-26 tions nvelope or explanation) mentation 3 tations of Mazozo (Luanda) for Technology Adoption APPSA/W-007 / Rehabilitatio Strengthening the Institution n of the Tissue Culture Labor Request for Quota Single Stage - One E Other (with field f Pending Imp 2023-12-2 IBRD / 89170 al and Enabling Environment Post Limited 50,000.00 0.00 2023-05-03 2023-06-28 atory at the Mazozo Agricultu tions nvelope or explanation) lementation 5 for Technology Adoption ral Experimental Station APPSA/W-009 / Construction Strengthening the Institution Request for Quota Single Stage - One E Other (with field f Pending Imp 2023-12-2 of a Warehouse at the Ceilun IBRD / 89170 al and Enabling Environment Post Limited 15,000.00 0.00 2023-05-05 2023-06-30 tions nvelope or explanation) lementation 7 ga Agricultural Experimental for Technology Adoption Field (Bié) GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual AO-IIA-188196-GO-RFQ / Offi Technology Generation and Request for Quota Single Stage - One E ce supplies for R&D projects IBRD / 89170 Post Limited 30,000.00 0.00 Canceled 2020-10-11 2020-12-06 2021-06-04 Dissemination tions nvelope and PIU office AO-IIA-193891-GO-RFQ / Pur Strengthening the Institution chase ot three vehicles stati Request for Quota Single Stage - One E IBRD / 89170 al and Enabling Environment Post Limited 120,000.00 174,219.91 Completed 2020-11-08 2021-02-19 2021-01-03 2021-04-01 2021-07-02 2021-10-30 on wagon 13 seats for Experi tions nvelope for Technology Adoption mental Fields of Luso, Ceilun ga and Zaire AO-IIA-193765-GO-RFB / Pur Strengthening the Institution Single Stage - One E chase of tractors and implem IBRD / 89170 al and Enabling Environment Post Request for Bids Open - National 400,000.00 0.00 Canceled 2021-01-10 2021-01-15 2021-02-26 2021-03-28 2021-05-02 2021-10-29 nvelope ents for Malanje and Huambo for Technology Adoption (Chianga) AO-IIA-188275-GO-RFQ / Thr Strengthening the Institution Request for Quota Single Stage - One E ee sets video conference equ IBRD / 89170 al and Enabling Environment Post Limited 30,000.00 0.00 Canceled 2020-11-08 2021-01-03 2021-07-02 tions nvelope ipment for Technology Adoption AO-IIA-221338-GO-RFQ / Veh Project management, monit Request for Quota Single Stage - One E icles to Support the monitori IBRD / 89170 oring and evaluation, and re Post Limited 200,000.00 281,067.85 Completed 2021-03-09 2021-06-11 2021-05-04 2021-10-01 2021-10-31 2022-02-26 tions nvelope ng Missions gional coordination Strengthening the Institution AO-IIA-187417-GO-RFB / Pur Single Stage - One E IBRD / 89170 al and Enabling Environment Post Request for Bids Open - National 880,000.00 0.00 Canceled 2020-09-21 2020-09-26 2020-11-07 2020-12-07 2021-01-11 2021-07-10 chase of vehicles nvelope for Technology Adoption Strengthening the Institution AO-IIA-188183-GO-RFQ / Pur Request for Quota Single Stage - One E IBRD / 89170 al and Enabling Environment Post Limited 15,000.00 0.00 Canceled 2021-05-09 2021-07-04 2021-12-31 chase of 10 motorbikes tions nvelope for Technology Adoption Strengthening the Institution APPSA/G-013 / Procurement IBRD / 89170 al and Enabling Environment Post Direct Selection Direct 25,000.00 81,865.99 Signed 2022-01-10 2022-01-26 2022-01-15 2022-01-31 2022-02-19 2022-02-18 2022-08-18 of Motorbikes for Technology Adoption Strengthening the Institution APPSA/G-014 / Procurement IBRD / 89170 al and Enabling Environment Post Direct Selection Direct 500,000.00 535,515.88 Signed 2022-01-10 2021-12-10 2022-01-15 2022-02-07 2022-02-19 2022-03-15 2022-08-18 Tractors and Implements for Technology Adoption Page 1 APPSA/G-015 / Procurement Strengthening the Institution of Vehicles for PIU, IIA Resear IBRD / 89170 al and Enabling Environment Post Direct Selection Direct 750,000.00 804,217.70 Signed 2022-01-11 2022-01-05 2022-01-16 2022-02-07 2022-02-20 2022-03-05 2022-08-19 ch Programmes and Stations for Technology Adoption Project management, monit APPSA/G-016 / License Softw IBRD / 89170 oring and evaluation, and re Post Direct Selection Direct 30,000.00 16,459.31 Signed 2022-01-16 2022-01-26 2022-01-21 2022-01-26 2022-02-25 2022-02-01 2022-08-24 are Accounting TOMPRO gional coordination AO-IIA-188898-GO-RFQ / Aut Technology Generation and Request for Quota Single Stage - One E Under Imple omatic Weather Stations for IBRD / 89170 Post Limited 97,000.00 0.00 2021-01-17 2021-03-14 2021-09-10 Dissemination tions nvelope mentation Research and Field Stations APPSA/G-017 / IT Equipment Strengthening the Institution Single Stage - One E Under Imple for UIP and Subprojects Supp IBRD / 89170 al and Enabling Environment Post Request for Bids Open - National 300,000.00 0.00 2022-05-31 2022-05-26 2022-06-05 2022-05-27 2022-07-17 2022-07-08 2022-08-16 2022-09-20 2023-03-19 nvelope mentation ort for Technology Adoption AO-IIA-188210-GO-RFQ / Lab oratory supplies (essencial e Technology Generation and Request for Quota Single Stage - One E IBRD / 89170 Post Limited 70,000.00 0.00 Canceled 2021-01-15 2021-03-12 2021-09-08 quipment, reagens and other Dissemination tions nvelope lab consumables) APPSA/G-021 / Procurement Strengthening the Institution Single Stage - One E of 6 Vehicles to Intensify the IBRD / 89170 al and Enabling Environment Post Request for Bids Open - National 500,000.00 0.00 Signed 2022-06-26 2022-07-18 2022-07-01 2022-07-27 2022-08-12 2022-08-31 2022-09-11 2022-09-05 2022-10-16 2023-04-14 nvelope Activities of the Research Su for Technology Adoption b-projects Fields APPSA/G-022 / Procurement Strengthening the Institution Request for Quota Single Stage - One E of 15 Motorbikes and Access IBRD / 89170 al and Enabling Environment Post Open - National 150,000.00 0.00 Signed 2022-07-19 2022-06-23 2022-09-13 2023-03-12 tions nvelope ories for Technology Adoption Strengthening the Institution APPSA/G-025 / Procurement Request for Quota Single Stage - One E IBRD / 89170 al and Enabling Environment Post Limited 80,000.00 0.00 Signed 2022-08-01 2022-08-25 2022-09-26 2023-03-25 1 Vehicle for Supporting UIP tions nvelope for Technology Adoption Strengthening the Institution APPSA/G-023 / Procurement Request for Quota Single Stage - One E IBRD / 89170 al and Enabling Environment Post Open - National 150,000.00 0.00 Signed 2022-09-10 2022-10-13 2023-04-11 of 3 Tractors tions nvelope for Technology Adoption AO-IIA-187401-GO-RFQ / Pur Technology Generation and Single Stage - One E IBRD / 89170 Post Request for Bids Open - National 120,000.00 0.00 Canceled 2021-01-18 2021-01-23 2021-03-06 2021-04-05 2021-05-10 2021-11-06 chase of IT equipments for R Dissemination nvelope &D Projects APPSA/G-032 / Procurement Technology Generation and Request for Quota Open - Internationa Single Stage - One E Under Imple IBRD / 89170 Post 100,000.00 0.00 2022-12-10 2023-04-01 2023-02-04 2023-08-03 of Laboratorial Reagents Dissemination tions l nvelope mentation Strengthening the Institution APPSA/G-018 / Procurement Single Stage - One E Under Imple IBRD / 89170 al and Enabling Environment Post Request for Bids Open - National 250,000.00 0.00 2023-01-15 2023-03-20 2023-01-20 2023-04-07 2023-03-03 2023-04-02 2023-05-07 2023-11-03 of Tractors and Implements I nvelope mentation for Technology Adoption APPSA/G-034 / Procurement Strengthening the Institution Request for Quota Single Stage - One E of Reagents, Equipment and IBRD / 89170 al and Enabling Environment Post Limited 120,000.00 0.00 Canceled 2022-11-05 2022-12-15 2023-06-13 tions nvelope other Laboratorial Consumab for Technology Adoption les I APPSA/G-033 / Procurement Strengthening the Institution Request for Quota Single Stage - One E Pending Impl of Irrigation System for Agric IBRD / 89170 al and Enabling Environment Post Limited 120,000.00 0.00 2023-01-22 2023-03-03 2023-08-30 tions nvelope ementation ultural Experimental Stations for Technology Adoption I APPSA/G-020 / Procurement Technology Generation and Request for Quota Open - Internationa Single Stage - One E Under Imple of Laboratory Equipment and IBRD / 89170 Post 150,000.00 0.00 2023-03-05 2023-04-01 2023-04-30 2023-10-27 Dissemination tions l nvelope mentation Consumables APPSA/G-26 / Lightning prot Strengthening the Institution ection equipment for UIP offi Request for Quota Single Stage - One E IBRD / 89170 al and Enabling Environment Post Limited 80,000.00 0.00 Canceled 2023-01-02 2023-02-27 2023-08-26 ces and Chianga Agricultural tions nvelope for Technology Adoption Experiment Station - Huambo APPSA/G-019 / Procurement Strengthening the Institution Request for Quota Single Stage - One E Pending Impl of 10 Freezers for the Conser IBRD / 89170 al and Enabling Environment Post Open - National 100,000.00 0.00 2023-08-05 2023-09-30 2024-03-28 tions nvelope ementation vation of Genetic Agricultural for Technology Adoption Material AO-IIA-193893-GO-RFQ / Pro Strengthening the Institution Single Stage - One E Pending Impl curement of Irrigation Syste IBRD / 89170 al and Enabling Environment Post Request for Bids Open - National 260,000.00 0.00 2023-06-30 2023-07-05 2023-08-16 2023-09-15 2023-10-20 2024-04-17 nvelope ementation m for Agricultural Experimen for Technology Adoption tal Stations AO-IIA-187641-GO-RFB / Pro Strengthening the Institution curement of Equipment and Single Stage - One E Pending Impl IBRD / 89170 al and Enabling Environment Post Request for Bids Open - National 400,000.00 0.00 2023-06-30 2023-07-05 2023-08-16 2023-09-15 2023-10-20 2024-04-17 Furniture for the Cassava Re nvelope ementation for Technology Adoption gional Leadership Center APPSA/G-027 / Procurement of 2 Refrigeration Chambers f Strengthening the Institution Request for Quota Single Stage - One E Pending Impl or Legume Seeds for the Agri IBRD / 89170 al and Enabling Environment Post Limited 110,000.00 0.00 2023-07-05 2023-08-30 2024-02-26 tions nvelope ementation cultural Experimental Station for Technology Adoption s of Mazozo and Chianga APPSA/G-043 / Procurement Technology Generation and Request for Quota Single Stage - One E Pending Impl IBRD / 89170 Post Limited 100,000.00 0.00 2023-07-01 2023-08-26 2024-02-22 of Fertilizer for Agricultural C Dissemination tions nvelope ementation ampaign APPSA/G-042 / Automatic W Technology Generation and Request for Quota Single Stage - One E Pending Impl IBRD / 89170 Post Limited 120,000.00 0.00 2023-07-04 2023-08-29 2024-02-25 eather Stations Dissemination tions nvelope ementation APPSA/G-045 / Procurement Technology Generation and Direct - Internation Under Imple 4 vehicles for High-Level Inte IBRD / 89170 Post Direct Selection 200,000.00 0.00 2023-06-29 2023-06-28 2023-07-04 2023-08-08 2024-02-04 Dissemination al mentation r-Ministerial missions to verif y Project Actions APPSA/G-044 / Procurement of 17 Generators for the Cass Technology Generation and Direct - Internation Pending Impl IBRD / 89170 Post Direct Selection 220,000.00 0.00 2023-06-29 2023-07-04 2023-08-08 2024-02-04 ava Regional Leadership Cen Dissemination al ementation ter and Agricultural Experime ntal Stations APPSA/G-041 / Procurement Technology Generation and Request for Quota Single Stage - One E Pending Impl of Solar Energy Equipment fo IBRD / 89170 Post Limited 115,000.00 0.00 2023-07-04 2023-08-29 2024-02-25 Dissemination tions nvelope ementation r Subproject NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 2 APPSA/S-002 / Repair Servic Strengthening the Institution Single Stage - One E es and Supply of Parts of Tra IBRD / 89170 al and Enabling Environment Post Request for Bids Open - National 300,000.00 0.00 Canceled 2022-06-30 2022-07-05 2022-08-16 2022-09-15 2022-10-20 2023-04-18 nvelope ctors for Experimental Agricu for Technology Adoption ltural Stations APPSA/S-003 / Website Desi Strengthening the Institution Request for Quota Single Stage - One E Pending Impl gn, Development and Manag IBRD / 89170 al and Enabling Environment Post Open - National 20,000.00 0.00 2022-12-27 2023-02-21 2023-08-20 tions nvelope ementation ement Services for the IIA an for Technology Adoption d APPSA APPSA/S-001 / Repair Servic Strengthening the Institution e and Supply of Parts for IIA IBRD / 89170 al and Enabling Environment Post Direct Selection Direct 300,000.00 0.00 Canceled 2022-05-26 2022-05-27 2022-05-31 2022-07-05 2023-01-01 Vehicles Within the scope of for Technology Adoption APPSA CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual AO-IIA-259173-CS-QCBS / Pr Strengthening the Institution oject Design and Supervision Quality And Cost- Open - Internationa IBRD / 89170 al and Enabling Environment Post 540,000.00 0.00 Signed 2021-10-29 2022-01-21 2021-11-19 2022-04-18 2022-01-02 2022-06-13 2022-01-30 2022-07-22 2022-03-01 2022-06-29 2022-04-05 2022-08-16 2022-05-10 2023-05-10 of the Supervision of the Cas Based Selection l for Technology Adoption sava Regional Leadership Ce nter AO-IIA-267731-CS-QCBS / As Project management, monit Quality And Cost- sessment the Agriculture Res IBRD / 89170 oring and evaluation, and re Post Open - National 180,000.00 99,929.00 Signed 2021-12-19 2022-01-10 2022-01-09 2022-01-20 2022-02-22 2022-04-14 2022-03-22 2022-05-30 2022-04-21 2022-06-03 2022-05-26 2022-06-06 2022-06-30 2022-07-31 2023-06-30 Based Selection earch Baseline gional coordination Project management, monit APPSA/C-028 / External Audi Least Cost Selecti Open - Internationa Under Implement IBRD / 89170 oring and evaluation, and re Post 200,000.00 0.00 2022-01-13 2022-02-02 2022-02-03 2022-03-04 2022-03-19 2022-07-15 2022-04-16 2022-08-31 2022-05-16 2022-06-20 2022-07-25 2023-01-21 t on l ation gional coordination AO-IIA-188277-CS-INDV / Ra pid rual survey for assement of conditions to stregthen the Technology Generation and Consultant Qualifi the basic seed and vegetativ IBRD / 89170 Post Limited 60,000.00 0.00 Canceled 2022-09-01 2022-09-15 2022-10-15 2022-11-19 2023-05-18 Dissemination cation Selection e propagation materials fram ework under coordination of Chianga Research Station in the Central Plateau of Angola APPSA/C-023 / Consultancy f or the Development of Enviro Strengthening the Institution Consultant Qualifi nmental Impact Studies for t IBRD / 89170 al and Enabling Environment Post Open - National 100,000.00 0.00 Canceled 2022-06-20 2022-06-16 2022-07-11 2022-08-04 2022-09-03 2022-10-08 2023-04-06 cation Selection he Construction Work of the for Technology Adoption Cassava Regional Leadership Center - Malanje INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual AO-IIA-187655-CS-INDV / Re Project management, monit Individual Consult cruitment of Procurement Sp IBRD / 89170 oring and evaluation, and re Prior Open 84,000.00 0.00 Canceled 2020-09-01 2021-01-15 2020-10-20 2021-07-16 2020-11-10 2020-12-15 2021-06-13 ant Selection ecialist gional coordination AO-IIA-187660-CS-INDV / Re Project management, monit Individual Consult cruitment of safeguards spec IBRD / 89170 oring and evaluation, and re Post Open 72,000.00 0.00 Canceled 2020-09-01 2020-10-09 2020-10-20 2021-07-01 2020-11-10 2021-07-09 2020-12-15 2021-06-13 ant Selection ialist gional coordination AO-IIA-187659-CS-INDV / Re Project management, monit Individual Consult cruitment of communication IBRD / 89170 oring and evaluation, and re Post Open 72,000.00 86,205.35 Signed 2020-09-01 2021-02-12 2020-10-20 2021-09-30 2020-11-10 2021-10-01 2020-12-15 2021-10-19 2021-06-13 ant Selection and information specialst gional coordination AO-IIA-187657-CS-INDV / Re Project management, monit Individual Consult cruitment of monitoring and IBRD / 89170 oring and evaluation, and re Post Open 84,000.00 111,873.80 Signed 2020-09-01 2020-10-09 2020-10-20 2021-04-28 2020-11-10 2021-05-24 2020-12-15 2021-06-08 2021-06-13 ant Selection evaluation specialist gional coordination AO-IIA-187647-CS-INDV / Re Project management, monit Individual Consult cruitment of the project coor IBRD / 89170 oring and evaluation, and re Post Open 96,000.00 0.00 Canceled 2020-09-01 2020-09-17 2020-10-20 2020-11-10 2020-12-15 2021-06-13 ant Selection dinator gional coordination Project management, monit AO-IIA-221339-CS-INDV / So Individual Consult IBRD / 89170 oring and evaluation, and re Post Open 72,500.00 97,039.57 Signed 2021-03-10 2021-09-21 2021-04-28 2021-11-08 2021-05-19 2021-11-09 2021-06-23 2021-11-11 2021-12-20 cial Safeguards Specialist ant Selection gional coordination Project management, monit AO-IIA-187662-CS-INDV / Re Individual Consult IBRD / 89170 oring and evaluation, and re Post Open 36,000.00 0.00 Canceled 2020-09-01 2020-10-09 2020-10-20 2020-11-10 2020-12-15 2021-06-13 cruitment of an accountant ant Selection gional coordination AO-IIA-187652-CS-INDV / Re Project management, monit Individual Consult cruitment of financial manag IBRD / 89170 oring and evaluation, and re Post Open 84,000.00 0.00 Canceled 2020-09-01 2020-10-09 2020-10-20 2020-11-10 2020-12-15 2021-06-13 ant Selection er gional coordination AO-IIA-239079-CS-INDV / Fin Project management, monit Individual Consult ancial Management Specialis IBRD / 89170 oring and evaluation, and re Post Open 140,000.00 150,376.47 Signed 2021-07-22 2021-07-27 2021-09-09 2021-09-27 2021-09-30 2021-09-29 2021-11-04 2021-10-09 2022-05-03 ant Selection t gional coordination Project management, monit AO-IIA-239084-CS-INDV / Ac Individual Consult IBRD / 89170 oring and evaluation, and re Post Open 72,000.00 64,954.01 Signed 2021-07-22 2021-07-27 2021-09-09 2021-10-14 2021-09-30 2021-10-20 2021-11-04 2021-10-26 2022-05-03 countant ant Selection gional coordination Project management, monit AO-IIA-252339-CS-INDV / IT Individual Consult IBRD / 89170 oring and evaluation, and re Post Open 45,000.00 33,285.56 Signed 2021-09-13 2021-10-05 2021-11-01 2022-02-08 2021-11-22 2022-03-24 2021-12-27 2022-04-27 2022-06-25 Specialist ant Selection gional coordination Project management, monit AO-IIA-252343-CS-INDV / Infr Individual Consult IBRD / 89170 oring and evaluation, and re Post Limited 74,000.00 34,485.56 Signed 2021-09-13 2021-10-21 2021-09-18 2022-01-14 2021-10-09 2022-03-24 2021-11-13 2022-04-27 2022-05-12 astructure Specialist ant Selection gional coordination AO-IIA-252344-CS-INDV / En Project management, monit Individual Consult vironmental Safeguards Spec IBRD / 89170 oring and evaluation, and re Post Open 74,000.00 98,039.57 Signed 2021-09-13 2021-09-29 2021-11-01 2021-07-01 2021-11-22 2021-10-19 2021-12-27 2021-10-21 2022-06-25 ant Selection ialist gional coordination AO-IIA-244838-CS-INDV / Fin Project management, monit Individual Consult ancial Management Consulta IBRD / 89170 oring and evaluation, and re Post Direct 60,000.00 0.00 Canceled 2021-07-23 2021-07-22 2021-08-02 2021-08-03 2021-08-23 2021-09-27 2022-03-26 ant Selection nt gional coordination Page 3 AO-IIA-252345-CS-INDV / Co nsultancy for Water Resource Strengthening the Institution Individual Consult s Assessment, Irrigation Cap IBRD / 89170 al and Enabling Environment Post Limited 60,000.00 0.00 Canceled 2021-09-27 2021-10-05 2021-10-02 2022-03-24 2021-10-23 2021-11-27 2022-05-26 ant Selection acity Review and Water Man for Technology Adoption agement Systems Proposals Project management, monit AO-IIA-254446-CS-INDV / Pro Individual Consult IBRD / 89170 oring and evaluation, and re Prior Open 176,000.00 156,793.58 Signed 2021-09-23 2021-10-12 2021-11-11 2021-12-02 2021-12-02 2021-12-08 2022-01-06 2021-12-20 2022-07-05 curement Specialist ant Selection gional coordination AO-IIA-218571-CS-INDV / Stu Strengthening the Institution Individual Consult dies on small scale irrigation IBRD / 89170 al and Enabling Environment Post Open 30,000.00 0.00 Canceled 2022-03-14 2022-05-02 2022-05-23 2022-06-27 2022-12-24 ant Selection schemes in Central Plateau o for Technology Adoption f Angola AO-IIA-188476-CS-INDV / Re Strengthening the Institution cruitment of a consultant for Individual Consult IBRD / 89170 al and Enabling Environment Post Limited 20,000.00 0.00 Canceled 2020-11-02 2020-11-06 2020-11-27 2021-01-01 2021-06-30 budget preparation and supe ant Selection for Technology Adoption rvision of rehabilitation works in Chianga RS Project management, monit AO-IIA-221336-CS-INDV / Pro Individual Consult IBRD / 89170 oring and evaluation, and re Post Open 100,000.00 0.00 Canceled 2022-03-31 2022-05-19 2022-06-09 2022-07-14 2023-01-10 ject Manager ant Selection gional coordination Project management, monit APPSA/C-029 / Procurement Individual Consult Under Implement IBRD / 89170 oring and evaluation, and re Prior Open 72,000.00 0.00 2022-01-14 2022-02-24 2022-03-04 2022-03-25 2022-04-29 2022-10-26 Assistant ant Selection ation gional coordination Project management, monit APPSA/C-030 / Financial Assi Individual Consult IBRD / 89170 oring and evaluation, and re Post Open 72,000.00 0.00 Signed 2022-01-14 2022-02-02 2022-03-04 2022-07-25 2022-03-25 2022-09-20 2022-04-29 2022-10-26 stant ant Selection gional coordination AO-IIA-193690-CS-INDV / Ass Strengthening the Institution Individual Consult essment the agriculture rese IBRD / 89170 al and Enabling Environment Post Open 50,000.00 0.00 Canceled 2020-11-03 2021-07-12 2020-12-22 2021-01-12 2021-02-16 2021-08-15 ant Selection ardh baseline for Technology Adoption AO-IIA-188286-CS-INDV / Ass Strengthening the Institution Individual Consult ess and design the IIA resear IBRD / 89170 al and Enabling Environment Post Open 45,000.00 0.00 Canceled 2022-06-30 2022-08-18 2022-09-08 2022-10-13 2023-04-11 ant Selection ch network investment for Technology Adoption APPSA/C-032 / Consultant fo Project management, monit Individual Consult Under Implement r Supporting the Installation, IBRD / 89170 oring and evaluation, and re Post Open 80,000.00 0.00 2022-05-13 2022-05-16 2022-07-01 2023-01-20 2022-07-22 2022-08-26 2023-02-22 ant Selection ation Operation and, Management gional coordination of DHIS2 Project management, monit APPSA/C-022 / Monitoring an Individual Consult IBRD / 89170 oring and evaluation, and re Post Open 120,000.00 0.00 Signed 2022-06-13 2022-06-03 2022-08-01 2022-10-04 2022-08-22 2022-10-31 2022-09-26 2023-03-25 d Evaluation Specialist ant Selection gional coordination AO-IIA-188291-CS-INDV / Stu Strengthening the Institution Individual Consult dies on cassava value chain i IBRD / 89170 al and Enabling Environment Post Open 30,000.00 0.00 Canceled 2022-07-19 2022-09-06 2022-09-27 2022-11-01 2023-04-30 ant Selection n Angola for Technology Adoption Project management, monit AO-IIA-221337-CS-INDV / Ca Individual Consult IBRD / 89170 oring and evaluation, and re Post Open 80,000.00 0.00 Canceled 2022-05-31 2022-07-19 2022-08-09 2022-09-13 2023-03-12 ssava Consultant Specialist ant Selection gional coordination Project management, monit APPSA/C-025 / Procurement Individual Consult Under Implement IBRD / 89170 oring and evaluation, and re Prior Open - National 30,000.00 0.00 2022-11-03 2023-02-06 2022-12-22 2023-01-12 2023-02-16 2023-08-15 Assistant ant Selection ation gional coordination Project management, monit APPSA/IC-20 / Financial Man Individual Consult Under Implement IBRD / 89170 oring and evaluation, and re Post Open - National 140,000.00 0.00 2023-05-02 2023-05-02 2023-06-20 2023-07-11 2023-08-15 2024-02-11 agement Specialist I ant Selection ation gional coordination Project management, monit Individual Consult APPSA/C-027 / Internal Audit IBRD / 89170 oring and evaluation, and re Post Open 70,000.00 0.00 Canceled 2022-01-12 2022-04-19 2022-03-02 2022-03-23 2022-04-27 2022-10-24 ant Selection gional coordination Page 4 PROCUREMENT PLAN (Textual Part) Project information: Nigeria [SPESSE ][P169405] Project Implementation agency: National University Commission Date of the Procurement Plan: August 9, 2019 Period covered by this Procurement Plan: [August 9, 2019 – Jan 31, 2019] Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in Nigeria 2017 Procurement Act, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. None When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Not Applicable Goods: is not applicable Works: is not applicable Other Relevant Procurement Information. None PROCUREMENT Nigeria : Sustainable Procurement, Environmental and Social Standards Enhancement Project (SPESSE) PLAN General Information Country: Nigeria 2020-05-15 Bank’s Approval Date of the Original Procurement Plan: 2023-06-01 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P169405 GPN Date: Project Name: Sustainable Procurement, Environmental and Social Standards Enhancement Project (SPESSE) Loan / Credit No: IDA / V2820 Federal Ministries of Women Affairs, Labour, Works and Housing Node Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned NG-FMWA LAB &WORKS-163 Component I: Technical assi Request for Quota Single Stage - One E 2020-05-1 934-CW-RFQ / Partitioning of IDA / V2820 stance and Support to imple Post Limited 10,000.00 0.00 Canceled 2020-03-15 2020-04-21 tions nvelope 2 Offices menting agencies NG-FMWA LAB &WORKS-239 Component I: Technical assi Request for Quota Request for Quota Single Stage - One E 2022-05-1 731-CW-RFQ / Maintenance o IDA / V2820 stance and Support to imple Post Limited tions (Non Bank-S 16,000.00 0.00 Canceled 2021-09-20 2021-11-15 tions nvelope 4 f office building. menting agencies PD) NG-FMWA LAB &WORKS-163 Component I: Technical assi Request for Quota Request for Quota Single Stage - One E 2022-03-0 934-CW-RFQ-2 / Partitioning IDA / V2820 stance and Support to imple Post Limited tions (Non Bank-S 10,000.00 9,779.38 Completed 2022-01-09 2022-01-06 2022-02-15 2022-02-11 tions nvelope 8 of Offices menting agencies PD) GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NG-FMWA LAB &WORKS-163 Component I: Technical assi Request for Quota Single Stage - One E 880-GO-RFQ / Procurement o IDA / V2820 stance and Support to imple Post Limited 25,000.00 24,088.82 Completed 2021-08-15 2021-12-15 2021-09-21 2022-01-29 2021-10-05 2022-03-03 tions nvelope f Office Furniture menting agencies NG-FMWA LAB &WORKS-239 Component I: Technical assi Request for Quota Single Stage - One E Pending Impl 639-GO-RFQ / Printing of Fina IDA / V2820 stance and Support to imple Post Limited 1,223.03 0.00 2021-08-30 2021-10-25 2022-04-23 tions nvelope ementation ncial documents menting agencies NG-FMWA LAB &WORKS-163 Component I: Technical assi Request for Quota Single Stage - One E 897-GO-RFQ / Procurement o IDA / V2820 stance and Support to imple Post Limited 8,450.00 8,278.82 Completed 2021-08-15 2021-12-15 2021-09-21 2022-02-09 2021-10-05 2022-04-14 tions nvelope f Inverters menting agencies NG-FMWA LAB &WORKS-163 Component I: Technical assi Request for Quota Single Stage - One E 898-GO-RFQ / Procurement o IDA / V2820 stance and Support to imple Post Limited 87,611.85 84,922.44 Signed 2021-08-15 2021-12-15 2021-09-21 2022-02-11 2021-10-12 tions nvelope f Project Vehicle, Registration menting agencies and Insurance NG-FMWA LAB &WORKS-163 Component I: Technical assi Request for Quota Single Stage - One E 935-GO-RFQ / Procurement o IDA / V2820 stance and Support to imple Post Limited 9,750.00 9,051.27 Completed 2021-08-15 2021-12-15 2021-09-21 2022-02-09 2021-10-12 2022-04-14 tions nvelope f Window Blinds & Internal D menting agencies ecorations NG-FMWA LAB &WORKS-163 Component I: Technical assi Request for Quota Single Stage - One E Pending Impl 895-GO-RFQ / NgREN Subscri IDA / V2820 stance and Support to imple Post Limited 120,000.00 0.00 2021-08-14 2021-09-20 2021-10-04 tions nvelope ementation ption and Equipment menting agencies NG-FMWA LAB &WORKS-163 Component I: Technical assi Request for Quota Single Stage - One E 886-GO-RFQ / Procurement o IDA / V2820 stance and Support to imple Post Limited 29,078.95 28,264.58 Completed 2021-08-20 2021-12-15 2021-09-26 2022-02-07 2021-10-10 2022-03-23 tions nvelope f Computers and Printers menting agencies NG-FMWA LAB &WORKS-164 Component I: Technical assi 007-GO-RFQ / Procurement o Request for Quota Single Stage - One E Under Imple IDA / V2820 stance and Support to imple Post Limited 34,750.00 0.00 2021-08-18 2021-12-15 2021-10-13 2022-04-11 f Sound Proof Diesel Generat tions nvelope mentation menting agencies or and its maintenance NG-FMWA LAB &WORKS-163 Component I: Technical assi Request for Quota 896-GO-RFQ / Procurement o IDA / V2820 stance and Support to imple Post 15,000.00 0.00 Canceled 2020-03-10 2020-03-10 2020-03-10 tions f Video Conference Device menting agencies NG-FMWA LAB &WORKS-246 Component I: Technical assi Request for Quota Single Stage - One E 371-GO-RFQ / Procurement o IDA / V2820 stance and Support to imple Post Limited 29,157.34 26,459.41 Completed 2021-09-18 2021-12-15 2021-10-09 2022-01-27 2021-10-23 2022-02-26 tions nvelope f Office Equipment menting agencies NG-FMWA LAB &WORKS-239 Component I: Technical assi Request for Quota Single Stage - One E 636-GO-RFQ / Office Accomm IDA / V2820 stance and Support to imple Post Limited 43,421.04 0.00 Canceled 2021-09-18 2021-11-13 2022-05-12 tions nvelope odation Rent (3 Years). menting agencies NG-FMWA LAB &WORKS-163 Component I: Technical assi Request for Quota Single Stage - One E 896-GO-RFQ-2 / Procurement IDA / V2820 stance and Support to imple Post Limited 15,000.00 14,653.88 Completed 2022-01-09 2022-01-14 2022-03-06 2022-02-22 2022-09-02 2022-03-17 tions nvelope of Video Conference Device menting agencies NG-FMWA LAB &WORKS-163 Component I: Technical assi Under Imple 931-GO-DIR / Procurement of IDA / V2820 stance and Support to imple Post Direct Selection Direct 12,000.00 0.00 2022-03-07 2022-03-29 2022-03-12 2022-03-28 2022-04-18 mentation Accounting Software menting agencies NG-FMWA LAB &WORKS-361 Component I: Technical assi Request for Quota Single Stage - One E Pending Impl 426-GO-RFQ / Procurement o IDA / V2820 stance and Support to imple Post Limited 32,000.00 0.00 2023-05-20 2023-06-26 2023-07-10 tions nvelope ementation f Local Area Network (LAN) menting agencies NG-FMWA LAB &WORKS-361 Component I: Technical assi Request for Quota Single Stage - One E Pending Impl 427-GO-RFQ / Procurement o IDA / V2820 stance and Support to imple Post Limited 35,000.00 0.00 2023-05-20 2023-06-26 2023-07-10 tions nvelope ementation f I.T. Tools menting agencies NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NG-FMWA LAB &WORKS-163 Component I: Technical assi Request for Quota Single Stage - One E 916-NC-RFQ / Engagement of IDA / V2820 stance and Support to imple Post Limited 15,000.00 14,249.58 Signed 2021-08-14 2022-02-07 2021-09-20 2022-02-22 2022-09-19 tions nvelope Security Services firm menting agencies Page 1 NG-FMWA LAB &WORKS-163 Component I: Technical assi Request for Quota Single Stage - One E 928-NC-RFQ / Engagement of IDA / V2820 stance and Support to imple Post Limited 12,000.00 11,774.79 Signed 2021-08-17 2022-02-07 2021-09-23 2022-02-22 2022-09-22 tions nvelope Cleaning Services firm menting agencies CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NG-FMWA LAB &WORKS-281 956-CS-CQS / Engagement of Component I: Technical assi Consultant Qualifi Under Implement consultancy firm for the Dev IDA / V2820 stance and Support to imple Post Limited 100,000.00 0.00 2022-03-09 2023-02-22 2022-03-23 2022-04-22 2022-05-11 2022-11-07 cation Selection ation elopment of Professional pro menting agencies grammes for online certificati on NG-FMWA LAB &WORKS-281 933-CS-CQS / Engagement of Component I: Technical assi Consultant Qualifi consultancy firm to Develop IDA / V2820 stance and Support to imple Post Limited 80,000.00 0.00 Canceled 2022-03-09 2022-12-28 2022-03-23 2022-04-22 2022-05-11 2022-11-07 cation Selection Local Training content for S. menting agencies D., Labour & resettlement Se ctors in Nigeria NG-FMWA LAB &WORKS-344 247-CS-CQS / Engagement of Component I: Technical assi Consultant Qualifi consultancy firm to Develop IDA / V2820 stance and Support to imple Post Limited 80,000.00 0.00 Under Review 2023-02-27 2023-06-14 2023-03-13 2023-04-02 2023-04-21 2023-10-18 cation Selection Local Training content for S. menting agencies D., Labour & resettlement Se ctors in Nigeria NG-FMWA LAB &WORKS-364 465-CS-CQS / Engagement of Component I: Technical assi Consultant Qualifi Under Implement a consultancy firm for the De IDA / V2820 stance and Support to imple Post Limited 280,000.00 0.00 2023-05-31 2023-02-22 2023-06-14 2023-07-14 2023-08-02 2024-01-29 cation Selection ation velopment of Professional pr menting agencies ogrammes for the online cert ification portal INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NG-FMWA LAB &WORKS-239 Component I: Technical assi Individual Consult 728-CS-INDV / Engagement o IDA / V2820 stance and Support to imple Post Limited 15,789.47 0.00 Signed 2021-09-14 2023-02-22 2021-09-19 2023-02-23 2021-10-10 2023-03-13 2021-11-14 2022-05-13 ant Selection f an ICT/LMS Specialist menting agencies NG-FMWA LAB &WORKS-357 Component I: Technical assi Individual Consult Under Implement 708-CS-INDV / Engagement o IDA / V2820 stance and Support to imple Post Limited 52,182.99 0.00 2023-04-19 2023-02-22 2023-04-24 2023-05-15 2023-06-19 2023-12-16 ant Selection ation f an ICT/LMS Specialist menting agencies NG-FMWA LAB &WORKS-361 Component I: Technical assi Individual Consult Pending Impleme 424-CS-INDV / Engagement o IDA / V2820 stance and Support to imple Post Limited 50,000.00 0.00 2023-05-15 2023-05-20 2023-06-10 2023-07-15 2024-07-09 ant Selection ntation f Certification Manager menting agencies NG-FMWA LAB &WORKS-361 Component I: Technical assi Individual Consult Pending Impleme 425-CS-INDV / Engagement o IDA / V2820 stance and Support to imple Post Limited 7,500.00 0.00 2023-05-15 2023-05-20 2023-06-10 2023-07-15 2023-10-13 ant Selection ntation f Strategy Document Consult menting agencies ant. NG-FMWA LAB &WORKS-362 Component I: Technical assi Individual Consult Under Implement 050-CS-INDV / Engagement o IDA / V2820 stance and Support to imple Post Limited 12,000.00 0.00 2023-05-22 2023-05-17 2023-05-27 2023-06-17 2023-07-22 2024-01-18 ant Selection ation f External Auditor menting agencies Page 2 PROCUREMENT PLAN (Textual Part) Project information: SENEGAL, PAES – P178750 Project Implementation agency: UGP/PAES in DFHE/MESRI Date of the Procurement Plan: May 30, 2023 Period covered by this Procurement Plan: The 18th first month (from May 2023 to November 2024) Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the decree n°2022-2295 dated December, 2022, National Procurement Code (NPC), such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. Actual National Bidding Documents do not include provisions, as agreed with the Bank, intended to adequately mitigate against environmental, social (including sexual exploitation and abuse and gender-based violence), health and safety (“ESHS”) risks and impacts. The SBD are to be aligned with the new procurement code. The Bank shall discuss during the CPPR both with ARMP and Ministry of finance in order to lose case: 1) the mandatory request on “attestation existence de credit”. NPC for projects financed by IDA, since the contract is backed on a Financial Agreement; 2) Article 50 : Margin of domestic preference is not applicable in case of national competitive procurement; 3) Article 52 : the article 3 : Contracts awarded pursuant to financing agreements or treaties are subject to the provisions of this Decree, subject to the application of contrary provisions resulting from the procedures provided for by such international agreements or treaties. Hence In view of this article 3, the article 52 is not applicable for project financed by IDA. Article 50. This requirement needs to be considered in the PPSD, When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. Not Applicable”. Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables “Not Applicable”. Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: is not applicable for those contracts identified in the Procurement Plan tables.; Works: is not applicable for those contracts identified in the Procurement Plan tables. Other Relevant Procurement Information. None. Table 1. Prior review thresholds. Thresholds exam prior to procurement (US$ million) Procurement type High Risk Risk Low Risk Risk Substantial Moderate Civil works 5 10 15 20 Supplies , IT Equipment and 1.5 2 4 6 Services other than Consulting Services Consultants ( Firms ) 0.5 1 2 4 Consultants ( 0.2 0.3 0.4 0.5 Individuals ) Table 2: Thresholds for Procurement Approach and Methods Thresholds for Procurement Approach and Methods (US$ million) List group of Category Open Nation national Quotation Internation al consultants request al Open (Consulting Services) Works ≥ 15 < 15 ≤ 0.2 N/A Supplies , IT N/A Equipment and ≥1 <1 ≤ 0.1 Services other than Consulting Services Consultants ( Firms N/A N/A N/A ≤ 0.3 ) Consultants N/A N/A N/A N/A (individuals ) PROCUREMENT Senegal : SENEGAL HIGHER EDUCATION PROJECT - ESPOIR-JEUNES PLAN General Information Country: Senegal 2023-06-02 Bank’s Approval Date of the Original Procurement Plan: 2023-06-02 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P178750 GPN Date: Project Name: SENEGAL HIGHER EDUCATION PROJECT - ESPOIR-JEUNES Loan / Credit No: IDA / V4460 Ministry of Higher Education, Research and Innovation Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SN-MESRI-361776-GO-RFB / Diversifying and Increasing Achat de deux véhicules stati Access to Tertiary Technical Single Stage - One E Pending Impl IDA / V4460 Post Request for Bids Open - National 220,000.00 0.00 2023-05-29 2023-06-03 2023-07-15 2023-08-14 2023-09-18 2024-03-16 on wagon 4X4 et d'un véhicul and Vocational Education for nvelope ementation e double cabine 4x4 Improved Employability of Y outh NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SN-MESRI-361588-CS-CQS / Diversifying and Increasing Sélection d'un cabinet en cha Access to Tertiary Technical Consultant Qualifi Under Implement IDA / V4460 Post Limited 50,000.00 0.00 2023-05-22 2023-05-30 2023-06-05 2023-07-05 2023-08-09 2024-02-05 rge du recrutement du perso and Vocational Education for cation Selection ation nnel du projet enseignement Improved Employability of Y supérieur outh INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SN-MESRI-361586-CS-CDS / Sélection d'un consultant po Diversifying and Increasing ur l'élaboration des instrume Access to Tertiary Technical Pending Impleme nts environnementaux et soc IDA / V4460 and Vocational Education for Post Direct Selection Direct - National 185,000.00 0.00 2023-05-22 2023-06-01 2023-08-05 2024-02-01 ntation iaux dans le cadre de la prép Improved Employability of Y aration du projet d'appui à l'e outh nseignement supérieur du Sé négal SN-MESRI-361589-CS-INDV / Diversifying and Increasing Sélection d'un consultant po Access to Tertiary Technical Individual Consult Under Implement ur l'élaboration du manuel de IDA / V4460 and Vocational Education for Post Limited 25,000.00 0.00 2023-05-22 2023-05-30 2023-05-27 2023-06-17 2023-07-22 2024-01-18 ant Selection ation procédures du projet d'appui Improved Employability of Y à l'enseignement supérieur outh Diversifying and Increasing SN-MESRI-361770-CS-INDV / Access to Tertiary Technical Individual Consult Pending Impleme Sélection d'un architecte pro IDA / V4460 Post Limited 70,000.00 0.00 2023-05-29 2023-06-03 2023-06-24 2023-07-29 2024-01-25 and Vocational Education for ant Selection ntation grammiste Improved Employability of Y outh Page 1 Procurement Plan for PPSD Contract Title, Estimate Bank Procurement Selection Evaluation Description and d Cost Oversig Approach/Competi Methods: Method: Category US$ and ht tion: Pre/Post Rated Risk National qualificati criteria Rating International on (VfM) Open SPD Lowest Limited (RFP/RFB) evaluated Direct Competiti cost ve Dialouge Framewor k Agreemen t E-Reverse auction QCBS/QBS etc. Negotiati on BAFO Equipment for 4,300,0 POST Direct RFB Direct 100 intensive 00 care beds (including ventilators, monitors, resuscitation equipment, rehabilitation of existing IVLs) (Goods) Infection 400,000 POST Direct RFB Direct protection supplies and Supplies for intensive care (Goods) Diagnostic 1,150,0 POST Direct RFB Direct supplies 00 (including lab reagents and testing kits) for ICU patients and staff & Other supplies for provision of intensive care (including bandages, intravenous fluids, medicines) (Goods) Training for 350,000 ICU staff Refurbishment 100,000 POST Open RFQ Lowest of existing National evaluated facilities cost (Works) Development 300,000 POST Direct (Unicef CQS Based on and as leading qualificatio implementatio communication ns n of a national s taskforce) communicatio ns strategy, including training for mass media Implementatio 350,000 POST Open National CQS Based on n of qualificatio community ns outreach and awareness raising activities focusing on prevention Printing 50,000 POST Open RFQ Lowest materials on National evaluated prevention and cost control of COVID-19 (Goods) Printing 100,000 POST Open RFQ Lowest application National evaluated forms and info cost materials Equipment for 25,000 POST Open RFQ Lowest recording of National evaluated audio and cost video spots (Goods) Hardware for 50,000 POST Open RFQ Lowest data National evaluated processing cost centers (in Bokhtar and Istaravshan) IT equipment 200,000 POST Open RFQ Lowest (server and National evaluated storage cost equipment) Rehabilitation 50,000 POST Open RFQ Lowest of data National evaluated processing cost centers (in Bokhtar and Istaravshan)(W ork International 75,000 Post Open IC(s) Based on advisers (MIS, International qualificatio business ns processes) Technical 162,000 Post Open IC(s) Based on support to International qualificatio MoHSP ns M&E of project 250,000 Post Open CQS Based on progress International qualificatio (Cons) ns Project Audit 5,000 Post Open Limited LCS Based on (Cons) qualificatio ns PROCUREMENT Tajikistan : Tajikistan Emergency COVID-19 Project PLAN General Information Country: Tajikistan 2020-04-29 Bank’s Approval Date of the Original Procurement Plan: 2023-06-02 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P173765 GPN Date: 2020-07-22 Project Name: Tajikistan Emergency COVID-19 Project Loan / Credit No: IDA / D6040, IDA / D7770, IDA / D7760, IDA / D9620 Ministry of Health and Social Protection of the Republic of Tajikistan Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned TEC-19/D6040/WRK/2020/00 Component 1. Strengthening Request for Quota Single Stage - One E 2021-01-1 IDA / D6040 Post Open - National 100,000.00 0.00 Canceled 2020-05-25 2020-07-20 01 / Refurbishment of existin intensive care capacity tions nvelope 6 g facilities TEC-19/D6040/SH/2020/000 Component 4. Project Imple Request for Quota Single Stage - One E 2021-08-0 6 / Creation of data processin IDA / D6040 Post Open - National 50,000.00 0.00 Canceled 2020-12-15 2021-02-09 mentation and Monitoring tions nvelope 8 g centers (in Bokhtar and Ist aravshan) TEC-19/D6040/SW/2020/01 / Component 1. Strengthening Request for Quota Single Stage - One E 2021-03-0 Rehabilitation of Hospitals in IDA / D6040 Post Open - National 150,000.00 192,623.01 Signed 2020-07-12 2020-07-08 2020-09-06 2020-09-01 intensive care capacity tions nvelope 5 Dushanbe and RRS TEC-19/D6040/SW/2020/02 / Component 1. Strengthening Request for Quota Single Stage - One E 2021-03-0 Rehabilitation of Hospitals in IDA / D6040 Post Open - National 90,000.00 113,846.67 Signed 2020-07-12 2020-07-08 2020-09-06 2020-09-01 intensive care capacity tions nvelope 5 Khatlon Oblast TEC-19/D6040/SW/2020/03 / Component 1. Strengthening Request for Quota Single Stage - One E 2021-03-0 IDA / D6040 Post Open - National 30,000.00 28,622.61 Signed 2020-07-12 2020-07-08 2020-09-06 2020-09-01 Rehabilitation of Hospital in S intensive care capacity tions nvelope 5 ogd oblast TEC-19/D6040/SW/2020/04 / Component 1. Strengthening Request for Quota Single Stage - One E 2021-03-0 Rehabilitation of Hospital in IDA / D6040 Post Open - National 30,000.00 28,897.10 Signed 2020-07-12 2020-07-08 2020-09-06 2020-08-19 intensive care capacity tions nvelope 5 GBAO oblast GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TEC-19/D6040/SH/2020/000 Component 4. Project Imple Request for Quota Single Stage - One E 3 / Equipment for recording o IDA / D6040 Post Open - National 25,000.00 0.00 Canceled 2020-05-20 2020-07-15 2021-01-11 mentation and Monitoring tions nvelope f audio and video spots TEC-19/D6040/SH/2020/000 Component 4. Project Imple Request for Quota Single Stage - One E 4 / Hardware for data proces IDA / D6040 Post Open - National 50,000.00 0.00 Canceled 2020-09-27 2020-11-22 2021-05-21 mentation and Monitoring tions nvelope sing centers (in Bokhtar and I staravshan) TEC-19/D6040/SH/2020/000 Component 4. Project Imple Request for Quota Single Stage - One E 5 / IT equipment (server and IDA / D6040 Post Open - National 200,000.00 0.00 Canceled 2020-11-15 2021-01-10 2021-07-09 mentation and Monitoring tions nvelope storage equipment) TEC-19/D6040/DC/2020/001 Component 1. Strengthening / Procurement of Medical Equ IDA / D6040 Post Direct Selection Direct 550,000.00 0.00 Canceled 2020-05-10 2020-05-15 2020-06-19 2020-12-16 intensive care capacity ipment (six items) TEC-19/D6040/DC/2020/000 3 / Diagnostic supplies (inclu ding lab reagents and testing Component 1. Strengthening kits) for ICU patients and staf IDA / D6040 Post Direct Selection Direct 1,150,000.00 0.00 Canceled 2020-05-12 2020-05-17 2020-06-21 2020-12-18 intensive care capacity f & Other supplies for provisi on of intensive care (includin g bandages, intravenous flui ds, medicines) TEC-19/D6040/DC/2020/000 Component 1. Strengthening 2 / Infection protection suppli IDA / D6040 Post Direct Selection Direct 400,000.00 0.00 Canceled 2020-05-15 2020-05-20 2020-06-24 2020-12-21 intensive care capacity es and Supplies for intensive care TEC-19/D6040/DC-UN/2020/ Component 1. Strengthening UN Agencies (Dire 01 / Procurement of Medical IDA / D6040 Post Direct 6,300,000.00 5,300,000.00 Signed 2020-05-28 2020-05-18 2020-06-02 2020-05-18 2020-07-07 2020-06-02 2021-01-03 intensive care capacity ct) Equipment and PPE TEC-19/D6040/SH/2020/000 Component 2. Multi-sectoral Request for Quota Single Stage - One E 1 / Printing of materials on pr IDA / D6040 response planning and com Post Open - National 100,000.00 97,480.62 Completed 2020-09-02 2020-10-28 2020-09-23 2021-04-26 2020-09-23 tions nvelope evention and control of COVI munity preparedness D-19 TEC-19/D6040/SH/2020/000 Component 1. Strengthening Request for Quota Single Stage - One E 7 / PROCUREMENT OF MEDICI IDA / D6040 Post Open - National 550,000.00 536,361.41 Completed 2020-10-07 2020-12-02 2020-10-23 2021-05-31 2020-10-31 intensive care capacity tions nvelope NES AND MEDICAL PRODUCT S TEC-19/D6040/RFQ/2020/00 Component 4. Project Imple Request for Quota Single Stage - One E 1 / Procurement of IT Equipm IDA / D6040 Post Open - National 177,000.00 98,188.51 Completed 2020-11-07 2020-10-27 2021-01-02 2020-12-12 2021-07-01 2021-01-29 mentation and Monitoring tions nvelope ent for PIU and Press Center of MHSPP TEC-19/D6040/SH/2020/000 Component 4. Project Imple Request for Quota Single Stage - One E 2 / Printing of application for IDA / D6040 Post Open - National 100,000.00 90,486.63 Completed 2020-08-25 2020-10-27 2020-10-20 2020-11-10 2021-04-18 2020-11-24 mentation and Monitoring tions nvelope ms and info materials TSA №TEC-19/D6040/RFQ/2021/0 Component 1. Strengthening Request for Quota Single Stage - One E 01 / Emergency Procurement IDA / D6040 Post Open - National 150,000.00 142,481.37 Completed 2021-03-02 2021-02-26 2021-04-27 2021-04-01 2021-10-24 2021-04-03 intensive care capacity tions nvelope of Disinfectants №TEC-19/D6040/RFQ/2021/0 02 / Emergency Procurement Component 1. Strengthening Request for Quota Open - Internationa Single Stage - One E of Reagents and Consumable IDA / D6040 Post 1,350,000.00 1,311,504.00 Completed 2021-03-03 2021-02-26 2021-04-28 2021-04-01 2021-10-25 2021-08-19 intensive care capacity tions l nvelope s for COVID-19 Tests by Poly merase Chain Reaction (PCR) Method №TEC-19/D6040/RFQ/2021/0 Component 1. Strengthening Request for Quota Single Stage - One E 04 / Emergency procurement IDA / D6040 Post Open - National 200,000.00 192,827.35 Completed 2021-03-22 2021-03-18 2021-05-17 2021-04-02 2021-11-13 2021-05-02 intensive care capacity tions nvelope of FIRST AID KITS Page 1 №TEC-19/D6040/RFQ/2021/0 Component 4. Project Imple Request for Quota Single Stage - One E 03 / Emergency Procurement IDA / D6040 Post Open - National 60,000.00 12,186.42 Completed 2021-03-24 2021-03-18 2021-05-19 2021-04-06 2021-11-15 2021-06-26 mentation and Monitoring tions nvelope of Office Furniture for PIU TEC-19/D7770/RFB/AF1/202 Component 3. Temporary so Single Stage - One E 1/01 / PROCUREMENT OF IT A IDA / D7770 cial assistance for vulnerabl Post Request for Bids Open - National 450,000.00 464,066.66 Completed 2021-04-22 2021-04-22 2021-04-27 2021-04-22 2021-06-08 2021-05-14 2021-07-08 2021-05-17 2021-08-12 2021-05-29 2022-02-08 2021-09-02 nvelope ND SERVER EQUIPMENT FOR e households DATA STORAGE TEC-19/D6040/RFQ/2021/00 Component 2. Multi-sectoral 5 / Printing of registration bo Request for Quota Single Stage - One E IDA / D6040 response planning and com Post Open - National 400,000.00 466,090.39 Completed 2021-05-29 2021-05-12 2021-07-24 2021-05-22 2022-01-20 2021-06-26 oks, reporting forms, vaccina tions nvelope munity preparedness tion certificate, posters & TS A forms TEC-19/D7770/RFQ/AF2/202 Component 1. Strengthening Request for Quota Open - Internationa Single Stage - One E 1/02 / EMERGENCY PROCURE IDA / D7770 Prior 3,000,000.00 2,944,135.00 Signed 2021-07-25 2021-08-26 2021-09-19 2021-12-30 2022-03-18 intensive care capacity tions l nvelope MENT OF OXYGEN STATIONS №TEC-19/D7760/DS/UN/202 Component 1. Strengthening 1/001 / Emergency Procurem IDA / D7760 Prior Direct Selection Direct 8,000,000.00 7,180,420.02 Signed 2021-08-10 2021-07-27 2021-08-15 2021-07-29 2021-09-19 2021-07-31 2022-03-18 intensive care capacity ent of Vaccines (UNICEF) №TEC-19/D6040/D7760/D77 70/RFQ/2021/001 / EMERGEN Component 1. Strengthening Request for Quota Single Stage - One E CY PRINTING OF VACCINATIO IDA / D6040 Post Open - National 280,000.00 466,090.39 Completed 2021-09-29 2021-10-04 2021-11-24 2021-10-09 2022-05-23 2021-10-29 intensive care capacity tions nvelope N CERTIFICATES, OTHER COV ID-19 AND TSA MATERIALS №TEC-19/D7760/RFQ/AF1/20 21/0001 / EMERGENCY PPRO CUREMENT OF OFFICE FURNI Component 1. Strengthening Request for Quota Single Stage - One E TURE, IT AND OTHER EQUIPM IDA / D6040 Post Open - National 300,000.00 385,855.65 Completed 2021-10-05 2021-10-04 2021-11-30 2021-10-15 2022-05-29 2021-12-25 intensive care capacity tions nvelope ENT FOR THE IMMUNOPROPH YLAXIS CENTER, ORGANIZATI ON OF HOTLINES - 511 AND MHSPP PROJECT COORDINATI NG GROUP №TEC-19/D6040/RFQ/2021/0 08 / EMERGENCY PROCUREM Component 1. Strengthening Request for Quota Single Stage - One E IDA / D6040 Post Open - National 320,000.00 316,000.00 Completed 2021-10-05 2021-10-04 2021-11-30 2021-10-15 2022-05-29 2021-12-01 ENT OF POWER GENERATOR intensive care capacity tions nvelope S FOR 10 HOSPITALS №TEC-19/D6040/RFQ/2020/0 Component 2. Multi-sectoral Request for Quota Single Stage - One E 02 / Printing of Materials on C IDA / D6040 response planning and com Post Open - National 10,000.00 0.00 Canceled 2021-01-04 2021-03-01 2021-08-28 tions nvelope OVID-19 Prevention and Trea munity preparedness tment TEC-19/D7760/RFQ/AF1/202 1/0002 / Emergency Procure Component 1. Strengthening Request for Quota Open - Internationa Single Stage - One E Under Imple ment/Development of Inform IDA / D7760 Post 50,000.00 0.00 2021-11-17 2021-11-16 2022-01-12 2022-07-11 intensive care capacity tions l nvelope mentation ation System for Electronic I mmunization Registry (EIR) №TEC-19/D7770/DC/AF2/202 1/03 / Emergency Procureme Component 1. Strengthening IDA / D7770 Post Direct Selection Direct 1,000,000.00 971,491.17 Signed 2021-12-31 2021-12-21 2022-01-05 2021-12-21 2022-02-09 2021-12-25 2022-08-08 nt of MMR Vaccines (measles intensive care capacity , rubella, mumps and season al flu and PPE) №TEC-19/D6040/RFQ/2022/0 Component 1. Strengthening Request for Quota Open - Internationa Single Stage - One E 001 / Emergency Procureme IDA / D6040 Post 580,000.00 576,588.00 Completed 2022-03-05 2022-03-02 2022-04-30 2022-03-19 2022-10-27 2022-04-07 intensive care capacity tions l nvelope nt of PCR tests for COVID-19 №TEC-19/D7770/RFQ/AF2/20 Component 3. Temporary so 22/001 / Procurement of Dev Request for Quota Single Stage - One E Under Imple IDA / D7770 cial assistance for vulnerabl Post Open - National 50,000.00 0.00 2022-03-15 2022-03-04 2022-05-10 2022-11-06 eloped of Emergency Social P tions nvelope mentation e households ayments System №TEC-19/D7760/RFB/AF1/20 Component 1. Strengthening Single Stage - One E Under Imple 21/0004 / Procrement of First IDA / D7760 Post Request for Bids Open - National 250,000.00 0.00 2022-04-01 2022-04-14 2022-04-06 2022-04-15 2022-04-08 2022-05-05 2022-04-22 2022-05-08 2022-07-22 intensive care capacity nvelope mentation Aid Kits for COVID-19 vaccina tion №TEC-19/D6040/RFQ/2022/0 11 / EMERGENCY PROCUREM Component 1. Strengthening Request for Quota Single Stage - One E IDA / D6040 Post Open - National 30,000.00 36,866.41 Completed 2022-05-03 2022-05-12 2022-06-28 2022-05-31 2022-12-25 2022-06-24 ENT OF AUTOMATIC HELIUM intensive care capacity tions nvelope DISPENSERS WITH THERMOM ETER FOR 10 HOSPITALS №TEC-19/D7770/RFQ/2022/0 Component 2. Multi-sectoral Request for Quota Single Stage - One E Under Imple 10 / Printing of Individual Fol IDA / D7770 response planning and com Post Open - National 60,000.00 0.00 2022-08-29 2022-08-23 2022-10-24 2023-04-22 tions nvelope mentation ders, Forms & Blanks of TSA munity preparedness №TEC-19/D962/RFQ/2022/01 / Electronic medical record sy Component 1. Strengthening Request for Quota Single Stage - One E Under Imple IDA / D9620 Post Open - National 100,000.00 0.00 2022-08-29 2022-08-23 2022-10-24 2023-04-22 stem and Electronic medical intensive care capacity tions nvelope mentation record COVID-19 patients №TEC-19/D962/RFQ/2022/02 Component 1. Strengthening Request for Quota Open - Internationa Single Stage - One E / EMERGENCY PROCUREMEN IDA / D9620 Prior 3,000,000.00 0.00 Completed 2022-09-25 2022-10-11 2022-11-20 2023-05-19 2023-02-08 intensive care capacity tions l nvelope T OF TEST KITS FOR COVID-1 9 №TEC-19/D962/RFQ/2022/04 Component 1. Strengthening Request for Quota Open - Internationa Single Stage - One E Under Imple / EMERGENCY PROCUREMEN IDA / D9620 Post 600,000.00 0.00 2022-09-25 2022-09-30 2022-11-20 2023-05-19 intensive care capacity tions l nvelope mentation T OF MEDICINES FOR MEDICA L INSTITUTIONS TEC-19/D962/RFB/AF3/2022/ 003 / Procurement of Server, IT Equipment and Office Furn Component 1. Strengthening Single Stage - One E Under Imple IDA / D9620 Post Request for Bids Open - National 660,000.00 0.00 2022-10-12 2022-10-05 2022-10-17 2022-11-07 2022-11-12 2022-12-17 2023-04-16 iture for the creating of COVI intensive care capacity nvelope mentation D-19 Patient Registries and T esting of Medical Institutions in the Republic of Tajikistan №:TEC-19/D962/UN/DC/AF3/ Component 1. Strengthening 2022/001 / Emergency Procu IDA / D9620 Prior Direct Selection Direct - National 10,700,000.00 0.00 Canceled 2022-10-31 2022-11-05 2022-12-10 2023-06-08 intensive care capacity rement of Vaccines for COVI D-19 №TEC-19/D962/RFQ/2022/03 / EMERGENCY PROCUREMEN Component 1. Strengthening Request for Quota Open - Internationa Single Stage - One E IDA / D9620 Prior 2,800,000.00 0.00 Canceled 2022-11-21 2023-01-16 2023-07-15 T OF MEDICAL WASTE TREAT intensive care capacity tions l nvelope EMENT EQUIPMENT TEC-19/D962/RFB/AF3/2022/ 004 / Emergency printing of Component 1. Strengthening Single Stage - One E Under Imple IDA / D9620 Post Request for Bids Open - National 200,000.00 0.00 2022-11-16 2022-11-15 2022-11-21 2022-11-15 2023-01-02 2023-02-01 2023-03-08 2023-09-04 materials related to COVID-1 intensive care capacity nvelope mentation 9 vaccinations and immuniza tions Page 2 №TEC-19/D962/RFB/2022/05 Component 1. Strengthening Open - Internationa Single Stage - One E Under Imple / EMERGENCY PROCUREMEN IDA / D9620 Prior Request for Bids 2,800,000.00 0.00 2022-12-26 2023-01-20 2022-12-31 2023-01-27 2023-02-11 2023-02-24 2023-03-13 2023-04-16 2023-04-17 2023-10-14 intensive care capacity l nvelope mentation T OF MEDICAL WASTE TREAT MENT EQUIPMENT №TEC-19/D962/DS//UN/MR- Component 1. Strengthening Direct - Internation MMR/2023/01 / Emergency Pr IDA / D9620 Prior Direct Selection 5,100,000.00 0.00 Signed 2023-04-12 2023-04-04 2023-04-26 2023-04-05 2023-05-31 2023-04-24 2023-11-27 intensive care capacity al ocurement of MR & MMR Vac cines TEC-19/D7760/RFQ-N/2023/ 001 / Procurement of modern Component 1. Strengthening Request for Quota Single Stage - One E Under Imple IDA / D7760 Post Open - National 100,000.00 0.00 2023-04-21 2023-06-16 2023-12-13 izated information system of intensive care capacity tions nvelope mentation electronic registration of imm unization TEC-19/D962/RFQ/2023/002 Component 1. Strengthening Request for Quota Single Stage - One E Under Imple / Emergency Procurement of IDA / D9620 Post Open - National 995,000.00 0.00 2023-05-05 2023-06-30 2023-12-27 intensive care capacity tions nvelope mentation Cold Chain Equipment TEC-19/D962/RFQ/2023/003 Component 1. Strengthening Request for Quota Single Stage - One E Pending Impl / Emergency Procurement of IDA / D9620 Post Open - National 350,000.00 0.00 2023-05-05 2023-06-30 2023-12-27 intensive care capacity tions nvelope ementation IT Equipment and Server for RCIP №TEC-19/D962/RFB/2023/00 Component 1. Strengthening Open - Internationa Single Stage - One E 1 / Emergency Procurement IDA / D9620 Prior Request for Bids 5,150,000.00 0.00 Canceled 2023-04-30 2023-06-05 2023-05-05 2023-06-04 2023-07-04 2023-08-08 2024-02-04 intensive care capacity l nvelope of Medical Eqipment №TEC-19/D962/RFB/2023/00 01 / Procurement of Medical Equipment (Lot-1: 13 No. U-A Component 1. Strengthening Open - Internationa Single Stage - One E Under Imple rm Direct digital X-ray unit fo IDA / D9620 Prior Request for Bids 3,000,000.00 0.00 2023-06-21 2023-06-28 2023-06-26 2023-06-29 2023-07-17 2023-08-16 2023-09-20 2024-03-18 intensive care capacity l nvelope mentation r general radiography compl ete system; Lot-2: 25 No. Eth ylene Oxide sterilizers (15 No . 250L and 10 No.500L) №TEC-19/D962/RFB/2023/00 2 / PROCUREMENT OF PCR E QUIPMENT WITH ACCESSORI ES packaged in 3 lots: (LOT 1 Component 1. Strengthening Open - Internationa Single Stage - One E Under Imple . PCR equipment with access IDA / D9620 Prior Request for Bids 2,150,000.00 0.00 2023-06-21 2023-06-26 2023-06-26 2023-06-28 2023-07-17 2023-08-16 2023-09-20 2024-03-18 intensive care capacity l nvelope mentation ories; LOT 2. assorted Univer sal Filter Tips, Assorted Dispe nsers and other laboratory co nsumables; LOT 3. Personal P rotective Equipment) NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TEC-19/D6040/NCS/2020/00 Component 4. Project Imple Request for Quota Single Stage - One E 01 / Procurement of updated IDA / D6040 Post Open - National 10,000.00 6,616.94 Completed 2020-12-05 2021-01-30 2020-12-10 2021-07-29 2020-12-15 mentation and Monitoring tions nvelope 1C Accounting System CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TEC-19/D6040/CQS/2020/00 Component 2. Multi-sectoral 02 / Implementation of com Consultant Qualifi IDA / D6040 response planning and com Post Open - National 350,000.00 0.00 Canceled 2020-06-10 2020-07-01 2020-08-14 2020-09-13 2020-10-18 2021-04-16 munity outreach and awaren cation Selection munity preparedness ess raising activities focusing on prevention TEC-19/D6040/CQS/2020/00 Component 2. Multi-sectoral Consultant Qualifi 04 / Selection of Company on IDA / D6040 response planning and com Post Open - National 150,000.00 0.00 Canceled 2020-06-22 2020-06-15 2020-07-13 2020-06-16 2020-08-26 2020-07-28 2020-09-25 2020-07-28 2020-10-30 2021-04-28 cation Selection Media Training Consultancy munity preparedness TEC-19/D6040/CQS/2020/02 Component 2. Multi-sectoral Consultant Qualifi / Selection of Company on M IDA / D6040 response planning and com Post Open - National 150,000.00 53,913.48 Completed 2020-08-18 2020-08-15 2020-09-08 2020-10-22 2020-09-28 2020-11-21 2021-06-18 2020-12-26 2021-06-19 2021-06-24 2021-12-01 cation Selection edia Training munity preparedness TEC-19/D6040/CQS/2020/00 Component 4. Project Imple Consultant Qualifi Open - Internationa 03 / Consulting Company on IDA / D6040 Post 250,000.00 0.00 Canceled 2021-05-10 2021-05-31 2021-07-14 2021-08-13 2021-09-17 2022-03-16 mentation and Monitoring cation Selection l M&E of project progress №TEC-19/D7770/CQS/2022/ 01 / Procurement of Moderniz Component 3. Temporary so Consultant Qualifi Open - Internationa Under Implement ated ISM of ASIST for Process IDA / D7770 cial assistance for vulnerabl Post 80,000.00 0.00 2022-03-08 2022-03-29 2022-03-29 2022-05-13 2022-05-12 2022-06-11 2022-07-16 2023-01-12 cation Selection l ation ing of TSA Data and Certifica e households tion of Disability for Medical and Social Expertise TEC-19/D962/CQS/2023/01 / PROVISION OF CONSULTING SERVICES ON THE IMPLEMEN Component 1. Strengthening Consultant Qualifi Under Implement TATION OF INFORMATION TE IDA / D9620 Post Open - National 295,000.00 0.00 2023-03-31 2023-03-18 2023-04-14 2023-05-28 2023-06-27 2023-08-01 2024-01-28 intensive care capacity cation Selection ation CHNOLOGIES AND DIGITALIZ ATION OF PROCESSES OF HE ALTH CARE AND SOCIAL PRO TECTION OF THE POPULATIO N SPHERE №TEC-19/D962/CQS/2023/0 2 / Conduction research to de Component 2. Multi-sectoral Consultant Qualifi Pending Impleme fine immunity to Covid-19 a IDA / D9620 response planning and com Post Open - National 100,000.00 0.00 2023-06-04 2023-06-18 2023-08-01 2023-08-31 2023-10-05 2024-04-02 cation Selection ntation mong healthcare workers an munity preparedness d develop a guideline packag e in the context of Covid-19 INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TEC-19/D6040/ICS/2020/000 Component 4. Project Imple Individual Consult 1 / International advisers (MI IDA / D6040 Post Open 75,000.00 0.00 Canceled 2020-12-10 2021-01-28 2021-02-18 2021-03-25 2021-09-21 mentation and Monitoring ant Selection S, business processes) TEC-19/D6040/ICS/2020/000 Component 4. Project Imple Individual Consult IDA / D6040 Post Open 162,000.00 0.00 Canceled 2020-11-10 2020-12-29 2021-01-19 2021-02-23 2021-08-22 2 / Technical support to MHS mentation and Monitoring ant Selection PP Page 3 TEC-19/D6040/ICS/2020/000 Component 2. Multi-sectoral 3 / EMERGENCY RESPONSE A Individual Consult IDA / D6040 response planning and com Post Open 7,000.00 13,473.00 Signed 2020-06-01 2020-05-19 2020-07-20 2020-07-23 2020-08-10 2020-07-23 2020-09-14 2020-07-25 2021-03-13 DVISOR TO NATIONAL COVID ant Selection munity preparedness -19 COORDINATOR TEC-19/D6040/DC-CQS/2020 /0001 / Development and im Component 2. Multi-sectoral plementation of a national co IDA / D6040 response planning and com Post Direct Selection Direct 300,000.00 0.00 Canceled 2020-06-30 2020-07-10 2020-09-13 2021-03-12 mmunications strategy, inclu munity preparedness ding training for mass media (UNICEF) TEC-19/D7770/IC/AF1/2021/ Component 3. Temporary so Individual Consult 001 / Selection of Internation IDA / D7770 cial assistance for vulnerabl Post Open 50,000.00 48,746.67 Signed 2021-04-22 2021-04-22 2021-06-10 2021-05-26 2021-07-01 2021-06-08 2021-08-05 2021-06-11 2022-02-01 ant Selection al MIS Consultant e households Page 4 PROCUREMENT PLAN Project information: Higher Education for Economic Transformation Project P166415 Project Implementation agency: ARU, COSTECH, DUCE, HESLB, MJNUAT,MOCU, MUCE, MUHAS,MUST, MZUMBE, MoEST, OUT, SUA, SUZ, TCU, UDOM, UDSM Date of the Procurement Plan: Sep 28, 2021 Period covered by this Procurement Plan: Oct 2021- Oct 2022 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international and national competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: When approaching the national market, as agreed in the Procurement Plan, the country’s own procurement procedures may be used. These procurement procedures shall be consistent with the Bank’s Core Procurement Principles and ensure that the Bank’s Anti- Corruption Guidelines and Sanctions Framework and contractual remedies set out in its Legal Agreement apply. For national open competitive procurement the requirements as per National Procurement Procedure (5.4) of Bank’s Procurement Regulations will apply Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Not Applicable Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations –Not Applicable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Not applicable Other Relevant Procurement Information. None PROCUREMENT Tanzania : Higher Education for Economic Transformation Project PLAN General Information Country: Tanzania 2023-05-17 Bank’s Approval Date of the Original Procurement Plan: 2023-06-02 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P166415 GPN Date: 2021-11-28 Project Name: Higher Education for Economic Transformation Project Loan / Credit No: IDA / 68870 Institute of Accoutancy Arusha Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TZ-IAA-346405-GO-RFQ / Pro Project Coordination and Ma Request for Quota Single Stage - One E Under Imple curement of projector and T IDA / 68870 Post Open - National 20,279.66 0.00 2023-05-03 2023-05-29 2023-06-21 2023-09-21 nagement tions nvelope mentation ablets for IPIUs members TZ-IAA-346408-GO-RFB / Pro Project Coordination and Ma Single Stage - One E Under Imple curement of one standard m IDA / 68870 Post Request for Bids Open - National 73,338.41 0.00 2023-05-03 2023-06-02 2023-05-12 2023-06-02 2023-06-16 2023-06-23 2023-07-17 2024-07-16 nagement nvelope mentation otor vehicle NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TZ-IAA-364203-CS-QCBS / P ROVISION OF CONSULTANCY SERVICES FOR DESIGN REVIE Project Coordination and Ma Quality And Cost- Open - Internationa Under Implement W AND CONSTRUCTION SUPE IDA / 68870 Post 509,567.48 0.00 2023-06-05 2023-06-21 2023-07-05 2023-08-18 2023-08-20 2023-09-03 2023-09-19 2023-10-24 2027-12-02 nagement Based Selection l ation RVISION OF BUILDINGS AT IN STITUTE OF ACCOUNTANCY A RUSHA – MAIN CAMPUS AND BABATI CAMPUS. TZ-IAA-364210-CS-QCBS / P ROVISION OF CONSULTANCY SERVICES FOR DESIGN REVIE Project Coordination and Ma Quality And Cost- Open - Internationa Under Implement IDA / 68870 Post 383,253.59 0.00 2023-06-07 2023-06-21 2023-07-07 2023-08-20 2023-08-22 2023-09-05 2023-09-21 2023-10-19 2026-09-03 W AND CONSTRUCTION SUPE nagement Based Selection l ation RVISION OF BUILDINGS AT IN STITUTE OF ACCOUNTANCY A RUSHA – SONGEA CAMPUS. INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 1 PLAN DE PASSATION DE MARCHES Information sur le Projet : PROJET D’ACCELERATION DE L’ACCES A L’ELECTRICITE AU NIGER. (HASKE-P174034). Agences d’exécution du Projet : NIGELEC, ANPER et ANERSOL Date du plan de passation des marchés : 22 octobre 2021 Période couverte par ce plan de passation des marchés : Décembre 2021 - Juin 2023 Préambule : Conformément au paragraphe 5.9 du “Règlement de Passation des Marchés pour les Emprunteurs sollicitant le Financement de Projets d’Investissement (FPI)” (Juillet 2016) révisé en Novembre 2017 puis en Août 2018 (“Règlement de Passation des Marchés”), le Système électronique de la Banque de suivi systématique des transactions de marchés publics (STEP) sera utilisé pour préparer, valider et actualiser les plans de passation des marchés et effectuer toutes les transactions liées à la passation des marchés du projet. Ce texte ainsi que les tableaux du plan de passation des marchés présents dans STEP constituent le plan de passation des marchés du projet. Les conditions suivantes s'appliquent à toutes les activités de passation de marchés du plan de passation de marchés. Les autres éléments du plan de passation des marchés tels que requis au paragraphe 4.4 du Règlement de passation des marchés sont énoncés dans STEP. Les Dossiers types de passation des marchés publics de la Banque devront être utilisés pour tous les contrats soumis à la concurrence internationale, ainsi que pour tous les autres contrats soumis à cette obligation telle que spécifiée dans les tableaux du plan de passation des marchés de STEP. Procédures nationales de passation des marchés : En accord avec le paragraphe 5.3 du Règlement de passation des marchés, dans le cas où la procédure de passation des marchés se fera au niveau national (telle que spécifiée dans les tableaux du plan de passation des marchés inclus de STEP), les procédures nationales de passation des marchés du Niger pourront être utilisées. Si l’Emprunteur utilise ses propres procédures d’appel d’offres national ouvert telles qu’énoncées dans la Loi N°2011-37 du 28 Octobre 2011 portant principes généraux, contrôle and régulation des marchés publics et des délégations de service public au Niger et le Décret N° 2016-641/PRN/PM du 21/Décembre 2016 portant Code des marchés Publics et des Délégations de Service Public, ces arrangements sont soumis aux dispositions du paragraphe 5.4 du Règlement de passation des marchés et aux conditions qui suivent. Les dispositions à respecter pour un appel d’offres/à propositions ouvert national sont les suivantes : a. le dossier d’appel d’offres/à propositions oblige le Soumissionnaire/Proposant présentant une Offre/Proposition à déposer un agrément signé, qui sera joint à tout contrat éventuel, pour confirmer qu’il applique et respecte les Directives de la Banque pour la lutte contre la corruption, y compris sans limitation, le droit de la Banque de sanctionner et les droits de la Banque pour l’inspection et l’audit ; b. Les documents de passation des marchés incluent des dispositions, convenues avec la Banque, destinées à atténuer de manière adéquate les risques et impacts environnementaux et sociaux (y compris l'exploitation et les abus sexuels et la violence basée sur le genre), l’hygiène et la sécurité (« ESHS ») ; c. les droits de la Banque d’examiner le dossier et les activités de passation des marchés ; d. l’existence d’un mécanisme efficace d’examen des plaintes ; et e. la gestion et l’archivage des dossiers relatifs au Processus de la Passation des Marchés. Les autres modalités nationales de passation des marchés (autres que sous forme d’appel d’offres/à propositions national ouvert) qui pourraient être appliquées par l’Emprunteur (appel d’offres limité/restreint, demande de prix/consultation de fournisseurs, entente directe) doivent être conformes avec les Principes Fondamentaux de Passation des Marchés de la Banque et garantir que les Directives de la Banque contre la corruption, son Cadre de Sanctions et les recours contractuels visés dans l’Accord Juridique s’appliquent. Crédit-bail tel que spécifié au paragraphe 5.10 du Règlement de Passation des marchés : Le crédit-bail peut être utilisé pour les contrats indiqués comme tel dans le Plan de passation des marchés. « Sans objet » Achat de biens d’occasion tel que spécifié au paragraphe 5.11 du Règlement de Passation des Marchés est autorisé pour les contrats indiqués comme tel dans le Plan de passation des marchés. « Sans objet » Préférence nationale telle que spécifiée au paragraphe 5.51 du Règlement de Passation des Marchés (Fournitures et Travaux). - Fournitures : s’applique - Travaux : s’applique L’Assistance directe à la mise en œuvre (sigle HEIS en anglais) tel que précisée aux paragraphes 3.10 et 3.11 du Règlement de Passation des marchés s’applique. Au besoin. Autres informations pertinentes sur la passation des marchés : Les dispositions contenues dans le « Guide de la Banque mondiale sur les procédures de passation des marchés dans les situations de besoin urgent d’assistance ou de contraintes de capacité publié le 7 mars 2019» s’appliquent au besoin et au cas par cas. Plan de Passation de marchés Catégor Date de Type de démarrage ie de Méthode % financé Montant Approche de Revue No Libellé du marché passati de par la prévue de US$ marché BM on de sélection Banque l’activité marché (mm/aaaa) Composante 1 Sous composante 1.1- Construction de l’interconnexion de transmission entre le Réseau Ouest et le Réseau Centre EST- NIGELEC Construction de 270 km Ouverte, ligne 132kV entre Zabori- Internationale (une 71 900 Appel A Priori Octobre 2022 1 Malbaza (lot1 et 2) et 50 km Tvx seule étape et 100 000 d’offres de ligne 66 kV entre Illéla et avec Tahoua NIGELEC (lot 3) préqualification) Construction de nouveaux postes 132/33 kV à Doucthi, Ouverte, Konni et Madaoua à Zabori, Internationale (une 13 100 Appel A Priori 100 Octobre 2022 2 66/33 kV à Tahoua et Tvx seule étape et 000 d’offres extension des postes à avec Zabori et Malbaza (132kV), préqualification) Illela (66 kV) NIGELEC (lot4) Ingénieurs du maître Ouverte, d'ouvrage pour la 5 000 Internationale (sur A Priori 100 Janvier 2022 3 supervision de la Cons SFQC 000 la base d’une liste construction des réseaux de restreinte) transmission – NIGELEC Sous composante 1.2 Ouverte, Densification et 30 000 Appel internationale (en A Priori 100 Janvier 2022 4 renforcement de réseau - Tvx 000 d’offres plusieurs lots, en NIGELEC une seule étape et Catégor Date de Type de démarrage ie de Méthode % financé Montant Approche de Revue No Libellé du marché passati de par la prévue de US$ marché BM on de sélection Banque l’activité marché (mm/aaaa) sans préqualification) Ouverte, Acquisition de matériel pour 40 000 Appel Internationale (une A Priori 100 Février 2022 5 l’électrification rurale - Four 000 d’offres seule étape et sans NIGELEC préqualification) Ouverte, Nationale (en plusieurs lots, 5bi Travaux électrification rurale 10 000 Appel A Priori 100 Mai 2022 Tvx une seule étape et s - NIGELEC 000 d’offres sans préqualification) Ingénieurs du maître Ouverte, d'ouvrage pour la 5 000 Internationale (sur A Priori 100 Janvier 2022 7 supervision de la Cons SFQC 000 la base d’une liste construction des réseaux de restreinte) distribution - NIGELEC Sous composante 1.3 Ouverte, Internationale (en Acquisition de compteurs 6 500 Appel A Priori 100 Janvier 2023 7 Four une seule étape, NIGELEC 000 d’offres sans préqualification) Ouverte, Internationale (en Acquisition de matériels de 8 500 Appel A Priori 100 Janvier 2023 8 Four une seule étape, branchements NIGELEC 000 d’offres sans préqualification) Catégor Date de Type de démarrage ie de Méthode % financé Montant Approche de Revue No Libellé du marché passati de par la prévue de US$ marché BM on de sélection Banque l’activité marché (mm/aaaa) Ouverte, Nationale Recrutements d'entreprises (en plusieurs lots, A pour la réalisation des 1 500 9 Tvx Appel en une seule étape Posteriori 100 Avril 2023 travaux de branchements 000 d’offres et sans NIGELEC préqualification) Recrutement d'un consultant Ouverte, pour la conception et l'appui Internationale (sur à la mise en œuvre de la la base d’une liste A 10 subvention des appareils et Cons 700 000 SFQC restreinte) Posteriori 100 Mai 2022 équipements d'usage productifs en milieu rural NIGELEC Composante 2 Sous Composante 2.1 Ouverte, Développement de Internationale (en nouveaux mini-réseaux 18 000 Appel plusieurs lots en A Priori 100 Juin 2022 12 solaires grâce à un Tvx 000 d’offres une seule étape, partenariat public-privé (30 avec sélection à 40 localités) - ANPER initiale) Ouverte, Acquisition de compteurs et Internationale (en 2 000 Appel A Priori 100 Juin 2023 13 matériel de branchements Four une seule étape, 000 d’offres pour l’ANPER sans préqualification) Ouverte, Ingénieur du Maître 2 000 Internationale (sur A Priori 100 14 d'Ouvrage pour la Cons SFQC Septembre 2021 000 la base d’une liste supervision de la restreinte) Catégor Date de Type de démarrage ie de Méthode % financé Montant Approche de Revue No Libellé du marché passati de par la prévue de US$ marché BM on de sélection Banque l’activité marché (mm/aaaa) construction de nouveaux mini-réseaux - ANPER Hybridation solaire et Ouverte, densification des mini- Internationale (en 15 000 Appel A Priori 100 Août 2022 15 réseaux (28 localité avec Tvx une seule étape et 000 d’offres réseau à renforcer) - avec NIGELEC préqualification) Ingénieur du Maître Ouverte, d'Ouvrage pour la 2 000 Internationale (sur A Priori 100 Janvier 2022 16 supervision de l'hybridation Cons SFQC 000 la base d’une liste des mini-réseaux existants - restreinte) NIGELEC Composante 3 Ouverte, Gestionnaire des fonds – 1 700 Internationale (sur A Priori 100 Février 2022 17 Cons SFQC DPED/ANERSOL 000 la base d’une liste restreinte) Ouverte, Agence de vérification 1 200 Internationale (sur A Priori 100 Décembre 2021 18 Cons SFQC indépendante- ANERSOL 000 la base d’une liste restreinte) Sous Composante 3.1 Ouverte, Nationale Travaux Electrification des (en plusieurs lots 11 000 Appel A Priori 100 Octobre 2022 18 écoles et centres de santé – Tvx en une seule 000 d’offres ANERSOL étape, sans préqualification) Catégor Date de Type de démarrage ie de Méthode % financé Montant Approche de Revue No Libellé du marché passati de par la prévue de US$ marché BM on de sélection Banque l’activité marché (mm/aaaa) Ouverte, Nationale O&M pendant les deux A (en une seule 20 premières années - cons 400 000 Appel Postériori 100 Novembre 2022 d’offres étape, sans ANERSOL– préqualification) Ouverte, Nationale Électrification des (en plusieurs lots A infrastructures publiques 1 000 21 Tvx Appel en une seule Posteriori 100 Janvier 2023 (éclairage public, marchés, 000 d’offres étape, sans mairies, etc.) - ANERSOL préqualification) Ouverte, Systèmes de pompage d'eau Internationale (en A 1 000 22 potable par énergie solaire - Tvx Appel une seule étape et Posteriori 100 Janvier 2023 000 d’offres ANERSOL avec préqualification) Acquisition et installation de A Restreinte, 23 systèmes de suivi à distance Four 100 000 Demande Posteriori 100 Mai 2023 Cotations Nationale ANERSOL A Acquisition et installation de Restreinte, Four 100 000 Demande Posteriori 100 Mai 2023 système de suivi à distance Cotations Nationale Ouverte, Assistance technique pour la A Internationale (sur 24 gestion et la pérennisation Cons 300 000 SFQC Posteriori 100 Janvier 2023 la base d’une liste des infrastructures ANERSOL restreinte) Ouverte, Assistance à la maitrise Internationale (sur 1 200 A Priori 100 Juin 2022 25 d'ouvrage et renforcement Cons SFQC la base d’une liste 000 de capacités ANERSOL restreinte) Catégor Date de Type de démarrage ie de Méthode % financé Montant Approche de Revue No Libellé du marché passati de par la prévue de US$ marché BM on de sélection Banque l’activité marché (mm/aaaa) Sous Composante 3.2 Communication et Ouverte, A sensibilisation - plan et appui Internationale (sur 29 Cons 250 000 SFQC Posteriori 100 Octobre 2022 à la mise en œuvre – la base d’une liste consultant ANERSOL restreinte) Ouverte, Consultant international A Internationale (sur 32 d'appui à la mise en œuvre Cons 500 000 SFQC Posteriori 100 Avril 2022 la base d’une liste technique ANERSOL restreinte) Sous composante 3.3 Assistance technique pour Ouverte, A l'approche de promotion des Internationale (sur 36 Cons 650 000 SFQC Posteriori 100 Avril 2022 foyers banco et innovation la base d’une liste DPED restreinte) Ouverte, Assistance technique aux A Internationale (sur 39 entreprises y compris Cons 650 000 SFQC Posteriori 100 Juin 2022 la base d’une liste femmes entrepreneurs DPED restreinte) Ouverte, Assistance technique au A Internationale (sur 45 renforcement de capacités Cons 200 000 SFQC Posteriori 100 Octobre 2022 la base d’une liste des distributeurs de LPG restreinte) Assistance technique au Ouverte, A renforcement de capacités Internationale (sur 46 Cons 200 000 SFQC Posteriori 100 Novembre 2022 des distributeurs de LPG la base d’une liste DPED restreinte) Catégor Date de Type de démarrage ie de Méthode % financé Montant Approche de Revue No Libellé du marché passati de par la prévue de US$ marché BM on de sélection Banque l’activité marché (mm/aaaa) Ouverte, Assistance technique à la A Internationale (sur 47 participation des femmes à Cons 300 000 SFQC Posteriori 100 Novembre 2022 la base d’une liste la filière LPG DPED restreinte) Ouverte, Etude de la filière LPG, A Internationale (sur 50 organisation, tarification Cons 350 000 SFQC Posteriori 100 Janvier 2023 la base d’une liste DPED restreinte) Service de consultant Ouverte, d'assistance à la mise en 1 700 Internationale (sur A Priori 100 Novembre 2022 51 Cons SFQC œuvre (solutions de 000 la base d’une liste cuissons propres) DPED restreinte) A 53 Consultant national DPED Cons 130 000 SCI Ouverte Posteriori 100 Décembre 2022 A Restreinte, 54 Mobilier pour bureau DPED Four 60 000 Demande Posteriori 100 Mai 2022 de cotation Nationale A Equipements pour contrôle Restreinte, 56 Four 120 000 Appel Posteriori 100 Février 2023 (GPL et Foyers) DPED d’offres Nationale Ouverte, Nationale A Achat de deux véhicules (en une seule 57 Four 120 000 Appel Posteriori 100 Février 2022 DPED d’offres étape, sans préqualification) A Restreinte, 58 Equipement Internet DPED Four 40 000 Demande Posteriori 100 Mai 2022 de cotation Nationale Catégor Date de Type de démarrage ie de Méthode % financé Montant Approche de Revue No Libellé du marché passati de par la prévue de US$ marché BM on de sélection Banque l’activité marché (mm/aaaa) Elaboration de la politique Ouverte, A nationale des énergies Internationale (sur 62 Cons 200 000 SFQC Posteriori 100 Septembre 2022 domestiques (une étude) la base d’une liste DPED restreinte) Composante 4 Composante 4.1 NIGELEC Ouverte, Programme de Protection Internationale (en 4 000 Appel A Priori 100 Mars 2022 64 des Recettes (RPP)- Four une seule étape, 000 d’offres Acquisitions NIGELEC sans préqualification) Ouverte, Système d'enregistrement et Internationale (en A 1 500 65 de gestion des incidents Four Appel une seule étape, Posteriori 100 Avril 2022 000 d’offres (IRMS)-Acquisition NIGELEC sans préqualification) Ouverte, Programme de réduction des Internationale (en A 1 500 66 pertes de distribution- Four Appel une seule étape, Posteriori 100 Avril 2022 000 d’offres Acquisition NIGELEC sans préqualification) Ouverte, Numérisation des processus Internationale (en 5 000 Appel A Priori 100 Octobre 2022 67 d'entreprise de la NIGELEC- Four une seule étape, 000 d’offres Acquisition sans préqualification) Catégor Date de Type de démarrage ie de Méthode % financé Montant Approche de Revue No Libellé du marché passati de par la prévue de US$ marché BM on de sélection Banque l’activité marché (mm/aaaa) Programme de Ouverte, développement des 1 500 Internationale (sur A Priori 100 Mai 2022 68 ressources humaines de la Cons SFQC 000 la base d’une liste NIGELEC-Consultants (centre restreinte) de formation) Efficacité énergétique pour Ouverte, la réduction de la demande Internationale (en A 1 500 69 de pointe – Acquisition Four Appel une seule étape, Posteriori 100 Juin 2022 000 d’offres sans préqualification) Sous composante 4.2 MPEER Ouverte, Préparation d'un programme A Internationale (sur 70 d'efficacité énergétique – Cons 400 000 SFQC Posteriori 100 Mai 2023 la base d’une liste MPEER restreinte) Ouverte, A Assistance technique au Internationale (sur 78 Cons 500 000 SFQC Posteriori 100 Février 2022 MPEER (Consultants) la base d’une liste restreinte) ARSE A Restreinte, 82 Mobilier de bureau (ARSE) Four 20 000 Demande Posteriori 100 Mai 2022 de cotation Nationale A Restreinte, 83 Matériel Informatique (ARSE) Four 40 000 Demande Posteriori 100 Mai 2022 de cotation Nationale Sous composante 4.3 Catégor Date de Type de démarrage ie de Méthode % financé Montant Approche de Revue No Libellé du marché passati de par la prévue de US$ marché BM on de sélection Banque l’activité marché (mm/aaaa) ANPER Ouverte, Nationale A (en une seule 85 Matériel roulant (ANPER) Four 120 000 Appel Posteriori 100 Mai 2022 d’offres étape et sans préqualification) A Restreinte, 86 Mobilier de bureau (ANPER) Four 20,000 Demande Posteriori 100 Avril 2022 de cotation Nationale A Matériel Informatique Restreinte, 87 Four 40,000 Demande Posteriori 100 Avril 2022 (ANPER) de cotation Nationale Renforcement UGP-ANPER Spécialiste en A 11 développement social et Cons 125 000 SCI Ouverte Posteriori 100 Janvier 2022 1 genre ANPER ANESRSOL Ouverte, Nationale Acquisition Equipements A 11 (en une seule contrôle technique et Four 172 414 Appel Posteriori 100 Janvier 2022 2 d’offres étape, sans logiciels (ANERSOL) préqualification) Acquisition Groupe A 11 Restreinte, électrogène/Centrale solaire Four 70 000 Demande Posteriori 100 Août 2022 3 de cotation Nationale (ANERSOL) Acquisition mobilier de A 11 Ouverte, Nationale bureaux et bureautique Four 160 000 Appel Posteriori 100 Mars 2022 4 d’offres (en une seule (ANERSOL) Catégor Date de Type de démarrage ie de Méthode % financé Montant Approche de Revue No Libellé du marché passati de par la prévue de US$ marché BM on de sélection Banque l’activité marché (mm/aaaa) étape, sans préqualification) A 11 Acquisition matériel Restreinte, Four 40 000 Demande Posteriori 100 Avril 2022 5 informatique (ANERSOL) de cotation Nationale Ouverte, Nationale A 11 Acquisition 2 véhicules (en une seule Four 120 000 Appel Posteriori 100 Mars 2022 6 (ANERSOL) d’offres étape, sans préqualification) Extension et Aménagement A 11 Restreinte, bureaux spécialistes Tvx 100 000 Demande Postériori 100 Juillet 2022 8 de cotation Nationale (ANERSOL) Ouverte, A 12 Internationale (sur Enquête de satisfaction Cons 50 000 SFQC Postériori 100 Janvier 2023 6 la base d’une liste restreinte) RENFORCEMENT UGP ANERSOL Cons Ouverte A 13 Coordonnateur de projets - SCI 225 000 Posteriori 100 Janvier 2022 6 ANERSOL Cons Ouverte A 13 Spécialiste en passation de SCI 125 000 Posteriori 100 Janvier 2022 7 marches - ANERSOL Spécialiste en gestion Cons Ouverte A 13 SCI financière (Comptable) - 125 000 Posteriori 100 Janvier 2022 8 ANERSOL Catégor Date de Type de démarrage ie de Méthode % financé Montant Approche de Revue No Libellé du marché passati de par la prévue de US$ marché BM on de sélection Banque l’activité marché (mm/aaaa) Spécialiste en sauvegarde Cons Ouverte A 13 SCI environnementale – 125 000 Posteriori 100 Janvier 2022 9 ANERSOL Cons Ouverte A 14 Spécialiste en sauvegarde SCI 125 000 Posteriori 100 Janvier 2022 0 sociale et genre – ANERSOL Cons Ouverte A 14 SCI Auditeur Interne – ANERSOL 125 000 Posteriori 100 Juin 2022 1 Cons Ouverte A 14 Spécialiste en SCI 125 000 Posteriori 100 Mars 2022 3 communication – ANERSOL Equipement NIGELEC A 14 Restreinte, Mobilier de bureau Four 20 000 Demande Posteriori 100 Avril 2022 5 de cotation Nationale A 14 Restreinte, Matériel Informatique Four 40 000 Demande Posteriori 100 Mai 2022 6 de cotation Nationale Acquisition de la plateforme Ouverte, Nationale A 14 Odyssey pour la préparation (en une seule Four 300 000 Appel Posteriori 100 Avril 2022 7 de nouveaux projets d’offres étape, sans (application informatique) préqualification) Ouverte, Nationale A 14 (en une seule Matériel roulant Four 120 000 Appel Posteriori 100 Février 2022 8 d’offres étape, sans préqualification) Catégor Date de Type de démarrage ie de Méthode % financé Montant Approche de Revue No Libellé du marché passati de par la prévue de US$ marché BM on de sélection Banque l’activité marché (mm/aaaa) Ouverte, A 16 Internationale (sur Audit des comptes du projet Cons 170 000 SFQC Posteriori 100 Aout 2022 9 la base d’une liste restreinte) RENFORCEMENT UGP NIGELEC Spécialiste genre chargé de Cons Ouverte A 17 SCI violence basée sur le genre – 125 000 Posteriori 100 Janvier 2022 4 NIGELEC Cons Ouverte A 17 Spécialiste en suivi SCI 125 000 Posteriori 100 Janvier 2022 5 évaluation – NIGELEC Cons Ouverte A 17 Spécialiste en SCI 125 000 Posteriori 100 Janvier 2022 6 communication - NIGELEC Cons Ouverte A 18 SCI Suivi-Evaluation – Haské 700 000 Posteriori 100 Janvier 2022 0 PROCUREMENT Niger : Niger Accelerating Electricity Access Project (Haské) PLAN General Information Country: Niger 2022-03-07 Bank’s Approval Date of the Original Procurement Plan: 2023-06-04 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P174034 GPN Date: 2023-01-25 Project Name: Niger Accelerating Electricity Access Project (Haské) Loan / Credit No: IDA / 70130, IDA / D9460 SOCIETIE NIGERIENNE D’ELECTRICITE (NIGELEC) Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned AOI-02/DPD/HASKE/22 / App Component 1. Reinforcemen Request for Bids - el d'offres international Dens t and expansion of transmiss Open - Internationa Single Stage - One E Works (without pr 30,000,000.0 2024-06-0 IDA / 70130 Prior Request for Bids 0.00 Signed 2022-04-30 2022-09-05 2022-05-05 2022-09-19 2022-07-04 2022-11-08 2022-08-03 2023-01-26 2022-09-13 2023-06-03 ification et renforcement des ion and distribution network l nvelope equalification) SP 0 4 réseaux de distribution - NIG s to increase access to grid D ELEC electricity services Request for Bids - AOI 01/HASKE/NIGELEC/22 / Component 2. Reinforcing th Works (without pr Appel d'offres international p e ecosystem for the develop Open - Internationa Single Stage - One E equalification) SP Under Imple 2024-07-0 IDA / 70130 Post Request for Bids 9,500,000.00 0.00 2022-06-22 2022-09-29 2022-06-27 2022-10-05 2022-08-26 2022-12-21 2022-09-10 2022-10-15 our l'Hybridation solaire et la ment of solar PV powered mi l nvelope D - Applying contr mentation 6 densification des mini-réseau ni grids in rural areas actor disqualificia x tion Component 4. Utility operati 03/DC/2022/HASKE/NIGELEC onal performance improvem Request for Quota / Fourniture et pose de hang Request for Quota Single Stage - One E 2023-01-2 IDA / 70130 ent, institutional strengtheni Post Limited tions (Non Bank-S 82,000.00 0.00 Signed 2022-12-10 2022-12-15 2023-01-08 ar et grille de protection du b tions nvelope 9 ng, technical assistance and PD) ureau UGP BM NIGELEC implementa tion support Request for Bids - Component 1. Reinforcemen Works (without pr AOI-04/2023/HASKE/NIGELE t and expansion of transmiss Open - Internationa Single Stage - One E equalification) SP Pending Imp 2024-09-0 C / Travaux de l'électrificatio IDA / 70130 Post Request for Bids 9,000,000.00 0.00 2023-07-05 2023-07-20 2023-09-18 2023-10-03 2023-11-07 ion and distribution network l nvelope D - Applying contr lementation 2 n rurale s to increase access to grid actor disqualificia electricity services tion GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual AOI 03/HASKE/NIGELEC/202 Component 1. Reinforcemen 2 / Fourniture de matériels d t and expansion of transmiss e réseaux de distribution pou Open - Internationa Single Stage - One E Under Imple IDA / 70130 ion and distribution network Prior Request for Bids 40,000,000.00 0.00 2022-09-20 2022-11-18 2022-09-25 2022-11-22 2022-11-06 2023-01-12 2022-12-06 2023-05-19 2023-01-10 2023-07-09 r l'électrification rurale basée l nvelope mentation s to increase access to grid sur le réseau dans les Région electricity services s de Tillabéry, Dosso, Agadez ,Maradi, Zinder et Tahoua Component 4. Utility operati 01/ED/2022/HASKE/NIGELEC onal performance improvem / Fourniture et installation du Direct - Internation IDA / 70130 ent, institutional strengtheni Post Direct Selection 41,000.00 0.00 Signed 2022-11-21 2022-11-25 2022-11-26 2022-11-30 2022-12-23 2023-01-22 Logiciel de suivi-évaluation ( al ng, technical assistance and RUCHE) implementa tion support 02/2023/HASKE/NIGELEC/FO Component 4. Utility operati URN / Fourniture et installatio onal performance improvem Request for Quota Single Stage - One E n des mobiliers de bureau po IDA / 70130 ent, institutional strengtheni Post Limited 64,000.00 0.00 Signed 2023-02-12 2023-05-03 2023-03-16 2023-04-10 tions nvelope ur le personnel de l'UGP/BM/ ng, technical assistance and NIGELEC implementa tion support Component 4. Utility operati 03/2023/HASKE/MEER/FOUR onal performance improvem N / Fourniture et installation Request for Quota Single Stage - One E IDA / 70130 ent, institutional strengtheni Post Limited 78,000.00 0.00 Signed 2023-02-20 2023-04-24 2023-03-24 2023-04-23 des équipements internet et tions nvelope ng, technical assistance and des cameras de surveillance implementa tion support 04/2023/HASKE/MEER/FOUR Component 4. Utility operati N / Acquisition d'un véhicule onal performance improvem Request for Quota Single Stage - One E Pending Impl tout terrain pour le Ministère IDA / 70130 ent, institutional strengtheni Post Limited 78,000.00 0.00 2023-02-20 2023-03-24 2023-04-23 tions nvelope ementation de l'Energie et des Energies ng, technical assistance and Renouvelables implementa tion support 05/2023/HASKE/ARSE/FOUR Component 4. Utility operati N / Fourniture et installation onal performance improvem Request for Quota Single Stage - One E Under Imple des matériels informatiques IDA / 70130 ent, institutional strengtheni Post Limited 78,000.00 0.00 2023-02-19 2023-05-18 2023-03-23 2023-04-12 tions nvelope mentation pour l'Agence de Régulation ng, technical assistance and du Secteur de l'Energie ARSE implementa tion support 06/2023/HASKE/NIGELEC/FO Component 4. Utility operati URN / Fourniture et installatio onal performance improvem Request for Quota Single Stage - One E n des matériels de vidéo conf IDA / 70130 ent, institutional strengtheni Post Limited 64,000.00 0.00 Signed 2023-02-18 2023-04-03 2023-03-22 2023-04-06 tions nvelope érence dans les salles de réu ng, technical assistance and nion du Projet HASKE implementa tion support 08/2023/HASKE/NIGELEC/FO Component 4. Utility operati URN / Acquisition des matéri onal performance improvem els pour le renforcement des Request for Quota Single Stage - One E IDA / 70130 ent, institutional strengtheni Post Limited 64,000.00 0.00 Signed 2023-03-04 2023-03-23 2023-04-05 2023-04-25 capacités de sauvegarde de tions nvelope ng, technical assistance and migration Upgrad onduleurs implementa tion support pare feux switch sauvegarde des serveurs 09/2023/HASKE/MEER/FOUR Component 4. Utility operati N / Acquisition des équipeme onal performance improvem Request for Quota Single Stage - One E nts et mobiliers de bureau po IDA / 70130 ent, institutional strengtheni Post Limited 32,000.00 0.00 Signed 2023-04-03 2023-04-27 2023-05-05 2023-05-25 tions nvelope ur le Ministère de l'Energie et ng, technical assistance and des Energies Renouvelables implementa tion support 11/2023/HASKE/ARSE/FOUR Component 4. Utility operati N / Acquisition des matériels onal performance improvem Request for Quota Single Stage - One E de bureau pour l’Autorité de IDA / 70130 ent, institutional strengtheni Post Limited 78,000.00 0.00 Signed 2023-04-15 2023-05-18 2023-05-17 2023-06-06 tions nvelope Régulation du Secteur de l’E ng, technical assistance and nergie ARSE implementa tion support Page 1 10/2023/HASKE/MEER/NIGEL EC / Fourniture et installation Component 4. Utility operati des matériels et équipement onal performance improvem s informatiques au profit du Request for Quota Single Stage - One E Under Imple IDA / 70130 ent, institutional strengtheni Post Limited 100,000.00 0.00 2023-04-04 2023-05-31 2023-05-06 2023-05-09 Ministère de l'Energie et des tions nvelope mentation ng, technical assistance and Energies Renouvelables et d implementa tion support u Personnel de l'Unité de Ge stion des Projets financés par la BM à la NIGELEC 13/2023/HASKE/UGP/NIGELE Component 4. Utility operati C / Acquisition de deux véhic onal performance improvem Request for Quota Single Stage - One E ules tout terrain pour les mis IDA / 70130 ent, institutional strengtheni Post Limited 100,000.00 0.00 Signed 2023-04-02 2023-05-05 2023-05-04 2023-06-03 tions nvelope sions de supervision et d'une ng, technical assistance and moto pour l'agent de liaison implementa tion support au profil de l'UGP BM AOI-02/2023/HASKE/NIGELE Component 1. Reinforcemen C / Fourniture des matériels t and expansion of transmiss Open - Internationa Single Stage - One E Under Imple de réseaux de distribution po IDA / 70130 ion and distribution network Prior Request for Bids 8,500,000.00 0.00 2023-06-30 2023-06-13 2023-07-15 2023-06-14 2023-08-26 2023-09-25 2023-10-30 2024-05-27 l nvelope mentation ur l’électrification rurale basé s to increase access to grid e sur le réseau dans la région electricity services de Maradi ex lot N°4 NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 02/DC/2022/HASKE/NIGELEC Component 1. Reinforcemen / Confection des outils et sup t and expansion of transmiss ports de communication (aut Request for Quota Single Stage - One E IDA / 70130 ion and distribution network Post Limited 41,000.00 0.00 Signed 2022-12-11 2022-12-01 2023-01-09 2023-01-30 ocollants, plaquettes de bure tions nvelope s to increase access to grid au, calendriers 2023, bols, ca electricity services rtes de visite, badges, gilets) 04/2022/HASKE/NIGELEC / F Component 5. Contingent E Request for Quota Single Stage - One E Under Imple ourniture et Installation du ré IDA / 70130 mergency Response Compo Post Limited 50,782.00 0.00 2022-12-20 2022-12-05 2023-02-14 2023-03-16 tions nvelope mentation seau internet nent CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NE-NIGELEC-281293-CS-QCB Component 2. Reinforcing th S / Recrutement d'un Ingénie e ecosystem for the develop Quality And Cost- Open - Internationa Under Implement ur Conseils pour le contrôle e IDA / 70130 Prior 2,000,000.00 0.00 2022-03-21 2022-07-15 2022-04-11 2022-07-19 2022-05-25 2023-01-04 2022-06-22 2023-02-28 2022-07-22 2023-04-06 2022-08-26 2022-09-30 2023-09-30 ment of solar PV powered mi Based Selection l ation t la supervision de l'hybridati ni grids in rural areas on des mini-réseaux existant s NE-NIGELEC-281294-CS-QCB Component 1. Reinforcemen S / Recrutement d'un Ingénie t and expansion of transmiss Quality And Cost- Open - Internationa IDA / 70130 Prior 5,000,000.00 0.00 Under Review 2022-06-23 2022-11-14 2022-07-14 2022-11-17 2022-08-07 2023-04-11 2022-09-16 2023-03-14 2022-09-26 2022-10-15 2022-11-19 2024-09-09 ur Conseils Contrôle et super ion and distribution network Based Selection l vision des travaux de distribu s to increase access to grid tion electricity services Component 4. Utility operati NE-NIGELEC-311958-CS-QCB onal performance improvem S / Audit des comptes du proj Quality And Cost- Open - Internationa Under Implement IDA / 70130 ent, institutional strengtheni Post 100,000.00 0.00 2022-09-20 2022-09-12 2022-10-11 2022-11-22 2022-11-24 2023-02-27 2022-12-22 2023-02-27 2023-01-21 2023-05-10 2023-02-25 2023-04-01 2024-03-31 et pour les exercices 2022, 2 Based Selection l ation ng, technical assistance and 023,2024 implementa tion support NE-NIGELEC-311612-CS-QCB Component 1. Reinforcemen S / Ingénieurs Conseils pour l t and expansion of transmiss Quality And Cost- Open - Internationa Pending Impleme IDA / 70130 Prior 5,000,000.00 0.00 2022-12-30 2023-01-20 2023-02-13 2023-02-17 2023-02-27 2023-03-20 2023-04-24 2025-04-13 a supervision de la constructi ion and distribution network Based Selection l ntation on des réseaux de transport s to increase access to grid Zabori- Malbaza electricity services 01/2023/SCE/HASKE/NIGELE Component 4. Utility operati C/PAR / Réalisation du plan d’ onal performance improvem actions de réinstallation des Consultant Qualifi Open - Internationa Under Implement IDA / D9460 ent, institutional strengtheni Post 65,000.00 0.00 2023-02-07 2023-04-11 2023-02-28 2023-05-18 2023-03-17 2023-04-16 2023-05-14 2023-07-13 personnes affectées par les t cation Selection l ation ng, technical assistance and ravaux de la réalisation de la implementa tion support ligne Zabori Malbaza et Illela Tahoua avec les postes sourc es 07/2023/HASKE/NIGELEC/SC Component 4. Utility operati E / Recrutement d'un Consult onal performance improvem Consultant Qualifi Open - Internationa Pending Impleme ant chargé de l'élaboration et IDA / 70130 ent, institutional strengtheni Post 78,000.00 0.00 2023-02-20 2023-03-13 2023-04-26 2023-05-26 2023-06-30 2023-12-27 cation Selection l ntation la mis en oeuvre de la Straté ng, technical assistance and gie de communication du pro implementa tion support jet HASKE INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 2 PROCUREMENT PLAN (Textual Part) Project information: [Burundi] [Burundi Youths Skills and Employability Project] [P-164416] Project Implementation agency: [Ministry of Education and Vocational and Professional Training] Date of the Procurement Plan: [October 2018] Period covered by this Procurement Plan: [October 2018 – December 2019] Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the national procurement legislation, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Not Applicable Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables Not Applicable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Not Applicable Other Relevant Procurement Information. Not Applicable PROCUREMENT Burundi : Burundi Skills for Jobs: Women and Youth Project PLAN General Information Country: Burundi 2019-03-01 Bank’s Approval Date of the Original Procurement Plan: 2023-06-05 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P164416 GPN Date: Project Name: Burundi Skills for Jobs: Women and Youth Project Loan / Credit No: IDA / V2370, IDA / D8580 Youth Skills and Job Creation Project Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BI-PACEJ-108280-GO-DIR / F Component 1: Improving La ourniture, installation et form IDA / V2370 bor-Market Orientation of Ski Post Direct Selection Direct 20,481.00 0.00 Canceled 2019-04-02 2019-10-15 2019-04-07 2019-04-12 2019-05-10 ation à l'utilisation du logiciel lls Development TOM2PRO Component 3: Reinforcing D BI-PACEJ-329926-GO-RFB / A ata Systems for Market-Orie Single Stage - One E Pending Impl cquisition des équipements IDA / D8580 Post Request for Bids Open - National 50,000.00 0.00 2022-12-08 2022-12-13 2023-01-24 2023-01-30 2023-02-15 2023-03-30 nted Skills Development, Pro nvelope ementation mobiliers pour le PACEJ ject Management, and Monit oring and Evalu ation BI-PACEJ-363908-GO-DIR / R ecrutement par entente direc Component 1: Improving La te de l'UNOPS pour la fournit Direct - Internation Pending Impl IDA / D8580 bor-Market Orientation of Ski Post Direct Selection 410,000.00 0.00 2023-05-31 2023-06-05 2023-07-10 2024-01-06 ure de quatre (04) Camionne al ementation lls Development ttes double cabines, Diesel, 4 x4 et trente (30) motos pour le PACEJ. Component 3: Reinforcing D BI-PACEJ-363974-GO-RFQ / A ata Systems for Market-Orie Request for Quota Single Stage - One E Pending Impl cquisition du mobilier de bur IDA / D8580 Post Limited 90,000.00 0.00 2023-06-10 2023-08-05 2024-02-01 nted Skills Development, Pro tions nvelope ementation eau du Projet PACEJ ject Management, and Monit oring and Evalu ation BI-PACEJ-363975-GO-RFQ / A Component 3: Reinforcing D cquisition des équipements i ata Systems for Market-Orie Request for Quota Single Stage - One E Pending Impl IDA / D8580 Post Limited 75,000.00 0.00 2023-06-12 2023-08-07 2024-02-03 nformatiques du Projet PACEJ nted Skills Development, Pro tions nvelope ementation . ject Management, and Monit oring and Evalu ation NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 3: Reinforcing D BI-PACEJ-140995-NC-DIR / A ata Systems for Market-Orie Under Imple cquisition et formation sur le IDA / V2370 Post Direct Selection Direct 20,481.00 0.00 2019-10-22 2019-10-28 2019-10-27 2019-11-19 2020-05-17 nted Skills Development, Pro mentation logiciel comptable TOM2PRO ject Management, and Monit oring and Evalu ation CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BI-PACEJ-108939-CS-QCBS / Component 1: Improving La Quality And Cost- Open - Internationa Etude de dimensionnement d IDA / V2370 bor-Market Orientation of Ski Post 250,000.00 0.00 Canceled 2019-04-26 2019-05-31 2019-05-10 2019-06-14 2019-06-17 2019-07-30 2019-08-15 2019-09-19 2019-10-24 2020-03-05 Based Selection l es besoins des centres sélect lls Development ionnés BI-PACEJ-117574-CS-QCBS / Component 1: Improving La Quality And Cost- Open - Internationa Under Implement Etude de Dimensionnement IDA / V2370 bor-Market Orientation of Ski Post 100,000.00 0.00 2019-06-14 2019-06-07 2019-06-21 2019-08-04 2019-09-04 2019-09-30 2019-11-04 2019-11-28 2020-03-10 Based Selection l ation des besoins des CEMs lls Development BI-PACEJ-282875-CS-QCBS / Component 3: Reinforcing D Recrutement d'un consultant ata Systems for Market-Orie Quality And Cost- Open - Internationa Under Implement pour l’évaluation de la situati IDA / D8580 nted Skills Development, Pro Post 50,000.00 0.00 2022-03-10 2022-04-28 2022-03-17 2022-04-30 2022-05-28 2022-06-13 2022-07-11 2022-08-01 2022-11-15 Based Selection l ation on dans le domaine du Genre ject Management, and Monit et des Violences Basées sur l oring and Evalu ation e Genre (VBG) BI-PACEJ-292840-CS-QCBS / Component 3: Reinforcing D - Recrutement d’une Firme ata Systems for Market-Orie Quality And Cost- Open - Internationa Under Implement Internationale pour faire la c IDA / D8580 nted Skills Development, Pro Post 100,000.00 0.00 2022-05-05 2022-04-29 2022-05-26 2022-10-05 2022-07-09 2022-08-06 2022-09-05 2022-10-10 2022-11-14 2023-02-28 Based Selection l ation artographie de l’écosystème ject Management, and Monit de l’entrepreneuriat des jeun oring and Evalu ation es au Burundi Component 3: Reinforcing D BI-PACEJ-315609-CS-QCBS / ata Systems for Market-Orie Quality And Cost- Open - Internationa Under Implement Recrutement d'un Fournisseu IDA / D8580 Prior 5,000,000.00 0.00 2022-09-19 2022-10-17 2022-10-10 2022-11-23 2022-12-21 2023-01-20 2023-02-24 2023-03-31 2024-03-30 nted Skills Development, Pro Based Selection l ation r de Services éducatifs ject Management, and Monit oring and Evalu ation BI-PACEJ-322985-CS-QCBS / Recrutement d'une firme inte rnationale pour l’implémenta Component 2: Fostering Entr Quality And Cost- Open - Internationa tion et la supervision des pro IDA / D8580 Prior 5,000,000.00 0.00 Canceled 2022-11-21 2022-12-12 2023-01-25 2023-02-22 2023-03-24 2023-04-28 2023-06-02 2026-06-30 epreneurship Based Selection l grammes de formation FIP et STEP, de networking et de m entorat, et d'accompagneme nt aux BDS BI-PACEJ-322986-CS-QCBS / Recrutement d'une firme inte rnationale pour la conception , l'implémentation et la super Component 2: Fostering Entr Quality And Cost- Open - Internationa Pending Impleme vision des COPA (30%) y com IDA / D8580 Prior 6,500,000.00 0.00 2022-11-25 2022-12-16 2023-01-29 2023-02-26 2023-03-28 2023-05-02 2023-06-06 2026-06-30 epreneurship Based Selection l ntation pris la distribution des subve ntions (au moins 4 000 new s tartups vont bénéficier d'un montant de subvention total de USD 4 100 000 Page 1 BI-PACEJ-322987-CS-QCBS / Recrutement d'une firme pou r une étude sur l'enteprenari at des femmes, et le dévelop Component 2: Fostering Entr Quality And Cost- Open - Internationa Pending Impleme IDA / D8580 Prior 1,000,000.00 0.00 2022-11-18 2022-12-09 2023-01-22 2023-02-19 2023-03-21 2023-04-25 2023-05-30 2024-05-29 pement et le pilotage d'une s epreneurship Based Selection l ntation tratégie numérique d'une ca mpagne de marketing social pour la promotion de entrepr eneuriat féminin BI-PACEJ-322989-CS-QCBS / Recrutement d'une firme pou Component 2: Fostering Entr Quality And Cost- Open - Internationa Pending Impleme IDA / D8580 Post 400,000.00 0.00 2022-11-11 2022-12-02 2023-01-15 2023-02-12 2023-03-14 2023-04-18 2023-05-23 2023-09-29 r une étude sur l'entrepreneu epreneurship Based Selection l ntation riat des réfugiés BI-PACEJ-322990-CS-QCBS / Recrutement d'un consultant pour la mise en place d'une p lateforme numérique d'écha Component 2: Fostering Entr Quality And Cost- Open - Internationa Pending Impleme nge et d'information pour les IDA / D8580 Prior 2,000,000.00 0.00 2022-11-10 2022-12-01 2023-01-14 2023-02-11 2023-03-13 2023-04-17 2023-05-22 2023-12-15 epreneurship Based Selection l ntation jeunes entrepreneurs, le dév eloppement des applications pour les bénéficiaires du proj et, soutien à la collecte de do nnées et mise en oeuvre BI-PACEJ-363907-CS-LCS / R Component 3: Reinforcing D ecrutement d'un Cabinet d'a ata Systems for Market-Orie Least Cost Selecti Open - Internationa Pending Impleme IDA / D8580 Post 40,000.00 0.00 2023-06-06 2023-06-27 2023-08-10 2023-09-07 2023-10-07 2023-11-11 2023-12-16 2024-06-13 udit financier pour les exerci nted Skills Development, Pro on l ntation ces 2022-2023 et 2023-2024 ject Management, and Monit du projet PACEJ. oring and Evalu ation BI-PACEJ-363999-CS-QCBS / Recrutement d'un Cabinet po ur le développement, la mise en œuvre et l'administration Component 2: Fostering Entr Quality And Cost- Open - Internationa Pending Impleme d'une plateforme électroniqu IDA / D8580 Post 200,000.00 0.00 2023-06-09 2023-06-30 2023-08-13 2023-09-10 2023-10-10 2023-11-14 2023-12-19 2024-12-18 epreneurship Based Selection l ntation e d'informations des jeunes s ur les opportunités et résulta ts de la formation et d'emploi et d'appui au dvpt d'initiativ es d'entrepreneuriat INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BI-PACEJ-102382-CS-INDV / Individual Consult IDA / V2370 Post Open 42,000.00 0.00 Canceled 2019-03-15 2019-10-15 2019-05-10 2019-05-31 2019-06-07 2021-06-06 Recruter un Coordonnateur ant Selection BI-PACEJ-102533-CS-INDV / Individual Consult Recrutement d'un spécialiste IDA / V2370 Post Open 36,000.00 0.00 Canceled 2019-03-15 2019-07-31 2019-05-03 2019-05-07 2019-05-24 2021-05-23 ant Selection en gestion financière BI-PACEJ-102538-CS-INDV / Individual Consult Recrutement d'un spécialiste IDA / V2370 Post Open 36,000.00 0.00 Canceled 2019-03-15 2019-07-31 2019-05-03 2019-05-07 2019-05-24 2021-05-23 ant Selection en suivi-évaluation BI-PACEJ-102542-CS-INDV / Individual Consult Recrutement d'un spécialiste IDA / V2370 Post Open 36,000.00 0.00 Canceled 2019-03-15 2019-07-31 2019-05-03 2019-05-24 2019-05-31 2021-05-30 ant Selection en passation des marchés BI-PACEJ-102546-CS-INDV / Component 1: Improving La Individual Consult Recrutement d'un spécialiste IDA / V2370 bor-Market Orientation of Ski Post Open 36,000.00 73,200.00 Signed 2019-03-15 2019-03-12 2019-05-03 2022-03-09 2019-05-24 2022-03-09 2019-05-31 2019-07-03 2021-05-30 ant Selection en ingénierie de formation lls Development BI-PACEJ-102562-CS-INDV / Recrutement d'un spécialiste Individual Consult IDA / V2370 Post Open 36,000.00 0.00 Canceled 2019-03-15 2019-07-31 2019-05-03 2019-05-24 2019-06-11 2021-06-10 en questions environnement ant Selection ales, sociales et genre BI-PACEJ-102566-CS-INDV / Individual Consult IDA / V2370 Post Open 24,000.00 0.00 Canceled 2019-03-15 2019-03-12 2019-05-03 2019-05-24 2019-06-13 2021-06-12 Recrutement d'un comptable ant Selection BI-PACEJ-102848-CS-INDV / Recrutement d'un Consultant Individual Consult Under Implement pour l'élaboration des docum IDA / V2370 Post Open 10,000.00 0.00 2019-02-27 2019-03-04 2019-03-22 2019-03-27 2019-03-29 2019-05-15 ant Selection ation ents de sauvegardes environ nementales et sociales BI-PACEJ-105956-CS-INDV / Recrutement d'un Consultant Individual Consult Under Implement pour l'élaboration du sous-m IDA / V2370 Post Open 30,000.00 0.00 2019-03-14 2019-04-04 2019-04-12 2023-03-12 2019-04-25 2023-03-12 2019-05-16 2019-07-16 ant Selection ation anuel sur les apprentissages et des supports de travail et f ormation des personnels. BI-PACEJ-105958-CS-INDV / Recrutement d'un Consultant Individual Consult Under Implement pour l'élaboration du sous-m IDA / V2370 Post Open 20,000.00 0.00 2019-03-14 2019-03-26 2019-04-12 2019-10-28 2019-05-02 2023-03-11 2019-05-23 2019-07-23 ant Selection ation anuel de la sous-composante développement de l'entrepre nariat. BI-PACEJ-105961-CS-INDV / Recrutement d'un Consultant Component 1: Improving La Individual Consult pour l'étude des dispositifs et IDA / V2370 bor-Market Orientation of Ski Post Open 20,000.00 37,720.00 Signed 2019-03-14 2019-03-29 2019-04-12 2020-02-11 2019-04-30 2020-02-11 2019-05-21 2019-07-11 2019-07-21 ant Selection des mécanismes d'insertion lls Development des jeunes et perspectives d e développement. BI-PACEJ-108935-CS-INDV / Etude d'évaluation et d'adapt Individual Consult Under Implement ation du cadre légal de l'Ense IDA / V2370 Post Open 25,000.00 0.00 2019-04-12 2019-05-31 2019-05-24 2019-06-07 2019-06-26 2019-08-30 ant Selection ation ignement Technique et Form ation Professionnelle (ETFP) BI-PACEJ-114305-CS-INDV / Component 3: Reinforcing D Recrutement d'un consultant ata Systems for Market-Orie Individual Consult Under Implement IDA / V2370 Post Open 25,000.00 0.00 2019-05-10 2019-05-09 2019-05-30 2019-06-04 2019-06-04 2019-06-14 pour l'élaboration de la strat nted Skills Development, Pro ant Selection ation égie de passation des march ject Management, and Monit és (PPSD) oring and Evalu ation BI-PACEJ-124382-CS-INDV / Component 2: Fostering Entr Individual Consult Under Implement Recrutement d'un Consultant IDA / V2370 Post Open 20,000.00 0.00 2019-07-29 2019-07-26 2019-09-09 2019-09-16 2019-10-01 2019-11-10 epreneurship ant Selection ation Expert en TICs Page 2 BI-PACEJ-125881-CS-INDV / Recrutement d'un consultant individuel chargé de réaliser Component 1: Improving La Individual Consult Pending Impleme une étude de dimensionnem IDA / V2370 bor-Market Orientation of Ski Post Open 50,000.00 0.00 2019-08-06 2019-09-27 2019-10-11 2019-10-25 2020-02-25 ant Selection ntation ent de la restructuration/mis lls Development e à niveau des instituts des t echniques agricoles de Karus i et Mahwa BI-PACEJ-127052-CS-INDV / Recrutement d'un consultant Component 1: Improving La Individual Consult Under Implement individuel chargé de l'étude IDA / V2370 bor-Market Orientation of Ski Post Open 25,500.00 0.00 2019-08-26 2019-08-16 2019-10-02 2019-10-16 2019-11-06 2020-03-06 ant Selection ation de dimensionnement des bes lls Development oins des CEMs Kinama, Muge rama et Karurama BI-PACEJ-127053-CS-INDV / Recrutement d'un consultant Component 1: Improving La Individual Consult Under Implement individuel pour réaliser l'étud IDA / V2370 bor-Market Orientation of Ski Post Open 25,500.00 0.00 2019-08-26 2019-08-16 2019-10-02 2019-10-16 2019-11-06 2020-03-06 ant Selection ation e de dimensionnement des b lls Development esoins des CEMs Bwoga, Ngo zi, Muyinga BI-PACEJ-127056-CS-INDV / Recrutement d'un consultant Component 1: Improving La Individual Consult Under Implement individuel pour réaliser une é IDA / V2370 bor-Market Orientation of Ski Post Open 25,500.00 0.00 2019-08-26 2019-08-16 2019-10-07 2019-10-21 2019-11-11 2020-03-11 ant Selection ation tude de dimensionnement de lls Development s besoins des CEMs Rugazi, Gasaka et Gikomeye BI-PACEJ-127059-CS-INDV / Recrutement d'un consultant Component 1: Improving La Individual Consult Under Implement individuel pour réaliser une é IDA / V2370 bor-Market Orientation of Ski Post Open 25,500.00 0.00 2019-08-26 2019-08-16 2019-10-14 2019-10-28 2019-11-18 2020-03-18 ant Selection ation tude de dimensionnement de lls Development s besoins des CEMs Bwagiriz a, Rutoke et Vyerwa BI-PACEJ-195037-CS-CDS / E Component 3: Reinforcing D ntente Directe avec le burea ata Systems for Market-Orie u IAC pour l'audit comptable IDA / V2370 nted Skills Development, Pro Post Direct Selection Direct 15,000.00 7,216.25 Signed 2020-09-21 2020-09-21 2020-10-01 2021-09-22 2020-11-14 2020-11-03 2020-12-21 et financier du PACEJ pour la ject Management, and Monit période de Juillet 2019 à Juin oring and Evalu ation 2020 BI-PACEJ-222263-CS-CDS / E Component 3: Reinforcing D ntente Directe avec le cabine ata Systems for Market-Orie Under Implement t IAC pour l'audit comptable IDA / V2370 nted Skills Development, Pro Post Direct Selection Direct 20,000.00 0.00 2021-03-10 2021-05-11 2021-03-20 2021-09-20 2021-05-24 2021-11-20 ation et financier du projet pour la ject Management, and Monit période allant du 01/07/2020 oring and Evalu ation au 31/07/2021 BI-PACEJ-227613-CS-INDV / Recrutement d'un Consultant Component 1: Improving La Individual Consult international pour le dévelop IDA / V2370 bor-Market Orientation of Ski Post Open 54,000.00 0.00 Canceled 2021-04-06 2021-04-17 2021-04-25 2021-04-27 2021-04-29 2021-08-05 ant Selection pement institutionnel de l'ins lls Development titut des TIC à l'université du Burundi BI-PACEJ-227615-CS-INDV / Recrutement d'un Consultant Component 1: Improving La international sur les compéte Individual Consult IDA / V2370 bor-Market Orientation of Ski Post Open 54,000.00 0.00 Canceled 2021-04-06 2021-04-17 2021-04-28 2021-05-03 2021-05-06 2021-08-11 nces numériques modernes e ant Selection lls Development t les programmes universitair es de transformation numéri que BI-PACEJ-227618-CS-INDV / Component 1: Improving La Recrutement d'un Consultant Individual Consult IDA / V2370 bor-Market Orientation of Ski Post Open 36,000.00 0.00 Canceled 2021-04-06 2021-04-17 2021-04-28 2021-05-05 2021-05-10 2021-08-17 national pour le développem ant Selection lls Development ent de l'institut de transform ation numérique BI-PACEJ-227619-CS-INDV / Recrutement d'un Consultant pour réalisation de l'étude d'i Component 1: Improving La dentification des principaux Individual Consult Under Implement IDA / V2370 bor-Market Orientation of Ski Post Open 36,000.00 0.00 2021-04-16 2021-11-05 2021-05-17 2021-05-25 2021-06-04 2021-12-01 domaines de formation pour l ant Selection ation lls Development 'apprentissage pratique, en f onction des spécificités local es des zones urbaines et rura les et de la demande existan te BI-PACEJ-227622-CS-INDV / Recrutement d'un Consultant pour réalisation de l'étude de Component 1: Improving La définition des outils et des su Individual Consult Pending Impleme IDA / V2370 bor-Market Orientation of Ski Post Open 36,000.00 0.00 2021-04-21 2021-05-12 2021-05-19 2021-05-28 2021-11-24 pports nécessaires au bon fo ant Selection ntation lls Development nctionnement et mise en pla ce d'un cadre national de cer tification et de pilotage du pr ogramme d’apprentissage BI-PACEJ-227623-CS-INDV / I Component 1: Improving La Individual Consult Pending Impleme dentification des centres (10 IDA / V2370 bor-Market Orientation of Ski Post Open 27,000.00 0.00 2021-04-15 2021-05-10 2021-05-24 2021-06-09 2021-09-16 ant Selection ntation 0) bénéficiaires directs du Pr lls Development ojet Component 3: Reinforcing D BI-PACEJ-227627-CS-INDV / ata Systems for Market-Orie Individual Consult Under Implement Recrutement d'un Coordonna IDA / V2370 Post Open 48,000.00 0.00 2021-04-15 2021-05-12 2021-05-16 2023-03-12 2021-05-21 2023-03-12 2021-08-31 2022-08-30 nted Skills Development, Pro ant Selection ation teur du Projet ject Management, and Monit oring and Evalu ation BI-PACEJ-227628-CS-INDV / Component 3: Reinforcing D Recrutement d'un Responsab ata Systems for Market-Orie Individual Consult Under Implement IDA / V2370 Post Open 40,800.00 0.00 2021-04-15 2021-05-12 2021-05-10 2023-03-12 2021-05-24 2023-03-12 2021-08-31 2022-08-30 le Administratif et Financier d nted Skills Development, Pro ant Selection ation u Projet ject Management, and Monit oring and Evalu ation BI-PACEJ-227677-CS-INDV / Component 3: Reinforcing D Recrutement d'un Responsab ata Systems for Market-Orie Individual Consult Under Implement IDA / V2370 Post Open 37,200.00 0.00 2021-04-14 2022-07-25 2021-05-05 2023-03-11 2021-05-14 2021-08-30 2022-08-29 le de la Passation des Marché nted Skills Development, Pro ant Selection ation s ject Management, and Monit oring and Evalu ation BI-PACEJ-227679-CS-INDV / Component 3: Reinforcing D Recrutement d'un Responsab ata Systems for Market-Orie Individual Consult Under Implement IDA / V2370 Post Open 37,200.00 0.00 2021-04-21 2021-06-10 2021-05-10 2021-05-16 2021-09-01 2022-08-31 le des Sauvegardes Environn nted Skills Development, Pro ant Selection ation ementales et Sociales du Proj ject Management, and Monit et oring and Evalu ation Component 3: Reinforcing D BI-PACEJ-227683-CS-INDV / ata Systems for Market-Orie Individual Consult Under Implement Recrutement d'un Comptable IDA / V2370 Post Open 24,000.00 0.00 2021-04-23 2021-05-12 2021-05-19 2021-05-28 2021-08-31 2022-08-30 nted Skills Development, Pro ant Selection ation du Projet ject Management, and Monit oring and Evalu ation Component 3: Reinforcing D BI-PACEJ-227686-CS-INDV / ata Systems for Market-Orie Individual Consult Under Implement Recrutement d'un Auditeur in IDA / V2370 Post Open 37,200.00 0.00 2021-04-23 2021-06-04 2021-06-03 2021-06-17 2021-09-03 2022-09-01 nted Skills Development, Pro ant Selection ation terne du Projet ject Management, and Monit oring and Evalu ation Page 3 Component 3: Reinforcing D BI-PACEJ-227736-CS-INDV / ata Systems for Market-Orie Individual Consult Pending Impleme Recrutement d'un aide comp IDA / V2370 Post Open 18,000.00 0.00 2021-04-21 2021-06-02 2021-06-14 2021-09-01 2022-08-31 nted Skills Development, Pro ant Selection ntation table du Projet ject Management, and Monit oring and Evalu ation Component 3: Reinforcing D BI-PACEJ-227849-CS-INDV / ata Systems for Market-Orie Individual Consult Under Implement Recrutement d'un Responsab IDA / V2370 Post Open 37,200.00 0.00 2021-04-14 2021-05-12 2021-06-02 2021-06-23 2021-08-31 2022-08-30 nted Skills Development, Pro ant Selection ation le du Suivi Evaluation ject Management, and Monit oring and Evalu ation BI-PACEJ-230479-CS-INDV / Component 3: Reinforcing D Recrutement d'un consultant ata Systems for Market-Orie Individual Consult IDA / V2370 Post Limited 36,000.00 19,598.67 Signed 2021-04-21 2021-04-21 2021-04-26 2021-09-22 2021-05-17 2021-11-05 2021-06-07 2021-10-12 2021-09-15 national pour le développem nted Skills Development, Pro ant Selection ent de l'Institut de transform ject Management, and Monit ations numériques oring and Evalu ation BI-PACEJ-230485-CS-INDV / Component 3: Reinforcing D Recrutement d'un consultant ata Systems for Market-Orie Individual Consult international sur les compéte IDA / V2370 nted Skills Development, Pro Post Limited 54,000.00 75,600.00 Signed 2021-04-21 2021-04-21 2021-04-26 2021-09-22 2021-05-17 2021-11-05 2021-06-07 2021-10-12 2021-09-16 ant Selection nces numériques et les progr ject Management, and Monit ammes universitaires de tran oring and Evalu ation sformation numérique BI-PACEJ-230490-CS-INDV / Component 3: Reinforcing D Recrutement d'un consultant ata Systems for Market-Orie Individual Consult international pour le dévelop IDA / V2370 nted Skills Development, Pro Post Limited 54,000.00 105,000.00 Signed 2021-04-21 2021-04-21 2021-04-26 2021-09-22 2021-05-17 2021-11-05 2021-06-07 2021-10-12 2021-09-17 ant Selection pement institutionnel de l'Ins ject Management, and Monit titut des TIC à l'Université du oring and Evalu ation Burundi BI-PACEJ-231460-CS-CDS / E Component 3: Reinforcing D ntente Directe avec Madame ata Systems for Market-Orie IDA / V2370 Post Direct Selection Direct 10,000.00 4,530.00 Signed 2021-04-27 2021-04-27 2021-04-28 2021-09-22 2021-04-28 2021-06-16 2021-05-10 Rym GHAZZALI pour l'actuali nted Skills Development, Pro sation de la PPSD du PACEJ ject Management, and Monit oring and Evalu ation BI-PACEJ-238681-CS-INDV / Component 3: Reinforcing D Recrutement d'un 2ième spé ata Systems for Market-Orie Individual Consult IDA / V2370 Post Open 24,000.00 0.00 Canceled 2021-07-15 2021-06-11 2021-09-02 2021-09-23 2021-10-28 2022-10-28 cialiste en ingénierie de form nted Skills Development, Pro ant Selection ation ject Management, and Monit oring and Evalu ation BI-PACEJ-238684-CS-INDV / Component 3: Reinforcing D Recrutement d'un spécialiste ata Systems for Market-Orie Individual Consult Under Implement IDA / V2370 Post Open 24,000.00 0.00 2021-07-15 2021-06-11 2021-09-02 2021-09-23 2021-10-28 2022-10-28 en sauvegardes sociales et g nted Skills Development, Pro ant Selection ation enre ject Management, and Monit oring and Evalu ation BI-PACEJ-108993-CS-INDV / Elaboration du manuel des pr Individual Consult IDA / V2370 Post Open 20,000.00 0.00 Canceled 2019-04-19 2021-09-18 2019-06-07 2019-06-21 2019-07-19 2019-08-30 océdures administratives et f ant Selection inancières du Projet BI-PACEJ-258872-CS-CDS / E Component 3: Reinforcing D ntente Directe avec le Consul ata Systems for Market-Orie Under Implement tant Monsieur Scarie NIVYINT IDA / V2370 nted Skills Development, Pro Post Direct Selection Direct 40,000.00 0.00 2021-11-03 2021-11-02 2021-11-07 2023-03-11 2021-11-21 2021-12-19 ation IZO pour l'élaboration des m ject Management, and Monit anuels des procédures et de oring and Evalu ation mise en oeuvre du PACEJ Component 3: Reinforcing D BI-PACEJ-261320-CS-INDV / ata Systems for Market-Orie Individual Consult Under Implement Recrutement d'un Spécialiste IDA / V2370 Post Open 24,000.00 0.00 2021-11-05 2021-11-10 2021-12-08 2023-03-11 2021-12-31 2022-01-14 2023-01-13 nted Skills Development, Pro ant Selection ation en entrepreneuriat ject Management, and Monit oring and Evalu ation BI-PACEJ-297885-CS-CDS / E ntente Directe avec Madame Diane MPINGANZIMA pour la Component 1: Improving La Under Implement Préparation d´une Évaluation IDA / D8580 bor-Market Orientation of Ski Post Direct Selection Direct - National 50,000.00 0.00 2022-07-29 2022-09-29 2022-08-08 2022-10-12 2022-12-16 ation Sociale et une Evaluation de l lls Development a situation dans le domaine d u Genre et des Violences Bas ées sur le Genre BI-PACEJ-305864-CS-CDS / E Component 3: Reinforcing D ntente Directe avec le burea ata Systems for Market-Orie Direct - Internation Under Implement IDA / D8580 Post Direct Selection 15,000.00 0.00 2022-07-29 2022-08-23 2022-08-08 2022-09-28 2022-10-12 2022-11-22 u IAC pour l'audit du dernier nted Skills Development, Pro al ation exercice du PPA du 01/07/20 ject Management, and Monit 21 au 30/06/2022 oring and Evalu ation BI-PACEJ-322983-CS-CDS / E ntente Directe avec la firme Component 2: Fostering Entr Direct - Internation Under Implement MOVE pour le développemen IDA / D8580 Post Direct Selection 600,000.00 0.00 2022-11-15 2023-01-19 2022-11-25 2023-01-29 2024-08-15 epreneurship al ation t de la méthodologie et la for mation des formateurs FIP et STEP BI-PACEJ-127063-CS-INDV / Recrutement d'un consultant individuel chargé de réaliser Component 1: Improving La Individual Consult une étude de dimensionnem IDA / V2370 bor-Market Orientation of Ski Post Open 100,000.00 0.00 Canceled 2019-08-23 2019-08-14 2019-10-04 2019-10-28 2019-10-18 2019-11-08 2020-03-09 ant Selection ent de la restructuration/mis lls Development e à niveau des instituts techn iques agricoles de Karusi et Mahwa BI-PACEJ-125873-CS-INDV / Recrutement d'un consultant Component 1: Improving La individuel chargé de réaliser Individual Consult IDA / V2370 bor-Market Orientation of Ski Post Open 50,000.00 0.00 Canceled 2019-08-04 2019-08-14 2019-09-10 2019-10-28 2019-10-07 2019-11-11 2020-03-11 une étude de dimensionnem ant Selection lls Development ent de la restructuration/mis e à niveau du centre de form ation professionnelle Rumon ge BI-PACEJ-125845-CS-INDV / Recrutement d'un Consultant Component 1: Improving La chargé de réaliser une de di Individual Consult IDA / V2370 bor-Market Orientation of Ski Post Open 50,000.00 0.00 Canceled 2019-08-04 2019-08-14 2019-09-04 2019-09-16 2019-10-07 2020-02-07 mensionnement de la restruc ant Selection lls Development turation/mise à niveau du ce ntre de formation profession nelle (CFP) Kigobe BI-PACEJ-125888-CS-INDV / Recrutement d'un consultant Component 1: Improving La individuel chargé de réaliser Individual Consult IDA / V2370 bor-Market Orientation of Ski Post Open 50,000.00 0.00 Canceled 2019-08-06 2019-08-14 2019-10-04 2019-10-18 2019-11-04 2020-03-02 une étude de dimensionnem ant Selection lls Development ent de la restructuration/mis e à niveau de l'école des trav aux publics de Gitega BI-PACEJ-356663-CS-INDV / Component 3: Reinforcing D Recrutement d'un (e) Spécial ata Systems for Market-Orie Individual Consult Under Implement IDA / D8580 Post Limited 23,152.82 0.00 2023-05-15 2023-05-15 2023-05-20 2023-06-10 2023-07-15 2024-01-11 iste en sauvegarde environn nted Skills Development, Pro ant Selection ation ementale. ject Management, and Monit oring and Evalu ation BI-PACEJ-356664-CS-INDV / Component 3: Reinforcing D Recrutement d'un (e) Spécial ata Systems for Market-Orie Individual Consult Under Implement IDA / D8580 Post Limited 23,152.82 0.00 2023-05-15 2023-05-15 2023-05-20 2023-06-10 2023-07-15 2024-01-11 iste en sauvegarde sociale et nted Skills Development, Pro ant Selection ation genre. ject Management, and Monit oring and Evalu ation Page 4 Component 3: Reinforcing D BI-PACEJ-363901-CS-INDV / ata Systems for Market-Orie Individual Consult Recrutement d'un Comptable IDA / D8580 Post Open - National 11,100.00 0.00 Under Review 2023-06-08 2023-06-19 2023-07-27 2023-08-17 2023-09-21 2024-03-19 nted Skills Development, Pro ant Selection N°2 (H/F) du Projet PACEJ ject Management, and Monit oring and Evalu ation BI-PACEJ-363903-CS-INDV / Component 3: Reinforcing D Recrutement d'un Consultant ata Systems for Market-Orie Individual Consult IDA / D8580 Post Open - National 24,000.00 0.00 Under Review 2023-05-31 2023-06-19 2023-07-19 2023-08-09 2023-09-13 2024-03-11 Individuel (H/F) en Communic nted Skills Development, Pro ant Selection ation du Projet PACEJ ject Management, and Monit oring and Evalu ation Page 5 PROCUREMENT PLAN Project information: Argentina- Strengthening the Digital Health Agenda in the Province of Buenos Aires (P179534) Status: Pipeline Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. PROCUREMENT Argentina : Strengthening the Digital Health Agenda in the Province of Buenos Aires PLAN General Information Country: Argentina 2023-03-13 Bank’s Approval Date of the Original Procurement Plan: 2023-06-05 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P179534 GPN Date: Project Name: Strengthening the Digital Health Agenda in the Province of Buenos Aires Loan / Credit No: / Provincial Directorate of Multilateral Organizations and Bilateral Financing Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Strengthening the Implemen AR-DPOMFB-348025-GO-RFB tation of Electronic Medical Single Stage - One E Pending Impl / Adquisición de servidores y / Post Request for Bids Open - National 500,000.00 0.00 2023-03-27 2023-04-01 2023-05-13 2023-06-12 2023-07-17 2023-11-14 Records (EMRs) / Integrated nvelope ementation licencias de base de datos Health Record (IHR) in public health fa cilities Strengthening the Implemen AR-DPOMFB-348022-GO-RFB tation of Electronic Medical Open - Internationa Single Stage - One E Under Imple / Adquisición de Equipamient / Prior Request for Bids 8,751,660.00 0.00 2023-03-15 2023-03-20 2023-05-01 2023-05-31 2023-07-05 2024-01-01 Records (EMRs) / Integrated l nvelope mentation o Informático Health Record (IHR) in public health fa cilities NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 1 PROCUREMENT PLAN (Textual Part) Project information: Tuvalu Maritime Investment in Climate Resilient Operations Project Implementation agency: The Ministry of Communications and Transport (MCT) Date of the Procurement Plan: 18 Nov. 2018 Period covered by this Procurement Plan: from 2018 to 2020 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. At this stage, no contracts are expected to be procured by approaching the national market. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Not Applicable. Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – Not Applicable. Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works) – not applicable. PROCUREMENT Tuvalu : Maritime Investment in Climate Resilient Operations PLAN General Information Country: Tuvalu 2019-01-22 Bank’s Approval Date of the Original Procurement Plan: 2023-06-06 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P161540 GPN Date: Project Name: Maritime Investment in Climate Resilient Operations Loan / Credit No: IDA / V0750, IDA / D4100 Ministry of Public Works, Infrastructure, Environment, Labour, Metrology and Disaster. Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned TV-MOCT-86551-CW-RFB / M Component 2: Climate Resili Open - Internationa Single Stage - One E 15,000,000.0 2020-09-2 aritime Infrastructure and Eq IDA / V0750 ent Maritime Infrastructure S Prior Request for Bids 0.00 Canceled 2019-08-01 2019-08-31 2019-10-12 2019-10-20 2019-11-03 l nvelope 0 7 uipment on Nanumaga olutions MCT-MICW-004 / Infrastructu Component 2: Climate Resili Open - Internationa Single Stage - One E 2019-12-0 re Investments and Operatio IDA / V0750 ent Maritime Infrastructure S Prior Request for Bids 3,500,000.00 0.00 Canceled 2019-02-25 2019-03-02 2019-04-01 2019-05-01 2019-06-05 l nvelope 2 nal Equipment on Funafuti olutions Request for Bids - TV-MOCT-135093-CW-RFB / Component 2: Climate Resili Open - Internationa Single Stage - One E Works (without pr 18,500,000.0 2020-08-1 Maritime Investments (works IDA / V0750 ent Maritime Infrastructure S Prior Request for Bids 0.00 Canceled 2019-10-10 2019-10-15 2019-12-14 2020-01-13 2020-02-17 l nvelope equalification) SP 0 5 and equipment) in Nanumag olutions D a and Funafuti TV-MPWIELMD-246360-CW-R FB / Works for improvement of the Funafuti Port yard, incl uding, Request for Bids - Component 2: Climate Resili 1) Paving of 6,000 sq. meters Open - Internationa Single Stage - One E Small Works SPD 2022-05-1 IDA / D4100 ent Maritime Infrastructure S Prior Request for Bids 3,500,000.00 0.00 Canceled 2021-07-30 2021-10-26 2021-08-04 2021-10-27 2021-09-15 2021-12-13 2021-10-15 2022-03-02 2021-11-19 at the container cargo yard l nvelope (1 envelope proce 8 olutions 2) Improvements to existing ss) warehouse 3) Improvement of lighting s ystem with the use of LED la mps and introduction of solar panels, TV-MPWIELMD-294783-CW-R FP / Works for Improvement of the Funafuti Port Yard incl Request for Bids - uding; 1) Paving of 6000aq m Component 2: Climate Resili Open - Internationa Single Stage - Two E Small Works SPD 2023-04-1 eters at the container cargo IDA / D4100 ent Maritime Infrastructure S Prior Request for Bids 7,000,000.00 0.00 Canceled 2022-05-13 2022-05-23 2022-05-18 2022-05-31 2022-06-29 2022-08-18 2022-10-16 l nvelope (2 envelope proce 4 yard. 2) Improvements to exi olutions ss) sting warehouse. 3) Improve ment of lighting system with the use of LED lamps and intr oduction of solar panels National Procure TV-MPWIELMD-368097-CW- Component 2: Climate Resili ment Document - Direct - Internation Pending Imp 2024-02-0 DIR / Funafuti Wharf Paveme IDA / D4100 ent Maritime Infrastructure S Prior Direct Selection 1 Envelope proce 3,500,000.00 0.00 2023-07-03 2023-07-08 2023-08-12 al lementation 8 nt Reconstruction and Buildin olutions ss (Non Bank-SPD g Works in Tuvalu ) GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TV-MOCT-86566-GO-RFQ / O Component 3: Strengthening Request for Quota Single Stage - One E IDA / V0750 Post Open - National 100,000.00 0.00 Canceled 2019-04-10 2019-06-05 2019-12-02 ffice Equipment / Supplies the Enabling Envrionment tions nvelope TV-MPWIELMD-226326-GO-U Component 4: Contingency UN Agencies (Dire N / CERC: "Medical Equipmen IDA / D4100 Prior Direct 1,600,000.00 1,600,000.00 Signed 2021-04-01 2021-05-11 2021-04-06 2021-05-19 2021-05-13 2021-05-30 2021-11-09 Emergency Response ct) t and Supply" NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MCT-MICCS-006 / Supervisio Component 3: Strengthening Quality And Cost- Open - Internationa IDA / V0750 Prior 1,000,000.00 0.00 Canceled 2019-03-31 2019-09-03 2019-04-10 2020-03-22 2019-06-19 2021-03-02 2019-07-17 2019-08-14 2019-09-25 2019-10-16 2020-10-15 n Services the Enabling Envrionment Based Selection l INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MCT-MICCS-001 / GIS Based Component 1: Sectoral and Individual Consult IDA / V0750 Post Open 30,000.00 30,000.00 Signed 2019-03-31 2020-08-20 2019-05-19 2020-11-26 2019-06-09 2021-02-24 2019-07-14 2021-03-06 2020-01-10 Mapping Spatial Planning Tools ant Selection TV-MOCT-86548-CS-INDV / H Component 1: Sectoral and Individual Consult IDA / V0750 Post Open 20,000.00 19,402.00 Signed 2019-03-31 2020-08-20 2019-05-19 2020-12-11 2019-06-09 2020-12-20 2019-07-14 2021-01-09 2020-01-10 ealth Outreach Campaign Spatial Planning Tools ant Selection MCT-MICCS-007 / Maritime A Component 3: Strengthening Individual Consult IDA / V0750 Post Open 200,000.00 200,000.00 Signed 2019-03-31 2021-02-17 2019-05-19 2021-05-21 2019-06-09 2021-08-03 2019-07-22 2021-08-15 2020-01-18 dvisor the Enabling Envrionment ant Selection TV-MOCT-97196-CS-INDV / P rocurement Specialist to Ass ist the client to update the ex Component 1: Sectoral and Individual Consult isting procurement plan. Ass IDA / D4100 Post Open 100,000.00 234,795.00 Completed 2019-01-29 2018-08-06 2019-02-18 2019-04-01 2019-02-21 2019-05-23 2019-03-08 2019-05-31 2024-03-20 2023-01-02 Spatial Planning Tools ant Selection ist the PMU to plan procurem ent activities over the anticip ated duration of the Project (i .e., the next 5 years). Page 1 TV-MOCT-105461-CS-INDV / Office Clerk, responsible for p erforming clerical and admini Component 1: Sectoral and Individual Consult strative duties in the PMU offi IDA / D4100 Post Open 60,000.00 21,624.37 Signed 2019-03-12 2019-12-04 2019-04-10 2020-04-22 2019-05-01 2020-05-11 2019-05-24 2020-05-16 2019-11-20 Spatial Planning Tools ant Selection ce setting. Assists Project Ma nagers by sorting mail, filing, answering phones, greeting c lients, scheduling meetings, etc... TV-MOCT-96580-CS-INDV / P Component 4: Contingency Individual Consult IDA / V0750 Post Direct 275,000.00 41,697.60 Completed 2019-12-04 2020-09-24 2019-12-14 2018-10-01 2020-01-04 2018-10-01 2020-02-08 2019-10-05 2020-08-06 2021-06-04 roject Manager Emergency Response ant Selection TV-MOCT-148299-CS-INDV / Component 1: Sectoral and Individual Consult Update of the ESIA and ESMP IDA / D4100 Post Direct 15,400.00 123,350.00 Completed 2019-12-06 2019-12-17 2019-12-08 2019-12-17 2019-12-09 2019-12-19 2019-12-31 2019-12-24 2020-06-28 2022-04-04 Spatial Planning Tools ant Selection for works under MICRO TV-MOCT-210628-CS-CDS / MICRO project accountant pa Component 3: Strengthening IDA / D4100 Post Direct Selection Direct 10,834.00 0.00 Canceled 2020-12-17 2021-01-04 2021-02-04 2021-04-01 2022-04-01 rt-time contract (8 working d the Enabling Envrionment ay a month) for two years TV-MPWIELMD-235853-CS-IN Component 3: Strengthening Individual Consult IDA / D4100 Post Limited 55,000.00 39,814.50 Signed 2021-05-23 2021-06-01 2021-05-28 2021-07-11 2021-06-18 2021-09-20 2021-07-01 2021-10-09 2022-06-30 DV / Project Manager the Enabling Envrionment ant Selection TV-MPWIELMD-246463-CS-C DS / Supervision of Works at Component 3: Strengthening Under Implement IDA / D4100 Post Direct Selection Direct 220,000.00 0.00 2021-08-10 2021-11-04 2021-08-20 2021-11-28 2021-10-24 2022-04-22 Funafuti wharf to be Directly the Enabling Envrionment ation Contracted with the firm GH D TV-MOCT-213798-CS-CDS / Component 3: Strengthening MICRO Project Accountant Pa IDA / D4100 Post Direct Selection Direct 10,834.00 0.00 Canceled 2021-01-14 2021-04-01 2021-01-24 2021-03-30 2021-09-26 the Enabling Envrionment rt-Time COntract ( 8 working days a month) TV-MOCT-128785-CS-INDV / Component 3: Strengthening Individual Consult SAFEGUARDS AND MONITORI IDA / D4100 Post Open 200,000.00 0.00 Canceled 2019-08-22 2021-03-16 2019-10-10 2019-10-31 2019-12-05 2020-06-02 the Enabling Envrionment ant Selection NG AND EVALUATION SPECIA LIST TV-MOCT-220155-CS-INDV / Component 3: Strengthening Individual Consult TECHNICAL ADVISOR -CONTR IDA / D4100 Post Open 100,000.00 0.00 Canceled 2021-02-17 2021-04-13 2021-04-07 2021-04-28 2021-06-02 2021-11-29 the Enabling Envrionment ant Selection ACT MANAGEMENT SPECIALI ST MCT-MICCS-008 / GBV,VAC a Component 3: Strengthening Individual Consult IDA / V0750 Post Open 100,000.00 0.00 Canceled 2019-03-31 2021-03-24 2019-05-19 2019-06-09 2019-07-14 2020-01-10 nd Trafficking Strategy the Enabling Envrionment ant Selection TV-MPWIELMD-360540-CS-IN Component 3: Strengthening Individual Consult Pending Impleme IDA / D4100 Post Direct - National 65,000.00 0.00 2023-05-15 2023-05-25 2023-06-15 2023-07-20 2024-01-16 DV / Project Accountant the Enabling Envrionment ant Selection ntation Page 2 PROCUREMENT PLAN (Textual Part) Project information: FYR of Macedonia Project Implementation agency: Ministry of Labor and Social Policy Date of the Procurement Plan: October 2018 Period covered by this Procurement Plan: Duration of the Project Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. PROCUREMENT North Macedonia : Social Services Improvement Project PLAN General Information Country: North Macedonia 2018-10-22 Bank’s Approval Date of the Original Procurement Plan: 2023-06-07 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P162246 GPN Date: 2018-09-18 Project Name: Social Services Improvement Project Loan / Credit No: / , IBRD / 89020 Ministry of Labor and Social Policy Executing Agency(ies): WORKS Activity Reference No. / Procureme Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH Ri Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method nt Docume ount (US$ and Recommendation Signed Contract o. h cess (Y/N) sk atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion nt Type ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MK-MLSP-72220-CW-RFB-13 1. Promoting social inclusi 4 / Renovation of MLSP, SWC on through improved access Single Stage - One E 2020-04-2 / Prior Request for Bids Open - National 0.00 Canceled 2019-08-01 2019-08-31 2019-10-05 2019-10-22 2019-10-30 s, Municipalities, NEA and oth to social benefits and servic nvelope 7 er institutions included in the es SP system MK-MLSP-96745-CW-RFB-13 1. Promoting social inclusi Request for Quota Single Stage - One E Pending Imp 2019-09-3 13 / Renovation of local offic IBRD / 89020 on through improved access Post Open - National 0.00 2019-02-06 2019-04-03 tions nvelope lementation 0 es to social benefits and servic es MK-MLSP-122572-CW-RFB-T 2. Expanding the access to Single Stage - One E 2021-02-2 RANSFERS-2.1.1 / Civil works IBRD / 89020 and improving of the quality Prior Request for Bids Open - National 850,675.56 Signed 2019-07-14 2019-08-01 2019-08-13 2019-09-17 2019-10-04 2019-10-07 2019-12-11 2019-10-29 2020-01-03 nvelope 0 -Kindergarten in Kavadarci of preschool services MK-MLSP-123252-CW-RFB-T 2. Expanding the access to Single Stage - One E 1,237,887.3 2021-02-2 RANSFERS-2.1.1.2 / Civil wor IBRD / 89020 and improving of the quality Post Request for Bids Open - National Signed 2019-07-19 2019-09-20 2019-08-18 2019-09-22 2019-11-05 2019-10-12 2019-12-10 2019-11-06 2020-01-02 nvelope 5 8 ks-Kindergarten in Negotino of preschool services MK-MLSP-123255-CW-RFB-T 2. Expanding the access to Single Stage - One E 2021-03-0 RANSFERS-2.1.1.3 / Civil wor IBRD / 89020 and improving of the quality Post Request for Bids Open - National 934,707.05 Signed 2019-07-21 2019-10-01 2019-08-20 2019-09-24 2019-11-21 2019-10-14 2019-12-10 2019-11-08 2020-01-03 nvelope 2 ks-Kindergarten in Kocani of preschool services MK-MLSP-123257-CW-RFB-T 2. Expanding the access to Single Stage - One E 2019-11-1 RANSFERS-2.1.1.4 / Civil wor IBRD / 89020 and improving of the quality Post Request for Bids Open - National 698,448.30 Signed 2019-07-25 2019-09-27 2019-08-24 2019-09-28 2019-11-15 2019-10-18 2019-12-09 2019-11-12 2020-01-04 nvelope 5 ks-Kindergarten in Kisela Vod of preschool services a MK-MLSP-129124-CW-RFQ-1 1. Promoting social inclusi 315 / Renovation of part of th on through improved access Request for Quota Single Stage - One E 2019-12-2 e Special Institution Demir Ka IBRD / 89020 Post Open - National 0.00 Canceled 2019-09-15 2019-10-11 to social benefits and servic tions nvelope 0 pija and part of the Public Ins es titution for rehabilitation of c hildren and youth MK-MLSP-142028-CW-RFB-2. 2. Expanding the access to Single Stage - One E 2021-06-2 1.1.5 / Civil works-Kindergart IBRD / 89020 and improving of the quality Post Request for Bids Open - National 365,321.40 Signed 2019-10-25 2020-07-10 2019-11-14 2019-12-29 2020-08-25 2020-01-18 2020-09-22 2020-03-06 2020-10-21 nvelope 9 en in Kriva Palanka of preschool services MK-MLSP-142030-CW-RFB-2. 2. Expanding the access to Single Stage - One E 1,553,358.1 2021-06-2 1.1.6 / Civil works-Kindergart IBRD / 89020 and improving of the quality Post Request for Bids Open - National Signed 2019-10-25 2019-10-31 2019-11-14 2019-12-29 2019-12-17 2020-01-18 2019-12-15 2020-03-06 2020-01-18 nvelope 4 9 en in Gjorce Petrov of preschool services MK-MLSP-142033-CW-RFQ-2. 2. Expanding the access to Request for Quota Single Stage - One E 2020-08-0 1.1.7 / Civil works-Kindergart IBRD / 89020 and improving of the quality Post Open - National 187,925.59 Signed 2019-11-14 2020-02-11 2019-12-22 tions nvelope 9 en in Bogovinje of preschool services MK-MLSP-142036-CW-RFB-2. 2. Expanding the access to Single Stage - One E 2021-06-2 1.1.8 / Civil works-Kindergart IBRD / 89020 and improving of the quality Post Request for Bids Open - National 404,688.09 Signed 2019-10-25 2019-12-13 2019-11-14 2019-12-29 2019-12-16 2020-01-18 2019-12-13 2020-03-06 2020-01-02 nvelope 9 en in Resen of preschool services MK-MLSP-142040-CW-RFB-2. 2. Expanding the access to Single Stage - One E 1,945,032.9 2021-06-2 1.1.9 / Civil works-Kindergart IBRD / 89020 and improving of the quality Post Request for Bids Open - National Signed 2019-10-25 2019-10-29 2019-11-14 2019-12-29 2019-12-13 2020-01-18 2019-12-11 2020-03-06 2020-01-03 nvelope 7 9 en in Strumica of preschool services MK-MLSP-151802-CW-RFB-2. 2. Expanding the access to Single Stage - One E 2021-10-3 1.1.10 / Civil works-Kindergar IBRD / 89020 and improving of the quality Post Request for Bids Open - National 871,380.00 Signed 2020-02-10 2021-05-25 2020-03-01 2020-03-15 2021-06-23 2020-03-22 2021-07-07 2020-05-09 2021-08-27 nvelope 1 ten in Aracinovo of preschool services MK-MLSP-151803-CW-RFB-2. 2. Expanding the access to Single Stage - One E 2021-10-3 1.1.11 / Civil works-Kindergar IBRD / 89020 and improving of the quality Post Request for Bids Open - National 358,953.04 Signed 2020-02-10 2020-12-14 2020-03-01 2020-03-15 2021-01-25 2020-03-22 2021-01-29 2020-05-09 2021-03-12 nvelope 1 ten in Valandovo of preschool services MK-MLSP-151804-CW-RFB-2. 2. Expanding the access to Single Stage - One E 2021-10-3 1.1.12 / Civil works-Kindergar IBRD / 89020 and improving of the quality Post Request for Bids Open - National 439,988.48 Signed 2020-02-10 2021-04-05 2020-03-01 2020-03-15 2021-05-05 2020-03-22 2021-06-01 2020-05-09 2021-07-15 nvelope 1 ten in Karposh 2 of preschool services MK-MLSP-151805-CW-RFB-2. 2. Expanding the access to Single Stage - One E 2021-10-3 1.1.13 / Civil works-Kindergar IBRD / 89020 and improving of the quality Post Request for Bids Open - National 378,560.95 Signed 2020-02-10 2020-09-17 2020-03-01 2020-03-15 2020-10-30 2020-03-22 2020-12-14 2020-05-09 2021-01-30 nvelope 1 ten in Probistip of preschool services MK-MLSP-167801-CW-RFQ-1. 1. Promoting social inclusi 3.15 / Renovation of part of t on through improved access Request for Quota Single Stage - One E 2020-12-0 he Special Institution Demir IBRD / 89020 Post Open - National 240,879.84 Signed 2020-04-11 2020-06-06 2019-11-02 to social benefits and servic tions nvelope 3 Kapija and part of the Public I es nstitution for rehabilitation of children and youth MK-MLSP-178969-CW-RFB-2. 2. Expanding the access to Single Stage - One E 1,052,790.3 2022-02-1 1.1.16 / Civil works-Kindergar IBRD / 89020 and improving of the quality Post Request for Bids Open - National Signed 2020-07-01 2021-03-12 2020-07-06 2020-08-17 2021-04-12 2020-09-16 2021-04-14 2020-10-21 2021-06-18 nvelope 2 3 ten in Bitola of preschool services MK-MLSP-178973-CW-RFB-2. 2. Expanding the access to Single Stage - One E 2022-02-1 1.1.17 / Civil works-Kindergar IBRD / 89020 and improving of the quality Post Request for Bids Open - National 903,823.66 Signed 2020-07-01 2021-05-19 2020-07-06 2020-08-17 2021-06-17 2020-09-16 2021-07-02 2020-10-21 2021-08-27 nvelope 3 ten in Lipkovo of preschool services MK-MLSP-178976-CW-RFB-2. 2. Expanding the access to Single Stage - One E 2022-02-1 1.1.18 / Civil works-Kindergar IBRD / 89020 and improving of the quality Post Request for Bids Open - National 463,607.71 Signed 2020-07-01 2021-12-30 2020-07-06 2020-08-17 2022-02-03 2020-09-16 2022-02-08 2020-10-21 2022-04-08 nvelope 3 ten in Gostivar of preschool services MK-MLSP-178979-CW-RFB-2. 2. Expanding the access to Single Stage - One E 2022-02-1 1.1.19 / Civil works-Kindergar IBRD / 89020 and improving of the quality Post Request for Bids Open - National 0.00 Canceled 2020-07-01 2020-07-06 2020-08-17 2020-09-16 2020-10-21 nvelope 3 ten in Karposh 2 of preschool services Page 1 MK-MLSP-294611-CW-RFQ-1. 1. Promoting social inclusi Other (with fi Request for Quota Single Stage - One E 2023-01-1 3.23 / Renovation of part of C IBRD / 89020 on through improved access Post Open - National eld for expla 0.00 Signed 2022-05-20 2022-07-15 tions nvelope 1 SR Strumica and PMU offices to social benefits and servic nation) es MK-MLSP-294615-CW-RFQ-2. 2. Expanding the access to Other (with fi Request for Quota Single Stage - One E 2022-09-1 1.1.3.1.1 / Civil works-Kinder IBRD / 89020 and improving of the quality Post Open - National eld for expla 0.00 Canceled 2022-05-20 2022-07-15 tions nvelope 3 garten in Kocani- installation of preschool services nation) of façade bricks Request for 1. Promoting social inclusi MK-MLSP-320130-CW-RFQ-1. Quotations - on through improved access Request for Quota Single Stage - One E 2023-03-0 3.25 / Renovation of PMU off IBRD / 89020 Post Open - National Small Works 0.00 Signed 2022-10-14 2022-12-09 to social benefits and servic tions nvelope 9 ices (Emergency) es SPD -Compet itive GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MK-MLSP-72180-GO-RFB-13 1. Promoting social inclusi 1 / Development of an integr on through improved access Open - Internationa Single Stage - One E / Post Request for Bids 0.00 Canceled 2019-01-15 2020-12-23 2019-02-14 2020-12-28 2019-03-21 2019-04-07 2019-04-15 2020-04-14 ated social welfare IS coverin to social benefits and servic l nvelope g both social assistance bene es fits and services MK-MLSP-72182-GO-RFB-13 1. Promoting social inclusi Single Stage - One E Pending Impl 2 / Hardware equipment for t / on through improved access Post Request for Bids Open - National 0.00 2019-03-01 2019-03-21 2019-04-25 2019-05-05 2019-05-13 2019-11-09 nvelope ementation he MLSP and the social instit to social benefits and servic utions es MK-MLSP-72678-GO-RFB-22 2. Expanding the access to Single Stage - One E 3 / Training for pre-primary s / and improving of the quality Post Request for Bids Open - National 0.00 Canceled 2019-01-15 2019-02-04 2019-03-11 2019-03-21 2019-03-29 2020-03-28 nvelope chool program of preschool services 2. Expanding the access to MK-MLSP-72679-GO-RFB-22 Single Stage - One E / and improving of the quality Post Request for Bids Open - National 0.00 Canceled 2019-02-15 2019-03-07 2019-04-11 2019-04-21 2019-04-29 2020-04-28 4 / In service teacher training nvelope of preschool services MK-MLSP-77087-GO-RFQ-31 3. Project Management, M Request for Quota Single Stage - One E / Post Open - National 26,617.47 Terminated 2019-01-09 2019-02-04 2019-12-11 2019-04-05 18 / Equipment (4 years ) onitoring and Evaluation tions nvelope MK-MLSP-93096-GO-DIR-131 1. Promoting social inclusi 0 / Maintenance and Upgrade IBRD / 89020 on through improved access Prior Direct Selection Direct 0.00 Canceled 2019-01-03 2019-01-08 2019-02-12 2021-01-02 of CBMIS to social benefits and servic es MK-MLSP-94588-GO-RFQ-31 3. Project Management, M Request for Quota Single Stage - One E IBRD / 89020 Post Open - National 15,750.48 Signed 2019-02-09 2019-03-07 2019-07-22 2019-04-06 21 / Camera and Recording d onitoring and Evaluation tions nvelope evices MK-MLSP-94585-GO-DIR-131 1. Promoting social inclusi 0 / Maintenance and Upgrade IBRD / 89020 on through improved access Prior Direct Selection Direct 363,357.44 Signed 2019-01-21 2019-01-28 2019-01-26 2019-01-30 2019-03-02 2019-02-13 2021-03-01 of CBMIS to social benefits and servic es MK-MLSP-96729-GO-RFB-13 1. Promoting social inclusi Single Stage - One E 11 / Hardware equipment for IBRD / 89020 on through improved access Prior Request for Bids Open - National 192,099.49 Signed 2019-02-01 2019-09-24 2019-03-03 2019-04-07 2019-11-08 2019-04-24 2019-11-21 2019-05-02 2019-12-19 2019-10-29 nvelope the local offices and the MLS to social benefits and servic P es MK-MLSP-96739-GO-RFQ-13 1. Promoting social inclusi Request for Quota Single Stage - One E Pending Impl 12 / Furniture for the local off IBRD / 89020 on through improved access Post Open - National 0.00 2019-02-10 2019-03-08 2019-09-04 tions nvelope ementation ices to social benefits and servic es MK-MLSP-77092-GO-RFQ-32 3. Project Management, M Request for Quota Single Stage - One E / Prior Open - National 0.00 Canceled 2019-02-15 2019-03-18 2019-05-17 6 / Vehicles (2) onitoring and Evaluation tions nvelope MK-MLSP-122570-GO-RFQ-3 3. Project Management, M Request for Quota Single Stage - One E IBRD / 89020 Prior Open - National 0.00 Canceled 2019-07-27 2019-09-02 2019-12-01 28 / Procurement of Vehicles onitoring and Evaluation tions nvelope (2) MK-MLSP-129121-GO-RFQ-1 1. Promoting social inclusi Request for Quota Single Stage - One E 314 / Furniture for the Center IBRD / 89020 on through improved access Post Open - National 22,554.84 Signed 2019-09-10 2019-10-24 2019-11-20 2019-12-23 tions nvelope for Cerebral palsy to social benefits and servic es MK-MLSP-129129-GO-DIR-13 1. Promoting social inclusi 16 / Upgrade of CBMIS-SSIP F IBRD / 89020 on through improved access Post Direct Selection Direct 10,079.30 Signed 2019-09-10 2019-10-01 2019-09-15 2019-10-01 2019-09-25 2019-11-26 2020-03-23 inancial module to social benefits and servic es MK-MLSP-169710-GO-RFQ-2. 1.1.14 / Furnishing and equi 2. Expanding the access to pment for the kindergarten i Request for Quota Single Stage - One E IBRD / 89020 and improving of the quality Post Open - National 97,878.71 Signed 2020-05-06 2020-07-01 2020-08-08 2020-08-30 n the municipality of Bogovin tions nvelope of preschool services je (village of Kamenjane), inc luding outside playground eq uipment MK-MLSP-173421-GO-RFQ-2. 1.1.15 / Furnishing and equi 2. Expanding the access to Request for Quota Single Stage - One E pment for the kindergarten i IBRD / 89020 and improving of the quality Post Open - National 131,723.10 Signed 2020-06-06 2020-08-01 2020-08-05 2020-09-10 tions nvelope n the municipality of Resen , of preschool services including outside playground equipment MK-MLSP-173425-GO-RFQ-3. 3. Project Management, M Request for Quota Single Stage - One E IBRD / 89020 Post Open - National 27,217.36 Signed 2020-06-06 2020-08-01 2020-08-08 2020-08-31 1.32 / Antivirus licenses onitoring and Evaluation tions nvelope MK-MLSP-173432-GO-RFQ-3. 3. Project Management, M Request for Quota Single Stage - One E 2.9 / Procurement of hardwar IBRD / 89020 Post Open - National 33,581.06 Signed 2020-07-06 2020-08-31 2020-08-25 2020-11-29 onitoring and Evaluation tions nvelope e equipment MK-MLSP-178981-GO-RFQ-2. 2. Expanding the access to Request for Quota Single Stage - One E 2.18 / Printing of age approp IBRD / 89020 and improving of the quality Post Open - National 41,603.07 Signed 2020-07-06 2020-08-31 2021-02-20 2020-09-30 tions nvelope riate teaching-learning mater of preschool services ials MK-MLSP-196377-GO-DIR-2. 2. Expanding the access to 2.19 / Distribution of age ap IBRD / 89020 and improving of the quality Post Direct Selection Direct 6,123.38 Signed 2020-09-30 2020-10-06 2020-10-05 2020-10-06 2020-11-09 2020-10-16 2020-12-24 propriate teaching-learning of preschool services materials MK-MLSP-203864-GO-RFB-2. 1.1.1.1 / Furnishing and equi 2. Expanding the access to Single Stage - One E pment for the kindergarten i IBRD / 89020 and improving of the quality Post Request for Bids Open - National 0.00 Canceled 2020-12-01 2020-12-06 2021-01-17 2021-02-16 2021-03-23 2021-06-21 nvelope n the municipality of Kavadar of preschool services ci , including outside playgro und equipment Page 2 MK-MLSP-203865-GO-RFB-2. 1.1.2.1 / Furnishing and equi 2. Expanding the access to Single Stage - One E pment for the kindergarten i IBRD / 89020 and improving of the quality Post Request for Bids Open - National 165,589.37 Signed 2020-12-01 2020-12-04 2020-12-06 2021-01-17 2021-01-15 2021-02-16 2021-01-29 2021-03-23 2021-04-22 2021-06-21 nvelope n the municipality of Negotin of preschool services o , including outside playgrou nd equipment MK-MLSP-203867-GO-RFQ-2. 1.1.3.1 / Furnishing and equi 2. Expanding the access to Request for Quota Single Stage - One E pment for the kindergarten i IBRD / 89020 and improving of the quality Post Open - National 122,262.75 Signed 2020-12-06 2021-01-31 2021-07-27 2021-05-01 tions nvelope n the municipality of Kocani , of preschool services including outside playground equipment MK-MLSP-203869-GO-RFQ-2. 1.1.4.1 / Furnishing and equi 2. Expanding the access to Request for Quota Single Stage - One E pment for the kindergarten i IBRD / 89020 and improving of the quality Post Open - National 82,835.63 Signed 2020-12-06 2021-01-31 2021-09-11 2021-05-01 tions nvelope n the municipality of Kisela V of preschool services oda , including outside playgr ound equipment MK-MLSP-203872-GO-RFQ-2. 1.1.6.1 / Furnishing and equi 2. Expanding the access to Request for Quota Single Stage - One E pment for the kindergarten i IBRD / 89020 and improving of the quality Post Open - National 120,852.03 Signed 2020-12-06 2021-01-31 2021-08-07 2021-05-01 tions nvelope n the municipality of Gjorce P of preschool services etrov , including outside play ground equipment MK-MLSP-226423-GO-RFQ-2. 1.1.2.1.2 / Furnishing and eq uipment for the kindergarten 2. Expanding the access to Request for Quota Single Stage - One E in the municipality of Negotin IBRD / 89020 and improving of the quality Post Open - National 11,415.11 Signed 2021-04-06 2021-06-01 2021-07-20 2021-07-01 tions nvelope o-Procurement, delivery and i of preschool services nstallation of Didactic equip ment and Procurement of mo vable partition panels MK-MLSP-234592-GO-RFQ-2. 1.1.1.1 / Furnishing and equi 2. Expanding the access to Request for Quota Single Stage - One E pment for the kindergarten i IBRD / 89020 and improving of the quality Post Open - National 160,804.18 Signed 2021-05-21 2021-07-16 2021-09-08 2021-09-14 tions nvelope n the municipality of Kavadar of preschool services ci , including outside playgro und equipment MK-MLSP-240823-GO-RFQ-2. 2. Expanding the access to Request for Quota Single Stage - One E 2.21 / Distribution of age ap IBRD / 89020 and improving of the quality Post Open - National 4,283.57 Signed 2021-07-02 2021-08-27 2021-07-24 2021-11-25 tions nvelope propriate teaching-learning of preschool services materials MK-MLSP-245169-GO-RFB-2. 1.1.9.1 / Furnishing and equi 2. Expanding the access to Single Stage - One E pment for the kindergarten i IBRD / 89020 and improving of the quality Post Request for Bids Open - National 71,404.75 Signed 2021-07-29 2021-07-27 2021-08-03 2021-09-14 2021-08-25 2021-10-14 2021-11-01 2021-11-18 2021-11-30 2022-01-27 nvelope n the municipality of Strumic of preschool services a , including outside playgrou nd equipment MK-MLSP-245188-GO-RFB-1. 1. Promoting social inclusi 3.1 / Development of an inte on through improved access Open - Internationa Single Stage - One E IBRD / 89020 Post Request for Bids 315,824.51 Signed 2021-08-15 2021-12-01 2021-08-20 2022-02-21 2021-10-01 2022-04-12 2021-10-31 2022-06-14 2021-12-05 2022-09-15 2024-06-30 grated social welfare IS cover to social benefits and servic l nvelope ing both social assistance be es nefits and services MK-MLSP-246187-GO-RFQ-2. 1.1.5.1 / Furnishing and equi 2. Expanding the access to Request for Quota Single Stage - One E pment for the kindergarten i IBRD / 89020 and improving of the quality Post Open - National 81,941.54 Signed 2021-09-06 2021-11-01 2022-04-28 2022-01-10 tions nvelope n the municipality of Kriva Pa of preschool services lanka , including outside play ground equipment MK-MLSP-246809-GO-RFQ-3. 3. Project Management, M Request for Quota Single Stage - One E Pending Impl IBRD / 89020 Post Open - National 0.00 2021-11-06 2022-01-01 2022-04-01 2.8 / Procurement of vehicles onitoring and Evaluation tions nvelope ementation (2) MK-MLSP-266952-GO-RFQ-2. 1.1.9.1.2 / Furnishing and eq 2. Expanding the access to uipment for the kindergarten Request for Quota Single Stage - One E IBRD / 89020 and improving of the quality Post Open - National 197,985.97 Signed 2021-12-24 2022-02-18 2022-03-02 2022-05-19 in the municipality of Strumic tions nvelope of preschool services a , including outside playgrou nd equipment (LOT 1 and LO T 5) MK-MLSP-266959-GO-RFQ-2. 1.1.11.1 / Furnishing and eq 2. Expanding the access to Request for Quota Single Stage - One E uipment for the kindergarten IBRD / 89020 and improving of the quality Post Open - National 93,450.92 Signed 2022-01-14 2022-03-11 2022-04-20 2022-06-09 tions nvelope in the municipality of Valand of preschool services ovo, including outside playgr ound equipment MK-MLSP-266964-GO-RFQ-3. 3. Project Management, M Request for Quota Single Stage - One E Pending Impl 1.41 / Hardware equipment f IBRD / 89020 Post Open - National 0.00 2021-12-24 2022-02-18 2022-04-19 onitoring and Evaluation tions nvelope ementation or PMU/MLSP MK-MLSP-276137-GO-RFQ-2. 1.1.10.1 / Furnishing and eq 2. Expanding the access to Request for Quota Single Stage - One E uipment for the kindergarten IBRD / 89020 and improving of the quality Post Open - National 0.00 Canceled 2022-02-20 2022-04-17 2022-10-14 tions nvelope in the municipality of Aracino of preschool services vo , including outside playgro und equipment MK-MLSP-276140-GO-RFQ-2. 1.1.13.1 / Furnishing and eq 2. Expanding the access to Request for Quota Single Stage - One E uipment for the kindergarten IBRD / 89020 and improving of the quality Post Open - National 0.00 Signed 2022-02-20 2022-04-17 2022-10-14 tions nvelope in the municipality of Probish of preschool services tip , including outside playgr ound equipment MK-MLSP-276142-GO-RFQ-2. 1.1.17.1 / Furnishing and eq 2. Expanding the access to Request for Quota Single Stage - One E Pending Impl uipment for the kindergarten IBRD / 89020 and improving of the quality Post Open - National 0.00 2022-02-20 2022-04-17 2022-10-14 tions nvelope ementation in the municipality of Lipkovo of preschool services , including outside playgroun d equipment MK-MLSP-294617-GO-RFQ-3. 3. Project Management, M Request for Quota Single Stage - One E 1.44 / Hardware equipment f IBRD / 89020 Post Open - National 13,098.18 Completed 2022-05-20 2022-07-15 2022-08-07 2022-10-13 2022-10-08 onitoring and Evaluation tions nvelope or MLSP/PMU MK-MLSP-303385-GO-RFQ-2. 1.1.12.1 / Furnishing and eq 2. Expanding the access to Request for Quota Single Stage - One E uipment for the kindergarten IBRD / 89020 and improving of the quality Post Open - National 0.00 Signed 2022-07-15 2022-09-09 2022-11-08 tions nvelope in the municipality of Karpos of preschool services h 2 , including outside playgr ound equipment MK-MLSP-312230-GO-RFB-2. 1.1.10.1 / Furnishing and equ 2. Expanding the access to Single Stage - One E Pending Impl ipment for the kindergarten i IBRD / 89020 and improving of the quality Post Request for Bids Open - National 0.00 2022-08-31 2022-09-05 2022-10-17 2022-11-16 2022-12-21 2022-12-31 nvelope ementation n the municipality of Aracino of preschool services vo , including outside playgro und equipment Page 3 MK-MLSP-326141-GO-RFQ-2. 2. Expanding the access to Request for Quota Single Stage - One E 1.1.3.1.2 / Equipment-Kinder IBRD / 89020 and improving of the quality Post Open - National 0.00 Signed 2022-11-18 2023-01-13 2023-03-14 tions nvelope garten in Kocani- aluminum s of preschool services liding doors MK-MLSP-334037-GO-RFQ-1. 1. Promoting social inclusi Request for Quota Single Stage - One E Pending Impl 3.26 / Furniture for CSR Stru IBRD / 89020 on through improved access Post Open - National 0.00 2023-01-20 2023-03-17 2023-05-16 tions nvelope ementation mica to social benefits and servic es MK-MLSP-334040-GO-RFB-2. 1.1.16.1 / Furnishing and eq 2. Expanding the access to Single Stage - One E Pending Impl uipment for the kindergarten IBRD / 89020 and improving of the quality Post Request for Bids Open - National 0.00 2023-02-01 2023-02-06 2023-03-20 2023-04-19 2023-05-24 2023-07-23 nvelope ementation in the municipality of Bitola, i of preschool services ncluding outside playground equipment MK-MLSP-334042-GO-RFQ2. 1.1.18.1 / Furnishing and eq 2. Expanding the access to Request for Quota Single Stage - One E Pending Impl uipment for the kindergarten IBRD / 89020 and improving of the quality Post Open - National 0.00 2023-02-20 2023-04-17 2023-06-16 tions nvelope ementation in the municipality of Gostiva of preschool services r , including outside playgrou nd equipment MK-MLSP-339228-GO-RFQ-2. 1.1.10.1.1 / Furnishing and e 2. Expanding the access to quipment for the kindergarte Request for Quota Single Stage - One E Pending Impl IBRD / 89020 and improving of the quality Post Open - National 0.00 2023-02-10 2023-04-07 2023-07-06 n in the municipality of Araci tions nvelope ementation of preschool services novo (didactic materials and outside playground equipme nt) MK-MLSP-365811-GO-RFQ-2. 2. Expanding the access to Request for Quota Single Stage - One E Pending Impl 1.1.3.1.3 / Civil works-Kinder IBRD / 89020 and improving of the quality Post Open - National 0.00 2023-06-16 2023-08-11 2024-02-07 tions nvelope ementation garten in Kocani- installation of preschool services of facade bricks NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MK-MLSP-72163-CS-CQS-112 1. Promoting social inclusi Consultant Qualifi / Technical assistance for acti / on through improved access Post Open - National 0.00 Canceled 2019-02-15 2019-02-23 2019-03-20 2019-03-27 2019-04-04 2020-04-03 cation Selection vation of GMI beneficiaries to social benefits and servic es MK-MLSP-72166-CS-CQS-122 1. Promoting social inclusi / Technical assistance for legi on through improved access Consultant Qualifi Pending Impleme / Post Open - National 0.00 2019-03-01 2019-03-09 2019-04-03 2019-04-10 2019-04-18 2020-04-17 slative changes regarding th to social benefits and servic cation Selection ntation e implementation of reforme es d licensing system MK-MLSP-72168-CS-CQS-123 1. Promoting social inclusi Consultant Qualifi / Social service needs assess / on through improved access Post Open - National 0.00 Canceled 2019-03-01 2019-03-09 2019-04-03 2019-04-10 2019-04-18 2020-04-17 cation Selection ment to social benefits and servic es MK-MLSP-72170-CS-CQS-124 1. Promoting social inclusi / Developing system for finan on through improved access Consultant Qualifi / Post Open - National 0.00 Canceled 2019-05-01 2019-05-09 2019-06-03 2019-06-10 2019-06-18 2020-06-17 cing of social services includi to social benefits and servic cation Selection ng determination of cost of s es ervices, MK-MLSP-72172-CS-CQS-127 / Transformation of the large 1. Promoting social inclusi institutional capacities into s on through improved access Consultant Qualifi mall group homes, living with / Post Open - National 0.00 Canceled 2019-01-15 2019-01-23 2019-02-17 2019-02-24 2019-03-04 2020-03-03 to social benefits and servic cation Selection support, deinstitutionalizatio es n through foster families and other appropriate forms of pr otection MK-MLSP-72175-CS-CQS-128 1. Promoting social inclusi Quality And Cost- / Outreach activities includei / on through improved access Prior Open - National 0.00 Canceled 2019-03-01 2019-03-15 2019-04-26 2019-05-01 2019-05-09 2019-05-22 2019-05-30 2020-05-29 Based Selection ng Citizen Angegement activi to social benefits and servic ties es MK-MLSP-72676-CS-CQS-222 2. Expanding the access to Consultant Qualifi / Developing a new capitatio / and improving of the quality Post Open - National 0.00 Canceled 2019-03-01 2019-03-09 2019-04-03 2019-04-10 2019-04-18 2020-04-17 cation Selection n formula of preschool services MK-MLSP-77086-CS-LCS-311 3. Project Management, M Least Cost Selecti IBRD / 89020 Prior Open - National 80,713.34 Signed 2019-01-01 2020-02-26 2019-01-15 2019-02-26 2020-03-23 2019-03-03 2020-05-05 2019-03-11 2020-06-05 2019-03-24 2020-06-18 2019-04-01 2020-07-14 2024-03-30 7 / Project Audit onitoring and Evaluation on MK-MLSP-77089-CS-CQS-321 / Operational and Performanc 3. Project Management, M Consultant Qualifi e Audit of the implementatio / Post Open - National 78,345.50 Signed 2019-02-01 2020-02-18 2019-02-09 2019-03-06 2020-04-23 2019-03-13 2020-06-03 2019-03-21 2020-06-10 2024-02-17 onitoring and Evaluation cation Selection n of the ECDE Grant program for infrastructure projects MK-MLSP-77090-CS-CQS-322 / Operational and Performanc e Audit for the implementatio 3. Project Management, M Consultant Qualifi / Post Open - National 78,536.61 Signed 2019-02-01 2020-02-18 2019-02-09 2019-03-06 2020-04-23 2019-03-13 2020-06-03 2019-03-21 2020-06-10 2024-02-17 n of the grant mechanism th onitoring and Evaluation cation Selection at will promote development of (non-institutional) social se rvices at local level MK-MLSP-77091-CS-CQS-323 / Baseline and Follow up Insti 3. Project Management, M Consultant Qualifi / Post Open - National 158,863.24 Signed 2019-02-01 2019-10-10 2019-02-09 2019-03-06 2019-12-06 2019-03-13 2019-12-25 2019-03-21 2020-01-04 2024-02-17 tutional Assessment of the pr onitoring and Evaluation cation Selection eschool quality process MK-MLSP-72681-CS-QCBS-2 2. Expanding the access to 25 / Developing a system for Quality And Cost- Open - Internationa IBRD / 89020 and improving of the quality Post 0.00 Canceled 2019-01-01 2019-01-09 2019-02-15 2019-02-20 2019-02-25 2019-03-07 2019-03-15 2020-03-14 evaluation of quality in the pr Based Selection l of preschool services eschool education system MK-MLSP-72232-CS-QCBS-2 2. Expanding the access to Quality And Cost- Open - Internationa 21 / Developing of age appro IBRD / 89020 and improving of the quality Post 0.00 Canceled 2019-04-01 2019-04-09 2019-05-16 2019-05-21 2019-05-26 2019-06-05 2019-06-13 2020-06-12 Based Selection l priate teaching-learning mat of preschool services erials MK-MLSP-72229-CS-QCBS-2 2. Expanding the access to Quality And Cost- Open - Internationa 12 / Project designs for kinde IBRD / 89020 and improving of the quality Prior 0.00 Canceled 2019-01-01 2019-01-15 2019-02-26 2019-03-03 2019-03-11 2019-03-24 2019-04-01 2023-12-31 Based Selection l rgartens of preschool services Page 4 MK-MLSP-72682-CS-QCBS-2 26 / Training of ECED admini 2. Expanding the access to Quality And Cost- Open - Internationa strators and other decision m IBRD / 89020 and improving of the quality Post 0.00 Canceled 2019-01-15 2019-01-23 2019-03-01 2019-03-06 2019-03-11 2019-03-21 2019-03-29 2020-03-28 Based Selection l akers to improve capacity an of preschool services d development of monitoring programs and tools MK-MLSP-76978-CS-QCBS-2 2. Expanding the access to Quality And Cost- Open - Internationa 27 / Outreach activities inclu IBRD / 89020 and improving of the quality Post 0.00 Canceled 2019-01-01 2019-01-09 2019-02-15 2019-02-20 2019-02-25 2019-03-07 2019-03-15 2020-03-14 Based Selection l ding Citizen Engagement acti of preschool services vities MK-MLSP-71874-CS-CQS-111 1. Promoting social inclusi / Technical assistance for legi on through improved access Consultant Qualifi / Prior Open - National 0.00 Canceled 2019-01-15 2019-01-29 2019-02-28 2019-03-10 2019-03-18 2020-03-17 slative changes regarding th to social benefits and servic cation Selection e implementation of GMI es MK-MLSP-72164-CS-CQS-121 1. Promoting social inclusi / Technical assistance for legi on through improved access Consultant Qualifi / Post Open - National 0.00 Canceled 2019-03-01 2019-03-09 2019-04-03 2019-04-10 2019-04-18 2020-04-17 slative changes regarding th to social benefits and servic cation Selection e implementation of social s es ervices reform MK-MLSP-72171-CS-CQS-125 1. Promoting social inclusi / Development of quality sta on through improved access Consultant Qualifi ndards including licensing an / Post Open - National 0.00 Canceled 2019-03-01 2019-03-09 2019-04-03 2019-04-10 2019-04-18 2020-04-17 to social benefits and servic cation Selection d accreditation and system f es or monitoring for their achiev ement MK-MLSP-95692-CS-CQS-327 3. Project Management, M Consultant Qualifi / Outreach activities includin IBRD / 89020 Post Open - National 0.00 Canceled 2019-03-01 2019-03-09 2019-04-03 2019-04-10 2019-04-18 2021-04-17 onitoring and Evaluation cation Selection g Citizen Engagement activiti es MK-MLSP-98479-CS-CQS-327 3. Project Management, M Consultant Qualifi / Outreach activities includin IBRD / 89020 Post Open - National 0.00 Canceled 2019-03-01 2019-03-09 2019-04-03 2019-04-10 2019-04-18 2021-04-17 onitoring and Evaluation cation Selection g Citizen Engagement activiti es MK-MLSP-99426-CS-CQS-114 1. Promoting social inclusi Consultant Qualifi / Counselling and Motivation IBRD / 89020 on through improved access Prior Open - National 0.00 Canceled 2019-02-07 2019-02-07 2019-02-28 2019-04-13 2019-05-13 2019-06-17 2020-06-16 cation Selection for activation of GMA benefici to social benefits and servic aries es MK-MLSP-115906-CS-CQS-12 1. Promoting social inclusi Consultant Qualifi 13 / Social service needs ass IBRD / 89020 on through improved access Post Open - National 61,155.24 Signed 2019-06-03 2019-06-11 2019-06-11 2019-07-06 2019-07-11 2019-07-13 2019-07-25 2019-07-21 2019-07-25 2020-01-17 cation Selection essment to social benefits and servic es MK-MLSP-115916-CS-CQS-32 3. Project Management, M Consultant Qualifi 4 / Public campaign including IBRD / 89020 Post Open - National 0.00 Canceled 2019-06-03 2019-06-11 2019-07-06 2019-07-13 2019-07-21 2023-12-31 onitoring and Evaluation cation Selection Citizen Engagement activitie s MK-MLSP-119370-CS-QCBS- 3. Project Management, M Quality And Cost- 325 / Public campaign includi IBRD / 89020 Prior Open - National 415,933.50 Signed 2019-06-17 2019-07-15 2019-07-01 2019-07-16 2019-08-12 2019-11-12 2019-08-17 2019-12-03 2019-08-25 2019-12-06 2019-09-09 2020-02-21 2019-09-22 2020-03-12 2024-06-30 onitoring and Evaluation Based Selection ng Citizen Engagement activi ties MK-MLSP-122574-CS-CQS-21 2. Expanding the access to 21 / Project designs for new k Consultant Qualifi IBRD / 89020 and improving of the quality Prior Open - National 93,887.86 Signed 2019-07-15 2019-07-26 2019-07-29 2019-08-23 2020-02-05 2019-09-07 2020-04-07 2019-09-15 2019-11-09 2020-01-13 indergartens in Arachinovo, cation Selection of preschool services Bitola, Lipkovo and Valandov o MK-MLSP-122578-CS-CQS-21 23 / Revision of basic Project 2. Expanding the access to Consultant Qualifi designs for kindergartens in IBRD / 89020 and improving of the quality Post Open - National 12,335.25 Signed 2019-08-01 2019-08-07 2019-08-15 2019-09-14 2019-12-23 2019-09-24 2020-01-02 2019-10-05 2020-01-09 2020-04-02 cation Selection Arachinovo, Bitola, Lipkovo, of preschool services Valandovo ,Probishtip, Gostiv ar, Karposh 1 and Karposh 2 MK-MLSP-122576-CS-CQS-21 2. Expanding the access to 22 / Project designs for upgra Consultant Qualifi IBRD / 89020 and improving of the quality Post Open - National 74,081.25 Signed 2019-07-30 2019-08-01 2019-08-13 2019-09-12 2019-10-10 2019-09-22 2019-10-30 2019-10-06 2019-11-13 2020-01-04 des of kindergartens in Probi cation Selection of preschool services shtip, Gostivar, Karposh 1 an d Karposh 2 MK-MLSP-129132-CS-CQS-21 2. Expanding the access to 3 / Supervision of works for c Consultant Qualifi IBRD / 89020 and improving of the quality Post Open - National 31,454.12 Signed 2019-09-09 2019-09-24 2019-09-17 2019-10-12 2019-12-05 2019-10-19 2019-12-25 2019-10-27 2019-12-31 2021-03-10 onstruction of kindergartens i cation Selection of preschool services n Negotino and Kavadarci MK-MLSP-129133-CS-CQS-21 2. Expanding the access to 4 / Supervision of works for c Consultant Qualifi IBRD / 89020 and improving of the quality Post Open - National 25,130.45 Signed 2019-09-09 2019-11-12 2019-09-17 2019-10-12 2019-12-06 2019-10-19 2019-12-27 2019-10-27 2020-01-04 2019-12-16 onstruction of kindergartens i cation Selection of preschool services n Kocani and Kisela Voda MK-MLSP-129135-CS-CQS-21 2. Expanding the access to 5 / Project for interior design Consultant Qualifi IBRD / 89020 and improving of the quality Post Open - National 39,061.04 Signed 2019-09-09 2020-01-24 2019-09-17 2019-10-12 2020-02-25 2019-10-19 2020-03-16 2019-10-27 2020-03-28 2020-01-25 for Kindergardens in Kocani, cation Selection of preschool services Negotino, Kisela Voda, Kavad arci and Bogovinje MK-MLSP-129136-CS-CQS-21 2. Expanding the access to 6 / Project for interior design Consultant Qualifi IBRD / 89020 and improving of the quality Post Open - National 41,802.26 Signed 2019-09-09 2020-01-24 2019-09-17 2019-10-12 2020-02-27 2019-10-19 2020-03-16 2019-10-27 2020-03-21 2020-01-25 for Kindergartens in Gjorce P cation Selection of preschool services etrov, Resen, Kriva Palanka a nd Strumica MK-MLSP-135022-CS-CQS-12 14 / Company for providing s 1. Promoting social inclusi upport to the municipalities/ on through improved access Consultant Qualifi IBRD / 89020 Post Open - National 127,667.71 Signed 2019-09-20 2019-09-27 2019-10-04 2019-10-14 2019-12-02 2019-10-17 2019-12-25 2019-10-23 2019-12-31 2023-07-04 potential service providers in to social benefits and servic cation Selection preparation of application do es cuments including the projec t proposals MK-MLSP-146042-CS-CQS-2. 1.7 / Supervision of works for 2. Expanding the access to Consultant Qualifi construction of kindergartens IBRD / 89020 and improving of the quality Post Open - National 66,840.50 Signed 2019-11-20 2019-11-19 2019-11-28 2019-12-23 2019-12-23 2019-12-30 2019-12-27 2020-02-03 2020-01-03 2021-10-25 cation Selection in the municipalities of Strum of preschool services ica, Resen, Gjorce Petrov, Bo govinje and Kriva Palanka MK-MLSP-147511-CS-CQS-2. 2.16 / Consultants' firm deliv 2. Expanding the access to Consultant Qualifi ering services for supporting IBRD / 89020 and improving of the quality Post Open - National 99,693.98 Signed 2019-11-29 2019-12-13 2019-12-13 2020-01-01 2019-12-20 2020-01-06 2020-02-21 2020-02-01 2020-02-25 2021-01-31 cation Selection the process of improving the of preschool services quality of preschool system MK-MLSP-201117-CS-CQS-2. 2. Expanding the access to 1.8 / Supervision of works for Consultant Qualifi IBRD / 89020 and improving of the quality Post Open - National 41,315.97 Signed 2020-12-01 2020-10-27 2020-12-22 2021-02-04 2021-02-03 2021-03-06 2021-02-24 2021-04-10 2021-03-13 2023-03-31 construction of kindergartens cation Selection of preschool services in Probishtip, Lipkovo, Bitola and Valandovo Page 5 MK-MLSP-201118-CS-CQS-2. 2. Expanding the access to 1.9 / Supervision of works for Consultant Qualifi IBRD / 89020 and improving of the quality Post Open - National 19,966.90 Signed 2020-12-01 2020-10-27 2020-12-22 2021-02-04 2021-03-26 2021-03-06 2021-05-25 2021-04-10 2021-06-01 2023-03-31 construction of kindergartens cation Selection of preschool services in Gostivar, Arachinovo and K arposh MK-MLSP-201119-CS-CQS-2. 2. Expanding the access to 1.10 / Project for interior desi Consultant Qualifi IBRD / 89020 and improving of the quality Post Open - National 24,744.21 Signed 2020-12-01 2020-10-27 2020-12-22 2021-02-04 2021-04-14 2021-03-06 2021-05-18 2021-04-10 2021-05-28 2023-03-31 gn for Kindergartens in Lipko cation Selection of preschool services vo, Aracinovo and Valandovo MK-MLSP-201120-CS-CQS-2. 2. Expanding the access to 1.11 / Project for interior desi Consultant Qualifi IBRD / 89020 and improving of the quality Post Open - National 14,214.43 Terminated 2020-12-01 2020-10-30 2020-12-22 2021-02-04 2021-06-15 2021-03-06 2021-07-28 2021-04-10 2021-08-06 2023-03-31 gn for Kindergartens in Probi cation Selection of preschool services shtip, Bitola, Gostivar and Ka rposh MK-MLSP-245170-CS-CQS-2. 2.21 / International Consulta 2. Expanding the access to Consultant Qualifi Open - Internationa ncy' Company for Designing , IBRD / 89020 and improving of the quality Post 0.00 Canceled 2021-08-01 2021-08-22 2021-10-05 2021-11-04 2021-12-09 2022-06-30 cation Selection l Implementing and Organizin of preschool services g Teacher’s Training Program MK-MLSP-266962-CS-CQS-2. 2. Expanding the access to 1.12 / Project for interior desi Consultant Qualifi IBRD / 89020 and improving of the quality Post Open - National 13,378.29 Signed 2021-12-19 2021-12-21 2022-01-09 2022-02-22 2022-02-21 2022-03-24 2022-03-14 2022-04-28 2022-03-29 2023-04-28 gn for Kindergardens in , Bito cation Selection of preschool services la, Gostivar and Karposh 3 MK-MLSP-267024-CS-QCBS- 2.2.22 / International Consult 2. Expanding the access to Quality And Cost- Open - Internationa Under Implement ancy' Company for Designing IBRD / 89020 and improving of the quality Post 0.00 2021-12-19 2021-12-22 2022-01-09 2022-02-21 2022-02-22 2022-03-22 2022-04-21 2022-05-26 2022-06-30 2023-06-30 Based Selection l ation , Implementing and Organizi of preschool services ng Teacher’s Training Progra m MK-MLSP-294626-CS-CQS-2. 2. Expanding the access to 2.23 / Consultant’s Company Consultant Qualifi IBRD / 89020 and improving of the quality Post Open - National 0.00 Signed 2022-05-15 2022-05-12 2022-06-05 2022-07-19 2022-08-22 2022-08-18 2022-09-16 2022-09-22 2023-03-21 for Development of Early Chil cation Selection of preschool services dhood Education and Care Fu nding Formula INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Actual Amount Invitation to Identifie Draft Negotiated Cont Component Review Type Method Contract Type Process Status Teams of Reference Signed Contract Contract Completion Description o. h (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MK-MLSP-72221-CS-CDS-135 1. Promoting social inclusi / Actuary in the Unit for Anal IBRD / 89020 on through improved access Prior Direct Selection Direct 79,664.25 Completed 2019-01-01 2018-11-12 2019-01-21 2018-10-01 2019-02-08 2018-10-02 2024-02-07 2021-01-31 ysis, Evaluation and Monitori to social benefits and servic ng es MK-MLSP-72223-CS-CDS-136 1. Promoting social inclusi Individual Consult / IT in the Unit for Analysis, E IBRD / 89020 on through improved access Prior Open 65,337.88 Completed 2019-01-01 2018-10-25 2019-01-29 2018-11-23 2019-02-08 2018-11-28 2019-02-16 2018-11-29 2024-02-15 2021-05-06 ant Selection valuation and Monitoring to social benefits and servic es MK-MLSP-72225-CS-CDS-137 1. Promoting social inclusi / Researcher in the Unit for A IBRD / 89020 on through improved access Prior Direct Selection Direct 75,392.24 Signed 2019-01-01 2018-11-12 2019-01-21 2018-10-01 2019-02-08 2018-10-02 2024-02-07 nalysis, Evaluation and Monit to social benefits and servic oring es MK-MLSP-72228-CS-CDS-139 1. Promoting social inclusi / Legal Advisor in the Unit for IBRD / 89020 on through improved access Prior Direct Selection Direct 197,332.13 Completed 2019-01-01 2018-11-12 2019-01-21 2018-10-01 2019-02-08 2018-10-02 2024-02-07 2021-01-31 Analysis, Evaluation and Mon to social benefits and servic itoring es MK-MLSP-76981-CS-INDV-22 8 / Capacity building of local 2. Expanding the access to Individual Consult architects and engineers for IBRD / 89020 and improving of the quality Post Open 84,037.50 Signed 2019-03-01 2019-02-04 2019-03-24 2019-03-29 2019-03-31 2019-05-10 2019-04-08 2019-05-13 2019-10-05 ant Selection such innovative and highly e of preschool services nergy-efficient infrastructure MK-MLSP-77005-CS-CDS-311 3. Project Management, M IBRD / 89020 Prior Direct Selection Direct 225,455.94 Signed 2019-01-01 2018-11-12 2019-01-21 2018-10-01 2019-02-08 2018-10-02 2024-02-07 / Project Manager onitoring and Evaluation MK-MLSP-77006-CS-CDS-312 3. Project Management, M IBRD / 89020 Prior Direct Selection Direct 189,073.72 Signed 2019-01-01 2018-11-12 2019-01-21 2019-02-08 2018-10-02 2024-02-07 / Procurement manager onitoring and Evaluation MK-MLSP-77007-CS-INDV-31 3. Project Management, M Individual Consult / Prior Open 0.00 Canceled 2019-01-01 2019-01-29 2019-02-08 2019-02-16 2024-02-13 3 / Coordinator for ECDE onitoring and Evaluation ant Selection MK-MLSP-77008-CS-INDV-31 3. Project Management, M Individual Consult 4 / Coordinator for Social ser IBRD / 89020 Prior Open 177,444.70 Signed 2019-01-01 2019-05-15 2019-01-29 2019-05-31 2019-02-08 2019-06-03 2019-02-16 2019-05-31 2024-02-15 onitoring and Evaluation ant Selection vices development MK-MLSP-77009-CS-INDV-31 3. Project Management, M IBRD / 89020 Prior Direct Selection Direct 175,079.26 Completed 2019-01-01 2018-11-12 2019-01-21 2018-10-01 2019-02-08 2018-10-02 2024-02-07 2021-08-05 5 / IT manager onitoring and Evaluation MK-MLSP-77010-CS-CDS-316 3. Project Management, M IBRD / 89020 Prior Direct Selection Direct 177,497.86 Signed 2019-01-01 2018-11-12 2019-01-21 2019-02-08 2018-10-02 2024-02-07 / Financial manager onitoring and Evaluation MK-MLSP-77016-CS-INDV-31 3. Project Management, M Individual Consult 11 / Environmental/social saf IBRD / 89020 Prior Open 79,853.27 Signed 2019-01-01 2019-01-24 2019-01-29 2019-03-18 2019-02-08 2019-03-26 2019-02-16 2019-03-29 2024-02-15 onitoring and Evaluation ant Selection eguards specialist MK-MLSP-72227-CS-CDS-138 1. Promoting social inclusi / Social Consultant in the Uni IBRD / 89020 on through improved access Prior Direct Selection Direct 132,358.19 Signed 2018-10-24 2018-11-12 2018-11-08 2018-10-01 2018-11-23 2018-10-04 2024-06-30 t for Analysis, Evaluation and to social benefits and servic Monitoring es MK-MLSP-77011-CS-CDS-317 3. Project Management, M IBRD / 89020 Prior Direct Selection Direct 53,314.64 Signed 2018-10-24 2018-11-12 2018-11-08 2018-10-01 2018-11-23 2018-10-02 2024-06-30 / Civil engineer/architect onitoring and Evaluation MK-MLSP-77012-CS-CDS-318 3. Project Management, M IBRD / 89020 Prior Direct Selection Direct 67,944.00 Signed 2018-10-24 2018-11-12 2018-11-08 2018-10-01 2018-11-23 2018-10-02 2024-06-30 / Civil engineer/architect onitoring and Evaluation MK-MLSP-77013-CS-CDS-319 3. Project Management, M IBRD / 89020 Prior Direct Selection Direct 52,145.31 Signed 2018-10-24 2018-11-12 2018-11-08 2018-10-01 2018-11-23 2018-10-02 2024-06-30 / Civil engineer/architect onitoring and Evaluation MK-MLSP-77014-CS-CDS-311 3. Project Management, M IBRD / 89020 Prior Direct Selection Direct 155,023.10 Signed 2018-10-24 2018-11-12 2018-11-08 2018-10-01 2018-11-23 2018-10-02 2024-06-30 0 / Civil engineer/architect onitoring and Evaluation MK-MLSP-77022-CS-CDS-311 3. Project Management, M Individual Consult Pending Impleme IBRD / 89020 Post Open 0.00 2019-01-01 2019-01-29 2019-02-08 2019-02-16 2024-06-30 4 / Grant application officer onitoring and Evaluation ant Selection ntation Page 6 MK-MLSP-77083-CS-INDV-31 3. Project Management, M Individual Consult IBRD / 89020 Prior Open 150,188.17 Completed 2019-01-01 2019-11-19 2019-01-24 2019-12-07 2019-01-31 2019-12-10 2019-02-08 2019-12-12 2024-06-30 2020-01-01 15 / M&E Officer onitoring and Evaluation ant Selection MK-MLSP-77018-CS-CDS-311 3. Project Management, M IBRD / 89020 Prior Direct Selection Direct 178,697.43 Signed 2018-10-24 2018-11-12 2018-11-08 2018-10-01 2018-11-23 2018-10-02 2024-06-30 12 / Grant Administrative Co onitoring and Evaluation ordinator MK-MLSP-77020-CS-CDS-311 3. Project Management, M IBRD / 89020 Prior Direct Selection Direct 88,621.61 Signed 2018-10-24 2018-11-12 2018-11-08 2018-10-01 2018-11-23 2018-10-02 2024-06-30 3 / Financial and administrati onitoring and Evaluation ve officer MK-MLSP-77085-CS-CDS-311 3. Project Management, M Individual Consult IBRD / 89020 Post Open 38,258.72 Signed 2019-01-01 2022-02-21 2019-01-29 2022-03-18 2019-02-08 2022-03-21 2019-02-16 2022-03-24 2024-06-30 6 / IT officer onitoring and Evaluation ant Selection MK-MLSP-94587-CS-INDV-31 3. Project Management, M Individual Consult 20 / Environmental/social saf IBRD / 89020 Post Open 87,697.46 Signed 2019-03-01 2020-05-20 2019-03-24 2020-06-09 2019-03-31 2020-06-29 2019-04-08 2020-07-02 2024-04-06 onitoring and Evaluation ant Selection eguards assistance MK-MLSP-94589-CS-INDV-31 3. Project Management, M Individual Consult IBRD / 89020 Post Open 153,586.85 Signed 2019-03-01 2019-02-07 2019-03-24 2019-04-12 2019-03-31 2019-04-15 2019-04-08 2019-04-20 2024-04-06 22 / Interior Designer onitoring and Evaluation ant Selection MK-MLSP-94590-CS-INDV-31 3. Project Management, M Individual Consult IBRD / 89020 Post Open 29,590.53 Signed 2019-02-01 2019-02-24 2019-03-18 2019-03-03 2019-04-01 2019-03-11 2019-04-05 2024-03-09 23 / Business Analyst onitoring and Evaluation ant Selection MK-MLSP-94593-CS-INDV-11 1. Promoting social inclusi Individual Consult 3 / Social Safety Net Speciali IBRD / 89020 on through improved access Post Open 96,631.92 Signed 2019-02-01 2019-02-04 2019-02-24 2019-03-29 2019-03-03 2019-04-09 2019-03-11 2019-05-15 2024-03-09 ant Selection st to social benefits and servic es MK-MLSP-94594-CS-INDV-12 1. Promoting social inclusi 9 / Development of norms an on through improved access Individual Consult d standards for establishing IBRD / 89020 Post Open 13,459.20 Signed 2019-03-01 2019-02-06 2019-03-24 2019-04-15 2019-03-31 2019-05-20 2019-04-08 2019-05-23 2020-04-07 to social benefits and servic ant Selection of social services and for ens es uring quality in the service d elivery MK-MLSP-94596-CS-INDV-12 1. Promoting social inclusi 10 / Support for Developmen on through improved access Individual Consult t of norms and standards for IBRD / 89020 Post Open 8,335.63 Signed 2019-03-01 2019-02-06 2019-03-24 2019-04-15 2019-03-31 2019-05-22 2019-04-08 2019-05-28 2020-04-07 to social benefits and servic ant Selection establishing of social service es s and for ensuring quality in t he service delivery MK-MLSP-94598-CS-INDV-12 1. Promoting social inclusi 11 / Developing a system for on through improved access Individual Consult Pending Impleme IBRD / 89020 Post Open 0.00 2019-03-01 2019-03-24 2019-03-31 2019-04-08 2020-04-07 evaluation of quality in the s to social benefits and servic ant Selection ntation ocial services delivery syste es m MK-MLSP-95684-CS-INDV-12 1. Promoting social inclusi 12 / Preparation of Cost Meth on through improved access Individual Consult IBRD / 89020 Post Open 22,275.54 Signed 2019-02-01 2019-02-06 2019-02-24 2019-04-17 2019-03-03 2019-05-27 2019-03-11 2019-05-27 2019-09-07 odology for Establishing of S to social benefits and servic ant Selection ocial Services including pricin es g list MK-MLSP-95686-CS-INDV-22 2. Expanding the access to Individual Consult 9 / Developing a new capitati IBRD / 89020 and improving of the quality Post Open 7,761.25 Signed 2019-05-01 2019-10-18 2019-05-24 2019-12-04 2019-05-31 2019-12-17 2019-06-08 2019-12-19 2019-12-05 ant Selection on formula of preschool services MK-MLSP-96725-CS-INDV-31 3. Project Management, M Individual Consult IBRD / 89020 Post Direct 0.00 Canceled 2019-02-01 2019-01-30 2019-02-14 2019-04-01 2019-02-24 2019-03-04 2024-03-02 24 / Business Analyst Assista onitoring and Evaluation ant Selection nt MK-MLSP-97638-CS-CDS-114 1. Promoting social inclusi / Counselling and Motivation IBRD / 89020 on through improved access Prior Direct Selection Direct 0.00 Canceled 2019-02-01 2019-02-11 2019-04-17 2020-04-16 for activation of GMA benefici to social benefits and servic aries es MK-MLSP-119013-CS-INDV-3 3. Project Management, M Individual Consult IBRD / 89020 Post Limited 102,630.85 Signed 2019-06-13 2019-01-30 2019-06-23 2019-04-01 2019-06-30 2019-04-04 2019-07-08 2019-04-11 2020-01-04 125 / Business Analyst Assist onitoring and Evaluation ant Selection ant MK-MLSP-129139-CS-INDV-3 3. Project Management, M Individual Consult IBRD / 89020 Post Open 117,305.19 Signed 2019-09-09 2019-12-03 2019-10-02 2019-12-28 2019-10-09 2019-12-30 2019-10-24 2020-01-01 2024-07-29 126 / Civil engineer onitoring and Evaluation ant Selection MK-MLSP-129140-CS-INDV-3 3. Project Management, M Individual Consult IBRD / 89020 Post Open 83,757.70 Signed 2019-09-09 2020-10-27 2019-10-02 2021-01-08 2019-10-09 2021-01-12 2019-10-24 2021-01-19 2024-07-29 127 / Civil engineer/arhitect onitoring and Evaluation ant Selection MK-MLSP-129143-CS-INDV-3 3. Project Management, M Individual Consult Pending Impleme IBRD / 89020 Post Open 0.00 2019-09-09 2019-10-02 2019-10-09 2019-10-24 2024-07-29 128 / Electrical engineer onitoring and Evaluation ant Selection ntation MK-MLSP-129144-CS-INDV-3 3. Project Management, M Individual Consult Pending Impleme IBRD / 89020 Post Open 0.00 2019-09-09 2019-10-02 2019-10-09 2019-10-24 2024-07-29 129 / Mechanical engineer onitoring and Evaluation ant Selection ntation MK-MLSP-129624-CS-INDV-1 1. Promoting social inclusi Individual Consult 317 / Economist in the Unit f IBRD / 89020 on through improved access Post Limited 157,335.13 Signed 2019-08-29 2019-09-13 2019-09-06 2019-09-17 2019-09-11 2019-09-17 2019-10-10 2019-09-18 2024-08-14 ant Selection or Analysis, Evaluation and M to social benefits and servic onitoring es MK-MLSP-129625-CS-INDV-3 3. Project Management, M Individual Consult IBRD / 89020 Post Open 113,545.04 Signed 2019-09-18 2019-09-19 2019-10-11 2019-10-18 2019-10-26 2019-10-20 2019-11-03 2019-10-22 2020-05-01 130 / Procurement officer onitoring and Evaluation ant Selection 2. Expanding the access to MK-MLSP-135381-CS-INDV-1 Individual Consult IBRD / 89020 and improving of the quality Post Open 109,940.00 Signed 2019-10-01 2019-10-10 2019-10-24 2019-12-04 2019-10-26 2020-01-20 2019-11-12 2020-01-22 2024-06-18 .2.10 / Principal Investigator ant Selection of preschool services MK-MLSP-135385-CS-INDV-2 2. Expanding the access to Individual Consult 211 / Local Support to the Pri IBRD / 89020 and improving of the quality Post Open 70,345.79 Signed 2019-10-01 2019-10-10 2019-10-24 2019-12-11 2019-10-31 2019-12-14 2019-11-22 2019-12-19 2024-06-28 ant Selection ncipal Investigator of preschool services MK-MLSP-135386-CS-INDV-2 2. Expanding the access to .2.12 / National Coordinator f Individual Consult IBRD / 89020 and improving of the quality Post Open 55,651.68 Signed 2019-10-01 2019-10-10 2019-10-24 2019-12-03 2019-10-31 2019-12-14 2019-11-08 2019-12-19 2024-06-14 or Measuring Early Learning ant Selection of preschool services Environment (MELE) MK-MLSP-135387-CS-INDV-2 2. Expanding the access to .2.13 / National Coordinator f Individual Consult IBRD / 89020 and improving of the quality Post Open 55,651.68 Signed 2019-10-01 2019-10-10 2019-10-24 2019-12-03 2019-10-31 2019-12-14 2019-11-08 2019-12-19 2024-06-14 or Measurement of Develop ant Selection of preschool services ment and Early Learning (MO DEL) MK-MLSP-135389-CS-INDV-2 .2.14 / Local Consultant for st 2. Expanding the access to Individual Consult rengthening the preschool sy IBRD / 89020 and improving of the quality Post Open 55,651.68 Signed 2019-10-01 2019-10-10 2019-10-24 2019-12-03 2019-10-31 2019-12-14 2019-11-08 2019-12-23 2024-06-14 ant Selection stem for pre-service and in-s of preschool services ervice teacher training MK-MLSP-147510-CS-INDV-2 2. Expanding the access to Individual Consult .2.15 / International Teacher IBRD / 89020 and improving of the quality Post Open 52,793.46 Signed 2019-11-27 2019-12-10 2019-12-14 2019-12-13 2019-12-19 2020-02-21 2020-01-16 2020-02-25 2024-06-23 ant Selection Training and Program Design of preschool services Expert Consultant Page 7 MK-MLSP-173423-CS-INDV-2 2. Expanding the access to Individual Consult .2.17 / Developing a new cap IBRD / 89020 and improving of the quality Post Open 38,250.00 Signed 2020-06-01 2020-08-18 2020-07-20 2021-01-22 2020-08-10 2021-02-18 2020-09-14 2021-03-02 2021-01-12 ant Selection itation formula of preschool services MK-MLSP-173424-CS-INDV-3 3. Project Management, M Individual Consult IBRD / 89020 Prior Limited 119,029.21 Terminated 2020-05-15 2020-05-29 2020-05-20 2020-06-01 2020-06-10 2020-06-15 2020-07-15 2020-06-17 2024-06-30 .1.31 / System administrator onitoring and Evaluation ant Selection MK-MLSP-173426-CS-INDV-3 3. Project Management, M Individual Consult IBRD / 89020 Prior Limited 67,102.22 Signed 2020-05-15 2020-05-20 2020-05-20 2020-06-08 2020-06-10 2020-06-26 2020-07-15 2020-07-02 2024-06-30 .1.33 / Assistant Civil enginee onitoring and Evaluation ant Selection r MK-MLSP-201109-CS-INDV-1 1. Promoting social inclusi .3.18 / Researcher/Analyst in on through improved access Individual Consult Under Implement IBRD / 89020 Post Open 0.00 2020-11-18 2020-11-09 2021-01-06 2021-01-27 2021-03-03 2024-06-30 the Unit for Analysis, Evaluati to social benefits and servic ant Selection ation on and Monitoring es MK-MLSP-201121-CS-INDV-3 3. Project Management, M Individual Consult Pending Impleme IBRD / 89020 Post Open 0.00 2020-12-01 2021-01-19 2021-02-09 2021-03-16 2024-06-30 .1.34 / Interior Designer onitoring and Evaluation ant Selection ntation MK-MLSP-201123-CS-INDV-3 3. Project Management, M Individual Consult IBRD / 89020 Prior Open 83,577.45 Signed 2020-12-01 2020-10-28 2021-01-19 2021-01-08 2021-02-09 2021-01-12 2021-03-16 2021-01-15 2024-06-30 .1.35 / Civil engineer/architec onitoring and Evaluation ant Selection t MK-MLSP-201124-CS-INDV-3 3. Project Management, M Individual Consult IBRD / 89020 Prior Open 61,306.83 Signed 2020-12-01 2020-11-09 2021-01-19 2020-12-29 2021-02-09 2021-01-11 2021-03-16 2021-01-14 2024-06-30 .1.36 / Assistant Coordinator onitoring and Evaluation ant Selection for ECDE MK-MLSP-201125-CS-INDV-3 3. Project Management, M Individual Consult .1.37 / Assistant Coordinator IBRD / 89020 Prior Open 76,755.50 Signed 2020-12-01 2020-11-09 2021-01-19 2020-12-22 2021-02-09 2020-12-30 2021-03-16 2021-01-01 2024-06-30 onitoring and Evaluation ant Selection for Social services developm ent MK-MLSP-201126-CS-INDV-3 3. Project Management, M Individual Consult IBRD / 89020 Prior Open 82,012.45 Signed 2020-12-01 2020-10-28 2021-01-19 2021-01-11 2021-02-09 2021-01-12 2021-03-16 2021-01-15 2024-06-30 .1.38 / Civil engineer/architec onitoring and Evaluation ant Selection t MK-MLSP-203846-CS-INDV-1 1. Promoting social inclusi Individual Consult .3.19 / Legal Advisor in the U IBRD / 89020 on through improved access Prior Open 79,187.98 Signed 2020-11-18 2020-11-16 2021-01-06 2021-03-08 2021-01-27 2021-04-21 2021-03-03 2021-04-27 2024-06-30 ant Selection nit for Analysis, Evaluation a to social benefits and servic nd Monitoring es MK-MLSP-203854-CS-INDV-3 3. Project Management, M Individual Consult .1.39 / Junior Assistant Coordi IBRD / 89020 Prior Open 76,034.50 Signed 2020-11-15 2020-11-16 2021-01-03 2020-12-22 2021-01-24 2020-12-31 2021-02-28 2021-01-01 2024-06-30 onitoring and Evaluation ant Selection nator for Social Services Dev elopment MK-MLSP-203861-CS-INDV-1 1. Promoting social inclusi Individual Consult .2.15 / Methodology for pricin IBRD / 89020 on through improved access Post Open 218.21 Signed 2020-11-15 2020-11-13 2021-01-03 2020-11-30 2021-01-24 2020-12-03 2021-02-28 2020-12-10 2021-04-29 ant Selection g social services to social benefits and servic es MK-MLSP-212355-CS-INDV-2 2. Expanding the access to Individual Consult .2.20 / Local Consultant for D IBRD / 89020 and improving of the quality Post Open 9,777.87 Signed 2021-01-07 2021-01-22 2021-02-25 2021-02-25 2021-03-18 2021-03-04 2021-04-22 2021-03-10 2022-04-22 ant Selection eveloping a new capitation fo of preschool services rmula MK-MLSP-219384-CS-INDV-3 3. Project Management, M Individual Consult IBRD / 89020 Prior Limited 72,538.72 Signed 2021-02-17 2021-02-17 2021-02-22 2021-02-22 2021-03-15 2021-03-02 2021-04-19 2021-03-05 2024-06-30 .1.40 / IT officer onitoring and Evaluation ant Selection MK-MLSP-232018-CS-INDV-1 1. Promoting social inclusi Individual Consult .2.16 / Methodology for Pricin IBRD / 89020 on through improved access Post Direct 13,130.98 Signed 2021-05-05 2021-07-09 2021-05-15 2021-07-14 2021-06-05 2021-07-25 2021-07-10 2021-07-29 2024-06-30 ant Selection g Social Services to social benefits and servic es MK-MLSP-244303-CS-INDV-1 1. Promoting social inclusi .3.20 / Disability and Inclusio on through improved access Individual Consult IBRD / 89020 Post Limited 69,015.98 Terminated 2021-07-19 2021-07-21 2021-07-24 2021-07-28 2021-08-14 2021-07-29 2021-09-18 2021-07-31 2024-06-30 n Consultant  in the Unit for to social benefits and servic ant Selection Analysis, Evaluation and Mon es itoring MK-MLSP-245182-CS-CDS-1. 1. Promoting social inclusi 2.17 / Expert in financial allo on through improved access IBRD / 89020 Post Direct Selection Direct 3,676.96 Completed 2021-08-01 2021-08-13 2021-08-11 2021-08-17 2021-10-15 2021-12-11 2022-01-13 2022-03-12 wances for social protection to social benefits and servic national program developme es nt MK-MLSP-245185-CS-CDS-1. 1. Promoting social inclusi 2.18 / Expert in social service on through improved access IBRD / 89020 Post Direct Selection Direct 3,637.93 Completed 2021-08-01 2021-08-13 2021-08-11 2021-08-17 2021-10-15 2021-12-11 2022-01-13 2022-03-12 s for social protection nation to social benefits and servic al program development es MK-MLSP-245187-CS-CDS-1. 1. Promoting social inclusi 2.19 / Expert in social protect on through improved access IBRD / 89020 Post Direct Selection Direct 3,676.96 Completed 2021-08-01 2021-08-13 2021-08-11 2021-08-17 2021-10-15 2021-12-11 2022-01-13 2022-03-12 ion system for national progr to social benefits and servic am development es MK-MLSP-269870-CS-INDV-3 3. Project Management, M Individual Consult IBRD / 89020 Post Open 56,642.40 Signed 2022-01-02 2021-12-23 2022-01-19 2021-12-31 2022-01-24 2022-01-03 2022-02-03 2022-01-11 2024-06-30 .1.42 / PMU Legal Advisor onitoring and Evaluation ant Selection MK-MLSP-278417-CS-INDV-1 1. Promoting social inclusi .3.21 / Disability and Inclusio on through improved access Individual Consult IBRD / 89020 Post Open 39,564.14 Signed 2022-02-15 2022-02-15 2022-04-05 2022-03-03 2022-04-26 2022-03-08 2022-05-31 2022-03-10 2024-06-30 n Consultant  in the Unit for to social benefits and servic ant Selection Analysis, Evaluation and Mon es itoring MK-MLSP-278418-CS-INDV-1 1. Promoting social inclusi .3.22 / Social Protection Spec on through improved access Individual Consult IBRD / 89020 Post Open 71,550.08 Signed 2022-02-15 2022-02-15 2022-04-05 2022-03-03 2022-04-26 2022-03-08 2022-05-31 2022-03-10 2024-06-30 ialist in the Unit for Analysis, to social benefits and servic ant Selection Evaluation and Monitoring es MK-MLSP-285014-CS-INDV-3 1. Promoting social inclusi Individual Consult .1.43 / Coordinator for Early IBRD / 89020 on through improved access Post Open 40,852.27 Signed 2022-03-20 2022-03-17 2022-05-08 2022-04-20 2022-05-29 2022-05-04 2022-07-03 2022-05-14 2024-06-30 ant Selection Childhood Education and Car to social benefits and servic e es MK-MLSP-302862-CS-INDV-2 2. Expanding the access to Individual Consult .2.24 / International STATA a IBRD / 89020 and improving of the quality Post Open 0.00 Signed 2022-07-10 2022-07-15 2022-08-28 2022-10-17 2022-09-18 2022-11-09 2022-10-23 2024-06-30 ant Selection nd Data Analysis Consultant of preschool services MK-MLSP-319376-CS-INDV-1 1. Promoting social inclusi Individual Consult .3.24 / Financial Expert in the IBRD / 89020 on through improved access Post Open - National 0.00 Signed 2022-10-04 2022-10-05 2022-11-22 2022-10-26 2022-12-13 2022-10-27 2023-01-17 2024-06-30 ant Selection Unit for Analysis, Evaluation to social benefits and servic and Monitoring es MK-MLSP-321319-CS-CDS-3. 3. Project Management, M 1.45 / Monitoring and Evaluat IBRD / 89020 Post Direct Selection Direct - National 0.00 Signed 2022-10-16 2022-11-01 2022-10-26 2022-09-30 2022-12-30 2024-06-30 onitoring and Evaluation ion Specialist MK-MLSP-363178-CS-INDV-3 3. Project Management, M Individual Consult Under Implement IBRD / 89020 Post Limited 0.00 2023-05-24 2023-05-26 2023-05-29 2023-06-19 2023-07-24 2024-06-30 .1.46 / Project Management onitoring and Evaluation ant Selection ation Assistant Page 8 Procurement 1. Procurement for the Project will be carried out in accordance with the World Bank’s "Guidelines: Procurement of Goods, Works and Non-consulting Services Under IBRD Loans and IDA Credits and Grants" dated January 2011 and revised as of July, 2014 (Procurement Guidelines); and "Guidelines: Selection and Employment of Consultants Under IBRD Loans and IDA Credits and Grants by World Bank Borrowers" dated January 2011 and revised as of July 2014 (Consultant Guidelines) and the provisions stipulated in the Legal Agreement (LA) and POM. The World Bank Guidelines on Preventing and Combating Fraud and Corruption in Projects Financed by IBRD Loans and IDA Credit and Grants dated October 15, 2006 and revised on January 2011, would also apply. Thresholds for Procurement Methods 2. Goods: Goods and equipment estimated to cost US$1,000,000 or more would be procured through International Competitive Bidding (ICB). Goods estimated to cost less than US$1,000,000 and more than US$100,000 would be procured through National Competitive Bidding (NCB). Readily available off-the-shelf goods estimated to cost equal to or less than US$100,000 each would be procured through Shopping (SH) on the basis of at least three written quotations obtained from qualified suppliers. Direct Contracting (DC) may be used in accordance with the requirements outlined in para. 3.7 of the Procurement Guidelines. 3. Works: Works estimated to cost equal to US$5,000,000 or more would be procured through ICB. Works estimated to cost less than US$5,000,000 and equal to or more than US$200,000 would be procured through NCB. Contracts estimated to cost less than US$200,000 each would be procured through Shopping (SH) procedures on the basis of at least three written quotations obtained from qualified contractors. Direct Contracting (DC) for works may be used in accordance with the requirements outlined in para. 3.7 of the Procurement Guidelines. 4. Consultant Services: Consultancy services to be provided by consulting firms estimated to cost more than US$300,000 would be procured through Quality and Cost Based Selection (QCBS) method. Consultancy services to be provided by consulting firms estimated to cost equal to or less than US$300,000 may be procured through Consultants’ Qualifications Selection (CQS) method. Other methods such as Fixed Budget Selection (FBS), Quality Based Selection (QBS), and Least Cost Selection (LCS) shall be made available through the Legal Agreement irrespective of the amount. Individual Consultants (IC) will be selected in accordance with Section V of the Consultant Guidelines. Single Source Selection (SSS) method for firms and individuals will also be specified in the Legal Agreement. For assignments estimated to cost equal to or less than US$300,000, the shortlist may comprise only of national firms according to the paragraph 2.7 of the Consultant Guidelines. However, if foreign firms express interest, they shall be considered. 5. NCB of the Borrower may be used for procurement of goods, works and non-consulting services for the project, provided that the following provisions are complied with: (a) Entities in which the Republic of Armenia owns a majority shareholding shall not be invited to participate in tenders for the government unless they are and can be shown to be legally and financially autonomous and operate under commercial law. (b) Post-qualification criteria shall only pertain to past contract performance, financial, managerial, and technical capabilities of bidders. (c) Joint venture partners shall be jointly and severally liable for their obligations. (d) Estimated contract prices shall not be advertised. (e) Except for late bids, no bids shall be rejected at the bid opening. The opening procedures shall comply with conditions of paragraph 2.45 of the Procurement Guidelines. (f) No bids shall be rejected solely because they exceed the estimated price. Bids can be cancelled and new bids invited, only if the conditions of paragraphs 2.61–2.64 of the Procurement Guidelines are met. (g) All bid evaluation criteria shall be quantifiable in monetary terms or expressed as pass/fail criteria. (h) Without limitation to paragraph 3 of Appendix 1 to the Procurement Guidelines, advance Bank approval is required for any modifications in the contract scope/conditions during implementation. Prior Review Thresholds Type of Procurement Prior Review Threshold Goods $1,000,000 Works First ICB regardless of value and contracts equal to or above $10,000,000 and first NCB IT System & Non-Consulting $1,000,000 Services Direct Contracting* $60,000 Consulting Services (Firm) First QCBS regardless of value and contracts equal to or above $500,000 and first CQS Consulting Services $200,000 (Individual) Single Source Selection** $5,000 *Must comply with the requirements of para. 3.7 of the Procurement Guidelines. ** Must comply with the requirements of paras. 3.8-3.11 of the Consultant Guidelines. 6. All TORs are subject to the Bank’s prior review irrespective of the prior or post review status of the consulting assignment in the procurement plan. Post Review Ratio 7. Contracts not subject to Bank’s prior review will be post reviewed by Bank’s supervision missions. Procurement Plan 8. All contracts to be financed under the project, the various procurement or consultant selection methods, the estimated costs, prior review requirements, and time frame have been agreed between the Borrower and the Bank and presented in the Procurement Plan (see below). The Procurement Plan will be updated as required to reflect the actual Project implementation needs and improvements in institutional capacity. The Procurement Plan its updates or modifications, shall be subject to the Bank’s prior review and no objection before implementation. The final version of the Procurement Plan will be disclosed (without cost estimates) and posted in the Bank’s external website in accordance with paragraph 1.18 of Procurement Guidelines and paragraph 1.25 of the Consultants Guidelines, ATDF’s database, and www.procurement.am. 32. Works contracts to be procured under the project include rehabilitation of heritage hubs, construction of tourism facilities and improvement of access roads and parking areas. There is no prequalification anticipated under the project and works are to be procured using NCB procedure. 33. Consultants to be selected under the project include services for preliminary assessment of buildings to undergo rehabilitation, preparation of detailed designs for the rehabilitation of heritage hubs and author’s supervision, technical supervision of works, destination management, marketing and promotion, audit services, monitoring and evaluation, training and site management plan. UNESCO will be contracted under Single Source Selection for advisory services for cultural heritage. 34. Goods to be procured under the project include vehicles, furniture, and equipment for the rehabilitated sites and tourism facilities. 35. A General Procurement Notice (GPN) will be published in UNDB on-line and in its printed version after negotiations. Specific Procurement Notices (SPN) for all ICB packages and consulting contracts each with cost estimate above US$300,000 will also be published in the UNDB. In addition, the SPNs for civil works contracts will be provided to the Union of Builders of Armenia. Filing and Record Keeping 36. ATDF will keep complete files of all procurement packages under the project to facilitate post review and Project audit. 37. The procurement related risks are summarized in Table 3.1 below. 38. Procurement Plan Table 3.1: Summary Risk Assessment Rating of Rating of Description of Risk Mitigation Measures Residual Risk Risk Current procurement Substantial ATDF will hire additional qualified Moderate staff is not able to cope procurement staff or procurement with the increased consultant. workload under LEIDP. High turnover of High ATDF will hire additional qualified Substantial procurement staff due to procurement staff or procurement low salary. consultant. Newly procurement staff Substantial ATDF’s procurement staff should Moderate may not have sufficient continuously improve their knowledge and knowledge of Bank’s procurement experience in Bank procedures by attending procurement. training/workshops offered by the World Bank, familiarizing themselves with the Procurement and Consultant Guidelines and on- the-job training. Given the multi- Substantial (a) Educate stakeholders about Moderate stakeholder environment, the POM through ATDF’s possibility of unnecessary Institutional Support intervention and Department. (b) Ensure pressures resulting in transparent decision making implementation delays based on evaluation criteria disclosed in bidding documents and proposal documents. Inadequate capacity in Substantial (a) DFA will apply additional Moderate the DFA to prepare TORs efforts to improve the and technical technical parts of procurement specifications and documents and quality of implement Bank-financed TORs for consulting services. Project. (b) Project to finance consulting services to build capacity in the DFA. PROCUREMENT Armenia : Local Economy and Infrastructure Development Project PLAN General Information Country: Armenia 2017-03-23 Bank’s Approval Date of the Original Procurement Plan: 2023-06-06 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P150327 GPN Date: Project Name: Local Economy and Infrastructure Development Project Loan / Credit No: IBRD / 85720, TF / A1063 Armenian Territorial Development Fund Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned TUR-01-1 / Rehabilitation of Heritage Hub and Tourism Ci Single Stage - One E 2019-05-0 IBRD / 85720 Post Request for Bids Open - National 1,200,000.00 0.00 Canceled 2017-10-11 2017-10-16 2017-11-03 2017-11-13 2017-12-01 2017-12-13 2018-01-10 road leading to Garni Stone S rcuit Development nvelope 5 ymphony TUR-01-01-1 / Rehabilitation Heritage Hub and Tourism Ci Single Stage - One E 1,496,995.5 2019-09-3 of road leading to Garni Ston IBRD / 85720 Post Request for Bids Open - National 1,427,000.00 Completed 2018-02-22 2018-03-05 2018-02-27 2018-03-19 2018-03-27 2018-04-16 2018-04-26 2018-05-07 2018-06-07 2018-06-19 rcuit Development nvelope 9 0 e Symphony TUR-06 / Rehabilitation of Ro Heritage Hub and Tourism Ci Single Stage - One E 1,901,802.7 2019-04-2 IBRD / 85720 Post Request for Bids Open - National 2,029,309.00 Completed 2018-05-11 2018-05-20 2018-05-16 2018-05-24 2018-06-13 2018-06-21 2018-07-13 2018-07-11 2018-08-24 2018-07-27 ad Segment Leading to Tatev rcuit Development nvelope 6 1 Monastery TUR-07 / Streets Rehabilitati on of Kumayri Historical Cent Heritage Hub and Tourism Ci Single Stage - One E 2,108,291.7 2019-03-2 IBRD / 85720 Post Request for Bids Open - National 2,146,640.88 Completed 2018-07-16 2018-07-12 2018-07-19 2018-07-12 2018-08-16 2018-08-09 2018-09-15 2018-08-24 2018-10-27 2018-09-04 er in Gyumri rcuit Development nvelope 8 6 (consist of 2 Lots) TUR-08 / Reconstruction of t Heritage Hub and Tourism Ci Single Stage - One E 2019-07-1 IBRD / 85720 Post Request for Bids Open - National 495,000.00 412,795.18 Completed 2018-11-05 2018-11-05 2018-11-10 2018-11-08 2018-12-08 2018-12-06 2019-01-07 2018-12-12 2019-02-18 2018-12-27 he Road Leading to "Sochut" rcuit Development nvelope 8 Dendropark TUR-02-01 / Improvement of Heritage Hub and Tourism Ci Single Stage - One E 2020-05-0 IBRD / 85720 Post Request for Bids Open - National 224,000.00 193,024.76 Completed 2019-07-26 2019-07-25 2019-07-29 2019-08-02 2019-08-26 2019-08-23 2019-09-25 2019-09-06 2019-11-06 2019-09-20 Khor Virap Monastery Area rcuit Development nvelope 4 TUR-PPI-01 / Provision of Util ity Infrastructure for Areni Wi ne Hotel: Lot 1 Gas Supply System for Heritage Hub and Tourism Ci Single Stage - One E 1,154,118.7 2021-03-2 IBRD / 85720 Post Request for Bids Open - National 1,337,000.00 Completed 2019-12-10 2019-12-10 2019-12-15 2019-12-11 2020-01-19 2020-01-14 2020-02-18 2020-02-14 2020-03-31 2020-04-07 Areni Wine Hotel; rcuit Development nvelope 0 6 Lot 2 Water supply and sewa ge system of Areni Wine Hot el ; Lot 3 Electricity and interne t Supply System for Areni Wi TUR-03 ne / Goris Hub Regener Hotel. ation Lot 1: Restoration of the right bank of Vararakn River, Heritage Hub and Tourism Ci Single Stage - One E 1,851,790.8 2021-07-2 Lot 2: Restoration of the hist IBRD / 85720 Post Request for Bids Open - National 4,714,000.00 Completed 2019-12-15 2019-12-17 2019-12-20 2019-12-17 2020-01-24 2020-01-21 2020-02-23 2020-02-14 2020-04-05 2020-04-08 rcuit Development nvelope 9 9 orical-cultural environment o f the central part of Goris tow n, Lot 3: Renovation of historica l residential houses in the ce ntral part of Goris TUR-04-1 / Partial restoratio Heritage Hub and Tourism Ci Single Stage - One E 2020-11-2 n and reinforcement of monu IBRD / 85720 Post Request for Bids Open - National 309,000.00 0.00 Canceled 2020-02-12 2020-02-12 2020-02-17 2020-02-15 2020-03-16 2020-03-13 2020-04-15 2020-05-27 rcuit Development nvelope 3 ments in the historical capita l of Armenia Dvin TUR-03-2 / Restoration of th Heritage Hub and Tourism Ci Single Stage - One E 2021-09-2 e historical-cultural environm IBRD / 85720 Post Request for Bids Open - National 2,390,000.00 0.00 Canceled 2020-02-21 2020-02-25 2020-02-26 2020-02-27 2020-03-25 2020-03-25 2020-04-24 2020-05-12 2020-06-05 rcuit Development nvelope 8 ent of the central part of Gori s town TUR-04-1-2 / Partial restorati on and reinforcement of mon Heritage Hub and Tourism Ci Single Stage - One E 2021-01-0 IBRD / 85720 Post Request for Bids Open - National 309,000.00 0.00 Canceled 2020-03-30 2020-03-30 2020-04-04 2020-05-02 2020-04-27 2020-06-01 2020-07-13 uments in the historical capit rcuit Development nvelope 9 al of Armenia Dvin TUR-04-1-3 / Partial restorati on and reinforcement of mon Heritage Hub and Tourism Ci Single Stage - One E 2021-03-0 IBRD / 85720 Post Request for Bids Open - National 305,000.00 0.00 Canceled 2020-05-22 2020-05-21 2020-05-27 2020-06-24 2020-06-18 2020-07-24 2020-09-04 uments in the historical capit rcuit Development nvelope 3 al of Armenia Dvin TUR-04-1-4 / Partial restorati on and reinforcement of mon Heritage Hub and Tourism Ci Single Stage - One E 2021-05-2 IBRD / 85720 Post Request for Bids Open - National 305,000.00 246,929.67 Signed 2020-07-10 2020-07-21 2020-07-15 2020-07-22 2020-08-12 2020-08-19 2020-09-11 2020-09-07 2020-10-23 2020-11-26 uments in the historical capit rcuit Development nvelope 1 al of Armenia Dvin ТUR-12 / Reconstruction of Y Heritage Hub and Tourism Ci Single Stage - One E 3,962,375.4 2022-04-1 IBRD / 85720 Post Request for Bids Open - National 5,108,000.00 Signed 2020-07-06 2020-07-06 2020-07-08 2020-07-09 2020-08-12 2020-08-10 2020-09-10 2020-08-21 2020-10-22 2020-11-07 erevan-Lanjazat-Garni road rcuit Development nvelope 5 5 ТUR-01-2 / Reconstruction of Heritage Hub and Tourism Ci Single Stage - One E 2021-11-2 IBRD / 85720 Post Request for Bids Open - National 450,000.00 429,538.72 Signed 2020-12-21 2021-03-26 2020-12-26 2021-03-26 2021-01-23 2021-04-23 2021-02-22 2021-05-05 2021-03-27 2021-06-19 the road to Khosrov Forest rcuit Development nvelope 2 TUR-11.6 / Improvement of Heritage Hub and Tourism Ci Single Stage - One E 2022-01-2 IBRD / 85720 Post Request for Bids Open - National 122,000.00 0.00 Canceled 2021-04-16 2021-04-09 2021-04-21 2021-04-09 2021-05-19 2021-05-07 2021-06-18 2021-07-30 Gndevank Hiking Trail rcuit Development nvelope 6 TUR-11.2 / Rehabilitation, Re storation of Shahumyan, V. V Heritage Hub and Tourism Ci Single Stage - One E 2022-09-2 ardanyan, Myasnikyan, Melik IBRD / 85720 Post Request for Bids Open - National 1,612,000.00 0.00 Canceled 2021-04-15 2021-04-09 2021-04-20 2021-04-09 2021-05-18 2021-05-10 2021-06-17 2021-07-29 rcuit Development nvelope 2 Adamyan and Charents Stree ts and Construction of the All ey Leading to “Qarayts” Request for Bids - TUR-11.2.3.6 / TUR 11.2.3.6 Heritage Hub and Tourism Ci Single Stage - One E Small Works SPD 3,021,754.4 2022-11-2 Reconstruction of the Roads IBRD / 85720 Post Request for Bids Open - National 3,072,000.00 Signed 2021-05-31 2021-05-25 2021-06-05 2021-05-25 2021-07-17 2021-07-06 2021-08-16 2021-07-21 2021-09-27 2021-08-15 rcuit Development nvelope (1 envelope proce 9 1 and Tourism Infrastructure of ss) Jermuk Request for Bids - ТUR-10.1 / Improvement of t Heritage Hub and Tourism Ci Single Stage - One E Small Works SPD 1,119,224.9 2023-02-0 IBRD / 85720 Post Request for Bids Open - National 1,106,000.00 Signed 2021-07-01 2021-06-24 2021-07-06 2021-06-24 2021-08-03 2021-07-22 2021-09-02 2021-08-05 2021-10-14 2021-08-21 he nearest area of the Garni rcuit Development nvelope (1 envelope proce 3 6 temple ss) Request for Bids - TUR-03.2-3 / Restoration of t Heritage Hub and Tourism Ci Single Stage - One E Small Works SPD 2,884,340.8 2023-02-2 he Historical-Cultural Environ IBRD / 85720 Post Request for Bids Open - National 2,796,000.00 Signed 2021-07-22 2021-07-09 2021-07-27 2021-07-23 2021-08-24 2021-08-06 2021-09-23 2021-09-10 2021-11-04 2021-09-19 rcuit Development nvelope (1 envelope proce 2 7 ment of the Central part of G ss) oris Town Request for Bids - TUR-05 / Improvement of th Heritage Hub and Tourism Ci Single Stage - One E Small Works SPD 2022-04-0 e Area Near the “Zorats Qare IBRD / 85720 Post Request for Bids Open - National 278,000.00 279,178.91 Signed 2021-07-22 2021-06-29 2021-07-27 2021-06-29 2021-08-24 2021-07-27 2021-09-23 2021-08-23 2021-11-04 2021-09-15 rcuit Development nvelope (1 envelope proce 3 r” Historical and Cultural Res ss) erve Page 1 Request for Bids - TUR-13.2 / Preparatory Work Heritage Hub and Tourism Ci Single Stage - One E Small Works SPD 1,801,475.1 2022-09-2 for the Reconstruction of the IBRD / 85720 Post Request for Bids Open - National 1,600,000.00 Signed 2021-07-22 2021-07-19 2021-07-27 2021-07-19 2021-08-24 2021-08-16 2021-09-23 2021-09-03 2021-11-04 2021-10-11 rcuit Development nvelope (1 envelope proce 6 0 "Barekamutyun" Town Park i ss) n Gyumri TUR-11.6-2 / Improvement o Heritage Hub and Tourism Ci Single Stage - One E Other (with field f 2022-06-0 IBRD / 85720 Post Request for Bids Open - National 130,000.00 0.00 Canceled 2021-08-27 2021-08-02 2021-09-01 2021-08-02 2021-09-29 2021-08-30 2021-10-29 2021-12-03 f Gndevank Hiking Trail rcuit Development nvelope or explanation) 1 TUR-09 / Rehabilitation of th Heritage Hub and Tourism Ci Single Stage - One E 2022-02-1 IBRD / 85720 Post Request for Bids Open - National 1,056,000.00 0.00 Canceled 2020-11-04 2020-11-03 2020-11-09 2020-11-03 2020-12-07 2020-12-01 2021-01-06 2021-02-17 e road leading to old Khndzor rcuit Development nvelope 2 esk TUR-11.6-3 / Improvement o Heritage Hub and Tourism Ci Request for Quota Single Stage - One E Other (with field f 2022-05-0 IBRD / 85720 Post Open - National 130,000.00 0.00 Canceled 2021-09-28 2021-11-02 f Gndevank hiking trail rcuit Development tions nvelope or explanation) 1 ТUR-06-2 / Reconstruction of Request for Bids - the damaged landslide sectio Heritage Hub and Tourism Ci Single Stage - One E Small Works SPD 2023-04-2 IBRD / 85720 Post Request for Bids Open - National 324,000.00 0.00 Canceled 2022-08-16 2022-08-12 2022-08-21 2022-08-12 2022-09-18 2022-09-09 2022-10-18 2022-11-29 n of the road leading to Tate rcuit Development nvelope (1 envelope proce 8 v monastery complex ss) ТUR-06-2-2 / Reconstruction Request for Bids - of the damaged landslide sec Heritage Hub and Tourism Ci Single Stage - One E Small Works SPD 2023-06-0 IBRD / 85720 Post Request for Bids Open - National 307,000.00 0.00 Signed 2022-09-22 2022-09-16 2022-09-27 2022-09-16 2022-10-25 2022-10-14 2022-11-24 2022-12-08 2023-01-05 tion of the road leading to Ta rcuit Development nvelope (1 envelope proce 4 tev monastery complex ss) Request for Bids - TUR-11.4/TUR-11.5.6 / Road Heritage Hub and Tourism Ci Single Stage - One E Small Works SPD 2023-12-0 Construction works in Jermuk IBRD / 85720 Post Request for Bids Open - National 929,000.00 0.00 Canceled 2022-10-24 2022-10-18 2022-10-29 2022-10-18 2022-11-26 2022-11-15 2022-12-26 2023-02-06 rcuit Development nvelope (1 envelope proce 3 community (2 Lots) ss) Request for Bids - TUR-11.4-2/TUR-11.5.6-2 / R Heritage Hub and Tourism Ci Single Stage - One E Small Works SPD Under Imple 2024-02-1 IBRD / 85720 Post Request for Bids Open - National 861,000.00 0.00 2022-12-28 2022-12-26 2023-01-02 2022-12-26 2023-02-06 2023-01-30 2023-03-08 2023-04-28 2023-04-19 econstruction of roads in Jer rcuit Development nvelope (1 envelope proce mentation 3 muk (2 Lots) ss) TUR-13.1/ТUR-13.4 / Rehabil Request for Bids - itation of Khanjian and Tchai Heritage Hub and Tourism Ci Single Stage - One E Small Works SPD 2024-04-1 IBRD / 85720 Post Request for Bids Open - National 3,891,000.00 0.00 Signed 2022-12-28 2022-12-29 2023-01-02 2022-12-29 2023-02-06 2023-02-03 2023-03-08 2023-03-02 2023-04-19 kovsky streets and Haghtana rcuit Development nvelope (1 envelope proce 8 k Avenue of Gyumri (2 Lots) ss) ТUR-15 / Major Rehabilitatio Request for Bids - n of the Road to Marmashen Heritage Hub and Tourism Ci Single Stage - One E Small Works SPD 2024-04-1 IBRD / 85720 Post Request for Bids Open - National 1,969,000.00 0.00 Signed 2022-12-28 2022-12-29 2023-01-02 2022-12-29 2023-02-06 2023-02-10 2023-03-08 2023-03-06 2023-04-19 Monastic Complex and Impro rcuit Development nvelope (1 envelope proce 3 vement of the Adjacent Area ss) TUR-13.5/TUR-13.6 / Restora Request for Bids - tion of Achemyan, Hanesoghl Heritage Hub and Tourism Ci Single Stage - One E Small Works SPD 2024-05-2 IBRD / 85720 Post Request for Bids Open - National 3,987,000.00 0.00 Signed 2023-02-15 2023-03-20 2023-02-20 2023-03-20 2023-03-20 2023-04-17 2023-04-19 2023-04-28 2023-05-31 yan, Jivani, Teryan and Nalba rcuit Development nvelope (1 envelope proce 5 ndyan streets of Gyumri (2 L ss) ots). TUR-13.3 / "Restoration of th Request for Bids - e Park Adjacent to the St. Am Heritage Hub and Tourism Ci Single Stage - One E Small Works SPD Under Imple 2024-09-2 enaprkich Church and Right IBRD / 85720 Post Request for Bids Open - National 2,709,000.00 0.00 2023-04-19 2023-04-28 2023-04-24 2023-04-28 2023-05-22 2023-05-30 2023-06-21 2023-06-09 2023-08-02 rcuit Development nvelope (1 envelope proce mentation 5 and Left Sections of the Adja ss) cent Abovyan Street", TUR-1 3.3 GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual LEID-NCS-GIS-01 / Geograph ic Information System (GIS) i mplementation services for G Single Stage - One E Under Imple IBRD / 85720 Institutional Development Post Request for Bids Open - National 80,000.00 0.00 2023-04-21 2023-05-25 2023-04-28 2023-05-25 2023-05-26 2023-06-15 2023-06-09 2023-07-03 2024-12-24 egharkunik Marz (5 enlarged nvelope mentation communities: Sevan, Gavar, Martuni, Vardenis, Chambara k) of the Republic of Armenia CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual LPD-01 / Development of Pro ject Design and Author's Sup Heritage Hub and Tourism Ci Consultant Qualifi ervision for the Rehabilitation IBRD / 85720 Post Open - National 50,000.00 44,049.21 Completed 2017-11-22 2017-12-06 2017-12-06 2017-12-08 2018-01-10 2017-12-28 2018-01-17 2018-01-13 2018-02-07 2018-01-12 2019-06-22 2019-08-04 rcuit Development cation Selection of Road Segment Leading to Tatev Monastery Sub-project LV-01 / Detailed Measureme Heritage Hub and Tourism Ci Consultant Qualifi IBRD / 85720 Post Open - National 800.00 686.43 Completed 2018-01-09 2018-01-09 2018-01-19 2018-01-17 2018-02-16 2018-02-16 2018-02-23 2018-02-20 2018-03-16 2018-02-23 2018-05-15 2018-04-06 nt, Assets Inventory and Valu rcuit Development cation Selection ation LTS-01 / Technical supervisi on of construction for Rehabil Heritage Hub and Tourism Ci Consultant Qualifi IBRD / 85720 Post Open - National 18,560.00 26,806.60 Completed 2018-04-13 2018-04-09 2018-04-27 2018-04-09 2018-05-25 2018-05-04 2018-06-15 2018-05-18 2018-07-06 2018-05-18 2019-10-29 2021-05-21 itation of road leading to Gar rcuit Development cation Selection ni Stone Symphony LTS-02 / Technical supervisi on of construction for Rehabil Heritage Hub and Tourism Ci Consultant Qualifi IBRD / 85720 Post Open - National 24,360.00 24,136.16 Completed 2018-05-17 2018-05-23 2018-05-24 2018-05-30 2018-06-21 2018-06-19 2018-07-12 2018-07-06 2018-08-02 2018-07-06 2019-03-30 2019-08-04 itation of Road Segment Lea rcuit Development cation Selection ding to Tatev Monaster LTS-03 / Technical Supervisi on of construction for "Stree Heritage Hub and Tourism Ci Consultant Qualifi IBRD / 85720 Post Open - National 23,700.00 33,893.03 Signed 2018-08-02 2018-07-27 2018-08-16 2018-07-27 2018-09-13 2018-08-27 2018-10-04 2018-08-31 2018-10-25 2018-09-03 2019-03-24 ts Rehabilitation of Kumayri rcuit Development cation Selection Historical Center in Gyumri LTS-04 / Technical Supervisi Heritage Hub and Tourism Ci Consultant Qualifi on for "Reconstruction of the IBRD / 85720 Post Open - National 7,800.00 7,745.90 Completed 2018-11-21 2018-11-29 2018-11-28 2018-12-20 2018-12-24 2019-01-25 2019-01-14 2019-02-04 2019-02-04 2019-02-07 2019-07-04 2019-09-16 rcuit Development cation Selection Road Leading to "Sochut" De ndropark" Page 2 AUD-18 / AUDIT OF THE LOC AL ECONOMY AND INFRASTR Heritage Hub and Tourism Ci Consultant Qualifi UCTURE DEVELOPMENT PROJ IBRD / 85720 Post Open - National 6,443.00 24,124.85 Completed 2018-12-04 2018-11-30 2018-12-11 2019-01-06 2018-12-24 2019-01-27 2018-12-28 2019-02-17 2018-12-28 2019-08-16 2019-06-27 rcuit Development cation Selection ECT (LEID) FOR THE PERIOD FROM DECEMBER 29, 2016 TO DECEMBER 31, 2018 LPD-06 / Design and Author' s Supervision for the Utility In Heritage Hub and Tourism Ci Consultant Qualifi IBRD / 85720 Post Open - National 28,070.00 0.00 Completed 2019-03-27 2019-03-21 2019-04-10 2019-04-04 2019-05-15 2019-04-29 2019-05-22 2019-05-14 2019-06-12 2019-05-14 2019-07-12 2019-12-03 frastructure of "Areni Wine h rcuit Development cation Selection otel" in Areni community LGS-01 / The geological and geophysical surveys of the ro Heritage Hub and Tourism Ci Consultant Qualifi ad section bypassing the la IBRD / 85720 Post Open - National 20,760.00 22,832.32 Completed 2019-05-14 2019-05-08 2019-05-21 2019-06-14 2019-06-27 2019-07-25 2019-07-27 2019-08-14 2019-08-17 2019-08-14 2019-09-26 2020-02-24 rcuit Development cation Selection ndslide of road leading to T atev monastery sub-project LTS-05 / Technical Supervisi Heritage Hub and Tourism Ci Consultant Qualifi on of construction for "Khor V IBRD / 85720 Post Open - National 3,680.00 3,677.73 Signed 2019-08-26 2019-08-16 2019-09-02 2019-08-26 2019-09-28 2019-09-18 2019-10-19 2019-09-27 2019-11-09 2019-09-30 2020-05-07 rcuit Development cation Selection irap Monastery Area Landsca ping". LTS-06 / Technical Supervisi on of Construction for Provisi Heritage Hub and Tourism Ci Consultant Qualifi IBRD / 85720 Post Open - National 16,000.00 15,801.97 Completed 2019-12-15 2019-12-16 2019-12-22 2019-12-23 2020-01-17 2020-03-23 2020-02-07 2020-04-10 2020-02-28 2020-04-14 2021-02-22 2021-01-30 on of Utility Infrastructure for rcuit Development cation Selection “Areni Wine Hotel” LTS-07 / Technical Supervisi Heritage Hub and Tourism Ci Consultant Qualifi on of Construction for Goris IBRD / 85720 Post Open - National 48,000.00 41,188.69 Signed 2019-12-15 2019-12-16 2019-12-22 2019-12-23 2020-01-17 2020-02-15 2020-02-07 2020-03-26 2020-02-28 2020-04-04 2021-06-22 rcuit Development cation Selection Hub Regeneration LPD-09 / Design for the “Im Heritage Hub and Tourism Ci Consultant Qualifi IBRD / 85720 Post Open - National 35,500.00 31,187.16 Signed 2019-12-30 2019-12-30 2020-01-20 2020-01-30 2020-03-04 2020-03-23 2020-04-03 2020-04-10 2020-05-08 2020-04-17 2020-10-05 2020-11-19 provement of Garni Temple a rcuit Development cation Selection rea” LPD-08 / Design for the “Re Heritage Hub and Tourism Ci Consultant Qualifi habilitation of the road leadi IBRD / 85720 Post Open - National 38,000.00 229,192.15 Signed 2019-12-30 2020-01-30 2020-01-20 2020-02-26 2020-03-11 2020-04-06 2020-04-10 2020-04-20 2020-05-15 2020-04-22 2020-08-15 2020-07-23 rcuit Development cation Selection ng to Old Khndzoresk” LCD-01 / Development of Co ncept Design for the Heritag Heritage Hub and Tourism Ci Quality Based Sel Open - Internationa IBRD / 85720 Post 114,815.00 178,779.00 Completed 2020-01-20 2020-01-09 2020-02-10 2020-01-23 2020-04-10 2020-04-06 2020-05-08 2020-06-19 2020-06-07 2020-07-28 2020-07-07 2020-07-28 2020-08-11 2020-12-22 2020-11-09 2021-09-28 e hub regeneration in Areni v rcuit Development ection l illage and adjacent villages LTS-08 / Technical supervisi on of the "Partial restoration Heritage Hub and Tourism Ci Consultant Qualifi IBRD / 85720 Post Open - National 3,039.00 5,443.18 Signed 2020-02-13 2020-02-07 2020-02-27 2020-02-26 2020-04-02 2020-04-20 2020-04-23 2020-05-21 2020-05-14 2020-05-28 2020-11-10 and reinforcement of monum rcuit Development cation Selection ents in the historical capital o f Armenia Dvin". LS-02 / International Visitor Heritage Hub and Tourism Ci Consultant Qualifi IBRD / 85720 Post Open - National 246,000.00 0.00 Canceled 2020-02-14 2020-02-27 2020-03-06 2020-02-27 2020-04-19 2020-05-19 2020-06-09 2021-11-01 Exit Survey on National Level rcuit Development cation Selection AUD-19 / "AUDIT OF THE AR MENIAN TERRITORIAL DEVEL OPMENT FUND and AUDIT OF Heritage Hub and Tourism Ci Consultant Qualifi IBRD / 85720 Post Open - National 30,918.00 23,973.29 Completed 2020-03-13 2020-03-09 2020-03-20 2020-03-18 2020-04-29 2020-04-10 2020-05-20 2020-05-05 2020-06-10 2020-05-07 2020-09-18 2020-07-29 THE LOCAL ECONOMY AND I rcuit Development cation Selection NFRASTRUCTURE DEVELOPM ENT (LEID) PROJECT FOR THE YEAR ENDED DECEMBER 31, 2019". LPD-13 / Modification of the sub-project design and autho Heritage Hub and Tourism Ci Consultant Qualifi IBRD / 85720 Post Open - National 46,280.00 45,768.21 Completed 2020-04-27 2020-04-23 2020-05-18 2020-04-27 2020-07-01 2020-05-21 2020-07-31 2020-05-27 2020-09-04 2020-05-28 2021-02-01 2020-06-23 r's supervision for the ”Reno rcuit Development cation Selection vation of Garni-Lanjazat road ”. LTS-09 / Technical supervisi Heritage Hub and Tourism Ci Consultant Qualifi on of the ”Reconstruction of IBRD / 85720 Post Open - National 50,780.00 49,189.36 Signed 2020-07-31 2020-08-05 2020-08-21 2020-08-13 2020-10-04 2020-09-24 2020-11-03 2020-10-09 2020-11-24 2020-10-13 2022-05-18 rcuit Development cation Selection Garni-Lanjazat road”. LPD-16 / Design and author' s supervision of Improvemen Heritage Hub and Tourism Ci Consultant Qualifi IBRD / 85720 Post Open - National 5,300.00 5,048.87 Signed 2020-09-11 2020-10-14 2020-09-25 2020-10-15 2020-11-08 2020-11-13 2020-12-08 2020-12-16 2021-01-12 2020-12-19 2021-07-18 t of the green zone near Khor rcuit Development cation Selection Virap Monastery, installation of sales pavilions LM-01 / Consultancy Service for the LEID Project Performa Heritage Hub and Tourism Ci Consultant Qualifi IBRD / 85720 Post Open - National 291,000.00 260,666.35 Signed 2021-01-18 2021-01-14 2021-02-01 2021-02-01 2021-03-01 2021-02-25 2021-03-15 2021-04-13 2021-04-01 2021-06-27 2023-04-01 nce Monitoring & Evaluation i rcuit Development cation Selection n the selected regions of Arm enia LTS-10 / Technical supervisi Heritage Hub and Tourism Ci Consultant Qualifi on of the “Rehabilitation of t IBRD / 85720 Post Open - National 12,500.00 0.00 Canceled 2020-11-30 2020-12-14 2020-12-21 2021-02-03 2021-03-05 2021-03-26 2022-03-26 rcuit Development cation Selection he road leading to old Khndz oresk” LTS-11 / Technical supervisi on of the construction works for sub-projects of Rehabilita tion of the road leading from Heritage Hub and Tourism Ci Consultant Qualifi IBRD / 85720 Post Open - National 20,000.00 20,768.52 Signed 2021-02-02 2021-03-17 2021-02-16 2021-04-29 2021-03-16 2021-05-26 2021-03-30 2021-07-06 2021-04-06 2021-07-10 2021-12-02 "Symphony of Stones" natura rcuit Development cation Selection l monument to "Khosrov Fore st State Reserve" and “Impro vement of the adjacent territ ory of the Garni temple” LTS-12 / Technical supervisi on of construction works for s ub-project "Rehabilitation of t Heritage Hub and Tourism Ci Consultant Qualifi IBRD / 85720 Post Open - National 16,300.00 16,855.61 Signed 2021-02-02 2021-03-25 2021-02-16 2021-04-30 2021-03-16 2021-06-01 2021-03-30 2021-07-06 2021-04-06 2021-07-10 2022-04-01 he road leading to old Khndz rcuit Development cation Selection oresk" & "Improvement of th e area near the Zorats Karer monument" AUD-20 / AUDIT OF THE LOC AL ECONOMY AND INFRASTR Consultant Qualifi UCTURE DEVELOPMENT PROJ IBRD / 85720 Institutional Development Post Open - National 42,000.00 28,456.65 Completed 2021-03-29 2021-03-24 2021-04-12 2021-04-23 2021-05-10 2021-04-30 2021-05-15 2021-05-14 2021-05-25 2021-05-15 2021-07-09 2021-07-30 cation Selection ECT (LEID) FOR THE YEAR EN DING DECEMBER 31, 2020 LPD-17 / Design and author' s supervision of Renovation, i mprovement and landscape gardening of the Drinking Gal Heritage Hub and Tourism Ci Consultant Qualifi IBRD / 85720 Post Open - National 49,000.00 51,758.75 Signed 2021-04-09 2021-05-07 2021-04-23 2021-05-27 2021-05-21 2021-06-18 2021-05-26 2021-07-06 2021-06-05 2021-07-10 2022-06-05 lery alleys, construction of pa rcuit Development cation Selection vilions and Information Cente r and Construction of the acc ess road to the “Yeghnik” sta tue and to the observation d eck Page 3 LPD-18 / Design and author' s supervision of the develop ment of design for the recons truction of the 320-meters of Heritage Hub and Tourism Ci Consultant Qualifi IBRD / 85720 Post Open - National 10,200.00 11,003.32 Signed 2021-07-05 2021-06-07 2021-07-26 2021-09-23 2021-08-23 2021-10-04 2021-08-28 2021-11-10 2021-09-07 2021-11-18 2022-09-07 not restored landslide sectio rcuit Development cation Selection n of the 6-kilometer road lea ding from the "Devil's Bridge " natural monument to Tatev monastery complex LEX-01-2 / Investigation of t Heritage Hub and Tourism Ci Consultant Qualifi he technical state of the exis IBRD / 85720 Post Open - National 2,600.00 2,618.01 Signed 2021-08-09 2021-08-06 2021-08-23 2021-09-23 2021-09-20 2021-10-07 2021-09-25 2021-12-08 2021-10-05 2021-12-11 2021-11-14 rcuit Development cation Selection ting building of the Drinking Gallery LTS-13 / Technical supervisi on of construction works for Rehabilitation, Restoration of Shahumyan, V. Vardanyan, M Heritage Hub and Tourism Ci Consultant Qualifi IBRD / 85720 Post Open - National 40,000.00 43,677.23 Signed 2021-08-11 2021-07-19 2021-08-25 2021-07-29 2021-09-22 2021-08-13 2021-10-06 2021-08-17 2021-10-13 2021-08-21 2022-12-07 yasnikyan, Melik Adamyan a rcuit Development cation Selection nd Charents Streets and Con struction of the Alley, Rehabil itation of Mashtots street, Im provement of Gndevank Hiki ng Trail LEX-01 / Investigation of the Heritage Hub and Tourism Ci Consultant Qualifi technical state of the existin IBRD / 85720 Post Open - National 1,700.00 0.00 Canceled 2021-04-09 2021-03-31 2021-04-23 2021-04-26 2021-05-21 2021-05-10 2021-05-26 2021-06-05 2021-07-15 rcuit Development cation Selection g building of the Drinking Gal lery LPD-19 / Designing and auth Heritage Hub and Tourism Ci Consultant Qualifi or’s supervision of the works IBRD / 85720 Post Open - National 96,390.00 96,558.53 Signed 2021-08-04 2021-08-06 2021-08-25 2021-09-29 2021-09-22 2021-10-15 2021-09-27 2021-10-25 2021-10-07 2021-10-30 2022-12-01 rcuit Development cation Selection under Component 1 and Com ponent 4. LPD-21 / Designing and auth Heritage Hub and Tourism Ci Consultant Qualifi or’s supervision of the works IBRD / 85720 Post Open - National 114,105.00 14,965.06 Signed 2021-08-04 2021-08-06 2021-08-25 2021-09-10 2021-09-22 2021-10-15 2021-09-27 2021-10-21 2021-10-07 2021-10-27 2023-03-31 rcuit Development cation Selection under Component 5 LTS-14 / Technical supervisi on of Construction of "Prepar Heritage Hub and Tourism Ci Consultant Qualifi IBRD / 85720 Post Open - National 18,735.00 26,493.21 Signed 2021-08-04 2021-08-13 2021-08-11 2021-09-03 2021-09-08 2021-10-05 2021-09-15 2021-10-07 2021-09-22 2021-10-17 2022-08-08 atory work for the reconstruc rcuit Development cation Selection tion of the "Barekamutyun" t own park in Gyumri". LPD-20 / Designing and auth Heritage Hub and Tourism Ci Consultant Qualifi or’s supervision of the works IBRD / 85720 Post Open - National 68,345.00 67,559.78 Signed 2021-08-04 2021-08-06 2021-08-11 2021-09-03 2021-09-08 2021-09-27 2021-09-13 2021-10-18 2021-09-23 2021-10-23 2023-03-02 rcuit Development cation Selection under Component 3 LPD-23 / Designing and auth or’s supervision of the works under Component 2- «Improv ement of Dvin ancient site an Heritage Hub and Tourism Ci Consultant Qualifi IBRD / 85720 Post Open - National 43,930.00 0.00 Canceled 2021-09-13 2021-10-08 2021-09-27 2021-10-26 2021-11-26 2021-12-15 2021-12-01 2021-12-11 2023-02-04 d the adjacent area and repl rcuit Development cation Selection enishment with tourist infrast ructure» of «The archeologic al site, historical town Dvin of Armenia» sub-project. LPD-24 / Designing and auth or’s supervision of the works under “Major Rehabilitation o Heritage Hub and Tourism Ci Consultant Qualifi IBRD / 85720 Post Open - National 70,770.00 49,971.02 Signed 2021-09-14 2021-09-29 2021-09-21 2021-10-25 2021-11-20 2021-12-10 2021-11-25 2021-12-30 2021-12-05 2022-01-10 2023-01-29 f the Road to Marmashen Mo rcuit Development cation Selection nastic Complex and Improve ment of the Adjacent Area” s ub-project. DMO-01 / Preparation of Des tination Management Organi Quality And Cost- Open - Internationa IBRD / 85720 Institutional Development Post 307,000.00 189,645.00 Signed 2021-11-01 2021-10-21 2021-11-29 2021-12-07 2022-01-24 2022-02-04 2022-02-21 2022-03-18 2022-03-21 2022-05-12 2022-04-11 2022-05-24 2022-05-16 2022-07-01 2022-11-12 zation (DMO) Development M Based Selection l odel for the Republic of Arme nia LPD-26 / Designing and Auth or’s Supervision of the Rehab Heritage Hub and Tourism Ci Consultant Qualifi IBRD / 85720 Post Open - National 57,160.00 61,848.38 Signed 2022-03-02 2022-04-07 2022-03-16 2022-05-18 2022-04-20 2022-05-20 2022-05-11 2022-06-15 2022-05-30 2022-06-16 2023-11-26 ilitation of Meghri Pokr Tagh ( rcuit Development cation Selection Small district) Tourism Infrast ructure LEX-02 / Expertise of Archite Heritage Hub and Tourism Ci Consultant Qualifi IBRD / 85720 Post Open - National 35,130.00 38,333.09 Signed 2022-03-22 2022-03-25 2022-03-29 2022-04-11 2022-05-03 2022-04-28 2022-05-08 2022-05-12 2022-05-18 2022-05-22 2023-05-18 ctural Design (16 projects). rcuit Development cation Selection LPD-27 / Designing and Auth or’s Supervision of the “Parti al Major Rehabilitation of Das Heritage Hub and Tourism Ci Consultant Qualifi IBRD / 85720 Post Open - National 62,130.00 71,330.80 Signed 2022-04-19 2022-05-12 2022-04-26 2022-06-03 2022-05-31 2022-07-14 2022-06-21 2022-09-14 2022-07-03 2022-09-24 2022-12-30 htadem Fortress, Establishm rcuit Development cation Selection ent of a Museum and Improv ement of the Area Adjoining t o the Monument”. LPD-29 / Design and Author’ s Supervision of the construc tion works provided under Co Heritage Hub and Tourism Ci Consultant Qualifi Under Implement mponent 2 of the “Improvem IBRD / 85720 Post Open - National 98,900.00 0.00 2022-06-21 2022-06-23 2022-07-05 2022-08-11 2022-08-09 2022-09-15 2022-08-30 2022-10-17 2022-09-11 2023-09-06 rcuit Development cation Selection ation ent of the Dvin Ancient Site a nd Adjacent Area and Additio n of Tourism Infrastructure” Subproject. LPD-28 / Design and Author’ s Supervision of the construc tion works provided under “R Heritage Hub and Tourism Ci Consultant Qualifi Under Implement IBRD / 85720 Post Open - National 28,800.00 0.00 2022-06-19 2022-06-23 2022-07-03 2023-04-03 2022-08-07 2023-05-10 2022-08-28 2023-06-12 2022-09-09 2023-02-06 econstruction and Strengthe rcuit Development cation Selection ation ning of the Drinking Gallery o f Jermuk City of the RA” com ponent. LPD-30 / Design and Author’ s Supervision of the improve Heritage Hub and Tourism Ci Consultant Qualifi Under Implement IBRD / 85720 Post Open - National 82,430.00 0.00 2022-07-13 2022-07-21 2022-07-27 2022-11-15 2022-09-05 2022-12-23 2022-09-26 2023-02-13 2022-10-08 2023-04-21 ment of the streets in Areni v rcuit Development cation Selection ation illage, marz of Vayots Dzor. LEID-QBS-MRA-01 / Tourism markets research and analysi Heritage Hub and Tourism Ci Quality Based Sel Open - Internationa IBRD / 85720 Post 285,000.00 0.00 Signed 2022-07-25 2022-09-13 2022-08-15 2022-10-27 2022-10-05 2022-12-12 2022-11-02 2023-01-09 2022-12-02 2023-01-27 2023-01-01 2023-02-17 2023-02-05 2023-06-05 s in Germany, France, Russia rcuit Development ection l and UAE countries LTS-15 / Technical supervisi on of construction works for t Heritage Hub and Tourism Ci Consultant Qualifi Under Implement he reconstruction of the dam IBRD / 85720 Post Open - National 3,800.00 0.00 2022-08-16 2022-08-29 2022-08-18 2022-12-02 2022-09-09 2022-12-20 2022-09-23 2023-03-07 2022-09-27 2023-08-13 rcuit Development cation Selection ation aged landslide section of the road leading to the Tatev mo nastery complex LEID-IVS-02 / International Vi Quality And Cost- Open - Internationa Under Implement IBRD / 85720 Institutional Development Post 300,000.00 0.00 2022-08-15 2022-09-06 2022-08-22 2022-09-07 2022-09-17 2022-10-05 2022-10-15 2022-11-04 2022-10-22 2022-11-14 2022-11-08 2022-11-22 2022-11-20 2023-11-20 sitor Survey on National Leve Based Selection l ation l Page 4 LPD-31 / Design and author supervision of construction of Heritage Hub and Tourism Ci Consultant Qualifi Under Implement IBRD / 85720 Post Open - National 75,600.00 0.00 2022-10-17 2022-12-15 2022-10-31 2022-12-27 2022-12-05 2023-01-31 2022-12-26 2023-03-06 2023-01-07 2023-08-05 the external engineering infr rcuit Development cation Selection ation astructures for 3 project acti vities. LTS-16 / Technical Supervisi Heritage Hub and Tourism Ci Consultant Qualifi on of Road Construction work IBRD / 85720 Post Open - National 15,000.00 0.00 Signed 2022-11-16 2023-01-24 2022-11-23 2023-04-03 2022-12-20 2023-04-21 2023-01-10 2023-05-30 2023-01-24 2023-11-20 rcuit Development cation Selection s in Jermuk community (2 Pro ject). LTS-17 / Technical supervisi Heritage Hub and Tourism Ci Consultant Qualifi IBRD / 85720 Post Open - National 59,100.00 0.00 Signed 2023-01-16 2023-01-26 2023-01-30 2023-01-31 2023-02-27 2023-03-22 2023-03-20 2023-04-03 2023-04-19 2024-04-18 on of the civil works (3 projec rcuit Development cation Selection ts). LTS-18 / Technical supervisi on of the Major Rehabilitation Heritage Hub and Tourism Ci Consultant Qualifi Under Implement of the Road to Marmashen M IBRD / 85720 Post Open - National 23,250.00 0.00 2023-02-07 2023-02-07 2023-02-14 2023-02-09 2023-03-14 2023-03-02 2023-04-04 2023-03-22 2023-04-18 2024-04-12 rcuit Development cation Selection ation onastic Complex and Improv ement of the Adjacent Area, Shirak Marz. Heritage Hub and Tourism Ci Consultant Qualifi TEST-1 / Test TF / A1063 Post Open - National 1.00 0.00 Canceled 2023-01-16 2023-01-18 2023-01-17 2023-01-18 2023-01-19 2023-01-20 2023-01-22 2023-01-23 rcuit Development cation Selection AUD-22 / AUDIT OF THE LOC AL ECONOMY AND INFRASTR Consultant Qualifi Under Implement UCTURE DEVELOPMENT PROJ IBRD / 85720 Institutional Development Post Open - National 20,000.00 0.00 2023-02-15 2023-02-09 2023-03-01 2023-03-22 2023-03-29 2023-04-10 2023-04-19 2023-04-28 2023-04-29 2023-12-30 cation Selection ation ECT (LEID) FOR THE YEAR EN DING DECEMBER 31, 2022. LTS-19 / Technical supervisi Heritage Hub and Tourism Ci Consultant Qualifi Under Implement IBRD / 85720 Post Open - National 73,500.00 0.00 2023-04-13 2023-04-21 2023-04-27 2023-04-26 2023-05-25 2023-05-17 2023-06-15 2023-05-30 2023-06-29 2024-08-22 on of the civil works (3 projec rcuit Development cation Selection ation ts). LEID-CQS-DF-01 / DEVELOP MENT OF THE CONTENT PRE Heritage Hub and Tourism Ci Consultant Qualifi Under Implement IBRD / 85720 Post Open - National 30,000.00 0.00 2023-06-05 2023-06-09 2023-06-10 2023-07-06 2023-07-08 2023-07-22 2023-11-19 SENTING THE CULTURAL-HIS rcuit Development cation Selection ation TORICAL HERITAGE OF THE D ASHADEM MUSEUM PLEID C- 2.2 / Rehabilitation of Goris Central Parks ; redev elopment of the Right Bank o f Goris River; restoration of H Heritage Hub and Tourism Ci Consultant Qualifi Open - Internationa TF / A1063 Prior 0.00 142,629.48 Signed 2016-10-21 2016-10-14 istorical and Architectural En rcuit Development cation Selection l vironment of the Central Part of Goris and development a Management Model for upgra ded infrastructures INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual LPD-02 / Autors supervision f or Construction For Rehabilit Heritage Hub and Tourism Ci IBRD / 85720 Post Direct Selection Direct 7,140.00 7,141.45 Completed 2018-04-26 2018-04-23 2018-05-06 2018-04-23 2018-05-30 2018-05-10 2019-09-22 2020-04-30 ation Of Road Leading To Gar rcuit Development ni Stone Symphony LPD-03/1 / Author's Supervis ion of construction for "Stree Heritage Hub and Tourism Ci IBRD / 85720 Post Direct Selection Direct 7,300.00 7,242.39 Signed 2018-08-02 2018-08-02 2018-08-12 2018-08-02 2018-09-05 2018-09-03 2019-02-02 ts Rehabilitation of Kumayri rcuit Development Historical Center in Gyumri LPD-04 / Geological researc h and Design development f Heritage Hub and Tourism Ci or the Rehabilitation of landsl IBRD / 85720 Post Direct Selection Direct 15,456.00 15,489.35 Completed 2018-12-14 2018-12-10 2018-12-22 2018-12-20 2019-01-15 2018-12-26 2019-02-04 2019-04-10 rcuit Development ide segment of road leading to Tatev monastery sub-proje ct. LPD-05 / Author's Supervisio Heritage Hub and Tourism Ci n of "Reconstruction of the R IBRD / 85720 Post Direct Selection Direct 1,980.00 1,986.01 Completed 2019-02-05 2019-01-30 2019-02-15 2019-02-18 2019-03-11 2019-02-19 2019-08-08 2019-09-16 rcuit Development oad Leading to "Sochut" Den dropark". LPD-07 / Author’s Supervisio Heritage Hub and Tourism Ci n of Construction of "Khor Vi IBRD / 85720 Post Direct Selection Direct 1,345.00 1,319.48 Completed 2019-09-20 2019-09-16 2019-09-30 2019-09-23 2019-11-09 2019-10-16 2020-05-07 2021-03-16 rcuit Development rap Monastery Area Landsca ping " LS-01 / Monitoring and Supe rvision of Tourism Internation al Visitor Survey on National Heritage Hub and Tourism Ci Individual Consult IBRD / 85720 Post Limited 12,600.00 12,533.21 Signed 2019-11-08 2019-11-04 2019-11-15 2019-11-19 2019-12-06 2019-12-06 2020-01-10 2019-12-06 2021-04-04 Level. rcuit Development ant Selection Baseline Data Assessment of the Armenia Local Economy and Infrastructure Developm ent Project LPD-10 / Author’s Supervisio Heritage Hub and Tourism Ci n of Construction of "Goris hu IBRD / 85720 Post Direct Selection Direct 18,790.00 18,781.89 Signed 2020-01-20 2020-01-09 2020-02-08 2020-01-21 2020-03-19 2020-02-29 2022-06-27 rcuit Development b regeneration". LPD-11 / Author's supervisio n of the "Partial restoration a Heritage Hub and Tourism Ci IBRD / 85720 Post Direct Selection Direct 1,823.00 1,744.37 Signed 2020-02-13 2020-02-07 2020-03-12 2020-02-25 2020-04-21 2020-03-25 2020-10-18 nd reinforcement of monume rcuit Development nts in the historical capital of Armenia Dvin". LPD-12 / Modification of the Heritage Hub and Tourism Ci subproject design for "Zorat IBRD / 85720 Post Direct Selection Direct 2,235.00 2,165.99 Completed 2020-03-04 2020-03-03 2020-03-14 2020-03-05 2020-05-18 2020-03-25 2020-06-17 2020-12-16 rcuit Development s Qarer Monument Tourism Z one". LNS-01 / Local Individual Co nsultancy Services for Touris Heritage Hub and Tourism Ci Individual Consult m Product Development und IBRD / 85720 Post Open 6,245.00 6,163.30 Signed 2020-03-04 2020-03-06 2020-05-08 2020-04-20 2020-05-29 2020-05-06 2020-07-03 2020-05-07 2020-10-31 rcuit Development ant Selection er the World Bank’s Local Ec onomy and Infrastructure De velopment Project LPD-14 / Update of the Desig n and Author’s Supervision of Heritage Hub and Tourism Ci IBRD / 85720 Post Direct Selection Direct 52,165.00 52,060.73 Terminated 2020-08-25 2020-08-19 2020-09-04 2020-08-31 2020-11-01 2020-09-09 2021-12-26 Reconstruction of tourism inf rcuit Development rastructure and streets of Jer muk city. LPD-15 / Update of Design a nd Author’s Supervision of Re Heritage Hub and Tourism Ci construction of beginning of t IBRD / 85720 Post Direct Selection Direct 5,150.00 5,235.99 Signed 2020-08-25 2020-09-01 2020-09-04 2020-09-07 2020-11-01 2020-09-16 2021-12-26 rcuit Development he road from Garni Symphon y of Stones monument to Kh osrov Forest State Reserve. Page 5 LIC-02 / Individual Consultan cy Services for Expertise Engi Heritage Hub and Tourism Ci Individual Consult neer under the World Bank’s IBRD / 85720 Post Open 12,600.00 0.00 Canceled 2020-09-22 2020-09-22 2020-11-10 2020-12-01 2021-01-05 2022-01-05 rcuit Development ant Selection Local Economy and Infrastruc ture Development Project. LIC-03 / Individual Consultan cy Services for Economic ana Heritage Hub and Tourism Ci Individual Consult lysis under the World Bank’s IBRD / 85720 Post Open 11,800.00 13,357.39 Terminated 2020-09-22 2020-09-22 2020-11-10 2020-10-14 2020-12-01 2020-10-15 2021-01-05 2020-10-17 2022-01-05 rcuit Development ant Selection Local Economy and Infrastruc ture Development Project. LIC-04 / Individual Consultan cy Services of Legal assistan Heritage Hub and Tourism Ci Individual Consult ce under the World Bank’s Lo IBRD / 85720 Post Open 11,600.00 11,578.97 Signed 2020-09-22 2020-09-22 2020-11-10 2020-11-25 2020-12-01 2020-12-01 2021-01-05 2020-12-03 2022-01-05 rcuit Development ant Selection cal Economy and Infrastructu re Development Project. LIC-02-2 / Individual Consult ancy Services for Expertise E Heritage Hub and Tourism Ci Individual Consult ngineer under the World Ban IBRD / 85720 Post Open 12,600.00 27,879.94 Signed 2021-03-24 2021-04-23 2021-04-26 2021-06-14 2021-05-03 2021-07-27 2021-05-15 2021-07-30 2022-05-15 rcuit Development ant Selection k’s Local Economy and Infras tructure Development Project LPD-22 / Author’s Supervisio n of Construction of "Prepara Heritage Hub and Tourism Ci IBRD / 85720 Post Direct Selection Direct 10,220.00 9,339.15 Signed 2021-08-04 2021-08-13 2021-08-14 2021-08-22 2021-09-27 2021-09-11 2022-08-13 tory work for the reconstructi rcuit Development on of the "Barekamutyun" to wn park in Gyumri". LIC-05 / Project Coordinator f Individual Consult or the LEID Project within the IBRD / 85720 Institutional Development Post Open 23,000.00 23,853.39 Terminated 2021-08-10 2021-08-03 2021-09-12 2021-10-14 2021-10-03 2021-10-27 2021-11-07 2021-11-02 2022-04-09 ant Selection Tourism Committee LPD-25 / Author’s Supervisio n of the ''Improvement of the Heritage Hub and Tourism Ci IBRD / 85720 Post Direct Selection Direct 1,730.00 1,786.90 Signed 2021-09-14 2021-09-22 2021-09-24 2021-09-23 2021-11-07 2021-10-17 2022-04-06 nearest area of the Zorats Q rcuit Development arer monument". LIC-06 / Individual Consultan cy Services for Economic ana Heritage Hub and Tourism Ci Individual Consult lysis under the World Bank’s IBRD / 85720 Post Direct 22,335.00 22,460.72 Terminated 2021-10-19 2021-10-19 2021-10-29 2021-10-20 2021-11-12 2021-10-20 2021-12-01 2021-10-21 2023-03-31 rcuit Development ant Selection Local Economy and Infrastruc ture Development Project LIC-07 / Individual Consultan cy Services for Economic ana Heritage Hub and Tourism Ci Individual Consult lysis under the World Bank’s IBRD / 85720 Post Limited 15,150.00 15,832.82 Signed 2022-04-06 2022-03-31 2022-04-11 2022-04-06 2022-04-16 2022-04-06 2022-05-05 2022-04-20 2023-03-31 rcuit Development ant Selection Local Economy and Infrastruc ture Development Project. LIC-01 / International Individ ual Consultancy Services for Leading Tourism Product Dev Heritage Hub and Tourism Ci Individual Consult IBRD / 85720 Post Open 43,435.00 0.00 Canceled 2020-03-04 2020-03-06 2020-05-08 2020-05-29 2020-07-03 2020-11-30 elopment activities under the rcuit Development ant Selection World Bank’s Local Economy and Infrastructure Developm ent Project. LIC-10 / PROJECT COORDINA TOR (COMPONENT 1) FOR LO Individual Consult CAL ECONOMY AND INFRAST IBRD / 85720 Institutional Development Post Limited 8,910.00 11,195.58 Signed 2022-08-18 2022-08-15 2022-08-23 2022-09-08 2022-09-13 2022-09-13 2022-09-27 2022-09-24 2023-03-31 ant Selection RUCTURE DEVELOPMENT PR OJECT WITHIN THE TOURISM COMMITTEE. LIC-08-1 / MARKETING PROJE CT COORDINATOR FOR LOCA Individual Consult Under Implement L ECONOMY AND INFRASTRU IBRD / 85720 Institutional Development Post Limited 4,050.00 0.00 2022-08-18 2022-08-15 2022-08-23 2022-09-05 2022-09-13 2022-10-06 2022-09-27 2023-03-31 ant Selection ation CTURE DEVELOPMENT PROJE CT WITHIN THE TOURISM CO MMITTEE LIC-08 / MARKETING PROJEC T COORDINATOR FOR LOCAL Individual Consult ECONOMY AND INFRASTRUC IBRD / 85720 Institutional Development Post Limited 4,050.00 0.00 Canceled 2022-08-08 2022-08-04 2022-08-13 2022-09-03 2022-10-01 2023-03-30 ant Selection TURE DEVELOPMENT PROJEC T WITHIN THE TOURISM COM MITTEE LIC-11 / Individual Consultan cy Services for Supervision E Heritage Hub and Tourism Ci Individual Consult Under Implement ngineer under the World Ban IBRD / 85720 Post Limited 13,500.00 0.00 2022-08-18 2022-08-31 2022-08-23 2022-09-07 2022-09-13 2022-11-01 2022-09-27 2023-03-31 rcuit Development ant Selection ation k’s Local Economy and Infras tructure Development Project . LIC-12 / Individual Consultan cy Services for Supervision E Heritage Hub and Tourism Ci Individual Consult Under Implement ngineer under the World Ban IBRD / 85720 Post Limited 13,500.00 0.00 2022-08-18 2022-09-06 2022-08-23 2022-09-08 2022-09-13 2022-09-27 2023-03-31 rcuit Development ant Selection ation k’s Local Economy and Infras tructure Development Project . LIC-13 / Individual Consultan cy Services for Supervision E Heritage Hub and Tourism Ci Individual Consult Under Implement ngineer under the World Ban IBRD / 85720 Post Limited 13,500.00 0.00 2022-08-18 2022-09-06 2022-08-23 2022-09-08 2022-09-13 2022-09-27 2023-03-31 rcuit Development ant Selection ation k’s Local Economy and Infras tructure Development Project . LIC-09 / International Touris Individual Consult IBRD / 85720 Institutional Development Post Limited 9,210.00 0.00 Canceled 2022-08-08 2022-08-04 2022-08-13 2022-09-03 2022-10-01 2023-03-30 m Visitor Research Consultan ant Selection t. LPD-09-1 / International Tour Individual Consult IBRD / 85720 Institutional Development Post Limited 22,110.00 23,905.18 Signed 2022-08-22 2022-09-06 2022-08-27 2022-09-08 2022-09-10 2022-09-13 2022-09-24 2022-09-15 2024-03-27 ism Visitor Research Consult ant Selection ant. LIC-14 / Consultant for asses sment of the visitors’ safety i Individual Consult Under Implement IBRD / 85720 Institutional Development Post Limited 3,300.00 0.00 2022-10-17 2022-10-17 2022-10-22 2022-11-08 2022-11-12 2022-11-11 2022-12-10 2023-05-09 mprovement at the Stone Sy ant Selection ation mphony natural monument. LIC-15 / Accountant Consulta Individual Consult Under Implement IBRD / 85720 Institutional Development Post Limited 8,920.00 0.00 2022-10-26 2022-10-25 2022-10-28 2022-10-28 2022-11-04 2022-11-01 2022-11-18 2023-03-31 nt for LEID project for ATDF. ant Selection ation LIC-16 / Translator for LEID p Heritage Hub and Tourism Ci Individual Consult Under Implement IBRD / 85720 Post Open - National 37,600.00 0.00 2022-12-10 2022-12-15 2023-01-06 2023-03-06 2023-01-09 2023-05-18 2023-01-15 2024-12-30 roject for ATDF. rcuit Development ant Selection ation LIC-17 / LOCAL TOURISM EX PERT FOR LOCAL ECONOMY Heritage Hub and Tourism Ci Individual Consult Under Implement IBRD / 85720 Post Limited 31,500.00 0.00 2023-03-15 2023-03-15 2023-03-21 2023-04-19 2023-04-03 2023-04-20 2023-05-01 2024-12-31 AND INFRASTRUCTURE DEVE rcuit Development ant Selection ation LOPMENT PROJECT WITHIN T HE TOURISM COMMITTEE Page 6 LIC-18 / Lawyer for LEID proj Heritage Hub and Tourism Ci Individual Consult Under Implement IBRD / 85720 Post Limited 9,500.00 0.00 2023-05-09 2023-05-02 2023-05-14 2023-05-25 2023-06-04 2023-05-30 2023-07-02 2023-12-29 ect. rcuit Development ant Selection ation LIC-19 / Geographic Informat Heritage Hub and Tourism Ci Individual Consult IBRD / 85720 Post Limited 23,800.00 0.00 Under Review 2023-06-14 2023-06-22 2023-06-19 2023-07-10 2023-07-31 2024-07-25 ion System control specialist. rcuit Development ant Selection Page 7 PROCUREMENT PLAN (Textual Part) Project information: Bosnia and Herzegovina Emergency COVID-19 Project – P173809 Project Implementation agencies: Ministry of Health and Social Welfare of the Republic of Srpska and Federal Ministry of Health (Federation of Bosnia and Herzegovina). Date of the Procurement Plan: December 14, 2020 Period covered by this Procurement Plan: 2020 – 2022 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the arrangements agreed shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables. Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations is Applicable. Other Relevant Procurement Information. Fast-Track Procurement. The proposed procurement approach prioritizes fast-track emergency procurement for the urgently required goods, works and services. Key measures to fast-track procurement include certain flexibilities related to bid and performance securities, advance payment, time for submission of bids/proposals; and standstill period. PROCUREMENT Bosnia and Herzegovina : Bosnia and Herzegovina Emergency COVID-19 Project PLAN General Information Country: Bosnia and Herzegovina 2021-01-25 Bank’s Approval Date of the Original Procurement Plan: 2023-06-06 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P173809 GPN Date: 2020-07-29 Project Name: Bosnia and Herzegovina Emergency COVID-19 Project Loan / Credit No: IBRD / 90970 Ministry of Health and Social Welfare Executing Agency(ies): WORKS Activity Reference No. / Procureme Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH Ri Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method nt Docume ount (US$ and Recommendation Signed Contract o. h cess (Y/N) sk atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion nt Type ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BA/RS/MOHSW/COVID-19/GO Component 1. Responding t /DIR/041-21 / Thermometers IBRD / 90970 o the COVID-19 Pandemic in Post Direct Selection Direct 613.56 Completed 2021-02-15 2021-02-03 2021-02-20 2021-02-03 2021-03-27 2021-02-04 2021-09-23 2021-02-04 - retroactive financing - PHI R Republika Srpska S BA/RS/MOHSW/COVID-19/GO Component 1. Responding t /DIR/040-21 / Bedding goods IBRD / 90970 o the COVID-19 Pandemic in Post Direct Selection Direct 17,336.17 Completed 2021-02-15 2021-02-03 2021-02-20 2021-02-03 2021-03-27 2021-02-04 2021-09-23 2021-02-04 - retroactive financing - SC Ni Republika Srpska kola Tesla BA-MZSZ RS-217226-GO-DIR Component 1. Responding t / Mattresses - BOTEX - retroa IBRD / 90970 o the COVID-19 Pandemic in Post Direct Selection Direct 3,154.16 Completed 2021-03-01 2021-07-27 2021-03-06 2021-07-27 2021-04-10 2021-07-28 2021-10-07 2021-07-28 ctive financing - City of Bijelji Republika Srpska na BA-MZSZ RS-217316-GO-DIR Component 1. Responding t / Bedding goods - TEXTIL (02- IBRD / 90970 o the COVID-19 Pandemic in Post Direct Selection Direct 8,513.28 Completed 2021-03-01 2021-07-27 2021-03-06 2021-07-27 2021-04-10 2021-07-28 2021-10-07 2021-07-28 85-12/20) - retroactive financ Republika Srpska ing - City of Bijeljina BA-MZSZ RS-217321-GO-DIR Component 1. Responding t / Bedding goods - TEXTIL (02- IBRD / 90970 o the COVID-19 Pandemic in Post Direct Selection Direct 6,511.27 Completed 2021-03-01 2021-07-27 2021-03-06 2021-07-27 2021-04-10 2021-07-28 2021-10-07 2021-07-28 85-14/20) - retroactive financ Republika Srpska ing - City of Bijeljina BA-MZSZ RS-217284-GO-DIR Component 1. Responding t / Bedding goods - TEXTIL (02- IBRD / 90970 o the COVID-19 Pandemic in Post Direct Selection Direct 1,278.93 Completed 2021-03-01 2021-02-12 2021-03-06 2021-02-12 2021-04-10 2021-02-13 2021-10-07 2021-02-13 85-21/20) retroactive financi Republika Srpska ng - City of Bijeljina BA-MZSZ RS-217286-GO-DIR Component 1. Responding t / Rapid diagnostics tests - AK IBRD / 90970 o the COVID-19 Pandemic in Post Direct Selection Direct 28,036.67 Completed 2021-03-01 2021-07-28 2021-03-06 2021-07-28 2021-04-10 2021-07-29 2021-10-07 2021-07-29 O MED - retroactive financing Republika Srpska - PHI RS BA-MZSZ RS-217467-GO-DIR Component 1. Responding t / Supplies for testing Covid 1 IBRD / 90970 o the COVID-19 Pandemic in Post Direct Selection Direct 1,375.83 Completed 2021-03-01 2021-03-31 2021-03-06 2021-03-31 2021-04-10 2021-04-01 2021-10-07 2021-04-01 9 - ANALITIKA (1598) - retroa Republika Srpska ctive financing - PHI RS BA-MZSZ RS-217287-GO-DIR Component 1. Responding t / Supplies for testing Covid 1 IBRD / 90970 o the COVID-19 Pandemic in Post Direct Selection Direct 2,672.22 Completed 2021-03-01 2021-03-31 2021-03-06 2021-03-31 2021-04-10 2021-04-01 2021-10-07 2021-04-01 9 - ANALITIKA (1839) - retroa Republika Srpska ctive financing - PHI RS BA-MZSZ RS-216990-GO-DIR Component 1. Responding t / Supplies for testing Covid 1 IBRD / 90970 o the COVID-19 Pandemic in Post Direct Selection Direct 2,672.22 Completed 2021-03-01 2021-03-31 2021-03-06 2021-03-31 2021-04-10 2021-04-01 2021-10-07 2021-04-01 9 - ANALITIKA (1841) - retroa Republika Srpska ctive financing - PHI RS BA-MZSZ RS-217288-GO-DIR Component 1. Responding t / Thermal cameras - ARMS (2 IBRD / 90970 o the COVID-19 Pandemic in Post Direct Selection Direct 215,944.44 Completed 2021-03-01 2021-03-31 2021-03-06 2021-03-31 2021-04-10 2021-04-01 2021-10-07 2021-04-01 389) - retroactive financing - Republika Srpska PHI RS BA-MZSZ RS-217460-GO-DIR Component 1. Responding t / Tests for COVID-19 - BIOME IBRD / 90970 o the COVID-19 Pandemic in Post Direct Selection Direct 2,138.57 Completed 2021-03-01 2021-03-08 2021-03-06 2021-03-08 2021-04-10 2021-03-09 2021-10-07 2021-03-09 DIKA (1430) - retroactive fina Republika Srpska ncing - PHI RS BA-MZSZ RS-217008-GO-DIR Component 1. Responding t / RT PCR kit for SARS CoV19 - IBRD / 90970 o the COVID-19 Pandemic in Post Direct Selection Direct 2,496.22 Completed 2021-03-01 2021-03-30 2021-03-06 2021-03-30 2021-04-10 2021-03-31 2021-10-07 2021-03-31 BIOMEDIKA (2555) - retroacti Republika Srpska ve financing - PHI RS BA-MZSZ RS-217258-GO-DIR Component 1. Responding t / RT PCR kit for SARS CoV1 - IBRD / 90970 o the COVID-19 Pandemic in Post Direct Selection Direct 2,496.22 Completed 2021-03-01 2021-03-30 2021-03-06 2021-03-30 2021-04-10 2021-03-31 2021-10-07 2021-03-31 BIOMEDIKA (2556) - retroacti Republika Srpska ve financing - PHI RS BA-MZSZ RS-217262-GO-DIR Component 1. Responding t / RT PCR device - BIOSISTEMI IBRD / 90970 o the COVID-19 Pandemic in Post Direct Selection Direct 34,666.67 Completed 2021-03-01 2021-04-05 2021-03-06 2021-04-05 2021-04-10 2021-04-06 2021-10-07 2021-04-06 (1827) - retroactive financing Republika Srpska - PHI RS BA-MZSZ RS-217340-GO-DIR Component 1. Responding t / RT PCR device - BIOSISTEMI IBRD / 90970 o the COVID-19 Pandemic in Post Direct Selection Direct 104,000.00 Completed 2021-03-01 2021-04-05 2021-03-06 2021-04-05 2021-04-10 2021-04-06 2021-10-07 2021-04-06 (2124) - retroactive financing Republika Srpska - PHI RS BA-MZSZ RS-217347-GO-DIR Component 1. Responding t / Virus transportation surface IBRD / 90970 o the COVID-19 Pandemic in Post Direct Selection Direct 9,750.00 Completed 2021-03-01 2021-04-05 2021-03-06 2021-04-05 2021-04-10 2021-04-06 2021-10-07 2021-04-06 s - BROMA BEL (1929) - retro Republika Srpska active financing - PHI RS BA-MZSZ RS-217290-GO-DIR Component 1. Responding t / RNA extraction kit - BROMA IBRD / 90970 o the COVID-19 Pandemic in Post Direct Selection Direct 99,811.11 Completed 2021-03-01 2021-04-05 2021-03-06 2021-04-05 2021-04-10 2021-04-06 2021-10-07 2021-04-06 BEL (2390) - retroactive finan Republika Srpska cing - PHI RS BA-MZSZ RS-216993-GO-DIR Component 1. Responding t / Power generator - ELEKTRO IBRD / 90970 o the COVID-19 Pandemic in Post Direct Selection Direct 11,465.03 Completed 2021-03-01 2021-04-05 2021-03-06 2021-04-05 2021-04-10 2021-04-06 2021-10-07 2021-04-06 RACIC (2421) - retroactive fin Republika Srpska ancing - PHI RS Page 1 BA-MZSZ RS-217270-GO-DIR Component 1. Responding t / Protective suits - EMGEN (2 IBRD / 90970 o the COVID-19 Pandemic in Post Direct Selection Direct 257,833.33 Completed 2021-03-01 2021-04-05 2021-03-06 2021-04-05 2021-04-10 2021-04-06 2021-10-07 2021-04-06 134) - retroactive financing - Republika Srpska PHI RS BA-MZSZ RS-217356-GO-DIR Component 1. Responding t / Protective masks FFP2 - EM IBRD / 90970 o the COVID-19 Pandemic in Post Direct Selection Direct 257,833.33 Completed 2021-03-01 2021-04-05 2021-03-06 2021-04-05 2021-04-10 2021-04-06 2021-10-07 2021-04-06 GEN (2234) - retroactive fina Republika Srpska ncing - PHI RS BA-MZSZ RS-217350-GO-DIR Component 1. Responding t / PCR filter tips - ENA (1832) - IBRD / 90970 o the COVID-19 Pandemic in Post Direct Selection Direct 2,145.00 Completed 2021-03-01 2021-04-05 2021-03-06 2021-04-05 2021-04-10 2021-04-06 2021-10-07 2021-04-06 retroactive financing - PHI RS Republika Srpska BA-MZSZ RS-217373-GO-DIR Component 1. Responding t / Disinfection supplies - GALE IBRD / 90970 o the COVID-19 Pandemic in Post Direct Selection Direct 14,797.61 Completed 2021-03-01 2021-03-31 2021-03-06 2021-03-31 2021-04-10 2021-04-01 2021-10-07 2021-04-01 NFARM (1738) - retroactive fi Republika Srpska nancing - PHI RS BA-MZSZ RS-217358-GO-DIR Component 1. Responding t / Disinfection supplies - GALE IBRD / 90970 o the COVID-19 Pandemic in Post Direct Selection Direct 2,881.67 Completed 2021-03-01 2021-03-31 2021-03-06 2021-03-31 2021-04-10 2021-04-01 2021-10-07 2021-04-01 NFARM (1975) - retroactive fi Republika Srpska nancing - PHI RS BA-MZSZ RS-217355-GO-DIR Component 1. Responding t / Disinfection supplies - GALE IBRD / 90970 o the COVID-19 Pandemic in Post Direct Selection Direct 2,881.67 Completed 2021-03-01 2021-03-31 2021-03-06 2021-03-31 2021-04-10 2021-04-01 2021-10-07 2021-04-01 NFARM (1977) - retroactive fi Republika Srpska nancing - PHI RS BA-MZSZ RS-217360-GO-DIR Component 1. Responding t / Disinfection supplies - GALE IBRD / 90970 o the COVID-19 Pandemic in Post Direct Selection Direct 2,881.67 Completed 2021-03-01 2021-03-31 2021-03-06 2021-03-31 2021-04-10 2021-04-01 2021-10-07 2021-04-01 NFARM (2227) - retroactive fi Republika Srpska nancing - PHI RS BA-MZSZ RS-217374-GO-DIR Component 1. Responding t / Disinfection supplies - GALE IBRD / 90970 o the COVID-19 Pandemic in Post Direct Selection Direct 2,881.67 Completed 2021-03-01 2021-03-31 2021-03-06 2021-03-31 2021-04-10 2021-04-01 2021-10-07 2021-04-01 NFARM (2466) - retroactive fi Republika Srpska nancing - PHI RS BA-MZSZ RS-217372-GO-DIR Component 1. Responding t / Latex gloves - MIPEX (1719) IBRD / 90970 o the COVID-19 Pandemic in Post Direct Selection Direct 2,744.44 Completed 2021-03-01 2021-03-29 2021-03-06 2021-03-29 2021-04-10 2021-03-30 2021-10-07 2021-03-30 - retroactive financing - PHI R Republika Srpska S BA-MZSZ RS-217264-GO-DIR Component 1. Responding t / Latex gloves - MIPEX (1720) IBRD / 90970 o the COVID-19 Pandemic in Post Direct Selection Direct 2,744.44 Completed 2021-03-01 2021-03-29 2021-03-06 2021-03-29 2021-04-10 2021-03-30 2021-10-07 2021-03-30 - retroactive financing - PHI R Republika Srpska S BA-MZSZ RS-217367-GO-DIR Component 1. Responding t / Nitrile gloves - MIPEX (1792 IBRD / 90970 o the COVID-19 Pandemic in Post Direct Selection Direct 2,708.33 Completed 2021-03-01 2021-03-29 2021-03-06 2021-03-29 2021-04-10 2021-03-30 2021-10-07 2021-03-30 ) - retroactive financing - PHI Republika Srpska RS BA-MZSZ RS-217297-GO-DIR Component 1. Responding t / Nitrile gloves - MIPEX (1793 IBRD / 90970 o the COVID-19 Pandemic in Post Direct Selection Direct 2,708.33 Completed 2021-03-01 2021-03-26 2021-03-06 2021-03-26 2021-04-10 2021-03-27 2021-10-07 2021-03-27 ) - retroactive financing - PHI Republika Srpska RS BA-MZSZ RS-217261-GO-DIR Component 1. Responding t / Nitrile gloves - MIPEX (2005 IBRD / 90970 o the COVID-19 Pandemic in Post Direct Selection Direct 2,708.33 Completed 2021-03-01 2021-03-26 2021-03-06 2021-03-26 2021-04-10 2021-03-27 2021-10-07 2021-03-27 ) - retroactive financing - PHI Republika Srpska RS BA-MZSZ RS-217277-GO-DIR Component 1. Responding t / Nitrile gloves - MIPEX (2006 IBRD / 90970 o the COVID-19 Pandemic in Post Direct Selection Direct 2,708.33 Completed 2021-03-01 2021-03-26 2021-03-06 2021-03-26 2021-04-10 2021-03-27 2021-10-07 2021-03-27 ) - retroactive financing - PHI Republika Srpska RS BA-MZSZ RS-217368-GO-DIR Component 1. Responding t / Protective masks - MIPEX (2 IBRD / 90970 o the COVID-19 Pandemic in Post Direct Selection Direct 1,094.89 Completed 2021-03-01 2021-03-29 2021-03-06 2021-03-29 2021-04-10 2021-03-30 2021-10-07 2021-03-30 007) - retroactive financing - Republika Srpska PHI RS BA-MZSZ RS-217222-GO-DIR Component 1. Responding t / Latex gloves - MIPEX (2151) IBRD / 90970 o the COVID-19 Pandemic in Post Direct Selection Direct 2,744.44 Completed 2021-03-01 2021-03-26 2021-03-06 2021-03-26 2021-04-10 2021-03-27 2021-10-07 2021-03-27 - retroactive financing - PHI R Republika Srpska S BA-MZSZ RS-216992-GO-DIR Component 1. Responding t / Latex gloves - MIPEX (2152) IBRD / 90970 o the COVID-19 Pandemic in Post Direct Selection Direct 2,744.44 Completed 2021-03-01 2021-03-26 2021-03-06 2021-03-26 2021-04-10 2021-03-27 2021-10-07 2021-03-27 - retroactive financing - PHI R Republika Srpska S BA-MZSZ RS-217292-GO-DIR Component 1. Responding t / Latex gloves - MIPEX (2397) IBRD / 90970 o the COVID-19 Pandemic in Post Direct Selection Direct 2,744.44 Completed 2021-03-01 2021-03-26 2021-03-06 2021-03-26 2021-04-10 2021-03-27 2021-10-07 2021-03-27 - retroactive financing - PHI R Republika Srpska S BA-MZSZ RS-217294-GO-DIR Component 1. Responding t / Latex gloves - MIPEX (2398) IBRD / 90970 o the COVID-19 Pandemic in Post Direct Selection Direct 2,744.44 Completed 2021-03-01 2021-03-26 2021-03-06 2021-03-26 2021-04-10 2021-03-27 2021-10-07 2021-03-27 - retroactive financing - PHI R Republika Srpska S BA-MZSZ RS-216991-GO-DIR Component 1. Responding t / Disinfection supplies - PERF IBRD / 90970 o the COVID-19 Pandemic in Post Direct Selection Direct 4,073.33 Completed 2021-03-01 2021-03-30 2021-03-06 2021-03-30 2021-04-10 2021-03-31 2021-10-07 2021-03-31 ECT CLEAN (1707) - retroacti Republika Srpska ve financing - PHI RS BA-MZSZ RS-217457-GO-DIR Component 1. Responding t / Disinfection supplies - PERF IBRD / 90970 o the COVID-19 Pandemic in Post Direct Selection Direct 4,073.33 Completed 2021-03-01 2021-03-30 2021-03-06 2021-03-30 2021-04-10 2021-03-31 2021-10-07 2021-03-31 ECT CLEAN (1877) - retroacti Republika Srpska ve financing - PHI RS BA-MZSZ RS-217299-GO-DIR Component 1. Responding t / Disinfection supplies - PERF IBRD / 90970 o the COVID-19 Pandemic in Post Direct Selection Direct 4,073.33 Completed 2021-03-01 2021-03-29 2021-03-06 2021-03-29 2021-04-10 2021-03-30 2021-10-07 2021-03-30 ECT CLEAN (1936) - retroacti Republika Srpska ve financing - PHI RS BA-MZSZ RS-217458-GO-DIR Component 1. Responding t / Disinfection supplies - PERF IBRD / 90970 o the COVID-19 Pandemic in Post Direct Selection Direct 4,073.33 Completed 2021-03-01 2021-03-30 2021-03-06 2021-03-30 2021-04-10 2021-03-31 2021-10-07 2021-03-31 ECT CLEAN (1961) - retroacti Republika Srpska ve financing - PHI RS BA-MZSZ RS-217224-GO-DIR Component 1. Responding t / Disinfection supplies - PERF IBRD / 90970 o the COVID-19 Pandemic in Post Direct Selection Direct 4,073.33 Completed 2021-03-01 2021-03-29 2021-03-06 2021-03-29 2021-04-10 2021-03-30 2021-10-07 2021-03-30 ECT CLEAN (1983) - retroacti Republika Srpska ve financing - PHI RS BA-MZSZ RS-217300-GO-DIR Component 1. Responding t / Disinfection supplies - PERF IBRD / 90970 o the COVID-19 Pandemic in Post Direct Selection Direct 4,073.33 Completed 2021-03-01 2021-03-29 2021-03-06 2021-03-29 2021-04-10 2021-03-30 2021-10-07 2021-03-30 ECT CLEAN (2016) - retroacti Republika Srpska ve financing - PHI RS Page 2 BA-MZSZ RS-217342-GO-DIR Component 1. Responding t / Disinfection supplies - PERF IBRD / 90970 o the COVID-19 Pandemic in Post Direct Selection Direct 4,073.33 Completed 2021-03-01 2021-03-30 2021-03-06 2021-03-30 2021-04-10 2021-03-31 2021-10-07 2021-03-31 ECT CLEAN (2039) - retroacti Republika Srpska ve financing - PHI RS BA-MZSZ RS-217359-GO-DIR Component 1. Responding t / Disinfection supplies - PERF IBRD / 90970 o the COVID-19 Pandemic in Post Direct Selection Direct 24,440.00 Completed 2021-03-01 2021-03-30 2021-03-06 2021-03-30 2021-04-10 2021-03-31 2021-10-07 2021-03-31 ECT CLEAN (2217) - retroacti Republika Srpska ve financing - PHI RS BA-MZSZ RS-217223-GO-DIR Component 1. Responding t / Protective masks FFP2 - PER IBRD / 90970 o the COVID-19 Pandemic in Post Direct Selection Direct 2,600.00 Completed 2021-03-01 2021-03-29 2021-03-06 2021-03-29 2021-04-10 2021-03-30 2021-10-07 2021-03-30 FECT CLEAN (2257) - retroact Republika Srpska ive financing - PHI RS BA-MZSZ RS-217003-GO-DIR Component 1. Responding t / Protective masks FFP2 - PER IBRD / 90970 o the COVID-19 Pandemic in Post Direct Selection Direct 2,600.00 Completed 2021-03-01 2021-03-29 2021-03-06 2021-03-29 2021-04-10 2021-03-30 2021-10-07 2021-03-30 FECT CLEAN (2258) - retroact Republika Srpska ive financing - PHI RS BA-MZSZ RS-217006-GO-DIR Component 1. Responding t / Protective suits - PREVENT ( IBRD / 90970 o the COVID-19 Pandemic in Post Direct Selection Direct 433,333.33 Completed 2021-03-01 2021-04-06 2021-03-06 2021-04-06 2021-04-10 2021-04-07 2021-10-07 2021-04-07 2153) - retroactive financing Republika Srpska - PHI RS BA-MZSZ RS-217303-GO-DIR Component 1. Responding t / Protective surgical masks - IBRD / 90970 o the COVID-19 Pandemic in Post Direct Selection Direct 505,555.55 Completed 2021-03-01 2021-04-06 2021-03-06 2021-04-06 2021-04-10 2021-04-07 2021-10-07 2021-04-07 SANITEKS (2129) - retroactiv Republika Srpska e financing - PHI RS BA-MZSZ RS-217276-GO-DIR Component 1. Responding t / Protective caps - SAVINA (1 IBRD / 90970 o the COVID-19 Pandemic in Post Direct Selection Direct 515.70 Completed 2021-03-01 2021-04-06 2021-03-06 2021-04-06 2021-04-10 2021-04-07 2021-10-07 2021-04-07 356) - retroactive financing - Republika Srpska PHI RS BA-MZSZ RS-217279-GO-DIR Component 1. Responding t / Protective caps - SAVINA (1 IBRD / 90970 o the COVID-19 Pandemic in Post Direct Selection Direct 1,870.55 Completed 2021-03-01 2021-04-06 2021-03-06 2021-04-06 2021-04-10 2021-04-07 2021-10-07 2021-04-07 889) - retroactive financing - Republika Srpska PHI RS BA-MZSZ RS-217305-GO-DIR Component 1. Responding t / Protective caps - SAVINA (2 IBRD / 90970 o the COVID-19 Pandemic in Post Direct Selection Direct 1,603.33 Completed 2021-03-01 2021-04-06 2021-03-06 2021-04-06 2021-04-10 2021-04-07 2021-10-07 2021-04-07 259) - retroactive financing - Republika Srpska PHI RS BA-MZSZ RS-217010-GO-DIR Component 1. Responding t / Portable ultrasound color D IBRD / 90970 o the COVID-19 Pandemic in Post Direct Selection Direct 40,242.22 Completed 2021-03-01 2021-04-06 2021-03-06 2021-04-06 2021-04-10 2021-04-07 2021-10-07 2021-04-07 oppler devices - SHIMADZU ( Republika Srpska 2127) - retroactive financing - PHI RS BA-MZSZ RS-217308-GO-DIR Component 1. Responding t / Surgical masks - SINEKS (15 IBRD / 90970 o the COVID-19 Pandemic in Post Direct Selection Direct 2,491.67 Completed 2021-03-01 2021-03-09 2021-03-06 2021-03-09 2021-04-10 2021-03-10 2021-10-07 2021-03-10 34) - retroactive financing - P Republika Srpska HI RS BA-MZSZ RS-217319-GO-DIR Component 1. Responding t / Surgical masks - SINEKS (15 IBRD / 90970 o the COVID-19 Pandemic in Post Direct Selection Direct 2,491.67 Completed 2021-03-01 2021-03-09 2021-03-06 2021-03-09 2021-04-10 2021-03-10 2021-10-07 2021-03-10 35) - retroactive financing - P Republika Srpska HI RS BA-MZSZ RS-217007-GO-DIR Component 1. Responding t / Surgical masks - SINEKS (15 IBRD / 90970 o the COVID-19 Pandemic in Post Direct Selection Direct 1,993.33 Completed 2021-03-01 2021-03-09 2021-03-06 2021-03-09 2021-04-10 2021-03-10 2021-10-07 2021-03-10 82) - retroactive financing - P Republika Srpska HI RS BA-MZSZ RS-217112-GO-DIR Component 1. Responding t / Surgical masks - SINEKS (16 IBRD / 90970 o the COVID-19 Pandemic in Post Direct Selection Direct 2,491.67 Completed 2021-03-01 2021-03-09 2021-03-06 2021-03-09 2021-04-10 2021-03-10 2021-10-07 2021-03-10 35) - retroactive financing - P Republika Srpska HI RS BA-MZSZ RS-217318-GO-DIR Component 1. Responding t / Surgical masks - SINEKS (16 IBRD / 90970 o the COVID-19 Pandemic in Post Direct Selection Direct 2,491.67 Completed 2021-03-01 2021-03-09 2021-03-06 2021-03-09 2021-04-10 2021-03-10 2021-10-07 2021-03-10 36) - retroactive financing - P Republika Srpska HI RS BA-MZSZ RS-217225-GO-DIR Component 1. Responding t / Surgical masks - SINEKS (17 IBRD / 90970 o the COVID-19 Pandemic in Post Direct Selection Direct 3,213.89 Completed 2021-03-01 2021-03-17 2021-03-06 2021-03-17 2021-04-10 2021-03-18 2021-10-07 2021-03-18 99-2) - retroactive financing - Republika Srpska PHI RS BA-MZSZ RS-217001-GO-DIR Component 1. Responding t / Surgical masks - SINEKS (17 IBRD / 90970 o the COVID-19 Pandemic in Post Direct Selection Direct 3,213.89 Completed 2021-03-01 2021-03-26 2021-03-06 2021-03-26 2021-04-10 2021-03-27 2021-10-07 2021-03-27 99-4) - retroactive financing - Republika Srpska PHI RS BA-MZSZ RS-217309-GO-DIR Component 1. Responding t / Surgical masks - SINEKS (18 IBRD / 90970 o the COVID-19 Pandemic in Post Direct Selection Direct 3,213.89 Completed 2021-03-01 2021-03-17 2021-03-06 2021-03-17 2021-04-10 2021-03-18 2021-10-07 2021-03-18 00) - retroactive financing - P Republika Srpska HI RS BA-MZSZ RS-217231-GO-DIR Component 1. Responding t / Surgical masks - SINEKS (18 IBRD / 90970 o the COVID-19 Pandemic in Post Direct Selection Direct 3,213.89 Completed 2021-03-01 2021-03-17 2021-03-06 2021-03-17 2021-04-10 2021-03-18 2021-10-07 2021-03-18 01) - retroactive financing - P Republika Srpska HI RS BA-MZSZ RS-217232-GO-DIR Component 1. Responding t / Surgical masks - SINEKS (19 IBRD / 90970 o the COVID-19 Pandemic in Post Direct Selection Direct 4,285.18 Completed 2021-03-01 2021-03-26 2021-03-06 2021-03-26 2021-04-10 2021-03-27 2021-10-07 2021-03-27 97) - retroactive financing - P Republika Srpska HI RS BA-MZSZ RS-217253-GO-DIR Component 1. Responding t / Surgical masks - SINEKS (22 IBRD / 90970 o the COVID-19 Pandemic in Post Direct Selection Direct 4,285.18 Completed 2021-03-01 2021-03-17 2021-03-06 2021-03-17 2021-04-10 2021-03-18 2021-10-07 2021-03-18 00) - retroactive financing - P Republika Srpska HI RS BA-MZSZ RS-217338-GO-DIR Component 1. Responding t / Surgical masks - SINEKS (22 IBRD / 90970 o the COVID-19 Pandemic in Post Direct Selection Direct 4,285.18 Completed 2021-03-01 2021-03-09 2021-03-06 2021-03-09 2021-04-10 2021-07-28 2021-10-07 2021-07-28 02) - retroactive financing - P Republika Srpska HI RS BA-MZSZ RS-216988-GO-DIR Component 1. Responding t / Surgical masks - SINEKS (22 IBRD / 90970 o the COVID-19 Pandemic in Post Direct Selection Direct 4,285.18 Completed 2021-03-01 2021-03-26 2021-03-06 2021-03-26 2021-04-10 2021-03-27 2021-10-07 2021-03-27 03) - retroactive financing - P Republika Srpska HI RS BA-MZSZ RS-217257-GO-DIR Component 1. Responding t / Surgical masks - STEPMED ( IBRD / 90970 o the COVID-19 Pandemic in Post Direct Selection Direct 26,000.00 Completed 2021-03-01 2021-04-06 2021-03-06 2021-04-06 2021-04-10 2021-04-07 2021-10-07 2021-04-07 1717) - retroactive financing Republika Srpska - PHI RS BA-MZSZ RS-217310-GO-DIR Component 1. Responding t / Volumetric infusion pumps - IBRD / 90970 o the COVID-19 Pandemic in Post Direct Selection Direct 2,816.67 Completed 2021-03-01 2021-04-06 2021-03-06 2021-04-06 2021-04-10 2021-04-07 2021-10-07 2021-04-07 STEPMED (2004) - retroactive Republika Srpska financing - PHI RS Page 3 BA-MZSZ RS-217255-GO-DIR Component 1. Responding t / Beds and mattresses - VIGM IBRD / 90970 o the COVID-19 Pandemic in Post Direct Selection Direct 6,843.06 Completed 2021-03-01 2020-04-06 2021-03-06 2020-04-08 2021-04-10 2020-04-09 2021-10-07 2020-04-30 ELT (02-85-13/20) - retroacti Republika Srpska ve financing - City of Bijeljina BA-MZSZ RS-214134-GO-RF Component 1. Responding t Request for Quota Single Stage - One E Q / Supplies for laboratory - P IBRD / 90970 o the COVID-19 Pandemic in Post Open - National 0.00 Canceled 2021-03-06 2021-05-01 2021-10-28 tions nvelope CR attachments Republika Srpska BA-MZSZ RS-214544-GO-RF Component 1. Responding t Request for Quota Single Stage - One E Q / Supplies for laboratory - o IBRD / 90970 o the COVID-19 Pandemic in Post Open - National 0.00 Canceled 2021-03-06 2021-05-01 2021-10-28 tions nvelope ptical tubes Republika Srpska BA-MZSZ RS-214542-GO-RF Component 1. Responding t Request for Quota Single Stage - One E Q / Supplies for laboratory - p IBRD / 90970 o the COVID-19 Pandemic in Post Open - National 0.00 Canceled 2021-03-06 2021-05-01 2021-10-28 tions nvelope ipettes Republika Srpska BA-MZSZ RS-214541-GO-RF Component 1. Responding t Request for Quota Single Stage - One E Q / Supplies for laboratory - t IBRD / 90970 o the COVID-19 Pandemic in Post Open - National 0.00 Canceled 2021-03-06 2021-05-01 2021-10-28 tions nvelope est tubes Republika Srpska BA-MZSZ RS-214072-GO-RF Component 1. Responding t Request for Quota Single Stage - One E Q / Supplies for laboratory - IBRD / 90970 o the COVID-19 Pandemic in Post Open - National 0.00 Canceled 2021-03-06 2021-05-01 2021-10-28 tions nvelope HEPA filters Republika Srpska BA-MZSZ RS-217366-GO-DIR Component 1. Responding t / Respiratory medical masks IBRD / 90970 o the COVID-19 Pandemic in Post Direct Selection Direct 249,166.67 Completed 2021-03-01 2021-03-08 2021-03-06 2021-03-09 2021-04-10 2021-03-10 2021-10-07 2021-03-10 KN95 - PROKONTROL (2078) Republika Srpska - retroactive financing - PHI R S BA-MZSZ RS-217344-GO-DIR Component 1. Responding t / Surgical masks - SINEKS (19 IBRD / 90970 o the COVID-19 Pandemic in Post Direct Selection Direct 4,285.18 Completed 2021-03-01 2021-03-09 2021-03-06 2021-03-09 2021-04-10 2021-03-10 2021-10-07 2021-03-10 98) - retroactive financing - P Republika Srpska HI RS BA-MZSZ RS-216987-GO-DIR Component 1. Responding t / Surgical masks - SINEKS (19 IBRD / 90970 o the COVID-19 Pandemic in Post Direct Selection Direct 4,285.18 Completed 2021-03-01 2021-03-09 2021-03-06 2021-03-09 2021-04-10 2021-03-10 2021-10-07 2021-03-10 99) - retroactive financing - P Republika Srpska HI RS BA-MZSZ RS-217291-GO-DIR Component 1. Responding t / RT PCR device - BIOSISTEMI IBRD / 90970 o the COVID-19 Pandemic in Post Direct Selection Direct 0.00 Canceled 2021-03-01 2021-03-06 2021-04-10 2021-10-07 (2408) - retroactive financing Republika Srpska - PHI RS BA-MZSZ RS-214079-GO-RF Component 1. Responding t Request for Quota Single Stage - One E Q / Volumetry - Automatic pi IBRD / 90970 o the COVID-19 Pandemic in Post Open - National 0.00 Canceled 2021-05-22 2021-07-17 2022-01-13 tions nvelope pettes Republika Srpska Component 1. Responding t BA-MZSZ RS-214180-GO-RF Request for Quota Single Stage - One E IBRD / 90970 o the COVID-19 Pandemic in Post Open - National 0.00 Canceled 2021-06-12 2021-08-07 2022-02-03 Q / Hygiene products tions nvelope Republika Srpska BA-MZSZ RS-214074-GO-RF Component 1. Responding t Request for Quota Single Stage - One E Q / Measuring systems devic IBRD / 90970 o the COVID-19 Pandemic in Post Open - National 0.00 Canceled 2021-06-12 2021-08-07 2022-02-03 tions nvelope es (social welfare institutions Republika Srpska ) Component 1. Responding t BA-MZSZ RS-214466-GO-RF Request for Quota Single Stage - One E IBRD / 90970 o the COVID-19 Pandemic in Post Open - National 0.00 Canceled 2021-06-12 2021-08-07 2022-02-03 Q / Disinfectants tions nvelope Republika Srpska BA/RS/MOHSW/COVID-19/GO Component 1. Responding t /DIR/039-21 / Washing machi IBRD / 90970 o the COVID-19 Pandemic in Post Direct Selection Direct 43,333.00 Completed 2021-03-01 2021-03-08 2021-03-06 2021-03-08 2021-04-10 2021-03-09 2021-10-07 2021-03-09 nes - retroactive financing - S Republika Srpska C Nikola Tesla BA-MZSZ RS-219489-GO-RF Component 3. Project Manag Request for Quota Single Stage - One E Q / Procurement of office fur IBRD / 90970 Post Open - National 12,809.33 Completed 2021-03-06 2021-05-01 2021-04-22 2021-10-28 2021-05-26 ement tions nvelope niture for MoHSW BA-MZSZ RS-214071-GO-RF Component 3. Project Manag Request for Quota Single Stage - One E Q / Office and computer equi IBRD / 90970 Post Open - National 72,876.73 Completed 2021-03-06 2021-05-01 2021-03-23 2021-10-28 2021-10-20 ement tions nvelope pment for MoHSW BA-MZSZ RS-217263-GO-DIR Component 1. Responding t / RT PCR device - BIOSISTEMI IBRD / 90970 o the COVID-19 Pandemic in Post Direct Selection Direct 0.00 Canceled 2021-03-01 2021-03-06 2021-04-10 2021-10-07 (2408) - retroactive financing Republika Srpska - PHI RS BA-MZSZ RS-214075-GO-RF Component 1. Responding t Request for Quota Single Stage - One E Q / Medical Equipment - Puls IBRD / 90970 o the COVID-19 Pandemic in Post Open - National 0.00 Canceled 2021-04-03 2021-05-29 2021-11-25 tions nvelope e oximeter Republika Srpska BA-MZSZ RS-214129-GO-RF Component 1. Responding t Request for Quota Single Stage - One E Q / Equipment for Social welf IBRD / 90970 o the COVID-19 Pandemic in Post Open - National 509,467.15 Completed 2021-03-06 2021-07-28 2021-06-01 2021-05-06 2021-11-28 2021-07-07 tions nvelope are institutions for accomoda Republika Srpska tion BA-MZSZ RS-214142-GO-RF Component 1. Responding t Request for Quota Single Stage - One E Q / Medical Equipment - Patie IBRD / 90970 o the COVID-19 Pandemic in Post Open - National 0.00 Canceled 2021-04-03 2021-05-29 2021-11-25 tions nvelope nt monitor Republika Srpska BA-MZSZ RS-214522-GO-RF Component 1. Responding t Single Stage - One E B / Medical Equipment - Radi IBRD / 90970 o the COVID-19 Pandemic in Post Request for Bids Open - National 0.00 Canceled 2021-03-15 2021-03-20 2021-05-01 2021-05-31 2021-07-05 2022-01-01 nvelope ography Republika Srpska BA-MZSZ RS-214523-GO-RF Component 1. Responding t Request for Quota Single Stage - One E Q / Medical Equipment - Ultra IBRD / 90970 o the COVID-19 Pandemic in Post Open - National 0.00 Canceled 2021-04-03 2021-05-29 2021-11-25 tions nvelope sound device Republika Srpska BA-MZSZ RS-214503-GO-RF Component 1. Responding t Single Stage - One E B / Medical Equipment - Com IBRD / 90970 o the COVID-19 Pandemic in Post Request for Bids Open - National 0.00 Canceled 2021-03-15 2021-03-20 2021-05-01 2021-05-31 2021-07-05 2022-01-01 nvelope puterized Tomography - Mobi Republika Srpska le CT device BA-MZSZ RS-214140-GO-RF Component 1. Responding t Request for Quota Single Stage - One E Q / Sample preparation - Sa IBRD / 90970 o the COVID-19 Pandemic in Post Open - National 0.00 Completed 2021-08-14 2022-08-23 2021-10-09 2021-12-01 2022-12-10 tions nvelope mple extraction - extractors Republika Srpska BA-MZSZ RS-214185-GO-RF Component 1. Responding t Request for Quota Single Stage - One E Q / Analysis of laboratory sa IBRD / 90970 o the COVID-19 Pandemic in Post Open - National 145,762.49 Completed 2021-08-07 2021-11-10 2021-10-02 2021-12-31 2021-11-24 2022-06-02 tions nvelope mples - Molecular diagnostic Republika Srpska instruments BA-MZSZ RS-214124-CS-CQ Component 1. Responding t Request for Quota Single Stage - One E S / Promotional campaign (le IBRD / 90970 o the COVID-19 Pandemic in Post Open - National 0.00 Canceled 2021-09-14 2021-11-09 2021-12-09 tions nvelope aflets) Republika Srpska Page 4 Component 1. Responding t BA-MZSZ RS-242813-GO-RF Single Stage - One E IBRD / 90970 o the COVID-19 Pandemic in Post Request for Bids Open - National 954,458.43 Completed 2021-08-15 2021-09-06 2021-08-20 2021-09-06 2021-10-01 2021-10-04 2021-10-31 2021-10-05 2021-12-05 2021-11-02 2022-02-03 2021-12-18 Q / Ambulances nvelope Republika Srpska BA-MZSZ RS-214534-GO-RF Component 1. Responding t Single Stage - One E B / Hardware and software fo IBRD / 90970 o the COVID-19 Pandemic in Post Request for Bids Open - National 0.00 Canceled 2021-06-21 2021-06-26 2021-08-07 2021-09-06 2021-10-11 2022-04-09 nvelope r hospitals networking Republika Srpska BA-MZSZ RS-214456-GO-RF Component 1. Responding t Request for Quota Single Stage - One E Q / Diagnostic Supplies - Test IBRD / 90970 o the COVID-19 Pandemic in Post Open - National 10,975.36 Completed 2021-08-21 2021-09-20 2021-10-16 2021-10-02 2022-04-14 2022-01-29 tions nvelope kits and Reagents Republika Srpska Component 1. Responding t BA-MZSZ RS-214487-GO-RF Request for Quota Single Stage - One E IBRD / 90970 o the COVID-19 Pandemic in Post Open - National 16,201.48 Completed 2021-08-21 2021-08-10 2021-10-16 2021-09-11 2022-04-14 2021-10-26 Q / Protective Equipment tions nvelope Republika Srpska BA-MZSZ RS-214445-GO-RF Component 1. Responding t Request for Quota Single Stage - One E Q / Specific laboratory equip IBRD / 90970 o the COVID-19 Pandemic in Post Open - National 71,126.64 Completed 2021-08-21 2021-10-14 2021-10-16 2021-11-27 2022-04-14 2022-03-03 tions nvelope ment - Microscopes Republika Srpska Component 1. Responding t BA-MZSZ RS-214525-GO-RF Request for Quota Single Stage - One E IBRD / 90970 o the COVID-19 Pandemic in Post Open - National 23,195.51 Completed 2021-08-21 2021-09-20 2021-10-16 2021-09-16 2022-04-14 2021-10-16 Q / Field vehicle tions nvelope Republika Srpska BA-MZSZ RS-214100-GO-RF Component 1. Responding t Q / Stirring and shaking syste Request for Quota Single Stage - One E IBRD / 90970 o the COVID-19 Pandemic in Post Open - National 28,171.55 Completed 2021-11-20 2022-04-13 2022-01-15 2022-05-23 2022-03-16 2022-12-06 ms - Shakers and Separation tions nvelope Republika Srpska system/Centrifugation BA-MZSZ RS-214121-GO-RF Q / Thermostatic devices - Re Component 1. Responding t Request for Quota Single Stage - One E frigerating units (Laboratory IBRD / 90970 o the COVID-19 Pandemic in Post Open - National 112,807.96 Completed 2021-12-06 2021-12-17 2022-01-31 2022-03-16 2022-04-01 2022-08-24 tions nvelope refrigerators and freezers) an Republika Srpska d Temperature controllers BA-MZSZ RS-228236-GO-RF Component 1. Responding t Request for Quota Single Stage - One E Q / Communication equipme IBRD / 90970 o the COVID-19 Pandemic in Post Open - National 0.00 Completed 2021-12-20 2022-10-21 2022-02-14 2022-08-13 tions nvelope nt Republika Srpska BA-MZSZ RS-214077-GO-RF Component 1. Responding t Request for Quota Single Stage - One E Q / Specific laboratory equip IBRD / 90970 o the COVID-19 Pandemic in Post Open - National 37,462.00 Completed 2022-01-08 2022-07-08 2022-03-05 2022-09-11 2022-04-19 2023-01-02 tions nvelope ment - Flow Cabinets Republika Srpska BA-MZSZ RS-214453-GO-RF Component 1. Responding t Request for Quota Single Stage - One E Q / Measuring systems devic IBRD / 90970 o the COVID-19 Pandemic in Post Open - National 1,489.27 Completed 2022-02-06 2022-04-13 2022-04-03 2022-06-13 2022-05-26 2022-10-21 tions nvelope es Republika Srpska Component 1. Responding t BA-MZSZ RS-214073-GO-RF Request for Quota Single Stage - One E IBRD / 90970 o the COVID-19 Pandemic in Post Open - National 0.00 Completed 2022-02-20 2022-08-09 2022-04-17 2022-06-01 Q / Sterilization devices tions nvelope Republika Srpska BA-MZSZ RS-214502-GO-RF Component 1. Responding t Request for Quota Single Stage - One E Q / Volumetry - Dispenser an IBRD / 90970 o the COVID-19 Pandemic in Post Open - National 0.00 Completed 2022-03-06 2022-10-26 2022-05-01 2022-10-28 tions nvelope d pipettes Republika Srpska Component 1. Responding t BA-MZSZ RS-214539-GO-RF Request for Quota Single Stage - One E IBRD / 90970 o the COVID-19 Pandemic in Post Open - National 0.00 Completed 2022-03-20 2022-10-26 2022-05-15 2022-11-11 Q / Supplies for laboratory tions nvelope Republika Srpska Component 1. Responding t BA-MZSZ RS-214105-GO-RF Request for Quota Single Stage - One E IBRD / 90970 o the COVID-19 Pandemic in Post Open - National 0.00 Signed 2022-05-07 2022-12-02 2022-07-02 2022-08-24 Q / Laboratory inventory tions nvelope Republika Srpska Component 1. Responding t BA-MZSZ RS-242806-GO-RF Open - Internationa Single Stage - One E IBRD / 90970 o the COVID-19 Pandemic in Prior Request for Bids 2,689,157.97 Completed 2021-09-01 2021-12-27 2021-09-06 2021-12-31 2021-10-18 2022-02-04 2021-11-17 2022-03-25 2021-12-22 2022-04-13 2022-02-20 2022-07-07 B / Medical Equipment l nvelope Republika Srpska BA-MZSZ RS-278890-GO-RF Component 1. Responding t Request for Quota Single Stage - One E Q / Procurement of 50,000 ra IBRD / 90970 o the COVID-19 Pandemic in Post Limited 994,855.64 Completed 2022-02-19 2020-05-11 2022-04-16 2020-05-12 2022-10-13 2020-08-22 tions nvelope pid COVID-19 tests Republika Srpska Component 1. Responding t BA-MZSZ RS-278892-GO-DIR IBRD / 90970 o the COVID-19 Pandemic in Post Direct Selection Direct 3,971.33 Completed 2022-02-14 2020-05-08 2022-02-19 2020-05-08 2022-03-26 2020-05-21 2022-09-22 2020-06-20 / Disposable protective suits Republika Srpska BA-MZSZ RS-278894-GO-DIR Component 1. Responding t / PCR detection kit for SARS IBRD / 90970 o the COVID-19 Pandemic in Post Direct Selection Direct 2,282.22 Completed 2022-02-14 2020-04-30 2022-02-19 2020-04-30 2022-03-26 2020-05-07 2022-09-22 2020-07-22 CoV19 Republika Srpska BA-MZSZ RS-278895-GO-DIR Component 1. Responding t / RT PCR kit for detection of S IBRD / 90970 o the COVID-19 Pandemic in Post Direct Selection Direct 2,268.47 Completed 2022-02-14 2020-04-09 2022-02-19 2020-04-14 2022-03-26 2020-04-15 2022-09-22 2020-05-15 ARS CoV19 Republika Srpska BA-MZSZ RS-278897-GO-DIR Component 1. Responding t / RT PCR kit for detection of S IBRD / 90970 o the COVID-19 Pandemic in Post Direct Selection Direct 2,268.47 Completed 2022-02-14 2020-04-09 2022-02-19 2020-04-14 2022-03-26 2020-04-15 2022-09-22 2020-05-07 ARS CoV19 Republika Srpska BA-MZSZ RS-278899-GO-DIR Component 1. Responding t / RT PCR kit for detection of S IBRD / 90970 o the COVID-19 Pandemic in Post Direct Selection Direct 2,268.47 Completed 2022-02-14 2020-04-09 2022-02-19 2020-04-14 2022-03-26 2020-04-15 2022-09-22 2020-05-20 ARS CoV19 Republika Srpska BA-MZSZ RS-278901-GO-DIR Component 1. Responding t / RT PCR kit for detection of S IBRD / 90970 o the COVID-19 Pandemic in Post Direct Selection Direct 2,268.47 Completed 2022-02-14 2020-04-09 2022-02-19 2020-04-14 2022-03-26 2020-04-15 2022-09-22 2020-06-06 ARS CoV19 Republika Srpska BA-MZSZ RS-278904-GO-DIR Component 1. Responding t / RT PCR kit for detection of S IBRD / 90970 o the COVID-19 Pandemic in Post Direct Selection Direct 2,268.47 Completed 2022-02-14 2020-04-27 2022-02-19 2020-04-30 2022-03-26 2020-05-01 2022-09-22 2020-07-22 ARS CoV19 Republika Srpska BA-MZSZ RS-278907-GO-DIR Component 1. Responding t / Reagents for preparation of IBRD / 90970 o the COVID-19 Pandemic in Post Direct Selection Direct 2,871.86 Completed 2022-02-14 2020-03-27 2022-02-19 2020-04-03 2022-03-26 2020-04-04 2022-09-22 2020-06-10 virus transportation surfaces Republika Srpska BA-MZSZ RS-278914-GO-DIR Component 1. Responding t / Reagents for preparation of IBRD / 90970 o the COVID-19 Pandemic in Post Direct Selection Direct 2,871.86 Completed 2022-02-14 2020-03-27 2022-02-19 2020-04-13 2022-03-26 2020-04-14 2022-09-22 2020-06-10 virus transportation surfaces Republika Srpska BA-MZSZ RS-278915-GO-DIR Component 1. Responding t / Reagents for preparation of IBRD / 90970 o the COVID-19 Pandemic in Post Direct Selection Direct 2,889.79 Completed 2022-02-14 2020-03-27 2022-02-19 2020-04-13 2022-03-26 2020-04-14 2022-09-22 2020-06-10 virus transportation surfaces Republika Srpska Page 5 BA-MZSZ RS-278917-GO-DIR Component 1. Responding t / Master Mix for PCR detectio IBRD / 90970 o the COVID-19 Pandemic in Post Direct Selection Direct 2,948.80 Completed 2022-02-14 2020-04-01 2022-02-19 2020-04-01 2022-03-26 2020-04-14 2022-09-22 2020-06-10 n of SARS CoV-2 Republika Srpska BA-MZSZ RS-278922-GO-DIR Component 1. Responding t / Master Mix for PCR detectio IBRD / 90970 o the COVID-19 Pandemic in Post Direct Selection Direct 2,948.80 Completed 2022-02-14 2020-04-01 2022-02-19 2020-04-01 2022-03-26 2020-04-14 2022-09-22 2020-06-10 n of SARS CoV-2 Republika Srpska BA-MZSZ RS-278926-GO-RF Component 1. Responding t Request for Quota Single Stage - One E Q / Virus transportation surfa IBRD / 90970 o the COVID-19 Pandemic in Post Limited 14,752.57 Completed 2022-02-19 2020-04-21 2022-04-16 2020-04-24 2022-10-13 2020-06-10 tions nvelope ces Republika Srpska BA-MZSZ RS-278927-GO-RF Component 1. Responding t Request for Quota Single Stage - One E Q / Kits for extraction of virus IBRD / 90970 o the COVID-19 Pandemic in Post Limited 45,687.07 Completed 2022-02-19 2020-04-24 2022-04-16 2020-04-28 2022-10-13 2020-06-10 tions nvelope RNA Republika Srpska Component 1. Responding t BA-MZSZ RS-279018-GO-DIR IBRD / 90970 o the COVID-19 Pandemic in Post Direct Selection Direct 1,334.62 Completed 2022-02-15 2020-03-31 2022-02-20 2020-03-31 2022-03-27 2020-04-01 2022-09-23 2020-06-10 / Protective masks FFP2 Republika Srpska Component 1. Responding t BA-MZSZ RS-279019-GO-DIR IBRD / 90970 o the COVID-19 Pandemic in Post Direct Selection Direct 2,616.12 Completed 2022-02-15 2020-04-07 2022-02-20 2020-04-07 2022-03-27 2020-04-14 2022-09-23 2020-05-20 / Disinfection supplies Republika Srpska Component 1. Responding t BA-MZSZ RS-279020-GO-RF Request for Quota Single Stage - One E IBRD / 90970 o the COVID-19 Pandemic in Post Limited 671,010.25 Completed 2022-02-20 2020-03-19 2022-04-17 2020-03-22 2022-10-14 2020-06-12 Q / 8 mobile X-ray devices tions nvelope Republika Srpska BA-MZSZ RS-279022-GO-RF Component 1. Responding t Request for Quota Single Stage - One E Q / 6 mobile ultrasound devic IBRD / 90970 o the COVID-19 Pandemic in Post Limited 169,726.13 Completed 2022-02-20 2020-03-31 2022-04-17 2020-04-02 2022-10-14 2020-06-27 tions nvelope es Republika Srpska Component 1. Responding t BA-MZSZ RS-279025-GO-RF Request for Quota Single Stage - One E IBRD / 90970 o the COVID-19 Pandemic in Post Limited 15,525.34 Completed 2022-02-20 2020-05-06 2022-04-17 2020-05-09 2022-10-14 2020-07-01 Q / 8 infusion pumps tions nvelope Republika Srpska Component 1. Responding t BA-MZSZ RS-279026-GO-RF Request for Quota Single Stage - One E IBRD / 90970 o the COVID-19 Pandemic in Post Limited 129,949.63 Completed 2022-02-20 2020-04-27 2022-04-17 2020-04-29 2022-10-14 2020-05-16 Q / 25 patient monitors tions nvelope Republika Srpska Component 1. Responding t BA-MZSZ RS-279028-GO-RF Request for Quota Single Stage - One E IBRD / 90970 o the COVID-19 Pandemic in Post Limited 16,190.70 Completed 2022-02-20 2020-05-05 2022-04-17 2020-05-07 2022-10-14 2020-05-16 Q / 10 infusion pumps tions nvelope Republika Srpska Component 1. Responding t BA-MZSZ RS-279029-GO-DIR IBRD / 90970 o the COVID-19 Pandemic in Post Direct Selection Direct 3,409.99 Completed 2022-02-15 2020-05-06 2022-02-20 2020-05-06 2022-03-27 2020-05-13 2022-09-23 2020-05-16 / Perfusion pumps Republika Srpska BA-MZSZ RS-279045-GO-DIR Component 1. Responding t / Production and installing of IBRD / 90970 o the COVID-19 Pandemic in Post Direct Selection Direct 1,129.44 Completed 2022-02-15 2020-04-14 2022-02-20 2020-04-15 2022-03-27 2020-04-17 2022-09-23 2020-05-19 doors Republika Srpska Component 1. Responding t BA-MZSZ RS-279048-GO-DIR IBRD / 90970 o the COVID-19 Pandemic in Post Direct Selection Direct 126.27 Completed 2022-02-15 2020-05-15 2022-02-20 2020-05-18 2022-03-27 2020-05-19 2022-09-23 2020-05-20 / 2 water hoses and 2 nozzles Republika Srpska Component 1. Responding t BA-MZSZ RS-279265-GO-DIR IBRD / 90970 o the COVID-19 Pandemic in Post Direct Selection Direct 3,964.38 Completed 2022-02-16 2020-05-04 2022-02-21 2020-05-04 2022-03-28 2020-05-05 2022-09-24 2020-07-16 / PVC dishes and utensils Republika Srpska BA-MZSZ RS-279317-GO-RF Component 1. Responding t Request for Quota Single Stage - One E Q / Meat, meat products, fres IBRD / 90970 o the COVID-19 Pandemic in Post Limited 164,553.06 Completed 2022-02-21 2020-02-17 2022-04-18 2020-02-19 2022-10-15 2020-07-16 tions nvelope h and frozen fish and fish pro Republika Srpska ducts BA-MZSZ RS-279050-GO-DIR Component 1. Responding t / Goods, bags and bins for inf IBRD / 90970 o the COVID-19 Pandemic in Post Direct Selection Direct 3,924.23 Completed 2022-02-15 2020-04-02 2022-02-20 2020-04-02 2022-03-27 2020-04-04 2022-09-23 2020-06-16 ectious waste Republika Srpska Component 1. Responding t BA-MZSZ RS-279285-GO-DIR IBRD / 90970 o the COVID-19 Pandemic in Post Direct Selection Direct 660.72 Completed 2022-02-16 2020-03-05 2022-02-21 2020-03-05 2022-03-28 2020-03-06 2022-09-24 2020-07-16 / Disinfection supplies Republika Srpska BA-MZSZ RS-279310-GO-RF Component 1. Responding t Single Stage - One E B / Hygiene and maintenance IBRD / 90970 o the COVID-19 Pandemic in Post Request for Bids Open - National 0.00 Canceled 2022-02-16 2022-02-21 2022-04-04 2022-05-04 2022-06-08 2022-12-05 nvelope supplies Republika Srpska Component 1. Responding t BA-MZSZ RS-278924-GO-DIR IBRD / 90970 o the COVID-19 Pandemic in Post Direct Selection Direct 762.46 Completed 2022-02-14 2020-04-30 2022-02-19 2020-04-30 2022-03-26 2020-05-12 2022-09-22 2020-06-10 / PCR test tubes Republika Srpska Component 1. Responding t BA-MZSZ RS-279030-GO-DIR IBRD / 90970 o the COVID-19 Pandemic in Post Direct Selection Direct 1,629.88 Completed 2022-02-15 2020-05-13 2022-02-20 2020-05-14 2022-03-27 2020-05-16 2022-09-23 2020-05-20 / Supplies for wall painting Republika Srpska Component 1. Responding t BA-MZSZ RS-279266-GO-RF Open - Internationa Single Stage - One E IBRD / 90970 o the COVID-19 Pandemic in Post Request for Bids 0.00 Canceled 2022-02-23 2018-10-29 2022-02-28 2022-04-11 2022-05-11 2022-06-15 2022-12-12 B / Food supplies l nvelope Republika Srpska BA-MZSZ RS-286264-GO-RF Component 1. Responding t Q / Food supplies - framewor Request for Quota Single Stage - One E IBRD / 90970 o the COVID-19 Pandemic in Post Limited 328,872.33 Completed 2022-03-28 2018-10-29 2022-05-23 2019-12-14 2022-11-19 2020-07-16 k agreement No. 339/19, and tions nvelope Republika Srpska contract No. 2191/19 (Novot eks) - SC Nikola Tesla BA-MZSZ RS-286284-GO-RF Q / Hygiene and maintenanc Component 1. Responding t Request for Quota Single Stage - One E e supplies - framework agree IBRD / 90970 o the COVID-19 Pandemic in Post Limited 25,170.71 Completed 2022-03-28 2019-03-05 2022-05-23 2019-07-05 2022-11-19 2020-07-16 tions nvelope ment No. 1237/19 (Novoteks) Republika Srpska - Contract No. 1238/19 - SC N ikola Tesla BA-MZSZ RS-289329-GO-RF Component 1. Responding t Request for Quota Single Stage - One E Q / Procurement of office fur IBRD / 90970 o the COVID-19 Pandemic in Post Limited 6,750.82 Completed 2022-04-17 2022-04-15 2022-06-12 2022-04-29 2022-12-09 2022-05-19 tions nvelope niture for MoHSW Republika Srpska BA-MZSZ RS-297862-GO-RF Component 1. Responding t Single Stage - One E B / Procurement of ambulanc IBRD / 90970 o the COVID-19 Pandemic in Post Request for Bids Open - National 0.00 Completed 2022-07-01 2022-09-30 2022-07-06 2022-09-30 2022-08-17 2022-10-28 2022-09-16 2022-10-31 2022-10-21 2023-04-19 nvelope es Republika Srpska BA-MZSZ RS-297864-GO-RF Component 1. Responding t Request for Quota Single Stage - One E Q / Procurement of microsco IBRD / 90970 o the COVID-19 Pandemic in Post Open - National 13,188.63 Completed 2022-09-06 2022-07-11 2022-11-01 2022-09-11 2023-04-30 2022-10-11 tions nvelope pes Republika Srpska Page 6 BA-MZSZ RS-214532-GO-RF Component 1. Responding t B / Hardware, software and c Single Stage - One E Under Imple IBRD / 90970 o the COVID-19 Pandemic in Post Request for Bids Open - National 0.00 2022-04-01 2022-12-13 2022-04-06 2023-02-08 2022-05-18 2023-01-13 2022-06-17 2023-01-25 2022-07-22 2022-09-11 ommunication equipment for nvelope mentation Republika Srpska PHI Institute for Public Health of Republika Srpska Component 1. Responding t BA-MZSZ RS-341230-GO-RF Request for Quota Single Stage - One E IBRD / 90970 o the COVID-19 Pandemic in Post Open - National 0.00 Signed 2023-03-06 2023-03-22 2023-05-01 2023-06-30 Q / Medical equipment tions nvelope Republika Srpska BA-MZSZ RS-341245-GO-RF Component 3. Project Manag Request for Quota Single Stage - One E Under Imple IBRD / 90970 Post Open - National 0.00 2023-02-25 2023-03-03 2023-04-22 2023-06-21 Q / IT and office equipment ement tions nvelope mentation BA-MZSZ RS-341253-GO-RF Component 3. Project Manag Request for Quota Single Stage - One E IBRD / 90970 Post Open - National 0.00 Completed 2023-02-20 2023-03-22 2023-04-17 2023-06-16 Q / Vehicle ement tions nvelope BA-MZSZ RS-364091-GO-RF Component 3. Project Manag Request for Quota Single Stage - One E Pending Impl IBRD / 90970 Post Open - National 0.00 2023-06-08 2023-06-18 2023-06-28 Q / IT Equipment ement tions nvelope ementation NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BA-MZSZ RS-217273-NC-DIR Component 1. Responding t / Laundry services - MAX FRE IBRD / 90970 o the COVID-19 Pandemic in Post Direct Selection Direct 925.93 Completed 2021-03-01 2021-07-27 2021-03-06 2021-07-27 2021-04-10 2021-07-28 2021-10-07 2021-07-28 SH (02-85-15/20) - retroactiv Republika Srpska e financing - City of Bijeljina Component 1. Responding t BA-MZSZ RS-214070-NC-RF Request for Quota Single Stage - One E IBRD / 90970 o the COVID-19 Pandemic in Post Open - National 17.33 Signed 2021-03-06 2021-05-01 2021-03-06 2021-10-28 Q / Translation services tions nvelope Republika Srpska BA-MZSZ RS-217333-NC-DIR Component 1. Responding t / Cleaning services - BINGO C IBRD / 90970 o the COVID-19 Pandemic in Post Direct Selection Direct 2,592.60 Completed 2021-03-01 2021-07-27 2021-03-06 2021-07-27 2021-04-10 2021-07-28 2021-10-07 2021-07-28 LEAN (02-85-20/20) - retroact Republika Srpska ive financing - City of Bijeljin a BA-MZSZ RS-254525-NC-DIR Component 3. Project Manag IBRD / 90970 Post Direct Selection Direct 2,771.04 Signed 2021-09-27 2021-09-24 2021-10-02 2021-10-18 2021-11-06 2021-11-02 2022-05-05 / COVID-19 related Media mo ement nitoring Component 1. Responding t BA-MZSZ RS-279040-NC-DIR IBRD / 90970 o the COVID-19 Pandemic in Post Direct Selection Direct 1,028.55 Completed 2022-02-15 2020-04-07 2022-02-20 2020-04-22 2022-03-27 2020-04-25 2022-09-23 2020-05-19 / Laundry services Republika Srpska Component 1. Responding t BA-MZSZ RS-279041-NC-DIR IBRD / 90970 o the COVID-19 Pandemic in Post Direct Selection Direct 1,021.51 Completed 2022-02-15 2020-05-11 2022-02-20 2020-05-11 2022-03-27 2020-05-14 2022-09-23 2020-05-20 / Laundry services Republika Srpska Component 1. Responding t BA-MZSZ RS-279043-NC-DIR IBRD / 90970 o the COVID-19 Pandemic in Post Direct Selection Direct 368.88 Completed 2022-02-15 2020-04-07 2022-02-20 2020-05-18 2022-03-27 2020-05-20 2022-09-23 2020-05-20 / Laundry services Republika Srpska BA-MZSZ RS-279051-NC-RF Component 1. Responding t Request for Quota Single Stage - One E Q / Infectious waste gatherin IBRD / 90970 o the COVID-19 Pandemic in Post Limited 33,015.32 Completed 2022-02-20 2020-03-30 2022-04-17 2020-04-04 2022-10-14 2020-07-16 tions nvelope g, transportation and treatm Republika Srpska ent BA-MZSZ RS-279056-NC-DIR Component 1. Responding t / Infectious waste gathering, IBRD / 90970 o the COVID-19 Pandemic in Post Direct Selection Direct 3,961.87 Completed 2022-02-15 2020-06-01 2022-02-20 2020-06-01 2022-03-27 2020-06-05 2022-09-23 2020-07-20 transportation and treatment Republika Srpska Component 1. Responding t BA-MZSZ RS-279059-NC-RF Request for Quota Single Stage - One E IBRD / 90970 o the COVID-19 Pandemic in Post Limited 13,074.07 Completed 2022-02-20 2020-03-14 2022-04-17 2020-03-17 2022-10-14 2020-07-30 Q / Disinfection services tions nvelope Republika Srpska Component 1. Responding t BA-MZSZ RS-279116-NC-DIR IBRD / 90970 o the COVID-19 Pandemic in Post Direct Selection Direct 3,862.79 Completed 2022-02-15 2020-03-30 2022-02-20 2020-03-30 2022-03-27 2020-03-31 2022-09-23 2020-06-16 / Installation of fence Republika Srpska BA-MZSZ RS-279033-NC-DIR Component 1. Responding t / Medical waste gathering, tr IBRD / 90970 o the COVID-19 Pandemic in Post Direct Selection Direct 5,352.81 Completed 2022-02-15 2020-03-31 2022-02-20 2020-04-01 2022-03-27 2020-04-04 2022-09-23 2020-05-20 ansportation and treatment Republika Srpska BA-MZSZ RS-286300-GO-DIR Component 1. Responding t / Washing of mattresses - Co IBRD / 90970 o the COVID-19 Pandemic in Post Direct Selection Direct 3,909.43 Completed 2022-03-23 2020-06-10 2022-03-28 2020-06-10 2022-05-02 2020-06-11 2022-10-29 2020-07-09 ntract No. 915/20 (Samsic) - Republika Srpska SC Nikola Tesla CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BA-MZSZ RS-214126-CS-CQ Component 1. Responding t Consultant Qualifi S / Public information campai IBRD / 90970 o the COVID-19 Pandemic in Post Open - National 0.00 Canceled 2021-06-14 2021-07-05 2021-08-18 2021-09-17 2021-10-22 2022-04-20 cation Selection gns Republika Srpska BA-MZSZ RS-242791-CS-CQ Component 1. Responding t Consultant Qualifi S / Education of Covid19 Trea IBRD / 90970 o the COVID-19 Pandemic in Post Open - National 0.00 Canceled 2022-05-16 2022-06-06 2022-07-20 2022-08-19 2022-09-23 2022-10-23 cation Selection tment Health Care Workers Republika Srpska BA-MZSZ RS-214128-CS-CQ Component 1. Responding t Consultant Qualifi S / Development of plans and IBRD / 90970 o the COVID-19 Pandemic in Post Open - National 0.00 Canceled 2022-04-15 2022-05-06 2022-06-19 2022-07-19 2022-08-23 2023-02-19 cation Selection strategies Republika Srpska BA-MZSZ RS-279473-CS-CQ Component 1. Responding t Consultant Qualifi S / Development of standard IBRD / 90970 o the COVID-19 Pandemic in Post Open - National 0.00 Canceled 2022-03-15 2022-05-10 2022-04-05 2022-07-08 2022-05-19 2022-06-18 2022-07-23 2022-10-21 cation Selection operational procedures Republika Srpska BA-MZSZ RS-279475-CS-CQ Component 1. Responding t Consultant Qualifi S / Development of pandemic IBRD / 90970 o the COVID-19 Pandemic in Post Open - National 0.00 Canceled 2022-04-15 2022-03-31 2022-05-06 2022-09-21 2022-06-19 2022-07-19 2022-08-23 2022-11-21 cation Selection preparedness/readiness plan Republika Srpska INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Actual Amount Invitation to Identifie Draft Negotiated Cont Component Review Type Method Contract Type Process Status Teams of Reference Signed Contract Contract Completion Description o. h (US$) d/Selected Consultant ract Page 7 Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 1. Responding t BA-MZSZ RS-214183-CS-IND Individual Consult IBRD / 90970 o the COVID-19 Pandemic in Post Open 15,243.71 Signed 2021-03-01 2021-04-05 2021-04-19 2021-05-10 2021-05-10 2021-05-21 2021-06-14 2021-05-27 2022-06-30 V / Consultant for ESM ant Selection Republika Srpska BA-MZSZ RS-214076-CS-IND Component 1. Responding t Individual Consult V / Consultant for M&E and S IBRD / 90970 o the COVID-19 Pandemic in Post Open 15,243.71 Completed 2021-03-01 2021-04-05 2021-04-19 2021-05-18 2021-05-10 2021-05-26 2021-06-14 2021-05-30 2022-06-30 2022-07-09 ant Selection EP Republika Srpska Component 1. Responding t BA-MZSZ RS-242796-CS-IND Individual Consult IBRD / 90970 o the COVID-19 Pandemic in Post Direct 5,441.18 Signed 2021-08-13 2021-07-29 2021-08-23 2021-09-06 2021-09-13 2021-09-17 2021-10-18 2021-09-24 2022-06-30 V / Procurement Specialist ant Selection Republika Srpska Component 1. Responding t BA-MZSZ RS-244832-CS-CD IBRD / 90970 o the COVID-19 Pandemic in Post Direct Selection Direct 0.00 Canceled 2021-08-16 2021-08-26 2021-10-30 2022-07-17 S / Press Clipping Republika Srpska Page 8 PROCUREMENT PLAN (Textual Part) Project information: Country: Bangladesh Project name: Cash Transfer Modernization Project (P160819) Project Implementation agency: Department of Social Services. Date of the Procurement Plan: October 04, 2017 Period covered by this Procurement Plan: December 2017 to June 2022 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the Public Procurement Act, 2006 - PPA, 1st amendment to PPA (2009) and the Public Procurement Rules, 2008, as amended in August 2009) of the People’s Republic of Bangladesh such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. a) Post bidding negotiations shall not be allowed with the lowest evaluated or any other bidder; b) Bids should be submitted and opened in public in one location immediately after the deadline for submission; c) Lottery in award of contracts shall not be allowed; d) Bidders’ qualification/experience requirement shall be mandatory e) Bids shall not be invited or rejected on the basis of percentage above or below the estimated cost. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. Not Applicable Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables – Not Applicable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: is applicable for those contracts identified in the Procurement Plan tables; Other Relevant Procurement Information. Prior Review Thresholds Type of Procurement Method Prior Review Thresholds Remarks Procurement (Estimated Cost of the Contract/Package) Works (including RFB, RFP, Direct Selection >=US$ 10,000,000 turnkey, supply & RFQ None installation of plant and equipment, and PPP) Goods, information RFB, RFP, Direct Selection >=US$ 2,000,000 technology and non- RFQ None consulting services Consultants: firms QCBS, QBS, FBS, CQS, >=US$ 1,000,000 LCS, Direct Selection Consultants: IC (Open, Limited), Direct >=US$ 300,000 Individual Selection Notes: 1. Irrespective of the contract value, the following procurement activities are subject to the Bank’s procurement prior review: a. procurement processes involving contract negotiations as, described in paragraphs 6.34-36 of Section VI of the Procurement Regulation for Borrowers; b. competitive dialogue; c. sustainable procurement; and d. best and final offer. 2. Use of Standard Procurement Documents: For all procurements under the project, the Bank’s Standard Procurement Documents (or other documents agreed with the Bank) shall be used; PROCUREMENT Bangladesh : Cash Transfer Modernization Project PLAN General Information Country: Bangladesh 2017-11-20 Bank’s Approval Date of the Original Procurement Plan: 2023-06-05 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P160819 GPN Date: 2020-02-20 Project Name: Cash Transfer Modernization Project Loan / Credit No: / , IDA / 61630 Department of Social Services Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Request for Quota WD-01 / Renovation & Setup Modernization of Service Del Request for Quota Single Stage - One E 2022-06-2 IDA / 61630 Post Limited tions (Non Bank-S 11,700.00 10,507.22 Completed 2022-04-25 2022-05-26 2022-05-09 2022-06-18 of New Rental office of CTM p ivery tions nvelope 3 PD) roject. WD-02 / Fitting fixing & Setu Request for Quota p of sitting arrangement of P Modernization of Service Del Request for Quota Single Stage - One E 2022-06-2 IDA / 61630 Post Limited tions (Non Bank-S 11,650.00 10,514.02 Signed 2022-04-30 2022-05-26 2022-05-14 2022-06-09 D, DPD and office staffs at N ivery tions nvelope 8 PD) ew Rental office of CTM Proje ct. GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GD-05 / Android tab (all USW Modernization of Service Del Single Stage - One E / Post Request for Bids Open - National 1,441,000.00 0.00 Canceled 2018-01-10 2018-01-15 2018-02-26 2018-03-28 2018-05-02 2018-10-29 s & TIs) ivery nvelope GD-06 / Supply of MIS Hardw are - (a) MIS Hardware & Equ Modernization of Service Del Single Stage - One E ipment (servers, racks, route IDA / 61630 Post Request for Bids Open - National 1,900,000.00 0.00 Canceled 2020-03-16 2020-03-21 2020-05-02 2020-06-01 2020-07-06 2021-01-02 ivery nvelope rs, etc.) & (b) Licensed Datab ase Software with required d evices/infrastructure GD-07 / Supply of Bio-metric Modernization of Service Del Single Stage - One E IDA / 61630 Post Request for Bids Open - National 82,000.00 0.00 Canceled 2019-08-18 2019-08-23 2019-10-04 2019-11-03 2019-12-08 2020-03-07 scanner for all units ivery nvelope GD-09 / Supply of Furniture f Modernization of Service Del Request for Quota Single Stage - One E IDA / 61630 Post Open - National 5,000.00 0.00 Canceled 2019-04-05 2019-05-31 2019-11-27 or PMU, DSS IT Cell & MSW IT ivery tions nvelope Cell GD-10 / Supply of Office fixt Modernization of Service Del Single Stage - One E IDA / 61630 Post Request for Bids Open - National 7,000.00 0.00 Canceled 2019-04-21 2019-04-26 2019-06-07 2019-07-07 2019-08-11 2019-08-31 ures for PMU, DSS IT Cell ivery nvelope GD-11 / Supply of Air Conditi Modernization of Service Del Request for Quota Single Stage - One E IDA / 61630 Post Open - National 2,400.00 0.00 Canceled 2019-04-30 2019-06-25 2019-07-28 oner For PMU, DSS IT Cell ivery tions nvelope GD-12 / Supply of Accountin Modernization of Service Del Request for Quota Single Stage - One E IDA / 61630 Post Open - National 6,000.00 0.00 Canceled 2019-04-05 2019-05-31 2019-06-20 g Software ivery tions nvelope GD-02 / Supply of Laptops, P rinters, Multimedia Projectors Modernization of Service Del Single Stage - One E IDA / 61630 Post Request for Bids Open - National 874,000.00 0.00 Canceled 2020-06-15 2020-06-14 2020-06-20 2020-08-01 2020-07-23 2020-08-31 2020-09-13 2020-10-05 2021-02-02 & Accessories (peripherals) f ivery nvelope or PMU, all districts and all u nit offices. GD 03 / Supply of Photocopi Modernization of Service Del Single Stage - One E IDA / 61630 Post Request for Bids Open - National 272,000.00 196,101.81 Completed 2020-06-15 2020-06-14 2020-06-20 2020-08-01 2020-07-23 2020-08-31 2020-09-13 2020-10-05 2020-10-13 2021-02-02 2021-05-07 er and Scanner (PMU and all ivery nvelope districts) GD 08 / Supply of Office fixt Modernization of Service Del Single Stage - One E IDA / 61630 Post Request for Bids Open - National 6,064.00 0.00 Canceled 2020-12-15 2021-02-28 2020-12-20 2021-01-31 2021-03-02 2021-04-06 2021-05-06 ures for PMU, DSS IT Cell ivery nvelope GD-13 / Supply of Desktops, Modernization of Service Del Request for Quota Single Stage - One E IDA / 61630 Post Limited 6,064.00 5,884.78 Signed 2020-06-05 2020-06-02 2020-06-26 2020-06-22 2020-07-26 Laptops, Printers & UPS for P ivery tions nvelope MU office GD-08 / Supply of Office fixt Modernization of Service Del Request for Quota Single Stage - One E IDA / 61630 Post Limited 6,064.00 5,890.16 Completed 2021-09-20 2021-02-28 2021-10-21 2021-03-10 2021-12-04 2021-04-13 ures for PMU, DSS IT Cell ivery tions nvelope GD 10 / Supply of Accountin Modernization of Service Del Request for Quota Single Stage - One E IDA / 61630 Post Open - National 6,000.00 5,885.96 Completed 2020-11-23 2021-01-18 2021-01-06 2021-04-18 2021-04-13 g Software ivery tions nvelope GD 07 / Supply of Furniture f Modernization of Service Del Request for Quota Single Stage - One E IDA / 61630 Post Open - National 6,064.00 11,672.06 Completed 2020-11-30 2021-01-25 2020-12-31 2021-02-24 2021-02-18 or PMU, DSS IT Cell ivery tions nvelope GD 09 / Supply of Air Conditi Modernization of Service Del Request for Quota Single Stage - One E IDA / 61630 Post Open - National 2,400.00 2,352.73 Completed 2021-03-02 2021-04-27 2021-03-10 2021-05-27 2021-04-13 oner For PMU, DSS IT Cell ivery tions nvelope GD-01 / Supply of Motor cycl Modernization of Service Del Single Stage - One E IDA / 61630 Post Request for Bids Open - National 1,200,000.00 0.00 Canceled 2021-01-10 2020-12-06 2021-01-13 2021-02-10 2021-01-18 2021-03-12 2021-03-21 2021-03-28 2021-06-26 e for all units ivery nvelope GD-04 / Supply of Android T Modernization of Service Del Single Stage - One E IDA / 61630 Post Request for Bids Open - National 1,400,000.00 1,354,178.21 Signed 2020-10-15 2020-11-10 2020-10-20 2020-11-19 2020-12-10 2020-12-19 2021-02-23 2021-01-23 2021-03-19 2021-05-23 ab for all USWs and TIs ivery nvelope GD-02.1 / Supply of Laptops, Printers, Multimedia Projector Enhancement of Cash Transf Single Stage - One E IDA / 61630 Post Request for Bids Open - National 869,328.09 825,500.92 Completed 2020-09-24 2020-10-11 2020-09-29 2020-10-20 2020-11-02 2020-11-10 2020-12-08 2020-12-22 2020-12-23 2021-04-21 2021-06-28 s & Accessories (peripherals) er Programs nvelope (PMU, all districts and all unit offices) GD-1 / Supply of Motor cycle Modernization of Service Del Single Stage - One E IDA / 61630 Post Request for Bids Open - National 1,246,875.00 1,049,289.77 Signed 2021-08-15 2021-12-15 2021-08-20 2021-09-17 2022-01-19 2021-10-17 2022-03-23 2021-11-21 2022-07-14 2022-05-20 for all unit offices of DSS ivery nvelope GD-14 / Supply and Installati Modernization of Service Del Request for Quota Single Stage - One E on of PABX system for PMU o IDA / 61630 Post Limited 3,600.00 3,491.80 Completed 2021-04-23 2021-06-07 2021-05-06 2021-06-15 2021-06-05 2021-06-21 ivery tions nvelope ffice of CTM Project. GD-15 / Setup of Seating arr Modernization of Service Del Request for Quota Single Stage - One E angement of Project Personn IDA / 61630 Post Limited 5,800.00 5,241.55 Signed 2022-04-10 2022-06-30 2022-05-02 2022-06-10 2022-05-23 ivery tions nvelope el at new Rental offices of CT M. Page 1 GD-16 / Maintenance and se Modernization of Service Del Request for Quota Single Stage - One E tup of Electric materials in th IDA / 61630 Post Limited 5,900.00 5,640.98 Signed 2022-04-19 2022-04-18 2022-05-07 2022-04-25 2022-06-06 ivery tions nvelope e new Rental office of CTM GD-17 / Printing and Binding of Book (Social Management Modernization of Service Del Request for Quota Single Stage - One E IDA / 61630 Post Limited 5,850.00 5,248.30 Signed 2022-04-30 2022-05-12 2022-05-14 2022-06-07 2022-06-13 framework & Small Ethnic Co ivery tions nvelope mmunity planning framework ) GD-18 / Supply of Computer Modernization of Service Del Request for Quota Single Stage - One E IDA / 61630 Post Limited 5,800.00 0.00 Signed 2022-04-25 2022-05-30 2022-05-09 2022-06-08 Consumables and Printer Car ivery tions nvelope tridge. GD-19 / Supply of Office Stat Modernization of Service Del Request for Quota Single Stage - One E ioneries, stamps and seals fo IDA / 61630 Post Limited 5,900.00 5,241.55 Completed 2022-04-25 2022-05-30 2022-05-09 2022-06-19 2022-06-08 2022-06-23 ivery tions nvelope r CTM Project. GD 05 / Supply of MIS Hardw are - (a) MIS Hardware & Equ Modernization of Service Del Single Stage - One E ipment (servers, racks, route IDA / 61630 Post Request for Bids Open - National 1,900,000.00 0.00 Canceled 2022-09-25 2022-09-30 2022-11-11 2022-12-11 2023-01-15 2023-06-30 ivery nvelope rs, etc.) & (b) Licensed Datab ase Software with required d evices/infrastructure GD 06 / Supply of Bio-metric Modernization of Service Del Single Stage - One E IDA / 61630 Post Request for Bids Open - National 82,000.00 0.00 Canceled 2022-09-30 2022-10-05 2022-10-26 2022-11-25 2023-01-06 2023-05-06 scanner for all units ivery nvelope GD-20 / Supply of Laptop, Pri Modernization of Service Del Single Stage - One E Under Imple nter and accessories for MoS IDA / 61630 Post Request for Bids Open - National 23,500.00 0.00 2023-03-15 2023-03-16 2023-03-20 2023-04-10 2023-04-10 2023-04-24 2023-05-09 2023-05-22 2023-09-19 ivery nvelope mentation W, Social Security wing of DS S & CTM. GD-22 / Supply of Office Stat Modernization of Service Del Request for Quota Single Stage - One E Under Imple IDA / 61630 Post Limited 5,900.00 0.00 2023-04-12 2023-05-11 2023-04-30 2023-05-30 ioneries, stamps and seals ivery tions nvelope mentation GD-23 / Printing of Folder, N Modernization of Service Del Request for Quota Single Stage - One E Under Imple ote Book, File Cover, Envelop IDA / 61630 Post Limited 5,800.00 0.00 2023-04-19 2023-05-08 2023-06-07 ivery tions nvelope mentation es etc. for office use, FY-202 2-23 GD-40 / Supply of Miscellane ous Consumable Items (such Modernization of Service Del Request for Quota Single Stage - One E Under Imple as Photocopier Toner, Printer IDA / 61630 Post Limited 5,000.00 0.00 2023-06-12 2023-06-21 2023-06-28 ivery tions nvelope mentation Toner, Portable Hard Drive, R echargeable Fan etc.) for offi ce Management. GD-24 / Supply and fitting fi Modernization of Service Del Request for Quota Single Stage - One E Pending Impl IDA / 61630 Post Limited 5,900.00 0.00 2023-08-18 2023-09-06 2023-10-06 xing of Furniture for Confere ivery tions nvelope ementation nce Room. GD-21 / Supply of Computer Modernization of Service Del Request for Quota Single Stage - One E Pending Impl Consumables, Printer Cartrid IDA / 61630 Post Limited 5,800.00 0.00 2023-10-20 2023-11-06 2023-12-06 ivery tions nvelope ementation ge and Photocopier Cartridge for FY2022-23. GD-33 / Supply & Installation Modernization of Service Del Request for Quota Single Stage - One E Pending Impl of IPS/Generator for PMU offi IDA / 61630 Post Limited 5,800.00 0.00 2023-07-13 2023-08-01 2023-08-31 ivery tions nvelope ementation ce of CTM Project NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NCS-02 / Selection of Interne t Service Provider Organizati Modernization of Service Del Single Stage - One E IDA / 61630 Post Request for Bids Open - National 1,963,050.00 0.00 Canceled 2022-04-25 2021-12-05 2022-04-30 2022-05-28 2022-01-10 2022-06-27 2022-08-01 2023-06-30 on for supply of Internet SIM ivery nvelope plus connectivity and Data CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SD-14 / Selection of Consult Modernization of Service Del Fixed Budget Sele IDA / 61630 Post Open - National 45,000.00 0.00 Canceled 2019-08-05 2019-08-26 2019-10-09 2019-11-06 2019-12-06 2020-01-10 2020-02-14 2021-02-13 ant for Internal Audit ivery ction SD-15 / Selection of Consult Modernization of Service Del Consultant Qualifi IDA / 61630 Post Open - National 37,000.00 0.00 Canceled 2019-06-10 2019-07-01 2019-08-14 2019-09-13 2019-10-18 2020-04-15 ant for IT Audit ivery cation Selection SD 09 / Selection of Consulta Modernization of Service Del Quality And Cost- Open - Internationa IDA / 61630 Post 600,000.00 544,520.22 Signed 2020-06-20 2020-07-09 2020-07-11 2020-07-29 2020-08-24 2020-11-04 2020-09-21 2020-12-17 2020-10-21 2021-02-11 2020-11-25 2021-04-13 2020-12-30 2021-06-25 2021-12-30 nt Firm for Operational Revie ivery Based Selection l w SD 08 / Selection of Consulta Modernization of Service Del Quality And Cost- Open - Internationa IDA / 61630 Prior 1,100,000.00 1,065,715.72 Signed 2020-11-15 2021-01-25 2020-12-06 2021-01-28 2021-01-19 2021-09-09 2021-02-16 2021-11-09 2021-03-18 2021-12-20 2021-04-22 2022-04-03 2021-05-27 2022-05-24 2022-05-27 nt Firm for Publicity & Trainin ivery Based Selection l g SD 11 / Selection of Consulta Modernization of Service Del Consultant Qualifi IDA / 61630 Post Open - National 37,000.00 0.00 Canceled 2021-09-20 2021-10-11 2021-11-24 2021-12-24 2022-01-28 2022-07-27 nt Firm for IT Audit ivery cation Selection SD 10 / Selection of Consulta Modernization of Service Del Fixed Budget Sele IDA / 61630 Post Open - National 45,000.00 0.00 Canceled 2022-09-15 2022-10-06 2022-11-19 2022-12-17 2023-01-16 2023-02-20 2023-03-27 2024-03-26 nt Firm for Internal Audit ivery ction SD 07 / Selection of Consulta Modernization of Service Del Quality And Cost- Open - Internationa IDA / 61630 Prior 2,150,000.00 0.00 Signed 2021-12-15 2021-11-02 2022-01-05 2021-11-16 2022-02-18 2022-11-03 2022-03-18 2022-12-27 2022-04-17 2023-03-07 2022-05-22 2023-04-13 2022-06-26 2024-06-30 nt Firm for Upgradation of MI ivery Based Selection l S SD-10 / Selection of Internal Modernization of Service Del Consultant Qualifi IDA / 61630 Post Limited 45,000.00 43,338.19 Signed 2021-09-15 2021-11-09 2021-09-29 2022-01-19 2021-10-29 2022-02-14 2021-12-03 2022-02-25 2022-06-01 Audit Firm ivery cation Selection SD-11 / Selection of Consult Modernization of Service Del Consultant Qualifi Pending Impleme IDA / 61630 Post Limited 37,000.00 0.00 2023-11-15 2023-11-22 2023-12-22 2024-01-26 2024-05-30 ant Firm for IT Audit ivery cation Selection ntation SD-13 / Selection of NGO for providing services for Produc Quality And Cost- Open - Internationa Under Implement IDA / 61630 Cash+ Innovations Prior 2,000,000.00 0.00 2023-04-16 2023-05-11 2023-05-07 2023-06-06 2023-06-20 2023-07-18 2023-08-17 2023-09-07 2023-10-01 2025-03-29 tive Economic Inclusion (PEI) Based Selection l ation Pilot Management.* SD - 14 / Selection of NGO fo Quality And Cost- Open - Internationa Under Implement r providing services for Older IDA / 61630 Cash+ Innovations Prior 1,500,000.00 0.00 2023-04-16 2023-05-11 2023-05-07 2023-06-06 2023-06-20 2023-07-18 2023-08-17 2023-09-07 2023-10-01 2025-03-29 Based Selection l ation Persons' Club (OPC) Pilot Ma nagement * Page 2 INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SD-02 / Selection of Consult Modernization of Service Del Individual Consult IDA / 61630 Prior Open 308,000.00 210,064.08 Signed 2019-03-31 2019-04-11 2019-05-28 2019-10-15 2019-06-18 2019-12-30 2019-07-23 2020-02-24 2023-06-30 ant for Financial Managemen ivery ant Selection t Specialist SD-01 / Selection of Consult Modernization of Service Del Individual Consult IDA / 61630 Prior Open 308,000.00 190,870.31 Signed 2019-03-31 2019-04-11 2019-05-25 2019-10-15 2019-06-15 2019-12-22 2019-07-20 2020-01-02 2023-06-29 ant for Procurement Specialis ivery ant Selection t SD-07 / Selection of Consult Modernization of Service Del Individual Consult IDA / 61630 Post Open 222,000.00 0.00 Canceled 2019-03-31 2019-05-19 2019-06-09 2019-07-14 2023-04-24 ant for Safeguard Specialist ivery ant Selection SD-03 / Selection of Consult Modernization of Service Del Individual Consult IDA / 61630 Post Open 280,000.00 0.00 Canceled 2019-04-15 2019-06-03 2019-06-24 2019-07-29 2023-06-30 ant for MIS Specialist ivery ant Selection SD-04 / Selection of Consult Modernization of Service Del Individual Consult IDA / 61630 Post Open 222,000.00 0.00 Canceled 2019-11-12 2019-12-31 2020-01-21 2020-02-25 2023-12-06 ant for Hardware & Network ivery ant Selection Engineer SD 04 / Selection of Consulta Modernization of Service Del Individual Consult IDA / 61630 Post Open 280,000.00 159,603.07 Signed 2019-08-08 2020-01-28 2019-09-26 2020-06-22 2019-10-17 2020-08-19 2019-11-21 2020-09-28 2023-06-29 nt for MIS Specialist ivery ant Selection SD-05 / Selection of Consult Modernization of Service Del Individual Consult IDA / 61630 Post Open 222,000.00 107,867.95 Signed 2019-08-08 2020-01-28 2019-09-26 2020-10-27 2019-10-17 2021-01-18 2019-11-21 2021-03-10 2023-06-29 ant for Database Administrat ivery ant Selection or SD 03 / Safeguards Specialis Modernization of Service Del Individual Consult IDA / 61630 Post Open 222,000.00 183,614.85 Signed 2019-05-09 2019-05-02 2019-06-27 2019-11-03 2019-07-18 2019-11-06 2019-08-22 2020-01-02 2023-06-02 t ivery ant Selection SD 06 / Selection of Consulta Modernization of Service Del Individual Consult IDA / 61630 Post Open 222,000.00 107,880.67 Signed 2020-06-25 2020-06-07 2020-08-13 2020-10-27 2020-09-03 2021-01-18 2020-10-08 2021-03-02 2023-06-30 nt for Hardware & Network E ivery ant Selection ngineer SD-12 / System Upgradation Modernization of Service Del , Feature Enhancement and IDA / 61630 Post Direct Selection Direct 119,048.00 113,309.60 Signed 2021-08-05 2021-07-26 2021-08-15 2021-08-08 2021-10-19 2022-02-21 2022-04-17 ivery Maintenance of existing MIS of DSS SD-16 / Monitoring & Evaluat Modernization of Service Del Individual Consult IDA / 61630 Post Open - National 118,000.00 0.00 Under Review 2023-06-12 2023-06-18 2023-07-15 2023-08-05 2023-09-02 2025-03-31 ion Specialist ivery ant Selection Modernization of Service Del Individual Consult SD--15 / Training Specialist IDA / 61630 Post Open - National 118,000.00 0.00 Under Review 2023-06-11 2023-06-18 2023-07-23 2023-08-13 2023-09-10 2025-03-31 ivery ant Selection Page 3 NATIONAL URBAN WATER SUPPLY PROJECT (NUWSP) LOAN No. IBRD Ln.8872-ID Procurement Plan Version No.: 1 Date: 14 December, 2018 I. General Information 1. Project information: a. Country: Indonesia b. Recipient: Republic of Indonesia c. Project Name: National Urban Water Supply Project (NUWSP) d. Project Implementing Agency (PIA): (i) Directorate General of Human Settlements, Ministry Public Works and Housing (MPWH) 2. Bank’s No Objection Date of the Procurement Plan: a. Original : April, 2018 3. Date of General Procurement Notice: 08 September 2018 4. Period covered by this procurement plan: Effectiveness – Loan Closing August 2018 – December 2022 II. Types of Contract, Bank’s Review Requirements and Applied Methods A. Works, Goods and Non-Consulting Services 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Ref. Procureme Bank’s Review Procurement Method No. nt Method Requirement 1. International Competitive ≥ $25 million Threshold Each contract shall Bidding (Works) be subject to Bank’s prior review. 2. National Competitive $200k - $25 Each contract ≥ $5 Bidding (Works) million million equivalent shall be subject to Bank’s prior review. All other contracts subject to post review. 3. Shopping for Works < $200k No prior review (only post review). 4. International Competitive ≥$2 million Each contract ≥ Bidding (Goods) $1.5 million equivalent shall be subject to Bank’s prior review. All other contracts 5. National Competitive $100k - $2 subject Each to post contract ≥ Bidding (Goods) million review. $1.5 million equivalent shall be subject to Bank’s prior review. All other contracts 6. Shopping for Goods <100k priorto subject No post review review. (only post review). 7. International Competitive ≥$10 million Each contract shall Bidding (Non-Consultant be subject to Bank’s Service) prior review. 8. National Competitive $100k - $10 Each contract ≥ Bidding (Non-Consultant million $1.5 million Service) equivalent shall be subject to Bank’s prior review. All other contracts 9. Shopping for Non- <$100,000 priorto subject No post review Consulting Service review. (only post review). 10. Direct Contracting N/A Justification shall be provided when submit procurement plan. 1. Pre-qualification: Not applicable. 2. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: As specified in the Project Operations Manual (POM) 3. Reference to (if any) Project Operational/Procurement Manual: Project Operations Manual of NUWSP 4. Any Other Special Procurement Arrangements: -NA- 5. Summary of the Procurement Packages planned during the first 18 months after project effectiveness (including those that are subject to retroactive financing and advanced procurement) 1 2 3 4 5 6 7 Ref. Descripti Estimat Packag Domesti Revie Commen No. on ed es c w ts Cost Prefere by (US$ nce Bank million) (yes/no) (Prior / Post) 1. Summary 9.041 5 No Post of the NCB (Works) B. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to prior review by Bank as stated in Appendix 1 to the Guidelines for Selection and Employment of Consultants: Ref. Selection Selection Method Bank’s Prior Review No. Method Threshold Requirement 1. Competitive ≥$300,000 Each contract ≥ $0.5 Method (Firms) million equivalent shall QCBS, QBS, be subject to Bank’s LCS, FBS prior review. All other contracts subject to post review. 2. Competitive <$300,000 Each contract ≥ $0.5 Methods (Firms) million equivalent shall QCS be subject to Bank’s prior review. All other contracts subject to post review. 3. Individual Competitive Selection by Each contract ≥ $0.2 Consultant comparing at least three million equivalent shall CVs be subject to Bank’s prior review. All other 4. Single Source N/A contracts subject Justification to post shall be (Firms and review. provided when submit Individual) procurement plan. 2. Short list comprising entirely of national consultants: Short list of consultants for services (firms), estimated to cost less than $ 400,000 equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: N/A 4. Summary of Consultancy Assignments with Selection Methods and Time Schedule during the first 18 months after project effectiveness (including those that are subject to retroactive financing and advanced procurement) 1 2 3 4 5 6 7 Ref Descripti Type of Estimat Packag Revie Commen . on of Assignme ed es/Posit w ts No. Assignme nts Cost ions by nts (US$ Bank million) (Prior / Post) 1. Summary (Time- 19.205 11 Prior TMC 4-6, of number Based Evaluation of /Lump- Consultan contracts Sum) t that will be let under QCBS PROCUREMENT Indonesia : National Urban Water Supply Project PLAN General Information Country: Indonesia 2023-06-07 Bank’s Approval Date of the Original Procurement Plan: 2023-06-07 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P156125 GPN Date: 2020-10-07 Project Name: National Urban Water Supply Project Loan / Credit No: IBRD / 88720 Balai Prasarana Permukiman Wilayah Maluku, PUPR Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned National Procure ID-BPPW MALUKU-365263-C Investment Support for Urba ment Document - Single Stage - One E Under Imple 2023-11-2 W-RFB / Optimalisasi SPAM IK IBRD / 88720 n Water Supply Infrastructur Post Request for Bids Open - National 1 Envelope proce 459,225.57 0.00 2023-06-07 2023-06-08 2023-06-12 2023-06-27 2023-07-10 2023-08-01 nvelope mentation 9 K Tehoru Kab. Maluku Tenga e Development ss (Non Bank-SPD h (NUWSP) ) GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 1 PROCUREMENT PLAN (Textual Part) Project information: [Ghana] [Ghana Productive Safety Net Project 2 (GPSNP 2) [P-175588] Project Implementation agency: [Ministry of Gender, Children and Social Protection (MoGCSP) and Ministry of Local Government, Decentralisation and Rural Development (MLGDRD) Date of the Procurement Plan: [26/02/2021] Period covered by this Procurement Plan: [01 July 2021 – 31 December 2022] Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the Public Procurement Act, 2003 (Act 663) which was amended in 2016 by the Public Procurement (Amendment) Act, 2016, (Act 914), such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. 56 (1) Tenders shall be opened (a) at the time specified in the tender documents as the deadline for the submission of tenders or at the deadline specified in any extension of the deadline; and (b) at the place and in accordance with the procedures specified the tender documents. (2) The time for opening of the tenders shall be the same as the deadline for the receipt of the tenders or promptly after that deadline. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. Not Applicable. Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables Not Applicable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: is not applicable for those contracts identified in the Procurement Plan tables Works: is not applicable for those contracts identified in the Procurement Plan tables Other Relevant Procurement Information. Procedures for CDD components: Community Driven Development (CDD) activities are works activities, which are carried out directly by communities. Procurement of Materials Procurement of materials for the activities would be done through the procurement method limited- open. The activities to be carried out: i. Issuance of Request for quotation (at least 3 bidders); ii. Submission and opening of bids for bidders; iii. Evaluation of bids iv. Issuance of Acceptance Letters; v. Signing of Contracts Selection of Community Members Selection of communities to participate in the CDD activities shall be done through direct selection procurement method. Agreement is then signed between the Implementation Agencies (Municipals and District Assemblies) to cover the duration of the activity. PROCUREMENT Ghana : Ghana Productive Safety Net Project 2 PLAN General Information Country: Ghana 2021-03-01 Bank’s Approval Date of the Original Procurement Plan: 2023-06-05 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P175588 GPN Date: Project Name: Ghana Productive Safety Net Project 2 Loan / Credit No: IDA / 68590 MINISTRY OF LOCAL GOVERNMENT AND RURAL DEVELOPMENT - RCU Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GH-MLGRD-RCU-334785-CW Request for Quota -RFQ / Rehabilitation of Abon Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2025-04-2 IDA / 68590 Post Open - National 72,000.00 0.00 2023-03-05 2023-04-30 gokrom -Tiabante - Owusukr Program tions nvelope s (Emergency) SP lementation 9 om Feeder Road (5.50km) D -Competitive Request for Quota GH-MLGRD-RCU-334788-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2025-04-0 -RFQ / Rehabilitation of Yabe IDA / 68590 Post Open - National 70,000.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP lementation 8 neagya - Kwamekuma Feede D -Competitive r Road (3.50km) GH-MLGRD-RCU-334790-CW Request for Quota -RFQ / Rehabilitation of Sunk Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2025-04-0 IDA / 68590 Post Open - National 66,000.00 0.00 2023-03-05 2023-04-09 wa -Tenso-Onwe-Dinkyini Fee Program tions nvelope s (Emergency) SP lementation 8 der Road (5.0km) D -Competitive Request for Quota GH-MLGRD-RCU-334791-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-0 -RFQ / Rehabilitation of Derm IDA / 68590 Post Open - National 33,000.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP mentation 8 a - Monta Feeder Road (2.50 D -Competitive km) GH-MLGRD-RCU-334792-CW Request for Quota -RFQ / Rehabilitation of New Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-0 IDA / 68590 Post Open - National 23,500.00 0.00 2023-03-05 2023-04-09 Bosankro - Akuraadadaa-Man Program tions nvelope s (Emergency) SP mentation 8 hutem Feeder Road (2.0km) D -Competitive Request for Quota GH-MLGRD-RCU-334793-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2025-04-0 -RFQ / Rehabilitation of Drom IDA / 68590 Post Open - National 69,500.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP lementation 8 ankuma -Fakawa Feeder Roa D -Competitive d (4.50km) GH-MLGRD-RCU-334794-CW Request for Quota -RFQ / Rehabilitation of Nkwa Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2025-04-0 IDA / 68590 Post Open - National 48,000.00 0.00 2023-03-05 2023-04-09 nta Farm Jnc.-Hiawoanwu Fe Program tions nvelope s (Emergency) SP lementation 8 eder Road (4.2km) D -Competitive Request for Quota GH-MLGRD-RCU-336045-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2025-04-0 -RFQ / Rehabilitation of Abes IDA / 68590 Post Open - National 44,000.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP lementation 8 ewa-Databi Feeder Road (4.4 D -Competitive km) Request for Quota GH-MLGRD-RCU-336046-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2025-04-0 -RFQ / Rehabilitation of Bons IDA / 68590 Post Open - National 54,300.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP lementation 8 ukrom Jnc.-Adense Feeder Ro D -Competitive ad (5.0km) Request for Quota GH-MLGRD-RCU-336047-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-0 -RFQ / Rehabilitation of Srent IDA / 68590 Post Open - National 36,200.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP mentation 8 iantia-Abrofoa Feeder Road ( D -Competitive 2.50km) GH-MLGRD-RCU-336049-CW Request for Quota -RFQ / Rehabilitation of Yebo Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-0 IDA / 68590 Post Open - National 67,500.00 0.00 2023-03-05 2023-04-09 ah Apatam - Nsuguasua Feed Program tions nvelope s (Emergency) SP mentation 8 er Road (5.70km) D -Competitive GH-MLGRD-RCU-336050-CW Request for Quota -RFQ / Rehabilitation of Ayaa Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2025-04-0 IDA / 68590 Post Open - National 60,000.00 0.00 2023-03-05 2023-04-09 kwa Junction-Bebeduaso Fee Program tions nvelope s (Emergency) SP lementation 8 der Road(4.50km) D -Competitive GH-MLGRD-RCU-336051-CW Request for Quota -RFQ / Rehabilitation of Mang Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-0 IDA / 68590 Post Open - National 51,000.00 0.00 2023-03-05 2023-04-09 oase Jnc -Akyease - Mpentua Program tions nvelope s (Emergency) SP mentation 8 se Feeder Road (4.0km) D -Competitive GH-MLGRD-RCU-336052-CW Request for Quota -RFQ / Rehabilitation of Hani- Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-0 IDA / 68590 Post Open - National 64,400.00 0.00 2023-03-05 2023-04-09 Proposed Tourist Site (Gbeho Program tions nvelope s (Emergency) SP mentation 8 ) Feeder Road (3.50km) D -Competitive Request for Quota GH-MLGRD-RCU-336053-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2025-04-0 -RFQ / Rehabilitation of Mire IDA / 68590 Post Open - National 83,800.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP lementation 8 mano -Berekumkroaso Feede D -Competitive r Road (5.50km) GH-MLGRD-RCU-336054-CW Request for Quota -RFQ / Rehabilitation of Nwoa Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-0 IDA / 68590 Post Open - National 69,000.00 0.00 2023-03-05 2023-04-09 se - Seiduakuraa - Aboabo Fe Program tions nvelope s (Emergency) SP mentation 8 eder Road (4.80km) D -Competitive Request for Quota GH-MLGRD-RCU-336055-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-0 -RFQ / Rehabilitation of Sikaa IDA / 68590 Post Open - National 58,300.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP mentation 8 -Wansamkuraa Feeder Road D -Competitive (5.0km) Request for Quota GH-MLGRD-RCU-336330-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2025-04-0 -RFQ / Rehabilitation of Akru IDA / 68590 Post Open - National 56,500.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP lementation 8 ma - Bobrobo Feeder Road (3 D -Competitive .80km) Request for Quota GH-MLGRD-RCU-336331-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2025-04-0 -RFQ / Rehabilitation Of Kobe IDA / 68590 Post Open - National 80,500.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP lementation 8 da No. 1 - Kobeda No. 2 Feed D -Competitive er Road (5.80km) Request for Quota GH-MLGRD-RCU-336336-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2025-04-0 -RFQ / Rehabilitation of Bami IDA / 68590 Post Open - National 70,300.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP lementation 8 ra - Asantanso Feeder Road ( D -Competitive 5.70km) Request for Quota GH-MLGRD-RCU-336341-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-0 -RFQ / Rehabilitation of Tawia IDA / 68590 Post Open - National 53,000.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP mentation 8 kwaa-Annan Feeder Road (3. D -Competitive 1km) Page 1 Request for Quota GH-MLGRD-RCU-336342-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-0 -RFQ / Rehabilitation of Enyis IDA / 68590 Post Open - National 60,000.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP mentation 8 am - Takyiman Feeder Road ( D -Competitive 3.5km) Request for Quota GH-MLGRD-RCU-336343-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-0 -RFQ / Rehabilitation of Yaw IDA / 68590 Post Open - National 66,000.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP mentation 8 Duodo-Kobiso Feeder Road ( D -Competitive 3.9km) Request for Quota GH-MLGRD-RCU-336344-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-0 -RFQ / Rehabilitation of Kwab IDA / 68590 Post Open - National 51,100.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP mentation 8 oadi No.2-Aboso Jnc. Feeder D -Competitive Road (4.7km) GH-MLGRD-RCU-336345-CW Request for Quota -RFQ / Rehabilitation of Sema Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-0 IDA / 68590 Post Open - National 75,000.00 0.00 2023-03-05 2023-04-09 nhyia-Kyeame Kissi-Kyemfre Program tions nvelope s (Emergency) SP mentation 8 Feeder Road (10.60km) D -Competitive GH-MLGRD-RCU-336346-CW Request for Quota -RFQ / Rehabilitation of Mota Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-0 IDA / 68590 Post Open - National 46,000.00 0.00 2023-03-05 2023-04-09 Afarikrom-Nkwaakwaasem F Program tions nvelope s (Emergency) SP mentation 8 eeder Road (2.4km) D -Competitive Request for Quota GH-MLGRD-RCU-336347-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-0 -RFQ / Rehabilitation of Agog IDA / 68590 Post Open - National 62,000.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP mentation 8 o-Okyerekrom Feeder Road ( D -Competitive 3.1km) Request for Quota GH-MLGRD-RCU-336348-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-0 -RFQ / Rehabilitation of Akrus IDA / 68590 Post Open - National 66,000.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP mentation 8 u Jnc.-Asekeso Feeder Road ( D -Competitive 3.64km) Request for Quota GH-MLGRD-RCU-336349-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-0 -RFQ / Rehabilitation of Wate IDA / 68590 Post Open - National 29,500.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP mentation 8 r Works Jnc.-Muerter Feeder D -Competitive Road (1.5km) Request for Quota GH-MLGRD-RCU-336350-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-0 -RFQ / Rehabilitation of Dave IDA / 68590 Post Open - National 41,200.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP mentation 8 -Gbleve Feeder Road (2.0km) D -Competitive Request for Quota GH-MLGRD-RCU-336352-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-0 -RFQ / Rehabilitation of Adze IDA / 68590 Post Open - National 66,400.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP mentation 8 kofe Jnc.-Adzekofe Feeder Ro D -Competitive ad (3.95km) Request for Quota GH-MLGRD-RCU-336354-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-0 -RFQ / Rehabilitation of Tsrib IDA / 68590 Post Open - National 62,400.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP mentation 8 ormi-Kesenyemito Feeder Ro D -Competitive ad (4.2km) Request for Quota GH-MLGRD-RCU-336355-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-0 -RFQ / Rehabilitation Of Kped IDA / 68590 Post Open - National 44,500.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP mentation 8 ze Tordze-Anagokope Feeder D -Competitive Road (1.8km) Request for Quota GH-MLGRD-RCU-336356-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-0 -RFQ / Rehabilitation of Duku IDA / 68590 Post Open - National 77,000.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP mentation 8 ma Tsrukpe-Zanukope Feede D -Competitive r Road (4.6km) Request for Quota GH-MLGRD-RCU-336549-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2023-10-2 -RFQ / Rehabilitation of Small IDA / 68590 Post Open - National 86,000.00 0.00 2023-03-05 2023-04-30 Program tions nvelope s (Emergency) SP mentation 7 Earth Dam at Adaklu Torda D -Competitive GH-MLGRD-RCU-336551-CW Request for Quota -RFQ / Rehabilitation of Korsi Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-0 IDA / 68590 Post Open - National 36,000.00 0.00 2023-03-05 2023-04-09 ve Jnc.-Cashew Plantation Sit Program tions nvelope s (Emergency) SP mentation 8 e Feeder Road (2.0km) D -Competitive Request for Quota GH-MLGRD-RCU-336555-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-0 -RFQ / Rehabilitation of Ladu IDA / 68590 Post Open - National 60,500.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP mentation 8 mdo-Nalogni-Tindando Feede D -Competitive r Road 5.00km Request for Quota GH-MLGRD-RCU-336557-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2023-10-2 -RFQ / Construction of Paralle IDA / 68590 Post Open - National 50,000.00 0.00 2023-03-05 2023-04-30 Program tions nvelope s (Emergency) SP mentation 7 l Drain at Wulensi Dam D -Competitive Request for Quota GH-MLGRD-RCU-336559-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-0 -RFQ / Rehabilitation of Mpah IDA / 68590 Post Open - National 27,500.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP mentation 8 a-Chukonto Feeder Road (2.0 D -Competitive 0 km) Request for Quota GH-MLGRD-RCU-336561-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-0 -RFQ / Rehabilitation of Naku IDA / 68590 Post Open - National 81,500.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP mentation 8 nga Jnt - Nakunga Feeder Ro D -Competitive ad (5.0km) Request for Quota GH-MLGRD-RCU-336562-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2025-04-0 -RFQ / Rehabilitation of Gbanl IDA / 68590 Post Open - National 84,000.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP lementation 8 ua - Ditani Feeder Road (6.5k D -Competitive m) Request for Quota GH-MLGRD-RCU-336564-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2025-04-2 -RFQ / Rehabilitation of Small IDA / 68590 Post Open - National 91,000.00 0.00 2023-03-05 2023-04-30 Program tions nvelope s (Emergency) SP lementation 9 Earth Dam at Kumoayili D -Competitive Request for Quota GH-MLGRD-RCU-336566-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2025-04-0 -RFQ / Rehabilitation of Bagli IDA / 68590 Post Open - National 51,500.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP lementation 8 - Bagkurli Feeder Road (3.5k D -Competitive m) Request for Quota GH-MLGRD-RCU-336567-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-0 -RFQ / Rehabilitation of Nant IDA / 68590 Post Open - National 76,700.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP mentation 8 on - Yapalsi Feeder Road (4. D -Competitive 8km) Request for Quota GH-MLGRD-RCU-336569-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2025-04-0 -RFQ / Rehabilitation of Nach IDA / 68590 Post Open - National 78,000.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP lementation 8 amba No. 2 - Tatale Feeder D -Competitive Road (5.2km) Request for Quota GH-MLGRD-RCU-336570-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-2 -RFQ / Rehabilitation of Small IDA / 68590 Post Open - National 55,000.00 0.00 2023-03-05 2023-04-30 Program tions nvelope s (Emergency) SP mentation 9 Earth Dam at Nanton Kurugu D -Competitive Request for Quota GH-MLGRD-RCU-336581-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2025-04-0 -RFQ / Rehabilitation of Gork IDA / 68590 Post Open - National 61,000.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP lementation 8 ugani- Natindo Feeder Road ( D -Competitive 5.0km) Page 2 Request for Quota GH-MLGRD-RCU-336584-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2025-04-2 -RFQ / Rehabilitation of Small IDA / 68590 Post Open - National 92,000.00 0.00 2023-03-05 2023-04-30 Program tions nvelope s (Emergency) SP lementation 9 Earth Dam at Kuyuli D -Competitive Request for Quota GH-MLGRD-RCU-336585-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2025-04-2 -RFQ / Rehabilitation of Small IDA / 68590 Post Open - National 86,000.00 0.00 2023-03-05 2023-04-30 Program tions nvelope s (Emergency) SP lementation 9 Earth Dam At Kpalgigbeni D -Competitive Request for Quota GH-MLGRD-RCU-336588-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2025-04-2 -RFQ / Rehabilitation of Small IDA / 68590 Post Open - National 91,000.00 0.00 2023-03-05 2023-04-30 Program tions nvelope s (Emergency) SP lementation 9 Earth Dam at Kuyuli D -Competitive Request for Quota GH-MLGRD-RCU-336589-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-2 -RFQ / Rehabilitation of Small IDA / 68590 Post Open - National 55,000.00 0.00 2023-03-05 2023-04-30 Program tions nvelope s (Emergency) SP mentation 9 Earth Dam at Nanton Kurugu D -Competitive Request for Quota GH-MLGRD-RCU-336590-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-2 -RFQ / Rehabilitation of Small IDA / 68590 Post Open - National 91,000.00 0.00 2023-03-05 2023-04-30 Program tions nvelope s (Emergency) SP mentation 9 Earth Dam at Buegmal D -Competitive Request for Quota GH-MLGRD-RCU-336591-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-0 -RFQ / Rehabilitation of Dika- IDA / 68590 Post Open - National 60,000.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP mentation 8 Ahamansu Feeder Roads (4.0 D -Competitive km) Ph2 Request for Quota GH-MLGRD-RCU-336592-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-0 -RFQ / Rehabilitation of Kachi IDA / 68590 Post Open - National 44,000.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP mentation 8 nke-Lugnuldo Feeder Road 2. D -Competitive 60 Km GH-MLGRD-RCU-336593-CW Request for Quota -RFQ / Rehabilitation of Pechi Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-0 IDA / 68590 Post Open - National 65,000.00 0.00 2023-03-05 2023-04-09 Akura Jnt. - Ahiamankyene F Program tions nvelope s (Emergency) SP mentation 8 eeder Road (5.0km D -Competitive Request for Quota GH-MLGRD-RCU-336594-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-0 -RFQ / Rehabilitation of Tsafo IDA / 68590 Post Open - National 71,000.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP mentation 8 kura Jnc. - Tsafokura Feeder D -Competitive Road (5.0km) Request for Quota GH-MLGRD-RCU-336595-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-0 -RFQ / Rehabilitation of Grubi IDA / 68590 Post Open - National 58,000.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP mentation 8 - Akaniem Feeder Road (4.0 D -Competitive km) GH-MLGRD-RCU-336596-CW Request for Quota -RFQ / Rehabilitation of Mam Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-0 IDA / 68590 Post Open - National 49,000.00 0.00 2023-03-05 2023-04-09 a Kura- Hundokope Feeder R Program tions nvelope s (Emergency) SP mentation 8 oad(3.0km) Phase 2 D -Competitive Request for Quota GH-MLGRD-RCU-336597-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-0 -RFQ / Rehabilitation of Kito- IDA / 68590 Post Open - National 48,000.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP mentation 8 Kito Nkwanta Feeder Road 4. D -Competitive 6km Request for Quota GH-MLGRD-RCU-336598-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2025-04-0 -RFQ / Rehabilitation of Fuu. - IDA / 68590 Post Open - National 83,000.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP lementation 8 Takpli Feeder Road (6.7km) D -Competitive Request for Quota GH-MLGRD-RCU-336600-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-0 -RFQ / Rehabilitation of Bonb IDA / 68590 Post Open - National 29,000.00 0.00 2023-03-05 2023-03-14 2023-04-09 Program tions nvelope s (Emergency) SP mentation 8 ontey Jnc - Bonbontey Feeder D -Competitive (1.50km) Request for Quota GH-MLGRD-RCU-336601-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-0 -RFQ / Rehabilitation of Noko IDA / 68590 Post Open - National 48,500.00 0.00 2023-03-05 2023-03-15 2023-04-09 Program tions nvelope s (Emergency) SP mentation 8 yiri - Samariyiri Feeder Road D -Competitive (2.50km) Request for Quota GH-MLGRD-RCU-336602-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-0 -RFQ / Rehabilitation Of Mank IDA / 68590 Post Open - National 78,000.00 0.00 2023-03-05 2023-03-16 2023-04-09 Program tions nvelope s (Emergency) SP mentation 8 arigu-Sakpala-Kpatarigu Fee D -Competitive der Road (4.5km) Request for Quota GH-MLGRD-RCU-336604-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-2 -RFQ / Rehabilitation of Kagb IDA / 68590 Post Open - National 85,000.00 0.00 2023-03-05 2023-03-16 2023-04-30 Program tions nvelope s (Emergency) SP mentation 9 al Small Earth Dam D -Competitive Request for Quota GH-MLGRD-RCU-336616-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-0 -RFQ / Rehabilitation of Moyir IDA / 68590 Post Open - National 77,800.00 0.00 2023-03-05 2023-03-15 2023-04-09 Program tions nvelope s (Emergency) SP mentation 8 i - Konzokala Feeder Road (4. D -Competitive 5km) Request for Quota GH-MLGRD-RCU-336636-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-0 -RFQ / Rehabilitation of Kont IDA / 68590 Post Open - National 77,400.00 0.00 2023-03-05 2023-03-16 2023-04-09 Program tions nvelope s (Emergency) SP mentation 8 wiri - Chachaa Feeder Road ( D -Competitive 3.5km) Request for Quota GH-MLGRD-RCU-336637-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-0 -RFQ / Rehabilitation of Kohu IDA / 68590 Post Open - National 77,800.00 0.00 2023-03-05 2023-03-16 2023-04-09 Program tions nvelope s (Emergency) SP mentation 8 o - Pina Feeder Road (4.7km) D -Competitive Request for Quota GH-MLGRD-RCU-336640-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-2 -RFQ / Rehabilitation of Small IDA / 68590 Post Open - National 85,000.00 0.00 2023-03-05 2023-03-16 2023-04-30 Program tions nvelope s (Emergency) SP mentation 9 Earth Dam at Boo D -Competitive Request for Quota GH-MLGRD-RCU-336641-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-0 -RFQ / Rehabilitation of Furo - IDA / 68590 Post Open - National 42,100.00 0.00 2023-03-05 2023-03-16 2023-04-09 Program tions nvelope s (Emergency) SP mentation 8 Gbier Feeder Road (2.5km) D -Competitive Request for Quota GH-MLGRD-RCU-336644-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-0 -RFQ / Rehabilitation of Goli - IDA / 68590 Post Open - National 64,000.00 0.00 2023-03-05 2023-03-16 2023-04-09 Program tions nvelope s (Emergency) SP mentation 8 Kaabogu Feeder Road (3.35k D -Competitive m) Request for Quota GH-MLGRD-RCU-336648-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-0 -RFQ / Rehabilitation of Domi IDA / 68590 Post Open - National 36,000.00 0.00 2023-03-05 2023-03-16 2023-04-09 Program tions nvelope s (Emergency) SP mentation 8 ngye - Nabugangn Feeder Ro D -Competitive ad (2.2km) Request for Quota GH-MLGRD-RCU-336649-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-0 -RFQ / Rehabilitation of Guo IDA / 68590 Post Open - National 43,400.00 0.00 2023-03-05 2023-03-16 2023-04-09 Program tions nvelope s (Emergency) SP mentation 8 mwaane - Hayore Feeder Ro D -Competitive ad (2.5km) Request for Quota GH-MLGRD-RCU-336652-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-0 -RFQ / Rehabilitation of Puze IDA / 68590 Post Open - National 78,000.00 0.00 2023-03-05 2023-03-16 2023-04-09 Program tions nvelope s (Emergency) SP mentation 8 ne-Boo Feeder Road (6.6km) D -Competitive Page 3 Request for Quota GH-MLGRD-RCU-336656-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-0 -RFQ / Rehabilitation of Dorn IDA / 68590 Post Open - National 98,000.00 0.00 2023-03-05 2023-03-16 2023-04-09 Program tions nvelope s (Emergency) SP mentation 8 ye - Dorkyire Feeder Road (5. D -Competitive 0km) Request for Quota GH-MLGRD-RCU-337227-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2025-04-0 -RFQ / Rehabilitation of Wiidi- IDA / 68590 Post Open - National 76,900.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP lementation 8 Kukanga-Buzunde Feeder Ro D -Competitive ad (5.8km) Request for Quota GH-MLGRD-RCU-337229-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2025-04-0 -RFQ / Rehabilitation of Gund IDA / 68590 Post Open - National 76,200.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP lementation 8 ago- Gbango-Kansogo Feeder D -Competitive Road (5.0km) Request for Quota GH-MLGRD-RCU-337232-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2025-04-0 -RFQ / Rehabilitation of Samb IDA / 68590 Post Open - National 80,000.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP lementation 8 oliga-Agatuse Feeder Road (3 D -Competitive .7km) Request for Quota GH-MLGRD-RCU-337234-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2025-04-0 -RFQ / Rehabilitation of Nayo IDA / 68590 Post Open - National 75,000.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP lementation 8 ko No. 2 - Gore Clinic Feeder D -Competitive Road (5.5km) Request for Quota GH-MLGRD-RCU-337235-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2025-04-0 -RFQ / Rehabilitation of Aniisi IDA / 68590 Post Open - National 58,500.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP lementation 8 - Belimpiisi Feeder Road (3.5 D -Competitive km) Request for Quota GH-MLGRD-RCU-337236-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2025-04-0 -RFQ / Rehabilitation of Sana IDA / 68590 Post Open - National 87,300.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP lementation 8 biisi -Kabre - Akulyor Feeder D -Competitive Road (5.0km) GH-MLGRD-RCU-337237-CW Request for Quota -RFQ / Rehabilitation of Akuy Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2025-04-0 IDA / 68590 Post Open - National 86,000.00 0.00 2023-03-05 2023-04-09 elingo - Tingre -Wegurigo Fee Program tions nvelope s (Emergency) SP lementation 8 der Road (5.0km) D -Competitive Request for Quota GH-MLGRD-RCU-337238-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2025-04-0 -RFQ / Rehabilitation of Donin IDA / 68590 Post Open - National 68,300.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP lementation 8 ga - Banyangsa Feeder Road D -Competitive (4.0km) Request for Quota GH-MLGRD-RCU-337239-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2025-04-0 -RFQ / Rehabilitation of Gban IDA / 68590 Post Open - National 84,300.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP lementation 8 koni - Nanjong No. 2 Feeder D -Competitive Road (6.9km) Request for Quota GH-MLGRD-RCU-337240-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2025-04-0 -RFQ / Rehabilitation of Natur IDA / 68590 Post Open - National 77,000.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP lementation 8 i -Tichangu Feeder Road (5.0 D -Competitive km) Request for Quota GH-MLGRD-RCU-337242-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2025-04-0 -RFQ / Rehabilitation of Natur IDA / 68590 Post Open - National 65,000.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP lementation 8 i Junc- Naturi Feeder Road (3. D -Competitive 4km) Request for Quota GH-MLGRD-RCU-337243-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2025-04-0 -RFQ / Rehabilitation of Gam IDA / 68590 Post Open - National 84,000.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP lementation 8 baga - Zimasa Feeder Road ( D -Competitive 5.0km) Request for Quota GH-MLGRD-RCU-337244-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2025-04-0 -RFQ / Rehabilitation of Song IDA / 68590 Post Open - National 81,000.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP lementation 8 o-Songure Feeder Road (5.0k D -Competitive m) Request for Quota GH-MLGRD-RCU-337246-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2025-04-0 -RFQ / Rehabilitation of Farfa IDA / 68590 Post Open - National 83,000.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP lementation 8 r- Walkman Feeder Road (5.0 D -Competitive km) Request for Quota GH-MLGRD-RCU-337247-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2025-04-0 -RFQ / Rehabilitation of Jade IDA / 68590 Post Open - National 86,000.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP lementation 8 ma-Buyinga Feeder Road (5. D -Competitive 4km) Request for Quota GH-MLGRD-RCU-337249-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2025-04-0 -RFQ / Rehabilitation of Kulsa IDA / 68590 Post Open - National 51,000.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP lementation 8 lboug - Zanlerigu Feeder Ro D -Competitive ad (2.1 Km) GH-MLGRD-RCU-337250-CW Request for Quota -RFQ / Rehabilitation of Zopel Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2025-04-0 IDA / 68590 Post Open - National 71,000.00 0.00 2023-03-05 2023-04-09 iga - Dagliga Basic School Fe Program tions nvelope s (Emergency) SP lementation 8 eder Road (4.0km) D -Competitive Request for Quota GH-MLGRD-RCU-337251-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2025-04-0 -RFQ / Rehabilitation of Ajeng IDA / 68590 Post Open - National 71,300.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP lementation 8 o Natinga- Tesnatinga Feede D -Competitive r Road (4.3km) Request for Quota GH-MLGRD-RCU-337252-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2025-04-0 -RFQ / Rehabilitation of Pwal IDA / 68590 Post Open - National 58,000.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP lementation 8 ugu-Manpelugu Feeder Road D -Competitive (3.5km) Request for Quota GH-MLGRD-RCU-337253-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2025-04-0 -RFQ / Rehabilitation of Wink IDA / 68590 Post Open - National 66,000.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP lementation 8 ongo-Dapore Feeder Road (4. D -Competitive 0km) Request for Quota GH-MLGRD-RCU-337254-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2025-04-0 -RFQ / Rehabilitation of Imigr IDA / 68590 Post Open - National 79,100.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP lementation 8 ation Junc- Tafakwan Feeder D -Competitive Road (5.0km) Request for Quota GH-MLGRD-RCU-337256-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-2 -RFQ / Completion of Small E IDA / 68590 Post Open - National 24,000.00 0.00 2023-03-05 2023-04-30 Program tions nvelope s (Emergency) SP mentation 9 arth Dam at Nayorku D -Competitive Request for Quota GH-MLGRD-RCU-337257-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2025-04-2 -RFQ / Completion of Small E IDA / 68590 Post Open - National 79,000.00 0.00 2023-03-05 2023-04-30 Program tions nvelope s (Emergency) SP lementation 9 arth Dam at Agargo D -Competitive Request for Quota GH-MLGRD-RCU-337258-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2025-04-2 -RFQ / Completion of Small E IDA / 68590 Post Open - National 22,000.00 0.00 2023-03-05 2023-04-30 Program tions nvelope s (Emergency) SP lementation 9 arth Dam at Mangor D -Competitive Request for Quota GH-MLGRD-RCU-337260-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-2 -RFQ / Completion of Small E IDA / 68590 Post Open - National 68,500.00 0.00 2023-03-05 2023-04-30 Program tions nvelope s (Emergency) SP mentation 9 arth Dam at Namongo D -Competitive Page 4 Request for Quota GH-MLGRD-RCU-336599-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2024-12-3 -RFQ / Rehabilitation of Small IDA / 68590 Post Open - National 127,000.00 0.00 2023-03-05 2023-03-15 2023-04-30 Program tions nvelope s (Emergency) SP mentation 1 Earth Dam at Sornyo D -Competitive Request for Quota GH-MLGRD-RCU-336619-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2024-12-3 -RFQ / Rehabilitation of Small IDA / 68590 Post Open - National 137,000.00 0.00 2023-03-05 2023-03-16 2023-04-30 Program tions nvelope s (Emergency) SP mentation 1 Earth Dam at Dapuoha D -Competitive Request for Quota GH-MLGRD-RCU-337262-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2024-12-3 -RFQ / Rehabilitation of Small IDA / 68590 Post Open - National 111,000.00 0.00 2023-03-05 2023-04-30 Program tions nvelope s (Emergency) SP mentation 1 Earth Dam at Dagubaa D -Competitive Request for Quota GH-MLGRD-RCU-337261-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2024-12-3 -RFQ / Rehabilitation of Small IDA / 68590 Post Open - National 170,000.00 0.00 2023-03-05 2023-03-16 2023-04-30 Program tions nvelope s (Emergency) SP mentation 1 Earth Dam at Dagbigu D -Competitive Request for Quota GH-MLGRD-RCU-336651-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2024-12-3 -RFQ / Rehabilitation of Small IDA / 68590 Post Open - National 111,400.00 0.00 2023-03-05 2023-03-16 2023-04-30 Program tions nvelope s (Emergency) SP mentation 1 Earth Dam at Bakwalla D -Competitive Request for Quota GH-MLGRD-RCU-336617-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2024-12-3 -RFQ / Rehabilitation of Small IDA / 68590 Post Open - National 170,800.00 0.00 2023-03-05 2023-03-16 2023-04-30 Program tions nvelope s (Emergency) SP mentation 1 Earth Dam at Nakpala D -Competitive Request for Quota GH-MLGRD-RCU-336642-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2024-12-3 -RFQ / Rehabilitation of Small IDA / 68590 Post Open - National 102,000.00 0.00 2023-03-05 2023-03-16 2023-04-30 Program tions nvelope s (Emergency) SP mentation 1 Earth Dam at Gbankor D -Competitive Request for Quota GH-MLGRD-RCU-336657-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2024-12-3 -RFQ / Rehabilitation of Small IDA / 68590 Post Open - National 128,000.00 0.00 2023-03-05 2023-03-16 2023-04-30 Program tions nvelope s (Emergency) SP mentation 1 Earth Dam at Janbob D -Competitive Request for Quota GH-MLGRD-RCU-336639-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2024-12-3 -RFQ / Rehabilitation of Small IDA / 68590 Post Open - National 176,500.00 0.00 2023-03-05 2023-04-30 Program tions nvelope s (Emergency) SP lementation 1 Earth Dam at Hachagagan D -Competitive Request for Quota GH-MLGRD-RCU-336618-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2024-12-3 -RFQ / Rehabilitation Of Smal IDA / 68590 Post Open - National 132,600.00 0.00 2023-03-05 2023-03-15 2023-04-30 Program tions nvelope s (Emergency) SP mentation 1 l Earth Dam at Saapari D -Competitive Request for Quota GH-MLGRD-RCU-336653-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2024-12-3 -RFQ / Rehabilitation of Small IDA / 68590 Post Open - National 174,000.00 0.00 2023-03-05 2023-03-16 2023-04-30 Program tions nvelope s (Emergency) SP mentation 1 Earth Dam at Nyentie D -Competitive Request for Quota GH-MLGRD-RCU-336654-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2024-12-3 -RFQ / Rehabilitation of Small IDA / 68590 Post Open - National 148,000.00 0.00 2023-03-05 2023-03-16 2023-04-30 Program tions nvelope s (Emergency) SP mentation 1 Earth Dam at Sogla D -Competitive GH-MLGRD-RCU-334786-CW Request for Quota -RFQ / Rehabilitation of Amo Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2024-12-3 IDA / 68590 Post Open - National 64,000.00 0.00 2023-03-05 2023-04-30 maso -Ninkyeama - Sentaso Program tions nvelope s (Emergency) SP lementation 1 Feeder Road (5.20km) D -Competitive Request for Quota GH-MLGRD-RCU-336334-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2024-12-3 -RFQ / Rehabilitation of Kofi IDA / 68590 Post Open - National 92,000.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP mentation 1 Djankrom - Kakraka Feeder R D -Competitive oad(6.30km) GH-MLGRD-RCU-337255-CW Request for Quota -RFQ / Rehabilitation of Bimb Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2025-01-3 IDA / 68590 Post Open - National 83,400.00 0.00 2023-04-05 2023-05-10 ago-Gbingbalanchet Phase 1 Program tions nvelope s (Emergency) SP lementation 1 Feeder Road (5.0km) D -Competitive Request for Quota GH-MLGRD-RCU-341117-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-02-1 -RFQ / Rehabilitation of Nako IDA / 68590 Post Open - National 113,500.00 0.00 2023-04-05 2023-05-31 Program tions nvelope s (Emergency) SP mentation 1 re - Kpongu Feeder Road (5.0 D -Competitive km) Request for Quota GH-MLGRD-RCU-341120-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-02-1 -RFQ / Rehabilitation of Small IDA / 68590 Post Open - National 132,000.00 0.00 2023-04-05 2023-05-31 Program tions nvelope s (Emergency) SP mentation 1 Earth Dam at Bokpieriyiri D -Competitive GH-MLGRD-RCU-365594-CW -RFQ / Construction of On-sit e Creches and Temporary Toi lets for CCMI Nurseries and Pl Request for Quota Labor-Intensive Public Works Request for Quota Single Stage - One E Pending Imp 2024-02-2 antations for Builsa South, B IDA / 68590 Post Open - National tions (Non Bank-S 32,000.00 0.00 2023-07-02 2023-08-27 Program tions nvelope lementation 3 uilsa North Municipal, Bongo, PD) Talensi, Nabdam, Bawku Wes t , Binduri, Bawku Municipal, Pusiga, Tempane and Garu Districts by the UERCC GH-MLGRD-RCU-365602-CW -RFQ / Construction of Fencin g for CCMI Nurseries and Pla Request for Quota ntations sites (119.3 Ha) for Labor-Intensive Public Works Request for Quota Single Stage - One E Pending Imp 2024-02-2 IDA / 68590 Post Open - National tions (Non Bank-S 131,664.00 0.00 2023-07-02 2023-08-27 Builsa South, Builsa North Mu Program tions nvelope lementation 3 PD) nicipal, Bongo, Talensi, Nabd am, Bawku West ,Binduri, Ba wku Municipal, Pusiga, Temp ane and Garu Districts by th e UERCC. GH-MLGRD-RCU-365610-CW -RFQ / Construction of Boreh oles for CCMI Nurseries and P lantations for Builsa South, B Request for Quota Labor-Intensive Public Works Request for Quota Single Stage - One E Pending Imp 2024-02-2 uilsa North Municipal, Bongo, IDA / 68590 Post Open - National tions (Non Bank-S 50,909.00 0.00 2023-07-02 2023-08-27 Program tions nvelope lementation 3 Talensi, Nabdam, Bawku Wes PD) t, Bawku Municipal, Binduri, Garu, Pusiga, Tempane, Bunk prugu, East mamprusi, and o ther Districts in UERCC. GH-MLGRD-RCU-365627-CW -RFQ / Construction of On-sit e Creches & Temporary Toile Request for Quota ts for CCMI Nurseries and Pla Labor-Intensive Public Works Request for Quota Single Stage - One E Pending Imp 2024-02-2 IDA / 68590 Post Open - National tions (Non Bank-S 12,273.00 0.00 2023-07-02 2023-08-27 ntations for Mamprugu Moag Program tions nvelope lementation 3 PD) duri, East Mamprusi Municipa l, Bunkpurugu-Nakpanduri an d Yunyoo-Nasuan Districts by the NERCC Page 5 GH-MLGRD-RCU-365630-CW -RFQ / Construction of Fence for CCMI Nurseries and Plant Request for Quota Labor-Intensive Public Works Request for Quota Single Stage - One E Pending Imp 2024-02-2 ations for Mamprugu Moagdu IDA / 68590 Post Open - National tions (Non Bank-S 4,727.00 0.00 2023-07-02 2023-08-27 Program tions nvelope lementation 3 ri, East Mamprusi Municipal, PD) Bunkpurugu - Nakpanduri an d Yunyoo-Nasuan Districts by the NERCC GH-MLGRD-RCU-364275-GO- RFQ / Supply of materials for Request for Quota concrete works for the rehabi Labor-Intensive Public Works Request for Quota Single Stage - One E Pending Imp 2024-01-2 IDA / 68590 Post Open - National tions (Non Bank-S 17,497.00 0.00 2023-06-25 2023-08-01 litation of 10ha degraded co Program tions nvelope lementation 8 PD) mmunal land and developme nt of watershed, facility at Ns esresu - concrete works GH-MLGRD-RCU-365584-CW Request for Quota -RFQ / Construction of 3 No. Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2024-02-2 Ancillary structures (On - site IDA / 68590 Post Open - National 4,910.00 0.00 2023-07-02 2023-08-27 Program tions nvelope s (Emergency) SP lementation 3 Creche and Temporary toilet) D -Competitive at Liati Soba and Ve Deme in Afadzato District GH-MLGRD-RCU-367456-CW -RFQ / Construction of on-site Request for Quota Creches and Temporary Toile Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2024-02-2 t for Kpandai, Gushegu, Nanu IDA / 68590 Post Open - National 29,444.00 0.00 2023-07-01 2023-08-26 Program tions nvelope s (Emergency) SP lementation 2 mba South, Saboba Tatale - D -Competitive Sanguli, Zabzugu, Karaga, Mi on and Nanton District Asse mblies. GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GH-MLGRD-RCU-220729-GO- RFB / Procurement of 500 No Productive Inclusion Progra Single Stage - One E IDA / 68590 Post Request for Bids Open - National 300,000.00 0.00 Signed 2022-07-22 2022-07-08 2022-07-27 2022-07-23 2022-09-07 2022-08-16 2022-10-17 2022-08-12 2022-11-21 2023-02-19 . tablets with Biometric Scan m nvelope ners for LIPW and PI Activitie s GH-MLGRD-RCU-286190-GO- RFB / Supply and Delivery of Labor-Intensive Public Works Single Stage - One E 294 All-Terrain Motorbikes fo IDA / 68590 Post Request for Bids Open - National 420,000.00 0.00 Completed 2022-07-22 2022-07-08 2022-07-27 2022-07-23 2022-09-07 2022-08-16 2022-10-21 2022-08-12 2022-11-25 2023-03-25 Program nvelope r Labour Intensive Public Wor ks (LIPW) and Productive Incl usion (PI) Monitoring Activitie s GH-MLGRD-RCU-220725-GO- RFB / Supply and Delivery of 7No. Photocopiers, 175 0No. Productive Inclusion Progra Single Stage - One E Printers, 175 Scanners, 5 Des IDA / 68590 Post Request for Bids Open - National 885,000.00 0.00 Signed 2022-07-22 2022-07-08 2022-07-27 2022-07-23 2022-09-07 2022-08-16 2022-10-21 2022-08-12 2022-11-25 2023-02-23 m nvelope ktops, 195 No. Laptops, 5 No. Projectors, 6 Digital Cameras and 5 No. Commercial Drone s GH-MLGRD-RCU-220726-GO- Project Management, Coordi RFB / Procurement of 8No. 4 Single Stage - One E IDA / 68590 nation, and Institutional Stre Post Request for Bids Open - National 650,000.00 0.00 Signed 2022-07-22 2022-07-08 2022-07-27 2022-07-23 2022-09-07 2022-08-16 2022-10-21 2022-08-12 2022-11-25 2023-02-23 X4 Vehicles for LIPW and PI M nvelope ngthening onitoring and Supervision GH-MLGRD-RCU-264274-GO- RFQ / Supply and Delivery of Labor-Intensive Public Works Request for Quota Single Stage - One E 400 Bags of Polyclonal Cashe IDA / 68590 Post Limited 70,000.00 0.00 Signed 2023-02-15 2022-03-28 2023-04-12 2023-06-11 Program tions nvelope w Seeds for LIPW activities in the 34 Southern Districts. GH-MLGRD-RCU-272643-GO- RFQ / Supply and Delivery of Labor-Intensive Public Works Request for Quota Single Stage - One E IDA / 68590 Post Limited 50,000.00 0.00 Completed 2023-02-22 2022-03-28 2023-04-19 2023-06-18 4Million Units of Polypots (Pol Program tions nvelope y bags) for Nursery Activities under LIPW GH-MLGRD-RCU-341125-GO- Labor-Intensive Public Works Request for Quota Single Stage - One E RFQ / Supply and Delivery of IDA / 68590 Post Open - National 85,000.00 0.00 Completed 2023-03-01 2023-04-26 2023-10-23 Program tions nvelope 7,000 Wellington Boots for LI PW Activities GH-MLGRD-RCU-341122-GO- RFB / Supply and Delivery of Productive Inclusion Progra Single Stage - One E Pending Impl 1 (One) Server to Host GMIS IDA / 68590 Post Request for Bids Open - National 90,000.00 0.00 2023-03-31 2023-04-05 2023-05-17 2023-06-16 2023-07-21 2024-01-17 m nvelope ementation PRO, E-DASH, PI System Appl ication Software and Data Ba se GH-MLGRD-RCU-365616-GO- RFQ / Procurement of Signag e and Transparency Account ability Boards for CCMI Nurse Labor-Intensive Public Works Request for Quota Single Stage - One E Pending Impl ries and Plantations for Buils IDA / 68590 Post Open - National 7,727.00 0.00 2023-07-02 2023-08-27 2024-02-23 Program tions nvelope ementation a South, Builsa North Municip al, Bongo, Talensi, Nabdam, Bawku West, Bawku Municip al, Binduri, Garu, Pusiga, Te mpane, and other Districts in EURCC GH-MLGRD-RCU-365618-GO- RFQ / Procurement of Tools, Equipment & PPEs for CCMI N Labor-Intensive Public Works Request for Quota Single Stage - One E Pending Impl urseries and Plantations for IDA / 68590 Post Open - National 5,338.00 0.00 2023-07-02 2023-08-27 2024-02-23 Program tions nvelope ementation Mamprugu Moagduri, East M amprusi Municipal, Bunkpuru gu - Nakpanduri and Yunyoo - Nasuan Districts by the NER CC GH-MLGRD-RCU-365573-GO- RFQ / Procurement of Tools, Equipment, and Materials for Labor-Intensive Public Works Request for Quota Single Stage - One E Pending Impl the establishment of coconut IDA / 68590 Post Open - National 31,000.00 0.00 2023-07-02 2023-08-27 2024-02-23 Program tions nvelope ementation plantation, including nursery at Liati Soba and establishme nt of oil palm plantation at V e Deme in Afadzato South Di strict. GH-MLGRD-RCU-365587-GO- RFQ / Procurement of Tools, Equipment & PPEs for CCMI N urseries and Plantations for B Labor-Intensive Public Works Request for Quota Single Stage - One E Pending Impl IDA / 68590 Post Open - National 22,404.00 0.00 2023-07-03 2023-08-28 2024-02-24 uilsa South, Builsa North, Bon Program tions nvelope ementation go, Talensi, Nabdam, Bawku West, Bawku Mun, Pusiga, Te mpani, Garu, Binduri, District s by the UERCC. Page 6 NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GH-MLGRD-RCU-322569-NC- RFB / Procurement of Service Productive Inclusion Progra Open - Internationa Single Stage - One E Under Imple IDA / 68590 Prior Request for Bids 4,000,000.00 0.00 2022-10-31 2022-10-25 2022-11-05 2022-10-26 2022-12-17 2022-08-19 2023-01-16 2022-11-14 2023-02-20 2025-12-31 Provider for LEAP, LIPW and P m l nvelope mentation I E-Payment Service GH-MLGRD-RCU-220724-NC- RFB / Procurement of Service Productive Inclusion Progra Open - Internationa Single Stage - Two E IDA / 68590 Prior Request for Bids 4,000,000.00 0.00 Canceled 2022-05-16 2022-06-22 2022-05-21 2022-07-14 2022-07-02 2022-08-19 2022-09-14 2022-10-19 2025-12-31 Provider for LEAP, LIPW and P m l nvelope I E-Payment Service CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GH-MLGRD-RCU-341523-CS- Project Management, Coordi CQS / Selection of Consultant Consultant Qualifi IDA / 68590 nation, and Institutional Stre Post Open - National 40,000.00 0.00 Under Review 2023-02-28 2023-02-27 2023-03-04 2023-03-29 2023-04-05 2023-04-19 2023-05-30 to undertake Independent Pr cation Selection ngthening ocurement Audit of Project a ctivities for 2022 INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GH-MLGRD-RCU-363850-CS- CDS / Selection of Consultant Labor-Intensive Public Works Pending Impleme to undertake impact Evaluati IDA / 68590 Prior Direct Selection Direct - National 250,000.00 0.00 2023-06-26 2023-07-28 2023-09-01 2025-09-26 Program ntation on of the Labour-Intensive Pu blic Works Component. Page 7 Procurement General 1. Procurement for the project would be carried out in accordance with the World Bank’s “Guidelines: Procurement of Goods, Works, and Non-Consulting Services under IBRD Loans and IDA Credits & Grants” dated January 2011 (revised July 2014); and “Guidelines: Selection and Employment of Consultants under IBRD Loans and IDA Credits & Grants by World Bank Borrowers” dated January 2011 (revised 2014); and the provisions stipulated in the Loan Agreement. The World Bank Guidelines on Preventing and Combating Fraud and Corruption in Projects Financed by IBRD Loans and IDA Credit and Grants dated October 15, 2006 and revised on January 2011, would also apply. Procurement arrangements and capacity assessment 2. The RGA, under the MCTI, would be the main implementing agency. This agency has already implemented the RECRP. A PIU would be established, which would report directly to the Director General of RGA. The PIU would be responsible for all procurement procedures under the project, supported from at least one full-time procurement officer for all procurement. The PIU Director and technical staff have some experience in World Bank procurement, but this is rather limited. A procurement officer experienced in WB procurement would be hired for the needs of the project, and would work in close coordination with the PIU team. The PIU would be supported also by a procurement assistant, as needed. In addition, technical staff from relevant departments within RGA which might be called on sitting in evaluation committee would be trained on their specific role and general principles of Bank procurement rules. 3. A detailed Project Operational Manual (POM) has been prepared based on previous versions used for RECRP and it was reviewed by the Bank. It would be further revised before the project starts. The manual includes procurement methods to be used in the project along with their step–by-step explanation as well as the standard and sample documents to be used for each method, and service standards, responsibilities and accountability of PIU staff and management for carrying out the activities. The procurement staff and all potential members of tender (or bid evaluation) committees would attend the project launch workshop that would be organized by the Bank staff following the signing of the loan agreement. Further, the Bank team would help the project coordinator identify suitable training courses for the PIU existing team. 4. Risk Mitigation: The following measures were agreed to mitigate the risks and maintain the implementing team’s capacity. Table 2: Summary Risk Assessment Risk Mitigation • Limited procurement • RGA will hire a PIU procurement expert with capacity of the PIU and experience in World Bank financed insufficient knowledge of projects/international procurement. Selection Bank’s procurement and of the procurement expert is a condition of consultant guidelines may effectiveness. delay selection/bidding process and contract management • Unsatisfactory quality of • Preparation of draft technical specifications technical designs/ToRs /terms of reference before project may lead to delays in effectiveness, at least for the contracts for contract implementation which the selection process is to take place in and to contract the first 12 months of the project amendments implementation; • Close involvement of Bank technical expert in the review of the TOR/ TS and designs; • Bank prior review of critical packages/ assignments. • PIU might be initially • Recruitment of key staff after loan signing so overwhelmed with the that ToRs, technical specifications and bidding number of the consultants documents can be prepared early on. and/or size of contracts to • Strengthening PIU's procurement, technical procure and implement and contract administration capacity via workshops. • The packages in the procurement plan will be sequenced and phased to allow sufficient time for bidding, evaluation and Bank review. • The public • Technical staff from relevant departments officials/technical staff, within RGA will be previously trained on their who will be involved in specific role and general principles of Bank project procurement procurement rules; through tender • Operations Manual will set out the service committees, may not be standards, responsibilities and accountability familiar with the applicable of PIU staff, technical staff management for procurement procedures, carrying out the activities. Furthermore, the and may slow down the Bank team will help the project coordinator procurement process identify suitable training courses for the PIU team; • The order for appointment of evaluation committees shall specify the timeframe by which the evaluation committee should complete evaluation and recommendation of award; Risk Mitigation • Insufficient technical • Adequate consulting services and technical capacity within the assistance, training, knowledge exchange supervision or other would be provided under the project departments on RGA may Component D, as needed; cause contract supervision • Intensive and close supervision by Bank delays related to technical team and procurement accredited implementation and poor staff in particular; quality of goods, works and services. • Insufficient knowledge of • PIU staff, and especially the Procurement the latest Procurement and Expert would attend procurement training Consultants Guidelines organized by the Bank (January 2011) • The Bank’s Procurement Specialist assigned to the project has provided the PIU with a full set of the relevant, most recent procurement documents, including but not limited to standard and sample bidding documents, proposal formats, evaluation report documents, etc. The Procurement Plan 5. The Borrower, at appraisal, finalized the procurement plan for project implementation, prepared during preparation phase, which provides the basis for procurement methods. It includes the Bank review requirements and thresholds. The procurement plan would be reviewed and agreed between the Borrower and the Bank during negotiations. It would be available as a separate project document at the office of the PIU, and on the Bank's external website. The Procurement Plan would be updated in agreement with the Bank as required to reflect the actual project implementation needs. Procurement of Goods, Works and Non-Consulting Services 6. The following methods may be used for procurement of goods, works and non-consulting services as agreed in the procurement plan: International Competitive Bidding (ICB), National Competitive Bidding (NCB), Shopping (S), and Direct Contracting (DC). Procurement of Works 7. Works procured under this project would include construction and rehabilitation of buildings and putting up concrete markers on part of or all the territory of the country, for the leveling grid stabilization. Procurement will be done using the Bank’s Standard Bidding Documents (SBD) for all ICB and NCB packages. Prequalification would not be used at all, regardless of the size of civil works contracts. Minor works, as relevant, could use Invitation to Quote (ITQ) for Works acceptable to the Bank for contracts less than or equal to EUR 85,000. Procurement of Goods and Non-Consulting Services 8. Goods and non-consulting services to be procured would include IT systems, furniture, IT equipment (hardware and software), purchase of vehicles for motorized levelling, measurements for the REC, gravity meter equipment, measurement of altitude differences and grid stabilization, data acquisition and improvement. Procurement for all ICB procedures would be done using the Bank’s SBDs. Smaller value contracts, as needed, would be procured using harmonized NCB documents for Goods or shopping using ITQ (June 2011), depending on the cost estimate for the package. The standard documents for supply and installation of information systems would be used for the procurement of the software development phases and roll out. Software maintenance for the control center will be procured through direct contracting considering the equipment already in use works with particular software (provided only by one supplier) and any new software would require changes of the whole equipment which is not feasible and costly. Selection of Consultants 9. Consultant services will include preparation of quality assurance system and data manual, data verification and analysis and modeling, preparation of corporate and business planning, individual consultants for entering of backlog data, map conversion and utility map conversion, capacity building, awareness raising and knowledge transfer, updating the ICT strategy. Multiple individual consultants/technical staff will be hired under the project for the entry of data. A sample contract for hiring of these individuals will be cleared by the Bank and used during the project. 10. The following methods may be used for the selection of consultants: Quality and Cost-Based Selection (QCBS), Quality-Based Selection (QBS), Least-Cost Selection (LCS), Fixed Budget Selection (FBS), Selection based on Consultants Qualifications (CQS), Individual Consultant Selection (IC), and Single Source Selection (SSS). The World Bank's Standard Request for Proposals will be used. All Terms of Reference, irrespective of prior/post review status, are subject to Bank’s review and no objection. Training and Training Plan 11. The institutions providing standard training, conducting seminars and organization of study tours would be selected on the basis of analysis of the most suitable program of training offered by the institutions, availability of services, the period of training and the reasonableness of cost. However, consultants hired to deliver training under the Project would be selected in accordance to the selection methods as stipulated in the Consultant Guidelines applicable to the project. An annual training plan would be prepared and agreed with the Bank. It would include information on the title of training, institution that would provide it, and timeline, cost, number, position and names of relevant people to be trained. The training plan would be updated in agreement with the Bank through the duration of the Project at least annually or as required to reflect the actual project implementation needs. Operating Costs 12. The activities to be financed by the project (as defined in the Loan Agreement) would be procured using the implementing agency’s administrative procedures, which were reviewed and found acceptable to the Bank. Post-review Percentages and Frequency. 13. Contracts not subject to Bank’s prior review would be subject to post review by the Bank’s procurement specialist assigned to the project. Post review of contracts will be carried out once per year. At a minimum, one out of five contracts will be randomly selected for post review. Physical inspection will be conducted for at least 10 percent of the contracts. General Procurement Notice 14. The GPN for the Project will be published in the UN Development Business after loan negotiations. Estim ated gory Re viewb y Type - Co st (EUR) Selection Bank Prio r Cate EUR 1 = Me thod / Po st Procurement Plan $1.21555 A. Valuation, Property Taxation and Public Real Estate Land Management I. Investment cost International Valuation Consultant and assesm ent of the m unicipalities specialist CS 123,400 IC Prior Entering of back log data and extraction of rental data for residential sam ple CS 287,936 IC (m ultiple) Prior Preparation of quality assurance systemand data m anual CS 8,228 IC Post Rental collection for sample of com m ercial properties CS 49,360 IC Post Consultancy for data verification and analisys & m odeling (1) CS 65,814 IC Post Consultancy for data verification and analisys & m odeling (1) - local staff CS 24,680 IC Post Consultancy for data verification and analisys & m odeling (2) CS 65,814 IC Post Consultancy for data verification and analisys & m odeling (2) - local staff CS 24,680 IC Post Data collection for the building register TS 3,948,830 ICB Prior Consultancy for systemim plem entation in at least 5 m unicipalities CS 1,645,345 QCBS Prior International Tax Collection Consultant CS 123,400 IC Prior Training for Municipal Office Staff TR 205,668 N/A Prior Total investm ent cost 6,573,155 Total cost for Com ponentA 6,573,155 B. E-governance for enabling access to real estate information B1. Integrated Real Estate Cadastre and Registration System Develop m ent I. Investm ent cost Upgrade of existing IT system s and sm all m odifications (s canning of incomming documents, import of CS 43,600 IC Prior Software Prototyping or pilot TS 164,535 CQS Prior Software Developm ent Phase I and roll out (front and back office, alphanumeric and graphic and WEB services for external users, e-signature, digitalisation of incoming docs and integration with digital archive, TS 1,472,584 ICB Prior disaster recovery), incl. licenses Software Developm ent Phase II and roll out (Address Register, Register of S patial Units, Mass TS 534,737 ICB Prior Valuation module, Price Index Module, Fiscal Building Register module) Software Developm ent Phase III - integration with key Governm ent registers, e-comm erce, TS 148,080 NCB Prior additional e-services External quality assurance advisor would be hired to support the RGA project m anager CS 164,535 CQS Prior Hardware Supply - phase I (em ergency) G 164,535 NCB Post Hardware Supply, com m unication and other equipm ent and standard licenses (for Data Centers G 3,948,830 ICB Prior and local offices) -phase II LAN/WAN im provm ents W 57,587 SH Post Supervision of data center extension CS 16,453 CQS Post Data Center extenssion W 172,761 NCB Prior Active network equipm ent (firewall, CISCO) G 361,976 ICB Prior Total investment cost 7,250,213 B2. S upport to the National Spatial Data Infrastructure. (NSDI) I. Investm en t cost National Geoportal Upgrade and Im plem entation - software developem nt TS 205,668 ICB Prior National Business Model, Capacity Building, Awareness, Data Harm onisation with INSPIRE TS, QCBS 699,272 QCBS Prior study visits, conference Total investment cost 904,940 B3. S ustainability of the Information Technologydepartment I. Investm ent cost Technical Assistance to develop and implement sustainable model for IT Sector operation, ICT CS 123,400 IC Prior Total investment cost 123,400 B4. C entral Analog ue and Digital Archives and Establishment of BDRC I. Investm en t cost CS 41,134 CQS Post Detailed Design for Archive building and Disaster Recovery Center +Technical control of the design Supervision of works for Archive building and Disaster Recovery Center CS 41,134 CQS Post Data entering/scanning specialists (scanning, indexing, quality control, verification) CS 1,974,415 QCBS Prior Construction works for Archive building and Disaster Recovery Center W 1,974,415 ICB Prior Archive shelves for the new building G 765,086 NCB Post Office furniture for the new Archive building G 41,134 SH Post Expert for preservation of archieved data CS 24,680 IC Post IT equipm ent (hardware and other equipm ent) G 493,604 NCB Prior Software upgrade and further developm ent G 106,947 NCB Post Supply of licences G 24,680 SH Post Operational costs (consum ables, IT equipment repair services, etc) IOC 164,535 IOC Total investment cost 5,651,764 B5. Im provingd igital data quality I. Investm ent cost Pilot Implementation in 3 Local Offices and Quality Assurance CS 123,400 IC Prior Data Quality im provem ent in all local offices CS 1,234,010 IC (m ultiple) Prior International and local advisors CS 41,134 IC Post Total investment cost 1,398,544 B6. S oftware d evelopm en t for the register of theunified procedu reas for contruction permits I. Investm ent cost Local consultants (prepartion of technical specifications for software development) CS 41,134 IC Post Local ICT consultant (4) supporting the system in the Business registry (APR) CS 148,081 IC (m ultiple) Prior QA & QC (consultatnt) CS 41,134 IC Prior Software upgrade and training TS 345,523 NCB Post Supporting hardware (specified in a technical specification for software development) G 493,604 ICB Prior Total In vestm en tC ost 1,069,476 Total cost for C om p onentB 16,398,337 C. Institutional Development of the Republic Geodetic Authority C1. C orporate and Business Planning I. Investm ent cost Preparation of Corporate and Business Planning CS 164,535 QCBS Prior Total investment cost 164,535 C2. National Reference Infrastructure I. Investmen t cost Procurem ent of 16 receivers for replacem ent of the outdated equipm ent for local cadastre offices G 431,903 ICB Prior Procurem ent of Tim e Station for the Control Center G 3,291 SH Post Software m aintenance for the control center G 189,215 DC Prior IT equipm ent for the Control Center G 12,340 SH Post Leveling grid stabilization for all Serbia territory W 608,778 NCB Prior Com pany to m easure altitude differences (South part of Serbia) TS 411,366 NCB Prior Procurem ent of vehicles for m otorized leveling G 180,988 NCB Post Digital levels and invar barcode staves for m otorized leveling G 24,680 SH Post Equipm ent for leveling (tablet pc, laser distance m eter, etc…) G 16,453 SH Post Gravity m eter equipm ent G 106,947 NCB Post Local technical staff for gravity m easurem ents CS 37,020 IC Post Consultant for gravity data processing quality control (QC) CS 14,808 IC Post Consultant for leveling quality control (QC) CS 20,567 IC Post Operating cost (for m easure altitude differences and leveling grid stabilization) IOC 82,267 IOC Total investment cost 2,140,623 C3. C om pletion of thedigital mappingprogram I. Investm ent cost Local technical staff for cadastre m ap conversion* CS/TS 2,632,553 IC/NCB Prior Local technical staff for utility map conversion CS 1,069,475 IC (m ultiple) Prior Total investment cost 3,702,028 C4. Im p roving services and removal of backlogs I. Investm en t cost Local technical staff for handling REC cases (back logs) CS 1,069,475 IC (multiple) Prior Construction works and reconstruction for 2 offices (Sopot and Ruma) W 139,854 NCB Post Total investment cost 1,209,329 C5. Real Estate Cad astre (REC) Improvement I. Investm ent cost Data acquisition TS 3,292,000 ICB Prior Operating costs for data collection IOC 83,000 IOC Total investm ent cost 3,375,000 Total cost for Com ponentC 10,591,515 D. Project Management and supporting activities D1. P roject Imp lem entation Unit I. Investm en t cost A. PIU Director CS 129,550 SSS Prior B. PIU Assistant director (With IT background) CS 115,257 IC Prior C. Training specialist (Part time) CS 53,556 IC Prior D. M&E specialist (Part tim e) CS 53,597 IC Prior E. Procurem ent specialist CS 107,030 IC Prior F. Procurem ent assistant CS 99,543 IC Prior G. FM Specialist CS 107,030 IC Prior H. FM Assistant CS 99,543 IC Prior I. Valuation specialist CS 107,030 IC Prior J. Office manager/Interpreter/Com unications CS 99,543 IC Prior K. Envirom ental Safeguard specialist/Civil Engineer (Part time during design and construction CS Prior works) 53,597 IC E. Increm ental operating costs 389,715 OC Total investment cost 1,414,991 D2. Mon itoring and Evaluation I. Investm ent cost Costumer & Social survey (year 1,3,5) CS 123,400 CQS Prior Annual Financial Audit CS 82,267 LCS Prior Total investment cost 205,667 D3. P ublic Awaren ess I. Investm ent cost Public Awareness Campaign CS 165,000 CQS Prior Total investment cost 165,000 D4. Training I. Investmen t cost Training TR 637,435 N/A Prior Total investment cost 637,435 D5. P olicies an d legal development I. Investm en t cost Legal drafting & Studies CS 123,400 CQ Post Total investm ent cost 123,400 Total cost for Com ponentD 2,546,493 Grand Total 36,109,500 Preparation fee (0.25%) 90,500 Total cost 36,200,000 PROCUREMENT METHOD THRESHOLDS PRIOR REVIEW THRESHOLDS ICB: =/>EUR 900,000 (Goods); =/>EUR All 4.5M (Works) NCB: EUR 265,000 =/> EUR 450,000 CQS: Works, Turnkey/S&I of Plant $5,000,000 1. All Works/Turnkey/S&I of plant and equipment National (NCB) < above US$5.0 million per contract $5,000,000 International (ICB) Goods/IT/non consulting services Goods, IT and non- >$1,000,000 2. above US$1.5 million per contract consulting services National (NCB) V $1,000,000 Request for quotations 3. < $100,000 - (goods) Request for quotations 4. <$200,000 - (works) Selection Method Prior Review Threshold Consulting services Quality Cost Based Selection 1. >$300,000 (QCBS) 2. Least Cost Selection (LCS) >$300,000 Consulting services firms above Single Source Selection US$0.5 million per contract 3. - (SSS) (Firms and individuals) Consultant Qualifications 4. CQ < $300,000 (CQ) Individuals above US$0.2 million 5. Individual Consultant (IC) per contract North Macedonia: Procurement Method Prior Review Threshold Procurement Method Threshold US$ US$ Goods, works, and non-consulting services International (ICB) > Works, Turnkey/S&I of Plant $5,000,000 1. All Works/Turnkey/S&I of plant and equipment National (NCB) < above US$10 million per contract $5,000,000 International (ICB) Goods/IT/non consulting services Goods, IT and non- >$1,000,000 2. above US$2 million per contract consulting services National (NCB) V $1,000,000 Request for quotations 3. < $100,000 - (goods) Request for quotations 4. <$200,000 - (works) Selection Method Prior Review Threshold Consulting services Quality Cost Based Selection 1. >$300,000 (QCBS) 2. Least Cost Selection (LCS) >$300,000 Consulting services firms above Single Source Selection US$1 million per contract 3. - (SSS) (Firms and individuals) Consultant Qualifications 4. CQ < $300,000 (CQ) Individuals above US$0.3 million 5. Individual Consultant (IC) per contract Albania: Procurement Method Prior Review Threshold Procurement Method Threshold US$ US$ Goods, works, and non-consulting services International (ICB) > Works, Turnkey/S&I of Plant $5,000,000 1. All Works/Turnkey/S&I of plant and equipment National (NCB) < above US$10 million per contract $5,000,000 International (ICB) Goods/IT/non consulting services Goods, IT and non- >$1,000,000 2. above US$2 million per contract consulting services National (NCB) V $1,000,000 Request for quotations 3. < $100,000 - (goods) Request for quotations 4. <$200,000 - (works) Selection Method Prior Review Threshold Consulting services Quality Cost Based Selection 1. >$300,000 (QCBS) 2. Least Cost Selection (LCS) >$300,000 Consulting services firms above Single Source Selection US$1 million per contract 3. - (SSS) (Firms and individuals) Consultant Qualifications 4. CQ < $300,000 (CQ) Individuals above US$0.3 million 5. Individual Consultant (IC) per contract PROCUREMENT Western Balkans : Western Balkans Trade and Transport Facilitation PLAN General Information Country: Western Balkans 2020-02-11 Bank’s Approval Date of the Original Procurement Plan: 2023-06-06 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P162043 GPN Date: 2020-05-06 Project Name: Western Balkans Trade and Transport Facilitation Loan / Credit No: IBRD / 89290 Ministry of Transport and Communications Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned WBTTFP-8929-MK-212A / De ployment of Intelligent Trans Request for Bids - port Systems (ITS) on highwa Enhancing transport efficien Open - Internationa Single Stage - One E Works (without pr 14,312,500.0 Under Revie 2024-03-2 y A1 (Corridor X) - South Part IBRD / 89290 Prior Request for Bids 0.00 2023-06-07 2023-06-12 2023-07-24 2023-08-23 2023-09-27 cy and predictability l nvelope equalification) SP 0 w 5 – chainage from km 74+950. D 00 (Interchange Veles South) to km 172+127.44 (Border cr ossing Bogorodica) GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual WBTTF-8929-MK-412B-RFQ / Suporting Project Implement Request for Quota Single Stage - One E IBRD / 89290 Post Open - National 20,000.00 11,263.19 Signed 2020-02-22 2020-04-18 2020-07-18 2020-06-17 Project Accounting Software ation and Coordination tions nvelope Application WBTTF-8929-MK-412A-RFQ / Suporting Project Implement Request for Quota Single Stage - One E Supply, Installation and Confi IBRD / 89290 Post Limited 40,000.00 4,330.40 Completed 2020-02-17 2020-05-11 2020-04-13 2020-08-25 2020-06-12 2020-09-05 ation and Coordination tions nvelope guration of IT Equipment for PIU WBTTFP-8929-MK-412A-2-RF Q / WBTTFP-8929-MK-412A-2 -RFQ (repeated procurement procedure) Suporting Project Implement Request for Quota Single Stage - One E Supply, Installation and Confi IBRD / 89290 Post Limited 36,000.00 25,485.72 Signed 2020-09-09 2020-10-09 2020-11-04 2020-11-27 2020-11-13 ation and Coordination tions nvelope guration of IT Equipment for PIU: Lot #1 - Desktop Personal Co mputers and Monitors; Lot # 2 – Notebooks; Lot #3 - LED TV and Projecto WBTTFP-8929-MK-121E-RFB r; / Provision of customs related Facilitating movement of go Open - Internationa Single Stage - One E Under Imple equipment - CCTV and ANPR IBRD / 89290 ods across the Western Balk Post Request for Bids 1,000,000.00 0.00 2023-02-08 2023-02-28 2023-02-13 2023-02-28 2023-03-27 2023-05-18 2023-04-26 2023-05-31 2024-05-30 l nvelope mentation systems – installation, commi ans ssioning and training of Cust om Administration staff. WBTTFP-8929-MK-212A-RFB / Deployment of Intelligent Tr ansport Systems (ITS) on hig hway A1 (Corridor X) - South Enhancing transport efficien Open - Internationa Single Stage - One E IBRD / 89290 Prior Request for Bids 14,312,500.00 0.00 Canceled 2023-04-25 2023-04-30 2023-06-11 2023-07-11 2023-08-15 2024-02-11 Part – chainage from km 74+ cy and predictability l nvelope 950.00 (Interchange Veles So uth) to km 172+127.44 (Bord er crossing Bogorodica) - WB TTFP-8929-MK-212A-RFB NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual WBTTFP-8929-MK-121D / Re view and analyze of the exist ing customs related equipme nt for all BPCs and Customs u Facilitating movement of go Consultant Qualifi tilities, preparation of Design IBRD / 89290 ods across the Western Balk Post Open - National 50,000.00 58,142.42 Signed 2020-10-07 2020-10-20 2020-10-28 2020-12-11 2021-05-10 2021-01-10 2021-11-29 2021-02-14 2021-12-03 2021-08-13 cation Selection and TS for equipment for ne ans w solution for CCTV and ANP R systems for all BPCs and p erform design audit during in stallation of equipment. WBTTF-8929MK-121A-CS-CQ S / Technical assistance for r eview of the existing physical Facilitating movement of go conditions of the Border Cros Consultant Qualifi IBRD / 89290 ods across the Western Balk Post Open - National 286,250.00 247,676.51 Signed 2021-02-11 2021-05-10 2021-03-04 2021-04-17 2021-11-12 2021-05-17 2022-02-04 2021-06-21 2022-02-15 2022-04-17 sing Points (BCPs) Deve Bair cation Selection ans and Kjafasan, and preparatio n of complete technical docu mentation – detailed designs for civil works WBTTFP-8929-MK-412E / Fin Suporting Project Implement Least Cost Selecti ancial Audit of the WBTTFP a IBRD / 89290 Post Open - National 100,000.00 48,680.67 Signed 2021-03-10 2021-03-11 2021-03-31 2021-04-02 2021-04-21 2021-04-23 2021-05-19 2021-06-01 2021-06-02 2021-06-21 2021-07-07 2021-07-19 2021-08-11 2021-09-15 2022-04-18 ation and Coordination on nd LRCP Projects WBTTFP-MK-CS-REOI-211A / Development of National Inte Enhancing transport efficien Consultant Qualifi Open - Internationa IBRD / 89290 Post 217,550.00 272,502.40 Signed 2021-03-18 2021-04-26 2021-04-08 2021-06-04 2021-05-22 2021-11-26 2021-06-21 2022-03-23 2021-07-26 2022-04-26 2022-03-03 lligent Transportation System cy and predictability cation Selection l (ITS) Strategy for North Mace donia WBTTF-MK-112A / NSW Prog Facilitating movement of go Quality And Cost- Open - Internationa IBRD / 89290 Post 750,000.00 0.00 Canceled 2021-07-01 2021-07-22 2021-09-04 2021-10-02 2021-11-01 2021-12-06 2022-01-10 2022-09-07 ram Management Support ods across the Western Balk Based Selection l ans Page 1 WBTTF-8929-MK-112A / New Facilitating movement of go Quality And Cost- Open - Internationa Under Implement Single Window (NSW) Progra IBRD / 89290 ods across the Western Balk Prior 950,000.00 0.00 2021-12-14 2022-01-07 2022-01-04 2022-02-03 2022-02-17 2022-06-09 2022-03-17 2022-08-12 2022-04-16 2022-11-09 2022-05-21 2023-01-09 2022-06-25 2025-02-09 Based Selection l ation m Management Support in N ans orth Macedonia WBTTFP-8929-MK-121-1A-CS -CQS / Design Audit of projec t documentation and designs for reconstruction and/or upg Facilitating movement of go Consultant Qualifi rade of the facilities and infra IBRD / 89290 ods across the Western Balk Post Open - National 25,000.00 20,223.79 Signed 2022-03-02 2022-03-03 2022-03-23 2022-05-06 2022-05-13 2022-06-05 2022-06-29 2022-07-10 2022-07-16 2022-10-28 cation Selection structure at the Border Cross ans ing Points (BCPs) Deve Bair a nd Kjafasan. Ref.no. WBTTFP-8929-MK-12 1-1A-CS-CQS. WBTTFP-8929-MK-212AC-1-S OUTH / Supervision of the De ployment (Installation and Int egration) of an Intelligent Tra Enhancing transport efficien Quality And Cost- Open - Internationa Under Implement IBRD / 89290 Prior 1,150,000.00 0.00 2023-06-12 2023-06-16 2023-07-03 2023-08-16 2023-09-13 2023-10-13 2023-11-17 2023-12-22 2025-12-15 nsport Systems (ITS) on the cy and predictability Based Selection l ation Highway A1 (Corridor X) - So uth Part (Interchange Veles S outh - Border crossing Bogor odica) - WBTTFP-8929-MK-21 2AC-1-South INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual WBTTFP-8929-MK-REOI-411 Suporting Project Implement Individual Consult IBRD / 89290 Post Open 24,000.00 100,026.00 Signed 2020-02-27 2020-06-01 2020-04-16 2020-11-10 2020-05-07 2020-11-10 2020-06-11 2020-12-16 2023-05-27 C / Transport - Road Infrastru ation and Coordination ant Selection cture Expert WBTTF-8929-MK-REOI-411D / The Consultant - Trade and Suporting Project Implement Individual Consult IBRD / 89290 Post Open 103,500.00 71,843.76 Signed 2020-02-28 2020-06-01 2020-04-17 2020-11-25 2020-05-08 2020-11-30 2020-06-12 2020-12-16 2024-02-22 Customs (National Single Win ation and Coordination ant Selection dow - NSW) Expert WBTTF-8929-MK-REOI-411E Suporting Project Implement Individual Consult IBRD / 89290 Post Open 103,500.00 71,843.76 Signed 2020-03-02 2021-03-12 2020-04-20 2021-06-03 2020-05-11 2021-08-20 2020-06-15 2021-09-01 2024-02-25 / Intelligent Transport Syste ation and Coordination ant Selection ms Expert WBTTF-8929-MK-REOI-411J / Suporting Project Implement Individual Consult Environmental and Social (E IBRD / 89290 Post Open 32,000.00 100,026.00 Signed 2020-03-03 2020-06-01 2020-04-21 2020-11-10 2020-05-12 2020-11-10 2020-06-16 2020-12-16 2021-10-09 ation and Coordination ant Selection &S) Specialist WBTTFP -8929-MKD-REOI 41 Suporting Project Implement Individual Consult IBRD / 89290 Post Open 24,000.00 72,054.00 Signed 2020-03-27 2020-06-01 2020-05-15 2020-11-10 2020-06-05 2020-11-10 2020-07-10 2020-12-16 2021-07-05 1I / Traffic Engineer ation and Coordination ant Selection WBTTFP-8929-MK-REOI-411 Suporting Project Implement Individual Consult IBRD / 89290 Post Open 24,000.00 100,026.00 Signed 2020-05-26 2020-06-01 2020-07-14 2020-11-10 2020-08-04 2020-11-10 2020-09-08 2020-12-16 2021-09-03 N / Transport - Road Infrastru ation and Coordination ant Selection cture Expert WBTTFP-8929-MK-411Q-1 / S upport to carry out public an Suporting Project Implement Individual Consult d multi-stakeholder consultat IBRD / 89290 Post Direct 26,335.00 27,164.15 Signed 2020-05-29 2020-05-28 2020-06-08 2020-06-03 2020-06-29 2020-06-08 2020-08-03 2020-10-01 2021-01-30 ation and Coordination ant Selection ions and surveys in regard to Environmental and Social Saf eguard WBTTFP-8929-MK-REOI-411 Suporting Project Implement Individual Consult IBRD / 89290 Post Open 26,638.00 86,400.00 Signed 2020-11-11 2020-11-18 2020-12-30 2020-11-23 2021-01-20 2019-10-20 2021-02-24 2019-10-26 2022-04-20 A / Project Director ation and Coordination ant Selection WBTTFP-8929-MK-REOI-411F Suporting Project Implement Individual Consult IBRD / 89290 Post Open 22,123.00 72,000.00 Signed 2020-11-11 2020-11-18 2020-12-30 2020-11-25 2021-01-20 2019-10-21 2021-02-24 2019-10-26 2022-04-20 / Transport Infrastructure Exp ation and Coordination ant Selection ert #1 WBTTFP-8929-MK-REOI-411 Suporting Project Implement Individual Consult IBRD / 89290 Post Open 22,123.00 72,000.00 Signed 2020-11-11 2020-11-18 2020-12-30 2020-11-25 2021-01-20 2019-10-21 2021-02-24 2019-10-26 2022-04-20 G / Transport Infrastructure E ation and Coordination ant Selection xpert #2 WBTTFP-8929-MK-REOI-411 Suporting Project Implement Individual Consult H / Consultant - Transport Inf IBRD / 89290 Post Open 22,123.00 72,000.00 Signed 2020-11-11 2020-11-18 2020-12-30 2020-11-25 2021-01-20 2019-10-21 2021-02-24 2019-10-26 2022-04-20 ation and Coordination ant Selection rastructure Expert #3 WBTTFP-8929-MK-REOI-411K Suporting Project Implement Individual Consult IBRD / 89290 Post Open 22,123.00 54,000.00 Signed 2020-11-11 2020-11-18 2020-12-30 2020-11-25 2021-01-20 2019-10-18 2021-02-24 2019-10-26 2022-04-20 / Procurement Specialist #1 ation and Coordination ant Selection WBTTFP-8929-MK-REOI-411L Suporting Project Implement Individual Consult IBRD / 89290 Post Open 22,123.00 54,000.00 Signed 2020-11-11 2020-11-18 2020-12-30 2020-11-25 2021-01-20 2019-10-18 2021-02-24 2019-10-26 2022-04-20 / Procurement Specialist #2 ation and Coordination ant Selection WBTTFP-8929-MK-REOI-411 Suporting Project Implement Individual Consult IBRD / 89290 Post Open 22,123.00 54,000.00 Signed 2020-11-11 2020-11-18 2020-12-30 2020-11-25 2021-01-20 2019-10-18 2021-02-24 2019-10-26 2021-08-23 M / Financial Management Sp ation and Coordination ant Selection ecialist WBTTFP-8929-MK-411R-CS-I Suporting Project Implement Individual Consult C / Information Technology (I IBRD / 89290 Post Open 82,440.00 0.00 Canceled 2022-06-27 2022-07-21 2022-07-30 2022-08-13 2022-09-03 2025-12-16 ation and Coordination ant Selection T) Expert - PIU Staff WBTTFP-8929-MK-212D-CS- DS / Improvement of the Desi gn documentation for the Int elligent Transport System (IT Enhancing transport efficien IBRD / 89290 Post Direct Selection Direct 185,000.00 157,705.05 Signed 2022-07-11 2022-07-11 2022-07-21 2022-07-13 2022-08-19 2022-09-02 2023-08-19 S) implementation on Highw cy and predictability ay A1 (E75) – Corridor X and preparation of the Tender do cumentation for selection of I mplementation Contractor WBTTFP-8929MK-411S-CS-IC -DS / High Level Project Coor Suporting Project Implement dinator for inter-institutional IBRD / 89290 Post Direct Selection Direct - National 22,000.00 0.00 Signed 2022-09-22 2022-09-22 2022-10-02 2022-09-28 2022-10-17 2023-10-17 ation and Coordination support of the Western Balka n Trade and Transport Facilit ation Project WBTTF-8929-MK-411O / Dat a Collection and Data Proces Suporting Project Implement sing regarding existing natio IBRD / 89290 Post Direct Selection Direct - National 67,000.00 0.00 Signed 2022-10-07 2022-10-10 2022-10-17 2022-10-19 2022-12-21 2026-02-03 ation and Coordination nal data on trade facilitation for period 2022-2025 WBTTF-8929-MK-411O WBTTF-8929-MK-311A / Revi ew of the existing national le gal and regulatory framewor Enhancing Market Access for Individual Consult Under Implement IBRD / 89290 Post Open - National 50,000.00 0.00 2023-01-31 2023-01-31 2023-03-05 2023-03-17 2023-03-19 2023-04-01 2023-04-16 2023-12-12 k for implementation of the c Trade and Investments ant Selection ation ountry specific commitments under the CEFTA AP5 and AP 6 and EU Acquis where relev ant Page 2 WBTTFP-8929-MKD-411R-1 / Urban planning and design s Suporting Project Implement Individual Consult Under Implement IBRD / 89290 Post Open - National 82,440.00 0.00 2023-04-13 2023-04-18 2023-06-01 2023-06-22 2023-07-27 2026-02-11 upport Expert - PIU staff - Ind ation and Coordination ant Selection ation ividual Consultant - WBTTFP- 411R-1 WBTTFP-8929MK-411T-CS-IC / Administrative and Financia Suporting Project Implement Individual Consult IBRD / 89290 Post Open - National 25,763.00 0.00 Canceled 2023-04-27 2023-04-28 2023-06-15 2023-07-06 2023-08-10 2025-12-27 l Management Assistant – PIU ation and Coordination ant Selection Staff - WBTTFP-8929MK-411T -CS-IC WBTTFP-8929MK-411U-CS-IC Suporting Project Implement Individual Consult Under Implement / Procurement Specialist #3 – IBRD / 89290 Prior Open - National 30,915.00 0.00 2023-04-27 2023-05-02 2023-06-15 2023-07-06 2023-08-10 2025-12-27 ation and Coordination ant Selection ation PIU Staff - WBTTFP-8929MK-4 11T-CS-IC Page 3 PROCUREMENT PLAN (Textual Part) Project information: Digital Acceleration Project (P173373) Project Implementation agency: Rwanda Information Society Authority Date of the Procurement Plan: August 24, 2022 Period covered by this Procurement Plan: For the first 18 month Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the Procurement Regulation for IPF Finance for Borrowers, November 2020, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets Not Applicable Procurement of Second Hand Goods Not Applicable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: is applicable for those contracts identified in the Procurement Plan tables. Works: is applicable for those contracts identified in the Procurement Plan tables. Other Relevant Procurement Information. Not Applicable PROCUREMENT Rwanda : Digital Acceleration Project PLAN General Information Country: Rwanda 2022-08-24 Bank’s Approval Date of the Original Procurement Plan: 2023-06-05 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P173373 GPN Date: 2022-06-02 Project Name: Digital Acceleration Project Loan / Credit No: COFN / C2100, IDA / 70000 Rwanda Information Society Authority Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned RW-RISA-309743-CW-RFB-(3 Request for Bids - .2) / Renovation and retrofitti Digital Innovation and Entre Single Stage - One E Small Works SPD Pending Imp 2022-11-2 COFN / C2100 Post Request for Bids Open - National 150,000.00 0.00 2022-08-26 2022-08-31 2022-09-30 2022-10-14 2022-11-11 ng works for Computer Labs, preneurship nvelope (1 envelope proce lementation 0 Classrooms and Offices ss) GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual RW-RISA-309748-GO-RFQ-(4 ) / Purchase of materials, tool Request for Quota Single Stage - One E Pending Impl COFN / C2100 Project Management Post Limited 20,000.00 0.00 2022-08-27 2022-10-01 2022-10-15 s, office furniture and equip tions nvelope ementation ment for the project team RW-RISA-309640-GO-RFB-(1. 2) / Purchase of smartphones Single Stage - One E Pending Impl COFN / C2100 Digital Access and Inclusion Post Request for Bids Limited 430,000.00 0.00 2022-09-28 2022-10-03 2022-10-24 2022-11-23 2022-12-21 2023-02-19 and internet connections for nvelope ementation digital ambassadors RW-RISA-317315-GO-RFB (2. Digital Public Service Deliver Single Stage - One E Under Imple 3) / Supply and installation of COFN / C2100 Post Request for Bids Open - National 176,400.00 0.00 2022-11-30 2022-11-18 2022-12-05 2023-01-16 2022-12-22 2023-02-15 2023-03-22 2024-03-21 y nvelope mentation IT equipment & software for t he helpdesk RW-RISA-309742-GO-RFB-(3. Digital Innovation and Entre Pending Impl 2) / Procurement of IT Equip COFN / C2100 Post Direct Selection Direct - National 453,000.00 0.00 2022-10-31 2022-11-05 2022-12-17 2023-02-15 preneurship ementation ment (Laptops, Projectors, Sc anners, Printers) RW-RISA-309523-GO-RFB-(1. Pending Impl 2) / Purchase of laptops for di COFN / C2100 Digital Access and Inclusion Post Direct Selection Direct - National 500,000.00 0.00 2022-10-21 2022-10-26 2022-12-05 2023-02-03 ementation gital ambassadors RW-RISA-309750-GO-RFQ-(4 Pending Impl ) / Purchase of computers, so COFN / C2100 Project Management Post Direct Selection Direct - National 10,000.00 0.00 2022-10-21 2022-10-26 2022-11-28 2022-12-28 ementation ftware for new project team RW-RISA-320654-GO-RFB (4) / E-waste management: Insta Single Stage - One E Pending Impl llation of 30 new decentralize COFN / C2100 Project Management Post Request for Bids Open - National 260,000.00 0.00 2022-10-28 2022-11-02 2022-12-14 2023-01-13 2023-02-17 2023-08-16 nvelope ementation d e-waste collection facilities across the Country (one per district) RW-RISA-317367-GO-RFB (2. Digital Public Service Deliver Single Stage - One E Pending Impl 4) / Procurement of basic ICT COFN / C2100 Post Request for Bids Open - National 250,000.00 0.00 2022-10-31 2022-11-05 2022-12-17 2023-01-16 2023-02-20 2023-04-21 y nvelope ementation systems for the Data Protecti on Office RW-RISA-327405-GO-RFB / S Digital Innovation and Entre Open - Internationa Single Stage - One E upply and Installation of CSIR COFN / C2100 Post Request for Bids 2,500,000.00 0.00 Canceled 2023-01-14 2023-01-19 2023-02-18 2023-03-20 2023-04-24 2023-06-23 preneurship l nvelope T’S ICT Equipment & Softwar e RW-RISA-329747-GO-RFB(2. 3) / Supply, Installation and c Digital Public Service Deliver Open - Internationa Single Stage - One E COFN / C2100 Prior Request for Bids 4,500,000.00 0.00 Canceled 2023-10-31 2023-11-05 2023-12-17 2024-01-16 2024-02-20 2024-11-16 onfiguration of the infrastruct y l nvelope ure to host the Government l ow-code platform. RW-RISA-344465-GO-RFB / T ender to upgrade of a mobile Single Stage - One E Pending Impl COFN / C2100 Digital Access and Inclusion Post Request for Bids Open - National 500,000.00 0.00 2023-02-26 2023-03-03 2023-04-14 2023-05-14 2023-06-18 2023-12-15 station and portable spectru nvelope ementation m monitoring station and trai ning of staff RW-RISA-344065-GO-RFB / T Digital Public Service Deliver Open - Internationa Single Stage - One E Pending Impl ender to upgrade of the build COFN / C2100 Post Request for Bids 300,000.00 0.00 2023-03-20 2023-03-25 2023-05-06 2023-06-05 2023-07-10 2024-07-09 y l nvelope ementation ing permit management syst em RW-RISA-344066-GO-RFB / T Digital Public Service Deliver Open - Internationa Single Stage - One E Pending Impl ender for Civil Registration Ar IDA / 70000 Prior Request for Bids 4,429,650.00 0.00 2024-02-29 2024-03-05 2024-04-16 2024-05-16 2024-06-20 2024-12-17 y l nvelope ementation chives Digitization RW-RISA-309734-GO-RFB-(3. Digital Innovation and Entre Single Stage - One E Pending Impl 2) / Procurement of Lab equi COFN / C2100 Post Request for Bids Open - National 800,000.00 0.00 2022-08-22 2022-08-27 2022-09-26 2022-10-10 2022-11-14 2023-02-12 preneurship nvelope ementation pment for various laboratorie s RW-RISA-309746-GO-RFQ-(3 Digital Innovation and Entre Request for Quota Single Stage - One E Pending Impl .2) / Supply of books (print b COFN / C2100 Post Limited 100,000.00 0.00 2022-08-27 2022-10-22 2022-11-21 preneurship tions nvelope ementation ooks for the library and eBoo ks) RW-RISA-344477-GO-RFB(2. Digital Public Service Deliver Open - Internationa Single Stage - One E Under Imple 1) / Development of pre-enro COFN / C2100 Prior Request for Bids 1,500,000.00 0.00 2023-03-15 2023-05-22 2023-03-20 2023-06-06 2023-05-01 2023-05-31 2023-07-05 2024-01-01 y l nvelope mentation lment and identity proofing s olution RW-RISA-344878-GO-RFB(2. Digital Public Service Deliver Open - Internationa Single Stage - One E Pending Impl 3) / Tender to develop E-parli COFN / C2100 Post Request for Bids 600,000.00 0.00 2023-04-12 2023-04-17 2023-05-29 2023-06-28 2023-08-02 2024-01-29 y l nvelope ementation ament system RW-RISA-333556-GO-RFB (2. 3) / Supply of health Center a Digital Public Service Deliver Open - Internationa Single Stage - One E Pending Impl nd referral hospital ICT equip COFN / C2100 Post Request for Bids 2,545,000.00 0.00 2023-01-06 2023-01-11 2023-02-22 2023-03-24 2023-04-28 2023-10-25 y l nvelope ementation ment including installation of LAN, UPS, radiology workstati on and smart screen Page 1 RW-RISA-333544-GO-DIR (2. 3) / Supply of health center a nd referral hospital's ICT equi Digital Public Service Deliver Pending Impl COFN / C2100 Post Direct Selection Direct - National 652,000.00 0.00 2023-01-13 2023-01-18 2023-02-22 2023-05-23 pment including desktops, se y ementation rvers, laptops, routers, switc h and heavy duty printer lea sing service RW-RISA-345960-GO-RFB(2. Digital Public Service Deliver Open - Internationa Single Stage - One E Pending Impl 1) / Upgrade the National PKI COFN / C2100 Post Request for Bids 970,940.00 0.00 2023-09-20 2023-09-25 2023-11-06 2023-12-06 2024-01-10 2024-07-08 y l nvelope ementation to comply with global trust st andard RW-RISA-345967-GO-RFB(2. 3) / Upgrade of Irembo platfo Digital Public Service Deliver Open - Internationa Single Stage - One E Pending Impl rms to the government e-ser COFN / C2100 Post Request for Bids 1,750,000.00 0.00 2023-05-17 2023-05-22 2023-07-03 2023-08-02 2023-09-06 2024-01-04 y l nvelope ementation vices low code/no code platfo rm and design of its infrastru cture architecture RW-RISA-345986-GO-RFB(2. Digital Public Service Deliver Open - Internationa Single Stage - One E Pending Impl 2) / Tender to Develop a Cent COFN / C2100 Post Request for Bids 1,500,000.00 0.00 2023-04-19 2023-04-24 2023-06-05 2023-07-05 2023-08-09 2024-02-05 y l nvelope ementation ralized electronic archiving s ystem RW-RISA-346032-GO-RFB(1. 2) / Tender to Design, Develo pment and Operationalizatio Open - Internationa Single Stage - One E Pending Impl n of a Shared Digital Skills Tr COFN / C2100 Digital Access and Inclusion Post Request for Bids 400,000.00 0.00 2023-04-20 2023-04-25 2023-06-06 2023-07-06 2023-08-10 2023-12-08 l nvelope ementation aining Platform and Digital A mbassadors Program Manag ement System with a mobile App (including M&E Platform) RW-RISA-346119-GO-RFB(2. Digital Public Service Deliver Open - Internationa Single Stage - One E Pending Impl 3) / Tender to develop the un COFN / C2100 Post Request for Bids 400,000.00 0.00 2023-04-20 2023-04-25 2023-06-06 2023-07-06 2023-08-10 2024-08-09 y l nvelope ementation ified business registry syste m RW-RISA-349445-GO-RFB(2. 3) / Tender to upgrade of ele Digital Public Service Deliver Open - Internationa Single Stage - One E Pending Impl COFN / C2100 Post Request for Bids 1,900,000.00 0.00 2023-05-23 2023-05-28 2023-07-09 2023-08-08 2023-09-12 2024-09-11 ctronic medical record and h y l nvelope ementation ospital management informa tion system RW-RISA-349465-GO-RFB(2. Digital Public Service Deliver Open - Internationa Single Stage - One E Under Imple 1) / Supply of Single Digital I COFN / C2100 Post Request for Bids 800,000.00 0.00 2023-05-17 2023-04-11 2023-05-22 2023-07-03 2023-08-02 2023-09-06 2024-03-04 y l nvelope mentation D Registration Kit RW-RISA-351862-GO-RFB (2. Digital Public Service Deliver Open - Internationa Single Stage - One E Pending Impl 3) / Tender to upgrade of the COFN / C2100 Post Request for Bids 1,300,000.00 0.00 2023-05-26 2023-05-31 2023-07-12 2023-08-11 2023-09-15 2025-03-08 y l nvelope ementation e-procurement system RW-RISA-351863-GO-RFB (2. 3) / Purchase of Infrastructur Digital Public Service Deliver Single Stage - One E Pending Impl COFN / C2100 Post Request for Bids Open - National 406,000.00 0.00 2023-05-26 2023-05-31 2023-07-12 2023-08-11 2023-09-15 2024-01-13 e and third-party licenses for y nvelope ementation the e-procurement system NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual RW-RISA-309732-NC-RFB- (2 Digital Innovation and Entre Open - Internationa Single Stage - One E .1) / Upgrade the National PK COFN / C2100 Post Request for Bids 970,940.00 0.00 Canceled 2022-09-15 2022-09-20 2022-11-04 2022-12-04 2023-01-08 2023-07-07 preneurship l nvelope I to comply with global trust standard RW-RISA-309643-GO-RFB-(1. Single Stage - One E Pending Impl 3) / Pilot phase of Smart clas COFN / C2100 Digital Access and Inclusion Post Request for Bids Open - National 500,000.00 0.00 2022-10-18 2022-10-23 2022-11-22 2022-12-22 2023-01-26 2023-07-25 nvelope ementation sroom internet connectivity RW-RISA-328525-NC-RFQ (3. Digital Innovation and Entre Request for Quota Single Stage - One E Under Imple COFN / C2100 Post Limited 90,000.00 0.00 2022-12-11 2023-02-05 2023-03-07 2) / Internet Connectivity for preneurship tions nvelope mentation RCA RW-RISA-329761-CS-QCBS(2 Digital Public Service Deliver Single Stage - One E Pending Impl COFN / C2100 Post Request for Bids Open - National 150,000.00 0.00 2022-12-30 2023-01-04 2023-02-15 2023-03-17 2023-04-21 2024-04-20 .1) / Tender for Call Centre as y nvelope ementation a Service RW-RISA-329775-CS-QCBS(2 .1) / Request for Bids Pre-enr Digital Public Service Deliver Open - Internationa Single Stage - One E COFN / C2100 Post Request for Bids 1,300,000.00 0.00 Canceled 2023-01-16 2023-01-21 2023-03-04 2023-04-03 2023-05-08 2023-11-04 olment Database Information y l nvelope System Design, Supply and I nstallation RW-RISA-339396-NC-DIR (1. 3) / Acquisition of additional Direct - Internation Pending Impl bandwidth capacity for Rwan COFN / C2100 Digital Access and Inclusion Post Direct Selection 350,000.00 0.00 2023-02-03 2023-02-08 2023-04-14 2023-05-14 al ementation da’s research and educationa l community through UBUNT UNET alliance RW-RISA-340882-NC-RFB (4) Single Stage - One E Under Imple / Hire of a company for proje COFN / C2100 Project Management Post Request for Bids Open - National 250,000.00 0.00 2023-02-28 2023-04-14 2023-03-05 2023-04-04 2023-05-04 2023-06-08 2024-06-07 nvelope mentation ct communication and brandi ng RW-RISA-340879-NC-RFB (1. Single Stage - One E Pending Impl 4) / Purchase of cellular mobi COFN / C2100 Digital Access and Inclusion Post Request for Bids Open - National 900,000.00 0.00 2023-02-17 2023-02-22 2023-03-24 2023-04-23 2023-05-28 2023-11-24 nvelope ementation le coverage planning tool an d staff training RW-RISA-347082-NC-DIR (2. Digital Public Service Deliver Pending Impl COFN / C2100 Post Direct Selection Direct - National 30,000.00 0.00 2023-03-10 2023-03-15 2023-04-19 2024-04-18 1) / Tender to provide media y ementation services RW-RISA-351828-NC-RFB (.3 Open - Internationa Single Stage - One E Pending Impl ) / Purchase of bulk dedicate COFN / C2100 Digital Access and Inclusion Prior Request for Bids 16,500,000.00 0.00 2023-04-14 2023-04-19 2023-05-31 2023-06-30 2023-08-04 2024-01-31 l nvelope ementation d internet bandwidth for gov ernment of Rwanda RW-RISA-363828-NC-DIR (2. Digital Public Service Deliver Direct - Internation Pending Impl 3) / Tender to upgrade the M COFN / C2100 Post Direct Selection 152,000.00 0.00 2023-05-31 2023-06-05 2023-07-10 2023-08-09 y al ementation ailing Solution for Governme nt Institutions RW-RISA-329771-CS-QCBS(2 Digital Public Service Deliver Open - Internationa Single Stage - One E Pending Impl .1) / Tender for Civil Registrat COFN / C2100 Post Request for Bids 3,800,000.00 0.00 2023-06-02 2023-06-07 2023-07-19 2023-08-18 2023-09-22 2024-09-21 y l nvelope ementation ion Archives Digitization CONSULTING FIRMS Page 2 Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual RW-RISA-309792-CS-QCBS-( 1.2) / Design, Development a nd Operationalization of a Sh Quality And Cost- Open - Internationa ared Digital Skills Training Pl COFN / C2100 Digital Access and Inclusion Post 400,000.00 0.00 Canceled 2022-08-26 2022-09-16 2022-10-05 2022-11-04 2022-11-18 2022-12-09 2023-01-06 2023-07-05 Based Selection l atform and Digital Ambassad ors Program Management Sy stem with a mobile App (incl uding M&E Platform) RW-RISA-309816-CS-QCBS-( 1.4) / Technical assistance to Quality And Cost- Open - Internationa Under Implement COFN / C2100 Digital Access and Inclusion Post 100,000.00 0.00 2022-09-16 2022-10-12 2022-10-07 2022-11-04 2022-12-04 2022-12-18 2023-01-15 2023-02-12 2023-08-11 assess social impact of the te Based Selection l ation lecommunications services m arket RW-RISA-309833-CS-QCBS-( 2.2) / Consulting firm for pre Digital Innovation and Entre Quality And Cost- Open - Internationa COFN / C2100 Post 200,000.00 0.00 Canceled 2022-12-02 2022-11-21 2022-12-23 2023-01-20 2023-02-19 2023-03-05 2023-04-02 2023-05-07 2023-11-03 paration of National Geospati preneurship Based Selection l al Data Strategy, Policy and I mplementation Plan RW-RISA-309850-CS-QCBS-( Digital Innovation and Entre Quality And Cost- Open - Internationa 2.4) / Development of Data P COFN / C2100 Post 300,000.00 0.00 Canceled 2022-09-02 2022-10-16 2022-09-23 2022-10-21 2022-11-20 2022-12-04 2023-01-08 2023-02-12 2023-08-11 preneurship Based Selection l rotection office 5-year strate gic plan RW-RISA-309963-CS-QCBS-( Digital Public Service Deliver Quality And Cost- Open - Internationa Pending Impleme 3.1) / TA for administering an COFN / C2100 Post 1,000,000.00 0.00 2022-12-16 2023-01-06 2023-02-03 2023-03-05 2023-03-19 2023-04-09 2023-05-14 2024-05-13 y Based Selection l ntation International accelerator pro gram RW-RISA-309965-CS-QCBS-( 3.1) / Selection of consultanc Digital Public Service Deliver Quality And Cost- Open - Internationa y firm for Training and capaci COFN / C2100 Post 150,000.00 0.00 Canceled 2022-11-18 2022-09-30 2022-12-09 2023-01-06 2023-02-05 2023-02-19 2023-03-26 2023-04-30 2023-10-27 y Based Selection l ty building for angel investor s and / staff of fund manager s RW-RISA-309960-CS-QCBS-( 3.1) / TA for entrepreneurial ecosystem market assessme Consultant Qualifi Open - Internationa nt, ecosystem mapping and COFN / C2100 Project Management Post 90,000.00 0.00 Canceled 2021-09-04 2022-10-16 2021-09-25 2022-07-27 2022-09-25 2022-10-23 2023-04-21 cation Selection l development of tender docu ments for ESO support and t he international acceleration program RW-RISA-309810-CS-QCBS-( 1.3) / Technical assistance to prepare a strategic and oper Quality And Cost- Open - Internationa Under Implement COFN / C2100 Digital Access and Inclusion Post 200,000.00 0.00 2021-10-06 2022-10-16 2021-10-16 2022-02-01 2022-03-03 2022-08-05 2022-08-30 2022-10-04 2023-04-02 ational plan for the developm Based Selection l ation ent of school digital infrastru cture and the national resear ch and education network RW-RISA-309842-CS-QCBS ( 2.4) / Hiring a consulting firm Digital Public Service Deliver Quality And Cost- Open - Internationa Under Implement for conducting a baseline nat COFN / C2100 Post 200,000.00 0.00 2022-05-13 2022-10-16 2022-05-23 2022-10-09 2022-11-06 2022-12-06 2023-01-10 2023-02-14 2023-08-13 y Based Selection l ation ional cyber security assessm ent and developing a strategi c action plan RW-RISA-309910-CS-QCBS-( 3.1) / Technical Assistance to Digital Innovation and Entre Quality And Cost- Open - Internationa Under Implement COFN / C2100 Post 300,000.00 0.00 2021-09-20 2022-12-20 2021-11-17 2022-04-12 2022-05-31 2022-07-30 2022-09-10 2022-10-01 2023-10-01 develop National Innovation preneurship Based Selection l ation Policy and Smart Rwanda Ma sterplan RW-RISA-309820-CS-QCBS-( 2.1) / Technical assistance to carry out a feasibility study t Digital Public Service Deliver Quality And Cost- Open - Internationa Under Implement COFN / C2100 Post 280,000.00 0.00 2021-02-02 2022-10-16 2021-12-01 2022-03-02 2022-04-11 2022-05-11 2022-06-13 2022-08-16 2023-02-12 o inform the GoR on best app y Based Selection l ation roach to digitalize civil registr y archives across all sectors and cells RW-RISA-309787-CS-QCBS-( Quality And Cost- Open - Internationa Under Implement 1.1) / Technical assistance fo COFN / C2100 Digital Access and Inclusion Post 300,000.00 0.00 2021-10-06 2022-10-16 2021-10-16 2022-06-22 2022-06-01 2022-07-20 2022-08-19 2022-09-02 2022-10-07 2022-10-08 Based Selection l ation r designing the affordable de vice scheme RW-RISA-313264-CS-QCBS-( 1.2) / Technical assistance fo Quality And Cost- Under Implement r evaluating digital skills prog COFN / C2100 Digital Access and Inclusion Post Open - National 350,000.00 0.00 2021-08-15 2022-10-16 2021-08-25 2022-01-06 2022-03-08 2022-04-07 2022-05-09 2022-08-16 2023-02-12 Based Selection ation rams, and developing requisi te digital skills framework an d interventions RW-RISA-309794-CS-QCBS-( 1.3) / Feasibility study to sup port the preparation of an op erational plan for the enhanc Quality And Cost- Open - Internationa Under Implement COFN / C2100 Digital Access and Inclusion Post 400,000.00 0.00 2021-08-20 2022-10-16 2021-09-21 2022-02-18 2022-04-04 2022-06-03 2022-07-12 2022-08-16 2023-02-12 ement of government networ Based Selection l ation k planning and management, and roll-out of public access points within the context of e xpanding last mile connectivi ty in Rwanda RW-RISA-312910-CS-QCBS-( 2.3) / Hiring a firm for data c Digital Public Service Deliver Quality And Cost- Open - Internationa COFN / C2100 Post 1,350,000.00 0.00 Canceled 2022-10-10 2022-10-31 2022-12-14 2023-01-11 2023-02-10 2023-03-17 2023-04-21 2023-10-18 ollection, data cleaning, data y Based Selection l immigration and training in D igital literacy RW-RISA-312908-CS-QCBS-( 2.3) / Quality Assurance for U Digital Public Service Deliver Quality And Cost- Open - Internationa Under Implement COFN / C2100 Post 300,000.00 0.00 2022-10-10 2022-10-30 2022-10-31 2022-12-14 2023-01-11 2023-02-10 2023-03-17 2023-04-21 2024-04-20 -SACCO Automation: Banking y Based Selection l ation Business, Software and Infras tructure RW-RISA-317474-CS-QCBS ( 2.4) / Hiring a Cybersecurity Digital Public Service Deliver Quality And Cost- Open - Internationa Under Implement Consultant Firm responsible f COFN / C2100 Post 300,000.00 0.00 2022-10-30 2023-04-05 2022-11-20 2023-01-03 2023-01-31 2023-03-02 2023-04-06 2023-05-11 2023-11-07 y Based Selection l ation or developing cybersecurity c ompliance and audit framew ork RW-RISA-317314-CS-QCBS ( 3.1) / TA to administer a perf Digital Innovation and Entre Quality And Cost- Open - Internationa Pending Impleme COFN / C2100 Post 200,000.00 0.00 2022-09-30 2022-10-21 2022-12-04 2023-01-01 2023-01-31 2023-03-07 2023-04-11 2023-10-08 ormance-based grants for th preneurship Based Selection l ntation e Entrepreneurial Support Or ganizations (ESOs) RW-RISA-317480-CS-QCBS ( 2.3) / Recruitment of the con Digital Public Service Deliver Quality And Cost- Open - Internationa COFN / C2100 Post 600,000.00 0.00 Canceled 2022-12-15 2023-01-05 2023-02-18 2023-03-18 2023-04-17 2023-05-22 2023-06-26 2023-12-23 sulting firm for development y Based Selection l of e-parliament system Page 3 RW-RISA-317485-CS-QCBS ( 2.3) / Recruitment of the con Digital Public Service Deliver Quality And Cost- Open - Internationa COFN / C2100 Post 400,000.00 0.00 Canceled 2022-12-15 2023-01-05 2023-02-18 2023-03-18 2023-04-17 2023-05-22 2023-06-26 2024-06-25 sulting firm for development y Based Selection l of the unified business regist ry system RW-RISA-317489-CS-QCBS ( 2.1) / consultancy services in Digital Public Service Deliver Quality And Cost- Open - Internationa Under Implement COFN / C2100 Post 250,000.00 0.00 2022-10-20 2022-10-23 2022-11-10 2022-12-24 2023-02-20 2023-01-21 2023-03-21 2023-02-20 2023-04-25 2023-03-27 2023-05-01 2023-10-28 support of upgrading the nati y Based Selection l ation onal public key infrastructure (NPKI) RW-RISA-309972-CS-QCBS-( 3.2) / Technical assistance to develop a sustainable operati Digital Innovation and Entre Quality And Cost- Open - Internationa Under Implement ng model for RCA and develo COFN / C2100 Post 200,000.00 0.00 2022-03-17 2022-12-20 2022-04-07 2022-06-22 2022-07-20 2022-08-19 2022-09-23 2022-10-28 2023-04-26 preneurship Based Selection l ation pment of bidding documents for RCA scale up intervention s and performance based ad vanced digital skills bootcam ps RW-RISA-321141-CS-CQS (3. 1) / Technical assistance to d Digital Innovation and Entre Consultant Qualifi Open - Internationa Under Implement COFN / C2100 Post 250,000.00 0.00 2021-08-21 2022-12-20 2021-11-09 2022-04-09 2022-05-09 2022-06-16 2022-09-09 evelop early-stage financing preneurship cation Selection l ation mechanisms for innovative t echnology startups RW-RISA-317391-CS-QCBS ( 4) / Project management sup Quality And Cost- Open - Internationa Pending Impleme COFN / C2100 Project Management Post 250,000.00 0.00 2022-10-30 2022-11-20 2023-01-03 2023-01-31 2023-03-02 2023-04-06 2023-05-11 2024-05-10 port for the implementation o Based Selection l ntation f the Digital Acceleration Proj ect (4) RW-RISA-317389-CS-QCBS ( 2.4) / Consultancy services to Digital Public Service Deliver Quality And Cost- Open - Internationa Pending Impleme develop and deliver training COFN / C2100 Post 200,000.00 0.00 2022-10-30 2022-11-20 2023-01-03 2023-01-31 2023-03-02 2023-04-06 2023-05-11 2023-11-07 y Based Selection l ntation programs in cybersecurity for the investigators, prosecutor s, and judges RW-RISA-325289-CS-QCBS(2 .2) / Consultancy services to support the detailed Technic Digital Innovation and Entre Quality And Cost- Open - Internationa COFN / C2100 Post 400,000.00 0.00 Canceled 2023-01-16 2022-11-23 2023-02-06 2023-03-13 2023-04-10 2023-05-10 2023-06-14 2023-07-19 2023-11-16 al and Organizational Design preneurship Based Selection l for the Establishment of a Ce ntralized and Collaborative G overnment Data Hub RW-RISA-325290-CS-QCBS(2 .2) / Consulting firm for Devel Digital Innovation and Entre Quality And Cost- Open - Internationa COFN / C2100 Post 1,500,000.00 0.00 Canceled 2023-01-16 2023-02-06 2023-03-13 2023-04-10 2023-05-10 2023-06-14 2023-07-19 2023-11-16 opment of a Centralized elect preneurship Based Selection l ronic archiving system RW-RISA-309837-CS-QCBS-( 2.2) / Consulting firm for Dev elopment of an interoperabili Digital Innovation and Entre Quality And Cost- Open - Internationa COFN / C2100 Post 400,000.00 0.00 Canceled 2022-08-15 2022-09-05 2022-10-12 2022-11-11 2022-11-25 2022-12-23 2023-01-27 2023-01-28 ty framework for the govern preneurship Based Selection l ment data hub, data governa nce and work processes for t he data hub RW-RISA-309827-CS-QCBS-( 2.2) / Consulting firm for con Digital Innovation and Entre Quality And Cost- Open - Internationa ducting Feasibility Study for t COFN / C2100 Post 350,000.00 0.00 Canceled 2022-12-02 2022-12-23 2023-01-13 2023-02-12 2023-02-26 2023-03-19 2023-04-23 2023-04-24 preneurship Based Selection l he Establishment of the Rwa nda Government Data Hub RW-RISA-325654-CS-QCBS ( 2.4) / Consultancy services to Digital Public Service Deliver Quality And Cost- Open - Internationa Under Implement COFN / C2100 Post 250,000.00 0.00 2022-11-18 2023-04-05 2022-12-09 2023-01-22 2023-02-19 2023-03-21 2023-04-25 2023-05-30 2023-06-17 develop and deliver training y Based Selection l ation program on conducting cyber risk assessment RW-RISA-325657-CS-QCBS ( 2.4) / Consultancy services to Digital Public Service Deliver Quality And Cost- Open - Internationa Pending Impleme COFN / C2100 Post 250,000.00 0.00 2022-11-18 2022-12-09 2023-01-22 2023-02-19 2023-03-21 2023-04-25 2023-05-30 2023-11-26 develop cybersecurity trainin y Based Selection l ntation g programs for red & blue te ams RW-RISA-328515-CS-QCBS ( 2.2) / consultancy services to develop a national geospatial Digital Public Service Deliver Quality And Cost- Open - Internationa Under Implement COFN / C2100 Post 250,000.00 0.00 2022-12-05 2022-11-29 2022-12-26 2023-02-08 2023-03-10 2023-03-31 2023-05-05 2023-06-09 2023-12-06 policy and strategy, and deta y Based Selection l ation iled technical design and imp lementation plan for the geos patial data hub RW-RISA-317394-CS-QCBS ( 1.4) / Develop cost-sharing m odels for passive telecommu Quality And Cost- Open - Internationa Under Implement COFN / C2100 Digital Access and Inclusion Post 250,000.00 0.00 2022-12-05 2022-11-29 2022-12-26 2023-02-08 2023-03-08 2023-04-07 2023-05-12 2023-06-16 2023-12-13 nication base station infrastr Based Selection l ation ucture, and fibre optic infrast ructure and develop their rel ated regulatory instruments RW-RISA-329699-CS-QCBS(2 .3) / Consulting project and p Digital Public Service Deliver Quality And Cost- Open - Internationa roduct management firm to c COFN / C2100 Post 864,000.00 0.00 Canceled 2023-02-28 2023-03-05 2023-03-21 2023-04-25 2023-05-23 2023-06-13 2023-07-18 2023-08-22 2024-08-21 y Based Selection l oordinate and manage the i mplementation of Governme nt e-Services platform RW-RISA-329703-CS-QCBS(2 .3) / Consulting firm to devel Digital Public Service Deliver Quality And Cost- Open - Internationa op the Government e-Service COFN / C2100 Post 1,750,000.00 0.00 Canceled 2023-02-28 2023-03-21 2023-04-25 2023-05-23 2023-06-13 2023-07-18 2023-08-22 2024-08-21 y Based Selection l s low-code platform and desi gn the infrastructure architec ture RW-RISA-329710-CS-QCBS(2 .3) / Consulting firm to desig Digital Public Service Deliver Quality And Cost- Open - Internationa Under Implement n and support the security op COFN / C2100 Post 360,000.00 0.00 2023-02-28 2023-05-10 2023-03-21 2023-04-25 2023-05-23 2023-06-13 2023-07-18 2023-08-22 2024-02-18 y Based Selection l ation timization of the Government e-Services low-code platform . RW-RISA-329757-CS-QCBS(2 .1) / Tender to hire of a cons ulting firm to serve as Syste Digital Public Service Deliver Quality And Cost- Open - Internationa ms Architect and Technical a COFN / C2100 Prior 2,500,000.00 0.00 Canceled 2022-12-30 2023-02-12 2023-01-20 2023-02-24 2023-03-24 2023-04-14 2023-05-19 2023-06-23 2024-06-22 y Based Selection l dvisers to help the Governm ent of Rwanda ensure a succ essful implementation of the envisioned Single Digital Iden tity (SDID). RW-RISA-329715-CS-QCBS(2 .3) / Hiring a consulting firm t o onboard 800 new services Digital Public Service Deliver Quality And Cost- Open - Internationa Pending Impleme COFN / C2100 Post 1,400,000.00 0.00 2023-04-30 2023-05-21 2023-06-25 2023-07-23 2023-08-13 2023-09-17 2023-10-22 2024-04-19 on the Government e-Service y Based Selection l ntation s low-code platform and prov ide training to 10,000 users. Page 4 RW-RISA-329691-CS-QCBS(2 .3) / Hiring a consulting firm t Digital Public Service Deliver Quality And Cost- Open - Internationa o develop governance frame COFN / C2100 Post 300,000.00 0.00 Canceled 2023-01-31 2023-02-21 2023-03-28 2023-04-25 2023-05-16 2023-06-20 2023-07-25 2023-12-22 y Based Selection l work, privacy, and security m anagement for health data s haring. RW-RISA-317483-CS-QCBS / Recruitment of the consultin Digital Public Service Deliver Quality And Cost- Open - Internationa COFN / C2100 Post 400,000.00 0.00 Canceled 2022-12-15 2023-01-05 2023-02-18 2023-03-18 2023-04-17 2023-05-22 2023-06-26 2024-06-25 g firm for development of bui y Based Selection l lding permit management inf ormation system RW-RISA-325175-CS-QCBS(2 .4) / Technical assistance to s Digital Public Service Deliver Quality And Cost- Open - Internationa Pending Impleme COFN / C2100 Post 250,000.00 0.00 2023-01-06 2023-01-27 2023-03-12 2023-04-09 2023-05-09 2023-06-13 2023-07-18 2024-08-16 upport cybersecurity awaren y Based Selection l ntation ess & communication service s RW-RISA-309917-CS-QCBS-( 3.1) / Technical Assistance to Digital Innovation and Entre Quality And Cost- Open - Internationa Pending Impleme COFN / C2100 Post 200,000.00 0.00 2022-08-26 2022-09-16 2022-10-14 2022-11-13 2022-11-27 2022-12-25 2023-01-29 2023-07-28 develop the strategy for the I preneurship Based Selection l ntation nnovation Agency RW-RISA-345915-CS-QCBS ( 2.4) / Consultancy Services t Digital Public Service Deliver Quality And Cost- Pending Impleme COFN / C2100 Post Open - National 100,000.00 0.00 2023-03-10 2023-03-31 2023-05-14 2023-06-11 2023-07-11 2023-08-15 2023-09-19 2024-03-17 o Develop and Deliver Traini y Based Selection ntation ng Programs on Data Protecti on RW-RISA-309818-CS-QCBS-( Quality And Cost- Open - Internationa Pending Impleme 1.4) / Technical Assistance in COFN / C2100 Digital Access and Inclusion Post 200,000.00 0.00 2022-10-05 2022-10-26 2022-11-23 2022-12-23 2023-01-06 2023-01-27 2023-03-03 2023-03-21 Based Selection l ntation the development of 5G road map technology RW-RISA-317486-CS-QCBS ( 1.4) / Preparatory support an Quality And Cost- Open - Internationa Pending Impleme COFN / C2100 Digital Access and Inclusion Post 200,000.00 0.00 2022-11-30 2022-12-21 2023-02-03 2023-03-03 2023-04-02 2023-05-07 2023-06-11 2023-09-09 d technical assistance to eval Based Selection l ntation uate impact of number porta bility RW-RISA-346020-CS-QCBS(3 .1) / Selection of consultancy Digital Innovation and Entre Quality And Cost- Open - Internationa Pending Impleme firm for Training and capacity COFN / C2100 Post 150,000.00 0.00 2023-04-19 2023-05-10 2023-06-23 2023-07-21 2023-08-20 2023-09-24 2023-10-29 2024-02-26 preneurship Based Selection l ntation building for angel investors a nd / staff of fund managers RW-RISA-346088-CS-QCBS(2 .2) / Consultancy services to support the detailed Technic Digital Public Service Deliver Quality And Cost- Open - Internationa Pending Impleme COFN / C2100 Post 400,000.00 0.00 2023-01-16 2023-02-06 2023-03-22 2023-04-19 2023-05-19 2023-06-23 2023-07-28 2023-11-25 al and Organizational Design y Based Selection l ntation for the Establishment of a Ce ntralized and Collaborative G overnment Data Hub RW-RISA-346075-CS-QCBS(2 Digital Public Service Deliver Quality And Cost- Open - Internationa Under Implement .4) / Development of Data Pr COFN / C2100 Post 300,000.00 0.00 2022-09-02 2023-03-28 2022-09-23 2022-11-06 2022-12-04 2023-01-03 2023-02-07 2023-03-14 2023-09-10 y Based Selection l ation otection office 5-year strateg ic plan RW-RISA-346081-CS-QCBS(3 .1) / TA for entrepreneurial e cosystem market assessmen Digital Innovation and Entre Quality And Cost- Open - Internationa Pending Impleme t, ecosystem mapping and d COFN / C2100 Post 90,000.00 0.00 2021-09-04 2021-09-25 2021-11-08 2021-12-06 2022-01-05 2022-02-09 2022-03-16 2022-07-14 preneurship Based Selection l ntation evelopment of tender docum ents for ESO support and the international acceleration pro gram RW-RISA-346072-CS-QCBS(2 .1) / Tender to hire of a cons ulting firm to serve as Syste Digital Public Service Deliver Quality And Cost- Open - Internationa Pending Impleme ms Architect and Technical a COFN / C2100 Post 1,000,000.00 0.00 2023-02-12 2023-03-05 2023-04-18 2023-05-16 2023-06-15 2023-07-20 2023-08-24 2024-08-23 y Based Selection l ntation dvisers to help the Governm ent of Rwanda ensure a succ essful implementation of the envisioned Single Digital Iden tity (SDID). RW-RISA-358181-CS-QCBS(3 .1) / Consultancy service for Digital Innovation and Entre Quality And Cost- Under Implement community management and COFN / C2100 Post Open - National 200,000.00 0.00 2023-06-21 2023-05-05 2023-07-12 2023-08-25 2023-09-22 2023-10-22 2023-11-26 2023-12-31 2025-12-30 preneurship Based Selection ation content development for the digital ecosystem manageme nt tool RW-RISA-358182-CS-QCBS(3 .1) / Technical assistance for the design, development, de ployment of digital ecosyste Digital Innovation and Entre Quality And Cost- Pending Impleme m management tools (functi COFN / C2100 Post Open - National 200,000.00 0.00 2023-06-21 2023-07-12 2023-08-25 2023-09-22 2023-10-22 2023-11-26 2023-12-31 2025-12-30 preneurship Based Selection ntation onalities include mapping, vi sualization, ecosystem user a ccounts, analytics, chatbot fu nctionality, connections to m ultiple APIs plus other admin an RW-RISA-362423-CS-QCBS / Technical assistance to asses Digital Public Service Deliver Quality And Cost- Open - Internationa Under Implement COFN / C2100 Post 500,000.00 0.00 2023-05-29 2023-06-10 2023-06-19 2023-08-02 2023-08-30 2023-09-29 2023-11-03 2023-12-08 2024-10-03 s the digital readiness of Met y Based Selection l ation eo Rwanda and develop a dig italization roadmap RW-RISA-317376-CS-QCBS ( 2.4) / Conduct training needs assessment and delivery in p Digital Public Service Deliver Quality And Cost- Open - Internationa hases for data protection key COFN / C2100 Post 300,000.00 0.00 Canceled 2022-09-30 2022-10-21 2022-12-04 2023-01-01 2023-01-31 2023-03-07 2023-04-11 2023-04-29 y Based Selection l groups, including DPO staff, prosecutors and judicial offic ers, data protection officers i n the public and private sect or RW-RISA-320655-CS-QCBS ( 2.4) / Consultancy services to develop and deliver training Digital Public Service Deliver Quality And Cost- Open - Internationa COFN / C2100 Post 300,000.00 0.00 Canceled 2022-11-25 2022-12-16 2023-01-29 2023-02-26 2023-03-28 2023-05-02 2023-06-06 2023-12-03 programs in cybersecurity for y Based Selection l key stakeholders and decisio n-makers in the public sector INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 5 RW-RISA-309912-CS-INDV (3 .1) / Recruitment of technical Digital Public Service Deliver Individual Consult Open - Internationa Pending Impleme advisors / experts to provide COFN / C2100 Post 150,000.00 0.00 2022-08-26 2022-09-28 2022-10-19 2022-11-23 2023-05-22 y ant Selection l ntation dedicated internal support to implement the innovation pol icy and strategy RW-RISA-309975-CS-INDV-(4 Individual Consult Under Implement COFN / C2100 Project Management Post Open - National 60,000.00 0.00 2022-09-13 2022-10-12 2022-10-16 2022-11-06 2022-12-11 2023-12-11 ) / Legal Expert – RISA SPIU ant Selection ation RW-RISA-309840-CS-INDV-(2 Individual Consult Open - Internationa Under Implement .4) / Hiring a Data Protection COFN / C2100 Project Management Post 120,000.00 0.00 2022-04-10 2022-10-12 2022-10-04 2022-10-18 2022-11-15 2023-11-15 ant Selection l ation & Privacy Expert RW-RISA-310013-CS-INDV-(4 Individual Consult Under Implement ) / Monitoring and Evaluation COFN / C2100 Project Management Post Open - National 30,000.00 0.00 2021-08-20 2022-10-16 2022-07-05 2022-07-26 2022-08-29 2023-08-29 ant Selection ation Expert – RISA SPIU RW-RISA-310205-CS-INDV-(4 Individual Consult COFN / C2100 Project Management Post Limited 22,920.00 0.00 Signed 2022-09-29 2022-10-12 2022-10-04 2022-10-25 2022-10-18 2022-12-06 2022-11-08 2023-11-08 ) / Project accountant – RISA ant Selection SPIU RW-RISA-313309-CS-INDV-(4 ) / Tender to hire an Environ Individual Consult Pending Impleme COFN / C2100 Project Management Post Open - National 21,157.00 0.00 2021-04-02 2021-04-11 2021-04-12 2021-05-04 2022-08-02 mental and Social Safeguard ant Selection ntation s Framework Expert RW-RISA-310206-CS-INDV-(4 Individual Consult Under Implement COFN / C2100 Project Management Post Open - National 98,824.00 0.00 2021-07-20 2022-10-16 2021-07-29 2021-07-30 2021-08-01 2024-07-31 ) / Coordinator-SPIU-RISA ant Selection ation RW-RISA-309980-CS-INDV-(4 Individual Consult Under Implement COFN / C2100 Project Management Post Open - National 53,648.00 0.00 2021-10-11 2022-10-16 2022-07-29 2022-08-06 2022-08-19 2022-08-30 2022-09-14 2023-09-16 ) / Procurement Officer – RIS ant Selection ation A SPIU RW-RISA-310215-CS-INDV-(4 Individual Consult Under Implement COFN / C2100 Project Management Post Open - National 60,000.00 0.00 2021-08-20 2022-10-16 2022-02-11 2022-02-18 2022-03-18 2023-03-18 ) / Financial Management Sp ant Selection ation ecialist RW-RISA-317853-CS-INDV (4 ) / Hiring of an ESF expert to Individual Consult Pending Impleme draft a project-related Resett COFN / C2100 Project Management Post Open - National 40,000.00 0.00 2021-04-20 2021-05-08 2021-05-10 2021-05-20 2021-07-19 ant Selection ntation lement Policy Framework and Environment Social and Com mitment Plan RW-RISA-309976-CS-INDV-(4 Individual Consult Under Implement COFN / C2100 Project Management Post Open - National 90,000.00 0.00 2022-04-13 2022-10-12 2022-10-04 2022-10-25 2022-11-29 2023-11-29 ) / Technical Advisor – RISA S ant Selection ation PIU RW-RISA-310014-CS-INDV-(4 Individual Consult Under Implement ) / Digital Innovation Eco-Syst COFN / C2100 Project Management Post Open - National 79,059.00 0.00 2022-01-04 2022-10-16 2022-10-01 2022-10-22 2022-11-26 2023-11-26 ant Selection ation em Expert – RISA SPIU RW-RISA-310212-CS-INDV-(4 Individual Consult Under Implement ) / Digital Platforms and Inter COFN / C2100 Project Management Post Open - National 80,000.00 0.00 2021-08-20 2022-10-16 2022-04-21 2022-05-05 2022-06-09 2023-06-09 ant Selection ation operability Expert RW-RISA-310211-CS-INDV (4 Individual Consult Under Implement COFN / C2100 Project Management Post Open - National 75,475.00 0.00 2021-07-01 2022-10-16 2021-07-20 2021-07-21 2021-08-01 2024-07-31 ) / Digital ID and Trust Servic ant Selection ation es Expert RW-RISA-310214-CS-INDV-(4 Individual Consult Under Implement COFN / C2100 Project Management Post Open - National 60,000.00 0.00 2022-01-16 2022-10-16 2022-03-03 2022-03-10 2022-03-18 2023-03-18 ) / Procurement Specialist RIS ant Selection ation A SPIU RW-RISA-310296-CS-INDV-(4 ) / Hire of an ESF expert to dr aft a project-related Environ Individual Consult Pending Impleme COFN / C2100 Project Management Post Open - National 33,000.00 0.00 2021-04-20 2021-05-09 2021-05-10 2021-05-20 2021-07-19 mental and Social Manageme ant Selection ntation nt Framework, Stakeholder E ngagement Plan and Labor M anagement Procedure RW-RISA-309983-CS-INDV-(4 Individual Consult Under Implement COFN / C2100 Project Management Post Open - National 80,000.00 0.00 2021-08-01 2022-10-16 2022-09-10 2022-02-23 2022-10-01 2022-10-27 2022-10-15 2023-10-29 ) / Cyber Security Expert – RI ant Selection ation SA SPIU RW-RISA-310210-CS-INDV-(4 Individual Consult Under Implement COFN / C2100 Project Management Post Open - National 53,648.00 0.00 2021-06-10 2022-10-16 2021-06-26 2021-06-27 2021-07-11 2024-07-10 ) / Digital Skills Expert ant Selection ation RW-RISA-310015-CS-INDV-(4 Individual Consult Under Implement ) / Digital Infrastructure and COFN / C2100 Project Management Post Open - National 80,000.00 0.00 2022-01-04 2022-10-16 2022-07-06 2022-07-27 2022-08-29 2023-08-29 ant Selection ation Broadband Access Expert – R ISA SPIU RW-RISA-310017-CS-INDV-(4 Individual Consult Under Implement ) / Social Safeguards Speciali COFN / C2100 Project Management Post Open - National 30,000.00 0.00 2022-10-28 2022-10-12 2022-12-16 2023-01-06 2023-02-10 2024-01-31 ant Selection ation st – RISA SPIU RW-RISA-310016-CS-INDV-(4 Individual Consult ) / Environmental Safeguards COFN / C2100 Project Management Post Limited 53,648.00 0.00 Signed 2022-09-29 2022-10-16 2022-10-04 2022-11-16 2022-10-14 2022-12-22 2022-10-28 2023-10-28 ant Selection Specialist- RISA SPIU RW-RISA-340884-CS-INDV (2 .4) / Individual Data Protectio n and Privacy Consultant to p Digital Public Service Deliver Individual Consult Open - Internationa Under Implement COFN / C2100 Post 100,000.00 0.00 2023-03-10 2023-02-19 2023-04-28 2023-05-19 2023-06-23 2024-06-22 rovide Technical Assistance o y ant Selection l ation n Legal Affairs and Complian ce for the Data Protection Off ice RW-RISA-340887-CS-INDV (2 .4) / Individual Data Protectio Digital Public Service Deliver Individual Consult Open - Internationa Under Implement n and Privacy Consultant to p COFN / C2100 Post 100,000.00 0.00 2023-03-24 2023-02-19 2023-05-12 2023-06-02 2023-07-07 2024-07-06 y ant Selection l ation rovide Technical Assistance o n Technology & Innovation fo r the Data Protection Office RW-RISA-317478-CS-INDV (1 .4) / Hiring of Two (2) Mobile and Fixed Quality of Service Individual Consult Under Implement COFN / C2100 Digital Access and Inclusion Post Limited 52,800.00 0.00 2023-02-28 2023-03-14 2023-03-05 2023-03-26 2023-04-30 2024-04-29 Network Engineers (Individua ant Selection ation l Consultants) for the Rwand a Utilities Regulatory Authorit y RW-RISA-351852-CS-INDV (2 Digital Public Service Deliver Individual Consult Open - Internationa Under Implement .3) / Hiring a senior System A COFN / C2100 Post 138,000.00 0.00 2023-04-16 2023-05-15 2023-06-04 2023-06-25 2023-07-30 2025-01-20 y ant Selection l ation rchitect consultant RW-RISA-351857-CS-INDV (2 Digital Public Service Deliver Individual Consult Pending Impleme .3) / Hiring a senior Procurem COFN / C2100 Post Open - National 60,000.00 0.00 2023-04-20 2023-06-08 2023-06-29 2023-08-03 2025-01-24 y ant Selection ntation ent consultant Page 6 RW-RISA-351859-CS-INDV (2 Digital Public Service Deliver Individual Consult Open - Internationa Pending Impleme .3) / Hiring a senior Business COFN / C2100 Post 96,000.00 0.00 2023-04-24 2023-06-12 2023-07-03 2023-08-07 2025-01-28 y ant Selection l ntation Analyst consultant RW-RISA-358160-CS-INDV(2. 3) / RECRUITMENT OF A SOFT Digital Public Service Deliver Individual Consult Under Implement COFN / C2100 Post Open - National 144,000.00 0.00 2023-06-21 2023-05-06 2023-08-09 2023-08-30 2023-10-04 2025-10-03 WARE ARCHITECT CONSULTA y ant Selection ation NT FOR THE RDAP PROJECT A T RISA RW-RISA-358161-CS-INDV(2. 3) / RECRUITMENT OF SIX(6)S Digital Public Service Deliver Individual Consult Under Implement COFN / C2100 Prior Open - National 720,000.00 0.00 2023-06-21 2023-05-16 2023-08-09 2023-08-30 2023-10-04 2025-10-03 OFTWARE DEVELOPERS CON y ant Selection ation SULTANTS FOR THE RDAP PR OJECT AT RISA RW-RISA-358164-CS-INDV(2. 3) / RECRUITMENT OF A PROJ ECT DIRECTOR CONSULTANT Digital Public Service Deliver Individual Consult Pending Impleme COFN / C2100 Post Open - National 192,000.00 0.00 2023-06-21 2023-08-09 2023-08-30 2023-10-04 2025-10-03 TO COORDINATE THE MASS S y ant Selection ntation ERVICE DIGITIZATION PROJEC T FOR THE IREMBO UPGRADE PROJECT RW-RISA-358165-CS-INDV(2. 3) / RECRUITMENT OF A SENI OR PROJECT MANAGER CONS Digital Public Service Deliver Individual Consult Pending Impleme ULTANT TO COORDINATE TH COFN / C2100 Post Open - National 120,000.00 0.00 2023-06-21 2023-08-09 2023-08-30 2023-10-04 2025-10-03 y ant Selection ntation E IMPLEMENTATION OF THE L OW-CODE PLATFORM DEVEL OPMENT FOR THE IREMBO UP GRADE PROJECT RW-RISA-358169-CS-INDV(2. 3) / RECRUITMENT OF A SENI OR PROJECT MANAGER CONS Digital Public Service Deliver Individual Consult Pending Impleme COFN / C2100 Post Open - National 120,000.00 0.00 2023-06-21 2023-08-09 2023-08-30 2023-10-04 2025-10-03 ULTANT TO COORDINATE TH y ant Selection ntation E IMPLEMENTATION OF INSTI TUTIONS API INTEGRATION F OR THE IREMBO UPGRADE P ROJECT RW-RISA-358171-CS-INDV(2. 3) / RECRUITMENT OF A SENI OR PROJECT MANAGER CONS Digital Public Service Deliver Individual Consult Pending Impleme COFN / C2100 Post Open - National 120,000.00 0.00 2023-06-21 2023-08-09 2023-08-30 2023-10-04 2025-10-03 ULTANT TO COORDINATE TH y ant Selection ntation E INFRASTRUCTURE SUPPLY AND INSTALLATION FOR THE IREMBO UPGRADE PROJECT RW-RISA-358173-CS-INDV(2. 3) / RECRUITMENT OF A PROJ ECT MANAGER CONSULTANT Digital Public Service Deliver Individual Consult Pending Impleme COFN / C2100 Post Open - National 96,000.00 0.00 2023-06-21 2023-08-09 2023-08-30 2023-10-04 2025-10-03 TO COORDINATE THE ON-BO y ant Selection ntation ARDING OF NEW SERVICES F OR THE IREMBO UPGRADE P ROJECT RW-RISA-358174-CS-INDV(2. 3) / RECRUITMENT OF A PROJ ECT MANAGER CONSULTANT Digital Public Service Deliver Individual Consult Pending Impleme COFN / C2100 Post Open - National 96,000.00 0.00 2023-06-21 2023-08-09 2023-08-30 2023-10-04 2025-10-03 TO COORDINATE THE CAPACI y ant Selection ntation TY BUILDING OF USERS FOR THE IREMBO UPGRADE PROJE CT RW-RISA-358176-CS-INDV(2. 3) / RECRUITMENT OF A SENI OR PROJECT MANAGER CONS Digital Public Service Deliver Individual Consult Pending Impleme COFN / C2100 Post Open - National 120,000.00 0.00 2023-06-21 2023-08-09 2023-08-30 2023-10-04 2025-10-03 ULTANT TO COORDINATE TH y ant Selection ntation E SECURITY OPTIMIZATION O F THE LOW-CODE PLATFORM FOR THE IREMBO UPGRADE P ROJECT RW-RISA-358185-CS-INDV(2. 4) / Tender to hire an individ Individual Consult Under Implement COFN / C2100 Project Management Post Open - National 70,000.00 0.00 2023-06-21 2023-05-10 2023-08-09 2023-08-30 2023-10-04 2024-10-03 ual consultant -program supp ant Selection ation ort Coordinator for the data p rotection office RW-RISA-317493-CS-INDV (1 .4) / Hiring 1 individual consu Individual Consult ltant for IT software support f COFN / C2100 Digital Access and Inclusion Post Open - National 26,400.00 0.00 Canceled 2022-10-30 2023-02-22 2022-12-18 2023-01-08 2023-02-12 2024-02-12 ant Selection or Quality of service monitori ng systems and tools for fixe d and mobile networks RW-RISA-317488-CS-INDV (1 .4) / Hiring 1 Project support Individual Consult Open - Internationa manager for Quality of servic COFN / C2100 Digital Access and Inclusion Post 56,400.00 0.00 Canceled 2022-10-30 2023-02-22 2022-12-18 2023-01-08 2023-02-12 2024-02-12 ant Selection l e monitoring systems and to ols for fixed and mobile netw orks Page 7 Plan de Passation de marchés I. Généralités 1. L'information sur le projet : Pays : Madagascar ; Emprunteur : République de Madagascar ; Nom de projet : Projet Filets Sociaux de Sécurité – Financement Additionnel (P160 544) ; Numéro du Crédit : D1450-MG ; Agence d’exécution du Projet : Unité Programme National de Nutrition Communautaire. 2. Date d’approbation du Plan de passation de marchés par la Banque : - ; Révision : - ; 3. Date de notification du Plan Général de Passation de marchés : - ; 4. Période couverte par le Plan de Passation de marchés : DOUZE (12) mois. II. Biens et Travaux et Services hors consultants 1. Seuil de Revue préalable : Les décisions de passation de marchés sujet aux revues préalables de la Banque comme indiqué dans le paragraphe 3.1 de l'Annexe II du Règlement de Passation des Marchés pour les Emprunteurs sollicitant le Financement de Projets d’Investissement (Juillet 2016) et sur la base de l'évaluation de la capacité de l'agence d’exécution : Seuil de Méthode de Passation de revue à Commentaires marchés priori (USD) Les montants 1 Biens : AOI/AON/UN/ED 2 000 000 estimatifs des marchés prévus 2 Travaux : AOI/AON/ED 10 000 000 sont au-dessous des seuils. Niveau de Services autres que 3 2 000 000 risque : consultants : AOI/AON/UN/ED « SUBSTANTIEL » 2. Pré-qualification (selon les dispositions des paragraphes 6.19 à 6.24 de la Section VI du Règlement de Passation des Marchés pour les Emprunteurs sollicitant le Financement de Projets d’Investissement (Juillet 2016)) : Non Applicable. 3. Procédures proposées pour les composantes CDD (selon le paragraphe. 6.52 et 6.53 de la Section VI du Règlement de Passation des Marchés pour les Emprunteurs sollicitant le Financement de Projets d’Investissement (Juillet 2016)) : Non Applicable 4. Référence (s’il y en a) au Manuel d’exécution du projet / Manuel de Passation de marchés : Manuels en cours de mise à jour 5. Tout autre arrangement spécial en passation de marchés : Non Applicable. 6. Allotissement de fournitures avec méthodes et calendrier : [Enumérer d’abord les allotissements qui nécessitent la revue préalable de la Banque, ensuite les autres allotissements] 1 2 3 4 5 6 7 8 9 Réf. No Description Contrat Approche/Méthod Revue de la Coût Pré- Préféren Date Commentaire e de sélection Banque (à estimatif qualificati ce prévue s priori / à (USD) on nationale d’ouverture posteriori) Oui / Non Oui / Non des soumission s Lot 1 : N°9 : Impression et Achevée multiplication de bulletins LIMITE 01 A.11 COT Post 12 000,00 NON NON 21-juin-18 Lot 2 : N°10 : en périodiques (02 numéros NATIONAL attente semestrielles) Maquette Acquisition outils de LIMITE Ordre de Service 03 A.11 COT Post 10 000,00 NON NON 13-mai-18 communication (Pagnes) NATIONAL signé Acquisition divers Pas encore LIMITE 04 A.17 équipements et mobiliers COT Post 5 000,00 NON NON 14-févr-19 lancée NATIONAL de bureau A programmer Acquisition de 293,2 SELECTION 1 475 246 Nouvelle activité 05 A.13 ED Post NON NON 12-févr-19 tonnes de Plumpy Sup DIRECTE ,46 PTA 2019 Acheminement vers LIMITE Nouvelle activité 06 A.13 Districts de 293,2 tonnes COT Post 77 644,55 NON NON 19-févr-19 NATIONAL PTA 2019 de Plumpy Sup Confection d’outils pour les sites : impression et LIMITE Nouvelle activité A.6.0 COT Post 11 812,50 NON NON 04-juin-19 livraison d’outils de NATIONAL PTA 2019 gestion : Registres Confection de plaques d'indication des sites et A.11.0 Supports de LIMITE Nouvelle activité COT Post 27 514,03 NON NON 04-juin-19 .1 communication : NATIONAL PTA 2019 Impression plaque, livrets et bulletins périodiques 1 2 3 4 5 6 7 8 9 Réf. No Description Contrat Approche/Méthod Revue de la Coût Pré- Préféren Date Commentaire e de sélection Banque (à estimatif qualificati ce prévue s priori / à (USD) on nationale d’ouverture posteriori) Oui / Non Oui / Non des soumission s Confection de Pagnes et A.11.0 T-shirt, Blouses pour LIMITE 17 578,13 Nouvelle activité .2 COT Post NON NON 04-juin-19 intervenants (Reny NATIONAL PTA 2019 mavitrika, …) Acquisition de matériels informatiques adaptés à l'actualisation du SIG et LIMITE Nouvelle activité A.14 COT Post 13 312,50 NON NON 04-juin-19 du développement du NATIONAL PTA 2019 Géoportail des données en ligne III. Sélection de consultants 1. Seuil de Revue Préalable : Décisions de sélection sujet à la revue préalable de la Banque comme indiqué dans le paragraphe 3 de l'Annexe II du Règlement de Passation des Marchés pour les Emprunteurs sollicitant le Financement de Projets d’Investissement (Juillet 2016) : Méthode de sélection Seuil de Commentaires revue à priori (USD) 1. Méthode compétitive (firmes) 1 000 000 Les montants 2. Entente directe (firmes) 1 000 000 estimatifs des 3. Méthode compétitive (Consultant 300 000 contrats prévus individuel) sont au-dessous 4. Entente directe (Consultant 300 000 des seuils. individuel) Niveau de risque : « SUBSTANTIEL » 2. Liste restreinte composée entièrement de consultants nationaux : Selon les dispositions du paragraphe 7.25 de l'Annexe II du Règlement de Passation des Marchés pour les Emprunteurs sollicitant le Financement de Projets d’Investissement (Juillet 2016), la liste restreinte de consultants peut comporter entièrement des consultants nationaux pour les cas suivants : Catégorie de Montant estimatif consultant 1. Firmes Inférieur à USD 300 000 2. Consultants individuels Inférieur à USD 100 000 3. Tout autre arrangement spécial de Sélection de consultants : Non applicable 4. Tâches de consultation avec des méthodes de sélection et calendrier 1 2 3 4 5 6 7 Réf. No Description des missions Approche/Méth Revue de la Coût Date Commentaires ode de Banque (à estimatif prévue de sélection priori / à (USD) soumission posteriori) s des proposition s Consultant en charge de la maintenance Nouvelle activité PTA 01 A.14 ED ED Post 12 000,00 29-avril-19 du système Géoportail 2019 Consultants chargés de saisie des Nouvelle activité PTA 02 A.16 Registres des sites ED ED Post 34 321,33 20-mai-19 2019 Consultant Individuel en charge de Nouvelle activité PTA 03 B.2 l’élaboration de l’ICR INDV ED Post 5 000,00 21-mai-19 2019 IV. Activités de renforcement de capacités de l’Agence d’exécution avec calendrier 1. Dans cette section, les activités de renforcement de capacité acceptées (quelques articles pourraient être des recommandations de CPAR) sont énumérées avec le calendrier No. Résultats Coût Durée Date de Commentaires escomptés / estimatif estimative début Description de l’activité PROCUREMENT Madagascar : Improving Nutrition Outcomes using the Multiphase Programmatic Approach PLAN General Information Country: Madagascar Bank’s Approval Date of the Original Procurement Plan:2017-11-15 2023-06-06 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P160848 GPN Date: 2020-09-07 Project Name: Improving Nutrition Outcomes using the Multiphase Programmatic Approach Loan / Credit No: IDA / V0970, IDA / D2570 Community Nutrition National Program Unit Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process S Draft Pre-qualificatio Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Comple Description Component Review Type Method Amount (U ount (US$ and Recommendatio Signed Contract o. h cess (Y/N) isk ocument Type tatus n Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes tion S$) ) n for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned UPNNC 3 25 DC TRX / Trava ux d'extension du Bureau de Project Management, Capac Request for Quot Single Stage - One 2018-04-2 l'Unité de Coordination de Pr IDA / V0970 ity Building and Operations Post Limited 45,000.00 34,783.92 Completed 2017-11-08 2017-11-20 2017-12-27 2018-03-27 ations Envelope 6 ojet - Ministère de la Santé P Support ublique à Ambohimiandra MG-UPNNC-233827-CW-RFB / Sélection d'entreprise pour Request for Bids - Project Management, Capac les travaux de réhabilitation, Single Stage - One Small Works SPD 2022-04-3 IDA / D2570 ity Building and Operations Post Request for Bids Open - National 450,000.00 0.00 Canceled 2021-08-03 2021-08-08 2021-09-20 2021-10-04 2021-11-01 d'extension et de surélévati Envelope (1 envelope proc 0 Support on d'un bâtiment public pour ess) servir de bureau à l'UPNNC e t l'ONN Request for Bids - MG-UPNNC-254375-CW-RFB Project Management, Capac Single Stage - One Works French Civ 2023-03-0 / Travaux de réhabilitation d IDA / D2570 ity Building and Operations Post Request for Bids Open - National 760,000.00 0.00 Canceled 2022-12-15 2023-02-02 2022-12-22 2023-02-02 2023-01-21 2023-02-17 2023-01-28 2023-02-14 Envelope il Law (French) SP 2 u bâtiment pour bureau de l' Support D ONN/UPNNC GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualificatio Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendatio Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus n Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes n for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual UPNNC 2 1 ET 2 2 UNOPS / Acquisition de divers matéri els informatiques, bureautiq Strengthen capacity to man UN Agencies (Dir ues et de communication (2 IDA / V0970 age and deliver the RMCHN Post Direct 272,000.00 316,648.00 Signed 2017-11-10 2017-11-15 2017-12-21 2017-12-27 2018-04-12 2018-03-27 ect) 3 Ordinateurs de bureau ave minimum package c onduleurs, 28 ordinateurs portables, 22 photocopieuse s, 22 vidéoprojecteurs et 92 tablettes UPNNC 2 1 ET 2 3 AON / Ac quisition kits de communicat Strengthen capacity to man Single Stage - One ion pour le Ministère de la S IDA / V0970 age and deliver the RMCHN Post Request for Bids Open - National 166,000.00 92,426.63 Completed 2017-11-12 2018-02-07 2017-11-17 2017-12-15 2018-03-07 2018-01-12 2018-05-22 2018-02-09 2018-06-13 2018-04-10 2018-09-05 Envelope anté Publique : Kit vidéocon minimum package férence et kit central de com munication Strengthen capacity to man UPNNC 3 1 DC / Multiplicati Request for Quot Single Stage - One IDA / V0970 age and deliver the RMCHN Post Limited 86,000.00 2,961.47 Signed 2017-11-05 2018-01-18 2017-12-24 2018-03-23 2018-02-22 2018-05-18 on et diffusion de PNAN III ations Envelope minimum package UPNNC 3 2 AON / Acquisitio Strengthen capacity to man Single Stage - One n supports de diffusion de d IDA / V0970 age and deliver the RMCHN Post Request for Bids Open - National 245,000.00 63,185.88 Signed 2017-11-03 2018-01-27 2017-11-08 2017-12-06 2018-02-27 2018-01-03 2018-03-28 2018-01-31 2018-05-02 2018-04-01 Envelope ocument cadre minimum package PARN UPNNC 1 6 UNICEF / A Strengthen capacity to man cquisition de matériels et éq UN Agencies (Dir IDA / D2570 age and deliver the RMCHN Post Direct 900,000.00 620,630.00 Signed 2018-05-14 2018-06-07 2018-05-28 2018-06-07 2018-07-02 2018-06-20 2018-08-31 uipements pour la mise en p ect) minimum package lace des sites communautair es PARN UPNNC 16 27 UNOPS1 Scale up coverage and utiliz UN Agencies (Dir / Acquisition de motos pour l IDA / D2570 ation of the RMCHN minimu Post Direct 1,200,000.00 1,135,115.00 Signed 2018-05-07 2018-06-06 2018-05-21 2018-06-06 2018-07-02 2018-06-26 2018-09-30 ect) es Animateurs et ES auprès m package UNOPS PARN UPNNC 27 31 UNOPS2 Strengthen capacity to man / Acquisition de véhicules de UN Agencies (Dir IDA / D2570 age and deliver the RMCHN Post Direct 275,000.00 249,715.01 Signed 2018-05-07 2018-06-06 2018-05-21 2018-06-06 2018-07-02 2018-06-26 2018-09-30 supervision pour les ORN et ect) minimum package l'UPNNC auprès de l'UNOPS PARN UPNNC 24 27 31 UNO Scale up coverage and utiliz PS1 / Acquisition de matériel UN Agencies (Dir IDA / D2570 ation of the RMCHN minimu Post Direct 300,000.00 295,744.00 Signed 2018-05-07 2018-06-06 2018-05-21 2018-06-06 2018-07-02 2018-08-14 2018-09-30 s informatiques, bureautique ect) m package s et de communication aupr ès UNOPS PARN UPNNC 16 AON01 / Ac Strengthen capacity to man Single Stage - One quisition de radio destinés a IDA / D2570 age and deliver the RMCHN Post Request for Bids Open - National 100,000.00 63,982.54 Signed 2018-05-01 2018-08-25 2018-05-15 2018-06-12 2018-10-10 2018-06-26 2019-01-22 2018-07-17 2019-03-23 2018-09-15 2019-06-18 Envelope ux sites communautaires minimum package PARN UPNNC 1 6 SUPPORT Strengthen capacity to man COM / Confection supports d Single Stage - One IDA / D2570 age and deliver the RMCHN Post Request for Bids Open - National 200,000.00 153,223.74 Signed 2018-08-06 2018-08-25 2018-08-20 2018-09-17 2018-09-26 2018-10-01 2019-02-13 2018-10-22 2019-03-22 2018-12-21 e communication répartis en Envelope minimum package cinq (05) lots (Banderoles, T ee-shirts, Pagnes, ...) PARN UPNNC 1 6 SUPPORT COM2 / Impression et multip Strengthen capacity to man Request for Quot Single Stage - One lication divers supports de c IDA / D2570 age and deliver the RMCHN Post Limited 65,000.00 5,971.68 Signed 2018-09-02 2019-06-25 2018-10-21 2019-10-16 2018-12-20 ations Envelope ommunication répartis en tr minimum package ois (03) lots (Affiches, Guide s, Bulletins périodiques) PARN UPNNC 2 4 OUTILS DE Scale up coverage and utiliz GESTION / Impression et mul Request for Quot Single Stage - One IDA / D2570 ation of the RMCHN minimu Post Limited 70,000.00 26,344.31 Signed 2018-05-15 2019-01-07 2018-07-03 2019-01-31 2018-07-31 tiplication des outils de gesti ations Envelope m package on répartis en deux (02) lots (Registres) PARN UPNNC 3 1 MOB BURE Project Management, Capac Request for Quot Single Stage - One IDA / D2570 Post Limited 6,000.00 5,149.31 Signed 2018-05-27 2019-11-05 2018-07-15 2019-11-21 2018-08-14 AU / Acquisition de mobiliers ity Building and Operations ations Envelope de bureau Support PARN UPNNC 1 6 SUPPORT Strengthen capacity to man Request for Quot Single Stage - One COM3 / Confection et multipl IDA / D2570 age and deliver the RMCHN Post Limited 35,000.00 0.00 Canceled 2018-08-21 2018-10-16 2018-12-15 ations Envelope ication calendriers 2019 minimum package PARN UPNNC 1 6 BALANCES Strengthen capacity to man / Acquisition de balances pè Request for Quot Single Stage - One IDA / D2570 age and deliver the RMCHN Post Limited 100,000.00 0.00 Canceled 2018-05-22 2018-07-17 2018-09-15 se-personne destinées aux s ations Envelope minimum package ites communautaires MG-UPNNC-93276-GO-DIR / Scale up coverage and utiliz UN Agencies (Dir Acquisition de matériels des IDA / D2570 ation of the RMCHN minimu Post Direct 450,000.00 350,213.45 Signed 2018-12-29 2018-05-28 2018-12-30 2018-11-27 2019-01-09 2018-12-11 2019-07-08 ect) tinés aux sites (Pèse-person m package nes) MG-UPNNC-93277-GO-RFQ / Scale up coverage and utiliz Request for Quot Single Stage - One Acquisition de piles recharge IDA / D2570 ation of the RMCHN minimu Post Limited 60,000.00 0.00 Canceled 2019-01-17 2019-03-14 2019-05-28 ations Envelope ables pour les Pèse-personn m package e PARN UPNNC 11 LNS / Acqui Strengthen capacity to man sition de suppléments alime IDA / D2570 age and deliver the RMCHN Prior Direct Selection Direct 1,188,074.00 1,286,399.27 Signed 2019-01-10 2019-11-01 2019-01-17 2019-11-06 2019-02-14 2019-12-28 2020-02-09 ntaires LNS riches en protéin minimum package es et lipides pour les enfants 6 à 18 mois Page 1 PARN UPNNC 13 PLUMPY / A Strengthen capacity to man cquisition d'aliments thérap IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 935,299.00 794,644.66 Signed 2019-01-10 2019-01-29 2019-02-07 2019-01-28 2019-03-21 2019-02-14 2020-03-15 eutiques Plumpy Sup pour tr minimum package aiter le cas de MAM MG-UPNNC-1 1 06 02-OUTIL S COMM / Production et livra ison des Outils de communic Scale up coverage and utiliz Single Stage - One ation Institutionnelle repartis IDA / D2570 ation of the RMCHN minimu Post Request for Bids Open - National 160,000.00 0.00 Canceled 2019-07-01 2019-07-06 2019-08-05 2019-09-04 2019-09-25 2019-12-24 Envelope en 5 lots (Stylo flash, Stylo m package personnalisé- Affiche offre d e services, Blouse sans man che, Tee-shirts FAFY) MG-UPNNC-1 1 06 02-OUTIL S DE COMMUNICATI / Produc Scale up coverage and utiliz Request for Quot Single Stage - One tion et livraison des outils de IDA / D2570 ation of the RMCHN minimu Post Limited 10,000.00 2,232.12 Signed 2019-06-05 2019-02-27 2019-06-29 2019-05-02 2019-07-14 ations Envelope communication institutionne m package lle (Agenda et blocs note) MG-UPNNC-110602-OUTILS Scale up coverage and utiliz Request for Quot Single Stage - One COMM / Confection des plaq IDA / D2570 ation of the RMCHN minimu Post Limited 87,000.00 32,636.06 Signed 2019-06-13 2019-06-21 2019-07-07 2019-06-25 2019-09-05 ations Envelope ues pour les sites m package MG-UPNNC-2 1 01 04-DOCU MENT DE FORMATION / Trav Strengthen capacity to man aux d'impression des docum Request for Quot Single Stage - One IDA / D2570 age and deliver the RMCHN Post Limited 16,000.00 15,438.71 Signed 2019-06-06 2019-03-04 2019-06-28 2019-03-05 2019-07-08 ents de formation AC (docu ations Envelope minimum package ment formateur, document participant et courbes de cro issance) MG-UPNNC-154719-GO-DIR / Acquérir des matériels et é quipements informatiques, i mprimante multifonction, ta Strengthen capacity to man UN Agencies (Dir blettes pour les Animateurs IDA / D2570 age and deliver the RMCHN Post Direct 375,000.00 374,327.00 Signed 2020-02-24 2019-10-25 2020-03-02 2019-12-16 2020-03-23 2019-12-28 2020-09-19 ect) de la Région Bongolava et p minimum package our la communication institu tionnelle, matériels techniq ues pour la communication, matériels de communication MG-UPNNC-154727-GO-DIR Strengthen capacity to man / Acquérir un véhicule pour UN Agencies (Dir IDA / D2570 age and deliver the RMCHN Post Direct 177,626.00 374,327.00 Signed 2020-02-10 2019-10-25 2020-02-17 2019-10-16 2020-03-09 2019-12-28 2020-09-05 ORN Bongolava et des moto ect) minimum package s pour Animateurs et ES de la Région Bongolava MG-UPNNC-154750-GO-DIR Scale up coverage and utiliz / Acquérir des matériels ant UN Agencies (Dir IDA / D2570 ation of the RMCHN minimu Post 164,926.00 83,634.60 Signed 2020-02-24 2019-09-11 2020-03-02 2019-11-11 2020-03-09 2019-11-12 2020-09-05 hropométriques pour les site ect) m package s de la région Bongolava MG-UPNNC-154769-GO-RFB Strengthen capacity to man / Impression et multiplicatio Single Stage - One IDA / D2570 age and deliver the RMCHN Post Request for Bids Open - National 135,000.00 27,978.36 Completed 2020-02-24 2020-01-14 2020-03-02 2020-04-01 2020-02-06 2020-04-15 2020-02-14 2020-05-02 2020-04-23 2020-07-01 2020-06-06 n de des feuillets d'animatio Envelope minimum package n et des bâches alimentaires MG-UPNNC-156503-GO-RFP Strengthen capacity to man / IMPRESSION ET LIVRAISON Request for Propo Single Stage - Two IDA / D2570 age and deliver the RMCHN Post Limited 15,400.00 0.00 Canceled 2020-02-24 2020-03-02 2020-03-17 2020-03-31 2020-04-17 2020-10-14 DE DEPLIANTS GUIDE DE ME sals Envelope minimum package SSAGE ET AFFICHES REPART IS EN DEUX (02) LOTS MG-UPNNC-152791-GO-RFQ Strengthen capacity to man Request for Quot Single Stage - One / Acquérir des registres pour IDA / D2570 age and deliver the RMCHN Post Limited 4,297.00 0.00 Canceled 2020-03-02 2020-04-06 2020-05-19 ations Envelope les sites de la Région de Bon minimum package golava MG-UPNNC-174129-GO-DIR / Acquisition des aliments th Scale up coverage and utiliz érapeutiques Plumpy sup po IDA / D2570 ation of the RMCHN minimu Prior Direct Selection Direct 5,543,428.00 3,925,665.69 Signed 2020-08-03 2020-10-15 2020-08-10 2020-11-05 2020-10-07 2020-12-16 2021-04-05 ur les 7 régions ( Itasy, Vaki m package nakaratra, Amoron'i Mania, Haute Matsiatra, Bongolava, Anlamanga, Alaotra Mangor o) MG-UPNNC-173972-GO-DIR Scale up coverage and utiliz / Acquisition des supplément IDA / D2570 ation of the RMCHN minimu Post Direct Selection Direct 593,492.00 1,286,894.53 Signed 2020-08-03 2019-11-01 2020-08-17 2019-11-18 2020-10-14 2019-12-27 2021-04-12 s alimentaires LNS riches en m package protéeines et lipides pour la région Itasy MG-UPNNC-181784-GO-RFB Scale up coverage and utiliz Single Stage - One / Fourniture et livraison de 2 IDA / D2570 ation of the RMCHN minimu Post Request for Bids Open - National 73,000.00 59,981.37 Completed 2020-07-27 2020-06-24 2020-08-03 2020-09-02 2020-08-14 2020-09-17 2020-09-04 2020-10-04 2020-11-04 2020-12-03 2021-01-26 Envelope 440 Radios solaires pour les m package sites. MG-UPNNC-186046-GO-UN / Acquisition des matériels inf Strengthen capacity to man UN Agencies (Dir ormatiques pour les régions IDA / D2570 age and deliver the RMCHN Post Direct 24,500.00 0.00 Canceled 2020-09-01 2020-08-03 2020-09-08 2020-11-21 2022-05-15 ect) Analamanga et Alaotra Man minimum package goro (Lap top, Imprimante e t vidéo projecteur) MG-UPNNC-199566-GO-UN / Acquisition des mobiliers et Scale up coverage and utiliz UN Agencies (Dir des matériels pour sites : 10 IDA / D2570 ation of the RMCHN minimu Prior Direct 2,500,000.00 0.00 Canceled 2020-11-16 2020-12-16 2021-02-14 2021-05-15 ect) 622 Tables, 21 244 Chaises, m package kits de matériels de mesures anthropométriques MG-UPNNC-174121-GO-UN / Scale up coverage and utiliz Acquisition de 2 139 armoire UN Agencies (Dir IDA / D2570 ation of the RMCHN minimu Post Direct 400,000.00 0.00 Canceled 2020-07-27 2020-08-03 2020-08-03 2020-09-19 2022-03-13 s métalliques pour les région ect) m package s Analamanga et Alaotra Ma ngoro MG-UPNNC-173960-GO-UN / Strengthen capacity to man Acquisition de 366 tablettes UN Agencies (Dir IDA / D2570 age and deliver the RMCHN Post Direct 172,695.00 0.00 Canceled 2020-07-27 2020-08-03 2020-08-03 2020-08-06 2020-10-16 2022-04-09 pour les animateurs des régi ect) minimum package ons Analamange et Alaotra Mangoro MG-UPNNC-173975-GO-UN / Scale up coverage and utiliz Acquisition des Motos pour l UN Agencies (Dir IDA / D2570 ation of the RMCHN minimu Post Direct 1,064,452.00 0.00 Canceled 2020-07-27 2020-08-03 2020-08-03 2019-10-14 2020-09-14 2021-03-13 es régions Analamanga et Al ect) m package aotra Mangoro (Animateurs et ES) MG-UPNNC-174122-GO-UN / Strengthen capacity to man Acquisition de 02 véhicules UN Agencies (Dir IDA / D2570 age and deliver the RMCHN Post Direct 92,000.00 0.00 Canceled 2020-07-27 2020-08-03 2020-08-03 2020-08-06 2020-10-16 2022-04-09 4x4 tout terrain pour les régi ect) minimum package ons Analama,ga et Alaotra M angoro MG-UPNNC-154740-GO-RFQ Strengthen capacity to man Request for Quot Single Stage - One / Imprimer des documents d IDA / D2570 age and deliver the RMCHN Post Limited 345,287.00 56,046.16 Signed 2020-12-28 2020-09-25 2021-01-25 2021-02-04 2021-02-24 ations Envelope e formation PCIME minimum package MG-UPNNC-216420-GO-RFQ Project Management, Capac Request for Quot Single Stage - One / Acquisition de 05 Ordinate IDA / D2570 ity Building and Operations Post Limited 20,119.00 23,286.27 Signed 2021-03-08 2021-08-12 2021-04-12 2021-11-03 2021-05-12 2021-12-14 ations Envelope urs portables pour l'Entité d Support e Coordination MG-UPNNC-216421-GO-RFQ Project Management, Capac / Acquisition des consomptib Request for Quot Single Stage - One Pending Impl IDA / D2570 ity Building and Operations Post Limited 7,400.00 0.00 2021-03-01 2021-04-05 2021-05-05 les informatiques et access ations Envelope ementation Support oires pour l'Entité de Coordi nation MG-UPNNC-173973-GO-UN / Scale up coverage and utiliz Acquisition des mesures ant UN Agencies (Dir IDA / D2570 ation of the RMCHN minimu Prior Direct 3,505,727.00 0.00 Canceled 2020-07-27 2021-02-04 2020-08-03 2021-02-19 2020-08-25 2021-02-21 hropométriques pour les rég ect) m package ions Alaotra Mangoro et Anal amanga MG-UPNNC-154774-GO-DIR Scale up coverage and utiliz UN Agencies (Dir IDA / D2570 Post Direct 844,000.00 0.00 Canceled 2020-12-28 2021-01-04 2021-01-25 2021-07-24 / Acquérir des mobiliers pour ation of the RMCHN minimu ect) les sites m package Page 2 MG-UPNNC-181777-GO-UN / Scale up coverage and utiliz Acquisition des mobiliers po UN Agencies (Dir IDA / D2570 ation of the RMCHN minimu Post Direct 370,000.00 0.00 Canceled 2021-01-25 2021-02-01 2021-02-22 2021-08-21 ur site: ect) m package 10 622 Tables 21 244 Chaises MG-UPNNC-222708-GO-UN / Scale up coverage and utiliz Acquisition de 1 584 Armoir UN Agencies (Dir IDA / D2570 ation of the RMCHN minimu Post Direct 380,000.00 0.00 Canceled 2021-04-26 2021-06-15 2021-05-10 2022-12-02 2021-05-31 2021-11-27 es métalliques pour Analam ect) m package anga, Alaotra Mangoro, Bon golava MG-UPNNC-222198-GO-UN / Acquisition des matériels de Scale up coverage and utiliz UN Agencies (Dir mesures anthropométriques IDA / D2570 ation of the RMCHN minimu Post Direct 360,000.00 338,142.33 Signed 2021-03-22 2021-01-04 2021-04-05 2021-01-06 2021-05-10 2021-03-27 2021-11-06 ect) pour les régions Analamang m package a et Alaotra Mangoro MG-UPNNC-203413-GO-UN / Acquisition des matériels inf ormatiques (02 ordinateurs Scale up coverage and utiliz UN Agencies (Dir portables, 02 imprimantes IDA / D2570 ation of the RMCHN minimu Post Direct 145,000.00 0.00 Canceled 2021-01-01 2021-01-31 2021-04-03 2021-08-06 ect) multifonction, 02 vidéos proj m package ecteurs, 366 tablettes) pour les régions Analamanga et A laotra Mangoro MG-UPNNC-202074-GO-UN / Strengthen capacity to man UN Agencies (Dir Acquisition de matériels roul IDA / D2570 age and deliver the RMCHN Post Direct 1,156,450.00 0.00 Canceled 2021-01-01 2021-01-15 2021-02-26 2021-05-28 ect) ants : véhicules tout terrain minimum package et motos MG-UPNNC-222712-GO-UN / Acquisition de mobiliers pou Scale up coverage and utiliz UN Agencies (Dir r les sites des 7 régions: IDA / D2570 ation of the RMCHN minimu Post Direct 891,000.00 0.00 Canceled 2021-04-19 2021-05-03 2021-05-24 2021-11-20 ect) - 8 524 Tables m package - 17 048 Chaises MG-UPNNC-248082-GO-RFB Strengthen capacity to man Single Stage - One / Acquisition de 283 tablette IDA / D2570 age and deliver the RMCHN Post Request for Bids Open - National 302,286.00 53,501.86 Signed 2021-10-07 2021-09-24 2021-10-14 2021-10-12 2021-11-13 2021-10-28 2021-11-20 2021-11-25 2021-12-07 2021-12-22 2022-02-05 Envelope s et accessoires minimum package MG-UPNNC-254374-GO-RFB Strengthen capacity to man Single Stage - One / Acquisition de 04 véhicules IDA / D2570 age and deliver the RMCHN Post Request for Bids Limited 195,274.00 129,701.56 Signed 2021-09-13 2021-09-24 2021-11-09 2021-09-24 2021-11-24 2021-10-27 2021-12-01 2021-11-05 2021-12-15 2022-04-29 2022-06-13 Envelope 4x4 station wagon minimum package MG-UPNNC-254371-GO-RFB Scale up coverage and utiliz Single Stage - One / Acquisition de 196 motos p IDA / D2570 ation of the RMCHN minimu Post Request for Bids Open - National 498,500.00 344,070.16 Signed 2021-10-15 2021-09-24 2021-10-22 2021-10-12 2021-11-21 2021-10-27 2021-11-28 2021-11-25 2021-12-15 2021-12-31 2022-02-13 Envelope our les animateurs et emplo m package yés de suivi MG-UPNNC-256591-GO-RFQ Scale up coverage and utiliz Request for Quot Single Stage - One / Fourniture et livraison de g IDA / D2570 ation of the RMCHN minimu Post Open - National 52,000.00 11,217.02 Completed 2021-12-08 2021-10-25 2022-01-08 2021-12-30 2022-02-07 2022-02-15 ations Envelope oodies _coffret article m package MG-UPNNC-252116-GO-RFQ Strengthen capacity to man Request for Quot Single Stage - One Under Imple / Acquisition de matériels inf IDA / D2570 age and deliver the RMCHN Post Open - National 60,532.00 0.00 2021-11-15 2021-10-24 2021-12-31 2022-03-01 ations Envelope mentation ormatiques minimum package MG-UPNNC-241657-GO-RFQ Scale up coverage and utiliz Request for Quot Single Stage - One / Acquisition de 43 000 boîte IDA / D2570 ation of the RMCHN minimu Post Open - National 43,106.00 23,845.82 Completed 2021-11-19 2021-10-25 2021-12-26 2021-12-31 2022-02-24 2022-01-21 ations Envelope s plastiques m package MG-UPNNC-254369-GO-RFB Scale up coverage and utiliz Single Stage - One / Acquisition de 6 000 table IDA / D2570 ation of the RMCHN minimu Post Request for Bids Open - National 492,000.00 0.00 Canceled 2021-10-26 2021-10-08 2021-11-02 2021-10-12 2021-12-02 2021-12-09 2022-01-09 2022-04-09 Envelope s pour les 7 régions répartie m package en 07lots MG-UPNNC-254361-GO-RFB Scale up coverage and utiliz Single Stage - One / Acquisition de 12 000 chais IDA / D2570 ation of the RMCHN minimu Post Request for Bids Open - National 372,000.00 0.00 Canceled 2021-10-26 2021-10-08 2021-11-02 2021-12-02 2021-12-09 2021-12-23 2022-03-23 Envelope es pour les 7 régions réparti m package e en 07 lots PARN UPNNC 3 1 KIT SONO Project Management, Capac Request for Quot Single Stage - One IDA / D2570 Post Limited 5,000.00 0.00 Canceled 2021-02-08 2021-03-29 2021-05-28 / Acquisition d'un kit de sono ity Building and Operations ations Envelope risation Support MG-UPNNC-283396-GO-RFB Strengthen capacity to man Single Stage - One / Acquisition de 283 tablette IDA / D2570 age and deliver the RMCHN Post Request for Bids Open - National 302,286.00 154,879.23 Signed 2022-04-01 2022-03-28 2022-04-03 2022-04-04 2022-05-03 2022-05-04 2022-05-17 2022-06-10 2022-06-07 2022-07-29 2022-12-04 Envelope s et accessoires. minimum package MG-UPNNC-286345-GO-RFQ / Fourniture et livraison des équipements informatiques Project Management, Capac Request for Quot Single Stage - One Under Imple répartis en 02 lots: IDA / D2570 ity Building and Operations Post Open - National 19,000.00 0.00 2022-04-27 2022-06-10 2022-08-09 ations Envelope mentation - lot 1: 2 Imprimantes multif Support onction - lot 2: 2 Onduleurs MG-UPNNC-303535-GO-RFB Scale up coverage and utiliz Single Stage - One IDA / D2570 Post Request for Bids Open - National 5,768.00 0.00 Canceled 2022-07-15 2022-08-19 2022-07-20 2022-08-31 2022-09-20 2022-09-30 2022-11-04 2023-02-10 / Acquisition de Balance Pès ation of the RMCHN minimu Envelope e-personne m package MG-UPNNC-258111-GO-RFQ Scale up coverage and utiliz Request for Quot IDA / D2570 Post 1,000.00 0.00 Canceled 2021-11-29 2022-01-17 2022-02-07 / Confection et livraison de 1 ation of the RMCHN minimu ations 00 Gilets. m package MG-UPNNC-310835-GO-RFQ Project Management, Capac / Fourniture et livraison d'éq Request for Quot Single Stage - One Under Imple IDA / D2570 ity Building and Operations Post Open - National 30,000.00 0.00 2022-09-12 2022-11-07 2023-02-15 uipements informatiques et ations Envelope mentation Support accessoires répartie en quat re lots PARN UPNNC 16 AON02 / Ac Strengthen capacity to man Single Stage - One quisition de kits pour démon IDA / D2570 age and deliver the RMCHN Post Request for Bids Open - National 300,000.00 0.00 Canceled 2021-01-25 2021-02-08 2021-03-08 2021-03-22 2021-04-19 2021-06-03 Envelope stration culinaire minimum package MG-UPNNC-283296-GO-RFQ Scale up coverage and utiliz Request for Quot Single Stage - One / Acquisition de 210 Clés US IDA / D2570 ation of the RMCHN minimu Post Open - National 4,700.00 0.00 Canceled 2022-04-03 2022-05-17 2022-07-01 ations Envelope B et gravage. m package MG-UPNNC-330791-GO-DIR Scale up coverage and utiliz / Fourniture et livraison de s Pending Impl IDA / D2570 ation of the RMCHN minimu Post Direct Selection Direct - National 700,727.00 0.00 2022-12-21 2023-01-10 2023-02-28 2023-07-18 upplément nutritif à base de ementation m package lipide "Lipid Nutrient Supple ment - LNS" MG-UPNNC-357336-GO-RFQ Project Management, Capac / Acquisition de Vidéo projec Request for Quot Single Stage - One Under Imple IDA / D2570 ity Building and Operations Post Open - National 20,000.00 0.00 2023-05-03 2023-05-30 2023-06-28 2023-07-26 teur, Imprimantes et Ondule ations Envelope mentation Support urs répartie en 3 lots MG-UPNNC-357585-GO-RFQ Project Management, Capac Request for Quot Single Stage - One Under Imple IDA / D2570 Post Open - National 82,000.00 0.00 2023-05-03 2023-05-30 2023-06-28 2023-07-26 / Acquisition d'ordinateurs p ity Building and Operations ations Envelope mentation ortables Support MG-UPNNC-357337-GO-RFQ Scale up coverage and utiliz Request for Quot Single Stage - One Under Imple / Fourniture et livraison de d IDA / D2570 ation of the RMCHN minimu Post Open - National 90,000.00 0.00 2023-05-03 2023-05-30 2023-06-28 2023-07-26 ations Envelope mentation eux véhicules Mini-bus m package MG-UPNNC-283292-GO-RFQ Scale up coverage and utiliz Request for Quot Single Stage - One / Fourniture et livraison de 0 IDA / D2570 ation of the RMCHN minimu Post Open - National 4,000.00 0.00 Canceled 2022-06-15 2022-07-25 2022-10-23 ations Envelope 8 appareils photos m package MG-UPNNC-315400-GO-RFQ Project Management, Capac Request for Quot Single Stage - One IDA / D2570 Post Open - National 100,000.00 0.00 Canceled 2022-10-02 2022-10-14 2022-11-27 2023-02-10 / Acquisition de 65 Moto-Cro ity Building and Operations ations Envelope ss Support NON CONSULTING SERVICES Page 3 Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualificatio Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendatio Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus n Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes n for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MG-UPNNC-181754-NC-RFB / Confection, impression et li vraison des outils de commu nications: lot 1:Tee-shirts, Strengthen capacity to man Single Stage - One lot 2: Casquettes IDA / D2570 age and deliver the RMCHN Post Request for Bids Open - National 205,736.00 91,092.95 Signed 2020-08-03 2020-06-24 2020-08-10 2020-09-09 2020-08-14 2020-09-23 2020-09-04 2020-10-24 2020-10-16 2020-12-28 2021-12-11 Envelope lot 3: Banderoles minimum package lot 4: Pagnes lot 5: Polos lot 6: Chapeaux Bob lot 7:Sacs à dos lot 8: Masques caches bouch es MG-UPNNC-184858-NC-RFB / Impression et livraison des Strengthen capacity to man Single Stage - One registres SPC et PECMAM po IDA / D2570 age and deliver the RMCHN Post Request for Bids Open - National 400,000.00 26,211.11 Signed 2020-08-03 2020-05-18 2020-08-10 2020-09-09 2020-06-05 2020-09-16 2020-06-29 2020-10-03 2020-07-23 2021-04-01 Envelope ur les 7 régions (Enimbolana minimum package voalohany et Enimbolana Fa haroa) MG-UPNNC-186044-NC-RFB / Travaux d'impression repar tis en 4 lots: Scale up coverage and utiliz lot 1: Agenda 2021 Single Stage - One IDA / D2570 ation of the RMCHN minimu Post Request for Bids Open - National 35,200.00 33,759.77 Signed 2020-09-01 2020-06-23 2020-09-08 2020-10-08 2020-08-14 2020-10-22 2020-09-04 2020-11-08 2021-03-16 2020-12-23 2021-12-15 lot 2: Calendriers muraux Envelope m package lot 3: Calendriers chevalets lot 4: Bulletins périodiques N°15 et N°16 MG-UPNNC-186002-NC-RFQ Scale up coverage and utiliz / Impression et livraison de d Request for Quot Single Stage - One IDA / D2570 ation of the RMCHN minimu Post Open - National 15,400.00 15,715.12 Completed 2020-09-08 2020-10-06 2020-03-19 2020-11-05 2020-05-08 épliants guide de message e ations Envelope m package t affiches répartis en 2 lots MG-UPNNC-203393-NC-RFQ Project Management, Capac Request for Quot Single Stage - One / Déménagement de l'UPNN IDA / D2570 ity Building and Operations Post Limited 30,000.00 2,909.87 Signed 2020-11-13 2020-08-04 2020-12-18 2020-09-24 2021-12-18 ations Envelope C, Prospection d'un nouveau Support local MG-UPNNC-189838-NC-RFP Project Management, Capac Request for Propo Single Stage - Two / Déménagement de l' UPNN IDA / D2570 ity Building and Operations Prior Limited 30,000.00 0.00 Canceled 2020-08-24 2020-08-25 2020-09-09 2020-09-15 2021-09-15 sals Envelope C. Prospection d'un nouveau Support local MG-UPNNC-154757-NC-RFQ Scale up coverage and utiliz / Transport vers districts (LN Request for Quot Single Stage - One IDA / D2570 ation of the RMCHN minimu Post Limited 90,156.00 568.79 Signed 2021-01-25 2021-06-15 2021-03-01 2021-06-23 2021-03-31 S/Plumpy/Matériels/Supports ations Envelope m package vers la région Bongolava MG-UPNNC-216417-NC-RFQ / lot 1: Acheminement de pl umpy sup pours les 06 régio ns lot 2: Acheminement de 2 4 Scale up coverage and utiliz Request for Quot Single Stage - One 40 Radios solaires pour Anal IDA / D2570 ation of the RMCHN minimu Post Limited 100,000.00 1,116.76 Completed 2021-03-01 2021-01-21 2021-03-26 2021-02-05 2021-04-09 2021-04-06 ations Envelope amanga et Alaotra Mangoro m package lot 3: Acheminement de 2 6 78 Armoires métalliques pou r les 05 régions lot 4: Acheminement des out ils de communication MG-UPNNC-221886-NC-RFQ / Confection et livraison des Scale up coverage and utiliz outils de communication rép Request for Quot Single Stage - One IDA / D2570 ation of the RMCHN minimu Post Limited 11,000.00 12,154.39 Completed 2021-04-06 2021-07-17 2021-05-11 2021-09-22 2021-06-10 2021-10-05 arties en 03 lots: ations Envelope m package Lot 1: 86 Roll up Lot 2: 36 Oriflammes Lot 3: 04 Fanions MG-UPNNC-221890-NC-RFB / Confection et livraison des outils de communications ré partis en 04 lots: Scale up coverage and utiliz Lot 1: 1 114 Banderoles Single Stage - One IDA / D2570 ation of the RMCHN minimu Post Request for Bids Open - National 65,800.00 41,399.77 Completed 2021-03-29 2021-03-01 2021-04-05 2021-05-20 2021-05-05 2021-04-12 2021-05-19 2021-06-15 2021-06-05 2021-08-05 2021-07-20 2021-11-26 Lot 2: 2 200 Blouses pour le Envelope m package s AC Lot 3: 2 200 Chapeaux bob p our les AC Lot 4: 1 400 Drapeaux pour l es sites communautaires Lot 5: 4 000 Tee shirts MG-UPNNC-223751-NC-RFB / Acquisition de visuel en co mmunication réparties en 0 5 lots: Lot 1: Confection 1 385 Plaq Scale up coverage and utiliz Single Stage - One ues pour sites IDA / D2570 ation of the RMCHN minimu Post Request for Bids Open - National 94,000.00 51,853.17 Completed 2021-03-15 2021-03-15 2021-03-22 2021-04-21 2021-04-19 2021-05-05 2021-06-21 2021-05-22 2021-07-16 2021-07-01 2021-08-28 Envelope Lot 2: Confection 10 Présen m package toirs de tables Lot 3: Impression 11 000 Dé pliants Lot 4: Impression 1 100 Feui llets Lot 5: Production 1 100 Bâch MG-UPNNC-240942-NC-RFQ es alim Scale up coverage and utiliz / Travaux d'impression et liv Request for Quot Single Stage - One IDA / D2570 ation of the RMCHN minimu Post Open - National 46,500.00 20,808.83 Completed 2021-06-30 2021-08-06 2021-08-26 2021-09-07 2021-09-17 raison de Registres SPC dest ations Envelope m package inés aux sites communautair es MG-UPNNC-241663-NC-RFQ Scale up coverage and utiliz Request for Quot Single Stage - One / Production de 6 500 Bulleti IDA / D2570 ation of the RMCHN minimu Post Limited 3,143.00 1,348.84 Completed 2021-07-14 2021-07-08 2021-08-06 2021-08-05 2021-08-21 2021-08-18 ations Envelope ns périodiques N°17 m package MG-UPNNC-242513-NC-RFQ / Production et livraison des outils de communication rep arties en 5 lots: Scale up coverage and utiliz - lot 1: Calendriers muraux 2 Request for Quot Single Stage - One IDA / D2570 ation of the RMCHN minimu Post Open - National 29,000.00 21,690.57 Completed 2021-10-05 2021-10-05 2021-11-07 2021-12-11 2022-01-06 2022-04-07 022 ations Envelope m package - lot 2: Calendriers chevalets 2022 - lot 3: Agenda modèle N°01 - lot 4: Kaliana N°18 - lot 5: Kaliana N°19 - lot 6: Production de 20 100 MG-UPNNC-248144-NC-RFQ stickers au / Acquisition de supports de Scale up coverage and utiliz communication pour LNS _ I Request for Quot Single Stage - One IDA / D2570 ation of the RMCHN minimu Post Open - National 69,111.00 0.00 Signed 2021-11-01 2022-02-08 2021-12-17 2022-01-16 mpression Affiche et guide ations Envelope m package Acquisition de supports de c ommunication imprimés MG-UPNNC-254378-NC-RFQ Scale up coverage and utiliz / Acheminement des matéri Request for Quot Single Stage - One Pending Impl IDA / D2570 ation of the RMCHN minimu Post Open - National 23,394.00 0.00 2021-11-22 2022-01-07 2022-02-06 els anthropométriques et su ations Envelope ementation m package pports de communication MG-UPNNC-254377-NC-RFQ Scale up coverage and utiliz Request for Quot Single Stage - One / Acheminement de 326 ton IDA / D2570 ation of the RMCHN minimu Post Open - National 43,329.00 568.61 Completed 2021-11-29 2022-01-14 2021-06-23 2022-01-29 2021-06-30 ations Envelope nes de LNS au niveaux distri m package cts MG-UPNNC-254376-NC-RFQ Scale up coverage and utiliz / Acheminement des aliment Request for Quot Single Stage - One IDA / D2570 ation of the RMCHN minimu Post Open - National 98,500.00 7,579.36 Signed 2021-11-08 2021-10-20 2022-01-06 2021-07-27 2022-01-21 s thérapeutiques plumpy su ations Envelope m package p aux districts (ONG) MG-UPNNC-257082-NC-RFQ Scale up coverage and utiliz Request for Quot Single Stage - One / Impression et pose affichag IDA / D2570 ation of the RMCHN minimu Post Open - National 1,700.00 444.30 Signed 2021-11-16 2022-03-07 2021-12-26 2022-06-30 2022-01-25 ations Envelope e sur panneau publicitaire 4 m package m x 3m Page 4 MG-UPNNC-248124-NC-RFQ Scale up coverage and utiliz Request for Quot Single Stage - One Pending Impl / Acquisition des supports de IDA / D2570 ation of the RMCHN minimu Post Open - National 94,800.00 0.00 2022-01-24 2022-03-08 2022-04-07 ations Envelope ementation communication confection/s m package érigraphie MG-UPNNC-261457-NC-RFQ Scale up coverage and utiliz Request for Quot Single Stage - One / Impression et livraison de 4 IDA / D2570 ation of the RMCHN minimu Post Open - National 18,000.00 14,380.15 Completed 2021-12-11 2022-01-18 2022-03-12 2022-01-21 2022-04-02 ations Envelope 526 registres SPC m package MG-UPNNC-252115-NC-RFQ Scale up coverage and utiliz / Acheminement des tables Request for Quot Single Stage - One IDA / D2570 ation of the RMCHN minimu Post Open - National 64,970.00 0.00 Canceled 2021-12-07 2022-01-21 2022-02-05 et chaises pour les sites com ations Envelope m package munautaires aux niveaux sit es communautaires MG-UPNNC-283287-NC-RFQ / Impression des bulletins KA LIANA répartie en 4 lots: Scale up coverage and utiliz Request for Quot Single Stage - One lot 1: KA LIANA N°20 IDA / D2570 ation of the RMCHN minimu Post Open - National 8,700.00 3,854.70 Signed 2022-12-03 2023-01-16 2022-08-20 2023-07-15 ations Envelope lot 2: KA LIANA N°21 m package lot 3: KA LIANA N°22 lot 4: KA LIANA N°23 MG-UPNNC-281937-NC-RFQ / Confection et production ré parties en 5 lots: lot 1: Pochette à rabat perso Scale up coverage and utiliz nnalisée Request for Quot Single Stage - One Under Imple IDA / D2570 ation of the RMCHN minimu Post Open - National 4,000.00 0.00 2022-06-08 2022-07-22 2022-09-20 lot 2: Sac kraft ations Envelope mentation m package lot 3: X banner lot 4: Mug VIP personnalisé lot 5: Impression bâches de f ond de stand pour les ORN P ARN MG-UPNNC-283277-NC-RFQ / Confection et livraison répa Scale up coverage and utiliz rtie en 3 lots: Request for Quot Single Stage - One IDA / D2570 ation of the RMCHN minimu Post Open - National 36,000.00 0.00 Signed 2022-04-27 2022-06-10 2022-09-08 lot 1: 1 000 Polos VIP ations Envelope m package lot 2: 6 000 Casquettes lot 3 : 100 Gilets MG-UPNNC-303662-NC-RFQ / Acquisition des supports de communication imprimés re partie en 3 lots : Strengthen capacity to man Lot 1 : Impression de 1 000 J Request for Quot Single Stage - One Under Imple IDA / D2570 age and deliver the RMCHN Post Open - National 5,000.00 0.00 2022-08-20 2022-10-15 2022-11-19 ob aids Coaching ations Envelope mentation minimum package Lot 2 : Impression de 9 000 J ob aids CIP Lot 3 : Impression de 2 000 Affiches des offres de servic e FAFY MG-UPNNC-281923-NC-RFQ / Impression et livraison rép Strengthen capacity to man arties en 3 lots: Request for Quot Single Stage - One IDA / D2570 age and deliver the RMCHN Post Open - National 26,500.00 0.00 Signed 2022-07-25 2022-09-09 2022-10-14 lot 1: 4 600 Registres SPC ations Envelope minimum package lot 2: 4 600 Registre PECMA M lot 3: 500 Rapports grand pu blic MG-UPNNC-248131-NC-RFQ Scale up coverage and utiliz Request for Quot Single Stage - One / Impression des supports de IDA / D2570 ation of the RMCHN minimu Post Open - National 66,000.00 0.00 Canceled 2022-01-10 2022-02-22 2022-03-24 ations Envelope communication (imprimés n m package umériques) MG-UPNNC-310887-NC-RFQ / Impression et livraison rép arties en cinq lots : Scale up coverage and utiliz Lot 1 Impression Affiches LN Request for Quot Single Stage - One IDA / D2570 ation of the RMCHN minimu Post Open - National 35,950.00 0.00 Completed 2022-10-19 2022-12-14 2023-01-18 S ations Envelope m package Lot 2 Impression Dépliants L NS Lot 3 Agenda VIP 2023 Lot 4 Calendriers chevalets Lot 5 Calendriers muraux MG-UPNNC-311035-NC-DIR Project Management, Capac / Consultant en charge du p Under Imple IDA / D2570 ity Building and Operations Post Direct Selection Direct - National 50,000.00 0.00 2022-12-12 2023-01-09 2022-12-19 2023-03-03 2023-01-16 2024-01-16 aiement des indemnités des mentation Support Agents Communautaires MG-UPNNC-221899-NC-RFQ Scale up coverage and utiliz Request for Quot Single Stage - One / Production de 1 000 Stylos IDA / D2570 ation of the RMCHN minimu Post Limited 1,800.00 0.00 Canceled 2021-03-22 2021-04-26 2021-05-26 ations Envelope personnalisé m package CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amoun Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Techni Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) t (US$) Notice equest for Proposals as Issued Proposals / Minutes cal Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual UPNNC 3 15 SMC / Consulta Project Management, Capac Least Cost Selecti IDA / V0970 Post Open - National 15,000.00 7,385.25 Completed 2017-11-08 2017-12-14 2017-11-22 2017-12-27 2017-12-13 2018-03-08 2017-12-27 2018-04-05 2018-01-10 2018-05-02 2018-02-14 2018-05-14 2018-03-14 2018-05-28 2018-06-12 2018-06-25 nt - Auditeur Externe ity Building and Operations on Support UPNNC 3 18 SQC MANUELS Project Management, Capac Consultant Qualifi / Consultant chargé de la mi IDA / V0970 ity Building and Operations Post Open - National 20,000.00 14,408.60 Completed 2017-12-26 2017-12-14 2018-01-09 2018-01-30 2018-01-22 2018-02-13 2018-02-07 2018-03-13 2018-02-07 2018-07-11 2018-04-12 cation Selection se à jour du manuel d'opérat Support ion du Projet UPNNC 3 16 SQC SUPPL / C Project Management, Capac Consultant Qualifi abinet de recrutement du pe IDA / V0970 ity Building and Operations Post Limited 10,000.00 9,876.60 Completed 2018-01-01 2018-01-11 2018-01-15 2018-02-16 2018-01-29 2018-02-22 2018-03-05 2018-02-22 2018-04-04 2018-05-23 cation Selection rsonnel supplémentaire (UC Support P) UPNNC 3 36 SQC EVAL BES OIN EN FORMATION / CONSE ILS ET ASSISTANCE TECHNIQ UE INTERNATIONALE POUR Strengthen capacity to man Consultant Qualifi Open - Internation MODERNISER LA FORMATIO IDA / V0970 age and deliver the RMCHN Post 500,000.00 312,906.00 Signed 2018-02-15 2018-03-08 2018-03-01 2018-03-09 2018-04-14 2018-05-16 2018-05-14 2018-09-28 2018-06-07 2018-10-01 2018-10-05 cation Selection al N DES AGENTS DANS LES CE minimum package NTRES DE SANTE DE BASE E T DES AGENTS COMMUNAUT AIRES DE SANTE ET DE NUT RITION A MADAGASCAR UPNNC 3 25 SMC CONTROL Project Management, Capac E TRAVAUX UCP / Bureau d'é Least Cost Selecti IDA / V0970 ity Building and Operations Post Open - National 12,000.00 6,811.02 Signed 2018-02-15 2018-01-11 2018-03-01 2018-03-29 2018-03-14 2018-04-26 2018-04-17 2018-05-10 2018-04-27 2018-06-07 2018-05-16 2018-07-05 2018-05-15 2019-01-01 2018-09-26 tude chargé du contrôle des on Support travaux extension Bureau U CP UPNNC 1 8 FORMATION EN Project Management, Capac AUDIT INTERNE / Renforcem Consultant Qualifi IDA / V0970 ity Building and Operations Post Limited 5,000.00 2,588.70 Signed 2018-02-15 2018-02-08 2018-03-01 2018-02-08 2018-03-15 2018-04-19 2018-02-16 2018-04-24 ent de capacité en matière d cation Selection Support 'audit interne de projets UPNNC 3 38 SFQC EVALUAT Scale up coverage and utiliz Quality And Cost- Open - Internation ION MIS / Firme international IDA / V0970 ation of the RMCHN minimu Post 350,000.00 329,513.00 Signed 2018-05-04 2018-03-28 2018-05-25 2018-07-08 2018-05-24 2018-08-05 2018-08-03 2018-09-04 2018-10-12 2018-10-09 2018-10-12 2018-11-13 2019-07-30 2019-05-12 Based Selection al e chargée de l'évaluation du m package HMIS PARN UPNNC 1 6 1 23 ONG HAUTE MATSIATRA / Sélectio n de ONG/Associations parte Strengthen capacity to man Consultant Qualifi naires chargées du fonction IDA / D2570 age and deliver the RMCHN Post Open - National 875,000.00 29,122.48 Signed 2018-05-18 2019-07-22 2018-06-30 2018-08-11 2018-09-21 2018-09-08 2018-08-02 2018-09-22 2018-10-31 2019-12-31 cation Selection nement des sites communa minimum package utaires et vouchers dans la Région Haute Matsiatra (737 sites dans 7 districts répartis en 33 lots) Page 5 PARN UPNNC 1 6 ONG VAKI NANKARATRA / Sélection de ONG/Associations partenaire Strengthen capacity to man Consultant Qualifi s chargées du fonctionneme IDA / D2570 age and deliver the RMCHN Post Open - National 1,100,000.00 30,623.37 Signed 2018-05-18 2018-05-17 2018-06-30 2018-08-11 2018-08-20 2018-09-08 2018-11-19 2018-09-22 2018-10-31 2019-12-31 cation Selection nt des sites communautaires minimum package et vouchers - Région Vakina nkaratra (904 sites dans 7 di stricts répartis en 40 lots) PARN UPNNC 1 6 1 23 ONG AMORONIMANIA / ONG/Asso ciations partenaires chargée Strengthen capacity to man Consultant Qualifi s du fonctionnement des sit IDA / D2570 age and deliver the RMCHN Post Open - National 875,000.00 36,728.23 Signed 2018-05-18 2018-09-12 2018-06-30 2018-08-11 2018-09-11 2018-09-08 2018-10-29 2018-09-22 2018-10-31 2019-12-31 cation Selection es communautaires et vouc minimum package hers dans la Région Amoron' i Mania (713 sites dans 4 dis tricts répartis en 32 lots) PARN UPNNC 1 6 1 23 ONG ITASY / ONG/Associations pa Strengthen capacity to man rtenaires chargées du foncti Consultant Qualifi IDA / D2570 age and deliver the RMCHN Post Open - National 650,000.00 31,789.95 Signed 2018-05-18 2018-05-17 2018-06-30 2018-08-11 2018-09-07 2018-09-08 2018-10-30 2018-09-22 2018-11-10 2019-12-31 onnement des sites commu cation Selection minimum package nautaires et vouchers dans l a Région Itasy (539 sites da ns 3 districts répartis en 24 l ots) PARN UPNNC 3 1 SMC RECR Project Management, Capac UTEMENT / Cabinet chargé d Least Cost Selecti IDA / D2570 ity Building and Operations Post Open - National 10,000.00 0.00 Canceled 2018-08-10 2018-08-10 2018-08-24 2018-09-21 2018-10-05 2018-11-02 2018-11-16 2018-12-14 u recrutement du personnel on Support complémentaire pour l'U-PN NC UPNNC 3 38 EVALUATION S Scale up coverage and utiliz Consultant Qualifi YSTEME INFO SANIT / Evalua IDA / V0970 ation of the RMCHN minimu Post Limited 250,000.00 0.00 Canceled 2017-12-26 2018-03-21 2018-01-09 2018-01-30 2018-02-20 2018-08-19 cation Selection tion du système d'informatio m package n sanitaire UPNNC 3 9 SQC ONG VAKIN ANKARATRA / Réactivation e Strengthen capacity to man Consultant Qualifi t redynamisation des activit IDA / V0970 age and deliver the RMCHN Post Open - National 123,000.00 0.00 Canceled 2017-11-17 2017-12-01 2017-12-29 2018-01-19 2018-02-16 2018-09-14 cation Selection és des sites de nutrition dan minimum package s le Vakinankaratra (22ONG/ 541sites/54animateurs) UPNNC 3 9 SQC ONG AMOR ONIMANIA / Réactivation et r Strengthen capacity to man Consultant Qualifi edynamisation des activités IDA / V0970 age and deliver the RMCHN Post Open - National 78,000.00 0.00 Canceled 2017-11-17 2017-12-01 2017-12-29 2018-01-19 2018-02-16 2018-09-14 cation Selection des sites de nutrition dans l' minimum package AmoronImania (17ONG/330s ites/33animateurs) UPNNC 3 9 SQC ONG ITASY / Réactivation et redynamisa Strengthen capacity to man Consultant Qualifi tion des activités des sites d IDA / V0970 age and deliver the RMCHN Post Open - National 22,000.00 0.00 Canceled 2017-11-17 2017-12-01 2017-12-29 2017-12-31 2018-01-21 2018-08-19 cation Selection e nutrition dans l'Itasy (6ON minimum package G/125sites/13animateurs) UPNNC 3 9 SQC ONG HAUT E MATSIATRA / Réactivation Strengthen capacity to man Consultant Qualifi et redynamisation des activi IDA / V0970 age and deliver the RMCHN Post Open - National 110,000.00 0.00 Canceled 2017-11-17 2017-12-01 2017-12-29 2018-01-19 2018-02-16 2018-09-14 cation Selection tés des sites de nutrition da minimum package ns la Haute Matsiatra (19ON G/484sites/48animateurs) UPNNC 1 14 SQC / Consulta Strengthen capacity to man Consultant Qualifi nt chargé de l'étude de faisa IDA / V0970 age and deliver the RMCHN Post Open - National 50,000.00 0.00 Canceled 2017-11-07 2017-11-21 2018-01-02 2018-01-16 2018-02-13 2018-06-13 cation Selection bilité pour la mise en place d minimum package u fonds dédié UPNNC 3 38 SQC EVALUATI Scale up coverage and utiliz Consultant Qualifi Open - Internation ON MIS / Firme international IDA / V0970 ation of the RMCHN minimu Post 350,000.00 0.00 Canceled 2018-03-09 2018-03-23 2018-03-21 2018-04-27 2018-05-27 2018-07-01 2018-12-28 cation Selection al e chargée de l'évaluation du m package HMIS MG-UPNNC-94277-CS-CQS / Project Management, Capac Consultant Qualifi Recrutement Directeur Natio IDA / D2570 ity Building and Operations Post Open - National 22,400.00 0.00 Canceled 2018-06-11 2018-06-07 2018-07-20 2019-07-22 2018-11-06 2019-01-11 2019-02-18 2020-02-18 cation Selection nal U-PNNC Support MG-UPNNC-3 1 01 03 00 CA BINET DE RECRUTE / Cabine Project Management, Capac Consultant Qualifi t chargé du recrutement du IDA / D2570 ity Building and Operations Post Open - National 5,000.00 5,890.25 Signed 2019-06-04 2018-12-31 2019-06-09 2019-07-01 2019-05-23 2019-07-06 2019-06-21 2019-07-13 2019-06-21 2019-08-02 cation Selection personnel complémentaire p Support our l'UPNNC (RSE-AI,Logistici en) MG-UPNNC-94277-B / Recru Project Management, Capac Consultant Qualifi Pending Impleme IDA / D2570 Post Open - National 22,400.00 0.00 2018-06-01 2018-06-29 2018-10-19 2018-12-14 2019-01-04 2023-01-04 tement Directeur National p ity Building and Operations cation Selection ntation our l'UPNNC Support MG-UPNNC-170818-CS-FBS / ONG/Partenaires chargées Strengthen capacity to man Fixed Budget Sele Under Implement du fonctionnement des sites IDA / D2570 age and deliver the RMCHN Post Open - National 200,000.00 0.00 2020-08-03 2020-03-21 2020-08-17 2020-09-14 2020-10-14 2020-11-13 2020-12-27 2021-02-09 2022-08-03 ction ation communautaires et voucher minimum package s dans la région Amoron'i M ania repartie en 7 lots. MG-UPNNC-170815-CS-FBS / ONG/Partenaires chargées Strengthen capacity to man Fixed Budget Sele Under Implement du fonctionnement des sites IDA / D2570 age and deliver the RMCHN Post Open - National 200,000.00 0.00 2020-08-03 2020-03-21 2020-08-17 2020-09-30 2020-10-30 2020-11-06 2020-12-04 2021-02-02 2022-07-27 ction ation communautaires et voucher minimum package s dans la région Haute Matsi atra repartie en 7 lots. MG-UPNNC-170820-CS-FBS / ONG/Partenaires chargées Strengthen capacity to man Fixed Budget Sele Under Implement du fonctionnement des sites IDA / D2570 age and deliver the RMCHN Post Open - National 120,000.00 0.00 2020-08-03 2020-03-21 2020-08-17 2020-09-30 2020-10-30 2020-11-29 2020-12-27 2021-02-25 2022-08-19 ction ation communautaires et voucher minimum package s dans la région Itasy reparti es en 4 lots MG-UPNNC-170841-CS-FBS / ONG/Partenaires chargées Strengthen capacity to man Fixed Budget Sele Under Implement du fonctionnement des sites IDA / D2570 age and deliver the RMCHN Post Open - National 330,000.00 0.00 2020-08-03 2020-03-21 2020-08-17 2020-09-30 2020-10-30 2020-11-13 2020-12-27 2021-02-25 2022-08-19 ction ation communautaires et voucher minimum package s dans la région Vakinakarat ra repartie en 10 lots MG-UPNNC-186006-CS-FBS / ONG/Partenaires chargées Strengthen capacity to man du fonctionnement des sites Fixed Budget Sele Under Implement IDA / D2570 age and deliver the RMCHN Post Open - National 400,000.00 0.00 2020-09-01 2019-10-08 2020-10-01 2020-10-17 2020-11-16 2020-11-30 2020-12-14 2021-01-07 2021-03-02 communautaires et voucher ction ation minimum package s dans la région Bongolava, dont 02 Districts répartis en 15 lots. MG-UPNNC-199553-CS-FBS / Sélection ONG/Associations Scale up coverage and utiliz Partenaires pour l'interventi Fixed Budget Sele Under Implement IDA / D2570 ation of the RMCHN minimu Post Open - National 900,000.00 0.00 2020-11-02 2020-06-15 2020-12-02 2021-01-31 2021-03-02 2021-04-01 2021-05-31 2021-06-08 2022-11-30 on dans les secteurs de la n ction ation m package utrition et de la santé dans l a région Alaotra Mangoro (3 0 lots dont 30 contrats) MG-UPNNC-199548-CS-FBS / Sélection ONG/Associations Scale up coverage and utiliz partenaires pour l'interventi Fixed Budget Sele Under Implement IDA / D2570 ation of the RMCHN minimu Prior Open - National 1,900,000.00 0.00 2020-12-28 2021-01-27 2021-03-28 2021-04-27 2021-05-27 2021-07-26 2021-08-12 2023-02-03 on dans les secteurs de la n ction ation m package utrition et de la santé dans l a région Analamanga (61 lot s c'est à dire 61 contrats) MG-UPNNC-234950-CS-CQS / Sélection de consultant en charge de l'étude Phase 1 et Project Management, Capac Consultant Qualifi Under Implement , Phase 2 la gestion, contrôle IDA / D2570 ity Building and Operations Post Limited 80,000.00 0.00 2021-06-15 2021-08-24 2021-06-22 2021-07-22 2021-08-12 2022-04-12 cation Selection ation et surveillance des travaux Support d'extension et surélévation d'un bâtiment à usage de bu reau pour l'UPNNC et l'ONN Page 6 MG-UPNNC-248121-CS-CQS / Recrutement de consultant Project Management, Capac Consultant Qualifi Open - Internation Under Implement en charge de renforcement IDA / D2570 ity Building and Operations Post 25,000.00 0.00 2021-09-23 2021-10-12 2021-10-08 2021-10-22 2021-10-29 2021-11-12 2021-12-12 cation Selection al ation de capacité des personnels Support de l'UPNNC en comptabilité et finances MG-UPNNC-254373-CS-CQS / Recrutement de consultant Project Management, Capac Consultant Qualifi Open - Internation Under Implement en charge de renforcement IDA / D2570 ity Building and Operations Post 132,000.00 0.00 2021-10-07 2021-10-12 2021-10-22 2021-11-05 2021-11-12 2021-11-26 2021-12-26 cation Selection al ation de capacité des personnels Support de l'UPNNC dans divers dom aines MG-UPNNC-267017-CS-FBS / Rescrutement de 2 ONG/Pa Scale up coverage and utiliz rtenaires chargés du fonctio Fixed Budget Sele Pending Impleme IDA / D2570 ation of the RMCHN minimu Post Open - National 33,000.00 0.00 2022-04-04 2022-04-18 2022-05-02 2022-05-16 2022-05-23 2022-06-06 2022-06-23 2023-03-20 nnement des sites commun ction ntation m package autaires de la région Vakina karatra__Districts Faratsiho et Betafo. MG-UPNNC-265950-CS-FBS / Recrutement 2 ONG/Parten Scale up coverage and utiliz aire chargé du fonctionneme Fixed Budget Sele Pending Impleme IDA / D2570 ation of the RMCHN minimu Post Open - National 21,700.00 0.00 2022-04-04 2022-04-18 2022-05-09 2022-05-23 2022-05-30 2022-06-20 2022-07-07 2023-06-02 nt des sites communautaires ction ntation m package dans les régions Bongolava_l ot 3_Districts Fenoarivobe et Tsiroanomandidy. MG-UPNNC-268843-CS-FBS / Recrutement de 02 ONG/Pa Scale up coverage and utiliz Fixed Budget Sele Pending Impleme rtenaires chargés du fonctio IDA / D2570 ation of the RMCHN minimu Post Open - National 40,000.00 0.00 2022-04-04 2022-04-18 2022-05-02 2022-05-16 2022-05-23 2022-06-06 2022-06-20 2023-03-17 ction ntation nnement des sites commun m package autaires de la région Ambosi tra__District Fandriana MG-UPNNC-267218-CS-FBS / Recrutement de 6 ONG/Par tenaires chargés du fonction Scale up coverage and utiliz Fixed Budget Sele Pending Impleme nement des sites communa IDA / D2570 ation of the RMCHN minimu Post Open - National 173,000.00 0.00 2022-04-04 2022-04-18 2022-05-02 2022-05-16 2022-05-23 2022-06-06 2022-06-23 2023-03-20 ction ntation utaires dans la région Haute m package Matsiatra_ Districts Ambalav ao, Ambohimahasoa, Isandr a et Lalangina. MG-UPNNC-283581-CS-CQS / Sélection de consultant en charge de l'étude, de la gest Project Management, Capac Consultant Qualifi ion, du contrôle et de la surv IDA / D2570 ity Building and Operations Post Open - National 80,000.00 0.00 Canceled 2022-04-07 2022-03-30 2022-04-21 2022-04-26 2022-06-04 2022-06-07 2022-07-12 2023-04-08 cation Selection eillance des travaux de réha Support bilitation (extension et surél évation) d'un bâtiment à usa ge de bureau pour l'UPNNC et l'ONN. MG-UPNNC-257627-CS-CQS Project Management, Capac Consultant Qualifi / Recrutement d'un cabinet IDA / D2570 ity Building and Operations Post Open - National 100,000.00 0.00 Canceled 2021-12-13 2022-02-11 2021-12-27 2022-02-11 2022-02-09 2022-05-18 2022-02-23 2022-03-16 2023-03-17 cation Selection pour le suivi de la gestion de Support s intrants INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Identifie Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amoun Draft Negotiated Con Description Component Review Type Method Process Status Terms of Reference d/Selected Consultan Signed Contract Contract Completion o. h unt (US$) t (US$) tract t Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual UPNNC 1-3 INDV / Consulta Scale up coverage and utiliz Individual Consult nt chargé de la consolidatio IDA / V0970 ation of the RMCHN minimu Post Open 64,000.00 33,580.86 Signed 2017-11-07 2017-12-14 2017-12-26 2018-01-19 2018-01-09 2018-02-13 2018-02-06 2018-05-14 2018-06-06 ant Selection n des mécanismes de gratui m package tés UPNNC 1 12 INDV / Consult Strengthen capacity to man ant chargé de l'analyse et co Individual Consult IDA / V0970 age and deliver the RMCHN Post Open 50,000.00 10,096.46 Signed 2017-11-07 2018-03-08 2018-01-02 2018-06-06 2018-01-16 2018-09-24 2018-02-13 2018-11-19 2018-05-14 nception de base de donnée ant Selection minimum package s intégrées sur tablettes UPNNC 3 3 INDV / Consulta Strengthen capacity to man Individual Consult nt chargé de l'évaluation de IDA / V0970 age and deliver the RMCHN Post Open 60,000.00 12,232.05 Signed 2017-11-07 2018-02-08 2017-12-24 2018-04-11 2018-01-07 2018-05-18 2018-02-04 2018-05-22 2018-04-05 ant Selection s besoins de renforcement d minimum package e capacité UPNNC 1 13 ED / Consultant Strengthen capacity to man chargé de l'étude préalable IDA / V0970 age and deliver the RMCHN Post Direct Selection Direct 115,000.00 101,480.00 Completed 2017-10-20 2017-11-21 2017-11-17 2017-11-27 2018-01-05 2017-11-29 2018-04-05 2018-09-26 à la mise à l'échelle du Fina minimum package ncement Basé sur les Résult ats (FBR) UPNNC 1 5 ED JHU / Consult ant chargé de la consolidatio n des systèmes de motivatio n utilisées et charges de tra Scale up coverage and utiliz vail /prestation de services, IDA / V0970 ation of the RMCHN minimu Post Direct Selection Direct 350,000.00 280,927.00 Signed 2017-11-16 2017-12-17 2017-11-26 2018-01-30 2018-03-27 2018-07-29 connaissances acquises et c m package ompétences des ACN et AC au niveau des 8 Régions (ro uge et jaune) et 2 Régions d u FA FSS dans le cadre des UPNNC 3 33 ED ALIVE THRI Scale up coverage and utiliz VE / Etat des lieux et prépar IDA / V0970 ation of the RMCHN minimu Post Direct Selection Direct 450,000.00 449,678.00 Signed 2017-11-17 2017-11-29 2017-11-27 2018-01-22 2018-02-12 2018-07-21 ation du Plan de communica m package tion pour le Projet suivant le PNAN III. UPNNC 1 13 INDV RBF2 / Dé termination des coûts et niv Strengthen capacity to man eaux de subvention par résu Individual Consult IDA / V0970 age and deliver the RMCHN Post Limited 15,000.00 16,600.00 Completed 2017-11-17 2017-12-14 2017-12-01 2017-12-16 2017-12-22 2018-02-08 2018-01-26 2018-02-24 2018-03-27 2018-04-18 ltat de la mise en oeuvre du ant Selection minimum package financement basé sur la perf ormance dans le secteur san té à Madagascar UPNNC 3 29 ED STIMULATIO N PRECOCEE / Stimulation pr écoce : appuyer la préparati Scale up coverage and utiliz on des différentes phases d'i IDA / V0970 ation of the RMCHN minimu Post Direct Selection Direct 50,000.00 5,123.42 Signed 2017-12-26 2018-03-08 2018-01-10 2018-03-21 2018-02-07 2018-03-26 2018-04-08 mplémentation et d'assurer m package un transfert de compétence à l'équipe nationale dans la f ormation, le suivi et la super vision UPNNC 3 40 COACH ED NAT Project Management, Capac / Consultant National chargé IDA / V0970 ity Building and Operations Post Direct Selection Direct 50,000.00 80,730.64 Signed 2018-01-01 2018-01-30 2018-01-11 2018-01-30 2018-03-17 2018-03-27 2019-03-12 de la facilitation et Coaching Support pour la mise en œuvre PARN -APPM UPNNC 3 15 IND AUDIT NAT IONAL MSANP / Consultant c Project Management, Capac hargé de l'exploitation des i Individual Consult IDA / V0970 ity Building and Operations Post Open 10,000.00 5,594.89 Signed 2018-02-16 2018-02-21 2018-04-06 2018-03-30 2018-04-27 2018-04-06 2018-05-25 2018-04-06 2018-06-24 nformations collectées et éla ant Selection Support boration du rapport de l'audi t national - Ministère de la S anté UPNNC 3 29 ED ECD INSTIT UTEUR / Assistance en ECD - Scale up coverage and utiliz Appuyer la psychologue (1) Individual Consult IDA / V0970 ation of the RMCHN minimu Post Direct 5,000.00 1,114.11 Signed 2018-03-20 2018-03-08 2018-03-30 2018-03-21 2018-04-13 2018-03-26 2018-05-11 2018-03-26 2019-03-07 dans la préparation et facilit ant Selection m package ation des ateliers, (2) réalisa tion du pré-test et (3) réunio n de discussion UPNNC 3 29 ED ECD EDUCA TEUR / Assistance en ECD - Scale up coverage and utiliz Appuyer la psychologue (1) Individual Consult IDA / V0970 ation of the RMCHN minimu Post Direct 5,000.00 571.34 Signed 2018-03-20 2018-03-08 2018-03-30 2018-03-21 2018-04-13 2018-03-26 2018-05-11 2018-03-26 2019-03-07 dans la préparation et facilit ant Selection m package ation des ateliers, (2) réalisa tion du pré-test et (3) réunio n de discussion Page 7 UPNNC 3 29 ED ECD ASSIST ANTE SOCIALE / Assistance e Scale up coverage and utiliz n ECD - Appuyer la psycholo Individual Consult IDA / V0970 ation of the RMCHN minimu Post Direct 5,000.00 1,114.11 Signed 2018-03-20 2018-03-08 2018-03-30 2018-03-21 2018-04-13 2018-03-26 2018-05-11 2018-03-26 2019-03-07 gue (1) dans la préparation ant Selection m package et facilitation des ateliers, (2 ) réalisation du pré-test et (3 ) réunion de discussion UPNNC 3 29 ED ECD ASSIST ANTE SOCIALE 2 / Assistanc Scale up coverage and utiliz e en ECD - Appuyer la psych Individual Consult IDA / V0970 ation of the RMCHN minimu Post Direct 5,000.00 1,114.11 Signed 2018-03-20 2018-03-08 2018-03-30 2018-03-21 2018-04-13 2018-03-26 2018-05-11 2018-03-26 2019-03-07 ologue (1) dans la préparati ant Selection m package on et facilitation des ateliers , (2) réalisation du pré-test e t (3) réunion de discussion PARN UPNNC 2 10 JHU / Assi Scale up coverage and utiliz stance technique internation IDA / D2570 ation of the RMCHN minimu Post Direct Selection Direct 400,000.00 0.00 Canceled 2018-05-20 2019-10-14 2018-06-17 2018-07-29 2019-12-31 ale effectuée par l'Université m package John Hopkins PARN UPNNC 2 10 TANGERI Scale up coverage and utiliz NE HCD / Consultant chargé IDA / D2570 ation of the RMCHN minimu Post Direct Selection Direct 100,000.00 0.00 Canceled 2018-05-04 2019-12-03 2018-05-18 2018-06-01 2019-06-01 de la recherche HCD m package PARN UPNNC 2 10 HCD CI / Scale up coverage and utiliz Groupe de consultants indivi Individual Consult IDA / D2570 ation of the RMCHN minimu Post Direct 100,000.00 7,578.65 Signed 2018-05-10 2018-06-14 2018-05-24 2018-05-31 2018-07-15 2018-05-31 2018-07-15 2019-05-31 duels - assistants locaux dan ant Selection m package s les recherches HCD PARN UPNNC 1 6 MANOP O Strengthen capacity to man NG / Consultant Individuel c Individual Consult IDA / D2570 age and deliver the RMCHN Post Direct 5,000.00 4,676.91 Signed 2018-08-03 2018-07-17 2018-08-17 2018-08-22 2018-08-31 2018-09-19 2018-09-14 2018-09-19 2018-11-13 hargé de l'élaboration du Ma ant Selection minimum package nuel d'Opération des ONG PARN UPNNC AT CP / Recrut Project Management, Capac Individual Consult ement Assistant Technique IDA / D2570 ity Building and Operations Post Direct 1,500.00 1,335.69 Signed 2018-08-16 2018-08-01 2018-08-30 2018-08-01 2018-09-06 2018-08-01 2018-09-06 2018-08-01 2018-12-31 ant Selection UPNNC - Coursier Planton Support PARN UPNNC AT RNAF / Rec Project Management, Capac rutement Assistant Techniqu Individual Consult IDA / D2570 ity Building and Operations Post Direct 9,000.00 7,643.24 Signed 2018-08-16 2018-08-01 2018-08-30 2018-08-01 2018-09-06 2018-08-01 2018-09-06 2018-08-01 2018-12-31 e UPNNC - Responsable Nati ant Selection Support onal Administratif et Financi er Intérimaire PARN UPNNC AT CPT01 / Re Project Management, Capac Individual Consult crutement Assistant Techniq IDA / D2570 ity Building and Operations Post Direct 3,000.00 2,412.10 Signed 2018-08-16 2018-08-01 2018-08-30 2018-08-01 2018-09-06 2018-08-01 2018-09-06 2018-08-01 2018-12-31 ant Selection ue UPNNC - Comptable Support PARN UPNNC AT CPT02 / Re Project Management, Capac Individual Consult crutement Assistant Techniq IDA / D2570 ity Building and Operations Post Direct 3,000.00 2,364.29 Signed 2018-08-16 2018-08-01 2018-08-30 2018-08-01 2018-09-06 2018-08-01 2018-09-06 2018-08-01 2018-12-31 ant Selection ue UPNNC - Comptable Support PARN UPNNC AT SCPT / Rec Project Management, Capac Individual Consult rutement Assistant Techniqu IDA / D2570 ity Building and Operations Post Direct 2,000.00 1,623.78 Signed 2018-08-16 2018-08-01 2018-08-30 2018-09-06 2018-08-01 2018-09-06 2018-08-01 2018-12-31 ant Selection e UPNNC - Secrétaire Comp Support table PARN UPNNC AT APM / Recr Project Management, Capac Individual Consult utement Assistant Techniqu IDA / D2570 ity Building and Operations Post Direct 3,000.00 2,389.55 Signed 2018-08-16 2018-08-01 2018-08-30 2018-09-06 2018-08-16 2018-09-06 2018-08-01 2018-12-31 ant Selection e UPNNC - Passation de Mar Support chés PARN UPNNC AT TM / Recru Project Management, Capac Individual Consult tement Assistant Technique IDA / D2570 ity Building and Operations Post Direct 2,000.00 1,528.26 Signed 2018-08-16 2018-08-01 2018-08-30 2018-08-01 2018-09-06 2018-08-01 2018-09-06 2018-08-01 2018-12-31 ant Selection UPNNC - Technicien de Main Support tenance PARN UPNNC AT MAG / Recr Project Management, Capac Individual Consult utement Assistant Techniqu IDA / D2570 ity Building and Operations Post Direct 2,000.00 1,623.78 Signed 2018-08-16 2018-08-01 2018-08-30 2018-08-01 2018-09-06 2018-08-01 2018-09-06 2018-08-01 2018-12-31 ant Selection e UPNNC - Magasinier Support UPNNC 1 11 INDV / Consult Strengthen capacity to man Individual Consult ant chargé de l'évaluation d IDA / V0970 age and deliver the RMCHN Post Open 82,000.00 0.00 Canceled 2017-11-07 2017-11-17 2017-12-31 2018-01-14 2018-02-11 2018-05-12 ant Selection u système MIS au niveau de minimum package s 2 Régions FSS UPNNC 3 36 INDV / Deux co nsultants individuels chargé de l'évaluation exhausitive d Strengthen capacity to man es besoins en formation et D Individual Consult IDA / V0970 age and deliver the RMCHN Post Open 500,000.00 0.00 Canceled 2017-11-16 2018-02-02 2018-01-04 2018-01-25 2018-03-01 2018-08-28 éveloppement de curriculum ant Selection minimum package (FdF et supports) des interve nants au niveau des platefor mes communautaires exista nts (AC, ACN et CSB) UPNNC 3 18 INDV / Consult ant chargé de la mise à jour Project Management, Capac Individual Consult du manuel de procédures du IDA / V0970 ity Building and Operations Post Open 20,000.00 0.00 Canceled 2017-11-07 2017-12-14 2017-12-17 2017-12-31 2018-01-28 2018-04-28 ant Selection projet (opérationnel et admi Support nistratif, santé et nutrition) UPNNC 3 40 COACH ED INT Project Management, Capac / Consultant International ch IDA / V0970 ity Building and Operations Post Direct Selection Direct 100,000.00 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2019-01-11 argé de la facilitation et Coa Support ching pour la mise en œuvre PARN-APPM MG-UPNNC-93278-CS-CDS / Sélection de Cabinet chargé Project Management, Capac de recrutement du personne IDA / D2570 ity Building and Operations Post Direct Selection Direct 10,000.00 7,107.95 Signed 2018-12-29 2018-12-03 2019-01-03 2018-12-11 2019-01-12 2018-12-29 2019-02-02 l complémentaire pour l'U-P Support NNC (RNAF, RPM, ACOM et C hargé de Suivi CT) MG-UPNNC-93279-CS-INDV / Sélection de Consultant Ind ividuel chargé d'appuyer l'U Project Management, Capac Individual Consult nité pour le recrutement du IDA / D2570 ity Building and Operations Post Direct 3,000.00 4,339.04 Signed 2018-12-29 2018-11-01 2019-01-05 2018-11-30 2019-01-08 2018-12-14 2019-01-14 2018-12-14 2019-02-04 ant Selection personnel complémentaire d Support e l'U-PNNC (Assistant Passati on de Marché, Comptable, In formaticien, Logisticien, ...) MG-UPNNC-93281-CS-CDS / Sélection de Consultant char gé de la Stratégie de change Strengthen capacity to man ment social et de comporte IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 1,300,000.00 1,353,791.00 Signed 2018-12-29 2019-01-17 2019-01-08 2019-02-22 2019-02-27 2019-09-10 2019-12-31 ment pour l'amélioration de minimum package l'Alimentation de Nourrisson et du Jeune Enfant et de la N utrition de la Femme (ANJE/ NdF) MG-UPNNC-95691-CS-CDS / Project Management, Capac Pending Impleme Recrutement Responsable P IDA / D2570 ity Building and Operations Post Direct Selection Direct 8,000.00 0.00 2018-10-22 2018-11-08 2018-12-13 2019-06-11 ntation assation de Marchés Intérim Support aire MG-UPNNC-3101 03 00-IND Project Management, Capac Individual Consult V / Recrutement Responsabl IDA / D2570 ity Building and Operations Post Direct 4,500.00 0.00 Canceled 2019-06-05 2019-06-15 2019-06-30 2019-07-10 2019-10-08 ant Selection e Suivi Evaluation pi Support MG-UPNNC-2 5 01 04-ASSIS Strengthen capacity to man TANCE TECHNIQUE / Assista IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 500,000.00 0.00 Canceled 2019-07-29 2019-09-26 2019-08-08 2019-09-04 2019-12-03 nce Technique minimum package (John Hopkins University) MG-UPNNC-124140-CS-IND Strengthen capacity to man V CONSULTANT HCD / Consu Individual Consult IDA / D2570 age and deliver the RMCHN Post Direct 21,772.80 4,215.84 Signed 2019-07-24 2019-08-01 2019-08-07 2019-08-07 2019-08-14 2019-08-14 2019-08-28 2019-08-14 2020-08-27 ltant chargé des recherches ant Selection minimum package HCD- Consultant 1 Page 8 MG-UPNNC-124143-CS-IND Strengthen capacity to man Individual Consult V / Consultant chargé des re IDA / D2570 age and deliver the RMCHN Post Direct 21,120.00 14,313.02 Signed 2019-07-24 2019-08-13 2019-08-07 2019-08-07 2019-08-14 2019-08-12 2019-08-28 2019-08-14 2020-08-27 ant Selection cherches HCD-Consultant 2 minimum package MG-UPNNC-124145-CS-IND Strengthen capacity to man Individual Consult V / Consultant chargé des re IDA / D2570 age and deliver the RMCHN Post Direct 6,220.80 14,771.21 Signed 2019-07-24 2019-08-13 2019-08-07 2019-08-07 2019-08-14 2019-08-13 2019-08-28 2019-08-14 2020-08-27 ant Selection cherches HCD-Consultant 3 minimum package MG-UPNNC-124161-CS-IND Strengthen capacity to man Individual Consult V / Consultant chargé des re IDA / D2570 age and deliver the RMCHN Post Direct 6,220.80 4,220.35 Signed 2019-07-24 2019-08-13 2019-08-07 2019-08-07 2019-08-14 2019-08-13 2019-08-28 2019-08-14 2020-08-27 ant Selection cherches HCD- Consultant 4 minimum package MG-UPNNC-124162-CS-IND Strengthen capacity to man Individual Consult V / Consultant chargé des re IDA / D2570 age and deliver the RMCHN Post Direct 16,800.00 14,746.79 Signed 2019-07-24 2019-08-13 2019-08-07 2019-08-07 2019-08-14 2019-08-12 2019-08-28 2019-08-14 2020-08-27 ant Selection cherches HCD- Consultant 5 minimum package MG-UPNNC-124243 / Consul tant assistant chargé de la c Scale up coverage and utiliz onception, développement e Individual Consult IDA / D2570 ation of the RMCHN minimu Post Direct 5,000.00 3,040.86 Signed 2019-01-04 2019-08-12 2019-04-05 2019-09-19 2019-05-03 2019-09-25 2019-06-21 2019-09-25 2019-07-02 t préparation à l'implémenta ant Selection m package tion des activités de stimulat ion précoce des jeunes enfa nts-Assistant 1 MG-UPNNC-124242 / Consul tant assistant chargé de la c Scale up coverage and utiliz onception, développement e Individual Consult IDA / D2570 ation of the RMCHN minimu Post Direct 5,000.00 3,040.86 Signed 2019-01-04 2019-08-12 2019-04-05 2019-09-19 2019-05-03 2019-09-25 2019-06-21 2019-09-26 2019-07-02 t préparation à l'implémenta ant Selection m package tion des activités de stimulat ion précoce des jeunes enfa nts- Assistant 2 MG-UPNNC-124236 / Consul tant assistant chargé de la c Scale up coverage and utiliz onception, développement e Individual Consult IDA / D2570 ation of the RMCHN minimu Post Direct 5,000.00 3,040.86 Signed 2019-01-04 2019-08-12 2019-04-05 2019-09-19 2019-05-03 2019-09-25 2019-06-21 2019-09-26 2019-07-02 t préparation à l'implémenta ant Selection m package tion des activités de stimulat ion précoce des jeunes enfa nts - Assistant 3 MG-UPNNC-124232 / Consul tant assistant chargé de la c Scale up coverage and utiliz onception, développement e IDA / D2570 ation of the RMCHN minimu Post Direct Selection Direct 50,000.00 13,249.64 Signed 2019-01-04 2019-08-12 2019-04-05 2019-09-19 2019-06-14 2019-09-26 2019-07-03 t préparation à l'implémenta m package tion des activités de stimulat ion précoce des jeunes enfa nts- Consultant MG-UPNNC-127989-CS-IND Scale up coverage and utiliz V / Recruter un Coordonnate Individual Consult IDA / D2570 ation of the RMCHN minimu Post Direct 75,000.00 70,000.00 Signed 2019-08-29 2019-08-28 2019-09-12 2019-08-29 2019-09-19 2019-10-03 2019-10-03 2019-10-06 2020-03-31 ur terrain des activités de pil ant Selection m package otage de la Stimulation Préc oce des enfants MG-UPNNC-127996-CS-CDS Project Management, Capac / Recrutement d'un cabinet Pending Impleme IDA / D2570 ity Building and Operations Post Direct Selection Direct 6,000.00 0.00 2019-08-26 2019-09-09 2019-09-30 2019-10-07 pour le renforcement de cap ntation Support acité en Passation de March és Strengthen capacity to man MG-UPNNC-134497-CS-CDS IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 4,000.00 4,005.42 Signed 2019-09-18 2019-09-16 2019-09-28 2019-09-24 2019-10-19 2019-10-12 2019-10-24 / Recyclage TOM 2 PRO minimum package MG-UPNNC-170725-CS-CDS / ONG/Partenaires chargées Strengthen capacity to man du fonctionnement des sites IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 30,000.00 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 communaitaires et vouchers minimum package dans la région Amoron'i Man ia lot 7 - Ambositra MG-UPNNC-170777-CS-CDS / ONG/Partenaires chargées Strengthen capacity to man du fonctionnement des sites IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 33,000.00 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 communautaires et voucher minimum package s dans la région Vakinakarat ra lot 2 Ambatolampy MG-UPNNC-170781-CS-CDS / ONG/Partenaires chargées Strengthen capacity to man du fonctionnement des sites IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 65,280.82 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 communautaires et voucher minimum package s dans la région Vakinakarat ra lot 3 Antanifotsy et lot 4 Ambatolampy MG-UPNNC-170267-CS-CDS / ONG/Partenaires chargées Strengthen capacity to man du fonctionnement des sites IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 24,000.00 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 communautaires et voucher minimum package s dans la région Haute Matsi atra (lot 6) - Ambalavao MG-UPNNC-170281-CS-CDS / ONG/Partenaires chargées Strengthen capacity to man du fonctionnement des sites IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 31,000.00 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 communautaires et voucher minimum package s dans la région Haute Matsi atra (lot 2) - Ikalamavony MG-UPNNC-170788-CS-CDS / ONG/Partenaires chargées Strengthen capacity to man du fonctionnement des sites IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 91,772.74 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 communautaires et voucher minimum package s dans la région Vakinakarat ra lot 1 Ambatolampy, lot 1 et lot 10 Antanifotsy MG-UPNNC-170791-CS-CDS / ONG/Partenaires chargées Strengthen capacity to man du fonctionnement des sites IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 47,989.23 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 communautaires et voucher minimum package s dans la région Vakinakarat ra lot 1 et lot 3 Antsirabe I MG-UPNNC-170797-CS-CDS / ONG/Partenaires chargées Strengthen capacity to man du fonctionnement des sites IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 33,000.00 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 communautaires et voucher minimum package s dans la région Vakinakarat ra lot 5 Antsirabe II MG-UPNNC-170284-CS-CDS / ONG/Partenaires chargées Strengthen capacity to man du fonctionnement des sites IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 26,000.00 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 communautaires et voucher minimum package s dans la région Haute Matsi atra (lot 2) - Isandra MG-UPNNC-170736-CS-CDS / ONG/Partenaires chargées du fonctionnement des sites Strengthen capacity to man communautaires et voucher IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 48,809.16 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 s dans la région Amoron'i M minimum package ania: lot 11 Fandriana lot 12 Fandriana MG-UPNNC-170747-CS-CDS / ONG/Partenaires chargées Strengthen capacity to man du fonctionnement des sites IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 39,000.00 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 communautaires et voucher minimum package s dans la région Amboron'i Mania lot 2 Ambatofinandra hana Page 9 MG-UPNNC-170737-CS-CDS / ONG/Partenaires chargées du fonctionnement des sites Strengthen capacity to man communautaires et voucher IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 61,247.54 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 s dans la région Amoron'i M minimum package ania: lot 11 Ambositra lot 3 Manandriana MG-UPNNC-170764-CS-CDS / ONG/Partenaires chargées Strengthen capacity to man du fonctionnement des sites IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 34,000.00 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 communautaires et voucher minimum package s dans la région Itasy lot 1 Miarinarivo MG-UPNNC-170801-CS-CDS / ONG/Partenaires chargées Strengthen capacity to man du fonctionnement des sites IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 34,000.00 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 communautaires et voucher minimum package s dans la région Vakinakarat ra lot 8 Antsirabe II MG-UPNNC-170716-CS-CDS / ONG/Partenaires chargées du fonctionnement des sites Strengthen capacity to man communautaires et voucher IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 67,029.98 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 s dans la région Amoron'i M minimum package ania lot 1-Ambositra lot 3 Ambositra MG-UPNNC-170728-CS-CDS / ONG/Partenaires chargées Strengthen capacity to man du fonctionnement des sites IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 40,000.00 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 communautaires et voucher minimum package s dans la région Amoron'i M ania lot 4- Fandriana MG-UPNNC-170745-CS-CDS / ONG/Partenaires chargées Strengthen capacity to man du fonctionnement des sites IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 34,000.00 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 communautaires et voucher minimum package s dans la région Amoron'i M ania lot 3- Ambatofinandrah ana MG-UPNNC-170756-CS-CDS / ONG/Partenaires chargées Strengthen capacity to man du fonctionnement des sites IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 29,000.00 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 communautaires et voucher minimum package s dans la région Itasy lot 4 A rivonimamo MG-UPNNC-170760-CS-CDS / ONG/Partenaires chargées Strengthen capacity to man du fonctionnement des sites IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 27,000.00 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 communautaires et voucher minimum package s dans la région Itasy lot 8 Arivonimamo MG-UPNNC-170766-CS-CDS / ONG/Partenaires chargées Strengthen capacity to man du fonctionnement des sites IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 32,000.00 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 communautaires et voucher minimum package s dans la région Itasy lot 3 Miarinarivo MG-UPNNC-170772-CS-CDS / ONG/Partenaires chargées Strengthen capacity to man du fonctionnement des sites IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 28,000.00 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 communautaires et voucher minimum package s dans la région Itasy lot 3 S oavinandriana MG-UPNNC-170775-CS-CDS / ONG/Partenaires chargées Strengthen capacity to man du fonctionnement des sites IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 58,049.26 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 communautaires et voucher minimum package s dans la région Itasy lot 4 e t lot 5 Soavinandriana MG-UPNNC-170782-CS-CDS / ONG/Partenaires chargées Strengthen capacity to man du fonctionnement des sites IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 30,000.00 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 communautaires et voucher minimum package s dans la région Vakinakarat ra lot 6 Antanifotsy MG-UPNNC-170787-CS-CDS / ONG/Partenaires chargées Strengthen capacity to man du fonctionnement des sites IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 76,729.35 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 communautaires et voucher minimum package s dans la région Vakinakarat ra lot 7, lot 8 et lot 9 Antanif otsy MG-UPNNC-170795-CS-CDS / ONG/Partenaires chargées Strengthen capacity to man du fonctionnement des sites IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 31,000.00 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 communautaires et voucher minimum package s dans la région Vakinakarat ra lot 4 Antsirabe II MG-UPNNC-170799-CS-CDS / ONG/Partenaires chargées Strengthen capacity to man du fonctionnement des sites IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 31,000.00 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 communautaires et voucher minimum package s dans la région Vakinakarat ra lot 7 Antsirabe II MG-UPNNC-170802-CS-CDS / ONG/Partenaires chargées Strengthen capacity to man du fonctionnement des sites IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 31,000.00 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 communautaires et voucher minimum package s dans la région Vakinakarat ra lot 1 Betafo I MG-UPNNC-170809-CS-CDS / ONG/Partenaires chargées Strengthen capacity to man du fonctionnement des sites IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 27,000.00 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 communautaires et voucher minimum package s dans la région Vakinakarat ra lot 1 Faratsiho MG-UPNNC-170810-CS-CDS / ONG/Partenaires chargées Strengthen capacity to man du fonctionnement des sites IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 27,000.00 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 communautaires et voucher minimum package s dans la région Vakinakarat ra lot 3 Faratsiho MG-UPNNC-170813-CS-CDS / ONG/Partenaires chargées Strengthen capacity to man du fonctionnement des sites IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 29,000.00 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 communautaires et voucher minimum package s dans la région Vakinakarat ra lot 3 Mandoto MG-UPNNC-170290-CS-CDS / ONG/Partenaires chargées Strengthen capacity to man du fonctionnement des sites IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 33,000.00 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 communautaires et voucher minimum package s dns la régions Haute Matsi atra (lot 4) Isandra MG-UPNNC-170307-CS-CDS / ONG/Partenaires chargées Strengthen capacity to man des sites communautaires et IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 38,000.00 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 vouchers dans la région Hau minimum package te Matsiatra (lot 2) - Vohibat o Page 10 MG-UPNNC-170748-CS-CDS / ONG/Partenaires chargées Strengthen capacity to man du fonctionnement des sites IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 39,000.00 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 communautaires et voucher minimum package s dans la région Amoron'i M ania lot 1 Ambatofinandrah ana MG-UPNNC-170754-CS-CDS / ONG/Partenaires chargées Strengthen capacity to man du fonctionnement des sites IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 30,000.00 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 communautaires et voucher minimum package s dans la région Itasy lot 2 A rivonimamo MG-UPNNC-170758-CS-CDS / ONG/Partenaires chargées Strengthen capacity to man du fonctionnement des sites IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 30,000.00 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 communautaires et voucher minimum package s dans la région Itasy lot 6 Arivonimamo MG-UPNNC-170769-CS-CDS / ONG/Partenaires chargées Strengthen capacity to man du fonctionnement des sites IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 32,000.00 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 communautaires et voucher minimum package s dans la région Itasy lot 5 Miarinarivo MG-UPNNC-170778-CS-CDS / ONG/Partenaires chargées Strengthen capacity to man du fonctionnement des sites IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 27,000.00 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 communautaires et voucher minimum package s dans la région Vakinakarat ra lot 3 Ambatolampy MG-UPNNC-170798-CS-CDS / ONG/Partenaires chargées Strengthen capacity to man du fonctionnement des sites IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 33,000.00 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 communautaires et voucher minimum package s dans la région Vakinakarat ra lot 6 Antsirabe II MG-UPNNC-170297-CS-CDS / ONG/Partenaires chargées Strengthen capacity to man du fonctionnement des sites IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 30,000.00 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 communautaires et voucher minimum package s dans la région Haute Matsi atra (lot 3) Lalangina MG-UPNNC-170712-CS-CDS / ONG/Partenaires chargées du fonctionnement des sites Strengthen capacity to man communautaires et voucher IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 54,000.00 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 s dans la région Amoron'i M minimum package ania lot 6-Ambositra lot 8 - Ambositra MG-UPNNC-170733-CS-CDS / ONG/Partenaires chargées du fonctionnement des sites Strengthen capacity to man communautaires et voucher IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 69,316.35 0.00 Canceled 2020-08-03 2020-09-09 2020-10-26 2022-04-19 s dans la région Amoron'i M minimum package ania: lot 6- Fandriana lot 2 Fandriana MG-UPNNC-170759-CS-CDS / ONG/Partenaires chargées Strengthen capacity to man du fonctionnement des sites IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 29,000.00 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 communautaires et voucher minimum package s dans la région Itasy lot 7 A rivonimamo MG-UPNNC-170770-CS-CDS / ONG/Partenaires chargées du fonctionnement des sites Strengthen capacity to man communautaires et voucher IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 232,504.36 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 s dans la région Itasy : minimum package lot 2, lot 4 et lot 6 Miarinari vo lot 1, lot 3, lot 5, lot 9 et lot 10 Arivonimamo MG-UPNNC-170771-CS-CDS / ONG/Partenaires chargées Strengthen capacity to man du fonctionnement des sites IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 31,000.00 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 communautaires et voucher minimum package s dans la région Itasy lot 1 S oavinandriana MG-UPNNC-170808-CS-CDS / ONG/Partenaires chargées Strengthen capacity to man du fonctionnement des sites IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 30,000.00 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 communautaires et voucher minimum package s dans la région Vakinakarat ra lot 6 Betafo MG-UPNNC-170812-CS-CDS / ONG/Partenaires chargées Strengthen capacity to man du fonctionnement des sites IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 55,171.63 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 communautaires et voucher minimum package s dans la région Vakinakarat ra lot 2 Mandoto et lot 5 Bet afo MG-UPNNC-170720-CS-CDS / ONG/Partenaires chargées Strengthen capacity to man du fonctionnent des sites co IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 24,000.00 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 mmunautaires et vouchers d minimum package ans la région Amoron'i Mani a lot 5-Ambositra MG-UPNNC-170724-CS-CDS / ONG/Partenaires chargées Strengthen capacity to man du fonctionnement des sites IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 25,000.00 0.00 Canceled 2020-08-03 2020-08-13 2020-10-26 2022-04-19 communautaires et voucher minimum package s dans la région Amoron'i M ania lot 9- Ambositra MG-UPNNC-170727-CS-CDS / ONG/Partenaires chargées Strengthen capacity to man du fonctionnement des sites IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 38,000.00 0.00 Canceled 2020-08-03 2020-09-09 2020-10-26 2022-04-19 communautaires et voucher minimum package s dans la région Amoron'i M ania - lot 3- Fandriana MG-UPNNC-170730-CS-CDS / ONG/Partenaires chargées Strengthen capacity to man du fonctionnement des sites IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 25,000.00 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 communautaires et voucher minimum package s dans la région Amoron'i M ania lot 5- Fandriana MG-UPNNC-170741-CS-CDS / ONG/Partenaires chargées du fonctionnement des sites Strengthen capacity to man communautaires et voucher IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 56,457.81 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 s dans la région Amoron'i M minimum package ania: lot 1 Manandriana lot 4 Ambositra MG-UPNNC-170278-CS-CDS / ONG/Partenaires chargées du fonctionnement dans les Strengthen capacity to man sites communautaires et vo IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 63,362.21 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 uchers dans la région Haute minimum package Matsiatra lot 1- Fianarantsoa I lot 4 - Lalalngina Page 11 MG-UPNNC-170286-CS-CDS / ONG/Partenaires chargées Strengthen capacity to man du fonctionnement des sites IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 32,000.00 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 communautaires et voucher minimum package s dans la région Haute Matsi atra (lot 3) - Isandra MG-UPNNC-170738-CS-CDS / ONG/Partenaires chargées du fonctionnement des sites Strengthen capacity to man communautaires et voucher IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 49,134.14 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 s dans la région Amoron'i M minimum package ania: lot 2 Manandriana lot 7 Fandriana MG-UPNNC-170743-CS-CDS / ONG/Partenaires chargées Strengthen capacity to man du fonctionnement des sites IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 28,000.00 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 communautaires et voucher minimum package s dans la région Amoron'i M ania lot 4 Manandriana MG-UPNNC-170265-CS-CDS / ONG/Partenaires chargées Strengthen capacity to man du fonctionnement des sites IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 27,000.00 0.00 Canceled 2020-08-03 2020-09-09 2020-11-06 2022-04-30 communautaires et voucher minimum package s dans la région Haute Matsi atra (lot 3)-Ambalavao MG-UPNNC-170291-CS-CDS / ONG/Partenaires chargées Strengthen capacity to man du fonctionnement des sites IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 34,000.00 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 communautaires et voucher minimum package s dans la région Haute Matsi atra (lot 1) - Lalangina MG-UPNNC-170293-CS-CDS / ONG/Partenaires chargées Strengthen capacity to man du fonctionnement des sites IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 31,000.00 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 communautaires et voucher minimum package s dans la région Haute Matsi atra (lot 2) - Lalangina MG-UPNNC-170266-CS-CDS / ONG/Partenaires chargées Strengthen capacity to man du fonctionnement des sites IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 28,000.00 0.00 Canceled 2020-08-03 2020-09-09 2020-11-06 2022-04-30 communautaires et voucher minimum package s dans la région Haute Matsi atra (lo 5) - Ambalavao MG-UPNNC-170272-CS-CDS / ONG/Partenaires chargées du fonctionnement des sites Strengthen capacity to man communautaires et voucher IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 55,753.37 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 s dans la région Haute Matsi minimum package atra lot 4 - Ambohimahasoa lot 6 - Ambohimahasoa MG-UPNNC-170277-CS-CDS / ONG/Partenaires chargées du fonctionnement des sites Strengthen capacity to man communautaires et voucher IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 62,184.24 0.00 Canceled 2020-08-03 2020-08-13 2020-10-26 2022-04-19 s dans la région Haute Matsi minimum package atra lot 7- Ambohimahasoa lot 2 Ambalavao MG-UPNNC-170279-CS-CDS / ONG/Partenaires chargées Strengthen capacity to man du fonctionnement des sites IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 36,000.00 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 communautaires et voucher minimum package s dans la région Haute Mats iatra (lot 2) - Fianarantsoa I MG-UPNNC-170283-CS-CDS / ONG/Partenaires chargées du fonctionnement des sites Strengthen capacity to man communautaires et voucher IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 67,651.61 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 s dans la région Haute Matsi minimum package atra lot 1- Isandra lot 1 Ambalavao MG-UPNNC-170269-CS-CDS / ONG/Partenaires chargées du fonctionnement des sites Strengthen capacity to man communautaires et voucher IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 54,299.59 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 s dans la région Haute Matsi minimum package atra: lot 2- Ambohimahasoa lot 3 Vohibato MG-UPNNC-170271-CS-CDS / ONG/Partenaires chargées du fonctionnement des sites Strengthen capacity to man communaitaires et vouchers IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 57,001.68 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 dans la région Haute Matsiat minimum package ra lot 3- Ambohimahasoa lot 5 Ambohimahasoa MG-UPNNC-170306-CS-CDS / ONG/Partenaires chargées Strengthen capacity to man du fonctionnement des sites IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 30,000.00 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 communautaires et voucher minimum package s dans la région Haute Matsi atra (lot 5) Lalangina MG-UPNNC-170803-CS-CDS / ONG/Partenaires chargées Strengthen capacity to man du fonctionnement des sites IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 32,000.00 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 communautaires et voucher minimum package s dans la région Vakinakarat ra lot 4 Betafo MG-UPNNC-170792-CS-CDS / ONG/Partenaires chargées Strengthen capacity to man du fonctionnement des sites IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 88,622.76 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 communautaires et voucher minimum package s dans la région Vakinakarat ra lot 1, lot 2 et lot 3 Antsira be II MG-UPNNC-170811-CS-CDS / ONG/Partenaires chargées Strengthen capacity to man du fonctionnement des sites IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 35,000.00 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 communautaires et voucher minimum package s dans la région Vakinakarat ra lot 1 Mandoto MG-UPNNC-173702-CS-CDS / ONG/Partenaires chargées Strengthen capacity to man du fonctionnement des sites IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 40,258.41 0.00 Canceled 2020-08-03 2020-09-09 2020-11-22 2022-05-16 communautaires et voucher minimum package s dans la région Haute Matsi atra lot 6 Vohibato MG-UPNNC-181752-CS-CDS / Consultant chargé du renfo Scale up coverage and utiliz rcement du système de soin IDA / D2570 ation of the RMCHN minimu Post Direct Selection Direct 980,000.00 1,046,548.00 Signed 2020-09-01 2020-12-08 2020-09-15 2021-01-14 2020-10-20 2020-04-25 2022-04-13 2022-04-20 s de santé primaires à base m package communautaire à travers de s études et des recherches o pérationnelles MG-UPNNC-185994-CS-CDS / ONG/Partenaires chargées Strengthen capacity to man du fonctionnement des sites IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 815,000.00 31,208.05 Signed 2020-09-01 2020-03-21 2020-09-22 2020-06-10 2020-11-12 2020-07-07 2022-05-06 communautaires et voucher minimum package s dans la région Amoron'i M ania, dont 4 Districts réparti s en 25 lots Page 12 MG-UPNNC-185995-CS-CDS / ONG/Partenaires chargées Strengthen capacity to man du fonctionnement des sites IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 830,000.00 26,466.97 Signed 2020-09-01 2020-03-21 2020-09-22 2020-06-10 2020-10-20 2020-07-07 2020-12-13 communautaires et voucher minimum package s dans la région Haute Matsi atra, dont 07 districts réparti s en 25 lots MG-UPNNC-185996-CS-CDS / ONG/Partenaires chargées Strengthen capacity to man du fonctionnement des sites IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 930,000.00 23,763.36 Signed 2020-09-01 2020-03-16 2020-09-22 2020-06-10 2020-10-20 2020-07-14 2022-04-13 communautaires et voucher minimum package s dans la région Vakinakarat ra, dont 07 Districts répartis en 30 lots MG-UPNNC-185997-CS-CDS / ONG/Partenaires chargées Strengthen capacity to man Under Implement du fonctionnement des sites IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 570,000.00 0.00 2020-09-01 2020-03-21 2020-09-22 2020-10-20 2022-04-13 ation communautaires et voucher minimum package s dans la région Itasy, dont 03 Districts répartis en 20 lo ts MG-UPNNC-199559-CS-CDS / Migration en version Web d Project Management, Capac u logiciel TOP2PRO et renfor IDA / D2570 ity Building and Operations Post Direct Selection Direct 45,000.00 37,750.48 Signed 2020-11-09 2020-09-28 2020-11-23 2021-08-12 2020-12-14 2021-10-16 2021-01-13 cement de capacités de l'éq Support uipe fiduciaire de l'UPNNC, O NN et des ORN sur l'utilisatio n du logiciel comptable TOM 2PRO MG-UPNNC-201768-CS-CDS / Consultant chargé de la co Scale up coverage and utiliz nception, développement et Under Implement IDA / D2570 ation of the RMCHN minimu Post Direct Selection Direct 230,000.00 0.00 2020-12-15 2020-11-11 2020-12-29 2020-11-17 2021-02-09 2022-08-03 préparation à l'implémentati ation m package on des activités de stimulati on précoce des jeunes enfan ts (ECD) PARN UPNNC 1 4 STIMULATI Strengthen capacity to man ON PRECOCE / Groupe de six Individual Consult IDA / D2570 age and deliver the RMCHN Post Direct 100,000.00 0.00 Canceled 2018-05-04 2018-03-08 2018-05-18 2018-06-15 2018-06-29 2019-12-31 (06) consultants individuels ant Selection minimum package chargé de la stimulation pré coce des enfants MG-UPNNC-203412-CS-IND Project Management, Capac Individual Consult Under Implement V / Recrutement d'un(e) Assi IDA / D2570 ity Building and Operations Post Open 4,800.00 0.00 2020-11-12 2020-08-17 2020-12-23 2021-01-13 2021-01-28 2021-07-27 ant Selection ation stant (e) en Passation de Ma Support rchés de l'UPNNC MG-UPNNC-201808-CS-CDS / Consultant chargé de l’app Scale up coverage and utiliz ui technique à l’intégration d Under Implement IDA / D2570 ation of the RMCHN minimu Post Direct Selection Direct 220,000.00 0.00 2020-12-21 2020-12-16 2021-01-04 2021-02-01 2022-07-26 e l’Approche Human Centere ation m package d Design dans le cadre du Pr ojet FAFY ainsi que la prépar ation de la mise à l’échelle MG-UPNNC-204559-CS-IND Strengthen capacity to man Individual Consult Under Implement V / 65 Consultants Animateu IDA / D2570 age and deliver the RMCHN Post Open 100,000.00 0.00 2020-11-12 2020-10-15 2020-12-20 2020-12-27 2021-01-17 2022-07-11 ant Selection ation rs encadreurs dans la région minimum package VV7V MG-UPNNC-204566-CS-IND Strengthen capacity to man Individual Consult Under Implement V / 16 Consultant Technicien IDA / D2570 age and deliver the RMCHN Post Open 100,000.00 0.00 2020-11-12 2020-10-15 2020-12-20 2020-12-27 2021-01-17 2022-07-11 ant Selection ation s Superviseurs dans la régio minimum package n VV7V MG-UPNNC-214558-CS-CDS Scale up coverage and utiliz / Recrutement d’une firme p IDA / D2570 ation of the RMCHN minimu Post Direct Selection Direct 240,000.00 277,945.50 Signed 2020-12-23 2020-12-23 2021-01-06 2021-01-12 2021-01-27 2021-04-21 2022-01-27 our la mise à jour du systèm m package e de collecte de données Nu trition/Santé MG-UPNNC-223763-CS-CDS / Consultant chargé de l'app Scale up coverage and utiliz ui technique à l'intégration d IDA / D2570 ation of the RMCHN minimu Post Direct Selection Direct 106,000.00 67,785.67 Signed 2021-05-03 2021-04-21 2021-05-24 2021-05-19 2021-06-14 2021-10-20 2022-06-14 e l'approche Human Centere m package d Design dans le cadre du pr ojet FAFY (HDA) MG-UPNNC-231573-CS-CDS Scale up coverage and utiliz / Consultant chargé de l'élab IDA / D2570 ation of the RMCHN minimu Post Direct Selection Direct 730,000.00 624,271.00 Signed 2021-05-03 2021-05-03 2021-05-24 2021-05-15 2021-06-14 2021-05-25 2022-04-11 oration et de la mise en œuv m package re de la stratégie du change ment social. MG-UPNNC-233819-CS-CDS / Sélection de consultant en charge du suivi de la mise e Strengthen capacity to man n place de la plateforme co IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 9,000.00 9,807.14 Signed 2021-05-18 2021-05-25 2021-05-22 2021-06-01 2021-06-03 2021-05-08 2021-11-30 mmunautaire et du démarra minimum package ge effectif des activités dans les régions d’Alaotra Mangor o, d’Analamanga et de Vato vavy Fito Vignany MG-UPNNC-235501-CS-IND V / Sélection de Consultant e Project Management, Capac n charge du Pilotage, de la p Individual Consult Under Implement IDA / D2570 ity Building and Operations Post Direct 1,500.00 0.00 2021-05-27 2021-05-25 2021-06-08 2021-06-01 2021-06-29 2021-06-30 2021-07-14 2022-05-14 réparation de la Mise à l’éch ant Selection ation Support elle des interventions de Sti mulation Précoce des Jeunes Enfants MG-UPNNC-247277-CS-CDS / ONG/Partenaires chargées Scale up coverage and utiliz du fonctionnement des sites Under Implement IDA / D2570 ation of the RMCHN minimu Post Direct Selection Direct 46,755.00 0.00 2021-10-21 2021-11-12 2021-12-03 2023-05-27 communautaires et voucher ation m package s dans la région Bongolava_ lot 1 et lot 10_Districts Tsiro anomandidy MG-UPNNC-247279-CS-CDS / ONG/Partenaires chargées Scale up coverage and utiliz du fonctionnement des sites Under Implement IDA / D2570 ation of the RMCHN minimu Post Direct Selection Direct 96,208.00 0.00 2021-10-21 2021-11-25 2021-11-12 2021-12-10 2023-06-03 communautaires et voucher ation m package s dans la région Bongolava_l ot 3,lot 4, lot 5 et lot 9_Distri ct Tsiroanomandidy MG-UPNNC-254524-CS-IND Project Management, Capac Individual Consult Under Implement V / Sélection d'un Supervise IDA / D2570 ity Building and Operations Post Open 10,000.00 0.00 2021-10-12 2021-10-11 2021-11-14 2021-12-05 2022-01-09 2022-07-08 ant Selection ation ur Régional au sein de l'UPN Support NC MG-UPNNC-247281-CS-CDS / ONG/Partenaires chargées Scale up coverage and utiliz du fonctionnement des sites Under Implement IDA / D2570 ation of the RMCHN minimu Post Direct Selection Direct 44,633.00 0.00 2021-10-21 2021-10-29 2021-11-19 2023-05-13 communautaires et voucher ation m package s dans la région Bogolava_lo t 6, lot 7_District Tsiroanoma ndidy MG-UPNNC-258108-CS-IND Project Management, Capac Individual Consult Under Implement V / Recrutement d'un Consul IDA / D2570 ity Building and Operations Post Open 12,000.00 0.00 2021-10-26 2021-10-14 2021-11-23 2021-12-14 2022-01-18 2022-07-17 ant Selection ation tant Spécialiste en Nutrition Support MG-UPNNC-261440-CS-IND Project Management, Capac Individual Consult Under Implement V / Recrutement d'un(e) Assi IDA / D2570 ity Building and Operations Post 10,000.00 0.00 2021-11-25 2021-11-17 2021-12-23 2022-01-13 2022-02-03 2023-02-03 ant Selection ation stant(e) de Programme (AP) Support à l’U-PNNC. MG-UPNNC-170722-CS-CDS / ONG/Partenaires chargées Strengthen capacity to man du fonctionnement des sites IDA / D2570 age and deliver the RMCHN Post Direct Selection Direct 39,000.00 0.00 Canceled 2020-09-01 2020-10-08 2020-12-21 2022-06-14 communautaires et voucher minimum package s dans la région Amoron'i M ANIA, dont 4 districts réparti s en 25 lots. Page 13 MG-UPNNC-267250-CS-CDS / Recrutement de 30 ONG/Pa rtenaires chargés du fonctio Scale up coverage and utiliz Pending Impleme nnement des sites commun IDA / D2570 ation of the RMCHN minimu Post Direct Selection Direct 300,000.00 0.00 2022-02-28 2022-03-21 2022-04-04 2022-10-31 ntation autaires dans la Région Amo m package ron'i Mania_Districts Ambosi tra, Manandriana et Ambatof inandrahina, Fandriana MG-UPNNC-265257-CS-CDS / Recrutement 6 ONG/Parten Scale up coverage and utiliz aire chargé du fonctionneme Pending Impleme IDA / D2570 ation of the RMCHN minimu Post Direct Selection Direct 85,400.00 0.00 2021-12-27 2022-01-15 2022-02-12 2023-01-08 nt des sites communautaires ntation m package dans la région Bongolava__D istricts Tsiroanomandidy et F enoarivobe MG-UPNNC-266386-CS-CDS / Recrutement de 24 ONG/Pa Scale up coverage and utiliz rtenaires chargés du fonctio Pending Impleme IDA / D2570 ation of the RMCHN minimu Post Direct Selection Direct 295,000.00 0.00 2022-01-17 2022-02-07 2022-03-03 2022-12-28 nnement des sites commun ntation m package autaires de la région Itasy_D istricts Arivonimamo, Miarin arivo et Soavinandriana MG-UPNNC-267020-CS-CDS / Recrutement de 38 ONG/Pa rtenaires chargés du fonctio Scale up coverage and utiliz nnement des sites commun Pending Impleme IDA / D2570 ation of the RMCHN minimu Post Direct Selection Direct 300,000.00 0.00 2022-04-04 2022-04-25 2022-05-16 2023-02-10 autaires de la région Vakina ntation m package karatra__Districts Ambatola mpy, Antanifotsy, Antsirabe I Antsirabe II, Betafo, Farats iho et Mandoto MG-UPNNC-267054-CS-CDS / Recrutement de 27 ONG/Pa rtenaires chargés du fonctio Scale up coverage and utiliz nnement des sites commun Pending Impleme IDA / D2570 ation of the RMCHN minimu Post Direct Selection Direct 289,800.00 0.00 2022-04-04 2022-04-25 2022-05-16 2023-02-10 autaires dans la région Haut ntation m package e Matsiatra__District Vohibat o, Ambalavao, Isandra, Lala ngina, Ambohimahasoa, Fia narantsoa I et Ikalamavony MG-UPNNC-295461-CS-IND Project Management, Capac Individual Consult V / Recrutement d'un(e) Assi IDA / D2570 ity Building and Operations Post Open - National 4,800.00 0.00 Canceled 2022-07-26 2022-09-16 2022-09-13 2022-10-04 2022-11-08 2023-05-07 ant Selection stant(e) en Passation de Mar Support ché MG-UPNNC-303654-CS-CDS / Sélection de consultant en charge de l'étude, de la gest Project Management, Capac Under Implement ion, du contrôle et de la surv IDA / D2570 ity Building and Operations Post Direct Selection Direct - National 80,000.00 0.00 2022-08-05 2022-08-11 2022-08-15 2022-08-11 2022-10-19 2023-05-17 ation eillance des travaux de réha Support bilitation (extension et surél évation) d'un bâtiment à usa ge de bureau pour l'UPNNC et l'ONN. MG-UPNNC-303926-CS-IND Project Management, Capac Individual Consult Under Implement V / Recrutement d'un(e) Spé IDA / D2570 ity Building and Operations Post Open - National 6,000.00 0.00 2022-07-27 2023-01-06 2022-09-14 2022-10-05 2022-11-09 2023-07-27 ant Selection ation cialiste en Passation de Marc Support hé MG-UPNNC-303928-CS-IND Project Management, Capac Individual Consult Pending Impleme V / Recrutement d'un Consul IDA / D2570 ity Building and Operations Post Limited 6,000.00 0.00 2022-08-26 2022-08-31 2022-09-21 2022-10-26 2023-04-24 ant Selection ntation tant Conseil Juridique Support MG-UPNNC-316965-CS-IND Project Management, Capac Individual Consult V / Recrutement d'un(e) Assi IDA / D2570 ity Building and Operations Post Open - National 4,800.00 0.00 Signed 2022-10-05 2022-12-04 2022-11-07 2023-04-12 2022-11-28 2023-04-17 2022-12-19 2023-07-31 ant Selection stant(e) en Communication Support UPNNC 1 9 FORMATION EN Project Management, Capac GESTION FINANCIE / Renforc IDA / V0970 ity Building and Operations Post Direct Selection Direct 5,000.00 0.00 Canceled 2018-02-16 2018-02-26 2018-05-02 2018-05-09 ement de capacité en matièr Support e d'audit interne de projets MG-UPNNC-330094-CS-IND Strengthen capacity to man Individual Consult Under Implement V / Consultant Spécialiste en IDA / D2570 age and deliver the RMCHN Post Open - National 5,000.00 0.00 2022-12-21 2023-01-09 2023-02-08 2023-04-14 2023-03-01 2023-04-05 2023-07-31 ant Selection ation Nutrition minimum package MG-UPNNC-330095-CS-IND Strengthen capacity to man Individual Consult Under Implement V / Recrutement de consulta IDA / D2570 age and deliver the RMCHN Post Open - National 6,000.00 0.00 2022-12-21 2023-01-09 2023-02-08 2023-04-18 2023-03-01 2023-06-08 2023-04-05 2023-07-31 ant Selection ation nt en Suivi Evaluation de l'U minimum package PNNC MG-UPNNC-330792-CS-IND Project Management, Capac Individual Consult Under Implement V / Recrutement d'un consul IDA / D2570 ity Building and Operations Prior Open - National 5,200.00 0.00 2023-03-15 2023-05-03 2023-05-03 2023-05-24 2023-06-28 2024-03-24 ant Selection ation tant Gestionnaire de Contrat Support MG-UPNNC-349848-CS-IND Project Management, Capac Individual Consult Under Implement V / Recrutement d'un Assista IDA / D2570 ity Building and Operations Post Open - National 4,500.00 0.00 2023-04-07 2023-04-18 2023-05-17 2023-06-07 2023-07-12 2024-01-08 ant Selection ation nt Audit Interne Support MG-UPNNC-349854-CS-IND Project Management, Capac Individual Consult Under Implement IDA / D2570 Post Open - National 3,500.00 0.00 2023-04-14 2023-04-19 2023-05-24 2023-06-14 2023-07-19 2024-01-15 V / Recrutement d'un(e) Co ity Building and Operations ant Selection ation mptable Support MG-UPNNC-281592-CS-IND Project Management, Capac Individual Consult V / Recrutement d'un Consul IDA / D2570 ity Building and Operations Post Open 3,000.00 0.00 Canceled 2022-04-11 2022-03-10 2022-05-02 2022-05-09 2022-05-30 2022-08-29 ant Selection tant chargé du Data Analyst Support MG-UPNNC-337076-CS-IND Project Management, Capac Individual Consult V / Recrutement Assistant(e) IDA / D2570 ity Building and Operations Post Open - National 6,000.00 0.00 Canceled 2023-03-03 2023-04-21 2023-05-12 2023-06-16 2024-06-15 ant Selection en Passation de Marchés Support Page 14 PROCUREMENT PLAN (Textual Part) Project information: Lebanon – Social Recovery Vulnerable Groups (P176622) Project Implementation agency: International Rescue Committee Date of the Procurement Plan: March 9, 2022 Period covered by this Procurement Plan: March 2022 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. Not Applicable Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables Not Applicable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: is not applicable for those contracts identified in the Procurement Plan tables; Works: is not applicable for those contracts identified in the Procurement Plan tables. PROCUREMENT Lebanon : Support for Social Recovery Needs of Vulnerable Groups in Beirut PLAN General Information Country: Lebanon 2022-03-09 Bank’s Approval Date of the Original Procurement Plan: 2023-06-07 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P176622 GPN Date: Project Name: Support for Social Recovery Needs of Vulnerable Groups in Beirut Loan / Credit No: TF / B7344, TF / B7390 International Rescue Committee Executing Agency(ies): WORKS Activity Reference No. / Procureme Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH Ri Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method nt Docume ount (US$ and Recommendation Signed Contract o. h cess (Y/N) sk atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion nt Type ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Request for LB-IRC-315197-CW-RFQ / Pro Component 1: Support for so Quotations ( 2022-12-1 curement of Office Maintena TF / B7390 cial services for vulnerable g Post Direct Selection Direct - National 0.00 Canceled 2022-10-01 2022-10-01 2022-10-07 Non Bank-SP 5 nce and repairs roups affected by the explos D) ion GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 1: Support for so 5LB/BEY/20/1050 / Procurem Request for Quota Single Stage - One E TF / B7390 cial services for vulnerable g Post Open - National 0.00 Canceled 2020-07-18 2020-09-12 2021-03-11 ent of IT Equipment tions nvelope roups affected by the explos ion Component 1: Support for so 5LB/BEY/21/1059.1 / Procure Request for Quota Single Stage - One E TF / B7390 cial services for vulnerable g Post Open - National 0.00 Canceled 2021-06-15 2021-08-10 2022-02-06 ment of Electrical Appliances tions nvelope roups affected by the explos ion Component 1: Support for so 5LB/BEY/20/LB1049.1 / Proc Request for Quota Single Stage - One E Under Imple TF / B7390 cial services for vulnerable g Post Open - National 0.00 2020-07-18 2020-09-12 2021-03-11 urement of Stationary tions nvelope mentation roups affected by the explos ion Component 1: Support for so 5LB/BEY/21/LB1056-C / Proc Request for Quota Single Stage - One E TF / B7390 cial services for vulnerable g Post Open - National 0.00 Canceled 2020-10-18 2020-12-13 2021-06-11 urement of Printings tions nvelope roups affected by the explos ion Component 1: Support for so 5LB/BEY/20/1048 / Procurem Request for Quota Single Stage - One E TF / B7390 cial services for vulnerable g Post Open - National 0.00 Canceled 2020-05-23 2020-07-18 2021-01-14 ent of Toners tions nvelope roups affected by the explos ion Component 1: Support for so LB-IRC-315143-GO-RFQP / Pr Request for Quota Single Stage - One E TF / B7390 cial services for vulnerable g Post Limited 0.00 Canceled 2022-10-06 2022-09-23 2022-12-01 2023-05-30 ocurement of Mobile phones tions nvelope roups affected by the explos ion LB-IRC-321807-GO-RFQ / Pri Component 1: Support for so Request for Quota Single Stage - One E nter Catridge PG445-Black TF / B7390 cial services for vulnerable g Post Limited 0.00 Terminated 2022-10-24 2022-10-26 2022-12-19 2023-06-17 tions nvelope Printer Cartridge PG445-color roups affected by the explos ed ion Component 1: Support for so PO#534488 / Procurement o Request for Quota Single Stage - One E TF / B7390 cial services for vulnerable g Post Open - National 0.00 Canceled 2022-12-03 2023-01-28 2023-07-27 f Air conditioner with Inverter tions nvelope roups affected by the explos ion LB-IRC-341914-GO-RFQ / Pro Component 1: Support for so Request for Quota Single Stage - One E curement of Diesel Heater co TF / B7390 cial services for vulnerable g Post Limited 0.00 Canceled 2023-02-10 2023-02-13 2023-03-08 2023-09-04 tions nvelope vering 80 M2 roups affected by the explos ion Component 1: Support for so PO#532711 / Procurement o Request for Quota Single Stage - One E TF / B7390 cial services for vulnerable g Post Limited 0.00 Canceled 2022-11-28 2023-01-23 2023-07-22 f Cartridges C-224 tions nvelope roups affected by the explos ion 5LB/BEY/21/1057 / Procurem Component 1: Support for so Request for Quota Single Stage - One E Under Imple ent Of Office & Kitchen Suppl TF / B7390 cial services for vulnerable g Post Open - National 0.00 2021-03-30 2021-05-25 2021-11-21 tions nvelope mentation ies roups affected by the explos ion NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual LB-IRC-286400-NC-DIR / Sup Component 1: Support for so port to the national hotline a cial services for vulnerable g TF / B7390 Prior Direct Selection Direct 0.00 Canceled 2022-03-23 2022-04-07 2022-03-28 2022-05-02 2022-10-29 nd Step-by-Step for targeted roups affected by the explos vulnerable groups ion LB-IRC-283109-NC-DIR / Assi sting with the operational cos Component 1: Support for so t of existing medium shelters cial services for vulnerable g TF / B7344 Post Direct Selection Direct 0.00 Canceled 2022-03-15 2022-03-30 2022-03-20 2022-05-09 2022-11-05 for women and children inclu roups affected by the explos ding capacity building and tr ion aining social workers on SoPs LB-IRC-290200-NC-DIR / Assi sting with the operational cos Component 1: Support for so t of existing large shelters for cial services for vulnerable g women and children includin TF / B7344 Post Direct Selection Direct 0.00 Signed 2022-04-13 2022-04-19 2022-04-18 2022-06-07 2022-05-20 2024-04-30 roups affected by the explos g capacity building and traini ion ng social worker and NGO sta ff on National GBV case man agement SOPs LB-IRC-291479-NC-DIR / Sup Component 1: Support for so port the national hotline and TF / B7390 cial services for vulnerable g Post Direct Selection Direct 0.00 Signed 2022-06-09 2022-06-03 2022-06-10 2022-06-08 2022-06-28 2023-11-27 Step-by-Step for targeted vul roups affected by the explos nerable groups ion LB-IRC-303376-NC-RFQ / Ass Component 1: Support for so isting with the provision of m cial services for vulnerable g Request for Quota Single Stage - One E Under Imple TF / B7390 Post Open - National 0.00 2022-07-13 2022-07-26 2022-09-07 2023-10-31 edical services for women an roups affected by the explos tions nvelope mentation d children in existing shelters ion Page 1 LB-IRC-303380-NC-RFQ / Co mmunity-Based Rehabilitatio Component 1: Support for so n services for persons with di cial services for vulnerable g Request for Quota Single Stage - One E TF / B7390 Post Open - National 0.00 Signed 2022-07-13 2022-07-26 2022-09-07 2023-03-06 sabilities and for older perso roups affected by the explos tions nvelope ns and, capacity Building & tr ion aining of care workers/NGO s taff LB-IRC-303382-NC-RFQ / Ass Component 1: Support for so istance to Mobile Medical Uni cial services for vulnerable g Request for Quota Single Stage - One E TF / B7390 Post Open - National 0.00 Signed 2022-07-13 2022-09-07 2023-10-31 ts & Fund NGO-run Primary H roups affected by the explos tions nvelope ealth Care Centres (PHCCs). ion LB-IRC-303383-NC-RFQ / De velopment of public sensitiza Component 1: Support for so tion awareness on mental he cial services for vulnerable g Request for Quota Single Stage - One E alth and for migrant domesti TF / B7390 Post Open - National 0.00 Canceled 2022-07-13 2022-07-26 2022-09-07 2023-10-31 roups affected by the explos tions nvelope c workers and training for mi ion grant and refugee Civil Socie ty Organizations (CSOs) work ing with domestic workers LB-IRC-303387-NC-RFQ / Est ablishment of shelter for boy Component 1: Support for so s under protection orders in cial services for vulnerable g Request for Quota Single Stage - One E Beirut/Mount Lebanon to pro TF / B7390 Post Open - National 0.00 Signed 2022-07-13 2022-07-26 2022-09-07 2023-10-31 roups affected by the explos tions nvelope vide and strengthen quality c ion hild protection services for b oys through the provision of psycho-social and life skills c ounseling. LB-IRC-303388-NC-RFQ / Exp anding the capacity of existin Component 1: Support for so g small shelters in Beirut/Mo cial services for vulnerable g Request for Quota Single Stage - One E Under Imple unt Lebanon to provide and s TF / B7390 Post Open - National 0.00 2022-07-13 2022-07-26 2022-09-07 2023-10-31 roups affected by the explos tions nvelope mentation trengthen quality GBV servic ion es for women and children th rough the provision of psych o-social and life skills counsel ing. LB-IRC-306080-NC-RFQ / Ass Component 1: Support for so isting with the provision of ed cial services for vulnerable g Request for Quota Single Stage - One E TF / B7390 Post Open - National 0.00 Canceled 2022-07-31 2022-08-03 2022-09-25 2023-10-31 ucation for children accompa roups affected by the explos tions nvelope nying women in existing shel ion ters Component 1: Support for so LB-IRC-306082-NC-RFQ / Su Request for Quota Single Stage - One E TF / B7390 cial services for vulnerable g Post Open - National 0.00 Signed 2022-07-31 2022-08-03 2022-09-25 2023-10-31 pport training hotline helpers tions nvelope roups affected by the explos ion LB-IRC-306085-NC-RFQ / De Component 1: Support for so velopment of Public Sensitiza cial services for vulnerable g Request for Quota Single Stage - One E TF / B7390 Post Open - National 0.00 Signed 2022-07-31 2022-08-03 2022-09-25 2023-10-31 tion Awareness for GBV survi roups affected by the explos tions nvelope vors and women at risk ion LB-IRC-306089-NC-RFQ / Str Component 1: Support for so engthening Identification & R cial services for vulnerable g Request for Quota Single Stage - One E TF / B7390 Post Open - National 0.00 Signed 2022-07-31 2022-08-03 2022-09-25 2023-10-31 eferral System through Com roups affected by the explos tions nvelope munity-Based Rehabilitation ion (CBR) LB-IRC-306091-NC-RFQ / Self Component 1: Support for so Request for Quota Single Stage - One E -Help Plus to targeted groups TF / B7390 cial services for vulnerable g Post Open - National 0.00 Canceled 2022-07-31 2022-08-03 2022-09-25 2023-10-31 tions nvelope , including online delivery roups affected by the explos ion LB-IRC-306092-NC-RFQ / Me Component 2: Capacity Buil Request for Quota Single Stage - One E TF / B7390 Post Open - National 0.00 Signed 2022-07-31 2022-08-03 2022-09-25 2023-10-31 ntal Health in the workplace ding and Project Manageme tions nvelope nt Component 1: Support for so 5LB/BEY/10/LB1041 / Procur Request for Quota Single Stage - One E TF / B7390 cial services for vulnerable g Post Open - National 39,400.00 Signed 2019-11-09 2020-01-04 2019-12-30 2020-07-02 ement of Fuel tions nvelope roups affected by the explos ion 5LB/BEY/20/LB1052.3 / Proc Component 1: Support for so Request for Quota Single Stage - One E urement of Venues and acco TF / B7390 cial services for vulnerable g Post Open - National 0.00 Canceled 2020-08-22 2020-10-17 2021-04-15 tions nvelope mmodation services roups affected by the explos ion LB-IRC-315377-NC-DIR / Proc Component 1: Support for so Request for Quota Single Stage - One E urement of Venue for team b TF / B7390 cial services for vulnerable g Post Limited 0.00 Canceled 2022-11-06 2023-01-01 2023-06-30 tions nvelope uilding retreat roups affected by the explos ion Component 1: Support for so LB-IRC-315198-NC-RFQ / Mai TF / B7390 cial services for vulnerable g Post Direct Selection Direct - National 0.00 Canceled 2022-10-01 2022-10-03 2022-10-06 2022-12-01 ntenance of Laptops roups affected by the explos ion LB-IRC-316707-NC-RFQ / Pro Component 1: Support for so Request for Quota Single Stage - One E curement of Lifeline system TF / B7390 cial services for vulnerable g Post Limited 0.00 Canceled 2023-02-06 2023-04-03 2023-09-30 tions nvelope update roups affected by the explos ion LB-IRC-319181-NC-RFQ / An Component 1: Support for so Request for Quota Single Stage - One E alyzing Software for Data coll TF / B7390 cial services for vulnerable g Post Limited 0.00 Canceled 2022-11-20 2023-03-27 2023-01-15 2023-07-14 tions nvelope ection roups affected by the explos ion LB-IRC-325166-NC-DIR / Ste Component 1: Support for so Direct - Internation p by Step Maintenance and I TF / B7390 cial services for vulnerable g Post Direct Selection 0.00 Signed 2022-11-07 2022-06-08 2022-11-12 2022-08-24 2022-12-17 2023-06-15 al mprovement roups affected by the explos ion LB-IRC-325374-NC-RFQ / Ass Component 1: Support for so isting with the provision of ed cial services for vulnerable g Request for Quota Single Stage - One E Under Imple TF / B7390 Post Open - National 0.00 2022-11-12 2022-11-08 2023-01-07 2023-07-06 ucation for children accompa roups affected by the explos tions nvelope mentation nying women in existing shel ion ters LB-IRC-315389-CS-QCBS / Pr Component 2: Capacity Buil Request for Quota Single Stage - One E ocurement of IT Maintenance TF / B7390 ding and Project Manageme Post Limited 0.00 Canceled 2022-10-06 2022-12-01 2023-05-30 tions nvelope and managed services consu nt ltant LB-IRC-343274-NC-RFQ / Out Component 1: Support for so door venue for 14 participant cial services for vulnerable g Request for Quota Single Stage - One E s for day out includes breakf TF / B7390 Post Limited 0.00 Canceled 2023-02-22 2023-04-19 2023-10-16 roups affected by the explos tions nvelope ast, Lunch, Activities (Ongoin ion g Games, Jsour elHawa, Valle y Zip Lines) LB-IRC-343370-NC-RFQ / Tea m Bonding Development Trai Component 1: Support for so ning for 14 people to improv cial services for vulnerable g Request for Quota Single Stage - One E TF / B7390 Post Limited 0.00 Canceled 2023-02-22 2023-04-19 2023-10-16 e team bonding. Build a high- roups affected by the explos tions nvelope performance team, improvin ion g communication skills, impr oving wellness. Page 2 5LB/BEY/19/LB1039 / Procur Component 1: Support for so Request for Quota Single Stage - One E ement of Transportation Serv TF / B7390 cial services for vulnerable g Post Open - National 0.00 Canceled 2019-09-14 2019-11-09 2020-05-07 tions nvelope ices roups affected by the explos ion LB-IRC-353431-NC-RFQ / De velopment of public sensitiza Component 1: Support for so tion awareness on mental he cial services for vulnerable g Request for Quota Single Stage - One E Under Imple alth and for migrant domesti TF / B7390 Post Open - National 0.00 2023-04-02 2023-03-31 2023-05-28 2023-11-24 roups affected by the explos tions nvelope mentation c workers and training for mi ion grant and refugee Civil Socie ty Organizations (CSOs) work ing with domestic workers LB-IRC-361317-NC-RFQ / Self Component 1: Support for so Request for Quota Single Stage - One E Under Imple -Help Plus to targeted groups TF / B7390 cial services for vulnerable g Post Open - National 0.00 2023-05-16 2023-05-11 2023-07-11 2024-01-07 tions nvelope mentation , including online delivery roups affected by the explos ion CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual LB-IRC-315374-CS-QCBS / Pr Component 1: Support for so Quality And Cost- ocurement of Communicatio TF / B7390 cial services for vulnerable g Post Open - National 0.00 Canceled 2022-09-15 2022-10-06 2022-11-19 2022-12-17 2023-01-16 2023-02-20 2023-03-27 2024-03-26 Based Selection n Consultant roups affected by the explos ion 1070162 / Consultancy for d eveloping public sensitization Component 1: Support for so awareness on the National Lif cial services for vulnerable g Fixed Budget Sele Pending Impleme TF / B7390 Post Open - National 0.00 2023-06-02 2023-06-23 2023-08-06 2023-09-03 2023-10-03 2023-11-07 2023-12-12 2024-12-11 eline and Step-by-Step with t roups affected by the explos ction ntation he National Mental Health Pr ion ogram (NMHP) at theMinistry of Public Health (MoPH) INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Actual Amount Invitation to Identifie Draft Negotiated Cont Component Review Type Method Contract Type Process Status Teams of Reference Signed Contract Contract Completion Description o. h (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual LB-IRC-283167-CS-INDV / Pr Component 2: Capacity Buil Individual Consult TF / B7344 Post Open 122,500.00 Signed 2021-07-14 2021-12-22 2021-09-01 2021-09-28 2021-09-22 2022-03-11 2021-10-27 2022-03-29 2023-10-31 oject Lead - Social Recovery ding and Project Manageme ant Selection Services nt LB-IRC-283118-CS-INDV / Pa Component 2: Capacity Buil Individual Consult TF / B7344 Post Open 70,250.00 Terminated 2021-07-17 2021-07-17 2021-09-04 2021-09-16 2021-09-25 2022-03-11 2021-10-30 2022-04-07 2022-04-28 rtnership Manager ding and Project Manageme ant Selection nt LB-IRC-286324-CS-INDV / En Component 1: Support for so Individual Consult vironmental and Social Speci TF / B7390 cial services for vulnerable g Post Open 0.00 Canceled 2022-03-23 2022-05-09 2022-05-11 2022-06-01 2022-07-06 2023-01-02 ant Selection alist roups affected by the explos ion LB-IRC-286388-CS-INDV / GB Component 1: Support for so Individual Consult V Standards Specialist (WPE TF / B7344 cial services for vulnerable g Post Open 50,681.00 Signed 2022-03-23 2021-07-16 2022-05-11 2021-10-21 2022-06-01 2022-03-24 2022-07-06 2022-05-17 2023-01-02 ant Selection Capacity Building and Partne roups affected by the explos rship Officer) ion LB-IRC-286685-CS-INDV / Pa Component 2: Capacity Buil Individual Consult TF / B7390 Post Open 73,909.00 Signed 2022-03-24 2021-07-26 2022-05-12 2021-09-01 2022-06-02 2022-03-25 2022-07-07 2022-04-13 2023-01-03 rtnership Finance Manager ding and Project Manageme ant Selection nt LB-IRC-286692-CS-INDV / Pa Component 2: Capacity Buil Individual Consult TF / B7390 Post Open 42,739.00 Signed 2022-03-24 2021-07-26 2022-05-12 2021-09-21 2022-06-02 2022-03-25 2022-07-07 2022-05-06 2023-01-03 rtnership Finance Assistant ding and Project Manageme ant Selection nt LB-IRC-286699-CS-INDV / Sa Component 1: Support for so Individual Consult feguarding and Quality Speci TF / B7344 cial services for vulnerable g Post Open 60,565.00 Signed 2022-03-24 2021-07-15 2022-05-12 2021-09-13 2022-06-02 2022-03-25 2022-07-07 2022-04-21 2023-01-03 ant Selection alist (Senior MEAL Officer) roups affected by the explos ion LB-IRC-286847-CS-INDV / Se Component 2: Capacity Buil Individual Consult TF / B7390 Post Open 0.00 Signed 2022-03-25 2022-04-29 2022-05-13 2022-08-23 2022-06-03 2022-09-08 2022-07-08 2023-01-04 nior Finance Officer ding and Project Manageme ant Selection nt LB-IRC-287066-CS-INDV / Se Component 2: Capacity Buil Individual Consult TF / B7390 Post Open 47,042.00 Signed 2022-03-28 2022-04-29 2022-05-16 2022-06-06 2022-06-06 2022-06-22 2022-07-11 2022-07-26 2023-01-07 nior Partnerships Officer ding and Project Manageme ant Selection nt LB-IRC-287740-CS-INDV / Se Component 2: Capacity Buil Individual Consult TF / B7390 Post Direct 0.00 Canceled 2022-03-31 2022-04-10 2022-05-01 2022-06-05 2022-12-02 nior Finance Manager ding and Project Manageme ant Selection nt LB-IRC-287821-CS-INDV / Su Component 2: Capacity Buil Individual Consult TF / B7390 Post Direct 0.00 Signed 2022-03-31 2022-06-29 2022-04-10 2022-05-01 2022-05-01 2022-05-01 2022-06-05 2022-12-02 pply Chain Officer ding and Project Manageme ant Selection nt Component 1: Support for so LB-IRC-287849-CS-INDV / He Individual Consult TF / B7390 cial services for vulnerable g Post Direct 28,462.00 Signed 2022-03-31 2022-06-14 2022-04-10 2022-04-01 2022-05-01 2022-04-01 2022-06-05 2022-04-02 2022-12-02 alth Technical Manager ant Selection roups affected by the explos ion Component 1: Support for so LB-IRC-288893-CS-INDV / GB Individual Consult TF / B7344 cial services for vulnerable g Post Direct 12,920.00 Signed 2022-04-07 2022-06-14 2022-04-17 2022-04-01 2022-05-08 2022-04-01 2022-06-12 2022-04-02 2022-12-09 V Technical Manager ant Selection roups affected by the explos ion LB-IRC-288899-CS-INDV / Ch Component 1: Support for so Individual Consult ild Protection Technical Mana TF / B7344 cial services for vulnerable g Post Direct 0.00 Canceled 2022-04-07 2022-04-17 2022-05-08 2022-06-12 2022-12-09 ant Selection ger roups affected by the explos ion LB-IRC-289324-CS-INDV / Di Component 1: Support for so Individual Consult sability and Elderly Technical TF / B7390 cial services for vulnerable g Post Open 0.00 Canceled 2022-04-08 2021-11-16 2022-05-27 2022-06-17 2022-07-22 2023-01-18 ant Selection Manager roups affected by the explos ion LB-IRC-288897-CS-INDV / Ch Component 1: Support for so Individual Consult ild Protection Technical Advis TF / B7344 cial services for vulnerable g Post Direct 10,032.00 Signed 2022-04-07 2022-06-29 2022-04-17 2022-04-01 2022-05-08 2022-04-01 2022-06-12 2022-04-02 2022-12-09 ant Selection or roups affected by the explos ion Component 1: Support for so LB-IRC-288888-CS-INDV / GB Individual Consult TF / B7344 cial services for vulnerable g Post Direct 4,208.00 Signed 2022-04-07 2022-06-29 2022-04-17 2022-04-01 2022-05-08 2022-06-30 2022-06-12 2022-04-02 2022-12-09 V Technical Advisor ant Selection roups affected by the explos ion Component 1: Support for so LB-IRC-287843-CS-INDV / He Individual Consult TF / B7344 cial services for vulnerable g Post Direct 18,605.00 Signed 2022-03-31 2022-06-29 2022-04-10 2022-04-01 2022-05-01 2022-04-01 2022-06-05 2022-04-02 2022-12-02 alth Technical Advisor ant Selection roups affected by the explos ion LB-IRC-307410-CS-INDV / Pa Component 2: Capacity Buil Individual Consult TF / B7390 Post Open - National 0.00 Signed 2022-08-03 2022-07-26 2022-09-21 2022-09-14 2022-10-12 2022-09-23 2022-11-16 2023-05-15 rtnership Manager ding and Project Manageme ant Selection nt Page 3 LB-IRC-311569-CS-INDV / Di Component 1: Support for so Individual Consult sability and Elderly Technical TF / B7390 cial services for vulnerable g Post Limited 0.00 Signed 2022-08-23 2022-07-05 2022-08-28 2022-02-22 2022-09-18 2022-08-05 2022-10-23 2023-04-21 ant Selection Manager roups affected by the explos ion LB-IRC-311582-CS-INDV / En Component 1: Support for so Individual Consult vironmental and Social Speci TF / B7390 cial services for vulnerable g Post Limited 0.00 Signed 2022-08-23 2022-05-09 2022-08-28 2022-06-22 2022-09-18 2022-07-18 2022-10-23 2023-04-21 ant Selection alist roups affected by the explos ion LB-IRC-323346-CS-INDV / Se Component 2: Capacity Buil Individual Consult TF / B7390 Post Open - National 0.00 Signed 2022-10-26 2022-10-31 2022-12-14 2022-11-23 2023-01-04 2022-12-13 2023-02-08 2023-08-07 nior Partnerships Officer ding and Project Manageme ant Selection nt LB-IRC-346945-CS-INDV / Sa Component 2: Capacity Buil Individual Consult Under Implement TF / B7390 Post Open - National 0.00 2022-12-21 2023-02-06 2023-02-08 2023-01-31 2023-03-01 2023-04-05 2023-10-02 feguarding and Quality Speci ding and Project Manageme ant Selection ation alist nt LB-IRC-352313-CS-INDV / GB Component 2: Capacity Buil Individual Consult Under Implement TF / B7390 Post Open - National 0.00 2023-03-24 2023-03-16 2023-05-12 2023-06-02 2023-07-07 2024-01-03 V Technical Manager ding and Project Manageme ant Selection ation nt LB-IRC-358873-CS-INDV / Vi Component 2: Capacity Buil Individual Consult Under Implement TF / B7390 Post Open - National 0.00 2023-04-27 2023-04-28 2023-06-15 2023-07-06 2023-08-10 2024-02-06 deo Animator ding and Project Manageme ant Selection ation nt LB-IRC-359886-CS-INDV / Su Component 2: Capacity Buil Individual Consult Under Implement TF / B7390 Post Direct - National 0.00 2023-05-03 2023-05-29 2023-05-13 2023-04-28 2023-06-03 2023-04-28 2023-07-08 2024-01-04 pply Chain Officer ding and Project Manageme ant Selection ation nt LB-IRC-359898-CS-INDV / Su Component 2: Capacity Buil Individual Consult Under Implement TF / B7390 Post Direct - National 0.00 2023-05-03 2023-05-29 2023-05-13 2023-04-28 2023-06-03 2023-04-28 2023-07-08 2024-01-04 pply Chain Senior Officer ding and Project Manageme ant Selection ation nt LB-IRC-359899-CS-INDV / W Component 2: Capacity Buil Individual Consult Under Implement TF / B7390 Post Direct - National 0.00 2023-05-03 2023-05-29 2023-05-13 2023-04-28 2023-06-03 2023-05-01 2023-07-08 2024-01-04 PE Coordinator ding and Project Manageme ant Selection ation nt LB-IRC-359903-CS-INDV / Pa Component 2: Capacity Buil Individual Consult Under Implement TF / B7390 Post Direct - National 0.00 2023-05-03 2023-05-29 2023-05-13 2023-04-28 2023-06-03 2023-06-01 2023-07-08 2024-01-04 rtnership Finance Manager ding and Project Manageme ant Selection ation nt LB-IRC-359910-CS-INDV / Dri Component 2: Capacity Buil Individual Consult Under Implement TF / B7390 Post Direct - National 0.00 2023-05-03 2023-05-29 2023-05-13 2023-04-28 2023-06-03 2023-04-28 2023-07-08 2024-01-04 ver ding and Project Manageme ant Selection ation nt LB-IRC-359912-CS-INDV / Fin Component 2: Capacity Buil Individual Consult TF / B7390 Post Direct - National 0.00 Under Review 2023-05-03 2023-05-29 2023-05-13 2023-06-03 2023-07-08 2024-01-04 ance Manager ding and Project Manageme ant Selection nt LB-IRC-359915-CS-INDV / Dri Component 2: Capacity Buil Individual Consult Under Implement TF / B7390 Post Direct - National 0.00 2023-05-03 2023-05-29 2023-05-13 2023-05-01 2023-06-03 2023-05-01 2023-07-08 2024-01-04 ver ding and Project Manageme ant Selection ation nt Page 4 ROCUREMENT PLAN - Textual Part Project information: Fiscal Management Improvement Project (P172352) Project Implementation Agency: Ministerio de Hacienda Costa Rica Date of the Procurement Plan: March 27, 2021 Period covered by this Procurement Plan: From March 2021 to July 2022 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: Shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the National Procurement Legislation such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions: 1. The request for bids/request for proposals document shall require that Bidders/Proposers submitting Bids/Proposals present a signed acceptance at the time of bidding to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights. The Bank’s Anti- Corruption Guidelines and Sanctions Framework shall be incorporated into the national bidding documents by adding a page entitled “Letter of Acceptance of the World Bank’s Anti-Corruption Guidelines and Sanctions Framework”. 2. Contracts with an appropriate allocation of responsibilities, risks, and liabilities between the Borrower and the contractors/suppliers/consultants. 3. Rights for the Bank to review procurement documentation and activities. In accordance with the Procurement Regulations, each bidding document and contract shall include provisions stating the Bank's policy to sanction firms or individuals, found to have engaged in fraud and/or corruption as defined in the Procurement Regulations. In accordance with the Procurement Regulations, each bidding document and contract financed out of the proceeds of the Financing Agreement shall provide that bidders, suppliers, contractors and their subcontractors, agents, personnel, consultants, service providers, or suppliers shall permit the Bank to inspect all accounts, records and other documents relating to the bid submission and performance of the contract and to have said accounts and records audited by auditors appointed by the Bank. Acts intended to materially impede the exercise of the Bank's inspection and audit rights provided for in the Procurement Regulations constitute an obstructive practice as defined in the Regulations. 4. No bids shall be rejected solely because they fall below or exceed the estimated cost. All bids (including in the case when less than two bids are received) shall not be rejected, the procurement process shall not be cancelled, and new bids shall not be solicited without the Bank's prior written concurrence. The Bidding Documents template to be used under “national open competitive procurement arrangements” are subject to prior written concurrence by the Bank. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Not Applicable. Procurement of Second-hand Goods as specified under paragraph 5.11 of the Procurement Regulations: Not Applicable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: not applicable Works: not applicable. Hands-on Expanded Implementation Support (HEIS): not applicable. PROCUREMENT Costa Rica : Costa Rica Fiscal Management Improvement Project PLAN General Information Country: Costa Rica 2021-03-29 Bank’s Approval Date of the Original Procurement Plan: 2023-06-06 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P172352 GPN Date: 2021-11-24 Project Name: Costa Rica Fiscal Management Improvement Project Loan / Credit No: IBRD / 90750 Ministry of Finance Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CR-MOF-270061-GO-RFQ / A Strengthening the technolog Request for Quota Single Stage - One E dquisión de licencias para di IBRD / 90750 ical, institutional and operati Post Open - National 14,305.00 0.00 Canceled 2022-01-11 2022-03-08 2022-09-04 tions nvelope gitalización de expedientes onal environment CR-MOF-270106-GO-RFB / Si Strengthening the technolog stema de interoperabilidad p Open - Internationa Single Stage - One E IBRD / 90750 ical, institutional and operati Post Request for Bids 1,000,000.00 0.00 Canceled 2022-01-06 2022-01-11 2022-02-22 2022-03-24 2022-04-28 2022-10-25 ara la comunicación externa l nvelope onal environment e interna de sistemas CR-MOF-270563-GO-RFQ / Si Strengthening public expend Request for Quota Single Stage - One E Under Imple IBRD / 90750 Post Open - National 50,000.00 0.00 2022-12-20 2022-12-14 2023-02-14 2023-08-13 stema de Auditoría Interna iture management tions nvelope mentation CR-MOF-270112-GO-RFQ / E- Strengthening public expend Request for Quota Single Stage - One E IBRD / 90750 Post Open - National 550,000.00 0.00 Canceled 2022-04-04 2022-05-30 2022-11-26 Learning iture management tions nvelope CR-MOF-270103-GO-RFQ / Si Enhancing customs controls Request for Quota Single Stage - One E Pending Impl stema de Actas, de Correspo IBRD / 90750 Post Open - National 200,000.00 0.00 2024-05-07 2024-07-02 2024-12-29 and services tions nvelope ementation ndencia, Seguimiento de Info rmes CR-MOF-270333-GO-RFB / Si Strengthening the technolog Open - Internationa Single Stage - Two E stema de Arquitectura Empre IBRD / 90750 ical, institutional and operati Post Request for Bids 140,000.00 0.00 Canceled 2022-01-06 2022-02-09 2022-01-11 2022-02-11 2022-02-22 2022-03-29 2022-05-07 2022-06-11 2022-12-08 l nvelope sarial onal environment NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CR-MOF-267124-NC-RFB / A Strengthening public expend Open - Internationa Single Stage - Two E dquisición Sistema Financier IBRD / 90750 Prior Request for Bids 30,000,000.00 0.00 Canceled 2021-12-07 2022-03-31 2021-12-12 2022-06-16 2022-01-23 2022-08-01 2022-04-07 2022-05-12 2022-11-08 iture management l nvelope o - Administrativo y Recursos Humanos CR-MOF-267120-NC-RFB / A Enhancing customs controls Open - Internationa Single Stage - Two E IBRD / 90750 Prior Request for Bids 25,000,000.00 0.00 Canceled 2021-12-07 2022-03-25 2021-12-12 2022-06-24 2022-01-23 2022-07-29 2022-04-07 2022-05-12 2022-11-08 dquisición del Sistema Aduan and services l nvelope ero CR-MOF-267122-NC-RFB / A Enhancing efficiency and cli Open - Internationa Single Stage - Two E IBRD / 90750 Prior Request for Bids 25,000,000.00 0.00 Canceled 2021-12-07 2022-03-14 2021-12-12 2022-06-10 2022-01-23 2022-07-18 2022-04-07 2022-05-12 2022-11-08 dquisición Sistema Tributario ent orientation of tax admini l nvelope stration CR-MOF-270095-NC-RFQ / S Enhancing efficiency and cli ervicio de Digitalización y Ge Request for Quota Single Stage - One E IBRD / 90750 ent orientation of tax admini Post Open - National 1,812,071.00 0.00 Signed 2022-01-11 2022-03-08 2022-09-04 stor Documental en el Minist tions nvelope stration erio de Hacienda, según dem anda CR-MOF-270109-NC-RFQ / Si Project Management & Capa Request for Quota Single Stage - One E IBRD / 90750 Post Open - National 80,000.00 0.00 Canceled 2022-01-11 2022-03-08 2022-09-04 stema de Gestión de Docume city Building tions nvelope ntos UCP CR-MOF-270358-NC-RFB / C Strengthening the technolog Open - Internationa Single Stage - One E ontratación de servicios de n IBRD / 90750 ical, institutional and operati Prior Request for Bids 5,000,000.00 0.00 Canceled 2022-01-06 2022-01-11 2022-02-22 2022-03-24 2022-04-28 2022-10-25 l nvelope ube / seguridad onal environment CR-MOF-292346-NC-DIR / Co ntratación de un equipo de r Strengthening the technolog espuesta y recuperación ant IBRD / 90750 ical, institutional and operati Post Direct Selection Direct 650,000.00 841,877.33 Signed 2022-04-25 2022-04-26 2022-04-30 2022-04-28 2022-06-04 2022-05-07 2022-12-01 e incidentes para funcionar c onal environment omo recursos suplementarios en la organización actual del Ministerio de Hacienda CR-MOF-292347-NC-DIR / Co Strengthening the technolog ntratación de una plataforma IBRD / 90750 ical, institutional and operati Post Direct Selection Direct 650,000.00 642,000.00 Signed 2022-04-25 2022-04-27 2022-04-30 2022-04-28 2022-06-04 2022-05-04 2022-12-01 de Tesoro Digital en modalid onal environment ad CLOUD CR-MOF-267122-NC-RFB2 / Enhancing efficiency and cli Open - Internationa Single Stage - One E Under Imple IBRD / 90750 Prior Request for Bids 25,000,000.00 0.00 2022-11-16 2022-11-21 2023-01-02 2023-02-01 2023-02-28 2023-03-08 2023-09-04 Adquisición del Sistema Tribu ent orientation of tax admini l nvelope mentation tario stration CR-MOF-267124-NC-RFB2 / Strengthening public expend Open - Internationa Single Stage - One E Under Imple Adquisición del Sistema Fina IBRD / 90750 Prior Request for Bids 30,000,000.00 0.00 2022-11-16 2022-11-21 2023-01-02 2023-02-01 2023-03-06 2023-03-08 2023-09-04 iture management l nvelope mentation nciero y de Talento Humano CR-MOF-267120-NC-RFB2 / Enhancing customs controls Open - Internationa Single Stage - One E Under Imple IBRD / 90750 Prior Request for Bids 25,000,000.00 0.00 2022-11-16 2022-11-21 2023-01-02 2023-02-01 2023-02-28 2023-03-08 2023-09-04 Adquisición de Sistema Adua and services l nvelope mentation nero CR-MOF-326888-NC-RFB / C Strengthening the technolog Open - Internationa Single Stage - One E Under Imple ontratación de Servicios de N IBRD / 90750 ical, institutional and operati Prior Request for Bids 9,046,154.40 0.00 2023-03-01 2023-04-13 2023-03-06 2023-04-17 2023-05-17 2023-06-21 2023-12-18 l nvelope mentation ube e Interoperabilidad onal environment CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Page 1 Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CR-MOF-270092-CS-QCBS / Sistema informático para la c Enhancing customs controls Quality And Cost- IBRD / 90750 Post Open - National 150,000.00 0.00 Canceled 2022-01-06 2022-03-21 2022-01-27 2022-03-28 2022-03-12 2022-04-09 2022-05-09 2022-06-13 2022-07-18 2023-07-18 onsolidación de saldos de los and services Based Selection Grandes Contribuyentes Naci onales CR-MOF-270090-CS-QCBS / Sistema informático para el n Enhancing customs controls Quality And Cost- IBRD / 90750 Post Open - National 150,000.00 0.00 Canceled 2022-01-06 2022-03-14 2022-01-27 2022-03-15 2022-03-12 2022-04-09 2022-05-09 2022-06-13 2022-07-18 2023-07-18 uevo Modelo de Operación e and services Based Selection n Depósito Aduanero CR-MOF-270101-CS-QCBS / Sistema Supres (Sistema Úni Strengthening public expend Quality And Cost- IBRD / 90750 Post Open - National 700,000.00 0.00 Under Review 2022-03-30 2023-06-27 2022-04-20 2023-05-09 2022-06-03 2022-07-01 2022-07-31 2022-09-04 2022-10-09 2023-10-09 co de pago de recurso social, iture management Based Selection para la Tesorería) CR-MOF-270107-CS-QCBS / Project Management & Capa Quality And Cost- IBRD / 90750 Post Open - National 300,000.00 0.00 Canceled 2022-06-30 2022-07-21 2022-09-03 2022-10-01 2022-10-31 2022-12-05 2023-01-09 2024-01-09 Auditoría Externa city Building Based Selection CR-MOF-270110-CS-QCBS / Strengthening public expend Quality And Cost- Sistema Planificación y Banc IBRD / 90750 Post Open - National 2,500,000.00 0.00 Canceled 2022-03-30 2022-04-20 2022-06-03 2022-07-01 2022-07-31 2022-09-04 2022-10-09 2023-10-09 iture management Based Selection o de Proyectos CR-MOF-314561-CS-LCS / Co Project Management & Capa Least Cost Selecti Under Implement IBRD / 90750 Post Open - National 300,000.00 0.00 2022-09-19 2022-10-24 2022-10-10 2022-11-23 2022-10-28 2022-12-21 2022-11-25 2023-01-20 2022-11-28 2023-02-24 2022-12-13 2023-03-31 2023-09-27 ntratacion de Auditoría Exter city Building on ation na CR-MOF-356322-CS-QCBS / Servicios de Consultoría para Strengthening the technolog Quality And Cost- Open - Internationa Under Implement la definición e implementació IBRD / 90750 ical, institutional and operati Post 554,000.00 0.00 2023-05-15 2023-05-19 2023-06-05 2023-05-25 2023-07-19 2023-08-16 2023-09-15 2023-10-20 2023-11-24 2024-11-23 Based Selection l ation n de la arquitectura empresa onal environment rial en el Ministerio de Hacie nda CR-MOF-270096-CS-QCBS / Strengthening the technolog Quality And Cost- Open - Internationa Pliego de Capacitación de Cie IBRD / 90750 ical, institutional and operati Post 2,000,000.00 0.00 Canceled 2022-01-06 2022-04-01 2022-01-27 2022-04-01 2022-03-12 2022-04-09 2022-05-09 2022-06-13 2022-07-18 2023-07-18 Based Selection l rre de Brechas onal environment CR-MOF-363960-CS-QCBS / Strengthening the technolog Quality And Cost- Open - Internationa Pending Impleme Programa de Capacitación y IBRD / 90750 ical, institutional and operati Prior 2,000,000.00 0.00 2023-08-01 2023-08-22 2023-10-05 2023-11-02 2023-12-02 2024-01-06 2024-02-10 2025-02-09 Based Selection l ntation Entrenamiento Proyecto Haci onal environment enda Digital INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CR-MOF-226322-CS-INDV / C Project Management & Capa Individual Consult onsultor para el rol de Direct IBRD / 90750 Prior Open 864,000.00 0.00 Signed 2021-04-30 2021-04-21 2021-06-18 2022-09-14 2021-07-09 2023-02-15 2021-08-13 2027-08-13 city Building ant Selection or de Proyecto CR-MOF-226321-CS-INDV / C Project Management & Capa Individual Consult IBRD / 90750 Post Open 468,000.00 320,000.00 Signed 2021-04-30 2021-04-20 2021-06-18 2021-05-26 2021-07-09 2021-07-14 2021-08-13 2021-08-13 2027-08-13 onsultor para el rol de Asesor city Building ant Selection Financiero CR-MOF-226317-CS-INDV / C Project Management & Capa Individual Consult onsultor para el rol de Asesor IBRD / 90750 Post Open 468,000.00 156,000.00 Signed 2021-04-30 2021-04-20 2021-06-18 2021-06-15 2021-07-09 2021-07-13 2021-08-13 2021-08-13 2027-08-13 city Building ant Selection en Planificación y Monitoreo CR-MOF-226310-CS-INDV / C onsultor para el rol de Asesor Project Management & Capa Individual Consult IBRD / 90750 Prior Open 468,000.00 204,000.00 Completed 2021-04-30 2021-04-20 2021-06-18 2021-06-13 2021-07-09 2021-07-14 2021-08-13 2021-08-26 2027-08-13 2021-09-22 de Adquisiciones y Administr city Building ant Selection ación de Contratos CR-MOF-226319-CS-INDV / C Project Management & Capa Individual Consult onsultor para el rol de Coordi IBRD / 90750 Prior Open 720,000.00 352,000.00 Signed 2021-04-30 2021-04-21 2021-06-18 2021-07-13 2021-07-09 2021-08-05 2021-08-13 2021-08-13 2027-08-13 city Building ant Selection nador Componente I Egresos CR-MOF-226324-CS-INDV / C Project Management & Capa Individual Consult onsultor para el rol de Coordi IBRD / 90750 Prior Open 720,000.00 352,000.00 Signed 2021-04-30 2021-04-21 2021-06-18 2021-06-28 2021-07-09 2021-07-20 2021-08-13 2021-08-13 2027-08-13 city Building ant Selection nador Componente II y III Ing resos CR-MOF-226318-CS-INDV / C onsultor para el rol de Coordi Project Management & Capa Individual Consult IBRD / 90750 Prior Open 720,000.00 240,000.00 Signed 2021-04-30 2021-04-21 2021-06-18 2021-07-05 2021-07-09 2021-07-20 2021-08-13 2021-08-16 2027-08-13 nador Componente IV Gestió city Building ant Selection n del Cambio y RRHH CR-MOF-226320-CS-INDV / C Project Management & Capa Individual Consult onsultor para el rol de Coordi IBRD / 90750 Prior Open 720,000.00 240,000.00 Signed 2021-04-30 2021-04-21 2021-06-18 2021-07-13 2021-07-09 2021-07-20 2021-08-13 2021-08-13 2027-08-13 city Building ant Selection nador Componente IV Imple mentación TIC CR-MOF-238360-CS-INDV / C Project Management & Capa Individual Consult onsultor para el rol de Especi IBRD / 90750 Post Open 39,000.00 45,000.00 Signed 2021-06-07 2021-06-11 2021-07-26 2021-07-12 2021-08-16 2021-07-16 2021-09-20 2021-08-13 2022-03-19 city Building ant Selection alista en Gestión Socio Ambi ental Strengthening the technolog CR-MOF-252324-CS-INDV / C Individual Consult IBRD / 90750 ical, institutional and operati Post Direct 112,000.00 145,063.00 Signed 2021-09-10 2021-09-16 2021-09-20 2021-09-22 2021-10-11 2021-11-12 2021-11-15 2021-12-18 2022-05-14 onsultor Asesor experto Líder ant Selection onal environment CR-MOF-252335-CS-INDV / C Strengthening public expend Individual Consult onsultor Especialista en Egre IBRD / 90750 Post Direct 102,000.00 105,000.00 Signed 2021-09-10 2021-09-16 2021-09-20 2021-09-22 2021-10-11 2021-11-12 2021-11-15 2022-01-29 2022-05-14 iture management ant Selection sos-Especialista en Finanzas CR-MOF-252338-CS-INDV / C Strengthening the technolog Individual Consult onsultor Especialista en Tran IBRD / 90750 ical, institutional and operati Post Direct 70,850.00 106,780.00 Signed 2021-09-10 2021-09-16 2021-09-20 2021-09-22 2021-10-11 2021-11-12 2021-11-15 2022-01-02 2022-05-14 ant Selection sformación Digital onal environment CR-MOF-252994-CS-INDV / C Enhancing customs controls Individual Consult onsultor Especialista en Ingre IBRD / 90750 Post Direct 90,600.00 121,232.00 Signed 2021-09-13 2021-09-16 2021-09-23 2021-09-22 2021-10-14 2021-11-12 2021-11-18 2021-12-18 2022-05-17 and services ant Selection sos-Especialista en Aduanas CR-MOF-254654-CS-INDV / C onsultor para el rol de Asesor Project Management & Capa Individual Consult IBRD / 90750 Prior Open 468,000.00 240,000.00 Signed 2021-09-22 2021-09-22 2021-11-10 2021-10-22 2021-12-01 2022-03-09 2022-01-05 2021-10-30 2022-07-04 de Adquisiciones y Administr city Building ant Selection ación de Contratos CR-MOF-254858-CS-INDV / C Project Management & Capa Individual Consult onsultor Especialista en Gesti IBRD / 90750 Post Open 54,000.00 48,000.00 Signed 2021-09-24 2021-09-23 2021-11-12 2021-10-21 2021-12-03 2021-10-29 2022-01-07 2021-10-30 2022-07-06 city Building ant Selection ón Documental Page 2 CR-MOF-270111-CS-INDV / C onsultor en planificación y pr esupuesto orientado a result Strengthening the technolog ados y capacitación y asesor Individual Consult Under Implement IBRD / 90750 ical, institutional and operati Post Open 150,000.00 0.00 2022-05-30 2022-10-26 2022-07-18 2022-10-27 2022-08-08 2023-02-10 2022-09-12 2023-03-11 amiento el ciclo de planificaci ant Selection ation onal environment ón por resultados y vinculaci ón plan - presupuesto bajo el enfoque de gestión de result ados y la cadena de resultad os CR-MOF-326883-CS-INDV / C Project Management & Capa Individual Consult Under Implement IBRD / 90750 Post Open - National 220,000.00 0.00 2022-12-15 2023-01-11 2023-02-02 2023-03-10 2023-02-23 2023-03-31 2023-03-30 2023-09-26 ontratación de Gestor Socio city Building ant Selection ation Ambiental CR-MOF-326887-CS-INDV / C Project Management & Capa Individual Consult IBRD / 90750 Post Direct - National 220,000.00 0.00 Signed 2022-12-01 2022-12-07 2022-12-11 2022-12-09 2023-01-01 2022-12-13 2023-02-05 2023-08-04 ontratación de Gestor Docum city Building ant Selection ental CR-MOF-270097-CS-INDV / C Strengthening the technolog Individual Consult Direct - Internation Under Implement ontratación de un conciliador IBRD / 90750 ical, institutional and operati Post 30,000.00 0.00 2023-02-01 2023-06-26 2023-02-11 2023-03-04 2023-04-08 2023-10-05 ant Selection al ation para desarrollos de sistemas onal environment de información CR-MOF-270104-CS-INDV / C onsultor para el desarrollo de Strengthening the technolog una estrategia para la adopci Individual Consult Open - Internationa Pending Impleme IBRD / 90750 ical, institutional and operati Post 50,000.00 0.00 2024-01-01 2024-02-19 2024-03-11 2024-04-15 2024-10-12 ón de la versíon 2014 del Ma ant Selection l ntation onal environment nual de Estadísticas de Finan zas Públicas deL FMI en el SP NF Page 3 WB Plan/ Estimated STATUS/ N Procur. Review Description Actu Cost COMMENT o Method (Prior/ al (in US$) S Post) GOODS (CURRENT) SCINHP/G/SH/2016-1 / Office plan RFQ Post Completed 20,000 1 equipment purchase (for MoT and actua ALRI) l 15,257 SCINHP/G/SH/2016-2 / Office plan RFQ Post Completed 20,000 2 furniture purchase (for MoT and actua ALRI) l 9,642 plan RFQ Post Under SCINHP/G/SH/2016-3 / Software 40,000 3 Implementa purchase actua tion l - plan RFQ Post Under SCINHP/G/SH/2016-04 / Purchase of 99,000 4 Implementa two SUV vehicle (4x4) actua tion l - plan 179,000 Total Goods (Current) actu 24,899 al CONSULTING SERVICES (CURRENT) plan QCBS Prior Under SCINHP/QCBS/2016-01 / Feasibility 950,000 5 Implementa Study and Detail Design for Bridges actua tion l 1,117,229 SCINHP/CQS/2016-01 / Feasibility Under plan CQS Prior 6 Study and Detail Design for flood 400,000 Implementa management activities in Kurgan- tion Tube area actua l 453,960 SCINHP/CQS/2016-02 / Feasibility plan CQS Prior Under Study and Detail Design for flood 400,000 7 Implementa management activities in Kulyab actua tion area l 336,346 SCINHP/IC/2016-08 / International plan IC Post Under 100,000 8 consultant on flood management Implementa actua activities (for MoF PIU) tion l 92,500 plan IC Post Under SCINHP/IC/2016-01 / Local Bridge 21,760 9 Implementa Engineer Consultant (for MoT) actua tion l 12,000 SCINHP/IC/2016-02 / Local plan IC Post Under Environmental Consultant for the 16,320 10 Implementa development of the EIA studies for actua tion bridges rehabilitation (for MoT) l 11,520 SCINHP/IC/2016-03 / Local Social plan IC Post 16,320 Under Consultant for the development of 11 Implementa the RPF studies for capital works for actua tion the flood protection (for MoT) l 11,520 plan IC Post Under SCINHP/IC/2016-04 / Local Flood 17,000 12 Implementa Engineer Consultant (for ALRI) actua tion l 14,400 SCINHP/IC/2016-05 / Local Environmental Consultant for the plan IC Post Under 16,320 13 development of EIA and the RPF Implementa studies for capital works for the actua tion flood protection (for ALRI) l 11,520 SCINHP/IC/2016-06 / Local Social Under Consultant for the development of plan IC Post Implementa 14 16,320 the RPF studies for capital works for tion the flood protection (for ALRI) actua l 11,520 plan IC Post Under SCINHP/IC/2016-07 / Project 20,400 15 Implementa Coordinator (for MoF PIU) actua tion l 14,400 Total Consulting Services plan (Current) 1,974,440 actu 2,086,915 al AUDITS plan Block Prior Pending 20,500 16 SCINHP/LCS/2016 / Project Audit Implementa actua Audit tion l 10,500 Operating costs (Current) plan 72,525 actu 72,525 al Unallocated funds (Current) plan 253,535 actu 83,146 al GENERAL TOTAL (CURRENT) plan 2,500,000 actu 2,277,985 al Saved Funds from current PPA: 222,015 GOODS (ADDITIONAL) SCINHP/G/ICB/2017-1/ Heavy Proposed / 17 RFB Prior Machinery for MoT and ALRI 1,950,000 Additional Total Goods (Additional) 1,950,000 CONSULTING SERVICES (ADDITIONAL) Increase SCINHP/QCBS/2016-01 / Feasibility Current Proposed / 18 Study and Detail Design for Bridges Prior 1,120,000 Contract Additional (9 additional bridges) Scope SCINHP/CQC/2016-01 / Feasibility Increase Study and Detail Design for flood Current Proposed / 19 management activities in Kurgan- Prior 230,000 Contract Additional Tube area (Additional restoration Scope work) SCINHP/CQC/2016-02 / Feasibility Increase Study and Detail Design for flood Current Proposed / 20 Prior management activities in Kulyab 120,000 Contract Additional area (Additional restoration work) Scope SCINHP/LCS (or CQS)/2017-01 / Designs and Specifications for Crisis Management Center, Emergency Proposed / 21 CQS Post Communication System, Mobile 80,000 Additional Command and Communication Vehicle Total Consulting (Additional) 1,550,000 GENERAL TOTAL (ADDITIONAL) 3,500,000 GENERAL TOTAL (CURRENT) 2,500,000 GENERAL TOTAL (CURRENT+PROPOSED) 6,000,000 PROCUREMENT Tajikistan : Strengthening Critical Infrastructure against Natural Hazards PLAN General Information Country: Tajikistan Bank’s Approval Date of the Original Procurement Plan: 2016-09-15 Revised Plan Date(s): (comma delineated, leave blank if2023-06-04 none) Project ID: P158298 GPN Date: Project Name: Strengthening Critical Infrastructure against Natural Hazards Loan / Credit No: IDA / V0220, IDA / V1410, IDA / D2050, IDA / 60890 STATE INSTITUTION "Project Implementation Unit for Access to Green and Rural Development Finance" Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned SCINHP/NCB-W-01 / Constru Making Critical Infrastructur ction of the NCMC in accorda Single Stage - One E 2020-10-0 IDA / D2050 e Resilient against Natural H Post Request for Bids Open - National 2,100,000.00 0.00 Canceled 2020-02-02 2020-01-28 2020-02-07 2020-02-07 2020-03-12 2020-03-08 2020-06-03 2020-04-12 nce with the approved detail nvelope 9 azards ed design and layout SCINHP-NCB-W-01 / Constru ction of the NCMC in accorda Strengthening Disaster Risk Single Stage - One E 1,849,759.5 2021-04-2 IDA / D2050 Post Request for Bids Open - National 2,100,000.00 Terminated 2020-07-21 2020-06-23 2020-07-26 2020-08-25 2020-07-23 2020-09-24 2020-08-07 2020-10-29 2020-10-27 nce with the approved detail Management Capacity nvelope 2 7 ed design and layout SCINHP/NCB-W-02 / NCMC c Request for Bids - onstruction in progress in acc Strengthening Disaster Risk Single Stage - One E Small Works SPD 2,199,074.2 2023-03-0 IDA / D2050 Post Request for Bids Open - National 2,100,000.00 Signed 2022-06-02 2022-06-02 2022-06-07 2022-07-07 2022-06-30 2022-08-06 2022-07-12 2022-09-10 2022-07-19 ordance with the approved d Management Capacity nvelope (1 envelope proce 0 9 esign solution and layout ss) GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SCINHP/G/SH/2016-1 / Office Strengthening Disaster Risk Request for Quota Single Stage - One E IDA / V0220 Post Open - National 20,000.00 11,633.33 Completed 2016-10-26 2016-12-21 2016-08-24 2017-06-19 2016-09-15 equipment purchase (for MoT Management Capacity tions nvelope and ALRI) SCINHP/G/SH/2016-2 / Office Strengthening Disaster Risk Request for Quota Single Stage - One E IDA / V0220 Post Open - National 20,000.00 7,366.76 Completed 2016-11-06 2017-01-01 2017-01-20 2017-06-30 2017-02-01 furniture purchase (for MoT a Management Capacity tions nvelope nd ALRI) SCINHP/G/SH/2016-4 / Purch Request for Quota Single Stage - One E IDA / V0220 Post Open - National 60,000.00 0.00 Canceled 2016-11-07 2017-01-02 2017-07-01 ase of vehicle (4x4) tions nvelope SCINHP/G/ICB/2017-1 / Heav Making Critical Infrastructur Open - Internationa Single Stage - One E IDA / V0220 Prior Request for Bids 1,950,000.00 1,700,004.00 Completed 2017-05-08 2017-05-18 2017-05-13 2017-06-19 2017-06-24 2017-06-29 2017-07-24 2017-08-02 2017-08-28 2017-08-17 2018-02-24 2018-01-04 y Machinery for MOT and ALR e Resilient against Natural H l nvelope I azards SCINHP/G/SH/2016-3 / Softw Request for Quota Single Stage - One E IDA / V0220 Post Open - National 40,000.00 0.00 Canceled 2016-11-06 2017-01-01 2017-06-30 are purchase tions nvelope SCINHP/G/SH/2016-5 / Purch Making Critical Infrastructur Request for Quota Single Stage - One E ase of drilling equipment and IDA / V1410 e Resilient against Natural H Post Open - National 100,000.00 98,600.00 Completed 2018-01-15 2018-03-12 2017-06-17 2018-09-08 2017-10-17 tions nvelope components azards SCINHP/G-SH-1 / Procureme Strengthening Disaster Risk Request for Quota Single Stage - One E IDA / V1410 Post Open - National 100,000.00 59,132.00 Completed 2018-01-15 2018-03-12 2019-07-11 2018-09-08 2019-08-29 nt of seismic stations for IoG Management Capacity tions nvelope EES SCINHP/G-SH-4 / Purchase of Request for Quota Single Stage - One E 1C Sowftware for PIU MOF, PI IDA / V1410 Project Management Post Open - National 20,000.00 13,350.87 Completed 2018-01-15 2018-03-12 2018-01-12 2018-09-08 2019-04-17 tions nvelope G MOT and PMU ALRI SCINHP/G-SH-5 / Procureme Request for Quota Single Stage - One E nt of furniture for PIU MOF, PI IDA / V1410 Project Management Post Open - National 10,000.00 0.00 Canceled 2018-01-15 2018-03-12 2018-09-08 tions nvelope G MT, PMU ALRI SCINHP/G/SH/2016-03 / Soft Making Critical Infrastructur Request for Quota Single Stage - One E IDA / V0220 Post Open - National 100,000.00 99,000.00 Completed 2018-01-15 2018-03-12 2017-06-15 2018-09-08 2017-08-25 ware purchase for MOT e Resilient against Natural H tions nvelope azards SCINHP/G-SH-2 / Procureme Strengthening Disaster Risk Request for Quota Single Stage - One E nt of IT equipment including IDA / V1410 Post Open - National 35,000.00 28,351.82 Completed 2018-01-15 2018-03-12 2018-07-18 2018-09-08 2018-09-04 Management Capacity tions nvelope software for IoGEES SCINHP/G-ICB-1 / Procureme Strengthening Disaster Risk Open - Internationa Single Stage - One E nt and installation of ICT equi IDA / V0220 Post Request for Bids 1,740,000.00 0.00 Canceled 2021-05-26 2021-07-12 2021-05-31 2021-07-13 2021-07-12 2021-08-26 2021-08-11 2021-12-15 2021-09-15 2022-03-14 Management Capacity l nvelope pment for NCMC SCINHP/G-ICB-2 / Procureme Strengthening Disaster Risk Open - Internationa Single Stage - One E nt of Mobile Command Cente IDA / V0220 Post Request for Bids 1,200,000.00 0.00 Canceled 2021-05-26 2021-07-12 2021-05-31 2021-07-13 2021-07-12 2021-08-26 2021-08-11 2021-12-15 2021-09-15 2022-03-14 Management Capacity l nvelope rs and Communication Vehicl es SCINHP/G/ICB-03 / Procurem ent and Installation of ICT eq Contingent Emergency Resp Open - Internationa Single Stage - One E Under Imple IDA / 60890 Prior Request for Bids 2,000,000.00 0.00 2023-03-01 2023-03-06 2023-03-06 2023-03-10 2023-04-17 2023-04-20 2023-05-17 2023-06-21 2023-12-31 uipment for National Crisis M onse Component l nvelope mentation anagement Center (NCMC) SCINHP/G-NCB-2 / Procurem Strengthening Disaster Risk Single Stage - One E Under Imple ent of office furniture and ac IDA / D2050 Post Request for Bids Open - National 320,000.00 0.00 2023-05-17 2023-06-07 2023-05-22 2023-07-03 2023-08-02 2023-09-06 2024-03-04 Management Capacity nvelope mentation cessories for NCMC SCINHP/G/SH/2016-04 / Purc Strengthening Disaster Risk Request for Quota Single Stage - One E IDA / V0220 Post Open - National 99,000.00 98,750.00 Completed 2016-11-14 2017-01-09 2017-05-31 2017-07-08 2017-07-18 hase of two SUV vehicle (4x4 Management Capacity tions nvelope ) NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Page 1 Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SCINHP/CQS/2016-01 / Feasi Making Critical Infrastructur bility Study and Detail Desig Consultant Qualifi IDA / V0220 e Resilient against Natural H Prior Open - National 400,000.00 527,462.00 Completed 2016-10-20 2016-11-02 2016-11-10 2016-11-02 2016-12-24 2016-12-20 2017-01-23 2016-12-23 2017-02-27 2016-12-23 2017-08-26 2018-12-23 n for flood management acti cation Selection azards vities in Kurgan-Tube area (lo cal company for ALRI) SCINHP/CQS/2016-02 / Feasi Making Critical Infrastructur bility Study and Detail Desig Consultant Qualifi IDA / V0220 e Resilient against Natural H Prior Open - National 400,000.00 446,316.00 Completed 2016-10-20 2016-11-02 2016-11-10 2016-11-02 2016-12-24 2016-12-20 2017-01-23 2016-12-23 2017-02-27 2016-12-23 2017-08-26 2021-05-20 n for flood management acti cation Selection azards vities in Kulyab area (local co mpany for ALRI) SCINHP/CQS/2017-01 / Prepa ration of detailed design and Strengthening Disaster Risk Consultant Qualifi bidding documents and speci IDA / V0220 Post Open - National 80,000.00 0.00 Canceled 2017-06-01 2017-06-22 2017-08-05 2017-09-04 2017-10-09 2018-04-07 Management Capacity cation Selection fications for the National Crisi s Management Center (NCMC ) SCINHP/QCBS-2017-01 / Pre paration of detailed design a nd bidding documents for the Strengthening Disaster Risk Quality And Cost- Open - Internationa National Crisis Management IDA / D2050 Post 430,000.00 526,341.24 Signed 2018-01-29 2018-01-08 2018-02-19 2018-01-31 2018-04-04 2018-06-13 2018-05-02 2018-08-10 2018-06-01 2018-10-05 2018-07-06 2018-10-26 2018-08-10 2018-12-19 2019-08-10 Management Capacity Based Selection l Center (NCMC), technical spe cifications of ICT equipments and Mobile Command and Co mmunication Vehicles SCINHP-CS-CQS-01 / Develo pment of Operational Manual for NCMC and capacity buildi ng of CMC staff by conductin Strengthening Disaster Risk Consultant Qualifi Open - Internationa IDA / V0220 Post 90,000.00 90,056.00 Signed 2021-11-22 2021-07-15 2021-12-13 2022-01-26 2021-12-15 2022-02-25 2022-02-16 2022-04-01 2022-02-17 2022-09-28 g trainings on CMC exploitati Management Capacity cation Selection l on, communication system w ork in crises, mobile commun ication vehicle work and Coor dination Center exploitation SCINHP-CS-CQS-02 / SUPERV ISION OF CONSTRUCTION "N Strengthening Disaster Risk Consultant Qualifi Under Implement IDA / D2050 Post Open - National 30,000.00 0.00 2022-06-16 2022-06-29 2022-07-07 2022-08-20 2022-09-19 2022-10-24 2023-06-21 ATIONAL CRISIS MANAGEME Management Capacity cation Selection ation NT CENTER" (NCMC) SCINHP/QCBS/2016-01 / Fea Making Critical Infrastructur Quality And Cost- Open - Internationa sibility Study and Detail Desi IDA / V0220 e Resilient against Natural H Prior 950,000.00 2,234,082.35 Completed 2016-09-14 2016-10-05 2016-10-10 2016-11-18 2016-10-21 2016-12-16 2016-11-21 2017-01-15 2016-12-01 2017-02-19 2017-01-04 2017-03-26 2016-12-23 2018-03-26 2018-10-31 Based Selection l gn for Bridges azards SCINHP/LCS/2016 / Project A IDA / V0220 Post Least Cost Selecti Open - Internationa 20,500.00 0.00 Canceled 2017-05-01 2017-05-22 2017-07-05 2017-08-02 2017-09-01 2017-10-06 2017-11-10 2018-05-09 udit on l INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SCINHP/IC/2016-01 / Local B Strengthening Disaster Risk Individual Consult IDA / V0220 Post Open 21,760.00 19,000.00 Completed 2016-10-13 2016-06-20 2016-12-01 2016-09-27 2016-12-22 2016-10-03 2017-01-26 2016-10-04 2017-07-25 2018-05-02 ridge Engineer Consultant (fo Management Capacity ant Selection r MoT) SCINHP/IC/2016-03 / Local S Strengthening Disaster Risk Individual Consult IDA / V0220 Post Open 16,320.00 11,520.00 Signed 2016-10-13 2016-06-24 2016-12-01 2016-07-28 2016-12-22 2016-08-01 2017-01-26 2016-08-02 2017-07-25 ocial Consultant (for MoT) Management Capacity ant Selection SCINHP/IC/2016-07 / Project Strengthening Disaster Risk Individual Consult IDA / V0220 Post Open 20,400.00 92,087.00 Signed 2016-10-13 2016-07-14 2016-12-01 2016-08-08 2016-12-22 2016-08-09 2017-01-26 2016-08-10 2017-07-25 Coordinator (for MoF PIU) Management Capacity ant Selection SCINHP/IC/2016-08 / Internat Strengthening Disaster Risk Individual Consult onal consultant on flood man IDA / V0220 Post Open 100,000.00 92,500.00 Completed 2016-10-20 2016-11-02 2016-12-08 2016-12-05 2016-12-29 2016-12-23 2017-02-02 2016-12-24 2017-08-01 2018-08-11 Management Capacity ant Selection agement activities (for MoF PIU) SCINHP-CS-IC-01 / FM Consul Individual Consult IDA / V1410 Project Management Post Open 50,400.00 42,000.00 Completed 2018-01-10 2017-10-10 2018-02-28 2017-11-30 2018-03-21 2017-12-01 2018-04-25 2017-12-13 2018-10-22 2022-12-11 tant for MOF PIU (full-time) ant Selection SCIHP-CS-IC-04 / Translator/ Individual Consult Enterpreter Consultant for M IDA / D2050 Project Management Post Open 50,400.00 16,800.00 Signed 2018-03-01 2018-02-20 2018-04-19 2018-04-18 2018-05-10 2018-05-01 2018-06-14 2018-05-01 2018-12-11 ant Selection OF PIU (full-time) SCINHP-CS-IC-02 / Environm IDA / D2050 Project Management Post Direct Selection Direct 58,560.00 46,080.00 Signed 2018-12-17 2018-12-17 2018-12-27 2018-12-19 2019-03-02 2018-12-22 2019-08-29 ent Safeguards Coordinator f or MOF PIU SCINHP-CS-IC-03 / Social iss IDA / D2050 Project Management Post Direct Selection Direct 58,560.00 46,080.00 Signed 2018-12-17 2018-12-17 2018-12-27 2018-12-19 2019-03-02 2018-12-22 2019-08-29 ues Consultant for MOF PIU SCINHP/CQS/2019-01 / Detai Making Critical Infrastructur led Design of Hoshadi canal s IDA / D2050 e Resilient against Natural H Post Direct Selection Direct 156,127.00 156,127.00 Completed 2019-07-14 2019-07-10 2019-07-24 2019-07-17 2019-09-27 2019-08-02 2020-03-25 2021-05-05 ite and Author Supervision in azards Kurgantyube Area SCINHP/CS-IC-2020-1 / Engin Strengthening Disaster Risk Individual Consult eer-consultant on constructio IDA / D2050 Post Open 18,000.00 21,600.00 Signed 2020-03-10 2020-07-28 2020-04-28 2021-02-01 2020-05-19 2021-02-02 2020-06-23 2021-02-03 2020-12-20 Management Capacity ant Selection n supervision SCINHP/CS-IC-2020-02 / Info Individual Consult rmation and Communications IDA / D2050 Project Management Post Open 18,000.00 19,200.00 Signed 2020-03-10 2020-03-10 2020-04-28 2020-07-27 2020-05-19 2020-07-29 2020-06-23 2020-08-04 2020-12-20 ant Selection Technology Consultant SCINHP/CS-IC-2020-03 / Proc Individual Consult IDA / D2050 Project Management Post Open 10,800.00 10,800.00 Completed 2020-05-17 2020-05-19 2020-07-05 2020-05-27 2020-07-26 2020-05-27 2020-08-30 2020-06-02 2021-02-26 2020-12-25 urement Consultant ant Selection SCINHP/CS-IC-2021-01 / Proc Individual Consult IDA / D2050 Project Management Post Open 10,800.00 10,800.00 Completed 2022-02-09 2022-02-10 2022-03-05 2022-02-24 2022-03-10 2022-02-25 2022-03-20 2022-02-26 2022-08-17 2022-08-02 urement Consultant ant Selection SCINHP-CS-SSS-01 / Detail a nd disclose all shop drawings , to prepare a bill of quantitie Strengthening Disaster Risk s and cost estimates based o IDA / D2050 Post Direct Selection Direct 11,000.00 11,425.29 Completed 2022-05-26 2022-05-26 2022-06-05 2022-05-27 2022-06-16 2022-05-28 2022-07-11 2022-06-28 Management Capacity n adapted shop drawings and determine the scope of existi ng defects for the NCMC buil ding of the CoESCD RT SCINHP/CS/IC/2022-01 / Proc Individual Consult IDA / D2050 Project Management Post Open - National 10,800.00 0.00 Signed 2022-09-25 2022-09-27 2022-11-13 2022-10-18 2022-12-04 2022-10-18 2023-01-08 2023-07-07 urement Consultant ant Selection Page 2 MOFPIU-TPRDP-DC-2022-01 / Strengthening Disaster Risk Under Implement IDA / D2050 Post Direct Selection Direct - National 6,500.00 0.00 2022-11-28 2022-11-28 2022-12-04 2022-12-13 2023-02-11 Environmental Consultant (s Management Capacity ation hort-term) MOFPIU-TPRDP-DC-2022-02 / Strengthening Disaster Risk Under Implement Social Development Consulta IDA / D2050 Post Direct Selection Direct - National 6,500.00 0.00 2022-11-28 2022-11-28 2022-12-04 2022-12-13 2023-02-11 Management Capacity ation nt (short-term) SCINHP/CS/IC/2022-02 / Fina Individual Consult Under Implement IDA / D2050 Project Management Post Open - National 8,400.00 0.00 2022-12-11 2022-12-08 2023-01-04 2023-01-07 2023-01-13 2024-01-03 ncial Management Consultan ant Selection ation t SCINHP/IC/2016-04 / Local Fl Strengthening Disaster Risk Individual Consult IDA / V0220 Post Open 17,000.00 14,400.00 Signed 2016-10-13 2016-06-20 2016-12-01 2016-09-29 2016-12-22 2016-10-13 2017-01-26 2016-10-14 2017-07-25 ood Engineer Consultant (for Management Capacity ant Selection ALRI) SCINHP/IC/2016-05 / Local E nvironmental Consultant for t Strengthening Disaster Risk Individual Consult he development of EIA and t IDA / V0220 Post Open 16,320.00 11,520.00 Signed 2016-10-13 2016-08-09 2016-12-01 2016-10-31 2016-12-22 2016-11-08 2017-01-26 2016-11-09 2017-07-25 Management Capacity ant Selection he RPF studies for capital wo rks for the flood protection (f or ALRI) SCINHP/IC/2016-02 / Local E nvironmental Consultant for t Strengthening Disaster Risk Individual Consult IDA / V0220 Post Open 16,320.00 11,520.00 Signed 2016-10-13 2016-06-20 2016-12-01 2016-10-31 2016-12-22 2016-11-01 2017-01-26 2016-11-02 2017-07-25 he development of the EIA st Management Capacity ant Selection udies for bridges rehabilitatio n (for MoT) SCINHP/IC/2016-06 / Local S ocial Consultant for the devel Strengthening Disaster Risk Individual Consult opment of EIA and the RPF st IDA / V0220 Post Open 16,320.00 11,520.00 Signed 2016-10-13 2016-08-09 2016-12-01 2016-10-13 2016-12-22 2016-10-14 2017-01-26 2016-10-15 2017-07-25 Management Capacity ant Selection udies for capital works for th e flood protection (for ALRI) Page 3 PROCUREMENT PLAN (Textual Part) Project information: Papua New Guinea, Emergency Tuberculosis Project (ETP), P-160947 Project Implementation agency: National Department of Health Date of the Procurement Plan: February 28, 2020 Period covered by this Procurement Plan: February 2020 to February 2021 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the National Procurement Act 2018, No. 12 of 2018, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. National preferences Eligibility: Eligibility to participate in a procurement process for and to be awarded a Bank financed contract shall be as defined under paragraphs 3.21-3.23 of the Procurement Regulations; accordingly, no bidder or potential bidder shall be declared ineligible for contracts financed by the Bank for reasons other than those provided in the said paragraphs. Foreign bidders shall be eligible to participate in bidding under the same conditions as national bidders. No domestic preference shall be granted in bid evaluation on the basis of bidder’s nationality, origin of goods or services, and/or preferential programs. Registration of bidders as Registration of bidders: condition for bidding Registration shall not be used to assess bidders’ qualifications. A foreign bidder shall not be required to register as a condition for submitting its bid, and a foreign bidder recommended for contract award shall be given a reasonable opportunity to register, with the reasonable cooperation of the Recipient, prior to contract signing. Procurement documents Procurement Documents: Templates of procurement documents, including contract forms, acceptable to the Association shall be used for all procurement financed by the Project. Document Fees Bidding Document Fees: A fee for bidding documents if applied must be reasonable and is to be used to offset the actual costs associated with reproduction of large bidding documents and associated plans and drawings. It is not to be used to generate revenue, or to limit or restrict participation in procurement processes. Bidding document fees are not to be charged for the procurement of consulting services (firms and individual), non-consulting services, or goods. Fraud and Corruption Fraud and Corruption: The procurement documents shall require that bidders submitting bids present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights. Negotiations and Cancellation of all bids: cancellation of All bids (or the sole bid if only one bid is procurement process received) shall not be rejected, the procurement process shall not be cancelled, and new bids shall not be solicited without the Bank’s prior written concurrence. Complaints Handling Complaints Review Mechanism: The Recipient shall establish and implement an effective, fair and timely complaints review mechanism allowing bidders to complain and to have their complaints handled in a timely manner. Until an adequate complaints review mechanism (as assessed by the Bank) is established the Bank’s review mechanism as set out in the Procurement Regulations will apply. Contract Award Notice Publication of Contract Award Notice: For purposes of Article 36(5) of the Act, within one month from award, a notice of all procurement contract awards shall include, at a minimum as relevant and applicable for each procurement method (a) the name of each bidder that submitted a bid; (b) bid prices as read out at bid opening; (c) evaluated prices of each bid that was evaluated; (d) the names of bidders whose bids were either rejected as nonresponsive or not meeting qualification criteria, or not evaluated, with the reasons thereof; and (e) the name of the winning bidder, the final total contract price, as well as the duration and a summary of the scope of the contract. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. The above captioned conditions also apply when approaching the international market. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Not Applicable Procurement of Second-Hand Goods as specified under paragraph 5.11 of the Procurement Regulations: Not Applicable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: is not applicable Works: is not applicable PROCUREMENT Papua New Guinea : Emergency Tuberculosis Project PLAN General Information Country: Papua New Guinea 2017-09-13 Bank’s Approval Date of the Original Procurement Plan: 2023-06-05 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P160947 GPN Date: 2017-08-24 Project Name: Emergency Tuberculosis Project Loan / Credit No: IDA / 60670 National Department of Health Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PG-NDOH-28385-GO-DIR / Pr ocurement of Medical Testing Early detection of active tub Equipment and consumables, IDA / 60670 Prior Direct Selection Direct 4.00 0.00 Canceled 2017-09-13 2017-09-18 2017-10-23 2018-04-21 erculosis patients TB medicine's if required and specialist vehicles. Procurem ent of LPA laboratory. PG-NDOH-28386-GO-RFQ / P Early detection of active tub Request for Quota Single Stage - One E urchase of Laptops and furnit IDA / 60670 Post Open - National 0.02 9,631.86 Completed 2017-09-18 2017-11-13 2019-04-02 2018-05-12 erculosis patients tions nvelope ure for PMU PG-NDOH-51604-GO-RFQ / C Early detection of active tub IDA / 60670 Post Direct Selection Direct 311,450.00 311,450.00 Signed 2018-03-30 2018-04-04 2018-05-09 2016-11-08 2018-11-05 ontainerized portable x-ray u erculosis patients nit PG-NDOH-52177-GO-RFQ / T Early detection of active tub Request for Quota Single Stage - One E ruck to carry the containerize IDA / 60670 Post Open - National 72,634.18 74,659.56 Signed 2018-04-04 2018-05-30 2016-12-02 2018-11-26 erculosis patients tions nvelope d x-ray unit. PG-NDOH-52183-GO-RFQ / M Early detection of active tub Request for Quota Single Stage - One E odifications to truck(Post initi IDA / 60670 Post Open - National 5,874.03 5,789.15 Completed 2018-04-04 2018-05-30 2017-09-04 2018-11-26 erculosis patients tions nvelope al procurement) PG-NDOH-52186-GO-RFQ / S Early detection of active tub Request for Quota Single Stage - One E IDA / 60670 Post Open - National 4,847.84 4,777.78 Completed 2018-04-04 2018-05-30 2018-05-05 2018-11-26 ignage for the truck erculosis patients tions nvelope PG-NDOH-52303-GO-UN / Dir ect Selection UN Agency spe Early detection of active tub UN Agencies (Dire cialized goods, equipment, c IDA / 60670 Prior Direct 4,000,000.00 2,999,646.00 Signed 2018-03-30 2018-06-01 2018-04-04 2019-02-06 2018-05-09 2019-01-14 2018-11-05 erculosis patients ct) onsumables, lab (and possibl y TB medicines) - UNOPS Strengthening government s PG-NDOH-90097-GO-RFQ / P ystems for managing its hea Request for Quota Single Stage - One E urchase 1 vehicle for Project IDA / 60670 Post Open - National 40,000.00 44,469.50 Completed 2019-02-11 2019-04-08 2019-07-26 2019-10-05 2019-09-02 lth services delivery and tub tions nvelope Coordinator erculosis response PG-NDOH-129403-GO-RFQ / Purchase of a 4 Wheel Drive f Early detection of active tub Request for Quota Single Stage - One E IDA / 60670 Post Open - National 45,000.00 40,180.00 Signed 2019-09-03 2019-10-29 2019-07-26 2020-04-26 or NCD Health to assist deliv erculosis patients tions nvelope ery ETP activities PG-NDOH-143827-GO-RFQ / Purchase of six Note Books, t Strengthening government s wo Laser Printers, two sets of ystems for managing its hea Request for Quota Single Stage - One E Printer Toners, six Microsoft IDA / 60670 Post Limited 10,307.00 11,655.36 Completed 2021-08-07 2020-02-21 2021-10-02 2020-03-31 2022-03-31 lth services delivery and tub tions nvelope Office, six Antivirus and six N erculosis response ote Book Bags for NCD Healt h and PMGH in support of TB program. Strengthening government s PG-NDOH-250962-NC-RFQ / I ystems for managing its hea Request for Quota Single Stage - One E CT Infrastructure Supply and IDA / 60670 Post Limited 16,000.00 15,496.88 Completed 2021-09-20 2019-01-09 2021-11-15 2019-03-15 2022-05-14 lth services delivery and tub tions nvelope Installation erculosis response Strengthening government s PG-NDOH-304137-NC-RFQ / ystems for managing its hea Request for Quota Single Stage - One E Vehicle Tracking System for t IDA / 60670 Post Limited 8,000.00 7,755.47 Signed 2022-07-27 2020-01-06 2022-08-16 2022-08-19 2024-03-31 lth services delivery and tub tions nvelope wo Project Vehicles erculosis response NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PG-NDOH-110121-NC-DIR / S Effective treatment of drug-s ervice providers in NCD to de IDA / 60670 usceptible and drug-resistan Prior Direct Selection Direct 2,800,000.00 2,862,184.00 Completed 2019-04-18 2019-08-16 2019-04-23 2020-01-06 2019-05-28 2020-04-04 2019-11-24 2022-11-27 liver community based TB se t tuberculosis patients rvices from October 2019 on wards PG-NDOH-329052-NC-RFQ / Effective treatment of drug-s HR/Finance Manager, Patient Request for Quota Single Stage - One E Under Imple IDA / 60670 usceptible and drug-resistan Post Limited 53,500.00 0.00 2022-12-09 2023-02-03 2024-01-31 Education and Counsellor (PE tions nvelope mentation t tuberculosis patients C)/Outreach Supervisor, and Logistics Supervisor. PG-NDOH-332132-NC-RFQ / Effective treatment of drug-s Procurement of Recruitment Request for Quota Single Stage - One E Pending Impl IDA / 60670 usceptible and drug-resistan Post Limited 475,000.00 0.00 2023-01-11 2023-02-09 2024-02-29 Firm for Non-Key Systematic tions nvelope ementation t tuberculosis patients Screening Intervention (SSI) Positions PG-NDOH-365428-NC-DIR / S ervice Provider to Support Co Effective treatment of drug-s mmunity-Based Tuberculosis Direct - Internation Under Imple IDA / 60670 usceptible and drug-resistan Prior Direct Selection 1,071,445.00 0.00 2023-06-12 2023-06-28 2023-06-17 2023-07-22 2024-01-31 Diagnostic and Treatment Se al mentation t tuberculosis patients rvices Delivery in the Nationa l Capital District (NCD) (Phas e II) Page 1 CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Strengthening government s PG-NDOH-51605-CS-UN / Dir ystems for managing its hea UN Agencies (Dire ect Selection of UN Agency t IDA / 60670 Prior Direct 3,200,000.00 2,979,810.00 Signed 2018-04-09 2018-11-05 2018-10-06 lth services delivery and tub ct) o provide TA support (WHO) erculosis response INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Strengthening government s PG-NDOH-28013-CS-INDV / A ystems for managing its hea Individual Consult IDA / 60670 Post Open 0.10 115,745.42 Completed 2017-09-11 2018-02-09 2017-10-30 2018-11-08 2017-11-20 2018-11-13 2017-12-25 2018-11-22 2018-06-23 ccountant lth services delivery and tub ant Selection erculosis response PG-NDOH-28014-CS-CDS / T Early detection of active tub IDA / 60670 Prior Direct Selection Direct 3.20 0.00 Canceled 2017-09-11 2017-10-06 2017-09-21 2017-11-25 2018-05-24 echnical Assistance by the U erculosis patients N Agency PG-NDOH-28387-CS-CDS / T echnical assistance for Tuber Early detection of active tub IDA / 60670 Post Direct Selection Direct 1.10 0.00 Canceled 2017-09-13 2017-09-23 2017-11-27 2018-05-26 culosis Patient Electronic rec erculosis patients ording and reporting system PG-NDOH-27561-CS-CQS / Pr Early detection of active tub Individual Consult IDA / 60670 Prior Open 450,000.00 1,014,141.80 Completed 2017-09-30 2017-09-29 2017-11-18 2017-12-09 2018-08-15 2018-01-13 2018-09-24 2018-07-12 2021-09-23 oject Coordinator erculosis patients ant Selection PG-NDOH-28011-CS-INDV / P Early detection of active tub Individual Consult IDA / 60670 Prior Open 0.20 283,750.43 Signed 2017-09-11 2018-01-22 2017-10-30 2019-06-18 2017-11-20 2019-07-10 2017-12-25 2019-07-17 2018-06-23 rocurement Specialist erculosis patients ant Selection PG-NDOH-44124-CS-INDV / A Strengthening government s dministration and Procureme ystems for managing its hea Individual Consult IDA / 60670 Post Open 0.10 0.00 Canceled 2018-01-17 2018-03-07 2018-03-28 2018-05-02 2018-10-29 nt Officer (Formally Finance lth services delivery and tub ant Selection Officer -IC-5) erculosis response Strengthening government s PG-NDOH-28390-CS-INDV / F ystems for managing its hea Individual Consult IDA / 60670 Post Open 193,000.00 0.00 Canceled 2017-09-13 2017-11-01 2017-11-22 2017-12-27 2018-06-25 inance Specialist lth services delivery and tub ant Selection erculosis response PG-NDOH-110123-CS-INDV / Strengthening government s Engagement of a consultant ystems for managing its hea Individual Consult to undertake environmental IDA / 60670 Post Open 15,000.00 2,361.56 Completed 2019-04-24 2019-04-29 2019-06-12 2019-06-18 2019-07-03 2019-07-15 2019-08-07 2019-07-05 2020-02-03 2019-10-03 lth services delivery and tub ant Selection and social assessment for th erculosis response e Impact Health Project Strengthening government s PG-NDOH-129387-CS-INDV / ystems for managing its hea Individual Consult Procurement and Administrat IDA / 60670 Post Open 100,000.00 27,724.51 Completed 2019-08-29 2019-08-29 2019-10-17 2020-02-25 2019-11-07 2020-02-27 2019-12-12 2020-03-10 2020-06-09 2022-04-01 lth services delivery and tub ant Selection ion Officer erculosis response Strengthening government s PG-NDOH-261286-CS-CDS / ystems for managing its hea IDA / 60670 Post Direct Selection Direct 15,000.00 14,107.50 Completed 2021-11-07 2021-09-29 2021-11-17 2021-09-29 2021-12-02 2021-10-03 2022-03-02 Audit Services lth services delivery and tub erculosis response Strengthening government s PG-NDOH-274846-CS-INDV / ystems for managing its hea Individual Consult IDA / 60670 Prior Open 450,000.00 0.00 Canceled 2022-03-04 2022-03-01 2022-05-08 2022-05-18 2022-06-12 2024-03-31 Project Coordinator lth services delivery and tub ant Selection erculosis response Strengthening government s PG-NDOH-289183-CS-INDV / ystems for managing its hea Individual Consult IDA / 60670 Post Direct 145,000.00 145,492.73 Completed 2022-04-22 2022-04-11 2022-05-02 2022-04-14 2022-05-07 2022-04-19 2022-05-17 2022-05-06 2023-02-11 2022-07-08 Project Coordinator lth services delivery and tub ant Selection erculosis response Strengthening government s PG-NDOH-300818-CS-INDV / ystems for managing its hea Individual Consult Procurement and Administrat IDA / 60670 Post Limited 38,000.00 0.00 Signed 2022-07-04 2022-06-23 2022-07-09 2022-11-29 2022-07-24 2022-12-05 2022-08-01 2023-03-29 lth services delivery and tub ant Selection ion Officer erculosis response Strengthening government s PG-NDOH-301270-CS-INDV / ystems for managing its hea Individual Consult Financial Management Speci IDA / 60670 Post Direct 80,000.00 0.00 Canceled 2022-07-01 2022-07-11 2022-07-21 2022-08-10 2024-03-31 lth services delivery and tub ant Selection alist (FMS) erculosis response Strengthening government s PG-NDOH-334496-CS-INDV / ystems for managing its hea Individual Consult Environmental Safeguard Sp IDA / 60670 Post Limited 50,000.00 0.00 Canceled 2023-01-16 2023-01-13 2023-01-21 2023-02-11 2023-03-18 2024-03-31 lth services delivery and tub ant Selection ecialist erculosis response Strengthening government s PG-NDOH-342639-CS-INDV / ystems for managing its hea Individual Consult Direct - Internation IDA / 60670 Post 141,345.00 0.00 Signed 2023-02-26 2023-03-19 2023-03-08 2023-03-20 2023-03-13 2023-03-20 2023-04-09 2023-10-31 Deputy Project Coordinator lth services delivery and tub ant Selection al erculosis response Strengthening government s PG-NDOH-347063-CS-INDV / ystems for managing its hea Individual Consult Under Implement IDA / 60670 Post Open - National 25,000.00 0.00 2023-03-13 2023-05-01 2023-05-01 2023-05-22 2023-06-26 2024-03-31 Accounts Officer lth services delivery and tub ant Selection ation erculosis response Strengthening government s PG-NDOH-347064-CS-INDV / ystems for managing its hea Individual Consult Open - Internationa Financial Management Speci IDA / 60670 Post 123,000.00 0.00 Canceled 2023-03-17 2023-05-05 2023-05-26 2023-06-30 2024-03-31 lth services delivery and tub ant Selection l alist erculosis response Strengthening government s PG-NDOH-347065-CS-INDV / ystems for managing its hea Individual Consult Open - Internationa Under Implement Monitoring & Evaluation Spec IDA / 60670 Post 123,000.00 0.00 2023-03-17 2023-05-01 2023-05-05 2023-05-26 2023-06-30 2024-03-31 lth services delivery and tub ant Selection l ation ialist erculosis response Strengthening government s PG-NDOH-347067-CS-INDV / ystems for managing its hea Individual Consult Monitoring & Evaluation Offic IDA / 60670 Post Open - National 38,000.00 0.00 Canceled 2023-03-17 2023-05-05 2023-05-26 2023-06-30 2024-03-31 lth services delivery and tub ant Selection er erculosis response Page 2 PG-NDOH-351208-CS-CDS / Strengthening government s Environmental, Social, Health ystems for managing its hea IDA / 60670 Post Direct Selection Direct - National 40,000.00 0.00 Signed 2023-03-26 2023-04-23 2023-04-05 2023-04-27 2023-04-20 2024-02-29 , Safety and Community Eng lth services delivery and tub agement Specialist erculosis response Strengthening government s PG-NDOH-360052-CS-INDV / ystems for managing its hea Individual Consult Financial Management Speci IDA / 60670 Post Limited 123,000.00 0.00 Canceled 2023-05-08 2023-05-13 2023-06-03 2023-07-08 2024-01-04 lth services delivery and tub ant Selection alist erculosis response Page 3 PROCUREMENT PLAN (Textual Part) Project information: Mauritania, Western Africa Regional Digital Integration Program (WARDIP) [P176932] Project Implementation agency: Ministere de la Transition Numerique, de l’Innovation et de la Modernisation de l’Administration (MTNIMA) Date of the Procurement Plan: December 22, 2021 Period covered by this Procurement Plan: December 22, 2021 - November 30, 2022 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in “le décret N° 2020-122 du 06 octobre 2020, modifiant et complétant certaines dispositions du décret N° 2017-126 du 02 novembre 2017, abrogeant et replaçant les dispositions des décrets d’applications de la loi N° 2010-044 du 22 juillet 2010”, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: [is not applicable]; Works: [is not applicable] Other Relevant Procurement Information. PROCUREMENT Western and Central Africa : Western Africa Regional Digital Integration Program SOP1 PLAN General Information Country: Western and Central Africa 2023-06-01 Bank’s Approval Date of the Original Procurement Plan: 2023-06-01 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P176932 GPN Date: Project Name: Western Africa Regional Digital Integration Program SOP1 Loan / Credit No: IDA / V4020 PCU Western Africa Regional Digital Integration Program Executing Agency(ies): WORKS Activity Reference No. / Procureme Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH Ri Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method nt Docume ount (US$ and Recommendation Signed Contract o. h cess (Y/N) sk atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion nt Type ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual WARDIP-F - 016-2023 / Mobil Component 5. Project Manag Request for Quota Single Stage - One E Pending Impl iário de escritório para a Unid IDA / V4020 ement and Implementation Post Open - National 0.00 2023-06-26 2023-08-21 2024-02-17 tions nvelope ementation ade de Gestão Support WARDIP-F - 017-2023 / IT an Component 5. Project Manag Request for Quota Single Stage - One E Pending Impl IDA / V4020 Post Open - National 0.00 2023-06-28 2023-08-23 2024-02-19 d Office Equipment ement and Implementation tions nvelope ementation Support WARDIP-F - 018-2023 / Stati Component 5. Project Manag Request for Quota Single Stage - One E Pending Impl IDA / V4020 Post Open - National 0.00 2023-07-03 2023-08-28 2024-02-24 onary ement and Implementation tions nvelope ementation Support WARDIP-F - 019-2023 / Com Component 5. Project Manag Request for Quota Single Stage - One E Pending Impl munication Devices (telepho IDA / V4020 ement and Implementation Post Open - National 0.00 2023-07-04 2023-08-29 2024-02-25 tions nvelope ementation ne, router, etc) Support NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual WARDIP-C - 006-2023 / Lega Component 1. Enabling envi l analysis of missing /outdate Quality And Cost- Open - Internationa Pending Impleme IDA / V4020 ronment for the establishme Post 0.00 2023-06-30 2023-07-21 2023-09-03 2023-10-01 2023-10-31 2023-12-05 2024-01-09 2025-01-08 d laws and regulations and re Based Selection l ntation nt of a continental SDM commendations for needed r eforms WARDIP-C - 007-2023 / Stud y of the national backbone: F Component 1. Enabling envi easibility (technical, financial Quality And Cost- Open - Internationa Pending Impleme IDA / V4020 ronment for the establishme Post 0.00 2023-06-19 2023-07-10 2023-08-23 2023-09-20 2023-10-20 2023-11-24 2023-12-29 2024-12-28 and governance), preparatio Based Selection l ntation nt of a continental SDM n of tender documents (DAO) , monitoring and evaluation ( M&E). WARDIP-C - 008-2023 / Stud y of (i) redundancy of interna Component 1. Enabling envi tional connectivity, (ii) sale of Quality And Cost- Open - Internationa Pending Impleme IDA / V4020 ronment for the establishme Post 0.00 2023-06-27 2023-07-18 2023-08-31 2023-09-28 2023-10-28 2023-12-02 2024-01-06 2025-01-05 excess capacity to neighbors Based Selection l ntation nt of a continental SDM , (iii) improvement of SCGB g overnance and (iv) improvem ent of FAU management WARDIP-C - 009-2023 / Feasi bility study for establishing a Component 3. Data Market Quality And Cost- Open - Internationa Under Implement n NREN and connecting it to t IDA / V4020 Development and Integratio Post 0.00 2023-07-15 2023-06-20 2023-08-05 2023-06-22 2023-09-18 2023-10-16 2023-11-15 2023-12-20 2024-01-24 2025-01-23 Based Selection l ation he Western and Central Afric n a Research and Education Ne twork (WACREN) WARDIP-C - 010-2023 / Stud y on government needs for a Security Operations Center ( Quality And Cost- Open - Internationa Under Implement SOC), Computer Emergency IDA / V4020 Component 6. CERC Post 0.00 2023-07-14 2023-06-20 2023-08-04 2023-06-22 2023-09-17 2023-10-15 2023-11-14 2023-12-19 2024-01-23 2025-01-22 Based Selection l ation Response Team (CERT) and n ational cloud, including a dat a sharing and infrastructure analysis and DAO WARDIP-C - 011-2023 / Gap analysis on (i) demand for di gital skills in the public and p Component 3. Data Market rivate sectors; (ii) current su Quality And Cost- Open - Internationa Pending Impleme IDA / V4020 Development and Integratio Post 0.00 2023-07-17 2023-08-07 2023-09-20 2023-10-18 2023-11-17 2023-12-22 2024-01-26 2025-01-25 pply of digital skills in the pri Based Selection l ntation n vate sector and public sector ; and (iii) suggestions on how to expand or strengthen exis ting and future programs and courses t WARDIP-C - 012-2023 / Gap analysis of the entrepreneurs Component 4. Online Market Quality And Cost- Open - Internationa hip ecosystem and needs of IDA / V4020 Development and Integratio Post 0.00 Under Review 2023-07-12 2023-06-22 2023-08-02 2023-09-15 2023-10-13 2023-11-12 2023-12-17 2024-01-21 2025-01-20 Based Selection l digital entrepreneurs and rec n ommended actions (DAO) WARDIP-C - 013-2023 / Detai Component 3. Data Market led analysis of digital payme Quality And Cost- Open - Internationa IDA / V4020 Development and Integratio Post 0.00 Under Review 2023-07-30 2023-06-22 2023-08-20 2023-10-03 2023-10-31 2023-11-30 2024-01-04 2024-02-08 2025-02-07 nts and financial digital servi Based Selection l n ces infrastructure WARDIP-C - 014-2023 / Feasi bility study for the developm Component 2. Connectivity Quality And Cost- Open - Internationa ent of an interoperability fra IDA / V4020 Market Development and Int Post 0.00 Under Review 2023-07-31 2023-06-22 2023-08-21 2023-10-04 2023-11-01 2023-12-01 2024-01-05 2024-02-09 2025-02-08 Based Selection l mework and platform, as well egration as digitalization of the main public services and DAO Page 1 WARDIP-C - 015-2023 / Tech nical assistance to the Minist Component 1. Enabling envi ry of Transport and Communi Quality And Cost- Open - Internationa Pending Impleme IDA / V4020 ronment for the establishme Post 0.00 2023-07-24 2023-08-14 2023-09-27 2023-10-25 2023-11-24 2023-12-29 2024-02-02 2025-02-01 cations for the development Based Selection l ntation nt of a continental SDM of human and institutional ca pacity in terms of digital tran sformation. INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Actual Amount Invitation to Identifie Draft Negotiated Cont Component Review Type Method Contract Type Process Status Teams of Reference Signed Contract Contract Completion Description o. h (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 2 PROCUREMENT PLAN General 1. Project Information a. Country: Federal Republic of Somalia b. Project Name: "Biyoole II" Second Water for Agro-Pastoral Productivity and Resilience II c. Project Number: P177627 d. Total Finance: USD 58 million 2. Project Implementation Agency: Ministry of Planning, Investment and Economic Development 3. Date of Project Plan: November 2022 4. Period Covered by this Procurement: November 2022 – May 2024 I. Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016 revised November 2017, August 2018 and November 2020 and) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. II. Bank’s Standard Procurement Document: The Bank’s standard Procurement Documents shall be used for all contracts subject to international competitive procurement and those contracts as specified into Procurement Plan tables in STEP III. National Procurement Arrangements: Not applicable IV. Prequalification: Not applicable V. Leased Assets: Not Applicable VI. Procurement of Second-hand Goods: Not Applicable VII. Domestic Preference: Not Applicable 1 VIII. Hands on Expanded Implementation Support (HEIS): Not applicable IX. Other Relevant Procurement Information: Not Applicable X. Thresholds for Procurement Approaches and Method (US$ millions) Based on the risks identified above, the following procurement arrangements are proposed: a) Approach to Market: Based on previous experience and available local market, the following threshold will be used of open national/international and RFQ bidding (all figures in million USD) Table 1.2: Thresholds for procurement approaches and methods Procurement Methods (US$ millions)–Goods, Works, and Non- Consulting Services Open Open Request for Direct Category Internatio National Quotation Selection nal (RfQ) Works ≥ 5.0 <5.0 ≤ 0.2 All Values Goods, IT, and non- ≥ 0.5 <0.5 ≤ 0.1 All Values consultin g services Thresholds for Procurement Approaches and Methods (US$, millions) – Consulting Services Category Short List of National Consultants Consulting Engineering and Services Construction Supervision Consultants (Firms) ≤ 0.1 ≤ 0.2 Individual Consultants n.a. n.a. Direct Selection Consultants (Firms) All Values All Values Individual Consultants All Values All Values 2 3 XI. Table Packages for Goods, Works and Non-Consulting Services (At Negotiations – to be entered in STEP) Selecti Expected Expected on date of date of Procurement Metho bid/ Contract Contract Title, Approach Ref. Estimated Bank d Evaluation proposal Signature Description and (Open- No Cost (US$) Oversight (RFP, Method opening Category National/ RFB, Limited etc.) RFQ etc.) Goods Most Office Furniture for 01/Nov/20 02/Feb/202 G1 Prior Open-National RFB advantageo the new officers 130,000.00 22 3 us Bid Most Supply of IT 01/Nov/20 02/Feb/202 G2 Prior Open-National RFB advantageo Equipment 140,000.00 22 3 us Bid Most Purchase of Office 01/Nov/20 02/Feb/202 250,000.00 Prior Open-National RFB advantageo G3 vehicles 22 3 us Bid Procurement and Most 01/Nov/20 02/Feb/202 G4 distribution of 210,000.00 Prior Open-National RFB advantageo 22 3 seeds and tools us Bid Sub-total 730,000.00 Works Most Construction of 4,800,000. 01/Dec/20 01/May/20 W1 Prior Open National RFB advantageo new water points 00 22 24 us Bid Most Rehabilitation of 3,800,000. 01/Dec/20 01/May/20 W2 Prior Open National RFB advantageo water points 00 22 24 us Bid 1 Selecti Expected Expected on date of date of Procurement Metho bid/ Contract Contract Title, Approach Ref. Estimated Bank d Evaluation proposal Signature Description and (Open- No Cost (US$) Oversight (RFP, Method opening Category National/ RFB, Limited etc.) RFQ etc.) Most Rangeland 2,300,000. 01/Dec/20 01/May/20 W3 Prior Open National RFB advantageo Rehabilitations 00 22 24 us Bid Sand dunes Most 1,200,000. 01/Dec/20 01/May/20 W4 rehabilitation and Prior Open National RFB advantageo 00 22 24 Restoration us Bid Most Fodder Production 1,500,000. 01/Dec/20 01/May/20 W5 Prior Open National RFB advantageo Fam 00 22 24 us Bid 13,600,000 Sub-total .00 Non-Consulting Services - none Consulting Services. Expected Expected Review by Market Approach Method (QCBS, date of date of Ref Contract Estimated Bank (Open-National/ LCBCS, QBS, bid/ Contract No. Description Cost (US$) (Prior/Post Limited etc.) DS proposal Signature ) opening Backstopping 1,700,000. 01/Nov/20 02/Apr/202 C1 Prior Open International QCBS Engineering firm 00 22 3 Third Party 1,500,000. 01/Nov/20 02/Apr/202 C2 Prior Open International QCBS Monitoring Firm 00 22 3 2 Expected Expected Review by Market Approach Method (QCBS, date of date of Ref Contract Estimated Bank (Open-National/ LCBCS, QBS, bid/ Contract No. Description Cost (US$) (Prior/Post Limited etc.) DS proposal Signature ) opening Security Risk 01/Nov/20 02/Apr/202 C3 Management Firm 1,000,000. Prior Open International QCBS 22 3 00 Project Coordinator 01/Nov/20 01/May/20 C4 144,000.00 Prior Open - National INDV FGS 22 24 Procurement INDV 01/Nov/20 01/May/20 C5 120,000.00 Prior Open - National Specialist FGS 22 24 01/Nov/20 01/May/20 C6 FM Specialist FGS Prior Open - National INDV 110,000.00 22 24 01/Nov/20 01/May/20 C7 GBV Specialist FGS 100,000.00 Prior Open - National INDV 22 24 C8 Environmental 01/Nov/20 01/May/20 100,000.00 Prior Open - National INDV Specialist FGS 22 24 C9 Security Specialist 01/Nov/20 01/May/20 100,000.00 Prior Open - National INDV FGS 22 24 C10 Community 01/Nov/20 01/May/20 Development/Social 100,000.00 Prior Open - National INDV 22 24 Specialist FGS C11 Monitoring and 01/Nov/20 01/May/20 100,000.00 Prior Open - National INDV Evaluation Specialist 22 24 C12 Communications 01/Nov/20 01/May/20 100,000.00 Prior Open - National INDV Specialist FGS 22 24 C13 State project 01/Nov/20 01/May/20 240,000.00 Prior Open - National INDV Coordinators 22 24 C14 State project 01/Nov/20 01/May/20 procurement 210,000.00 Prior Open - National INDV 22 24 specialists C15 State project FM 01/Nov/20 01/May/20 180,000.00 Prior Open - National INDV specialists 22 24 3 Expected Expected Review by Market Approach Method (QCBS, date of date of Ref Contract Estimated Bank (Open-National/ LCBCS, QBS, bid/ Contract No. Description Cost (US$) (Prior/Post Limited etc.) DS proposal Signature ) opening C16 State project Environmental 01/Nov/20 01/May/20 180,000.00 Prior Open - National INDV Safeguards 22 24 specialists C17 State project Social 01/Nov/20 01/May/20 Safeguards 180,000.00 Prior Open - National INDV 22 24 specialists C18 State project M&E 01/Nov/20 01/May/20 180,000.00 Prior Open - National INDV specialists 22 24 C19 01/Nov/20 01/May/20 Senior Engineers 210,000.00 Prior Open - National INDV 22 24 C20 Agricultural 180,000.00 01/Nov/20 01/May/20 Prior Open - National INDV specialist 22 24 180,000.00 01/Nov/20 01/May/20 C21 Livestock specialists Prior Open - National INDV 22 24 Environmental 180,000.00 01/Nov/20 01/May/20 C22 Prior Open - National INDV specialists 22 24 7,094,000. Sub-total 00 21,424,000 Grand-total .00 4 PROCUREMENT Somalia : Barwaaqo - Somalia Water for Rural Resilience Project PLAN General Information Country: Somalia 2023-02-22 Bank’s Approval Date of the Original Procurement Plan: 2023-06-06 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P177627 GPN Date: Project Name: Barwaaqo - Somalia Water for Rural Resilience Project Loan / Credit No: IDA / E1320 Ministry of Planning and National Development Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Request for Bids - SO-MOPND-SL-365137-CW-R Development of Environmen Single Stage - One E Small Works SPD Pending Imp 2024-04-0 FB / Office Construction for M IDA / E1320 tal Catchment Services in Pr Prior Request for Bids Open - National 340,000.00 0.00 2023-06-17 2023-06-22 2023-08-03 2023-09-02 2023-10-07 nvelope (1 envelope proce lementation 4 inistry of Environment and Cl oject Areas ss) imate Change SO-MOPND-SL-365141-CW-R Development of Agriculture Request for Quota Request for Quota Single Stage - One E Pending Imp 2024-02-1 FQ / Office Construction for M IDA / E1320 and Livestock Services Arou Prior Limited tions (Non Bank-S 170,000.00 0.00 2023-06-20 2023-08-15 tions nvelope lementation 1 inistry of Livestock and Fishe nd Water Points PD) ry Development GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SO-MOPND-SL-361040-GO-R Development of Environmen Single Stage - One E Under Revie FB / FRONT END LOADER - Eq IDA / E1320 tal Catchment Services in Pr Prior Request for Bids Open - National 360,000.00 0.00 2023-05-20 2023-06-25 2023-05-25 2023-06-22 2023-07-22 2023-08-26 2027-12-31 nvelope w uipment oject Areas NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SO-MOPND-SL-344283-CS-C Project Management, Comm Under Implement DS / Project Coordinator at PI IDA / E1320 unity-Driven Development a Prior Direct Selection Direct - National 58,500.00 0.00 2023-02-23 2023-02-23 2023-03-02 2023-02-23 2023-03-31 2024-03-01 ation U nd Enhancing Livelihoods Pl anning SO-MOPND-SL-344287-CS-C Project Management, Comm Under Implement DS / Procurement Specialist IDA / E1320 unity-Driven Development a Prior Direct Selection Direct - National 43,200.00 0.00 2023-02-23 2023-02-22 2023-03-05 2023-03-04 2023-03-31 2024-03-01 ation at PIU nd Enhancing Livelihoods Pl anning SO-MOPND-SL-344840-CS-IN Project Management, Comm Individual Consult Under Implement DV / Financial Management S IDA / E1320 unity-Driven Development a Prior Open - National 41,000.00 0.00 2023-02-27 2023-02-23 2023-04-17 2023-05-01 2023-05-29 2024-03-01 ant Selection ation pecialist nd Enhancing Livelihoods Pl anning SO-MOPND-SL-357292-CS-IN Project Management, Comm Individual Consult Under Implement DV / Communication Speciali IDA / E1320 unity-Driven Development a Prior Open - National 28,620.00 0.00 2023-04-22 2023-04-24 2023-05-13 2023-02-28 2023-05-20 2023-05-08 2023-06-10 2024-06-09 ant Selection ation st nd Enhancing Livelihoods Pl anning SO-MOPND-SL-357293-CS-IN Project Management, Comm Individual Consult Under Implement DV / Social Safeguard Special IDA / E1320 unity-Driven Development a Prior Open - National 39,840.00 0.00 2023-04-23 2023-04-25 2023-05-30 2023-04-08 2023-06-06 2023-05-08 2023-06-20 2024-06-19 ant Selection ation ist nd Enhancing Livelihoods Pl anning Project Management, Comm SO-MOPND-SL-357294-CS-IN Individual Consult Under Implement IDA / E1320 unity-Driven Development a Prior Open - National 39,840.00 0.00 2023-04-22 2023-04-25 2023-05-06 2023-05-16 2023-05-13 2023-05-30 2023-06-03 2024-06-02 DV / GBV Specialist ant Selection ation nd Enhancing Livelihoods Pl anning SO-MOPND-SL-357295-CS-IN Project Management, Comm Individual Consult Under Implement DV / Monitoring and Evaluati IDA / E1320 unity-Driven Development a Prior Open - National 39,840.00 0.00 2023-04-22 2023-04-25 2023-06-01 2023-05-13 2023-06-06 2023-05-24 2023-06-25 2024-06-24 ant Selection ation on Specialist nd Enhancing Livelihoods Pl anning Project Management, Comm SO-MOPND-SL-357296-CS-IN Individual Consult Under Implement IDA / E1320 unity-Driven Development a Prior Open - National 39,840.00 0.00 2023-04-22 2023-04-25 2023-06-01 2023-05-13 2023-06-08 2023-05-30 2023-06-29 2024-06-28 DV / Environmental Specialist ant Selection ation nd Enhancing Livelihoods Pl anning SO-MOPND-SL-357448-CS-C Development of Multiuse Wa Direct - Internation Under Implement QS / Backstopping Firm (Sele IDA / E1320 Prior Direct Selection 875,000.00 0.00 2023-04-30 2023-04-28 2023-05-10 2023-06-30 2028-01-23 ter Sources al ation ction, Design and Supervisio n) Page 1 PROCUREMENT PLAN (Textual Part) Project information: Ethiopia, Urban Productive Safety Net and Jobs Project (P169943) Project Implementation agency: Ministry of Labor and Social Affairs (MoLSA), Ministry of Urban Development and Construction (MoUDC), Urban Job Creation and Food Security Agency (UJCFSA) Date of the Procurement Plan: November 2020. Period covered by this Procurement Plan: December 2020 to December 2021. Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016 revised August 2018) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in Section 33(1)(a) from page 35-48 of the Proclamation Number 649/2009 of the Ethiopian Federal Government Procurement and Property Administration Proclamation, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. • Open Advertising of the procurement opportunity at the national level; • The procurement is open to eligible firms from any country; • The request for bids/Proposal documents shall require that bidders/proposers submitting Bids/Proposal present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of and compliance with the Bank’s Anti-Corruption Guidelines, including without limitation the bank’s right to sanction and the Bank’s inspection and audit right; • Contracts with an appropriate allocation of responsibilities, risks and liabilities; • Application of Standstill period and Publication of contract award information; • Maintenance of records of the procurement process; and • The Bank has the right to review procurement documentation and activities. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. “Not Applicable” Procurement of Second-Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: Is applicable for those contracts identified in the Procurement Plan; Works: Is applicable for those contracts identified in the Procurement Plan. Other Relevant Procurement Information. None PROCUREMENT Ethiopia : Urban Productive Safety Net and Jobs Project PLAN General Information Country: Ethiopia 2021-08-10 Bank’s Approval Date of the Original Procurement Plan: 2023-06-06 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P169943 GPN Date: 2020-12-18 Project Name: Urban Productive Safety Net and Jobs Project Loan / Credit No: IDA / D7320 Addis Ababa City Food Security and Productive Safety Net Agency Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned ET-AA ADDIS KETEMA-34775 Request for Quota 2-CW-RFQ / Refurbishment of Foster Urban Youth Employ Request for Quota Single Stage - One E 2023-07-1 IDA / D7320 Post Limited tions (Non Bank-S 73,000.00 0.00 Signed 2023-03-16 2023-04-25 2023-04-14 Woreda 11 OSSC in Addis Ket ment tions nvelope 3 PD) ema sub city of Addis Ababa by component 2.2 ET-AA -GULLELE-347754-CW Request for Quota -RFQ / Refurbishment of Wor Foster Urban Youth Employ Request for Quota Single Stage - One E Under Imple 2023-07-1 IDA / D7320 Post Limited tions (Non Bank-S 39,000.00 0.00 2023-03-16 2023-04-25 2023-04-14 eda 03 OSSC in Gulele Sub Ci ment tions nvelope mentation 3 PD) ty of Addis Ababa by compon ent 2.2 ET-AA -ARADA-347756-CW-R Request for Quota FQ / Refurbishment of Wored Foster Urban Youth Employ Request for Quota Single Stage - One E Under Imple 2023-07-1 IDA / D7320 Post Limited tions (Non Bank-S 34,000.00 0.00 2023-03-16 2023-04-25 2023-04-14 a 05 OSSC of Arada Sub city ment tions nvelope mentation 3 PD) of Addis Ababa by componen t 2.2 ET-AA - ARADA-347757-CW- Request for Quota RFQ / Refurbishment of Wore Foster Urban Youth Employ Request for Quota Single Stage - One E 2023-07-1 IDA / D7320 Post Limited tions (Non Bank-S 45,000.00 0.00 Signed 2023-03-16 2023-04-25 2023-04-14 da 02 OSSC in Arada Sub city ment tions nvelope 3 PD) of Addis Ababa by componen t 2.2 GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ET-AA FSPSNA-247413-GO-R Institutional Strengthening, FQ / Procurement of 20 pcs o Request for Quota Single Stage - One E Under Imple IDA / D7320 Project Management and Mo Post Limited 23,256.00 0.00 2021-08-20 2021-09-20 2021-10-20 f laptop computer for addis a tions nvelope mentation nitoring and Evaluation baba regional hub and imple menting agency ET-AA FSPSNA-247414-GO-R Institutional Strengthening, FQ / procurement of 20 file c Request for Quota Single Stage - One E Pending Impl IDA / D7320 Project Management and Mo Post Limited 13,953.00 0.00 2021-08-20 2021-09-20 2021-10-20 abinet for Addis Ababa city h tions nvelope ementation nitoring and Evaluation ub and implementing agency ET-AA FSPSNA-247419-GO-R Expand the Urban Productiv Single Stage - One E FB / Procurement of safety cl IDA / D7320 e Safety Net to Improve the Post Request for Bids Open - National 460,000.00 268,449.79 Completed 2021-08-15 2021-08-31 2021-08-20 2021-09-21 2021-10-01 2021-10-21 2021-10-08 2021-11-21 2021-11-09 2022-01-20 2021-12-09 nvelope oth/ overall work wear Urban Environment ET-AA FSPSNA-247420-GO-R Expand the Urban Productiv Single Stage - One E FB / procurement of safety sh IDA / D7320 e Safety Net to Improve the Post Request for Bids Open - National 880,000.00 730,075.54 Completed 2021-08-15 2021-08-21 2021-08-20 2021-09-21 2021-09-30 2021-10-21 2021-10-08 2021-11-21 2021-10-28 2022-01-20 2021-12-10 nvelope oes for public work participan Urban Environment t ET-AA FSPSNA-247422-GO-R Expand the Urban Productiv Single Stage - One E FB / procurement of leather g IDA / D7320 e Safety Net to Improve the Post Request for Bids Open - National 158,000.00 136,429.87 Completed 2021-08-15 2021-08-31 2021-08-20 2021-09-23 2021-09-30 2021-10-23 2021-10-08 2021-11-23 2021-11-16 2021-12-23 2021-12-16 nvelope love for public work beneficia Urban Environment ries ET-AA FSPSNA-247423-GO-R Expand the Urban Productiv Request for Quota Single Stage - One E FQ / procurement of washabl IDA / D7320 e Safety Net to Improve the Post Limited 33,220.00 28,038.58 Completed 2021-08-20 2021-08-30 2021-09-20 2021-09-18 2021-10-20 2021-10-14 tions nvelope e face mask for public work b Urban Environment eneficiaries ET-AA FSPSNA-247424-GO-R Expand the Urban Productiv Request for Quota Single Stage - One E FQ / procurement of first aid IDA / D7320 e Safety Net to Improve the Post Limited 60,000.00 51,788.48 Completed 2021-08-20 2021-08-27 2021-09-23 2021-09-18 2021-10-23 2021-10-14 tions nvelope kit Urban Environment ET-AA FSPSNA-247425-GO-R Expand the Urban Productiv Request for Quota Single Stage - One E FQ / procurement of local ma IDA / D7320 e Safety Net to Improve the Post Limited 37,218.00 32,096.17 Completed 2021-08-20 2021-08-27 2021-10-01 2021-09-18 2021-10-31 2021-10-15 tions nvelope de broom Urban Environment ET-AA FSPSNA-250058-GO-R Expand the Urban Productiv Single Stage - One E Under Imple FB / Procurement of safety m IDA / D7320 e Safety Net to Improve the Post Request for Bids Open - National 527,605.00 0.00 2021-08-30 2021-12-31 2021-09-04 2021-10-04 2022-02-02 2021-10-29 2022-03-01 2021-11-23 2022-01-22 nvelope mentation aterials/ Reflective vest and Urban Environment hat ET-AA FSPSNA-250063-GO-R Expand the Urban Productiv FB / Procurement of movable Single Stage - One E IDA / D7320 e Safety Net to Improve the Post Request for Bids Open - National 248,000.00 161,097.88 Completed 2021-08-31 2021-09-20 2021-09-05 2021-10-05 2021-10-25 2021-10-25 2021-11-16 2021-11-19 2021-12-23 2022-02-02 2022-03-04 canvas tent for day care of p nvelope Urban Environment ublic work participants ET-AA FSPSNA-250065-GO-R Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl FQ / Procurement of signboar IDA / D7320 e Safety Net to Improve the Post Limited 26,400.00 0.00 2021-09-04 2021-10-16 2021-11-15 tions nvelope ementation d Urban Environment ET-AA FSPSNA-250067-GO-R Expand the Urban Productiv Request for Quota Single Stage - One E FQ / Procurement of local bro IDA / D7320 e Safety Net to Improve the Post Limited 71,100.00 60,991.55 Completed 2021-09-04 2021-09-24 2021-10-16 2021-12-17 2021-11-30 2021-12-17 tions nvelope oms Urban Environment ET-AA FSPSNA-250069-GO-R Expand the Urban Productiv Single Stage - One E Pending Impl FB / Procurement of seedling IDA / D7320 e Safety Net to Improve the Post Request for Bids Open - National 326,665.00 0.00 2022-02-01 2022-02-06 2022-03-08 2022-04-07 2022-05-12 2022-06-26 nvelope ementation s Urban Environment ET-AA FSPSNA-290332-GO-R FQ / Procurement of 79 chair s and tables for (10 city level specialists, 11*3 sub cities an Foster Urban Youth Employ Request for Quota Single Stage - One E d 36 Woredas) in Addis Abab IDA / D7320 Post Limited 24,681.00 0.00 Canceled 2022-05-04 2022-06-17 2022-07-17 ment tions nvelope a City Administration Labor, Enterprise and Industry Deve lopment Bureau; Job Creation and Food Security Sector for Youth Employment Rollout Page 1 ET-AA FSPSNA-290986-GO-R FB / Procurement of Informati on Technology (IT) equipmen t (computers, scanners, and Foster Urban Youth Employ Single Stage - One E printers) for Addis Ababa Cit IDA / D7320 Post Request for Bids Open - National 222,815.00 0.00 Canceled 2022-04-22 2022-04-27 2022-06-01 2022-07-01 2022-07-29 2022-08-31 ment nvelope y Administration Labor, Enter prise and Industry Developm ent Bureau, Job Creation and Food Security Sector UPSNJP, Youth Employment Rollout ET-AA FSPSNA-353474-GO-R FB / Procurement of LCD Proj Expand the Urban Productiv Single Stage - One E Pending Impl ector, Printer, Desktop comp IDA / D7320 e Safety Net to Improve the Post Request for Bids Open - National 858,182.00 0.00 2023-04-13 2023-04-18 2023-05-19 2023-06-18 2023-07-11 2023-09-09 nvelope ementation uter, Lap top computer for yo Urban Environment uth employment apprentices hip and for regional PCU ET-AA FSPSNA-353505-GO-R FQ / Procurement of tables a Foster Urban Youth Employ Request for Quota Single Stage - One E Pending Impl IDA / D7320 Post Limited 12,750.00 0.00 2023-04-14 2023-05-13 2023-06-12 nd chairs for for youth appre ment tions nvelope ementation nticeship specialist ET-AA FSPSNA- KOLFE 35443 Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl 4-GO-RFQ / Procurement of L IDA / D7320 e Safety Net to Improve the Post Limited 21,000.00 0.00 2023-04-13 2023-05-12 2023-06-13 tions nvelope ementation ocal Stand broom for Kolfe S Urban Environment ub city ET-AA FSPSNA- KOLFE-3544 38-GO-RFQ / Procurement of Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl Protective Cloth (Tuta), Gaw IDA / D7320 e Safety Net to Improve the Post Limited 86,500.00 0.00 2023-04-13 2023-05-12 2023-06-12 tions nvelope ementation an and Mask made of cotton Urban Environment for Colfe sub city public work Beneficiaries ET-AA FSPSNA- KOLFE-3544 Expand the Urban Productiv 42-GO-RFQ / Procurement of Request for Quota Single Stage - One E Pending Impl IDA / D7320 e Safety Net to Improve the Post Limited 25,600.00 0.00 2023-04-13 2023-05-12 2023-06-12 Leather Glove for Kolfe Sub C tions nvelope ementation Urban Environment ity Public Work Beneficiaries ET-AA FSPSNA- AKAKI-35445 0-GO-RFQ / Procurement of S Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl afety Materials (Tuta, Gawan, IDA / D7320 e Safety Net to Improve the Post Limited 80,000.00 0.00 2023-04-15 2023-05-14 2023-06-14 tions nvelope ementation Mask & glove) for Akaki Sub Urban Environment city public work beneficiaries ET-AA FSPSNA- AKAKI- 3544 Expand the Urban Productiv 52-GO-RFQ / Procurement of Request for Quota Single Stage - One E Pending Impl IDA / D7320 e Safety Net to Improve the Post Limited 15,700.00 0.00 2023-04-15 2023-05-14 2023-06-15 local stand broom for Akaki S tions nvelope ementation Urban Environment ub city public work beneficiar ies ET-AA FSPSNA-354455- KIRK OS-GO-RFQ / Procurement of Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl Safety Materials (Tuta, Gawa IDA / D7320 e Safety Net to Improve the Post Limited 92,600.00 0.00 2023-04-13 2023-05-12 2023-06-12 tions nvelope ementation n, Mask & glove) for Kirkos S Urban Environment ub city public work beneficiar ies ET-AA FSPSNA-354456- KIRK Expand the Urban Productiv OS- GO-RFQ / Procurement of Request for Quota Single Stage - One E Pending Impl IDA / D7320 e Safety Net to Improve the Post Limited 16,800.00 0.00 2023-04-13 2023-05-11 2023-06-12 Local Broom for Kirkos Sub c tions nvelope ementation Urban Environment ity Public Work beneficiaries ET-AA FSPSNA- NIFAS SILK-3 Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl 54460-GO-RFQ / Procuremen IDA / D7320 e Safety Net to Improve the Post Limited 17,705.00 0.00 2023-04-13 2023-05-12 2023-06-12 tions nvelope ementation t of Local stand broom for Nif Urban Environment as silk sub city ET-AA FSPSNA- NIFAS SILK- 354462-GO-RFQ / Procureme Expand the Urban Productiv Request for Quota Pending Impl nt of Safety Material (Tuta, G IDA / D7320 e Safety Net to Improve the Post 85,200.00 0.00 2023-04-13 2023-05-12 2023-06-12 tions ementation awan,& Mask) made of cotto Urban Environment n for public work beneficiarie s in Nifas silk ET-AA FSPSNA- NIFAS SILK-3 Expand the Urban Productiv 54463-GO-RFQ / Procuremen Request for Quota Single Stage - One E Pending Impl IDA / D7320 e Safety Net to Improve the Post Limited 23,200.00 0.00 2023-04-13 2023-05-12 2023-06-12 t of Leather Glove for Nifas Si tions nvelope ementation Urban Environment lk Public Work Beneficiaries ET-AA FSPSNA- ARADA-3544 Expand the Urban Productiv 65-GO-RFQ / Procurement of Request for Quota Single Stage - One E Pending Impl IDA / D7320 e Safety Net to Improve the Post Limited 29,500.00 0.00 2023-04-17 2023-05-15 2023-06-15 local broom for Arada Sub Cit tions nvelope ementation Urban Environment y public work beneficiaries ET-AA FSPSNA- ADDIS KETE MA-354471-GO-RFB / Procure Expand the Urban Productiv Single Stage - One E Pending Impl ment of Safety Materials( Ma IDA / D7320 e Safety Net to Improve the Post Request for Bids Open - National 268,600.00 0.00 2023-04-10 2023-04-15 2023-05-16 2023-06-15 2023-07-05 2023-09-04 nvelope ementation sk, Glove gawan and tuta) for Urban Environment Addis Ketema Public work be neficiaries ET-AA FSPSNA- ADIS KETEM Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl A-354473-GO-RFQ / Procure IDA / D7320 e Safety Net to Improve the Post Limited 44,000.00 0.00 2023-04-13 2023-05-12 2023-06-12 tions nvelope ementation ment of local broom for Addis Urban Environment Ketema sub city ET-AA FSPSNA-LEMI KURA-3 Expand the Urban Productiv 55189-GO-RFQ / Procuremen Request for Quota Single Stage - One E Pending Impl IDA / D7320 e Safety Net to Improve the Post Limited 10,500.00 0.00 2023-04-13 2023-05-12 2023-06-12 t of local stand broom for lem tions nvelope ementation Urban Environment i kura sub city PW Buneficiari es ET-AA FSPSNA- LEMI KURA-3 55191-GO-RFQ / Procuremen Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl t of safety materials (Gawan, IDA / D7320 e Safety Net to Improve the Post Limited 63,200.00 0.00 2023-04-13 2023-05-12 2023-06-12 tions nvelope ementation tuta, leather glove and mask Urban Environment s) for Lemi kura sub city PW beneficiaries ET-AA FSPSNA- GULELE-355 Expand the Urban Productiv 192-GO-RFQ / Procurement o Request for Quota Single Stage - One E Pending Impl IDA / D7320 e Safety Net to Improve the Post Limited 16,800.00 0.00 2023-04-13 2023-05-12 2023-06-12 f local stand broom for Gulell tions nvelope ementation Urban Environment e sub city PW beneficiaries ET-AA FSPSNA- GULELE- 355 193-GO-RFQ / Procurement o Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl f Safety materials (Tuta, gaw IDA / D7320 e Safety Net to Improve the Post Limited 95,600.00 0.00 2023-04-13 2023-05-12 2023-06-23 tions nvelope ementation an, mask and leather glove) f Urban Environment or Gullele sub city PW benefi ciaries ET-AA FSPSNA- BOLE-35519 Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl 4-GO-RFQ / Procurement of l IDA / D7320 e Safety Net to Improve the Post Limited 10,500.00 0.00 2023-04-13 2023-05-12 2023-06-13 tions nvelope ementation ocal stand broom for bole su Urban Environment b city PW activities Page 2 ET-AA FSPSNA- BOLE- 35519 Expand the Urban Productiv 5-GO-RFQ / Procurement of S Request for Quota Single Stage - One E Pending Impl IDA / D7320 e Safety Net to Improve the Post Limited 71,200.00 0.00 2023-04-13 2023-05-12 2023-06-21 afety materials (GAWAN, TUT tions nvelope ementation Urban Environment A, GLOVE, AND MASK) for PW beneficiaries ET-AA FSPSNA- YEKA-35519 Expand the Urban Productiv 6-GO-RFQ / Procurement of l Request for Quota Single Stage - One E Pending Impl IDA / D7320 e Safety Net to Improve the Post Limited 16,800.00 0.00 2023-04-13 2023-05-12 2023-06-12 ocal stand broom for yeka pu tions nvelope ementation Urban Environment blic work activities ET-AA FSPSNA- YEKA-35519 Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl 7-GO-RFQ / Procurement of l IDA / D7320 e Safety Net to Improve the Post Limited 21,500.00 0.00 2023-04-13 2023-05-12 2023-06-11 tions nvelope ementation eather glove for yeka sub cit Urban Environment y PW beneficiaries ET-AA FSPSNA- YEKA-35519 8-GO-RFQ / procurement of s Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl afety materials (gawan, vest, IDA / D7320 e Safety Net to Improve the Post Limited 80,700.00 0.00 2023-04-13 2023-05-12 2023-06-26 tions nvelope ementation tuta, hat and mask) for yeka Urban Environment sub city PW beneficiaries ET-AA FSPSNA- LIDETA-3552 Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl 01-GO-RFQ / Procurement of IDA / D7320 e Safety Net to Improve the Post Limited 16,800.00 0.00 2023-04-13 2023-05-12 2023-06-12 tions nvelope ementation local stand broom for lideta P Urban Environment W beneficiaries ET-AA FSPSNA- LIDETA-3552 Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl 04-GO-RFQ / Procurement of IDA / D7320 e Safety Net to Improve the Post Limited 26,700.00 0.00 2023-04-13 2023-05-12 2023-06-12 tions nvelope ementation leather glove for lideta PW b Urban Environment eneficiaries ET-AA FSPSNA-LIDETA-3552 Expand the Urban Productiv 05-GO-RFQ / Procurement of Request for Quota Single Stage - One E Pending Impl IDA / D7320 e Safety Net to Improve the Post Limited 89,100.00 0.00 2023-04-16 2023-05-16 2023-06-25 safety materials (gawan, tuta tions nvelope ementation Urban Environment & mask) for lideta sub city P W beneficiaries ET-AA FSPSNA- ARADA-3544 68-GO-RFB / Procurement of Expand the Urban Productiv Single Stage - One E Pending Impl safety Materials (Tuta, Gawa IDA / D7320 e Safety Net to Improve the Post Request for Bids Open - National 171,000.00 0.00 2023-06-16 2023-06-21 2023-07-24 2023-08-07 2023-08-27 2023-10-26 nvelope ementation n, Mask and leataher Glove) f Urban Environment or Arada Public work benefici aries NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ET-AA FSPSNA-247412-CS-IN Institutional Strengthening, DV / Recruitment of procure Individual Consult Under Implement IDA / D7320 Project Management and Mo Prior Open 6,200.00 0.00 2021-08-15 2021-09-16 2021-09-18 2021-10-03 2021-10-28 2022-10-28 ment specialist for Addis Aba ant Selection ation nitoring and Evaluation ba city regional hub ET-AA FSPSNA/ADDIS K/SC1- 289901-CS-INDV / Recruitme nt of Apprenticeship Specialis Foster Urban Youth Employ Individual Consult Under Implement IDA / D7320 Post Open 3,876.00 0.00 2022-04-25 2022-06-06 2022-06-08 2023-04-19 2022-06-23 2022-07-19 2023-07-19 t for Youth Employment Rollo ment ant Selection ation ut in Addis Ketema Sub City Labor, Enterprise and Industr y Development Office ET-AA FSPSNA/ADDIS K/SC/2 -289989-CS-INDV / Recruitme nt of Apprenticeship Specialis t for Youth Employment Rollo Foster Urban Youth Employ Individual Consult Under Implement IDA / D7320 Post Open 3,876.00 0.00 2022-04-25 2022-06-06 2022-06-08 2022-06-23 2022-07-19 2023-07-19 ut in Addis Ababa City Admin ment ant Selection ation istration, Addis Ketema Sub City Administration Labor, En terprise and Industry Develo pment Office ET-AA FSPSNA/ADDIS K/SC/3 -290000-CS-INDV / Recruitme nt of Apprenticeship Specialis t for Youth Employment Rollo Foster Urban Youth Employ Individual Consult Under Implement IDA / D7320 Post Open 3,876.00 0.00 2022-04-25 2022-06-06 2022-06-08 2022-06-23 2022-07-19 2023-07-19 ut in Addis Ababa City Admin ment ant Selection ation istration, Addis Ketema Sub City Administration Labor, En terprise and Industry Develo pment Office ET-AA FSPSNA/AKAKI S/C/1-2 90007-CS-INDV / Recruitmen t of Apprenticeship Specialist for Youth Employment Rollou Foster Urban Youth Employ Individual Consult Under Implement IDA / D7320 Post Open 3,876.00 0.00 2022-04-25 2022-06-06 2022-06-08 2022-06-23 2022-07-19 2023-07-19 t in Addis Ababa City Adminis ment ant Selection ation tration, Akaki Kality Sub City Administration Labor, Enterpr ise and Industry Developmen t Office ET-AA FSPSNA/AKAKI K/S/C2- 290011-CS-INDV / Recruitme nt of Apprenticeship Specialis t for Youth Employment Rollo Foster Urban Youth Employ Individual Consult Under Implement IDA / D7320 Post Open 3,876.00 0.00 2022-04-25 2022-06-06 2022-06-08 2022-06-23 2022-07-19 2023-07-19 ut in Addis Ababa City Admin ment ant Selection ation istration, Akaki Kality Sub Cit y Administration Labor, Enter prise and Industry Developm ent Office Page 3 ET-AA FSPSNA/AKAKI K/S/C3- 290018-CS-INDV / Recruitme nt of Apprenticeship Specialis t for Youth Employment Rollo Foster Urban Youth Employ Individual Consult Under Implement IDA / D7320 Post Open 3,876.00 0.00 2022-04-25 2022-06-06 2022-06-08 2022-06-23 2022-07-19 2023-07-19 ut in Addis Ababa City Admin ment ant Selection ation istration, Akaki Kality Sub Cit y Administration Labor, Enter prise and Industry Developm ent Office ET-AA FSPSNA/ARADA S/C/1- 290021-CS-INDV / Recruitme nt of Apprenticeship Specialis Foster Urban Youth Employ Individual Consult Under Implement t for Youth Employment Rollo IDA / D7320 Post Open 3,876.00 0.00 2022-04-25 2022-06-06 2022-06-08 2022-06-23 2022-07-19 2023-07-19 ment ant Selection ation ut in Addis Ababa City Admin istration, Arada Sub City Adm inistration Labor, Enterprise and Industry Development Of fice ET-AA FSPSNA/ARADA S/C/2- 290024-CS-INDV / Recruitme nt of Apprenticeship Specialis Foster Urban Youth Employ Individual Consult Under Implement t for Youth Employment Rollo IDA / D7320 Post Open 3,876.00 0.00 2022-04-25 2022-06-06 2022-06-08 2022-06-23 2022-07-19 2023-07-19 ment ant Selection ation ut in Addis Ababa City Admin istration, Arada Sub City Adm inistration Labor, Enterprise and Industry Development Of fice ET-AA FSPSNA/ARADA S/C/3- 290029-CS-INDV / Recruitme nt of Apprenticeship Specialis Foster Urban Youth Employ Individual Consult Under Implement t for Youth Employment Rollo IDA / D7320 Post Open 3,876.00 0.00 2022-04-25 2022-06-06 2022-06-08 2022-06-23 2022-07-19 2023-07-19 ment ant Selection ation ut in Addis Ababa City Admin istration, Arada Sub City Adm inistration Labor, Enterprise and Industry Development Of fice ET-AA FSPSNA/BOLE S/C/1-2 90033-CS-INDV / Recruitmen t of Apprenticeship Specialist Foster Urban Youth Employ Individual Consult Under Implement for Youth Employment Rollou IDA / D7320 Post Open 3,876.00 0.00 2022-04-25 2022-06-06 2022-06-08 2022-06-23 2022-07-19 2023-07-19 ment ant Selection ation t in Addis Ababa City Adminis tration, Bole Sub City Admini stration Labor, Enterprise an d Industry Development Offic e ET-AA FSPSNA/BOLE S/C/2-2 90034-CS-INDV / Recruitmen t of Apprenticeship Specialist Foster Urban Youth Employ Individual Consult Under Implement for Youth Employment Rollou IDA / D7320 Post Open 3,876.00 0.00 2022-04-25 2022-06-06 2022-06-08 2022-06-23 2022-07-19 2023-07-19 ment ant Selection ation t in Addis Ababa City Adminis tration, Bole Sub City Admini stration Labor, Enterprise an d Industry Development Offic e ET-AA FSPSNA/BOLE S/C/3-2 90038-CS-INDV / Recruitmen t of Apprenticeship Specialist Foster Urban Youth Employ Individual Consult Under Implement for Youth Employment Rollou IDA / D7320 Post Open 3,876.00 0.00 2022-04-25 2022-06-06 2022-06-08 2022-06-23 2022-07-19 2023-07-19 ment ant Selection ation t in Addis Ababa City Adminis tration, Bole Sub City Admini stration Labor, Enterprise an d Industry Development Offic e ET-AA FSPSNA/GULELE S/C/1 -290041-CS-INDV / Recruitme nt of Apprenticeship Specialis Foster Urban Youth Employ Individual Consult Under Implement t for Youth Employment Rollo IDA / D7320 Post Open 3,876.00 0.00 2022-04-25 2022-06-06 2022-06-08 2022-06-23 2022-07-19 2023-07-19 ment ant Selection ation ut in Addis Ababa City Admin istration, Gulele Sub City Ad ministration Labor, Enterpris e and Industry Development Office ET-AA FSPSNA/GULELE S/C/2 -290043-CS-INDV / Recruitme nt of Apprenticeship Specialis Foster Urban Youth Employ Individual Consult Under Implement t for Youth Employment Rollo IDA / D7320 Post Open 3,876.00 0.00 2022-04-25 2022-06-06 2022-06-08 2022-06-23 2022-07-19 2023-07-19 ment ant Selection ation ut in Addis Ababa City Admin istration, Gulele Sub City Ad ministration Labor, Enterpris e and Industry Development Office ET-AA FSPSNA/GULELE S/C/3 -290044-CS-INDV / Recruitme nt of Apprenticeship Specialis Foster Urban Youth Employ Individual Consult Under Implement t for Youth Employment Rollo IDA / D7320 Post Open 3,876.00 0.00 2022-04-25 2022-06-06 2022-06-08 2022-06-23 2022-07-19 2023-07-19 ment ant Selection ation ut in Addis Ababa City Admin istration, Gulele Sub City Ad ministration Labor, Enterpris e and Industry Development Office ET-AA FSPSNA/KIRKOS S/C/1- 290046-CS-INDV / Recruitme nt of Apprenticeship Specialis Foster Urban Youth Employ Individual Consult Under Implement t for Youth Employment Rollo IDA / D7320 Post Open 3,876.00 0.00 2022-04-25 2022-06-06 2022-06-08 2022-06-23 2022-07-19 2023-07-19 ment ant Selection ation ut in Addis Ababa City Admin istration, Kirkos Sub City Ad ministration Labor, Enterpris e and Industry Development Office ET-AA FSPSNA/KIRKOS S/C/2- 290048-CS-INDV / Recruitme nt of Apprenticeship Specialis Foster Urban Youth Employ Individual Consult Under Implement t for Youth Employment Rollo IDA / D7320 Post Open 3,876.00 0.00 2022-04-25 2022-05-19 2022-06-08 2022-06-23 2022-07-19 2023-07-19 ment ant Selection ation ut in Addis Ababa City Admin istration, Kirkos Sub City Ad ministration Labor, Enterpris e and Industry Development Office ET-AA FSPSNA/KIRKOS S/C/3- 290049-CS-INDV / Recruitme nt of Apprenticeship Specialis Foster Urban Youth Employ Individual Consult Under Implement t for Youth Employment Rollo IDA / D7320 Post Open 3,876.00 0.00 2022-04-25 2022-06-06 2022-06-08 2022-06-23 2022-07-19 2023-07-19 ment ant Selection ation ut in Addis Ababa City Admin istration, Kirkos Sub City Ad ministration Labor, Enterpris e and Industry Development Office ET-AA FSPSNA/KOLFE S/C/1- 290052-CS-INDV / Recruitme nt of Apprenticeship Specialis t for Youth Employment Rollo Foster Urban Youth Employ Individual Consult Under Implement IDA / D7320 Post Open 3,876.00 0.00 2022-04-25 2022-06-06 2022-06-08 2022-06-23 2022-07-19 2023-07-19 ut in Addis Ababa City Admin ment ant Selection ation istration, Kolfe Keraniyo Sub City Administration Labor, En terprise and Industry Develo pment Office Page 4 ET-AA FSPSNA/KOLFE S/C/2- 290053-CS-INDV / Recruitme nt of an Apprenticeship Speci Foster Urban Youth Employ Individual Consult Under Implement alist for Youth Employment R IDA / D7320 Post Open 3,876.00 0.00 2022-04-25 2022-06-06 2022-06-08 2022-06-23 2022-07-19 2023-07-19 ment ant Selection ation ollout in Kolfe Keraniyo Sub C ity Administration Labor, Ent erprise and Industry Develop ment Office ET-AA FSPSNA/KOLFE S/C/3- 290079-CS-INDV / Recruitme nt of Apprenticeship Specialis t for Youth Employment Rollo Foster Urban Youth Employ Individual Consult Under Implement IDA / D7320 Post Open 3,876.00 0.00 2022-04-25 2022-06-06 2022-06-08 2022-06-23 2022-07-19 2023-07-19 ut in Addis Ababa City Admin ment ant Selection ation istration, Kolfe Keraniyo Sub City Administration Labor, En terprise and Industry Develo pment Bureau ET-AA FSPSNA/LEMI KURA 1- 290083-CS-INDV / Recruitme nt of Apprenticeship Specialis t for Youth Employment Rollo Foster Urban Youth Employ Individual Consult Under Implement IDA / D7320 Post Open 3,876.00 0.00 2022-04-25 2022-06-06 2022-06-08 2022-06-23 2022-07-19 2023-07-19 ut in Addis Ababa City Admin ment ant Selection ation istration, Lemi Kura Sub City Administration Labor, Enterpr ise and Industry Developmen t Bureau ET-AA FSPSNA/LEMI KURA 2- 290106-CS-INDV / Recruitme nt of Apprenticeship Specialis t for Youth Employment Rollo Foster Urban Youth Employ Individual Consult Under Implement IDA / D7320 Post Open 3,876.00 0.00 2022-04-25 2022-06-06 2022-06-08 2022-06-23 2022-07-19 2023-07-19 ut in Addis Ababa City Admin ment ant Selection ation istration, Lemi Kura Sub City Administration Labor, Enterpr ise and Industry Developmen t Bureau ET-AA FSPSNA/LEMI KURA 3- 290259-CS-INDV / Recruitme nt of Apprenticeship Specialis t for Youth Employment Rollo Foster Urban Youth Employ Individual Consult Under Implement IDA / D7320 Post Open 3,876.00 0.00 2022-04-25 2022-06-06 2022-06-08 2022-06-23 2022-07-19 2023-07-19 ut in Addis Ababa City Admin ment ant Selection ation istration, Lemi Kura Sub City Administration Labor, Enterpr ise and Industry Developmen t Bureau ET-AA FSPSNA/LIDETA S/C/1- 290110-CS-INDV / Recruitme nt of Apprenticeship Specialis Foster Urban Youth Employ Individual Consult Under Implement t for Youth Employment Rollo IDA / D7320 Post Open 3,876.00 0.00 2022-04-25 2022-06-06 2022-06-08 2022-06-23 2022-07-19 2023-07-19 ment ant Selection ation ut in Addis Ababa City Admin istration, Lideta Sub City Ad ministration Labor, Enterpris e and Industry Development Office ET-AA FSPSNA/LIDETA S/C/2- 290113-CS-INDV / Recruitme nt of Apprenticeship Specialis Foster Urban Youth Employ Individual Consult Under Implement t for Youth Employment Rollo IDA / D7320 Post Open 3,876.00 0.00 2022-04-25 2022-06-06 2022-06-08 2022-06-23 2022-07-19 2023-07-19 ment ant Selection ation ut in Addis Ababa City Admin istration, Lideta Sub City Ad ministration Labor, Enterpris e and Industry Development Office ET-AA FSPSNA/LIDETA S/C/3- 290114-CS-INDV / Recruitme nt of Apprenticeship Specialis Foster Urban Youth Employ Individual Consult Under Implement t for Youth Employment Rollo IDA / D7320 Post Open 3,876.00 0.00 2022-04-25 2022-06-06 2022-06-08 2022-06-23 2022-07-19 2023-07-19 ment ant Selection ation ut in Addis Ababa City Admin istration, Lideta Sub City Ad ministration Labor, Enterpris e and Industry Development Office ET-AA FSPSNA/NEFAS SL 1/- 290117-CS-INDV / Recruitme nt of Apprenticeship Specialis t for Youth Employment Rollo Foster Urban Youth Employ Individual Consult Under Implement IDA / D7320 Post Open 3,876.00 0.00 2022-04-25 2022-06-06 2022-06-08 2022-06-23 2022-07-19 2023-07-19 ut in Addis Ababa City Admin ment ant Selection ation istration, Nefas Silk Lafto Sub City Administration Labor, En terprise and Industry Develo pment Office ET-AA FSPSNA/NEFAS SL 2/- 290120-CS-INDV / Recruitme nt of Apprenticeship Specialis t for Youth Employment Rollo Foster Urban Youth Employ Individual Consult Under Implement IDA / D7320 Post Open 3,876.00 0.00 2022-04-25 2022-06-06 2022-06-08 2022-06-23 2022-07-19 2023-07-19 ut in Addis Ababa City Admin ment ant Selection ation istration, Nefas Silk Lafto Sub City Administration Labor, En terprise and Industry Develo pment Office ET-AA FSPSNA/NEFAS SL 3/- 290122-CS-INDV / Recruitme nt of Apprenticeship Specialis t for Youth Employment Rollo Foster Urban Youth Employ Individual Consult Under Implement IDA / D7320 Post Open 3,876.00 0.00 2022-04-25 2022-06-06 2022-06-08 2022-06-23 2022-07-19 2023-07-19 ut in Addis Ababa City Admin ment ant Selection ation istration, Nefas Silk Lafto Sub City Administration Labor, En terprise and Industry Develo pment Office ET-AA FSPSNA/YEKA SUB C1- 290123-CS-INDV / Recruitme nt of Apprenticeship Specialis Foster Urban Youth Employ Individual Consult Under Implement t for Youth Employment Rollo IDA / D7320 Post Open 3,876.00 0.00 2022-04-25 2022-06-06 2022-06-08 2022-06-23 2022-07-19 2023-07-19 ment ant Selection ation ut in Addis Ababa City Admin istration, Yeka Sub City Admi nistration Labor, Enterprise a nd Industry Development Offi ce ET-AA FSPSNA/YEKA SUB C2/ -290124-CS-INDV / Recruitme nt of Apprenticeship Specialis Foster Urban Youth Employ Individual Consult Under Implement t for Youth Employment Rollo IDA / D7320 Post Open 3,876.00 0.00 2022-04-18 2022-06-06 2022-06-01 2022-06-16 2022-07-12 2023-07-12 ment ant Selection ation ut in Addis Ababa City Admin istration, Yeka Sub City Admi nistration Labor, Enterprise a nd Industry Development Offi ce ET-AA FSPSNA/YEKA SUB C3/ -290126-CS-INDV / Recruitme nt of Apprenticeship Specialis Foster Urban Youth Employ Individual Consult Under Implement t for Youth Employment Rollo IDA / D7320 Post Open 3,876.00 0.00 2022-04-25 2022-06-06 2022-06-08 2022-06-23 2022-07-19 2023-07-19 ment ant Selection ation ut in Addis Ababa City Admin istration, Yeka Sub City Admi nistration Labor, Enterprise a nd Industry Development Offi ce Page 5 ET-AA FSPSNA/ADDIS ABABA -290132-CS-INDV / Recruitme nt of Apprenticeship Senior S pecialist for Youth Employme Foster Urban Youth Employ Individual Consult Under Implement IDA / D7320 Post Open 3,984.00 0.00 2022-04-25 2022-06-06 2022-06-08 2022-06-23 2022-07-19 2023-07-19 nt Rollout in Addis Ababa Cit ment ant Selection ation y Administration Labor, Enter prise and Industry Developm ent Bureau, Job Creation and Food Security Sector ET-AA FSPSNA-305124-CS-IN DV / Recruitment of Individua Institutional Strengthening, l Procurement Consultant for Individual Consult Under Implement IDA / D7320 Project Management and Mo Prior Limited 12,000.00 0.00 2022-09-09 2023-02-07 2022-09-14 2023-02-01 2022-10-04 2023-03-20 2022-10-24 2023-10-24 12 months for UPSNJP imple ant Selection ation nitoring and Evaluation mented in Addis Ababa City Administration in 11 Sub Citi es ET-AA FSPSNA-364925-CS-IN Institutional Strengthening, DV / Recruitment of Monitori Individual Consult Under Implement IDA / D7320 Project Management and Mo Post Open - National 5,000.00 0.00 2023-06-12 2023-06-14 2023-07-24 2023-08-03 2023-08-24 2024-08-23 ng and Evaluation Specialist f ant Selection ation nitoring and Evaluation or Addis Ababa City Hub ET-AA FSPSNA-364929-CS-IN Institutional Strengthening, Individual Consult Under Implement DV / Recruitment of Gender S IDA / D7320 Project Management and Mo Post Open - National 5,000.00 0.00 2023-06-12 2023-06-14 2023-07-24 2023-08-03 2023-08-24 2024-08-23 ant Selection ation pecialist for Addis Ababa City nitoring and Evaluation Hub ET-AA FSPSNA-364934-CS-IN Institutional Strengthening, Individual Consult Under Implement DV / Recruitment of Safeguar IDA / D7320 Project Management and Mo Post Open - National 5,000.00 0.00 2023-06-12 2023-06-14 2023-07-24 2023-08-03 2023-08-24 2024-08-23 ant Selection ation d Specialist for Addis Ababa nitoring and Evaluation City Hub Page 6 PROCUREMENT PLAN (Textual Part) Project information: Kiribati Pacific Islands Regional Oceanscape Program (P165821) Project Implementation agency: Ministry of Fisheries and Marine Resource Development (MFMRD) Date of the Procurement Plan: March 20, 2019 Period covered by this Procurement Plan: March 1, 2019 – February 28, 2020. Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in 2002 Kiribati Procurement Act, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. a. open advertising of the procurement opportunity at the national level; b. the procurement is open to eligible firms from any country; c. the request for bids/request for proposals document shall require that Bidders/Proposers submitting Bids/Proposals present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights; d. contracts with an appropriate allocation of responsibilities, risks, and liabilities; e. publication of contract award information; f. rights for the Bank to review procurement documentation and activities; g. an effective complaints mechanism; and h. maintenance of records of the Procurement Process. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. Not Applicable Procurement of Second-Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables Not Applicable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Specify for each Goods: is not applicable for those contracts identified in the Procurement Plan tables; Works: is not applicable for those contracts identified in the Procurement Plan tables Other Relevant Procurement Information. Procurement in Situations of Urgent Need of Assistance or Capacity Constraints or Capacity Constraints PROCUREMENT Kiribati : Kiribati: Pacific Islands Regional Oceanscape Program PLAN General Information Country: Kiribati 2019-03-28 Bank’s Approval Date of the Original Procurement Plan: 2023-06-06 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P165821 GPN Date: Project Name: Kiribati: Pacific Islands Regional Oceanscape Program Loan / Credit No: IDA / D5570, / Ministry of Fisheries and Marine Resource Development Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned KI-MFMRD-243979-CW-RFQ / Delivering Effective Project Request for Quota Single Stage - One E Other (with field f 2022-03-1 The minor construction work IDA / D5570 Post Limited 8,000.00 9,223.59 Completed 2021-07-20 2021-06-01 2021-09-14 2021-07-01 Management tions nvelope or explanation) 3 cost for PROP new Office at K PF Complex GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Strengthening Monitoring, C MFMRD-GD-1 / Computers, p Request for Quota Single Stage - One E IDA / D5570 ontrol and Surveillance of La Post Open - National 6,000.00 4,847.26 Signed 2019-04-01 2019-05-27 2019-07-31 2019-11-23 2019-07-31 rinter and software tions nvelope rge-Scale Oceanic Fisheries Strengthening Monitoring, C MFMRD-GD-2 / Operation Ve Request for Quota Open - Internationa Single Stage - One E IDA / D5570 ontrol and Surveillance of La Post 120,000.00 91,917.00 Completed 2019-04-01 2019-12-01 2019-05-27 2019-07-25 2019-11-23 2019-10-09 hicle (2 units) tions l nvelope rge-Scale Oceanic Fisheries MFMRD-GD-3 / Office Furnitu Request for Quota Single Stage - One E / Post Open - National 16,500.00 4,470.89 Completed 2019-04-01 2019-11-28 2019-05-27 2019-07-30 2019-11-23 2019-08-23 re (table, chair and filing cabi tions nvelope nets) Strengthening Monitoring, C MFMRD-GD-4 / Boat (to facili Request for Quota Open - Internationa Single Stage - One E IDA / D5570 ontrol and Surveillance of La Post 58,000.00 37,351.00 Completed 2019-04-01 2020-02-24 2019-05-27 2020-03-14 2019-11-23 2020-04-29 tate coastal survey) tions l nvelope rge-Scale Oceanic Fisheries Strengthening Monitoring, C PROP-GO- RFQ1 / MCS office Request for Quota Open - Internationa Single Stage - One E Pending Impl IDA / D5570 ontrol and Surveillance of La Post 90,000.00 0.00 2024-06-08 2024-08-03 2025-01-30 furniture tions l nvelope ementation rge-Scale Oceanic Fisheries PROP-GO- RFQ5 / Hardware Strengthening Monitoring, C and software to transition fro Request for Quota Open - Internationa Single Stage - One E Pending Impl IDA / D5570 ontrol and Surveillance of La Post 150,000.00 0.00 2024-03-06 2024-05-01 2024-10-28 m paper-based data collectio tions l nvelope ementation rge-Scale Oceanic Fisheries n to an online e-reporting sys tem PROP-GO- RFQ6 / Catalyze s Diversifying Marine-Based R Request for Quota Open - Internationa Single Stage - One E Pending Impl ysteme for sustainable suppl IDA / D5570 evenue Streams for Outer Isl Post 400,000.00 0.00 2023-07-05 2023-08-30 2024-02-26 tions l nvelope ementation y chains in up to four outer is and Coastal Communities lands KI-MFMRD-154493-GO-RFQ / Delivering Effective Project Request for Quota Single Stage - One E Pending Impl IDA / D5570 Post Open - National 21,000.00 0.00 2021-02-13 2021-04-10 2021-10-07 Office IT equipment for new Management tions nvelope ementation PMU staff KI-MFMRD-157413-CS-INDV / Delivering Effective Project Request for Quota Single Stage - One E Pending Impl IDA / D5570 Post Open - National 10,000.00 0.00 2021-02-20 2021-04-17 2021-10-14 Furniture for new PMU staff Management tions nvelope ementation PROP-GO- RFQ3 / Observer t Strengthening Monitoring, C Request for Quota Open - Internationa Single Stage - One E ransport vessel - Betio &Kiriti IDA / D5570 ontrol and Surveillance of La Post 160,000.00 0.00 Canceled 2021-03-15 2021-05-13 2021-05-10 2021-11-06 tions l nvelope mati rge-Scale Oceanic Fisheries PROP-GO- RFQ2 / Supply an Strengthening Monitoring, C Request for Propo Open - Internationa d Install 3 camera system on IDA / D5570 ontrol and Surveillance of La Prior Multi Stage 750,000.00 0.00 Canceled 2022-07-01 2022-09-16 2022-09-16 2022-07-06 2022-11-25 2023-04-13 2024-10-04 sals l 50 long-liners rge-Scale Oceanic Fisheries KI-MFMRD-250635-GO-RFQ / Strengthening Monitoring, C Request for Quota Single Stage - One E PROP Office operational vehi IDA / D5570 ontrol and Surveillance of La Post Open - National 40,000.00 37,200.60 Signed 2021-09-25 2021-09-19 2021-11-20 2021-10-19 2022-05-19 tions nvelope cle #3. rge-Scale Oceanic Fisheries KI-MFMRD-314392-GO-RFQ / Purchasing 2 Hp Notebook la Delivering Effective Project Request for Quota Single Stage - One E IDA / D5570 Post Open - National 3,070.00 0.00 Canceled 2022-09-24 2022-11-19 2023-05-18 ptops (replacement for 2 staf Management tions nvelope f) and 6 flash drives (32GB) f or PMU Staff KI-MFMRD-247579-GO-RFQ / Strengthening Monitoring, C Request for Quota Open - Internationa Single Stage - One E Observer transport vessel - B IDA / D5570 ontrol and Surveillance of La Post 160,000.00 0.00 Canceled 2022-03-06 2021-08-18 2022-05-01 2022-10-28 tions l nvelope etio & Kiritimati rge-Scale Oceanic Fisheries KI-MFMRD-247577-GO-RFB / Strengthening Monitoring, C Open - Internationa Single Stage - One E Pending Impl Supply and Install 3 camera s IDA / D5570 ontrol and Surveillance of La Post Request for Bids 750,000.00 0.00 2024-05-22 2024-05-27 2024-07-08 2024-08-07 2024-09-11 2025-03-10 l nvelope ementation ystem on 50 long-liners rge-Scale Oceanic Fisheries NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Strengthening Monitoring, C PROP-CS-FIRM1 / Support a t Consultant Qualifi Open - Internationa Pending Impleme IDA / D5570 ontrol and Surveillance of La Post 100,000.00 0.00 2023-06-30 2023-07-21 2023-09-03 2023-10-03 2023-11-07 2024-05-05 rial with KFL vessels cation Selection l ntation rge-Scale Oceanic Fisheries Page 1 Strengthening Monitoring, C PROP-CS-FIRM4 / Legislative Consultant Qualifi Open - Internationa Pending Impleme IDA / D5570 ontrol and Surveillance of La Post 70,000.00 0.00 2020-07-01 2020-07-22 2020-09-04 2020-10-04 2020-11-08 2021-05-07 and policy reviews. cation Selection l ntation rge-Scale Oceanic Fisheries PROP-CS-FIRM6 / ER training Strengthening Monitoring, C - consultant (Preparation of Consultant Qualifi Open - Internationa Pending Impleme IDA / D5570 ontrol and Surveillance of La Post 80,000.00 0.00 2022-07-04 2022-07-25 2022-09-07 2022-10-07 2022-11-11 2023-05-10 materials; language translati cation Selection l ntation rge-Scale Oceanic Fisheries on - for skippers and MFMRD staff to support ER] PROP-CS-FIRM7 / Consultant/ Strengthening Monitoring, C Consultant Qualifi Open - Internationa Pending Impleme TA for Evidence and case pre IDA / D5570 ontrol and Surveillance of La Post 90,000.00 0.00 2023-03-03 2023-03-24 2023-05-07 2023-06-06 2023-07-11 2024-01-07 cation Selection l ntation paration rge-Scale Oceanic Fisheries PROP-CS-FIRM8 / Observer d Strengthening Monitoring, C Consultant Qualifi Open - Internationa Pending Impleme e-briefer and trainer training IDA / D5570 ontrol and Surveillance of La Post 140,000.00 0.00 2022-01-03 2022-01-24 2022-03-09 2022-04-08 2022-05-13 2022-11-09 cation Selection l ntation & VMS systems maintenance rge-Scale Oceanic Fisheries training PROP-CS-FIRM10 / PSM proc Strengthening Monitoring, C Consultant Qualifi Open - Internationa Pending Impleme esses and procedures (includ IDA / D5570 ontrol and Surveillance of La Post 75,000.00 0.00 2020-07-01 2020-07-22 2020-09-04 2020-10-04 2020-11-08 2021-05-07 cation Selection l ntation ing transhipment monitoring) rge-Scale Oceanic Fisheries PROP-CS-FIRM12 / Preparati on of a Kiritimati Ocean Reso Strengthening Monitoring, C urces Master Plan, Kiritimati Consultant Qualifi Open - Internationa Under Implement IDA / D5570 ontrol and Surveillance of La Post 580,000.00 0.00 2021-09-01 2022-04-08 2021-09-22 2022-04-13 2021-11-05 2022-11-16 2021-12-05 2022-01-09 2022-07-08 Sports Fishing Management cation Selection l ation rge-Scale Oceanic Fisheries Plan and the operationalisati on of the Kiritimati aquaium f ish management plan. PROP-CS-FIRM13 / Strengthe ning coastal resource licensin g systems nationwide, enhan Diversifying Marine-Based R Consultant Qualifi Open - Internationa Pending Impleme cing community participation IDA / D5570 evenue Streams for Outer Isl Post 400,000.00 0.00 2022-07-01 2022-07-22 2022-09-04 2022-10-04 2022-11-08 2023-05-07 cation Selection l ntation and strengthening the capaci and Coastal Communities ty and operational effectiven ess of MFMRD's Coastal Fishe ries Division. PROP-CS-FIRM15 / Developm Improving Seafood Toxicolog ent of a lagoon and coastal fi Consultant Qualifi Open - Internationa Pending Impleme IDA / D5570 y and Safety Measures in Sel Post 500,000.00 0.00 2020-07-01 2020-07-22 2020-09-04 2020-10-04 2020-11-08 2021-05-07 sheries pollution and seafood cation Selection l ntation ected Fisheries toxin monitoring and manag ement plan. PROP-CS-FIRM16 / Seafood T Improving Seafood Toxicolog Consultant Qualifi Open - Internationa Pending Impleme oxicology Training and Capac IDA / D5570 y and Safety Measures in Sel Post 200,000.00 0.00 2022-07-08 2022-07-29 2022-09-11 2022-10-11 2022-11-15 2023-05-14 cation Selection l ntation ity Builiding Program - design ected Fisheries consultant PROP-CS-FIRM17 / Kiribati Se Improving Seafood Toxicolog Consultant Qualifi Open - Internationa Pending Impleme afood Safety Scheme - consu IDA / D5570 y and Safety Measures in Sel Post 350,000.00 0.00 2022-06-15 2022-07-06 2022-08-19 2022-09-18 2022-10-23 2023-04-21 cation Selection l ntation ltant ected Fisheries PROP-CS-FIRM2 / Market Sta Strengthening Monitoring, C te & Catch Documentation As Consultant Qualifi Open - Internationa Pending Impleme IDA / D5570 ontrol and Surveillance of La Post 470,000.00 0.00 2021-07-01 2021-07-22 2021-09-04 2021-10-04 2021-11-08 2022-05-07 sessment (Assessing and res cation Selection l ntation rge-Scale Oceanic Fisheries ponding to market State requ irements) PROP-CS-FIRM5 / EM (install Strengthening Monitoring, C Consultant Qualifi Open - Internationa Pending Impleme ation, aministration and main IDA / D5570 ontrol and Surveillance of La Post 200,000.00 0.00 2023-08-07 2023-08-28 2023-10-11 2023-11-10 2023-12-15 2024-06-12 cation Selection l ntation tenance, data review training rge-Scale Oceanic Fisheries )- consultant PROP-CS-FIRM9 / VMS syste Strengthening Monitoring, C Consultant Qualifi Open - Internationa Pending Impleme ms maintenance and support IDA / D5570 ontrol and Surveillance of La Post 60,000.00 0.00 2024-06-03 2024-06-24 2024-08-07 2024-09-06 2024-10-11 2025-04-09 cation Selection l ntation traing rge-Scale Oceanic Fisheries PROP-CS-FIRM20 / Design an Improving Seafood Toxicolog Consultant Qualifi Open - Internationa Pending Impleme d Supervision consultant for t IDA / D5570 y and Safety Measures in Sel Post 250,000.00 0.00 2024-06-03 2024-06-24 2024-08-07 2024-09-06 2024-10-11 2025-04-09 cation Selection l ntation he Kiribati Seafood Safety La ected Fisheries boratory PROP-CS-FIRM18 / Design an Strengthening Monitoring, C Consultant Qualifi Open - Internationa Pending Impleme d Supervision of the Betio an IDA / D5570 ontrol and Surveillance of La Post 500,000.00 0.00 2022-07-01 2022-07-22 2022-09-04 2022-10-04 2022-11-08 2023-05-07 cation Selection l ntation d Kiritimati MCS facilities. rge-Scale Oceanic Fisheries KI-MFMRD-277859-CS-CQS / ToR for Policy Work and Conc Improving Seafood Toxicolog eptualizing Seafood Toxicolo Consultant Qualifi Open - Internationa Under Implement IDA / D5570 y and Safety Measures in Sel Post 245,000.00 0.00 2022-02-10 2022-03-15 2022-03-11 2022-04-04 2022-05-14 2022-06-01 2022-06-13 2022-07-18 2023-01-14 gy and Coastal Fisheries Lab cation Selection l ation ected Fisheries oratores | Financed under co mponent 3 subcomponents 3 .2 & 2.5 KI-MFMRD-309772-CS-CQS / Strengthening Monitoring, C Consultant Qualifi Open - Internationa Under Implement Combating IUU Review and U IDA / D5570 ontrol and Surveillance of La Post 30,000.00 0.00 2022-09-19 2022-09-27 2022-10-10 2022-12-07 2022-11-23 2022-12-23 2023-01-27 2023-07-26 cation Selection l ation pdate NPoA IUU rge-Scale Oceanic Fisheries KI-MFMRD-315301-CS-QCBS / Development of a lagoon an Improving Seafood Toxicolog Quality And Cost- Open - Internationa Under Implement d coastal fisheries pollution a IDA / D5570 y and Safety Measures in Sel Post 500,000.00 0.00 2022-09-19 2022-11-10 2022-10-10 2022-11-22 2022-11-23 2022-12-21 2023-01-20 2023-02-24 2023-03-31 2024-03-30 Based Selection l ation nd seafood toxin monitoring ected Fisheries and management plan. KI-MFMRD-328801-CS-QCBS / Preparation of a needs asse ssment for a CPPL Fisheries c Diversifying Marine-Based R Quality And Cost- Open - Internationa Under Implement entre on Kiritimati Island and IDA / D5570 evenue Streams for Outer Isl Post 390,000.00 0.00 2023-01-08 2023-03-01 2023-01-29 2023-05-21 2023-03-14 2023-04-11 2023-05-11 2023-06-15 2023-07-20 2024-07-19 Based Selection l ation economic assessment of the and Coastal Communities viability of developing sustai nable supply chains in the Li ne Islands. PROP-CS-FIRM3 / Transhipm Strengthening Monitoring, C ent Support implementation Consultant Qualifi Open - Internationa IDA / D5570 ontrol and Surveillance of La Post 70,000.00 0.00 Canceled 2022-01-03 2022-01-24 2022-03-09 2022-04-08 2022-05-13 2022-11-09 of the Transhipment Monitori cation Selection l rge-Scale Oceanic Fisheries ng Plan through the provision of equipment KI-MFMRD-354918-CS-QCBS Diversifying Marine-Based R Quality And Cost- Open - Internationa Under Implement / Establishment of a Marine S IDA / D5570 evenue Streams for Outer Isl Post 310,000.00 0.00 2023-04-05 2023-04-12 2023-04-26 2023-05-11 2023-06-09 2023-06-21 2023-07-07 2023-08-06 2023-09-10 2023-10-15 2024-10-14 Based Selection l ation patial Plan (MSP) for Tarawa. and Coastal Communities KI-MFMRD-317961-CS-QCBS / Preparation and Implement Diversifying Marine-Based R Quality And Cost- Open - Internationa Pending Impleme ation of Sustainable supply c IDA / D5570 evenue Streams for Outer Isl Post 500,000.00 0.00 2023-06-30 2023-07-21 2023-09-03 2023-10-01 2023-10-31 2023-12-05 2024-01-09 2025-01-08 Based Selection l ntation hain development plans for t and Coastal Communities argeted outer islands in the Gilbert Groups. Page 2 KI-MFMRD-309767-CS-CQS / Strengthening Monitoring, C Implementation of transship Consultant Qualifi Open - Internationa IDA / D5570 ontrol and Surveillance of La Post 400,000.00 0.00 Canceled 2022-09-19 2022-09-28 2022-10-10 2023-02-01 2022-11-23 2022-12-23 2023-01-27 2023-07-26 ment plan through the provis cation Selection l rge-Scale Oceanic Fisheries ion of equipment INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Strengthening Monitoring, C MFMRD-CS-IND-1 / Project M Individual Consult IDA / D5570 ontrol and Surveillance of La Post Open 47,234.00 43,600.00 Signed 2019-03-27 2019-05-01 2019-05-15 2019-04-25 2019-06-05 2019-04-29 2019-07-10 2020-05-01 2020-01-06 anager ant Selection rge-Scale Oceanic Fisheries Strengthening Monitoring, C MFMRD-CS-IND-2 / POM Con Individual Consult IDA / D5570 ontrol and Surveillance of La Post Open 50,000.00 42,365.00 Completed 2019-03-27 2019-05-28 2019-05-15 2019-08-23 2019-06-05 2019-11-04 2019-07-10 2019-11-08 2020-01-06 2020-03-10 sultant ant Selection rge-Scale Oceanic Fisheries Strengthening Monitoring, C MFMRD-CS-IND-3 / M&E Con Individual Consult IDA / D5570 ontrol and Surveillance of La Post Open 36,400.00 36,400.00 Signed 2019-03-27 2019-06-04 2019-05-15 2019-06-19 2019-06-05 2019-06-21 2019-07-10 2019-06-28 2020-01-06 sultant ant Selection rge-Scale Oceanic Fisheries Strengthening Monitoring, C MFMRD-CS-IND-4 / MCS-Infor Individual Consult IDA / D5570 ontrol and Surveillance of La Post Open 70,000.00 57,450.00 Completed 2019-03-27 2019-06-04 2019-05-15 2019-09-19 2019-06-05 2019-10-15 2019-07-10 2019-10-16 2020-01-06 2019-12-18 mation System Specialist ant Selection rge-Scale Oceanic Fisheries MFMRD-CS-IND-5 / Project G Individual Consult Pending Impleme / Post Open 50,000.00 0.00 2019-03-27 2019-05-15 2019-06-05 2019-07-10 2020-01-06 ender Consultant ant Selection ntation Strengthening Monitoring, C MFMRD-CS-IND-6 / Small sca Individual Consult Under Implement / ontrol and Surveillance of La Post Open 46,000.00 0.00 2019-03-27 2019-08-23 2019-05-15 2019-06-05 2019-07-10 2020-01-06 le fisheries Scoping -Int ant Selection ation rge-Scale Oceanic Fisheries Strengthening Monitoring, C MFMRD-CS-IND-7 / Small sca Individual Consult IDA / D5570 ontrol and Surveillance of La Post Open 14,000.00 10,000.00 Signed 2019-03-27 2019-08-23 2019-05-15 2019-10-21 2019-06-05 2019-11-04 2019-07-10 2019-11-05 2020-01-06 le fisheries Scoping -Nat ant Selection rge-Scale Oceanic Fisheries Strengthening Monitoring, C MFMRD-CS-IND-10 / Seafood Individual Consult IDA / D5570 ontrol and Surveillance of La Post Open 50,000.00 50,000.00 Completed 2019-03-27 2019-05-28 2019-05-15 2019-08-30 2019-06-05 2019-09-09 2019-07-10 2019-09-06 2020-01-06 2020-04-01 Toxicology Specialist ant Selection rge-Scale Oceanic Fisheries MFMRD-CS-IND-9 / Civil Wor Individual Consult / Post Open 75,000.00 0.00 Canceled 2019-03-27 2019-05-15 2019-06-05 2019-07-10 2020-01-06 ks Consultant-Design and Su ant Selection pervision KI-MFMRD-154029-CS-INDV / Strengthening Monitoring, C Individual Consult Pending Impleme Electronic monitoring cost re IDA / D5570 ontrol and Surveillance of La Post Open 30,000.00 0.00 2020-07-01 2020-08-19 2020-09-09 2020-10-07 2021-10-07 ant Selection ntation covery policy development rge-Scale Oceanic Fisheries KI-MFMRD-154030-CS-INDV / Strengthening Monitoring, C Individual Consult Pending Impleme Combating IUU Review and U IDA / D5570 ontrol and Surveillance of La Post Open 30,000.00 0.00 2022-07-01 2022-08-19 2022-09-09 2022-10-14 2023-04-12 ant Selection ntation pdate NPoA IUU rge-Scale Oceanic Fisheries KI-MFMRD-154272-CS-INDV / Improving Seafood Toxicolog Prepare draft legislation to i Individual Consult Pending Impleme / y and Safety Measures in Sel Post Open 200,000.00 0.00 2022-07-01 2022-12-01 2022-12-16 2023-01-13 2024-01-12 mplement the Kiribati Seafoo ant Selection ntation ected Fisheries d Safety Scheme and draft S eafood Safety Scheme KI-MFMRD-154281-CS-INDV / Delivering Effective Project Individual Consult IDA / D5570 Post Open 26,000.00 26,000.00 Terminated 2021-01-19 2021-03-02 2021-03-09 2021-05-25 2021-03-30 2021-07-05 2021-05-04 2021-07-06 2021-10-31 Finance Officer (PROP) Management ant Selection KI-MFMRD-154284-CS-INDV / Delivering Effective Project Individual Consult IDA / D5570 Post Open 36,400.00 36,400.00 Signed 2021-01-27 2020-07-31 2021-03-17 2020-09-01 2021-04-07 2020-09-14 2021-05-12 2020-09-15 2021-11-08 Gender Specialist Management ant Selection KI-MFMRD-154283-CS-INDV / Delivering Effective Project Individual Consult IDA / D5570 Post Open 26,000.00 26,000.00 Signed 2021-03-22 2021-03-18 2021-05-10 2021-05-21 2021-05-31 2021-05-21 2021-07-05 2021-05-25 2022-01-01 Operations Officer - Kiritimati Management ant Selection Island KI-MFMRD-154280-CS-INDV / Delivering Effective Project Individual Consult IDA / D5570 Post Open 26,000.00 26,000.00 Terminated 2021-03-03 2021-04-29 2021-04-21 2020-10-19 2021-05-12 2020-10-26 2021-06-16 2020-10-27 2021-12-13 Procurement Officer (PROP) Management ant Selection KI-MFMRD-157407-CS-INDV / Improving Seafood Toxicolog Individual Consult Pending Impleme Comprehensive Health Impac IDA / D5570 y and Safety Measures in Sel Post Open 150,000.00 0.00 2021-07-01 2021-08-19 2021-09-09 2021-10-14 2022-04-12 ant Selection ntation t Assessment - Proposed labo ected Fisheries ratory MFMRD-CS-IND-12 / National Strengthening Monitoring, C observer programme (Imple Individual Consult Pending Impleme IDA / D5570 ontrol and Surveillance of La Post Open 50,000.00 0.00 2021-07-01 2021-08-19 2021-09-09 2021-10-14 2022-04-12 ment Observer e-reporting fo ant Selection ntation rge-Scale Oceanic Fisheries r the domestic longline fleet) MFMRD-CS-IND-13 / National Strengthening Monitoring, C observer programme (Imple Individual Consult Pending Impleme IDA / D5570 ontrol and Surveillance of La Post Open 30,000.00 0.00 2022-07-18 2022-09-05 2022-09-26 2022-10-31 2023-04-29 ment Observer e-reporting fo ant Selection ntation rge-Scale Oceanic Fisheries r the domestic longline fleet) KI-MFMRD-154285-CS-INDV / Delivering Effective Project Individual Consult Safeguard and Communicati IDA / D5570 Post Open 36,400.00 36,400.00 Signed 2021-03-01 2021-05-11 2021-04-19 2021-05-12 2021-05-10 2021-05-12 2021-06-14 2021-05-11 2021-12-11 Management ant Selection on Specialist KI-MFMRD-225326-CS-CDS / Fisheries Specialist is needed Delivering Effective Project for the focus on the drafting IDA / D5570 Post Direct Selection Direct 25,000.00 25,000.00 Signed 2021-04-05 2021-04-14 2021-04-15 2021-04-15 2021-06-19 2021-04-21 2021-12-16 Management and finalization of certain To Rs on MSCs components. KI-MFMRD-262659-CS-QCBS Strengthening Monitoring, C / Legislation & Policy Review Individual Consult Under Implement IDA / D5570 ontrol and Surveillance of La Post Open 70,000.00 0.00 2021-11-26 2022-01-26 2022-02-05 2022-08-08 2022-02-26 2022-06-20 2022-04-02 2022-09-29 Expressionof Interest - comp ant Selection ation rge-Scale Oceanic Fisheries onent 1.1: State ofthe art MC S Facility Betio KI-MFMRD-262661-CS-CQS / Strengthening Monitoring, C Port State Measures Impleme Individual Consult Under Implement IDA / D5570 ontrol and Surveillance of La Post Open 60,000.00 0.00 2021-11-26 2021-12-09 2022-02-05 2022-02-26 2022-04-02 2022-09-29 ntation Support Consultancy ant Selection ation rge-Scale Oceanic Fisheries : Component 1 subcomponen t 1.4.5 Page 3 KI-MFMRD-262665-CS-CQS / ToR for Policy Work and Conc Improving Seafood Toxicolog eptualizing Seafood Toxicolo Individual Consult IDA / D5570 y and Safety Measures in Sel Post Open 245,000.00 0.00 Canceled 2021-11-26 2021-12-09 2022-02-15 2022-03-08 2022-04-12 2022-10-09 gy and Coastal Fishereies La ant Selection ected Fisheries boratories | Financed under c omponent 3 subcomponents 3.2 & 3.5 KI-MFMRD-290475-CS-CDS / Strengthening Monitoring, C Fisheries Specialist2 IDA / D5570 ontrol and Surveillance of La Post Direct Selection Direct 17,250.00 17,250.00 Signed 2022-04-19 2022-05-03 2022-04-29 2022-04-06 2022-05-09 2022-05-24 2022-06-09 . rge-Scale Oceanic Fisheries KI-MFMRD-290479-CS-CQS / Delivering Effective Project Individual Consult IDA / D5570 Post Open 26,000.00 26,000.00 Signed 2022-04-28 2022-02-18 2022-06-16 2022-04-14 2022-07-07 2022-04-14 2022-08-11 2022-04-26 2023-02-07 Procurement Officer Management ant Selection KI-MFMRD-154271-CS-INDV / Diversifying Marine-Based R Individual Consult CPPL Building Study & Supply IDA / D5570 evenue Streams for Outer Isl Post Open 390,000.00 0.00 Canceled 2022-04-08 2022-06-03 2022-06-24 2022-07-25 2023-07-15 ant Selection Chain in the Line Islands and Coastal Communities KI-MFMRD-328800-CS-INDV / Diversifying Marine-Based R Individual Consult Open - Internationa CPPL Building study in Kiritim IDA / D5570 evenue Streams for Outer Isl Post 70,000.00 0.00 Canceled 2023-01-08 2023-02-26 2023-03-19 2023-04-23 2023-10-20 ant Selection l ati Island. and Coastal Communities KI-MFMRD-339187-CS-INDV / Delivering Effective Project Individual Consult Under Implement IDA / D5570 Post Open - National 26,000.00 0.00 2023-01-30 2023-01-06 2023-03-20 2023-03-09 2023-04-10 2023-02-08 2023-05-15 2023-11-11 PROP Finance Officer Management ant Selection ation KI-MFMRD-339186-CS-INDV / Delivering Effective Project Individual Consult Under Implement IDA / D5570 Post Open - National 36,400.00 0.00 2023-01-30 2023-03-01 2023-03-20 2023-01-12 2023-04-10 2023-05-15 2023-11-11 PROP Gender Specialist Management ant Selection ation KI-MFMRD-346446-CS-INDV / Delivering Effective Project Individual Consult Under Implement PROP Safeguard and Commu IDA / D5570 Post Open - National 36,400.00 0.00 2023-03-01 2023-03-01 2023-04-19 2023-03-23 2023-05-10 2023-03-27 2023-06-14 2023-12-11 Management ant Selection ation nication Specialist Strengthening Monitoring, C KI-MFMRD-362570-CS-CDS / Direct - Internation Under Implement IDA / D5570 ontrol and Surveillance of La Post Direct Selection 25,000.00 0.00 2023-04-28 2023-05-19 2023-05-08 2023-05-09 2023-07-12 2024-01-08 PROP Fisheries Specialist al ation rge-Scale Oceanic Fisheries MFMRD-CS-IND-8 / Solar Salt Diversifying Marine-Based R Individual Consult Pending Impleme Rapid Assessment - Beru Nik IDA / D5570 evenue Streams for Outer Isl Post Open - National 48,000.00 0.00 2023-07-03 2023-08-21 2023-09-11 2023-10-16 2024-04-13 ant Selection ntation u and Coastal Communities KI-MFMRD-366617-CS-INDV / Strengthening Monitoring, C Individual Consult Open - Internationa Pending Impleme Technical advisor for tranship IDA / D5570 ontrol and Surveillance of La Post 40,000.00 0.00 2023-06-30 2023-08-18 2023-09-08 2023-10-13 2024-04-10 ant Selection l ntation ment monitoring support rge-Scale Oceanic Fisheries KI-MFMRD-262660-CS-CQS / Electronic Reporting (e-repor ting) Policy,Capacity Building Strengthening Monitoring, C , Implementation support an Individual Consult IDA / D5570 ontrol and Surveillance of La Post Open 60,000.00 0.00 Canceled 2021-11-26 2021-12-09 2022-02-05 2022-02-26 2022-04-02 2022-09-29 d training : Component 1 sub ant Selection rge-Scale Oceanic Fisheries components 1.1 & 1.2 | Finan ced under component 1.1.3 a nd 1.2.3 for year 1 operation al budget total is halve KI-MFMRD-262662-CS-CQS / Consultant on Electronic Mon itoring Policy, Capacity Buiildi Strengthening Monitoring, C Individual Consult ng, Implementation Support IDA / D5570 ontrol and Surveillance of La Post Open 60,000.00 0.00 Canceled 2021-11-26 2021-12-08 2022-02-05 2022-02-26 2022-04-02 2022-09-29 ant Selection and Training | Financed unde rge-Scale Oceanic Fisheries r component 1.1.3 and 1.2.3 where year 1 operational bud get is halve. KI-MFMRD-262663-CS-CQS / Observer de-briefer and train Strengthening Monitoring, C Individual Consult er training consultant | Finan IDA / D5570 ontrol and Surveillance of La Post Open 30,000.00 0.00 Canceled 2021-11-26 2021-12-08 2022-02-05 2022-02-26 2022-04-02 2022-09-29 ant Selection ced under component 1.4.9 f rge-Scale Oceanic Fisheries or year 1 operational year Page 4 PROJECT: GHANA TREE CROP DIVERSIFICATION PROJECT (GTCDP) Project Identification No. P180060 PROCUREMENT PLAN SIMPLIFIED VERSION N° 1: PROJECT PREPRATION ADVANCE (PPA) ACTIVITIES I. General 1. Project Information Borrower : Government of Ghana Lead Department : Ministry of Food and Agriculture Project Name : Ghana Tree Crop Diversification Project (GTCPD) Identification : P180060 IDA N° : - Agency responsible : Ministry of Food and Agriculture (MOFA)/Tree Crop for implementing Development Authority (TDCA) and Ghana Cocoa the project Board (COCOBOD) 2. Date of approval by the Bank of the contracting plan: December 2022 3. Date of publication of the General Notice of Procurement: Not Applicable 4. Period covered by the Procurement Plan (only PPA): December 2022 to December 2023 5. Evaluation of risk as per the P-RAMS: High Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank's Standard Procurement Files shall be used for all contracts subject to international competition, as well as for all other contracts subject to this obligation as specified in the tables of the STEP procurement plan. 2 National procurement procedures: In accordance with paragraph 5.3 of the Procurement Rules, in the event that the procurement procedure is conducted at the national level (as specified in the tables of the procurement plan included in STEP), the national procurement procedures of the country concerned may be used.  If the Borrower uses its own open national tender procedures as set out in the Public Procurement Act, 2003 (Act 663), which was amended in 2016 by the Public Procurement (Amendment) Act, 2016, (Act 914), and the related implementing texts, such arrangements shall be subject to the provisions of paragraph 5.4 of the Procurement Rules and to the following conditions: • The tender/proposal documents oblige the Bidder(s) submitting a Bid/Proposal to submit a signed approval, which will be attached to any contract, to confirm that it complies with the Bank's Anti-Corruption Guidelines, including without limitation, the Bank's right to sanction and the Bank's rights for inspection and audit; • The procurement documents contain arrangements agreed with the Bank to mitigate environmental, social (including sexual exploitation and abuse and gender-based violence), and health and safety ("HSS") risks and impacts; • The Bank's right to review the file and procurement activities.  Where the Borrower uses procedures other than the national open tender, such procedures shall be in accordance with the provisions of paragraph 5.5 of the Procurement Rules. Leasing as specified in paragraph 5.10 of the Procurement Regulations: Leasing may be used for contracts indicated as such in the Procurement Plan. "Not applicable" Purchase of second-hand goods as specified in paragraph 5.11 of the Procurement Regulations is permitted for contracts indicated as such in the Procurement Plan. "Not applicable" National preference as specified in paragraph 5.51 of the Procurement (Supplies and Works) Regulations. Hands-on Expanded Implementation Support (HEIS) as specified in paragraphs 3.10 and 3.11 of the Procurement Regulations does not apply. Other Relevant Procurement Information SELECTION OF CONSULTANTS 1. Provisions relating to prior review and post review shall be as set out in paragraphs 3.5 to 3.8 of Section III, and Annex II of the Procurement Regulations for Borrowers Seeking Investment Project Financing (IPF) of November 2020. 3 2. Shortlist composed entirely of national firms: The shortlist of consultants for engineering & construction supervision consultancy services estimated at less than or equal to US$ 500,000 per contract, and for any other type of consulting services, estimated at less than US$ 300,000 per contract, may consist entirely of national consultants in accordance with the provisions of this contract. 3. Other Special Consultant Selection Arrangement: The threshold for the use of the consultant selection method based on the qualifications of consultants has been determined on a case-by-case basis considering the nature and complexity of the engagement. The estimated cost for these services should however not exceed the equivalent of US$ 300,000 except in exceptional cases such as emergency situations in accordance with the Procurement Regulation. The simplified procurement plan for the PPA activities is as presented below: Consulting Services Contracts- COCOBOD 1. 2. 3. 4. 5. 6. 7. 8. 9. Ref. Description Ref. Estimat Selecti Bank Date of Market Expected N° Compon ed Cost on Review Initiation approac Completion ent (US$) Method (Prior/Pos h t) 1 Consultancy to conduct technical audit of PPA 100,000 CQS Prior - December Open - December CMC, assessment of IT infrastructure and review 2022 National 2023 logistics for COCOBOD 2 Consultancy for capacity assessment; PPA 80,000 IC Prior - December Open - December strengthening of R & D towards review 2022 National 2023 development of an integrated management of CSSVD at CRIG 3 Consultancy for climate change PPA 250,000 CQS Prior - December Open - December monitoring, acquisition of carbon credits review 2022 National 2023 by farmer etc. 4 Consultancy for review and updating of PPA 150,000 CQS Prior - December Open - December protocols for rehabilitation of CSSVD review 2022 National 2023 infested and Moribund/over aged farms 5 Consultancy for the development of PPA 150,000 CQS Prior - December Open - December manual for Cocoa Extension review 2022 National 2023 6 Consultancy for strategy to increase PPA 70,000 CQS Prior - December Open - December adoption of GAP by Farmers review 2022 National 2023 7 Consultancy to conduct studies to PPA 30,000 IC Prior - December Open - December determine the adequacy of review 2022 National 2023 compensations payments for farmers 8 Consultancy to develop a strategy PPA 50,000 IC Prior - December Open - December document for the implementation of review 2022 National 2023 sustainable intensification, finance mechanism 9 Consultancy to conduct input subsidy PPA 60,000 IC Prior - December Open - December programme assessment review 2022 National 2023 10 Consultancy to undertake market PPA 70,000 CQS Prior - December Open - December scoping review 2022 National 2023 5 11 Consultancy to conduct assessment and PPA 50,000 IC Prior - December Open - December design of components pertaining to review 2022 National 2023 support to private investment in postharvest and processing infrastructure for value additions and financing mechanism needs Consulting Services Contracts-TCDA 1. 2. 3. 4. 5. 6. 7. 8. 9. Ref. Description Ref. Estimat Selecti Bank Date of Market Expected N° Compon ed Cost on Review Initiation approac Completion ent (US$) Method (Prior/Pos h t) 1 Consultancy to conduct a TCDA PPA 200,000 QCBS Prior - December Open - December organizational capacity needs review 2022 National 2023 assessment and design an appropriate organizational development (OD) training programme for TCDA. 2 Consultancy to conduct capacity PPA 100,000 CQS Prior - December Open - December assessment of selected research review 2022 National 2023 institutions 3 Consultancy for the development of web- PPA 400,000 QCBS Prior - December Open - December based platform, mobile app for TCDA review 2022 National 2023 4 Consultancy to carry out feasibility PPA 300,000 QCBS Prior - December Open - December studies and design the proposed Hub and review 2022 National 2023 Spoke concept for private sector input delivery system 5 Consultancy to develop a Project PPA 50,000 IC Prior - December Open - December strategy for implementation of hub and review 2022 National 2023 spoke (modalities, responsibilities/ implementing), including financing mechanism for cashew and coconut. 6 Consultancy to examine the PPA 100,000 CQS Prior - December Open - December opportunities in the tree crop value chain review 2022 National 2023 (cashew and coconut) and the challenges within the private sector involved 7 Consultancy to conduct studies on PPA 50,000 IC Prior - December Open - December creating enabling environment (policies, review 2022 National 2023 regulations and penalties etc.) for VCs. 7 8 Consultancy for the strengthening PPA 50,000 IC Prior - December Open - December coconut sanitary and phytosanitary review 2022 National 2023 advisory in Ghana. 9 Consultancy for understanding the PPA 50,000 IC Prior - December Open - December potential through value addition and review 2022 National 2023 processing for coconut by product as well as climate adaptation, mitigation impact etc. Consulting Services Contracts- MOFA, COCOBOD & TCDA 1. 2. 3. 4. 5. 6. 7. 8. 9. Ref. Description Ref. Estimat Selecti Bank Date of Market Expected N° Compon ed Cost on Review Initiation approac Completion ent (US$) Method (Prior/Pos h t) 1 Consultancy for assessment of key target PPA 30,000 IC Prior - December Open - December areas by crop (and jointly) and establish review 2022 National 2023 criteria for selection of target communities + selection of beneficiaries for implementation manual use 2 Consultancy for the baseline study for PPA 40,000 IC Prior - December Open - December GSTEP review 2022 National 2023 3 Consultancy for development of Project PPA 30,000 IC Prior - December Open - December implementation manual (PIM) review 2022 National 2023 4 Consultancy for development of M &E PPA 20,000 IC Prior - December Open - December manual review 2022 National 2023 5 Consultancy for the development of PPA 210,000 CQS Prior - December Open - December Environmental and Social Management review 2022 National 2023 Instruments 6 Consultancy for the elaboration of PPA 20,000 IC Prior - December Open - December communications strategy review 2022 National 2023 Glossary of Acronyms and Abbreviations PP Procurement Plan ICT International Call for Tenders NCT National Call for Tenders RFQ Request for Quotations CQS Selection Based on Quality QCBS Selection Based on Consultants' Qualification IC Individual Consultant DS/DA Direct Selection or Direct Agreement Post Post-clearance review Prior A prior review PROCUREMENT Ghana : Ghana Tree Crop Diversification Project PLAN General Information Country: Ghana 2022-12-23 Bank’s Approval Date of the Original Procurement Plan: 2023-06-07 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P180060 GPN Date: Project Name: Ghana Tree Crop Diversification Project Loan / Credit No: IDA / V4540 Ministry of Food and Agriculture/Tree Crop Development Authority Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GH-MOFA/TCDA-363425-GO- C1. Institutional Strengtheni RFQ / Supply and Installation Request for Quota Single Stage - One E Under Imple IDA / V4540 ng and Value Chain Governa Post Limited 75,000.00 0.00 2023-06-02 2023-06-14 2023-07-28 2023-10-26 of 2no. servers and 3no. proc tions nvelope mentation nce essing machines for TCDA NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GH-MOFA/TCDA-333756-CS- QCBS / Consultancy to condu ct a TCDA organizational cap Quality And Cost- IDA / V4540 Post Open - National 200,000.00 0.00 Canceled 2023-04-02 2023-04-23 2023-05-21 2023-06-04 2023-06-18 2023-07-16 2023-08-06 2023-11-04 acity needs assessment and Based Selection design an appropriate organi zational development (OD) tr aining programme for TCDA GH-MOFA/TCDA-334128-CS- QCBS / Consultancy to condu ct a TCDA organizational cap Quality And Cost- Under Implement IDA / V4540 Post Open - National 200,000.00 0.00 2023-04-02 2023-01-07 2023-04-23 2023-03-01 2023-05-21 2023-06-04 2023-06-18 2023-07-16 2023-08-06 2023-11-04 acity needs assessment and Based Selection ation design an appropriate organi zational development (OD) tr aining programme for TCDA GH-MOFA/TCDA-336196-CS- C1. Institutional Strengtheni QCBS / Consultancy services Quality And Cost- Under Implement IDA / V4540 ng and Value Chain Governa Post Open - National 100,000.00 0.00 2023-02-07 2023-02-28 2023-02-28 2023-03-01 2023-04-13 2023-05-11 2023-06-10 2023-07-15 2023-08-19 2023-12-17 to conduct Capacity Assessm Based Selection ation nce ent of Public Research Institu tions GH-MOFA/TCDA-343811-CS- QCBS / Multidisciplinary cons ulting services for a feasibilit C1. Institutional Strengtheni Quality And Cost- Under Implement y study to enhance private s IDA / V4540 ng and Value Chain Governa Post Open - National 100,000.00 0.00 2023-02-20 2023-02-28 2023-03-13 2023-03-01 2023-04-26 2023-05-24 2023-06-23 2023-07-28 2023-09-01 2023-11-30 Based Selection ation ector competitiveness in cas nce hew, coconut and rubber val ue addition, processing, and marketing. INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GH-MOFA/TCDA-332472-CS-I Individual Consult NDV / Consultancy for stakeh IDA / V4540 Post Direct - National 15,000.00 0.00 Canceled 2022-12-28 2022-12-25 2023-01-07 2023-01-17 2023-01-27 2023-03-28 ant Selection older engagement plan GH-MOFA/TCDA-332474-CS-I Individual Consult NDV / Consultancy for Labour IDA / V4540 Post Direct - National 20,000.00 0.00 Canceled 2022-12-28 2022-12-25 2023-01-07 2023-01-17 2023-01-27 2023-03-28 ant Selection Management Procedures GH-MOFA/TCDA-332478-CS-I Individual Consult NDV / Consultancy for integr IDA / V4540 Post Direct - National 30,000.00 0.00 Canceled 2022-12-28 2022-12-25 2023-01-07 2023-01-17 2023-01-27 2023-03-28 ant Selection ated pest management plan GH-MOFA/TCDA-334123-CS-I Individual Consult NDV / Consultancy for Stakeh IDA / V4540 Prior Direct - National 15,000.00 0.00 Signed 2022-12-29 2022-12-31 2023-01-08 2023-01-16 2023-01-18 2023-01-25 2023-01-28 2023-03-29 ant Selection older Engagement Plan (SEP) GH-MOFA/TCDA-334122-CS-I Individual Consult NDV / Consultancy for Labour IDA / V4540 Prior Direct - National 20,000.00 0.00 Signed 2022-12-29 2022-12-31 2023-01-08 2023-01-16 2023-01-18 2023-02-01 2023-01-28 2023-03-29 ant Selection Management Procedures (LM P) GH-MOFA/TCDA-334124-CS-I Individual Consult NDV / Consultancy for Integr IDA / V4540 Prior Direct - National 30,000.00 0.00 Signed 2022-12-29 2022-12-31 2023-01-08 2023-01-16 2023-01-18 2023-01-25 2023-01-28 2023-03-29 ant Selection ated Pest Management Plan GH-MOFA/TCDA-337114-CS- CDS / Operationalization of t C2. Improving Tree Crops Pr he Tree Crops Development Under Implement IDA / V4540 oductivity and Climate Resili Post Direct Selection Direct - National 60,000.00 0.00 2023-02-28 2023-03-07 2023-03-10 2023-05-14 2023-08-22 Authority E-Digital Solution fo ation ence r enhanced traceable tree cr op supply chains and revenu e mobilization Page 1 PROCUREMENT PLAN (Textual Part) Project information: OECS Regional Health Project P168539 , Commonwealth of Dominica, Grenada, Saint Lucia, Saint Vincent, Caribbean Public Health Agency (CARPHA) and the OECS Commission Project Implementation agencies: MoH StL, MoH SVG, MoH Grenada, MoH Domonica, CARPHA & OECS Commission Date of the Procurement Plan: [01-24-2020] Period covered by this Procurement Plan: 01/24/2020-01-24/2022 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Not Applicable Other Relevant Procurement Information. 1. Procurement Plan for the Project- St. Lucia Type of Contract Ref. Selection Me Contract Signing . Activity Description Procurem Completion Date No. thod Date (Planned) ent (Planned) Establish National Standards for the implementation and use of an independent 1 1.01 quality control mechanism Consultant CQS 15 Feb 2020 15 Aug 2020 for physical infrastructure and internal finishing of health facilities. Type of Contract Ref. Selection Me Contract Signing . Activity Description Procurem Completion Date No. thod Date (Planned) ent (Planned) SMART Health Facilities 2 Works RFB (National) 15 Jan 2020 15 Jan 2023 1.02 Retrofitting a. Design and Supervision Consultant CQS 15 Jan 2020 15 Jan 2023 RFQ 3 Laboratory Infrastructure Goods/ICT 15 Mar 2020 15 Jun 2020 (International) 1.03 Capacity Building (Food Consultant CQS 15 Mar 2020 15 Jun 2020 Safety) 9 1.08 Specimen Transportation Goods/ICT RFQ (National) 15 Jul 2021 15 Dec 2022 10 2.1 Lab Data Management Tool Goods/ICT RFQ (National) 15 Apr 2020 15 Jun 2021 4 Medical Technologists 11 2.2 Training NA TBD TBD (Training Skills) 2 Pathologists (Training 12 3 Training NA TBD TBD Skills) 2 Histotechnologists 13 3 Training NA TBD TBD (Training Skills) 14 3 Lab Disaster Management Training NA TBD TBD Training for Capacity Type of Contract Ref. Selection Me Contract Signing . Activity Description Procurem Completion Date No. thod Date (Planned) ent (Planned) Building/skills for laboratory staff RFQ 17 2.03 Food safety equipment Goods/ICT 15 Apr 2020 15 Jun 2021 (International) Health and Safety RFQ 18 2.04 improvement in the Goods/ICT 15 Apr 2020 15 Jun 2021 (International) workplace (equipment) Vector Control Programme – Capacity Building for Vector Control Officers in Vector Consultant CQS 15 Jun 2021 15 Jul 2022 Management and Surveillance Capacity Building for 19 2.05 Community Groups and Local Consultant CQS Government Procurement of Essential equipment to support and RFQ implement the vector control Goods/ICT 15 Aug 2020 15 Dec 2021 (International) programme (Entomology Laboratory) Type of Contract Ref. Selection Me Contract Signing . Activity Description Procurem Completion Date No. thod Date (Planned) ent (Planned) 2.08 Capacity building at Ports of Consultant CQS 15 Jun 2021 15 Jul 2022 a Entry – Training 22 2.08 Capacity Building at Ports of Goods/ICT RFQ (National) 15 Aug 2020 15 Dec 2021 b Entry – Equipment Finalization and Implementation of the 2.09 national health disaster Consultant CQS 15 Jan 2021 15 Jun 2022 a management plan – Consultancy on Comm. 23 Finalization and implementation of the 2.10 national health disaster Goods/ICT RFQ (National) 15 Mar 2021 15 Jun 2022 b management plan – Equipment 25 2.11 Hearse Goods/ICT RFQ (National) 15 Feb 2020 15Apr 2021 Caribbean Field Epidemiology RFQ (National) and Laboratory Training 15 Feb 2022 Goods/ICT 15 Feb 2020 Programme (Cr-FELTP) Frontline Training Caribbean Field Epidemiology Goods/ICT RFQ (National) 15 Feb 2020 15 Feb 2022 and Laboratory Training Type of Contract Ref. Selection Me Contract Signing . Activity Description Procurem Completion Date No. thod Date (Planned) ent (Planned) Programme (Cr-FELTP) Level 1 Training Project Management 26 3.01 Operational Expensed NA NA Total project cost 2. Procurement Plan for the Project- OECS Commission Re Type of Contract Contract f. Selection Me No Activity Description Procurem Signing Date Completion Date No thod ent (Planned) (Planned) . Consultancy for Health Facilities Inventory- Inventory of All Emergency/ Urgent Care Facilities in Consultant 1.1 CQS 22-Feb-20 18-Nov-20 four Countries and Emergency and Services Critical Care Services- Procurement of Software for 1.2 Database of Inventory and for GIS Goods RFQ 8-Feb-20 08-May-20 Mapping Lab Transport System Assessment and Action Plan for implementation of Consultant 1.3 IC 16-Oct-19 12-Apr20 agreements, policy and legislation Services (PPA Activity) Development and Implementation of Lab transportation Agreements and Consultant 1.4 QCBS 13-Nov-20 8-Nov-21 Policies Services OECS Pharmaceutical Facility - Support for Existing Software Direct 1.5 Goods 8-Feb-20 08-May-20 Development Selection Re Type of Contract Contract f. Selection Me No Activity Description Procurem Signing Date Completion Date No thod ent (Planned) (Planned) . Initiative for implementation of policy Consultant Direct 1.7 10-Mar-20 5-Mar-21 and legislation - CMLF Services Selection Development of Resource budgets and plans for Countries to meet LQMS Consultant Direct 1.8 7-Oct-19 5-Jan-20 Tier 1 and Tier 2 Requirements – Services Selection CMLF (PPA Activity) Development of relevant Policies and Legislation to facilitate the OECS Consultant 2.1 CQS 26-May-20 21-May-21 Unique ID Services Regional Public Education Campaign Risk Assessment and Action Plan for Implementation of OECS Unique ID Consultant 2.2 CQS 26-Oct-19 24-Jan-20 linked to a Unique Health Identifier Services (PPA Activity) Complete Risk Assessment and Develop and Action Plan for OECS Consultant 2.3 CQS 28-Mar-21 26-Jul-21 Health Emergency Services Services Coordinating Mechanism Prepositioned contract development Consultant 2.4 CQS 26-Jan-20 24-Jun-20 assignment Services Re Type of Contract Contract f. Selection Me No Activity Description Procurem Signing Date Completion Date No thod ent (Planned) (Planned) . Procurement of software to manage 2.5 Goods RFB 15-Mar-20 05-Nov-20 pre-positioned contracts Consultancy for Assessment of Registration Process and Requirement Consultant 2.6 ICS 1-Apr-20 30-Jun-20 for Software to Facilitate Services Harmonisation Web-based platform for registration 2.7 of Health Professional (Consultancy to Goods RFB 12-Oct-20 9-Feb-21 undertake assessment $48,000) Training 2.8 Training NA Meeting for harmonization of 2.9 Registration Requirements for Health Workshop NA professional PIU Staff (Project Manager, IC / Direct Procurement Officer, Accountant, Consultant Selection 3.1 1-Nov-19 30-Oct-22 Project Assistant) Services Multiple 3.2 Procurement of Office Equipment Goods RFQ 8-Sep-19 6-Jan-20 Re Type of Contract Contract f. Selection Me No Activity Description Procurem Signing Date Completion Date No thod ent (Planned) (Planned) . 3.3 Procurement of Office Furniture Goods RFQ 8-Sep-19 6-Jan-20 Procurement of Office Supplies 3.4 Goods RFQ 8-Sep-19 6-Jan-20 Retrofitting of existing office building 3.5 Works RFQ 8-Sep-19 7-Dec-19 Procurement of Audit Firm to Consultant 3.6 undertake Project Audit LCS 20-Nov-20 4-Jan-21 Services Operating Expenses 3.7 NA NA NA NA Total 3. Procurement Plan for the Project- Dominica No Re Activity Description Type of Selection Contract Contract Completion Date . f. Procure Signing Date (Planned) Method No ment (Planned) . 1 Upgrade works for 3 health centres - Castle Bruce (800k) + St Joseph ($700k) + Wesley ($500k): -Extension of physical structure & construction of additional rooms (Wesley only) Design/supervision Consulta CQS 15-Dec-19 30-Apr-22 ncy Works Works RFB 15-Apr-20 15-Apr-21 (National) Furniture/equipment Goods RFQ 15-Mar-21 15-Apr-21 (National) 2 Community outreach, printed Goods RFQ TBD TBD material, rental of PA System, etc. (National) 3 Biomedical Waste Management; Goods RFQ TBD TBD improvement for resiliency: (Internatio nal) Purchase of waste management vehicle to transport biomedical waste No Re Activity Description Type of Selection Contract Contract Completion Date . f. Procure Signing Date (Planned) Method No ment (Planned) . 4 Biomedical Waste Management; Goods RFQ TBD TBD improvement for resiliency: (National) Improve Storage of Biomedical Waste at sites including purchase refrigerators 5 Biomedical Waste Management; Training TBD improvement for resiliency: Training of medical staff to handle biomedical waste management 6 Upgrade laboratory facility and Goods RFQ TBD TBD capacity by equipping district (National) hospital lab in Portsmouth, Marigot, La Plaine & Grand Bay Expand testing and support with diagnostic capacity (procurement of Purchase analyzers to include handheld systems e.g. i-stat 7 Strengthen laboratory data Goods/IC RFQ TBD TBD management system – Supply and T (National) Installation of additional components of existing Lab Information System (Schuylab); Schuylab Remote Printing, Schuylab web base No Re Activity Description Type of Selection Contract Contract Completion Date . f. Procure Signing Date (Planned) Method No ment (Planned) . 8 Ensure adequate transportation Goods RFQ TBD TBD of laboratory specimen: (National) • Purchase solar refrigerators (2) and regular refrigerators - Main Lab and Portsmouth • sturdy Icebox coolers – Type 3 District Health Centers (7) transportation of samples • shipping containers – Main lab (for shipping samples overseas) 9 Training for managing essential Training TBD Laboratory functions 10 Consultant to Develop and Consulta IC TBD TBD implement Quality Management ncy national System 11 Mapping of prevalence of Goods/IC RFQ TBD TBD communicable diseases - including T (National) vector borne diseases and leptospirosis. Mapping i.e. geocode of No Re Activity Description Type of Selection Contract Contract Completion Date . f. Procure Signing Date (Planned) Method No ment (Planned) . all health facilities and towns/villages/hamlets •Equipment – GPS device (Garmin eTrex 20x GPS), 5qty. •GIS software 12 Training of Mapping i.e. geocode of Training all health facilities and towns/villages/hamlets on the Island 13 Set up and equip situation room Goods/IC RFQ TBD TBD Command Centre Communication T (National) Equipment to include 14 Set up and equip situation Goods/IC RFQ TBD TBD Room/HEOCs/Emergency Command T (National) Centre 15 Strengthen health information Goods/IC RFQ TBD TBD system. Equipment for Health T (National) Information Unit 16 Strengthening public health system Consulta TBD TBD by improving public health ncy IC emergency response to control (Internatio disease outbreaks and surveillance nal) systems No Re Activity Description Type of Selection Contract Contract Completion Date . f. Procure Signing Date (Planned) Method No ment (Planned) . 17 Health Emergency Preparedness plan Consulta IC National TBD TBD ncy 18 Project Officer for implementation Consulta IC TBD TBD (duration of the project) ncy National 19 Short Service Contracts in: Consulta IC National TBD TBD ncy • Procurement (when required) • Audit (annually) • Environmental safeguard Multiple (during retrofitting) TOTAL 4. Procurement Plan for the Project- St. Vincent Contract Contract Type of Signing Activity Description Selection Method Completion Date Procurement Date (Planned) (Planned) COMPONENT 1 Upgrade works for priority health facilities based on PAHO Smart Hospital criteria including Contract Contract Type of Signing Activity Description Selection Method Completion Date Procurement Date (Planned) (Planned) renovations, and retrofitting, furniture & equipment Design/supervision Consultancy CQS 15-Dec-19 30-Apr-22 Upgrade Works- Works RFB (National) 15-Apr-20 15-Apr-21 Furniture/equipment Goods RFQ (National) 15-Mar-21 15-Apr-21 Lab Equipment Goods RFQ (National) 15-Mar-21 15-Apr-21 Construction/Create a Public Health Laboratory Design/supervision - 50000 Consultancy CQS 15-Dec-19 30-Apr-22 Works - 1475000 Works RFB (National) 15-Apr-20 15-Apr-22 Public health Laboratory Equipment Goods/ICT RFQ (National) 15-May-21 15-May-22 300000 Furniture & Equipment - 100000 Goods/ICT RFQ (National) 15-May-21 15-May-22 Contract Contract Type of Signing Activity Description Selection Method Completion Date Procurement Date (Planned) (Planned) Strengthened laboratory data management systems - Lab Goods/ICT RFQ (National) 15-May-21 15-May-22 Information System with Health Information System (HIS) Improve the transportation system for laboratory specimens - Cold Goods/ICT RFQ (National) 15-Jul-21 15-Jul-22 chain and laboratory specimen transportation vehicle Strengthen Local capacity to utilize an enhanced regional reference Consultancy CQS 15-Jul-21 15-Jul-22 laboratory Training in Modern Laboratory Technology, Food Safety, Consultancy CQS 15-Jun-21 15-Jun-22 Entomology etc. Implement a regional quality assurance program and develop Consultancy CQS 15-Jun-21 15-Jun-22 common standards for National Laboratories, SVG. Provide training to ensure sufficient human resource capacity for Consultancy CQS 15-May-21 15-May-22 managing essential laboratory functions Contract Contract Type of Signing Activity Description Selection Method Completion Date Procurement Date (Planned) (Planned) Regional Accreditation of laboratories with quality standards Consultancy CQS 15-May-21 15-May-22 and development of quality assurance programs COMPONENT 2 Update/develop protocols (including development of an active case- Consultancy CQS 15-Mar-21 15-Sep-21 finding protocol for vector-borne diseases and clinical protocols) Strengthen health information systems for collection of incidence and prevalence data (HIS) ICT Equipment Goods/ICT RFQ (National) 15-Aug-21 15-Aug-23 Consultancy for ICT assessment, Consultancy CQS 15-Aug-21 15-Aug-23 training - Roll-out Field Epidemiology and Laboratory Training Program Consultancy CQS 15-Nov-19 15-Nov-20 (FELTP) among field-level epidemiologists (as needed) Contract Contract Type of Signing Activity Description Selection Method Completion Date Procurement Date (Planned) (Planned) Develop procedures on disease surveillance and information sharing with regard to infectious disease Consultancy CQS 15-Jan-20 15-Jan-21 protocols - microcephaly testing and confirmation in pregnant women suspected to be Zika infected Develop regional information and communications technology platform for surveillance and Consultancy CQS management, including Geographic Information Systems (GIS) 15-Jan-20 15-Jan-21 Renovation of Health Emergency Disaster Management Unit facility Design and supervision - Consultancy CQS 15-Dec-19 30-Apr-22 Works Works RFB (National) 15-Apr-20 15-Apr-21 EOC Equipment Goods/ICT RFB (National) 15-Apr-20 15-Apr-21 Disaster Supplies &Equipment- Goods/ICT RFB (National) 15-Apr-20 15-Apr-21 Furniture & Fixtures Goods/ICT RFB (National) 15-Apr-20 15-Apr-21 Contract Contract Type of Signing Activity Description Selection Method Completion Date Procurement Date (Planned) (Planned) Emergency Response Equipment Goods/ICT RFB (National) 15-Apr-20 15-Apr-21 Pickup truck (4ton) retrofitted with Goods/ICT RFB (National) 15-Apr-20 15-Apr-21 trailer truck Create external monitoring and assessment of core public health capacities of national structures to Consultancy meet International Health Regulations CQS 15-Jun-20 15-Dec-20 Plan and conduct simulation exercises and training on joint outbreak investigations as part of Consultancy CQS an early warning and response system 15-Jun-20 15-Dec-20 Develop/upgrade curriculum for training of country level health workforce in surveillance and Consultancy response for priority infectious diseases CQS 15-Dec-20 15-May-21 Component 3 Contract Contract Type of Signing Activity Description Selection Method Completion Date Procurement Date (Planned) (Planned) Project Financial Specialist Consultancy IC 1-Feb-20 1-Feb-24 Procurement Specialist Consultancy IC 1-Feb-20 1-Feb-24 Fiduciary capacity building for implementation - MOHWE staff Training trained to an enhanced fiduciary level NA 1-Oct-19 1-Oct-21 Project Monitoring and evaluation of Consultancy project activities IC 1-Oct-19 2-Oct-21 Project Audit Consultancy LCS 1-Feb-20 1-Feb-24 Biohazard Waste Management Plan Consultancy IC 1-Feb-20 1-Feb-23 Environmental and Social Consultancy Management Framework (ESMF) CQS 1-Feb-20 1-Feb-23 Office set up Goods DS 1-Sep-19 1-Dec-19 Operational Expenses N/A N/A TOTAL 5. Procurement Plan for the Project- CARPHA Type of N Activity Selection Me Contract Signing Contract Completion Ref. No. Procure o. Description thod Date (Planned) Date (Planned) ment Laboratory 1 - 2.1 G RFB 30-Sep-19 30-Nov-19 Equipment 1 - 2.1.6 Reagents G Single Source 30-Sep-19 29-Sep-24 Shipping 1 - 4.2.2 G RFQ 31-Jul-19 30-Sep-19 materials 2- Stationery and G RFQ 30-Sep-19 29-Sep-24 1.1.10 printing costs 2- Promotional G RFQ 27-Jul-20 30-Sep-20 1.1.11 materials 2- 3.3d/3.3 IT Goods G RFQ 30-Oct-19 29-Oct-20 f IT equipment for CARPHA; 2 - 1.1.9 country training G RFQ 29-May-20 31-Jul-20 and field projects Maintenance of Laboratory Equi 1 - 2.1.7 30-Sep-19 29-Sep-24 p-ment (New & Existing) NCS RFB Type of N Activity Selection Me Contract Signing Contract Completion Ref. No. Procure o. Description thod Date (Planned) Date (Planned) ment Proficiency testing (PT) programme for OECS 1- (including TR NA 30-Sep-19 30-Sep-24 3.1.1a standards, monitoring and supportive interventions) Perform PT at CARPHA to ensure that the 1- quality of testing NCS Single Source 30-Sep-19 29-Sep-24 3.1.1c services is being maintained and monitored Provide broadband service to 2 - 3.3e NCS RFQ 1-Oct-19 29--aug-24 support increased internet capacity Type of N Activity Selection Me Contract Signing Contract Completion Ref. No. Procure o. Description thod Date (Planned) Date (Planned) ment Type of N Activity Selection Me Contract Signing Contract Completion Ref. No. Procure o. Description thod Date (Planned) Date (Planned) ment Establishment of a regional system for 1 1 - 1.2.5 CS Single Source 30-Sep-19 14-Oct-19 validation of equipment and methods Software: Inform ation management 2 1 - 2.2.1 capacity for 25-Aug-21 integrated surveillance approaches CS FBS 26-Feb-21 Support mechanism for 3 1 - 2.2.2 inter-country 29-Jun-21 technical collaboration CS FBS 30-Jun-20 LIMS 4 1 - 2.2.3 Consultant/Deve 29-Oct-21 loper CS CQS 30-Jun-20 Building CARPHA 5 1 - 2.2.4 CS 30-Sep-19 29-Mar-22 LIMS capacity CQS 6 1-6 Communication CS CQS 30-Oct-20 30-Jul-22 products for Type of N Activity Selection Me Contract Signing Contract Completion Ref. No. Procure o. Description thod Date (Planned) Date (Planned) ment laboratory services Level III training 7 2 - 1.1.2 curriculum CS CQS 31-Aug-20 30-Apr-21 development "Train the trainers" progra m to increase 8 2 - 1.1.3 country capacity TR NA 31-Aug-20 30-Apr-21 for FELTP - Hire Training Consultant Upgrade and maintain 9 2 - 1.1.5 capacity for CS CQS 30-Sep-19 29-Sep-24 eLearning Platform - Contracts for 10 2 - 1.1.6 Subject Matter CS CQS 30-Jun-20 31-Aug-21 Experts (SMEs) - Contract for Training 11 2 - 1.1.6 CS CQS 30-Sep-19 31-Aug-20 Development consultant Type of N Activity Selection Me Contract Signing Contract Completion Ref. No. Procure o. Description thod Date (Planned) Date (Planned) ment Independent peer review/assessm ent of CARPHA’s existing 12 2 - 2.1b surveillance CS CQS 30-Jul-19 30-Nov-19 system and its adequacy to fulfil its public health surveillance role In-country support to developing routine reporting structures for 13 2 - 2.1d populating CS CQS 30-Oct-20 29-Oct-22 yearly ministerial report, also known as CMO Report Update and produce CARPHA 14 2 - 2.2a Data CS CQS 30-Oct-19 29-Oct-20 Appreciation and M&E manuals, Type of N Activity Selection Me Contract Signing Contract Completion Ref. No. Procure o. Description thod Date (Planned) Date (Planned) ment materials and tools to support public health surveillance Develop and roll out ICD-11 selection of underlying 15 2 - 2.6 cause of death CS IC 4-Jan-21 30-Oct-21 training towards the strengthening of mortality data Upgrade (to ICD- 11) and enhance, 16 2 - 2.8 CS CQS 2-Mar-21 30-Jun-21 mortality data capture tool (MORTBASE) Morbidity coding training 17 2 - 2.9a workshop to CS IC 1-Nov-20 30-Jun-22 improve morbidity data 18 2 - 3.1a IT Gap analysis, CS CQS 30-Jan-20 30-Mar-20 needs Type of N Activity Selection Me Contract Signing Contract Completion Ref. No. Procure o. Description thod Date (Planned) Date (Planned) ment assessment and architecture design to support CARPHA Regional Surveillance system Draft CARPHA's surveillance platform (using DHIS2) to integrate GIS 19 2 - 3.1 b CS CQS 30-Sep-21 2-Jan-22 and data visualization to enhance real time reporting and feedback DHIS2 platform 20 2 - 3.3a Maintenance of CS CQS 1-Oct-19 29--aug-24 service contract Improve IT capacity at 21 2 - 3.3b CARPHA to host CS CQS 1-Jun-20 30-Nov-20 DHIS-2 installation Type of N Activity Selection Me Contract Signing Contract Completion Ref. No. Procure o. Description thod Date (Planned) Date (Planned) ment Gap analysis on Data sharing interoperability between the selected CMS 22 2 - 3.4 CS CQS 30-Sep-20 29-Oct-21 using CARPHA LIMS and automatically importing data into DHIS2. Development of a mobile app for public health 23 2 - 3.5 alerts and CS CQS 30-Oct-20 29-Oct-21 dissemination of public health information Knowledge 24 2 - 3.6 CS CQS 30-Oct-19 29-Sep-22 Management Development of the action plan 25 2 - 4.2 for regional CS IC 30-Oct-20 30-Jun-21 preparedness and response 26 2 - 4.6 Simulation CS CQS 30-Sep-21 29-Sep-24 Exercise on Type of N Activity Selection Me Contract Signing Contract Completion Ref. No. Procure o. Description thod Date (Planned) Date (Planned) ment responding to public health emergencies Continued Implementation of 27 2 - 5.1 CS CQS 31-Jul-20 31-Jan-21 Communication and Marketing Plan Development of country-level National Action 28 2 - 6 CS QCBS 30-Aug-23 Pan for Health Security (NAPHS) 1-Sep-21 Regional level 29 2 - 7 workshop on JEE TR TR 29-Sep-20 self-evaluation 30-Sep-19 Development and Implementation 30 3 - 3.2.6 of CS CQS Communication Strategy for Increased 30-Sep-19 30-Aug-24 Visibility of Type of N Activity Selection Me Contract Signing Contract Completion Ref. No. Procure o. Description thod Date (Planned) Date (Planned) ment Grant, its outputs and outcomes 31 3 - 3.2.1 Project Officer CS IC 1-Oct-19 30-Sep-24 32 3 - 3.2.1 M&E officer CS IC 1-Oct-19 30-Sep-24 33 3 - 3.2.1 Finance Officer CS IC 1-Oct-19 30-Sep-24 Procurement 34 CS IC Officer 1-Oct-19 30-Sep-24 Total Amount 6. Procurement Plan for the Project- Grenada Re Type of N f. Selection Me Contract Signing Contract Completion Activity Description Procurem o. No thod Date (Planned) Date (Planned) ent . Procurement of upgrade works at 1 Mount Gay Psychiatric Works RFB 4-Jul-20 31-Jul-23 Hospital Re Type of N f. Selection Me Contract Signing Contract Completion Activity Description Procurem o. No thod Date (Planned) Date (Planned) ent . Consultancy to conduct situational analysis to establish Consultan 2 CQS 4-Nov-19 1-Mar-20 baseline for Child & cy Geriatric Mental health Services Procurement of upgrades and refurbishment to the 3 Works RFB 1-Nov-21 29-Jul-22 Isolation Room, ICU of the General Hospital and Rathdune Expansion of 5 Sauteaurs Health Works RFB 1-Mar-22 31-Aug-22 Centre Expansion of St. 6 David's Health Centre Works RFB 11-Jan-21 28-Apr-22 Consultancy to Implement critical Consultan 7 CQS 2-Mar-20 31-Dec-21 health system cy upgrades Re Type of N f. Selection Me Contract Signing Contract Completion Activity Description Procurem o. No thod Date (Planned) Date (Planned) ent . Procurement of equipment for the 9 Goods DS 1-Nov-19 30-Jun-20 upgrade of laboratory facilities Consultancy to Consultan 10 strengthen laboratory IC 1-Nov-19 31-Dec-20 cy information system Procurement of 11 equipment to Goods RFQ (National) 2-Mar-20 31-Dec-20 strengthen LIS Procurement of equipment to improve 12 Goods RFB 2-Mar-20 31-Dec-20 efficiency of lab operations Design and Supervision for the refurbishment of Mount Gay Hospital, Consultan 13 QCBS 5-Apr-20 31-Dec-24 General Hospital cy (Rathdune), Sauteurs and St. David's Health Centres Re Type of N f. Selection Me Contract Signing Contract Completion Activity Description Procurem o. No thod Date (Planned) Date (Planned) ent . Procurement of Furniture and 14 Goods RFB 1-Mar-22 31-Aug-23 Equipment for refurbished buildings Training in 13 Procurement for Staff Training TR 11-Mar-19 31-Jan-20 (Biomedical) Consultancy to provide Short Term IC 1-Jan-20 31-Dec-20 Training for New Lab Consultan 14 Technicians cy Consultancy to provide national training programme DS 1-Sep-20 1-Dec-23 for laboratory Consultan 14 technicians cy Consultancy to strengthen Consultan DS 15 surveillance systems cy 6-Jul-20 1-Jun-23 Re Type of N f. Selection Me Contract Signing Contract Completion Activity Description Procurem o. No thod Date (Planned) Date (Planned) ent . Strengthen Surveillance Systems TR 16 FELTP Training 1 & 2 Training 1-Sep-20 31-Jul-24 Consultancy to provide morbidity and Consultan DS 17 mortality Surveillance cy 1-Feb-21 31-Dec-22 Procurement of Hardware and RFQ software for chronic 18 disease registry Goods 1-Jul-20 31-Dec-20 Consultancy to guide in the development of Consultan IC 19 HEOC cy 1-Jan-20 30-Apr-20 Consultancy and implementation of Consultan IC 20 desktop simulation cy 1-Jan-24 31-Aug-24 Consultancy for the Training of emergency Consultan CQS 21 technicians cy 1-Jan-20 31-Jul-21 Procurement of ambulances, and RFB emergency response 22 vehicles Goods 1-Jan-21 31-Dec-21 Re Type of N f. Selection Me Contract Signing Contract Completion Activity Description Procurem o. No thod Date (Planned) Date (Planned) ent . Procurement of communications RFQ 23 equipment for HEOC Goods 1-Oct-20 30-Jul-21 Procurement of RFQ 24 Computer Equipment Goods 1-Oct-20 30-Jul-21 Procurement of Personal Protective RFQ 25 Equipment Goods 1-Oct-20 31-Dec-21 Training in TR 26 Psychological First Aid Training 1-Sep-20 30-Sep-21 Consultan IC 27 Project Coordinator cy 11-Nov-19 31-Dec-24 Procurement of RFQ 28 Project Vehicle Goods 11-Nov-19 31-Jan-20 Procurement of Computer and RFQ Acceories for Project 29 Office Goods 11-Nov-19 31-Jul-20 Project Operating Cost NA NA NA NA Re Type of N f. Selection Me Contract Signing Contract Completion Activity Description Procurem o. No thod Date (Planned) Date (Planned) ent . 30 Project Visibility NCS RFQ 1-Feb-20 4-Feb-20 Consultan IC 31 Project M & E Officer cy 1-Jan-21 31-Dec-21 Capacity Building for TR 32 Staff Training September,2020 1-Dec-22 Total PROCUREMENT OECS Countries : OECS Regional Health Project PLAN General Information Country: OECS Countries 2020-04-17 Bank’s Approval Date of the Original Procurement Plan: 2023-06-01 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P168539 GPN Date: 2020-05-21 Project Name: OECS Regional Health Project Loan / Credit No: IDA / 64810 Ministry of Health of SVG Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Request for Bids - SVGRHP-W-RFB-1 / Construc Strengthening Public Health Single Stage - One E Small Works SPD Pending Imp 2022-08-2 tion/upgrades of Selected He IDA / 64810 Surveillance and Emergency Post Request for Bids Open - National 500,000.00 0.00 2021-11-08 2021-11-13 2021-12-25 2022-01-24 2022-02-28 nvelope (1 envelope proce lementation 7 alth Facilities Management ss) SVGRHP-W - DC-3C / Electric Contingency Emergency Res Other (with field f Pending Imp 2022-05-2 al and plumbing connection t IDA / 64810 Post Direct Selection Direct 1,006.00 0.00 2022-04-18 2022-04-23 2022-05-14 ponse Component (CERC) or explanation) lementation 8 o laboratory container at Uni on Island. SVGRHP-W-DC-1A / Construc Contingency Emergency Res 2020-12-1 IDA / 64810 Post Direct Selection Direct 100,000.00 0.00 Canceled 2020-05-04 2020-05-09 2020-06-13 tion of Isolation staff hostel ponse Component (CERC) 0 SVGRHP-W-DC-1B / Isolation Contingency Emergency Res 2020-12-1 IDA / 64810 Post Direct Selection Direct 350,000.00 0.00 Canceled 2020-05-04 2020-05-09 2020-06-13 Facility ponse Component (CERC) 0 SVGRHP-W-DC-1C / Ancillary Contingency Emergency Res 2020-12-1 IDA / 64810 Post Direct Selection Direct 160,000.00 0.00 Canceled 2020-05-04 2020-05-09 2020-06-13 Buildings for Isolation Facility ponse Component (CERC) 0 GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SVGRHP-G-RFQ-1 / Purchase Improved Health Facilities a Request for Quota Single Stage - One E Under Imple IDA / 64810 Post Limited 50,000.00 0.00 2020-04-19 2020-04-28 2020-06-14 2020-12-11 of vehicle nd Laboratory Capacity tions nvelope mentation SVGRHP-G-DC-6 / QPCR Rea Contingency Emergency Res Pending Impl IDA / 64810 Post Direct Selection Direct 200,000.00 0.00 2020-04-20 2020-04-25 2020-05-30 2020-11-26 gents and Consumables ponse Component (CERC) ementation SVGRHP-G-DC-5 / Supportin Contingency Emergency Res Under Imple IDA / 64810 Post Direct Selection Direct 20,000.00 0.00 2020-04-20 2020-05-12 2020-04-25 2020-05-12 2020-05-30 2020-11-26 g Equipment - PRC System ponse Component (CERC) mentation SVGRHP-G-DC-4 / Q PRC Sys Contingency Emergency Res IDA / 64810 Post Direct Selection Direct 62,000.00 16,458.10 Signed 2020-04-20 2021-01-11 2020-04-25 2020-03-20 2020-05-30 2020-05-13 2020-11-26 tem ponse Component (CERC) SVGRHP-G-DC-3 / Mobile Isol Contingency Emergency Res IDA / 64810 Post Direct Selection Direct 2,500,000.00 256,241.31 Signed 2020-04-20 2020-11-30 2020-04-25 2020-02-14 2020-05-30 2020-04-02 2020-11-26 ation Units and Tents ponse Component (CERC) SVGRHP-G-DC-2 / Mobile Isol Contingency Emergency Res IDA / 64810 Post Direct Selection Direct 335,000.00 294,976.24 Signed 2020-04-20 2020-11-30 2020-04-25 2020-03-03 2020-05-30 2020-12-01 2020-11-26 ation Chambers and Tents ponse Component (CERC) SVGRHP-G-DC-1 / Isolation F Contingency Emergency Res Under Imple IDA / 64810 Post Direct Selection Direct 500,000.00 0.00 2020-04-22 2020-11-30 2020-04-27 2020-06-01 2020-11-28 acility - Equipment & Furnishi ponse Component (CERC) mentation ng SVGRHP-G-RFB-1 / Supply of Improved Health Facilities a Single Stage - One E Goods - Lab equipment: Com IDA / 64810 Post Request for Bids Open - National 135,000.00 149,327.66 Signed 2020-07-31 2020-11-06 2020-08-05 2020-09-16 2020-12-11 2020-10-16 2021-01-27 2020-11-20 2021-07-09 2021-05-19 nd Laboratory Capacity nvelope munity Level SVGRHP-G-RFQ-2 / Supply of Institutional Capacity Buildin Request for Quota Single Stage - One E Under Imple Goods, furniture and equipm IDA / 64810 g, Project Management and Post Open - National 10,000.00 0.00 2020-09-23 2020-11-18 2021-05-17 tions nvelope mentation ent Coordination SVGRHP-G-DC-11A / Equipm Contingency Emergency Res Under Imple IDA / 64810 Post Direct Selection Direct 5,000.00 0.00 2020-11-24 2021-02-02 2020-11-29 2020-07-24 2021-01-03 2021-07-02 ent to assist in data gatherin ponse Component (CERC) mentation g -laptops SVGRHP-G-DC-11B / COVID - Contingency Emergency Res Under Imple 19 Response - Equipment to IDA / 64810 Post Direct Selection Direct 5,000.00 0.00 2020-11-24 2021-02-02 2020-11-29 2020-07-24 2021-01-03 2021-07-02 ponse Component (CERC) mentation assist in data gathering - Lap tops SVGRHP-G-DC-10 / COVID-1 Contingency Emergency Res Pending Impl 9 Response - Consumables - IDA / 64810 Post Direct Selection Direct 120,000.00 0.00 2020-11-24 2020-11-29 2021-01-03 2021-07-02 ponse Component (CERC) ementation Personal Protective Equipme nt SVGRHP-G-DC-9 / COVID-19 Response - Supporting Equip Contingency Emergency Res Under Revie IDA / 64810 Prior Direct Selection Direct 350,000.00 0.00 2020-11-24 2021-04-28 2020-11-29 2021-01-03 2021-07-02 ment and consumables - Aut ponse Component (CERC) w omated extraction equipmen t SVGRHP-G-DC-8 / COVID-19 Contingency Emergency Res Under Imple Response - Supporting Equip IDA / 64810 Post Direct Selection Direct 200,000.00 0.00 2020-11-24 2021-02-02 2020-11-29 2020-07-08 2021-01-03 2021-07-02 ponse Component (CERC) mentation ment and consumables - Swa bs SVGRHP-G-DC-7 / COVID-19 Contingency Emergency Res Pending Impl Response - Supporting Equip IDA / 64810 Post Direct Selection Direct 325,000.00 0.00 2020-11-24 2020-11-29 2021-01-03 2021-07-02 ponse Component (CERC) ementation ment and consumables - Gen eral Items SVGRHP-G-RFB-2 / Procurem Contingency Emergency Res Single Stage - One E Pending Impl IDA / 64810 Post Request for Bids Open - National 15,000.00 0.00 2021-01-08 2021-01-13 2021-02-24 2021-03-26 2021-04-30 2021-10-27 ent of Supplies: Rape and HI ponse Component (CERC) nvelope ementation V rapid kits SVGRHP-G-DC-17 / Procurem Contingency Emergency Res ent of Acrylic Partitions at Ar IDA / 64810 Post Direct Selection Direct 6,000.00 0.00 Canceled 2021-01-19 2021-01-08 2021-01-24 2021-01-08 2021-02-28 2021-08-27 ponse Component (CERC) gyle Isolation Facility SVGRHP-G-DC-14 / COVID-1 Contingency Emergency Res Under Imple 9 Response - Consumables - IDA / 64810 Post Direct Selection Direct 30,000.00 0.00 2021-01-18 2021-02-02 2021-01-23 2022-12-09 2021-02-27 2021-08-26 ponse Component (CERC) mentation GeneXpert Machine Page 1 SVGRHP-G-DC-13 / COVID-1 Contingency Emergency Res Pending Impl 9 Response - Consumables - IDA / 64810 Post Direct Selection Direct 150,000.00 0.00 2021-01-18 2021-01-23 2021-02-27 2021-08-26 ponse Component (CERC) ementation Medical supplies for Isolation units SVGRHP-G-DC-12 / COVID-1 Contingency Emergency Res 9 Response - Consumables - IDA / 64810 Post Direct Selection Direct 300,000.00 174,374.00 Signed 2021-01-18 2021-02-04 2021-01-23 2021-01-13 2021-02-27 2021-04-20 2021-08-26 ponse Component (CERC) Containerized Laboratory an d Storage SVGRHP-G-DC-20 / COVID-1 Contingency Emergency Res Under Imple 9 Response - Consumables - IDA / 64810 Post Direct Selection Direct 147,600.00 0.00 2021-08-27 2021-09-03 2021-09-01 2021-04-12 2021-10-06 2022-04-04 ponse Component (CERC) mentation Testing supplies. SVGRHP-G-DC-23 / COVID-1 Contingency Emergency Res Request for Quota Single Stage - One E 9 Response - Equipment and IDA / 64810 Post Open - National 14,722.00 0.00 Canceled 2021-09-07 2021-11-02 2022-05-01 ponse Component (CERC) tions nvelope Furnishing for Isolation Facilit y - CCTV SVGRHP-W-RFQ-2 / COVID-1 9 Response - Containerized S Contingency Emergency Res Request for Quota Single Stage - One E Under Imple IDA / 64810 Post Open - National 10,000.00 0.00 2021-09-08 2021-11-03 2022-05-02 torage - Retrofitting works fo ponse Component (CERC) tions nvelope mentation r two (2) containers. SVGRHP-G-DC-18 / COVID-1 Contingency Emergency Res Pending Impl 9 Response - Containerized S IDA / 64810 Post Direct Selection Direct 3,720.00 0.00 2021-09-03 2021-09-08 2021-10-13 2022-04-11 ponse Component (CERC) ementation torage - 20ft Shipping Contai ners. SVGRHP-G-DC-24 / COVID-1 9 Response - Equipment and Contingency Emergency Res Under Imple Furnishing for Isolation Facilit IDA / 64810 Post Direct Selection Direct 176,100.00 0.00 2021-09-07 2021-09-08 2021-09-12 2021-09-02 2021-10-17 2022-04-15 ponse Component (CERC) mentation y - Medical Equipment - Argyl e Isolation Facility - BPF. SVGRHP-G-RFQ-9 / Equipme Contingency Emergency Res Request for Quota Single Stage - One E Pending Impl nt: Royal St. Vincent and the IDA / 64810 Post Open - National 10,000.00 0.00 2021-09-22 2021-11-17 2022-05-16 ponse Component (CERC) tions nvelope ementation Grenadines Police Force Sexu al Offenders Unit. SVGRHP-G-DC-21 / COVID-1 Contingency Emergency Res 9 Response - Consumables - IDA / 64810 Post Direct Selection Direct 250,000.00 432,050.00 Signed 2021-09-03 2021-09-09 2021-09-08 2021-09-02 2021-10-13 2021-09-10 2022-04-11 ponse Component (CERC) testing supplies SVGRHP-G-DC-26 / COVID-1 Contingency Emergency Res IDA / 64810 Post Direct Selection Direct 262,717.50 271,114.00 Signed 2021-11-03 2021-11-01 2021-11-08 2021-10-14 2021-12-13 2021-11-09 2022-06-11 9 Testing Supplies ponse Component (CERC) SVGRHP-G-DC-26(A) / COVID Contingency Emergency Res IDA / 64810 Post Direct Selection Direct 144,486.00 0.00 Canceled 2021-10-14 2021-11-09 2021-10-19 2021-11-23 2022-05-22 -19 Testing Supplies ponse Component (CERC) SVGRHP-G-DC-27 / Goods an Contingency Emergency Res Under Imple d Related Services for Servici IDA / 64810 Post Direct Selection Direct 15,009.00 0.00 2021-10-14 2021-11-09 2021-10-19 2021-11-11 2021-11-23 2022-05-22 ponse Component (CERC) mentation ng & Maintenance of QPCR M achine SVGRHP-RFQ-4 / COVID-19 R Contingency Emergency Res Request for Quota Single Stage - One E Under Imple IDA / 64810 Post Open - National 350,000.00 0.00 2021-08-24 2021-10-19 2022-04-17 esponse - PPE's. ponse Component (CERC) tions nvelope mentation SVGRHP-G-RFQ-26 (B) / COVI D-19 Response - Testing Sup Contingency Emergency Res Request for Quota Single Stage - One E IDA / 64810 Post Limited 262,717.50 0.00 Canceled 2021-11-08 2021-12-20 2022-02-28 plies (Extraction kits, Sample ponse Component (CERC) tions nvelope collections devices - VTMs et c.) SVGRHP-G-RFQ-4 / Personal Protective Equipment - for us Contingency Emergency Res Request for Quota Single Stage - One E Under Imple IDA / 64810 Post Limited 350,000.00 0.00 2021-11-15 2022-01-07 2021-12-30 2022-03-30 e in the Health Sector toward ponse Component (CERC) tions nvelope mentation s COVID-19 response. SVGRHP-G-DC-22 / Medical E Contingency Emergency Res Under Imple IDA / 64810 Post Direct Selection Direct 100,000.00 0.00 2021-11-10 2021-09-20 2021-11-15 2021-01-18 2021-12-09 2022-02-07 quipment - Mobile X-Ray ponse Component (CERC) mentation SVGRHP-G-RFQ-5 / Medical E Contingency Emergency Res Request for Quota Single Stage - One E IDA / 64810 Post Limited 361,184.40 0.00 Canceled 2021-12-27 2022-01-07 2022-02-10 2022-05-11 quipment, furniture and fittin ponse Component (CERC) tions nvelope gs SVGRHP-G-DC-26B / COVID- 19 Response - Testing Suppli Contingency Emergency Res Under Imple IDA / 64810 Post Direct Selection Direct 262,717.50 0.00 2022-01-10 2022-01-10 2022-01-15 2022-02-19 2022-08-18 es (Extraction kits, Sample c ponse Component (CERC) mentation ollections devices - VTMs etc. ) SVGRHP-G-RFQ-23 / COVID-1 Contingency Emergency Res Request for Quota Single Stage - One E Pending Impl 9 Response - Equipment and IDA / 64810 Post Open - National 14,722.00 0.00 2022-02-20 2022-04-17 2022-10-14 ponse Component (CERC) tions nvelope ementation Furnishing for Isolation Facilit y - CCTV SVGRHP-G-DC-26-C / COVID- Contingency Emergency Res Under Imple IDA / 64810 Post Direct Selection Direct 70,000.00 0.00 2022-01-04 2021-12-15 2022-01-09 2021-12-16 2022-02-13 2022-08-12 19 Testing Supplies ponse Component (CERC) mentation SVGRHP-G-DC-28 / COVID19 Contingency Emergency Res Under Imple IDA / 64810 Post Direct Selection Direct 50,000.00 0.00 2022-04-20 2022-04-24 2022-04-25 2022-05-30 2022-11-26 Response: GeneXpert Testin ponse Component (CERC) mentation g Kits SVGRHP-G-RFQ-29 / PCR Co Contingency Emergency Res Request for Quota Single Stage - One E Pending Impl IDA / 64810 Post Limited 14,950.00 0.00 2022-06-04 2022-07-05 2022-09-03 nsumables (Molecular Grade ponse Component (CERC) tions nvelope ementation Ethanol) SVGRHP-G-DC-30 / Testing S upplies (Modular SARS-CoV-2 Contingency Emergency Res Pending Impl IDA / 64810 Post Direct Selection Direct 22,500.00 0.00 2022-05-30 2022-06-04 2022-06-12 2022-08-11 RdRp 530,LightMix SabeccoV ponse Component (CERC) ementation E-gene plus EAV control) SVGRHP-G-RFQ-5B / Comput Contingency Emergency Res Request for Quota Single Stage - One E Under Imple IDA / 64810 Post Limited 4,400.00 0.00 2022-07-25 2022-10-04 2022-08-22 2022-10-21 er Equipment ponse Component (CERC) tions nvelope mentation Contingency Emergency Res Request for Quota Single Stage - One E Pending Impl SVGRHP-G-DC-5C / AC Units IDA / 64810 Post Limited 15,200.00 0.00 2022-07-29 2022-08-21 2022-10-20 ponse Component (CERC) tions nvelope ementation SVGRHP-G-RFG-5D / Office F Contingency Emergency Res Request for Quota Single Stage - One E Under Imple IDA / 64810 Post Limited 6,516.00 0.00 2022-08-05 2022-10-04 2022-08-28 2022-10-27 urniture and Equipment ponse Component (CERC) tions nvelope mentation SVGRHP-G-DC-5E / Refrigera Contingency Emergency Res Pending Impl IDA / 64810 Post Direct Selection Direct - National 3,240.00 0.00 2022-07-22 2022-08-05 2022-08-26 2022-10-25 tors ponse Component (CERC) ementation SVGRHP-G-RFQ-5A / Medical Contingency Emergency Res Request for Quota Single Stage - One E Under Imple IDA / 64810 Post Open - National 369,184.40 0.00 2022-07-29 2022-09-21 2022-12-20 Equipment ponse Component (CERC) tions nvelope mentation SVGRHP-G-FRQ-32 / Testing Contingency Emergency Res Request for Quota Single Stage - One E Pending Impl IDA / 64810 Post Limited 40,000.00 0.00 2022-09-02 2022-10-07 2022-12-06 Supplies and reagents ponse Component (CERC) tions nvelope ementation Page 2 SVGRHP-G-FRQ-31 / Laborat Contingency Emergency Res Request for Quota Single Stage - One E Pending Impl IDA / 64810 Post Limited 7,600.00 0.00 2022-09-11 2022-10-13 2022-10-19 ory Refrigerator ponse Component (CERC) tions nvelope ementation SVGRHP-G-DC- 30A / Covid-1 Contingency Emergency Res Pending Impl IDA / 64810 Post Direct Selection Direct - National 5,000.00 0.00 2022-11-25 2022-11-27 2022-12-06 2022-12-26 9 Testing Supplies ponse Component (CERC) ementation SVGRHP-G-RFQ-8 / Supply of Contingency Emergency Res Request for Quota Single Stage - One E IDA / 64810 Post Open - National 10,000.00 0.00 Canceled 2021-09-20 2021-11-15 2022-05-14 goods: Sexual assault kits. ponse Component (CERC) tions nvelope SVGRHP-G-RFQ-6 / COVID-19 Contingency Emergency Res Request for Quota Single Stage - One E Response - Decontamination IDA / 64810 Post Open - National 30,000.00 0.00 Canceled 2021-08-23 2021-10-18 2022-04-16 ponse Component (CERC) tions nvelope Equipment. SVGRHP-G-DC-25 / COVID-1 9 Response - Supporting Equi Contingency Emergency Res IDA / 64810 Post Direct Selection Direct 9,899.18 0.00 Canceled 2021-09-22 2021-09-27 2021-11-01 2022-04-30 pment, Bryden and Stokes (R ponse Component (CERC) eimbursement). SVGRHP-G-DC-16 / Procurem Institutional Capacity Buildin ent of Items for use in Project IDA / 64810 g, Project Management and Post Direct Selection Direct 4,500.00 0.00 Canceled 2021-01-11 2021-01-16 2021-02-20 2021-08-19 Office in response to Local C Coordination ovid019 spread. SVGRHP-G-RFQ-7 / COVID-19 Contingency Emergency Res Request for Quota Single Stage - One E IDA / 64810 Post Open - National 45,600.00 0.00 Canceled 2021-08-16 2021-10-11 2022-04-09 Response - Electrical Generat ponse Component (CERC) tions nvelope or SVGRHP-G-RFQ-26D / COVID Contingency Emergency Res Request for Quota Single Stage - One E IDA / 64810 Post Open - National 44,486.00 0.00 Canceled 2022-01-19 2022-03-16 2022-09-12 -19 Testing Supplies ponse Component (CERC) tions nvelope SVGRHP-G-DC-38 / Water Fil Contingency Emergency Res Under Imple IDA / 64810 Post Direct Selection Direct - National 9,350.00 0.00 2023-05-31 2023-06-27 2023-06-04 2023-06-09 2023-06-29 ter System ponse Component (CERC) mentation NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SVGRHP-NCS-RFQ-5 / Monito Institutional Capacity Buildin ring and evaluation- Allotme Request for Quota Single Stage - One E Pending Impl IDA / 64810 g, Project Management and Post Open - National 21,000.00 0.00 2020-08-05 2020-09-30 2021-03-29 nt for PIU/MOH staff training i tions nvelope ementation Coordination n fiduciary (WB etc.) SVGRHP-NCS-TR-1 / Conduct Strengthening Public Health Request for Quota Single Stage - One E Pending Impl Basic Field Epidemiology Trai IDA / 64810 Surveillance and Emergency Post Limited 5,000.00 0.00 2021-08-21 2021-10-16 2022-04-14 tions nvelope ementation ning Programme / Conduct M Management entorship FELTP SVGRHP-NCS-DC-1 / COVID- Contingency Emergency Res Pending Impl 19 Response - Consumables - IDA / 64810 Post Direct Selection Direct 20,400.00 0.00 2021-09-08 2021-09-13 2021-10-18 2022-04-16 ponse Component (CERC) ementation Inland Transportation for Con tainerized Lab. SVGRHP-NCS-DC-2 / COVID- Contingency Emergency Res Pending Impl 19 Response - Consumables - IDA / 64810 Post Direct Selection Direct 20,400.00 0.00 2021-09-08 2021-09-13 2021-10-18 2022-04-16 ponse Component (CERC) ementation Inland Transportation for Con tainerized Lab. SVGRHP-NCS-DC-4 / COVID- 19 Response - Transporting o Contingency Emergency Res Pending Impl IDA / 64810 Post Direct Selection Direct - National 485.00 0.00 2022-11-15 2022-11-20 2022-12-02 2022-12-05 f Laboratory Container to loc ponse Component (CERC) ementation ation in Canouan SVGRHP-NCS-DC-35 A / COVI Contingency Emergency Res Pending Impl D-19 Response - GBV Rental IDA / 64810 Post Direct Selection Direct - National 3,000.00 0.00 2022-11-25 2022-11-30 2022-12-07 2023-01-04 ponse Component (CERC) ementation of Venue of Community Cons ultations SVGRHP-NCS-DC-35B / COVI Contingency Emergency Res Pending Impl D-19 Response GBV - Comm IDA / 64810 Post Direct Selection Direct - National 2,000.00 0.00 2022-11-25 2022-11-30 2022-12-07 2022-12-27 ponse Component (CERC) ementation unity Consultations Provision of Refreshment SVGRHP-NCS-RFQ-4 / Activit Strengthening Public Health Request for Quota Single Stage - One E y to address weakness in co IDA / 64810 Surveillance and Emergency Post Open - National 30,000.00 0.00 Canceled 2020-12-01 2021-01-26 2021-07-25 tions nvelope mpliance with the 2005 IHR, i Management ncluding training SVGRHP-NCS-RFQ-1 / Frontli Strengthening Public Health Request for Quota Single Stage - One E ne & Basic Field Epidemiolog IDA / 64810 Surveillance and Emergency Post Limited 1,000.00 0.00 Canceled 2020-07-20 2020-09-14 2021-03-13 tions nvelope y Training Programme Management Strengthening Public Health SVGRHP-NCS-RFQ-2 / Condu Request for Quota Single Stage - One E IDA / 64810 Surveillance and Emergency Post Limited 3,000.00 0.00 Canceled 2020-07-18 2020-09-12 2021-03-11 ct Level 1 FELTP tions nvelope Management SVGRHP-NCS-RFQ-3 / Condu Strengthening Public Health Request for Quota Single Stage - One E ct Frontline Field Epidemiolo IDA / 64810 Surveillance and Emergency Post Limited 6,200.00 0.00 Canceled 2020-08-10 2020-10-05 2021-04-03 tions nvelope gy Training Program Management CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SVGRHP-C-CQS-1 / Feasibilit Improved Health Facilities a Consultant Qualifi y study of the existing Public IDA / 64810 Post Open - National 50,000.00 0.00 Canceled 2020-08-05 2020-08-26 2020-10-09 2020-11-08 2020-12-13 2021-06-11 nd Laboratory Capacity cation Selection Health Laboratory system SVGRHP-C-LCS-1 / Design an d Supervision for the constru Improved Health Facilities a Least Cost Selecti Under Implement IDA / 64810 Post Open - National 300,000.00 0.00 2020-12-15 2022-07-07 2021-01-05 2022-07-14 2021-02-18 2022-10-07 2021-03-18 2022-11-11 2021-04-17 2023-01-03 2021-05-22 2023-01-10 2021-06-26 2021-12-23 ction of the National Public H nd Laboratory Capacity on ation ealth building (to also house the EOC) SVGRHP-C-CQS-2 / TA to upd Strengthening Public Health Consultant Qualifi Pending Impleme ate and finalise communicabl IDA / 64810 Surveillance and Emergency Post Open - National 50,000.00 0.00 2020-08-05 2020-08-26 2020-10-09 2020-11-08 2020-12-13 2021-06-11 cation Selection ntation e disease preparedness & res Management ponse plans . SVGRHP-C-CQS - 3 / Establis Strengthening Public Health Consultant Qualifi hment of Isolation Facilities a IDA / 64810 Surveillance and Emergency Post Open - National 150,000.00 0.00 Signed 2020-07-31 2020-11-24 2020-08-21 2020-12-28 2020-10-04 2021-04-20 2020-11-03 2022-02-03 2020-12-08 2021-06-06 cation Selection t identified locations Management Page 3 SVGRHP-C-CQS-5 / Activity f or the Management of Biome Strengthening Public Health Consultant Qualifi dical waste - TA waste dispos IDA / 64810 Surveillance and Emergency Post Open - National 10,000.00 0.00 Canceled 2020-11-11 2020-12-02 2021-01-15 2021-02-14 2021-03-21 2021-09-17 cation Selection al system & Procurement of Management Decontaminated equipment Institutional Capacity Buildin SVGRHP-C-LCS-4 / Project Fi Least Cost Selecti Pending Impleme IDA / 64810 g, Project Management and Post Open - National 30,000.00 0.00 2021-02-05 2021-02-26 2021-04-11 2021-05-09 2021-06-08 2021-07-13 2021-08-17 2022-02-13 nancial Audit on ntation Coordination SVHRHP-C-CQS-4 / TA to Co mplete Depth Assessment of Improved Health Facilities a Consultant Qualifi Open - Internationa Pending Impleme IDA / 64810 Post 10,000.00 0.00 2021-09-06 2021-09-27 2021-11-10 2021-12-10 2022-01-14 2022-07-13 Health Facilities and Final Sc nd Laboratory Capacity cation Selection l ntation oring of Upgraded Facilities SVGRHP-C-LCS-6 / TA for the Improved Health Facilities a Least Cost Selecti Design and Supervision of Se IDA / 64810 Post Open - National 100,000.00 162,306.27 Signed 2021-08-09 2021-08-23 2021-08-30 2021-09-08 2021-10-13 2022-01-03 2021-11-10 2022-02-18 2021-12-10 2022-05-03 2022-01-14 2022-06-14 2022-02-18 2022-07-15 2022-08-17 nd Laboratory Capacity on lected Facilities to be Upgrad ed SVGRHP-C-CQS-6 / Improve t Strengthening Public Health Consultant Qualifi Open - Internationa he Information Base for Surv IDA / 64810 Surveillance and Emergency Post 50,000.00 0.00 Canceled 2021-08-16 2021-09-06 2021-10-20 2021-11-19 2021-12-24 2022-06-22 cation Selection l eillance - Training and invest Management ments in HIS SVGRHP-C-CQS-7 / Consulta Strengthening Public Health ncy to update Existing Food Consultant Qualifi Open - Internationa Pending Impleme IDA / 64810 Surveillance and Emergency Post 30,000.00 0.00 2021-09-15 2021-10-06 2021-11-19 2021-12-19 2022-01-23 2022-07-22 Safety, Port Health SOPs, Pro cation Selection l ntation Management tocols and supporting regulat ions INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Institutional Capacity Buildin SVGRHP-C-IC-1 / TA for Proc Individual Consult IDA / 64810 g, Project Management and Post Open 140,000.00 0.00 Under Review 2020-08-31 2020-11-03 2020-10-19 2020-11-09 2020-12-14 2021-06-12 urement assistant ant Selection Coordination SVGRHP-C-IC-3 / Safeguard c onsultancies and Gender Bas Contingency Emergency Res Individual Consult Pending Impleme ed Violence Service Providers IDA / 64810 Post Limited 25,000.00 0.00 2021-01-11 2021-01-16 2021-02-06 2021-03-13 2021-09-09 ponse Component (CERC) ant Selection ntation : TA for the Development of t he protocol and training Institutional Capacity Buildin SVGRHP-C-IC-4 / Contract M Individual Consult Pending Impleme IDA / 64810 g, Project Management and Post Open 21,000.00 0.00 2021-08-09 2021-09-27 2021-10-18 2021-11-22 2022-05-21 anagement Assistant ant Selection ntation Coordination SVGRHP-C-IC-9 / Consultanc Strengthening Public Health Under Implement y for the Updating National O IDA / 64810 Surveillance and Emergency Post Direct Selection Direct 42,000.00 0.00 2022-04-08 2022-04-04 2022-04-18 2022-03-24 2022-06-22 2022-12-19 ation ne Health All Hazards Manag Management ement Plan SVGRHP-IC-DC-35 / COVID-1 Contingency Emergency Res Pending Impleme 9 Response - GBV Communit IDA / 64810 Post Direct Selection Direct - National 1,550.00 0.00 2022-11-25 2022-12-02 2022-12-08 2022-12-10 ponse Component (CERC) ntation y Consultations SVGRHP-C-DC-1 / Improve th Strengthening Public Health e Information Base for Survei IDA / 64810 Surveillance and Emergency Post Direct Selection Direct 70,000.00 0.00 Canceled 2022-05-02 2022-05-12 2022-07-16 2023-01-12 llance - Training and investm Management ents in HIS Institutional Capacity Buildin SVGRHP-C-IC-5 / Environmen Individual Consult IDA / 64810 g, Project Management and Post Open 21,000.00 0.00 Canceled 2021-08-09 2021-09-29 2021-09-27 2021-10-18 2021-11-22 2022-05-21 tal & Safeguards Officer ant Selection Coordination SVGRHP-C-IC-7 / TA for the d Contingency Emergency Res Individual Consult IDA / 64810 Post Open 10,000.00 0.00 Canceled 2021-09-13 2021-11-01 2021-11-22 2021-12-27 2022-06-25 evelopment of the protocol a ponse Component (CERC) ant Selection nd training. SVGRHP-C-IC-8 / TOR - Traini Contingency Emergency Res Individual Consult IDA / 64810 Post Open 20,000.00 0.00 Canceled 2021-09-13 2021-11-01 2021-11-22 2021-12-27 2022-06-25 ng manual and training on G ponse Component (CERC) ant Selection BV SOP. Institutional Capacity Buildin SVGRHP-C-IC-2 / TA for Fina Individual Consult IDA / 64810 g, Project Management and Post Open 80,000.00 0.00 Canceled 2020-07-31 2020-11-04 2020-09-18 2020-10-09 2020-11-13 2021-05-12 ncial assistant ant Selection Coordination SVGRHP-C-IC-6 / Consultanc Strengthening Public Health y for the Development of Hea Individual Consult IDA / 64810 Surveillance and Emergency Post Open 30,000.00 0.00 Canceled 2021-09-12 2021-09-09 2021-10-31 2021-12-17 2021-11-21 2021-12-26 2022-06-24 lth Care Waste Management ant Selection Management System (HWMS) SVGRHP-C-IC-6A / Consultan Strengthening Public Health Direct - Internation Under Implement cy for Health Care Waste Ma IDA / 64810 Surveillance and Emergency Post Direct Selection 35,000.00 0.00 2023-05-17 2023-06-20 2023-05-28 2023-07-06 2024-03-04 al ation nagement System Management SVGRHP-C-IC-10 / National H Strengthening Public Health Individual Consult Pending Impleme ealth Multi-Hazard Incident M IDA / 64810 Surveillance and Emergency Post Limited 32,500.00 0.00 2023-06-12 2023-06-17 2023-07-25 2023-09-02 2024-03-30 ant Selection ntation anagement Plan Management Page 4 PROCUREMENT PLAN (Textual Part) Project information: El Salvador Growing Up Healthy Together P169677 Project Implementation agency: Ministerio de Salud Date of the Procurement Plan: January 10, 2022 Period covered by this Procurement Plan: 18 months Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. PROCUREMENT El Salvador : Growing up Healthy Together: Comprehensive Early Childhood Development in El Salvador PLAN General Information Country: El Salvador 2023-05-09 Bank’s Approval Date of the Original Procurement Plan: 2023-06-01 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P169677 GPN Date: 2022-01-21 Project Name: Growing up Healthy Together: Comprehensive Early Childhood Development in El Salvador Loan / Credit No: IBRD / 90650 Ministry of Public Works and Transport Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned SDO-003/2023 / “Reconstruc Request for Bids - ción de bordas para el Río gr Component 3: Contingent E Single Stage - One E Small Works SPD Pending Imp 2024-03-0 ande de San Miguel, municipi IBRD / 90650 mergency Response Compo Post Request for Bids Open - National 3,738,397.02 0.00 2023-05-22 2023-05-27 2023-07-08 2023-08-07 2023-09-11 nvelope (1 envelope proce lementation 9 os de Usulután y Concepción nent (CERC) ss) Batres, departamento de Usu lután” SDO-004/2023 / “Rehabilitac Request for Bids - ión de tres obras de paso sob Component 3: Contingent E Single Stage - One E Small Works SPD Pending Imp 2024-03-0 re el río Las Piñas, municipio IBRD / 90650 mergency Response Compo Post Request for Bids Open - National 1,860,000.00 0.00 2023-05-22 2023-05-27 2023-07-08 2023-08-07 2023-09-11 nvelope (1 envelope proce lementation 9 de Santa Rosa de Lima, depa nent (CERC) ss) rtamento de la Unión” SDO-005/2023 / “Reconstruc ción de calle que conduce de Request for Bids - Component 3: Contingent E Panchimalco a cantones El Di Single Stage - One E Small Works SPD Pending Imp 2024-03-0 IBRD / 90650 mergency Response Compo Post Request for Bids Open - National 930,000.00 0.00 2023-05-22 2023-05-27 2023-07-08 2023-08-07 2023-09-11 visadero y Panchimalquito, m nvelope (1 envelope proce lementation 9 nent (CERC) unicipio de Panchimalco, dep ss) artamento de San Salvador” SDO-002/2023 / “Reconstruc ción de Puente sobre río Titu Request for Bids - Component 3: Contingent E huapa, ruta SAV25N, Tramo Single Stage - One E Small Works SPD 12,090,000.0 Under Imple 2024-03-0 IBRD / 90650 mergency Response Compo Post Request for Bids Open - National 0.00 2023-05-22 2023-06-02 2023-05-27 2023-06-02 2023-07-08 2023-08-07 2023-09-11 San Ildefonso-L.D. Cabañas. nvelope (1 envelope proce 0 mentation 9 nent (CERC) Municipio de San Ildefonso, e ss) ntre departamentos de San V icente y Cabañas” GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SDP-SBCC-004 / Supervisión de la “Reconstrucción de Pue nte sobre río Tituhuapa, ruta Component 3: Contingent E Quality And Cost- SAV25N, Tramo San Ildefons IBRD / 90650 mergency Response Compo Post Open - National 910,000.00 0.00 Canceled 2023-05-22 2023-06-12 2023-07-26 2023-08-23 2023-09-22 2023-10-27 2023-12-01 2024-11-30 Based Selection o-L.D. Cabañas. Municipio de nent (CERC) San Ildefonso, entre departa mentos de San Vicente y Cab añas” SDP-SCC-005/2023 / Supervi sión de la “Reconstrucción d Component 3: Contingent E e bordas para el Río grande d Consultant Qualifi Pending Impleme IBRD / 90650 mergency Response Compo Post Open - National 261,602.98 0.00 2023-05-22 2023-06-12 2023-07-26 2023-08-25 2023-09-29 2024-03-27 e San Miguel, municipios de cation Selection ntation nent (CERC) Usulután y Concepción Batre s, departamento de Usulután ” SDP-SCC-006/2023 / Supervi sión de la “Rehabilitación de Component 3: Contingent E Consultant Qualifi Pending Impleme tres obras de paso sobre el rí IBRD / 90650 mergency Response Compo Post Open - National 140,000.00 0.00 2023-05-22 2023-06-12 2023-07-26 2023-08-25 2023-09-29 2024-03-27 cation Selection ntation o Las Piñas, municipio de San nent (CERC) ta Rosa de Lima, departamen to de la Unión” SDP-SCC-007/2023 / Supervi sión de “Reconstrucción de c Component 3: Contingent E alle que conduce de Panchim Consultant Qualifi Pending Impleme IBRD / 90650 mergency Response Compo Post Open - National 70,000.00 0.00 2023-05-22 2023-06-12 2023-07-26 2023-08-25 2023-09-29 2024-03-27 alco a cantones El Divisadero cation Selection ntation nent (CERC) y Panchimalquito, municipio de Panchimalco, departamen to de San Salvador” SDP-SCC-004/2023 / Supervi sión de la “Reconstrucción d e Puente sobre río Tituhuapa, Component 3: Contingent E Consultant Qualifi Under Implement ruta SAV25N, Tramo San Ilde IBRD / 90650 mergency Response Compo Post Open - National 910,000.00 0.00 2023-05-29 2023-06-02 2023-06-19 2023-06-02 2023-08-02 2023-09-01 2023-10-06 2024-04-03 cation Selection ation fonso-L.D. Cabañas. Municipi nent (CERC) o de San Ildefonso, entre dep artamentos de San Vicente y Cabañas” INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 1 PROCUREMENT PLAN (Textual Part) Project information: Mauritania Projet d’Appui au Development et des Innovations dans le Secteur Agricole P168847 Project Implementation agency: Unité de Coordination du projet PARIIS Date of the Procurement Plan: January 11, 2022 Period covered by this Procurement Plan: For the duration of the PPA Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. “Not Applicable” Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. Otherwise state “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables Otherwise state “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Specify for each Goods: “Not Applicable” Works: “Not Applicable” Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations is Applicable. “Not Applicable” Other Relevant Procurement Information. “Not Applicable” PROCUREMENT Mauritania : Mauritania Agriculture Development and Innovation Support Project PLAN General Information Country: Mauritania 2023-06-01 Bank’s Approval Date of the Original Procurement Plan: 2023-06-01 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P168847 GPN Date: 2023-06-01 Project Name: Mauritania Agriculture Development and Innovation Support Project Loan / Credit No: IDA / 72250 Mauritania Agriculture Development and Innovation Support Project Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Request for Bids - MR-PADISAM-362459-CW-RF Community-Driven Territoria Single Stage - One E Small Works SPD Pending Imp 2024-06-1 B / Réhabilitation des locaux IDA / 72250 l Development and Preserva Post Request for Bids Open - National 285,714.00 0.00 2023-08-31 2023-09-05 2023-10-17 2023-11-16 2023-12-21 nvelope (1 envelope proce lementation 8 de l’ancienne Direction de l’A tion ss) griculture GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MR-PADISAM-362457-GO-RF Community-Driven Territoria B / Fourniture de 30 motos p Single Stage - One E Pending Impl IDA / 72250 l Development and Preserva Post Request for Bids Open - National 83,000.00 0.00 2023-07-03 2023-07-08 2023-08-19 2023-09-18 2023-10-23 2024-04-20 our les délégations régionale nvelope ementation tion s du Brakna, du Gorgol et de l’Assaba MR-PADISAM-362471-GO-RF Project Management and Mo Request for Quota Single Stage - One E Pending Impl Q / Fourniture et installation IDA / 72250 Post Limited 10,000.00 0.00 2023-07-01 2023-08-26 2024-02-22 nitoring & Evaluation tions nvelope ementation d'un système de visio-confér ence pour l'UGP MR-PADISAM-362473-GO-RF Project Management and Mo Request for Quota Single Stage - One E Pending Impl Q / Fournitures de consomma IDA / 72250 Post Limited 25,000.00 0.00 2023-06-04 2023-07-30 2024-01-26 nitoring & Evaluation tions nvelope ementation bles informatiques pour l'UG P MR-PADISAM-362474-GO-RF Project Management and Mo Request for Quota Single Stage - One E Pending Impl IDA / 72250 Post Limited 22,857.00 0.00 2023-06-06 2023-08-01 2024-01-28 Q / Acquisition Logiciel Tomp nitoring & Evaluation tions nvelope ementation ro MR-PADISAM-362482-GO-RF Project Management and Mo Single Stage - One E Pending Impl B / Acquisition et installation IDA / 72250 Post Request for Bids Open - National 22,200.00 0.00 2023-08-30 2023-09-04 2023-10-16 2023-11-15 2023-12-20 2024-06-17 nitoring & Evaluation nvelope ementation d’un groupe électrogène po ur l'UGP MR-PADISAM-362483-GO-RF Project Management and Mo Single Stage - One E Pending Impl B / Acquisition de 2 véhicules IDA / 72250 Post Request for Bids Limited 45,000.00 0.00 2023-07-31 2023-08-05 2023-09-16 2023-10-16 2023-11-20 2024-05-18 nitoring & Evaluation nvelope ementation légers pour l'UGP MR-PADISAM-362651-GO-RF Project Management and Mo Request for Quota Single Stage - One E Pending Impl Q / Fourniture de consomma IDA / 72250 Post Limited 25,000.00 0.00 2023-06-20 2023-08-15 2024-02-11 nitoring & Evaluation tions nvelope ementation ble de bureaux MR-PADISAM-362654-GO-RF Project Management and Mo Request for Quota Single Stage - One E Pending Impl Q / Fourniture d'ordinateurs IDA / 72250 Post Limited 16,000.00 0.00 2023-07-05 2023-08-30 2024-02-26 nitoring & Evaluation tions nvelope ementation portables pour l'UGP NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MR-PADISAM-362453-CS-QC BS / Recrutement d'un cabin Community-Driven Territoria Quality And Cost- Pending Impleme et pour élaborer 6 plans de D IDA / 72250 l Development and Preserva Post Open - National 86,171.00 0.00 2023-06-15 2023-07-06 2023-08-19 2023-09-16 2023-10-16 2023-11-20 2023-12-25 2024-12-24 Based Selection ntation éveloppement et de Gestion i tion ntegré du paysage au niveau des SBV retenus MR-PADISAM-362462-CS-QC BS / Recrutement d’une firm Inclusive Commercial Agricul Quality And Cost- Open - Internationa Under Implement IDA / 72250 Post 500,000.00 0.00 2023-08-31 2023-06-15 2023-09-21 2023-11-04 2023-12-02 2024-01-01 2024-02-05 2024-03-11 2025-03-11 e/société spécialisée pour as ture Based Selection l ation sister le projet dans la mise e n œuvre des ZOCA INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MR-PADISAM-362455-CS-IND V / Recrutement d’un consult Community-Driven Territoria ant pour la préparation de la Individual Consult Pending Impleme IDA / 72250 l Development and Preserva Post Limited 19,389.00 0.00 2023-05-30 2023-06-04 2023-06-25 2023-07-30 2024-01-26 revue de la stratégie national ant Selection ntation tion e du Secteur Agricole et l’éla boration d’un plan national d e relance du secteur agricole MR-PADISAM-362460-CS-IND V / Recrutement d'un consult ant pour l’Élaboration, valida Inclusive Commercial Agricul Individual Consult Pending Impleme tion et vulgarisation d'un gui IDA / 72250 Post Limited 26,509.00 0.00 2023-07-30 2023-08-04 2023-08-25 2023-09-29 2024-03-27 ture ant Selection ntation de de procédure relatif aux p rogrammes de mise en valeu r optimale du patrimoine fon cier national agricole Page 1 MR-PADISAM-362465-CS-IND V / Recrutement d'un consult Project Management and Mo Individual Consult Under Implement IDA / 72250 Post Limited 11,000.00 0.00 2023-05-31 2023-06-15 2023-06-05 2023-06-26 2023-07-31 2024-01-27 ant pour la rédaction d'un m nitoring & Evaluation ant Selection ation anuel de suivi et évaluation MR-PADISAM-362470-CS-IND Project Management and Mo Individual Consult Pending Impleme V / Conception et mise en pla IDA / 72250 Post Limited 7,143.00 0.00 2023-07-31 2023-08-05 2023-08-26 2023-09-30 2024-03-28 nitoring & Evaluation ant Selection ntation ce d'un site Web du Projet MR-PADISAM-362475-CS-IND Project Management and Mo Individual Consult Pending Impleme V / Conception d'un système IDA / 72250 Post Limited 21,429.00 0.00 2023-07-31 2023-08-05 2023-08-26 2023-09-30 2024-03-28 nitoring & Evaluation ant Selection ntation informatisé de Suivi évaluati on MR-PADISAM-362477-CS-IND Project Management and Mo Individual Consult Pending Impleme V / Conception d'un système IDA / 72250 Post Limited 21,429.00 0.00 2023-08-31 2023-09-05 2023-09-26 2023-10-31 2024-04-28 nitoring & Evaluation ant Selection ntation informatisé de Suivi des cont rats MR-PADISAM-362657-CS-IND Project Management and Mo Individual Consult Pending Impleme V / Recrutement d'un spéciali IDA / 72250 Post Open - National 25,000.00 0.00 2023-06-12 2023-07-31 2023-08-21 2023-09-25 2024-03-23 nitoring & Evaluation ant Selection ntation ste genre pour l'UGP MR-PADISAM-362656-CS-IND Project Management and Mo Individual Consult Pending Impleme V / Recrutement d'un spéciali IDA / 72250 Post Open - National 25,000.00 0.00 2023-06-15 2023-08-03 2023-08-24 2023-09-28 2024-03-26 nitoring & Evaluation ant Selection ntation ste communication pour l'UG P MR-PADISAM-362655-CS-IND Project Management and Mo Individual Consult Pending Impleme V / Recrutement d'un compta IDA / 72250 Post Open - National 22,857.00 0.00 2023-06-20 2023-08-08 2023-08-29 2023-10-03 2024-03-31 nitoring & Evaluation ant Selection ntation ble pour l'UGP MR-PADISAM-362658-CS-IND Project Management and Mo Individual Consult Under Implement V / Recrutement d'un expert IDA / 72250 Post Open - National 25,000.00 0.00 2023-06-13 2023-06-15 2023-08-01 2023-08-22 2023-09-26 2024-03-24 nitoring & Evaluation ant Selection ation subvention pour l'UGP Page 2 Informations Seuils de revue préalable : Décisions soumises à la revue préalable par la Banque tel que visé dans l’annexe 1 des Directives pour la passation de marchés. Seuils de revue a priori (Milliers de USD) Seuil de revue Seuil de préalable revue pour Type de contrat préalable l’entente (Millier de directe USD) (Millier de USD) Travaux (y compris, des contrats clé-en-main, des fournitures et 10 000 3 000 installations de sites et d’équipements, et PPP) Fournitures, technologies de l’information et services autres 2 000 800 que des services de consultants Consultants (Entreprises) 1 000 500 Consultants (Individuels) 300 150 Seuils pour les modalités et méthodes de passation de marchés (Milliers USD) Ouvert Ouvert Demande International National < de Type de contrat ≧ Cotation s =< Travaux (y compris, des contrats clé-en-main, des fournitures et 10 000 10 000 300 installations de sites et d’équipements, et PPP) Fournitures, technologies de l’information et services autres que 3 000 3 000 200 des services de consultants Consultants : entreprises (SQC) 300 (limité national et international) Préqualification. N/A. Procédures proposées pour les composantes CDD (selon le paragraphe 3.17 des Directives). N/A. Référence au Manuel d’opérations du projet/ Manuel de passation de marchés : Le Manuel d’Opérations du Projet (MOP) sera finalisé et approuvé dans les semaines à venir. Tout autre arrangement spécial de passation de marchés, y compris la passation de marchés anticipée et le financement rétroactif, si applicable. N/A PROCUREMENT Morocco : Morocco - Community-Based Rural Roads Maintenance PLAN General Information Country: Morocco 2019-12-19 Bank’s Approval Date of the Original Procurement Plan: 2023-06-01 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P165411 GPN Date: Project Name: Morocco - Community-Based Rural Roads Maintenance Loan / Credit No: / , TF / B0252 Ministry of Logistics Equipment for Transport and Water, Directions of Roads Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned MA-METLE/DR-229074-CW-R FQ / S/P-DD N°01- Entretien c Request for Quota Single Stage - One E 2021-08-2 TF / B0252 Component 1 : Subprojects Post Limited 40,000.00 52,082.26 Signed 2021-05-03 2021-05-10 2021-06-28 2021-05-29 ommunautaire de la RP1900 tions nvelope 7 du PK 121 au PK 141 MA-METLE/DR-242699-CW-R FQ / DD N°02- TRAVAUX D’E Request for Quota NTRETIEN COMMUNAUTAIRE Request for Quota Single Stage - One E tions - Small Work 2021-10-3 TF / B0252 Component 1 : Subprojects Post Limited 51,000.00 43,678.89 Signed 2021-07-14 2021-09-14 2021-09-01 2021-10-16 DE LA RP1900 ENTRE LE PK 1 tions nvelope s (Emergency) SP 1 04+800 ET LE PK 119+600. P D -Competitive ROVINCE DE CHTOUKA AIT B AHA MA-METLE/DR-242701-CW-R FQ / DD N°03 - TRAVAUX D’E Request for Quota NTRETIEN COMMUNAUTAIRE Request for Quota Single Stage - One E tions - Small Work 2021-11-0 TF / B0252 Component 1 : Subprojects Post Limited 30,000.00 20,470.59 Signed 2021-07-21 2021-09-02 2021-09-08 2021-12-09 DE LA RP1900 ENTRE LE PK 8 tions nvelope s (Emergency) SP 7 2+100 ET LE PK 104+600. P D -Competitive ROVINCE DE CHTOUKA AIT B AHA MA-METLE/DR-242705-CW-R FQ / DD N°04 - TRAVAUX D’E Request for Quota NTRETIEN COMMUNAUTAIRE Request for Quota Single Stage - One E tions - Small Work 2021-11-1 TF / B0252 Component 1 : Subprojects Post Limited 45,000.00 41,848.94 Signed 2021-07-28 2021-09-06 2021-09-15 2021-12-16 DE LA RP1900 ENTRE LE PK 7 tions nvelope s (Emergency) SP 4 0+000 ET LE PK 81+900. PR D -Competitive OVINCE DE CHTOUKA AIT BA HA DPETLE-AGA01 / Travaux d’e Request for Quota ntretien communautaire de l Request for Quota Single Stage - One E tions - Small Work 2022-02-1 TF / B0252 Component 1 : Subprojects Post Limited 41,000.00 38,208.48 Signed 2021-10-28 2021-11-03 2021-12-16 2021-12-29 a RP1002 entre le PK 00+00 tions nvelope s (Emergency) SP 4 0 et le PK 24+000. Préfectur D -Competitive e d’Agadir Ida Outanane DPETLE-AGA02 / TRAVAUX D Request for Quota E TRAITEMENT DE L’ENVIRON Request for Quota Single Stage - One E tions - Small Work 2022-02-1 NEMENT SUR LA RP1001 ENT TF / B0252 Component 1 : Subprojects Post Limited 49,500.00 46,878.88 Signed 2021-11-02 2021-11-04 2021-12-21 2021-12-29 tions nvelope s (Emergency) SP 9 RE LE PK0+000 ET LE PK 30+ D -Competitive 000. PRÉFECTURE DE D’AGA DIR IDA-OUTANANE DPETLE-AGA03 / TRAVAUX D Request for Quota E TRAITEMENT DE L’ENVIRON Request for Quota Single Stage - One E tions - Small Work 2022-02-2 NEMENT SUR LA RP1000A EN TF / B0252 Component 1 : Subprojects Post Limited 33,000.00 31,573.52 Signed 2021-11-05 2021-11-04 2021-12-24 2021-12-31 tions nvelope s (Emergency) SP 2 TRE LE PK 28+000 ET LE PK D -Competitive 50+600 PRÉFECTURE D’AGA DIR IDA-OUTANANE DPETLE-AGA04 / TRAVAUX D Request for Quota E TRAITEMENT DE L’ENVIRON Request for Quota Single Stage - One E tions - Small Work 2022-02-2 NEMENT SUR LA RP1004 ENT TF / B0252 Component 1 : Subprojects Post Limited 42,500.00 39,574.08 Signed 2021-11-05 2021-11-04 2021-12-24 2021-12-29 tions nvelope s (Emergency) SP 2 RE LE PK 46+000 ET LE PK 7 D -Competitive 0+000. PRÉFECTURE D’AGAD IR IDA-OUTANANE. DPETLE-TAR01 / TRAVAUX D Request for Quota ’ENTRETIEN COMMUNAUTAIR Request for Quota Single Stage - One E tions - Small Work 2022-02-2 E DE LA RR1727 ENTRE LE P TF / B0252 Component 1 : Subprojects Post Limited 44,500.00 40,674.80 Signed 2021-11-05 2021-12-02 2021-12-24 2022-06-11 tions nvelope s (Emergency) SP 2 K 0+000 ET LE PK 20+000 P D -Competitive ROVINCE DE TAROUDANT DPETLE-TAR02 / TRAVAUX D Request for Quota ’ENTRETIEN COMMUNAUTAIR Request for Quota Single Stage - One E tions - Small Work 2022-02-2 E DE LA RR1727 ENTRE LE P TF / B0252 Component 1 : Subprojects Post Limited 37,500.00 37,653.43 Signed 2021-11-05 2021-11-10 2021-12-24 2022-06-11 tions nvelope s (Emergency) SP 2 K 20+000 ET LE PK 50+000 D -Competitive PROVINCE DE TAROUDANT DPETLE-CHT05 / TRAVAUX D Request for Quota ’ENTRETIEN COMMUNAUTAIR Request for Quota Single Stage - One E tions - Small Work 2022-02-2 E DE LA RP1013 ENTRE LE PK TF / B0252 Component 1 : Subprojects Post Limited 55,000.00 48,426.01 Signed 2021-11-08 2021-11-09 2021-12-27 2022-04-02 tions nvelope s (Emergency) SP 5 0+000 ET LE PK 24+000. PR D -Competitive OVINCE DE CHTOUKA AIT BA HA DPETLE-TAR03 / TRAVAUX D Request for Quota ’ENTRETIEN COMMUNAUTAIR Request for Quota Single Stage - One E tions - Small Work Under Imple 2022-02-2 TF / B0252 Component 1 : Subprojects Post Limited 44,500.00 0.00 2021-11-08 2021-11-09 2021-12-27 E DE LA RP 2040 ENTRE PK8 tions nvelope s (Emergency) SP mentation 5 +000 ET PK30+000, PROVIN D -Competitive CE DE TAROUDANT DPETLE-TAR05 / TRAVAUX D Request for Quota ’ENTRETIEN COMMUNAUTAIR Request for Quota Single Stage - One E tions - Small Work 2022-02-2 E DE LA RP1702 ENTRE LE PK TF / B0252 Component 1 : Subprojects Post Limited 34,000.00 35,150.19 Signed 2021-11-08 2021-11-09 2021-12-27 2022-06-21 tions nvelope s (Emergency) SP 5 20+000 ET LE PK 35+000, P D -Competitive ROVINCE DE TAROUDANT DPETLE-TAR04 / TRAVAUX D Request for Quota ’ENTRETIEN COMMUNAUTAIR Request for Quota Single Stage - One E tions - Small Work 2022-02-2 E DE LA RP1731 ENTRE LE PK TF / B0252 Component 1 : Subprojects Post Limited 34,000.00 30,312.99 Signed 2021-11-10 2021-11-15 2021-12-29 2022-06-14 tions nvelope s (Emergency) SP 7 0+000 ET LE PK 15+400, PR D -Competitive OVINCE DE TAROUDANT DPETLE-TIZ01 / TRAVAUX D’ Request for Quota ENTRETIEN DE L’ENVIRONNE Request for Quota Single Stage - One E tions - Small Work 2022-03-0 MENT SUR LA RP1921 ENTRE TF / B0252 Component 1 : Subprojects Post Limited 31,000.00 0.00 Signed 2021-11-12 2022-03-16 2021-12-31 tions nvelope s (Emergency) SP 1 LE PK 0+000 ET LE PK 25+80 D -Competitive 0. PROVINCE DE TIZNIT DPETLE-TAT01 / Travaux d’e Request for Quota ntretien de la route N° RR 11 Request for Quota Single Stage - One E tions - Small Work Under Imple 2022-03-0 9 (ex RP 1743) reliant la RN1 TF / B0252 Component 1 : Subprojects Post Limited 45,000.00 0.00 2021-11-15 2021-11-30 2022-01-03 tions nvelope s (Emergency) SP mentation 4 7 à la RN10, du PK 32+000 a D -Competitive u PK 52+000, Province de TA TA Page 1 DPETLE-TAT02 / Travaux d’e Request for Quota ntretien de la route N° RP180 Request for Quota Single Stage - One E tions - Small Work Under Imple 2022-03-0 TF / B0252 Component 1 : Subprojects Post Limited 48,000.00 0.00 2021-11-15 2021-11-25 2022-01-03 3 reliant Akka à Imtek, du PK tions nvelope s (Emergency) SP mentation 4 00+000 au PK 34+500, Provi D -Competitive nce de TATA DPETLE-TAT03 / Travaux d’e ntretien de la route N° RR11 Request for Quota 6 (Ex RP 1807 & 1805) relian Request for Quota Single Stage - One E tions - Small Work Under Imple 2022-03-0 TF / B0252 Component 1 : Subprojects Post Limited 47,000.00 0.00 2021-11-15 2021-11-25 2022-01-03 t Tagmout et Oum El Guerda tions nvelope s (Emergency) SP mentation 4 ne à Tata, du PK 67+000 au D -Competitive PK 95+000, Province de TAT A DPETLE-TAT04 / Travaux d’e ntretien de la route N° RR11 Request for Quota 6 (Ex RP 1807 & 1805) relian Request for Quota Single Stage - One E tions - Small Work Under Imple 2022-03-0 TF / B0252 Component 1 : Subprojects Post Limited 49,000.00 0.00 2021-11-15 2021-11-25 2022-01-03 t Tagmout et Oum El Guerda tions nvelope s (Emergency) SP mentation 4 ne à Tata, du PK 47+400 au D -Competitive PK 65+800, Province de TAT A DPETLE-TAT05 / Travaux d’e Request for Quota ntretien de la route N° RP180 Request for Quota Single Stage - One E tions - Small Work Under Imple 2022-03-0 8 reliant la route R119 à la c TF / B0252 Component 1 : Subprojects Post Limited 45,000.00 0.00 2021-11-15 2023-02-20 2022-01-03 tions nvelope s (Emergency) SP mentation 4 ommune Ibn Yacoub, du PK 0 D -Competitive 0+000 au PK 16+000, Provin ce de TATA DPETLE-TIZ02 / TRAVAUX D’ Request for Quota ENTRETIEN DE LA RP1903 EN Request for Quota Single Stage - One E tions - Small Work 2022-03-0 TF / B0252 Component 1 : Subprojects Post Limited 45,000.00 0.00 Signed 2021-11-12 2022-04-19 2021-12-31 TRE LE PK 0+000 ET LE PK 3 tions nvelope s (Emergency) SP 1 4+000. PROVINCE DE TIZNIT D -Competitive DPETLE-TIZ03 / TRAVAUX DE Request for Quota TRAITEMENT DE L’ENVIRONN Request for Quota Single Stage - One E tions - Small Work 2022-03-1 EMENT SUR LA RP1923 ENTR TF / B0252 Component 1 : Subprojects Post Limited 48,000.00 0.00 Signed 2021-11-22 2022-02-04 2022-01-10 tions nvelope s (Emergency) SP 1 E LE PK 12+000 ET LE PK 32 D -Competitive +000. PROVINCE DE TIZNIT DPETLE-TAR06 / TRAVAUX D Request for Quota E TRAIREMENT DE L’ENVIRO Request for Quota Single Stage - One E tions - Small Work 2022-03-1 NNEMENT SUR LA RP1702 EN TF / B0252 Component 1 : Subprojects Post Limited 34,000.00 24,142.70 Signed 2021-11-25 2021-11-26 2022-01-13 2022-06-14 tions nvelope s (Emergency) SP 4 TRE LE PK 35+000 ET LE PK D -Competitive 50+000, PROVINCE DE TARO UDANNT DPETLE-TAR07 / TRAVAUX D Request for Quota ’ENTRETIEN DE LA RP1733 E Request for Quota Single Stage - One E tions - Small Work 2022-03-2 TF / B0252 Component 1 : Subprojects Post Limited 45,000.00 37,823.89 Signed 2021-12-06 2021-12-02 2022-01-24 2022-06-14 NTRE LE PK 66+100 ET LE 88 tions nvelope s (Emergency) SP 5 +300. PROVINCE DE TAROU D -Competitive DANNT DPETLE-CHT06 / TRAVAUX D Request for Quota ’ENTRETIEN COMMUNAUTAIR Request for Quota Single Stage - One E tions - Small Work 2022-04-0 E DE LA RP1011 ENTRE LE PK TF / B0252 Component 1 : Subprojects Post Limited 52,000.00 0.00 Signed 2021-12-17 2022-04-19 2022-02-04 tions nvelope s (Emergency) SP 5 68+900 ET LE PK 98+900. P D -Competitive ROVINCE DE CHTOUKA AIT B AHA DPETLE-CHT07 / TRAVAUX D Request for Quota ’ENTRETIEN COMMUNAUTAIR Request for Quota Single Stage - One E tions - Small Work 2022-04-0 E DE LA RR115(EX RP1007) E TF / B0252 Component 1 : Subprojects Post Limited 23,000.00 0.00 Signed 2021-12-17 2022-04-19 2022-02-04 tions nvelope s (Emergency) SP 5 NTRE LE PK 33+000 ETLE PK D -Competitive 64+500. PROVINCE DE CHT OUKA AIT BAHA DPETLE-TAR08 / TRAVAUX D Request for Quota ’ENTRETIEN DE LA RP1735 E Request for Quota Single Stage - One E tions - Small Work 2022-04-2 TF / B0252 Component 1 : Subprojects Post Limited 46,000.00 37,090.08 Signed 2022-01-03 2022-01-18 2022-02-21 2022-06-14 NTRE LE PK 00+000 ET LE PK tions nvelope s (Emergency) SP 2 20+000. PROVINCE DE TARO D -Competitive UDANT DPETLE-TAR09 / TRAVAUX D Request for Quota ’ENTRETIEN DE LA RP1737 E Request for Quota Single Stage - One E tions - Small Work 2022-04-2 TF / B0252 Component 1 : Subprojects Post Limited 45,000.00 33,839.45 Signed 2022-01-03 2022-01-18 2022-02-21 2022-06-18 NTRE LE PK 0+000 ET LE PK tions nvelope s (Emergency) SP 2 23+000. PROVINCE DE TARO D -Competitive UDANT DPETLE-TAR10 / TRAVAUX D Request for Quota ’ENTRETIEN DE LA RP1510 E Request for Quota Single Stage - One E tions - Small Work 2022-05-1 TF / B0252 Component 1 : Subprojects Post Limited 36,000.00 24,633.43 Signed 2022-01-24 2022-01-18 2022-03-14 2022-06-18 NTRE LE PK 36+600 ET LE PK tions nvelope s (Emergency) SP 3 52+600. PROVINCE DE TARO D -Competitive UDANT DPETLE-TAR11 / TRAVAUX D Request for Quota ’ENTRETIEN DE LA RP1735 E Request for Quota Single Stage - One E tions - Small Work 2022-05-1 TF / B0252 Component 1 : Subprojects Post Limited 32,000.00 23,520.40 Signed 2022-01-24 2022-01-18 2022-03-14 2022-06-18 NTRE LE PK 20+000 ET LE PK tions nvelope s (Emergency) SP 3 37+000. PROVINCE DE TARO D -Competitive UDANT. DPETLE-TAR12 / TRAVAUX D Request for Quota ’ENTRETIEN DE LA RP1737 E Request for Quota Single Stage - One E tions - Small Work 2022-05-1 TF / B0252 Component 1 : Subprojects Post Limited 44,000.00 33,190.20 Signed 2022-01-24 2022-01-18 2022-03-14 2022-06-18 NTRE LE PK 24+000 ET LE PK tions nvelope s (Emergency) SP 3 50+000. PROVINCE DE TARO D -Competitive UDANT DPETLE-TAR13 / TRAVAUX D Request for Quota ’ENTRETIEN DE LA RP1718 E Request for Quota Single Stage - One E tions - Small Work 2022-06-0 TF / B0252 Component 1 : Subprojects Post Limited 45,000.00 30,570.80 Signed 2022-02-17 2022-02-17 2022-04-07 2022-07-14 NTRE LE PK 52+000 ET LE PK tions nvelope s (Emergency) SP 6 86+000. PROVINCE DE TARO D -Competitive UDANNT DPETLE-TAR14 / TRAVAUX D Request for Quota ’ENTRETIEN DE LA RP1729 E Request for Quota Single Stage - One E tions - Small Work 2022-06-0 TF / B0252 Component 1 : Subprojects Post Limited 40,000.00 26,296.88 Signed 2022-02-17 2022-02-17 2022-04-07 2022-06-18 NTRE LE PK 0+000 ET LE PK tions nvelope s (Emergency) SP 6 36+000. PROVINCE DE TARO D -Competitive UDANNT DPETLE-AGA05 / TRAVAUX D Request for Quota E TRAITEMENT DE L’ENVIRON Request for Quota Single Stage - One E tions - Small Work 2022-06-0 NEMENT SUR LA RP1001 ENT TF / B0252 Component 1 : Subprojects Post Limited 42,000.00 0.00 Signed 2022-02-17 2022-06-01 2022-04-07 tions nvelope s (Emergency) SP 6 RE LE PK68+000 ET LE PK 85 D -Competitive +000. PRÉFECTURE DE D’AG ADIR IDA-OUTANANE DPETLE-AGA06 / TRAVAUX D Request for Quota E TRAITEMENT DE L’ENVIRON Request for Quota Single Stage - One E tions - Small Work 2022-08-2 NEMENT SUR LA RP1002 ENT TF / B0252 Component 1 : Subprojects Post Limited 37,000.00 0.00 Signed 2022-05-09 2022-06-01 2022-06-27 tions nvelope s (Emergency) SP 6 RE LE PK25+000 ET LE PK 59 D -Competitive +000. PRÉFECTURE DE D’AG ADIR IDA-OUTANANE. DPETLE-TAR15 / TRAVAUX D Request for Quota ’ENTRETIEN DE LA RP1723 E Request for Quota Single Stage - One E tions - Small Work 2022-08-2 TF / B0252 Component 1 : Subprojects Post Limited 35,000.00 0.00 Signed 2022-05-09 2022-05-23 2022-06-27 NTRE LE PK 0+000 ET LE PK tions nvelope s (Emergency) SP 6 40+000. PROVINCE DE TARO D -Competitive UDANNT Page 2 DPETLE-AGA07 / TRAVAUX D Request for Quota ’ENTRETIEN COMMUNAUTAIR Request for Quota Single Stage - One E tions - Small Work Pending Imp 2023-09-1 E DE LA RP1000A ENTRE LE P TF / B0252 Component 1 : Subprojects Post Limited 40,000.00 0.00 2023-06-02 2023-07-21 tions nvelope s (Emergency) SP lementation 9 K28+000 ET LE PK 50+600. D -Competitive PRÉFECTURE DE D’AGADIR I DA-OUTANANE DPETLE-CHT08 / TRAVAUX D Request for Quota ’ENTRETIEN COMMUNAUTAIR Request for Quota Single Stage - One E tions - Small Work Pending Imp 2023-09-2 E DE LA RP1009 ENTRE LE PK TF / B0252 Component 1 : Subprojects Post Limited 38,000.00 0.00 2023-06-09 2023-07-28 tions nvelope s (Emergency) SP lementation 6 51+600 ET LE PK 62+500, P D -Competitive ROVINCE DE CHTOUKA AIT B AHA GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MA-METLE/DR-123200-NC-R Component 3: Project mana FQ / Services de planification gement and administration ( Request for Quota Single Stage - One E / Post Open - National 10,000.00 0.00 Canceled 2019-11-16 2020-01-11 2020-07-09 d'événements pour l'organis PMA), monitoring and evalua tions nvelope ation d'un atelier de lanceme tion (M&E), and knowledge d nt de projet. issemination MA-METLE/DR-123207-CS-C Component 2: Capacity buil Request for Quota Single Stage - One E QS / Préparation et conduite TF / B0252 Post Limited 100,000.00 101,170.71 Signed 2021-04-26 2021-05-05 2021-06-21 2021-10-06 2021-08-30 ding tions nvelope de formations pour renforce ment de capacités CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MA-METLE/DR-123205-CS-FB S / Services des consultants pour la préparation et la con Component 2: Capacity buil Consultant Qualifi / Post Open - National 50,000.00 0.00 Canceled 2019-10-10 2019-10-31 2019-12-14 2020-01-13 2020-02-17 2020-08-15 duite de formation sur des as ding cation Selection pects techniques pour le pers onnel des contreparties et le s bénéficiaires. MA-METLE/DR-152226-CS-C Component 3: Project mana QS / Assistance technique po gement and administration ( Consultant Qualifi TF / B0252 Post Open - National 200,000.00 223,422.38 Signed 2020-01-30 2020-01-30 2020-04-22 2020-07-01 2020-06-12 2020-07-31 2020-06-12 2020-11-09 2020-11-14 2023-02-02 ur la gestion, l'administration PMA), monitoring and evalua cation Selection et le suivi du projet tion (M&E), and knowledge d issemination MA-METLE/DR-123204-CS-FB S / Services des consultants Least Cost Selecti TF / B0252 Component 1 : Subprojects Post Open - National 150,000.00 134,099.03 Signed 2021-07-19 2021-08-12 2021-08-09 2021-09-22 2021-10-28 2021-10-20 2021-11-12 2021-11-19 2021-11-15 2021-12-24 2021-11-26 2022-01-28 2022-01-01 2022-07-27 pour les inspections techniqu on es des sous-projets MA-METLE/DR-286948-CS-Q Component 3: Project mana CBS / RÉALISATION D’UNE ÉT gement and administration ( UDE D’ÉVALUATION DE L’IMP Quality And Cost- TF / B0252 PMA), monitoring and evalua Post Open - National 70,000.00 0.00 Signed 2022-03-28 2022-03-28 2022-04-04 2022-04-13 2022-05-16 2022-05-05 2022-06-16 2022-05-09 2022-06-24 2022-05-23 2022-07-27 2022-06-27 2023-12-27 ACT SOCIO-ÉCONOMIQUE DU Based Selection tion (M&E), and knowledge d PROJET D’ENTRETIEN COMM issemination UNAUTAIRE DE ROUTES RUR ALES (ECRR) INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 3 PROCUREMENT PLAN Project information: Tanzania, Digital Tanzania Project P160766 Project Implementation agency: Ministry of Communication and Information Technology (MCIT) Date of the Procurement Plan: Sep 28, 2021 Period covered by this Procurement Plan: Oct 2021- Oct 2022 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international and national competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: When approaching the national market, as agreed in the Procurement Plan, the country’s own procurement procedures may be used. These procurement procedures shall be consistent with the Bank’s Core Procurement Principles and ensure that the Bank’s Anti- Corruption Guidelines and Sanctions Framework and contractual remedies set out in its Legal Agreement apply. For national open competitive procurement the requirements as per National Procurement Procedure (5.4) of Bank’s Procurement Regulations will apply Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Not Applicable Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations –Not Applicable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Not applicable Other Relevant Procurement Information. None PROCUREMENT Tanzania : Digital Tanzania Project PLAN General Information Country: Tanzania 2021-10-04 Bank’s Approval Date of the Original Procurement Plan: 2023-06-02 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P160766 GPN Date: 2021-08-17 Project Name: Digital Tanzania Project Loan / Credit No: IDA / 68930 Ministry of Communication and Information Technology Executing Agency(ies): WORKS Activity Reference No. / Procureme Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH Ri Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method nt Docume ount (US$ and Recommendation Signed Contract o. h cess (Y/N) sk atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion nt Type ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual National Proc TZ-MCIT-254774-CW-RFB / R urement Doc 3. Digital Platforms and Serv Single Stage - One E Under Imple 2023-02-2 ehabilitation of Huduma Pam IDA / 68930 Post Request for Bids Open - National ument - 1 En 0.00 2022-05-08 2022-01-06 2022-05-13 2022-06-24 2022-07-24 2022-08-28 ices nvelope mentation 4 oja Building -Phase I velope proce ss (Non Bank -SPD) National Proc TZ-MCIT-254784-CW-RFB / R urement Doc Single Stage - One E Pending Imp 2024-02-2 ehabilitation of e-commerce i IDA / 68930 1. Digital Ecosystem Post Request for Bids Open - National ument - 1 En 0.00 2023-06-30 2023-07-05 2023-08-16 2023-09-15 2023-10-20 nvelope lementation 0 nnovation Center at TPC-HQ velope proce ss (Non Bank -SPD) National Proc urement Doc TZ-MCIT-254771-CW-RFB / R Single Stage - One E Pending Imp 2024-06-1 IDA / 68930 1. Digital Ecosystem Post Request for Bids Open - National ument - 1 En 0.00 2023-08-25 2023-08-30 2023-10-11 2023-11-10 2023-12-15 ehabilitation of Refurb Labs nvelope lementation 2 velope proce ss (Non Bank -SPD) National Proc TZ-MCIT-254780-CW-RFB / E urement Doc Single Stage - One E Under Imple 2024-01-0 xpansion of Government Net IDA / 68930 2. Digital Connectivity Post Request for Bids Open - National ument - 1 En 0.00 2023-03-15 2023-03-06 2023-03-20 2023-05-01 2023-05-31 2023-07-05 nvelope mentation 1 work- Phase I velope proce ss (Non Bank -SPD) National Proc TZ-MCIT-254785-CW-RFB / R urement Doc Single Stage - One E Pending Imp 2024-05-2 ehabilitation of Zonal Innovat IDA / 68930 1. Digital Ecosystem Post Request for Bids Open - National ument - 1 En 0.00 2023-08-10 2023-08-15 2023-09-26 2023-10-26 2023-11-30 nvelope lementation 8 ion Centers velope proce ss (Non Bank -SPD) Request for B TZ-MCIT-289679-CW-RFB / P ids - Small W Single Stage - One E Pending Imp 2024-02-0 roposed Extension of Office B IDA / 68930 4. Project Management Post Request for Bids Open - National orks SPD (1 e 0.00 2023-04-30 2023-05-05 2023-06-04 2023-07-04 2023-08-08 nvelope lementation 4 uildings of Digital Tanzania P nvelope proc roject ess) National Proc TZ-MCIT-254764-CW-RFB / P urement Doc roposed Design and Build of Single Stage - One E 2023-05-3 IDA / 68930 1. Digital Ecosystem Post Request for Bids Open - National ument - 1 En 0.00 Canceled 2022-11-08 2022-11-13 2022-12-25 2023-01-24 2023-02-28 Digital Technology Institute ( nvelope 1 velope proce DTI) ss (Non Bank -SPD) Request for B TZ-MCIT-254781-CW-RFB / C ids - Small W Single Stage - One E 2022-11-0 onstruction and enhancemen IDA / 68930 2. Digital Connectivity Post Request for Bids Open - National orks SPD (1 e 0.00 Canceled 2022-01-16 2022-06-08 2022-01-21 2022-03-04 2022-04-03 2022-05-08 nvelope 4 t of Resilient network infrastr nvelope proc ucture ess) GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TZ-MCIT-254586-GO-RFB / S upply, Installation and Comm 3. Digital Platforms and Serv Open - Internationa Single Stage - One E Under Imple issioning of Bulk computing a IDA / 68930 Prior Request for Bids 0.00 2022-04-30 2022-08-01 2022-05-05 2022-08-22 2022-06-20 2022-10-07 2022-07-04 2022-08-08 2022-12-08 ices l nvelope mentation nd storage capacity for enha ncement and Development o f Data Center Infrastructure TZ-MCIT-278874-GO-RFB / S UPPLY, INSTALLATION AND C Single Stage - One E IDA / 68930 2. Digital Connectivity Prior Request for Bids Open - National 0.00 Signed 2022-02-28 2022-03-07 2022-03-05 2022-03-24 2022-04-16 2022-04-22 2022-05-16 2022-09-16 2022-06-20 2022-12-17 OMMISSIOINING OF BANDWI nvelope DTH TERMINATION EQUIPME NT TZ-MCIT-254802-GO-RFB / S upply, Installation and Comm Open - Internationa Single Stage - One E issioning of Active and Passiv IDA / 68930 2. Digital Connectivity Prior Request for Bids 0.00 Canceled 2022-03-24 2022-03-29 2022-05-13 2022-06-12 2022-07-17 2022-10-17 l nvelope e Network Equipment, Power Back Up for GovNet Connect ivity -Phase I TZ-MCIT-300888-GO-RFB / S upply, Installation and Comm Open - Internationa Single Stage - One E Under Imple issioning of Active and Passiv IDA / 68930 2. Digital Connectivity Prior Request for Bids 0.00 2022-07-04 2022-08-01 2022-07-09 2022-08-22 2022-08-23 2022-10-07 2022-09-22 2022-10-27 2023-01-27 l nvelope mentation e Network Equipment, Power Back Up for GovNet Connecti vity -Phase I TZ-MCIT-254584-GO-RFQ / S upply of Communication wor 3. Digital Platforms and Serv Request for Quota Single Stage - One E IDA / 68930 Post Open - National 0.00 Canceled 2022-02-26 2022-04-28 2022-04-23 2022-06-10 king tools and promotional m ices tions nvelope aterial for Digital Tanzania Pr oject TZ-MCIT-306161-GO-RFQ / S upply of Communication tool 3. Digital Platforms and Serv Request for Quota Single Stage - One E IDA / 68930 Post Limited 0.00 Signed 2022-08-20 2022-08-29 2022-09-30 2022-10-30 s and promotion materials fo ices tions nvelope r Digital Tanzania Project TZ-MCIT-254806-GO-RFB / S upply, Installation and Comm Single Stage - One E Pending Impl IDA / 68930 1. Digital Ecosystem Post Request for Bids Open - National 0.00 2023-06-20 2023-06-25 2023-08-06 2023-09-05 2023-10-10 2024-01-29 issioning of ICT Equipment f nvelope ementation or Digital e-Commerce Platfo rm TZ-MCIT-254804-GO-RFB / S upply, Installation and Comm 3. Digital Platforms and Serv Single Stage - One E Pending Impl issioning of ICT Equipment a IDA / 68930 Prior Request for Bids Open - National 0.00 2023-06-15 2023-06-20 2023-08-04 2023-09-03 2023-10-08 2024-04-05 ices nvelope ementation nd Associated Software for H uduma Pamoja Center-Phase I TZ-MCIT-306312-GO-DIR / S Under Imple upply of Four Motor Vehicles IDA / 68930 4. Project Management Post Direct Selection Direct - National 0.00 2022-08-15 2022-09-26 2022-08-20 2022-09-26 2022-09-24 2023-03-23 mentation for the Project TZ-MCIT-254787-GO-RFB / S upply, Installation and Comm Single Stage - One E Pending Impl IDA / 68930 1. Digital Ecosystem Post Request for Bids Open - National 0.00 2022-12-21 2022-12-26 2023-02-09 2023-03-11 2023-04-15 2023-08-31 issioning of ICT Equipment fo nvelope ementation r Digital Technology Institute -Phase I Page 1 TZ-MCIT-254797-GO-RFB / S Single Stage - One E Pending Impl upply, Installation and Comm IDA / 68930 1. Digital Ecosystem Post Request for Bids Open - National 0.00 2024-01-10 2024-01-15 2024-02-26 2024-03-27 2024-05-01 2024-08-13 nvelope ementation issioning of ICT Equipment fo r Zonal Centers TZ-MCIT-254799-GO-RFB / S upply, Installation and Comm Single Stage - One E Pending Impl IDA / 68930 1. Digital Ecosystem Post Request for Bids Open - National 0.00 2024-01-25 2024-01-30 2024-03-15 2024-04-14 2024-05-19 2024-09-27 issioning of of ICT Equipment nvelope ementation for Refurbishment Center TZ-MCIT-254575-GO-RFB / S Single Stage - One E Pending Impl upply, Installation and Comm IDA / 68930 1. Digital Ecosystem Post Request for Bids Open - National 0.00 2023-04-10 2023-04-15 2023-05-30 2023-06-29 2023-08-03 2023-11-10 nvelope ementation issioning of ICT Equipment fo r NISMIS TZ-MCIT-258719-GO-RFB / S upply of four Motor vehicles f IDA / 68930 4. Project Management Post Direct Selection Direct 0.00 Canceled 2022-02-25 2022-03-02 2022-04-06 2022-10-03 or the Project NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TZ-MCIT-254587-NC-RFQ / Pr 3. Digital Platforms and Serv Request for Quota Single Stage - One E ovision of air time for TV and IDA / 68930 Post Open - National 0.00 Canceled 2021-10-30 2021-12-25 2022-06-23 ices tions nvelope Radio Programs for ICT Devel opment TZ-MCIT-254597-NC-RFB / Pr Open - Internationa Single Stage - One E Under Imple e-purchase of Dedicated Ban IDA / 68930 2. Digital Connectivity Prior Request for Bids 0.00 2022-01-31 2022-09-23 2022-02-05 2022-09-30 2022-03-22 2022-11-11 2022-04-21 2023-03-29 2022-05-26 2022-08-24 l nvelope mentation dwidth for GovNet TZ-MCIT-285632-NC-RFB / U Open - Internationa Single Stage - One E Under Imple pgrade of Existing Cell Tower IDA / 68930 2. Digital Connectivity Prior Request for Bids 0.00 2022-04-20 2022-08-22 2022-04-25 2022-08-31 2022-06-06 2022-10-13 2022-07-06 2023-04-08 2022-07-29 2022-10-27 l nvelope mentation s from 2G to 3G, 4G and abo ve TZ-MCIT-285550-NC-RFB / E xtension of contract for Inter net Bandwidth under the Tan IDA / 68930 2. Digital Connectivity Post Direct Selection Direct 410,000.00 Signed 2022-04-13 2022-04-16 2022-04-20 2022-04-21 2022-05-28 2022-07-10 2022-11-24 zania Communication Infrastr ucture and e-Government Pr oject- CONTRACT NO. ME.006 /2011-2012/NC/RCIP/01 TZ-MCIT-306158-NC-RFB / N Open - Internationa Single Stage - One E Under Imple ew Cell Sites in Underserved IDA / 68930 2. Digital Connectivity Prior Request for Bids 0.00 2022-09-30 2022-10-13 2022-10-05 2022-11-24 2022-11-16 2023-01-31 2022-12-16 2023-04-19 2023-01-20 2023-07-19 l nvelope mentation Areas -DTP Phase I TZ-MCIT-254590-NC-RFB / Pr 3. Digital Platforms and Serv Single Stage - One E Pending Impl oduction and Dissemination IDA / 68930 Post Request for Bids Open - National 0.00 2023-10-31 2023-11-05 2023-12-17 2024-01-16 2024-02-20 2024-04-30 ices nvelope ementation of Content on Digital Tanzani a Project CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TZ-MCIT-268417-CS-QCBS / Provision of Consultancy Serv ices to Conduct assessment f Quality And Cost- or Establishment of the Digit IDA / 68930 1. Digital Ecosystem Post Open - National 0.00 Signed 2022-01-14 2022-05-29 2022-02-04 2022-06-10 2022-03-20 2022-08-17 2022-04-17 2022-09-16 2022-05-17 2022-10-19 2022-06-21 2022-10-24 2022-07-26 2022-11-27 Based Selection al Technology Institute, Zona l Soft Centers and ICT equip ment refurbishment centers ( Fab labs) TZ-MCIT-268423-CS-QCBS / Provision of consultancy serv ices to conduct analysis, revi 3. Digital Platforms and Serv Quality And Cost- IDA / 68930 Post Open - National 276,752.28 Signed 2022-01-14 2022-01-28 2022-02-04 2022-03-04 2022-03-20 2022-04-27 2022-04-17 2022-07-08 2022-05-17 2022-06-17 2022-06-21 2022-07-14 2022-07-26 2022-08-10 2022-12-26 ew process mapping, re-engi ices Based Selection neering and establish service s requirements offered by go vernment TZ-MCIT-268429-CS-CQS / Pr ovision of consultancy servic es to conduct business and o 3. Digital Platforms and Serv Consultant Qualifi IDA / 68930 Post Open - National 0.00 Signed 2022-01-30 2022-01-29 2022-02-20 2022-03-04 2022-04-05 2022-04-27 2022-05-05 2022-09-07 2022-06-09 2022-09-09 perational model design and ices cation Selection development of operational manual for huduma pamoja c enters TZ-MCIT-268757-CS-CQS / Pr ovision of Consultancy Servic Consultant Qualifi IDA / 68930 2. Digital Connectivity Post Open - National 240,951.79 Signed 2022-01-30 2022-02-04 2022-02-20 2022-02-16 2022-04-05 2022-04-20 2022-05-05 2022-07-13 2022-06-09 2022-08-10 2022-09-09 es to undertake study on TV cation Selection White Space Spectrum TZ-MCIT-268760-CS-CQS / Pr ovision of consultancy Servic 3. Digital Platforms and Serv Consultant Qualifi IDA / 68930 Post Open - National 0.00 Canceled 2022-01-20 2022-02-02 2022-02-10 2022-02-15 2022-03-26 2022-04-20 2022-04-25 2022-05-30 2022-08-30 es for Preparation of National ices cation Selection Digital Economy Strategy TZ-MCIT-254648-CS-CQS / Pr ovision of Consultancy servic Consultant Qualifi IDA / 68930 1. Digital Ecosystem Post Open - National 0.00 Signed 2022-01-20 2022-04-04 2022-01-20 2022-04-16 2022-03-05 2022-09-26 2022-04-04 2022-10-19 2022-05-09 2022-08-15 e to conduct feasibility study cation Selection for e-commerce redness TZ-MCIT-258591-CS-QCBS / Provision of Consultancy for Quality And Cost- Open - Internationa System Analysis, Designing IDA / 68930 1. Digital Ecosystem Post 0.00 Signed 2022-02-04 2022-03-30 2022-02-25 2022-05-09 2022-04-10 2022-08-25 2022-05-08 2022-09-23 2022-06-07 2022-12-14 2022-07-12 2022-12-14 2022-08-16 2023-08-16 Based Selection l and deployment for National Statistical Information Manag ement System (NISMIS) TZ-MCIT-254810-CS-CQS / Pr ovision of Consultancy Servic Consultant Qualifi es to conduct feasibility stud IDA / 68930 1. Digital Ecosystem Post Open - National 0.00 Canceled 2021-10-28 2021-11-18 2022-01-01 2022-01-31 2022-03-07 2022-09-03 cation Selection y, design and supervision for establishment of refurb Labs TZ-MCIT-254811-CS-QCBS / Provision of Consultancy Serv 3. Digital Platforms and Serv Quality And Cost- Open - Internationa ices for Business Process Ree IDA / 68930 Post 0.00 Canceled 2021-10-20 2021-11-10 2021-12-24 2022-01-21 2022-02-20 2022-03-27 2022-05-01 2023-05-01 ices Based Selection l ngineering, Mapping and Ope rational mode for Huduma Pa moja Center Page 2 TZ-MCIT-254814-CS-QCBS / Provision of Consultancy Serv Consultant Qualifi IDA / 68930 1. Digital Ecosystem Post Open - National 184,116.34 Signed 2022-01-10 2022-01-31 2022-01-31 2022-02-15 2022-03-16 2022-04-20 2022-04-15 2022-07-12 2022-05-20 2022-08-10 2022-11-16 ices for scanning of ICT Polic cation Selection y, Legal and Regulatory Envir onment TZ-MCIT-254809-CS-CQS / Pr ovision of Consultancy Servic Consultant Qualifi Under Implement es to conduct assessment for IDA / 68930 1. Digital Ecosystem Post Open - National 0.00 2022-02-21 2022-01-29 2022-03-14 2022-04-27 2022-05-27 2022-07-01 2022-12-28 cation Selection ation development of Digital Maps for National Addressing and P ostcode system TZ-MCIT-254653-CS-QCBS / Provision of consultancy serv ice to conduct feasibility stu Quality And Cost- IDA / 68930 1. Digital Ecosystem Post Open - National 0.00 Canceled 2021-10-27 2021-11-17 2021-12-31 2022-01-28 2022-02-27 2022-04-03 2022-05-08 2023-05-08 dy, design and supervision fo Based Selection r establishment of National C enter for ICT Professionals a nd Zonal Innovation Center TZ-MCIT-300894-CS-CQS / Pr ovision of Consultancy Servic Consultant Qualifi Under Implement es for Design Review and Su IDA / 68930 4. Project Management Post Open - National 0.00 2022-10-20 2023-02-25 2022-11-10 2023-03-15 2022-12-24 2023-01-23 2023-02-27 2023-08-26 cation Selection ation pervision for Extension of PIU Offices Building for Digital Ta nzania Office TZ-MCIT-314860-CS-CQS / Pr ovision of Consultancy Servic es to conduct Environmental Consultant Qualifi Under Implement and Social Impact Assessmen IDA / 68930 4. Project Management Post Open - National 0.00 2022-09-30 2022-09-30 2022-10-21 2022-10-17 2022-12-04 2023-01-17 2023-01-03 2023-02-07 2023-04-28 cation Selection ation ts and Environmental Audits f or the Sub-Projects implemen ted under Digital Tanzania Pr oject (DTP) TZ-MCIT-314850-CS-QCBS / Provision of Consultancy for 3. Digital Platforms and Serv Quality And Cost- Under Implement IDA / 68930 Post Open - National 0.00 2022-10-10 2022-09-27 2022-10-31 2022-12-14 2023-01-11 2023-02-10 2023-03-07 2023-04-02 2023-09-29 Design and Supervision for re ices Based Selection ation habilitation of Huduma Pamoj a Centers TZ-MCIT-258590-CS-QCBS / Provision of Consultancy for s Quality And Cost- Open - Internationa Pending Impleme IDA / 68930 1. Digital Ecosystem Post 0.00 2023-03-15 2023-04-05 2023-05-19 2023-06-16 2023-07-16 2023-08-20 2023-09-15 2024-08-20 ystem analysis, designing an Based Selection l ntation d deployment of e-commerce Platform TZ-MCIT-331709-CS-CQS / Pr ovision of Consultancy Servic Consultant Qualifi Pending Impleme es for Review of Design and IDA / 68930 1. Digital Ecosystem Post Open - National 0.00 2023-01-20 2023-02-10 2023-03-26 2023-04-25 2023-05-30 2023-06-30 cation Selection ntation Supervision for Rehabilitation of e-Commerce innovation Center at TPC-HQ TZ-MCIT-254808-CS-CQS / Pr 3. Digital Platforms and Serv Consultant Qualifi Pending Impleme ovision of Consultancy Servic IDA / 68930 Post Open - National 0.00 2023-03-20 2023-04-10 2023-05-24 2023-06-23 2023-07-28 2023-11-27 ices cation Selection ntation es for ICT short course Traini ng TZ-MCIT-335718-CS-QCBS / Provision of Consultancy Serv Quality And Cost- Pending Impleme IDA / 68930 1. Digital Ecosystem Post Open - National 0.00 2023-03-15 2023-04-05 2023-05-19 2023-06-16 2023-07-16 2023-08-20 2023-09-24 2024-01-31 ices to Conduct National ICT Based Selection ntation house hold Survey in Tanzani a TZ-MCIT-345710-CS-QCBS / 3. Digital Platforms and Serv Quality And Cost- Under Implement Provision of Consultancy Serv IDA / 68930 Post Open - National 0.00 2023-04-28 2023-03-25 2023-05-19 2023-05-03 2023-07-02 2023-07-30 2023-08-29 2023-10-03 2023-10-20 2024-02-13 ices Based Selection ation ices for Set Up the Data Prot ection Authority TZ-MCIT-360329-CS-QCBS / PROVISION OF CONSULTANC 3. Digital Platforms and Serv Quality And Cost- Open - Internationa Pending Impleme Y SERVICES FOR DESIGN AN IDA / 68930 Post 0.00 2023-06-15 2023-06-21 2023-07-20 2023-08-17 2023-09-16 2023-10-21 2023-11-25 2025-04-30 ices Based Selection l ntation D SUPERVISION OF REHABILI TATION OF HUDUMA PAMOJA CENTERS INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Actual Amount Invitation to Identifie Draft Negotiated Cont Component Review Type Method Contract Type Process Status Teams of Reference Signed Contract Contract Completion Description o. h (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TZ-MCIT-364000-CS-INDV / P rovision of Consultancy servi 3. Digital Platforms and Serv Individual Consult Pending Impleme ces for Supervision(Lead Con IDA / 68930 Post Limited 0.00 2023-06-15 2023-06-20 2023-07-11 2023-08-15 2024-07-31 ices ant Selection ntation sultant) of Huduma Pamoja S ystem design, development and implementation Page 3 PROCUREMENT PLAN (Textual Part) Project information: Mauritania Youth Employability Project Preparation Advance [P162916] Project Implementation agency: Ministry of Employment, Youth and Sports & Department of Education and Training Projects Date of the Procurement Plan: February 2, 2021 Period covered by this Procurement Plan: February 2- December 30, 2021 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in Le décret N° 2020-122 du 06 octobre 2020, modifiant et complétant certaines dispositions du décret N° 2017-126 du 02 novembre 2017, abrogeant et replaçant les dispositions des décrets d’applications de la loi N° 2010-044 du 22 juillet 2010, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: [is not applicable]; Works: [is not applicable] Other Relevant Procurement Information. PROCUREMENT Mauritania : Mauritania Youth Employability Project PLAN General Information Country: Mauritania 2021-02-25 Bank’s Approval Date of the Original Procurement Plan: 2023-06-01 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P162916 GPN Date: 2021-02-25 Project Name: Mauritania Youth Employability Project Loan / Credit No: IDA / V3030, IDA / D8480 Mauritania Youth Employability Project Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 22/2021/PEJ-RIM / Acquisitio Project management, monit Request for Quota Single Stage - One E IDA / V3030 Post Open - National 35,000.00 0.00 Canceled 2021-03-15 2021-04-05 2021-04-22 n équipement oring, and evaluation tions nvelope 25/2021/PEJ-RIM / Achat Logi Project management, monit IDA / V3030 Post Direct Selection Direct 11,000.00 0.00 Canceled 2021-02-15 2021-09-22 2021-02-20 2021-03-27 2021-04-15 ciel de gestion comptable oring, and evaluation 31-2021/PEJ-RIM / Achat Logi Project management, monit Request for Quota Single Stage - One E Pending Impl IDA / V3030 Post Open - National 11,000.00 0.00 2021-05-02 2021-06-03 2021-06-14 ciel de gestion comptable oring, and evaluation tions nvelope ementation 33/2021/PEJ-RIM / Achat des Orientation, job counseling, Single Stage - One E IDA / D8480 Post Request for Bids Open - National 237,260.00 0.00 Signed 2021-09-21 2021-11-08 2021-09-27 2021-11-09 2021-11-08 2021-12-13 2021-12-08 2022-02-07 2022-01-12 2022-02-11 Mobiliers de bureau pour le p and life skills training nvelope rojet (PEJ) 34/2021/PEJ-RIM / Acquisitio Orientation, job counseling, n des véhicules pour pour to IDA / D8480 Post Direct Selection Direct 376,000.00 0.00 Signed 2021-09-30 2021-11-01 2021-10-05 2021-11-03 2021-11-09 2022-02-08 and life skills training utes les composantes du Proj et (PEJ) 23/2021/PEJ-RIM / Achat de Project management, monit Request for Quota Single Stage - One E IDA / V3030 Post Open - National 16,000.00 0.00 Canceled 2021-03-15 2021-04-12 2021-04-22 matériel informatique oring, and evaluation tions nvelope 63/2021/PEJ-RIM / Achat équ Project management, monit Request for Quota Single Stage - One E Pending Impl IDA / D8480 Post Limited 16,000.00 0.00 2021-11-21 2021-12-27 2022-02-15 ipements informatiques oring, and evaluation tions nvelope ementation 64/2021/PEJ-RIM / Achat et i Project management, monit Request for Quota Single Stage - One E Under Imple nstallation d'une salle de vid IDA / D8480 Post Limited 16,000.00 0.00 2021-11-22 2022-01-04 2022-03-04 oring, and evaluation tions nvelope mentation éo conférence 24/2021/PEJ-RIM / Achat et i Project management, monit Request for Quota Single Stage - One E nstallation d'une salle de vid IDA / V3030 Post Open - National 16,000.00 0.00 Canceled 2021-03-15 2021-04-22 2021-10-19 oring, and evaluation tions nvelope éo conférence 35/2021/PEJ-RIM / Acquisitio Orientation, job counseling, Single Stage - One E n matériels informatiques po IDA / D8480 Post Request for Bids Open - National 380,000.00 0.00 Canceled 2021-09-15 2021-11-05 2021-09-20 2021-11-05 2021-11-01 2022-02-23 2021-12-01 2021-12-20 2022-01-20 and life skills training nvelope ur le Projet PEJ 71/2022/PEJ- RIM / Acquisitio Orientation, job counseling, Single Stage - One E IDA / D8480 Post Request for Bids Open - National 380,000.00 0.00 Signed 2022-01-31 2022-02-18 2022-02-05 2022-02-18 2022-03-09 2022-03-24 2022-03-23 2022-04-08 2022-04-21 2022-05-23 n de matériel informatique p and life skills training nvelope our le PEJ 89/2022/PEJ-RIM / Complém Orientation, job counseling, Request for Quota Single Stage - One E ent matériel de bureaux pour IDA / D8480 Post Limited 16,000.00 0.00 Signed 2022-10-10 2022-11-30 2022-11-07 2022-11-15 and life skills training tions nvelope la composante 1 91/2022/PEJ-RIM / Fourniture Orientation, job counseling, Request for Quota Single Stage - One E d'une salle de vidéo conféren IDA / D8480 Post Limited 16,000.00 0.00 Signed 2022-10-06 2022-11-30 2022-11-07 2022-12-12 and life skills training tions nvelope ce pour l'Agence de TECHGHI L 96/2023/PEJ-RIM / Acquisitio Contingency emergency res Request for Quota Single Stage - One E IDA / D8480 Prior Limited 8,432,432.00 0.00 Canceled 2023-04-17 2023-05-01 2023-06-30 n d'hydocureuses de camion ponse tions nvelope s vidangeurs 97/2023/PEJ - RIM / Acquisiti Contingency emergency res Request for Quota Single Stage - One E on de camions bennes de ca IDA / D8480 Post Limited 851,350.00 0.00 Canceled 2023-04-17 2023-05-01 2023-08-25 ponse tions nvelope mions grues et deux porte ch ars 98/2023/PEJ -RIM / Acquisitio Contingency emergency res Request for Quota Single Stage - One E IDA / D8480 Post Limited 1,248,500.00 0.00 Canceled 2023-04-17 2023-05-13 2023-11-09 n de véhicules pour brigades ponse tions nvelope ONAS 99/2023/PEJ - RIM / Acquisiti Contingency emergency res Request for Quota Single Stage - One E on d'une pelle hydraulique et IDA / D8480 Post Limited 1,364,865.00 0.00 Canceled 2023-04-17 2023-05-01 2023-06-30 ponse tions nvelope deux tracto-pelles 100/2023/PEJ - RIM / Acquisit Contingency emergency res Request for Quota Single Stage - One E ion de Groupes motopompes IDA / D8480 Post Limited 1,743,243.00 0.00 Canceled 2023-04-17 2023-05-01 2023-06-30 ponse tions nvelope et de groupes électrogènes 101/2023/PEJ - RIM / Acquisit Contingency emergency res Request for Quota Single Stage - One E IDA / D8480 Post Limited 145,946.00 0.00 Canceled 2023-04-17 2023-05-01 2023-06-30 ion de matériel topographiqu ponse tions nvelope e 103/2023/PEJ - RIM / Acquisit Contingency emergency res Request for Quota Single Stage - One E ion de tuyaux PEHD,de machi IDA / D8480 Post Limited 1,213,500.00 0.00 Canceled 2023-04-10 2023-05-01 2023-06-30 ponse tions nvelope nes à souder et accessoires 104/2023/PEJ-RIM / Achat d' Project management, monit Request for Quota Single Stage - One E Pending Impl IDA / D8480 Post Limited 50,000.00 0.00 2023-04-27 2023-06-22 2023-07-25 un véhicule 4x4 station wago oring, and evaluation tions nvelope ementation n 105/2023/PEJ-RIM / Acquisiti Contingency emergency res Direct - Internation Under Imple on d'Hydrocureuses et de ca IDA / D8480 Prior Direct Selection 8,387,097.00 0.00 2023-05-20 2023-05-23 2023-05-25 2023-06-01 2023-07-03 2023-08-31 ponse al mentation mions vidangeurs 106/2023/PEJ - RIM / Acquisit Contingency emergency res IDA / D8480 Post Direct Selection Direct - National 846,774.00 0.00 Signed 2023-05-20 2023-05-23 2023-05-25 2023-05-23 2023-06-26 2023-08-24 ion de camions grues et de p ponse ortes chars Page 1 107/2023/PEJ-RIM / Acquisiti Contingency emergency res Under Imple IDA / D8480 Post Direct Selection Direct - National 1,241,935.00 0.00 2023-05-20 2023-05-23 2023-05-25 2023-05-23 2023-06-26 2023-08-31 on de véhicules pour brigade ponse mentation s ONAS 108/2023/PEJ-RIM / Acquisiti Contingency emergency res on de pelle hydrauliques, des IDA / D8480 Post Direct Selection Direct - National 1,357,527.00 0.00 Signed 2023-05-20 2023-05-23 2023-05-25 2023-05-23 2023-06-12 2023-08-31 ponse chargeurs et de et deux tract o-pelles 109/2023/PEJ-RIM / Acquisiti on de Groupes motopompes, Contingency emergency res Under Imple IDA / D8480 Post Direct Selection Direct - National 1,733,871.00 0.00 2023-05-20 2023-05-23 2023-05-25 2023-05-23 2023-06-12 2023-08-22 de pompes immergées et de ponse mentation groupes électrogenes 110/2023/PEJ-RIM / Acquisiti Contingency emergency res Under Imple IDA / D8480 Post Direct Selection Direct - National 145,161.00 0.00 2023-05-20 2023-05-23 2023-05-25 2023-05-23 2023-06-21 2023-08-31 on de matériel topographiqu ponse mentation e 111/2023/PEJ-RIM / Acquisiti Contingency emergency res Under Imple on de tuyaux PEHD,de machi IDA / D8480 Post Direct Selection Direct - National 1,206,989.00 0.00 2023-05-20 2023-05-23 2023-05-25 2023-05-23 2023-06-13 2023-08-31 ponse mentation nes à souder et accessoires 114/2023/PEJ - RIM / Achat d Fostering micro-entrepreneu Request for Quota Single Stage - One E Pending Impl ’un véhicule léger au profit d IDA / D8480 rship for income-generating Post Limited 25,000.00 0.00 2023-06-04 2023-07-07 2023-08-07 tions nvelope ementation e la composante 3 (TAAZOUR activities ) 117/2023/PEJ-RIM / Acquisiti on de 3 systèmes centraux d e vidéoconférences pour les Project management, monit Request for Quota Single Stage - One E Pending Impl IDA / D8480 Post Limited 50,000.00 0.00 2023-07-05 2023-08-30 2023-09-29 3 Wilayas de l’est d’intervent oring, and evaluation tions nvelope ementation ion du projet : Assaba, Hodh Gharbi, Hodh Chargui (Opéra tion test) 119/2023/PEJ-RIM / Acquisiti Orientation, job counseling, Request for Quota Single Stage - One E Pending Impl on du matériel informatique IDA / D8480 Post Limited 50,000.00 0.00 2023-07-02 2023-08-27 2024-02-23 and life skills training tions nvelope ementation au profit de la composante 1 du projet NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 46/2021/PEJ-RIM / Multiplicat Project management, monit Request for Quota Single Stage - One E IDA / D8480 Post Open - National 11,000.00 0.00 Canceled 2021-09-05 2021-10-31 2021-12-31 ion Supports de communicati oring, and evaluation tions nvelope on 44/2021/PEJ-RIM / Contractu Orientation, job counseling, Request for Quota Single Stage - One E alisation avec un opérateur t IDA / D8480 Post Open - National 4,800.00 0.00 Canceled 2021-10-05 2021-11-30 2022-05-29 and life skills training tions nvelope élécom (Numéro ver, GFU, in ternet, ...) 39/2021/PEJ-RIM / Contractu Project management, monit Request for Quota Single Stage - One E alisation d'une structure pour IDA / D8480 Post Open - National 30,000.00 0.00 Canceled 2021-09-19 2021-11-14 2022-11-14 oring, and evaluation tions nvelope l’assurance médicale du pers onnel :UCTP 73/2022/PEJ-RIM / Recrutem Orientation, job counseling, Request for Quota Single Stage - One E ent d'un prestataire de téléc IDA / D8480 Post Open - National 25,000.00 0.00 Canceled 2022-03-15 2022-05-25 2022-05-24 2023-05-24 and life skills training tions nvelope om pour la fourniture de serv ice 74/2022/PEJ - RIM / Recrute Project management, monit Request for Quota Single Stage - One E ment d'un prestataire pour n IDA / D8480 Post Limited 10,000.00 0.00 Signed 2022-03-23 2022-03-25 2022-05-18 2023-05-18 oring, and evaluation tions nvelope ettoyages du siège de l'UCTP . 94/2022/PEJ-RIM / Formation Orientation, job counseling, de 15 conseillers d'accueil, d' IDA / D8480 Post Direct Selection Direct - National 11,820.00 0.00 Signed 2023-01-16 2023-01-17 2023-01-21 2023-01-20 2023-02-28 2023-04-29 and life skills training orientation et d'accompagne ment (coaching) 95/2023/PEJ-RIM / Contractu alisation avec un prestataire Orientation, job counseling, Request for Quota Single Stage - One E Under Imple de télécommunication pour l IDA / D8480 Post Limited 50,000.00 0.00 2023-02-20 2023-03-31 2023-04-17 2024-04-16 and life skills training tions nvelope mentation a fourniture de services en a ppui aux activités du projet ( PEJ) 118/2023/PEJ-RIM / Recrute ment d’un prestataire pour la Fostering micro-entrepreneu Pending Impl plateforme de paiement des IDA / D8480 rship for income-generating Post Direct Selection Direct - National 280,000.00 0.00 2023-06-20 2023-06-30 2023-08-21 2024-08-21 ementation subventions au profit des bé activities néficiaires de la composante 3 du PEJ. CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 02/2021/PEJ-RIM / Développ ement de contenu et formati Orientation, job counseling, Consultant Qualifi Open - Internationa IDA / V3030 Post 90,000.00 0.00 Under Review 2021-03-08 2021-03-09 2021-03-15 2022-12-25 2021-04-06 2021-04-13 2021-04-20 2021-07-20 on des conseillers d'accueil, and life skills training cation Selection l d'orientation et d'accompagn ement (coaching) 03/2021/PEJ-RIM / Formation Orientation, job counseling, Quality And Cost- Open - Internationa IDA / V3030 Post 230,000.00 0.00 Canceled 2021-03-08 2021-04-01 2021-03-08 2021-03-08 2021-04-08 2021-04-15 2021-05-03 2021-05-17 2023-05-17 en compétences de vie and life skills training Based Selection l 06/2021/PEJ-RIM / Appui des entreprises structurées et du Technical skills training and i Consultant Qualifi Pending Impleme IDA / V3030 Post Open - National 100,000.00 0.00 2021-03-08 2021-03-08 2021-03-08 2021-03-15 2021-03-25 2022-09-26 secteur informel dans l'identi nternship cation Selection ntation fication des besoins en main d'œuvre ; 07/2021/PEJ-RIM / Conceptio Project management, monit Consultant Qualifi Under Implement n et la mise en place d'un sy IDA / V3030 Post Open - National 45,000.00 0.00 2021-03-09 2021-03-29 2021-03-10 2021-03-30 2021-04-14 2021-05-10 2021-06-24 oring, and evaluation cation Selection ation stème de Suivi et évaluation du projet PEJ 04/2021/PEJ-RIM / Contractu Orientation, job counseling, Consultant Qualifi Open - Internationa alisation d'une structure pour IDA / V3030 Post 40,000.00 0.00 Canceled 2021-02-15 2021-03-02 2021-03-08 2021-04-21 2021-05-21 2021-06-25 2021-12-22 and life skills training cation Selection l la formation en gestion 05/2021/PEJ-RIM / Développ Project management, monit Consultant Qualifi ement du système de gestio IDA / V3030 Post Open - National 50,000.00 0.00 Canceled 2021-02-17 2021-03-02 2021-03-10 2021-04-23 2021-05-23 2021-06-27 2021-12-24 oring, and evaluation cation Selection n de l'information Page 2 28/2021/PEJ-RIM / Développ Project management, monit Consultant Qualifi Under Implement ement du système de gestio IDA / V3030 Post Open - National 80,000.00 0.00 2021-03-26 2021-06-17 2021-04-06 2021-05-04 2021-05-11 2021-05-21 2021-07-31 oring, and evaluation cation Selection ation n de l'information 08/2021/PEJ-RIM / Conceptio Project management, monit Consultant Qualifi n et la mise en place d'un sy IDA / V3030 Post Open - National 39,000.00 0.00 Canceled 2021-02-18 2021-03-11 2021-04-24 2021-05-24 2021-06-28 2021-12-25 oring, and evaluation cation Selection stème de Suivi et évaluation projet PEJ 27/2021/PEJ-RIM / Contractu Fostering micro-entrepreneu Quality And Cost- Open - Internationa alisation d'une structure pour IDA / V3030 rship for income-generating Post 330,000.00 0.00 Signed 2021-03-15 2021-03-27 2021-03-22 2021-09-10 2021-04-28 2021-10-22 2021-05-31 2022-02-23 2021-06-07 2022-04-13 2021-07-05 2022-06-08 2021-07-26 2022-07-26 Based Selection l la formation en gestion activities 01/2021/PEJ6RIM / Développ ement et mise en œuvre d'u Orientation, job counseling, Consultant Qualifi n plan de communication(str IDA / V3030 Post Open - National 50,000.00 0.00 Under Review 2021-04-23 2021-09-21 2021-04-26 2021-09-22 2021-06-09 2021-07-09 2021-08-13 2022-02-09 and life skills training cation Selection atégie nationale et program me d'inclusion économique) 37/2021/PEJ-RIM / Recrutem Project management, monit Least Cost Selecti Under Implement IDA / D8480 Post Open - National 32,000.00 0.00 2021-09-30 2021-10-26 2021-10-21 2021-11-25 2021-11-05 2021-11-17 2021-11-19 2021-12-10 2022-01-14 2022-07-13 ent auditeur externe. UCTP oring, and evaluation on ation 51/2021/PEJ-RIM / Recrutem ent d’un consultant pour le d Orientation, job counseling, Consultant Qualifi IDA / D8480 Post Open - National 230,000.00 0.00 Signed 2021-09-30 2021-09-28 2021-10-06 2021-10-20 2021-11-09 2022-02-01 2021-12-01 2022-03-21 2021-12-08 2022-06-06 éveloppement de programm and life skills training cation Selection es et contenu de formation e n compétence de vie 59/2021/PEJ-RIM / Recrutem ent des ONGs et associations Orientation, job counseling, Consultant Qualifi IDA / D8480 Post Open - National 17,000.00 0.00 Signed 2021-12-07 2021-12-23 2021-12-28 2022-02-19 2022-02-10 2022-03-21 2022-03-12 2022-05-10 2022-04-16 2022-10-13 pour la sensibilisation comm and life skills training cation Selection unautaire Zone 3 (Nouakchot t Sud et Guidimakha) 58/2021/PEJ-RIM / Recrutem ent des ONGs et associations Orientation, job counseling, Consultant Qualifi pour la sensibilisation comm IDA / D8480 Post Limited 39,000.00 0.00 Under Review 2021-12-07 2021-12-23 2021-12-21 2022-01-06 2022-02-10 2022-12-31 and life skills training cation Selection unautaire Zone 2 (Nouakchot t Nord+ Assaba + Traza) 60/2021/PEJ-RIM / Recrutem ent des ONGs pour la formati on en compétences de vie de s bénéficiaires trois lots disti ncts: Orientation, job counseling, Fixed Budget Sele IDA / D8480 Prior 8,700,000.00 0.00 Signed 2021-11-26 2021-12-29 2021-12-10 2022-04-22 2022-01-04 2022-09-13 2022-02-17 2022-10-26 2022-03-04 2022-11-30 2022-03-25 2023-01-11 2022-04-20 2026-04-20 lot 1: Nouakchott Ouest + Ho and life skills training ction dh Chargui + Hodh Gharbi lot 2: Nouakchott Nord +Assa ba + Trarza lot 3: Nouakchott Sud + Gui dimaka 36/2021/PEJ-RIM / Recrutem ent des ONGs et associations Orientation, job counseling, Consultant Qualifi pour la sensibilisation comm IDA / D8480 Post Limited 33,000.00 0.00 Signed 2021-12-07 2021-12-23 2021-12-14 2022-04-04 2022-01-03 2022-05-20 2022-02-04 2022-12-31 and life skills training cation Selection unautaire (Zone 1: Nouakcho tt ouest + Hodh Gharbi + Ho dh Echargui) 68/2022/PEJ-RIM / Recrutem ent des ONGs pour la formati on de 17073 jeunes bénéficia ires en micro-entreprenariat Fostering micro-entrepreneu en trois zones : Fixed Budget Sele Open - Internationa IDA / D8480 rship for income-generating Prior 2,475,500.00 0.00 Signed 2022-02-21 2022-04-11 2022-03-14 2022-07-15 2022-04-19 2022-10-11 2022-06-16 2022-10-17 2022-07-16 2022-12-12 2022-08-22 2023-01-11 2022-09-28 2023-03-30 2026-06-30 Zone 1: Nouakchott Ouest + ction l activities Hodh Chargui + Hodh Gharbi Zone 2: Nouakchott Nord +A ssaba + Trarza Zone 3: Nouakchott Sud + G uidimaka 80/2022/PEJ-RIM / Recrutem Technical skills training and i Consultant Qualifi ent d'une structure pour la fo IDA / D8480 Post Limited 22,900.00 0.00 Under Review 2022-08-15 2022-11-29 2022-08-29 2022-09-28 2022-11-02 2023-05-01 nternship cation Selection rmation de 25 agents de séc urité 79/2022/PEJ-RIM / Recrutem ent d'une structure de format Technical skills training and i Consultant Qualifi Under Implement IDA / D8480 Post Limited 37,000.00 0.00 2022-08-15 2022-11-29 2022-08-29 2022-09-28 2022-11-02 2023-05-01 ion pour la formation de 30 a nternship cation Selection ation gents d'assurance 81/2022/PEJ-RIM / Recrutem Technical skills training and i Consultant Qualifi Under Implement ent d'une structure de format IDA / D8480 Post Limited 39,000.00 0.00 2022-08-15 2022-11-29 2022-08-29 2022-09-28 2022-11-02 2023-05-01 nternship cation Selection ation ion de 33 agents bancaires 93/2022/PEJ-RIM / Formation locale sur la méthode GEMS ( Project management, monit Consultant Qualifi IDA / D8480 Post Limited 16,000.00 0.00 Signed 2022-11-15 2022-11-02 2022-11-29 2022-11-25 2022-12-06 2023-01-06 2022-12-20 2023-01-09 Géo-Enabing for monitoring a oring, and evaluation cation Selection nd supervision) de l'UCTP et Composante 88/2022/PEJ-RIM / Recrutem ent d’un prestataire de téléc Orientation, job counseling, Least Cost Selecti ommunication pour la fournit IDA / D8480 Post Open - National 50,000.00 0.00 Canceled 2022-10-05 2022-10-12 2022-11-02 2022-11-14 2022-11-17 2022-12-01 2022-12-15 2023-01-15 and life skills training on ure de services en appui aux activités du projet (PEJ) INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 17/2021/PEJ-RIM / Consultan Fostering micro-entrepreneu t-e-s pour l’appui à la compo Individual Consult Under Implement IDA / V3030 rship for income-generating Post Open 7,000.00 0.00 2021-02-04 2021-03-03 2021-03-25 2021-04-15 2021-05-20 2021-11-16 sante 2 (adaptation et dével ant Selection ation activities oppement des outils de l'ingé nierie de formation) ; 09/2021/PEJ-RIM / Elaboratio n d'un manuel de procédures Project management, monit Individual Consult Under Implement IDA / V3030 Post Open 13,000.00 0.00 2021-02-18 2021-03-27 2021-04-08 2021-04-29 2021-06-03 2021-11-30 administratives, financières e oring, and evaluation ant Selection ation t de passation des marchés d u PEJ 11/2021/PEJ-RIM / Coordinat Technical skills training and i Individual Consult IDA / V3030 Post Open 49,000.00 0.00 Signed 2021-02-18 2021-03-17 2021-04-08 2022-03-07 2021-04-29 2022-03-07 2021-06-03 2021-11-30 eur technique du projet nternship ant Selection 12/2021/PEJ-RIM / Spécialist Project management, monit Individual Consult IDA / V3030 Post Open 26,000.00 0.00 Signed 2021-02-18 2021-03-17 2021-04-08 2021-09-22 2021-04-29 2021-09-22 2021-06-03 2021-11-30 e en passation de marchés d oring, and evaluation ant Selection u PEJ Page 3 13/2021/PEJ-RIM / Responsa Project management, monit Individual Consult IDA / V3030 Post Open 26,000.00 0.00 Under Review 2021-02-04 2021-03-17 2021-03-25 2021-04-15 2021-05-20 2021-11-16 ble administratif et financier oring, and evaluation ant Selection 14/2021/PEJ-RIM / Spécialist Project management, monit Individual Consult Under Implement IDA / V3030 Post Open 26,000.00 0.00 2021-02-04 2021-03-17 2021-03-25 2021-04-15 2021-05-20 2021-11-16 e en suivi et évaluation oring, and evaluation ant Selection ation 15/2021/PEJ-RIM / Spécialist Technical skills training and i Individual Consult Under Implement e en formation professionnell IDA / V3030 Post Open 26,000.00 0.00 2021-02-18 2021-03-17 2021-04-08 2021-04-29 2021-06-03 2021-11-30 nternship ant Selection ation e et entrepreneuriat 16/2021/PEJ-RIM / Consultan t-e-s pour l’appui à la compo Fostering micro-entrepreneu Individual Consult sante 3 micro-entrepreneuri IDA / V3030 rship for income-generating Post Open 10,000.00 0.00 Canceled 2021-02-04 2021-03-08 2021-03-25 2021-04-15 2021-05-20 2021-11-16 ant Selection at pour les activités génératri activities ces de revenus, consultant in dividuel ; 18/2021/PEJ-RIM / Spécialist Project management, monit Individual Consult Under Implement IDA / V3030 Post Open 26,000.00 0.00 2021-02-04 2021-03-17 2021-03-25 2021-04-15 2021-05-20 2021-11-16 e en communication oring, and evaluation ant Selection ation 19/2021/PEJ-RIM / Spécialist Project management, monit Individual Consult Under Implement IDA / V3030 Post Open 26,000.00 0.00 2021-02-04 2021-03-17 2021-03-25 2021-04-15 2021-05-20 2021-11-16 e genre et sauvegardes socia oring, and evaluation ant Selection ation les 21/2021/PEJ-RIM / Comptabl Project management, monit Individual Consult Under Implement IDA / V3030 Post Open 15,000.00 0.00 2021-02-04 2021-03-17 2021-03-25 2021-04-15 2021-05-20 2021-11-16 e du PEJ oring, and evaluation ant Selection ation 20/2021/PEJ-RIM / Consultan Contingency emergency res Individual Consult IDA / V3030 Post Open 7,000.00 0.00 Canceled 2021-02-04 2021-03-03 2021-03-25 2021-04-15 2021-05-20 2021-11-16 t-e pour l'extension du SI de l ponse ant Selection 'ANAPEJ 26/2021/PEJ-RIM / Recrutem ent d'un consultant-e pour l'e Orientation, job counseling, Under Implement IDA / V3030 Post Direct Selection Direct 30,000.00 0.00 2021-03-15 2021-03-17 2021-03-23 2021-04-01 2021-06-01 xtension du système de l'info and life skills training ation rmation de l'ANAPEJ 10/2021/PEJ-RIM / Mission d' appui et d'accompagnement Project management, monit Individual Consult IDA / V3030 Post Direct 12,000.00 0.00 Canceled 2021-02-04 2021-03-01 2021-02-14 2021-03-07 2021-04-11 2021-10-08 pour la finalisation des condit oring, and evaluation ant Selection ions de négociation du PEJ 30/2021/PEJ-RIM / Spécialist Project management, monit Individual Consult Pending Impleme IDA / V3030 Post Open 26,000.00 0.00 2021-03-08 2021-03-15 2021-03-20 2021-04-26 2022-04-25 e en Gestion du système d'in oring, and evaluation ant Selection ntation formation; 29/2021/PEJ6RIM / Mission d' Project management, monit Individual Consult Under Implement IDA / V3030 Post Open 13,000.00 0.00 2021-03-15 2021-03-15 2021-04-14 2021-04-21 2021-04-28 2021-10-25 appui et d'accompagnement oring, and evaluation ant Selection ation du PEJ 32/2021/PEJ-RIM / Élaboratio n d’un mécanisme de gestion Project management, monit Individual Consult des plaintes et d’un plan de IDA / V3030 Post Open 10,000.00 0.00 Signed 2021-05-20 2021-05-05 2021-06-22 2023-03-21 2021-07-02 2023-03-22 2021-08-03 2021-10-04 oring, and evaluation ant Selection prévention et d’atténuation d e l’exploitation et abus sexue ls/Harcèlement sexuel 41/2021/PEJ-RIM / Recrutem Project management, monit Individual Consult ent d’un consultant pour l’ap IDA / D8480 Post Open 28,000.00 0.00 Canceled 2021-09-30 2021-11-22 2021-12-07 2022-01-11 2022-07-10 oring, and evaluation ant Selection pui aux agences d’exécution 42/2021/PEJ-RIM / Recrutem Fostering micro-entrepreneu ent d'un Conseiller technique Individual Consult IDA / D8480 rship for income-generating Post Open 11,400.00 0.00 Signed 2021-09-28 2021-12-08 2021-11-02 2022-04-15 2021-11-16 2023-03-22 2021-12-14 2022-06-12 pour la Formation au profit d ant Selection activities e la composante 3 45/2021/PEJ-RIM / Recrutem ent d'un consultant pour l'ani Project management, monit Individual Consult mation d'un atelier validation IDA / D8480 Post Open 4,000.00 0.00 Canceled 2021-09-27 2021-10-02 2021-11-02 2021-11-15 2021-11-30 2022-01-31 oring, and evaluation ant Selection Stratégie de Communication de SNE et plan de communic ation PEJ 47/2021/PEJ-RIM / Recrutem ent d'un consultant pour l'ani Orientation, job counseling, Individual Consult IDA / D8480 Post Open 15,000.00 0.00 Canceled 2021-09-30 2021-11-03 2021-11-10 2021-12-01 2022-05-30 mation d'un atelier de sensib and life skills training ant Selection ilisation et d'information 48/2021/PEJ-RIM / Recrutem Project management, monit Individual Consult IDA / D8480 Post Open 23,000.00 0.00 Under Review 2021-09-30 2021-12-01 2021-10-27 2021-11-17 2021-12-22 2022-12-22 ent d’un consultant pour l’ap oring, and evaluation ant Selection pui à la CPE 50/2021/PEJ-RIM / Recrutem ent d'un consultant pour l'ap Project management, monit Individual Consult IDA / D8480 Post Open 40,000.00 0.00 Canceled 2021-10-13 2021-12-01 2021-11-08 2021-11-29 2021-12-27 2022-12-26 pui de l'Unité de Coordinatio oring, and evaluation ant Selection n Technique du Projet (UCTP) 52/2021/PEJ-RIM / Recrutem ent d'un consultant pour l'ap Project management, monit Individual Consult IDA / D8480 Post Limited 40,000.00 0.00 Signed 2021-10-28 2021-11-14 2021-11-08 2022-01-25 2021-11-12 2022-02-25 2021-12-31 2022-12-31 pui de l'Unité de Coordinatio oring, and evaluation ant Selection n Technique du Projet (UCTP) 43/2021/PEJ-RIM / Réalisatio Project management, monit Individual Consult IDA / D8480 Post Open 30,000.00 0.00 Canceled 2021-09-15 2021-10-06 2021-10-09 2021-10-15 2021-10-26 2021-11-25 n d'un hymne du Projet oring, and evaluation ant Selection 53/2021/PEJ-RIM / Recrutem Project management, monit Individual Consult Under Implement ent d’un consultant pour réal IDA / D8480 Post Limited 30,000.00 0.00 2021-10-28 2021-10-31 2021-11-02 2021-11-08 2021-11-29 2022-01-28 oring, and evaluation ant Selection ation isation de l’hymne du projet ( PEJ) 40/2021/PEJ-RIM / Recrutem Fostering micro-entrepreneu Individual Consult IDA / D8480 Post Open 11,400.00 0.00 Canceled 2021-09-15 2021-10-12 2021-10-20 2021-11-15 2022-05-14 ent d’un Conseiller technique rship for income-generating ant Selection AGR activities 49/2021/PEJ-RIM / Recrutem ent d’un consultant pour l’ani mation d’un atelier d'inform Project management, monit Individual Consult IDA / D8480 Post Open 4,000.00 0.00 Canceled 2021-09-07 2021-10-02 2021-11-02 2021-11-16 2021-12-07 2022-01-06 ation et de sensibilisation sur oring, and evaluation ant Selection les normes sociales et envir onnementales, CGES, PEES, ect 55/2021/PEJ-RIM / Recrutem ent d’un consultant pour l’ani Project management, monit Individual Consult Under Implement mation d’un atelier d'informa IDA / D8480 Post Limited 4,000.00 0.00 2021-10-27 2021-10-31 2021-11-01 2021-11-08 2021-12-01 2022-02-01 oring, and evaluation ant Selection ation tion et de sensibilisation sur l es normes sociales et enviro nnementales, CGES, PEES, 56/2021/PEJ - RIM / Recrute Fostering micro-entrepreneu Individual Consult ment d’une assistante admin IDA / D8480 rship for income-generating Post Limited 9,000.00 0.00 Under Review 2021-11-15 2021-12-08 2021-11-22 2021-12-06 2022-01-03 2022-12-31 ant Selection istratif pour la composante 3 activities du PEJ Page 4 54/2021/PEJ-RIM / Recrutem Fostering micro-entrepreneu Individual Consult IDA / D8480 Post Direct 26,000.00 0.00 Signed 2021-10-29 2021-11-01 2021-11-08 2021-11-10 2021-11-29 2022-05-11 2022-01-03 2022-12-29 ent d’un Conseiller technique rship for income-generating ant Selection AGR activities 38/2021/PEJ-RIM / Recrutem Project management, monit Individual Consult IDA / D8480 Post Open 15,000.00 0.00 Signed 2021-09-30 2021-11-24 2021-11-18 2022-03-09 2021-12-09 2022-05-03 2022-01-13 2022-07-12 ent d'un auditeur interne pou oring, and evaluation ant Selection r l' UCTP 66/2021/PEJ-RIM / Recrutem Project management, monit Individual Consult ent d'un consultant pour l'éla IDA / D8480 Post Open 15,000.00 0.00 Signed 2021-11-30 2021-12-08 2021-12-28 2022-05-01 2022-01-03 2023-01-10 2022-02-01 2022-04-06 oring, and evaluation ant Selection boration d'un manuel de proc édure de la CPE 57/2021/PEJ-RIM / Recrutem ent de 4 agents conseillers e Orientation, job counseling, Individual Consult IDA / D8480 Post Open 32,000.00 0.00 Signed 2022-01-07 2022-02-08 2022-02-03 2022-07-20 2022-02-22 2022-09-14 2022-03-14 2022-04-15 n emploi au profit de l'agen and life skills training ant Selection ce de TACHGHIL pour la Wila ya du Hodh El Gharbi. 61/2021/PEJ-RIM / Recrutem ent de 4 agents conseillers e Orientation, job counseling, Individual Consult IDA / D8480 Post Open 32,000.00 0.00 Signed 2022-01-07 2022-02-08 2022-02-07 2022-08-18 2022-02-21 2022-09-15 2022-03-28 2022-05-03 n emploi au profit de l'agen and life skills training ant Selection ce de TACHGHIL pour la Wila ya du Hodh El Chargui. 62/2021/PEJ-RIM / Recrutem ent de 4 agents conseillers e Orientation, job counseling, Individual Consult IDA / D8480 Post Open 32,000.00 0.00 Signed 2022-01-07 2022-02-08 2022-02-22 2022-09-15 2022-03-10 2022-09-15 2022-03-31 2022-05-03 n emploi au profit de l'agen and life skills training ant Selection ce de TACHGHIL pour la Wila ya d'Assaba 65/2021/PEJ-RIM / Recrutem ent de 4 agents conseillers e Orientation, job counseling, Individual Consult IDA / D8480 Post Open 32,000.00 0.00 Signed 2022-01-07 2022-02-08 2022-02-04 2022-07-20 2022-02-11 2023-03-28 2022-03-11 2022-04-25 n emploi au profit de l'agen and life skills training ant Selection ce de TACHGHIL pour la Wila ya du Guidimagha. 67/2021/PEJ-RIM / Recrutem ent de 4 agents conseillers e Orientation, job counseling, Individual Consult IDA / D8480 Post Open 32,000.00 0.00 Signed 2022-01-07 2022-02-08 2022-02-02 2022-07-20 2022-02-09 2022-09-15 2022-03-09 2022-04-11 n emploi au profit de l'agen and life skills training ant Selection ce de TACHGHIL pour la Wila ya du Traza. 70/2022/PEJ - RIM / Recrute ment d'un consultant pour l'é laboration d’un plan de com Project management, monit Individual Consult munication et des modalités IDA / D8480 Post Limited 11,000.00 0.00 Signed 2022-03-07 2022-03-23 2022-03-15 2023-02-02 2022-04-01 2022-06-07 2022-05-06 2022-08-04 oring, and evaluation ant Selection de mise en œuvre de session s d’information et de sensibili sation sur le MGP/Plan EAS/H S/VBG 72/2022/PEJ-RIM / Recrutem Project management, monit Individual Consult ent d'un assistant de passati IDA / D8480 Post Limited 10,000.00 0.00 Canceled 2022-03-15 2022-04-19 2022-03-22 2022-04-12 2022-05-17 2023-05-17 oring, and evaluation ant Selection on des marchés 75/2022/PEJ-RIM / Recrutem Project management, monit Individual Consult IDA / D8480 Post Limited 10,000.00 0.00 Signed 2022-03-15 2022-09-30 2022-03-22 2022-11-02 2022-04-12 2022-11-07 2022-05-17 2023-05-17 ent d'un comptable oring, and evaluation ant Selection 76/2022/PEJ - RIM / Agent ad Project management, monit Individual Consult IDA / D8480 Post Limited 10,000.00 0.00 Signed 2022-03-15 2022-03-24 2022-03-22 2022-06-06 2022-04-12 2022-06-15 2022-05-17 2023-05-17 ministratif pour le PEJ oring, and evaluation ant Selection 77/2022/PEJ - RIM / Recrute Project management, monit Individual Consult ment d'un assistance du Coo IDA / D8480 Post Limited 11,000.00 0.00 Canceled 2022-03-02 2022-03-24 2022-03-09 2022-03-30 2022-05-04 2023-05-04 oring, and evaluation ant Selection rdinateur Technique du PEJ 78/2022/PEJ-RIM / Recrutem Project management, monit Individual Consult ent de l'assistante du Coordi IDA / D8480 Post Limited 13,000.00 0.00 Signed 2022-05-13 2022-05-07 2022-05-31 2022-10-31 2022-06-21 2022-11-03 2022-07-26 2023-07-26 oring, and evaluation ant Selection nateur technique du PEJ 69/2022/PEJ-RIM / Recrutem Project management, monit Individual Consult ent d'un assistant de passati IDA / D8480 Post Limited 11,500.00 0.00 Signed 2022-04-28 2022-05-07 2022-05-03 2022-11-21 2022-05-24 2022-06-15 2022-06-28 2023-06-28 oring, and evaluation ant Selection on des marches 82/2022/PEJ-RIM / Contractu alisation avec la Mauritanien Technical skills training and i ne de Tissage de Tapies (MA IDA / D8480 Post Direct Selection Direct - National 54,000.00 0.00 Canceled 2022-08-15 2022-08-25 2022-10-29 2023-04-27 nternship TIS) pour la formation de 62 des jeunes filles en Tissage d e tapies 83/2022/PEJ-RIM / Recrutem ent d'un expert en orientatio Orientation, job counseling, Individual Consult IDA / D8480 Post Limited 26,000.00 0.00 Signed 2022-09-26 2022-09-30 2022-10-01 2023-02-08 2022-10-22 2023-03-29 2022-11-26 2023-11-27 n et formation des bénéficiair and life skills training ant Selection es pour la composante 1 84/2022/PEJ-RIM / Recrutem ent d'un expert pour le traite Orientation, job counseling, Individual Consult IDA / D8480 Post Limited 26,000.00 0.00 Signed 2022-09-26 2022-09-30 2022-10-01 2023-02-08 2022-10-22 2023-03-29 2022-11-26 2023-11-27 ment et l'analyse de données and life skills training ant Selection des bénéficiaires au profit la composante 1 85/2022/PEJ-RIM / Recrutem Contingency emergency res Individual Consult ent d'un/une assistant(e) ad IDA / D8480 Post Limited 9,000.00 0.00 Signed 2022-09-26 2022-11-11 2022-10-01 2023-02-07 2022-10-22 2023-03-29 2022-11-26 2023-11-27 ponse ant Selection ministratif-(ve) 86/2022/PEJ-RIM / Consultan t d'un/une consultant(e) pou r la mise en place d’un interf Project management, monit Individual Consult IDA / D8480 Post Limited 14,000.00 0.00 Signed 2022-09-23 2022-09-30 2022-09-28 2022-10-31 2022-10-11 2022-10-31 2022-11-04 2022-12-26 açage entre le system d’infor oring, and evaluation ant Selection mation du PEJ, son Système de suivi-évaluation et le syst ème DELLIL de l’Agence Tech ghil. 87/2022/PEJ-RIM / Recrutem Project management, monit Individual Consult Under Implement ent d’un/une technicien(ne) e IDA / D8480 Post Limited 11,500.00 0.00 2022-10-05 2022-11-08 2022-10-10 2022-10-31 2022-12-05 2023-12-04 oring, and evaluation ant Selection ation n informatique pour l’UCTP 90/2022/PEJ-RIM / Recrutem ent d’un consultant en vue d e l’évaluation des risques VB Project management, monit Individual Consult IDA / D8480 Post Limited 11,000.00 0.00 Signed 2022-10-05 2022-09-30 2022-10-10 2022-11-01 2022-10-14 2022-11-07 2022-12-20 2023-02-20 G, d’exploitation et abus sex oring, and evaluation ant Selection uels (EAS) et de harcèlement sexuel (HS) dans la zone d’in tervention du PEJ. 92/2022/PEJ-RIM / Recrutem ent d'un consultant pour l'év Technical skills training and i Individual Consult aluation des activités de for IDA / D8480 Post Limited 16,000.00 0.00 Signed 2022-10-13 2022-10-29 2022-10-18 2022-11-25 2022-10-25 2022-11-25 2022-11-14 2022-12-29 nternship ant Selection mation professionnelle condu ites dans le cadre l’action pil ote. Page 5 112/2023/PEJ - RIM / Recrute ment d’un(e) consultant pour Contingency emergency res Individual Consult Pending Impleme IDA / D8480 Post Limited 26,000.00 0.00 2023-05-25 2023-05-31 2023-06-21 2023-07-26 2024-05-31 le suivi de la sauvegarde env ponse ant Selection ntation ironnementale et sociales 113/2023/PEJ - RIM / Recrute ment d’un(e) expert pour l'ac Technical skills training and i Individual Consult Pending Impleme compagnement de la mise e IDA / D8480 Post Limited 26,000.00 0.00 2023-05-25 2023-05-31 2023-06-15 2023-07-13 2024-06-27 nternship ant Selection ntation n place du cadre de concerta tion entre le secteur privé et les services de l'emploi. 115/2023/PEJ-RIM / Recrute ment de trois opérateurs (tric Project management, monit Individual Consult Under Implement IDA / D8480 Post Limited 25,000.00 0.00 2023-06-15 2023-06-01 2023-06-23 2023-07-07 2023-07-20 2024-07-19 es) de saisie pour la mise à j oring, and evaluation ant Selection ation our des bases de données du projet 116/2023/PEJ-RIM / Recrute ment d’un Expert pour l’appu Project management, monit Individual Consult Pending Impleme IDA / D8480 Post Limited 15,000.00 0.00 2023-06-15 2023-06-20 2023-07-11 2023-08-15 2023-11-13 i à la mise en œuvre de la co oring, and evaluation ant Selection ntation mposante « CERC » Page 6 PROCUREMENT PLAN (Textual Part) Project information: P163023: PE Integrated Forest Management in Atalaya Project Implementation agency: Programa Nacional de Conservación de Bosques para la Mitigación del Cambio Climático – PNBC Date of the Procurement Plan: Feb 15, 2017 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. Leased Assets Not Applicable Procurement of Second Hand Goods Not Applicable Domestic preference Not Applicable Other Relevant Procurement Information. Not Applicable PROCUREMENT Peru : Integrated Forest Landscape Management Project in Atalaya, Ucayali PLAN General Information Country: Peru 2017-10-10 Bank’s Approval Date of the Original Procurement Plan: 2023-06-02 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P163023 GPN Date: 2020-03-12 Project Name: Integrated Forest Landscape Management Project in Atalaya, Ucayali Loan / Credit No: TF / A4636, TF / A8849, TF / A8845 Prog Nacional de Conservacion de Bosques para Mitigacion del Cambio Climatico Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PE-PNCB-29185-GO-DIR / Úti Request for Quota Single Stage - One E les, papelería, otros, material TF / A4636 Post Limited 1,364.00 0.00 Canceled 2017-11-03 2017-11-20 2017-11-30 tions nvelope es para Talleres PE-PNCB-143148-GO-RFQ / Ú Project Management, Monito Request for Quota Single Stage - One E TF / A8849 Post Open - National 1,515.15 887.39 Completed 2019-11-07 2019-12-09 2019-11-24 2019-12-19 2019-12-04 2019-12-31 TILES DE OFICINA ring and Evaluation tions nvelope PE-PNCB-146447-GO-RFQ / A DQUISICIÓN EQUIPOS INFOR Project Management, Monito Request for Quota Single Stage - One E TF / A8849 Post Open - National 23,652.00 25,754.29 Completed 2019-11-30 2019-12-09 2019-12-11 2020-03-11 2019-12-21 2020-04-19 MÁTICOS PARA EL EQUIPO D ring and Evaluation tions nvelope E GESTIÓN DE PROYECTOS – EGP PE-PNCB-C.8.16.17-GO-RFQ / Adquisición de equipos de co Project Management, Monito Request for Quota Single Stage - One E TF / A8849 Post Limited 14,354.00 11,789.27 Completed 2020-04-15 2020-12-01 2020-04-29 2020-12-24 2020-05-29 2021-01-01 mputo, insumos de impresió ring and Evaluation tions nvelope n y software antivirus PE-PNCB-C.11-GO-RFQ / Adq Project Management, Monito Request for Quota Single Stage - One E TF / A8849 Post Limited 4,848.00 0.00 Canceled 2020-09-09 2020-09-23 2020-10-23 uisición de útiles de oficina ring and Evaluation tions nvelope PE-PNCB-C.14-GO-RFQ / Serv Project Management, Monito Request for Quota Single Stage - One E TF / A8849 Post Limited 36,364.00 0.00 Canceled 2020-03-30 2020-04-21 2021-01-07 icio de alquiler de local ring and Evaluation tions nvelope PE-PNCB-29443-GO-RFQ / Ad Project Management, Monito Request for Quota Single Stage - One E TF / A8849 Post Limited 3,000.00 3,112.55 Completed 2020-10-09 2020-11-05 2020-10-24 2020-11-26 2020-10-28 2020-12-01 quisición de Impresoras ring and Evaluation tions nvelope PE-PNCB-A.3.5.3-GO-RFQ / A dquisición de medicamentos Project Management, Monito Request for Quota Single Stage - One E TF / A8849 Post Limited 9,091.00 0.00 Canceled 2021-02-24 2021-03-10 2021-04-09 y equipos de protección para ring and Evaluation tions nvelope los viajes de campo PE-PNCB-A.3.5.3.2-GO-RFQ / Institutional Strengthening f Request for Quota Single Stage - One E Equipos de salud y Bioseguri TF / A8849 Post Open - National 4,000.00 4,917.36 Completed 2021-04-15 2021-10-02 2021-04-29 2022-04-26 2021-05-29 2022-05-07 or Forest Conservation tions nvelope dad (equipo de seguridad) PE-PNCB-A.3.5.4.2-GO-RFQ / Institutional Strengthening f Request for Quota Single Stage - One E TF / A8849 Post Open - National 500.00 0.00 Canceled 2021-04-15 2021-04-29 2021-05-29 20 linternas con cargador sol or Forest Conservation tions nvelope ar PE-PNCB-B.4.1.1.3-GO-RFQ / Licencias (pix4d planificacion Institutional Strengthening f Request for Quota Single Stage - One E TF / A8849 Post Open - National 5,000.00 0.00 Canceled 2021-07-06 2021-08-31 2021-09-30 de vuelo y postprocesamient or Forest Conservation tions nvelope o de imágenes aéreas) PE-PNCB-C.8.2.2.1-GO-RFQ / Institutional Strengthening f Request for Quota Single Stage - One E TF / A8849 Post Open - National 3,500.00 3,790.11 Completed 2021-05-01 2021-10-02 2021-06-15 2021-11-08 2021-07-01 2021-12-10 Aire acondicionado or Forest Conservation tions nvelope PE-PNCB-C.8.2.2.4-GO-RFQ / Otros (cable, rauter, swicht, c ables, extensión)(100 mt de cable para Internet, 01 raute Institutional Strengthening f Request for Quota Single Stage - One E TF / A8849 Post Open - National 1,000.00 683.53 Completed 2021-04-29 2021-09-29 2021-05-13 2021-11-08 2021-06-12 2021-12-05 r wifi 3 antenas largo alcance or Forest Conservation tions nvelope , 01 swicht 16 puertos, 01 an tena receptora acces point, 0 1 patch cord cables conector es RJ y otros, 15 metros de e xtensión) PE-PNCB-C.10.1-GO-RFQ / M obiliario (05 escritorios, 05 sil las giratorias, 12 sillas fijas, 0 Project Management, Monito Request for Quota Single Stage - One E 3 estantes, 01 mueble con ca TF / A8849 Post Open - National 7,000.00 5,381.13 Completed 2021-05-01 2021-09-28 2021-06-26 2021-11-15 2021-07-26 2021-12-12 ring and Evaluation tions nvelope jones para archivador, 02 mu ebles para impresora y 01 m esa de reuniones con capaci dad para 12 personas) PE-PNCB-C.11.1-GO-RFQ / Út Institutional Strengthening f Request for Quota Single Stage - One E TF / A8849 Post Open - National 1,500.00 0.00 Canceled 2021-07-10 2021-09-04 2021-09-24 iles de oficina or Forest Conservation tions nvelope PE-PNCB-C.17.1-GO-RFQ / A Institutional Strengthening f Request for Quota Single Stage - One E TF / A8849 Post Open - National 500.00 0.00 Canceled 2021-05-01 2021-06-26 2021-07-26 ntivirus or Forest Conservation tions nvelope PE-PNCB-C.17.3-GO-RFQ / Li Institutional Strengthening f Request for Quota Single Stage - One E TF / A8849 Post Open - National 12,500.00 0.00 Canceled 2021-05-01 2021-06-26 2021-07-26 cencias de MS Project or Forest Conservation tions nvelope PE-PNCB-COMBUST.Y.LUB.20 Institutional Strengthening f Request for Quota Single Stage - One E 21.A.B-GO-RFQ / COMBUSTIB TF / A8849 Post Open - National 4,000.00 0.00 Canceled 2021-07-20 2021-09-14 2021-10-14 or Forest Conservation tions nvelope LE Y LUBRICANTE PE-PNCB-C.19.9-2021-GO-RF Q / Servicios de elaboración Project Management, Monito Request for Quota Single Stage - One E TF / A8849 Post Open - National 13,000.00 0.00 Canceled 2021-07-20 2021-09-14 2022-03-13 de material informativo y co ring and Evaluation tions nvelope municacional para talleres y reuniones del FIP-BM PE-PNCB-29165-GO-RFQ / Ad Request for Quota Single Stage - One E TF / A4636 Post Limited 4,727.00 0.00 Canceled 2017-10-03 2017-10-16 2017-10-20 quisición de 02 laptops tions nvelope Page 1 PE-PNCB-A.3.5-GO-RFQ / Adq uisición de equipos: (i) camar Project Management, Monito Request for Quota Single Stage - One E TF / A8849 Post Open - National 3,031.00 0.00 Canceled 2020-12-14 2020-12-28 2021-01-27 a filmadora y camara fotogra ring and Evaluation tions nvelope fica, (ii) proyector y ecran PE-PNCB-GEN.ENERGIA.2021 -ABC-GO-RFQ / Generadores Institutional Strengthening f Request for Quota Single Stage - One E TF / A8849 Post Open - National 17,000.00 2,617.14 Completed 2021-07-29 2021-10-03 2021-08-12 2022-04-15 2021-09-11 2022-05-08 eléctricos y paneles solares d or Forest Conservation tions nvelope e recarga de energía PE-PNCB-EQUIP.CAMPO.2021 -AB-GO-RFQ / Equipos y herr amientas de trabajo de camp Institutional Strengthening f Request for Quota Single Stage - One E o: Carpas y bolsas de dormir, TF / A8849 Post Open - National 16,500.00 2,245.59 Terminated 2021-08-19 2021-09-29 2021-09-02 2022-05-03 2021-10-02 or Forest Conservation tions nvelope ropas impermeables, botas, machetes, brújulas, limas, ca ntimploras, mochilas de cam paña. PE-PNCB-C.10-GO-RFQ / Adq Project Management, Monito Request for Quota Single Stage - One E TF / A8849 Post Limited 8,333.00 0.00 Canceled 2020-07-08 2020-07-25 2020-08-24 uisición de Mobiliario ring and Evaluation tions nvelope PE-PNCB-B.EQUIPOS.COMUN ICACIONES-GO-RFQ / Equipo de telecomunicación con bat Institutional Strengthening f Request for Quota Single Stage - One E TF / A8849 Post Open - National 1,175.00 0.00 Canceled 2022-06-06 2022-07-20 2022-08-19 ería recargable de 25 km (wa or Forest Conservation tions nvelope lkie talkie) y Equipos de audi o y seguimiento, grabadora PE-PNCB-EQ.COMPUTO.ACCE S.2021-ABC-GO-RFQ / Compu tadoras de escritorio, laptops Project Management, Monito Single Stage - One E Pending Impl TF / A4636 Post Request for Bids Open - National 66,700.00 0.00 2022-04-30 2022-05-05 2022-06-16 2022-07-16 2022-08-20 2022-11-18 , tablets, proyectores multim ring and Evaluation nvelope ementation edia, ecran y discos (unidade s) de almacenamiento extern o PE-PNCB-HERRAMIENTAS.EQ UIPOS.CAMP-GO-RFQ / Herra mientas y equipos para traba jo de los consultores en cam Institutional Strengthening f Single Stage - One E po: Camisas, polos, pantalon TF / A8849 Post Request for Bids Open - National 52,160.00 5,121.35 Completed 2022-04-30 2021-09-16 2022-05-05 2022-06-28 2022-06-16 2021-10-21 2022-07-16 2021-10-21 2022-08-20 2021-11-26 2022-11-18 2022-03-09 or Forest Conservation nvelope es, chalecos, mochilas, carpa s, botas, linternas, brújulas, b olsas de dormir, binoculares, machetes, colchonetas, capa s impermeables, botiquín, ca scos. PE-PNCB-INDUMENTARIA.CA MPO-GO-RFQ / Indumentaria Institutional Strengthening f Request for Quota Single Stage - One E TF / A8849 Post Open - National 7,539.00 0.00 Completed 2022-07-16 2022-09-07 2022-08-20 2022-09-19 2022-12-04 para trabajo del personal en l or Forest Conservation tions nvelope as comunidades nativas PE-PNCB-C.17.2-GO-DIR / Lic Institutional Strengthening f encias ARC GIS, extensiones TF / A8849 Post Direct Selection Direct 65,152.00 0.00 Canceled 2020-12-11 2020-12-30 2020-12-16 2020-12-28 2021-02-26 or Forest Conservation y capacitación PE-PNCB-B.4.1.1.5-GO-RFQ / Institutional Strengthening f Request for Quota Single Stage - One E TF / A8849 Post Open - National 1,000.00 0.00 Canceled 2021-06-21 2021-08-16 2021-09-15 Discos externos (4 terabyte) or Forest Conservation tions nvelope PE-PNCB-B.4.3.4.4-GO-RFQ / Institutional Strengthening f Request for Quota Single Stage - One E TF / A8849 Post Open - National 6,000.00 0.00 Canceled 2021-09-04 2021-10-30 2021-11-29 Equipos de comunicación (sis or Forest Conservation tions nvelope tema) PE-PNCB-B.4.3.4.6-GO-RFQ / Institutional Strengthening f Request for Quota Single Stage - One E TF / A8849 Post Open - National 1,800.00 0.00 Canceled 2021-07-03 2021-08-28 2021-09-27 Calculadoras or Forest Conservation tions nvelope PE-PNCB-B.4.3.4.10-GO-RFQ Institutional Strengthening f Request for Quota Single Stage - One E TF / A8849 Post Open - National 1,000.00 0.00 Canceled 2021-07-29 2021-08-12 2021-09-11 / Winchas (grandes y pequeñ or Forest Conservation tions nvelope as). PE-PNCB-309472-GO-RFQ-E.I NFORMATICOS / ADQUISICIÓ Institutional Strengthening f Request for Quota Single Stage - One E TF / A8849 Post Open - National 41,837.83 0.00 Signed 2022-08-22 2022-08-25 2022-09-26 2022-10-16 N DE EQUIPOS INFORMÁTICO or Forest Conservation tions nvelope S DEL PIP 02 FIP/BM PE-PNCB-316298-GO-RFQ / A DQUISICIÓN DE EQUIPOS DE TECNOLOGÍA PARA EL FORTA Institutional Strengthening f Request for Quota Single Stage - One E TF / A8849 Post Open - National 43,743.20 0.00 Canceled 2022-09-26 2022-10-14 2022-11-03 LECIMIENTO DEL SISTEMA DE or Forest Conservation tions nvelope CONTROL Y VIGILANCIA DE L OS BOSQUES EN EL MARCO DEL PIP 02 FIP/BM PE-PNCB-A.3.5.5-GO-RFQ / E Project Management, Monito Request for Quota Single Stage - One E quipos de geo posicionamien TF / A8849 Post Limited 19,697.00 0.00 Canceled 2020-12-16 2020-12-30 2021-02-28 ring and Evaluation tions nvelope to para los trabajos de camp o PE-PNCB-CAM.GPS.2021-AB- GO-RFQ / Cámaras fotográfic Institutional Strengthening f Request for Quota Single Stage - One E TF / A8849 Post Open - National 31,100.00 0.00 Canceled 2021-08-19 2021-09-02 2021-10-02 as, trípodes y accesorios y Eq or Forest Conservation tions nvelope uipos de georreferenciación ( GPS) PE-PNCB-C.8.2.2.2-GO-RFQ / Institutional Strengthening f Request for Quota Single Stage - One E TF / A8849 Post Open - National 1,000.00 0.00 Canceled 2021-05-01 2021-06-15 2021-07-01 Ventilador de techo or Forest Conservation tions nvelope PE-PNCB-DRON.2021-B-GO- Strengthening Sustainable F Request for Quota Single Stage - One E TF / A8849 Post Open - National 25,000.00 0.00 Canceled 2021-07-25 2021-09-19 2021-10-19 RFQ / Drones orest Landscape Manageme tions nvelope nt and Use PE-PNCB-322978-GO-RFQ / A DQUISICIÓN DE BOLSA DE D Project Management, Monito TF / A8849 Post Direct Selection Direct - National 2,985.14 0.00 Completed 2022-10-21 2022-11-29 2022-10-24 2022-11-29 2022-10-27 2022-11-01 2023-01-09 ORMIR, COLCHONETA, CARP ring and Evaluation A Y MOCHILA PARA EL PERSO NAL DEL FIP/BM PE-PNCB-EQUIPAMIENTO.TR Institutional Strengthening f Single Stage - One E AB.CAMPO-GO-RFQ / Equipa TF / A8849 Post Request for Bids Open - National 75,569.00 0.00 Canceled 2022-07-11 2022-07-16 2022-07-31 2022-08-05 2022-08-15 2022-09-14 or Forest Conservation nvelope miento para trabajo en camp o PE-PNCB-335360-GO-RFQ- 3. Project Management, Monito Request for Quota Single Stage - One E Pending Impl TF / A8849 Post Open - National 12,563.00 0.00 2023-08-22 2023-09-05 2023-10-05 2.2.1.1 / Adquisición de Mobil ring and Evaluation tions nvelope ementation iario PE-PNCB-335364-GO-RFQ- P Project Management, Monito Request for Quota Single Stage - One E OA 3.2.2.1.2 / Adquisición de TF / A8849 Post Open - National 2,010.00 0.00 Canceled 2023-08-01 2023-08-21 2023-09-10 ring and Evaluation tions nvelope Útiles de oficina PE-PNCB-335381-GO-RFQ- P Project Management, Monito Request for Quota Single Stage - One E Pending Impl OA 3.2.4.1.9 / Adquisición de TF / A8849 Post Open - National 3,015.00 0.00 2023-01-18 2023-01-29 2023-12-25 ring and Evaluation tions nvelope ementation Combustible para lancha- Ata laya Page 2 PE-PNCB-335397-GO-RFQ / E Institutional Strengthening f Request for Quota Single Stage - One E Pending Impl TF / A8849 Post Open - National 49,874.00 0.00 2023-05-12 2023-06-12 2023-10-10 quipos de tecnología or Forest Conservation tions nvelope ementation PE-PNCB-335400-GO-RFQ / A Strengthening Sustainable F Request for Quota Single Stage - One E Pending Impl dquisición de equipos de ca TF / A8845 orest Landscape Manageme Post Open - National 8,794.00 0.00 2023-06-06 2023-06-20 2023-08-19 tions nvelope ementation mpo- indumentaria para el p nt and Use ersonal PE-PNCB-335404-GO-RFQ / Institutional Strengthening f Request for Quota Single Stage - One E Pending Impl TF / A8849 Post Open - National 45,515.00 0.00 2023-06-04 2023-06-25 2023-10-23 Materiales y herramientas or Forest Conservation tions nvelope ementation PE-PNCB-335408-GO-RFQ- P Institutional Strengthening f Request for Quota Single Stage - One E Pending Impl TF / A8849 Post Open - National 23,116.00 0.00 2023-06-09 2023-06-24 2023-07-24 OA 1.2.3.1.2 / Equipos de tra or Forest Conservation tions nvelope ementation nsporte PE-PNCB-364718-GO-DIR / A Project Management, Monito Pending Impl dquisición de Útiles de oficin TF / A8849 Post Direct Selection Direct - National 753.77 0.00 2023-05-31 2023-06-01 2023-06-06 2023-06-12 ring and Evaluation ementation a para el Equipo Técnico de Atalaya NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PE-PNCB-C.19-NC-RFQ / Serv Project Management, Monito Request for Quota Single Stage - One E icios de acondicionamiento y TF / A8849 Post Limited 6,424.00 0.00 Canceled 2020-07-05 2020-07-26 2020-12-31 ring and Evaluation tions nvelope mantenimiento de la oficina PE-PNCB-29186-NC-DIR / Otr Project Management, Monito Request for Quota Single Stage - One E TF / A8849 Post Limited 1,808.00 549.21 Completed 2020-10-09 2020-05-08 2020-10-28 2020-05-22 2020-12-22 2020-05-26 os, impresiones, fotocopias y ring and Evaluation tions nvelope anillados PE-PNCB-29184-NC-DIR / Pas Project Management, Monito Request for Quota Single Stage - One E TF / A8849 Post Limited 5,455.00 0.00 Canceled 2017-10-25 2017-10-25 2018-01-23 ajes Aéreos ring and Evaluation tions nvelope PE-PNCB-A.3.2-NC-RFQ / Adq Project Management, Monito Request for Quota Single Stage - One E TF / A8849 Post Open - National 23,970.00 18,739.37 Completed 2020-10-17 2021-04-20 2020-11-01 2020-12-20 2021-12-31 2022-01-11 uisición de pasajes aéreos ring and Evaluation tions nvelope PE-PNCB-C.14-NC-DIR / Servi Project Management, Monito TF / A8849 Post Direct Selection Direct 36,364.00 16,847.36 Signed 2020-10-19 2021-10-22 2020-10-26 2020-10-23 2020-11-10 2020-10-28 2021-12-31 cio de Alquiler de Local en At ring and Evaluation alaya PE-PNCB-B.4.1.2-NC-RFQ / C apacitación en tecnologías y herramientas para el control Strengthening Sustainable F Request for Quota Single Stage - One E y vigilancia y sensibilización TF / A8849 orest Landscape Manageme Post Open - National 5,000.00 0.00 Canceled 2021-07-10 2021-09-04 2021-10-04 tions nvelope a la población colindante de l nt and Use a RCS sobre la conservación de bosques y la importancia para los medios de vida local . PE-PNCB-B.4.2.2-NC-RFQ / D esarrollo de programas de ca pacitación en el uso de herra Institutional Strengthening f Request for Quota Single Stage - One E TF / A8849 Post Open - National 24,000.00 0.00 Canceled 2021-06-13 2021-08-08 2021-11-06 mientas tecnológicas para m or Forest Conservation tions nvelope onitoreo y vigilancia (4 CAPA CITADORES POR 4 MESES + TRANSPORTE+ MATERIALES) PE-PNCB-A.3.4.1-NC-RFQ / S Institutional Strengthening f Request for Quota Single Stage - One E ervicio de talleres para la ge TF / A8849 Post Open - National 15,000.00 5,331.13 Completed 2021-04-03 2021-09-28 2021-05-29 2021-09-18 2021-08-27 2021-10-01 or Forest Conservation tions nvelope stión ambiental en Atalaya PE-PNCB-A.3.4.2-NC-RFQ / S Institutional Strengthening f Request for Quota Single Stage - One E ervicio de talleres para la ge TF / A8849 Post Open - National 10,000.00 10,422.89 Completed 2021-04-05 2021-10-03 2021-05-31 2021-11-29 2021-06-30 2022-01-01 or Forest Conservation tions nvelope stión ambiental en Pucallpa PE-PNCB-B.4.2.3-NC-RFQ / Li cenciamiento de operadores Institutional Strengthening f Request for Quota Single Stage - One E de drones (integrante del co TF / A8849 Post Open - National 3,000.00 0.00 Canceled 2021-09-11 2021-11-06 2021-12-06 or Forest Conservation tions nvelope mité de vigilancia)(curso-tras lados-viaticos-derecho) PE-PNCB-B.4.3.1-NC-RFQ / T alleres de capacitación para Institutional Strengthening f Request for Quota Single Stage - One E el monitoreo y control de la d TF / A8849 Post Open - National 3,000.00 0.00 Canceled 2021-07-03 2021-08-28 2021-09-27 or Forest Conservation tions nvelope eforestación (uso de tecnolo gía, coordinación interinstitu cional, otros) PE-PNCB-C.8.2.1-NC-RFQ / A Institutional Strengthening f Request for Quota Single Stage - One E condicionamiento de local d TF / A8849 Post Open - National 1,800.00 2,006.47 Completed 2021-05-01 2021-09-28 2021-06-26 2021-08-21 2021-07-26 2021-08-27 or Forest Conservation tions nvelope e Atalaya (cableado entre otr os) PE-PNCB-B.3.5-NC-RFQ / For Strengthening Sustainable F Request for Quota Single Stage - One E TF / A8845 Post Open - National 10,000.00 0.00 Canceled 2021-05-29 2021-07-24 2022-01-20 malización de juntas directiv orest Landscape Manageme tions nvelope as nt and Use PE-PNCB-B.1.2.3.2.3-NC-RFQ / Operador logístico para Tall Institutional Strengthening f Request for Quota Single Stage - One E TF / A8849 Post Open - National 9,900.00 0.00 Canceled 2022-05-05 2022-06-30 2022-07-30 er de diseño de la estrategia or Forest Conservation tions nvelope de monitoreo y vigilancia de cobertura del bosque PE-PNCB-B.1.2.3.3.2-NC-RFQ / Operador logístico para rea Institutional Strengthening f Request for Quota Single Stage - One E TF / A8849 Post Open - National 5,600.00 0.00 Canceled 2022-05-05 2022-06-30 2022-07-30 ctivación de la asociación de or Forest Conservation tions nvelope concesionarios forestales de atalaya PE-PNCB-B.1.2.3.4.3-NC-RFQ / Operador logístico para Fort Institutional Strengthening f Request for Quota Single Stage - One E alecimiento de capacidades TF / A8849 Post Open - National 3,400.00 0.00 Canceled 2022-05-06 2022-07-01 2022-07-31 or Forest Conservation tions nvelope de entidades públicas para el monitoreo y control de la def orestación PE-PNCB-A.4.4-NC-RFQ / Ser vicio de operador logístico (tr ansporte, alojamiento y alim entación) para los salvaguar Project Management, Monito Request for Quota Single Stage - One E TF / A8849 Post Open - National 6,000.00 0.00 Canceled 2022-05-06 2022-05-21 2022-12-27 das presten la asistencia téc ring and Evaluation tions nvelope nica y seguimiento a la imple mentación del MGAS y del m ecanismo de resolución de co nflictos a empresas consultor as. Page 3 PE-PNCB-A.4.8-NC-RFQ / Ser vicio de operador logístico pa Project Management, Monito Request for Quota Single Stage - One E ra el fortalecimiento de capa TF / A8849 Post Open - National 7,500.00 0.00 Canceled 2022-07-25 2022-08-09 2022-12-22 ring and Evaluation tions nvelope cidades en el marco de gesti ón forestal con actores del pr oyecto PE-PNCB-B.1.1.1.2.1-NC-RFQ / Servicio de operador logísti co (TRANSPORTE TERRESTRE Institutional Strengthening f Request for Quota Single Stage - One E Y FLUVIAL) para la realizació TF / A8849 Post Open - National 15,000.00 0.00 Canceled 2022-07-25 2022-08-12 2022-12-25 or Forest Conservation tions nvelope n de asambleas con las comu nidades nativas priorizadas p ara definir amplio apoyo al pr oyecto y participación en el P IP 02 PE-PNCB-C.2.6-NC-RFQ / Ser Project Management, Monito Request for Quota Single Stage - One E TF / A8849 Post Open - National 2,250.00 0.00 Canceled 2022-06-06 2022-06-24 2022-12-30 vicios de limpieza, seguridad ring and Evaluation tions nvelope y vigilancia PE-PNCB-SERVICIO.IMPRESIO Institutional Strengthening f Request for Quota Single Stage - One E N-NC-RFQ / Servicio de impre TF / A8849 Post Open - National 7,500.00 0.00 Terminated 2022-03-06 2022-06-27 2022-03-31 2022-07-05 2022-12-26 or Forest Conservation tions nvelope sión de documentos varios y planos PE-PNCB-PASAJES.AEREOS-N C-RFQ / Agenciamiento de pa Institutional Strengthening f Request for Quota Single Stage - One E TF / A8849 Post Open - National 14,250.00 5,053.95 Completed 2022-03-06 2022-05-29 2022-03-21 2022-05-20 2024-02-19 2023-01-11 sajes aéreos para la gestión or Forest Conservation tions nvelope ambiental y actividades de s upervisión PE-PNCB-TRANSPORTE.FLUVI Institutional Strengthening f Single Stage - One E AL.TERRES-NC-RFQ / Transpo TF / A8849 Post Request for Bids Open - National 52,600.00 0.00 Terminated 2022-04-30 2022-05-03 2022-05-05 2022-05-30 2022-06-16 2022-05-27 2022-07-16 2022-05-27 2022-08-20 2022-09-24 2022-11-28 or Forest Conservation nvelope rte terrestre y fluvial PE-PNCB-B.1.2.3.2.7-NC-RFQ / Operador logístico para cap Institutional Strengthening f Single Stage - One E TF / A8849 Post Request for Bids Open - National 56,419.00 0.00 Canceled 2022-04-30 2022-05-05 2022-06-16 2022-07-16 2022-08-20 2022-11-18 acitación en gestión de bosq or Forest Conservation nvelope ues, legislación y delitos amb ientales PE-PNCB-GASTOS.NOTARIAL Project Management, Monito Request for Quota Single Stage - One E TF / A8849 Post Open - National 2,500.00 2,638.35 Completed 2022-06-05 2022-06-30 2022-07-31 2022-07-13 2022-11-28 2022-07-16 ES-NC-RFQ / Gastos notariale ring and Evaluation tions nvelope s. POA 3.7 PE-PNCB-B.SEGUROS-NC-RF Q / Seguro para activos, Póliz a de Seguro (Multirriesgo y R Institutional Strengthening f Request for Quota Single Stage - One E TF / A8849 Post Open - National 2,950.00 0.00 Canceled 2022-06-05 2022-06-23 2023-06-18 esponsabilidad Civil para bie or Forest Conservation tions nvelope nes) y Seguro patrimonial. P OA: 1.2.3.4.9.14, 1.2.3.4.10.1 4, 1.2.3.4.11.14 y 3.8 PE-PNCB-C.3.4.2.TRANSP.BIE NES-NC-RFQ / Servicio de tra Project Management, Monito Request for Quota Single Stage - One E TF / A8849 Post Open - National 2,703.00 0.00 Canceled 2022-06-11 2022-07-06 2022-12-03 nsporte de bienes y material ring and Evaluation tions nvelope es diversos (courier) PE-PNCB-C.3.4.3.PUBLICA.DI ARIO-NC-RFQ / Publicaciones Project Management, Monito Request for Quota Single Stage - One E de convocatorias de proceso TF / A8849 Post Open - National 2,703.00 2,244.52 Completed 2022-05-29 2022-09-09 2022-06-23 2022-10-01 2022-12-20 2023-01-09 ring and Evaluation tions nvelope s de selección en diarios de mayor circulación nacional PE-PNCB-B.1.2.3.1.16-NC-RF Q / Operador logístico para ta Institutional Strengthening f Request for Quota Single Stage - One E TF / A8849 Post Open - National 4,600.00 0.00 Canceled 2022-06-05 2022-07-31 2022-08-30 ller de intercambio de experi or Forest Conservation tions nvelope encias de control y vigilancia PE-PNCB-B.1.2.3.1.13-NC-RF Q / Operador logístico para ta Institutional Strengthening f Request for Quota Single Stage - One E TF / A8849 Post Open - National 17,952.00 0.00 Canceled 2022-05-30 2022-06-17 2022-07-17 ller de sensibilización a la po or Forest Conservation tions nvelope blación colindante PE-PNCB-B.1.2.3.1.6-NC-RFQ Institutional Strengthening f Request for Quota Single Stage - One E TF / A8849 Post Open - National 300.00 0.00 Canceled 2022-06-06 2022-06-24 2022-07-24 / Servicio de refrigerio or Forest Conservation tions nvelope PE-PNCB-B.1.2.3.1.5.1-NC-RF Institutional Strengthening f Request for Quota Single Stage - One E Q / Servicio de Internet Sateli TF / A8849 Post Open - National 1,800.00 0.00 Canceled 2022-06-06 2022-06-24 2023-06-19 or Forest Conservation tions nvelope tal (Hughesnet) PE-PNCB-C.15-NC-RFQ / Serv Project Management, Monito Request for Quota Single Stage - One E TF / A8849 Post Open - National 3,030.00 0.00 Canceled 2020-03-30 2020-04-29 2020-07-31 icios de organización de even ring and Evaluation tions nvelope tos PE-PNCB-19.6-NC-RFQ / Serv icio de transmisión remota m ultipantalla 3 para paquete d Project Management, Monito Request for Quota Single Stage - One E TF / A8849 Post Open - National 12,000.00 0.00 Canceled 2020-09-25 2020-10-02 2020-12-31 e talleres informativos virtual ring and Evaluation tions nvelope es sobre el Programa de Inve rsión Forestal del Perú (FIP P ERÚ) PE-PNCB-C.14.2-NC-DIR / Alq Project Management, Monito TF / A8849 Post Direct Selection Direct 33,334.00 0.00 Canceled 2021-01-30 2021-03-01 2021-03-29 2022-12-31 uiler de local en Lima ring and Evaluation PE-PNCB-304479-NC-DIR / S ERVICIO DE ALIMENTACIÓN P ARA TALLER DE ARTICULACI Project Management, Monito TF / A8849 Post Direct Selection Direct - National 459.46 0.00 Completed 2022-07-19 2022-07-19 2022-07-19 2022-07-19 2022-07-22 2022-07-24 2023-01-08 ÓN MULTISECTORIAL DEL PR ring and Evaluation OYECTO FIP/BM EN LA PROVI NCIA DE ATALAYA, REGIÓN U CAYALI PE-PNCB-308306-NC-RFQ- P OA 3.7 / POA 3.7- PRESENCIA Project Management, Monito Request for Quota Single Stage - One E NOTARIAL PARA ACTOS PÚBL TF / A8849 Post Limited 2,902.16 2,771.03 Completed 2022-08-08 2022-08-10 2022-08-11 2022-08-20 2022-12-31 2023-01-10 ring and Evaluation tions nvelope ICOS DE LOS PROCESOS DE SELECCIÓN DEL FIP/BM PE-PNCB-A.3.4-NC-DIR-1 / Se Project Management, Monito rvicio de operador logístico p TF / A8849 Post Direct Selection Direct 5,000.00 0.00 Canceled 2020-12-04 2020-12-09 2021-02-22 2021-03-24 ring and Evaluation ara el taller de Atalaya PE-PNCB-B.4.2.1.7-NC-RFQ / Institutional Strengthening f Request for Quota Single Stage - One E Capacitación en el uso y man TF / A8849 Post Open - National 1,500.00 0.00 Canceled 2021-09-04 2021-10-30 2021-11-29 or Forest Conservation tions nvelope ejo del dron (incluye licencia miento) PE-PNCB-A.3.4.3-NC-RFQ / S Institutional Strengthening f Request for Quota Single Stage - One E ervicio de talleres para la ge TF / A8849 Post Open - National 10,000.00 0.00 Canceled 2021-09-28 2021-11-23 2021-12-23 or Forest Conservation tions nvelope stión ambiental en Lima Page 4 PE-PNCB-LAB-COVID19-2021 -NC-RFQ / Servicio de realiza ción de pruebas para descart Project Management, Monito Request for Quota Single Stage - One E e de COVID-19 (antígenos) p TF / A8849 Post Open - National 4,000.00 0.00 Canceled 2021-08-28 2021-10-23 2022-04-21 ring and Evaluation tions nvelope ara el personal del proyecto FIP/BM cuando realice viajes a la zona de intervención del proyecto. PE-PNCB-328688-NC-DIR / Al Project Management, Monito TF / A8849 Post Direct Selection Direct - National 19,780.59 0.00 Terminated 2022-11-30 2022-11-29 2022-11-30 2022-11-29 2022-11-30 2022-12-30 quiler de local en Lima ring and Evaluation PE-PNCB-332232-NC-DIR / Al Project Management, Monito TF / A8849 Post Direct Selection Direct - National 42,182.10 0.00 Completed 2022-12-16 2022-12-16 2022-12-16 2022-12-16 2022-12-31 2023-02-28 2023-03-11 quiler local en Lima ring and Evaluation PE-PNCB-335340-NC-RFQ / I Strengthening Sustainable F Request for Quota Single Stage - One E TF / A8845 Post Open - National 3,518.00 0.00 Canceled 2023-01-16 2023-01-31 2023-12-27 mpresión de planos y docum orest Landscape Manageme tions nvelope entos nt and Use PE-PNCB-335372-NC-RFQ- P Project Management, Monito Request for Quota Single Stage - One E Pending Impl OA 3.2.4.1.1 / Servicio de pu TF / A8849 Post Open - National 3,015.00 0.00 2023-01-19 2023-01-30 2023-12-29 ring and Evaluation tions nvelope ementation blicación en diarios PE-PNCB-335378-NC-RFQ- P Project Management, Monito Request for Quota Single Stage - One E Pending Impl TF / A8849 Post Open - National 3,769.00 0.00 2023-02-21 2023-03-04 2023-12-29 OA 3.2.4.1.4 / Servicios notar ring and Evaluation tions nvelope ementation iales PE-PNCB-335379-NC-RFQ- P Project Management, Monito Request for Quota Single Stage - One E Pending Impl OA 3.2.4.1.8 / Servicio de con TF / A8849 Post Open - National 4,146.00 0.00 2023-01-17 2023-01-30 2023-12-26 ring and Evaluation tions nvelope ementation ductor de embarcación PE-PNCB-335405-NC-RFQ- P Project Management, Monito Request for Quota Single Stage - One E Pending Impl OA 3.2.4.1.7 / Servicios de se TF / A8849 Post Open - National 4,146.00 0.00 2023-01-18 2023-03-02 2024-01-26 ring and Evaluation tions nvelope ementation guridad y vigilancia Atalaya PE-PNCB-341431-NC-RFQ- P Institutional Strengthening f Request for Quota Single Stage - One E OA 2.1.4.1.1 / SERVICIO DE A TF / A8849 Post Open - National 34,828.53 0.00 Signed 2023-02-18 2023-03-29 2023-03-21 2024-08-31 or Forest Conservation tions nvelope GENCIAMIENTO DE PASAJES AÉREOS CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PE-PNCB-29181-CS-INDV / A Quality And Cost- TF / A4636 Post Open - National 28,000.00 0.00 Canceled 2017-12-07 2017-12-14 2017-12-28 2018-01-05 2018-01-11 2018-01-19 2018-01-26 2018-04-16 uditoria Based Selection PE-PNCB-A.4-CS-CQS / Contr atación del servicio de audito Project Management, Monito Quality And Cost- ria del FIP/BM por los ejercici TF / A8849 Post Open - National 200,000.00 88,056.79 Signed 2020-07-13 2021-03-19 2020-07-28 2021-09-16 2020-08-07 2021-07-07 2020-09-04 2021-07-26 2020-09-19 2021-07-30 2020-10-08 2021-08-23 2020-11-06 2021-10-18 2024-08-30 ring and Evaluation Based Selection os económicos dentro del per iodo 2019 hasta 2024 PE-PNCB-A.1-CS-QBS / Elabo Project Management, Monito Quality Based Sel ración del Estudio Definitivo TF / A8849 Post Open - National 333,333.00 292,786.80 Completed 2020-02-28 2020-05-20 2020-03-14 2021-04-23 2020-03-24 2020-06-29 2020-04-21 2020-09-11 2020-04-26 2020-11-05 2020-05-01 2020-11-16 2020-05-30 2021-03-15 2020-11-26 2022-03-09 ring and Evaluation ection y Linea de Base del Proyecto PE-PNCB-B.1.1.5.1-CS-QCBS / - Contratación de servicio p ara actividades de demarcaci ón de comunidades nativas, Strengthening Sustainable F apoyo logístico y servicio de Quality And Cost- TF / A8849 orest Landscape Manageme Post Open - National 290,000.00 0.00 Canceled 2021-04-30 2021-05-21 2021-07-04 2021-08-01 2021-08-31 2021-10-05 2021-11-09 2022-11-09 diagnóstico - DIAGNOSTICO y Based Selection nt and Use DEMARCACIÓN. - Servicio para reconocimient o (02 CCNN en 03 meses). -Servicio para ampliación y ti tulación. PE-PNCB-B.1.1.5.2-CS-QCBS / Servicio para actividades de Strengthening Sustainable F Quality And Cost- demarcación de comunidade TF / A8849 orest Landscape Manageme Post Open - National 140,000.00 0.00 Canceled 2021-06-01 2021-06-22 2021-08-05 2021-09-02 2021-10-02 2021-11-06 2021-12-11 2022-07-09 Based Selection s nativas, apoyo logístico y s nt and Use ervicio de diagnóstico - DEM ARCACIÓN PE-PNCB-B.3.1.1-CS-QCBS / Strengthening Sustainable F Quality Based Sel Servicio para elaboración de TF / A8849 orest Landscape Manageme Post Open - National 185,000.00 0.00 Canceled 2021-05-31 2021-06-21 2021-08-04 2021-09-01 2021-10-01 2021-10-31 2021-12-05 2022-05-04 ection planes de vida y asistencia té nt and Use cnica PE-PNCB-B.3.1.1-CS-CQS / C Institutional Strengthening f Consultant Qualifi ontratación de servicio para TF / A8849 Post Limited 127,273.00 0.00 Canceled 2020-04-13 2020-05-05 2020-05-10 2020-06-08 2020-12-25 or Forest Conservation cation Selection elaboración de planes de vid a PE-PNCB-B.1.1.5.1.SAN.FIS.L EGAL.-CS-QCBS / Servicio de Strengthening Sustainable F consultoría para el saneamie Quality And Cost- TF / A8849 orest Landscape Manageme Post Open - National 800,000.00 0.00 Signed 2021-11-30 2022-03-24 2022-03-30 2022-03-16 2022-04-29 2022-05-13 2022-05-27 2022-06-17 2022-06-20 2022-07-05 2022-07-15 2022-08-17 2022-08-19 2023-08-19 nto físico legal de comunidad Based Selection nt and Use es nativas (reconocimiento, t itulación, ampliación y georr eferenciación) PE-PNCB-B.1.2.2.1.4-CS-QCB S / Contratación de empresa Institutional Strengthening f Quality And Cost- TF / A8849 Post Open - National 368,373.00 0.00 Canceled 2022-04-01 2022-04-22 2022-06-05 2022-07-03 2022-08-02 2022-09-06 2022-10-11 2023-11-15 consultora para elaboración or Forest Conservation Based Selection de planes de vida PE-PNCB-B.2.1.1.3.1-CS-QCB S / Servicio de Consultoría pa Institutional Strengthening f Quality And Cost- ra el Fortalecimiento de capa TF / A8845 Post Open - National 31,550.00 0.00 Canceled 2022-03-01 2022-03-16 2022-04-05 2022-04-15 2022-04-25 2022-05-30 2022-06-29 2022-08-28 or Forest Conservation Based Selection cidades para elaboración de l as ideas de negocios PE-PNCB-B.2.1.1.4.1-CS-QCB S / Servicio de Consultoría Fo Institutional Strengthening f Quality And Cost- rtalecimiento de capacidades TF / A8845 Post Open - National 60,942.00 0.00 Canceled 2022-04-27 2022-05-12 2022-06-01 2022-06-11 2022-06-21 2022-07-26 2022-08-10 2022-11-08 or Forest Conservation Based Selection para la formulación de plane s de negocios - Talleres PE-PNCB-B.2.1.2.1.1-CS-QCB S / Servicio de Consultoría pa Institutional Strengthening f Quality And Cost- TF / A8845 Post Open - National 50,250.00 0.00 Canceled 2022-06-15 2022-06-30 2022-07-20 2022-07-30 2022-08-09 2022-09-13 2022-09-28 2022-12-27 ra Evaluación de planes de n or Forest Conservation Based Selection egocios presentados Page 5 PE-PNCB-B.2.1.3.6.1-CS-QCB S / Servicio de Consultoría pa Institutional Strengthening f Quality And Cost- TF / A8845 Post Open - National 95,650.00 0.00 Canceled 2022-04-01 2022-04-11 2022-05-01 2022-05-11 2022-05-21 2022-06-05 2022-06-20 2022-09-18 ra Diseño del curso para la g or Forest Conservation Based Selection estión de negocios sostenible s PE-PNCB-B.2.1.4.1.3-CS-QCB S / Servicio de Consultoría pa Institutional Strengthening f Quality And Cost- ra la Implementación del cur TF / A8845 Post Open - National 54,875.00 0.00 Canceled 2022-06-01 2022-06-11 2022-07-01 2022-07-11 2022-07-21 2022-08-05 2022-08-20 2022-11-18 or Forest Conservation Based Selection so de fortalecimiento de cap acidades para la gestión de n egocios sostenibles PE-PNCB-B.2.1.4.2.1-CS-QCB S / Consultoría para curso de Institutional Strengthening f Quality And Cost- fortalecimiento de capacidad TF / A8845 Post Open - National 44,527.00 0.00 Canceled 2022-08-08 2022-08-18 2022-09-07 2022-09-17 2022-09-27 2022-10-12 2022-10-27 2022-12-26 or Forest Conservation Based Selection es para el aprovechamiento s ostenible de recursos forestal es maderables PE-PNCB-2.1-EVAL-PLAN-NE GOCIO-CS-QCBS / Consultoría Strengthening Sustainable F Quality And Cost- para el fortalecimiento de ca TF / A8845 orest Landscape Manageme Post Open - National 254,537.00 0.00 Canceled 2022-04-15 2022-04-20 2022-04-24 2022-05-24 2022-06-21 2022-07-15 2022-08-09 2022-09-13 2022-12-12 Based Selection pacidades para elaboración y nt and Use evaluación de planes de neg ocios sostenibles PE-PNCB-B.1.1.1.2.2-CS-QCB S / Servicio de consultoría pa ra el saneamiento físico legal Institutional Strengthening f Quality And Cost- de comunidades nativas para TF / A8849 Post Open - National 746,552.00 0.00 Canceled 2022-05-01 2022-05-22 2022-07-05 2022-08-02 2022-09-01 2022-10-06 2022-11-10 2023-12-15 or Forest Conservation Based Selection el reconocimiento, titulación, ampliación y georreferenciac ión de 26 comunidades nativ as PE-PNCB-2.1.FORT.PLAN.NE GOCIO-CS-QCBS / Fortalecimi Strengthening Sustainable F ento de capacidades técnicas Quality And Cost- TF / A8845 orest Landscape Manageme Post Open - National 698,132.00 0.00 Signed 2022-06-30 2022-06-16 2022-07-09 2022-06-17 2022-08-08 2022-07-08 2022-09-05 2022-08-12 2022-09-20 2022-08-26 2022-10-10 2022-09-15 2022-11-03 2023-08-05 , organizativas, empresariale Based Selection nt and Use s y comerciales para los neg ocios sostenibles en el ámbit o del PIP 02 del FIP/BM PE-PNCB-1.2.3.1.VIGILANCIA. ELSIRA-CS-CQS / Servicio de Strengthening Sustainable F consultoría para el fortalecim Consultant Qualifi TF / A8849 orest Landscape Manageme Post Open - National 94,507.00 0.00 Canceled 2022-06-27 2022-06-27 2022-07-18 2022-09-23 2022-08-31 2022-10-17 2022-09-30 2022-12-21 2022-11-04 2023-06-02 iento del sistema de control cation Selection nt and Use y vigilancia en el entorno de l a reserva comunal El Sira en el ámbito del PIP 02. PE-PNCB-B.1.1.1-CS-CQS / C Institutional Strengthening f Consultant Qualifi ontratación de servicio para t TF / A8849 Post Limited 42,368.00 0.00 Canceled 2020-04-13 2020-05-03 2020-05-08 2020-06-06 2020-12-13 or Forest Conservation cation Selection oma de datos de campo para diagnostico PE-PNCB-B.1.1.2-CS-CQS / C Institutional Strengthening f Consultant Qualifi ontratación de servicio para t TF / A8849 Post Limited 46,004.00 0.00 Canceled 2020-04-13 2020-05-05 2020-05-10 2020-06-08 2020-12-15 or Forest Conservation cation Selection rabajo de gabinete con el Go bierno Regional PE-PNCB-B.1.1.3-CS-CQS / C Institutional Strengthening f Consultant Qualifi ontratación de consultoria pa TF / A8849 Post Limited 46,004.00 0.00 Canceled 2020-04-13 2020-05-05 2020-05-10 2020-06-08 2020-12-15 or Forest Conservation cation Selection ra apoyo logístico PE-PNCB-B.5.1-CS-QCBS / Se rvicio de consultoría consiste Strengthening Sustainable F nte en el diseño de la metod Quality And Cost- TF / A8845 orest Landscape Manageme Post Open - National 25,000.00 0.00 Canceled 2021-11-30 2021-10-13 2022-03-31 2022-05-14 2022-06-11 2022-07-11 2022-08-15 2022-09-19 2023-09-19 ología a ser empleada en los Based Selection nt and Use talleres de capacitación para la elaboración de planes de n egocio (dos módulos) PE-PNCB-B.4.1-CS-QCBS / Se Strengthening Sustainable F rvicio de consultoría en la ev Quality And Cost- TF / A8845 orest Landscape Manageme Post Open - National 60,000.00 0.00 Canceled 2021-11-30 2021-10-13 2022-03-31 2022-05-14 2022-06-11 2022-07-11 2022-08-15 2022-09-19 2023-09-19 aluación de planes de negoci Based Selection nt and Use o. (60 planes de negocio eval uados) PE-PNCB-B.3.1.1-2022-CS-Q Strengthening Sustainable F Quality And Cost- CBS / Servicio para elaboraci TF / A8849 orest Landscape Manageme Post Open - National 185,000.00 0.00 Canceled 2021-11-30 2021-10-19 2022-03-31 2022-05-14 2022-06-11 2022-07-11 2022-08-15 2022-09-19 2023-09-19 Based Selection ón de planes de vida y asiste nt and Use ncia técnica PE-PNCB-335383-CS-QCBS- Project Management, Monito Quality And Cost- Pending Impleme POA 3.3.1.1.1 / Consultoría d TF / A8849 Post Open - National 25,126.00 0.00 2023-04-14 2023-04-21 2023-05-08 2023-05-18 2023-05-28 2023-05-30 2023-06-07 2023-09-05 ring and Evaluation Based Selection ntation e evaluación intermedia y fin al INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PE-PNCB-127087-CS-INDV / Project Management, Monito Individual Consult TF / A8849 Post Open 256,060.61 8,743.81 Completed 2019-09-08 2020-03-03 2019-09-30 2020-03-04 2019-10-03 2020-04-15 2019-10-15 2020-04-18 2025-02-15 2021-01-08 COORDINADOR DEL PROYEC ring and Evaluation ant Selection TO PE-PNCB-127088-CS-INDV / Project Management, Monito Individual Consult TF / A8849 Post Open 88,636.63 32,780.87 Signed 2019-09-08 2019-12-09 2019-09-30 2020-01-14 2019-10-03 2020-04-02 2019-10-15 2020-04-10 2025-02-15 ASISTENTE ADMINISTRATIVO ring and Evaluation ant Selection PE-PNCB-127089-CS-INDV / Project Management, Monito Individual Consult TF / A8849 Post Open 196,969.70 35,326.05 Terminated 2019-09-08 2019-09-17 2019-09-30 2019-10-31 2019-10-03 2019-11-13 2019-10-15 2019-12-03 2025-02-15 ESPECIALISTA EN ADQUISICI ring and Evaluation ant Selection ONES PE-PNCB-127090-CS-INDV / Project Management, Monito Individual Consult TF / A8849 Post Open 177,272.73 59,005.57 Completed 2019-09-08 2019-12-09 2019-09-30 2019-12-12 2019-10-03 2020-04-02 2019-10-15 2020-04-10 2025-02-15 2022-05-21 ESPECIALISTA FINANCIERO ring and Evaluation ant Selection PE-PNCB-127091-CS-INDV / Project Management, Monito Individual Consult ESPECIALISTA EN CONTABILI TF / A8849 Post Open 136,363.64 49,244.16 Completed 2019-09-08 2019-12-09 2019-09-30 2020-01-14 2019-10-03 2020-01-20 2019-10-15 2020-04-10 2024-09-18 2023-01-09 ring and Evaluation ant Selection DAD Y TESORERIA PE-PNCB-A.3.7-CS-INDV / Co Project Management, Monito Individual Consult TF / A8849 Prior Direct 9,091.00 0.00 Canceled 2020-05-20 2020-06-06 2020-06-11 2020-06-26 2020-12-31 ntratación de especialista ind ring and Evaluation ant Selection ígena PE-PNCB-B.1.2-CS-INDV / Co Institutional Strengthening f Individual Consult nsultoría individual para resp TF / A8849 Post Limited 29,091.00 0.00 Canceled 2020-04-06 2020-04-13 2020-04-18 2020-04-30 2020-05-24 or Forest Conservation ant Selection onsable de demarcación terri torial PE-PNCB-B.1.3-CS-INDV / Co Institutional Strengthening f Individual Consult nsultoría individual para asist TF / A8849 Post Limited 16,970.00 0.00 Canceled 2020-05-04 2020-05-11 2020-05-16 2020-05-31 2020-12-31 or Forest Conservation ant Selection ente técnico Page 6 PE-PNCB-B.2.1-CS-INDV / Co ntratación del servicio de con Institutional Strengthening f Individual Consult sultoria para diseño y actuali TF / A8849 Post Limited 15,394.00 0.00 Canceled 2020-08-03 2020-08-03 2020-08-10 2020-08-15 2020-08-30 2020-11-28 or Forest Conservation ant Selection zación del Diagnostico y Age nda Ambiental Regional de la s CAR PE-PNCB-C.4-CS-INDV / Espe Project Management, Monito Individual Consult cialista en Salvaguarda Socio TF / A8849 Post Limited 147,273.00 14,960.52 Completed 2020-03-05 2020-05-07 2020-03-10 2020-05-08 2020-03-15 2020-06-30 2020-03-27 2020-07-01 2020-12-31 2020-12-01 ring and Evaluation ant Selection -ambiental PE-PNCB-C.7-CS-INDV / Enla Project Management, Monito Individual Consult TF / A8849 Post Limited 144,545.00 0.00 Canceled 2020-04-06 2020-04-11 2020-04-16 2020-04-28 2020-12-31 ce Zonal ring and Evaluation ant Selection PE-PNCB-C.18.1-CS-INDV / C Project Management, Monito Individual Consult onsultoría individual para det TF / A8849 Post Limited 7,273.00 6,499.57 Completed 2020-05-25 2020-05-29 2020-05-28 2020-05-29 2020-05-31 2020-06-05 2020-06-06 2020-06-06 2020-07-31 2020-08-21 ring and Evaluation ant Selection erminación de áreas prioritar ias PE-PNCB-C.19.1-CS-CDS / Co nsultoría individual para la el Project Management, Monito aboración del manual de line TF / A8849 Post Direct Selection Direct 3,576.00 2,859.53 Completed 2020-06-19 2020-09-30 2020-06-22 2020-10-20 2020-07-14 2020-11-17 2020-08-23 2020-12-31 ring and Evaluation amientos gráficos del Progra ma de Inversión Forestal del Perú (FIP PERÚ) PE-PNCB-C.2-CS-INDV / Espe Project Management, Monito Individual Consult TF / A8849 Post Open 178,788.00 12,025.48 Completed 2020-07-03 2020-07-13 2020-07-16 2020-08-06 2020-07-26 2020-08-12 2020-08-07 2020-08-28 2024-08-31 2020-09-28 cialista en Adquisiciones ring and Evaluation ant Selection PE-PNCB-185357-CS-INDV / Project Management, Monito Individual Consult TF / A8849 Post Limited 9,091.00 24,019.14 Signed 2020-07-23 2020-09-27 2020-07-28 2020-10-13 2020-08-06 2020-10-20 2020-08-30 2020-11-18 2020-12-30 Contratación de especialista i ring and Evaluation ant Selection ndígena PE-PNCB-185360-CS-INDV / Project Management, Monito Individual Consult TF / A8849 Post Open 144,545.00 41,160.96 Completed 2020-07-23 2020-08-03 2020-08-02 2020-08-21 2020-08-04 2020-09-04 2020-08-10 2020-09-08 2020-12-30 2023-04-07 Enlace Zonal ring and Evaluation ant Selection PE-PNCB-185361-CS-INDV / Institutional Strengthening f Individual Consult Consultoría individual para re TF / A8849 Post Open 29,091.00 54,878.98 Terminated 2020-07-23 2020-09-27 2020-08-02 2020-10-30 2020-08-04 2020-11-04 2020-08-10 2020-11-21 2020-12-30 or Forest Conservation ant Selection sponsable de demarcación te rritorial PE-PNCB-185363-CS-INDV / Institutional Strengthening f Individual Consult Consultoría individual para a TF / A8849 Post Open 16,970.00 12,343.59 Completed 2020-07-23 2020-08-03 2020-08-03 2020-08-07 2020-08-05 2020-09-07 2020-08-11 2020-09-24 2020-12-31 2021-02-23 or Forest Conservation ant Selection sistente técnico PE-PNCB-B 2.1-CS-INDV-1 / C ontratación del servicio de co Institutional Strengthening f Individual Consult nsultoría para diseño y actua TF / A8849 Post Open 15,394.00 14,008.08 Completed 2020-09-07 2020-10-09 2020-09-17 2020-11-06 2020-09-17 2020-11-25 2020-09-25 2020-12-02 2020-12-31 2021-03-23 or Forest Conservation ant Selection lización del diagnóstico y age nda ambiental regional de la s CAR PE-PNCB-C.2-CS-INDV-2 / Es Project Management, Monito Individual Consult TF / A8849 Post Open 175,000.00 51,717.84 Terminated 2020-09-17 2020-09-21 2020-09-28 2020-10-01 2020-10-01 2021-04-12 2020-10-05 2020-10-24 2024-10-29 pecialista en Adquisiciones ring and Evaluation ant Selection PE-PNCB-19.2-CS-INDV / Asis Project Management, Monito Individual Consult tente Técnico en Adquisicion TF / A8849 Post Limited 6,520.00 34,883.15 Terminated 2020-09-22 2020-09-27 2020-09-26 2020-11-24 2020-09-28 2020-11-24 2020-10-02 2020-12-23 2020-12-31 ring and Evaluation ant Selection es y Logística PE-PNCB-19.3-CS-INDV / Arti Project Management, Monito Individual Consult TF / A8849 Post Limited 7,300.00 39,042.53 Completed 2020-09-21 2020-10-05 2020-09-26 2020-10-13 2020-09-28 2020-10-20 2020-10-02 2020-11-10 2020-12-31 2023-04-07 culador Técnico ring and Evaluation ant Selection PE-PNCB-19.4-CS-INDV / Esp Project Management, Monito Individual Consult TF / A8849 Post Open 8,200.00 44,730.83 Completed 2020-09-21 2020-10-02 2020-09-28 2020-10-29 2020-09-30 2020-11-13 2020-10-02 2020-11-17 2020-12-31 2022-07-01 ecialista Legal ring and Evaluation ant Selection PE-PNCB-19.5-CS-INDV / Esp Project Management, Monito Individual Consult TF / A8849 Post Open 8,200.00 20,164.01 Completed 2020-09-21 2020-09-27 2020-09-28 2020-10-26 2020-09-30 2021-04-12 2020-10-02 2020-11-10 2020-12-31 2021-08-01 ecialista en Comunicaciones ring and Evaluation ant Selection PE-PNCB-C.4-CS-INDV-2 / Es Project Management, Monito Individual Consult pecialista en Salvaguarda So TF / A8849 Post Limited 133,637.00 34,466.84 Completed 2020-12-11 2020-12-14 2020-12-14 2020-12-28 2020-12-15 2021-01-12 2020-12-23 2021-03-02 2024-08-31 2022-08-01 ring and Evaluation ant Selection cio Ambiental PE-PNCB-C.1-SC-INDV-2 / Co Project Management, Monito Individual Consult TF / A8849 Post Open 218,560.00 57,037.21 Completed 2020-12-28 2021-02-02 2021-01-19 2021-02-11 2021-01-22 2021-03-01 2021-02-01 2021-03-06 2025-02-15 2022-05-10 ordinador del Proyecto FIP-B ring and Evaluation ant Selection M PE-PNCB-B.1.3-CS-INDV-2 / A Strengthening Sustainable F Individual Consult TF / A8849 Post Open 80,000.00 18,893.25 Signed 2021-03-31 2021-04-27 2021-05-19 2021-07-16 2021-06-09 2021-07-26 2021-07-14 2021-09-04 2022-01-10 sistente técnico en demarcac orest Landscape Manageme ant Selection ión nt and Use PE-PNCB-B.1.1.2.1-CS-INDV / Institutional Strengthening f Individual Consult Servicio para diagnostico de TF / A8849 Post Open 7,000.00 5,622.49 Completed 2021-04-19 2021-09-14 2021-06-07 2022-03-16 2021-06-28 2022-04-06 2021-08-02 2022-05-07 2022-01-29 2022-09-04 or Forest Conservation ant Selection gabinete: Especialista 1 PE-PNCB-B.2.2.1-CS-INDV / A Strengthening Sustainable F Individual Consult sistencia Técnica Especialista TF / A8849 orest Landscape Manageme Post Open 22,000.00 11,738.16 Signed 2021-04-28 2022-04-19 2021-06-16 2022-05-30 2021-07-07 2022-06-22 2021-08-11 2022-07-03 2021-12-29 ant Selection en Acompañamiento técnico nt and Use (CAR Y CAM) PE-PNCB-B.3.2-CS-INDV / Re Strengthening Sustainable F Individual Consult TF / A8849 Post Open 32,000.00 1,934.96 Completed 2021-03-31 2021-08-18 2021-05-19 2021-09-17 2021-06-09 2021-09-27 2021-07-14 2022-03-31 2021-10-12 2023-02-11 sponsable de planes de vida orest Landscape Manageme ant Selection nt and Use PE-PNCB-A.3.8.1-CS-INDV / S ervicio de elaboración de kit Institutional Strengthening f Individual Consult de herramientas de comunic TF / A8849 Post Open 15,000.00 11,327.69 Completed 2021-04-29 2021-07-30 2021-06-17 2021-11-10 2021-07-08 2022-03-18 2021-08-12 2022-03-29 2021-11-10 2022-09-07 or Forest Conservation ant Selection ación para la socialización de las Salvaguardas Sociales y A mbiental del BM PE-PNCB-A.3.8.2-CS-INDV / S ervicio de elaboración de Pro tocolo de Relacionamiento y/ Institutional Strengthening f Individual Consult TF / A8849 Post Open 7,000.00 5,463.73 Completed 2021-04-30 2021-07-12 2021-06-18 2021-10-12 2021-07-09 2022-03-18 2021-08-13 2022-03-29 2022-02-09 2022-05-25 o código de Ética para el rela or Forest Conservation ant Selection cionamiento con actores soci ales en el ámbito de interven ción del FIP-BM PE-PNCB-C.20-CS-INDV / Esp Strengthening Sustainable F Individual Consult ecialista en Sistemas Product TF / A8849 orest Landscape Manageme Post Open 22,000.00 0.00 Signed 2021-05-03 2022-06-21 2021-05-27 2022-09-21 2021-06-01 2022-09-21 2021-07-02 2021-12-29 ant Selection ivos Sostenibles nt and Use PE-PNCB-C.25-CS-INDV / Esp Strengthening Sustainable F Individual Consult TF / A8849 Post Open 14,000.00 11,386.65 Signed 2021-06-01 2021-09-14 2021-07-20 2021-11-04 2021-08-10 2021-12-07 2021-08-29 2021-12-08 2021-12-27 ecialista Zonal Salvaguardas orest Landscape Manageme ant Selection nt and Use PE-PNCB-B.1.1.2.2-CS-INDV / Institutional Strengthening f Individual Consult Servicio para diagnostico de TF / A8849 Post Open 7,000.00 0.27 Completed 2021-04-19 2021-09-14 2021-06-07 2022-04-01 2021-06-28 2022-04-22 2021-08-02 2022-05-07 2022-01-29 2022-09-02 or Forest Conservation ant Selection gabinete: Especialista 2 Page 7 PE-PNCB-B.1.1.2.3-CS-INDV / Institutional Strengthening f Individual Consult Servicio para diagnostico de TF / A8849 Post Open 7,000.00 0.27 Completed 2021-04-26 2021-09-14 2021-06-14 2022-04-04 2021-07-05 2022-04-27 2021-08-09 2022-05-21 2022-02-05 2022-09-03 or Forest Conservation ant Selection gabinete: Especialista 3 PE-PNCB-29167-CS-INDV / Es Individual Consult TF / A4636 Post Direct 18,787.88 0.00 Canceled 2017-09-22 2017-09-27 2017-09-28 2017-10-02 2017-12-31 pecialista en Inversión Públic ant Selection a PE-PNCB-29177-CS-INDV / Pl Individual Consult TF / A4636 Post Direct 12,121.21 0.00 Canceled 2017-09-22 2017-09-27 2017-09-28 2017-10-02 2017-12-31 an de Evaluación de impacto ant Selection PE-PNCB-29180-CS-INDV / Di seño del componente de gob Individual Consult TF / A4636 Post Direct 9,090.91 0.00 Canceled 2017-09-22 2017-10-26 2017-09-27 2017-10-20 2017-09-28 2017-10-02 2017-12-31 ernanza forestal y fortalecimi ant Selection ento institucional. PE-PNCB-29178-CS-INDV / E Individual Consult TF / A4636 Post Direct 13,636.36 0.00 Canceled 2017-09-22 2017-10-26 2017-09-27 2017-10-20 2017-09-28 2017-10-02 2017-12-31 valuación Ambiental ant Selection PE-PNCB-29176-CS-INDV / E Individual Consult TF / A4636 Post Direct 12,272.73 0.00 Canceled 2017-09-22 2017-10-26 2017-09-27 2017-10-20 2017-09-28 2017-10-02 2017-12-31 valuación Social ant Selection PE-PNCB-29183-CS-INDV / Es Individual Consult TF / A4636 Post Direct 12,121.00 0.00 Canceled 2017-09-22 2017-10-26 2017-09-27 2017-10-20 2017-09-28 2017-10-02 2017-12-31 pecialista Fiduciario BM ant Selection PE-PNCB-29179-CS-INDV / D Individual Consult TF / A4636 Post Direct 9,090.91 0.00 Canceled 2017-09-22 2017-10-26 2017-09-27 2017-10-20 2017-09-28 2017-10-02 2017-12-31 ocumentos Operativos del pr ant Selection oyecto PE-PNCB-29175-CS-INDV / A poyo al diseño del componen Individual Consult TF / A4636 Post Direct 12,272.73 0.00 Canceled 2017-09-22 2017-10-26 2017-09-27 2017-10-20 2017-09-28 2017-10-02 2017-12-31 te inversiones comunitarias e ant Selection n Paisajes Forestales Sosteni bles PE-PNCB-29182-CS-INDV / S Individual Consult TF / A4636 Post Direct 21,818.00 0.00 Canceled 2017-09-22 2017-10-26 2017-09-27 2017-10-20 2017-09-28 2017-10-02 2017-12-31 upervisor de Diseño ant Selection PE-PNCB-29173-CS-INDV / A Individual Consult sistente Técnico para proces TF / A4636 Post Direct 3,636.36 0.00 Canceled 2017-09-22 2017-10-26 2017-09-27 2017-10-20 2017-09-28 2017-10-02 2017-12-31 ant Selection amiento de información PE-PNCB-29174-CS-INDV / E Individual Consult TF / A4636 Post Direct 6,060.61 0.00 Canceled 2017-09-22 2017-10-26 2017-09-27 2017-10-20 2017-09-28 2017-10-02 2017-12-31 ditor Revisor ant Selection PE-PNCB-29172-CS-INDV / E Individual Consult TF / A4636 Post Direct 6,060.61 0.00 Canceled 2017-09-22 2017-10-26 2017-09-27 2017-10-20 2017-09-28 2017-10-02 2017-12-31 valuación económica/social ant Selection PE-PNCB-29171-CS-INDV / Es Individual Consult TF / A4636 Post Direct 8,181.82 0.00 Canceled 2017-09-22 2017-10-26 2017-09-27 2017-10-20 2017-09-28 2017-10-02 2017-12-31 pecialista en Econegocios ant Selection PE-PNCB-29170-CS-INDV / Es Individual Consult pecialista SIG, con experienc TF / A4636 Post Direct 8,636.36 0.00 Canceled 2017-09-22 2017-10-26 2017-09-27 2017-10-20 2017-09-28 2017-10-02 2017-12-31 ant Selection ia en cuantificación de carbo no PE-PNCB-29169-CS-INDV / Es Individual Consult TF / A4636 Post Direct 12,272.73 0.00 Canceled 2017-09-22 2017-10-26 2017-09-27 2017-10-20 2017-09-28 2017-10-02 2017-12-31 pecialista Forestal ant Selection PE-PNCB-29168-CS-INDV / Es Individual Consult pecialista Social en pueblos i TF / A4636 Post Direct 12,272.73 0.00 Canceled 2017-09-22 2017-10-26 2017-09-27 2017-10-20 2017-09-28 2017-10-02 2017-12-31 ant Selection ndígenas y poblaciones rural es PE-PNCB-29166-CS-INDV / C Individual Consult oordinador Técnico del Equip TF / A4636 Post Direct 21,503.03 0.00 Canceled 2017-10-19 2017-10-26 2017-10-25 2017-10-20 2017-10-27 2017-10-31 2018-01-30 ant Selection o Consultor PE-PNCB-29444-CS-CDS / Ev entos participativos, talleres TF / A4636 Post Direct Selection Direct 151,515.15 0.00 Canceled 2017-09-25 2017-10-26 2017-09-28 2017-10-20 2017-10-03 2017-12-31 y otros (Plan de Participación e Involucramiento de Actores ) PE-PNCB-B.3.5-CS-INDV / For Strengthening Sustainable F Individual Consult TF / A8845 Post Open 9,000.00 0.00 Canceled 2021-11-30 2021-10-13 2022-05-05 2022-05-26 2022-06-30 2022-12-27 malización de juntas directiv orest Landscape Manageme ant Selection as nt and Use PE-PNCB-A.4.7-CS-INDV / Co nsultoría para elaborar herra Strengthening Sustainable F mientas comunicaciones del Individual Consult TF / A8849 orest Landscape Manageme Post Open 4,500.00 0.00 Canceled 2022-06-01 2022-07-20 2022-08-10 2022-09-14 2022-10-14 Mecanismos de Resolución d ant Selection nt and Use e Quejas, Consultas y Conflic tos y medidas de mitigación de los planes de negocio PE-PNCB-B.1.1.1.1.3.1-CS-IN DV / Coordinador (Especialist a legal) del equipo de monito Institutional Strengthening f Individual Consult TF / A8849 Post Open 5,250.00 0.00 Canceled 2022-06-17 2022-08-05 2022-08-26 2022-09-30 2022-12-29 reo de Apoyar la titulación, a or Forest Conservation ant Selection mpliación y asignación de de rechos de comunidades nativ as PE-PNCB-B.1.1.1.1.3.2-CS-IN DV / Especialista SIG del equi Institutional Strengthening f Individual Consult po de monitoreo de Apoyar l TF / A8849 Post Open 5,625.00 0.00 Canceled 2022-06-17 2022-08-05 2022-08-26 2022-09-30 2022-12-29 or Forest Conservation ant Selection a titulación, ampliación y asi gnación de derechos de com unidades nativas PE-PNCB-B.1.1.1.1.3.3-CS-IN DV / Especialista en ciencias sociales del equipo de monit Institutional Strengthening f Individual Consult TF / A8849 Post Open 5,625.00 0.00 Canceled 2022-06-17 2022-08-05 2022-08-26 2022-09-30 2022-12-29 oreo de Apoyar la titulación, or Forest Conservation ant Selection ampliación y asignación de d erechos de comunidades nati vas PE-PNCB-B.1.1.1.1.3.4-CS-IN DV / Técnico Indígena del eq Institutional Strengthening f Individual Consult uipo de monitoreo de Apoyar TF / A8849 Post Open 4,500.00 0.00 Canceled 2022-06-17 2022-08-05 2022-08-26 2022-09-30 2022-12-29 or Forest Conservation ant Selection la titulación, ampliación y asi gnación de derechos de com unidades nativas PE-PNCB-B.1.2.1.2.3-CS-IND Institutional Strengthening f Individual Consult V / Actualización del plan reg TF / A8849 Post Open 5,500.00 0.00 Canceled 2022-06-18 2022-08-06 2022-08-27 2022-10-01 2022-10-31 or Forest Conservation ant Selection ional de acción ambiental - t aller 01 y 02 Page 8 PE-PNCB-B.1.2.1.2.4-CS-IND Institutional Strengthening f Individual Consult V / Actualización del plan reg TF / A8849 Post Open 1,600.00 0.00 Canceled 2022-07-18 2022-09-05 2022-09-26 2022-10-31 2022-11-30 or Forest Conservation ant Selection ional de acción ambiental - t aller 03 PE-PNCB-B.1.2.3.2.2-CS-IND V / Asistente técnico para For Institutional Strengthening f Individual Consult talecimiento de capacidades TF / A8849 Post Open 6,800.00 0.00 Canceled 2022-03-01 2022-04-14 2022-05-05 2022-06-09 2022-12-06 or Forest Conservation ant Selection para la vigilancia de bosques en comunidades nativas PE-PNCB-B.1.2.3.2.5-CS-IND V / Facilitador indígena del F Institutional Strengthening f Individual Consult ortalecimiento de capacidade TF / A8849 Post Open 6,800.00 0.00 Canceled 2022-03-01 2022-04-14 2022-05-05 2022-06-09 2022-12-06 or Forest Conservation ant Selection s para la vigilancia de bosqu es en comunidades nativas PE-PNCB-B.1.2.3.4.2-CS-IND V / Asistente de capacitación Institutional Strengthening f Individual Consult del Fortalecimiento de capaci TF / A8849 Post Open 5,700.00 0.00 Canceled 2022-03-31 2022-05-14 2022-06-04 2022-07-09 2022-12-06 or Forest Conservation ant Selection dades de entidades públicas para el monitoreo y control d e la deforestación PE-PNCB-B.1.2.3.4.6-CS-IND V / Técnico forestal 3 del Fort Institutional Strengthening f Individual Consult Under Implement alecimiento de capacidades TF / A8849 Post Open 10,200.00 0.00 2022-04-01 2022-09-30 2022-05-15 2022-10-14 2022-06-05 2022-10-18 2022-07-04 2022-12-31 or Forest Conservation ant Selection ation de entidades públicas para el monitoreo y control de la def orestación PE-PNCB-B.1.2.1.3.1-CS-IND V / Consultoría individual Esp Institutional Strengthening f Individual Consult ecialista en Gestión Institucio TF / A8849 Post Open 11,341.00 0.00 Canceled 2022-06-01 2022-06-22 2022-06-24 2022-07-29 2022-12-26 or Forest Conservation ant Selection nal para actualización de ins trumentos de gestión ambien tal. PE-PNCB-B.1.2.2.1.2-CS-IND Institutional Strengthening f Individual Consult V / Consultoría individual de TF / A8849 Post Open 13,500.00 0.00 Canceled 2022-03-01 2022-03-25 2022-03-27 2022-04-27 2022-12-23 or Forest Conservation ant Selection Técnico Indígena - URPIA PE-PNCB-B.1.2.2.1.3-CS-IND Institutional Strengthening f Individual Consult V / Consultoría individual de TF / A8849 Post Open 13,500.00 1,321.79 Completed 2022-04-01 2022-05-23 2022-04-25 2022-06-09 2022-04-27 2022-06-10 2022-05-28 2022-07-18 2022-12-24 2023-04-07 or Forest Conservation ant Selection Técnico Indígena - CORPIAA PE-PNCB-B.1.2.3.2.1-CS-IND Institutional Strengthening f Individual Consult V / Especialista en diseño de TF / A8849 Post Open 11,250.00 0.00 Canceled 2022-04-01 2022-04-25 2022-04-27 2022-05-28 2022-11-24 or Forest Conservation ant Selection estrategia de monitoreo y vig ilancia PE-PNCB-B.1.2.3.2.4-CS-IND Institutional Strengthening f Individual Consult V / Especialista en capacitaci TF / A8849 Post Open 11,250.00 0.00 Canceled 2022-04-01 2022-04-25 2022-04-27 2022-05-28 2022-11-24 or Forest Conservation ant Selection ón en temas de control y vigi lancia PE-PNCB-B.1.2.3.3.1-CS-IND Institutional Strengthening f Individual Consult V / Especialista en fortalecimi TF / A8849 Post Open 11,250.00 0.00 Canceled 2022-04-01 2022-04-25 2022-04-27 2022-05-28 2022-11-24 or Forest Conservation ant Selection ento organizacional y asociat ividad PE-PNCB-B.1.2.3.3.9-CS-IND Institutional Strengthening f Individual Consult V / Especialista en sensibiliza TF / A8849 Post Open 11,250.00 0.00 Canceled 2022-04-01 2022-04-25 2022-04-27 2022-05-28 2022-11-24 or Forest Conservation ant Selection ción ambiental PE-PNCB-B.1.2.3.4.1-CS-IND Institutional Strengthening f Individual Consult V / Especialista en fortalecimi TF / A8849 Post Open 9,375.00 0.00 Canceled 2022-04-01 2022-04-25 2022-04-27 2022-05-28 2022-10-25 or Forest Conservation ant Selection ento de capacidades PE-PNCB-B.1.2.3.4.7-CS-IND Institutional Strengthening f Individual Consult TF / A8849 Post Open 11,250.00 0.00 Canceled 2022-05-01 2022-05-25 2022-05-27 2022-06-27 2022-12-24 V / Especialista forestal or Forest Conservation ant Selection PE-PNCB-B.1.2.3.4.8-CS-IND Institutional Strengthening f Individual Consult V / Especialista en temas de TF / A8849 Post Open 11,250.00 0.00 Completed 2022-05-02 2022-09-30 2022-05-26 2022-10-17 2022-05-28 2022-10-17 2022-06-28 2022-12-25 2023-04-07 or Forest Conservation ant Selection control y vigilancia PE-PNCB-B.2.1.1.2.1-CS-IND V / Consultoría para el diseño de la metodología a ser empl Institutional Strengthening f Individual Consult eada en los talleres de capac TF / A8845 Post Open 16,145.00 0.00 Canceled 2022-06-01 2022-06-25 2022-06-27 2022-07-07 2022-10-05 or Forest Conservation ant Selection itación para elaboración de p lanes de negocio. Diseño de l os talleres de presentación d e las bases PE-PNCB-B.2.1.4.1.1-CS-IND V / Consultoría individual par Institutional Strengthening f Individual Consult TF / A8845 Post Open 18,000.00 2,300.76 Signed 2022-04-01 2022-04-19 2022-04-21 2022-06-07 2022-04-23 2022-07-11 2022-05-03 2022-08-14 2022-12-29 a un responsable en comerci or Forest Conservation ant Selection alización y articulación come rcial PE-PNCB-1.2.2.1.4-PLAN.VID A-URPIA-CS-CDS / Servicio de consultoría para elaboración Institutional Strengthening f de planes de vida de las com TF / A8849 Post Direct Selection Direct 164,014.00 167,997.39 Signed 2022-03-31 2022-05-13 2022-04-10 2022-05-23 2022-06-14 2022-08-11 2022-08-13 or Forest Conservation unidades nativas en la provin cia de Atalaya de la región U cayali – grupo de comunidad es A PE-PNCB-1.2.2.1.4-PLAN.VID A-CORPI-CS-CDS / Servicio de consultoría para elaboración Institutional Strengthening f de planes de vida de las com TF / A8849 Post Direct Selection Direct 166,864.00 172,228.67 Signed 2022-03-31 2022-05-13 2022-04-10 2022-05-23 2022-06-14 2022-08-05 2022-08-13 or Forest Conservation unidades nativas en la provin cia de Atalaya de la región U cayali – grupo de comunidad es B PE-PNCB-1.1.5.ESP.FINANCIE Project Management, Monito Individual Consult TF / A8849 Post Open 67,500.00 2,935.72 Completed 2022-05-16 2022-05-23 2022-06-07 2022-08-15 2022-06-10 2022-08-17 2022-06-22 2022-09-03 2024-12-31 2023-04-07 RO-2-CS-INDV / Especialista f ring and Evaluation ant Selection inanciero PE-PNCB-3.4.1.ASIST.TEC1-C Project Management, Monito Individual Consult TF / A8849 Post Limited 3,750.00 0.00 Canceled 2022-05-23 2022-06-21 2022-05-28 2022-06-06 2022-06-24 2022-08-23 S-INDV / Asistente técnico 1 ring and Evaluation ant Selection PE-PNCB-3.4.2.ASIST-TEC-2- Project Management, Monito Individual Consult TF / A8849 Post Limited 3,750.00 0.00 Canceled 2022-05-23 2022-05-28 2022-06-02 2022-06-20 2022-08-19 CS-INDV / Asistente técnico 2 ring and Evaluation ant Selection Page 9 PE-PNCB-B.1.2.2.1.2.TEC.IND -CS-INDV / consultoría individ ual de técnico indígena para Institutional Strengthening f Individual Consult brindar asistencia técnica en TF / A8849 Post Limited 8,108.00 7,734.25 Completed 2022-06-09 2022-06-16 2022-06-14 2022-07-21 2022-06-19 2022-08-03 2022-07-09 2022-08-21 2023-01-05 2023-04-07 or Forest Conservation ant Selection la elaboración e implementac ión de PLANES DE VIDA y su articulación con otros instru mentos de gestión PE-PNCB-1.1.3.ESP.ADQUIS- Project Management, Monito Individual Consult CS-INDV-3 / Especialista en a TF / A8849 Prior Open 21,081.00 10,218.79 Signed 2022-06-25 2022-06-24 2022-07-06 2022-08-10 2022-07-09 2022-08-24 2022-07-13 2022-09-11 2022-12-31 ring and Evaluation ant Selection dquisiciones PE-PNCB-B.1.2.3.1.15-CS-IN DV / Asistente administrativo Institutional Strengthening f Individual Consult del Fortalecimiento del siste TF / A8849 Post Open 1,100.00 0.00 Canceled 2022-04-23 2022-06-06 2022-06-27 2022-08-01 2022-08-31 or Forest Conservation ant Selection ma de control y vigilancia en el entorno de la RC El Sira en el ámbito del PIP 2 PE-PNCB-B.1.2.3.1.14-CS-IN Institutional Strengthening f Individual Consult DV / Especialista en conserva TF / A8849 Post Open 2,100.00 0.00 Canceled 2022-04-22 2022-06-05 2022-06-26 2022-07-31 2022-08-30 or Forest Conservation ant Selection ción de bosques amazónicos II PE-PNCB-B.1.2.3.1.12-CS-IN DV / Facilitador indígena del Institutional Strengthening f Individual Consult Fortalecimiento del sistema d TF / A8849 Post Open 3,800.00 0.00 Canceled 2022-04-23 2022-06-06 2022-06-27 2022-08-01 2022-10-30 or Forest Conservation ant Selection e control y vigilancia en el en torno de la RC El Sira en el á mbito del PIP 2 PE-PNCB-B.1.2.3.1.11-CS-IN DV / Asistente de capacitació Institutional Strengthening f Individual Consult n II del Fortalecimiento del si TF / A8849 Post Open 7,700.00 0.00 Canceled 2022-03-01 2022-04-14 2022-05-05 2022-06-09 2022-12-06 or Forest Conservation ant Selection stema de control y vigilancia en el entorno de la RC El Sira en el ámbito del PIP 2 PE-PNCB-B.1.2.3.1.10-CS-IN Institutional Strengthening f Individual Consult DV / Especialista en conserva TF / A8849 Post Open 11,250.00 0.00 Canceled 2022-04-01 2022-04-25 2022-04-27 2022-05-28 2022-11-24 or Forest Conservation ant Selection ción de bosques amazónicos I PE-PNCB-B.1.2.3.1.9-CS-IND V / Operador logístico para c Institutional Strengthening f Individual Consult TF / A8849 Post Open 4,500.00 0.00 Canceled 2022-05-19 2022-07-07 2022-07-28 2022-09-01 2022-10-01 apacitación en tecnologías y or Forest Conservation ant Selection herramientas para el control y vigilancia PE-PNCB-B.1.2.3.1.8-CS-IND V / Asistente de capacitación Institutional Strengthening f Individual Consult I del Fortalecimiento del siste TF / A8849 Post Open 6,400.00 0.00 Canceled 2022-04-18 2022-06-06 2022-06-27 2022-08-01 2022-12-29 or Forest Conservation ant Selection ma de control y vigilancia en el entorno de la RC El Sira en el ámbito del PIP 2 PE-PNCB-B.1.2.3.1.7-CS-IND V / Especialista en capacitaci Institutional Strengthening f Individual Consult TF / A8849 Post Open 9,375.00 0.00 Canceled 2022-07-01 2022-07-25 2022-07-27 2022-08-27 2022-12-25 ón de tecnologías para contr or Forest Conservation ant Selection ol y vigilancia en comunidad es PE-PNCB-3.4.5.ASESOR.TEC Project Management, Monito Individual Consult TF / A8849 Post Limited 7,567.00 5,588.51 Signed 2022-07-11 2022-06-28 2022-07-16 2022-08-03 2022-07-26 2022-08-08 2022-08-10 2022-08-22 2022-10-09 NICO-CS-INDV / Asesor técnic ring and Evaluation ant Selection o PE-PNCB-C.1.1.1.COORD.PR Project Management, Monito Individual Consult OY-CS-INDV-3 / Coordinador TF / A8849 Post Direct 24,324.00 11,696.51 Completed 2022-06-30 2022-07-13 2022-07-10 2022-07-27 2022-07-15 2022-08-24 2022-07-25 2022-09-02 2023-01-21 2023-02-11 ring and Evaluation ant Selection del proyecto PE-PNCB-A.3.4-CS-INDV / Ser Project Management, Monito Individual Consult vicio para el diseño, organiza TF / A8849 Post Limited 3,030.00 0.00 Canceled 2020-04-13 2020-04-20 2020-04-25 2020-05-10 2020-07-29 ring and Evaluation ant Selection ción y desarrollo de talleres PE-PNCB-A.3.6-CS-INDV / Ser Project Management, Monito Individual Consult vicio para el diseño, organiza TF / A8849 Post Limited 3,030.00 0.00 Canceled 2020-05-12 2020-05-19 2020-05-24 2020-06-08 2020-07-08 ring and Evaluation ant Selection ción y desarrollo de talleres d e Salvaguardas PE-PNCB-C.18.2-CS-INDV / C Project Management, Monito Individual Consult onsultoría individual para cad TF / A8849 Post Limited 13,637.00 0.00 Canceled 2020-03-16 2020-08-16 2020-03-23 2020-03-28 2020-04-12 2020-07-31 ring and Evaluation ant Selection enas productivas PE-PNCB-B.3.2-CS-CQS / Con Institutional Strengthening f Individual Consult tratación del servicio para re TF / A8849 Post Limited 19,091.00 0.00 Canceled 2020-05-04 2020-05-09 2020-05-14 2020-05-29 2020-12-31 or Forest Conservation ant Selection sponsable de planes de vida PE-PNCB-B.3.2-CS-CQS-2 / C Institutional Strengthening f Individual Consult ontratación del servicio para TF / A8849 Post Open 19,091.00 0.00 Canceled 2020-12-11 2020-12-14 2020-12-23 2020-12-28 2021-01-01 2021-12-31 or Forest Conservation ant Selection responsable de planes de vid a PE-PNCB-C.23-CS-INDV / Esp Strengthening Sustainable F Individual Consult TF / A8849 Post Open 9,000.00 0.00 Canceled 2021-08-02 2021-08-26 2021-08-31 2021-09-19 2021-12-18 ecialista Zonal Negocios 1 orest Landscape Manageme ant Selection nt and Use PE-PNCB-316146-CS-INDV / Project Management, Monito Individual Consult TF / A8849 Post Open - National 7,297.30 0.00 Completed 2022-09-14 2022-09-30 2022-09-26 2022-10-21 2022-09-29 2022-10-25 2022-10-05 2023-01-03 2023-02-10 ESPECIALISTA LEGAL ring and Evaluation ant Selection PE-PNCB-316148-CS-INDV / Project Management, Monito Individual Consult ASISTENTE TÉCNICO EN ADQ TF / A8849 Post Open - National 6,486.49 0.00 Canceled 2022-09-14 2022-09-16 2022-09-26 2022-09-29 2022-10-05 2023-01-03 ring and Evaluation ant Selection UISICIONES PE-PNCB-316149-CS-INDV / Project Management, Monito Individual Consult ESPECIALISTA EN SALVAGUA TF / A8849 Post Open - National 7,297.30 0.00 Signed 2022-09-15 2022-09-17 2022-09-28 2022-10-10 2022-10-01 2022-10-12 2022-10-07 2023-01-05 ring and Evaluation ant Selection RDAS SOCIO AMBIENTALES PE-PNCB-B.2.1.1.2.2-CS-IND Strengthening Sustainable F V / FORMALIZACIÓN DE JUNT Individual Consult TF / A8845 orest Landscape Manageme Post Open - National 6,081.08 0.00 Signed 2022-06-01 2022-09-16 2022-06-25 2022-10-11 2022-06-27 2022-10-13 2022-07-07 2022-12-04 AS DIRECTIVAS DE LAS COM ant Selection nt and Use UNIDADES NATIVAS PE-PNCB-317141-CS-INDV / Project Management, Monito Individual Consult ASISTENTE TÉCNICO EN ADQ TF / A8849 Prior Open - National 6,486.49 0.00 Canceled 2022-09-20 2022-09-29 2022-10-05 2022-11-16 2022-10-08 2022-10-14 2023-01-12 ring and Evaluation ant Selection UISICIONES PE-PNCB-B.3.1-CS-INDV / Val Strengthening Sustainable F Individual Consult TF / A8845 Post Open 3,500.00 0.00 Canceled 2021-06-28 2021-07-27 2021-08-06 2021-08-26 2021-09-25 idación de beneficiarios pote orest Landscape Manageme ant Selection nciales nt and Use PE-PNCB-B.4.1-CS-INDV / Ser Strengthening Sustainable F Individual Consult vicio para reconocimiento (0 TF / A8849 orest Landscape Manageme Post Open 30,000.00 0.00 Canceled 2021-06-08 2021-07-27 2021-08-17 2021-09-21 2022-02-18 ant Selection 2 Comunidades Nativas en 0 nt and Use 3 meses) Page 10 PE-PNCB-B.4.2-CS-INDV / Ser Strengthening Sustainable F Individual Consult TF / A8849 Post Open 37,000.00 0.00 Canceled 2021-06-28 2021-08-16 2021-08-21 2021-08-31 2022-01-28 vicio para ampliación y titula orest Landscape Manageme ant Selection ción nt and Use PE-PNCB-B.4.3.5-CS-INDV / E Strengthening Sustainable F specialista en control y vigila Individual Consult TF / A8849 orest Landscape Manageme Post Open 19,000.00 0.00 Canceled 2021-04-26 2021-05-21 2021-05-31 2021-06-11 2021-12-08 ncia forestal (perfil legal para ant Selection nt and Use Planes de Negocio) PE-PNCB-C.19.11-CS-INDV / Servicio de elaboración de co Project Management, Monito Individual Consult ntenidos informativos para s TF / A8849 Post Open 8,000.00 0.00 Canceled 2021-04-26 2021-06-14 2021-07-05 2021-08-09 2021-12-07 ring and Evaluation ant Selection u difusión en el ámbito de int ervención del proyecto PE-PNCB-B.3.2.1-CS-INDV / D Institutional Strengthening f Individual Consult TF / A8845 Post Open 9,500.00 0.00 Canceled 2021-05-31 2021-07-19 2021-08-09 2021-08-25 2021-09-24 iseño de metodología para ta or Forest Conservation ant Selection lleres PE-PNCB-B.4.3.6-CS-INDV / E Project Management, Monito Individual Consult TF / A8849 Post Open 14,000.00 0.00 Canceled 2021-03-29 2021-04-23 2021-05-03 2021-06-03 2021-11-30 specialista en monitoreo de b ring and Evaluation ant Selection osques PE-PNCB-C.22-CS-INDV / Esp Strengthening Sustainable F Individual Consult TF / A8849 Post Open 6,000.00 0.00 Canceled 2021-08-02 2021-08-31 2021-09-05 2021-09-24 2021-12-23 ecialista Financiero Zonal orest Landscape Manageme ant Selection nt and Use PE-PNCB-B.4.3.2-CS-INDV / D Project Management, Monito Individual Consult esarrollo de protocolos de ac TF / A8849 Post Open 8,000.00 0.00 Canceled 2021-07-26 2021-08-30 2021-09-02 2021-09-09 2021-12-08 ring and Evaluation ant Selection tuación para el monitoreo y v igilancia PE-PNCB-B.3.3.1-CS-INDV / I Strengthening Sustainable F Individual Consult mplementación de talleres d TF / A8845 orest Landscape Manageme Post Open 17,000.00 0.00 Canceled 2021-07-26 2021-08-24 2021-09-03 2021-09-15 2021-11-14 ant Selection e ideas de negocio nt and Use PE-PNCB-C.19.6-CS-INDV / E Project Management, Monito Individual Consult TF / A8849 Post Open 20,000.00 0.00 Canceled 2021-04-26 2021-07-27 2021-05-20 2021-06-10 2021-07-05 2022-01-01 specialista en Seguimiento y ring and Evaluation ant Selection Monitoreo PE-PNCB-B.3.3-CS-INDV / Es Strengthening Sustainable F Individual Consult TF / A8849 Post Open 15,000.00 0.00 Canceled 2021-03-31 2021-08-26 2021-05-19 2021-06-09 2021-07-14 2022-01-10 pecialista Indígena orest Landscape Manageme ant Selection nt and Use PE-PNCB-B.1.2.3.4.4-CS-IND Institutional Strengthening f Individual Consult TF / A8849 Post Open - National 6,486.49 0.00 Canceled 2022-10-03 2022-10-06 2022-10-16 2022-11-22 2022-10-19 2022-10-29 2022-12-28 V / Técnico forestal or Forest Conservation ant Selection PE-PNCB-B.1.2.3.4.5-CS-IND V / Técnico forestal 2 del Fort Institutional Strengthening f Individual Consult alecimiento de capacidades TF / A8849 Post Open 10,200.00 0.00 Canceled 2022-04-01 2022-05-15 2022-06-05 2022-07-04 2022-12-31 or Forest Conservation ant Selection de entidades públicas para el monitoreo y control de la def orestación PE-PNCB-B.1.2.1.2.2-CS-IND V / Consultoría para Actualiza ción de la Agenda Ambiental Institutional Strengthening f Individual Consult TF / A8849 Post Open - National 7,770.27 0.00 Signed 2022-04-22 2022-10-06 2022-06-10 2022-10-28 2022-07-01 2022-11-02 2022-08-05 2022-09-04 de la Región Ucayali y Actuali or Forest Conservation ant Selection zación del Plan Regional de A cción Ambiental de Ucayali PE-PNCB-319331-CS-CDS / S ERVICIO PARA LA SERVICIO D E PRODUCCIÓN AUDIOVISUA Project Management, Monito TF / A8849 Post Direct Selection Direct - National 4,729.73 0.00 Completed 2022-10-06 2022-10-13 2022-10-15 2022-10-20 2022-10-24 2022-11-13 2022-11-27 L DE FOTOS Y VIDEO INFORM ring and Evaluation ATIVO SOBRE IMPLEMENTACI ÓN DE LAS ACTIVIDADES DEL FIP/BM PE-PNCB-319332-CS-CDS / s ervicio de consultoría individ Project Management, Monito TF / A8849 Post Direct Selection Direct - National 5,675.68 0.00 Signed 2022-10-06 2022-11-25 2022-10-13 2022-12-05 2022-10-22 2022-12-31 ual para la elaboración de m ring and Evaluation anual de implementación de fondos de incentivos PE-PNCB-B.2.1.4.1.2-CS-IND Institutional Strengthening f Individual Consult V / ASISTENTE EN COMERCIA TF / A8845 Post Open - National 22,702.70 0.00 Signed 2022-10-26 2022-11-02 2022-11-08 2022-12-21 2022-11-11 2022-12-29 2022-11-17 2023-12-31 or Forest Conservation ant Selection LIZACIÓN Y ARTICULACIÓN C OMERCIAL PE-PNCB-322546-CS-INDV / Project Management, Monito Individual Consult CONTRATACIÓN DE CONSULT TF / A8849 Post Limited 34,054.05 0.00 Signed 2022-10-26 2022-10-28 2022-10-31 2022-11-17 2022-11-03 2022-11-18 2022-11-06 2023-12-31 ring and Evaluation ant Selection ORIA EN PRESUPUESTO PÚBL ICO PE-PNCB-322975-CS-INDV / Project Management, Monito Individual Consult TF / A8849 Post Limited 22,702.70 0.00 Canceled 2022-10-26 2022-10-28 2022-11-01 2022-11-05 2023-12-31 ASISTENTE TÉCNICO ADMINI ring and Evaluation ant Selection STRATIVO PE-PNCB-322976-CS-INDV / Project Management, Monito Individual Consult ASISTENTE ADMINISTRATIVO TF / A8849 Post Open - National 11,351.35 0.00 Signed 2022-10-26 2022-11-02 2022-11-07 2022-11-28 2022-11-09 2022-11-28 2022-11-17 2023-12-31 ring and Evaluation ant Selection PARA OFICINA REGIONAL ATA LAYA PE-PNCB-335057-CS-INDV- P Institutional Strengthening f Individual Consult OA 1.1.1.1.3 / Especialista 1- TF / A8849 Post Open - National 22,613.00 0.00 Canceled 2023-01-09 2023-01-27 2023-01-28 2023-01-31 2024-01-26 or Forest Conservation ant Selection Equipo de Monitoreo PE-PNCB-335058-CS-INDV- P Institutional Strengthening f Individual Consult OA 1.1.1.1.3 / Especialista 2- TF / A8849 Post Open - National 22,613.00 0.00 Canceled 2023-01-09 2023-01-27 2023-01-28 2023-01-31 2024-01-26 or Forest Conservation ant Selection Equipo de Monitoreo PE-PNCB-335060-CS-INDV- P OA 1.2.1.2.1 / Especialista 2- Institutional Strengthening f Individual Consult TF / A8849 Post Open - National 7,538.00 0.00 Canceled 2023-10-02 2023-10-21 2023-10-22 2023-10-26 2023-12-25 Instrumentos de gestión amb or Forest Conservation ant Selection iental de la CAR actualizados PE-PNCB-335064-CS-INDV- P OA 1.2.1.3.1 / Especialista en Gestión Institucional para act Institutional Strengthening f Individual Consult Pending Impleme TF / A8849 Post Open - National 9,034.00 0.00 2023-01-09 2023-01-28 2023-01-29 2023-02-02 2023-04-18 ualización de instrumentos d or Forest Conservation ant Selection ntation e gestión ambiental - Política Climática y Ambiental Local de Atalaya PE-PNCB-335065-CS-INDV- P OA 1.2.1.2.1 / Consultoría par Institutional Strengthening f Individual Consult a la "Elaboración de la Polític TF / A8849 Post Open - National 7,538.00 0.00 Canceled 2023-10-02 2023-10-21 2023-10-22 2023-10-26 2023-12-25 or Forest Conservation ant Selection a Ambiental y Climática Local de Atalaya (PACLA)" PE-PNCB-335067-CS-INDV- P Institutional Strengthening f Individual Consult Pending Impleme OA 1.2.3.4.1 / Asistente de c TF / A8849 Post Open - National 15,075.00 0.00 2023-02-03 2023-02-24 2023-02-25 2023-03-01 2023-12-26 or Forest Conservation ant Selection ntation apacitación Page 11 PE-PNCB-335068-CS-INDV- P Institutional Strengthening f Individual Consult Pending Impleme OA 1.2.3.4.2 / Técnico Forest TF / A8849 Post Open - National 15,075.00 0.00 2023-02-03 2023-02-24 2023-02-25 2023-03-01 2023-12-26 or Forest Conservation ant Selection ntation al SOFFSA 1 PE-PNCB-335069-CS-INDV- P Institutional Strengthening f Individual Consult Pending Impleme OA 1.2.3.4.3 / Técnico Forest TF / A8849 Post Open - National 15,075.00 0.00 2023-02-03 2023-02-24 2023-02-25 2023-03-01 2023-12-26 or Forest Conservation ant Selection ntation al SOFFSA 2 PE-PNCB-335072-CS-INDV- P Institutional Strengthening f Individual Consult Pending Impleme TF / A8849 Post Open - National 15,075.00 0.00 2023-02-03 2023-02-24 2023-02-25 2023-03-01 2023-12-26 OA 1.2.3.4.5 / Técnico Forest or Forest Conservation ant Selection ntation al UTMFC PE-PNCB-335073-CS-INDV- P Strengthening Sustainable F Individual Consult Pending Impleme OA 2.1.1.1.4 / Especialista Fi TF / A8845 orest Landscape Manageme Post Open - National 22,613.00 0.00 2023-01-09 2023-01-27 2023-01-28 2023-02-01 2024-01-27 ant Selection ntation nanciero Zonal nt and Use PE-PNCB-335074-CS-INDV- P Strengthening Sustainable F Individual Consult Pending Impleme TF / A8845 Post Limited 13,568.00 0.00 2023-01-09 2023-01-17 2023-01-22 2023-01-30 2024-01-25 OA 2.1.1.1.7 / Asistente técni orest Landscape Manageme ant Selection ntation co nt and Use PE-PNCB-335348-CS-INDV- P Strengthening Sustainable F Individual Consult Pending Impleme OA 2.1.5.1.3 / Especialista en TF / A8845 orest Landscape Manageme Post Open - National 16,332.00 0.00 2023-02-03 2023-02-24 2023-02-25 2023-03-01 2023-12-26 ant Selection ntation Planes de Negocio y Salvagu nt and Use ardas 1 PE-PNCB-335350-CS-INDV- P Strengthening Sustainable F Individual Consult Pending Impleme OA 2.1.5.1.4 / Especialista en TF / A8845 orest Landscape Manageme Post Open - National 16,332.00 0.00 2023-02-03 2023-02-24 2023-02-25 2023-03-01 2023-12-26 ant Selection ntation Planes de Negocio y Salvagu nt and Use ardas 2 PE-PNCB-335352-CS-INDV- P Project Management, Monito Individual Consult Pending Impleme OA 3.1.1.1.8 / Asistente en A TF / A8849 Prior Limited 24,121.00 0.00 2023-01-11 2023-01-17 2023-01-24 2023-01-30 2024-01-25 ring and Evaluation ant Selection ntation dquisiciones PE-PNCB-335353-CS-INDV- P Project Management, Monito Individual Consult Pending Impleme OA 3.1.1.1.9 / Especialista en TF / A8849 Post Open - National 30,151.00 0.00 2023-01-11 2023-01-31 2023-02-02 2023-02-06 2024-02-01 ring and Evaluation ant Selection ntation Seguimiento PE-PNCB-335359-CS-INDV- P Project Management, Monito Individual Consult Pending Impleme OA 3.1.1.1.10 / Asistente en TF / A8849 Post Limited 15,201.00 0.00 2023-01-13 2023-01-19 2023-01-26 2023-01-31 2023-12-27 ring and Evaluation ant Selection ntation Contabilidad y Tesorería PE-PNCB-335369-CS-INDV- P Project Management, Monito Individual Consult Pending Impleme OA 3.2.3.1.1 / Especialista en TF / A8849 Post Open - National 19,347.00 0.00 2023-01-12 2023-02-01 2023-02-03 2023-02-07 2024-01-03 ring and Evaluation ant Selection ntation comunicaciones 1 PE-PNCB-335371-CS-INDV-P Project Management, Monito Individual Consult Pending Impleme OA 3.2.3.1.2 / Especialista en TF / A8849 Post Open - National 15,829.00 0.00 2023-03-08 2023-03-28 2023-03-30 2023-04-03 2023-12-29 ring and Evaluation ant Selection ntation comunicaciones 2 PE-PNCB-341424-CS-INDV- P Project Management, Monito Individual Consult OA 3.2.4.1.1 / ASISTENTE EN TF / A8849 Post Limited 4,113.11 0.00 Canceled 2023-02-13 2023-02-15 2023-02-16 2023-02-19 2023-02-23 2023-04-24 ring and Evaluation ant Selection SEGUIMIENTO Y MONITOREO DE PROYECTOS PE-PNCB-344947-CS-INDV-P Project Management, Monito Individual Consult OA 3.2.4.1.1 / Asistente Técni TF / A8849 Post Limited 3,391.96 0.00 Signed 2023-02-27 2023-02-17 2023-03-02 2023-03-06 2023-03-05 2023-03-09 2023-03-11 2023-06-09 ring and Evaluation ant Selection co Administrativo PE-PNCB-335059-CS-INDV- P OA 1.2.1.2.1 / Consultoría par Institutional Strengthening f Individual Consult Pending Impleme TF / A8849 Post Open - National 7,538.00 0.00 2023-05-02 2023-05-21 2023-05-22 2023-05-26 2023-07-25 a la "Elaboración de la Estrat or Forest Conservation ant Selection ntation egia Regional de Cambio Cli mático" PE-PNCB-360660-CS-INDV / Institutional Strengthening f Individual Consult Under Implement Especialista en Temas de Co TF / A8849 Post Open - National 6,784.00 0.00 2023-05-11 2023-05-09 2023-05-27 2023-05-29 2023-06-03 2023-09-01 or Forest Conservation ant Selection ation ntrol y vigilancia PE-PNCB-363248-CS-INDV / Project Management, Monito Individual Consult Under Implement TF / A8849 Prior Open - National 9,798.99 0.00 2023-05-24 2023-06-09 2023-06-05 2023-06-07 2023-06-12 2023-09-10 ESPECIALISTA EN ADQUISICI ring and Evaluation ant Selection ation ONES PE-PNCB-363475-CS-INDV / Strengthening Sustainable F Individual Consult Under Implement Supervisor del Fondo de Ince TF / A8845 orest Landscape Manageme Post Limited 39,195.98 0.00 2023-05-26 2023-05-30 2023-05-29 2023-06-01 2023-06-06 2024-06-05 ant Selection ation ntivos para Conservación de nt and Use Bosques PE-PNCB-363477-CS-INDV / Strengthening Sustainable F Individual Consult Under Implement TF / A8849 Post Open - National 27,135.68 0.00 2023-05-26 2023-06-07 2023-06-10 2023-06-16 2023-07-22 Enlace Zonal orest Landscape Manageme ant Selection ation nt and Use Page 12 PROCUREMENT PLAN (Textual Part) Project information: Northern Urban Development Project (P175266) Project Implementation agency: Fundo de Fomento de Habitação Date of the Procurement Plan: July 1, 2021 Period covered by this Procurement Plan: July 1, 2021 – June 20, 2022 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (November 2020) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in Decree 5/2016 of March 8, 2016, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Not Applicable Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – Not Applicable PROCUREMENT Mozambique : Mozambique Northern Urban Development Project PLAN General Information Country: Mozambique 2023-06-05 Bank’s Approval Date of the Original Procurement Plan: 2023-06-05 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P175266 GPN Date: 2023-04-04 Project Name: Mozambique Northern Urban Development Project Loan / Credit No: IDA / D9430 National Directorate of Water Supply and Sanitation Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned MZ-DNGRH-CERC-NUDP- W0 01 / Restoration of normal op National Procure eration of dams affected by t ment Document - he floods including acquisitio Component 5 - Contingency Single Stage - One E Under Imple 2024-03-1 IDA / D9430 Post Request for Bids Open - National 1 Envelope proce 2,088,000.00 0.00 2023-06-05 2023-06-19 2023-06-19 2023-06-27 2023-07-10 2023-08-09 2023-09-13 n and installation of the moni Emergency Response nvelope mentation 1 ss (Non Bank-SPD toring systems - Southern Re ) gion, Pequenos Libombos , M acarretanea and Massingir D ams (4 Lots) MZ-DNGRH-CERC-NUDP-W0 02 / Replacement of 4 cables and acquisition and installati Request for Quota on of required dam safety m Component 5 - Contingency Request for Quota Single Stage - One E Pending Imp 2024-02-1 IDA / D9430 Post Limited tions (Non Bank-S 122,000.00 0.00 2023-06-19 2023-08-14 onitoring equipment and rem Emergency Response tions nvelope lementation 0 PD) oval of debris accumulated in the reservoir by high runoff d uring the rains at the Gorong osa Dam MZ-DNGRH-CERC-NUDP- W0 Request for Quota 04 / Replacement of the roof Component 5 - Contingency Request for Quota Single Stage - One E Pending Imp 2024-02-1 IDA / D9430 Post Limited tions (Non Bank-S 110,000.00 0.00 2023-06-19 2023-08-14 of Caia's office, damaged by Emergency Response tions nvelope lementation 0 PD) extreme events. National Procure MZ-DNGRH-CERC-NUDP- W0 ment Document - Component 5 - Contingency Single Stage - One E Pending Imp 2024-03-2 03 / Replacement of leaks in IDA / D9430 Post Request for Bids Open - National 1 Envelope proce 3,750,000.00 0.00 2023-06-16 2023-06-30 2023-07-21 2023-08-20 2023-09-24 Emergency Response nvelope lementation 2 the XaiXai and Chokwe Dyke ss (Non Bank-SPD s (2 Lots) ) National Procure MZ-DNGRH-CERC-NUDP- W0 ment Document - Component 5 - Contingency Request for Quota Single Stage - One E Pending Imp 2024-02-1 05 / Replacement of leaks in IDA / D9430 Post Limited 1 Envelope proce 115,000.00 0.00 2023-06-23 2023-08-18 Emergency Response tions nvelope lementation 4 the Muziva Dykes ss (Non Bank-SPD ) GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MZ-DNGRH-CERC-NUDP-CS0 01-CQS / Supervision of Rest Component 5 - Contingency Consultant Qualifi IDA / D9430 Post Open - National 489,000.00 0.00 Canceled 2023-06-05 2023-06-16 2023-07-30 2023-08-29 2023-10-03 2024-03-31 oration of Normal Operation Emergency Response cation Selection of Dams Southern Region an d Central Region MZ-DNGRH-CERC-NUDP-CS0 02-CQS / Supervision of Rest Component 5 - Contingency Consultant Qualifi Pending Impleme IDA / D9430 Post Open - National 460,000.00 0.00 2023-06-18 2023-07-09 2023-08-22 2023-09-21 2023-10-26 2024-04-23 oration of Normal Operation Emergency Response cation Selection ntation of Dams in the Southern Regi on INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MZ-DNGRH-CERC-NUDP-CS0 03-INDV / Supervision of Rest Component 5 - Contingency Individual Consult Pending Impleme IDA / D9430 Post Limited 29,000.00 0.00 2023-06-19 2023-06-24 2023-07-15 2023-08-19 2024-02-15 oration of Normal Operation Emergency Response ant Selection ntation of Dams in the Central Regio n Page 1 Project Procurement Strategy for Development April 18, 2022 I. Project overview Country: The Republic of Tajikistan Full Project Name: Technical Assistance for Financing Framework for Rogun Hydropower Project Total Finance ($): US$15,000,000 Project number: P178819 Project Development The development objective is to improve the Objective readiness of Rogun hydropower project to raise a financing package required for completion of construction II. Project Description The TA Project will help to: (a) strengthen technical, environmental and social aspects of the Rogun hydropower plant construction project (Rogun HPP Project); (b) develop the commercial framework of the Rogun HPP Project; and (c) strengthen the institutional capacity of the Project Management Group for Energy Facilities Construction under the President of the Republic of Tajikistan Rogun (Rogun PMG), which is the implementing entity for Rogun HPP Project. The TA Project would be implemented during the period of April 2022 and April 2031. The TA Project will have the following key components: Component 1: Improvement of the dam safety of Rogun HPP Project (estimated cost of about US$6.3 million). This component will finance: (a) the panel of experts (POE) for the dam safety, which will carry out due diligence and ensure international quality standards in the design and construction of Rogun HPP Project; provide high level and professional independent advice and guidance to support objectivity and credibility in the development and implementation of designs and in the construction of the project; share technical expertise and knowledge and so contribute to dialogue amongst the various stakeholders; and (b) technical and engineering studies that may be required for improvement of technical aspects of the Project. Component 2: Strengthening of environmental and social (E&S) performance of Rogun HPP Project (estimated cost of about US$5.2 million). This component will finance the following: (a) update of E&S instruments for Rogun HPP Project to align them with the requirements of the World Bank’s Environmental and Social Framework (ESF); assistance to Rogun PMG in developing a Contractor Management Plan that will include the details of how Rogun PMG will supervise the E&S performance of its contractors; recommendations on modification of existing contractors, to 1 include relevant E&S requirements to comply with the applicable E&S standards and requirements; (d) E&S panel of experts; and (e) design of local community benefit-sharing program. Component 3: Development of the commercial framework for Rogun HPP Project (estimated cost of US$2 million). This component will finance: (a) preparation of a macroeconomically sustainable Project construction completion schedule taking into account the existing and projected macro-fiscal framework of the country; (b) prepare a Project financing plan taking into account the updated Project construction completion schedule; (c) transaction advisory service to help the Government draft, negotiate, and sign long-term PPAs for sale of Rogun electricity; and (d) technical and engineering studies that may be required for strengthening o Component 4: Strengthening of institutional capacity of Rogun PMG and other technical assistance (estimated cost of US$1.5 million). This component will finance: (a) strengthening of Rogun PMG team to implement the TA Project; (b) capacity building for Rogun PMG and Rogun JSC staff in dam safety, operation and management of hydro facilities, and project management; (c) Purchase of Information and Communication Technologies (ITC) and office equipment for Rogun PMG; (d) TA Project audits; and (e) incremental operating costs of Rogun PMG. III. Strategic Assessment of Country, Borrower and Marketplace a. Operational context Governance aspects. Government of the Republic of Tajikistan established the Rogun Open Joint Stock Company to own and operate the Rogun Hydropower Project (HPP). By the executive order of the President (No. 1361, dated October 26, 2012), Rogun PMG was established. It is the implementing entity for the construction of the Project. The HPP is being constructed on the Vakhsh River about 110 kilometers east of Dushanbe and about 70 kilometers upstream of the Nurek HPP. The dam will be 335 meters high and the facility will have generation capacity of 3,780 MW. This large hydropower project of 3,780 MW located on the Vakhsh cascade has the potential to generate a multitude of benefits for Tajikistan and the broader Central Asia (CA) region. For Tajikistan, the project could provide reliable electricity to meet growing domestic electricity demand at affordable costs. The legal and regulatory framework to be applicable to the key aspects of the TA Project is clear and well-defined. The World Bank Procurement Regulations applicable to the project take precedence over any conflicting regulations from the national public procurement laws. This has been enabled in the Constitution of the Republic of Tajikistan. The current Law on Public Procurement of Goods, Works and Services was adopted in March 2006 and was amended on April 16, 2012. The Government is working on preparation of a new PPL based on the UNCITRAL Model Law 2011 and the principles of the WTO GPA, and, in parallel, on the development of secondary legislation and standard bidding documents to be in line with the new draft 2 PPL. The licensing framework for provision of technical consulting services is clear. In addition, the consultants will be required to comply with the requirements of the World Bank’s relevant Environmental and Social Standards (ESS) as detailed in the relevant E&S documents prepared as well as the requirements of the local legislation related to labor policies. Economic aspects. In 2021, Tajikistan’s per capita income (GNI, Atlas method) was about US$1,100, which is slightly above the lower-middle- income threshold. The poverty rate fell from 17.8 percent in 2015 to about 13.9 percent in 2021. Tajikistan's economy relies heavily on primary commodity production and exports, with limited economic diversification. Domestic investment and consumption depend heavily on migrant remittances, which are about a third of GDP, thus leaving the economy highly vulnerable to external shocks. Sanctions on the Russian economy have exposed this vulnerability since Russia is the largest employer of Tajik migrant workers and is among the largest trading partners. Reforms aimed at private sector growth, public sector efficiency, and greater inclusion are vital to further economic development. Sustainability aspects. There are no issues with the sustainability aspects of the TA Project-financed activities since they only include advisory services and technical assistance for the needs of PMG. The proposed TA Project would contribute to strengthening the sustainability of the Rogun HPP Project by introducing requirements for good-practice E&S standards; robust criteria for E&S performance of the existing and new contractors; and design of community benefit sharing program that would contribute to equitable development and sustainable socio-economic growth at the local and national levels. Technological aspects. The assessments and studies under the TA Project will be relying on methodologies (such as hydropower planning, probable maximum flood modelling, least-cost system planning with economic optimization), which are considered to be standard for the hydropower sector and overall electricity industry. Therefore, there are no issues or risks to the grant-financed activities from technology-driven change or deployment of untested methods for technical studies. Key Conclusion. No major issues expected given that the grant would be financing primarily consulting services. b. Client Capability and PMG Assessment Experience. Rogun PMG will be responsible for the implementation of the Project. PMG staff consists of 34 persons. In its procurement activities, it is guided by the developed regulations, instructions, the Public Procurement Law of the Republic of Tajikistan, and the Rules for International Tender for Construction of Rogun Project. Rogun PMG has significant experience in implementing projects funded by the state budget including preparation of bidding documents for works and goods contracts, evaluation of bids, contract negotiations, and contract management. Rogun HPP team and the Resettlement Unit will be involved in reviewing the relevant documents, 3 reports, and outputs to be produced by the consultants to be hired by Rogun PMG. They would be involved in reviewing and approving the contractual, technical, environmental and social recommendations and advice to be provided by the consultants that would be hired by Rogun PMG , con. In addition to its primary function, Rogun PMG is also responsible for coordination of the activities with various ministries, departments and international financial organizations in the implementation of the state policy of the Republic of Tajikistan related to issues related to the construction of energy facilities and their upgrade in accordance with the programs of socio- economic development of the Republic of Tajikistan. The activities of the Rogun PMG related to procurement process include, among other things, the following: • Coordination of activities with ministries and departments, enterprises, institutions of Tajikistan and other international financial organizations related to the construction of energy facilities. • Ensuring, together with the authorized state bodies, the organization of the work of tender commissions related to the construction of power facilities. • Development and preparation of documentation for procurement of goods, works, consulting and non-consulting services for the construction of power facilities. • Monitoring the use of funds attracted and allocated by the Government of the Republic of Tajikistan for the implementation of projects for the construction of energy facilities. • Coordination and provision of working conditions for international and domestic specialists, consultants, experts in the preparation and implementation of projects. • Together with the authorized state bodies, organizing meetings with representatives of international organizations and, based on their results, providing information to the President of the Republic of Tajikistan. However, Rogun PMG does not have experience in implementation of projects financed by IFIs including the World Bank. It currently has one procurement consultant with experience in procurement in World Bank financed projects – CASA-1000 and Rural Electrification Project. The consultant will continue providing support to the Rogun PMG under her current financing until Rogun PMG selects a procurement specialist funded by the TA Project to carry out the required functions till the end of the TA Project. Her performance to date has been satisfactory. The procurement specialist will receive the required training to further strengthen the capacity in World Bank’s procurement rules and policies. Contract management capacity. Contract management is the responsibility of the relevant staff (director, manager, technical experts, etc.). Rogun PMG maintains an Excel file to track key contract dates. PMG has experience in managing contracts for similar projects such as pre- contract works on Rogun HPP Project that involved management of several 4 civil works contractors, construction of electricity transmission line projects for evacuation of electricity from Rogun HPP Project. In general, Rogun PMG will benefit from further training in contract management. Complaint management and dispute resolution systems. Rogun PMG will follow the requirements of The World Bank Procurement Regulations for IPF Borrowers (Nov 2020) in handling the complaints under consulting and goods contracts. Specifically, if a complaint is received, consistent with the requirements of an RFP or a request for bids, then Rogun PMG will respond to the complaint by ensuring the following minimum information is provided: (a) statement of issues; (b) facts and evidence; (c) decision and reference to the basis for the decision; and (d) analysis. Rogun PMG will act consistent with the roles and responsibilities of the Borrower/Recipient as specified in the World Bank Procurement Regulations Conclusions on PMG capacity. PMG has experience in implementing projects financed by the Government. However, it has no experience with the World Bank procurement procedures; have limited monitoring and contract management skills, as this function was mainly assigned to external consultants. The existing capacity is not sufficient to manage the growing volume of procurement activities across multiple projects running in parallel. Therefore, this will require further strengthening of PMG’s capacity to meet the TA Project needs. c. Market analysis Market sector dynamics. There are many specialized consulting firms that provide technical, economic analysis, environmental and social advisory, as well as financial and legal advisory services related to various aspects of hydropower projects and that have been very active in Tajikistan. These firms have been contracted to perform various large consulting assignments for new investment projects in the hydropower as well as rehabilitation projects; technical and economic assessments of new investments; feasibility studies; preparation of tender documentation; and preparation of environmental and social instruments/documents as required by various financial institutions; and financial and legal advisory for various project-level needs. Additionally, there have been strong interest from global individual experts to assume roles under the POE for dam safety and E&S issues. This has been demonstrated during implementation of techno-economic assessment studies (TEAS) for the Project as well as engagement of those experts for the needs of Nurek Hydropower Rehabilitation Project. Procurement risk analysis Keeping in view the nature of the consulting contracts to be procured under the TA Project, the main risks associated with the implementation of the TA Project and the proposed mitigation measures are described hereunder. Risk Description A B Overal Description of Risk l Risk proposed owner 5 Likelihood Impact Rating mitigation Rating Rating (A*B) through the procurement process Lack of interest 2 3 6 Procurement Rogun from reputable activities related to PMG international Rogun HPP that is a consultants. very large and complex project. Therefore, it is expected to generate significant interest from reputable international consultant. Moreover, competitive procurement is expected to be the main approach. Issues with 2 4 8 The TA Project Rogun contract would finance PMG management due capacity building to limited and training of the familiarity of relevant staff in Rogun PMG staff procurement and with Procurement contract Regulations of the management. World Bank. IV. Procurement objectives The main procurement objectives to be achieved are: • Advance preparation of TOR to avoid delays in procurement; • Monitoring of the procurement process so that the timing of each tender does not exceed the planned deadlines. V. Recommended Procurement Approach for a Grant Activity 1: Panel of Experts (POE) on Dam Safety Selection method for all nine POE members: International Competitive Selection. Individual consultant contracts (time-based). The POE will be comprised of various experts and those will need to be hired under individual contracts because POE members will need to be internationally renowned experts in their respective fields and the experience and qualifications of the individuals are of paramount requirement. This cannot be achieved through hiring of a firm. We will invite those individual consultants that we deem 6 qualified to provide the required consulting services. The complete TOR will be sent with the invitation. Estimated cost: The estimated cost of each POE member contract is presented in the Procurement Plan (PP) and is expected to range from US$142,000 to US$770,000 Duration of contract: The POE members will provide services during the period of May 2022 – April 2031. Level of risk: Low. Activity 2: Update of the environmental and social instruments of the Rogun HPP Project Selection method: Quality and Cost Based Solution (QCBS). International Competitive. Estimated cost: US$4,000,000. Duration of contract: June 2022 – June 2026. Risk level: Medium. Activity 3: POE on Social and Environmental Issues Selection method for all three POE members: International Competitive Selection. Individual consultant contracts (time-based). The POE will be comprised of various experts and those will need to be hired under individual contracts because POE members will need to be internationally renowned experts in their respective fields and the experience and qualifications of the individuals are of paramount requirement. This cannot be achieved through hiring of a firm. We will invite those individual consultants that we deem qualified to provide the required consulting services. The complete TOR will be sent with the invitation. Estimated cost: The estimated cost of each POE member contract is presented in the Procurement Plan (PP) and is expected to range from US$300,000 to US$574,000. Duration of contract: The POE members will provide services during the period of May 2022 – May 2031. Level of risk: Low. Activity 4: Update of the Project implementation completion schedule Selection method: Direct contract with joint venture of Tractebel-ELC (France-Italy). The direct contracting is justified for the following reasons: 7 a. The JV of Tractebel-ELC was selected in 2018 using international competitive process. The contract is financed by the Government. The consultant was hired to carry out update of the project implementation schedule, technical supervision of some construction activities and manage the interface among existing civil works contractors under Rogun HPP Project. The contract is still ongoing with the focus on technical supervision of construction works. b. The engagement of JV of Tractebel-ELC is justified because this assignment is related to ongoing services under the existing contract. The procurement is of both very low value and low risk. Estimated cost: US$100,000. Duration of contract: May 2022 – July 2022. Risk level: Low. Activity 5: Preparation of a financing plan to complete construction of the Project Selection method: Quality and Cost Based Solution (QCBS). International Competitive. Estimated cost: US$474,000. Duration of contract: July 2022 – September 2022. Risk level: Medium. Activity 6: Financial and legal advisor to negotiate and sign long- term power purchase agreements Selection method: Quality and Cost Based Solution (QCBS). International Competitive. Estimated cost: US$1,100,000. Duration of contract: August 2022 – June 2023. Risk level: Medium. Activity 7: Update of economic analysis of the Project Selection method: Direct contract with Poweren Consulting (UAE). This method is justified given that the Consultant has knowledge of the Project of exceptional worth to the needs of the assignment. The proposed consultant has previously completed a similar contract with the Borrower for detailed modelling of electricity sector, dispatch simulation, and valuation of economic costs and benefits of large hydro rehabilitation projects. The contract was under Nurek Hydropower Rehabilitation Project financed by the World Bank. Therefore, the Consultant can perform the task with much 8 greater speed and precision, which is of critical importance for the Rogun HPP. Without detailed and very rigorous updated economic analysis, based on the updated implementation schedule, it will be impossible to secure financing for the completion of the Rogun HPP. This, in turn, will create technical and safety risks. The performance of this consultant was satisfactory under the previous contract. Estimated cost: US$ 200,000. Duration of contract: July 2022 – October 2022. Risk level: Low. Activity 8: Purchase of IT and office equipment for Rogun PIG Selection method: Request for Quotation. Estimated cost: US$50,000. Duration of contract: September 2022. Risk level: Low. Activity 9: Audit of the annual financial statements of the grant Selection method: LCS. The audit firms will be selected from the World Bank’s list of auditors eligible to carry out Project audits. Estimated cost: US$20,000 per year (needs to be carried out for each year during 10-year implementation period of the TA) Duration of contract: Recurring. Risk level: Low. 9 Procurement plan Sl. Activity Estimated Procureme Contract Prior/pos N cost nt method signing date t review o in US$ (including taxes) 1 Dam Safety POE Dam engineering expert/POE 767,700 IC May 16, 2022 Post Chair Hydrology and sediment 108,300 IC May 16, 2022 Post management expert Engineering geology and 171,200 IC May 16, 2022 Post hydrogeology expert Geotechnical engineering expert 672,400 IC May 16, 2022 Post Hydraulics expert 672,400 IC May 16, 2022 Post Seismology and seismic design 142,300 IC May 16, 2022 Post expert 10 Sl. Activity Estimated Procureme Contract Prior/pos N cost nt method signing date t review o in US$ (including taxes) Electro-mechanical expert 672,400 IC May 16, 2022 Post Hydromechanical expert 199,510 IC May 16, 2022 Post Hydropower construction 409,800 IC May 16, 2022 Post management expert 2 E&S POE Hydrology and water resources 574,000 IC June 10, 2022 Post expert/POE Chair Environmental and planning 300,500 IC June 10, 2022 Post expert Social and resettlement expert 425,500 IC June 10, 2022 Post 3 Update of the environmental 4,000,000 QCBS July 20, 2022 Prior and social instruments of the Rogun HPP Project 4 Update of the Project 100,000 DS May 16, 2022 Post implementation completion schedule 5 Preparation of a financing plan 400,000 QCBS July 30, 2022 Post to complete construction of the Project 6 Financial and legal advisor to 1,100,000 QCBS July 30, 2022 Post negotiate and sign long-term power purchase agreements 7 Update of economic analysis of 200,000 DS July 20, 2022 Post the Project 8 Purchase of ICT and office 50,000 RFQ September 30, Post equipment for Rogun PIG 2022 9 Audit 200,000 LCS Annually Post 11 PROCUREMENT Tajikistan : Technical Assistance for Financing Framework for Rogun Hydropower Project PLAN General Information Country: Tajikistan Bank’s Approval Date of the Original Procurement Plan:2022-04-29 2023-06-05 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P178819 GPN Date: Project Name: Technical Assistance for Financing Framework for Rogun Hydropower Project Loan / Credit No: / , IDA / E1460 Project Management Group for Energy Facilities Construction under the President of the RT Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual RHPP/SH/G/01 / Purchase of I Request for Quota Single Stage - One E Pending Impl / Post Open - National 50,000.00 0.00 2022-07-06 2022-08-31 2022-09-30 CT and office equipment for tions nvelope ementation Rogun PIG NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual RHPP/CS/CQBS/03 / Financial and legal advisor to negotiat Quality And Cost- Open - Internationa / Post 1,100,000.00 0.00 Canceled 2022-07-01 2022-07-15 2022-08-19 2022-09-18 2022-10-09 2022-11-13 2022-12-11 2023-11-06 e and sign long-term power p Based Selection l urchase agreements RHPP/CS/CQBS/01 / Update Quality And Cost- Open - Internationa of the environmental and soc / Prior 4,000,000.00 0.00 Signed 2022-06-01 2022-05-04 2022-06-15 2022-05-31 2022-07-20 2022-07-16 2022-08-19 2022-08-24 2022-09-09 2022-09-11 2022-10-14 2022-11-17 2022-11-11 2026-11-10 Based Selection l ial instruments of the Rogun HPP Project RHPP/CS/CQBS/02 / Preparat Quality And Cost- Open - Internationa ion of a financing plan to co / Post 400,000.00 0.00 Canceled 2022-07-01 2022-07-15 2022-08-19 2022-09-18 2022-10-09 2022-11-13 2022-12-11 2023-03-11 Based Selection l mplete construction of the Pr oject Component 1: Development RHPP/CS/CQS/01 / Independ of macroeconomically sustai Consultant Qualifi Open - Internationa ent assessment of Lot 3 Cont / Post 180,000.00 0.00 Signed 2022-08-14 2022-08-02 2022-09-04 2022-08-19 2022-10-18 2022-09-05 2022-11-17 2022-11-04 2022-12-22 2023-02-20 nable financing plan and a c cation Selection l ract ommercial framework for Ro gun HPP project RHPP/CS/QCBS/02 / Preparat Component 1: Development ion of Rogun HPP Project Fina of macroeconomically sustai Quality And Cost- Open - Internationa Under Implement / Prior 1,500,000.00 0.00 2022-09-15 2022-09-01 2022-09-29 2022-09-09 2022-11-03 2022-12-28 2022-12-03 2023-02-02 2022-12-24 2023-03-15 2023-01-28 2023-06-01 2023-03-04 2023-10-30 ncing Plan and Development nable financing plan and a c Based Selection l ation of Power Purchase Agreemen ommercial framework for Ro ts for Rogun HPP gun HPP project RHPP/CS/QCBS/3 / Design an Component 3: Strengthening d Implementation Support for of E&S framework and benef Quality And Cost- Open - Internationa Under Implement IDA / E1460 Post 600,000.00 0.00 2023-02-23 2023-03-17 2023-03-09 2023-05-08 2023-04-13 2023-05-13 2023-06-03 2023-07-08 2023-08-12 2025-06-12 Benefit Sharing Program for it sharing aspects of Rogun Based Selection l ation Rogun HPP Project HPP Project RHPP/CS/QCBS/03 / Design o Component 3: Strengthening Quality And Cost- Open - Internationa f Benefit Sharing Program for / of E&S framework and benef Post 600,000.00 0.00 Canceled 2022-11-15 2022-12-30 2022-11-29 2023-01-17 2023-01-03 2023-02-02 2023-02-23 2023-03-30 2023-05-04 2024-05-03 Based Selection l Rogun HPP it sharing aspects of Rogun HPP Project RHPP/CS/CQS/02 / Audit of t he Quality Assurance and Qu Component 2: Improvement Consultant Qualifi Open - Internationa Under Implement IDA / E1460 Post 200,000.00 0.00 2023-03-31 2023-04-05 2023-04-14 2023-05-03 2023-05-19 2023-05-23 2023-06-02 2023-07-07 2023-09-05 ality Control Systems and As of the dam safety cation Selection l ation sociated Procedures followed for construction works RHPP/CS/CQS/03 / Seismic H Component 2: Improvement Consultant Qualifi Open - Internationa Pending Impleme IDA / E1460 Post 300,000.00 0.00 2023-06-30 2023-07-14 2023-08-18 2023-09-01 2023-10-06 2024-04-03 azard Update Study of the dam safety cation Selection l ntation RHPP/CS/CQS/04 / Sediment Component 2: Improvement Consultant Qualifi Open - Internationa Pending Impleme IDA / E1460 Post 300,000.00 0.00 2023-07-02 2023-07-16 2023-08-20 2023-09-03 2023-10-08 2024-04-05 ation Study of the dam safety cation Selection l ntation RHPP/CS/QCBS/05 / Hydrolo Component 2: Improvement Quality And Cost- Open - Internationa Pending Impleme IDA / E1460 Prior 1,000,000.00 0.00 2023-07-04 2023-07-18 2023-08-22 2023-09-21 2023-10-12 2023-11-16 2023-12-21 2024-12-20 gy and Climate Change Stud of the dam safety Based Selection l ntation y Component 1: Development RHPP/CS/ QCBS/04 / Electrici of macroeconomically sustai Quality And Cost- Open - Internationa Pending Impleme ty Sector Cost of Service Stu IDA / E1460 Post 350,000.00 0.00 2023-07-31 2023-08-14 2023-09-18 2023-10-18 2023-11-08 2023-12-13 2024-01-17 2024-07-21 nable financing plan and a c Based Selection l ntation dy ommercial framework for Ro gun HPP project RHPP/CS/CQS/05 / Support w Component 2: Improvement Consultant Qualifi Open - Internationa Pending Impleme ith Negotiation of Amendmen IDA / E1460 Post 295,000.00 0.00 2023-06-30 2023-07-14 2023-08-18 2023-09-01 2023-10-06 2024-02-08 of the dam safety cation Selection l ntation ts to Existing Contracts INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual RHPP/CS/IC/02 / Hydraulics e Individual Consult / Prior Limited 672,400.00 765,280.00 Signed 2022-05-04 2022-05-16 2022-05-09 2022-07-25 2022-05-19 2022-08-26 2022-06-12 2022-08-27 2031-06-10 xpert ant Selection Page 1 RHPP/CS/IC/03 / Geotechnica Individual Consult / Prior Limited 672,400.00 631,100.00 Signed 2022-05-04 2022-05-16 2022-05-09 2022-07-25 2022-05-19 2022-08-25 2022-06-12 2022-08-26 2031-06-10 l engineering expert ant Selection RHPP/CS/IC/04 / Electro-mec Individual Consult / Prior Limited 672,400.00 619,900.00 Signed 2022-05-04 2022-05-16 2022-05-09 2022-07-25 2022-05-19 2022-08-26 2022-06-12 2022-09-05 2031-06-10 hanical expert ant Selection RHPP/CS/DC/01 / Update of e Pending Impleme / Post Direct Selection Direct 200,000.00 0.00 2022-06-01 2022-06-07 2022-07-02 2022-09-30 conomic analysis of the Proje ntation ct RHPP/CS/DC/02 / Update of t Pending Impleme he Project implementation co / Post Direct Selection Direct 100,000.00 0.00 2022-06-01 2022-06-07 2022-07-02 2022-09-30 ntation mpletion schedule RHPP/CS/IC/01 / Dam engine Individual Consult / Prior Limited 767,700.00 554,750.00 Signed 2022-05-05 2022-05-16 2022-05-10 2022-07-25 2022-05-20 2022-08-23 2022-06-13 2022-08-25 2031-06-11 ering expert/POE Chair ant Selection RHPP/CS/IC/7 / Seismology a Component 2: Improvement Individual Consult / Post Open 142,300.00 431,640.00 Signed 2022-05-30 2022-07-26 2022-07-09 2022-08-17 2022-07-30 2022-08-24 2022-08-13 2022-08-26 2031-08-11 nd Seismic Design Expert of the dam safety ant Selection RHPP/CS/IC/6 / Engineering g Component 2: Improvement Individual Consult / Post Open 171,200.00 509,000.00 Signed 2022-05-30 2022-06-17 2022-07-09 2022-08-01 2022-07-30 2022-08-24 2022-08-13 2022-08-26 2031-08-11 eology and hydrogeology ex of the dam safety ant Selection pert RHPP/CS/IC/06 / Engineering Individual Consult / Post Limited 171,200.00 0.00 Canceled 2022-05-04 2022-05-09 2022-05-19 2022-06-12 2031-06-10 geology and hydrogeology e ant Selection xpert RHPP/CS/IC/07 / Seismology Individual Consult / Post Limited 142,300.00 0.00 Canceled 2022-05-04 2022-05-09 2022-05-19 2022-06-12 2031-06-10 and seismic design expert ant Selection RHPP/CS/IC/5 / Hydrology an Component 2: Improvement Individual Consult / Post Open 108,300.00 395,330.00 Signed 2022-05-30 2022-08-22 2022-07-09 2022-09-08 2022-07-30 2022-09-08 2022-08-13 2022-09-10 2031-08-11 d Sediment Management Exp of the dam safety ant Selection ert RHPP/CS/IC/05 / Hydrology a Individual Consult / Post Limited 108,300.00 0.00 Canceled 2022-05-04 2022-05-09 2022-05-19 2022-06-12 2031-06-10 nd sediment management ex ant Selection pert RHPP/CS/IC/8 / Hydromecha Component 2: Improvement Individual Consult / Post Open 199,510.00 287,960.00 Signed 2022-05-30 2022-05-25 2022-07-09 2022-07-25 2022-07-30 2022-08-24 2022-08-13 2022-08-26 2031-08-11 nical Expert of the dam safety ant Selection RHPP/CS/IC/08 / Hydromech Individual Consult / Post Limited 199,510.00 0.00 Canceled 2022-05-04 2022-05-09 2022-05-19 2022-06-12 2031-06-10 anical expert ant Selection RHPP/CS/IC/09 / Hydropower Individual Consult / Prior Limited 409,800.00 0.00 Canceled 2022-05-04 2022-05-09 2022-05-19 2022-06-12 2031-06-10 construction management ex ant Selection pert RHPP/CS/IC/10 / Hydrology a Individual Consult / Prior Limited 574,000.00 0.00 Canceled 2022-06-01 2022-06-06 2022-06-16 2022-07-10 2031-07-08 nd water resources expert/P ant Selection OE Chair RHPP/CS/IC/11 / Environmen Individual Consult / Prior Limited 300,500.00 0.00 Canceled 2022-06-01 2022-06-06 2022-06-16 2022-07-10 2031-07-08 tal and planning expert ant Selection RHPP/CS/IC/12 / Social and r Individual Consult / Prior Limited 425,500.00 0.00 Canceled 2022-06-01 2022-06-06 2022-06-16 2022-07-10 2031-07-08 esettlement expert ant Selection Component 3: Strengthening RHPP/CS/IC_12 / Social and r Individual Consult / of E&S framework and benef Prior Open 425,500.00 0.00 Signed 2022-06-20 2022-09-01 2022-07-30 2022-09-29 2022-08-20 2022-10-10 2022-09-03 2031-09-01 esettlement expert ant Selection it sharing aspects of Rogun HPP Project RHPP/CS/IC/9 / Hydropower Component 2: Improvement Individual Consult Open - Internationa / Prior 409,800.00 524,800.00 Signed 2022-08-14 2022-08-02 2022-10-02 2022-08-26 2022-10-23 2022-09-07 2022-11-27 2022-09-08 2023-05-26 Construction Management Ex of the dam safety ant Selection l pert Component 3: Strengthening RHPP/CS/IC_11 / Environmen Individual Consult Open - Internationa / of E&S framework and benef Prior 300,500.00 0.00 Signed 2022-08-08 2022-09-01 2022-09-26 2022-09-22 2022-10-17 2022-10-13 2022-11-21 2023-05-20 tal and planning expert ant Selection l it sharing aspects of Rogun HPP Project Component 1: Development RHHP/CS/DC/02 / Update of t of macroeconomically sustai Direct - Internation he Project implementation co / Post Direct Selection 150,000.00 0.00 Signed 2022-07-31 2022-08-02 2022-08-10 2022-08-05 2022-10-14 2023-04-12 nable financing plan and a c al mpletion schedule ommercial framework for Ro gun HPP project RHPP/CS/IC/13 / Senior Envir Component 3: Strengthening Individual Consult Open - Internationa onmental and Social Advisor / of E&S framework and benef Prior 430,000.00 0.00 Signed 2022-11-08 2022-10-31 2022-12-18 2022-11-16 2023-01-08 2022-11-17 2023-02-12 2024-03-18 ant Selection l for Rogun Project Manageme it sharing aspects of Rogun nt Group HPP Project RHHP/CS/DC/03 / Preparatio Component 2: Improvement Direct - Internation Under Implement n of Lot 4 bidding documents IDA / E1460 Post Direct Selection 565,000.00 0.00 2023-02-23 2023-03-10 2023-03-05 2023-05-09 2024-05-08 of the dam safety al ation and assistance during tender ing RHPP/CS/IC/10/ / Occupation Component 3: Strengthening Individual Consult Pending Impleme al Health and Safety Speciali IDA / E1460 of E&S framework and benef Post Limited 100,000.00 0.00 2023-06-29 2023-07-04 2023-07-14 2023-08-07 2025-02-04 ant Selection ntation st for Rogun PMG it sharing aspects of Rogun HPP Project RHPP/CS/IC_10 / Hydrology a Component 3: Strengthening Individual Consult nd water resources expert/P / of E&S framework and benef Prior Open 574,000.00 0.00 Canceled 2022-06-20 2022-09-01 2022-07-30 2022-08-20 2022-09-03 2031-09-01 ant Selection OE Chair it sharing aspects of Rogun HPP Project RHPP/ CS/IC/14 / Probity Adv Component 2: Improvement Individual Consult Open - Internationa Pending Impleme IDA / E1460 Post 65,000.00 0.00 2023-06-04 2023-07-14 2023-08-04 2023-09-08 2024-05-05 iser of the dam safety ant Selection l ntation RHPP/CS/DC/05 / Summary o Component 1: Development f existing capacity of hydrog of macroeconomically sustai en and ammonia production i Direct - Internation Pending Impleme IDA / E1460 nable financing plan and a c Post Direct Selection 30,000.00 0.00 2023-07-27 2023-08-06 2023-08-31 2023-10-30 n Tajikistan and overview of al ntation ommercial framework for Ro main existing global projects gun HPP project in advanced stages of develo pment RHPP/CS/DC/04 / Preliminary Component 1: Development evaluation of competitivenes of macroeconomically sustai Direct - Internation Pending Impleme s of green hydrogen and gre IDA / E1460 nable financing plan and a c Post Direct Selection 80,000.00 0.00 2023-07-31 2023-08-10 2023-09-04 2023-11-03 al ntation en ammonia production and ommercial framework for Ro exports from Tajikistan gun HPP project Page 2 PROCUREMENT PLAN (Textual Part) Project information: Mozambique P172657 - Improving Learning and Empowering Girls Project Implementation agency: Ministry of Education Date of the Procurement Plan: June 24, 2020 Period covered by this Procurement Plan: June 2020 – June 2021 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in Decree 5/2016 of March 8, 2016, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Not Applicable Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations: Not Applicable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works): None PROCUREMENT Mozambique : Improving Learning and Empowering Girls in Mozambique PLAN General Information Country: Mozambique 2020-06-24 Bank’s Approval Date of the Original Procurement Plan: 2023-06-05 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P172657 GPN Date: 2023-06-09 Project Name: Improving Learning and Empowering Girls in Mozambique Loan / Credit No: / , IDA / V3610, IDA / D7930, TF / B5326 Ministry of Education and Human Development Executing Agency(ies): WORKS Activity Reference No. / Procureme Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH Ri Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method nt Docume ount (US$ and Recommendation Signed Contract o. h cess (Y/N) sk atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion nt Type ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual National Proc 123/W/ILEGP/23 / Constructi urement Doc on of new Multimedia Studi Improving learning in primar Single Stage - One E Pending Imp 2024-02-1 IDA / D7930 Post Request for Bids Open - National ument - 1 En 0.00 2023-05-02 2023-05-08 2023-06-19 2023-07-18 2023-08-22 o, in Maputo province ( to be y education nvelope lementation 8 velope proce built by in IEDA plot) ss (Non Bank -SPD) 91/W/ILEGP/22 / Constructio Request for B n of 39 new ED centers in sc ids - Works ( hools, in all provinces (the in Improving learning in primar Single Stage - One E Pending Imp 2024-04-2 IDA / D7930 Prior Request for Bids Open - National without preq 0.00 2023-07-05 2023-07-10 2023-08-21 2023-09-20 2023-10-25 dication of the sites to be bui y education nvelope lementation 2 ualification) lt by IEDA to be provided to SPD DIEE) to be carried out by pr ovinces Request for B 133/W/ILEGP/23 / Constructi ids - Small W on of Support and learning C Improving learning in primar Single Stage - One E Pending Imp 2024-04-2 IDA / D7930 Prior Request for Bids Open - National orks SPD (1 e 0.00 2023-07-04 2023-07-10 2023-08-21 2023-09-20 2023-10-25 anters in Niassa, Cabo Delga y education nvelope lementation 2 nvelope proc do, Nampula, Zambezia and ess) Tete Province Request for B 144/W/ILEGP/23 / Constructi Increasing access and retent ids - Small W on of Support and learning C ion of girls in upper primary Single Stage - One E Pending Imp 2024-04-2 IDA / D7930 Prior Request for Bids Open - National orks SPD (1 e 0.00 2023-07-05 2023-07-10 2023-08-21 2023-09-20 2023-10-25 enters in Sofala, Manica, Inha and lower secondary educati nvelope lementation 2 nvelope proc mbane, Gaza and Maputo Pro on ess) vince Request for B 132/W/ILEGP/23 / Constructi ids - Small W on of 50 pre-primary centers Improving learning in primar Single Stage - One E Pending Imp 2024-04-2 IDA / D7930 Prior Request for Bids Open - National orks SPD (1 e 0.00 2023-07-06 2023-07-12 2023-08-23 2023-09-22 2023-10-27 in Niassa (20) and Cabo Delg y education nvelope lementation 4 nvelope proc ado (30) Province. ess) Request for B 134/W/ILEGP/23 / Constructi ids - Small W Improving learning in primar Single Stage - One E Pending Imp 2024-04-2 on of 50 pre-primary centers IDA / D7930 Prior Request for Bids Open - National orks SPD (1 e 0.00 2023-07-06 2023-07-12 2023-08-23 2023-09-22 2023-10-27 y education nvelope lementation 4 in Nampula (30) and Zambez nvelope proc ia (20) Provinces ess) GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MZ-MEDH-206235-GO-RFB / Increasing access and retent Open - Internationa Single Stage - One E Pending Impl Printing 6 million books of 1s / ion of girls in upper primary Prior Request for Bids 0.00 2020-11-25 2020-11-30 2021-01-11 2021-02-10 2021-03-17 2021-09-13 l nvelope ementation t, 2nd and 3rd grades. and lower secondary educati on MZ-MEDH-206915-GO-RFB / Increasing access and retent Printing and Distribution of th ion of girls in upper primary Single Stage - One E Pending Impl e new instrument of SICOLE / Post Request for Bids Open - National 0.00 2020-12-10 2020-12-15 2021-01-26 2021-02-25 2021-04-01 2021-09-28 and lower secondary educati nvelope ementation and printing 5.000 copies of t on he 3rd grade student's book, in Braille. 05/G/ILEGP/21 / Print 3,000, 000 copies of 1st class books Improving learning in primar Open - Internationa Single Stage - One E , 3,000,000 copies of 2nd Cla IDA / D7930 Prior Request for Bids 7,591,283.95 Signed 2021-08-10 2021-08-10 2021-08-15 2021-08-12 2021-09-29 2021-09-28 2021-10-19 2022-01-21 2021-11-17 2022-01-06 2022-02-28 y education l nvelope ss books, x copies of 5th clas s books and 6th class books f or the academic year 2022. 23/G/ILEGP/21 / IT Equipmen t's (Acquisition of computers, Project management, monit Single Stage - One E Pending Impl laptops, scanners and printe IDA / D7930 Post Request for Bids Open - National 0.00 2021-10-04 2021-10-09 2021-11-08 2021-11-23 2021-12-07 2022-06-05 oring and evaluation nvelope ementation rs for the project team includ ing project provincial coordin ators). 27/G/ILEGP/21 / Printing and Strengthening governance t Distribution of Modules of the o improve efficiency and mo Open - Internationa Single Stage - One E Under Imple TF / B5326 Prior Request for Bids 0.00 2021-10-15 2022-07-16 2021-10-20 2022-07-19 2021-12-01 2022-09-16 2021-12-31 2023-01-04 2022-02-04 2022-08-03 Secondary Distance Learning nitoring of education outcom l nvelope mentation Program of the first cycle es progress 33/NCS/ILEGP/22 / Storage o Improving learning in primar Request for Quota Single Stage - One E f Textbooks and Teaching Ma IDA / D7930 Prior Limited 469,794.06 Signed 2022-03-08 2022-07-29 2022-05-03 2022-08-13 2022-10-30 y education tions nvelope terials for year 2022 -Zona N orte 34/G/ILEGP/22 / Printing of t he books for 1st , 2nd , 3rd ( Improving learning in primar Open - Internationa Single Stage - One E Under Imple IDA / D7930 Prior Request for Bids 0.00 2022-03-14 2022-04-26 2022-03-19 2022-05-03 2022-05-03 2022-06-17 2022-06-02 2022-07-07 2023-01-03 mathematics) 5th and 6th g y education l nvelope mentation rade for the academic year 2 023. 51/G/ILEGP/22 / Printing 4,9 Improving learning in primar Open - Internationa Single Stage - One E Under Imple IDA / D7930 Prior Request for Bids 0.00 2022-06-15 2022-08-06 2022-06-20 2022-08-17 2022-08-01 2022-09-22 2022-08-31 2022-12-19 2022-10-05 2023-04-03 00,000 Units Fiches y education l nvelope mentation Increasing access and retent 54/G/ILEGP/22 / Forniture for Single Stage - One E Under Imple TF / B5326 ion of girls in upper primary Post Request for Bids Open - National 0.00 2022-07-13 2022-06-02 2022-07-18 2022-08-29 2022-07-15 2022-09-28 2022-11-02 2023-05-01 DL Center nvelope mentation and lower secondary educati on Increasing access and retent 57/G/ILEGP/22 / Equipment f Request for Quota Single Stage - One E Under Imple IDA / D7930 ion of girls in upper primary Post Open - National 0.00 2022-07-18 2022-09-12 2023-03-11 or Studio tions nvelope mentation and lower secondary educati on 56/G/ILEGP/22 / Print copies of the activities manual for c Increasing access and retent ommunity little school, the or ion of girls in upper primary Single Stage - One E Pending Impl IDA / D7930 Post Request for Bids Open - National 0.00 2022-07-06 2022-07-11 2022-08-22 2022-09-21 2022-10-26 2023-04-24 ientation manual for facilitat and lower secondary educati nvelope ementation ors and printing and layout b on rochures and exercise books for 1st cycle Increasing access and retent 58/G/ILEGP/22 / IT Equipmen Open - Internationa Single Stage - One E Under Revie IDA / D7930 ion of girls in upper primary Prior Request for Bids 0.00 2022-07-28 2022-08-02 2022-09-13 2022-10-13 2022-11-17 2023-05-16 t for IEDA l nvelope w and lower secondary educati on Page 1 62/G/ILEGP/22 / Supply of 15 Strengthening governance t 0 Motobyks including safety o improve efficiency and mo Single Stage - One E Pending Impl IDA / D7930 Post Request for Bids Open - National 0.00 2022-07-15 2022-07-20 2022-08-31 2022-09-30 2022-11-04 2023-05-03 equipment ( gloves and helm nitoring of education outcom nvelope ementation ets) for Coordinators of the L es progress earn Project 61/G/ILEGP/22 / Supply of sp ecific materials for students Increasing access and retent with SEN (10 Braille machine ion of girls in upper primary Single Stage - One E Pending Impl IDA / D7930 Post Request for Bids Open - National 0.00 2022-07-28 2022-08-02 2022-09-13 2022-10-13 2022-11-17 2023-01-16 s, 10 Braille forms and paper, and lower secondary educati nvelope ementation 5050 staves, 50 canes, 50 pu on nches and d 200 Dactilogy m aps in LS Strengthening governance t 70/G/ILEGP/22 / Supply of 75 Open - Internationa Single Stage - One E Under Imple IDA / D7930 o improve efficiency and mo Prior Request for Bids 0.00 2022-07-22 2022-07-27 2022-09-07 2022-10-07 2022-11-11 2023-05-10 Vehicles for the MINEDH l nvelope mentation nitoring of education outcom es progress 71/G/ILEGP/22 / Supply of p Strengthening governance t ersonal protective equipment o improve efficiency and mo Request for Quota Single Stage - One E Pending Impl (EP - Boots, Helmets, T-shirts IDA / D7930 Post Open - National 0.00 2022-07-30 2022-09-24 2022-10-24 nitoring of education outcom tions nvelope ementation , Shirts, Gloves, Glasses, Vest es progress s) for the 30 technicians of th e DIEE 77/G/ILEGP/22 / Illustration, l ayout, Printing and Distributi Increasing access and retent on of 30,000 copies of Broch ion of girls in upper primary Single Stage - One E Pending Impl IDA / D7930 Post Request for Bids Open - National 0.00 2022-08-01 2022-08-06 2022-09-05 2022-09-20 2022-10-25 2023-01-23 ures and exercise books for and lower secondary educati nvelope ementation Reading and writing Exercise on s for the 1st cycle (1st, 2nd a nd 3rd grades) 96/G/ILEGP/22 / Produce and Strengthening governance t Request for Quota Single Stage - One E Pending Impl print data collection maps for IDA / D7930 o improve efficiency and mo Post Open - National 0.00 2022-10-03 2022-11-28 2023-05-27 tions nvelope ementation the 2021 use and 2022 surve nitoring of education outcom y es progress 99/G/ILEGP/22 / Acquisition Increasing access and retent of 3 million calligraphy noteb ion of girls in upper primary Open - Internationa Single Stage - One E Pending Impl IDA / D7930 Prior Request for Bids 0.00 2022-09-28 2022-10-03 2022-11-14 2022-12-14 2023-01-18 2023-07-17 ooks and syllabic charts (1st, and lower secondary educati l nvelope ementation 2nd and 3rd grade) on 101/G/ILEGP/22 / Manuals of Increasing access and retent Single Stage - One E Pending Impl the continuous training strat IDA / D7930 ion of girls in upper primary Post Request for Bids Open - National 0.00 2022-09-27 2022-10-03 2022-11-14 2022-12-14 2023-01-18 2023-07-17 nvelope ementation egy for the Provinces of Nias and lower secondary educati sa and Manica on 95/G/ILEGP/22 / Printing of 2 500 copies of 1st cycle Secon Improving learning in primar Single Stage - One E Pending Impl IDA / D7930 Post Request for Bids Open - National 0.00 2022-10-27 2022-11-01 2022-12-13 2023-01-12 2023-02-16 2023-08-15 dary School Program, and 25 y education nvelope ementation 00 copies of 2nd cycle Secon dary School Program 100/G/ILEGP/22 / One (1) bra Increasing access and retent Request for Quota Single Stage - One E Under Imple ille printer to ensure the tran IDA / D7930 ion of girls in upper primary Post Limited 0.00 2022-10-17 2023-03-30 2022-12-12 2023-06-10 tions nvelope mentation sformation of NEE materials and lower secondary educati on 102/G/ILEGP/22 / Acquire 12 Increasing access and retent Request for Quota Single Stage - One E Under Imple 0 kits of History and Geograp IDA / D7930 ion of girls in upper primary Post Limited 0.00 2022-11-28 2022-11-18 2023-01-23 2023-07-22 tions nvelope mentation hy Maps for 120 schools and lower secondary educati on 105/DC/ILEGP/2022 / Acquisi Increasing access and retent tion of Off the Shelf Stock -Su ion of girls in upper primary Direct - Internation Under Imple IDA / D7930 Post Direct Selection 0.00 2022-11-16 2022-10-06 2022-11-21 2022-10-06 2022-12-26 2023-06-24 pply of Educational Material and lower secondary educati al mentation Textbooks for Grades 3 For S on chool Year 2023 105/G/ILEGP/22 / Acquire 50 Increasing access and retent Single Stage - One E Pending Impl 00 staves, Punches and 200 IDA / D7930 ion of girls in upper primary Post Request for Bids Open - National 0.00 2022-11-16 2022-11-21 2023-01-02 2023-02-01 2023-03-08 2023-09-04 nvelope ementation Dactilogy maps in LS and lower secondary educati on 108/G/ILEGP/22 / Acquire 33 Increasing access and retent Single Stage - One E Pending Impl solar panels to equip 60 DL C IDA / D7930 ion of girls in upper primary Post Request for Bids Open - National 0.00 2023-02-01 2023-02-06 2023-03-20 2023-04-19 2023-05-24 2023-11-20 nvelope ementation enters (CAA) and lower secondary educati on 107/G/ILEGP/22 / Printing of Strengthening governance t Single Stage - One E Pending Impl 2500 copies of 1st cycle Seco IDA / D7930 o improve efficiency and mo Post Request for Bids Open - National 0.00 2022-12-21 2022-12-26 2023-02-06 2023-03-08 2023-04-12 2023-10-09 nvelope ementation ndary School Program nitoring of education outcom es progress 112/G/ILEGP/22 / Reproduce and distribute information, e Increasing access and retent ducation and communication ion of girls in upper primary Single Stage - One E Pending Impl IDA / D7930 Post Request for Bids Open - National 0.00 2022-12-21 2022-12-26 2023-02-06 2023-03-08 2023-04-12 2023-10-09 materials on SRH and HIV & and lower secondary educati nvelope ementation AIDS (posters, leaflets and bo on oklets) in the 335 Programm e schools in the 7 provinces 104/G/ILEGP/22 / Equipment Strengthening governance t for support rooms for inclusiv o improve efficiency and mo Single Stage - One E Pending Impl e education in 10 secondary IDA / D7930 Post Request for Bids Open - National 0.00 2022-12-15 2022-12-20 2023-01-31 2023-03-02 2023-04-06 2023-10-03 nitoring of education outcom nvelope ementation schools to attend to students es progress with disabilities and SEN (4 n ew rooms) 84/G/ILEGP/22 / Print 2000 c Strengthening governance t opies of the activities manual o improve efficiency and mo Request for Quota Single Stage - One E Pending Impl for community school's and 2 IDA / D7930 Post Limited 0.00 2023-03-06 2023-05-01 2023-10-28 nitoring of education outcom tions nvelope ementation 000 of the orientation manua es progress l for facilitators/educators Increasing access and retent 122/G/ILEGP/23 / Forniture d Open - Internationa Single Stage - One E Pending Impl IDA / D7930 ion of girls in upper primary Prior Request for Bids 0.00 2023-05-24 2023-05-29 2023-07-10 2023-08-09 2023-09-13 2024-03-11 or 140 DL Center l nvelope ementation and lower secondary educati on 126/G/ILEGP/23 / Design and Increasing access and retent Single Stage - One E Pending Impl printing of the instruments of IDA / D7930 ion of girls in upper primary Post Request for Bids Open - National 0.00 2023-04-26 2023-05-01 2023-06-12 2023-07-12 2023-08-16 2024-02-12 nvelope ementation the National Evaluation of 20 and lower secondary educati 22 on 34/G/ILEGP/22-R / Printing of the books for 1st , 2nd , 3rd ( Improving learning in primar Open - Internationa Single Stage - One E Under Imple IDA / D7930 Prior Request for Bids 0.00 2023-03-30 2023-06-16 2023-04-04 2023-05-16 2022-06-17 2023-06-15 2023-06-27 2023-07-20 2024-01-16 mathematics) 5th and 6th gr y education l nvelope mentation ade for the academic year 20 23. Strengthening governance t 131/G/ILEGP/23 / Supply of 1 Open - Internationa Single Stage - One E Under Imple IDA / D7930 o improve efficiency and mo Prior Request for Bids 0.00 2023-06-07 2023-06-12 2023-07-24 2023-08-23 2023-09-27 2024-03-25 61 Vehicles for the MINEDH l nvelope mentation nitoring of education outcom es progress 128/G/ILEGP/23 / Acquire an d distribute 5000 hygiene an Improving learning in primar Single Stage - One E Pending Impl d digenite kits for girls in boa IDA / D7930 Post Request for Bids Open - National 0.00 2023-06-28 2023-07-04 2023-08-15 2023-09-14 2023-10-19 2024-04-16 y education nvelope ementation rding schools and homes in a ll the provinces of the countr y Page 2 140/G/ILEGP/23 / Framework Improving learning in primar Open - Internationa Single Stage - One E Under Imple Agreement – Grade 1,2,3 and IDA / D7930 Prior Request for Bids 0.00 2023-06-14 2023-06-19 2023-07-31 2023-08-30 2023-10-04 2024-04-01 y education l nvelope mentation 6 books Quadro 135/G/ILEGP/23 / IT Equipam Strengthening governance t Open - Internationa Single Stage - One E Pending Impl ent for DL Centers and MINE IDA / D7930 o improve efficiency and mo Prior Request for Bids 0.00 2023-06-30 2023-07-05 2023-08-16 2023-09-15 2023-10-20 2024-04-17 l nvelope ementation DH nitoring of education outcom es progress 149/G/ILEGP/23 / Motorcycle Increasing access and retent Single Stage - One E Pending Impl for ZIP Coordinators, teacher IDA / D7930 ion of girls in upper primary Prior Request for Bids Open - National 0.00 2023-07-05 2023-07-10 2023-08-21 2023-09-20 2023-10-25 2024-04-22 nvelope ementation s and mentors and lower secondary educati on 145/G/ILEGP/23 / Print 2000 copies of activity manuals for Improving learning in primar Request for Quota Single Stage - One E Pending Impl the community school and 2 IDA / D7930 Post Limited 0.00 2023-07-10 2023-09-04 2024-03-02 y education tions nvelope ementation 000 copies of guidelines for f acilitators/educators/animato rs NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 27/NCS/ILEGP/21 / Customs Strengthening governance t Single Stage - One E Clearance of Monolingual, Bili IDA / D7930 o improve efficiency and mo Post Request for Bids Open - National 968,918.72 Signed 2021-11-25 2021-12-10 2021-11-30 2021-12-14 2021-12-30 2022-01-11 2022-01-17 2022-02-18 2022-02-07 2022-03-12 2022-08-06 nvelope ngual and Braille Textbooks nitoring of education outcom 2021 and 2022. es progress 28/NCS/ILEGP/21 / Storage o Strengthening governance t Single Stage - One E f Textbooks and Teaching Ma IDA / D7930 o improve efficiency and mo Post Request for Bids Open - National 281,239.97 Signed 2021-12-12 2021-12-21 2021-12-17 2022-01-08 2022-01-28 2022-01-07 2022-02-27 2022-01-24 2022-04-03 2022-02-16 2022-09-30 nvelope terials for year 2022. nitoring of education outcom es progress 29/NCS/ILEGP/21 / Distributi Strengthening governance t Single Stage - One E Under Imple on of Textbooks and Teachin IDA / D7930 o improve efficiency and mo Post Request for Bids Open - National 0.00 2021-12-27 2022-01-06 2022-01-01 2022-01-06 2022-02-12 2022-01-27 2022-03-14 2022-03-28 2022-04-18 2022-10-15 nvelope mentation g Materials for year 2022. nitoring of education outcom es progress 60/NCS/ILEGP/22 / Customs Increasing access and retent Single Stage - One E Clearance of Monolingual, Bili IDA / D7930 ion of girls in upper primary Post Request for Bids Open - National 0.00 Signed 2022-07-12 2022-08-23 2022-07-17 2022-08-28 2022-09-27 2022-09-27 2022-10-14 2022-11-01 2023-04-30 nvelope ngual and Braille Textbooks and lower secondary educati 2023. on 74/NCS/ILEGP/22 / Provision Increasing access and retent Request for Quota Single Stage - One E Pending Impl of production services and in IDA / D7930 ion of girls in upper primary Post Open - National 0.00 2022-08-03 2022-09-28 2022-12-27 tions nvelope ementation sertion of advertising spots f and lower secondary educati or IEDA on 92/NCS/ILEGP/22 / Distributi Increasing access and retent Single Stage - One E Under Imple on of Textbooks and Teachin IDA / D7930 ion of girls in upper primary Post Request for Bids Open - National 0.00 2022-09-28 2022-10-31 2022-10-03 2022-11-04 2022-11-14 2023-01-19 2022-12-14 2023-01-17 2023-01-18 2023-07-17 nvelope mentation g Materials for year 2023. and lower secondary educati on 94/NCS/ILEGP/22 / Storage o Improving learning in primar Single Stage - One E Under Imple f Textbooks and Teaching Ma IDA / D7930 Post Request for Bids Open - National 0.00 2022-09-28 2022-08-26 2022-10-03 2022-11-14 2022-10-14 2022-12-14 2022-11-08 2023-01-18 2023-07-17 y education nvelope mentation terials for year 2023. 76/G/ILEGP/22 / Design, Prin Increasing access and retent ting, transportation and distri ion of girls in upper primary Single Stage - One E IDA / D7930 Post Request for Bids Open - National 0.00 Canceled 2022-07-29 2022-08-03 2022-09-14 2022-10-14 2022-11-18 2023-04-17 bution of the Instruments for and lower secondary educati nvelope the SEACMEQ V Main Study on 98/NCS/ILEGP/22 / Reproduc Increasing access and retent e copies of brochures and co ion of girls in upper primary Request for Quota Single Stage - One E Pending Impl pies of the Guide for the impl IDA / D7930 Post Limited 0.00 2022-10-24 2022-12-19 2023-06-17 and lower secondary educati tions nvelope ementation ementation of the Multi-Sect on oral Mechanism on Denuncia tion 76/NCS/ILEGP/22 / Transport Increasing access and retent Request for Quota Single Stage - One E Pending Impl ation and distribution of the I IDA / D7930 ion of girls in upper primary Post Limited 0.00 2022-10-24 2022-12-19 2023-06-17 tions nvelope ementation nstruments for the SEACMEQ and lower secondary educati V Main Study on 78/NCS/ILEGP/22 / Design, P Increasing access and retent Request for Quota Single Stage - One E Under Imple rinting of the Instruments for IDA / D7930 ion of girls in upper primary Post Limited 0.00 2022-10-17 2022-10-13 2022-12-12 2023-06-10 tions nvelope mentation the SEACMEQ V Main Study and lower secondary educati on 106/NCS/ILEGP/22 / Design, Increasing access and retent printing, transport and distrib ion of girls in upper primary Request for Quota Single Stage - One E Pending Impl IDA / D7930 Post Limited 0.00 2022-11-28 2023-01-23 2023-07-22 ution of the instruments of th and lower secondary educati tions nvelope ementation e National Evaluation of 2022 on 114/NCS/ILEGP/22 / Installati Increasing access and retent Single Stage - One E Pending Impl on of technological equipmen IDA / D7930 ion of girls in upper primary Post Request for Bids Open - National 0.00 2022-12-27 2023-01-03 2023-02-14 2023-03-16 2023-04-20 2023-10-17 nvelope ementation t in the CAAs and lower secondary educati on 113/NCS/ILEGP/22 / Customs Strengthening governance t Clearance of 12,986 Module o improve efficiency and mo Single Stage - One E Pending Impl IDA / D7930 Post Request for Bids Open - National 0.00 2022-12-14 2022-12-19 2023-01-30 2023-03-01 2023-04-05 2023-10-02 Kits of the Secondary Distanc nitoring of education outcom nvelope ementation e Learning Program (PESD) es progress 111/G/NCS/ILEGP/22 / Labor Increasing access and retent Request for Quota Single Stage - One E Pending Impl atory analysis of the 1st to 7t IDA / D7930 ion of girls in upper primary Post Limited 0.00 2023-01-03 2023-02-27 2023-08-26 tions nvelope ementation h grade textbooks. and lower secondary educati on 123/NCS/ILEGP/23 / Connecti Increasing access and retent Single Stage - One E Under Imple vity/internet services to supp IDA / D7930 ion of girls in upper primary Post Request for Bids Open - National 0.00 2023-04-26 2023-04-13 2023-05-01 2023-06-12 2023-07-12 2023-08-16 2024-02-12 nvelope mentation ort 200 Learning Center (CAA and lower secondary educati ) on 125/NCS/ILEGP/23 / Transpor Increasing access and retent Single Stage - One E Under Imple t and distribution of the instr IDA / D7930 ion of girls in upper primary Post Request for Bids Open - National 0.00 2023-04-19 2023-04-05 2023-04-24 2023-06-08 2023-06-05 2023-07-05 2023-08-09 2024-02-05 nvelope mentation uments of the National Evalu and lower secondary educati ation of 2022 on CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 22/CONS/ILEGP/21 / Hire a c onsultant for data collection, Improving learning in primar Consultant Qualifi Pending Impleme TF / B5326 Post Open - National 0.00 2021-09-20 2021-10-11 2021-11-15 2021-11-30 2021-12-15 2022-06-13 date entry and processing for y education cation Selection ntation the National Assessment pilo t study. Page 3 Strengthening governance t 25/CONS/ILEGP/21 / Indepen Quality And Cost- Under Implement TF / B5326 o improve efficiency and mo Prior Open - National 0.00 2021-09-17 2022-04-13 2021-10-08 2022-06-03 2021-11-21 2022-09-22 2021-12-19 2022-11-04 2021-12-27 2023-01-03 2022-01-31 2023-03-17 2022-03-07 2023-03-07 dent Verification Agent Based Selection ation nitoring of education outcom es progress Strengthening governance t 24/CONS/ILEGP/2021 / Hiring Least Cost Selecti Open - Internationa Under Implement TF / B5326 o improve efficiency and mo Post 0.00 2021-09-29 2021-12-14 2021-10-20 2022-01-05 2021-12-03 2021-12-31 2022-01-30 2022-03-06 2022-04-10 2022-10-07 of Financial Audit Services on l ation nitoring of education outcom es progress 32/CONS/ILEGP/21 / Consult Strengthening governance t ant Services to Assess Vulner o improve efficiency and mo Consultant Qualifi Under Implement ability and Prepare Executive IDA / D7930 Post Open - National 0.00 2021-12-28 2022-03-10 2022-01-18 2022-02-17 2022-02-15 2022-06-09 2022-03-17 2022-10-24 2022-04-21 2022-10-18 nitoring of education outcom cation Selection ation Projects for the Re-qualificati es progress on of Primary Schools. Zona Norte 30/CONS/ILEGP/21 / Consult Strengthening governance t ant Services to Assess Vulner o improve efficiency and mo Quality And Cost- Under Implement ability and Prepare Executive IDA / D7930 Post Open - National 0.00 2021-12-20 2022-03-10 2022-01-10 2022-02-17 2022-02-23 2022-05-17 2022-03-23 2022-07-12 2022-04-22 2022-08-04 2022-05-27 2022-09-09 2022-07-01 2022-12-30 nitoring of education outcom Based Selection ation Projects for the Requalificatio es progress n of Primary Schools. Zona C entro 31/CONS/ILEGP/21 / Consult Strengthening governance t ant Services to Assess Vulner o improve efficiency and mo Quality And Cost- Under Implement ability and Prepare Executive IDA / D7930 Post Open - National 0.00 2021-12-28 2022-03-10 2022-01-18 2022-02-17 2022-03-03 2022-06-13 2022-03-31 2022-07-12 2022-04-30 2022-06-04 2022-07-09 2023-01-08 nitoring of education outcom Based Selection ation Projects for the Re-qualificati es progress on of Primary Schools. Zona Sul 36/CONS/ILEGP/22 / Consulti Increasing access and retent Quality And Cost- Open - Internationa Under Implement ng service for editorial elabor IDA / D7930 ion of girls in upper primary Prior 0.00 2022-05-02 2022-05-24 2022-05-23 2022-05-26 2022-07-06 2022-11-04 2022-08-03 2022-09-02 2022-10-07 2022-11-11 2023-04-10 Based Selection l ation ation books of grade 7,8 and and lower secondary educati 9 ( Português) on 37/CONS/ILEGP/22 / Consulti Increasing access and retent Quality And Cost- Open - Internationa Under Implement ng service for editorial elabor IDA / D7930 ion of girls in upper primary Post 0.00 2022-05-02 2022-05-23 2022-05-23 2022-05-30 2022-07-06 2022-08-03 2022-09-02 2022-10-07 2022-11-11 2023-04-10 Based Selection l ation ation books of grade 7,8 and and lower secondary educati 9 (Inglês), on 38/CONS/ILEGP/22 / Consulti Increasing access and retent Quality And Cost- Open - Internationa Under Implement ng service for editorial elabor IDA / D7930 ion of girls in upper primary Post 0.00 2022-05-04 2022-05-24 2022-05-25 2022-05-30 2022-07-08 2022-08-05 2022-09-04 2022-10-09 2022-11-13 2023-04-20 Based Selection l ation ation books of grade 7,8 and and lower secondary educati 9 (Francês), on 40/CONS/ILEGP/22 / Consulti Increasing access and retent Quality And Cost- Under Implement ng service for editorial elabor IDA / D7930 ion of girls in upper primary Post Open - National 0.00 2022-05-03 2022-05-24 2022-05-24 2022-05-30 2022-07-07 2022-08-04 2022-09-03 2022-10-08 2022-11-12 2023-04-11 Based Selection ation ation books of grade 7,8 and and lower secondary educati 9 (História), on 41/CONS/ILEGP/22 / Consulti Increasing access and retent Quality And Cost- Under Implement ng service for editorial elabor IDA / D7930 ion of girls in upper primary Post Open - National 0.00 2022-05-04 2022-05-24 2022-05-25 2022-05-30 2022-07-08 2022-08-05 2022-09-04 2022-10-09 2022-11-13 2023-04-12 Based Selection ation ation books of grade 7,8 and and lower secondary educati 9 (Geografia) on 42/CONS/ILEGP/22 / Consulti Increasing access and retent Quality And Cost- Open - Internationa Under Implement ng service for editorial elabor IDA / D7930 ion of girls in upper primary Prior 0.00 2022-05-04 2022-05-23 2022-05-25 2022-06-08 2022-07-08 2022-10-19 2022-08-05 2022-09-04 2022-10-09 2022-11-13 2023-04-12 Based Selection l ation ation books of grade 7,8 and and lower secondary educati 9 (Matemática) on 43/CONS/ILEGP/22 / Consulti Increasing access and retent Quality And Cost- Under Implement ng service for editorial elabor IDA / D7930 ion of girls in upper primary Post Open - National 0.00 2022-05-05 2022-05-24 2022-05-26 2022-05-30 2022-07-09 2022-08-06 2022-09-05 2022-10-10 2022-11-14 2023-04-13 Based Selection ation ation books of grade 7,8 and and lower secondary educati 9 (Quimica) on 44/CONS/ILEGP/22 / Consulti Increasing access and retent Quality And Cost- Under Implement ng service for editorial elabor IDA / D7930 ion of girls in upper primary Post Open - National 0.00 2022-05-05 2022-05-24 2022-05-26 2022-05-30 2022-07-09 2022-08-06 2022-09-05 2022-10-10 2022-11-14 2023-04-13 Based Selection ation ation books of grade 7,8 and and lower secondary educati 9 (Física) on 45/CONS/ILEGP/22 / Consulti Increasing access and retent ng service for editorial elabor ion of girls in upper primary Quality And Cost- Under Implement IDA / D7930 Post Open - National 0.00 2022-05-05 2022-05-24 2022-05-26 2022-05-30 2022-07-09 2022-08-06 2022-09-05 2022-10-10 2022-11-14 2023-04-13 ation books of grade 7,8 and and lower secondary educati Based Selection ation 9 (Educação Visual) on 46/CONS/ILEGP/22 / Consulti Increasing access and retent Quality And Cost- Under Implement ng service for editorial elabor IDA / D7930 ion of girls in upper primary Post Open - National 0.00 2022-05-05 2022-05-24 2022-05-26 2022-05-30 2022-07-09 2022-08-06 2022-09-05 2022-10-10 2022-11-14 2023-04-13 Based Selection ation ation books of grade 7,8 and and lower secondary educati 9 (TIC) on 47/CS/ILEGP/22 / Consulting Strengthening governance t service for editorial elaborati o improve efficiency and mo Quality And Cost- Open - Internationa IDA / D7930 Prior 0.00 Canceled 2022-03-16 2022-04-06 2022-05-20 2022-06-17 2022-07-17 2022-08-19 2022-09-23 2023-09-23 on books of grade 7,8 and 9 nitoring of education outcom Based Selection l (first cycle), Secondary schoo es progress l-INDE 39/CONS/ILEGP/22 / Consulti Increasing access and retent Quality And Cost- Open - Internationa Under Implement ng service for editorial elabor IDA / D7930 ion of girls in upper primary Post 0.00 2022-05-03 2022-05-24 2022-05-24 2022-05-30 2022-07-07 2022-08-04 2022-09-03 2022-10-08 2022-11-12 2023-04-11 Based Selection l ation ation books of grade 7,8 and and lower secondary educati 9 (Biologia) on 59/CONS/ILEGP/22 / Procure Project management, monit Least Cost Selecti Under Implement IDA / D7930 Prior Open - National 0.00 2022-07-15 2022-08-11 2022-08-05 2022-08-16 2022-09-18 2022-10-19 2022-10-16 2022-12-09 2022-11-15 2023-01-03 2022-12-20 2023-04-13 2023-01-24 2023-07-23 ment Audit for years 2021 to oring and evaluation on ation 2023 75/CONS/ILEGP/22 / Technic Increasing access and retent al Assistance for the collectio ion of girls in upper primary Consultant Qualifi Under Implement n, typing, and processing of IDA / D7930 Post Open - National 0.00 2022-07-29 2022-08-09 2022-08-19 2022-09-06 2022-10-02 2022-11-04 2022-11-01 2022-12-06 2023-06-04 and lower secondary educati cation Selection ation data, and the elaboration of t on he report for the SEACMEQ V Main Study 72/CONS/ILEGP/22 / Consulti ng services for conduct a ba Increasing access and retent seline study of girls' and boy ion of girls in upper primary Consultant Qualifi Under Implement s' knowledge and information IDA / D7930 Post Open - National 0.00 2022-07-28 2022-08-23 2022-08-18 2022-10-01 2023-05-11 2022-10-31 2022-12-05 2023-06-03 and lower secondary educati cation Selection ation on SRH in selected schools, i on ncluding an analysis of the ri sk factors associated with GB V in schools 93/NCS/ILEGP/22 / Collection Increasing access and retent , data processing and prepar ion of girls in upper primary Quality And Cost- Open - Internationa ation of the report of the nati IDA / D7930 Prior 0.00 Under Review 2022-08-31 2022-09-24 2022-09-21 2022-10-04 2022-11-04 2023-06-15 2022-12-02 2023-05-26 2023-01-01 2023-02-05 2023-03-12 2024-03-11 and lower secondary educati Based Selection l onal approval of the monolin on gual and bilingual modalities in the revised curriculum 110/CS/ILEGP/22 / Consultan Increasing access and retent cy Service for harmony and r ion of girls in upper primary Consultant Qualifi IDA / D7930 Post Open - National 0.00 Canceled 2023-01-18 2023-03-23 2023-02-08 2023-03-24 2023-04-24 2023-05-29 2023-11-25 evise the program for sexual and lower secondary educati cation Selection health and reproductive and on HIV/SIDA 136/CS/ILEGP/23 / Supervisi Improving learning in primar Quality And Cost- Pending Impleme on of work of 30 pre-primary IDA / D7930 Prior Open - National 0.00 2023-09-06 2023-09-27 2023-11-10 2023-12-08 2024-01-08 2024-02-12 2024-03-18 2025-03-18 y education Based Selection ntation canters in Cabo Delgado Prov ince 137/CS/ILEGP/23 / Supervisi Improving learning in primar Quality And Cost- Pending Impleme on of work of 20 pre-primary IDA / D7930 Prior Open - National 0.00 2023-09-13 2023-10-04 2023-11-17 2023-12-15 2024-01-15 2024-02-19 2024-03-25 2025-03-25 y education Based Selection ntation canters in Niassa Province Page 4 138/CS/ILEGP/23 / Supervisi Improving learning in primar Quality And Cost- Pending Impleme on of work of 30 pre-primary IDA / D7930 Prior Open - National 0.00 2023-09-13 2023-10-04 2023-11-17 2023-12-15 2024-01-15 2024-02-19 2024-03-25 2025-03-25 y education Based Selection ntation canters in Nampula Province 139/CS/ILEGP/23 / Supervisi Improving learning in primar Quality And Cost- Pending Impleme on of work of 20 pre-primary IDA / D7930 Prior Open - National 0.00 2023-09-13 2023-10-04 2023-11-17 2023-12-15 2024-01-15 2024-02-19 2024-03-25 2025-03-25 y education Based Selection ntation canters in Zambezia Province 147-A/CS/ILEGP/23 / Service Increasing access and retent Provider for the implementati ion of girls in upper primary Quality And Cost- Open - Internationa Pending Impleme IDA / D7930 Prior 0.00 2023-06-29 2023-07-20 2023-09-04 2023-10-02 2023-11-01 2023-12-06 2024-01-10 2025-01-09 on of the Multisectoral Mecha and lower secondary educati Based Selection l ntation nism for the Prevention, Den on ouncement, Referral. 147/CS/ILEGP/23 / Service Pr Increasing access and retent ovider for the implementatio ion of girls in upper primary Quality And Cost- IDA / D7930 Post Open - National 0.00 Canceled 2023-06-06 2023-06-27 2023-08-10 2023-09-07 2023-10-07 2023-11-11 2023-12-16 2024-12-15 n of the Multisectoral Mechan and lower secondary educati Based Selection ism for the Prevention, Deno on uncement, Referral. INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Actual Amount Invitation to Identifie Draft Negotiated Cont Component Review Type Method Contract Type Process Status Teams of Reference Signed Contract Contract Completion Description o. h (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MZ-MEDH-181667-CS-INDV / Improving learning in primar Individual Consult Under Implement Development of environment / Post Limited 0.00 2020-06-24 2020-06-26 2020-06-29 2020-07-06 2020-07-20 2020-11-02 2020-08-24 2021-02-20 y education ant Selection ation al and social instruments. MZ-MEDH-206281-CS-INDV / Increasing access and retent Consultancy Services for the ion of girls in upper primary Individual Consult Pending Impleme / Post Limited 0.00 2020-11-30 2020-12-05 2020-12-26 2021-01-30 2021-07-29 Preparation of Environmental and lower secondary educati ant Selection ntation and Social studies on MZ-MEDH-206291-CS-INDV / Increasing access and retent Individual Consult Under Implement Gender Specialist and GBV M / ion of girls in upper primary Post Limited 0.00 2020-12-20 2021-11-30 2020-12-25 2021-01-15 2021-02-19 2021-08-18 ant Selection ation atters. and lower secondary educati on Increasing access and retent MZ-MEDH-206286-CS-CDS / / ion of girls in upper primary Prior Direct Selection Direct 0.00 Canceled 2020-12-10 2020-12-20 2021-02-23 2021-08-22 Procuremet Specialist. and lower secondary educati on MZ-MEDH-206246-CS-INDV / Increasing access and retent Individual Consult Pending Impleme Environmental Safeguards Sp / ion of girls in upper primary Post Limited 0.00 2020-12-15 2020-12-20 2021-01-10 2021-02-14 2021-08-13 ant Selection ntation ecialist for DIEE and lower secondary educati on MZ-MEDH-206272-CS-INDV / Increasing access and retent Individual Consult Pending Impleme Project Implementation Manu / ion of girls in upper primary Post Limited 0.00 2020-12-06 2020-12-11 2021-01-01 2021-02-05 2021-08-04 ant Selection ntation al (PIM). and lower secondary educati on MZ-MEDH-206288-CS-CDS / Increasing access and retent Financial management Speci / ion of girls in upper primary Post Direct Selection Direct 0.00 Canceled 2020-12-20 2020-12-30 2021-03-05 2021-09-01 alist and lower secondary educati on MZ-MEDH-206290-CS-CDS / Increasing access and retent Procurement Specialist for Bo / ion of girls in upper primary Prior Direct Selection Direct 0.00 Canceled 2020-12-30 2021-01-09 2021-03-15 2021-09-11 oks and Teaching Materials. and lower secondary educati on MZ-MEDH-206258-CS-CQS / Increasing access and retent Damage and vulnerability as ion of girls in upper primary Individual Consult Pending Impleme sessment of school infrastruc / Post Open 0.00 2020-12-15 2021-02-02 2021-02-23 2021-03-30 2021-09-26 and lower secondary educati ant Selection ntation ture, including sanitation and on water availability in schools MZ-MEDH-206265-CS-INDV / Increasing access and retent Technical Assistance to supp ion of girls in upper primary Individual Consult Under Implement / Post Limited 0.00 2020-12-15 2023-03-27 2020-12-20 2021-01-10 2021-02-14 2021-08-13 ort DIPLAC in statics analysis and lower secondary educati ant Selection ation and evaluation of the educati on on system. MZ-MEDH-206276-CS-INDV / Increasing access and retent Technical Assistance to the P ion of girls in upper primary Individual Consult Under Implement / Post Open 0.00 2020-11-29 2022-08-01 2021-01-17 2021-02-07 2021-03-14 2021-09-10 re-school Department and co and lower secondary educati ant Selection ation ordination with MGCAS. on 01/CONS/ILEGP/21 / Procure Project management, monit Individual Consult Under Implement ment Specialist for Books an IDA / V3610 Prior Open 0.00 2021-03-19 2021-03-15 2021-04-25 2021-05-07 2021-06-03 2022-06-03 oring and evaluation ant Selection ation d Teaching Materials 02/CONS/ILEGP/21 / Procure Project management, monit Individual Consult IDA / V3610 Prior Open 163,200.00 Signed 2021-04-05 2021-03-23 2021-05-12 2021-11-03 2021-05-27 2021-12-20 2021-06-24 2022-01-08 2022-06-24 ment Specialist oring and evaluation ant Selection 03/CON/ILEGP/21 / Financial Project management, monit Individual Consult Under Implement IDA / V3610 Post Open 0.00 2021-04-15 2021-11-30 2021-05-24 2021-06-08 2021-06-30 2022-06-30 Manager Specialist oring and evaluation ant Selection ation 04/CON/ILEGP/21 / Develop Improving learning in primar Individual Consult ment of Environmental and S IDA / V3610 Post Limited 110,500.00 Signed 2021-04-28 2021-04-26 2021-05-03 2020-06-30 2021-05-07 2020-10-15 2021-05-19 2020-10-23 2021-06-30 y education ant Selection ocial Instruments 06/CONS/ILEGP/21 / Project Project management, monit Individual Consult Under Implement IDA / D7930 Post Open 0.00 2021-09-03 2021-11-30 2021-10-09 2021-10-19 2021-11-05 2023-11-06 Coordinator oring and evaluation ant Selection ation 07/CONS/ILEGP/21 / Project Project management, monit Individual Consult Under Implement TF / B5326 Post Open 0.00 2021-09-06 2021-11-30 2021-10-16 2021-10-25 2021-11-08 2023-11-08 Accountant oring and evaluation ant Selection ation 08/CONS/ILEGP/21 / Social D Project management, monit Individual Consult Under Implement IDA / D7930 Post Open 0.00 2021-09-10 2021-09-16 2021-10-15 2021-10-22 2021-11-05 2023-11-06 evelopment Specialist oring and evaluation ant Selection ation 09/CONS/ILEGP/21 / Infrastru Project management, monit Individual Consult Under Implement TF / B5326 Post Open 0.00 2021-09-17 2021-11-30 2021-10-23 2021-10-28 2021-11-08 2023-11-08 cture Development Specialist oring and evaluation ant Selection ation 10/CONS/ILEGP/21 / Project Project management, monit Individual Consult Under Implement Provincial Coordinator - Cabo IDA / D7930 Post Open 0.00 2021-09-30 2021-09-16 2021-11-10 2021-11-25 2021-12-23 2023-12-26 oring and evaluation ant Selection ation Delegado Province 11/CONS/ILGEP/21 / Project Project management, monit Individual Consult Under Implement IDA / D7930 Post Open 0.00 2021-09-30 2021-11-30 2021-11-10 2021-11-25 2021-12-23 2023-12-26 Provincial Coordinator - Niass oring and evaluation ant Selection ation a Province 12/CONS/ILEGP/21 / Project Project management, monit Individual Consult Under Implement Provincial Coordinator - Nam IDA / D7930 Post Open 0.00 2021-09-30 2021-11-30 2021-11-10 2021-11-25 2021-12-23 2023-12-26 oring and evaluation ant Selection ation pula Province Page 5 13/CONS/ILEGP/21 / Project Project management, monit Individual Consult Provincial Coordinator - Zam IDA / D7930 Post Open 0.00 Signed 2021-09-30 2021-11-30 2021-11-10 2023-02-02 2021-11-25 2023-02-02 2021-12-23 2023-12-26 oring and evaluation ant Selection bézia Province 14/CONS/ILEGP/21 / Project Project management, monit Individual Consult Under Implement IDA / D7930 Post Open 0.00 2021-09-30 2021-11-30 2021-11-10 2021-11-25 2021-12-23 2023-12-26 Provincial Coordinator - Tete oring and evaluation ant Selection ation Province 15/CONS/ILEGP/21 / Project Project management, monit Individual Consult IDA / D7930 Post Open 0.00 Signed 2021-09-30 2021-11-30 2021-11-10 2022-06-15 2021-11-25 2022-06-17 2021-12-23 2023-12-26 Provincial Coordinator - Sofal oring and evaluation ant Selection a province 16/CONS/ILEGP/21 / Project Project management, monit Individual Consult Under Implement IDA / D7930 Post Open 0.00 2021-09-30 2021-11-30 2021-11-10 2021-11-25 2021-12-23 2023-12-26 Provincial Coordinator - Mani oring and evaluation ant Selection ation ca Province 17/CONS/ILEGP/21 / Project Project management, monit Individual Consult Under Implement Provincial Coordinator - Inha IDA / D7930 Post Open 0.00 2021-09-30 2021-11-30 2021-11-10 2021-11-25 2021-12-23 2023-12-26 oring and evaluation ant Selection ation mbane Province 18/CONS/ILEGP/21 / Project Project management, monit Individual Consult Under Implement IDA / D7930 Post Open 0.00 2021-09-30 2021-09-16 2021-11-10 2021-11-25 2021-12-23 2023-12-26 Provincial Coordinator - Gaza oring and evaluation ant Selection ation Province 19/CONS/ILEGP/21 / Project Project management, monit Individual Consult Under Implement IDA / D7930 Post Open 0.00 2021-09-30 2021-11-30 2021-11-10 2022-07-19 2021-11-25 2022-07-22 2021-12-23 2023-12-26 Provincial Coordinator - Mapu oring and evaluation ant Selection ation to Province 20/CONS/ILEGP/21 / Project Project management, monit Individual Consult Under Implement IDA / D7930 Post Open 0.00 2021-09-30 2021-11-30 2021-11-10 2021-11-25 2021-12-23 2023-12-26 Provincial Coordinator - Cida oring and evaluation ant Selection ation de de Maputo 35/CONS/ILEGP/22 / Procure Project management, monit Individual Consult IDA / D7930 Prior Direct 64,800.00 Signed 2022-04-04 2022-03-23 2022-04-14 2022-03-28 2022-05-05 2022-04-26 2022-06-09 2022-05-06 2022-12-06 ment Specialist oring and evaluation ant Selection 50/CONS/ILEGP/22 / Consult Improving learning in primar Individual Consult Pending Impleme ant for Publishing (Edition, La IDA / D7930 Post Limited 0.00 2022-05-31 2022-06-05 2022-06-13 2022-06-30 2022-08-29 y education ant Selection ntation yout, Pagination and Ilustrati on); Consultant 1 48/CONS/ILEGP/22 / Consult Improving learning in primar Individual Consult Pending Impleme ant for Publishing (Edition, La IDA / D7930 Post Limited 0.00 2022-05-31 2022-06-05 2022-06-13 2022-06-30 2022-08-29 y education ant Selection ntation yout, Pagination and Ilustrati on); Consultant 2 49/CONS/ILEGP/22 / Consult Improving learning in primar Individual Consult Pending Impleme ant for Publishing (Edition, La IDA / D7930 Post Limited 0.00 2022-05-31 2022-06-05 2022-06-13 2022-06-30 2022-08-29 y education ant Selection ntation yout, Pagination and Ilustrati on); Consultant 3 63/CONS/ILEGP/22 / Speciali Increasing access and retent Individual Consult Under Implement st for Quality Control for file IDA / D7930 ion of girls in upper primary Post Open 0.00 2022-07-18 2022-07-28 2022-09-05 2022-09-26 2022-10-31 2023-04-29 ant Selection ation notes (fichas) for class 7. Co and lower secondary educati nsultant 1 on 64/CONS/ILEGP/22 / Speciali Increasing access and retent Individual Consult Under Implement st for Quality Control for file IDA / D7930 ion of girls in upper primary Post Open 0.00 2022-07-18 2022-07-28 2022-09-05 2022-09-26 2022-10-31 2023-04-29 ant Selection ation notes (fichas) for class 7 Con and lower secondary educati sultant 2 on 65/CONS/ILEGP/22 / Speciali Increasing access and retent Individual Consult Under Implement st for Quality Control for file IDA / D7930 ion of girls in upper primary Post Open 0.00 2022-07-18 2022-07-28 2022-09-05 2022-09-26 2022-10-31 2023-04-29 ant Selection ation notes (fichas) for class 7. Co and lower secondary educati nsultant 3 on 66/CONS/ILEGP/22 / Speciali Increasing access and retent Individual Consult Under Implement st for Quality Control for file IDA / D7930 ion of girls in upper primary Post Open 0.00 2022-07-18 2022-07-28 2022-09-05 2022-09-26 2022-10-31 2023-04-29 ant Selection ation notes (fichas) for class 7 Con and lower secondary educati sultant 4 on 67/CONS/ILEGP/22 / Speciali Increasing access and retent Individual Consult Under Implement st for Quality Control for file IDA / D7930 ion of girls in upper primary Post Open 0.00 2022-07-18 2022-07-28 2022-09-05 2022-09-26 2022-10-31 2023-04-29 ant Selection ation notes (fichas) for class 7. Co and lower secondary educati nsultant 5 on 68/CONS/ILEGP/22 / Speciali Increasing access and retent Individual Consult Under Implement st for Quality Control for file IDA / D7930 ion of girls in upper primary Post Open 0.00 2022-07-18 2022-07-28 2022-09-05 2022-09-26 2022-10-31 2023-04-29 ant Selection ation notes (fichas) for class 7 Con and lower secondary educati sultant 6 on 69/CONS/ILEGP/22 / Speciali Increasing access and retent Individual Consult Under Implement st for Quality Control for file IDA / D7930 ion of girls in upper primary Post Open 0.00 2022-07-18 2022-07-28 2022-09-05 2022-09-26 2022-10-31 2023-04-29 ant Selection ation notes (fichas) for class 7. Co and lower secondary educati nsultant 7 on 73/CONS/ILEGP/22 / Procure Project management, monit Direct - Internation Under Implement IDA / D7930 Prior Direct Selection 0.00 2022-07-22 2022-07-29 2022-08-01 2022-08-04 2022-10-05 2023-04-03 ment Audit for year 2020 oring and evaluation al ation 52/CONS/ILEGP/22 / Procure Project management, monit Individual Consult IDA / D7930 Prior Direct 0.00 Canceled 2022-06-06 2022-06-16 2022-06-20 2022-06-30 2024-06-30 ment Specialist oring and evaluation ant Selection 94/IC/ILEGP/22 / Senior Proc Project management, monit Individual Consult Open - Internationa Under Implement IDA / D7930 Prior 0.00 2022-08-17 2022-08-29 2022-10-05 2023-04-12 2022-10-26 2023-05-24 2022-11-30 2023-05-29 urement Specialist oring and evaluation ant Selection l ation 109/IC/ILEGP/22 / Technical Increasing access and retent Assistance to design the mon ion of girls in upper primary Individual Consult Under Implement IDA / D7930 Post Open - National 0.00 2022-12-14 2022-12-28 2023-02-01 2023-02-22 2023-03-29 2023-09-25 itoring system foe the attend and lower secondary educati ant Selection ation ance, punctuality and attend on ance for teacher’s 103/IC/ILEGP/22 / Individual Consultant for psychometric Project management, monit Individual Consult Under Implement IDA / D7930 Post Open - National 0.00 2023-01-11 2023-02-27 2023-03-01 2023-03-22 2023-04-26 2023-10-23 and data analysis and suppor oring and evaluation ant Selection ation t in the preparation of the 20 22 National 90/IC/ILEGP/22 / Individual C onsultant to support INDE in Project management, monit Individual Consult Pending Impleme IDA / D7930 Post Open - National 0.00 2023-01-25 2023-03-15 2023-04-05 2023-05-10 2023-11-06 the implementation of Large oring and evaluation ant Selection ntation Scale Assessments 81/IC/ILEGP/23 / Senior Acco Project management, monit Individual Consult Under Implement IDA / D7930 Post Limited 0.00 2023-04-03 2023-03-22 2023-04-10 2023-05-01 2023-06-05 2025-05-05 untant I oring and evaluation ant Selection ation 82/IC/ILEGP/23 / Senior Acco Project management, monit Individual Consult Under Implement IDA / D7930 Post Limited 0.00 2023-04-03 2023-03-22 2023-04-10 2023-05-01 2023-06-05 2025-05-05 untant II oring and evaluation ant Selection ation 80/IC/ILEGP/23 / Financer Ma Project management, monit Individual Consult Under Implement IDA / D7930 Post Limited 0.00 2023-04-03 2023-03-22 2023-04-10 2023-05-01 2023-06-05 2025-05-05 nagement oring and evaluation ant Selection ation 83-A/IC/ILEGP/23 / Financial Project management, monit Individual Consult Under Implement IDA / D7930 Post Limited 0.00 2023-04-19 2023-04-06 2023-04-24 2023-05-15 2023-06-19 2023-12-16 Assistant oring and evaluation ant Selection ation 83/IC/ILEGP/23 / Financial As Project management, monit Individual Consult IDA / D7930 Prior Limited 0.00 Canceled 2023-04-03 2023-04-10 2023-05-01 2023-06-05 2025-05-05 sistant oring and evaluation ant Selection Page 6 110/IC/ILEGP/23 / Consultan cy Service for harmony and r Improving learning in primar Individual Consult Pending Impleme IDA / D7930 Post Open - National 0.00 2023-05-02 2023-06-20 2023-07-11 2023-08-15 2024-02-11 evise the program for sexual y education ant Selection ntation health and reproductive and HIV/SIDA 142/IC/ILEGP/23 / Procureme Project management, monit Individual Consult Under Implement IDA / D7930 Prior Open - National 0.00 2023-06-01 2023-06-15 2023-07-24 2023-08-14 2023-09-18 2024-03-16 nt Specialist I oring and evaluation ant Selection ation 143/IC/ILEGP/23 / Procureme Project management, monit Individual Consult Under Implement IDA / D7930 Prior Open - National 0.00 2023-06-01 2023-06-20 2023-07-24 2023-08-14 2023-09-18 2024-03-16 nt Specialist oring and evaluation ant Selection ation Page 7 Procurement Plan General 1. Bank’s approval Date of the procurement Plan January 28, 2022 2. Date of General Procurement Notice: February 22, 2022 3. Period covered by this procurement plan: 18 Months (January 2022 to August, 2023) II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Annex II to the Regulation for Procurement: No. Procurement Method Prior Review Threshold Comments US$ 1. ICB and LIB (Goods) Above US$ 2,000,000 All 2. NCB (Goods) Above US$ 2,000,000 All 3. ICB (Works) Above US$ 10,000,000 All 4. NCB (Works) Above US$ 10,000,000 All 5. (Non-Consultant Services) Above US$ 2,000,000 All 2. Prequalification. Bidders when applicable_ shall be prequalified in accordance with the provisions of paragraphs 6.23 and 6.24 of the Regulation. 3. Proposed Procedures for CDD Components (as per paragraph. 6.9 of the Regulations: Not applicable 4. Reference to (if any) Project Operational/Procurement Manual: Project Implementation Manual for World Bank Loan Project 5. Any Other Special Procurement Arrangements: Not Applicable 6. Summary of the Procurement Packages planned during the first 18 months after project effectiveness (including those that are subject to retroactive financing and advanced procurement) 1 2 3 4 5 6 7 Estimate Domesti Review Ref d Packag c by Bank . Description Cost es Prefere (Prior / Comments No. US$ nce Post) million (yes/no) January 17, 2022 Summary of the 1 RFB- 8.200 2 No Prior International/DIR. (Goods) Summary of the 2 RFB-National/RFQ 7.584 12 No Post (Goods) 3 Summary of the RFB-International, 9.000 1 No Prior Dir/Limited (Works) 4 Summary of the RFB-National/RFQ 13.049 9 No Post (Works) III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Annex II to the Regulation Selection and Employment of Consultants: Selection Method Prior Review Threshold Comments 1. Competitive Methods Above US$ 1,000,000 (Firms) 2. Single Source (Firms) All 3. Individual Above US$ 300,000 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $300,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of the Consultant Regulations 3. Any Other Special Selection Arrangements: Not Applicable 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 Ref Description of Estimated Review . Assignment Cost Packag by Bank Commen No. US$ es (Prior / ts million Post) Summary of 2.000 3 Prior 1number of contracts that will be let under QCBS Summary of 26 2 number of 2.488 Post contracts that will January 17, 2022 be let under other methods January 17, 2022 PROCUREMENT Western and Central Africa : West Africa Food System Resilience Program (FSRP) Phase 2 PLAN General Information Country: Western and Central Africa 2023-01-17 Bank’s Approval Date of the Original Procurement Plan: 2023-06-05 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P178132 GPN Date: 2023-06-27 Project Name: West Africa Food System Resilience Program (FSRP) Phase 2 Loan / Credit No: IDA / E1160 Ministry of Agriculture and Food Security Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned SL-MAFS-348035-CW-RFQ / Engagement of Contractor fo r the rehabilitation of Office s Digital Advisory Services for Request for Quota Request for Quota Single Stage - One E Pending Imp 2023-11-1 pace for Project Management IDA / E1160 Agriculture and Food Crisis P Post Limited tions (Non Bank-S 118,000.00 0.00 2023-03-25 2023-05-20 tions nvelope lementation 6 Unit and Renovation of Planni reventionand Management PD) ng Evaluation Monitoring and Statistics data processing roo m both Offices are in Freeto wn GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SL-MAFS-348020-GO-RFQ / P rocurement of Furniture for P Request for Quota Single Stage - One E Pending Impl IDA / E1160 Project Management Post Limited 96,000.00 0.00 2023-03-25 2023-05-20 2023-11-16 roject Management Unit Offic tions nvelope ementation e (Office, tables, chairs, etc) SL-MAFS-348027-GO-RFB / P Digital Advisory Services for rocurement of 19 Vehicles (1 Single Stage - One E Pending Impl IDA / E1160 Agriculture and Food Crisis P Post Request for Bids Open - National 850,000.00 0.00 2023-08-29 2023-09-03 2023-10-15 2023-11-14 2023-12-19 2024-06-16 3-Double Cabin, 2- pick-up tr nvelope ementation reventionand Management ucks and 4 Station Wagon) SL-MAFS-348038-GO-RFQ / P Sustainability and Adaptive Request for Quota Single Stage - One E Pending Impl rocurement of 21 Motor Bike IDA / E1160 Capacity of the Food System Post Limited 61,500.00 0.00 2023-09-05 2023-10-31 2024-04-28 tions nvelope ementation s with Helmets 's Productive Base SL-MAFS-348086-GO-RFB / P Sustainability and Adaptive rocurement of 400 tons soil li Single Stage - One E Pending Impl IDA / E1160 Capacity of the Food System Post Request for Bids Open - National 600,000.00 0.00 2023-08-31 2023-09-05 2023-10-17 2023-11-16 2023-12-21 2024-06-18 me for soil restoration in land nvelope ementation 's Productive Base valley swamp (IVS) locations SL-MAFS-348113-GO-RFB / P rocurement of 31 Laptop Co Digital Advisory Services for Single Stage - One E Pending Impl mputers, 64 Tablets, 32 Reco IDA / E1160 Agriculture and Food Crisis P Post Request for Bids Open - National 205,400.00 0.00 2023-07-31 2023-08-05 2023-09-16 2023-10-16 2023-11-20 2024-05-18 nvelope ementation rders, 108 smart phones Prin reventionand Management ter, Scanner and Photocopier SL-MAFS-348105-GO-RFB / P rocurement of 12 Tons of Fer Contingent Emergency Resp Single Stage - One E Pending Impl IDA / E1160 Post Request for Bids Open - National 200,000.00 0.00 2023-08-31 2023-09-05 2023-10-17 2023-11-16 2023-12-21 2024-06-18 tilizer for farmers and school onse (CERC) nvelope ementation garden and Pesticides for sch ool gardens SL-MAFS-365420-GO-RFQ / p rocurement, Installation, Trai Digital Advisory Services for Request for Quota Under Imple ning and configuration of Qui IDA / E1160 Agriculture and Food Crisis P Post 30,000.00 0.00 2023-07-31 2023-06-08 2023-07-31 2023-07-31 tions mentation ckBooks Enterprise Solution reventionand Management Software (Financial Managem ent Software) NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SL-MAFS-365411-CS-CQS / H iring of a Consultant to desig n, supervise and train the dril Sustainability and Adaptive ling and construction of 20 b Consultant Qualifi Pending Impleme IDA / E1160 Capacity of the Food System Post Open - National 150,000.00 0.00 2023-08-31 2023-09-21 2023-11-04 2023-12-04 2024-01-08 2024-07-06 oreholes which includes 10 g cation Selection ntation 's Productive Base roundwater monitoring statio ns and 10 solar powered bor eholes, and the location is th e 14 project districts. INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SL-MAFS-335750-CS-INDV / Recruitment of Emergency R Contingent Emergency Resp Individual Consult Under Implement esponse Technical Lead for t IDA / E1160 Post Open - National 84,000.00 0.00 2023-01-25 2023-01-18 2023-03-15 2023-04-05 2023-05-10 2023-11-06 onse (CERC) ant Selection ation he Contingent Emergency Re sponse Component (CERC) SL-MAFS-348133-CS-INDV / Individual Consult Under Implement Recruitment of Consultant to IDA / E1160 Project Management Post Open - National 61,280.00 0.00 2023-05-25 2023-06-02 2023-07-13 2023-08-03 2023-09-07 2024-03-05 ant Selection ation Conduct Baseline Survey for FSRP Page 1 SL-MAFS-348139-CS-INDV / Individual Consult Under Implement Recruitment of Consultant to IDA / E1160 Project Management Post Open - National 61,280.00 0.00 2023-05-26 2023-06-02 2023-07-14 2023-08-04 2023-09-08 2024-03-06 ant Selection ation Develop the M& E plan SL-MAFS-348157-CS-INDV / Individual Consult Under Implement Recruitment of Consultant to IDA / E1160 Project Management Post Open - National 51,000.00 0.00 2023-04-28 2023-03-29 2023-06-16 2023-07-07 2023-08-11 2024-02-07 ant Selection ation Develop Food Security Action Plan SL-MAFS-348128-CS-INDV / Recruitment of Consultant to Conduct diagnostic Integrate d Landscape Management su Sustainability and Adaptive Individual Consult Pending Impleme rvey in four targeted areas in IDA / E1160 Capacity of the Food System Post Open - National 41,900.00 0.00 2023-08-31 2023-10-19 2023-11-09 2023-12-14 2024-06-11 ant Selection ntation watershed areas (Gbondape 's Productive Base Watershed-Bonthe), Moa and Mano Watershed-Pujehun), G reat Scares and Little Scarce s-Kambia and Rokel Rive- To nkolili SL-MAFS-348124-CS-INDV / Recruitment of Consultant to Study and assess existing res Sustainability and Adaptive earch capacity at National Ce Individual Consult Pending Impleme IDA / E1160 Capacity of the Food System Post Open - National 20,000.00 0.00 2023-08-25 2023-10-13 2023-11-03 2023-12-08 2024-06-05 nter of Specialization (NCoS) ant Selection ntation 's Productive Base and Regional Center of Excell ence (RCoE) and develop acti on plans for Njala Agricultura l Research Center and Rokup rr SL-MAFS-348117-CS-INDV / Recruitment of Consultant to Digital Advisory Services for Individual Consult Pending Impleme Review and assess the availa IDA / E1160 Agriculture and Food Crisis P Post Open - National 25,530.00 0.00 2023-05-31 2023-07-19 2023-08-09 2023-09-13 2024-03-11 ant Selection ntation ble decision support in Food reventionand Management security national early warni ng systems SL-MAFS-348129-CS-INDV / Sustainability and Adaptive Recruitment of Consultant to Individual Consult Pending Impleme IDA / E1160 Capacity of the Food System Post Open - National 61,280.00 0.00 2023-08-31 2023-10-19 2023-11-09 2023-12-14 2024-06-11 Develop national action plan ant Selection ntation 's Productive Base s for the rice and cassava val ue chains SL-MAFS-348142-CS-INDV / Individual Consult Pending Impleme Hiring of consultant to Devel IDA / E1160 Project Management Post Open - National 40,850.00 0.00 2023-08-31 2023-10-19 2023-11-09 2023-12-14 2024-06-11 ant Selection ntation op communication plan SL-MAFS-337197-CS-INDV / Recruitment of Consultant to Update and Prepare Environ Digital Advisory Services for mental Social Management F IDA / E1160 Agriculture and Food Crisis P Post Direct Selection Direct - National 50,000.00 0.00 Canceled 2023-02-13 2023-01-23 2023-02-23 2023-01-26 2023-04-29 2023-10-26 ramework (ESMF) Addendum reventionand Management of CERC (CERC-ESMF) Grieva nce Mechanism and GBV/SEA /SH Action Plan for FSRP Proj ect. SL-MAFS-348155-CS-CDS / R ecruitment of Consultant to IDA / E1160 Project Management Post Direct Selection 15,000.00 0.00 Canceled 2023-03-17 2023-03-27 2023-05-31 2023-11-27 Develop Stakeholder Engage ment Plan of FSRP Page 2 18 MONTHS PROCUREMENT PLAN Project information: Liberia; Monrovia Integrated Development Project (MIDP); P169718 Project Implementation Agency: Ministry of Public Works Date of the Procurement Plan: September 2021 Period covered by this Procurement Plan: September 2021-December 2022 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (November 2020) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitutes the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the Public Procurement and Concessions Act, 2010 of the Republic of Liberia, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations. In accordance with paragraph 5.3 of the Procurement Regulations, the request for bids/request for proposals document shall require that Bidders/Proposers submitting Bids/Proposals present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights. The form of the Letter of Acceptance is attached in Appendix 1. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. Not Applicable Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables. Not Applicable. Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: Not Applicable for those contracts identified in the Procurement Plan tables; Works: Not Applicable for those contracts identified in the Procurement Plan tables. Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations: Not Applicable. Other Relevant Procurement Information: (a). Prior Procurement Arrangements: The Procurement Arrangements as indicated in the below table and within the thresholds indicated in the below tables will be used. The thresholds for the Bank’s prior review requirements are also provided in the table below: Table: Thresholds*, Procurement Arrangements, and Prior Review (The table below depicts the Thresholds and Procurement Methods to be used under the MIDP project): Thresholds*, Procurement Methods, and Prior Review Contract (C) Value Expenditure Procurement Contracts Subject to No Threshold* [eq. Category Method Prior Review /[eq. US$] USD] All contracts at or above USD 10,000,000 are subject to Open Competition international advertising and C ≥ 5,000,000 International Market the use of the Bank’s SPDs (or Approach 1 Works other documents agreed with the Bank). Open Competition 200,000 < C < 5,000,000 None National Contract (C) Value Expenditure Procurement Contracts Subject to No Threshold* [eq. Category Method Prior Review /[eq. US$] USD] Request for ≤ 200,000 Quotation/National None Shopping All contracts at or above USD 2,000,000 are subject to Open Competition international advertising and ≥ 500,000 International Market the use of the Bank’s SPDs (or Approach other documents agreed with the Bank). Goods, IT and 2 non-consulting Open Competition services National Market : Approach None 100,000 < C < 500,000 Request for Quotation/National C ≤ 100,000 None Shopping All contracts at or above USD 100,000 are subject to For international advertising and C < 100,000 Consulting Services the use of the Bank’s SPDs (or other documents agreed with Shortlist of the Bank) 3 National All contracts at or above USD Consultants For 200,000 are subject to Engineering and international advertising and C ≤ 200,000 Construction the use of the Bank’s SPDs (or Supervision other documents agreed with the Bank). Selection of All values ≥ 100,000 4 Individual All Approaches consultants Training, Workshops, Based on approved This line activity is not subject 5 Study Tours All Values Annual Work Plan & to procurement Review. Budgets (AWPB) by TTL (Special procurement arrangements like direct contracting, use of SOEs, UN Agencies, third party monitors, local NGOs, Force Account, servants needs, results based arrangements. It is not expected that there will need for prequalification in the procurement arrangements under the PMU.) *These thresholds are for the purposes of the initial procurement plan for the first 18 months. The thresholds will be revised periodically based on re-assessment of risks. All contracts not subject to prior review will be post-reviewed. Pre-qualification: Expected for the packages of works/goods packages in the procurement plan. Proposed Procedures for CDD Components: Not Applicable Reference to (if any) Project Operational/Procurement Manual: the PMU team will update the existing Procurement manuals. The Procurement Plan will also form part of the Project Implementation Manual. Any Other Special Procurement Arrangements: Regional procurement collaboration under MIDP is envisaged. Procurement Packages/PLAN with Procurement Arrangements and Time Schedule: as per the Table below: b) PROCUREMENT PLAN Goods 1 2 3 4 5 6 7 8 9 10 Ref. Contract Estimat Procure Preq Natio Revie Expect Expecte Comments No. ed ment ualifi nal w ed bid d (Description) Method catio Prefe openin Contrac Cost n rence by g date t Start (yes/ (yes/ Bank Date US$ no) no) (Prior / Post) 1. Procurement of $15,000. RFQ, No No Post Office Equipment 00 Open, Decemb Nationa er 2021,20 January 2 months l 22 2022 delivery pd. 2. Procurement of $96,000. RFB, No No Post Decemb vehicles (purchase, 00 Open, er 2021 registration & Nationa insurance of 2 l January vehicles) 2022 3 months delivery pd 3. Procurement of $7,500.0 RFQ, No No Post Decemb Office Furniture. 0 Open, er 2021 January Nationa 2022 1 month l delivery pd Consultancy Services 1 2 3 4 5 6 7 8 Ref. Description of Estimate Revie Expected Expected No. Assignment d Selectio w date of n proposal Contract Comments Cost Method/ by submissi Start Arrange Bank on US$ Date ment (Prior / Post) 1. Consulting service for $250,000. QCS Prior Decemb March 2022 Hydro/top/bathymetric 00 review er 2021 surveys 2. Consulting service for $900,000. QCBS Prior Decemb April 2022 Works Feasibility & 00 review er 2021 Design Studies 3. Project Coordinator 132,000.0 IC Post Novemb January (24months) 0 review er 2021 2022 4. Procurement Specialist 72,000.00 IC Post Novemb January review er 2021 2022 (24months) 5. Financial Management 72,000.00 IC Post Novemb January Officer (24months) review er 2021 2022 6. Environmental 72,000.00 IC Post Novemb January Specialist review er 2021 2022 (24months) 7. Social & Safeguard 72,000.00 IC Post Novemb January engagement specialist review er 2021 2022 (24months) 8. Community 72,000.00 IC Post Novemb January Engagement & review er 2021 2022 Communications specialist (24months) 9. Lead Civil 96,000.00 IC Post Novemb January engineer(24months) review er 2021 2022 10. Civil/Hydraulic 84,000.00 IC Post Novemb January engineer(24months) review er 2021 2022 11. Junior IT/ digital 48,000.00 IC Post Novemb January D communication review er 2021 2022 specialist (24months) 12. Individual Consultant 50,000.00 IC Post Novemb December for the conduct of ESMF review er 2021 2021 13. Individual Consultant $50,000.0 IC Post Novemb December for the conduct of RPF 0 review er 2021 2021 14. Consulting Firm for the 400,000.0 QCBS Prior Decemb March 2022 conduct of ESIA, RAP, 0 review er 2021 ESMP, OHSP, LMP Consultancy Services $300,000. QCBS Prior December January 2022 for Technical Assistance 00 review 2021 to the PMU Appendix 1 Letter of Acceptance of the World Bank’s Anti-Corruption Guidelines and Sanctions Framework Date: Invitation of Bids/Proposals No.__________ To: ___________________________________________________________________________ We, along with our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not) consultants and personnel, acknowledge and agree to abide by the World Bank’s policy regarding Fraud and Corruption (corrupt, fraudulent, collusive, coercive, and obstructive practices), as set out and defined in the World Bank’s Anti-Corruption Guidelines1 in connection with the procurement and execution of the contract (in case of award), including any amendments thereto. We declare and warrant that we, along our sub-contractors, sub- consultants, service providers, suppliers, agents (whether declared or not), consultants and personnel, , are not subject to, and are not controlled by any entity or individual that is subject to, a temporary suspension, early temporary suspension, or debarment imposed by a member of the World Bank Group, including, inter alia, a cross-debarment imposed by the World Bank Group as agreed with other international financial institutions (including multilateral development banks), or through the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement. Further, we are not ineligible under the laws or official regulations of [Insert name of Employer as per bidding document] or pursuant to a decision of the United Nations Security Council. We confirm our understanding of the consequences of not complying with the World Bank’s Anti-Corruption Guidelines, which may include the following: a. rejection of our Proposal/Bid for award of contract; b. in the case of award, termination of the contract, without prejudice to any other remedy for breach of contract; and c. sanctions, pursuant to the Bank’s Anti-corruption Guidelines and in accordance with its prevailing sanctions policies and procedures as set forth in the Bank’s Sanctions Framework. This may include a public 1Guidelines on Preventing and Combating Fraud and Corruption in Projects Financed by International Bank for Reconstruction and Development Loans and the International Development Agency Credits and Grants, dated October 15, 2006, and revised in January 2011 and July 2016, as they may be revised from time to time. declaration of ineligibility, either indefinitely or for a stated period of time, (i) to be awarded or otherwise benefit from a Bank-financed contract, financially or in any other manner;2 (ii) to be a nominated3 sub- contractor, consultant, manufacturer or supplier, or service provider of an otherwise eligible firm being awarded a Bank-financed contract; and (iii) to receive the proceeds of any loan made by the Bank or otherwise to participate further in the preparation or implementation of any Bank- financed project. We understand that we may be declared ineligible as set out above upon: a. completion of World Bank Group sanctions proceedings according to its prevailing sanctions procedures; b. cross-debarment as agreed with other international financial institutions (including multilateral development banks); c. the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement; or d. temporary suspension or early temporary suspension in connection with an ongoing World Bank Group sanctions proceeding. For avoidance of doubt, the foregoing effects of ineligibility do not extend to a sanctioned firm’s or individual’s execution of its ongoing Bank-financed contracts (or its ongoing sub-agreements under such contracts) that are not the subject of a material modification, as determined by the Bank. We shall permit, and shall cause our sub-contractors, sub-consultants, agents (whether declared or not), personnel, consultants, service providers or suppliers, to permit the Bank to inspect4 all accounts, records, and other 2 For the avoidance of doubt, a sanctioned party’s ineligibility to be awarded a contract shall include, without limitation, (i) applying for pre-qualification, expressing interest in a consultancy, and bidding, either directly or as a nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider, in respect of such contract, and (ii) entering into an addendum or amendment introducing a material modification to any existing contract. 3 A nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider (different names are used depending on the particular bidding document) is one which has been: (i) included by the bidder in its pre-qualification application or bid because it brings specific and critical experience and know-how that allow the bidder to meet the qualification requirements for the particular bid; or (ii) appointed by the Borrower. 4 Inspections in this context are usually investigative (i.e., forensic) in nature: they involve fact-finding activities undertaken by the Bank or persons appointed by the Bank to address specific matters related to investigations/audits, such as evaluating the veracity of an allegation of possible Fraud and Corruption, through the appropriate mechanisms. Such activity includes but is not limited to accessing and examining a firm's or individual's financial records and information, and making copies thereof as relevant; accessing and examining any other documents, data, and information (whether in hard copy or electronic format) deemed documents relating to the procurement process and/or contract execution (in the case of award), and to have them audited by auditors appointed by the Bank. We agree to preserve all accounts, records, and other documents (whether in hard copy or electronic format) related to the procurement and execution of the contract. Name of the Bidder/Consultant: Name of the person duly authorized to sign the Bid/Proposal on behalf of the Bidder/Consultant: Title of the person signing the Letter: relevant for the investigation/audit, and making copies thereof as relevant; interviewing staff and other relevant individuals; performing physical inspections and site visits; and obtaining third-party verification of information. PROCUREMENT Liberia : Liberia Urban Resilience Project PLAN General Information Country: Liberia 2021-11-19 Bank’s Approval Date of the Original Procurement Plan: 2023-06-05 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P169718 GPN Date: 2023-05-24 Project Name: Liberia Urban Resilience Project Loan / Credit No: / , IDA / V3930, IDA / 71220, IDA / E0410 Ministry of Public Works Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned LR-MPW-360151-CW-RFQ / C Request for Quota Climate Resilient Infrastruct Request for Quota Single Stage - One E Under Imple 2024-01-0 leaning of Drainage Facilities IDA / 71220 Post Limited tions (Non Bank-S 96,687.50 0.00 2023-05-10 2023-05-18 2023-07-05 ure and Urban Upgrading tions nvelope mentation 1 for LURP in Bushrod Island PD) LR-MPW-360152-CW-RFQ / C Request for Quota Climate Resilient Infrastruct Request for Quota Single Stage - One E Under Imple 2024-01-0 leaning of Drainage Facilities IDA / 71220 Post Limited tions (Non Bank-S 64,902.50 0.00 2023-05-10 2023-05-18 2023-07-05 ure and Urban Upgrading tions nvelope mentation 1 for LUPR in Paynesville PD) LR-MPW-360155-CW-RFQ / C Request for Quota Climate Resilient Infrastruct Request for Quota Single Stage - One E Under Imple 2024-01-0 leaning of Drainage Facilities IDA / 71220 Post Limited tions (Non Bank-S 87,210.00 0.00 2023-05-10 2023-05-18 2023-07-05 ure and Urban Upgrading tions nvelope mentation 1 for LURP in Central Monrovia PD) GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual LR-MPW-263581-GO-RFQ / P Request for Quota Single Stage - One E / Project Management Post Open - National 15,000.00 0.00 Canceled 2022-01-19 2022-03-02 2022-05-01 urchase and Supply of Office tions nvelope equipment LR-MPW-263569-GO-RFQ / P Request for Quota Single Stage - One E / Project Management Post Open - National 7,500.00 0.00 Canceled 2022-01-15 2023-02-06 2022-02-26 2022-04-27 urchase and Supply of Office tions nvelope Furniture LR-MPW-263766-GO-RFQ / P Request for Quota Single Stage - One E / Project Management Post Open - National 96,000.00 0.00 Canceled 2022-01-25 2022-03-08 2022-06-06 urchase and supply of Vehicl tions nvelope e LR-MPW-341388-GO-RFQ / S Request for Quota Single Stage - One E IDA / 71220 Project Management Post Limited 7,500.00 0.00 Signed 2023-02-08 2023-02-08 2023-04-01 2023-05-31 upply & Delivery of Office Fur tions nvelope niture LR-MPW-341402-GO-RFQ / S Request for Quota Single Stage - One E IDA / 71220 Project Management Post Limited 15,000.00 0.00 Signed 2023-02-08 2023-02-08 2023-03-08 2023-05-07 upply & Delivery of Office Eq tions nvelope uipment LR-MPW-352210-GO-RFB / Pr Request for Quota Single Stage - One E ocurement and Delivery Mot IDA / E0410 Project Management Post Open - National 130,500.00 0.00 Canceled 2023-04-01 2023-05-27 2023-11-23 tions nvelope or Vehicles For PMU LR-MPW-352905-GO-RFQ / P Request for Quota Single Stage - One E Under Imple rocurement & Delivery of Mo IDA / E0410 Project Management Post Limited 130,500.00 0.00 2023-04-02 2023-03-29 2023-05-28 2023-11-24 tions nvelope mentation tor vehicles for PMU LR-MPW-358886-GO-RFQ / P Request for Quota Single Stage - One E Under Imple rocurement, Delivery & Instal IDA / 71220 Project Management Post Limited 49,075.20 0.00 2023-05-09 2023-05-04 2023-07-04 2023-10-02 tions nvelope mentation lation of 25kVA Solar Power S ystem for PMU NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual LR-MPW-263267-CS-QCBS / Climate Resilient Infrastruct Quality And Cost- Open - Internationa Under Implement / Post 400,000.00 0.00 2021-12-20 2021-12-27 2022-01-10 2022-02-21 2022-03-21 2022-04-11 2022-05-16 2022-06-20 2023-03-17 Conduct of ESIA, RAP, ESMP, ure and Urban Upgrading Based Selection l ation OHSP, LMP LR-MPW-263712-CS-QCBS / Quality And Cost- Open - Internationa Pending Impleme / Project Management Post 300,000.00 0.00 2022-01-10 2022-01-31 2022-03-07 2022-04-04 2022-04-25 2022-05-23 2022-06-20 2023-06-20 Technical Assistance to the P Based Selection l ntation MU LR-MPW-270591-CS-QCBS / Climate Resilient Infrastruct Quality And Cost- Open - Internationa Under Implement Consulting Services for Feasi / Post 900,000.00 0.00 2021-12-27 2022-04-09 2022-01-17 2022-05-16 2022-03-02 2022-09-22 2022-03-30 2022-11-21 2022-04-29 2023-06-06 2022-06-03 2022-07-08 2023-04-04 ure and Urban Upgrading Based Selection l ation bility Studies & Design LR-MPW-263588-CS-CQS / C Climate Resilient Infrastruct Consultant Qualifi Open - Internationa onsulting service for the con / Post 250,000.00 0.00 Canceled 2021-12-20 2022-01-10 2022-02-23 2022-03-25 2022-04-29 2022-10-26 ure and Urban Upgrading cation Selection l duct of Hydro/topo/bathymet ric surveys LR-MPW-360812-CS-QCBS / Consultancy Services for Spa Strengthening Integrated Re tial Development & Infrastruc Quality And Cost- Open - Internationa Under Implement IDA / 71220 silient Urban Development C Prior 1,050,000.00 0.00 2023-05-10 2023-05-10 2023-05-31 2023-05-24 2023-07-14 2023-08-11 2023-09-10 2023-10-15 2023-11-19 2024-11-18 ture Investment Plans for Gre Based Selection l ation apacity ater Monrovia, including Floo d Risk Assessment ToR in Fiv e Urban areas in Liberia LR-MPW-365332-CS-CQS / C onsultancy Services for Const Strengthening Integrated Re Consultant Qualifi Open - Internationa Under Implement ruction Supervision of Chees IDA / 71220 silient Urban Development C Post 350,000.00 0.00 2023-06-08 2023-06-12 2023-06-29 2023-06-12 2023-08-12 2023-09-11 2023-10-16 2024-04-13 cation Selection l ation emanburg Landfill Developm apacity ent (Design & Build) Contract INDIVIDUAL CONSULTANTS Page 1 Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual LR-MPW-263802-CS-INDV / C Climate Resilient Infrastruct Individual Consult onsulting Services for Enviro / Post Limited 50,000.00 0.00 Completed 2021-11-25 2021-11-25 2021-11-30 2021-11-25 2021-12-21 2022-02-03 2022-01-11 2022-04-11 ure and Urban Upgrading ant Selection nmental Social Management Framework LR-MPW-263805-CS-INDV / C Climate Resilient Infrastruct Individual Consult onsulting Services for the co / Post Limited 50,000.00 0.00 Completed 2021-11-25 2021-11-25 2021-11-30 2021-11-25 2021-12-21 2022-01-31 2022-01-11 2022-04-11 ure and Urban Upgrading ant Selection nduct of Resettlement Policy Framework LR-MPW-288612-CS-INDV / P Individual Consult IDA / V3930 Project Management Post Open 132,000.00 0.00 Signed 2022-04-07 2022-04-18 2022-05-26 2022-09-05 2022-06-16 2022-09-30 2022-07-21 2023-01-17 roject Manager ant Selection LR-MPW-288618-CS-INDV / E Individual Consult IDA / V3930 Project Management Post Open 72,000.00 0.00 Signed 2022-04-07 2022-04-18 2022-05-26 2022-09-05 2022-06-16 2022-11-30 2022-07-21 2023-01-17 nvironment Safeguard Speci ant Selection alist LR-MPW-288656-CS-INDV / S Individual Consult IDA / V3930 Project Management Post Open 72,000.00 0.00 Signed 2022-04-07 2022-04-18 2022-05-26 2022-09-05 2022-06-16 2022-09-29 2022-07-21 2023-01-17 ocial Safeguards & Gender S ant Selection pecialist LR-MPW-288659-CS-INDV / C Individual Consult onsultancy for Community En IDA / V3930 Project Management Post Open 72,000.00 0.00 Signed 2022-04-07 2022-04-18 2022-05-26 2022-09-05 2022-06-16 2022-09-30 2022-07-21 2023-01-17 ant Selection gagement & Communication Specialist LR-MPW-288661-CS-INDV / C Individual Consult onsultancy Service for Senior IDA / V3930 Project Management Post Open 96,000.00 0.00 Signed 2022-04-07 2022-04-18 2022-05-26 2022-09-06 2022-06-16 2022-09-30 2022-07-21 2023-01-17 ant Selection Procurement Specialist LR-MPW-288662-CS-INDV / p Individual Consult IDA / V3930 Project Management Post Open 72,000.00 0.00 Signed 2022-04-07 2022-04-18 2022-05-26 2022-09-06 2022-06-16 2022-09-30 2022-07-21 2023-01-17 rocurement Specialist ant Selection LR-MPW-288663-CS-INDV / c Individual Consult IDA / V3930 Project Management Post Open 72,000.00 0.00 Signed 2022-04-07 2022-04-18 2022-05-26 2022-09-06 2022-06-16 2022-09-30 2022-07-21 2023-01-17 onsultancy services for Finan ant Selection cial Officer LR-MPW-288664-CS-INDV / c Individual Consult onsultancy Service for Civil E IDA / V3930 Project Management Post Open 96,000.00 0.00 Signed 2022-04-07 2022-04-18 2022-05-26 2022-09-05 2022-06-16 2022-09-27 2022-07-21 2023-01-17 ant Selection ngineer/Hydraulic Engineer LR-MPW-288665-CS-INDV / c Individual Consult IDA / V3930 Project Management Post Open 72,000.00 0.00 Signed 2022-04-07 2022-04-18 2022-05-26 2022-09-05 2022-06-16 2022-09-27 2022-07-21 2023-01-17 onsultancy Services for Civil ant Selection Engineer LR-MPW-288666-CS-INDV / C Individual Consult onsultancy Services for IT/Di IDA / V3930 Project Management Post Open 48,000.00 0.00 Signed 2022-04-07 2022-04-18 2022-05-26 2022-09-06 2022-06-16 2022-09-30 2022-07-21 2023-01-17 ant Selection gital Communication Speciali st LR-MPW-361168-CS-INDV / H Strengthening Integrated Re Individual Consult Direct - Internation Under Implement ire of Solid Waste Manageme IDA / 71220 silient Urban Development C Prior 300,000.00 0.00 2023-05-12 2023-05-23 2023-05-22 2023-06-27 2023-06-12 2023-07-17 2024-01-13 ant Selection al ation nt (SWM) Technical Advisor apacity Page 2 PROCUREMENT PLAN (Textual Part) Project information: Country: Nigeria Project Name: Multi-Sectoral Crisis Recovery Project for North East Nigeria (MCRP) P- Number: P157891 Project Implementation Agency: MCRP PCU (Federal and States) Date of the Procurement Plan: Updated -December 22, 2017. Period covered by this Procurement Plan: From 01/12/2018 – 30/06/2019. Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the FGN Public Procurement Act 2007; such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. “Not Applicable” THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables. “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Specify for each: Goods: is not applicable for those contracts identified in the Procurement Plan tables; Works: is not applicable for those contracts identified in the Procurement Plan tables. Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations is Applicable. Other Relevant Procurement Information. 1. Prior Review Threshold for Goods, Works and Non-Consulting Services: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Prior Review Procurement Method Threshold (US$ Comments equivalent) ICB and LIB (Goods and services other than ≥ 5,000,000 ALL consultancy services) NCB (Goods, IT Systems and Non Consulting Services 100,000 < 5,000,000 NONE (NCB) ICB (Works) ≥ 20,000,000 ALL NCB (Works) 150,000 < 20,000,000 NONE Shopping-Goods ≤ 100,000 NONE Shopping-Works ≤ 150,000 NONE Based on Annual Training, Workshops, Study All Values Work Plans & Tours Budgets 2. Prequalification: Bidders for major works shall be prequalified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines, although it is not expected that there will be need for prequalification in the procurement arrangements for the MCRP. MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 2 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT 3. Proposed Procedures for CDD Components (as per paragraph. 6.52 of the Procurement Regulations): Shall apply. 4. Reference to the Project Implementation Manual: Shall apply. 5. Any Other Special Procurement Arrangements: Not Applicable 6. Procurement Packages (Goods and Works) indicating Bank’s Prior and Post Review. MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 3 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT a. Summary of Procurement of Goods: 1 2 3 4 5 6 Review by Estimated Ref. Packag Bank Commen Description Cost (US$ No. es (Prior / ts Million) Post) Total NCB 12.82 43 Post (Goods) Total RfQ (Goods/Non 0.04 1 Post Consulting Services) Procurement of Goods with Selection Methods and Time Schedule (Please see Annex I). b. Summary of Procurement of Civil Works 1 2 3 4 5 6 Review by Estimated Ref. Bank Commen Description Cost (US$ Packages No. (Prior / ts Million) Post) Total NCB 23.59 64 Post (Works) Total RfQ 2.29 20 Post (Works) Procurement of Civil Works with Selection Methods and Time Schedule (Please see Annex II). c. Summary of Procurement of Non- Consulting Services (TBD) 1 2 3 4 5 6 Review by Estimated Ref. Bank Commen Description Cost (US$ Packages No. (Prior / ts Million) Post) Total NCB 0.175 2 Post MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 4 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT 7. Prior Review Threshold for Consultancies: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Prior Review Selection Method Comments Threshold (USD) Consultant Services-QCBS- International 1. Consulting Services ≥ 300,000 ALL 2. Engineering and Construction ≥ 500,000 Supervision Consultant Services-QCBS < 300,000.00 NONE Consultant Services-CQS < 300,000.00 NONE Consultant Services-lC >300,000.00 ALL Consultant Services-lC <300,000.00 NONE Consultant Services- Single Source All Values ALL Selection Note: All ToRs to be prior review QCBS = Quality and Cost Based Selection SSS = Single Source Selection CQ = Consultant Qualification LCS = Least Cost Selection IC = Individual Consultant 8. Short list comprising entirely of National Consultants: Short list of consultants for services, estimated to cost less than $300,000.00 equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. a. Summary of Consultancies 1 2 3 4 5 6 Ref. Description Estimate Package Review by Comment No. d Cost s Bank s (US$ (Prior/Post Million) ) Summary of number of 5.72 7 Prior contracts that will be let under International QCBS Summary of number of 6.45 16 Post contracts that will be let under National QCBS Summary of number of 1.74 30 Post contracts that will be let under CQS Summary of number of 0.35 3 Post contracts that will be let under MOU MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 5 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Summary of number of 0.021 3 Post contracts that will be let under Individual Consultancies MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 6 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Estimated Estimated Prior Number of Amount in Investable or Expected Procureme Pre- USD (Over Amount Post Bid- Description (List of Componen nt Procureme qualificati the Project for 18 Revie Opening Contracts) t/Sector Packages nt Method on Life) months w Date WORKS BORNO Construction Of 18-No Double Classroom Blocks in Ngohi, Biji-Biji, Ngulde, C2/Educati Post Tue-19-Jun- Rumirgo, Chul on 3 NCB No 708,196.72 354,098.36 Review 18 Construction Of 10- No. Double Classroom Block - C2/Educati Post Tue-19-Jun- Bama (Banki Town) on 2 NCB No 393,442.62 314,754.10 Review 18 Reconstruction Of 39- No. Double Classroom Block in C2/Educati Post Damasak, Mobbar on 4 NCB No 575,409.84 71,926.23 Review Tue-24-Jul-18 Construction Of 15- No. Double Classroom Block - C2/Educati Post Gajibo, Logomane (Dikwa) on 2 NCB No 590,163.93 147,540.98 Review Tue-24-Jul-18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 7 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Construction Of 25 No. Double Classroom Block C2/Educati Post GUZAMALA on 2 NCB No 983,606.56 245,901.64 Review Tue-24-Jul-18 Construction Of 20- No. Double Classroom Block - Kukawa Town, Baga, Cross- C2/Educati Post Tue-18-Sep- Kauwa on 2 NCB No 786,885.25 196,721.31 Review 18 Construction Of 10- No. Double Classroom Block - C2/Educati Post Tue-18-Sep- Monguno on 1 NCB No 393,442.62 98,360.66 Review 18 Construction Of 4- No. Double Classroom Block in C2/Educati Post Tue-20-Nov- Ajiri. Mafa on 1 NCB No 157,377.05 39,344.26 Review 18 Renovation Of 20- No. Double Classroom Blockin C2/Educati Post Tue-20-Nov- Damboa Town -Abadam on 2 NCB No 295,081.97 73,770.49 Review 18 Renovation Of 31- No. Double Classroom Block - C2/Educati Post Tue-23-Oct- Bama on 2 NCB No 457,377.05 114,344.26 Review 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 8 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Construction Of 3-No. C2/Educati Post Tue-18-Sep- Educational Office -Kukawa on 1 NCB No 196,721.31 98,360.66 Review 18 Construction Of 2-No. Educational Office - C2/Educati Post Tue-20-Nov- Konduga on 1 NCB No 131,147.54 32,786.89 Review 18 Construction Of 2-No. Educational Office -Hawul C2/Educati Post Tue-23-Oct- Sakwa, Kwajafa on 1 NCB No 131,147.54 32,786.89 Review 18 Construction Of 4-No Vip C2/Educati Post Tue-18-Dec- Toilets -Askira-Uba on 1 RfQ No 59,016.39 47,213.11 Review 18 Construction Of 4-No Vip C2/Educati Post Tue-18-Dec- Toilets -Mafa on 1 RfQ No 59,016.39 47,213.11 Review 18 Construction Of 5-No Vip C2/Educati Post Tue-18-Dec- Toilets -Monguno on 1 RfQ No 73,770.49 59,016.39 Review 18 Renovation Of 1-No. Educational Office - C2/Educati Post Tue-18-Dec- Damboa on 1 RfQ No 18,032.79 4,508.20 Review 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 9 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Renovation Of 1-No. Educational Office and 1- No. Principal's Quarters - Benisheik, Kaga- Benisheik, C2/Educati Post Tue-23-Oct- Kaga on 1 RfQ No 42,622.95 16,803.28 Review 18 Rehabilitation of 66KM C2/Transpo 1,223,144. Prior Tue-27-Feb- Maiduguri to Bama road rt 1 NCB No 9,785,152.68 08 Review 18 Rehabilitation of 1 Ngala C2/Transpo Prior Tue-27-Feb- Bridge rt 1 NCB No 2,295,081.97 483,983.71 Review 18 C2/Transpo Post Tue-27-Feb- Rehabilitation of Biu bridge rt 1 NCB No 902,111.48 73,770.49 Review 18 Construction of galameri- dusuman-zabarmari- C2/Transpo Prior Tue-27-Feb- gongulong feeder road rt 1 NCB No 1,104,625.69 59,016.39 Review 18 RehabilitatIon of 3 General Hospital in ABADAM, ASKIRA UBA, KALA-BALGEe and Rehabilitation of Prior Tue-27-Mar- comprehensive Healthcare C2/Health 3 NCB No 1,555,779.01 986,195.83 Review 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 10 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT center (Civil Works, Solar Borehole, Fence & Security Post) Construction of PHC for 15 2,254,098. Prior Tue-27-Mar- LGAs C2/Health 5 NCB No 3,606,557.38 36 Review 18 Rehabilitation of Borno C2/Educati Post Tue-24-Apr- State Library on 2 NCB No 557,377.05 34,426.23 Review 18 Rehabilitation of Umar Ibn C2/Educati Post Tue-24-Apr- Ibrahim college Bama on 2 NCB No 557,377.05 278,688.52 Review 18 Construction of Solar Powered Boreholes (2Nos) in Umar Ibn Ibrahim college Bama Solar Lighting System to Borno C2/Educati Post Tue-24-Apr- Library on 1 NCB No 196,721.31 98,360.66 Review 18 Rehabilitation of Court Buildings in Bama Gwoza C2/Public Post Tue-22-May- Dikwa Mobbar Buildings 4 RfQ No 393,442.62 49,180.33 Review 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 11 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Rehabilitation of Local Govt Secretariats in Kukawa, Monguno, biu ,Abadam, Kala-Balge, Marte, C2/Public 1,229,508. Post Tue-05-Jun- Magumeri, Guzamala Buildings 8 RfQ No 1,967,213.11 20 Review 18 Rehabilitation of Traditional Rulers' Konduga , Monguno, Kukawa, Nganzai, Baga, Marte, Ngala, Abadam, Guzamala, C2/Public Post Tue-05-Jun- Kwajafa, Kumshe Buildings 6 RfQ No 1,442,622.95 180,327.87 Review 18 Provision of Community Resource Centres in 20 C2/Public Post LGAs Buildings 10 NCB No 2,295,081.97 860,655.74 Review Thu-05-Jul-18 Construction of Handpump Wells in Bama (3) Chibok (5), Biu (5), Mafa(3), Hawul (5), Askira/Uba(5), Konduga(4), Jere(5) Dikwa Post Fri-03-Aug- (3), Gwoza(5), C2/WASH 10 RfQ No 140,983.61 35,245.90 Review 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 12 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Construction of Solar Powered Boreholes in Askira Uba Gwoza(4),Bama(4), Ngala(3), Damboa(3) Jere(4),Kukawa(3), Biu(2),Konduga(3), Gubio(3), Askira/Uba(3), Magumeri(3), Marte(3), Mobbar(3), Monguno(3), Dikwa(2), Mafa(3), Abadam(3), Nganzai(3), Guzamala(3), Kaga(2), Chibok(2), Kala/Balge(3), Hawul(2)(To include 2Nos 5,000lt Plastic water tanks on a 1.5m raised platform , five fetching points/tap gallery, chain link 3,501,639. Post Wed-25-Jul- perimeter fence) C2/WASH 14 NCB No 4,668,852.46 34 Review 18 REHABILITATION OF LOCAL GOVERNMENT LODGES (Marte, Kaga, Chibok, Magumeri, Gwoza, Kala- Balge, Ngala, Guzamala, Abadam, Hawul, C2/Public Post Tue-21-Aug- Askira/Uba, Bama) Buildings 6 NCB No 1,311,475.41 786,885 Review 18 Rehabilitationof Traditional Rulers' Buildings Bama, Konduga, Gwoza ,Kareto, C2/Public Post Damboa , Monguno, Buildings 11 RfQ No 1,442,622.95 180,327.87 Review Thu-26-Jul-18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 13 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Kukawa, Askira-Uba , Dikwa, Baga, Marte REHABILITATION OF MINISTRY BUILDING (Ngala, C2/Public Post Tue-21-Aug- Monguno) Buildings 2 NCB No 276,577 Review 18 CONSTRUCTION OF SANITATION FACILITIES IN 21 LOCAL GOVERNMENT AREAS.ABADAM (6) ASKIRA(6) BAMA(6) BIU(6) CHIBOK(6) DAMBOA(6) DIKWA(6) GUBIO(6) GWOZA(6) JERE(6) KAGA(6) KALA-BALGE(6) KONDUGA(6) KUKAWA(6) MAFA(5) MOBBAR(6) MONGUNO(6) MARTE(6) NGALA(6) NGANZAI(6) Post Wed-19-Sep- MAGUMERI(6) C2/WASH 21 NCB No 781,517 Review 18 REHABILITATION OF EXISTING NON- FUNCTIONAL BOREHOLES ABADAM (1) ASKIRA UBA (2) BIU (2) DIKWA (1) Post Tue-18-Sep- GUBIO (1) GUZAMALA (1) C2/WASH 6 NCB No 258,525 Review 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 14 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT JERE (2) KALA BALGE (1) MAFA (2) MAGUMERI (1) MARTE (2) MOBBAR (1) NGALA (1) NGANZAI (1) Rehabilitation of 8 blocks of Laborataries (Umar Ibn C1/Educati Post Tue-18-Sep- Ibrahim college Bama) on 1 NCB No 262,295 Review 18 ADAMAWA Rehabilitation of Gulak Post Mon-14-May- Water Supply System C2/Water 1 NCB No 179,190.16 134,392.62 Review 18 Rehabilitation of Hong Post Mon-14-May- Water Supply System C2/Water 1 NCB No 116,646.90 87,485.18 Review 18 Rehabilitation of Michika Post Mon-14-May- Water supply system C2/Water 1 NCB No 138,193.44 103,645.08 Review 18 Rehabilitation of Uba Water Post Tue-15-May- Supply system C2/Water 1 NCB No 71,967.21 71,967.21 Review 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 15 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Rehabilitation of exisitng Water Supply sources in Post Tue-15-May- Gombi C2/Water 1 NCB No 30,475.41 30,475.41 Review 18 Construction of Uba New Post Mon-28-May- Water Supply Project C2/Water 1 NCB No 721,222.95 108,183.44 Review 18 Pella New Water Supply Post Mon-28-May- Project C2/Water 1 NCB No 555,289.34 83,293.40 Review 18 Construction of Hong New Post Mon-28-May- Water supply project C2/Water 1 NCB No 1,256,442.62 188,466.39 Review 18 Construction of Michika Post Tue-29-May- New Water supply project C2/Water 1 NCB No 1,189,261.84 178,389.28 Review 18 Construction GOMBI NEW Post Tue-29-May- WATER SUPPLY PROJECT C2/Water 1 NCB No 915,241.80 137,286.27 Review 18 Installation of 12 nos. Solar Boreholes (in secondary schools)- GSS Gombi, GDSS Garkida, GSS Hong, GDSS Pella, GSSS Uba, Post Thu-10-May- GJSS Uba, GDSS Garaha, C2/Water 1 NCB No 377,609.70 75,521.94 Review 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 16 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT GDSS Kwarhi, GDSS Za'ah, GSS Madagli, GSS Shuwa, GSS Gulak, GCSS Shuwa Installation of 37 Nos Solar Boreholes in 37 Health Centers in 7 Local Post Thu-10-May- Governments Areas C2/Water 4 NCB No 1,164,296.59 291,074.15 Review 18 Construction of 295Nos Hand Powered Bore Holes (in 2 primary schools per 35 wards, 35 Markets, 35 Motor parls and 155 Communities across 7 Post Thu-03-May- LGAs) C2/Water 4 NCB No 1,257,377.05 503,483.61 Review 18 Construction of VIP Latrines of 3-Comp (2 Blks Post Tue-14-Aug- in 24 pri sch) C2/WASH 3 RfQ No 212,459.02 79,672.13 Review 18 VIP Latrine of 3-Comp (2 Post Tue-14-Aug- Blks in 26 Markets) C2/WASH 3 RfQ No 230,163.93 92,065.57 Review 18 VIP Latrine of 3-Comp (2 Post Tue-14-Aug- Blks in 26 Motor Parks) C2/WASH 3 RfQ No 230,163.93 92,065.57 Review 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 17 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Rehabilitation of Lokwa C2/Transpo Post Mon-11-Jun- Bridge Mubi rt 1 NCB No 475,143.96 356,357.97 Review 18 Reconstruction of Main Road - Bangshika Road C2/Transpo Prior Mon-11-Jun- 2.5Km rt 1 NCB No 1,019,295.08 127,411.89 Review 18 Rehabilitation of Mubi Bazza Road with a spur to C2/Transpo 1,255,469. Prior Mon-11-Jun- Mayo Bani 45Km rt 1 NCB No 8,369,796.72 51 Review 18 Rehabilitation of PHC, Construction of Perimeter Fence and Staff Quarters (Civil Works, Solar Borehole, Fence & Security C2/Educati Prior Tue-10-Apr- Post) in 7 Communities on 7 NCB No 1,139,130.43 451,779.49 Review 18 Rehabilitation of Cottage Post Tue-10-Apr- Hospital C2/Health 1 NCB No 451,768.85 192,001.76 Review 18 Establishment of Trauma Post Thu-17-May- Center @ general hospital C2/Health 1 RfQ No 65,194.96 65,194.96 Review 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 18 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Renovation of GSS in 10 Towns (Gombi, Hong, Uba, Shuwa, Michika, Bazza, Mubi 1, Maiha, Madagali, C2/Educati Post Mubi North) on 10 NCB No 2,305,292.65 442,327.22 Review Tue-10-Jul-18 Renovation of 25Nos C2/Educati Post Primary School over 7 LGAs on 4 NCB No 865,747.88 324,655.45 Review Tue-10-Jul-18 Rehabilitation of Local Government Secretariat - C2/Public Post Thu-07-Jun- Song Buildings 1 NCB No 288,590.56 144,295.28 Review 18 Rehabilitation of Local Government Secretariat - C2/Public Post Thu-07-Jun- Madagali Buildings 1 NCB No 315,082.89 157,541.44 Review 18 Rehabilitation of District Head's Palace in 5 Communities (Uba, Gella, Gombi, Maiha/Pakka, C2/Public Post Thu-07-Jun- Gulak) Buildings 5 NCB No 422,463.57 158,423.84 Review 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 19 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT YOBE Conversion of Motorised Boreholes (28 Communities in Gulani and Damaturu) into Solar Post Mon-26-Mar- Powered C2/Water 1 NCB No 334,013.66 250,510.24 Review 18 Conversion of existing Motorized powered Borehole without Overhead tank into solar powered (Gujba, Gulani, Yunusari, Damaturu,& Post Mon-26-Mar- Geidam ) C2/Water 1 NCB No 277,532.56 208,149.42 Review 18 Conversion of existing Motorized powered Borehole into solar powered and construction of New Overhead tank (Gujba, Gulani, Yunusari, Post Mon-26-Mar- Damaturu,& Geidam) C2/Water 2 NCB No 542,490.73 406,868.05 Review 18 Drilling of New Solar Powered Boreholes in Gujba, Gulani, Yunusari, Damaturu, Fika, Potiskum, Post Mon-02-Apr- Geidam & Fune C2/Water 2 NCB No 878,917.25 329,593.97 Review 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 20 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Rehabilitation of Solar Powered Boreholes in Gulani, Gujba and Post Mon-02-Apr- Damaturu C2/Water 1 NCB No 244,228.65 183,171.49 Review 18 Construction & Upgrade of Post Wed-24-Oct- 33 nos. PHC Centres C2/Health 5 NCB No 5,386,554.10 538,655.41 Review 18 Reconstruction of Vandalized 3 Nos Post Wed-09-May- Immunization Offices C2/Health 1 RfQ No 68,618.27 68,618.27 Review 18 Renovation of 1No. General Post Mon-03-Sep- Hospital in Buni Yadi C2/Health 1 RfQ No 88,524.59 44,262.30 Review 18 Construction of 1No. Student Hostel each in College of Nursing and Midwifery Damaturu and College of Health Sciences Post Wed-22-Aug- and Technology, Nguru C2/Health 2 NCB No 983,606.56 245,901.64 Review 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 21 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Renovation of Govt Secondary Schools in Goniri,Bara, Bularafa, ,Kananma, Damagum, Buni Yadi, Kukuwa, Gujba and C2/Educati Post Mon-09-Apr- Best Center in Goniri on 5 NCB No 2,001,760.77 800,704.31 Review 18 Renovation of Dokshi C2/Educati Post Mon-09-Apr- Primary school, Gulani on 1 NCB No 168,034.42 67,213.77 Review 18 Rehabilitation of Local Government Office Secretariat in Gujba and C2/Public Post Wed-09-May- Potiskum Buildings 2 NCB No 472,529.40 75,459.62 Review 18 Rehabilitation of Development Offices in Gujba , Gulani, Yunusari & C2/Public Post Wed-09-May- Geidam Buildings 1 RfQ No 62,203.18 15,550.80 Review 18 Provision of Community Resource Centres in all 17 C2/Public Post Wed-23-May- LGAs Buildings 5 NCB No 1,950,819.67 731,557.38 Review 18 Rehabilitation of Audit C2/Public Post Wed-26-Sep- Office Buildings 1 RfQ No 63,078.12 15,769.53 Review 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 22 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Rehabilitation of Zonal C2/Public Post Wed-26-Sep- Statistical Office Buildings 1 RfQ No 50,491.80 25,245.90 Review 18 Rehabilitation ofCultural Buildings (District Head's Palace) in Buni Yadi and C2/Public Post Mon-27-Aug- Damagum Buildings 2 NCB No 446,682.62 111,670.66 Review 18 Rehabilitation of Government Buildings; C2/Public Post Mon-11-Jun- Agency for Mass Literacy Buildings 1 RfQ No 121,445.24 60,722.62 Review 18 Rehabilitation of Government Buildings; C2/Public Post Mon-11-Jun- Town Engineers Office Buildings 1 RfQ No 121,445.24 60,722.62 Review 18 GOODS BORNO Supply of Returnee C1/Transiti Resettlement Kits Bama, onal 2,216,737. Tue-13-Feb- Dikwa, Gwoza, Ngala, Support 4 NCB No 2,216,737.30 30 Post 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 23 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Monguno, Damboa, Gudumbali, Mobbar, Kala Balge) Supply of Agricultural Support kits with Seeds, Fertilizers and Small Work Farm Tools (Bama, Biu, Gwoza, Ngala, Monguno, C1/Transiti Damboa, Askira, Mobbar, onal Tue-13-Feb- Kukawa) Support 3 NCB No 681,729.10 681,729.10 Post 18 Supply of Small Animals (Bama, Mafa, Gwoza, Ngala, Monguno, Damboa, C1/Transiti Chibok, Nganzai, Kala onal Tue-20-Feb- Balge) Support 3 NCB No 788,935.25 788,935.25 Post 18 Supply of Non-agricultural Livelihood Kits (Bama, Dikwa, Gwoza, Ngala, C1/Transiti Monguno, Damboa, Chibok, onal Tue-13-Feb- Mobbar, Hawul Support 2 NCB No 227,377.05 227,377.05 Post 18 C1/Transiti Supply of Skills Acquisition onal Tue-20-Feb- Start up Kits Support 3 NCB No 737,704.92 387,295.08 Post 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 24 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Supply of solar electrification to 3 GENERAL HOSPITALS in ABADAM, GWOZA and KALA-BALGE and five Comprehensive Health Centre in Abadam, 2 in Gwoza, Kala-Balge, Askira - Tue-01-Jan- Uba C2/Health 3 NCB No 670,553.40 516,770.59 Post 19 Supply of Medical Equipment For 3General Hospitals in ABADAM, ASKIRA UBA, and KALA- Tue-15-Jan- BALGE C2/Health 3 NCB No 590,163.93 73,770.49 Post 19 Supply of Essential Drugs/Medical Consumables For 3 General Hospitals in HAWUL, Tue-05-Mar- MOBBAR AND DAMBOA C2/Health 3 NCB No 472,131.15 59,016.39 Post 19 Supply of Medical Equipment for Comprehensive Health Wed-09-Jan- Centers (Gwoza- Izge) C2/Health 1 NCB No 245,901.64 30,737.70 Post 19 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 25 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Supply of Essential Drugs/Medical Consumables for Comprehensive Health Tue-05-Feb- Center (Gwoza-izge) C2/Health 1 NCB No 236,065.57 29,508.20 Post 19 Supply of Medical Equipment to 15 PHCs to (Ngala, Nganzai Kukawa, Biu, Konduga, Gubio, Askira/Uba, Guzamala, Bama, Jere, Marte, Mobbar, Dikwa, Tue-15-Jan- Mafa, Abadam) C2/Health 2 NCB No 983,606.56 122,950.82 Post 19 Supply of Essential Drugs to 15 PHCs (Ngala, Nganzai Kukawa, Biu, Konduga, Gubio, Askira/Uba, Guzamala, Bama, Jere, Marte, Mobbar, Dikwa, Tue-05-Feb- Mafa, Abadam) C2/Health 2 NCB No 786,885.25 98,360.66 Post 19 Supply and Installation of Solar Inverters in 15 PHCs in (Ngala, Nganzai Kukawa, Biu, Konduga, Gubio, Askira/Uba, Guzamala, Bama, Jere, Marte, Mobbar, Tue-06-Mar- Dikwa, Mafa, Abadam) C2/Health 1 NCB No 262,295.08 65,573.77 Post 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 26 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Furniture for Library/ Offices in the Borno State Library and Furniture for 15 blocks of classrooms in Umar Ibn ibrahim college C2/Educati Tue-19-Mar- Bama on 2 NCB No 491,803.28 245,901.64 Post 19 Books and other learning Materials including elibrary C2/Educati Tue-19-Mar- in the Borno State library on 1 NCB No 262,295.08 131,147.54 Post 19 Suppy of Computers and other accessories to the Borno State Library , Maiduguri and Umar Ibn C2/Educati Tue-19-Mar- ibrahim college Bama on 2 RfQ No 81,967.21 40,983.61 Post 19 Supply of Medical Equipment TO 3 Comprehensive Health centers IN HAWUL, MOBBAR AND DAMBOA Tue-06-Mar- (Kwajafa, Kareto, Damboa) C2/Health 1 NCB No 196,721.31 49,180.33 Post 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 27 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Installation of solar inverters for PHC Gwoza( Tue-06-Mar- Izge) C2/Health 1 NCB No 13,114.75 13,114.75 Post 18 ADAMAWA C1/Transiti Supply of Returnee onal Mon-19-Mar- Resettlement Kits Support 2 NCB No 490,780.33 490,780.33 Post 18 Supply of Agricultural Support kits with Seeds, C1/Transiti Fertilizers and Small Work onal 1,496,508. Mon-19-Mar- Farm Tools Support 7 NCB No 1,496,508.20 20 Prior 18 C1/Transiti onal Thu-19-Apr- Supply of Small Animals Support 1 NCB No 182,950.82 182,950.82 Post 18 C1/Transiti Supply of Non-agricultural onal Mon-19-Mar- Livelihood Kits Support 1 NCB No 213,442.62 213,442.62 Post 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 28 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT C1/Transiti Start up kits for quick to onal Mon-19-Mar- market trading Support 1 NCB No 114,754.10 114,754.10 Post 18 Housing Refurbishment Returnee Packs for Voluntary Returnees across C1/Transiti the 7 LGAs being onal Thu-14-Jun- rehabilitated. Support 2 NCB No 390,163.93 331,639.34 Post 18 Supply of Medical Equipment to PHCs in 7 communities and Cottage Hospital in Gulak C2/Health 2 NCB No 344,262.30 43,032.79 Post Thu-19-Jul-18 Supply of Essential Drugs/Medical Consumable to PHCs in 7 Communities and Cottage Hospital in Thu-01-Nov- Gulak C2/Health 2 NCB No 452,459.02 108,196.72 Post 18 Installation of Solar Inverters in 7 Rehabilitated PHCs, Cottage Hospital in Mon-06-Aug- Gulak C2/Health 3 NCB No 268,861.16 18,852.46 Post 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 29 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Equipping of Trauma Center @ Michika General Mon-06-Aug- hospital C2/Health 1 NCB No 214,142.46 80,303.42 Post 18 Supply of Furniture to C2/Educati Thu-29-Mar- Primary Schools in 7 LGAs on 1 NCB No 245,901.64 30,737.70 Post 18 Supply of Books and Teaching/Learning Materials to Primary C2/Educati Thu-29-Mar- Schools in 7 LGAs on 1 NCB No 327,868.85 122,950.82 Post 18 Establishment of spare part supply chain/buffer Mon-16-Apr- stock for Water Facilities C2/WASH 1 NCB No 114,754.10 86,065.57 Post 18 Train the Trainer/User Workshops (i.e. 2 per LGA) for VLOM (Village Level Operation and Maintenance) WASHCOMS, (WASH Committees at LGA Level, WASH Units @ LGAs, VHPs (Voluntary Hygiene Promoters) State/LGA Govt Tue-24-Apr- Officials. C2/WASH 1 NCB No 72,131.15 54,098.36 Post 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 30 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT YOBE C1/Transiti Supply of Non Food Items onal Wed-21-Mar- (NFIs) Kits Support 3 NCB No 559,213.11 559,213.11 Post 18 C1/Transiti Supply of Agricultural kits onal 1,048,940. Wed-21-Mar- with seeds, oil, small tools Support 3 NCB No 1,048,940.98 98 Post 18 C1/Transiti onal Mon-23-Apr- Supply of Small Animals Support 3 NCB No 688,524.59 688,524.59 Post 18 C1/Transiti Non-agricultural Livelihood onal Mon-26-Mar- kits Support 2 NCB No 352,295.08 352,295.08 Post 18 C1/Transiti Supply of Skills Acquisition onal Wed-21-Mar- Start up Kits Support 3 NCB No 786,885.25 550,819.67 Post 18 Procure and distribute Plumpy Nuts for Wed-25-Apr- malnourished children in C2/Health 1 NCB No 215,438.65 32,315.80 Post 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 31 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Gujba, Geidam and Yunusari LGAs Equipping of Trauma Mon-12-Feb- Center C2/Health 1 NCB No 214,147.54 53,536.89 Post 18 Supply of Students Textbooks and Teachers' C2/Educati Mon-17-Sep- Guides on 1 NCB No 284,062.30 71,015.57 Post 18 Supply of Laboratory Equipment Physics. C2/Educati Mon-17-Sep- Chemistry & Biology on 1 NCB No 213,114.75 53,278.69 Post 18 C2/Educati Mon-17-Sep- Supply of School Furniture on 3 NCB No 804,885.25 201,221.31 Post 18 CONSULTING SERVICES BORNO Skills Acquisition Training C1/Transiti (3Nos Consultancies across onal Mon-09-Jul- 10 LGAs) Support 3 QCBS No 491,803.28 258,196.72 Post 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 32 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Specialized psycho-social support responding to C1/Commu needs (3Nos Consultancies nity Wed-28-Mar- across 10 LGAs) Resilience 3 QCBS No 826,229.51 619,672.13 Post 18 Consultancy for the Mobilisation and Organisation of Civic Education with Cultural and Recreational activities at Community Level with programs that respond to needs as prioritized by community based diagnosis (3Nos C1/Commu Consultancies across 10 nity Wed-11-Apr- LGAs) Resilience 3 QCBS No 442,622.95 265,573.77 Post 18 Consultancy for Sensitization, Community Mobilization and formation of peace groups within 7 Communities(establishmen t of community platforms to discuss community needs, grievances; and C1/Commu redress mechanisms. (1No nity Mon-30-Apr- Consultancy) Resilience 1 QCBS No 531,147.54 318,688.52 Prior 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 33 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Consultancy for Post- C1/Commu Conflict Transitional Justice nity Mon-21-May- and Accountability Resilience 1 QCBS No 147,540.98 88,524.59 Post 18 Statewide sponsorship for Radio Programming for Peacebuilding Campaign and Content for dissemination (focusing on deradicalisation, grievance C1/Commu redress and peacebuilding nity Mon-04-Jun- outreach themes) Resilience 1 CQS No 475,409.84 178,278.69 Prior 18 Consultancy for Educational campaigns for the prevention of mine and unexploded ordinance accidents /Mobilisation and Sensitization Campaign on Mine Action (Unexploded C1/Commu Ordnances) (1No nity Mon-04-Jun- Consultancy) Resilience 1 QCBS No 442,622.95 354,098.36 Prior 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 34 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Consultancy for Leadership Accountability and Transparency Training Programme (NELATTP) Targeting 20 LGA Staff and State Ministry Personal per LGA - Development of a transparency and accountability Local Governance Model through community participation C1/Commu (social accountability nity Fri-25-May- mechanisms) Resilience 1 CQS No 88,524.59 55,327.87 Post 18 Consultancy for Registration, Mapping and C1/Strengt Profiling of all local hening government structures and Local existing capacities State Governanc Fri-25-May- Wide e 1 CQS No 49,180.33 30,737.70 Post 18 Consultancy to provide C1/Strengt Capacity building of LG hening Officers for economic Local planning and policy Governanc Fri-25-May- development e CQS No 88,524.59 55,327.87 Post 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 35 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT C1/Strengt hening Capacity building for LG Local officials on programme Governanc Fri-25-May- design and implementation e CQS No 88,524.59 55,327.87 Post 18 Capacity building of LG C1/Strengt Officers for local hening governments on budget Local planning and execution, Governanc Fri-25-May- monitoring and reporting e 1 CQS No 88,524.59 55,327.87 Post 18 Capacity building of LG Officers for strategic communications C1/Strengt (Legislative Advocacy, hening Media relations, Local Stakeholder Management Governanc Fri-25-May- etc). e CQS No 88,524.59 55,327.87 Post 18 Capacity Building for 10 Local Government C1/Strengt Emergency Management hening Responders in Displaced Local and Transitional Local Governanc Fri-25-May- Government Officials e 1 CQS No 203,278.69 152,459.02 Post 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 36 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Sensitization, training (especially on Identification, Documentation, Tracing and Reunification and follow up) and coaching for state and non-state partners on case management of UASC C1/Program (Unaccompanied and Support to Fri-25-May- Separated Children) UASC 1 MOU No 73,770.49 59,016.39 Post 18 Training for officials of relevant State MDAs on C1/Program effective approaches to Support to Thu-28-Jun- UASC UASC 1 IC No 16,393.44 13,114.75 Post 18 Teacher Training and C1/Educati Fri-25-May- Recertification on 1 MOU No 442,622.95 77,459.02 Post 18 Training of Community Health Workers (CHeWs, VHWs, Midwives) to Staff Targeted Health Facilities (3Nos consultancies across the state. Amount Inclusive of Workshop and per diem Mon-29-Apr- payments) C1/Health 3 QCBS No 796,721.31 298,770.49 Post 19 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 37 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Sensitization and Mobilisation for Health (Outreach Programs) in 27 LGAs (Over 10 Fri-25-May- engagements) C1/Health 10 CQS No 708,196.72 265,573.77 Post 18 Identification and training of Village Levels Mechanics and Local Area Mechanics on Operation and Maintenance of existing Hand Pump and Solar powered Borehole for effective utilization and Fri-25-May- management. C2/WASH 1 CQS No 98,360.66 73,770.49 Post 18 ADAMAWA Refresher Training of Existing Extension Workers C1/Transiti to support Livelihoods onal Thu-10-May- Projects Support 1 CQS No 65,573.77 65,573.77 Post 18 Training of affected farmers to apply inputs and access targeted C1/Transiti agricultural value chains onal Thu-21-Jun- and agribusiness skills Support 1 CQS No 167,216.39 167,216.39 Post 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 38 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Establishment of Returnees Resettlement Registry at each LGA for Sensitization, Mobilisation and Logistics support for Safe and C1/Transiti Voluntary returns to 7 onal Thu-24-May- LGAs being rehabilitated Support 1 CQS No 61,565.57 49,252.46 Post 18 Consultancy to provide C1/Transiti Training for Bio Data onal Thu-10-May- Registration Support Support 1 IC No 1,377.05 1,101.64 Post 18 Consultancy for Sensitization, Community Mobilization and formation of peace groups within 7 Communities(establishmen t of community platforms to discuss community C1/Commu needs, grievances; and nity Mon-04-Jun- redress mechanisms Resilience 1 QCBS No 344,262.30 206,557.38 Prior 18 Diagnosis of community- specific reconciliation, peacebuilding and social C1/Commu cohesion needs and nity Thu-03-May- consequent development Resilience 2 QCBS No 344,262.30 206,557.38 Post 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 39 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT of Civil Education Programs using Cultural and Recreational activities at Community Level (2Nos Consultancies) Provision of specialized psycho-social assessment and support responding to needs through group support, recreational, customary and socializing activities, referrals etc C1/Commu (3Nos Consultancies across nity Mon-11-Jun- the affected areas) Resilience 3 QCBS No 642,622.95 481,967.21 Post 18 Sensitization and Mobilisation Programs for Awareness against Stigmatization of Woman and Children associated C1/Commu with armed groups. (1No nity Mon-04-Jun- Consultancy) Resilience 1 QCBS No 413,114.75 247,868.85 Prior 18 Consultancy for Mediation and Alternate Dispute Resolution Capacity C1/Commu Building within the nity Mon-18-Jun- Community Leadership and Resilience 3 QCBS No 425,960.66 255,576.39 Post 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 40 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Governance Structures (3Nos Consultancies acrossthe state) C1/Citizen- Consultancy for Leadership Governmen Accountability and t Transparency Training Relationshi Thu-10-May- Programme p Building 1 CQS No 72,131.15 45,081.97 Post 18 Registration, Mapping and C1/Strengt Profiling of all local hening government structures and Local existing capacities State Governanc Mon-28-May- Wide e 1 CQS No 39,344.26 24,590.16 Post 18 C1/Strengt Capacity building of LG hening Officers for economic Local planning and policy Governanc Mon-28-May- development e 1 CQS No 72,131.15 45,081.97 Post 18 C1/Strengt hening Capacity building for Local programme design and Governanc Mon-28-May- implementation e 1 CQS No 72,131.15 45,081.97 Post 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 41 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Capacity building of LG C1/Strengt Officers for local hening governments on budget Local planning and execution, Governanc Mon-28-May- monitoring and reporting e 1 CQS No 72,131.15 45,081.97 Post 18 Capacity building of LG Officers for strategic communications C1/Strengt (Legislative Advocacy, hening Media relations, Local Stakeholder Management Governanc Thu-21-Jun- etc). e 1 CQS No 72,131.15 45,081.97 Post 18 Hygiene Promotion Mon-17-Sep- Sensitization/Mobilization C2/WASH 1 IC No 9,180.33 6,885.25 Post 18 Hygiene Promotion Mon-12-Nov- Campaign C2/WASH 1 CQS No 85,677.59 64,258.20 Post 18 Training of Community Health Workers (CHeWs) to Staff Targeted Health Thu-13-Dec- Facilities C2/Health 1 CQS No 68,852.46 55,081.97 Post 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 42 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Sensitization and Mobilisation for Health Mon-17-Sep- (Outreach Programs) C2/Health 1 CQS No 183,606.56 146,885.25 Post 18 Mobilization and Sensitization for Children C2/Educati Thu-31-May- Education on 1 CQS No 206,557.38 206,557.38 Post 18 Teacher Training and Recertification ( Primary C2/Educati Thu-13-Dec- and Secondary Schools ) on 1 CQS No 360,655.74 360,656.74 Prior 18 YOBE Skills Acquisition Training C1/Transiti 3 Nos Consultancies across onal Wed-25-Apr- 8 LGAs) Support 3 QCBS No 524,590.16 367,213.11 Post 18 Consultancy for Sensitization, Community Mobilization and formation of peace groups within 15 C1/Peace Wed-23-May- Communities Building 1 QCBS No 491,803.28 319,672.13 Prior 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 43 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Diagnosis of community- specific reconciliation, peacebuilding and social cohesion needs and consequentt development of Civil Education Programs using Cultural and Recreational activities at C1/Peace Mon-04-Jun- Community Level Building 1 CQS No 49,180.33 31,967.21 Post 18 Consultancy for Mediation and Alternate Dispute Resolution Capacity Building within the Community Leadership and C1/Peace Mon-04-Jun- Governance Structures Building 1 CQS No 177,049.18 115,081.97 Post 18 Radio programs on mine awareness, dispute resolution in Hausa, Kanuri C1/Peace Wed-25-Jul- and Fulfulde Building 1 CQS No 280,719.92 105,269.97 Post 18 Provision of specialized psycho-social assessment and support responding to needs (3 Nos Consultancies C1/Peace Wed-20-Jun- across 8 LGAs) Building 3 QCBS No 625,822.95 438,076.07 Post 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 44 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Mapping and profiling of local government C1/Strengt structures and hening communities in places of Local both displacement and Governanc Thu-28-Jun- origin e 1 CQS No 39,344.26 39,344.26 Post 18 Establishment of C1/Strengt community platforms to hening discuss community needs, Local grievances; and building a Governanc Wed-06-Jun- bottom-up planning model e 1 CQS No 74,948.93 59,959.14 Post 18 Development of a transparency and accountability model C1/Strengt through community hening participation (social Local accountability Governanc Wed-06-Jun- mechanisms) e 1 CQS No 47,377.05 37,901.64 Post 18 C1/Strengt Capacity building of LG hening Officers for economic Local planning and policy Governanc Thu-28-Jun- development e 1 CQS No 55,737.70 44,590.16 Post 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 45 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT C1/Strengt hening Capacity building for Local programme design and Governanc Thu-28-Jun- implementation e 1 CQS No 55,737.70 44,590.16 Post 18 Capacity building of LG C1/Strengt Officers for local hening governments on budget Local planning and execution, Governanc Thu-28-Jun- monitoring and reporting e 1 CQS No 55,737.70 44,590.16 Post 18 Capacity building of LG Officers for strategic communications C1/Strengt (Legislative Advocacy, hening Media relations, Local Stakeholder Management Governanc etc). e 1 CQS No 55,737.70 44,590.16 Post Thu-26-Jul-18 Sensitization, training (especially on Identification, Documentation, Tracing and Reunification and follow up) and coaching for state and non-state C1/Program partners on case Support on Thu-07-Jun- management of UASC UASC 1 CQS No 52,459.02 41,967.21 Post 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 46 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Training for officials of C1/Program relevant MDAs on effective Support on Thu-28-Jun- approaches to UASC UASC 1 CQS No 8,196.72 6,557.38 Post 18 Menstrual Hygiene Management to support Women and Girls of productive ages to effectively maintain their Thu-17-May- menstrual hygiene C2/WASH 1 QCBS No 110,163.93 41,311.48 Post 18 Community Led Total Sanitation (CLTS) Implementation in Thu-31-May- communities C2/WASH 1 QCBS No 220,327.87 82,622.95 Post 18 Community Management training of entire Communities in the 8 proposed LGAs to effectively manage their Water, Sanitation and Mon-18-Jun- Hygiene Facilities C2/WASH 3 QCBS No 293,770.49 110,163.93 Post 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 47 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Identification and training of Village Levels Mechanics and Local Area Mechanics on Operation and Maintenance of existing Hand Pump and Solar powered Borehole for effective utilization and Thu-17-May- management. C2/WASH 1 CQS No 98,360.66 61,475.41 Post 18 Water Safety Plan implementation in the entire Communities of the Mon-16-Jul- four LGAs. C2/WASH 1 CQS No 112,459.02 84,344.26 Post 18 Integrated Outreach Services (Up to 5 activities Thu-17-May- envisaged) C2/Health 5 QCBS No 344,262.30 129,098.36 Post 18 Training of Community Health Workers (CHeWs, VHWs, Midwives) to Staff Thu-15-Nov- Targeted Health Facilities C2/Health 1 QCBS No 501,639.34 376,229.51 Prior 18 Teacher Training and C2/Educati Mon-26-Nov- Recertification in all LGAs on 1 MOU No 278,688.52 209,016.39 Post 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 48 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT PCNI NERSP PMC CELL Project Wide Project C3/Technic Management Consultancy al 2,000,000. Wed-11-Apr- Firm Assistance 1 QCBS No 3,000,000.00 00 Prior 18 Consultancy services for immediate- and medium- term implementation capacity building (4 C3/Technic separate Consultancies al Thu-03-May- Envisaged) Assistance 4 CQS No 536,393.44 268,196.72 Prior 18 Consultancy Services for C3/Technic Monitoring and Evaluation al Baseline Study Assistance 1 QCBS No 177,049.18 177,049.18 Post Fri-27-Apr-18 Consultancy services for setting up citizen engagement and third C3/Technic party monitoring al mechanisms Assistance 1 CQS No 177,049.00 59,016.33 Post Fri-06-Apr-18 Consultancy Services for C3/Technic Environmental Impact al Assessment Assistance 1 QCBS No 39,344.26 39,344.26 Post Fri-13-Apr-18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 49 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT NON- CONSULTING SERVICES ADAMAWA Door to Door Collection of Thu-24-May- Solid waste in 7 LGAs C2/WASH 1 NCB No 236,065.57 88,524.59 Post 18 Disposal of Waste from Door to Door Collection in Tue-13-Feb- 7 LGAs C2/WASH 1 NCB No 229,508.20 86,065.57 Post 18 OPERATIONAL COSTS PCNI NERSP PMC CELL PMC Software, Intranet and C3/Operati Tools onal Costs 3 RfQ No 159,240.16 159,240.16 Post Fri-27-Apr-18 Video Conferencing C3/Operati Thu-25-Jan- Equipment onal Costs 1 RfQ No 131,147.54 131,147.54 Post 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 50 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT C3/Operati Tue-27-Mar- Office Vehicles onal Costs 1 RfQ No 344,265.00 344,265.00 Post 18 BORNO STATE Procurement of 12 laptop computers, 12 laserjet printers, 4 photocopiers, 3 desktops, 15 desktops for work stations, 2 deskjet printers, HP Scanjet C3/Operati scanner onal Costs 1 RfQ No 159,240.16 159,240.16 Post Fri-27-Apr-18 Procurement of video conference equipment and C3/Operati internet connectivity onal Costs 1 RfQ No 65,574.00 65,574.00 Post Fri-27-Apr-18 Procurement of Office C3/Operati Tue-27-Mar- Furniture onal Costs 1 NCB No 32,786.89 32,786.89 Post 18 Procurement of 1 Video C3/Operati Wed-28-Mar- Camera, 2 DLSR Cameras, onal Costs 1 RfQ No 7,000.00 7,000.00 Post 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 51 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Procurement of 100KVA sound proof Generator, C3/Operati Sun-20-May- 10KVA Inverter System onal Costs 1 RfQ No 42,623.00 42,623.00 Post 18 Procurement of Office Vehicles - 2 Toyota Prado Jeep, 3 Toyota Hilux, 1 C3/Operati Wed-14-Mar- Toyota Corolla onal Costs 1 NCB No 448,525.00 448,525.00 Post 18 ADAMAWA STATE Procurement of computers, printers and other C3/Operati Wed-28-Mar- accessories onal Costs 1 RfQ No 24,131.15 24,131.15 Post 18 Procurement of video conference equipment and C3/Operati Wed-28-Mar- internet connectivity onal Costs 1 RfQ No 65,574.00 65,574.00 Post 18 Procurement of Office C3/Operati Tue-27-Mar- Furniture onal Costs 1 NCB No 32,786.89 32,786.89 Post 18 Procurement of 1 Video C3/Operati Wed-28-Mar- Camera, 2 DLSR Cameras, onal Costs 1 RfQ No 20,327.87 20,327.87 Post 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 52 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Procurement of 100KVA sound proof Generator, C3/Operati Mon-26-Mar- 10KVA Inverter System onal Costs 1 RfQ No 42,623.00 42,623.00 Post 18 Procurement of Office Vehicles - 2 Toyota Prado Jeep, 3 Toyota Hilux, 1 C3/Operati Tue-27-Mar- Toyota Corolla onal Costs 1 RfQ No 518,033.00 518,033.00 Post 18 YOBE STATE Procurement of computers, printers and other C3/Operati Wed-28-Mar- accessories onal Costs 1 RfQ No 24,131.15 24,131.15 Post 18 Procurement of video conference equipment and C3/Operati Wed-28-Mar- internet connectivity onal Costs 1 RfQ No 65,574.00 65,574.00 Post 18 Procurement of Office C3/Operati Tue-27-Mar- Furniture onal Costs 1 NCB No 32,786.89 32,786.89 Post 18 Procurement of 1 Video C3/Operati Wed-28-Mar- Camera, 2 DLSR Cameras, onal Costs 1 RfQ No 20,327.87 20,327.87 Post 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 53 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Procurement of 100KVA sound proof Generator, C3/Operati Mon-26-Mar- 10KVA Inverter System onal Costs 1 RfQ No 42,623.00 42,623.00 Post 18 Procurement of Office C3/Operati Tue-27-Mar- Vehicles onal Costs 1 RfQ No 468,852.46 468,852.46 Post 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 54 PROCUREMENT Nigeria : Multi-Sectoral Crisis Recovery Project for North Eastern Nigeria PLAN General Information Country: Nigeria 2018-03-12 Bank’s Approval Date of the Original Procurement Plan: 2023-06-02 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P157891 GPN Date: Project Name: Multi-Sectoral Crisis Recovery Project for North Eastern Nigeria Loan / Credit No: IDA / 59880, IDA / 66490 MCRP Federal Coordinating Unit Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NG-MCRP-FED-UNIT-52655-G Technical Assistance and Pro Request for Quota Single Stage - One E IDA / 59880 Post Limited 395,500.00 180,889.66 Completed 2018-02-05 2018-05-22 2018-04-02 2018-06-25 2018-09-29 2018-07-23 O-RFQ / Office Vehicles ject Management Support tions nvelope NG-MCRP-FED-52656-GO-RF Technical Assistance and Pro Request for Quota Single Stage - One E IDA / 59880 Post Limited 131,147.54 84,481.67 Completed 2017-12-20 2018-04-06 2018-02-14 2018-05-22 2018-08-13 2018-07-20 Q / Video Conferencing Equip ject Management Support tions nvelope ment NG-MCRP-FED-87191-GO-RF Technical Assistance and Pro Request for Quota Single Stage - One E Q / Supply of Camera and oth IDA / 59880 Post Limited 12,164.00 0.00 Canceled 2018-11-28 2019-01-23 2019-07-22 ject Management Support tions nvelope er equipment for Strategic C ommunication NG-MCRP-FED-52657-GO-RF Technical Assistance and Pro Request for Quota Single Stage - One E IDA / 59880 Post Open - National 159,240.16 0.00 Canceled 2018-03-20 2018-05-15 2018-11-11 Q / PMC Software, Intranet a ject Management Support tions nvelope nd Tools NG-MCRP-FED-103654-GO-R Technical Assistance and Pro Request for Quota Single Stage - One E IDA / 59880 Post Limited 7,575.19 0.00 Canceled 2019-03-23 2019-05-18 2019-11-14 FQ / Office equipment & facili ject Management Support tions nvelope ties NG-MCRP FED COORD. UNIT- Technical Assistance and Pro Request for Quota Single Stage - One E Pending Impl 182107-GO-RFQ / Strategic C IDA / 59880 Post Limited 20,000.00 0.00 2020-06-29 2020-09-07 2020-11-06 ject Management Support tions nvelope ementation ommunications Equipment NG-MCRP FED COORD. UNIT- Technical Assistance and Pro Request for Quota Single Stage - One E 182115-GO-RFQ / Access Con IDA / 59880 Post Limited 5,000.00 4,277.16 Completed 2020-06-29 2020-09-17 2020-08-24 2020-10-31 2021-02-20 2020-11-13 ject Management Support tions nvelope trol System for the MCRP Offi ce NG-MCRP FED COORD. UNIT- Technical Assistance and Pro Request for Quota Single Stage - One E 207041-GO-RFQ / Fire Protec IDA / 59880 Post Limited 4,931.00 3,489.49 Completed 2020-07-20 2020-10-06 2020-09-14 2020-11-19 2021-03-13 2020-12-22 ject Management Support tions nvelope tive & Prevention Equipment NG-MCRP FED COORD. UNIT- Technical Assistance and Pro Request for Quota Single Stage - One E 207045-GO-RFQ / COVID 19 IDA / 59880 Post Limited 74,548.00 72,869.88 Completed 2020-06-20 2020-05-28 2020-08-15 2020-06-27 2021-02-11 2020-07-15 ject Management Support tions nvelope Remote Access Equipment NG-MCRP FED COORD. UNIT- 337063-GO-RFQ / Upgrading Technical Assistance and Pro Request for Quota Single Stage - One E Pending Impl IDA / 66490 Post Limited 40,000.00 0.00 2023-02-13 2023-04-10 2023-10-07 of Data and Spatial Informati ject Management Support tions nvelope ementation on Unit at Modibbo Adama U niversity NG-MCRP FED COORD. UNIT- 337067-GO-RFQ / Establishm ent of Community Nursery/Ar Technical Assistance and Pro Request for Quota Single Stage - One E Pending Impl IDA / 66490 Post Limited 30,000.00 0.00 2023-02-14 2023-04-11 2023-10-08 boretum and Furnishing of N ject Management Support tions nvelope ementation orth East Advancement and Development Center at Modi bbo Adama University NG-MCRP FED COORD. UNIT- 337010-GO-RFQ / Supply of L Technical Assistance and Pro Request for Quota Single Stage - One E Pending Impl ab Equipment for the Seed L IDA / 66490 Post Limited 11,000.00 0.00 2023-02-19 2023-04-16 2023-10-13 ject Management Support tions nvelope ementation ab and Research Farm at La ke Chad Research Institute, Maiduguri NG-MCRP FED COORD. UNIT- 337078-GO-RFQ / Regional Pr Technical Assistance and Pro Request for Quota Single Stage - One E Under Imple oject Vehicles (6 Nos: 3 4 wh IDA / 66490 Post Limited 450,000.00 0.00 2023-02-20 2023-04-17 2023-10-14 ject Management Support tions nvelope mentation eel drive double cabin pickup trucks, 1 SUV,1 Bus, 1 saloon ) NG-MCRP FED COORD. UNIT- 362287-GO-RFQ / Provision o f Laptops, Printers, Research Technical Assistance and Pro Request for Quota Single Stage - One E Pending Impl IDA / 66490 Post Limited 77,000.00 0.00 2023-06-06 2023-08-01 2024-01-28 Software, and other Equipme ject Management Support tions nvelope ementation nt to Researchers at the Mod dibo Adama University of Tec hnology, Yola. NG-MCRP FED COORD. UNIT- 362304-GO-RFQ / Provision o Technical Assistance and Pro Request for Quota Single Stage - One E Pending Impl f Laptops, Printers, Research IDA / 66490 Post Limited 18,000.00 0.00 2023-06-06 2023-08-01 2024-01-28 ject Management Support tions nvelope ementation Software, and other Equipme nt to Researchers at the Fed eral University Gashua NG-MCRP FED COORD. UNIT- 362317-GO-RFQ / Provision o f Laptops, Printers, Research Technical Assistance and Pro Request for Quota Single Stage - One E Pending Impl IDA / 66490 Post Limited 27,000.00 0.00 2023-06-06 2023-08-01 2024-01-28 Software, and other Equipme ject Management Support tions nvelope ementation nt to Researchers at the Born o State University Maiduguri NG-MCRP FED COORD. UNIT- 362349-GO-RFQ / Provision o Technical Assistance and Pro Request for Quota Single Stage - One E Pending Impl f Laptops, Printers, Research IDA / 66490 Post Limited 10,000.00 0.00 2023-06-06 2023-08-01 2024-01-28 ject Management Support tions nvelope ementation Software, and other Equipme nt to Researchers at the Yob e State University Page 1 NG-MCRP FED COORD. UNIT- 362351-GO-RFQ / Supply and Technical Assistance and Pro Request for Quota Single Stage - One E Pending Impl Installation of Greenhouse fo IDA / 66490 Post Limited 15,000.00 0.00 2023-06-06 2023-08-01 2024-01-28 ject Management Support tions nvelope ementation r Agriculture to Researcher in Federal University of Gahsua NG-MCRP FED COORD. UNIT- 362353-GO-RFQ / Provision o Technical Assistance and Pro Request for Quota Single Stage - One E Pending Impl f Research Software’s and Sa IDA / 66490 Post Limited 49,000.00 0.00 2023-06-06 2023-08-01 2024-01-28 ject Management Support tions nvelope ementation tellite Image to Researchers at the University of Maidugur i NG-MCRP FED COORD. UNIT- 362358-GO-RFQ / Provision o Technical Assistance and Pro Request for Quota Single Stage - One E Pending Impl IDA / 66490 Post Limited 87,000.00 0.00 2023-06-06 2023-08-01 2024-01-28 f Laptops, Printers, Equipmen ject Management Support tions nvelope ementation t to Researchers at the Unive rsity of Maiduguri NG-MCRP FED COORD. UNIT- 337105-GO-RFQ / Equipment Technical Assistance and Pro Request for Quota Single Stage - One E Pending Impl IDA / 66490 Post Limited 180,000.00 0.00 2023-02-16 2023-04-13 2023-10-10 for the GIS and Survey Labor ject Management Support tions nvelope ementation atory at Federal University G ashua NG-MCRP FED COORD. UNIT- 337059-GO-RFQ / Supply and Installation of Research Equi Technical Assistance and Pro Request for Quota Single Stage - One E Pending Impl pment (Pyranometer and Sun IDA / 66490 Post Limited 180,000.00 0.00 2023-02-17 2023-04-14 2023-10-11 ject Management Support tions nvelope ementation photometer) for the study of Solar Radiation and Climate Change at Adamawa State U niversity, Mubi NG-MCRP FED COORD. UNIT- 337112-GO-RFQ / Set Up and Technical Assistance and Pro Request for Quota Single Stage - One E Pending Impl Equipping the Centre for Envi IDA / 66490 Post Limited 190,000.00 0.00 2023-02-18 2023-04-15 2023-10-12 ject Management Support tions nvelope ementation ronmental and Geographical Research at Yobe State Univ. Damaturu NG-MCRP FED COORD. UNIT- 336989-GO-RFQ / Supply of R Technical Assistance and Pro Request for Quota Single Stage - One E Pending Impl IDA / 66490 Post Limited 280,000.00 0.00 2023-02-11 2023-04-08 2023-10-05 esearch Equipment (Optical ject Management Support tions nvelope ementation Emission Spectroscopy) at Bo rno State University NG-MCRP FED COORD. UNIT- 337079-GO-RFQ / Equiping th e Soil Research Laboratory a Technical Assistance and Pro Request for Quota Single Stage - One E Pending Impl IDA / 66490 Post Limited 220,000.00 0.00 2023-02-12 2023-04-09 2023-10-06 nd Deployment of Solar Powe ject Management Support tions nvelope ementation r for the GIS and Carthograp hy Labs at University of Maid uguri NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NG-MCRP-FED-103648-NC-DI Technical Assistance and Pro R / Office Cleaning and Janito IDA / 59880 Post Direct Selection Direct 12,000.00 9,137.59 Signed 2019-03-04 2018-12-03 2019-03-09 2018-12-06 2019-04-13 2018-12-21 2019-10-10 ject Management Support rial Services NG-MCRP FED COORD. UNIT- 286712-NC-RFQ / Quarterly P Technical Assistance and Pro Request for Quota Single Stage - One E Pending Impl IDA / 66490 Post Limited 10,000.00 0.00 2022-06-07 2022-08-02 2023-01-29 roduction and Circulation of ject Management Support tions nvelope ementation NE RECOVERY NEWSLETTER (Showcasing MCRP) NG-MCRP FED COORD. UNIT- 337126-NC-RFQ / MIT Region Technical Assistance and Pro Request for Quota Single Stage - One E Pending Impl IDA / 66490 Post Limited 300,000.00 0.00 2023-04-10 2023-06-05 2023-12-02 al Entrepreneurship Accelera ject Management Support tions nvelope ementation tion Program (REAP) CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NG-MCRP-FED-52659-CS-CQ Technical Assistance and Pro Consultant Qualifi S / Consultancy Services for IDA / 59880 Post Open - National 39,344.26 0.00 Canceled 2018-01-23 2018-06-04 2018-02-13 2018-03-29 2018-04-28 2018-06-02 2018-11-29 ject Management Support cation Selection Environmental Impact Assess ment NG-MCRP-FED-52645-CS-QC Technical Assistance and Pro Quality And Cost- Open - Internationa BS / Regional (Project Wide) IDA / 59880 Prior 3,000,000.00 0.00 Canceled 2018-03-07 2018-03-12 2018-03-28 2018-03-12 2018-05-11 2018-07-18 2018-06-08 2018-09-03 2018-07-08 2018-08-12 2018-09-16 2019-09-16 ject Management Support Based Selection l Project Management Consult ancy Firm NG-MCRP FED-86994-CS-CQ S / Mapping of services for su Technical Assistance and Pro Consultant Qualifi IDA / 59880 Post Open - National 150,000.00 0.00 Canceled 2018-11-13 2018-12-04 2019-01-17 2019-02-16 2019-03-23 2019-09-19 rvivors of Sexual Exploitation ject Management Support cation Selection and Abuse (SEA)/Gender Bas ed Violence (GBV) NG-MCRP-FED-52658-CS-CQ Technical Assistance and Pro Consultant Qualifi S / Consultancy Services for IDA / 59880 Post Open - National 177,049.18 0.00 Canceled 2018-02-06 2018-09-11 2018-02-27 2018-04-12 2018-05-12 2018-06-16 2018-12-13 ject Management Support cation Selection Monitoring and Evaluation Ba seline Study NG-MCRP-FED-103651-CS-C Technical Assistance and Pro Consultant Qualifi IDA / 59880 Post Open - National 9,040.00 0.00 Canceled 2019-03-11 2019-04-01 2019-05-15 2019-06-14 2019-07-19 2020-01-15 QS / Website Design ject Management Support cation Selection NG-MCRP-FED-87190-CS-CQ S / Consultancy for Pre-Deplo Technical Assistance and Pro Consultant Qualifi yment Services, Software Co IDA / 59880 Post Open - National 40,000.00 0.00 Canceled 2018-11-23 2018-12-07 2019-01-11 2019-02-10 2019-03-17 2019-04-16 ject Management Support cation Selection nfiguration and Deployment of the MCRP Knowledge Man agement System NG-MCRP-FED-103653-CS-C Technical Assistance and Pro Consultant Qualifi QS / Consultancy for Grievan IDA / 59880 Post Open - National 150,000.00 0.00 Canceled 2019-03-18 2019-04-08 2019-05-22 2019-06-21 2019-07-26 2020-01-22 ject Management Support cation Selection ce Redress Mechanism NG-MCRP-FED-52662-CS-CQ S / Consultancy services for s Technical Assistance and Pro Consultant Qualifi IDA / 59880 Post Open - National 177,049.00 0.00 Canceled 2018-01-12 2018-02-02 2018-03-18 2018-04-17 2018-05-22 2018-11-18 etting up citizen engagement ject Management Support cation Selection and third party monitoring m echanisms Page 2 NG-MCRP FED COORD. UNIT- 182113-CS-CQS / Consultanc Technical Assistance and Pro Consultant Qualifi y for preparation of detailed IDA / 59880 Post Limited 50,000.00 0.00 Under Review 2020-06-29 2020-07-23 2020-07-13 2020-08-12 2020-09-16 2021-03-15 ject Management Support cation Selection Documentary of the achieve ments of the MCRP Project NG-MCRP FED COORD. UNIT- 182110-CS-CQS / Consultanc y to provide TA towards deve Technical Assistance and Pro Consultant Qualifi IDA / 59880 Post Limited 30,000.00 0.00 Under Review 2020-07-02 2020-07-23 2020-07-23 2020-08-22 2020-09-26 2021-03-25 loping high quality Strategic ject Management Support cation Selection communication Content and i ntegrated public relations an d media strategy NG-MCRP FED COORD. UNIT- 182111-CS-CQS / Consultanc Technical Assistance and Pro Consultant Qualifi Under Implement y for design and establishme IDA / 59880 Post Limited 51,147.54 0.00 2020-06-29 2020-07-20 2020-08-19 2020-09-23 2021-03-22 ject Management Support cation Selection ation nt of Security Advisory Syste m for the MCRP Federal Coor dinating Unit NG-MCRP FED COORD. UNIT- 181286-CS-CQS / BAY Registr Technical Assistance and Pro Consultant Qualifi Under Implement IDA / 59880 Post Limited 119,296.00 0.00 2020-06-15 2020-06-03 2020-06-29 2020-09-21 2020-07-29 2020-09-02 2021-03-01 y (Web based Beneficiary Tr ject Management Support cation Selection ation acking and Monitoring Applic ation) NG-MCRP FED COORD. UNIT- Technical Assistance and Pro Consultant Qualifi 182104-CS-CQS / BAYSmart ( IDA / 59880 Post Limited 64,350.36 0.00 Under Review 2020-06-15 2020-06-12 2020-06-29 2020-07-29 2020-09-02 2021-03-01 ject Management Support cation Selection Infrastructure Projects Tracki ng Tool) NG-MCRP FED COORD. UNIT- Technical Assistance and Pro Consultant Qualifi Under Implement 182106-CS-CQS / Website (D IDA / 59880 Post Limited 9,890.00 0.00 2020-06-08 2020-06-03 2020-06-22 2020-07-22 2020-08-26 2021-02-22 ject Management Support cation Selection ation esign, hosting, etc) NG-MCRP FED COORD. UNIT- 181691-CS-CQS / Mapping of Technical Assistance and Pro Consultant Qualifi services for survivors of Sexu IDA / 59880 Post Limited 150,000.00 0.00 Canceled 2020-07-20 2020-03-22 2020-08-03 2020-03-30 2020-09-02 2020-10-07 2021-04-05 ject Management Support cation Selection al Exploitation and Abuse (SE A)/Gender Based Violence (G BV) NG-MCRP FED COORD. UNIT- 206976-CS-CQS / Mapping of Technical Assistance and Pro Consultant Qualifi services for survivors of Sexu IDA / 59880 Post Limited 210,000.00 0.00 Under Review 2020-07-20 2020-03-22 2020-08-03 2020-09-02 2020-10-07 2021-04-05 ject Management Support cation Selection al Exploitation and Abuse (SE A)/Gender Based Violence (G BV) NG-MCRP FED COORD. UNIT- 207020-CS-CQS / Consultanc Technical Assistance and Pro Consultant Qualifi y for Preparation of Environm IDA / 59880 Post Limited 100,000.00 80,973.06 Completed 2020-07-15 2020-08-06 2020-07-29 2020-08-12 2020-08-28 2020-10-15 2020-10-02 2020-10-20 2021-03-31 2021-06-07 ject Management Support cation Selection ental and Social Managemen t Framework; and Resettlem ent Policy Framework NG-MCRP FED COORD. UNIT- 286721-CS-CQS / Consultanc Technical Assistance and Pro Consultant Qualifi IDA / 66490 Post Limited 25,000.00 0.00 Under Review 2022-04-04 2022-04-25 2022-04-18 2022-05-18 2022-06-22 2022-12-19 y for Skill Gap Assessment & ject Management Support cation Selection Capacity Building Plan of NER SP NG-MCRP FED COORD. UNIT- Technical Assistance and Pro Consultant Qualifi Under Implement 286716-CS-CQS / Third Party IDA / 66490 Post Limited 100,000.00 0.00 2022-04-04 2022-04-25 2022-04-18 2022-06-17 2022-05-18 2022-08-29 2022-06-22 2022-12-19 ject Management Support cation Selection ation Monitoring in Borno NG-MCRP FED COORD. UNIT- Technical Assistance and Pro Consultant Qualifi Under Implement 286708-CS-CQS / Third Party IDA / 66490 Post Limited 100,000.00 0.00 2022-04-04 2022-04-25 2022-04-18 2022-05-26 2022-05-18 2022-08-29 2022-06-22 2022-12-19 ject Management Support cation Selection ation Monitoring in Adamawa NG-MCRP FED COORD. UNIT- Technical Assistance and Pro Consultant Qualifi Under Implement 286718-CS-CQS / Third Party IDA / 66490 Post Limited 100,000.00 0.00 2022-04-04 2022-04-25 2022-04-18 2022-08-03 2022-05-18 2022-08-29 2022-06-22 2022-12-19 ject Management Support cation Selection ation Monitoring in Yobe NG-MCRP FED COORD. UNIT- 286725-CS-CQS / MCRP I Co Technical Assistance and Pro Consultant Qualifi Under Implement IDA / 66490 Post Limited 142,105.27 0.00 2022-05-11 2022-06-14 2022-05-25 2022-06-24 2022-07-29 2023-01-25 mponent 1 Beneficiary Impac ject Management Support cation Selection ation t Assessment (in 2022) NG-MCRP FED COORD. UNIT- 286720-CS-CQS / MCRP 1 Co Technical Assistance and Pro Consultant Qualifi Pending Impleme IDA / 66490 Post Limited 250,000.00 0.00 2022-05-25 2022-06-08 2022-07-08 2022-08-12 2023-02-08 mponent 2 Impact & Functio ject Management Support cation Selection ntation nality Assessment (2022) NG-MCRP FED COORD. UNIT- 286722-CS-CQS / Climate Ch Technical Assistance and Pro Consultant Qualifi IDA / 66490 Post Limited 100,000.00 0.00 Under Review 2022-05-20 2023-03-07 2022-06-03 2022-07-03 2022-08-07 2023-02-03 ange Vulnerability Mapping a ject Management Support cation Selection nd Adaptability Assessment NG-MCRP FED COORD. UNIT- 302343-CS-CQS / Consultanc Technical Assistance and Pro Consultant Qualifi Under Implement y for Development of Multi-S IDA / 66490 Post Limited 150,000.00 0.00 2022-06-30 2022-08-16 2022-07-14 2022-08-13 2022-09-17 2023-03-16 ject Management Support cation Selection ation ectoral Crisis Recovery Proje ct (MCRP) Management Infor mation System NG-MCRP FED COORD. UNIT- 286717-CS-CQS / Rapid Basel Technical Assistance and Pro Consultant Qualifi ine Assessment of Public Hea IDA / 66490 Post Limited 150,000.00 0.00 Canceled 2022-05-04 2022-05-18 2022-06-17 2022-07-22 2023-01-18 ject Management Support cation Selection lth Care Services in Borno, A damawa & Yobe States NG-MCRP FED COORD. UNIT- 337001-CS-CQS / Capacity & Technical Assistance and Pro Consultant Qualifi Under Implement Skills Gap Assessment of Fed IDA / 66490 Post Limited 100,000.00 0.00 2023-01-22 2023-03-13 2023-02-05 2023-03-07 2023-04-11 2023-10-08 ject Management Support cation Selection ation eral & State MDAs (Capacity to support MCRP PROLAC Act ivities) NG-MCRP FED COORD. UNIT- 337050-CS-CQS / Capacity B Technical Assistance and Pro Consultant Qualifi Pending Impleme uilding Trainings for MDAs (B IDA / 66490 Post Limited 280,000.00 0.00 2023-03-12 2023-03-26 2023-04-25 2023-05-30 2023-11-26 ject Management Support cation Selection ntation ased on MCRP PROLAC Skills Gaps Identified From the Ass essment) NG-MCRP FED COORD. UNIT- 337117-CS-CQS / Consultanc y for Management of Lake Ch Technical Assistance and Pro Consultant Qualifi Under Implement IDA / 66490 Post Limited 160,000.00 0.00 2023-02-03 2023-05-08 2023-02-17 2023-03-19 2023-04-23 2023-10-20 ad Basin Scholarships (Schol ject Management Support cation Selection ation arships Online Portal, Selecti on Process, Placement, Mana gement ) Page 3 NG-MCRP FED COORD. UNIT- Technical Assistance and Pro Consultant Qualifi 337135-CS-CQS / Consultanc IDA / 66490 Post Limited 150,000.00 0.00 Under Review 2023-02-04 2023-02-13 2023-02-18 2023-03-20 2023-04-24 2023-10-21 ject Management Support cation Selection y for Safeguards Audit of MC RP OF & AF NG-MCRP FED COORD. UNIT- 337131-CS-CQS / MCRP Com Technical Assistance and Pro Consultant Qualifi Pending Impleme IDA / 66490 Post Limited 250,000.00 0.00 2023-03-06 2023-03-20 2023-04-19 2023-05-24 2023-11-20 ponent 2 Impact & Functional ject Management Support cation Selection ntation ity Assessment (2023) NG-MCRP FED COORD. UNIT- Technical Assistance and Pro Consultant Qualifi Pending Impleme 337088-CS-CQS / Consultanc IDA / 66490 Post Limited 100,000.00 0.00 2023-02-07 2023-02-21 2023-03-23 2023-04-27 2023-10-24 ject Management Support cation Selection ntation y for Greviance Redress Mec hanism (GRM) NG-MCRP FED COORD. UNIT- 336981-CS-CQS / Consultanc Technical Assistance and Pro Consultant Qualifi Pending Impleme IDA / 66490 Post Limited 50,000.00 0.00 2023-05-09 2023-05-23 2023-06-22 2023-07-27 2024-01-23 y for Professional Project Man ject Management Support cation Selection ntation agement Support and Softwa re NG-MCRP FED COORD. UNIT- Technical Assistance and Pro Consultant Qualifi Pending Impleme 337044-CS-CQS / Security Ri IDA / 66490 Post Limited 100,000.00 0.00 2023-02-10 2023-02-24 2023-03-26 2023-04-30 2023-10-27 ject Management Support cation Selection ntation sk Assessment & Monitoring System INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NG-MCRP-FED-78900-CS-CD S / Consultancy Services for Technical Assistance and Pro IDA / 59880 Prior Direct Selection Direct 280,000.00 232,046.60 Signed 2018-06-04 2018-09-20 2018-07-02 2018-09-25 2018-09-05 2018-11-08 2019-03-04 Safeguards Screening, Capac ject Management Support ity Building And Compliance To the PCU. NG-MCRP-FED-103650-CS-IN Technical Assistance and Pro Individual Consult DV / Training on ESRI Arc GIS IDA / 59880 Post Limited 12,500.00 0.00 Canceled 2019-03-11 2019-03-16 2019-04-06 2019-05-11 2019-11-07 ject Management Support ant Selection including Licencing NG-MCRP FED COORD. UNIT- 239091-CS-INDV / Procureme nt of Agric Specialist for the Technical Assistance and Pro Individual Consult Under Implement IDA / 59880 Post Limited 33,000.00 0.00 2021-06-27 2021-06-14 2021-07-02 2021-07-23 2021-09-01 2022-09-01 North East Recovery and Sta ject Management Support ant Selection ation bility Programme Project Man agement and Coordination C ell NG-MCRP FED COORD. UNIT- 239093-CS-INDV / Procureme nt of Community Engagemen Technical Assistance and Pro Individual Consult Under Implement IDA / 59880 Post Limited 33,000.00 0.00 2021-07-30 2021-09-29 2021-08-04 2021-08-25 2021-09-29 2022-09-29 t Specialist for the North East ject Management Support ant Selection ation Recovery and Stability Progr amme Project Management a nd Coordination Cell NG-MCRP FED COORD. UNIT- 239097-CS-INDV / Procureme nt of M&E Specialist for the N Technical Assistance and Pro Individual Consult Under Implement IDA / 59880 Post Limited 33,000.00 0.00 2021-04-01 2021-05-28 2021-04-06 2021-04-27 2021-06-01 2022-06-01 orth East Recovery and Stabil ject Management Support ant Selection ation ity Programme Project Mana gement and Coordination Cel l Page 4 PROCUREMENT PLAN (Textual Part) Project information: Republic of Congo- Integrated Public Sector Reform Project- P160801 Project Implementation agency: PSTAT Date of the Procurement Plan: March 22, 2017 Period covered by this Procurement Plan: March-December 2017 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in N/A, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. Not Applicable Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables Not Applicable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Specify for each Goods: is not applicable; Works: is not applicable Other Relevant Procurement Information. Not Applicable PROCUREMENT Congo, Republic of : Integrated Public Sector Reform Project PLAN General Information Country: Congo, Republic of 2017-09-05 Bank’s Approval Date of the Original Procurement Plan: 2023-06-07 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P160801 GPN Date: Project Name: Integrated Public Sector Reform Project Loan / Credit No: IDA / V0780, IDA / 60230 PRISP IMPLEMENTATION UNIT Executing Agency(ies): WORKS Activity Reference No. / Procurem Actual A Bid Evaluation Repor Loan / Credit Market Approa Procurement Pr Prequalificatio High SEA/SH Process S Draft Pre-qualificatio Prequalification Eval Draft Bidding Docu Specific Procurement Bidding Documents Proposal Submission Contract Compl Description Component Review Type Method ent Docu mount (U t and Recommendati Signed Contract No. ch ocess n (Y/N) Risk tatus n Documents uation Report ment / Justification Notice / Invitation as Issued / Opening / Minutes etion ment Typ S$) on for Award e Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PRISP-432-DC-T-2022 / Amé nagement et la mise aux no Strengthening Revenue Mo Other (with Request for Quot Single Stage - One Under Impl 2023-04-0 2023-02-0 2023-05-3 2023-11- rmes des salles techniques IDA / 60230 bilization and Public Expen Post Limited field for expl 0.00 ations Envelope ementation 5 8 1 27 des sites administratifs et d diture Management anation) es inspections divisionnaires des impôts GOODS Activity Reference No. / Bid Evaluation Repor Loan / Credit Market Approa Procurement Pr Prequalificatio Actual Amoun Process St Draft Pre-qualificatio Prequalification Eval Draft Bidding Docu Specific Procurement Bidding Documents Proposal Submission Description Component Review Type Method t and Recommendati Signed Contract Contract Completion No. ch ocess n (Y/N) t (US$) atus n Documents uation Report ment / Justification Notice / Invitation as Issued / Opening / Minutes on for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PRISP-008-F-ED-17 / Acquisi Project Implementation Sup 2017-10-3 2017-11-0 2017-11-0 2017-12-0 2017-12-1 2018-02-0 2018-06-0 2018-06-0 IDA / V0780 Prior Direct Selection Direct 28,961.06 Completed tion du logiciel TOM2PRO_ ( port 1 6 5 8 0 2 8 1 TOMATE) PRISP-007-F-DC-17 / Acquisi tion d'un matériel informati Project Implementation Sup Request for Quot Single Stage - One 2017-11-0 2017-10-1 2017-12-3 2017-11-0 2018-06-2 2017-12-0 IDA / V0780 Post Limited 30,547.76 Completed que dédié à la comptabilité port ations Envelope 5 6 1 7 9 7 et installation de TOMPRO PRISP-002/F-DC-18 / Mobilie Project Implementation Sup Request for Quot Single Stage - One 2018-04-1 2018-03-2 2018-06-0 2018-04-1 2018-12-0 2018-04-2 IDA / V0780 Post Limited 24,119.69 Completed r de bureau de l'UCP port ations Envelope 4 9 9 6 6 3 PRISP-005-F-DC-18 / Acquisi Project Implementation Sup Request for Quot Single Stage - One 2018-10-3 2017-10-1 2018-12-2 2017-11-0 2019-06-2 2017-12-1 tion équipements informatiq IDA / 60230 Post Limited 33,992.99 Completed port ations Envelope 0 6 5 7 3 2 ues de l'UCP PRISP-003-F-DC-18 / Acquisi Project Implementation Sup Request for Quot Single Stage - One 2018-09-2 2018-08-2 2018-11-1 2018-09-1 2019-05-1 2018-10-1 tion de deux(2) véhicules 4 IDA / 60230 Post Limited 95,335.95 Completed port ations Envelope 1 0 6 3 5 2 x4 tout terrain PRISP-007-F-DC-18 / Acquisi tion et déploiement du logic Project Implementation Sup Request for Quot Single Stage - One 2018-10-2 2018-12-2 2018-12-1 2019-02-2 2019-06-1 2019-07-3 IDA / 60230 Post Limited 115,454.16 Completed iel de suivi-évaluation y com port ations Envelope 4 8 9 7 7 1 pris matériel de sécurisatio n PRISP-004-F-DC-18 / Acquisi tion équipements informatiq Improving Transparency an Request for Quot Single Stage - One 2019-05-0 2018-12-1 2019-06-3 2019-01-1 2019-12-2 2019-03-3 IDA / 60230 Post Limited 86,712.79 Completed ues aux profit des ECOFIN d d Accountability ations Envelope 5 3 0 9 7 0 u sénat et de l'assemblée PRISP-006-F-DC-18 / Acquisi Project Implementation Sup Request for Quot Single Stage - One 2019-05-0 2018-12-1 2019-06-3 2018-12-2 2019-12-2 2019-01-2 IDA / 60230 Post Limited 24,560.38 Completed tion groupe électrogène de l port ations Envelope 5 3 0 4 7 1 'UCP PRISP-006-F-DC-17 / Achat Project Implementation Sup Request for Quot Single Stage - One 2019-04-0 2018-03-2 2019-05-2 2018-04-2 2019-11-2 2018-04-3 des fournitures de bureau et IDA / V0780 Post Limited 2,800.75 Completed port ations Envelope 3 9 9 3 5 0 des consommables informat iques P-071-AOI-F-18 / Appel d off res international relatif aux t Modernization of the Public Open - Internation Single Stage - One 2019-02-2 2019-10-3 2019-03-0 2020-12-0 2019-04-1 2020-02-1 2019-05-1 2021-06-1 2019-06-2 2021-08-1 2019-12-1 ravaux de raccordement de IDA / 60230 Prior Request for Bids 6,272,478.65 Signed Administration al Envelope 8 0 5 8 6 0 6 5 0 4 7 s centres des impots a trave rs le backbone de fibre opti que PRISP-086-ED-F-18 / Acquisi tion des droits d'utilisation e Project Implementation Sup 2019-01-1 2019-02-0 2019-01-2 2018-12-0 2019-02-2 2019-03-0 2019-08-2 2019-04-1 n réseau du logiciel TOM2 P IDA / 60230 Post Direct Selection Direct 11,589.48 Completed port 5 8 0 3 4 9 3 1 RO et clés d'accès supplém entaire auprès de la Société TOMATE PRISP-107-F-DC-19 / Acquisi Strengthening Revenue Mo Request for Quot Single Stage - One 2019-04-0 2019-05-2 2019-11-2 tion equipements informatiq IDA / 60230 bilization and Public Expen Post Limited 0.00 Canceled ations Envelope 3 9 5 ues et bureautiques au prof diture Management it de la DGPP PRISP-109-F-DAOI-19 / Firm e pour la mise en oeuvre du Modernization of the Public Open - Internation Single Stage - One 2019-04-3 2019-05-0 2019-06-1 2019-07-1 2019-08-2 2020-02-1 IDA / 60230 Prior Request for Bids 0.00 Canceled systeme integre de la gestio Administration al Envelope 0 5 6 6 0 6 n des ressources humaines de l Etat PRISP-101-F-DAO-19 / firme Strengthening Revenue Mo Single Stage - One 2019-04-3 2019-05-0 2019-06-1 2019-07-1 2019-08-2 2020-02-1 pour réparation des infrastr IDA / 60230 bilization and Public Expen Post Request for Bids Open - National 0.00 Canceled Envelope 0 5 6 6 0 6 uctures à Brazzaville diture Management PRISP-116-F-DC-19 / Firme pour le Developpement d u n systeme informatise d opti Project Implementation Sup Request for Quot Open - Internation Single Stage - One 2019-05-0 2019-06-3 2019-06-2 2019-12-2 2019-12-3 IDA / 60230 Post 85,678.94 Completed misation des processus dem port ations al Envelope 5 0 9 7 1 aterialisation et gestion elec tronique des documents au niveau de l UCP PRISP-130-F-DC-19 / Acquisi Modernization of the Public Request for Quot Single Stage - One 2019-07-0 2019-08-2 2020-02-2 tion des equipements pour l IDA / 60230 Post Limited 0.00 Canceled Administration ations Envelope 3 8 4 organisation des formations de l ARMP PRISP-132-F-DC-19 / Acquisi Improving Transparency an Request for Quot Single Stage - One 2019-06-0 2019-07-3 2020-01-2 tion materiels et equipemen IDA / 60230 Post Limited 0.00 Canceled d Accountability ations Envelope 5 1 7 ts informatiques au profit de la CCDB PRISP-134-F-DC-19 / Acquisi Improving Transparency an Request for Quot Single Stage - One 2019-07-0 2019-08-2 2020-02-2 tion equipements informatiq IDA / 60230 Post Limited 0.00 Canceled d Accountability ations Envelope 3 8 4 ues et bureautiques au profi t de l IGF PRISP-139-F-DC-19 / Acquisi Project Implementation Sup Request for Quot Single Stage - One 2019-04-0 2018-04-2 2019-05-2 2019-07-1 2019-11-2 2019-09-2 tion des fournitures de bure IDA / 60230 Post Limited 38,912.13 Completed port ations Envelope 3 4 9 7 5 6 au et materiels informatique s du PRISP PRISP-117-F-DAOI-19 / Acqu isition des fournitures relati ves a la mise en place d'un Improving Transparency an Single Stage - One 2019-06-2 2019-04-0 2019-07-0 2019-08-1 2019-07-1 2019-09-1 2019-07-1 2019-10-1 2019-10-2 2020-04-1 2020-10-0 IDA / 60230 Post Request for Bids Open - National 275,931.97 Completed systeme de gestion electron d Accountability Envelope 8 9 3 4 7 3 9 8 2 5 1 ique des documents pour le s deux commissions ecnomi que et finances du Parlemen t PRISP-140-F-DAOI-19 / Acqu Strengthening Revenue Mo Open - Internation Single Stage - One 2019-12-3 2020-01-0 2020-02-1 2020-03-1 2020-04-2 2020-10-1 isition des infrastructures so IDA / 60230 bilization and Public Expen Post Request for Bids 0.00 Canceled al Envelope 1 5 6 7 1 8 laires a Brazzaville de 100 K diture Management VA PRISP-109-F-DAOI-19 TER / Mise en oeuvre d un system Modernization of the Public Open - Internation Single Stage - Two 2019-05-3 2019-08-1 2019-08-1 2019-06-0 2019-10-2 2020-02-1 2021-08-0 IDA / 60230 Prior Request for Bids 0.00 Canceled e intégré de gestion des res Administration al Envelope 1 6 6 5 5 1 4 sources humaines de l Etat ( SIGRHE) PRISP-109-F-DAOI-19 TER B IS-C-CI-18 / Mise en oeuvre Modernization of the Public Open - Internation Single Stage - One 2019-08-3 2019-09-0 2019-10-1 2019-11-1 2019-12-2 2020-06-1 IDA / 60230 Prior Request for Bids 0.00 Canceled du système de gestion des r Administration al Envelope 0 4 6 5 0 7 essources de l'Etat (SIGRHE) PRISP-156-AON-F-2019 / Ac Improving Transparency an Single Stage - One 2019-07-3 2019-07-1 2019-08-0 2019-09-1 2019-08-2 2019-10-1 2019-09-0 2019-11-2 2019-10-2 2020-05-1 2020-01-0 quisition du matériel inform IDA / 60230 Post Request for Bids Open - National 334,684.00 Completed d Accountability Envelope 1 2 5 6 3 6 7 0 3 8 1 atique au profit de CCDB, IG F, ARMP et DGPP PRISP 174-F-DAOI-19 / Mise à jour du Datacenters et acq Strengthening Revenue Mo Open - Internation Single Stage - One 2019-11-2 2019-11-0 2019-12-0 2021-03-3 2020-01-1 2020-02-1 2020-02-1 2021-04-0 2020-03-2 2021-05-2 2020-09-1 uisition d’un outil de Supervi IDA / 60230 bilization and Public Expen Prior Request for Bids 4,352,695.13 Signed al Envelope 9 4 4 1 5 1 4 8 0 6 6 sion des infrastructures de l diture Management a Fibre optique Inter Admini stration (FIA) à Brazzaville PRISP-143-F-DAOI-19 / Acqu Strengthening Revenue Mo Single Stage - One 2019-12-3 2019-09-3 2020-01-0 2020-02-1 2020-03-1 2020-04-2 2020-10-1 isition et installation d infras IDA / 60230 bilization and Public Expen Post Request for Bids Open - National 0.00 Canceled Envelope 1 0 5 6 7 1 8 tructures solaires de 100 KV diture Management A a Ponte-Noire PRISP-102-F-DAOI-19 / Acqu Strengthening Revenue Mo Open - Internation Single Stage - One 2019-03-2 2019-04-0 2019-05-1 2019-06-1 2019-07-1 2020-01-1 isition et installation infrastr IDA / 60230 bilization and Public Expen Post Request for Bids 0.00 Canceled al Envelope 9 3 5 4 9 5 uctures solaires 100 KVA à diture Management Pointe-Noire PRISP-143 BIS-F-DAOI-19 / Strengthening Revenue Mo Dimensionnement,acquisitio Open - Internation Single Stage - One 2019-12-3 2019-11-0 2020-01-0 2019-11-0 2020-02-1 2021-01-3 2020-03-1 2020-09-1 2020-04-2 2020-12-0 2020-10-1 IDA / 60230 bilization and Public Expen Post Request for Bids 1,251,775.07 Signed n et installation du systeme al Envelope 0 8 4 8 5 1 6 6 0 8 7 diture Management solaire a Brazzaville et a Poi nte-Noire PRISP-180--F-DAON-19 / Im Strengthening Revenue Mo Single Stage - One 2019-12-3 2019-11-2 2020-01-0 2020-02-1 2020-01-0 2020-03-1 2020-02-0 2020-04-2 2020-03-0 2020-10-1 2020-10-0 pression documents PND po IDA / 60230 bilization and Public Expen Post Request for Bids Open - National 158,361.10 Completed Envelope 1 9 5 6 6 7 5 1 5 8 1 ur dissémination diture Management PRISP-142-F-DAOI-19 / Acqu isition des equipements pou Modernization of the Public Single Stage - One 2019-12-3 2020-01-0 2020-02-1 2020-03-1 2020-04-2 2020-10-1 IDA / 60230 Post Request for Bids Open - National 0.00 Canceled r l operationnalisation du sy Administration Envelope 1 5 6 7 1 8 steme d information de l AR MP PRISP-141-F-DAOI-19 / Acqu Strengthening Revenue Mo isition des equipements d e Single Stage - One 2019-12-3 2020-01-0 2020-02-1 2020-03-1 2020-04-2 2020-10-1 IDA / 60230 bilization and Public Expen Post Request for Bids Open - National 0.00 Canceled xtension de la FIA et la remi Envelope 1 5 6 7 1 8 diture Management se aux normes du DATA cen ter de Brazzaville PRISP-144-F-DAOI-19 / Mise ne place d un systeme d inf Modernization of the Public Open - Internation Single Stage - Two 2019-08-2 2019-11-1 2019-11-1 2019-09-0 2020-01-2 2020-05-1 2021-11-0 IDA / 60230 Post Request for Bids 0.00 Canceled ormation pour l autorité de r Administration al Envelope 8 3 3 2 2 0 1 égulation des marchés publi cs (ARMP) PRISP-186-F-CF-2020 / Firm e en charge de la mise en pl Improving Transparency an Request for Quot Single Stage - One 2020-03-0 2020-02-1 2020-04-2 2020-07-2 2020-10-2 2020-12-2 ace d'un systeme de gestio IDA / 60230 Post Limited 168,301.39 Completed d Accountability ations Envelope 4 1 9 1 6 5 n electronique des docume nts de l inspection generale des finances (IGF) Page 1 PRISP-194-F-DC-20 / Mobilie Project Implementation Sup Request for Quot Single Stage - One 2020-04-0 2020-03-0 2020-05-3 2020-05-1 2020-11-2 2020-07-1 r de bureau de la cellule de IDA / 60230 Post Limited 25,249.64 Completed port ations Envelope 5 3 1 2 7 1 suivi des erformes sur la go uvernance PRISP-195-F-DC-20 / Acquisi tion materiel informatique d Project Implementation Sup Request for Quot Single Stage - One 2020-04-0 2020-03-0 2020-05-3 2020-05-1 2020-11-2 2020-09-1 IDA / 60230 Post Limited 54,126.55 Completed e la cellule de suivi des refo port ations Envelope 5 3 1 2 7 6 rmes de gouvernance PRISP-196-F-DC-20 / Acquisi tion groupe électrogène pou Project Implementation Sup Request for Quot Single Stage - One 2020-04-0 2020-03-0 2020-05-3 2020-05-1 2020-11-2 2020-07-2 IDA / 60230 Post Limited 24,645.82 Completed r la cellule de suivi des refor port ations Envelope 5 3 1 2 7 1 mes de la gouvernance PRISP-145-F-DAOI-19 / Acqu Modernization of the Public Open - Internation Single Stage - One 2019-11-2 2019-12-0 2020-01-1 2020-02-1 2020-03-2 2020-09-1 isition des equipements pou IDA / 60230 Prior Request for Bids 0.00 Canceled Administration al Envelope 9 4 5 4 0 6 r la mise en oeuvre du SIGR HE PRISP-226-AON-F-20 / Acqui Strengthening Revenue Mo sition du matériel informatiq Single Stage - One 2020-11-3 2020-10-2 2020-12-0 2021-01-1 2020-11-2 2021-02-1 2020-12-1 2021-03-2 2021-03-1 2021-09-1 2021-04-2 IDA / 60230 bilization and Public Expen Post Request for Bids Open - National 139,061.81 Completed ue et outils informatiques d Envelope 0 0 5 6 7 5 0 2 7 8 8 diture Management u ministère en charge du pl an PRISP-227-AON-F-20 / Acqui sition matériel informatique Modernization of the Public Single Stage - One 2020-10-2 2020-08-2 2020-10-2 2020-12-0 2020-10-3 2021-01-0 2020-12-0 2021-02-1 2021-04-2 2021-08-1 2021-07-1 IDA / 60230 Post Request for Bids Open - National 328,153.03 Signed et câblage réseaux au profit Administration Envelope 3 1 8 9 0 8 4 2 7 1 6 du ministère en charge de l a fonction publique PRISP-235-F-DC-20 / Acquisi Strengthening Revenue Mo Single Stage - One 2020-10-3 2020-11-0 2020-12-1 2021-01-1 2021-02-1 2021-08-1 tion du matériel informatiqu IDA / 60230 bilization and Public Expen Post Request for Bids Open - National 0.00 Canceled Envelope 0 4 6 5 9 8 e du ministère en charge du diture Management plan PRISP-280-CF-F-21 / Acquisi Project Implementation Sup Request for Quot Single Stage - One 2021-11-1 2021-10-1 2022-01-1 2021-10-2 2022-07-0 2021-11-2 tion du véhicule de l'unité d IDA / 60230 Post Limited 51,303.00 Completed port ations Envelope 5 3 0 3 9 9 e coordination du PRISP PRISP-308-CF-F-2022 / Acqu Project Implementation Sup Request for Quot Single Stage - One 2022-07-2 2022-05-2 2022-09-1 2022-06-1 2023-03-1 isition de deux véhicules de IDA / 60230 Post Limited 52,941.00 Signed port ations Envelope 4 4 8 0 7 l'unité de coordination du pr ojet PRISP-306-CF-F-2022 / Acqu isition de 5 ordinateurs de b ureau, 25 ordinateurs porta bles, 54 tablettes, 5 vidéo p Improving Transparency an Request for Quot Single Stage - One 2022-07-2 2022-06-2 2022-09-1 2022-07-0 2023-03-1 2022-07-2 IDA / 60230 Post Limited 110,966.30 Completed rojecteurs, 5 imprimantes m d Accountability ations Envelope 0 1 4 5 3 6 ulti fonction, 5 gros copieurs , 5 appareils de reliure, 5 on duleurs, 5 dictaphones, 5 en ceinte sono portables,30 ant ivirus pour OSC PRISP-309-CF-F-2022 / Acqu isition de 11 ordinateurs por Improving Transparency an Request for Quot Single Stage - One 2022-07-2 2022-05-2 2022-09-1 2022-06-1 2023-03-1 2022-07-0 tables, 11 disques dur exter IDA / 60230 Post Limited 17,508.22 Completed d Accountability ations Envelope 5 4 9 6 8 1 ne, 11 antivirus, 11 sacs des tinés à l'unité de gestion du programme REDD+ PRISP-400-CF-F-2022 / Impr ession quadrichromie sur pa pier couché brillant 120g du Strengthening Revenue Mo document annexe de 66 pa Request for Quot Single Stage - One 2022-08-2 2022-07-0 2022-10-2 2022-07-1 2023-04-2 IDA / 60230 bilization and Public Expen Post Limited 49,458.24 Signed ges en 500 exemplaires et d ations Envelope 7 4 2 3 0 diture Management u document annexe traducti on de 146 pages en 500 exe mplaires du plan national de développement (PND) versi on anglaise PRISP-405-CF-C-22 / Acquisi tion du matériel informatiqu Modernization of the Public Request for Quot Single Stage - One 2022-10-1 2022-08-1 2022-12-1 2023-06-1 IDA / 60230 Post Limited 0.00 Signed e de la CGMP du ministère d Administration ations Envelope 9 6 4 2 e la santé et de la populatio n PRISP-404-CF-F-22 / Acquisi tion des équipements infor Modernization of the Public Request for Quot Single Stage - One 2022-10-1 2022-12-1 2023-06-0 IDA / 60230 Post Limited 0.00 Canceled matiques du ministère en ch Administration ations Envelope 5 0 8 arge du contrôle d'Etat PRISP-410-AON-F-2022 / Ac quisition des équipements i Strengthening Revenue Mo nformatiques au profit de la Single Stage - One Under Imple 2022-11-3 2022-10-2 2022-12-0 2023-02-0 2023-01-1 2022-11-2 2023-02-1 2023-03-2 2023-09-1 IDA / 60230 bilization and Public Expen Post Request for Bids Open - National 0.00 direction départementale de Envelope mentation 0 0 5 7 6 9 5 2 8 diture Management s douanes du Kouilou, du mi nistère en charge du contrôl e d'Etat et du SIVL PRISP-426-DC-F-2022 / Acq uisition de 161 tablettes, 5 Modernization of the Public Request for Quot Single Stage - One 2023-01-0 2022-10-1 2023-03-0 2023-08-2 ordinateurs portables et de IDA / 60230 Post Limited 0.00 Signed Administration ations Envelope 4 3 1 8 48 imprimantes pour l'enrôl ement biométrique des age nts de la fonction publique PRISP-429-DC-F-22 / Acquisi tion de 10 ordinateurs porta bles pour le projet numéro d 'identification unique (NIU) Modernization of the Public Request for Quot Single Stage - One 2023-01-0 2022-11-0 2023-03-0 2023-08-2 IDA / 60230 Post Limited 0.00 Signed dans le cadre de l'opération Administration ations Envelope 4 4 1 8 d'enrôlement biométrique d es agents civils de l'Etat, de s enseignants volontaires et communautaires PRISP-430-DC-F-2022 / Acq uisition de 40 ordinateurs co mplémentaires pour le proje t numéro d'identification uni Modernization of the Public Request for Quot Single Stage - One 2022-12-2 2022-11-2 2023-02-1 2023-08-1 IDA / 60230 Post Limited 0.00 Signed que (NIU) dans le cadre de l' Administration ations Envelope 5 9 9 8 opération d'enrôlement bio métrique des agents civils d e l'Etat, des enseignants vol ontaires et communautaires PRISP-431-DC-F-2022 / Acq Strengthening Revenue Mo uisition et installation d’un r Request for Quot Single Stage - One 2023-03-0 2023-01-2 2023-04-3 2023-10-2 IDA / 60230 bilization and Public Expen Post Limited 0.00 Signed égulateur plus puissant de p ations Envelope 5 5 0 7 diture Management rès de 630 KVA pour la sécu rité des appareils PRISP-434-DC-F-2022 / Acq uisition des Backgrounds po Modernization of the Public Request for Quot Single Stage - One 2023-03-0 2022-12-0 2023-04-3 2023-10-2 ur l'enrôlement biométrique IDA / 60230 Post Limited 0.00 Signed Administration ations Envelope 5 5 0 7 des agents civils de l'Etat et des enseignants volontaires PRISP-453-F-ED-2023 / Acq uisition d'un Véhicule destin Modernization of the Public Pending Imp 2023-05-0 2023-05-0 2023-06-1 2023-12-0 é à L’unité de gestion du pr IDA / 60230 Post Direct Selection Direct - National 0.00 Administration lementation 2 7 1 8 ogramme de réduction des émissions de Sangha-Likoua la PRISP-471-F-ED-2023 / acq uisition des consommables de bureau pour la deuxième Modernization of the Public Pending Imp 2023-04-0 2023-04-0 2023-05-1 2023-11-0 phase de l’opération d’enrôl IDA / 60230 Post Direct Selection Direct - National 0.00 Administration lementation 3 8 3 9 ement biométrique des age nts civils de l’état, des ensei gnants volontaires et comm unautaires du MEPPPSA. PRISP-472-F-ED-2023 / Acq uisition des fiches pour pour la deuxième phase de l’opér Modernization of the Public Pending Imp 2023-04-0 2023-04-0 2023-05-1 2023-11-0 IDA / 60230 Post Direct Selection Direct - National 0.00 ation d’enrôlement biométri Administration lementation 3 8 3 9 que des agents civils de l’Ét at, des enseignants volontai res et communautaires du MEPPPSA PRISP-411-CF-F-2022 / Acqu Strengthening Revenue Mo Single Stage - One 2022-12-2 2022-11-0 2023-01-0 2023-02-1 2023-03-1 2023-04-2 2023-10-1 isition de quinze (15) véhicu IDA / 60230 bilization and Public Expen Post Request for Bids Open - National 0.00 Canceled Envelope 9 4 3 4 6 0 7 les tout terrain diture Management PRISP-473-F-DC-23 / Acquisi Improving Transparency an Request for Quot Single Stage - One Pending Imp 2023-08-2 2023-10-2 2024-04-2 IDA / 60230 Post Limited 0.00 tion de quinze véhicules d Accountability ations Envelope lementation 8 3 0 PRISP-474-F-CD-23 / Acquisi tion des consommables de Modernization of the Public Request for Quot Single Stage - One Pending Imp 2023-08-2 2023-10-2 2024-04-1 bureau pour l’opération d’e IDA / 60230 Post Limited 0.00 Administration ations Envelope lementation 7 2 9 nrôlement biométrique des contribuables recensés à Br azzaville et Pointe-Noire PRISP-475-F-CD-23 / Acquisi tion du matériel informatiqu Modernization of the Public Request for Quot Single Stage - One Pending Imp 2023-09-0 2023-10-3 2024-04-2 e pour l’opération d’enrôlem IDA / 60230 Post Limited 0.00 Administration ations Envelope lementation 5 1 8 ent biométrique des contrib uables recensés à Brazzavill e et Pointe-Noire PRISP-477-F-CD-23 / Impres sion des rapports de suivi b Modernization of the Public Request for Quot Single Stage - One Pending Imp 2023-08-2 2023-10-2 2024-04-2 udgétaire pour leur dissémi IDA / 60230 Post Limited 0.00 Administration ations Envelope lementation 9 4 1 nation dans les 12 départe ments de la République du Congo PRISP-484-F-CF-2023 / Acqu isition et installation du mat Strengthening Revenue Mo Request for Quot Single Stage - One Pending Imp 2023-08-0 2023-10-0 2024-04-0 ériel anti-incendie destiné a IDA / 60230 bilization and Public Expen Post Limited 0.00 ations Envelope lementation 9 4 1 u site du ministère en charg diture Management e des finances abritant le sy stème solaire PRISP-476 BIS -F-CD-23 / Ac quisition des équipements i Modernization of the Public Request for Quot Single Stage - One Pending Imp 2023-08-2 2023-10-2 2024-04-2 IDA / 60230 Post Limited 0.00 nformatiques au profit de la Administration ations Envelope lementation 8 3 0 cour des comptes et de disc ipline budgétaire (CCDB) NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Repor Loan / Credit Market Approa Procurement Pr Prequalificatio Actual Amoun Process St Draft Pre-qualificatio Prequalification Eval Draft Bidding Docu Specific Procurement Bidding Documents Proposal Submission Description Component Review Type Method t and Recommendati Signed Contract Contract Completion No. ch ocess n (Y/N) t (US$) atus n Documents uation Report ment / Justification Notice / Invitation as Issued / Opening / Minutes on for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PRISP-61-C-SC-18 / Service Project Implementation Sup Request for Quot Single Stage - One 2018-10-3 2018-09-2 2018-12-2 2018-09-2 2019-06-2 2018-10-1 IDA / 60230 Post Limited 4,841.57 Completed d'assurance véhicule port ations Envelope 0 4 5 7 3 6 PRISP-62-SC-ED-18 / Install Project Implementation Sup 2018-09-2 2018-09-2 2018-10-3 2019-04-2 IDA / 60230 Post Direct Selection Direct 0.00 Canceled ation et déploiement interne port 0 5 0 8 t PRISP-63-S-SC-18 / Entretie Project Implementation Sup Request for Quot Single Stage - One 2018-09-2 2018-11-2 2019-05-1 IDA / 60230 Post Limited 0.00 Canceled n groupe électrogène de l'U port ations Envelope 5 0 9 CP PRISP-59-C-SC-18 / Locatio Project Implementation Sup Request for Quot Single Stage - One 2019-02-0 2019-04-0 2019-09-2 IDA / 60230 Post Limited 0.00 Canceled n siège PRISP port ations Envelope 5 2 9 Page 2 PRISP-58-C-SC-18 / Service Project Implementation Sup Request for Quot Single Stage - One 2019-02-0 2018-11-2 2019-04-0 2018-12-1 2019-09-2 IDA / 60230 Post Limited 13,349.92 Signed de gardiennage port ations Envelope 5 3 2 3 9 PRISP-60-C-SC-18 / Service Project Implementation Sup Request for Quot Single Stage - One 2019-02-0 2018-11-2 2019-04-0 2018-12-1 2019-09-2 IDA / 60230 Post Limited 7,028.16 Signed d'entretien siège port ations Envelope 5 3 2 1 9 PRISP-254-SC-2020 / Renou Project Implementation Sup 2020-12-2 2020-12-0 2020-12-2 2020-12-0 2021-02-0 2020-12-1 2021-08-0 vellement du contrat d entr IDA / 60230 Post Direct Selection Direct 7,707.38 Signed port 4 7 9 7 2 1 1 etien des locaux du PRISP PRISP-255-SC-2020 / Renou Project Implementation Sup 2020-12-2 2020-12-0 2020-12-2 2020-12-0 2021-02-0 2020-12-1 2021-07-3 vellement du contrat du gar IDA / 60230 Post Direct Selection Direct 14,369.78 Signed port 3 7 8 7 1 1 1 diennage des locaux du PRI SP CONSULTING FIRMS Activity Reference No. / Short List and Draft Combined Evaluatio Loan / Credit Market Approa Contract Type Actual Amount Process Statu Expression of Interes Request for Proposal Opening of Technical Evaluation of Techni Description Component Review Type Method Terms of Reference Request for Proposal n Report and Draft N Signed Contract Contract Completion No. ch (US$) s t Notice s as Issued Proposals / Minutes cal Proposal s egotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PRISP-013-C-SC-17 / Sélecti on d'une firme sélection pou Improving Transparency an Quality And Cost- Open - Internation 2017-11-2 2018-01-0 2018-02-0 2018-03-0 2018-04-0 2018-05-1 2019-05-1 IDA / V0780 Prior 0.00 Canceled 2017-10-31 r la mise en place d'un systè d Accountability Based Selection al 1 4 1 3 7 2 2 me d'information et de gesti on des marchés publics PRISP-011-C-SC-17 / Sélecti on d'une firme international Improving Transparency an Quality And Cost- Open - Internation 2018-03-2 2018-04-1 2018-03-2 2018-05-3 2018-09-0 2018-06-2 2018-10-0 2018-07-2 2018-10-1 2018-08-3 2019-01-1 2018-10-0 2019-01-3 2019-10-0 pour l'élaboration du plan d' IDA / V0780 Post 351,790.17 Signed 2018-03-26 d Accountability Based Selection al 8 6 8 0 3 7 2 7 2 1 6 5 1 5 action stratégique pour la ré forme des finances publique s PRISP-25-C-18 / firme en ch arge de la conduite de l'audi Improving Transparency an Quality And Cost- Open - Internation 2018-12-1 2018-08-1 2019-04-2 2018-09-2 2018-10-2 2018-11-2 2018-12-2 2019-02-0 2020-02-0 IDA / V0780 Post 0.00 Canceled 2018-07-24 t indépendant des marchés d Accountability Based Selection al 1 4 4 7 5 4 9 2 2 publics pour l'exercice 2017 PRISP-27-C-18 / Recruteme nt d'un cabinet spécialisé en système d'information char Modernization of the Public Quality And Cost- Open - Internation Under Implemen 2018-06-0 2018-07-1 2018-06-1 2018-08-2 2018-08-0 2018-09-2 2018-09-2 2018-10-2 2018-12-0 2018-11-3 2019-01-0 2020-01-0 gé de la modernisation du s IDA / 60230 Prior 0.00 2018-06-25 Administration Based Selection al tation 6 6 1 9 6 6 1 6 6 0 4 4 ystème de gestion des impô ts du ministère des finances et du budget de la Républiq ue du Congo PRISP-34-C-18 / Recruteme nt d'une firme en charge de Modernization of the Public Consultant Qualif Open - Internation 2018-08-1 2018-09-2 2018-10-2 2018-12-0 2019-05-3 IDA / 60230 Post 0.00 Canceled 2018-07-25 l'audit independant des mar Administration ication Selection al 5 8 8 2 1 ches publics pour l'exercice 2017 PRISP-36-C-SFQC-18 / Recr utement d'un firme internati Strengthening Revenue Mo Quality And Cost- Open - Internation 2018-09-2 2018-11-0 2018-12-0 2019-01-0 2019-02-0 2019-03-1 2020-03-1 onal pour l'élaboration du Pl IDA / 60230 bilization and Public Expen Post 0.00 Canceled 2018-08-31 Based Selection al 1 4 2 1 5 2 1 an d'action stratégique pour diture Management la réforme des Finances Pub liques PRISP-37-C-SQC-18 / Recrut ement d' un Cabinet intern Improving Transparency an Consultant Qualif Open - Internation 2018-08-0 2018-09-2 2018-11-0 2018-10-1 2018-12-0 2018-11-2 2019-01-0 2018-11-2 2019-07-0 IDA / 60230 Post 345,098.77 Signed 2018-08-30 ational en charge de l'élabor d Accountability ication Selection al 8 0 3 9 3 3 7 7 6 ation des rapports ITIE exer cices 2016 et 2017 PRISP-52-C-SFQC-18 / Firme Strengthening Revenue Mo Quality And Cost- Open - Internation 2018-11-2 2019-01-0 2019-01-3 2019-03-0 2019-04-0 2019-05-1 2020-05-1 pour la réparation des infras IDA / 60230 bilization and Public Expen Post 0.00 Canceled 2018-10-30 Based Selection al 0 3 1 2 6 1 0 tructures à BZV diture Management PRISP-033-C-CI-17 / Sélecti Strengthening Revenue Mo on d'une firme pour l'Analys Consultant Qualif Open - Internation 2018-02-2 2018-04-0 2018-05-0 2018-06-1 2018-12-0 IDA / 60230 bilization and Public Expen Post 0.00 Canceled 2018-01-31 e diagnostic de la chaîne de ication Selection al 1 6 6 0 7 diture Management planification et gestion des i nvestissements publics PRISP-030-C-CI-17 / Sélecti on d'une firme pour le Dével Modernization of the Public Consultant Qualif Open - Internation 2018-02-1 2018-03-3 2018-04-3 2018-06-0 2018-12-0 IDA / V0780 Post 0.00 Canceled 2018-01-25 oppement du Plan stratégiq Administration ication Selection al 5 1 0 4 1 ue de la réforme de l'Etat PRISP-032-C-CI-17 / Sélecti on d'une firme pour l'Analys Modernization of the Public Consultant Qualif Open - Internation 2018-02-1 2018-03-2 2018-04-2 2018-06-0 2018-11-2 e diagnostique de la gestion IDA / V0780 Post 0.00 Canceled 2018-01-22 Administration ication Selection al 2 8 7 1 8 de la fonction publique: Aud it institutionnel de la MFPRE PRISP-015-C-SC-17 / Recrut Project Implementation Sup Quality And Cost- Open - Internation 2017-09-1 2017-11-1 2017-12-2 2018-11-2 2018-01-2 2018-02-2 2018-03-2 2018-05-0 2019-05-0 ement d'un cabinet d'audit f IDA / V0780 Prior 0.00 Canceled 2017-10-22 port Based Selection al 5 2 6 2 3 2 9 3 3 inancier externe ( pour le PP A et deux exercices) PRISP-109 BIS-C-SFQC-19 / Firme pour la mise en oeuvr Modernization of the Public Quality And Cost- Open - Internation 2019-02-2 2019-03-2 2019-05-0 2019-06-0 2019-07-0 2019-08-0 2019-09-0 2020-09-0 IDA / 60230 Prior 0.00 Canceled 2019-02-28 e du système intégré de ges Administration Based Selection al 0 1 4 1 1 5 9 8 tion des ressources humain es de l'état (SIGRHE) PRISP-138-C-CI-19 / Firme p Improving Transparency an Quality And Cost- Open - Internation 2019-12-2 2020-02-0 2020-03-0 2020-03-3 2020-05-0 2020-06-0 2021-06-0 our la production des rappor IDA / 60230 Post 0.00 Canceled 2019-11-29 d Accountability Based Selection al 0 2 1 1 5 9 9 ts trimestriels de l ITIE PRISP-015-C-SFQC-18 BIS / Recrutement d'un cabinet d' Project Implementation Sup Quality And Cost- Open - Internation 2017-09-1 2019-07-1 2019-09-0 2018-09-2 2019-09-2 2018-10-3 2019-10-2 2018-12-2 2019-12-0 2019-01-1 2020-01-0 2019-01-2 2021-01-0 2020-08-0 IDA / 60230 Post 33,695.10 Completed 2019-06-28 audit externe des comptes port Based Selection al 5 9 1 8 9 1 9 6 3 1 7 6 6 1 exercices 2017, 2018 et 201 9 du PRISP PRISP-37-C-SFQC-18 BIS / R ecrutement d'un cabinet en Improving Transparency an Consultant Qualif 2018-09-2 2018-11-2 2018-12-2 2019-06-2 IDA / 60230 Post Limited 0.00 Canceled 2018-09-06 charge de l'élaboration des d Accountability ication Selection 0 3 8 6 rapports ITIE des exercices 2016 et 2017 P-109-QTO-C-SFQ-19 / Firm e pour pour la mise en oeuv Modernization of the Public Quality Based Sel Open - Internation 2019-08-1 2019-10-2 2019-09-1 2019-12-0 2019-12-3 2020-01-0 2020-03-1 2020-01-3 2020-08-1 2020-03-0 2020-04-0 2021-04-0 IDA / 60230 Prior 0.00 Canceled 2019-09-30 re du systeme integre de ge Administration ection al 3 1 8 4 0 1 3 1 8 1 5 5 stion des ressources humain es de l Etat (SIGRHE) PRISP-110-C-SQC-19 / Firm e en charge de la revue du c Modernization of the Public Quality And Cost- Open - Internation 2019-08-2 2019-04-1 2019-08-2 2019-06-0 2019-10-0 2019-06-3 2019-07-3 2019-09-0 2019-10-0 2020-10-0 IDA / 60230 Post 0.00 Canceled 2019-03-29 adre legal reglementaire et i Administration Based Selection al 1 9 8 2 8 0 0 3 8 7 nstitutionnel de la fonction publique PRISP-110 BIS-C-SQC-19 / R ecrutement d'une firme cha Modernization of the Public Consultant Qualif Open - Internation 2019-08-2 2016-01-0 2016-02-1 2019-10-0 2016-03-1 2019-10-2 2016-04-2 2019-10-2 2016-10-2 rgée de l'élaboration de la r IDA / 60230 Post 341,033.80 Signed 2015-12-15 Administration ication Selection al 1 5 8 8 9 5 3 6 0 evue du cadre légal et régle mentaire de la fonction publ ique PRISP-197-C-SFQC-20 / Fir me pour la mise en oeuvre Modernization of the Public Quality And Cost- Open - Internation 2020-08-2 2020-10-0 2020-09-1 2020-11-1 2021-03-0 2020-12-1 2021-04-2 2021-01-1 2021-09-3 2021-02-1 2021-12-1 2021-03-2 2021-12-2 2022-03-2 IDA / 60230 Prior 581,780.00 Signed 2020-09-10 du système de gestion des r Administration Based Selection al 5 1 0 4 9 2 9 1 0 5 3 2 4 2 essources humaines de l' Et at (SIGRHE) PRISP-224-C-SQC-20 / Recr utement d’une firme chargé e de la formation sur le man Modernization of the Public Consultant Qualif 2020-10-1 2020-11-0 2020-09-0 2020-12-0 2020-12-2 2021-01-0 2021-01-2 2021-07-0 2021-06-0 agement et le leadership p IDA / 60230 Post Limited 25,183.61 Completed 2020-10-20 Administration ication Selection 9 3 3 3 1 7 6 6 2 our les cadres et agents de l a direction des systèmes d’i nformation du ministère en charge de la fonction publiq ue PRISP-231-C-SFQC-20 / Fir me chargée de l'audit exter Project Implementation Sup Quality And Cost- Open - Internation 2020-10-1 2021-01-0 2020-11-2 2021-02-2 2021-02-0 2021-03-2 2021-02-2 2021-04-2 2021-03-0 2021-05-2 2021-03-2 2021-06-2 2021-04-2 2022-06-2 IDA / 60230 Post 18,415.80 Signed 2020-12-18 ne des comptes du PRISP de port Based Selection al 9 8 3 1 1 1 6 0 6 5 6 9 2 9 s exercices 2020, 2021 et cl ôture PRISP-223-C-SQC-20 / Recr utement d’une firme chargé e de la formation sur la bure Modernization of the Public Consultant Qualif 2020-10-1 2020-11-0 2020-12-0 2021-01-0 2021-07-0 IDA / 60230 Post Limited 0.00 Canceled 2020-10-20 autique : Word, Excel et po Administration ication Selection 9 3 3 7 6 werpoint, pour les agents et cadres du cabinet du minist re en charge de la fonction publique PRISP-225-C-SQC-20 / Recr utement d’une firme chargé e de la formation en gestion Modernization of the Public Consultant Qualif 2020-10-2 2020-11-1 2020-12-1 2021-01-1 2021-07-1 des projets informatiques p IDA / 60230 Post Limited 0.00 Canceled 2020-10-30 Administration ication Selection 0 3 3 7 6 our les cadres et agents de l a direction des systèmes d’i nformation du ministère en charge de la fonction publiq ue PRISP-276-C-SQC-2021 / Re crutement d'un cabinet char Modernization of the Public Consultant Qualif Open - Internation 2021-09-0 2021-11-1 2021-10-0 2022-01-0 2021-10-2 2022-02-0 2021-11-2 2022-03-0 2021-12-1 2022-09-0 gé la mise en œuvre du régi IDA / 60230 Post 512,473.20 Signed 2021-10-29 Administration ication Selection al 7 9 4 2 9 1 2 8 1 4 stre de la fonction publique (avec contribution du NIU) PRISP-427-C-SFQC-2022 / R ecrutement d'un cabinet po Project Implementation Sup Quality And Cost- Open - Internation Under Implemen 2022-11-1 2023-01-2 2023-01-0 2023-03-0 2023-04-0 2023-05-0 2023-06-0 2023-07-1 2024-07-1 IDA / 60230 Post 0.00 2022-12-30 ur l'audit externe des compt port Based Selection al tation 8 0 5 5 2 2 6 1 0 es du PRISP des exercices 2 022 et clôture INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit Market Approa Actual Amount Process Statu Invitation to Identifie Draft Negotiated Con Component Review Type Method Contract Type Teams of Reference Signed Contract Contract Completion Description No. ch (US$) s d/Selected Consultan tract Planned Actual Planned t Actual Planned Actual Planned Actual Planned Actual PRISP-001-C-CI-17 / Recrute Project Implementation Sup Individual Consul 2017-09-0 2017-07-1 2017-12-0 2017-07-3 2018-02-0 2017-09-0 2018-02-1 2018-03-0 2019-02-1 ment d'un Coordonnateur p IDA / V0780 Prior Open 57,088.20 Completed 2017-05-22 port tant Selection 6 0 8 1 7 4 5 3 8 our l'Unité de Coordination du Projet PRISP-002-C-CI-17 / Recrute Project Implementation Sup Individual Consul 2017-09-0 2017-07-1 2017-11-1 2017-07-3 2018-03-0 2017-09-0 2018-03-0 2018-03-0 2019-03-0 ment du Spécialiste en Suivi IDA / V0780 Prior Open 45,019.44 Completed 2017-05-22 port tant Selection 6 0 6 1 2 4 2 3 4 évaluation du projet PRISP-003-C-CI-17 / Recrute Project Implementation Sup Individual Consul 2017-09-1 2017-07-1 2017-12-0 2017-07-3 2018-02-2 2017-09-0 2018-03-0 2018-03-0 2019-03-0 ment du Spécialiste en Pass IDA / V0780 Prior Open 40,858.34 Completed 2017-05-22 port tant Selection 1 0 8 1 6 4 6 3 6 ation des Marchés PRISP-004-C-CI-17 / Recrute Project Implementation Sup Individual Consul 2017-09-0 2017-07-1 2017-11-1 2017-07-3 2018-02-0 2017-09-0 2018-02-1 2018-03-0 2019-02-1 ment du Responsable Admi IDA / V0780 Prior Open 40,911.05 Completed 2017-05-22 port tant Selection 6 0 6 1 7 4 5 3 9 nistratif , Financier et Compt able (RAFC) Page 3 PRISP-005-C-CI-17 / Recrute ment d'un consultant individ Project Implementation Sup Individual Consul 2017-09-0 2017-07-1 2017-07-3 2017-09-0 2018-03-0 IDA / V0780 Post Open 0.00 Canceled 2017-05-22 uel pour l'élaboration du ma port tant Selection 5 0 1 4 3 nuel de procédures PRISP-009-C-CI-17 / Recrute Project Implementation Sup Individual Consul 2017-09-0 2017-10-3 2017-09-2 2017-11-2 2017-11-0 2017-12-2 2017-11-0 2018-06-2 2018-06-1 ment d'un consultant individ IDA / V0780 Post Open 29,970.00 Completed 2017-09-12 port tant Selection 8 1 0 1 7 6 8 4 1 uel pour l'élaboration du ma nuel d'exécution PRISP-010-C-CI-17 / Recrute ment d'un consultant individ uel de l'étude de faisabilité Modernization of the Public Individual Consul 2017-09-1 2017-11-0 2018-06-2 2017-11-2 2018-08-1 2017-12-3 2018-08-2 2018-06-2 2018-11-2 IDA / V0780 Post Open 32,150.74 Completed 2017-09-17 pour la mise en place d'un s Administration tant Selection 2 5 2 6 7 1 0 9 0 ystème de Gestion Électroni que des Documents. ( pour l e parlement) PRISP-012-C-CI-17 / Recrute Improving Transparency an Individual Consul 2017-12-1 2018-01-0 2018-06-2 2018-01-2 2018-08-2 2018-03-0 2018-08-2 2018-08-3 2019-06-3 ment d'un consultant individ IDA / V0780 Post Open 72,189.00 Completed 2017-11-19 d Accountability tant Selection 6 7 6 8 1 4 2 1 0 uel pour l'Audit fiscal du sec teur forestier PRISP-014-C-CI-17 / Recrute Project Implementation Sup Individual Consul 2017-09-1 2017-12-1 2018-06-2 2017-12-3 2018-07-3 2018-02-0 2018-07-0 2018-08-0 2019-07-0 ment d'un Auditeur Interne IDA / V0780 Prior Open 48,000.00 Completed 2017-10-22 port tant Selection 5 0 5 1 0 4 4 3 8 ua sein de l'UCP PRISP PRISP-016-C-CI-17 / Recrute ment d'un consultant individ Improving Transparency an Individual Consul 2017-12-1 2017-12-1 2018-06-2 2018-01-0 2018-08-2 2018-02-1 2018-08-2 2018-08-1 IDA / V0780 Post Open 40,211.00 Signed 2017-10-31 uel international chargé de l d Accountability tant Selection 6 9 5 9 4 3 8 2 'élaboration du plan stratégi que PRISP-017-C-CI-17 / Recrute ment d'un consultant individ Improving Transparency an Individual Consul 2017-12-1 2018-01-1 2018-07-1 2018-02-0 2018-08-2 2018-03-1 2018-08-2 2018-09-1 2019-04-1 IDA / V0780 Post Open 39,864.65 Completed 2017-11-30 uel pour l'analyse diagnostic d Accountability tant Selection 5 8 0 8 1 5 1 1 5 sur la mobilisation des impô ts fonciers PRISP-018-C-CI-17 / Recrute ment d'un consultant individ Improving Transparency an Individual Consul 2017-12-1 2017-12-1 2018-06-2 2018-01-0 2018-08-1 2018-02-1 2018-08-2 2018-08-1 2019-03-3 uel pour la mise en place d' IDA / V0780 Post Open 87,321.31 Completed 2017-10-30 d Accountability tant Selection 6 8 2 8 7 2 2 1 0 un système d'information et de gestion des marchés pub lics PRISP-019-C-CI-17 / Recrute ment d'un consultant individ Improving Transparency an Individual Consul 2017-09-2 2017-12-1 2017-10-1 2018-01-0 2017-11-0 2018-02-1 2017-11-0 2018-08-1 IDA / V0780 Post Open 41,343.62 Under Review 2017-10-31 uel international pour élabor d Accountability tant Selection 0 9 7 9 2 3 3 2 ation du plan de formation PRISP-021-C-CI-17 / Recrute ment d'un consultant individ uel international au titre t'a Improving Transparency an Individual Consul 2017-12-1 2017-12-1 2018-01-0 2018-02-0 2018-08-0 IDA / V0780 Post Open 0.00 Canceled 2017-10-25 ppui au Directeur Général d d Accountability tant Selection 5 3 3 7 6 e la Comptabilité dans le ca dre de pilotage de la reform e des Finances Publiques PRISP-022-C-CI-17 / Recrute ment d'un consultant individ uel international pour le dév Modernization of the Public Individual Consul 2017-12-1 2017-12-1 2018-07-1 2018-01-0 2018-08-3 2018-02-0 2018-09-0 2018-08-0 2019-03-1 IDA / V0780 Post Open 31,651.00 Completed 2017-10-26 eloppement d'un plan de for Administration tant Selection 5 4 6 4 1 8 3 7 4 mation pour les institutions de contrôle : Commissions Finances du Parlement. PRISP-023-C-CI-17 / Recrute ment d'un consultant individ Modernization of the Public Individual Consul 2017-12-1 2017-12-1 2018-01-0 2018-10-2 2018-02-1 2018-11-0 2018-08-1 2019-02-0 uel international pour le dév IDA / V0780 Post Open 36,436.00 Completed 2017-10-31 Administration tant Selection 6 9 9 5 3 2 2 8 eloppement d'un plan de for mation pour les institutions de contrôle : IGF PRISP-025-C-CI-17 / Recrute Improving Transparency an Individual Consul 2018-03-2 2018-04-1 2018-05-1 2018-11-1 ment d'un consultant individ IDA / V0780 Post Open 0.00 Canceled 2018-01-31 d Accountability tant Selection 1 1 6 2 uel pour la revue de la polit ique fiscale PRISP-026-C-CI-17 / Recrute ment d'un consultant individ Improving Transparency an Individual Consul 2017-12-1 2018-03-1 2018-06-2 2018-04-0 2018-08-2 2018-05-0 2018-08-2 2018-11-0 2018-12-1 IDA / V0780 Post Open 23,090.00 Completed 2018-01-24 uel pour l'Identification et Él d Accountability tant Selection 6 4 6 4 0 9 2 5 3 aboration de formation pour le Ministère du plan PRISP-027-C-CI-17 / Recrute ment d'un consultant individ Improving Transparency an Individual Consul 2018-03-2 2018-03-1 2018-04-0 2018-05-1 2018-11-0 IDA / V0780 Post Open 0.00 Canceled 2018-01-25 uel pour le développement d Accountability tant Selection 8 5 5 0 6 de programme de formation pour la DGI PRISP-028-C-CI-17 / Recrute ment d'un consultant individ Modernization of the Public Individual Consul 2018-03-1 2018-04-0 2018-08-2 2018-05-0 2018-08-2 2018-11-0 2019-01-1 uel de l'étude de faisabilité IDA / V0780 Post Open 52,811.34 Completed 2018-01-24 Administration tant Selection 4 4 2 9 8 5 5 pour la mise en oeuvre du fi chier unique de la fonction p ublique. PRISP-029-C-CI-17 / Recrute ment d'un consultant individ Modernization of the Public Individual Consul 2018-03-2 2018-03-2 2018-06-2 2018-04-1 2018-06-1 2018-05-1 2018-08-2 2018-11-1 2019-12-3 IDA / V0780 Post Open 65,483.36 Completed 2018-01-30 uel pour l'élaboration du bil Administration tant Selection 8 0 2 0 9 5 2 1 1 an de compétences pour le MFPRE PRISP-020-C-CI-17 / Recrute ment d'un consultant individ Improving Transparency an Individual Consul 2017-12-1 2018-01-0 2018-02-1 2018-08-1 IDA / V0780 Post Open 0.00 Canceled 2017-10-31 uel international pour l'Assis d Accountability tant Selection 9 9 3 2 tance technique à la revue du système informatique PRISP-024-C-CI-17 / Recrute ment d'un consultant individ Modernization of the Public Individual Consul 2017-12-0 2018-04-1 2018-03-2 2018-05-0 2018-03-2 2018-06-1 2018-03-3 2018-12-1 2018-05-0 IDA / V0780 Post Open 22,219.00 Completed 2018-02-28 uel international pour l'etud Administration tant Selection 9 8 7 9 9 3 1 0 4 e sur l'interconnexion entre les centres des impôts PRISP-01-C-CI-18 / Recrute Project Implementation Sup Individual Consul 2018-03-0 2018-05-1 2018-04-2 2018-06-0 2018-04-2 2018-07-0 2018-05-1 2019-01-0 2019-05-1 IDA / V0780 Post Open 29,778.34 Completed 2018-03-26 ment du Comptable au sein port tant Selection 8 4 4 4 6 9 5 5 4 du PRISP PRISP-11-C-CI-18 / Consulta Improving Transparency an Individual Consul 2018-05-0 2018-05-2 2017-09-2 2018-06-3 2017-09-2 2018-12-2 2017-11-0 nt national expert en straté IDA / V0780 Post Limited 9,968.00 Completed 2018-04-30 d Accountability tant Selection 5 6 8 0 8 7 9 gie sectorielle_ (Gouvernan ce) PRISP-13-C-CI-18 / Régulari sation dans STEP Consultant Improving Transparency an Individual Consul 2017-08-0 2017-08-2 2017-08-1 2017-10-0 2017-08-2 2018-03-3 2017-10-2 IDA / V0780 Post Limited 59,200.00 Completed 2017-08-02 international_ Expert sectori d Accountability tant Selection 7 8 4 2 9 1 9 el Hydorcabure et mines PRISP-15-C-CI-18 / Régulari sation dans STEP Consultant Improving Transparency an Individual Consul 2017-08-0 2017-08-2 2017-08-1 2017-10-0 2017-08-2 2018-03-3 2017-11-1 IDA / V0780 Post Limited 53,250.00 Completed 2017-08-02 international_ Expert sectori d Accountability tant Selection 7 8 4 2 9 1 0 el Gouvernance Économiqu e PRISP-14-C-CI-18 / Régulari sation dans STEP Consultant Improving Transparency an Individual Consul 2017-08-0 2017-08-2 2017-08-1 2017-10-0 2017-08-2 2018-03-3 2017-11-1 IDA / V0780 Post Limited 59,200.00 Completed 2017-08-02 international_ Expert sectori d Accountability tant Selection 7 8 4 2 9 1 0 el Ressources Humaines PRISP-16-C-CI-18 / Régulari sation dans STEP Consultant Improving Transparency an Individual Consul 2017-08-0 2017-08-2 2017-08-1 2017-10-0 2017-08-2 2018-03-3 2017-11-0 IDA / V0780 Post Limited 59,200.00 Completed 2017-08-02 international_ Expert sectori d Accountability tant Selection 7 8 4 2 9 1 9 el Gouvernance administrati ve PRISP-18-C-CI-18 / Régulari Improving Transparency an Individual Consul 2017-10-0 2017-10-2 2017-09-2 2017-11-2 2017-09-2 2018-05-2 2017-12-2 sation dans STEP Consultant IDA / V0780 Post Limited 8,663.69 Completed 2017-09-27 d Accountability tant Selection 2 3 9 7 9 6 9 national_cadrage macroéco nomique PRISP-19-C-CI-18 / Régulari sation dans STEP Consultant Improving Transparency an Individual Consul 2017-10-0 2017-10-2 2017-09-2 2017-11-2 2017-09-2 2018-05-2 2017-10-3 IDA / V0780 Post Limited 8,663.69 Completed 2017-09-27 national_documents de polit d Accountability tant Selection 2 3 9 7 9 6 1 ique et de programmation macroéconomique PRISP-21-C-CI-18 / Régulari Improving Transparency an Individual Consul 2017-10-0 2017-10-2 2017-11-2 2018-05-2 sation dans STEP Consultant IDA / V0780 Post Limited 0.00 Canceled 2017-09-27 d Accountability tant Selection 2 3 7 6 national_Gouvernance écon omique PRISP-20-C-CI-18 / Régulari Improving Transparency an Individual Consul 2017-10-0 2017-10-2 2017-09-2 2017-11-2 2017-09-2 2018-05-2 2017-10-3 sation dans STEP Consultant IDA / V0780 Post Limited 8,663.69 Completed 2017-09-27 d Accountability tant Selection 2 3 6 7 9 6 1 national_Ressources humain es PRISP-17-C-CI-18 / Régulari sation dans STEP Consultant Improving Transparency an Individual Consul 2017-08-0 2017-08-2 2017-08-1 2017-10-0 2017-08-2 2018-03-3 2017-11-1 IDA / V0780 Post Limited 59,200.00 Completed 2017-08-02 international_ Expert sectori d Accountability tant Selection 7 8 4 2 9 1 0 el Finance et Banque PRISP-23-C-CI-18 / Régulari Improving Transparency an Individual Consul 2017-10-0 2017-10-2 2017-10-0 2017-11-2 2017-10-0 2018-05-2 2017-11-0 sation dans STEP Consultant IDA / V0780 Post Limited 8,663.69 Completed 2017-09-27 d Accountability tant Selection 2 3 3 7 3 6 3 national_développement so cial_ santé PRISP-22-C-CI-18 / Régulari Improving Transparency an Individual Consul 2017-10-0 2017-10-2 2017-10-0 2017-11-2 2018-10-1 2018-05-2 2018-11-1 sation Consultant PND_ nati IDA / V0780 Post Limited 8,663.69 Completed 2017-09-27 d Accountability tant Selection 2 3 3 7 2 6 2 onal sectoriel _ agriculture e t foret PRISP-24-C-CI-18 / consulta nt individuel international p Improving Transparency an Individual Consul 2018-12-2 2018-09-1 2018-10-0 2018-11-0 2019-05-0 our la revue du et la mise à IDA / V0780 Post Open 0.00 Canceled 2018-07-23 d Accountability tant Selection 7 0 1 5 4 jour du cadre légal et régle mentaire des marchés publi cs PRISP-26-C-CI-18 / consulta nt individuel international e Improving Transparency an Individual Consul 2018-09-1 2018-10-0 2018-11-0 2019-05-0 IDA / V0780 Post Open 0.00 Canceled 2018-07-24 n charge de l'élaboration d' d Accountability tant Selection 1 2 6 5 une stratégie de communic ation de l'ARMP PRISP-03-C-CI-18 / Régulari Improving Transparency an Individual Consul 2018-04-0 2018-08-0 2018-08-2 2018-05-0 2018-09-3 2018-05-0 2019-03-2 2018-07-3 sation_ Consultant internati IDA / V0780 Post Limited 25,100.00 Completed 2018-07-31 d Accountability tant Selection 9 5 6 3 0 7 9 0 onal Experts Programmation PRISP-02-C-CI-18 / Régulari Improving Transparency an Individual Consul 2018-04-0 2018-08-0 2018-08-2 2018-05-0 2018-09-3 2018-05-1 2019-03-2 2018-07-3 sation_ Contrat du consulta IDA / V0780 Post Limited 39,100.00 Completed 2018-07-31 d Accountability tant Selection 9 5 6 3 0 0 9 0 nt principal_ pour l'éboratio n du PND_ PRISP-04-C-CI-18 / Régulari Improving Transparency an Individual Consul 2018-04-0 2018-08-0 2018-08-2 2018-05-0 2018-09-3 2018-05-0 2019-03-2 2018-07-3 sation_ Contrat consultant_ IDA / V0780 Post Limited 25,100.00 Completed 2018-07-31 d Accountability tant Selection 9 5 6 3 0 4 9 0 expert en programmation_ PRISP-06-C-CI-18 / Régulari sation_ Consultant internati Improving Transparency an Individual Consul 2018-04-0 2018-08-0 2018-08-2 2018-04-3 2018-09-3 2018-05-0 2019-03-2 2018-07-2 IDA / V0780 Post Limited 18,800.00 Completed 2018-07-31 onal- Expert en stratégie se d Accountability tant Selection 9 5 6 0 0 4 9 5 ctoriel_ Gouvernance PRISP-07-C-CI-18 / Régulari Improving Transparency an Individual Consul 2018-04-2 2018-08-0 2018-08-2 2018-05-0 2018-09-3 2018-05-0 2019-03-2 2018-07-3 sation Consultant internatio IDA / V0780 Post Limited 18,800.00 Completed 2018-07-31 d Accountability tant Selection 4 5 6 3 0 4 9 0 nal expert en stratégie sect orielle_ Agriculture Page 4 PRISP-08-C-CI-18 / Régulari Improving Transparency an Individual Consul 2018-08-0 2018-08-2 2018-04-1 2018-09-3 2018-05-0 2019-03-2 2018-07-3 sation_Consultant national_ IDA / V0780 Post Limited 9,467.00 Completed 2018-07-31 d Accountability tant Selection 5 6 9 0 3 9 0 expert en stratégie sectoriel le_ (agriculture) PRISP-12-C-CI-18 / Régulari sation dans STEP Consultant Improving Transparency an Individual Consul 2017-08-0 2017-08-2 2017-08-1 2017-10-0 2017-08-2 2018-03-3 2017-11-1 IDA / V0780 Post Limited 59,200.00 Completed 2017-08-02 international_ Expert sectori d Accountability tant Selection 7 8 4 2 9 1 0 el Gouvernance administrati ve PRISP-09-C-CI-18 / Régulari sation_ Consultant national_ Improving Transparency an Individual Consul 2018-08-0 2018-08-2 2018-05-0 2018-09-3 2018-05-0 2019-03-2 2018-07-3 expert stratégie sectorielle_ IDA / V0780 Post Limited 9,467.00 Completed 2018-07-31 d Accountability tant Selection 5 6 3 0 3 9 0 (ressources humaines: éduc ation, formation, emploi) PRISP-10-C-CI-18 / Régulari sation_Consultant national e Improving Transparency an Individual Consul 2018-08-0 2018-08-2 2018-05-0 2018-09-3 2018-05-0 2019-03-2 2018-07-3 IDA / V0780 Post Limited 9,467.00 Completed 2018-07-31 xpert en stratégie sectoriell d Accountability tant Selection 5 6 3 0 4 9 0 e (santé et affaires sociales) PRISP-28-C-CI-18 / Recrute Strengthening Revenue Mo ment d'un consultant individ Individual Consul 2018-06-2 2018-08-1 2018-06-2 2018-09-0 2018-07-1 2018-10-1 2018-07-1 2019-04-0 2018-08-0 IDA / V0780 bilization and Public Expen Post Open 18,104.00 Completed 2018-06-27 uel international en charge tant Selection 5 5 9 5 2 0 2 8 2 diture Management de la formation en fibre opti que PRISP-29-C-CI-18 / Recrute ment d'un consultant individ Strengthening Revenue Mo Individual Consul 2018-06-2 2018-09-0 2018-06-2 2018-09-2 2018-07-0 2018-10-3 2018-07-0 2019-04-2 2018-08-1 uel international pour effect IDA / V0780 bilization and Public Expen Post Open 27,241.20 Completed 2018-07-18 tant Selection 5 5 9 6 2 1 2 9 7 uer un etat des lieux et capi diture Management talisation des projets d'infor matisation PRISP-31-C-CI-18 / Recrute ment consultant individuel n Improving Transparency an Individual Consul 2018-07-2 2018-09-1 2018-11-0 2018-10-0 2018-11-0 2018-11-0 2018-11-1 2019-05-0 2019-07-3 ational en charge de l'etude IDA / 60230 Post Open 25,195.20 Completed 2018-07-27 d Accountability tant Selection 4 4 2 5 5 9 2 8 1 et la mise en place de deux sites web du SENAT et asse mblee nationale PRISP-32-C-CI-18 / Recrute ment d'un consultant individ Modernization of the Public Individual Consul 2018-12-2 2018-09-1 2019-03-1 2018-10-0 2019-03-1 2018-11-1 2019-03-1 2019-05-1 IDA / 60230 Post Open 36,396.17 Terminated 2018-07-31 uel international pour l'elab Administration tant Selection 7 8 1 9 1 3 2 2 oration d'une strategie de c ommunicationd e l'ARMP PRISP-33-C-CI-18 / Recrute ment d'un consultant individ Modernization of the Public Individual Consul 2018-07-2 2018-09-0 2018-09-2 2018-11-0 2019-05-0 IDA / 60230 Post Open 0.00 Canceled 2018-07-20 uel en charge de la restruct Administration tant Selection 4 7 8 2 1 uration et le renforcement d es CGMP PRISP-35-C-CI-18 / Recrute ment d'un consultant individ Project Implementation Sup Individual Consul 2018-07-2 2018-09-1 2018-10-1 2018-10-0 2018-10-2 2018-11-1 2018-10-3 2019-05-1 2019-03-1 uel international chargé de l IDA / 60230 Post Open 72,260.00 Completed 2018-07-31 port tant Selection 4 8 9 9 4 3 1 2 6 a mise en place d'une cellul e des reformes en matiere d e gouvernance PRISP-031-C-CI-17 / Recrute ment d'un consultant individ Improving Transparency an Individual Consul 2018-03-2 2018-04-1 2018-05-1 2018-11-1 uel international pour l'élab IDA / V0780 Post Open 0.00 Canceled 2018-01-30 d Accountability tant Selection 0 0 5 1 oration du Plan d'action stra tégique pour la réforme des Finances Publiques PRISP-25-C-CI-18 / consulta nt individuel international e Improving Transparency an Individual Consul 2018-09-1 2018-10-0 2018-11-0 2019-05-0 IDA / V0780 Post Open 0.00 Canceled 2018-07-24 n charge de la restructuratio d Accountability tant Selection 1 2 6 5 n et le renforcement des CG MP PRISP-30-C-CI-18 / Recrute Improving Transparency an Individual Consul 2018-08-0 2018-08-1 2018-09-0 2018-10-0 2019-04-0 ment consultant individuel e IDA / 60230 Prior Open 0.00 Canceled 2018-06-26 d Accountability tant Selection 7 4 4 9 7 n charge de l'elaboration de s rapports ITIE PRISP-05-C-CI-18 / Régulari Improving Transparency an 2018-08-1 2018-10-1 2019-04-1 sation_ Contrat du consulta IDA / V0780 Post Direct Selection Direct 0.00 Canceled 2018-07-31 d Accountability 0 4 2 nt_ Expert sectoriel_RH PRISP-43-C-CI-18 / Consulta Strengthening Revenue Mo nt Pour le développement d Individual Consul 2018-11-1 2018-12-0 2019-01-0 2019-07-0 IDA / 60230 bilization and Public Expen Post Open 0.00 Canceled 2018-09-26 e l'application Système de G tant Selection 4 5 9 8 diture Management estion RH de la DGID PRISP-44-C-CI-18 / Consulta Strengthening Revenue Mo nt pour la mise en place de l Individual Consul 2018-09-0 2018-11-1 2018-12-0 2019-01-2 2019-01-1 2019-01-2 2019-07-0 IDA / 60230 bilization and Public Expen Post Open 104,549.48 Signed 2018-09-27 a gestion prévisionnelle des tant Selection 6 5 6 9 0 9 9 diture Management emplois et compétences (G EPC) à la DGID PRISP-45-C-CI-18 / Consulta Strengthening Revenue Mo nt individuel international p Individual Consul 2018-09-0 2018-11-1 2018-12-0 2019-01-1 2019-07-0 IDA / 60230 bilization and Public Expen Post Open 0.00 Canceled 2018-09-27 our la formation des inspect tant Selection 6 5 6 0 9 diture Management eurs aux métiers de la Fiscal ité PRISP-46-C-CI-18 / Consulta Strengthening Revenue Mo nt international pour l'élabor Individual Consul 2018-11-1 2018-12-0 2019-01-1 2019-07-1 IDA / 60230 bilization and Public Expen Post Open 0.00 Canceled 2018-09-28 ation du plan directeur de l' tant Selection 6 7 1 0 diture Management organisation générale du sy stème comptable public PRISP-47-C-CI-18 / Consulta Strengthening Revenue Mo Individual Consul 2018-11-1 2018-12-1 2019-01-1 2019-07-1 nt individuel pour l'étude de IDA / 60230 bilization and Public Expen Post Open 0.00 Canceled 2018-10-01 tant Selection 9 0 4 3 mise à niveau des data cent diture Management ers de BZV et P/N PRISP-48-C-CI-18 / Consulta nt individuel international e Strengthening Revenue Mo Individual Consul 2018-09-0 2018-11-1 2019-01-1 2018-12-0 2019-01-1 2019-01-1 2019-01-2 2019-07-1 2020-03-0 n charge de la formation et IDA / 60230 bilization and Public Expen Post Open 69,545.62 Completed 2018-09-28 tant Selection 5 6 1 7 5 1 4 0 9 accompagnement des ingén diture Management ieurs développeurs PL/SQL s ous oracle EBS du SIGFIP PRISP-49-C-CI-18 / Consulta Strengthening Revenue Mo nt individuel international p Individual Consul 2018-09-0 2018-11-1 2019-01-2 2018-12-0 2019-01-2 2019-01-1 2019-01-2 2019-07-1 2019-10-1 IDA / 60230 bilization and Public Expen Post Open 72,813.38 Completed 2018-09-28 our la formation et accompa tant Selection 5 6 4 7 9 1 5 0 5 diture Management gnement en JAVA/EBS du SI GFIP PRISP-50-C-CI-18 / Consulta nt individuel international c Strengthening Revenue Mo Individual Consul 2018-09-0 2018-11-1 2018-11-1 2018-12-0 2018-12-2 2019-01-1 2019-01-1 2019-07-0 2019-09-3 hargé de la formation des in IDA / 60230 bilization and Public Expen Post Open 86,022.82 Completed 2018-09-27 tant Selection 5 5 4 6 4 0 5 9 0 génieurs développeurs sous diture Management Oracle HYPERION PLANNING EBS du SIGFIP PRISP-54-C-CI-18 / Consulta nt individuel international c Modernization of the Public Individual Consul 2018-09-0 2018-11-2 2018-12-1 2019-01-2 2019-07-2 hargé de la revue du cadre l IDA / 60230 Post Open 0.00 Canceled 2018-10-10 Administration tant Selection 5 8 9 3 2 égal, réglementaire et instit utionnelle de la fonction pub lique PRISP-55-C-CI-18 / Consulta nt individuel international p Modernization of the Public Individual Consul 2018-09-0 2018-11-2 2018-11-1 2018-12-1 2018-11-2 2019-01-2 2018-11-2 2019-07-2 2019-06-3 our le développement du pl IDA / 60230 Post Open 85,210.00 Completed 2018-10-08 Administration tant Selection 5 6 9 7 3 1 7 0 0 an de formation pour le renf orcement des capacités des agents du MFPRE PRISP-56-C-CI-18 / Consulta nt individuel national chargé Improving Transparency an Individual Consul 2018-08-1 2018-11-2 2018-12-1 2019-01-2 2019-07-2 IDA / 60230 Post Open 0.00 Canceled 2018-10-10 des études et de la mise en d Accountability tant Selection 6 8 9 3 2 place de deux sites web du sénat et de l'assemblée PRISP-57-C-CI-18 / Consulta Improving Transparency an Individual Consul 2018-08-2 2018-11-0 2018-11-2 2019-01-0 2019-07-0 nt individuel international c IDA / 60230 Post Open 0.00 Canceled 2018-09-20 d Accountability tant Selection 3 8 9 3 2 hargé de l'identification et d e l'appui aux OSC PRISP-38-C-CI-18 / Trésorier Project Implementation Sup Individual Consul 2018-09-1 2018-11-1 2018-11-3 2018-12-0 2018-12-0 2019-01-0 2018-12-1 2019-07-0 2019-12-1 IDA / 60230 Post Open 20,169.96 Completed 2018-09-24 PRISP port tant Selection 9 2 0 3 4 7 0 6 0 PRISP-39-C-CI-18 / Assistant Project Implementation Sup Individual Consul 2018-09-1 2018-11-1 2018-11-0 2018-12-0 2018-12-0 2019-01-0 2018-12-1 2019-07-0 2019-12-1 IDA / 60230 Post Open 16,505.47 Completed 2018-09-25 de Direction du PRISP port tant Selection 9 3 9 4 4 8 0 7 0 PRISP-40-C-CI-18 / Chauffeu Project Implementation Sup Individual Consul 2018-09-1 2018-11-1 2018-11-1 2018-12-0 2018-11-1 2019-01-0 2018-11-1 2019-07-0 2019-11-1 IDA / 60230 Post Open 6,175.01 Completed 2018-09-24 r coursier PRISP port tant Selection 9 2 2 3 2 7 3 6 4 PRISP-41-C-CI-18 / Planton Project Implementation Sup Individual Consul 2018-09-1 2018-11-1 2018-11-1 2018-12-0 2018-11-1 2019-01-0 2018-11-1 2019-07-0 2019-11-1 IDA / 60230 Post Open 4,108.08 Completed 2018-09-25 PRISP port tant Selection 9 3 2 4 2 8 3 7 4 PRISP-42-C-CI-18 / Chargé d Project Implementation Sup Individual Consul 2018-10-1 2018-11-1 2019-01-3 2018-12-0 2019-01-3 2019-01-0 2019-01-3 2019-07-0 2020-02-0 IDA / 60230 Post Open 30,234.24 Completed 2018-09-26 e la communication PRISP port tant Selection 6 4 1 5 1 9 1 8 1 PRISP-070-C-CI-18 / Recrute Project Implementation Sup Individual Consul 2018-11-2 2018-10-2 2018-12-0 2018-11-1 2018-12-0 2018-12-2 2018-12-1 2019-06-2 2019-12-1 ment d'un Assistant en pass IDA / 60230 Post Limited 21,828.43 Completed 2018-10-22 port tant Selection 3 7 4 7 5 2 0 0 0 ation des marchés au sein d e l'UCP PRISP-65-C-CI-18 / Consulta nt individuel international p Modernization of the Public Individual Consul 2019-04-1 2019-05-0 2019-06-1 2019-12-1 our le développement d'un r IDA / 60230 Post Open 0.00 Canceled 2019-02-28 Administration tant Selection 8 9 3 0 egistre de la fonction publiq ue sue la base du recensem ent en cours PRISP-51-C-CI-18 / Consulta nt individuel international p Strengthening Revenue Mo Individual Consul 2018-08-1 2018-12-1 2018-08-2 2019-01-0 2018-09-1 2019-02-1 2018-09-1 2019-08-1 our l'assistance technique a IDA / 60230 bilization and Public Expen Prior Open 214,239.00 Signed 2018-10-31 tant Selection 4 9 1 9 2 3 2 2 ux travaux interconnexion d diture Management es centres des impôts de BZ V et de P/N PRISP-64-C-CI-18 / Consulta Strengthening Revenue Mo nt individuel international e Individual Consul 2018-11-0 2018-11-2 2018-08-0 2018-12-3 2018-09-1 2019-06-2 IDA / 60230 bilization and Public Expen Post Limited 88,295.00 Signed 2018-10-31 n charge de la conception d tant Selection 5 6 7 1 2 9 diture Management es modules et la formation en fibre optique PRISP-63-C-CI-18 / Consulta nt individuel international c Strengthening Revenue Mo Individual Consul 2018-11-0 2018-11-2 2018-08-2 2018-12-3 2018-08-2 2019-06-2 2019-08-2 hargé d'accompagner les pr IDA / 60230 bilization and Public Expen Prior Limited 161,907.76 Completed 2018-10-31 tant Selection 5 6 1 1 8 9 8 ojets d'informatisation,de fi diture Management nances publiques et des ad ministrations publiques PRISP-073-C-CI-18 / Consult ant Individuel international Strengthening Revenue Mo Individual Consul 2018-12-2 2019-02-1 2019-03-1 2019-03-1 2019-03-1 2019-04-1 2019-03-1 2019-10-1 2020-03-0 pour la revue organisationn IDA / 60230 bilization and Public Expen Post Open 52,200.92 Completed 2018-12-31 tant Selection 7 8 1 1 5 5 5 2 9 elle et des procédures de la diture Management DSI finances à la gestion de s RH PRISP-075-C-CI-18 / Consult ant Individuel international Strengthening Revenue Mo pour l'élaboration des spécif Individual Consul 2018-12-2 2019-03-1 2019-04-1 2019-04-0 2019-04-3 2019-05-1 2019-05-2 2019-11-1 2020-04-0 IDA / 60230 bilization and Public Expen Post Open 54,920.00 Completed 2019-01-29 ications techniques et réalis tant Selection 7 9 6 9 0 4 3 0 5 diture Management ations de l'étude pour la rép aration du système solaire à Pointe-Noire Page 5 PRISP-076-C-CI-18 / Consult Strengthening Revenue Mo ant Individuel national pour Individual Consul 2018-12-2 2019-02-1 2019-03-0 2019-03-1 2019-03-1 2019-04-1 2019-03-1 2019-10-1 2020-07-3 IDA / 60230 bilization and Public Expen Post Open 20,582.13 Completed 2018-12-31 la création, l'organisation et tant Selection 7 8 7 1 1 5 2 2 0 diture Management l'animation d'un site web de la DGPD PRISP-077-C-CI-18 / Recrute Strengthening Revenue Mo Individual Consul 2018-12-2 2019-01-0 2019-01-2 2019-01-2 2019-01-2 2019-02-2 2019-01-3 2019-08-2 2020-02-0 ment d'un ingénieur dévelo IDA / 60230 bilization and Public Expen Post Limited 14,669.82 Completed 2018-12-28 tant Selection 7 2 9 3 9 7 1 6 2 ppeur 1 à la DSI Finances diture Management PRISP-079-C-CI-18 / Recrute Strengthening Revenue Mo Individual Consul 2018-12-2 2019-01-0 2019-01-2 2019-01-3 2019-01-2 2019-03-0 2019-01-3 2019-09-0 2020-02-0 ment d'un ingénieur dévelo IDA / 60230 bilization and Public Expen Post Limited 15,274.89 Completed 2019-01-04 tant Selection 7 9 9 0 9 6 0 2 1 ppeur 2 à la DSI Finances diture Management PRISP-080-C-CI-18 / Recrute Strengthening Revenue Mo Individual Consul 2018-12-2 2019-01-0 2019-01-2 2019-01-2 2019-01-2 2019-03-0 2019-01-3 2019-09-0 2020-02-0 ment d'un ingénieur dévelo IDA / 60230 bilization and Public Expen Post Limited 15,274.89 Completed 2019-01-03 tant Selection 7 8 9 9 9 5 0 1 1 ppeur 4 à la DSI Finances diture Management PRISP-081-C-CI-18 / Consult Project Implementation Sup Individual Consul 2018-12-2 2018-12-3 2019-01-3 2019-01-2 2019-01-3 2019-02-2 2019-01-3 2019-08-2 2020-01-3 ant Individuel national en inf IDA / 60230 Post Limited 40,339.92 Completed 2018-12-26 port tant Selection 7 1 0 1 0 5 0 4 0 ormatique pour appuyer le P RISP PRISP-082-C-CI-18 / Recrute Strengthening Revenue Mo Individual Consul 2018-12-2 2019-01-1 2019-01-2 2019-02-0 2019-01-2 2019-03-0 2019-01-3 2019-09-0 2020-02-0 ment d'un ingénieur admini IDA / 60230 bilization and Public Expen Post Limited 15,274.89 Completed 2019-01-07 tant Selection 7 2 9 2 9 9 0 5 1 strateur base de données 1 diture Management à la DSI finances PRISP-083-C-CI-18 / Recrute Strengthening Revenue Mo Individual Consul 2018-12-2 2019-01-1 2019-01-2 2019-02-0 2019-01-2 2019-03-1 2019-01-3 2019-09-0 2020-02-0 ment d'un ingénieur admini IDA / 60230 bilization and Public Expen Post Limited 14,930.55 Completed 2019-01-09 tant Selection 7 4 9 4 9 1 1 7 2 strateur base de données 2 diture Management à la DSI finances PRISP-084-C-CI-18 / Recrute Strengthening Revenue Mo Individual Consul 2018-12-2 2019-01-1 2019-01-0 2019-02-0 2019-01-2 2019-03-1 2019-01-3 2019-09-1 2020-02-0 ment d'un ingénieur admini IDA / 60230 bilization and Public Expen Post Limited 16,211.34 Completed 2019-01-14 tant Selection 7 9 9 9 9 6 1 2 2 strateur base de données 3 diture Management à la DSI finances PRISP-085-C-CI-18 / Recrute Strengthening Revenue Mo Individual Consul 2018-12-2 2019-01-1 2019-02-0 2019-01-3 2019-03-1 2019-01-3 2019-09-0 2020-02-0 ment d'un ingénieur admini IDA / 60230 bilization and Public Expen Post Limited 15,434.82 Completed 2019-01-10 tant Selection 7 5 5 0 2 1 8 1 strateur base de données 4 diture Management à la DSI finances PRISP-088-C-CI-18 / Recrute Strengthening Revenue Mo ment d'un ingénieur admini Individual Consul 2018-12-2 2019-01-2 2019-02-1 2019-01-3 2019-03-1 2019-01-3 2019-09-1 2020-02-0 IDA / 60230 bilization and Public Expen Post Limited 15,434.82 Completed 2019-01-15 strateur des systèmes et rés tant Selection 7 0 0 0 7 1 3 1 diture Management eaux 1 à la DSI finances PRISP-089-C-CI-18 / Recrute Strengthening Revenue Mo ment d'un ingénieur admini Individual Consul 2018-12-2 2019-01-2 2019-02-1 2019-01-3 2019-03-2 2019-01-3 2019-09-1 2020-02-0 IDA / 60230 bilization and Public Expen Post Limited 15,434.82 Completed 2019-01-18 strateur des systèmes et rés tant Selection 7 3 3 0 0 1 6 1 diture Management eaux 2 à la DSI finances PRISP-090-C-CI-18 / Recrute Strengthening Revenue Mo ment d'un ingénieur admini Individual Consul 2018-12-2 2019-01-1 2019-01-2 2019-02-0 2019-01-2 2019-03-1 2019-01-3 2019-09-1 2020-02-0 IDA / 60230 bilization and Public Expen Post Limited 15,434.82 Completed 2019-01-14 strateur des systèmes et rés tant Selection 7 9 9 9 9 6 0 2 1 diture Management eaux 3 à la DSI finances PRISP-091-C-CI-18 / Recrute Strengthening Revenue Mo ment d'un ingénieur admini Individual Consul 2018-12-2 2019-01-2 2019-01-3 2019-02-1 2019-01-3 2019-03-2 2019-02-0 2019-09-1 2020-02-0 IDA / 60230 bilization and Public Expen Post Limited 15,166.53 Completed 2019-01-21 strateur des systèmes et rés tant Selection 7 6 1 6 0 3 1 9 2 diture Management eaux 4 à la DSI finances PRISP-092-C-CI-18 / Recrute Strengthening Revenue Mo ment d'un ingénieur admini Individual Consul 2018-12-2 2019-01-2 2019-02-1 2019-01-3 2019-03-2 2019-01-3 2019-09-1 2020-02-0 IDA / 60230 bilization and Public Expen Post Limited 15,434.82 Signed 2019-01-21 strateur des systèmes et rés tant Selection 7 6 6 0 3 1 9 1 diture Management eaux 5 à la DSI finances PRISP-093-C-CI-18 / Recrute Strengthening Revenue Mo ment d'un ingénieur admini Individual Consul 2018-12-2 2019-01-3 2019-02-2 2019-01-3 2019-03-2 2019-01-3 2019-09-2 2020-02-0 IDA / 60230 bilization and Public Expen Post Limited 15,434.82 Completed 2019-01-25 strateur des systèmes et rés tant Selection 7 0 0 0 7 0 3 1 diture Management eaux 6 à la DSI finances PRISP-094-C-CI-18 / Recrute Strengthening Revenue Mo ment d'un ingénieur admini Individual Consul 2018-12-2 2019-01-2 2019-01-2 2019-02-1 2019-01-3 2019-03-2 2019-02-0 2019-09-2 2020-02-0 IDA / 60230 bilization and Public Expen Post Limited 15,178.86 Completed 2019-01-22 strateur des systèmes et rés tant Selection 7 7 9 7 0 4 1 0 2 diture Management eaux 7 à la DSI finances PRISP-078-C-CI-18 / Recrute Strengthening Revenue Mo Individual Consul 2019-01-0 2019-01-2 2019-01-2 2019-02-2 2019-01-3 2019-08-2 2020-02-0 ment d'un ingénieur dévelo IDA / 60230 bilization and Public Expen Post Limited 15,434.82 Completed 2018-12-27 tant Selection 1 2 9 6 0 5 1 ppeur 2 à la DSI Finances diture Management PRISP-53-C-CI-18 / Consulta Strengthening Revenue Mo nt individuel national pour l Individual Consul 2018-12-0 2019-05-1 2019-06-0 2019-07-1 2020-01-0 IDA / 60230 bilization and Public Expen Post Open 0.00 Canceled 2019-03-29 a création, l'organisation et tant Selection 3 7 7 2 8 diture Management l'animation d'un site web à l a DSI/DGPD PRISP-95-C-CI-19 / Renouve Project Implementation Sup Individual Consul 2019-02-2 2019-03-1 2019-02-2 2019-03-3 2019-02-2 2019-05-0 2019-02-2 2019-11-0 2019-08-1 IDA / 60230 Post Direct 25,467.30 Completed 2019-02-28 llement du contrat du coord port tant Selection 0 0 0 1 0 5 0 1 9 onnateur PRISP-96-C-CI-19 / Renouve Project Implementation Sup Individual Consul 2019-02-2 2019-04-0 2019-02-2 2019-04-2 2019-02-2 2019-06-0 2019-02-2 2019-11-3 2019-09-0 llement du contrat du spéci IDA / 60230 Post Direct 20,366.52 Completed 2019-03-29 port tant Selection 2 8 1 9 1 3 1 0 4 aliste en suivi-évaluation PRISP-97-C-CI-19 / Renouve Project Implementation Sup Individual Consul 2019-02-2 2019-04-0 2019-02-2 2019-04-2 2019-02-2 2019-06-0 2019-02-2 2019-11-3 2019-09-0 llement contrat du spécialist IDA / 60230 Post Direct 21,670.02 Completed 2019-03-29 port tant Selection 2 8 1 9 1 3 1 0 7 e en passation des marchés PRISP-98-C-CI-19 / Renouve Project Implementation Sup Individual Consul 2019-02-2 2019-03-1 2019-02-2 2019-03-3 2019-02-2 2019-05-0 2019-02-2 2019-11-0 2019-08-1 llement contrat du Respons IDA / 60230 Post Direct 18,329.87 Completed 2019-02-28 port tant Selection 0 0 0 1 0 5 0 1 9 able Administratif Financier et Comptable PRISP-99-C-CI-19 / Renouve Project Implementation Sup Individual Consul 2019-06-1 2019-08-1 2019-06-1 2019-08-3 2019-06-1 2019-10-0 2019-06-1 2020-04-0 2020-07-0 IDA / 60230 Post Direct 48,000.00 Completed 2019-07-31 llement contrat Auditeur int port tant Selection 2 0 0 1 2 5 3 2 8 erne PRISP-100-C-CI-19 / Renouv Project Implementation Sup Individual Consul 2019-04-2 2019-06-1 2019-04-2 2019-07-0 2019-04-2 2019-08-0 2019-04-2 2020-02-0 2020-05-1 IDA / 60230 Post Direct 28,267.34 Completed 2019-05-31 ellement contrat Comptable port tant Selection 0 0 3 1 3 5 3 1 4 PRISP-105-C-CI-19 / Consult Strengthening Revenue Mo Individual Consul 2019-02-2 2019-05-1 2019-04-1 2019-06-0 2019-05-2 2019-07-1 2019-05-2 2020-01-0 2020-03-0 ant individuel international IDA / 60230 bilization and Public Expen Post Open 62,900.00 Completed 2019-03-28 tant Selection 4 6 6 6 3 1 4 7 9 en charge audit institutionn diture Management el DGPP PRISP-106-C-CI-19 / Consult Strengthening Revenue Mo Individual Consul 2019-02-2 2019-05-1 2019-04-1 2019-06-0 2019-05-0 2019-07-1 2019-05-1 2020-01-0 2019-10-0 ant individuel international IDA / 60230 bilization and Public Expen Post Open 35,173.51 Completed 2019-03-28 tant Selection 4 6 6 6 8 1 1 7 1 en charge elaboration plan diture Management de formation DGPP PRISP-108-C-CI-19 / Consult ant individuel pour la conce Strengthening Revenue Mo Individual Consul 2019-02-2 2019-05-1 2019-04-1 2019-06-0 2019-12-2 2019-07-1 2020-01-1 2020-01-0 ption et mise en place d un IDA / 60230 bilization and Public Expen Post Open 113,180.00 Signed 2019-03-29 tant Selection 4 7 6 7 6 2 7 8 systeme de gestion electron diture Management ique de document à la DGPP PRISP-111-C-CI-19 / Consult Improving Transparency an Individual Consul 2019-02-0 2019-05-1 2019-04-1 2019-06-0 2019-08-2 2019-07-1 2019-08-2 2020-01-0 2020-09-1 IDA / 60230 Post Open 40,400.92 Completed 2019-03-29 ant charge audit institutionn d Accountability tant Selection 9 7 6 7 7 2 8 8 6 el ENAM PRISP-112-C-CI-19 / Consult ant individuel charge de la c Improving Transparency an Individual Consul 2019-04-0 2019-04-1 2019-05-0 2019-06-1 2019-12-1 onception et mise en place IDA / 60230 Post Open 0.00 Canceled 2019-02-28 d Accountability tant Selection 5 8 9 3 0 ssyteme de gestion electron ique des documents de la C CDB PRISP-113-C-CI-19 / Consult ant individuel en charge de l Improving Transparency an Individual Consul 2019-04-0 2019-05-1 2019-06-0 2019-07-1 2020-01-0 IDA / 60230 Post Open 0.00 Canceled 2019-03-29 a creation et animation du s d Accountability tant Selection 5 7 7 2 8 ite web de la CCDB PRISP-114-C-CI-19 / Consult ant national homologue pou Improving Transparency an Individual Consul 2019-02-0 2019-05-0 2019-01-2 2019-05-2 2019-02-1 2019-06-3 2019-02-1 2019-12-2 IDA / 60230 Post Limited 40,579.20 Signed 2019-04-30 r accompagner le consultant d Accountability tant Selection 9 5 5 6 5 0 6 7 international a l engagemen t citoyen PRISP-115-C-CI-19 / Consult ant national homologue pou Project Implementation Sup Individual Consul 2019-05-0 2019-05-2 2019-03-0 2019-06-3 2019-03-0 2019-12-2 2020-02-2 IDA / 60230 Post Limited 61,722.72 Completed 2019-04-30 r accompagner le consultant port tant Selection 5 6 1 0 1 7 8 international en matiere de gouvernance PRISP-122-C-CI-19 / Recrute ment d un consultant indivi Strengthening Revenue Mo Individual Consul 2019-05-2 2019-09-1 2019-07-3 2019-10-0 2019-08-0 2019-11-1 2019-08-2 2020-05-1 duel international charge de IDA / 60230 bilization and Public Expen Post Open 134,950.00 Signed 2019-07-31 tant Selection 7 8 0 9 2 3 0 1 l appui au pilotage de la ref diture Management orme des finances publique s PRISP-124-C-CI-19 / Recrute ment d un consultant indivi Strengthening Revenue Mo Individual Consul 2019-05-1 2019-08-1 2019-07-2 2019-09-0 2019-08-2 2019-10-1 2019-08-2 2020-04-0 2019-12-2 duel international charge de IDA / 60230 bilization and Public Expen Post Open 66,321.10 Completed 2019-06-28 tant Selection 7 6 9 6 0 1 0 8 4 l elaboration du schema dire diture Management cteur informatique du MPSIR PRISP-126-C-CI-19 / Recrute ment d un consultant indivi Modernization of the Public Individual Consul 2019-07-2 2019-06-1 2019-07-0 2019-08-1 2020-02-0 IDA / 60230 Post Open 0.00 Canceled 2019-04-30 duel international pour l ope Administration tant Selection 5 8 9 3 9 rationnalisation du plan stra tegique du MFPRETSS PRISP-128-C-CI-19 / Recrute ment consultant individuel i Modernization of the Public Individual Consul 2019-06-1 2019-07-0 2019-08-1 2020-02-0 IDA / 60230 Post Open 0.00 Canceled 2019-04-30 nternational en charge de la Administration tant Selection 8 9 3 9 surveillance des travaux du SIGRHE PRISP-129-C-CI-19 / Recrute ment d un consultant indivi duel international pour l app Modernization of the Public Individual Consul 2019-08-1 2019-09-0 2019-10-1 2020-04-0 ui a la mise en place d un sy IDA / 60230 Post Open 0.00 Canceled 2019-06-28 Administration tant Selection 6 6 1 8 steme de collecte et de trait ement des informations stat istiques des marches public s au nuveau des differents a cteurs PRISP-131-C-CI-19 / Recrute ment d un consultant indivi duel en charge de la redacti Modernization of the Public Individual Consul 2019-08-1 2019-09-0 2019-10-1 2020-04-0 on des supports et guide de IDA / 60230 Post Open 0.00 Canceled 2019-06-28 Administration tant Selection 6 6 1 8 formation dans le cadre de l initiation a la professionnalis ation des fonctions des spec ialistes en passation des ma rches publics PRISP-133-C-CI-19 / Recrute ment d un consultant indivi Improving Transparency an Individual Consul 2019-03-2 2019-07-1 2019-05-2 2019-08-0 2019-06-2 2019-09-1 2019-06-2 2020-03-1 2020-03-2 duel international pour l ela IDA / 60230 Post Open 37,000.00 Completed 2019-05-31 d Accountability tant Selection 8 9 8 9 1 3 2 1 1 boration d un guide metjodo logique d audit au profit de l IGF Page 6 PRISP-135-C-CI-19 / Recrute ment d un consultant indivi duel international pour la co Improving Transparency an Individual Consul 2019-03-2 2019-07-1 2019-08-0 2019-09-1 2020-03-1 nception et mise en place d IDA / 60230 Post Open 0.00 Canceled 2019-05-31 d Accountability tant Selection 8 9 9 3 1 un systeme de gestion elect ronique des lois et reglemen ts des documents et des arc hives pour l IGF PRISP-137-C-CI-19 / Recrute ment consultant individuel i Improving Transparency an Individual Consul 2019-08-2 2019-09-1 2020-01-1 2019-10-0 2020-03-3 2019-11-1 2020-04-0 2020-05-1 IDA / 60230 Post Open 76,145.97 Signed 2019-07-31 nternational pour l etude su d Accountability tant Selection 1 8 0 9 0 3 1 1 r la proprete reelle pour l ITI E PRISP-103-C-CI-19 / Consult ant individuel international Strengthening Revenue Mo Individual Consul 2019-05-1 2019-06-0 2019-07-1 2020-01-0 chargé etude sur les specifi IDA / 60230 bilization and Public Expen Post Open 0.00 Canceled 2019-03-28 tant Selection 6 6 1 7 cations techniques des infra diture Management structures solaires Pointe-N oire et surveillance travaux PRISP-66-C-CI-18 / Consulta nt individuel en charge de la Modernization of the Public Individual Consul 2019-05-1 2019-06-0 2019-07-1 2020-01-0 conception d'un système inf IDA / 60230 Post Open 0.00 Canceled 2019-03-29 Administration tant Selection 7 7 2 8 ormatisé pour la gestion des carrières des fonctionnaires PRISP-67-C-CI-18 / Consulta Strengthening Revenue Mo nt individuel international p Individual Consul 2019-06-0 2019-06-2 2019-08-0 2020-01-2 IDA / 60230 bilization and Public Expen Post Open 0.00 Canceled 2019-04-18 our l'appui à l'assistance tec tant Selection 6 7 1 8 diture Management hnique pour la partie RH PA YROLL PRISP-68-C-CI-18 / Consulta nt individuel international p Strengthening Revenue Mo Individual Consul 2019-06-1 2019-07-0 2019-08-1 2020-02-0 our la mise en place d'un sy IDA / 60230 bilization and Public Expen Post Open 0.00 Canceled 2019-04-30 tant Selection 8 9 3 9 stème de gestion des invent diture Management aires et de maintenance inf ormatiques au profit de la D SI PRISP-147-C-CI-18 / Consult ant individuel international Improving Transparency an Individual Consul 2018-08-2 2018-09-1 2018-10-1 2018-10-1 2018-10-0 2019-04-1 2019-10-0 IDA / 60230 Post Limited 116,000.00 Completed 2018-08-16 chargé de la redevabilite de d Accountability tant Selection 1 1 0 6 1 4 1 l engagement citoyen PRISP-025-C-CI-17 BIS / Con sultant individuel internatio Strengthening Revenue Mo Individual Consul 2017-10-0 2017-10-2 2018-09-2 2017-11-3 2018-10-1 2018-05-2 2019-04-1 nal pour la revue de la politi IDA / 60230 bilization and Public Expen Post Limited 72,715.00 Completed 2017-09-30 tant Selection 5 6 7 0 0 9 2 ques fiscale des regimes d e diture Management xemption (impots et douane s) PRISP-032-C-CI-17 BIS / Con sultant individuel internatio Modernization of the Public Individual Consul 2016-02-0 2016-02-2 2018-06-2 2016-03-3 2018-08-2 2016-09-2 2019-02-2 nal pour l analyse diagnosti IDA / 60230 Post Open 51,723.00 Completed 2015-12-17 Administration tant Selection 4 5 2 1 2 7 0 que de la gestion de la fonct ion publique: audit organisa tionnel PRISP-119-C-CI-19 / Recrute Project Implementation Sup Individual Consul 2019-08-1 2019-09-0 2019-10-1 2020-04-0 ment du Responsable admin IDA / 60230 Post Open 0.00 Canceled 2019-06-28 port tant Selection 6 6 1 8 istratif financier et comptabl e du PRISP PRISP-125-C-CI-19 / Consult Strengthening Revenue Mo ant pour l assistance techni Individual Consul 2019-11-0 2019-11-2 2019-12-3 2020-06-2 IDA / 60230 bilization and Public Expen Prior Limited 0.00 Canceled 2019-10-31 que au plan national de dev tant Selection 5 6 1 8 diture Management eloppement et son operatio nnalisation PRISP-146-C-CI-19 / Recrute ment d un consultant indivi Strengthening Revenue Mo duel international pour la for Individual Consul 2019-03-2 2019-05-0 2019-04-0 2019-05-2 2019-04-0 2019-06-3 2019-04-0 2019-12-2 2019-04-2 IDA / 60230 bilization and Public Expen Post Limited 39,314.00 Completed 2019-04-30 mation en fibre optique des tant Selection 8 5 1 6 2 0 3 7 3 diture Management agents du ministère du plan de la statistique et de l inte gration regionale PRISP-147-C-CI-19 / Recrute ment d'un consultant nation Project Implementation Sup Individual Consul 2019-07-2 2019-06-2 2019-09-2 2019-07-1 2019-09-2 2019-08-2 2019-09-2 2020-02-1 2019-10-0 IDA / 60230 Post Limited 4,339.68 Completed 2019-06-20 al 1 chargé de la formation port tant Selection 5 5 3 6 4 0 5 6 4 des points focaux et experts bénéficiaires du PRISP PRISP-148-C-CI-18 / Recrute ment d'un consultant nation Project Implementation Sup Individual Consul 2019-06-0 2019-07-3 2019-09-2 2019-08-2 2019-09-2 2019-09-2 2019-09-2 2020-03-2 2019-10-0 IDA / 60230 Post Limited 723.28 Completed 2019-07-25 al 2 en charge de la formati port tant Selection 4 0 3 0 4 4 7 2 4 on des points focaux et des bénéciaires du PRISP PRISP-150-C-CI-19 / Recrute ment d'un consultant individ uel international pour la for Improving Transparency an Individual Consul 2019-06-0 2019-11-1 2019-07-2 2019-12-0 2019-07-2 2020-01-1 2019-08-2 2020-07-1 2021-02-2 IDA / 60230 Post Open 198,766.00 Completed 2019-09-30 mation du personnel des Co d Accountability tant Selection 4 8 2 9 5 3 1 1 7 rps de Contrôle sur le Systè me Comptable OHADA révis é en République du Congo PRISP-154-C-CI-19 / Recrute ment d'un consultant nation al chargé du suivi de la refo Project Implementation Sup Individual Consul 2019-10-0 2019-10-0 2019-11-2 2019-10-2 2019-12-2 2019-11-3 2020-01-1 2020-05-2 2021-01-1 IDA / 60230 Post Limited 30,357.72 Completed 2019-09-30 rme des finances publiques port tant Selection 8 5 9 6 0 0 5 8 5 au sein de la cellule de suivi de la reforme du secteur pu blic en République du Congo PRISP-149-C-CI-19 / Recrute ment d'un consultant nation al chargé du suivi de la refo Project Implementation Sup Individual Consul 2019-10-0 2019-10-0 2019-11-2 2019-10-2 2019-12-2 2019-11-3 2020-01-1 2020-05-2 2020-01-1 IDA / 60230 Post Limited 30,286.44 Completed 2019-09-30 rme des entreprises publiqu port tant Selection 8 5 9 6 0 0 5 8 5 es au sein de la cellule de s uivi de la reforme du secteu r public en République du C ongo PRISP-151-C-CI-19 / Recrute ment d'un consultant nation al chargé du suivi de la refo Project Implementation Sup Individual Consul 2019-10-0 2019-10-0 2019-11-2 2019-10-2 2019-12-2 2019-11-3 2020-01-1 2020-05-2 2020-07-2 IDA / 60230 Post Limited 30,282.30 Completed 2019-09-30 rme de l Etat au sein de la c port tant Selection 8 5 9 6 0 0 4 8 2 ellule de suivi de la reforme du secteur public en Républi que du Congo PRISP-152-C-CI-19 / Recrute ment d'un consultant nation al chargé du suivi de la red Project Implementation Sup Individual Consul 2019-10-0 2019-10-0 2020-09-0 2019-10-2 2020-09-0 2019-11-3 2020-09-0 2020-05-2 IDA / 60230 Post Limited 33,270.66 Signed 2019-09-30 dition des comptes et la red port tant Selection 8 5 4 6 7 0 8 8 evabilité au sein de la cellul e de suivi de la reforme du s ecteur public en République du Congo PRISP-153-C-CI-19 / Recrute ment d'un consultant nation al chargé du suivi de la refo Project Implementation Sup Individual Consul 2019-10-0 2019-10-0 2020-03-1 2019-10-2 2020-03-1 2019-11-3 2020-04-0 2020-05-2 2021-03-3 IDA / 60230 Post Limited 32,406.30 Completed 2019-09-30 rme des marchés publics au port tant Selection 8 5 8 6 9 0 1 8 1 sein de la cellule de suivi de la reforme du secteur public en République du Congo PRISP-155-C-CI-19 / Recrute ment d'un consultant individ uel international chargé de l Project Implementation Sup Individual Consul 2019-06-2 2019-10-1 2019-07-0 2019-10-3 2019-07-0 2019-12-0 2019-07-2 2020-06-0 2019-12-3 IDA / 60230 Post Direct 87,575.00 Completed 2019-09-30 a mise en place d'une cellul port tant Selection 6 0 5 1 8 5 6 2 1 e de suivi de la reforme en matière de gouvernance (ph ase 2): ONGANANA Maximil ien PRISP-157-C-CI-2019 / Reno Project Implementation Sup Individual Consul 2019-07-1 2019-08-3 2020-08-2 2019-09-2 2020-08-2 2019-10-2 2020-08-2 2020-04-2 2020-08-2 uvellement contrat 2 du coo IDA / 60230 Post Direct 55,247.40 Completed 2019-08-20 port tant Selection 1 0 0 0 0 5 0 2 0 rdonnateur PRISP PRISP-158-C-CI-2019 / Reno Project Implementation Sup Individual Consul 2019-07-1 2019-09-1 2019-07-1 2019-10-0 2019-08-0 2019-11-1 2019-08-2 2020-05-0 2020-09-0 uvellement Contrat 2 du spe IDA / 60230 Post Direct 40,542.96 Completed 2019-09-06 port tant Selection 1 6 5 7 5 1 0 9 7 cialiste en passation des ma rches PRISP-159-C-CI-2019 / Reno Project Implementation Sup Individual Consul 2019-07-1 2019-08-2 2019-07-1 2019-09-1 2019-08-0 2019-10-2 2019-08-2 2020-04-2 2020-08-1 uvellement contrat 2 du res IDA / 60230 Post Direct 36,488.66 Completed 2019-08-19 port tant Selection 1 9 5 9 5 4 0 1 9 ponsable administratif finan cier et comptable PRISP-160-C-CI-2019 / Reno Project Implementation Sup Individual Consul 2019-07-1 2019-09-1 2019-07-1 2019-10-0 2019-08-0 2019-11-0 2019-08-2 2020-05-0 2020-09-0 uvellement contrat 2 du spé IDA / 60230 Post Direct 40,542.96 Completed 2019-09-04 port tant Selection 1 4 5 5 5 9 1 7 5 cialiste en suivi-evaluation PRISP-161-C-CI-19 / Consult ant individuel international Strengthening Revenue Mo Individual Consul 2019-09-0 2019-11-0 2019-09-0 2019-11-3 2019-09-1 2020-01-0 2019-09-3 2020-07-0 2021-04-2 pour la revue de la politique IDA / 60230 bilization and Public Expen Post Direct 98,560.00 Completed 2019-10-30 tant Selection 5 9 6 0 0 4 0 2 9 s fiscale des regimes d exe diture Management mption (impots et douanes) Phase 2:BIRERE Yves PRISP-162-C-CI-19 / Consult ant individuel international Project Implementation Sup Individual Consul 2019-09-0 2019-10-0 2019-09-1 2019-10-2 2019-09-3 2019-11-3 2019-09-3 2020-05-2 2020-12-0 IDA / 60230 Post Limited 169,964.68 Completed 2019-09-30 en charge de l appui techniq port tant Selection 5 5 9 6 0 0 0 8 1 ue aux activités des réforme s du secteur public PRISP-163-C-CI-19 / Consult ant individuel international Improving Transparency an Individual Consul 2019-09-0 2019-11-0 2019-11-0 2019-11-2 2019-11-1 2019-12-3 2019-11-1 2020-06-2 2020-11-1 IDA / 60230 Post Limited 159,550.00 Completed 2019-10-31 en charge de la formation IN d Accountability tant Selection 6 5 7 6 3 1 5 8 7 TOSSAI au profit de l IGF PRISP-164-C-CI-19 / Consult Strengthening Revenue Mo ant individuel international Individual Consul 2019-09-0 2019-11-0 2019-11-2 2019-11-2 2019-10-0 2019-12-3 2019-11-3 2020-06-2 IDA / 60230 bilization and Public Expen Post Limited 164,183.42 Signed 2019-10-30 pour la mise en oeuvre des tant Selection 5 4 7 5 8 0 0 7 diture Management recommandations issues de l'audit fiscal forestier PRISP-170-C-CI-19 / consult ant individuel international Modernization of the Public Individual Consul 2019-09-0 2019-11-0 2019-10-2 2019-11-2 2019-10-2 2019-12-3 2019-10-2 2020-06-2 2021-01-0 IDA / 60230 Post Limited 154,765.42 Completed 2019-10-31 chargé de la mise en oeuvre Administration tant Selection 5 5 1 6 1 1 6 8 1 du plan de formation de la f onction publique PRISP-173-C-CI-19 / consult ant individuel international Project Implementation Sup Individual Consul 2019-09-0 2019-12-0 2020-09-0 2019-12-2 2020-09-1 2020-01-2 2020-10-1 2020-07-2 2021-03-2 IDA / 60230 Post Limited 29,413.16 Completed 2019-11-29 chargé de l elaboration du p port tant Selection 5 4 3 5 7 9 0 7 6 lan de formation des OSC PRISP-174-C-CI-19 / Consult ant individuel International Improving Transparency an Individual Consul 2019-12-2 2020-01-0 2020-03-2 2020-01-3 2020-05-1 2020-03-0 2020-05-1 2020-09-0 2020-11-0 chargé d’appuyer la mise en IDA / 60230 Post Direct 107,120.00 Completed 2019-12-30 d Accountability tant Selection 7 9 0 0 2 5 4 1 8 œuvre de la redevabilité de l’engagement citoyen:Phase 2- NIYONKURU Evariste PRISP-175-CI-C-19 / Renouv Project Implementation Sup Individual Consul 2019-11-0 2019-11-2 2019-11-0 2019-12-1 2019-11-0 2020-01-2 2019-11-0 2020-07-1 2020-11-1 ellement du contrat du Plant IDA / 60230 Post Direct 4,054.30 Completed 2019-11-15 port tant Selection 4 5 5 6 6 0 6 8 4 on du PRISP: NGAMOKOBA Ghislain Aymar PRISP-176-C-CI-19 / Renouv Project Implementation Sup Individual Consul 2019-11-0 2019-11-2 2019-11-0 2019-12-1 2019-11-0 2020-01-2 2019-11-0 2020-07-1 2020-11-1 ellement contrat Chauffeur IDA / 60230 Post Direct 6,148.94 Completed 2019-11-15 port tant Selection 4 5 5 6 6 0 7 8 5 coursier: AKOLI IBOMBO Jea n Sylvain PRISP-177-C-CI-19 / Renouv Project Implementation Sup Individual Consul 2019-12-1 2019-12-2 2019-12-0 2020-01-1 2019-12-1 2020-02-1 2019-12-1 2020-08-1 2020-12-1 ellement contrat Assistant d IDA / 60230 Post Direct 16,397.18 Completed 2019-12-11 port tant Selection 0 1 6 1 0 5 0 3 0 e direction PRISP: BATSOTS A MAKOLA Yvon Page 7 PRISP-178-C-CI-19 / Renouv Project Implementation Sup Individual Consul 2019-12-1 2019-12-2 2019-12-0 2020-01-1 2019-12-1 2020-02-1 2019-12-1 2020-08-1 2020-12-1 ellement contrat Trésorière IDA / 60230 Post Direct 20,361.12 Completed 2019-12-12 port tant Selection 0 2 6 2 0 6 1 4 1 PRISP: FOUNGUI OTOUNGO U Léa Prisca PRISP- 179-C-CI-19 / Renou vellement contrat Assistant Project Implementation Sup Individual Consul 2019-12-1 2019-12-2 2019-12-0 2020-01-1 2019-12-1 2020-02-1 2019-12-1 2020-08-1 2020-12-1 IDA / 60230 Post Direct 20,496.48 Completed 2019-12-11 en passation des marchés: port tant Selection 0 1 6 1 0 5 1 3 1 NDALA NKENDA Grâce Child éric PRISP-188-C-CI-19 / Recrute ment consultant national ch Strengthening Revenue Mo argé des EIES dans le cadre Individual Consul 2019-11-2 2019-12-2 2020-01-2 2020-01-1 2020-01-2 2020-02-1 2020-01-3 2020-08-1 2020-03-3 IDA / 60230 bilization and Public Expen Post Limited 9,268.44 Completed 2019-12-16 du projet de raccordement tant Selection 7 1 3 1 9 5 0 3 1 diture Management des centres des impôts à tra vers le backbone de fibre op tique inter-administration (F IA) PRISP-182-C-CI-19 / Recrute ment d'un consultant nation Strengthening Revenue Mo al homologue pour revue de Individual Consul 2019-11-2 2019-12-2 2020-01-1 2020-02-1 2020-08-1 IDA / 60230 bilization and Public Expen Post Limited 0.00 Canceled 2019-12-17 la politique fiscale: Etude su tant Selection 7 2 2 6 4 diture Management r les dépenses fiscales des r égimes d’exemption (impots et douanes) PRISP-183-C-CI-19 / Consult ant national chargé de l'App Strengthening Revenue Mo ui à la mise en œuvre des re Individual Consul 2019-11-2 2019-12-2 2020-01-1 2020-01-1 2020-01-2 2020-02-1 2020-01-2 2020-08-1 IDA / 60230 bilization and Public Expen Post Limited 55,525.14 Signed 2019-12-16 commandations issues de l' tant Selection 7 1 0 1 0 5 2 3 diture Management audit du secteur forestier po ur la Direction Générale des Impôts et des Domaines (D GID) PRISP-184-C-CI-19 / Consult ant national chargé de l'App Strengthening Revenue Mo ui à la mise en œuvre des re Individual Consul 2019-11-2 2019-12-2 2020-01-1 2020-01-1 2020-01-2 2020-02-1 2020-01-2 2020-08-1 IDA / 60230 bilization and Public Expen Post Limited 55,525.14 Signed 2019-12-17 commandations issues de l' tant Selection 7 2 0 2 0 6 2 4 diture Management audit du secteur forestier po ur le compte du ministère d e l'économie forestière PRISP-165-C-CI-19 / Consult ant individuel international Strengthening Revenue Mo chargé de la mise en oeuvr Individual Consul 2019-11-0 2019-11-2 2019-12-3 2020-06-2 IDA / 60230 bilization and Public Expen Post Limited 0.00 Canceled 2019-10-30 e des recommandations issu tant Selection 4 5 0 7 diture Management es de l'analyse diagnostique sur la mobilisation des impô ts fonciers PRISP-166-C-CI-19 / consult ant individuel international Modernization of the Public Individual Consul 2019-11-0 2019-11-2 2019-12-3 2020-06-2 chargé de la mise en oeuvre IDA / 60230 Post Limited 0.00 Canceled 2019-10-31 Administration tant Selection 5 6 1 8 des recommandations issue s de l audit institutionnel de la fonction publique PRISP-167-C-CI-19 / consult ant individuel international Improving Transparency an Individual Consul 2019-11-0 2019-11-2 2019-12-3 2020-06-2 IDA / 60230 Post Limited 0.00 Canceled 2019-10-31 chargé de la mise en oeuvr d Accountability tant Selection 5 6 1 8 e du plan de formation de la CCDB PRISP-171-C-CI-19 / consult Strengthening Revenue Mo ant individuel international Individual Consul 2019-11-0 2019-11-3 2020-01-0 2020-07-0 IDA / 60230 bilization and Public Expen Post Limited 0.00 Canceled 2019-11-04 chargé de la mise en oeuvre tant Selection 9 0 4 2 diture Management du plan de formation de la D GDDI PRISP-172-C-CI-19 / consult Strengthening Revenue Mo ant individuel international Individual Consul 2019-12-0 2019-12-2 2020-01-2 2020-07-2 IDA / 60230 bilization and Public Expen Post Limited 0.00 Canceled 2019-11-29 chargé de la mise en oeuvre tant Selection 4 5 9 7 diture Management du plan de formation de la D GPD PRISP-169-C-CI-19 / consult ant individuel international Improving Transparency an Individual Consul 2019-11-0 2019-11-2 2019-12-3 2020-06-2 IDA / 60230 Post Limited 0.00 Canceled 2019-10-31 chargé de la mise en oeuvre d Accountability tant Selection 5 6 1 8 du plan de formation des EC OFIN du Parlement PRISP-168-C-CI-19 / consult ant individuel international Improving Transparency an Individual Consul 2019-11-0 2019-11-2 2019-12-3 2020-06-2 IDA / 60230 Post Limited 0.00 Canceled 2019-10-31 chargé de la mise en oeuvre d Accountability tant Selection 5 6 1 8 du plan de formation de l IG F PRISP-136-C-CI-19 / Recrute ment d un consultant indivi Improving Transparency an Individual Consul 2019-08-1 2019-09-0 2019-10-1 2020-04-0 duel pour l etde de faisabilit IDA / 60230 Post Open 0.00 Canceled 2019-06-28 d Accountability tant Selection 6 6 1 8 e du projet de creation de la fonction publique parlement aire PRISP-121-C-CI-19 / Recrute ment d un consultant indivi Strengthening Revenue Mo Individual Consul 2019-06-1 2019-07-0 2019-08-1 2020-02-0 duel international pour la re IDA / 60230 bilization and Public Expen Post Open 0.00 Canceled 2019-04-30 tant Selection 8 9 3 9 daction des normes compta diture Management bles publiques specifiques a u Congo au profit de la DGC P PRISP-123-C-CI-19 / Recrute ment d un consultant indivi Strengthening Revenue Mo Individual Consul 2019-08-1 2019-09-0 2019-10-1 2020-04-0 duel international charge de IDA / 60230 bilization and Public Expen Post Open 0.00 Canceled 2019-06-28 tant Selection 6 6 1 8 l elaboration d un plan de fo diture Management rmation au profit de la DGC P PRISP-191-C-CI-2020 / Recr utement d'un consultant ind ividuel international 1 en ch Strengthening Revenue Mo Individual Consul 2020-02-0 2020-02-0 2020-07-0 2020-02-2 2020-07-1 2020-04-0 2020-07-2 2020-09-2 2020-10-2 arge de l'évaluation des offr IDA / 60230 bilization and Public Expen Post Limited 7,639.80 Completed 2020-01-31 tant Selection 3 5 2 6 7 1 1 8 7 es relatives au raccordemen diture Management t des centres des impôts à t ravers le Backbone de Fibre Optique Inter-administration (FIA) PRISP-192-C-CI-2020 / Recr utement du consultant indiv iduel international 2 en char Strengthening Revenue Mo Individual Consul 2020-02-0 2020-02-0 2020-10-0 2020-02-2 2020-10-0 2020-04-0 2020-10-1 2020-09-2 ge de l'évaluation des offres IDA / 60230 bilization and Public Expen Post Limited 7,656.97 Signed 2020-01-31 tant Selection 3 5 9 6 9 1 3 8 relatives au raccordement diture Management des centres des impôts à tra vers le Backbone de Fibre O ptique Inter-administration ( FIA). PRISP-193-C-CI-2020 / Recr utement du consultant indiv Strengthening Revenue Mo Individual Consul 2020-02-0 2020-02-2 2020-04-0 2020-09-2 iduel international en charg IDA / 60230 bilization and Public Expen Post Limited 0.00 Canceled 2020-01-31 tant Selection 5 6 1 8 e de l' évaluation des offres diture Management relatives à la mise à jour du datacenter de Brazzaville PRISP-189-C-CI-2020 / Reno uvellement du contrat du ch Project Implementation Sup Individual Consul 2020-02-1 2020-02-1 2020-03-0 2020-03-0 2020-03-1 2020-04-0 2020-03-1 2020-10-0 2021-01-0 IDA / 60230 Post Direct 32,356.80 Completed 2020-01-31 argé de de la communicatio port tant Selection 0 0 6 2 0 6 2 3 1 n du PRISP: NTI Raymond PRISP-190-C-CI-2020 / Reno uvellement du contrat du co Project Implementation Sup Individual Consul 2020-01-3 2020-02-1 2020-03-2 2020-03-0 2020-03-3 2020-04-0 2020-04-0 2020-10-0 2021-01-0 IDA / 60230 Post Direct 10,773.24 Completed 2020-01-31 nsultant national en informa port tant Selection 1 0 7 2 1 6 2 3 1 tique du PRISP: EBALE Ghisl ain PRISP-087-C-CI-18 / Consult ant Individuel international Modernization of the Public Individual Consul 2019-03-0 2019-03-2 2019-05-0 2019-10-2 pour l'évaluation des besoin IDA / 60230 Post Open 0.00 Canceled 2019-01-17 Administration tant Selection 7 8 2 9 s de l'ENAM en vue du dével oppement de la formation d es auditeurs PRISP-104-C-CI-19 / Consult Strengthening Revenue Mo Individual Consul 2019-06-1 2019-07-0 2019-08-1 2020-02-0 ant charge etude mise en o IDA / 60230 bilization and Public Expen Post Open 0.00 Canceled 2019-04-30 tant Selection 8 9 3 9 euvre infrastructure cloud diture Management PRISP-074-C-CI-18 / Consult ant Individuel international Strengthening Revenue Mo Individual Consul 2018-12-2 2019-03-2 2019-04-1 2019-05-1 2019-11-1 pour la mise en place d'un s IDA / 60230 bilization and Public Expen Post Open 0.00 Canceled 2019-01-30 tant Selection 7 0 0 5 1 ystème de gestion des inve diture Management ntaires et maintenance infor matique à la DSI finances PRISP-194-C-CI-20 / Recrute ment d'un consultant nation Improving Transparency an Individual Consul 2020-03-1 2020-05-1 2020-03-2 2020-05-3 2020-03-3 2020-07-0 2020-04-0 2021-01-0 al homologue en charge de IDA / 60230 Post Direct 33,255.60 Signed 2020-04-30 d Accountability tant Selection 8 0 0 1 0 5 1 1 la redevabilité et de l'engag ement (phase 2): BAKINDISS A Josephine PRISP-127-C-CI-19 / Recrute ment d un consultant indivi duel international charge de Modernization of the Public Individual Consul 2019-08-2 2019-10-1 2019-11-0 2019-12-1 2020-06-1 l emaboration d une strtaegi IDA / 60230 Post Open 0.00 Canceled 2019-08-30 Administration tant Selection 0 8 8 3 0 e de communication de la re forme de l Etat au profit du ministere en charge de la fo nction publique PRISP-195-C-CI-20 / Recrute ment d'un consultant individ uel international en charge Project Implementation Sup Individual Consul 2020-03-2 2020-04-1 2020-03-2 2020-05-0 2020-03-2 2020-06-0 2020-04-0 2020-12-0 de la mise en place et l'opér IDA / 60230 Post Direct 115,884.00 Signed 2020-03-31 port tant Selection 3 0 0 1 5 5 2 2 ationnalisation de la cellule de suivi en matière de gouv ernance (phase): ONGANAN A Maximilien PRISP-196-C-CI-20 / Renouv Project Implementation Sup Individual Consul 2020-03-2 2020-05-1 2020-03-3 2020-05-3 2020-04-0 2020-07-0 2020-04-1 2021-01-0 2021-01-0 ellement 2 contrat du Comp IDA / 60230 Post Direct 30,245.88 Completed 2020-04-30 port tant Selection 3 0 0 1 2 5 5 1 1 table du PRISP: Madame IBA TA Lydie PRISP-120-C-CI-19 / Recrute ment d un consultant indivi Strengthening Revenue Mo Individual Consul 2019-05-2 2020-01-1 2020-02-0 2020-03-1 2020-09-0 duel international pour l ope IDA / 60230 bilization and Public Expen Post Open 0.00 Canceled 2019-11-28 tant Selection 7 6 6 2 8 rationnalisation des procedu diture Management res d execution des recette s au profit de la DGCP PRISP-116-C-CI-19 / Recrute Strengthening Revenue Mo ment consultant individuel i Individual Consul 2019-07-2 2019-08-1 2019-09-0 2019-10-1 2020-04-0 IDA / 60230 bilization and Public Expen Post Open 0.00 Canceled 2019-06-27 nternational en charge de l tant Selection 5 5 5 0 7 diture Management etude sur l evaluation du po tentiel fiscal PRISP-118-C-CI-19 / Recrute ment d un consultant indivi Strengthening Revenue Mo duel international pour l ela Individual Consul 2019-09-1 2019-10-0 2019-11-1 2020-05-1 IDA / 60230 bilization and Public Expen Post Open 0.00 Canceled 2019-07-31 boration d un plan directeur tant Selection 8 9 3 1 diture Management de l organisation generale d u systeme de comptabilite p ublique a la DGCP PRISP-072-C-CI-18 / Consult ant Individuel international Project Implementation Sup Individual Consul 2018-12-2 2019-01-0 2019-01-2 2019-03-0 2019-08-2 IDA / 60230 Post Limited 0.00 Canceled 2018-12-31 en suic=vi-évaluation charg port tant Selection 7 5 6 2 9 é d'accompagner le PRISP Page 8 PRISP-198- C-CI-20 / Renou vellement 2 contrat de EBA Project Implementation Sup Individual Consul 2020-09-0 2020-09-2 2020-03-2 2020-10-1 2020-03-3 2020-11-2 2020-04-0 2021-05-1 2020-07-0 LE Ghislain au poste de resp IDA / 60230 Post Direct 11,088.84 Completed 2020-09-15 port tant Selection 3 5 7 6 1 0 2 9 1 onsable informatique au sei n du PRISP par entente direc te PRISP-199-C-CI-20 / Recrute ment d'un consultant nation Improving Transparency an Individual Consul 2020-10-1 2020-09-2 2020-07-0 2020-10-1 2020-07-1 2020-11-2 2020-08-0 2021-05-2 2020-10-0 al chargé de la mise en plac IDA / 60230 Post Limited 26,868.00 Completed 2020-09-21 d Accountability tant Selection 9 6 2 7 6 1 4 0 9 e du site Web de la cour des comptes et de discipline bu dgétaire PRISP-200-C-CI-20 / Renouv ellement 2 contrat de mada Project Implementation Sup Individual Consul 2020-10-1 2020-09-2 2020-03-3 2020-10-1 2020-04-0 2020-11-2 2020-04-1 2021-05-1 2021-01-0 IDA / 60230 Post Direct 30,140.88 Completed 2020-09-15 me IBATA Lydie au poste de port tant Selection 9 5 0 6 2 0 5 9 1 comptable au sein du PRISP par entente directe PRISP-201-C-ED-20 / recrut ement du cabinet AMBRE AS SOCIATES pour l'assistance Project Implementation Sup 2020-10-1 2020-09-1 2020-05-0 2020-11-2 2020-07-1 2021-05-2 au renforcement du systèm IDA / 60230 Post Direct Selection Direct 96,868.23 Signed 2020-09-07 port 9 7 6 1 7 0 e de suivi-évaluation et à l'a ppropriation du système Th émis auprès de l'UCP, par e ntente directe PRISP-202-C-CI-20 / Renouv ellement 2 contrat de mada Project Implementation Sup Individual Consul 2020-10-1 2020-09-1 2020-05-2 2020-10-0 2020-05-2 2020-11-0 2020-06-1 2021-05-0 2021-01-0 me LEWO MASSAMBA Aleda IDA / 60230 Post Direct 48,000.00 Completed 2020-08-31 port tant Selection 9 0 2 1 9 5 3 4 1 au poste d'auditeur interne au sein du PRISP par entent e directe PRISP-203-C-CI-20 / Recrute ment consultant national po Improving Transparency an Individual Consul 2020-10-1 2020-09-0 2020-11-1 2020-09-2 2020-11-2 2020-10-2 2020-12-0 2021-04-2 2022-02-0 ur appuyer l'inspection géné IDA / 60230 Post Limited 31,748.86 Completed 2020-08-28 d Accountability tant Selection 9 2 1 3 6 8 1 6 1 rale dans la mise en oeuvre de son plan de formation PRISP-209-C-CI-20 / Renouv ellement 3 contrat de MAKA Project Implementation Sup Individual Consul 2020-10-1 2020-09-0 2020-06-1 2020-09-2 2020-06-1 2020-11-0 2020-08-2 2021-05-0 IDA / 60230 Post Direct 22,422.84 Signed 2020-08-28 MBALA MATHURIN au poste port tant Selection 9 7 7 8 7 2 0 1 de spécialiste en passation des marchés du PRISP PRISP-2010-C-CI-20 / Renou vellement 3 contrat de MOU ANDA MINGOUOLO Francis Project Implementation Sup Individual Consul 2020-08-1 2020-09-0 2020-06-1 2020-09-2 2020-06-1 2020-11-0 2020-08-1 2021-05-0 2021-01-0 IDA / 60230 Post Direct 44,845.68 Completed 2020-08-28 Borel au poste de responsab port tant Selection 9 7 7 8 7 2 9 1 1 le administratif financier et comptable du PRISP par ent ente directe PRISP-211-C-CI-20 / Renouv ellement 3 du contrat de mo Project Implementation Sup Individual Consul 2020-08-1 2020-09-0 2020-08-1 2020-09-2 2020-08-1 2020-11-0 2020-08-2 2021-05-0 2021-03-1 nsieur NGOULOU JEAN NOEL IDA / 60230 Post Direct 27,572.25 Completed 2020-08-28 port tant Selection 1 7 4 8 7 2 1 1 0 au poste de coordonnateur du PRISP par entente direct e PRISP-212-C-CI-20 / Recrute ment consultant individuel i Modernization of the Public Individual Consul 2020-10-1 2020-10-0 2020-10-2 2020-11-3 2021-05-2 nternational pour l'appui à l IDA / 60230 Post Limited 0.00 Canceled 2020-09-30 Administration tant Selection 9 5 6 0 9 a mise en oeuvre des recom mandations de l'audit institu tionnel de la fonction publiq ue PRISP-213-C-CI-20 / Recrute ment consultant individuel i Strengthening Revenue Mo nternational chargé de la mi Individual Consul 2020-05-2 2020-10-0 2020-11-0 2020-10-2 2020-11-2 2020-12-0 2020-12-0 2021-05-3 IDA / 60230 bilization and Public Expen Post Limited 65,047.81 Signed 2020-10-01 se en place du système de g tant Selection 8 6 2 7 3 1 5 0 diture Management estion électronique des doc uments du ministère en cha rge du plan PRISP-214-CI-ED-20 / Recru tement consultant individuel Strengthening Revenue Mo international phase 2 de l'ét Individual Consul 2020-05-2 2020-09-1 2020-05-2 2020-10-0 2020-06-0 2020-11-0 2020-07-1 2021-05-0 IDA / 60230 bilization and Public Expen Post Direct 42,147.83 Signed 2020-08-31 ude, dimensionnement et ac tant Selection 6 0 9 1 9 5 8 4 diture Management quisition du système solaire à Ponte-Noire: WILONDJA DE PUTE, par entente directe PRISP-215-C-ED-20 / Recrut ement par entente directe d u cabinet GLOBAL CHALLEN Modernization of the Public 2020-05-2 2020-10-1 2020-05-2 2020-12-2 2020-06-0 2021-06-1 2020-12-3 IDA / 60230 Post Direct Selection Direct 109,569.16 Completed 2020-10-06 GE CORPORATION pour la re Administration 7 6 7 0 3 8 0 vue du cadre légal et régle mentaire de la fonction publ ique: phase 2 PRISP-216-CI-ED-20 / Recru tement par entente directe de BOBASSA-EBALE Pascal e Project Implementation Sup Individual Consul 2020-03-1 2020-10-1 2020-03-2 2020-10-3 2020-03-3 2020-12-0 2020-04-0 2021-06-0 n qualité de Consultant nati IDA / 60230 Post Direct 54,026.40 Signed 2020-09-30 port tant Selection 8 0 0 1 0 5 1 3 onal chargé de l’opérationn alisation de la cellule de sui vi de la réforme en matière de gouvernance en Républi que du Congo PRISP-217-CI-ED-20 / Renou vellement 2 contrat de FOU Project Implementation Sup Individual Consul 2020-10-1 2020-12-1 2020-11-0 2020-12-3 2020-11-0 2021-02-0 2020-11-1 2021-08-0 2021-01-0 NGUI OTOUNGOU Léa Prisca IDA / 60230 Post Direct 22,248.96 Completed 2020-11-30 port tant Selection 9 0 3 1 4 4 4 3 1 au poste de Trésorière au se in de l'UCP par entente dire cte PRISP-218-CI-ED-20 / Renou vellement 2 contrat de NGA Project Implementation Sup Individual Consul 2020-10-1 2020-10-2 2020-11-0 2020-11-1 2020-11-0 2020-12-2 2020-11-1 2021-06-1 2021-01-0 IDA / 60230 Post Direct 4,449.79 Completed 2020-10-15 MOKOBA Ghislain Aymar au port tant Selection 9 5 3 5 4 0 4 8 1 poste de planton par entent e directe PRISP-219-CI-ED-20 / Renou vellement 2 contrat AKOLI I Project Implementation Sup Individual Consul 2020-10-2 2020-10-2 2020-11-0 2020-11-1 2020-11-0 2020-12-2 2020-11-1 2021-06-1 2021-01-0 IDA / 60230 Post Direct 6,674.69 Completed 2020-10-15 BOMBO Jean Sylvain au post port tant Selection 0 5 3 5 4 0 4 8 1 e de chauffeur par entente directe PRISP-220-CI-ED-20 / Renou vellement 2 contrat de BATS Project Implementation Sup Individual Consul 2020-10-2 2020-11-1 2020-11-0 2020-12-0 2020-11-0 2021-01-1 2020-11-1 2021-07-1 2021-01-0 OTSA MAKOLA Yvon Claver IDA / 60230 Post Direct 17,799.17 Completed 2020-11-06 port tant Selection 0 6 3 7 4 1 4 0 1 au poste d'assistant adminis tratif au sein de l'UCP par e ntente directe PRISP-221-CI-ED-20 / Renou vellement 2 contrat de NDA Project Implementation Sup Individual Consul 2020-11-2 2020-11-1 2020-11-3 2020-12-1 2020-12-0 2021-01-1 2020-12-0 2021-07-1 2021-01-0 LA NKENDA Grâce Childéric IDA / 60230 Post Direct 21,465.12 Completed 2020-11-09 port tant Selection 3 9 0 0 1 4 5 3 1 au poste d'assistant en pas sation des marchés par ente nte directe au sein du PRISP PRISP-222-C-CI-20 / Recrute ment d’un consultant nation al chargé de la formation su Modernization of the Public Individual Consul 2020-10-1 2020-10-2 2020-12-1 2020-11-1 2021-02-1 2020-12-1 2021-02-1 2021-06-1 2021-09-2 r l’élaboration des fiches d’a IDA / 60230 Post Limited 4,142.37 Completed 2020-10-15 Administration tant Selection 9 0 1 0 7 5 8 3 8 nalyse, de synthèse et des n otes de présentation aux ag ents et cadres du cabinet du ministre en charge de la fon ction publique PRISP-229-C-CI-20 / Recrute ment d’un consultant indivi duel international chargé de Strengthening Revenue Mo la mise en œuvre des recom Individual Consul 2020-10-0 2020-10-2 2020-11-3 2021-05-2 IDA / 60230 bilization and Public Expen Post Limited 0.00 Canceled 2020-09-30 mandations issues du rappo tant Selection 5 6 0 9 diture Management rt final du schéma directeur informatique du ministère d u plan, de la statistique et d e l’intégration régionale PRISP-181-C-CI-19 / Recrute ment d'un secrétaire perma Project Implementation Sup Individual Consul 2020-03-1 2020-02-1 2020-03-1 2020-04-1 2020-10-1 IDA / 60230 Post Open 0.00 Canceled 2019-12-31 nent de la cellule des réfor port tant Selection 8 8 0 4 1 mes pour la gouvernance so ciale PRISP-97 BIS-C-CI-2019 / Re Project Implementation Sup Individual Consul 2019-08-1 2019-08-3 2019-10-0 2020-04-0 gularisation du contrat reno IDA / 60230 Post Direct 0.00 Canceled 2019-07-31 port tant Selection 0 1 5 2 uvele du specialiste en pass ation des marches PRISP-208-C-CI-20 / Renouv ellement 3 contrat de monsi Project Implementation Sup Individual Consul 2020-10-1 2020-09-0 2020-06-1 2020-09-2 2020-06-1 2020-11-0 2020-08-2 2021-05-0 2021-01-0 eur KEHOUA André au poste IDA / 60230 Post Direct 22,422.84 Completed 2020-08-28 port tant Selection 9 7 7 8 7 2 0 1 1 de spécialiste en suivi-évalu ation au sein du PRISP par e ntente directe PRISP-228-C-CI-20 / Recrute ment par entente directe du Strengthening Revenue Mo 2020-09-0 2020-12-2 2020-09-0 2021-02-2 2020-09-0 2021-08-2 2020-10-1 consultant individuel interna IDA / 60230 bilization and Public Expen Post Direct Selection Direct 27,003.69 Completed 2020-12-10 3 0 3 3 8 2 7 tional FONIN Jerôme pour l'é diture Management valuation du dispositif E-Tax PRISP-232-C-CI-20 / Recrute ment du consultant individ uel international chargé de l Improving Transparency an Individual Consul 2020-10-1 2020-12-2 2021-01-1 2021-02-1 2021-08-1 IDA / 60230 Post Limited 0.00 Canceled 2020-12-15 'appui à la mise en oeuvre d d Accountability tant Selection 3 0 0 4 3 es recommandations issues du guide méthodologie d'au dit au profit de l'IGF PRISP-233-C-CI-20 / Recrute ment du consultant individu Improving Transparency an Individual Consul 2020-10-1 2021-01-0 2021-01-2 2021-02-2 2021-08-2 el international pour l'appui IDA / 60230 Post Limited 0.00 Canceled 2020-12-28 d Accountability tant Selection 3 2 3 7 6 à la mise en oeuvre des rec ommandations issues de l'a udit institutionnel de l'ENAM PRISP-234- C-CI-20 / Recrut ement d'un consultant natio nal en charge de l'étude et s Improving Transparency an Individual Consul 2020-10-1 2021-01-0 2021-01-2 2021-03-0 2021-08-2 IDA / 60230 Post Limited 0.00 Canceled 2020-12-31 urveillance des travaux pour d Accountability tant Selection 3 5 6 2 9 la réhabilitation d'un local d e formation au niveau de l'E NAM PRISP-230-C-CI-20 / Recrute ment d'un consultant nation Modernization of the Public Individual Consul 2020-10-1 2020-12-0 2020-12-0 2020-12-2 2020-12-2 2021-01-3 2020-12-2 2021-07-2 2021-07-3 al chargé de l'étude et la ré IDA / 60230 Post Limited 27,002.85 Completed 2020-11-30 Administration tant Selection 9 5 7 6 2 0 5 9 1 alisation du portail Web du ministère en charge de la fo nction publique PRISP-236-C-CI-20 / Recrute ment du consultant national Project Implementation Sup Individual Consul 2020-10-1 2020-10-0 2020-11-0 2020-10-2 2020-11-0 2020-11-3 2020-11-0 2021-05-2 2021-11-0 homologue chargé de l'opér IDA / 60230 Post Limited 53,969.10 Completed 2020-09-30 port tant Selection 3 5 3 6 3 0 5 9 4 ationnalisation de la cellule de suivi des réformes en ma tière de gouvernance PRISP-237-C-CI-20 / Recrute ment du consultant expert n Project Implementation Sup Individual Consul 2020-10-1 2020-10-0 2020-11-0 2020-10-2 2020-11-0 2020-11-3 2020-11-0 2021-05-2 ational chargé de la réforme IDA / 60230 Post Limited 32,381.46 Signed 2020-09-30 port tant Selection 3 5 3 6 3 0 5 9 de l'Etat au sein de la cellul e des réformes en matière d e gouvernance Page 9 PRISP-239-C-CI-20 / Recrute ment du consultant individu Project Implementation Sup Individual Consul 2020-10-1 2020-10-0 2020-10-0 2020-10-2 2020-10-2 2020-11-2 2020-10-2 2021-05-2 2021-03-2 el international chargé de la IDA / 60230 Post Limited 79,479.45 Completed 2020-09-28 port tant Selection 9 3 6 4 1 8 2 7 3 mise en oeuvre des recomm andations du schéma direct eur PRISP-240-C-CI-20 / Recrute ment du consultant individu el international chargé de l' Modernization of the Public Individual Consul 2020-08-3 2020-10-1 2020-12-1 2020-11-0 2020-12-2 2020-12-1 2020-12-2 2021-06-1 2021-03-2 étude pour la mise en place IDA / 60230 Post Limited 20,396.64 Completed 2020-10-12 Administration tant Selection 1 7 6 7 4 2 5 0 7 du système de gestion élect ronique des documents du ministère en charge de la fo nction publique PRISP-238-C-CI-20 / Recrute ment d'un consultant indivi duel international chargé de Strengthening Revenue Mo Individual Consul 2020-10-0 2020-10-2 2020-11-2 2021-05-2 la mise en place d’un systè IDA / 60230 bilization and Public Expen Post Limited 0.00 Canceled 2020-09-29 tant Selection 4 5 9 8 me intégré de gestion électr diture Management onique de documents et d’a rchivage du ministère en ch arge du plan. PRISP-249-C-CI-20 / Recrute ment consultant individuel i nternational pour le dévelop Modernization of the Public Individual Consul 2020-12-0 2020-12-2 2021-01-3 2021-07-2 pement d'un programme de IDA / 60230 Post Limited 0.00 Canceled 2020-11-30 Administration tant Selection 5 6 0 9 formation en passation des marchés en faveur des acte urs impliqués dans les marc hés publics PRISP-250-C-CI-20 / Recrute ment consultant individuel i Modernization of the Public Individual Consul 2020-12-0 2020-12-2 2021-01-3 2021-07-2 nternational pour l'appui à l' IDA / 60230 Post Limited 0.00 Canceled 2020-11-30 Administration tant Selection 5 6 0 9 élaboration des supports de formation sur les marchés p ublics PRISP-251-C-CI-20 / Recrute ment consultant individuel i nternational en charge de la Modernization of the Public Individual Consul 2020-12-0 2020-12-2 2021-01-2 2021-07-2 IDA / 60230 Post Limited 0.00 Canceled 2020-11-27 structuration et la renforce Administration tant Selection 2 3 7 6 ment des CGMP au niveau d es autorités contractantes e t des organes de contrôle PRISP-252-C-CI-20 / Recrute ment consultant individuel i nternational pour l'appui à l Modernization of the Public Individual Consul 2020-12-0 2020-12-2 2021-01-3 2021-07-2 a mise en place d'un systèm IDA / 60230 Post Limited 0.00 Canceled 2020-11-30 Administration tant Selection 5 6 0 9 e de collecte et de traiteme nt des informations statistiq ues des marchés publics (A RMP,DGCMP,DGGT,CGMP,M PSIR) PRISP-247-C-CI-20 / Recrute ment consultant individuel i nternational chargé de la c Improving Transparency an Individual Consul 2020-12-2 2021-01-1 2021-02-2 2021-08-2 IDA / 60230 Post Limited 0.00 Canceled 2020-12-22 onception et mise en place d Accountability tant Selection 7 7 1 0 d'un système de gestion éle ctronique des documents de la CCDB PRISP-253-C-CI-2020 / Recr Project Implementation Sup Individual Consul 2020-12-0 2021-01-0 2020-09-2 2021-01-2 2020-09-3 2021-02-2 2020-10-0 2021-08-2 2021-01-0 utement d un informaticien IDA / 60230 Post Limited 11,088.84 Completed 2020-12-28 port tant Selection 1 2 5 3 0 7 2 6 1 au sein de l unité de coordin ation du PRISP PRISP-254-C-CI-21 / Renouv ellement du contrat de mon sieur MBOUNGOU Jean-de-D ieu expert national chargé d Project Implementation Sup 2021-02-1 2021-02-0 2021-01-0 2021-04-1 2021-01-1 2021-10-1 u suivi de la réforme des en IDA / 60230 Post Direct Selection Direct 32,319.72 Signed 2021-01-29 port 0 8 7 4 2 1 treprises publiques au sein de la cellule de suivi de la ré forme en matière de gouver nance en République du Co ngo par entente directe PRISP-255-C-CI-21 / Renouv ellement du contrat de mon sieur KABA MBOUALA exper t national chargé du suivi de Project Implementation Sup 2021-02-1 2021-02-0 2021-01-0 2021-04-1 2021-01-1 2021-10-1 IDA / 60230 Post Direct Selection Direct 32,319.72 Signed 2021-01-29 la réforme des finances publ port 0 8 7 4 2 1 iques au sein de la cellule d e suivi de la réforme en mat ière de gouvernance en Rép ublique du Congo, par enten te directe PRISP-256-C-CI-21 / Renouv ellement du contrat de mad ame LEGERNARD Sylvie exp ert national chargé du suivi Project Implementation Sup 2021-02-1 2021-03-2 2021-02-2 2021-05-2 2021-02-2 2021-11-2 IDA / 60230 Post Direct Selection Direct 32,319.72 Signed 2021-03-15 de la réforme des marchés port 0 5 2 9 4 5 publics au sein de la cellule de suivi de la réforme en m atière de gouvernance en R épublique du Congo, par ent ente PRISP-257-C-CI-21 / recrute ment d’un consultant intern ational pour l’assistance tec Project Implementation Sup 2021-02-1 2021-03-0 2021-05-1 2021-11-0 IDA / 60230 Post Direct Selection Direct 0.00 Canceled 2021-02-26 hnique dans le cadre de la r port 1 8 2 8 estructuration du Projet des Réformes Intégrées du Sect eur Publics (PRISP) PRISP-258-C-CI-21 / recrute ment d’un consultant nation al pour l’assistance techniqu Project Implementation Sup 2021-02-1 2021-03-0 2021-05-1 2021-11-0 IDA / 60230 Post Direct Selection Direct 0.00 Canceled 2021-02-26 e dans le cadre de la restruc port 1 8 2 8 turation du Projet des Réfor mes Intégrées du Secteur P ublics (PRISP) PRISP-257 BIS-C-CI-21 / Rec rutement de monsieur FON IN JEROME en qualité de con Project Implementation Sup 2021-02-1 2021-03-0 2021-02-1 2021-05-0 2021-02-1 2021-11-0 2021-09-0 sultant individuel internatio IDA / 60230 Post Direct Selection Direct 111,289.14 Completed 2021-02-22 port 2 4 2 8 3 4 3 nal pour l’assistance techniq ue dans le cadre de la restr ucturation du Projet des Réf ormes Intégrées du Secteur Publics (PRISP) PRISP-258 BIS-C-CI-21 / Rec rutement par entente direct e de monsieur OLLOY BERN ARD en qualité de consultan Project Implementation Sup 2021-02-1 2021-03-0 2021-02-1 2021-05-0 2021-02-1 2021-11-0 2021-07-0 IDA / 60230 Post Direct Selection Direct 41,316.45 Completed 2021-02-22 t national pour l’assistance t port 2 4 2 8 3 4 1 echnique dans le cadre de l a restructuration du Projet d es Réformes Intégrées du S ecteur Publics (PRISP) PRISP-260-C-ED-21 / Recrut Project Implementation Sup 2021-04-0 2021-05-1 2021-03-3 2021-07-1 2021-04-0 2022-01-1 2021-06-1 ement du cabinet ERNST & IDA / 60230 Post Direct Selection Direct 6,433.53 Completed 2021-04-30 port 1 0 0 4 9 0 6 YOUNG pour l'évaluation du personnel du PRISP PRISP-259-C-ED-21 / Recrut ement de monsieur Breitzer MOUNZEO par entente direc te en qualité de consultant Project Implementation Sup 2021-04-0 2021-06-1 2021-04-1 2021-08-1 2021-04-1 2022-02-1 2021-10-0 IDA / 60230 Post Direct Selection Direct 4,603.95 Completed 2021-05-31 national pour élaboration d’ port 1 0 2 4 8 0 8 un statut fiscal du personnel des Unités de Coordination ou de Gestion des Projets d u Congo financés par la Ban que Mondiale PRISP-261-C-ED-21 / Recrut ement de monsieur AKOND ZO Joseph en qualité de con sultant national pour la réda Project Implementation Sup 2021-04-0 2021-06-1 2021-04-1 2021-08-1 2021-04-1 2022-02-1 2021-10-1 IDA / 60230 Post Direct Selection Direct 4,603.95 Completed 2021-05-31 ction d’un règlement intérie port 1 0 2 4 4 0 2 ur devant régir le personnel chargé de la mise en œuvre des Projets financés par la B anque Mondiale en Républiq ue du CONGO PRISP-242-C-CI-20 / Recrute ment du consultant individu Strengthening Revenue Mo Individual Consul 2020-12-1 2020-12-0 2021-04-0 2020-12-2 2021-01-2 2021-07-2 el international chargé de l' IDA / 60230 bilization and Public Expen Post Limited 0.00 Canceled 2020-11-27 tant Selection 4 2 1 3 7 6 appui à la mise en oeuvre d diture Management u plan de formation pour la DGPP PRISP-243-C-CI-20 / Recrute ment consultant individuel i Strengthening Revenue Mo nternational en charge de la Individual Consul 2020-11-1 2020-11-2 2020-12-1 2021-01-2 2021-07-1 IDA / 60230 bilization and Public Expen Post Limited 0.00 Canceled 2020-11-20 formation de 15 ingénieurs tant Selection 2 5 6 0 9 diture Management du ministère en charge du p lan en administration systè me et réseaux PRISP-241-C-CI-20 / Recrute ment consultant individuel i Strengthening Revenue Mo nternational chargé de l'app Individual Consul 2021-02-1 2020-12-0 2020-12-2 2021-01-3 2021-07-2 IDA / 60230 bilization and Public Expen Post Limited 0.00 Canceled 2020-11-30 ui à la mise en oeuvre du pl tant Selection 2 5 6 0 9 diture Management an de formation pour la dire ction générale des douanes et des droits indirects PRISP-244-C-CI-20 / Recrute ment consultant individuel i Strengthening Revenue Mo nternational chargé de la for Individual Consul 2021-02-1 2020-12-1 2021-01-0 2021-02-0 2021-08-0 IDA / 60230 bilization and Public Expen Post Limited 0.00 Canceled 2020-12-10 mation de 20 cadres et age tant Selection 2 5 5 9 8 diture Management nts du ministère en charge du plan en matière de suivi- évaluation des projets et pr ogrammes PRISP-246-C-CI-20 / Recrute ment consultant national ch Project Implementation Sup Individual Consul 2020-12-1 2021-01-0 2021-02-0 2021-08-0 argé du renforcement du sit IDA / 60230 Post Limited 0.00 Canceled 2020-12-10 port tant Selection 5 5 9 8 e web de la Primature et hé bergement sur la durée de v ie du projet PRISP-265-C-ED-2021 / Rec rutement par entente direct e de madame Olivia RAKOT Project Implementation Sup 2021-05-0 2021-06-1 2021-05-0 2021-08-1 2021-05-1 2022-02-1 2021-08-3 IDA / 60230 Post Direct Selection Direct 9,000.00 Completed 2021-05-31 OMALALA pour l’appui à la port 3 0 7 4 1 0 1 mise en œuvre du projet de s réformes intégrées du sect eur public (PRISP) PRISP-278-C-CI-2021 / Recr utement du consultant natio nal en gestion des investiss Strengthening Revenue Mo ements publics pour appuye Individual Consul 2021-09-0 2021-10-1 2021-09-1 2021-11-0 2021-09-2 2021-12-1 2021-10-0 2022-06-1 IDA / 60230 bilization and Public Expen Post Limited 45,132.25 Signed 2021-10-12 r la mission d'assistance tec tant Selection 7 7 5 7 0 2 6 0 diture Management hnique pour la mise en œuv re du Plan d’Action triennal 2021-2023 de la réforme du système de Gestion des fina nces publiques Page 10 PRISP-270-C-ED-2021 / Rec rutement par entente direct e de monsieur MBOU LIKIBI Strengthening Revenue Mo Gaspard Symphorien en qua 2021-09-1 2021-10-1 2021-09-2 2021-12-1 2021-09-2 2022-06-1 2021-12-2 IDA / 60230 bilization and Public Expen Post Direct Selection Direct 11,432.20 Completed 2021-09-30 lité de consultant national, s 8 0 1 4 3 2 5 diture Management pécialiste en macroéconomi e pour l’évaluation du plan national de développement (PND) 2018-2022 PRISP-268-C-ED-2021 / Rec rutement par entente direct e de monsieur NDONGO Her Strengthening Revenue Mo 2021-09-2 2021-10-1 2021-09-2 2021-12-1 2021-09-2 2022-06-1 2021-12-2 vé en qualité de consultant IDA / 60230 bilization and Public Expen Post Direct Selection Direct 11,432.20 Completed 2021-09-30 0 0 1 4 3 2 5 national, spécialiste en micr diture Management ofinance pour l’évaluation d u plan national de développ ement (PND) 2018-2022 PRISP-275-C-ED-2021 / Rec rutement par entente direct Strengthening Revenue Mo e de monsieur WILONDJA Dé 2021-09-0 2021-10-1 2021-08-2 2021-12-1 2021-08-2 2022-06-1 IDA / 60230 bilization and Public Expen Post Direct Selection Direct 26,343.15 Signed 2021-09-30 puté en qualité de consultan 8 0 7 4 8 2 diture Management t chargé de la surveillance d es travaux des infrastructur es solaires à BZV & PNR PRISP-266-C-ED-2021 / Rec rutement par entente direct e de monsieur MAYEKO Léo Strengthening Revenue Mo 2021-09-2 2021-10-1 2021-09-2 2021-12-1 2021-09-2 2022-06-1 2021-12-2 n en qualité de consultant n IDA / 60230 bilization and Public Expen Post Direct Selection Direct 11,456.51 Completed 2021-09-30 0 0 1 4 3 2 5 ational, spécialiste d’écono diture Management mie internationale pour l’év aluation du plan national de développement (PND) 2018- 2022 PRISP-272-C-ED-2021 / Rec rutement par entente direct e de madame Olivia RAKOT Project Implementation Sup 2021-09-0 2021-10-1 2021-09-1 2021-12-1 2021-09-2 2022-06-1 OMALALA en qualité de Con IDA / 60230 Post Direct Selection Direct 45,750.22 Signed 2021-09-30 port 8 0 3 4 1 2 sultant chargé de l'appui au suivi et évaluation de l'UCP et renforcement des capacit és en gestion et suivi des co ntrats. PRISP-279-C-ED-2021 / Rec rutement par entente direct e de monsieur MAKOSSO Be Strengthening Revenue Mo thuel comme consultant nat 2021-09-2 2021-11-0 2021-09-2 2022-01-1 2021-09-2 2022-07-1 2021-11-0 IDA / 60230 bilization and Public Expen Post Direct Selection Direct 14,949.80 Completed 2021-10-29 ional, coordonnateur de l’éq 0 8 1 2 3 1 9 diture Management uipe des consultants, spécia liste des politiques économi ques et sociales pour l’évalu ation du plan national de dé veloppement (PND) PRISP-267-C-ED-2021 / Rec rutement par entente direct e de monsieur MOULEMVO Strengthening Revenue Mo André en qualité de consult 2021-09-2 2021-10-1 2021-09-2 2021-12-1 2021-09-2 2022-06-1 2021-12-2 IDA / 60230 bilization and Public Expen Post Direct Selection Direct 11,456.51 Completed 2021-09-30 ant national, spécialiste des 0 0 1 4 3 2 5 diture Management politiques économiques et s ociales pour l’évaluation du plan national de développe ment (PND) 2018-2022 PRISP-273-C-ED-2021 / Rec rutement de Max RASENDR ASOA en qualité de Consult Strengthening Revenue Mo 2021-09-0 2021-10-1 2021-09-2 2021-12-1 2021-10-0 2022-06-1 ant international chargé de l IDA / 60230 bilization and Public Expen Post Direct Selection Direct 56,518.43 Signed 2021-09-30 8 0 7 4 1 2 ’appui technique aux activit diture Management és de réformes des finances publiques dans le cadre des projets de digitalisation PRISP-274-C-ED-2021 / Rec rutement par entente direct e de monsieur SALL en quali Strengthening Revenue Mo té de consultant internation 2021-09-0 2021-10-1 2021-08-1 2021-12-1 2021-08-1 2022-06-1 2022-04-3 IDA / 60230 bilization and Public Expen Post Direct Selection Direct 58,682.68 Completed 2021-09-30 al chargé de l'étude pour l'a 7 0 7 4 9 2 0 diture Management utomatisation des procédur es relatives à la planification des projets d'investissement s publics de l'Etat PRISP-269-C-ED-2021 / Rec rutement par entente direct e de monsieur SAMBA Bruno Strengthening Revenue Mo 2021-09-2 2021-10-1 2021-09-2 2021-12-1 2021-09-2 2022-06-1 2021-12-2 en qualité de consultant nat IDA / 60230 bilization and Public Expen Post Direct Selection Direct 11,432.20 Completed 2021-09-30 0 0 1 4 3 2 5 ional, spécialiste en techniq diture Management ues quantitatives pour l’éval uation du plan national de d éveloppement (PND) 2018-2 022 PRISP-277-C-CI-2021 / Recr utement du consultant natio nal en comptabilité publique Strengthening Revenue Mo pour appuyer la mission d'a Individual Consul 2021-09-0 2021-10-1 2021-08-3 2021-11-0 2021-10-2 2021-12-1 2021-10-2 2022-06-0 IDA / 60230 bilization and Public Expen Post Limited 40,462.37 Signed 2021-10-11 ssistance technique pour la tant Selection 7 6 0 6 8 1 9 9 diture Management mise en œuvre du Plan d’Ac tion triennal 2021-2023 de l a réforme du système de Ge stion des Finances PRISP-271-C-ED-2021 / Rec rutement de monsieur BAG HANA Rufin comme du cons Strengthening Revenue Mo ultant international en charg 2021-09-0 2021-10-1 2021-03-3 2021-12-1 2021-04-2 2022-06-1 2022-01-1 IDA / 60230 bilization and Public Expen Post Direct Selection Direct 361,506.06 Completed 2021-09-30 e de l’appui à la mise en œu 8 0 1 4 9 2 2 diture Management vre du Plan d’Action triennal 2021-2023 de la réforme du système de Gestion des Fin ances Publiques en Républiq ue du Congo PRISP-281-C-CI-21 / Recrute ment d'un consultant nation Modernization of the Public Individual Consul 2021-11-3 2022-02-1 2022-03-1 2022-04-1 2022-10-1 al en charge de la conceptio IDA / 60230 Post Open 0.00 Canceled 2021-12-30 Administration tant Selection 0 7 0 4 1 n du plan de classement de s archives de la fonction pu blique PRISP-289-C-CI-21 / Recrute ment expert international sp Improving Transparency an Individual Consul Under Implemen 2021-10-1 2022-02-1 2022-03-1 2022-04-1 2022-10-1 IDA / 60230 Post Open 0.00 2021-12-30 écialiste MNV pour l'unité de d Accountability tant Selection tation 6 7 0 4 1 gestion du programme RED D+ PRISP-290-C-CI-21 / Recrute ment d'un consultant intern Strengthening Revenue Mo ational chargé de la mise en Individual Consul 2021-11-3 2022-02-0 2022-02-2 2022-04-0 2022-10-0 IDA / 60230 bilization and Public Expen Post Open 0.00 Canceled 2021-12-20 place d'une base de donnée tant Selection 0 7 8 4 1 diture Management s sur la dette publique cong olaise au profit de la caisse congolaise d'amortissement (CCA) PRISP-291-C-CI-21 / Recrute ment d'un consultant nation Strengthening Revenue Mo Individual Consul 2021-10-1 2022-02-1 2022-03-0 2022-04-1 2022-10-0 al chargé de la création et d IDA / 60230 bilization and Public Expen Post Open 0.00 Canceled 2021-12-27 tant Selection 8 4 7 1 8 e la gestion du site internet diture Management au profit de la caisse congol aise d'amortissement (CCA) PRISP-282-C-CI-2021 / Recr utement d'un consultant nat Strengthening Revenue Mo Individual Consul 2021-11-1 2021-12-0 2021-10-1 2021-12-2 2021-10-2 2022-01-3 2021-10-2 2022-07-2 2022-02-1 ional chargé d'élaborer la st IDA / 60230 bilization and Public Expen Post Limited 8,598.90 Completed 2021-11-30 tant Selection 7 5 8 6 8 0 9 9 5 ratégie de communication d diture Management u plan national de développ ement (PND) 2022-2028 PRISP-283-C-CI-2021 / Recr utement par entente directe de monsieur BAKOULOU JEA Project Implementation Sup Individual Consul 2021-11-1 2022-01-1 2021-11-2 2022-01-3 2021-11-2 2022-03-0 2021-11-2 2022-09-0 N ROGER au poste de cons IDA / 60230 Post Direct 24,733.35 Signed 2021-12-31 port tant Selection 7 0 5 1 6 7 7 3 ultant national chargé de l'o pérationnalisation de la cell ule de suivi des réformes en matière de gouvernance (CS RG) PRISP-284-C-CI-2021 / Recr utement par entente directe de monsieur MATOKOT OUN Project Implementation Sup Individual Consul 2021-11-1 2022-01-1 2021-11-2 2022-01-3 2021-11-2 2022-03-0 2021-11-2 2022-09-0 IME Fred au poste d'expert IDA / 60230 Post Direct 14,840.01 Signed 2021-12-31 port tant Selection 7 0 5 1 6 7 7 3 national chargé du suivi des réformes de l'Etat au sein d e la cellule de suivi des réfo rmes en matière de gouvern ance PRISP-293-C-CI-ED-22 / Ren ouvellement du contrat de monsieur KABA-MBOUALA a Project Implementation Sup 2022-01-1 2022-02-1 2022-01-1 2022-04-1 2022-01-1 2022-10-1 u poste d'expert national ch IDA / 60230 Post Direct Selection Direct 31,181.04 Signed 2022-01-31 port 4 0 4 6 8 3 argé de la réforme des finan ces publiques au sein de la cellule de suivi des réformes en matière de gouvernance PRISP-294-C-CI-ED-22 / Ren ouvellement du contrat de monsieur MBOUNGOU Jean Project Implementation Sup 2022-01-1 2022-02-1 2022-01-1 2022-04-1 2022-01-1 2022-10-1 de Dieu au poste d'expert n IDA / 60230 Post Direct Selection Direct 31,137.12 Signed 2022-01-31 port 4 0 4 6 8 3 ational chargé de la réforme des entreprises publiques a u sein de la cellule de suivi des réformes en matière de gouvernance PRISP-296-C-ED-2022 / Ren ouvellement du contrat de madame LEGERNARD Sylvie Project Implementation Sup 2022-01-1 2022-03-1 2022-01-1 2022-05-1 2022-01-1 2022-11-1 au poste d'expert national c IDA / 60230 Post Direct Selection Direct 23,352.84 Signed 2022-02-28 port 4 0 4 4 8 0 hargé de la réforme des ma rchés publics au sein de la c ellule de suivi des réformes en matière de gouvernance PRISP-297-C-CI-2022 / Recr utement d'un expert nation al chargé de suivi de la rédd Project Implementation Sup Individual Consul 2022-03-0 2022-03-2 2022-04-3 2022-10-2 IDA / 60230 Post Limited 0.00 Canceled 2022-02-28 ition des comptes et de la re port tant Selection 5 6 0 7 devabilité au sein de la cellu le de suivi en matière de go uvernance PRISP-298-C-ED-2022 / Rec rutement par sélection direc te de monsieur BAGHANA R ufin en qualité de consultant Strengthening Revenue Mo 2022-02-0 2022-02-1 2021-03-3 2022-04-1 2021-04-2 2022-10-1 international en charge pour IDA / 60230 bilization and Public Expen Post Direct Selection Direct 188,277.37 Signed 2022-01-31 3 0 1 6 0 3 l'assistance technique à la diture Management mise en œuvre du Plan d’Ac tion triennal 2021-2023 de l a réforme du système de Ge stion des Finances Publique s PRISP-297 BIS-C-ED-2022 / Recrutement de monsieur M ASSAMBA Lévy par entente directe en qualité d'expert n Project Implementation Sup Individual Consul 2022-02-1 2022-03-1 2022-02-1 2022-03-3 2022-02-2 2022-05-0 2022-02-2 2022-11-0 ational chargé du suivi des r IDA / 60230 Post Direct 25,556.55 Signed 2022-02-28 port tant Selection 7 0 8 1 2 5 3 1 éformes en matière de réd dition des comptes et de re devabilité au sein de la cellu le du suivi des réformes en matière de gouvernance. Page 11 PRISP-299-C-ED-2022 / Rec rutement de monsieur SERO NDE Benoît Jean François M Project Implementation Sup Individual Consul 2022-02-0 2022-03-1 2022-02-0 2022-04-0 2022-02-1 2022-05-0 2022-02-1 2022-11-0 2022-03-1 arie par entente directe en IDA / 60230 Post Direct 23,109.06 Completed 2022-03-01 port tant Selection 8 1 8 1 4 6 6 2 7 qualité de consultant individ uel international chargé de l a formation PPSD auprès de s SPM de la République du C ongo PRISP-300-C-ED-2022 / Rec rutement du cabinet TACTIS par sélection directe pour as Strengthening Revenue Mo 2022-02-0 2022-04-1 2022-02-0 2022-06-1 2022-02-2 2022-12-1 surer la mission de contrôle IDA / 60230 bilization and Public Expen Post Direct Selection Direct 311,625.62 Signed 2022-03-31 8 0 8 4 3 1 relative au raccordement de diture Management s centres des impôts et de l a mise à jour du datacenter du ministère des finances à Brazzaville. PRISP-300-C-CI-2022 / Recr utement du consultant indiv Project Implementation Sup Individual Consul 2022-02-1 2022-04-0 2022-02-1 2022-04-2 2022-02-1 2022-05-3 2022-02-1 2022-11-2 iduel international chargé d' IDA / 60230 Post Limited 39,951.86 Signed 2022-03-31 port tant Selection 8 5 8 6 8 1 9 7 appui à la mise en oeuvre a xée sur les résultats et gesti on du changement PRISP-301-C-CI-2022 / Recr utement d’un consultant ind Strengthening Revenue Mo ividuel international pour ap Individual Consul 2022-04-2 2022-04-2 2022-02-2 2022-05-1 2022-02-2 2022-06-1 2022-02-2 2022-12-1 IDA / 60230 bilization and Public Expen Post Limited 17,735.53 Signed 2022-04-15 puyer l’élaboration de la feu tant Selection 1 0 4 1 5 5 6 2 diture Management ille de route pour le dévelop pement du système d’infor mation fiscale en Républiqu e du Congo PRISP-302-C-CI-2022 / Cons ultant individuel chargé de l’ Strengthening Revenue Mo Individual Consul 2022-04-2 2022-04-2 2022-03-0 2022-05-1 2022-03-1 2022-06-1 2022-03-1 2022-12-1 appui à l’évaluation du syst IDA / 60230 bilization and Public Expen Post Limited 29,686.93 Signed 2022-04-15 tant Selection 1 0 4 1 1 5 2 2 ème d’information de l’admi diture Management nistration fiscale et aux paie ments digitaux (G2Px & GIM AC) PRISP-303-C-CI-2022 / Recr utement d'un consultant ind Strengthening Revenue Mo Individual Consul 2022-03-1 2022-04-2 2022-03-1 2022-05-1 2022-03-1 2022-06-1 2022-03-1 2022-12-1 ividuel en charge de la réfor IDA / 60230 bilization and Public Expen Post Limited 33,760.42 Signed 2022-04-15 tant Selection 5 0 6 1 8 5 9 2 me de Gestion des Finances diture Management Publiques et des systèmes d e paiements au Congo PRISP-304-C-CI-2022 / Recr utement d’un consultant nat ional en charge de l’étude s Strengthening Revenue Mo ur les arriérés de l’audit fisc Individual Consul 2022-04-2 2022-06-2 2022-06-0 2022-07-1 2022-09-2 2022-08-1 2022-10-0 2023-02-1 IDA / 60230 bilization and Public Expen Post Limited 22,787.28 Signed 2022-06-15 al dans le cadre de la mise tant Selection 0 0 3 1 3 5 3 1 diture Management en œuvre des recommandat ions issues du rapport final de l’audit fiscal du secteur f orestier en République du C ongo PRISP-305-C-CI-2022 / Recr utement d’un consultant nat ional en charge de l’étude d ’impact et de conformité de Strengthening Revenue Mo Individual Consul 2022-04-2 2022-06-2 2022-06-0 2022-07-1 2022-06-2 2022-08-1 2022-08-0 2023-02-1 s règles actuelles de gouve IDA / 60230 bilization and Public Expen Post Limited 14,979.29 Signed 2022-06-15 tant Selection 0 0 7 1 2 5 2 1 rnance sur le secteur foresti diture Management er dans le cadre de La mise en œuvre des recommandat ions issues du rapport final de l’audit fiscal du secteur PRISP-307-CI-C-2022 / Recr utement d'un consultant ind Improving Transparency an Individual Consul 2022-08-0 2022-07-2 2022-05-3 2022-08-1 2022-06-0 2022-09-1 2022-06-1 2023-03-1 ividuel international chargé IDA / 60230 Post Limited 53,732.32 Signed 2022-07-18 d Accountability tant Selection 9 3 1 3 9 7 4 6 d'appuyer le Congo dans le cadre du processus de valid ation à la norme ITIE 2019 PRISP-403-C-CI-2022 / Recr utement d'un consultant nat Improving Transparency an Individual Consul 2022-09-0 2022-10-0 2022-10-1 2022-10-2 2022-10-1 2022-11-2 2023-05-2 IDA / 60230 Post Limited 0.00 Signed 2022-09-28 ional senior chargé d'appuy d Accountability tant Selection 3 3 0 4 8 8 7 er les OSC dans la collecte d es données. PRISP-406-C-CI-2022 / Recr utement d’un consultant int ernational pour l’élaboration Improving Transparency an Individual Consul 2022-09-0 2022-11-0 2023-01-3 2022-11-2 2023-02-2 2022-12-2 2023-06-2 des guides méthodologique IDA / 60230 Post Limited 0.00 Signed 2022-10-28 d Accountability tant Selection 3 2 1 3 4 8 6 s d’audit et d’un manuel de procédures au profit de la c our des comptes et de disci pline budgétaire PRISP-407-C-CI-2022 / Recr Strengthening Revenue Mo Individual Consul 2022-09-0 2022-11-1 2022-11-0 2022-12-0 2022-12-0 2023-01-1 2023-07-0 utement d'un consultant nat IDA / 60230 bilization and Public Expen Post Limited 0.00 Signed 2022-11-10 tant Selection 3 5 4 6 1 0 9 ional en gestion des investis diture Management sements publics PRISP-408-C-CI-2022 / Recr Strengthening Revenue Mo Individual Consul Under Implemen 2022-09-0 2022-11-1 2022-12-0 2023-01-1 2023-07-1 utement d'un consultant nat IDA / 60230 bilization and Public Expen Post Limited 0.00 2022-11-11 tant Selection tation 3 6 7 1 0 ional en planification stratég diture Management ique PRISP-415-C-ED-2022 / Rec rutement de monsieur Max RASENDRASOA par sélectio n directe en qualité de cons Strengthening Revenue Mo Individual Consul Direct - Internatio 2022-10-0 2022-11-1 2022-10-1 2022-12-0 2022-10-2 2023-01-0 2023-07-0 ultant international chargé d IDA / 60230 bilization and Public Expen Post 0.00 Signed 2022-10-31 tant Selection nal 5 0 1 1 0 5 4 e l’appui technique pour le s diture Management uivi et le contrôle qualité de s projets majeurs de digitali sation dans le cadre des réf ormes des finances publiqu es PRISP-416-C-CI-2022 / Recr Strengthening Revenue Mo utement d'un consultant nat Individual Consul 2022-10-0 2023-01-0 2022-10-1 2023-01-2 2022-12-0 2023-02-2 2023-08-2 IDA / 60230 bilization and Public Expen Post Open - National 0.00 Signed 2022-11-15 ional en planification stratég tant Selection 6 3 3 4 1 8 7 diture Management ique et en administration pu blique PRISP-417-C-CI-2022 / Recr Strengthening Revenue Mo utement d'un consultant nat Individual Consul 2022-10-0 2022-12-1 2022-10-1 2023-01-0 2022-12-0 2023-02-1 2023-08-1 IDA / 60230 bilization and Public Expen Post Open - National 0.00 Signed 2022-10-31 ional en planification stratég tant Selection 6 9 3 9 1 3 2 diture Management ique et en développement i ndustriel PRISP-418-C-CI-2022 / Recr Strengthening Revenue Mo utement d'un consultant nat Individual Consul 2022-10-0 2022-12-1 2022-10-1 2023-01-0 2022-12-0 2023-02-1 2023-08-1 IDA / 60230 bilization and Public Expen Post Open - National 0.00 Signed 2022-10-31 ional en planification stratég tant Selection 6 9 3 9 1 3 2 diture Management ique et en éducation PRISP-419-C-CI-2022 / Recr Strengthening Revenue Mo utement d'un consultant nat Individual Consul 2022-10-0 2022-12-1 2022-10-1 2023-01-0 2022-12-0 2023-02-1 2023-08-1 IDA / 60230 bilization and Public Expen Post Open - National 0.00 Signed 2022-10-31 ional en planification stratég tant Selection 6 9 3 9 1 3 2 diture Management ique et en appui aux PME PRISP-420-C-CI-2022 / Recr Strengthening Revenue Mo utement d'un consultant nat Individual Consul 2022-10-0 2022-12-1 2022-11-1 2023-01-0 2022-12-0 2023-02-1 2023-08-1 IDA / 60230 bilization and Public Expen Post Open - National 0.00 Signed 2022-10-31 ional en planification stratég tant Selection 6 9 8 9 1 3 2 diture Management ique et en transports PRISP-423-C-ED-2022 / Rec rutement par entente direct e de Taha TRIKI pour accom Strengthening Revenue Mo pagner le Ministère des Fina Individual Consul Direct - Internatio 2022-11-1 2023-01-0 2022-11-0 2023-01-3 2022-11-1 2023-03-0 2023-09-0 IDA / 60230 bilization and Public Expen Post 0.00 Signed 2022-12-30 nces, du Budget et du Portef tant Selection nal 8 9 3 0 1 6 2 diture Management euille Public dans le suivi d es activités de l’intégrateur pour la stabilisation des solu tions Oracle PSRM et Oracle Payroll PRISP-409-C-CI-22 / Recrute ment par entente directe de Strengthening Revenue Mo monsieur Taha TRIKI en qua Individual Consul Direct - Internatio 2022-11-1 2022-11-0 2022-05-0 2022-11-2 2022-05-0 2023-01-0 2023-07-0 IDA / 60230 bilization and Public Expen Post 0.00 Signed 2022-10-28 lité de consultant individuel tant Selection nal 8 7 4 8 9 2 1 diture Management international chargé de de l a mise en oeuvre de la feuill e de route E-Tax. PRISP-428-C-CI-2022 / Recr utement d’un consultant ind ividuel national spécialiste e Improving Transparency an Individual Consul 2022-11-1 2023-01-0 2022-11-2 2023-01-2 2022-12-0 2023-03-0 2023-08-2 n planification budgétaire p IDA / 60230 Post Limited 0.00 Signed 2022-12-30 d Accountability tant Selection 8 4 4 5 7 1 8 our appuyer les OSC dans la mission de suivi des investis sements publics dans les se cteurs de la santé et de l’éd ucation PRISP-401-C-CI-2022 / Recr utement d'un consultant nat Modernization of the Public Individual Consul 2022-09-0 2022-10-0 2022-10-2 2022-11-3 2023-05-2 ional chargé de l'élaboration IDA / 60230 Post Limited 0.00 Canceled 2022-09-30 Administration tant Selection 3 5 6 0 9 de la stratégie de communic ation du ministère en charg e du contrôle d'Etat PRISP-402-C-CI-2022 / Recr utement d'un consultant nat Modernization of the Public Individual Consul 2022-09-0 2022-10-0 2022-10-2 2022-11-2 2023-05-2 ional chargé de l'élaboration IDA / 60230 Post Limited 0.00 Canceled 2022-09-29 Administration tant Selection 3 4 5 9 8 d'un site web au profit du m inistère en charge du contrô le d'Etat. PRISP-421-C-CI-2022 / Recr utement d'un consultant ind Strengthening Revenue Mo ividuel international chargé Individual Consul 2022-12-2 2022-12-1 2023-01-0 2023-02-0 2023-08-0 IDA / 60230 bilization and Public Expen Post Limited 0.00 Canceled 2022-12-09 de l'assistance à la finalisati tant Selection 7 4 4 8 7 diture Management on du plan stratégique de la direction générale des impô ts et des domaines PRISP-414-C-CI-2022 / Recr Strengthening Revenue Mo utement d'un consultant po Individual Consul 2022-10-0 2023-01-3 2023-02-2 2023-03-2 2023-09-2 IDA / 60230 bilization and Public Expen Post Open - National 0.00 Canceled 2022-12-12 ur la mise en place du porta tant Selection 5 0 0 7 3 diture Management il web de la caisse congolai se d’amortissement (cca) PRISP-413-C-CI-2022 / Recr utement du consultant char Strengthening Revenue Mo gé de la mise en place d’un Individual Consul Open - Internation 2022-10-0 2023-01-3 2023-02-2 2023-03-2 2023-09-2 IDA / 60230 bilization and Public Expen Post 0.00 Canceled 2022-12-12 e base de données sur la de tant Selection al 5 0 0 7 3 diture Management tte publique congolaise à la caisse congolaise d'amortiss ement (CCA) PRISP-422-C-CI-2022 / Recr utement d'un consultant ch Strengthening Revenue Mo argé de la mission de contrô Individual Consul 2023-01-0 2023-01-2 2023-03-0 2023-08-2 IDA / 60230 bilization and Public Expen Post Limited 0.00 Canceled 2022-12-30 le pour le suivi de l'installati tant Selection 4 5 1 8 diture Management on des anti-incendies dans l es sites du ministère des fin ances abritant le système s olaire PRISP-433-C-ED-2022 / Rec rutement du cabinet POPAY Strengthening Revenue Mo par entente directe pour po Direct - Internatio 2023-04-1 2023-06-1 2023-12-1 IDA / 60230 bilization and Public Expen Prior Direct Selection 0.00 Under Review 2023-03-31 ursuite la stabilisation du s nal 0 4 1 diture Management ystème intégré de la paie d es agents de l’Etat « SIPAE » à la direction générale du budget Page 12 PRISP-435-C-ED-2022 / Ren ouvellement du contrat de monsieur MASSAMBA Levy Dominique au poste d’exper Project Implementation Sup Under Implemen 2023-04-1 2023-04-1 2023-06-2 2023-12-1 IDA / 60230 Post Direct Selection Direct - National 0.00 2023-04-07 t national chargé de la reddi port tation 4 7 1 8 tion des comptes et de la re devabilité au sein de la cellu le de suivi des reformes en matière de gouvernance PRISP-436-C-ED-2023 / Ren ouvellement du contrat de Project Implementation Sup Under Implemen 2023-04-1 2023-04-1 2023-06-2 2023-12-1 monsieur MATOKOT Fred Jo IDA / 60230 Post Direct Selection Direct - National 0.00 2023-04-07 port tation 4 7 1 8 nas Ounimé au poste d’exp ert national chargé du suivi de la réforme de l’Etat PRISP-437-C-ED-2023 / Ren ouvellement du contrat de monsieur BAKOULOU Jean R Project Implementation Sup Under Implemen 2023-04-1 2023-04-1 2023-06-2 2023-12-1 oger au poste d’expert natio IDA / 60230 Post Direct Selection Direct - National 0.00 2023-04-07 port tation 5 7 1 8 nal chargé l'opérationnalisat ion de la cellule de suivi de l a réforme en matière de go uvernance en République d u Congo PRISP-438-C-ED-2023 / Ren ouvellement du contrat de Project Implementation Sup Under Implemen 2023-04-1 2023-04-1 2023-06-2 2023-12-1 monsieur MBOUNGOU Jean IDA / 60230 Post Direct Selection Direct - National 0.00 2023-04-07 port tation 4 7 1 8 de Dieu au poste d’expert n ational chargé de la réforme des entreprises publiques PRISP-439-C-ED-2023 / Ren ouvellement du contrat de Project Implementation Sup Under Implemen 2023-04-1 2023-04-1 2023-06-2 2023-12-1 monsieur KAKA MBOUALA a IDA / 60230 Post Direct Selection Direct - National 0.00 2023-04-07 port tation 5 7 1 8 u poste d’expert national ch argé du suivi de la réforme des finances publiques PRISP-450-C-ED-2023 / Ren ouvellement du contrat de madame LEGERNARD Sylvie Project Implementation Sup Under Implemen 2023-04-1 2023-04-1 2023-06-2 2023-12-1 au poste d'expert national c IDA / 60230 Post Direct Selection Direct - National 0.00 2023-04-07 port tation 5 7 1 8 hargé de la réforme des ma rchés publics au sein de la c ellule de suivi des réformes en matière de gouvernance PRISP-451-C-ED-2023 / Rec rutement par entent direct Strengthening Revenue Mo Direct - Internatio Under Implemen 2023-03-1 2023-04-2 2023-06-2 2023-12-2 de madame Sylvie ZAITRA B IDA / 60230 bilization and Public Expen Post Direct Selection 0.00 2023-04-14 nal tation 6 4 8 5 ECK, consultante internation diture Management ale chargée de la réalisation de la mission PEFA PRISP-452-C-ED-2023 / Rec rutement par entente direct e e Raphaël POUYE, consult Improving Transparency an Direct - Internatio Under Implemen 2023-03-1 2023-04-2 2023-06-2 2023-12-2 IDA / 60230 Post Direct Selection 0.00 2023-04-14 ant en charge du renforcem d Accountability nal tation 6 4 8 5 ent des capacités des partie s prenantes du partenariat p our un gouvernement ouver t PRISP-454-C-ED-2023 / Rec rutement par entente direct e de monsieur BAGHANA Ru fin en qualité de consultant i Strengthening Revenue Mo Direct - Internatio Under Implemen 2023-03-0 2023-04-1 2023-03-0 2023-06-2 2023-12-1 ndividuel international en ch IDA / 60230 bilization and Public Expen Post Direct Selection 0.00 2023-04-07 nal tation 1 7 6 1 8 arge de la mise en œuvre d diture Management u plan d’action triennal 202 1-2023 de la réforme du sys tème de gestion des finance s publiques en République d u Congo PRISP-456-C-CI-2023 / Recr utement d’un consultant ind ividuel international Assista Strengthening Revenue Mo Individual Consul Under Implemen 2023-03-1 2023-05-0 2023-05-2 2023-06-2 2023-12-2 nt de chef de projet pour ac IDA / 60230 bilization and Public Expen Post Limited 0.00 2023-04-28 tant Selection tation 5 3 4 8 5 compagner le Ministère de l' diture Management Economie et des Finances ( MEF) dans les activités de d e stabilisation de la solution E-TAX PRISP-457-C-CI-2023 / Recr utement d’un consultant ind ividuel international Busines Strengthening Revenue Mo Individual Consul Under Implemen 2023-03-1 2023-05-0 2023-05-2 2023-06-2 2023-12-2 s Analyst pour accompagner IDA / 60230 bilization and Public Expen Post Limited 0.00 2023-04-28 tant Selection tation 5 3 4 8 5 le Ministère de l'Economie e diture Management t des Finances (MEF) dans le s activités de de stabilisatio n de la solution E-TAX PRISP-458 / Recrutement d’ un consultant individuel inte rnational Expert reprise des Strengthening Revenue Mo Individual Consul Under Implemen 2023-05-0 2023-05-2 2023-06-2 2023-12-2 données pour accompagner IDA / 60230 bilization and Public Expen Post Limited 0.00 2023-04-28 tant Selection tation 3 4 8 5 le Ministère de l'Economie e diture Management t des Finances (MEF) dans le s activités de de stabilisatio n de la solution E-TAX PRISP-459-C-CI-2023 / Recr utement d’un consultant ind ividuel international Expert Strengthening Revenue Mo Individual Consul Under Implemen 2023-03-1 2023-05-0 2023-05-2 2023-06-2 2023-12-2 en conduite de changement IDA / 60230 bilization and Public Expen Post Limited 0.00 2023-04-28 tant Selection tation 5 3 4 8 5 pour accompagner le Minist diture Management ère de l'Economie et des Fin ances (MEF) dans les activit és de de stabilisation de la s olution E-TAX PRISP-460-C-CI-2023 / Recr utement d’un consultant ind ividuel international Expert Strengthening Revenue Mo Individual Consul Under Implemen 2023-05-0 2023-05-2 2023-06-2 2023-12-2 en Base des Données pour a IDA / 60230 bilization and Public Expen Post Limited 0.00 2023-04-28 tant Selection tation 3 4 8 5 ccompagner le Ministère de diture Management l'Economie et des Finances ( MEF) dans les activités de d e stabilisation de la solution E-TAX PRISP-461-C-CI-2023 / Recr utement d’un consultant ind ividuel international Expert Strengthening Revenue Mo en solution Oracle PSRM (Pu Individual Consul Under Implemen 2023-03-0 2023-05-0 2023-05-2 2023-06-2 2023-12-2 IDA / 60230 bilization and Public Expen Post Limited 0.00 2023-04-28 blic Sector Revenue Manage tant Selection tation 7 3 4 8 5 diture Management ment) pour accompagner le Ministère de l'Economie et d es Finances (MEF) dans les activités de de stabilisation de la solution E-TAX PRISP-462-C-CI-2023 / Recr utement d’un consultant ind ividuel international Expert Strengthening Revenue Mo en solution Oracle PSRM2 (P Individual Consul Under Implemen 2023-05-0 2023-05-2 2023-06-2 2023-12-2 IDA / 60230 bilization and Public Expen Post Limited 0.00 2023-04-28 ublic Sector Revenue Manag tant Selection tation 3 4 8 5 diture Management ement) pour accompagner l e Ministère de l'Economie et des Finances (MEF) dans les activités de de stabilisation de la solution E-TAX PRISP-463-C-CI-2023 / Recr utement d’un consultant ind ividuel international Archite Strengthening Revenue Mo cte technique et expert en s Individual Consul Under Implemen 2023-05-0 2023-05-2 2023-06-2 2023-12-2 IDA / 60230 bilization and Public Expen Post Limited 0.00 2023-04-28 écurité pour accompagner l tant Selection tation 3 4 8 5 diture Management e Ministère de l'Economie et des Finances (MEF) dans les activités de de stabilisation de la solution E-TAX PRISP-464-C-CI-2023 / Recr utement d’un consultant ind ividuel international Expert Strengthening Revenue Mo Individual Consul Under Implemen 2023-05-0 2023-05-2 2023-06-2 2023-12-2 en JEE (Java Enterprise Editi IDA / 60230 bilization and Public Expen Post Limited 0.00 2023-04-28 tant Selection tation 3 4 8 5 on) pour accompagner le Mi diture Management nistère de l'Economie et des Finances (MEF) dans les acti vités de de stabilisation de l a solution E-TAX PRISP-465-C-CI-2023 / Recr utement d’un consultant ind ividuel international Expert Strengthening Revenue Mo Individual Consul Under Implemen 2023-05-0 2023-05-2 2023-06-2 2023-12-2 en recette logicielle pour ac IDA / 60230 bilization and Public Expen Post Limited 0.00 2023-04-28 tant Selection tation 3 4 8 5 compagner le Ministère de l' diture Management Economie et des Finances ( MEF) dans les activités de d e stabilisation de la solution E-TAX PRISP-466-C-CI-2023 / Recr utement d’un consultant ind ividuel international Expert Strengthening Revenue Mo en JIRA (un système de suivi Individual Consul Under Implemen 2023-05-0 2023-05-2 2023-06-2 2023-12-2 IDA / 60230 bilization and Public Expen Post Limited 0.00 2023-04-28 de bugs, de gestion des inci tant Selection tation 3 4 8 5 diture Management dents et de gestion de proje ts) pour accompagner le Min istère de l'Economie et des Finances (MEF) dans les acti vités de de stabilisation PRISP-467-C-ED-2023 / Rec rutement par entente direct e du conseil régional de for mation des institutions supé Improving Transparency an Direct - Internatio Under Implemen 2023-04-3 2023-07-0 2023-12-3 rieures de contrôle des fina IDA / 60230 Post Direct Selection 0.00 2023-04-20 d Accountability nal tation 0 4 1 nces publiques d’Afrique su bsaharienne (CREFIAF) pour la formation des agents de c ontrôle public (CCDB, IGF, I GE, etc.) sur l’audit des cont r PRISP-468-C-CI-2023 / Recr utement d’un consultant ind ividuel chargé de la formati on en technologie java et or Modernization of the Public Individual Consul Under Implemen 2023-05-0 2023-05-2 2023-06-2 2023-12-2 acle application développe IDA / 60230 Post Limited 0.00 2023-04-28 Administration tant Selection tation 3 4 8 5 ment Framework (ADF) dan s le cadre de la mise en oeu vre du système intègre de g estion des ressources humai nes de l’ETAT et du registre des age PRISP-469-C-CI-2023 / Recr utement d’un consultant ind ividuel en vue de former les techniciens de la direction d Modernization of the Public Individual Consul Under Implemen 2023-04-0 2023-04-2 2023-05-2 2023-11-2 es systèmes d’information e IDA / 60230 Post Limited 0.00 2023-03-28 Administration tant Selection tation 2 3 8 4 n administration de bases d e données sous oracle (DBA NIVEAU 1) dans le cadre de l a mise en œuvre du systèm e intègre de gestion des res sourc PRISP-470-C-CI-2023 / Recr utement de l’Administrateur Improving Transparency an Individual Consul Under Implemen 2023-05-0 2023-05-2 2023-06-2 2023-12-2 indépendant chargé d’élabo IDA / 60230 Post Limited 0.00 2023-04-28 d Accountability tant Selection tation 3 4 8 5 rer le rapport ITIE exercice 2 021 de la République du Co ngo Page 13 PRISP-455-C-ED-2023 / Rec rutement par ED du groupe ment SOTEK TACTIS pour la mission de supervision, de s Strengthening Revenue Mo Direct - Internatio Under Implemen 2023-04-3 2023-07-0 2023-12-3 uivi et de contrôle des trava IDA / 60230 bilization and Public Expen Post Direct Selection 0.00 2023-04-20 nal tation 0 4 1 ux de la fia, du datacenter e diture Management t du système énergétique h ybride (e2c, ge et panneaux solaires) sur les sites du min istère de l’économie et des f in PRISP-478-C-ED-23 / sélecti on par entente directe de m onsieur Jérôme FONIN en qu Modernization of the Public Direct - Internatio Pending Implem 2023-09-0 2023-11-0 2024-05-0 alité de consultant individue IDA / 60230 Post Direct Selection 0.00 2023-08-24 Administration nal entation 3 7 5 l pour l'assistance technique à la finalisation du système i nformatique de la direction générale des impôts et des domaines PRISP-479-C-CI-23 / Recrute ment de deux consultants s eniors spécialises en dévelo Strengthening Revenue Mo ppement d'application oracl Individual Consul Pending Implem 2023-09-0 2023-09-2 2023-10-3 2024-04-2 IDA / 60230 bilization and Public Expen Post Limited 0.00 2023-08-31 e e·business suite pour l'acc tant Selection entation 5 6 1 8 diture Management ompagnement du MBCPPP d ans la stabilisation et la final isation des modules restant s de la solution e-business s uite de SIGFIP PRISP-480-C-CI-23 / Recrute ment d'un (01) consultant p our l'assistance à la maitrise Strengthening Revenue Mo Individual Consul Pending Implem 2023-09-0 2023-09-2 2023-10-3 2024-04-2 d'ouvrage du MBCPPP dans l IDA / 60230 bilization and Public Expen Post Limited 0.00 2023-08-31 tant Selection entation 5 6 1 8 a stabilisation et la finalisati diture Management on des modules restants de la solution e-business suite de l'application SIGFIP PRISP-481-C-CI-23 / consult ant individuel expert dévelo ppeur PUSQL & OAF sous O Strengthening Revenue Mo RACLE EBS R12 pour la form Individual Consul Pending Implem 2023-09-0 2023-09-2 2023-10-3 2024-04-2 IDA / 60230 bilization and Public Expen Post Limited 0.00 2023-08-31 ation des ingénieurs en char tant Selection entation 5 6 1 8 diture Management ge du SIGFIP à la direction d es systèmes d'information du ministère du budget, de s comptes publics et du po rtefeuille public PRISP-482-C-CI-23 / Consult ant technico-fonctionnel spé cialisé en oracle e- business Strengthening Revenue Mo Individual Consul Pending Implem 2023-09-0 2023-09-2 2023-10-3 2024-04-2 suite pour l'accompagneme IDA / 60230 bilization and Public Expen Post Limited 0.00 2023-08-31 tant Selection entation 5 6 1 8 nt MBCPPP dans la stabilisa diture Management tion et la finalisation des m odules restants de la soluti on e-business suite de l'ap plication SIGFIP PRISP-483-C-ED-2023 / Rec rutement par entente direct Modernization of the Public Direct - Internatio Under Implemen 2023-06-0 2023-08-1 2023-10-1 2024-04-1 e du Cabinet BEESOSMART IDA / 60230 Post Direct Selection 0.00 2023-08-02 Administration nal tation 8 2 6 3 spécialisé en développemen t d’application oracle E-busi ness suite PRISP-485-C-CI-2023 / Recr utement d'un Consultant Int Project Implementation Sup Individual Consul Open - Internation Under Implemen 2023-06-0 2023-12-1 2024-01-0 2024-02-1 2024-08-1 IDA / 60230 Post 0.00 2023-10-30 ernational chargé d'élaborer port tant Selection al tation 9 8 8 2 0 le rapport d'achèvement du projet PRISP PRISP-486-C-ED-2023 / Rec rutement par entente direct Strengthening Revenue Mo Under Implemen 2023-06-0 2023-08-0 2023-10-1 2024-04-1 e du consultant individuel Y IDA / 60230 bilization and Public Expen Post Direct Selection Direct - National 0.00 2023-07-30 tation 8 9 3 0 von Didier MEHAKANDA pou diture Management r l'appui au suivi des activit és de la digitalisation Page 14 PROCUREMENT PLAN (Textual Part) Information sur le Projet : Cote d’Ivoire, Projet Multisectoriel de Nutrition et de Développement de la Petite Enfance, P161770 Agence d’exécution du Projet : Unité de Gestion du Projet, Secrétariat Exécutif du Conseil National de la Nutrition, de l’Alimentation et de la Petite Enfance Date du plan de passation des marchés : 11 novembre 2019 Période couverte par ce plan de passation des marchés : Novembre 2019 – April 2021 Préambule Conformément au paragraphe 5.9 du “Règlement de Passation des Marchés pour les Emprunteurs sollicitant le Financement de Projets d’Investissement (FPI)” (Juillet 2016, révisé en aout 2019) (“Règlement de Passation des Marchés”) le Système électronique de la Banque de suivi systématique des transactions de marchés publics (STEP) sera utilisé pour préparer, valider et actualiser les plans de passation des marchés et effectuer toutes les transactions liées à la passation des marchés du projet. Ce texte ainsi que les tableaux du plan de passation des marchés présents dans STEP constituent le plan de passation des marchés du projet. Les conditions suivantes s'appliquent à toutes les activités de passation de marchés du plan de passation de marchés. Les autres éléments du plan de passation des marchés tels que requis au paragraphe 4.4 du Règlement de passation des marchés sont énoncés dans STEP. Les Dossiers types de passation des marchés publics de la Banque devront être utilisés pour tous les contrats soumis à la concurrence internationale, ainsi que pour tous les autres contrats soumis à cette obligation telle que spécifiée dans les tableaux du plan de passation des marchés de STEP. Procédures nationales de passation des marchés : En accord avec le paragraphe 5.3 du Règlement de passation des marchés, dans le cas où la procédure de passation des marché se fera au niveau national (telle que spécifiée dans les tableaux du plan de passation des marchés inclus de STEP), les procédures nationales de passation des marchés du pays considéré pourront être utilisées. Si l’Emprunteur utilise ses propres procédures d’appel d’offres national ouvert telles qu’énoncées, ces arrangements sont soumis aux dispositions du paragraphe 5.4 du Règlement de passation des marchés et aux conditions suivantes : Sans objet. Lorsque l’Emprunteur utilise d’autres procédures que l’appel d’offres national ouvert, ces procédures devront être en accord avec les dispositions du paragraphe 5.5 du Règlement de passation des marchés. Crédit-bail tel que spécifié au paragraphe 5.10 du Règlement de Passation des marchés : Le crédit-bail peut être utilisé pour les contrats indiqués comme tel dans le Plan de passation des marchés. « Sans objet » Achat de biens d’occasion tel que spécifié au paragraphe 5.11 du Règlement de Passation des Marchés est autorisé pour les contrats indiqués comme tel dans le Plan de passation des marchés. « Sans objet » Préférence nationale telle que spécifiée au paragraphe 5.51 du Règlement de Passation des Marchés (Fournitures et Travaux). Fournitures : ne s’applique pas Travaux : ne s’applique pas Autres informations pertinentes sur la passation des marchés : Néant. PROCUREMENT Cote d'Ivoire : Multisectoral Nutrition and Child Development Project PLAN General Information Country: Cote d'Ivoire Bank’s Approval Date of the Original Procurement Plan:2019-12-06 2023-06-05 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P161770 GPN Date: Project Name: Multisectoral Nutrition and Child Development Project Loan / Credit No: IDA / 61740, IDA / V1050 Multisectoral Nutrition and Child Development Project Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process S Draft Pre-qualificatio Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Comple Description Component Review Type Method Amount (U ount (US$ and Recommendatio Signed Contract o. h cess (Y/N) isk ocument Type tatus n Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes tion S$) ) n for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualificatio Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendatio Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus n Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes n for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CI-PMNDPE-72404-GO-RFQ / Request for Quot Single Stage - One Pending Impl Acquisition de fournitures de IDA / 61740 Project management Post Limited 10,000.00 0.00 2018-08-20 2018-10-15 2018-10-30 ations Envelope ementation bureau pour le PPF-PMNDPE CI-PMNDPE-72467-GO-RFQ / ACQUISITION DE MATÉRIELS Request for Quot Single Stage - One Pending Impl IDA / 61740 Project management Post Limited 10,000.00 0.00 2018-08-06 2018-10-09 2019-04-10 DE DÉMONSTRATION CULIN ations Envelope ementation AIRE (marmites, casseroles, cuisinière) CI-PMNDPE-72469-GO-RFQ / ACQUISITION DE SUPPORTS Early child nutrition and dev Request for Quot Single Stage - One Pending Impl D'ANIMATION ET DE COMMU IDA / 61740 Post Limited 10,000.00 0.00 2018-08-27 2018-10-11 2018-11-10 elopment interventions ations Envelope ementation NICATION (outils de démons tration,supports de jeux,boit es à images) CI-PMNDPE-72472-GO-RFQ / Request for Quot Single Stage - One Pending Impl ACQUISITION DE MOBILIER D IDA / 61740 Project management Post Limited 50.00 0.00 2018-09-10 2018-11-05 2019-05-07 ations Envelope ementation E BUREAU POUR LE PMNDPE CI-PMNDPE-72575-GO-DIR / Acquisition d'équipements p Early child nutrition and dev Pending Impl IDA / 61740 Post Direct Selection Direct 20,000.00 0.00 2018-08-23 2018-09-07 2018-10-12 2018-11-11 our les structures communa elopment interventions ementation utaires (balance, toise, mètr e ruban, MUAC) CI-PMNDPE-72680-GO-RFQ / Acquisition de Matériels info Request for Quot Single Stage - One Pending Impl IDA / 61740 Project management Post Limited 40,000.00 0.00 2018-09-03 2018-10-29 2018-11-28 rmatiques et de Matériels de ations Envelope ementation Bureau pour le PMNDPE CI-PMNDPE-109850-GO-DIR / Acquérir du matériel anthr Early child nutrition and dev Pending Impl opométrique de démonstrati IDA / 61740 Post Direct Selection Direct 600,000.00 0.00 2019-04-25 2019-04-30 2019-06-04 2019-12-01 elopment interventions ementation on culinaire d'éveil et les éq uipements au profit des FRA NC CI-PMNDPE-110685-GO-RFQ / Acquisition d'équipements Request for Quot Single Stage - One Pending Impl et bureau pour le déploieme IDA / 61740 Project management Post Open - National 80,000.00 0.00 2019-04-30 2019-06-24 2019-12-21 ations Envelope ementation nt et l'installation des équip es régionales (Points focau x, comptables) CI-PMNDPE-110616-GO-RFQ Request for Quot Single Stage - One Pending Impl / Acquisition de groupe élect IDA / 61740 Project management Post Open - National 30,000.00 0.00 2019-04-29 2019-06-24 2019-12-21 ations Envelope ementation rogène pour l'UGP PMNDPE CI-PMNDPE-110625-GO-RFQ / Fourniture et installation d Request for Quot Single Stage - One Pending Impl IDA / 61740 Project management Post Open - National 20,000.00 0.00 2019-04-09 2019-06-04 2019-12-01 e consommables informatiq ations Envelope ementation ues pour le PMNDPE CI-PMNDPE-110621-GO-DIR / Fourniture et installation d' Pending Impl IDA / 61740 Project management Post Direct Selection Direct 160,000.00 0.00 2019-04-01 2019-04-11 2019-05-16 2019-11-12 un Progiciel de suivi et éval ementation uation spécifique au Projet CI-PMNDPE-110622-GO-DIR / Acquérir du matériel anthr opométrique, de démonstrat ion culinaire, d'éveil et les é Pending Impl quipements au profit des FR IDA / 61740 Project management Post Direct Selection Direct 600,000.00 0.00 2019-03-01 2019-03-06 2019-04-10 2019-10-07 ementation ANC (150 kits de matériel an thropométrique, 150 Kits de démonstration culinaire, 150 Kits d'éveil, et des équipeme nts sont disponibles) CI-PMNDPE-123693-GO-RFQ Request for Quot Single Stage - One Pending Impl / ACQUISITION DE MOBILIER IDA / 61740 Project management Post Open - National 60,000.00 0.00 2019-07-24 2019-09-18 2020-03-16 ations Envelope ementation S DE BUREAU COMPLÉMENT AIRE CI-PMNDPE-123698-GO-RFQ / FOURNITURE ET INSTALLAT Request for Quot Single Stage - One Pending Impl IDA / 61740 Project management Post Open - National 40,000.00 0.00 2019-08-05 2019-09-30 2020-03-28 ION DE MATÉRIELS INFORMA ations Envelope ementation TIQUES POUR LES ANTENNE S RÉGIONALES CI-PMNDPE-123700-GO-RFQ / FOURNITURE ET INSTALLAT Request for Quot Single Stage - One Pending Impl ION DE MOBILIERS DE BURE IDA / 61740 Project management Post Open - National 6,000.00 0.00 2019-08-05 2019-09-30 2020-03-28 ations Envelope ementation AU AUTRE QU'INFORMATIQU ES POUR LES ANTENNES RÉ GIONALES CI-PMNDPE-123701-GO-RFQ / FOURNITURE ET INSTALLAT Request for Quot Single Stage - One Pending Impl ION DE MATÉRIELS ET OUTIL IDA / 61740 Project management Post Open - National 8,000.00 0.00 2019-08-05 2019-09-30 2020-03-28 ations Envelope ementation LAGES TECHNIQUES POUR L ES ANTENNES RÉGIONALES CI-PMNDPE-123704-GO-RFP Request for Quot Single Stage - One / ACQUISITION DE VÉHICULE IDA / 61740 Project management Post Limited 400,000.00 286,092.07 Signed 2019-10-21 2019-09-26 2019-12-16 2019-11-07 2020-06-13 ations Envelope S POUR LES ANTENNES RÉGI ONALES CI-PMNDPE-123707-GO-RFP / ACQUISITION DE 31 MOTOS Request for Propo Single Stage - Two Under Imple POUR LES SUPERVISEURS D IDA / 61740 Project management Post Open - National 100,000.00 0.00 2019-07-31 2019-07-30 2019-08-05 2019-09-16 2019-11-29 2020-01-03 2020-07-01 sals Envelope mentation ANS LE CADRE DE LA MISE E N OEUVRE DES ACTIONS CO MMUNAUTAIRES CI-PMNDPE-123723-GO-DIR / ACQUÉRIR DU MATÉRIEL A NTHROPOMÉTRIQUE, DE DÉ MONSTRATION CULINAIRE, D 'ÉVEIL ET LES ÉQUIPEMENTS Pending Impl IDA / 61740 Project management Post Direct Selection Direct 600,000.00 0.00 2019-07-31 2019-08-05 2019-09-09 2020-03-07 AU PROFIT DES FRANC (150 ementation KITS DE MATÉRIEL ANTHROP OMÉTRIQUE, 150 KITS DE DÉ MONSTRATION CULINAIRE, 1 50 KITS D'ÉVEIL, ET DES ÉQ UIPEMENTS SONT DISPONIB LES) Page 1 CI-PMNDPE-123766-GO-RFQ Request for Quot Single Stage - One Pending Impl / ACQUISITION DE FOURNITU IDA / 61740 Project management Post Open - National 80,000.00 0.00 2019-07-24 2019-09-18 2020-03-16 ations Envelope ementation RES DE BUREAU POUR L’UG P CI-PMNDPE-123768-GO-RFQ / Fourniture et installation d Request for Quot Single Stage - One Pending Impl IDA / 61740 Project management Post Open - National 22,000.00 0.00 2019-07-24 2019-09-18 2020-03-16 e consommables informatiq ations Envelope ementation ues pour le PMNDPE CI-PMNDPE-139031-GO-RFQ Request for Quot Single Stage - One Pending Impl / Acquisition de GPS pour les IDA / 61740 Project management Post Open - National 20,000.00 0.00 2019-11-04 2019-12-30 2020-02-28 ations Envelope ementation véhicules du projet CI-PMNDPE-139035-GO-RFQ Request for Quot Single Stage - One Pending Impl / Fourniture et installation d' IDA / 61740 Project management Post Limited 40,000.00 0.00 2019-11-13 2020-01-08 2020-07-06 ations Envelope ementation un serveur pour l'UGP PMND PE CI-PMNDPE-72587-GO-DIR / Pending Impl Acquisition d'un GPS pour le IDA / 61740 Project management Post Direct Selection Direct 1.00 0.00 2018-09-05 2018-09-10 2018-10-06 2018-10-16 ementation s besoins du STP CNN CI-PMNDPE-183000-GO-RFQ / Fourniture et livraison de 7 Early child nutrition and dev Request for Quot Single Stage - One Under Imple véhicules (3 pour les antenn IDA / 61740 Post Open - National 500,000.00 0.00 2020-08-01 2020-09-26 2021-03-25 elopment interventions ations Envelope mentation es régionales, 3 pour le SE-C ONNAPE et 1 pour UGP PMN DPE) CI-PMNDPE-183004-GO-RFQ / Fourniture et livraison de Early child nutrition and dev Request for Quot Single Stage - One Pending Impl IDA / 61740 Post Open - National 80,000.00 0.00 2020-07-19 2020-09-13 2021-03-12 mobilier de bureau complém elopment interventions ations Envelope ementation entaire pour les antennes ré gionales CI-PMNDPE-183010-GO-RFQ / Fourniture et livraison de Early child nutrition and dev Request for Quot Single Stage - One Pending Impl IDA / 61740 Post Open - National 40,000.00 0.00 2020-08-04 2020-09-29 2021-03-28 matériels informatiques com elopment interventions ations Envelope ementation plémentaires pour les anten nes régionales CI-PMNDPE-183011-GO-RFQ / Fourniture et livraison d'ou Early child nutrition and dev Request for Quot Single Stage - One Pending Impl IDA / 61740 Post Limited 40,000.00 0.00 2020-08-02 2020-09-27 2021-03-26 tillages techniques complém elopment interventions ations Envelope ementation entaires pour les antennes r égionales CI-PMNDPE-183279-GO-RFQ Early child nutrition and dev Request for Quot Single Stage - One Pending Impl / Acquisition de fournitures d IDA / 61740 Post Open - National 80,000.00 0.00 2020-08-19 2020-10-14 2021-04-12 elopment interventions ations Envelope ementation e bureau pour l'UGP CI-PMNDPE-183519-GO-RFQ Early child nutrition and dev Request for Quot Single Stage - One Pending Impl / Fourniture de consommabl IDA / 61740 Post Limited 40,000.00 0.00 2020-08-17 2020-10-12 2021-04-10 elopment interventions ations Envelope ementation es informatiques pour l'UGP PMNDPE CI-PMNDPE-183533-GO-RFQ Early child nutrition and dev Request for Quot Single Stage - One Pending Impl / Acquisition de fournitures t IDA / 61740 Post Limited 60,000.00 0.00 2020-08-04 2020-09-29 2021-03-28 elopment interventions ations Envelope ementation echniques pour l'UGP CI-PMNDPE-183540-GO-DIR / Fourniture et livraison de 4 Early child nutrition and dev 5 motos au profit des superv IDA / 61740 Post Direct Selection Direct 138,000.00 120,942.29 Signed 2020-07-20 2020-03-16 2020-07-25 2020-03-30 2020-08-29 2020-06-06 2021-02-25 elopment interventions iseurs de 45 sous-préfecture s dans le cadre du PMNDPE CI-PMNDPE-184233-GO-DIR Early child nutrition and dev Pending Impl / Fourniture de carburant à l' IDA / 61740 Post Direct Selection Direct 150,000.00 0.00 2020-07-23 2020-07-28 2020-09-01 2021-02-28 elopment interventions ementation UGP PMNDPE au titre de l'an née 2020 CI-PMNDPE-185140-GO-RFB / Fournitures et livraison de Early child nutrition and dev Single Stage - One Under Imple IDA / 61740 Post Request for Bids Open - National 520,000.00 0.00 2020-08-31 2020-09-01 2020-09-05 2020-09-21 2020-10-17 2020-10-14 2020-11-16 2020-12-21 2021-06-19 130 motos pour les supervis elopment interventions Envelope mentation eurs dans le cadre du PMND PE CI-PMNDPE-233975-GO-RFQ Early child nutrition and dev Request for Quot Single Stage - One Pending Impl / Acquérir le matériel inform IDA / 61740 Post Limited 50,000.00 0.00 2021-06-23 2021-08-18 2022-02-14 elopment interventions ations Envelope ementation atique pour l'UGP CI-PMNDPE-233982-GO-RFQ Early child nutrition and dev Request for Quot Single Stage - One Under Imple / Acquérir des consommable IDA / 61740 Post Limited 50,000.00 0.00 2021-06-23 2021-02-18 2021-08-18 2022-02-14 elopment interventions ations Envelope mentation s informatiques pour l'UGP CI-PMNDPE-233965-GO-RFQ / Acquisition de fournitures d Early child nutrition and dev Request for Quot Single Stage - One Pending Impl IDA / 61740 Post Limited 60,000.00 0.00 2021-06-23 2021-08-18 2022-02-14 e bureau pour l'Unité de Ges elopment interventions ations Envelope ementation tion du POMNDPE CI-PMNDPE-233937-GO-RFQ Early child nutrition and dev Request for Quot Single Stage - One Pending Impl / Acquisition de matériels inf IDA / 61740 Post Limited 30,000.00 0.00 2021-06-23 2021-08-18 2022-02-14 elopment interventions ations Envelope ementation ormatiques pour les CORNA PE CI-PMNDPE-234039-NC-RFQ / Acquérir du matériel de lutt Early child nutrition and dev Request for Quot Single Stage - One Pending Impl e contre la COVID (Masques, IDA / 61740 Post Limited 60,000.00 0.00 2021-06-23 2021-08-18 2022-02-14 elopment interventions ations Envelope ementation dispositif de lavage des mai ns, gel hydroalcoolique, sav ons, etc) CI-PMNDPE-233894-GO-RFQ / Acquisition de matériels bu Early child nutrition and dev Request for Quot Single Stage - One Pending Impl IDA / 61740 Post Limited 70,000.00 0.00 2021-06-23 2021-08-18 2022-02-14 reautiques bureautiques et i elopment interventions ations Envelope ementation nformatiques pour le SE-CO NNAPE CI-PMNDPE-233959-GO-RFQ / Acquisition de matériels inf ormatiques, de fournitures d Early child nutrition and dev Request for Quot Single Stage - One Pending Impl IDA / 61740 Post Limited 66,000.00 0.00 2021-06-23 2021-08-18 2022-02-14 e bureau pour le SE-CONNAP elopment interventions ations Envelope ementation E, les Comités Régionaux de Nutrition et les ministères se ctoriels CI-PMNDPE-234016-NC-RFQ / Acquisition de matériels an thropométriques et kits de d Early child nutrition and dev Request for Quot Single Stage - One Pending Impl IDA / 61740 Post Limited 84,000.00 0.00 2021-06-30 2021-08-25 2022-02-21 émonstration culinaires pour elopment interventions ations Envelope ementation l'équipement des Unités Nut ritionnelles en supplémentat ion dans les centres sociaux CI-PMNDPE-233952-GO-RFQ Early child nutrition and dev Request for Quot Single Stage - One Pending Impl / Acquisition de fourniture d IDA / 61740 Post Limited 20,000.00 0.00 2021-06-23 2021-08-18 2022-02-14 elopment interventions ations Envelope ementation e bureau pour les CORNAPE CI-PMNDPE-234013-NC-RFQ Early child nutrition and dev Request for Quot Single Stage - One Pending Impl / Acquisition de kits d'alphab IDA / 61740 Post Limited 70,000.00 0.00 2021-07-27 2021-09-21 2022-03-20 elopment interventions ations Envelope ementation étisation pour l'équipement de 2000 FRANC CI-PMNDPE-241114-GO-RFQ Early child nutrition and dev Request for Quot Single Stage - One Pending Impl / Acquisition de groupe élect IDA / 61740 Post Limited 74,000.00 0.00 2021-07-25 2021-09-19 2022-03-18 elopment interventions ations Envelope ementation rogène pour le SE-CONNAPE CI-PMNDPE-268505-GO-DIR Early child nutrition and dev Pending Impl IDA / 61740 Post Direct Selection Direct 120,000.00 0.00 2021-06-03 2021-06-08 2021-07-13 2022-01-09 / Assurer le carburant elopment interventions ementation Page 2 CI-PMNDPE-271509-GO-RFB / Acquisition de kits de com munication (boîte à image, Guide de Réhabilitation Nutr Early child nutrition and dev Single Stage - One Pending Impl IDA / 61740 Post Request for Bids Open - National 239,268.00 0.00 2022-01-28 2022-02-02 2022-03-16 2022-04-15 2022-05-20 2022-11-16 itionnelle à base d'aliments l elopment interventions Envelope ementation ocaux (PASLOC) pour les FR ANC et les Unités Nutritionn elles de Soins (UNS) dans le s centres sociaux CI-PMNDPE-271513-GO-RFB / Acquisition de matériel de Early child nutrition and dev Single Stage - One Pending Impl IDA / 61740 Post Request for Bids Open - National 204,300.00 0.00 2022-01-26 2022-01-31 2022-03-14 2022-04-13 2022-05-18 2022-11-14 diffusion de film sur la Nutrit elopment interventions Envelope ementation ion et le Développement de l a Petite Enfance (DPE) CI-PMNDPE-271683-GO-RFQ Early child nutrition and dev Request for Quot Single Stage - One Pending Impl / Acquisition d'un matériel p IDA / 61740 Post Limited 20,000.00 0.00 2022-02-02 2022-03-30 2022-09-26 elopment interventions ations Envelope ementation our l'archivage numérique CI-PMNDPE-271694-GO-RFQ / Acquisition de fournitures d Early child nutrition and dev Request for Quot Single Stage - One Pending Impl IDA / 61740 Post Limited 20,000.00 0.00 2022-02-02 2022-03-30 2022-09-26 e bureau pour l’UGP au titre elopment interventions ations Envelope ementation de l’exercice 2022 CI-PMNDPE-271699-GO-RFQ / Acquisition des consomma Early child nutrition and dev Request for Quot Single Stage - One Pending Impl IDA / 61740 Post Limited 10,000.00 0.00 2022-02-02 2022-03-30 2022-09-26 bles informatiques pour l’UG elopment interventions ations Envelope ementation P au titre de l’exercice 2022 CI-PMNDPE-271704-GO-RFQ Early child nutrition and dev Request for Quot Single Stage - One Pending Impl / Acquisition de 10 motos au IDA / 61740 Post Limited 20,000.00 0.00 2022-03-02 2022-04-27 2022-10-24 elopment interventions ations Envelope ementation titre de l’exercice 2022 CI-PMNDPE-271703-GO-DIR / Fourniture de carburant po Early child nutrition and dev Pending Impl IDA / 61740 Post Direct Selection Direct 70,000.00 0.00 2022-03-25 2022-03-30 2022-05-04 2022-10-31 ur l’UGP avec Total CI au titr elopment interventions ementation e de l’exercice 2022 CI-PMNDPE-271507-GO-DIR / Fourniture et livraison de ki ts anthropométriques avec UNICEF (balances mères enf Early child nutrition and dev Under Imple IDA / 61740 Post Direct Selection Direct 146,783.00 0.00 2022-03-17 2022-03-08 2022-03-22 2022-03-01 2022-04-26 2022-10-23 ants, MUAC adultes, MUAC e elopment interventions mentation nfants) pour l’équipement d es FRANC et des Unités Nutr itionnelles de Soins (UNS) da ns les centres sociaux. CI-PMNDPE-271680-GO-RFB Early child nutrition and dev Request for Quot Single Stage - One Pending Impl / Production de gadgets (T-s IDA / 61740 Post Limited 50,000.00 0.00 2022-04-02 2022-05-28 2022-11-24 elopment interventions ations Envelope ementation hirts, polo, blocs-notes, Cale ndriers, Agenda) CI-PMNDPE-282122-CS-LCS / Fourniture d'intrants (Seme nces améliorées, engrais, et Early child nutrition and dev Request for Quot Single Stage - One Pending Impl petits outillages) pour l’appu IDA / 61740 Post Limited 60,000.00 0.00 2022-06-05 2022-07-31 2023-01-27 elopment interventions ations Envelope ementation i à la mise en place de parce lles communautaires pour al imenter les greniers commu nautaires CI-PMNDPE-310932-GO-RFQ / Fourniture et installation d Early child nutrition and dev Single Stage - One Pending Impl e panneaux photovoltaïques IDA / 61740 Post Request for Bids Open - National 100,000.00 0.00 2022-10-04 2022-10-09 2022-11-20 2022-12-20 2023-01-24 2023-07-23 elopment interventions Envelope ementation dans 12 sites de productions maraîchères dans les région s du PORO et de la Bagoué CI-PMNDPE-328787-GO-RFQ / Souscription de police d’as Early child nutrition and dev Request for Quot Single Stage - One Pending Impl IDA / 61740 Post Limited 80,000.00 0.00 2022-12-11 2023-02-05 2023-08-04 surance maladie pour le per elopment interventions ations Envelope ementation sonnel du PMNDPE au titre d e l’année 2023 CI-PMNDPE-328788-GO-RFQ / Souscription de police d’as Early child nutrition and dev Request for Quot Single Stage - One Pending Impl surance individuelle acciden IDA / 61740 Post Limited 5,400.00 0.00 2022-12-11 2023-02-05 2023-08-04 elopment interventions ations Envelope ementation t pour le personnel du PMND PE au titre de l’année 2023 CI-PMNDPE-328789-GO-RFQ / Souscription de police d’as Early child nutrition and dev Request for Quot Single Stage - One Pending Impl IDA / 61740 Post Limited 6,400.00 0.00 2022-12-11 2023-02-05 2023-08-04 surance multirisque professi elopment interventions ations Envelope ementation onnelle au titre de l’année 2 023 CI-PMNDPE-328790-GO-RFQ / Souscription de police d’as Early child nutrition and dev Request for Quot Single Stage - One Pending Impl surance responsabilité civile IDA / 61740 Post Limited 1,200.00 0.00 2022-12-11 2023-02-05 2023-08-04 elopment interventions ations Envelope ementation professionnelle pour le pers onnel du PMNDPE au titre de l’année 2023 CI-PMNDPE-328791-GO-RFQ / Souscription de police d’as Early child nutrition and dev Request for Quot Single Stage - One Pending Impl IDA / 61740 Post Limited 16,700.00 0.00 2022-12-11 2023-02-05 2023-08-04 surance automobile au profit elopment interventions ations Envelope ementation des véhicules du PMNDPE au titre de l’année 2023 CI-PMNDPE-342584-GO-DIR / Acquisition de kits culinaire Early child nutrition and dev Pending Impl s des UNS (Unités Nutritionn IDA / 61740 Post Direct Selection Direct - National 33,333.00 0.00 2023-02-28 2023-03-05 2023-04-09 2023-10-06 elopment interventions ementation elles de Supplémentation) d ans les centres sociaux CI-PMNDPE-342670-GO-DIR / Fourniture d’intrants, de N oyaux d'élevages au bénéfic e des ménages vulnérables ( Early child nutrition and dev Pending Impl IDA / 61740 Post Direct Selection Direct - National 75,000.00 0.00 2023-02-28 2023-03-05 2023-04-09 2023-10-06 ayant des cas de MAS) avec elopment interventions ementation le MIRAH dans le cadre d’un appui à la mise en place de petits élevages (petits rumin ants et volaille) et de jardins potagers CI-PMNDPE-342675-GO-RFQ Early child nutrition and dev Request for Quot Single Stage - One Pending Impl IDA / 61740 Post Limited 25,000.00 0.00 2023-03-05 2023-04-30 2023-10-27 / Acquisition de matériel info elopment interventions ations Envelope ementation rmatique CI-PMNDPE-342686-GO-RFQ / Acquisition des boîtes à ph Early child nutrition and dev Request for Quot Single Stage - One Pending Impl IDA / 61740 Post Limited 88,000.00 0.00 2023-03-05 2023-04-30 2023-10-27 armacie pour les sites FRAN elopment interventions ations Envelope ementation C, UGP, UGPR, et véhicules d e mission CI-PMNDPE-343124-GO-RFQ Early child nutrition and dev Request for Quot Single Stage - One Pending Impl IDA / 61740 Post Limited 75,000.00 0.00 2023-03-05 2023-04-30 2023-10-27 / Acquérir du Mobilier de bur elopment interventions ations Envelope ementation eaux CI-PMNDPE-343147-GO-DIR Early child nutrition and dev Pending Impl / Fourniture de carburant à l’ IDA / 61740 Post Direct Selection Direct - National 131,416.00 0.00 2023-03-31 2023-04-05 2023-05-10 2023-11-06 elopment interventions ementation UGP avec TOTAL CI au titre de l’exercice 2023 NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualificatio Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendatio Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus n Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes n for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 3 CI-PMNDPE-72668-NC-RFQ / Recrutement d'un Prestatair Pending Impl e pour la fourniture de polic IDA / 61740 Project management Post Direct Selection Direct 5,000.00 0.00 2018-08-22 2018-08-27 2018-10-01 2019-03-30 ementation es d'assurances pour le véhi cule acquis pour les besoins du STP CI-PMNDPE-110627-NC-RFQ Request for Quot Single Stage - One Pending Impl / Assurer les charges de com IDA / 61740 Project management Post Open - National 20,000.00 0.00 2019-03-05 2019-05-03 2019-10-30 ations Envelope ementation munication du personnel CI-PMNDPE-110631-NC-DIR Pending Impl / Acquisition de carburant po IDA / 61740 Project management Post Direct Selection Direct 60,000.00 0.00 2019-03-15 2019-03-20 2019-04-24 2019-10-21 ementation ur l'UGP PMNDPE CI-PMNDPE-110623-NC-RFB / Vulgariser le plan de comm Nutrition governance and m Single Stage - One Pending Impl IDA / 61740 Post Request for Bids Open - National 120,000.00 0.00 2019-04-15 2019-04-20 2019-06-01 2019-07-01 2019-08-05 2020-02-01 unication intégré et multisec anagement Envelope ementation toriel (2000 exemplaires du PICM) CI-PMNDPE-110687-NC-RFQ Nutrition governance and m Request for Quot Single Stage - One Pending Impl / Reproduire en série les sup IDA / 61740 Post Open - National 100,000.00 0.00 2019-04-20 2019-06-15 2019-12-12 anagement ations Envelope ementation ports de communication CI-PMNDPE-110626-NC-RFQ / Reproduire les supports de Nutrition governance and m Request for Quot Single Stage - One Pending Impl IDA / 61740 Post Open - National 40,000.00 0.00 2019-04-20 2019-06-15 2019-12-12 formation pour 1000 structu anagement ations Envelope ementation res dotées de kit de formatio n dans les régions CI-PMNDPE-110630-NC-RFQ Request for Quot Single Stage - One Pending Impl / Assurer les frais d'entretien IDA / 61740 Project management Post Open - National 7,000.00 0.00 2019-06-20 2019-08-15 2020-02-11 ations Envelope ementation des véhicules CI-PMNDPE-110639-NC-RFQ / Acquisition de petits matéri els de bureau et fournitures Request for Quot Single Stage - One Pending Impl IDA / 61740 Project management Post Open - National 30,000.00 0.00 2019-03-29 2019-05-16 2019-11-12 (électroménagers, assiette e ations Envelope ementation t autres liés à la cuisine et r estauration du personnel du PMNDPE CI-PMNDPE-110636-NC-RFQ Request for Quot Single Stage - One Pending Impl / Aménagement des locaux ( IDA / 61740 Project management Post Open - National 100,000.00 0.00 2019-03-16 2019-05-03 2019-10-30 ations Envelope ementation cloisonnement, câblage rése au) CI-PMNDPE-110637-NC-RFQ Request for Quot Single Stage - One Pending Impl / Service de nettoyage des l IDA / 61740 Project management Post Open - National 30,000.00 0.00 2019-03-27 2019-05-16 2019-11-12 ations Envelope ementation ocaux du PMNDPE CI-PMNDPE-123716-NC-RFB / VULGARISER LE PLAN DE C Nutrition governance and m Single Stage - One Pending Impl IDA / 61740 Post Request for Bids Open - National 120,000.00 0.00 2019-08-30 2019-09-04 2019-10-16 2019-11-15 2019-12-20 2020-06-17 OMMUNICATION INTÉGRÉ ET anagement Envelope ementation MULTI SECTORIEL 2000 EXE MPLAIRES DU PICM CI-PMNDPE-123714-NC-RFQ Nutrition governance and m Request for Quot Single Stage - One Pending Impl / Reproduire en série les sup IDA / 61740 Post Open - National 100,000.00 0.00 2019-09-04 2019-10-30 2020-04-27 anagement ations Envelope ementation ports de communication CI-PMNDPE-123717-NC-RFQ / Reproduire les supports de Nutrition governance and m Request for Quot Single Stage - One Pending Impl IDA / 61740 Post Open - National 40,000.00 0.00 2019-09-04 2019-10-30 2020-04-27 formation pour 1000 structu anagement ations Envelope ementation res dotées de kit de formatio n dans les régions CI-PMNDPE-123719-NC-RFQ Request for Quot Single Stage - One Pending Impl / Assurer les charges de com IDA / 61740 Project management Post Open - National 20,000.00 0.00 2019-08-05 2019-09-30 2020-03-28 ations Envelope ementation munication du personnel CI-PMNDPE-123720-NC-RFP Request for Propo Single Stage - Two Pending Impl / ASSURER LES FRAIS D'ENT IDA / 61740 Project management Post Open - National 7,000.00 0.00 2019-08-30 2019-09-04 2019-10-16 2019-12-29 2020-02-02 2020-07-31 sals Envelope ementation RETIEN DES VÉHICULES CI-PMNDPE-123721-NC-DIR / FOURNITURE DE SERVICES Pending Impl DE POLICE D’ASSURANCES, IDA / 61740 Project management Post Direct Selection Direct 20,000.00 0.00 2019-07-31 2019-08-05 2019-09-09 2020-03-07 ementation AUTOMOBILES POUR LES 4 V ÉHICULES ACQUIS DANS LE CADRE DU PMNDPE CI-PMNDPE-123728-NC-RFP / ACQUÉRIR DU MATÉRIEL A NTHROPOMÉTRIQUE, DE DÉ MONSTRATION CULINAIRE, D 'ÉVEIL ET LES ÉQUIPEMENTS Request for Propo Single Stage - Two Pending Impl IDA / 61740 Project management Post Open - National 30,000.00 0.00 2019-07-31 2019-08-05 2019-09-16 2019-11-29 2020-01-03 2020-07-01 AU PROFIT DES FRANC (150 sals Envelope ementation KITS DE MATÉRIEL ANTHROP OMÉTRIQUE, 150 KITS DE DÉ MONSTRATION CULINAIRE, 1 50 KITS D'ÉVEIL, ET DES ÉQ UIPEMENTS SONT DISPONIB LES) CI-PMNDPE-123730-NC-RFP / RÉHABILITATION DES LOCA Request for Propo Single Stage - Two Pending Impl IDA / 61740 Project management Post Open - National 90,000.00 0.00 2019-07-31 2019-08-05 2019-09-16 2019-11-29 2020-01-03 2020-07-01 UX DE TROIS ANTENNES RÉ sals Envelope ementation GIONALES (KORHOGO, BON DOUKOU ET ODIENNÉ) CI-PMNDPE-123734-NC-RFP / MAINTENANCE D’UN PROG Request for Propo Single Stage - Two Pending Impl IDA / 61740 Project management Post Open - National 50,000.00 0.00 2019-09-02 2019-09-07 2019-10-19 2020-01-01 2020-02-05 2020-08-03 ICIEL DE SUIVI ET ÉVALUATI sals Envelope ementation ON SPÉCIFIQUE AU PROJET CI-PMNDPE-123743-NC-RFP Request for Propo Single Stage - Two Pending Impl / SERVICE DE GARDIENNAGE IDA / 61740 Project management Post Open - National 18,000.00 0.00 2019-07-19 2019-07-24 2019-09-04 2019-11-17 2019-12-22 2020-06-19 sals Envelope ementation DES LOCAUX DU PMNDPE CI-PMNDPE-123746-NC-RFP Request for Propo Single Stage - Two Pending Impl / SERVICE DE NETTOYAGE D IDA / 61740 Project management Post Open - National 30,000.00 0.00 2019-07-19 2019-07-24 2019-09-04 2019-11-17 2019-12-22 2020-06-19 sals Envelope ementation ES LOCAUX DU PMNDPE CI-PMNDPE-123748-NC-RFP / TRAVAUX DE CÂBLAGE DE Request for Propo Single Stage - Two Pending Impl S NOUVEAUX LOCAUX DU P IDA / 61740 Project management Post Open - National 20,000.00 0.00 2019-07-19 2019-07-24 2019-09-04 2019-11-17 2019-12-22 2020-06-19 sals Envelope ementation MNDPE ET FOURNITURE ET I NSTALLATION D’UN AUTOCO MMUTATEUR CI-PMNDPE-123749-NC-RFP / FOURNITURE ET POSE D’U Request for Propo Single Stage - Two Pending Impl NE ENSEIGNE LUMINEUSE + IDA / 61740 Project management Post Open - National 30,000.00 0.00 2019-07-19 2019-07-24 2019-09-04 2019-11-17 2019-12-22 2020-06-19 sals Envelope ementation PANNEAUX DIRECTIONNELS DES NOUVEAUX LOCAUX DU PMNDPE CI-PMNDPE-123750-NC-RFQ Request for Quot Single Stage - One Pending Impl / TRAVAUX DE PLOMBERIE D IDA / 61740 Project management Post Open - National 3,000.00 0.00 2019-07-24 2019-09-18 2020-03-16 ations Envelope ementation ES NOUVEAUX LOCAUX DU P MNDPE CI-PMNDPE-123751-NC-RFP / TRAVAUX D’AMÉNAGEMEN Request for Propo Single Stage - Two Pending Impl T DU BÂTIMENT ANNEXE DE IDA / 61740 Project management Post Open - National 80,000.00 0.00 2019-07-19 2019-07-24 2019-09-04 2019-11-17 2019-12-22 2020-06-19 sals Envelope ementation S NOUVEAUX LOCAUX DU P MNDPE (CONTENEUR MODU LAIRE) CI-PMNDPE-123753-NC-RFP / TRAVAUX D’AMÉNAGEMEN Request for Propo Single Stage - Two Pending Impl IDA / 61740 Project management Post Open - National 60,000.00 0.00 2019-07-19 2019-07-24 2019-09-04 2019-11-17 2019-12-22 2020-06-19 T DU BÂTIMENT PRINCIPAL D sals Envelope ementation ES NOUVEAUX LOCAUX DU P MNDPE Page 4 CI-PMNDPE-123756-NC-RFP / FOURNITURE ET INSTALLAT Request for Quot Single Stage - One Pending Impl IDA / 61740 Project management Post Limited 80,000.00 0.00 2019-10-23 2019-12-18 2020-06-15 ION D’UN GROUPE ÉLECTRO ations Envelope ementation GÈNE + TRAVAUX D’ÉLECTR ICITÉ CI-PMNDPE-123759-NC-RFQ Request for Quot Single Stage - One Pending Impl / FOURNITURE ET POSE DE S IDA / 61740 Project management Post Open - National 30,000.00 0.00 2019-07-24 2019-09-18 2020-03-16 ations Envelope ementation PLITS DES NOUVEAUX LOCA UX DU PMNDPE CI-PMNDPE-139042-NC-RFQ Request for Quot Single Stage - One Pending Impl / Sélection d’un garage pour IDA / 61740 Project management Post Open - National 20,000.00 0.00 2019-11-04 2019-12-30 2019-12-31 ations Envelope ementation l’entretien des véhicules du Projet à Abidjan CI-PMNDPE-139051-NC-RFQ / Sélection d’un garage pour Request for Quot Single Stage - One Pending Impl l’entretien des véhicules du IDA / 61740 Project management Post Open - National 5,000.00 0.00 2019-11-04 2019-12-30 2020-06-27 ations Envelope ementation Projet dans les antennes rég ionales du Poro, Tchologo et Bagoué CI-PMNDPE-139056-NC-RFQ / Sélection d’un prestataire Request for Quot Single Stage - One Pending Impl IDA / 61740 Project management Post Open - National 20,000.00 0.00 2019-11-04 2019-12-30 2020-06-27 pour l’entretien et la mainte ations Envelope ementation nance du matériel informati que à Abidjan CI-PMNDPE-139066-NC-RFQ / Sélection d’un prestataire pour l’entretien et la mainte Request for Quot Single Stage - One Pending Impl IDA / 61740 Project management Post Limited 5,000.00 0.00 2019-12-04 2020-01-29 2020-07-27 nance du matériel informati ations Envelope ementation que dans les antennes régio nales du Poro, Tchologo et B agoué CI-PMNDPE-139069-NC-RFQ / Sélection d’un prestataire Request for Quot Single Stage - One Pending Impl IDA / 61740 Project management Post Open - National 20,000.00 0.00 2019-11-04 2019-12-30 2020-06-27 pour l’entretien des splits et ations Envelope ementation climatiseurs à Abidjan CI-PMNDPE-139094-NC-RFQ / Sélection d’un prestataire Request for Quot Single Stage - One Pending Impl IDA / 61740 Project management Post Open - National 20,000.00 0.00 2019-11-04 2019-12-30 2020-06-27 pour l’entretien de la plomb ations Envelope ementation erie- Electricité et menuiseri e à Abidjan CI-PMNDPE-139117-NC-RFQ / Sélection d’un prestataire pour l’entretien de la plomb Request for Quot Single Stage - One Pending Impl IDA / 61740 Project management Post Open - National 5,000.00 0.00 2019-11-04 2019-12-30 2020-06-27 erie- Electricité et menuiseri ations Envelope ementation e dans les antennes régional es du Poro, Tchologo et Bag oué CI-PMNDPE-139122-NC-RFQ / Sélection d’un prestataire Request for Quot Single Stage - One Pending Impl IDA / V1050 Project management Post Open - National 10,000.00 0.00 2019-11-04 2019-12-30 2020-06-27 pour l’entretien et la mainte ations Envelope ementation nance du matériel informati que à Abidjan CI-PMNDPE-139126-NC-RFQ / Sélection d’un prestataire pour l’entretien et la mainte Request for Quot Single Stage - One Pending Impl IDA / 61740 Project management Post Open - National 5,000.00 0.00 2019-11-04 2019-12-30 2020-06-27 nance du matériel informati ations Envelope ementation que dans les antennes régio nales du Poro, Tchologo et B agoué CI-PMNDPE-139128-NC-RFQ / Sélection d’un prestataire Request for Quot Single Stage - One Pending Impl pour l’entretien et la mainte IDA / 61740 Project management Post Open - National 10,000.00 0.00 2019-11-04 2019-12-30 2020-06-27 ations Envelope ementation nance des copieurs, imprima ntes, vidéoprojecteurs et ap pareils photos à Abidjan CI-PMNDPE-139131-NC-RFQ / Sélection d’un prestataire pour l’entretien et la mainte Request for Quot Single Stage - One Pending Impl nance des copieurs, imprima IDA / 61740 Project management Post Open - National 5,000.00 0.00 2019-11-05 2019-12-31 2020-06-28 ations Envelope ementation ntes, vidéoprojecteurs et ap pareils photos dans les ante nnes régionales du Poro, Tch ologo et Bagoué CI-PMNDPE-139135-NC-RFQ / Fourniture de services de g Request for Quot Single Stage - One Pending Impl IDA / 61740 Project management Post Open - National 20,000.00 0.00 2019-11-04 2019-12-30 2020-06-27 ardiennage pour les locaux ations Envelope ementation du bureau régional du PMND PE – KORHOGO CI-PMNDPE-139137-NC-RFQ / Fourniture de services d'en Request for Quot Single Stage - One Pending Impl IDA / 61740 Project management Post Open - National 20,000.00 0.00 2019-11-05 2019-12-31 2020-06-28 tretien et de nettoyage des l ations Envelope ementation ocaux du bureau régional du PMNDPE – KORHOGO CI-PMNDPE-139141-NC-RFQ Request for Quot Single Stage - One Pending Impl / Entretien du groupe électro IDA / 61740 Project management Post Open - National 10,000.00 0.00 2020-01-05 2020-03-01 2020-08-28 ations Envelope ementation gène du PMNDPE à Abidjan CI-PMNDPE-139178-NC-RFQ / Travaux de câblage des no Request for Quot Single Stage - One Pending Impl IDA / 61740 Project management Post Limited 40,000.00 0.00 2019-10-13 2019-12-08 2020-06-05 uveaux locaux du PMNDPE e ations Envelope ementation t fourniture et installation d’ un autocommutateur CI-PMNDPE-183557-NC-DIR / Reproduction et distributio n de 170 Kits (Boîtes à Imag es AEN/DPE, guides de réha Early child nutrition and dev Pending Impl bilitation nutritionnelle à bas IDA / 61740 Post Direct Selection Direct 40,000.00 0.00 2020-07-17 2020-07-22 2020-08-26 2021-02-22 elopment interventions ementation e d’aliments locaux, Guide- Mémoires pour les soins et s outiens nutritionnels, guide national de recette pour l’ali mentation de complément, t abl CI-PMNDPE-183563-NC-RFQ / Mise en place et équipeme Early child nutrition and dev Request for Quot Single Stage - One Pending Impl IDA / 61740 Post Limited 100,000.00 0.00 2020-08-29 2020-10-24 2021-04-22 nts des Unités nutritionnels elopment interventions ations Envelope ementation de supplémentaires (UNS) d ans les centres sociaux CI-PMNDPE-183710-NC-RFQ / Appui au SE CONNAPE pour Early child nutrition and dev Request for Quot Single Stage - One Pending Impl IDA / 61740 Post Limited 70,000.00 0.00 2020-08-18 2020-10-13 2021-04-11 les travaux d'aménagement elopment interventions ations Envelope ementation des nouveaux locaux à usag e de bureau CI-PMNDPE-183734-NC-RFQ / Acquisition et Équipement Early child nutrition and dev Request for Quot Single Stage - One Pending Impl IDA / 61740 Post Open - National 70,000.00 0.00 2020-08-29 2020-10-24 2021-04-22 des FRANC en 2000 kits d'al elopment interventions ations Envelope ementation phabétisation révisés CI-PMNDPE-183735-NC-RFQ / Reproduction des supports Early child nutrition and dev Request for Quot Single Stage - One Pending Impl IDA / 61740 Post Limited 10,000.00 0.00 2020-08-29 2020-10-24 2021-04-22 de formation du Corps préfe elopment interventions ations Envelope ementation ctoral et AEL (Environ 20 ex emplaires de chaque) CI-PMNDPE-183737-NC-DIR / Convention avec les radios Early child nutrition and dev Pending Impl de proximité pour la product IDA / 61740 Post Direct Selection Direct 55,000.00 0.00 2020-07-24 2020-07-29 2020-09-02 2021-03-01 elopment interventions ementation ion et la diffusion d'émission s interactives communautair es CI-PMNDPE-184236-NC-DIR Early child nutrition and dev Pending Impl / Assurance maladie, autom IDA / 61740 Post Direct Selection Direct 180,000.00 0.00 2020-07-23 2020-07-28 2020-09-01 2021-02-28 elopment interventions ementation obile, exploitation et individ uelle accident Page 5 CI-PMNDPE-184239-NC-RFQ / Enseigne lumineuse des lo Early child nutrition and dev Request for Quot Single Stage - One Pending Impl caux des antennes régionale IDA / 61740 Post Limited 24,000.00 0.00 2020-08-26 2020-10-21 2021-04-19 elopment interventions ations Envelope ementation s (Korhogo, Bondoukou, Ség uéla, Odienné, Bouaflé et Da oukro) CI-PMNDPE-184241-NC-RFQ / Recrutement d'un Prestatai Early child nutrition and dev Request for Quot Single Stage - One Pending Impl IDA / 61740 Post Open - National 5,000.00 0.00 2020-08-05 2020-09-30 2021-03-29 re pour l'entretien des centr elopment interventions ations Envelope ementation aux téléphoniques et autoco mmutateur CI-PMNDPE-184243-NC-RFQ / Aménagement des locaux ( Early child nutrition and dev Request for Quot Single Stage - One Pending Impl IDA / 61740 Post Limited 10,000.00 0.00 2020-08-18 2020-10-13 2021-04-11 pause de pavés dans la cour elopment interventions ations Envelope ementation et pause de rideaux) pour l' UGP PMNDPE CI-PMNDPE-184966-NC-DIR / Acquisition par entente dir ecte, de matériels anthropo métriques (balances électro Early child nutrition and dev IDA / 61740 Post Direct Selection Direct 208,000.00 186,215.26 Signed 2020-07-31 2020-07-19 2020-08-05 2020-07-21 2020-09-09 2020-09-17 2021-03-08 niques (350),MUAC adultes ( elopment interventions 300) et MUAC enfants (300) dans le cadre de la conduite des interventions communa utaires du PMNDPE CI-PMNDPE-185145-NC-RFQ Early child nutrition and dev Request for Quot Single Stage - One / Recrutement d'un prestatai IDA / 61740 Post Limited 20,000.00 11,024.71 Signed 2020-07-29 2020-04-23 2020-09-23 2020-07-15 2021-03-22 elopment interventions ations Envelope re pour la création du site W eb pour le PMNDPE CI-PMNDPE-190080-NC-RFB / Reproduction de supports de communication et de doc uments de base en nutrition Early child nutrition and dev Single Stage - One (Boîtes à Images AEN/DPE, g IDA / 61740 Post Request for Bids Open - National 750,000.00 252,937.78 Signed 2020-09-08 2020-08-11 2020-09-13 2020-08-26 2020-10-25 2020-09-22 2020-11-24 2020-09-25 2020-12-29 2020-11-17 2021-06-27 elopment interventions Envelope uides de réhabilitation nutrit ionnelle à base d’aliments lo caux, Guide-Mémoires pour l es soins et soutiens nutrition nels, guide national de recet te CI-PMNDPE-233994-NC-RFQ / Reproduire les maquettes et outils de communication en rapport avec la nutrition Early child nutrition and dev Request for Quot Single Stage - One Pending Impl IDA / 61740 Post Limited 60,000.00 0.00 2021-06-23 2021-08-18 2022-02-14 et le DPE (supports de com elopment interventions ations Envelope ementation munication intégrant la pro motion des comportements sur la nutrition, la stimulatio n et l'éveil au niveau commu nautaire) CI-PMNDPE-234031-NC-RFQ Early child nutrition and dev Request for Quot Single Stage - One Pending Impl / Reproduire les supports de IDA / 61740 Post Limited 10,000.00 0.00 2021-06-23 2021-08-18 2022-02-14 elopment interventions ations Envelope ementation communication du corps pré fectoral CI-PMNDPE-234310-NC-DIR Early child nutrition and dev Request for Quot Single Stage - One Pending Impl / Sélection d'un prestataire p IDA / 61740 Post Limited 60,000.00 0.00 2021-07-25 2021-09-19 2022-03-18 elopment interventions ations Envelope ementation our assurer les frais d'entreti en des véhicules CI-PMNDPE-234342-NC-DIR Early child nutrition and dev Request for Quot Single Stage - One Pending Impl IDA / 61740 Post Limited 60,000.00 0.00 2021-07-07 2021-09-01 2022-02-28 / Assurances automobiles et elopment interventions ations Envelope ementation exploitation CI-PMNDPE-241118-NC-DIR / Recrutement d’un prestatai Early child nutrition and dev Under Imple re pour la Maintenance et l’a IDA / 61740 Post Direct Selection Direct 12,000.00 0.00 2021-07-20 2021-09-03 2021-07-25 2021-09-08 2021-08-29 2022-02-25 elopment interventions mentation ssistance sur les logiciels to mate pour le compte de l’un ité de gestion du PMNDPE CI-PMNDPE-267590-NC-RFQ / Assurance maladie et indivi Early child nutrition and dev Request for Quot Single Stage - One Pending Impl IDA / 61740 Post Limited 100,000.00 0.00 2021-12-25 2022-02-19 2022-08-18 duelle accident du personnel elopment interventions ations Envelope ementation de l'UGP PMNDPE CI-PMNDPE-271706-NC-RFB Early child nutrition and dev Single Stage - One Pending Impl / Confection de pancartes po IDA / 61740 Post Request for Bids Open - National 175,000.00 0.00 2022-02-03 2022-02-08 2022-03-22 2022-04-21 2022-05-26 2022-11-22 elopment interventions Envelope ementation ur la visibilité des FRANC CI-PMNDPE-271708-NC-RFQ / Sélection d’une compagnie d’assurance pour Early child nutrition and dev Request for Quot Single Stage - One Pending Impl IDA / 61740 Post Limited 86,000.00 0.00 2022-01-26 2022-03-23 2022-09-19 l’Assurance maladie en fave elopment interventions ations Envelope ementation ur du personnel de l’UGP sur Part Bailleur au titre de l’exe rcice 2022 CI-PMNDPE-271709-NC-RFQ / Sélection d’une compagnie d’assurance pour l’assuranc Early child nutrition and dev Request for Quot Single Stage - One Pending Impl IDA / 61740 Post Limited 10,400.00 0.00 2022-01-26 2022-03-23 2022-09-19 e individuelle accident en fa elopment interventions ations Envelope ementation veur du personnel de l’UGP sur Part Bailleur au titre de l’ exercice 2022 CI-PMNDPE-271710-NC-RFQ / Sélection d’une compagnie Early child nutrition and dev Request for Quot Single Stage - One Pending Impl d’assurance pour l’assuranc IDA / 61740 Post Limited 34,000.00 0.00 2022-01-26 2022-03-23 2022-09-19 elopment interventions ations Envelope ementation e automobile et exploitation des véhicules du projet au ti tre de l’exercice 2022 CI-PMNDPE-271711-NC-RFQ / Sélection d’une compagnie Early child nutrition and dev Request for Quot Single Stage - One Pending Impl d’assurance pour l’assuranc IDA / 61740 Post Limited 7,000.00 0.00 2022-01-26 2022-03-23 2022-09-19 elopment interventions ations Envelope ementation e multirisque professionnelle des locaux de l’UGP au titre de l’exercice 2022 CI-PMNDPE-271712-NC-RFQ / Sélection d’une compagnie Early child nutrition and dev Request for Quot Single Stage - One Pending Impl d’assurance pour l’assuranc IDA / 61740 Post Limited 3,000.00 0.00 2022-01-26 2022-03-23 2022-09-19 elopment interventions ations Envelope ementation e responsabilité civile profes sionnelle au titre de l’exercic e 2022 CI-PMNDPE-271707-NC-RFQ Early child nutrition and dev Request for Quot Single Stage - One Pending Impl / Acquisition de serveur infor IDA / 61740 Post Limited 20,000.00 0.00 2022-03-16 2022-05-11 2022-11-07 elopment interventions ations Envelope ementation matique (serveur cloud) CI-PMNDPE-271705-NC-RFB / Reproduction des supports de communication intégrant Early child nutrition and dev Single Stage - One Pending Impl IDA / 61740 Post Request for Bids Open - National 200,000.00 0.00 2022-05-12 2022-05-17 2022-06-28 2022-07-28 2022-09-01 2023-02-28 la promotion des comporte elopment interventions Envelope ementation ments sur la nutrition, la sti mulation et l'éveil au niveau communautaire CI-PMNDPE-271773-NC-DIR / Recrutement de l’AEL GFM 3 (GENERATION FEMME DU Early child nutrition and dev Pending Impl 3ème MILLEMAIRE) pour pou IDA / 61740 Post Direct Selection Direct 119,192.00 0.00 2022-03-11 2022-03-16 2022-04-20 2022-10-17 elopment interventions ementation rsuivre la mise en œuvre de s activités communautaires dans la région du Poro dans 15 villages dans le cadre du PMNDPE CI-PMNDPE-332597-NC-RFQ / Migration du logiciel TOM2 PRO V2, version Windows en Early child nutrition and dev Request for Quot Single Stage - One Pending Impl sa version évoluée Full web IDA / 61740 Post Limited 27,658.00 0.00 2022-12-28 2023-02-22 2023-08-21 elopment interventions ations Envelope ementation (TOM2PRO Full Web), y com pris l’hébergement et l’infog érance sur un serveur distan t pendant une période de 24 mois Page 6 CI-PMNDPE-342709-NC-RFQ Early child nutrition and dev Request for Quot Single Stage - One Pending Impl IDA / 61740 Post Limited 87,000.00 0.00 2023-04-02 2023-05-28 2023-11-24 / Reprographie du guide réfé elopment interventions ations Envelope ementation rentiel CI-PMNDPE-342728-NC-RFQ Early child nutrition and dev Request for Quot Single Stage - One Pending Impl / Reprographie des manuels IDA / 61740 Post Limited 91,666.00 0.00 2023-03-01 2023-04-26 2023-10-23 elopment interventions ations Envelope ementation de formations et de la boîte à image CI-PMNDPE-342731-NC-RFQ Early child nutrition and dev Request for Quot Single Stage - One Pending Impl / Conception et production d IDA / 61740 Post Limited 35,500.00 0.00 2023-03-14 2023-05-09 2023-11-05 elopment interventions ations Envelope ementation e gadgets dans le cadre de l a foire au FRANC CI-PMNDPE-342734-NC-RFB Early child nutrition and dev Single Stage - One Pending Impl / Diffusion d'affiches sur des IDA / 61740 Post Request for Bids Open - National 166,666.00 0.00 2023-03-28 2023-04-02 2023-05-14 2023-06-13 2023-07-18 2024-01-14 elopment interventions Envelope ementation panneaux routiers CI-PMNDPE-342780-NC-RFB / Reproduction des supports de communication intégrant Early child nutrition and dev Single Stage - One Pending Impl la promotion des comporte IDA / 61740 Post Request for Bids Open - National 203,333.00 0.00 2023-03-31 2023-04-05 2023-05-17 2023-06-16 2023-07-21 2024-01-17 elopment interventions Envelope ementation ments sur la nutrition, l'alim entation et le développemen t de la petite enfance au niv eau communautaire CI-PMNDPE-342782-NC-RFB / Production des gadgets int égrant la promotion des com Early child nutrition and dev Single Stage - One Pending Impl IDA / 61740 Post Request for Bids Open - National 312,500.00 0.00 2023-03-31 2023-04-05 2023-05-17 2023-06-16 2023-07-21 2024-01-17 portements sur la nutrition, l elopment interventions Envelope ementation 'alimentation et le développ ement de la petite enfance a u niveau communautaire CI-PMNDPE-342785-NC-RFQ / Réaliser la maintenance du Early child nutrition and dev Request for Quot Single Stage - One Pending Impl IDA / 61740 Post Limited 16,666.00 0.00 2023-04-05 2023-05-31 2023-11-27 SISE (Système Informatisé d elopment interventions ations Envelope ementation e Suivi Evaluation) du projet CI-PMNDPE-342789-NC-RFB Early child nutrition and dev Single Stage - One Pending Impl / Confection de pancartes po IDA / 61740 Post Request for Bids Open - National 166,666.00 0.00 2023-03-24 2023-03-29 2023-05-10 2023-06-09 2023-07-14 2024-01-10 elopment interventions Envelope ementation ur la visibilité des FRANC CI-PMNDPE-343139-NC-RFQ Early child nutrition and dev Request for Quot Single Stage - One Pending Impl / Reprographie de la revue a IDA / 61740 Post Limited 50,000.00 0.00 2023-10-04 2023-11-29 2024-05-27 elopment interventions ations Envelope ementation nnuelle sur les interventions du projet CI-PMNDPE-343140-NC-DIR / Partenariat avec la RTI pou Early child nutrition and dev Pending Impl r la production et la diffusion IDA / 61740 Post Direct Selection Direct - National 133,333.00 0.00 2023-03-31 2023-04-05 2023-05-10 2023-11-06 elopment interventions ementation mensuellement des émissio ns sur la nutrition et le DPE CI-PMNDPE-343137-NC-RFQ / Assurer l’entretien, la fonct Early child nutrition and dev Request for Quot Single Stage - One Pending Impl IDA / 61740 Post Limited 25,000.00 0.00 2023-03-05 2023-04-30 2023-10-27 ionnalité, la mise à jour du si elopment interventions ations Envelope ementation te Web et du dispositif d’arc hivage électronique CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amoun Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Techni Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) t (US$) Notice equest for Proposals as Issued Proposals / Minutes cal Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CI-PMNDPE-110642-CS-LCS / Recrutement de cinq (05) a gences d'exécution locales ( AEL), pour la mise en œuvre Early child nutrition and dev Least Cost Selecti Pending Impleme IDA / 61740 Post Open - National 200,000.00 0.00 2018-12-18 2019-01-08 2019-02-21 2019-03-20 2019-04-19 2019-05-24 2019-06-28 2019-12-25 des projets de nutrition à ba elopment interventions on ntation se communautaire dans 23 sous-préfectures gans la rég ion du Poro, zone d'intervent ion du PMNDPE CI-PMNDPE-110649-CS-LCS / Recrutement de trois (03) agences d'exécution locales (AEL), pour la mise en œuvr Early child nutrition and dev Least Cost Selecti Pending Impleme IDA / 61740 Post Open - National 200,000.00 0.00 2018-12-23 2019-01-13 2019-02-26 2019-03-20 2019-04-19 2019-05-24 2019-06-28 2019-12-25 e des projets de nutrition à b elopment interventions on ntation ase communautaire dans 12 sous-préfectures gans la rég ion du Tchologo, zone d'inte rvention du PMNDPE CI-PMNDPE-110646-CS-LCS / Recrutement de trois (03) agences d'exécution locales (AEL), pour la mise en œuvr Early child nutrition and dev Least Cost Selecti Pending Impleme IDA / 61740 Post Open - National 200,000.00 0.00 2018-12-23 2019-01-13 2019-02-26 2019-03-20 2019-04-19 2019-05-24 2019-06-28 2019-12-25 e des projets de nutrition à b elopment interventions on ntation ase communautaire dans 13 sous-préfectures gans la rég ion de la Bagoue, zone d'int ervention du PMNDPE CI-PMNDPE-110650-CS-LCS / Recrutement de six (06) ag ences d'exécution locales (A EL), pour la mise en œuvre d Early child nutrition and dev Least Cost Selecti Pending Impleme IDA / 61740 Post Open - National 200,000.00 0.00 2018-12-23 2019-01-13 2019-02-26 2019-03-20 2019-04-19 2019-05-24 2019-06-28 2019-12-25 es projets de nutrition à bas elopment interventions on ntation e communautaire dans 27 s ous-préfectures gans la régi on du Gontougo, zone d'inte rvention du PMNDPE CI-PMNDPE-110652-CS-LCS / Recrutement de trois (03) agences d'exécution locales (AEL), pour la mise en œuvr Early child nutrition and dev Least Cost Selecti Pending Impleme IDA / 61740 Post Open - National 200,000.00 0.00 2018-12-17 2019-01-07 2019-02-20 2019-03-20 2019-04-19 2019-05-24 2019-06-28 2019-12-25 e des projets de nutrition à b elopment interventions on ntation ase communautaire dans 3 s ous-préfectures gans la régi on du Bounkani, zone d'inter vention du PMNDPE CI-PMNDPE-110653-CS-LCS Early child nutrition and dev Least Cost Selecti Pending Impleme / Recrutement d'un consulta IDA / 61740 Post Open - National 90,000.00 0.00 2018-12-21 2019-01-11 2019-02-24 2019-03-24 2019-04-23 2019-05-28 2019-07-02 2019-12-29 elopment interventions on ntation nt pour la réalisation d'une é tude de base CI-PMNDPE-110679-CS-LCS / Recrutement d'un consulta Quality And Cost- Pending Impleme IDA / 61740 Project management Post Open - National 100,000.00 0.00 2015-01-10 2015-01-31 2015-03-16 2015-04-13 2015-05-13 2015-06-17 2015-07-22 2016-07-21 nt pour l'audit comptable et Based Selection ntation financier du PMNDPE CI-PMNDPE-110682-CS-CQS Consultant Qualifi Pending Impleme / Recrutement d'un consulta IDA / 61740 Project management Post Open - National 240,000.00 0.00 2019-02-11 2019-03-04 2019-04-20 2019-05-20 2019-06-24 2019-12-21 cation Selection ntation nt pour l'enquête de référen ce du projet CI-PMNDPE-124070-CS-CQS / RECRUTEMENT D’AGENCES D’EXECUTION LOCALES (AEL Early child nutrition and dev Consultant Qualifi Under Implement ), POUR LA MISE EN ŒUVRE IDA / 61740 Post Open - National 4,000,000.00 0.00 2019-07-22 2020-04-08 2019-08-12 2019-09-25 2019-05-16 2019-10-25 2019-11-29 2020-05-27 elopment interventions cation Selection ation DES PROJETS DE NUTRITION A BASE COMMUNAUTAIRE D ANS LES ZONES D’INTERVEN TION DU PMNDPE CI-PMNDPE-124074-CS-CQS Early child nutrition and dev Consultant Qualifi Pending Impleme / RECRUTEMENT D’UN CABIN IDA / 61740 Post Open - National 50,000.00 0.00 2019-07-22 2019-08-12 2019-09-25 2019-10-25 2019-11-29 2020-05-27 elopment interventions cation Selection ntation ET EVALUATEUR DES CAPAC ITES DES AEL Page 7 CI-PMNDPE-124078-CS-CQS / RECRUTEMENT D’UN CONS Early child nutrition and dev Consultant Qualifi Pending Impleme IDA / 61740 Post Open - National 90,000.00 0.00 2019-08-15 2019-09-05 2019-10-19 2019-11-18 2019-12-23 2020-06-20 ULTANT POUR LA REALISATI elopment interventions cation Selection ntation ON D’UNE ETUDE DE BASE CI-PMNDPE-124142-CS-LCS / RECRUTEMENT D'UN CONS Least Cost Selecti Pending Impleme IDA / 61740 Project management Post Open - National 100,000.00 0.00 2019-09-30 2019-10-21 2019-12-04 2020-01-01 2020-01-31 2020-03-06 2020-04-10 2020-10-07 ULTANT POUR L’AUDIT COM on ntation PTABLE ET FINANCIER DU P MNDPE CI-PMNDPE-124146-CS-CQS / RECRUTEMENT D'UN CONS Consultant Qualifi Pending Impleme IDA / 61740 Project management Post Limited 240,000.00 0.00 2019-07-22 2019-08-05 2019-09-04 2019-10-09 2020-04-06 ULTANT POUR L'ENQUÊTE D cation Selection ntation E RÉFÉRENCE DU PROJET CI-PMNDPE-124151-CS-CQS / RECRUTEMENT D’UN CABIN ET POUR LA CONCEPTION, L Consultant Qualifi Pending Impleme IDA / 61740 Project management Post Limited 100,000.00 0.00 2019-07-31 2019-08-14 2019-09-13 2019-10-18 2020-04-15 A FOURNITURE ET INSTALLA cation Selection ntation TION D’UN PROGICIEL DE S UIVI ET ÉVALUATION SPÉCIFI QUE AU PROJET CI-PMNDPE-139150-CS-CQS / Recrutement d’un cabinet Consultant Qualifi Pending Impleme pour la conception, la fournit IDA / 61740 Project management Post Open - National 100,000.00 0.00 2019-10-31 2019-11-21 2020-01-04 2020-02-03 2020-03-09 2020-09-05 cation Selection ntation ure et installation d’un Prog iciel de suivi et évaluation s pécifique au Projet CI-PMNDPE-184247-CS-CQS / Appui à la mise en place de Early child nutrition and dev Consultant Qualifi Pending Impleme 1320 FRANC dans 138 nouv IDA / 61740 Prior Limited 10,000,000.00 0.00 2020-07-30 2020-08-13 2020-09-12 2020-10-17 2021-04-15 elopment interventions cation Selection ntation elles sous-préfectures de 11 régions non couvertes en 20 19 CI-PMNDPE-184422-CS-CQS / Recrutement d'un cabinet d'études pour l'évaluation d Early child nutrition and dev Consultant Qualifi Pending Impleme IDA / 61740 Post Limited 100,000.00 0.00 2020-08-03 2020-08-17 2020-09-16 2020-10-21 2021-04-19 u démarrage des prestations elopment interventions cation Selection ntation des Agences d'Exécution Lo cales dans la région du Poro, Tchologo et Bagoué CI-PMNDPE-184424-CS-CQS Early child nutrition and dev Consultant Qualifi Pending Impleme / Recrutement d'un cabinet IDA / 61740 Post Limited 100,000.00 0.00 2020-08-04 2020-08-18 2020-09-17 2020-10-22 2021-04-20 elopment interventions cation Selection ntation pour la conduite de l'étude ( LQAS) CI-PMNDPE-184425-CS-CQS / Recrutement d'un cabinet Early child nutrition and dev Consultant Qualifi Pending Impleme IDA / 61740 Post Limited 36,000.00 0.00 2020-08-05 2020-08-19 2020-09-18 2020-10-23 2021-04-21 pour la réalisation du diagno elopment interventions cation Selection ntation stic organisationnel du SE-C ONNAPE CI-PMNDPE-234387-CS-CQS / Recrutement d'un consulta Early child nutrition and dev Consultant Qualifi nt pour conduire des études IDA / 61740 Post Limited 260,000.00 0.00 Under Review 2021-06-30 2021-08-17 2021-07-14 2021-08-13 2021-09-17 2022-03-16 elopment interventions cation Selection et des évaluations (LQAS? C oût-Efficacité, évaluation de la qualité des données) CI-PMNDPE-234350-CS-CQS / Recrutement d’une agence Early child nutrition and dev Consultant Qualifi Under Implement conseil en communication p IDA / 61740 Post Limited 270,000.00 0.00 2021-07-20 2022-03-02 2021-08-03 2021-09-02 2021-10-07 2022-04-05 elopment interventions cation Selection ation our renforcer la communicat ion institutionnelle du PMND PE CI-PMNDPE-241744-CS-CQS / Recrutement d’une firme p Early child nutrition and dev Consultant Qualifi Pending Impleme our l’appui à la Communicati IDA / 61740 Post Limited 60,000.00 0.00 2021-07-20 2021-08-03 2021-09-02 2021-10-07 2022-04-05 elopment interventions cation Selection ntation on pour la médiatisation des interventions du PMNDPE CI-PMNDPE-271828-CS-CQS / Recrutement d’un cabinet pour l’évaluation à mi-parco Early child nutrition and dev Consultant Qualifi Pending Impleme urs du projet (réaliser une ét IDA / 61740 Post Open - National 240,000.00 0.00 2022-02-25 2022-03-18 2022-05-01 2022-05-31 2022-07-05 2023-01-01 elopment interventions cation Selection ntation ude sur la performance du p rojet, pertinence des approc hes, efficacité, efficience, du rabilité, pérennisation, cohér ence) CI-PMNDPE-267563-CS-CDS / Recrutement d’une firme p our renforcer la Communicat Early child nutrition and dev Quality Based Sel Under Implement IDA / 61740 Post Open - National 260,000.00 0.00 2022-03-25 2022-03-02 2022-04-15 2022-05-29 2022-06-26 2022-07-26 2022-08-25 2022-09-29 2023-09-29 ion pour le Changement des elopment interventions ection ation Normes Sociales et de Comp ortement (CCNSC) dans le c adre du PMNDPE CI-PMNDPE-282120-CS-QBS / Recrutement d’ONG charg Early child nutrition and dev Quality Based Sel Under Implement ées de la formation des acte IDA / 61740 Post Open - National 82,700.00 0.00 2022-04-22 2022-08-29 2022-05-13 2022-12-19 2022-06-26 2022-07-24 2022-08-23 2022-09-22 2022-10-27 2023-10-27 elopment interventions ection ation urs communautaires dans le cadre de l’alphabétisation fo nctionnelle CI-PMNDPE-288657-CS-QCB S / Recrutement d’un cabine Early child nutrition and dev Least Cost Selecti Under Implement t pour la réalisation de l’audi IDA / 61740 Post Open - National 50,000.00 0.00 2022-06-17 2022-10-21 2022-07-08 2022-08-21 2022-09-18 2022-10-18 2022-11-22 2022-12-27 2023-06-25 elopment interventions on ation t externe comptable et finan cier du PMNDPE pour les exe rcices 2022, 2023 et 2024 CI-PMNDPE-342793-CS-CQS / Recrutement d'un cabinet pour réaliser l'évaluation fin Early child nutrition and dev Consultant Qualifi Pending Impleme IDA / 61740 Post Limited 133,333.00 0.00 2023-04-28 2023-05-12 2023-06-11 2023-07-16 2024-01-12 ale du projet (pertinence des elopment interventions cation Selection ntation approches, efficacité, efficie nce, durabilité, pérennisatio n, cohérence) CI-PMNDPE-342799-CS-CQS / Recrutement d'un cabinet Early child nutrition and dev Consultant Qualifi Pending Impleme pour contribuer à l'évaluatio IDA / 61740 Post Limited 150,000.00 0.00 2023-03-30 2023-04-13 2023-05-13 2023-06-17 2023-12-14 elopment interventions cation Selection ntation n de l'impact nutritionnel de la fortification des aliments en Côte d'Ivoire CI-PMNDPE-342810-CS-CQS / Recrutement d'un cabinet pour réaliser une étude pour Early child nutrition and dev Consultant Qualifi Pending Impleme IDA / 61740 Post Limited 16,666.00 0.00 2023-03-31 2023-04-14 2023-05-14 2023-06-18 2023-12-15 analyser les conditions d'im elopment interventions cation Selection ntation plémentation des AVEC (Ass ociation Villageoise de Crédi t) dans des FRANC CI-PMNDPE-342816-CS-CQS / Recrutement d'un cabinet Early child nutrition and dev Consultant Qualifi Pending Impleme pour une étude comparative IDA / 61740 Post Limited 33,333.00 0.00 2023-03-30 2023-04-13 2023-05-13 2023-06-17 2023-12-14 elopment interventions cation Selection ntation / coût efficacité des approch es FRANC initiées par PNN, P MNDPE, UNICEF, HKI CI-PMNDPE-342818-CS-CQS / Recrutement d'un cabinet Early child nutrition and dev Consultant Qualifi Pending Impleme pour l’évaluation des interve IDA / 61740 Post Limited 66,666.00 0.00 2023-03-31 2023-04-14 2023-05-14 2023-06-18 2023-12-15 elopment interventions cation Selection ntation ntions du DPE sur les enfant s issus des FRANC dans le sy stème éducatif primaire CI-PMNDPE-342822-CS-CQS / Recrutement d'une firme p Early child nutrition and dev Consultant Qualifi Under Implement our faire la formation des AE IDA / 61740 Post Limited 118,333.00 0.00 2023-05-31 2023-06-16 2023-06-14 2023-07-14 2023-08-18 2024-02-14 elopment interventions cation Selection ation L sur les techniques alternat ives et économiques à l'usag e des pesticides Page 8 CI-PMNDPE-344926-CS-CQS / Recrutement d'un cabinet Early child nutrition and dev Consultant Qualifi Under Implement IDA / 61740 Post Open - National 83,333.00 0.00 2023-03-31 2023-05-25 2023-04-21 2023-06-04 2023-07-04 2023-08-08 2024-02-04 pour l’évaluation de la perfo elopment interventions cation Selection ation rmance opérationnelle des A EL CI-PMNDPE-364276-CS-CDS / Recrutement d’une firme p our la reformation des mem Early child nutrition and dev Consultant Qualifi Pending Impleme IDA / 61740 Post Limited 41,666.00 0.00 2023-06-08 2023-06-22 2023-07-22 2023-08-26 2024-02-22 bres de l’UGP-PMNDPE et de elopment interventions cation Selection ntation s structures d’appui à la mis e en œuvre du PMNDPE sur l e comportement organisatio nnel INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Identifie Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amoun Draft Negotiated Con Description Component Review Type Method Process Status Terms of Reference d/Selected Consultan Signed Contract Contract Completion o. h unt (US$) t (US$) tract t Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CI-PMNDPE-72503-CS-CQS / RECRUTEMENT D'UN CONSU Nutrition governance and m Individual Consult Pending Impleme LTANT INDIVIDUEL JURISTE P IDA / 61740 Post Limited 15,000.00 0.00 2018-08-30 2018-09-04 2018-09-25 2018-10-30 2019-04-28 anagement ant Selection ntation OUR L'ÉLABORATION DES A RRÊTES RELATIFS A LA MISE EN ŒUVRE DU PNMN CI-PMNDPE-72505-CS-CQS / RECRUTEMENT D'UN CONSU LTANT INDIVIDUEL POUR UN Nutrition governance and m Individual Consult Pending Impleme IDA / 61740 Post Limited 30,000.00 0.00 2018-08-30 2018-09-04 2018-09-25 2018-10-30 2019-01-28 E ÉTUDE DE FAISABILITÉ PO anagement ant Selection ntation UR LA MISE EN PLACE DES F ONDS INNOVANTS DE NUTRI TION CI-PMNDPE-72507-CS-CQS / RECRUTEMENT D'UN CONSU LTANT POUR LA CARTOGRAP Early child nutrition and dev Individual Consult Pending Impleme IDA / 61740 Post Limited 10,000.00 0.00 2018-08-30 2018-09-04 2018-09-25 2018-10-30 2018-12-14 HIE DES INTERVENANTS ET elopment interventions ant Selection ntation DES INTERVENTIONS EN DÉ VELOPPEMENT DE LA PETITE ENFANCE CI-PMNDPE-72519-CS-CQS / RECRUTEMENT D'UN RESPO NSABLE TECHNIQUE CHARG Individual Consult Pending Impleme IDA / 61740 Project management Post Open 40.00 0.00 2018-08-30 2018-10-18 2018-11-08 2018-12-13 2019-06-11 E DE LA NUTRITION A BASE ant Selection ntation COMMUNAUTAIRE ET DU DÉ VELOPPEMENT DES ENFANT S (RCCSC) CI-PMNDPE-72523-CS-QCBS Individual Consult Pending Impleme / RECRUTEMENT D'UN CHEF IDA / 61740 Project management Post Open 80.00 0.00 2018-08-30 2018-10-18 2018-11-08 2018-12-13 2019-06-11 ant Selection ntation DE PROJET POUR LE PMNDPE CI-PMNDPE-72596-CS-INDV Individual Consult Pending Impleme / Recrutement d'un Respons IDA / 61740 Project management Post Open 55.00 0.00 2018-08-09 2018-09-27 2018-10-18 2018-11-22 2019-05-21 ant Selection ntation able Financier et Administrat if pour le PMNDPE CI-PMNDPE-72656-CS-INDV Individual Consult Pending Impleme / Recrutement d'une Assista IDA / 61740 Project management Post Limited 15,000.00 0.00 2018-08-30 2018-09-04 2018-09-25 2018-10-30 2019-04-28 ant Selection ntation nte Administrative pour le P MNDPE CI-PMNDPE-72660-CS-INDV Individual Consult Pending Impleme / Recrutement de deux (02) IDA / 61740 Project management Post Limited 17,000.00 0.00 2018-08-16 2018-08-31 2018-09-21 2018-10-11 2019-10-11 ant Selection ntation Chauffeurs pour le PMNDPE CI-PMNDPE-72661-CS-INDV / Recrutement d'un Consulta Nutrition governance and m Individual Consult Pending Impleme nt pour le dévéloppement d IDA / 61740 Post Limited 55,000.00 0.00 2018-09-07 2018-09-22 2018-10-13 2018-11-17 2019-05-16 anagement ant Selection ntation es outils de gestion du CNN (politique de gestion des con flits) CI-PMNDPE-72662-CS-INDV / Recrutement d'un consulta nt en vue de soutenir l'élabo Early child nutrition and dev Individual Consult Pending Impleme IDA / 61740 Post Limited 36,000.00 0.00 2018-08-30 2018-09-14 2018-10-05 2018-11-02 2019-01-01 ration des textes règlement elopment interventions ant Selection ntation ant la vente des aliments et boissons pour enfants et ado lescents CI-PMNDPE-72664-CS-INDV / Recrutement d'un consulta Nutrition governance and m Individual Consult Pending Impleme nt en vue d'élaborer le docu IDA / 61740 Post Limited 40,000.00 0.00 2018-08-30 2018-09-13 2018-10-04 2018-10-19 2018-12-18 anagement ant Selection ntation ment de plaidoyer pour la cr éation d'un fonds national d e nutrition CI-PMNDPE-72666-CS-INDV / Recrutement d'un Consulta nt en vue de soutenir l'élabo Individual Consult Pending Impleme IDA / 61740 Project management Post Limited 10,000.00 0.00 2018-08-30 2018-09-13 2018-10-04 2018-10-29 2019-10-29 ration des documents de pla ant Selection ntation idoyer et participer aux conf érences PIP pour la mobilisat ion des ressources domestiq ues CI-PMNDPE-72667-CS-INDV / Recrutement d'un Consulta Nutrition governance and m Individual Consult Pending Impleme nt en vue de réaliser une ét IDA / 61740 Post Limited 6,000.00 0.00 2018-08-30 2018-09-13 2018-10-04 2018-10-24 2018-12-08 anagement ant Selection ntation ude de faisabilité pour le rec rutement à la fonction publi que des nutritionnistes CI-PMNDPE-72669-CS-CDS / Recrutement d'un Consultan Early child nutrition and dev Pending Impleme t pour la finalisation du docu IDA / 61740 Post Direct Selection Direct 40,000.00 0.00 2018-08-30 2018-09-09 2018-10-20 2019-04-18 elopment interventions ntation ment FRANCS et élaboration de la stratégie de mobilisati on communautaire CI-PMNDPE-72674-CS-INDV / Recrutement d'un consulta nt pour la réalisation d'une é Individual Consult Pending Impleme IDA / 61740 Project management Post Limited 10,000.00 0.00 2018-08-30 2018-09-13 2018-09-28 2018-10-22 2018-12-06 tude sur les synergies opéra ant Selection ntation tionnelles des projets sectori els de la Banque Mondiale e n Côte d'Ivoire avec le PMND PE CI-PMNDPE-110691-CS-IND V / Recrutement d'un consul Nutrition governance and m Individual Consult Pending Impleme IDA / 61740 Post Limited 50,000.00 0.00 2015-11-10 2015-11-15 2015-12-06 2016-01-10 2016-07-08 tant pour l'élaboration du m anagement ant Selection ntation anuel de formation des AEL et des Communautés CI-PMNDPE-110663-CS-IND V / Recrutement d'un consul tant pour élaborer les manu Nutrition governance and m Individual Consult Pending Impleme els de formation du Corps pr IDA / 61740 Post Limited 60,000.00 0.00 2015-01-10 2015-01-15 2015-02-05 2015-03-12 2015-09-08 anagement ant Selection ntation éfectoral, collectivités locale s, des Directions régionales des secteurs, des prestatair es de services CI-PMNDPE-110688-CS-IND V / Recrutement d'un consul tant pour l'élaboration et la validation du manuel/Guide Nutrition governance and m Individual Consult Pending Impleme IDA / 61740 Post Limited 80,000.00 0.00 2015-12-17 2015-12-22 2016-01-12 2016-02-16 2016-08-14 National d'éducation parent anagement ant Selection ntation ale pour le DPE et le guide d e formation des facilitateurs du programme d'éducation parentale s'inspirant du Man uel National CI-PMNDPE-110689-CS-IND V / Recrutement d'un consul Nutrition governance and m Individual Consult Pending Impleme IDA / 61740 Post Limited 30,000.00 0.00 2016-01-07 2016-01-12 2016-02-02 2016-03-08 2016-09-04 tant pour développer le paq anagement ant Selection ntation uet minimum des activités ( nutrition et DPE) Page 9 CI-PMNDPE-110690-CS-IND V / Recrutement de deux co nsultants (un consultant inte Nutrition governance and m Individual Consult Pending Impleme rnational et un consultant na IDA / 61740 Post Limited 110,000.00 0.00 2015-12-15 2015-12-20 2016-01-10 2016-02-14 2016-08-12 anagement ant Selection ntation tional) pour développer la St ratégie de communication p our le changement social et de comportements + Plan o pérationnel CI-PMNDPE-110693-CS-IND V / Recrutement d'un consul tant pour l'élaboration d'un Nutrition governance and m Individual Consult Pending Impleme manuel de procédures intég IDA / 61740 Post Limited 30,000.00 0.00 2015-11-10 2015-11-15 2015-12-06 2016-01-10 2016-07-08 anagement ant Selection ntation rées d'acquisition des intran ts nutritionnels (ATPE, matér iels anthropométriques et au tres intrants) CI-PMNDPE-110695-CS-IND V / Recrutement d'un consul tant pour la réalisation de la Nutrition governance and m Individual Consult Pending Impleme IDA / 61740 Post Limited 60,000.00 0.00 2015-01-10 2015-01-15 2015-02-05 2015-03-12 2015-09-08 cartographie des intervenan anagement ant Selection ntation ts et des interventions en dé veloppement de la petite en fance CI-PMNDPE-110696-CS-IND V / Recrutement d'un consul Nutrition governance and m Individual Consult Pending Impleme tant pour l'élaboration et la IDA / 61740 Post Limited 100,000.00 0.00 2015-12-17 2015-12-22 2016-01-12 2016-02-16 2016-08-14 anagement ant Selection ntation mise en œuvre le Plan de co mmunication institutionnelle du projet CI-PMNDPE-110675-CS-IND V / Recrutement des membr Individual Consult Pending Impleme IDA / 61740 Project management Post Limited 50,000.00 0.00 2016-01-07 2016-01-12 2016-02-02 2016-03-08 2016-09-04 es des équipes régionales ( ant Selection ntation Points focaux, comptables) CI-PMNDPE-110694-CS-IND V / Recrutement d'un consul Nutrition governance and m Individual Consult Pending Impleme IDA / 61740 Post Limited 100,000.00 0.00 2015-12-15 2015-12-20 2016-01-10 2016-02-14 2016-08-12 tant pour la réalisation d'une anagement ant Selection ntation enquête primaire Genre CI-PMNDPE-110681-CS-IND V / Recrutement d'un consul Individual Consult Pending Impleme IDA / 61740 Project management Post Limited 60,000.00 0.00 2018-11-20 2018-11-25 2018-12-16 2019-01-20 2019-07-19 tant pour l'élaboration du ca ant Selection ntation dre de suivi et évaluation du PMNDPE CI-PMNDPE-110683-CS-IND V / Recrutement des assista Individual Consult Pending Impleme nts aux spécialistes au PMN IDA / 61740 Project management Post Open 48,000.00 0.00 2019-01-17 2019-03-05 2019-03-26 2019-04-30 2019-10-27 ant Selection ntation DPE (Assistants en PM, Suivi et évaluation et assistant co mptable) CI-PMNDPE-110677-CS-IND V / Recrutement d'un consul Individual Consult Pending Impleme IDA / 61740 Project management Post Limited 40,000.00 0.00 2019-02-18 2019-02-24 2019-03-17 2019-04-21 2019-10-18 tant pour la révision/actualis ant Selection ntation ation du manuel de mise en œuvre (PIM) CI-PMNDPE-124095-CS-IND V / RECRUTEMENT D’UN CO NSULTANT POUR L’ÉLABORA TION ET LA VALIDATION DU MANUEL/GUIDE NATIONAL D Nutrition governance and m Individual Consult Pending Impleme IDA / 61740 Post Limited 80,000.00 0.00 2019-07-22 2019-07-27 2019-08-17 2019-09-21 2020-03-19 ’ÉDUCATION PARENTALE PO anagement ant Selection ntation UR LE DPE ET LE GUIDE DE F ORMATION DES FACILITATEU RS DU PROGRAMME D’ÉDUC ATION PARENTALE S’INSPIRA NT DU MANUEL NATIONAL CI-PMNDPE-124103-CS-CDS / RECRUTEMENT D’UN CONS ULTANT POUR LA FINALISATI Nutrition governance and m Pending Impleme IDA / 61740 Post Direct Selection Direct 140,000.00 0.00 2019-07-22 2019-08-01 2019-10-05 2020-04-02 ON DU GUIDE FRANC ET L’É anagement ntation LABORATION DE LA STRATÉ GIE DE MOBILISATION COMM UNAUTAIRE CI-PMNDPE-124110-CS-IND V / RECRUTEMENT D’UN CO Nutrition governance and m Individual Consult Pending Impleme NSULTANT POUR DÉVELOPP IDA / 61740 Post Limited 30,000.00 0.00 2019-07-22 2019-07-27 2019-08-17 2019-09-21 2020-03-19 anagement ant Selection ntation ER LE PAQUET MINIMUM DE S ACTIVITÉS (NUTRITION ET DPE) CI-PMNDPE-124111-CS-IND V / RECRUTEMENT DE DEUX CONSULTANTS (UN CONSUL TANT INTERNATIONAL ET UN Nutrition governance and m Individual Consult Pending Impleme CONSULTANT NATIONAL) PO IDA / 61740 Post Limited 168,000.00 0.00 2019-07-22 2019-07-27 2019-08-17 2019-09-21 2020-03-19 anagement ant Selection ntation UR DÉVELOPPER LA STRATÉ GIE DE COMMUNICATION PO UR LE CHANGEMENT SOCIAL ET DE COMPORTEMENTS + P LAN OPÉRATIONNEL CI-PMNDPE-124114-CS-IND V / RECRUTEMENT D’UN CO NSULTANT POUR ÉLABORER LES MANUELS DE FORMATIO Nutrition governance and m Individual Consult Pending Impleme IDA / 61740 Post Limited 60,000.00 0.00 2019-07-22 2019-07-27 2019-08-17 2019-09-21 2020-03-19 N DU CORPS PRÉFECTORAL, anagement ant Selection ntation COLLECTIVITÉS LOCALES, D ES DIRECTIONS RÉGIONALES DES SECTEURS, DES PREST ATAIRES DE SERVICES CI-PMNDPE-124115-CS-IND V / RECRUTEMENT D’UN CO Nutrition governance and m Individual Consult Pending Impleme NSULTANT POUR L’ÉLABORA IDA / 61740 Post Limited 50,000.00 0.00 2019-07-22 2019-07-27 2019-08-17 2019-09-21 2020-03-19 anagement ant Selection ntation TION DU MANUEL DE FORMA TION DES AEL ET DES COMM UNAUTÉS CI-PMNDPE-124119-CS-IND V / RECRUTEMENT D’UN CO NSULTANT POUR L’ÉLABORA TION D’UN MANUEL DE PRO Nutrition governance and m Individual Consult Pending Impleme IDA / 61740 Post Limited 30,000.00 0.00 2019-08-30 2019-09-04 2019-09-25 2019-10-30 2020-04-27 CÉDURES INTÉGRÉES D'ACQ anagement ant Selection ntation UISITION DES INTRANTS NUT RITIONNELS (ATPE, MATÉRIE LS ANTHROPOMÉTRIQUES E T AUTRES INTRANTS) CI-PMNDPE-124122-CS-IND V / RECRUTEMENT D’UN CO Nutrition governance and m Individual Consult Pending Impleme IDA / 61740 Post Limited 100,000.00 0.00 2019-08-15 2019-08-20 2019-09-10 2019-10-15 2020-04-12 NSULTANT POUR LA RÉALISA anagement ant Selection ntation TION D’UNE ENQUÊTE PRIMA IRE GENRE CI-PMNDPE-124123-CS-IND V / RECRUTEMENT D’UN CO NSULTANT POUR LA RÉALISA Nutrition governance and m Individual Consult Pending Impleme IDA / 61740 Post Limited 60,000.00 0.00 2019-07-22 2019-07-27 2019-08-17 2019-09-21 2020-03-19 TION DE LA CARTOGRAPHIE anagement ant Selection ntation DES INTERVENANTS ET DES INTERVENTIONS EN DÉVELO PPEMENT DE LA PETITE ENF ANCE CI-PMNDPE-124137-CS-IND V / RECRUTEMENT DES MEM Individual Consult Pending Impleme IDA / 61740 Project management Post Open 50,000.00 0.00 2019-07-22 2019-09-09 2019-09-30 2019-11-04 2020-05-02 BRES DES ÉQUIPES RÉGION ant Selection ntation ALES (POINTS FOCAUX, CO MPTABLES) CI-PMNDPE-124141-CS-IND V / RECRUTEMENT D’UN CO Individual Consult Pending Impleme NSULTANT POUR LA RÉVISIO IDA / 61740 Project management Post Limited 40,000.00 0.00 2019-07-31 2019-08-05 2019-08-26 2019-09-30 2020-03-28 ant Selection ntation N/ACTUALISATION DU MANU EL DE MISE EN ŒUVRE (PIM) Page 10 CI-PMNDPE-124144-CS-IND V / RECRUTEMENT D’UN CO Individual Consult Pending Impleme NSULTANT POUR L’ÉLABORA IDA / 61740 Project management Post Limited 60,000.00 0.00 2019-07-22 2019-07-27 2019-08-17 2019-09-21 2020-03-19 ant Selection ntation TION DU CADRE DE SUIVI ET ÉVALUATION DU PMNDPE CI-PMNDPE-124147-CS-IND V / RECRUTEMENT DES ASSI Individual Consult Pending Impleme STANTS AUX SPÉCIALISTES IDA / 61740 Project management Post Open 48,000.00 0.00 2019-07-22 2019-09-09 2019-09-30 2019-11-04 2020-05-02 ant Selection ntation AU PMNDPE (ASSISTANTS EN PM, SUIVI ET ÉVALUATION E T ASSISTANT COMPTABLE) CI-PMNDPE-124148-CS-IND Individual Consult Pending Impleme V / RECRUTEMENT D’UN CO IDA / 61740 Project management Post Limited 16,000.00 0.00 2019-08-15 2019-08-20 2019-09-10 2019-10-15 2020-04-12 ant Selection ntation MPTABLE PRINCIPAL POUR L E PMNDPE CI-PMNDPE-124149-CS-IND V / RECRUTEMENT D’UN SEC Individual Consult Pending Impleme IDA / 61740 Project management Post Limited 48,000.00 0.00 2019-08-15 2019-08-20 2019-09-10 2019-10-15 2020-04-12 OND ASSISTANT COMPTABL ant Selection ntation E POUR LE PMNDPE CI-PMNDPE-139154-CS-IND Individual Consult Pending Impleme V / Sélection d’un infographi IDA / 61740 Project management Post Open 12,000.00 0.00 2019-11-20 2020-01-08 2020-01-29 2020-03-04 2020-08-31 ant Selection ntation ste pour le PMNDPE CI-PMNDPE-139158-CS-IND Individual Consult Under Implement V / Sélection d’un informatici IDA / 61740 Project management Post Open 12,000.00 0.00 2019-10-31 2022-03-08 2019-12-19 2020-01-09 2020-02-13 2020-08-11 ant Selection ation en archiviste pour l’UGP PM NDPE CI-PMNDPE-139160-CS-IND Individual Consult Pending Impleme V / Sélection d’un reprograp IDA / 61740 Project management Post Open 7,200.00 0.00 2019-11-28 2020-01-16 2020-02-06 2020-03-12 2020-09-08 ant Selection ntation he pour l’UGP PMNDPE CI-PMNDPE-72598-CS-INDV Individual Consult Pending Impleme / Recrutement d'un Respons IDA / 61740 Project management Post Open 55,000.00 0.00 2018-08-23 2018-10-11 2018-10-13 2018-10-15 2019-10-15 ant Selection ntation able Administratif et Financi er pour le PMNDPE CI-PMNDPE-72653-CS-INDV Individual Consult Pending Impleme / Recrutement d'un Spécialis IDA / 61740 Project management Post Open 55.00 0.00 2018-08-16 2018-09-14 2018-09-21 2018-10-08 2019-10-08 ant Selection ntation te en Passation de Marchés pour le PMNDPE CI-PMNDPE-72654-CS-INDV Individual Consult Pending Impleme / Recrutement d'un Spécialis IDA / 61740 Project management Post Open 55,000.00 0.00 2018-08-16 2018-09-19 2018-09-29 2018-10-30 2019-10-30 ant Selection ntation te Suivi-Evaluation pour le P MNDPE CI-PMNDPE-72655-CS-INDV Individual Consult Pending Impleme / Recrutement d'un Compta IDA / 61740 Project management Post Open 24,000.00 0.00 2018-08-16 2018-09-14 2018-09-24 2018-10-20 2019-10-20 ant Selection ntation ble pour le PMNDPE CI-PMNDPE-72592-CS-INDV / Recrutement d'un Respons Individual Consult Pending Impleme IDA / 61740 Project management Post Open 40,000.00 0.00 2018-09-02 2018-10-21 2018-10-26 2018-11-19 2019-11-19 able chargé de Communicati ant Selection ntation on pour le changement soci al et de comportement CI-PMNDPE-234378-CS-IND V / Recrutement d'un consul tant individuel international Early child nutrition and dev Individual Consult Under Implement en Communication pour le C IDA / 61740 Post Limited 90,000.00 0.00 2021-06-18 2022-03-01 2021-06-23 2021-07-14 2021-08-18 2022-02-14 elopment interventions ant Selection ation hangement Social et de Com portement (CCSC) pour le dé veloppement de supports co mplémentaires multimédias CI-PMNDPE-234380-CS-IND Early child nutrition and dev Individual Consult Pending Impleme V / Recrutement d'un consul IDA / 61740 Post Limited 50,000.00 0.00 2021-06-18 2021-06-23 2021-07-14 2021-08-18 2022-02-14 elopment interventions ant Selection ntation tant pour la revue à mi-parc ours du projet CI-PMNDPE-234450-CS-IND Early child nutrition and dev Individual Consult Under Implement V / Recrutement de deux (02 IDA / 61740 Post Limited 16,800.00 0.00 2021-06-25 2021-07-19 2021-06-30 2021-07-21 2021-08-25 2022-02-21 elopment interventions ant Selection ation ) assistants (es) comptables du PMNDPE CI-PMNDPE-234452-CS-IND Early child nutrition and dev Individual Consult Pending Impleme V / Recrutement d'un techni IDA / 61740 Post Limited 7,200.00 0.00 2021-06-18 2021-06-23 2021-07-14 2021-08-18 2022-02-14 elopment interventions ant Selection ntation cien reprographe pour le PM NDPE CI-PMNDPE-234401-CS-CDS / Recrutement d'un Cabinet en vue du renforcement du Early child nutrition and dev Under Implement IDA / 61740 Post Direct Selection Direct 80,000.00 0.00 2021-06-30 2022-04-06 2021-07-10 2021-09-13 2022-03-12 SISE et passer à la version 2 elopment interventions ation .0 (Volet cartographie, Finan ce et collecte mobile au nive au FRANC) CI-PMNDPE-234385-CS-IND V / Recrutement d'un consul Early child nutrition and dev Individual Consult Pending Impleme IDA / 61740 Post Open 150,000.00 0.00 2021-06-18 2021-08-06 2021-08-27 2021-10-01 2022-03-30 tant pour l'appui à l'élaborat elopment interventions ant Selection ntation ion du nouveau plan multise ctoriel (PNMN2) CI-PMNDPE-234435-CS-IND V / Recrutement d'un consul Early child nutrition and dev Individual Consult Pending Impleme tant pour la réalisation de l'a IDA / 61740 Post Open 90,000.00 0.00 2021-05-31 2021-07-19 2021-08-09 2021-09-13 2022-03-12 elopment interventions ant Selection ntation udit de mise en conformité e nvironnementale et sociale du PMNDPE CI-PMNDPE-241119-CS-IND V / Recrutement d’un(e) Spé Early child nutrition and dev Individual Consult Under Implement cialiste en Sauvegarde Envir IDA / 61740 Post Limited 72,000.00 0.00 2021-07-14 2021-06-21 2021-07-19 2021-09-15 2021-08-09 2021-09-13 2022-03-12 elopment interventions ant Selection ation onnementale et Sociale à l’U nité de Gestion du PMNDPE CI-PMNDPE-268524-CS-IND V / Recrutement d'un(e) con Early child nutrition and dev Individual Consult Pending Impleme sultant(e) chargé de l'élabor IDA / 61740 Post Open 80,000.00 0.00 2021-03-09 2021-04-27 2021-05-18 2021-06-22 2021-12-19 elopment interventions ant Selection ntation ation d'un mécanisme de ge stion des plaintes dans le ca dre du PMNDPE CI-PMNDPE-258793-CS-IND V / Recrutement d’un consul tant individuel pour la conce Early child nutrition and dev Individual Consult Pending Impleme IDA / 61740 Post Limited 10,000.00 0.00 2022-01-28 2022-02-02 2022-02-23 2022-03-30 2022-09-26 ption de maquettes et suppo elopment interventions ant Selection ntation rts de communication en rap port avec la nutrition et le D PE dans le cadre du PMNDPE CI-PMNDPE-271823-CS-IND V / Recrutement d’un consul tant individuel pour la mise Early child nutrition and dev Individual Consult Pending Impleme en place d'un mécanisme pil IDA / 61740 Post Limited 60,000.00 0.00 2022-02-02 2022-02-07 2022-02-28 2022-04-04 2022-10-01 elopment interventions ant Selection ntation ote de FBR à base communa utaire et/ou à la demande d e service dans une zone pilo te du PMNDPE CI-PMNDPE-271892-CS-IND V / Recrutement d’un consul tant individuel pour la mise Early child nutrition and dev Individual Consult Pending Impleme IDA / 61740 Post Limited 60,000.00 0.00 2022-02-02 2022-02-07 2022-02-28 2022-04-04 2022-10-01 en place d'un dispositif de c elopment interventions ant Selection ntation apitalisation des acquis du p rojet et de gestion des conn aissances CI-PMNDPE-271893-CS-IND V / Recrutement d’un consul Early child nutrition and dev Individual Consult Pending Impleme tant individuel pour l’élabora IDA / 61740 Post Limited 30,000.00 0.00 2022-02-02 2022-02-07 2022-02-28 2022-04-04 2022-10-01 elopment interventions ant Selection ntation tion d'un document de Gesti on sécuritaire et sanitaire de s aliments Page 11 CI-PMNDPE-271894-CS-IND V / Recrutement d’un consul Early child nutrition and dev Individual Consult Pending Impleme IDA / 61740 Post Limited 80,000.00 0.00 2022-02-02 2022-02-07 2022-02-28 2022-04-04 2022-10-01 tant individuel pour l’exécuti elopment interventions ant Selection ntation on du plan de gestion enviro nnementale et sociale CI-PMNDPE-271895-CS-IND V / Recrutement d’un consul Early child nutrition and dev Individual Consult Pending Impleme IDA / 61740 Post Limited 20,000.00 0.00 2022-02-02 2022-02-07 2022-02-28 2022-04-04 2022-10-01 tant individuel pour la mise elopment interventions ant Selection ntation en œuvre des mécanismes d e gestion des plaintes CI-PMNDPE-271673-GO-DIR / Convention avec le PNN po ur l’appui à la mise en place Early child nutrition and dev Pending Impleme IDA / 61740 Post Direct Selection Direct 140,000.00 0.00 2022-03-25 2022-04-04 2022-06-08 2022-12-05 de 221 GDS (Groupe de Sout elopment interventions ntation ien) à l'allaitement dans le c adre de SSAB (Structures Sa nitaires Amies des Bébés) CI-PMNDPE-271810-CS-CDS / Recrutement de l’AEL AIP ( Association ivoirienne pour l Early child nutrition and dev Pending Impleme e progrès) pour poursuivre l IDA / 61740 Post Direct Selection Direct 182,761.00 0.00 2022-03-11 2022-03-21 2022-05-25 2022-11-21 elopment interventions ntation a mise en œuvre des activit és communautaires dans la région du Gontougo dans 23 villages dans le cadre du PM NDPE CI-PMNDPE-271818-CS-CDS / Recrutement de l’AEL HKI ( Helen Keller International) p Early child nutrition and dev Pending Impleme our poursuivre la mise en œ IDA / 61740 Post Direct Selection Direct 198,653.00 0.00 2022-03-11 2022-03-21 2022-05-25 2022-11-21 elopment interventions ntation uvre des activités communa utaires dans la région de la Marahoué dans 25 villages d ans le cadre du PMNDPE CI-PMNDPE-271804-CS-CDS / Recrutement de l’AEL CIP ( Côte d’Ivoire Prospérité) pou Early child nutrition and dev Pending Impleme r poursuivre la mise en œuvr IDA / 61740 Post Direct Selection Direct 190,707.00 0.00 2022-03-11 2022-03-21 2022-05-25 2022-11-21 elopment interventions ntation e des activités communautai res dans la région de la Mar ahoué dans 24 villages dans le cadre du PMNDPE CI-PMNDPE-271777-CS-CDS / Recrutement de l’AEL EICF (Ensemble Imaginons et Con Early child nutrition and dev Pending Impleme struisons le Futur) pour pour IDA / 61740 Post Direct Selection Direct 190,707.00 0.00 2022-03-11 2022-03-21 2022-05-25 2022-11-21 elopment interventions ntation suivre la mise en œuvre des activités communautaires d ans la région du Gontougo d ans 24 villages dans le cadr e du PMNDPE CI-PMNDPE-288577-CS-CDS / Recrutement de l'AEL ONG ADIAS pour le suivi des FRA NC existants prenant en co Early child nutrition and dev Under Implement IDA / 61740 Post Direct Selection Direct 941,414.00 0.00 2022-04-11 2022-03-30 2022-04-21 2022-04-26 2022-06-25 2022-12-22 mpte les activités résiduelle elopment interventions ation s et la création de nouveaux FRANC pour la mise en œuvr e des interventions commun autaires dans le cadre du PM NDPE CI-PMNDPE-288626-CS-CDS / Recrutement de l’AEL SAVE THE CHILDREN INTERNATIO NAL pour le suivi des FRANC Early child nutrition and dev Pending Impleme existants prenant en compte IDA / 61740 Post Direct Selection Direct 987,999.00 0.00 2022-04-11 2022-04-21 2022-06-25 2022-12-22 elopment interventions ntation les activités résiduelles et la création de nouveaux FRAN C pour la mise en œuvre des interventions communautair es dans le cadre du PMNDPE CI-PMNDPE-288632-CS-CDS / Recrutement de l’AEL LUMI ERE ACTION pour le suivi de s FRANC existants prenant e Early child nutrition and dev Under Implement IDA / 61740 Post Direct Selection Direct 904,668.00 0.00 2022-04-11 2022-03-30 2022-04-21 2022-05-03 2022-06-25 2022-12-22 n compte les activités résidu elopment interventions ation elles et la création de nouve aux FRANC pour la mise en œuvre des interventions co mmunautaires dans le cadre du PMNDPE CI-PMNDPE-288634-CS-CDS / Recrutement de l’AEL GEN ERATION FEMME DU 3ème M ILLENAIRE pour le suivi des F Early child nutrition and dev Under Implement RANC existants prenant en c IDA / 61740 Prior Direct Selection Direct 1,459,107.00 0.00 2022-04-11 2022-04-19 2022-04-21 2022-06-25 2022-12-22 elopment interventions ation ompte les activités résiduell es et la création de nouveau x FRANC pour la mise en œu vre des interventions comm unautaires dans le cadre du PMNDPE CI-PMNDPE-288636-CS-CDS / Recrutement de l’AEL ENSE MBLE IMAGINONS ET CONST RUISONS LE FUTUR pour le s Early child nutrition and dev Under Implement uivi des FRANC existants pre IDA / 61740 Prior Direct Selection Direct 2,024,119.00 0.00 2022-04-11 2022-04-19 2022-04-21 2022-06-25 2022-12-22 elopment interventions ation nant en compte les activités résiduelles et la création de nouveaux FRANC pour la mi se en œuvre des interventio ns communautaires dans le cadre du PMNDPE CI-PMNDPE-288646-CS-CDS / Recrutement de l’AEL ANIM ATION RURALE DE KORHOG O pour le suivi des FRANC e Early child nutrition and dev Under Implement xistants prenant en compte l IDA / 61740 Prior Direct Selection Direct 1,370,569.00 0.00 2022-04-11 2022-04-19 2022-04-21 2022-06-25 2022-12-22 elopment interventions ation es activités résiduelles et la création de nouveaux FRAN C pour la mise en œuvre des interventions communautair es dans le cadre du PMNDPE CI-PMNDPE-288650-CS-CDS / Recrutement de l’AEL ANA DER pour le suivi des FRANC existants prenant en compte Early child nutrition and dev Under Implement IDA / 61740 Prior Direct Selection Direct 2,038,224.00 0.00 2022-04-11 2022-04-19 2022-04-21 2022-06-25 2022-12-22 les activités résiduelles et la elopment interventions ation création de nouveaux FRAN C pour la mise en œuvre des interventions communautair es dans le cadre du PMNDPE CI-PMNDPE-288652-CS-CDS / Recrutement de l’AEL ALLI ANCE COTE D’IVOIRE pour le suivi des FRANC existants pr Early child nutrition and dev Under Implement IDA / 61740 Prior Direct Selection Direct 1,022,393.00 0.00 2022-04-11 2022-04-19 2022-04-21 2022-05-03 2022-06-25 2022-12-22 enant en compte les activité elopment interventions ation s résiduelles et la création d e nouveaux FRANC pour la mise en œuvre des intervent ions communautaires dans l e cadre du P CI-PMNDPE-288654-CS-CDS / Recrutement de l’AEL ASS OCIATION IVOIRIENNE POUR LE PROGRES pour le suivi de Early child nutrition and dev Under Implement s FRANC existants prenant e IDA / 61740 Prior Direct Selection Direct 1,631,683.00 0.00 2022-04-11 2022-04-21 2022-04-21 2022-06-25 2022-12-22 elopment interventions ation n compte les activités résidu elles et la création de nouve aux FRANC pour la mise en œuvre des interventions co mmunautaires dans le cadre du PMNDPE Page 12 CI-PMNDPE-288655-CS-CDS / Recrutement de l’AEL AFRI CA GLOBAL INTERNATIONAL (Consortium) pour le suivi d Early child nutrition and dev Under Implement es FRANC existants prenant IDA / 61740 Prior Direct Selection Direct 1,261,674.00 0.00 2022-04-11 2022-04-21 2022-04-21 2022-06-25 2022-12-22 elopment interventions ation en compte les activités résid uelles et la création de nouv eaux FRANC pour la mise en œuvre des interventions co mmunautaires dans le cadre du PMNDPE CI-PMNDPE-247633-CS-CDS / Convention TRECC/UGP PM NDPE relative au co-finance Early child nutrition and dev Under Implement IDA / 61740 Post Direct Selection Direct 80,000.00 0.00 2022-04-28 2022-04-27 2022-05-08 2022-07-12 2023-01-08 ment pour l’étude coût-effic elopment interventions ation acité des programmes d’édu cation parentale sur la Petite Enfance CI-PMNDPE-288644-CS-CDS / Recrutement de l’AEL ASAP SU pour le suivi des FRANC existants prenant en compte Early child nutrition and dev Under Implement IDA / 61740 Prior Direct Selection Direct 1,650,308.00 0.00 2022-04-11 2022-04-25 2022-04-21 2022-06-25 2022-12-22 les activités résiduelles et la elopment interventions ation création de nouveaux FRAN C pour la mise en œuvre des interventions communautair es dans le cadre du PMNDPE CI-PMNDPE-288643-CS-CDS / Recrutement de l’AEL COT E D’IVOIRE PROSPERITE pou r le suivi des FRANC existant Early child nutrition and dev Under Implement s prenant en compte les acti IDA / 61740 Prior Direct Selection Direct 1,559,976.00 0.00 2022-04-11 2022-04-25 2022-04-21 2022-06-25 2022-12-22 elopment interventions ation vités résiduelles et la créatio n de nouveaux FRANC pour l a mise en œuvre des interve ntions communautaires dan s le cadre du PMNDPE CI-PMNDPE-288640-CS-CDS / Recrutement de l’AEL CROI X ROUGE CI pour le suivi des FRANC existants prenant en Early child nutrition and dev Under Implement IDA / 61740 Post Direct Selection Direct 994,378.00 0.00 2022-04-11 2022-04-21 2022-04-21 2022-05-03 2022-06-25 2022-12-22 compte les activités résiduel elopment interventions ation les et la création de nouvea ux FRANC pour la mise en œ uvre des interventions com munautaires dans le cadre d u PMNDPE CI-PMNDPE-288629-CS-CDS / Recrutement de l'AEL NOT RE TERRE NOURRICIERE pou r le suivi des FRANC existant Early child nutrition and dev Under Implement s prenant en compte les acti IDA / 61740 Prior Direct Selection Direct 1,446,492.00 0.00 2022-04-11 2022-04-25 2022-04-21 2022-06-25 2022-12-22 elopment interventions ation vités résiduelles et la créatio n de nouveaux FRANC pour l a mise en œuvre des interve ntions communautaires dan s le cadre du PMNDPE CI-PMNDPE-291100-CS-IND V / Recrutement d’un consul tant individuel national char Early child nutrition and dev Individual Consult Under Implement IDA / 61740 Post Limited 26,000.00 0.00 2022-04-22 2022-04-14 2022-04-27 2022-04-26 2022-05-18 2022-06-22 2022-12-19 gé de collecter les données elopment interventions ant Selection ation sur le coût des interventions nutritionnelles à fort impact en Côte d’Ivoire CI-PMNDPE-324866-CS-IND V / Recrutement d’un consul Early child nutrition and dev Individual Consult Under Implement tant individuel pour l’élabora IDA / 61740 Post Limited 30,000.00 0.00 2022-11-28 2022-11-01 2022-12-03 2022-12-05 2022-12-24 2023-01-28 2023-07-27 elopment interventions ant Selection ation tion d’un guide d’installation et de fonctionnement de l’es pace DPE des FRANCS CI-PMNDPE-342820-CS-IND V / Recrutement d’un Consul Early child nutrition and dev Individual Consult Pending Impleme tant individuel pour élaborer IDA / 61740 Post Limited 16,666.00 0.00 2023-03-30 2023-04-04 2023-04-25 2023-05-30 2023-11-26 elopment interventions ant Selection ntation un manuel de bonnes pratiq ues environnementales et d e gestion sécuritaire CI-PMNDPE-342824-CS-IND V / Recrutement d’un Consul Early child nutrition and dev Individual Consult Under Implement tant individuel pour la forma IDA / 61740 Post Limited 41,666.00 0.00 2023-03-31 2023-03-29 2023-04-05 2023-04-26 2023-05-31 2023-11-27 elopment interventions ant Selection ation tion du personnel de l'UGP s ur les gestes d'urgence et d e premier secours CI-PMNDPE-343144-CS-CDS / Convention avec l'INFS pou r apporter un appui aux com munautés dans la mise en Early child nutrition and dev Under Implement IDA / 61740 Post Direct Selection Direct - National 100,000.00 0.00 2023-02-28 2023-03-09 2023-03-10 2023-04-24 2023-05-14 2023-11-10 œuvre des activités DPE dan elopment interventions ation s les FRANC à travers l'exper tise de l’INSFS (Institut Natio nal Supérieur de la Formatio n Sociale) autrefois NFS CI-PMNDPE-343145-CS-IND V / Recrutement d’un consul Early child nutrition and dev Individual Consult Pending Impleme IDA / 61740 Post Limited 16,666.00 0.00 2023-03-31 2023-04-05 2023-04-26 2023-05-31 2023-11-27 tant individuel pour produire elopment interventions ant Selection ntation un film institutionnel CI-PMNDPE-345360-CS-IND V / Recrutement d’un (e) co Early child nutrition and dev Individual Consult Under Implement nsultant (e) spécialiste en g IDA / 61740 Post Open - National 66,666.00 0.00 2023-03-17 2023-02-20 2023-05-05 2023-05-26 2023-06-30 2023-12-27 elopment interventions ant Selection ation estion financière pour l’appu i au service administratif et f inancier du PMNDPE CI-PMNDPE-345339-CS-CDS / Mission d’assistance et d’a Early child nutrition and dev Pending Impleme ppui conseil de l’AEL ARK po IDA / 61740 Post Direct Selection Direct - National 277,999.00 0.00 2023-03-01 2023-03-11 2023-05-15 2023-11-11 elopment interventions ntation ur les interventions commun autaires dans 153 villages CI-PMNDPE-345294-CS-CDS / Mission d’assistance et d’a Early child nutrition and dev Pending Impleme ppui conseil de l’AEL ONG A IDA / 61740 Post Direct Selection Direct - National 176,139.00 0.00 2023-03-01 2023-03-11 2023-05-15 2023-11-11 elopment interventions ntation DIAS pour les interventions c ommunautaires dans 123 vil lages CI-PMNDPE-345355-CS-CDS / Mission d’assistance et d’a Early child nutrition and dev Pending Impleme ppui conseil de l’AEL EICF po IDA / 61740 Post Direct Selection Direct - National 431,142.00 0.00 2023-03-01 2023-03-11 2023-05-15 2023-11-11 elopment interventions ntation ur les interventions commun autaires dans 264 villages CI-PMNDPE-345342-CS-CDS / Mission d’assistance et d’a Early child nutrition and dev Pending Impleme ppui conseil de l’AEL ASAPS IDA / 61740 Post Direct Selection Direct - National 345,547.00 0.00 2023-03-01 2023-03-11 2023-05-15 2023-11-11 elopment interventions ntation U pour les interventions com munautaires dans 190 villag es CI-PMNDPE-345310-CS-CDS / Mission d’assistance et d’a Early child nutrition and dev Pending Impleme ppui conseil de l’AEL AGI po IDA / 61740 Post Direct Selection Direct - National 300,227.00 0.00 2023-03-01 2023-03-11 2023-05-15 2023-11-11 elopment interventions ntation ur les interventions commun autaires dans 130 villages CI-PMNDPE-345336-CS-CDS / Mission d’assistance et d’a Early child nutrition and dev Pending Impleme ppui conseil de l’AEL ANADE IDA / 61740 Post Direct Selection Direct - National 465,535.00 0.00 2023-03-01 2023-03-11 2023-05-15 2023-11-11 elopment interventions ntation R pour les interventions com munautaires dans 244 villag es Page 13 CI-PMNDPE-345357-CS-CDS / Mission d’assistance et d’a Early child nutrition and dev Pending Impleme ppui conseil de l’AEL GFM3 p IDA / 61740 Post Direct Selection Direct - National 293,700.00 0.00 2023-03-01 2023-03-11 2023-05-15 2023-11-11 elopment interventions ntation our les interventions commu nautaires dans 199 villages CI-PMNDPE-345359-CS-CDS / Mission d’assistance et d’a Early child nutrition and dev Pending Impleme ppui conseil de l’AEL NTN po IDA / 61740 Post Direct Selection Direct - National 324,397.00 0.00 2023-03-01 2023-03-11 2023-05-15 2023-11-11 elopment interventions ntation ur les interventions commun autaires dans 162 villages CI-PMNDPE-345331-CS-CDS / Mission d’assistance et d’a Early child nutrition and dev Pending Impleme ppui conseil de l’AEL ALLIAN IDA / 61740 Post Direct Selection Direct - National 394,563.00 0.00 2023-03-01 2023-03-11 2023-05-15 2023-11-11 elopment interventions ntation CE CI pour les interventions communautaires dans 268 v illages CI-PMNDPE-345345-CS-CDS / Mission d’assistance et d’a Early child nutrition and dev Pending Impleme ppui conseil de l’AEL CIP pou IDA / 61740 Post Direct Selection Direct - National 333,462.00 0.00 2023-03-01 2023-03-11 2023-05-15 2023-11-11 elopment interventions ntation r les interventions communa utaires dans 174 villages CI-PMNDPE-345314-CS-CDS / Mission d’assistance et d’a Early child nutrition and dev Pending Impleme ppui conseil de l’AEL AIP pou IDA / 61740 Post Direct Selection Direct - National 345,385.00 0.00 2023-03-01 2023-03-11 2023-05-15 2023-11-11 elopment interventions ntation r les interventions communa utaires dans 216 villages CI-PMNDPE-345349-CS-CDS / Mission d’assistance et d’a Early child nutrition and dev Pending Impleme ppui conseil de l’AEL CROIX IDA / 61740 Post Direct Selection Direct - National 218,005.00 0.00 2023-03-01 2023-03-11 2023-05-15 2023-11-11 elopment interventions ntation ROUGE CI pour les interventi ons communautaires dans 1 26 villages CI-PMNDPE-345358-CS-CDS / Mission d’assistance et d’a Early child nutrition and dev Pending Impleme ppui conseil de l’AEL LUMIER IDA / 61740 Post Direct Selection Direct - National 180,752.00 0.00 2023-03-01 2023-03-11 2023-05-15 2023-11-11 elopment interventions ntation E ACTION pour les interventi ons communautaires dans 1 16 villages CI-PMNDPE-365116-CS-CDS / Recrutement d’un cabinet Early child nutrition and dev Under Implement en vue de la réalisation de l’ IDA / 61740 Post Direct Selection Direct - National 6,666.00 0.00 2023-06-06 2023-06-05 2023-06-16 2023-06-14 2023-08-20 2024-02-16 elopment interventions ation audit externe comptable et f inancier du PMNDPE pour l’e xercice 2022 Page 14 PROCUREMENT PLAN Project information: Country: Brazil Project Name: Energy and Mineral Sectors Strengthening Project II – META II (P170850) Project Implementation agency: Ministry of Energy and Mines Date of the Procurement Plan: December 17, 2020 Period covered by this Procurement Plan: The first 18 months of project implementation from the date of its effectiveness. Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the Procurement National Law or Federal Decree 10,024/2019 regulating e-reverse auctions procedures, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. a) open advertising of the procurement opportunity at the national level; b) the procurement is open to eligible firms from any country; c) the request for bids/request for proposals document shall require that Bidders/Proposers submitting Bids/Proposals present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights; d) contracts with an appropriate allocation of responsibilities, risks, and liabilities; e) publication of contract award information; f) rights for the Bank to review procurement documentation and activities; g) an effective complaints mechanism; and h) maintenance of records of the Procurement Process. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Not Applicable Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – Not Applicable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: is not applicable for those contracts identified in the Procurement Plan tables; Works: is not applicable for those contracts identified in the Procurement Plan tables. PROCUREMENT Brazil : Energy and Mineral Sectors Strengthening Project II PLAN General Information Country: Brazil 2021-01-13 Bank’s Approval Date of the Original Procurement Plan: 2023-06-05 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P170850 GPN Date: 2022-10-26 Project Name: Energy and Mineral Sectors Strengthening Project II Loan / Credit No: IBRD / 90740 Ministry of Mines and Energy Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual (30) BR-MME-210641-GO-RF Component 1 – Technical as P / Observatorio Nacional de sistance to increase efficienc Mineracao - Montagem de u y, long term infrastructure a Open - Internationa Single Stage - One E m sistema (Banco de dados) IBRD / 90740 Post Request for Bids 1,234,567.90 0.00 Canceled 2023-01-16 2023-01-21 2023-03-04 2023-04-03 2023-05-08 2023-11-04 dequacy and climate resilien l nvelope aberto do setor mineral de d ce in the energy and mining ados e informacoes de Geolo sectors. gia e Mineracao ( parceria co m IPEA ) (37) BR-MME-210614-NC-RF P / Contratação de Instituição Component 2 – Institutional de Ensino para ministrar curs strengthening of energy and os técnicos (presenciais, sem Single Stage - Two E Pending Impl IBRD / 90740 mining institutions to establi Post Request for Bids Open - National 617,283.95 0.00 2023-07-03 2023-07-08 2023-08-19 2023-11-01 2023-12-06 2025-07-28 ipresenciais, EAD) para servi nvelope ementation sh and implement strategies dores do MME, com conteúdo , policie s and regulation s programáticos desenvolvid os e elaborados pelas própria s Secretarias do Ministério. (36) BR-MME-210608-NC-RF Component 1 – Technical as P / Contratação de serviços d sistance to increase efficienc Single Stage - One E Pending Impl estinados à realização do Ce IBRD / 90740 y, long term infrastructure a Post Request for Bids Open - National 493,827.16 0.00 2022-09-04 2022-09-09 2022-10-21 2022-11-20 2022-12-25 2023-06-23 nvelope ementation nso Energético. Balanço de E dequacy and climate resilien nergia Útil ce in the energy and mining sectors. CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual (27) BR-MME-210606-CS-QC Component 1 – Technical as BS / Contratação de Consulto sistance to increase efficienc ria para Realizar o Estudo pa y, long term infrastructure a Quality And Cost- Open - Internationa IBRD / 90740 Post 740,740.74 0.00 Under Review 2022-07-04 2022-08-23 2022-07-25 2022-09-07 2022-10-05 2022-11-04 2022-12-09 2023-01-13 2024-01-13 ra a Inserção Tecnológica de dequacy and climate resilien Based Selection l Pequenas e Médias Empresa ce in the energy and mining s de Mineração para Aprimor sectors. amento do Processo Produtiv o Component 2 – Institutional (26) BR-MME-210639-CS-QC strengthening of energy and Quality And Cost- Open - Internationa Pending Impleme BS / Politica Publica para a G IBRD / 90740 mining institutions to establi Post 493,827.16 0.00 2024-02-05 2024-02-26 2024-04-10 2024-05-08 2024-06-07 2024-07-12 2024-08-16 2025-08-16 Based Selection l ntation eracao Distribuida - GD sh and implement strategies , policie s and regulation (28) BR-MME-210610-CS-QC Component 1 – Technical as BS / Mineração e sociedade: sistance to increase efficienc Estudo para elaboração de p y, long term infrastructure a Quality And Cost- Open - Internationa Under Implement oliticas públicas locais voltad IBRD / 90740 Prior 1,728,395.06 0.00 2022-07-04 2022-10-26 2022-07-25 2023-05-08 2022-09-07 2022-10-05 2022-11-04 2022-12-09 2023-01-13 2024-01-13 dequacy and climate resilien Based Selection l ation as à diversificação da matriz ce in the energy and mining econômica - atividade miner sectors. al - e percepção da sociedad e sobre a mineração (29) BR-MME-210613-CS-QC Component 1 – Technical as BS / Aproveitamento de resid sistance to increase efficienc uos da mineracao (Execucao y, long term infrastructure a Quality And Cost- Open - Internationa Pending Impleme IBRD / 90740 Prior 1,728,395.06 0.00 2023-01-16 2023-02-06 2023-03-22 2023-04-19 2023-05-19 2023-06-23 2023-07-28 2024-07-27 em parceria com a CPRM) Ap dequacy and climate resilien Based Selection l ntation roveitamento de Residuos So ce in the energy and mining lidos e Rejeitos da Mineracao sectors. (31) BR-MME-210634-NC-RF P / Economia Mineral - Subsi Component 2 – Institutional diar a estruturacao do “Obse strengthening of energy and Consultant Qualifi Open - Internationa Pending Impleme rvatorio da Mineracao” e da IBRD / 90740 mining institutions to establi Post 98,765.44 0.00 2023-01-16 2023-02-06 2023-03-22 2023-04-21 2023-05-26 2023-11-22 cation Selection l ntation area Economia Mineral (ativi sh and implement strategies dade suplementar à (30) BR- , policie s and regulation MME-210641 juntamente co m IPEA) (34) BR-MME-210636-CS-QC BS / Consultoria para identifi Component 2 – Institutional car as mudancas climaticas e strengthening of energy and Consultant Qualifi Pending Impleme mapear ameacas ao Sistema IBRD / 90740 mining institutions to establi Post Open - National 160,493.83 0.00 2024-02-01 2024-02-22 2024-04-06 2024-05-06 2024-06-10 2024-12-07 cation Selection ntation Interligado Nacional (SIN). Pr sh and implement strategies oposicao de metodos e proce , policie s and regulation ssos para o estudo da vulner abilidade sistemica do SIN. BR-MME-210637-CS-CQS / S Component 3 – Implementat upervisao ministerial e gover ion support, monitoring and Consultant Qualifi Pending Impleme IBRD / 90740 Post Open - National 148,148.15 0.00 2024-02-05 2024-02-26 2024-04-10 2024-05-10 2024-06-14 2024-12-11 nanca corporativa de estatai evaluation, knowledge shari cation Selection ntation s ng and dissemination. Page 1 (39) BR-MME-311379-CS-QC Component 2 – Institutional BS / ANÁLISE DOS IMPACTOS strengthening of energy and Quality And Cost- DA TRIBUTAÇÃO NO SETOR D IBRD / 90740 mining institutions to establi Post Open - National 171,243.00 0.00 Canceled 2022-08-23 2022-10-06 2022-09-13 2022-10-27 2022-11-24 2022-12-24 2023-01-28 2023-03-04 2024-03-03 Based Selection E GERAÇÃO DE ENERGIA ELÉ sh and implement strategies TRICA POR FONTE , policie s and regulation (39) BR-MME-360026-CS-CQ Component 2 – Institutional S / Análise dos impactos da t strengthening of energy and Consultant Qualifi Pending Impleme ributação no setor de geraçã IBRD / 90740 mining institutions to establi Post Open - National 171,243.00 0.00 2023-05-03 2023-05-24 2023-07-07 2023-08-06 2023-09-10 2024-03-08 cation Selection ntation o de energia elétrica por font sh and implement strategies e. , policie s and regulation INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 2 PROCUREMENT PLAN (Textual Part) Project information: Bosnia and Herzegovina – Real Estate Registration Project (Additional Financing) – P128950 Project Implementation agency: Federal Administration for Geodetic and Real Property Affairs and Republic of Srpska Administration for Geodetic and Property Affairs Date of the Procurement Plan: December 22, 2020 Period covered by this Procurement Plan: January – December 2021 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Not Applicable Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – Not Applicable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Specify for each Goods: Not applicable Works: Not applicable PROCUREMENT Bosnia and Herzegovina : REAL ESTATE REGISTRATION PROJECT PLAN General Information Country: Bosnia and Herzegovina 2020-12-22 Bank’s Approval Date of the Original Procurement Plan: 2023-06-07 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P128950 GPN Date: 2020-12-29 Project Name: REAL ESTATE REGISTRATION PROJECT Loan / Credit No: IBRD / 90480 Federal Administration for Geodetic and Real Property Affairs Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Request for Bids - BA-FGA-253286-CW-RFB - B. Component B - Real Estate R Single Stage - One E Works (without pr 2022-06-3 1.1.3.1 / Renovation of CO's/ IBRD / 90480 egistration Infrastructure De Post Request for Bids Open - National 236,819.99 227,865.76 Signed 2021-09-22 2021-11-04 2021-10-04 2021-11-10 2021-11-03 2021-11-30 2021-12-03 2021-11-09 2022-01-01 2022-01-07 nvelope equalification) SP 0 LRO's - Phase 1 velopment D BA-FGA-333030-CW-RFQ-B.1 Component B - Real Estate R Request for Quota .1.4.4.-3 / Land Administratio Request for Quota Single Stage - One E 2023-03-1 IBRD / 90480 egistration Infrastructure De Post Open - National tions (Non Bank-S 3,720.13 0.00 Canceled 2022-12-23 2023-02-15 n Offices - Miscellaneous-Ren tions nvelope 7 velopment PD) ovation of the FGU building BA-FGA-336623-CW-RFQ-B.1 Component B - Real Estate R Request for Quota Request for Quota Single Stage - One E 2023-03-1 .1.4.4.-3 / Land Administratio IBRD / 90480 egistration Infrastructure De Post Limited tions (Non Bank-S 3,785.28 0.00 Signed 2023-01-19 2023-02-16 2023-02-15 tions nvelope 7 n Offices - Miscellaneous- B.1 velopment PD) .1.4.4.-3 BA-FGA-367832-CW-RFQ-B.1 .1.4.4.-4 / ADAPTATION OF A Component B - Real Estate R Request for Quota DDITIONAL OFFICE SPACE AN Request for Quota Single Stage - One E Under Imple 2024-02-1 IBRD / 90480 egistration Infrastructure De Post Limited tions (Non Bank-S 4,276.74 0.00 2023-06-24 2023-08-19 D MAINTENANCE WORKS - FG tions nvelope mentation 5 velopment PD) A BUILDING” as sub-activity within B.1.1.4.4. Land Admini stration Offices – Miscellaneo us BA-FGA-368456-CW-RFQ-B.1 Component B - Real Estate R Request for Quota .1.4.4.-5 / Land Administratio Request for Quota Single Stage - One E Pending Imp 2023-10-0 IBRD / 90480 egistration Infrastructure De Post Limited tions (Non Bank-S 8,410.71 0.00 2023-06-29 2023-08-24 n Offices - Miscellaneous, Ad tions nvelope lementation 8 velopment PD) aptation of additional space f or the LRO in Mostar GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BA-FGA-212516-GO-RFQ-B.2 Component B - Real Estate R .2.1.3 / Replaceable HW com Request for Quota Single Stage - One E IBRD / 90480 egistration Infrastructure De Post Limited 24,541.99 0.00 Canceled 2021-02-01 2021-05-02 2021-07-01 ponents required for HW mai tions nvelope velopment ntenance - Phase 1 BA-FGA-227681-GO-RFQ-B.2 Component B - Real Estate R Request for Quota Single Stage - One E .2.1.3 / Replaceable HW com IBRD / 90480 egistration Infrastructure De Post Limited 35,175.00 51,011.74 Signed 2021-04-06 2021-04-16 2021-05-15 2021-05-31 2022-07-31 tions nvelope ponents required for HW mai velopment ntenance BA-FGA-239590-GO-RFQ-C.3 Component C - Policy and in Request for Quota Single Stage - One E .2.2.2 / Office supply - Phase IBRD / 90480 stitutional development, and Post Limited 6,645.85 2,540.40 Signed 2021-06-21 2021-06-18 2021-07-09 2021-07-16 2022-08-09 tions nvelope 1, CY 2021 - C.3.2.2.2 project management BA-FGA-243574-GO-RFQ - A. Component A - Real Estate R Request for Quota Single Stage - One E 2.2.2.1 / A.2.2.2.1 - Office su IBRD / 90480 egistration Data Developme Post Limited 94,751.97 95,221.32 Signed 2021-08-09 2021-08-11 2021-09-01 2021-09-04 2022-07-31 tions nvelope pply and toners - Phase 1 nt BA-FGA-248526-GO-RFQ-B.2 Component B - Real Estate R .2.1.1. / Suplly of equipment Request for Quota Single Stage - One E IBRD / 90480 egistration Infrastructure De Post Limited 100,000.00 97,292.44 Signed 2021-08-17 2021-09-08 2021-09-10 2021-10-13 2021-12-10 for the ICT system - (for cada tions nvelope velopment stre and land registry) - Phas e 1 - B.2.2.1.1. BA-FGA-248708-GO-RFB-B.1. 3.1 / Surveying technology e Component B - Real Estate R quipment - Phase 1 - B.1.3.1 Single Stage - One E IBRD / 90480 egistration Infrastructure De Post Request for Bids Open - National 277,291.84 293,382.87 Signed 2021-08-18 2021-09-03 2021-08-24 2021-09-03 2021-09-23 2021-10-04 2021-09-27 2021-10-07 2021-10-10 2021-10-29 2022-01-16 Procurement of surveying tec nvelope velopment hnology equipment, GNSS ro ver and total station. BA-FGA-250486-GO-RFQ-B.2 Component B - Real Estate R .2.1.4 / Supply of equipment Request for Quota Single Stage - One E IBRD / 90480 egistration Infrastructure De Post Limited 93,887.98 91,393.73 Signed 2021-08-27 2021-09-08 2021-09-20 2021-10-12 2021-12-20 for LR and cadaster ICT syste tions nvelope velopment ms - UPS and backup devices - B.2.2.1.4 BA-FGA-264840-GO-RFQ-B.1 Component B - Real Estate R Request for Quota Single Stage - One E .1.4.1. / Furniture for offices - IBRD / 90480 egistration Infrastructure De Post Limited 90,071.99 92,694.67 Signed 2021-12-17 2021-12-23 2022-01-04 2022-01-27 2022-05-04 tions nvelope Phase 1 - B.1.1.4.1. velopment BA-FGA-268507-GO-RFQ-B.1 Component B - Real Estate R Request for Quota Single Stage - One E .1.4.2. / Furniture for offices - IBRD / 90480 egistration Infrastructure De Post Limited 4,511.20 1,665.70 Signed 2021-12-17 2021-12-17 2021-12-24 2021-12-28 2022-01-24 tions nvelope Other phases - B.1.1.4.2 velopment BA-FGA-282738-GO-RFQ-C.3 Component C - Policy and in Request for Quota Single Stage - One E .2.2.2A / Office supply - Phas IBRD / 90480 stitutional development, and Post Limited 2,732.25 2,744.11 Signed 2022-03-14 2022-03-11 2022-04-04 2022-04-01 2022-05-09 tions nvelope e 2, CY 2022 project management BA-FGA-282742-GO-RFQ-C.3 Component C - Policy and in Request for Quota Single Stage - One E .2.2.1 / Procurement of IT eq IBRD / 90480 stitutional development, and Post Limited 4,371.60 0.00 Canceled 2022-03-21 2022-03-22 2022-04-19 2022-10-19 tions nvelope uipment for PIU project management BA-FGA-282742-GO-RFQ-C.3 Component C - Policy and in Request for Quota Single Stage - One E .2.2.1-2 / Procurement of IT e IBRD / 90480 stitutional development, and Post Limited 4,440.40 4,975.41 Signed 2022-04-04 2022-04-08 2022-04-22 2022-04-21 2022-07-22 tions nvelope quipment for PIU - C.3.2.2.1. project management BA-FGA-300023-GO-RFQ-A.2 Component A - Real Estate R Request for Quota Single Stage - One E .2.2.2. / A.2.2.2.2.-Office sup IBRD / 90480 egistration Data Developme Post Limited 78,232.49 0.00 Canceled 2022-06-30 2022-06-21 2022-08-01 2023-07-31 tions nvelope ply and toners - Phase 2 nt Page 1 BA-FGA-300506-GO-RFQ-B.2 Component B - Real Estate R .2.1.2. / Suplly of equipment Request for Quota Single Stage - One E IBRD / 90480 egistration Infrastructure De Post Limited 10,486.00 10,921.29 Signed 2022-06-22 2022-06-28 2022-07-18 2022-08-03 2022-09-16 for the ICT system - (for cada tions nvelope velopment stre and land registry) - Othe r Phases BA-FGA-305197-GO-RFQ-A.2 Component A - Real Estate R Request for Quota Single Stage - One E .2.2.2. / Office supply and ton IBRD / 90480 egistration Data Developme Post Limited 76,492.52 95,526.40 Signed 2022-07-22 2022-07-28 2022-08-27 2022-09-01 2023-08-26 tions nvelope ers - Phase 2 nt BA-FGA-318249-GO-RFQ-B.1 Component B - Real Estate R Request for Quota Single Stage - One E IBRD / 90480 Post Limited 82,955.61 0.00 Signed 2022-09-28 2022-09-29 2022-10-28 2023-05-05 .2.1. / Vehicle purchase - B.1. egistration Infrastructure De tions nvelope 2.1. velopment BA-FGA-319010-GO-RFQ-B.1 Component B - Real Estate R Request for Quota Single Stage - One E .1.4.4.-1 / Land Administratio IBRD / 90480 egistration Infrastructure De Post Limited 17,470.80 0.00 Signed 2022-10-04 2022-10-05 2022-10-27 2022-11-28 tions nvelope n Offices-Miscellaneous_Archi velopment ve shelves BA-FGA-319012-GO-RFQ-B.1 Component B - Real Estate R Request for Quota Single Stage - One E .1.4.4.-2 / Land Administratio IBRD / 90480 egistration Infrastructure De Post Limited 2,426.50 0.00 Signed 2022-10-05 2022-10-05 2022-10-28 2022-11-28 tions nvelope n Offices Miscellaneous_Proje velopment ct plaques BA-FGA-319033-GO-RFB-B.1. Component B - Real Estate R Single Stage - One E 3.2. / Surveying technology e IBRD / 90480 egistration Infrastructure De Post Request for Bids Open - National 142,678.21 0.00 Signed 2022-09-30 2022-10-06 2022-10-03 2022-10-06 2022-10-23 2022-11-17 2022-10-27 2022-10-28 2022-12-01 2023-06-03 nvelope quipment - Phase 2 velopment BA-FGA-338305-GO-RFQ-C.3 Component C - Policy and in Request for Quota Single Stage - One E .2.2.3. / Office supply - Phase IBRD / 90480 stitutional development, and Post Limited 2,718.75 0.00 Signed 2023-01-26 2023-02-09 2023-02-16 2023-03-16 tions nvelope 3, CY 2023 project management BA-FGA-347663-GO-RFB-B.1. Component B - Real Estate R Single Stage - One E 3.2.-2 / Surveying technology IBRD / 90480 egistration Infrastructure De Post Request for Bids Open - National 4,907.43 0.00 Canceled 2023-03-07 2023-01-30 2023-03-07 2023-03-31 2023-03-31 2023-04-03 2023-04-05 2023-06-28 nvelope equipment - Phase 2 velopment BA-FGA-368879-GO-RFQ-A.2 Component A - Real Estate R Request for Quota Single Stage - One E Under Imple .2.2.6. / A.2.2.2.6. Office sup IBRD / 90480 egistration Data Developme Post Limited 70,000.00 0.00 2023-06-27 2023-06-27 2023-08-07 2024-07-31 tions nvelope mentation ply and toners - Phase 3 nt NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BA-FGA-212390-NC-RFQ-A.1. Component A - Real Estate R 3.1 / Printing of promo materi Request for Quota Single Stage - One E IBRD / 90480 egistration Data Developme Post Limited 18,408.65 1,757.59 Signed 2021-01-15 2021-01-29 2021-03-31 2021-03-02 2022-07-31 al (brochures, flyers, posters, tions nvelope nt and other promo mat.) - Phas e1 BA-FGA-212394-NC-RFB-A.2. Component A - Real Estate R Single Stage - One E 1.1.1 / Harmonization data o IBRD / 90480 egistration Data Developme Post Request for Bids Open - National 983,679.97 743,497.20 Signed 2021-01-07 2021-02-05 2021-01-12 2021-02-05 2021-02-26 2021-03-22 2021-03-10 2021-04-02 2021-04-12 2021-04-22 2021-10-09 nvelope n cadastre and land book - P nt hase 1 BA-FGA-212457-NC-RFB-A.3. Component A - Real Estate R 1 / Vectorization and cadastr Single Stage - One E IBRD / 90480 egistration Data Developme Post Request for Bids Open - National 122,709.96 128,287.42 Signed 2021-01-07 2021-02-01 2021-01-12 2021-02-02 2021-02-26 2021-03-19 2021-03-05 2021-04-02 2021-04-12 2021-04-22 2021-08-25 al database creation (prepar nvelope nt ation for REC) - Phase 1 BA-FGA-212461-NC-RFB-B.3. Component B - Real Estate R Single Stage - One E 2.1 / Cadastral scanning and IBRD / 90480 egistration Infrastructure De Post Request for Bids Open - National 49,083.98 43,712.73 Signed 2021-01-07 2021-02-05 2021-01-12 2021-02-05 2021-02-26 2021-03-22 2021-03-05 2021-04-02 2021-04-12 2021-04-30 2021-08-10 nvelope indexing for digital archives - velopment Phase 1 BA-FGA-212703-NC-DIR - A.2 Component A - Real Estate R .2.2.3.1 / Publishing costs - O IBRD / 90480 egistration Data Developme Post Direct Selection Direct 2,207.91 5,374.71 Signed 2021-01-07 2021-01-01 2021-01-07 2021-01-04 2021-01-12 2021-01-13 2021-12-31 fficial Gazette of B&H, Officia nt l Gazette of Federation B&H BA-FGA-212704-NC-DIR-A.2. Component A - Real Estate R 2.2.3.2 / Publishing costs - da IBRD / 90480 egistration Data Developme Post Direct Selection Direct 2,207.91 13,534.94 Signed 2021-01-07 2021-01-01 2021-01-07 2021-01-04 2021-01-12 2021-01-13 2021-12-31 ily newspaper Avaz -roto pre nt ss d.o.o. Sarajevo BA-FGA-212705-NC-DIR-A.2. Component A - Real Estate R 2.2.3.3 / Publishing costs - da IBRD / 90480 egistration Data Developme Post Direct Selection Direct 2,207.91 11,125.25 Signed 2021-01-07 2021-01-01 2021-01-07 2021-01-04 2021-01-12 2021-01-13 2021-12-31 ily newspaper Večernji List nt BA-FGA-213262-NC-DIR- A.2. Component A - Real Estate R 2.2.5.1 / Delivery cost of Deci IBRD / 90480 egistration Data Developme Post Direct Selection Direct 6,106.74 375.88 Completed 2021-01-11 2021-01-01 2021-01-12 2020-12-23 2021-02-01 2021-02-02 2022-12-31 2022-01-01 sions on registrations (Two p nt osts) - JP BH POŠTA d.o.o. Sar ajevo BA-FGA-213268-NC-DIR-A.2. Component A - Real Estate R 2.2.5.2 / Delivery cost of Deci IBRD / 90480 egistration Data Developme Post Direct Selection Direct 6,106.74 375.88 Completed 2021-01-11 2021-01-01 2021-01-12 2020-12-29 2021-02-01 2021-02-02 2022-12-31 2022-01-01 sions on registrations (Two p nt osts) - Hrvatska pošta d.o.o. Mostar BA-FGA-236325-NC-RFQ-B.3. Component B - Real Estate R Request for Quota Single Stage - One E 3.1 / Indexing of land registry IBRD / 90480 egistration Infrastructure De Post Limited 18,318.00 7,567.55 Signed 2021-06-01 2021-07-07 2021-08-10 2021-07-28 2022-01-31 tions nvelope data for digital archives - Pha velopment se 1 BA-FGA-253609-NC-RFB-A.3. Component A - Real Estate R 2 / Vectorization and cadastr Single Stage - One E IBRD / 90480 egistration Data Developme Post Request for Bids Open - National 153,581.98 95,260.57 Signed 2021-09-16 2021-09-20 2021-09-23 2021-09-24 2021-11-07 2021-10-25 2021-11-22 2021-11-02 2021-12-22 2021-11-23 2022-05-06 al database creation (prepar nvelope nt ation for REC) - Phase 2 BA-FGA-260299-NC-RFQ-A.1. Component A - Real Estate R 3.1.B / Printing of promo mat Request for Quota Single Stage - One E IBRD / 90480 egistration Data Developme Post Limited 8,712.75 8,167.32 Signed 2021-11-01 2021-11-05 2021-11-23 2021-11-18 2022-07-31 erial (brochures, flyers, poste tions nvelope nt rs, and other promo mat.) - A .1.3.1.B BA-FGA-282733-NC-RFQ-B.3. Component B - Real Estate R Request for Quota Single Stage - One E 2.2 / Cadastral scanning and IBRD / 90480 egistration Infrastructure De Post Limited 93,989.40 83,177.58 Signed 2022-03-14 2022-03-14 2022-04-20 2022-04-15 2022-08-18 tions nvelope indexing for digital archives - velopment Phase 2 BA-FGA-282730-NC-RFB-A.2. Component A - Real Estate R Open - Internationa Single Stage - One E 1.1.2 / Harmonization data o IBRD / 90480 egistration Data Developme Post Request for Bids 1,202,190.12 872,556.02 Signed 2022-03-08 2022-03-10 2022-03-14 2022-03-14 2022-04-28 2022-04-28 2022-05-05 2022-05-12 2022-05-24 2022-05-29 2022-11-20 l nvelope n cadastre and land book - P nt hase 2 Page 2 BA-FGA-296920-NC-RFB-A.2. Component A - Real Estate R 1.1.2.-LOT 2 / Harmonization Single Stage - One E IBRD / 90480 egistration Data Developme Post Request for Bids Open - National 334,217.43 321,478.64 Signed 2022-05-25 2022-05-27 2022-05-27 2022-05-27 2022-07-11 2022-06-27 2022-07-15 2022-06-29 2022-08-10 2022-07-16 2023-02-06 data on cadastre and land bo nvelope nt ok - Phase 2 - lot 2 BA-FGA-319007-NC-RFQ-A.1. Component A - Real Estate R Request for Quota Single Stage - One E 3.1.C / Printing promo materi IBRD / 90480 egistration Data Developme Post Limited 4,853.00 0.00 Signed 2022-10-03 2022-10-13 2022-11-25 2022-12-31 tions nvelope al - Phase III, 2022 nt BA-FGA-321396-NC-RFQ-B.3. Component B - Real Estate R Request for Quota Single Stage - One E 2.3. / Cadastral scanning and IBRD / 90480 egistration Infrastructure De Post Limited 88,624.91 0.00 Signed 2022-10-29 2022-11-22 2022-11-28 2023-03-28 tions nvelope indexing for digital archives - velopment Phase 3 BA-FGA-319029-NC-RFQ-A.2. Component A - Real Estate R 1.2.1. / Preparation and conv Request for Quota Single Stage - One E IBRD / 90480 egistration Data Developme Post Open - National 67,942.01 0.00 Canceled 2022-10-05 2022-10-31 2023-03-31 ersion of real estate cadastre tions nvelope nt data for handover to land reg istry BA-FGA-321692-CS-INDV-A.2 Component B - Real Estate R .1.2.1. / Preparation and conv Request for Quota Single Stage - One E IBRD / 90480 egistration Infrastructure De Post Limited 50,596.80 0.00 Signed 2022-10-18 2022-10-18 2022-11-07 2023-04-11 ersion of real estate cadastre tions nvelope velopment data for handover to land reg istry BA-FGA-368414-NC-RFB-B.3. Component B - Real Estate R Single Stage - One E Under Imple 2.4. / Cadastral scanning and IBRD / 90480 egistration Infrastructure De Post Request for Bids Open - National 194,429.42 0.00 2023-06-22 2023-06-22 2023-06-27 2023-06-26 2023-08-11 2023-09-10 2023-10-15 2024-02-12 nvelope mentation indexing for digital archives - velopment Phase 4 CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BA-FGA-227687-CS-CQS-B.1. Component B - Real Estate R 1.2A / Design for renovation Consultant Qualifi IBRD / 90480 egistration Infrastructure De Post Open - National 58,625.01 42,039.92 Signed 2021-04-01 2021-04-06 2021-04-22 2021-06-07 2021-05-24 2021-06-30 2021-05-26 2021-07-15 2021-07-07 2021-07-17 2022-07-15 od CO's/LRO's and Supervisi cation Selection velopment on of renovation works of CO' s/LRO's BA-FGA-236340-CS-CQS-C.2. 2.1-A.1.2.1 / Project Public A Component A - Real Estate R Consultant Qualifi wareness Campaigne (C.2.2. IBRD / 90480 egistration Data Developme Post Open - National 79,378.00 59,502.35 Signed 2021-05-25 2021-05-27 2021-06-09 2021-06-08 2021-07-12 2021-07-07 2021-07-26 2021-08-10 2021-08-16 2021-08-17 2022-07-31 cation Selection 1) and Media Services (Local nt Radio and TV) - Phase 1 (A.1. 2.1) BA-FGA-247342-CS-CQS-B.2. Component B - Real Estate R Consultant Qualifi 2.7. / Cyber security policy a IBRD / 90480 egistration Infrastructure De Post Open - National 35,421.00 52,512.37 Signed 2021-08-11 2021-08-11 2021-08-16 2021-08-17 2021-09-03 2021-10-07 2021-09-08 2021-12-01 2021-09-10 2021-12-09 2022-01-10 cation Selection nd action plan-B.2.2.7. velopment BA-FGA-301700-CS-CQS-B.1. 1.2C-B.1.1.2D / Design for re Component B - Real Estate R Consultant Qualifi novation od CO's/LRO's - Pha IBRD / 90480 egistration Infrastructure De Post Open - National 26,310.01 0.00 Canceled 2022-06-28 2022-06-29 2022-06-30 2022-06-30 2022-07-17 2022-07-20 2022-08-01 2024-07-31 cation Selection se 2-Supervision of renovatio velopment n works of CO's/LRO's - Phas e2 BA-FGA-301724-CS-CQS-A.1. Component A - Real Estate R Consultant Qualifi 2.2. / Media Services (Local R IBRD / 90480 egistration Data Developme Post Open - National 21,048.00 11,251.92 Signed 2022-06-28 2022-06-29 2022-06-30 2022-06-30 2022-07-17 2022-08-15 2022-07-20 2022-09-16 2022-09-01 2022-09-29 2024-07-31 cation Selection adio and TV) - Phase 2 nt BA-FGA-301700-CS-CQS-B.1. 1.2C-B.1.1.2D-2 / Design for r Component B - Real Estate R Consultant Qualifi enovation od CO's/LRO's - Ph IBRD / 90480 egistration Infrastructure De Post Open - National 24,817.49 0.00 Signed 2022-08-24 2022-08-29 2022-09-01 2022-09-01 2022-09-18 2022-10-28 2022-09-21 2022-12-16 2022-10-03 2023-04-01 cation Selection ase 2-Supervision of renovati velopment on works of CO's/LRO's - Pha se 2 BA-FGA-347664-CS-CQS-C.3. Component C - Policy and in Consultant Qualifi Under Implement 1.1. / C.3.1.1. - Customer sati IBRD / 90480 stitutional development, and Post Open - National 26,662.39 0.00 2023-03-07 2023-01-26 2023-03-07 2023-06-12 2023-03-15 2023-03-31 2023-03-17 2023-03-21 2023-09-19 cation Selection ation sfaction study project management INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BA-FGA-210575-CS-CDS - C. Component C - Policy and in 3.2.1A.1 / Monitoring and Eva IBRD / 90480 stitutional development, and Post Direct Selection Direct 9,705.61 9,577.77 Completed 2020-12-17 2020-12-23 2020-12-21 2020-12-22 2021-01-01 2021-01-02 2021-03-31 2021-04-01 luation Specialist project management BA-FGA-210580-CS-CDS - C. Component C - Policy and in 3.2.1A.2 / Procurement speci IBRD / 90480 stitutional development, and Post Direct Selection Direct 5,510.34 55,260.12 Signed 2020-12-17 2020-12-23 2020-12-21 2020-12-22 2021-01-01 2021-01-02 2021-03-31 alist project management BA-FGA-210581-CS-CDS - C. Component C - Policy and in 3.2.1A.3 / Administrative assi IBRD / 90480 stitutional development, and Post Direct Selection Direct 4,007.61 40,821.15 Signed 2020-12-17 2020-12-23 2020-12-21 2020-12-22 2021-01-01 2021-01-06 2021-03-31 stant project management Component C - Policy and in BA-FGA-210582-CS-CDS - C. IBRD / 90480 stitutional development, and Post Direct Selection Direct 5,510.70 53,582.12 Signed 2020-12-17 2020-12-23 2020-12-21 2020-12-22 2021-01-01 2021-01-02 2021-03-31 3.2.1A.4 / Finance consultant project management BA-FGA-210585-CS-CDS - C. Component C - Policy and in 3.2.1A.5 / Land Administratio IBRD / 90480 stitutional development, and Post Direct Selection Direct 5,510.70 55,362.38 Signed 2020-12-17 2020-12-23 2020-12-21 2020-12-22 2021-01-01 2021-01-02 2021-03-31 n specialist project management Component C - Policy and in BA-FGA-210592-CS-CDS - C. IBRD / 90480 stitutional development, and Post Direct Selection Direct 5,510.70 54,813.85 Signed 2020-12-17 2020-12-23 2020-12-21 2020-12-22 2021-01-01 2021-01-02 2021-03-31 3.2.1A.6 / Cadastre specialist project management BA-FGA-210598-CS-CDS - B. Component B - Real Estate R IBRD / 90480 Post Direct Selection Direct 5,320.37 53,861.99 Signed 2020-12-17 2020-12-23 2020-12-21 2020-12-22 2021-01-01 2021-01-02 2021-03-31 2.1.1A.1 / IT Consultant egistration Infrastructure De velopment BA-FGA-210600-CS-CDS - A. Component A - Real Estate R IBRD / 90480 Post Direct Selection Direct 4,446.53 2,007.67 Terminated 2020-12-17 2020-12-23 2020-12-21 2020-12-22 2021-01-01 2021-01-02 2021-03-31 1.1.1A.1 / Social Specialist egistration Data Developme nt BA-FGA-210601-CS-CDS - A. Component A - Real Estate R 2.2.2.4A.1 / Individual consul IBRD / 90480 egistration Data Developme Post Direct Selection Direct 6,262.57 6,275.09 Signed 2020-12-17 2020-12-23 2020-12-21 2020-12-22 2021-01-01 2021-01-06 2021-12-31 tant for delivery of decisions nt on registration Page 3 BA-FGA-210744-CS-CDS - A. Component A - Real Estate R 2.2.2.4A.2 / Individual consul IBRD / 90480 egistration Data Developme Post Direct Selection Direct 8,772.05 8,785.12 Signed 2020-12-18 2020-12-23 2020-12-23 2020-12-22 2021-01-01 2021-01-06 2021-12-31 tant for delivery of decisions nt on registration BA-FGA-210745-CS-CDS - A. Component A - Real Estate R 2.2.2.4A.3 / Individual consul IBRD / 90480 egistration Data Developme Post Direct Selection Direct 9,404.98 17,396.96 Signed 2020-12-18 2020-12-23 2020-12-22 2020-12-22 2021-01-01 2021-01-02 2021-12-31 tant for delivery of decisions nt on registration BA-FGA-210746-CS-CDS - A. Component A - Real Estate R 2.2.2.4A.4 / Individual consul IBRD / 90480 egistration Data Developme Post Direct Selection Direct 7,524.87 7,530.10 Signed 2020-12-18 2020-12-23 2020-12-22 2020-12-22 2021-01-01 2021-01-02 2021-12-31 tant for delivery of decisions nt on registration BA-FGA-210748-CS-CDS - A. Component A - Real Estate R 2.2.2.4A.5 / Individual consul IBRD / 90480 egistration Data Developme Post Direct Selection Direct 8,779.54 4,034.69 Terminated 2020-12-18 2020-12-23 2020-12-22 2020-12-22 2021-01-01 2021-01-02 2021-12-31 tant for delivery of decisions nt on registration BA-FGA-210751-CS-CDS - A. Component A - Real Estate R 2.2.2.4A.6 / Individual consul IBRD / 90480 egistration Data Developme Post Direct Selection Direct 6,270.73 11,515.20 Signed 2020-12-18 2020-12-23 2020-12-22 2020-12-22 2021-01-01 2021-01-06 2021-12-31 tant for delivery of decisions nt on registration BA-FGA-210754-CS-CDS - A. Component A - Real Estate R 2.2.2.4A.7 / Individual consul IBRD / 90480 egistration Data Developme Post Direct Selection Direct 8,775.99 8,785.12 Terminated 2020-12-18 2020-12-23 2020-12-22 2020-12-22 2021-01-01 2021-01-02 2021-12-31 tant for delivery of decisions nt on registration Component C - Policy and in BA-FGA-210755-CS-CDS - C. IBRD / 90480 stitutional development, and Post Direct Selection Direct 739.96 848.02 Completed 2020-12-18 2020-12-23 2020-12-24 2020-12-22 2021-01-01 2021-01-02 2021-03-31 2021-04-01 3.2.3.1A.1 / Interpreter project management BA-FGA-210756-CS-CDS - A. Component A - Real Estate R 2.2.1A.1 / Temporary Land R IBRD / 90480 egistration Data Developme Post Direct Selection Direct 7,518.69 14,093.71 Signed 2020-12-18 2020-12-23 2020-12-22 2020-12-22 2021-01-01 2021-01-06 2021-12-31 egistry Assistant nt BA-FGA-210758-CS-CDS - A. Component A - Real Estate R 2.2.1A.2 / Temporary Land R IBRD / 90480 egistration Data Developme Post Direct Selection Direct 7,518.69 14,093.71 Signed 2020-12-18 2020-12-23 2020-12-22 2020-12-22 2021-01-01 2021-01-02 2021-12-31 egistry Assistant nt BA-FGA-210759-CS-CDS - A. Component A - Real Estate R 2.2.1A.3 / Temporary Land R IBRD / 90480 egistration Data Developme Post Direct Selection Direct 7,518.69 9,033.46 Signed 2020-12-18 2020-12-23 2020-12-22 2020-12-22 2021-01-01 2021-01-02 2021-12-31 egistry Assistant nt BA-FGA-210761-CS-CDS - A. Component A - Real Estate R 2.2.1A.4 / Temporary Land R IBRD / 90480 egistration Data Developme Post Direct Selection Direct 9,397.38 1,466.65 Terminated 2020-12-18 2020-12-23 2020-12-22 2020-12-22 2021-01-01 2021-01-02 2021-12-31 egistry Assistant nt BA-FGA-210762-CS-CDS - A. Component A - Real Estate R 2.2.1A.5 / Temporary Land R IBRD / 90480 egistration Data Developme Post Direct Selection Direct 9,397.38 12,082.98 Signed 2020-12-18 2020-12-23 2020-12-22 2020-12-22 2021-01-01 2021-01-02 2021-12-31 egistry Assistant nt BA-FGA-210763-CS-CDS - A. Component A - Real Estate R 2.2.1A.6 / Temporary Land R IBRD / 90480 egistration Data Developme Post Direct Selection Direct 7,516.60 4,275.25 Completed 2020-12-18 2020-12-23 2020-12-22 2020-12-22 2021-01-01 2021-01-02 2021-12-31 2022-01-01 egistry Assistant nt BA-FGA-210764-CS-CDS- A.2 Component A - Real Estate R .2.1A.7 / Temporary Land Re IBRD / 90480 egistration Data Developme Post Direct Selection Direct 9,394.61 1,131.62 Terminated 2020-12-18 2020-12-23 2020-12-22 2020-12-22 2021-01-01 2021-01-02 2021-12-31 gistry Assistant nt BA-FGA-210765-CS-CDS -A.2 Component A - Real Estate R .2.1A.8 / Temporary Land Re IBRD / 90480 egistration Data Developme Post Direct Selection Direct 7,514.60 0.00 Completed 2020-12-18 2020-12-23 2020-12-22 2020-12-22 2021-01-01 2021-01-02 2021-12-31 2022-01-01 gistry Assistant nt BA-FGA-210766-CS-CDS - A. Component A - Real Estate R 2.2.1A.9 / Temporary Land R IBRD / 90480 egistration Data Developme Post Direct Selection Direct 11,272.58 9,429.09 Terminated 2020-12-18 2020-12-23 2020-12-22 2020-12-22 2021-01-01 2021-01-02 2021-12-31 egistry Assistant nt BA-FGA-210767-CS-CDS-A.2. Component A - Real Estate R 2.1A.10 / Temporary Land Re IBRD / 90480 egistration Data Developme Post Direct Selection Direct 11,272.58 10,327.54 Terminated 2020-12-18 2020-12-23 2020-12-22 2020-12-22 2021-01-01 2021-01-02 2021-12-31 gistry Assistant nt BA-FGA-210769-CS-CDS-A.2. Component A - Real Estate R 2.1A.11 / Temporary Land Re IBRD / 90480 egistration Data Developme Post Direct Selection Direct 9,393.21 22,834.55 Signed 2020-12-18 2020-12-23 2020-12-22 2020-12-22 2021-01-01 2021-01-02 2021-12-31 gistry Assistant nt BA-FGA-210771-CS-CDS-A.2. Component A - Real Estate R 2.1A.12 / Temporary Land Re IBRD / 90480 egistration Data Developme Post Direct Selection Direct 9,393.21 15,157.50 Signed 2020-12-18 2020-12-23 2020-12-22 2020-12-22 2021-01-01 2021-01-02 2021-12-31 gistry Assistant nt BA-FGA-210774-CS-CDS-A.2. Component A - Real Estate R 2.1A.13 / Temporary Land Re IBRD / 90480 egistration Data Developme Post Direct Selection Direct 9,393.21 19,971.32 Signed 2020-12-18 2020-12-23 2020-12-22 2020-12-22 2021-01-01 2021-01-02 2021-12-31 gistry Assistant nt BA-FGA-210775-CS-CDS-A.2. Component A - Real Estate R 2.1A.14 / Temporary Land Re IBRD / 90480 egistration Data Developme Post Direct Selection Direct 9,393.21 17,412.30 Signed 2020-12-21 2020-12-23 2020-12-23 2020-12-22 2021-01-01 2021-01-02 2021-12-31 gistry Assistant nt BA-FGA-210778-CS-CDS-A.2. Component A - Real Estate R 2.1A.15 / Temporary Land Re IBRD / 90480 egistration Data Developme Post Direct Selection Direct 12,525.38 10,559.37 Completed 2020-12-18 2020-12-23 2020-12-22 2020-12-22 2021-01-01 2021-01-02 2021-12-31 2022-01-01 gistry Assistant nt BA-FGA-210780-CS-CDS-A.2. Component A - Real Estate R 2.1A.16 / Temporary Land Re IBRD / 90480 egistration Data Developme Post Direct Selection Direct 12,525.38 23,229.52 Signed 2020-12-18 2020-12-23 2020-12-22 2020-12-22 2021-01-01 2021-01-02 2021-12-31 gistry Assistant nt BA-FGA-210785-CS-CDS-A.2. Component A - Real Estate R 2.1A.18 / Temporary Land Re IBRD / 90480 egistration Data Developme Post Direct Selection Direct 3,131.80 21,590.71 Signed 2020-12-18 2020-12-23 2020-12-22 2020-12-22 2021-01-01 2021-01-06 2021-07-31 gistry Assistant nt BA-FGA-210787-CS-CDS - A. Component A - Real Estate R 2.2.1A.19 / Temporary Land IBRD / 90480 egistration Data Developme Post Direct Selection Direct 3,131.80 22,057.76 Signed 2020-12-18 2020-12-23 2020-12-22 2020-12-22 2021-01-01 2021-01-02 2021-07-31 Registry Assistant nt BA-FGA-210790-CS-CDS - A. Component A - Real Estate R 2.2.1A.21 / Temporary Land IBRD / 90480 egistration Data Developme Post Direct Selection Direct 3,131.80 22,051.63 Signed 2020-12-18 2020-12-23 2020-12-22 2020-12-22 2021-01-01 2021-01-06 2021-07-31 Registry Assistant nt BA-FGA-210791-CS-CDS-A.2. Component A - Real Estate R 2.1A.22 / Temporary Land Re IBRD / 90480 egistration Data Developme Post Direct Selection Direct 3,131.80 2,493.50 Terminated 2020-12-18 2020-12-23 2020-12-22 2020-12-22 2021-01-01 2021-01-02 2021-07-31 gistry Assistant nt Page 4 BA-FGA-210792-CS-CDS - A. Component A - Real Estate R 2.2.1A.23 / Temporary Land IBRD / 90480 egistration Data Developme Post Direct Selection Direct 3,131.80 261.39 Terminated 2020-12-18 2020-12-23 2020-12-22 2020-12-22 2021-01-01 2021-01-02 2021-07-31 Registry Assistant nt BA-FGA-210793-CS-CDS-A.2. Component A - Real Estate R 2.1A.24 / Temporary Land Re IBRD / 90480 egistration Data Developme Post Direct Selection Direct 3,131.80 149.46 Terminated 2020-12-18 2020-12-23 2020-12-22 2020-12-22 2021-01-01 2021-01-02 2021-07-31 gistry Assistant nt BA-FGA-210795-CS-CDS - A. Component A - Real Estate R 2.2.1A.25 / Temporary Land IBRD / 90480 egistration Data Developme Post Direct Selection Direct 7,514.06 7,515.38 Signed 2020-12-18 2020-12-23 2020-12-22 2020-12-22 2021-01-01 2021-01-02 2021-12-31 Registry Assistant nt BA-FGA-210796-CS-CDS-A.2. Component A - Real Estate R 2.1A.26 / Temporary Land Re IBRD / 90480 egistration Data Developme Post Direct Selection Direct 7,514.06 2,569.68 Terminated 2020-12-18 2020-12-23 2020-12-22 2020-12-22 2021-01-01 2021-01-02 2021-12-31 gistry Assistant nt BA-FGA-210798-CS-CDS-A.2. Component A - Real Estate R 2.1A.27 / Temporary Land Re IBRD / 90480 egistration Data Developme Post Direct Selection Direct 9,392.15 1,404.30 Terminated 2020-12-18 2020-12-23 2020-12-22 2020-12-22 2021-01-01 2021-01-02 2021-12-31 gistry Assistant nt BA-FGA-210800-CS-CDS - A. Component A - Real Estate R 2.2.1A.28 / Temporary Land IBRD / 90480 egistration Data Developme Post Direct Selection Direct 9,392.15 16,984.60 Signed 2020-12-18 2020-12-23 2020-12-22 2020-12-22 2021-01-01 2021-01-02 2021-12-31 Registry Assistant nt BA-FGA-210801-CS-CDS-A.2. Component A - Real Estate R 2.1A.29 / Temporary Land Re IBRD / 90480 egistration Data Developme Post Direct Selection Direct 9,392.15 20,217.76 Signed 2020-12-18 2020-12-23 2020-12-22 2020-12-22 2021-01-01 2021-01-02 2021-12-31 gistry Assistant nt BA-FGA-210803-CS-CDS-A.2. Component A - Real Estate R 2.1A.30 / Temporary Land Re IBRD / 90480 egistration Data Developme Post Direct Selection Direct 8,140.42 9,386.57 Terminated 2020-12-18 2020-12-23 2020-12-22 2020-12-22 2021-01-01 2021-01-02 2021-12-31 gistry Assistant nt BA-FGA-210805-CS-CDS - A. Component A - Real Estate R 2.2.1A.31 / Temporary Land IBRD / 90480 egistration Data Developme Post Direct Selection Direct 8,140.42 14,581.43 Signed 2020-12-18 2020-12-23 2020-12-22 2020-12-22 2021-01-01 2021-01-02 2021-12-31 Registry Assistant nt BA-FGA-210807-CS-CDS - A. Component A - Real Estate R 2.2.1A.32 / Temporary Land IBRD / 90480 egistration Data Developme Post Direct Selection Direct 9,395.63 22,966.72 Signed 2020-12-18 2020-12-23 2020-12-22 2020-12-22 2021-01-01 2021-01-02 2021-12-31 Registry Assistant nt BA-FGA-210808-CS-CDS - A. Component A - Real Estate R 2.2.1A.33 / Temporary Land IBRD / 90480 egistration Data Developme Post Direct Selection Direct 9,395.63 22,966.72 Signed 2020-12-18 2020-12-23 2020-12-22 2020-12-22 2021-01-01 2021-01-06 2021-12-31 Registry Assistant nt BA-FGA-210810-CS-CDS - A. Component A - Real Estate R 2.2.1A.34 / Temporary Land IBRD / 90480 egistration Data Developme Post Direct Selection Direct 9,395.63 22,966.72 Signed 2020-12-18 2020-12-23 2020-12-22 2020-12-22 2021-01-01 2021-01-06 2021-12-31 Registry Assistant nt BA-FGA-210811-CS-CDS - A. Component A - Real Estate R 2.2.1A.35 / Temporary Land IBRD / 90480 egistration Data Developme Post Direct Selection Direct 9,395.63 22,966.72 Signed 2020-12-18 2020-12-23 2020-12-22 2020-12-22 2021-01-01 2021-01-02 2021-12-31 Registry Assistant nt BA-FGA-211121-CS-CDS - A. Component A - Real Estate R 2.2.1A.36 / Temporary Land IBRD / 90480 egistration Data Developme Post Direct Selection Direct 11,172.99 10,073.75 Completed 2020-12-21 2020-12-23 2020-12-23 2020-12-22 2021-01-01 2021-01-02 2021-12-31 2022-01-01 Registry Assistant nt BA-FGA-211122-CS-CDS - A. Component A - Real Estate R 2.2.1A.37 / Temporary Land IBRD / 90480 egistration Data Developme Post Direct Selection Direct 11,172.99 22,554.82 Signed 2020-12-21 2020-12-23 2020-12-23 2020-12-22 2021-01-01 2021-01-02 2021-12-31 Registry Assistant nt BA-FGA-211124-CS-CDS - A. Component A - Real Estate R 2.2.1A.38 / Temporary Land IBRD / 90480 egistration Data Developme Post Direct Selection Direct 11,172.99 23,200.07 Signed 2020-12-21 2020-12-23 2020-12-23 2020-12-22 2021-01-01 2021-01-02 2021-12-31 Registry Assistant nt BA-FGA-211126-CS-CDS - A. Component A - Real Estate R 2.2.1A.39 / Temporary Land IBRD / 90480 egistration Data Developme Post Direct Selection Direct 12,420.26 29,050.58 Signed 2020-12-21 2020-12-23 2020-12-23 2020-12-22 2021-01-01 2021-01-02 2021-12-31 Registry Assistant nt BA-FGA-211127-CS-CDS-A.2. Component A - Real Estate R 2.1A.40 / Temporary Land Re IBRD / 90480 egistration Data Developme Post Direct Selection Direct 4,967.38 5,010.25 Signed 2020-12-21 2020-12-23 2020-12-23 2020-12-22 2021-01-01 2021-01-02 2021-12-31 gistry Assistant nt BA-FGA-211132-CS-CDS - A. Component A - Real Estate R 2.2.1A.42 / Temporary Land IBRD / 90480 egistration Data Developme Post Direct Selection Direct 9,315.48 20,156.79 Signed 2020-12-21 2020-12-23 2020-12-23 2020-12-22 2021-01-01 2021-01-02 2021-12-31 Registry Assistant nt BA-FGA-211133-CS-CDS - A. Component A - Real Estate R 2.2.1A.43 / Temporary Land IBRD / 90480 egistration Data Developme Post Direct Selection Direct 9,315.48 13,560.05 Signed 2020-12-21 2020-12-23 2020-12-23 2020-12-22 2021-01-01 2021-01-02 2021-12-31 Registry Assistant nt BA-FGA-211135-CS-CDS-A.2. Component A - Real Estate R 2.1A.44 / Temporary Land Re IBRD / 90480 egistration Data Developme Post Direct Selection Direct 9,315.48 3,717.81 Terminated 2020-12-21 2020-12-23 2020-12-23 2020-12-22 2021-01-01 2021-01-02 2021-12-31 gistry Assistant nt BA-FGA-211137-CS-CDS - A. Component A - Real Estate R 2.2.1A.45 / Temporary Land IBRD / 90480 egistration Data Developme Post Direct Selection Direct 9,315.48 12,284.04 Signed 2020-12-21 2020-12-23 2020-12-23 2020-12-22 2021-01-01 2021-01-02 2021-12-31 Registry Assistant nt BA-FGA-211139-CS-CDS - A. Component A - Real Estate R 2.2.1A.46 / Temporary Land IBRD / 90480 egistration Data Developme Post Direct Selection Direct 9,315.48 679.51 Terminated 2020-12-21 2020-12-23 2020-12-23 2020-12-22 2021-01-01 2021-01-02 2021-12-31 Registry Assistant nt BA-FGA-211140-CS-CDS - A. Component A - Real Estate R 2.2.1A.47 / Temporary Land IBRD / 90480 egistration Data Developme Post Direct Selection Direct 9,315.48 17,402.07 Signed 2020-12-21 2020-12-23 2020-12-23 2020-12-22 2021-01-01 2021-01-02 2021-12-31 Registry Assistant nt BA-FGA-211141-CS-CDS - A. Component A - Real Estate R 2.2.1A.48 / Temporary Land IBRD / 90480 egistration Data Developme Post Direct Selection Direct 9,315.48 17,402.07 Signed 2020-12-21 2020-12-23 2020-12-23 2020-12-22 2021-01-01 2021-01-02 2021-12-31 Registry Assistant nt BA-FGA-211143-CS-CDS - A. Component A - Real Estate R 2.2.1A.49 / Temporary Land IBRD / 90480 egistration Data Developme Post Direct Selection Direct 7,463.40 17,257.12 Signed 2020-12-21 2020-12-23 2020-12-23 2020-12-22 2021-01-01 2021-01-02 2021-12-31 Registry Assistant nt BA-FGA-211144-CS-CDS - A. Component A - Real Estate R 2.2.1A.50 / Temporary Land IBRD / 90480 egistration Data Developme Post Direct Selection Direct 6,219.00 15,949.85 Signed 2020-12-21 2020-12-23 2020-12-23 2020-12-22 2021-01-01 2021-01-02 2021-07-31 Registry Assistant nt Page 5 BA-FGA-211149-CS-CDS-A.2. Component A - Real Estate R 2.1A.51 / Temporary Land Re IBRD / 90480 egistration Data Developme Post Direct Selection Direct 6,219.00 3,229.07 Terminated 2020-12-21 2020-12-23 2020-12-23 2020-12-22 2021-01-01 2021-01-02 2021-07-31 gistry Assistant nt BA-FGA-211150-CS-CDS - A. Component A - Real Estate R 2.2.1A.52 / Temporary Land IBRD / 90480 egistration Data Developme Post Direct Selection Direct 9,331.11 20,234.12 Signed 2020-12-21 2020-12-23 2020-12-23 2020-12-22 2021-01-01 2021-01-02 2021-12-31 Registry Assistant nt BA-FGA-211153-CS-CDS - A. Component A - Real Estate R 2.2.1A.53 / Temporary Land IBRD / 90480 egistration Data Developme Post Direct Selection Direct 9,331.11 7,215.37 Completed 2020-12-21 2020-12-23 2020-12-23 2020-12-22 2021-01-01 2021-01-02 2021-12-31 2022-01-01 Registry Assistant nt BA-FGA-211154-CS-CDS - A. Component A - Real Estate R 2.2.1A.54 / Temporary Land IBRD / 90480 egistration Data Developme Post Direct Selection Direct 6,226.46 25,448.70 Signed 2020-12-21 2020-12-23 2020-12-23 2020-12-22 2021-01-01 2021-01-02 2021-12-31 Registry Assistant nt BA-FGA-211155-CS-CDS - A. Component A - Real Estate R 2.2.1A.55 / Temporary Land IBRD / 90480 egistration Data Developme Post Direct Selection Direct 6,226.46 461.18 Completed 2020-12-21 2020-12-23 2020-12-23 2020-12-22 2021-01-01 2021-01-02 2021-12-31 2022-01-01 Registry Assistant nt BA-FGA-211157-CS-CDS-A.2. Component A - Real Estate R 2.1A.56 / Temporary Land Re IBRD / 90480 egistration Data Developme Post Direct Selection Direct 12,447.62 28,608.05 Signed 2020-12-21 2020-12-23 2020-12-23 2020-12-22 2021-01-01 2021-01-06 2021-12-31 gistry Assistant nt BA-FGA-211159-CS-CDS-A.2. Component A - Real Estate R 2.1A.57 / Temporary Land Re IBRD / 90480 egistration Data Developme Post Direct Selection Direct 3,110.76 13,638.84 Signed 2020-12-21 2020-12-23 2020-12-23 2020-12-22 2021-01-01 2021-01-02 2021-07-31 gistry Assistant nt BA-FGA-211161-CS-CDS-A.2. Component A - Real Estate R 2.1A.58 / Temporary Land Re IBRD / 90480 egistration Data Developme Post Direct Selection Direct 3,110.76 13,638.84 Signed 2020-12-21 2020-12-23 2020-12-23 2020-12-22 2021-01-01 2021-01-02 2021-07-31 gistry Assistant nt BA-FGA-211162-CS-CDS - A. Component A - Real Estate R 2.2.1A.59 / Temporary Land IBRD / 90480 egistration Data Developme Post Direct Selection Direct 3,110.76 2,058.14 Completed 2020-12-21 2020-12-23 2020-12-23 2020-12-22 2021-01-01 2021-01-02 2021-07-31 2022-01-01 Registry Assistant nt BA-FGA-211163-CS-CDS-A.2. Component A - Real Estate R 2.1A.60 / Temporary Land Re IBRD / 90480 egistration Data Developme Post Direct Selection Direct 3,110.76 13,638.84 Signed 2020-12-21 2020-12-23 2020-12-23 2020-12-22 2021-01-01 2021-01-02 2021-07-31 gistry Assistant nt BA-FGA-211168-CS-CDS-A.2. Component A - Real Estate R 2.1A.61 / Temporary Land Re IBRD / 90480 egistration Data Developme Post Direct Selection Direct 12,443.64 4,073.93 Terminated 2020-12-21 2020-12-23 2020-12-23 2020-12-22 2021-01-01 2021-01-02 2021-12-31 gistry Assistant nt BA-FGA-211169-CS-CDS-A.2. Component A - Real Estate R 2.1A.62 / Temporary Land Re IBRD / 90480 egistration Data Developme Post Direct Selection Direct 12,443.64 16,545.48 Terminated 2020-12-21 2020-12-23 2020-12-23 2020-12-22 2021-01-01 2021-01-02 2021-12-31 gistry Assistant nt BA-FGA-211170-CS-CDS-A.2. Component A - Real Estate R 2.1A.63 / Temporary Land Re IBRD / 90480 egistration Data Developme Post Direct Selection Direct 4,977.27 6,188.01 Signed 2020-12-21 2020-12-23 2020-12-23 2020-12-22 2021-01-01 2021-01-02 2021-07-31 gistry Assistant nt BA-FGA-211171-CS-CDS - A. Component A - Real Estate R 2.2.1A.64 / Temporary Land IBRD / 90480 egistration Data Developme Post Direct Selection Direct 4,977.27 5,385.81 Completed 2020-12-21 2020-12-23 2020-12-23 2020-12-22 2021-01-01 2021-01-02 2021-07-31 2022-03-01 Registry Assistant nt BA-FGA-211172-CS-CDS-A.2. Component A - Real Estate R 2.1A.65 / Temporary Land Re IBRD / 90480 egistration Data Developme Post Direct Selection Direct 3,112.47 4,945.11 Terminated 2020-12-21 2020-12-23 2020-12-23 2020-12-22 2021-01-01 2021-01-02 2021-07-31 gistry Assistant nt BA-FGA-211174-CS-CDS-A.2. Component A - Real Estate R 2.1A.66 / Temporary Land Re IBRD / 90480 egistration Data Developme Post Direct Selection Direct 6,223.89 1,557.36 Completed 2020-12-21 2020-12-23 2020-12-23 2020-12-22 2021-01-01 2021-01-02 2021-12-31 2022-01-01 gistry Assistant nt BA-FGA-211176-CS-CDS-A.2. Component A - Real Estate R 2.1A.67 / Temporary Land Re IBRD / 90480 egistration Data Developme Post Direct Selection Direct 6,223.89 17,104.50 Signed 2020-12-21 2020-12-23 2020-12-23 2020-12-22 2021-01-01 2021-01-02 2021-12-31 gistry Assistant nt BA-FGA-211178-CS-CDS-A.2. Component A - Real Estate R 2.1A.68 / Temporary Land Re IBRD / 90480 egistration Data Developme Post Direct Selection Direct 6,223.89 9,114.61 Terminated 2020-12-21 2020-12-23 2020-12-23 2020-12-22 2021-01-01 2021-01-02 2021-12-31 gistry Assistant nt BA-FGA-211180-CS-CDS-A.2. Component A - Real Estate R 2.1A.69 / Temporary Land Re IBRD / 90480 egistration Data Developme Post Direct Selection Direct 6,223.89 3,929.76 Terminated 2020-12-21 2020-12-23 2020-12-23 2020-12-22 2021-01-01 2021-01-02 2021-12-31 gistry Assistant nt BA-FGA-211181-CS-CDS-A.2. Component A - Real Estate R 2.1A.70 / Temporary Land Re IBRD / 90480 egistration Data Developme Post Direct Selection Direct 6,223.89 1,197.69 Terminated 2020-12-21 2020-12-23 2020-12-23 2020-12-22 2021-01-01 2021-01-02 2021-12-31 gistry Assistant nt BA-FGA-211559-CS-CDS-A.2. Component A - Real Estate R 2.2.4A.8 / Individual consulta IBRD / 90480 egistration Data Developme Post Direct Selection Direct 6,236.51 16,971.82 Signed 2020-12-24 2020-12-29 2020-12-28 2020-12-22 2021-01-01 2021-01-06 2021-07-31 nt for delivery of decisions on nt registration BA-FGA-211560-CS-CDS-A.2. Component A - Real Estate R 2.2.4A.9 / Individual consulta IBRD / 90480 egistration Data Developme Post Direct Selection Direct 6,236.51 8,603.56 Terminated 2020-12-24 2020-12-29 2020-12-28 2020-12-22 2021-01-01 2021-01-02 2021-07-31 nt for delivery of decisions on nt registration BA-FGA-211875-CS-CDS-A.2. Component A - Real Estate R 2.2.4A.10 / Individual consult IBRD / 90480 egistration Data Developme Post Direct Selection Direct 9,399.88 9,412.63 Signed 2020-12-29 2020-12-29 2020-12-30 2020-12-22 2021-01-01 2021-01-02 2021-12-31 ant for delivery of decisions o nt n registrations BA-FGA-212460-CS-INDV-B.1 Component B - Real Estate R Individual Consult IBRD / 90480 Post Limited 36,812.99 34,350.53 Signed 2021-01-06 2021-01-01 2021-01-18 2021-01-28 2021-02-01 2021-02-15 2021-02-18 2021-03-02 2022-07-31 .1.1 / Architect required for ci egistration Infrastructure De ant Selection vil works velopment BA-FGA-212495-CS-INDV-A.1 Component A - Real Estate R Individual Consult IBRD / 90480 Post Limited 44,629.61 2,735.74 Terminated 2021-01-06 2021-02-08 2021-01-28 2021-02-25 2021-02-12 2021-03-19 2021-04-01 2021-04-02 2022-07-31 .1.1B / Social Specialist egistration Data Developme ant Selection nt BA-FGA-212518-CS-INDV-B.2 .2.4 / Feasibility study of new Component B - Real Estate R Individual Consult system and software architec IBRD / 90480 egistration Infrastructure De Post Limited 61,354.98 0.00 Canceled 2021-01-06 2021-02-01 2021-02-21 2021-04-01 2021-09-28 ant Selection tures with tehnical specificati velopment ons in accordance with the IC T Strategy BA-FGA-212519-CS-INDV-B.2 Component B - Real Estate R Individual Consult .2.7 / Cyber security policy a IBRD / 90480 egistration Infrastructure De Post Limited 36,812.99 0.00 Canceled 2021-01-07 2021-03-04 2021-03-24 2021-05-03 2021-08-01 ant Selection nd action plan velopment Page 6 BA-FGA-212520-CS-INDV-C.3 Component C - Policy and in Individual Consult .2.3.1B / Interpreter - Phase IBRD / 90480 stitutional development, and Post Limited 6,614.06 6,344.84 Signed 2021-01-07 2021-01-01 2021-01-28 2021-02-25 2021-02-12 2021-03-30 2021-04-01 2021-04-02 2022-07-31 ant Selection 1 project management BA-FGA-211131-CS-CDS - A. Component A - Real Estate R 2.2.1A.41 / Temporary Land IBRD / 90480 egistration Data Developme Post Direct Selection Direct 11,177.80 0.00 Canceled 2020-12-21 2020-12-23 2020-12-23 2020-12-30 2021-01-01 2021-12-31 Registry Assistant nt BA-FGA-210788-CS-CDS - A. Component A - Real Estate R 2.2.1A.20 / Temporary Land IBRD / 90480 egistration Data Developme Post Direct Selection Direct 3,131.80 0.00 Canceled 2020-12-18 2020-12-23 2020-12-22 2020-12-30 2021-01-01 2021-07-31 Registry Assistant nt BA-FGA-210782-CS-CDS-A.2. Component A - Real Estate R 2.1A.17 / Temporary Land Re IBRD / 90480 egistration Data Developme Post Direct Selection Direct 6,262.97 0.00 Canceled 2020-12-18 2020-12-23 2020-12-22 2020-12-30 2021-01-01 2021-12-31 gistry Assistant nt BA-FGA-218523-CS-INDV-A.4 Component A - Real Estate R .1.1 / Project managers for H Individual Consult IBRD / 90480 egistration Data Developme Post Open 60,634.98 57,119.63 Completed 2021-02-11 2021-02-24 2021-03-14 2021-04-12 2021-03-17 2021-04-21 2021-04-21 2021-04-22 2021-11-17 2021-12-02 armonization data on cadastr ant Selection nt e and land book - Phase 1 BA-FGA-212498-CS-INDV-A.4 Component A - Real Estate R .1.1 / Project managers for H Individual Consult IBRD / 90480 egistration Data Developme Post Limited 61,354.98 0.00 Canceled 2021-01-06 2021-01-05 2021-02-05 2021-02-20 2021-03-28 2021-10-24 armonization data on cadastr ant Selection nt e and land book - Phase 1 BA-FGA-218764-CS-INDV-A.2 Component A - Real Estate R .2.1B / Updating (establishm Individual Consult IBRD / 90480 egistration Data Developme Post Open 78,907.66 89,945.92 Signed 2021-02-12 2021-04-22 2021-03-15 2021-04-15 2021-03-18 2021-04-22 2021-04-01 2021-05-24 2021-12-31 2022-01-05 ent and/or renewal) of land r ant Selection nt egister data - Temp LR Assist ants BA-FGA-219067-CS-INDV-B.2 Component B - Real Estate R Individual Consult .1.2 / Technical Assistance fo IBRD / 90480 egistration Infrastructure De Post Limited 23,322.24 33,495.05 Signed 2021-02-11 2021-02-24 2021-02-17 2021-02-25 2021-03-04 2021-03-30 2021-04-01 2021-04-03 2022-07-31 ant Selection r QA/QC, ICT Strategy update velopment , others BA-FGA-219075-CS-INDV-B.3 Component B - Real Estate R Individual Consult .1 / Scanning, data entry and IBRD / 90480 egistration Infrastructure De Post Limited 52,083.65 47,342.43 Signed 2021-02-11 2021-04-22 2021-02-24 2021-03-24 2021-03-15 2021-05-14 2021-05-01 2021-05-21 2021-12-31 2022-01-01 ant Selection indexing of LB arhives docum velopment entation BA-FGA-219077-CS-INDV-A.4 Component A - Real Estate R Individual Consult IBRD / 90480 Post Limited 23,322.24 22,570.02 Signed 2021-02-11 2021-02-19 2021-02-19 2021-02-25 2021-03-06 2021-03-30 2021-04-01 2021-04-03 2022-07-31 .2 / Quality Control - RECDB egistration Data Developme ant Selection nt BA-FGA-219088-CS-INDV-C.3 Component C - Policy and in Individual Consult .2.1B.2 / Monitoring and Eval IBRD / 90480 stitutional development, and Post Limited 30,953.61 0.00 Canceled 2021-02-11 2021-03-09 2021-03-01 2021-03-16 2021-04-01 2022-07-31 ant Selection uation Specialist project management Component C - Policy and in BA-FGA-219100-CS-INDV-C.3 Individual Consult IBRD / 90480 stitutional development, and Post Limited 37,144.34 0.00 Canceled 2021-02-11 2021-02-28 2021-03-15 2021-04-01 2022-07-31 .2.1B.5 / Finance consultant ant Selection project management BA-FGA-219308-CS-INDV-A.2 Component A - Real Estate R Individual Consult .2.2.4B / Delivery cost of De IBRD / 90480 egistration Data Developme Post Limited 19,874.12 27,028.11 Signed 2021-02-12 2021-03-09 2021-02-19 2021-03-10 2021-03-06 2021-04-12 2021-04-01 2021-04-19 2021-12-31 ant Selection cisions on registrations nt Component C - Policy and in BA-FGA-219315-CS-INDV-C.3 Individual Consult IBRD / 90480 stitutional development, and Post Limited 52,621.15 84,509.54 Signed 2021-02-15 2021-03-09 2021-02-28 2021-03-11 2021-03-15 2021-03-30 2021-04-01 2021-04-02 2022-07-31 .2.1B.1 / Team Leader ant Selection project management BA-FGA-212511-CS-INDV-B.2 Component B - Real Estate R Individual Consult .1.1B / Technical ICT Assistan IBRD / 90480 egistration Infrastructure De Post Limited 56,017.10 0.00 Canceled 2021-01-06 2021-01-01 2021-01-28 2021-02-12 2021-04-01 2022-07-31 ant Selection ce for project activities velopment BA-FGA-224275-CS-INDV-B.2 .2.4 / Feasibility study of new Component B - Real Estate R Individual Consult system and software architec IBRD / 90480 egistration Infrastructure De Post Open 59,460.00 50,939.42 Signed 2021-03-11 2021-04-05 2021-03-28 2021-05-26 2021-03-28 2021-07-07 2021-04-01 2021-07-16 2021-09-28 ant Selection tures with tehnical specificati velopment ons in accordance with the IC T Strategy BA-FGA-227676-CS-INDV-C.3 Component C - Policy and in Individual Consult .2.2.5 / Project Controls and IBRD / 90480 stitutional development, and Post Limited 25,795.00 44,084.83 Signed 2021-04-01 2021-04-06 2021-04-01 2021-04-09 2021-04-16 2021-04-12 2021-04-17 2021-04-20 2022-07-31 ant Selection QAQC project management BA-FGA-233043-CS-INDV-A.2 Component A - Real Estate R Individual Consult .2.2.4B.VIS1 / Delivery cost o IBRD / 90480 egistration Data Developme Post Limited 3,706.45 3,718.42 Signed 2021-05-04 2021-05-05 2021-05-11 2021-04-30 2021-05-13 2021-05-17 2021-05-20 2021-06-02 2021-12-31 ant Selection f Decisions on registrations nt - A.2.2.2.4B.VIS1 BA-FGA-235303-CS-INDV-A.2 Component A - Real Estate R .2.1B / Updating (establishm Individual Consult IBRD / 90480 egistration Data Developme Post Open 46,867.55 67,551.96 Signed 2021-05-20 2021-05-21 2021-07-13 2021-07-09 2021-07-15 2021-07-12 2021-08-01 2021-10-05 2022-07-31 ent and/or renewal) of land r ant Selection nt egister data - Temp LR Assist ants BA-FGA-236315-CS-INDV-A.1 Component A - Real Estate R Individual Consult IBRD / 90480 Post Limited 25,718.04 41,736.01 Signed 2021-05-25 2021-05-27 2021-05-28 2021-06-01 2021-06-11 2021-06-10 2021-06-15 2021-06-16 2022-07-31 .1.1C / Social Specialist egistration Data Developme ant Selection nt BA-FGA-243298-CS-INDV-A.2 Component A - Real Estate R .2.1B / Updating (establishm Individual Consult IBRD / 90480 egistration Data Developme Post Open 76,353.87 143,053.63 Signed 2021-07-13 2021-07-14 2021-08-26 2021-10-14 2021-09-08 2021-10-12 2021-10-01 2021-11-16 2022-07-31 ent and/or renewal) of land r ant Selection nt egister data - Temp LR Assist ants BA-FGA-224273-CS-INDV-B.2 Component B - Real Estate R Individual Consult .2.7 / Cyber security policy a IBRD / 90480 egistration Infrastructure De Post Open 35,676.00 0.00 Canceled 2021-03-11 2021-04-05 2021-04-02 2021-04-06 2021-05-03 2021-08-01 ant Selection nd action plan velopment BA-FGA-250497-CS-INDV - B. Component B - Real Estate R 3.1. / Scanning, data entry a Individual Consult IBRD / 90480 egistration Infrastructure De Post Limited 1,800.15 6,967.24 Signed 2021-08-26 2021-10-28 2021-08-27 2021-09-02 2021-09-11 2021-10-15 2021-10-01 2021-10-19 2021-12-31 nd indexing of LB arhives doc ant Selection velopment umentation - B.3.1. BA-FGA-255488-CS-INDV - A. Component A - Real Estate R Individual Consult 2.2.2.4B / Delivery cost of D IBRD / 90480 egistration Data Developme Post Limited 3,582.51 8,068.49 Signed 2021-09-29 2021-09-30 2021-10-04 2021-10-01 2021-10-19 2021-11-22 2021-11-01 2021-11-28 2022-07-31 ant Selection ecisions on registrations - A.2 nt .2.2.4b BA-FGA-257111-CS-INDV - A. Component A - Real Estate R 2.2.1B/4 / Updating (establis Individual Consult IBRD / 90480 egistration Data Developme Post Open 33,047.45 0.00 Canceled 2021-10-07 2021-11-05 2021-11-10 2021-12-01 2022-07-31 hment and/or renewal) of lan ant Selection nt d register data - Temp LR Ass istants - A.2.2.1B/4 BA-FGA-257687-CS-INDV-A.2 Component A - Real Estate R .2.1B/4 / Updating (establish Individual Consult IBRD / 90480 egistration Data Developme Post Open 46,138.06 65,187.85 Signed 2021-10-11 2021-10-12 2021-11-09 2021-12-07 2021-11-11 2021-12-01 2021-12-01 2022-01-11 2022-07-31 ment and/or renewal) of land ant Selection nt register data - Temp LR Assis tants - A.2.2.1B Page 7 BA-FGA-260873-CS-INDV-A.2 Component A - Real Estate R .2.1B/5 / Updating (establish Individual Consult IBRD / 90480 egistration Data Developme Post Open 8,335.59 12,949.16 Signed 2021-11-01 2021-11-02 2021-12-01 2021-12-08 2021-12-03 2021-12-17 2021-12-15 2021-12-21 2022-07-31 ment and/or renewal) of land ant Selection nt register data - Temp LR Assis tants - A.2.2.1B BA-FGA-261517-CS-CDS-C.2. 3.1.1A.1 / Real estate registr ation institutions/Land Regist Component C - Policy and in ry,Cadastre offices, Spatial pl IBRD / 90480 stitutional development, and Post Direct Selection Direct 4,283.86 4,172.49 Signed 2021-11-04 2021-11-10 2021-11-08 2021-11-11 2021-11-19 2021-11-30 2021-12-19 anning for 2021 - C.2.3.1.1a project management DATA MANIPULATION (advan ced Safe software FME traini ng by licensed distribution C ompany) BA-FGA-261524-CS-CDS-C.2. 3.1.1A.2 / Real estate registr ation institutions/Land Regist ry,Cadastre offices, Spatial pl Component C - Policy and in anning for 2021 - C.2.3.1.1A. IBRD / 90480 stitutional development, and Post Direct Selection Direct 5,789.00 5,394.98 Signed 2021-11-04 2021-11-10 2021-11-08 2021-11-11 2021-11-19 2021-12-01 2021-12-19 SERVING GEOGRAPHIC DATA project management ON THE WEB (advanced ESRI ArcGIS Enterprise training by licensed distribution Compan y) BA-FGA-261526-CS-CDS-C.2. 3.1.1A.3 / Real estate registr ation institutions/Land Regist Component C - Policy and in ry,Cadastre offices, Spatial pl Pending Impleme IBRD / 90480 stitutional development, and Post Direct Selection Direct 11,578.00 0.00 2021-11-04 2021-11-08 2021-11-19 2021-12-19 anning for 2021 - C.2.3.1.1a ntation project management SERVING GEOGRAPHIC DATA ON THE WEB (advanced Geo Server training) BA-FGA-261530-CS-INDV-C.2 .3.1.1A.4 / Real estate registr ation institutions/Land Regist Component C - Policy and in ry,Cadastre offices, Spatial pl Individual Consult IBRD / 90480 stitutional development, and Post Limited 1,505.14 0.00 Canceled 2021-11-04 2021-11-08 2021-11-05 2021-11-15 2021-11-19 2021-12-19 anning for 2021 - C.2.3.1.1A ant Selection project management SPATIAL DATABASES (Spatial databases – PostgreSQL/Post GIS and Oracle training by IC ) BA-FGA-276127-CS-INDV-B.3 Component B - Real Estate R .1. / Scanning, data entry an Individual Consult IBRD / 90480 egistration Infrastructure De Post Limited 5,133.57 5,047.98 Signed 2022-02-01 2022-02-01 2022-02-03 2022-02-03 2022-02-10 2022-03-04 2022-02-15 2022-03-08 2022-07-31 d indexing of LB arhives docu ant Selection velopment mentation - B.3.1. BA-FGA-282727-CS-INDV-A.4 Component A - Real Estate R .1.2. / Project managers for H Individual Consult IBRD / 90480 egistration Data Developme Post Open 65,574.00 33,519.22 Signed 2022-03-07 2022-03-08 2022-04-10 2022-05-17 2022-04-13 2022-05-18 2022-05-17 2022-06-02 2022-11-27 armonization data on cadastr ant Selection nt e and land book - Phase 2 BA-FGA-286813-CS-INDV-A.2 Component A - Real Estate R .2.1B/6 / Updating (establish Individual Consult IBRD / 90480 egistration Data Developme Post Open 28,064.81 0.00 Signed 2022-03-25 2022-03-28 2022-05-04 2022-05-09 2022-05-10 2022-06-13 2022-05-31 2024-07-31 ment and/or renewal) of land ant Selection nt register data - Temp LR Assis tants BA-FGA-287171-CS-INDV-C.2 Component C - Policy and in .3.1.2A / Real estate registrat Individual Consult IBRD / 90480 stitutional development, and Post Limited 1,740.16 1,704.69 Signed 2022-03-29 2022-03-31 2022-04-01 2022-04-07 2022-04-18 2022-04-20 2022-04-25 2022-04-22 2022-08-25 ion institutions/Land Registry ant Selection project management ,Cadastre offices, Spatial pla nning - 2022 BA-FGA-295155-CS-INDV-A.2 Component A - Real Estate R .2.1B-7 / Updating (establish Individual Consult IBRD / 90480 egistration Data Developme Post Open 23,414.72 0.00 Signed 2022-05-13 2022-05-20 2022-06-22 2022-07-13 2022-06-28 2022-08-31 2022-07-19 2024-07-31 ment and/or renewal) of land ant Selection nt register data - Temp LR Assis tants BA-FGA-296883-CS-INDV-A.4 Component A - Real Estate R .1.2-2 / Project managers for Individual Consult IBRD / 90480 egistration Data Developme Post Open 24,919.40 24,454.46 Signed 2022-05-25 2022-05-25 2022-06-27 2022-06-22 2022-06-28 2022-06-23 2022-07-08 2022-07-11 2023-02-18 Harmonization data on cadas ant Selection nt tre and land book - Phase 2 - 2 BA-FGA-322367-CS-INDV-A.2 .2.1.B-8 / Updating (establish Component A - Real Estate R Individual Consult ment and/or renewal) of land IBRD / 90480 egistration Data Developme Post Open - National 104,011.08 0.00 Signed 2022-10-20 2022-10-20 2022-11-15 2023-01-25 2022-11-22 2023-02-20 2022-12-01 2024-07-31 ant Selection register data - Temp LR Assis nt tants (DS, limited and open p rocedure) BA-FGA-325445-CS-INDV-C.2 .3.1.2A / Real estate registrat Component C - Policy and in Direct - Internation ion institutions/Land Registry IBRD / 90480 stitutional development, and Post Direct Selection 2,468.00 0.00 Signed 2022-11-15 2022-11-22 2022-11-17 2022-11-24 2022-12-01 2022-12-31 al ,Cadastre offices, Spatial pla project management nning - 2022-C.2.3.1.2A BA-FGA-330906-CS-INDV-A.2 .2.1B/9 / Updating (establish Component A - Real Estate R Individual Consult Under Implement ment and/or renewal) of land IBRD / 90480 egistration Data Developme Post Open - National 74,494.54 0.00 2022-12-12 2022-12-20 2023-01-16 2023-01-31 2023-01-24 2023-02-13 2023-02-01 2024-07-31 ant Selection ation register data - Temp LR Assis nt tants (DS, limited and open p rocedure) BA-FGA-347654-CS-INDV-C.3 Component C - Policy and in Individual Consult .2.1. / C.3.2.1.-PIU Staff - Ad IBRD / 90480 stitutional development, and Post Open - National 19,217.63 0.00 Signed 2023-03-07 2023-03-06 2023-03-27 2023-03-24 2023-03-28 2023-03-31 2023-04-01 2024-07-31 ant Selection ministrative Assistant project management BA-FGA-347658-CS-INDV-B.2 Component C - Policy and in Individual Consult Under Implement .2.6. / B.2.2.6. Development IBRD / 90480 stitutional development, and Post Open - National 85,398.33 0.00 2023-03-07 2023-02-16 2023-03-14 2023-03-14 2023-03-16 2023-03-22 2023-09-27 ant Selection ation and specification of integrate project management d Data Model BA-FGA-358030-CS-INDV-C.3 Component C - Policy and in Individual Consult Under Implement .2.1. / C.3.2.1. - PIU Staff - Pr IBRD / 90480 stitutional development, and Post Limited 26,777.50 0.00 2023-04-21 2021-01-07 2023-05-04 2023-05-19 2023-06-05 2024-07-31 ant Selection ation ocurement Specialist project management BA-FGA-366258-CS-INDV-23- C.2.3.1.3A / Real estate regis Component C - Policy and in Direct - Internation Pending Impleme tration institutions/Land Regi IBRD / 90480 stitutional development, and Post Direct Selection 1,500.00 0.00 2023-06-09 2023-06-19 2023-08-28 2024-02-24 al ntation stry,Cadastre offices, Spatial project management planning - 2023 - C.2.3.1.3a Page 8 Procurement Plan I. General 1. Bank’s approval Date of the procurement Plan: Mar 2018 2. Date of General Procurement Notice: not as yet 3. Period covered by this procurement plan: The procurement period for the PPF II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank 2. Procurement Method Prior Review Comments Threshold US$ 1. Goods and Non-Consultant US$ 1.5 million All Services 2. Works NCB (Goods) US$ 5 million All 2. Prequalification. Bidders for _ _ shall be prequalified N/A 3. Reference to (if any) Project Operational/Procurement Manual: Procurement Manual will be developed. 4. Any Other Special Procurement Arrangements: Not Applicable 5. Summary of the Procurement Packages planned during the first 18 months after project effectiveness ( including those that are subject to retroactive financing and advanced procurement) Some small goods and works could be undertaken, which are not identified as yet. III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Comments Threshold 1. Competitive Methods (Firms) Above US$ 0.5 m 3. Individual Above US$ 200, 000 Aug 8, 2017 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_500,000_equivalent per contract, may comprise entirely of national consultants in accordance with the OPCS guidance. 3. Any Other Special Selection Arrangements: [including advance procurement and retroactive financing, if applicable or delete if not applicable] 4. Consultancy Assignments with Selection Methods S Contract title Estimat Bank Procurem Selection Evaluati N ed cost oversi ent method on US $ ght approach method and risk rating 1 Project 10,000,0 Prior Internation QCBS Rated Implementation 00 al criteria Consultants High PPF pays about US $ 2m for design Remaini ng 8 m is from the main project 2 Environment and 450,000 Post National CQS Negotiat Social ed cost High Consultants - ESIA and RAP for Panjkora HPP sites, CIA of Swat River Basin, ESMF and Resettlement Framework Aug 8, 2017 3 Power 400,000 Post National CQS Negotiat Evacuation and ed cost Dispersal of Swat High Cascade 4 a. Gabral-Kalam 1m Prior Internation QCBS Rated additional each al criteria studies (if needed) Substant ial b. Independent review of ESIA of Gabral- Kalam 5 goods/equipmen 300,000 Post National Shopping/N Lowest t including two CB evaluate 4x4 to support Substant d cost project ial (shall be preparation detailed) 6 Independent 150,000 Post Internation Competitive Negotiat Panel of Experts al/ ed cost - 7 members 20 National days on average per year each incl travel 7 5-6 Individual 300,000 Post National Competitive Negotiat Consultants/Advi /prior (shall be ed cost sors (Contracts, detailed) Financial Advisor, Env & Social, Competitive Bidding, Technical) 50-75 days each Aug 8, 2017 PROCUREMENT Pakistan : Khyber Pakhtunkhwa Hydropower and Renewable Energy Development PLAN General Information Country: Pakistan 2019-04-04 Bank’s Approval Date of the Original Procurement Plan: 2023-06-01 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P163461 GPN Date: 2020-12-21 Project Name: Khyber Pakhtunkhwa Hydropower and Renewable Energy Development Loan / Credit No: IBRD / 91640, IDA / V1780, IDA / 67790 Pakhtunkhwa Energy Development Organization Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned PK-PEDO-211744-CW-RFB / Gabral Kalam Hydropower Pr Development of Hydropower oject : Open - Internationa Single Stage - One E 125,000,000. 2026-11-0 IBRD / 91640 and Renewable Energy Inves Prior Request for Bids 0.00 Canceled 2021-01-20 2021-02-05 2021-05-17 2022-09-28 2021-05-27 2022-10-28 2021-03-06 2021-03-31 2021-08-05 2022-12-19 2021-09-04 2023-02-16 2021-10-09 Package 1: Civil Works - wate l nvelope 00 2 tments r conveyance structure (weir, diversion structure, tunnels, etc.), access roads, and bridg es. PK-PEDO-211748-CW-RFB / Gabral Kalam Hydropower Pr Development of Hydropower oject: Open - Internationa Single Stage - One E 50,000,000.0 Under Revie 2026-11-0 IBRD / 91640 and Renewable Energy Inves Prior Request for Bids 0.00 2021-01-20 2021-02-03 2021-05-17 2022-09-29 2021-05-27 2022-12-13 2021-03-06 2021-03-31 2021-08-05 2023-05-03 2021-09-04 2021-10-09 Package 2: Power House (Su l nvelope 0 w 2 tments pply & Install) - civil structure ; turbines, generators, electri cal system, switchyard, powe r evacuation PK-PEDO-211751-CW-RFB / Development of Hydropower Gabral Kalam Hydropower Pr Single Stage - One E 2024-12-0 IBRD / 91640 and Renewable Energy Inves Post Request for Bids Open - National 5,000,000.00 0.00 Signed 2021-01-30 2022-05-20 2021-03-16 2022-05-31 2021-04-27 2022-07-05 2021-05-27 2022-07-05 2021-07-01 oject: nvelope 2 tments Package 3: Residential colon y, offices, and roads PK-PEDO-279716-CW-RFQ / Institutional Strengthening a Request for Quota Repair & Renovation Works f Request for Quota Single Stage - One E Pending Imp 2022-10-2 IDA / 67790 nd Energy Sector Developm Post Limited tions (Non Bank-S 23,000.00 0.00 2022-03-05 2022-04-30 or PMO office, E&P office and tions nvelope lementation 7 ent PD) Site office GKHPP - KHRE PK-PEDO-339715-CW-RFB / Madyan HPP Civil Works: All Civil Structures including Wei Development of Hydropower Request for Bids - Open - Internationa Single Stage - One E 300,000,000. Under Imple 2027-11-3 r, Intake, Tunnel, Tail Race, P IBRD / 91640 and Renewable Energy Inves Prior Request for Bids Works SPD (after 0.00 2023-02-15 2023-03-07 2023-05-16 2023-05-31 2023-03-02 2023-03-27 2023-07-15 2023-08-29 2023-10-03 l nvelope 00 mentation 0 ower House Building, Colony, tments prequalification) Roads, Bridges, Water Treat ment Plant and Hydraulic Ste el Structures. PK-PEDO-339716-CW-RFB / Madyan HPP E&M Works: Sup ply, Installation, Testing & Co mmissioning of Turbines, Ge Development of Hydropower Request for Bids - Open - Internationa Single Stage - One E 100,000,000. Under Imple 2027-12-1 nerators, Control Room Equip IBRD / 91640 and Renewable Energy Inves Prior Request for Bids Works SPD (after 0.00 2023-02-15 2023-03-09 2023-05-31 2023-06-15 2023-03-02 2023-03-29 2023-07-30 2023-08-29 2023-10-03 l nvelope 00 mentation 5 ment, SCADA, Auxiliaries, Po tments prequalification) wer Transformers, Switch Yar d, Switch Gear (GIS), Transmi ssion Line, Control equipmen t at Weir and allied E&M work s PK-PEDO-344261-CW-RFB / Gabral Kalam Hydropower Pr Request for Bids - Development of Hydropower oject: Package-1, Civil Works Open - Internationa Single Stage - One E Works (without pr 150,000,000. Under Imple 2027-07-2 IBRD / 91640 and Renewable Energy Inves Prior Request for Bids 0.00 2023-03-15 2023-05-26 2023-03-20 2023-06-02 2023-05-04 2023-06-18 2023-07-23 - water conveyance structure l nvelope equalification) SP 00 mentation 2 tments (weir, diversion structure, tu D nnels, etc.), access roads an d bridges. GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PK-PEDO-248543-GO-RFQ / I T hardware is required to be i nstalled, configured, and co Institutional Strengthening a Single Stage - One E Under Imple mmissioned in the Committe IDA / 67790 nd Energy Sector Developm Post Request for Bids Open - National 191,000.00 0.00 2021-12-28 2022-01-06 2022-01-02 2022-02-13 2022-03-15 2022-04-19 2022-07-18 nvelope mentation e Rooms, (PEDO House Pesh ent awar, Energy & Power Depart ment, Civil Secretariat, and P MO KHRE Office, Peshawar. PK-PEDO-276438-GO-RFQ / S Development of Hydropower upply of Goods with services Request for Quota Single Stage - One E IDA / 67790 and Renewable Energy Inves Post Limited 95,000.00 0.00 Canceled 2022-02-26 2022-04-23 2022-10-20 for Office Renovation (PMO, E tions nvelope tments &P and 88MW-GKHPP Site off ice) - KHRE PK-PEDO-279713-GO-RFQ / P Institutional Strengthening a Request for Quota Single Stage - One E Pending Impl urchase of IT Equipment/Har IDA / 67790 nd Energy Sector Developm Post Limited 18,550.00 0.00 2022-03-05 2022-04-30 2022-10-27 tions nvelope ementation dware (Goods) for 88MW-GK ent HPP, KHRE PK-PEDO-279714-GO-RFQ / P Institutional Strengthening a urchase of Electrical Applianc Request for Quota Single Stage - One E Pending Impl IDA / 67790 nd Energy Sector Developm Post Limited 10,650.00 0.00 2022-03-05 2022-04-30 2022-10-27 es (Goods) for PMO office, E& tions nvelope ementation ent P office and Site office GKHP P - KHRE PK-PEDO-279715-GO-RFQ / P Institutional Strengthening a urchase of Office Furniture ( Request for Quota Single Stage - One E Pending Impl IDA / 67790 nd Energy Sector Developm Post Limited 47,650.00 0.00 2022-03-05 2022-04-30 2022-10-27 Goods) for PMO office, E&P of tions nvelope ementation ent fice and Site office GKHPP - K HRE NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Page 1 Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PK-PEDO-107050-CS-QCBS / Development of Hydropower Quality And Cost- Open - Internationa Project Implementation Cons IBRD / 91640 and Renewable Energy Inves Prior 10,000,000.00 11,665,401.74 Signed 2019-04-15 2019-04-11 2019-05-16 2019-04-15 2019-06-29 2022-02-07 2019-07-27 2021-05-05 2019-08-26 2022-04-05 2019-09-30 2022-04-28 2019-11-04 2021-11-30 2020-11-03 Based Selection l ultants (PICs) tments PK-PEDO-144022-CS-QCBS / MANAGEMENT SUPPORT CON Development of Hydropower SULTANTS(MSCS) - Quality And Cost- Open - Internationa Under Implement IDA / V1780 and Renewable Energy Inves Prior 6,000,000.00 0.00 2019-11-12 2019-11-12 2019-12-12 2019-11-15 2020-02-16 2021-09-09 2020-03-15 2022-01-14 2020-04-14 2022-08-02 2020-05-19 2020-06-23 2026-06-23 KHYBER PAKHTUNKHWA HYD Based Selection l ation tments ROPOWER DEVELOPMENT PR OGRAM (KPHDP) PK-PEDO-144028-CS-QCBS / PLANNING CONSULTANT - CO NSULTING SERVICES FOR DE VELOPMENT OF COMPREHEN Development of Hydropower Quality And Cost- Open - Internationa SIVE PLAN FOR HYDROPOWE IDA / V1780 and Renewable Energy Inves Prior 20,000,000.00 0.00 Canceled 2019-11-12 2019-11-13 2019-12-12 2019-11-15 2020-02-16 2020-03-15 2020-04-14 2020-05-19 2020-06-23 2026-06-23 Based Selection l R AND ENERGY SYSTEMS IN tments KHYBER PAKHTUNKHWA - UN DER KHYBER PAKHTUNKHWA HYDROPOWER DEVELOPMEN T PROGRAM (KPHDP) PK-PEDO-238876-CS-QCBS / PLANNING CONSULTANT - CO NSULTING SERVICES FOR DE VELOPMENT OF COMPREHEN Development of Hydropower SIVE PLAN FOR HYDROPOWE Quality And Cost- Open - Internationa IDA / 67790 and Renewable Energy Inves Prior 16,000,000.00 0.00 Signed 2021-06-21 2021-06-21 2021-07-12 2021-06-23 2021-08-25 2021-07-29 2021-09-22 2021-11-30 2021-10-22 2022-03-22 2021-11-26 2022-12-13 2021-12-31 2023-04-15 2027-06-23 R AND RENEWABLE ENERGY Based Selection l tments SYSTEMS IN KHYBER PAKHTU NKHWA - UNDER KHYBER PA KHTUNKHWA HYDROPOWER AND RENEWABLE ENERGY D EVELOPMENT (KHRE) INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PK-PEDO-113884-CS-INDV / Individual Consult Under Implement Environment Social Impact A IDA / V1780 Post Limited 125,000.00 0.00 2019-07-24 2019-06-13 2019-07-29 2019-08-19 2019-09-16 2020-09-15 ant Selection ation ssessment Consultant PK-PEDO-113892-CS-INDV / Individual Consult Under Implement IDA / V1780 Post Limited 125,000.00 0.00 2019-07-24 2019-06-17 2019-07-29 2019-08-19 2019-09-16 2020-09-15 Resettlement Action Plan Co ant Selection ation nsultant PK-PEDO-113907-CS-INDV / I Development of Hydropower Individual Consult POE member for Dam, Tunne IDA / V1780 and Renewable Energy Inves Post Limited 150,000.00 150,000.00 Signed 2019-11-08 2021-12-30 2019-11-13 2021-12-30 2019-12-04 2021-12-31 2020-01-08 2022-01-16 2022-01-07 ant Selection l and Geology tments PK-PEDO-180925-CS-INDV / Development of Hydropower Individual Consult Pending Impleme IDA / V1780 Post Limited 20,000.00 0.00 2020-06-26 2020-07-01 2020-07-17 2020-08-07 2021-02-03 Tariff Consultant and Renewable Energy Inves ant Selection ntation tments PK-PEDO-220908-CS-INDV / PMO – Financial Management Project Implementation Sup Specialist’ to manage the fin Individual Consult Pending Impleme IDA / 67790 port and Technical Assistanc Post Limited 15,000.00 0.00 2021-03-10 2021-03-28 2021-04-07 2021-04-18 2021-10-15 ancial management matters ant Selection ntation e of the Khyber Pakhtunkhwa Hydropower and Renewable Energy Development Progra m. PK-PEDO-222667-CS-INDV / Project Implementation Sup Individual Consult Pending Impleme Technical Expert - Colony an IDA / 67790 port and Technical Assistanc Post Limited 15,000.00 0.00 2021-03-10 2021-03-25 2021-04-04 2021-05-09 2021-11-05 ant Selection ntation d Small Works e PK-PEDO-244291-CS-INDV / Land Purchase Expert for De aling with the purchase of la Development of Hydropower Individual Consult nd from farmers and various IDA / 67790 and Renewable Energy Inves Post Limited 9,000.00 18,000.00 Signed 2021-07-30 2021-08-02 2021-08-04 2021-07-26 2021-08-25 2021-08-02 2021-09-29 2021-08-03 2022-03-28 ant Selection communities and governmen tments t departments for World Ban k projects namely Gabral Kal am HPP and Madyan HPP. PK-PEDO-264014-CS-INDV / I nternational Procurement Sp ecialist to be hired to assist K Development of Hydropower Individual Consult HRE PMO in the procurement IDA / 67790 and Renewable Energy Inves Post Limited 60,000.00 85,888.00 Signed 2021-12-15 2021-12-14 2021-12-20 2021-12-14 2022-01-10 2021-12-14 2022-02-14 2021-12-22 2022-08-13 ant Selection process. This Specialist is m tments ainly required because there are many parallel urgent pro curement activities under pro cess. PK-PEDO-264016-CS-INDV / I Development of Hydropower Individual Consult ndependent Panel of Expert ( IDA / 67790 and Renewable Energy Inves Post Limited 125,000.00 78,507.00 Signed 2021-12-15 2021-12-14 2021-12-20 2021-12-14 2022-01-10 2022-01-02 2022-02-14 2022-01-16 2024-02-14 ant Selection IPOE) Member Electrical tments PK-PEDO-264635-CS-INDV / I Institutional Strengthening a Individual Consult Under Implement ndependent Panel of Expert ( IDA / 67790 nd Energy Sector Developm Post Limited 125,000.00 0.00 2021-12-15 2021-12-28 2021-12-20 2021-12-28 2022-01-10 2022-01-02 2022-02-14 2024-02-14 ant Selection ation IPOE) Member Mechanical, K ent HRE PK-PEDO-113902-CS-INDV / I Development of Hydropower Individual Consult POE member for Hydrology, IDA / V1780 and Renewable Energy Inves Post Limited 55,000.00 14,973.93 Signed 2022-01-19 2021-12-28 2022-01-19 2021-12-28 2022-01-19 2021-12-28 2022-01-19 2022-01-16 2024-01-19 ant Selection Hydraulic Structures, Sedime tments nts and GLOF PK-PEDO-113895-CS-INDV / I Development of Hydropower Individual Consult IDA / V1780 Post Limited 130,000.00 130,000.00 Signed 2022-01-20 2021-12-28 2022-01-20 2021-12-28 2022-01-20 2021-12-28 2022-01-20 2022-01-16 2024-01-20 POE Member for Environment and Renewable Energy Inves ant Selection and OHS tments PK-PEDO-113927-CS-INDV / I Development of Hydropower Individual Consult POE Member for Social and R IDA / V1780 and Renewable Energy Inves Post Limited 125,000.00 125,000.00 Signed 2019-11-08 2021-12-28 2019-11-13 2021-12-28 2019-12-04 2021-12-28 2020-01-08 2022-01-16 2022-01-07 ant Selection esettlement tments PK-PEDO-113923-CS-INDV / I Development of Hydropower Individual Consult POE member for Constructio IDA / V1780 and Renewable Energy Inves Post Limited 55,000.00 55,000.00 Signed 2019-07-25 2022-01-28 2019-07-30 2021-12-28 2019-08-20 2021-12-28 2019-09-24 2022-01-16 2021-09-23 ant Selection n Planning and Contract ma tments nagement PK-PEDO-276297-CS-INDV / Development of Hydropower Individual Consult Pending Impleme Lead Technical Specialist / C IDA / 67790 and Renewable Energy Inves Post Limited 50,000.00 0.00 2022-02-10 2022-02-15 2022-03-08 2022-04-12 2023-04-12 ant Selection ntation oordinator, 88MW-GKHPP, PM tments O KHRE PK-PEDO-363678-CS-INDV / Development of Hydropower Individual Consult Pending Impleme IDA / 67790 Post Limited 50,000.00 0.00 2023-05-27 2023-06-01 2023-06-22 2023-07-27 2025-07-26 Regulatory Affairs Expert and Renewable Energy Inves ant Selection ntation tments Page 2 Page 3 PROCUREMENT PLAN (Textual Part) Project information: Jiangxi Integrated Rural And Urban Water Supply And Wastewater Management Project Project Implementation agency: Jiangxi Integrated Rural And Urban Water Supply And Wastewater Management Project Management Office Date of the Procurement Plan: Sept. 2019 Period covered by this Procurement Plan: 24 months Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016, Revised November 2017 and August 2018) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. A. The Bank’s Standard Procurement Documents (SPDs): The Bank’s SPDs shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. B. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures (Tendering and Bidding Law of the Peoples’ Republic of China, i.e. TBL promulgated by its Order No. 21 dated August 30, 1999 and the Implementation Regulations of the TBL promulgated by its State Council Order No. 613 dated November 30, 2011 and any amendments thereof) may be used with the following conditions to meet the requirements for open competitive procurement of paragraph 5.4 of the Procurement Regulations: a) All procurement notices shall be published in a national newspaper of wide circulation, or on a widely- used website / electronic portal with free access. b) A minimum of twenty (20) business days shall be given to Bidders between the date of such advertisement (or the date of availability of procurement documents, whichever is later and the deadline for the submission of bids). The advertisement and procurement documents shall specify the deadline for the submission of bids. Potential Bidders shall be allowed to inspect and purchase procurement documents at any time prior to the deadline for the submission of bids. c) Any Bidder/Consultant should be eligible to participate in a procurement process and to be awarded a Bank-financed contract as defined in paragraphs 3.21, 3.22 and 3.23 of the Procurement Regulations. d) Bidders/Consultants shall be allowed to submit bids/proposals by mail or in person. Bidders/consultants shall not be mandatory required to be present at the bid/proposal opening session. e) Bidders should not be required to register as a condition for inspecting or purchasing procurement documents, submitting its bid or receiving contract award. A winner Bidder, shall be given reasonable opportunity of registering (if required) before contract signing without any let or hindrance. Bidding shall not be restricted to any class of contractors. f) The winning bidder shall not be required, as a condition of award, to reduce its bid price No contract negotiation shall be permitted unless agreed in the procurement plan. g) No bid may be rejected solely on the basis that the bid price exceeds any cost estimate. Rejection of all bids or re-bidding shall not be allowed solely because the number of bids is less than three (3). Rebidding shall not take place without any sound justification. h) The Bank’s procurement documents for approaching the national market or any procurement document acceptable to the Bank shall be used. All procurement documents must require that bidders/consultants present a signed acceptance at the time of bidding or submitting a proposal, to be incorporated in any resulting contract, confirming application of and compliance with the Bank’s Anti- Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights. i) The procurement documents shall disclose the newspaper and / or the electronic means in which the information on contract award shall be published. j) The contract award notification shall identify: (a) name and address of the Borrower’s Project Implementing Unit, (b) name and reference number of the contract being awarded and the selection method used (c) names of all Bidders/Consultants that submitted bids/proposals and their prices as read out at the bid opening meeting and as evaluated (d) names of all Bidders/ Consultants whose bids/proposals were rejected either as nonresponsive or as not meeting qualification criteria or were not evaluated, with the reasons therefor and (e) the name of the successful Bidder/Consultant, the final contract price, the contract duration and a summary of its scope. i) The Borrower shall implement an effective complaint mechanism allowing bidders or consultants to complain, and have their complaints handled and responded in a timely manner. Procurement documents should indicate the complaint mechanism procedure and provide the professional title and address of the officials to whom such protests should be sent. j) The Bank shall be allowed to review procurement documentation and activities related to the activities included in the procurement plan. C. Other national procurement arrangements: When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. D. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. E. Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations is not applicable: F. Domestic Preference as specified under paragraph 5.51 of the Procurement Regulations: Goods: Domestic Preference is applicable for those contracts identified in the Procurement Plan tables. Works: Domestic Preference is not applicable G. Other Relevant Procurement Information:. Please insert the Procurement Plan   PROCUREMENT PLAN FOR THE JIANGXI INTEGRATED RURAL AND URBAN WATER SUPPLY AND WASTEWATER MANAGEMENT PROJECT Date of procurement plan:   1 USD = 6.68 RMB               2019/ Estim Estima Estim Estim ated Origin Estimate Lo New Fundi ted ated Procur Evalu Bank ated Date al Contr Market d Date N ca Contr ng Contract Cost Cost ement ation Review Date of Contr act Metho of Remarks o. tio act Sourc Name (10,00 (10,0 Metho Stand (Prior/P of Bid Contr act Type d Advertis n No. e 0 00 d ard ost  Open act No. ement RMB  USD  ning Signi ng Purchasing Contract on Ductile Iron Pipe for Pipes for Water Supply raw water Infrastructur pipeline e Lump Open / project from D Construction Lowes SH- -sum Reque Domes Hengshan on SHST- World and t DX- Contr 1522.3 227.9 st for tic / 2019. 2019. reservoir- 1 gx WB- Bank Renovation Evalu Post 2019.6 GC- act / 7 0 Bid Post- 7 7 Chengdong ia 0049 Loan Project ated 01 Good (RFB  qualific waterworks ng (Water Cost s ation ,Hofang Intake Reservoir- Project) in Chengdong Dongxiang waterworks County loaned by the wold bank General Including Contract for the raw BoQ Construction water based of Water installation, Adme Open / D Supply Lowes intake asure Reque Domes on SH- SHST- World Infrastructur t pumping ment 1523.9 228.1 st for tic / 2019. 2019. 2 gx DX- WB- Bank e Evalu Post 2019.6 house and Contr 4 3 Bid Post- 7 7 ia SG-02 0050 Loan Construction ated integrated act / (RFB  qualific ng and Cost pumping Const ation Renovation station ructio Project works and n (Water equipment Intake installation. Project) in Dongxiang County loaned by the World Bank Purchasing Contract on Ductile Iron Pipe for Water Supply Infrastructur e Lump Open / Construction Lowes SH- -sum Reque Domes Le SHST- World and t LP- Contr 6457.6 966.7 st for tic / 2019. 2019. Raw water 3 pi WB- Bank Renovation Evalu Prior 2019.6 GC- act / 6 2 Bid Post- 7 7 installation ng 0051 Loan Project ated 01 Good (RFB  qualific (Water Cost s ation Intake Project) in Leping County, loaned by the wold bank General Contract for Construction Including of Water the raw BoQ Supply water based Infrastructur installation, Adme e Open / Lowes intake asure Construction Reque Domes Le SH- SHST- World t pumping ment and 8753.4 1310. st for tic / 2019. 2019. 4 pi LP- WB- Bank Evalu Prior 2019.6 house and Contr Renovation 3 39 Bid Post- 7 7 ng SG-01 0052 Loan ated integrated act / Project (RFB  qualific Cost pumping Const (Water ation station ructio Intake works and n Project) in equipment Leping installation. County loaned by the World Bank Purchasing Contract on Smart Water Meters for Leping Lump CouontyWate Open / Lowes -sum r Supply Reque Domes Le SH- SHST- World t Smart Contr Infrastructur 5005.8 749.3 st for tic / 2019. 2019. 5 pi LP- WB- Bank Evalu Prior 2019.6 Water act / e 0 7 Bid Post- 7 7 ng SB-01 0053 Loan ated Meters Good Construction (RFB  qualific Cost s and ation Renovation Project, loaned by the wold bank Purchasing Contract on Ductile Iron Pipe for Pipes Water Supply DN800 used Infrastructur from the e Lump Open / Emergency Construction Lowes Li SH- -sum Reque Domes water SHST- World and t nc LC- Contr st for tic / 2019. 2019. source 6 WB- Bank Renovation 444.48 66.54 Evalu Post 2019.6 hu GC- act / Bid Post- 7 7 intake 0054 Loan Project ated an 01 Good (RFB  qualific pumping (Water Cost s ation station to Intake Lingchuan Project) in NO.2 Linchuan waterworks County loaned by the wold bank . General Contract for Construction of Water Supply Including BoQ Infrastructur the based e installation Adme Construction Open / Lowes of raw Li asure and Reque Domes SH- SHST- World t water pipes nc ment Renovation 5113.0 765.4 st for tic / 2019. 2019. 7 LC- WB- Bank Evalu Post 2019.6 and the hu Contr Project 2 2 Bid Post- 7 7 SG-02 0055 Loan ated infrastructio an act / (Water (RFB  qualific Cost n Const Intake ation construction ructio Project and of new n Water Plant) waterworks in Linchuan County loaned by the world bank Purchasing Contract on Ductile Iron Pipe for Water Supply Infrastructur e Lump Open / Construction Lowes Xi SH- -sum Reque Domes SHST- World and t us XS- Contr 2801.7 419.4 st for tic / 2019. 2019. Raw water 8 WB- Bank Renovation Evalu Prior 2019.6 hu GC- act / 2 2 Bid Post- 7 7 pipeline 0056 Loan Project ated i 01 Good (RFB  qualific (Water Cost s ation Intake Project) in Xiushui County loaned by the wold bank General Including BoQ Contract for the raw based Construction water Adme Open / of Water Lowes installation, Xi asure Reque Domes SH- SHST- World Supply t intake us ment 4154.7 621.9 st for tic / 2019. 2019. 9 XS- WB- Bank Infrastructur Evalu Post 2019.6 pumping hu Contr 0 6 Bid Post- 7 7 SG-01 0057 Loan e ated house and i act / (RFB  qualific Construction Cost integrated Const ation and pumping ructio Renovation station n Project works and (Water equipment Intake installation. Project) in Xiushui County loaned by the World Bank Purchasing Contract on Smart Water Meters for Leping Lump CouontyWate Open / Lowes Xi -sum r Supply Reque Domes SH- SHST- World t Smart 1 us Contr Infrastructur 4326.0 647.6 st for tic / 2019. 2019. XS- WB- Bank Evalu Prior 2019.6 Water 0 hu act / e 0 0 Bid Post- 7 7 SB-01 0058 Loan ated Meters i Good Construction (RFB  qualific Cost s and ation Renovation Project, loaned by the wold bank General Contract on Including BoQ Pipeline general based Installation contracting Adme for Xiushui Open / Lowes for Pipeline asure County Reque Domes Zh SH- SHST- World t installation, 1 ment Zhajin 3126.4 468.0 st for tic / 2019. 2019. aji XSZJ- WB- Bank Evalu Post 2019.6 newly built 1 Contr Township 6 3 Bid Post- 7 7 n SG-02 0059 Loan ated inspection act / Wastewater (RFB  qualific Cost wells,house Const management ation hold ructio Project connection n loaned by project the world bank Purchasing Contract on Lump PE Pipes for Open / Lowes -sum Xiushui Reque Domes Zh SH- SHST- World t 1 Contr County 1072.5 160.5 st for tic / 2019. 2019. aji XSZJ- WB- Bank Evalu Post 2019.6 PE Pipes 2 act / Zhajin 1 6 Bid Post- 7 7 n PE-03 0060 Loan ated Good Township (RFB  qualific Cost s Wastewater ation management Project loaned by the world bank Purchasing Contract on Ductile Iron Pipe for Water Supply Infrastructur e Lump Open / Construction Lowes Yo SH- -sum Reque Domes Pipes for SHST- World and t 1 ng YX- Contr 4335.5 649.0 st for tic / 2019. 2019. water WB- Bank Renovation Evalu Prior 2019.6 3 xi GC- act / 8 4 Bid Post- 7 7 intake 0061 Loan Project ated n 01 Good (RFB  qualific projects (Water Cost s ation Intake Project) in Yongxin County loaned by the wold bank General Contract for Construction of Water Including Supply the raw BoQ Infrastructur water based e installation, Adme Open / Construction Lowes intake Yo asure Reque Domes SH- SHST- World and t pumping 1 ng ment 6163.7 922.7 st for tic / 2019. 2019. YX- WB- Bank Renovation Evalu Post 2019.6 house and 4 xi Contr 1 1 Bid Post- 7 7 SG-01 0062 Loan Project ated integrated n act / (RFB  qualific (Water Cost pumping Const ation Intake station ructio Project) in works and n Yongxin equipment County installation. loaned by the World Bank Purchasing Contract on Smart Water Meters for Yongxin Lump CouontyWate Open / Lowes Yo -sum r Supply Reque Domes SH- SHST- World t Smart 1 ng Contr Infrastructur st for tic / 2019. 2019. YX- WB- Bank 324.82 48.63 Evalu Post 2019.6 Water 5 xi act / e Bid Post- 7 7 SB-01 0063 Loan ated Meters n Good Construction (RFB  qualific Cost s and ation Renovation Project, loaned by the wold bank Purchasing contract WB Integrated Rural and Urban Water Lump all Supply and Reque Lowes -sum co SH- SHST- World Wastewater st for t 1 Contr Domes 2019. 2019. Office un BG- WB- Bank Management 92.40 13.83 Quota Evalu Post 2019.6 6 act / tic 7 7 Supplies tie 01 0064 Loan Project tion ated Good s Provision of (RFQ  Cost s Office Supplies for the Project Management Office Purchasing contract on Vehicle for Jiangxi Lump all Integrated Reque Lowes -sum co SH- SHST- World Rural and st for t 1 Contr Domes 2019. 2019. un BG- WB- Bank Urban Water 150.00 22.46 Quota Evalu Post 2019.6 Vehicle 7 act / tic 7 7 tie 01 0065 Loan Supply and tion ated Good s Wastewater (RFQ  Cost s Management Projec ,loane d by the world bank Purchasing Contract on Ductile Iron Lump Open / D Pipe for Lowes PT- -sum Reque Domes on SHST- World urban water t 1 DX- Contr 2233.0 314.5 st for tic / 2019.1 gx WB- Bank supply Evalu Post 2019.10 2019.11 8 GC- act / 0 1 Bid Post- 1 ia 0092 Loan network ated 01 Good (RFB  qualific ng reconstructio Cost s ation n in Dongxiang County Purchasing Contract on Lump Ductile Iron Open / Lowes PT- -sum Pipe for Reque Domes Le SHST- World t 1 LP- Contr urban water 129.5 st for tic / 2019.1 pi WB- Bank 919.98 Evalu Post 2019.10 2019.11 9 GC- act / supply 7 Bid Post- 1 ng 0093 Loan ated 03 Good network (RFB  qualific Cost s reconstructio ation n in Leping County Purchasing Contract on Lump Ductile Iron Open / Lowes Li PT- -sum Pipe for Reque Domes SHST- World t 2 nc LC- Contr urban water 1272.0 179.1 st for tic / 2019.1 WB- Bank Evalu Post 2019.10 2019.11 0 hu GC- act / supply 0 5 Bid Post- 1 0094 Loan ated an 02 Good network (RFB  qualific Cost s reconstructio ation n in Linchuan County Purchasing Contract on Lump Ductile Iron Open / Lowes Xi PT- -sum Pipe for Reque Domes SHST- World t 2 us XS- Contr urban water 3066.0 431.8 st for tic / 2019.1 WB- Bank Evalu Prior 2019.10 2019.11 1 hu GC- act / supply 0 3 Bid Post- 1 0095 Loan ated i 03 Good network (RFB  qualific Cost s reconstructio ation n in Xiushui County Purchasing Contract on Lump Ductile Iron Open / Lowes Yo PT- -sum Pipe for Reque Domes SHST- World t 2 ng YX- Contr urban water st for tic / 2019.1 WB- Bank 275.00 38.73 Evalu Post 2019.10 2019.11 2 xi GC- act / supply Bid Post- 1 0096 Loan ated n 02 Good network (RFB  qualific Cost s reconstructio ation n in Yongxin County PROCUREMENT China : Jiangxi Integrated Rural and Urban Water Supply and Wastewater Management Project PLAN General Information Country: China 2019-05-28 Bank’s Approval Date of the Original Procurement Plan: 2023-06-07 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P158760 GPN Date: 2018-04-24 Project Name: Jiangxi Integrated Rural and Urban Water Supply and Wastewater Management Project Loan / Credit No: IBRD / 88490 Jiangxi water Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned SHST-WB-0050 / Jiangxi Inte grated Rural and Urban Wate r Supply and Wastewater Ma Expansion, Rehabilitation, a nagement Project loaned by t Single Stage - One E 2021-02-1 IBRD / 88490 nd Modernization of Water S Post Request for Bids Open - National 2,281,300.00 0.00 Canceled 2019-06-03 2019-06-08 2019-07-08 2019-07-15 2019-08-19 he World Bank—General Con nvelope 7 upply System tract for Construction of Raw Water Pipe Installation Projec t at ChengDong Water Treat ment Plant in Dongxiang Cou nty SHST-WB-0055 / Jiangxi Inte grated Rural and Urban Wate r Supply and Wastewater Ma Expansion, Rehabilitation, a nagement Project loaned by t Single Stage - One E 6,107,417.3 2021-08-1 IBRD / 88490 nd Modernization of Water S Post Request for Bids Open - National 7,654,200.00 Signed 2019-06-03 2019-11-14 2019-06-08 2019-11-14 2019-07-08 2019-12-12 2019-07-15 2019-12-31 2019-08-19 2020-03-27 he World Bank—General Con nvelope 3 8 upply System tract for Water Plant Constru ction Project and Raw Water Pipe installation Project of Lin chuan NO.2 Water Treatment Plant SHST-WB-0059 / Jiangxi Inte grated Rural and Urban Wate r Supply and Wastewater Ma nagement Project loaned by t Demonstration of Rural Wast Single Stage - One E 3,768,384.5 2021-08-1 IBRD / 88490 Post Request for Bids Open - National 4,680,300.00 Signed 2019-06-03 2019-11-14 2019-06-08 2019-11-14 2019-07-08 2019-12-12 2019-07-15 2019-12-31 2019-08-19 2020-03-26 he World Bank—General Con ewater Management nvelope 3 8 tract on Pipeline Installation for Xiushui County Zhajin To wnship Wastewater manage ment Project SHST-WB-0068 / Jiangxi Inte grated Rural and Urban Wate r Supply and Wastewater Ma Expansion, Rehabilitation, a Single Stage - One E 2021-11-0 nagement Project loaned by t IBRD / 88490 nd Modernization of Water S Post Request for Bids Open - National 8,439,500.00 0.00 Canceled 2019-08-25 2019-08-30 2019-09-29 2019-10-06 2019-11-10 nvelope 9 he World Bank—General Con upply System tract for Construction of Che ngDong Water Treatment Pla nt project in Dongxiang Coun ty SHST-WB-0070 / Jiangxi Inte grated Rural and Urban Wate r Supply and Wastewater Ma Expansion, Rehabilitation, a nagement Project loaned by t Single Stage - One E 1,749,048.6 2021-11-1 IBRD / 88490 nd Modernization of Water S Post Request for Bids Open - National 2,352,400.00 Signed 2019-08-25 2020-03-03 2019-08-30 2020-03-23 2019-09-29 2020-03-31 2019-10-09 2020-05-14 2019-11-13 2020-07-01 he World Bank—General Con nvelope 3 2 upply System tract for Construction of reha bilitation and expansion pro ject at RunQuan and LiLin W ater Plant in Leping County SHST-WB-0072 / Jiangxi Inte grated Rural and Urban Wate r Supply and Wastewater Ma Expansion, Rehabilitation, a Single Stage - One E 1,568,156.6 2021-05-1 nagement Project loaned by t IBRD / 88490 nd Modernization of Water S Post Request for Bids Open - National 3,355,800.00 Signed 2019-08-25 2020-03-03 2019-08-30 2020-03-23 2019-09-29 2020-03-31 2019-10-09 2020-05-14 2019-11-13 2020-07-01 nvelope 3 4 he World Bank—General Con upply System tract for rehabilitation and e xpansion Project of Xiushui No.3 Water Treatment Plant SHST-WB-0073 / Jiangxi Inte grated Rural and Urban Wate r Supply and Wastewater Ma Expansion, Rehabilitation, a Single Stage - One E 13,262,600.0 9,211,763.2 2021-11-1 nagement Project loaned by t IBRD / 88490 nd Modernization of Water S Post Request for Bids Open - National Signed 2019-08-25 2020-03-03 2019-08-30 2020-03-23 2019-09-29 2020-03-31 2019-10-09 2020-05-14 2019-11-13 2020-07-03 nvelope 0 8 2 he World Bank—General Con upply System tract for Construction of Che ngNan water treatment plant project in Yongxin County SHST-WB-0052 / Jiangxi Inte grated Rural and Urban Wate r Supply and Wastewater Ma Expansion, Rehabilitation, a Single Stage - One E 6,087,119.6 2021-02-1 nagement Project loaned by t IBRD / 88490 nd Modernization of Water S Prior Request for Bids Open - National 6,442,900.00 Signed 2019-06-03 2019-08-31 2019-06-08 2019-09-11 2019-07-08 2019-10-11 2019-07-15 2019-11-07 2019-08-19 2019-12-30 nvelope 6 6 he World Bank—General Con upply System tract for Raw Water Pipe Inst allation Project of RunQuan Water Treatment Plant in Lep ing County SHST-WB-0057 / Jiangxi Inte grated Rural and Urban Wate r Supply and Wastewater Ma Expansion, Rehabilitation, a Single Stage - One E 1,711,008.6 2021-02-1 nagement Project loaned by t IBRD / 88490 nd Modernization of Water S Post Request for Bids Open - National 1,804,200.00 Signed 2019-06-03 2019-09-05 2019-06-08 2019-09-09 2019-07-08 2019-10-11 2019-07-15 2019-11-06 2019-08-19 2019-12-30 nvelope 4 7 he World Bank—General Con upply System tract for Construction of Raw Water Pipe Installation Projec t at Xiushui NO.3 Water Treat ment Plant SHST-WB-0062 / Jiangxi Inte grated Rural and Urban Wate r Supply and Wastewater Ma Expansion, Rehabilitation, a Single Stage - One E 3,250,711.9 2021-02-1 nagement Project loaned by t IBRD / 88490 nd Modernization of Water S Post Request for Bids Open - National 3,429,300.00 Signed 2019-06-03 2019-09-05 2019-06-08 2019-09-09 2019-07-08 2019-10-11 2019-07-15 2019-11-06 2019-08-19 2019-12-16 nvelope 6 7 he World Bank—General Con upply System tract for Raw Water Pipe Inst allation Project of ChengNan Water Treatment Plant in Yon gxin County SHST-SH-0097 / General Con tract for Construction of Che Expansion, Rehabilitation, a Single Stage - One E 9,188,436.6 2022-01-2 ngDong Water Treatment Pla IBRD / 88490 nd Modernization of Water S Post Request for Bids Open - National 8,450,700.00 Signed 2019-10-30 2019-11-14 2019-11-04 2019-11-14 2019-12-04 2019-12-12 2019-12-19 2019-12-31 2020-01-23 2020-03-12 nvelope 5 2 nt project and Raw Water Pip upply System e Installation project in Dong xiang County SHST-WB-0127 / General Co nstruction contract on install Expansion, Rehabilitation, a ation of rural water distributi Single Stage - One E 7,997,675.7 2021-09-2 IBRD / 88490 nd Modernization of Water S Post Request for Bids Open - National 8,028,200.00 Signed 2020-07-01 2020-08-11 2020-07-06 2020-08-11 2020-08-05 2020-09-10 2020-08-20 2020-10-11 2020-09-24 2020-12-09 on network and reconstructio nvelope 2 4 upply System n of water supply network in some urban areas of Dongxia ng District Page 1 SHST-WB-0128 / General Co nstruction Contract on rural water distribution network in Expansion, Rehabilitation, a Single Stage - One E 5,351,659.7 2021-09-2 Jinxi County, water plant con IBRD / 88490 nd Modernization of Water S Post Request for Bids Open - National 8,450,700.00 Signed 2020-07-01 2020-08-11 2020-07-06 2020-08-11 2020-08-05 2020-09-10 2020-08-20 2020-10-11 2020-09-24 2021-03-19 nvelope 0 4 struction at Huangtong Town upply System ship and part of the urban wa ter supply network reconstru ction in Jinxi County SHST-WB-0130 / General Co nstruction contract on install Expansion, Rehabilitation, a ation of rural water distributi Single Stage - One E 2,799,382.4 2021-09-2 IBRD / 88490 nd Modernization of Water S Post Request for Bids Open - National 3,413,700.00 Signed 2020-07-01 2020-08-11 2020-07-06 2020-08-11 2020-08-05 2020-09-10 2020-08-20 2020-10-20 2020-09-24 2021-01-06 on network and reconstructio nvelope 1 4 upply System n of water supply network in some urban area of Linchua n County SHST-WB-0131 / General Co nstruction contract on install Expansion, Rehabilitation, a ation of rural water distributi Single Stage - One E 14,084,500.0 2021-09-2 IBRD / 88490 nd Modernization of Water S Prior Request for Bids Open - National 0.00 Canceled 2020-07-01 2020-07-30 2020-07-06 2020-08-09 2020-08-05 2020-09-10 2020-08-20 2020-11-19 2020-09-24 on network and reconstructio nvelope 0 4 upply System n of water supply network in some urban areas of Xiushui County SHST-WB-0132 / General Co nstruction contract on install Expansion, Rehabilitation, a ation of rural water distributi Single Stage - One E 6,608,050.5 2021-09-2 IBRD / 88490 nd Modernization of Water S Post Request for Bids Open - National 5,633,800.00 Signed 2020-07-01 2020-08-11 2020-07-06 2020-08-11 2020-08-05 2020-09-10 2020-08-20 2020-10-20 2020-09-24 2021-03-19 on network and reconstructio nvelope 3 4 upply System n of water supply network in some urban areas of Yongxin County SHST-WB-0133 / General Co Expansion, Rehabilitation, a nstruction contract on install Single Stage - One E 3,087,172.1 2021-09-2 IBRD / 88490 nd Modernization of Water S Post Request for Bids Open - National 3,943,700.00 Signed 2020-07-01 2020-08-11 2020-07-06 2020-08-11 2020-08-05 2020-09-10 2020-08-20 2020-10-20 2020-09-24 2020-12-11 ation of rural water distributi nvelope 5 4 upply System on network in Nanfeng Count y SHST-WB-0129 / General Co nstruction contract on install Expansion, Rehabilitation, a ation of rural water distributi Single Stage - One E 8,879,969.1 2021-11-0 IBRD / 88490 nd Modernization of Water S Post Request for Bids Open - National 4,368,000.00 Signed 2020-07-19 2020-08-11 2020-07-24 2020-08-11 2020-09-04 2020-09-10 2020-10-04 2020-10-11 2020-11-08 2021-03-19 on network and reconstructio nvelope 5 8 upply System n of water supply network in some urban areas of Leping county SHST-WB-0131-1 / General Construction contract on inst Expansion, Rehabilitation, a allation of rural water distrib Single Stage - One E 20,704,200.0 13,551,936. 2021-12-2 IBRD / 88490 nd Modernization of Water S Prior Request for Bids Open - National Signed 2021-03-12 2021-03-23 2021-03-17 2021-04-02 2021-04-28 2021-05-07 2021-05-28 2021-06-15 2021-07-02 2021-08-24 ution network and reconstruc nvelope 0 17 9 upply System tion of water supply network in some urban areas of Xiush ui County National Procure SHST-WB-0161 / The Constr Expansion, Rehabilitation, a ment Document - Single Stage - One E 2023-01-0 uction Contract for water sup IBRD / 88490 nd Modernization of Water S Post Request for Bids Open - National 1 Envelope proce 2,272,700.00 0.00 Signed 2022-03-15 2022-08-04 2022-03-20 2022-08-19 2022-05-01 2022-09-01 2022-05-31 2022-09-18 2022-07-05 nvelope 1 ply dispatching center in Xius upply System ss (Non Bank-SPD hui Conuty ) SHST-WB-0162 / The Constr National Procure uction Contract on rural pipe Expansion, Rehabilitation, a ment Document - Single Stage - One E 2023-01-0 network installation project f IBRD / 88490 nd Modernization of Water S Post Request for Bids Open - National 1 Envelope proce 3,030,300.00 0.00 Signed 2022-03-15 2022-08-04 2022-03-20 2022-08-19 2022-05-01 2022-09-01 2022-05-31 2022-09-18 2022-07-05 nvelope 1 or extension from entering vi upply System ss (Non Bank-SPD llages to households in Yon ) gxin County National Procure SHST-WB-0176 / Constructio Expansion, Rehabilitation, a ment Document - Single Stage - One E Under Imple 2024-02-1 n contract for extension secti IBRD / 88490 nd Modernization of Water S Post Request for Bids Open - National 1 Envelope proce 8,823,500.00 0.00 2023-04-24 2023-06-05 2023-04-29 2023-06-10 2023-07-10 2023-08-14 nvelope mentation 0 on of water supply network i upply System ss (Non Bank-SPD n Xiushui County ) National Procure SHST-WB-0177 / Constructio Expansion, Rehabilitation, a ment Document - Single Stage - One E 12,500,000.0 Under Imple 2024-02-1 n contract for extension secti IBRD / 88490 nd Modernization of Water S Post Request for Bids Open - National 1 Envelope proce 0.00 2023-04-24 2023-06-05 2023-04-29 2023-06-10 2023-07-10 2023-08-14 nvelope 0 mentation 0 on of water supply network i upply System ss (Non Bank-SPD n Leping County ) National Procure SHST-WB-0178 / Constructio Expansion, Rehabilitation, a ment Document - Single Stage - One E Under Imple 2024-02-1 n contract for extension secti IBRD / 88490 nd Modernization of Water S Post Request for Bids Open - National 1 Envelope proce 1,470,600.00 0.00 2023-04-24 2023-06-05 2023-04-29 2023-06-10 2023-07-10 2023-08-14 nvelope mentation 0 on of water supply network i upply System ss (Non Bank-SPD n Yongxin County ) National Procure SHST-WB-0173 / Constructio Expansion, Rehabilitation, a ment Document - n Contract for rehabilitation a Single Stage - One E Under Imple 2024-02-0 IBRD / 88490 nd Modernization of Water S Post Request for Bids Open - National 1 Envelope proce 1,818,200.00 0.00 2023-04-23 2023-04-26 2023-04-28 2023-06-09 2023-05-30 2023-07-09 2023-06-06 2023-08-13 nd expansion of Water Treat nvelope mentation 9 upply System ss (Non Bank-SPD ment Plant in Xiushui County ) National Procure SHST-WB-0179 / Decoration Expansion, Rehabilitation, a ment Document - Request for Quota Single Stage - One E Pending Imp 2024-01-2 Contract for office building of IBRD / 88490 nd Modernization of Water S Post Limited 1 Envelope proce 454,500.00 0.00 2023-05-30 2023-07-25 tions nvelope lementation 1 Water Treatment Plant in Yon upply System ss (Non Bank-SPD gxin County ) National Procure SHST-WB-0180 / Constructio Expansion, Rehabilitation, a ment Document - Single Stage - One E Pending Imp 2024-04-0 n contract for extension secti IBRD / 88490 nd Modernization of Water S Post Request for Bids Open - National 1 Envelope proce 4,545,500.00 0.00 2023-06-18 2023-06-23 2023-08-04 2023-09-03 2023-10-08 nvelope lementation 5 on of water supply network i upply System ss (Non Bank-SPD n Jinxi County ) GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SHST-WB-0063 / Jiangxi Inte grated Rural and Urban Wate r Supply and Wastewater Ma Expansion, Rehabilitation, a Single Stage - One E nagement Project loaned by t IBRD / 88490 nd Modernization of Water S Post Request for Bids Open - National 486,300.00 421,719.06 Signed 2019-06-03 2020-01-16 2019-06-08 2020-01-16 2019-07-08 2020-03-26 2019-07-15 2020-05-20 2019-08-19 2020-07-04 2020-08-18 nvelope he World Bank—Purchasing C upply System ontract on Smart Water Mete rs for urban water supply ne twork reconstruction in Yong xin County SHST-WB-0058 / Jiangxi Inte grated Rural and Urban Wate r Supply and Wastewater Ma Expansion, Rehabilitation, a Single Stage - One E nagement Project loaned by t IBRD / 88490 nd Modernization of Water S Prior Request for Bids Open - National 6,476,000.00 3,393,075.78 Signed 2019-06-03 2020-01-11 2019-06-08 2020-01-16 2019-07-08 2020-03-26 2019-07-15 2020-05-19 2019-08-19 2020-06-24 2020-08-18 nvelope he World Bank—Purchasing C upply System ontract on Smart Water Mete rs for urban water supply ne twork reconstruction in Xiush ui County SHST-WB-0049 / Jiangxi Inte grated Rural and Urban Wate r Supply and Wastewater Ma Expansion, Rehabilitation, a nagement Project loaned by t Single Stage - One E IBRD / 88490 nd Modernization of Water S Post Request for Bids Open - National 2,279,000.00 1,540,379.09 Signed 2019-06-03 2019-11-19 2019-06-08 2019-11-19 2019-07-08 2020-01-06 2019-07-15 2020-01-06 2019-08-19 2020-04-16 2020-08-18 he World Bank—Purchasing C nvelope upply System ontract on Ductile Iron Pipe f or Raw Water Pipe Installatio n Project of ChengDong Wate r Treatment Plant in Dongxia ng County Page 2 SHST-WB-0053 / Jiangxi Inte grated Rural and Urban Wate r Supply and Wastewater Ma Expansion, Rehabilitation, a Single Stage - One E nagement Project loaned by t IBRD / 88490 nd Modernization of Water S Prior Request for Bids Open - National 7,493,700.00 2,332,483.15 Signed 2019-06-03 2020-01-11 2019-06-08 2020-01-16 2019-07-08 2020-03-26 2019-07-15 2020-05-19 2019-08-19 2020-06-24 2020-08-18 nvelope he World Bank—Purchasing C upply System ontract on Smart Water Mete rs for urban water supply ne twork reconstruction in Lepin g County SHST-WB-0060 / Jiangxi Inte grated Rural and Urban Wate r Supply and Wastewater Ma Demonstration of Rural Wast Single Stage - One E nagement Project loaned by t IBRD / 88490 Post Request for Bids Open - National 1,605,600.00 1,357,501.00 Signed 2019-06-03 2019-11-19 2019-06-08 2019-11-19 2019-07-08 2019-12-17 2019-07-15 2020-01-10 2019-08-19 2020-03-21 2020-08-18 ewater Management nvelope he World Bank—Purchasing C ontract on HDPE Pipes for Xi ushui County Zhajin Townshi p Wastewater management Project SHST-WB-0054 / Jiangxi Inte grated Rural and Urban Wate r Supply and Wastewater Ma Expansion, Rehabilitation, a nagement Project loaned by t Single Stage - One E IBRD / 88490 nd Modernization of Water S Post Request for Bids Open - National 665,400.00 464,961.69 Signed 2019-06-03 2019-11-19 2019-06-08 2019-11-19 2019-07-08 2020-01-06 2019-07-15 2020-01-06 2019-08-19 2020-04-16 2020-08-18 he World Bank—Purchasing C nvelope upply System ontract on Ductile Iron Pipe f or Raw Water Pipe Installatio n Project of Linchuan NO.2 W ater Treatment Plant SHST-WB-0065 / Jiangxi Inte grated Rural and Urban Wate r Supply and Wastewater Ma Public Engagement and Proj Request for Quota Single Stage - One E IBRD / 88490 Post Limited 224,600.00 140,398.94 Signed 2019-06-08 2019-11-07 2019-07-28 2019-12-11 2020-01-24 nagement Project loaned by t ect Management tions nvelope he World Bank—Purchasing c ontract on Vehicle for the Pro ject SHST-WB-0064 / Jiangxi Inte grated Rural and Urban Wate r Supply and Wastewater Ma Public Engagement and Proj Request for Quota Single Stage - One E nagement Project loaned by t IBRD / 88490 Post Limited 138,300.00 65,137.22 Signed 2019-06-08 2019-12-04 2019-07-28 2020-01-17 2020-01-24 ect Management tions nvelope he World Bank—Purchasing c ontract on Provision of Offic e Supplies for the Project Ma nagement Office SHST-WB-0069 / Jiangxi Inte grated Rural and Urban Wate r Supply and Wastewater Ma Expansion, Rehabilitation, a nagement Project loaned by t Request for Quota Single Stage - One E IBRD / 88490 nd Modernization of Water S Post Limited 373,100.00 0.00 Canceled 2019-08-30 2019-10-19 2020-04-16 he World Bank—Purchasing c tions nvelope upply System ontract on Floating Pumping Station for Water Intake Proje ct of Hengshan Reservoir in Dongxiang County SHST-WB-0071 / Jiangxi Inte grated Rural and Urban Wate r Supply and Wastewater Ma Expansion, Rehabilitation, a nagement Project loaned by t Single Stage - One E Pending Impl IBRD / 88490 nd Modernization of Water S Post Request for Bids Open - National 625,300.00 0.00 2019-08-25 2019-08-30 2019-09-29 2019-10-09 2019-11-13 2020-11-12 he World Bank—Purchasing c nvelope ementation upply System ontract on Matching Equipme nt for Modernization and Rec onstruction in Linchuan No. 1 Water treatment plant SHST-WB-0074 / Jiangxi Inte grated Rural and Urban Wate r Supply and Wastewater Ma Expansion, Rehabilitation, a Single Stage - One E nagement Project loaned by t IBRD / 88490 nd Modernization of Water S Post Request for Bids Open - National 1,197,600.00 722,749.67 Signed 2019-08-25 2019-10-15 2019-08-30 2019-10-14 2019-09-29 2019-11-21 2019-10-09 2019-12-24 2019-11-13 2020-03-16 2020-11-12 nvelope he World Bank—Purchasing c upply System ontract on Valves for Raw W ater Pipe Installation Project i n Leping,Xiushui and Yongxin County SHST-WB-0051 / Jiangxi Inte grated Rural and Urban Wate r Supply and Wastewater Ma Expansion, Rehabilitation, a nagement Project loaned by t Single Stage - One E IBRD / 88490 nd Modernization of Water S Prior Request for Bids Open - National 11,994,400.00 10,363,507.16 Signed 2019-06-03 2019-08-19 2019-06-08 2019-08-23 2019-07-08 2019-09-29 2019-07-15 2019-10-25 2019-08-19 2019-12-16 2020-08-18 he World Bank—Purchasing C nvelope upply System ontract on Ductile Iron Pipe f or Raw Water Pipe Installatio n Project of RunQuan Water Treatment Plant in Leping Co unty SHST-WB-0061 / Jiangxi Inte grated Rural and Urban Wate r Supply and Wastewater Ma Expansion, Rehabilitation, a nagement Project loaned by t Single Stage - One E IBRD / 88490 nd Modernization of Water S Prior Request for Bids Open - National 7,682,400.00 6,718,546.18 Signed 2019-06-03 2019-08-19 2019-06-08 2019-08-28 2019-07-08 2019-09-29 2019-07-15 2019-10-25 2019-08-19 2019-12-16 2020-08-18 he World Bank—Purchasing C nvelope upply System ontract on Ductile Iron Pipe f or Raw Water Pipe Installatio n Project of ChengNan Water Treatment Plant in Yongxin C ounty SHST-WB-0056 / Jiangxi Inte grated Rural and Urban Wate r Supply and Wastewater Ma Expansion, Rehabilitation, a nagement Project loaned by t Single Stage - One E IBRD / 88490 nd Modernization of Water S Post Request for Bids Open - National 2,818,600.00 2,501,795.98 Signed 2019-06-03 2019-08-21 2019-06-08 2019-08-21 2019-07-08 2019-09-29 2019-07-15 2019-10-26 2019-08-19 2019-12-17 2020-08-18 he World Bank—Purchasing C nvelope upply System ontract on Ductile Iron Pipe f or Raw Water Pipe Installatio n Project of Xiushui NO.3 Wat er Treatment Plant SHST-WB-0092 / Purchase C ontract on ductile iron pipe f Expansion, Rehabilitation, a Single Stage - One E or reconstruction of pipe net IBRD / 88490 nd Modernization of Water S Post Request for Bids Open - National 3,686,000.00 3,654,811.89 Signed 2019-10-21 2019-11-19 2019-10-26 2019-11-19 2019-11-25 2020-01-06 2019-12-10 2020-01-06 2020-01-14 2020-04-16 2023-01-13 nvelope work for urban water supply upply System and extension of rural pipe n etwork in Dongxiang county SHST-WB-0093 / Purchase C ontract on ductile iron pipe f Expansion, Rehabilitation, a Single Stage - One E or reconstruction of pipe net IBRD / 88490 nd Modernization of Water S Prior Request for Bids Open - National 5,614,100.00 3,884,383.04 Signed 2019-10-21 2019-11-15 2019-10-26 2019-11-20 2019-11-25 2020-01-06 2019-12-10 2020-03-24 2020-01-14 2020-04-30 2023-01-13 nvelope work for urban water supply upply System and extension of rural pipe n etwork in Leping County SHST-WB-0094 / Purchase C ontract on ductile iron pipe f Expansion, Rehabilitation, a Single Stage - One E or reconstruction of pipe net IBRD / 88490 nd Modernization of Water S Post Request for Bids Open - National 2,806,500.00 2,803,583.14 Signed 2019-10-21 2019-11-19 2019-10-26 2019-11-19 2019-11-25 2020-01-06 2019-12-10 2020-01-06 2020-01-14 2020-04-16 2023-01-13 nvelope work for urban water supply upply System and extension of rural pipe n etwork in Linchuan County SHST-WB-0095 / Purchase C ontract on ductile iron pipe f Expansion, Rehabilitation, a Single Stage - One E or reconstruction of pipe net IBRD / 88490 nd Modernization of Water S Prior Request for Bids Open - National 11,074,800.00 9,593,788.11 Signed 2019-10-21 2019-11-15 2019-10-26 2019-11-20 2019-11-25 2020-01-06 2019-12-10 2020-03-25 2020-01-14 2020-04-30 2023-01-13 nvelope work for urban water supply upply System and extension of rural pipe n etwork in Xiushui County Page 3 SHST-WB-0096 / Purchase C ontract on ductile iron pipe f Expansion, Rehabilitation, a Single Stage - One E or reconstruction of pipe net IBRD / 88490 nd Modernization of Water S Prior Request for Bids Open - National 4,111,200.00 4,215,409.66 Signed 2019-10-21 2019-11-15 2019-10-26 2019-11-20 2019-11-25 2020-01-06 2019-12-10 2020-03-24 2020-01-14 2020-04-30 2023-01-13 nvelope work for urban water supply upply System and extension of rural pipe n etwork in Yongxin County SHST-WB-0111 / Purchase c ontract of electrical equipme Expansion, Rehabilitation, a nts for construction, rehabilit Single Stage - One E IBRD / 88490 nd Modernization of Water S Prior Request for Bids Open - National 5,070,400.00 1,802,137.63 Signed 2020-06-25 2020-07-19 2020-06-30 2020-07-24 2020-07-30 2020-08-31 2020-08-14 2020-11-10 2020-09-18 2020-12-10 2021-09-18 ation and expansion of wate nvelope upply System r plant in Leping, Dongxiang, Yongxin, Linchuan and Xiush ui counties SHST-WB-0112 / Purchase c ontract of process equipment Expansion, Rehabilitation, a s for construction, rehabilitat Single Stage - One E IBRD / 88490 nd Modernization of Water S Prior Request for Bids Open - National 6,338,000.00 5,922,229.19 Signed 2020-06-25 2020-07-19 2020-06-30 2020-07-23 2020-07-30 2020-08-31 2020-08-14 2020-11-19 2020-09-18 2020-12-21 2021-09-18 ion and expansion of water nvelope upply System plant in Leping, Dongxiang, Y ongxin, Linchuan and Xiushui counties SHST-WB-0113 / Purchase c ontract of automatic control Expansion, Rehabilitation, a equipments for construction, Single Stage - One E IBRD / 88490 nd Modernization of Water S Post Request for Bids Open - National 2,323,900.00 1,204,975.09 Signed 2020-06-25 2020-07-23 2020-06-30 2020-07-23 2020-07-30 2020-08-31 2020-08-14 2020-09-17 2020-09-18 2020-12-01 2021-09-18 rehabilitation and expansion nvelope upply System of water plant in Leping, Don gxiang, Yongxin, Linchuan an d Xiushui counties SHST-WB-0114 / Purchase c ontract of valves for construc Expansion, Rehabilitation, a Single Stage - One E tion, rehabilitation and expa IBRD / 88490 nd Modernization of Water S Post Request for Bids Open - National 2,816,900.00 2,707,491.96 Signed 2020-06-25 2020-07-23 2020-06-30 2020-07-23 2020-07-30 2020-12-10 2020-08-14 2020-12-10 2020-09-18 2021-01-21 2021-09-18 nvelope nsion of water plant in Lepin upply System g, Dongxiang, Yongxin, Linch uan and Xiushui counties SHST-WB-0115 / Purchase c ontract of water pumps for c Expansion, Rehabilitation, a onstruction, rehabilitation an Single Stage - One E IBRD / 88490 nd Modernization of Water S Post Request for Bids Open - National 2,957,700.00 651,839.04 Signed 2020-06-25 2020-07-23 2020-06-30 2020-07-23 2020-07-30 2020-08-31 2020-08-14 2020-09-17 2020-09-18 2020-11-21 2021-09-18 d expansion of water plant i nvelope upply System n Leping, Dongxiang, Yongxi n, Linchuan and Xiushui coun ties SHST-WB-0119 / Purchase C ontract on PE pipe for rural pi Expansion, Rehabilitation, a Single Stage - One E peline installation from villa IBRD / 88490 nd Modernization of Water S Post Request for Bids Open - National 2,911,800.00 2,475,882.82 Signed 2020-07-05 2020-07-10 2020-07-10 2020-07-13 2020-08-09 2020-08-13 2020-08-24 2020-08-27 2020-09-28 2020-10-27 2021-09-28 nvelope ge to household) in Nanfeng, upply System Leping county and Linchuan county of Fuzhou City SHST-WB-0124 / The Second Purchase Contract on ductile iron pipe for reconstruction o Expansion, Rehabilitation, a Single Stage - One E f pipe network for urban wat IBRD / 88490 nd Modernization of Water S Post Request for Bids Open - National 2,920,400.00 3,467,504.12 Signed 2020-07-12 2020-07-10 2020-07-17 2020-07-13 2020-08-16 2020-08-13 2020-08-31 2020-08-27 2020-10-05 2020-10-27 2021-10-05 nvelope er supply and extension of ru upply System ral pipe network in Yongxin,X iushui,Nanfeng County and Li nchuan county of Fuzhou Cit y SHST-WB-0123 / The Second Purchase Contract on ductile iron pipe for reconstruction o Expansion, Rehabilitation, a Single Stage - One E f pipe network for urban wat IBRD / 88490 nd Modernization of Water S Post Request for Bids Open - National 3,810,500.00 1,885,187.85 Signed 2020-07-05 2020-07-10 2020-07-10 2020-07-13 2020-08-09 2020-08-13 2020-08-24 2020-08-27 2020-09-28 2020-10-27 2021-09-28 nvelope er supply and extension of ru upply System ral pipe network in Leping, Ji nxi county and Dongxiang of Fuzhou city SHST-WB-0120 / Purchase C ontract on PE pipe for urban Expansion, Rehabilitation, a pipeline reconstruction and r Single Stage - One E IBRD / 88490 nd Modernization of Water S Post Request for Bids Open - National 3,411,600.00 2,727,750.86 Signed 2020-07-12 2020-07-10 2020-07-17 2020-07-13 2020-08-28 2020-08-13 2020-09-27 2020-08-27 2020-11-01 2020-10-27 2021-11-01 ural pipeline installation(from nvelope upply System village to household) in Yong xin,Xiushui,Jinxi County and Dongxiang county of Fuzhou City SHST-WB-0121 / Purchasing Contract on smart water met Expansion, Rehabilitation, a ers for reconstruction of urb Single Stage - One E IBRD / 88490 nd Modernization of Water S Prior Request for Bids Open - National 4,881,400.00 0.00 Canceled 2020-08-20 2020-08-25 2020-10-06 2020-11-05 2020-12-10 2021-12-10 an water supply network and nvelope upply System for rural drinking water user s newly increased in Dongxia ng County SHST-WB-0125 / Purchasing Contract on smart water met Expansion, Rehabilitation, a ers for Reconstruction of urb Single Stage - One E IBRD / 88490 nd Modernization of Water S Post Request for Bids Open - National 3,730,400.00 1,380,394.18 Signed 2020-08-20 2021-02-25 2020-08-25 2021-02-25 2020-10-06 2021-03-25 2020-11-05 2021-03-25 2020-12-10 2021-04-24 2021-06-08 an water supply network and nvelope upply System for rural drinking water user s newly increased in Linchu an County SHST-WB-0126 / Purchasing Contract on Smart Water Met Expansion, Rehabilitation, a ers for reconstruction of urba Single Stage - One E IBRD / 88490 nd Modernization of Water S Post Request for Bids Open - National 1,631,200.00 1,398,722.53 Signed 2020-08-20 2021-02-25 2020-08-25 2021-02-25 2020-10-06 2021-03-25 2020-11-05 2021-03-25 2020-12-10 2021-04-24 2021-12-10 n water supply network and f nvelope upply System or rural drinking water users newly increased in Nanfeng County SHST-WB-0135 / Purchasing Expansion, Rehabilitation, a Single Stage - One E Contract on sensors used for IBRD / 88490 nd Modernization of Water S Post Request for Bids Open - National 3,367,600.00 2,559,686.18 Signed 2020-08-25 2020-09-04 2020-08-30 2020-09-04 2020-10-11 2020-10-13 2020-11-10 2020-10-13 2020-12-15 2020-11-26 2021-06-13 nvelope pipe network of smart water upply System supply system SHST-WB-0138 / Purchasing Contract on Smart Water Met Expansion, Rehabilitation, a ers for reconstruction of urba Single Stage - One E IBRD / 88490 nd Modernization of Water S Post Request for Bids Open - National 2,647,900.00 976,232.66 Signed 2020-11-10 2021-02-25 2020-11-15 2021-02-25 2020-12-27 2021-03-25 2021-01-26 2021-03-25 2021-03-02 2021-04-24 2021-08-29 n water supply network and f nvelope upply System or rural drinking water users newly increased in Jinxi Cou nty SHST-WB-0152 / Purchasing contract on Floating Pumping Expansion, Rehabilitation, a Single Stage - One E Station for Water Intake Proje IBRD / 88490 nd Modernization of Water S Post Request for Bids Open - National 769,200.00 694,990.85 Signed 2021-02-22 2021-02-20 2021-02-27 2021-02-21 2021-03-29 2021-03-19 2021-04-28 2021-03-19 2021-06-02 2021-04-27 2021-11-29 nvelope ct of Hengshan Reservoir and upply System Hefang Reservior in Dongxia ng County SHST-WB-0121-1 / The First Purchase Contract on smart Expansion, Rehabilitation, a water meters for Reconstruc Single Stage - One E IBRD / 88490 nd Modernization of Water S Post Request for Bids Open - National 2,606,100.00 1,943,036.58 Signed 2021-02-28 2021-02-25 2021-03-05 2021-02-25 2021-04-16 2021-03-25 2021-05-16 2021-03-25 2021-06-20 2021-04-24 2021-12-17 tion of urban water supply ne nvelope upply System twork and for rural drinking water users newly increased in Dongxiang County Page 4 SHST-WB-0153 / The Second Purchase Contract on ductile iron pipe for reconstruction o Expansion, Rehabilitation, a Single Stage - One E f pipe network for urban wat IBRD / 88490 nd Modernization of Water S Prior Request for Bids Open - National 6,818,200.00 7,185,807.40 Signed 2021-04-05 2021-04-01 2021-04-10 2021-04-02 2021-05-22 2021-05-08 2021-06-21 2021-06-01 2021-07-26 2021-06-25 2022-01-22 nvelope er supply and extension of ru upply System ral pipe network in Leping,Do ngxiang,Jinxi,Yongxin,Xiushui ,Linchuan and Nanfeng Coun ty SHST-WB-0155 / The Second Expansion, Rehabilitation, a Request for Quota Single Stage - One E Purchasing Contract on Vehic IBRD / 88490 nd Modernization of Water S Post Open - National 57,600.00 58,176.64 Signed 2021-06-01 2021-07-27 2021-07-08 2022-01-23 tions nvelope le for the Project upply System SHST-WB-0156 / The Third P urchase Contract on ductile ir Expansion, Rehabilitation, a on pipe for reconstruction of Single Stage - One E IBRD / 88490 nd Modernization of Water S Post Request for Bids Open - National 3,863,600.00 4,594,822.70 Signed 2021-06-21 2021-08-02 2021-06-26 2021-08-07 2021-08-31 2021-09-06 2021-08-31 2021-10-11 2021-09-30 2022-04-09 pipe network for urban water nvelope upply System supply and extension of rural pipe network in Leping,Dong xiang,Yongxin and Linchuan County SHST-WB-0157 / The Forth P urchase Contract on ductile ir on pipe for reconstruction of Expansion, Rehabilitation, a Single Stage - One E pipe network for urban water IBRD / 88490 nd Modernization of Water S Prior Request for Bids Open - National 18,939,400.00 0.00 Canceled 2022-03-15 2022-03-20 2022-05-01 2022-05-31 2022-07-05 2023-01-01 nvelope supply and extension of rural upply System pipe network in Leping,Dong xiang,Yongxin,Linchuan,Xius hui,Nanfeng and Jinxi County SHST-WB-0158 / Supplemen tary purchase contract on S Expansion, Rehabilitation, a Single Stage - One E Under Imple mart Water Meters for water- IBRD / 88490 nd Modernization of Water S Post Request for Bids Open - National 2,424,200.00 0.00 2022-04-01 2022-11-01 2022-04-06 2022-05-18 2022-11-30 2022-06-17 2022-11-30 2022-07-22 2023-01-18 nvelope mentation users newly increased in sma upply System rt water supply system SHST-WB-0159 / The Purcha Expansion, Rehabilitation, a se Contract on Goods for Rec Single Stage - One E Pending Impl IBRD / 88490 nd Modernization of Water S Prior Request for Bids Open - National 5,000,000.00 0.00 2022-04-01 2022-04-06 2022-05-18 2022-06-17 2022-07-22 2023-01-18 onstruction of secondary pre nvelope ementation upply System ssurized pump house of smar t water supply system SHST-WB-0160 / The Purcha Expansion, Rehabilitation, a se Contract on Equipments fo Single Stage - One E Under Imple IBRD / 88490 nd Modernization of Water S Post Request for Bids Open - National 3,181,800.00 0.00 2022-02-21 2023-03-02 2022-02-26 2022-04-09 2023-03-30 2022-05-09 2023-03-30 2022-06-13 2022-12-10 r energy efficiency review an nvelope mentation upply System d renovation project of smart water supply system SHST-WB-0164 / The Second Expansion, Rehabilitation, a Purchase Contract on Goods Single Stage - One E Under Imple IBRD / 88490 nd Modernization of Water S Post Request for Bids Open - National 1,515,200.00 0.00 2022-03-15 2022-12-26 2022-03-20 2022-05-01 2023-01-31 2022-05-31 2023-02-01 2022-07-05 2023-01-01 for Water plant automatic co nvelope mentation upply System ntrol system transformation SHST-WB-0165 / The Purcha Expansion, Rehabilitation, a se Contract on Materials for p Single Stage - One E Pending Impl IBRD / 88490 nd Modernization of Water S Post Request for Bids Open - National 1,515,200.00 0.00 2022-03-15 2022-03-20 2022-05-01 2022-05-31 2022-07-05 2023-01-01 ipe network extension enteri nvelope ementation upply System ng from the village to househ old in Leping County SHST-WB-0166 / The Purcha se contract on equipment for integrated pump station of w Expansion, Rehabilitation, a Single Stage - One E Pending Impl ater intake pump house, urb IBRD / 88490 nd Modernization of Water S Post Request for Bids Open - National 1,818,200.00 0.00 2022-03-15 2022-03-20 2022-05-01 2022-05-31 2022-07-05 2023-01-01 nvelope ementation an pipe network reconstructi upply System on and Rural water distributi on network extension project in Dongxiang,Leping and Xiu shui County SHST-WB-0167 / The Purcha se Contract on smart water Expansion, Rehabilitation, a meters for pipe network exte Single Stage - One E Pending Impl IBRD / 88490 nd Modernization of Water S Post Request for Bids Open - National 954,500.00 0.00 2022-02-21 2022-02-26 2022-04-09 2022-05-09 2022-06-13 2022-12-10 nsion from entering village to nvelope ementation upply System household in Leping,Xiushui, Yongxin,Dongxiang,Linchuan ,Nanfeng and Jinxi County SHST-WB-0168 / The Purcha Expansion, Rehabilitation, a Request for Quota Single Stage - One E Pending Impl se Contract on Vehicle for Jia IBRD / 88490 nd Modernization of Water S Post Open - National 227,300.00 0.00 2022-02-26 2022-04-23 2022-10-20 tions nvelope ementation ngxi PMO upply System SHST-WB-0169 / The Forth P urchase Contract on ductile ir Expansion, Rehabilitation, a on pipe for reconstruction of Single Stage - One E IBRD / 88490 nd Modernization of Water S Post Request for Bids Open - National 2,424,200.00 5,056,463.47 Signed 2022-04-11 2022-05-23 2022-04-16 2022-05-28 2022-06-21 2022-06-27 2022-06-21 2022-08-01 2022-08-07 2023-01-28 pipe network for urban water nvelope upply System supply and extension of rural pipe network in Leping,Dong xiang and Nanfeng County SHST-WB-0170 / The Forth P urchase Contract on ductile ir Expansion, Rehabilitation, a on pipe for reconstruction of Single Stage - One E IBRD / 88490 nd Modernization of Water S Prior Request for Bids Open - National 6,060,600.00 5,825,797.05 Signed 2022-04-11 2022-04-13 2022-04-16 2022-05-23 2022-05-28 2022-06-21 2022-06-27 2022-07-12 2022-08-01 2022-08-07 2023-01-28 pipe network for urban water nvelope upply System supply and extension of rural pipe network in Yongxin Cou nty SHST-WB-0171 / The Forth P urchase Contract on ductile ir Expansion, Rehabilitation, a on pipe for reconstruction of Single Stage - One E IBRD / 88490 nd Modernization of Water S Prior Request for Bids Open - National 7,575,800.00 7,851,557.57 Signed 2022-04-11 2022-04-13 2022-04-16 2022-05-23 2022-05-28 2022-06-21 2022-06-27 2022-07-13 2022-08-01 2022-07-29 2023-01-28 pipe network for urban water nvelope upply System supply and extension of rural pipe network in Xiushui Coun ty SHST-WB-0172 / The Second Supplementary purchase con Expansion, Rehabilitation, a Single Stage - One E Under Imple tract on Smart Water Meters IBRD / 88490 nd Modernization of Water S Post Request for Bids Open - National 2,727,300.00 0.00 2022-07-01 2022-12-05 2022-07-06 2022-08-17 2022-11-30 2022-09-16 2022-11-30 2022-10-21 2023-04-19 nvelope mentation for water-users newly increas upply System ed in smart water supply syst em SHST-WB-0174 / The First Pr ocurement Contract for hous Expansion, Rehabilitation, a ehold connection materials o Single Stage - One E IBRD / 88490 nd Modernization of Water S Prior Request for Bids Open - National 8,939,400.00 0.00 Signed 2022-12-25 2023-01-05 2022-12-30 2023-03-02 2023-02-10 2023-03-30 2023-03-12 2023-04-07 2023-04-16 2023-06-27 2023-10-13 f Water Supply New Users on nvelope upply System Urban and Rural Pipe Networ k Project of Water Supply Sys tem SHST-WB-0175 / The Second Procurement Contract for h Expansion, Rehabilitation, a ousehold connection material Single Stage - One E IBRD / 88490 nd Modernization of Water S Prior Request for Bids Open - National 9,090,900.00 0.00 Signed 2022-12-25 2023-01-05 2022-12-30 2023-03-02 2023-02-10 2023-03-30 2023-03-12 2023-04-07 2023-04-16 2023-06-27 2023-10-13 s of Water Supply New User nvelope upply System s on Urban and Rural Pipe Ne twork Project of Water Suppl y System Page 5 SHST-WB-0163 / The Constr action Contract for capacity e Expansion, Rehabilitation, a xpansion and basic applicatio Single Stage - One E Pending Impl IBRD / 88490 nd Modernization of Water S Post Request for Bids Open - National 3,676,500.00 0.00 2022-04-01 2022-04-06 2022-05-18 2022-06-17 2022-07-22 2023-01-18 n of smart water supply syst nvelope ementation upply System em, smart water supply appl ication subsystem, GIS engin e and cloud GIS service platf orm SHST-WB-0181 / The Fifth Pu rchase Contract on ductile iro Expansion, Rehabilitation, a n pipe for reconstruction of p Single Stage - One E Pending Impl IBRD / 88490 nd Modernization of Water S Post Request for Bids Open - National 3,787,900.00 0.00 2023-06-18 2023-06-23 2023-08-04 2023-09-03 2023-10-08 2024-04-05 ipe network for urban water s nvelope ementation upply System upply and extension of rural pipe network in Leping,Xiush ui,Yongxin and Jinxi County NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 6 PROCUREMENT Ecuador : Transformation of the Tertiary Technical and Technological Institutes Project PLAN General Information Country: Ecuador 2017-06-22 Bank’s Approval Date of the Original Procurement Plan: 2023-06-06 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P157425 GPN Date: 2017-07-10 Project Name: Transformation of the Tertiary Technical and Technological Institutes Project Loan / Credit No: IBRD / 86670 Higher Education Secretariat Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned EC-SENESCYT-32822-CW-RF B / READECUACIÓN ARQUITE CTÓNICA URBANÍSTICA Y DE I Component 1: Optimizing an Open - Internationa Single Stage - One E 2020-05-2 NGENIERÍA DE LA INFRAESTR IBRD / 86670 d Upgrading the Supply in T Prior Request for Bids 5,627,229.57 0.00 Canceled 2019-04-29 2019-05-06 2019-05-20 2019-07-08 2019-08-20 l nvelope 5 UCTURA EXISTENTE SECAP - argeted Provinces. CERFIN (QUITO NORTE) UBIC ADO EN EL CANTÓN QUITO, P ROVINCIA DE PICHINCHA. EC-SENESCYT-32823-CW-RF B / READECUACIÓN ARQUITE CTÓNICA URBANÍSTICA Y DE I Component 1: Optimizing an NGENIERÍA DE LA INFRAESTR Single Stage - One E 2019-09-1 IBRD / 86670 d Upgrading the Supply in T Post Request for Bids Open - National 2,439,361.53 0.00 Canceled 2018-11-05 2018-11-12 2018-11-26 2018-12-24 2019-02-05 UCTURA EXISTENTE (SECAP) nvelope 6 argeted Provinces. DESTINADA PARA EL FUNCIO NAMIENTO DEL INSTITUTO S UPERIOR TECNOLÓGICO UBIC ADO EN LA CIUDAD DE AMBA TO EC-SENESCYT-32821-CW-RF B / READECUACIÓN ARQUITE CTÓNICA URBANÍSTICA Y DE I Component 1: Optimizing an NGENIERÍA DE LA INFRAESTR Open - Internationa Single Stage - One E 2019-12-0 IBRD / 86670 d Upgrading the Supply in T Prior Request for Bids 7,050,218.41 0.00 Canceled 2018-11-05 2018-11-12 2018-11-26 2019-01-14 2019-02-26 UCTURA EXISTENTE (SECAP) l nvelope 2 argeted Provinces. DESTINADA PARA EL FUNCIO NAMIENTO DEL INSTITUTO S UPERIOR TECNOLÓGICO UBIC ADO EN LA CIUDAD DE DURÁ N EC-SENESCYT-79371-CW-RF Component 1: Optimizing an Request for Propo Open - Internationa Single Stage - One E 2020-11-0 P / CONSTRUCCIÓN IST AMBA IBRD / 86670 d Upgrading the Supply in T Prior 9,260,000.00 0.00 Canceled 2019-12-20 2019-12-26 2020-02-06 2020-03-02 2020-03-30 sals l nvelope 5 TO argeted Provinces. EC-SENESCYT-120064-CW-R Component 1: Optimizing an Single Stage - One E 3,105,374.4 2020-08-1 FB / CONSTRUCCIÓN DEL IST IBRD / 86670 d Upgrading the Supply in T Post Request for Bids Open - National 2,972,900.00 Completed 2019-10-01 2019-12-22 2019-10-13 2020-03-22 2019-11-17 2020-06-17 2019-12-02 2020-07-14 2019-12-23 2020-11-24 nvelope 5 9 LUIS A. MARTÍNEZ DE MANAB argeted Provinces. Í, MANTA EC-SENESCYT-120067-CW-R Component 1: Optimizing an Single Stage - One E 1,396,254.5 2020-11-2 FB / CONSTRUCCIÓN DEL IST IBRD / 86670 d Upgrading the Supply in T Post Request for Bids Open - National 1,782,000.00 Signed 2020-02-03 2020-08-30 2020-02-15 2021-10-21 2020-03-21 2020-10-02 2020-04-05 2020-12-04 2020-04-26 2020-12-18 nvelope 0 2 EN PICHINCHA, QUITO (YAVIR argeted Provinces. AC) EC-SENESCYT-120201-CW-R Component 1: Optimizing an Single Stage - One E 2020-05-2 FB / CONSTRUCCIÓN DEL IST IBRD / 86670 d Upgrading the Supply in T Post Request for Bids Open - National 2,290,800.00 0.00 Canceled 2019-10-01 2020-03-04 2019-10-13 2020-03-22 2019-11-17 2020-06-15 2019-12-02 2019-12-23 nvelope 1 EN SUCUMBÍOS, LAGO AGRIO argeted Provinces. EC-SENESCYT-120213-CW-R Component 1: Optimizing an Single Stage - One E 2020-09-0 FB / CONSTRUCCIÓN DEL IST IBRD / 86670 d Upgrading the Supply in T Post Request for Bids Open - National 3,687,750.00 0.00 Canceled 2019-11-04 2019-11-16 2019-12-21 2020-01-05 2020-01-26 nvelope 7 EN BOLÍVAR, CHIMBO argeted Provinces. EC-SENESCYT-120245-CW-R Component 1: Optimizing an Open - Internationa Single Stage - One E 10,079,387.4 2021-08-2 FB / CONSTRUCCIÓN DEL IST IBRD / 86670 d Upgrading the Supply in T Post Request for Bids 0.00 Canceled 2020-08-24 2020-09-08 2020-10-20 2020-11-19 2020-12-23 l nvelope 7 0 EN PICHINCHA, QUITO (LA M argeted Provinces. OYA) EC-SENESCYT-79354-CW-RF Component 1: Optimizing an Request for Propo Single Stage - One E 2019-12-1 P / CONSTRUCCIÓN IST CHIM IBRD / 86670 d Upgrading the Supply in T Post Open - National 3,340,000.00 0.00 Canceled 2019-04-09 2019-04-19 2019-05-31 2019-06-30 2019-07-24 sals nvelope 1 BO argeted Provinces. EC-SENESCYT-79377-CW-RF Component 1: Optimizing an Request for Propo Single Stage - One E 2019-10-0 P / CONSTRUCCIÓN IST LAGO IBRD / 86670 d Upgrading the Supply in T Post Open - National 2,010,000.00 0.00 Canceled 2019-03-15 2019-03-20 2019-05-01 2019-05-21 2019-06-16 sals nvelope 8 AGRIO argeted Provinces. EC-SENESCYT-79363-CW-RF Component 1: Optimizing an Request for Propo Open - Internationa Single Stage - One E 2020-07-0 P / CONSTRUCCIÓN IST MAC IBRD / 86670 d Upgrading the Supply in T Prior 9,260,000.00 0.00 Canceled 2019-04-23 2019-04-28 2019-06-09 2019-07-09 2019-08-06 sals l nvelope 1 HALA argeted Provinces. EC-SENESCYT-79373-CW-RF Component 1: Optimizing an Request for Propo Single Stage - One E 2019-11-1 P / CONSTRUCCIÓN SEGUND IBRD / 86670 d Upgrading the Supply in T Post Open - National 2,730,000.00 0.00 Canceled 2019-03-04 2019-03-12 2019-04-23 2019-05-19 2019-06-04 sals nvelope 9 A ETAPA IST YAVIRAC argeted Provinces. EC-SENESCYT-120204-CW-R Component 1: Optimizing an Open - Internationa Single Stage - One E 10,319,021.9 11,519,846. 2021-02-2 FB / CONSTRUCCIÓN DEL IST IBRD / 86670 d Upgrading the Supply in T Prior Request for Bids Signed 2019-12-30 2020-03-24 2020-01-19 2020-03-30 2020-03-01 2020-06-22 2020-03-31 2020-08-28 2020-04-29 2020-11-24 l nvelope 4 58 3 EN EL ORO, MACHALA argeted Provinces. EC-SENESCYT-180417-CW-R Component 1: Optimizing an Single Stage - One E 2,732,032.3 2021-01-2 FB / CONSTRUCCIÓN DEL IST IBRD / 86670 d Upgrading the Supply in T Post Request for Bids Open - National 2,632,106.93 Signed 2020-06-16 2020-06-23 2020-06-22 2021-10-20 2020-07-22 2020-07-24 2020-08-11 2020-08-17 2020-09-01 2020-11-24 nvelope 3 9 EN SUCUMBÍOS, LAGO AGRIO argeted Provinces. GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual EC-SENESCYT-40222-GO-RF B / ADQUISICIÓN DE EQUIPO Component 2: Improving Pro S COMPUTACIONALES PARA grams Relevance, Quality of Single Stage - One E IBRD / 86670 Post Request for Bids Open - National 89,285.71 0.00 Canceled 2018-11-05 2018-11-10 2018-12-10 2018-12-25 2019-01-19 2019-02-04 EL DESARROLLO Y LA IMPLE Teaching and IST Manageme nvelope MENTACIÓN DEL SISTEMA DE nt Capacity. GESTIÓN INTEGRAL DE EDUC ACIÓN SUPERIOR Component 3: Strengthening EC-SENESCYT-78569-GO-DIR Mechanisms for Institutional / ADQUISICION SOFTWARE FI IBRD / 86670 Coordination, Boosting Dem Post Direct Selection Direct 26,785.71 10,000.00 Completed 2018-10-01 2019-02-05 2018-10-06 2019-02-12 2018-11-10 2019-03-25 2018-12-10 2019-06-28 NANCIERO and, and Management, Moni toring and Eval uation of the Project. Page 1 EC-SENESCYT-44457-GO-RF B / ADQUISICIÓN DE EQUIPA MIENTO PARA EL LABORATO Component 1: Optimizing an Open - Internationa Single Stage - One E RIO DE SIMULADORES DE LO IBRD / 86670 d Upgrading the Supply in T Prior Request for Bids 1,750,238.00 0.00 Canceled 2018-02-15 2018-02-25 2018-03-27 2018-04-04 2018-04-19 2019-05-09 l nvelope GÍSTICA DE LOS INSTITUTOS argeted Provinces. SUPERIORES TECNOLÓGICOS PÚBLICOS DE LAS CIUDADES DE MANTA Y MACHALA EC-SENESCYT-44452-GO-RF B / ADQUISICIÓN DE EQUIPA MIENTO ESPECIALIZADO DE L Component 1: Optimizing an AS CARRERAS DE ELECTRÓNI Open - Internationa Single Stage - One E IBRD / 86670 d Upgrading the Supply in T Prior Request for Bids 2,710,642.50 0.00 Canceled 2018-02-13 2018-02-23 2018-03-25 2018-03-30 2018-04-17 2019-05-07 CA Y ELECTRICIDAD DE LOS I l nvelope argeted Provinces. NSTITUTOS SUPERIORES TEC NOLÓGICOS PÚBLICOS DE LA S CIUDADES DE MANTA, MAC HALA Y LAGO AGRIO EC-SENESCYT-40219-GO-RF B / ADQUISICIÓN DE INFRAES Component 2: Improving Pro TRUCTURA TECNOLÓGICA P grams Relevance, Quality of Open - Internationa Single Stage - One E IBRD / 86670 Prior Request for Bids 1,510,000.00 0.00 Canceled 2019-01-18 2019-01-23 2019-03-06 2019-03-21 2019-04-21 2019-07-16 ARA EL ALOJAMIENTO DEL SI Teaching and IST Manageme l nvelope STEMA DE GESTIÓN INTEGRA nt Capacity. L DE EDUCACIÓN SUPERIOR EC-SENESCYT-44456-GO-RF B / ADQUISICIÓN DE MOBILIA RIO BÁSICO, ADMINISTRATIV O, MOBILIARIO ESPECIALIZAD Component 1: Optimizing an Single Stage - One E O Y MATERIAL DIDÁCTICO PA IBRD / 86670 d Upgrading the Supply in T Prior Request for Bids Open - National 1,676,939.66 0.00 Canceled 2018-02-15 2018-02-25 2018-03-17 2018-03-28 2018-04-19 2019-05-09 nvelope RA LOS INSTITUTOS SUPERIO argeted Provinces. RES TECNOLÓGICOS PÚBLIC OS UBICADOS EN LAS CIUDA DES DE MANTA, NUEVA LOJA, QUITO IÑAQUITO y MACHALA EC-SENESCYT-44453-GO-RF B / ADQUISICIÓN DE EQUIPA MIENTO PARA EL TALLER DE MECÁNICA AUTOMOTRIZ Y EL Component 1: Optimizing an Open - Internationa Single Stage - One E TALLER DE REFRIGERACIÓN I IBRD / 86670 d Upgrading the Supply in T Prior Request for Bids 1,648,557.55 0.00 Canceled 2018-02-13 2018-02-23 2018-03-25 2018-04-04 2018-04-17 2019-05-07 l nvelope NDUSTRIAL Y AIRE ACONDICI argeted Provinces. ONADODE LOS INSTITUTOS S UPERIORES TECNOLÓGICOS PÚBLICOS DE LAS CIUDADES DE MANTA Y MACHALA EC-SENESCYT-44455-GO-RF B / ADQUISICIÓN DE EQUIPO S DE COMPUTACIÓN, IMPRESI ÓN, PROYECCIÓN Y SOLUCIO Component 1: Optimizing an NES TECNOLÓGICAS INTERA Open - Internationa Single Stage - One E IBRD / 86670 d Upgrading the Supply in T Prior Request for Bids 1,429,960.25 0.00 Canceled 2018-02-14 2018-02-24 2018-03-26 2018-03-31 2018-04-18 2019-05-08 CTIVAS PARA LOS LABORATO l nvelope argeted Provinces. RIOS DE INFORMÁTICA PARA LOS INSTITUTOS SUPERIORE S TECNOLÓGICOS PÚBLICOS UBICADOS EN LAS CIUDADES DE QUITO-IÑAQUITO, MANTA, NUEVA LOJA Y M EC-SENESCYT-44451-GO-RF B / ADQUISICIÓN DEL EQUIPA MIENTO PARA EL LABORATO RIO DE ENSAYOS MECÁNICO Component 1: Optimizing an Open - Internationa Single Stage - One E S, LIMPIEZA MECÁNICA, PINT IBRD / 86670 d Upgrading the Supply in T Prior Request for Bids 1,839,585.98 0.00 Canceled 2018-02-12 2018-02-22 2018-03-24 2018-03-29 2018-04-16 2019-05-06 l nvelope URA, AJUSTAJE MECÁNICO, C argeted Provinces. HAPISTERÍA Y METROLOGÍA DE LOS INSTITUTOS SUPERIO RES TECNOLÓGICOS PÚBLIC OS DE LAS CIUDADES DE MA NTA Y MACHALA EC-SENESCYT-44450-GO-RF B / ADQUISICIÓN DE MAQUIN ARIA Y EQUIPOS PARA EL TAL Component 1: Optimizing an Open - Internationa Single Stage - One E LER DE METALMECÁNICA DE IBRD / 86670 d Upgrading the Supply in T Prior Request for Bids 3,063,979.72 0.00 Canceled 2018-02-12 2018-02-22 2018-03-24 2018-03-29 2018-04-16 2019-05-06 l nvelope LOS INSTITUTOS SUPERIORE argeted Provinces. S TECNOLÓGICOS PÚBLICOS DE LAS CIUDADES DE MANTA Y MACHALA EC-SENESCYT-44454-GO-RF B / ADQUISICIÓN DE EQUIPO S PARA LOS LABORATORIOS DE QUÍMICA, FÍSICA, PETROQ Component 1: Optimizing an UÍMICA, MEDICIÓN Y MONITO Open - Internationa Single Stage - One E IBRD / 86670 d Upgrading the Supply in T Prior Request for Bids 1,242,716.98 0.00 Canceled 2018-02-14 2018-02-24 2018-03-31 2018-04-05 2018-04-18 2019-05-08 REO AMBIENTAL, CIENCIAS BI l nvelope argeted Provinces. OLÓGICAS, MICROALGAS, AG UA Y SUELOS DE LOS INSTIT UTOS SUPERIORES TECNOLÓ GICOS PÚBLICOS UBICADOS EN LAS CIUDADES DE NUEVA LOJA Y MACHA EC-SENESCYT-79372-GO-RF Component 1: Optimizing an Request for Propo Open - Internationa Single Stage - One E P / EQUIPAMIENTO IST AMBA IBRD / 86670 d Upgrading the Supply in T Prior 4,704,000.00 0.00 Canceled 2020-04-08 2020-04-13 2020-05-25 2020-06-24 2020-07-29 2021-03-16 sals l nvelope TO argeted Provinces. EC-SENESCYT-79375-GO-RF Component 1: Optimizing an Request for Propo Single Stage - One E P / EQUIPAMIENTO DEL IST Q IBRD / 86670 d Upgrading the Supply in T Post Open - National 484,000.00 0.00 Canceled 2018-12-10 2018-12-15 2019-01-26 2019-02-25 2019-03-19 2019-08-16 sals nvelope UITO IÑAQUITO argeted Provinces. EC-SENESCYT-79376-GO-RF Component 1: Optimizing an Request for Propo Open - Internationa Single Stage - One E P / EQUIPAMIENTO DEL IST M IBRD / 86670 d Upgrading the Supply in T Prior 5,379,000.00 0.00 Canceled 2018-12-13 2018-12-18 2019-01-27 2019-02-26 2019-04-03 2019-12-04 sals l nvelope ANTA argeted Provinces. EC-SENESCYT-115029-GO-R Component 1: Optimizing an Open - Internationa Single Stage - One E FB / EQUIPAMIENTO DEL IST IBRD / 86670 d Upgrading the Supply in T Prior Request for Bids 5,600,000.00 0.00 Canceled 2019-06-03 2019-06-07 2019-06-05 2019-10-22 2019-07-11 2020-01-28 2019-07-26 2019-08-24 2020-02-20 l nvelope LUIS A. MARTÍNEZ DE MANAB argeted Provinces. Í, MANTA EC-SENESCYT-120069-GO-R Component 1: Optimizing an Open - Internationa Single Stage - One E FB / EQUIPAMIENTO DEL IST IBRD / 86670 d Upgrading the Supply in T Prior Request for Bids 1,969,334.35 0.00 Canceled 2019-12-23 2020-01-12 2020-02-23 2020-03-24 2020-04-27 2021-01-22 l nvelope EN PICHINCHA, QUITO (YAVIR argeted Provinces. AC) EC-SENESCYT-120203-GO-R Component 1: Optimizing an Open - Internationa Single Stage - One E FB / EQUIPAMIENTO DEL IST IBRD / 86670 d Upgrading the Supply in T Prior Request for Bids 3,100,001.00 0.00 Canceled 2019-11-15 2019-12-05 2020-01-16 2020-02-15 2020-03-20 2020-07-28 l nvelope EN SUCUMBÍOS, LAGO AGRIO argeted Provinces. EC-SENESCYT-120209-GO-R Component 1: Optimizing an Open - Internationa Single Stage - One E FB / EQUIPAMIENTO DEL IST IBRD / 86670 d Upgrading the Supply in T Prior Request for Bids 7,700,001.00 0.00 Canceled 2020-03-27 2020-04-16 2020-05-28 2020-06-27 2020-07-31 2021-04-17 l nvelope EN EL ORO, MACHALA argeted Provinces. EC-SENESCYT-120224-GO-R Component 1: Optimizing an Open - Internationa Single Stage - One E FB / EQUIPAMIENTO DEL IST IBRD / 86670 d Upgrading the Supply in T Prior Request for Bids 2,800,000.00 0.00 Canceled 2019-10-01 2019-10-21 2019-12-02 2020-01-01 2020-02-04 2020-11-20 l nvelope EN BOLÍVAR, CHIMBO argeted Provinces. Page 2 EC-SENESCYT-120250-GO-R Component 1: Optimizing an Open - Internationa Single Stage - One E FB / EQUIPAMIENTO DEL IST IBRD / 86670 d Upgrading the Supply in T Prior Request for Bids 5,450,670.32 0.00 Canceled 2020-08-24 2020-09-13 2020-10-25 2020-11-24 2020-12-28 2021-10-24 l nvelope EN PICHINCHA, QUITO (LA M argeted Provinces. OYA) EC-SENESCYT-120350-GO-R FB / ADQUISICIÓN DE INFRAE Component 2: Improving Pro STRUCTURA TECNOLÓGICA P grams Relevance, Quality of Open - Internationa Single Stage - One E IBRD / 86670 Post Request for Bids 1,440,000.00 0.00 Canceled 2020-03-16 2020-04-05 2020-05-17 2020-06-16 2020-07-20 2021-01-16 ARA EL ALOJAMIENTO DEL SI Teaching and IST Manageme l nvelope STEMA DE GESTIÓN NACION nt Capacity. AL DE LOS IST (CONECTIVIDA D IST + DATA CENTER) EC-SENESCYT-120608-GO-R Component 1: Optimizing an FB / SISTEMA DE GESTIÓN NA Single Stage - One E IBRD / 86670 d Upgrading the Supply in T Post Request for Bids Open - National 147,877.44 0.00 Canceled 2019-09-23 2019-10-05 2019-11-09 2019-11-24 2019-12-15 2020-03-14 CIONAL DE LOS IST (BUSINES nvelope argeted Provinces. S INTELLIGENCE) EC-SENESCYT-79357-GO-RF Component 1: Optimizing an Request for Propo Open - Internationa Single Stage - One E P / EQUIPAMIENTO IST CHIMB IBRD / 86670 d Upgrading the Supply in T Prior 2,189,000.00 0.00 Canceled 2019-05-02 2019-05-07 2019-06-18 2019-07-10 2019-07-25 2019-12-17 sals l nvelope O argeted Provinces. EC-SENESCYT-79378-GO-RF Component 1: Optimizing an Request for Propo Open - Internationa Single Stage - One E P / EQUIPAMIENTO DEL IST L IBRD / 86670 d Upgrading the Supply in T Prior 2,453,000.00 0.00 Canceled 2019-03-20 2019-03-25 2019-05-06 2019-05-26 2019-06-19 2019-12-26 sals l nvelope AGO AGRIO argeted Provinces. EC-SENESCYT-79367-GO-RF Component 1: Optimizing an Request for Propo Open - Internationa Single Stage - One E P / EQUIPAMIENTO IST MACH IBRD / 86670 d Upgrading the Supply in T Prior 6,457,000.00 0.00 Canceled 2019-08-12 2019-08-19 2019-09-30 2019-11-09 2019-12-15 2020-08-01 sals l nvelope ALA argeted Provinces. EC-SENESCYT-79374-GO-RF Component 1: Optimizing an Request for Propo Open - Internationa Single Stage - One E P / EQUIPAMIENTO PARA LA S IBRD / 86670 d Upgrading the Supply in T Prior 2,040,000.00 0.00 Canceled 2019-03-18 2019-03-23 2019-05-04 2019-05-26 2019-06-11 2019-12-16 sals l nvelope EGUNDA ETAPA IST YAVIRAC argeted Provinces. EC-SENESCYT-183129-GO-DI R / APOYO FORMATIVO INDIVI Component 2: Improving Pro DUALIZADO MEDIANTE INFRA grams Relevance, Quality of Under Imple IBRD / 86670 Post Direct Selection Direct 201,164.00 0.00 2020-07-09 2020-07-10 2020-07-14 2020-07-23 2021-08-31 ESTRUCTURA TECNOLÓGICA Teaching and IST Manageme mentation EN LOS INSTITUTOS SUPERIO nt Capacity. RES PÚBLICOS A NIVEL NACI ONAL EC-SENESCYT-195915-GO-R FB / EQUIPAMIENTO PARA IN Component 1: Optimizing an STITUTOS TÉCNICOS SUPERI Open - Internationa Single Stage - One E IBRD / 86670 d Upgrading the Supply in T Prior Request for Bids 9,094,108.50 8,113,206.44 Signed 2020-09-30 2021-02-19 2020-10-02 2021-02-24 2020-11-01 2021-04-26 2020-11-11 2022-03-23 2020-12-05 2022-06-03 2021-08-22 ORES EN LAS ÁREAS: CIENCI l nvelope argeted Provinces. AS DE LA VIDA, ELECTRÓNIC A, MAQUINARIA INDUSTRIAL Y AUTOMOTRIZ EC-SENESCYT-195916-GO-R Component 1: Optimizing an Open - Internationa Single Stage - One E FB / EQUIPAMIENTO PARA IN IBRD / 86670 d Upgrading the Supply in T Prior Request for Bids 1,170,800.39 0.00 Canceled 2020-09-30 2020-10-02 2020-11-01 2020-11-11 2020-12-05 2021-08-22 l nvelope STITUTOS TÉCNICOS SUPERI argeted Provinces. ORES: MOBILIARIO EC-SENESCYT-195917-GO-R Component 1: Optimizing an FB / EQUIPAMIENTO PARA IN Open - Internationa Single Stage - One E IBRD / 86670 d Upgrading the Supply in T Prior Request for Bids 1,417,544.22 1,056,618.12 Signed 2020-09-30 2021-03-16 2020-10-02 2021-03-22 2020-11-01 2021-05-12 2020-11-11 2021-08-24 2020-12-05 2022-05-31 2021-08-22 STITUTOS TÉCNICOS SUPERI l nvelope argeted Provinces. ORES: EQUIPOS INFORMÁTIC OS EC-SENESCYT-195918-GO-R Component 1: Optimizing an FB / EQUIPAMIENTO PARA IN Open - Internationa Single Stage - One E IBRD / 86670 d Upgrading the Supply in T Prior Request for Bids 725,625.61 0.00 Canceled 2020-09-30 2020-10-02 2020-11-01 2020-11-11 2020-12-05 2021-08-22 STITUTOS TÉCNICOS SUPERI l nvelope argeted Provinces. ORES: HERRAMIENTAS DE CO MPLEMENTO EC-SENESCYT-195919-GO-R Component 1: Optimizing an FB / EQUIPAMIENTO PARA IN Single Stage - One E IBRD / 86670 d Upgrading the Supply in T Post Request for Bids Open - National 344,999.15 0.00 Canceled 2020-09-30 2021-03-21 2020-10-02 2021-11-22 2020-11-01 2021-04-22 2020-11-11 2020-12-05 2021-08-22 STITUTO TÉCNICO SUPERIOR nvelope argeted Provinces. EN EL ÁREA DE GASTRONOMÍ A EC-SENESCYT-225888-GO-R Component 1: Optimizing an Single Stage - One E Under Imple FB / EQUIPAMIENTO PARA IN IBRD / 86670 d Upgrading the Supply in T Post Request for Bids Open - National 1,170,800.39 0.00 2021-03-25 2021-03-26 2021-03-28 2021-12-22 2021-04-27 2021-05-25 2021-05-17 2021-07-14 2021-06-15 2021-11-12 nvelope mentation STITUTOS TÉCNICOS SUPERI argeted Provinces. ORES: MOBILIARIO EC-SENESCYT-225890-GO-R FB / EQUIPAMIENTO PARA IN Component 1: Optimizing an Single Stage - One E Under Imple STITUTOS TÉCNICOS SUPERI IBRD / 86670 d Upgrading the Supply in T Post Request for Bids Open - National 725,625.61 0.00 2021-03-24 2021-03-26 2021-03-28 2022-10-07 2021-04-27 2021-05-17 2021-06-15 2021-11-12 nvelope mentation ORES: HERRAMIENTAS, INSU argeted Provinces. MOS Y ELEMENTOS DE SEGU RIDAD EC-SENESCYT-251355-GO-R Component 2: Improving Pro FQ / ADQUISICIÓN DE INSUM grams Relevance, Quality of Request for Quota Single Stage - One E Under Imple OS DE ASEO Y LIMPIEZA PAR IBRD / 86670 Post Open - National 86,360.47 0.00 2021-09-09 2021-10-15 2021-11-14 Teaching and IST Manageme tions nvelope mentation A LOS INSTITUTOS Y CONSER nt Capacity. VATORIOS SUPERIORES PÚBL ICOS A NIVEL NACIONAL EC-SENESCYT-278703-GO-R FB / EQUPAMIENTO PARA EL I Component 1: Optimizing an Single Stage - One E Pending Impl NSTITUTO SUPERIOR TECNOL IBRD / 86670 d Upgrading the Supply in T Post Request for Bids Open - National 361,912.13 0.00 2022-02-28 2022-03-01 2022-03-31 2022-04-10 2022-05-04 2022-09-01 nvelope ementation ÓGICO DE TURISMO Y PATRI argeted Provinces. MONIO YAVIRAC ISTTP-Y: EQ UIPOS DE GASTRONOMÍA EC-SENESCYT-278704-GO-R FQ / EQUIPAMIENTO PARA EL Component 1: Optimizing an INSTITUTO SUPERIOR TECNO Request for Quota Single Stage - One E Pending Impl IBRD / 86670 d Upgrading the Supply in T Post Open - National 53,924.39 0.00 2022-03-01 2022-04-15 2022-06-14 LÓGICO DE TURISMO Y PATRI tions nvelope ementation argeted Provinces. MONIO YAVIRAC ISTTP-Y: ME NAJE COMPLEMENTARIO PAR A GASTRONOMÍA EC-SENESCYT-278706-GO-R FQ / EQUIPAMIENTO PARA EL Component 1: Optimizing an Request for Quota Single Stage - One E Pending Impl INSTITUTO SUPERIOR TECNO IBRD / 86670 d Upgrading the Supply in T Post Limited 5,089.17 0.00 2022-03-05 2022-04-19 2022-05-19 tions nvelope ementation LÓGICO DE TURISMO Y PATRI argeted Provinces. MONIO YAVIRAC ISTTP-Y: ME NAJE ARTESANAL EC-SENESCYT-288677-GO-R Component 2: Improving Pro FB / ADQUISICIÓN DE SISTEM grams Relevance, Quality of Single Stage - One E Pending Impl AS DE AULAS HÍBRIDAS PARA IBRD / 86670 Post Request for Bids Open - National 347,994.83 0.00 2022-04-13 2022-04-18 2022-05-18 2022-06-02 2022-06-26 2022-10-24 Teaching and IST Manageme nvelope ementation LOS INSTITUTOS Y CONSERV nt Capacity. ATORIOS SUPERIORES PÚBLI COS EC-SENESCYT-348653-GO-R Component 2: Improving Pro FB / ADQUISICIÓN DEL EQUIP grams Relevance, Quality of Open - Internationa Single Stage - One E Under Imple IBRD / 86670 Post Request for Bids 2,442,432.32 0.00 2023-03-20 2023-04-05 2023-03-22 2023-04-05 2023-05-06 2023-05-26 2023-06-24 2023-11-21 AMIENTO INFORMÁTICO PAR Teaching and IST Manageme l nvelope mentation A INSTITUTOS SUPERIORES T nt Capacity. ECNOLÓGICOS Page 3 EC-SENESCYT-348867-GO-R Component 2: Improving Pro FB / ADQUISICIÓN DE MOBILI grams Relevance, Quality of Open - Internationa Single Stage - One E Under Imple IBRD / 86670 Post Request for Bids 1,519,982.79 0.00 2023-03-20 2023-04-05 2023-03-22 2023-04-05 2023-05-06 2023-05-26 2023-06-24 2023-11-21 ARIO PARA LOS INSTITUTOS Teaching and IST Manageme l nvelope mentation SUPERIORES PÚBLICOS nt Capacity. EC-SENESCYT-348869-GO-R Component 2: Improving Pro FQ / ADQUISICIÓN DE MENAJ grams Relevance, Quality of Request for Quota Single Stage - One E Pending Impl E COMPLEMENTARIO DE GAS IBRD / 86670 Post Open - National 10,437.06 0.00 2023-03-22 2023-05-23 2023-07-22 Teaching and IST Manageme tions nvelope ementation TRONOMÍA PARA LOS INSTIT nt Capacity. UTOS SUPERIORES PÚBLICOS EC-SENESCYT-348871-GO-R Component 2: Improving Pro FB / ADQUISICIÓN DE EQUIPA grams Relevance, Quality of Single Stage - One E Pending Impl IBRD / 86670 Post Request for Bids Open - National 191,535.70 0.00 2023-03-20 2023-03-25 2023-04-24 2023-05-14 2023-06-12 2023-10-10 MIENTO DE GASTRONOMÍA P Teaching and IST Manageme nvelope ementation ARA LOS INSTITUTOS SUPERI nt Capacity. ORES PÚBLICOS EC-SENESCYT-348873-GO-R Component 2: Improving Pro FB / ADQUISICIÓN DE MAQUI grams Relevance, Quality of Open - Internationa Single Stage - One E Under Imple NARIA INDUSTRIAL Y AUTOM IBRD / 86670 Post Request for Bids 1,174,903.13 0.00 2023-03-20 2023-04-05 2023-03-22 2023-04-05 2023-05-06 2023-05-26 2023-06-24 2023-11-21 Teaching and IST Manageme l nvelope mentation OTRIZ PARA LOS INSTITUTOS nt Capacity. SUPERIORES PÚBLICOS NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 3: Strengthening EC-SENESCYT-32829-NC-RF Mechanisms for Institutional B / ADQUISICIÓN DE UN SOFT Request for Quota Single Stage - One E IBRD / 86670 Coordination, Boosting Dem Post Open - National 30,000.00 0.00 Canceled 2018-02-11 2018-04-19 2018-07-02 WARE CONTABLE-FINANCIER tions nvelope and, and Management, Moni O toring and Eval uation of the Project. EC-SENESCYT-79214-NC-RF Q / CONTRATACIÓN DEL SER VICIO DE LOGÍSTICA PARA LA Component 2: Improving Pro ORGANIZACIÓN DE EVENTOS grams Relevance, Quality of Request for Quota Single Stage - One E , TALLERES Y REUNIONES PA IBRD / 86670 Post Limited 54,520.71 19,602.50 Signed 2018-10-10 2019-03-29 2018-11-03 2019-04-18 2019-03-03 Teaching and IST Manageme tions nvelope RA LA IMPLEMENTACIÓN, SE nt Capacity. GUIMIENTO Y EVALUACIÓN D EL PLAN DE FORTALECIMIENT O Y REVALORIZACÓN DE LA F ORMACIÓN TÉCNICA Y TECN OLÓGICA EC-SENESCYT-43189-NC-RF Q / CONTRATACIÓN DEL SER VICIO DE LOGÍSTICA PARA LA Component 2: Improving Pro OGANIZACIÓN DE EVENTOS, grams Relevance, Quality of Single Stage - One E TALLERES Y REUNIONES PAR IBRD / 86670 Post Request for Bids Open - National 159,018.74 0.00 Canceled 2018-02-19 2018-03-06 2018-03-21 2018-03-31 2018-04-22 2018-12-15 Teaching and IST Manageme nvelope A LA IMPLEMENTACIÓN, SEG nt Capacity. UIMIENTO Y EVALUACIÓN DE L PLAN DE FORTALECIMIENT O Y REVALORIZACÓN DE LA F ORMACIÓN TÉCNICA Y TECN OLÓGICA. FASE I EC-SENESCYT-79351-NC-RF Component 2: Improving Pro Request for Quota Single Stage - One E Q / LOGÍSTICA PARA EL SEMI IBRD / 86670 grams Relevance, Quality of Post Limited 70,000.00 0.00 Canceled 2018-11-17 2018-12-12 2019-03-02 tions nvelope NARIO DE FORMACIÓN DE FO Teaching and IST Manageme RMADORES nt Capacity. EC-SENESCYT-44810-NC-RF B / CONTRATACIÓN DE SERVI Component 2: Improving Pro CIOS PARA EL DESARROLLO grams Relevance, Quality of Open - Internationa Single Stage - One E IBRD / 86670 Prior Request for Bids 625,200.00 0.00 Canceled 2018-04-16 2018-04-21 2018-06-05 2018-06-15 2018-07-16 2019-07-16 Y LA IMPLEMENTACIÓN DEL S Teaching and IST Manageme l nvelope ISTEMA DE GESTIÓN INTEGR nt Capacity. AL DE EDUCACIÓN SUPERIOR EC-SENESCYT-30888-NC-RF Component 2: Improving Pro B / EJECUCION DE LOS PROG grams Relevance, Quality of Single Stage - One E RAMAS DE CAPACITACION E I IBRD / 86670 Post Request for Bids Open - National 430,309.52 0.00 Canceled 2019-03-01 2019-03-06 2019-04-17 2019-05-17 2019-06-21 2019-12-31 Teaching and IST Manageme nvelope NVESTIGACION DEL CENTRO nt Capacity. DE INVESTIGACION Y CAPACI TACION DOCENTE EC-SENESCYT-120623-NC-RF Component 2: Improving Pro Request for Quota Single Stage - One E Pending Impl Q / LOGÍSTICA PARA EL SEMI IBRD / 86670 grams Relevance, Quality of Post Open - National 95,000.00 0.00 2019-09-21 2019-10-23 2019-11-22 tions nvelope ementation NARIO DE FORMACIÓN DE FO Teaching and IST Manageme RMADORES nt Capacity. EC-SENESCYT-138860-NC-RF Q / LOGÍSTICA PARA LA ORG ANIZACIÓN DE EVENTOS, TA Component 2: Improving Pro LLERES Y REUNIONES PARA L grams Relevance, Quality of Request for Quota Single Stage - One E Pending Impl IBRD / 86670 Post Limited 40,178.88 0.00 2019-10-09 2019-11-02 2020-03-01 A IMPLEMENTACIÓN, SEGUIM Teaching and IST Manageme tions nvelope ementation IENTO Y EVALUACIÓN DEL PL nt Capacity. AN DE FORTALECIMIENTO Y REVALORIZACIÓN DE LA FOR MACIÓN TÉCNICA Y TECNOLÓ GICA EC-SENESCYT-203252-NC-DI R / DATA CENTER VIRTUAL, S ISTEMA DE SEGURIDAD PERI METRAL, SISTEMA DE RESPAL Component 2: Improving Pro DOS, ENLACES DE DATOS E I grams Relevance, Quality of Under Imple IBRD / 86670 Post Direct Selection Direct 1,693,152.40 0.00 2020-11-09 2020-11-13 2020-11-14 2020-11-20 2020-11-30 2021-11-30 NTERNET CON SUS RESPECTI Teaching and IST Manageme mentation VOS COMPONENTES DE ADMI nt Capacity. NISTRACIÓN Y MONITOREO, PARA LA HABILITACIÓN Y PUE STA EN OPERACIÓN DE LOS S ERVICIOS Y COMPONENTES T ECNOLÓGICOS D EC-SENESCYT-295276-NC-DI R / CONTRATACIÓN DE LOS S ERVICIOS DE: DATA CENTER VIRTUAL, SISTEMA DE SEGUR Component 2: Improving Pro IDAD PERIMETRAL, SISTEMA grams Relevance, Quality of Under Imple IBRD / 86670 Post Direct Selection Direct 1,130,720.56 0.00 2022-05-17 2022-05-10 2022-05-19 2022-05-27 2022-12-31 DE RESPALDOS, ENLACES DE Teaching and IST Manageme mentation DATOS E INTERNET CON SUS nt Capacity. RESPECTIVOS COMPONENTE S DE ADMINISTRACIÓN Y MO NITOREO, PARA LA HABILITA CIÓN Y PUESTA EN OPERACIÓ N DE LOS SER EC-SENESCYT-293817-NC-RF Q / PLATAFORMA DE GEO-SE Component 2: Improving Pro GMENTACIÓN, BIG DATA Y M grams Relevance, Quality of Request for Quota Single Stage - One E IBRD / 86670 Post Open - National 34,092.80 0.00 Canceled 2022-05-18 2022-06-18 2022-12-31 ARKETING DE CERCANÍA PAR Teaching and IST Manageme tions nvelope A USUARIOS DE INSTITUTOS nt Capacity. Y CONSERVATORIOS SUPERI ORES PÚBLICOS CONSULTING FIRMS Page 4 Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual EC-SENESCYT-29310-CS-QB S / CONTRATACIÓN DEL SER Component 2: Improving Pro VICIO DE CONSULTORÍA PAR grams Relevance, Quality of Consultant Qualifi Under Implement IBRD / 86670 Post Open - National 168,000.00 0.00 2018-02-01 2019-05-09 2018-02-11 2018-04-16 2018-03-13 2018-03-23 2018-04-17 2018-09-14 A DESARROLLAR JORNADAS Teaching and IST Manageme cation Selection ation DE CAPACITACIÓN SOBRE LA nt Capacity. IMPLEMENTACIÓN DE CARRE RAS DE MODALIDAD DUAL EC-SENESCYT-35439-CS-QC BS / Contratación del servicio Component 3: Strengthening de consultoría para la elabor Mechanisms for Institutional ación de una investigación d Coordination, Boosting Dem Quality And Cost- e necesidades del sector em IBRD / 86670 Post Open - National 495,802.89 409,200.00 Completed 2018-01-25 2018-02-05 2018-02-09 2018-04-05 2018-03-02 2019-03-26 2018-03-07 2019-04-22 2018-03-12 2019-04-24 2018-03-22 2019-05-15 2018-04-06 2019-06-11 2018-10-06 2020-04-23 and, and Management, Moni Based Selection presarial de profesionales de toring and Eval uation of the nivel técnico y tecnológico e Project. n las provincias de Bolívar, El Oro, Guayas, Manabi, Pichinc ha, Sucumbios y Tungurahua EC-SENESCYT-39935-CS-CQ S / CONTRATACION DE SERVI CIOS DE CONSULTORIA PARA Component 1: Optimizing an Consultant Qualifi EL ESTUDIO DE INSTITUTO S IBRD / 86670 d Upgrading the Supply in T Post Open - National 110,000.00 0.00 Canceled 2018-06-15 2018-06-16 2018-07-14 2018-07-23 2018-08-16 2018-12-16 cation Selection UPERIOR TECNOLÓGICO TER argeted Provinces. RITORIAL PROVINCIA DE GU AYAS CIUDAD DURÁN UBIC ADO EN SECAP EC-SENESCYT-31905-CS-CQ S / CONSULTORÍA PARA EL LE VANTAMIENTO DE LAS ESPEC Component 3: Strengthening IFICACIONES TÉCNICAS REQU Mechanisms for Institutional ERIDAS PARA EL DESARROLL Coordination, Boosting Dem Consultant Qualifi IBRD / 86670 Post Open - National 102,600.00 0.00 Canceled 2017-10-27 2017-11-17 2017-12-31 2018-01-30 2018-03-06 2018-06-04 O E IMPLEMENTACIÓN DE UN and, and Management, Moni cation Selection A PLATAFORMA TECNOLÓGIC toring and Eval uation of the A DE GESTIÓN ACADÉMICA, A Project. DMINISTRATIVA Y FINANCIER A PARA LOS INSTITUTOS TÉC NICOS Y TECNOLÓGICOS SUP ERIORES EC-SENESCYT-43382-CS-CQ S / CONSULTORÍA PARA EL DI Component 2: Improving Pro SEÑO DE ESTRATEGIAS E IMP grams Relevance, Quality of Consultant Qualifi IBRD / 86670 Post Open - National 30,299.94 0.00 Canceled 2018-01-23 2018-02-07 2018-02-27 2018-03-02 2018-03-15 2018-12-15 LEMENTACIÓN DE LA PROPU Teaching and IST Manageme cation Selection ESTA DEL MODELO DE GESTI nt Capacity. ÓN EN RED DE LA FORMACIÓ N TÉCNICA Y TECNOLÓGICA EC-SENESCYT-30765-CS-IND V / CONTRATACION DE LO SE RVICIOS DE CONSULTORIA P Component 1: Optimizing an Consultant Qualifi ARA EL ESTUDIO DE INSTITU IBRD / 86670 d Upgrading the Supply in T Post Open - National 85,000.00 0.00 Canceled 2018-02-02 2018-02-05 2018-02-28 2018-03-07 2018-04-09 2018-07-18 cation Selection TO SUPERIOR TECNOLÓGICO argeted Provinces. SECTORIAL DE TURISMO Y PA TRIMONIO UBICADO EN SECA P (COLON) EC-SENESCYT-31907-CS-CQ S / CONSULTORÍA PARA EL DI SEÑO DE LA ESTRATEGIA GE Component 3: Strengthening NERAL DE COMUNICACIÓN Y Mechanisms for Institutional POSICIONAMIENTO DE LA FO Coordination, Boosting Dem Consultant Qualifi IBRD / 86670 Post Open - National 100,116.00 0.00 Canceled 2017-10-17 2017-11-07 2017-12-21 2018-01-20 2018-02-24 2018-05-25 RMACIÓN TÉCNICA Y TECNOL and, and Management, Moni cation Selection ÓGICA A NIVEL NACIONAL QU toring and Eval uation of the E CONSIGA INCENTIVAR LA S Project. ELECCIÓN, POSTULACIÓN, AC EPTACIÓN E INSERCIÓN DE C IUDADANOS EN EL ITINERARI O FORMATIVO EC-SENESCYT-30581-CS-QC BS / CONTRATACIÓN DEL SE RVICIOS DE CONSULTORÍA P Component 2: Improving Pro ARA EL DESARROLLO DE EST grams Relevance, Quality of Quality And Cost- UDIOS DE PERTINENCIA (MAC IBRD / 86670 Post Open - National 312,500.00 0.00 Canceled 2018-11-30 2018-12-10 2018-12-22 2019-01-19 2019-02-03 2019-02-13 2019-03-01 2019-08-28 Teaching and IST Manageme Based Selection ROCURRÍCULOS) DE CARRER nt Capacity. AS DE NIVEL TÉCNICO Y TEC NOLÓGICO EN LOS INSTITUT OS SUPERIORES TÉCNICOS Y TECNOLÓGICOS PÚBLICOS. Component 3: Strengthening EC-SENESCYT-79352-CS-QC Mechanisms for Institutional BS / SERVICIOS DE AUDITORÍ Quality And Cost- IBRD / 86670 Coordination, Boosting Dem Post Open - National 25,000.00 12,000.00 Signed 2018-11-05 2018-10-15 2018-11-20 2018-12-10 2019-02-15 2018-12-15 2019-02-04 2018-12-20 2019-02-15 2018-12-30 2019-03-08 2019-01-14 2019-04-15 2019-05-14 A FINANCIERA DEL PROYECT Based Selection and, and Management, Moni O BANCO MUNDIAL toring and Eval uation of the Project. EC-SENESCYT-31011-CS-CQ S / CONTRATACIÓN DE SERVI CIOS DE CONSULTORÍA PARA Component 3: Strengthening LA ELABORACIÓN DE UN EST Mechanisms for Institutional UDIO DE DIAGNÓSTICO SITU Coordination, Boosting Dem Consultant Qualifi IBRD / 86670 Post Open - National 98,427.95 0.00 Canceled 2018-01-03 2018-02-16 2018-01-17 2018-03-02 2018-03-16 2018-03-29 2018-08-01 ACIONAL SOBRE LA PERCEPC and, and Management, Moni cation Selection IÓN DE LA FORMACIÓN TÉCNI toring and Eval uation of the CA Y TECNOLÓGICA Y EL DIS Project. EÑO DE LA ESTRATÉGICA Y P LAN DE COMUNICACIÓN QUE PERMITA MEJORAR SU POSICI ONAMIENTO(..) EC-SENESCYT-77152-CS-CQ S / CONTRATACIÓN DE SERVI CIOS DE CONSULTORÍA PARA Component 3: Strengthening LA ELABORACIÓN DE UN EST Mechanisms for Institutional UDIO DE DIAGNÓSTICO SITU Coordination, Boosting Dem Consultant Qualifi IBRD / 86670 Post Open - National 87,882.10 77,398.74 Signed 2018-11-15 2018-11-26 2018-11-30 2018-12-22 2019-04-08 2019-01-06 2019-06-12 2019-01-25 2019-06-12 2019-07-24 ACIONAL SOBRE LA PERCEPC and, and Management, Moni cation Selection IÓN DE LA FORMACIÓN TÉCNI toring and Eval uation of the CA Y TECNOLÓGICA Y EL DIS Project. EÑO DE LA ESTRATEGIA Y PL AN DE COMUNICACIÓN QUE PERMITA MEJORAR SU POSICI ONAMIENTO EC-SENESCYT-32836-CS-CQ Component 2: Improving Pro S / CONSULTORÍA PARA LA IM grams Relevance, Quality of Consultant Qualifi IBRD / 86670 Post Open - National 45,000.00 0.00 Canceled 2019-04-01 2019-04-21 2019-05-08 2019-05-15 2019-05-31 2019-08-29 PLEMENTACIÓN DE UN SERVI Teaching and IST Manageme cation Selection CIO DEL MODELO EN RED Y nt Capacity. DESCONCENTRADO Component 3: Strengthening EC-SENESCYT-79353-CS-CQ Mechanisms for Institutional S / ESTUDIO PANORAMA DE L Consultant Qualifi IBRD / 86670 Coordination, Boosting Dem Post Open - National 33,005.03 0.00 Canceled 2018-11-30 2018-12-08 2018-12-14 2018-12-17 2018-12-29 2019-04-28 A EDUCACIÓN TÉCNICA Y PR cation Selection and, and Management, Moni OFESIONAL EN EL ECUADOR toring and Eval uation of the Project. Page 5 EC-SENESCYT-44116-CS-CQ S / FISCALIZACIÓN READECU ACIÓN ARQUITECTÓNICA UR BANÍSTICA Y DE INGENIERÍA Component 1: Optimizing an Consultant Qualifi DE LA INFRAESTRUCTURA EX IBRD / 86670 d Upgrading the Supply in T Post Open - National 146,361.69 0.00 Canceled 2018-10-29 2018-11-19 2019-01-02 2019-01-20 2019-02-05 2019-09-16 cation Selection ISTENTE (SECAP) DESTINADA argeted Provinces. PARA EL FUNCIONAMIENTO D EL INSTITUTO SUPERIOR TEC NOLÓGICO UBICADO EN LA C IUDAD DE AMBATO EC-SENESCYT-30595-CS-QC BS / CONSULTORIA PARA EL Component 2: Improving Pro DISEÑO Y DESARROLLO DE E grams Relevance, Quality of Consultant Qualifi IBRD / 86670 Post Open - National 100,000.00 0.00 Canceled 2019-05-22 2019-06-12 2019-07-26 2019-08-25 2019-09-29 2020-02-16 STRATEGIAS DE IMPLEMENTA Teaching and IST Manageme cation Selection CION DE UN CENTRO DE FOR nt Capacity. MACION E INVESTIGACION TE CNICA Y TECNOLOGICA EC-SENESCYT-30768-CS-IND V / CONTRATACION DE SERVI CIOS DE CONSULTORIA PARA Component 1: Optimizing an Consultant Qualifi LOS ESTUDIOS DE LA OBRA I IBRD / 86670 d Upgrading the Supply in T Post Open - National 85,000.00 0.00 Canceled 2018-03-21 2018-04-11 2018-04-25 2018-04-30 2018-05-19 2018-06-18 cation Selection NSTITUTO SUPERIOR TECNOL argeted Provinces. ÓGICO TERRITORIAL DE TUN GURAHUA CIUDAD AMBATO UBICADO EN SECAP (AMBAT O) EC-SENESCYT-39924-CS-QC BS / FISCALIZACIÓN READEC UACIÓN ARQUITECTÓNICA U RBANÍSTICA Y DE INGENIERÍA Component 1: Optimizing an Quality And Cost- DE LA INFRAESTRUCTURA EX IBRD / 86670 d Upgrading the Supply in T Post Open - National 423,013.10 0.00 Canceled 2018-10-29 2018-11-12 2018-12-25 2019-01-09 2019-01-24 2019-02-10 2019-02-26 2019-12-02 Based Selection ISTENTE (SECAP) DESTINADA argeted Provinces. PARA EL FUNCIONAMIENTO D EL INSTITUTO SUPERIOR TEC NOLÓGICO UBICADO EN LA C IUDAD DE DURÁN EC-SENESCYT-39925-CS-QC BS / FISCALIZACIÓN READEC UACIÓN ARQUITECTÓNICA U Component 1: Optimizing an RBANÍSTICA Y DE INGENIERÍA Quality And Cost- IBRD / 86670 d Upgrading the Supply in T Post Open - National 337,633.78 0.00 Canceled 2019-04-29 2019-05-14 2019-06-08 2019-06-20 2019-07-03 2019-07-29 2019-08-20 2020-05-25 DE LA INFRAESTRUCTURA EX Based Selection argeted Provinces. ISTENTE SECAP - CERFIN (QU ITO NORTE) UBICADO EN EL CANTÓN QUITO, PROVINCIA DE PICHINCHA. EC-SENESCYT-30762-CS-IND V / CONTRATACION DE SERVI Component 1: Optimizing an Consultant Qualifi CIOS DE CONSULTORIA PARA IBRD / 86670 d Upgrading the Supply in T Post Open - National 73,931.28 0.00 Canceled 2018-01-26 2018-01-29 2018-02-21 2018-02-28 2018-04-02 2018-07-11 cation Selection EL ESTUDIO DEL INSTITUTO T argeted Provinces. ERRITORIAL EN LA CIUDAD D E AMBATO EC-SENESCYT-79355-CS-QC Component 1: Optimizing an Quality And Cost- BS / FISCALIZACIÓN CONSTR IBRD / 86670 d Upgrading the Supply in T Post Open - National 416,700.00 0.00 Canceled 2019-11-04 2019-11-25 2019-12-13 2020-01-10 2020-01-16 2020-01-27 2020-02-18 2021-03-14 Based Selection UCCIÓN IST AMBATO argeted Provinces. EC-SENESCYT-79370-CS-CQ S / ESTUDIOS DEFINITIVOS P Component 1: Optimizing an Consultant Qualifi ARA EL DISEÑO ARQUITECTÓ IBRD / 86670 d Upgrading the Supply in T Post Open - National 90,000.00 0.00 Canceled 2019-05-27 2019-06-06 2019-06-28 2019-07-04 2019-08-01 2019-12-04 cation Selection NICO URBANÍSTICO Y DE ING argeted Provinces. ENIERÍAS DEL IST AMBATO EC-SENESCYT-30616-CS-CQ S / CONTRATACIÓN DE SERVI CIOS DE CONSULTORÍA PARA LA ELABORACIÒN E IMPLEME Component 2: Improving Pro NTACIÓN DE UN PLAN DE CA grams Relevance, Quality of Quality And Cost- IBRD / 86670 Post Open - National 175,907.00 0.00 Canceled 2019-01-07 2019-01-28 2019-03-13 2019-04-10 2019-05-10 2019-06-14 2019-07-19 2020-07-18 PACITACIÓN PARA EL FORTAL Teaching and IST Manageme Based Selection ECIMIENTO DE CAPACIDADES nt Capacity. PEDAGÓGICAS PARA DOCEN TES DE INSTITUTOS SUPERIO RES TÉCNICOS Y TECNOLÓGI COS PÚBLICOS DEL ECUADO R EC-SENESCYT-93263-CS-CQ S / ESTUDIOS DE DIAGNÓSTI CO Y PROPUESTA ARQUITECT Component 1: Optimizing an ÓNICA E INGENIERÍAS PARA L Consultant Qualifi IBRD / 86670 d Upgrading the Supply in T Post Open - National 90,000.00 90,040.40 Signed 2019-01-08 2019-01-23 2019-01-18 2019-01-28 2019-01-29 2019-04-19 2019-02-04 2019-05-17 2019-02-20 2019-05-17 2019-07-15 A REPOTENCIACIÓN DEL INST cation Selection argeted Provinces. ITUTO DE EDUCACIÓN SUPER IOR "LUIS ARBOLEDA MARTÍN EZ" UBICADO EN LA CIUDAD DE MANTA, PROVINCIA DE M ANABÍ EC-SENESCYT-79280-CS-CQ S / ESTUDIOS DEFINITIVOS P ARA EL DISEÑO ARQUITECTÓ NICO Y URBANÍSTICO Y DE IN Component 1: Optimizing an Consultant Qualifi GENIERÍAS PARA LOS INSTIT IBRD / 86670 d Upgrading the Supply in T Post Open - National 143,981.02 0.00 Canceled 2018-10-09 2018-10-19 2018-10-30 2018-11-05 2018-11-21 2019-04-15 cation Selection UTOS DE EDUCACIÓN SUPERI argeted Provinces. OR PÚBLICO UBICADOS EN L A CIUDAD DE CHIMBO, PROVI NCIA DE BOLÍVAR Y EN LA CI UDAD DE MACHALA PROVINC IA DE EL ORO EC-SENESCYT-96290-CS-CQ S / ESTUDIOS DEFINITIVOS P ARA EL DISEÑO ARQUITECTÓ Component 1: Optimizing an NICO, URBANÍSTICO Y DE IN Consultant Qualifi IBRD / 86670 d Upgrading the Supply in T Post Open - National 81,350.00 81,340.06 Terminated 2019-01-31 2019-01-29 2019-02-12 2019-03-03 2019-04-19 2019-03-09 2019-04-22 2019-03-30 2019-05-17 2019-07-28 GENIERÍAS PARA EL INSTITUT cation Selection argeted Provinces. O DE EDUCACIÓN SUPERIOR PÚBLICO UBICADO EN LA CIU DAD DE CHIMBO, PROVINCIA DE BOLIVAR EC-SENESCYT-96289-CS-CQ S / ESTUDIOS DEFINITIVOS P ARA EL DISEÑO ARQUITECTÓ Component 1: Optimizing an NICO, URBANÍSTICO Y DE IN Consultant Qualifi IBRD / 86670 d Upgrading the Supply in T Post Open - National 130,500.00 130,000.00 Signed 2019-01-31 2019-01-29 2019-02-12 2019-03-03 2019-04-19 2019-03-09 2019-05-17 2019-03-30 2019-05-17 2019-08-27 GENIERÍAS PARA EL INSTITUT cation Selection argeted Provinces. O DE EDUCACIÓN SUPERIOR PÚBLICO UBICADO EN LA CIU DAD DE MACHALA, PROVINCI A DE EL ORO EC-SENESCYT-96566-CS-CQ S / ESTUDIOS DE DIAGNÓSTI CO Y PROPUESTA ARQUITECT Component 1: Optimizing an ÓNICA Y DE INGENIERÍAS PA Consultant Qualifi IBRD / 86670 d Upgrading the Supply in T Post Open - National 86,550.00 86,500.00 Signed 2019-01-31 2019-01-29 2019-02-12 2019-03-03 2019-04-19 2019-03-09 2019-04-22 2019-03-30 2019-05-17 2019-08-05 RA LA READECUACIÓN DEL I cation Selection argeted Provinces. NSTITUTO DE EDUCACIÓN SU PERIOR UBICADO EN LA CIUD AD DE NUEVA LOJA, PROVINC IA DE SUCUMBÍOS Page 6 EC-SENESCYT-105953-CS-C QS / DESARROLLO E IMPLEM Component 1: Optimizing an Consultant Qualifi ENTACIÓN DEL SISTEMA NAC IBRD / 86670 d Upgrading the Supply in T Post Open - National 95,000.00 95,000.00 Signed 2019-04-10 2019-04-11 2019-04-25 2019-05-14 2019-05-06 2019-05-28 2019-06-18 2019-06-06 2019-06-19 2019-12-03 cation Selection IONAL DE INFORMACIÓN Y G argeted Provinces. ESTIÓN PARA LOS IST (MÓDU LOS) EC-SENESCYT-109843-CS-Q CBS / CONSULTORÍA PARA LA Component 1: Optimizing an Quality And Cost- PERTINENCIA Y VIABILIDAD D IBRD / 86670 d Upgrading the Supply in T Post Open - National 230,000.00 207,844.80 Completed 2019-04-12 2019-04-11 2019-04-22 2019-05-07 2019-06-21 2019-06-01 2019-07-12 2019-06-11 2019-08-16 2019-06-20 2019-08-21 2019-07-09 2019-09-20 2020-03-05 2020-10-15 Based Selection EL IST INTERCULTURAL DE S argeted Provinces. ABERES ANCESTRALES EC-SENESCYT-79274-CS-CQ S / ESTUDIOS Y DISEÑOS AR Component 1: Optimizing an Consultant Qualifi QUITECTÓNICOS Y DE INGENI IBRD / 86670 d Upgrading the Supply in T Post Open - National 57,202.13 64,066.39 Signed 2019-04-25 2019-05-14 2019-05-05 2019-05-20 2019-09-11 2019-05-22 2019-10-15 2019-06-06 2019-11-06 2019-10-04 cation Selection ERÍAS PARA EL IST EN PICHIN argeted Provinces. CHA, QUITO (YAVIRAC) EC-SENESCYT-118608-CS-Q Component 2: Improving Pro CBS / CONSULTORÍA PARA LA grams Relevance, Quality of Quality And Cost- IBRD / 86670 Post Open - National 233,810.25 0.00 Canceled 2019-06-12 2019-06-13 2019-07-02 2019-07-19 2019-08-18 2019-08-25 2019-09-06 2019-09-27 2020-05-04 IMPLEMENTACIÓN DEL MODE Teaching and IST Manageme Based Selection LO DE GESTIÓN EN RED Y DE nt Capacity. SCONCENTRADO EC-SENESCYT-120068-CS-C Component 1: Optimizing an QS / FISCALIZACIÓN DE LA C Consultant Qualifi IBRD / 86670 d Upgrading the Supply in T Post Open - National 89,100.00 0.00 Canceled 2020-02-03 2020-02-18 2020-03-16 2020-04-02 2020-04-26 2020-12-22 ONSTRUCCIÓN DEL IST EN PI cation Selection argeted Provinces. CHINCHA (YAVIRAC) EC-SENESCYT-120236-CS-C QS / ESTUDIOS Y DISEÑOS A Component 1: Optimizing an Consultant Qualifi RQUITECTÓNICOS Y DE INGE IBRD / 86670 d Upgrading the Supply in T Post Open - National 72,676.22 0.00 Canceled 2019-12-16 2019-12-31 2020-01-27 2020-02-13 2020-03-08 2020-08-05 cation Selection NIERÍAS PARA EL IST EN PICH argeted Provinces. INCHA, QUITO (LA MOYA) EC-SENESCYT-80384-CS-QC Component 1: Optimizing an Quality And Cost- BS / FISCALIZACIÓN IST MAC IBRD / 86670 d Upgrading the Supply in T Post Open - National 416,700.00 0.00 Canceled 2019-04-15 2019-05-06 2019-05-24 2019-06-21 2019-06-27 2019-07-08 2019-07-30 2020-08-23 Based Selection HALA argeted Provinces. EC-SENESCYT-79379-CS-QC Component 1: Optimizing an Quality And Cost- BS / FISCALIZACIÓN DE LOS I IBRD / 86670 d Upgrading the Supply in T Post Open - National 363,600.00 0.00 Canceled 2019-06-19 2019-07-04 2019-07-24 2019-08-21 2019-08-31 2019-09-19 2019-10-08 2020-05-05 Based Selection ST LAGO AGRIO, QUITO YAVI argeted Provinces. RAC, CHIMBO EC-SENESCYT-120618-CS-Q Component 2: Improving Pro CBS / DISEÑO DE PROYECTO grams Relevance, Quality of Quality And Cost- Pending Impleme IBRD / 86670 Post Open - National 150,000.00 0.00 2020-06-15 2020-06-30 2020-07-22 2020-08-21 2020-08-29 2020-09-10 2020-10-04 2021-04-02 S DE CARRERAS DE TERCER Teaching and IST Manageme Based Selection ntation Y CUARTO NIVEL TECNOLÓGI nt Capacity. CO EC-SENESCYT-120207-CS-Q Component 1: Optimizing an CBS / FISCALIZACIÓN DE LA Quality And Cost- IBRD / 86670 d Upgrading the Supply in T Post Open - National 447,993.75 0.00 Canceled 2019-10-01 2019-10-16 2019-11-07 2019-12-07 2019-12-15 2019-12-27 2020-01-25 2021-04-04 CONSTRUCCIÓN DEL IST EN Based Selection argeted Provinces. EL ORO, MACHALA EC-SENESCYT-120247-CS-Q Component 1: Optimizing an CBS / FISCALIZACIÓN DE LA Quality And Cost- Open - Internationa IBRD / 86670 d Upgrading the Supply in T Post 503,969.32 0.00 Canceled 2020-08-24 2020-09-08 2020-10-02 2020-11-13 2020-11-21 2020-12-06 2021-01-09 2021-10-06 CONSTRUCCIÓN DEL IST EN Based Selection l argeted Provinces. PICHINCHA, QUITO (LA MOYA ) EC-SENESCYT-120349-CS-Q Component 2: Improving Pro CBS / IMPLEMENTACIÓN DE L grams Relevance, Quality of Quality And Cost- Pending Impleme A ESTRATEGIA DE COMUNICA IBRD / 86670 Post Open - National 400,000.00 0.00 2020-05-04 2020-05-19 2020-06-10 2020-07-10 2020-07-18 2020-07-30 2020-08-28 2021-04-25 Teaching and IST Manageme Based Selection ntation CIÓN ORIENTADO A LA INCLU nt Capacity. SIÓN DE GRUPOS VULNERAB LES EC-SENESCYT-120352-CS-Q CBS / ELABORACIÓN DE UNA Component 3: Strengthening INVESTIGACIÓN DE NECESID Mechanisms for Institutional ADES DEL SECTOR EMPRESA Coordination, Boosting Dem Quality And Cost- Pending Impleme RIAL DE PROFESIONALES DE IBRD / 86670 Post Open - National 316,193.04 0.00 2020-06-15 2020-06-30 2020-07-22 2020-08-21 2020-08-29 2020-09-10 2020-10-09 2021-04-07 and, and Management, Moni Based Selection ntation NIVEL TÉCNICO Y TECNOLÓGI toring and Eval uation of the CO EN LAS PROVINCIAS DE B Project. OLÍVAR, EL ORO, GUAYAS, M ANABÍ, PICHINCHA, SUCUMBÍ OS Y TUNGURAHUA (SEGUND A ETAPA) EC-SENESCYT-120218-CS-Q Component 1: Optimizing an CBS / FISCALIZACIÓN DE LA Quality And Cost- IBRD / 86670 d Upgrading the Supply in T Post Open - National 184,387.50 0.00 Canceled 2019-10-14 2019-10-29 2019-11-20 2019-12-20 2019-12-28 2020-01-09 2020-02-07 2020-10-24 CONSTRUCCIÓN DEL IST EN Based Selection argeted Provinces. BOLÍVAR, CHIMBO EC-SENESCYT-120616-CS-Q Component 2: Improving Pro CBS / DESARROLLO DE PROY grams Relevance, Quality of Quality And Cost- Open - Internationa Under Implement IBRD / 86670 Post 519,972.67 0.00 2019-09-03 2019-09-23 2019-09-18 2019-10-22 2019-10-12 2019-11-11 2019-11-19 2019-12-04 2020-01-02 2020-09-28 ECTOS DE CARRERAS DE NIV Teaching and IST Manageme Based Selection l ation EL TÉCNICO Y TECNOLÓGICO nt Capacity. EN LOS IST EC-SENESCYT-130256-CS-C Component 1: Optimizing an QS / ESTUDIOS Y DISEÑOS A Consultant Qualifi IBRD / 86670 d Upgrading the Supply in T Post Open - National 81,348.82 81,300.00 Signed 2019-09-03 2019-08-30 2019-09-17 2019-10-05 2019-09-25 2019-10-11 2019-10-15 2019-11-08 2019-11-06 2020-03-07 RQUITECTÓNICOS Y DE INGE cation Selection argeted Provinces. NIERÍAS PARA EL IST EN BOLÍ VAR, CHIMBO EC-SENESCYT-120202-CS-Q Component 1: Optimizing an CBS / FISCALIZACIÓN DE LA Quality And Cost- Under Implement IBRD / 86670 d Upgrading the Supply in T Post Open - National 176,441.16 0.00 2019-11-17 2020-03-05 2019-12-02 2020-03-22 2019-12-20 2020-01-19 2020-01-27 2020-02-05 2020-03-02 2020-11-27 CONSTRUCCIÓN DEL IST EN Based Selection ation argeted Provinces. SUCUMBÍOS, LAGO AGRIO EC-SENESCYT-120065-CS-Q Component 1: Optimizing an CBS / FISCALIZACIÓN DE LA Quality And Cost- IBRD / 86670 d Upgrading the Supply in T Post Open - National 200,731.32 0.00 Canceled 2019-11-17 2019-11-05 2019-12-02 2019-12-20 2020-01-19 2020-01-27 2020-02-05 2020-03-02 2020-11-27 CONSTRUCCIÓN DEL IST LUIS Based Selection argeted Provinces. A. MARTÍNEZ DE MANABÍ, MA NTA EC-SENESCYT-160267-CS-Q CBS / FISCALIZACIÓN DE LA Component 1: Optimizing an Quality And Cost- Open - Internationa CONSTRUCCIÓN DEL IST LUIS IBRD / 86670 d Upgrading the Supply in T Prior 520,434.77 0.00 Canceled 2020-02-20 2020-03-18 2020-03-06 2020-03-23 2020-04-15 2020-07-13 2020-05-13 2020-08-13 2020-06-12 2020-08-28 2020-07-06 2020-08-04 2021-06-30 Based Selection l A. MARTÍNEZ DE MANABÍ, MA argeted Provinces. NTA Y EL IST DE EL ORO EN L A CIUDAD DE MACHALA EC-SENESCYT-173827-CS-Q Component 2: Improving Pro CBS / CONSULTORÍA PARA LA grams Relevance, Quality of Quality And Cost- Under Implement ESTIMACIÓN DE COSTOS REF IBRD / 86670 Post Open - National 213,080.00 0.00 2020-05-15 2020-04-29 2020-06-05 2020-07-19 2020-08-16 2020-09-15 2020-10-20 2020-11-24 2021-11-24 Teaching and IST Manageme Based Selection ation ERENCIALES PARA CARRERA nt Capacity. S TÉCNICAS Y TECNOLÓGICA S EC-SENESCYT-183133-CS-C Component 1: Optimizing an QS / FISCALIZACIÓN PARA LA Consultant Qualifi Under Implement IBRD / 86670 d Upgrading the Supply in T Post Open - National 59,686.22 0.00 2020-07-09 2020-07-10 2020-07-24 2020-08-13 2020-08-30 2020-09-20 2021-04-18 CONSTRUCCIÓN DEL IST EN cation Selection ation argeted Provinces. PICHINCHA, QUITO (YAVIRAC) - II ETAPA Page 7 EC-SENESCYT-190108-CS-Q Component 1: Optimizing an CBS / FISCALIZACIÓN DE LA Quality And Cost- IBRD / 86670 d Upgrading the Supply in T Post Open - National 136,799.30 0.00 Canceled 2020-08-26 2020-09-07 2020-09-20 2020-10-18 2020-10-28 2020-11-03 2020-11-27 2021-08-24 CONSTRUCCIÓN DEL IST LUIS Based Selection argeted Provinces. ARBOLEDA MARTÍNEZ DE MA NABÍ, MANTA EC-SENESCYT-190109-CS-Q Component 1: Optimizing an CBS / FISCALIZACIÓN DE LA Quality And Cost- Under Implement IBRD / 86670 d Upgrading the Supply in T Post Open - National 383,635.47 0.00 2020-08-26 2020-08-27 2020-09-07 2023-06-09 2020-09-20 2020-09-18 2020-10-18 2020-10-19 2020-10-28 2020-10-26 2020-11-03 2020-11-09 2020-11-27 2021-10-23 CONSTRUCCIÓN DEL IST DE Based Selection ation argeted Provinces. EL ORO EN LA CIUDAD DE M ACHALA EC-SENESCYT-190564-CS-C Component 1: Optimizing an QS / FISCALIZACIÓN DE LA C Consultant Qualifi Under Implement IBRD / 86670 d Upgrading the Supply in T Post Open - National 136,799.30 0.00 2020-08-27 2020-08-28 2020-09-08 2020-09-18 2020-09-25 2020-10-10 2021-07-07 ONSTRUCCIÓN DEL IST LUIS cation Selection ation argeted Provinces. ARBOLEDA MARTÍNEZ DE MA NABÍ, MANTA EC-SENESCYT-208214-CS-Q CBS / DESARROLLO E IMPLEM Component 2: Improving Pro ENTACIÓN DE UN PLAN DE M grams Relevance, Quality of Quality And Cost- Under Implement EJORA PARA EL PERFECCION IBRD / 86670 Post Open - National 120,000.00 0.00 2020-12-09 2020-12-15 2020-12-24 2021-01-06 2021-02-03 2021-02-18 2021-02-28 2021-03-17 2021-12-15 Teaching and IST Manageme Based Selection ation AMIENTO DE nt Capacity. COMPETENCIAS PARA EL APR ENDIZAJE EN INSTITUTOS SU PERIORES PÚBLICOS EC-SENESCYT-224800-CS-Q Component 2: Improving Pro CBS / CONSULTORÍA PARA EL grams Relevance, Quality of Quality And Cost- Open - Internationa Under Implement FORTALECIMIENTO DE LOS E IBRD / 86670 Post 971,376.00 0.00 2021-03-18 2021-03-18 2021-03-30 2021-04-27 2021-04-14 2021-05-26 2021-06-10 2021-06-16 2021-07-04 2021-12-31 Teaching and IST Manageme Based Selection l ation DUCADORES DEL SISTEMA D nt Capacity. E FORMACIÓN SUPERIOR TÉC NICA Y TECNOLÓGICA EC-SENESCYT-320817-CS-Q CBS / CONSULTORÍA PARA LA Component 2: Improving Pro IMPLEMENTACIÓN DEL PLAN grams Relevance, Quality of Quality And Cost- Under Implement IBRD / 86670 Post Open - National 336,000.00 0.00 2022-10-17 2023-04-28 2022-10-29 2022-11-13 2022-12-11 2022-12-26 2023-01-10 2023-01-31 2023-11-27 DE CAPACITACIÓN VIRTUAL P Teaching and IST Manageme Based Selection ation ARA LOS DOCENTES DE LOS I nt Capacity. NSTITUTOS Y CONSERVATORI OS SUPERIORES PÚBLICOS INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 3: Strengthening EC-SENESCYT-14342-CS-IND Mechanisms for Institutional Individual Consult V / Contratación Especialista IBRD / 86670 Coordination, Boosting Dem Prior Direct 182,280.00 182,280.00 Terminated 2017-05-04 2018-03-07 2017-05-08 2017-05-17 2017-05-09 2018-10-10 2017-05-15 2021-12-31 ant Selection Financiero and, and Management, Moni toring and Eval uation of the Project. Component 3: Strengthening EC-SENESCYT-14343-CS-IND Mechanisms for Institutional Individual Consult V / Contratación Especialista IBRD / 86670 Coordination, Boosting Dem Prior Direct 109,368.00 25,583.16 Terminated 2017-05-04 2018-02-23 2017-05-08 2017-05-17 2017-05-09 2019-01-09 2017-05-15 2017-05-23 2019-12-31 ant Selection de Infraestructura Fìsica and, and Management, Moni toring and Eval uation of the Project. Component 3: Strengthening EC-SENESCYT-14344-CS-IND Mechanisms for Institutional Individual Consult V / Contratación Especialista IBRD / 86670 Coordination, Boosting Dem Prior Direct 109,368.00 109,368.00 Terminated 2017-05-04 2018-02-23 2017-05-08 2017-07-11 2017-05-09 2018-10-03 2017-05-15 2017-08-01 2019-12-31 ant Selection de Adquisiciones and, and Management, Moni toring and Eval uation of the Project. Component 3: Strengthening EC-SENESCYT-19100-CS-IND Mechanisms for Institutional Individual Consult V / Contratación Especialista IBRD / 86670 Coordination, Boosting Dem Post Limited 109,368.00 91,140.00 Terminated 2017-07-12 2017-12-15 2017-07-12 2017-10-26 2017-07-19 2018-01-23 2017-08-01 2018-02-22 2018-01-28 ant Selection de Microplanificación and, and Management, Moni toring and Eval uation of the Project. EC-SENESCYT-19101-CS-IND Component 3: Strengthening V / Contratación Especialista Mechanisms for Institutional Individual Consult Social de Comunidades Indíg IBRD / 86670 Coordination, Boosting Dem Post Open 91,140.00 3,038.00 Terminated 2017-08-08 2017-08-15 2017-09-26 2017-10-31 2017-10-17 2018-04-16 2017-11-21 2020-05-15 ant Selection enas, Nacionalidades y Géne and, and Management, Moni ros (30 meses) toring and Eval uation of the Project. Component 3: Strengthening EC-SENESCYT-24321-CS-IND Mechanisms for Institutional V / Contratación Especialista Individual Consult IBRD / 86670 Coordination, Boosting Dem Post Open 109,368.00 0.00 Canceled 2017-08-08 2017-08-16 2017-09-26 2017-10-17 2017-11-21 2020-10-31 de Microplanificacicón (36 m ant Selection and, and Management, Moni eses) toring and Eval uation of the Project. Component 3: Strengthening EC-SENESCYT-42378-CS-IND Mechanisms for Institutional Individual Consult V / ESPECIALISTA DE INFRAE IBRD / 86670 Coordination, Boosting Dem Prior Limited 198,063.16 0.00 Canceled 2018-01-03 2018-03-07 2018-01-03 2018-01-04 2018-01-06 2021-12-31 ant Selection STRUCTURA FÍSICA and, and Management, Moni toring and Eval uation of the Project. EC-SENESCYT-69067-CS-IND V / CONSULTOR INDIVIDUAL Component 2: Improving Pro PARA EL DISEÑO DEL PROCE grams Relevance, Quality of Individual Consult IBRD / 86670 Post Limited 8,000.00 0.00 Canceled 2018-10-15 2018-10-20 2018-11-10 2018-12-15 2019-08-22 SO DE EVALUACIÓN DE IMPA Teaching and IST Manageme ant Selection CTO DE LAS CAPACITACIONE nt Capacity. S DE FORTALECIMIENTO PED AGÓGICO FASE I Component 3: Strengthening EC-SENESCYT-69083-CS-IND Mechanisms for Institutional V / CONTRATACIÓN DE UN ES Individual Consult IBRD / 86670 Coordination, Boosting Dem Post Limited 94,300.00 93,916.67 Signed 2018-07-18 2018-05-14 2018-07-23 2018-06-25 2018-07-26 2018-08-06 2018-08-06 2018-08-06 2021-12-31 PECIALISTA EN GESTIÓN Y AC ant Selection and, and Management, Moni OMPAÑAMIENTO JURÍDICO toring and Eval uation of the Project. EC-SENESCYT-40575-CS-IND V / CONTRATACIÓN DE UN C Component 3: Strengthening ONSULTOR ESPECIALIZADO P Mechanisms for Institutional ARA LA ACTUALIZACIÓN DEL Coordination, Boosting Dem Individual Consult IBRD / 86670 Post Direct 19,040.00 0.00 Canceled 2018-01-02 2018-01-12 2018-01-27 2018-02-16 2018-06-16 MANUAL OPERATIVO DEL "PR and, and Management, Moni ant Selection OYECTO DE APOYO A LA REC toring and Eval uation of the ONVERSIÓN DE LA EDUCACI Project. ÓN TÉCNICA Y TECNOLÓGICA SUPERIOR PÚBLICA DEL ECU ADOR. EC-SENESCYT-51943-CS-IND V / CONSULTORÍA PARA LA C Component 2: Improving Pro OORDINACIÓN DEL DISEÑO, I grams Relevance, Quality of Individual Consult MPLEMENTACIÓN Y EVALUAC IBRD / 86670 Post Limited 27,053.57 0.00 Canceled 2018-11-01 2018-11-06 2018-11-11 2018-11-30 2019-03-30 Teaching and IST Manageme ant Selection IÓN DEL MODELO DE GESTIÓ nt Capacity. N EN RED Y DESCONCENTRA DO PARA LA FORMACIÓN TÉC NICA Y TECNOLÓGICA. Page 8 Component 3: Strengthening EC-SENESCYT-19099-CS-CD Mechanisms for Institutional Individual Consult S / CONTRATACIÓN ESPECIAL IBRD / 86670 Coordination, Boosting Dem Prior Limited 188,160.00 0.00 Canceled 2018-02-01 2018-04-24 2018-02-06 2018-02-11 2018-02-22 2020-02-02 ant Selection ISTA AMBIENTAL and, and Management, Moni toring and Eval uation of the Project. EC-SENESCYT-26944-CS-IND Component 3: Strengthening V / Contratación de un Especi Mechanisms for Institutional Individual Consult alista de Especialista de Plani IBRD / 86670 Coordination, Boosting Dem Post Limited 151,900.00 0.00 Canceled 2017-11-15 2017-12-07 2017-11-20 2018-01-08 2017-12-11 2018-01-15 2021-12-31 ant Selection ficación, Monitoreo y Evaluac and, and Management, Moni ión del Proyecto Banco Mundi toring and Eval uation of the al Project. EC-SENESCYT-78568-CS-CQ S / ESTUDIOS DE DIAGNÓSTI CO Y PROPUESTA ARQUITECT Component 1: Optimizing an ÓNICA Y DE INGENIERÍAS PA IBRD / 86670 d Upgrading the Supply in T Post Direct Selection Direct 66,700.00 0.00 Canceled 2018-10-05 2018-10-09 2018-10-27 2018-12-26 RA LA READECUACIÓN DEL I argeted Provinces. NSTITUTO DE EDUCACIÓN SU PERIOR UBICADO EN LA CIUD AD DE NUEVA LOJA, PROVINC IA DE SUCUMBÍOS EC-SENESCYT-78815-CS-IND Component 2: Improving Pro V / CONSULTOR PARA EL DIS grams Relevance, Quality of Individual Consult EÑO DE UNA PROPUESTA INT IBRD / 86670 Post Direct 18,000.00 18,000.00 Completed 2018-09-19 2018-06-01 2018-09-25 2018-07-20 2018-09-28 2018-08-06 2018-10-06 2018-08-06 2018-11-20 2018-10-18 Teaching and IST Manageme ant Selection EGRAL DEL SUBSISTEMA DE nt Capacity. FORMACIÓN TÉCNICA Y TECN OLÓGICA EC-SENESCYT-32832-CS-IND Component 2: Improving Pro V / ESTUDIO DE ARTICULACI grams Relevance, Quality of Individual Consult ÓN DE LA EDUCACIÓN TÉCNI IBRD / 86670 Post Direct 13,440.00 0.00 Canceled 2018-01-23 2018-01-24 2018-01-29 2018-02-01 2018-02-09 2018-03-07 Teaching and IST Manageme ant Selection CA Y TECNOLÓGICA EN EL SI nt Capacity. STEMA DE EDUCACIÓN SUPE RIOR EN ECUADOR EC-SENESCYT-80394-CS-IND Component 2: Improving Pro V / CONSULTORIA PARA EL DI grams Relevance, Quality of Individual Consult SEÑO DE EVALUACION DE IM IBRD / 86670 Post Direct 7,000.00 0.00 Canceled 2019-03-01 2019-03-11 2019-03-16 2019-04-04 2019-07-03 Teaching and IST Manageme ant Selection PACTO DE LAS CAPACITACIO nt Capacity. NES DE FORTALECIMIENTO P EDAGOGICO FASE II Component 3: Strengthening EC-SENESCYT-42377-CS-IND Mechanisms for Institutional Individual Consult V / ESPECIALISTA DE GESTIÓ IBRD / 86670 Coordination, Boosting Dem Prior Limited 198,063.16 0.00 Canceled 2018-01-03 2018-04-03 2018-01-03 2018-01-04 2018-01-07 2022-01-04 ant Selection N FINANCIERA and, and Management, Moni toring and Eval uation of the Project. Component 3: Strengthening Mechanisms for Institutional EC-SENESCYT-73839-CS-IND Individual Consult IBRD / 86670 Coordination, Boosting Dem Post Limited 120,000.00 109,800.00 Signed 2018-08-13 2018-10-17 2018-08-18 2018-10-19 2018-08-23 2018-12-13 2018-09-03 2018-12-13 2021-12-31 V / ESPECIALISTA AMBIENTAL ant Selection and, and Management, Moni toring and Eval uation of the Project. EC-SENESCYT-73840-CS-IND Component 3: Strengthening V / ESPECIALISTA SOCIAL DE Mechanisms for Institutional Individual Consult COMUNIDADES DE PUEBLOS IBRD / 86670 Coordination, Boosting Dem Post Limited 120,000.00 99,900.00 Signed 2018-10-10 2018-09-03 2018-10-15 2018-11-05 2018-11-05 2018-11-30 2018-12-10 2018-11-30 2022-02-27 ant Selection INDÍGENAS, NACIONALIDADE and, and Management, Moni S Y GÉNEROS toring and Eval uation of the Project. Component 3: Strengthening EC-SENESCYT-73841-CS-IND Mechanisms for Institutional Individual Consult V / ESPECIALISTA DE ADQUISI IBRD / 86670 Coordination, Boosting Dem Post Limited 154,200.00 154,200.00 Signed 2018-08-13 2022-01-14 2018-08-18 2018-05-29 2018-09-08 2018-06-29 2018-10-13 2018-06-29 2021-12-31 ant Selection CIONES and, and Management, Moni toring and Eval uation of the Project. Component 3: Strengthening EC-SENESCYT-73842-CS-IND Mechanisms for Institutional Individual Consult V / ESPECIALISTA EN MICROP IBRD / 86670 Coordination, Boosting Dem Post Limited 120,000.00 0.00 Canceled 2018-08-13 2018-08-18 2018-09-08 2018-10-13 2021-12-31 ant Selection LANIFICACIÓN and, and Management, Moni toring and Eval uation of the Project. Component 3: Strengthening EC-SENESCYT-73843-CS-IND Mechanisms for Institutional Individual Consult V / ESPECIALISTA DE INFRAE IBRD / 86670 Coordination, Boosting Dem Post Limited 147,600.00 147,600.00 Signed 2018-08-13 2018-06-20 2018-08-13 2018-06-25 2018-08-14 2018-08-06 2018-08-16 2018-08-06 2021-12-31 ant Selection STRUCTURA and, and Management, Moni toring and Eval uation of the Project. Component 3: Strengthening EC-SENESCYT-73844-CS-IND Mechanisms for Institutional V / ESPECIALISTA EN PLANIFI Individual Consult IBRD / 86670 Coordination, Boosting Dem Post Limited 140,000.00 129,500.00 Signed 2018-08-13 2018-06-20 2018-08-18 2018-07-09 2018-09-08 2018-11-30 2018-10-13 2018-11-30 2021-12-31 CACIÓN, MONITOREO Y EVAL ant Selection and, and Management, Moni UACIÓN toring and Eval uation of the Project. Component 3: Strengthening EC-SENESCYT-32834-CS-IND Mechanisms for Institutional Individual Consult V / ESPECIALISTA COORDINA IBRD / 86670 Coordination, Boosting Dem Post Limited 163,400.00 162,766.67 Signed 2017-12-01 2018-05-29 2017-12-06 2018-05-29 2017-12-27 2018-06-29 2018-01-31 2018-06-29 2021-12-31 ant Selection DOR DEL PROYECTO and, and Management, Moni toring and Eval uation of the Project. Component 3: Strengthening EC-SENESCYT-94108-CS-IND Mechanisms for Institutional V / CONTRATACIÓN DEL ESPE Individual Consult IBRD / 86670 Coordination, Boosting Dem Post Limited 154,200.00 154,200.00 Signed 2019-01-10 2022-01-14 2019-01-11 2018-05-29 2019-01-12 2018-06-05 2019-01-15 2018-06-05 2023-01-12 CIALISTA EN GESTIÓN FINAN ant Selection and, and Management, Moni CIERA. toring and Eval uation of the Project. Component 3: Strengthening EC-SENESCYT-96491-CS-IND Mechanisms for Institutional V / ESPECIALISTA SOCIAL DE Individual Consult IBRD / 86670 Coordination, Boosting Dem Post Limited 96,600.00 96,660.00 Completed 2019-01-24 2018-09-03 2019-01-29 2018-12-03 2019-02-19 2018-12-17 2019-03-26 2018-12-17 2022-06-13 2020-02-07 COMUNIDADES DE PUEBLOS ant Selection and, and Management, Moni INDIGENAS Y GENEROS. toring and Eval uation of the Project. Component 3: Strengthening EC-SENESCYT-120351-CS-IN Mechanisms for Institutional Individual Consult Under Implement DV / ESPECIALISTA DE MICRO IBRD / 86670 Coordination, Boosting Dem Post Limited 87,000.00 0.00 2019-08-05 2019-09-02 2019-08-10 2019-08-13 2019-08-30 2021-12-31 ant Selection ation PLANIFICACIÓN and, and Management, Moni toring and Eval uation of the Project. Component 3: Strengthening EC-SENESCYT-120353-CS-Q Mechanisms for Institutional Under Implement CBS / AUDITORÍA FINANCIER IBRD / 86670 Coordination, Boosting Dem Post Direct Selection Direct 43,000.00 0.00 2019-10-14 2019-11-04 2019-10-22 2019-11-13 2019-11-07 2021-12-31 ation A BM 2019-2021 and, and Management, Moni toring and Eval uation of the Project. EC-SENESCYT-120600-CS-C Component 1: Optimizing an DS / LEVANTAMIENTO DE RE IBRD / 86670 d Upgrading the Supply in T Post Direct Selection Direct 12,000.00 0.00 Canceled 2019-08-01 2019-08-09 2019-08-24 2019-11-22 QUERIMIENTOS Y CONDICION argeted Provinces. ES DE OPERACIÓN SIGA EN L OS IST Page 9 EC-SENESCYT-120619-CS-C Component 2: Improving Pro DS / DISEÑO E IMPLEMENTAC grams Relevance, Quality of Pending Impleme IÓN DEL SISTEMA INTEGRAL IBRD / 86670 Post Direct Selection Direct 1,144,000.00 0.00 2019-09-16 2019-10-04 2019-12-02 2020-12-26 Teaching and IST Manageme ntation DE FORMACIÓN E INVESTIGA nt Capacity. CIÓN TÉCNICA Y TECNOLÓGI CA EC-SENESCYT-150125-CS-IN Component 3: Strengthening DV / CONSULTOR INDIVIDUAL Mechanisms for Institutional PARA EVALUACIÓN DE IMPAC Coordination, Boosting Dem Individual Consult Under Implement TO EN EL MARCO DE LAS CO IBRD / 86670 Post Limited 67,320.00 0.00 2019-12-12 2019-10-15 2019-12-17 2019-11-26 2019-12-20 2020-01-06 2022-05-09 and, and Management, Moni ant Selection ation NSULTORÍAS IMPLEMENTADA toring and Eval uation of the S EN LA SUBSECRETARÍA DE Project. FORMACIÓN TÉCNICA Y TECN OLÓGICA Component 3: Strengthening EC-SENESCYT-150127-CS-IN Mechanisms for Institutional DV / ESPECIALISTA EN MERC Individual Consult IBRD / 86670 Coordination, Boosting Dem Post Limited 73,920.00 42,873.60 Signed 2019-12-12 2019-10-22 2019-12-17 2019-11-26 2019-12-20 2019-12-12 2020-01-06 2019-12-14 2022-05-09 ADO LABORAL ECUATORIAN ant Selection and, and Management, Moni O toring and Eval uation of the Project. EC-SENESCYT-162869-CS-IN Component 3: Strengthening DV / CONTRATACIÓN DEL ES Mechanisms for Institutional Individual Consult PECIALISTA SOCIAL, DE COM IBRD / 86670 Coordination, Boosting Dem Post Limited 72,600.00 9,020.00 Signed 2020-03-04 2022-01-14 2020-03-09 2020-02-28 2020-03-30 2020-03-09 2020-05-04 2020-03-10 2023-07-23 ant Selection UNIDADES DE PUEBLOS INDÍ and, and Management, Moni GENAS, NACIONALIDADES Y toring and Eval uation of the GÉNERO Project. Component 3: Strengthening EC-SENESCYT-162872-CS-IN Mechanisms for Institutional DV / CONTRATACIÓN DEL ES Individual Consult IBRD / 86670 Coordination, Boosting Dem Post Limited 79,800.00 10,766.67 Signed 2020-03-04 2020-02-03 2020-03-09 2020-02-26 2020-03-30 2020-03-06 2020-05-04 2020-03-07 2024-04-03 PECIALISTA COORDINADOR D ant Selection and, and Management, Moni EL PROYECTO toring and Eval uation of the Project. Component 3: Strengthening EC-SENESCYT-162877-CS-IN Mechanisms for Institutional DV / CONTRATACIÓN DE ESP Individual Consult Under Implement IBRD / 86670 Coordination, Boosting Dem Post Limited 16,200.00 0.00 2020-03-04 2020-02-03 2020-03-09 2020-03-12 2020-03-29 2022-07-31 ECIALISTA EN PERTINENCIA D ant Selection ation and, and Management, Moni E CARRERAS toring and Eval uation of the Project. Component 3: Strengthening EC-SENESCYT-162880-CS-IN Mechanisms for Institutional Individual Consult Under Implement DV / CONTRATACIÓN DE ESP IBRD / 86670 Coordination, Boosting Dem Post Limited 16,200.00 0.00 2020-03-04 2020-02-03 2020-03-09 2020-03-12 2020-03-29 2022-07-31 ant Selection ation ECIALISTA CURRICULAR and, and Management, Moni toring and Eval uation of the Project. EC-SENESCYT-162881-CS-IN Component 3: Strengthening DV / CONTRATACIÓN DE DIE Mechanisms for Institutional Individual Consult Under Implement Z (10) TÉCNICOS CONSULTO IBRD / 86670 Coordination, Boosting Dem Post Limited 12,555.00 0.00 2020-03-04 2020-06-18 2020-03-09 2020-03-12 2020-03-29 2022-07-31 ant Selection ation RES DE PROYECTO DE CARRE and, and Management, Moni RA toring and Eval uation of the Project. EC-SENESCYT-162886-CS-IN Component 3: Strengthening DV / CONTRATACIÓN DE ESP Mechanisms for Institutional ECIALISTA PARA LA GESTIÓN Coordination, Boosting Dem Individual Consult IBRD / 86670 Post Limited 66,000.00 0.00 Under Review 2020-03-04 2020-03-06 2020-03-09 2020-03-12 2020-03-29 2022-07-31 Y MONITOREO DE LOS ÓRGA and, and Management, Moni ant Selection NOS CONSULTIVOS PROVINCI toring and Eval uation of the ALES DE LA FORMACIÓN TÉC Project. NICA Y TECNOLÓGICA Component 3: Strengthening EC-SENESCYT-168846-CS-IN Mechanisms for Institutional DV / CONTRATACIÓN DE UN Individual Consult Under Implement IBRD / 86670 Coordination, Boosting Dem Post Limited 72,128.00 0.00 2020-04-15 2019-10-01 2020-04-20 2020-04-23 2020-05-04 2023-09-29 CONSULTOR ESPECIALISTA JU ant Selection ation and, and Management, Moni RÍDICO toring and Eval uation of the Project. EC-SENESCYT-173455-CS-IN Component 3: Strengthening DV / CONTRATACIÓN DE ESP Mechanisms for Institutional Individual Consult ECIALISTA EN MERCADO LAB IBRD / 86670 Coordination, Boosting Dem Post Limited 45,582.19 0.00 Under Review 2020-05-15 2020-05-27 2020-05-20 2020-05-23 2020-06-09 2022-10-11 ant Selection ORAL ECUATORIANO Y FORM and, and Management, Moni ACIÓN PROFESIONAL toring and Eval uation of the Project. Component 3: Strengthening EC-SENESCYT-183812-CS-IN Mechanisms for Institutional Individual Consult Pending Impleme DV / ESPECIALISTA DE PLANI IBRD / 86670 Coordination, Boosting Dem Post Limited 38,571.44 0.00 2020-07-12 2020-07-15 2020-07-20 2020-08-06 2021-12-31 ant Selection ntation FICACIÓN and, and Management, Moni toring and Eval uation of the Project. EC-SENESCYT-184674-CS-C DS / EVALUACIÓN DE COMPE Component 2: Improving Pro TENCIAS PARA EL APRENDIZ grams Relevance, Quality of Under Implement AJE A TRAVÉS DE LA PRUEBA IBRD / 86670 Post Direct Selection Direct 200,000.00 0.00 2020-07-20 2020-08-12 2020-07-28 2020-08-22 2021-04-03 Teaching and IST Manageme ation DESCAES A SER APLICADA A nt Capacity. ESTUDIANTES Y DOCENTES D E INSTITUTOS SUPERIORES P ÚBLICOS Component 3: Strengthening EC-SENESCYT-193697-CS-IN Mechanisms for Institutional Individual Consult Under Implement DV / ESPECIALISTA DE INFRA IBRD / 86670 Coordination, Boosting Dem Post Limited 34,500.00 0.00 2020-09-14 2020-09-17 2020-09-17 2020-09-22 2020-09-24 2021-12-31 ant Selection ation ESTRUCTURA FÍSICA and, and Management, Moni toring and Eval uation of the Project. Component 3: Strengthening EC-SENESCYT-200754-CS-IN Mechanisms for Institutional Individual Consult Under Implement DV / ESPECIALISTA AMBIENT IBRD / 86670 Coordination, Boosting Dem Post Limited 32,500.00 0.00 2020-10-22 2020-11-09 2020-10-23 2020-10-26 2020-11-10 2021-12-31 ant Selection ation AL DEL PRETT and, and Management, Moni toring and Eval uation of the Project. EC-SENESCYT-204164-CS-IN DV / ESPECIALISTA LÍDER DE Component 2: Improving Pro PROYECTO PARA DESARROLL grams Relevance, Quality of Individual Consult IBRD / 86670 Post Limited 25,704.74 0.00 Canceled 2020-11-23 2020-11-13 2020-11-26 2020-12-01 2020-12-20 2021-12-15 O DE LA SEGUNDA FASE DEL Teaching and IST Manageme ant Selection SISTEMA INTEGRADO DE GES nt Capacity. TIÓN ACADÉMICA DE INSTITU TOS SUPERIORES PÚBLICOS EC-SENESCYT-204168-CS-IN DV / ESPECIALISTA DESARRO Component 2: Improving Pro LLADOR DE SOFTWARE PARA grams Relevance, Quality of Individual Consult Under Implement IBRD / 86670 Post Limited 16,796.40 0.00 2020-11-23 2021-11-05 2020-11-26 2020-12-01 2020-12-20 2021-12-15 EL DESARROLLO DE LA SEGU Teaching and IST Manageme ant Selection ation NDA FASE DEL SISTEMA INTE nt Capacity. GRADO DE GESTIÓN ACADÉ MICA DE INSTITUTOS EC-SENESCYT-204170-CS-IN DV / ESPECIALISTA DESARRO Component 2: Improving Pro LLADOR DE SOFTWARE PARA grams Relevance, Quality of Individual Consult Under Implement IBRD / 86670 Post Limited 16,796.40 0.00 2020-11-23 2021-11-05 2020-11-26 2020-12-01 2020-12-20 2021-12-15 EL DESARROLLO DE LA SEGU Teaching and IST Manageme ant Selection ation NDA FASE DEL SISTEMA INTE nt Capacity. GRADO DE GESTIÓN ACADÉ MICA DE INSTITUTOS Page 10 EC-SENESCYT-204172-CS-IN DV / ESPECIALISTA DESARRO Component 2: Improving Pro LLADOR DE SOFTWARE PARA grams Relevance, Quality of Individual Consult Under Implement IBRD / 86670 Post Limited 16,796.40 0.00 2020-11-23 2021-11-05 2020-11-26 2020-12-01 2020-12-20 2021-12-15 EL DESARROLLO DE LA SEGU Teaching and IST Manageme ant Selection ation NDA FASE DEL SISTEMA INTE nt Capacity. GRADO DE GESTIÓN ACADÉ MICA DE INSTITUTOS EC-SENESCYT-204173-CS-IN DV / ESPECIALISTA DESARRO Component 2: Improving Pro LLADOR DE SOFTWARE PARA grams Relevance, Quality of Individual Consult Under Implement IBRD / 86670 Post Limited 16,796.40 0.00 2020-11-23 2021-11-05 2020-11-26 2020-12-01 2020-12-20 2021-12-15 EL DESARROLLO DE LA SEGU Teaching and IST Manageme ant Selection ation NDA FASE DEL SISTEMA INTE nt Capacity. GRADO DE GESTIÓN ACADÉ MICA DE INSTITUTOS EC-SENESCYT-204174-CS-IN DV / ESPECIALISTA DE BASE Component 2: Improving Pro DE DATOS PARA ANÁLISIS, D grams Relevance, Quality of Individual Consult Under Implement IBRD / 86670 Post Limited 21,718.32 0.00 2020-11-23 2020-11-13 2020-11-26 2020-12-01 2020-12-20 2021-12-15 ESARROLLO E IMPLEMENTACI Teaching and IST Manageme ant Selection ation ÓN DE LAS BASES DE DATOS nt Capacity. DE LOS SISTEMAS DE EDUCA CIÓN SUPERIOR EC-SENESCYT-204175-CS-IN DV / ESPECIALISTA DE BASE Component 2: Improving Pro DE DATOS PARA ANÁLISIS, D grams Relevance, Quality of Individual Consult Under Implement IBRD / 86670 Post Limited 21,718.32 0.00 2020-11-23 2020-11-13 2020-11-26 2020-12-01 2020-12-20 2021-12-15 ESARROLLO E IMPLEMENTACI Teaching and IST Manageme ant Selection ation ÓN DE LAS BASES DE DATOS nt Capacity. DE LOS SISTEMAS DE EDUCA CIÓN SUPERIOR EC-SENESCYT-204176-CS-IN DV / ANALISTA DE BASE DE D Component 2: Improving Pro ATOS PARA ANÁLISIS, DESAR grams Relevance, Quality of Individual Consult Under Implement IBRD / 86670 Post Limited 18,811.97 0.00 2020-11-23 2020-11-13 2020-11-26 2020-12-01 2020-12-20 2021-12-15 ROLLO E IMPLEMENTACIÓN D Teaching and IST Manageme ant Selection ation E LAS BASES DE DATOS DE L nt Capacity. OS SISTEMAS DE EDUCACIÓN SUPERIOR EC-SENESCYT-231190-CS-IN DV / ESPECIALISTA DE INFRA Component 2: Improving Pro ESTRUCTURA PARA ADMINIS grams Relevance, Quality of Individual Consult Under Implement TRAR Y GESTIONAR LOS IBRD / 86670 Post Open 20,270.43 0.00 2021-05-06 2021-06-07 2021-05-28 2021-06-02 2021-06-26 2021-12-23 Teaching and IST Manageme ant Selection ation RECURSOS INFORMATICOS D nt Capacity. E LA PLATAFORMA TECNOLO GICA DE LOS INSTITUTOS EC-SENESCYT-231191-CS-IN DV / ESPECIALISTA DE INFRA Component 2: Improving Pro ESTRUCTURA PARA ADMINIS grams Relevance, Quality of Individual Consult Under Implement TRAR Y GESTIONAR LOS IBRD / 86670 Post Open 20,270.43 0.00 2021-05-06 2021-06-07 2021-05-28 2021-06-02 2021-06-26 2021-12-23 Teaching and IST Manageme ant Selection ation RECURSOS INFORMATICOS D nt Capacity. E LA PLATAFORMA TECNOLO GICA DE LOS INSTITUTOS EC-SENESCYT-231192-CS-IN Component 2: Improving Pro Individual Consult Under Implement DV / ESPECIALISTA EN GÉNE IBRD / 86670 grams Relevance, Quality of Post Open 14,478.88 0.00 2021-05-06 2021-06-07 2021-05-28 2021-06-02 2021-06-26 2021-12-23 ant Selection ation RO Teaching and IST Manageme nt Capacity. Component 3: Strengthening EC-SENESCYT-234533-CS-IN Mechanisms for Institutional Individual Consult Pending Impleme DV / ESPECIALISTA DE INFRA IBRD / 86670 Coordination, Boosting Dem Post Limited 20,000.00 0.00 2021-05-14 2021-05-17 2021-05-27 2021-06-13 2021-12-31 ant Selection ntation ESTRUCTURA FÍSICA and, and Management, Moni toring and Eval uation of the Project. EC-SENESCYT-234536-CS-IN DV / TÉCNICO CONSULTOR JU Component 2: Improving Pro RÍDICO PARA EL FORTALECIM grams Relevance, Quality of Individual Consult Under Implement IBRD / 86670 Post Open 14,500.00 0.00 2021-05-18 2021-06-03 2021-06-06 2021-06-23 2021-12-31 IENTO DE LA GESTIÓN ACAD Teaching and IST Manageme ant Selection ation ÉMICA Y ADMINISTRATIVA DE nt Capacity. INSTITUTOS Y CONSERVATOR IOS SUPERIORES EC-SENESCYT-234537-CS-IN DV / TÉCNICO CONSULTOR JU Component 2: Improving Pro RÍDICO PARA EL FORTALECIM grams Relevance, Quality of Individual Consult Under Implement IBRD / 86670 Post Open 14,500.00 0.00 2021-05-18 2021-06-07 2021-06-03 2021-06-06 2021-06-23 2021-12-31 IENTO DE LA GESTIÓN ACAD Teaching and IST Manageme ant Selection ation ÉMICA Y ADMINISTRATIVA DE nt Capacity. INSTITUTOS Y CONSERVATOR IOS SUPERIORES EC-SENESCYT-242127-CS-IN Component 3: Strengthening DV / ESPECIALISTA EN GESTI Mechanisms for Institutional Individual Consult Under Implement ON Y ACOMPAÑAMIENTO JURI IBRD / 86670 Coordination, Boosting Dem Post Open 14,394.38 0.00 2021-07-05 2021-07-20 2021-07-16 2021-07-19 2021-08-04 2021-12-31 ant Selection ation DICO DE LOS CONTRATOS DE and, and Management, Moni L PRETT toring and Eval uation of the Project. Component 3: Strengthening EC-SENESCYT-242131-CS-IN Mechanisms for Institutional Individual Consult Under Implement DV / ESPECIALISTA EN MICRO IBRD / 86670 Coordination, Boosting Dem Post Open 14,394.38 0.00 2021-07-05 2021-07-20 2021-07-16 2021-07-19 2021-08-04 2021-12-31 ant Selection ation PLANIFICACIÓN and, and Management, Moni toring and Eval uation of the Project. EC-SENESCYT-242143-CS-IN Component 3: Strengthening DV / ESPECIALISTA PARA LA Mechanisms for Institutional GESTIÓN Y MONITOREO DE L Coordination, Boosting Dem Individual Consult Under Implement IBRD / 86670 Post Open 14,394.38 0.00 2021-07-05 2021-07-20 2021-07-16 2021-07-19 2021-08-23 2021-12-31 OS ÓRGANOS CONSULTIVOS and, and Management, Moni ant Selection ation PROVINCIALES DE LA FORMA toring and Eval uation of the CIÓN TÉCNICA Y TECNOLÓGI Project. CA Component 3: Strengthening EC-SENESCYT-255428-CS-IN Mechanisms for Institutional Individual Consult Under Implement DV / CONSULTOR ESPECIALIS IBRD / 86670 Coordination, Boosting Dem Post Open 35,985.94 0.00 2021-10-04 2021-10-31 2021-10-23 2021-10-27 2021-11-12 2022-12-31 ant Selection ation TA COORDINADOR and, and Management, Moni toring and Eval uation of the Project. Component 3: Strengthening EC-SENESCYT-255430-CS-IN Mechanisms for Institutional DV / ESPECIALISTA DE PLANI Individual Consult Under Implement IBRD / 86670 Coordination, Boosting Dem Post Open 35,985.94 0.00 2021-10-04 2021-10-31 2021-10-14 2021-10-19 2021-11-04 2022-12-31 FICACIÓN, MONITOREO Y EVA ant Selection ation and, and Management, Moni LUACIÓN toring and Eval uation of the Project. EC-SENESCYT-262599-CS-IN DV / ESPECIALISTA LÍDER DE PROYECTO PARA IMPLEMENT Component 2: Improving Pro ACIÓN DE LA PRIMERA FASE grams Relevance, Quality of Individual Consult IBRD / 86670 Post Open 17,136.16 0.00 Canceled 2021-11-15 2021-10-19 2021-11-30 2021-12-01 2021-12-18 2022-06-16 Y DESARROLLO DE LA SEGUN Teaching and IST Manageme ant Selection DA FASE DEL SISTEMA INTEG nt Capacity. RADO DE GESTIÓN ACADÉMI CA DE INSTITUTOS SUPERIOR ES PÚBLICOS Page 11 Component 3: Strengthening EC-SENESCYT-277867-CS-C Mechanisms for Institutional DS / ESPECIALISTA EN GESTI Under Implement IBRD / 86670 Coordination, Boosting Dem Post Direct Selection Direct 29,000.00 0.00 2022-02-10 2022-02-09 2022-02-12 2022-02-15 2022-12-31 ÓN FINANCIERA DEL PROYEC ation and, and Management, Moni TO toring and Eval uation of the Project. Component 3: Strengthening EC-SENESCYT-277871-CS-C Mechanisms for Institutional Under Implement DS / ESPECIALISTA SOCIAL D IBRD / 86670 Coordination, Boosting Dem Post Direct Selection Direct 29,000.00 0.00 2022-02-10 2022-02-09 2022-02-12 2022-02-15 2022-12-31 ation EL PROYECTO and, and Management, Moni toring and Eval uation of the Project. Component 3: Strengthening EC-SENESCYT-277873-CS-C Mechanisms for Institutional DS / ESPECIALISTA EN ADQUI IBRD / 86670 Coordination, Boosting Dem Prior Direct Selection Direct 29,000.00 27,189.37 Signed 2022-02-10 2022-02-09 2022-02-12 2022-03-07 2022-02-15 2022-03-08 2022-12-31 SICIONES and, and Management, Moni toring and Eval uation of the Project. Component 3: Strengthening EC-SENESCYT-278446-CS-C Mechanisms for Institutional Under Implement DS / AUDITORIA FINANCIERA IBRD / 86670 Coordination, Boosting Dem Post Direct Selection Direct 14,336.00 0.00 2022-03-08 2022-01-31 2022-03-14 2022-03-31 2022-05-30 ation BM PERIODO 2021 and, and Management, Moni toring and Eval uation of the Project. EC-SENESCYT-283262-CS-C DS / IMPLEMENTACIÓN DEL P Component 2: Improving Pro LAN DE CAPACITACIÓN VIRTU grams Relevance, Quality of Under Implement IBRD / 86670 Post Direct Selection Direct 335,916.00 0.00 2022-03-17 2022-05-20 2022-03-27 2022-04-18 2022-12-31 AL PARA LOS DOCENTES DE Teaching and IST Manageme ation LOS INSTITUTOS Y CONSERV nt Capacity. ATORIOS SUPERIORES PÚBLI COS EC-SENESCYT-288671-CS-C DS / ESPECIALISTA DE INFRA Component 2: Improving Pro ESTRUCTURA PARA ADMINIS grams Relevance, Quality of Under Implement IBRD / 86670 Post Direct Selection Direct 24,324.52 0.00 2022-04-06 2022-04-08 2022-04-09 2022-04-16 2022-12-31 TRAR Y GESTIONAR LOS REC Teaching and IST Manageme ation URSOS INFORMATICOS DE LA nt Capacity. PLATAFORMA TECNOLOGICA DE LOS INSTITUTOS NUEVO EC-SENESCYT-288672-CS-C DS / ESPECIALISTA DE INFRA Component 2: Improving Pro ESTRUCTURA PARA ADMINIS grams Relevance, Quality of Under Implement IBRD / 86670 Post Direct Selection Direct 24,324.52 0.00 2022-04-06 2022-04-08 2022-04-09 2022-04-16 2022-12-31 TRAR Y GESTIONAR LOS REC Teaching and IST Manageme ation URSOS INFORMATICOS DE LA nt Capacity. PLATAFORMA TECNOLOGICA DE LOS INSTITUTOS NUEVO EC-SENESCYT-288673-CS-C DS / ANALISTA DE BASE DE D Component 2: Improving Pro ATOS PARA ANÁLISIS, DESAR grams Relevance, Quality of Under Implement IBRD / 86670 Post Direct Selection Direct 18,811.97 0.00 2022-04-06 2022-04-08 2022-04-09 2022-04-16 2022-12-31 ROLLO E IMPLEMENTACIÓN D Teaching and IST Manageme ation E LAS BASES DE DATOS DE L nt Capacity. OS SISTEMAS DE EDUCACIÓN SUPERIOR NUEVO EC-SENESCYT-288675-CS-C DS / ESPECIALISTA DE BASE Component 2: Improving Pro DE DATOS PARA ANÁLISIS, D grams Relevance, Quality of Under Implement IBRD / 86670 Post Direct Selection Direct 24,324.52 0.00 2022-04-06 2022-04-08 2022-04-09 2022-04-16 2022-12-31 ESARROLLO E IMPLEMENTACI Teaching and IST Manageme ation ÓN DE LAS BASES DE DATOS nt Capacity. DE LOS SISTEMAS DE EDUCA CIÓN SUPERIOR NUEVO EC-SENESCYT-288676-CS-C DS / ESPECIALISTA DE BASE Component 2: Improving Pro DE DATOS PARA ANÁLISIS, D grams Relevance, Quality of Under Implement IBRD / 86670 Post Direct Selection Direct 24,324.52 0.00 2022-04-06 2022-04-08 2022-04-09 2022-04-16 2022-12-31 ESARROLLO E IMPLEMENTACI Teaching and IST Manageme ation ÓN DE LAS BASES DE DATOS nt Capacity. DE LOS SISTEMAS DE EDUCA CIÓN SUPERIOR NUEVO EC-SENESCYT-293801-CS-IN Component 2: Improving Pro Individual Consult Under Implement DV / ESPECIALISTA LÍDER SE IBRD / 86670 grams Relevance, Quality of Post Open 16,795.00 0.00 2022-05-09 2022-05-13 2022-05-23 2022-05-24 2022-06-10 2022-12-31 ant Selection ation GUIMIENTO ACADÉMICO Teaching and IST Manageme nt Capacity. EC-SENESCYT-302409-CS-IN DV / ESPECIALISTA DE BASE Component 2: Improving Pro DE DATOS PARA ANÁLISIS, D grams Relevance, Quality of Individual Consult Under Implement IBRD / 86670 Post Open 12,162.26 0.00 2022-07-04 2022-07-19 2022-07-20 2022-07-22 2022-08-06 2022-12-31 ESARROLLO E IMPLEMENTACI Teaching and IST Manageme ant Selection ation ÓN DE LAS BASES DE DATOS nt Capacity. DE LOS SISTEMAS DE EDUCA CIÓ SUPERIOR EC-SENESCYT-302410-CS-IN DV / ESPECIALISTA DE BASE Component 2: Improving Pro DE DATOS PARA ANÁLISIS, D grams Relevance, Quality of Individual Consult Under Implement IBRD / 86670 Post Open 12,162.26 0.00 2022-07-04 2022-07-19 2022-07-20 2022-07-22 2022-08-06 2022-12-31 ESARROLLO E IMPLEMENTACI Teaching and IST Manageme ant Selection ation ÓN DE LAS BASES DE DATOS nt Capacity. DE LOS SISTEMAS DE EDUCA CIÓN SUPERIOR Component 3: Strengthening EC-SENESCYT-288798-CS-IN Mechanisms for Institutional Individual Consult DV / ESPECIALISTA AMBIENT IBRD / 86670 Coordination, Boosting Dem Post Open 19,192.50 0.00 Canceled 2022-04-07 2022-04-16 2022-04-19 2022-05-05 2022-12-31 ant Selection AL DEL PRETT and, and Management, Moni toring and Eval uation of the Project. Component 3: Strengthening Mechanisms for Institutional EC-SENESCYT-277877-CS-C IBRD / 86670 Coordination, Boosting Dem Post Direct Selection Direct 29,000.00 0.00 Canceled 2022-02-10 2022-02-09 2022-02-12 2022-02-15 2022-12-31 DS / ESPECIALISTA JURIDICO and, and Management, Moni toring and Eval uation of the Project. Component 3: Strengthening Mechanisms for Institutional EC-SENESCYT-305598-CS-IN Individual Consult Under Implement IBRD / 86670 Coordination, Boosting Dem Post Limited 11,996.00 0.00 2022-07-27 2022-08-10 2022-07-30 2022-07-31 2022-08-15 2022-12-31 DV / ESPECIALISTA JURÍDICO ant Selection ation and, and Management, Moni toring and Eval uation of the Project. Component 3: Strengthening EC-SENESCYT-305599-CS-IN Mechanisms for Institutional DV / ESPECIALISTA DE INFRA Individual Consult Under Implement IBRD / 86670 Coordination, Boosting Dem Post Limited 11,996.00 0.00 2022-07-27 2022-07-31 2022-07-30 2022-07-31 2022-08-15 2022-12-31 ESTRUCTURA Y MONITOREO ant Selection ation and, and Management, Moni DE OBRAS toring and Eval uation of the Project. Component 3: Strengthening EC-SENESCYT-305594-CS-IN Mechanisms for Institutional Individual Consult Under Implement DV / ESPECIALISTA AMBIENT IBRD / 86670 Coordination, Boosting Dem Post Limited 11,996.00 0.00 2022-07-27 2022-07-27 2022-07-28 2022-07-31 2022-08-15 2022-12-31 ant Selection ation AL and, and Management, Moni toring and Eval uation of the Project. Page 12 EC-SENESCYT-320820-CS-IN DV / TÉCNICO CONSULTOR JU Component 2: Improving Pro RÍDICO PARA EL FORTALECIM grams Relevance, Quality of Individual Consult Under Implement IBRD / 86670 Post Open - National 21,947.30 0.00 2022-10-21 2023-02-15 2022-11-06 2022-11-09 2022-11-26 2022-12-31 IENTO DE LA GESTIÓN ACAD Teaching and IST Manageme ant Selection ation ÉMICA Y ADMINISTRATIVA DE nt Capacity. INSTITUTOS Y CONSERVATOR IOS SUPERIORES EC-SENESCYT-320823-CS-IN DV / TÉCNICO CONSULTOR JU Component 2: Improving Pro RÍDICO PARA EL FORTALECIM grams Relevance, Quality of Individual Consult Under Implement IBRD / 86670 Post Open - National 21,947.30 0.00 2022-10-21 2023-02-15 2022-11-06 2022-11-09 2022-11-26 2022-12-31 IENTO DE LA GESTIÓN ACAD Teaching and IST Manageme ant Selection ation ÉMICA Y ADMINISTRATIVA DE nt Capacity. INSTITUTOS Y CONSERVATOR IOS SUPERIORES Component 3: Strengthening EC-SENESCYT-339407-CS-C Mechanisms for Institutional Under Implement DS / AUDITORÍA FINANCIERA IBRD / 86670 Coordination, Boosting Dem Post Direct Selection Direct - National 14,336.00 0.00 2023-02-20 2023-02-27 2023-02-26 2023-03-15 2023-05-14 ation BM 2022 and, and Management, Moni toring and Eval uation of the Project. Component 3: Strengthening EC-SENESCYT-337878-CS-C Mechanisms for Institutional Individual Consult Under Implement DS / ESPECIALISTA DE ADQUI IBRD / 86670 Coordination, Boosting Dem Prior Direct - National 26,400.00 0.00 2023-02-10 2023-02-28 2023-02-12 2023-02-15 2023-02-19 2023-11-30 ant Selection ation SICIONES and, and Management, Moni toring and Eval uation of the Project. Component 3: Strengthening Mechanisms for Institutional EC-SENESCYT-337901-CS-C Individual Consult Under Implement IBRD / 86670 Coordination, Boosting Dem Post Direct - National 26,400.00 0.00 2023-02-10 2023-02-15 2023-02-12 2023-02-15 2023-02-19 2023-11-30 DS / ESPECIALISTA JURÍDICO ant Selection ation and, and Management, Moni toring and Eval uation of the Project. Component 3: Strengthening EC-SENESCYT-337880-CS-C Mechanisms for Institutional Individual Consult Under Implement DS / ESPECIALISTA EN GESTI IBRD / 86670 Coordination, Boosting Dem Post Direct - National 26,400.00 0.00 2023-02-10 2023-03-10 2023-02-12 2023-02-15 2023-02-19 2023-11-30 ant Selection ation ÓN FINANCIERA and, and Management, Moni toring and Eval uation of the Project. Component 3: Strengthening EC-SENESCYT-337898-CS-C Mechanisms for Institutional Individual Consult DS / ESPECIALISTA AMBIENTA IBRD / 86670 Coordination, Boosting Dem Post Direct - National 26,400.00 0.00 Canceled 2023-02-10 2023-02-12 2023-02-15 2023-02-19 2023-11-30 ant Selection L and, and Management, Moni toring and Eval uation of the Project. Component 3: Strengthening EC-SENESCYT-337899-CS-C Mechanisms for Institutional DS / ESPECIALISTA DE INFRA Individual Consult Under Implement IBRD / 86670 Coordination, Boosting Dem Post Direct - National 26,400.00 0.00 2023-02-10 2023-02-15 2023-02-12 2023-02-15 2023-02-19 2023-11-30 ESTRUCTURA Y MONITOREO ant Selection ation and, and Management, Moni DE OBRAS toring and Eval uation of the Project. Component 3: Strengthening Mechanisms for Institutional EC-SENESCYT-337882-CS-C Individual Consult Under Implement IBRD / 86670 Coordination, Boosting Dem Post Direct - National 26,400.00 0.00 2023-02-10 2023-02-15 2023-02-12 2023-02-15 2023-02-19 2023-11-30 DS / ESPECIALISTA SOCIAL ant Selection ation and, and Management, Moni toring and Eval uation of the Project. Component 3: Strengthening EC-SENESCYT-345405-CS-IN Mechanisms for Institutional Individual Consult Under Implement DV / ESPECIALISTA AMBIENT IBRD / 86670 Coordination, Boosting Dem Post Open - National 26,400.00 0.00 2023-02-28 2023-03-10 2023-03-14 2023-03-16 2023-04-01 2023-11-30 ant Selection ation AL and, and Management, Moni toring and Eval uation of the Project. EC-SENESCYT-345407-CS-IN Component 2: Improving Pro Individual Consult Under Implement DV / ESPECIALISTA LÍDER SE IBRD / 86670 grams Relevance, Quality of Post Open - National 19,192.50 0.00 2023-02-28 2023-03-10 2023-03-14 2023-03-16 2023-04-01 2023-11-30 ant Selection ation GUIMIENTO ACADÉMICO Teaching and IST Manageme nt Capacity. Component 3: Strengthening EC-SENESCYT-349335-CS-IN Mechanisms for Institutional DV / ESPECIALISTA DE PLANI Individual Consult Under Implement IBRD / 86670 Coordination, Boosting Dem Post Direct - National 20,850.00 0.00 2023-03-20 2023-03-21 2023-03-23 2023-03-25 2023-03-27 2023-11-30 FICACIÓN, MONITORIO Y EVA ant Selection ation and, and Management, Moni LUACIÓN toring and Eval uation of the Project. Component 3: Strengthening Mechanisms for Institutional EC-SENESCYT-349338-CS-IN Individual Consult Under Implement IBRD / 86670 Coordination, Boosting Dem Post Direct - National 20,850.00 0.00 2023-03-20 2023-03-28 2023-03-23 2023-03-25 2023-03-27 2023-11-30 DV / ESPECIALISTA JURÍDICO ant Selection ation and, and Management, Moni toring and Eval uation of the Project. EC-SENESCYT-356318-CS-IN DV / ESPECIALISTA DE INFRA Component 2: Improving Pro ESTRUCTURA PARA ADMINIS grams Relevance, Quality of Individual Consult Under Implement IBRD / 86670 Post Direct - National 20,270.45 0.00 2023-05-08 2023-05-10 2023-05-11 2023-05-14 2023-05-16 2023-12-31 TRAR Y GESTIONAR LOS REC Teaching and IST Manageme ant Selection ation URSOS INFORMÁTICOS DE LA nt Capacity. PLATAFORMA TECNOLÓGICA DE LOS INSTITUTOS 2 EC-SENESCYT-362740-CS-IN DV / ESPECIALISTA DE BASE Component 2: Improving Pro DE DATOS PARA ANÁLISIS, D grams Relevance, Quality of Individual Consult Under Implement IBRD / 86670 Post Direct - National 22,297.50 0.00 2023-05-22 2023-05-29 2023-05-26 2023-05-27 2023-05-30 2023-11-30 ESARROLLO E IMPLEMENTACI Teaching and IST Manageme ant Selection ation ÓN DE LAS BASES DE DATOS nt Capacity. DE LOS SISTEMAS DE EDUCA CIÓN SUPERIOR 2 EC-SENESCYT-362741-CS-IN DV / ESPECIALISTA DE BASE Component 2: Improving Pro DE DATOS PARA ANÁLISIS, D grams Relevance, Quality of Individual Consult Under Implement IBRD / 86670 Post Direct - National 22,297.50 0.00 2023-05-22 2023-06-07 2023-05-26 2023-05-27 2023-05-30 2023-11-30 ESARROLLO E IMPLEMENTACI Teaching and IST Manageme ant Selection ation ÓN DE LAS BASES DE DATOS nt Capacity. DE LOS SISTEMAS DE EDUCA CIÓN SUPERIOR 2 EC-SENESCYT-362742-CS-IN DV / ESPECIALISTA DESARRO Component 2: Improving Pro LLADOR DE SOFTWARE PARA grams Relevance, Quality of Individual Consult Pending Impleme IBRD / 86670 Post Direct - National 15,396.70 0.00 2023-05-22 2023-05-26 2023-05-27 2023-05-30 2023-11-30 EL DESARROLLO DE LA SEGU Teaching and IST Manageme ant Selection ntation NDA FASE DEL SISTEMA INTE nt Capacity. GRADO DE GESTIÓN ACADÉ MICA DE INSTITUTOS 2 EC-SENESCYT-362743-CS-IN DV / ESPECIALISTA DESARRO Component 2: Improving Pro LLADOR DE SOFTWARE PARA grams Relevance, Quality of Individual Consult Pending Impleme IBRD / 86670 Post Direct - National 15,396.70 0.00 2023-05-22 2023-05-26 2023-05-27 2023-05-30 2023-11-30 EL DESARROLLO DE LA SEGU Teaching and IST Manageme ant Selection ntation NDA FASE DEL SISTEMA INTE nt Capacity. GRADO DE GESTIÓN ACADÉ MICA DE INSTITUTOS 2 Page 13 PROCUREMENT PLAN (Textual Part) Information sur le Projet : CBLT/Projet : Projet de Relance et de Développement de la Région du Lac Tchad (PROLAC) – Financement IDA Agence d’exécution du Projet : Secrétariat Exécutif de la Commission du Bassin du Lac Tchad Date du plan de passation des marchés : 06 avril 2020 Période couverte par ce plan de passation des marchés : Juin 2020 – Décembre 2021 Préambule Conformément au paragraphe 5.9 du “Règlement de Passation des Marchés pour les Emprunteurs sollicitant le Financement de Projets d’Investissement (FPI)” (Juillet 2016) (“Règlement de Passation des Marchés”) le Système électronique de la Banque de suivi systématique des transactions de marchés publics (STEP) sera utilisé pour préparer, valider et actualiser les plans de passation des marchés et effectuer toutes les transactions liées à la passation des marchés du projet. Ce texte ainsi que les tableaux du plan de passation des marchés présents dans STEP constituent le plan de passation des marchés du projet. Les conditions suivantes s'appliquent à toutes les activités de passation de marchés du plan de passation de marchés. Les autres éléments du plan de passation des marchés tels que requis au paragraphe 4.4 du Règlement de passation des marchés sont énoncés dans STEP. Les Dossiers types de passation des marchés publics de la Banque devront être utilisés pour tous les contrats soumis à la concurrence internationale, ainsi que pour tous les autres contrats soumis à cette obligation telle que spécifiée dans les tableaux du plan de passation des marchés de STEP. Procédures nationales de passation des marchés : En accord avec le paragraphe 5.3 du Règlement de passation des marchés, dans le cas où la procédure de passation des marchés se fera au niveau local (telle que spécifiée dans les tableaux du plan de passation des marchés inclus de STEP), les procédures de passation des marchés décrites dans le Manuel de Procédures Administratives, Financières et Comptables pourront être utilisées. Si l’Emprunteur utilise ses propres procédures d’appel d’offres ouvert telles qu’énoncées dans son Manuel de Procédures Administratives, Financières et Comptables, ces arrangements sont soumis aux dispositions du paragraphe 5.4 du Règlement de passation des marchés et aux conditions suivantes : Les dispositions à respecter pour un appel d’offres/à propositions ouvert sont les suivantes : a. le dossier d’appel d’offres/à propositions oblige le Soumissionnaire/Proposant présentant une Offre/Proposition à déposer un agrément signé, qui sera joint à tout contrat éventuel, pour confirmer qu’il applique et respecte les Directives de la Banque pour la lutte contre la corruption, y compris sans limitation, le droit de la Banque de sanctionner et les droits de la Banque pour l’inspection et l’audit ; b. Les documents de passation des marchés incluent des dispositions, convenues avec la Banque, destinées à atténuer de manière adéquate les risques et impacts environnementaux, sociaux (y compris l'exploitation et les abus sexuels et la violence basée sur le genre), l’hygiène et la sécurité (« ESHS ») ; c. les droits de la Banque d’examiner le dossier et les activités de passation des marchés ; d. l’existence d’un mécanisme efficace d’examen des plaintes ; et e. la gestion et l’archivage des dossiers relatifs au Processus de la Passation des Marchés. Les autres modalités de passation des marchés (autres que sous forme d’appel d’offres/à propositions ouvert) qui pourraient être appliquées par l’Emprunteur (appel d’offres limité/restreint, demande de prix/consultation de fournisseurs, entente directe) doivent être conformes avec les Principes Fondamentaux de Passation des Marchés de la Banque et garantir que les Directives de la Banque contre la corruption, son Cadre de Sanctions et les recours contractuels visés dans l’Accord Juridique s’appliquent. Crédit-bail tel que spécifié au paragraphe 5.10 du Règlement de Passation des marchés : Le crédit-bail peut être utilisé pour les contrats indiqués comme tel dans le Plan de passation des marchés. « Sans objet » Achat de biens d’occasion tel que spécifié au paragraphe 5.11 du Règlement de Passation des Marchés est autorisé pour les contrats indiqués comme tel dans le Plan de passation des marchés. « Sans objet » Préférence nationale telle que spécifiée au paragraphe 5.51 du Règlement de Passation des Marchés (Fournitures et Travaux). - Fournitures : ne s’applique pas - Travaux : ne s’applique pas L’Assistance directe à la mise en œuvre (sigle HEIS en anglais) tel que précisée aux paragraphes 3.10 et 3.11 du Règlement de Passation des marchés s’applique. « Sans objet » Autres informations pertinentes sur la passation des marchés « Sans objet » PROCUREMENT Western and Central Africa : Lake Chad Region Recovery and Development Project PLAN General Information Country: Western and Central Africa 2020-08-12 Bank’s Approval Date of the Original Procurement Plan: 2023-06-01 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P161706 GPN Date: 2021-07-27 Project Name: Lake Chad Region Recovery and Development Project Loan / Credit No: IDA / V3280, IDA / D6340, IDA / 66440, IDA / D6350, IDA / D6330 Strategy for Development and Security Agency Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned NE-SDS-187246-CW-RFB / Mi Component 1: Regional Lake se à niveau technologique de Chad Knowledge and Monito Single Stage - One E 2022-03-2 l'Université de Diffa (forage é IDA / V3280 ring Platform and Secretariat Post Request for Bids Open - National 295,000.00 0.00 Canceled 2021-06-02 2021-06-07 2021-07-19 2021-08-18 2021-09-22 nvelope 1 quipé sur les sites d'expérim for the Development of the L etation, matériaux de travau ake Chad Reg ion x pratiques) NE-SDS-187223-CW-RFB / C Component 3: Strengthening Single Stage - One E 2022-03-0 onstruction du comptoir de p IDA / D6340 the Recovery of Agricultural Post Request for Bids Open - National 255,000.00 0.00 Canceled 2021-05-17 2021-05-22 2021-07-03 2021-08-02 2021-09-06 nvelope 5 oisson Livelihoods NE-SDS-187225-CW-RFB / R Component 3: Strengthening Single Stage - One E 2022-03-0 éhabilitation de marchés rura IDA / V3280 the Recovery of Agricultural Post Request for Bids Open - National 455,000.00 0.00 Canceled 2021-05-17 2021-05-22 2021-07-03 2021-08-02 2021-09-06 nvelope 5 ux Livelihoods NE-SDS-187259-CW-RFB / C Component 3: Strengthening onstruction/réhabiitation des Single Stage - One E 2022-05-2 IDA / V3280 the Recovery of Agricultural Post Request for Bids Open - National 364,000.00 0.00 Canceled 2021-08-04 2021-08-09 2021-09-20 2021-10-20 2021-11-24 magasins de stockage au niv nvelope 3 Livelihoods eau des sites de production NE-SDS-187240-CW-RFB / Cl Component 3: Strengthening Single Stage - One E 2022-05-2 ôture en grillage des sites m IDA / V3280 the Recovery of Agricultural Post Request for Bids Open - National 1,018,000.00 0.00 Canceled 2021-08-04 2021-08-09 2021-09-20 2021-10-20 2021-11-24 nvelope 3 araichers ou des cutvettes Livelihoods Component 1: Regional Lake NE-SDS-187252-CW-RFB / C Chad Knowledge and Monito Single Stage - One E 2022-05-2 onstruction de bassins de sto IDA / V3280 Post Request for Bids Open - National 454,000.00 0.00 Canceled 2021-08-04 2021-08-09 2021-09-20 2021-10-20 2021-11-24 ring Platform and Secretariat nvelope 3 ckage d'eau for the Development of the L ake Chad Reg ion NE-SDS-187199-CW-RFB / R Component 3: Strengthening Single Stage - One E 2022-01-2 éalisation de forages maraich IDA / V3280 the Recovery of Agricultural Post Request for Bids Open - National 329,000.00 0.00 Canceled 2021-04-08 2020-12-03 2021-04-13 2021-05-25 2021-06-24 2021-07-29 nvelope 5 ers Livelihoods NE-SDS-187261-CW-RFB / In Component 3: Strengthening stallation et gestion des rése Single Stage - One E 2022-05-2 IDA / V3280 the Recovery of Agricultural Post Request for Bids Open - National 764,000.00 0.00 Canceled 2021-08-04 2021-08-09 2021-09-20 2021-10-20 2021-11-24 aux californien et autres syst nvelope 3 Livelihoods ème de gestion d'eau NE-SDS-187209-CW-RFB / In Component 3: Strengthening Single Stage - One E 2022-05-2 stallation et gestion des syst IDA / V3280 the Recovery of Agricultural Post Request for Bids Open - National 1,591,000.00 0.00 Canceled 2021-08-04 2021-08-09 2021-09-20 2021-10-20 2021-11-24 nvelope 3 ème solaires pour les petites Livelihoods irrigations NE-SDS-187237-CW-RFB / C Component 3: Strengthening Single Stage - One E 2021-12-1 onstruction des ouvrages de IDA / V3280 the Recovery of Agricultural Post Request for Bids Open - National 3,800,000.00 0.00 Canceled 2021-03-01 2021-03-06 2021-04-17 2021-05-17 2021-06-21 nvelope 8 protection des terres agricole Livelihoods s et d'habitation NE-SDS-187250-CW-RFB / R Component 2: Restoring Sus Open - Internationa Single Stage - One E 22,910,000.0 2021-06-0 éhabilitation de 140 km des t IDA / V3280 tainable Rural Mobility and C Prior Request for Bids 0.00 Canceled 2020-08-19 2020-08-24 2020-10-05 2020-11-04 2020-12-09 l nvelope 0 7 ronçons de routes rurales onnectivity Component 2: Restoring Sus NE-SDS-187272-CW-RFB / Tr Request for Quota Single Stage - One E 2021-04-2 IDA / V3280 tainable Rural Mobility and C Post Open - National 54,500.00 0.00 Canceled 2020-08-31 2020-10-26 aitement des points critiques tions nvelope 4 onnectivity NE-SDS-282886-CW-RFB / R Request for Bids - Component 3: Strengthening éaliser les travaux d'aménag Single Stage - One E Works French Civi Under Imple 2023-02-0 IDA / 66440 the Recovery of Agricultural Post Request for Bids Open - National 2,231,182.00 0.00 2022-04-15 2022-05-12 2022-04-20 2022-06-01 2022-06-23 2022-07-01 2022-08-08 2022-08-05 ement de 18 sites des cuvett nvelope l Law (French) SP mentation 1 Livelihoods es dans la commune de Mai D né Soroa National Procure NE-SDS-283313-CW-RFB / R Component 3: Strengthening ment Document - éaliser les travaux d'aménag Single Stage - One E Under Imple 2023-03-1 IDA / 66440 the Recovery of Agricultural Post Request for Bids Open - National 1 Envelope proce 3,718,636.00 0.00 2022-05-25 2022-05-12 2022-05-30 2022-07-11 2022-06-22 2022-08-10 2022-08-09 2022-09-14 ement de 30 sites des cuvett nvelope mentation 3 Livelihoods ss (Non Bank-SPD es dans la commune de Gou ) doumaria National Procure NE-SDS-285307-CW-RFB / tr Component 3: Strengthening ment Document - Single Stage - One E Under Imple 2023-02-1 avaux de réalisation des fora IDA / 66440 the Recovery of Agricultural Post Request for Bids Open - National 1 Envelope proce 1,417,918.00 0.00 2022-04-25 2022-05-12 2022-04-30 2022-06-11 2022-06-30 2022-07-11 2022-09-24 2022-08-15 nvelope mentation 1 ges des SPP Livelihoods ss (Non Bank-SPD ) National Procure NE-SDS-282933-CW-RFB / Tr Component 3: Strengthening ment Document - Single Stage - One E Under Imple 2023-02-1 avaux de réalisation/réhabilit IDA / 66440 the Recovery of Agricultural Post Request for Bids Open - National 1 Envelope proce 1,461,000.00 0.00 2022-05-02 2022-05-02 2022-05-07 2022-06-18 2022-06-24 2022-07-18 2022-08-22 nvelope mentation 8 ation des puits cimentés Livelihoods ss (Non Bank-SPD ) NE-SDS-314490-CW-RFB / Tr Request for Bids - Component 2: Restoring Sus avaux de Constructions/Amé Single Stage - One E Small Works SPD Under Imple 2023-07-1 IDA / 66440 tainable Rural Mobility and C Post Request for Bids Open - National 708,252.00 0.00 2022-12-23 2022-12-15 2022-12-28 2023-02-08 2023-02-14 2023-03-10 2023-04-14 nagement de Bâtiments et d’ nvelope (1 envelope proce mentation 3 onnectivity Infrastructures à l'UDA. ss) NE-SDS-325820-CW-RFQ / Tr Request for Quota avaux d’aménagement de de Component 3: Strengthening Request for Quota Single Stage - One E tions - Small Work Under Imple 2023-08-2 ux (2) sites maraichers de 10 IDA / 66440 the Recovery of Agricultural Post Limited 200,000.00 0.00 2023-01-02 2022-12-29 2023-02-27 tions nvelope s (Emergency) SP mentation 6 ha dans les cuvettes de Babo Livelihoods D -Competitive ulwa (5 ha) et Lawan Adjiri ( 5 ha) Request for Bids - NE-SDS-342180-CW-RFB / Tr Component 2: Restoring Sus Works – Roads (O avaux de réhabilitation/réalis Open - Internationa Single Stage - One E 20,090,909.0 Pending Imp 2024-11-2 IDA / 66440 tainable Rural Mobility and C Prior Request for Bids utput and Perform 0.00 2023-02-20 2023-02-25 2023-03-27 2023-04-26 2023-05-31 ation des pistes rurales dans l nvelope 0 lementation 1 onnectivity ance Based Road la Région de Diffa Contracts) SPD NE-SDS-361635-CW-RFQ / Tr avaux d’aménagement de tr Request for Quota Component 3: Strengthening ois (3) sites maraichers de 9 Request for Quota Single Stage - One E tions - Small Work Pending Imp 2024-02-2 IDA / 66440 the Recovery of Agricultural Post Limited 200,000.00 0.00 2023-07-06 2023-08-31 ha dans les cuvettes de Konk tions nvelope s (Emergency) SP lementation 7 Livelihoods orimaram (3 ha), Djangomar D -Competitive am (3 ha),Bariram Koura (3 h a) ; Page 1 NE-SDS-361636-CW-RFQ / Tr avaux d’aménagement de tr Request for Quota Component 3: Strengthening ois (3) sites maraichers de 9 Request for Quota Single Stage - One E tions - Small Work Pending Imp 2024-02-2 IDA / 66440 the Recovery of Agricultural Post Limited 200,000.00 0.00 2023-07-06 2023-08-31 ha dans les cuvettes de Kano tions nvelope s (Emergency) SP lementation 7 Livelihoods mari (Gutilla) (3 ha), Katafour D -Competitive oram (3 ha) et Walaram (3 h a). NE-SDS-361638-CW-RFQ / Tr Request for Quota avaux d’aménagement de de Component 3: Strengthening Request for Quota Single Stage - One E tions - Small Work Pending Imp 2024-02-2 ux (2) sites maraichers de 6 IDA / 66440 the Recovery of Agricultural Post Limited 190,000.00 0.00 2023-07-08 2023-09-02 tions nvelope s (Emergency) SP lementation 9 ha dans les cuvettes de Koji Livelihoods D -Competitive méri Koura (3 ha), et Djidji G adoua (3 ha). NE-SDS-187244-CW-RFB / C Component 3: Strengthening Single Stage - One E 2022-10-2 onstruction de banques d'intr IDA / V3280 the Recovery of Agricultural Post Request for Bids Open - National 212,000.00 0.00 Canceled 2022-01-10 2022-01-15 2022-02-26 2022-03-28 2022-05-02 nvelope 9 ants agricoles Livelihoods NE-SDS-187267-CW-RFB / R Component 3: Strengthening éalisation/réhabilitation des p Single Stage - One E 2022-09-0 IDA / V3280 the Recovery of Agricultural Post Request for Bids Open - National 3,000,000.00 0.00 Canceled 2021-11-15 2021-11-20 2022-01-01 2022-01-31 2022-03-07 oints d'eau pastoraux et stati nvelope 3 Livelihoods ons de pompage Component 3: Strengthening NE-SDS-187260-CW-RFB / St Single Stage - One E 2022-09-2 IDA / V3280 the Recovery of Agricultural Post Request for Bids Open - National 4,113,000.00 0.00 Canceled 2021-12-04 2021-12-09 2022-01-20 2022-02-19 2022-03-26 abilisation des dunes vives nvelope 2 Livelihoods National Procure NE-SDS-277355-CW-RFB / R Component 3: Strengthening ment Document - ecruter des entreprises pour Single Stage - One E 2023-02-1 IDA / 66440 the Recovery of Agricultural Post Request for Bids Open - National 1 Envelope proce 1,336,363.00 0.00 Canceled 2022-05-02 2022-05-07 2022-06-18 2022-07-18 2022-08-22 la réalisation des travaux de nvelope 8 Livelihoods ss (Non Bank-SPD fonçage de 7 stations de po ) mpage et 40 puits GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NE-SDS-187211-GO-RFQ / Ac Component 4: Project Manag Request for Quota Single Stage - One E quisition de logiciel de suivi-é IDA / V3280 Post Open - National 30,000.00 0.00 Canceled 2020-09-06 2020-11-01 2021-04-30 ement tions nvelope valuation NE-SDS-187258-GO-RFB / Ac Component 4: Project Manag Single Stage - One E Under Imple IDA / V3280 Post Request for Bids Open - National 128,000.00 0.00 2020-08-18 2021-05-31 2020-08-23 2020-10-04 2021-07-06 2020-11-03 2020-12-08 2021-06-06 quisition de groupe électrogè ement nvelope mentation ne NE-SDS-187192-GO-RFQ / Ac Component 4: Project Manag Request for Quota Single Stage - One E quisition de logiciel comptabl IDA / V3280 Post Open - National 40,000.00 0.00 Canceled 2020-09-06 2020-11-01 2021-04-30 ement tions nvelope e de gestion financière NE-SDS-187271-GO-RFB / Ac Component 1: Regional Lake quisition de fournitures et éq Chad Knowledge and Monito Open - Internationa Single Stage - One E IDA / V3280 Post Request for Bids 618,000.00 0.00 Canceled 2020-08-26 2020-08-31 2020-10-12 2020-11-11 2020-12-16 2021-06-14 uipement pour le compte de l ring Platform and Secretariat l nvelope 'Université de Diffa for the Development of the L ake Chad Reg ion NE-SDS-187266-GO-RFB / Ac Component 4: Project Manag Request for Quota Single Stage - One E IDA / V3280 Post Open - National 250,000.00 475,464.40 Completed 2020-08-24 2021-04-16 2020-10-19 2021-07-28 2021-04-17 2021-09-03 quisition de véhicules ement tions nvelope NE-SDS-187248-GO-RFQ / Ac Component 4: Project Manag Request for Quota Single Stage - One E Pending Impl quisition des équipement inf IDA / V3280 Post Open - National 80,000.00 0.00 2020-08-23 2020-10-18 2021-04-16 ement tions nvelope ementation ormatiques NE-SDS-223837-GO-RFB / Ac Component 1: Regional Lake quisition de fournitures et éq Chad Knowledge and Monito Single Stage - One E Under Imple IDA / 66440 Post Request for Bids Open - National 250,953.00 0.00 2021-06-15 2022-09-13 2021-06-20 2021-08-01 2022-10-28 2021-08-31 2021-10-05 2022-04-03 uipement pour le compte de l ring Platform and Secretariat nvelope mentation 'Université de Diffa for the Development of the L ake Chad Reg ion NE-SDS-223551-GO-RFQ / Ac Component 4: Project Manag Request for Quota Single Stage - One E quisition des équipements inf IDA / D6350 Post Limited 35,091.00 61,164.65 Completed 2021-03-21 2021-04-06 2021-05-16 2021-04-30 2021-11-12 2021-05-22 ement tions nvelope ormatiques complémentaires NE-SDS-223570-GO-RFQ / Ac Component 4: Project Manag Request for Quota Single Stage - One E quisition de matériel et mobil IDA / 66440 Post Limited 85,590.00 30,442.34 Completed 2021-03-20 2021-04-06 2021-05-15 2021-05-01 2021-11-11 2021-06-12 ement tions nvelope ier de bureau complémentair es NE-SDS-223568-GO-RFQ / Ac Component 4: Project Manag Request for Quota Single Stage - One E quisition de Logiciel comptab IDA / 66440 Post Limited 40,000.00 38,716.34 Completed 2021-03-13 2021-03-16 2021-05-08 2021-04-01 2021-11-04 2021-05-27 ement tions nvelope le de gestion financière NE-SDS-223562-GO-RFQ / Ac Component 4: Project Manag Request for Quota Single Stage - One E quisition et Installation des E IDA / 66440 Post Limited 34,000.00 20,930.60 Completed 2021-06-30 2021-05-19 2021-08-25 2021-06-26 2022-02-21 2021-08-06 ement tions nvelope quipements de Communicati on NE-SDS-223571-GO-RFB / Ac Component 3: Strengthening Single Stage - One E Pending Impl quisition de deux tricycles à l IDA / 66440 the Recovery of Agricultural Post Request for Bids Limited 8,000.00 0.00 2021-06-30 2021-07-05 2021-08-16 2021-09-15 2021-10-20 2022-04-18 nvelope ementation ’Université de Diffa Livelihoods NE-SDS-223573-GO-RFQ / Ac Component 4: Project Manag Request for Quota Single Stage - One E quisition et Installation de de IDA / 66440 Post Limited 80,000.00 80,508.67 Completed 2021-04-08 2021-06-11 2021-06-03 2021-07-07 2021-11-30 2021-09-07 ement tions nvelope ux systèmes de VC à l’UMOP NE-SDS-223581-GO-RFB / Ac Component 3: Strengthening quérir des semences (mil, sor Single Stage - One E IDA / 66440 the Recovery of Agricultural Post Request for Bids Open - National 290,909.00 231,262.41 Completed 2021-04-05 2021-05-31 2021-04-10 2021-05-22 2021-07-05 2021-06-21 2021-07-13 2021-07-26 2021-09-02 2022-01-22 2021-10-20 gho, niébé, riz, sésame) pour nvelope Livelihoods les cultures pluviales et mise en place NE-SDS-223845-GO-RFQ / Ac Component 3: Strengthening Request for Quota Single Stage - One E quérir de l'angrais pour les c IDA / 66440 the Recovery of Agricultural Post Limited 82,909.00 88,116.12 Completed 2021-05-04 2021-06-11 2021-06-29 2021-07-15 2021-12-26 2021-09-01 tions nvelope ultures pluviales et mise en p Livelihoods lace NE-SDS-223843-GO-RFB / Ac Component 3: Strengthening Open - Internationa Single Stage - One E Under Imple quérir des aliments bétail (so IDA / 66440 the Recovery of Agricultural Prior Request for Bids 2,041,818.00 0.00 2021-05-25 2021-06-10 2021-05-30 2021-06-21 2021-07-11 2021-08-06 2021-08-10 2021-11-29 2021-09-14 2022-03-13 l nvelope mentation n, tourteaux et pierres à léch Livelihoods er) NE-SDS-238568-GO-RFQ / Ac quisition d'équipements de h Component 4: Project Manag Request for Quota Single Stage - One E IDA / 66440 Post Limited 9,090.00 8,689.88 Completed 2021-06-30 2021-11-25 2021-08-25 2021-12-23 2022-02-21 2021-12-25 aute qualité ( salon et Tapis ) ement tions nvelope pour le coordonnateur Adjoin t du PROLAC, Page 2 NE-SDS-277359-GO-RFQ / Ac quérir quatre-vingts (80) tabl Component 4: Project Manag Request for Quota Single Stage - One E IDA / 66440 Post Limited 36,364.00 24,090.56 Completed 2022-04-25 2022-04-08 2022-06-20 2022-04-26 2022-12-17 2022-05-06 ettes pour la collecte des don ement tions nvelope nées de suivi sur GEMS/ODK NE-SDS-277374-GO-RFQ / Ac Component 4: Project Manag Request for Quota Single Stage - One E quérir du matériel compléme IDA / V3280 Post Limited 26,273.00 24,640.72 Signed 2022-03-30 2022-07-12 2022-05-25 2022-09-01 2022-11-21 ement tions nvelope ntaire de communication et i nformatique. NE-SDS-277400-GO-RFQ / Ac Component 4: Project Manag Request for Quota Single Stage - One E Under Imple IDA / 66440 Prior Limited 5,455.00 0.00 2022-02-28 2022-04-25 2022-10-22 quérir des Kits COVID ement tions nvelope mentation Component 1: Regional Lake NE-SDS-223842-GO-RFQ / Ac Chad Knowledge and Monito Single Stage - One E Under Imple quisition de Matériels roulant IDA / 66440 Post Request for Bids Open - National 136,364.00 0.00 2022-04-01 2022-05-16 2022-04-06 2022-05-18 2022-06-21 2022-06-17 2022-08-10 2022-07-22 2023-01-18 ring Platform and Secretariat nvelope mentation s à l’Université de Diffa for the Development of the L ake Chad Reg ion NE-SDS-283342-GO-RFQ / Ac Component 4: Project Manag Request for Quota Single Stage - One E Under Imple quisition de 30 pneus pour le IDA / 66440 Post Limited 10,909.00 0.00 2022-03-30 2022-05-25 2022-11-21 ement tions nvelope mentation s 6 véhicules du Projet NE-SDS-295978-GO-RFQ / Ac quisition de fourniture des m Component 3: Strengthening Request for Quota Single Stage - One E Under Imple atériels et matériaux pour la IDA / 66440 the Recovery of Agricultural Post Limited 45,454.00 0.00 2022-06-01 2022-07-19 2022-07-27 2023-01-23 tions nvelope mentation clôture du Centre de Santé et Livelihoods de l’Ecole de Blahardé NE-SDS-295977-GO-RFQ / Ac quisition de fourniture de qu Component 3: Strengthening atre (4) pompes solaires SQF Request for Quota Single Stage - One E Under Imple IDA / 66440 the Recovery of Agricultural Post Limited 84,727.00 0.00 2022-05-31 2022-07-19 2022-07-26 2023-01-22 de 3,6 KW pour la réhabilitati tions nvelope mentation Livelihoods on de quatre Postes d’Eau Au tonomes Solaire dans les co mmunes de N’Gourti et Tesk er NE-SDS-295999-GO-RFQ / Ac quisitions des Equipements e Component 3: Strengthening Request for Quota Single Stage - One E Under Imple t Matériaux pour le traiteme IDA / 66440 the Recovery of Agricultural Post Limited 97,455.00 0.00 2022-06-27 2022-06-20 2022-08-22 2023-02-18 tions nvelope mentation nt des points critiques comm Livelihoods unales Gamari-Nguelkolo NE-SDS-297775-GO-RFQ / Ac Component 3: Strengthening quisition d’intrants pour la mi Request for Quota Single Stage - One E Pending Impl IDA / 66440 the Recovery of Agricultural Post Limited 95,456.00 0.00 2022-06-20 2022-08-15 2023-02-11 se en valeur de 175 ha dans tions nvelope ementation Livelihoods les cuvettes oasiennes NE-SDS-297812-GO-RFB / Ac Component 3: Strengthening quisition des matériels et ma Single Stage - One E Pending Impl IDA / 66440 the Recovery of Agricultural Post Request for Bids Open - National 586,727.00 0.00 2022-06-20 2022-06-25 2022-08-06 2022-09-05 2022-10-10 2023-04-08 tériaux pour le traitement de nvelope ementation Livelihoods s points critiques dans la Rég ion de Diffa NE-SDS-325816-GO-RFQ / Ac quisition des équipements inf Component 4: Project Manag Request for Quota Single Stage - One E Under Imple IDA / V3280 Post Limited 14,545.00 0.00 2022-12-01 2022-12-01 2023-01-26 2023-07-25 ormatiques complémentaires ement tions nvelope mentation pour les nouveaux consultant s. NE-SDS-325817-GO-RFQ / Ac quisition des matériels de bu Component 4: Project Manag Request for Quota Single Stage - One E Under Imple IDA / 66440 Post Limited 6,363.00 0.00 2022-12-05 2022-12-01 2023-01-30 2023-07-29 reau (Réfrigérateur, Cafetièr ement tions nvelope mentation e...etc.) pour les consultants. NE-SDS-295991-GO-RFQ / Ac Component 4: Project Manag Request for Quota Single Stage - One E Pending Impl quérir un logiciel et des équi IDA / V3280 Post Limited 6,364.00 0.00 2022-07-09 2022-09-03 2023-03-02 ement tions nvelope ementation pements pour l'archivage éle ctronique NE-SDS-325813-GO-RFQ / Eq Component 1: Regional Lake uipements matériels fermes Chad Knowledge and Monito Request for Quota Single Stage - One E Pending Impl IDA / 66440 Post Limited 100,000.00 0.00 2022-12-30 2023-02-24 2023-04-25 avicoles, piscicoles, agropast ring Platform and Secretariat tions nvelope ementation orales. for the Development of the L ake Chad Reg ion NE-SDS-343346-GO-RFQ / A quérir des matériels et matér Component 2: Restoring Sus Request for Quota Single Stage - One E Under Imple iaux pour la réhabilitation de IDA / 66440 tainable Rural Mobility and C Post Limited 100,000.00 0.00 2023-03-15 2023-05-23 2023-03-15 2023-04-14 2023-04-29 2023-05-28 2023-06-27 tions nvelope mentation s puits pastoraux dans les Ré onnectivity gions de Diffa et Zinder NE-SDS-325810-GO-RFQ / Ac quisition des équipements po Component 4: Project Manag Request for Quota Single Stage - One E Pending Impl IDA / 66440 Post Limited 21,818.00 0.00 2023-04-10 2023-06-05 2023-12-02 ur la mise en place de la bas ement tions nvelope ementation e des données de la SDS NE-SDS-343353-GO-RFQ / R éaliser l'édition et la reprogra Component 3: Strengthening phie des Manuels et Guides ( Request for Quota Single Stage - One E Pending Impl IDA / 66440 the Recovery of Agricultural Post Limited 54,545.00 0.00 2023-05-30 2023-07-25 2023-08-24 MGP, Moyen de Subsitence A tions nvelope ementation Livelihoods gricole, Engagement Citoyen, Statégie HIMO, Etude Genre.. .) NE-SDS-343368-GO-RFQ / C onfection et pause de panne Component 3: Strengthening Request for Quota Single Stage - One E Pending Impl aux de visibilité au niveau de IDA / 66440 the Recovery of Agricultural Post Limited 30,000.00 0.00 2023-03-19 2023-05-14 2023-05-20 tions nvelope ementation la zone d'intervention et des Livelihoods réalisations du PROLAC NE-SDS-349952-GO-RFQ / O Component 2: Restoring Sus Request for Quota Single Stage - One E Under Imple uvrages de bibliothèque pour IDA / D6350 tainable Rural Mobility and C Post Limited 51,818.00 0.00 2023-05-02 2023-05-23 2023-06-27 2023-12-24 tions nvelope mentation le compte de l’UDA onnectivity NE-SDS-349953-GO-RFQ / Éq Component 2: Restoring Sus Request for Quota Single Stage - One E Under Imple uipements et logiciel informa IDA / D6330 tainable Rural Mobility and C Post Limited 100,000.00 0.00 2023-04-26 2023-05-23 2023-06-21 2023-12-18 tions nvelope mentation tique onnectivity NE-SDS-349955-GO-RFQ / Éq Component 2: Restoring Sus Request for Quota Single Stage - One E Under Imple uipements et logiciels de Car IDA / D6350 tainable Rural Mobility and C Post Limited 49,818.00 0.00 2023-04-30 2023-05-23 2023-06-25 2023-12-22 tions nvelope mentation tographie onnectivity NE-SDS-350270-GO-RFQ / Ac quisition d'EPI au profit des b Component 3: Strengthening Request for Quota Single Stage - One E Pending Impl rigadiers phytosanitaires dan IDA / D6350 the Recovery of Agricultural Post Limited 7,272.00 0.00 2023-05-30 2023-07-25 2024-01-21 tions nvelope ementation s les communes de Diffa, Mai Livelihoods ne, Chetimari et Goudoumari a Page 3 NE-SDS-349951-GO-RFQ / Fo urniture des Équipements de Component 2: Restoring Sus Request for Quota Single Stage - One E Under Imple bureau ( chaises, fauteuil, ta IDA / D6350 tainable Rural Mobility and C Post Limited 63,636.00 0.00 2023-05-06 2023-05-23 2023-07-01 2023-12-28 tions nvelope mentation bles, armoires, réfrigérateur, onnectivity congélateur Etc....) à l'UDA/D iffa. NE-SDS-361639-GO-RFQ / Ac quisition des matériels pour l Component 3: Strengthening Request for Quota Single Stage - One E Pending Impl es travaux de fixation des du IDA / 66440 the Recovery of Agricultural Post Limited 6,545.00 0.00 2023-07-02 2023-08-27 2024-02-23 tions nvelope ementation nes au niveau de 6 sites dan Livelihoods s la commune de Goudoumar ia NE-SDS-361640-GO-RFQ / Ac quisition des matériels pour l Component 2: Restoring Sus Request for Quota Single Stage - One E Pending Impl es travaux de fixation des du IDA / 66440 tainable Rural Mobility and C Post Limited 8,727.00 0.00 2023-06-26 2023-06-26 2023-07-26 2023-08-10 2023-09-08 2023-10-08 tions nvelope ementation nes au niveau de 8 sites dan onnectivity s la commune de Mainé Soro a NE-SDS-187205-GO-RFQ / Ac Component 4: Project Manag Request for Quota Single Stage - One E IDA / V3280 Post Open - National 50,000.00 0.00 Canceled 2020-08-23 2020-10-18 2021-04-16 quisition de mobilier de bure ement tions nvelope au NE-SDS-302820-GO-RFB / Fo urniture des matériels et m Component 3: Strengthening Single Stage - One E atériaux pour la réhabilitatio IDA / 66440 the Recovery of Agricultural Post Request for Bids Open - National 295,732.00 0.00 Canceled 2022-06-29 2022-07-04 2022-08-15 2022-09-14 2022-10-19 2023-04-17 nvelope n des puits pastoraux dans le Livelihoods s Régions de Diffa et Zinder NE-SDS-277388-GO-RFQ / Ac Component 1: Regional Lake quérir des kits aux survivant Chad Knowledge and Monito Request for Quota Single Stage - One E IDA / 66440 Post Limited 40,909.00 0.00 Canceled 2022-03-09 2022-05-04 2022-10-31 es pour la réinsertion sociopr ring Platform and Secretariat tions nvelope ofessionnelle après la prise e for the Development of the L n charge ake Chad Reg ion NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NE-SDS-223578-GO-RFQ / C Component 4: Project Manag Request for Quota Single Stage - One E onception et pose de Pannea IDA / 66440 Post Limited 8,000.00 10,726.90 Completed 2021-04-20 2021-05-19 2021-06-15 2021-06-26 2021-12-12 2021-09-08 ement tions nvelope ux de visibilité NE-SDS-223549-GO-RFQ / C onception, réalisation et impr Component 4: Project Manag Request for Quota Single Stage - One E ession d'un bulletin trimestri IDA / 66440 Post Limited 12,000.00 6,888.97 Signed 2021-04-15 2021-09-02 2021-06-10 2021-10-01 2021-12-07 ement tions nvelope el en quadrichromie de 32 pa ges en 1500 exemplaires NE-SDS-282881-NC-RFQ / Ré Component 4: Project Manag Request for Quota Single Stage - One E aliser et éditer quatre (4) bull IDA / 66440 Post Limited 36,364.00 27,607.65 Signed 2022-03-30 2022-03-25 2022-05-25 2022-04-21 2022-11-21 ement tions nvelope etins trimestriel NE-SDS-325818-NC-RFQ / Re Component 4: Project Manag Request for Quota Single Stage - One E Under Imple cruter une agence pour la ré IDA / 66440 Post Limited 18,188.00 0.00 2022-11-27 2022-11-22 2023-01-22 2023-07-21 ement tions nvelope mentation alisation d’un film document aire NE-SDS-343322-NC-RFQ / Ré Component 4: Project Manag Request for Quota Single Stage - One E Under Imple aliser et éditer quatre (4) bull IDA / 66440 Post Limited 34,545.00 0.00 2023-04-08 2023-06-03 2024-05-28 ement tions nvelope mentation etins trimestriel en 2023 CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NE-SDS-187264-CS-CQS / Or Component 1: Regional Lake ganisation des séances de se Chad Knowledge and Monito Consultant Qualifi nsibilisation, des activités so IDA / V3280 ring Platform and Secretariat Post Open - National 200,000.00 0.00 Canceled 2020-09-01 2020-09-22 2020-11-05 2020-12-05 2021-01-09 2021-07-08 cation Selection cio-sportives et des rencontr for the Development of the L es intercommunautaires ake Chad Reg ion NE-SDS-187195-CS-QCBS / E Component 3: Strengthening tudes techniques, y compris Quality And Cost- Open - Internationa IDA / V3280 the Recovery of Agricultural Post 364,000.00 0.00 Canceled 2020-11-15 2020-12-06 2021-01-19 2021-02-16 2021-03-18 2021-04-22 2021-05-27 2022-05-27 environnementale et sociales Based Selection l Livelihoods des pistes rurales identifiées Component 1: Regional Lake NE-SDS-187228-CS-CQS / Et Chad Knowledge and Monito Consultant Qualifi udes sur la problématique de IDA / V3280 Post Open - National 20,000.00 0.00 Canceled 2020-10-11 2020-09-11 2020-11-01 2020-10-12 2020-12-15 2021-01-14 2021-02-18 2021-08-17 ring Platform and Secretariat cation Selection l'employabilité des jeunes for the Development of the L ake Chad Reg ion NE-SDS-187255-CS-CQS / Fir Component 4: Project Manag Consultant Qualifi Under Implement me pour le recrutement du p IDA / V3280 Post Open - National 20,000.00 0.00 2020-08-25 2020-08-31 2020-09-15 2020-10-29 2020-11-28 2021-01-02 2021-07-01 ement cation Selection ation ersonnel clé du projet NE-SDS-187263-CS-QCBS / E Component 3: Strengthening Consultant Qualifi laboration de plan d'amenag IDA / V3280 the Recovery of Agricultural Post Open - National 45,000.00 211,538.67 Signed 2021-02-02 2020-09-11 2021-02-23 2020-10-08 2021-04-08 2021-05-26 2021-05-08 2021-10-04 2021-06-12 2021-10-15 2021-12-09 cation Selection ement des cuvettes Livelihoods NE-SDS-187226-CS-CQS / El aboration de Manuels d'exéc Component 4: Project Manag Consultant Qualifi Under Implement ution du projet, de gestion ad IDA / V3280 Post Open - National 120,000.00 0.00 2020-08-25 2020-09-11 2020-09-15 2020-10-29 2020-11-28 2021-01-02 2021-07-01 ement cation Selection ation ministrative, financière et co mptable et de suivi-évaluatio n Component 1: Regional Lake NE-SDS-187217-CS-CQS / Et Chad Knowledge and Monito Consultant Qualifi Under Implement udes sur la prise en compte IDA / V3280 Post Open - National 20,000.00 0.00 2020-08-26 2020-10-19 2020-09-16 2020-10-30 2020-11-29 2021-01-03 2021-07-02 ring Platform and Secretariat cation Selection ation du genre for the Development of the L ake Chad Reg ion NE-SDS-187269-CS-CQS / Re Component 1: Regional Lake dynamisation des comités co Chad Knowledge and Monito Consultant Qualifi mmunaux existants et les for IDA / V3280 ring Platform and Secretariat Post Open - National 200,000.00 0.00 Canceled 2020-09-25 2020-10-16 2020-11-29 2020-12-29 2021-02-02 2021-08-01 cation Selection mer sur divers thématiques r for the Development of the L elatives à l'engagement citoy ake Chad Reg ion en Page 4 NE-SDS-187216-CS-CQS / Ap Component 1: Regional Lake pui aux communes à l'élabor Chad Knowledge and Monito Consultant Qualifi IDA / V3280 Post Open - National 125,000.00 0.00 Canceled 2020-08-19 2020-09-09 2020-10-23 2020-11-22 2020-12-27 2021-06-25 ation et au suivi de l'exécutio ring Platform and Secretariat cation Selection n du budget participatif for the Development of the L ake Chad Reg ion NE-SDS-187257-CS-CQS / Et Component 3: Strengthening udes techniques pour la réali Consultant Qualifi IDA / V3280 the Recovery of Agricultural Post Open - National 91,000.00 138,278.33 Signed 2020-09-24 2020-10-07 2020-10-15 2020-10-19 2020-11-28 2021-05-26 2020-12-28 2021-07-16 2021-02-01 2021-09-10 2021-07-31 sation/réhabilitation des ouvr cation Selection Livelihoods ages d'hydraulique pastorale NE-SDS-187251-CS-CQS / Et Component 3: Strengthening Consultant Qualifi udes pour la priorisation des IDA / V3280 the Recovery of Agricultural Post Open - National 20,000.00 0.00 Canceled 2020-08-26 2020-10-07 2020-09-16 2020-10-19 2020-10-30 2020-11-29 2021-01-03 2021-07-02 cation Selection sites d'intervention du projet Livelihoods Component 1: Regional Lake NE-SDS-187238-CS-CQS / Et Chad Knowledge and Monito Consultant Qualifi ude sur la stratégie d'Engage IDA / V3280 Post Open - National 20,000.00 41,190.13 Completed 2020-08-19 2020-10-07 2020-09-09 2020-10-19 2020-10-23 2021-05-26 2020-11-22 2021-10-15 2020-12-27 2021-10-26 2021-06-25 2022-03-31 ring Platform and Secretariat cation Selection ment Citoyen for the Development of the L ake Chad Reg ion NE-SDS-198564-CS-QCBS / A Component 4: Project Manag Quality And Cost- Open - Internationa Under Implement IDA / V3280 Post 136,250.00 0.00 2020-11-20 2021-04-28 2020-12-11 2021-01-24 2021-12-15 2021-02-21 2022-01-25 2021-03-23 2022-02-17 2021-04-27 2022-03-25 2021-06-01 2022-06-01 udit externe ement Based Selection l ation NE-SDS-223575-CS-CQS / Ré Component 3: Strengthening aliser une étude pour la mise Consultant Qualifi IDA / 66440 the Recovery of Agricultural Post Open - National 65,565.00 0.00 Canceled 2021-06-27 2021-07-18 2021-08-31 2021-09-30 2021-11-04 2022-05-03 à jour des PDC de Goudouma cation Selection Livelihoods ria, Ngourti et Tesker NE-SDS-223574-CS-CQS / Re cruter un cabinet pour réalis er l’Inventaire -socioéconomi Component 2: Restoring Sus Quality And Cost- Open - Internationa que des études Techniques , IDA / 66440 tainable Rural Mobility and C Post 500,000.00 224,880.22 Signed 2021-04-02 2021-04-06 2021-04-23 2021-06-03 2021-06-06 2021-09-17 2021-07-04 2021-10-29 2021-08-03 2021-11-30 2021-09-07 2022-01-18 2021-10-12 2022-03-16 2022-10-12 Based Selection l Environnementales et sociale onnectivity s des travaux de Réhabilitati on de 140 km de Routes dan s la Région de Diffa NE-SDS-238567-CS-CQS / Re crutement un cabinet pour le Component 4: Project Manag Consultant Qualifi Under Implement IDA / 66440 Post Open - National 9,090.00 0.00 2021-06-20 2021-06-23 2021-07-11 2021-08-24 2021-10-07 2021-09-23 2021-10-28 2022-04-26 recrutement du personnel co ement cation Selection ation mplémentaire du PROLAC NE-SDS-252450-CS-CQS / Re crutement d’un Cabinet d’étu des, chargé de Réaliser les ét Component 3: Strengthening Consultant Qualifi Under Implement udes préparatoires sur l’Appr IDA / 66440 the Recovery of Agricultural Post Open - National 45,454.00 0.00 2021-10-01 2021-09-13 2021-10-22 2021-12-05 2022-01-04 2022-02-08 2022-08-07 cation Selection ation oche HIMO du Projet de Rela Livelihoods nce et de Développement de la Région du Lac Tchad (PRO LAC) NE-SDS-277350-CS-CQS / Re Component 1: Regional Lake cruter une ONG d'accompag Chad Knowledge and Monito nement sur la mobilisation so Consultant Qualifi Under Implement IDA / 66440 ring Platform and Secretariat Post Open - National 218,182.00 0.00 2022-04-15 2022-05-19 2022-05-06 2022-06-19 2023-01-20 2022-07-19 2022-08-23 2023-02-19 ciale pour les accords sociau cation Selection ation for the Development of the L x, ciblage de bénéficiaires fix ake Chad Reg ion ation de dunes, formation et encadrement des travaux NE-SDS-277381-CS-CQS / Re cruter un consultant pour la Component 4: Project Manag Consultant Qualifi IDA / 66440 Post Open - National 63,636.00 0.00 Canceled 2022-04-11 2022-05-02 2022-06-15 2022-07-15 2022-08-19 2023-02-15 mise en place de la base des ement cation Selection données de la SDS NE-SDS-277340-CS-CQS / Re cruter un bureau d'étude pou Component 3: Strengthening Consultant Qualifi Under Implement r le contrôle technique des tr IDA / 66440 the Recovery of Agricultural Post Open - National 90,909.00 0.00 2022-04-15 2022-05-09 2022-05-06 2022-06-19 2022-11-08 2022-07-19 2022-12-22 2022-08-23 2023-02-19 cation Selection ation avaux de réalisation/réhabilit Livelihoods ation des ouvrages hydrauliq ues pastorales NE-SDS-302821-CS-CQS / Re Component 3: Strengthening cruter un cabinet pour le con Consultant Qualifi Open - Internationa Under Implement IDA / 66440 the Recovery of Agricultural Post 109,091.00 0.00 2022-07-15 2022-08-09 2022-08-05 2022-09-18 2022-11-08 2022-10-18 2023-01-02 2022-11-22 2023-05-21 trôle technique des travaux d cation Selection l ation Livelihoods 'aménagement des cuvettes NE-SDS-313010-CS-CQS / Re crutement d'un consultant po Component 2: Restoring Sus ur l'élaboration d'une étude Consultant Qualifi Under Implement IDA / 66440 tainable Rural Mobility and C Post Limited 36,363.00 0.00 2022-09-15 2022-09-02 2022-09-29 2022-10-29 2022-12-03 2023-06-01 d'Impact Environnementale e cation Selection ation onnectivity t Sociale des travaux d'amén agement de 140 km de route s dans la région de Diffa. NE-SDS-343351-CS-CQS / Re cruter un consultant pour la r Component 3: Strengthening éalisation de l'étude techniqu Consultant Qualifi Under Implement IDA / 66440 the Recovery of Agricultural Post Open - National 109,091.00 0.00 2023-06-01 2023-05-23 2023-06-22 2023-08-05 2023-09-04 2023-10-09 2024-04-06 e d’infrastructure de commer cation Selection ation Livelihoods cialisation et pour la construc tion/réhabilitation d’entrepôt s de stockage (APS/APD/DAO ) NE-SDS-343362-CS-QCBS / R Component 2: Restoring Sus ecruter un Cabinet/consultan Quality And Cost- Open - Internationa Pending Impleme IDA / 66440 tainable Rural Mobility and C Prior 1,454,545.00 0.00 2023-05-01 2023-05-22 2023-07-05 2023-08-02 2023-09-01 2023-10-06 2023-11-10 2024-11-09 t pour le suivi contrôle des tr Based Selection l ntation onnectivity avaux de réhabilitation des r outes rurales NE-SDS-277403-CS-CQS / Re cruter une ONG d’accompag Component 3: Strengthening Consultant Qualifi nement sur la mobilisation d IDA / 66440 the Recovery of Agricultural Post Open - National 254,545.00 0.00 Canceled 2022-04-05 2022-04-26 2022-06-09 2022-07-09 2022-08-13 2023-02-09 cation Selection es acteurs HIMO, ciblage, enr Livelihoods egistrement des bénéficiaire s, Suivi et reporting NE-SDS-223839-CS-CQS / Re Component 1: Regional Lake cruter une ONG d'accompag Chad Knowledge and Monito Consultant Qualifi IDA / 66440 Post Open - National 200,000.00 0.00 Canceled 2021-10-01 2021-10-22 2021-12-05 2022-01-04 2022-02-08 2022-08-07 nement pour l'execution des ring Platform and Secretariat cation Selection activités d'engagement citoy for the Development of the L en ake Chad Reg ion NE-SDS-223561-CS-CQS / Re Component 4: Project Manag Consultant Qualifi cruter une ONG pour le suivi IDA / 66440 Post Open - National 80,000.00 0.00 Canceled 2021-11-02 2021-11-23 2022-01-06 2022-02-05 2022-03-12 2022-09-08 ement cation Selection externe de la qualité des trav aux NE-SDS-223835-CS-CQS / Ré aliser l'étude technique (APS Component 3: Strengthening APD et DAO) d'actualisation Consultant Qualifi IDA / 66440 the Recovery of Agricultural Post Open - National 140,000.00 0.00 Canceled 2021-05-05 2021-05-21 2021-05-26 2021-07-09 2021-08-08 2021-09-12 2022-03-11 de la faisabilité et faire le Sui cation Selection Livelihoods vi-contrôles des travaux de p rotection des terres agricoles et habitations à Diffa Page 5 NE-SDS-187206-CS-CQS / Pri Component 1: Regional Lake se en charge psycho-social d Chad Knowledge and Monito es personnes victimes des Vi Consultant Qualifi Open - Internationa IDA / V3280 ring Platform and Secretariat Post 200,000.00 0.00 Canceled 2020-08-19 2020-09-09 2020-10-23 2020-11-22 2020-12-27 2021-06-25 olences Basées sur le genres cation Selection l for the Development of the L (VBG), des viols, des prises d' ake Chad Reg ion otages, victimes des mines/e xplosifs, les repentis etc, INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NE-SDS-223553-CS-INDV / Et udes préparatoires nécessair es à la mise en œuvre de l’ap Component 3: Strengthening Individual Consult proche HIMO dans une comm IDA / 66440 the Recovery of Agricultural Post Open 38,000.00 0.00 Canceled 2021-04-25 2021-06-13 2021-07-04 2021-08-08 2022-02-04 ant Selection unauté, y compris les évaluat Livelihoods ions rapides du développeme nt au niveau communautaire Component 1: Regional Lake NE-SDS-223834-CS-INDV / Et Chad Knowledge and Monito Individual Consult ude sur la problématique de l IDA / 66440 Post Open 20,000.00 23,969.03 Signed 2021-05-15 2021-05-20 2021-07-03 2021-09-13 2021-07-24 2021-10-14 2021-08-28 2021-10-26 2022-02-24 ring Platform and Secretariat ant Selection ’employabilité des jeunes for the Development of the L ake Chad Reg ion Component 1: Regional Lake NE-SDS-223831-CS-INDV / Et Chad Knowledge and Monito Individual Consult udes sur la prise en compte IDA / 66440 Post Open 20,000.00 21,417.82 Signed 2021-06-23 2021-04-29 2021-08-11 2021-11-15 2021-09-01 2021-11-22 2021-10-06 2022-01-13 2022-04-04 ring Platform and Secretariat ant Selection du genre for the Development of the L ake Chad Reg ion NE-SDS-223565-CS-INDV / R ecruter un consultant Individ Component 3: Strengthening Individual Consult uel pour la réalisation de l'ét IDA / 66440 the Recovery of Agricultural Post Open 60,000.00 23,793.41 Completed 2021-03-10 2021-04-01 2021-04-28 2021-04-22 2021-05-19 2021-10-14 2021-06-23 2021-10-21 2021-12-20 2022-03-31 ant Selection ude sur les Chaines de Valeu Livelihoods rs agricoles dans les Cuvette s Oasiennes NE-SDS-223560-CS-INDV / R ecruter un consultant individ Component 4: Project Manag Individual Consult IDA / 66440 Post Limited 60,000.00 101,128.43 Signed 2021-05-05 2021-05-19 2021-05-10 2021-06-05 2021-05-31 2021-09-23 2021-07-05 2021-10-05 2022-01-01 uel pour réaliser l’étude sur l ement ant Selection a situation de référence du p rojet NE-SDS-234017-CS-INDV / R Component 4: Project Manag Individual Consult Under Implement ecrutement d'un auditeur int IDA / 66440 Post Open 36,000.00 0.00 2021-05-25 2021-05-31 2021-07-13 2021-08-03 2021-09-07 2022-04-25 ement ant Selection ation erne au projet PROLAC NE-SDS-234020-CS-INDV / R Component 4: Project Manag Individual Consult Under Implement ecrutement d'un comptable P IDA / 66440 Post Open 26,182.00 0.00 2021-05-25 2021-05-31 2021-07-13 2021-08-03 2021-09-07 2022-04-25 ement ant Selection ation rincipal au projet PROLAC NE-SDS-238566-CS-INDV / R ecruter un consultant pour m Component 4: Project Manag Individual Consult IDA / 66440 Post Limited 27,000.00 19,938.97 Signed 2021-07-07 2021-09-22 2021-07-12 2021-12-22 2021-08-02 2022-02-28 2021-09-06 2022-03-17 2022-03-05 ettre en place la plateforme ement ant Selection KoboCollect et former les act eurs NE-SDS-238569-CS-INDV / R ecruter un consultant pour la Component 4: Project Manag Individual Consult IDA / 66440 Post Limited 9,090.00 0.00 Canceled 2021-07-01 2021-07-06 2021-07-27 2021-08-31 2022-02-27 formation des acteurs du Proj ement ant Selection et en planification opérationn elle NE-SDS-238573-CS-INDV / R ecruter un consultant pour la Component 4: Project Manag Individual Consult réalisation d’une stratégie de IDA / 66440 Post Limited 27,000.00 16,260.67 Completed 2021-06-25 2021-07-08 2021-06-30 2022-02-15 2021-07-21 2021-12-24 2021-08-25 2021-12-25 2022-02-21 2022-03-22 ement ant Selection Communication et son plan d ’action pour le PROLAC Niger NE-SDS-251467-CS-INDV / R Component 4: Project Manag Individual Consult Under Implement ecrutement d'un Assistant en IDA / 66440 Post Open 21,818.00 0.00 2021-10-01 2022-02-08 2021-11-19 2021-12-10 2022-01-14 2022-09-01 ement ant Selection ation Passation de Marchés pour l' UMOP Niamey NE-SDS-251472-CS-INDV / R Component 4: Project Manag Individual Consult Under Implement ecrutement d'un contrôleur I IDA / 66440 Post Open 21,818.00 0.00 2021-10-05 2021-10-14 2021-11-23 2021-12-14 2022-01-18 2022-09-05 ement ant Selection ation nterne à Diffa NE-SDS-251473-CS-INDV / R ecrutement d'un Assistant au Component 4: Project Manag Individual Consult Under Implement IDA / 66440 Post Open 21,818.00 0.00 2021-09-15 2021-10-08 2021-11-03 2021-11-24 2021-12-29 2022-08-16 Spécialiste en suivi et évalua ement ant Selection ation tion pour l'UMOP Diffa NE-SDS-251475-CS-INDV / R Component 4: Project Manag Individual Consult Under Implement ecrutement d'un Spécialiste IDA / 66440 Post Open 32,727.00 0.00 2021-09-16 2021-10-14 2021-11-04 2021-11-25 2021-12-30 2022-08-17 ement ant Selection ation en genre et violence basée s ur le genre NE-SDS-277377-CS-INDV / R ecruter un consultant individ Component 4: Project Manag Individual Consult uel pour appuyer l’UDA dans IDA / 66440 Post Limited 7,272.00 10,417.98 Completed 2022-02-20 2022-02-23 2022-02-25 2022-03-09 2022-03-18 2022-03-29 2022-04-22 2022-03-31 2022-10-19 2022-08-10 ement ant Selection l’élaboration des spécificatio ns techniques des leurs équi pements NE-SDS-277406-CS-INDV / R ecrutement d'un Assistant en Component 4: Project Manag Individual Consult Under Implement Infrastructures pour l'UMOP IDA / 66440 Post Open 21,818.00 0.00 2022-02-15 2022-02-23 2022-04-05 2022-04-26 2022-05-31 2023-01-16 ement ant Selection ation Diffa dans le cadre de la mis e en œuvre des activités du PROLAC NE-SDS-295992-CS-INDV / R ecruter un consultant pour as Component 4: Project Manag Individual Consult Under Implement IDA / 66440 Post Limited 5,455.00 0.00 2022-06-15 2023-06-14 2022-06-20 2022-07-11 2022-08-15 2023-02-11 surer la mise en place et la f ement ant Selection ation ormation en archivage électr onique NE-SDS-302822-CS-INDV / R ecruter un consultant pour la Component 4: Project Manag Individual Consult Under Implement IDA / 66440 Post Open 12,727.00 0.00 2022-08-25 2022-08-05 2022-10-13 2022-12-01 2022-11-03 2023-01-10 2022-12-08 2023-06-06 mise en place de la base des ement ant Selection ation données de la SDS NE-SDS-361634-CS-INDV / R ecruter un consultant chargé Component 3: Strengthening Individual Consult Under Implement d'élaborer les modules et out IDA / 66440 the Recovery of Agricultural Post Limited 18,181.00 0.00 2023-06-26 2023-06-03 2023-07-01 2023-07-22 2023-08-26 2024-02-22 ant Selection ation ils et de la formation sur l'ad Livelihoods aptation aux changements cl imatiques Page 6 NE-SDS-366073-CS-INDV / R ecrutement d’un Consultant Component 3: Strengthening dans le cadre de l’évaluation Individual Consult Pending Impleme IDA / 66440 the Recovery of Agricultural Post Limited 20,000.00 0.00 2023-10-04 2023-10-09 2023-10-30 2023-12-04 2024-01-03 à mi-parcours du Projet de R ant Selection ntation Livelihoods edressement et de Développ ement de la Région du Lac T chad -- PROLAC NIGER. Page 7 PROCUREMENT PLAN (Textual Part) Project information: Ethiopia, Digital Ethiopia (P171034) Project Implementation agency: Ministry of Finance and Economic Cooperation, Channel One Project Coordination Directorate Date of the Procurement Plan: September 2019 Period covered by this Procurement Plan: from September 2019 to June 2020 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in Section 33(1)(a) from 35-48 of the Proclamation Number 649/2009 of the Ethiopian Federal Government Procurement and Property Administration Proclamation such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. • Open Advertising of the procurement opportunity at the national level; • The procurement is open to eligible firms from any country; • The request for bids/Proposal documents shall require that bidders/proposers submitting Bids/Proposal present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of and compliance with the Bank’s Anti-Corruption Guidelines, including without limitation the bank’s right to sanction and the Bank’s inspection and audit right; • Contracts with an appropriate allocation of responsibilities, risks and liabilities; • Application of Standstill period and Publication of contract award information; • Maintenance of records of the procurement process; and • The Bank has the right to review procurement documentation and activities. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. PROCUREMENT Ethiopia : Ethiopia Digital Foundations Project PLAN General Information Country: Ethiopia 2021-05-19 Bank’s Approval Date of the Original Procurement Plan: 2023-06-07 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P171034 GPN Date: 2022-06-25 Project Name: Ethiopia Digital Foundations Project Loan / Credit No: IDA / 68560 Ministry of Innovation and Technology Executing Agency(ies): WORKS Activity Reference No. / Procureme Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH Ri Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method nt Docume ount (US$ and Recommendation Signed Contract o. h cess (Y/N) sk atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion nt Type ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MINT/DE/NCB/G-07/21 / Proc urement of End Devices for i 2. Digital government and c Open - Internationa Single Stage - One E Pending Impl IDA / 68560 Prior Request for Bids 0.00 2021-07-30 2021-08-04 2021-09-15 2021-10-15 2021-11-19 2022-05-18 mplementation of portal and onnectivity l nvelope ementation transaction systems MINT/DE/NCB/G-12-1/21 / Su pply and installation of Impr oved facilities for remote wor 2. Digital government and c Open - Internationa Single Stage - One E IDA / 68560 Post Request for Bids 799,894.95 Signed 2021-07-28 2021-09-20 2021-08-02 2021-12-17 2021-09-13 2022-02-11 2021-10-13 2022-03-14 2021-11-17 2022-04-28 2022-05-16 king, and the installation of c onnectivity l nvelope ommunications rooms for fiv e institutions (MInT, ECA, Eth ERNet, MoP & MoF) MINT/DE/NCB/G-01-1/21 / Ac quisition of IT equipments for 2. Digital government and c Open - Internationa Single Stage - One E Under Imple IDA / 68560 Post Request for Bids 0.00 2021-09-15 2022-03-21 2021-09-20 2023-03-13 2021-11-01 2021-12-01 2022-01-05 2022-07-04 assisting EthERNet to becom onnectivity l nvelope mentation e a fully operational NREN ph ysically MINT/DE/NCB/G-01-2/21 / Ac quisition of Vehicles for assis 2. Digital government and c Pending Impl IDA / 68560 Post Direct Selection Direct 0.00 2021-09-08 2021-09-13 2021-10-23 2022-04-21 ting EthERNet to become a fu onnectivity ementation lly operational NREN physical ly MINT/DE/NCB/G-01/21 / Acqu isition of IT equipments for a 2. Digital government and c Single Stage - One E Pending Impl IDA / 68560 Post Request for Bids Open - National 0.00 2021-09-22 2021-09-27 2021-11-08 2021-12-08 2022-01-12 2022-07-11 ssisting EthERNet to become onnectivity nvelope ementation a fully operational NREN phy sically MINT/DE/ICB/G-13/21 / Suppl 1. Digital economy, enabling Single Stage - One E Pending Impl IDA / 68560 Post Request for Bids Open - National 0.00 2021-09-20 2021-09-25 2021-10-25 2021-11-24 2021-12-29 2022-06-27 y of Registration Kits for Digit legal and regulatory environ nvelope ementation al ID - MoP ment ET-MINT-251134-GO-RFQ / P Request for Quota Single Stage - One E rocurement of Sanitation and IDA / 68560 4. Project management Post Limited 539.86 Completed 2021-09-20 2021-11-24 2021-11-15 2021-12-04 2022-01-14 2021-12-10 tions nvelope Utilities Equipment ET-MINT-251135-GO-RFQ / P Request for Quota Single Stage - One E Pending Impl IDA / 68560 4. Project management Post Limited 0.00 2021-09-25 2021-11-20 2022-01-19 rocurement of Office Furnitur tions nvelope ementation e for PIU ET-MINT-251137-GO-RFQ / P Request for Quota Single Stage - One E rocurement of Laptop Compu IDA / 68560 4. Project management Post Limited 18,128.45 Completed 2021-09-20 2021-12-15 2021-11-15 2022-01-11 2022-02-13 2022-01-27 tions nvelope ter and IT Equipment for PIU ET-MINT-251138-GO-RFQ / P Request for Quota Single Stage - One E Under Imple IDA / 68560 4. Project management Post Limited 0.00 2021-09-20 2021-11-24 2021-11-15 2021-12-15 rocurement of Stationery Mat tions nvelope mentation erials ET-MINT-251962-GO-RFB / S upply & Installation of IT equi 2. Digital government and c Open - Internationa Single Stage - One E Pending Impl IDA / 68560 Prior Request for Bids 0.00 2021-10-25 2021-10-30 2021-12-11 2022-01-10 2022-02-14 2022-08-13 pment for Transitioning existi onnectivity l nvelope ementation ng systems to the unified por tal - MInT ET-MINT-251963-GO-RFB / S upply & Installation of IT equi 2. Digital government and c Open - Internationa Single Stage - One E Pending Impl IDA / 68560 Prior Request for Bids 0.00 2021-11-25 2021-11-30 2022-01-11 2022-02-10 2022-03-17 2022-09-13 pment for integrating the nat onnectivity l nvelope ementation ional databases - MInT ET-MINT-251964-GO-RFB / S 2. Digital government and c Open - Internationa Single Stage - One E Pending Impl upply and installation of Clou IDA / 68560 Prior Request for Bids 0.00 2021-11-25 2021-11-30 2022-01-11 2022-02-10 2022-03-17 2022-09-13 onnectivity l nvelope ementation d-based National Data-center - MInT ET-MINT-253581-GO-RFB / S 1. Digital economy, enabling Single Stage - One E upply and Delivery of Registr IDA / 68560 legal and regulatory environ Post Request for Bids Open - National 354,688.83 Signed 2021-10-05 2022-04-20 2021-10-10 2022-04-25 2021-11-09 2022-05-25 2021-12-09 2022-07-01 2022-01-13 2022-08-03 2022-07-12 nvelope ation Kits for Digital ID ment ET-MINT-253622-GO-RFB / Pr 2. Digital government and c Single Stage - One E Under Imple IDA / 68560 Post Request for Bids Open - National 0.00 2021-09-22 2021-12-17 2021-09-27 2021-12-17 2021-10-27 2022-02-04 2021-11-26 2021-12-31 2022-06-29 ocurement of office furniture onnectivity nvelope mentation for ECA ET-MINT-253627-GO-RFB / Pr 1. Digital economy, enabling Open - Internationa Single Stage - One E Under Imple ocurement of basic Spectrum IDA / 68560 legal and regulatory environ Post Request for Bids 0.00 2021-09-30 2022-03-21 2021-10-05 2022-03-21 2021-11-16 2022-05-20 2021-12-16 2022-01-20 2022-07-19 l nvelope mentation Monitoring Equipment - ECA ment ET-MINT-253628-GO-RFB / Pr 1. Digital economy, enabling ocurement of ICT Equipment Single Stage - One E IDA / 68560 legal and regulatory environ Post Request for Bids Open - National 543,300.00 Signed 2021-10-12 2022-03-21 2021-10-17 2022-03-21 2021-11-16 2022-05-04 2021-12-16 2022-06-21 2022-01-20 2022-08-11 2022-07-19 for Establishing Quality of Se nvelope ment rvice Monitoring System ET-MINT-253629-GO-RFB / Pr ocurement of Equipment for 1. Digital economy, enabling Single Stage - One E Under Imple establishing a National Telec IDA / 68560 legal and regulatory environ Post Request for Bids Open - National 0.00 2021-09-30 2022-03-21 2021-10-05 2022-03-21 2021-10-08 2022-04-18 2021-11-07 2022-05-19 2021-12-12 2022-06-10 nvelope mentation ommunications Numbering M ment anagement System - ECA ET-MINT-253630-GO-RFB / S 1. Digital economy, enabling upply, Installation and Comm Open - Internationa Single Stage - One E IDA / 68560 legal and regulatory environ Post Request for Bids 1,463,748.67 Signed 2021-10-20 2022-03-21 2021-10-25 2022-03-21 2021-12-06 2022-05-18 2022-01-05 2022-06-21 2022-02-09 2022-08-26 2022-08-08 issioning of Internal Network l nvelope ment Infrastructure and Databases for ECA Page 1 MINT/DE/ICB/G-04/21 / Procu rement of Network equipmen t to support points of presenc 2. Digital government and c Open - Internationa Single Stage - One E Under Imple e, and data caches, around E IDA / 68560 Prior Request for Bids 0.00 2021-09-30 2022-02-08 2021-10-05 2022-02-10 2021-11-16 2022-04-12 2021-12-16 2022-07-22 2022-01-20 2023-01-15 onnectivity l nvelope mentation thiopia for 40 TVET, 30 Unive rsities and EthERNet Datacen ter and aggregation centre u pgrades. ET-MINT-286361-GO-RFQ / P 3. Digital business and entre Request for Quota Single Stage - One E IDA / 68560 Post Limited 0.00 Canceled 2022-04-01 2022-03-29 2022-05-05 2022-08-03 rocurement of Server preneurship tions nvelope ET-MINT-296844-GO-RFB / Pr ocurement of Heavy Duty Sc 2. Digital government and c Single Stage - One E anner, Desk Top Computer & IDA / 68560 Post Request for Bids Open - National 0.00 Signed 2022-05-30 2022-06-06 2022-06-04 2022-06-08 2022-07-04 2022-07-12 2022-08-03 2022-10-11 2022-09-01 2022-11-30 onnectivity nvelope UPS for Digitalization of Fede ral Supreme Court Archive D ocumentation ET-MINT-298918-GO-RFQ / P rocurement of Office Furnitur 2. Digital government and c Request for Quota Single Stage - One E IDA / 68560 Post Limited 0.00 Signed 2022-06-15 2022-06-10 2022-07-22 2022-08-21 e for establishment of EthER onnectivity tions nvelope Net Office at Ministry of Educ ation. ET-MINT-298920-GO-RFQ / P 2. Digital government and c Request for Quota Single Stage - One E Pending Impl rocurement of Laptop Compu IDA / 68560 Post Limited 0.00 2022-06-15 2022-07-30 2022-09-13 onnectivity tions nvelope ementation ters and other IT Equipment ET-MINT-299205-GO-RFQ / P 2. Digital government and c Request for Quota Single Stage - One E Pending Impl rocurement of Server for MIn IDA / 68560 Post Limited 0.00 2022-06-15 2022-07-30 2022-09-28 onnectivity tions nvelope ementation T for disaster recovery ET-MINT-307547-GO-RFQ / P Request for Quota Single Stage - One E Pending Impl rocurement of IT and Office E IDA / 68560 4. Project management Post Limited 0.00 2022-08-08 2022-09-19 2022-11-18 tions nvelope ementation quipment for PIU Team ET-MINT-312087-GO-RFB / Pr 2. Digital government and c Open - Internationa Single Stage - One E Under Imple ocurement of IT Related Equi IDA / 68560 Prior Request for Bids 0.00 2022-08-30 2022-12-21 2022-09-04 2023-01-03 2022-10-19 2023-03-07 2022-11-18 2022-12-23 2023-06-21 onnectivity l nvelope mentation pment for National Network E xchange Project ET-MINT-345379-GO-RFB / S UPPLY, INSTALLATION AND C 2. Digital government and c Open - Internationa Single Stage - One E Pending Impl IDA / 68560 Prior Request for Bids 0.00 2023-03-10 2023-03-15 2023-04-29 2023-05-29 2023-07-03 2023-12-30 ONFIGURATION OF PREFABRI onnectivity l nvelope ementation CATED MODULAR DATA CENT ER ON TURNKEY BASIS ET-MINT-345383-GO-RFB / S 2. Digital government and c Open - Internationa Single Stage - One E Under Imple upply, Delivery and Installati IDA / 68560 Prior Request for Bids 0.00 2023-03-12 2023-04-20 2023-03-17 2023-06-05 2023-03-21 2023-04-20 2023-05-25 2023-11-21 onnectivity l nvelope mentation on of National Data Center F acilities ET-MINT-345419-GO-RFB / S upply, Installation and Comm 2. Digital government and c Open - Internationa Single Stage - One E Under Imple issioning of Smart Communic IDA / 68560 Prior Request for Bids 0.00 2023-03-06 2023-04-06 2023-03-11 2023-04-12 2023-04-25 2023-05-25 2023-06-29 2024-06-23 onnectivity l nvelope mentation ation Rooms at Selected Twe nty Governmental Institution s on Turnkey Basis ET-MINT-345636-GO-RFB / Pr 1. Digital economy, enabling Single Stage - One E Pending Impl ocurement of Mobile Network IDA / 68560 legal and regulatory environ Post Request for Bids Open - National 0.00 2023-04-20 2023-04-25 2023-06-06 2023-07-06 2023-08-10 2024-02-06 nvelope ementation Coverage Mapping Simulatio ment n Tools (ECA) ET-MINT-346845-GO-RFB / Pr ocurement of software Licens 2. Digital government and c Open - Internationa Single Stage - One E Under Revie IDA / 68560 Prior Request for Bids 0.00 2023-03-14 2023-03-19 2023-04-30 2023-05-30 2023-07-04 2023-12-31 es, Vendor Support and Spar onnectivity l nvelope w e parts for the Core data Cen ter (MInT) ET-MINT-346849-GO-RFB / Pr 2. Digital government and c Open - Internationa Single Stage - One E Pending Impl ocurement of IT Equipment f IDA / 68560 Prior Request for Bids 0.00 2023-03-30 2023-04-04 2023-05-16 2023-06-15 2023-07-20 2024-01-16 onnectivity l nvelope ementation or upgrading the National Se curity System ET-MINT-346871-GO-RFB / Pr 1. Digital economy, enabling ocurement of Campus Netwo Open - Internationa Single Stage - One E Pending Impl IDA / 68560 legal and regulatory environ Prior Request for Bids 0.00 2023-04-30 2023-05-05 2023-06-16 2023-07-16 2023-08-20 2024-02-16 rk System focus for female d l nvelope ementation ment ormitories and conflict affect ed areas (MoE) ET-MINT-346902-GO-RFB / S upply and Installation of Solu 2. Digital government and c Open - Internationa Single Stage - One E Under Imple IDA / 68560 Prior Request for Bids 0.00 2023-03-27 2023-04-01 2023-05-13 2023-06-12 2023-07-17 2024-01-13 tions to set up ITIL based IT S onnectivity l nvelope mentation ervice Management Center ( MInT) ET-MINT-345421-GO-RFB / Pr ocurement of Equipment for 2. Digital government and c Open - Internationa Single Stage - One E Pending Impl IDA / 68560 Prior Request for Bids 0.00 2023-03-15 2023-03-20 2023-05-01 2023-05-31 2023-07-05 2024-01-01 establishment of Addressing onnectivity l nvelope ementation System for Addis Ababa ET-MINT-345619-GO-RFB / Pr 1. Digital economy, enabling Single Stage - One E Pending Impl ocurement of Central SIM Car IDA / 68560 legal and regulatory environ Post Request for Bids Open - National 0.00 2023-04-20 2023-04-25 2023-06-06 2023-07-06 2023-08-10 2024-02-06 nvelope ementation d Registration System (ECA) ment ET-MINT-345621-GO-RFB / Pr 1. Digital economy, enabling Single Stage - One E Pending Impl ocurement of OSS Based Qua IDA / 68560 legal and regulatory environ Post Request for Bids Open - National 0.00 2023-04-25 2023-06-20 2023-12-17 nvelope ementation lity of Monitoring System (EC ment A) NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MINT/DE/ICB/NC-01/21 / Prov ision of connectivity services and value-added services to 2. Digital government and c IDA / 68560 Post Direct Selection Direct 911,110.20 Completed 2021-08-23 2021-08-09 2021-08-28 2021-08-09 2021-10-02 2021-08-31 2022-03-31 2021-12-28 EthERNet (Research and Edu onnectivity cation Network of Ethiopia), t hrough membership of EU Af ricaConnect 3 program ET-MINT-251142-NC-RFQ / Pr Request for Quota Single Stage - One E Pending Impl IDA / 68560 4. Project management Post Limited 0.00 2021-09-25 2021-11-20 2022-11-20 ocurement of Car Rental Serv tions nvelope ementation ice ET-MINT-252701-NC-RFQ / E 1. Digital economy, enabling ngage an event organizer for Request for Quota Single Stage - One E Pending Impl IDA / 68560 legal and regulatory environ Post Limited 0.00 2021-10-05 2021-11-30 2022-11-25 civic society and public enga tions nvelope ementation ment gement for Digital ID - MoP Page 2 ET-MINT-257310-NC-RFB / Pr 1. Digital economy, enabling Single Stage - One E ocurement of Broadband Con IDA / 68560 legal and regulatory environ Post Request for Bids Limited 0.00 Canceled 2021-11-15 2022-01-25 2021-11-20 2022-01-25 2021-12-20 2022-01-19 2022-02-23 2022-08-22 nvelope nectivity for ICT Park ment ET-MINT-307546-NC-RFB / S 3. Digital business and entre Single Stage - One E Under Imple election of an Event and Logi IDA / 68560 Post Request for Bids Limited 0.00 2022-08-10 2022-08-25 2022-08-15 2022-08-25 2022-09-14 2022-09-30 2022-10-04 2022-10-20 2022-11-08 2023-04-07 preneurship nvelope mentation stics Management Firm ET-MINT-311777-NC-RFB / S 2. Digital government and c Single Stage - One E Under Imple upply and Installation of Very IDA / 68560 Post Request for Bids Limited 0.00 2022-09-15 2022-10-07 2022-09-20 2022-10-07 2022-10-20 2022-11-10 2022-11-09 2023-02-27 2022-12-14 2023-04-13 onnectivity nvelope mentation Small Aperture Terminal (VS AT) ET-MINT-345387-NC-RFB / S election of Event Organizer f 2. Digital government and c Single Stage - One E Pending Impl IDA / 68560 Post Request for Bids Open - National 0.00 2023-04-18 2023-04-23 2023-06-04 2023-07-04 2023-08-08 2024-02-04 or Telecom Capacity Building onnectivity nvelope ementation International Conference hel d in Ethiopia. ET-MINT-348049-NC-RFB / Pr 1. Digital economy, enabling inting and Distribution of Fay Single Stage - One E IDA / 68560 legal and regulatory environ Post Request for Bids Open - National 0.00 Canceled 2023-03-24 2023-03-29 2023-04-28 2023-05-28 2023-07-02 2023-10-30 da ID Pre-personalized Cards nvelope ment & Pilot for Credentials Person alization ET-MINT-354184-NC-RFB / Pr 1. Digital economy, enabling inting and Distribution of Fay Open - Internationa Single Stage - One E Under Imple IDA / 68560 legal and regulatory environ Post Request for Bids 0.00 2023-04-10 2023-05-10 2023-04-15 2023-05-27 2023-05-27 2023-06-26 2023-07-31 2023-10-29 da ID Pre-personalized Cards l nvelope mentation ment & Pilot for Credentials Person alization CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MINT/DE/QCBS/C-21/21 / Ass isting ECA in its role of monit 1. Digital economy, enabling oring market development, i Quality And Cost- Open - Internationa IDA / 68560 legal and regulatory environ Prior 0.00 Canceled 2021-07-15 2021-08-05 2021-09-18 2021-10-16 2021-11-15 2021-12-20 2022-01-24 2023-01-24 ncluding setting up an ICT in Based Selection l ment dicators unit, and training sta ff in data collection and analy sis MINT/DE/QCBS/C-21-1/21 / A ssistance to ECA on Advisory 1. Digital economy, enabling Services on Analysis of Whol Quality And Cost- Open - Internationa IDA / 68560 legal and regulatory environ Post 515,108.30 Signed 2021-07-28 2021-08-03 2021-08-18 2021-09-02 2021-10-01 2021-12-30 2021-10-29 2022-02-10 2021-11-28 2022-02-24 2022-01-02 2022-04-18 2022-02-06 2022-05-21 2023-02-06 esale and Retail Tariffs, Pote Based Selection l ment ntial Application of Price Cap s and Establishment of a Mar ket Analysis Unit (Firm) MINT/DE/QCBS/C-18/21 / Dat 1. Digital economy, enabling Quality And Cost- Under Implement a collection and study on gen IDA / 68560 legal and regulatory environ Post Open - National 0.00 2021-09-30 2022-02-10 2021-10-21 2022-03-10 2021-12-04 2022-05-06 2022-01-01 2022-07-07 2022-01-31 2022-08-15 2022-03-07 2022-11-01 2022-04-11 2023-04-11 Based Selection ation der disparities in the sector - ment MInT MINT/DE/QCBS/C-22/21 / Ass isting ECA to issue further cla 1. Digital economy, enabling Quality And Cost- Open - Internationa Pending Impleme ss licenses and authorization IDA / 68560 legal and regulatory environ Post 0.00 2021-09-27 2021-10-18 2021-12-01 2021-12-29 2022-01-28 2022-03-04 2022-04-08 2023-04-08 Based Selection l ntation s in specific market segment ment s, including broadcasting - E CA MINT/DE/QCBS/C-20/21 / Ass 1. Digital economy, enabling isting ECA with ensuring that Quality And Cost- Open - Internationa Pending Impleme IDA / 68560 legal and regulatory environ Prior 0.00 2021-09-30 2021-10-21 2021-12-04 2022-01-01 2022-01-31 2022-03-07 2022-04-11 2023-04-11 Ethio Telecom implements a Based Selection l ntation ment functional separation-ECA MINT/DE/QCBS/C-14/21 / Sup 1. Digital economy, enabling port to the government throu Quality And Cost- Open - Internationa Pending Impleme IDA / 68560 legal and regulatory environ Post 0.00 2021-09-20 2021-10-11 2021-11-24 2021-12-22 2022-01-21 2022-02-25 2022-04-01 2023-04-01 gh technical assistance for es Based Selection l ntation ment tablishing an internet Exchan ge - ECA MINT/DE/QCBS/C-11/21 / Co nsultancy Services for Gap A 2. Digital government and c Quality And Cost- Open - Internationa IDA / 68560 Prior 0.00 Under Review 2021-10-05 2022-02-23 2021-10-26 2022-03-15 2021-12-09 2022-07-19 2022-01-06 2022-09-20 2022-02-05 2022-12-27 2022-03-12 2022-04-16 2023-04-16 nalysis Study of Government onnectivity Based Selection l Bandwidth Needs MInT MINT/DE/QCBS/C-01/21 / Co 2. Digital government and c Quality And Cost- Open - Internationa Pending Impleme nsultancy Services for Portal IDA / 68560 Prior 0.00 2021-10-10 2021-10-31 2021-12-14 2022-01-11 2022-02-10 2022-03-17 2022-04-21 2023-04-21 onnectivity Based Selection l ntation Design - MInT MINT/DE/QCBS/C-17/21 / Sel ection of a Consulting Firm th 1. Digital economy, enabling Quality And Cost- Under Implement at develops legal framework IDA / 68560 legal and regulatory environ Post Open - National 0.00 2021-07-15 2022-05-06 2021-08-05 2022-06-30 2021-09-18 2021-10-16 2021-11-15 2021-12-20 2022-01-24 2022-07-23 Based Selection ation and Guidelines on Data Prote ment ction and digital ID - MInT ET-MINT-251133-CS-LCS / Se Least Cost Selecti Under Implement IDA / 68560 4. Project management Post Open - National 0.00 2021-11-15 2022-04-04 2021-12-06 2022-01-19 2022-04-20 2022-02-16 2022-05-17 2022-03-18 2022-06-29 2022-04-22 2022-07-31 2022-05-27 2022-11-23 lection of Financial Audit Fir on ation m ET-MINT-251968-CS-QCBS / Selection of a consulting firm 1. Digital economy, enabling that provides technical assist Quality And Cost- Open - Internationa Pending Impleme IDA / 68560 legal and regulatory environ Prior 0.00 2021-10-25 2021-11-15 2022-01-13 2022-02-10 2022-03-12 2022-04-16 2022-05-21 2024-05-20 ance for the establishment of Based Selection l ntation ment PMU to support in the area of the legal framework for data protection and digital ID-MoP ET-MINT-253910-CS-CQS / S electing a Consultant firm th at supports ECA in Transferri 1. Digital economy, enabling Consultant Qualifi Under Implement ng of responsibility for the .et IDA / 68560 legal and regulatory environ Post Open - National 0.00 2021-10-12 2023-03-23 2021-11-02 2023-05-19 2021-12-16 2022-01-15 2022-02-19 2022-08-18 cation Selection ation domain name management f ment rom Ethio Telecom to ECA, a nd managing the .gov.et sub- domain (by MInT) MINT/DE/QCBS/C-15/21 / Co 1. Digital economy, enabling Quality And Cost- Open - Internationa Pending Impleme nsultancy Services for Develo IDA / 68560 legal and regulatory environ Post 0.00 2021-09-30 2021-10-21 2021-12-04 2022-01-01 2022-01-31 2022-03-07 2022-04-11 2023-04-11 Based Selection l ntation ping Universal Service Fund ( ment USF) - ECA MINT/DE/QCBS/C-02/21 / Co nsultancy Services for Develo 2. Digital government and c Quality And Cost- Open - Internationa Pending Impleme ping online transaction syste IDA / 68560 Prior 0.00 2021-09-30 2021-10-21 2021-12-04 2022-01-01 2022-01-31 2022-03-07 2022-04-11 2023-04-11 onnectivity Based Selection l ntation ms for different Ministries an d Agencies /Phase-One/-MInT Page 3 ET-MINT-278360-CS-QCBS / Selection of a consulting firm 3. Digital business and entre Quality And Cost- Under Implement IDA / 68560 Post Open - National 0.00 2022-02-21 2022-02-14 2022-03-08 2022-04-06 2022-05-06 2022-05-26 2022-06-23 2022-07-13 2022-11-10 that develops legal framewor preneurship Based Selection ation k and guideline on Data prot ection and Digital ID ET-MINT-288456-CS-QCBS / Selection of a consulting firm 2. Digital government and c Quality And Cost- Open - Internationa Under Implement that provides Training on Clo IDA / 68560 Post 0.00 2022-04-25 2022-04-12 2022-05-10 2022-05-24 2022-06-13 2022-08-05 2022-06-28 2022-09-05 2022-07-28 2022-09-20 2022-09-01 2022-10-20 2022-10-06 2023-01-04 onnectivity Based Selection l ation ud Architect & Design, Power BI and Certification for EthER Net Staffs ET-MINT-307528-CS-QCBS / Selection of a consulting firm 1. Digital economy, enabling that undertakes Environment Quality And Cost- Under Implement IDA / 68560 legal and regulatory environ Post Open - National 0.00 2022-08-10 2022-08-08 2022-08-25 2022-09-11 2022-09-28 2023-03-09 2022-10-26 2022-11-25 2022-12-30 2023-02-03 2023-06-03 al and Social Management Fr Based Selection ation ment amework for Digital Identifica tion and Inclusion & Service Project (National ID) ET-MINT-307532-CS-QCBS / Selection of a consulting firm Quality And Cost- Under Implement that prepares a Resettlement IDA / 68560 4. Project management Post Open - National 0.00 2022-08-10 2022-08-08 2022-08-25 2022-09-28 2022-10-26 2022-11-25 2022-12-30 2023-02-03 2023-08-02 Based Selection ation Framework (RF) for the Imple mentation of Universal Acces s Fund (UAF) ET-MINT-309295-CS-QCBS / Sector Assessment and Imple 3. Digital business and entre Quality And Cost- Under Implement IDA / 68560 Post Open - National 0.00 2022-08-15 2022-09-06 2022-08-30 2022-10-13 2022-10-13 2022-11-10 2022-12-10 2023-01-14 2023-02-18 2024-02-18 mentation Plan for Window 2 preneurship Based Selection ation of Component 3.1 (Selection of a Consulting Firm) ET-MINT-320079-CS-QCBS / Selection of a consulting firm that support MInT in the Impl 3. Digital business and entre Quality And Cost- Open - Internationa Pending Impleme IDA / 68560 Post 0.00 2022-10-12 2022-11-02 2022-12-16 2023-01-13 2023-02-12 2023-03-19 2023-04-23 2024-04-22 ementation of National Digita preneurship Based Selection l ntation l Gateway (gov.et), Office aut omation & Technical Assistan ce ET-MINT-345230-CS-QCBS / 1. Digital economy, enabling Selection of a consulting firm Quality And Cost- Open - Internationa Pending Impleme IDA / 68560 legal and regulatory environ Post 0.00 2023-03-15 2023-04-05 2023-05-19 2023-06-16 2023-07-16 2023-08-20 2023-09-24 2024-03-22 that support the Pilot Authen Based Selection l ntation ment tication Platform & Mobile Ap plication ET-MINT-345377-CS-QCBS / 1. Digital economy, enabling Selection of third-party HR Fi Quality And Cost- Open - Internationa Under Implement IDA / 68560 legal and regulatory environ Prior 0.00 2023-03-20 2023-04-10 2023-05-24 2023-06-21 2023-07-21 2023-08-25 2023-09-29 2024-09-28 rm for supporting Pilots of dif Based Selection l ation ment ferent Registration Strategies for NID ET-MINT-345420-CS-QCBS / Selection of a consulting firm 2. Digital government and c Quality And Cost- Open - Internationa Under Implement IDA / 68560 Prior 0.00 2023-03-30 2023-04-20 2023-06-03 2023-07-01 2023-07-31 2023-09-04 2023-10-09 2024-10-08 that develops Addressing Sys onnectivity Based Selection l ation tem for Addis Ababa City (MI nT) ET-MINT-345612-CS-QCBS / Selection of a consulting firm 1. Digital economy, enabling that Develops a Plan for Impl Quality And Cost- Open - Internationa Pending Impleme IDA / 68560 legal and regulatory environ Prior 0.00 2023-03-30 2023-04-20 2023-06-03 2023-07-01 2023-07-31 2023-09-04 2023-10-09 2024-04-06 ementing Mobile Number Por Based Selection l ntation ment tability, Short Code Harmonization, a nd Migration Strategy ET-MINT-345635-CS-QCBS / Selection of a Consulting Fir 1. Digital economy, enabling m that supports ECA in devel Quality And Cost- Open - Internationa Pending Impleme IDA / 68560 legal and regulatory environ Prior 0.00 2023-04-25 2023-05-16 2023-06-29 2023-07-27 2023-08-26 2023-09-30 2023-11-04 2024-05-02 oping Telecommunication Inf Based Selection l ntation ment rastructure rollout project de sign and implementation for the Borderland Project ET-MINT-346868-CS-QCBS / Selection of a consulting firm 2. Digital government and c Quality And Cost- Open - Internationa Pending Impleme IDA / 68560 Prior 0.00 2023-04-25 2023-05-16 2023-06-29 2023-07-27 2023-08-26 2023-09-30 2023-11-04 2024-11-03 that upgrades and expanding onnectivity Based Selection l ntation of the National E-Service Syst em ET-MINT-346889-CS-QCBS / Selection of a Consulting Fir 3. Digital business and entre Quality And Cost- Open - Internationa Pending Impleme IDA / 68560 Prior 0.00 2023-03-31 2023-04-21 2023-06-04 2023-07-02 2023-08-01 2023-09-05 2023-10-10 2024-04-07 m that support the accelerati preneurship Based Selection l ntation on of program service for digi tal Startup (MInT) INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Actual Amount Invitation to Identifie Draft Negotiated Cont Component Review Type Method Contract Type Process Status Teams of Reference Signed Contract Contract Completion Description o. h (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ET-MINT-234123-CS-INDV / F inance Officer positions for th e Ethiopian Education and Re search Network (EthERNet) t Individual Consult o work under MoSHE reportin IDA / 68560 4. Project management Post Open 30,208.11 Terminated 2021-05-13 2021-05-25 2021-07-01 2021-06-29 2021-07-22 2021-06-29 2021-08-26 2021-08-10 2022-11-30 ant Selection g to PIU for 18 months durati on, subject to renewal based on performance. The estimat ed budget is for the 18 mont hs. Full time position. ET-MINT-234135-CS-INDV / I T Project Manager positions t o work under PIU initially for f Individual Consult Under Implement or 18 months duration, subje IDA / 68560 4. Project management Post Open 0.00 2021-05-13 2021-05-26 2021-07-01 2021-07-22 2021-08-26 2022-11-30 ant Selection ation ct to renewal based on perfor mance. The estimated budge t is for the 18 months. Full ti me position. ET-MINT-234179-CS-INDV / C ontract Management Speciali st is to work under the PIU ha ndling the overall project. To Individual Consult IDA / 68560 4. Project management Prior Open 0.00 Canceled 2021-05-13 2021-06-11 2021-07-01 2021-07-22 2021-08-26 2022-11-30 be contracted for 18 months ant Selection subject to renewal based on t he performance of the consul tant. The estimated budget is only for the 18 months. Full ti me position. ET-MINT-233870-CS-INDV / P Individual Consult IDA / 68560 4. Project management Prior Open 58,187.81 Signed 2021-05-25 2021-06-10 2021-06-16 2021-07-13 2021-06-23 2021-07-16 2021-07-07 2021-08-05 2022-11-30 rocurement Specialist ant Selection ET-MINT-233864-CS-INDV / P Individual Consult IDA / 68560 4. Project management Post Limited 67,369.19 Signed 2021-05-26 2021-05-26 2021-06-05 2021-06-01 2021-06-12 2021-06-14 2021-06-26 2021-07-18 2022-11-30 IU Manager ant Selection Page 4 ET-MINT-234125-CS-INDV / E Individual Consult IDA / 68560 4. Project management Post Open 50,346.85 Signed 2021-05-26 2021-05-26 2021-06-17 2021-07-04 2021-06-24 2021-07-08 2021-07-08 2021-07-29 2022-11-30 nvironmental Safeguards Spe ant Selection cialist ET-MINT-234131-CS-INDV / Individual Consult IDA / 68560 4. Project management Post Open 50,346.85 Signed 2021-05-26 2021-05-26 2021-06-17 2021-07-04 2021-06-24 2021-07-08 2021-07-08 2021-07-29 2022-11-30 M&E Specialist ant Selection ET-MINT-233871-CS-INDV / F Individual Consult IDA / 68560 4. Project management Post Open 58,737.99 Signed 2021-05-26 2021-05-26 2021-06-17 2021-07-04 2021-06-24 2021-07-08 2021-07-08 2021-07-29 2022-11-30 inancial Management Special ant Selection ist ET-MINT-234133-CS-INDV / F inance Officer positions to wo rk under PIU initially for for 1 Individual Consult 8 months duration, subject to IDA / 68560 4. Project management Post Open 30,208.11 Signed 2021-05-25 2021-05-26 2021-06-14 2021-07-04 2021-06-19 2021-07-08 2021-06-29 2021-07-29 2022-10-25 ant Selection renewal based on performan ce. The estimated budget is f or the 18 months. Full time p osition. MINT/DE/IC/C-61/21 / Websit Individual Consult Pending Impleme e Developer for the Digital Fo IDA / 68560 4. Project management Post Limited 0.00 2021-06-30 2021-07-05 2021-07-26 2021-08-30 2022-02-26 ant Selection ntation undation Project and support for one year ET-MINT-234130-CS-INDV / S Individual Consult IDA / 68560 4. Project management Post Open 0.00 Canceled 2021-05-26 2021-05-26 2021-06-17 2021-07-08 2021-06-24 2021-07-08 2022-11-30 ocial Safeguards Specialist ant Selection MINT/DE/IC/C-53/22 / Individ 1. Digital economy, enabling ual Consultant for Digital ID f Individual Consult IDA / 68560 legal and regulatory environ Post Open 0.00 Canceled 2022-01-10 2022-02-28 2022-03-21 2022-04-25 2023-07-30 or determination of significan ant Selection ment t market power (local IC spec ialist) MINT/DE/IC/C-50/22 / Individ 1. Digital economy, enabling ual Consultant for Digital ID f Individual Consult IDA / 68560 legal and regulatory environ Post Open 0.00 Canceled 2022-01-10 2022-02-28 2022-03-21 2022-04-25 2023-07-30 or determination of significan ant Selection ment t market power (Int. lawyer) MINT/DE/IC/C-51/22 / Individ 1. Digital economy, enabling ual Consultant for Digital ID f Individual Consult IDA / 68560 legal and regulatory environ Post Open 0.00 Canceled 2022-01-10 2022-02-28 2022-03-21 2022-04-25 2023-07-30 or determination of significan ant Selection ment t market power (Int.Economis t) MINT/DE/IC/C-52/22 / Individ 1. Digital economy, enabling ual Consultant for Digital ID f Individual Consult IDA / 68560 legal and regulatory environ Post Open 0.00 Canceled 2022-01-10 2022-02-28 2022-03-21 2022-04-25 2023-07-30 or determination of significan ant Selection ment t market power (local market researcher) ET-MINT-234130-CS-INDV-2 / Individual Consult Under Implement IDA / 68560 4. Project management Post Limited 0.00 2021-07-28 2022-05-10 2021-08-02 2021-08-23 2021-09-27 2022-12-30 Social Safeguards Specialist ant Selection ation ET-MINT-234179-CS-INDV-2 / Individual Consult Pending Impleme IDA / 68560 4. Project management Post Limited 0.00 2021-07-28 2021-08-02 2021-08-23 2021-09-27 2022-12-31 Contract Management Specia ant Selection ntation list MINT/DE/IC/C-21-1/21 / Assis tance to ECA in Conducting a 1. Digital economy, enabling Individual Consult Determination of Significant IDA / 68560 legal and regulatory environ Post Open 0.00 Canceled 2021-07-29 2021-07-28 2021-09-16 2021-09-30 2021-10-07 2021-11-11 2022-05-10 ant Selection Market Power (SMP), internat ment ional expert with expertise in telecom law and regulation MINT/DE/IC/C-21-2/21 / Assis tance to ECA in Conducting a 1. Digital economy, enabling Determination of Significant Individual Consult IDA / 68560 legal and regulatory environ Post Open 0.00 Canceled 2021-07-29 2021-07-28 2021-09-16 2021-09-30 2021-10-07 2021-11-11 2022-05-10 Market Power (SMP), internat ant Selection ment ional expert with expertise in the economics of telecommu nications MINT/DE/IC/C-21-4/21 / Assis tance to ECA in Conducting a 1. Digital economy, enabling Individual Consult Determination of Significant IDA / 68560 legal and regulatory environ Post Open 0.00 Canceled 2021-07-29 2021-07-28 2021-09-16 2021-09-30 2021-10-07 2021-11-11 2022-05-10 ant Selection Market Power (SMP), local ex ment pert with expertise in market analysis MINT/DE/QCBS/C-23-2/21 / T 1. Digital economy, enabling Individual Consult Pending Impleme echnical adviser for develop IDA / 68560 legal and regulatory environ Post Direct 0.00 2021-08-18 2021-08-28 2021-09-18 2021-10-23 2022-04-21 ant Selection ntation ment of Universal Service fra ment mework for ECA MINT/DE/QCBS/C-23-3/21 / L 1. Digital economy, enabling Individual Consult Pending Impleme egal and Regulatory Adviser f IDA / 68560 legal and regulatory environ Post Direct 0.00 2021-08-18 2021-08-28 2021-09-18 2021-10-23 2022-04-21 ant Selection ntation or Pricing and Interconnectio ment n for ECA MINT/DE/IC/C-54/21 / Chief T 2. Digital government and c Individual Consult Under Implement IDA / 68560 Post Open 0.00 2021-08-10 2021-09-29 2021-09-01 2021-09-08 2021-09-22 2023-03-16 echnical Officer at Ethernet onnectivity ant Selection ation MINT/DE/IC/C-55/21 / Senior 2. Digital government and c Individual Consult Under Implement IDA / 68560 Post Open 0.00 2021-09-20 2021-09-29 2021-10-12 2021-10-19 2021-11-02 2023-04-26 Security Engineer at Ethernet onnectivity ant Selection ation MINT/DE/IC/C-56/21 / Senior 2. Digital government and c Individual Consult Under Implement IDA / 68560 Post Open 0.00 2021-08-10 2021-09-29 2021-09-01 2021-09-08 2021-09-22 2023-03-16 Network Operations Engineer onnectivity ant Selection ation at Ethernet, MINT/DE/IC/C-57/21 / Senior 2. Digital government and c Individual Consult Under Implement IDA / 68560 Post Open 0.00 2021-09-22 2021-09-29 2021-10-14 2021-10-21 2021-11-04 2023-04-28 Systems Engineer at Etherne onnectivity ant Selection ation t ET-MINT-234121-CS-INDV / F 1. Digital economy, enabling Individual Consult Under Implement inance Officer at Ethiopian C IDA / 68560 legal and regulatory environ Post Open 0.00 2021-09-15 2022-05-06 2021-11-03 2021-11-24 2021-12-29 2022-12-29 ant Selection ation ommunication Authority (ECA ment ) MINT/DE/IC/C-32/21 / Develo 1. Digital economy, enabling Individual Consult Pending Impleme IDA / 68560 Post Open 0.00 2021-07-15 2021-09-02 2021-09-23 2021-10-28 2022-04-26 ping Guidelines on Data Prot legal and regulatory environ ant Selection ntation ection ment MINT/DE/IC/C-33/21 / Develo 1. Digital economy, enabling Individual Consult Pending Impleme ping Guidelines on Cybersec IDA / 68560 legal and regulatory environ Post Open 0.00 2021-09-24 2021-11-12 2021-12-03 2022-01-07 2022-07-06 ant Selection ntation urity and Privacy - MInT ment MINT/DE/IC/C-35/21 / Creatin 1. Digital economy, enabling Individual Consult Pending Impleme IDA / 68560 Post Open 0.00 2021-09-30 2021-11-18 2021-12-09 2022-01-13 2022-07-12 g a Dispute Resolution Mech legal and regulatory environ ant Selection ntation anism - ECA ment MINT/DE/IC/C-34/21 / Develo 1. Digital economy, enabling Individual Consult Pending Impleme ping Regulations to Support t IDA / 68560 legal and regulatory environ Post Open 0.00 2021-09-20 2021-11-08 2021-11-29 2022-01-03 2022-07-02 ant Selection ntation he Development of eCommer ment ce - MInT Page 5 MINT/DE/IC/C-37/21 / Develo pment of TOR and relevant d 2. Digital government and c Individual Consult Pending Impleme ocuments for Sub Componen IDA / 68560 Post Open 0.00 2021-09-23 2021-11-11 2021-12-02 2022-01-06 2022-07-05 onnectivity ant Selection ntation t 2.2 (Connecting Targeted P ublic Institutions to Broadban d) - MInT MINT/DE/IC/C-29/21 / Develo 1. Digital economy, enabling ping a communications plan, Individual Consult Pending Impleme IDA / 68560 legal and regulatory environ Post Open 0.00 2021-07-15 2021-09-02 2021-09-23 2021-10-28 2022-04-26 for the wider telecoms refor ant Selection ntation ment m process and especially for the privatization - ECA ET-MINT-253585-CS-INDV / S election of a consulting firm t 2. Digital government and c Individual Consult hat undertakes the review of IDA / 68560 Post Open 0.00 Canceled 2021-10-01 2021-11-19 2021-12-10 2022-01-14 2022-07-13 onnectivity ant Selection legal portfolio relating to Digi tal Business and Entrepreneu rship - MInT ET-MINT-253906-CS-INDV / S electing a consultant that su 1. Digital economy, enabling pports ECA in developing Qu Individual Consult Pending Impleme IDA / 68560 legal and regulatory environ Post Open 0.00 2021-09-30 2021-11-18 2021-12-09 2022-01-13 2022-07-12 ality of Service Measurement ant Selection ntation ment methodologies and Telecom munications Quality of Servic e Monitoring ET-MINT-253909-CS-INDV / S 1. Digital economy, enabling electing an individual consult Individual Consult Pending Impleme IDA / 68560 legal and regulatory environ Post Open 0.00 2021-09-30 2021-11-18 2021-12-09 2022-01-13 2023-01-08 ant that supports ECA in Tele ant Selection ntation ment communications Number Ma nagement ET-MINT-253918-CS-INDV / S 1. Digital economy, enabling election of an Individual Cons Individual Consult Pending Impleme IDA / 68560 legal and regulatory environ Post Open 0.00 2021-10-19 2021-12-07 2021-12-28 2022-02-01 2022-07-31 ultant that provides Legal Ad ant Selection ntation ment visory Service (IC) -ECA ET-MINT-253915-CS-INDV / L 1. Digital economy, enabling egal and Regulatory Adviser f Individual Consult Pending Impleme IDA / 68560 legal and regulatory environ Post Direct 0.00 2021-09-30 2021-10-10 2021-10-31 2021-12-05 2022-06-03 or Spectrum Planning and m ant Selection ntation ment anagement for ECA MINT/DE/IC/C-21-3/21 / Assis tance to ECA in Conducting a 1. Digital economy, enabling Individual Consult Determination of Significant IDA / 68560 legal and regulatory environ Post Open 0.00 Canceled 2021-07-29 2021-07-28 2021-09-16 2021-10-07 2021-11-11 2022-05-10 ant Selection Market Power (SMP), local ex ment pert with expertise in Ethiopi an law on competition ET-MINT-257279-CS-INDV / 1. Digital economy, enabling Individual Consult Under Implement IDA / 68560 Post Open 0.00 2021-10-25 2021-10-27 2021-11-28 2021-12-08 2021-12-28 2022-12-23 Hiring a Technical Director fo legal and regulatory environ ant Selection ation r MoP ment ET-MINT-257299-CS-INDV / 1. Digital economy, enabling Individual Consult Under Implement IDA / 68560 Post Open 0.00 2021-10-25 2021-10-27 2021-11-28 2021-12-08 2022-01-02 2022-12-28 Hiring of System Engineer for legal and regulatory environ ant Selection ation MoP ment ET-MINT-257300-CS-INDV / R 1. Digital economy, enabling Individual Consult Under Implement IDA / 68560 Post Open 0.00 2021-10-25 2021-10-27 2021-11-28 2021-12-08 2022-01-01 2022-12-27 ecruitment of Biometric Expe legal and regulatory environ ant Selection ation rt for MoP ment ET-MINT-257305-CS-INDV / R 1. Digital economy, enabling Individual Consult Under Implement ecruitment of Infrastructure IDA / 68560 legal and regulatory environ Post Open 0.00 2021-10-25 2021-10-27 2021-11-28 2021-12-08 2021-12-28 2022-12-23 ant Selection ation and Security Expert for MoP ment ET-MINT-257308-CS-INDV / R 3. Digital business and entre Individual Consult Pending Impleme IDA / 68560 Post Open 0.00 2021-11-15 2021-12-19 2021-12-29 2022-01-18 2023-01-13 ecruitment of Grant Manager preneurship ant Selection ntation for MinT ET-MINT-260063-CS-INDV / S 1. Digital economy, enabling election of Individual Consult Individual Consult Under Implement IDA / 68560 legal and regulatory environ Post Open 0.00 2021-10-27 2021-10-28 2021-11-21 2021-12-01 2021-12-21 2022-12-16 ants - Additional System Engi ant Selection ation ment neer for Digital ID Program ET-MINT-262727-CS-INDV / A 1. Digital economy, enabling Individual Consult Pending Impleme dvisor to ECA on Public Certif IDA / 68560 legal and regulatory environ Post Open 0.00 2021-11-11 2021-11-26 2021-12-01 2021-12-18 2022-06-16 ant Selection ntation ication Authority (CA) ment ET-MINT-262732-CS-INDV / A 1. Digital economy, enabling Individual Consult Pending Impleme dvisor for Internet Governanc IDA / 68560 legal and regulatory environ Post Open 0.00 2021-11-11 2021-11-26 2021-12-01 2021-12-18 2022-06-16 ant Selection ntation e and Domain Name System ment ET-MINT-262733-CS-INDV / S upport ECA to establish e-Co 1. Digital economy, enabling Individual Consult Pending Impleme mmerce Regulation and Activ IDA / 68560 legal and regulatory environ Post Open 0.00 2021-11-11 2021-11-26 2021-12-06 2021-12-26 2022-06-24 ant Selection ntation ities (Advisor for e-Commerc ment e Regulation and Activities) ET-MINT-297123-CS-INDV / S 1. Digital economy, enabling election of Individual Consult Individual Consult Under Implement IDA / 68560 legal and regulatory environ Post Open 0.00 2022-05-29 2022-06-01 2022-06-27 2022-07-07 2022-07-27 2023-07-22 ant for a position of Chief Inf ant Selection ation ment ormation Security Expert for National ID Program ET-MINT-297978-CS-INDV / F 2. Digital government and c Individual Consult Under Implement inance Officer for the Ethiopi IDA / 68560 Post Open 0.00 2022-06-06 2022-06-05 2022-07-06 2022-07-16 2022-08-05 2023-07-31 onnectivity ant Selection ation an Education and Research N etwork ET-MINT-301263-CS-INDV / S election of Individual Consult 3. Digital business and entre Individual Consult Under Implement ant - Digital Business Progra IDA / 68560 Post Open 0.00 2022-06-27 2022-07-11 2022-07-31 2022-12-22 2022-08-10 2022-12-22 2022-08-30 2023-08-25 preneurship ant Selection ation m Specialist that support the Digital Foundations Project ET-MINT-324775-CS-INDV / 2. Digital government and c Individual Consult Under Implement Hiring of Special Advisor for IDA / 68560 Post Limited 0.00 2022-11-07 2022-11-03 2022-11-17 2022-12-16 2022-12-08 2023-01-12 2024-01-07 onnectivity ant Selection ation Ministry of Education ET-MINT-324779-CS-INDV / 2. Digital government and c Individual Consult Under Implement Hiring of Project Manager for IDA / 68560 Post Open - National 0.00 2022-11-07 2022-11-03 2022-12-26 2023-01-16 2023-02-20 2024-02-15 onnectivity ant Selection ation EthERNeT Project under Minis try of Education ET-MINT-326790-CS-INDV / S election of an Individual Cons Individual Consult Under Implement IDA / 68560 4. Project management Post Open - National 0.00 2022-11-24 2022-12-12 2023-01-02 2023-03-30 2023-01-17 2023-04-03 2023-02-15 2024-02-10 ultant for the position of Moni ant Selection ation toring and Evaluation Special ist ET-MINT-326792-CS-INDV / S election of an individual cons Individual Consult Under Implement IDA / 68560 4. Project management Post Open - National 0.00 2022-11-24 2022-12-12 2023-01-02 2023-01-22 2023-02-20 2024-02-15 ultant for the position of Envi ant Selection ation ronmental and Social Safegu ard Specialist Page 6 ET-MINT-326794-CS-INDV / S election of an individual cons Individual Consult Under Implement IDA / 68560 4. Project management Post Open - National 0.00 2022-11-24 2022-12-12 2023-01-02 2023-01-23 2023-02-21 2024-02-16 ultant for the position of Cont ant Selection ation ract Managment Specialist ET-MINT-327952-CS-INDV / S 3. Digital business and entre Individual Consult election of a Senior Advisor f IDA / 68560 Post Limited 0.00 Signed 2022-11-25 2022-12-07 2022-11-30 2022-12-21 2022-12-21 2023-02-15 2023-01-25 2024-01-20 preneurship ant Selection or the Minister (MInT) ET-MINT-327953-CS-INDV / S Individual Consult Under Implement IDA / 68560 4. Project management Post Open - National 0.00 2022-11-25 2022-12-12 2022-12-29 2023-01-19 2023-02-23 2024-02-18 election of Social Safeguard ant Selection ation Specialist ET-MINT-328205-CS-INDV / S Individual Consult Under Implement election of Project Coordinato IDA / 68560 4. Project management Post Open - National 0.00 2022-11-30 2023-02-15 2023-01-18 2023-03-30 2023-02-08 2023-04-03 2023-03-15 2024-03-14 ant Selection ation r for PIU - New ET-MINT-328206-CS-INDV / S Individual Consult Under Implement election of Procurement Man IDA / 68560 4. Project management Prior Open - National 0.00 2022-11-30 2022-12-20 2023-01-18 2023-04-12 2023-02-08 2023-05-01 2023-03-15 2024-03-14 ant Selection ation agement Specialist for PIU -N ew ET-MINT-328207-CS-INDV / S Individual Consult Under Implement election of Finance Managem IDA / 68560 4. Project management Post Open - National 0.00 2022-11-30 2022-12-12 2023-01-18 2023-02-08 2023-03-15 2024-03-14 ant Selection ation ent Specialist for PIU - New ET-MINT-327950-CS-INDV / S 3. Digital business and entre Individual Consult election of Communication A IDA / 68560 Post Limited 0.00 Canceled 2022-11-25 2022-11-30 2022-12-21 2023-01-25 2024-01-20 preneurship ant Selection dvisor for the Minister (MInT) ET-MINT-329831-CS-INDV / S 3. Digital business and entre Individual Consult election of Technology Advis IDA / 68560 Post Open - National 0.00 Canceled 2022-12-05 2023-01-04 2023-01-14 2023-02-03 2024-01-29 preneurship ant Selection or for the Minster (MInT) ET-MINT-328204-CS-CDS / S Individual Consult Under Implement election of Procurement Man IDA / 68560 4. Project management Prior Direct - National 0.00 2022-12-11 2022-12-20 2022-12-21 2022-12-23 2022-12-26 2023-03-06 2023-01-10 2024-01-05 ant Selection ation agement Specialist ET-MINT-328203-CS-CDS / S Individual Consult Under Implement election of Finance Managem IDA / 68560 4. Project management Post Direct - National 0.00 2022-12-11 2022-12-12 2022-12-21 2022-12-21 2022-12-26 2022-12-22 2023-01-10 2024-01-05 ant Selection ation ent Specialist ET-MINT-330745-CS-INDV / S 3. Digital business and entre Individual Consult Under Implement election of Technology Advis IDA / 68560 Prior Limited 0.00 2022-12-11 2023-01-03 2022-12-16 2023-01-27 2022-12-26 2023-01-15 2024-01-10 preneurship ant Selection ation er for the Minister ET-MINT-345634-CS-INDV / S election of Individual Consult 1. Digital economy, enabling ant that support ECA in Unive Individual Consult Direct - Internation Pending Impleme IDA / 68560 legal and regulatory environ Post 0.00 2023-03-20 2023-03-30 2023-04-20 2023-05-25 2024-05-19 rsal Access and Service Rural ant Selection al ntation ment Telecommunication Infrastru cture and Service Project Des ign and Implementation ET-MINT-345638-CS-INDV / S 1. Digital economy, enabling election of Technology Advis Individual Consult Under Implement IDA / 68560 legal and regulatory environ Post Limited 0.00 2023-03-07 2023-03-13 2023-03-12 2023-03-28 2023-03-27 2023-04-25 2024-04-19 or that support Ethiopian Cap ant Selection ation ment ital market Authority ET-MINT-347469-CS-INDV / S 3. Digital business and entre Individual Consult Under Implement election of Communication A IDA / 68560 Post Open - National 0.00 2023-04-25 2023-03-23 2023-06-13 2023-07-04 2023-08-08 2024-08-07 preneurship ant Selection ation dvisor for MInT ET-MINT-328202-CS-CDS / S Individual Consult election of Advisor Project M IDA / 68560 4. Project management Post Direct - National 0.00 Canceled 2022-12-11 2022-12-12 2022-12-21 2022-12-21 2022-12-26 2022-12-22 2023-01-10 2024-01-05 ant Selection anager for EDFP - PIU ET-MINT-345637-CS-CDS / S 1. Digital economy, enabling election of a training firm tha Direct - Internation Pending Impleme IDA / 68560 legal and regulatory environ Prior Direct Selection 0.00 2023-04-25 2023-05-05 2023-07-09 2024-07-03 t provides a tailored training al ntation ment program for ECA staff and Ma nagement. ET-MINT-257304-CS-INDV / R 1. Digital economy, enabling Individual Consult ecruitment of Ecosystem Dev IDA / 68560 legal and regulatory environ Post Open 0.00 Canceled 2021-10-25 2021-11-28 2021-12-08 2022-01-08 2023-01-03 ant Selection elopment Expert for MoP ment ET-MINT-257307-CS-INDV / 1. Digital economy, enabling Individual Consult IDA / 68560 Post Open 0.00 Canceled 2021-10-25 2021-11-28 2021-12-08 2021-12-28 2022-12-23 Hiring of Legal Specialist for legal and regulatory environ ant Selection MoP ment ET-MINT-362721-CS-INDV / S Individual Consult election of Procurement Man IDA / 68560 4. Project management Prior Open - National 0.00 Under Review 2023-05-26 2023-06-22 2023-06-25 2023-07-05 2023-07-25 2024-07-24 ant Selection agement Specialist for EDFP - PIU ET-MINT-362726-CS-INDV / S election of Project Coordinato 1. Digital economy, enabling Individual Consult Under Implement r for the new upcoming proje IDA / 68560 legal and regulatory environ Post Open - National 0.00 2023-05-31 2023-06-16 2023-07-19 2023-08-09 2023-09-13 2024-09-12 ant Selection ation ct called "Digital Identity for I ment nclusion and Service Delivery " under National ID ET-MINT-362728-CS-INDV / S election of Procurement Spec 1. Digital economy, enabling Individual Consult ialist for the new upcoming p IDA / 68560 legal and regulatory environ Prior Open - National 0.00 Under Review 2023-05-31 2023-06-21 2023-07-19 2023-08-09 2023-09-13 2024-09-12 ant Selection roject called "Digital Identity ment for Inclusion and Service Deli very" under National ID ET-MINT-362729-CS-INDV / S election of Financial Specialis 1. Digital economy, enabling Individual Consult Under Implement t for the new upcoming proje IDA / 68560 legal and regulatory environ Post Open - National 0.00 2023-05-31 2023-06-16 2023-07-19 2023-08-09 2023-09-13 2024-09-12 ant Selection ation ct called "Digital Identity for I ment nclusion and Service Delivery " under National ID ET-MINT-362730-CS-INDV / S election of Environmental an 1. Digital economy, enabling d Social Safeguarde Specialis Individual Consult Under Implement IDA / 68560 legal and regulatory environ Post Open - National 0.00 2023-05-31 2023-06-16 2023-07-19 2023-08-09 2023-09-13 2024-09-12 t for the new upcoming proje ant Selection ation ment ct called "Digital Identity for I nclusion and Service Delivery " under National ID ET-MINT-362731-CS-INDV / S election of Planning, Monitori 1. Digital economy, enabling ng and Evaluation Specialist f Individual Consult Under Implement IDA / 68560 legal and regulatory environ Post Open - National 0.00 2023-05-31 2023-06-16 2023-07-19 2023-08-09 2023-09-13 2024-09-12 or the new upcoming project ant Selection ation ment called "Digital Identity for Inc lusion and Service Delivery" under National ID Page 7 PROCUREMENT PLAN (Textual Part) Project Country: Kyrgyz Republic information Full Project Name: Regional Economic Development Project (RED) Total Finance ($): USD 60,000,000 Project Number: P167428 Project Implementation agency Community Development and Investment Agency of the Kyrgyz Republic (ARIS) Date of the Procurement Plan February 5, 2020 Period covered by this Procurement September 2020 – December, 2026 Plan: Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016, revised November 2017 and August 2018) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), procurement under World Bank financed operations may be carried out in accordance with “Single-Stage Bidding” method set forth in the Public Procurement Law of the Kyrgyz Republic dated April 3, 2015 № 72 (the “PPL”) with amendments dated November 18, 2016 No. 182, December 10, 2016 No. 195, February 14, 2017 No. 25, May 30, 2017 No. 93, March 29, 2018 No. 32, January 11, 2019 No. 4, June 26, 2019 No. 76, provided that such arrangements continue to meet requirements of the paragraph 5.4 of the Procurement Regulations and the following conditions: • The request for bids/request for proposals document shall require that bidders/proposers submitting bids/proposals present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, Bank Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights; • Bidding documents, including contract forms, acceptable to the Bank shall be used. Bidding documents shall include provisions, as agreed with the Bank, intended to adequately mitigate against environmental, social, health and safety (“ESHS”) risks and impacts. • The Bidding process shall not be cancelled solely on the reason that minimum bid price is larger than the amount allocated by procuring entity for the procurement. • There shall be no preference applied during procurement of goods and works. • Implementing agency shall have an option to publish procurement notice without disclosing cost estimate. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Other national procurement arrangements such as “Simplified Method” (Request for Quotation) may be applied on the same conditions stated above for procuring limited quantities of readily available off-the-shelf goods or simple civil works of small value. In addition, not less than three quotations shall be requested to ensure competition. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: is not applicable; Works: is not applicable. PROCUREMENT Kyrgyz Republic : Kyrgyz Republic Regional Economic Development Project PLAN General Information Country: Kyrgyz Republic 2021-03-03 Bank’s Approval Date of the Original Procurement Plan: 2023-06-01 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P167428 GPN Date: 2020-09-16 Project Name: Kyrgyz Republic Regional Economic Development Project Loan / Credit No: IDA / 65580 Community Development and Investment Agency Executing Agency(ies): WORKS Activity Reference No. / Procureme Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH Ri Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method nt Docume ount (US$ and Recommendation Signed Contract o. h cess (Y/N) sk atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion nt Type ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IDA-REDP-W-RFQ-2021-1 / O Improving Regional Economi Request for Quota Single Stage - One E Pending Imp 2023-07-2 ffice repair for Osh technical IDA / 65580 c Planning and Regulatory F Post Open - National 0.00 2021-06-10 2021-07-23 tions nvelope lementation 3 agricultural college unctions IDA-REDP-W-RFQ-2021-2 / O Improving Regional Economi Request for Quota Single Stage - One E Pending Imp 2022-07-2 IDA / 65580 Post Open - National 0.00 2021-06-10 2021-07-23 ffice repair of Laboratory IST c Planning and Regulatory F tions nvelope lementation 3 A unctions IDA-REDP-W-RFQ-2021-3 / R Improving Regional Economi Request for Quota Single Stage - One E Pending Imp 2022-07-2 econstruction of driving field IDA / 65580 c Planning and Regulatory F Post Open - National 0.00 2021-06-10 2021-07-16 tions nvelope lementation 3 s for Osh technical agricultur unctions al college IDA-REDP-W-RFB-2021-4 / Pr Catalyzing Investments for T ovision of tourism services a Single Stage - One E Pending Imp 2023-09-1 IDA / 65580 ourism and Urban Developm Post Request for Bids Open - National 0.00 2021-06-10 2021-06-10 2021-07-15 2021-08-05 2021-08-22 nd amenities (eg. rest stops) nvelope lementation 1 ent along the main circuits IDA-REDP-W-RFQ-2021-8 / O Improving Regional Economi Request for Quota Single Stage - One E Pending Imp 2023-01-2 ffice repair for Osh technolog IDA / 65580 c Planning and Regulatory F Post Open - National 0.00 2021-12-17 2022-01-22 tions nvelope lementation 9 ical university unctions IDA-REDP-W-RFB-2021-6 / S uleiman-Too Museum and Co mplex upgrading and Uzgen Catalyzing Investments for T Open - Internationa Single Stage - Two E Pending Imp 2023-11-0 Museum and grounds upgrad IDA / 65580 ourism and Urban Developm Prior Request for Bids 0.00 2021-06-13 2021-06-18 2021-07-30 2021-10-12 2021-11-16 l nvelope lementation 6 ing (including infra, services, ent exhibition organization, mus eum site and visitor manage ment plan etc.) IDA-REDP-W-RFB-2021-7 / A Catalyzing Investments for T Single Stage - One E Pending Imp 2023-12-2 bshir-Ata: Kara-Shoro Park Ky IDA / 65580 ourism and Urban Developm Post Request for Bids Open - National 0.00 2021-06-13 2021-06-13 2021-08-01 2021-08-22 2021-09-11 nvelope lementation 0 rgyz-Ata: infrastructure impr ent ovement IDA-REDP-W-RFQ-2022-9 / O Improving Regional Economi Request for Quota Single Stage - One E Pending Imp 2023-07-3 IDA / 65580 Post Open - National 0.00 2022-06-17 2022-07-30 ffice repair of Interdistrict La c Planning and Regulatory F tions nvelope lementation 0 boratories unctions IDA-REDP-W-RFB-2021-5 / " Osh City downtown and key and Uzgen City urban regen Catalyzing Investments for T Open - Internationa Single Stage - Two E 2023-11-0 eration (roads, parks and oth IDA / 65580 ourism and Urban Developm Prior Request for Bids 0.00 Canceled 2021-06-13 2021-06-18 2021-07-30 2021-10-12 2021-11-16 l nvelope 6 er public spaces, utilities, etc ent .) (roads, parks and other pu blic spaces, pedestrian bridges a cross river, utilities, etc.)" IDA-REDP-W-RFB-2022-14 / Catalyzing Investments for T Other (with fi Construction works: Tynchtyk Open - Internationa Single Stage - One E Pending Imp 2023-09-0 IDA / 65580 ourism and Urban Developm Post Request for Bids eld for expla 0.00 2022-11-15 2022-12-04 2023-01-03 2023-01-24 2023-03-05 park, park near the stadium, l nvelope lementation 1 ent nation) stadium, park bridge. IDA-REDP-W-RFB-2022-11 / I mprove and landscape the le Catalyzing Investments for T Other (with fi ft and right banks and shore Single Stage - One E 2024-04-2 IDA / 65580 ourism and Urban Developm Post Request for Bids Open - National eld for expla 0.00 Canceled 2023-01-23 2023-01-27 2023-01-31 2023-03-02 2023-04-01 2023-04-23 strengthening works at the A nvelope 2 ent nation) k-Bura river in Osh city starti ng from Navoi street to Vakh apov street IDA-REDP-W-RFB-2022-11/1 / Procurement of works for wi Request for B dening the sidewalk with lan Catalyzing Investments for T ids - Small W Single Stage - One E Under Imple 2024-05-1 dscaping and improvement o IDA / 65580 ourism and Urban Developm Post Request for Bids Open - National orks SPD (1 e 0.00 2023-01-31 2023-02-01 2023-02-05 2023-02-01 2023-03-19 2023-04-18 2023-05-23 nvelope mentation 7 f the coast of the Ak-Buura ri ent nvelope proc ver at the section of B. Nurm ess) atov and A. Navoi streets (on the part of Tileke-Batyr stree t) IDA-REDP-W-RFB-2022-10 / Catalyzing Investments for T Other (with fi Construction works: Open - Internationa Single Stage - One E 2023-04-0 IDA / 65580 ourism and Urban Developm Post Request for Bids eld for expla 0.00 Canceled 2022-06-17 2022-07-06 2022-08-05 2022-08-15 2022-10-05 Theater park, Toktogul theat l nvelope 3 ent nation) er and Navoi park. IDA-REDP-W-RFB-2023-1 / I mprovement of the territory Catalyzing Investments for T Other (with fi Single Stage - One E Pending Imp 2023-08-2 of the Osh National Drama T IDA / 65580 ourism and Urban Developm Post Request for Bids Open - National eld for expla 0.00 2023-04-14 2023-04-19 2023-05-31 2023-06-30 2023-08-04 nvelope lementation 8 heater named after S. Ibraim ent nation) ov located on the street. Kur manzhan-Datka IDA-REDP-W-RFB-2023-2 / R Catalyzing Investments for T Other (with fi econstruction of the central s Single Stage - One E Pending Imp 2023-09-1 IDA / 65580 ourism and Urban Developm Post Request for Bids Open - National eld for expla 0.00 2023-04-21 2023-04-26 2023-06-07 2023-07-07 2023-08-11 quare of Osh city on Lenin St nvelope lementation 6 ent nation) reet No. 220/2 in MTU No. 2 Sulaiman-Too IDA-REDP-W-RFB-2023-3 / R epair of the existing building of the summer theater name Catalyzing Investments for T Other (with fi d after T. Satylganov with th Single Stage - One E Pending Imp 2024-02-0 IDA / 65580 ourism and Urban Developm Post Request for Bids Open - National eld for expla 0.00 2023-04-21 2023-04-26 2023-06-07 2023-07-07 2023-08-11 e construction of a canopy fo nvelope lementation 7 ent nation) r the auditorium of the summ er theater at the address: Le nina str. b/n in MTU № 2 "Sul aiman-Too" Osh city IDA-REDP-W-RFB-2022-12 / Construction works: Zones b Catalyzing Investments for T Other (with fi Open - Internationa Single Stage - One E Pending Imp 2023-07-0 etween residential quarters / IDA / 65580 ourism and Urban Developm Post Request for Bids eld for expla 0.00 2022-09-15 2022-10-04 2022-10-24 2022-11-23 2023-01-03 l nvelope lementation 2 blocks, wall painting (mosaic) ent nation) , northern part of Lenin stree t. Page 1 IDA-REDP-W-RFB-2023-4 / R Catalyzing Investments for T Other (with fi econstruction of the park on Single Stage - One E Pending Imp 2024-08-2 IDA / 65580 ourism and Urban Developm Post Request for Bids Open - National eld for expla 0.00 2023-05-15 2023-05-20 2023-07-01 2023-07-31 2023-09-04 Sai Boyu Street b/n in MTU № nvelope lementation 9 ent nation) 2 "Sulaiman-Too" of Osh city IDA-REDP-RFB-WORKS-VC"A PPLE"-2023-1 / Rehabilitation Other (with fi Strengthening Agri-Food Sup Single Stage - Two E Pending Imp 2024-05-3 works for the leader of the V IDA / 65580 Post Request for Bids Open - National eld for expla 0.00 2023-06-30 2023-07-05 2023-08-16 2023-10-29 2023-12-03 ply Chains and SMEs nvelope lementation 1 C "Apple" and for the benefic nation) iaries of the VC "Apple" (2 Lo ts) GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IDA-REDP-GOODS-RFQ-2020 Improving Regional Economi Request for Quota Single Stage - One E Pending Impl -1 / PCs for the office of infor IDA / 65580 c Planning and Regulatory F Post Open - National 0.00 2020-12-20 2021-02-16 2021-08-15 tions nvelope ementation mation market system unctions IDA-REDP-GOODS-RFQ-2021 Improving Regional Economi Request for Quota Single Stage - One E Pending Impl IDA / 65580 Post Open - National 0.00 2021-12-15 2022-01-23 2022-04-23 -5 / Tractor with equipment c Planning and Regulatory F tions nvelope ementation unctions IDA-REDP-GOODS-RFQ-2022 Improving Regional Economi Request for Quota Single Stage - One E Pending Impl -11 / Special vehicle for testi IDA / 65580 c Planning and Regulatory F Post Open - National 0.00 2022-02-23 2022-04-23 2022-10-20 tions nvelope ementation ng points of expertise of crop unctions s IDA-REDP-GOODS-RFB-2022- 12 / Abshir-Ata, Kara-Shoro P ark, Kyrgyz-Ata: goods for to Catalyzing Investments for T Open - Internationa Single Stage - One E Pending Impl urist infrastructure upgrading IDA / 65580 ourism and Urban Developm Post Request for Bids 0.00 2022-01-13 2022-01-18 2022-03-01 2022-03-31 2022-05-05 2023-04-30 l nvelope ementation and solid waste management ent improvements ; Trucks and b ins for Kyrgyz-Ata, Abshyr-At a, Karashoroo IDA-REDP-GOODS-RFB-2022- Improving Regional Economi 9 / Mechanization and electrif Single Stage - One E Pending Impl IDA / 65580 c Planning and Regulatory F Post Request for Bids Open - National 0.00 2022-08-11 2022-08-11 2022-08-25 2022-08-28 2022-09-16 2022-12-15 ication of agriculture for Osh nvelope ementation unctions technical agricultural college IDA-REDP-GOODS-RFQ-2022 Improving Regional Economi Request for Quota Single Stage - One E Pending Impl -10 / Promotion materials for IDA / 65580 c Planning and Regulatory F Post Open - National 0.00 2022-06-26 2022-07-30 2022-11-06 tions nvelope ementation National Stakeholders platfor unctions m IDA-REDP-GOODS-RFB-2022- Catalyzing Investments for T 13 / Furniture, goods and exi Open - Internationa Single Stage - One E Pending Impl IDA / 65580 ourism and Urban Developm Post Request for Bids 0.00 2022-08-10 2022-08-15 2022-09-26 2022-10-26 2022-11-30 2023-05-29 bition equipment for Suleimq l nvelope ementation ent n-Too and Uzgen museums IDA-REDP-GOODS-RFQ-2021 Improving Regional Economi Request for Quota Single Stage - One E Pending Impl -6 / Software for information IDA / 65580 c Planning and Regulatory F Post Open - National 0.00 2021-12-12 2022-01-20 2022-04-20 tions nvelope ementation market system unctions IDA-REDP-GOODS-RFB-2023- 18 / Purchase of goods (traini ng materials, printed materia Supporting Tourism and Rur Single Stage - Two E Pending Impl ls, etc.) for training in the hos IDA / 65580 al Development through Sm Post Request for Bids Open - National 0.00 2022-01-02 2022-01-07 2022-02-18 2022-05-03 2022-06-07 2022-12-04 nvelope ementation pitality industry for tour guid all Grants es, tour operators and mana gers / accommodation perso nnel. Technical support IDA-REDP-GOODS-RFB-2023- Improving Regional Economi Single Stage - One E 15 / Goods for Implementatio IDA / 65580 c Planning and Regulatory F Post Request for Bids Open - National 0.00 Canceled 2023-01-10 2023-01-17 2023-01-31 2023-02-21 2023-03-10 2023-09-06 nvelope n of acitivities suggested by t unctions he REDP IDA-REDP-GOODS-RFB-2023- Improving Regional Economi Single Stage - One E 16 / Goods for regional onlin IDA / 65580 c Planning and Regulatory F Post Request for Bids Open - National 0.00 Canceled 2023-01-10 2023-01-17 2023-01-31 2023-02-21 2023-03-10 2023-09-06 nvelope e platform development unctions IDA-REDP-GOODS-RFB-2021- Catalyzing Investments for T Open - Internationa Single Stage - One E 7 / Goods for Branding, mark IDA / 65580 ourism and Urban Developm Post Request for Bids 0.00 Canceled 2021-10-01 2021-10-06 2021-11-17 2021-12-17 2022-01-21 2022-04-21 l nvelope eting and promotion activitie ent s for Osh region IDA-REDP-GOODS-RFB-2022- 14 / Ensuring the product de Catalyzing Investments for T Open - Internationa Single Stage - One E velopment at the regional lev IDA / 65580 ourism and Urban Developm Post Request for Bids 0.00 Canceled 2022-03-10 2022-03-13 2022-04-24 2022-05-24 2022-06-28 2022-12-25 l nvelope el (fairs, exhibitions, PR, med ent ia campaigns, cultural events , forums) IDA-REDP-GOODS-RFB-2023- Improving Regional Economi Single Stage - One E Pending Impl 20 / Goods for regional onlin IDA / 65580 c Planning and Regulatory F Post Request for Bids Open - National 0.00 2023-01-10 2023-01-15 2023-02-04 2023-02-24 2023-03-10 2023-09-06 nvelope ementation e platform development unctions IDA-REDP-GOODS-RFB-2023- Improving Regional Economi Open - Internationa Single Stage - One E Pending Impl 19 / Goods for Implementatio IDA / 65580 c Planning and Regulatory F Post Request for Bids 0.00 2023-01-10 2023-01-15 2023-01-30 2023-02-14 2023-03-21 2023-09-17 l nvelope ementation n of acitivities suggested by t unctions he REDP IDA-REDP-GOODS-RFQ-2021 -4 / Printing of education mat erials on veterinary, artificial Improving Regional Economi Request for Quota Single Stage - One E Pending Impl insemination, mechanization IDA / 65580 c Planning and Regulatory F Post Open - National 0.00 2022-07-05 2022-08-13 2022-11-11 tions nvelope ementation and electrification of agricult unctions ure for Osh agricolledge and printing education materials f or Osh technological universi ty IDA-REDP-GOODS-RFB-2022- 15 / Ensuring the product de Catalyzing Investments for T Open - Internationa Single Stage - One E Pending Impl velopment at the regional lev IDA / 65580 ourism and Urban Developm Post Request for Bids 0.00 2022-03-10 2022-03-15 2022-04-24 2022-05-24 2022-06-26 2022-12-25 l nvelope ementation el (fairs, exhibitions, PR, med ent ia campaigns, cultural events , forums). IDA-REDP-GOODS-RFQ-2022 Catalyzing Investments for T -17 / Handouts for participant Request for Quota Single Stage - One E IDA / 65580 ourism and Urban Developm Post Open - National 0.00 Canceled 2022-09-13 2022-09-28 2022-10-28 s of the Regional Tourism For tions nvelope ent um "Sustainable Tourism De velopment Together" IDA-REDP-PP-GOODS-RFQ-20 23-1/1 / Apple tree seedlings Strengthening Agri-Food Sup Request for Quota Single Stage - One E IDA / 65580 Post Open - National 0.00 Canceled 2023-01-27 2023-02-26 2023-03-10 for "Apple" Productive Partne ply Chains and SMEs tions nvelope rship : Golden Delicious (M9 r ootstock) Page 2 IDA-REDP-PP-GOODS-RFQ-20 23-1/3 / Apple tree seedlings Strengthening Agri-Food Sup Request for Quota Single Stage - One E for "Apple" Productive Partne IDA / 65580 Post Open - National 0.00 Canceled 2023-01-27 2023-02-23 2023-08-22 ply Chains and SMEs tions nvelope rship : Red Chif (MM 106 root stock),Red Chif (M9 rootstock ), Gala Must (M9 rootstock) IDA-REDP-PP-GOODS-RFQ-20 23-1/4 / Apple trees seedling Strengthening Agri-Food Sup Request for Quota Single Stage - One E s for "Apple" Productive Par IDA / 65580 Post Open - National 0.00 Canceled 2023-02-10 2023-03-09 2023-09-05 ply Chains and SMEs tions nvelope tnership for IE Boydonov S. a nd СHС "Baglan": Gala (M9 r ootstock) IDA-REDP-PP-GOODS-RFQ-20 23-2/1 / Cherry tree seedling for "Acoustic fruit and vegeta Strengthening Agri-Food Sup Request for Quota Single Stage - One E ble freezing" Product Partner IDA / 65580 Post Open - National 0.00 Canceled 2023-01-27 2023-02-23 2023-08-22 ply Chains and SMEs tions nvelope ship: Cordia (Maxma 14 roots tock), Valovaya 3 (cherry ro otstock), Regina (Maxma 14 r ootstock) IDA-REDP-PP-GOODS-RFQ-20 23-2/3 / Pear tree seedlings f or "Acoustic fruit and vegeta Strengthening Agri-Food Sup Request for Quota Single Stage - One E IDA / 65580 Post Open - National 0.00 Canceled 2023-01-27 2023-02-23 2023-03-10 ble freezing" Product Partner ply Chains and SMEs tions nvelope ship: Santa Maria (ВА 29 Po llinator), Carmen (ВА 29 Polli nator),Williams (ВА 29 Pollina tor) IDA-REDP-PP-GOODS-RFQ-20 23-2/4 / Seedlings of remont Strengthening Agri-Food Sup Request for Quota Single Stage - One E ant strawberries for "Acousti IDA / 65580 Post Open - National 0.00 Canceled 2023-01-27 2023-02-23 2023-08-22 ply Chains and SMEs tions nvelope c fruit and vegetable freezing " Product Partnership: Clery, Black Prince IDA-REDP-PP-GOODS-RFQ-20 23-1/5 / Apple trees seedling Strengthening Agri-Food Sup Request for Quota Single Stage - One E s for "Apple" Productive Par IDA / 65580 Post Open - National 0.00 Canceled 2023-02-10 2023-03-09 2023-09-05 ply Chains and SMEs tions nvelope tnership for "Termez" Agricu ltural Production Cooperative : Gala (M9 rootstock) IDA-REDP-PP-GOODS-RFQ-20 23-1/2 / Cherry tree seedling Strengthening Agri-Food Sup Request for Quota Single Stage - One E IDA / 65580 Post Open - National 0.00 Canceled 2023-01-27 2023-02-23 2023-03-10 s for "Apple" Productive Part ply Chains and SMEs tions nvelope nership : Regina, Cordia (Max ma 14 rootstock) IDA-REDP-PP-GOODS-RFQ-20 23-1/6 / Apple tree seedlings Strengthening Agri-Food Sup Request for Quota Single Stage - One E IDA / 65580 Post Open - National 0.00 Canceled 2023-01-27 2023-02-23 2023-03-10 for "Apple" Productive Partn ply Chains and SMEs tions nvelope ership for LLC "Agrocomplex ": Gala (M9 rootstock) IDA-REDP-PP-GOODS-RFQ-20 23-2/5 / Seedlings for "Acous Strengthening Agri-Food Sup Request for Quota Single Stage - One E tic fruit and vegetable freezin IDA / 65580 Post Open - National 0.00 Canceled 2023-01-27 2023-02-23 2023-08-22 ply Chains and SMEs tions nvelope g" Product Partnership of Plu m Leto and Raspberry Polka IDA-REDP-PP-GOODS-RFQ-20 23-1/7 / Apple tree seedlings Strengthening Agri-Food Sup Request for Quota Single Stage - One E IDA / 65580 Post Open - National 0.00 Canceled 2023-02-06 2023-03-01 2023-03-10 for "Apple" Productive Partne ply Chains and SMEs tions nvelope rship : Golden Delicious (M9 r ootstock) IDA-REDP-PP-GOODS-RFQ-20 23-1/8 / Apple tree seedlings Strengthening Agri-Food Sup Request for Quota Single Stage - One E for "Apple" Productive Partn IDA / 65580 Post Open - National 0.00 Canceled 2023-02-06 2023-03-01 2023-03-10 ply Chains and SMEs tions nvelope ership for LLC "Agrocomplex ": Red Chif (M9 rootstock) IDA-REDP-GOODS-RFB-2022- Catalyzing Investments for T Open - Internationa Single Stage - One E Pending Impl 17 / Goods for Branding,mark IDA / 65580 ourism and Urban Developm Post Request for Bids 0.00 2022-01-23 2022-01-28 2022-03-11 2022-04-10 2022-05-15 2022-11-11 l nvelope ementation eting and promotion activitie ent s for Osh region IDA-REDP-GOODS-RFQ-2021 -3 / Printing of materials for d evelopment of information m Improving Regional Economi arket system and for MinAgri, Request for Quota Single Stage - One E Pending Impl IDA / 65580 c Planning and Regulatory F Post Open - National 0.00 2022-07-22 2022-08-30 2022-11-28 Osh obl administration and 7 tions nvelope ementation unctions laborotories, market fairs, 6 border control points, soil agr ochemical map and its e-cad astre and 7 centers IDA-REDP-GOODS-RFB-2021- 2 / Laboratory equipment (for 7 sampling points for laborat ory testing, for 7 border cont Improving Regional Economi Open - Internationa Single Stage - Two E Pending Impl rol points, for 2 phytosanitar IDA / 65580 c Planning and Regulatory F Prior Request for Bids 0.00 2021-12-12 2021-12-17 2022-01-28 2022-04-12 2022-05-17 2022-11-13 l nvelope ementation y laboratories under GosStan unctions dard, food kaboratory (Sanep idnadzor), Venerinary Service and CoCommerse and small f ood laboratories etc... IDA-REDP-GOODS-RFB-2023- 10 / Laboratory equipment fo r laboratories of veterinary di Improving Regional Economi Single Stage - One E Pending Impl agnostics and examination, d IDA / 65580 c Planning and Regulatory F Post Request for Bids Open - National 0.00 2023-04-28 2023-05-03 2023-06-14 2023-07-14 2023-08-18 2024-02-14 nvelope ementation isease prevention and state s unctions anitary and epidemiological s upervision, standardization a nd metrology IDA-REDP-GOODS-RFB-2022- 8 / Office equipment, furnitur e for laboratory (ISTA) for on Improving Regional Economi testing points of expertise of Open - Internationa Single Stage - One E Pending Impl IDA / 65580 c Planning and Regulatory F Post Request for Bids 0.00 2022-02-23 2022-02-28 2022-04-11 2022-05-11 2022-06-15 2022-12-12 crops; Office equipment, furn l nvelope ementation unctions iture for 7 sampling points fo r laboratory testing; Office eq uipment, furniture for 7 bord er control points and etc. IDA-REDP-GOODS-RFQ-2023 -9 / Household equipment an d diesel generator for laborat Improving Regional Economi Request for Quota Single Stage - One E Pending Impl ories of veterinary diagnostic IDA / 65580 c Planning and Regulatory F Post Open - National 0.00 2023-05-03 2023-06-28 2023-12-25 tions nvelope ementation s and examination, disease p unctions revention and state sanitary and epidemiological supervis ion, standardization and metr ology Page 3 IDA-REDP-GOODS-RFQ-2023 -7 / Office equipment for labo ratories of veterinary diagnos Implementation Support and Request for Quota Single Stage - One E Pending Impl tics and examination, diseas IDA / 65580 Post Open - National 0.00 2023-05-16 2023-07-11 2024-01-07 Monitoring and Evaluation tions nvelope ementation e prevention and state sanita ry and epidemiological super vision, standardization and m etrology IDA-REDP-GOODS-RFQ-2023 -8 / Office furniture for labora tories of veterinary diagnosti Improving Regional Economi Request for Quota Single Stage - One E Pending Impl cs and examination, disease IDA / 65580 c Planning and Regulatory F Post Open - National 0.00 2023-05-16 2023-07-11 2024-01-07 tions nvelope ementation prevention and state sanitary unctions and epidemiological supervis ion, standardization and metr ology IDA-REDP-GOODS-RFB-2023- Strengthening Agri-Food Sup Single Stage - Two E Pending Impl 11 / Purchasing of cattle for v IDA / 65580 Post Request for Bids Open - National 0.00 2023-05-11 2023-05-16 2023-06-27 2023-09-09 2023-10-14 2024-04-11 ply Chains and SMEs nvelope ementation alue chain "Milk" IDA-REDP-PP-GOODS-RFQ-20 23-2/2 / Apple tree seedlings for "Acoustic fruit and vegeta ble freezing" Product Partner Strengthening Agri-Food Sup Request for Quota Single Stage - One E IDA / 65580 Post Open - National 0.00 Canceled 2023-01-27 2023-02-23 2023-03-10 ship:Golden Delicious (MM10 ply Chains and SMEs tions nvelope 6 rootstock), Gala (MM106 r ootstock), Red Chif (MM106 r ootstock), Super Chif (M9 ro otstock) Fudji IDA-REDP-AFSC-GOODS-RFQ Strengthening Agri-Food Sup Request for Quota Single Stage - One E -2023-4 / Fertilizer for Value IDA / 65580 Post Open - National 0.00 Canceled 2023-06-05 2023-07-31 2024-01-27 ply Chains and SMEs tions nvelope Chain "Apple" IDA-REDP-AFSC-GOODS-RFQ Strengthening Agri-Food Sup Request for Quota Single Stage - One E -2023-5 / Seeds for Value Ch IDA / 65580 Post Open - National 0.00 Canceled 2023-06-05 2023-07-31 2024-01-27 ply Chains and SMEs tions nvelope ai "Vegetables and Fruits" IDA-REDP-AFSC-GOODS-RFQ Strengthening Agri-Food Sup Request for Quota Single Stage - One E -2023-6 / Equipment for Valu IDA / 65580 Post Open - National 0.00 Canceled 2023-06-05 2023-07-31 2024-01-27 ply Chains and SMEs tions nvelope e Chai"Vegetables and Fruits " IDA-REDP-AFSC-GOODS-RFQ Strengthening Agri-Food Sup Request for Quota Single Stage - One E -2023-7 / Drip irrigation syste IDA / 65580 Post Open - National 0.00 Canceled 2023-06-05 2023-07-31 2024-01-27 ply Chains and SMEs tions nvelope m for Value Chain "Vegetable s and Fruits" IDA-REDP-AFSC-GOODS-RFQ Strengthening Agri-Food Sup Request for Quota Single Stage - One E -2023-8 / reservoir for Value IDA / 65580 Post Open - National 0.00 Canceled 2023-06-05 2023-07-31 2024-01-27 ply Chains and SMEs tions nvelope Chain "Vegetables and Fruits " IDA-REDP-AFSC-GOODS-RFQ Strengthening Agri-Food Sup Request for Quota Single Stage - One E -2023-9 / pumps for Value Ch IDA / 65580 Post Open - National 0.00 Canceled 2023-06-05 2023-07-31 2024-01-27 ply Chains and SMEs tions nvelope ain "Vegetables and Fruits" IDA-REDP-GOODS-RFQ-2023 Strengthening Agri-Food Sup Request for Quota Single Stage - One E -10 / Purchasing of equipmen IDA / 65580 Post Open - National 0.00 Canceled 2023-05-03 2023-06-28 2023-08-27 ply Chains and SMEs tions nvelope t for value chain "Milk" IDA-REDP-GOODS-RFB-2023- 12 / Purchasing of equipment Strengthening Agri-Food Sup Single Stage - One E IDA / 65580 Post Request for Bids Open - National 0.00 Canceled 2023-04-28 2023-04-28 2023-05-03 2023-06-14 2023-05-26 2023-07-14 2023-08-18 2023-08-19 for the leader of value chain ply Chains and SMEs nvelope "Milk" for "Alaiku Organics" L td. IDA-REDP-GOODS-RFQ-2023 Strengthening Agri-Food Sup Request for Quota Single Stage - One E Pending Impl -10/RT1 / Purchasing of equip IDA / 65580 Post Open - National 0.00 2023-06-21 2023-08-16 2024-02-12 ply Chains and SMEs tions nvelope ementation ment for value chain "Milk" IDA-REDP-GOODS-RFB-2023- 12/RT1 / Purchasing of equip Strengthening Agri-Food Sup Single Stage - Two E Pending Impl IDA / 65580 Post Request for Bids Open - National 0.00 2023-06-30 2023-07-05 2023-08-16 2023-10-29 2023-12-03 2024-05-31 ment for the leader of value- ply Chains and SMEs nvelope ementation chain "Milk" for "Alaikum Org anics" Ltd. IDA-REDP-RFQ-GOODS-VC-V F/A-2023-1 / Procurement of Strengthening Agri-Food Sup Request for Quota Single Stage - One E Pending Impl goods for the beneficiaries of IDA / 65580 Post Open - National 0.00 2023-07-05 2023-08-30 2024-02-26 ply Chains and SMEs tions nvelope ementation the Apple VC and for LLC Tur an Group Leader Vegetables and Fruits (2 Lots) IDA-REDP-RFB-GOODS-VC-A- Strengthening Agri-Food Sup Single Stage - Two E Pending Impl 2023-2 / Supply of plastic co IDA / 65580 Post Request for Bids Open - National 0.00 2023-06-30 2023-07-05 2023-08-16 2023-10-29 2023-12-03 2024-05-31 ply Chains and SMEs nvelope ementation ntainers for Leader of VC App le IDA-REDP-RFQ-GOODS-VC-V F-2023-3 / Supply of cargo el Strengthening Agri-Food Sup Request for Quota Single Stage - One E Pending Impl IDA / 65580 Post Open - National 0.00 2023-07-05 2023-08-30 2024-02-26 evator of LLC Turan Group fo ply Chains and SMEs tions nvelope ementation r Leader of VC Vegetables an d Fruits IDA-REDP-RFB-GOODS-VC-V F-2023-3 / Supply of equipme Strengthening Agri-Food Sup Single Stage - Two E Pending Impl IDA / 65580 Post Request for Bids Open - National 0.00 2023-06-30 2023-07-05 2023-08-16 2023-10-29 2023-12-03 2024-05-31 nt for LLC Turan Group of Lea ply Chains and SMEs nvelope ementation der of VC Vegetables and Fru its (2 Lots) IDA-REDP-RFB-GOODS-VC-V F/A-2023-4 / Supply of metal Strengthening Agri-Food Sup Request for Quota Single Stage - One E Pending Impl ware and reinforced concrete IDA / 65580 Post Open - National 0.00 2023-07-05 2023-08-30 2024-02-26 ply Chains and SMEs tions nvelope ementation poles for beneficiaries for VC Vegetables and Fruits and Ap ple (2 Lots) IDA-REDP-RFB-GOODS-VC-F V/A-2023-5 / Supply of drip ir Strengthening Agri-Food Sup Single Stage - Two E Pending Impl IDA / 65580 Post Request for Bids Open - National 0.00 2023-06-30 2023-07-05 2023-08-16 2023-10-29 2023-12-03 2024-05-31 rigation systems for benefici ply Chains and SMEs nvelope ementation aries for VC Apple and Veget ables and Fruits (5 Lots) IDA-REDP-RFQ-GOODS- VC-V F/A-2023-6 / Supply of fertiliz Strengthening Agri-Food Sup Request for Quota Single Stage - One E Pending Impl IDA / 65580 Post Open - National 0.00 2023-07-05 2023-08-30 2024-02-26 ers and seeds for beneficiarie ply Chains and SMEs tions nvelope ementation s for VC Apple and Vegetable s and Fruits (2 Lots) IDA-REDP-RFB-GOODS-VC-V F/A-2023-7 / Supply of equip Strengthening Agri-Food Sup Single Stage - Two E Pending Impl IDA / 65580 Post Request for Bids Open - National 0.00 2023-06-30 2023-07-05 2023-08-16 2023-10-29 2023-12-03 2024-05-31 ment for beneficiaries for VC ply Chains and SMEs nvelope ementation Apple and Vegetables and Fr uits (3 Lots) Page 4 NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IDA-REDP-NS-2022-5 / Acco mmodation for participants Catalyzing Investments for T Request for Quota Single Stage - One E Pending Impl of International scientific and IDA / 65580 ourism and Urban Developm Post Open - National 0.00 2022-10-08 2022-12-03 2023-06-01 tions nvelope ementation practical conference on Geot ent ourism and prospects of the geopark in the Osh region CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IDA-REDP-CS-CQS-2021-1 / R Improving Regional Economi Consultant Qualifi Pending Impleme egional development platfor IDA / 65580 c Planning and Regulatory F Post Open - National 0.00 2021-01-25 2021-01-31 2021-03-16 2021-04-15 2021-05-20 2021-08-18 cation Selection ntation m implementation unctions IDA-REDP-CS-CQS-2021-5 / S urvey on agribusiness value Strengthening Agri-Food Sup Consultant Qualifi IDA / 65580 Post Open - National 52,594.80 Signed 2021-06-29 2021-05-06 2021-06-30 2021-05-18 2021-07-18 2022-04-12 2021-08-17 2022-04-12 2021-10-15 2022-04-14 2022-01-13 chain. Survey on diagnostic s ply Chains and SMEs cation Selection tudies. Consulting company for survey IDA-REDP-CS-LCS-2021-1 / P Implementation Support and Least Cost Selecti Open - Internationa IDA / 65580 Post 0.00 Canceled 2021-10-15 2021-11-05 2021-12-19 2022-01-16 2022-02-15 2022-03-22 2022-04-26 2026-08-23 roject audit (financial audit) Monitoring and Evaluation on l IDA-REDP-CS-QCBS-2021-10 / Сonsulting company for M& E to conduct a baseline surve Implementation Support and Quality And Cost- Open - Internationa Pending Impleme y, focus group interviews, etc IDA / 65580 Prior 0.00 2022-10-10 2022-10-31 2022-12-14 2023-01-11 2023-02-10 2023-03-17 2023-04-21 2024-04-20 Monitoring and Evaluation Based Selection l ntation . collect quantitive and qualit ative data through the projec t and then at closing provide the summary with the impact results IDA-REDP-CS-QCBS-2021-4 / Consulting company for feasi Improving Regional Economi bilty studies for SPS investm Quality And Cost- Open - Internationa IDA / 65580 c Planning and Regulatory F Post 158,295.00 Signed 2021-07-17 2021-05-01 2021-08-07 2021-05-18 2021-09-20 2021-08-25 2021-10-18 2021-09-23 2021-11-17 2022-02-08 2021-12-22 2022-02-24 2022-01-26 2022-04-01 2022-07-25 ents and design of technical Based Selection l unctions specifications for equipment of laboratories, centers and p oints IDA-REDP-CS-CQS-2021-25 / Catalyzing Investments for T Consultant Qualifi Regional Tourism Strategy C IDA / 65580 ourism and Urban Developm Post Open - National 90,744.99 Signed 2021-10-27 2021-09-22 2021-11-17 2021-12-31 2022-05-11 2022-01-30 2022-05-11 2022-03-06 2022-05-12 2022-09-02 cation Selection onsultant for Osh Oblast ent IDA-REDP-CS-QCBS-2021-11 / Consulting company to iden Strengthening Agri-Food Sup Quality And Cost- Open - Internationa tify specific supply chain acto IDA / 65580 Post 0.00 Canceled 2021-07-23 2021-07-28 2021-09-01 2021-10-03 2021-10-23 2021-11-13 2021-12-10 2022-04-09 ply Chains and SMEs Based Selection l rs for participation and the c ompetitive selection of sub-p rojects IDA-REDP-CS-QCBS-2021-1 / Training in hospitality industr Catalyzing Investments for T Quality And Cost- Open - Internationa y for tour guides, tour operat IDA / 65580 ourism and Urban Developm Prior 0.00 Canceled 2021-08-25 2021-09-15 2021-10-29 2021-11-26 2021-12-26 2022-01-30 2022-03-06 2023-03-06 Based Selection l ors and accomodation mana ent gers/staff; Technical support in business planning IDA-REDP-CS-CQS-2021-27 / Consulting company providin Strengthening Agri-Food Sup Consultant Qualifi Pending Impleme g training and advice to mem IDA / 65580 Post Open - National 0.00 2022-04-04 2022-04-25 2022-06-08 2022-07-08 2022-08-12 2023-02-08 ply Chains and SMEs cation Selection ntation bers of productive partnershi ps for productivity, quality, m arketing and sales ARIS-AUDIT-LCS-2021-1 / Au Implementation Support and Least Cost Selecti Open - Internationa Under Implement IDA / 65580 Post 0.00 2021-09-01 2021-09-13 2021-09-15 2021-09-24 2021-10-13 2021-10-20 2021-10-27 2021-11-10 2021-12-08 2024-12-07 dit (financial audit) Monitoring and Evaluation on l ation IDA-REDP-CS-QCBS-2021-5 / Implementation Support and Quality And Cost- Open - Internationa Company for Preparation of f IDA / 65580 Prior 0.00 Canceled 2021-05-20 2021-06-10 2021-07-24 2021-08-21 2021-09-20 2021-10-25 2021-11-29 2022-11-29 Monitoring and Evaluation Based Selection l uture projects IDA-REDP-CS-CQS-2021-20 / Conducting an information ca mpaign, social mobilization a Strengthening Agri-Food Sup Consultant Qualifi nd diagnostic study in order t IDA / 65580 Post Open - National 0.00 Canceled 2021-09-20 2021-09-16 2021-10-11 2021-11-24 2021-12-24 2022-01-28 2022-07-27 ply Chains and SMEs cation Selection o build value chains and crea te productive partnerships in Osh oblast and Osh city and t heir further development IDA-REDP-CS-CQS-2021-22 / Conducting an information ca mpaign, social mobilization a Strengthening Agri-Food Sup Consultant Qualifi nd diagnostic study in order t IDA / 65580 Post Open - National 288,773.33 Signed 2021-12-20 2021-10-29 2022-01-10 2022-02-23 2022-04-19 2022-03-25 2022-04-19 2022-04-29 2022-04-20 2024-04-18 ply Chains and SMEs cation Selection o build value chains and crea te productive partnerships in Osh oblast and Osh city and t heir further development IDA-REDP-CS-QCBS-2021-3 / Support to department of To Improving Regional Economi Quality And Cost- Open - Internationa urism and regional/local touri IDA / 65580 c Planning and Regulatory F Prior 0.00 Canceled 2021-06-20 2021-07-11 2021-08-24 2021-09-21 2021-10-21 2021-11-25 2021-12-30 2022-05-29 Based Selection l sm agencies for improved st unctions atistics and data collection IDA-REDP-CS-CQS-2021-21 / Training in hospitality industr Supporting Tourism and Rur Consultant Qualifi y for tour guides, tour operat IDA / 65580 al Development through Sm Post Open - National 0.00 Canceled 2021-09-27 2021-10-18 2021-12-01 2021-12-31 2022-02-04 2022-08-03 cation Selection ors and accomodation mana all Grants gers/staff; Technical support in business planning IDA-REDP-CS-QCBS-2021-2 / Comprehensive assessment Catalyzing Investments for T of SulaimanToo and Uzgen m Quality And Cost- Open - Internationa IDA / 65580 ourism and Urban Developm Post 0.00 Canceled 2021-08-25 2021-10-22 2021-09-15 2021-10-29 2021-11-26 2021-12-26 2022-01-30 2022-03-06 2023-08-28 useums complexes Detailed Based Selection l ent designs and Construction Su pervision for SulaimanToo an d the Uzgen Museum IDA-REDP-CS-CQS-2021-3 / Improving Regional Economi Consultant Qualifi Open - Internationa Development of Visitors Man IDA / 65580 c Planning and Regulatory F Post 0.00 Canceled 2021-06-29 2021-07-20 2021-09-02 2021-10-02 2021-11-06 2022-02-04 cation Selection l agement Plans for Suleiman unctions Too and Uzgen Page 5 IDA-REDP-CS-CQS-2021-2 / Improving Regional Economi Development of Visitors Man Consultant Qualifi IDA / 65580 c Planning and Regulatory F Post Open - National 0.00 Canceled 2021-06-17 2021-06-23 2021-08-06 2021-09-05 2021-10-10 2022-01-08 agement Plans for Kyrgyz-At cation Selection unctions a, Abshyr-Ata, Karashoroo IDA-REDP-CS-CQS-2021-24 / Consulting company for the p reparation of the regional ec onomic development progra Strengthening Agri-Food Sup Consultant Qualifi IDA / 65580 Post Open - National 0.00 Canceled 2021-09-26 2021-10-22 2021-10-17 2021-11-30 2021-12-30 2022-02-03 2022-08-02 m of osh oblast and economi ply Chains and SMEs cation Selection c development program of os h city under the implementat ion of the regional economic development project IDA-REDP-CS-CQS-2021-7 / Desing for tourism site touri Catalyzing Investments for T Consultant Qualifi sm services and amenities (e IDA / 65580 ourism and Urban Developm Post Open - National 0.00 Canceled 2021-06-29 2021-10-22 2021-07-06 2021-08-19 2021-09-30 2021-10-12 2022-07-14 cation Selection g Desing Abshir-Ata: Kara-Sh ent oro Park Kyrgyz-Ata: infrastr ucture improvement) IDA-REDP-CS-QCBS-2021-15 / Support to department of T Catalyzing Investments for T Quality And Cost- Open - Internationa Pending Impleme ourism and regional/local tou IDA / 65580 ourism and Urban Developm Post 0.00 2022-01-11 2022-02-01 2022-03-17 2022-04-14 2022-05-14 2022-06-18 2022-07-23 2023-07-23 Based Selection l ntation rism agencies for improved s ent tatistics and data collection IDA-REDP-CS-CQS-2021-9 / T Catalyzing Investments for T Consultant Qualifi Open - Internationa IDA / 65580 Post 0.00 Canceled 2021-06-29 2021-07-20 2021-09-02 2021-10-02 2021-11-06 2022-03-06 echnical audit ourism and Urban Developm cation Selection l ent IDA-REDP-CS-QCBS-2021-6 / Catalyzing Investments for T Quality And Cost- Open - Internationa Osh City Construction Superv IDA / 65580 ourism and Urban Developm Post 0.00 Canceled 2021-07-23 2021-08-13 2021-09-05 2021-10-03 2021-10-23 2021-11-13 2021-12-10 2023-12-30 Based Selection l ision Services ent IDA-REDP-CS-CQS-2021-6 / P Catalyzing Investments for T reparation of detailed design Consultant Qualifi IDA / 65580 ourism and Urban Developm Post Open - National 0.00 Canceled 2021-06-29 2021-07-04 2021-08-17 2021-09-28 2021-10-10 2022-01-13 packages for Osh and Uzgen cation Selection ent Design packages IDA-REDP-CS-CQS-2021-8 / T echnical supervision for touri Catalyzing Investments for T Consultant Qualifi sm sites (infrastructure impr IDA / 65580 ourism and Urban Developm Post Open - National 0.00 Canceled 2021-06-29 2021-07-06 2021-08-19 2021-09-30 2021-10-17 2022-04-15 cation Selection ovement: Abshir-Ata, park Ka ent ra-Shoro, Kyrgyz-Ata) IDA-REDP-CS-CQS-2021-13 / Catalyzing Investments for T DED: Zones between residen Consultant Qualifi Pending Impleme IDA / 65580 ourism and Urban Developm Post Open - National 0.00 2021-11-21 2021-12-12 2022-01-25 2022-02-24 2022-03-31 2022-09-27 tial quarters/blocks, wall pain cation Selection ntation ent ting (mosaic), the northern p art of Lenin Street. IDA-REDP-CS-QCBS-2021-14 / DED: Development of feasib Catalyzing Investments for T Quality And Cost- Open - Internationa Under Implement ility study and DED of infrastr IDA / 65580 ourism and Urban Developm Post 0.00 2021-11-30 2022-07-12 2021-12-05 2022-07-29 2021-12-15 2021-12-30 2022-01-09 2022-01-29 2022-02-25 2023-02-25 Based Selection l ation ucture of Sulaiman-Too comp ent lex and Uzgen historical and architectural complex IDA-REDP-CS-CQS-2021-28 / Consulting company for prep Improving Regional Economi Consultant Qualifi aration of a regional economi IDA / 65580 c Planning and Regulatory F Post Open - National 148,095.79 Signed 2021-11-26 2021-12-02 2021-12-06 2021-12-26 2022-05-11 2021-12-31 2022-05-11 2022-01-26 2022-05-12 2022-07-25 cation Selection c development program for t unctions he Osh oblast and Osh city IDA-REDP-CS-CQS-2021-11 / Catalyzing Investments for T Detailed design packages an Consultant Qualifi IDA / 65580 ourism and Urban Developm Post Open - National 49,479.16 Signed 2021-11-30 2022-03-04 2021-12-21 2022-02-03 2022-04-12 2022-03-05 2022-06-01 2022-04-29 2022-06-08 2022-07-28 d author supervision for the s cation Selection ent elected facilities in the city of Osh IDA-REDP-CS-CQS-2021-15 / Detailed design packages for Catalyzing Investments for T : City Park of Culture and Lei Consultant Qualifi IDA / 65580 ourism and Urban Developm Post Open - National 50,868.60 Signed 2021-11-21 2022-03-02 2021-12-12 2022-01-25 2022-04-05 2022-02-24 2022-06-01 2022-03-31 2022-06-08 2022-09-27 sure "Tynchtyk" named after cation Selection ent N. Aznabakieva, park near th e city stadium, city stadium a nd park bridge IDA-REDP-CS-CQS-2021-17 / Design services and author s Catalyzing Investments for T Consultant Qualifi upervision for Kara-Shoro an IDA / 65580 ourism and Urban Developm Post Open - National 0.00 Canceled 2021-11-28 2022-03-18 2021-12-19 2022-03-29 2022-02-01 2022-07-22 2022-03-03 2022-08-22 2022-04-07 2022-10-04 cation Selection d Kyrgyz-Ata national parks a ent nd Abshir-Ata Waterfall IDA-REDP-CS-CQS-2021-12 / Catalyzing Investments for T Consultant Qualifi IDA / 65580 Post Open - National 0.00 Canceled 2021-11-21 2021-12-12 2022-01-25 2022-02-24 2022-03-31 2022-09-27 DED: coastal zone of the Ak- ourism and Urban Developm cation Selection Buura river ent IDA-REDP-CS-QCBS-2021-13 Supporting Tourism and Rur / Consulting company for the Quality And Cost- Open - Internationa IDA / 65580 al Development through Sm Post 0.00 Signed 2022-05-08 2022-05-11 2022-05-18 2022-06-07 2022-07-22 2022-06-17 2022-08-23 2022-06-27 2022-09-13 2022-07-17 2022-09-27 2022-08-11 2025-02-18 preparation and implementat Based Selection l all Grants ion of the Small Grants Progr am IDA-REDP-CS-CQS-2021-31 / Selection of consulting comp any for assessment of the sol Implementation Support and Consultant Qualifi IDA / 65580 Post Open - National 0.00 Canceled 2022-03-01 2022-03-04 2022-03-22 2022-05-05 2022-06-04 2022-07-09 2023-01-05 id waste management syste Monitoring and Evaluation cation Selection ms in selected towns and the identification of priority secto r investments IDA-REDP-CS-CQS-2021-31- RT / Selection of consulting c ompany for assessment of th Implementation Support and Consultant Qualifi Open - Internationa IDA / 65580 Post 35,578.71 Signed 2022-06-17 2022-06-17 2022-07-08 2022-08-21 2022-07-07 2022-09-20 2022-08-02 2022-10-25 2022-08-09 2023-04-23 e solid waste management s Monitoring and Evaluation cation Selection l ystems in selected towns an d the identification of priority sector investments IDA-REDP-CS-CQS-2021-23 / Consulting Services for the pr eparation of a Tourism Mana gement Plan for Catalyzing Investments for T Consultant Qualifi Open - Internationa the Sulaiman-Too and Uzgen IDA / 65580 ourism and Urban Developm Post 0.00 Signed 2022-07-25 2022-07-27 2022-08-15 2022-08-01 2022-09-18 2022-10-20 2022-10-18 2022-12-16 2022-11-15 2023-09-08 cation Selection l Historical and Architectural C ent omplexes; Interior Design an d Exhibition Plan for the Sulai man-Too Cave Museum; and Recommendation for enlistin g Uzgen Histo IDA-REDP-CS-QCBS-2021-12 Implementation Support and Quality And Cost- Open - Internationa Pending Impleme / Company for Preparation of IDA / 65580 Prior 0.00 2024-02-05 2024-02-26 2024-04-10 2024-05-08 2024-06-07 2024-07-12 2024-08-16 2025-02-12 Monitoring and Evaluation Based Selection l ntation future projects Page 6 IDA-REDP-CS-QCBS-2021-7 / Catalyzing Investments for T Quality And Cost- Open - Internationa Tech supervision SulaimanT IDA / 65580 ourism and Urban Developm Post 0.00 Canceled 2021-07-23 2022-08-05 2021-08-07 2021-09-05 2021-10-03 2021-10-23 2021-11-13 2021-12-10 2023-12-30 Based Selection l oo and the Uzgen Museum ent IDA-REDP-CS-QCBS-2021-7. / Technical Supervision of Civil Catalyzing Investments for T Quality And Cost- Open - Internationa Works at the Sulaiman-Too a IDA / 65580 ourism and Urban Developm Post 0.00 Canceled 2022-08-22 2022-08-24 2022-09-12 2022-08-29 2022-10-26 2023-04-01 2022-11-23 2023-04-01 2022-12-23 2023-04-01 2023-01-27 2023-04-01 2023-03-03 2024-03-02 Based Selection l nd Uzgen Historical and Archi ent tectural Complexes IDA-REDP-CS-CQS-2021-14 / Catalyzing Investments for T Consultant Qualifi Pending Impleme DED: road networks (5 street IDA / 65580 ourism and Urban Developm Post Open - National 0.00 2021-11-21 2021-12-12 2022-01-25 2022-02-24 2022-03-31 2022-09-27 cation Selection ntation s) and extension of Dostuk p ent ark IDA-REDP-CS-CQS-2021-19 / Preparation of Design Estima te Documentation (DED) pac Catalyzing Investments for T kages for the construction of Consultant Qualifi IDA / 65580 ourism and Urban Developm Post Open - National 0.00 Signed 2022-10-10 2022-10-13 2022-10-31 2022-10-28 2022-12-14 2023-03-07 2023-01-13 2023-03-07 2023-02-17 2023-08-16 an access road, installation o cation Selection ent f transformer substation, pow er transmission line within Pu blic-Private Cooperation Prog ram of RED-1 IDA-REDP-CS-CQS-2021-18 / Catalyzing Investments for T Consultant Qualifi Technical Supervision of Civil IDA / 65580 ourism and Urban Developm Post Open - National 0.00 Canceled 2022-06-20 2022-06-13 2022-07-11 2022-07-21 2022-08-24 2022-09-23 2022-11-07 2024-07-05 cation Selection Works under the RED-1 ent IDA-REDP-CS-CQS-2021-26 / Consulting Services for the pr Catalyzing Investments for T Consultant Qualifi Under Implement eparation of Management Pla IDA / 65580 ourism and Urban Developm Post Open - National 0.00 2021-12-01 2022-10-05 2021-12-11 2022-10-11 2021-12-28 2022-01-07 2022-02-10 2022-08-09 cation Selection ation ns for the State Nature Parks ent Kara-Shoro, Kyrgyz-Ata and waterfall Abshir-Ata IDA-REDP-CS-CQS-2021-18- Catalyzing Investments for T Consultant Qualifi Under Implement RT / Technical Supervision of IDA / 65580 ourism and Urban Developm Post Open - National 0.00 2022-10-03 2022-10-04 2022-10-24 2022-10-06 2022-12-07 2023-01-12 2023-01-06 2023-02-15 2023-02-10 2026-05-25 cation Selection ation Civil Works under the RED-1 ent IDA-REDP-CS-QCBS-2021-8 / Catalyzing Investments for T Company for Branding,marke Quality And Cost- Open - Internationa Pending Impleme IDA / 65580 ourism and Urban Developm Post 0.00 2023-07-23 2023-07-28 2023-09-13 2023-10-03 2023-10-23 2023-11-13 2023-12-10 2024-08-04 ting and promotion activities Based Selection l ntation ent for Osh region IDA-REDP-CS-CQS-2022-28 / Selection of a consulting com pany for the provision of trai Strengthening Agri-Food Sup Consultant Qualifi Under Implement IDA / 65580 Post Open - National 0.00 2022-11-17 2023-05-23 2022-12-08 2023-05-26 2023-01-21 2023-02-20 2023-03-27 2023-09-23 ning consultancy service to t ply Chains and SMEs cation Selection ation he participants of the Produc tive Partnership of Osh Oblas t and Osh City IDA-REDP-CS-CQS-2021-17- RT / Consulting Company for Catalyzing Investments for T Feasibility Studies, Design Se Consultant Qualifi Under Implement IDA / 65580 ourism and Urban Developm Post Open - National 0.00 2023-03-03 2023-03-24 2023-03-24 2023-04-08 2023-05-07 2023-06-06 2023-07-11 2024-03-07 rvices and Author Supervisio cation Selection ation ent n for Kara-Shoro and Kyrgyz- Ata National Parks and Abshi r-Ata Waterfall IDA-REDP-CS-CQS-2021-4 / Consulting company to cond Strengthening Agri-Food Sup Consultant Qualifi Pending Impleme IDA / 65580 Post Open - National 0.00 2021-06-29 2021-07-04 2021-08-17 2021-09-28 2021-10-15 2023-10-05 uct market studies. Methodol ply Chains and SMEs cation Selection ntation ogy for National Stakeholders Platform IDA-REDP-CS-CQS-2023-1 / Improving Regional Economi Consulting company for the d Consultant Qualifi Under Implement IDA / 65580 c Planning and Regulatory F Post Open - National 0.00 2023-03-24 2023-03-31 2023-04-14 2023-04-08 2023-05-28 2023-06-27 2023-08-01 2024-01-28 evelopment of detailed desig cation Selection ation unctions n for facilities in Osh region a nd Osh city IDA-REDP-CS-CQS-2021-10 / Consulting company for Deve lopment of design document ation and supervision of repa Improving Regional Economi Consultant Qualifi Pending Impleme ir of the office of Osh technic IDA / 65580 c Planning and Regulatory F Post Open - National 0.00 2021-12-20 2021-12-25 2022-02-07 2022-03-21 2022-04-02 2022-10-18 cation Selection ntation al agriculture college, (includi unctions ng driving fields) and office o f Osh technological university , warehouses of seed farms a nd plemzavod etc... IDA-REDP-CS-QCBS-2021-7- RT / Technical Supervision of Catalyzing Investments for T Quality And Cost- Open - Internationa Under Implement Civil Works at the Sulaiman-T IDA / 65580 ourism and Urban Developm Post 0.00 2023-04-14 2023-04-10 2023-05-05 2023-04-28 2023-06-18 2023-07-16 2023-08-15 2023-09-19 2023-10-24 2024-10-18 Based Selection l ation oo and Uzgen Historical and ent Architectural Complexes IDA-REDP-CS-CQS-2023-33 / For Consultancy Services to Catalyzing Investments for T Consultant Qualifi Under Implement deliver a Capacity Building Pr IDA / 65580 ourism and Urban Developm Post Open - National 0.00 2023-04-28 2023-05-02 2023-05-19 2023-05-13 2023-07-02 2023-08-01 2023-09-05 2024-03-03 cation Selection ation ogram for the Tourism Sector ent Stakeholders in the Osh Regi on IDA-REDP-CS-CQS-2023-34 / Tourism Product developmen Catalyzing Investments for T Consultant Qualifi Pending Impleme t at the regional level (fairs, IDA / 65580 ourism and Urban Developm Post Open - National 0.00 2023-05-29 2023-06-19 2023-08-02 2023-09-01 2023-10-06 2024-04-03 cation Selection ntation exhibitions, PR, media campa ent igns, cultural events, forums) INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Actual Amount Invitation to Identifie Draft Negotiated Cont Component Review Type Method Contract Type Process Status Teams of Reference Signed Contract Contract Completion Description o. h (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IDA-REDP-CS-IC-2021-11 / Lo Improving Regional Economi Individual Consult Pending Impleme cal consultant for review of le IDA / 65580 c Planning and Regulatory F Post Open 0.00 2021-12-21 2022-01-23 2022-02-25 2022-03-22 2023-03-17 ant Selection ntation gal acts for exports 3 unctions IDA-REDP-CS-IC-2021-12 / Lo Improving Regional Economi Individual Consult Pending Impleme cal consultant for review of le IDA / 65580 c Planning and Regulatory F Post Open 0.00 2021-12-21 2022-01-23 2022-01-25 2022-03-26 2023-03-21 ant Selection ntation gal acts for exports 4 unctions IDA-REDP-CS-IC-2021-13 / C Improving Regional Economi onsultant for Development of Individual Consult Pending Impleme IDA / 65580 c Planning and Regulatory F Post Open 0.00 2021-12-21 2022-01-23 2022-01-25 2022-03-26 2023-03-21 legal documents of 7 samplin ant Selection ntation unctions g points for laboratory testin g Page 7 IDA-REDP-CS-IC-2021-4 / Co Improving Regional Economi nsultant for Development of Individual Consult Pending Impleme IDA / 65580 c Planning and Regulatory F Post Open 0.00 2020-11-25 2020-12-25 2020-12-30 2021-02-28 2022-02-23 education materials for Osh t ant Selection ntation unctions echnical agricultural college and Osh university IDA-REDP-CS-IC-2021-8 / Int Improving Regional Economi Individual Consult Pending Impleme ernational consultant for revi IDA / 65580 c Planning and Regulatory F Post Open 0.00 2020-12-21 2021-01-20 2021-01-25 2021-03-26 2022-03-21 ant Selection ntation ew of legal acts for exports unctions IDA-REDP-CS-IC-2021-10 / Lo Improving Regional Economi Individual Consult Pending Impleme cal consultant for review of le IDA / 65580 c Planning and Regulatory F Post Open 0.00 2020-12-21 2021-01-20 2021-01-25 2021-03-26 2022-03-21 ant Selection ntation gal acts for exports 2 unctions IDA-REDP-CS-IC-2021-9 / Loc Improving Regional Economi Individual Consult Pending Impleme al consultant for review of le IDA / 65580 c Planning and Regulatory F Post Open 0.00 2020-12-21 2021-01-20 2021-01-25 2021-03-26 2021-05-01 ant Selection ntation gal acts for exports 1 unctions IDA-REDP-CS-IC-2021-20 / C Supporting Tourism and Rur onsultant to provide support Individual Consult IDA / 65580 al Development through Sm Post Open 16,421.51 Signed 2021-10-21 2021-08-19 2021-12-09 2022-04-15 2021-12-30 2022-04-15 2022-02-03 2022-04-16 2022-08-02 to ARIS with Small Grants Pro ant Selection all Grants gram and Public and Private Cooperation initiative IDA-REDP-CS-IC-2021-1 / Co Improving Regional Economi Individual Consult nsultant for Regional Econom IDA / 65580 c Planning and Regulatory F Post Open 0.00 Canceled 2020-11-25 2020-12-25 2020-12-30 2021-02-28 2022-02-23 ant Selection ic Development Plan for Osh unctions region IDA-REDP-CS-IC-2021-2 / Co Improving Regional Economi Individual Consult nsultant for Development of t IDA / 65580 c Planning and Regulatory F Post Open 0.00 Canceled 2021-09-27 2021-05-18 2021-10-27 2021-11-01 2021-12-31 2022-12-26 ant Selection he Regional tourism strategy unctions for Osh region IDA-REDP-CS-IC-2021-21 / Fo r the Consultancy to provide Implementation Support and Individual Consult IDA / 65580 Post Open 0.00 Canceled 2021-12-12 2021-10-07 2022-01-30 2022-02-20 2022-03-27 2022-09-23 support to ARIS with Social Is Monitoring and Evaluation ant Selection sues for RED Project IDA-REDP-CS-IC-2021-22 / Fo r the Consultancy to provide Implementation Support and Individual Consult IDA / 65580 Post Limited 7,055.99 Signed 2021-12-12 2021-10-12 2021-12-26 2022-04-04 2022-02-20 2022-04-04 2022-03-27 2022-04-06 2022-09-23 support to ARIS with Social Is Monitoring and Evaluation ant Selection sues for RED Project IDA-REDP-CS-IC-2021-19 / C onsultants for the developme Strengthening Agri-Food Sup Individual Consult nt of business plans and proj IDA / 65580 Post Open 0.00 Canceled 2021-10-29 2021-12-17 2022-01-07 2022-02-11 2022-08-10 ply Chains and SMEs ant Selection ect proposals at the stages o f selection of productive part nerships IDA-REDP-CS-IC-2021-24 / C Catalyzing Investments for T onsulting for conducting rese Individual Consult Pending Impleme IDA / 65580 ourism and Urban Developm Post Open 0.00 2021-11-30 2021-12-25 2022-01-04 2022-01-20 2022-04-20 arch on tourism statistics an ant Selection ntation ent d developing recommendatio ns for impoving IDA-REDP-CS-IC-2021-6 / Loc Improving Regional Economi al consultant for for MinAgri, Individual Consult IDA / 65580 c Planning and Regulatory F Post Open 0.00 Canceled 2020-11-25 2020-12-25 2020-12-30 2021-02-28 2022-02-23 Osh oblast administration an ant Selection unctions d other stakeholders 1 IDA-REDP-CS-IC-2021-7 / Loc Improving Regional Economi al consultant for for MinAgri, Individual Consult IDA / 65580 c Planning and Regulatory F Post Open 0.00 Canceled 2020-12-21 2021-01-20 2021-01-25 2021-03-26 2022-03-21 Osh oblast administration an ant Selection unctions d other stakeholders 2 IDA-REDP-CS-IC-2021-25 / C onsultant - trainer for capacit y building of specialists of go Improving Regional Economi vernment bodies and process Individual Consult IDA / 65580 c Planning and Regulatory F Post Open 1,627.02 Signed 2021-12-05 2021-11-25 2022-01-23 2022-04-05 2022-02-13 2022-04-03 2022-03-20 2022-04-14 2022-09-16 ing enterprises on food safet ant Selection unctions y in accordance with internat ional food quality and safety standards (ISO 9001, ISO 220 00, FSSC 22000). IDA-REDP-CS-IC-2021-26 / C onsultant-trainer for capacity building of specialists of gove rnment bodies and agricultur Improving Regional Economi Individual Consult al producers on ensuring the IDA / 65580 c Planning and Regulatory F Post Open 1,627.02 Signed 2021-12-05 2021-11-25 2022-01-23 2022-04-01 2022-02-13 2022-04-01 2022-03-20 2022-04-06 2022-09-16 ant Selection safety of agricultural producti unctions on in accordance with intern ational standards (GLOBAL G .A.P., Organic, ISO 14000, etc .) for domestic mar IDA-REDP-CS-CQS-2021-30 / Implementation Support and Individual Consult Pending Impleme IDA / 65580 Post Open 0.00 2023-05-05 2023-06-23 2023-07-14 2023-08-18 2024-02-14 Technical audit Monitoring and Evaluation ant Selection ntation IDA-REDP-CS-IC-2021-31 / S Implementation Support and Individual Consult election of institutional devel IDA / 65580 Post Limited 9,490.78 Signed 2021-12-05 2021-12-08 2021-12-10 2022-04-05 2021-12-31 2022-04-05 2022-02-04 2022-04-07 2022-08-03 Monitoring and Evaluation ant Selection opment consultant IDA-REDP-CS-IC-2021-27 / In dependent consultant on eva Strengthening Agri-Food Sup Individual Consult IDA / 65580 Post Open 0.00 Canceled 2021-12-27 2022-02-14 2022-03-07 2022-04-11 2023-10-03 luation of business plans and ply Chains and SMEs ant Selection Sub-project proposals IDA-REDP-CS-IC-2021-32 / C Catalyzing Investments for T Individual Consult Under Implement onsultant to develop a websit IDA / 65580 ourism and Urban Developm Post Open 0.00 2022-04-28 2022-05-13 2022-06-16 2022-07-07 2022-08-11 2023-02-07 ant Selection ation e of the Public-Private Coope ent ration Program IDA-REDP-CS-IC-2021-14 / C onsultant-trainer on capacity building of employees of the Ministry of Agriculture of the Strengthening Agri-Food Sup Individual Consult Under Implement Kyrgyz Republic, specialists o IDA / 65580 Post Open 0.00 2022-05-25 2022-06-06 2022-07-13 2022-08-03 2022-09-07 2023-03-06 ply Chains and SMEs ant Selection ation f the Regional Economic Dev elopment Project of Osh obla st and Osh city, ARIS and the Agribusiness Competitivenes s Center on building a IDA-REDP-CS-IC-2021-5 / Int Improving Regional Economi ernational consultant for Min Individual Consult Pending Impleme IDA / 65580 c Planning and Regulatory F Post Open - National 0.00 2022-07-22 2022-09-09 2022-09-30 2022-11-04 2023-05-03 Agri, Osh oblast administrati ant Selection ntation unctions on and other stakeholders Page 8 IDA-REDP-CS-IC-2021-28 / In dependent consultant on eva Strengthening Agri-Food Sup Individual Consult Under Implement IDA / 65580 Post Open - National 0.00 2022-10-06 2022-10-04 2022-11-24 2022-11-02 2022-12-15 2022-11-02 2023-01-19 2023-07-18 luation of business plans and ply Chains and SMEs ant Selection ation Sub-project proposals IDA-REDP-CS-IC-2022-33 / C Catalyzing Investments for T Individual Consult onsultancy services of an int IDA / 65580 ourism and Urban Developm Post Open - National 0.00 Canceled 2022-11-14 2022-10-31 2023-01-02 2023-01-23 2023-02-27 2023-08-26 ant Selection ernational expert in the field ent of museology IDA-REDP-CS-IC-2022-34 / C Catalyzing Investments for T Individual Consult onsultancy services of an int IDA / 65580 ourism and Urban Developm Post Open - National 0.00 Canceled 2022-11-14 2022-10-31 2023-01-02 2023-01-23 2023-02-27 2023-08-26 ant Selection ernational World Heritage ex ent pert IDA-REDP-CS-IC-2022-34/1 / Catalyzing Investments for T Individual Consult Open - Internationa Under Implement Consultancy services of an in IDA / 65580 ourism and Urban Developm Post 0.00 2022-11-14 2022-11-23 2023-01-02 2023-01-23 2023-02-27 2023-05-28 ant Selection l ation ternational World Heritage ex ent pert IDA-REDP-CS-IC-2021-29 / In dependent consultant on eva Strengthening Agri-Food Sup Individual Consult Under Implement IDA / 65580 Post Open - National 0.00 2023-03-24 2023-03-24 2023-05-12 2023-06-02 2023-07-07 2024-01-03 luation of business plans and ply Chains and SMEs ant Selection ation Sub-project proposals IDA-REDP-CS-IC-2023-3 / Cre Strengthening Agri-Food Sup Individual Consult Under Implement dit specialist for evaluation of IDA / 65580 Post Open - National 0.00 2023-03-24 2023-03-25 2023-05-12 2023-06-02 2023-07-07 2024-01-03 ply Chains and SMEs ant Selection ation credit documentation of VC p articipants IDA-REDP-CS-IC-2021-30 / In dependent consultant on eva Strengthening Agri-Food Sup Individual Consult Under Implement IDA / 65580 Post Open - National 0.00 2023-03-31 2023-03-24 2023-05-19 2023-06-09 2023-07-14 2024-01-10 luation of business plans and ply Chains and SMEs ant Selection ation Sub-project proposals IDA-REDP-CS-IC-2023-2 / Sh Improving Regional Economi Individual Consult Under Implement ort-term individual consultan IDA / 65580 c Planning and Regulatory F Post Open - National 0.00 2023-03-31 2023-03-25 2023-05-19 2023-06-09 2023-07-14 2024-01-10 ant Selection ation t for laboratory equipment unctions IDA-REDP-CS-IC-2021-3 / Co Improving Regional Economi Individual Consult Under Implement nsultant for sowtfare desing IDA / 65580 c Planning and Regulatory F Post Open - National 0.00 2020-11-25 2023-04-19 2020-12-25 2020-12-30 2021-02-28 2022-02-23 ant Selection ation and on-job training unctions IDA-REDP-CS-IC-2022-33/1/T R1 / Consultancy services of Strengthening Agri-Food Sup Individual Consult Pending Impleme IDA / 65580 Post Open - National 0.00 2023-06-16 2023-08-04 2023-08-25 2023-09-29 2024-03-27 an international expert in the ply Chains and SMEs ant Selection ntation field of museology IDA-REDP-CS-IC-2022-33/1 / Catalyzing Investments for T Individual Consult Open - Internationa Consultancy services of an in IDA / 65580 ourism and Urban Developm Post 0.00 Canceled 2022-11-14 2022-11-23 2023-01-02 2023-04-06 2023-01-23 2023-02-27 2023-05-28 ant Selection l ternational expert in the field ent of museology Page 9 P177646 PPSD PPSD will be uploaded when ready PROCUREMENT Comoros : Comoros Solar Energy Access Project PLAN General Information Country: Comoros 2022-10-10 Bank’s Approval Date of the Original Procurement Plan: 2023-06-02 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P177646 GPN Date: Project Name: Comoros Solar Energy Access Project Loan / Credit No: IDA / 71290, IDA / E0490 AEP SOLAR SONELEC Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned KM-AEP SONELEC-362622-C Request for Bids - Component 3. Technical Assi W-RFB / Réhabilitation du bât Single Stage - One E Small Works SPD Pending Imp 2025-02-1 IDA / E0490 stance and Project Manage Post Request for Bids Open - National 470,000.00 0.00 2023-06-07 2023-06-14 2023-07-29 2023-08-12 2023-08-26 iment qui abritera les Unités nvelope (1 envelope proce lementation 6 ment de coordination et d’exécutio ss) n du projet GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual KM-AEP SONELEC-304146-G Component 2: SONELEC Co Open - Internationa Single Stage - One E Under Revie O-RFB / Acquisition de 130,0 IDA / 71290 mmercial and Operational R Prior Request for Bids 4,000,000.00 0.00 2022-07-25 2023-04-07 2022-07-30 2023-05-09 2022-09-10 2022-10-10 2022-11-14 2023-05-13 l nvelope w 00 compteurs prépayés de ty ecovery pe STS KM-AEP SONELEC-346653-G Component 3. Technical Assi Request for Quota Single Stage - One E Pending Impl IDA / 71290 Post Open - National 24,000.00 0.00 2023-03-13 2023-03-25 2023-05-24 O-RFQ / Mobilier de bureau p stance and Project Manage tions nvelope ementation our l'AEP ment KM-AEP SONELEC-346660-G Component 3. Technical Assi Request for Quota Single Stage - One E Pending Impl O-RFQ / Achat du materiel inf IDA / E0490 stance and Project Manage Post Open - National 42,000.00 0.00 2023-03-29 2023-04-21 2023-06-20 tions nvelope ementation ormatique pour l'AEP ment KM-AEP SONELEC-350445-G O-RFB / Fournitures d'une inf Component 2: SONELEC Co rastructure de comptage ava Open - Internationa Single Stage - Two E Pending Impl IDA / E0490 mmercial and Operational R Prior Request for Bids 4,000,000.00 0.00 2023-03-20 2023-04-03 2023-06-09 2023-06-19 2023-07-06 2024-07-05 ncée (AMI) comprenant des c l nvelope ementation ecovery ompteurs STS communicants et un système automatisé de gestion des compteurs KM-AEP SONELEC-346647-G O-RFQ / Achat de 4 véhicules Component 3. Technical Assi Request for Quota Single Stage - One E Pending Impl pour l'AEP dont 2 véhicules d IDA / E0490 stance and Project Manage Post Open - National 150,000.00 0.00 2023-05-27 2023-06-13 2023-08-12 tions nvelope ementation e terrain et 2 pour le bureau ment (coordination et administrati on). KM-AEP SONELEC-363637-G O-DIR / Acquisition, formatio Component 3. Technical Assi Direct - Internation Pending Impl n et assistance du logiciel TO IDA / E0490 stance and Project Manage Post Direct Selection 25,000.00 0.00 2023-05-25 2023-05-28 2023-06-21 2027-12-31 al ementation MPRO WEB pour la gestion d ment es deux unités de coordinatio n UCP et AEP. KM-AEP SONELEC-363840-G Component 3. Technical Assi O-RFQ / Fournitures d'un gén Request for Quota Single Stage - One E Pending Impl IDA / E0490 stance and Project Manage Post Open - National 30,000.00 0.00 2023-06-05 2023-07-31 2024-01-27 érateur solaire pour l’énergie tions nvelope ementation ment de secours du bureau du proj et NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual KM-AEP SONELEC-346565-N C-DIR / Location de bureaux t Component 3. Technical Assi Pending Impl emporaire pour l'AEP, en atte IDA / E0490 stance and Project Manage Post Direct Selection Direct - National 32,000.00 0.00 2023-03-01 2023-03-06 2023-03-10 2024-03-09 ementation ndant la construction et l'am ment énagement du bâtiment dev ant abriter le projet CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual KM-AEP SONELEC-321844-C Component 3. Technical Assi S-CQS / Recrutement du resp Consultant Qualifi IDA / 71290 stance and Project Manage Post Open - National 90,000.00 0.00 Canceled 2022-10-18 2022-11-28 2022-11-08 2022-12-22 2023-01-21 2023-02-25 2023-08-24 onsable Administratif et finan cation Selection ment cier (RAF) PIU SONELEC KM-AEP SONELEC-324703-C Component 3. Technical Assi Consultant Qualifi S-CQS / Recrutement du spéc IDA / 71290 stance and Project Manage Post Open - National 72,000.00 0.00 Canceled 2022-11-05 2022-11-26 2023-01-09 2023-02-08 2023-03-15 2023-09-11 cation Selection ialiste en gestion commercial ment e KM-AEP SONELEC-324705-C Component 3. Technical Assi Consultant Qualifi S-CQS / Recrutement du spéc IDA / 71290 stance and Project Manage Post Open - National 72,000.00 0.00 Canceled 2022-11-05 2022-11-26 2023-01-09 2023-02-08 2023-03-15 2023-09-11 cation Selection ialiste en Protection de reven ment us KM-AEP SONELEC-324706-C Component 3. Technical Assi S-CQS / Recrutement du spéc Consultant Qualifi IDA / 71290 stance and Project Manage Post Open - National 90,000.00 0.00 Canceled 2022-11-05 2022-11-26 2023-01-09 2023-02-08 2023-03-15 2023-09-11 ialiste en Système informatiq cation Selection ment ue de gestion KM-AEP SONELEC-304150-C Component 2: SONELEC Co S-LCS / Assistance technique Quality And Cost- Open - Internationa Under Implement IDA / 71290 mmercial and Operational R Prior 500,000.00 0.00 2022-11-21 2023-01-17 2022-12-12 2023-05-09 2023-01-25 2023-02-22 2023-03-24 2023-04-28 2023-06-02 2024-06-01 relative à la séparation de S Based Selection l ation ecovery ONELEC et SONEDE, fusion M AMWE et EDA Page 1 KM-AEP SONELEC-330521-C Component 3. Technical Assi Consultant Qualifi S-CQS / Recrutement d'un sp IDA / 71290 stance and Project Manage Post Open - National 72,000.00 0.00 Canceled 2022-12-07 2022-12-09 2022-12-28 2023-02-10 2023-03-12 2023-04-16 2023-10-13 cation Selection écialiste en sauvegarde envir ment onnementale. KM-AEP SONELEC-330522-C Component 3. Technical Assi Consultant Qualifi S-CQS / Recrutement d'un sp IDA / 71290 stance and Project Manage Post Open - National 72,000.00 0.00 Canceled 2022-12-07 2022-12-10 2022-12-28 2023-02-10 2023-03-12 2023-04-16 2023-10-13 cation Selection écialiste en sauvegarde socia ment le KM-AEP SONELEC-333020-C S-CQS / Recrutement Ingénie Component 3. Technical Assi Consultant Qualifi Open - Internationa ur Conseil pour les travaux d IDA / 71290 stance and Project Manage Post 300,000.00 0.00 Canceled 2022-12-23 2023-01-13 2023-02-26 2023-03-28 2023-05-02 2023-10-29 cation Selection l e réhabilitation et d'automati ment sation des réseaux de distrib ution KM-AEP SONELEC-333022-C Component 3. Technical Assi S-CQS / Recrutement Ingénie Consultant Qualifi Open - Internationa IDA / 71290 stance and Project Manage Post 300,000.00 0.00 Canceled 2022-12-23 2023-01-13 2023-02-26 2023-03-28 2023-05-02 2023-10-29 ur conseil pour la maitrise d' cation Selection l ment œuvre du centre de dispatchi ng KM-AEP SONELEC-345662-C S-QCBS / Recrutement Ingéni Component 3. Technical Assi eur conseil pour les travaux Quality And Cost- Open - Internationa IDA / 71290 stance and Project Manage Prior 600,000.00 0.00 Canceled 2023-02-28 2023-03-21 2023-04-13 2023-04-27 2023-05-18 2023-06-15 2023-07-01 2025-06-30 de rehabilitation, d'automatis Based Selection l ment ation du réseau électrique et la mise en place du centre de dispatching. KM-AEP SONELEC-333013-C S-CQS / RECRUTEMENT D’UN Component 3. Technical Assi INGÉNIEUR CONSEIL CONSTR Consultant Qualifi Open - Internationa IDA / E0490 stance and Project Manage Prior 1,000,000.00 0.00 Under Review 2023-05-12 2023-05-19 2023-06-09 2023-06-23 2023-07-28 2024-07-27 UCTION DE CENTRALE PV AV cation Selection l ment EC STOCKAGE, RÉSEAU, TEL ECONDUITE ET DISPATCHING KM-AEP SONELEC-362591-C Component 3. Technical Assi S-QCBS / Audit des états fina Quality And Cost- Open - Internationa Pending Impleme IDA / E0490 stance and Project Manage Post 40,000.00 0.00 2023-05-30 2023-06-20 2023-07-21 2023-08-04 2023-08-25 2023-09-29 2023-11-03 2024-11-02 nciers de MAMWE et EDA pou Based Selection l ntation ment r 2018-2019, SONELEC 2020- 2022 INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual KM-AEP SONELEC-318192-C Component 3. Technical Assi Individual Consult Under Implement S-INDV / Recrutement du res IDA / 71290 stance and Project Manage Post Open - National 90,000.00 0.00 2022-09-30 2022-11-28 2022-11-18 2022-12-09 2023-01-13 2023-07-12 ant Selection ation ponsable en passation de ma ment rche de l'AEP KM-AEP SONELEC-321846-C Component 3. Technical Assi S-INDV / Recrutement d'un s Individual Consult IDA / 71290 stance and Project Manage Post Open - National 90,000.00 0.00 Canceled 2022-10-20 2022-12-08 2022-12-29 2023-02-02 2023-08-01 pécialiste en énergie solaire ant Selection ment et distribution électrique pou r le PIU SONELEC KM-AEP SONELEC-346299-C Component 3. Technical Assi S-INDV / Recrutement du spé Individual Consult IDA / 71290 stance and Project Manage Post Open - National 90,000.00 0.00 Canceled 2023-03-07 2023-04-09 2023-04-23 2023-05-07 2024-05-06 cialiste en Système Informati ant Selection ment que de Gestion KM-AEP SONELEC-346301-C Component 3. Technical Assi Individual Consult S-INDV / Recrutement du Spé IDA / 71290 stance and Project Manage Post Open - National 72,000.00 0.00 Canceled 2023-03-07 2023-04-09 2023-04-19 2023-05-03 2024-05-02 ant Selection cialiste en Gestion Commerci ment ale KM-AEP SONELEC-346567-C S-INDV / Recrutement d'un e Component 3. Technical Assi Individual Consult Open - Internationa xpert pour fournir assistance IDA / 71290 stance and Project Manage Post 50,000.00 0.00 Under Review 2023-03-08 2023-06-17 2023-04-17 2023-05-01 2023-05-22 2023-11-18 ant Selection l technique à l’implémentation ment du Système Informatique de Gestion de la SONELEC KM-AEP SONELEC-347463-C S-INDV / Recrutement d'un s pécialiste en Passation de m Component 3. Technical Assi Individual Consult Direct - Internation arché temporaire, en attenda IDA / E0490 stance and Project Manage Post 20,000.00 0.00 Under Review 2023-05-29 2023-06-03 2023-06-08 2023-06-15 2023-07-09 2023-10-07 ant Selection al nt de relancer de l'appel à ca ment ndidatures du Responsable Passation de Marché pour l'A EP et pour l'UCP. KM-AEP SONELEC-346548-C Component 3. Technical Assi Individual Consult Pending Impleme S-INDV / Recrutement du Res IDA / E0490 stance and Project Manage Post Open - National 90,000.00 0.00 2022-09-30 2023-02-07 2023-02-10 2023-03-05 2024-03-04 ant Selection ntation ponsable Administratif et Fin ment ancier AEP KM-AEP SONELEC-346556-C Component 3. Technical Assi Individual Consult Pending Impleme S-INDV / Recrutement du Spe IDA / E0490 stance and Project Manage Post Open - National 90,000.00 0.00 2022-09-30 2023-02-07 2023-02-10 2023-03-05 2024-03-04 ant Selection ntation cialiste en Sauvegarde Social ment e AEP KM-AEP SONELEC-346465-C Component 3. Technical Assi S-INDV / Recrutement du Coo Individual Consult Pending Impleme IDA / E0490 stance and Project Manage Post Open - National 150,000.00 0.00 2022-05-30 2022-10-27 2022-12-01 2023-01-03 2024-01-03 rdonnateur de l'Agence d’Exé ant Selection ntation ment cution du Projet (AEP) KM-AEP SONELEC-346558-C Component 3. Technical Assi S-INDV / Recrutement du Spé Individual Consult Pending Impleme IDA / E0490 stance and Project Manage Post Open - National 90,000.00 0.00 2022-09-30 2023-02-07 2023-02-10 2023-03-05 2023-09-01 cialiste en Sauvegarde Envir ant Selection ntation ment onnementale de l'AEP KM-AEP SONELEC-346322-C S-INDV / Recrutement d'un C Component 3. Technical Assi Individual Consult Open - Internationa onsultant en Programme de IDA / E0490 stance and Project Manage Post 50,000.00 0.00 Under Review 2023-03-07 2023-06-07 2023-04-25 2023-05-16 2023-06-09 2023-12-06 ant Selection l Protection des Revenus pour ment la mise en oeuvre des compt eurs communicants KM-AEP SONELEC-349463-C Component 3. Technical Assi Individual Consult Under Implement S-INDV / Recrutement d'un c IDA / E0490 stance and Project Manage Post Open - National 53,000.00 0.00 2023-03-17 2023-04-03 2023-04-10 2023-04-12 2023-04-16 2023-10-13 ant Selection ation omptable de l'AEP ment KM-AEP SONELEC-349484-C Component 3. Technical Assi Individual Consult Under Implement S-INDV / Recrutement de l'As IDA / E0490 stance and Project Manage Post Open - National 45,000.00 0.00 2023-03-24 2023-05-24 2023-04-25 2023-04-30 2023-05-24 2024-05-23 ant Selection ation sistant(e) Administratif(ve) d ment e l'AEP KM-AEP SONELEC-362597-C Component 3. Technical Assi Individual Consult Under Implement S-INDV / Recrutement d'un S IDA / E0490 stance and Project Manage Post Open - National 90,000.00 0.00 2023-05-31 2023-06-19 2023-06-20 2023-07-04 2023-07-25 2024-01-21 ant Selection ation pécialiste en Violence Basée ment sur le Genre Page 2 KM-AEP SONELEC-362614-C Component 3. Technical Assi Individual Consult Pending Impleme S-INDV / Recrutement Spécia IDA / E0490 stance and Project Manage Post Open - National 90,000.00 0.00 2023-05-31 2023-07-03 2023-07-10 2023-07-31 2024-07-30 ant Selection ntation liste Hygiène Santé Securite ment au travail KM-AEP SONELEC-362637-C Component 3. Technical Assi Individual Consult Pending Impleme S-INDV / Recrutement de l'As IDA / E0490 stance and Project Manage Post Open - National 53,000.00 0.00 2023-05-24 2023-06-22 2023-06-24 2023-06-29 2023-07-02 ant Selection ntation sistant(e) en passation de m ment archés de l'AEP KM-AEP SONELEC-362674-C Component 3. Technical Assi Individual Consult Pending Impleme S-INDV / Recrutement du gar IDA / E0490 stance and Project Manage Post Limited 29,000.00 0.00 2023-05-26 2023-05-31 2023-06-03 2023-06-09 2024-06-08 ant Selection ntation dien de l'AEP ment KM-AEP SONELEC-362675-C Component 3. Technical Assi Individual Consult Pending Impleme S-INDV / Recrutement d'un A IDA / E0490 stance and Project Manage Post Limited 24,000.00 0.00 2023-05-26 2023-05-31 2023-06-03 2023-06-15 2024-06-14 ant Selection ntation gent d'entretien des bureaux ment de l'AEP KM-AEP SONELEC-362676-C Component 3. Technical Assi Individual Consult Pending Impleme S-INDV / Recrutement du cha IDA / E0490 stance and Project Manage Post Limited 33,000.00 0.00 2023-06-08 2023-06-13 2023-06-18 2023-06-28 2024-06-27 ant Selection ntation uffeur de la coordination de l' ment AEP KM-AEP SONELEC-362677-C Component 3. Technical Assi Individual Consult Pending Impleme S-INDV / Recrutement du cha IDA / E0490 stance and Project Manage Post Limited 33,000.00 0.00 2023-06-15 2023-06-20 2023-06-25 2023-07-01 2024-06-30 ant Selection ntation uffeur coursier de l'AEP ment KM-AEP SONELEC-362679-C Component 3. Technical Assi S-INDV / Recrutement du (1e Individual Consult Pending Impleme IDA / E0490 stance and Project Manage Post Limited 33,000.00 0.00 2023-06-15 2023-06-20 2023-06-25 2023-07-01 2024-06-30 r) chauffeur pour les visites d ant Selection ntation ment e terrain de l'AEP KM-AEP SONELEC-362680-C Component 3. Technical Assi Individual Consult Pending Impleme S-INDV / Recrutement du (2e IDA / E0490 stance and Project Manage Post Limited 33,000.00 0.00 2023-06-15 2023-06-20 2023-06-25 2023-07-01 2024-06-30 ant Selection ntation r) chauffeur de terrain de l'A ment EP KM-AEP SONELEC-362683-C Component 3. Technical Assi Individual Consult Pending Impleme S-INDV / Recrutement d'un (1 IDA / E0490 stance and Project Manage Post Open - National 5,500.00 0.00 2023-05-31 2023-07-01 2023-07-04 2023-07-16 2024-12-27 ant Selection ntation er) stagiaire en passation de ment marchés KM-AEP SONELEC-362689-C Component 3. Technical Assi Individual Consult Pending Impleme S-INDV / Recrutement d'un (2 IDA / E0490 stance and Project Manage Post Open - National 5,500.00 0.00 2023-05-31 2023-06-26 2023-06-29 2023-07-11 2024-12-22 ant Selection ntation eme) stagiaire en passation ment de marchés Page 3 PROCUREMENT PLAN (Textual Part) Project information: [country] [Project name] [P-number] Sri Lanka CLIMATE RESILIENCE MULTIPHASE PROGRAMMATIC APPROACH P 160005 Project Implementation agency: Ministry of Agriculture, Rural Economic Affairs, Livestock Development, Irrigation, Fisheries and Aquatic Resources Development : [insert legal name] Date of the Procurement Plan: [insert date]April 18, 2019 Period covered by this Procurement Plan: [insert from – to period]April 2019 to October 2021 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with the Procurement Regulations for IPF Borrowers (July 2016, revised November 2017) (“Procurement Regulations”), when approaching the national market, as agreed in the Procurement Plan tables in STEP, the country’s own procurement procedures may be used. When the Borrower, for the procurement of goods, works and non-consulting services, uses its own national open competitive procurement arrangements as set forth in Sri Lanka’s Procurement Guidelines 2006, such arrangements shall be subject to paragraph 5.4 of the Bank’s Procurement Regulations and the following conditions: 1. Only bidding documents acceptable to the Bank shall be used for all national open competitive procurement. 2. The request for bids/request for proposals document shall require that bidders/proposers submitting bids/proposals present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights. 3. The eligibility of bidders shall be as defined under Section III of the World Bank Procurement Regulations for IPF Borrowers (Procurement Regulations): accordingly, no bidder or potential bidder shall be declared ineligible for contracts financed by the Bank for reasons other than those provided in Section III of the Procurement Regulations. : In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in [insert appropriate references to the national procurement legislation], such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. List only the applicable conditions required to ensure consistency with paragraph 5.4 of the Procurement Regulations. If no conditions apply, delete the phrase “and the following conditions”. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. Otherwise state “Not Applicable”Not Applicable Procurement of Second- Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables : Otherwise state “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Specify for each Goods: [is not applicable/is applicable for those contracts identified in the Procurement Plan tables]; Works: [is not applicable/is applicable for those contracts identified in the Procurement Plan tables] Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations is Applicable. [Include this sentence only if the Bank has formally agreed to provide the Borrower with HEIS. Otherwise delete] Other Relevant Procurement Information. Provide any other relevant procurement information such as procedures for CDD components, Procurement in Situations of Urgent Need of Assistance or Capacity Constraints etc. PROCUREMENT Sri Lanka : Climate Resilience Multi-Phase Programmatic Approach PLAN General Information Country: Sri Lanka 2022-07-29 Bank’s Approval Date of the Original Procurement Plan: 2023-06-05 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P160005 GPN Date: 2019-07-28 Project Name: Climate Resilience Multi-Phase Programmatic Approach Loan / Credit No: IBRD / 89960 MINISTRY OF IRRIGATION Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned National Procure SLMOI/CRES/DOM/W/NCB/01 Component 1: Forecasting a ment Document - / Construction of National Me nd Early Warning of High Im Single Stage - One E 2024-06-1 IBRD / 89960 Post Request for Bids Open - National 1 Envelope proce 4,500,000.00 0.00 Canceled 2022-09-30 2022-10-05 2022-10-26 2022-11-25 2023-02-17 teorological Center Building a pact Weather, Floods and La nvelope 4 ss (Non Bank-SPD t Department of Meteorology ndslides ) National Procure SLMOI/CRES/ID/W/NCB/03 / Component 1: Forecasting a ment Document - Refurbishment of the office s nd Early Warning of High Im Single Stage - One E Under Imple 2023-01-1 IBRD / 89960 Post Request for Bids Open - National 1 Envelope proce 56,000.00 0.00 2022-08-31 2022-10-12 2022-09-05 2022-09-26 2022-10-17 2022-11-14 pace of Hydrology & DM Divi pact Weather, Floods and La nvelope mentation 3 ss (Non Bank-SPD sion of Irrigation Department ndslides ) National Procure SLMOI/CRES/DMC/W/NCB/08 Component 1: Forecasting a ment Document - Single Stage - One E Pending Imp 2023-05-2 / Refurbishment of EOC at Di IBRD / 89960 nd Early Warning of High Im Post Request for Bids Open - National 1 Envelope proce 400,000.00 0.00 2022-11-21 2022-11-26 2022-12-17 2023-01-16 2023-02-27 nvelope lementation 8 saster Management Centre pact Weather, Floods and La ss (Non Bank-SPD ndslides ) Request for Bids - SLMOI/CRES/ID/W/ICB/02 / C Component 2: Flood Risk Mit Open - Internationa Single Stage - One E Small Works SPD 16,750,000.0 Pending Imp 2026-05-0 onstruction of Ambatale Salin IBRD / 89960 igation Investments in the lo Prior Request for Bids 0.00 2023-10-02 2023-10-16 2023-12-15 2024-03-14 2024-05-19 l nvelope (1 envelope proce 0 lementation 9 ity Barrier wer Kelani basin ss) SLMOI/CRES/ID/W/NCB/04 / National Procure Development of Flood Monito Component 1: Forecasting a ment Document - ring and Operation Center co nd Early Warning of High Im Single Stage - One E Pending Imp 2023-06-0 IBRD / 89960 Post Request for Bids Open - National 1 Envelope proce 520,000.00 0.00 2022-09-12 2022-09-17 2022-10-08 2022-10-23 2022-12-11 upled with CCTV Flood Level pact Weather, Floods and La nvelope lementation 9 ss (Non Bank-SPD Monitoring System at Hydrol ndslides ) ogy & Disaster Management Division GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SLMOI/CRES/ID/G/NCB/05 / P Component 1: Forecasting a rocurement of Computers an nd Early Warning of High Im Single Stage - One E Under Imple d UPS for Hydrology and Disa IBRD / 89960 Post Request for Bids Open - National 52,000.00 0.00 2022-08-26 2022-10-10 2022-08-28 2022-10-18 2022-09-18 2022-11-09 2022-10-03 2023-01-04 2022-11-09 2023-03-09 pact Weather, Floods and La nvelope mentation ster Management Division at ndslides Irrigational Department SLMOI/CRES/NBRO/G/NCB/0 Component 1: Forecasting a 2 / Procurement of IT and oth nd Early Warning of High Im Single Stage - One E Under Imple IBRD / 89960 Post Request for Bids Open - National 203,500.00 0.00 2022-10-26 2022-10-12 2022-10-28 2022-11-18 2022-12-02 2023-01-08 2023-05-08 er related equipment and Hi pact Weather, Floods and La nvelope mentation gh-end server for NBRO ndslides SLMOI/CRES/ID/G/NCB/04 / P Component 1: Forecasting a rocurement of hydrological m nd Early Warning of High Im Single Stage - One E Under Imple easuring equipment and wea IBRD / 89960 Post Request for Bids Open - National 172,000.00 0.00 2022-08-31 2022-10-10 2022-09-02 2022-10-18 2022-09-23 2022-11-09 2022-10-14 2022-12-28 2022-11-20 2023-03-20 pact Weather, Floods and La nvelope mentation ther instruments for Hydrolo ndslides gy and Disaster Management Division SLMOI/CRES/NBRO/G/S/03 / Component 1: Forecasting a Procurement of Digital Panals nd Early Warning of High Im Request for Quota Single Stage - One E IBRD / 89960 Post Limited 35,500.00 0.00 Canceled 2022-10-28 2023-01-09 2023-05-09 for displaying ARG System an pact Weather, Floods and La tions nvelope d other sensor networks of N ndslides BRO SLMOI/CRES/NBRO/G/S/06 / Component 1: Forecasting a Procurement of office furnitur nd Early Warning of High Im Request for Quota Single Stage - One E Under Imple IBRD / 89960 Post Limited 22,000.00 0.00 2022-10-02 2022-12-14 2023-04-13 e for Landslide Early Warning pact Weather, Floods and La tions nvelope mentation Center at National Building R ndslides esearch Organization SLMOI/CRES/NBRO/G/NCB/0 Component 1: Forecasting a 3 / Procurement of Digital Pa nd Early Warning of High Im Single Stage - One E Under Imple IBRD / 89960 Post Request for Bids Open - National 70,000.00 0.00 2022-10-17 2022-10-12 2022-10-22 2022-12-03 2023-01-18 2023-01-02 2023-05-03 2023-02-06 2023-06-06 nels for Displaying ARG Syste pact Weather, Floods and La nvelope mentation m and other Sensor Network ndslides s of NBRO NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SLMOI/CRES/ID/C/CQS/28 / C Component 2: Flood Risk Mit Consultant Qualifi Pending Impleme onsultancy Services for Socio IBRD / 89960 igation Investments in the lo Post Open - National 25,000.00 0.00 2022-09-30 2022-10-21 2022-12-04 2023-01-03 2023-02-07 2023-05-08 cation Selection ntation -economic Survey for Wee O wer Kelani basin ya Reservoir SLMOI/CRES/DMC/C/CQS/12 / Comprehensive Study on D Component 1: Forecasting a ata Availability, potential App nd Early Warning of High Im Consultant Qualifi Pending Impleme IBRD / 89960 Post Open - National 44,000.00 0.00 2022-10-17 2022-11-07 2022-12-21 2023-01-20 2023-02-24 2023-08-23 lication of Spatial and non sp pact Weather, Floods and La cation Selection ntation atial data for DRM and devel ndslides opment of governance mech anism for utilization Page 1 SLMOI/CRES/ID/C/CQS/10 / D Component 1: Forecasting a eveloping a cloud-based Web nd Early Warning of High Im Consultant Qualifi IBRD / 89960 Post Limited 28,000.00 0.00 Under Review 2022-08-31 2022-10-05 2022-09-20 2022-10-20 2022-11-24 2023-05-23 Portal for archiving and displ pact Weather, Floods and La cation Selection aying data gathered from var ndslides ious systems SLMOI/CRES/ID/C/QCBS/03 / Component 2: Flood Risk Mit Quality And Cost- Pending Impleme Preparation of Environmental IBRD / 89960 igation Investments in the lo Post Open - National 225,000.00 0.00 2023-01-16 2023-02-06 2023-03-22 2023-04-19 2023-05-19 2023-06-23 2023-07-28 2024-01-24 Based Selection ntation Impact Assessments for Wee wer Kelani basin Oya Reservoir SLMOI/CRES/ID/C/QCBS/05 / Component 2: Flood Risk Mit Consultancy Service for Desi Quality And Cost- Open - Internationa Under Implement IBRD / 89960 igation Investments in the lo Prior 2,500,000.00 0.00 2022-09-12 2022-10-12 2022-10-12 2022-10-20 2022-12-26 2023-05-15 2023-01-25 2023-03-26 2023-05-09 2023-07-07 2026-05-13 gn Review and Construction Based Selection l ation wer Kelani basin Supervision of Salinity Barrie r at Ambatale SLMOI/CRES/ID/C/QCBS/02 / Component 2: Flood Risk Mit Quality And Cost- Pending Impleme Preparation of Resettlement IBRD / 89960 igation Investments in the lo Post Open - National 220,000.00 0.00 2023-01-16 2023-02-06 2023-03-22 2023-04-19 2023-05-19 2023-06-23 2023-07-28 2024-04-23 Based Selection ntation Action Plan for Wee Oya Res wer Kelani basin ervoir SLMOI/CRES/DMC/C/CQS/18 Component 1: Forecasting a / Engineering assistance for t nd Early Warning of High Im Consultant Qualifi Pending Impleme he architectural and interior IBRD / 89960 Post Limited 20,000.00 0.00 2022-09-19 2022-10-03 2022-11-02 2022-12-07 2023-06-05 pact Weather, Floods and La cation Selection ntation designing of EOC considering ndslides the maximum utilization of th e existing resources SLMOI/CRES/PCT/C/CQS/24 / Developing of the Web Based Component 4: Project Manag Consultant Qualifi Under Implement IBRD / 89960 Post Limited 25,000.00 0.00 2022-09-15 2023-02-13 2022-09-29 2023-03-27 2022-10-29 2022-12-03 2023-06-01 Management Information Sys ement cation Selection ation tem (MIS) for CResMPA SLMOI/CRES/ID/C/CQS/06 / B Component 2: Flood Risk Mit Consultant Qualifi Under Implement iodiversity Assessment for W IBRD / 89960 igation Investments in the lo Post Limited 30,000.00 0.00 2022-09-15 2022-11-01 2022-10-05 2022-11-04 2022-12-09 2023-04-08 cation Selection ation ee Oya Reservoir Area wer Kelani basin SLMOI/CRES/ID/C/CQS/29 / H Component 2: Flood Risk Mit Consultant Qualifi Pending Impleme iring of Consultants for Dam IBRD / 89960 igation Investments in the lo Post Limited 40,000.00 0.00 2022-12-15 2023-01-14 2023-03-15 2023-05-15 2026-08-27 cation Selection ntation Safety Review Panel for Wee wer Kelani basin Oya Reservoir SLMOI/CRES/ID/C/QCBS/01 / Component 2: Flood Risk Mit Preparation of Detail Enginee Quality And Cost- Open - Internationa IBRD / 89960 igation Investments in the lo Prior 3,500,000.00 0.00 Canceled 2022-09-15 2022-10-11 2022-10-15 2022-10-20 2023-02-12 2023-02-26 2023-04-27 2023-06-25 2023-07-23 2024-04-18 ring Design and Bidding Doc Based Selection l wer Kelani basin ument for Wee Oya Reservoir SLMOI/CRES/DOM/C/QCBS/3 Component 1: Forecasting a 0 / Consultancy Services for nd Early Warning of High Im Quality And Cost- Open - Internationa Systems Integration for the IBRD / 89960 Prior 3,000,000.00 0.00 Canceled 2023-01-10 2023-01-31 2023-03-16 2023-04-13 2023-05-13 2023-06-17 2023-07-22 2024-07-21 pact Weather, Floods and La Based Selection l Modernization of the Depart ndslides ment of Meteorology, Sri Lan ka SLMOI/CRES/ID/C/QCBS/01-2 Component 2: Flood Risk Mit / Preparation of Detail Engine Quality And Cost- Open - Internationa Under Implement IBRD / 89960 igation Investments in the lo Prior 2,400,000.00 0.00 2023-06-12 2023-07-12 2023-11-09 2023-11-23 2024-01-22 2024-03-21 2024-04-18 2025-02-12 ering Design and Bidding Do Based Selection l ation wer Kelani basin cument for Wee Oya Reservo ir SLMOI/CRES/DOM/C/QCBS/3 Component 1: Forecasting a 0-2 / Consultancy Services fo nd Early Warning of High Im Quality And Cost- Open - Internationa Under Implement r Systems Integration for the IBRD / 89960 Prior 3,000,000.00 0.00 2023-06-12 2023-06-07 2023-07-03 2023-06-23 2023-08-16 2023-09-13 2023-10-13 2023-11-17 2023-12-22 2026-12-31 pact Weather, Floods and La Based Selection l ation Modernization of the Depart ndslides ment of Meteorology, Sri Lan ka INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual LK-MAREALIFA-302011-CS-IN Component 1: Forecasting a DV / Cres/ID/C/IC/26 - Individ nd Early Warning of High Im Individual Consult ual consultant for ICT infrastr IBRD / 89960 Post Limited 8,000.00 0.00 Canceled 2022-07-15 2022-07-20 2022-08-10 2022-09-14 2023-03-13 pact Weather, Floods and La ant Selection ucture development of flood ndslides monitoring and operation roo m SLMOI/CRES/ID/C/IC/26 / Indi Component 1: Forecasting a vidual consultant for ICT infra nd Early Warning of High Im Individual Consult Under Implement IBRD / 89960 Post Limited 8,000.00 0.00 2022-08-29 2022-09-14 2022-09-03 2022-09-24 2022-10-29 2023-04-27 structure development of flo pact Weather, Floods and La ant Selection ation od monitoring and operation ndslides room SLMOI/CRES/PCT/C/DS/23 / C onsortium Architectural Cons Component 1: Forecasting a ultancy Services of Proposed nd Early Warning of High Im Pending Impleme IBRD / 89960 Post Direct Selection Direct - National 47,000.00 0.00 2022-11-15 2022-11-25 2023-01-29 2024-08-01 Disaster Risk Reduction Obse pact Weather, Floods and La ntation rvation, Forecasting and Com ndslides munication Hubs for Depart ment of Meteorology Component 1: Forecasting a SLMOI/CRES/PCT/C/DS/25 / H Pending Impleme IBRD / 89960 nd Early Warning of High Im Post Direct Selection Direct - National 6,400.00 0.00 2022-09-16 2022-09-26 2022-11-30 2023-08-27 iring of Local Expert - ICT ntation pact Weather, Floods and La ndslides SLMOI/CRES/ID/C/DS/27 / Co nsultancy Services for updati Component 2: Flood Risk Mit ng the Environmental and So IBRD / 89960 igation Investments in the lo Post Direct Selection Direct - National 25,000.00 0.00 Under Review 2023-02-01 2023-05-25 2023-02-11 2023-04-28 2026-03-15 cial Impact Assessment for A wer Kelani basin mbathale Salinity Barrier Page 2 PROCUREMENT PLAN (Textual Part) Project information: [country] [Project name] [P-number] Project Implementation agency: [insert legal name] Date of the Procurement Plan: [insert date] Period covered by this Procurement Plan: [insert from – to period] Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in [insert appropriate references to the national procurement legislation], such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. List only the applicable conditions required to ensure consistency with paragraph 5.4 of the Procurement Regulations. If no conditions apply, delete the phrase “and the following conditions”. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. Otherwise state “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables Otherwise state “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Specify for each Goods: [is not applicable/is applicable for those contracts identified in the Procurement Plan tables]; Works: [is not applicable/is applicable for those contracts identified in the Procurement Plan tables] Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations is Applicable. [Include this sentence only if the Bank has formally agreed to provide the Borrower with HEIS. Otherwise delete] Other Relevant Procurement Information. Provide any other relevant procurement information such as procedures for CDD components, Procurement in Situations of Urgent Need of Assistance or Capacity Constraints etc. PROCUREMENT Tanzania : Zanzibar Improving Quality of Basic Education Project PLAN General Information Country: Tanzania 2023-03-28 Bank’s Approval Date of the Original Procurement Plan: 2023-06-06 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P178157 GPN Date: 2023-03-28 Project Name: Zanzibar Improving Quality of Basic Education Project Loan / Credit No: IDA / 72580 Ministry of Education and Vocational Traiing Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TZ-MOEVT-342184-CS-QCBS / Consulting Services for Desi gn, Preparation of Cost Estim ate, Bidding documents and Support Conducive Learning Quality And Cost- Under Implement IDA / 72580 Post Open - National 420,000.00 0.00 2023-04-10 2023-04-06 2023-05-01 2023-06-08 2023-06-20 2023-07-04 2023-07-24 2023-08-17 2023-09-21 2023-11-16 Construction Supervision for Environments Based Selection ation the Proposed Extension of M oEVT Head Office and two Te acher's Training Collage at M azizini Unguja and Micheweni n Pemba. TZ-MOEVT-353450-CS-CQS / Consultancy Services for Envi ronmental and Social Impact s Assessment for Proposed E Support Conducive Learning Consultant Qualifi xtension of MoEVT Head Offic IDA / 72580 Post Open - National 96,000.00 0.00 Canceled 2023-04-05 2023-04-06 2023-04-20 2023-05-01 2023-06-09 2023-06-29 2023-08-03 2023-11-01 Environments cation Selection e, Proposed Construction of 7 Secondary Schools and Exten sion of Teacher's Training Col lage at Mazizini Unguja and Micheweni Pemba. TZ-MOEVT-364353-CS-CQS / Consultancy Services for Envi ronmental and Social Impact s Assessment for Proposed E Support Conducive Learning Consultant Qualifi Under Implement xtension of MoEVT Head Offic IDA / 72580 Post Open - National 60,000.00 0.00 2023-05-30 2023-06-20 2023-07-11 2023-07-21 2023-08-25 2023-11-23 Environments cation Selection ation e, Proposed Construction of 7 Secondary Schools and Exten sion of Teacher's Training Col lage at Mazizini Unguja and Micheweni Pemba. TZ-MOEVT-353471-CS-CQS / Consulting Services for Desig n, Preparation of Cost Estima Support Conducive Learning Consultant Qualifi te, Bidding documents and C IDA / 72580 Post Open - National 210,000.00 0.00 Canceled 2023-04-10 2023-04-25 2023-06-14 2023-07-04 2023-08-08 2024-11-30 Environments cation Selection onstruction Supervision for th e Proposed Construction of 7 Secondary Schools in Unguja and Pemba INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TZ-MOEVT-342191-CS-INDV / Employment of Individual Pr ocurement Specialist to supp Strengthen Systems and Su Individual Consult Under Implement IDA / 72580 Prior Open - National 90,000.00 0.00 2023-04-10 2023-04-20 2023-05-24 2023-06-14 2023-07-19 2025-07-18 ort the implementation of the pport Project Management ant Selection ation Procurement functions for fir st 18 months implementation of ZIQUE Project. Page 1 PLAN DE PASSATION DE MARCHÉS (Texte) Information sur le Projet : Djibouti, Projet Intégré de Résorption des Bidonvilles (P162901) Agence d’exécution du Projet : Fonds de l’Habitat Date du plan de passation des marchés : 2 novembre 2017 Période couverte par ce plan de passation des marchés : 17 juillet 2017-31 décembre 2018 Préambule Conformément au paragraphe 5.9 du “Règlement de Passation des Marchés pour les Emprunteurs sollicitant le Financement de Projets d’Investissement (FPI)” (Juillet 2016) (“Règlement de Passation des Marchés”) le Système électronique de la Banque de suivi systématique des transactions de marchés publics (STEP) sera utilisé pour préparer, valider et actualiser les plans de passation des marchés et effectuer toutes les transactions liées à la passation des marchés du projet. Ce texte ainsi que les tableaux du plan de passation des marchés présents dans STEP constituent le plan de passation des marchés du projet. Les conditions suivantes s'appliquent à toutes les activités de passation de marchés du plan de passation de marchés. Les autres éléments du plan de passation des marchés tels que requis au paragraphe 4.4 du Règlement de passation des marchés sont énoncés dans STEP. Les Dossiers types de passation des marchés publics de la Banque devront être utilisés pour tous les contrats soumis à la concurrence internationale, ainsi que pour tous les autres contrats soumis à cette obligation telle que spécifiée dans les tableaux du plan de passation des marchés de STEP. Procédures nationales de passation des marchés : En accord avec le paragraphe 5.3 du Règlement de passation des marchés, dans le cas où la procédure de passation des marché se fera au niveau national (telle que spécifiée dans les tableaux du plan de passation des marchés inclus de STEP), les procédures nationales de passation des marchés du pays considéré pourront être utilisées. Si l’Emprunteur utilise ses propres procédures d’appel d’offres national ouvert telles qu’énoncées dans la Loi n°53/AN/09/6ème L portant Nouveau Code des Marchés Publics, ces arrangements sont soumis aux dispositions du paragraphe 5.4 du Règlement de passation des marchés. Lorsque l’Emprunteur utilise d’autres procédures que l’appel d’offres national ouvert, ces procédures devront être en accord avec les dispositions du paragraphe 5.5 du Règlement de passation des marchés. Crédit-bail tel que spécifié au paragraphe 5.10 du Règlement de Passation des marchés : « Sans objet » Achat de biens d’occasion tel que spécifié au paragraphe 5.11 du Règlement de Passation des Marchés : « Sans objet » Préférence nationale telle que spécifiée au paragraphe 5.51 du Règlement de Passation des Marchés (Fournitures et Travaux). Fournitures : ne s’applique pas Travaux : ne s’applique pas PROCUREMENT Djibouti : Djibouti Integrated Slum Upgrading Project PLAN General Information Country: Djibouti 2017-11-07 Bank’s Approval Date of the Original Procurement Plan: 2023-06-06 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P162901 GPN Date: Project Name: Djibouti Integrated Slum Upgrading Project Loan / Credit No: IDA / V0980, IDA / 63380, IDA / D7590 Habitat Fund Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned DJ-FDH-68733-CW-RFB / Rec Participatory upgrading inve rutement d'une entreprise po Single Stage - One E 1,725,830.5 2019-05-2 IDA / V0980 stments in selected urban ar Post Request for Bids Open - National 1,500,000.00 Completed 2018-08-01 2018-11-23 2018-08-06 2018-09-17 2019-01-30 2018-10-17 2019-02-20 2018-11-21 2019-04-23 ur les travaux de constructio nvelope 1 0 eas n de la voie de désenclavem ent de Balbala ancien DJ-FDH-126388-CW-RFB / Tr Participatory upgrading inve avaux de démolition/reconstr Single Stage - One E 2019-12-1 IDA / 63380 stments in selected urban ar Post Request for Bids Limited 600,000.00 894,180.22 Signed 2019-08-15 2019-09-01 2019-08-20 2019-09-02 2019-09-10 2019-09-25 2019-09-25 2019-12-04 2019-10-16 2020-01-09 uction des biens physiques i nvelope 5 eas mpactés par la voie commer çante DJ-FDH-68740-CW-RFB / Rec rutement d'une entreprise po Participatory upgrading inve Single Stage - One E 2019-02-1 ur les travaux de reconstructi IDA / V0980 stments in selected urban ar Post Request for Bids Limited 70,000.00 0.00 Canceled 2018-08-01 2018-08-06 2018-09-17 2018-10-17 2018-11-21 nvelope 9 on des biens eas physiques impactés par la vo ie commercante DJ-FDH-126389-CW-RFB / Tr Participatory upgrading inve Open - Internationa Single Stage - One E 1,788,421.6 2020-11-1 avaux d'aménagement de la IDA / 63380 stments in selected urban ar Post Request for Bids 2,000,000.00 Signed 2020-01-30 2021-05-05 2020-02-04 2021-05-16 2020-03-17 2021-06-10 2020-04-16 2021-06-23 2020-05-21 2021-10-06 l nvelope 2 7 zone de récasement eas DJ-FDH-209424-CW-RFQ / Tr avaux d'aménagement des l Emergency response to COV Request for Quota Single Stage - One E 2021-07-0 ocaux de l'ARULoS pour resp IDA / 63380 Post Open - National 100,000.00 99,829.27 Signed 2021-01-08 2021-03-05 2021-05-27 ID-19 and to the floods tions nvelope 3 ecter la politique de préventi on et de la propagation du C ovid-19 DJ-FDH-209425-CW-RFQ / Tr Emergency response to COV Request for Quota Single Stage - One E 2021-05-2 avaux de construction d'un o IDA / 63380 Post Open - National 400,000.00 534,835.13 Signed 2020-12-26 2021-02-20 2021-05-27 ID-19 and to the floods tions nvelope 1 uvrage de drainage à Nassib DJ-FDH-239880-CW-DIR / Tra vaux d’électricité et d’éclaira Participatory upgrading inve Other (with field f 2022-02-0 ge public de la mailles 2 de l IDA / 63380 stments in selected urban ar Post Direct Selection Direct 600,700.00 599,655.84 Signed 2021-07-01 2021-07-04 2021-07-06 2021-09-29 2021-08-10 2022-02-17 or explanation) 6 a zone de relogement et de p eas révention de Balbala Sud Request for Bids - DJ-FDH-266465-CW-RFB / Tr Participatory upgrading inve Single Stage - One E Works (without pr 1,441,292.3 2022-07-2 avaux de voirie de Balbala a IDA / 63380 stments in selected urban ar Post Request for Bids Open - National 1,500,000.00 Signed 2021-10-04 2021-10-05 2021-10-09 2021-11-20 2021-11-17 2021-12-20 2021-11-24 2022-01-24 2022-03-11 nvelope equalification) SP 1 3 ncien: 2 voies en pierre taillé eas D es Request for Bids - DJ-FDH-301096-CW-RFB / Co Participatory upgrading inve Single Stage - One E Small Works SPD Under Imple 2023-08-1 nstruction d'un CDC et d'un t IDA / 63380 stments in selected urban ar Post Request for Bids Open - National 310,000.00 0.00 2022-06-29 2022-06-22 2022-07-04 2022-08-15 2022-09-14 2022-10-19 nvelope (1 envelope proce mentation 5 errain de sport à Balbala Anci eas ss) en DJ-FDH-353352-CW-RFB / Tr Request for Bids - Participatory upgrading inve avaux de construction des éq Single Stage - One E Works (without pr Under Imple 2024-07-1 IDA / 63380 stments in selected urban ar Post Request for Bids Open - National 335,000.00 0.00 2023-03-28 2023-05-03 2023-04-02 2023-05-14 2023-06-13 2023-07-18 uipements publics pour le qu nvelope equalification) SP mentation 7 eas artier 9 du Balbala ancien D GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual DJ-FDH-102334-GO-RFB / Ac Single Stage - One E quisition de deux véhicules Pi IDA / V0980 Project management Post Request for Bids Open - National 70,000.00 59,941.03 Completed 2019-02-21 2019-02-26 2019-03-26 2019-03-27 2019-04-16 2019-04-10 2019-05-21 2019-05-02 2019-06-20 2019-06-02 nvelope ck up pour la coordination et le suivi DJ-FDH-126354-GO-RFQ / Ac Request for Quota Single Stage - One E IDA / 63380 Project management Post Limited 30,000.00 27,805.88 Completed 2019-08-30 2019-09-09 2019-10-25 2019-10-20 2020-04-22 2019-11-20 hats de matériels informatiqu tions nvelope es DJ-FDH-126373-GO-RFQ / Ac Request for Quota Single Stage - One E IDA / 63380 Project management Post Limited 30,000.00 27,253.76 Completed 2019-08-30 2019-09-09 2019-10-25 2019-10-20 2020-04-22 2019-11-20 hats de mobiliers de bureaux tions nvelope DJ-FDH-126411-GO-RFQ / Ac Participatory upgrading inve quisition des équipements inf Request for Quota Single Stage - One E IDA / 63380 stments in selected urban ar Post Limited 12,000.00 27,962.83 Completed 2019-10-05 2022-04-19 2019-11-30 2022-07-05 2019-12-30 2022-07-27 ormatiques et des mobiliers tions nvelope eas pour l'Ingénierie Sociale DJ-FDH-34737-GO-RFQ / Ach Request for Quota Single Stage - One E at d'ordinateur et de mobilier IDA / V0980 Post Open - National 20,000.00 0.00 Canceled 2017-11-20 2018-01-15 2018-03-01 tions nvelope s de bureaux pour l'expert DJ-FDH-126409-GO-RFB / Ac Participatory upgrading inve quisition d'un véhicule pour l Request for Quota Single Stage - One E IDA / 63380 stments in selected urban ar Post Open - National 28,000.00 28,057.86 Completed 2019-09-14 2019-11-09 2020-01-08 2019-12-09 2020-02-24 a supervision et le déplacem tions nvelope eas ent de l'équipe de l'Ingénieri e Sociale DJ-FDH-202547-GO-RFQ / Ac Emergency response to COV Request for Quota Single Stage - One E quisition de matériaux de co IDA / 63380 Post Open - National 900,000.00 474,493.70 Signed 2020-11-13 2021-01-08 2021-10-11 2022-01-08 ID-19 and to the floods tions nvelope nstructions - Ciments et fer à béton DJ-FDH-202581-GO-RFQ / Ac Emergency response to COV Request for Quota Single Stage - One E quisition de matériaux de co IDA / 63380 Post Open - National 400,000.00 301,839.69 Signed 2020-11-13 2021-01-08 2021-07-28 2022-01-08 ID-19 and to the floods tions nvelope nstructions - Parpaings DJ-FDH-202582-GO-RFQ / Ac Emergency response to COV Request for Quota Single Stage - One E quisition de matériaux de co IDA / 63380 Post Open - National 300,000.00 291,588.33 Signed 2020-11-13 2021-01-08 2022-06-16 2022-01-08 ID-19 and to the floods tions nvelope nstructions - Menuiseries Page 1 DJ-FDH-202583-GO-RFQ / Ac Emergency response to COV Request for Quota Single Stage - One E quisition de matériaux de co IDA / 63380 Post Open - National 300,000.00 238,959.48 Signed 2020-11-13 2021-01-08 2021-07-28 2022-01-08 ID-19 and to the floods tions nvelope nstructions - Toiture et quinc ailleries DJ-FDH-216883-GO-RFB / Ac Support to the elaboration of quisitions des véhicules et de Single Stage - One E IDA / 63380 the ZSP strategic framework Post Request for Bids Open - National 285,000.00 277,854.30 Completed 2020-08-23 2020-08-24 2020-08-28 2020-10-09 2020-09-16 2020-11-08 2020-10-07 2020-12-13 2020-10-15 2021-02-11 2020-12-29 s engins de construction pour nvelope and investment plan la préfecture de Djibouti DJ-FDH-236685-GO-RFQ / Ac Support to the elaboration of Request for Quota Single Stage - One E quisition de matériels inform IDA / 63380 the ZSP strategic framework Post Open - National 30,000.00 49,890.34 Completed 2021-05-14 2021-07-09 2021-10-29 2021-09-07 2021-12-31 tions nvelope atiques pour le compte de la and investment plan DATUH DJ-FDH-239886-GO-RFB / Ac Single Stage - One E IDA / D7590 Project management Post Request for Bids Open - National 120,000.00 84,443.92 Completed 2021-07-01 2021-07-28 2021-07-06 2021-08-05 2021-08-25 2021-08-20 2021-09-01 2021-09-24 2021-09-28 2021-11-23 2021-10-06 quistion de véhicules nvelope DJ-FDH-266862-GO-RFB / Ac Support to the elaboration of Single Stage - One E quisitions de 3 vehicules pick IDA / D7590 the ZSP strategic framework Post Request for Bids Open - National 105,000.00 92,845.70 Completed 2021-09-01 2021-09-23 2021-09-06 2021-10-06 2021-10-27 2021-10-20 2021-11-03 2021-11-24 2021-11-19 2021-12-24 2021-12-27 nvelope up au profit de la DDCF and investment plan DJ-FDH-244881-GO-RFQ / Ac quisition et installation d'une Support to the elaboration of Single Stage - One E station CORS et les logiciels c IDA / 63380 the ZSP strategic framework Post Request for Bids Open - National 80,000.00 0.00 Canceled 2021-09-08 2021-09-05 2021-09-13 2021-10-13 2021-10-27 2021-10-28 2021-12-02 2022-03-02 nvelope orrespondants pour la Directi and investment plan on des Domaines et de la Co nservation Foncière DJ-FDH-244878-GO-RFQ / Ac Support to the elaboration of quisition de tablettes pour la Request for Quota Single Stage - One E IDA / D7590 the ZSP strategic framework Post Open - National 34,000.00 0.00 Canceled 2021-08-06 2021-10-01 2021-12-30 Direction des Domaines et de tions nvelope and investment plan la Conservation Foncière DJ-FDH-244876-GO-RFQ / Ac Support to the elaboration of quisition de GPS pour la Dire Single Stage - One E IDA / 63380 the ZSP strategic framework Post Request for Bids Open - National 85,000.00 0.00 Canceled 2021-09-08 2021-09-05 2021-09-13 2021-10-13 2021-10-27 2021-10-28 2021-12-02 2022-03-02 ction des Domaines et de la nvelope and investment plan Conservation Foncière DJ-FDH-297938-GO-RFQ / L’ ACQUISITION DE MATÉRIELS I Support to the elaboration of Request for Quota Single Stage - One E Under Imple NFORMATIQUE - HARDWARE IDA / D7590 the ZSP strategic framework Post Limited 45,000.00 0.00 2022-06-28 2022-06-15 2022-09-08 2022-12-07 tions nvelope mentation POUR LA DIRECTION DES DO and investment plan MAINES ET DE LA CONSERVA TION FONCIÈRE DJ-FDH-298543-GO-RFQ / L’ ACQUISITION DE MATÉRIELS I Support to the elaboration of Request for Quota Single Stage - One E Under Imple NFORMATIQUE - SOFTWARE IDA / D7590 the ZSP strategic framework Post Limited 35,000.00 0.00 2022-06-28 2022-06-15 2022-08-30 2022-11-28 tions nvelope mentation POUR LA DIRECTION DES DO and investment plan MAINES ET DE LA CONSERVA TION FONCIÈRE DJ-FDH-301104-GO-RFQ / Ac Support to the elaboration of quisition de matériels géodés Open - Internationa Single Stage - One E Under Imple IDA / D7590 the ZSP strategic framework Post Request for Bids 240,000.00 0.00 2022-07-13 2022-07-12 2022-07-18 2022-08-17 2022-08-29 2022-09-07 2022-09-05 2022-09-14 2022-10-10 2023-01-08 iques pour la Direction des D l nvelope mentation and investment plan omaines et de la Conservatio n foncière DJ-FDH-364031-GO-RFQ / Ac Participatory upgrading inve Single Stage - One E Pending Impl IDA / D7590 Post Request for Bids Open - National 70,000.00 0.00 2023-06-06 2023-06-11 2023-07-11 2023-07-26 2023-08-30 2023-10-29 quisition d'un véhicule pour l stments in selected urban ar nvelope ementation a MASS eas NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual DJ-FDH-35172-NC-RFQ / Acti Request for Quota Single Stage - One E vités et supports divers de co IDA / V0980 Post Limited 45,000.00 0.00 Canceled 2017-12-23 2018-02-17 2018-04-18 tions nvelope mmunication CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual DJ-FDH-34629-CS-QCBS / Re crutement d'un consultant po Quality And Cost- IDA / V0980 Post Open - National 80,000.00 0.00 Canceled 2017-12-20 2018-01-10 2018-02-23 2018-03-23 2018-04-22 2018-05-27 2018-07-01 2018-11-28 ur l'étude sur la gestion du fo Based Selection ncier urbain au service de l'h abitat DJ-FDH-34632-CS-QBS / Recr utement d'un consultant pou Quality Based Sel Open - Internationa IDA / V0980 Post 150,000.00 0.00 Canceled 2017-12-11 2018-01-01 2018-02-14 2018-03-14 2018-04-13 2018-05-13 2018-06-17 2018-09-15 r le recensement des populat ection l ions des quartiers DJ-FDH-34618-CS-CQS / Recr Least Cost Selecti IDA / V0980 Post Open - National 30,000.00 0.00 Canceled 2017-12-04 2017-12-25 2018-02-07 2018-03-07 2018-04-06 2018-05-11 2018-06-15 2018-07-30 utement d'un cabinet d'audit on externe DJ-FDH-51535-CS-LCS / Recr Least Cost Selecti IDA / V0980 Prior Open - National 30,000.00 0.00 Canceled 2018-02-27 2018-04-04 2018-03-20 2018-04-19 2018-05-03 2018-06-11 2018-05-31 2018-07-18 2018-06-30 2018-09-03 2018-08-04 2018-09-08 2019-06-20 utement d'un cabinet d'audit on externe DJ-FDH-55870-CS-QCBS / Re crutement d'un consultant po Support to the elaboration of Quality And Cost- Open - Internationa ur les études urbaines et tec IDA / V0980 the ZSP strategic framework Post 200,000.00 192,922.37 Signed 2018-04-24 2018-04-19 2018-05-15 2018-05-10 2018-06-28 2018-07-17 2018-07-26 2018-09-05 2018-08-25 2018-09-26 2018-09-29 2018-11-14 2018-11-03 2019-01-27 2019-09-04 Based Selection l hniques de la zone de reloge and investment plan ment et de prévention à Balb ala Sud DJ-FDH-56020-CS-QCBS / Re Support to the elaboration of crutement d'un consultant po Quality And Cost- Open - Internationa IDA / V0980 the ZSP strategic framework Post 250,000.00 240,000.00 Completed 2018-04-24 2018-04-19 2018-05-15 2018-05-10 2018-06-28 2018-07-17 2018-07-26 2018-09-12 2018-08-25 2018-09-26 2018-09-29 2018-11-14 2018-11-03 2019-01-27 2019-05-02 2020-01-27 ur l'étude de restructuration Based Selection l and investment plan du quartier de Balbala Ancie n DJ-FDH-68702-CS-QCBS / Re Support to the elaboration of crutement d'un cabinet char Quality And Cost- Open - Internationa IDA / V0980 the ZSP strategic framework Post 80,000.00 106,948.00 Completed 2018-07-09 2018-07-30 2018-09-12 2018-09-02 2018-10-10 2018-10-03 2018-11-09 2018-10-31 2018-12-14 2018-11-14 2019-01-18 2019-01-27 2019-04-18 2020-11-15 gé de l'élaboration du cadre i Based Selection l and investment plan nstitutionnel et organisationn el de l'ARULoS Page 2 DJ-FDH-68705-CS-QCBS / Re crutement d'un consultant po Participatory upgrading inve Quality And Cost- Open - Internationa ur l'élaboration d'un plan de IDA / V0980 stments in selected urban ar Post 300,000.00 288,208.21 Completed 2018-08-06 2018-09-12 2018-08-27 2018-11-05 2018-10-10 2018-12-13 2018-11-07 2019-01-30 2018-12-07 2019-03-20 2019-01-11 2019-04-17 2019-02-15 2019-07-24 2019-08-14 2020-12-31 Based Selection l développement urbain et pro eas grammes d'investissement p our Balbala Nord DJ-FDH-68706-CS-QCBS / Re crutement d'un consultant po Participatory upgrading inve Quality And Cost- ur le suivi et contrôle des tra IDA / V0980 stments in selected urban ar Post Open - National 120,000.00 489,997.38 Completed 2018-07-16 2018-12-06 2018-08-06 2018-09-19 2019-02-12 2018-10-17 2019-03-13 2018-11-16 2019-04-30 2018-12-21 2019-05-16 2019-01-25 2019-08-08 2019-07-24 2021-01-07 Based Selection vaux de la voie de désenclav eas ement de Balbala ancien DJ-FDH-68736-CS-QCBS / Re Participatory upgrading inve crutement d'un consultant po Quality And Cost- Open - Internationa IDA / V0980 stments in selected urban ar Post 120,000.00 0.00 Canceled 2018-09-03 2018-09-24 2018-11-07 2018-12-05 2019-01-04 2019-02-08 2019-03-15 2024-03-13 ur des services d'ingénierie s Based Selection l eas ociale du projet à Balbala anc ien DJ-FDH-94102-CS-LCS / Recr Least Cost Selecti IDA / V0980 Project management Post Open - National 30,000.00 13,500.00 Completed 2019-01-08 2018-04-04 2019-01-29 2019-03-14 2018-06-11 2019-04-11 2018-07-18 2019-05-11 2018-08-08 2019-06-15 2018-08-29 2019-07-20 2019-03-31 2019-09-21 2019-06-13 utement d'un cabinet d'audit on externe DJ-FDH-125271-CS-QCBS / R Participatory upgrading inve ecrutement d'un consultant p Quality And Cost- IDA / 63380 stments in selected urban ar Post Open - National 200,000.00 223,400.00 Signed 2019-11-11 2021-06-22 2019-12-02 2020-01-15 2021-08-12 2020-02-12 2021-09-01 2020-02-26 2021-09-08 2020-04-01 2021-09-22 2020-05-06 2021-10-14 2020-11-02 our la supervision des travau Based Selection eas x de la zone de recasement DJ-FDH-127998-CS-LCS / Rec Least Cost Selecti rutement d'un cabinet pour l' IDA / 63380 Project management Post Open - National 50,000.00 14,655.00 Completed 2019-09-09 2019-11-26 2019-09-30 2019-11-13 2020-01-15 2019-12-11 2020-02-19 2020-01-10 2020-04-15 2020-02-14 2020-06-10 2020-03-20 2020-08-11 2020-09-16 2021-07-08 on audit des états financiers du projet DJ-FDH-126380-CS-QCBS / R Support to the elaboration of ecrutement d'un consultant p Quality And Cost- Open - Internationa IDA / 63380 the ZSP strategic framework Post 250,000.00 303,290.00 Completed 2019-11-04 2019-12-25 2019-11-25 2020-01-07 2020-01-08 2020-04-16 2020-02-05 2020-06-10 2020-03-06 2020-08-12 2020-04-10 2020-08-26 2020-05-15 2021-01-06 2021-01-10 2021-09-01 our l'élaboration d'une étude Based Selection l and investment plan pour la restructuration des p etits quartiers DJ-FDH-154476-CS-QCBS / R Support to the elaboration of ecrutement d'un consultant p Quality And Cost- Open - Internationa IDA / 63380 the ZSP strategic framework Post 150,000.00 161,750.00 Completed 2020-01-26 2020-01-22 2020-02-16 2020-03-31 2020-04-16 2020-04-28 2020-05-27 2020-05-28 2020-07-22 2020-07-02 2020-08-12 2020-08-06 2020-10-20 2020-08-27 2021-11-01 our l'étude de restructuration Based Selection l and investment plan et d'alignement du quartier T ora-Dora DJ-FDH-154517-CS-QCBS / R Support to the elaboration of ecrutement d'un consultant p Quality And Cost- Open - Internationa IDA / 63380 the ZSP strategic framework Post 100,000.00 158,197.57 Completed 2020-01-22 2020-01-22 2020-02-12 2020-03-27 2020-04-16 2020-04-24 2020-05-27 2020-05-24 2020-07-22 2020-06-28 2020-08-12 2020-08-02 2020-10-20 2021-01-29 2021-10-01 our l'étude de faisabilité du q Based Selection l and investment plan uartier de bâche à eau DJ-FDH-155166-CS-QCBS / R Participatory upgrading inve ecrutement d'un consultant Quality And Cost- Open - Internationa IDA / 63380 stments in selected urban ar Post 100,000.00 76,704.77 Completed 2020-04-13 2020-10-01 2020-05-04 2020-10-05 2020-06-17 2020-11-15 2020-07-15 2020-12-23 2020-07-29 2021-03-09 2020-08-26 2021-04-01 2020-09-30 2021-05-29 2021-01-28 2022-07-03 pour l'élaboration d'un PAR Based Selection l eas pour l'ensemble du quartier de Balbala Ancien DJ-FDH-155172-CS-QCBS / R Participatory upgrading inve ecrutement d'un consultant p Quality And Cost- Open - Internationa IDA / 63380 stments in selected urban ar Post 100,000.00 76,150.00 Signed 2020-04-13 2021-01-26 2020-05-04 2021-02-07 2020-06-17 2021-04-27 2020-07-15 2021-06-02 2020-07-29 2021-06-23 2020-08-26 2021-07-14 2020-09-30 2021-09-27 2021-01-28 our l'élaboration d'un EIES po Based Selection l eas ur l'ensemble du quartier de Balbala Ancien DJ-FDH-125272-CS-QCBS / E Participatory upgrading inve tudes techniques et supervisi Quality And Cost- Open - Internationa IDA / 63380 stments in selected urban ar Post 150,000.00 285,750.00 Terminated 2020-08-16 2020-08-25 2020-09-06 2020-09-02 2020-10-20 2020-10-13 2020-11-17 2020-11-18 2020-12-01 2020-12-23 2021-01-05 2021-01-06 2021-02-09 2021-02-15 2021-06-09 on des travaux de la restruct Based Selection l eas uration de Balbala Ancien DJ-FDH-126404-CS-QCBS / R ecrutement d'un consultant p Participatory upgrading inve Quality And Cost- our le développement d'un m IDA / 63380 stments in selected urban ar Post Open - National 51,000.00 0.00 Canceled 2019-11-04 2019-11-25 2019-12-24 2020-01-21 2020-01-22 2020-02-26 2020-04-01 2020-06-30 Based Selection écanisme de gestion de plain eas tes pour l'Ingénierie Sociale DJ-FDH-216884-CS-QCBS / E Support to the elaboration of Quality And Cost- Open - Internationa tude de restructuration et d'a IDA / 63380 the ZSP strategic framework Post 150,000.00 213,967.70 Signed 2021-02-10 2021-02-03 2021-03-03 2021-02-12 2021-04-16 2021-04-27 2021-05-14 2021-06-02 2021-06-13 2021-06-23 2021-07-18 2021-07-14 2021-08-22 2021-10-01 2022-05-15 Based Selection l lignement du quartier Djebel and investment plan DJ-FDH-216885-CS-QCBS / E Support to the elaboration of tude de restructuration et d'a Quality And Cost- Open - Internationa IDA / 63380 the ZSP strategic framework Post 150,000.00 259,167.60 Signed 2021-02-10 2021-02-03 2021-03-03 2021-02-12 2021-04-16 2021-04-27 2021-05-14 2021-06-02 2021-06-13 2021-06-23 2021-07-18 2021-07-14 2021-08-22 2021-09-02 2022-05-15 lignement de la zone de Djag Based Selection l and investment plan a-Bouldhouq(Quartier 7) DJ-FDH-216882-CS-QCBS / El Support to the elaboration of Quality And Cost- Open - Internationa aboration du plan de restruct IDA / 63380 the ZSP strategic framework Post 150,000.00 218,471.92 Signed 2021-02-10 2021-02-03 2021-03-03 2021-02-12 2021-04-16 2021-04-27 2021-05-14 2021-06-02 2021-06-13 2021-06-23 2021-07-18 2021-07-14 2021-08-22 2021-10-01 2022-06-18 Based Selection l uration du quartier d'Arhiba and investment plan DJ-FDH-216881-CS-QCBS / El Support to the elaboration of Quality And Cost- Open - Internationa aboration d'une étude de res IDA / 63380 the ZSP strategic framework Post 150,000.00 227,090.69 Signed 2021-02-10 2021-02-03 2021-03-03 2021-02-12 2021-04-16 2021-04-27 2021-05-14 2021-06-02 2021-06-13 2021-06-23 2021-07-18 2021-07-14 2021-08-22 2021-09-02 2022-07-18 Based Selection l tructuration de la zone de Vi and investment plan etnam DJ-FDH-216880-CS-QCBS / E Support to the elaboration of tude de marché du logement Quality And Cost- Open - Internationa IDA / 63380 the ZSP strategic framework Post 200,000.00 188,615.45 Signed 2021-02-10 2021-02-03 2021-03-03 2021-02-07 2021-04-16 2021-04-27 2021-05-14 2021-06-02 2021-06-13 2021-06-23 2021-07-18 2021-07-14 2021-08-22 2021-10-01 2022-02-18 et la promotion d'un habitat Based Selection l and investment plan abordable à Djibouti DJ-FDH-239884-CS-LCS / Rec rutement d'un cabinet en vu Least Cost Selecti IDA / 63380 Project management Post Open - National 30,000.00 12,285.36 Signed 2021-07-15 2021-11-09 2021-08-05 2021-09-18 2022-01-20 2021-10-16 2022-02-23 2021-11-15 2022-03-09 2021-12-20 2022-03-23 2022-01-24 2022-05-06 2024-01-24 e de l’audit comptable et fina on ncier exercices 2021 et 2022 DJ-FDH-266463-CS-QCBS / R ecrutement d’un consultant Support to the elaboration of pour l’élaboration de l’étude Quality And Cost- Open - Internationa IDA / D7590 the ZSP strategic framework Post 150,000.00 175,793.78 Signed 2021-11-01 2021-11-08 2021-11-22 2022-01-06 2022-01-05 2022-02-07 2022-02-02 2022-03-09 2022-03-04 2022-03-23 2022-04-08 2022-04-06 2022-05-13 2022-05-13 2022-10-10 de diagnostic participatif et l Based Selection l and investment plan a rédaction de plan d’action sur la mise en œuvre de la lo i nationale sur les refugies DJ-FDH-266451-CS-QCBS / S ervices de consultation d’un Support to the elaboration of Quality And Cost- Open - Internationa bureau d’études pour l’élabo IDA / D7590 the ZSP strategic framework Post 150,000.00 249,680.00 Signed 2021-10-20 2021-10-21 2021-11-10 2021-12-24 2021-12-29 2022-01-21 2022-02-02 2022-02-20 2022-02-23 2022-03-27 2022-03-16 2022-05-01 2022-05-09 2023-02-25 Based Selection l ration des plans de restructu and investment plan ration des villages d’Ali Adde h et Holl-Holl DJ-FDH-267022-CS-QCBS / E tudes techniques et supervisi Participatory upgrading inve Quality And Cost- Open - Internationa on des travaux de constructi IDA / 63380 stments in selected urban ar Post 150,000.00 349,400.00 Signed 2021-12-29 2022-01-13 2022-01-19 2022-03-04 2022-03-01 2022-04-01 2022-04-06 2022-05-01 2022-04-13 2022-06-05 2022-04-27 2022-07-10 2022-05-20 2023-01-06 Based Selection l on des équipements du quart eas ier 9 « Balbala ancien » Page 3 DJ-FDH-269624-CS-QCBS / R ecrutement d'un consultant p Participatory upgrading inve our la mise en place d’un mé Consultant Qualifi Open - Internationa Under Implement IDA / 63380 stments in selected urban ar Post 150,000.00 0.00 2022-04-13 2022-05-09 2022-05-04 2022-07-27 2022-06-17 2022-09-05 2022-07-17 2022-08-21 2022-11-27 canisme de micro-crédit en cation Selection l ation eas matériaux et préparation d’u n manuel des procédures op érationnelles DJ-FDH-267549-CS-QCBS / S upervision des travaux de co Participatory upgrading inve Quality And Cost- Open - Internationa nstruction des voiries de Balb IDA / 63380 stments in selected urban ar Post 150,000.00 170,000.00 Signed 2021-12-29 2022-02-25 2022-01-19 2022-03-04 2022-04-25 2022-04-15 2022-05-25 2022-05-15 2022-06-01 2022-06-19 2022-06-15 2022-07-24 2022-08-19 2023-01-25 Based Selection l ala Nord et des infrastructure eas s (Voirie, AEP, et électricité) de Balbala Ancien DJ-FDH-291720-CS-QCBS / E tudes techniques APS-APD-EI Participatory upgrading inve ES et DAO des travaux des re Quality And Cost- Open - Internationa IDA / 63380 stments in selected urban ar Post 150,000.00 144,000.00 Signed 2022-01-15 2021-10-26 2022-02-05 2022-03-21 2022-03-01 2022-05-02 2022-04-06 2022-06-01 2022-04-20 2022-07-06 2022-05-04 2022-08-10 2022-06-03 2023-02-08 structuration et mise en plac Based Selection l eas e des équipements et infrastr uctures dans le quartier de T ora Dora DJ-FDH-291738-CS-QCBS / E tudes techniques APS-APD-EI ES et DAO des travaux des re Participatory upgrading inve Quality And Cost- Open - Internationa structuration et mise en plac IDA / 63380 stments in selected urban ar Post 150,000.00 159,425.00 Signed 2022-01-15 2021-10-26 2022-02-05 2022-03-21 2022-03-01 2022-05-02 2022-04-06 2022-06-01 2022-04-13 2022-07-06 2022-04-27 2022-08-10 2022-05-20 2023-02-08 Based Selection l e des équipements et infrastr eas uctures dans les quartiers de Balbala T9, Balbala Q11, Qua rawil / Pompage et Harirad). DJ-FDH-291737-CS-QCBS / L’ élaboration du cadre financie Support to the elaboration of r, institutionnel, organisation Quality And Cost- Open - Internationa Under Implement IDA / D7590 the ZSP strategic framework Post 100,000.00 0.00 2022-03-06 2022-03-06 2022-03-27 2022-05-10 2022-05-05 2022-06-21 2022-06-08 2022-07-21 2022-06-23 2022-08-25 2022-07-13 2022-09-29 2023-03-28 nel et humain de la Société I Based Selection l ation and investment plan mmobilière et d’Aménageme nt Foncier de Djibouti (SIAF) DJ-FDH-291736-CS-QCBS / L’ Participatory upgrading inve élaboration d’un plan d’actio Quality And Cost- Open - Internationa Under Implement IDA / 63380 stments in selected urban ar Post 100,000.00 0.00 2022-04-06 2022-04-06 2022-04-27 2022-06-10 2022-06-02 2022-07-22 2022-07-13 2022-08-21 2022-07-20 2022-09-25 2022-08-02 2022-10-30 2023-01-28 n de réinstallation – PAR pour Based Selection l ation eas les quartiers de Balbala nord DJ-FDH-291716-CS-QCBS / L’ Support to the elaboration of Quality And Cost- Open - Internationa Under Implement élaboration d’un plan de mis IDA / D7590 the ZSP strategic framework Post 250,000.00 0.00 2022-03-06 2022-01-18 2022-03-27 2022-05-10 2022-05-26 2022-06-21 2022-07-06 2022-07-21 2022-08-17 2022-08-25 2022-08-31 2022-09-29 2023-02-26 Based Selection l ation e à niveau des anciens quarti and investment plan ers de Djibouti DJ-FDH-291718-CS-QCBS / E tude d’impact environnemen Participatory upgrading inve Quality And Cost- Open - Internationa Under Implement tal et social de restructuratio IDA / 63380 stments in selected urban ar Post 100,000.00 0.00 2022-03-06 2021-11-26 2022-03-27 2022-05-10 2022-06-11 2022-06-21 2022-07-20 2022-07-21 2022-08-02 2022-08-25 2022-08-24 2022-09-29 2022-12-28 Based Selection l ation n et d’alignement (EIES) des eas 4 quartiers de balbala nord DJ-FDH-272107-CS-QCBS / E Support to the elaboration of tudes urbaines et techniques Quality And Cost- Open - Internationa IDA / 63380 the ZSP strategic framework Post 200,000.00 345,428.00 Signed 2021-09-01 2021-09-13 2021-09-22 2021-11-05 2021-12-07 2021-12-17 2022-01-05 2022-01-16 2022-01-19 2022-02-20 2022-02-02 2022-03-27 2022-05-09 2022-09-23 des quartiers de Layableh-Mo Based Selection l and investment plan ustiquaire et WARABLEH II DJ-FDH-269606-CS-QCBS / E tude technique des travaux d Participatory upgrading inve e construction des 2 voies de Quality And Cost- Open - Internationa Under Implement IDA / 63380 stments in selected urban ar Post 150,000.00 0.00 2021-12-19 2022-04-04 2022-01-09 2022-02-22 2022-05-23 2022-04-05 2022-07-06 2022-05-05 2022-07-20 2022-06-09 2022-08-02 2022-07-14 2023-01-10 désenclavement de Balbala Based Selection l ation eas Nord et des infrastructures ( Voirie, AEP, et électricité) de Balbala Ancien DJ-FDH-126441-CS-QCBS / R ecrutement d'un consultant p Support to the elaboration of Quality And Cost- Open - Internationa Under Implement our la mise en place d’une ba IDA / 63380 the ZSP strategic framework Post 250,000.00 0.00 2022-07-20 2022-07-20 2022-08-10 2022-08-21 2022-09-23 2022-09-26 2022-11-04 2022-10-27 2022-11-18 2022-11-09 2022-12-23 2022-12-14 2023-01-27 2023-10-24 Based Selection l ation se de données des ménages and investment plan de la zone de Balbala nord DJ-FDH-318103-CS-QCBS / R Support to the elaboration of ecrutement d'un bureau d’ét Quality And Cost- Open - Internationa Under Implement IDA / 63380 the ZSP strategic framework Post 150,000.00 0.00 2022-09-26 2022-09-28 2022-10-17 2022-10-20 2022-11-14 2022-11-15 2022-12-29 2022-12-14 2023-01-12 2023-01-11 2023-02-16 2023-03-23 2023-09-19 udes pour l’étude de restruct Based Selection l ation and investment plan uration et d’alignement du q uartier Bâche-à-eau DJ-FDH-341171-CS-QCBS / EI Participatory upgrading inve Quality And Cost- Open - Internationa Under Implement IDA / 63380 Post 100,000.00 0.00 2023-02-08 2023-02-01 2023-03-01 2023-04-14 2023-05-14 2023-05-28 2023-07-02 2023-08-06 2023-11-04 ES pour les 2 voies de Balbal stments in selected urban ar Based Selection l ation a Nord eas INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual DJ-FDH-34539-CS-INDV / Rec Support to the elaboration of Individual Consult Under Implement rutement d'un expert en app IDA / V0980 the ZSP strategic framework Prior Open 195,000.00 0.00 2017-10-29 2019-07-26 2017-12-17 2017-12-06 2018-01-07 2019-07-08 2018-02-11 2019-02-11 ant Selection ation ui à l'unité de gestion de l'av and investment plan ance DJ-FDH-34597-CS-CDS / Recr Support to the elaboration of utement d'un consultant pou IDA / V0980 the ZSP strategic framework Prior Direct Selection Direct 210,000.00 184,345.00 Completed 2017-10-30 2017-11-09 2017-10-29 2018-01-13 2018-01-29 2018-07-12 2018-09-30 r la stratégie de resorption d and investment plan es quartiers DJ-FDH-34616-CS-INDV / Rec Individual Consult rutement d'un consultant en IDA / V0980 Prior Open 30,000.00 0.00 Canceled 2017-11-12 2017-12-31 2018-01-21 2018-02-25 2019-02-25 ant Selection passation des marchés DJ-FDH-34623-CS-INDV / Rec Support to the elaboration of Individual Consult rutement d'un consultant po IDA / V0980 the ZSP strategic framework Post Open 5,000.00 9,200.00 Completed 2017-11-15 2017-11-20 2018-01-03 2017-12-26 2018-01-24 2018-01-09 2018-02-28 2018-01-15 2018-03-30 2018-02-23 ant Selection ur l'élaboration d'un plan de and investment plan communication DJ-FDH-40539-CS-CDS / Recr Participatory upgrading inve utement d'un consultant pou IDA / V0980 stments in selected urban ar Post Direct Selection Direct 40,000.00 28,100.00 Completed 2017-12-20 2017-12-30 2018-03-05 2018-02-07 2018-04-04 2018-03-20 r l'actualisations des études t eas echniques d'investissements prioritaires DJ-FDH-49621-CS-INDV / Rec rutement d'un expert dans le Support to the elaboration of cadre d'une étude d'évaluati Individual Consult IDA / V0980 the ZSP strategic framework Post Open 40,000.00 57,189.50 Completed 2017-12-04 2017-12-20 2018-01-22 2018-01-14 2018-02-12 2018-01-25 2018-03-19 2018-02-26 2018-06-17 2018-03-26 on des impacts environneme ant Selection and investment plan ntaux et sociaux (EIES) et de la gestion environnemental ( CGES) Page 4 DJ-FDH-51532-CS-INDV / Rec rutement d'un expert dans le Support to the elaboration of Individual Consult cadre de politique de réinstal IDA / V0980 the ZSP strategic framework Post Open 30,000.00 91,540.00 Completed 2017-12-04 2017-12-20 2018-01-22 2018-01-14 2018-02-12 2018-01-30 2018-03-19 2018-02-26 2018-04-23 2018-03-26 ant Selection lation des populations (CPR) and investment plan et dans le plan de réinstallati on des populations (PAR) DJ-FDH-59799-CS-INDV / Rec Individual Consult rutement d'un consultant cha IDA / V0980 Project management Post Open 45,000.00 31,740.00 Signed 2018-04-18 2018-04-18 2018-06-06 2018-06-07 2018-06-27 2018-06-12 2018-08-01 2018-07-01 2019-08-01 ant Selection rgé de la communication DJ-FDH-68703-CS-INDV / Rec rutement d'un consultant po Individual Consult ur la préparation du manuel IDA / V0980 Project management Post Open 30,000.00 28,750.00 Completed 2018-07-08 2018-08-26 2018-05-07 2018-09-16 2018-06-04 2018-10-21 2018-06-06 2018-11-15 2018-07-10 ant Selection de procédures du projet inté gré de résorption de bidonvill es DJ-FDH-68731-CS-INDV / Rec Individual Consult rutement d'un spécialiste en IDA / V0980 Project management Post Open 120,000.00 18,000.00 Completed 2018-07-31 2018-11-12 2018-09-18 2018-11-19 2018-10-09 2018-12-02 2018-11-13 2018-12-18 2019-11-13 2019-09-18 ant Selection sauvegarde DJ-FDH-127350-CS-INDV / Re Individual Consult crutement d'un assistant co IDA / 63380 Project management Post Open 20,000.00 53,486.88 Terminated 2019-08-18 2019-04-25 2019-09-13 2019-06-13 2019-09-27 2019-06-20 2019-11-01 2019-07-07 2020-10-31 ant Selection mptable pour appuyer le cha rgé fiduciaire DJ-FDH-126386-CS-CDS / Re Support to the elaboration of crutement d'un consultant po IDA / 63380 the ZSP strategic framework Post Direct Selection Direct 30,000.00 28,035.00 Signed 2019-08-18 2019-07-17 2019-08-28 2019-07-28 2019-10-17 2019-08-29 2019-12-16 ur une enquête socio-écono and investment plan mique de Balbala Ancien DJ-FDH-126407-CS-INDV / Re crutement d'un consultant po Participatory upgrading inve Individual Consult ur le recensement de structu IDA / 63380 stments in selected urban ar Post Open 40,000.00 19,910.00 Signed 2019-11-04 2021-02-23 2019-12-23 2021-04-15 2020-01-13 2021-04-15 2020-02-17 2021-04-16 2020-05-17 ant Selection res associatives et communa eas utaires existantes pour l'Ingé nierie Sociale DJ-FDH-127773-CS-INDV / Re Participatory upgrading inve crutement d'un animateur co Individual Consult IDA / 63380 stments in selected urban ar Post Direct 27,000.00 22,918.14 Signed 2019-11-04 2019-10-01 2019-11-14 2019-11-03 2019-11-21 2019-11-20 2019-12-26 2019-12-02 2020-06-23 mmunautaire pour la zone 4 ant Selection eas pour la durée du projet (Ingé nierie Sociale) DJ-FDH-127772-CS-INDV / Re Participatory upgrading inve crutement d'un animateur co Individual Consult IDA / 63380 stments in selected urban ar Post Direct 27,000.00 22,918.14 Signed 2019-11-04 2019-10-01 2019-11-14 2020-01-03 2019-11-21 2019-11-20 2019-12-26 2019-12-02 2020-12-25 mmunautaire pour la zone 3 ant Selection eas pour la durée du projet (Ingé nierie Sociale) DJ-FDH-127771-CS-INDV / Re Participatory upgrading inve crutement d'un animateur co Individual Consult IDA / 63380 stments in selected urban ar Post Direct 27,000.00 22,918.14 Signed 2019-11-04 2019-10-01 2019-11-14 2019-11-03 2019-11-21 2019-11-20 2019-12-26 2019-12-01 2020-12-25 mmunautaire pour la zone 2 ant Selection eas pour la durée du projet (Ingé nierie Sociale) DJ-FDH-127770-CS-INDV / Re Participatory upgrading inve crutement d'un animateur co Individual Consult IDA / 63380 stments in selected urban ar Post Direct 27,000.00 22,918.14 Signed 2019-11-04 2019-10-01 2019-11-14 2019-11-03 2019-11-21 2019-11-20 2019-12-26 2019-12-02 2020-12-25 mmunautaire pour la zone 1 ant Selection eas pour la durée du projet (Ingé nierie Sociale) DJ-FDH-127774-CS-INDV / Re Participatory upgrading inve crutement d'un animateur co Individual Consult IDA / 63380 stments in selected urban ar Post Direct 27,000.00 22,918.14 Signed 2019-11-04 2019-10-01 2019-11-14 2019-11-03 2019-11-21 2019-11-20 2019-12-26 2019-12-02 2020-06-23 mmunautaire pour la zone 5 ant Selection eas pour la durée du projet (Ingé nierie Sociale) DJ-FDH-148119-CS-INDV / Re Individual Consult crutement d'un expert en ap IDA / 63380 Project management Post Open 185,000.00 234,230.00 Completed 2019-12-02 2019-12-02 2020-01-20 2020-06-15 2020-02-10 2020-06-30 2020-03-16 2020-08-14 2021-03-16 2022-03-01 ant Selection pui de restructuration DJ-FDH-154472-CS-INDV / Re crutement d'un consultant po Individual Consult IDA / 63380 Project management Post Direct 5,000.00 3,229.88 Completed 2020-01-19 2019-12-17 2020-01-29 2019-12-29 2020-02-19 2019-12-29 2020-03-25 2019-12-31 2020-05-04 2020-02-11 ur la mise à jour des docume ant Selection nts de sauvegarde (CGES et CPR) DJ-FDH-155179-CS-INDV / Re Participatory upgrading inve crutement d'un consultant po Individual Consult IDA / 63380 stments in selected urban ar Post Open 50,000.00 36,225.00 Completed 2020-04-13 2020-02-11 2020-06-01 2020-06-11 2020-06-22 2020-06-25 2020-07-27 2020-07-15 2020-09-10 2020-10-15 ur l'élaboration d'un EIES pou ant Selection eas r le site d'accueil de 110 Ha DJ-FDH-154518-CS-CDS / Co Support to the elaboration of ntrat entre l'ARULoS et la RT IDA / 63380 the ZSP strategic framework Post Direct Selection Direct 30,000.00 25,501.90 Signed 2020-04-01 2020-05-11 2020-04-11 2020-05-17 2020-06-15 2020-06-02 2021-06-15 D pour la communication sur and investment plan le PIRB DJ-FDH-171635-CS-CDS / Re crutement d'un consultant po Support to the elaboration of ur les études techniques d'un IDA / 63380 the ZSP strategic framework Post Direct Selection Direct 260,000.00 305,275.74 Completed 2020-04-30 2020-05-03 2020-05-10 2020-05-27 2020-06-29 2020-08-11 2021-02-01 2021-08-11 site de 100 Ha dans la zone d and investment plan e prévention et de relogeme nt à Balbala Sud DJ-FDH-202546-CS-INDV / Re crutement d'un consultant po Individual Consult IDA / 63380 Project management Post Direct 25,000.00 22,960.73 Completed 2020-11-02 2020-10-14 2020-11-12 2020-10-20 2020-11-17 2020-10-21 2020-11-24 2020-10-26 2020-12-14 2020-11-12 ur la mise à jour des docume ant Selection nts de sauvegarde (CGES et CPR) DJ-FDH-209731-CS-INDV / Él aboration d'un PAR pour les Emergency response to COV Individual Consult IDA / 63380 Post Open 50,000.00 9,350.00 Signed 2021-01-03 2021-05-08 2021-02-21 2021-05-23 2021-03-14 2021-05-26 2021-04-18 2021-07-14 2021-06-17 ménages installés dans le lit ID-19 and to the floods ant Selection d'oued Langobaleyeh DJ-FDH-236686-CS-INDV / Re Individual Consult crutement d'un spécialiste e IDA / D7590 Project management Post Open 50,000.00 25,920.00 Signed 2021-06-15 2021-06-14 2021-08-03 2021-08-05 2021-08-24 2021-09-01 2021-09-28 2021-09-20 2022-09-28 ant Selection n sauvegarde environnement al DJ-FDH-127351-NC-RFQ / Act Support to the elaboration of ivités de communication pou IDA / 63380 the ZSP strategic framework Post Direct Selection Direct 20,000.00 0.00 Canceled 2019-11-03 2019-11-13 2020-01-17 2020-07-15 r préparer un reportage vidé and investment plan o sur le PZB DJ-FDH-239883-CS-INDV / Re Individual Consult IDA / 63380 Project management Post Limited 30,000.00 17,828.96 Signed 2021-06-01 2021-06-01 2021-06-06 2021-05-26 2021-06-27 2021-05-27 2021-08-01 2021-05-31 2022-08-01 crutement d'un assistant co ant Selection mptable DJ-FDH-236692-CS-INDV / Re Individual Consult crutement d'un spécialiste e IDA / D7590 Project management Post Open 50,000.00 33,366.11 Signed 2021-07-12 2021-06-14 2021-08-30 2021-08-05 2021-09-20 2021-09-13 2021-10-25 2021-10-01 2022-10-25 ant Selection n suivi-évaluation Page 5 DJ-FDH-266863-CS-CDS / Re crutement d'un consultant po IDA / D7590 Project management Post Direct Selection Direct 20,000.00 17,952.00 Signed 2021-07-01 2021-07-03 2021-07-11 2021-07-11 2021-08-29 2021-08-23 2021-11-27 ur la mise à jour du manuel d es procédures du PIRB DJ-FDH-265961-CS-INDV / Se rvices de consultation local p Participatory upgrading inve Individual Consult our l’élaboration d’une étude IDA / 63380 stments in selected urban ar Post Open 20,000.00 19,679.83 Signed 2021-10-15 2021-10-17 2021-12-03 2021-12-28 2021-12-24 2022-01-12 2022-01-28 2022-01-24 2022-04-28 ant Selection de profilage des jeunes du qu eas artier 9 « Balbala Ancien »-M ASS DJ-FDH-266453-CS-INDV / Re Participatory upgrading inve crutement d'un consultant po Individual Consult IDA / 63380 stments in selected urban ar Post Open 20,000.00 21,824.00 Signed 2021-08-01 2021-08-02 2021-08-26 2021-09-08 2021-08-31 2021-09-16 2021-10-05 2021-09-20 2022-02-02 ur la supervision des travaux ant Selection eas d'ouvrage hydraulique de Na ssib DJ-FDH-265965-CS-CDS / Etu des techniques APS-APD-EIES et DAO des travaux des restr Participatory upgrading inve ucturation et mise en place d IDA / 63380 stments in selected urban ar Post Direct Selection Direct 150,000.00 0.00 Canceled 2021-10-20 2021-10-30 2022-01-03 2022-07-02 es équipements et infrastruct eas ures dans les quartiers de Ba lbala T9, Balbala Q11, Quara wil / Pompage et Harirad). DJ-FDH-266452-CS-CDS / Etu des techniques APS-APD-EIES Participatory upgrading inve et DAO des travaux des restr IDA / 63380 stments in selected urban ar Post Direct Selection Direct 150,000.00 0.00 Canceled 2021-10-21 2021-10-31 2021-12-14 2022-06-12 ucturation et mise en place d eas es équipements et infrastruct ures dans le quartier de Tora Dora DJ-FDH-236676-CS-INDV / Re Individual Consult crutement d'un spécialiste e IDA / D7590 Project management Post Open 50,000.00 0.00 Canceled 2021-06-15 2021-06-14 2021-08-03 2021-08-24 2021-09-28 2022-09-28 ant Selection n passation de marché DJ-FDH-126351-CS-INDV / Re Support to the elaboration of crutement d'un consultant po Individual Consult IDA / 63380 the ZSP strategic framework Post Direct 30,000.00 0.00 Canceled 2020-02-02 2020-02-12 2020-03-04 2020-04-08 2020-05-23 ur appuyer le gouvernement ant Selection and investment plan à organiser la conférence des bailleurs DJ-FDH-297935-CS-INDV / EX Support to the elaboration of PERT D’APPUI A LA DIRECTIO Individual Consult Under Implement IDA / D7590 the ZSP strategic framework Post Open 150,000.00 0.00 2022-06-12 2022-05-29 2022-08-12 2022-10-31 2022-09-02 2023-01-18 2022-10-07 2023-10-07 N DES DOMAINES ET DE LA C ant Selection ation and investment plan ONSERVATION FONCIERE DJ-FDH-305006-CS-INDV / Re crutement d’un consultant n Support to the elaboration of ational pour la rédaction du Individual Consult Under Implement IDA / D7590 the ZSP strategic framework Post Open - National 20,000.00 0.00 2022-07-24 2022-07-25 2022-09-11 2022-10-06 2022-10-02 2022-12-15 2022-11-06 2023-03-06 manuel des procédures et de ant Selection ation and investment plan s opérations aux activités ex écutées par le MASS dans le cadre du PIRB DJ-FDH-305011-CS-INDV / Re crutement d’un consultant in Support to the elaboration of Individual Consult Open - Internationa Under Implement ternational du volet l’ingénie IDA / D7590 the ZSP strategic framework Post 60,000.00 0.00 2022-07-24 2022-07-25 2022-09-23 2022-10-14 2022-11-18 2023-05-17 ant Selection l ation rie sociale relative aux activit and investment plan és exécutées par le MASS da ns le cadre du PIRB DJ-FDH-345218-CS-CDS / Re crutement d'un spécialiste e IDA / D7590 Project management Post Direct Selection Direct - National 26,000.00 0.00 Canceled 2023-02-23 2023-03-05 2023-04-23 2024-04-22 n sauvegarde environnement al DJ-FDH-353343-CS-INDV / RE CRUTEMENT D’UN CONSULT Support to the elaboration of Individual Consult Open - Internationa Under Implement ANT D’APPUI AUPRES DE L’O IDA / D7590 the ZSP strategic framework Post 72,000.00 0.00 2023-03-28 2023-03-07 2023-05-16 2023-06-06 2023-07-11 2024-07-10 ant Selection l ation FFICE NATIONAL D’ASSISTAN and investment plan CE AUPRES DES REFUGIES ET SINISTRES DJ-FDH-358947-CS-INDV / Re Support to the elaboration of Individual Consult Under Implement crutement d'un animateur so IDA / D7590 the ZSP strategic framework Post Direct - National 22,250.00 0.00 2022-12-05 2022-12-05 2022-12-15 2023-01-05 2023-02-09 2023-08-08 ant Selection ation cial pour la MASS- Zone 1 and investment plan DJ-FDH-358958-CS-INDV / Re Support to the elaboration of Individual Consult Under Implement crutement d'un animateur so IDA / D7590 the ZSP strategic framework Post Direct - National 22,250.00 0.00 2022-12-05 2022-12-05 2022-12-15 2023-01-05 2023-02-09 2025-11-10 ant Selection ation cial pour la MASS- Zone 2 and investment plan DJ-FDH-358950-CS-INDV / Re Support to the elaboration of Individual Consult Under Implement crutement d'un animateur so IDA / D7590 the ZSP strategic framework Post Direct - National 22,250.00 0.00 2022-12-05 2022-12-05 2022-12-15 2023-01-05 2023-02-09 2025-11-10 ant Selection ation cial pour la MASS- Zone 3 and investment plan DJ-FDH-358953-CS-INDV / Re Support to the elaboration of Individual Consult Under Implement crutement d'un animateur so IDA / D7590 the ZSP strategic framework Post Direct - National 22,250.00 0.00 2022-12-05 2022-12-05 2022-12-15 2023-01-05 2023-02-09 2025-11-10 ant Selection ation cial pour la MASS- Zone 4 and investment plan DJ-FDH-358940-CS-INDV / Re Support to the elaboration of Individual Consult Under Implement crutement d'un animateur so IDA / D7590 the ZSP strategic framework Post Direct - National 22,250.00 0.00 2022-12-05 2022-12-05 2022-12-15 2023-01-05 2023-02-09 2025-11-10 ant Selection ation cial pour la MASS- Zone 5 and investment plan DJ-FDH-353478-CS-INDV / Re Individual Consult IDA / 63380 Project management Post Open - National 50,000.00 0.00 Under Review 2021-12-05 2021-12-07 2022-01-23 2022-02-13 2022-03-20 2023-03-20 crutement d'un auditeur inte ant Selection rne Page 6 Revised Project Procurement Strategy for Development (PPSD) October 17, 2021 Lao PDR Covid-19 Response Project AF Department of Planning and Cooperation Ministry of Health Page 0 Table of Contents 1. Project Overview .............................................................................................2 1.1. Scope of Project ........................................................................................2 1.2. Major Procurement Activities ....................................................................2 2. Overview of Marketplace .................................................................................3 3. Procurement Risk Analysis ..............................................................................3 4. Procurement Objective ....................................................................................4 4.1. General Procurement Objectives...............................................................4 4.2. Specific Procurement Objectives...............................................................5 5. Recommended Procurement Arrangements for the Project ............................5 5.1. Procurement Approach..............................................................................5 For Goods ........................................................................................................5 For Works ........................................................................................................6 For Consultant services ...................................................................................6 6. Summary of PPSD to be inform the Bank’s Preparation of the PAD.................6 7. Procurement Plan ............................................................................................6 Page 1 1. Project Overview Country: Lao People’s Democratic Republic Full Project Lao PDR Covid-19 Response Project Additional Financing Name: Total Finance US$ 33 million, in which: ($): - IDA loan 6606 US$ 18 million - IDA loan 6946 US$10 million - HEPR Trust Funds no. B5890 US$ 3 million - HEPR Trust Fund no. B5891 US$2 million Project Number: P173817 and P175771 Implementing Ministry of Health, Department of Planning and Agency Corporation The project development objective (PDO) is to respond to Summary of the COVID-19 outbreak and strengthen national systems Project for public health emergency preparedness in Lao PDR. Development Objectives 1.1. Scope of Project The AF would support the costs of expanding activities of the Lao PDR COVID-19 Response Project (P173817 and P175771) under the COVID-19 Strategic Preparedness and Response Program (SPRP) using the Multiphase Programmatic Approach (MPA), approved by the Board on April 2, 2020, and the vaccines AF to the SPRP approved on April 6, 2020, and the vaccines AF to the SPRP approved on October 13, 20201. The primary objectives of the AF are to enable affordable and equitable access to COVID-19 vaccines and help ensure effective vaccine deployment in Lao PDR through vaccination system strengthening, and to further strengthen preparedness and response activities under the parent project. The Lao PDR COVID- 19 Response Project in an amount of US$ 18 million IDA – was approved on April 2, 2020 prepared under the SPRP. The additional financing of IDA US$10 million loan, IDA of US$3 million grant for Covid-19 vaccine deployment, and US$ 2 million to Strengthen Health Facility and Lifeline Infrastructure for HEPR. This AF is being provided mainly to assist the safe and effective deployment of vaccines in Lao PDR. 1.2. Major Procurement Activities The AF financing will be predominantly allocated to vaccine deployment (51.6% of AF) and vaccine procurement (33.3% of the AF). The AF will also include support staff for the project operation, and monitoring. It also comprises technical assistant of the medical waste management, water treatment, quality and safety of isolation facilities and health facilities. 1 The Bank approved a US$12 billion WBG Fast Track COVID-19 Facility (FTCF or “the Facility”) to assist IBRD and IDA countries in addressing the global pandemic and its impacts. Of this amount, US$6 billion came from IBRD/IDA (“the Bank”) and US$6 billion from the International Finance Corporation (IFC). The IFC subsequently increased its contribution to US$8 billion, bringing the FTCF total to US$14 billion. The Additional Financing of US$12 billion (IBRD/IDA) was approved on October 13, 2020 to support the purchase and deployment of vaccines as well as strengthening the related immunization and health care delivery system. Page 2 Procurement methods shall be used under the AF are Direct Selection, and Request for Quotations. 2. Overview of Marketplace Experience from the parent project shows that the largest packages were goods and most bidders were local and there was no interest from foreign bidders because of the country lockdown due to the COVID crisis. However, under the AF, the largest contract will be the procurement of the COVID vaccine, which will be not available at the suppliers in the country. The procurement of vaccines can possibly be done in ways such as a bilateral contract between the government, procuring directly from manufacturers, procuring through cost-sharing of COVAX facility by contracting with UNICEF who has the expertise in procuring vaccine and vaccine logistic management. Most of the key options were to be procured by using the Direct Selection Method to shorten the time and process of procurement in order to respond to urgency. 3. Procurement Risk Analysis The main procurement under the AF devoted to the procurement of Covid-19 vaccine. The funding goes to this procurement item as high as 5 million. Initially, the decision on the vaccine type to be procured is Johnson and Johnson, with potentially arranged through cost-sharing of the Covax facility. With such decision imposes, it must be taken into account the risk of the vaccine supply doses will not being offered to the Government of Laos. In addition, there is the possibility of the government potentially encountering delayed delivery given the limited number of vaccine suppliers in the marketplace which can affect the national vaccine deployment plan. Besides, there is the need to pay attention to the arrangement of procurement, logistic arrangement, timeline of vaccine delivery as well as the efficiency and economical choice of the vaccine supplier in terms financial spending. Nevertheless, any of the vaccine types that has passed WHO EUL is technically acceptable under this WB financing. From the above analysis, procurement risk should be manageable. Key risks identified and proposed risk mitigation measures are shown in Table 1 below. Table 1 – Procurement Related Risks and Mitigation Measures Risk Description Risk Description of Mitigation Risk Rating Owner Limited experience of Moderate (i) DPC staff and the Local Consultant will World Bank staff in the DPC and be provided with procurement training and DPC the Local Consultant initially by the World Bank with WB new regulations Delays in the Substanti (i) assist other departments in preparing DPC procurement process al technical specifications; (ii) Procurement monitoring using STEP; World Bank and DPC Page 3 Risk Description Risk Description of Mitigation Risk Rating Owner (iii) development of the procurement DPC tracking system and share with the Bank weekly. (iv) request for setting procurement DPC thresholds for goods and services that can be delegated to the MOH’s procurement committee (v) Closer coordination between World Bank Implementing Departments and IDA, and DPC and supervisions and follow up by IDA. Governance risks Moderate (i) Enhanced disclosure of procurement DPC associated with information, including publication of the conflict of interest, annual procurement plan and a fraud and corruption quarterly summary of the contract award information for all procurement packages on MoH’ s website and in newspapers. (ii) Require staff involved in procurement DPC to declare their interest and sign a declaration form (iii) Monitoring and reporting on the DPC implementation of actions Point 2 (i) to (v) and Point 3 (i) to (iii) for strengthening transparency and procurement training for the project. Limitation of value for Low (i) Due diligence by both World Bank and World Bank, money and Ministry of Health prior to the extension MoH transparency in of contracts extension of the existing contracts A limited number of Moderate (i) Careful procurement planning and DPC qualified consultants scheduling, preparing TOR, REOI and submitted proposals request for proposals advanced as much as possible, (ii) Widely advertise, post RFB and REOI on the ministry’s website, local newspapers and at the same time inform the known qualified consultants directly (iii) Allow more time for the consultant to prepare their proposals Limited experience of High (i) DPC and MOH officers should closely DPC MOH staff in the consult the National Taskforce procurement of Committee for COVID-19 prevention COVID-19 vaccine and control regarding the purchase of the vaccine. Page 4 Risk Description Risk Description of Mitigation Risk Rating Owner (ii) Closer coordination between Implementing Departments under MOH, IDA and UNICEF in purchasing vaccine. 4. Procurement Objective 4.1. General Procurement Objectives The main procurement objectives for the project in the selection of contractors, suppliers and consultants for the supply of works, goods and equipment and consultancy services are: i) Obtain value for money in the extension of existing contracts to cover Project financing ii) Greater transparency in the selection process for all packages in a timely manner for contractors, suppliers and consultants that have sufficient capacities and qualifications to successfully execute works, supply of goods and equipment and perform consultancy services as required; iii) Timely acquisition of goods and services (efficiency) to support the delivery of services specifically the attainment of the Universal Health coverage 4.2. Specific Procurement Objectives The specific procurement objectives under the projects are: (i) Effectively manage the procurement process and arrangement in order to get the medical supplies and Covid-19 vaccine in timeliness of need; (ii) Efficiently utilize the fund available by knowing the availability of vaccine stock in the country and the type of vaccine that is going to be needing. Timely procure medical equipment supplies and COVID-19 vaccine. (iii) Ensure timely supply and availability of equipment and supplies for logistics of vaccine distribution. 5. Recommended Procurement Arrangements for the Project Procurement under the AF will be carried out in accordance with the World Bank’s Procurement Regulations for IPF Borrowers for Goods, Works, Non-Consulting and Consulting Services, dated November 2020. As with the parent project, the AF will be subject to the World Bank’s Anticorruption Guidelines, dated October 15, 2006, revised in January 2011, and as of July 1, 2016. The Project will use the Systematic Tracking of Exchanges in Procurement (STEP) to plan, record and track procurement transactions. The major planned procurement under this AF will include: (i) additional capacity support of national, subnational and on site cold chain management; including equipment and supplies of cold rooms, vaccine containers, vaccine carriers, ice lined refrigerators (ILR) and transporting vehicles including refrigerator (temperature Page 5 controlled vehicle) this is to support the logistic arrangement of vaccines and ensuring that vaccines will be delivered to the vaccination site safely with proven control of the quality; (ii) technical assistance for production of mass media and communication campaigns including procuring camcorders and computers for production of media; ; (iii) supplies of Covid-19 Vaccine and vaccination support equipment. It will also include consultancy and non-consultant services such as (iv) works to improve isolation facilities in the 3 southern provinces; waste management and quality and safety of isolation facilities. The current demand for COVID-19 vaccines exceeds the supply in the market which makes it more difficult for client countries to negotiate terms and conditions. Procurement of vaccines will therefore follow Direct Selection from (i) purchase through COVAX (specify whether AMC or self-financing) or (ii) direct purchase from manufacturers. Contracts for vaccines purchase financed by the Bank will be subject to the Bank’s technical prior review irrespective of value and procurement approach. Options considered under the project include, among others, (i) streamlined competitive procedures with shorter bidding time, (ii) use of framework agreements including existing ones, (iii) procurement from UN Agencies enabled and expedited by Bank procedures and standard agreements, (iv) increased thresholds for Requests for Quotations and national procurement, and (v) Hands-on Expanded Implementation Support (HEIS). 5.1. Procurement Approach Procurement arrangements are defined based on the current context and the market analysis described above. For Goods Based on the analysis in the above sections, there will be 20 goods packages to be procured (14 packages under Initial Financing-IF and 6 packages under AF). The amount is estimated at US$ 20.3 million. 6 packages under IF had been completed by applying RFQ methods, while AF packages are ongoing using the Direct Selection market approach. The largest goods package is the procurement of COVID-19 vaccine, with the amount of US$ 5. million. This is expected to be directly purchased with potentially arranged through cost-sharing of the Covax facility, instead of through direct purchase Sinopharm (by using the bilateral negotiation) as mentioned in the initial PPSD. Furthermore, goods packages including Computer and Camcorder, Covid-19 Waste Management Equipment, Equipment for vaccine cold chain container and vehicle for vaccine delivery will purchased through Direct Selection method. For Works There is a total of 5 works packages, four under the IF and another under AF. Under the IF only one Improvement of isolation facilities would be procured through RFQ method. However, due to the pandemic situation and urgent requirements, there will be additional 4 works packages including 1 Improvement/renovation of the Quarantine facility for Champassak provinces, 3 Construction of isolation and lab facilities for Champassak, Sekong and Attapeu Provinces and Infectious Waste Disposal. All those works contracts will be procured using the DS method. Page 6 For Consultant services 14 Procurement for Consulting Services packages is foreseen involving of 11 packages under IF and 3 packages under AF. Most of the packages will be done through DS approaches. For detail please see procurement plan in below section (section 7) 6. Summary of PPSD to be inform the Bank’s Preparation of the PAD The procurement will be carried out in accordance with the World Bank Procurement Regulations for Borrowers under Investment Project Financing (IPF) dated July 1, 2016, revised November 2020 and per the provisions stipulated in the Financing Agreement. Since the RFQ method will be used for the procurement of some goods packages as the government standard Harmonized Bidding Documents and Request for Quotations for goods shall be applied. Most of the works and consulting services shall be conducted through a Direct Selection method, which will be completed much faster than other competitive approaches to support the emergency response project. The Covid-19 Procurement Committee of the MOH as per decree no 025/MOH dated 13 April 2020 will support some of the procurement packages. New procurable activities will include small packages of goods and consulting services. The procurement approach and methods of each package are shown in Procurement plan (section 7) below. 7. Procurement Plan Based on the PPSD a procurement plan for the project has been developed with a total of 40 packages including 20 goods, 6 works and 14 consulting services packages. The detailed procurement plan is available as a separate project document, which will be updated at any time as needed to reflect the current status of the implementation of each package or to add new packages as needed. PROCUREMENT PLAN Project Name: Lao PDR COVID-19 Response Project and AF (P173817 and P175771) Project Implementation Agency: Department of Planning and Cooperation, Ministry of Health Date of the Procurement Plan: Oct 17, 2021 Period covered by this Procurement Plan: Until December 31, 2023 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. Page 7 This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the Public Procurement Law and the Instruction on Implementation Public Procurement Law, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. a) The request for bids/request for proposals document shall require that bidders/proposers submitting bids/proposals present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, Bank Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights; b) Information related to award of contract including reasons for rejection of unsuccessful bidders shall be published on the implementing agency websites and/or newspaper of wide circulation. c) All complaints on procurement related matters including complaints arising from procurement under Bank financed Projects whilst using National Procurement Procedures shall be dealt with in accordance with Article 46 of the Public Procurement Law. Borrower shall put in place an effective complaints review mechanism for dealing with procurement related complaints, and shall disclose the details in all the bidding documents. All complaints shall be recorded by the Borrower in the appropriate tracking and monitoring system, as agreed between the Bank and the Borrower. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. Not Applicable Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables. Not Applicable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: is applicable for those contracts identified in the Procurement Plan tables; Page 8 Works: is applicable for those contracts identified in the Procurement Plan tables Other Relevant Procurement Information. I. Works and Goods and Non-Consultant Services 1.1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Annex II of the Procurement Regulations: Procurement Method Prior Review Thresholds Thresholds Category Applicable Applicable thresholds Remarks thresholds (in Remarks (in US$) US$) Works Request for None None quotations Direct Selection No threshold; meet None Specified in the - requirements of procurement regulations 7.13- plan table. 7.15 Goods and Non-Consulting Services Request for bids None None Request for None None quotations Direct Selection None No threshold; meet None requirements of regulations 7.13- 7.15 Procurement None No threshold; meet None from UN requirements of agencies regulations 6.47 and (Goods) 6.48 1.2 Procurement packages for Works, Goods and Non-Consulting Services (prior and post reviews) with method and Time Schedule Ref. Contract Estimated Procureme Revie Expect Comments No. (Description) Cost (US$) nt Method w by ed bid Bank openin g Date G-20 Procurement of medical 4,400,000 RFQ Post Apr-20 Completed; equipment Lot 1* G-23 Vehicle 782,000 RFB Post Oct-20 Completed; G-24 IT equipment 110,000 RFQ Post Feb-21 Completed; G-25 Sodium Hypochlorite 350,000 RFQ Post July -21 Ongoing Gernerator (Evaluation process) Page 9 G-26 Camera Camcorder 31,000 RFQ Post Feb-21 Contract awarded G-27 Procurement of medical 5,221,977 RFB Post Oct-20 Completed; equipment Lot 2 G-28 Medical Equipment: 1,285,000 RFQ Post Apr-21 Contract awarded 1. Conventional PCR testing of microbiological on sanitizer and gel and alcohol and N95 Mask, 2. GC-MS Headspace and 3. Autoclave for waste management 200L G-30 High flow nasal oxygen 230,000 DS Post Oct-21 On going and Glucose meter G-31 PPE: gown and coverall 600,000 DS Post Oct-21 On going G-32 Mattress 20,000 DS Post Oct-21 On going G-33 Autoclave 200 litres 40,000 DS Post Oct-21 On going G-34 Autoclave 110 litres 200,000 DS Post Oct-21 On going G-35 Chemical reagents and 1,254,000 DS Post Oct-21 On going lab consumables for diagnosis G-36 COVID-19 Test Kits 500,000 DS Post Oct-21 On going W-01 Improvement/renovatio 40,000 DS Post Dec-21 n of the Quarantine facility for Champasack province W-02 Construction of isolation and lab facilities for W-02.1 Oupalath Village, 962,400 DS Post Oct-21 On going Phonthong District, Champasack Province W-02.2 Mai Huameuang 898,500 DS Post Oct-21 On going Village, Laman District, Sekong Province W-02.3 Veunkhene Village, 866,600 DS Post Oct-21 On going Samakkhixay District, Attapeu Province AF-G 01 Computer and 60,000 DS Post Oct-21 On going Camcorder* Page 10 AF-G 02 Covid-19 Vaccine 5,000,000 DS Prior Dec-21 Negotiation .01 (Johnson & Johnson) (through Process. Covax Facility) AF-G 04 Equipment for vaccine 30,000 DS Post Oct-21 On going cold chain container** (cold box, dry ice, carrier) AF-G 05 Vehicles for Vaccine 110,000 DS Post Oct-21 On going Delivery** AF-G 06 Essential Drug and 70,000 DS Post Oct-21 On going Alcohol AF-G 07 Essential Drug and 9,100 DS Post Oct-21 On going equipment: Meropenem, Amikacin AF-W Infectious Waste 60,000 DS Post Oct -21 Contract 01 Disposal awarded Total Goods and Works 23,130,577 Notes: RFQ: Request for Quotations RFB: Request for Bids DS: Direct Selection * For those packages that will be procured through Direct Selection, the PCO is advised to direct contracting with the suppliers who won the contracts through open competitive bidding under the parent project. II. Selection of Consultants 2.1 Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Annex II of the Procurement Regulations: Procurement Method Thresholds Prior Review Thresholds Applicable Applicable Category thresholds Remarks thresholds Remarks (US$) (US$) QCBS, QBS, FBS, ≥ 300,000 Methods for consulting ≥ 4.0 million Risk-based LCS (Using the services are specified approach most in paragraph 7.3 to appropriate 7.12, Section VII of the market Procurement approach) Regulations. CQS (Open or < 300,000 QCBS, QBS, FBS, LCS) None limited can be applied for competition contracts with value through national under US$300,000 or international Page 11 market approach, specified in the PP and agreed with the Bank. Direct Selection None No threshold; meet Same as for This has not of firms requirements of competitive been foreseen regulations 7.13-7.15 selection at the project preparation stage. Individual N/A Essential individual ≥ 400,000 and Risk-based Consultants depending on assignments will be for the positions approach nature of defined in the as specified in services Procurement Plan the PP agreed agreed with the Bank with the Bank and in line with regulations 7.34-7.39 using the most appropriate market approach 2.2 Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than US$ 200,000 equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 7.1, Section VII of the Procurement Regulations. 2.3 Consultancy Assignments with Selection Methods and Time Schedule Ref. Description of Estimated Selecti Revie Expected Comments No. Assignment Cost on w by Proposal (US$) Metho Bank s d Submissi on Date C-01 Project Manager 120,000 DS Post Aug-20 Contract awarded C-02 Procurement 50,000 DS Post Dec-2020 Contract Assistant awarded C-04 Project 57,600 DS Post June-20 Contract Accountant -1 awarded Project Contract C-05 36,000 DS Post Jun-20 Accountant -2 awarded C-06 Safeguard 72,000 DS Post Sep-20 Contract Consultant awarded C-07 M&E Consultant 100,000 DS Post Oct-21 On going C-08 Project Financial 30,000 DS Post Dec-20 Contract Statements Audit awarded Page 12 Ref. Description of Estimated Selecti Revie Expected Comments No. Assignment Cost on w by Proposal (US$) Metho Bank s d Submissi on Date Logistic and Quality assurance Contract C-09 93,578 DS Post May-21 Support Officer awarded (For FDD) C-10 Design and 210,000 CQS Post Dec-20 Contract construction awarded supervision services for isolation and treatments COVID-19 facilities C-11 Satisfactory 350,000 DS Post Dec-2020 Contract survey firm awarded C-12 Environmental 132,000 DS Post Dec-2020 Contract and Social awarded Consultant (2) Waste management AF-C-01 450,000 DS Post Oct-21 Consultant/Servic e Quality and safety AF-C-02 of Isolation 50,000 DS Post Oct-21 Facilities AF-C-13 Financial and 18,400 DS Post Nov-21 On going Program Officer for COVID-19 Vaccine Deployment Total consulting services 1,769,578 Total Goods, Works and 24,900,15 Consulting Services 5 Notes: DS: Direct Selection CQS: Consultant’s Qualification-Based Selection Page 13 Annex 1 Ref. Contract (Description) Estimated Procurement Comments No. Cost Method (US$) G- Procurement of medical 4,400,000 RFQ (national- Completed 20 equipment Lot 1 limited) rtPCR machine, 4 provinces, 1,166,256 CPS, SVK, LP, KMN, VC (2) - laboratory testing Ventilator 706,977 Oxygen concentrator 57,140 Digital mobile X-ray 150 MA (7 2,387,163 central hospitals, 17 provinces) Patient monitoring with cart 61,395 Suction pump 17,442 G- Procurement of medical 5,211,977 27 equipment Lot 2 I. Medical Equipment and 1,358,333 laboratory Syringe pump Autoclave for waste management 250 L ICU patient bed, mobile Patient monitoring device II. Medical Device Quality 608,650 Control Equipment BFE Testing machine for capacity of microbiology Medical mask synthetic blood penetration tester Material for blood synthetic( CMC-Na, Pyrrolidol monolaurate, NaCl, Amaranth, KDP, DKP( Air exchange pressure tester Respirator Particles Filtration Tester (10-100L/min, efficacy of filtration 20-30mg/m3, accuracy: level 1) Mask Tension Tester Flame Retardant Tester (Speed 60±5mm/s, V1.0, Meas&Ctrl 2.0 testing software, time range 0(99.99s) Biosafety cabinet Autoclave 79L Incubator 160L Hot air Oven 160L GC-MS Headspace Page 14 Ref. Contract (Description) Estimated Procurement Comments No. Cost Method (US$) Alcohol Meter Alcohol Densitometer Rotary Evaporator III. Medical Supplies (1) 3,250,810 Oxygen supply with regulator and humidifier (5 central hospitals and 17 provinces) Gas cylinder, WMA219-40-15 Pulse Oximeter, portable Pulse Oximeter, fingertip / spot-check IV. Medical Supplies (2) 4,184 Nasal cannula, adult (S, M, L) Oxygen mask, with reservoir bag, adult Adhesive tape Infusion giving set IV flow regulator extension set Ref. Contract (Description) Estimated Procurement Comments No. Cost Method (US$) AF- Equipment for vaccine cold 30.000 DS G chain container 04 Cold box (vaccine container) Dry ice Vaccine carrier AF- G Vehicle (pick up) 110.000 DS 05 Page 15 PROCUREMENT Lao People's Democratic Republic : Lao PDR COVID-19 Response Project PLAN General Information Country: Lao People's Democratic Republic Bank’s Approval Date of the Original Procurement Plan: 2020-04-23 2023-06-04 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P173817 GPN Date: 2021-08-27 Project Name: Lao PDR COVID-19 Response Project Loan / Credit No: IDA / 66060, IDA / 69460, TF / B5890, TF / B5891 Department of Planning and Cooperation, Ministry of Health Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Request for Quota W-01 / Improvement/renovat Component 3: Project Manag tions - Small Work 2022-01-2 ion of the Quarantine facility IDA / 66060 ement and Monitoring and E Post Direct Selection Direct s (Emergency) SP 40,000.00 0.00 Canceled 2021-06-17 2021-06-22 2021-07-27 3 for Champasack province valuation D -Non Competiti ve Request for Quota W-02.1 / Construction of isol tions - Small Work ation and lab facilities for Ou Component 1: Emergency C 2022-03-0 IDA / 66060 Post Direct Selection Direct s (Emergency) SP 962,400.00 982,453.00 Signed 2021-07-29 2021-08-02 2021-08-03 2021-09-27 2021-09-07 2021-12-31 palath Village, Phonthong Dis OVID-19 Response 6 D -Non Competiti trict, Champasack Province ve Request for Quota W-02.2 / Construction of isol tions - Small Work ation and lab facilities for Mai Component 1: Emergency C 2022-03-0 IDA / 66060 Post Direct Selection Direct s (Emergency) SP 898,500.00 942,335.00 Signed 2021-07-29 2021-08-02 2021-08-03 2021-09-27 2021-09-07 2021-12-31 Huameuang Village, Laman OVID-19 Response 6 D -Non Competiti District, Sekong Province ve Request for Quota W-02.3 / Construction of isol tions - Small Work ation and lab facilities for Ve Component 1: Emergency C 2022-03-0 IDA / 66060 Post Direct Selection Direct s (Emergency) SP 866,600.00 802,212.00 Signed 2021-07-29 2021-08-02 2021-08-03 2021-09-27 2021-09-07 2022-01-11 unkhene Village, Samakkhixa OVID-19 Response 6 D -Non Competiti y District, Attapeu Province ve Request for Quota W-01. / Improvement/renova Component 3: Project Manag Request for Quota Single Stage - One E tions - Small Work 2022-06-3 tion of the Quarantine facility IDA / 69460 ement and Monitoring and E Post Open - National 40,000.00 0.00 Signed 2021-11-06 2022-01-01 tions nvelope s (Emergency) SP 0 for Champasack province valuation D -Competitive Request for Quota W-04 / Construction and ren Component 3: Project Manag Request for Quota Single Stage - One E tions - Small Work 2023-10-3 ovation of the existing POE H IDA / 69460 ement and Monitoring and E Post Limited 10,000.00 0.00 Signed 2023-03-08 2023-03-15 2023-05-03 tions nvelope s (Emergency) SP 0 ealth screening facilities at V valuation D -Competitive uangTao POE, CPS Request for Quota AF-W-02.01 / Champasack: Component 3: Project Manag Request for Quota Single Stage - One E tions - Small Work 2023-10-3 Construction and installation TF / B5891 ement and Monitoring and E Post Limited 48,000.00 0.00 Signed 2023-03-08 2023-04-04 2023-05-03 tions nvelope s (Emergency) SP 0 of RC waste pit for needle/sh valuation D -Competitive arp waste Request for Quota AF-W-02.02 / Attapue: Const Component 3: Project Manag Request for Quota Single Stage - One E tions - Small Work Under Imple 2023-10-3 ruction and installation of RC TF / B5891 ement and Monitoring and E Post Limited 18,000.00 0.00 2023-03-08 2023-05-03 tions nvelope s (Emergency) SP mentation 0 waste pit for needle/sharp w valuation D -Competitive aste AF-W-02.06 / Saravan:(provi Request for Quota Component 3: Project Manag ncial hospital, 7 community h Request for Quota Single Stage - One E tions - Small Work Pending Imp 2023-10-3 TF / B5891 ement and Monitoring and E Post Limited 9,000.00 0.00 2023-03-09 2023-05-04 ospitals and Covid-19 treatm tions nvelope s (Emergency) SP lementation 1 valuation ent center, at NongBouHin vil D -Competitive lage Request for Quota AF-W-02.04 / Luan Prabang: Component 3: Project Manag Request for Quota Single Stage - One E tions - Small Work 2023-10-3 Construction and installation TF / B5891 ement and Monitoring and E Post Limited 12,000.00 0.00 Canceled 2023-03-08 2023-05-03 tions nvelope s (Emergency) SP 0 of RC waste pit for needle/sh valuation D -Competitive arp waste Request for Quota AF-W-02.05 / Vientiane Provi Component 3: Project Manag Request for Quota Single Stage - One E tions - Small Work Under Imple 2023-10-3 nce: Construction and install TF / B5891 ement and Monitoring and E Post Limited 50,000.00 0.00 2023-03-08 2023-05-10 2023-05-03 tions nvelope s (Emergency) SP mentation 0 ation of RC waste pit for nee valuation D -Competitive dle/sharp waste AF-W-03 / Construction and r Request for Quota Component 3: Project Manag enovation of existing garbag Request for Quota Single Stage - One E tions - Small Work 2023-10-3 TF / B5891 ement and Monitoring and E Post Limited 25,000.00 0.00 Signed 2023-03-08 2023-03-16 2023-05-03 e collection facilities at 103 tions nvelope s (Emergency) SP 0 valuation Hospital, Vientiane Capital D -Competitive Request for Quota AF-W-04 / Construction and r Component 3: Project Manag Request for Quota Single Stage - One E tions - Small Work Pending Imp 2023-10-3 enovation of existing LAB fac TF / B5891 ement and Monitoring and E Post Limited 20,000.00 0.00 2023-03-08 2023-05-03 tions nvelope s (Emergency) SP lementation 0 ilities at WASH Center valuation D -Competitive AF-W-05 / Improve the existi ng toilet and septic tank, and Component 3: Project Manag Request for Quota Request for Quota Single Stage - One E 2023-10-3 builds the fence and stair to TF / B5891 ement and Monitoring and E Post Limited tions (Non Bank-S 18,000.00 0.00 Canceled 2023-03-08 2023-05-03 tions nvelope 0 access the building at the Co valuation PD) vid-19 lab at Khoua DHO, Ph ongsaly Province AF-W-06 / Xienkhouang Prov Request for Quota Component 3: Project Manag ince: Request for Quota Single Stage - One E tions - Small Work Under Imple 2023-10-3 TF / B5891 ement and Monitoring and E Post Limited 45,000.00 0.00 2023-03-08 2023-05-03 To renovate the existing buil tions nvelope s (Emergency) SP mentation 0 valuation ding to be the standard Corvi D -Competitive d 19 Laboratory. AF-W-07.01 / HCF in Savann akhet Hospital: Request for Quota Improve the two existing sep Component 3: Project Manag Request for Quota Single Stage - One E tions - Small Work Pending Imp 2023-10-3 tic tanks and connection syst TF / B5891 ement and Monitoring and E Post Limited 100,000.00 0.00 2023-03-08 2023-05-03 tions nvelope s (Emergency) SP lementation 0 em for treating the grey wate valuation D -Competitive r 25 m3/day and 32 m3/day before discharge to the publi c canal. AF-W-07.02 / HCF in Ngern D istrict Hospital, Xayabouly Pr Request for Quota Component 3: Project Manag ovince Request for Quota Single Stage - One E tions - Small Work Pending Imp 2023-10-3 TF / B5891 ement and Monitoring and E Post Limited 55,000.00 0.00 2023-03-08 2023-05-03 To improve the existing septi tions nvelope s (Emergency) SP lementation 0 valuation c tank and connection syste D -Competitive m for treating the grey water 12m3/day before discharge t o the public canal. Request for Quota AF-W-08 / Construction brick Component 3: Project Manag Request for Quota Single Stage - One E tions - Small Work Under Imple 2023-10-3 walls at Namor Community H TF / B5891 ement and Monitoring and E Post Limited 50,000.00 0.00 2023-03-09 2023-05-04 tions nvelope s (Emergency) SP mentation 1 ospital valuation D -Competitive W-09.01 / Construction and i Request for Quota Component 3: Project Manag nstallation a chlorine drop ta Request for Quota Single Stage - One E tions - Small Work Pending Imp 2023-10-3 IDA / 69460 ement and Monitoring and E Post Limited 10,000.00 0.00 2023-03-09 2023-05-04 nk 200 liters including conne tions nvelope s (Emergency) SP lementation 1 valuation ction system in Saravan D -Competitive Page 1 W-09.02 / Installation a chlor Request for Quota Component 3: Project Manag ine drop tank 200 liters inclu Request for Quota Single Stage - One E tions - Small Work Pending Imp 2023-10-3 IDA / 69460 ement and Monitoring and E Post Limited 4,000.00 0.00 2023-03-09 2023-05-04 ding connection system tions nvelope s (Emergency) SP lementation 1 valuation in Xayabouly D -Competitive W-09.03 / Construction and i Request for Quota Component 3: Project Manag nstallation a chlorine drop ta Request for Quota Single Stage - One E tions - Small Work 2023-10-3 IDA / 69460 ement and Monitoring and E Post Limited 1,000.00 0.00 Signed 2023-03-09 2023-03-20 2023-05-04 nk 200 liters including conne tions nvelope s (Emergency) SP 1 valuation ction system in Sekong D -Competitive Request for Quota W-10.01 / Construction and i Component 3: Project Manag Request for Quota Single Stage - One E tions - Small Work Pending Imp 2023-10-3 nstallation Bio-sand filter sys IDA / 69460 ement and Monitoring and E Post Limited 100,000.00 0.00 2023-03-09 2023-05-04 tions nvelope s (Emergency) SP lementation 1 tem (for 18 m3) valuation D -Competitive Request for Quota W-11 / Construction of Eleva Component 3: Project Manag Request for Quota Single Stage - One E tions - Small Work Pending Imp 2023-10-3 ted RC water tank 25m3 incl IDA / 69460 ement and Monitoring and E Post Limited 30,000.00 0.00 2023-03-09 2023-05-04 tions nvelope s (Emergency) SP lementation 1 uding connection system valuation D -Competitive Request for Quota W-12 / Construction and inst Component 3: Project Manag Request for Quota Single Stage - One E tions - Small Work 2023-10-3 allation partition walls (clear IDA / 69460 ement and Monitoring and E Post Limited 5,000.00 0.00 Signed 2023-03-09 2023-04-03 2023-05-04 tions nvelope s (Emergency) SP 1 glass) valuation D -Competitive W-13 / Construction and Inst Request for Quota Component 3: Project Manag allation aluminum water tank Request for Quota Single Stage - One E tions - Small Work Pending Imp 2023-10-3 IDA / 69460 ement and Monitoring and E Post Limited 10,000.00 0.00 2023-03-09 2023-05-04 2500 liters and a chlorine dro tions nvelope s (Emergency) SP lementation 1 valuation p tank 200 liters including co D -Competitive nnection system Request for Quota W-03 / Construct the quaran Component 3: Project Manag Request for Quota Single Stage - One E tions - Small Work 2023-10-3 tine at Phoukeau POE at Atta IDA / 69460 ement and Monitoring and E Post Limited 100,000.00 0.00 Canceled 2023-03-08 2023-05-03 tions nvelope s (Emergency) SP 0 peu province valuation D -Competitive GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual G-20 / Procurement of medic Component 1: Emergency C Request for Quota Single Stage - One E IDA / 66060 Post Limited 4,400,000.00 4,200,000.00 Signed 2020-04-05 2020-04-03 2020-05-31 2020-04-11 2020-11-27 al equipment Lot 1 OVID-19 Response tions nvelope G-1 / Medical Equipment and Component 1: Emergency C Single Stage - One E IDA / 66060 Post Request for Bids Open - National 871,333.00 0.00 Canceled 2020-10-19 2020-10-24 2020-12-05 2021-01-04 2021-02-08 2021-08-07 laboratory OVID-19 Response nvelope G-2 / Medical Device Quality Component 1: Emergency C Single Stage - One E IDA / 66060 Post Request for Bids Open - National 608,650.00 0.00 Canceled 2020-10-19 2020-10-24 2020-12-05 2021-01-04 2021-02-08 2021-08-07 Control Equipment OVID-19 Response nvelope Component 1: Emergency C Single Stage - One E G-21 / Medical Supplies (1) IDA / 66060 Post Request for Bids Open - National 3,250,810.00 0.00 Canceled 2020-10-19 2020-10-24 2020-12-05 2021-01-04 2021-02-08 2021-08-07 OVID-19 Response nvelope G-27 / Procurement of medic Component 1: Emergency C Single Stage - One E IDA / 66060 Post Request for Bids Open - National 4,734,977.00 844,461.16 Signed 2020-09-10 2020-09-10 2020-09-15 2020-10-27 2020-10-20 2020-11-26 2020-12-08 2020-12-31 2021-01-14 2021-06-29 al equipment Lot 2 OVID-19 Response nvelope Component 1: Emergency C Single Stage - One E G-23 / Vehicle IDA / 66060 Post Request for Bids Open - National 782,000.00 716,137.46 Signed 2020-10-22 2020-10-11 2020-10-27 2020-12-08 2020-11-10 2021-01-07 2020-12-08 2021-02-11 2021-01-14 2021-08-10 OVID-19 Response nvelope Component 1: Emergency C Request for Quota Single Stage - One E G-26 / Camera Camcorder IDA / 66060 Post Open - National 31,000.00 43,725.88 Signed 2020-12-06 2021-01-31 2021-05-05 2021-07-30 OVID-19 Response tions nvelope Component 1: Emergency C Request for Quota Single Stage - One E G-24 / IT equipment IDA / 66060 Post Open - National 107,500.00 100,200.04 Signed 2020-12-15 2021-02-09 2021-05-05 2021-08-08 OVID-19 Response tions nvelope Component 3: Project Manag Request for Quota Single Stage - One E G-28 / Medical Equipment IDA / 66060 Post Open - National 1,285,000.00 485,977.52 Signed 2021-06-01 2021-07-27 2021-08-21 2022-01-23 ement and Monitoring and E tions nvelope valuation AF-G 01 / Computer and Ca Component 3: Project Manag IDA / 66060 Post Direct Selection Direct 60,000.00 0.00 Canceled 2021-06-17 2021-06-30 2021-08-04 2022-01-31 mcorder ement and Monitoring and E valuation AF-G 05 / Vehicles for Vaccin Component 3: Project Manag IDA / 66060 Post Direct Selection Direct 110,000.00 73,000.00 Signed 2021-06-17 2021-06-17 2021-06-22 2021-10-05 2021-07-27 2021-11-10 2022-01-23 e Delivery ement and Monitoring and E valuation AF-G 04 / Equipment for vac Component 3: Project Manag cine cold chain container (col IDA / 66060 ement and Monitoring and E Post Direct Selection Direct 30,000.00 255,000.00 Signed 2021-06-17 2021-06-17 2021-06-22 2021-10-04 2021-07-27 2021-11-10 2022-01-23 d box, dry ice, carrier) valuation G27 / Procurement of medic Component 1: Emergency C Single Stage - One E IDA / 66060 Post Request for Bids Open - National 5,221,977.00 1,314,361.23 Signed 2020-09-10 2020-09-10 2020-09-15 2020-10-27 2020-10-20 2020-11-26 2020-12-08 2020-12-31 2021-01-14 2021-06-29 al equipment Lot 2 OVID-19 Response nvelope G-30 / High flow nasal oxyge Component 3: Project Manag IDA / 66060 Post Direct Selection Direct 230,000.00 224,700.00 Signed 2021-11-04 2021-11-04 2021-11-09 2021-10-18 2021-12-14 2021-11-10 2022-06-12 n and Glucose meter ement and Monitoring and E valuation AF-G 06 / Essential Drug and Component 3: Project Manag IDA / 66060 Post Direct Selection Direct 70,000.00 41,423.86 Signed 2021-11-04 2021-11-04 2021-11-09 2021-11-05 2021-12-14 2021-12-22 2022-06-12 Alcohol ement and Monitoring and E valuation Component 3: Project Manag Request for Quota Single Stage - One E G-32 / Mattress for patients IDA / 66060 Post Limited 20,000.00 17,223.98 Signed 2021-11-24 2021-11-12 2022-01-19 2022-02-01 2022-07-18 ement and Monitoring and E tions nvelope valuation G-35 / Chemical reagents an Component 3: Project Manag IDA / 66060 Post Direct Selection Direct 1,254,000.00 240,900.00 Signed 2021-11-19 2021-11-19 2021-11-24 2021-11-19 2021-12-29 2021-12-22 2022-06-27 d lab consumables for diagno ement and Monitoring and E sis valuation G-31 / PPE: gown and covera Component 3: Project Manag IDA / 66060 Post Direct Selection Direct 600,000.00 155,000.00 Signed 2021-12-23 2021-12-23 2021-12-28 2021-12-24 2022-02-01 2022-02-18 2022-07-31 ll ement and Monitoring and E valuation AF-G 07 / Essential Drug : M Component 3: Project Manag eropenem 1g and Amikacin i IDA / 69460 ement and Monitoring and E Post Direct Selection Direct 9,100.00 7,282.04 Signed 2021-12-23 2021-12-13 2021-12-28 2021-12-27 2022-02-01 2022-02-10 2022-07-31 njection 500mg/2ml valuation G-33 / Procurement of Autoc Component 3: Project Manag IDA / 66060 Post Direct Selection Direct 240,000.00 82,000.00 Signed 2021-12-23 2022-02-09 2021-12-28 2022-02-09 2022-02-01 2022-04-20 2022-07-31 lave ement and Monitoring and E valuation AF-G 01. / Computer and Ca Component 3: Project Manag Request for Quota Single Stage - One E IDA / 66060 Post Open - National 92,000.00 0.00 Completed 2022-03-05 2022-04-30 2022-10-27 2023-01-12 mcorder ement and Monitoring and E tions nvelope valuation AF-G 08 / Diagnostic Chemic Component 3: Project Manag Request for Quota Single Stage - One E IDA / 69460 Post Open - National 604,000.00 0.00 Signed 2022-03-12 2022-05-07 2022-11-03 al Reagents for Laboratory ement and Monitoring and E tions nvelope valuation Page 2 AF-G 09 / Disinfectant, alcoh Component 4: Strengthening TF / B5890 Post Direct Selection Direct 135,000.00 0.00 Canceled 2022-05-20 2022-05-25 2022-06-29 2022-12-26 ol, general (available size 5L) Preparedness for Health Em 70% ergency AF-G 10 / Molnupiravir 200 Component 4: Strengthening TF / B5890 Post Direct Selection Direct 74,000.00 0.00 Canceled 2022-05-20 2022-05-25 2022-06-29 2022-12-26 mg Preparedness for Health Em ergency Component 4: Strengthening AF-G 11 / Favipiravir 200mg TF / B5890 Post Direct Selection Direct 5,000.00 0.00 Canceled 2022-05-20 2022-05-25 2022-06-29 2022-12-26 Preparedness for Health Em ergency AF-G 12 / Enoxaparin Sodiu Component 4: Strengthening TF / B5890 Post Direct Selection Direct 97,000.00 0.00 Canceled 2022-05-20 2022-05-25 2022-06-29 2022-12-26 m BP 40 mg/0.4 mL Preparedness for Health Em ergency AF-G 13 / Meropenem Trihyd Component 4: Strengthening TF / B5890 Post Direct Selection Direct 214,000.00 0.00 Canceled 2022-05-20 2022-05-25 2022-06-29 2022-12-26 rate eq. to anhydrous Merop Preparedness for Health Em enem 1 g ergency AF-G 14 / Drugs (Dabigatran Component 4: Strengthening 110 mg, Dabigatran 150 mg TF / B5890 Preparedness for Health Em Post Direct Selection Direct 32,000.00 0.00 Canceled 2022-05-20 2022-05-25 2022-06-29 2022-12-26 and Immunogloburin) ergency AF-G 15 / Diagnostic Chemic Component 4: Strengthening TF / B5890 Post Direct Selection Direct 647,000.00 0.00 Canceled 2022-05-26 2022-07-20 2023-04-18 al Reagent for Real-time PCR Preparedness for Health Em -01 ergency AF-G 16 / Diagnostic Chemic Component 4: Strengthening TF / B5890 Post Direct Selection Direct 679,000.00 0.00 Canceled 2022-05-20 2022-05-25 2022-06-29 2022-12-26 al Reagent for Real-time PCR Preparedness for Health Em -02 ergency AF-G 17 / Diagnostic Chemic Component 4: Strengthening al Reagent for Real-time PCR Request for Quota Single Stage - One E TF / B5890 Preparedness for Health Em Post Open - National 900,000.00 0.00 Canceled 2022-05-25 2022-07-20 2023-01-16 -03 and Prevention and Contr tions nvelope ergency ol - all PPE items AF-G 18 / AccuViral Collectio Component 3: Project Manag Request for Quota Single Stage - One E n Kit, 3ml VTM Medium with TF / B5891 ement and Monitoring and E Post Open - National 216,000.00 0.00 Canceled 2022-07-09 2022-09-03 2023-03-02 tions nvelope one Nasopharyngeal and one valuation Throat swabs G-37 / Medical Equipment fo Component 3: Project Manag r COVID-19 Treatment Faciliti TF / B5891 ement and Monitoring and E Post Direct Selection Direct - National 500,000.00 0.00 Canceled 2022-09-07 2022-09-12 2022-10-17 2023-04-15 es in Champasak , Sekong an valuation d Attapue Provinces AF-G 19 / Motorcycles for Dis Component 3: Project Manag TF / B5891 Post Direct Selection Direct - National 100,000.00 0.00 Signed 2022-10-03 2022-09-23 2022-10-08 2022-10-17 2022-11-12 2023-05-11 tricts ement and Monitoring and E valuation AF-G 20 / Megaphones for Di Component 3: Project Manag Request for Quota Single Stage - One E TF / B5891 Post Open - National 35,000.00 0.00 Signed 2022-10-08 2022-12-03 2023-06-01 stricts ement and Monitoring and E tions nvelope valuation G-37. / Medical Equipment f Component 3: Project Manag or Single Stage - One E Under Imple IDA / 69460 ement and Monitoring and E Post Request for Bids Open - National 500,000.00 0.00 2022-11-15 2022-12-01 2022-11-20 2023-01-01 2022-12-27 2023-01-31 2023-03-10 2023-03-07 2023-09-03 COVID-19 Treatment Facilitie nvelope mentation valuation s in Champasak , Sekong and Attapue Provinces AF-G 22 / Hospital Furniture Component 3: Project Manag for isolation and lab facilities Request for Quota Single Stage - One E TF / B5891 ement and Monitoring and E Post Open - National 200,000.00 0.00 Signed 2022-11-20 2023-01-15 2023-07-14 for Champasak, Sekong and tions nvelope valuation Attapeu Provinces G-38 / Refrigerated Vaccine Component 3: Project Manag Request for Quota Single Stage - One E TF / B5891 Post Open - National 585,000.00 0.00 Signed 2022-12-10 2023-02-04 2023-08-03 Transport Vehicle ement and Monitoring and E tions nvelope valuation G-39 / Computer for POE sta Component 3: Project Manag Request for Quota Single Stage - One E Pending Impl TF / B5891 Post Open - National 38,000.00 0.00 2022-12-10 2023-02-04 2023-08-03 ff 28 POE ement and Monitoring and E tions nvelope ementation valuation AF-G 23 / Procurement of wa Component 3: Project Manag Request for Quota Single Stage - One E Pending Impl ste collection, segregation an TF / B5891 ement and Monitoring and E Post Open - National 1,350,000.00 0.00 2022-12-10 2023-02-04 2023-08-03 tions nvelope ementation d disinfection technology valuation AF-G 09. / Procurement of Di Component 3: Project Manag sinfectant, alcohol, general ( Request for Quota Single Stage - One E TF / B5891 ement and Monitoring and E Post Open - National 209,000.00 0.00 Signed 2022-12-19 2023-02-13 2023-08-12 available size 5L) 70% , Moln tions nvelope valuation upiravir 200 mg and medical consumables AF-G 24 / Procurement of lap Component 3: Project Manag Request for Quota Single Stage - One E Pending Impl TF / B5891 Post Open - National 287,100.00 0.00 2023-01-28 2023-03-25 2023-09-21 top computers for health cen ement and Monitoring and E tions nvelope ementation ters valuation AF-G 25 / Laboratory reagen Component 3: Project Manag Request for Quota Single Stage - One E TF / B5891 Post Open - National 1,350,000.00 0.00 Canceled 2023-02-01 2023-03-29 2023-09-25 ts and supplies for testing ement and Monitoring and E tions nvelope valuation AF-G 26 / Vehicle for transpo Component 3: Project Manag Request for Quota Single Stage - One E Pending Impl TF / B5891 Post Open - National 234,000.00 0.00 2023-02-07 2023-04-04 2023-10-01 rtation of Drug and medical e ement and Monitoring and E tions nvelope ementation quipment valuation Component 3: Project Manag Pending Impl G-40 / TB Drug IDA / 69460 Post Direct Selection Direct - National 652,400.00 0.00 2023-03-04 2023-03-09 2023-04-13 2023-10-10 ement and Monitoring and E ementation valuation AF-G 21 / Sleeveless shirt jac Component 3: Project Manag Request for Quota Single Stage - One E TF / B5891 Post Open - National 50,000.00 0.00 Canceled 2022-10-08 2022-12-03 2023-06-01 kets for health centers ement and Monitoring and E tions nvelope valuation AF-G 27 / Vaccines Procurem Component 1: Emergency C IDA / 66060 Post Direct Selection Direct - National 991,267.00 0.00 Signed 2023-03-03 2023-03-03 2023-03-15 2023-03-15 2023-05-30 2023-12-30 ent (MR5, Penta, PCV and HP OVID-19 Response V) AF-G 28 / Medical Equipment Component 3: Project Manag Request for Quota Single Stage - One E Pending Impl TF / B5891 Post Open - National 639,884.00 0.00 2023-06-08 2023-08-03 2024-01-30 for Community Health Facilit ement and Monitoring and E tions nvelope ementation y valuation AF-G 29 / Laboratory COVID- Component 3: Project Manag Request for Quota Single Stage - One E Pending Impl TF / B5891 Post Open - National 500,100.00 0.00 2023-06-08 2023-08-03 2024-01-30 19 detection kits and consum ement and Monitoring and E tions nvelope ementation ables valuation AF-G 30 / Laboratory equipm Component 3: Project Manag Request for Quota Single Stage - One E Pending Impl ent and Standard Reagent fo TF / B5891 ement and Monitoring and E Post Open - National 286,010.00 0.00 2023-06-08 2023-08-03 2024-01-30 tions nvelope ementation r Medicine Quality Testing valuation NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 3 AF-W 01 / Infectious Waste Component 3: Project Manag IDA / 66060 Post Direct Selection Direct 60,000.00 0.00 Completed 2021-06-17 2021-06-17 2021-06-22 2021-11-05 2021-07-27 2022-01-23 2021-12-06 Disposal ement and Monitoring and E valuation CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual C-10 / Design and constructi Component 1: Emergency C Consultant Qualifi on supervision services for is IDA / 66060 Post Open - National 210,000.00 205,392.00 Signed 2020-10-30 2021-02-08 2020-11-20 2021-01-03 2021-02-22 2021-02-02 2021-04-05 2021-03-09 2021-04-24 2021-09-05 OVID-19 Response cation Selection olation and treatments COVI D-19 facilities INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 3: Project Manag C-04 / Project Accountant-1 IDA / 66060 Post Direct Selection Direct 32,000.00 14,400.00 Signed 2020-04-28 2020-04-28 2020-05-08 2020-04-30 2020-07-12 2020-06-02 2021-01-08 ement and Monitoring and E valuation Component 3: Project Manag C-01 / Project Manager IDA / 66060 Post Direct Selection Direct 69,000.00 33,600.00 Signed 2020-06-13 2020-06-13 2020-06-23 2020-06-09 2020-08-27 2020-08-11 2021-02-23 ement and Monitoring and E valuation Component 3: Project Manag C-06 / Safeguard Consultant IDA / 66060 Post Direct Selection Direct 34,000.00 24,000.00 Signed 2020-06-13 2020-06-13 2020-06-23 2020-08-04 2020-08-27 2020-09-02 2021-02-23 ement and Monitoring and E valuation Component 3: Project Manag C-05 / Project Accountant-2 IDA / 66060 Post Direct Selection Direct 32,000.00 0.00 Canceled 2020-04-28 2020-05-06 2020-05-08 2020-07-12 2021-01-08 ement and Monitoring and E valuation C-03 / Chief Project Account Component 3: Project Manag IDA / 66060 Post Direct Selection Direct 48,000.00 0.00 Canceled 2020-04-28 2020-05-08 2020-07-12 2021-01-08 ant ement and Monitoring and E valuation C-08 / Project Financial State Component 1: Emergency C IDA / 66060 Post Direct Selection Direct 30,000.00 9,000.00 Signed 2020-10-22 2020-10-26 2020-11-01 2020-12-20 2021-01-05 2021-03-16 2021-07-04 ments Audit OVID-19 Response C-02 / Procurement Assistan Component 1: Emergency C IDA / 66060 Post Direct Selection Direct 34,500.00 15,600.00 Signed 2020-12-01 2020-12-10 2020-12-11 2020-12-29 2021-02-14 2021-01-26 2021-08-13 t OVID-19 Response C-12 / Environmental and So Component 1: Emergency C IDA / 66060 Post Direct Selection Direct 34,500.00 175.00 Signed 2020-12-01 2020-12-15 2020-12-11 2021-01-24 2021-02-14 2021-02-16 2021-08-13 cial Consultant (2) OVID-19 Response C-11 / Satisfactory survey fir Component 1: Emergency C IDA / 66060 Post Direct Selection Direct 200,000.00 198,910.00 Signed 2020-12-11 2020-12-15 2020-12-21 2021-01-19 2021-02-24 2021-04-23 2021-08-23 m OVID-19 Response C-09.1 / Logistic and Quality Component 1: Emergency C assurance Support Officer(Fo IDA / 66060 Post Direct Selection Direct 60,000.00 24,000.00 Signed 2020-12-15 2021-02-02 2020-12-25 2021-03-15 2021-02-28 2021-05-11 2021-08-27 OVID-19 Response r Department of Food and Dr ug) Component 3: Project Manag C-07 / M&E Consultant IDA / 66060 Post Direct Selection Direct 100,000.00 21,600.00 Signed 2021-06-17 2021-06-23 2021-06-30 2021-10-24 2021-09-03 2021-11-02 2022-03-02 ement and Monitoring and E valuation Component 3: Project Manag C-5 / Project Accountant -2 IDA / 66060 Post Direct Selection Direct 36,000.00 14,400.00 Signed 2021-06-17 2021-06-23 2021-06-27 2021-06-24 2021-08-31 2021-07-02 2022-02-27 ement and Monitoring and E valuation C-13 / Consultant for Financi Component 3: Project Manag al and Program Officer for CO IDA / 69460 ement and Monitoring and E Post Direct Selection Direct 18,400.00 18,000.00 Signed 2021-10-18 2021-10-20 2021-10-28 2021-10-28 2022-01-01 2021-11-16 2022-06-30 VID-19 Vaccine Deployment valuation AF-C-01 / Individual Consulta Component 3: Project Manag nt: Rapid Assessment of Medi IDA / 69460 ement and Monitoring and E Post Direct Selection Direct 10,000.00 0.00 Canceled 2021-12-17 2021-12-27 2022-03-02 2022-08-29 cal Waste Management in Pr valuation ovincial Hospitals AF-C-01. / Individual Consult Component 3: Project Manag ant: Rapid Assessment of Me Individual Consult IDA / 69460 ement and Monitoring and E Post Direct 10,000.00 6,000.00 Signed 2021-12-23 2022-01-05 2022-01-02 2022-01-06 2022-01-23 2022-01-06 2022-02-27 2022-01-18 2022-08-26 dical Waste Management in P ant Selection valuation rovincial Hospitals C-03. / Chief of Project Acco Component 3: Project Manag Individual Consult IDA / 66060 Post Direct 75,600.00 36,852.00 Signed 2021-12-23 2022-01-04 2022-01-02 2021-12-27 2022-01-23 2021-12-27 2022-02-27 2022-01-05 2022-08-26 untant ement and Monitoring and E ant Selection valuation C-14 / GRM Public Relation O Component 3: Project Manag Individual Consult IDA / 66060 Post Direct 14,400.00 6,600.00 Signed 2022-01-26 2022-02-08 2022-02-05 2022-02-18 2022-02-26 2022-02-18 2022-04-02 2022-03-02 2022-09-29 fficer ement and Monitoring and E ant Selection valuation AF-C-03 / Waste Handling Su Component 3: Project Manag Individual Consult IDA / 69460 Post Direct 7,200.00 5,400.00 Signed 2022-01-26 2022-02-08 2022-02-05 2022-02-21 2022-02-26 2022-02-22 2022-04-02 2022-03-02 2022-09-29 pport Staff ement and Monitoring and E ant Selection valuation AF-C-02 / Consulting Firm: O Component 3: Project Manag n Medical Wastewater Manag IDA / 69460 ement and Monitoring and E Post Direct Selection Direct 440,000.00 0.00 Completed 2022-02-17 2022-02-21 2022-02-27 2022-03-10 2022-05-03 2022-10-30 2023-01-16 ement at Healthcare Facilitie valuation s C-15 / Short Term Individual Component 4: Strengthening Consultant on WASH need as Individual Consult TF / B5890 Preparedness for Health Em Post Direct 25,000.00 0.00 Completed 2022-05-11 2022-05-16 2022-05-21 2022-07-13 2022-06-11 2022-08-01 2022-07-16 2023-01-12 2022-11-10 sessment for health emergen ant Selection ergency cy response and preparedne ss C-16 / Medical Waste manag Component 4: Strengthening TF / B5890 Post Direct Selection Direct 100,000.00 0.00 Canceled 2022-05-11 2022-05-16 2022-05-21 2022-07-25 2023-01-21 ement Consultant at health f Preparedness for Health Em acilities ergency AF-C-04 / Short Term Individ Component 4: Strengthening Individual Consult IDA / 69460 Post Direct 5,000.00 0.00 Completed 2022-05-13 2022-05-16 2022-05-23 2022-09-19 2022-06-13 2022-09-26 2022-07-18 2023-01-14 2023-01-12 ual Legal Consultant Preparedness for Health Em ant Selection ergency C-17 / National Data Progra Component 3: Project Manag Individual Consult IDA / 66060 Post Direct 10,800.00 0.00 Signed 2022-06-14 2022-06-17 2022-06-24 2022-07-13 2022-07-15 2022-07-15 2022-08-19 2023-02-15 m Officer ement and Monitoring and E ant Selection valuation AF-C-05 / Consulting Firm for Technical Assistance on COVI Component 3: Project Manag D-19 Treatment Facilities Op TF / B5891 ement and Monitoring and E Post Direct Selection Direct 100,000.00 0.00 Completed 2022-06-29 2022-07-12 2022-07-09 2022-08-09 2022-09-12 2023-03-11 2023-01-13 eration and Maintenance in C valuation hampasak, Attapeu, and Sek ong Provinces AF-C-08 / Wastewater and S Component 3: Project Manag Individual Consult IDA / 69460 Post Direct 12,000.00 0.00 Completed 2022-07-11 2022-12-13 2022-07-21 2022-07-15 2022-08-11 2022-07-18 2022-09-15 2023-03-14 2022-11-02 olid Waste Management Con ement and Monitoring and E ant Selection sultant valuation Page 4 AF-C-06 / National Architectu Component 3: Project Manag Individual Consult IDA / 69460 Post Direct 64,000.00 0.00 Completed 2022-07-11 2022-07-18 2022-07-21 2022-10-19 2022-08-11 2022-10-24 2022-09-15 2023-03-14 2023-01-12 re Consultant ement and Monitoring and E ant Selection valuation AF-C-07 / National Assessme nt of Multi-Hazard risk and cri Component 3: Project Manag Individual Consult tical infrastructure under cli IDA / 69460 ement and Monitoring and E Post Direct 140,000.00 0.00 Canceled 2022-07-11 2022-07-18 2022-07-21 2022-08-11 2022-09-15 2023-03-14 ant Selection mate change and Developme valuation nt and Pilot-Testing of Lao PD R Hospital Safety Index AF-C-07. / Assessing of Healt Component 3: Project Manag h Facility and Lifeline Infrastr TF / B5891 ement and Monitoring and E Post Direct Selection Direct - National 140,000.00 0.00 Canceled 2022-11-07 2022-11-01 2022-11-17 2023-01-21 2023-07-20 ucture for Health Emergency valuation Preparedness in Lao PDR C-18 / Procurement Consulta Component 3: Project Manag Individual Consult IDA / 69460 Post Direct - National 48,000.00 0.00 Signed 2023-01-13 2023-01-19 2023-01-23 2023-02-02 2023-02-13 2023-02-02 2023-03-20 2023-09-16 nt ement and Monitoring and E ant Selection valuation C-19 / Admin and Finance Of Component 3: Project Manag Individual Consult IDA / 69460 Post Direct - National 28,800.00 0.00 Signed 2023-01-13 2023-01-19 2023-01-23 2023-01-16 2023-02-13 2023-01-16 2023-03-20 2023-09-16 ficer ement and Monitoring and E ant Selection valuation Component 3: Project Manag Individual Consult C-20 / M&E Consultant IDA / 69460 Post Direct - National 24,000.00 0.00 Signed 2023-01-13 2023-01-19 2023-01-23 2023-02-01 2023-02-13 2023-02-02 2023-03-20 2023-09-16 ement and Monitoring and E ant Selection valuation AF-C07 / Consulting Firm for Component 4: Strengthening Assessing of Health Facility a TF / B5891 Preparedness for Health Em Post Direct Selection Direct - National 220,000.00 0.00 Signed 2023-01-23 2023-01-19 2023-02-02 2023-01-20 2023-04-08 2023-10-05 nd Lifeline Infrastructure for ergency Health Emergency Preparedn ess in Lao PDR AF-C-10 / Individual Consulta Component 3: Project Manag nt on Design and Constructio Individual Consult TF / B5891 ement and Monitoring and E Post Direct - National 35,000.00 0.00 Signed 2023-04-03 2023-05-03 2023-04-13 2023-05-05 2023-05-04 2023-05-08 2023-06-08 2023-12-05 n Supervision for Septic tank ant Selection valuation Treatment System and Scree ning Building AF-C-09 / Consulting Firm for Design and construction sup Component 3: Project Manag ervision services for wastewa TF / B5891 ement and Monitoring and E Post Direct Selection Direct - National 45,000.00 0.00 Canceled 2023-01-27 2023-01-26 2023-02-06 2023-04-12 2023-10-09 ter system, water supply syst valuation em, and small civil works for improvement of WASH in He alth Facility C-16. / Consulting Services o Component 3: Project Manag n Medical Waste Managemen IDA / 69460 ement and Monitoring and E Post Direct Selection Direct - National 100,000.00 0.00 Canceled 2023-01-13 2023-01-19 2023-01-23 2023-03-29 2023-09-25 t at Healthcare Facilities valuation AF-C-11 / Technical Advisor f Component 3: Project Manag Individual Consult Direct - Internation Under Implement IDA / 69460 Post 25,000.00 0.00 2023-05-03 2023-06-01 2023-05-13 2023-06-03 2023-07-08 2024-01-04 or Development of Referral G ement and Monitoring and E ant Selection al ation uideline valuation Page 5 FEDERAL REPUBLIC OF NIGERIA 18-Months Procurement Plan General: Project Information: Nigeria; REDISSE; P159040. Project Implementation Agency: Nigeria Centre for Disease Control (NCDC) Date of the Procurement Plan: April 2018 Period covered by this Procurement Plan: April 2018 - November, 2019 I. Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers”, July 2016 (Revised November 2017) (“Procurement Regulations”), the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. II. Bank’s Standard Procurement Documents: The Bank’s Standard Procurement Documents shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. III. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in Nigeria Public Procurement Act 2007 and the Regulations, 2016, such arrangements shall be subject to paragraph 5.3 and 5.4 of the Procurement Regulations and the following conditions: o There should be no mandatory requirements for inclusion of local experts and firms for the consulting assignments; o There should be no exclusive preference based on threshold prescribed in PPA and credit and its Regulations; o Negotiations with the lowest evaluated bidder to reduce price in the case of goods, works and non-consulting services where competitive methods have been used shall not be allowed; 1 o The fixed budget method shall not be used for goods, works and non- consulting services; o Established and approved procurement standards by the government may be used, provided that they are not restrictive When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. In accordance with paragraph 5.4(c) and 5.5 of the Procurement Regulations, the request for bids/request for proposals/request for quotations document shall require that Bidders/Proposers submitting Bids/Proposals/quotations present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights. The form of the Letter of Acceptance is attached in Appendix 1. IV. Prequalification: Applicable (May be applicable at the Federal for high value Consultant Assignments V. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Not Applicable VI. Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations: Not Applicable VII. Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Not Applicable Domestic preference is not applicable for National Open Competitive Procurement VIII. Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations is: Not Applicable IX. Other Relevant Procurement Information: Not Applicable 2 3 X. Threshold for Prior Review, Procurement Approaches and Methods – Goods, Works and Non- Consulting Services Procurement Approaches and Methods (US$ millions) Category Open Open National Request for Quotation International (RfQ) Works, Turnkey, and ≥5 <5 ≤ 0.2 S&I of Plant and Equipment Goods, IT, and non- ≥5 <0.5 ≤ 0.1 consulting services Post Review: All contracts not subject to prior review shall be subject to post review. XI. Summary of the procurement packages for Goods, Works and Non-Consulting Services: Sr. Contract Implem Estima Revie Market Selecti Evaluati Procurem Prequ Domesti Expect Expect No Description enting ted w by Approa on on ent alifica c ed ed date Agency Cost Bank ch Metho Options Process tion Prefere date of (US$) (Prior (Open- d (Most (Single (Yes/ nce of bid/ Contra / Nationa (RFP, Advanta stage- No) (Yes/No propo ct Post) l/ RFB, geous single ) sal Signat Limited RFQ, Bid, envelope openin ure etc.) DS BAFO, etc.) g etc.) Rated Criteria etc.) GOODS 1 Procureme NCDC 3,579,1 Post Open, RFB Most Single No No 08-10- 22-10-18 nt of (AH & 39 National Advanta stage- 18 Vehicles HH) geous single (12 Nos. Bid envelope 4WD DC; 6Nos. 4WD Veterinary Ambulatory vehicle; 4 Nos. 4WD 4 SUVs; 1No. 20Tonnes Truck; 75 Motorcycle and 175 Tricycle 2 Procureme NCDC 198,162 Post Open, RFB Most Single No No 20-03- 10-04-19 nt of Office (AH) National Advanta stage- 19 Equipment geous single & Furniture Bid envelope for 37 state Vet. Public Health /Epidemiolo gy Offices 3 Procureme NCDC 97,377 Post Limited RfQ Rated Single No No 17-09- 01-10-18 nt of (AH) Criteria envelope 18 Laptops and Internet Modem for Surveillanc e activities & Non- Android Phones for animal disease informants 4 Procureme NCDC 926,423 Post Open, RFB Most Single No No 08-10- 22-10-18 nt of Lab. (HH) National Advanta envelope 18 Equipt. , geous Reagents & Bid Consumabl es and Biosecurity Materials (4Lots) 5 Procureme NCDC 295,082 Prior DIR DIR Direct Single No No Nov. Nov. nt of (AH) Selection envelope 2018 2021 5 50000/Vial of ARV Vaccine 6 Procureme NCDC 1,067,8 Post Open, RFB Most Single No No 08-10- 22-10-18 nt of (AH 68 National Advanta envelope 18 Veterinary &HH) geous Stockpiles Bid for preventabl e Zoonotic diseases (AH ) & Consumabl e for HEPR Stockpiling (HH) -2 Lots 7 Procureme NCDC 45,015 Post Limited RfQ Rated Single No No 17-09- 01-10-18 nt of Office (AH) Criteria envelope 18 Furniture/E quipment for Crises Manageme nt Centre (AH) 8 Supply of NCDC 75,374 Post Limited RfQ Rated Single No No 17-09- 01-10-18 Office (AH) Criteria envelope 18 Furniture and Equipment for REDISSE Animal Health Component Office (AH) 9 Printing of NCDC 146,787 Post Limited RfQ Rated Single No No 31-10- 14-11-18 IDSR (HH) Criteria envelope 18 Guideline 10 Printing of NCDC 200,164 Post Limited RfQ Rated Single No No 31-10- 14-11-18 IDSR Tools (HH) Criteria envelope 18 6 (Forms 001,002, 003) 11 Printing of NCDC 36,393 Post Limited RfQ Rated Single No No 31-10- 14-11-18 IDSR Policy (HH) Criteria envelope 18 12 Procureme NCDC 819,672 Post Open, RFB Most Single No No 08-10- 22-10-18 nt of (HH) National Advanta envelope 18 Emergency geous Laboratory Bid reagents and consumable s for NRL/CPHL 13 Procureme NCDC 606,557 Post Open, RFB Most Single No No 08-10- 22-10-18 nt of (HH) National Advanta envelope 18 Consumabl geous e and IPC Bid Materials (HH) 14 Supply of NCDC 68,508 Post Limited RfQ Most Single No No 17-09- 01-10-18 Office (HH) Advanta envelope 18 Furniture geous and Bid Equipment for REDISSE PCU Office - (HH) 15 Procureme NCDC 57,172 Post Limited RfQ Rated Single No No 31-10- 14-11-18 nt of Tabs (HH) Criteria envelope 18 (80), Laptops (35) and 2GB/Month USB Internet Service for step-down training for IDSR for HH 7 16 Supply and NCDC 98,361 Post Limited RfQ Rated Single No No 17-09- 01-10-18 Installation (HH) Criteria envelope 18 of 250 KVA Gen. Set and 20 KVAs Solar Panels and Inverters for REDISSE PCU's Office Total Goods 8,318, 954 WORKS 17 Rehabilitati NCDC 110,16 Post Limited RfQ Rated Single No No 21-01- 04-02-19 on of 7 Nos (AH) 4 Criteria envelope 19 State Veterinary Public Health/Epid emiology offices - NW ZONE ( Kaduna, Katsina, Kano, Jigawa,Keb bi, Zamfara & Sokoto) 18 Rehabilitati NCDC 94,426 Post Limited RfQ Rated Single No No 21-01- 04-02-19 on of 6 Nos. (AH) Criteria envelope 19 State Veterinary Public Health/Epid emiology offices- NE ZONE (Bauchi, Borno, 8 Yobe, Adamawa, Gombe & Taraba) 19 Rehabilitati NCDC 110,16 Post Limited RfQ Rated Single No No 21-01- 04-02-19 on of 7 Nos (AH) 4 Criteria envelope 19 State Veterinary Public Health/Epid emiology offices - NC ZONE ( Plateau, Nasarawa, Benue, Niger, Kogi, Kwara & FCT) 20 Rehabilitati NCDC 94,426 Limited Limited RfQ Rated Single No No 21-01- 04-02-19 on of 6 Nos. (AH) Criteria envelope 19 State Veterinary Public Health/Epid emiology offices - SW ZONE (Osun, Oyo, Ogun, Ondo, Lagos & Ekiti) 21 Rehabilitati NCDC 94,426 Limited Limited RfQ Rated Single No No 21-01- 04-02-19 on of 6 Nos. (AH) Criteria envelope 19 State Veterinary Public Health/Epid emiology 9 offices - SS ZONE ( Edo, Delta, Bayelsa, Rivers, Cross- Rivers & Akwa-Ibom) 22 Rehabilitati NCDC 78,688 Post Limited RfQ Rated Single No No 21-01- 04-02-19 on of 5 Nos. (AH) Criteria envelope 19 State Veterinary Public Health/Epid emiology offices - SE ZONE ( Enugu, Ebonyi, Imo, Anambra & Abia) 23 Refurbishm NCDC 75,374 Post Limited RfQ Rated Single No No 21-01- 04-02-19 ent of (HH) Criteria envelope 19 REDISSE Animal Health component office at Headquarte r 24 Renovation NCDC 114,75 Post Limited RfQ Rated Single No No 21-01- 04-02-19 and (HH) 4 Criteria envelope 19 upgrade of 7 Nos. Isolation Centers in NW ZONE ( Kaduna, Katsina, 10 Kano, Jigawa, Kebbi, Zamfara & Sokoto) 25 Renovation NCDC 98,360 Post Limited RfQ Rated Single No No 21-01- 04-02-19 and (HH) Criteria envelope 19 upgrade of 6 Nos. Isolation Centers in NE ZONE (Bauchi, Borno, Yobe, Adamawa, Gombe & Taraba) 26 Renovation NCDC 114,75 Post Limited RfQ Rated Single No No 21-01- 04-02-19 and (HH) 4 Criteria envelope 19 upgrade of 7 Nos. Isolation Centers in NC ZONE ( Plateau, Nasarawa, Benue, Niger, Kogi, Kwara & FCT) 27 Renovation NCDC 98,360 Post Limited RfQ Rated Single No No 21-01- 04-02-19 and (HH) Criteria envelope 19 upgrade of 6 Nos. Isolation Centers in SW ZONE (Osun, Oyo, Ogun, 11 Ondo, Lagos & Ekiti) 28 Renovation NCDC 98,360 Post Limited RfQ Rated Single No No 21-01- 04-02-19 and (HH) Criteria envelope 19 upgrade of 6 Nos. Isolation Centers in SS ZONE ( Edo, Delta, Bayelsa, Rivers, Cross- Rivers & Akwa-Ibom) 29 Renovation NCDC 81,967 Post Limited RfQ Rated Single No No 21-01- 04-02-19 and (HH) Criteria envelope 19 upgrade of 5 Nos. Isolation Centres in SE ZONE ( Enugu, Ebonyi, Imo, Anambra & Abia) 30 Supply and NCDC 606,55 Post Open, RFB Most Single No No 04-03- 25-03-19 Installation (HH) 7 National Advanta envelope 19 of 1No. geous Incinerator Bid in a selected facilty in each of the six geopolitical zones Total works 1,870, 780 12 NON-CONSULTING SERVICES 31 Registration NCDC (AH) 20,492 Post Limited RfQ Rated Single No No 18-12- 02-10-19 of Criteria envelope 18 motorcycles (75 Nos. ) and tricycle (175 Nos.) for AH 32 Registration NCDC (AH) 266,437 Post Limited RfQ Rated Single No No 18-12- 02-10-19 and Insurance Criteria envelope 18 for 9 Nos. 4WD DC vehicles; 2 Nos. 15- Seater Bus; 6 Nos. 4WD Vet. Ambulatory vehicle; 2 Nos. SUVs; and 1No. 20Tonne Truck for AH 33 Registration NCDC 93,098 Post Limited RfQ Rated Single No No 18-12- 02-10-19 and Insurance (HH) Criteria envelope 18 for 3 Nos. 4WD DC vehicles; 2 Nos. SUVs for HH 34 Installation of NCDC 4,049 Post Limited RfQ Rated Single No No 18-12- 02-10-19 tracking (AH) Criteria envelope 18 systems in 9 Nos. 4WD DC vehicles; 2 Nos. 15- Seater Bus; 6 Nos. 4WD Vet. Ambulatory vehicle; 2 Nos. SUV for AH 35 Installation of NCDC 1,066 Post Limited RfQ Rated Single No No 18-12- 02-10-19 tracking (HH) Criteria envelope 18 systems in 3 Nos. 4WD DC vehicles; 2 Nos. SUV for HH 36 Support for NCDC 16,393 Post Limited RfQ Rated Single No No 18-12- 02-10-19 Distribution of (AH) 18 13 Office logistic Criteria envelope and Lab. Materials to 37 state, NVRI and 10 VTHs 37 Procurement NCDC 142,043 Post Limited RfQ Rated Single No No 18-12- 02-10-19 of courier (HH) Criteria envelope 18 service logistics for specimen transportation and pre- positioning of supplies 38 Recruitment NCDC 45,246 Post Limited RfQ Rated Single No No 17-09- 01-10-18 of 17 (AH) Criteria envelope 18 contract/ad hoc staff (AH) Total Non- 588,82 Consulting 5 Services Note: Based on Liberia’s specific needs and circumstances, shopping threshold for the purchase of vehicles and fuel may be increased up to US$500,000. Thresholds for Prior Review, Selection Approaches and Methods – Consulting Services Category Prior Review Short List of National Consultants (US$ millions) Consulting Engineering and Construction Supervision Services Consultants (Firms) ≥ 0.5 ≤ 0.1 ≤ 0.2 Individual Consultants ≥ 0.2 n.a. n.a. Note: Consultancy services estimated to cost equivalent to US$ 300,000 and above per contract shall be advertised in the United Nations Development Business (UNDB) online in addition to advertising in national newspaper(s) of wide circulation and/or regional newspaper. XI. Summary of the procurement packages for Consulting Services -Planned for the first 18 months after project effectiveness): 14 Sr. Contract Implem Estimat Revie Market Selection Shortlist Expected Expected No Description enting ed Cost w by Approach Method ing date of date of Agency (US$) Bank (Open - (QCBS, (Yes/ No) bid/ Contract (Prior/ Internation FBS, LCBS, proposal Signature Post) al/ QBS, CQS, opening National/ DS etc.) etc.) 39 Engagement of NCDC 7,026 Post Limited INDV No 15-10-18 29-10-18 Individual Consultants from relevant Sectors to develop a National Strategy for ONE Health and Workforce strategy 40 Recruitment of NCDC 201,836 Prior Open, INDV No 01-10-18 15-10-18 3 Consultants National to support for 12 months to facilitate NCDC-FETP training and lead redesign of the FETP programme 41 Engagement of NCDC 243,934 Prior Open, INDV No 01-10-18 22-10-18 5 Consultants/ National Specialists in relevant Thematic Areas to support Project Implementatio n 42 Consultancy NCDC 197,871 Post Open, CQS No 15-10-18 29-10-18 for Branding National and corporate 15 communication including development of risk communication strategies for the REDISSE project 43 Consultancy to NCDC 66,953 Post Open, CQS No 15-10-18 29-10-18 develop project National website and project intranet including overhaul and upgrade of NCDC website and development of REDISSE webpages 44 Consultancy NCDC 177,540 Post Open, CQS No 18-03-19 01-04-19 for National Establishing, developing, training, and licensing enterprise management of software for Procurement, Audit and Financial management 45 Engagement of NCDC 11,689 Post Limited INDV No 15-10-18 29-10-18 a Consultant to provide Safeguard, Waste Management 16 and Grievance Support 46 Engagement of NCDC 9,797 Post Limited INDV No 20-02-19 06-03-19 2 Individual Consultants to conduct situational analysis and develop a road map for development of laboratory standards 47 Consultancy to NCDC 80,343 Post Open, CQS No 20-02-19 06-03-19 conduct Needs National assessment and consensus building for human and animal health information systems to develop a plan and road map for an interconnected real-time system for human and animal health including a development of a technical plan data systems integration 48 Consultancy NCDC 106,749 Post Open, CQS No 17-04-19 02-05-19 for a National National Public Health Laboratory 17 Needs Assessment 49 Consultancy to NCDC 7,065 post Limited INDV No 20-02-19 06-03-19 develop strategy and training modules on shipment of samples for diagnosis of) zoonotic and epidemic prone diseases 50 Consultancy NCDC 180,343 Post Open, CQS No 17-04-19 02-05-19 for the National assessment of isolation units in all the state capitals in the country to identify gaps compared to global best practice and develop minimum standards for isolation practice 51 Consultancy NCDC 78,220 Post Open, CQS No 17-04-19 02-05-19 for Situational National Analysis and Development of a Multi- hazard Plans 52 Consultancy to NCDC 71,555 Post Open, CQS No 17-04-19 02-05-19 conduct gap National analysis of the existing surveillance 18 system for Transboundary Animal Diseases and zoonotic diseases 53 Consultancy to NCDC 48,355 Post Limited INDV No 15-11-18 29-11-18 conduct the prioritization of TADs and zoonotic diseases. Review and update priority animal diseases TADs 54 Consultancy to NCDC 64,575 Post Open, CQS No 17-04-19 02-05-19 harmonize and National develop guidelines, protocols and tools for animal disease surveillance and disease reporting processes 55 Consultancy to NCDC 14,942 Post Limited INDV No 17-04-19 02-05-19 develop training manual for Surveillance Agents (AH) 56 Consultancy to NCDC 24,104 Post Limited INDV No 17-04-19 02-05-19 identify and develop the GIS Mapping of Hot-spots in human, Wild and Domestic 19 animals interface(AH) 57 Engagement of NCDC 196,721 Post Open, INDV No 15-10-18 29-10-18 25 National Veterinarians as ad hoc staff (AH) 58 Engagement of NCDC 61,967 Post Open, INDV No 15-10-18 29-10-18 10 ad-hoc National Laboratory Scientists at NRL (HH) 59 Consultancy NCDC 56,429 Post Open, CQS No 14-11-18 28-11-18 for re- National assessment of 37 Veterinary Public Health/ Epidemiology offices, preparation of BOQs and Supervision of Rehabilitation 60 Consultancy NCDC 60,656 Post Open, CQS No 14-11-18 28-11-18 for re- National assessment of 37 Isolation Centers, preparation of BOQs and Supervision of renovation Total Consultancy 1,968,6 Services 70 20 Appendix 1 Letter of Acceptance of the World Bank’s Anti-Corruption Guidelines and Sanctions Framework Date: Invitation of Bids/Proposals No.__________ To: ___________________________________________________________________________ We, along with our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not) consultants and personnel, acknowledge and agree to abide by the World Bank’s policy regarding Fraud and Corruption (corrupt, fraudulent, collusive, coercive, and obstructive practices), as set out and defined in the World Bank’s Anti-Corruption Guidelines1 in connection with the procurement and execution of the contract (in case of award), including any amendments thereto. We declare and warrant that we, along our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not), consultants and personnel, , are not subject to, and are not controlled by any entity or individual that is subject to, a temporary suspension, early temporary suspension, or debarment imposed by a member of the World Bank Group, including, inter alia, a cross-debarment imposed by the World Bank Group as agreed with other international financial institutions (including multilateral development banks), or through the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement. Further, we are not ineligible under the laws or official regulations of [Insert name of Employer as per bidding document] or pursuant to a decision of the United Nations Security Council. We confirm our understanding of the consequences of not complying with the World Bank’s Anti-Corruption Guidelines, which may include the following: a. rejection of our Proposal/Bid for award of contract; b. in the case of award, termination of the contract, without prejudice to any other remedy for breach of contract; and c. sanctions, pursuant to the Bank’s Anti-corruption Guidelines and in accordance with its prevailing sanctions policies and procedures as set forth in the Bank’s Sanctions Framework. This may include a public declaration of ineligibility, either indefinitely or for a stated period of time, (i) to be awarded or otherwise benefit from a Bank- financed contract, financially or in any other manner;2 (ii) to be a nominated3 sub- 1Guidelines on Preventing and Combating Fraud and Corruption in Projects Financed by International Bank for Reconstruction and Development Loans and the International Development Agency Credits and Grants, dated October 15, 2006, and revised in January 2011 and July 2016, as they may be revised from time to time. 2 For the avoidance of doubt, a sanctioned party’s ineligibility to be awarded a contract shall include, without limitation, (i) applying for pre-qualification, expressing interest in a consultancy, and bidding, either directly or as a nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider, in respect of such contract, and (ii) entering into an addendum or amendment introducing a material modification to any existing contract. 21 contractor, consultant, manufacturer or supplier, or service provider of an otherwise eligible firm being awarded a Bank-financed contract; and (iii) to receive the proceeds of any loan made by the Bank or otherwise to participate further in the preparation or implementation of any Bank-financed project. We understand that we may be declared ineligible as set out above upon: a. completion of World Bank Group sanctions proceedings according to its prevailing sanctions procedures; b. cross-debarment as agreed with other international financial institutions (including multilateral development banks); c. the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement; or d. temporary suspension or early temporary suspension in connection with an ongoing World Bank Group sanctions proceeding. For avoidance of doubt, the foregoing effects of ineligibility do not extend to a sanctioned firm’s or individual’s execution of its ongoing Bank-financed contracts (or its ongoing sub-agreements under such contracts) that are not the subject of a material modification, as determined by the Bank. We shall permit, and shall cause our sub-contractors, sub-consultants, agents (whether declared or not), personnel, consultants, service providers or suppliers, to permit the Bank to inspect4 all accounts, records, and other documents relating to the procurement process and/or contract execution (in the case of award), and to have them audited by auditors appointed by the Bank. We agree to preserve all accounts, records, and other documents (whether in hard copy or electronic format) related to the procurement and execution of the contract. Name of the Bidder/Consultant: Name of the person duly authorized to sign the Bid/Proposal on behalf of the Bidder/Consultant: 3 A nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider (different names are used depending on the particular bidding document) is one which has been: (i) included by the bidder in its pre-qualification application or bid because it brings specific and critical experience and know-how that allow the bidder to meet the qualification requirements for the particular bid; or (ii) appointed by the Borrower. 4 Inspections in this context are usually investigative (i.e., forensic) in nature: they involve fact-finding activities undertaken by the Bank or persons appointed by the Bank to address specific matters related to investigations/audits, such as evaluating the veracity of an allegation of possible Fraud and Corruption, through the appropriate mechanisms. Such activity includes but is not limited to accessing and examining a firm's or individual's financial records and information, and making copies thereof as relevant; accessing and examining any other documents, data, and information (whether in hard copy or electronic format) deemed relevant for the investigation/audit, and making copies thereof as relevant; interviewing staff and other relevant individuals; performing physical inspections and site visits; and obtaining third-party verification of information. 22 Title of the person signing the Letter: 23 PROCUREMENT Western and Central Africa : Regional Disease Surveillance Systems Enhancement (REDISSE) Phase II PLAN General Information Country: Western and Central Africa 2018-04-19 Bank’s Approval Date of the Original Procurement Plan: 2023-06-05 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P159040 GPN Date: Project Name: Regional Disease Surveillance Systems Enhancement (REDISSE) Phase II Loan / Credit No: IDA / 59690, IDA / 59680 Ministry of Health and Social Welfare Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned LR-MOHSW-96574-CW-FCA / Component 2: Strengthening Request for Quota Single Stage - One E 2020-04-2 Rehabilitate REDISSE Project IDA / 59690 Post Limited 217,718.31 210,513.41 Completed 2019-09-04 2019-05-09 2019-10-30 2019-06-20 of Laboratory Capacity tions nvelope 7 Staff Office Space/One Healt h LR-MOHSW-96575-CW-FCA / Component 2: Strengthening Pending Imp 2020-03-0 IDA / 59690 Post Force Account Direct 72,388.73 0.00 2019-07-31 2019-08-05 2019-09-09 Rehabilitation of Biomedical of Laboratory Capacity lementation 7 workshop LR-MOHSW-198580-CW-RFQ / Rehabilitation of the Nation al Public Health Reference La Component 2: Strengthening Request for Quota Single Stage - One E 2021-02-1 IDA / 59690 Post Limited 48,956.77 0.00 Canceled 2020-10-19 2020-10-20 2020-12-14 boratory to ensure Biosafety of Laboratory Capacity tions nvelope 2 and Biosecurity of equipment and results linked to testing s amples. LR-MOHSW-295659-CW-RFQ Request for Quota / Renovation of the National Component 2: Strengthening Request for Quota Single Stage - One E Under Imple 2023-02-1 IDA / 59690 Post Limited tions (Non Bank-S 30,000.00 0.00 2022-06-27 2022-11-08 2022-08-22 Reference Laboratory wareh of Laboratory Capacity tions nvelope mentation 8 PD) ouse facility at Charlesville, Margibi County LR-MOHSW-295673-CW-RFQ / Procurement for the provisi on of construction and install Request for Quota ation of a bole hole including Component 2: Strengthening Request for Quota Single Stage - One E Under Imple 2023-02-1 IDA / 59690 Post Limited tions (Non Bank-S 20,000.00 0.00 2022-06-25 2022-11-08 2022-08-20 water tower system with 500 of Laboratory Capacity tions nvelope mentation 6 PD) gallons tank to support wate r supply at Center Veterinary Laboratory of Ministry of Agri culture, Fendell LR-MOHSW-360816-CW-RFQ / Rehabiliation and upgrading Request for Quota of the Molecular Laboratory t Component 2: Strengthening Request for Quota Single Stage - One E Pending Imp 2023-08-3 IDA / 59690 Post Limited tions (Non Bank-S 61,986.34 0.00 2023-05-17 2023-07-12 o include sequencing at the of Laboratory Capacity tions nvelope lementation 1 PD) National Reference laborator y, at Charlesville, Margibi Co unty. GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual LR-MOHSW-56358-GO-RFQ / Component 2: Strengthening Single Stage - One E Procurement & installation of IDA / 59690 Prior Request for Bids Open - National 162,500.00 0.00 Canceled 2018-10-15 2018-10-20 2018-12-01 2018-12-31 2019-02-04 2019-08-03 of Laboratory Capacity nvelope solar panels LR-MOHSW-56363-GO-RFB / Component 2: Strengthening Single Stage - One E Procurement of laboratory e IDA / 59690 Post Request for Bids Open - National 102,350.00 0.00 Canceled 2018-05-10 2018-05-15 2018-06-26 2018-07-26 2018-08-30 2019-02-26 of Laboratory Capacity nvelope quipment for Biomedical tech inicans LR-MOHSW-56385-GO-RFQ / Component 2: Strengthening Request for Quota Single Stage - One E Procurement of ICT equipme IDA / 59690 Post Open - National 4,380.00 0.00 Canceled 2018-12-25 2019-02-19 2019-08-18 of Laboratory Capacity tions nvelope nt for Biomedical warehouse technicians LR-MOHSW-56414-GO-RFQ / Component 5: Institutional C Procurement of ICT equipme apacity Building, Project Ma Request for Quota Single Stage - One E Under Imple nt ( laptops, desktop, printer, IDA / 59690 Post Open - National 48,800.00 0.00 2018-08-20 2018-10-15 2019-04-13 nagement, Coordination and tions nvelope mentation scanners, cameras, smart ph Advocacy ones, photocopies) for centra l level PCU LR-MOHSW-56405-GO-RFQ / Component 1: Surveillance a Request for Quota Single Stage - One E Under Imple Procurement of motor bikes f IDA / 59690 Post Open - National 450,000.00 0.00 2018-08-18 2018-10-13 2019-04-11 nd Information Systems tions nvelope mentation or district & Counties surveill ance officers LR-MOHSW-56329-GO-RFQ / Component 2: Strengthening Request for Quota Single Stage - One E Under Imple Procurement of vehicles for IDA / 59690 Post Open - National 295,000.00 0.00 2018-08-11 2018-10-06 2019-04-04 of Laboratory Capacity tions nvelope mentation NPHIL and MOA LR-MOHSW-91256-GO-RFB / Component 5: Institutional C Request for Quota Single Stage - One E Pending Impl Procurement of ICT Equipme IDA / 59690 apacity Building, Project Ma Post Limited 138,058.00 0.00 2019-02-11 2019-04-08 2019-10-05 tions nvelope ementation nt for central and counties le nagement, Coordination and vel Advocacy LR-MOHSW-96565-GO-RFQ / Component 2: Strengthening Request for Quota Single Stage - One E Under Imple Procure 15 motorcycles for C IDA / 59690 Post Limited 80,250.00 0.00 2019-06-03 2018-08-13 2019-07-29 2020-01-25 of Laboratory Capacity tions nvelope mentation ounties Diagnostic Officers LR-MOHSW-96567-GO-RFQ / Procure ICT Equipment and s Component 1: Surveillance a Request for Quota Single Stage - One E IDA / 59690 Post Limited 104,550.00 0.00 Canceled 2019-06-04 2019-07-30 2020-01-26 upplies for NPHIL/MOH counti nd Information Systems tions nvelope es and Districts Surveillance Officers LR-MOHSW-96571-GO-RFQ / Procurement of reagents and Component 2: Strengthening Request for Quota Single Stage - One E IDA / 59690 Post Limited 169,545.00 0.00 Canceled 2019-06-12 2019-08-07 2020-02-03 test kits for National Referen of Laboratory Capacity tions nvelope ce and Regional Laboratory LR-MOHSW-96576-GO-RFQ / Procurement of Office Equip Component 2: Strengthening Request for Quota Single Stage - One E IDA / 59690 Post Limited 29,240.00 27,023.50 Completed 2019-08-04 2020-01-20 2019-09-29 2020-04-08 2020-03-27 2020-08-05 ment and Furniture for REDIS of Laboratory Capacity tions nvelope SE Office/One Health Page 1 LR-MOHSW-56391-GO-RFQ / Component 4: Human Resou procurement of ICT equipme rce Management for Effectiv Request for Quota Single Stage - One E IDA / 59690 Post Open - National 37,200.00 0.00 Canceled 2019-08-05 2019-09-30 2020-03-28 nt for (FETP-V & MPH) of the e Disease Surveillance and E tions nvelope University of Liberia pidemic Preparedness LR-MOHSW-56396-GO-RFQ / Procurement of ICT equipme Component 1: Surveillance a Request for Quota Single Stage - One E IDA / 59690 Post Open - National 89,250.00 0.00 Canceled 2019-07-03 2019-08-28 2020-02-24 nt ( laptops & Desktops) for d nd Information Systems tions nvelope istrict surveillance officer- ani mal & human LR-MOHSW-91259-GO-RFB / Procurement of motorcycles f Component 2: Strengthening Single Stage - One E Pending Impl IDA / 59690 Post Request for Bids Limited 450,000.00 0.00 2019-03-29 2019-04-03 2019-05-15 2019-06-14 2019-07-19 2020-01-15 or District Animal Surveillanc of Laboratory Capacity nvelope ementation e and Health Surveillance Off icers LR-MOHSW-122593-GO-RFQ / procure reagent & materials to conduct AMR Detection, c Component 3: Preparedness Request for Quota Single Stage - One E haracterization and antimicro IDA / 59690 Post Limited 20,042.41 19,944.82 Completed 2019-07-19 2019-07-19 2019-09-13 2019-10-10 2020-03-11 2019-12-10 and Emergency Response tions nvelope bial resistance pattern of pat hogenic enteric bacteria asso ciated with paediatric gastro enteritis in Monsterrado coun ty. Liberia LR-MOHSW-135173-GO-RFQ / Support to ECO Central and Counties level through purch Component 3: Preparedness Request for Quota Single Stage - One E IDA / 59690 Post Open - National 32,475.00 25,168.00 Completed 2019-10-01 2019-11-26 2019-12-05 2019-12-25 2019-12-17 ase of ICT supplies, Furniture and Emergency Response tions nvelope and Fixture (eg. printer, proj ector, TV monitor, chairs and desks) LR-MOHSW-135180-GO-RFQ / Support to disease surveilla Component 1: Surveillance a Request for Quota Single Stage - One E IDA / 59690 Post Open - National 3,000.00 0.00 Canceled 2019-10-08 2019-12-03 2020-01-02 nce interoperable reporting s nd Information Systems tions nvelope ystems (Roll out eIDSR) LR-MOHSW-96569-GO-RFQ / Procure and Install solar pan Component 2: Strengthening Request for Quota Single Stage - One E IDA / 59690 Post Limited 101,250.00 0.00 Canceled 2020-02-29 2020-04-25 2020-05-25 els for the storage of sample of Laboratory Capacity tions nvelope s at selected health facilities LR-MOHSW-163505-GO-RFB / Purchase of reagents and te Component 2: Strengthening Single Stage - One E IDA / 59690 Post Request for Bids Open - National 398,440.00 0.00 Canceled 2020-03-16 2020-03-21 2020-05-02 2020-06-01 2020-07-06 2020-09-04 st kits for the National Refere of Laboratory Capacity nvelope nce and Regional Laboratorie s (NRL and others) LR-MOHSW-167819-GO-RFQ / Purchase of assorted labora Component 2: Strengthening Request for Quota Single Stage - One E tory supplies and reagent, an IDA / 59690 Post Limited 139,215.00 139,051.47 Completed 2020-04-14 2020-04-07 2020-06-09 2020-05-04 2020-06-21 2020-09-18 of Laboratory Capacity tions nvelope d sample collection materials under Laboratory Services LR-MOHSW-169547-GO-RFQ / Printing of assorted Awaren ess Jacket/vest with wording Component 3: Preparedness Request for Quota Single Stage - One E IDA / 59690 Post Limited 13,300.00 10,640.00 Completed 2020-05-02 2020-04-29 2020-06-27 2020-06-13 2020-07-04 2020-06-30 Community Response 1220 p and Emergency Response tions nvelope ieces & Rapid Response 100 pieces for Operations & Coun ty Services LR-MOHSW-169940-GO-RFQ / Purchase of Assorted Medic al & Non-Medical Supplies for WASH & Dead Body Manage Component 3: Preparedness Request for Quota Single Stage - One E ment: PPE suits - IDA / 59690 Post Limited 265,190.00 265,023.66 Completed 2020-04-22 2020-04-17 2020-06-17 2020-05-26 2020-07-01 2020-05-31 and Emergency Response tions nvelope Assorted Biohazard bags, bo dy bags, buckets Examination Gloves; Infrared forehead thermomet er; etc LR-MOHSW-169927-GO-RFQ / Purchase of Assorted Medic al Materials for Logistic & Op erations: Gloves: Examinatio n, assorted sizes (S, M, L, XL) Component 3: Preparedness Request for Quota Single Stage - One E IDA / 59690 Post Limited 35,325.00 144,247.50 Completed 2020-04-13 2020-04-08 2020-06-08 2020-05-05 2020-06-22 2020-05-27 and Emergency Response tions nvelope Thermometer: Infrared, Non- contact Forehead Chlorine: 99% mirco bacteria ; Face shield: Transparent pet anti-virus etc. LR-MOHSW-171297-GO-UN / Procurement of 5 ambulance Component 3: Preparedness UN Agencies (Dire IDA / 59690 Post Direct 300,000.00 290,074.00 Completed 2020-03-23 2020-04-04 2020-03-28 2020-04-22 2020-05-02 2020-04-30 2020-10-29 2020-06-17 to support counties in respon and Emergency Response ct) se mode for Prepareness & R esponse LR-MOHSW-171857-GO-RFQ / Printing of assorted materia ls: 1142 copies -job aides co pies, 1150 booklets -training Component 3: Preparedness Request for Quota Single Stage - One E materials for participate and IDA / 59690 Post Limited 12,888.00 20,866.00 Completed 2020-05-09 2020-05-12 2020-07-04 2020-06-24 2020-07-16 2020-07-14 and Emergency Response tions nvelope 27 booklets for faciliator guid es to train community animal health workers to support cro ss broader surveillance for C OVID-19 response. LR-MOHSW-169551-GO-RFQ / Purchase of 1-unit Projector Component 3: Preparedness Request for Quota Single Stage - One E IDA / 59690 Post Limited 1,900.00 1,884.00 Completed 2020-05-02 2020-04-29 2020-06-27 2020-06-13 2020-07-11 2020-07-14 , 2 -Projector Pointer, 1 Printe and Emergency Response tions nvelope r for Operations & County Se rvices LR-MOHSW-176426-GO-RFQ / Purchase of assorted Labor atories equipment and Suppli Component 2: Strengthening Request for Quota Single Stage - One E IDA / 59690 Post Limited 1,257,000.00 0.00 Canceled 2020-06-07 2020-08-02 2020-10-31 es to increase PCR Machine t of Laboratory Capacity tions nvelope esting and other supplies as support to Laboratory Servic es. LR-MOHSW-181532-GO-RFQ / Printing of COVID-19 Interi Component 3: Preparedness Request for Quota Single Stage - One E IDA / 59690 Post Limited 7,000.00 2,366.00 Completed 2020-06-30 2020-06-30 2020-08-25 2020-07-23 2020-09-24 2020-08-09 m Guide, Patient Flow Chart and Emergency Response tions nvelope and SOPs for Case Managem ent Page 2 LR-MOHSW-184752-GO-RFQ / Printing and distribution of awareness materials (Flyers, Bumper Stickers, Brochures Component 3: Preparedness Request for Quota Single Stage - One E IDA / 59690 Post Limited 18,935.00 6,437.28 Completed 2020-07-27 2021-01-19 2020-09-21 2021-03-17 2020-10-21 2021-04-30 and posters) for 6 affected C and Emergency Response tions nvelope ounties with Lassa Fever (Mo ntserrado, Margibi, Bong, lof a, Grand Bassa and Nimba) u nder the Lassa Fever Emerge ncy Response. LR-MOHSW-187106-GO-RFQ / Printing of assorted IEC/Bcc materials for nationwide soci al mobilization community ou Component 3: Preparedness Request for Quota Single Stage - One E Under Imple IDA / 59690 Post Limited 93,000.00 0.00 2020-08-12 2020-09-28 2020-10-07 2020-11-06 treach and awareness linked and Emergency Response tions nvelope mentation to prevention of COVID-19 in Liberia. These include: poster for hand washing, poster for traveler, bill board, flyers, etc . LR-MOHSW-187265-GO-UN / Purchase of Xpert Xpress SA Component 2: Strengthening UN Agencies (Dire RS-COV-2 Cartridges (PCR M IDA / 59690 Post Direct 931,625.00 0.00 Canceled 2020-06-15 2020-06-20 2020-07-25 2020-10-23 of Laboratory Capacity ct) achine Cartridge) and other Consumables through WHO f or the Laboratory Pillar LR-MOHSW-218929-GO-RFQ / Purchase of Assorted ICT Eq uipment for the National Acti on accelerated response to L Component 3: Preparedness Request for Quota Single Stage - One E IDA / 59690 Post Limited 5,000.00 0.00 Canceled 2021-02-22 2021-04-19 2021-05-19 assa fever outbreak. and Emergency Response tions nvelope 1 - pc -High speed Printer wit h 3 pcs spare cartridges, 1 - pc - Projector 2 - Pcs - Laptop computer LR-MOHSW-227323-GO-RFQ / Purchase of 4 pieces of Lapt Component 5: Institutional C ops and 2 units of Desktops c apacity Building, Project Ma Request for Quota Single Stage - One E omputers for use by staff of t IDA / 59690 Post Limited 13,500.00 8,894.00 Completed 2021-04-11 2021-05-27 2021-06-06 2021-07-07 2021-08-05 2021-07-21 nagement, Coordination and tions nvelope he COVID-19 & REDISSE Proj Advocacy ects and one desktop to be u se as server for internal netw orking purposes. LR-MOHSW-227419-GO-RFQ / Printing of Dog Vaccination certificates for the 15 Counti Component 3: Preparedness Request for Quota Single Stage - One E IDA / 59690 Post Limited 10,000.00 10,000.00 Completed 2021-04-11 2021-04-27 2021-06-06 2021-07-17 2021-07-06 2021-07-24 es to support routine dog vac and Emergency Response tions nvelope cination to prevent rabies an d create awareness campaig n LR-MOHSW-238593-GO-RFQ / Procurement of Internal ICT Infrastructural Network Instal lation Materials for the REDIS Component 5: Institutional C SE-II Project/One Health Build apacity Building, Project Ma Request for Quota Single Stage - One E ing conference room. IDA / 59690 Post Limited 8,000.00 5,995.00 Completed 2021-06-19 2021-06-25 2021-08-14 2021-09-10 2021-09-13 2022-01-06 nagement, Coordination and tions nvelope Lot#: 1 ICT Equip. Advocacy Network access storage drive & laptop computer Lot#: 2 Office Equip. 65" TV, Camera &streamin LR-MOHSW-295490-GO-RFQ / Procurement of 10 motor bi Component 1: Surveillance a Request for Quota Single Stage - One E Under Imple kes for District Surveillance O IDA / 59690 Post Limited 45,000.00 0.00 2022-05-29 2022-08-02 2022-07-24 2023-01-20 nd Information Systems tions nvelope mentation fficer under NPHIL as additio nal logistics needed to streng then Surveillance. LR-MOHSW-295496-GO-RFQ / Procurement of Assorted Ve Component 1: Surveillance a Request for Quota Single Stage - One E Pending Impl terinary kits/package for 260 IDA / 59690 Post Limited 20,850.00 0.00 2022-06-04 2022-07-30 2023-01-26 nd Information Systems tions nvelope ementation community animal health wo rkers (CAHWs) for MoA LR-MOHSW-295589-GO-RFQ / Procurement of Assorted Ict & Office Equipment and Fixt Component 1: Surveillance a Request for Quota Single Stage - One E Under Imple IDA / 59690 Post Limited 80,730.00 0.00 2022-05-31 2022-06-01 2022-07-26 2023-01-22 ures for use by MOA - Lab & nd Information Systems tions nvelope mentation EPi Unit, REDISSE-II Coordina tion office & Risk communica tion. LR-MOHSW-295651-GO-RFQ Component 2: Strengthening Request for Quota Single Stage - One E Pending Impl / Printing of assorted Laborat IDA / 59690 Post Limited 7,800.00 0.00 2022-06-11 2022-08-06 2022-11-04 of Laboratory Capacity tions nvelope ementation ory Regulation Standards. LR-MOHSW-295666-GO-RFB / Procurement of assorted La boratory reagents, equipmen t, supplies and consumables Component 2: Strengthening Single Stage - One E Under Imple for the National Reference La IDA / 59690 Post Request for Bids Open - National 655,038.93 0.00 2022-07-01 2023-01-10 2022-07-06 2023-01-11 2022-08-17 2022-09-16 2022-10-21 2023-04-19 of Laboratory Capacity nvelope mentation b-NPHIL, EPA Laboratory, and the Central Veterinary Labor atory of the Ministry of Agric ulture for strengthening of th e laboratory systems. LR-MOHSW-295816-GO-RFQ Component 3: Preparedness Request for Quota Single Stage - One E / Procurement of Human Rabi IDA / 59690 Post Limited 70,610.00 68,113.60 Signed 2022-06-20 2022-08-01 2022-08-15 2022-09-07 2023-02-11 and Emergency Response tions nvelope es vaccine and assorted cons umables. LR-MOHSW-295826-GO-RFQ / Procurement of assorted off Component 5: Institutional C road vehicles and buses for t apacity Building, Project Ma Request for Quota Single Stage - One E Under Imple IDA / 59690 Post Limited 405,000.00 0.00 2022-06-05 2022-07-22 2022-07-31 2023-01-27 he Ministry of Agriculture, NP nagement, Coordination and tions nvelope mentation HIL and the Project Coordinat Advocacy ion Unit (PCU). 5 units SUV of f road Jeeps and 2 units bus es LR-MOHSW-307604-GO-RFQ / Printing of 505 pieces of foo Component 3: Preparedness Request for Quota Single Stage - One E Under Imple d safety brochure for Lassa F IDA / 59690 Post Limited 1,720.00 0.00 2022-08-13 2022-08-17 2022-10-08 2023-01-06 and Emergency Response tions nvelope mentation ever affected Counties. Bong , Grand Bassa, Nimba, Margi bi and Montserrado Counties LR-MOHSW-359462-GO-RFQ / Procurement of 3 units of of Component 5: Institutional C f road vehicles: two (2) for N apacity Building, Project Ma Request for Quota Single Stage - One E Pending Impl PHIL to faciliate supervision a IDA / 59690 Post Limited 151,650.00 0.00 2023-05-10 2023-07-05 2023-08-31 nagement, Coordination and tions nvelope ementation ctivities for Emergency Prepa Advocacy redness and Reponse across the Country & one (1) for PF MU to enhance its operationa l efficiency. Page 3 LR-MOHSW-359463-GO-RFQ / Procurement of assorted IC Component 5: Institutional C T equipment: 2 units Laptop apacity Building, Project Ma Request for Quota Single Stage - One E Pending Impl s for laboratories of CVL & Ga IDA / 59690 Post Limited 8,250.00 0.00 2023-05-08 2023-07-03 2023-08-31 nagement, Coordination and tions nvelope ementation nta for MOA, 15 pcs anti viru Advocacy s licenses for staff laptops, 3 projectors & pointers and 1 U PS for use by the REDISSE-II project LR-MOHSW-359478-GO-RFQ / Printing of 50 copies of Inter Component 1: Surveillance a Request for Quota Single Stage - One E Pending Impl grate disease survillance and IDA / 59690 Post Limited 800.00 0.00 2023-05-09 2023-07-04 2023-08-29 nd Information Systems tions nvelope ementation response 2nd edition docum ents for the Ministry of Agric uulture. LR-MOHSW-363725-GO-RFQ / Procurement of High Qualit y recent Laptop for County S urveillance Team: 55 Pueces Component 5: Institutional C 1. EOC Coordinators - 15 apacity Building, Project Ma Request for Quota Single Stage - One E Pending Impl 2. Environmental Health Tec IDA / 59690 Post Limited 96,250.00 0.00 2023-05-31 2023-07-26 2023-08-31 nagement, Coordination and tions nvelope ementation hnicians - 15 Advocacy 3. Laboratory Diagnostic Offi cers - 15 4. Central-Level environment s Health Officers - 10 LR-MOHSW-363722-GO-RFQ / Procurement of the purchas Component 5: Institutional C e assorted transport equime apacity Building, Project Ma Request for Quota Single Stage - One E Pending Impl IDA / 59690 Post Limited 151,650.00 0.00 2023-05-31 2023-07-26 2023-08-31 nt: nagement, Coordination and tions nvelope ementation 1. 3 Units off road Jeeps for N Advocacy ational Surveillance Program s (2 NPHIL Lab & ESS, 1 MOA Lab) LR-MOHSW-365248-GO-RFQ Component 5: Institutional C / Procurement of 55 Units of apacity Building, Project Ma Request for Quota Single Stage - One E Pending Impl IDA / 59690 Post Limited 261,650.00 0.00 2023-06-11 2023-08-06 2023-08-31 rough terrine motobikes for S nagement, Coordination and tions nvelope ementation urviellance staff at NPHIL & Advocacy MOH NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual LR-MOHSW-56332-NC-RFQ / Printing of SOP for animals w Component 1: Surveillance a Request for Quota Single Stage - One E IDA / 59690 Post Open - National 31,350.00 0.00 Canceled 2018-04-15 2018-06-10 2018-12-07 orkers, technical training ma nd Information Systems tions nvelope uls, data collection tools, ass essment tools, etc. Component 4: Human Resou LR-MOHSW-56348-NC-RFQ / rce Management for Effectiv Request for Quota Single Stage - One E Printing of training materials IDA / 59690 Post Open - National 4,500.00 0.00 Canceled 2018-04-15 2018-06-10 2018-12-07 e Disease Surveillance and E tions nvelope for front line Vet. pidemic Preparedness LR-MOHSW-56346-NC-RFQ / Component 3: Preparedness Request for Quota Single Stage - One E printing of materials for inter IDA / 59690 Post Open - National 3,450.00 0.00 Canceled 2018-10-23 2018-12-18 2019-06-16 and Emergency Response tions nvelope national one health day awar eness LR-MOHSW-56342-NC-RFQ / Printing of SOP of laboratory Component 2: Strengthening Request for Quota Single Stage - One E IDA / 59690 Post Open - National 6,250.00 0.00 Canceled 2019-07-02 2019-08-27 2020-02-23 quality management system of Laboratory Capacity tions nvelope s, harmonized data collection tools LR-MOHSW-56349-NC-RFQ / Component 5: Institutional C Request for Quota Single Stage - One E printing & publications for pr IDA / 59690 apacity Building, Project Ma Post Open - National 5,000.00 0.00 Canceled 2019-10-02 2019-11-27 2020-05-25 tions nvelope oject visibility nagement, Coordination and Advocacy LR-MOHSW-135170-NC-RFQ / Print and distribute develop ed training modules includin Component 1: Surveillance a Request for Quota Single Stage - One E IDA / 59690 Post Open - National 13,500.00 13,152.10 Completed 2019-09-30 2019-11-25 2019-11-27 2019-11-29 2019-12-14 g job aides, data collection to nd Information Systems tions nvelope ols for 2 hundred community animal health worker in Liber ia LR-MOHSW-135177-NC-RFQ / Support to rabies vaccinatio Component 3: Preparedness Request for Quota Single Stage - One E IDA / 59690 Post Open - National 7,850.00 1,655.00 Completed 2019-09-29 2019-11-24 2019-10-23 2019-12-23 2019-10-26 n and awareness campaign d and Emergency Response tions nvelope uring World Rabies Day LR-MOHSW-167769-GO-RFQ / Printing of assorted fact she Component 3: Preparedness Request for Quota Single Stage - One E et & bill boards for health pro IDA / 59690 Post Limited 20,000.00 18,400.00 Completed 2020-04-13 2020-04-06 2020-06-08 2020-04-16 2020-06-21 2020-05-08 and Emergency Response tions nvelope motion materials across targ eted communities under Risk Communication LR-MOHSW-167797-NC-RFQ / Printing of assorted training materials: SOPs/ booklet, SO Ps to frontline health workers Component 1: Surveillance a Request for Quota Single Stage - One E IDA / 59690 Post Limited 78,000.00 0.00 Canceled 2020-04-15 2020-06-10 2020-06-22 , 2000 copies of COVID-19 da nd Information Systems tions nvelope ta collection and reporting to ols, 1500 copies of job aides for use by EPi Surveillance, C oordination and point of entr y LR-MOHSW-179942-NC-DIR / Hiring of LoneStar Communic ation Corporation (LCC MTN) Component 3: Preparedness IDA / 59690 Post Direct Selection Direct 76,200.00 59,760.00 Signed 2020-06-16 2020-06-02 2020-06-21 2020-08-12 2020-07-26 2022-04-08 2021-07-21 to provide internet services t and Emergency Response o the 15 Counties Emergency Operation Centers (EOC) for a period of 1 year. LR-MOHSW-179943-NC-DIR / Hiring of Liberia Telecommun ications Corporation (LIBTELC Component 3: Preparedness O) for high spee.d internet fo IDA / 59690 Post Direct Selection Direct 42,000.00 49,860.00 Signed 2020-06-17 2020-06-02 2020-06-22 2021-06-29 2020-07-27 2022-01-25 2021-07-22 and Emergency Response r the National EOC located at the National Public Health Ins titution of Liberia (NPHIL) for the period of 1 year. LR-MOHSW-295879-NC-RFQ Component 5: Institutional C / Hiring of firm to develop an apacity Building, Project Ma Request for Quota Single Stage - One E Pending Impl IDA / 59690 Post Limited 1,950.00 0.00 2022-06-28 2022-08-23 2023-08-23 d host project website for pro nagement, Coordination and tions nvelope ementation ject visibility for a period 1 y Advocacy ear. Page 4 LR-MOHSW-295663-NC-DIR / Procurement of Internet Con nectivity at 3 locations, the E pi Unit - MOA, Central Veterin Component 1: Surveillance a Pending Impl IDA / 59690 Post Direct Selection Direct 68,600.00 0.00 2022-06-23 2022-06-28 2022-08-02 2023-08-02 ary Lab- MOA and One Healt nd Information Systems ementation h Building through direct sele ction to Liberia Telecommuni cation Cooperation (LTC-Mobi le) for the period of 1 year. CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual LR-MOHSW-132375-CS-FBS / hiring a Individual consultant to conduct AMR Integrated K Component 3: Preparedness Fixed Budget Sele IDA / 59690 Post Open - National 18,000.00 0.00 Canceled 2019-09-12 2019-09-03 2019-10-03 2019-11-16 2019-12-14 2020-01-13 2020-02-17 2020-03-23 2020-07-03 nowledge, attitude and practi and Emergency Response ction ce (KAP) behavior survey to g uide training and education INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual LR-MOHSW-56441-CS-CDS / Component 5: Institutional C Procurement of National Tec IDA / 59690 apacity Building, Project Ma Prior Direct Selection Direct 48,000.00 0.00 Canceled 2018-04-05 2018-04-27 2018-04-15 2018-04-20 2018-06-19 2018-12-16 hnical Coordinator (REDISSE) nagement, Coordination and Advocacy LR-MOHSW-56443-CS-INDV / Component 5: Institutional C Individual Consult Recruitment of Program Assi IDA / 59690 apacity Building, Project Ma Post Open 12,000.00 0.00 Canceled 2018-04-20 2018-05-07 2018-06-08 2018-06-29 2018-08-03 2019-07-29 ant Selection stant (support Central level c nagement, Coordination and oordination) Advocacy LR-MOHSW-56447-CS-CDS / Component 5: Institutional C Recruitment of Project Accou IDA / 59690 apacity Building, Project Ma Prior Direct Selection Direct 18,000.00 0.00 Canceled 2018-04-20 2018-05-15 2018-04-30 2018-07-04 2019-06-29 nt Assistant (PFMU) nagement, Coordination and Advocacy LR-MOHSW-56450-CS-CDS / Component 5: Institutional C Under Implement Recruitment of Project Accou IDA / 59690 apacity Building, Project Ma Prior Direct Selection Direct 30,000.00 0.00 2018-04-20 2018-05-22 2018-04-30 2018-07-04 2019-06-29 ation ntant nagement, Coordination and Advocacy LR-MOHSW-56457-CS-INDV / Component 5: Institutional C Individual Consult Recruitment of 2 Liaison Offic IDA / 59690 apacity Building, Project Ma Post Open 60,000.00 6,070.00 Signed 2018-04-20 2018-05-07 2018-06-08 2018-12-27 2018-06-29 2018-12-31 2018-08-03 2019-01-08 2019-07-29 ant Selection er (for MOH/NPHIL & MOA) nagement, Coordination and Advocacy LR-MOHSW-56461-CS-CQS / Component 5: Institutional C Individual Consult Under Implement Recruitment of Internal Audit IDA / 59690 apacity Building, Project Ma Post Open 30,000.00 0.00 2018-04-20 2018-05-07 2018-06-08 2018-06-29 2018-08-03 2019-07-29 ant Selection ation or Support to Central Manage nagement, Coordination and ment Advocacy LR-MOHSW-56467-CS-INDV / Component 5: Institutional C Recruitment of consultant to apacity Building, Project Ma Individual Consult IDA / 59690 Post Open 48,000.00 0.00 Canceled 2018-09-19 2018-11-07 2018-11-28 2019-01-02 2019-02-01 revise national public health l nagement, Coordination and ant Selection aw to incorporate one health Advocacy framework Component 4: Human Resou LR-MOHSW-56545-CS-INDV / rce Management for Effectiv Individual Consult Recruit one M&E Officer (MO IDA / 59690 Post Open 18,000.00 0.00 Canceled 2018-04-20 2018-05-07 2018-06-08 2018-06-29 2018-08-03 2019-07-29 e Disease Surveillance and E ant Selection A) pidemic Preparedness Component 4: Human Resou LR-MOHSW-56548-CS-INDV / rce Management for Effectiv Individual Consult Recruitment of Surveillance IDA / 59690 Post Open 7,200.00 0.00 Canceled 2018-04-20 2018-05-07 2018-06-08 2018-06-29 2018-08-03 2019-07-29 e Disease Surveillance and E ant Selection Officer (Central and MOA) pidemic Preparedness LR-MOHSW-56549-CS-INDV / Component 4: Human Resou Recruit 8 Animal Diseases Su rce Management for Effectiv Individual Consult Under Implement IDA / 59690 Post Open 28,800.00 0.00 2018-04-20 2018-05-07 2018-06-08 2018-06-29 2018-08-03 2019-07-29 rveillance Officers for eight c e Disease Surveillance and E ant Selection ation ounties (MOA) pidemic Preparedness Component 4: Human Resou LR-MOHSW-56551-CS-INDV / rce Management for Effectiv Individual Consult Recruit 8 counties Level REDI IDA / 59690 Post Open 48,000.00 0.00 Canceled 2018-04-20 2018-05-07 2018-06-08 2018-06-29 2018-08-03 2019-07-29 e Disease Surveillance and E ant Selection SSE Project Focal Persons pidemic Preparedness LR-MOHSW-56557-CS-INDV / Recruitment of consultant to Component 1: Surveillance a Individual Consult IDA / 59690 Post Open 23,500.00 0.00 Canceled 2018-08-15 2018-10-03 2018-10-24 2018-11-28 2019-01-07 develop surveillance training nd Information Systems ant Selection module for Zoonotic LR-MOHSW-56559-CS-INDV / Recruitment consultant to c Component 1: Surveillance a Individual Consult onduct comprehensive livest IDA / 59690 Post Open 45,000.00 0.00 Canceled 2018-06-08 2018-10-25 2018-07-27 2018-08-17 2018-09-21 2018-10-31 nd Information Systems ant Selection ock census for animal move ment (dogs, cats and wide lif e) LR-MOHSW-56469-CS-INDV / Component 4: Human Resou Recruitment to conduct need rce Management for Effectiv Individual Consult IDA / 59690 Post Open 29,500.00 0.00 Canceled 2018-08-06 2018-09-25 2018-09-24 2019-08-27 2018-10-15 2018-11-19 2018-12-10 assessment for public health e Disease Surveillance and E ant Selection workforce strategy developm pidemic Preparedness ent LR-MOHSW-56554-CS-INDV / Recruitment of consultant to Component 3: Preparedness Individual Consult develop national case manag IDA / 59690 Post Open 45,000.00 0.00 Canceled 2018-08-15 2018-09-25 2018-10-03 2019-08-26 2018-10-24 2018-11-28 2019-01-07 and Emergency Response ant Selection ement -isolated unit guidelin e (human health and animal f or quarantine centers) LR-MOHSW-56553-CS-INDV / Consultancy to develop stan dardized training package for Component 3: Preparedness Individual Consult contact tracers or community IDA / 59690 Post Open 42,500.00 0.00 Canceled 2018-10-15 2018-09-25 2018-12-03 2019-08-30 2018-12-24 2019-01-28 2019-03-09 and Emergency Response ant Selection peer educators, POE, and sa mples transport and referral guidelines (human, animal a nd environmental) LR-MOHSW-56455-CS-CDS / Component 5: Institutional C Recruitment of Project Procur IDA / 59690 apacity Building, Project Ma Prior Direct Selection Direct 30,000.00 0.00 Canceled 2018-08-30 2018-09-21 2018-09-09 2019-03-09 2018-11-13 2019-11-08 ement Officer (MOA) nagement, Coordination and Advocacy Page 5 LR-MOHSW-56472-CS-INDV / Component 4: Human Resou Recruitment of consultant to rce Management for Effectiv Individual Consult develop disease surveillance IDA / 59690 Post Open 42,900.00 0.00 Canceled 2018-09-21 2018-09-25 2018-11-09 2019-08-30 2018-11-30 2019-01-04 2019-07-03 e Disease Surveillance and E ant Selection workforce strategy (animal, h pidemic Preparedness uman & environmental) LR-MOHSW-79821-CS-CDS / Component 5: Institutional C Pending Impleme Recruitment of Environmenta IDA / 59690 apacity Building, Project Ma Post Direct Selection Direct 30,000.00 0.00 2018-09-28 2018-10-08 2018-12-12 2019-06-10 ntation l Social and Safe Guard Offic nagement, Coordination and er Advocacy LR-MOHSW-56460-CS-INDV / Component 5: Institutional C Individual Consult Recruitment of Environmenta IDA / 59690 apacity Building, Project Ma Post Open 30,000.00 0.00 Canceled 2018-10-10 2018-11-28 2018-12-19 2019-01-23 2020-01-18 ant Selection l Social and Safe Guard Offic nagement, Coordination and er Advocacy LR-MOHSW-85795-CS-INDV / Recruit Consultant to develo Component 1: Surveillance a Individual Consult IDA / 59690 Post Open 45,200.00 0.00 Canceled 2018-11-30 2019-01-18 2019-02-08 2019-03-15 2019-09-11 p diseases Surveillance workf nd Information Systems ant Selection orce strategy for human and animals environment LR-MOHSW-96738-CS-INDV / Component 2: Strengthening Recruit Communication Speci IDA / 59690 Post Direct Selection Direct 30,000.00 0.00 Canceled 2019-06-28 2019-07-08 2019-09-11 2020-03-09 of Laboratory Capacity alist for REDISSE LR-MOHSW-96756-CS-INDV / Component 4: Human Resou Recruit Consultant to conduc rce Management for Effectiv Individual Consult IDA / 59690 Post Limited 35,000.00 0.00 Canceled 2019-01-31 2018-09-25 2019-02-05 2019-02-26 2019-04-02 2019-09-29 t needs assessment for publi e Disease Surveillance and E ant Selection c health and veterinary healt pidemic Preparedness h workforce in country LR-MOHSW-56463-CS-INDV / Component 5: Institutional C Recruitment of consultant to apacity Building, Project Ma Individual Consult conduct multi-hazard vulnera IDA / 59690 Post Open 48,000.00 0.00 Canceled 2019-08-30 2019-10-18 2019-11-08 2019-12-13 2020-02-11 nagement, Coordination and ant Selection bility and risk assessment pr Advocacy eparedness and response LR-MOHSW-96742-CS-CDS / Component 2: Strengthening Under Implement IDA / 59690 Post Direct Selection Direct 30,000.00 0.00 2019-07-30 2019-01-10 2019-08-09 2019-01-18 2019-10-13 2020-04-10 Recruitment of Epidemiology of Laboratory Capacity ation for MOA LR-MOHSW-96747-CS-CDS / Component 3: Preparedness IDA / 59690 Post Direct Selection Direct 30,000.00 0.00 Canceled 2019-05-30 2019-06-09 2019-08-13 2020-02-09 Recruit M & E Specialist and Emergency Response LR-MOHSW-56552-CS-CDS / Component 5: Institutional C Recruit GAC to conduct Annu IDA / 59690 apacity Building, Project Ma Post Direct Selection Direct 20,000.00 0.00 Canceled 2018-08-10 2018-08-20 2018-10-24 2019-04-22 al Audit for REDISSE nagement, Coordination and Advocacy LR-MOHSW-122585-CS-INDV / Hiring of a Individual consul tant to conduct AMR integrat Component 3: Preparedness Individual Consult IDA / 59690 Post Limited 18,000.00 0.00 Canceled 2019-07-12 2019-08-10 2019-07-17 2019-08-07 2019-09-11 2020-03-09 ed Knowledge, attitude and and Emergency Response ant Selection practice (KAP) behavior surv ey to guide training and educ ation. LR-MOHSW-111764-CS-CDS Component 4: Human Resou / Hiring of AFENET to Implem rce Management for Effectiv IDA / 59680 Post Direct Selection Direct 197,736.00 0.00 Canceled 2019-04-01 2019-04-11 2019-06-15 2019-12-12 ent the Training Program for e Disease Surveillance and E FETP-V on Behalf of NPHIL/M pidemic Preparedness OA LR-MOHSW-126079-CS-CDS Component 4: Human Resou / Hiring of AFENET to implem rce Management for Effectiv IDA / 59690 Post Direct Selection Direct 197,736.00 197,731.00 Completed 2019-08-02 2019-08-05 2019-08-12 2019-08-12 2019-10-16 2019-12-07 2020-04-13 2021-03-04 ent the training program for e Disease Surveillance and E FET-V-NPHIL/MOA pidemic Preparedness LR-MOHSW-142351-CS-INDV / Hiring an Individual Consult ant to conduct AMR Integrate Component 3: Preparedness Individual Consult IDA / 59690 Post Open 18,000.00 0.00 Canceled 2019-10-29 2019-10-14 2019-12-17 2021-02-26 2020-01-07 2020-02-11 2020-05-01 d Knowledge, Attitude and Pr and Emergency Response ant Selection actice (KAP) behavior Survey to guide training and educati on LR-MOHSW-135190-CS-INDV / Recruitment of animal healt h surveillance officers in 7 Co unties, Namely: RiverCess, Ri Component 4: Human Resou verGee, Bomi, Grand Kru, Gr rce Management for Effectiv Individual Consult IDA / 59690 Post Open 32,400.00 32,400.00 Signed 2019-09-30 2019-12-28 2019-11-18 2020-03-19 2019-12-09 2020-03-29 2020-01-13 2020-07-25 2021-01-12 and Bassa, Sinoe, and Margib e Disease Surveillance and E ant Selection i Counties. pidemic Preparedness There is an additional 2 Coun ties Montserrado & Nimba to increase the officers LR-MOHSW-171858-CS-CDS Component 5: Institutional C / Hiring of a Laboratory Cons apacity Building, Project Ma ultant for laboratory system IDA / 59690 Post Direct Selection Direct 42,000.00 42,000.00 Signed 2020-05-04 2020-04-28 2020-05-14 2020-05-12 2020-07-18 2020-06-02 2021-07-13 nagement, Coordination and strengthening at the National Advocacy Public Health Reference Labo ratory. LR-MOHSW-175618-CS-INDV Component 5: Institutional C Individual Consult / Hiring of Monitoring and Ev IDA / 59690 apacity Building, Project Ma Post Limited 24,000.00 0.00 Canceled 2020-06-05 2020-05-19 2020-06-10 2021-03-26 2020-07-01 2020-08-05 2021-07-31 ant Selection aluation Officer for the REDIS nagement, Coordination and SE Project Advocacy LR-MOHSW-175619-CS-INDV Component 5: Institutional C Individual Consult / Hiring of Communication Of IDA / 59690 apacity Building, Project Ma Post Limited 24,000.00 1,900.00 Signed 2020-06-05 2020-05-19 2020-06-10 2020-10-14 2020-07-01 2020-12-15 2020-08-05 2021-03-06 2021-02-01 ant Selection ficer for the REDISSE Project nagement, Coordination and Advocacy LR-MOHSW-179945-CS-CDS / Hiring of a ICT Officer for 1 Component 4: Human Resou year to support the Interope rce Management for Effectiv IDA / 59690 Post Direct Selection Direct 10,800.00 10,800.00 Signed 2020-06-16 2019-11-13 2020-06-26 2020-07-17 2020-08-30 2020-09-01 2021-02-26 rable Surveillance and Repor e Disease Surveillance and E ting System eIDSR impleme pidemic Preparedness ntation at the Ministry of Hea lth LR-MOHSW-179946-CS-CDS Component 4: Human Resou / Hiring of Data Manager for rce Management for Effectiv 1 year for interoperable surv IDA / 59690 Post Direct Selection Direct 9,600.00 9,600.00 Signed 2020-06-17 2019-11-13 2020-06-27 2020-07-17 2020-08-31 2020-09-02 2020-10-06 e Disease Surveillance and E eillance and reporting syste pidemic Preparedness m (eIDSR) implementation at the Ministry of Health LR-MOHSW-231400-CS-INDV Component 5: Institutional C Individual Consult / Recruitment of Project Proc IDA / 59690 apacity Building, Project Ma Post Direct 30,000.00 30,000.00 Signed 2018-04-20 2018-09-21 2018-04-30 2019-03-09 2018-05-21 2019-03-11 2018-06-25 2019-04-25 2019-06-20 ant Selection urement Officer (MOA) nagement, Coordination and Advocacy LR-MOHSW-231404-CS-INDV Component 5: Institutional C Individual Consult / Recruitment Project Nationa IDA / 59690 apacity Building, Project Ma Post Direct 48,000.00 56,400.00 Signed 2018-04-05 2018-04-27 2018-04-15 2018-05-20 2018-05-06 2018-06-24 2018-06-10 2018-07-02 2019-06-05 ant Selection l Technical Coordinator nagement, Coordination and Advocacy Page 6 Component 5: Institutional C MOF-REF-1 / Recruitment of Individual Consult Under Implement IDA / 59690 apacity Building, Project Ma Post Direct 18,000.00 0.00 2018-04-20 2018-05-15 2018-04-30 2018-05-21 2018-06-25 2018-12-22 Project Accountant Assistant ant Selection ation nagement, Coordination and Advocacy LR-MOHSW-251751-CS-INDV / Recruitment of a Local Indiv Component 5: Institutional C idual Consultant to conduct apacity Building, Project Ma Individual Consult Mid-Term Review (MTR) for t IDA / 59690 Post Limited 9,825.00 0.00 Canceled 2021-09-06 2021-08-30 2021-09-11 2021-11-01 2021-10-02 2022-01-02 2021-11-06 2022-02-04 nagement, Coordination and ant Selection he Regional Disease Surveilla Advocacy nce Systems Enhancement ( REDISSE-II) for a period of 1 month or 30 days. LR-MOHSW-295813-CS-INDV / Hiring of consultant to devel op national case managemen Component 3: Preparedness Individual Consult Under Implement IDA / 59690 Post Open 45,000.00 0.00 2022-06-01 2022-04-17 2022-07-20 2022-08-10 2022-09-14 2023-03-13 t/isolation unit guidelines (hu and Emergency Response ant Selection ation man health clinical managem ent and quarantine center for animal health) LR-MOHSW-295818-CS-INDV / Hiring of consultant to cond Component 3: Preparedness Individual Consult Under Implement uct AMR integrated knowledg IDA / 59690 Post Open 16,350.00 0.00 2022-06-10 2022-05-02 2022-07-29 2022-08-19 2022-09-23 2023-03-22 and Emergency Response ant Selection ation e, attitude and practice (KAP) behavioral survey to guide tr aining and education. LR-MOHSW-295820-CS-INDV / Hiring of consultant to cond Component 3: Preparedness Individual Consult Under Implement uct gender gap assessment i IDA / 59690 Post Open 23,500.00 0.00 2022-06-01 2022-07-06 2022-07-20 2022-08-10 2022-09-14 2023-03-13 and Emergency Response ant Selection ation n infectious disease preventi on and control with emphasis on zoonoses. LR-MOHSW-295821-CS-INDV Component 4: Human Resou / Hiring of consultant to cond rce Management for Effectiv Individual Consult Under Implement uct needs assessment for pu IDA / 59690 Post Open 11,200.00 0.00 2022-06-01 2022-04-17 2022-07-20 2022-08-10 2022-09-14 2023-03-13 e Disease Surveillance and E ant Selection ation blic health and veterinary he pidemic Preparedness alth workforce (including rete ntion) in the country. LR-MOHSW-295824-CS-INDV Component 4: Human Resou / Hiring of consultant to devel rce Management for Effectiv Individual Consult Under Implement op strategic plan for the One IDA / 59690 Post Open 5,350.00 0.00 2022-06-30 2022-04-17 2022-08-18 2022-09-08 2022-10-13 2023-04-11 e Disease Surveillance and E ant Selection ation Health workforce including re pidemic Preparedness tention strategy (animal, hu man and environmental). LR-MOHSW-295871-CS-INDV Component 5: Institutional C Individual Consult Under Implement / Hiring of Monitoring & Evalu IDA / 59690 apacity Building, Project Ma Post Open 30,000.00 0.00 2022-06-01 2022-04-17 2022-07-20 2022-08-10 2022-09-14 2023-09-14 ant Selection ation ation Officer nagement, Coordination and Advocacy LR-MOHSW-295827-CS-INDV Component 5: Institutional C Individual Consult Under Implement / Hiring of Human Health Proj IDA / 59690 apacity Building, Project Ma Post Open 30,000.00 0.00 2022-06-01 2022-05-02 2022-07-20 2022-08-10 2022-09-14 2023-09-14 ant Selection ation ect Officer - MoH - 1 person nagement, Coordination and Advocacy Component 4: Human Resou LR-MOHSW-297161-CS-INDV rce Management for Effectiv Individual Consult Under Implement / Hiring of Animal Health Proj IDA / 59690 Post Open 30,000.00 0.00 2022-06-01 2022-05-02 2022-07-20 2022-08-10 2022-09-14 2023-09-14 e Disease Surveillance and E ant Selection ation ect Officer - MoA - 1 Person pidemic Preparedness LR-MOHSW-344346-CS-CDS / Recruitment of a consultant for the development of case management and isolation g Component 3: Preparedness uideline for priority diseases IDA / 59690 Post Direct Selection Direct - National 24,950.00 0.00 Signed 2023-02-24 2023-02-09 2023-03-06 2023-03-23 2023-05-10 2023-08-31 and Emergency Response ((human health clinical mana gement and Quarantine cent er for animal health) through direct selection by Dr. Phiona Nakyyeyune for 3 months Page 7 Procurement Plan for P124015 (PFS) I. General 2. Bank’s approval Date of the procurement Plan 3. Date of General Procurement Notice: 4. Period covered by this procurement plan: Year 2017. II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Mandatory threshold to Prior Review Type of Procurement procurement use Thresholds in methods Procurement USD method in USD Works (including ≥ ICB turnkey, supply 5.000.000 All contract with & installation of NCB < 5.000.000 estimated cost plant and Shopping < 200.000 equal or above equipment, and Direct 10 million No threshold PPP) contracting ≥ Goods, ICB 1.000.000 All contract with information NCB < 1.000.000 estimated cost technology and Shopping < 100.000 equal or above 2 non-consulting Direct million services No threshold contracting 2. Prequalification. Not applicable 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: Not applicable Reference to (if any) Project Operational/Procurement Manual: Project Implementation Manual for World Bank Project P124015 4. Any Other Special Procurement Arrangements: Not applicable June 19, 2017 June 19, 2017 5. Summary of the Procurement Packages planned during the first 18 months after project effectiveness: This Project is implementing since 2013. This Procurement plan is only for the current year. 1 2 3 4 5 6 7 Ref. Descripti Estimat Packages Dome Review Comme No. on ed stic by Bank nts Cost Prefe (Prior / US$ rence Post) (yes/ no) Summary There is no contracts to be led under ICB of the ICB Works (Works) Summary There is no contracts to be led under ICB of the ICB Goods (Goods) Summary There is no contracts to be led under NCB of the NCB Works (Works) Summary There is no contracts to be led under NCB of the NCB Goods (Goods) Summary There is no contracts to be led under ICB Non of the ICB consulting (Non- Consultant Services) III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Mandatory threshold to Prior Review Type of Procurement procurement use Thresholds in methods Procurement USD method in USD QCBS; QBS; FBS; All contract with No threshold Consultants: LCS; SSS estimated cost firms equal or above CQS < 300.000 1million Consultants: Competitive and All contract with No threshold individuals SSS estimated cost June 19, 2017 equal or above 0.3 million 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_200,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: Not applicable 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 Ref. No. Description Estimat Package Review Comment of ed s by Bank s Assignmen Cost (Prior / t US$ Post) Summary There is no contracts to be led under of number QCBS of contracts that will be let under QCBS Summary 443,47 14 Post of number 0 of contracts that will be let under other methods June 19, 2017 PROCUREMENT Burkina Faso : Social Safety Net Project PLAN General Information Country: Burkina Faso 2017-06-22 Bank’s Approval Date of the Original Procurement Plan: Revised Plan Date(s): (comma delineated, leave blank 2023-06-05 if none) Project ID: P124015 GPN Date: 2020-02-25 Project Name: Social Safety Net Project Loan / Credit No: IDA / 54290, TF / A3975, IDA / 64340, IDA / D4760 Project Coordination Unit of Social Nets Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Comple Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes tion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BF-PFS-17932-GO-RFQ / Con Request for Quota Single Stage - One E sommables informatiques et IDA / 54290 Project management Post Limited 14,000.00 13,323.37 Completed 2017-09-04 2017-09-04 2018-06-20 2017-09-04 2016-06-14 tions nvelope de reprographie BF-PFS-17939-GO-RFQ / Joue Cash transfers and awarenes Request for Quota Single Stage - One E ts pour enfants Groupes d'éd IDA / 54290 s programs for poor and vuln Post Limited 36,000.00 33,927.84 Completed 2017-10-02 2017-10-02 2018-12-28 2017-10-02 2019-06-15 tions nvelope ucation erable households BF-PFS-17929-GO-RFQ / Mobi Request for Quota Single Stage - One E Under Imple liers de bureau pour le perso IDA / 54290 Project management Post Limited 90,000.00 0.00 2017-07-15 2017-07-15 2017-07-15 tions nvelope mentation nnel complémentaire BF-PFS-17928-GO-RFQ / Mat Laying the foundations for a Request for Quota Single Stage - One E IDA / 54290 Post Limited 40,000.00 25,582.09 Signed 2017-05-30 2017-07-03 2017-11-08 2017-07-03 ériel d'inscription des bénéfici basic national safety net syst tions nvelope aires em BF-PFS-17535-GO-RFQ / 200 Request for Quota Single Stage - One E boîtes à image au profit des F IDA / 54290 Project management Post Limited 8,000.00 6,163.54 Signed 2017-10-04 2017-09-20 2017-11-29 2017-11-06 2018-05-28 tions nvelope ACOM et Travailleurs Sociaux BF-PFS-17559-GO-RFQ / Mat Laying the foundations for a ériel d'inscription des bénéfici Request for Quota Single Stage - One E IDA / 54290 basic national safety net syst Post Limited 40,000.00 24,059.89 Completed 2017-06-16 2017-08-26 2017-08-11 2017-11-08 2018-02-07 2017-12-01 aires (imprimantes, cartes de tions nvelope em bénéficiaires....) BF-PFS-17573-GO-RFQ / Cart Cash transfers and awarenes Request for Quota Single Stage - One E es conseils petit forma pour l IDA / 54290 s programs for poor and vuln Post Limited 93,000.00 85,155.85 Completed 2017-10-04 2017-09-05 2017-11-29 2017-12-07 2018-05-28 2018-03-12 tions nvelope es bénéficiaires erable households BF-PFS-30236-GO-RFQ / Mat Laying the foundations for a Request for Quota Single Stage - One E ériel de sonorisation pour les IDA / 54290 basic national safety net syst Post Limited 70,000.00 41,414.91 Completed 2017-10-28 2018-09-03 2017-12-23 2018-12-28 2018-06-21 2019-03-25 tions nvelope mobilisations communautaire em s BF-PFS-41091-GO-RFQ / réali Request for Quota Single Stage - One E sation du câblage réseau et d IDA / 54290 Project management Post Limited 34,000.00 24,816.49 Completed 2018-01-20 2018-04-30 2018-03-17 2018-06-13 2018-09-13 2018-10-01 tions nvelope u contrôle d'accès au siège d u PFS BF-PFS-49339-GO-RFB / Maté Laying the foundations for a Single Stage - One E riel informatique et peri-infor IDA / 54290 basic national safety net syst Post Request for Bids Open - National 110,000.00 87,712.65 Signed 2018-04-09 2018-09-11 2018-04-19 2019-02-19 2018-05-19 2019-03-11 2018-05-26 2019-08-27 2018-06-24 2019-11-29 2018-08-23 nvelope matique au profit du Profit du em Projet BF-PFS-49325-GO-RFQ / Acq Request for Quota Single Stage - One E uisition de plaques et sacs sol IDA / 54290 Project management Post Limited 69,760.00 58,150.06 Completed 2018-04-07 2018-09-03 2018-05-27 2018-12-06 2018-07-26 2019-01-17 tions nvelope aires au profit du projet BF-PFS-49654-GO-RFQ / Conf Request for Quota Single Stage - One E ection de plaques pour les no IDA / 54290 Project management Post Limited 14,000.00 12,255.87 Completed 2018-03-24 2018-12-14 2018-05-13 2019-01-30 2018-06-12 2019-02-25 tions nvelope uvelles communes du projet BF-PFS-17949-GO-RFQ / Outil Request for Quota Single Stage - One E IDA / 54290 Project management Post Limited 10,000.00 9,620.52 Signed 2018-04-04 2018-07-11 2018-05-24 2018-10-08 2018-08-22 s de communication au profit tions nvelope du PFS BF-PFS-30891-GO-RFQ / Acq uisition de matériel de protec Request for Quota Single Stage - One E IDA / 54290 Project management Post Limited 19,600.00 15,162.22 Completed 2018-04-15 2018-08-07 2018-05-21 2018-10-10 2018-08-19 2018-11-22 tion au profit du personnel de tions nvelope terrain du PFS (CRO et FACO M) BF-PFS-22747-GO-RFQ / 35 k its de dissémination audiovis Laying the foundations for a Request for Quota Single Stage - One E uelle (Projecteurs PICO, encei IDA / 54290 basic national safety net syst Post Limited 50,000.00 41,024.43 Completed 2018-04-07 2018-09-03 2018-05-27 2018-12-06 2018-08-25 2019-06-14 tions nvelope ntes, cartes mémoires et ad em aptateurs) pour la sensibilisat ion FA BF-PFS-57177-GO-RFB / Acqu Laying the foundations for a Single Stage - One E isition de tablettes et de télé IDA / 54290 basic national safety net syst Post Request for Bids Open - National 196,200.00 0.00 Signed 2018-04-16 2018-05-04 2018-04-21 2018-06-02 2018-09-28 2018-06-17 2018-09-28 2018-07-22 2018-10-20 nvelope phone au profit du Projet Filet em s Sociaux BF-PFS-57291-GO-RFQ / Joue Laying the foundations for a ts pour enfants au profit des Request for Quota Single Stage - One E IDA / 54290 basic national safety net syst Post Open - National 36,000.00 33,754.49 Completed 2018-06-23 2018-08-28 2018-12-28 2018-10-27 2019-06-15 mères de l'Est, du Centre-Est tions nvelope em et du Nord (Loroum et Passor é) BF-PFS-68463-GO-RFQ / Acq Cash transfers and awarenes Request for Quota Single Stage - One E uisition de kits complémentai TF / A3975 s programs for poor and vuln Post Limited 12,000.00 10,216.74 Completed 2018-08-11 2018-10-11 2018-10-06 2018-11-09 2018-12-05 2018-12-20 tions nvelope res AVEC erable households BF-PFS-68683-GO-DIR / Acqu isition d'un logiciel de gestion IDA / 54290 Project management Post Direct Selection Direct 94,000.00 78,354.47 Completed 2018-07-16 2018-07-11 2018-07-31 2018-08-08 2018-08-29 2018-12-28 2018-10-28 2019-07-15 comptable et des ressources humaines (TOM2 PRO et TOM -Paie) BF-PFS-53859-GO-DIR / Acqu isition d'un logiciel de gestion IDA / 54290 Project management Prior Direct Selection Direct 140,000.00 0.00 Canceled 2018-03-19 2018-07-11 2018-04-03 2018-05-02 2018-07-01 comptable et des ressources humaines (TOM2 PRO et TOM -Paie) BF-PFS-49385-GO-RFB / Maté Single Stage - One E riel roulant (véhicule et moto IDA / 54290 Project management Post Request for Bids Open - National 315,000.00 0.00 Canceled 2018-03-26 2018-04-05 2018-05-05 2018-05-12 2018-06-10 2018-09-08 nvelope cyclettes) au profit du Projet BF-PFS-83445-GO-RFQ / Réal Request for Quota Single Stage - One E isation de cloison en alu vitre IDA / 54290 Project management Post Limited 20,000.00 17,268.88 Signed 2018-11-06 2018-11-16 2018-12-12 2018-12-12 2019-01-11 tions nvelope des locaux du projet Filets so ciaux Page 1 BF-PFS-83447-GO-RFQ / Four Request for Quota Single Stage - One E niture et pose de rideaux typ IDA / 54290 Project management Post Limited 6,000.00 5,125.34 Completed 2018-12-03 2018-11-16 2019-01-08 2018-12-12 2019-01-23 2019-03-04 tions nvelope e stores au profit du Projet Fil ets Sociaux BF-PFS-57317-GO-RFB / Acqu isition de cartes conseil en pe Laying the foundations for a Single Stage - One E tit format pour les bénéficiair TF / A3975 basic national safety net syst Post Request for Bids Open - National 357,000.00 0.00 Canceled 2018-06-11 2018-06-16 2018-07-28 2018-08-04 2018-09-08 2019-09-08 nvelope es de l'est,du Centre Est et d em u Nord (Loroum et Passoré) BF-PFS-19408-GO-RFQ / Acq Cash transfers and awarenes Request for Quota Single Stage - One E uisition de 120 sacs solaires IDA / 54290 s programs for poor and vuln Post Limited 48,000.00 0.00 Canceled 2017-07-09 2017-09-03 2018-03-02 tions nvelope pour la recharge des tablette erable households s BF-PFS-48964-GO-RFB / Maté Single Stage - One E riels audio visuel et de comm TF / A3975 Project management Post Request for Bids Open - National 131,200.00 0.00 Canceled 2018-03-29 2018-04-13 2018-05-13 2018-05-20 2018-06-18 2018-08-17 nvelope unication au profit du projet BF-PFS-49323-GO-RFQ / Carn Cash transfers and awarenes ets de bénéficiaires du Bouki Request for Quota Single Stage - One E TF / A3975 s programs for poor and vuln Post Limited 32,000.00 0.00 Canceled 2018-03-31 2018-05-20 2019-05-20 emdé, du Sanguié, du Nayala tions nvelope erable households , du Sourou et Bam BF-PFS-119896-GO-RFQ / Ac Request for Quota Single Stage - One E quisition de consommables In IDA / 54290 Project management Post Limited 15,850.00 14,562.38 Signed 2019-09-09 2019-10-08 2019-10-19 2019-10-24 2020-10-18 tions nvelope formatiques BF-PFS-119891-GO-RFQ / Ca Request for Quota Single Stage - One E blâge réseau téléphonique et IDA / 54290 Project management Post Limited 1,850.00 0.00 Signed 2019-09-21 2020-01-27 2019-10-31 2019-11-25 tions nvelope informatique BF-PFS-119892-GO-RFQ / Ins Request for Quota Single Stage - One E tallation de vidéo surveillanc IDA / 54290 Project management Post Limited 15,100.00 0.00 Signed 2019-07-14 2020-03-06 2019-08-23 2019-09-22 tions nvelope e dans les locaux de l'UGP BF-PFS-119772-GO-RFQ / Am Request for Quota Single Stage - One E énagement d'un parking pour IDA / 54290 Project management Post Limited 20,000.00 0.00 Signed 2019-07-24 2019-10-25 2019-09-02 2019-10-02 tions nvelope 21 véhicules BF-PFS-119780-GO-RFB / Acq uisition de jouets pour enfant Cash transfers and awarenes Single Stage - One E s à mettre à la disposition de IDA / 54290 s programs for poor and vuln Post Request for Bids Open - National 104,500.00 0.00 Signed 2019-07-08 2019-10-03 2019-07-22 2023-05-26 2019-09-02 2020-10-03 2019-09-16 2020-10-03 2019-10-21 2020-01-19 nvelope s mères de l'Est, du Centre-E erable households st et du Nord (Loroum et Pass oré) BF-PFS-48967-GO-RFQ / Tabl Request for Quota Single Stage - One E es et bancs au profit des villa TF / A3975 Project management Post Limited 24,060.00 0.00 Canceled 2018-03-11 2018-04-30 2018-06-29 tions nvelope ges du Nord (Loroum et Pass oré) BF-PFS-17931-GO-RFQ / Assu Request for Quota Single Stage - One E IDA / 54290 Project management Post Limited 15,000.00 0.00 Canceled 2017-07-15 2017-07-15 2017-07-15 rance pour les locaux du PFS tions nvelope BF-PFS-48663-GO-RFB / mat Laying the foundations for a Single Stage - One E ériel et des logiciels informati IDA / 54290 basic national safety net syst Post Request for Bids Open - National 200,000.00 0.00 Canceled 2018-03-12 2018-03-27 2018-04-26 2018-05-11 2018-06-15 2018-08-14 nvelope ques pour le déploiement du em registre BF-PFS-17936-GO-RFQ / Clim Request for Quota Single Stage - One E IDA / 54290 Project management Post Limited 1,500.00 0.00 Canceled 2017-08-15 2017-08-15 2017-08-15 atiseurs entretien et réparati tions nvelope on BF-PFS-120226-GO-RFQ / Fo Cash transfers and awarenes urnitures de bureau et divers Request for Quota Single Stage - One E TF / A3975 s programs for poor and vuln Post Open - National 58,000.00 29,564.79 Signed 2019-04-24 2019-07-03 2019-10-08 2019-07-09 équipements pour la formatio tions nvelope erable households n des bénéficiaires en ACV et GERME BF-PFS-140264-GO-RFQ / Ac quisition de fourniture de bur Request for Quota Single Stage - One E IDA / 54290 Project management Post Limited 40,000.00 0.00 Signed 2019-11-04 2019-02-06 2019-12-26 2019-12-30 eau et de produits d'entretien tions nvelope pour l'UGP, les CRO et les FA COM BF-PFS-48979-GO-RFB / mat Single Stage - One E ériels de couchage au profit d TF / A3975 Project management Post Request for Bids Open - National 306,000.00 0.00 Canceled 2018-03-26 2018-04-10 2018-05-10 2018-05-25 2018-06-23 2019-06-23 nvelope es groupes d'éducation BF-PFS-57288-GO-RFB / Acqu isition de fourniture de burea Single Stage - One E IDA / 54290 Project management Post Request for Bids Open - National 40,000.00 0.00 Canceled 2018-06-04 2018-06-09 2018-07-21 2018-07-28 2018-09-01 2019-09-01 u et de produits d'entretien p nvelope our l'UGP, les CRO et les FAC OM BF-PFS-17937-GO-RFQ / Assu Request for Quota Single Stage - One E IDA / 54290 Project management Post Limited 40,000.00 0.00 Canceled 2017-07-16 2017-07-16 2017-07-16 rance pour véhicules et moto tions nvelope s BF-PFS-119667-GO-RFQ / Ac Cash transfers and awarenes quisition de rubans pour les v Request for Quota Single Stage - One E IDA / 54290 s programs for poor and vuln Post Limited 4,400.00 0.00 Canceled 2019-07-07 2019-08-11 2019-08-26 isionnages 2 et 3 pendant AC tions nvelope erable households V et GERME (1 ruban par gro upe) BF-PFS-88892-GO-RFQ / Acq Request for Quota Single Stage - One E uisition de matériel roulant (v IDA / 54290 Project management Post Open - National 45,000.00 0.00 Canceled 2018-12-15 2019-02-14 2019-04-15 tions nvelope éhicule) au profit du projet fil ets sociaux BF-PFS-119675-GO-RFQ / Ac Request for Quota Single Stage - One E quisition de matériel roulant ( IDA / 54290 Project management Post Open - National 95,000.00 0.00 Canceled 2019-09-15 2019-12-01 2020-02-29 tions nvelope vehicule 4X4 pick up et berlin e) BF-PFS-154432-GO-RFQ / Ins tallation d'un système de géo Request for Quota Single Stage - One E IDA / 54290 Project management Post Limited 10,000.00 0.00 Signed 2020-02-01 2020-12-17 2020-03-19 2020-04-18 localisation (GPS) sur les véhi tions nvelope cules du projets BF-PFS-140259-GO-RFQ / Mo Request for Quota Single Stage - One E biliers de bureau pour le pers IDA / 54290 Project management Post Limited 90,000.00 0.00 Signed 2020-02-15 2020-06-15 2020-03-29 2020-05-28 tions nvelope onnel complémentaire du PFS BF-PFS-159686-GO-RFB / Acq Cash transfers and awarenes uisition de materiels et fourni Single Stage - One E Pending Impl IDA / 64340 s programs for poor and vuln Post Request for Bids Open - National 433,814.00 0.00 2020-03-27 2020-04-01 2020-05-13 2020-06-12 2020-07-17 2020-09-15 tures spécifiques pour la mis nvelope ementation erable households e en œuvre de l'école par la r adio BF-PFS-159682-GO-RFQ / Pro duction de carnets pour les b Cash transfers and awarenes énéficiares des régions de la Request for Quota Single Stage - One E IDA / 54290 s programs for poor and vuln Post Limited 49,000.00 0.00 Signed 2020-07-11 2021-05-21 2020-09-05 2020-10-20 Boucle du Mouhoun et du Ce tions nvelope erable households ntre (39 000 carnets pour la Boucle du Mouhoun, 10 000 carnets pour le Centre) BF-PFS-159664-GO-RFQ / Ac quisition de matériel spécifiq Request for Quota Single Stage - One E IDA / 54290 Project management Post Limited 4,100.00 0.00 Signed 2020-02-29 2020-03-20 2020-04-03 2020-04-18 ue au profit du spécialiste en tions nvelope sauvegarde environnemental e Page 2 BF-PFS-159685-GO-RFQ / Ac Request for Quota Single Stage - One E quisition de matériel informat IDA / 54290 Project management Post Limited 30,740.00 0.00 Signed 2020-03-28 2020-07-01 2020-05-23 2020-07-07 tions nvelope ique et de logiciel BF-PFS-140260-GO-RFQ / Ac Request for Quota Single Stage - One E quisition de matériel roulant IDA / 54290 Project management Post Limited 90,000.00 0.00 Signed 2020-03-07 2020-04-06 2020-04-28 2020-06-27 tions nvelope au profit du projet filets socia ux BF-PFS-165586-GO-RFQ / Ins Request for Quota Single Stage - One E tallation d'un système de vid IDA / 54290 Project management Post Limited 9,000.00 0.00 Signed 2020-03-18 2020-03-18 2020-03-20 2020-03-22 tions nvelope éo conférence au profit du PF S BF-PFS-171204-GO-RFQ / Ins tallation d'un système de vid Request for Quota Single Stage - One E IDA / 54290 Project management Post Limited 9,000.00 0.00 Signed 2020-04-22 2020-06-08 2020-05-14 2020-05-29 éo conférence au Cabinet de tions nvelope la Ministre / MFSNFAH BF-PFS-231183-GO-RFQ / Re crutement d'un prestataire p Cash transfers and awarenes our la production des carnets Request for Quota Single Stage - One E IDA / 64340 s programs for poor and vuln Post Limited 67,000.00 53,366.45 Signed 2021-04-28 2021-05-07 2021-06-23 2021-06-01 2021-12-20 des bénéficiaires dans les rég tions nvelope erable households ions du Nord, Centre-nord et de la Boucle du Mouhoun au profit du projet Filets sociaux BF-PFS-236705-GO-RFQ / Re crutement d’une firme pour l Request for Quota Single Stage - One E IDA / 64340 Project management Post Limited 100,000.00 0.00 Signed 2021-06-02 2021-06-09 2021-07-28 2022-01-24 es travaux d’imprimerie au pr tions nvelope ofit du Projet Filets Sociaux BF-PFS-241486-GO-RFQ / Ac quisition de matériel informat Request for Quota Single Stage - One E IDA / 64340 Project management Post Limited 50,000.00 39,987.82 Signed 2021-07-10 2021-12-15 2021-09-04 2022-01-20 2022-03-03 ique et péri-informatique au tions nvelope profit du Projet Filets Sociaux BF-PFS-241487-GO-RFQ / Ac quisition de matériels, logiciel Request for Quota Single Stage - One E IDA / 64340 Project management Post Limited 31,000.00 24,001.75 Signed 2021-07-10 2021-12-15 2021-09-04 2022-01-20 2022-03-03 s et consommables informati tions nvelope ques au profit du Projet Filets Sociaux BF-PFS-241488-GO-RFQ / Ac Request for Quota Single Stage - One E quisition de matériel de vidéo IDA / 64340 Project management Post Limited 16,000.00 12,713.84 Signed 2021-07-13 2021-11-19 2021-09-07 2021-11-30 2022-03-06 tions nvelope conférence au profit du Projet Filets Sociaux BF-PFS-241490-GO-RFQ / Ac quisition et installation d’une solution de Call Center coupl Cash transfers and awarenes Request for Quota Single Stage - One E ée à une plateforme de traite IDA / 64340 s programs for poor and vuln Post Limited 32,000.00 0.00 Signed 2021-07-14 2021-07-22 2021-09-08 2021-08-05 2022-03-07 tions nvelope ment des plaintes et enregist erable households rement des communication h ébergée au niveau du Centre d’appel du Projet Filets Socia ux BF-PFS-264484-GO-DIR / Acq uisition du carburant au profit IDA / 64340 Project management Post Direct Selection Direct 30,000.00 0.00 Signed 2021-11-30 2021-10-28 2021-12-05 2021-11-04 2022-01-09 2021-11-30 2022-07-08 du parc automobile de l'unité de gestion du Projet filets file ts sociaux BF-PFS-280326-GO-RFQ / PR Cash transfers and awarenes ODUCTION DES CARNETS DE Request for Quota Single Stage - One E IDA / 64340 s programs for poor and vuln Post Limited 49,051.00 0.00 Signed 2022-03-05 2022-02-21 2022-04-30 2022-10-27 BENEFICIAIRES DE LA BOUCL tions nvelope erable households E DU MOUHOUN, DU CENTRE ET DU SAHEL BF-PFS-293364-GO-RFQ / Ac Laying the foundations for a quisition de kits par Associati Request for Quota Single Stage - One E IDA / 64340 basic national safety net syst Post Limited 18,480.00 0.00 Signed 2022-05-21 2021-05-21 2022-07-16 2023-01-12 ons villageoises d’épargne et tions nvelope em de crédit (AVEC) au profit du Projet Filets Sociaux BF-PFS-293366-GO-RFQ / Ac quisition de téléphones (flott Request for Quota Single Stage - One E Pending Impl IDA / 64340 Project management Post Limited 7,000.00 0.00 2022-05-29 2022-07-24 2023-01-20 es) au profit de l'unité de ges tions nvelope ementation tion du projet filets sociaux BF-PFS-302220-GO-RFQ / Ma Laying the foundations for a tériels roulants (Station wago Request for Quota Single Stage - One E IDA / 64340 basic national safety net syst Post Limited 85,000.00 0.00 Canceled 2022-07-16 2022-09-10 2023-03-09 n et berline) au profit du Secr tions nvelope em étariat technique du Registre Social Unique. BF-PFS-302227-GO-RFQ / Ac quisition de matériels informa Laying the foundations for a Request for Quota Single Stage - One E tiques et péri-informatiques a IDA / 64340 basic national safety net syst Post Limited 99,000.00 0.00 Signed 2022-07-17 2022-09-22 2022-09-11 2023-03-10 tions nvelope u profit du Secrétariat techni em que du Registre Social Uniqu e. BF-PFS-302229-GO-RFQ / Ac Laying the foundations for a quisition de matériels et mobi Request for Quota Single Stage - One E IDA / 64340 basic national safety net syst Post Limited 37,000.00 0.00 Signed 2022-07-18 2022-09-16 2022-09-12 2023-03-11 liers de bureau au profit du S tions nvelope em ecrétariat technique du Regis tre Social Unique BF-PFS-302234-GO-RFQ / Ac Laying the foundations for a quisition de Matériels électro Request for Quota Single Stage - One E IDA / 64340 basic national safety net syst Post Limited 6,000.00 0.00 Signed 2022-07-19 2022-10-13 2022-09-13 2023-03-12 ménagers au profit du Secrét tions nvelope em ariat technique du Registre S ocial Unique BF-PFS-302245-GO-RFQ / Ac quisition de consommables et Laying the foundations for a Request for Quota Single Stage - One E fournitures de bureau au prof IDA / 64340 basic national safety net syst Post Limited 9,000.00 0.00 Completed 2022-07-20 2022-09-13 2022-09-14 2023-03-13 2022-10-22 tions nvelope it du Secrétariat technique du em Registre Social Unique BF-PFS-302251-GO-RFQ / Ac Laying the foundations for a quisition de Produits d’entreti Request for Quota Single Stage - One E IDA / 64340 basic national safety net syst Post Limited 5,000.00 0.00 Completed 2022-07-22 2022-10-19 2022-09-16 2023-03-15 2022-10-27 en et de nettoyage au profit tions nvelope em du Secrétariat technique du R egistre Social Unique. BF-PFS-303524-GO-RFQ / Ac quisition de Matériels roulant Laying the foundations for a s (01 Station wagon et 01 Pic Request for Quota Single Stage - One E IDA / 64340 basic national safety net syst Post Limited 160,000.00 0.00 Signed 2022-07-23 2022-09-23 2022-09-17 2023-03-16 k up double cabine) au profit tions nvelope em du Secrétariat technique du r egistre social unique (ST RSU ) BF-PFS-316329-GO-RFQ / Ac Laying the foundations for a quisition de matériel de cuisi Request for Quota Single Stage - One E IDA / 64340 basic national safety net syst Post Limited 17,260.00 0.00 Signed 2022-10-13 2022-11-15 2022-11-10 2022-12-10 ne au profit du Projet Filets S tions nvelope em ociaux pour les Crèches Mobil es/Haltes Garderies BF-PFS-319429-GO-RFQ / Ac quisition de jeux et matériels Laying the foundations for a Request for Quota Single Stage - One E didactiques au profit du Proje IDA / 64340 basic national safety net syst Post Limited 95,440.00 0.00 Signed 2022-10-08 2022-11-21 2022-11-05 2023-01-04 tions nvelope t Filets Sociaux pour les Crèc em hes Mobiles/Haltes Garderies Page 3 BF-PFS-319431-GO-RFQ / Ac quisition de mobilier, de maté Laying the foundations for a Request for Quota Single Stage - One E riel d'hygiène et de sécurité a IDA / 64340 basic national safety net syst Post Limited 80,340.00 0.00 Signed 2022-10-08 2022-11-18 2022-11-05 2023-01-04 tions nvelope u profit du Projet Filets Socia em ux pour les Crèches Mobiles/ Haltes Garderies BF-PFS-355213-GO-RFQ / Ac quisition de matériels et de lo Request for Quota Single Stage - One E Pending Impl giciels informatiques au profi IDA / 54290 Project management Post Limited 96,580.00 0.00 2023-04-10 2023-05-20 2023-06-19 tions nvelope ementation t de l'unité de gestion du proj et filets sociaux et au profit d u SE-CNSA (02 LOTS) BF-PFS-355215-GO-RFQ / Ac quisition de fournitures de bu Request for Quota Single Stage - One E Pending Impl IDA / 54290 Project management Post Limited 80,000.00 0.00 2023-05-06 2023-06-27 2024-04-12 reau et produit d'entretiens a tions nvelope ementation u profit du projet filets sociau x BF-PFS-293365-GO-RFQ / Ac quisition de licences/ logiciels (Systèmes d'exploitation, plat Request for Quota Single Stage - One E Pending Impl IDA / 64340 Project management Post Limited 21,380.00 0.00 2023-04-15 2023-06-10 2023-07-10 eforme de développement, a tions nvelope ementation nti-virus, logiciels de scryptag e, logiciel de de planification de projet)/ST RSU BF-PFS-355217-GO-RFQ / Ac Request for Quota Single Stage - One E Pending Impl quisition de matériels informa IDA / 54290 Project management Post Limited 53,650.00 0.00 2023-05-06 2023-07-01 2023-08-30 tions nvelope ementation tiques pour l'équipe SIG-RSU BF-PFS-355221-GO-RFQ / Ac Request for Quota Single Stage - One E Pending Impl quisition d'un véhicule Pick u IDA / 54290 Project management Post Limited 75,000.00 0.00 2023-05-04 2023-06-25 2023-08-24 tions nvelope ementation p double cabine au profit du ST-RSU BF-PFS-355224-GO-RFQ / Ac Laying the foundations for a quisition de matériels informa Request for Quota Single Stage - One E Pending Impl IDA / 64340 basic national safety net syst Post Limited 55,014.00 0.00 2023-05-02 2023-06-27 2023-08-26 tiques et péri-informatiques a tions nvelope ementation em u profit du ST-RSU BF-PFS-355225-GO-RFQ / Ac Laying the foundations for a Request for Quota Single Stage - One E quisition de matériels et mobi IDA / 64340 basic national safety net syst Post Limited 15,250.00 0.00 Signed 2023-05-14 2022-09-28 2023-07-09 2024-01-05 tions nvelope liers de bureau au profit du S em T-RSU BF-PFS-355226-GO-RFQ / Ac quisition de consommables, d Laying the foundations for a Request for Quota Single Stage - One E Pending Impl e fournitures et matériel élect IDA / 64340 basic national safety net syst Post Limited 5,540.00 0.00 2023-05-14 2023-07-09 2023-07-24 tions nvelope ementation romenagers de bureau au pro em fit du ST-RSU (02 Lots) BF-PFS-355231-GO-RFQ / Ac quisition de Système de sécu Request for Quota Single Stage - One E Pending Impl IDA / 54290 Project management Post Limited 5,000.00 0.00 2023-04-23 2023-06-02 2023-07-02 rité par vidéo surveillance au tions nvelope ementation profit du ST-RSU BF-PFS-355232-GO-RFQ / Ac quisition d'outils de communi Request for Quota Single Stage - One E Pending Impl cation (gadgets, tee shirt, cas IDA / 54290 Project management Post Limited 154,920.00 0.00 2023-04-16 2023-06-05 2023-09-03 tions nvelope ementation quette, etc) au profit de l'UGP et du ST RSU (O2 LOTS) BF-PFS-355370-GO-RFQ / Ac quisition de consommable inf Request for Quota Single Stage - One E Pending Impl IDA / 54290 Project management Post Limited 45,300.00 0.00 2023-04-24 2023-06-03 2023-07-03 ormatique au profit de l'unité tions nvelope ementation de gestion du projet filets soc iaux BF-PFS-355216-GO-RFQ / Câ blage informatique du bâtime Single Stage - One E Pending Impl IDA / 54290 Project management Post Request for Bids Open - National 160,000.00 0.00 2023-04-25 2023-04-30 2023-06-11 2023-07-11 2023-08-15 2024-02-11 nt du ST/RSU et l'interconnexi nvelope ementation on avec RESINA y compris le l ocal technique BF-PFS-362181-GO-RFQ / Ac quisition de matériel informat ique au profit des stagiaires d Request for Quota Single Stage - One E Pending Impl IDA / 54290 Project management Post Limited 20,000.00 0.00 2023-05-25 2023-06-11 2023-06-26 ans le cadre de l'initiative Ma tions nvelope ementation sse Critiques des Professionn els de Projets et Programmes de Développement BF-PFS-364234-GO-RFQ / Ac quisition de fournitures de bu Request for Quota Single Stage - One E Pending Impl reau dans le cadre du protoc IDA / 54290 Project management Post Limited 5,219.00 0.00 2023-06-03 2023-06-20 2023-07-05 tions nvelope ementation ole de collaboration avec l’Ag ence Nationale de la Formati on Professionnelle (ANFP) BF-PFS-364238-GO-RFQ / Ac quisition de matières d’œuvr Request for Quota Single Stage - One E Pending Impl e dans le cadre du protocole IDA / 54290 Project management Post Limited 36,300.00 0.00 2023-06-03 2023-06-20 2023-07-05 tions nvelope ementation de collaboration avec l’Agenc e Nationale de la Formation P rofessionnelle (ANFP) BF-PFS-364239-GO-RFQ / Ac quisition de matériels informa tiques et péri-informatiques d Request for Quota Single Stage - One E Pending Impl IDA / 54290 Project management Post Limited 4,480.00 0.00 2023-06-03 2023-06-20 2023-07-05 ans le cadre du protocole de tions nvelope ementation collaboration avec l’Agence N ationale de la Formation Prof essionnelle (ANFP) NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BF-PFS-17795-NC-RFB / Agen Cash transfers and awarenes Single Stage - One E ce de paiement région du Nor IDA / 54290 s programs for poor and vuln Post Request for Bids Open - National 170,000.00 0.00 Canceled 2017-07-05 2017-09-18 2017-07-05 2017-07-05 2017-07-05 2017-07-05 2017-07-05 nvelope d erable households BF-PFS-49964-NC-DIR / Assur ance Santé au profit du perso IDA / 54290 Project management Post Direct Selection Direct 180,000.00 106,631.92 Completed 2018-02-28 2018-03-22 2018-03-15 2018-03-26 2018-04-04 2018-05-23 2019-04-04 2019-05-31 nnel du PFS BF-PFS-25754-NC-RFB / Agen Cash transfers and awarenes Single Stage - One E ce de paiement pour le Boulki IDA / 54290 s programs for poor and vuln Post Request for Bids Open - National 110,000.00 0.00 Canceled 2017-08-22 2017-08-27 2017-10-08 2017-11-07 2017-12-12 2018-06-10 nvelope emdé, le Lorum et le Passoré erable households BF-PFS-38412-NC-DIR / Reno Cash transfers and awarenes uvellement Contrat Agence d IDA / 54290 s programs for poor and vuln Post Direct Selection Direct 180,000.00 156,584.39 Completed 2017-11-30 2016-11-03 2017-12-05 2018-01-09 2016-12-01 2018-07-08 2017-12-01 e paiement du Nord erable households BF-PFS-51763-NC-DIR / Assur IDA / 54290 Project management Post Direct Selection Direct 40,000.00 15,939.36 Completed 2018-03-12 2018-11-12 2018-03-22 2018-08-20 2018-04-20 2018-09-11 2019-04-20 2018-09-19 ance des véhicules et motos Page 4 BF-PFS-53695-NC-RFB / Agen Cash transfers and awarenes Single Stage - One E ce de paiement pour le Boulki TF / A3975 s programs for poor and vuln Post Request for Bids Open - National 110,000.00 116,965.80 Signed 2017-08-01 2017-08-17 2017-08-11 2018-04-18 2017-09-10 2017-09-26 2017-09-17 2017-09-26 2017-10-16 2017-10-20 2018-10-16 nvelope emdé, Loroum et Passoré erable households BF-PFS-30904-NC-RFQ / Recr utement d'agences de gardie Request for Quota Single Stage - One E IDA / 54290 Project management Post Limited 57,800.00 36,596.14 Completed 2018-05-01 2017-08-23 2018-06-26 2017-09-19 2019-06-26 2018-09-19 nnage et de sécurité pour le tions nvelope compte du Projet Filets Socia ux BF-PFS-57178-NC-RFB / Agen Cash transfers and awarenes Single Stage - One E ce de paiement dans le cadre IDA / 54290 s programs for poor and vuln Post Request for Bids Open - National 177,600.00 373,890.82 Signed 2018-04-23 2018-05-07 2018-04-28 2018-06-09 2018-09-28 2018-06-24 2018-09-29 2018-07-29 2019-04-29 2019-07-29 nvelope de la mise en oeuvre du PAD erable households EL BF-PFS-57176-NC-DIR / Assur ance des locaux de l'UGP et l IDA / 54290 Project management Post Direct Selection Direct 15,000.00 0.00 Canceled 2017-02-15 2017-02-20 2017-03-27 2018-03-27 es équipements du projet BF-PFS-48976-NC-RFQ / Tran Request for Quota Single Stage - One E sport et implantation des pla IDA / 54290 Project management Post Limited 10,000.00 0.00 Canceled 2018-03-25 2018-05-04 2018-05-19 tions nvelope ques du projet dans les 42 co mmunes BF-PFS-105867-NC-DIR / Tra Cash transfers and awarenes nsfert monétaires électroniqu IDA / 54290 s programs for poor and vuln Post Direct Selection Direct 727,000.00 0.00 Completed 2019-03-26 2019-04-01 2019-03-31 2019-04-01 2019-05-03 2019-06-21 2020-05-02 2019-06-21 es au profit des ménages bén erable households éficiaires de l'Est et du Centr e Est BF-PFS-114536-NC-DIR / Ren ouvellement de l'assurance s IDA / 54290 Project management Post Direct Selection Direct 123,000.00 103,139.07 Signed 2019-04-09 2019-04-01 2019-04-14 2019-04-10 2019-05-13 2019-05-31 2020-05-12 anté au profit du personnel d u Projet Filets Sociaux BF-PFS-52055-NC-RFQ / Acqu isition d'un système de gestio Request for Quota Single Stage - One E IDA / 54290 Project management Post Limited 70,000.00 0.00 Canceled 2018-04-02 2018-05-22 2018-07-21 n électronique et d'archivage tions nvelope des documents BF-PFS-17530-NC-RFQ / Assu Request for Quota Single Stage - One E IDA / 54290 Project management Post Limited 95,000.00 0.00 Canceled 2017-06-23 2017-07-10 2017-08-18 2018-02-14 rance maladie au profit du pe tions nvelope rsonnel BF-PFS-56782-NC-DIR / Recr utement d'un cabinet pour l'a IDA / 54290 Project management Post Direct Selection Direct 40,000.00 0.00 Canceled 2017-01-10 2017-01-15 2017-02-19 2018-02-19 ssistance technique et le recr utement du personnel du proj et BF-PFS-53839-NC-RFB / Réali Cash transfers and awarenes sation de théâtres-forums à l' Single Stage - One E IDA / 54290 s programs for poor and vuln Post Request for Bids Open - National 171,200.00 0.00 Canceled 2018-04-09 2018-04-14 2018-05-26 2018-06-02 2018-07-01 2018-09-29 Est, au Centre-Est, au Loroum nvelope erable households et au Passoré BF-PFS-140254-NC-DIR / Ren ouvellement de l'assurance d IDA / 54290 Project management Post Direct Selection Direct 20,000.00 15,828.79 Signed 2019-09-01 2019-09-01 2019-09-06 2019-09-02 2019-10-11 2019-09-19 2019-10-14 u matériel roulant du PFS BF-PFS-140249-NC-DIR / Ren Cash transfers and awarenes ouvellement du contrat de l'a TF / A3975 s programs for poor and vuln Post Direct Selection Direct 40,000.00 0.00 Signed 2019-10-22 2021-12-10 2019-10-27 2021-12-10 2019-12-01 2020-11-30 gence de paiement pour le Lo erable households rum et le Passoré BF-PFS-140262-NC-RFQ / Ag Request for Quota Single Stage - One E Pending Impl ence de sécurité pour les loca IDA / 54290 Project management Post Limited 22,800.00 0.00 2019-10-25 2019-12-16 2020-12-15 tions nvelope ementation ux du Projet Filets Sociaux BF-PFS-140246-NC-RFQ / Rec Request for Quota Single Stage - One E rutement d'agences de netto IDA / 54290 Project management Post Limited 21,600.00 0.00 Signed 2019-10-25 2019-10-28 2019-12-16 2020-12-15 tions nvelope yage pour le compte du Proje t Filets Sociaux BF-PFS-99913-NC-RFB / Agen Cash transfers and awarenes Single Stage - One E ce de paiement pour les tran IDA / 54290 s programs for poor and vuln Post Request for Bids Open - National 530,000.00 0.00 Canceled 2019-02-25 2019-03-05 2019-03-07 2019-04-06 2019-04-13 2019-05-12 2020-05-11 nvelope sferts électroniques dans la r erable households égion de l'Est BF-PFS-140261-NC-DIR / Ren ouvellement du contrat de l'a Cash transfers and awarenes Pending Impl gence pour le transfert moné IDA / 54290 s programs for poor and vuln Post Direct Selection Direct 376,960.00 0.00 2019-11-04 2019-11-09 2019-12-14 2020-12-13 ementation taires électroniques au profit erable households des ménages bénéficiaires de l'Est et du Centre Est BF-PFS-168971-NC-DIR / Tra nsferts monétaires physiques Cash transfers and awarenes au profit des bénéficiaires de IDA / D4760 s programs for poor and vuln Post Direct Selection Direct 22,000.00 0.00 Signed 2020-04-20 2020-03-10 2020-04-25 2020-04-02 2020-05-20 2020-06-19 la subvention productive au ti erable households tre de la mesure 6 dans la ré gion du Nord BF-PFS-168977-NC-RFQ / Ass Request for Quota Single Stage - One E urance maladie du personnel IDA / D4760 Project management Post Limited 90,000.00 0.00 Signed 2020-04-29 2020-05-05 2020-06-24 2020-12-21 tions nvelope du projet filets sociaux BF-PFS-171201-NC-DIR / Tra nsferts monétaires électroniq ue au profit des personnes vu Contingent Emergency Resp IDA / D4760 Post Direct Selection Direct 92,000.00 0.00 Signed 2020-04-30 2020-03-05 2020-05-03 2020-04-24 2020-05-15 2020-08-13 lnérables affectées par la pan onse Component demie du COVID 19 et les per sonnes indigentes de Ouagad ougou BF-PFS-195596-NC-RFQ / Ass Request for Quota Single Stage - One E urance des véhicules et moto IDA / D4760 Project management Post Limited 20,000.00 0.00 Signed 2020-09-30 2020-11-20 2020-11-01 2021-11-01 tions nvelope s du projet BF-PFS-54420-NC-RFB / Réali Cash transfers and awarenes Single Stage - One E sation de supports audio visu IDA / 54290 s programs for poor and vuln Post Request for Bids Open - National 300,000.00 0.00 Canceled 2018-04-20 2019-10-21 2018-04-25 2018-06-06 2018-07-06 2018-08-10 2019-02-06 nvelope el au profit du projet Filets so erable households ciaux BF-PFS-229261-NC-DIR / Séle ction des opérateurs de trans ferts monétaires au profit des ménages internes pauvres et Cash transfers and awarenes Under Imple vulnérables issues des ména IDA / 64340 s programs for poor and vuln Post Direct Selection Direct 780,000.00 0.00 2021-04-14 2021-06-03 2021-04-19 2021-05-24 2021-11-20 mentation ges des déplacés, des comm erable households unautés hôtes et des réfugiés de la Boucle du Mouhoun, du Nord, du Centre nord, du Sah el et du Centre BF-PFS-231181-NC-RFQ / Sél ection de radios communauta Cash transfers and awarenes Request for Quota Single Stage - One E ires pour la réalisation d'activ IDA / 64340 s programs for poor and vuln Post Limited 250,000.00 207,344.47 Signed 2021-04-27 2021-07-14 2021-06-22 2021-12-04 2021-12-19 tions nvelope ités de sensibilisation et de c erable households ommunication du projet Filets sociaux BF-PFS-236703-NC-DIR / Ren ouvellement du contrat de l’a IDA / 64340 Project management Post Direct Selection Direct 98,000.00 51,066.53 Signed 2021-05-28 2021-05-10 2021-06-02 2021-05-17 2021-07-07 2021-07-16 2022-01-03 gence d’assurance maladie d u personnel du Projet Filets S ociaux Page 5 BF-PFS-236707-NC-DIR / Ren ouvellement des contrats d'e ntretien et de maintenance d IDA / 64340 Project management Post Direct Selection Direct 52,000.00 39,278.83 Signed 2021-05-28 2021-06-15 2021-06-02 2021-06-22 2021-07-07 2021-07-13 2022-01-03 e divers équipements du Proj et Filets Sociaux (Groupe élec trogène, plomberie sanitaire, climatiseurs, matériel roulant ). BF-PFS-241483-NC-DIR / Ren ouvellement du contrat de m aintenance préventive et cur IDA / 64340 Project management Post Direct Selection Direct 16,000.00 0.01 Signed 2021-06-29 2021-06-10 2021-07-04 2021-06-22 2021-08-08 2021-07-13 2022-02-04 ative du matériel informatiqu e et péri-informatique du Proj et Filets Sociaux BF-PFS-244343-NC-RFB / Rec Cash transfers and awarenes rutement d’un prestataire po Single Stage - One E IDA / 64340 s programs for poor and vuln Post Request for Bids Open - National 457,760.00 0.00 Signed 2021-07-26 2021-11-15 2021-07-31 2022-05-05 2021-09-11 2021-12-20 2021-10-11 2021-12-30 2021-11-15 2022-05-14 ur la production de boîtes a i nvelope erable households mages au profit du projet filet s sociaux BF-PFS-261515-NC-RFQ / Rec rutement d’une agence de co Cash transfers and awarenes Request for Quota Single Stage - One E mmunication pour la réalisati IDA / 64340 s programs for poor and vuln Post Limited 62,600.00 0.00 Signed 2021-11-15 2021-11-02 2022-01-10 2021-12-01 2022-07-09 tions nvelope on de films documentaires au erable households profit du Projet Filets Sociaux BF-PFS-264482-NC-DIR / Ren ouvellement du contrat d'ass IDA / 64340 Project management Post Direct Selection Direct 18,956.00 12,620.30 Signed 2021-11-29 2021-10-04 2021-12-04 2021-10-08 2022-01-08 2021-12-01 2022-07-07 urance des véhicules de l'unit é de gestion du Projet Filets S ociaux BF-PFS-275635-NC-DIR / Ren ouvellement du contrat d’ent IDA / 64340 Project management Post Direct Selection Direct 30,000.00 19,326.63 Signed 2022-01-31 2021-12-08 2022-02-05 2021-12-13 2022-03-12 2022-01-02 2022-09-08 retien et de nettoyage des lo caux de l’unité de gestion du Projet Filets Sociaux BF-PFS-275637-NC-DIR / Ren ouvellement du contrat de ga rdiennage et de surveillance IDA / 64340 Project management Post Direct Selection Direct 30,000.00 25,156.93 Signed 2022-01-31 2021-12-10 2022-02-05 2021-12-13 2022-03-12 2022-01-02 2022-09-08 des locaux de l’unité de gesti on du Projet Filets Sociaux BF-PFS-275639-NC-DIR / Ren ouvellement des contrats d'e ntretien et de maintenance d e divers équipements du Proj IDA / 64340 Project management Post Direct Selection Direct 78,000.00 52,429.40 Signed 2022-02-08 2022-01-02 2022-02-13 2022-01-05 2022-03-20 2022-01-02 2022-09-16 et Filets Sociaux (Groupe élec trogène, plomberie sanitaire, climatiseurs, matériel roulant , matériel informatique, télép honique et vidéo surveillance ) BF-PFS-278580-NC-DIR / Con trat cadre avec MOOV AFRICA pour l'acquisition de téléphon es portables, de cartes SIM id Cash transfers and awarenes entifiées et munies de compt IDA / 64340 s programs for poor and vuln Post Direct Selection Direct 1,322,412.00 1,466,712.00 Signed 2022-02-16 2021-03-08 2022-02-21 2021-04-08 2022-03-28 2021-06-09 2022-09-24 es mobiles et d'opérations de erable households transferts monétaires électro niques au profit des bénéficia ires dans diverses régions du Burkina Faso. BF-PFS-278611-NC-DIR / Con trat cadre avec WIZALL BURK INA pour l'acquisition de télé phones portables, de cartes S Cash transfers and awarenes IM identifiées et munies de co IDA / 64340 s programs for poor and vuln Post Direct Selection Direct 446,000.00 363,933.00 Signed 2022-02-16 2021-03-10 2022-02-21 2021-04-08 2022-03-28 2021-06-09 2022-09-24 mptes mobiles et d'opération erable households s de transferts monétaires él ectroniques au profit des bén éficiaires dans diverses régio ns du Burkina Faso. BF-PFS-278620-NC-DIR / Con trat cadre avec ORANGE MON EY pour l'acquisition de télép hones portables, de cartes SI Cash transfers and awarenes M identifiées et munies de co IDA / 64340 s programs for poor and vuln Post Direct Selection Direct 696,000.00 566,118.00 Signed 2022-02-16 2021-03-08 2022-02-21 2021-04-08 2022-03-28 2021-08-05 2022-09-24 mptes mobiles et d'opération erable households s de transferts monétaires él ectroniques au profit des bén éficiaires dans diverses régio ns du Burkina Faso. BF-PFS-293368-NC-RFQ / Ass urance maladie au profit du p Request for Quota Single Stage - One E Pending Impl IDA / 64340 Project management Post Limited 90,000.00 0.00 2022-05-24 2022-07-19 2023-01-15 ersonnel de l’unité de gestion tions nvelope ementation du projet filets sociaux BF-PFS-297616-NC-DIR / Ren ouvellement du contrat d'ass urance maladie au profit du p IDA / 64340 Project management Post Direct Selection Direct 90,000.00 0.00 Signed 2022-06-01 2022-05-30 2022-06-06 2021-05-31 2022-07-11 2023-01-07 ersonnel de l'unité de gestion du Projet Filets Sociaux BF-PFS-355085-NC-DIR / Ren ouvellement des contrats d'e ntretien et de maintenance d e divers équipements du Proj Pending Impl IDA / 64340 Project management Post Direct Selection Direct - National 72,000.00 0.00 2023-04-06 2023-04-11 2023-05-16 2024-05-10 et Filets Sociaux (Groupe élec ementation trogène, plomberie sanitaire, climatiseurs, matériel roulant , matériel informatique, télép honique et vidéo surveillance ) BF-PFS-355208-NC-DIR / Ren ouvellement du contrat d'Ent Pending Impl IDA / 64340 Project management Post Direct Selection Direct - National 30,000.00 0.00 2023-04-05 2023-04-10 2023-05-15 2024-05-14 retien et nettoyage des locau ementation x de l'unité de gestion du pro jet filets sociaux BF-PFS-355209-NC-DIR / Ren ouvellement du contrat de ga Pending Impl rdiennage et surveillance des IDA / 64340 Project management Post Direct Selection Direct - National 30,000.00 0.00 2023-04-05 2023-04-10 2023-05-15 2023-11-11 ementation locaux de l'unité de gestion du projet filets sociaux BF-PFS-355227-NC-DIR / Mai Request for Quota Single Stage - One E Pending Impl ntenance informatique au pro IDA / 64340 Project management Post Limited 12,000.00 0.00 2023-04-23 2023-06-18 2023-12-15 tions nvelope ementation fit du ST-RSU BF-PFS-355228-NC-RFQ / Ent Request for Quota Single Stage - One E Pending Impl IDA / 64340 Project management Post Limited 6,000.00 0.00 2023-04-23 2023-06-18 2024-04-13 retien des motos au profit du tions nvelope ementation ST-RSU BF-PFS-355229-NC-RFQ / Ent Request for Quota Single Stage - One E Pending Impl IDA / 64340 Project management Post Limited 7,000.00 0.00 2023-04-23 2023-06-18 2024-04-13 retien de locaux au profit du tions nvelope ementation ST-RSU BF-PFS-355230-NC-RFQ / Gar Request for Quota Single Stage - One E Pending Impl diennage de locaux au profit IDA / 64340 Project management Post Limited 5,000.00 0.00 2023-04-23 2023-06-18 2024-04-13 tions nvelope ementation du ST-RSU Page 6 BF-PFS-355328-NC-DIR / Ren ouvellement du contrat de RA Cash transfers and awarenes DIO SAVANE FM pour la réalis Pending Impl IDA / 64340 s programs for poor and vuln Post Direct Selection Direct - National 59,023.00 0.00 2023-04-06 2023-04-11 2023-05-16 2024-05-10 ation des couvertures médiati ementation erable households ques des activités du Projet Fi lets Sociaux dans la région d u Centre BF-PFS-358249-NC-DIR / Ren ouvellement du contrat de RA Cash transfers and awarenes DIO MANEGDA KAYA pour la r Pending Impl IDA / 64340 s programs for poor and vuln Post Direct Selection Direct - National 49,868.00 0.00 2023-04-24 2023-04-29 2023-06-03 2024-05-28 éalisation des couvertures m ementation erable households édiatiques des activités du Pr ojet Filets Sociaux dans la rég ion du Centre Nord. BF-PFS-358252-NC-DIR / Ren ouvellement du contrat de la Cash transfers and awarenes RADIO MUNICIPALE DE DORI Pending Impl IDA / 64340 s programs for poor and vuln Post Direct Selection Direct - National 48,860.00 0.00 2023-04-24 2023-04-29 2023-06-03 2024-01-19 pour la réalisation des couver ementation erable households tures médiatiques des activit és du Projet Filets Sociaux da ns la région du Sahel. BF-PFS-358254-NC-DIR / Ren ouvellement du contrat de RA Cash transfers and awarenes DIO SALAKI pour la réalisatio Pending Impl IDA / 64340 s programs for poor and vuln Post Direct Selection Direct - National 49,860.00 0.00 2023-04-24 2023-04-29 2023-06-03 2024-05-28 n des couvertures médiatique ementation erable households s des activités du Projet Filets Sociaux dans la région de la Boucle du Mouhoun. BF-PFS-358255-NC-DIR / Ren ouvellement du contrat de RA Cash transfers and awarenes DIO LA VOIX DU PAYSAN pour Pending Impl IDA / 64340 s programs for poor and vuln Post Direct Selection Direct - National 49,860.00 0.00 2023-04-24 2023-04-29 2023-06-03 2024-05-28 la réalisation des couvertures ementation erable households médiatiques des activités du Projet Filets Sociaux dans la r égion du Nord. CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Techni Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes cal Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BF-PFS-22748-CS-CQS / Recr utement de prestataires pour Laying the foundations for a Consultant Qualifi la réalisation de vidéos comm IDA / 54290 basic national safety net syst Post Open - National 28,000.00 0.00 Canceled 2017-08-20 2017-09-10 2017-10-24 2017-11-23 2017-12-28 2018-06-26 cation Selection unautaires au profit des villag em es de la région du Nord BF-PFS-49406-CS-QCBS / Au Quality And Cost-B dit des comptes 2018 et 201 IDA / 54290 Project management Post Open - National 40,000.00 96,319.84 Signed 2018-04-16 2018-06-18 2018-05-07 2018-06-20 2018-09-05 2018-07-20 2019-01-18 2018-08-19 2019-01-21 2018-09-23 2019-04-08 2018-10-22 2019-06-10 2018-12-21 ased Selection 9 du projet BF-PFS-68278-CS-CQS / ONG Cash transfers and awarenes Consultant Qualifi pour la sensibilisation dans la IDA / 54290 s programs for poor and vuln Post Open - National 540,000.00 500,052.11 Signed 2017-03-10 2017-04-10 2017-03-31 2017-05-14 2017-12-28 2017-06-13 2018-01-25 2017-07-18 2018-10-03 2018-07-18 cation Selection région de l'Est erable households BF-PFS-68283-CS-CQS / ONG Cash transfers and awarenes Consultant Qualifi pour la sensibilisation dans la IDA / 54290 s programs for poor and vuln Post Open - National 300,000.00 260,150.35 Signed 2017-03-10 2017-04-10 2017-03-31 2017-05-14 2017-12-28 2017-06-13 2018-01-25 2017-07-18 2018-10-03 2018-07-18 cation Selection région du Centre Est erable households BF-PFS-68280-CS-CQS / Réali Cash transfers and awarenes sation de 51 cinés-débats au Consultant Qualifi IDA / 54290 s programs for poor and vuln Post Open - National 30,100.00 22,564.70 Signed 2017-03-10 2017-03-10 2017-03-31 2017-05-14 2017-12-28 2017-06-13 2018-01-26 2017-07-18 2018-08-31 2017-08-17 YATENGA (Ouahigouya, Oula cation Selection erable households et Namissiguima) BF-PFS-68342-CS-CQS / Réali Cash transfers and awarenes sation de 47 cinés-débats au Consultant Qualifi IDA / 54290 s programs for poor and vuln Post Open - National 28,000.00 24,548.44 Completed 2017-03-10 2017-03-10 2017-03-31 2017-05-14 2017-12-28 2017-06-13 2018-01-26 2017-07-18 2018-08-31 2017-08-12 2019-01-28 YATENGA (Barga,Kain, Koum cation Selection erable households bri,Tangaye,Thiou et Zogoré) BF-PFS-68341-CS-CQS / Réali Cash transfers and awarenes Consultant Qualifi sation de 29 cinés-débats au IDA / 54290 s programs for poor and vuln Post Open - National 17,200.00 12,830.91 Signed 2017-03-10 2017-03-10 2017-03-31 2017-05-14 2017-12-28 2017-06-13 2018-01-26 2017-07-18 2018-09-13 2017-09-01 cation Selection ZONDOMA erable households BF-PFS-68281-CS-CQS / Réali Cash transfers and awarenes sation de 51 théâtres forums Consultant Qualifi IDA / 54290 s programs for poor and vuln Post Open - National 36,200.00 27,077.63 Signed 2017-03-10 2017-03-10 2017-03-31 2017-05-14 2017-12-28 2017-06-13 2018-01-26 2017-07-18 2018-08-31 2017-08-17 au YATENGA (Ouahigouya, O cation Selection erable households ula et Namissiguima) BF-PFS-68272-CS-CQS / Réali Cash transfers and awarenes sation de 47 théâtres forums Consultant Qualifi IDA / 54290 s programs for poor and vuln Post Open - National 34,000.00 29,445.60 Signed 2017-03-10 2017-03-10 2017-03-31 2017-05-14 2017-12-28 2017-06-13 2018-01-26 2017-07-18 2018-08-31 2017-08-12 au YATENGA (Barga,Kain, Ko cation Selection erable households umbri,Tangaye,Thiou et Zogo ré) BF-PFS-68276-CS-CQS / Réali Cash transfers and awarenes Consultant Qualifi sation de 29 théâtres forums IDA / 54290 s programs for poor and vuln Post Open - National 21,000.00 18,025.35 Signed 2017-03-10 2017-03-10 2017-03-31 2017-05-14 2017-12-28 2017-06-13 2018-01-26 2017-07-18 2018-08-31 2017-08-12 cation Selection au ZONDOMA erable households BF-PFS-17941-CS-CQS / ONG Cash transfers and awarenes Consultant Qualifi pour la Sensibilisation dans la IDA / 54290 s programs for poor and vuln Post Open - National 100,000.00 0.00 Canceled 2017-07-03 2017-04-10 2017-07-03 2017-09-07 2017-07-03 2017-12-28 2017-07-03 2017-07-03 2017-07-03 cation Selection Région de l'Est et du Centre- erable households Est BF-PFS-17935-CS-CQS / Sens Cash transfers and awarenes ibilisation par le canal du thé Consultant Qualifi IDA / 54290 s programs for poor and vuln Post Open - National 40,000.00 0.00 Canceled 2017-05-15 2017-09-11 2017-05-15 2017-05-15 2017-05-15 2017-05-15 2017-05-15 atre forum et des cinés débat cation Selection erable households s Région du Nord BF-PFS-30755-CS-QCBS / Ser Laying the foundations for a vice de consultants pour la ré Consultant Qualifi IDA / 54290 basic national safety net syst Post Open - National 195,000.00 0.00 Canceled 2017-10-25 2017-11-27 2017-11-15 2017-12-06 2017-12-29 2018-01-28 2018-03-04 2018-08-31 alisation de l'enquête de bas cation Selection em e dans les Provinces du Nord BF-PFS-100385-CS-CQS / Rec rutement de prestataires pou Cash transfers and awarenes Consultant Qualifi r la réalisation de vidéos com TF / A3975 s programs for poor and vuln Post Open - National 54,000.00 0.00 Signed 2019-02-25 2019-02-17 2019-03-27 2023-06-01 2019-04-08 2019-08-26 2019-04-23 2019-10-24 2019-05-22 2019-08-20 cation Selection munautaires au profit des vill erable households ages de la région du Nord BF-PFS-106835-CS-CQS / Proj ections d'une vidéo commun Cash transfers and awarenes Consultant Qualifi autaire dans le cadre de la mi TF / A3975 s programs for poor and vuln Post Open - National 54,000.00 45,862.91 Signed 2019-02-25 2019-03-24 2019-03-27 2019-09-03 2019-04-08 2019-09-11 2019-04-23 2019-10-17 2019-05-22 2019-10-28 2019-08-20 cation Selection se en œuvre des mesures pro erable households ductives dans la région du No rd BF-PFS-120124-CS-LCS / Org Cash transfers and awarenes anisation des microprogram Least Cost Selecti IDA / 54290 s programs for poor and vuln Post Open - National 231,000.00 0.00 Canceled 2019-09-02 2019-10-07 2019-09-23 2019-11-06 2019-12-04 2019-12-18 2020-01-15 2020-02-19 2020-05-19 mes, des cinés -débats et des on erable households théatres-forum dans la Régio n du Nord Page 7 BF-PFS-120123-CS-LCS / Org Cash transfers and awarenes anisation des microprogram Least Cost Selecti Under Implement IDA / 54290 s programs for poor and vuln Post Open - National 130,300.00 0.00 2019-09-02 2019-10-07 2019-09-23 2019-11-06 2019-12-04 2020-01-03 2020-02-07 2020-03-13 2020-06-11 mes, des cinés -débats et des on ation erable households théatres-forum dans la Régio n de l'Est BF-PFS-119884-CS-LCS / Org Cash transfers and awarenes anisation des microprogram Least Cost Selecti IDA / 54290 s programs for poor and vuln Post Open - National 206,900.00 0.00 Canceled 2019-09-02 2019-10-07 2019-09-23 2019-11-06 2019-12-04 2020-01-03 2020-01-31 2020-02-28 2020-05-28 mes, des cinés -débats et des on erable households théatres-forum dans la Régio n du Centre-Est BF-PFS-49650-CS-CQS / Réali Consultant Qualifi sation d'émissions spéciales r IDA / 54290 Project management Post Open - National 12,000.00 0.00 Canceled 2018-05-07 2018-05-28 2018-07-04 2018-08-03 2018-09-01 2018-11-30 cation Selection adio/télé sur le projet BF-PFS-49397-CS-CQS / Form ation des PRC à l'utilisation d Consultant Qualifi es données géosatellitaires p TF / A3975 Project management Post Open - National 24,000.00 0.00 Canceled 2018-05-10 2018-05-31 2018-07-14 2018-07-21 2018-08-19 2018-09-18 cation Selection our la production et la comm ercialisation des produits agr opastoraux BF-PFS-49394-CS-CQS / Appu i/accompagnement du projet Cash transfers and awarenes Consultant Qualifi en ACV et GERME dans le cad TF / A3975 s programs for poor and vuln Post Open - National 24,000.00 0.00 Canceled 2018-04-09 2018-04-30 2018-06-13 2018-06-27 2018-07-26 2018-09-24 cation Selection re de la mise en œuvre des erable households mesures d'accompagnement productives BF-PFS-119673-CS-CQS / Org Cash transfers and awarenes anisation des microprogram Consultant Qualifi IDA / 54290 s programs for poor and vuln Post Open - National 700.00 0.00 Canceled 2019-09-02 2019-09-23 2019-10-23 2019-11-22 2019-12-11 2019-12-18 mes, des cinés -débats et des cation Selection erable households théatres-forum dans la Régio n du Sahel BF-PFS-119885-CS-QCBS / C Laying the foundations for a onception et développement Quality And Cost-B IDA / 54290 basic national safety net syst Post Open - National 500,000.00 0.00 Canceled 2019-11-28 2019-09-24 2019-12-19 2020-02-01 2020-02-29 2020-03-30 2020-05-04 2020-06-08 2021-06-08 du Registre Unique et la form ased Selection em ation aux outils de développe ment BF-PFS-119672-CS-CQS / Org anisation des microprogram Cash transfers and awarenes Consultant Qualifi mes, des cinés -débats et des IDA / 54290 s programs for poor and vuln Post Open - National 750.00 0.00 Canceled 2019-09-02 2019-10-07 2019-09-23 2019-10-23 2019-11-22 2019-12-11 2019-12-18 cation Selection théatres-forum dans la Provin erable households ce du BOULKIEMDE (Région d u Centre-Ouest) BF-PFS-49396-CS-QCBS / Ré Laying the foundations for a Quality And Cost-B alisation de l'enquête de bas TF / A3975 basic national safety net syst Post Open - National 600,000.00 0.00 Canceled 2018-04-02 2018-04-23 2018-06-06 2018-07-06 2018-08-05 2018-09-09 2018-10-14 2019-01-12 ased Selection e dans la région du Nord em BF-PFS-49393-CS-QCBS / Enq Cash transfers and awarenes Quality And Cost-B uête de base pour l'évaluatio TF / A3975 s programs for poor and vuln Post Open - National 800,000.00 0.00 Canceled 2018-03-12 2018-04-02 2018-05-16 2018-06-15 2018-07-15 2018-08-19 2018-09-23 2018-11-22 ased Selection n d'impact au Nord erable households BF-PFS-167750-CS-CQS / Sél ection de cabinet pour le recr Consultant Qualifi IDA / 54290 Project management Post Open - National 12,000.00 0.00 Signed 2020-04-13 2020-04-09 2020-04-15 2020-04-26 2020-05-12 2020-05-01 2020-05-21 2020-05-09 2020-07-08 utement du personnel compl cation Selection émentaire du PFS BF-PFS-171202-CS-CQS / Ela boration d’une stratégie glob Consultant Qualifi IDA / 54290 Project management Post Open - National 19,500.00 0.00 Signed 2020-04-20 2020-05-20 2020-04-30 2023-05-24 2020-05-06 2020-05-12 2020-05-11 2020-05-20 2020-06-09 2020-08-08 ale de communication du MF cation Selection SNFAH et du projet filets soci aux BF-PFS-168966-CS-CQS / ON Productive Labor-Intensive P Consultant Qualifi G locale pour la mise en œuv IDA / 64340 Post Open - National 85,000.00 0.00 Canceled 2020-04-23 2020-04-24 2020-05-14 2020-06-27 2020-07-12 2020-08-16 2021-02-12 ublic Works (LIPW) Program cation Selection re des THIMO au Séno BF-PFS-202211-CS-FBS / ON Cash transfers and awarenes G locale pour la mise en œuv Fixed Budget Sele IDA / 64340 s programs for poor and vuln Post Open - International 672,000.00 534,634.88 Signed 2020-11-09 2021-04-02 2020-11-24 2021-01-07 2021-02-18 2021-02-19 2021-04-13 2021-03-21 2021-04-16 2021-04-25 2021-05-25 2021-05-30 2021-07-16 2022-05-30 re des activités du projet dan ction erable households s la région du Sahel BF-PFS-228650-CS-QBS / Rec rutement d’un cabinet pour l’ Cash transfers and awarenes Quality Based Sele Under Implement élaboration d’un manuel d’au IDA / 64340 s programs for poor and vuln Post Open - National 110,130.00 0.00 2021-04-09 2021-09-17 2021-04-30 2021-06-13 2021-07-11 2021-08-10 2021-09-09 2021-10-14 2022-10-14 ction ation dit et d’une cartographie des erable households risques pour le projet filets so ciaux BF-PFS-205406-CS-FBS / Rec rutement de trois (03) ONGs l Cash transfers and awarenes ocale pour la mise en œuvre Fixed Budget Sele IDA / 64340 s programs for poor and vuln Prior Open - International 2,016,000.00 0.00 Canceled 2020-11-18 2021-09-13 2020-12-09 2021-01-22 2021-02-19 2021-03-21 2021-04-25 2021-05-30 2022-05-30 des activités dans les régions ction erable households de la Boucle du Mouhoun, du Centre nord et du Nord. BF-PFS-257964-CS-FBS / Rec rutement d’ONG locale pour l Cash transfers and awarenes Fixed Budget Sele a mise en œuvre des activité IDA / 64340 s programs for poor and vuln Post Open - National 1,316,000.00 1,062,075.07 Signed 2021-10-12 2021-09-13 2021-11-02 2021-12-16 2021-07-19 2022-01-13 2021-08-09 2022-02-12 2021-08-17 2022-03-19 2021-11-29 2022-04-23 2022-01-29 2023-04-23 ction s dans les nouvelles zones d’i erable households ntervention du Projet Filets S ociaux (Centre Nord) BF-PFS-257966-CS-FBS / Rec rutement d’ONG locale pour l Cash transfers and awarenes Fixed Budget Sele a mise en œuvre des activité IDA / 64340 s programs for poor and vuln Post Open - National 672,000.00 486,271.29 Signed 2021-10-12 2021-09-13 2021-11-02 2021-12-16 2021-07-19 2022-01-13 2021-08-09 2022-02-12 2021-08-17 2022-03-19 2021-08-17 2022-04-23 2022-01-21 2023-04-23 ction s dans les nouvelles zones d’i erable households ntervention du Projet Filets S ociaux (Nord) BF-PFS-257971-CS-FBS / Rec rutement d’ONG locale pour l Cash transfers and awarenes a mise en œuvre des activité Fixed Budget Sele IDA / 64340 s programs for poor and vuln Post Open - National 1,120,000.00 905,642.17 Signed 2021-10-12 2021-09-13 2021-11-02 2021-12-16 2021-07-19 2022-01-13 2021-08-09 2022-02-12 2021-08-17 2022-03-19 2021-11-30 2022-04-23 2022-01-21 2023-04-23 s dans les nouvelles zones d’i ction erable households ntervention du Projet Filets S ociaux (Boucle du Mouhoun) BF-PFS-257989-CS-CQS / Rec rutement de cabinets pour la Cash transfers and awarenes réalisation de Post Distributio Consultant Qualifi Under Implement IDA / 64340 s programs for poor and vuln Post Open - National 262,360.00 0.00 2021-10-28 2021-11-25 2021-11-18 2022-01-01 2022-01-31 2022-03-07 2022-09-03 n Monitoring (PDM) ou enquê cation Selection ation erable households te post paiement dans les rég ions d’intervention du Projet Filets Sociaux BF-PFS-257992-CS-CQS / Rec rutement de cabinets pour la Cash transfers and awarenes réalisation des appels téléph Consultant Qualifi Pending Impleme IDA / 64340 s programs for poor and vuln Post Open - National 76,546.00 0.00 2021-10-28 2021-11-18 2022-01-01 2022-01-31 2022-03-07 2022-09-03 oniques ou Phone Call dans le cation Selection ntation erable households s différentes régions d’interv ention du Projet Filets Sociau x. BF-PFS-264480-CS-LCS / Aud it financier et comptable du p Least Cost Selecti IDA / 64340 Project management Post Open - National 120,000.00 0.00 Signed 2021-11-30 2021-11-19 2021-12-21 2023-06-08 2022-02-03 2022-10-19 2022-03-03 2021-03-15 2022-04-02 2022-06-07 2022-05-07 2022-08-22 2022-06-11 2022-12-08 rojet pour les exercices 2021, on 2022, 2023 et la période de g râce Page 8 BF-PFS-293362-CS-CQS / Rec rutement d’une ONG pour la conception des outils et la for Laying the foundations for a Consultant Qualifi Under Implement mation des animateurs des O IDA / 64340 basic national safety net syst Post Open - National 170,000.00 0.00 2022-05-09 2022-05-20 2022-05-30 2022-07-13 2022-08-12 2022-09-16 2023-03-15 cation Selection ation NG sur les mesures d’accomp em agnement productives dans l es régions du nord et du Sah el du Burkina Faso BF-PFS-316349-CS-CQS / Rec rutement d’un cabinet charge Cash transfers and awarenes du recrutement et de la gesti Consultant Qualifi IDA / 64340 s programs for poor and vuln Post Open - National 4,358.00 0.00 Signed 2022-09-16 2022-10-10 2022-09-26 2023-06-15 2022-10-06 2022-10-22 2022-10-11 2022-11-15 2022-10-17 2023-10-12 on d’opérateurs pour l’opérat cation Selection erable households ionnalisation du centre d’app el du projet filets sociaux BF-PFS-320834-CS-CQS / Rec rutement d’une agence de co Cash transfers and awarenes Consultant Qualifi mmunication pour la mise en IDA / 64340 s programs for poor and vuln Post Open - National 20,000.00 0.00 Signed 2022-10-17 2022-10-17 2022-10-27 2023-06-03 2022-11-06 2022-12-12 2022-11-11 2023-02-09 2022-11-17 2023-11-17 cation Selection œuvre des activités de comm erable households unication du projet filets soci aux. BF-PFS-327451-CS-CQS / Sél Cash transfers and awarenes ection d’un cabinet en charge Consultant Qualifi IDA / 64340 s programs for poor and vuln Post Open - National 2,000.00 0.00 Signed 2022-11-28 2023-01-17 2022-12-08 2023-03-07 2022-12-18 2022-11-26 2022-12-23 2022-12-08 2022-12-29 2023-01-28 du recrutement d’un (e) spéci cation Selection erable households aliste en sauvegardes sociale s du PFS-BNS BF-PFS-355233-CS-CQS / Sél ection d'un cabinet pour le re Consultant Qualifi Pending Impleme IDA / 64340 Project management Post Open - National 20,000.00 0.00 2023-04-30 2023-05-21 2023-07-04 2023-08-03 2023-09-07 2024-03-05 crutement de personnel au pr cation Selection ntation ofit de l'Unité de gestion du P rojet Filets Sociaux BF-PFS-355324-CS-CDS / Rec rutement d'un consultant pou Laying the foundations for a r la formation des animateurs Consultant Qualifi Pending Impleme IDA / 64340 basic national safety net syst Post Open - National 430,776.00 0.00 2023-04-24 2023-05-15 2023-06-13 2023-07-13 2023-08-17 2024-05-13 des ONG et des équipes proje cation Selection ntation em t en inclusion économique (F ormation et suivi AVEC, coac hing et PAS) BF-PFS-355335-CS-CQS / Rec rutement d'un consultant pou r la mise en place d'un systè Consultant Qualifi Pending Impleme IDA / 64340 Project management Post Open - National 25,800.00 0.00 2023-04-25 2023-05-16 2023-06-29 2023-07-29 2023-09-02 2023-10-17 me de secours Interne de sau cation Selection ntation vegarde et de restauration de s données des application MI S et de Planification BF-PFS-355348-CS-CQS / Ela Consultant Qualifi Under Implement boration de la Stratégie de co IDA / 64340 Project management Post Open - National 20,000.00 0.00 2023-04-10 2020-04-30 2023-05-01 2023-06-14 2023-07-14 2023-08-18 2023-10-02 cation Selection ation mmunication du RSU (Cabine t) BF-PFS-355351-CS-CQS / Rec rutement d'ONG pour la mise en œuvre des activités de cib Laying the foundations for a Quality And Cost-B Pending Impleme lage communautaire dans 05 IDA / 64340 basic national safety net syst Prior Open - National 2,625,000.00 0.00 2023-05-08 2023-05-29 2023-07-12 2023-08-09 2023-09-08 2023-10-13 2023-11-17 2024-01-01 ased Selection ntation régions dans le cadre de l'op em érationnalisation du Registre social unique (RSU) (mise à l' echelle) BF-PFS-365491-CS-QCBS / R ecrutement d’une ONG pour l a mise en œuvre des activité Cash transfers and awarenes Consultant Qualifi Under Implement s de ciblage communautaire IDA / 64340 s programs for poor and vuln Post Open - National 272,930.00 0.00 2023-06-12 2023-06-26 2023-06-26 2023-07-31 2023-08-05 2023-08-15 2023-09-29 cation Selection ation dans la région du Nord dans l erable households e cadre de l’opérationnalisati on du Registre social unique ( RSU) (phase de mise à l’échel le) BF-PFS-365495-CS-QCBS / R ecrutement d’une ONG pour l a mise en œuvre des activité s de ciblage communautaire Cash transfers and awarenes Consultant Qualifi Under Implement dans la région de la Boucle d IDA / 64340 s programs for poor and vuln Post Open - National 329,270.00 0.00 2023-06-12 2023-06-26 2023-06-26 2023-07-31 2023-08-05 2023-08-15 2023-09-29 cation Selection ation u Mouhoun et des Hauts-Bass erable households ins dans le cadre de l’opérati onnalisation du Registre soci al unique (RSU) (phase de mi se à l’échelle) BF-PFS-365496-CS-QCBS / R ecrutement d’une ONG pour l a mise en œuvre des activité Cash transfers and awarenes s de ciblage communautaire Quality And Cost-B Under Implement IDA / 64340 s programs for poor and vuln Post Open - National 1,088,165.00 0.00 2023-06-12 2023-06-26 2023-06-26 2023-07-06 2023-08-05 2023-08-19 2023-09-06 2023-09-23 2023-11-07 dans la région du Plateau Cen ased Selection ation erable households tral et du Centre-Sud dans le cadre de l’opérationnalisation du Registre social unique (RS U) (phase de mise à l’échelle) BF-PFS-365498-CS-QCBS / R ecrutement d’une ONG pour l a mise en œuvre des activité Cash transfers and awarenes s de ciblage communautaire Consultant Qualifi Under Implement IDA / 64340 s programs for poor and vuln Post Open - National 217,750.00 0.00 2023-06-12 2023-06-26 2023-06-26 2023-07-31 2023-08-05 2023-08-15 2023-09-29 dans la région du Sud-Ouest cation Selection ation erable households dans le cadre de l’opérationn alisation du Registre social u nique (RSU) (phase de mise à l’échelle) INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Con Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant tract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BF-PFS-17944-CS-INDV / Eval Laying the foundations for a Individual Consult uation processus de paiemen IDA / 54290 basic national safety net syst Post Limited 12,000.00 8,777.13 Completed 2017-05-02 2017-01-20 2017-05-02 2017-12-21 2017-05-02 2018-01-10 2017-05-02 2018-03-22 2017-05-02 2018-05-12 ant Selection t dans le nord em BF-PFS-17945-CS-INDV / For Individual Consult mation des FACOM et des CR IDA / 54290 Project management Post Limited 11,000.00 8,612.46 Completed 2017-11-15 2018-05-30 2017-11-15 2018-08-29 2017-11-15 2018-09-04 2017-11-15 2018-10-02 2017-11-15 2019-04-18 ant Selection O en gestion axée sur les rés ultats BF-PFS-17758-CS-INDV / Réal Individual Consult IDA / 54290 Project management Post Limited 8,550.00 8,489.00 Signed 2017-06-23 2017-08-07 2017-06-28 2018-05-28 2017-07-19 2018-06-26 2017-08-23 2018-07-27 2018-02-19 isation d'un site Web au profi ant Selection t du PFS BF-PFS-16926-CS-CDS / Cons Laying the foundations for a ultant principal pour le Suivi- IDA / 54290 basic national safety net syst Post Direct Selection Direct 21,000.00 16,840.66 Completed 2017-06-11 2017-06-29 2017-06-21 2017-07-13 2017-08-25 2017-08-03 2018-02-21 2017-09-15 Contrôle enquête PMT Centre em -Est BF-PFS-19405-CS-CDS / Cons ultant individuel assistant au Laying the foundations for a consultant principal pour le s IDA / 54290 basic national safety net syst Post Direct Selection Direct 13,000.00 10,396.76 Completed 2017-06-28 2017-05-02 2017-07-08 2017-05-02 2017-09-11 2017-08-03 2018-03-10 2017-09-15 uivi contrôle de l'enquête PM em T dans la région du Centre-Es t Page 9 BF-PFS-17794-CS-CDS / cons Laying the foundations for a ultant principal pour le Suivi-c IDA / 54290 basic national safety net syst Post Direct Selection Direct 20,000.00 15,794.84 Completed 2017-07-27 2017-08-10 2017-08-04 2017-08-14 2017-08-25 2017-12-30 2018-02-21 2018-03-07 ontrôle de l'enquête PMT dan em s la région du Boulkiemdé BF-PFS-22426-CS-CDS / Cons Laying the foundations for a ultant assistant chargé du sui IDA / 54290 basic national safety net syst Post Direct Selection Direct 12,500.00 10,286.70 Completed 2017-07-31 2017-06-29 2017-08-10 2017-07-13 2017-10-14 2017-08-03 2018-04-12 2017-09-15 vi contrôle de l'enquête PMT em au Boulkiemdé, Loroum et Pa ssoré BF-PFS-30015-CS-INDV / Con Laying the foundations for a Individual Consult sultant individuel pour la réali IDA / 54290 basic national safety net syst Post Limited 28,000.00 8,833.26 Completed 2017-10-06 2017-08-25 2017-10-11 2017-10-06 2017-11-01 2017-11-03 2017-12-06 2017-11-21 2018-06-04 2017-12-15 ant Selection sation de vidéo communautai em res BF-PFS-38403-CS-INDV / For mation des FACOM en ANJE ( Individual Consult IDA / 54290 Project management Post Limited 8,400.00 7,352.78 Completed 2017-12-04 2018-02-07 2017-12-09 2018-02-21 2017-12-30 2018-03-12 2018-02-03 2018-04-10 2018-08-02 2018-10-25 Est, du Centre-Est et des Prov ant Selection inces du Loroum et du Passor é) BF-PFS-38404-CS-INDV / For mation des FACOM sur DPE ( Individual Consult IDA / 54290 Project management Post Limited 4,800.00 3,503.06 Completed 2017-11-27 2018-02-07 2017-12-02 2018-02-21 2017-12-23 2018-03-12 2018-01-27 2018-03-22 2018-07-26 2018-10-18 Région Est,Centre-Est et Prov ant Selection inces Loroum et Passoré) BF-PFS-38406-CS-INDV / For mation des FACOM sur les tec Individual Consult hniques d'animation (Région IDA / 54290 Project management Post Limited 6,000.00 4,753.72 Completed 2017-12-03 2018-02-07 2017-12-08 2018-02-21 2017-12-29 2018-03-12 2018-02-02 2018-03-22 2018-08-01 2018-11-29 ant Selection de l'Est, du Centre-Est et Prov inces du Loroum et du Passor é) BF-PFS-25698-CS-CDS / Cons Cash transfers and awarenes ultant individuel pour l'appui IDA / 54290 s programs for poor and vuln Post Direct Selection Direct 3,990.00 3,342.60 Completed 2017-09-11 2017-07-28 2017-09-21 2017-07-13 2017-11-25 2017-10-16 2018-05-24 2018-07-06 au SIG dans la mise en place erable households du registre unifié BF-PFS-25753-CS-CDS / Reno Laying the foundations for a uvellement contrat du Consul IDA / 54290 basic national safety net syst Post Direct Selection Direct 21,000.00 12,841.15 Signed 2017-09-24 2017-09-04 2017-10-04 2017-09-08 2017-12-08 2017-12-20 2018-06-06 tant individuel pour la mise e em n place du SIG du PFS BF-PFS-49665-CS-INDV / Éval Individual Consult uation du processus de ciblag IDA / 54290 Project management Post Limited 12,000.00 9,760.04 Completed 2018-04-10 2017-04-01 2018-04-15 2017-04-07 2018-05-06 2017-04-19 2018-06-10 2017-05-05 2018-08-09 2017-06-12 ant Selection e dans la région du Centre-Es t BF-PFS-61897-CS-INDV / Elab oration du document cadre d Individual Consult e politiques de réinstallation IDA / 54290 Project management Post Limited 10,000.00 3,714.90 Completed 2018-05-09 2018-05-07 2018-05-14 2018-05-08 2018-06-04 2018-05-09 2018-07-09 2018-05-11 2018-08-08 2018-06-11 ant Selection des populations (CPR) dans le cadre du projet réfugié BF-PFS-61895-CS-INDV / Elab oration du cadre de gestion e Individual Consult IDA / 54290 Project management Post Limited 10,000.00 3,801.29 Signed 2018-05-07 2018-05-07 2018-05-12 2018-05-08 2018-06-02 2018-05-09 2018-07-07 2018-05-11 2018-08-06 nvironnementale et sociale d ant Selection ans le cadre du projet réfugié BF-PFS-61896-CS-INDV / Eval Individual Consult uation de la composante THI IDA / 54290 Project management Post Limited 10,000.00 3,628.34 Completed 2018-05-09 2018-05-08 2018-05-14 2018-05-07 2018-06-04 2018-05-09 2018-07-09 2018-05-09 2018-08-08 2018-05-24 ant Selection MO dans le cadre du projet ré fugié BF-PFS-61898-CS-CDS / Agen Cash transfers and awarenes ce de paiement pour les tran IDA / 54290 s programs for poor and vuln Post Direct Selection Direct 960,000.00 820,263.43 Signed 2017-04-10 2017-02-08 2017-04-20 2018-02-28 2017-06-24 2018-05-04 2018-06-24 sferts monétaires dans l'Est e erable households t le Centre-Est BF-PFS-61899-CS-INDV / Con ception (infographie) de boite Individual Consult IDA / 54290 Project management Post Limited 1,300.00 1,122.60 Completed 2018-05-18 2018-05-22 2018-05-23 2018-05-28 2018-06-13 2018-07-12 2018-07-18 2018-08-29 2018-08-02 2018-09-28 s à images sur les nouveaux t ant Selection hèmes du projet BF-PFS-68471-CS-CDS / Form ation des PRC à l'utilisation d Cash transfers and awarenes es données géo satellitaires p TF / A3975 s programs for poor and vuln Post Direct Selection Direct 35,400.00 29,486.33 Signed 2018-07-23 2018-09-25 2018-08-02 2019-05-21 2018-10-06 2019-06-25 2019-10-06 our la production et la comm erable households ercialisation des produits agr opastoraux BF-PFS-17571-CS-CDS / Agen Cash transfers and awarenes ce de paiement pour les tran IDA / 54290 s programs for poor and vuln Prior Direct Selection Direct 960,000.00 0.00 Canceled 2017-07-26 2017-07-31 2017-09-10 2018-03-09 sferts monétaires dans l'Est e erable households t le Centre-Est BF-PFS-78848-CS-INDV / App Laying the foundations for a ui accompagnement du proje Individual Consult IDA / 54290 basic national safety net syst Post Limited 20,000.00 14,208.91 Completed 2018-09-24 2018-09-21 2018-09-29 2018-09-21 2018-10-03 2018-09-27 2018-10-22 2018-10-02 2018-12-31 2018-11-09 t dans la collecte des donnée ant Selection em s au sahel (enquête de ciblag e des ménages) BF-PFS-78849-CS-INDV / App Laying the foundations for a Individual Consult ui au SIG pour la mise en plac IDA / 54290 basic national safety net syst Post Limited 24,000.00 10,197.03 Signed 2018-09-26 2018-09-26 2018-10-01 2019-05-03 2018-10-08 2019-05-20 2018-10-29 2019-06-03 2018-12-18 ant Selection e du registre social unique em BF-PFS-78847-CS-INDV / Mai Laying the foundations for a Individual Consult ntenance du SIG du projet et IDA / 54290 basic national safety net syst Post Limited 20,000.00 16,169.02 Completed 2018-09-24 2018-09-23 2018-09-29 2018-09-25 2018-10-03 2018-10-04 2018-10-22 2018-11-05 2019-01-30 2019-04-05 ant Selection assistance em BF-PFS-84196-CS-INDV / Act ualisation du document cadre Individual Consult IDA / 54290 Project management Post Limited 3,000.00 0.00 Completed 2018-11-01 2018-11-05 2018-11-04 2018-10-10 2018-11-09 2018-12-12 2018-11-26 2018-12-18 2018-12-02 2019-07-13 de politique de réinstallation ant Selection des populations (CPRP) BF-PFS-84198-CS-INDV / Act ualisation du document cadre Individual Consult IDA / 54290 Project management Post Limited 3,000.00 9,376.40 Completed 2018-11-01 2018-11-06 2018-11-04 2018-10-10 2018-11-09 2018-12-12 2018-11-26 2018-12-18 2018-12-02 2019-07-10 de gestion environnementale ant Selection et sociale (CGES) BF-PFS-88899-CS-INDV / Réal Individual Consult Under Implement isation de la rétraite stratégiq IDA / 54290 Project management Post Limited 17,000.00 0.00 2018-12-03 2018-12-05 2018-12-08 2018-12-11 2018-12-16 2019-02-19 ant Selection ation ue du personnel du projet file ts sociaux BF-PFS-53417-CS-INDV / For Individual Consult mation du personnel sur les p IDA / 54290 Project management Post Open 80,000.00 0.00 Canceled 2018-09-10 2018-10-15 2018-10-30 2018-11-28 2018-12-28 ant Selection rocédures de décaissement d e la Banque BF-PFS-56370-CS-INDV / Assi Individual Consult stance technique en gestion f IDA / 54290 Project management Post Open 20,000.00 0.00 Canceled 2018-05-25 2018-07-03 2018-07-24 2018-08-28 2019-08-28 ant Selection inancière et comptable  BF-PFS-57179-CS-INDV / Rec rutement par une agence d'u Individual Consult IDA / 54290 Project management Post Open 11,000.00 0.00 Canceled 2017-07-25 2017-09-12 2017-10-03 2017-11-07 2018-11-07 n Responsable en Passation d ant Selection es marchés au profit du proje t Filets Sociaux Page 10 BF-PFS-46536-CS-INDV / GR Individual Consult H Consultant individuel pour IDA / 54290 Project management Post Direct 10,000.00 0.00 Canceled 2017-09-30 2017-10-10 2017-10-31 2017-12-05 2018-06-03 ant Selection Assistance technique BF-PFS-106848-CS-CDS / For mation des formateurs en AC Cash transfers and awarenes V et GERME dans la cadre de TF / A3975 s programs for poor and vuln Post Direct Selection Direct 134,000.00 111,755.73 Completed 2018-07-16 2018-09-17 2018-07-26 2018-09-24 2018-09-29 2019-07-01 2019-09-29 2020-12-28 la mise en œuvre des mesure erable households s productives dans la région du Nord BF-PFS-114535-CS-INDV / Re crutement d'un consultant in Individual Consult dividuel pour l'appui à l'élabo IDA / 54290 Project management Post Limited 30,000.00 16,614.67 Completed 2019-05-15 2019-05-15 2019-05-20 2019-05-15 2019-05-30 2019-05-23 2019-06-18 2019-05-23 2019-07-18 2019-07-26 ant Selection ration d'un manuel opération nel des travaux HIMO pour le Projet Filets Sociaux BF-PFS-119889-CS-INDV / Ré vision du manuel de procédur Individual Consult IDA / 54290 Project management Post Limited 10,000.00 15,435.73 Completed 2019-07-03 2019-06-28 2019-07-08 2019-07-01 2019-07-22 2019-07-19 2019-08-10 2019-07-20 2019-08-30 2019-09-16 es de gestion administrative, ant Selection financière et comptable du pr ojet BF-PFS-119895-CS-INDV / Dé Cash transfers and awarenes veloppement des modules su Individual Consult IDA / 54290 s programs for poor and vuln Post Limited 2,200.00 0.00 Canceled 2019-07-15 2019-07-20 2019-08-03 2019-08-22 2019-09-06 r le mariage d'enfant et les Vi ant Selection erable households olences Basées sur le Genre BF-PFS-119802-CS-INDV / Co Cash transfers and awarenes Individual Consult nception du scénario et le tes IDA / 54290 s programs for poor and vuln Post Limited 8,200.00 0.00 Canceled 2019-09-02 2019-09-07 2019-09-21 2019-10-10 2019-11-09 ant Selection t de théâtre forum erable households BF-PFS-119792-CS-INDV / Ré alisation d'un film documenta Individual Consult Pending Impleme IDA / 54290 Project management Post Open 62,600.00 0.00 2019-09-02 2019-10-30 2019-11-20 2019-12-25 2020-04-23 ire de capitalisation (26 minu ant Selection ntation tes) et de 2 films thématique s (13 minutes) BF-PFS-119897-CS-CDS / Tra duction des boîtes à images Cash transfers and awarenes ANJE et DPE en langues local TF / A3975 s programs for poor and vuln Post Direct Selection Direct 17,100.00 0.00 Signed 2019-07-22 2019-11-21 2019-08-01 2020-03-17 2019-10-05 2019-12-04 es (Fulfuldé, Mooré, Tamache erable households k, Goulmanchema, Dioula, So nraï) BF-PFS-119941-CS-INDV / Ela Individual Consult boration du manuel d’opérati IDA / 54290 Project management Post Limited 7,200.00 6,011.45 Completed 2019-06-06 2019-06-10 2019-06-11 2019-06-17 2019-06-12 2019-06-26 2019-07-01 2019-07-01 2019-07-31 2019-07-31 ant Selection on de l’éducation par la radio (E PR) BF-PFS-17926-CS-INDV / Réal Individual Consult IDA / 54290 Project management Post Limited 10,000.00 0.00 Canceled 2017-11-15 2017-11-15 2017-11-15 2017-11-15 2017-11-15 isation d'un vidéographe ant Selection BF-PFS-53416-CS-INDV / For Individual Consult mation du personnel du PFS s IDA / 54290 Project management Post Open 50,000.00 0.00 Canceled 2018-04-09 2018-05-05 2018-05-10 2018-06-08 2018-07-08 ant Selection ur la gestion du temps et des priorités BF-PFS-101199-CS-INDV / Re Individual Consult lecture du manuel des opérat IDA / 54290 Project management Post Open 6,000.00 0.00 Canceled 2019-02-25 2019-03-31 2019-04-15 2019-05-20 2019-06-04 ant Selection ions du Projet Filets Sociaux BF-PFS-68466-CS-CDS / Appu i accompagnement du projet Cash transfers and awarenes en ACV et GERME dans le cad TF / A3975 s programs for poor and vuln Post Direct Selection Direct 82,600.00 0.00 Canceled 2018-07-16 2018-09-17 2018-07-26 2018-09-29 2019-09-29 re de la mise en oeuvre des erable households mesures d'accompagnement productives BF-PFS-140251-CS-INDV / As Individual Consult sistance juridique au profit du IDA / 54290 Project management Post Limited 10,000.00 0.00 Signed 2019-11-15 2020-01-23 2019-11-20 2020-03-13 2019-12-04 2020-03-16 2020-01-02 2021-01-01 ant Selection projet filets sociaux BF-PFS-140267-CS-INDV / Mi se en place d'un système d'ar Individual Consult IDA / 54290 Project management Post Limited 11,000.00 8,803.94 Signed 2019-10-20 2019-10-20 2019-10-25 2019-09-23 2019-11-04 2019-10-10 2019-11-28 2019-10-15 2020-01-12 chivage et formation du pers ant Selection onnel du projet filets sociaux BF-PFS-140268-CS-INDV / Dé Laying the foundations for a Individual Consult Under Implement veloppement et réalisation d IDA / 54290 basic national safety net syst Post Limited 20,000.00 0.00 2019-10-20 2019-10-19 2019-10-25 2019-11-04 2019-12-09 2020-01-18 ant Selection ation u module sur la gestion des p em laintes BF-PFS-140848-CS-INDV / Re Cash transfers and awarenes Individual Consult crutement de 60 formateurs TF / A3975 s programs for poor and vuln Post Limited 90,000.00 76,008.00 Signed 2019-10-18 2019-10-23 2019-10-23 2019-10-16 2019-10-28 2019-10-24 2019-11-07 2019-10-28 2019-12-22 ant Selection pour la formation en GERME erable households BF-PFS-17791-CS-INDV / Eval Laying the foundations for a Individual Consult IDA / 54290 Post Limited 12,000.00 0.00 Canceled 2017-05-30 2017-05-30 2017-05-30 2017-05-30 2017-05-30 uation processus de paiemen basic national safety net syst ant Selection t em BF-PFS-119894-CS-INDV / Ré Individual Consult IDA / 54290 Project management Post Limited 10,900.00 0.00 Canceled 2019-07-15 2019-10-04 2019-07-20 2019-07-25 2019-08-13 2019-10-12 alisation des scoreboard ant Selection BF-PFS-17557-CS-CDS / Recr Laying the foundations for a utement et déploiement d'en IDA / 54290 basic national safety net syst Post Direct Selection Direct 17,000.00 0.00 Canceled 2017-06-11 2017-06-21 2017-08-25 2018-02-21 quêteurs dans le Lorum et Pa em ssoré BF-PFS-119776-CS-INDV / Fo Cash transfers and awarenes Individual Consult rmation de Mères-leaders du IDA / 54290 s programs for poor and vuln Post Limited 2,800.00 0.00 Canceled 2019-07-15 2019-07-20 2019-08-10 2019-08-29 2019-09-13 ant Selection Sahel sur le DPE erable households BF-PFS-119666-CS-INDV / Fo Cash transfers and awarenes Individual Consult rmation de Mères-leaders du IDA / 54290 s programs for poor and vuln Post Limited 3,860.00 0.00 Canceled 2019-07-15 2019-07-20 2019-07-30 2019-08-18 2019-09-02 ant Selection Sahel à la stratégie de ANJE erable households BF-PFS-53415-CS-INDV / Eval uation des effets du cash et d Individual Consult IDA / 54290 Project management Post Open 12,000.00 0.00 Canceled 2018-04-05 2018-11-14 2018-05-01 2018-05-16 2018-06-14 2018-07-14 es mesures d'accompagneme ant Selection nt dans le nord BF-PFS-153956-CS-INDV / Co Individual Consult llecte des données sur les per IDA / 54290 Project management Post Limited 10,000.00 0.00 Signed 2020-01-27 2020-01-27 2020-01-30 2020-05-08 2020-02-14 2020-05-25 2020-03-04 2020-04-03 ant Selection sonnes déplacées internes au Burkina Faso BF-PFS-140256-CS-CDS / Ren Cash transfers and awarenes ouvellement du contrat de l'O IDA / 54290 s programs for poor and vuln Post Direct Selection Direct 365,585.00 334,165.42 Signed 2020-01-27 2020-01-23 2020-02-06 2019-10-10 2020-03-26 2020-04-28 2021-03-26 NG pour la mise en œuvre de erable households s activités de sensibilisation a u Centre Est BF-PFS-156033-CS-INDV / Éla borer un programme de renfo rcement des capacités pour l' Individual Consult Under Implement IDA / 54290 Project management Post Limited 8,880.00 0.00 2020-02-10 2020-02-19 2020-02-15 2020-02-29 2020-03-19 2020-04-18 évaluation et la gestion des ri ant Selection ation sques de violences des femm es bénéficiaires du projet Page 11 BF-PFS-159688-CS-INDV / Mi se en place d'un système de Cash transfers and awarenes Individual Consult Under Implement collecte des données dans tro IDA / 64340 s programs for poor and vuln Post Limited 34,935.00 0.00 2020-02-28 2020-04-06 2020-03-04 2020-03-25 2020-04-29 2020-07-28 ant Selection ation is nouvelles régions (Boucle d erable households u Mouhoun, Centre-Ouest et l e Centre) BF-PFS-159683-CS-INDV / Ev Cash transfers and awarenes Individual Consult aluation des effets du cash et IDA / 54290 s programs for poor and vuln Post Limited 18,000.00 0.00 Signed 2020-03-03 2020-02-28 2020-03-08 2019-08-21 2020-03-29 2020-04-08 2020-05-03 2020-10-30 ant Selection des mesures d'accompagnem erable households ent BF-PFS-159647-CS-INDV / Fo Cash transfers and awarenes Individual Consult rmation des mères-leader de IDA / 64340 s programs for poor and vuln Post Limited 11,480.00 0.00 Signed 2020-03-10 2020-06-23 2020-03-15 2020-11-16 2020-04-05 2020-12-10 2020-04-24 2020-05-24 ant Selection l'Est en fabrication de farine erable households enricihie BF-PFS-159629-CS-INDV / Ma Laying the foundations for a intenance évolutive et adapta Individual Consult IDA / 54290 basic national safety net syst Post Limited 31,500.00 0.00 Signed 2020-02-28 2020-02-28 2020-03-09 2020-04-03 2020-03-30 2020-04-17 2020-05-04 2020-10-01 tive des applications du Proje ant Selection em t et l'assistance à l'équipe SI G BF-PFS-159655-CS-INDV / Ela boration d'une stratégie de c Individual Consult IDA / 54290 Project management Post Limited 19,500.00 0.00 Canceled 2020-02-21 2020-03-03 2020-02-26 2020-03-18 2020-04-22 2020-06-21 ommunication et de capitalis ant Selection ation des accquis BF-PFS-140253-CS-CDS / Ren Cash transfers and awarenes ouvellement du contrat de l'O IDA / 54290 s programs for poor and vuln Post Direct Selection Direct 553,056.00 0.00 Signed 2020-03-02 2020-03-18 2020-03-12 2020-03-05 2020-04-21 2021-04-21 NG pour la mise en œuvre de erable households s activités de sensibilisation à l'Est BF-PFS-168964-CS-INDV / Fo rmation des acteurs terrains Productive Labor-Intensive P Individual Consult Pending Impleme et élus locaux en évaluation IDA / 64340 Post Limited 3,120.00 0.00 2020-07-01 2020-07-06 2020-07-21 2020-07-31 2020-08-12 ublic Works (LIPW) Program ant Selection ntation environnementale et sociale des sous projets et suivi envir onnemental des travaux BF-PFS-172512-CS-INDV / As sistance dans la Collecte et le Cash transfers and awarenes Individual Consult Pending Impleme traitement des données dans IDA / D4760 s programs for poor and vuln Post Limited 14,600.00 0.00 2020-05-09 2020-05-14 2020-05-17 2020-05-21 2020-07-12 ant Selection ntation le cadre des réponses au Cov erable households id19 et de l'appui au PDI BF-PFS-178608-CS-INDV / Re crutement d'un Responsable Individual Consult Under Implement IDA / D4760 Project management Post Open 21,500.00 0.00 2020-06-11 2020-06-10 2020-07-30 2020-08-20 2020-09-24 2021-09-24 en passation des marchés (R ant Selection ation PM) pour le compte du projet Filets sociaux BF-PFS-200790-CS-INDV / As sistance du projet dans la coll Cash transfers and awarenes Individual Consult Pending Impleme ecte et le traitement des don IDA / D4760 s programs for poor and vuln Post Limited 40,000.00 0.00 2020-10-26 2020-10-31 2020-11-21 2020-12-26 2021-04-18 ant Selection ntation nées des régions de la Boucle erable households du Mouhoun, du Centre-Nord et du Nord. BF-PFS-202215-CS-CDS / Mis Cash transfers and awarenes e en œuvre des activités de s IDA / D4760 s programs for poor and vuln Post Direct Selection Direct 71,600.00 0.00 Signed 2020-11-09 2020-02-03 2020-11-19 2020-11-18 2021-01-23 2021-04-23 ensibilisation au Centre Est p erable households endant trois (3) mois au titre de 2020 BF-PFS-159678-CS-INDV / Sui Laying the foundations for a vi des recommandations issu Individual Consult IDA / 54290 basic national safety net syst Post Limited 19,150.00 0.00 Canceled 2020-02-24 2020-02-29 2020-03-21 2020-04-19 2020-09-16 es du diagnostic 2019 du SIG ant Selection em et la mise en place du registr e unique BF-PFS-233764-CS-CDS / Rec rutement d'un cabinet pour le Cash transfers and awarenes ciblage complémentaire dans IDA / 64340 s programs for poor and vuln Prior Direct Selection Direct 3,200,000.00 0.00 Canceled 2021-05-07 2021-05-17 2021-07-21 2022-01-17 08 communes de la Boucle d erable households u Mouhoun dans le cadre du programme d'urgence BF-PFS-236701-CS-CDS / Rec rutement d’un cabinet pour l e ciblage des bénéficiaires du Cash transfers and awarenes Projet Filets Sociaux dans la IDA / 64340 s programs for poor and vuln Prior Direct Selection Direct 3,800,000.00 1,578,358.18 Completed 2021-05-26 2021-07-27 2021-06-05 2021-08-18 2021-08-09 2021-10-30 2022-02-05 2022-04-21 Boucle du Mouhoun et dans l erable households es quartiers spontanés des ar rondissements 7, 8 et 11 de Ouagadougou BF-PFS-236702-CS-CDS / Rec rutement d’un cabinet pour l a réalisation d’une collecte d Cash transfers and awarenes e données auprès des ménag IDA / 64340 s programs for poor and vuln Post Direct Selection Direct 350,000.00 267,749.41 Signed 2021-05-26 2021-07-22 2021-06-05 2021-07-28 2021-08-09 2021-11-24 2022-02-05 es: erable households Evaluation d'impact du projet filets sociaux – au Centre Est du Burkina Faso BF-PFS-241494-CS-INDV / Re crutement d’un consultant po Cash transfers and awarenes ur le renforcement des capaci Individual Consult Under Implement IDA / 64340 s programs for poor and vuln Post Limited 4,000.00 0.00 2021-07-05 2021-08-31 2021-07-10 2021-07-31 2021-09-04 2022-03-03 tés de l’UGP, du SP/CONASUR ant Selection ation erable households et de la DGSAH sur les norme s et principes humanitaires BF-PFS-244346-CS-INDV / Re crutement d’un consultant po Cash transfers and awarenes ur la conception du site web Individual Consult IDA / 64340 s programs for poor and vuln Post Limited 10,000.00 0.00 Signed 2021-07-28 2021-07-26 2021-08-02 2021-10-19 2021-08-23 2021-11-22 2021-09-27 2022-03-26 du ministère de la femme, de ant Selection erable households la solidarité nationale, de la f amille et de l’action humanita ire et du Projet Filets Sociaux BF-PFS-275620-CS-CDS / Sél ection d’un cabinet de recrut Under Implement IDA / 64340 Project management Post Direct Selection Direct 20,000.00 0.00 2022-02-04 2020-05-21 2022-02-14 2022-04-20 2022-10-17 ement du personnel au profit ation du Projet Filets Sociaux BF-PFS-275629-CS-INDV / Re crutement d’un consultant po ur l’assistance technique à la Individual Consult Pending Impleme maintenance évolutive et ada IDA / 64340 Project management Post Limited 18,600.00 0.00 2022-02-04 2022-02-09 2022-03-02 2022-04-06 2022-10-03 ant Selection ntation ptative de l’application MIS et des applications mobiles de l ’unité de gestion du Projet Fil ets Sociaux. BF-PFS-275630-CS-INDV / Re crutement d’un consultant po ur l’élaboration de la stratégi Individual Consult Pending Impleme e de communication du minis IDA / 64340 Project management Post Limited 18,000.00 0.00 2022-02-11 2022-02-16 2022-03-09 2022-04-13 2022-10-10 ant Selection ntation tère du genre, de la solidarité nationale, de la famille et de l ’action humanitaire et du Proj et Filets Sociaux BF-PFS-293363-CS-INDV / Re crutement d’un consultant po Cash transfers and awarenes Individual Consult ur le renforcement des capaci IDA / 64340 s programs for poor and vuln Post Limited 19,600.00 0.00 Signed 2022-05-13 2022-07-29 2022-05-18 2022-04-05 2022-06-08 2022-06-08 2022-07-13 2023-01-09 ant Selection tés de l’UGP sur l’accès huma erable households nitaire, la sécurité, la sureté et la redevabilité Page 12 BF-PFS-302217-CS-INDV / Re crutement de trois (03) consu ltants individuels pour la trad Cash transfers and awarenes Individual Consult uction des outils de dissémin IDA / 64340 s programs for poor and vuln Post Limited 4,710.00 0.00 Signed 2022-07-08 2022-09-12 2022-07-13 2022-10-20 2022-08-03 2022-10-20 2022-09-07 2023-03-06 ant Selection ation du mécanisme de gesti erable households on des plaintes (MGP) du proj et filets sociaux en langues n ationales Moore, Dioula et Ful fudé. BF-PFS-307644-CS-CDS / Ren ouvellement du contrat de l’O Cash transfers and awarenes NG AGED pour la mise en œu IDA / 64340 s programs for poor and vuln Post Direct Selection Direct - National 500,000.00 0.00 Signed 2022-08-08 2022-08-22 2022-08-18 2022-10-20 2022-10-22 2023-04-20 vre des activités du Projet Fil erable households ets dans la région du Sahel BF-PFS-316326-CS-CDS / Rec rutement cabinet de consulta Cash transfers and awarenes nce en sécurité pour l’évaluat Direct - Internation IDA / 64340 s programs for poor and vuln Post Direct Selection 26,107.00 0.00 Signed 2022-09-16 2022-10-17 2022-09-24 2022-10-19 2022-10-07 2022-10-23 ion des risques dans la région al erable households du Centre-Nord et de la Boucl e du Mouhoun au profit du pr ojet filets sociaux BF-PFS-334522-CS-INDV / Re crutement d’un consultant in dividuel pour l’élaboration du Cash transfers and awarenes Plan d’Engagement Environn Individual Consult IDA / 64340 s programs for poor and vuln Post Limited 20,000.00 0.00 Signed 2023-01-04 2023-01-04 2023-01-09 2023-02-15 2023-01-27 2023-02-15 2023-02-08 2023-03-10 ementale et Social (PEES), du ant Selection erable households Plan de Mobilisation des Parti es Prenantes (PMPP) et des Pr océdures de Gestion de la Ma in d’œuvre (PGMO) du PAPSA BF-PFS-334551-CS-INDV / Re crutement d’un consultant in dividuel en vue de l’Evaluatio Cash transfers and awarenes Individual Consult n du Risque Sécuritaire et l’él IDA / 64340 s programs for poor and vuln Post Limited 20,000.00 0.00 Signed 2023-01-04 2023-01-04 2023-01-09 2023-02-06 2023-01-27 2022-02-10 2023-02-08 2023-03-10 ant Selection aboration d’un Plan de Gestio erable households n Sécuritaire pour un futur pr ojet d’appui à la protection so ciale adaptative BF-PFS-334562-CS-INDV / Re crutement d’un consultant in Cash transfers and awarenes Individual Consult dividuel en charge de l’évalu IDA / 64340 s programs for poor and vuln Post Limited 20,000.00 0.00 Signed 2023-01-09 2023-01-17 2023-01-14 2022-01-12 2023-02-01 2023-01-18 2023-02-13 2023-04-14 ant Selection ation sociale du Projet d’Appu erable households i à la Protection sociale Adapt ative BF-PFS-334563-CS-INDV / Re crutement d’un consultant in dividuel pour l’élaboration d’ Cash transfers and awarenes un Plan de Gestion Environne Individual Consult IDA / 64340 s programs for poor and vuln Post Limited 20,000.00 0.00 Signed 2023-01-09 2023-01-19 2023-01-14 2023-01-30 2023-02-01 2023-02-13 2023-02-13 2023-03-15 mentale et Sociale (PGES) gé ant Selection erable households nérique incluant un plan de g estion des déchets électroniq ues pour un futur Projet d’Ap pui à la Protection Sociale Ad aptative BF-PFS-339632-CS-CDS / Sél ection de l’Association Songui Manegre /Aide au Développe Laying the foundations for a ment Endogène (ASMADE) po IDA / 64340 basic national safety net syst Post Direct Selection Direct - National 331,175.00 0.00 Signed 2023-02-01 2023-01-16 2023-02-11 2023-01-31 2023-03-12 2023-04-02 ur les activités de ciblage co em mmunautaire dans la région du centre-ouest dans le cadre de l'opérationnalisation du Re gistre social unique (RSU). BF-PFS-339684-CS-CDS / Sél ection de l’Association Jeunes se Volontaire pour la Promoti on du Leadership la Santé et l Laying the foundations for a e Développement (AJVLS) po IDA / 64340 basic national safety net syst Post Direct Selection Direct - National 277,002.00 0.00 Signed 2023-02-01 2023-01-16 2023-02-11 2023-01-31 2023-03-12 2023-04-02 ur les activités de ciblage co em mmunautaire dans la région du centre-est dans le cadre d e l'opérationnalisation du Reg istre social unique BF-PFS-346996-CS-CDS / Rec rutement de l’Institut Nationa l de la Statistique et de la Dé Laying the foundations for a mographie (INSD) la conduite IDA / 64340 basic national safety net syst Post Direct Selection Direct - National 1,464,000.00 0.00 Canceled 2023-03-03 2023-03-15 2023-03-13 2023-03-23 2023-04-11 2023-05-11 de la collecte de données des em ménages et personnes pauvr es et vulnérables de la région du Centre-Ouest BF-PFS-346992-CS-CDS / Rec rutement de l’Institut Supérie ur des Sciences de la Populati Laying the foundations for a on (ISSP) pour la conduite de IDA / 64340 basic national safety net syst Post Direct Selection Direct - National 1,061,280.00 0.00 Canceled 2023-03-03 2023-03-15 2023-03-13 2023-03-23 2023-04-11 2023-05-02 la collecte de données des m em énages et personnes pauvres et vulnérables de la région du Centre Est BF-PFS-353775-CS-CDS / Rec rutement de l’Institut Nationa l de la Statistique et de la Dé Laying the foundations for a Under Implement mographie (INSD) la conduite IDA / 64340 basic national safety net syst Prior Direct Selection Direct - National 1,464,000.00 0.00 2023-03-29 2023-03-30 2023-04-08 2023-03-30 2023-05-07 2023-06-06 ation de la collecte de données des em ménages et personnes pauvr es et vulnérables de la région du Centre-Ouest BF-PFS-353801-CS-CDS / Rec rutement de l’Institut Supérie ur des Sciences de la Populati Laying the foundations for a Under Implement on (ISSP) pour la conduite de IDA / 64340 basic national safety net syst Prior Direct Selection Direct - National 1,061,280.00 0.00 2023-03-29 2023-03-30 2023-04-08 2023-03-30 2023-05-07 2023-06-06 ation la collecte de données des m em énages et personnes pauvres et vulnérables de la région du Centre Est BF-PFS-355234-CS-CDS / Ren ouvellement du contrat de l'O Cash transfers and awarenes Pending Impleme NG en charge de la mise en IDA / 64340 s programs for poor and vuln Post Direct Selection Direct - National 57,057.00 0.00 2023-04-18 2023-04-28 2023-07-02 2023-07-20 ntation œuvre des activités du Projet erable households Filets Sociaux dans la région du Sahel BF-PFS-355327-CS-INDV / Re crutement d'un consultant po Individual Consult Pending Impleme ur la formation du personnel IDA / 54290 Project management Post Limited 16,800.00 0.00 2023-04-10 2023-04-23 2023-04-26 2023-05-02 2023-05-12 ant Selection ntation des ONGS sur la sécurité, la s ûreté et l'acces humanitaire BF-PFS-355333-CS-INDV / Re crutement d'un consultant po Individual Consult Pending Impleme ur la maintenance évolutive IDA / 64340 Project management Post Limited 4,500.00 0.00 2023-05-02 2023-05-07 2023-05-28 2023-07-02 2023-08-16 ant Selection ntation et adaptative de l'application MIS et des applications mobil es BF-PFS-355338-CS-INDV / Fo rmation du personnel du ST/R Individual Consult Pending Impleme IDA / 64340 Project management Post Limited 9,000.00 0.00 2023-04-26 2023-05-01 2023-05-22 2023-06-26 2023-07-01 SU et autres acteurs sur les f ant Selection ntation ondamentaux du Registre soc ial unique Page 13 BF-PFS-355340-CS-INDV / Fo rmation des managers du sys Individual Consult Pending Impleme tème informatique et de gesti IDA / 64340 Project management Post Limited 5,000.00 0.00 2023-04-12 2023-04-17 2023-05-08 2023-06-12 2023-06-17 ant Selection ntation on sur la conception et la ges tion de la base de données d u RSU BF-PFS-355342-CS-INDV / Fo rmation du personnel du ST/R Individual Consult Pending Impleme IDA / 64340 Project management Post Limited 3,000.00 0.00 2023-05-01 2023-05-06 2023-05-27 2023-07-01 2023-07-06 SU sur le système d'informati ant Selection ntation on géographique BF-PFS-355343-CS-INDV / Fo rmation du personnel du ST R SU et autres acteurs sur les Individual Consult Pending Impleme IDA / 64340 Project management Post Limited 3,000.00 0.00 2023-05-18 2023-05-23 2023-06-13 2023-07-18 2023-07-23 mesures de sécurisation des ant Selection ntation systèmes informatiques et la protection des données à car actère personnel BF-PFS-355344-CS-INDV / Fo rmation du personnel du ST R Individual Consult Pending Impleme IDA / 64340 Project management Post Limited 3,000.00 0.00 2023-05-11 2023-05-16 2023-06-06 2023-07-11 2023-07-16 SU et autres acteurs sur ll'an ant Selection ntation alyse de la pauvreté multidim ensionnelle BF-PFS-355356-CS-INDV / Et Individual Consult Pending Impleme ude pour la capitalisation et a IDA / 64340 Project management Post Limited 20,000.00 0.00 2023-09-30 2023-10-05 2023-10-26 2023-11-30 2023-12-30 ant Selection ntation pprentissage BF-PFS-355253-CS-CDS / Ren ouvellement du contrat du G ROUPEMENT ASSOCIATION D’ AIDE AUX ENFANTS ET AUX F Cash transfers and awarenes Pending Impleme AMILLES DEMUNIES (ADEFAD IDA / 64340 s programs for poor and vuln Post Direct Selection Direct - National 491,775.00 0.00 2023-04-24 2023-04-28 2023-06-25 2024-01-21 ntation )/ASSOCIATION SINIGNANSSI erable households GUI en charge en charge de l a mise en œuvre des activité s dans les nouvelles zones d'i ntervention du PFS (Boucle d u Mouhoun) BF-PFS-355255-CS-CDS / Ren ouvellement du contrat de l'O Cash transfers and awarenes NG ASD en charge de la mise Pending Impleme IDA / 64340 s programs for poor and vuln Post Direct Selection Direct - National 583,149.00 0.00 2023-04-24 2023-04-28 2023-06-25 2024-01-21 en œuvre des activités dans l ntation erable households es nouvelles zones d'interven tion du PFS (Centre Nord) BF-PFS-355355-CS-CDS / Ren ouvellement du contrat de EV AL + pour la réalisation de Ph Cash transfers and awarenes one Call ou Appels téléphoniq Under Implement IDA / 64340 s programs for poor and vuln Post Direct Selection Direct - National 36,191.00 0.00 2023-04-24 2021-10-29 2023-05-04 2023-07-08 2023-12-05 ues dans le cadre du suivi de ation erable households s transferts monétaires dans l es régions du Nord et du Sah el au profit du Projet Filets So ciaux. BF-PFS-355353-CS-CDS / Ren ouvellement du contrat de "I MCG" pour la réalisation de P Cash transfers and awarenes ost Distribution Monitoring (P Under Implement IDA / 64340 s programs for poor and vuln Post Direct Selection Direct - National 159,167.00 0.00 2023-04-24 2021-11-30 2023-05-04 2023-07-08 2023-10-06 DM) ou enquêtes post paiem ation erable households ent des cash transferts dans l es régions de la Boucle du Mo uhoun et du Centre au profit du Projet Filets Sociaux. BF-PFS-355252-CS-CDS / Ren ouvellement du contrat de l'O Cash transfers and awarenes Pending Impleme NG ADEFAD en charge de la IDA / 64340 s programs for poor and vuln Post Direct Selection Direct - National 297,238.00 0.00 2023-04-24 2023-04-28 2023-06-25 2023-12-22 ntation mise en œuvre des activités erable households dans les nouvelles zones d'int ervention du PFS (Nord) BF-PFS-358257-CS-CDS / Ren ouvellement de contrat de "I NNOVATIVE HUB FOR RESEAR Cash transfers and awarenes CH IN AFRICA Sarl" pour la ré Pending Impleme IDA / 64340 s programs for poor and vuln Post Direct Selection Direct - National 166,615.00 0.00 2023-04-24 2023-05-04 2023-07-08 2023-10-06 alisation de Post Distribution ntation erable households Monitoring (PDM) ou enquête s post paiement des cash tra nsferts dans la région du Cen tre Nord au profit du Projet Fil ets Sociaux. BF-PFS-358258-CS-CDS / Ren ouvellement du contrat de "C ENTRE D’ETUDE EN DEVELOP PEMENT (CED) Sarl" pour la r Cash transfers and awarenes Pending Impleme éalisation de Post Distribution IDA / 64340 s programs for poor and vuln Post Direct Selection Direct - National 144,763.00 0.00 2023-04-24 2023-05-04 2023-07-08 2023-10-06 ntation Monitoring (PDM) ou enquête erable households s post paiement des cash tra nsferts dans les régions du N ord et du Sahel au profit du P rojet Filets Sociaux. BF-PFS-358259-CS-CDS / Ren ouvellement du contrat de IN NOVATIVE HUB FOR RESEARC Cash transfers and awarenes H IN AFRICA Sarl pour la réali Pending Impleme IDA / 64340 s programs for poor and vuln Post Direct Selection Direct - National 41,654.00 0.00 2023-04-24 2023-05-04 2023-07-08 2023-12-05 sation de Phone Call ou Appel ntation erable households s téléphoniques dans le cadre du suivi des transferts monét aires dans la région du Centr e Nord au profit du Projet File ts Sociaux. BF-PFS-358260-CS-CDS / Ren ouvellement du contrat de H ORUS CD pour réalisation de Cash transfers and awarenes Phone Call ou Appels télépho Pending Impleme IDA / 64340 s programs for poor and vuln Post Direct Selection Direct - National 39,792.00 0.00 2023-04-24 2023-05-04 2023-07-08 2023-12-05 niques dans le cadre du suivi ntation erable households des transferts monétaires da ns les régions de la Boucle du Mouhoun et du Centre au pro fit du Projet Filets Sociaux. Page 14 PROCUREMENT PLAN (Textual Part) Project information: STRENGTHENING PERU'S NATIONAL SCIENCE, TECHNOLOGY AND INNOVATION SYSTEM (P176297) Project Implementation agency: NATIONAL PROGRAM FOR SCIENTIFIC RESEARCH AND ADVANCED STUDIES (PROCIENCIA) Date of the Procurement Plan: 01/18/2023 Period covered by this Procurement Plan: 18 months Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (Fourth Edition November 2020) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. Not Applicable. Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables Not Applicable. Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: is not applicable; Works: is not applicable. PROCUREMENT Peru : STRENGTHENING PERU'S NATIONAL SCIENCE, TECHNOLOGY AND INNOVATION SYSTEM PLAN General Information Country: Peru 2023-01-18 Bank’s Approval Date of the Original Procurement Plan: 2023-06-05 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P176297 GPN Date: 2022-12-30 Project Name: STRENGTHENING PERU'S NATIONAL SCIENCE, TECHNOLOGY AND INNOVATION SYSTEM Loan / Credit No: IBRD / 93340 National Program for Scientific Research and Advanced Studies Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PE-PROCIENCIA-339687-GO- RFQ / Adquisición de mobiliar io para oficinas del Proyecto 4. Project Management and Request for Quota Single Stage - One E Pending Impl “Mejoramiento y Ampliación IBRD / 93340 Post Open - National 50,000.00 0.00 2023-07-08 2023-08-27 2023-09-26 Monitoring & Evaluation tions nvelope ementation de los Servicios de CTI para f ortalecer el Sistema Nacional de Ciencia, Tecnología e Inno vación”. PE-PROCIENCIA-334146-GO- RFB / Adquisición de Bienes p ara Equipamiento Tecnológic 1: Strengthening SINACTI’s i Single Stage - One E Pending Impl o para el Proyecto: Mejorami IBRD / 93340 nstitutions and governance t Post Request for Bids Open - National 821,105.00 0.00 2023-07-03 2023-07-06 2023-08-17 2023-09-06 2023-10-07 2024-02-04 nvelope ementation ento y ampliación de los serv o bolster innovation in Peru icios de CTI para fortalecer el Sistema Nacional de Ciencia, Tecnología e Innovación PE-PROCIENCIA-337438-GO- 1: Strengthening SINACTI’s i RFB / Adquisición de licencias Single Stage - One E Pending Impl IBRD / 93340 nstitutions and governance t Post Request for Bids Open - National 158,291.00 0.00 2023-08-01 2023-08-06 2023-09-17 2023-10-17 2023-11-21 2023-12-21 informáticas de herramientas nvelope ementation o bolster innovation in Peru necesarias para la gestión de l Proyecto PE-PROCIENCIA-352355-GO- RFQ / Adquisición de equipo 4. Project Management and Request for Quota Single Stage - One E Pending Impl IBRD / 93340 Post Open - National 77,600.00 0.00 2023-06-28 2023-08-17 2023-09-16 de computo para el equipo i Monitoring & Evaluation tions nvelope ementation mplementador del Proyecto NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PE-PROCIENCIA-333995-NC- RFB / Servicio de alquiler de i nfraestructura en nube - Proy 1: Strengthening SINACTI’s i Single Stage - One E Pending Impl ecto Mejoramiento y ampliaci IBRD / 93340 nstitutions and governance t Post Request for Bids Open - National 476,146.00 0.00 2023-04-03 2023-04-08 2023-05-23 2023-06-06 2023-07-24 2026-07-23 nvelope ementation ón de los servicios de CTI par o bolster innovation in Peru a fortalecer el Sistema Nacio nal de Ciencia, Tecnología e I nnovación PE-PROCIENCIA-333997-NC- RFB / Servicio de levantamie 1: Strengthening SINACTI’s i Single Stage - One E Pending Impl nto y procesamiento de dato IBRD / 93340 nstitutions and governance t Post Request for Bids Open - National 72,236.00 0.00 2023-02-01 2023-02-06 2023-03-20 2023-04-19 2023-05-30 2023-11-26 nvelope ementation s de la encuesta de eficiencia o bolster innovation in Peru de gasto público en CTI PE-PROCIENCIA-334001-NC- 1: Strengthening SINACTI’s i Direct - Internation DIR / Suscripción a base de d IBRD / 93340 nstitutions and governance t Post Direct Selection 120,000.00 0.00 Canceled 2023-03-01 2023-03-06 2023-05-10 2026-05-09 al atos de referencias bibliográf o bolster innovation in Peru icas y citas PE-PROCIENCIA-335374-NC- DIR / Servicio de alquiler de o ficina para el Proyecto Mejor 4. Project Management and Under Imple IBRD / 93340 Post Direct Selection Direct - National 459,470.00 0.00 2023-04-01 2023-06-12 2023-04-06 2023-05-11 2026-04-25 amiento y ampliación de los Monitoring & Evaluation mentation servicios de CTI para fortalec er el Sistema Nacional de Cie ncia, Tecnología e Innovación PE-PROCIENCIA-334000-NC- 1: Strengthening SINACTI’s i RFB / Suscripción de recursos Open - Internationa Single Stage - One E IBRD / 93340 nstitutions and governance t Prior Request for Bids 3,607,035.00 0.00 Canceled 2023-04-03 2023-04-08 2023-05-20 2023-06-19 2023-07-24 2026-07-23 de información de texto com l nvelope o bolster innovation in Peru pleto con editor PE-PROCIENCIA-334005-NC- 4. Project Management and Request for Quota Single Stage - One E Pending Impl RFQ / Servicio de correo elect IBRD / 93340 Post Open - National 42,211.00 0.00 2023-08-06 2023-10-01 2024-09-30 Monitoring & Evaluation tions nvelope ementation rónico para el Proyecto PE-PROCIENCIA-352954-NC- 1: Strengthening SINACTI’s i RFB / Servicio de suscripción Open - Internationa Single Stage - One E IBRD / 93340 nstitutions and governance t Post Request for Bids 340,000.00 0.00 Canceled 2023-04-21 2023-04-22 2023-06-06 2023-06-20 2023-08-01 2025-07-31 a base de datos de referenci l nvelope o bolster innovation in Peru as bibliográficas y citas PE-PROCIENCIA-353049-NC- RFQ / Servicio de publicación de avisos en diarios para el P 4. Project Management and Request for Quota Single Stage - One E Pending Impl royecto “Mejoramiento y Am IBRD / 93340 Post Open - National 50,000.00 0.00 2023-04-12 2023-05-28 2024-05-27 Monitoring & Evaluation tions nvelope ementation pliación de los Servicios de C TI para fortalecer el Sistema Nacional de Ciencia, Tecnolo gía e Innovación” PE-PROCIENCIA-358440-NC- 1: Strengthening SINACTI’s i Direct - Internation Under Imple DIR / Suscripción Nacional de IBRD / 93340 nstitutions and governance t Prior Direct Selection 4,009,946.00 0.00 2023-05-09 2023-05-02 2023-05-29 2023-05-04 2023-07-04 2025-07-03 al mentation Recursos de información de o bolster innovation in Peru Texto Completo Page 1 PE-PROCIENCIA-361882-NC- RFQ / Servicio de agenciamie 4. Project Management and Request for Quota Single Stage - One E Pending Impl IBRD / 93340 Post Open - National 30,000.00 0.00 2023-07-05 2023-08-20 2024-08-19 nto de pasajes aéreos a nivel Monitoring & Evaluation tions nvelope ementation nacional para el Proyecto PE-PROCIENCIA-338461-NC- RFQ / Servicio de mejoramie nto y adecuación de instalaci ones para las Oficinas del Pro 4. Project Management and Request for Quota Single Stage - One E Pending Impl IBRD / 93340 Post Open - National 50,000.00 0.00 2023-07-05 2023-08-24 2023-10-23 yecto Mejoramiento y amplia Monitoring & Evaluation tions nvelope ementation ción de los servicios de CTI p ara fortalecer el Sistema Naci onal de Ciencia, Tecnología e Innovación PE-PROCIENCIA-339685-NC- RFQ / Contratación de servici 4. Project Management and Request for Quota Single Stage - One E Pending Impl o de cableado estructurado d IBRD / 93340 Post Open - National 50,000.00 0.00 2023-07-05 2023-08-24 2023-10-23 Monitoring & Evaluation tions nvelope ementation e red de datos y eléctrico par a Oficinas del Proyecto CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PE-PROCIENCIA-334143-CS-L CS / Auditoria Externa para el Proyecto Mejoramiento y am 4. Project Management and Least Cost Selecti Pending Impleme IBRD / 93340 Post Open - National 85,427.00 0.00 2023-06-01 2023-06-22 2023-08-05 2023-09-02 2023-10-02 2023-11-06 2023-12-11 2026-12-10 pliación de los servicios de C Monitoring & Evaluation on ntation TI para fortalecer el Sistema Nacional de Ciencia, Tecnolo gía e Innovación PE-PROCIENCIA-334361-CS-L 1: Strengthening SINACTI’s i Least Cost Selecti Pending Impleme CS / Servicio de control de ca IBRD / 93340 nstitutions and governance t Post Open - National 213,065.33 0.00 2023-04-01 2023-04-22 2023-05-25 2023-06-22 2023-07-22 2023-09-06 2023-10-27 2025-12-05 on ntation lidad de software o bolster innovation in Peru PE-PROCIENCIA-334358-CS- 1: Strengthening SINACTI’s i CQS / Servicio para elaborar Consultant Qualifi Pending Impleme IBRD / 93340 nstitutions and governance t Post Open - National 11,871.86 0.00 2023-05-01 2023-05-22 2023-07-21 2023-08-20 2023-09-24 2024-01-22 un estudio de vigilancia tecn cation Selection ntation o bolster innovation in Peru ológica en biotecnología agro alimentaria PE-PROCIENCIA-334346-CS- CQS / Servicio para elaborar 1: Strengthening SINACTI’s i Consultant Qualifi Pending Impleme un estudio de vigilancia tecn IBRD / 93340 nstitutions and governance t Post Open - National 11,871.86 0.00 2023-05-01 2023-05-22 2023-07-26 2023-08-25 2023-10-05 2024-02-02 cation Selection ntation ológica en Tecnologías emer o bolster innovation in Peru gentes y disruptivas para SM ART CITIES PE-PROCIENCIA-334364-CS- 3. Strengthening Industry-ac CQS / Desarrollo de metodolo ademia linkages to accelerat Consultant Qualifi Pending Impleme gías para priorizar tecnología IBRD / 93340 e technology transfer and sc Post Open - National 62,814.07 0.00 2023-04-01 2023-04-22 2023-06-21 2023-07-21 2023-09-10 2024-03-08 cation Selection ntation s con potencial de financiami ience-based business innova ento y con alto impacto tion PE-PROCIENCIA-334345-CS- 3. Strengthening Industry-ac CQS / Servicio de preevaluaci ademia linkages to accelerat Consultant Qualifi Pending Impleme ón de proyectos financiados IBRD / 93340 e technology transfer and sc Post Open - National 75,376.88 0.00 2023-05-01 2023-05-22 2023-07-21 2023-08-20 2023-10-10 2024-04-07 cation Selection ntation por CONCYTEC y acompaña ience-based business innova miento para financiamiento tion PE-PROCIENCIA-334360-CS- CQS / Servicio de elaboración de la linea base del Proyecto 4. Project Management and Consultant Qualifi Mejoramiento y ampliación d IBRD / 93340 Post Open - National 100,502.51 0.00 Canceled 2023-06-01 2023-06-22 2023-08-21 2023-09-20 2023-10-31 2024-04-28 Monitoring & Evaluation cation Selection e los servicios de CTI para for talecer el Sistema Nacional d e Ciencia, Tecnología e Innov ación PE-PROCIENCIA-334332-CS- CQS / Desarrollo del módulo 4. Project Management and Consultant Qualifi Under Implement de vinculación con usuarios d IBRD / 93340 Post Open - National 87,939.70 0.00 2023-04-01 2023-06-22 2023-04-22 2023-06-05 2023-06-25 2023-07-19 2024-01-15 Monitoring & Evaluation cation Selection ation e fondos concursables (Plataf orma de Gestión de Fondos) PE-PROCIENCIA-334341-CS- CQS / Servicio de desarrollo 2. Capacity development for del análisis de demanda de s Consultant Qualifi Pending Impleme IBRD / 93340 the generation of knowledge Post Open - National 50,251.26 0.00 2023-08-01 2023-08-22 2023-10-26 2023-11-15 2023-12-26 2024-06-23 ectores productivos para el d cation Selection ntation in Strategic Areas esarrollo de proyectos de inv estigación en áreas estratégi cas PE-PROCIENCIA-334308-CS- 1: Strengthening SINACTI’s i Consultant Qualifi Pending Impleme CQS / Implementación de her IBRD / 93340 nstitutions and governance t Post Open - National 179,899.00 0.00 2023-08-01 2023-08-22 2023-10-21 2023-11-20 2023-12-25 2024-03-24 cation Selection ntation ramientas de soporte al gobi o bolster innovation in Peru erno de datos PE-PROCIENCIA-334302-CS- 1: Strengthening SINACTI’s i CQS / Servicio de diseño e im Consultant Qualifi Pending Impleme IBRD / 93340 nstitutions and governance t Post Open - National 150,754.00 0.00 2023-04-01 2023-04-22 2023-06-05 2023-07-05 2023-08-09 2024-02-05 plementación del proceso de cation Selection ntation o bolster innovation in Peru mesa de ayuda. PE-PROCIENCIA-347908-CS- CQS / Desarrollo de propuest 1: Strengthening SINACTI’s i a de arreglos normativos par Consultant Qualifi Pending Impleme IBRD / 93340 nstitutions and governance t Post Open - National 100,503.00 0.00 2023-08-01 2023-08-15 2023-10-09 2023-10-23 2023-11-20 2024-05-18 a la implementación de los p cation Selection ntation o bolster innovation in Peru rocesos de licenciamiento y a creditación de programas de posgrado PE-PROCIENCIA-334307-CS- 1: Strengthening SINACTI’s i CQS / Servicio de diseño e im Consultant Qualifi Pending Impleme IBRD / 93340 nstitutions and governance t Post Open - National 30,151.00 0.00 2023-08-01 2023-08-22 2023-10-05 2023-11-04 2023-12-09 2024-06-06 plementación de la línea de p cation Selection ntation o bolster innovation in Peru roducción de microformas PE-PROCIENCIA-334340-CS- 1: Strengthening SINACTI’s i CQS / Servicio de diseño de a Consultant Qualifi Pending Impleme IBRD / 93340 nstitutions and governance t Post Open - National 92,964.82 0.00 2023-12-01 2023-12-22 2024-02-10 2024-03-11 2024-04-15 2024-10-12 rreglo institucional para desa cation Selection ntation o bolster innovation in Peru rrollar red de sostenibilidad PE-PROCIENCIA-334347-CS- CQS / Desarrollo del módulo 1: Strengthening SINACTI’s i Consultant Qualifi Pending Impleme de gestión de evaluadores co IBRD / 93340 nstitutions and governance t Post Open - National 62,814.07 0.00 2023-09-01 2023-09-22 2023-11-05 2023-11-25 2023-12-19 2025-01-12 cation Selection ntation n enfoque regional – Latinoa o bolster innovation in Peru mérica (Plataforma de Gestió n de Fondos) Page 2 PE-PROCIENCIA-334365-CS- CQS / Servicio de programa d 1: Strengthening SINACTI’s i Consultant Qualifi Pending Impleme e capacitación especializada IBRD / 93340 nstitutions and governance t Post Open - National 251,256.28 0.00 2023-10-02 2023-10-23 2023-12-06 2023-12-21 2024-01-10 2024-11-05 cation Selection ntation para el fortalecimiento de ca o bolster innovation in Peru pacidades en gestión y opera ción de laboratorios PE-PROCIENCIA-334348-CS-L 1: Strengthening SINACTI’s i CS / Servicio para levantamie Least Cost Selecti Pending Impleme IBRD / 93340 nstitutions and governance t Post Open - National 75,376.88 0.00 2023-11-01 2023-11-22 2024-01-05 2024-01-12 2024-01-22 2024-02-08 2024-03-03 2024-08-30 nto de información sobre gru on ntation o bolster innovation in Peru pos, líneas y áreas de investi gación PE-PROCIENCIA-347915-CS- 1: Strengthening SINACTI’s i QCBS / Servicio para el desar Quality And Cost- Pending Impleme IBRD / 93340 nstitutions and governance t Post Open - National 201,005.00 0.00 2023-07-03 2023-07-24 2023-08-28 2023-10-17 2023-10-31 2023-12-14 2024-01-27 2025-01-26 rollo de diagnóstico y estado Based Selection ntation o bolster innovation in Peru del arte para programas de p osgrado PE-PROCIENCIA-335076-CS- QCBS / Servicio para la siste 1: Strengthening SINACTI’s i matización de procesos admi Quality And Cost- Open - Internationa Pending Impleme IBRD / 93340 nstitutions and governance t Post 482,412.00 0.00 2023-08-01 2023-08-22 2023-09-26 2023-11-15 2023-11-29 2024-01-12 2024-02-09 2025-02-08 nistrativos y misionales, de g Based Selection l ntation o bolster innovation in Peru estión documental, e implem entación de herramientas de optimización de procesos PE-PROCIENCIA-334352-CS- 3. Strengthening Industry-ac QCBS / Consultoría para defi ademia linkages to accelerat Quality And Cost- Open - Internationa Pending Impleme IBRD / 93340 Prior 1,130,653.00 0.00 2023-10-02 2023-10-23 2023-11-27 2024-01-16 2024-01-30 2024-03-14 2024-04-18 2024-08-16 nición de modelo de Oficina e technology transfer and sc Based Selection l ntation de Transferencia Tecnológica ience-based business innova y capacitaciones tion PE-PROCIENCIA-337449-CS- 1: Strengthening SINACTI’s i Quality And Cost- Pending Impleme QCBS / Consultoría para la im IBRD / 93340 nstitutions and governance t Post Open - National 188,944.72 0.00 2023-09-01 2023-09-22 2023-12-01 2023-12-06 2023-12-20 2024-01-20 2024-02-24 2027-02-23 Based Selection ntation plementación de funcionalida o bolster innovation in Peru des de PerúCris PE-PROCIENCIA-334344-CS- 3. Strengthening Industry-ac QCBS / Capacitación, acompa ademia linkages to accelerat ñamiento y asistencia técnic Quality And Cost- Open - Internationa Pending Impleme IBRD / 93340 e technology transfer and sc Post 829,145.36 0.00 2023-07-03 2023-07-24 2023-08-28 2023-10-17 2023-10-31 2023-12-14 2024-01-07 2025-01-06 a para la formulación e identi Based Selection l ntation ience-based business innova ficación de las iniciativas de tion vinculación academia industr ia INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PE-PROCIENCIA-334889-CS- 4. Project Management and Individual Consult CDS / Asistente Coordinación IBRD / 93340 Post Direct - National 21,105.53 0.00 Signed 2023-02-17 2023-03-07 2023-02-27 2023-03-14 2023-03-09 2023-03-23 2023-03-24 2024-03-23 Monitoring & Evaluation ant Selection Administrativa 1 PE-PROCIENCIA-334895-CS- 4. Project Management and Individual Consult Under Implement CDS / Analista en Soporte y S IBRD / 93340 Post Direct - National 33,166.00 0.00 2023-02-17 2023-03-23 2023-02-27 2023-03-14 2023-03-09 2023-03-23 2023-03-24 2024-03-23 Monitoring & Evaluation ant Selection ation eguimiento Subvenciones PE-PROCIENCIA-335025-CS-I 4. Project Management and Individual Consult Under Implement NDV / Analista en Tecnología IBRD / 93340 Post Limited 24,121.00 0.00 2023-03-01 2023-06-09 2023-03-06 2023-03-21 2023-04-14 2024-04-13 Monitoring & Evaluation ant Selection ation de la Información 1 PE-PROCIENCIA-335027-CS-I 4. Project Management and Individual Consult Under Implement NDV / Analista en Tecnología IBRD / 93340 Post Limited 24,121.00 0.00 2023-03-01 2023-06-09 2023-03-06 2023-03-21 2023-04-14 2024-04-13 Monitoring & Evaluation ant Selection ation de la Información 2 PE-PROCIENCIA-334618-CS-I 1: Strengthening SINACTI’s i Individual Consult Under Implement NDV / Apoyo de recopilación, IBRD / 93340 nstitutions and governance t Post Open - National 48,241.20 0.00 2023-03-15 2023-03-06 2023-04-08 2023-04-18 2023-05-12 2024-05-11 ant Selection ation calidad y procesamiento de d o bolster innovation in Peru atos - PerúCris PE-PROCIENCIA-334619-CS-I 1: Strengthening SINACTI’s i Individual Consult Under Implement NDV / Especialista para la ge IBRD / 93340 nstitutions and governance t Post Limited 21,105.53 0.00 2023-03-01 2023-03-06 2023-03-06 2023-03-21 2023-04-14 2024-04-13 ant Selection ation stión de implementación de i o bolster innovation in Peru nteroperabilidad PE-PROCIENCIA-334620-CS-I 1: Strengthening SINACTI’s i Individual Consult Under Implement NDV / Soporte administrativo IBRD / 93340 nstitutions and governance t Post Open - National 21,105.53 0.00 2023-03-15 2023-03-06 2023-04-08 2023-04-18 2023-05-12 2024-05-11 ant Selection ation para gestión administrativa o bolster innovation in Peru PE-PROCIENCIA-334621-CS-I 1: Strengthening SINACTI’s i NDV / Especialista en soporte Individual Consult Under Implement IBRD / 93340 nstitutions and governance t Post Open - National 30,150.76 0.00 2023-03-15 2023-03-06 2023-04-08 2023-04-18 2023-05-12 2024-05-11 funcional y técnico para los d ant Selection ation o bolster innovation in Peru irectorios y plataformas de C TI PE-PROCIENCIA-334795-CS-I 1: Strengthening SINACTI’s i Individual Consult Under Implement NDV / Experto en gestión de IBRD / 93340 nstitutions and governance t Post Limited 39,195.98 0.00 2023-03-01 2023-04-14 2023-03-06 2023-03-21 2023-04-14 2024-04-13 ant Selection ation organismos de investigación o bolster innovation in Peru PE-PROCIENCIA-334800-CS-I 1: Strengthening SINACTI’s i Individual Consult Under Implement NDV / Experto en gestión y r IBRD / 93340 nstitutions and governance t Post Limited 30,150.75 0.00 2023-03-01 2023-04-20 2023-03-06 2023-03-21 2023-04-14 2024-04-13 ant Selection ation egulación o bolster innovation in Peru PE-PROCIENCIA-334801-CS- 1: Strengthening SINACTI’s i Individual Consult Under Implement CDS / Soporte administrativo IBRD / 93340 nstitutions and governance t Post Direct - National 21,105.53 0.00 2023-02-17 2023-02-01 2023-02-27 2023-03-14 2023-03-09 2023-03-23 2023-03-24 2024-03-23 ant Selection ation para gestión administrativa - o bolster innovation in Peru Componente I PE-PROCIENCIA-334799-CS- 1: Strengthening SINACTI’s i Individual Consult Direct - Internation Under Implement CDS / Consultoría para el Est IBRD / 93340 nstitutions and governance t Post 50,251.26 0.00 2023-04-03 2023-04-10 2023-04-13 2023-04-23 2023-05-08 2023-11-04 ant Selection al ation udio de Eficiencia del Gasto P o bolster innovation in Peru úblico en CTI PE-PROCIENCIA-334802-CS-I 1: Strengthening SINACTI’s i Individual Consult Under Implement NDV / Experto en gestión y a IBRD / 93340 nstitutions and governance t Post Limited 39,195.98 0.00 2023-03-01 2023-04-20 2023-03-06 2023-03-21 2023-04-14 2024-04-13 ant Selection ation rticulación de CTI o bolster innovation in Peru PE-PROCIENCIA-334804-CS-I 1: Strengthening SINACTI’s i Individual Consult Pending Impleme NDV / Monitor Financiero par IBRD / 93340 nstitutions and governance t Post Open - National 12,060.30 0.00 2023-06-01 2023-06-25 2023-07-05 2023-07-29 2024-01-25 ant Selection ntation a supervisión - Redes de inve o bolster innovation in Peru stigación PE-PROCIENCIA-334805-CS-I 2. Capacity development for Individual Consult Pending Impleme NDV / Monitores Técnicos par IBRD / 93340 the generation of knowledge Post Open - National 60,301.51 0.00 2023-06-01 2023-06-25 2023-07-05 2023-07-29 2024-01-25 ant Selection ntation a supervisión in Strategic Areas PE-PROCIENCIA-334809-CS-I 2. Capacity development for Individual Consult Under Implement NDV / Servicio de análisis de IBRD / 93340 the generation of knowledge Post Limited 16,582.91 0.00 2023-03-01 2023-04-20 2023-03-06 2023-03-21 2023-04-14 2024-04-13 ant Selection ation datos - Programa de Doctora in Strategic Areas do Page 3 PE-PROCIENCIA-334808-CS-I 2. Capacity development for Individual Consult NDV / Experto en programas IBRD / 93340 the generation of knowledge Post Limited 39,195.98 0.00 Canceled 2023-03-01 2023-03-06 2023-03-21 2023-04-14 2024-04-13 ant Selection de postgrado de investigació in Strategic Areas n 3. Strengthening Industry-ac PE-PROCIENCIA-334821-CS-I ademia linkages to accelerat Individual Consult Under Implement IBRD / 93340 Post Limited 16,582.91 0.00 2023-03-01 2023-05-05 2023-03-06 2023-03-21 2023-04-14 2024-04-13 NDV / Apoyo Comunicacional e technology transfer and sc ant Selection ation ience-based business innova tion 3. Strengthening Industry-ac PE-PROCIENCIA-334823-CS-I ademia linkages to accelerat Individual Consult Pending Impleme NDV / Servicio en análisis de IBRD / 93340 Post Open - National 16,582.91 0.00 2023-03-15 2023-04-08 2023-04-18 2023-05-12 2024-05-11 e technology transfer and sc ant Selection ntation datos ience-based business innova tion 3. Strengthening Industry-ac PE-PROCIENCIA-334838-CS-I ademia linkages to accelerat Individual Consult Under Implement IBRD / 93340 Post Limited 39,195.98 0.00 2023-03-01 2023-04-20 2023-03-06 2023-03-21 2023-04-14 2024-04-13 NDV / Experto en innovación e technology transfer and sc ant Selection ation ience-based business innova tion PE-PROCIENCIA-334845-CS- CDS / Coordinador Adjunto p ara el Proyecto “Mejoramient 4. Project Management and Individual Consult Under Implement IBRD / 93340 Post Direct - National 60,301.51 0.00 2023-02-17 2023-03-02 2023-02-27 2023-03-14 2023-03-09 2023-03-23 2023-03-24 2024-03-23 o y Ampliación de los servicio Monitoring & Evaluation ant Selection ation s de CTI para fortalecer el Sis tema Nacional de Ciencia, Te cnología e Innovación” PE-PROCIENCIA-334848-CS- 4. Project Management and Individual Consult Under Implement CDS / Coordinador de Segui IBRD / 93340 Post Direct - National 51,256.28 0.00 2023-02-17 2023-03-02 2023-02-27 2023-03-14 2023-03-09 2023-03-23 2023-03-24 2024-03-23 Monitoring & Evaluation ant Selection ation miento y Monitoreo PE-PROCIENCIA-334850-CS- 4. Project Management and Individual Consult CDS / Asistente Administrativ IBRD / 93340 Post Direct - National 21,105.53 0.00 Signed 2023-02-17 2023-03-02 2023-02-27 2023-03-14 2023-03-09 2023-03-23 2023-03-24 2024-03-23 Monitoring & Evaluation ant Selection o para la Coordinación Adjunt a PE-PROCIENCIA-334853-CS-I 4. Project Management and Individual Consult Under Implement NDV / Asistente Administrativ IBRD / 93340 Post Open - National 15,075.38 0.00 2023-10-02 2023-05-05 2023-10-26 2023-11-05 2023-11-29 2024-11-28 Monitoring & Evaluation ant Selection ation o en Archivo PE-PROCIENCIA-339636-CS-I 4. Project Management and Individual Consult Under Implement IBRD / 93340 Post Open - National 39,195.98 0.00 2023-03-15 2023-03-17 2023-04-08 2023-04-18 2023-05-12 2024-05-11 NDV / Coordinador de Compo Monitoring & Evaluation ant Selection ation nente 1 PE-PROCIENCIA-334857-CS- 4. Project Management and Individual Consult Under Implement IBRD / 93340 Post Direct - National 39,195.98 0.00 2023-02-17 2023-03-23 2023-02-27 2023-03-09 2023-03-24 2024-03-23 CDS / Coordinador de Compo Monitoring & Evaluation ant Selection ation nente 2 PE-PROCIENCIA-334859-CS-I 4. Project Management and Individual Consult Under Implement NDV / Coordinador de Compo IBRD / 93340 Post Limited 39,195.98 0.00 2023-03-01 2023-03-17 2023-03-06 2023-03-24 2023-03-21 2023-04-21 2023-04-14 2024-04-13 Monitoring & Evaluation ant Selection ation nente 3 - Personal Clave PE-PROCIENCIA-334869-CS- 4. Project Management and Individual Consult Under Implement IBRD / 93340 Post Direct - National 39,195.98 0.00 2023-02-17 2023-03-02 2023-02-27 2023-03-14 2023-03-09 2023-03-23 2023-03-24 2024-03-23 CDS / Especialista Socio Amb Monitoring & Evaluation ant Selection ation iental PE-PROCIENCIA-334879-CS- 4. Project Management and Individual Consult Under Implement IBRD / 93340 Post Direct - National 30,150.75 0.00 2023-02-17 2023-03-02 2023-02-27 2023-03-14 2023-03-09 2023-03-23 2023-03-24 2024-03-23 CDS / Analista Ambiental Monitoring & Evaluation ant Selection ation PE-PROCIENCIA-334883-CS-I 4. Project Management and Individual Consult Under Implement IBRD / 93340 Post Open - National 30,150.75 0.00 2023-03-15 2023-03-02 2023-04-08 2023-04-18 2023-05-12 2024-05-11 NDV / Analista Social y de Gé Monitoring & Evaluation ant Selection ation nero PE-PROCIENCIA-334884-CS-I 4. Project Management and Individual Consult Under Implement IBRD / 93340 Post Open - National 33,165.83 0.00 2023-03-15 2023-03-15 2023-04-08 2023-04-18 2023-05-12 2024-05-11 NDV / Especialista en Comuni Monitoring & Evaluation ant Selection ation caciones PE-PROCIENCIA-334885-CS- 4. Project Management and Individual Consult Under Implement IBRD / 93340 Post Direct - National 30,150.75 0.00 2023-02-17 2023-03-15 2023-02-27 2023-03-09 2023-03-24 2024-03-23 CDS / Analista de Comunicaci Monitoring & Evaluation ant Selection ation ones PE-PROCIENCIA-334886-CS- 4. Project Management and Individual Consult Under Implement IBRD / 93340 Post Direct - National 39,195.98 0.00 2023-02-17 2023-03-07 2023-02-27 2023-03-14 2023-03-09 2023-03-23 2023-03-24 2024-03-23 CDS / Especialista en Diseño Monitoring & Evaluation ant Selection ation PE-PROCIENCIA-334890-CS- 4. Project Management and Individual Consult Under Implement CDS / Asistente Administrativ IBRD / 93340 Post Direct - National 21,105.53 0.00 2023-02-17 2023-03-07 2023-02-27 2023-03-14 2023-03-09 2023-03-23 2023-03-24 2024-03-23 Monitoring & Evaluation ant Selection ation o - Unidad Gestión de Concur sos PE-PROCIENCIA-334891-CS-I 4. Project Management and Individual Consult Under Implement NDV / Especialista en Evalua IBRD / 93340 Post Open - National 39,195.98 0.00 2023-03-15 2023-04-14 2023-04-08 2023-04-18 2023-05-12 2024-05-11 Monitoring & Evaluation ant Selection ation ción de Beneficiarios PE-PROCIENCIA-334893-CS- 4. Project Management and Individual Consult CDS / Especialista en Soporte IBRD / 93340 Post Direct - National 39,195.98 0.00 Canceled 2023-02-17 2023-03-23 2023-02-27 2023-03-09 2023-03-24 2024-03-23 Monitoring & Evaluation ant Selection y Seguimiento Subvenciones PE-PROCIENCIA-334989-CS-I 4. Project Management and Individual Consult Under Implement IBRD / 93340 Post Limited 39,195.98 0.00 2023-03-01 2023-05-30 2023-03-06 2023-03-21 2023-04-14 2024-04-13 NDV / Especialista en Vincula Monitoring & Evaluation ant Selection ation ción PE-PROCIENCIA-335075-CS-I 4. Project Management and Individual Consult Under Implement NDV / Asistente Técnico - Uni IBRD / 93340 Post Open - National 21,105.53 0.00 2023-03-15 2023-05-30 2023-04-08 2023-04-18 2023-05-12 2024-05-11 Monitoring & Evaluation ant Selection ation dad de Vinculación PE-PROCIENCIA-334992-CS-I 4. Project Management and Individual Consult Under Implement IBRD / 93340 Post Open - National 33,165.83 0.00 2023-03-15 2023-03-07 2023-04-08 2023-04-17 2023-04-18 2023-04-17 2023-05-12 2024-05-11 NDV / Analista Legal Monitoring & Evaluation ant Selection ation PE-PROCIENCIA-334993-CS- 4. Project Management and Individual Consult Under Implement CDS / Especialista en Planific IBRD / 93340 Post Direct - National 42,211.06 0.00 2023-02-17 2023-03-01 2023-02-27 2023-03-09 2023-03-24 2024-03-23 Monitoring & Evaluation ant Selection ation ación y Presupuesto PE-PROCIENCIA-334996-CS-I 4. Project Management and Individual Consult Pending Impleme NDV / Especialista en Seguim IBRD / 93340 Post Open - National 39,195.98 0.00 2023-10-02 2023-10-26 2023-11-05 2023-11-29 2024-11-28 Monitoring & Evaluation ant Selection ntation iento y Monitoreo PE-PROCIENCIA-334998-CS- 4. Project Management and Individual Consult Under Implement CDS / Analista de Seguimient IBRD / 93340 Post Direct - National 30,150.75 0.00 2023-02-17 2023-03-02 2023-02-27 2023-03-09 2023-03-24 2024-03-23 Monitoring & Evaluation ant Selection ation o y Monitoreo PE-PROCIENCIA-335000-CS- CDS / Especialista de Implem 4. Project Management and Individual Consult Under Implement IBRD / 93340 Post Direct - National 28,643.22 0.00 2023-02-17 2023-03-01 2023-02-27 2023-03-09 2023-03-24 2024-03-23 entación, Gestión y Monitore Monitoring & Evaluation ant Selection ation o de Intervenciones PE-PROCIENCIA-335001-CS- 4. Project Management and Individual Consult Under Implement CDS / Especialista en Soporte IBRD / 93340 Post Direct - National 24,120.60 0.00 2023-02-17 2023-03-01 2023-02-27 2023-03-14 2023-03-09 2023-03-23 2023-03-24 2024-03-23 Monitoring & Evaluation ant Selection ation de Gestión Administrativa Page 4 PE-PROCIENCIA-335002-CS- 4. Project Management and Individual Consult Under Implement CDS / Especialista Técnico pa IBRD / 93340 Post Direct - National 39,195.98 0.00 2023-02-17 2023-03-01 2023-02-27 2023-03-14 2023-03-09 2023-03-23 2023-03-24 2024-03-23 Monitoring & Evaluation ant Selection ation ra implementación de proyec tos de CTI PE-PROCIENCIA-335003-CS-I 4. Project Management and Individual Consult Under Implement IBRD / 93340 Prior Open - National 45,226.13 0.00 2023-03-15 2023-03-02 2023-04-08 2023-04-24 2023-04-18 2023-04-27 2023-05-12 2024-05-11 NDV / Especialista en Adquisi Monitoring & Evaluation ant Selection ation ciones PE-PROCIENCIA-335005-CS-I 4. Project Management and Individual Consult NDV / Especialista en Adquisi IBRD / 93340 Prior Open - National 39,195.98 0.00 Canceled 2023-03-15 2023-03-02 2023-04-08 2023-04-18 2023-05-12 2024-05-11 Monitoring & Evaluation ant Selection ciones - Subproyectos PE-PROCIENCIA-335007-CS-I 4. Project Management and Individual Consult Under Implement NDV / Asistente Administrativ IBRD / 93340 Prior Limited 21,105.53 0.00 2023-03-01 2023-03-07 2023-03-06 2023-04-24 2023-03-21 2023-05-19 2023-04-14 2024-04-13 Monitoring & Evaluation ant Selection ation o - Adquisiciones PE-PROCIENCIA-335008-CS- 4. Project Management and Individual Consult Under Implement IBRD / 93340 Prior Direct - National 30,151.00 0.00 2023-02-17 2023-03-08 2023-02-27 2023-03-14 2023-03-09 2023-04-24 2023-03-24 2024-03-23 CDS / Analista en Adquisicion Monitoring & Evaluation ant Selection ation es 1 PE-PROCIENCIA-335011-CS- 4. Project Management and Individual Consult Under Implement IBRD / 93340 Post Direct - National 42,211.06 0.00 2023-02-17 2023-03-15 2023-02-27 2023-03-09 2023-03-24 2024-03-23 CDS / Especialista en Tesorer Monitoring & Evaluation ant Selection ation ía PE-PROCIENCIA-335012-CS- 4. Project Management and Individual Consult Under Implement IBRD / 93340 Post Direct - National 27,135.68 0.00 2023-02-17 2023-03-15 2023-02-27 2023-03-09 2023-03-24 2024-03-23 CDS / Analista en Tesorería Monitoring & Evaluation ant Selection ation PE-PROCIENCIA-335019-CS- 4. Project Management and Individual Consult Under Implement IBRD / 93340 Post Direct - National 27,135.68 0.00 2023-02-17 2023-03-17 2023-02-27 2023-03-09 2023-03-24 2024-03-23 CDS / Analista de Contabilida Monitoring & Evaluation ant Selection ation d PE-PROCIENCIA-335021-CS-I 4. Project Management and Individual Consult Under Implement NDV / Especialista en Tecnol IBRD / 93340 Post Open - National 39,195.98 0.00 2023-03-15 2023-06-09 2023-04-08 2023-04-18 2023-05-12 2024-05-11 Monitoring & Evaluation ant Selection ation ogía de la Información PE-PROCIENCIA-335023-CS-I 4. Project Management and Individual Consult IBRD / 93340 Post Limited 21,105.53 0.00 Canceled 2023-03-01 2023-03-06 2023-03-21 2023-04-14 2024-04-13 NDV / Analista Técnico SIGA - Monitoring & Evaluation ant Selection SIAF PE-PROCIENCIA-335029-CS-I 4. Project Management and Individual Consult Under Implement IBRD / 93340 Post Limited 30,150.75 0.00 2023-03-01 2023-03-06 2023-03-06 2023-03-21 2023-04-14 2024-04-13 NDV / Profesional Ejecución C Monitoring & Evaluation ant Selection ation ontractual PE-PROCIENCIA-335032-CS-I 4. Project Management and Individual Consult Under Implement IBRD / 93340 Post Limited 21,105.53 0.00 2023-03-01 2023-03-06 2023-03-06 2023-04-26 2023-03-21 2023-04-14 2024-04-13 NDV / Analista Ejecución Con Monitoring & Evaluation ant Selection ation tractual PE-PROCIENCIA-335010-CS-I 4. Project Management and Individual Consult IBRD / 93340 Prior Limited 30,151.00 0.00 Canceled 2023-03-01 2023-03-07 2023-03-06 2023-03-21 2023-04-14 2024-04-13 NDV / Analista en Adquisicion Monitoring & Evaluation ant Selection es 3 PE-PROCIENCIA-335009-CS-I 4. Project Management and Individual Consult IBRD / 93340 Prior Limited 30,151.00 0.00 Canceled 2023-03-01 2023-03-08 2023-03-06 2023-03-21 2023-04-14 2024-04-13 NDV / Analista en Adquisicion Monitoring & Evaluation ant Selection es 2 PE-PROCIENCIA-337642-CS-I 2. Capacity development for Individual Consult Under Implement NDV / Especialista en I+D - N IBRD / 93340 the generation of knowledge Post Limited 30,151.00 0.00 2023-03-01 2023-04-14 2023-03-06 2023-03-21 2023-04-14 2024-04-13 ant Selection ation ecesidades de Áreas Estratég in Strategic Areas icas PE-PROCIENCIA-347874-CS-I 4. Project Management and Individual Consult Under Implement IBRD / 93340 Post Open - National 42,211.00 0.00 2023-03-22 2023-03-10 2023-04-20 2023-04-16 2023-04-25 2023-04-17 2023-05-19 2024-05-18 NDV / Especialista Legal Monitoring & Evaluation ant Selection ation PE-PROCIENCIA-347875-CS-I 1: Strengthening SINACTI’s i Individual Consult Under Implement NDV / Experto en diseño de p IBRD / 93340 nstitutions and governance t Post Open - National 30,151.00 0.00 2023-03-22 2023-04-20 2023-04-20 2023-04-30 2023-05-24 2024-05-23 ant Selection ation olíticas publicas de CTI o bolster innovation in Peru PE-PROCIENCIA-347877-CS-I 2. Capacity development for NDV / Especialista en Fortale Individual Consult Under Implement IBRD / 93340 the generation of knowledge Post Open - National 30,150.25 0.00 2023-03-22 2023-04-20 2023-04-20 2023-04-30 2023-05-24 2024-05-23 cimiento de Capital Físico - F ant Selection ation in Strategic Areas ortalecimiento de Laboratori os 3. Strengthening Industry-ac PE-PROCIENCIA-347881-CS-I ademia linkages to accelerat Individual Consult Under Implement NDV / Experto en Transferen IBRD / 93340 Post Open - National 39,196.00 0.00 2023-03-22 2023-05-05 2023-04-20 2023-04-30 2023-05-24 2024-05-23 e technology transfer and sc ant Selection ation cia de Tecnología ience-based business innova tion PE-PROCIENCIA-347883-CS-I 3. Strengthening Industry-ac NDV / Profesional en gestión ademia linkages to accelerat Individual Consult Under Implement IBRD / 93340 Post Open - National 30,151.00 0.00 2023-03-22 2023-04-14 2023-04-20 2023-04-30 2023-05-24 2024-05-23 de la innovación y transferen e technology transfer and sc ant Selection ation cia de tecnología ience-based business innova tion PE-PROCIENCIA-347884-CS-I 4. Project Management and Individual Consult Under Implement IBRD / 93340 Post Open - National 42,211.00 0.00 2023-03-22 2023-03-10 2023-04-25 2023-04-17 2023-05-05 2023-04-17 2023-05-29 2024-05-28 NDV / Especialista Financiero Monitoring & Evaluation ant Selection ation PE-PROCIENCIA-334991-CS-I 4. Project Management and Individual Consult IBRD / 93340 Post Limited 42,211.06 0.00 Canceled 2023-03-01 2023-03-06 2023-03-21 2023-04-14 2024-04-13 NDV / Especialista Legal Monitoring & Evaluation ant Selection PE-PROCIENCIA-334796-CS-I 1: Strengthening SINACTI’s i Individual Consult NDV / Experto en Diseño de IBRD / 93340 nstitutions and governance t Post Limited 30,150.75 0.00 Canceled 2023-03-01 2023-03-06 2023-03-21 2023-04-14 2024-04-13 ant Selection políticas publicas de CTI o bolster innovation in Peru PE-PROCIENCIA-334816-CS-I 2. Capacity development for NDV / Especialista en Fortale Individual Consult IBRD / 93340 the generation of knowledge Post Limited 30,150.75 0.00 Canceled 2023-03-01 2023-03-06 2023-03-21 2023-04-14 2024-04-13 cimiento de Capital Físico - F ant Selection in Strategic Areas ortalecimiento de laboratorio s 3. Strengthening Industry-ac PE-PROCIENCIA-334833-CS-I ademia linkages to accelerat Individual Consult NDV / Experto en transferenc IBRD / 93340 Post Limited 39,195.98 0.00 Canceled 2023-03-01 2023-03-06 2023-03-21 2023-04-14 2024-04-13 e technology transfer and sc ant Selection ia de tecnología ience-based business innova tion PE-PROCIENCIA-334835-CS-I 3. Strengthening Industry-ac NDV / Profesional en gestión ademia linkages to accelerat Individual Consult IBRD / 93340 Post Limited 30,150.75 0.00 Canceled 2023-03-01 2023-03-06 2023-03-21 2023-04-14 2024-04-13 de la innovación y transferen e technology transfer and sc ant Selection cia de tecnología ience-based business innova tion PE-PROCIENCIA-335013-CS- 4. Project Management and Individual Consult IBRD / 93340 Post Direct - National 42,211.06 0.00 Canceled 2023-02-17 2023-02-27 2023-03-09 2023-03-24 2024-03-23 CDS / Especialista Financiero Monitoring & Evaluation ant Selection PE-PROCIENCIA-352364-CS-I 4. Project Management and Individual Consult Under Implement IBRD / 93340 Post Limited 21,106.00 0.00 2023-04-20 2023-04-14 2023-04-25 2023-05-10 2023-06-03 2024-06-02 NDV / Apoyo Técnico en SIGA Monitoring & Evaluation ant Selection ation - SIAF PE-PROCIENCIA-357990-CS- 4. Project Management and IBRD / 93340 Post Direct Selection Direct - National 33,166.00 0.00 Canceled 2023-05-08 2023-05-15 2023-05-18 2023-06-12 2024-06-11 CDS / Analista en Adquisicion Monitoring & Evaluation es 2 Page 5 PE-PROCIENCIA-357991-CS- 4. Project Management and Under Implement IBRD / 93340 Prior Direct Selection Direct - National 33,166.00 0.00 2023-05-08 2023-05-19 2023-05-18 2023-06-20 2023-06-12 2024-06-11 CDS / Analista en Adquisicion Monitoring & Evaluation ation es 3 PE-PROCIENCIA-334995-CS-I 4. Project Management and Individual Consult Under Implement NDV / Analista en Planeamie IBRD / 93340 Post Open - National 36,180.90 0.00 2023-03-15 2023-05-15 2023-04-08 2023-04-18 2023-05-12 2024-05-11 Monitoring & Evaluation ant Selection ation nto y Presupuesto Sénior PE-PROCIENCIA-361886-CS-I 2. Capacity development for Individual Consult Under Implement NDV / Experto en programas IBRD / 93340 the generation of knowledge Post Limited 39,196.00 0.00 2023-07-03 2023-06-09 2023-07-08 2023-07-23 2023-08-16 2024-08-15 ant Selection ation de postgrado de investigació in Strategic Areas n 1: Strengthening SINACTI’s i PE-PROCIENCIA-334624-CS-I Individual Consult Under Implement IBRD / 93340 nstitutions and governance t Post Limited 18,844.22 0.00 2023-07-03 2023-06-09 2023-07-08 2023-07-23 2023-08-16 2024-08-15 NDV / Especialista en testing ant Selection ation o bolster innovation in Peru PE-PROCIENCIA-334888-CS-I 4. Project Management and Individual Consult Pending Impleme IBRD / 93340 Post Open - National 30,150.75 0.00 2023-07-03 2023-07-27 2023-08-06 2023-08-30 2024-08-29 NDV / Analista de Diseño Monitoring & Evaluation ant Selection ntation PE-PROCIENCIA-334623-CS-I 1: Strengthening SINACTI’s i Individual Consult Pending Impleme NDV / Especialista en desarro IBRD / 93340 nstitutions and governance t Post Limited 60,301.50 0.00 2023-07-03 2023-07-08 2023-07-23 2023-08-16 2024-08-15 ant Selection ntation llo de software - PerúCris o bolster innovation in Peru PE-PROCIENCIA-334988-CS-I 4. Project Management and Individual Consult Pending Impleme NDV / Asistente Técnico para IBRD / 93340 Post Open - National 21,105.53 0.00 2023-07-03 2023-07-27 2023-08-06 2023-08-30 2024-08-29 Monitoring & Evaluation ant Selection ntation la Unidad de Vinculación PE-PROCIENCIA-334994-CS-I 4. Project Management and Individual Consult Pending Impleme NDV / Asistente Administrativ IBRD / 93340 Post Open - National 21,105.53 0.00 2023-07-03 2023-07-27 2023-08-06 2023-08-30 2024-08-29 Monitoring & Evaluation ant Selection ntation o - Coordinación Administrati va 2 PE-PROCIENCIA-335015-CS-I 4. Project Management and Individual Consult Pending Impleme NDV / Asistente Administrativ IBRD / 93340 Post Open - National 21,105.53 0.00 2023-07-03 2023-07-27 2023-08-06 2023-08-30 2024-08-29 Monitoring & Evaluation ant Selection ntation o - Coordinación Administrati va 3 PE-PROCIENCIA-334615-CS-I 1: Strengthening SINACTI’s i Individual Consult Pending Impleme NDV / Apoyo Técnico en mes IBRD / 93340 nstitutions and governance t Post Limited 12,060.30 0.00 2023-07-03 2023-07-08 2023-07-23 2023-08-16 2024-08-15 ant Selection ntation a de ayuda o bolster innovation in Peru PE-PROCIENCIA-334810-CS-I 2. Capacity development for Individual Consult Pending Impleme NDV / Monitores senior - bec IBRD / 93340 the generation of knowledge Post Open - National 265,326.63 0.00 2023-08-01 2023-08-25 2023-09-04 2023-09-28 2024-09-27 ant Selection ntation as in Strategic Areas PE-PROCIENCIA-334814-CS-I 2. Capacity development for NDV / Monitor Financiero par Individual Consult Pending Impleme IBRD / 93340 the generation of knowledge Post Open - National 24,120.60 0.00 2023-08-01 2023-08-25 2023-09-04 2023-09-28 2024-09-27 a supervisión - Fortalecimient ant Selection ntation in Strategic Areas o de laboratorios 3. Strengthening Industry-ac PE-PROCIENCIA-334840-CS-I ademia linkages to accelerat Individual Consult Pending Impleme NDV / Monitores Técnicos par IBRD / 93340 Post Open - National 241,206.03 0.00 2023-08-01 2023-08-25 2023-09-04 2023-09-28 2024-09-27 e technology transfer and sc ant Selection ntation a supervisión ience-based business innova tion PE-PROCIENCIA-334616-CS-I 1: Strengthening SINACTI’s i Individual Consult Pending Impleme NDV / Coordinación de proye IBRD / 93340 nstitutions and governance t Post Open - National 36,180.90 0.00 2023-08-01 2023-08-25 2023-09-04 2023-09-28 2024-09-27 ant Selection ntation ctos de transformación digita o bolster innovation in Peru l PE-PROCIENCIA-334813-CS-I 2. Capacity development for Individual Consult Pending Impleme NDV / Monitor Técnico para s IBRD / 93340 the generation of knowledge Post Open - National 30,150.75 0.00 2023-08-01 2023-08-25 2023-09-04 2023-09-28 2024-09-27 ant Selection ntation upervisión - Fortalecimiento in Strategic Areas de laboratorios PE-PROCIENCIA-334819-CS-I 3. Strengthening Industry-ac NDV / Consultores para brind ademia linkages to accelerat Individual Consult Pending Impleme ar apoyo y seguimiento a los IBRD / 93340 e technology transfer and sc Post Open - National 84,422.11 0.00 2023-09-01 2023-09-25 2023-10-05 2023-10-29 2024-10-28 ant Selection ntation equipos de gestión de iniciati ience-based business innova vas de vinculación academia tion industria 3. Strengthening Industry-ac PE-PROCIENCIA-334842-CS-I ademia linkages to accelerat Individual Consult Pending Impleme NDV / Monitores Financieros IBRD / 93340 Post Open - National 192,964.82 0.00 2023-08-01 2023-08-25 2023-09-04 2023-09-28 2024-09-27 e technology transfer and sc ant Selection ntation para supervisión ience-based business innova tion PE-PROCIENCIA-334892-CS-I 4. Project Management and Individual Consult Under Implement IBRD / 93340 Post Open - National 30,150.75 0.00 2023-07-03 2023-06-21 2023-07-27 2023-08-06 2023-08-30 2024-08-29 NDV / Analista de Evaluación Monitoring & Evaluation ant Selection ation PE-PROCIENCIA-334803-CS-I 1: Strengthening SINACTI’s i Individual Consult Pending Impleme NDV / Monitor Técnico para s IBRD / 93340 nstitutions and governance t Post Open - National 15,075.38 0.00 2023-09-01 2023-09-25 2023-10-05 2023-10-29 2024-04-26 ant Selection ntation upervisión - Redes de investi o bolster innovation in Peru gación PE-PROCIENCIA-334622-CS-I 1: Strengthening SINACTI’s i NDV / Coordinador en imple Individual Consult Pending Impleme IBRD / 93340 nstitutions and governance t Post Open - National 37,688.44 0.00 2023-08-01 2023-08-25 2023-09-04 2023-09-28 2024-09-27 mentación y operación de inf ant Selection ntation o bolster innovation in Peru raestructura AWS PE-PROCIENCIA-334807-CS-I 2. Capacity development for Individual Consult Pending Impleme NDV / Monitores Financieros IBRD / 93340 the generation of knowledge Post Open - National 24,120.60 0.00 2023-08-01 2023-08-25 2023-09-04 2023-09-28 2024-09-27 ant Selection ntation para supervisión in Strategic Areas PE-PROCIENCIA-335018-CS-I 4. Project Management and Individual Consult Pending Impleme IBRD / 93340 Post Open - National 27,135.68 0.00 2023-12-01 2023-12-25 2024-01-04 2024-01-28 2025-01-27 NDV / Analista de Finanzas Monitoring & Evaluation ant Selection ntation PE-PROCIENCIA-364431-CS-I 1: Strengthening SINACTI’s i NDV / Servicio de identificaci Individual Consult Under Implement IBRD / 93340 nstitutions and governance t Post Open - National 25,126.00 0.00 2023-07-03 2023-06-27 2023-08-01 2023-08-11 2023-08-26 2023-11-24 ón, análisis y propuesta meto ant Selection ation o bolster innovation in Peru dológica para la priorización de cadenas de valor PE-PROCIENCIA-369588-CS-I 4. Project Management and Individual Consult Pending Impleme NDV / Especialista en Adquisi IBRD / 93340 Prior Limited 39,200.00 0.00 2023-07-10 2023-07-15 2023-08-05 2023-08-17 2024-08-11 Monitoring & Evaluation ant Selection ntation ciones - Subproyectos Page 6 PROCUREMENT PLAN (Textual Part) Country: Republic of Tajikistan Full Project Name: CASA-1000 Community Support Project Project information Total Finance ($): US$ 26 million equivalent Project Number: P165313 Project Implementing Agencies ESPMU and NSIFT Date of the Procurement Plan February 6, 2019 (initial) Period covered by this Procurement Project duration (5 years) Plan: Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016, revised November 2017 and August 2018) (“Procurement Regulations”), the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), procurement under World Bank financed operations may be carried out in accordance with “Tendering with Unlimited Participation” method set forth in the Law of the Republic of Tajikistan “Оn Public Procurement of Goods, Works and Services”, # 168 dated March 3, 2006 (as amended by Law #815, the “Law of the Republic of Tajikistan on “Introduction of Amendments and Additions to the Law of the Republic of Tajikistan on ‘Public Procurement of Goods, Works and Services’” dated April 16, 2012), provided that such arrangements continue to meet requirements of the paragraph 5.4 of the Procurement Regulations and the following conditions: • The request for bids/request for proposals document shall require that bidders/proposers submitting bids/proposals present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, World Bank Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights; • The request for bids/request for proposals document, including contract forms, acceptable to the Bank shall be used. • The request for bids/request for proposals document and contract shall provide the right to the Bank to review procurement documentation and activities. • Borrower shall put in place an effective complaints review mechanism with procurement related complaints and shall disclose the details in all the bidding documents. All complaints shall be recorded by the Borrower in the appropriate tracking and monitoring system, as agreed between the Bank and the Borrower. • No preference shall be applied under competitive bidding following national market approach. Other national procurement arrangements such as tendering with limited participation, request for quotations, direct contracting, may be used on the above stated conditions. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works): “Not Applicable” Other Relevant Procurement Information. The community-driven development (CDD) approach and procurement by the communities will follow Procurement Regulations paragraph 6.52 and Annex XII - Selection Methods, paragraphs 6.9 and 6.10. The procurement arrangements at the community level (including procurement responsibilities, procedures, disclosure requirements, sample documentation and oversight mechanisms) will be elaborated in the Project Operations Manual (POM) and Sub-Grant Manual (SGM) that shall be approved by the Bank and made publicly available by the Borrower. Community procurement will follow the Guidance Note for Design and Management of Procurement Responsibilities in Community Driven Development Projects (March 15, 2012). PROCUREMENT Central Asia : CASA1000 Community Support Project for Tajikistan PLAN General Information Country: Central Asia 2019-10-01 Bank’s Approval Date of the Original Procurement Plan: 2023-06-01 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P165313 GPN Date: Project Name: CASA1000 Community Support Project for Tajikistan Loan / Credit No: IDA / D4400, TF / A9568 Energy Sector Project Management Unit Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned BT/CSP/1BC / Supply and Ins tallation for construction of Is Component 1. Rural Electrici Open - Internationa Single Stage - One E 4,171,208.7 2021-01-2 IDA / D4400 Post Request for Bids 4,000,000.00 Signed 2020-04-09 2020-07-21 2020-04-14 2020-07-22 2020-05-26 2020-09-04 2020-06-25 2020-12-28 2020-07-30 2021-01-30 fara-1 SS & distribution netw ty Supply Improvements l nvelope 7 6 orks improvements 110/10kV , line & substation BT/CSP/1AGW / Supply and i nstallation contract for villag e electricity in Sogd, Khatlon, Component 1. Rural Electrici Open - Internationa Single Stage - One E 4,838,966.2 2021-10-0 IDA / D4400 Post Request for Bids 5,200,000.00 Signed 2020-12-20 2021-03-26 2020-12-25 2021-03-30 2021-02-05 2021-05-25 2021-03-07 2021-07-07 2021-04-11 2021-09-17 RRS Regions & Vorukh and C ty Supply Improvements l nvelope 8 8 horkuh –Village electricity su pply improvements in the cor ridor of impact GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 1C-IT-CSP / Informational Te Component 1. Rural Electrici Request for Quota Single Stage - One E chnology (IT) equipment and IDA / D4400 Post Open - National 15,862.00 13,186.56 Completed 2021-09-21 2021-11-16 2021-11-02 2022-05-15 2021-12-14 ty Supply Improvements tions nvelope furniture for equipping the pr oject offices. Component 4. Project Manag BT-RFQ/G-01 / Procurement Request for Quota Single Stage - One E IDA / D4400 ement, Monitoring and Evalu Post Open - National 98,000.00 0.00 Signed 2022-02-24 2022-04-23 2022-07-22 of vehicles to PMU tions nvelope ation, and Communications NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CASA-CS-PR-T / To deliver an external massage to the Taji k society and outside that fu Component 4. Project Manag lfills their common objectives Consultant Qualifi TF / A9568 ement, Monitoring and Evalu Post Open - National 50,000.00 0.00 Signed 2022-11-11 2020-06-02 2022-12-02 2023-02-10 2023-01-15 2020-07-21 2023-02-14 2020-08-18 2023-03-21 2025-03-20 - to inform and attract intere cation Selection ation, and Communications st in the on going economic d evelopment and related trad e and investment opportuniti es in the Tajikistan and regio n. INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ESPMU-CSP-1C-IC-1B / Cons ultant(s) for a design of tech Component 1. Rural Electrici Individual Consult nical specifications, bidding d IDA / D4400 Post Open 40,000.00 26,444.76 Completed 2019-09-30 2019-08-10 2019-11-18 2019-11-11 2019-12-09 2019-12-17 2020-01-13 2019-12-26 2020-07-11 2020-12-16 ty Supply Improvements ant Selection ocumentation and supervisio n for Subcomponent 1B ESPMU-CSP-1C-IC-1A / Cons ultant(s) for the design of te Component 1. Rural Electrici Individual Consult chnical specifications, biddin IDA / D4400 Post Open 60,000.00 56,128.66 Completed 2019-09-30 2019-08-10 2019-11-18 2019-11-11 2019-12-09 2019-12-17 2020-01-13 2019-12-25 2020-07-11 2021-01-18 ty Supply Improvements ant Selection g documentation and supervi sion for Subcomponent 1A PMU/CSP/IC/B / Individual co nsultant for technical specific Component 1. Rural Electrici Individual Consult ations, bidding documents, e IDA / D4400 Post Open 40,000.00 0.00 Canceled 2020-12-10 2021-01-20 2021-01-28 2021-02-18 2021-03-25 2022-08-07 ty Supply Improvements ant Selection valuation, contract award, an d supervision of subcompone nt 1B CSP/IC/ES / Preparation of an Environmental and Social Im pact Assessment (ESIA) and Environment and Social man Component 1. Rural Electrici IDA / D4400 Post Direct Selection Direct 9,980.00 9,896.80 Signed 2020-12-23 2020-12-23 2021-01-02 2021-01-20 2021-03-08 2021-01-21 2021-09-04 agement plan for the new 11 ty Supply Improvements 0/10 kV substation to be con structed in the rural settleme nt of Vahdat in Isfara city an d its supporting infrastructur e. CSP-IC-1A / Consultant for d esign of technical specificatio Component 1. Rural Electrici Individual Consult ns, bidding documentation, e IDA / D4400 Post Open 40,000.00 0.00 Canceled 2020-12-30 2021-01-20 2021-02-17 2021-03-10 2021-04-14 2021-10-11 ty Supply Improvements ant Selection valuation process, awarding and supervision for Subcomp onent 1A Page 1 PCS-IC-1A / Consultant for d esign of technical specificatio Component 1. Rural Electrici Individual Consult ns, bidding documentation, e IDA / D4400 Post Open 35,000.00 19,289.78 Signed 2021-02-08 2021-02-04 2021-03-29 2021-05-06 2021-04-19 2021-05-20 2021-05-24 2021-06-01 2021-11-20 ty Supply Improvements ant Selection valuation process, awarding and supervision for Subcomp onent 1A PCS-IC-1B / Individual consul tant for technical specificatio Component 1. Rural Electrici Individual Consult IDA / D4400 Post Open 25,000.00 16,694.43 Signed 2021-02-04 2021-03-30 2021-03-25 2021-05-06 2021-04-15 2021-05-20 2021-05-20 2021-06-01 2021-11-16 ns, supervision and engineeri ty Supply Improvements ant Selection ng technical matters of subc omponent 1B IC-RS / Reporting Specialist Component 1. Rural Electrici Individual Consult under CASA-1000 and CASA- IDA / D4400 Post Open 20,000.00 15,907.04 Signed 2021-11-01 2021-12-16 2021-12-20 2022-01-13 2022-01-10 2022-01-17 2022-02-14 2022-01-18 2022-08-13 ty Supply Improvements ant Selection 100 CSP Projects CSP-FIC / Financial individual Component 4. Project Manag Individual Consult Pending Impleme consultant for Community Su IDA / D4400 ement, Monitoring and Evalu Post Open - National 22,000.00 0.00 2023-01-05 2023-01-27 2023-02-03 2023-02-11 2024-06-10 ant Selection ntation pport Project ation, and Communications Page 2 PROCUREMENT PLAN (Textual Part) Project information: [country] [Project name] [P-number] Project Implementation agency: [insert legal name] Date of the Procurement Plan: [insert date] Period covered by this Procurement Plan: [insert from – to period] Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in [insert appropriate references to the national procurement legislation], such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. List only the applicable conditions required to ensure consistency with paragraph 5.4 of the Procurement Regulations. If no conditions apply, delete the phrase “and the following conditions”. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. Otherwise state “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables Otherwise state “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Specify for each Goods: [is not applicable/is applicable for those contracts identified in the Procurement Plan tables]; Works: [is not applicable/is applicable for those contracts identified in the Procurement Plan tables] Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations is Applicable. [Include this sentence only if the Bank has formally agreed to provide the Borrower with HEIS. Otherwise delete] Other Relevant Procurement Information. Provide any other relevant procurement information such as procedures for CDD components, Procurement in Situations of Urgent Need of Assistance or Capacity Constraints etc. PROCUREMENT Brazil : Amazon Sustainable Landscapes Project PLAN General Information Country: Brazil 2021-08-02 Bank’s Approval Date of the Original Procurement Plan: 2023-06-05 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P158000 GPN Date: Project Name: Amazon Sustainable Landscapes Project Loan / Credit No: TF / A6057, TF / B6898 Getulio Vargas Foundation Executing Agency(ies): WORKS Activity Reference No. / Procureme Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH Ri Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method nt Docume ount (US$ and Recommendation Signed Contract o. h cess (Y/N) sk atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion nt Type ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BR-FGV-242223-GO-RFQ / A quisicao de GPS para utilizac ao pelos monitores de campo durante atividade de monitor Component 2: Integrated La Request for Quota Single Stage - One E TF / A6057 Post Open - National 0.00 Canceled 2022-03-05 2022-04-30 2022-10-27 amento das parcelas, para re ndscape Management tions nvelope alizar pesquisa do potencial produtivo para cadeia produt iva dos oleos vegetais em flo restas nativa no medio jurua BR-FGV-242262-GO-RFQ / A quisicao de cadeiras (300 uni dades) para realizar assembl Component 2: Integrated La Request for Quota Single Stage - One E eias anuais das organizações TF / A6057 Post Open - National 0.00 Canceled 2022-03-05 2022-04-30 2022-10-27 ndscape Management tions nvelope de base que atuam no TMJ p ara socializar e construir estr ategias de implementaçao d o Sitio Ramsar BR-FGV-242224-GO-RFQ / A quisicao de caixa de som (4 unidades)para realizar assem Component 2: Integrated La Request for Quota Single Stage - One E bleias anuais das organizaçõ TF / A6057 Post Open - National 0.00 Canceled 2022-03-05 2022-04-30 2022-10-27 ndscape Management tions nvelope es de base que atuam no TMJ para socializar e construir est rategias de implementaçao d o Sitio Ramsar BR-FGV-242251-GO-RFQ / A quisicao de microfone (5 uni dades) para realizar assembl Component 2: Integrated La Request for Quota Single Stage - One E eias anuais das organizações TF / A6057 Post Open - National 0.00 Canceled 2022-03-05 2022-04-30 2022-10-27 ndscape Management tions nvelope de base que atuam no TMJ p ara socializar e construir estr ategias de implementaçao d o Sitio Ramsar BR-FGV-253877-GO-RFQ / A quisicao de software para ras Component 4: Capacity Buil treabilidade do pirarucu: do l Request for Quota Single Stage - One E TF / A6057 ding, Cooperation and Projec Post Open - National 0.00 Canceled 2022-03-05 2022-04-30 2022-10-27 ago ate o consumidor, para C tions nvelope t Management onsolidaçao de processos de rastreabilidade do pirarucu d e manejo no TMJ BR-FGV-253900-GO-RFQ / C ompra de 250 mesinhas de s ecagem nas comunidades (c om transporte e instalação). Component 2: Integrated La Request for Quota Single Stage - One E TF / A6057 Post Open - National 0.00 Canceled 2022-03-05 2022-04-30 2022-10-27 Demanda visa estruturar uni ndscape Management tions nvelope dades de produção familiar p or intermédio do uso de mesi nhas de secagem de sement es oleaginosas. BR-FGV-357680-GO-RFQ / A quisicao de insumos (aliment acao para os participantes) p Component 1: Amazon Prote Request for Quota Single Stage - One E TF / B6898 Post Open - National 0.00 Signed 2023-04-14 2023-04-19 2023-04-30 ara realizacao de oficinas par cted Areas System tions nvelope a a regulamentacao da gesta o da RESEX (Unidade de Con servacao) BR-FGV-365052-GO-RFQ / A quisicao de alimentos para a poio a atividade de treiname Component 2: Integrated La Request for Quota Single Stage - One E Under Imple nto em boas praticas de mon TF / B6898 Post Open - National 0.00 2023-06-02 2023-06-04 2023-06-05 ndscape Management tions nvelope mentation itoramento de quelonios para 53 monitores de tabuleiro an tecedendo o inicio do periodo reprodutivo com duracao de 5 dias BR-FGV-365062-GO-RFQ / A quisicao de produtos de limp eza para apoio a atividade d e treinamento em boas prati Component 2: Integrated La Request for Quota Single Stage - One E Under Imple TF / B6898 Post Open - National 0.00 2023-06-02 2023-06-05 2023-06-05 cas de monitoramento de qu ndscape Management tions nvelope mentation elonios para 53 monitores de tabuleiro antecedendo o inici o do periodo reprodutivo co m duracao de 5 dias BR-FGV-365061-GO-RFQ / A quisicao de gasolina para ap oio a atividade de treinament Component 2: Integrated La Request for Quota Single Stage - One E Under Imple o em boas praticas de monit TF / B6898 Post Open - National 0.00 2023-06-02 2023-06-05 2023-06-05 ndscape Management tions nvelope mentation oramento de quelonios para 53 monitores de tabuleiro an tecedendo o inicio do periodo reprodutivo com duracao de 5 dias BR-FGV-365064-GO-RFQ / A quisicao de material de papel aria para apoio a atividade d e treinamento em boas prati Component 2: Integrated La Request for Quota Single Stage - One E Under Imple TF / B6898 Post Open - National 0.00 2023-06-02 2023-06-04 2023-06-05 cas de monitoramento de qu ndscape Management tions nvelope mentation elonios para 53 monitores de tabuleiro antecedendo o inici o do periodo reprodutivo co m duracao de 5 dias Page 1 BR-FGV-365065-GO-RFQ / A quisicao de 265 unidades de GLP (13kg) a serem entregue s a cada mes (53 por mes) d Component 2: Integrated La Request for Quota Single Stage - One E Pending Impl urante 5 meses para apoio a TF / B6898 Post Open - National 0.00 2023-06-02 2023-06-04 2023-06-05 ndscape Management tions nvelope ementation atividade de monitoramento de quelonios para 53 monitor es de tabuleiro antecedendo o inicio do periodo reprodutiv o com duracao de 5 meses BR-FGV-365063-GO-RFQ / A quisicao de diesel para apoio a atividade de treinamento e Component 2: Integrated La Request for Quota Single Stage - One E Under Imple m boas praticas de monitora TF / B6898 Post Open - National 0.00 2023-06-02 2023-06-05 2023-06-05 ndscape Management tions nvelope mentation mento de quelonios para 53 monitores de tabuleiro antec edendo o inicio do periodo re produtivo com duracao de 5 dias BR-FGV-365066-GO-RFQ / A quisicao de 265 cestas basic as a serem entregues a cada mes (53 por mes) durante ci Component 2: Integrated La Request for Quota Single Stage - One E Pending Impl nco meses para apoio a ativi TF / B6898 Post Open - National 0.00 2023-06-02 2023-06-04 2023-06-05 ndscape Management tions nvelope ementation dade de monitoramento de q uelonios para 53 monitores d e tabuleiro antecedendo o ini cio do período reprodutivo co m duracao de 5 meses BR-FGV-369632-GO-RFQ / C onfecção de banner e faixa p ara comunicação visual para Component 2: Integrated La Request for Quota Single Stage - One E Pending Impl o evento “Diálogos da Amazô TF / B6898 Post Open - National 0.00 2023-06-30 2023-07-05 2023-07-06 ndscape Management tions nvelope ementation nia Brasileira”, a ser realizad o no dia 10 de julho de 2023, no auditório do Parque da Ci ência do INPA, em Manaus. NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BR-FGV-242270-NC-RFQ / Co ntratacao de servico tecnico de analise laboratorial de am ostras, para pesquisar e estu Component 2: Integrated La Request for Quota Single Stage - One E dar o potencial de novas esp TF / A6057 Post Open - National 0.00 Canceled 2022-03-05 2022-04-30 2022-10-27 ndscape Management tions nvelope ecies da regiao, e estruturar o modelo de manejo e desen volvimento dos ativos, da ca deia produtiva dos óleos veg etais no medio jurua BR-FGV-242258-NC-RFP / Co ntratacao de servico tecnico de mapeamento de lagos, pa Component 3: Policies for Pr Request for Quota Single Stage - One E ra Zoneamento espacial e m TF / A6057 otection and Recovery of Na Post Open - National 0.00 Canceled 2022-03-05 2022-04-30 2022-10-27 tions nvelope apeamento dos lagos para in tive Vegetation clusao no acordo nos municí piod de Carauari, Itamarati e Jurua BR-FGV-367915-NC-RFQ / Co ntratação de serviço de orga nização de expedição imersiv a embarcada (fluvial) pelo M Component 2: Integrated La Request for Quota Single Stage - One E Pending Impl osaico de Áreas Protegidas d TF / B6898 Post Open - National 0.00 2023-06-24 2023-07-03 2023-07-23 ndscape Management tions nvelope ementation o Baixo Rio Negro, parte inte grante do evento "Diálogos d a Amazônia Brasileira" a ser r ealizada entre os dias 7 a 10 de julho de 2023. BR-FGV-368971-NC-RFQ / Co ntratação de serviços de apoi o à organização (translado, r Component 2: Integrated La Request for Quota Single Stage - One E Pending Impl ecepção e alimentação) do e TF / B6898 Post Open - National 0.00 2023-06-28 2023-07-05 2023-07-25 ndscape Management tions nvelope ementation vento “Diálogos da Amazônia Brasileira”, a ser realizado no s dias 6, 7, 10, 13 e 14 de jul ho de 2023. BR-FGV-368991-NC-RFQ / Co ntratação de serviço de forne cimento e locação equipame ntos de tradução simultânea Component 2: Integrated La Request for Quota Single Stage - One E Pending Impl (cabine, receptores multican TF / B6898 Post Open - National 0.00 2023-06-25 2023-07-05 2023-07-20 ndscape Management tions nvelope ementation al, controle de distribuição d e receptores), para o evento “Diálogos da Amazônia Brasil eira”, a ser realizado no dia 1 0 de julho de 2023. CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BR-FGV-246992-CS-LCS / Ela boração de Plano de Negócio s para apoiar o grupo de mul heres do Juruá. Demanda vis Component 2: Integrated La Least Cost Selecti TF / A6057 Post Open - National 0.00 Canceled 2022-02-28 2022-03-21 2022-05-04 2022-06-01 2022-07-01 2022-08-05 2022-09-09 2023-03-08 a apoiar e promover o desen ndscape Management on volvimento de novos produto s utilizando fibras vegetais lo cais para acesso a mercado l ocal e externo BR-FGV-253852-CS-LCS / Co ntratacao de parataxonomo para identificacao das especi es e ministrar curso de identi Component 4: Capacity Buil Least Cost Selecti ficacao e monitoramento em TF / A6057 ding, Cooperation and Projec Post Open - National 0.00 Canceled 2022-02-28 2022-03-21 2022-05-04 2022-06-01 2022-07-01 2022-08-05 2022-09-09 2023-03-08 on parcelas para realizar pesqui t Management sa do potencial produtivo par a cadeia produtiva dos oleos vegetais em florestas nativa no medio jurua Page 2 BR-FGV-253862-CS-LCS / Co ntratacao de parataxonomo para formaçao de parabotani Component 2: Integrated La Least Cost Selecti cos no local, para realizar pe TF / A6057 Post Open - National 0.00 Canceled 2022-02-28 2022-03-21 2022-05-04 2022-06-01 2022-07-01 2022-08-05 2022-09-09 2023-03-08 ndscape Management on squisa do potencial produtivo para cadeia produtiva dos ol eos vegetais em florestas nat iva no medio jurua BR-FGV-253886-CS-LCS / Co ntratacao de consultoria para avaliaçao dos resultados (5 Component 2: Integrated La Least Cost Selecti meses para execucao), para TF / A6057 Post Open - National 0.00 Canceled 2022-02-28 2022-03-21 2022-05-04 2022-06-01 2022-07-01 2022-08-05 2022-09-09 2023-03-08 ndscape Management on apoiar a continuidade e expa nsao das ações de monitora mento e proteçao das praias de desova de quelonios no ri o Jurua BR-FGV-254000-CS-LCS / Co ntratacao de consultoria para coordenar e executar as reun Component 3: Policies for Pr ioes com as comunidades de Least Cost Selecti TF / A6057 otection and Recovery of Na Post Open - National 0.00 Canceled 2022-02-28 2022-03-21 2022-05-04 2022-06-01 2022-07-01 2022-08-05 2022-09-09 2023-03-08 Jurua, Carauari e Itamarati, p on tive Vegetation ara Reuniao com 40 comunid ades rurais e colonias de pes cadores para consolidar o ac ordo de pesca nos município s BR-FGV-253887-CS-LCS / Co ntratacao de consultoria PJ p ara elaboracao de mapas e b Component 3: Policies for Pr Least Cost Selecti ancos de dados geograficos ( TF / A6057 otection and Recovery of Na Post Open - National 0.00 Canceled 2022-02-28 2022-03-21 2022-05-04 2022-06-01 2022-07-01 2022-08-05 2022-09-09 2023-03-08 on SIG), Zoneamento espacial e tive Vegetation mapeamento dos lagos para inclusao no acordo nos muni cípios de Carauari, Itamarati e Jurua BR-FGV-253874-CS-LCS / Co ntratacao de consultoria PJ p ara realizar moderacao de e Component 2: Integrated La Least Cost Selecti ventos, para realizar intercâ TF / A6057 Post Open - National 0.00 Canceled 2022-02-28 2022-03-21 2022-05-04 2022-06-01 2022-07-01 2022-08-05 2022-09-09 2023-03-08 ndscape Management on mbio para troca de experiênc ias na estruturação de arranj os de cadeias produtivas da sociobiodiversidade no TMJ BR-FGV-253885-CS-LCS / Co ntratacao de consultoria PF p ara realizar moderacao de e ventos, para realizar assembl Component 2: Integrated La Least Cost Selecti TF / A6057 Post Open - National 0.00 Canceled 2022-02-28 2022-03-21 2022-05-04 2022-06-01 2022-07-01 2022-08-05 2022-09-09 2023-03-08 eias anuais das organizações ndscape Management on de base que atuam no TMJ p ara socializar e construir estr ategias de implementaçao d o Sitio Ramsar BR-FGV-253884-CS-LCS / Co ntratacao de consultoria para Component 4: Capacity Buil a avaliaçao dos resultados d Least Cost Selecti TF / A6057 ding, Cooperation and Projec Post Open - National 0.00 Canceled 2022-02-28 2022-03-21 2022-05-04 2022-06-01 2022-07-01 2022-08-05 2022-09-09 2023-03-08 as atividades propostas, para on t Management Consolidaçao de processos d e rastreabilidade do pirarucu de manejo no TMJ BR-FGV-253868-CS-LCS / Co ntratacao de consultoria para elaboracao de plano de nego cios para pesquisar e estuda Component 2: Integrated La Least Cost Selecti r o potencial de novas especi TF / A6057 Post Open - National 0.00 Canceled 2022-02-28 2022-03-21 2022-05-04 2022-06-01 2022-07-01 2022-08-05 2022-09-09 2023-03-08 ndscape Management on es da regiao, e estruturar o modelo de manejo e desenvo lvimento dos ativos, da cadei a produtiva dos óleos vegetai s no medio jurua BR-FGV-242043-CS-LCS / Co nsultoria em coleta de dados Component 2: Integrated La Least Cost Selecti , sistematização, análise de d TF / A6057 Post Open - National 0.00 Canceled 2022-02-28 2022-03-21 2022-05-04 2022-06-01 2022-07-01 2022-08-05 2022-09-09 2023-03-08 ndscape Management on ados, redação de relatórios t écnicos e publicações cientifi cas. BR-FGV-306170-CS-CQS / Se rviço de consultoria para aud itoria financeira do projeto n o período definido no TDR D Component 4: Capacity Buil Least Cost Selecti Under Implement o 01 de janeiro - 31 de deze TF / B6898 ding, Cooperation and Projec Post Open - National 0.00 2022-07-27 2022-07-07 2022-08-17 2022-09-30 2023-05-19 2022-10-28 2022-11-27 2023-01-01 2023-02-05 2023-08-04 on ation mbro de 2022. Contrato que t Management pode ser renovável se o trab alho do auditor for satisfatóri o pela Fundação Getulio Varg as e pelo Banco Mundial. BR-FGV-317780-CS-CQS / Co ntratacao de consultoria para Component 4: Capacity Buil atuar como instituicao ancor Consultant Qualifi Pending Impleme TF / B6898 ding, Cooperation and Projec Post Open - National 0.00 2023-01-01 2023-01-22 2023-03-07 2023-04-06 2023-05-11 2023-11-07 a para apoiar a execucao das cation Selection ntation t Management atividades junto as areas dos sitios RAMSAR Rio Negro BR-FGV-317781-CS-CQS / Co ntratacao de consultoria para Component 4: Capacity Buil Consultant Qualifi Pending Impleme atuar como instituicao ancor TF / B6898 ding, Cooperation and Projec Post Open - National 0.00 2023-01-01 2023-01-22 2023-03-07 2023-04-06 2023-05-11 2023-11-07 cation Selection ntation a para apoiar a execucao das t Management atividades junto as areas dos sitios RAMSAR Jurua BR-FGV-317782-CS-LCS / Co ntratacao de consultoria para criacao de curso online e trei Component 4: Capacity Buil Least Cost Selecti Pending Impleme namento de capacitacao par TF / B6898 ding, Cooperation and Projec Post Open - National 0.00 2022-11-01 2022-11-22 2023-01-05 2023-02-02 2023-03-04 2023-04-08 2023-05-13 2023-11-09 on ntation a apoiar a implementação de t Management programas de conservacao, r ecuperacao e uso sustentáve l dos ecossistemas amazônic os. INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Actual Amount Invitation to Identifie Draft Negotiated Cont Component Review Type Method Contract Type Process Status Teams of Reference Signed Contract Contract Completion Description o. h (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BR-FGV-253896-CS-INDV / C ontratacao de consultor para realizacao de pesquisa de ca mpo. Demanda visa estudar Component 2: Integrated La Individual Consult o potencial de novas especie TF / A6057 Post Direct 0.00 Canceled 2022-02-28 2022-03-10 2022-03-31 2022-05-05 2022-11-01 ndscape Management ant Selection s da regiao, e estruturar o m odelo de manejo e desenvolv imento dos ativos, da cadeia produtiva dos oleos vegetais no medio jurua. Page 3 BR-FGV-253882-CS-INDV / C ontratacao de consultoria PF para realizar moderacao de e ventos, para 01 Encontro Re Component 2: Integrated La Individual Consult TF / A6057 Post Direct 0.00 Canceled 2022-02-28 2022-03-10 2022-03-31 2022-05-05 2022-11-01 gional para planejamento co ndscape Management ant Selection njunto, de ações integradas de desenvolvimento das cad eias produtivas da sociobiodi versidade no território Medio Jurua BR-FGV-253870-CS-CDS / Co ntrataçao de consultoria para desenvolv. de produtos (desi gn) utilizando fibras vegetais Component 2: Integrated La Individual Consult locais, para apoiar o grupo d TF / A6057 Post Open 0.00 Canceled 2022-02-28 2022-04-18 2022-05-09 2022-06-13 2022-12-10 ndscape Management ant Selection e mulheres do Jurua no dese nvolvimento de novos produt os utilizando fibras vegetais l ocais para acesso a mercado local e externo BR-FGV-253879-CS-CDS / Co ntratacao de coordenador loc al para acompanhamento do projeto de artesanato. Dema Component 2: Integrated La Individual Consult TF / A6057 Post Open 0.00 Canceled 2022-02-28 2022-04-18 2022-05-09 2022-06-13 2022-12-10 nda visa apoiar o grupo de m ndscape Management ant Selection ulheres do Jurua no desenvol vimento de novos produtos u tilizando fibras vegetais locai s para acesso a mercado loc al e externo. BR-FGV-253872-CS-CDS / Co ntrataçao de consultoria para desenvolv. de produtos (desi gn) utilizando fibras vegetais Component 2: Integrated La Individual Consult locais para apoiar o grupo de TF / A6057 Post Open 0.00 Canceled 2022-02-28 2022-04-18 2022-05-09 2022-06-13 2022-12-10 ndscape Management ant Selection mulheres do Jurua no desenv olvimento de novos produtos utilizando fibras vegetais loc ais para acesso a mercado lo cal e externos. BR-FGV-253878-CS-CDS / Co ntratacao de coordenador loc al para acompanhamento do projeto de artesanato, para a Component 2: Integrated La Individual Consult TF / A6057 Post Open 0.00 Canceled 2022-02-28 2022-04-18 2022-05-09 2022-06-13 2022-12-10 poiar o grupo de mulheres do ndscape Management ant Selection Jurua no desenvolvimento de novos produtos utilizando fib ras vegetais locais para aces so a mercado local e externo BR-FGV-242277-CS-LCS / Co ntratacao de consultor para elaborar Mapeamento partici pativo com os comunitarios d Component 2: Integrated La Individual Consult a regiao durante viagem de c TF / A6057 Post Open 0.00 Canceled 2022-02-28 2022-04-18 2022-05-09 2022-06-13 2022-12-10 ndscape Management ant Selection ampo. Demanda visa a realiz ação de pesquisa do potenci al produtivo para cadeia prod utiva dos oleos vegetais em f lorestas nativa no medio juru a BR-FGV-317776-CS-LCS / Co Component 4: Capacity Buil ntratacao de coordenador de Individual Consult Pending Impleme TF / B6898 ding, Cooperation and Projec Post Open - National 0.00 2022-10-01 2022-11-19 2022-12-10 2023-01-14 2023-07-13 integracao e monitoramento ant Selection ntation t Management das Fases 1 e 2 do ASL. Page 4 Procurement Plan National Roads and Airport Infrastructure Project (P122007) I. General 1. Bank’s approval Date of the procurement Plan Original: September 6, 2017 in Excel format 2. Date of General Procurement Notice: 3. Period covered by this procurement plan: The procurement period of project covered from year 2015 to 2018 II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Procurement Method Prior Review Comments Threshold US$ 1. ICB and LIB (Goods and Non- Above US$ 500,000 All Consultant Services) 2. NCB (Goods) Above US$ 50,000 None 3. ICB (Works) Above US$ 5 million All 4. NCB (Works) Above US$ 250,000 None 2. Prequalification. Not applicable. 3. Reference to (if any) Project Operational/Procurement Manual: Project Implementation Manual for World Bank Loan Project P122007 04/10/2012 issued by AASANA III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Comments Threshold 1. Competitive Methods (Firms) Above US$ 500,000 2. Single Source (Firms) Above US$ 500,000 3. Individual Above US$ 200,000 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_200,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. PROCUREMENT Bolivia : National Roads and Airport Infrastructure Project PLAN General Information Country: Bolivia 2022-05-06 Bank’s Approval Date of the Original Procurement Plan: 2023-06-06 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P122007 GPN Date: Project Name: National Roads and Airport Infrastructure Project Loan / Credit No: IDA / 49230 Air Navigation and Bolivian Airports Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned NAABOLPMARLPN012022 / C ONSTRUCCION ESTABILIZACI National Procure ÓN DE TERRENO- ACCESO SE ment Document - Improving the Rurrenabaque Single Stage - One E 2022-12-1 I VIAS DE COMUNICACION P IDA / 49230 Post Request for Bids Open - National 1 Envelope proce 957,828.00 925,090.99 Signed 2022-05-31 2022-06-03 2022-06-08 2022-06-29 2022-07-04 2022-07-07 2022-07-05 2022-08-03 2022-08-06 Airport nvelope 5 AVIMENTO RIGIDO H25 ACC ss (Non Bank-SPD ESO SEI VIAS DE COMUNIC ) ACIÓN CONCLUSION CERCO PERIMETRAL Y CAMINO PERI METRAL NAABOLPMARLPN022022 / C National Procure ONSTRUCCION ESTABILIZACI ment Document - Improving the Rurrenabaque Single Stage - One E 1,019,572.7 2022-11-2 ÓN DE TERRENO - CALLE DE IDA / 49230 Post Request for Bids Open - National 1 Envelope proce 1,078,956.00 Signed 2022-05-31 2022-06-06 2022-06-07 2022-06-24 2022-07-06 2022-06-30 2022-07-07 2022-07-28 2022-07-28 Airport nvelope 3 2 RODAJE PAVIMENTO RIGIDO ss (Non Bank-SPD H25 CALLE DE RODAJE DREN ) AJE PLUVIAL National Procure NAABOLPMARLPN032022 / C ment Document - ONSTRUCCION: ESTABILIZAC Improving the Rurrenabaque Single Stage - One E 2022-11-2 IDA / 49230 Post Request for Bids Open - National 1 Envelope proce 846,958.00 803,985.21 Signed 2022-05-31 2022-06-07 2022-06-09 2022-06-28 2022-07-07 2022-07-05 2022-07-11 2022-08-02 2022-07-28 IÓN DE TERRENO - PLATAFOR Airport nvelope 4 ss (Non Bank-SPD MA PAVIMENTO RIGIDO H25 ) PLATAFORMA GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NAABOLPMARCP092022 / AD QUISICION EQUIPOS DE COM Improving the Rurrenabaque Request for Quota Single Stage - One E IDA / 49230 Post Open - National 29,155.00 0.00 Canceled 2022-06-05 2022-06-29 2022-08-25 PUTACION PARA LAS OFICINA Airport tions nvelope S ADMINISTRATIVAS PMAR NAABOLPMARCP102022 / AD Improving the Rurrenabaque Request for Quota Single Stage - One E QUISICION DE MUEBLES PAR IDA / 49230 Post Open - National 21,865.00 9,527.96 Completed 2022-06-05 2022-06-30 2022-07-05 2022-08-04 2022-07-20 Airport tions nvelope A OFICINAS ADMINISTRATIVA S PMAR NAABOLPMARCP012022 / AD Improving the Rurrenabaque Request for Quota Single Stage - One E QUISICION DE UN GRUPO ELE IDA / 49230 Post Open - National 43,730.00 41,905.52 Completed 2022-05-21 2022-06-15 2022-07-16 2022-07-18 2022-08-05 2022-08-15 Airport tions nvelope CTROGENO DE 150 KVA NAABOLPMARCP022022 / AD Improving the Rurrenabaque Request for Quota Single Stage - One E QUISICION DE UNA MAQUINA IDA / 49230 Post Open - National 25,510.00 21,267.30 Signed 2022-05-28 2022-07-21 2022-08-02 2022-07-27 Airport tions nvelope FRANJADORA NAABOLPMARCP032022 / AD Improving the Rurrenabaque Request for Quota Single Stage - One E QUISICION DE UNA ESCALER IDA / 49230 Post Open - National 32,466.00 0.00 Canceled 2022-06-04 2022-07-15 2022-08-26 Airport tions nvelope A TIPO TIJERA DE 14 P NAABOLPMARCP082022 / AD Improving the Rurrenabaque Request for Quota Single Stage - One E QUISICION Y EQUIPAMIENTO IDA / 49230 Post Open - National 23,785.00 0.00 Canceled 2022-06-05 2022-07-15 2022-08-31 Airport tions nvelope MOBILIARIO UNIDAD MEDICA NAABOLPMARLPN042022 / A DQUISICION DE EQUIPOS PAR Improving the Rurrenabaque Single Stage - One E IDA / 49230 Post Request for Bids Open - National 124,113.00 0.00 Canceled 2022-05-26 2022-09-26 2022-05-31 2022-07-12 2022-07-12 2022-08-09 2022-10-13 A EL SERVICIO DE SALVAMEN Airport nvelope TO Y EXTINCION DE INCENDI OS NAABOLPMARLPN052022 / A Improving the Rurrenabaque Single Stage - One E DQUISICION E INSTALACION IDA / 49230 Post Request for Bids Open - National 348,623.00 0.00 Completed 2022-05-26 2022-10-04 2022-05-31 2022-06-17 2022-11-03 2022-06-22 2022-11-10 2022-07-14 2022-09-22 2023-03-01 Airport nvelope PARA EL EQUIPAMIENTO AVS EC NAABOLPMARLPN092022 / A Improving the Rurrenabaque Single Stage - One E DQUISICION DE UNA AMBULA IDA / 49230 Post Request for Bids Open - National 144,314.00 0.00 Completed 2022-05-27 2022-06-07 2022-06-01 2022-06-15 2022-07-05 2022-06-22 2022-07-08 2022-07-14 2022-09-14 2022-09-28 Airport nvelope NCIA EQUIPADA NAABOLPMARLPN102022 / A Improving the Rurrenabaque Single Stage - One E DQUISICION DE UNA MINIPLA IDA / 49230 Post Request for Bids Open - National 106,530.00 0.00 Completed 2022-05-27 2022-06-07 2022-06-01 2022-06-21 2022-07-05 2022-06-28 2022-07-06 2022-07-25 2022-08-24 2022-10-01 Airport nvelope NTA DE ASFALTO NAABOLPMARLPN112022 / A Improving the Rurrenabaque Single Stage - One E DQUISICIÓN DE EQUIPO DE A IDA / 49230 Post Request for Bids Open - National 269,712.00 0.00 Canceled 2022-05-27 2022-06-01 2022-07-13 2022-08-12 2022-09-16 2022-12-30 Airport nvelope USCULTACIÓN DE PAVIMENT OS NAABOLPMARLPN122022 / A DQUISICION DE UN EQUIPO D Improving the Rurrenabaque Single Stage - One E IDA / 49230 Post Request for Bids Open - National 110,000.00 0.00 Canceled 2022-05-27 2022-09-28 2022-06-01 2022-07-13 2022-08-12 2022-09-16 2022-11-23 E TEXTURIZACION DE HORMI Airport nvelope GON Y ASFALTO (GRANULLA DORA) NAABOLPMARCP062022 / AD Improving the Rurrenabaque Request for Quota Single Stage - One E QUISICION DE UNA CORTADO IDA / 49230 Post Open - National 7,457.00 6,684.92 Completed 2022-06-05 2022-07-31 2022-07-14 2022-08-30 2022-07-29 Airport tions nvelope RA DE ASFALTO Y UNA COMP ACTADORA NAABOLPMARLPI022022 / A Improving the Rurrenabaque Open - Internationa Single Stage - One E DQUISICION E INSTALACION IDA / 49230 Post Request for Bids 1,333,000.00 0.00 Canceled 2022-06-10 2022-09-08 2022-06-20 2022-09-14 2022-08-01 2022-08-12 2022-09-20 2023-01-20 Airport l nvelope SISTEMA DE ILUMINACION DE PISTA NAABOLPMARLPI032022 / A Improving the Rurrenabaque Open - Internationa Single Stage - One E DQUISICION Y EQUIPAMIENT IDA / 49230 Post Request for Bids 655,172.00 0.00 Signed 2022-06-09 2022-07-26 2022-06-16 2022-09-09 2022-07-29 2022-10-03 2022-08-25 2022-10-10 2022-09-29 2023-01-27 Airport l nvelope O METEOROLOGICO (SISTEM A AWOS III) BO-NAABOL-312879-GO-RFQ Improving the Rurrenabaque Request for Quota Single Stage - One E / ADQUISICIÓN DE UNA PLAT IDA / 49230 Post Open - National 32,466.00 0.00 Signed 2022-09-30 2022-11-05 2022-12-05 Airport tions nvelope AFORMA TIJERA ELÉCTRICA Page 1 BO-NAABOL-319326-GO-RFQ / ADQUISICIÓN DE EQUIPOS Improving the Rurrenabaque Request for Quota Single Stage - One E IDA / 49230 Post Limited 29,155.00 0.00 Signed 2022-10-11 2022-10-11 2022-10-30 2022-11-29 DE COMPUTACIÓN PARA LAS Airport tions nvelope OFICINAS DEL PMAR NAABOLPMARCP042022 / AD Improving the Rurrenabaque Request for Quota Single Stage - One E IDA / 49230 Post Open - National 40,000.00 0.00 Canceled 2022-05-31 2022-07-07 2022-08-17 QUISICION DE UN TRACTOR S Airport tions nvelope EGADOR BO-NAABOL-336224-GO-RFP Improving the Rurrenabaque Single Stage - One E / ADQUISICIÓN DE EQUIPO D IDA / 49230 Post Request for Bids Open - National 180,141.00 0.00 Signed 2023-02-05 2023-02-02 2023-02-07 2023-03-09 2023-03-09 2023-03-14 2023-03-15 2023-03-31 2023-06-29 Airport nvelope E AUSCULTACIÓN DE PAVIME NTOS NAABOLPMARLPN062022 / A DQUISICION E INSTALACION Improving the Rurrenabaque Single Stage - One E IDA / 49230 Post Request for Bids Open - National 261,465.00 0.00 Canceled 2022-05-26 2022-08-29 2022-05-31 2022-07-12 2022-10-06 2022-07-15 2022-07-25 2022-09-23 DE CINTAS TRANSPORTADOR Airport nvelope AS DE EQUIPAJES NAABOLPMARLPN082022 / A Improving the Rurrenabaque Single Stage - One E DQUISICION Y EQUIPAMIENT IDA / 49230 Post Request for Bids Open - National 143,525.00 0.00 Canceled 2022-05-27 2022-10-11 2022-06-01 2022-07-13 2022-10-31 2022-08-12 2022-08-31 2022-10-13 Airport nvelope O DE MOBILIARIO Y EQUIPOS DE FACILITACION BO-NAABOL-336540-GO-RFP Improving the Rurrenabaque Single Stage - One E / MINICARGADOR CON DESB IDA / 49230 Post Request for Bids Open - National 92,718.00 0.00 Signed 2023-02-01 2023-03-08 2023-02-03 2023-03-05 2023-03-31 2023-03-10 2023-04-04 2023-03-17 2023-03-29 Airport nvelope ROZADOR BO-NAABOL-338156-GO-RFB / ADQUISICION E INSTALACIO Improving the Rurrenabaque Single Stage - One E IDA / 49230 Post Request for Bids Open - National 495,627.00 0.00 Signed 2023-01-27 2023-01-19 2023-01-30 2023-03-01 2023-03-01 2023-03-06 2023-03-07 2023-03-21 2023-07-28 N DE CINTAS TRANSPORTAD Airport nvelope ORAS DE EQUIPAJES BO-NAABOL-340771-GO-RFB / ADQUISICIÓN Y EQUIPAMIE Improving the Rurrenabaque Single Stage - One E IDA / 49230 Post Request for Bids Open - National 163,680.32 0.00 Signed 2023-02-13 2023-02-06 2023-02-15 2023-03-17 2023-03-10 2023-03-24 2023-03-17 2023-04-07 2023-07-06 NTO DE MOBILIARIO Y EQUIP Airport nvelope OS DE FACILITACIÓN BO-NAABOL-336226-GO-RFP Improving the Rurrenabaque Request for Quota Single Stage - One E / ADQUISICIÓN DE 2 ITEMS P IDA / 49230 Post Limited 9,795.00 0.00 Canceled 2023-03-13 2023-04-14 2023-07-13 Airport tions nvelope ARA EQUIPO AVSEC BO-NAABOL-336210-GO-RFP / ADQUISICIÓN DE EQUIPOS P Improving the Rurrenabaque Single Stage - One E IDA / 49230 Post Request for Bids Open - National 64,528.00 0.00 Canceled 2023-02-12 2023-02-14 2023-03-16 2023-03-21 2023-04-07 2023-07-06 ARA EL SERVICIO DE SALVAM Airport nvelope ENTO Y EXTINCIÓN DE INCEN DIOS BO-NAABOL-350649-GO-RFB Improving the Rurrenabaque Single Stage - One E / ADQUISICIÓN DE UN EQUIP IDA / 49230 Post Request for Bids Open - National 134,306.00 0.00 Signed 2023-03-24 2023-03-23 2023-03-27 2023-04-10 2023-04-14 2023-04-17 2023-04-18 2023-04-28 2023-07-27 Airport nvelope O DE TEXTURIZACIÓN DE PA VIMENTOS NAABOLPMARLPI012022 / A Improving the Rurrenabaque Open - Internationa Single Stage - One E DQUISICION Y EQUIPAMIENT IDA / 49230 Post Request for Bids 963,662.00 0.00 Canceled 2022-06-10 2022-07-25 2022-06-20 2022-09-09 2022-08-02 2022-10-03 2022-09-01 2022-10-13 2022-10-06 2023-01-31 Airport l nvelope O DE COMUNICACIONES NAABOLPMARLPI012022-2 / Improving the Rurrenabaque Direct - Internation Adquisición y Equipamiento d IDA / 49230 Post Direct Selection 917,931.00 0.00 Signed 2022-12-07 2022-12-14 2022-12-14 2022-12-14 2023-01-05 2023-08-02 Airport al e Comunicaciones BO-NAABOL-358056-GO-RFQ Improving the Rurrenabaque Request for Quota Single Stage - One E / ADQUISICIÓN DE UNA CAMI IDA / 49230 Post Open - National 39,900.00 0.00 Canceled 2023-05-07 2023-06-18 2023-07-18 Airport tions nvelope ONETA - CAPACIDAD 1000 K G NAABOLPMARCP072022 / AD Improving the Rurrenabaque Request for Quota Single Stage - One E IDA / 49230 Post Open - National 18,000.00 0.00 Canceled 2022-06-05 2022-08-16 2022-10-13 QUISICION DE UN CUADRATR Airport tions nvelope ACK BO-NAABOL-361174-GO-RFQ Improving the Rurrenabaque Request for Quota Single Stage - One E / ADQUISICIÓN DE UN SISTE IDA / 49230 Post Open - National 83,870.00 0.00 Signed 2023-05-19 2023-06-13 2023-08-02 Airport tions nvelope MA DE PERIFONEO BO-NAABOL-364688-GO-RFQ Improving the Rurrenabaque Request for Quota Single Stage - One E Under Imple / ADQUISICION DE UN GENER IDA / 49230 Post Open - National 51,000.00 0.00 2023-06-06 2023-06-12 2023-07-12 2023-07-27 Airport tions nvelope mentation ADOR MOVIL DE 115 KV NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BO-NAABOL-315059-NC-RFQ Improving the Rurrenabaque Request for Quota Single Stage - One E / SERVICIOS DE LABORATORI IDA / 49230 Post Open - National 13,927.00 0.00 Canceled 2022-09-16 2022-10-22 2023-03-21 Airport tions nvelope O DE SUELOS Y HORMIGONE S BO-NAABOL-315059-NC-RFQ Improving the Rurrenabaque Request for Quota Single Stage - One E -. / SERVICIOS DE LABORATO IDA / 49230 Post Open - National 23,325.00 0.00 Signed 2022-09-20 2022-10-22 2023-03-21 Airport tions nvelope RIO DE SUELOS Y HORMIGON ES BO-NAABOL-315044-NC-RFQ Improving the Rurrenabaque Request for Quota Single Stage - One E / SERVICIO DE MONITOREO Y IDA / 49230 Post Open - National 5,831.00 0.00 Signed 2022-09-16 2022-10-22 2023-03-21 Airport tions nvelope ANÁLISIS AMBIENTALES CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NAABOLPMARSBCC012022 / SUPERVISION OBRAS COMPL Improving the Rurrenabaque Quality And Cost- IDA / 49230 Post Open - National 170,500.00 0.00 Canceled 2022-05-24 2022-06-08 2022-06-14 2022-07-28 2022-08-25 2022-09-09 2022-09-20 2022-10-05 2023-02-15 EMENTARIAS MEJORAMIENT Airport Based Selection O AEROPUERTO DE RURREN ABAQUE INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 2 NAABOLPMARCD012022 / C ONSULTOR INDIVIDUAL DE LI Improving the Rurrenabaque IDA / 49230 Post Direct Selection Direct 16,562.00 11,687.72 Signed 2022-05-11 2022-05-10 2022-05-12 2022-05-16 2022-05-18 2022-06-11 2022-08-07 NEA ESPECIALISTA ADMINIST Airport RATIVO-FINANCIERO NAABOLPMARCD022022 / C Improving the Rurrenabaque ONSULTOR INDIVIDUAL DE LI IDA / 49230 Post Direct Selection Direct 16,562.00 3,685.55 Completed 2022-05-12 2022-05-10 2022-05-18 2022-05-16 2022-05-22 2022-06-11 2022-08-11 2022-08-16 Airport NEA ESPECIALISTA EN ADQUI SICIONES NAABOLPMARCD032022 / C Improving the Rurrenabaque ONSULTOR INDIVIDUAL DE LI IDA / 49230 Post Direct Selection Direct 16,562.00 10,811.62 Signed 2022-05-12 2022-05-10 2022-05-18 2022-05-31 2022-05-22 2022-06-27 2022-08-11 Airport NEA FISCAL EN EQUIPAMIENT O NAABOLPMARCD042022 / C Improving the Rurrenabaque ONSULTOR INDIVIDUAL DE LI IDA / 49230 Post Direct Selection Direct 10,067.00 7,040.14 Signed 2022-05-12 2022-05-10 2022-05-16 2022-05-16 2022-05-22 2022-06-13 2022-08-11 Airport NEA ASISTENTE DE ADQUISIC IONES NAABOLPMARCD052022 / C Improving the Rurrenabaque ONSULTOR INDIVIDUAL DE LI IDA / 49230 Post Direct Selection Direct 16,562.00 3,245.50 Signed 2022-05-12 2022-05-10 2022-05-16 2022-05-31 2022-05-22 2022-06-20 2022-08-11 Airport NEA ESPECIALISTA AMBIENTA L NAABOLPMARCD062022 / A UDITORIA DE LOS ESTADOS F INANCIEROS GESTION 2021, Improving the Rurrenabaque 2022 HASTA EL CIERRE DEL IDA / 49230 Post Direct Selection Direct 17,492.00 27,597.39 Signed 2022-05-11 2022-05-10 2022-05-15 2022-05-16 2022-05-24 2022-06-06 2022-06-27 Airport PROYECTO MEJORAMIENTO D EL AEROPUERTO DE RURREN ABAQUE FINANCIADO POR EL BANCO MUNDIAL NAABOLPMARCD0072022 / Improving the Rurrenabaque CONSULTOR INDIVIDUAL DE IDA / 49230 Post Direct Selection Direct 16,562.00 3,355.41 Completed 2022-05-25 2022-05-23 2022-06-02 2022-05-31 2022-06-17 2022-06-17 2022-08-07 2022-08-15 Airport LINEA ESPECIALISTA EN ADQ UISICIONES II BO-NAABOL-310963-CS-IND Improving the Rurrenabaque Individual Consult V / CONSULTOR INDIVIDUAL IDA / 49230 Prior Limited 17,970.00 0.00 Signed 2022-08-29 2022-08-29 2022-08-31 2022-08-29 2022-09-15 2022-09-13 2022-09-30 2023-03-14 Airport ant Selection DE LINEA ESPECIALISTA EN A DQUISICIONES BO-NAABOL-310970-CS-IND Improving the Rurrenabaque Individual Consult IDA / 49230 Post Limited 15,700.00 0.00 Signed 2022-08-29 2022-08-29 2022-08-31 2022-09-07 2022-09-15 2022-09-13 2022-09-30 2023-03-14 V / GERENTE DE SUPERVISIO Airport ant Selection N BO-NAABOL-311007-CS-IND Improving the Rurrenabaque Individual Consult V / SERVICIO DE CONSULTOR IDA / 49230 Post Limited 11,000.00 0.00 Signed 2022-08-29 2022-09-02 2022-08-31 2022-10-11 2022-09-15 2022-09-13 2022-09-30 2023-03-14 Airport ant Selection ÍA INDIVIDUAL PARA TRABAJO TOPOGRÁFICO BO-NAABOL-310975-CS-IND Improving the Rurrenabaque Individual Consult V / CONSULTOR EN BIOLOGÍA IDA / 49230 Post Limited 14,900.00 0.00 Signed 2022-08-29 2022-08-29 2022-08-31 2022-09-07 2022-09-15 2022-09-14 2022-09-30 2023-03-14 Airport ant Selection Y CONSERVACIÓN DE FLORA Y FAUNA BO-NAABOL-310974-CS-IND Improving the Rurrenabaque Individual Consult IDA / 49230 Post Limited 14,900.00 0.00 Signed 2022-08-29 2022-08-29 2022-08-31 2022-09-07 2022-09-15 2022-09-14 2022-09-30 2023-03-14 V / INGENIERO AMBIENTAL Airport ant Selection BO-NAABOL-311008-CS-IND Improving the Rurrenabaque Individual Consult IDA / 49230 Post Limited 11,000.00 0.00 Signed 2022-08-29 2022-08-29 2022-08-31 2022-09-07 2022-09-15 2022-09-15 2022-09-30 2023-03-14 V / APOYO TÉCNICO A SUPER Airport ant Selection VISIÓN NAABOL/PMAR/CI/001/2021 / Improving the Rurrenabaque Individual Consult IDA / 49230 Post Open - National 14,374.00 0.00 Signed 2021-12-01 2021-02-08 2021-12-13 2021-08-29 2021-12-14 2021-10-04 2021-12-31 2022-08-07 COORDINADOR DEL PROYEC Airport ant Selection TO NAABOL/PMAR/CD-CIL-004/2 Improving the Rurrenabaque Individual Consult IDA / 49230 Post Direct - National 17,955.00 0.00 Signed 2021-12-01 2020-03-15 2021-12-11 2020-03-16 2021-12-16 2020-03-24 2021-12-31 2022-08-07 019 / FISCAL DE OBRA - PMA Airport ant Selection R BO-NAABOL-327951-CS-CDS Improving the Rurrenabaque Individual Consult / CONSULTOR INDIVIDUAL DE IDA / 49230 Prior Direct - National 12,500.00 0.00 Signed 2022-11-28 2022-11-28 2022-12-02 2022-12-01 2022-12-04 2022-12-15 2022-12-11 2023-05-25 Airport ant Selection LINEA ESPECIALISTA EN ADQ UISICIONES BO-NAABOL-332062-CS-CDS / CONSULTORIA POR PRODU Improving the Rurrenabaque CTO RELEVAMIENTO DE BIOD IDA / 49230 Post Direct Selection Direct - National 35,781.00 0.00 Signed 2022-12-27 2023-01-17 2023-01-16 2023-01-19 2023-02-14 2023-04-18 Airport IVERSIDAD Y MIGRACION ASI STIDA DE FAUNA SILVESTRE NAABOLPMARCDEX062022 / CONSULTOR INDIVIDUAL DE Improving the Rurrenabaque Individual Consult Under Implement IDA / 49230 Post Direct - National 13,251.00 0.00 2022-11-16 2023-04-13 2022-11-22 2022-11-25 2022-12-01 2023-07-31 LINEA ESPECIALISTA ADMINIS Airport ant Selection ation TRATIVO - FINANCIERO NAABOLPMARCDEX072022 / Improving the Rurrenabaque Individual Consult Under Implement CONSULTOR INDIVIDUAL DE IDA / 49230 Post Direct - National 13,251.00 0.00 2022-11-16 2023-04-13 2022-11-22 2022-11-25 2022-12-01 2023-07-31 Airport ant Selection ation LINEA FISCAL EN EQUIPAMIE NTO NAABOLPMARCDEX082022 / Improving the Rurrenabaque Individual Consult Under Implement CONSULTOR INDIVIDUAL DE IDA / 49230 Post Direct - National 8,054.00 0.00 2022-11-16 2023-03-09 2022-11-22 2022-11-25 2022-12-01 2023-07-31 Airport ant Selection ation LINEA ASISTENTE DE ADQUIS ICIONES NAABOLPMARCDEX092022 / Improving the Rurrenabaque Individual Consult Under Implement CONSULTOR INDIVIDUAL DE IDA / 49230 Post Direct - National 13,251.00 0.00 2022-11-16 2023-04-13 2022-11-22 2022-11-25 2022-12-01 2023-07-31 Airport ant Selection ation LINEA ESPECIALISTA AMBIEN TAL BO-NAABOL-336197-CS-IND Improving the Rurrenabaque Individual Consult V / ESPECIALISTA EN CALIDA IDA / 49230 Post Limited 9,938.00 0.00 Canceled 2023-01-25 2023-01-24 2023-01-26 2023-02-02 2023-02-07 2023-07-31 Airport ant Selection D DE LOS PROCESOS BO-NAABOL-315048-CS-IND Improving the Rurrenabaque Individual Consult V / CONSULTORÍA INDIVIDUA IDA / 49230 Post Limited 14,900.00 0.00 Canceled 2022-09-29 2022-10-01 2022-10-11 2022-10-21 2023-03-20 Airport ant Selection L INGENIERO EN PAVIMENTO S Y GEOTECNIA BO-NAABOL-362105-CS-IND Improving the Rurrenabaque Individual Consult V / CONSULTOR INDIVIDUAL IDA / 49230 Prior Direct - National 4,252.00 0.00 Signed 2023-05-18 2023-05-17 2023-05-20 2023-05-17 2023-05-22 2023-05-25 2023-05-26 2023-06-10 2023-08-02 Airport ant Selection DE LÍNEA ESPECIALISTA EN A DQUISICIONES BO-NAABOL-364653-CS-IND Improving the Rurrenabaque Individual Consult Under Implement V / Especialista en Calidad de IDA / 49230 Post Direct - National 3,313.00 0.00 2023-06-05 2023-06-06 2023-06-07 2023-06-07 2023-06-08 2023-06-12 2023-08-02 Airport ant Selection ation los Procesos BO-NAABOL-365456-CS-IND V / Consultor Individual profe Improving the Rurrenabaque Individual Consult Under Implement IDA / 49230 Post Direct - National 3,000.00 0.00 2023-06-05 2023-06-06 2023-06-07 2023-06-07 2023-06-12 2023-08-02 sional apoyo técnico en gesti Airport ant Selection ation ón y calidad de documentos de obra Page 3 BO-NAABOL-365457-CS-IND V / Consultor Individual profe Improving the Rurrenabaque Individual Consult Under Implement IDA / 49230 Post Direct - National 3,000.00 0.00 2023-06-05 2023-06-06 2023-06-07 2023-06-07 2023-06-12 2023-08-02 sional apoyo técnico en gesti Airport ant Selection ation ón y calidad de documentos de obra BO-NAABOL-365458-CS-IND V / Consultor Individual profe Improving the Rurrenabaque Individual Consult Under Implement IDA / 49230 Post Direct - National 3,000.00 0.00 2023-06-05 2023-06-06 2023-06-07 2023-06-07 2023-06-12 2023-08-02 sional apoyo técnico en gesti Airport ant Selection ation ón y calidad de documentos de obra BO-NAABOL-365455-CS-IND Improving the Rurrenabaque Individual Consult Pending Impleme V / Consultor Individual Profe IDA / 49230 Post Direct - National 3,000.00 0.00 2023-06-09 2023-06-11 2023-06-11 2023-06-15 2023-08-02 Airport ant Selection ntation sional Apoyo en Administraci ón y Finanzas Page 4 PROCUREMENT PLAN (Textual Part) Project information: Ethiopia, Urban Productive Safety Net and Jobs Project (P169943) Project Implementation agency: Ministry of Labor and Social Affairs (MoLSA), Ministry of Urban Development and Construction (MoUDC), Urban Job Creation and Food Security Agency (UJCFSA) Date of the Procurement Plan: November 2020. Period covered by this Procurement Plan: December 2020 to December 2021. Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016 revised August 2018) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in Section 33(1)(a) from page 35-48 of the Proclamation Number 649/2009 of the Ethiopian Federal Government Procurement and Property Administration Proclamation, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. • Open Advertising of the procurement opportunity at the national level; • The procurement is open to eligible firms from any country; • The request for bids/Proposal documents shall require that bidders/proposers submitting Bids/Proposal present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of and compliance with the Bank’s Anti-Corruption Guidelines, including without limitation the bank’s right to sanction and the Bank’s inspection and audit right; • Contracts with an appropriate allocation of responsibilities, risks and liabilities; • Application of Standstill period and Publication of contract award information; • Maintenance of records of the procurement process; and • The Bank has the right to review procurement documentation and activities. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. “Not Applicable” Procurement of Second-Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: Is applicable for those contracts identified in the Procurement Plan; Works: Is applicable for those contracts identified in the Procurement Plan. Other Relevant Procurement Information. None PROCUREMENT Ethiopia : Urban Productive Safety Net and Jobs Project PLAN General Information Country: Ethiopia 2022-08-01 Bank’s Approval Date of the Original Procurement Plan: 2023-06-06 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P169943 GPN Date: 2020-12-18 Project Name: Urban Productive Safety Net and Jobs Project Loan / Credit No: IDA / D7320 Ministry of Urban Development and Infrastructure Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned ET-HAWASSA-347872-CW-RF Request for Quota Foster Urban Youth Employ Request for Quota Single Stage - One E Pending Imp 2023-07-1 Q / Refurbishment of Menahe IDA / D7320 Post Limited tions (Non Bank-S 65,000.00 0.00 2023-03-16 2023-04-14 ment tions nvelope lementation 3 rya OSSC in Hawassa by com PD) ponent 2.2 ET-HARER-347873-CW-RFQ / Request for Quota Foster Urban Youth Employ Request for Quota Single Stage - One E Pending Imp 2023-06-1 Refurbishment of Aboker OS IDA / D7320 Post Limited tions (Non Bank-S 49,000.00 0.00 2023-03-16 2023-04-14 ment tions nvelope lementation 3 SC in Harar city by compone PD) nt 2.2 GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ET-MOUDI-300547-GO-RFQ / Expand the Urban Productiv Procurement of 10 pcs of lapt Request for Quota Single Stage - One E Pending Impl IDA / D7320 e Safety Net to Improve the Post Limited 17,695.00 0.00 2022-06-29 2022-08-10 2022-09-09 op computer for Ethiopia refu tions nvelope ementation Urban Environment gees and returnees service ET-HAWASSA-325903-GO-DI Expand the Urban Productiv Under Imple R / Procurement of Cement f IDA / D7320 e Safety Net to Improve the Post Direct Selection Direct - National 207,700.00 0.00 2022-11-22 2023-04-10 2022-11-26 2022-12-26 2023-02-24 mentation or Hawassa City Urban Environment ET-HAWASSA-325907-GO-RF Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl Q / Procurement of Safety Ma IDA / D7320 e Safety Net to Improve the Post Limited 46,035.00 0.00 2022-11-27 2022-12-27 2023-02-25 tions nvelope ementation terials for Hawassa City Urban Environment ET-HAWASA-325909-GO-RFQ Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl / Procurement of Angle Iron, IDA / D7320 e Safety Net to Improve the Post Limited 31,730.00 0.00 2022-11-27 2022-12-26 2023-01-25 tions nvelope ementation RHS and reinforced Bar Urban Environment ET-HAWASA-325918-GO-RFQ Institutional Strengthening, Request for Quota Single Stage - One E Pending Impl / Procurement of Local Const IDA / D7320 Project Management and Mo Post Limited 66,650.00 0.00 2022-11-27 2022-12-26 2023-01-25 tions nvelope ementation ruction Materials for Hawasa nitoring and Evaluation City ET-HAWASSA-325919-GO-RF Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl Q / Procurement of Hallow Co IDA / D7320 e Safety Net to Improve the Post Limited 26,500.00 0.00 2022-11-27 2022-12-26 2023-01-25 tions nvelope ementation ncrete Block Urban Environment ET-HAWASA-325922-GO-RFQ Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl / Procurement of Morale, Perl IDA / D7320 e Safety Net to Improve the Post Limited 6,000.00 0.00 2022-11-27 2022-12-26 2023-01-25 tions nvelope ementation in and timber Urban Environment ET-HAWASSA-325924-GO-RF Expand the Urban Productiv Request for Quota Single Stage - One E Under Imple Q / Procurement of metal doo IDA / D7320 e Safety Net to Improve the Post Limited 35,900.00 0.00 2022-11-27 2022-12-26 2023-01-25 tions nvelope mentation r, window and Sign board Urban Environment ET-YIRGALEM-325940-GO-RF Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl Q / Procurement of Hand tool IDA / D7320 e Safety Net to Improve the Post Limited 8,550.00 0.00 2022-11-20 2022-12-19 2023-01-18 tions nvelope ementation s for Yirhalem city Urban Environment ET-YIRGALEM-325945-GO-RF Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl Q / Procurement of Safety m IDA / D7320 e Safety Net to Improve the Post Limited 48,000.00 0.00 2022-11-26 2022-12-25 2023-01-24 tions nvelope ementation aterials for Yirgalem City Urban Environment ET-YIRGALEM-325946-GO-RF Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl Q / Procurement of Industrial IDA / D7320 e Safety Net to Improve the Post Limited 28,400.00 0.00 2022-11-26 2022-12-25 2023-01-24 tions nvelope ementation Construction Materials Urban Environment ET-YIIRGALEM-325948-GO-R Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl FQ / Procurement of Local Co IDA / D7320 e Safety Net to Improve the Post Limited 15,200.00 0.00 2022-11-20 2022-12-19 2023-01-18 tions nvelope ementation nstruction Materials Urban Environment ET-HARAR-326742-GO-RFQ / Expand the Urban Productiv Request for Quota Single Stage - One E Under Imple Procurement of Hand tools fo IDA / D7320 e Safety Net to Improve the Post Limited 11,570.00 0.00 2022-11-26 2022-12-25 2023-01-24 tions nvelope mentation r Harar City Urban Environment ET-HARAR-326823-GO-RFQ / Expand the Urban Productiv Request for Quota Single Stage - One E Under Imple Procurement of Safety Materi IDA / D7320 e Safety Net to Improve the Post Limited 15,500.00 0.00 2022-11-27 2022-12-26 2023-01-25 tions nvelope mentation als for Harar City Urban Environment ET-HARAR-326826-GO-RFQ / Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl Procurement of Construction IDA / D7320 e Safety Net to Improve the Post Limited 32,600.00 0.00 2022-11-26 2023-01-07 2023-02-06 tions nvelope ementation materials Urban Environment ET-HARAR-326828-GO-DIR / Expand the Urban Productiv Procurement of Cement for H IDA / D7320 e Safety Net to Improve the Post Direct Selection Direct - National 9,300.00 0.00 Canceled 2022-11-21 2022-11-26 2022-12-13 2023-01-12 arar City Urban Environment ET-MIZAN AMAN-326829-GO Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl -RFQ / Procurement of hand t IDA / D7320 e Safety Net to Improve the Post Limited 27,675.00 0.00 2022-11-26 2022-12-25 2023-01-24 tions nvelope ementation ools for Mizan Aman City Urban Environment ET-MIZAN AMAN-326830-GO Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl -RFQ / Procurement of Safety IDA / D7320 e Safety Net to Improve the Post Limited 99,500.00 0.00 2022-11-27 2022-12-26 2023-01-25 tions nvelope ementation materials for mizan Aman Cit Urban Environment y ET-TEPI-326831-GO-RFQ / Pr Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl ocurement of hand tools for IDA / D7320 e Safety Net to Improve the Post Limited 27,600.00 0.00 2022-11-27 2022-12-26 2023-01-25 tions nvelope ementation Tepi city Urban Environment Page 1 ET-TEPI-326832-GO-RFQ / Pr Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl ocurement of Safety Material IDA / D7320 e Safety Net to Improve the Post Limited 94,100.00 0.00 2022-11-27 2022-12-26 2023-01-25 tions nvelope ementation s for Tepi City Urban Environment ET-TEPI-326836-GO-RFQ / Pr Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl ocurement of Construction m IDA / D7320 e Safety Net to Improve the Post Limited 61,500.00 0.00 2022-11-28 2022-12-27 2023-01-26 tions nvelope ementation aterials for Tepi city Urban Environment ET-SEMERA LOGYA-326840- GO-RFQ / Procurement of ha Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl nd tools, safety materials an IDA / D7320 e Safety Net to Improve the Post Limited 7,580.00 0.00 2022-11-27 2023-01-08 2023-07-07 tions nvelope ementation d other construction material Urban Environment s in three lots for Semera log ya city ET-ABEALA-326842-GO-RFQ Expand the Urban Productiv / Procurement of Hand tools, Request for Quota Single Stage - One E Pending Impl IDA / D7320 e Safety Net to Improve the Post Limited 19,000.00 0.00 2022-11-27 2022-12-26 2023-01-25 safety materials and other co tions nvelope ementation Urban Environment nstruction materials for abeal a city by lot system ET-ASOSA-326844-GO-RFQ / Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl Procurement of hand tools fo IDA / D7320 e Safety Net to Improve the Post Limited 15,260.00 0.00 2022-11-27 2022-12-26 2023-01-25 tions nvelope ementation r Asosa City Urban Environment ET-ASOSA-326846-GO-RFQ / Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl Procurement of safety Materi IDA / D7320 e Safety Net to Improve the Post Limited 43,400.00 0.00 2022-11-27 2022-12-25 2023-01-24 tions nvelope ementation als for Asosa City Urban Environment ET-ASOSA-326847-GO-RFQ / Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl Procurement of construction IDA / D7320 e Safety Net to Improve the Post Limited 10,000.00 0.00 2022-11-27 2022-12-26 2023-01-25 tions nvelope ementation materials Urban Environment ET-GILGEL BELES-326848-G O-RFQ / Procurement of Hand Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl tools, safety materials and co IDA / D7320 e Safety Net to Improve the Post Limited 12,600.00 0.00 2022-11-27 2022-12-26 2023-01-25 tions nvelope ementation nstruction materials for Gilge Urban Environment l beles city in three lots ET-GAMBELA-326852-GO-RF Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl Q / Procurement of Hand tool IDA / D7320 e Safety Net to Improve the Post Limited 24,700.00 0.00 2022-11-27 2022-12-26 2023-01-25 tions nvelope ementation s for gambela city Urban Environment ET-GAMBELAI-326855-GO-RF Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl Q / Procurement of safety ma IDA / D7320 e Safety Net to Improve the Post Limited 16,500.00 0.00 2022-11-27 2022-12-26 2023-01-25 tions nvelope ementation terials for Gambela city Urban Environment ET-METI-326859-GO-RFQ / Pr Expand the Urban Productiv ocurement of Hand tools, Saf Request for Quota Single Stage - One E Pending Impl IDA / D7320 e Safety Net to Improve the Post Limited 23,650.00 0.00 2022-11-27 2022-12-26 2022-12-29 ety materials and constructio tions nvelope ementation Urban Environment n materials for meti city in th ree lots ET-MOUDI-326890-GO-RFQ / Institutional Strengthening, Request for Quota Single Stage - One E Procurement of Scanners for IDA / D7320 Project Management and Mo Post Limited 95,000.00 0.00 Signed 2022-11-28 2023-03-10 2022-12-27 2023-02-10 tions nvelope cities nitoring and Evaluation ET-MOUDI-326892-GO-RFQ / Institutional Strengthening, Request for Quota Single Stage - One E Under Imple Procurement of laptop comp IDA / D7320 Project Management and Mo Post Limited 95,000.00 0.00 2022-11-28 2023-03-10 2022-12-27 2023-01-26 tions nvelope mentation uter nitoring and Evaluation ET-MOUDI-326896-GO-RFB / Procurement of Computer, Sc Foster Urban Youth Employ Single Stage - One E Under Imple IDA / D7320 Post Request for Bids Open - National 655,400.00 0.00 2022-11-28 2023-06-03 2022-12-03 2023-06-15 2023-01-03 2023-02-02 2023-03-09 2023-05-08 aner, Printer, Copy machine ment nvelope mentation and tablet computer for com ponent 2.2 ET-HAWASSA-336189-GO-RF Q / Procurement of Laptop, P Foster Urban Youth Employ Request for Quota Single Stage - One E Pending Impl rinter, Desktop computer and IDA / D7320 Post Limited 58,175.00 0.00 2023-01-23 2023-02-21 2023-03-23 ment tions nvelope ementation LCD Projectors for Hawassa C ity in Youth Employment, ET-HAWASSA -336190-GO-R FQ / Procurement of Office Fu Foster Urban Youth Employ Request for Quota Single Stage - One E Pending Impl IDA / D7320 Post Limited 385.00 0.00 2023-01-23 2023-02-21 2023-03-13 rniture for Hawwasa City in ment tions nvelope ementation Youth Employment, Expand the Urban Productiv ET-HARER-347871-GO-RFQ / Request for Quota Single Stage - One E Pending Impl IDA / D7320 e Safety Net to Improve the Post Limited 9,300.00 0.00 2023-03-20 2023-04-18 2023-05-18 Procurement of cement tions nvelope ementation Urban Environment ET-MOUDI-321006-GO-RFQ / Expand the Urban Productiv Procurement of digital came Request for Quota Single Stage - One E IDA / D7320 e Safety Net to Improve the Post Limited 12,000.00 0.00 Canceled 2022-10-22 2022-11-16 2022-12-16 ra for Ethiopian refuges and r tions nvelope Urban Environment eturnees service ET-HARER-MOUDI-362247-G Expand the Urban Productiv O-RFQ / Procurement of differ Request for Quota Single Stage - One E Pending Impl IDA / D7320 e Safety Net to Improve the Post Limited 16,350.00 0.00 2023-06-04 2023-07-06 2023-07-21 ent seedlings and fertile soil f tions nvelope ementation Urban Environment or Harer greenery activities ET-GILGEL BELES-MOUDI-36 Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl 2273-GO-RFQ / Procurement IDA / D7320 e Safety Net to Improve the Post Limited 275.00 0.00 2023-06-04 2023-07-05 2023-07-20 tions nvelope ementation of different seeds for gilgel b Urban Environment eles ET-ASOSSA-MOUDI-362285- Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl GO-RFQ / Procurement of diff IDA / D7320 e Safety Net to Improve the Post Limited 5,060.00 0.00 2023-06-05 2023-07-06 2023-07-26 tions nvelope ementation erent seeds and seedlings Urban Environment ET-MOUDI- RRS-356027-GO- Expand the Urban Productiv RFQ / Procurement of laptop Request for Quota Single Stage - One E Pending Impl IDA / D7320 e Safety Net to Improve the Post Limited 52,000.00 0.00 2023-06-04 2023-07-03 2023-08-02 computer and tablet for Ethio tions nvelope ementation Urban Environment pian refuges and returnees s ervice ET-MOUDI- RRS-356026-GO- Expand the Urban Productiv RFQ / Procurement of digital Request for Quota Single Stage - One E Pending Impl IDA / D7320 e Safety Net to Improve the Post Limited 16,500.00 0.00 2023-06-04 2023-07-03 2023-07-18 camera for Ethiopian refuges tions nvelope ementation Urban Environment and returnees service ET-MOUDI-362396-GO-RFQ / Institutional Strengthening, Request for Quota Single Stage - One E Pending Impl Procurement of Scaners for E IDA / D7320 Project Management and Mo Post Limited 82,000.00 0.00 2023-06-04 2023-07-03 2023-08-02 tions nvelope ementation merging cities and subcities nitoring and Evaluation in Addis Ababa Page 2 ET-MOUDI-362398-GO-DIR-U Foster Urban Youth Employ Pending Impl N / Procurement of 18 Moter IDA / D7320 Post Direct Selection Direct - National 82,000.00 0.00 2023-05-30 2023-06-20 2023-08-14 2024-02-10 ment ementation Biscle for OSSC ET-HAWASSA-367397-GO-RF Expand the Urban Productiv Q / Procurement of Cement f Request for Quota Single Stage - One E Pending Impl IDA / D7320 e Safety Net to Improve the Post Limited 98,000.00 0.00 2023-06-29 2023-07-28 2023-08-27 or hawassa city for social infr tions nvelope ementation Urban Environment astructure building and main tenance NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ET-HAWASA-326882-NC-RFQ / Semi Skill for Hawassa city t Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl o construct additional class r IDA / D7320 e Safety Net to Improve the Post Limited 99,000.00 0.00 2022-11-27 2022-12-26 2023-03-11 tions nvelope ementation oom for schools, additional h Urban Environment ealth care Buildings and Gre enery fences ET-YIRGALEM-328433-NC-RF Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl Q / Semi Skill for social infra IDA / D7320 e Safety Net to Improve the Post Limited 30,200.00 0.00 2022-12-04 2023-01-08 2023-03-27 tions nvelope ementation structure in Yirgalem city Urban Environment ET-ASOSA-328436-NC-RFQ / Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl Semi skill for social infrastruc IDA / D7320 e Safety Net to Improve the Post Limited 5,000.00 0.00 2022-12-04 2023-01-02 2023-03-03 tions nvelope ementation ture in Assosa City Urban Environment ET-GILGEL BELES-328438-N Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl C-RFQ / Semi skill for Social I IDA / D7320 e Safety Net to Improve the Post Limited 3,000.00 0.00 2022-12-04 2023-01-02 2023-03-03 tions nvelope ementation nfrastructure in Gil gel Beles Urban Environment ET-MOUDI-335570-NC-DIR / Institutional Strengthening, Procurement of Third Party s Direct - Internation IDA / D7320 Project Management and Mo Prior Direct Selection 3,200,000.00 0.00 Signed 2023-01-16 2023-02-10 2023-01-21 2023-02-13 2023-02-19 2024-02-19 ervice provider for Tigray Re al nitoring and Evaluation gion in UPSNJP additional Fin ance ET-MOUDI- GILGEL BELES-36 Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl 2397-NC-RFQ / Semi Skill for IDA / D7320 e Safety Net to Improve the Post Limited 2,500.00 0.00 2023-06-02 2023-07-01 2023-07-31 tions nvelope ementation Commun latrin construction Urban Environment at Gilgel beles CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ET-MOUDI-326889-CS-QCBS Institutional Strengthening, Quality And Cost- Pending Impleme / Environmental and social A IDA / D7320 Project Management and Mo Post Open - National 250,000.00 0.00 2022-11-23 2022-12-14 2023-01-27 2023-02-24 2023-03-26 2023-04-30 2023-06-04 2023-08-18 Based Selection ntation udit for 2014 EFY nitoring and Evaluation ET-MOUDI-328491-CS-QCBS Institutional Strengthening, Quality And Cost- Under Implement / Public work review for the y IDA / D7320 Project Management and Mo Post Open - National 220,000.00 0.00 2022-11-29 2023-05-18 2022-12-14 2023-06-15 2023-01-27 2023-02-27 2023-03-29 2023-05-03 2023-06-07 2023-08-21 Based Selection ation ear 2014 EFY nitoring and Evaluation ET-MOUDI-328495-CS-QCBS Institutional Strengthening, Quality And Cost- Under Implement / Procurement Audit for the y IDA / D7320 Project Management and Mo Prior Open - National 200,000.00 0.00 2022-11-30 2022-12-15 2023-01-28 2023-02-28 2023-03-30 2023-05-04 2023-06-08 2023-08-22 Based Selection ation ear 2014 EFY nitoring and Evaluation ET-MOUDI-345014-CS-QCBS Institutional Strengthening, / UPSNJP Multiyear independ Quality And Cost- Open - Internationa Under Implement IDA / D7320 Project Management and Mo Prior 500,000.00 0.00 2023-06-07 2023-06-14 2023-06-22 2023-06-27 2023-07-27 2023-08-28 2023-09-27 2023-10-26 2023-11-24 2026-04-07 ent procurement Audit FY22/ Based Selection l ation nitoring and Evaluation EFY 2014 to FY26/EFY2018" INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ET-MOUDI-325892-CS-INDV / Institutional Strengthening, Individual Consult Under Implement Recruit Senior Procurement s IDA / D7320 Project Management and Mo Post Direct - National 16,500.00 0.00 2022-11-14 2023-02-13 2022-11-24 2022-12-09 2023-01-07 2024-01-07 ant Selection ation pecialist/ Consultant nitoring and Evaluation ET-MOUDI-325893-CS-INDV / Institutional Strengthening, Individual Consult Under Implement Recruit Senior Procurement S IDA / D7320 Project Management and Mo Prior Direct - National 16,500.00 0.00 2022-11-15 2023-02-16 2022-11-25 2022-12-10 2023-01-08 2024-01-08 ant Selection ation pecialist/ Consultant nitoring and Evaluation ET-MOUDI-325894-CS-INDV / Institutional Strengthening, Individual Consult Under Implement Recruit Safeguard Specialist f IDA / D7320 Project Management and Mo Post Open - National 8,350.00 0.00 2022-11-15 2023-02-01 2023-01-04 2023-01-25 2023-03-01 2024-02-29 ant Selection ation or Federal PCU nitoring and Evaluation ET-MOUDI-325897-CS-INDV / Recruit Procurement Speciali Institutional Strengthening, st for Federal PCU who will su Individual Consult Pending Impleme IDA / D7320 Project Management and Mo Post Open - National 8,350.00 0.00 2022-11-17 2023-01-05 2023-01-26 2023-03-02 2024-03-01 pport cities in the region of S ant Selection ntation nitoring and Evaluation omale , Benshangul , Gambel a, Afar, South West Ethiopia and Harari ET-SIDAMA-325934-CS-INDV Foster Urban Youth Employ Individual Consult Under Implement / Recruitment of Youth Emplo IDA / D7320 Post Open - National 5,000.00 0.00 2022-11-15 2023-01-13 2023-01-04 2023-01-25 2023-03-01 2024-02-29 ment ant Selection ation yment Specialist for Hawassa City ET-MOUDI-325358-CS-INDV / Institutional Strengthening, Individual Consult Under Implement Recruitment of project coordi IDA / D7320 Project Management and Mo Post Direct - National 20,000.00 0.00 2022-11-29 2023-02-14 2022-12-08 2022-12-29 2023-01-18 2024-01-18 ant Selection ation nator for UPSNJP at Federal P nitoring and Evaluation CU ET-MOUDI-328498-CS-INDV / Institutional Strengthening, Individual Consult Pending Impleme Recruit additional Monitoring IDA / D7320 Project Management and Mo Post Open - National 8,150.00 0.00 2022-11-30 2023-01-19 2023-02-09 2023-03-16 2024-03-15 ant Selection ntation and evaluation specialist at f nitoring and Evaluation ederal PCU Page 3 ET-MOUDI-344999-CS-INDV / Recruit Federal Project Coord Institutional Strengthening, ination Unit Coordinator who Individual Consult Pending Impleme IDA / D7320 Project Management and Mo Post Limited 26,500.00 0.00 2023-03-13 2023-03-18 2023-04-07 2023-04-20 2024-04-19 will responsible for managem ant Selection ntation nitoring and Evaluation ent, coordination and implem entation of all components a nd activities of the UPSNJP ET-MOUDI-345001-CS-INDV / Recruit Senior Procurement S Institutional Strengthening, pecialist/ Consultant at Feder Individual Consult Pending Impleme IDA / D7320 Project Management and Mo Prior Limited 20,000.00 0.00 2023-03-13 2023-03-18 2023-04-07 2023-04-20 2024-04-19 al PCU who will manage and ant Selection ntation nitoring and Evaluation coordinate the over all procu rement activities across all i mplementing institutions. ET-MOUDI-345006-CS-INDV / Recruit Senior Procurement S Institutional Strengthening, pecialist/ Consultant at Feder Individual Consult Pending Impleme IDA / D7320 Project Management and Mo Prior Limited 20,000.00 0.00 2023-03-13 2023-03-18 2023-04-07 2023-04-20 2024-04-19 al PCU who will manage and ant Selection ntation nitoring and Evaluation coordinate the over all procu rement activities across all i mplementing institutions. ET-HARAR-367398-CS-INDV / Institutional Strengthening, Individual Consult Pending Impleme Recruit UPSNJP Safeguard sp IDA / D7320 Project Management and Mo Post Open - National 4,000.00 0.00 2023-06-26 2023-08-15 2023-08-25 2023-09-14 2024-09-13 ant Selection ntation ecialist for Harar city nitoring and Evaluation ET-AFAR-367402-CS-INDV / Institutional Strengthening, Individual Consult Pending Impleme Recruit UPSNJP Safeguard sp IDA / D7320 Project Management and Mo Post Open - National 4,000.00 0.00 2023-06-26 2023-08-15 2023-08-25 2023-09-14 2024-09-13 ant Selection ntation ecialist for cities in Afar Regi nitoring and Evaluation on ET-GAMBELA-367403-CS-IND Institutional Strengthening, Individual Consult Pending Impleme V / Recruit UPSNJP Safeguard IDA / D7320 Project Management and Mo Post Open - National 4,000.00 0.00 2023-06-25 2023-08-14 2023-08-24 2023-09-13 2024-09-12 ant Selection ntation specialist for cities in Gambel nitoring and Evaluation la Region ET-SIDAMA-367404-CS-INDV Institutional Strengthening, Individual Consult Pending Impleme / Recruit UPSNJP Safeguard s IDA / D7320 Project Management and Mo Post Open - National 4,000.00 0.00 2023-06-25 2023-08-14 2023-08-24 2023-09-13 2024-09-12 ant Selection ntation pecialist for cities in Sidama nitoring and Evaluation Region ET-B/GUMUZ-367410-CS-IND Institutional Strengthening, V / Recruit UPSNJP Safeguard Individual Consult Pending Impleme IDA / D7320 Project Management and Mo Post Open - National 4,000.00 0.00 2023-06-26 2023-08-15 2023-08-25 2023-09-14 2024-09-13 specialist for cities in Bensha ant Selection ntation nitoring and Evaluation ngul Gumuz Region ET-SOUTH WEST ETHIOPIA-3 Institutional Strengthening, 67411-CS-INDV / Recruit UPS Individual Consult Pending Impleme IDA / D7320 Project Management and Mo Post Open - National 4,000.00 0.00 2023-06-26 2023-08-15 2023-08-25 2023-09-14 2024-09-13 NJP Safeguard specialist for c ant Selection ntation nitoring and Evaluation ities in South West Ethiopia R egion Page 4 PROCUREMENT PLAN (Textual Part) Project information: Ethiopia COVID-19 Emergency Response (P173750) Project Implementation agency: Ministry of Health Date of the Procurement Plan: May 6, 2020 Period covered by this Procurement Plan: May 6, 2020 to January 1, 2021 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in Public Procurement and Property Administration Proclamation No. 649/2009, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations is Applicable. Other Relevant Procurement Information. Procurement procedures in Situations of Urgent Need of Assistance or Capacity Constraints is applicable in the Project. PROCUREMENT Ethiopia : Ethiopia COVID-19 Emergency Response PLAN General Information Country: Ethiopia 2020-05-06 Bank’s Approval Date of the Original Procurement Plan: 2023-06-06 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P173750 GPN Date: 2020-11-20 Project Name: Ethiopia COVID-19 Emergency Response Loan / Credit No: IDA / 65870, IDA / D7910, IDA / D9550, IDA / E0640, IDA / D5940 Ministry of Health Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned ET-MOH-173028-CW-RFQ / R Quarantine, Isolation and Tr Request for Quota Single Stage - One E 2021-01-2 enovation of quarantine in A IDA / 65870 Post Open - National 227,973.00 0.00 Canceled 2020-06-05 2020-07-31 eatment Centers tions nvelope 7 mhara region-Metema 1Site ET-MOH-173263-CW-RFQ / R Quarantine, Isolation and Tr Request for Quota Single Stage - One E 2021-01-2 enovation of quarantine in S IDA / 65870 Post Open - National 227,973.00 0.00 Canceled 2020-06-05 2020-07-31 eatment Centers tions nvelope 7 NNP region- South OmoKakut a Site ET-MOH-173264-CW-RFQ / R Quarantine, Isolation and Tr Request for Quota Single Stage - One E 2021-01-2 enovation of of quarantine n IDA / 65870 Post Open - National 227,973.00 0.00 Canceled 2020-06-05 2020-07-31 eatment Centers tions nvelope 7 Tigray region-Mekele Dima Si te ET-MOH-173268-CW-RFQ / R Quarantine, Isolation and Tr Request for Quota Single Stage - One E 2021-01-2 enovation of quarantine in IDA / 65870 Post Open - National 227,973.00 0.00 Canceled 2020-06-05 2020-07-31 eatment Centers tions nvelope 7 Oromia region-Ethio-Kenya B ole Site ET-MOH-173271-CW-RFQ / R Quarantine, Isolation and Tr Request for Quota Single Stage - One E 2021-01-2 enovation of quarantine in A IDA / 65870 Post Open - National 227,973.00 0.00 Canceled 2020-06-05 2020-07-31 eatment Centers tions nvelope 7 far region-Ethio- Semera Tow n ET-MOH-173272-CW-RFQ / R Quarantine, Isolation and Tr Request for Quota Single Stage - One E 2021-01-2 enovation of quarantine in IDA / 65870 Post Open - National 227,973.00 0.00 Canceled 2020-06-05 2020-07-31 eatment Centers tions nvelope 7 Gambela region-GambelaLar e ET-MOH-173274-CW-RFQ / R Quarantine, Isolation and Tr Request for Quota Single Stage - One E 2021-01-2 enovation of quarantine in D IDA / 65870 Post Open - National 227,973.00 0.00 Canceled 2020-06-05 2020-07-31 eatment Centers tions nvelope 7 ire DawaCity-DewoleLandpor t site ET-MOH-173278-CW-RFQ / R enovation of quarantine in B Quarantine, Isolation and Tr Request for Quota Single Stage - One E 2021-01-2 IDA / 65870 Post Open - National 227,973.00 0.00 Canceled 2020-06-05 2020-07-31 eneshangulGumz Region- Be eatment Centers tions nvelope 7 nishangul Kumruk ET-MOH-173280-CW-RFQ / R Quarantine, Isolation and Tr Request for Quota Single Stage - One E 2021-01-2 enovation of quarantine in S IDA / 65870 Post Open - National 227,973.00 0.00 Canceled 2020-06-05 2020-07-31 eatment Centers tions nvelope 7 omali Region-Togo Chale ET-MOH-173281-CW-RFQ / R Quarantine, Isolation and Tr Request for Quota Single Stage - One E 2021-01-2 enovation of Isolation Centre IDA / 65870 Post Open - National 294,746.00 0.00 Canceled 2020-06-05 2020-07-31 eatment Centers tions nvelope 7 in Addis Ababa-Basha Wolde site ET-MOH-173282-CW-RFQ / R Quarantine, Isolation and Tr Request for Quota Single Stage - One E 2021-01-2 enovation of Isolation Centre IDA / 65870 Post Open - National 294,746.00 0.00 Canceled 2020-06-05 2020-07-31 eatment Centers tions nvelope 7 in Amhara Region- Bahir Dar City ET-MOH-173283-CW-RFQ / R Quarantine, Isolation and Tr Request for Quota Single Stage - One E 2021-01-2 enovation of Isolation Centre IDA / 65870 Post Open - National 294,746.00 0.00 Canceled 2020-06-05 2020-07-31 eatment Centers tions nvelope 7 in SNNP Region-Hawasa Tow n ET-MOH-173285-CW-RFQ / R Quarantine, Isolation and Tr Request for Quota Single Stage - One E 2021-01-2 enovation of Isolation Centre IDA / 65870 Post Open - National 294,746.00 0.00 Canceled 2020-06-05 2020-07-31 eatment Centers tions nvelope 7 in Tigray Region-Mekele Airp ort ET-MOH-173286-CW-RFQ / R Quarantine, Isolation and Tr Request for Quota Single Stage - One E 2021-01-2 enovation of Isolation Centre IDA / 65870 Post Open - National 294,746.00 0.00 Canceled 2020-06-05 2020-07-31 eatment Centers tions nvelope 7 in Oromia Region-Jimma ET-MOH-173288-CW-RFQ / R Quarantine, Isolation and Tr Request for Quota Single Stage - One E 2021-01-2 enovation of Isolation Centre IDA / 65870 Post Open - National 294,746.00 0.00 Canceled 2020-06-05 2020-07-31 eatment Centers tions nvelope 7 in Somali Region-Jigjiga Airp ort ET-MOH-173291-CW-RFQ / R Quarantine, Isolation and Tr Request for Quota Single Stage - One E 2021-01-2 enovation of Isolation Centre IDA / 65870 Post Open - National 294,746.00 0.00 Canceled 2020-06-05 2020-07-31 eatment Centers tions nvelope 7 in Afar Region-Semera Town ET-MOH-173294-CW-RFQ / R Quarantine, Isolation and Tr Request for Quota Single Stage - One E 2021-01-2 enovation of Isolation Centre IDA / 65870 Post Open - National 294,746.00 0.00 Canceled 2020-06-05 2020-07-31 eatment Centers tions nvelope 7 in BeneshangulGumzRegion- Assosa ET-MOH-173296-CW-RFQ / R Quarantine, Isolation and Tr Request for Quota Single Stage - One E 2021-01-2 enovation of Isolation Centre IDA / 65870 Post Open - National 294,746.00 0.00 Canceled 2020-06-05 2020-07-31 eatment Centers tions nvelope 7 in Harari Region-Harari Town ET-MOH-173299-CW-RFQ / R Quarantine, Isolation and Tr Request for Quota Single Stage - One E 2021-01-2 enovation of Isolation Centre IDA / 65870 Post Open - National 294,746.00 0.00 Canceled 2020-06-05 2020-07-31 eatment Centers tions nvelope 7 in Dire Dawa -Dire Dawa Cit y ET-MOH-173300-CW-RFQ / C Quarantine, Isolation and Tr Request for Quota Single Stage - One E 2021-01-2 onstruction of Point of Entry i IDA / 65870 Post Open - National 290,136.00 0.00 Canceled 2020-06-05 2020-07-31 eatment Centers tions nvelope 7 n Tigray Region-Lugdi ET-MOH-173303-CW-RFQ / C Quarantine, Isolation and Tr Request for Quota Single Stage - One E 2021-01-2 onstruction of Point of Entry i IDA / 65870 Post Open - National 290,136.00 0.00 Canceled 2020-06-05 2020-07-31 eatment Centers tions nvelope 7 n Oromia Region-Moyale ET-MOH-173304-CW-RFQ / C Quarantine, Isolation and Tr Request for Quota Single Stage - One E 2021-01-2 onstruction of Point of Entry i IDA / 65870 Post Open - National 290,136.00 0.00 Canceled 2020-06-05 2020-07-31 eatment Centers tions nvelope 7 n Somali Region-Daale Page 1 ET-MOH-173307-CW-RFQ / C Quarantine, Isolation and Tr Request for Quota Single Stage - One E 2021-01-2 onstruction of Point of Entry i IDA / 65870 Post Open - National 290,136.00 0.00 Canceled 2020-06-05 2020-07-31 eatment Centers tions nvelope 7 n Somali Region-Togo Wucha le ET-MOH-173308-CW-RFQ / C Quarantine, Isolation and Tr Request for Quota Single Stage - One E 2021-01-2 onstruction of Point of Entry i IDA / 65870 Post Open - National 290,136.00 0.00 Canceled 2020-06-05 2020-07-31 eatment Centers tions nvelope 7 n BeneshangulGumz Region- Kumruk ET-MOH-173292-CW-RFQ / R Quarantine, Isolation and Tr Request for Quota Single Stage - One E 2021-01-2 enovation of Isolation Centre IDA / 65870 Post Open - National 294,746.00 0.00 Canceled 2020-06-05 2020-07-31 eatment Centers tions nvelope 7 in Gambela Region-Gambela City ET-MOH-182230-W-RFQ / / R Quarantine, Isolation and Tr Request for Quota Single Stage - One E 2020-10-3 enovation of Isolation Centre IDA / 65870 Post Limited 295,000.00 0.00 Canceled 2020-07-01 2020-08-26 eatment Centers tions nvelope 0 in SNNP Region-Hawasa Tow n ET-MOH-182226-W-RFQ / / R Quarantine, Isolation and Tr Request for Quota Single Stage - One E 2020-10-3 enovation of Isolation Centre IDA / 65870 Post Limited 295,000.00 226,590.25 Signed 2020-07-02 2020-10-21 2020-08-27 2020-12-18 eatment Centers tions nvelope 0 in Beneshangul Gumz Region -Assosa ET-MOH-182246-W-RFQ / / R Quarantine, Isolation and Tr Request for Quota Single Stage - One E 2020-10-3 enovation of quarantine in A IDA / 65870 Post Limited 227,975.00 0.00 Canceled 2020-07-02 2020-08-27 eatment Centers tions nvelope 0 far region-Ethio- Semera Tow n ET-MOH-182228-W-RFQ / / R Quarantine, Isolation and Tr Request for Quota Single Stage - One E 2020-10-3 enovation of Isolation Centre IDA / 65870 Post Limited 295,000.00 0.00 Canceled 2020-07-02 2020-08-27 eatment Centers tions nvelope 0 in Dire Dawa -Dire Dawa Cit y ET-MOH-182234-W-RFQ / / R enovation of quarantine in B Quarantine, Isolation and Tr Request for Quota Single Stage - One E 2020-10-3 IDA / 65870 Post Limited 227,975.00 0.00 Canceled 2020-07-02 2020-08-27 eneshangul Gumz Region- Be eatment Centers tions nvelope 0 nishangul Kumruk ET-MOH-182241-W-RFQ / / R Quarantine, Isolation and Tr Request for Quota Single Stage - One E 2020-10-3 enovation of quarantine in S IDA / 65870 Post Limited 227,975.00 169,596.65 Signed 2020-07-02 2020-10-09 2020-08-27 2020-12-11 eatment Centers tions nvelope 0 omali Region-Togo Chale ET-MOH-182245-W-RFQ / / R Quarantine, Isolation and Tr Request for Quota Single Stage - One E 2020-10-3 enovation of Isolation Centre IDA / 65870 Post Limited 295,000.00 260,321.02 Signed 2020-07-02 2020-10-27 2020-08-27 2020-12-09 eatment Centers tions nvelope 0 in Amhara Region- Bahir Dar City ET-MOH-182224-W-RFQ / / R Quarantine, Isolation and Tr Request for Quota Single Stage - One E 2020-10-3 enovation of Isolation Centre IDA / 65870 Post Limited 295,000.00 226,027.27 Completed 2020-07-02 2020-10-09 2020-08-27 2020-12-10 eatment Centers tions nvelope 0 in Oromia Region-Jimma ET-MOH-182239-W-RFQ / / C Quarantine, Isolation and Tr Request for Quota Single Stage - One E 2020-10-3 onstruction of Point of Entry i IDA / 65870 Post Limited 295,000.00 197,659.35 Completed 2020-07-02 2020-10-09 2020-08-27 2020-12-14 eatment Centers tions nvelope 0 n Oromia Region-Moyale ET-MOH-182221-W-RFQ / / R Quarantine, Isolation and Tr Request for Quota Single Stage - One E 2020-10-3 enovation of quarantine in S IDA / 65870 Post Limited 227,970.00 0.00 Canceled 2020-07-02 2020-08-27 eatment Centers tions nvelope 0 NNP region- South Omo Kaku ta Site ET-MOH-182231-W-RFQ / / C Quarantine, Isolation and Tr Request for Quota Single Stage - One E 2020-10-3 onstruction of Point of Entry i IDA / 65870 Post Limited 295,000.00 0.00 Canceled 2020-07-02 2020-08-27 eatment Centers tions nvelope 0 n Tigray Region-Lugdi ET-MOH-182255-W-RFQ / / R Quarantine, Isolation and Tr Request for Quota Single Stage - One E 2020-10-3 enovation of quarantine in D IDA / 65870 Post Limited 227,975.00 0.00 Canceled 2020-07-02 2020-08-27 eatment Centers tions nvelope 0 ire DawaCity-DewoleLandpor t site ET-MOH-182235-W-RFQ / / R Quarantine, Isolation and Tr Request for Quota Single Stage - One E 2020-10-3 enovation of Isolation Centre IDA / 65870 Post Limited 295,000.00 252,327.37 Signed 2020-07-02 2020-10-05 2020-08-27 2020-12-10 eatment Centers tions nvelope 0 in Harari Region-Harari Town ET-MOH-182247-W-RFQ / / R Quarantine, Isolation and Tr Request for Quota Single Stage - One E 2020-10-3 enovation of Isolation Centre IDA / 65870 Post Limited 295,000.00 201,176.24 Signed 2020-07-02 2020-10-09 2020-08-27 2020-12-11 eatment Centers tions nvelope 0 in Somali Region-Jigjiga Airp ort ET-MOH-182242-W-RFQ / / R Quarantine, Isolation and Tr Request for Quota Single Stage - One E 2020-10-3 enovation of Isolation Centre IDA / 65870 Post Limited 295,000.00 195,809.72 Signed 2020-07-02 2020-10-26 2020-08-27 2020-12-18 eatment Centers tions nvelope 0 in Addis Ababa-Basha Wolde site ET-MOH-182252-W-RFQ / / R Quarantine, Isolation and Tr Request for Quota Single Stage - One E 2020-10-3 enovation of quarantine in IDA / 65870 Post Limited 227,975.00 183,626.85 Completed 2020-07-02 2020-10-09 2020-08-27 2020-12-24 eatment Centers tions nvelope 0 Oromia region-Ethio-Kenya B ole Site ET-MOH-182237-W-RFQ / / R Quarantine, Isolation and Tr Request for Quota Single Stage - One E 2020-10-3 enovation of of quarantine n IDA / 65870 Post Limited 227,975.00 0.00 Canceled 2020-07-02 2020-08-27 eatment Centers tions nvelope 0 Tigray region-Mekele Dima Si te ET-MOH-182240-W-RFQ / / R Quarantine, Isolation and Tr Request for Quota Single Stage - One E 2020-10-3 enovation of Isolation Centre IDA / 65870 Post Limited 295,000.00 0.00 Canceled 2020-07-02 2020-08-27 eatment Centers tions nvelope 0 in Afar Region-Semera Town ET-MOH-182254-W-RFQ / / C Quarantine, Isolation and Tr Request for Quota Single Stage - One E 2020-10-3 onstruction of Point of Entry i IDA / 65870 Post Limited 295,000.00 185,124.77 Signed 2020-07-02 2020-10-09 2020-08-27 2020-12-18 eatment Centers tions nvelope 0 n Somali Region-Daale ET-MOH-182236-W-RFQ / / C Quarantine, Isolation and Tr Request for Quota Single Stage - One E 2020-10-3 onstruction of Point of Entry i IDA / 65870 Post Limited 295,000.00 186,650.85 Signed 2020-07-02 2020-10-09 2020-08-27 2020-12-11 eatment Centers tions nvelope 0 n Somali Region-Togo Wucha le ET-MOH-182244-W-RFQ / / R Quarantine, Isolation and Tr Request for Quota Single Stage - One E 2020-10-3 enovation of quarantine in IDA / 65870 Post Limited 227,975.00 167,552.67 Signed 2020-07-02 2020-10-05 2020-08-27 2020-12-26 eatment Centers tions nvelope 0 Gambela region-GambelaLar e ET-MOH-182249-W-RFQ / / R Quarantine, Isolation and Tr Request for Quota Single Stage - One E 2020-10-3 enovation of Isolation Centre IDA / 65870 Post Limited 295,000.00 0.00 Canceled 2020-07-02 2020-08-27 eatment Centers tions nvelope 0 in Tigray Region-Mekele Airp ort ET-MOH-182251-W-RFQ / / R Quarantine, Isolation and Tr Request for Quota Single Stage - One E 2020-10-3 enovation of Isolation Centre IDA / 65870 Post Limited 295,000.00 168,792.71 Signed 2020-07-02 2020-10-05 2020-08-27 2020-12-24 eatment Centers tions nvelope 0 in GambelaRegion-Gambela City ET-MOH-182229-W-RFQ / / R Quarantine, Isolation and Tr Request for Quota Single Stage - One E 2020-10-3 enovation of quarantine in A IDA / 65870 Post Limited 227,975.00 0.00 Canceled 2020-07-02 2020-08-27 eatment Centers tions nvelope 0 mhara region-Metema 1Site Page 2 ET-MOH-182238-W-RFQ / / C Quarantine, Isolation and Tr Request for Quota Single Stage - One E 2020-10-3 onstruction of Point of Entry i IDA / 65870 Post Limited 295,000.00 0.00 Canceled 2020-07-02 2020-08-27 eatment Centers tions nvelope 0 n Beneshangul Gumz Region- Kumruk ET-MOH-213333-CW-RFQ / B Quarantine, Isolation and Tr Single Stage - One E 2021-12-0 lacklion Hospital COVID 19 d IDA / 65870 Post Request for Bids Open - National 1,877,094.00 0.00 Canceled 2021-02-20 2021-03-14 2021-02-25 2021-02-12 2021-04-08 2021-03-16 2021-05-08 2021-06-12 eatment Centers nvelope 9 edicated building renovation works ET-MOH-213334-CW-RFQ / S Quarantine, Isolation and Tr Single Stage - One E 2021-12-0 aint Paul Hospital COVID 19 d IDA / 65870 Post Request for Bids Open - National 1,250,000.00 919,542.28 Signed 2021-02-20 2021-02-12 2021-02-25 2021-02-12 2021-04-08 2021-03-12 2021-05-08 2021-03-30 2021-06-12 2021-05-02 eatment Centers nvelope 9 edicated building Request for Bids - ET-MOH-237444-CW-RFB / Bl Quarantine, Isolation and Tr Single Stage - One E Small Works SPD 2,072,310.4 2022-03-2 acklion Hospital COVID 19 de IDA / 65870 Post Request for Bids Open - National 1,877,094.00 Signed 2021-06-06 2021-06-09 2021-06-11 2021-07-23 2021-07-09 2021-08-22 2021-08-02 2021-09-26 2021-10-13 eatment Centers nvelope (1 envelope proce 4 5 dicated building renovation ss) works ET-MOH-240997-CW-RFB / R Request for Bids - enovation of vaccine laborat Medical Supplies and Equip Open - Internationa Single Stage - One E Works (without pr 22,470,000.0 2023-12-3 IDA / D7910 Prior Request for Bids 0.00 Canceled 2021-07-19 2021-07-24 2021-09-04 2021-10-04 2022-02-28 ory –(equipped with air condi ment l nvelope equalification) SP 0 1 tionings to create clean zone D s) ET-MOH-241018-CW-RFB / Pr Request for Bids - ocurement of Water treatme Quarantine, Isolation and Tr Single Stage - One E Small Works SPD Pending Imp 2022-12-3 nt system and Effluent treat IDA / D7910 Post Request for Bids Open - National 2,030,000.00 0.00 2021-07-02 2021-07-07 2021-08-18 2021-09-17 2021-12-31 eatment Centers nvelope (1 envelope proce lementation 1 ment plant (pharmaceutical ss) grade waters and waste treat ment plant ET-MOH-258050-CW-RFB / C Request for Bids - onstruction of vaccine labor Medical Supplies and Equip Open - Internationa Single Stage - One E Works (without pr 22,470,000.0 2022-08-0 IDA / D7910 Prior Request for Bids 0.00 Signed 2021-10-17 2021-12-16 2021-10-22 2022-02-17 2021-12-03 2022-04-01 2022-01-02 2022-08-16 2022-02-06 atory –(equipped with air con ment l nvelope equalification) SP 0 5 ditioning to create clean zon D es) Request for Bids - ET-MOH-282959-CW-RFB / R Medical Supplies and Equip Open - Internationa Single Stage - One E Works (without pr 19,500,000.0 Under Imple 2023-01-0 IDA / D7910 Prior Request for Bids 0.00 2022-03-20 2022-09-21 2022-03-25 2022-10-17 2022-05-06 2022-12-09 2022-06-05 2023-02-06 2022-07-10 enovation of cold room & wa ment l nvelope equalification) SP 0 mentation 6 rehouse D ET-MOH-294835-CW-RFB / R Request for Bids - enovation of Health facilities Quarantine, Isolation and Tr Single Stage - One E Small Works SPD Pending Imp 2023-04-0 found in Amhara Region- Sou IDA / D7910 Post Request for Bids Open - National 5,220,000.00 0.00 2022-06-15 2022-06-20 2022-08-01 2022-08-31 2022-10-05 eatment Centers nvelope (1 envelope proce lementation 3 th Wollo, Oromo N. & North ss) Wollo Zones (lot based) ET-MOH-294857-CW-RFB / R Request for Bids - enovation of different Health Quarantine, Isolation and Tr Single Stage - One E Small Works SPD Pending Imp 2023-04-0 facilities found in Amhara Re IDA / D7910 Post Request for Bids Open - National 6,510,000.00 0.00 2022-06-20 2022-06-25 2022-08-06 2022-09-05 2022-10-10 eatment Centers nvelope (1 envelope proce lementation 8 gion- North Wollo, & South W ss) ollo Zones( lot Based) ET-MOH-294858-CW-RFB / R Request for Bids - enovation of Different Health Quarantine, Isolation and Tr Single Stage - One E Small Works SPD Pending Imp 2023-04-0 IDA / D7910 Post Request for Bids Open - National 4,170,000.00 0.00 2022-06-20 2022-06-25 2022-08-06 2022-09-05 2022-10-10 Facilities found in Afar Regio eatment Centers nvelope (1 envelope proce lementation 8 n - Zone 1, Zone 4, & Zone 5 ss) (lot based) ET-MOH-294854-CW-RFB / R enovation of different Health Request for Bids - facilities found in Amhara Re Quarantine, Isolation and Tr Single Stage - One E Small Works SPD Pending Imp 2023-04-0 IDA / D7910 Post Request for Bids Open - National 6,600,000.00 0.00 2022-06-20 2022-06-25 2022-08-06 2022-09-05 2022-10-10 gion -South Gonder, Wag-Hi eatment Centers nvelope (1 envelope proce lementation 8 mra, North Gonder, Oromo N. ss) & North Shoa Zones (lot bas ed) ET-MOH-328802-CW-RFB / W Request for Bids - ater well electromechanical a Quarantine, Isolation and Tr Single Stage - One E Small Works SPD Pending Imp 2023-10-0 nd pipeline works for selecte IDA / D9550 Post Request for Bids Open - National 966,479.25 0.00 2022-12-20 2022-12-25 2023-02-05 2023-03-07 2023-04-11 eatment Centers nvelope (1 envelope proce lementation 8 d Hospitals ( Alert, St. Paule, ss) Eka kotebe, and Ministry of H ealth) ET-MOH-344264-CW-RFB / R Request for Bids - enovation of COVID-19 dedic Quarantine, Isolation and Tr Single Stage - One E Small Works SPD Pending Imp 2023-12-1 IDA / D7910 Post Request for Bids Open - National 5,200,000.00 0.00 2023-03-01 2023-03-06 2023-04-17 2023-05-17 2023-06-21 ated Hospitals(Saint Peter, E eatment Centers nvelope (1 envelope proce lementation 8 ka Abado, Saint Amanuel, an ss) d Alert Hospitals) GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ET-MOH-COVID-RF-1 / Procur Medical Supplies and Equip IDA / 65870 Post Direct Selection Direct 15,000,000.00 15,000,000.00 Completed 2019-12-03 2020-01-02 2019-12-08 2020-01-04 2020-01-12 2020-01-06 2020-07-10 2022-01-29 ement of PPE from EPSA ment ET-MOH-COVID-RF-2 / Procur Medical Supplies and Equip ement of PPE Medical Equip IDA / 65870 Post Direct Selection Direct 2,800,137.50 2,800,137.50 Completed 2019-12-03 2020-05-13 2019-12-08 2020-01-05 2020-01-12 2020-01-06 2020-07-10 2021-09-09 ment ment from EPSA ET-MOH-COVID-RF-3 / Procur Medical Supplies and Equip IDA / 65870 Post Direct Selection Direct 947,829.00 947,829.91 Completed 2019-12-03 2020-01-01 2019-12-08 2020-01-04 2020-01-12 2020-01-06 2020-07-10 2021-05-21 ement of Pharmaceuticals ment ET-MOH-173310-GO-RFQ / Pr Quarantine, Isolation and Tr Request for Quota Single Stage - One E ocurement of Incinerator for IDA / 65870 Post Open - National 700,000.00 0.00 Canceled 2020-06-05 2020-07-31 2021-01-27 eatment Centers tions nvelope renovated Facilities ET-MOH-COVID-BFP-1 / Porta Quarantine, Isolation and Tr IDA / 65870 Post Direct Selection Direct 1,200,000.00 2,565,946.56 Completed 2020-04-16 2020-04-10 2020-04-21 2020-04-20 2020-05-26 2020-05-06 2020-11-22 2020-09-10 ble x-ray Machine through BF eatment Centers P ET-MOH-COVID-BFP-2 / Oxyg Quarantine, Isolation and Tr IDA / 65870 Post Direct Selection Direct 1,208,000.00 0.00 Canceled 2020-04-16 2020-04-21 2020-05-26 2020-11-22 en concentrator through BFP eatment Centers ET-MOH-COVID-BFP-3 / Strec Quarantine, Isolation and Tr IDA / 65870 Post Direct Selection Direct 39,075.00 0.00 Canceled 2020-04-16 2020-04-21 2020-05-26 2020-11-22 her through BFP eatment Centers ET-MOH-COVID-BFP-4 / Whe Quarantine, Isolation and Tr IDA / 65870 Post Direct Selection Direct 28,125.00 0.00 Canceled 2020-04-16 2020-04-21 2020-05-26 2020-11-22 el chair through BFP eatment Centers ET-MOH-COVID-BFP-5 / Lary Quarantine, Isolation and Tr IDA / 65870 Post Direct Selection Direct 101,250.00 0.00 Canceled 2020-04-16 2020-04-21 2020-05-26 2020-11-22 ngoscope through BFP eatment Centers ET-MOH-COVID-BFP-6 / Oxyg Quarantine, Isolation and Tr IDA / 65870 Post Direct Selection Direct 3,000.00 0.00 Canceled 2020-04-16 2020-04-21 2020-05-26 2020-11-22 en mask through BFP eatment Centers Page 3 ET-MOH-COVID-BFP-7 / Nebu Quarantine, Isolation and Tr IDA / 65870 Post Direct Selection Direct 22,100.00 0.00 Canceled 2020-04-16 2020-04-21 2020-05-26 2020-11-22 lizer through BFP eatment Centers ET-MOH-COVID-BFP-8 / Proc Medical Supplies and Equip urement of PPE- Glove and pr IDA / 65870 Post Direct Selection Direct 280,000.00 277,760.70 Signed 2020-05-11 2020-06-01 2020-05-16 2020-06-03 2020-06-20 2020-06-16 2020-09-30 ment otective Googles through BFP ET-MOH-179350-GO-DIR / Pr Medical Supplies and Equip ocurement of Medical Equip IDA / 65870 Post Direct Selection Direct 14,213,616.50 9,361,850.00 Terminated 2020-06-15 2020-07-01 2020-06-20 2020-07-06 2020-07-25 2020-08-22 2021-01-21 ment ment from EPSA ET-MOH-179354-GO-DIR / Pr Medical Supplies and Equip IDA / 65870 Post Direct Selection Direct 3,562,466.54 8,634,433.86 Terminated 2020-06-15 2020-07-01 2020-06-20 2020-07-06 2020-07-25 2020-08-22 2021-01-21 ocurement of PPE from EPSA ment ET-MOH-182221-GO-RFQ / R Quarantine, Isolation and Tr Request for Quota Single Stage - One E enovation of quarantine in S IDA / 65870 Post Limited 227,970.00 0.00 Canceled 2020-07-04 2020-08-29 2020-10-30 eatment Centers tions nvelope NNP region- South Omo Kaku ta Site ET-MOH-182224-GO-RFQ / R Quarantine, Isolation and Tr Request for Quota Single Stage - One E enovation of Isolation Centre IDA / 65870 Post Limited 295,000.00 0.00 Canceled 2020-07-04 2020-08-29 2020-10-30 eatment Centers tions nvelope in Oromia Region-Jimma ET-MOH-182226-GO-RFQ / R Quarantine, Isolation and Tr Request for Quota Single Stage - One E enovation of Isolation Centre IDA / 65870 Post Limited 295,000.00 0.00 Canceled 2020-07-04 2020-08-29 2020-10-30 eatment Centers tions nvelope in Beneshangul Gumz Region -Assosa ET-MOH-182228-GO-RFQ / R Quarantine, Isolation and Tr Request for Quota Single Stage - One E enovation of Isolation Centre IDA / 65870 Post Limited 295,000.00 0.00 Canceled 2020-07-04 2020-08-29 2020-10-30 eatment Centers tions nvelope in Dire Dawa -Dire Dawa Cit y ET-MOH-182229-GO-RFQ / R Quarantine, Isolation and Tr Request for Quota Single Stage - One E enovation of quarantine in A IDA / 65870 Post Limited 227,975.00 0.00 Canceled 2020-07-04 2020-08-29 2020-10-30 eatment Centers tions nvelope mhara region-Metema 1Site ET-MOH-182230-GO-RFQ / R Quarantine, Isolation and Tr Request for Quota Single Stage - One E enovation of Isolation Centre IDA / 65870 Post Limited 295,000.00 0.00 Canceled 2020-07-04 2020-08-29 2020-10-30 eatment Centers tions nvelope in SNNP Region-Hawasa Tow n ET-MOH-182231-GO-RFQ / C Quarantine, Isolation and Tr Request for Quota Single Stage - One E onstruction of Point of Entry i IDA / 65870 Post Limited 295,000.00 0.00 Canceled 2020-07-04 2020-08-29 2020-10-30 eatment Centers tions nvelope n Tigray Region-Lugdi ET-MOH-182234-GO-RFQ / R enovation of quarantine in B Quarantine, Isolation and Tr Request for Quota Single Stage - One E IDA / 65870 Post Limited 227,975.00 0.00 Canceled 2020-07-04 2020-08-29 2020-10-30 eneshangul Gumz Region- Be eatment Centers tions nvelope nishangul Kumruk ET-MOH-182235-GO-RFQ / R Quarantine, Isolation and Tr Request for Quota Single Stage - One E enovation of Isolation Centre IDA / 65870 Post Limited 295,000.00 0.00 Canceled 2020-07-04 2020-08-29 2020-10-30 eatment Centers tions nvelope in Harari Region-Harari Town ET-MOH-182236-GO-RFQ / C Quarantine, Isolation and Tr Request for Quota Single Stage - One E onstruction of Point of Entry i IDA / 65870 Post Limited 295,000.00 0.00 Canceled 2020-07-04 2020-08-29 2020-10-30 eatment Centers tions nvelope n Somali Region-Togo Wucha le ET-MOH-182237-GO-RFQ / R Quarantine, Isolation and Tr Request for Quota Single Stage - One E enovation of of quarantine n IDA / 65870 Post Limited 227,975.00 0.00 Canceled 2020-07-04 2020-08-29 2020-10-30 eatment Centers tions nvelope Tigray region-Mekele Dima Si te ET-MOH-182238-GO-RFQ / C Quarantine, Isolation and Tr Request for Quota Single Stage - One E onstruction of Point of Entry i IDA / 65870 Post Limited 295,000.00 0.00 Canceled 2020-07-04 2020-08-29 2020-10-30 eatment Centers tions nvelope n Beneshangul Gumz Region- Kumruk ET-MOH-182239-GO-RFQ / C Quarantine, Isolation and Tr Request for Quota Single Stage - One E onstruction of Point of Entry i IDA / 65870 Post Limited 295,000.00 0.00 Canceled 2020-07-04 2020-08-29 2020-10-30 eatment Centers tions nvelope n Oromia Region-Moyale ET-MOH-182240-GO-RFQ / R Quarantine, Isolation and Tr Request for Quota Single Stage - One E enovation of Isolation Centre IDA / 65870 Post Limited 295,000.00 0.00 Canceled 2020-07-04 2020-08-29 2020-10-30 eatment Centers tions nvelope in Afar Region-Semera Town ET-MOH-182241-GO-RFQ / R Quarantine, Isolation and Tr Request for Quota Single Stage - One E enovation of quarantine in S IDA / 65870 Post Limited 227,975.00 0.00 Canceled 2020-07-04 2020-08-29 2020-10-30 eatment Centers tions nvelope omali Region-Togo Chale ET-MOH-182242-GO-RFQ / R Quarantine, Isolation and Tr Request for Quota Single Stage - One E enovation of Isolation Centre IDA / 65870 Post Limited 295,000.00 0.00 Canceled 2020-07-04 2020-08-29 2020-10-30 eatment Centers tions nvelope in Addis Ababa-Basha Wolde site ET-MOH-182244-GO-RFQ / R Quarantine, Isolation and Tr Request for Quota Single Stage - One E enovation of quarantine in IDA / 65870 Post Limited 227,975.00 0.00 Canceled 2020-07-04 2020-08-29 2020-10-30 eatment Centers tions nvelope Gambela region-GambelaLar e ET-MOH-182245-GO-RFQ / R Quarantine, Isolation and Tr Request for Quota Single Stage - One E enovation of Isolation Centre IDA / 65870 Post Limited 295,000.00 0.00 Canceled 2020-07-04 2020-08-29 2020-10-30 eatment Centers tions nvelope in Amhara Region- Bahir Dar City ET-MOH-182246-GO-RFQ / R Quarantine, Isolation and Tr Request for Quota Single Stage - One E enovation of quarantine in A IDA / 65870 Post Limited 227,975.00 0.00 Canceled 2020-07-04 2020-08-29 2020-10-30 eatment Centers tions nvelope far region-Ethio- Semera Tow n ET-MOH-182247-GO-RFQ / R Quarantine, Isolation and Tr Request for Quota Single Stage - One E enovation of Isolation Centre IDA / 65870 Post Limited 295,000.00 0.00 Canceled 2020-07-04 2020-08-29 2020-10-30 eatment Centers tions nvelope in Somali Region-Jigjiga Airp ort ET-MOH-182249-GO-RFQ / R Quarantine, Isolation and Tr Request for Quota Single Stage - One E enovation of Isolation Centre IDA / 65870 Post Limited 295,000.00 0.00 Canceled 2020-07-04 2020-08-29 2020-10-30 eatment Centers tions nvelope in Tigray Region-Mekele Airp ort ET-MOH-182251-GO-RFQ / R Quarantine, Isolation and Tr Request for Quota Single Stage - One E enovation of Isolation Centre IDA / 65870 Post Limited 295,000.00 0.00 Canceled 2020-07-04 2020-08-29 2020-10-30 eatment Centers tions nvelope in GambelaRegion-Gambela City ET-MOH-182252-GO-RFQ / R Quarantine, Isolation and Tr Request for Quota Single Stage - One E enovation of quarantine in IDA / 65870 Post Limited 227,975.00 0.00 Canceled 2020-07-04 2020-08-29 2020-10-30 eatment Centers tions nvelope Oromia region-Ethio-Kenya B ole Site Page 4 ET-MOH-182254-GO-RFQ / C Quarantine, Isolation and Tr Request for Quota Single Stage - One E onstruction of Point of Entry i IDA / 65870 Post Limited 295,000.00 0.00 Canceled 2020-07-04 2020-08-29 2020-10-30 eatment Centers tions nvelope n Somali Region-Daale ET-MOH-182255-GO-RFQ / R Quarantine, Isolation and Tr Request for Quota Single Stage - One E enovation of quarantine in D IDA / 65870 Post Limited 227,975.00 0.00 Canceled 2020-07-04 2020-08-29 2020-10-30 eatment Centers tions nvelope ire DawaCity-DewoleLandpor t site ET-MOH-199154-GO-DIR / Pr Medical Supplies and Equip ocurement of Gloves and cyli IDA / 65870 Post Direct Selection Direct 6,500,000.00 6,431,322.06 Completed 2020-10-12 2020-07-21 2020-10-17 2020-07-21 2020-11-21 2020-08-11 2021-02-28 2022-05-12 ment nders with 20L & 50L oxygen from EPSA ET-MOH-199155-GO-DIR / Pr Medical Supplies and Equip ocurement of surgical and N9 IDA / 65870 Post Direct Selection Direct 8,650,000.00 8,634,433.86 Completed 2020-10-12 2020-07-21 2020-10-17 2020-07-21 2020-11-21 2020-08-11 2021-03-31 2021-05-21 ment 5 masks from EPSA ET-MOH-231833-GO-DIR / Su pply and Installation of Oxyg Quarantine, Isolation and Tr Under Imple IDA / 65870 Post Direct Selection Direct 1,100,000.00 0.00 2021-05-05 2021-08-12 2021-05-10 2021-06-14 2021-12-11 en Plants and Maintenance of eatment Centers mentation Existing Oxygen Plants ET-MOH-241005-GO-RFB / Pr Medical Supplies and Equip Single Stage - One E Pending Impl ocurement of Vaccine Labora IDA / D7910 Post Request for Bids Open - National 1,070,000.00 0.00 2022-07-05 2022-07-10 2022-08-21 2022-08-31 2022-10-27 2022-12-31 ment nvelope ementation tory furnishing (office furnitur e) ET-MOH-241014-GO-RFB / Di Preparedness, Capacity Buil Single Stage - One E Pending Impl gitizing with IT system (Hard IDA / D7910 Post Request for Bids Open - National 590,000.00 0.00 2021-08-02 2021-08-07 2021-09-18 2021-10-18 2021-11-22 2021-12-31 ding and Training nvelope ementation ware and Networking) ET-MOH-241026-GO-RFB / Pr Medical Supplies and Equip Single Stage - One E Pending Impl ocurement of Equipment for IDA / D7910 Post Request for Bids Open - National 530,000.00 0.00 2021-07-20 2021-07-25 2021-09-05 2021-10-05 2021-11-09 2021-12-31 ment nvelope ementation animal husbandry house ET-MOH-241039-GO-DIR / Pr ocurement of 25 Vehicles for Project Implementation and IDA / D7910 Post Direct Selection Direct 2,670,000.00 0.00 Canceled 2021-07-08 2021-07-13 2021-08-17 2022-02-13 Covid-19 supply chain Regula Monitoring tion and management ET-MOH-241056-GO-RFQ / Pr ocurement of 15 tablets for C Project Implementation and Request for Quota Single Stage - One E Under Imple IDA / D7910 Post Limited 60,000.00 0.00 2021-08-02 2022-10-28 2021-09-27 2021-10-31 ovid-19 supply chain Regulati Monitoring tions nvelope mentation on and management ET-MOH-241071-GO-RFQ / Pr ocurement one software for Preparedness, Capacity Buil Request for Quota Single Stage - One E Pending Impl IDA / D7910 Post Limited 14,000.00 0.00 2022-01-10 2022-03-07 2022-06-30 Eris (Develop and Integrate V ding and Training tions nvelope ementation accine regulatory information system into eRIS,) ET-MOH-241075-GO-DIR / Pri Preparedness, Capacity Buil IDA / D7910 Post Direct Selection Direct 15,000.00 0.00 Canceled 2021-07-05 2021-10-26 2021-07-10 2021-10-27 2021-08-14 2021-11-30 nting of AEFI tools ding and Training ET-MOH-240986-GO-DIR / Pr ocurement of COVID-19 Vacc Medical Supplies and Equip IDA / D7910 Prior Direct Selection Direct 27,000,000.00 26,855,990.08 Signed 2021-08-06 2021-08-13 2021-08-11 2021-08-17 2021-11-05 2021-08-26 2022-07-26 ine and associated supplies f ment or 4% of the total population ET-MOH-240991-GO-DIR / Pr ocurement of medical Suppli Medical Supplies and Equip IDA / D7910 Post Direct Selection Direct 820,000.00 0.00 Canceled 2021-07-05 2021-07-10 2021-11-07 2022-07-22 es (Surgical Mask and Alcoho ment l based hand sanitizer) ET-MOH-241065-GO-DIR / Pr ocurement of M&E tools pri nting (Tally sheets, reporting and recording materials, che Preparedness, Capacity Buil IDA / D7910 Post Direct Selection Direct 2,435,000.00 1,646,147.16 Signed 2021-08-24 2021-08-11 2021-08-29 2021-08-12 2021-10-03 2021-09-08 2022-02-13 ck list, vaccination cardsc Pri ding and Training nting materials for Communi cation (Banner, brochure, job aid, graphic designs) and Pri nting of AEFI tools ET-MOH-241061-GO-DIR / Pr ocurement of Printing materi Preparedness, Capacity Buil IDA / D7910 Post Direct Selection Direct 1,050,000.00 0.00 Canceled 2021-07-20 2021-07-25 2021-08-29 2021-12-31 als for Communication (Bann ding and Training er, brochure, job aid, graphic designs) ET-MOH-240996-GO-DIR / Pr ocurement of Medical equip ment's (Ice pack freezers, Re Medical Supplies and Equip frigerators, Passive transport IDA / D7910 Prior Direct Selection Direct 32,320,000.00 32,756,781.06 Signed 2021-08-31 2021-09-08 2021-09-05 2021-10-07 2021-10-20 2022-04-09 2022-01-20 ment ation devices and Spare Part s- CCEs) and Procurement of medical Supplies (Surgical M ask and Alcohol based hand sanitizer ET-MOH-246942-GO-DIR / Pr Medical Supplies and Equip ocurement of COVID 19 Vacci IDA / D7910 Prior Direct Selection Direct 53,700,000.00 0.00 Canceled 2021-08-25 2021-08-30 2021-10-04 2022-04-02 ment ne and associated supplies ET-MOH-259205-GO-DIR / Pr ocurement of 30 Vehicles for Project Implementation and IDA / D7910 Post Direct Selection Direct 2,670,000.00 1,189,338.00 Completed 2021-11-01 2021-11-30 2021-11-06 2021-12-02 2021-12-11 2021-12-27 2022-06-09 2022-11-01 Covid-19 supply chain Regula Monitoring tion and management ET-MOH-241028-GO-RFB / Pr Medical Supplies and Equip Open - Internationa Single Stage - One E Under Imple ocurement of Physical and Mi IDA / D7910 Prior Request for Bids 3,200,000.00 0.00 2021-12-01 2023-02-07 2021-12-06 2023-03-31 2022-01-17 2022-02-16 2022-03-23 2023-01-02 ment l nvelope mentation crobiological testing equipme nt ( Lot based) ET-MOH-241033-GO-RFB / Pr Medical Supplies and Equip Open - Internationa Single Stage - One E Under Imple ocurement of Chemical, Purit IDA / D7910 Prior Request for Bids 4,800,000.00 0.00 2021-12-01 2023-02-06 2021-12-06 2023-03-31 2022-01-17 2022-02-16 2022-03-23 2023-10-28 ment l nvelope mentation y and Potency Equipment ( L ot based) ET-MOH-173309-GO-RFQ / Pr Quarantine, Isolation and Tr Request for Quota Single Stage - One E ocurement of Furniture for re IDA / 65870 Post Open - National 185,357.00 0.00 Canceled 2020-06-05 2020-07-31 2021-01-27 eatment Centers tions nvelope novated Facilities ET-MOH-301305-GO-DIR / Pr Medical Supplies and Equip Under Imple ocurement of ICU medical eq IDA / D9550 Prior Direct Selection Direct 9,000,000.00 0.00 2022-07-31 2022-11-23 2022-08-05 2022-09-09 2023-03-08 ment mentation uipment's for 20 facilities Page 5 ET-MOH-328230-GO-DIR / Pr ocurement of medicines and Medical Supplies and Equip Direct - Internation Under Imple medical supplies for conflict IDA / D9550 Prior Direct Selection 6,164,414.00 0.00 2022-11-30 2022-12-10 2022-12-05 2023-01-12 2023-01-09 2023-07-08 ment al mentation affected areas of the Norther n Regions through UNICEF ET-MOH-332037-GO-DIR / Pr ocurement of Medical Equip ment and related supplies a Medical Supplies and Equip Direct - Internation Under Imple nd PSA plant with medical gr IDA / D7910 Prior Direct Selection 20,898,027.00 0.00 2022-12-30 2023-01-30 2023-01-04 2023-02-08 2023-08-07 ment al mentation ade oxygen, medical air, and vacuum Plants for 9 hospitals with 2 years’ service agreem ent through UNICEF ET-MOH-331691-GO-DIR / Pr ocurement of Medical Equip ment for Health centre, Healt Medical Supplies and Equip Open - Internationa Single Stage - One E Pending Impl IDA / D7910 Prior Request for Bids 16,902,490.27 0.00 2023-01-20 2023-01-25 2023-03-08 2023-04-07 2023-05-12 2023-11-08 h Post and Health Extension ment l nvelope ementation Workers outreach program a nd Imaging and Emergency Equipment ( lot based) ET-MOH-337973-GO-RFB / Pr ocurement of medical equip Medical Supplies and Equip Open - Internationa Single Stage - One E Pending Impl IDA / D7910 Prior Request for Bids 29,217,595.00 0.00 2023-02-28 2023-03-05 2023-04-16 2023-05-16 2023-06-20 2023-12-17 ment for (primary hospitals, ment l nvelope ementation health centers and OR Blocks ) ET-MOH-337979-GO-RFB / Pr ocurement of basic emergen Medical Supplies and Equip Open - Internationa Single Stage - One E Pending Impl IDA / D7910 Prior Request for Bids 6,890,000.00 0.00 2023-02-28 2023-03-05 2023-04-16 2023-05-16 2023-06-20 2023-12-17 cy equipment for 370 hospita ment l nvelope ementation ls, ultrasound and burn equip ment ET-MOH-337985-GO-DIR / Pr Medical Supplies and Equip Direct - Internation Pending Impl ocurement of medical equip IDA / D7910 Prior Direct Selection 12,117,139.00 0.00 2023-02-10 2023-02-15 2023-03-22 2023-09-18 ment al ementation ment and related supplies for 10 ICU ET-MOH-337987-GO-DIR / pr Preparedness, Capacity Buil Direct - Internation Under Imple ocurement of vehicles( mobil IDA / D7910 Prior Direct Selection 19,910,612.13 0.00 2023-02-08 2023-04-03 2023-02-13 2023-04-05 2023-03-20 2023-09-16 ding and Training al mentation e clinics and ambulances) ET-MOH-337988-GO-DIR / Pr ocurement of vehicles & mot Preparedness, Capacity Buil Direct - Internation Under Imple IDA / D5940 Prior Direct Selection 15,192,172.62 0.00 2023-02-08 2023-04-07 2023-02-13 2023-04-11 2023-03-20 2023-09-16 orbikes( hard top, pickup, mi ding and Training al mentation nibus,coaster and city bus wi th 65 seasts) ET-MOH-351346-GO-DIR / Pr Preparedness, Capacity Buil Direct - Internation Pending Impl IDA / D7910 Post Direct Selection 480,000.00 0.00 2023-03-25 2023-03-30 2023-05-04 2023-10-31 ocurement of Laptops ding and Training al ementation ET-MOH-355020-GO-RFB / Pr Preparedness, Capacity Buil Single Stage - One E Pending Impl IDA / D7910 Post Request for Bids Open - National 530,000.00 0.00 2023-04-30 2023-05-05 2023-06-16 2023-07-16 2023-08-20 2024-02-16 ocurement of IT Equipment ding and Training nvelope ementation ET-MOH-354708-GO-RFB / Pr ocurement of Supply, Installa Preparedness, Capacity Buil Open - Internationa Single Stage - One E Pending Impl tion, Training and commissio IDA / D7910 Prior Request for Bids 1,502,697.00 0.00 2023-04-30 2023-05-05 2023-06-16 2023-07-16 2023-08-20 2024-02-16 ding and Training l nvelope ementation ning of modular data center i nfrastructure projects on a T urnkey basis NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ET-MOH-197708-NC-DIR / Pr Medical Supplies and Equip UN Agencies (Dire ocurement service from WFP IDA / 65870 Post Direct 108,705.00 108,702.89 Completed 2020-10-06 2020-08-05 2020-10-11 2020-08-06 2020-11-15 2020-09-02 2021-05-14 2020-09-28 ment ct) for BFP contract to MOH ET-MOH-241068-NC-RFQ / Pr Preparedness, Capacity Buil Request for Quota Single Stage - One E ocurement of services(Media IDA / D7910 Post Limited 220,000.00 0.00 Canceled 2021-07-16 2021-09-10 2023-12-31 ding and Training tions nvelope spot service) ET-MOH-241072-NC-RFQ / R Medical Supplies and Equip Request for Quota Single Stage - One E Pending Impl ecruit vaccine testing Labora IDA / D7910 Post Limited 100,000.00 0.00 2021-10-06 2021-12-01 2022-03-31 ment tions nvelope ementation tory service providers ET-MOH-272778-NC-DIR / Pr Preparedness, Capacity Buil Pending Impl ocurement of services(Media IDA / D7910 Post Direct Selection Direct 120,000.00 0.00 2022-01-25 2022-01-30 2022-03-06 2022-09-02 ding and Training ementation spot service) ET-MOH-317159-NC-DIR / Im Preparedness, Capacity Buil Direct - Internation plementation of COVID-19 E IDA / E0640 Prior Direct Selection 4,987,583.00 4,987,583.00 Signed 2022-10-10 2022-09-22 2022-10-15 2022-09-24 2022-11-19 2022-10-08 2023-05-18 ding and Training al mergency Response in Tigra y Region (TPI) ET-MOH-330385-NC-DIR / Pr ocurement of M&E tools pri Preparedness, Capacity Buil Direct - Internation Pending Impl IDA / D7910 Post Direct Selection 1,061,520.00 0.00 2022-12-25 2022-12-30 2023-02-03 2023-08-02 nting (Tally sheets, vaccinati ding and Training al ementation on cards and Printing of AEFI tools) CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ET-MOH-343852-CS-QCBS / Recruitment of consultant fir Quarantine, Isolation and Tr Quality And Cost- Open - Internationa Under Implement m to design, supervise and c IDA / D7910 Prior 800,000.00 0.00 2023-02-28 2023-05-03 2023-03-21 2023-05-04 2023-06-01 2023-07-01 2023-08-05 2023-09-09 2024-09-08 eatment Centers Based Selection l ation ommissioning of the vaccine manufacturing building const ruction ET-MOH-348664-CS-QCBS / Consultancy service to cond Quarantine, Isolation and Tr Quality And Cost- Open - Internationa Pending Impleme IDA / D7910 Post 100,000.00 0.00 2023-03-31 2023-04-21 2023-06-04 2023-07-02 2023-08-01 2023-09-05 2023-10-10 2024-10-09 uct interior architectural desi eatment Centers Based Selection l ntation gn and furnishing of the com plex building INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Page 6 Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ET-MOH-241057-CS-CDS / R ecruitment of TAs for the Na Project Implementation and IDA / D7910 Post Direct Selection Direct 1,540,000.00 1,540,000.00 Completed 2021-07-01 2021-08-13 2021-07-11 2021-10-18 2021-09-14 2021-10-21 2022-06-30 2023-06-17 tional, Regional and Zonal le Monitoring vel to support the COVID vac cine deployment ET-MOH-300094-CS-CDS / R ecruitment of technical Assist Project Implementation and IDA / D9550 Prior Direct Selection Direct 4,787,144.00 0.00 Signed 2022-07-15 2022-08-04 2022-07-25 2022-09-05 2022-09-28 2023-03-27 ants to MoH, Regions and Zo Monitoring nes ( through UNICEF). Page 7 PROCUREMENT PLAN (Textual Part) Project information: OECS Regional Health Project P168539 , Commonwealth of Dominica, Grenada, Saint Lucia, Saint Vincent, Caribbean Public Health Agency (CARPHA) and the OECS Commission Project Implementation agencies: MoH StL, MoH SVG, MoH Grenada, MoH Domonica, CARPHA & OECS Commission Date of the Procurement Plan: [01-24-2020] Period covered by this Procurement Plan: 01/24/2020-01-24/2022 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Not Applicable Other Relevant Procurement Information. 1. Procurement Plan for the Project- St. Lucia Type of Contract Ref. Selection Me Contract Signing . Activity Description Procurem Completion Date No. thod Date (Planned) ent (Planned) Establish National Standards for the implementation and use of an independent 1 1.01 quality control mechanism Consultant CQS 15 Feb 2020 15 Aug 2020 for physical infrastructure and internal finishing of health facilities. Type of Contract Ref. Selection Me Contract Signing . Activity Description Procurem Completion Date No. thod Date (Planned) ent (Planned) SMART Health Facilities 2 Works RFB (National) 15 Jan 2020 15 Jan 2023 1.02 Retrofitting a. Design and Supervision Consultant CQS 15 Jan 2020 15 Jan 2023 RFQ 3 Laboratory Infrastructure Goods/ICT 15 Mar 2020 15 Jun 2020 (International) 1.03 Capacity Building (Food Consultant CQS 15 Mar 2020 15 Jun 2020 Safety) 9 1.08 Specimen Transportation Goods/ICT RFQ (National) 15 Jul 2021 15 Dec 2022 10 2.1 Lab Data Management Tool Goods/ICT RFQ (National) 15 Apr 2020 15 Jun 2021 4 Medical Technologists 11 2.2 Training NA TBD TBD (Training Skills) 2 Pathologists (Training 12 3 Training NA TBD TBD Skills) 2 Histotechnologists 13 3 Training NA TBD TBD (Training Skills) 14 3 Lab Disaster Management Training NA TBD TBD Training for Capacity Type of Contract Ref. Selection Me Contract Signing . Activity Description Procurem Completion Date No. thod Date (Planned) ent (Planned) Building/skills for laboratory staff RFQ 17 2.03 Food safety equipment Goods/ICT 15 Apr 2020 15 Jun 2021 (International) Health and Safety RFQ 18 2.04 improvement in the Goods/ICT 15 Apr 2020 15 Jun 2021 (International) workplace (equipment) Vector Control Programme – Capacity Building for Vector Control Officers in Vector Consultant CQS 15 Jun 2021 15 Jul 2022 Management and Surveillance Capacity Building for 19 2.05 Community Groups and Local Consultant CQS Government Procurement of Essential equipment to support and RFQ implement the vector control Goods/ICT 15 Aug 2020 15 Dec 2021 (International) programme (Entomology Laboratory) Type of Contract Ref. Selection Me Contract Signing . Activity Description Procurem Completion Date No. thod Date (Planned) ent (Planned) 2.08 Capacity building at Ports of Consultant CQS 15 Jun 2021 15 Jul 2022 a Entry – Training 22 2.08 Capacity Building at Ports of Goods/ICT RFQ (National) 15 Aug 2020 15 Dec 2021 b Entry – Equipment Finalization and Implementation of the 2.09 national health disaster Consultant CQS 15 Jan 2021 15 Jun 2022 a management plan – Consultancy on Comm. 23 Finalization and implementation of the 2.10 national health disaster Goods/ICT RFQ (National) 15 Mar 2021 15 Jun 2022 b management plan – Equipment 25 2.11 Hearse Goods/ICT RFQ (National) 15 Feb 2020 15Apr 2021 Caribbean Field Epidemiology RFQ (National) and Laboratory Training 15 Feb 2022 Goods/ICT 15 Feb 2020 Programme (Cr-FELTP) Frontline Training Caribbean Field Epidemiology Goods/ICT RFQ (National) 15 Feb 2020 15 Feb 2022 and Laboratory Training Type of Contract Ref. Selection Me Contract Signing . Activity Description Procurem Completion Date No. thod Date (Planned) ent (Planned) Programme (Cr-FELTP) Level 1 Training Project Management 26 3.01 Operational Expensed NA NA Total project cost 2. Procurement Plan for the Project- OECS Commission Re Type of Contract Contract f. Selection Me No Activity Description Procurem Signing Date Completion Date No thod ent (Planned) (Planned) . Consultancy for Health Facilities Inventory- Inventory of All Emergency/ Urgent Care Facilities in Consultant 1.1 CQS 22-Feb-20 18-Nov-20 four Countries and Emergency and Services Critical Care Services- Procurement of Software for 1.2 Database of Inventory and for GIS Goods RFQ 8-Feb-20 08-May-20 Mapping Lab Transport System Assessment and Action Plan for implementation of Consultant 1.3 IC 16-Oct-19 12-Apr20 agreements, policy and legislation Services (PPA Activity) Development and Implementation of Lab transportation Agreements and Consultant 1.4 QCBS 13-Nov-20 8-Nov-21 Policies Services OECS Pharmaceutical Facility - Support for Existing Software Direct 1.5 Goods 8-Feb-20 08-May-20 Development Selection Re Type of Contract Contract f. Selection Me No Activity Description Procurem Signing Date Completion Date No thod ent (Planned) (Planned) . Initiative for implementation of policy Consultant Direct 1.7 10-Mar-20 5-Mar-21 and legislation - CMLF Services Selection Development of Resource budgets and plans for Countries to meet LQMS Consultant Direct 1.8 7-Oct-19 5-Jan-20 Tier 1 and Tier 2 Requirements – Services Selection CMLF (PPA Activity) Development of relevant Policies and Legislation to facilitate the OECS Consultant 2.1 CQS 26-May-20 21-May-21 Unique ID Services Regional Public Education Campaign Risk Assessment and Action Plan for Implementation of OECS Unique ID Consultant 2.2 CQS 26-Oct-19 24-Jan-20 linked to a Unique Health Identifier Services (PPA Activity) Complete Risk Assessment and Develop and Action Plan for OECS Consultant 2.3 CQS 28-Mar-21 26-Jul-21 Health Emergency Services Services Coordinating Mechanism Prepositioned contract development Consultant 2.4 CQS 26-Jan-20 24-Jun-20 assignment Services Re Type of Contract Contract f. Selection Me No Activity Description Procurem Signing Date Completion Date No thod ent (Planned) (Planned) . Procurement of software to manage 2.5 Goods RFB 15-Mar-20 05-Nov-20 pre-positioned contracts Consultancy for Assessment of Registration Process and Requirement Consultant 2.6 ICS 1-Apr-20 30-Jun-20 for Software to Facilitate Services Harmonisation Web-based platform for registration 2.7 of Health Professional (Consultancy to Goods RFB 12-Oct-20 9-Feb-21 undertake assessment $48,000) Training 2.8 Training NA Meeting for harmonization of 2.9 Registration Requirements for Health Workshop NA professional PIU Staff (Project Manager, IC / Direct Procurement Officer, Accountant, Consultant Selection 3.1 1-Nov-19 30-Oct-22 Project Assistant) Services Multiple 3.2 Procurement of Office Equipment Goods RFQ 8-Sep-19 6-Jan-20 Re Type of Contract Contract f. Selection Me No Activity Description Procurem Signing Date Completion Date No thod ent (Planned) (Planned) . 3.3 Procurement of Office Furniture Goods RFQ 8-Sep-19 6-Jan-20 Procurement of Office Supplies 3.4 Goods RFQ 8-Sep-19 6-Jan-20 Retrofitting of existing office building 3.5 Works RFQ 8-Sep-19 7-Dec-19 Procurement of Audit Firm to Consultant 3.6 undertake Project Audit LCS 20-Nov-20 4-Jan-21 Services Operating Expenses 3.7 NA NA NA NA Total 3. Procurement Plan for the Project- Dominica No Re Activity Description Type of Selection Contract Contract Completion Date . f. Procure Signing Date (Planned) Method No ment (Planned) . 1 Upgrade works for 3 health centres - Castle Bruce (800k) + St Joseph ($700k) + Wesley ($500k): -Extension of physical structure & construction of additional rooms (Wesley only) Design/supervision Consulta CQS 15-Dec-19 30-Apr-22 ncy Works Works RFB 15-Apr-20 15-Apr-21 (National) Furniture/equipment Goods RFQ 15-Mar-21 15-Apr-21 (National) 2 Community outreach, printed Goods RFQ TBD TBD material, rental of PA System, etc. (National) 3 Biomedical Waste Management; Goods RFQ TBD TBD improvement for resiliency: (Internatio nal) Purchase of waste management vehicle to transport biomedical waste No Re Activity Description Type of Selection Contract Contract Completion Date . f. Procure Signing Date (Planned) Method No ment (Planned) . 4 Biomedical Waste Management; Goods RFQ TBD TBD improvement for resiliency: (National) Improve Storage of Biomedical Waste at sites including purchase refrigerators 5 Biomedical Waste Management; Training TBD improvement for resiliency: Training of medical staff to handle biomedical waste management 6 Upgrade laboratory facility and Goods RFQ TBD TBD capacity by equipping district (National) hospital lab in Portsmouth, Marigot, La Plaine & Grand Bay Expand testing and support with diagnostic capacity (procurement of Purchase analyzers to include handheld systems e.g. i-stat 7 Strengthen laboratory data Goods/IC RFQ TBD TBD management system – Supply and T (National) Installation of additional components of existing Lab Information System (Schuylab); Schuylab Remote Printing, Schuylab web base No Re Activity Description Type of Selection Contract Contract Completion Date . f. Procure Signing Date (Planned) Method No ment (Planned) . 8 Ensure adequate transportation Goods RFQ TBD TBD of laboratory specimen: (National) • Purchase solar refrigerators (2) and regular refrigerators - Main Lab and Portsmouth • sturdy Icebox coolers – Type 3 District Health Centers (7) transportation of samples • shipping containers – Main lab (for shipping samples overseas) 9 Training for managing essential Training TBD Laboratory functions 10 Consultant to Develop and Consulta IC TBD TBD implement Quality Management ncy national System 11 Mapping of prevalence of Goods/IC RFQ TBD TBD communicable diseases - including T (National) vector borne diseases and leptospirosis. Mapping i.e. geocode of No Re Activity Description Type of Selection Contract Contract Completion Date . f. Procure Signing Date (Planned) Method No ment (Planned) . all health facilities and towns/villages/hamlets •Equipment – GPS device (Garmin eTrex 20x GPS), 5qty. •GIS software 12 Training of Mapping i.e. geocode of Training all health facilities and towns/villages/hamlets on the Island 13 Set up and equip situation room Goods/IC RFQ TBD TBD Command Centre Communication T (National) Equipment to include 14 Set up and equip situation Goods/IC RFQ TBD TBD Room/HEOCs/Emergency Command T (National) Centre 15 Strengthen health information Goods/IC RFQ TBD TBD system. Equipment for Health T (National) Information Unit 16 Strengthening public health system Consulta TBD TBD by improving public health ncy IC emergency response to control (Internatio disease outbreaks and surveillance nal) systems No Re Activity Description Type of Selection Contract Contract Completion Date . f. Procure Signing Date (Planned) Method No ment (Planned) . 17 Health Emergency Preparedness plan Consulta IC National TBD TBD ncy 18 Project Officer for implementation Consulta IC TBD TBD (duration of the project) ncy National 19 Short Service Contracts in: Consulta IC National TBD TBD ncy • Procurement (when required) • Audit (annually) • Environmental safeguard Multiple (during retrofitting) TOTAL 4. Procurement Plan for the Project- St. Vincent Contract Contract Type of Signing Activity Description Selection Method Completion Date Procurement Date (Planned) (Planned) COMPONENT 1 Upgrade works for priority health facilities based on PAHO Smart Hospital criteria including Contract Contract Type of Signing Activity Description Selection Method Completion Date Procurement Date (Planned) (Planned) renovations, and retrofitting, furniture & equipment Design/supervision Consultancy CQS 15-Dec-19 30-Apr-22 Upgrade Works- Works RFB (National) 15-Apr-20 15-Apr-21 Furniture/equipment Goods RFQ (National) 15-Mar-21 15-Apr-21 Lab Equipment Goods RFQ (National) 15-Mar-21 15-Apr-21 Construction/Create a Public Health Laboratory Design/supervision - 50000 Consultancy CQS 15-Dec-19 30-Apr-22 Works - 1475000 Works RFB (National) 15-Apr-20 15-Apr-22 Public health Laboratory Equipment Goods/ICT RFQ (National) 15-May-21 15-May-22 300000 Furniture & Equipment - 100000 Goods/ICT RFQ (National) 15-May-21 15-May-22 Contract Contract Type of Signing Activity Description Selection Method Completion Date Procurement Date (Planned) (Planned) Strengthened laboratory data management systems - Lab Goods/ICT RFQ (National) 15-May-21 15-May-22 Information System with Health Information System (HIS) Improve the transportation system for laboratory specimens - Cold Goods/ICT RFQ (National) 15-Jul-21 15-Jul-22 chain and laboratory specimen transportation vehicle Strengthen Local capacity to utilize an enhanced regional reference Consultancy CQS 15-Jul-21 15-Jul-22 laboratory Training in Modern Laboratory Technology, Food Safety, Consultancy CQS 15-Jun-21 15-Jun-22 Entomology etc. Implement a regional quality assurance program and develop Consultancy CQS 15-Jun-21 15-Jun-22 common standards for National Laboratories, SVG. Provide training to ensure sufficient human resource capacity for Consultancy CQS 15-May-21 15-May-22 managing essential laboratory functions Contract Contract Type of Signing Activity Description Selection Method Completion Date Procurement Date (Planned) (Planned) Regional Accreditation of laboratories with quality standards Consultancy CQS 15-May-21 15-May-22 and development of quality assurance programs COMPONENT 2 Update/develop protocols (including development of an active case- Consultancy CQS 15-Mar-21 15-Sep-21 finding protocol for vector-borne diseases and clinical protocols) Strengthen health information systems for collection of incidence and prevalence data (HIS) ICT Equipment Goods/ICT RFQ (National) 15-Aug-21 15-Aug-23 Consultancy for ICT assessment, Consultancy CQS 15-Aug-21 15-Aug-23 training - Roll-out Field Epidemiology and Laboratory Training Program Consultancy CQS 15-Nov-19 15-Nov-20 (FELTP) among field-level epidemiologists (as needed) Contract Contract Type of Signing Activity Description Selection Method Completion Date Procurement Date (Planned) (Planned) Develop procedures on disease surveillance and information sharing with regard to infectious disease Consultancy CQS 15-Jan-20 15-Jan-21 protocols - microcephaly testing and confirmation in pregnant women suspected to be Zika infected Develop regional information and communications technology platform for surveillance and Consultancy CQS management, including Geographic Information Systems (GIS) 15-Jan-20 15-Jan-21 Renovation of Health Emergency Disaster Management Unit facility Design and supervision - Consultancy CQS 15-Dec-19 30-Apr-22 Works Works RFB (National) 15-Apr-20 15-Apr-21 EOC Equipment Goods/ICT RFB (National) 15-Apr-20 15-Apr-21 Disaster Supplies &Equipment- Goods/ICT RFB (National) 15-Apr-20 15-Apr-21 Furniture & Fixtures Goods/ICT RFB (National) 15-Apr-20 15-Apr-21 Contract Contract Type of Signing Activity Description Selection Method Completion Date Procurement Date (Planned) (Planned) Emergency Response Equipment Goods/ICT RFB (National) 15-Apr-20 15-Apr-21 Pickup truck (4ton) retrofitted with Goods/ICT RFB (National) 15-Apr-20 15-Apr-21 trailer truck Create external monitoring and assessment of core public health capacities of national structures to Consultancy meet International Health Regulations CQS 15-Jun-20 15-Dec-20 Plan and conduct simulation exercises and training on joint outbreak investigations as part of Consultancy CQS an early warning and response system 15-Jun-20 15-Dec-20 Develop/upgrade curriculum for training of country level health workforce in surveillance and Consultancy response for priority infectious diseases CQS 15-Dec-20 15-May-21 Component 3 Contract Contract Type of Signing Activity Description Selection Method Completion Date Procurement Date (Planned) (Planned) Project Financial Specialist Consultancy IC 1-Feb-20 1-Feb-24 Procurement Specialist Consultancy IC 1-Feb-20 1-Feb-24 Fiduciary capacity building for implementation - MOHWE staff Training trained to an enhanced fiduciary level NA 1-Oct-19 1-Oct-21 Project Monitoring and evaluation of Consultancy project activities IC 1-Oct-19 2-Oct-21 Project Audit Consultancy LCS 1-Feb-20 1-Feb-24 Biohazard Waste Management Plan Consultancy IC 1-Feb-20 1-Feb-23 Environmental and Social Consultancy Management Framework (ESMF) CQS 1-Feb-20 1-Feb-23 Office set up Goods DS 1-Sep-19 1-Dec-19 Operational Expenses N/A N/A TOTAL 5. Procurement Plan for the Project- CARPHA Type of N Activity Selection Me Contract Signing Contract Completion Ref. No. Procure o. Description thod Date (Planned) Date (Planned) ment Laboratory 1 - 2.1 G RFB 30-Sep-19 30-Nov-19 Equipment 1 - 2.1.6 Reagents G Single Source 30-Sep-19 29-Sep-24 Shipping 1 - 4.2.2 G RFQ 31-Jul-19 30-Sep-19 materials 2- Stationery and G RFQ 30-Sep-19 29-Sep-24 1.1.10 printing costs 2- Promotional G RFQ 27-Jul-20 30-Sep-20 1.1.11 materials 2- 3.3d/3.3 IT Goods G RFQ 30-Oct-19 29-Oct-20 f IT equipment for CARPHA; 2 - 1.1.9 country training G RFQ 29-May-20 31-Jul-20 and field projects Maintenance of Laboratory Equi 1 - 2.1.7 30-Sep-19 29-Sep-24 p-ment (New & Existing) NCS RFB Type of N Activity Selection Me Contract Signing Contract Completion Ref. No. Procure o. Description thod Date (Planned) Date (Planned) ment Proficiency testing (PT) programme for OECS 1- (including TR NA 30-Sep-19 30-Sep-24 3.1.1a standards, monitoring and supportive interventions) Perform PT at CARPHA to ensure that the 1- quality of testing NCS Single Source 30-Sep-19 29-Sep-24 3.1.1c services is being maintained and monitored Provide broadband service to 2 - 3.3e NCS RFQ 1-Oct-19 29--aug-24 support increased internet capacity Type of N Activity Selection Me Contract Signing Contract Completion Ref. No. Procure o. Description thod Date (Planned) Date (Planned) ment Type of N Activity Selection Me Contract Signing Contract Completion Ref. No. Procure o. Description thod Date (Planned) Date (Planned) ment Establishment of a regional system for 1 1 - 1.2.5 CS Single Source 30-Sep-19 14-Oct-19 validation of equipment and methods Software: Inform ation management 2 1 - 2.2.1 capacity for 25-Aug-21 integrated surveillance approaches CS FBS 26-Feb-21 Support mechanism for 3 1 - 2.2.2 inter-country 29-Jun-21 technical collaboration CS FBS 30-Jun-20 LIMS 4 1 - 2.2.3 Consultant/Deve 29-Oct-21 loper CS CQS 30-Jun-20 Building CARPHA 5 1 - 2.2.4 CS 30-Sep-19 29-Mar-22 LIMS capacity CQS 6 1-6 Communication CS CQS 30-Oct-20 30-Jul-22 products for Type of N Activity Selection Me Contract Signing Contract Completion Ref. No. Procure o. Description thod Date (Planned) Date (Planned) ment laboratory services Level III training 7 2 - 1.1.2 curriculum CS CQS 31-Aug-20 30-Apr-21 development "Train the trainers" progra m to increase 8 2 - 1.1.3 country capacity TR NA 31-Aug-20 30-Apr-21 for FELTP - Hire Training Consultant Upgrade and maintain 9 2 - 1.1.5 capacity for CS CQS 30-Sep-19 29-Sep-24 eLearning Platform - Contracts for 10 2 - 1.1.6 Subject Matter CS CQS 30-Jun-20 31-Aug-21 Experts (SMEs) - Contract for Training 11 2 - 1.1.6 CS CQS 30-Sep-19 31-Aug-20 Development consultant Type of N Activity Selection Me Contract Signing Contract Completion Ref. No. Procure o. Description thod Date (Planned) Date (Planned) ment Independent peer review/assessm ent of CARPHA’s existing 12 2 - 2.1b surveillance CS CQS 30-Jul-19 30-Nov-19 system and its adequacy to fulfil its public health surveillance role In-country support to developing routine reporting structures for 13 2 - 2.1d populating CS CQS 30-Oct-20 29-Oct-22 yearly ministerial report, also known as CMO Report Update and produce CARPHA 14 2 - 2.2a Data CS CQS 30-Oct-19 29-Oct-20 Appreciation and M&E manuals, Type of N Activity Selection Me Contract Signing Contract Completion Ref. No. Procure o. Description thod Date (Planned) Date (Planned) ment materials and tools to support public health surveillance Develop and roll out ICD-11 selection of underlying 15 2 - 2.6 cause of death CS IC 4-Jan-21 30-Oct-21 training towards the strengthening of mortality data Upgrade (to ICD- 11) and enhance, 16 2 - 2.8 CS CQS 2-Mar-21 30-Jun-21 mortality data capture tool (MORTBASE) Morbidity coding training 17 2 - 2.9a workshop to CS IC 1-Nov-20 30-Jun-22 improve morbidity data 18 2 - 3.1a IT Gap analysis, CS CQS 30-Jan-20 30-Mar-20 needs Type of N Activity Selection Me Contract Signing Contract Completion Ref. No. Procure o. Description thod Date (Planned) Date (Planned) ment assessment and architecture design to support CARPHA Regional Surveillance system Draft CARPHA's surveillance platform (using DHIS2) to integrate GIS 19 2 - 3.1 b CS CQS 30-Sep-21 2-Jan-22 and data visualization to enhance real time reporting and feedback DHIS2 platform 20 2 - 3.3a Maintenance of CS CQS 1-Oct-19 29--aug-24 service contract Improve IT capacity at 21 2 - 3.3b CARPHA to host CS CQS 1-Jun-20 30-Nov-20 DHIS-2 installation Type of N Activity Selection Me Contract Signing Contract Completion Ref. No. Procure o. Description thod Date (Planned) Date (Planned) ment Gap analysis on Data sharing interoperability between the selected CMS 22 2 - 3.4 CS CQS 30-Sep-20 29-Oct-21 using CARPHA LIMS and automatically importing data into DHIS2. Development of a mobile app for public health 23 2 - 3.5 alerts and CS CQS 30-Oct-20 29-Oct-21 dissemination of public health information Knowledge 24 2 - 3.6 CS CQS 30-Oct-19 29-Sep-22 Management Development of the action plan 25 2 - 4.2 for regional CS IC 30-Oct-20 30-Jun-21 preparedness and response 26 2 - 4.6 Simulation CS CQS 30-Sep-21 29-Sep-24 Exercise on Type of N Activity Selection Me Contract Signing Contract Completion Ref. No. Procure o. Description thod Date (Planned) Date (Planned) ment responding to public health emergencies Continued Implementation of 27 2 - 5.1 CS CQS 31-Jul-20 31-Jan-21 Communication and Marketing Plan Development of country-level National Action 28 2 - 6 CS QCBS 30-Aug-23 Pan for Health Security (NAPHS) 1-Sep-21 Regional level 29 2 - 7 workshop on JEE TR TR 29-Sep-20 self-evaluation 30-Sep-19 Development and Implementation 30 3 - 3.2.6 of CS CQS Communication Strategy for Increased 30-Sep-19 30-Aug-24 Visibility of Type of N Activity Selection Me Contract Signing Contract Completion Ref. No. Procure o. Description thod Date (Planned) Date (Planned) ment Grant, its outputs and outcomes 31 3 - 3.2.1 Project Officer CS IC 1-Oct-19 30-Sep-24 32 3 - 3.2.1 M&E officer CS IC 1-Oct-19 30-Sep-24 33 3 - 3.2.1 Finance Officer CS IC 1-Oct-19 30-Sep-24 Procurement 34 CS IC Officer 1-Oct-19 30-Sep-24 Total Amount 6. Procurement Plan for the Project- Grenada Re Type of N f. Selection Me Contract Signing Contract Completion Activity Description Procurem o. No thod Date (Planned) Date (Planned) ent . Procurement of upgrade works at 1 Mount Gay Psychiatric Works RFB 4-Jul-20 31-Jul-23 Hospital Re Type of N f. Selection Me Contract Signing Contract Completion Activity Description Procurem o. No thod Date (Planned) Date (Planned) ent . Consultancy to conduct situational analysis to establish Consultan 2 CQS 4-Nov-19 1-Mar-20 baseline for Child & cy Geriatric Mental health Services Procurement of upgrades and refurbishment to the 3 Works RFB 1-Nov-21 29-Jul-22 Isolation Room, ICU of the General Hospital and Rathdune Expansion of 5 Sauteaurs Health Works RFB 1-Mar-22 31-Aug-22 Centre Expansion of St. 6 David's Health Centre Works RFB 11-Jan-21 28-Apr-22 Consultancy to Implement critical Consultan 7 CQS 2-Mar-20 31-Dec-21 health system cy upgrades Re Type of N f. Selection Me Contract Signing Contract Completion Activity Description Procurem o. No thod Date (Planned) Date (Planned) ent . Procurement of equipment for the 9 Goods DS 1-Nov-19 30-Jun-20 upgrade of laboratory facilities Consultancy to Consultan 10 strengthen laboratory IC 1-Nov-19 31-Dec-20 cy information system Procurement of 11 equipment to Goods RFQ (National) 2-Mar-20 31-Dec-20 strengthen LIS Procurement of equipment to improve 12 Goods RFB 2-Mar-20 31-Dec-20 efficiency of lab operations Design and Supervision for the refurbishment of Mount Gay Hospital, Consultan 13 QCBS 5-Apr-20 31-Dec-24 General Hospital cy (Rathdune), Sauteurs and St. David's Health Centres Re Type of N f. Selection Me Contract Signing Contract Completion Activity Description Procurem o. No thod Date (Planned) Date (Planned) ent . Procurement of Furniture and 14 Goods RFB 1-Mar-22 31-Aug-23 Equipment for refurbished buildings Training in 13 Procurement for Staff Training TR 11-Mar-19 31-Jan-20 (Biomedical) Consultancy to provide Short Term IC 1-Jan-20 31-Dec-20 Training for New Lab Consultan 14 Technicians cy Consultancy to provide national training programme DS 1-Sep-20 1-Dec-23 for laboratory Consultan 14 technicians cy Consultancy to strengthen Consultan DS 15 surveillance systems cy 6-Jul-20 1-Jun-23 Re Type of N f. Selection Me Contract Signing Contract Completion Activity Description Procurem o. No thod Date (Planned) Date (Planned) ent . Strengthen Surveillance Systems TR 16 FELTP Training 1 & 2 Training 1-Sep-20 31-Jul-24 Consultancy to provide morbidity and Consultan DS 17 mortality Surveillance cy 1-Feb-21 31-Dec-22 Procurement of Hardware and RFQ software for chronic 18 disease registry Goods 1-Jul-20 31-Dec-20 Consultancy to guide in the development of Consultan IC 19 HEOC cy 1-Jan-20 30-Apr-20 Consultancy and implementation of Consultan IC 20 desktop simulation cy 1-Jan-24 31-Aug-24 Consultancy for the Training of emergency Consultan CQS 21 technicians cy 1-Jan-20 31-Jul-21 Procurement of ambulances, and RFB emergency response 22 vehicles Goods 1-Jan-21 31-Dec-21 Re Type of N f. Selection Me Contract Signing Contract Completion Activity Description Procurem o. No thod Date (Planned) Date (Planned) ent . Procurement of communications RFQ 23 equipment for HEOC Goods 1-Oct-20 30-Jul-21 Procurement of RFQ 24 Computer Equipment Goods 1-Oct-20 30-Jul-21 Procurement of Personal Protective RFQ 25 Equipment Goods 1-Oct-20 31-Dec-21 Training in TR 26 Psychological First Aid Training 1-Sep-20 30-Sep-21 Consultan IC 27 Project Coordinator cy 11-Nov-19 31-Dec-24 Procurement of RFQ 28 Project Vehicle Goods 11-Nov-19 31-Jan-20 Procurement of Computer and RFQ Acceories for Project 29 Office Goods 11-Nov-19 31-Jul-20 Project Operating Cost NA NA NA NA Re Type of N f. Selection Me Contract Signing Contract Completion Activity Description Procurem o. No thod Date (Planned) Date (Planned) ent . 30 Project Visibility NCS RFQ 1-Feb-20 4-Feb-20 Consultan IC 31 Project M & E Officer cy 1-Jan-21 31-Dec-21 Capacity Building for TR 32 Staff Training September,2020 1-Dec-22 Total PROCUREMENT OECS Countries : OECS Regional Health Project PLAN General Information Country: OECS Countries 2020-04-17 Bank’s Approval Date of the Original Procurement Plan: 2023-06-06 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P168539 GPN Date: 2020-05-21 Project Name: OECS Regional Health Project Loan / Credit No: IDA / 64810 Ministry of Health of SVG Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Request for Bids - SVGRHP-W-RFB-1 / Construc Strengthening Public Health Single Stage - One E Small Works SPD Pending Imp 2022-08-2 tion/upgrades of Selected He IDA / 64810 Surveillance and Emergency Post Request for Bids Open - National 500,000.00 0.00 2021-11-08 2021-11-13 2021-12-25 2022-01-24 2022-02-28 nvelope (1 envelope proce lementation 7 alth Facilities Management ss) SVGRHP-W - DC-3C / Electric Contingency Emergency Res Other (with field f Pending Imp 2022-05-2 al and plumbing connection t IDA / 64810 Post Direct Selection Direct 1,006.00 0.00 2022-04-18 2022-04-23 2022-05-14 ponse Component (CERC) or explanation) lementation 8 o laboratory container at Uni on Island. SVGRHP-W-DC-1A / Construc Contingency Emergency Res 2020-12-1 IDA / 64810 Post Direct Selection Direct 100,000.00 0.00 Canceled 2020-05-04 2020-05-09 2020-06-13 tion of Isolation staff hostel ponse Component (CERC) 0 SVGRHP-W-DC-1B / Isolation Contingency Emergency Res 2020-12-1 IDA / 64810 Post Direct Selection Direct 350,000.00 0.00 Canceled 2020-05-04 2020-05-09 2020-06-13 Facility ponse Component (CERC) 0 SVGRHP-W-DC-1C / Ancillary Contingency Emergency Res 2020-12-1 IDA / 64810 Post Direct Selection Direct 160,000.00 0.00 Canceled 2020-05-04 2020-05-09 2020-06-13 Buildings for Isolation Facility ponse Component (CERC) 0 GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SVGRHP-G-RFQ-1 / Purchase Improved Health Facilities a Request for Quota Single Stage - One E Under Imple IDA / 64810 Post Limited 50,000.00 0.00 2020-04-19 2020-04-28 2020-06-14 2020-12-11 of vehicle nd Laboratory Capacity tions nvelope mentation SVGRHP-G-DC-6 / QPCR Rea Contingency Emergency Res Pending Impl IDA / 64810 Post Direct Selection Direct 200,000.00 0.00 2020-04-20 2020-04-25 2020-05-30 2020-11-26 gents and Consumables ponse Component (CERC) ementation SVGRHP-G-DC-5 / Supportin Contingency Emergency Res Under Imple IDA / 64810 Post Direct Selection Direct 20,000.00 0.00 2020-04-20 2020-05-12 2020-04-25 2020-05-12 2020-05-30 2020-11-26 g Equipment - PRC System ponse Component (CERC) mentation SVGRHP-G-DC-4 / Q PRC Sys Contingency Emergency Res IDA / 64810 Post Direct Selection Direct 62,000.00 16,458.10 Signed 2020-04-20 2021-01-11 2020-04-25 2020-03-20 2020-05-30 2020-05-13 2020-11-26 tem ponse Component (CERC) SVGRHP-G-DC-3 / Mobile Isol Contingency Emergency Res IDA / 64810 Post Direct Selection Direct 2,500,000.00 256,241.31 Signed 2020-04-20 2020-11-30 2020-04-25 2020-02-14 2020-05-30 2020-04-02 2020-11-26 ation Units and Tents ponse Component (CERC) SVGRHP-G-DC-2 / Mobile Isol Contingency Emergency Res IDA / 64810 Post Direct Selection Direct 335,000.00 294,976.24 Signed 2020-04-20 2020-11-30 2020-04-25 2020-03-03 2020-05-30 2020-12-01 2020-11-26 ation Chambers and Tents ponse Component (CERC) SVGRHP-G-DC-1 / Isolation F Contingency Emergency Res Under Imple IDA / 64810 Post Direct Selection Direct 500,000.00 0.00 2020-04-22 2020-11-30 2020-04-27 2020-06-01 2020-11-28 acility - Equipment & Furnishi ponse Component (CERC) mentation ng SVGRHP-G-RFB-1 / Supply of Improved Health Facilities a Single Stage - One E Goods - Lab equipment: Com IDA / 64810 Post Request for Bids Open - National 135,000.00 149,327.66 Signed 2020-07-31 2020-11-06 2020-08-05 2020-09-16 2020-12-11 2020-10-16 2021-01-27 2020-11-20 2021-07-09 2021-05-19 nd Laboratory Capacity nvelope munity Level SVGRHP-G-RFQ-2 / Supply of Institutional Capacity Buildin Request for Quota Single Stage - One E Under Imple Goods, furniture and equipm IDA / 64810 g, Project Management and Post Open - National 10,000.00 0.00 2020-09-23 2020-11-18 2021-05-17 tions nvelope mentation ent Coordination SVGRHP-G-DC-11A / Equipm Contingency Emergency Res Under Imple IDA / 64810 Post Direct Selection Direct 5,000.00 0.00 2020-11-24 2021-02-02 2020-11-29 2020-07-24 2021-01-03 2021-07-02 ent to assist in data gatherin ponse Component (CERC) mentation g -laptops SVGRHP-G-DC-11B / COVID - Contingency Emergency Res Under Imple 19 Response - Equipment to IDA / 64810 Post Direct Selection Direct 5,000.00 0.00 2020-11-24 2021-02-02 2020-11-29 2020-07-24 2021-01-03 2021-07-02 ponse Component (CERC) mentation assist in data gathering - Lap tops SVGRHP-G-DC-10 / COVID-1 Contingency Emergency Res Pending Impl 9 Response - Consumables - IDA / 64810 Post Direct Selection Direct 120,000.00 0.00 2020-11-24 2020-11-29 2021-01-03 2021-07-02 ponse Component (CERC) ementation Personal Protective Equipme nt SVGRHP-G-DC-9 / COVID-19 Response - Supporting Equip Contingency Emergency Res Under Revie IDA / 64810 Prior Direct Selection Direct 350,000.00 0.00 2020-11-24 2021-04-28 2020-11-29 2021-01-03 2021-07-02 ment and consumables - Aut ponse Component (CERC) w omated extraction equipmen t SVGRHP-G-DC-8 / COVID-19 Contingency Emergency Res Under Imple Response - Supporting Equip IDA / 64810 Post Direct Selection Direct 200,000.00 0.00 2020-11-24 2021-02-02 2020-11-29 2020-07-08 2021-01-03 2021-07-02 ponse Component (CERC) mentation ment and consumables - Swa bs SVGRHP-G-DC-7 / COVID-19 Contingency Emergency Res Pending Impl Response - Supporting Equip IDA / 64810 Post Direct Selection Direct 325,000.00 0.00 2020-11-24 2020-11-29 2021-01-03 2021-07-02 ponse Component (CERC) ementation ment and consumables - Gen eral Items SVGRHP-G-RFB-2 / Procurem Contingency Emergency Res Single Stage - One E Pending Impl IDA / 64810 Post Request for Bids Open - National 15,000.00 0.00 2021-01-08 2021-01-13 2021-02-24 2021-03-26 2021-04-30 2021-10-27 ent of Supplies: Rape and HI ponse Component (CERC) nvelope ementation V rapid kits SVGRHP-G-DC-17 / Procurem Contingency Emergency Res ent of Acrylic Partitions at Ar IDA / 64810 Post Direct Selection Direct 6,000.00 0.00 Canceled 2021-01-19 2021-01-08 2021-01-24 2021-01-08 2021-02-28 2021-08-27 ponse Component (CERC) gyle Isolation Facility SVGRHP-G-DC-14 / COVID-1 Contingency Emergency Res Under Imple 9 Response - Consumables - IDA / 64810 Post Direct Selection Direct 30,000.00 0.00 2021-01-18 2021-02-02 2021-01-23 2022-12-09 2021-02-27 2021-08-26 ponse Component (CERC) mentation GeneXpert Machine Page 1 SVGRHP-G-DC-13 / COVID-1 Contingency Emergency Res Pending Impl 9 Response - Consumables - IDA / 64810 Post Direct Selection Direct 150,000.00 0.00 2021-01-18 2021-01-23 2021-02-27 2021-08-26 ponse Component (CERC) ementation Medical supplies for Isolation units SVGRHP-G-DC-12 / COVID-1 Contingency Emergency Res 9 Response - Consumables - IDA / 64810 Post Direct Selection Direct 300,000.00 174,374.00 Signed 2021-01-18 2021-02-04 2021-01-23 2021-01-13 2021-02-27 2021-04-20 2021-08-26 ponse Component (CERC) Containerized Laboratory an d Storage SVGRHP-G-DC-20 / COVID-1 Contingency Emergency Res Under Imple 9 Response - Consumables - IDA / 64810 Post Direct Selection Direct 147,600.00 0.00 2021-08-27 2021-09-03 2021-09-01 2021-04-12 2021-10-06 2022-04-04 ponse Component (CERC) mentation Testing supplies. SVGRHP-G-DC-23 / COVID-1 Contingency Emergency Res Request for Quota Single Stage - One E 9 Response - Equipment and IDA / 64810 Post Open - National 14,722.00 0.00 Canceled 2021-09-07 2021-11-02 2022-05-01 ponse Component (CERC) tions nvelope Furnishing for Isolation Facilit y - CCTV SVGRHP-W-RFQ-2 / COVID-1 9 Response - Containerized S Contingency Emergency Res Request for Quota Single Stage - One E Under Imple IDA / 64810 Post Open - National 10,000.00 0.00 2021-09-08 2021-11-03 2022-05-02 torage - Retrofitting works fo ponse Component (CERC) tions nvelope mentation r two (2) containers. SVGRHP-G-DC-18 / COVID-1 Contingency Emergency Res Pending Impl 9 Response - Containerized S IDA / 64810 Post Direct Selection Direct 3,720.00 0.00 2021-09-03 2021-09-08 2021-10-13 2022-04-11 ponse Component (CERC) ementation torage - 20ft Shipping Contai ners. SVGRHP-G-DC-24 / COVID-1 9 Response - Equipment and Contingency Emergency Res Under Imple Furnishing for Isolation Facilit IDA / 64810 Post Direct Selection Direct 176,100.00 0.00 2021-09-07 2021-09-08 2021-09-12 2021-09-02 2021-10-17 2022-04-15 ponse Component (CERC) mentation y - Medical Equipment - Argyl e Isolation Facility - BPF. SVGRHP-G-RFQ-9 / Equipme Contingency Emergency Res Request for Quota Single Stage - One E Pending Impl nt: Royal St. Vincent and the IDA / 64810 Post Open - National 10,000.00 0.00 2021-09-22 2021-11-17 2022-05-16 ponse Component (CERC) tions nvelope ementation Grenadines Police Force Sexu al Offenders Unit. SVGRHP-G-DC-21 / COVID-1 Contingency Emergency Res 9 Response - Consumables - IDA / 64810 Post Direct Selection Direct 250,000.00 432,050.00 Signed 2021-09-03 2021-09-09 2021-09-08 2021-09-02 2021-10-13 2021-09-10 2022-04-11 ponse Component (CERC) testing supplies SVGRHP-G-DC-26 / COVID-1 Contingency Emergency Res IDA / 64810 Post Direct Selection Direct 262,717.50 271,114.00 Signed 2021-11-03 2021-11-01 2021-11-08 2021-10-14 2021-12-13 2021-11-09 2022-06-11 9 Testing Supplies ponse Component (CERC) SVGRHP-G-DC-26(A) / COVID Contingency Emergency Res IDA / 64810 Post Direct Selection Direct 144,486.00 0.00 Canceled 2021-10-14 2021-11-09 2021-10-19 2021-11-23 2022-05-22 -19 Testing Supplies ponse Component (CERC) SVGRHP-G-DC-27 / Goods an Contingency Emergency Res Under Imple d Related Services for Servici IDA / 64810 Post Direct Selection Direct 15,009.00 0.00 2021-10-14 2021-11-09 2021-10-19 2021-11-11 2021-11-23 2022-05-22 ponse Component (CERC) mentation ng & Maintenance of QPCR M achine SVGRHP-RFQ-4 / COVID-19 R Contingency Emergency Res Request for Quota Single Stage - One E Under Imple IDA / 64810 Post Open - National 350,000.00 0.00 2021-08-24 2021-10-19 2022-04-17 esponse - PPE's. ponse Component (CERC) tions nvelope mentation SVGRHP-G-RFQ-26 (B) / COVI D-19 Response - Testing Sup Contingency Emergency Res Request for Quota Single Stage - One E IDA / 64810 Post Limited 262,717.50 0.00 Canceled 2021-11-08 2021-12-20 2022-02-28 plies (Extraction kits, Sample ponse Component (CERC) tions nvelope collections devices - VTMs et c.) SVGRHP-G-RFQ-4 / Personal Protective Equipment - for us Contingency Emergency Res Request for Quota Single Stage - One E Under Imple IDA / 64810 Post Limited 350,000.00 0.00 2021-11-15 2022-01-07 2021-12-30 2022-03-30 e in the Health Sector toward ponse Component (CERC) tions nvelope mentation s COVID-19 response. SVGRHP-G-DC-22 / Medical E Contingency Emergency Res Under Imple IDA / 64810 Post Direct Selection Direct 100,000.00 0.00 2021-11-10 2021-09-20 2021-11-15 2021-01-18 2021-12-09 2022-02-07 quipment - Mobile X-Ray ponse Component (CERC) mentation SVGRHP-G-RFQ-5 / Medical E Contingency Emergency Res Request for Quota Single Stage - One E IDA / 64810 Post Limited 361,184.40 0.00 Canceled 2021-12-27 2022-01-07 2022-02-10 2022-05-11 quipment, furniture and fittin ponse Component (CERC) tions nvelope gs SVGRHP-G-DC-26B / COVID- 19 Response - Testing Suppli Contingency Emergency Res Under Imple IDA / 64810 Post Direct Selection Direct 262,717.50 0.00 2022-01-10 2022-01-10 2022-01-15 2022-02-19 2022-08-18 es (Extraction kits, Sample c ponse Component (CERC) mentation ollections devices - VTMs etc. ) SVGRHP-G-RFQ-23 / COVID-1 Contingency Emergency Res Request for Quota Single Stage - One E Pending Impl 9 Response - Equipment and IDA / 64810 Post Open - National 14,722.00 0.00 2022-02-20 2022-04-17 2022-10-14 ponse Component (CERC) tions nvelope ementation Furnishing for Isolation Facilit y - CCTV SVGRHP-G-DC-26-C / COVID- Contingency Emergency Res Under Imple IDA / 64810 Post Direct Selection Direct 70,000.00 0.00 2022-01-04 2021-12-15 2022-01-09 2021-12-16 2022-02-13 2022-08-12 19 Testing Supplies ponse Component (CERC) mentation SVGRHP-G-DC-28 / COVID19 Contingency Emergency Res Under Imple IDA / 64810 Post Direct Selection Direct 50,000.00 0.00 2022-04-20 2022-04-24 2022-04-25 2022-05-30 2022-11-26 Response: GeneXpert Testin ponse Component (CERC) mentation g Kits SVGRHP-G-RFQ-29 / PCR Co Contingency Emergency Res Request for Quota Single Stage - One E Pending Impl IDA / 64810 Post Limited 14,950.00 0.00 2022-06-04 2022-07-05 2022-09-03 nsumables (Molecular Grade ponse Component (CERC) tions nvelope ementation Ethanol) SVGRHP-G-DC-30 / Testing S upplies (Modular SARS-CoV-2 Contingency Emergency Res Pending Impl IDA / 64810 Post Direct Selection Direct 22,500.00 0.00 2022-05-30 2022-06-04 2022-06-12 2022-08-11 RdRp 530,LightMix SabeccoV ponse Component (CERC) ementation E-gene plus EAV control) SVGRHP-G-RFQ-5B / Comput Contingency Emergency Res Request for Quota Single Stage - One E Under Imple IDA / 64810 Post Limited 4,400.00 0.00 2022-07-25 2022-10-04 2022-08-22 2022-10-21 er Equipment ponse Component (CERC) tions nvelope mentation Contingency Emergency Res Request for Quota Single Stage - One E Pending Impl SVGRHP-G-DC-5C / AC Units IDA / 64810 Post Limited 15,200.00 0.00 2022-07-29 2022-08-21 2022-10-20 ponse Component (CERC) tions nvelope ementation SVGRHP-G-RFG-5D / Office F Contingency Emergency Res Request for Quota Single Stage - One E Under Imple IDA / 64810 Post Limited 6,516.00 0.00 2022-08-05 2022-10-04 2022-08-28 2022-10-27 urniture and Equipment ponse Component (CERC) tions nvelope mentation SVGRHP-G-DC-5E / Refrigera Contingency Emergency Res Pending Impl IDA / 64810 Post Direct Selection Direct - National 3,240.00 0.00 2022-07-22 2022-08-05 2022-08-26 2022-10-25 tors ponse Component (CERC) ementation SVGRHP-G-RFQ-5A / Medical Contingency Emergency Res Request for Quota Single Stage - One E Under Imple IDA / 64810 Post Open - National 369,184.40 0.00 2022-07-29 2022-09-21 2022-12-20 Equipment ponse Component (CERC) tions nvelope mentation SVGRHP-G-FRQ-32 / Testing Contingency Emergency Res Request for Quota Single Stage - One E Pending Impl IDA / 64810 Post Limited 40,000.00 0.00 2022-09-02 2022-10-07 2022-12-06 Supplies and reagents ponse Component (CERC) tions nvelope ementation Page 2 SVGRHP-G-FRQ-31 / Laborat Contingency Emergency Res Request for Quota Single Stage - One E Pending Impl IDA / 64810 Post Limited 7,600.00 0.00 2022-09-11 2022-10-13 2022-10-19 ory Refrigerator ponse Component (CERC) tions nvelope ementation SVGRHP-G-DC- 30A / Covid-1 Contingency Emergency Res Pending Impl IDA / 64810 Post Direct Selection Direct - National 5,000.00 0.00 2022-11-25 2022-11-27 2022-12-06 2022-12-26 9 Testing Supplies ponse Component (CERC) ementation SVGRHP-G-RFQ-8 / Supply of Contingency Emergency Res Request for Quota Single Stage - One E IDA / 64810 Post Open - National 10,000.00 0.00 Canceled 2021-09-20 2021-11-15 2022-05-14 goods: Sexual assault kits. ponse Component (CERC) tions nvelope SVGRHP-G-RFQ-6 / COVID-19 Contingency Emergency Res Request for Quota Single Stage - One E Response - Decontamination IDA / 64810 Post Open - National 30,000.00 0.00 Canceled 2021-08-23 2021-10-18 2022-04-16 ponse Component (CERC) tions nvelope Equipment. SVGRHP-G-DC-25 / COVID-1 9 Response - Supporting Equi Contingency Emergency Res IDA / 64810 Post Direct Selection Direct 9,899.18 0.00 Canceled 2021-09-22 2021-09-27 2021-11-01 2022-04-30 pment, Bryden and Stokes (R ponse Component (CERC) eimbursement). SVGRHP-G-DC-16 / Procurem Institutional Capacity Buildin ent of Items for use in Project IDA / 64810 g, Project Management and Post Direct Selection Direct 4,500.00 0.00 Canceled 2021-01-11 2021-01-16 2021-02-20 2021-08-19 Office in response to Local C Coordination ovid019 spread. SVGRHP-G-RFQ-7 / COVID-19 Contingency Emergency Res Request for Quota Single Stage - One E IDA / 64810 Post Open - National 45,600.00 0.00 Canceled 2021-08-16 2021-10-11 2022-04-09 Response - Electrical Generat ponse Component (CERC) tions nvelope or SVGRHP-G-RFQ-26D / COVID Contingency Emergency Res Request for Quota Single Stage - One E IDA / 64810 Post Open - National 44,486.00 0.00 Canceled 2022-01-19 2022-03-16 2022-09-12 -19 Testing Supplies ponse Component (CERC) tions nvelope SVGRHP-G-DC-38 / Water Fil Contingency Emergency Res Under Imple IDA / 64810 Post Direct Selection Direct - National 9,350.00 0.00 2023-05-31 2023-06-27 2023-06-04 2023-06-09 2023-06-29 ter System ponse Component (CERC) mentation NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SVGRHP-NCS-RFQ-5 / Monito Institutional Capacity Buildin ring and evaluation- Allotme Request for Quota Single Stage - One E Pending Impl IDA / 64810 g, Project Management and Post Open - National 21,000.00 0.00 2020-08-05 2020-09-30 2021-03-29 nt for PIU/MOH staff training i tions nvelope ementation Coordination n fiduciary (WB etc.) SVGRHP-NCS-TR-1 / Conduct Strengthening Public Health Request for Quota Single Stage - One E Pending Impl Basic Field Epidemiology Trai IDA / 64810 Surveillance and Emergency Post Limited 5,000.00 0.00 2021-08-21 2021-10-16 2022-04-14 tions nvelope ementation ning Programme / Conduct M Management entorship FELTP SVGRHP-NCS-DC-1 / COVID- Contingency Emergency Res Pending Impl 19 Response - Consumables - IDA / 64810 Post Direct Selection Direct 20,400.00 0.00 2021-09-08 2021-09-13 2021-10-18 2022-04-16 ponse Component (CERC) ementation Inland Transportation for Con tainerized Lab. SVGRHP-NCS-DC-2 / COVID- Contingency Emergency Res Pending Impl 19 Response - Consumables - IDA / 64810 Post Direct Selection Direct 20,400.00 0.00 2021-09-08 2021-09-13 2021-10-18 2022-04-16 ponse Component (CERC) ementation Inland Transportation for Con tainerized Lab. SVGRHP-NCS-DC-4 / COVID- 19 Response - Transporting o Contingency Emergency Res Pending Impl IDA / 64810 Post Direct Selection Direct - National 485.00 0.00 2022-11-15 2022-11-20 2022-12-02 2022-12-05 f Laboratory Container to loc ponse Component (CERC) ementation ation in Canouan SVGRHP-NCS-DC-35 A / COVI Contingency Emergency Res Pending Impl D-19 Response - GBV Rental IDA / 64810 Post Direct Selection Direct - National 3,000.00 0.00 2022-11-25 2022-11-30 2022-12-07 2023-01-04 ponse Component (CERC) ementation of Venue of Community Cons ultations SVGRHP-NCS-DC-35B / COVI Contingency Emergency Res Pending Impl D-19 Response GBV - Comm IDA / 64810 Post Direct Selection Direct - National 2,000.00 0.00 2022-11-25 2022-11-30 2022-12-07 2022-12-27 ponse Component (CERC) ementation unity Consultations Provision of Refreshment SVGRHP-NCS-RFQ-4 / Activit Strengthening Public Health Request for Quota Single Stage - One E y to address weakness in co IDA / 64810 Surveillance and Emergency Post Open - National 30,000.00 0.00 Canceled 2020-12-01 2021-01-26 2021-07-25 tions nvelope mpliance with the 2005 IHR, i Management ncluding training SVGRHP-NCS-RFQ-1 / Frontli Strengthening Public Health Request for Quota Single Stage - One E ne & Basic Field Epidemiolog IDA / 64810 Surveillance and Emergency Post Limited 1,000.00 0.00 Canceled 2020-07-20 2020-09-14 2021-03-13 tions nvelope y Training Programme Management Strengthening Public Health SVGRHP-NCS-RFQ-2 / Condu Request for Quota Single Stage - One E IDA / 64810 Surveillance and Emergency Post Limited 3,000.00 0.00 Canceled 2020-07-18 2020-09-12 2021-03-11 ct Level 1 FELTP tions nvelope Management SVGRHP-NCS-RFQ-3 / Condu Strengthening Public Health Request for Quota Single Stage - One E ct Frontline Field Epidemiolo IDA / 64810 Surveillance and Emergency Post Limited 6,200.00 0.00 Canceled 2020-08-10 2020-10-05 2021-04-03 tions nvelope gy Training Program Management CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SVGRHP-C-CQS-1 / Feasibilit Improved Health Facilities a Consultant Qualifi y study of the existing Public IDA / 64810 Post Open - National 50,000.00 0.00 Canceled 2020-08-05 2020-08-26 2020-10-09 2020-11-08 2020-12-13 2021-06-11 nd Laboratory Capacity cation Selection Health Laboratory system SVGRHP-C-LCS-1 / Design an d Supervision for the constru Improved Health Facilities a Least Cost Selecti Under Implement IDA / 64810 Post Open - National 300,000.00 0.00 2020-12-15 2022-07-07 2021-01-05 2022-07-14 2021-02-18 2022-10-07 2021-03-18 2022-11-11 2021-04-17 2023-01-03 2021-05-22 2023-01-10 2021-06-26 2021-12-23 ction of the National Public H nd Laboratory Capacity on ation ealth building (to also house the EOC) SVGRHP-C-CQS-2 / TA to upd Strengthening Public Health Consultant Qualifi Pending Impleme ate and finalise communicabl IDA / 64810 Surveillance and Emergency Post Open - National 50,000.00 0.00 2020-08-05 2020-08-26 2020-10-09 2020-11-08 2020-12-13 2021-06-11 cation Selection ntation e disease preparedness & res Management ponse plans . SVGRHP-C-CQS - 3 / Establis Strengthening Public Health Consultant Qualifi hment of Isolation Facilities a IDA / 64810 Surveillance and Emergency Post Open - National 150,000.00 0.00 Signed 2020-07-31 2020-11-24 2020-08-21 2020-12-28 2020-10-04 2021-04-20 2020-11-03 2022-02-03 2020-12-08 2021-06-06 cation Selection t identified locations Management Page 3 SVGRHP-C-CQS-5 / Activity f or the Management of Biome Strengthening Public Health Consultant Qualifi dical waste - TA waste dispos IDA / 64810 Surveillance and Emergency Post Open - National 10,000.00 0.00 Canceled 2020-11-11 2020-12-02 2021-01-15 2021-02-14 2021-03-21 2021-09-17 cation Selection al system & Procurement of Management Decontaminated equipment Institutional Capacity Buildin SVGRHP-C-LCS-4 / Project Fi Least Cost Selecti Pending Impleme IDA / 64810 g, Project Management and Post Open - National 30,000.00 0.00 2021-02-05 2021-02-26 2021-04-11 2021-05-09 2021-06-08 2021-07-13 2021-08-17 2022-02-13 nancial Audit on ntation Coordination SVHRHP-C-CQS-4 / TA to Co mplete Depth Assessment of Improved Health Facilities a Consultant Qualifi Open - Internationa Pending Impleme IDA / 64810 Post 10,000.00 0.00 2021-09-06 2021-09-27 2021-11-10 2021-12-10 2022-01-14 2022-07-13 Health Facilities and Final Sc nd Laboratory Capacity cation Selection l ntation oring of Upgraded Facilities SVGRHP-C-LCS-6 / TA for the Improved Health Facilities a Least Cost Selecti Design and Supervision of Se IDA / 64810 Post Open - National 100,000.00 162,306.27 Signed 2021-08-09 2021-08-23 2021-08-30 2021-09-08 2021-10-13 2022-01-03 2021-11-10 2022-02-18 2021-12-10 2022-05-03 2022-01-14 2022-06-14 2022-02-18 2022-07-15 2022-08-17 nd Laboratory Capacity on lected Facilities to be Upgrad ed SVGRHP-C-CQS-6 / Improve t Strengthening Public Health Consultant Qualifi Open - Internationa he Information Base for Surv IDA / 64810 Surveillance and Emergency Post 50,000.00 0.00 Canceled 2021-08-16 2021-09-06 2021-10-20 2021-11-19 2021-12-24 2022-06-22 cation Selection l eillance - Training and invest Management ments in HIS SVGRHP-C-CQS-7 / Consulta Strengthening Public Health ncy to update Existing Food Consultant Qualifi Open - Internationa Pending Impleme IDA / 64810 Surveillance and Emergency Post 30,000.00 0.00 2021-09-15 2021-10-06 2021-11-19 2021-12-19 2022-01-23 2022-07-22 Safety, Port Health SOPs, Pro cation Selection l ntation Management tocols and supporting regulat ions INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Institutional Capacity Buildin SVGRHP-C-IC-1 / TA for Proc Individual Consult IDA / 64810 g, Project Management and Post Open 140,000.00 0.00 Under Review 2020-08-31 2020-11-03 2020-10-19 2020-11-09 2020-12-14 2021-06-12 urement assistant ant Selection Coordination SVGRHP-C-IC-3 / Safeguard c onsultancies and Gender Bas Contingency Emergency Res Individual Consult Pending Impleme ed Violence Service Providers IDA / 64810 Post Limited 25,000.00 0.00 2021-01-11 2021-01-16 2021-02-06 2021-03-13 2021-09-09 ponse Component (CERC) ant Selection ntation : TA for the Development of t he protocol and training Institutional Capacity Buildin SVGRHP-C-IC-4 / Contract M Individual Consult Pending Impleme IDA / 64810 g, Project Management and Post Open 21,000.00 0.00 2021-08-09 2021-09-27 2021-10-18 2021-11-22 2022-05-21 anagement Assistant ant Selection ntation Coordination SVGRHP-C-IC-9 / Consultanc Strengthening Public Health Under Implement y for the Updating National O IDA / 64810 Surveillance and Emergency Post Direct Selection Direct 42,000.00 0.00 2022-04-08 2022-04-04 2022-04-18 2022-03-24 2022-06-22 2022-12-19 ation ne Health All Hazards Manag Management ement Plan SVGRHP-IC-DC-35 / COVID-1 Contingency Emergency Res Pending Impleme 9 Response - GBV Communit IDA / 64810 Post Direct Selection Direct - National 1,550.00 0.00 2022-11-25 2022-12-02 2022-12-08 2022-12-10 ponse Component (CERC) ntation y Consultations SVGRHP-C-DC-1 / Improve th Strengthening Public Health e Information Base for Survei IDA / 64810 Surveillance and Emergency Post Direct Selection Direct 70,000.00 0.00 Canceled 2022-05-02 2022-05-12 2022-07-16 2023-01-12 llance - Training and investm Management ents in HIS Institutional Capacity Buildin SVGRHP-C-IC-5 / Environmen Individual Consult IDA / 64810 g, Project Management and Post Open 21,000.00 0.00 Canceled 2021-08-09 2021-09-29 2021-09-27 2021-10-18 2021-11-22 2022-05-21 tal & Safeguards Officer ant Selection Coordination SVGRHP-C-IC-7 / TA for the d Contingency Emergency Res Individual Consult IDA / 64810 Post Open 10,000.00 0.00 Canceled 2021-09-13 2021-11-01 2021-11-22 2021-12-27 2022-06-25 evelopment of the protocol a ponse Component (CERC) ant Selection nd training. SVGRHP-C-IC-8 / TOR - Traini Contingency Emergency Res Individual Consult IDA / 64810 Post Open 20,000.00 0.00 Canceled 2021-09-13 2021-11-01 2021-11-22 2021-12-27 2022-06-25 ng manual and training on G ponse Component (CERC) ant Selection BV SOP. Institutional Capacity Buildin SVGRHP-C-IC-2 / TA for Fina Individual Consult IDA / 64810 g, Project Management and Post Open 80,000.00 0.00 Canceled 2020-07-31 2020-11-04 2020-09-18 2020-10-09 2020-11-13 2021-05-12 ncial assistant ant Selection Coordination SVGRHP-C-IC-6 / Consultanc Strengthening Public Health y for the Development of Hea Individual Consult IDA / 64810 Surveillance and Emergency Post Open 30,000.00 0.00 Canceled 2021-09-12 2021-09-09 2021-10-31 2021-12-17 2021-11-21 2021-12-26 2022-06-24 lth Care Waste Management ant Selection Management System (HWMS) SVGRHP-C-IC-6A / Consultan Strengthening Public Health Direct - Internation Under Implement cy for Health Care Waste Ma IDA / 64810 Surveillance and Emergency Post Direct Selection 35,000.00 0.00 2023-05-17 2023-06-20 2023-05-28 2023-07-06 2024-03-04 al ation nagement System Management SVGRHP-C-IC-10 / National H Strengthening Public Health Individual Consult Pending Impleme ealth Multi-Hazard Incident M IDA / 64810 Surveillance and Emergency Post Limited 32,500.00 0.00 2023-06-12 2023-06-17 2023-07-25 2023-09-02 2024-03-30 ant Selection ntation anagement Plan Management Page 4 PROCUREMENT PLAN (Textual Part) Project information: Central Africa Republic Local Governance and Resilience Communities P-178699 Project Implementation agency: LONDO Plus Date of the Procurement Plan: May 5, 2023 Period covered by this Procurement Plan: 18 months Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in [insert appropriate references to the national procurement legislation], such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. Not Applicable When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables “Not Applicable” Other Relevant Procurement Information. Not Applicable PROCUREMENT Central African Republic : Local Governance and Resilient Communities PLAN General Information Country: Central African Republic 2023-05-05 Bank’s Approval Date of the Original Procurement Plan: 2023-06-07 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P178699 GPN Date: Project Name: Local Governance and Resilient Communities Loan / Credit No: IDA / V4720 Ministry of Economy, Planning and International Cooperation Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CF-MEPIC-356232-CS-CDS / Sélection d'un Consultant Int ernational chargé de la prépa ration du cadre de gestion en Direct - Internation IDA / V4720 Post Direct Selection 140,000.00 0.00 Signed 2023-05-31 2023-01-10 2023-06-10 2023-04-07 2023-08-14 2024-02-10 vironnemental (CGE), du cad al re de politique de réinstallati on (CPR) et du cadre de plani fication en faveur des peuple s autochtones (CPPA) CF-MEPIC-364784-CS-CDS / Sélection d'un Consultant ch argé de l'élaboration de la St Deconcentrating Financing a ratégie générale de passatio Direct - Internation Under Implement IDA / V4720 nd Enhancing Local Capacity Post Direct Selection 40,000.00 0.00 2023-07-31 2023-06-07 2023-08-10 2023-06-01 2023-10-14 2024-04-11 n des marchés pour promouv al ation for Service Delivery oir le développement (PPSD) ainsi que la formation de l'éq uipe du projet sur l'élaboratio n de PPSD Page 1 Revised Project Procurement Strategy for Development (PPSD) October 17, 2021 Lao PDR Covid-19 Response Project AF Department of Planning and Cooperation Ministry of Health Page 0 Table of Contents 1. Project Overview .............................................................................................2 1.1. Scope of Project ........................................................................................2 1.2. Major Procurement Activities ....................................................................2 2. Overview of Marketplace .................................................................................3 3. Procurement Risk Analysis ..............................................................................3 4. Procurement Objective ....................................................................................4 4.1. General Procurement Objectives...............................................................4 4.2. Specific Procurement Objectives...............................................................5 5. Recommended Procurement Arrangements for the Project ............................5 5.1. Procurement Approach..............................................................................5 For Goods ........................................................................................................5 For Works ........................................................................................................6 For Consultant services ...................................................................................6 6. Summary of PPSD to be inform the Bank’s Preparation of the PAD.................6 7. Procurement Plan ............................................................................................6 Page 1 1. Project Overview Country: Lao People’s Democratic Republic Full Project Lao PDR Covid-19 Response Project Additional Financing Name: Total Finance US$ 33 million, in which: ($): - IDA loan 6606 US$ 18 million - IDA loan 6946 US$10 million - HEPR Trust Funds no. B5890 US$ 3 million - HEPR Trust Fund no. B5891 US$2 million Project Number: P173817 and P175771 Implementing Ministry of Health, Department of Planning and Agency Corporation The project development objective (PDO) is to respond to Summary of the COVID-19 outbreak and strengthen national systems Project for public health emergency preparedness in Lao PDR. Development Objectives 1.1. Scope of Project The AF would support the costs of expanding activities of the Lao PDR COVID-19 Response Project (P173817 and P175771) under the COVID-19 Strategic Preparedness and Response Program (SPRP) using the Multiphase Programmatic Approach (MPA), approved by the Board on April 2, 2020, and the vaccines AF to the SPRP approved on April 6, 2020, and the vaccines AF to the SPRP approved on October 13, 20201. The primary objectives of the AF are to enable affordable and equitable access to COVID-19 vaccines and help ensure effective vaccine deployment in Lao PDR through vaccination system strengthening, and to further strengthen preparedness and response activities under the parent project. The Lao PDR COVID- 19 Response Project in an amount of US$ 18 million IDA – was approved on April 2, 2020 prepared under the SPRP. The additional financing of IDA US$10 million loan, IDA of US$3 million grant for Covid-19 vaccine deployment, and US$ 2 million to Strengthen Health Facility and Lifeline Infrastructure for HEPR. This AF is being provided mainly to assist the safe and effective deployment of vaccines in Lao PDR. 1.2. Major Procurement Activities The AF financing will be predominantly allocated to vaccine deployment (51.6% of AF) and vaccine procurement (33.3% of the AF). The AF will also include support staff for the project operation, and monitoring. It also comprises technical assistant of the medical waste management, water treatment, quality and safety of isolation facilities and health facilities. 1 The Bank approved a US$12 billion WBG Fast Track COVID-19 Facility (FTCF or “the Facility”) to assist IBRD and IDA countries in addressing the global pandemic and its impacts. Of this amount, US$6 billion came from IBRD/IDA (“the Bank”) and US$6 billion from the International Finance Corporation (IFC). The IFC subsequently increased its contribution to US$8 billion, bringing the FTCF total to US$14 billion. The Additional Financing of US$12 billion (IBRD/IDA) was approved on October 13, 2020 to support the purchase and deployment of vaccines as well as strengthening the related immunization and health care delivery system. Page 2 Procurement methods shall be used under the AF are Direct Selection, and Request for Quotations. 2. Overview of Marketplace Experience from the parent project shows that the largest packages were goods and most bidders were local and there was no interest from foreign bidders because of the country lockdown due to the COVID crisis. However, under the AF, the largest contract will be the procurement of the COVID vaccine, which will be not available at the suppliers in the country. The procurement of vaccines can possibly be done in ways such as a bilateral contract between the government, procuring directly from manufacturers, procuring through cost-sharing of COVAX facility by contracting with UNICEF who has the expertise in procuring vaccine and vaccine logistic management. Most of the key options were to be procured by using the Direct Selection Method to shorten the time and process of procurement in order to respond to urgency. 3. Procurement Risk Analysis The main procurement under the AF devoted to the procurement of Covid-19 vaccine. The funding goes to this procurement item as high as 5 million. Initially, the decision on the vaccine type to be procured is Johnson and Johnson, with potentially arranged through cost-sharing of the Covax facility. With such decision imposes, it must be taken into account the risk of the vaccine supply doses will not being offered to the Government of Laos. In addition, there is the possibility of the government potentially encountering delayed delivery given the limited number of vaccine suppliers in the marketplace which can affect the national vaccine deployment plan. Besides, there is the need to pay attention to the arrangement of procurement, logistic arrangement, timeline of vaccine delivery as well as the efficiency and economical choice of the vaccine supplier in terms financial spending. Nevertheless, any of the vaccine types that has passed WHO EUL is technically acceptable under this WB financing. From the above analysis, procurement risk should be manageable. Key risks identified and proposed risk mitigation measures are shown in Table 1 below. Table 1 – Procurement Related Risks and Mitigation Measures Risk Description Risk Description of Mitigation Risk Rating Owner Limited experience of Moderate (i) DPC staff and the Local Consultant will World Bank staff in the DPC and be provided with procurement training and DPC the Local Consultant initially by the World Bank with WB new regulations Delays in the Substanti (i) assist other departments in preparing DPC procurement process al technical specifications; (ii) Procurement monitoring using STEP; World Bank and DPC Page 3 Risk Description Risk Description of Mitigation Risk Rating Owner (iii) development of the procurement DPC tracking system and share with the Bank weekly. (iv) request for setting procurement DPC thresholds for goods and services that can be delegated to the MOH’s procurement committee (v) Closer coordination between World Bank Implementing Departments and IDA, and DPC and supervisions and follow up by IDA. Governance risks Moderate (i) Enhanced disclosure of procurement DPC associated with information, including publication of the conflict of interest, annual procurement plan and a fraud and corruption quarterly summary of the contract award information for all procurement packages on MoH’ s website and in newspapers. (ii) Require staff involved in procurement DPC to declare their interest and sign a declaration form (iii) Monitoring and reporting on the DPC implementation of actions Point 2 (i) to (v) and Point 3 (i) to (iii) for strengthening transparency and procurement training for the project. Limitation of value for Low (i) Due diligence by both World Bank and World Bank, money and Ministry of Health prior to the extension MoH transparency in of contracts extension of the existing contracts A limited number of Moderate (i) Careful procurement planning and DPC qualified consultants scheduling, preparing TOR, REOI and submitted proposals request for proposals advanced as much as possible, (ii) Widely advertise, post RFB and REOI on the ministry’s website, local newspapers and at the same time inform the known qualified consultants directly (iii) Allow more time for the consultant to prepare their proposals Limited experience of High (i) DPC and MOH officers should closely DPC MOH staff in the consult the National Taskforce procurement of Committee for COVID-19 prevention COVID-19 vaccine and control regarding the purchase of the vaccine. Page 4 Risk Description Risk Description of Mitigation Risk Rating Owner (ii) Closer coordination between Implementing Departments under MOH, IDA and UNICEF in purchasing vaccine. 4. Procurement Objective 4.1. General Procurement Objectives The main procurement objectives for the project in the selection of contractors, suppliers and consultants for the supply of works, goods and equipment and consultancy services are: i) Obtain value for money in the extension of existing contracts to cover Project financing ii) Greater transparency in the selection process for all packages in a timely manner for contractors, suppliers and consultants that have sufficient capacities and qualifications to successfully execute works, supply of goods and equipment and perform consultancy services as required; iii) Timely acquisition of goods and services (efficiency) to support the delivery of services specifically the attainment of the Universal Health coverage 4.2. Specific Procurement Objectives The specific procurement objectives under the projects are: (i) Effectively manage the procurement process and arrangement in order to get the medical supplies and Covid-19 vaccine in timeliness of need; (ii) Efficiently utilize the fund available by knowing the availability of vaccine stock in the country and the type of vaccine that is going to be needing. Timely procure medical equipment supplies and COVID-19 vaccine. (iii) Ensure timely supply and availability of equipment and supplies for logistics of vaccine distribution. 5. Recommended Procurement Arrangements for the Project Procurement under the AF will be carried out in accordance with the World Bank’s Procurement Regulations for IPF Borrowers for Goods, Works, Non-Consulting and Consulting Services, dated November 2020. As with the parent project, the AF will be subject to the World Bank’s Anticorruption Guidelines, dated October 15, 2006, revised in January 2011, and as of July 1, 2016. The Project will use the Systematic Tracking of Exchanges in Procurement (STEP) to plan, record and track procurement transactions. The major planned procurement under this AF will include: (i) additional capacity support of national, subnational and on site cold chain management; including equipment and supplies of cold rooms, vaccine containers, vaccine carriers, ice lined refrigerators (ILR) and transporting vehicles including refrigerator (temperature Page 5 controlled vehicle) this is to support the logistic arrangement of vaccines and ensuring that vaccines will be delivered to the vaccination site safely with proven control of the quality; (ii) technical assistance for production of mass media and communication campaigns including procuring camcorders and computers for production of media; ; (iii) supplies of Covid-19 Vaccine and vaccination support equipment. It will also include consultancy and non-consultant services such as (iv) works to improve isolation facilities in the 3 southern provinces; waste management and quality and safety of isolation facilities. The current demand for COVID-19 vaccines exceeds the supply in the market which makes it more difficult for client countries to negotiate terms and conditions. Procurement of vaccines will therefore follow Direct Selection from (i) purchase through COVAX (specify whether AMC or self-financing) or (ii) direct purchase from manufacturers. Contracts for vaccines purchase financed by the Bank will be subject to the Bank’s technical prior review irrespective of value and procurement approach. Options considered under the project include, among others, (i) streamlined competitive procedures with shorter bidding time, (ii) use of framework agreements including existing ones, (iii) procurement from UN Agencies enabled and expedited by Bank procedures and standard agreements, (iv) increased thresholds for Requests for Quotations and national procurement, and (v) Hands-on Expanded Implementation Support (HEIS). 5.1. Procurement Approach Procurement arrangements are defined based on the current context and the market analysis described above. For Goods Based on the analysis in the above sections, there will be 20 goods packages to be procured (14 packages under Initial Financing-IF and 6 packages under AF). The amount is estimated at US$ 20.3 million. 6 packages under IF had been completed by applying RFQ methods, while AF packages are ongoing using the Direct Selection market approach. The largest goods package is the procurement of COVID-19 vaccine, with the amount of US$ 5. million. This is expected to be directly purchased with potentially arranged through cost-sharing of the Covax facility, instead of through direct purchase Sinopharm (by using the bilateral negotiation) as mentioned in the initial PPSD. Furthermore, goods packages including Computer and Camcorder, Covid-19 Waste Management Equipment, Equipment for vaccine cold chain container and vehicle for vaccine delivery will purchased through Direct Selection method. For Works There is a total of 5 works packages, four under the IF and another under AF. Under the IF only one Improvement of isolation facilities would be procured through RFQ method. However, due to the pandemic situation and urgent requirements, there will be additional 4 works packages including 1 Improvement/renovation of the Quarantine facility for Champassak provinces, 3 Construction of isolation and lab facilities for Champassak, Sekong and Attapeu Provinces and Infectious Waste Disposal. All those works contracts will be procured using the DS method. Page 6 For Consultant services 14 Procurement for Consulting Services packages is foreseen involving of 11 packages under IF and 3 packages under AF. Most of the packages will be done through DS approaches. For detail please see procurement plan in below section (section 7) 6. Summary of PPSD to be inform the Bank’s Preparation of the PAD The procurement will be carried out in accordance with the World Bank Procurement Regulations for Borrowers under Investment Project Financing (IPF) dated July 1, 2016, revised November 2020 and per the provisions stipulated in the Financing Agreement. Since the RFQ method will be used for the procurement of some goods packages as the government standard Harmonized Bidding Documents and Request for Quotations for goods shall be applied. Most of the works and consulting services shall be conducted through a Direct Selection method, which will be completed much faster than other competitive approaches to support the emergency response project. The Covid-19 Procurement Committee of the MOH as per decree no 025/MOH dated 13 April 2020 will support some of the procurement packages. New procurable activities will include small packages of goods and consulting services. The procurement approach and methods of each package are shown in Procurement plan (section 7) below. 7. Procurement Plan Based on the PPSD a procurement plan for the project has been developed with a total of 40 packages including 20 goods, 6 works and 14 consulting services packages. The detailed procurement plan is available as a separate project document, which will be updated at any time as needed to reflect the current status of the implementation of each package or to add new packages as needed. PROCUREMENT PLAN Project Name: Lao PDR COVID-19 Response Project and AF (P173817 and P175771) Project Implementation Agency: Department of Planning and Cooperation, Ministry of Health Date of the Procurement Plan: Oct 17, 2021 Period covered by this Procurement Plan: Until December 31, 2023 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. Page 7 This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the Public Procurement Law and the Instruction on Implementation Public Procurement Law, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. a) The request for bids/request for proposals document shall require that bidders/proposers submitting bids/proposals present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, Bank Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights; b) Information related to award of contract including reasons for rejection of unsuccessful bidders shall be published on the implementing agency websites and/or newspaper of wide circulation. c) All complaints on procurement related matters including complaints arising from procurement under Bank financed Projects whilst using National Procurement Procedures shall be dealt with in accordance with Article 46 of the Public Procurement Law. Borrower shall put in place an effective complaints review mechanism for dealing with procurement related complaints, and shall disclose the details in all the bidding documents. All complaints shall be recorded by the Borrower in the appropriate tracking and monitoring system, as agreed between the Bank and the Borrower. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. Not Applicable Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables. Not Applicable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: is applicable for those contracts identified in the Procurement Plan tables; Page 8 Works: is applicable for those contracts identified in the Procurement Plan tables Other Relevant Procurement Information. I. Works and Goods and Non-Consultant Services 1.1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Annex II of the Procurement Regulations: Procurement Method Prior Review Thresholds Thresholds Category Applicable Applicable thresholds Remarks thresholds (in Remarks (in US$) US$) Works Request for None None quotations Direct Selection No threshold; meet None Specified in the - requirements of procurement regulations 7.13- plan table. 7.15 Goods and Non-Consulting Services Request for bids None None Request for None None quotations Direct Selection None No threshold; meet None requirements of regulations 7.13- 7.15 Procurement None No threshold; meet None from UN requirements of agencies regulations 6.47 and (Goods) 6.48 1.2 Procurement packages for Works, Goods and Non-Consulting Services (prior and post reviews) with method and Time Schedule Ref. Contract Estimated Procureme Revie Expect Comments No. (Description) Cost (US$) nt Method w by ed bid Bank openin g Date G-20 Procurement of medical 4,400,000 RFQ Post Apr-20 Completed; equipment Lot 1* G-23 Vehicle 782,000 RFB Post Oct-20 Completed; G-24 IT equipment 110,000 RFQ Post Feb-21 Completed; G-25 Sodium Hypochlorite 350,000 RFQ Post July -21 Ongoing Gernerator (Evaluation process) Page 9 G-26 Camera Camcorder 31,000 RFQ Post Feb-21 Contract awarded G-27 Procurement of medical 5,221,977 RFB Post Oct-20 Completed; equipment Lot 2 G-28 Medical Equipment: 1,285,000 RFQ Post Apr-21 Contract awarded 1. Conventional PCR testing of microbiological on sanitizer and gel and alcohol and N95 Mask, 2. GC-MS Headspace and 3. Autoclave for waste management 200L G-30 High flow nasal oxygen 230,000 DS Post Oct-21 On going and Glucose meter G-31 PPE: gown and coverall 600,000 DS Post Oct-21 On going G-32 Mattress 20,000 DS Post Oct-21 On going G-33 Autoclave 200 litres 40,000 DS Post Oct-21 On going G-34 Autoclave 110 litres 200,000 DS Post Oct-21 On going G-35 Chemical reagents and 1,254,000 DS Post Oct-21 On going lab consumables for diagnosis G-36 COVID-19 Test Kits 500,000 DS Post Oct-21 On going W-01 Improvement/renovatio 40,000 DS Post Dec-21 n of the Quarantine facility for Champasack province W-02 Construction of isolation and lab facilities for W-02.1 Oupalath Village, 962,400 DS Post Oct-21 On going Phonthong District, Champasack Province W-02.2 Mai Huameuang 898,500 DS Post Oct-21 On going Village, Laman District, Sekong Province W-02.3 Veunkhene Village, 866,600 DS Post Oct-21 On going Samakkhixay District, Attapeu Province AF-G 01 Computer and 60,000 DS Post Oct-21 On going Camcorder* Page 10 AF-G 02 Covid-19 Vaccine 5,000,000 DS Prior Dec-21 Negotiation .01 (Johnson & Johnson) (through Process. Covax Facility) AF-G 04 Equipment for vaccine 30,000 DS Post Oct-21 On going cold chain container** (cold box, dry ice, carrier) AF-G 05 Vehicles for Vaccine 110,000 DS Post Oct-21 On going Delivery** AF-G 06 Essential Drug and 70,000 DS Post Oct-21 On going Alcohol AF-G 07 Essential Drug and 9,100 DS Post Oct-21 On going equipment: Meropenem, Amikacin AF-W Infectious Waste 60,000 DS Post Oct -21 Contract 01 Disposal awarded Total Goods and Works 23,130,577 Notes: RFQ: Request for Quotations RFB: Request for Bids DS: Direct Selection * For those packages that will be procured through Direct Selection, the PCO is advised to direct contracting with the suppliers who won the contracts through open competitive bidding under the parent project. II. Selection of Consultants 2.1 Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Annex II of the Procurement Regulations: Procurement Method Thresholds Prior Review Thresholds Applicable Applicable Category thresholds Remarks thresholds Remarks (US$) (US$) QCBS, QBS, FBS, ≥ 300,000 Methods for consulting ≥ 4.0 million Risk-based LCS (Using the services are specified approach most in paragraph 7.3 to appropriate 7.12, Section VII of the market Procurement approach) Regulations. CQS (Open or < 300,000 QCBS, QBS, FBS, LCS) None limited can be applied for competition contracts with value through national under US$300,000 or international Page 11 market approach, specified in the PP and agreed with the Bank. Direct Selection None No threshold; meet Same as for This has not of firms requirements of competitive been foreseen regulations 7.13-7.15 selection at the project preparation stage. Individual N/A Essential individual ≥ 400,000 and Risk-based Consultants depending on assignments will be for the positions approach nature of defined in the as specified in services Procurement Plan the PP agreed agreed with the Bank with the Bank and in line with regulations 7.34-7.39 using the most appropriate market approach 2.2 Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than US$ 200,000 equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 7.1, Section VII of the Procurement Regulations. 2.3 Consultancy Assignments with Selection Methods and Time Schedule Ref. Description of Estimated Selecti Revie Expected Comments No. Assignment Cost on w by Proposal (US$) Metho Bank s d Submissi on Date C-01 Project Manager 120,000 DS Post Aug-20 Contract awarded C-02 Procurement 50,000 DS Post Dec-2020 Contract Assistant awarded C-04 Project 57,600 DS Post June-20 Contract Accountant -1 awarded Project Contract C-05 36,000 DS Post Jun-20 Accountant -2 awarded C-06 Safeguard 72,000 DS Post Sep-20 Contract Consultant awarded C-07 M&E Consultant 100,000 DS Post Oct-21 On going C-08 Project Financial 30,000 DS Post Dec-20 Contract Statements Audit awarded Page 12 Ref. Description of Estimated Selecti Revie Expected Comments No. Assignment Cost on w by Proposal (US$) Metho Bank s d Submissi on Date Logistic and Quality assurance Contract C-09 93,578 DS Post May-21 Support Officer awarded (For FDD) C-10 Design and 210,000 CQS Post Dec-20 Contract construction awarded supervision services for isolation and treatments COVID-19 facilities C-11 Satisfactory 350,000 DS Post Dec-2020 Contract survey firm awarded C-12 Environmental 132,000 DS Post Dec-2020 Contract and Social awarded Consultant (2) Waste management AF-C-01 450,000 DS Post Oct-21 Consultant/Servic e Quality and safety AF-C-02 of Isolation 50,000 DS Post Oct-21 Facilities AF-C-13 Financial and 18,400 DS Post Nov-21 On going Program Officer for COVID-19 Vaccine Deployment Total consulting services 1,769,578 Total Goods, Works and 24,900,15 Consulting Services 5 Notes: DS: Direct Selection CQS: Consultant’s Qualification-Based Selection Page 13 Annex 1 Ref. Contract (Description) Estimated Procurement Comments No. Cost Method (US$) G- Procurement of medical 4,400,000 RFQ (national- Completed 20 equipment Lot 1 limited) rtPCR machine, 4 provinces, 1,166,256 CPS, SVK, LP, KMN, VC (2) - laboratory testing Ventilator 706,977 Oxygen concentrator 57,140 Digital mobile X-ray 150 MA (7 2,387,163 central hospitals, 17 provinces) Patient monitoring with cart 61,395 Suction pump 17,442 G- Procurement of medical 5,211,977 27 equipment Lot 2 I. Medical Equipment and 1,358,333 laboratory Syringe pump Autoclave for waste management 250 L ICU patient bed, mobile Patient monitoring device II. Medical Device Quality 608,650 Control Equipment BFE Testing machine for capacity of microbiology Medical mask synthetic blood penetration tester Material for blood synthetic( CMC-Na, Pyrrolidol monolaurate, NaCl, Amaranth, KDP, DKP( Air exchange pressure tester Respirator Particles Filtration Tester (10-100L/min, efficacy of filtration 20-30mg/m3, accuracy: level 1) Mask Tension Tester Flame Retardant Tester (Speed 60±5mm/s, V1.0, Meas&Ctrl 2.0 testing software, time range 0(99.99s) Biosafety cabinet Autoclave 79L Incubator 160L Hot air Oven 160L GC-MS Headspace Page 14 Ref. Contract (Description) Estimated Procurement Comments No. Cost Method (US$) Alcohol Meter Alcohol Densitometer Rotary Evaporator III. Medical Supplies (1) 3,250,810 Oxygen supply with regulator and humidifier (5 central hospitals and 17 provinces) Gas cylinder, WMA219-40-15 Pulse Oximeter, portable Pulse Oximeter, fingertip / spot-check IV. Medical Supplies (2) 4,184 Nasal cannula, adult (S, M, L) Oxygen mask, with reservoir bag, adult Adhesive tape Infusion giving set IV flow regulator extension set Ref. Contract (Description) Estimated Procurement Comments No. Cost Method (US$) AF- Equipment for vaccine cold 30.000 DS G chain container 04 Cold box (vaccine container) Dry ice Vaccine carrier AF- G Vehicle (pick up) 110.000 DS 05 Page 15 PROCUREMENT Lao People's Democratic Republic : Lao PDR COVID-19 Response Project PLAN General Information Country: Lao People's Democratic Republic Bank’s Approval Date of the Original Procurement Plan: 2020-04-23 2023-06-02 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P173817 GPN Date: 2021-08-27 Project Name: Lao PDR COVID-19 Response Project Loan / Credit No: IDA / 66060, IDA / 69460, TF / B5890, TF / B5891 Department of Planning and Cooperation, Ministry of Health Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Request for Quota W-01 / Improvement/renovat Component 3: Project Manag tions - Small Work 2022-01-2 ion of the Quarantine facility IDA / 66060 ement and Monitoring and E Post Direct Selection Direct s (Emergency) SP 40,000.00 0.00 Canceled 2021-06-17 2021-06-22 2021-07-27 3 for Champasack province valuation D -Non Competiti ve Request for Quota W-02.1 / Construction of isol tions - Small Work ation and lab facilities for Ou Component 1: Emergency C 2022-03-0 IDA / 66060 Post Direct Selection Direct s (Emergency) SP 962,400.00 982,453.00 Signed 2021-07-29 2021-08-02 2021-08-03 2021-09-27 2021-09-07 2021-12-31 palath Village, Phonthong Dis OVID-19 Response 6 D -Non Competiti trict, Champasack Province ve Request for Quota W-02.2 / Construction of isol tions - Small Work ation and lab facilities for Mai Component 1: Emergency C 2022-03-0 IDA / 66060 Post Direct Selection Direct s (Emergency) SP 898,500.00 942,335.00 Signed 2021-07-29 2021-08-02 2021-08-03 2021-09-27 2021-09-07 2021-12-31 Huameuang Village, Laman OVID-19 Response 6 D -Non Competiti District, Sekong Province ve Request for Quota W-02.3 / Construction of isol tions - Small Work ation and lab facilities for Ve Component 1: Emergency C 2022-03-0 IDA / 66060 Post Direct Selection Direct s (Emergency) SP 866,600.00 802,212.00 Signed 2021-07-29 2021-08-02 2021-08-03 2021-09-27 2021-09-07 2022-01-11 unkhene Village, Samakkhixa OVID-19 Response 6 D -Non Competiti y District, Attapeu Province ve Request for Quota W-01. / Improvement/renova Component 3: Project Manag Request for Quota Single Stage - One E tions - Small Work 2022-06-3 tion of the Quarantine facility IDA / 69460 ement and Monitoring and E Post Open - National 40,000.00 0.00 Signed 2021-11-06 2022-01-01 tions nvelope s (Emergency) SP 0 for Champasack province valuation D -Competitive Request for Quota W-04 / Construction and ren Component 3: Project Manag Request for Quota Single Stage - One E tions - Small Work 2023-10-3 ovation of the existing POE H IDA / 69460 ement and Monitoring and E Post Limited 10,000.00 0.00 Signed 2023-03-08 2023-03-15 2023-05-03 tions nvelope s (Emergency) SP 0 ealth screening facilities at V valuation D -Competitive uangTao POE, CPS Request for Quota AF-W-02.01 / Champasack: Component 3: Project Manag Request for Quota Single Stage - One E tions - Small Work 2023-10-3 Construction and installation TF / B5891 ement and Monitoring and E Post Limited 48,000.00 0.00 Signed 2023-03-08 2023-04-04 2023-05-03 tions nvelope s (Emergency) SP 0 of RC waste pit for needle/sh valuation D -Competitive arp waste Request for Quota AF-W-02.02 / Attapue: Const Component 3: Project Manag Request for Quota Single Stage - One E tions - Small Work Under Imple 2023-10-3 ruction and installation of RC TF / B5891 ement and Monitoring and E Post Limited 18,000.00 0.00 2023-03-08 2023-05-03 tions nvelope s (Emergency) SP mentation 0 waste pit for needle/sharp w valuation D -Competitive aste AF-W-02.06 / Saravan:(provi Request for Quota Component 3: Project Manag ncial hospital, 7 community h Request for Quota Single Stage - One E tions - Small Work Pending Imp 2023-10-3 TF / B5891 ement and Monitoring and E Post Limited 9,000.00 0.00 2023-03-09 2023-05-04 ospitals and Covid-19 treatm tions nvelope s (Emergency) SP lementation 1 valuation ent center, at NongBouHin vil D -Competitive lage Request for Quota AF-W-02.04 / Luan Prabang: Component 3: Project Manag Request for Quota Single Stage - One E tions - Small Work 2023-10-3 Construction and installation TF / B5891 ement and Monitoring and E Post Limited 12,000.00 0.00 Canceled 2023-03-08 2023-05-03 tions nvelope s (Emergency) SP 0 of RC waste pit for needle/sh valuation D -Competitive arp waste Request for Quota AF-W-02.05 / Vientiane Provi Component 3: Project Manag Request for Quota Single Stage - One E tions - Small Work Under Imple 2023-10-3 nce: Construction and install TF / B5891 ement and Monitoring and E Post Limited 50,000.00 0.00 2023-03-08 2023-05-10 2023-05-03 tions nvelope s (Emergency) SP mentation 0 ation of RC waste pit for nee valuation D -Competitive dle/sharp waste AF-W-03 / Construction and r Request for Quota Component 3: Project Manag enovation of existing garbag Request for Quota Single Stage - One E tions - Small Work 2023-10-3 TF / B5891 ement and Monitoring and E Post Limited 25,000.00 0.00 Signed 2023-03-08 2023-03-16 2023-05-03 e collection facilities at 103 tions nvelope s (Emergency) SP 0 valuation Hospital, Vientiane Capital D -Competitive Request for Quota AF-W-04 / Construction and r Component 3: Project Manag Request for Quota Single Stage - One E tions - Small Work Pending Imp 2023-10-3 enovation of existing LAB fac TF / B5891 ement and Monitoring and E Post Limited 20,000.00 0.00 2023-03-08 2023-05-03 tions nvelope s (Emergency) SP lementation 0 ilities at WASH Center valuation D -Competitive AF-W-05 / Improve the existi ng toilet and septic tank, and Component 3: Project Manag Request for Quota Request for Quota Single Stage - One E 2023-10-3 builds the fence and stair to TF / B5891 ement and Monitoring and E Post Limited tions (Non Bank-S 18,000.00 0.00 Canceled 2023-03-08 2023-05-03 tions nvelope 0 access the building at the Co valuation PD) vid-19 lab at Khoua DHO, Ph ongsaly Province AF-W-06 / Xienkhouang Prov Request for Quota Component 3: Project Manag ince: Request for Quota Single Stage - One E tions - Small Work Under Imple 2023-10-3 TF / B5891 ement and Monitoring and E Post Limited 45,000.00 0.00 2023-03-08 2023-05-03 To renovate the existing buil tions nvelope s (Emergency) SP mentation 0 valuation ding to be the standard Corvi D -Competitive d 19 Laboratory. AF-W-07.01 / HCF in Savann akhet Hospital: Request for Quota Improve the two existing sep Component 3: Project Manag Request for Quota Single Stage - One E tions - Small Work Pending Imp 2023-10-3 tic tanks and connection syst TF / B5891 ement and Monitoring and E Post Limited 100,000.00 0.00 2023-03-08 2023-05-03 tions nvelope s (Emergency) SP lementation 0 em for treating the grey wate valuation D -Competitive r 25 m3/day and 32 m3/day before discharge to the publi c canal. AF-W-07.02 / HCF in Ngern D istrict Hospital, Xayabouly Pr Request for Quota Component 3: Project Manag ovince Request for Quota Single Stage - One E tions - Small Work Pending Imp 2023-10-3 TF / B5891 ement and Monitoring and E Post Limited 55,000.00 0.00 2023-03-08 2023-05-03 To improve the existing septi tions nvelope s (Emergency) SP lementation 0 valuation c tank and connection syste D -Competitive m for treating the grey water 12m3/day before discharge t o the public canal. Request for Quota AF-W-08 / Construction brick Component 3: Project Manag Request for Quota Single Stage - One E tions - Small Work Under Imple 2023-10-3 walls at Namor Community H TF / B5891 ement and Monitoring and E Post Limited 50,000.00 0.00 2023-03-09 2023-05-04 tions nvelope s (Emergency) SP mentation 1 ospital valuation D -Competitive W-09.01 / Construction and i Request for Quota Component 3: Project Manag nstallation a chlorine drop ta Request for Quota Single Stage - One E tions - Small Work Pending Imp 2023-10-3 IDA / 69460 ement and Monitoring and E Post Limited 10,000.00 0.00 2023-03-09 2023-05-04 nk 200 liters including conne tions nvelope s (Emergency) SP lementation 1 valuation ction system in Saravan D -Competitive Page 1 W-09.02 / Installation a chlor Request for Quota Component 3: Project Manag ine drop tank 200 liters inclu Request for Quota Single Stage - One E tions - Small Work Pending Imp 2023-10-3 IDA / 69460 ement and Monitoring and E Post Limited 4,000.00 0.00 2023-03-09 2023-05-04 ding connection system tions nvelope s (Emergency) SP lementation 1 valuation in Xayabouly D -Competitive W-09.03 / Construction and i Request for Quota Component 3: Project Manag nstallation a chlorine drop ta Request for Quota Single Stage - One E tions - Small Work 2023-10-3 IDA / 69460 ement and Monitoring and E Post Limited 1,000.00 0.00 Signed 2023-03-09 2023-03-20 2023-05-04 nk 200 liters including conne tions nvelope s (Emergency) SP 1 valuation ction system in Sekong D -Competitive Request for Quota W-10.01 / Construction and i Component 3: Project Manag Request for Quota Single Stage - One E tions - Small Work Pending Imp 2023-10-3 nstallation Bio-sand filter sys IDA / 69460 ement and Monitoring and E Post Limited 100,000.00 0.00 2023-03-09 2023-05-04 tions nvelope s (Emergency) SP lementation 1 tem (for 18 m3) valuation D -Competitive Request for Quota W-11 / Construction of Eleva Component 3: Project Manag Request for Quota Single Stage - One E tions - Small Work Pending Imp 2023-10-3 ted RC water tank 25m3 incl IDA / 69460 ement and Monitoring and E Post Limited 30,000.00 0.00 2023-03-09 2023-05-04 tions nvelope s (Emergency) SP lementation 1 uding connection system valuation D -Competitive Request for Quota W-12 / Construction and inst Component 3: Project Manag Request for Quota Single Stage - One E tions - Small Work 2023-10-3 allation partition walls (clear IDA / 69460 ement and Monitoring and E Post Limited 5,000.00 0.00 Signed 2023-03-09 2023-04-03 2023-05-04 tions nvelope s (Emergency) SP 1 glass) valuation D -Competitive W-13 / Construction and Inst Request for Quota Component 3: Project Manag allation aluminum water tank Request for Quota Single Stage - One E tions - Small Work Pending Imp 2023-10-3 IDA / 69460 ement and Monitoring and E Post Limited 10,000.00 0.00 2023-03-09 2023-05-04 2500 liters and a chlorine dro tions nvelope s (Emergency) SP lementation 1 valuation p tank 200 liters including co D -Competitive nnection system Request for Quota W-03 / Construct the quaran Component 3: Project Manag Request for Quota Single Stage - One E tions - Small Work 2023-10-3 tine at Phoukeau POE at Atta IDA / 69460 ement and Monitoring and E Post Limited 100,000.00 0.00 Canceled 2023-03-08 2023-05-03 tions nvelope s (Emergency) SP 0 peu province valuation D -Competitive GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual G-20 / Procurement of medic Component 1: Emergency C Request for Quota Single Stage - One E IDA / 66060 Post Limited 4,400,000.00 4,200,000.00 Signed 2020-04-05 2020-04-03 2020-05-31 2020-04-11 2020-11-27 al equipment Lot 1 OVID-19 Response tions nvelope G-1 / Medical Equipment and Component 1: Emergency C Single Stage - One E IDA / 66060 Post Request for Bids Open - National 871,333.00 0.00 Canceled 2020-10-19 2020-10-24 2020-12-05 2021-01-04 2021-02-08 2021-08-07 laboratory OVID-19 Response nvelope G-2 / Medical Device Quality Component 1: Emergency C Single Stage - One E IDA / 66060 Post Request for Bids Open - National 608,650.00 0.00 Canceled 2020-10-19 2020-10-24 2020-12-05 2021-01-04 2021-02-08 2021-08-07 Control Equipment OVID-19 Response nvelope Component 1: Emergency C Single Stage - One E G-21 / Medical Supplies (1) IDA / 66060 Post Request for Bids Open - National 3,250,810.00 0.00 Canceled 2020-10-19 2020-10-24 2020-12-05 2021-01-04 2021-02-08 2021-08-07 OVID-19 Response nvelope G-27 / Procurement of medic Component 1: Emergency C Single Stage - One E IDA / 66060 Post Request for Bids Open - National 4,734,977.00 844,461.16 Signed 2020-09-10 2020-09-10 2020-09-15 2020-10-27 2020-10-20 2020-11-26 2020-12-08 2020-12-31 2021-01-14 2021-06-29 al equipment Lot 2 OVID-19 Response nvelope Component 1: Emergency C Single Stage - One E G-23 / Vehicle IDA / 66060 Post Request for Bids Open - National 782,000.00 716,137.46 Signed 2020-10-22 2020-10-11 2020-10-27 2020-12-08 2020-11-10 2021-01-07 2020-12-08 2021-02-11 2021-01-14 2021-08-10 OVID-19 Response nvelope Component 1: Emergency C Request for Quota Single Stage - One E G-26 / Camera Camcorder IDA / 66060 Post Open - National 31,000.00 43,725.88 Signed 2020-12-06 2021-01-31 2021-05-05 2021-07-30 OVID-19 Response tions nvelope Component 1: Emergency C Request for Quota Single Stage - One E G-24 / IT equipment IDA / 66060 Post Open - National 107,500.00 100,200.04 Signed 2020-12-15 2021-02-09 2021-05-05 2021-08-08 OVID-19 Response tions nvelope Component 3: Project Manag Request for Quota Single Stage - One E G-28 / Medical Equipment IDA / 66060 Post Open - National 1,285,000.00 485,977.52 Signed 2021-06-01 2021-07-27 2021-08-21 2022-01-23 ement and Monitoring and E tions nvelope valuation AF-G 01 / Computer and Ca Component 3: Project Manag IDA / 66060 Post Direct Selection Direct 60,000.00 0.00 Canceled 2021-06-17 2021-06-30 2021-08-04 2022-01-31 mcorder ement and Monitoring and E valuation AF-G 05 / Vehicles for Vaccin Component 3: Project Manag IDA / 66060 Post Direct Selection Direct 110,000.00 73,000.00 Signed 2021-06-17 2021-06-17 2021-06-22 2021-10-05 2021-07-27 2021-11-10 2022-01-23 e Delivery ement and Monitoring and E valuation AF-G 04 / Equipment for vac Component 3: Project Manag cine cold chain container (col IDA / 66060 ement and Monitoring and E Post Direct Selection Direct 30,000.00 255,000.00 Signed 2021-06-17 2021-06-17 2021-06-22 2021-10-04 2021-07-27 2021-11-10 2022-01-23 d box, dry ice, carrier) valuation G27 / Procurement of medic Component 1: Emergency C Single Stage - One E IDA / 66060 Post Request for Bids Open - National 5,221,977.00 1,314,361.23 Signed 2020-09-10 2020-09-10 2020-09-15 2020-10-27 2020-10-20 2020-11-26 2020-12-08 2020-12-31 2021-01-14 2021-06-29 al equipment Lot 2 OVID-19 Response nvelope G-30 / High flow nasal oxyge Component 3: Project Manag IDA / 66060 Post Direct Selection Direct 230,000.00 224,700.00 Signed 2021-11-04 2021-11-04 2021-11-09 2021-10-18 2021-12-14 2021-11-10 2022-06-12 n and Glucose meter ement and Monitoring and E valuation AF-G 06 / Essential Drug and Component 3: Project Manag IDA / 66060 Post Direct Selection Direct 70,000.00 41,423.86 Signed 2021-11-04 2021-11-04 2021-11-09 2021-11-05 2021-12-14 2021-12-22 2022-06-12 Alcohol ement and Monitoring and E valuation Component 3: Project Manag Request for Quota Single Stage - One E G-32 / Mattress for patients IDA / 66060 Post Limited 20,000.00 17,223.98 Signed 2021-11-24 2021-11-12 2022-01-19 2022-02-01 2022-07-18 ement and Monitoring and E tions nvelope valuation G-35 / Chemical reagents an Component 3: Project Manag IDA / 66060 Post Direct Selection Direct 1,254,000.00 240,900.00 Signed 2021-11-19 2021-11-19 2021-11-24 2021-11-19 2021-12-29 2021-12-22 2022-06-27 d lab consumables for diagno ement and Monitoring and E sis valuation G-31 / PPE: gown and covera Component 3: Project Manag IDA / 66060 Post Direct Selection Direct 600,000.00 155,000.00 Signed 2021-12-23 2021-12-23 2021-12-28 2021-12-24 2022-02-01 2022-02-18 2022-07-31 ll ement and Monitoring and E valuation AF-G 07 / Essential Drug : M Component 3: Project Manag eropenem 1g and Amikacin i IDA / 69460 ement and Monitoring and E Post Direct Selection Direct 9,100.00 7,282.04 Signed 2021-12-23 2021-12-13 2021-12-28 2021-12-27 2022-02-01 2022-02-10 2022-07-31 njection 500mg/2ml valuation G-33 / Procurement of Autoc Component 3: Project Manag IDA / 66060 Post Direct Selection Direct 240,000.00 82,000.00 Signed 2021-12-23 2022-02-09 2021-12-28 2022-02-09 2022-02-01 2022-04-20 2022-07-31 lave ement and Monitoring and E valuation AF-G 01. / Computer and Ca Component 3: Project Manag Request for Quota Single Stage - One E IDA / 66060 Post Open - National 92,000.00 0.00 Completed 2022-03-05 2022-04-30 2022-10-27 2023-01-12 mcorder ement and Monitoring and E tions nvelope valuation AF-G 08 / Diagnostic Chemic Component 3: Project Manag Request for Quota Single Stage - One E IDA / 69460 Post Open - National 604,000.00 0.00 Signed 2022-03-12 2022-05-07 2022-11-03 al Reagents for Laboratory ement and Monitoring and E tions nvelope valuation Page 2 AF-G 09 / Disinfectant, alcoh Component 4: Strengthening TF / B5890 Post Direct Selection Direct 135,000.00 0.00 Canceled 2022-05-20 2022-05-25 2022-06-29 2022-12-26 ol, general (available size 5L) Preparedness for Health Em 70% ergency AF-G 10 / Molnupiravir 200 Component 4: Strengthening TF / B5890 Post Direct Selection Direct 74,000.00 0.00 Canceled 2022-05-20 2022-05-25 2022-06-29 2022-12-26 mg Preparedness for Health Em ergency Component 4: Strengthening AF-G 11 / Favipiravir 200mg TF / B5890 Post Direct Selection Direct 5,000.00 0.00 Canceled 2022-05-20 2022-05-25 2022-06-29 2022-12-26 Preparedness for Health Em ergency AF-G 12 / Enoxaparin Sodiu Component 4: Strengthening TF / B5890 Post Direct Selection Direct 97,000.00 0.00 Canceled 2022-05-20 2022-05-25 2022-06-29 2022-12-26 m BP 40 mg/0.4 mL Preparedness for Health Em ergency AF-G 13 / Meropenem Trihyd Component 4: Strengthening TF / B5890 Post Direct Selection Direct 214,000.00 0.00 Canceled 2022-05-20 2022-05-25 2022-06-29 2022-12-26 rate eq. to anhydrous Merop Preparedness for Health Em enem 1 g ergency AF-G 14 / Drugs (Dabigatran Component 4: Strengthening 110 mg, Dabigatran 150 mg TF / B5890 Preparedness for Health Em Post Direct Selection Direct 32,000.00 0.00 Canceled 2022-05-20 2022-05-25 2022-06-29 2022-12-26 and Immunogloburin) ergency AF-G 15 / Diagnostic Chemic Component 4: Strengthening TF / B5890 Post Direct Selection Direct 647,000.00 0.00 Canceled 2022-05-26 2022-07-20 2023-04-18 al Reagent for Real-time PCR Preparedness for Health Em -01 ergency AF-G 16 / Diagnostic Chemic Component 4: Strengthening TF / B5890 Post Direct Selection Direct 679,000.00 0.00 Canceled 2022-05-20 2022-05-25 2022-06-29 2022-12-26 al Reagent for Real-time PCR Preparedness for Health Em -02 ergency AF-G 17 / Diagnostic Chemic Component 4: Strengthening al Reagent for Real-time PCR Request for Quota Single Stage - One E TF / B5890 Preparedness for Health Em Post Open - National 900,000.00 0.00 Canceled 2022-05-25 2022-07-20 2023-01-16 -03 and Prevention and Contr tions nvelope ergency ol - all PPE items AF-G 18 / AccuViral Collectio Component 3: Project Manag Request for Quota Single Stage - One E n Kit, 3ml VTM Medium with TF / B5891 ement and Monitoring and E Post Open - National 216,000.00 0.00 Canceled 2022-07-09 2022-09-03 2023-03-02 tions nvelope one Nasopharyngeal and one valuation Throat swabs G-37 / Medical Equipment fo Component 3: Project Manag r COVID-19 Treatment Faciliti TF / B5891 ement and Monitoring and E Post Direct Selection Direct - National 500,000.00 0.00 Canceled 2022-09-07 2022-09-12 2022-10-17 2023-04-15 es in Champasak , Sekong an valuation d Attapue Provinces AF-G 19 / Motorcycles for Dis Component 3: Project Manag TF / B5891 Post Direct Selection Direct - National 100,000.00 0.00 Signed 2022-10-03 2022-09-23 2022-10-08 2022-10-17 2022-11-12 2023-05-11 tricts ement and Monitoring and E valuation AF-G 20 / Megaphones for Di Component 3: Project Manag Request for Quota Single Stage - One E TF / B5891 Post Open - National 35,000.00 0.00 Signed 2022-10-08 2022-12-03 2023-06-01 stricts ement and Monitoring and E tions nvelope valuation G-37. / Medical Equipment f Component 3: Project Manag or Single Stage - One E Under Imple IDA / 69460 ement and Monitoring and E Post Request for Bids Open - National 500,000.00 0.00 2022-11-15 2022-12-01 2022-11-20 2023-01-01 2022-12-27 2023-01-31 2023-03-10 2023-03-07 2023-09-03 COVID-19 Treatment Facilitie nvelope mentation valuation s in Champasak , Sekong and Attapue Provinces AF-G 22 / Hospital Furniture Component 3: Project Manag for isolation and lab facilities Request for Quota Single Stage - One E TF / B5891 ement and Monitoring and E Post Open - National 200,000.00 0.00 Signed 2022-11-20 2023-01-15 2023-07-14 for Champasak, Sekong and tions nvelope valuation Attapeu Provinces G-38 / Refrigerated Vaccine Component 3: Project Manag Request for Quota Single Stage - One E TF / B5891 Post Open - National 585,000.00 0.00 Signed 2022-12-10 2023-02-04 2023-08-03 Transport Vehicle ement and Monitoring and E tions nvelope valuation G-39 / Computer for POE sta Component 3: Project Manag Request for Quota Single Stage - One E Pending Impl TF / B5891 Post Open - National 38,000.00 0.00 2022-12-10 2023-02-04 2023-08-03 ff 28 POE ement and Monitoring and E tions nvelope ementation valuation AF-G 23 / Procurement of wa Component 3: Project Manag Request for Quota Single Stage - One E Pending Impl ste collection, segregation an TF / B5891 ement and Monitoring and E Post Open - National 1,350,000.00 0.00 2022-12-10 2023-02-04 2023-08-03 tions nvelope ementation d disinfection technology valuation AF-G 09. / Procurement of Di Component 3: Project Manag sinfectant, alcohol, general ( Request for Quota Single Stage - One E TF / B5891 ement and Monitoring and E Post Open - National 209,000.00 0.00 Signed 2022-12-19 2023-02-13 2023-08-12 available size 5L) 70% , Moln tions nvelope valuation upiravir 200 mg and medical consumables AF-G 24 / Procurement of lap Component 3: Project Manag Request for Quota Single Stage - One E Pending Impl TF / B5891 Post Open - National 287,100.00 0.00 2023-01-28 2023-03-25 2023-09-21 top computers for health cen ement and Monitoring and E tions nvelope ementation ters valuation AF-G 25 / Laboratory reagen Component 3: Project Manag Request for Quota Single Stage - One E TF / B5891 Post Open - National 1,350,000.00 0.00 Canceled 2023-02-01 2023-03-29 2023-09-25 ts and supplies for testing ement and Monitoring and E tions nvelope valuation AF-G 26 / Vehicle for transpo Component 3: Project Manag Request for Quota Single Stage - One E Pending Impl TF / B5891 Post Open - National 234,000.00 0.00 2023-02-07 2023-04-04 2023-10-01 rtation of Drug and medical e ement and Monitoring and E tions nvelope ementation quipment valuation Component 3: Project Manag Pending Impl G-40 / TB Drug IDA / 69460 Post Direct Selection Direct - National 652,400.00 0.00 2023-03-04 2023-03-09 2023-04-13 2023-10-10 ement and Monitoring and E ementation valuation AF-G 21 / Sleeveless shirt jac Component 3: Project Manag Request for Quota Single Stage - One E TF / B5891 Post Open - National 50,000.00 0.00 Canceled 2022-10-08 2022-12-03 2023-06-01 kets for health centers ement and Monitoring and E tions nvelope valuation AF-G 27 / Vaccines Procurem Component 1: Emergency C IDA / 66060 Post Direct Selection Direct - National 991,267.00 0.00 Signed 2023-03-03 2023-03-03 2023-03-15 2023-03-15 2023-05-30 2023-12-30 ent (MR5, Penta, PCV and HP OVID-19 Response V) AF-G 28 / Medical Equipment Component 3: Project Manag Request for Quota Single Stage - One E Pending Impl TF / B5891 Post Open - National 639,884.00 0.00 2023-06-08 2023-08-03 2024-01-30 for Community Health Facilit ement and Monitoring and E tions nvelope ementation y valuation AF-G 29 / Laboratory COVID- Component 3: Project Manag Request for Quota Single Stage - One E Pending Impl TF / B5891 Post Open - National 500,100.00 0.00 2023-06-08 2023-08-03 2024-01-30 19 detection kits and consum ement and Monitoring and E tions nvelope ementation ables valuation AF-G 30 / Laboratory equipm Component 3: Project Manag Request for Quota Single Stage - One E Pending Impl ent and Standard Reagent fo TF / B5891 ement and Monitoring and E Post Open - National 286,010.00 0.00 2023-06-08 2023-08-03 2024-01-30 tions nvelope ementation r Medicine Quality Testing valuation NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 3 AF-W 01 / Infectious Waste Component 3: Project Manag IDA / 66060 Post Direct Selection Direct 60,000.00 0.00 Completed 2021-06-17 2021-06-17 2021-06-22 2021-11-05 2021-07-27 2022-01-23 2021-12-06 Disposal ement and Monitoring and E valuation CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual C-10 / Design and constructi Component 1: Emergency C Consultant Qualifi on supervision services for is IDA / 66060 Post Open - National 210,000.00 205,392.00 Signed 2020-10-30 2021-02-08 2020-11-20 2021-01-03 2021-02-22 2021-02-02 2021-04-05 2021-03-09 2021-04-24 2021-09-05 OVID-19 Response cation Selection olation and treatments COVI D-19 facilities INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 3: Project Manag C-04 / Project Accountant-1 IDA / 66060 Post Direct Selection Direct 32,000.00 14,400.00 Signed 2020-04-28 2020-04-28 2020-05-08 2020-04-30 2020-07-12 2020-06-02 2021-01-08 ement and Monitoring and E valuation Component 3: Project Manag C-01 / Project Manager IDA / 66060 Post Direct Selection Direct 69,000.00 33,600.00 Signed 2020-06-13 2020-06-13 2020-06-23 2020-06-09 2020-08-27 2020-08-11 2021-02-23 ement and Monitoring and E valuation Component 3: Project Manag C-06 / Safeguard Consultant IDA / 66060 Post Direct Selection Direct 34,000.00 24,000.00 Signed 2020-06-13 2020-06-13 2020-06-23 2020-08-04 2020-08-27 2020-09-02 2021-02-23 ement and Monitoring and E valuation Component 3: Project Manag C-05 / Project Accountant-2 IDA / 66060 Post Direct Selection Direct 32,000.00 0.00 Canceled 2020-04-28 2020-05-06 2020-05-08 2020-07-12 2021-01-08 ement and Monitoring and E valuation C-03 / Chief Project Account Component 3: Project Manag IDA / 66060 Post Direct Selection Direct 48,000.00 0.00 Canceled 2020-04-28 2020-05-08 2020-07-12 2021-01-08 ant ement and Monitoring and E valuation C-08 / Project Financial State Component 1: Emergency C IDA / 66060 Post Direct Selection Direct 30,000.00 9,000.00 Signed 2020-10-22 2020-10-26 2020-11-01 2020-12-20 2021-01-05 2021-03-16 2021-07-04 ments Audit OVID-19 Response C-02 / Procurement Assistan Component 1: Emergency C IDA / 66060 Post Direct Selection Direct 34,500.00 15,600.00 Signed 2020-12-01 2020-12-10 2020-12-11 2020-12-29 2021-02-14 2021-01-26 2021-08-13 t OVID-19 Response C-12 / Environmental and So Component 1: Emergency C IDA / 66060 Post Direct Selection Direct 34,500.00 175.00 Signed 2020-12-01 2020-12-15 2020-12-11 2021-01-24 2021-02-14 2021-02-16 2021-08-13 cial Consultant (2) OVID-19 Response C-11 / Satisfactory survey fir Component 1: Emergency C IDA / 66060 Post Direct Selection Direct 200,000.00 198,910.00 Signed 2020-12-11 2020-12-15 2020-12-21 2021-01-19 2021-02-24 2021-04-23 2021-08-23 m OVID-19 Response C-09.1 / Logistic and Quality Component 1: Emergency C assurance Support Officer(Fo IDA / 66060 Post Direct Selection Direct 60,000.00 24,000.00 Signed 2020-12-15 2021-02-02 2020-12-25 2021-03-15 2021-02-28 2021-05-11 2021-08-27 OVID-19 Response r Department of Food and Dr ug) Component 3: Project Manag C-07 / M&E Consultant IDA / 66060 Post Direct Selection Direct 100,000.00 21,600.00 Signed 2021-06-17 2021-06-23 2021-06-30 2021-10-24 2021-09-03 2021-11-02 2022-03-02 ement and Monitoring and E valuation Component 3: Project Manag C-5 / Project Accountant -2 IDA / 66060 Post Direct Selection Direct 36,000.00 14,400.00 Signed 2021-06-17 2021-06-23 2021-06-27 2021-06-24 2021-08-31 2021-07-02 2022-02-27 ement and Monitoring and E valuation C-13 / Consultant for Financi Component 3: Project Manag al and Program Officer for CO IDA / 69460 ement and Monitoring and E Post Direct Selection Direct 18,400.00 18,000.00 Signed 2021-10-18 2021-10-20 2021-10-28 2021-10-28 2022-01-01 2021-11-16 2022-06-30 VID-19 Vaccine Deployment valuation AF-C-01 / Individual Consulta Component 3: Project Manag nt: Rapid Assessment of Medi IDA / 69460 ement and Monitoring and E Post Direct Selection Direct 10,000.00 0.00 Canceled 2021-12-17 2021-12-27 2022-03-02 2022-08-29 cal Waste Management in Pr valuation ovincial Hospitals AF-C-01. / Individual Consult Component 3: Project Manag ant: Rapid Assessment of Me Individual Consult IDA / 69460 ement and Monitoring and E Post Direct 10,000.00 6,000.00 Signed 2021-12-23 2022-01-05 2022-01-02 2022-01-06 2022-01-23 2022-01-06 2022-02-27 2022-01-18 2022-08-26 dical Waste Management in P ant Selection valuation rovincial Hospitals C-03. / Chief of Project Acco Component 3: Project Manag Individual Consult IDA / 66060 Post Direct 75,600.00 36,852.00 Signed 2021-12-23 2022-01-04 2022-01-02 2021-12-27 2022-01-23 2021-12-27 2022-02-27 2022-01-05 2022-08-26 untant ement and Monitoring and E ant Selection valuation C-14 / GRM Public Relation O Component 3: Project Manag Individual Consult IDA / 66060 Post Direct 14,400.00 6,600.00 Signed 2022-01-26 2022-02-08 2022-02-05 2022-02-18 2022-02-26 2022-02-18 2022-04-02 2022-03-02 2022-09-29 fficer ement and Monitoring and E ant Selection valuation AF-C-03 / Waste Handling Su Component 3: Project Manag Individual Consult IDA / 69460 Post Direct 7,200.00 5,400.00 Signed 2022-01-26 2022-02-08 2022-02-05 2022-02-21 2022-02-26 2022-02-22 2022-04-02 2022-03-02 2022-09-29 pport Staff ement and Monitoring and E ant Selection valuation AF-C-02 / Consulting Firm: O Component 3: Project Manag n Medical Wastewater Manag IDA / 69460 ement and Monitoring and E Post Direct Selection Direct 440,000.00 0.00 Completed 2022-02-17 2022-02-21 2022-02-27 2022-03-10 2022-05-03 2022-10-30 2023-01-16 ement at Healthcare Facilitie valuation s C-15 / Short Term Individual Component 4: Strengthening Consultant on WASH need as Individual Consult TF / B5890 Preparedness for Health Em Post Direct 25,000.00 0.00 Completed 2022-05-11 2022-05-16 2022-05-21 2022-07-13 2022-06-11 2022-08-01 2022-07-16 2023-01-12 2022-11-10 sessment for health emergen ant Selection ergency cy response and preparedne ss C-16 / Medical Waste manag Component 4: Strengthening TF / B5890 Post Direct Selection Direct 100,000.00 0.00 Canceled 2022-05-11 2022-05-16 2022-05-21 2022-07-25 2023-01-21 ement Consultant at health f Preparedness for Health Em acilities ergency AF-C-04 / Short Term Individ Component 4: Strengthening Individual Consult IDA / 69460 Post Direct 5,000.00 0.00 Completed 2022-05-13 2022-05-16 2022-05-23 2022-09-19 2022-06-13 2022-09-26 2022-07-18 2023-01-14 2023-01-12 ual Legal Consultant Preparedness for Health Em ant Selection ergency C-17 / National Data Progra Component 3: Project Manag Individual Consult IDA / 66060 Post Direct 10,800.00 0.00 Signed 2022-06-14 2022-06-17 2022-06-24 2022-07-13 2022-07-15 2022-07-15 2022-08-19 2023-02-15 m Officer ement and Monitoring and E ant Selection valuation AF-C-05 / Consulting Firm for Technical Assistance on COVI Component 3: Project Manag D-19 Treatment Facilities Op TF / B5891 ement and Monitoring and E Post Direct Selection Direct 100,000.00 0.00 Completed 2022-06-29 2022-07-12 2022-07-09 2022-08-09 2022-09-12 2023-03-11 2023-01-13 eration and Maintenance in C valuation hampasak, Attapeu, and Sek ong Provinces AF-C-08 / Wastewater and S Component 3: Project Manag Individual Consult IDA / 69460 Post Direct 12,000.00 0.00 Completed 2022-07-11 2022-12-13 2022-07-21 2022-07-15 2022-08-11 2022-07-18 2022-09-15 2023-03-14 2022-11-02 olid Waste Management Con ement and Monitoring and E ant Selection sultant valuation Page 4 AF-C-06 / National Architectu Component 3: Project Manag Individual Consult IDA / 69460 Post Direct 64,000.00 0.00 Completed 2022-07-11 2022-07-18 2022-07-21 2022-10-19 2022-08-11 2022-10-24 2022-09-15 2023-03-14 2023-01-12 re Consultant ement and Monitoring and E ant Selection valuation AF-C-07 / National Assessme nt of Multi-Hazard risk and cri Component 3: Project Manag Individual Consult tical infrastructure under cli IDA / 69460 ement and Monitoring and E Post Direct 140,000.00 0.00 Canceled 2022-07-11 2022-07-18 2022-07-21 2022-08-11 2022-09-15 2023-03-14 ant Selection mate change and Developme valuation nt and Pilot-Testing of Lao PD R Hospital Safety Index AF-C-07. / Assessing of Healt Component 3: Project Manag h Facility and Lifeline Infrastr TF / B5891 ement and Monitoring and E Post Direct Selection Direct - National 140,000.00 0.00 Canceled 2022-11-07 2022-11-01 2022-11-17 2023-01-21 2023-07-20 ucture for Health Emergency valuation Preparedness in Lao PDR C-18 / Procurement Consulta Component 3: Project Manag Individual Consult IDA / 69460 Post Direct - National 48,000.00 0.00 Signed 2023-01-13 2023-01-19 2023-01-23 2023-02-02 2023-02-13 2023-02-02 2023-03-20 2023-09-16 nt ement and Monitoring and E ant Selection valuation C-19 / Admin and Finance Of Component 3: Project Manag Individual Consult IDA / 69460 Post Direct - National 28,800.00 0.00 Signed 2023-01-13 2023-01-19 2023-01-23 2023-01-16 2023-02-13 2023-01-16 2023-03-20 2023-09-16 ficer ement and Monitoring and E ant Selection valuation Component 3: Project Manag Individual Consult C-20 / M&E Consultant IDA / 69460 Post Direct - National 24,000.00 0.00 Signed 2023-01-13 2023-01-19 2023-01-23 2023-02-01 2023-02-13 2023-02-02 2023-03-20 2023-09-16 ement and Monitoring and E ant Selection valuation AF-C07 / Consulting Firm for Component 4: Strengthening Assessing of Health Facility a TF / B5891 Preparedness for Health Em Post Direct Selection Direct - National 220,000.00 0.00 Signed 2023-01-23 2023-01-19 2023-02-02 2023-01-20 2023-04-08 2023-10-05 nd Lifeline Infrastructure for ergency Health Emergency Preparedn ess in Lao PDR AF-C-10 / Individual Consulta Component 3: Project Manag nt on Design and Constructio Individual Consult TF / B5891 ement and Monitoring and E Post Direct - National 35,000.00 0.00 Signed 2023-04-03 2023-05-03 2023-04-13 2023-05-05 2023-05-04 2023-05-08 2023-06-08 2023-12-05 n Supervision for Septic tank ant Selection valuation Treatment System and Scree ning Building AF-C-09 / Consulting Firm for Design and construction sup Component 3: Project Manag ervision services for wastewa TF / B5891 ement and Monitoring and E Post Direct Selection Direct - National 45,000.00 0.00 Canceled 2023-01-27 2023-01-26 2023-02-06 2023-04-12 2023-10-09 ter system, water supply syst valuation em, and small civil works for improvement of WASH in He alth Facility C-16. / Consulting Services o Component 3: Project Manag n Medical Waste Managemen IDA / 69460 ement and Monitoring and E Post Direct Selection Direct - National 100,000.00 0.00 Canceled 2023-01-13 2023-01-19 2023-01-23 2023-03-29 2023-09-25 t at Healthcare Facilities valuation AF-C-11 / Technical Advisor f Component 3: Project Manag Individual Consult Direct - Internation Under Implement IDA / 69460 Post 25,000.00 0.00 2023-05-03 2023-06-01 2023-05-13 2023-06-03 2023-07-08 2024-01-04 or Development of Referral G ement and Monitoring and E ant Selection al ation uideline valuation Page 5 PLAN DE PASSATION DE MARCHÉS (Texte) Information sur le Projet : Sénégal - Investissement dans la petite enfance pour un développement humain - P161332 Agence d’exécution du Projet : Ministère de la Femme, de la Famille et du genre (MFFG) Date du plan de passation des marchés : 10 septembre 2019 Période couverte par ce plan de passation des marchés : Septembre – Février 2021 Préambule Conformément au paragraphe 5.9 du “Règlement de Passation des Marchés pour les Emprunteurs sollicitant le Financement de Projets d’Investissement (FPI)” (Juillet 2016, révisé en aout 2019) (“Règlement de Passation des Marchés”) le Système électronique de la Banque de suivi systématique des transactions de marchés publics (STEP) sera utilisé pour préparer, valider et actualiser les plans de passation des marchés et effectuer toutes les transactions liées à la passation des marchés du projet. Ce texte ainsi que les tableaux du plan de passation des marchés présents dans STEP constituent le plan de passation des marchés du projet. Les conditions suivantes s'appliquent à toutes les activités de passation de marchés du plan de passation de marchés. Les autres éléments du plan de passation des marchés tels que requis au paragraphe 4.4 du Règlement de passation des marchés sont énoncés dans STEP. Les Dossiers types de passation des marchés publics de la Banque devront être utilisés pour tous les contrats soumis à la concurrence internationale, ainsi que pour tous les autres contrats soumis à cette obligation telle que spécifiée dans les tableaux du plan de passation des marchés de STEP. Procédures nationales de passation des marchés : En accord avec le paragraphe 5.3 du Règlement de passation des marchés, dans le cas où la procédure de passation des marché se fera au niveau national (telle que spécifiée dans les tableaux du plan de passation des marchés inclus de STEP), les procédures nationales de passation des marchés du pays considéré pourront être utilisées. Si l’Emprunteur utilise ses propres procédures d’appel d’offres national ouvert telles qu’énoncées, ces arrangements sont soumis aux dispositions du paragraphe 5.4 du Règlement de passation des marchés et aux conditions suivantes : Sans objet. Lorsque l’Emprunteur utilise d’autres procédures que l’appel d’offres national ouvert, ces procédures devront être en accord avec les dispositions du paragraphe 5.5 du Règlement de passation des marchés. Crédit-bail tel que spécifié au paragraphe 5.10 du Règlement de Passation des marchés : Le crédit-bail peut être utilisé pour les contrats indiqués comme tel dans le Plan de passation des marchés. « Sans objet » Achat de biens d’occasion tel que spécifié au paragraphe 5.11 du Règlement de Passation des Marchés est autorisé pour les contrats indiqués comme tel dans le Plan de passation des marchés. « Sans objet » Préférence nationale telle que spécifiée au paragraphe 5.51 du Règlement de Passation des Marchés (Fournitures et Travaux). Fournitures : ne s’applique pas Travaux : ne s’applique pas Autres informations pertinentes sur la passation des marchés : Néant. PROCUREMENT Senegal : Senegal Investing in the Early Years for Human Development PLAN General Information Country: Senegal 2019-10-22 Bank’s Approval Date of the Original Procurement Plan: 2023-06-02 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P161332 GPN Date: 2019-10-28 Project Name: Senegal Investing in the Early Years for Human Development Loan / Credit No: IDA / 63200 MINISTÈRE DE LA FEMME, DE LA FAMILLE ET DU GENRE Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned SN-MFFG-143710-CW-RFQ / Project management and tec Request for Quota Single Stage - One E 2020-02-1 Agencements Aménagement IDA / 63200 Post Limited 5,454.00 3,129.28 Signed 2019-11-25 2020-03-09 2020-01-20 2020-03-20 hnical assistance tions nvelope 9 et Installation (cloisonnemen t) SN-MFFG-135512-CW-RFQ / Réhabilitation des structures de DPE existantes (y compris Request for Quota Single Stage - One E 2021-09-2 les espaces pour une stimula IDA / 63200 Quality early learning Post Limited 178,871.00 0.00 Canceled 2020-09-08 2020-11-30 tions nvelope 6 tion précoce) dans les région s de Fatick, Diourbel, Kaolack , Kaffrine, Matam, Tambacou nda, et Kolda SN-MFFG-135506-CW-RFB / Construction de 14 écoles m Single Stage - One E 1,384,864.4 2021-08-1 aternelles publiques Daara d IDA / 63200 Quality early learning Post Request for Bids Open - National 676,028.00 Signed 2021-04-14 2021-08-04 2021-04-14 2021-05-18 2021-09-09 2021-06-08 2021-09-16 2021-07-14 2021-10-27 nvelope 1 3 ans les régions de Fatick, Dio urbel, Kaolack, Kaffrine, Mata m, Tambacounda, et Kolda SN-MFFG-135507-CW-RFB / Construction de33 Cases des Single Stage - One E 2,481,632.5 2021-08-1 Touts Petits dans les régions IDA / 63200 Quality early learning Post Request for Bids Open - National 3,600,000.00 Signed 2020-07-13 2021-02-09 2020-07-13 2021-03-01 2020-08-14 2021-04-08 2020-09-03 2021-04-23 2020-10-14 2021-07-23 nvelope 1 0 de Fatick, Diourbel, Kaolack, Kaffrine, Matam Tambacound a, et Kolda National Procure SN-MFFG-135504-CW-RFB / ment Document - Construction de 90 classes p Single Stage - One E 1,192,751.5 2022-12-2 IDA / 63200 Quality early learning Post Request for Bids Open - National 1 Envelope proce 1,000,000.00 Signed 2022-03-28 2021-04-02 2022-03-28 2022-05-02 2021-05-06 2022-05-22 2021-05-21 2022-06-25 2021-08-18 réscolaires dans les régions nvelope 4 2 ss (Non Bank-SPD d'intervention du projet ) Request for Bids - SN-MFFG-344136-CW-RFB / Single Stage - One E Small Works SPD Pending Imp 2023-11-1 Construction de 60 Classes P IDA / 63200 Quality early learning Post Request for Bids Open - National 995,000.00 0.00 2023-02-20 2023-02-20 2023-03-27 2023-04-16 2023-05-20 nvelope (1 envelope proce lementation 6 réparatoires à l'Elémentaire ( ss) CPE) GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SN-MFFG-135371-GO-RFQ / Achat de tablettes électroniq ues pour 7 inspecteurs régio Child protection and system Request for Quota Single Stage - One E naux de l'éducation, 24 DEI, IDA / 63200 Post Limited 30,769.00 28,086.62 Completed 2019-12-02 2019-12-16 2020-01-03 2020-01-22 2020-02-03 2020-03-10 strengthening tions nvelope 24 CODEPE, 7 RC-ECD dans l es régions de Fatick, Diourbe l, Kaolack, Kaffrine, Matam T ambacounda, et Kolda SN-MFFG-135494-GO-RFQ / Achats Equipement pour 150 CPE, 66 CTP et 14 Daara (éq uipement de salle de classe ( Single Stage - One E Pending Impl IDA / 63200 Quality early learning Post Request for Bids Open - National 978,533.00 0.00 2021-11-16 2021-11-16 2021-12-20 2022-01-10 2022-02-14 2022-05-25 tables bancs), jeux de plein a nvelope ementation ir (toboggans), etc.) dans les régions de Fatick, Diourbel, K aolack, Kaffrine, Matam Tam bacounda, et Kolda SN-MFFG-135498-GO-RFQ / Acquisition équipement pour Request for Quota Single Stage - One E IDA / 63200 Quality early learning Post Limited 89,445.00 81,889.78 Signed 2020-01-13 2020-01-24 2020-02-28 2020-02-28 2020-04-13 les espaces de stimulation pr tions nvelope écoce pour les Case des Tout s petits SN-MFFG-135540-GO-RFQ / Acquisition de matériel infor Project management and tec Request for Quota Single Stage - One E IDA / 63200 Post Limited 49,090.00 80.75 Completed 2019-09-24 2019-09-20 2019-10-19 2019-10-18 2019-11-03 2019-11-13 matique pour le personnel de hnical assistance tions nvelope l'UGP du PIPADHS SN-MFFG-136157-GO-UN / A cquisition de 12 véhicules de Child nutrition and early sti supervision au profit de l'Unit UN Agencies (Dire IDA / 63200 mulation in the first 1,000 d Post Direct 1,496,364.00 1,074,344.88 Completed 2019-11-06 2019-12-18 2019-11-06 2019-11-11 2019-12-10 2020-04-09 2020-02-08 2020-05-08 é de Gestion du PIPADHS, de ct) ays s Partenaires de mise en oeu vre et 11 véhicules de superv ision pour la CLM SN-MFFG-138710-NC-RFQ / F ourniture et câblage du rése au informatique et téléphoni Project management and tec Request for Quota Single Stage - One E IDA / 63200 Post Limited 23,600.00 18,935.82 Completed 2019-10-14 2019-10-16 2019-10-28 2019-11-22 2019-11-17 2019-11-30 que du local de l'Unité de Ge hnical assistance tions nvelope stion du PIPADHS (fourniture serveur, appareil téléphoniqu e, câble ect....) SN-MFFG-138704-GO-RFQ / Acquisition et installation de Project management and tec Request for Quota Single Stage - One E matériel de froid (Splits et réf IDA / 63200 Post Limited 9,090.00 0.00 Canceled 2019-10-14 2019-10-31 2019-11-30 hnical assistance tions nvelope rigérateur) pour les locaux d e l'Unité de Gestion du PIPAD HS SN-MFFG-135539-GO-RFQ / Project management and tec Request for Quota Single Stage - One E Acquisition de mobiliers de b IDA / 63200 Post Limited 37,271.00 28,353.80 Completed 2019-10-07 2019-10-09 2019-11-07 2019-10-30 2019-12-07 2019-12-10 hnical assistance tions nvelope ureaux et de climatiseurs SN-MFFG-143703-GO-RFQ / Project management and tec Request for Quota Single Stage - One E Acquisition de fournitures de IDA / 63200 Post Limited 14,545.00 19,037.92 Completed 2019-11-17 2019-10-16 2019-12-21 2019-11-21 2020-01-20 2020-02-13 hnical assistance tions nvelope bureau et de consommables informatique Page 1 SN-MFFG-143705-GO-RFQ / Acquérir des produits d'entre Project management and tec Request for Quota Single Stage - One E IDA / 63200 Post Limited 2,727.00 982.90 Completed 2019-11-14 2020-01-07 2019-12-16 2020-01-25 2020-01-15 2020-02-14 tien et de nettoyage des bur hnical assistance tions nvelope eaux de l'unité de gestion du PIPADHS SN-MFFG-145120-GO-RFQ / Project management and tec Request for Quota Single Stage - One E Acquisition de téléphone port IDA / 63200 Post Limited 3,182.00 2,933.02 Completed 2019-12-02 2019-12-03 2019-12-24 2019-12-13 2020-01-03 2019-12-20 hnical assistance tions nvelope able pour le personnel de l'U GP PIPADHS SN-MFFG-145872-GO-RFQ / Edition et imprimer du cahier Request for Quota Single Stage - One E d'activités du curriculum d'éd IDA / 63200 Quality early learning Post Limited 63,618.00 54,764.51 Signed 2019-11-27 2019-12-11 2019-12-23 2019-12-28 2020-01-22 tions nvelope ucation de base en 53 317 e xemplaires au profit de l'ANP ECTP SN-MFFG-146135-GO-RFQ / Request for Quota Single Stage - One E Acquisition de balances pour IDA / 63200 Quality early learning Post Limited 56,090.00 34,909.66 Signed 2019-12-03 2020-01-21 2019-12-27 2020-02-28 2020-01-26 tions nvelope les structures DIPE SN-MFFG-145864-GO-RFQ / Acquisition de matériels de p Request for Quota Single Stage - One E IDA / 63200 Quality early learning Post Limited 98,090.00 0.00 Canceled 2019-11-26 2019-12-25 2020-01-24 lein air pour 83 structures de tions nvelope développement intégré de la petite enfance SN-MFFG-167405-GO-RFQ / Acquisition de matériel infor Request for Quota Single Stage - One E matique au profit des parten IDA / 63200 Quality early learning Post Limited 75,000.00 0.00 Completed 2020-04-20 2020-04-27 2020-05-10 2020-05-13 tions nvelope aires de mise en oeuvre du P IPADHS dans le cadre de l'ap pui institutionnel SN-MFFG-168084-GO-RFQ / Doter les centres d'états civil Child protection and system Request for Quota Single Stage - One E d'imprimés, de registres, des IDA / 63200 Post Limited 55,950.00 24,847.73 Signed 2020-05-05 2020-06-24 2020-06-30 2020-07-22 2020-12-27 strengthening tions nvelope imprimés d'actes de naissanc e au profit de la Direction de l'Etat Civil SN-MFFG-168105-GO-DIR / A cquisition de mobilier de bur Project management and tec IDA / 63200 Post Direct Selection Direct 1,814.00 2,016.98 Completed 2020-04-13 2020-03-13 2020-04-18 2020-03-12 2020-04-28 2020-03-25 2020-05-13 2020-04-16 eau complémentaire pour le hnical assistance personnel additionnel avec M aster Office SN-MFFG-138617-GO-RFQ / Project management and tec Request for Quota Single Stage - One E Production de support de co IDA / 63200 Post Limited 33,333.00 0.00 Completed 2019-11-30 2020-04-20 2020-01-25 2020-07-23 hnical assistance tions nvelope mmunication au profit de L'U GP PIPADHS SN-MFFG-173350-GO-RFQ / Acquisition de kits ludiques p Request for Quota Single Stage - One E our les enfants des structure IDA / 63200 Quality early learning Post Limited 660,000.00 405,215.49 Signed 2020-05-19 2020-06-09 2020-06-02 2020-07-09 2020-07-02 tions nvelope s DIPE des regions d’interven ir dans le cadre du COVID po ur le stimulation précoce. SN-MFFG-173353-GO-RFQ / Acquisition de kits d’ hygiène pour la protection des enfant Child protection and system Request for Quota Single Stage - One E IDA / 63200 Post Limited 751,667.00 714,138.42 Completed 2020-05-20 2020-06-08 2020-06-04 2020-07-09 2020-07-04 2020-10-17 s des structures DIPE dans le strengthening tions nvelope s sept régions d’intervention du projet dans le cadre de la prévention du covid SN-MFFG-177475-GO-DIR / R eproduction de supports de c Child protection and system Request for Quota Single Stage - One E ommunication dans le cadre IDA / 63200 Post Limited 31,818.00 23,477.08 Signed 2020-06-14 2020-06-23 2020-07-27 2020-07-09 2020-08-16 strengthening tions nvelope de la lutte contre le Covid au profit des PMOs du PIPADHS SN-MFFG-183270-GO-RFQ / Project management and tec Request for Quota Single Stage - One E Acquisition de produits d'entr IDA / 63200 Post Limited 2,727.00 2,643.12 Signed 2020-07-18 2020-09-25 2020-09-12 2020-10-06 2021-03-11 hnical assistance tions nvelope etien et de nettoiement des bureaux SN-MFFG-183265-GO-RFQ / Edition de supports de comm unication (guides, affiches, fl Child protection and system Request for Quota Single Stage - One E IDA / 63200 Post Limited 9,090.00 10,495.72 Signed 2020-11-16 2021-06-01 2021-01-11 2021-07-08 2021-07-10 yers, tee shirts, casquettes.... strengthening tions nvelope ) au profit de la Direction de l a Protection des Droits et la P romotion des Enfants SN-MFFG-168048-GO-RFB / Acquérir des manuels,Livres de compte, Album de jeunes se, Imagiers pour les appren Single Stage - One E IDA / 63200 Quality early learning Post Request for Bids Open - National 672,684.00 397,941.74 Signed 2020-11-16 2020-12-08 2020-11-21 2021-03-01 2020-12-24 2021-03-16 2021-01-13 2021-03-30 2021-02-17 2021-09-22 2021-08-16 ants, de matériels didactiqu nvelope es (puzzle, peinture, pâtes à modeler..) au profit de la Dir ection de l'Education Prescol aire (en deux lots) SN-MFFG-173357-GO-RFQ / Acquisition de fournitures de Request for Quota Single Stage - One E bureau et de consommables IDA / 63200 Quality early learning Post Limited 27,084.00 56,359.60 Completed 2020-11-17 2020-12-11 2021-01-12 2021-05-13 2021-07-11 2021-06-24 tions nvelope informatique pour l’UGP, le M FFGPE, les PMO dans le cadre de l’appui institutionnel. SN-MFFG-202533-GO-DIR / A cquisition de dispositif lave Child protection and system Under Imple mains et de kits d'hygiène po IDA / 63200 Post Direct Selection Direct 168,598.00 0.00 2020-11-05 2020-11-25 2020-11-10 2020-11-24 2020-11-19 2020-12-10 strengthening mentation ur les structures DIPE pour pr endre en charge la préventio n des élèves SN-MFFG-183263-GO-RFB / Acquisition de matériels dida Single Stage - One E ctiques (puzzle, peinture, pât IDA / 63200 Quality early learning Post Request for Bids Open - National 200,455.00 0.00 Canceled 2020-11-17 2020-11-22 2020-12-22 2021-01-06 2021-02-10 2021-03-27 nvelope es à modeler..) au profit de l a Direction de l'Education Pre scolaire SN-MFFG-214878-GO-RFQ / Request for Quota Single Stage - One E Acquisition de matériel et out IDA / 63200 Quality early learning Post Limited 5,454.00 0.00 Signed 2021-02-28 2022-11-08 2021-04-11 2021-05-26 tions nvelope ils de santé de nutrition pour l'ANPECTP SN-MFFG-216480-GO-RFQ / Acquisition de batterie cuisin Request for Quota Single Stage - One E e pour les DIPE dans les zone IDA / 63200 Quality early learning Post Limited 50,482.00 40,695.80 Signed 2021-03-02 2021-06-16 2021-04-27 2021-07-14 2021-10-24 tions nvelope s d'intervention du PIPADHS pour le compte de l'ANPECTP Page 2 SN-MFFG-216485-GO-RFQ / Project management and tec Request for Quota Single Stage - One E Pending Impl Acquisition de mobilier additi IDA / 63200 Post Limited 27,273.00 0.00 2021-02-22 2021-04-19 2021-10-16 hnical assistance tions nvelope ementation onnel pour l'unité de gestion du PIPADHS SN-MFFG-216490-GO-RFQ / Child protection and system Request for Quota Single Stage - One E Acquisition de tablette électr IDA / 63200 Post Limited 65,454.00 38,918.39 Signed 2021-03-08 2021-03-27 2021-05-03 2021-05-19 2021-10-30 strengthening tions nvelope onique pour la Direction de l' état civil SN-MFFG-217260-GO-RFQ / Acquisition de véhicules de s Child protection and system Request for Quota Single Stage - One E Pending Impl IDA / 63200 Post Limited 45,545.00 0.00 2021-03-15 2021-05-10 2021-11-06 upervision au profit de la Dir strengthening tions nvelope ementation ection de l'Etat civil SN-MFFG-216482-NC-RFQ / Doter les centres d'état civil Child protection and system Request for Quota Single Stage - One E IDA / 63200 Post Limited 83,636.00 59,241.26 Signed 2021-02-15 2021-06-03 2021-04-12 2021-07-14 2021-10-09 de registres et d'actes de na strengthening tions nvelope issance pour le compte de la Direction de l'état civil SN-MFFG-222109-GO-RFQ / Acquisition de matériel infor Request for Quota Single Stage - One E Under Imple matiques dans le cadre de l'a IDA / 63200 Quality early learning Post Limited 45,454.00 0.00 2021-03-28 2021-04-22 2021-05-23 2021-11-19 tions nvelope mentation ppui institutionnel pour l'exer cice 2021 au profit des PMO et du MFFGPE SN-MFFG-238592-GO-RFQ / Child protection and system Request for Quota Single Stage - One E acquisition et édition de supp IDA / 63200 Post Limited 3,900.00 11,865.07 Signed 2021-06-15 2021-06-01 2021-08-10 2021-07-08 2022-02-06 strengthening tions nvelope orts pour l'organisation de la JEA et de la SNE SN-MFFG-239705-GO-RFQ / Achat de téléphones portable s destinés aux animateurs co Project management and tec Request for Quota Single Stage - One E IDA / 63200 Post Limited 6,099.00 0.00 Signed 2021-06-20 2021-06-11 2021-08-15 2022-02-11 mmunautaires pour un suivi hnical assistance tions nvelope des plaintes potentielles aux projets de construction des 3 3 cases des tout-petits SN-MFFG-239802-GO-RFQ / Confection des outils d'enreg Project management and tec Request for Quota Single Stage - One E IDA / 63200 Post Limited 7,392.00 1,311.40 Signed 2021-07-03 2021-06-11 2021-08-28 2021-10-01 2022-02-24 istrement des griefs (registre hnical assistance tions nvelope s, récépissé de dépôt de grief s) SN-MFFG-239890-GO-RFQ / Project management and tec Request for Quota Single Stage - One E Achat mobilier et matériel de IDA / 63200 Post Limited 4,141.00 0.00 Signed 2021-06-27 2022-06-22 2021-08-22 2022-02-18 hnical assistance tions nvelope bureau complémentaire SN-MFFG-240231-GO-RFQ / Request for Quota Single Stage - One E Acquisition de dispositifs de l IDA / 63200 Quality early learning Post Limited 95,252.00 87,879.56 Signed 2021-06-28 2021-08-02 2021-08-23 2021-09-01 2022-02-19 tions nvelope avage des mains SN-MFFG-240237-GO-RFQ / Request for Quota Single Stage - One E Achat de kits lave main pour IDA / 63200 Quality early learning Post Limited 38,101.00 77,737.39 Signed 2021-06-27 2021-08-02 2021-08-22 2021-09-01 2022-02-18 tions nvelope les structures DIPE SN-MFFG-239876-GO-RFQ / Project management and tec Request for Quota Single Stage - One E achat de matériel informatiq IDA / 63200 Post Limited 35,200.00 0.00 Signed 2021-06-28 2021-06-22 2021-08-23 2022-02-19 hnical assistance tions nvelope ue complémentaire SN-MFFG-273475-GO-RFB / I Open - Internationa Single Stage - One E mpression et fourniture de liv IDA / 63200 Quality early learning Post Request for Bids 1,392,682.00 0.00 Signed 2022-03-25 2022-04-01 2022-03-25 2022-05-17 2022-05-11 2022-05-30 2022-06-10 2022-06-22 2022-07-15 2023-01-11 l nvelope rets de lecture pour enfants SN-MFFG-273482-GO-RFQ / I mpression de cahiers de qua Child protection and system Request for Quota Single Stage - One E IDA / 63200 Post Limited 73,986.00 61,330.97 Signed 2022-01-30 2021-09-14 2022-03-27 2021-10-06 2022-09-23 rtier et de village pour l'enre strengthening tions nvelope gistrement des naissances SN-MFFG-306992-GO-RFB / F Single Stage - One E ourniture de matériel de plei IDA / 63200 Quality early learning Post Request for Bids Open - National 144,123.00 0.00 Signed 2022-07-31 2022-05-05 2022-08-02 2022-09-02 2022-07-05 2022-09-16 2022-07-20 2022-10-03 2023-04-01 nvelope n air destiné aux structures DIPE SN-MFFG-309251-GO-RFQ / Acquisition de 10 000 registr Child protection and system Request for Quota Single Stage - One E IDA / 63200 Post Limited 78,000.00 0.00 Signed 2022-08-17 2022-02-22 2022-10-12 2023-04-10 es et 15 000 imprimés d'acte strengthening tions nvelope s de naissance destinés à la DEC. SN-MFFG-309253-GO-RFQ / Acquisition de 130 tablettes, Child protection and system Request for Quota Single Stage - One E IDA / 63200 Post Limited 94,936.00 0.00 Signed 2022-08-17 2022-02-02 2022-10-12 2023-04-10 15 ordinateurs portables et 3 strengthening tions nvelope 0 clés USB destinés à l'enquê te DIPE/ANSD. SN-MFFG-309254-GO-RFQ / Acquisition de balance, toise s et kit médicaments pour l'e Request for Quota Single Stage - One E nquête ESD dans le cadre du IDA / 63200 Quality early learning Post Limited 34,810.00 0.00 Completed 2022-08-12 2022-05-06 2022-09-05 2022-10-05 2022-07-04 tions nvelope projet Investir dans les premi ères années pour le Dévelop pement humain au Sénégal ( PIPADHS). SN-MFFG-309257-GO-RFQ / Project management and tec Request for Quota Single Stage - One E Acquisition de produits d'entr IDA / 63200 Post Limited 8,227.00 0.00 Completed 2022-08-17 2021-12-03 2022-10-12 2023-04-10 hnical assistance tions nvelope etien destinés à l'UGP du PIP ADHS. SN-MFFG-309258-GO-RFQ / Acquisition de Mobiliers de B Project management and tec Request for Quota Single Stage - One E Under Imple ureau (Lot 1) et Matériels Inf IDA / 63200 Post Limited 72,784.00 0.00 2022-08-17 2022-05-09 2022-10-12 2023-04-10 hnical assistance tions nvelope mentation ormatique (Lot 2) destinés au x PMO et à l'UGP dans le cadr e du PIPADHS. SN-MFFG-309261-GO-RFQ / Child protection and system Request for Quota Single Stage - One E Acquisition produits d'hygièn IDA / 63200 Post Limited 14,240.00 0.00 Signed 2022-08-14 2022-04-11 2022-08-29 2022-09-28 strengthening tions nvelope es au profit de l'ANPECTP. SN-MFFG-312381-GO-RFQ / Request for Quota Single Stage - One E Fournitures de matériels ludi IDA / 63200 Quality early learning Post Limited 88,500.00 0.00 Signed 2022-08-30 2022-09-13 2022-09-13 2022-10-13 tions nvelope ques destinés aux structures DIPE SN-MFFG-312386-GO-RFQ / Request for Quota Single Stage - One E Acquisition de matériels péd IDA / 63200 Quality early learning Post Limited 87,000.00 0.00 Signed 2022-09-03 2022-09-12 2022-10-29 2023-04-27 tions nvelope agogiques au profit de l'ANPE CTP. SN-MFFG-314779-GO-RFQ / Request for Quota Single Stage - One E Acquisition de batteries de c IDA / 63200 Quality early learning Post Limited 13,500.00 0.00 Signed 2022-09-12 2022-10-07 2022-11-07 2023-05-06 tions nvelope uisine destinées aux structur es DIPE Page 3 SN-MFFG-314780-GO-RFQ / Request for Quota Single Stage - One E Fournitures Scolaires pour le IDA / 63200 Quality early learning Post Limited 87,000.00 0.00 Signed 2022-09-12 2022-09-01 2022-11-07 2023-05-06 tions nvelope s structures DIPE SN-MFFG-314844-GO-RFQ / Child protection and system Request for Quota Single Stage - One E Acquisition de supports de co IDA / 63200 Post Limited 22,500.00 0.00 Signed 2022-09-12 2022-09-22 2022-11-07 2023-05-06 strengthening tions nvelope mmunication destinés à la D EC SN-MFFG-314862-GO-RFQ / Project management and tec Request for Quota Single Stage - One E Reproduction de supports de IDA / 63200 Post Limited 29,524.00 0.00 Signed 2022-10-19 2022-08-31 2022-12-14 2023-06-12 hnical assistance tions nvelope communication destinés à l’U GP. SN-MFFG-321347-GO-RFQ / Confection de supports de co Project management and tec Request for Quota Single Stage - One E IDA / 63200 Post Limited 8,700.00 0.00 Signed 2022-09-12 2022-05-06 2022-11-07 2023-05-06 mmunication pour l’organisat hnical assistance tions nvelope ion de la JEA et de la SNE au profit de la DPDPE SN-MFFG-314835-GO-RFQ / Project management and tec Request for Quota Single Stage - One E Acquisition de mobiliers de r IDA / 63200 Post Limited 18,000.00 0.00 Signed 2022-10-14 2022-09-01 2022-11-14 2022-12-14 hnical assistance tions nvelope angement au profit du DEC. SN-MFFG-321356-GO-RFQ / Reproduction de 75 130 cahi Project management and tec Request for Quota Single Stage - One E IDA / 63200 Post Limited 81,000.00 0.00 Signed 2022-09-12 2022-02-14 2022-11-07 2023-05-06 ers d'activité de l'éducation r hnical assistance tions nvelope eligieuse au profit de l'ANPEC TP SN-MFFG-321351-GO-RFQ / Reproduction de 5000 exem Project management and tec Request for Quota Single Stage - One E IDA / 63200 Post Limited 36,000.00 0.00 Completed 2022-09-12 2022-04-12 2022-11-07 2023-05-06 plaires du guide communaut hnical assistance tions nvelope aire au profit de la DPDPE SN-MFFG-321346-GO-RFQ / Project management and tec Request for Quota Single Stage - One E Under Imple Acquisition de mobiliers scola IDA / 63200 Post Limited 66,000.00 0.00 2022-10-14 2022-06-24 2022-11-14 2022-12-14 hnical assistance tions nvelope mentation ires destinés aux structures DIPE. SN-MFFG-314861-GO-RFQ / Project management and tec Request for Quota Single Stage - One E Reproduction de 35 000 carn IDA / 63200 Post Limited 99,254.00 0.00 Signed 2022-10-19 2022-09-08 2022-12-14 2023-06-12 hnical assistance tions nvelope ets de santé au profit de la D EC. SN-MFFG-321355-GO-RFQ / Reproduction de livrets de fa Project management and tec Request for Quota Single Stage - One E IDA / 63200 Post Limited 42,000.00 0.00 Signed 2022-09-12 2022-04-12 2022-11-07 2023-05-06 mille au profit de la Direction hnical assistance tions nvelope de l'Etat Civil DEC SN-MFFG-321345-GO-RFB / F ourniture de matériel didacti Single Stage - One E IDA / 63200 Quality early learning Post Request for Bids Open - National 109,125.00 0.00 Signed 2022-10-14 2022-06-01 2022-10-19 2022-11-21 2022-07-04 2022-11-27 2022-07-19 2022-12-10 2023-01-13 que et ludique pour les daara nvelope préscolaires publiques SN-MFFG-348305-GO-RFB / F Single Stage - One E Under Imple ourniture d’équipement de 1 IDA / 63200 Quality early learning Post Request for Bids Open - National 480,000.00 0.00 2023-03-09 2023-02-03 2023-03-09 2023-04-12 2023-05-03 2023-06-07 2023-09-15 nvelope mentation 4 Daaras Préscolaires Publics (DPP). SN-MFFG-348324-GO-RFB / F ourniture d’équipement de 9 Single Stage - One E Pending Impl IDA / 63200 Quality early learning Post Request for Bids Open - National 340,000.00 0.00 2023-03-09 2023-03-09 2023-04-12 2023-05-03 2023-06-07 2023-09-15 0 Classes Préparatoires à l’El nvelope ementation émentaire (CPE). SN-MFFG-348338-GO-RFB / F Single Stage - One E Under Imple ourniture d’équipement de 3 IDA / 63200 Quality early learning Post Request for Bids Open - National 400,000.00 0.00 2023-03-09 2023-02-20 2023-03-09 2023-04-12 2023-05-03 2023-06-07 2023-09-15 nvelope mentation 3 Cases des Tout-Petits (CTP) . SN-MFFG-348344-GO-RFB / Acquisition et acheminement Project management and tec Single Stage - One E Pending Impl de matériel de rayonnage po IDA / 63200 Post Request for Bids Open - National 240,000.00 0.00 2023-03-20 2023-03-25 2023-05-06 2023-06-05 2023-07-10 2024-01-06 hnical assistance nvelope ementation ur 252 Centres d’Etat Civil (C EC) au profit de la Direction d e l’Etat Civil (DEC). SN-MFFG-348348-GO-RFB / F ourniture de Manuels Scolair Single Stage - One E Pending Impl IDA / 63200 Quality early learning Post Request for Bids Open - National 675,000.00 0.00 2023-03-21 2023-03-26 2023-04-28 2023-05-18 2023-06-22 2023-12-19 es pour la Direction de l’Educ nvelope ementation ation Préscolaire (DEPS). SN-MFFG-348353-GO-RFQ / Child protection and system Request for Quota Single Stage - One E Under Imple Acquisition de 10 000 registr IDA / 63200 Post Limited 48,000.00 0.00 2023-03-14 2023-02-28 2023-05-09 2023-11-05 strengthening tions nvelope mentation es destinés à la DEC. SN-MFFG-348371-GO-RFQ / Acquisition de 500 000 impri Child protection and system Request for Quota Single Stage - One E IDA / 63200 Post Limited 45,000.00 0.00 Completed 2023-03-14 2023-02-10 2023-05-09 2023-11-05 més d’acte de naissance et 6 strengthening tions nvelope 00 états trimestriels destinés à la DEC. SN-MFFG-348384-GO-RFQ / Acquisition de deux (02) arm Request for Quota Single Stage - One E oires sous forme de bibliothè IDA / 63200 Quality early learning Post Limited 1,200.00 0.00 Signed 2023-03-14 2023-02-17 2023-05-09 2023-11-05 tions nvelope que pour l'archivage et la ge stion de la documentation au niveau de l'UGP. SN-MFFG-357908-GO-RFQ / Request for Quota Single Stage - One E Pending Impl Acquisition d'un logiciel intég IDA / 63200 Quality early learning Post Limited 58,000.00 0.00 2023-06-10 2023-07-22 2023-09-05 tions nvelope ementation ré de suivi évaluation pour le MFFPE. SN-MFFG-357914-GO-RFQ / Recrutement d’un prestatair e pour l’édition de 4 500 exe Project management and tec Request for Quota Single Stage - One E Pending Impl IDA / 63200 Post Limited 75,000.00 0.00 2023-08-28 2023-10-23 2024-04-20 mplaires du guide d'éducatio hnical assistance tions nvelope ementation n religieuse et 75 000 cahier s d’activités traduits en arab e. SN-MFFG-357915-GO-RFB / Dotation de salles multimédi Project management and tec Single Stage - One E Pending Impl IDA / 63200 Post Request for Bids Open - National 140,000.00 0.00 2023-08-09 2023-08-14 2023-09-25 2023-10-25 2023-11-29 2024-05-27 as pour les 33 cases des tout hnical assistance nvelope ementation -petits nouvellement construi tes. SN-MFFG-357925-GO-RFQ / Recrutement d'un prestataire pour la Production de tee-shi Child protection and system Request for Quota Single Stage - One E Pending Impl rt, de casquettes, de plaquet IDA / 63200 Post Limited 33,200.00 0.00 2023-07-24 2023-09-18 2024-03-16 strengthening tions nvelope ementation te, de flyers, de sacs de sport et de banderoles pour la com munication sur la promotion et la protection des droits de s enfants. Page 4 SN-MFFG-357926-GO-RFQ / Recrutement d'un prestataire pour la conception et l’éditio n des plaquettes et dépliants Child protection and system Request for Quota Single Stage - One E Pending Impl IDA / 63200 Post Limited 17,000.00 0.00 2023-07-23 2023-09-17 2024-03-15 sur les modèles de structurat strengthening tions nvelope ementation ion et de fonctionnement des CDPE, du dispositif communa utaire de protection et de pré sentation de la DPDPE. SN-MFFG-362702-GO-RFQ / Request for Quota Single Stage - One E Pending Impl Acquisition d’outils de gestio IDA / 63200 Quality early learning Post Limited 9,000.00 0.00 2023-11-20 2024-01-15 2024-07-13 tions nvelope ementation n pour les structures DIPE da ns 11 régions. SN-MFFG-357938-GO-RFQ / Acquisition de fourniture de b ureau, de consommables info Project management and tec Request for Quota Single Stage - One E Pending Impl IDA / 63200 Post Limited 94,000.00 0.00 2023-11-11 2023-12-13 2024-01-12 rmatiques et de produits d'e hnical assistance tions nvelope ementation ntretien et de nettoyage des bureaux pour l'UGP et les PM O(s). SN-MFFG-357947-GO-RFB / L 'équipement de la salle de ré Request for Quota Single Stage - One E Pending Impl union du ministère de la fem IDA / 63200 Quality early learning Post Limited 90,000.00 0.00 2023-12-04 2024-01-29 2024-07-27 tions nvelope ementation me, de la famille et de la prot ection des enfants (MFFPE). SN-MFFG-357948-GO-RFQ / Acquisition de matériels infor matique et logistiques (vidéo Project management and tec Request for Quota Single Stage - One E Pending Impl projecteur, imprimantes mult IDA / 63200 Post Limited 25,000.00 0.00 2023-07-16 2023-09-10 2024-03-08 hnical assistance tions nvelope ementation ifonctionnelle, ordinateurs po rtables performants, scanner , broyeuses, tablettes) au pro fit du MFFPE. NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SN-MFFG-135548-NC-RFQ / S Project management and tec Request for Quota Single Stage - One E ouscription police assurance IDA / 63200 Post Limited 37,818.00 8,254.96 Completed 2019-09-24 2019-09-23 2019-10-25 2019-11-01 2020-10-24 2019-12-03 hnical assistance tions nvelope maladie pour le personnel du PIPADHS SN-MFFG-136242-NC-RFB / I mpression du guide de gestio Request for Quota Single Stage - One E IDA / 63200 Quality early learning Post Limited 53,667.00 48,572.56 Completed 2019-12-16 2019-12-03 2020-02-10 2019-12-21 2020-03-26 2020-03-10 n pour les structures de la pe tions nvelope tite enfance (10000 exemplai res) SN-MFFG-146133-NC-RFQ / I mpression des outils de nutri Request for Quota Single Stage - One E IDA / 63200 Quality early learning Post Limited 15,705.00 14,627.00 Signed 2019-11-27 2020-01-03 2019-12-23 2019-12-20 2020-01-22 tion et des boites à images a tions nvelope u profit de l'ANPECTP SN-MFFG-152908-NC-RFQ / Recrutement d'une agence d Project management and tec Request for Quota Single Stage - One E IDA / 63200 Post Limited 11,637.00 457.80 Signed 2020-01-15 2020-01-16 2020-02-01 2020-02-28 2020-12-31 e gardiennage pour assurer l hnical assistance tions nvelope a sécurité des locaux du PIPA DHS SN-MFFG-138634-NC-RFQ / S Child nutrition and early sti élection d’une agence pour l Request for Quota Single Stage - One E IDA / 63200 mulation in the first 1,000 d Post Limited 36,364.00 0.00 Canceled 2020-06-02 2020-07-28 2021-01-24 a mise en œuvre de la straté tions nvelope ays gie de communication digital e au profit de la CLM SN-MFFG-138645-NC-RFQ / Recrutement d'un cabinet év Project management and tec Request for Quota Single Stage - One E IDA / 63200 Post Limited 55,000.00 0.00 Canceled 2019-10-26 2019-12-21 2020-06-18 énementiel pour organiser le hnical assistance tions nvelope lancement du projet PIPADHS SN-MFFG-183274-NC-RFQ / Recrutement d'un prestataire Project management and tec Request for Quota Single Stage - One E Under Imple pour assure la maintenance IDA / 63200 Post Limited 1,818.00 0.00 2020-07-27 2020-09-21 2021-03-20 hnical assistance tions nvelope mentation du parc informatique de l'uni té de gestion du PIPADHS SN-MFFG-183271-NC-RFQ / Recrutement de prestataire p Project management and tec Request for Quota Single Stage - One E IDA / 63200 Post Limited 1,636.00 1,724.51 Signed 2021-01-25 2021-08-13 2021-03-22 2021-11-05 2021-09-18 our assurer la maintenance d hnical assistance tions nvelope u matériel de froid SN-MFFG-136239-NC-RFQ / I mpression du guide de l'ense ignant en 14500 exemplaires (10K pour le système formel Request for Quota Single Stage - One E Pending Impl IDA / 63200 Quality early learning Post Limited 24,150.00 0.00 2021-03-03 2021-04-18 2021-05-18 à l'échelle nationale, 3000 po tions nvelope ementation ur les enseignants SMC, 500 pour les enseignants Daara e t 1000 pour les enseignants en éducation religieuse) SN-MFFG-214876-NC-RFQ / E dition et reproduction des ca Request for Quota Single Stage - One E Pending Impl hiers d'activités du curriculu IDA / 63200 Quality early learning Post Limited 99,345.00 0.00 2021-02-15 2021-04-01 2021-05-16 tions nvelope ementation m de l'éducation de base au profit de l'ANPECTP dans le c adre du PIPADHS SN-MFFG-216487-NC-RFQ / E Project management and tec Request for Quota Single Stage - One E Pending Impl ntretien et maintenance des l IDA / 63200 Post Limited 5,454.00 0.00 2021-03-20 2021-05-15 2021-11-11 hnical assistance tions nvelope ementation ocaux de l'UGP du PIPADHS SN-MFFG-216488-NC-RFQ / Project management and tec Under Imple Assurer le gardiennage des l IDA / 63200 Post Direct Selection Direct 6,000.00 0.00 2021-02-10 2021-02-26 2021-02-15 2021-03-22 2021-09-18 hnical assistance mentation ocaux de l'UGP du PIPADHS SN-MFFG-216486-NC-RFQ / Assurer la maintenance du ré Project management and tec Request for Quota Single Stage - One E IDA / 63200 Post Limited 2,000.00 2,749.89 Signed 2021-03-10 2021-08-13 2021-05-05 2021-10-09 2021-11-01 seau informatique et télépho hnical assistance tions nvelope nique de l'UGP PIPADHS SN-MFFG-246452-NC-RFQ / Project management and tec Request for Quota Single Stage - One E Reproduction de supports de IDA / 63200 Post Limited 27,216.00 23,585.32 Signed 2021-08-08 2021-08-04 2021-10-03 2021-09-22 2022-04-01 hnical assistance tions nvelope communication destinés à l'U GP Page 5 SN-MFFG-314820-NC-RFQ / L Request for Quota Single Stage - One E ocation de 13 véhicules 4X4 IDA / 63200 Quality early learning Post Limited 66,200.00 0.00 Signed 2022-09-12 2022-02-10 2022-11-07 2023-05-06 tions nvelope destinés à l’enquête EDS SN-MFFG-321352-NC-RFQ / I Request for Quota Single Stage - One E mpression du recueil d’activit IDA / 63200 Quality early learning Post Limited 19,900.00 0.00 Signed 2022-09-07 2022-07-06 2022-10-03 2022-11-02 tions nvelope és sous forme de jeux au pro fit de la DEPS SN-MFFG-314813-NC-RFQ / I mpression des cahiers d’acti Request for Quota Single Stage - One E Under Imple IDA / 63200 Quality early learning Post Limited 72,000.00 0.00 2022-10-14 2022-05-06 2022-11-09 2022-12-09 vité et des guides pédagogiq tions nvelope mentation ues des Daaras préscolaires SN-MFFG-314856-NC-RFQ / L ocation de sono, à la réalisati Request for Quota Single Stage - One E on de film et à la couverture IDA / 63200 Quality early learning Post Limited 31,450.00 0.00 Completed 2022-10-19 2022-05-31 2022-12-14 2023-06-12 2022-10-03 tions nvelope médiatique de la campagne de communication de la DPD PE. SN-MFFG-314815-NC-RFQ / I Request for Quota Single Stage - One E mpression du rapport de la S IDA / 63200 Quality early learning Post Limited 28,000.00 0.00 Signed 2022-10-14 2022-07-19 2022-11-09 2022-12-09 tions nvelope NPE au profit de la DPDPE SN-MFFG-321353-NC-RFQ / I Request for Quota Single Stage - One E IDA / 63200 Quality early learning Post Limited 65,000.00 0.00 Signed 2022-09-07 2022-05-25 2022-10-03 2022-11-02 mpression des documents du tions nvelope PNEP SN-MFFG-327255-NC-RFB / L ocations de 53 véhicules (50 Project management and tec Single Stage - One E Under Imple véhicules Pick up et 3 véhicul IDA / 63200 Post Request for Bids Open - National 252,000.00 0.00 2022-11-21 2023-01-07 2022-11-26 2023-01-07 2023-02-08 2023-02-06 2023-03-13 2023-09-09 hnical assistance nvelope mentation es station wagon) dans le ca dre de la collecte de l’EDS 20 22. SN-MFFG-333092-NC-RFQ / E dition de supports de commu Request for Quota Single Stage - One E nication pour la célébration d IDA / 63200 Quality early learning Post Limited 14,000.00 0.00 Signed 2022-12-26 2022-11-02 2023-02-20 2023-08-19 tions nvelope u 33ème anniversaire de l’ad option de la CDE au profit de la DPDPE. SN-MFFG-344133-NC-RFQ / I mpression et diffusion des 15 000 nouveaux guides (5000 Request for Quota Single Stage - One E Pending Impl IDA / 63200 Quality early learning Post Limited 61,000.00 0.00 2023-04-08 2023-06-03 2023-11-30 exemplaires par section) et 1 tions nvelope ementation 0 000 recueils de jeux pour l a Direction de l'Enseignemen t Préscolaire. SN-MFFG-357927-GO-RFQ / Recrutement d'un prestataire pour l’édition des supports d Child protection and system Request for Quota Single Stage - One E Pending Impl IDA / 63200 Post Limited 33,200.00 0.00 2023-11-27 2024-01-22 2024-07-20 e communication lors des év strengthening tions nvelope ementation ènements spéciaux dédiés à l'enfant (JEA et SNE, Annivers aire CDE). SN-MFFG-357928-NC-RFQ / Recrutement d'un prestataire Request for Quota Single Stage - One E Pending Impl IDA / 63200 Quality early learning Post Limited 56,500.00 0.00 2023-09-20 2023-10-16 2023-11-15 pour la reproduction des sup tions nvelope ementation ports de communication sur l e PNEP. SN-MFFG-357930-NC-RFQ / Recrutement d'un prestataire pour la conception, l’impressi Child protection and system Request for Quota Single Stage - One E Pending Impl on de supports, la publication IDA / 63200 Post Limited 7,500.00 0.00 2023-10-15 2023-12-10 2024-06-07 strengthening tions nvelope ementation de bannières et de bandeaux , la diffusion de spots et de b andes annonces pour la SNP ECTP. SN-MFFG-357932-NC-RFP / R ecruter un prestataire de ser Project management and tec Request for Quota Single Stage - One E Pending Impl vice pour le tri, l’empaquetag IDA / 63200 Post Limited 92,000.00 0.00 2023-10-22 2023-12-17 2024-06-14 hnical assistance tions nvelope ementation e et la distribution des livres de l’initiative Read@Home. SN-MFFG-357933-NC-RFQ / Recrutement d'un prestataire pour l’édition des supports et Child protection and system Request for Quota Single Stage - One E Pending Impl IDA / 63200 Post Limited 33,200.00 0.00 2023-06-13 2023-08-08 2024-02-04 outils de communication pou strengthening tions nvelope ementation r la poursuite de la campagn e de sensibilisation et de co mmunication sur la PEL. SN-MFFG-357934-NC-RFQ / Recrutement d'un prestataire pour l’édition du Guide sur l'é Child protection and system Request for Quota Single Stage - One E Pending Impl IDA / 63200 Post Limited 16,500.00 0.00 2023-08-27 2023-10-22 2024-04-19 thique journalistique et les dr strengthening tions nvelope ementation oits de l'enfant (impression d e 200 guides) au profit de la DPDPE. SN-MFFG-357943-NC-RFQ / Recrutement d'un prestataire pour l'édition et la communic Child protection and system Request for Quota Single Stage - One E Pending Impl IDA / 63200 Post Limited 99,500.00 0.00 2023-08-28 2023-10-23 2024-04-20 ation (prise en charge conve strengthening tions nvelope ementation ntion avec organes de presse s, support de com., spots, etc .) au profit du MFFPE. SN-MFFG-362703-NC-RFQ / I mpression de 200 000 guides Request for Quota Single Stage - One E Under Imple IDA / 63200 Quality early learning Post Limited 96,000.00 0.00 2023-08-18 2023-03-22 2023-09-13 2023-10-13 d’éducation parentale et 100 tions nvelope mentation rapports annuels. CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SN-MFFG-136285-CS-INDV / Sélection d’un consultant po ur la réalisation d’une Étude sur la situation de référence Consultant Qualifi IDA / 63200 Quality early learning Post Open - National 90,000.00 0.00 Canceled 2019-12-16 2019-12-21 2020-01-19 2020-02-09 2020-03-15 2020-09-11 de la prise en charge intégré cation Selection e de la Petite Enfance dans l es régions de Diourbel, Kaffri ne, Fatick, Kaolack, Kolda, Ta mbacounda et Matam Page 6 SN-MFFG-138601-CS-QCBS / Etude qualitative sur les nor Child nutrition and early sti Quality And Cost- mes de genre et les pratique IDA / 63200 mulation in the first 1,000 d Post Open - National 89,000.00 0.00 Canceled 2019-11-18 2019-12-09 2020-01-22 2020-02-19 2020-03-20 2020-04-24 2020-05-29 2020-06-07 Based Selection s de soins aux femmes et au ays x enfants au profit de la CLM SN-MFFG-167409-CS-QCBS / Recrutement d'un bureau de Consultant Qualifi contrôle pour les travaux de IDA / 63200 Quality early learning Post Open - National 83,333.00 79,141.83 Signed 2020-05-12 2020-08-27 2020-05-19 2020-06-16 2021-08-06 2020-06-23 2021-09-10 2020-07-07 2021-11-13 2021-01-03 cation Selection constructions de vingt deux (22) cases des tout-petits SN-MFFG-173369-CS-CQS / R ecrutement d'un cabinet pou Consultant Qualifi Under Implement r la réalisation de l'étude pou IDA / 63200 Quality early learning Post Open - National 66,666.00 0.00 2020-07-08 2020-05-19 2020-07-29 2020-12-22 2020-09-11 2020-10-11 2020-11-15 2021-05-14 cation Selection ation r l'élaboration d'un program me national d'éducation pare ntale SN-MFFG-178016-CS-CQS / S élection d’un cabinet pour la réalisation d’une Étude sur la cartographie des structures Consultant Qualifi DIPE (daaras, services d’éduc IDA / 63200 Quality early learning Post Open - National 54,545.00 81,023.67 Signed 2020-06-23 2020-07-01 2020-07-14 2020-08-27 2020-07-10 2020-09-26 2020-07-09 2020-10-31 2021-01-30 2021-04-29 cation Selection ation préscolaire et d’appren tissage précoce) dans les rég ions de Diourbel, Kaffrine, Fa tick, Kaolack, Kolda, Tambac ounda et Matam SN-MFFG-178019-CS-CQS / s élection d'un cabinet pour la Consultant Qualifi réalisation de l'étude de référ IDA / 63200 Quality early learning Post Open - National 54,545.00 0.00 Canceled 2020-06-30 2020-06-17 2020-07-21 2020-09-03 2020-10-03 2020-11-07 2021-05-06 cation Selection ence sur le développement d e l'enfant au profit de l'ANPE CPT SN-MFFG-315591-CS-CQS / R ecrutement d’un cabinet pou r la conception de supports p Project management and tec Consultant Qualifi Under Implement IDA / 63200 Post Limited 23,250.00 0.00 2022-09-13 2022-09-12 2022-09-27 2022-10-27 2022-12-01 2023-05-30 our soutenir des actions de p hnical assistance cation Selection ation laidoyer de communication e t de sensibilisation sur la prot ection des enfants en ligne. SN-MFFG-314841-CS-INDV / Recrutement d'un consultant Project management and tec Consultant Qualifi Under Implement individuel pour l'atelier de for IDA / 63200 Post Limited 4,500.00 0.00 2022-10-03 2022-08-11 2022-10-17 2022-11-16 2022-12-21 2023-06-19 hnical assistance cation Selection ation mation des enfants sur leurs droits et l’autoprotection. SN-MFFG-309323-NC-RFQ / Recrutement d'une Agence o Project management and tec Consultant Qualifi Pending Impleme u Cabinet de communication IDA / 63200 Post Limited 96,265.00 0.00 2022-10-03 2022-10-17 2022-11-16 2022-12-21 2023-06-19 hnical assistance cation Selection ntation pour la mise en œuvre de la communication du program me de Read@Home. SN-MFFG-357921-CS-CQS / R ecrutement d’un bureau suivi Consultant Qualifi Pending Impleme IDA / 63200 Quality early learning Post Limited 50,000.00 0.00 2023-05-02 2023-05-16 2023-06-15 2023-07-20 2024-01-16 des constructions de 33 CTP cation Selection ntation (deuxième phase). SN-MFFG-357923-CS-CQS / R ecrutement d’un bureau de c Consultant Qualifi Pending Impleme IDA / 63200 Quality early learning Post Limited 83,000.00 0.00 2023-05-02 2023-05-16 2023-06-15 2023-07-20 2024-01-16 ontrôle technique des constr cation Selection ntation uctions des 33 CTP (deuxièm e phase) SN-MFFG-362706-CS-CQS / R ecrutement d’un bureau de s Consultant Qualifi Pending Impleme IDA / 63200 Quality early learning Post Limited 93,200.00 0.00 2023-06-07 2023-06-21 2023-07-21 2023-08-25 2024-02-21 uivi des constructions des 60 cation Selection ntation CPE (deuxième phase). SN-MFFG-362707-CS-CQS / R ecrutement d’un bureau de c Consultant Qualifi Pending Impleme IDA / 63200 Quality early learning Post Limited 93,200.00 0.00 2023-06-05 2023-06-19 2023-07-19 2023-08-23 2024-02-19 ontrôle des constructions des cation Selection ntation 60 CPE (Deuxième phase). SN-MFFG-362710-CS-CQS / R Project management and tec Consultant Qualifi Pending Impleme ecrutement d'un consultant p IDA / 63200 Post Limited 55,000.00 0.00 2023-08-11 2023-08-25 2023-09-24 2023-10-29 2024-04-26 hnical assistance cation Selection ntation our l’Audit genre du Ministèr e. SN-MFFG-362711-CS-CQS / R ecrutement d'un consultant p Project management and tec Consultant Qualifi Pending Impleme IDA / 63200 Post Limited 55,000.00 0.00 2023-09-14 2023-09-28 2023-10-28 2023-12-02 2024-05-30 our la Gestion électronique d hnical assistance cation Selection ntation es documents (Consultants, équipements). INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SN-MFFG-136279-CS-INDV / Sélection d’un consultant po ur la réalisation d’une Étude sur la cartographie des struct Individual Consult ures DIPE (daaras, services d IDA / 63200 Quality early learning Post Limited 60,000.00 0.00 Canceled 2019-10-15 2019-10-21 2019-10-28 2019-11-14 2019-12-29 ant Selection ’éducation préscolaire et d’a pprentissage précoce) dans l es régions de Diourbel, Kaffri ne, Fatick, Kaolack, Kolda, Ta mbacounda et Matam SN-MFFG-136284-CS-INDV / Sélection d’un consultant indi viduel pour la réalisation d’u Individual Consult ne Étude sur l’implication de IDA / 63200 Quality early learning Post Limited 30,000.00 17,646.24 Completed 2019-11-27 2019-11-21 2019-11-27 2019-12-03 2019-12-04 2020-01-08 2019-12-25 2020-01-18 2019-12-31 ant Selection s collectivités locales dans la prise en charge du Développ ement Intégré de la Petite En fance SN-MFFG-145124-CS-INDV / Recrutement d'un consultant Project management and tec Individual Consult individuel pour l'élaboration IDA / 63200 Post Limited 9,090.00 7,647.75 Signed 2019-11-20 2019-12-23 2019-11-25 2019-12-17 2019-12-02 2020-01-17 2019-12-24 2020-01-21 2020-06-21 hnical assistance ant Selection de la charte graphique et du plan branding du PIPADHS. Page 7 SN-MFFG-145863-CS-INDV / Recrutement d'un consultant Individual Consult pour l'étude sur la cartograp IDA / 63200 Quality early learning Post Limited 10,909.00 0.00 Canceled 2019-11-25 2020-01-10 2019-11-25 2019-12-05 2019-12-17 2020-02-15 ant Selection hie du système d'information et de gestion au profit de l'A NPECTP SN-MFFG-146131-CS-INDV / RECRUTEMENT D’UN CONSU Project management and tec Individual Consult LTANT POUR LA CONCEPTION IDA / 63200 Post Limited 13,636.00 12,518.70 Completed 2019-11-28 2019-12-18 2019-12-03 2019-12-19 2019-12-10 2020-01-16 2019-12-24 2020-02-13 2020-02-07 hnical assistance ant Selection DU SYSTEME DE SUIVI-EVALU ATION DU PIPADHS SN-MFFG-145118-CS-INDV / Recrutement de consultant i nternational pour rénover le Individual Consult Under Implement IDA / 63200 Quality early learning Post Open 36,000.00 0.00 2020-01-15 2020-01-14 2020-02-24 2020-03-09 2020-04-13 2020-05-28 curriculum et les guides et le ant Selection ation cahier d'activités pour l’appr entissage précoce (système f ormel) SN-MFFG-138631-CS-INDV / Sélection d’un consultant indi Child nutrition and early sti Individual Consult viduel pour l’élaboration du p IDA / 63200 mulation in the first 1,000 d Post Limited 18,180.00 0.00 Canceled 2020-06-17 2020-06-22 2020-07-13 2020-08-17 2021-02-13 ant Selection lan de communication autour ays du dialogue communautaire au profit de la CLM SN-MFFG-155428-CS-INDV / Recrutement d'un consultant Child nutrition and early sti Individual Consult individuel pour assurer la for IDA / 63200 mulation in the first 1,000 d Post Limited 8,950.00 0.00 Canceled 2020-01-27 2020-01-24 2020-01-30 2020-02-10 2020-02-17 2020-03-18 ant Selection mation des agents du BEN en ays gestion financière au profit d e la CLM SN-MFFG-155427-CS-INDV / Recrutement d'un consultant Child nutrition and early sti Individual Consult individuel pour assurer la for IDA / 63200 mulation in the first 1,000 d Post Limited 8,950.00 0.00 Canceled 2020-01-27 2020-01-24 2020-01-27 2020-02-10 2020-02-17 2020-03-18 ant Selection mation des agents du BEN en ays Passation des marchés au pr ofit de la CLM SN-MFFG-168047-CS-INDV / Recrutement d'un consultant Individual Consult Under Implement IDA / 63200 Quality early learning Post Limited 10,000.00 0.00 2020-08-04 2020-07-08 2020-08-09 2020-08-26 2020-08-30 2020-10-04 2021-04-02 pour élaborer un Guide d’édu ant Selection ation cation religieuse pour les Cas es des Tout Petits SN-MFFG-168066-CS-INDV / Individual Consult réaliser une étude de référen IDA / 63200 Quality early learning Post Limited 10,000.00 0.00 Canceled 2020-05-20 2020-05-25 2020-06-15 2020-07-20 2021-01-16 ant Selection ce sur le développement de l'enfant SN-MFFG-168079-CS-INDV / Recrutement d'un consultant Project management and tec Individual Consult IDA / 63200 Post Limited 13,333.00 12,592.79 Signed 2020-04-22 2020-04-15 2020-04-27 2020-07-21 2020-05-18 2020-08-25 2020-06-22 2020-09-22 2020-12-19 individuel pour la mise en pla hnical assistance ant Selection ce du site web du PIPADHS SN-MFFG-168073-CS-INDV / Recruter un consultant indivi Individual Consult duel pour réaliser une étude IDA / 63200 Quality early learning Post Limited 16,666.00 0.00 Canceled 2020-06-10 2020-06-15 2020-07-06 2020-08-10 2021-02-06 ant Selection sur les pratiques parentales dans les premières années p our le compte de l'ANPECTP SN-MFFG-168075-CS-INDV / Sélection d'un consultant indi Project management and tec Individual Consult viduel pour l'élaboration de l IDA / 63200 Post Limited 20,000.00 0.00 Signed 2020-04-29 2020-04-29 2020-05-04 2020-09-07 2020-05-25 2020-09-30 2020-06-29 2020-12-26 hnical assistance ant Selection a stratégie et le plan de com munication du PIPADHS. SN-MFFG-173371-CS-INDV / Sélection d’un consultant po ur la réalisation d’une Étude sur la cartographie des struct Individual Consult ures DIPE (daaras, services d IDA / 63200 Quality early learning Post Limited 16,363.00 0.00 Canceled 2020-06-10 2020-05-18 2020-06-15 2020-07-06 2020-08-10 2021-02-06 ant Selection ’éducation préscolaire et d’a pprentissage précoce) dans l es régions de Diourbel, Kaffri ne, Fatick, Kaolack, Kolda, Ta mbacounda et Matam SN-MFFG-173372-CS-INDV / Recruter un consultant indivi Individual Consult duel pour l'élaboration du gui IDA / 63200 Quality early learning Post Limited 15,000.00 22,009.56 Signed 2020-07-15 2020-05-15 2020-07-20 2020-06-17 2020-08-10 2020-07-14 2020-09-14 2020-07-28 2021-03-13 ant Selection de d'activités pour les Comit és de Gestion des Ecoles SN-MFFG-202535-NC-RFB / R ecrutement d'un personnel e Project management and tec Individual Consult Pending Impleme IDA / 63200 Post Open 33,842.00 0.00 2021-02-03 2021-03-24 2021-04-14 2021-05-19 2021-11-15 n suivi-évaluation pour l'unit hnical assistance ant Selection ntation é de gestion du PIPADHS SN-MFFG-217267-CS-INDV / Recrutement d'un consultant Project management and tec Individual Consult Pending Impleme individuel pour la conception IDA / 63200 Post Limited 5,454.00 0.00 2021-03-03 2021-03-08 2021-03-29 2021-05-03 2021-10-30 hnical assistance ant Selection ntation d'un système de informatisé de gestion. des plaintes dans le cadre du MGP SN-MFFG-202534-CS-CDS / R ecrutement d'un consultant e n suivi et évaluation pour ap Project management and tec Individual Consult Pending Impleme IDA / 63200 Post Direct 7,272.00 0.00 2021-02-05 2021-02-15 2021-03-08 2021-04-12 2021-10-09 puyer l'UGP pour la phase de hnical assistance ant Selection ntation transition avant le recruteme nt d'un personnel permanent pour l'UGP SN-MFFG-167411-CS-CQS / R ecrutement d'un bureau de s IDA / 63200 Quality early learning Post Direct Selection Direct 116,666.00 0.00 Under Review 2021-03-15 2020-08-24 2021-03-25 2021-05-29 2021-11-25 uivi pour la construction de tr ente trois (33) cases des tou t-petits SN-MFFG-239827-CS-CQS / r ecrutement d'un consultant p Project management and tec Individual Consult our le renforcement des capa IDA / 63200 Post Limited 2,310.00 0.00 Under Review 2021-06-30 2021-05-28 2021-07-05 2021-07-26 2021-08-30 2022-02-26 hnical assistance ant Selection cités des animateurs du MGG en dynamique communautair e SN-MFFG-314809-CS-INDV / Recrutement d'un consultant pour l'animation des ateliers Project management and tec Individual Consult Pending Impleme régionaux de partage de la st IDA / 63200 Post Limited 4,900.00 0.00 2022-09-07 2022-09-12 2022-10-03 2022-11-07 2023-05-06 hnical assistance ant Selection ntation ratégie et des outils d'intégra tion des dimensions transver sales dont la nutrition et le DI PE dans la planification territ oriale. Page 8 SN-MFFG-314810-CS-INDV / recrutement d'un consultant Project management and tec Individual Consult Under Implement IDA / 63200 Post Limited 3,700.00 0.00 2022-09-07 2022-07-21 2022-09-12 2022-10-03 2022-11-07 2023-05-06 pour la capitalisation des exp hnical assistance ant Selection ation ériences du PIPADHS à l’an 3 SN-MFFG-314812-CS-INDV / Elaboration d’un projet de loi sur la sécurité des enfants co ntre les formes d’abus sexuel Project management and tec Individual Consult Pending Impleme IDA / 63200 Post Limited 10,300.00 0.00 2022-09-07 2022-09-12 2022-10-03 2022-11-07 2023-05-06 s et d’exploitation en ligne et hnical assistance ant Selection ntation l’animation de l’atelier de ren forcement des capacités des acteurs sur l’exploitation sex uelle des enfants en ligne SN-MFFG-314817-CS-INDV / Recrutement d'un Infographi ste pour la conception des ill Project management and tec Individual Consult IDA / 63200 Post Limited 5,200.00 0.00 Signed 2022-09-07 2022-06-01 2022-09-12 2022-06-01 2022-09-19 2022-06-13 2022-10-11 2023-04-09 ustrations graphiques et de l hnical assistance ant Selection a mise en forme de la maque tte de la boite a image pour l e PIPADHS SN-MFFG-314837-CS-INDV / Recrutement d'un consultant Project management and tec Individual Consult Under Implement individuel pour le renforceme IDA / 63200 Post Limited 2,800.00 0.00 2022-09-07 2022-08-17 2022-09-12 2022-10-03 2022-11-07 2023-05-06 hnical assistance ant Selection ation nt des capacités acteurs du P IPADHS en violences Basées sur le Genre (VBG). SN-MFFG-314839-CS-INDV / Recrutement d'un consultant Project management and tec Individual Consult Under Implement individuel pour l'animation d IDA / 63200 Post Limited 3,250.00 0.00 2022-09-07 2022-08-17 2022-09-12 2022-10-03 2022-11-07 2023-05-06 hnical assistance ant Selection ation u module Hygiène Sécurité e t Environnement (HSE). SN-MFFG-314845-CS-INDV / recrutement d'un consultant Project management and tec Individual Consult Under Implement individuel pour la mise en pla IDA / 63200 Post Limited 88,500.00 0.00 2022-09-07 2022-08-19 2022-09-12 2022-10-03 2022-11-07 2023-05-06 hnical assistance ant Selection ation ce du Système d’Information et de Suivi sur le DIPE. SN-MFFG-314846-CS-INDV / Recrutement d'un consultant individuel pour la conception, Project management and tec Individual Consult Pending Impleme IDA / 63200 Post Limited 22,250.00 0.00 2022-09-07 2022-09-12 2022-10-03 2022-11-07 2023-05-06 la rédaction des articles, et la hnical assistance ant Selection ntation mise en page et l’Impression du bulletin semestriel d’infor mation du PIPADHS. SN-MFFG-314847-CS-INDV / Recrutement d'un consultant Project management and tec Individual Consult Pending Impleme individuel pour l'hébergemen IDA / 63200 Post Limited 1,950.00 0.00 2022-09-07 2022-09-12 2022-09-19 2022-10-11 2023-04-09 hnical assistance ant Selection ntation t du Site WEB et des pages d édiées au Projet sur les résea ux sociaux . SN-MFFG-314855-CS-INDV / Recrutement d'un consultant Project management and tec Individual Consult Under Implement individuel pour la digitalisatio IDA / 63200 Post Limited 6,500.00 0.00 2022-09-07 2021-09-01 2022-09-12 2022-10-03 2022-11-07 2023-05-06 hnical assistance ant Selection ation n des jeux et jouets tradition nels et de réalisation d’applic ation Android et/ou IOS. SN-MFFG-314858-CS-INDV / Recrutement d'un consultant individuel pour la conception Project management and tec Individual Consult Under Implement de visuels, de spot, à la diffu IDA / 63200 Post Limited 23,000.00 0.00 2022-09-07 2022-06-01 2022-09-12 2022-10-03 2022-11-07 2023-05-06 hnical assistance ant Selection ation sion de B.A. et au sponsoring des émissions de la campagn e de communication de la DP DPE. SN-MFFG-323214-CS-INDV / Recrutement d'un consultant individuel pour la production et la diffusion de supports de Project management and tec Individual Consult Pending Impleme IDA / 63200 Post Limited 44,500.00 0.00 2022-10-24 2022-10-29 2022-11-19 2022-12-24 2023-06-22 communication visuels, audi hnical assistance ant Selection ntation o et digital sur la protection d es droits des enfants et le Dé veloppement Intégré de la Pe tite Enfance DIPE. SN-MFFG-323213-CS-INDV / Recrutement d'un consultant Project management and tec Individual Consult Pending Impleme IDA / 63200 Post Limited 1,000.00 0.00 2022-10-24 2022-10-29 2022-11-19 2022-12-24 2023-06-22 individuel pour l'atelier de re hnical assistance ant Selection ntation nforcement de capacités des agents de la DPDPE. SN-MFFG-357912-CS-INDV / Recrutement d’un consultant Individual Consult Pending Impleme pour la traduction des guides IDA / 63200 Quality early learning Post Limited 13,000.00 0.00 2023-06-12 2023-06-17 2023-07-08 2023-08-12 2024-02-08 ant Selection ntation et cahiers d'activité en langu e arabe au profit de l'ANPECT P. SN-MFFG-357935-CS-INDV / Recrutement de consultants f Project management and tec Individual Consult Pending Impleme IDA / 63200 Post Limited 19,000.00 0.00 2023-11-22 2023-11-27 2023-12-18 2024-01-22 2024-07-20 ormateurs pour le renforcem hnical assistance ant Selection ntation ent des capacités des agents de l'ANPECTP. SN-MFFG-357936-CS-INDV / Recrutement d'un prestataire Project management and tec Individual Consult Pending Impleme IDA / 63200 Post Limited 83,000.00 0.00 2023-07-11 2023-07-16 2023-08-06 2023-09-10 2024-03-08 pour la conception et la mise hnical assistance ant Selection ntation en place d’un système d'infor mation et de suivi SN-MFFG-357937-CS-INDV / Recrutement d'un prestataire pour la formation des acteurs Project management and tec Individual Consult Pending Impleme IDA / 63200 Post Limited 29,000.00 0.00 2023-09-21 2023-09-26 2023-10-17 2023-11-21 2024-05-19 des niveaux central et décon hnical assistance ant Selection ntation centré sur le système d'infor mation et de suivi au profit d e l'ANPECTP. Page 9 PROJET DE DEVELOPPEMENT LOCAL ET D’ADAPTATION AUX CHANGEMENTS CLIMATIQUES (ALBIA) ___________________________________________________________ PLAN SIMPLIFIE DE PASSATION DES MARCHES (PPM) – SEPTEMBRE 2019 Information sur le Projet : Pays : République du Tchad; Nom du Projet : Projet de Développement Local et d’Adaptation aux changements climatiques (ALBIA) Numéro d’Identification du projet : P171611 Agence d’exécution du Projet : Projet de Renforcement de la Résilience Climatique et de la Productivité Agricole Durable (ProPAD) Date du plan de passation des marchés : Septembre 2019 Période couverte par ce plan de passation des marchés : Octobre 2019- Septembre 2020 Préambule Conformément au paragraphe 5.9 du “Règlement de Passation des Marchés pour les Emprunteurs sollicitant le Financement de Projets d’Investissement (FPI)” (Juillet 2016) (“Règlement de Passation des Marchés”) le Système électronique de la Banque de suivi systématique des transactions de marchés publics (STEP) sera utilisé pour préparer, valider et actualiser les plans de passation des marchés et effectuer toutes les transactions liées à la passation des marchés du projet. Ce texte ainsi que les tableaux du plan de passation des marchés présents dans STEP constituent le plan de passation des marchés du projet. Les conditions suivantes s'appliquent à toutes les activités de passation de marchés du plan de passation de marchés. Les autres éléments du plan de passation des marchés tels que requis au paragraphe 4.4 du Règlement de passation des marchés sont énoncés dans STEP. Les Dossiers types de passation des marchés publics de la Banque devront être utilisés pour tous les contrats soumis à la concurrence internationale, ainsi que pour tous les autres contrats soumis à cette obligation telle que spécifiée dans les tableaux du plan de passation des marchés de STEP. Procédures nationales de passation des marchés : En accord avec le paragraphe 5.3 du Règlement de passation des marchés, dans le cas où la procédure de passation des marchés se fera au niveau national (telle que spécifiée dans les tableaux du plan de passation des marchés inclus de STEP), les procédures nationales de passation des marchés du pays considéré pourront être utilisées. Si l’Emprunteur utilise ses propres procédures d’appel d’offres national ouvert telles qu’énoncées dans le Décret No 2417/PR/PM/2015 du 17 Décembre 2015 portant Code des Marches Publics au Tchad, ces arrangements sont soumis aux dispositions du paragraphe 5.4 du Règlement de passation des marchés et aux conditions suivantes : 1 a) Les entreprises éligibles de tout pays peuvent concourir ; b) Le dossier d’appel d’offres/a propositions oblige le Soumissionnaire/Proposant présentant une Offre/Proposition à déposer un agreement signe, qui sera joint à tout contrat éventuel, pour confirmer qu’il applique et respecte les Directives de la Banque pour la lutte contre la corruption, y compris sans limitation, le droit de la Banque de sanctionner et les droits de la Banque pour l’inspection et l’audit ; c) Les marchés doivent comporter une répartition appropriée des attributions, risques et responsabilités ; d) Les documents de passation des marchés incluent des dispositions, convenues avec la Banque, destinées à atténuer de manière adéquate les risques et impacts environnementales, sociaux (y compris l’exploitation et les abus sexuels et la violence basée sur le genre), l’hygiène et la sécurité (« EHS ») e) La publication des informations relatives à l’attribution du marché ; f) Le droit de la Banque d’examiner le dossier et les activités de passation des marchés ; g) L’existence d’un mécanisme efficace d’examen des plaintes ; et h) La gestion et l’archivage des dossiers relatifs au Processus de passation des marchés. Lorsque l’Emprunteur utilise d’autres procédures que l’appel d’offres national ouvert, ces procédures devront être en accord avec les dispositions du paragraphe 5.5 du Règlement de passation des marchés. Crédit-bail tel que spécifié au paragraphe 5.10 du Règlement de Passation des marchés : Le crédit-bail peut être utilisé pour les contrats indiqués comme tel dans le Plan de passation des marchés : « Sans objet » Achat de biens d’occasion tel que spécifié au paragraphe 5.11du Règlement de Passation des Marchés est autorisé pour les contrats indiqués comme tel dans le Plan de passation des marchés. « Sans objet » Préférence nationale telle que spécifiée au paragraphe 5.51 du Règlement de Passation des Marchés (Fournitures et Travaux). Fournitures : ne s’applique pas Travaux ne s’applique pas Autres informations pertinentes sur la passation des marchés : « Sans Objet » Les seuils pour les méthodes de passation des marchés : Les seuils de passation des marchés se présentent comme suit au vu des conditions du marché : 2 PROCUREMENT Chad : Chad Local Development and Adaptation Project PLAN General Information Country: Chad 2022-04-06 Bank’s Approval Date of the Original Procurement Plan: 2023-06-02 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P171611 GPN Date: 2021-01-14 Project Name: Chad Local Development and Adaptation Project Loan / Credit No: IDA / D6730 Sahara Conservation Fund-ALBIA Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TD-SCF-ALBIA-317169-GO-DI Component 1. Sustainable N Direct - Internation R / Acquisition d'un avion lég IDA / D6730 atural Resources Manageme Post Direct Selection 130,000.00 0.00 Canceled 2022-09-27 2022-09-26 2022-10-02 2022-09-27 2022-11-06 2023-05-05 al er nt and Protected Areas TD-SCF-ALBIA-274180-GO-R Component 1. Sustainable N Request for Quota Single Stage - One E FQ / Equipement/Uniformes E IDA / D6730 atural Resources Manageme Post Limited 30,000.00 0.00 Canceled 2023-01-25 2022-12-12 2023-03-15 2023-05-14 tions nvelope cogarde nt and Protected Areas TD-SCF-ALBIA-328588-GO-R Component 1. Sustainable N FQ / Achat des filtres, lubrifia Request for Quota Single Stage - One E IDA / D6730 atural Resources Manageme Post Limited 2,364.00 0.00 Signed 2022-11-30 2022-11-10 2023-01-25 2023-07-24 nts et pièces détachées pour tions nvelope nt and Protected Areas les véhicules de terrain. TD-SCF-ALBIA-328589-GO-R Component 1. Sustainable N Single Stage - One E Under Imple FB / Acquisition des moyens r IDA / D6730 atural Resources Manageme Post Request for Bids Open - National 440,000.00 0.00 2022-11-30 2022-11-01 2022-12-05 2023-02-03 2023-01-16 2023-01-12 2023-02-15 2023-03-22 2023-09-18 nvelope mentation oulants et engins en 4 lots. nt and Protected Areas TD-SCF-ALBIA-340397-GO-R Component 1. Sustainable N Request for Quota Single Stage - One E FQ / ACHAT CARBURANT 202 IDA / D6730 atural Resources Manageme Post Limited 55,527.00 0.00 Signed 2023-02-09 2023-01-10 2023-04-06 2023-10-03 tions nvelope 3 nt and Protected Areas TD-SCF-ALBIA-340408-GO-R Component 1. Sustainable N Request for Quota Single Stage - One E FQ / Achat des filtres, huile et IDA / D6730 atural Resources Manageme Post Limited 34,255.00 0.00 Signed 2023-02-08 2023-01-10 2023-04-05 2023-10-02 tions nvelope pneus des véhicules nt and Protected Areas Component 1. Sustainable N TD-SCF-ALBIA-340417-GO-R Request for Quota Single Stage - One E IDA / D6730 atural Resources Manageme Post Limited 3,700.00 0.00 Signed 2023-02-08 2023-01-10 2023-04-05 2023-10-02 FQ / Fourniture de bureau tions nvelope nt and Protected Areas TD-SCF-ALBIA-346804-GO-R Component 1. Sustainable N FQ / Achat des équipements Request for Quota Single Stage - One E IDA / D6730 atural Resources Manageme Post Limited 3,700.00 0.00 Signed 2023-03-07 2023-02-22 2023-05-02 2023-10-29 camp de passage et gardiens tions nvelope nt and Protected Areas de la Base de Arada TD-SCF-ALBIA-346810-GO-R Component 1. Sustainable N FQ / Achat matériels informat Request for Quota Single Stage - One E IDA / D6730 atural Resources Manageme Post Limited 8,950.00 0.00 Signed 2023-03-07 2023-02-28 2023-05-02 2023-10-29 iques au profit du personnel tions nvelope nt and Protected Areas du projet ALBIA/SC TD-SCF-ALBIA-317185-GO-R Component 1. Sustainable N FQ / Acquisition des pièces d Request for Quota Open - Internationa Single Stage - One E Pending Impl IDA / D6730 atural Resources Manageme Post 8,000.00 0.00 2023-07-05 2023-08-30 2024-02-26 étachées, consommables et tions l nvelope ementation nt and Protected Areas outillages pour un avion lége r. TD-SCF-ALBIA-356548-GO-R Component 1. Sustainable N Request for Quota Single Stage - One E FQ / Achat carburant au profi IDA / D6730 atural Resources Manageme Post Limited 11,900.00 0.00 Signed 2023-04-18 2023-03-27 2023-06-13 2023-12-10 tions nvelope t du SECTEUR DE LA FAUNE S nt and Protected Areas UD ET NORD TD-SCF-ALBIA-356559-GO-R Component 1. Sustainable N FQ / Achat des pneus, des filt Request for Quota Single Stage - One E IDA / D6730 atural Resources Manageme Post Limited 7,230.00 0.00 Signed 2023-04-18 2023-03-27 2023-06-13 2023-12-10 res et de l'huile moteur au pr tions nvelope nt and Protected Areas ofit du SECTEUR DE LA FAUN E SUD ET NORD TD-SCF-ALBIA-364584-GO-R Component 1. Sustainable N Request for Quota Single Stage - One E FQ / Achat des uniformes et IDA / D6730 atural Resources Manageme Post Limited 30,000.00 0.00 Signed 2023-06-20 2022-12-07 2023-08-15 2024-02-11 tions nvelope équipements des écogardes nt and Protected Areas NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TD-SCF-ALBIA-315342-CS-Q Component 1. Sustainable N CBS / Etude, contrôle et supe Quality And Cost- IDA / D6730 atural Resources Manageme Post Open - National 118,794.00 0.00 Signed 2022-10-10 2022-10-10 2022-10-31 2022-10-25 2022-12-14 2022-12-03 2023-01-11 2023-01-11 2023-02-10 2023-01-31 2023-03-17 2023-02-13 2023-04-21 2024-04-20 rvision des travaux de constr Based Selection nt and Protected Areas uction d'une base vie et des avants postes. TD-SCF-ALBIA-340432-CS-C QS / Actualisation du notice d Component 1. Sustainable N Consultant Qualifi 'impact environnemental et IDA / D6730 atural Resources Manageme Post Limited 3,637.00 0.00 Signed 2023-02-03 2023-02-03 2023-02-17 2023-02-17 2023-03-19 2022-04-05 2023-04-23 2023-10-20 cation Selection social pour les travaux de co nt and Protected Areas nstruction d'une base vie à A rada Page 1 INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TD-SCF-ALBIA-281149-CS-IN DV / Étude technique pour un Component 1. Sustainable N Individual Consult Pending Impleme e meilleure compréhension d IDA / D6730 atural Resources Manageme Post Open - National 10,000.00 0.00 2023-11-02 2023-12-03 2023-12-10 2024-01-07 2024-03-07 ant Selection ntation e l'utilisation pastorale de la nt and Protected Areas réserve et des implications d u zonage sur sa pratique TD-SCF-ALBIA-281152-CS-IN Component 1. Sustainable N DV / Développement touristi Individual Consult Pending Impleme IDA / D6730 atural Resources Manageme Post Open - National 20,000.00 0.00 2024-01-10 2024-02-10 2024-02-17 2024-03-16 2024-05-15 que – Etude pour le potentiel ant Selection ntation nt and Protected Areas de développement touristiqu e Page 2 Plan de passation des marches (PPM) Information sur le projet : Projet de Promotion de la Gestion intégrée et de l’Economie des Déchets Solides au Sénégal (PROMOGED) Agence de mise en Œuvre du projet : Unité de Coordination de la Gestion des déchets solides (UCG) Date de la Plan de passation des marchés : Décembre 2017 Période couverte par le présent Plan de passation des marchés : Décembre 2017 à décembre 2019 Niveau de Risque de la passation des marchés : Substantiel Préambule Conformément au paragraphe 5.9 du “Règlement de Passation des Marchés pour les Emprunteurs sollicitant le Financement de Projets d’Investissement (FPI)” (Juillet 2016 et mis à jour en novembre 2017) (“Règlement de Passation des Marchés”) l’Emprunteur utilise les outils électroniques de planification et de suivi de la passation des marchés (STEP) pour préparer, valider et actualiser ses plans de passation des marchés et effectuer toutes les transactions liées à la passation des marchés du projet. Cette partie textuelle ainsi que les tableaux du plan de passation des marchés dans STEP constituent le plan de passation des marchés du projet. Les conditions suivantes s'appliquent à toutes les activités de passation de marchés du plan de passation de marchés. Les autres éléments du plan de passation des marchés tels que requis au paragraphe 4.4 du Règlement de passation des marchés sont énoncés dans STEP. Les Dossiers types d’appel d’offres publiés par la Banque devront être utilisés pour tous les contrats soumis à la concurrence internationale ainsi que pour tous les autres contrats spécifiés dans les tableaux du plan de passation des marchés inclus dans STEP. Procédures nationales de passation des marchés : En accord avec le paragraphe 5.3 du Règlement de passation des marchés, au cas où la procédure de passation des marchés est retenue (telle que spécifiée dans les tableaux du plan de passation des marchés inclus dans STEP), les procédures de passation de marchés du pays considéré peuvent être appliquées. Si l’Emprunteur utilise ses propres procédures d’appel d’offres national ouvert telles qu’énoncées dans le code des marchés du Sénégal: DÉCRET n° 2014 - 1212 du 22 Septembre 2014 PORTANT CODE DES MARCHÉS PUBLICS, ces dispositions devront être soumis à l'alinéa 5.4 de la réglementation des marchés et les conditions suivantes. Seule la liste applicable conditions nécessaires pour assurer la cohérence avec le paragraphe 5.4 de la réglementation des marchés. Si aucune des conditions s'appliquent, à supprimer les mots "et des conditions suivantes". Lorsque l’Emprunteur utilise d’autres procédures que l’appel d’offres national ouvert, ces procédures devront être en accord avec les dispositions du paragraphe 5.5 du Règlement de passation des marchés. Crédit-bail tel que spécifié au paragraphe 5.10 du Règlement de Passation des marchés : Le crédit-bail peut être utilisé pour les contrats indiqués dans le Plan de passation des marchés. « Sans objet » Achat de biens d’occasion tel que spécifié au paragraphe 5.11 du Règlement de Passation des Marchés est autorisé pour les contrats indiqués dans le Plan de passation des marchés. « Sans objet » Préférence nationale telle que spécifiée au paragraphe 2.1 du Règlement de Passation des Marchés (Fournitures et Travaux). Fournitures : ne s’applique pas pour les contrats indiqués dans les tableaux du Plan de passation des marchés : sans objet Travaux ne s’applique pas pour les contrats indiqués dans les tableaux du Plan de passation des marchés : sans objet 1. Seuil d’examen préalable : contrats qui seront soumis à l’examen préalable de la Banque conformément aux seuils de revue en vigueur effectif depuis Juillet 2016. N° Méthode de sélection Seuil d’examen Commentaires préalable 1. Services de consultants >ou=1.000.000 - Examen (firmes) préalable pour tous les marchés 2. Consultants firme ou > ou = 1.000.000 Examen individuels (entente préalable pour directe) tous les marchés Consultants individuels > ou = 300.000 Examen 3. basé sur comparaison des préalable pour CV tous les marchés 2. Préqualification. Sans Objet. 3. Procédures applicable aux Composantes relatives au Développement Conduit par les Communautés : Sans objet. 4. Référence (si nécessaire) au Manuel opérationnel/passation de marchés : Manuel des projets IDA 5. Marchés et Planning et Méthode de Passation : Description Monta Métho Cible Revue Date Date Date Démarr Fin des Observati nt de de national/internati à priori prévue prévue prévue age des prestati ons Estima Sélecti onal / pour la pour d’attribut prestati ons tif en on Posteri sollicitatio l’ouvertu ion du ons en ori n des re des contrat millier manifestat propositi s de ions ons USD d'intérêt techniqu TTC es sélection d’un consultant A individuel charge de la 150 CI National posterio 2-mai-18 12-mai-18 3-juin-18 25-juin- 24-août- 3 mois réalisation du cadre de 000 ri 18 18 gestion environnementale et sociale (CGES) et du cadre de politique de réinstallation (CPR) au niveau des villes secondaires sélection d’un consultant CI National A 2-mai-18 12-mai-18 3-juin-18 25-juin- 4-août- 40 jours individuel charge de 50 000 posterio 18 18 l'élaboration du manuel ri des opération du PROMOGED appui à la gestion du CI National A 8-déc.-17 21-déc.- 12 mois projet - sélection d’un 100 posterio 17 consultant individuel 000 ri spécialiste en sauvegarde environnementale appui à la gestion du CI National A 4-déc.-17 21-déc.- 12 mois projet - sélection d’un 100 posterio 17 consultant individuel 000 ri spécialiste en appui expert en appui institutionnel et reforme juridique appui à la gestion du CI National A 30-déc.-17 18-déc.- 12 mois projet - sélection d’un 100 posterio 17 consultant individuel 000 ri spécialiste en gestion financière et comptable Appui à la gestion du CI National A 26-avr.-18 12 mois projet - sélection d’un 100 posterio consultant individuel 000 ri spécialiste en communication / marketing social et développement communautaire appui à la gestion du CI National A 4-déc.-17 21-déc.- 12 mois projet - sélection d’un 100 posterio 17 consultant individuel 000 ri spécialiste en passation de marches Description Monta Métho Cibles Revue Date Date Date Démarr Fin des Observati nt de de national/internati à priori prévue prévue prévue age des prestati ons Estima Sélecti onal / pour la pour d’attribut prestati ons tif en on Posteri sollicitatio l’ouvertu ion du ons en ori n des re des contrat millier manifestat propositi s de ions ons USD d'intérêt techniqu TTC es Date de 66 jours 44 jours 33 jours démarrage ouvrés ouvrés ouvrés sélection d’un cabinet Firme International A 1-juin-18 6-août-18 19-sept.- 22-oct.- 19-juin- 8 mois Juillet - d’assistance à la maitrise 400 SFQC posterio 18 18 19 Mars d’ouvrage pour la 000 ri 2018 contractualisation d'un ppp dans le cadre de la réalisation et de l'exploitation des infrastructures de gestion des déchets solides de la région de Dakar sélection d’un cabinet en Firme National A 5-mai-18 10-juil.-18 23-août-18 25-sept.- 22-févr.- 5 Mois Juillet - charge de la réalisation 300 QC posterio 18 19 Décemb EIES et par des 000 ri re 2018 infrastructures de gestion des déchets solides de la région de Dakar sélection d’un cabinet Firme International A 23-mars-18 28-mai-18 11-juil.-18 13-août- 10-avr.- 8 Mois Août - d’assistance à la maitrise 550 SFQC posterio 18 19 Avril d’ouvrage pour étude 000 ri 2019 définition du projet de résorption et de conception détaillée et préparation des documents de consultation et suivi des travaux de résorption du site de Mbeubeuss sélection d’un cabinet en ED International A 3-mai-18 8-juil.-18 21-août-18 23-sept.- 20-févr.- 5 mois Septem charge de la réalisation 200 posterio 18 19 bre - EIES et par pour les 000 ri Février travaux de résorption du 2019 site de Mbeubeuss sélection d’un cabinet Firme International A 3-mai-17 8-juil.-17 21-août-17 23-sept.- 20-févr.- 5 mois Septem d’assistance à la maitrise 350 SFQC posterio 17 18 bre - d’ouvrage pour la 000 ri Février l’élaboration des plans 2019 intercommunaux de gestion des déchets pour les pôles Thiés, Casamance et nord sélection d’un cabinet Firme International A 23-avr.-18 28-juin-18 11-août-18 13-sept.- 11-mai- 9 mois Septem pour l’appui à la 200 SFQC posterio 18 19 bre - Mai définition du cadre de 000 ri 2019 réforme de la fiscalité directe et l’appui à l’opérationnalisation de l’ECOTAXE pour le secteur des déchets solides municipaux au Sénégal PROCUREMENT Senegal : Senegal Municipal Solid Waste Management Project PLAN General Information Country: Senegal 2018-05-03 Bank’s Approval Date of the Original Procurement Plan: 2023-06-02 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P161477 GPN Date: Project Name: Senegal Municipal Solid Waste Management Project Loan / Credit No: / , IDA / 65520, IDA / V1600, IDA / 65530 Unité de coordination de la Gestion des déchets solides (UCG) Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned National Procure SN-PROMOGED-179832-CW- Improving Solid Waste Infras ment Document - Request for Quota Single Stage - One E 2022-08-2 RFQ / Aménagement des loca IDA / 65530 tructure and Services in Sele Post Limited 1 Envelope proce 20,000.00 14,114.67 Completed 2022-01-03 2021-09-28 2022-02-28 2021-12-14 tions nvelope 7 ux et installation cted Agglomerations ss (Non Bank-SPD ) National Procure SN-PROMOGED-226246-CW- ment Document - RFQ / Travaux d'aménageme Project Implementation Sup Request for Quota Single Stage - One E 2023-07-2 IDA / 65520 Post Open - National 1 Envelope proce 200,000.00 0.00 Canceled 2022-12-05 2023-01-30 nt des plateformes actives d port tions nvelope 9 ss (Non Bank-SPD e la décharge de Mbeubeus ) SN-PROMOGED-231988-CW- National Procure RFQ / Aménagement d'une pl ment Document - Project Implementation Sup Request for Quota Single Stage - One E 2021-12-2 ate forme et d'une voie d'ac IDA / 65520 Post Open - National 1 Envelope proce 36,000.00 28,323.29 Completed 2021-05-05 2021-06-30 2021-05-13 port tions nvelope 7 cès pour le cortège président ss (Non Bank-SPD iel à l'occasion du lancement ) du Projet PROMOGED SN-PROMOGED-226251-CW- RFB / LES TRAVAUX DE REHA National Procure BILITATION DE LA PISTE D’AC ment Document - Project Implementation Sup Single Stage - One E 2022-10-0 CES ET D’AMENAGEMENT D’ IDA / 65520 Post Request for Bids Open - National 1 Envelope proce 560,000.00 492,427.36 Signed 2021-12-15 2021-07-27 2021-12-20 2021-07-27 2022-01-31 2021-09-10 2022-03-02 2021-09-27 2022-04-06 2021-12-24 port nvelope 3 UNE PLATEFORME DE DECHA ss (Non Bank-SPD RGEMENT AU NIVEAU DE LA ) DECHARGE DE DANS LA COMMUNE DE MALI KA SN-PROMOGED-259672-CW- Request for Bids - Improving Solid Waste Infras RFB / Travaux d'aménageme Open - Internationa Single Stage - One E Small Works SPD Under Imple 2022-10-2 IDA / 65530 tructure and Services in Sele Post Request for Bids 586,000.00 0.00 2022-01-06 2022-06-01 2022-01-11 2022-06-01 2022-02-22 2022-07-21 2022-03-24 2022-08-22 2022-04-28 nt de décharges au niveau d l nvelope (1 envelope proce mentation 5 cted Agglomerations es pôles en trois (03) lots ss) SN-PROMOGED-226480-CW- Request for Quota RFQ / Travaux d'aménageme Project Implementation Sup Request for Quota Single Stage - One E 2022-11-1 IDA / 65520 Post Limited tions (Non Bank-S 96,000.00 78,439.02 Signed 2022-03-23 2022-03-28 2022-05-18 2022-05-06 nt d'infrastructures intermédi port tions nvelope 4 PD) aires pour le dispositif de pré collecte SN-PROMOGED-259680-CW- Request for Bids - Improving Solid Waste Infras RFB / Travaux de constructio Open - Internationa Single Stage - One E Small Works SPD 2023-01-0 IDA / 65530 tructure and Services in Sele Post Request for Bids 1,500,000.00 0.00 Signed 2022-03-22 2022-03-23 2022-03-27 2022-03-23 2022-05-08 2022-04-28 2022-06-07 2022-07-06 2022-07-12 n des infrastructures intermé l nvelope (1 envelope proce 8 cted Agglomerations diaires pour Dakar et les pôle ss) s en quatre (04) lots SN-PROMOGED-276756-CW- Request for Bids - RFB / Travaux de constructio Improving Solid Waste Infras Open - Internationa Single Stage - One E Works (without pr 14,160,000.0 2023-08-1 n du Centre de Tri et de Tran IDA / 65530 tructure and Services in Sele Prior Request for Bids 0.00 Canceled 2022-04-26 2022-05-01 2022-06-12 2022-07-12 2022-08-16 l nvelope equalification) SP 0 6 sfert (CTT) & plateforme de c cted Agglomerations D ompostage de la décharge d e Mbeubeuss National Procure SN-PROMOGED-177919-CW- Improving Solid Waste Infras ment Document - Open - Internationa Single Stage - Two E 28,320,000.0 2023-02-2 RFB / Réalisation des travaux IDA / 65520 tructure and Services in Sele Prior Request for Bids 1 Envelope proce 0.00 Canceled 2022-03-24 2022-03-29 2022-05-10 2022-07-23 2022-08-27 l nvelope 0 3 de résorption de la décharge cted Agglomerations ss (Non Bank-SPD de Mbeubues ) SN-PROMOGED-282956-CW- Request for Bids - Improving Solid Waste Infras RFB / Réalisation des Travau Open - Internationa Single Stage - One E Works (without pr 28,320,000.0 Under Imple 2023-08-1 IDA / 65530 tructure and Services in Sele Prior Request for Bids 0.00 2022-04-28 2022-06-17 2022-05-03 2022-08-23 2022-06-14 2022-09-29 2022-07-14 2023-02-24 2022-08-18 x de réhabilitation de la déch l nvelope equalification) SP 0 mentation 8 cted Agglomerations arge de Mbeubeuss D SN-PROMOGED-295205-CW- National Procure RFB / Travaux de terrasseme Improving Solid Waste Infras ment Document - Request for Quota Single Stage - One E 2023-08-1 nts de la plateforme de réinst IDA / 65530 tructure and Services in Sele Post Limited 1 Envelope proce 99,600.00 0.00 Signed 2022-12-19 2022-06-09 2023-02-13 tions nvelope 2 allation de places d’affaires s cted Agglomerations ss (Non Bank-SPD ur une superficie de 2,5 hect ) ares National Procure SN-PROMOGED-295208-CW- Strengthening Sector Gover ment Document - Request for Quota Single Stage - One E 2023-08-2 RFQ / Travaux de réfection d IDA / 65530 nance and Institutional Capa Post Limited 1 Envelope proce 64,000.00 0.00 Signed 2023-01-03 2022-06-09 2023-02-28 tions nvelope 7 es locaux de la DEFCCS sis à city ss (Non Bank-SPD Mbao ) SN-PROMOGED-301669-CW- Request for Bids - RFB / TRAVAUX DE CONSTRU Works (after preq Improving Solid Waste Infras CTION DU CENTRE DE TRI ET Open - Internationa Single Stage - One E ualification) SPD - 14,160,000.0 Under Imple 2024-08-3 IDA / 65530 tructure and Services in Sele Prior Request for Bids 0.00 2022-08-10 2023-05-18 2022-10-26 2022-10-26 2022-08-15 2023-06-12 2023-01-04 2023-02-03 2023-03-10 DE TRANSFERT (CTT) & PLAT l nvelope Applying contract 0 mentation 1 cted Agglomerations EFORME DE COMPOSTAGE D or disqualificiatio E LA DECHARGE DE MBEUBE n USS SN-PROMOGED-301690-CW- National Procure RFB / Travaux de constructio Improving Solid Waste Infras ment Document - Single Stage - One E Under Imple 2023-07-3 n de l'herbié national de Mba IDA / 65520 tructure and Services in Sele Post Request for Bids Open - National 1 Envelope proce 400,000.00 0.00 2022-10-12 2022-10-19 2022-10-17 2022-10-20 2022-11-28 2022-11-24 2022-12-28 2022-12-04 2023-02-01 nvelope mentation 1 o dans le cadre de la convent cted Agglomerations ss (Non Bank-SPD ion avec les Eaux et Forêts ) SN-PROMOGED-323149-CW- Request for Bids - Improving Solid Waste Infras RFB / Aménagement du Cent Open - Internationa Single Stage - One E Small Works SPD Pending Imp 2024-04-0 IDA / 65530 tructure and Services in Sele Post Request for Bids 2,000,000.00 0.00 2023-06-14 2023-06-19 2023-07-31 2023-08-30 2023-10-04 re de Regroupement et de C l nvelope (1 envelope proce lementation 1 cted Agglomerations ommercialisation (CRC) de ss) Mbeubeuss National Procure SN-PROMOGED-323151-CW- Improving Solid Waste Infras ment Document - RFB / Construction de Points Single Stage - One E Under Imple 2024-03-1 IDA / 65530 tructure and Services in Sele Post Request for Bids Open - National 1 Envelope proce 300,000.00 0.00 2023-05-30 2023-05-05 2023-06-04 2023-06-01 2023-07-16 2023-08-15 2023-09-19 de Regroupement normalisé nvelope mentation 7 cted Agglomerations ss (Non Bank-SPD ( PRN) à Dakar - Phase 2 ) National Procure SN-PROMOGED-323155-CW- Improving Solid Waste Infras ment Document - RFB / Construction de murs d Single Stage - One E Under Imple 2024-05-0 IDA / 65530 tructure and Services in Sele Post Request for Bids Open - National 1 Envelope proce 2,400,000.00 0.00 2023-07-20 2023-05-25 2023-07-25 2023-05-26 2023-09-05 2023-10-05 2023-11-09 e clôture des CIVD de Sébiko nvelope mentation 7 cted Agglomerations ss (Non Bank-SPD tane et de Bambilor ) Page 1 SN-PROMOGED-295202-CW- National Procure RFQ / Travaux d’aménageme ment Document - Project Implementation Sup Request for Quota Single Stage - One E 2023-08-2 nt, de décoration et d’ameub IDA / 65530 Post Limited 1 Envelope proce 12,000.00 0.00 Canceled 2022-12-27 2023-02-21 port tions nvelope 0 lement des locaux du PROMO ss (Non Bank-SPD GED au 3ème étage ) National Procure SN-PROMOGED-262105-CW- Improving Solid Waste Infras ment Document - Single Stage - One E Pending Imp 2026-06-1 RFB / Travaux d'aménageme IDA / 65530 tructure and Services in Sele Post Request for Bids Open - National 1 Envelope proce 600,000.00 0.00 2025-08-22 2025-08-27 2025-10-08 2025-11-07 2025-12-12 nvelope lementation 0 nts paysagers et espaces ver cted Agglomerations ss (Non Bank-SPD ts ) SN-PROMOGED-177936-CW- RFB / Réalisation des infrastr Improving Solid Waste Infras Request for Bids - uctures à Dakar (CTT Mbeub Open - Internationa Single Stage - Two E 75,410,000.0 2028-02-2 IDA / 65530 tructure and Services in Sele Prior Request for Bids Works SPD (after 0.00 Canceled 2025-12-17 2026-03-04 2026-03-04 2025-12-22 2026-05-13 2026-08-30 eus, CTT Mbao, CTT Diameni l nvelope 0 1 cted Agglomerations prequalification) adio, CTT de Sébikhotane,CIV D de Bambilor CET et CTT en 6 lots SN-PROMOGED-178925-CW- RFB / Travaux de constructio Improving Solid Waste Infras Request for Bids - n des bâtimants (PRN-CRC;C Open - Internationa Single Stage - Two E 45,649,552.0 2026-11-0 IDA / 65530 tructure and Services in Sele Prior Request for Bids Plant SPD (after 0.00 Canceled 2024-08-30 2024-11-15 2024-11-15 2024-09-04 2025-01-24 2025-04-08 2025-05-13 T-CTT;CET-CIVD et Réhabilita l nvelope 0 4 cted Agglomerations prequalification) tion décharge) avec fournitu re d'équipement pour le Pôle NORD en 5 lots SN-PROMOGED-178927-CW- RFB / Travaux de constructio Improving Solid Waste Infras Request for Bids - Open - Internationa Single Stage - Two E 23,387,507.0 2027-03-1 n des bâtiments (PRN-CRC;C IDA / 65530 tructure and Services in Sele Prior Request for Bids Plant SPD (after 0.00 Canceled 2025-01-06 2025-03-24 2025-03-24 2025-01-11 2025-06-02 2025-08-15 2025-09-19 l nvelope 0 3 T-CRC-CTT;CET-CIVD et Réha cted Agglomerations prequalification) bilitation décharge )pour le P ôle Casamance en 6lots SN-PROMOGED-179436-CW- RFB / Travaux de constructio Improving Solid Waste Infras n des bâtiments (PRN-CRC-.C Open - Internationa Single Stage - Two E 24,936,325.0 2024-05-1 IDA / 65530 tructure and Services in Sele Prior Request for Bids 0.00 Canceled 2022-03-10 2022-05-26 2022-05-26 2022-03-15 2022-08-04 2022-10-17 2022-11-21 TT-CRC;CET-CIVD et Réhabilit l nvelope 0 4 cted Agglomerations ation de décharge) avec four niture d'équipements pour le s Pôles Thiés en 7lots GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SN-PROMOGED-81170-GO-R Strengthening Sector Gover Request for Quota Single Stage - One E Under Imple FQ / Acquisition de matériels IDA / V1600 nance and Institutional Capa Post Limited 26,000.00 0.00 2018-10-25 2018-11-12 2018-11-25 2018-12-25 tions nvelope mentation et mobiliers de bureau city SN-PROMOGED-81173-GO-R Project Implementation Sup Request for Quota Single Stage - One E FQ / Acquisition de fourniture IDA / V1600 Post Limited 6,136.00 5,520.98 Completed 2018-10-29 2018-11-14 2018-12-24 2018-12-12 2019-01-23 2019-01-04 port tions nvelope s de bureau et consommable s informatiques SN-PROMOGED-152983-GO- Project Implementation Sup Request for Quota Single Stage - One E IDA / V1600 Post Limited 3,000.00 2,399.08 Signed 2020-01-12 2019-12-23 2020-03-08 2020-01-16 2020-09-04 RFQ / Achat d'un photocopie port tions nvelope ur SN-PROMOGED-173550-GO- RFQ / Achat de fournitures po Project Implementation Sup Request for Quota Single Stage - One E IDA / V1600 Post Limited 99,859.00 90,912.08 Completed 2020-05-15 2020-05-15 2020-05-25 2020-06-05 2020-05-29 2020-07-01 ur le plan de sensibilistaion e port tions nvelope t de communication sur la C OVID -19 SN-PROMOGED-179541-GO- Improving Solid Waste Infras Request for Quota Single Stage - One E RFQ / Acquisition Mobiliers et IDA / 65530 tructure and Services in Sele Post Limited 45,548.00 91,542.99 Completed 2020-11-17 2020-11-02 2021-01-12 2020-12-16 2021-07-11 2021-04-07 tions nvelope matériels de bureau UGP/Pôl cted Agglomerations es SN-PROMOGED-179544-GO- Improving Solid Waste Infras Request for Quota Single Stage - One E RFQ / Acquisition de véhicule IDA / 65530 tructure and Services in Sele Post Limited 308,000.00 382,104.36 Signed 2020-10-20 2021-01-19 2020-12-15 2021-10-13 2021-06-13 2022-01-06 tions nvelope s UGP/Pôles cted Agglomerations SN-PROMOGED-179825-GO- Improving Solid Waste Infras RFQ / Acquisition d'équipeme Request for Quota Single Stage - One E IDA / 65530 tructure and Services in Sele Post Limited 73,432.00 90,380.14 Completed 2020-10-20 2020-12-04 2020-12-15 2021-01-22 2021-06-13 2021-04-02 nts informatiques et équipem tions nvelope cted Agglomerations ents pour le SIG UGP/Pôles SN-PROMOGED-225274-GO- RFQ / Achat équipements inf Project Implementation Sup Request for Quota Single Stage - One E IDA / 65530 Post Limited 5,500.00 5,225.04 Completed 2021-05-25 2021-03-30 2021-07-20 2021-04-22 2022-01-16 2021-06-10 ormatiques pour mise en œu port tions nvelope vre du PAR de Mbeubues SN-PROMOGED-225277-GO- RFQ / Achat fournitures et co Project Implementation Sup Request for Quota Single Stage - One E IDA / 65530 Post Limited 2,500.00 2,045.18 Completed 2021-05-25 2021-03-30 2021-07-20 2021-04-22 2022-01-16 2021-06-10 nsommables pour mise en œ port tions nvelope uvre du PAR de Mbeubeus SN-PROMOGED-226245-GO- RFB / Acquisition d'équipeme Project Implementation Sup Single Stage - One E IDA / 65520 Post Request for Bids Open - National 240,000.00 178,729.67 Signed 2021-11-18 2021-07-27 2021-11-23 2021-07-27 2022-01-04 2021-09-08 2022-02-03 2021-09-20 2022-03-10 2021-12-14 2022-09-06 nts de protection pour les tra port nvelope vailleurs de la décharge de M beubeus SN-PROMOGED-227436-GO- RFQ / Acquisition matériel et Project Implementation Sup Request for Quota Single Stage - One E IDA / 65520 Post Limited 100,000.00 0.00 Canceled 2021-12-28 2022-02-22 2022-08-21 logiciel Visio conférence / Ins port tions nvelope tallation et abonnement SN-PROMOGED-231983-GO- RFQ / Acquisition de fournitur es et d'équipements pour l'a Project Implementation Sup Request for Quota Single Stage - One E IDA / 65520 Post Open - National 100,000.00 90,440.96 Completed 2021-05-04 2021-06-29 2021-05-11 2021-12-26 2021-06-26 ppui aux écoles dans le cadr port tions nvelope e de la mise en oeuvre des m esures d'urgence de Mbeube us SN-PROMOGED-231972-GO- DIR / Achat de cinquante (5 Project Implementation Sup 0) tricycles dans le cadre du IDA / 65520 Post Direct Selection Direct 200,000.00 149,572.48 Completed 2021-04-29 2021-04-28 2021-05-04 2021-04-22 2021-06-08 2021-06-30 2021-12-05 2021-06-30 port projet de modernisation de la pré-collette des déchets au S énégal SN-PROMOGED-248593-GO- Improving Solid Waste Infras Open - Internationa Single Stage - One E Pending Impl RFB / Acquisition des équipe IDA / 65530 tructure and Services in Sele Post Request for Bids 649,066.00 0.00 2025-06-10 2025-06-15 2025-07-27 2025-08-26 2025-09-30 2026-03-29 l nvelope ementation ments de pré-collecte pour l cted Agglomerations e Grand Dakar Page 2 SN-PROMOGED-177937-GO- Improving Solid Waste Infras Single Stage - One E RFB / Acquisition des équipe IDA / 65530 tructure and Services in Sele Post Request for Bids Open - National 649,066.00 0.00 Canceled 2021-07-07 2021-07-12 2021-08-23 2021-09-22 2021-10-27 2022-04-25 nvelope ments de pré-collecte pour l cted Agglomerations e Grand Dakar SN-PROMOGED-152979-GO- Project Implementation Sup Request for Quota Single Stage - One E RFQ / Achat de fournitures de IDA / V1600 Post Limited 3,300.00 0.00 Canceled 2021-11-30 2022-01-25 2022-07-24 port tions nvelope bureau et consommables inf ormatiques SN-PROMOGED-252100-GO- RFQ / Acquisition de fournitur Project Implementation Sup Request for Quota Single Stage - One E IDA / 65530 Post Open - National 100,000.00 80,137.10 Completed 2021-10-04 2021-11-29 2021-12-25 2022-05-28 2022-02-01 es de bureau et consommabl port tions nvelope es informatiques UGP/Pôles SN-PROMOGED-179543-GO- Improving Solid Waste Infras RFB / Acquisition de fournitur Single Stage - One E IDA / 65530 tructure and Services in Sele Post Request for Bids Open - National 201,139.00 0.00 Canceled 2022-01-05 2022-01-10 2022-02-21 2022-03-23 2022-04-27 2022-10-24 es de bureau et consommabl nvelope cted Agglomerations es informatiques UGP/Pôles SN-PROMOGED-254968-GO- RFQ / Achat mobiliers ,matéri Project Implementation Sup Request for Quota Single Stage - One E els de bureau et équipement IDA / 65530 Post Open - National 90,000.00 74,716.09 Signed 2021-11-07 2022-01-02 2021-12-24 2022-07-01 port tions nvelope s informatiques pour personn el complémentaire du PROJE T SN-PROMOGED-259678-GO- RFB / Acquisition de petits m Improving Solid Waste Infras Open - Internationa Single Stage - One E Under Imple atériel de nettoiement, d'équ IDA / 65530 tructure and Services in Sele Prior Request for Bids 2,210,200.00 0.00 2022-01-04 2022-02-16 2022-01-09 2022-03-03 2022-02-20 2022-04-21 2022-03-22 2022-09-14 2022-04-26 2022-10-23 l nvelope mentation ipement de protection individ cted Agglomerations uelle, de bacs et de poubelle s en cinq (05) lots SN-PROMOGED-262143-GO- RFQ / Acquisition de divers m Project Implementation Sup Request for Quota Single Stage - One E Pending Impl atériels pour l'amélioration d IDA / 65530 Post Limited 20,000.00 0.00 2022-01-16 2022-03-13 2022-09-09 port tions nvelope ementation e la communication du PROM OGED (Totem, appareils phot os, etc.) SN-PROMOGED-226487-GO- Project Implementation Sup Request for Quota Single Stage - One E RFQ / Acquisition de mobilier IDA / 65520 Post Limited 89,100.00 72,483.52 Completed 2022-01-31 2022-03-28 2022-03-28 2022-05-16 2022-09-24 2022-10-18 port tions nvelope s urbains pour le dispositif de pré collecte SN-PROMOGED-262341-GO- RFQ / Recrutement d'un Pres Project Implementation Sup Request for Quota Single Stage - One E tataire chargé de la réalisatio IDA / 65530 Post Limited 30,000.00 0.00 Signed 2022-01-30 2021-12-15 2022-03-27 2022-09-23 port tions nvelope n et la pose de supports sign alétiques et du branding des bureaux et autres SN-PROMOGED-272517-GO- RFQ / Recrutement d'un pres tataire pour la conception , la Project Implementation Sup Request for Quota Single Stage - One E Pending Impl IDA / 65530 Post Limited 30,000.00 0.00 2022-03-23 2022-05-18 2022-11-14 réalisation d'un film institutio port tions nvelope ementation nnel sur le PROMOGED et d'u n reportage sur la décharge de Mbeubeus SN-PROMOGED-272518-GO- Project Implementation Sup Request for Quota Single Stage - One E RFQ / Acquisition d'appareils IDA / 65530 Post Limited 34,000.00 27,491.66 Completed 2022-03-13 2022-02-24 2022-05-08 2022-04-21 2022-11-04 2022-06-06 port tions nvelope photos multifonctionnels SN-PROMOGED-272523-GO- Project Implementation Sup Request for Quota Single Stage - One E RFQ / Acquisition d'équipeme IDA / 65530 Post Limited 50,000.00 35,956.30 Signed 2022-03-14 2022-04-26 2022-05-09 2022-05-26 2022-11-05 port tions nvelope nts de communication en tex tiles SN-PROMOGED-272524-GO- Project Implementation Sup Request for Quota Single Stage - One E IDA / 65530 Post Limited 40,000.00 32,933.12 Completed 2022-03-14 2022-02-03 2022-05-09 2022-04-14 2022-11-05 2022-05-28 RFQ / Acquisition de bureaux port tions nvelope amovibles SN-PROMOGED-272679-GO- Improving Solid Waste Infras RFQ / Acquisition et mise en Request for Quota Single Stage - One E IDA / 65530 tructure and Services in Sele Post Limited 96,000.00 77,469.68 Completed 2022-04-09 2022-02-15 2022-06-04 2022-04-07 2022-12-01 2022-07-14 place de latrines et de réserv tions nvelope cted Agglomerations oirs d'eau au niveau de la dé charge de Mbeubeus SN-PROMOGED-272683-GO- Improving Solid Waste Infras RFB / Acquisition et pose de l Single Stage - One E IDA / 65530 tructure and Services in Sele Post Request for Bids Open - National 300,000.00 239,884.14 Signed 2022-04-12 2022-02-24 2022-04-17 2022-03-24 2022-05-29 2022-03-29 2022-06-28 2022-04-07 2022-08-02 2022-05-29 2023-01-29 ampadaires solaires au nivea nvelope cted Agglomerations u de la décharge de Mbeube uss SN-PROMOGED-226483-GO- Project Implementation Sup Request for Quota Single Stage - One E RFQ / Acquisition d'équipeme IDA / 65520 Post Limited 36,000.00 29,145.09 Completed 2022-03-15 2022-03-28 2022-05-10 2022-05-15 2022-11-06 2022-10-15 port tions nvelope nts fixes pour le dispositif de pré collecte SN-PROMOGED-272525-GO- Project Implementation Sup Request for Quota Single Stage - One E RFQ / Acquisition de véhicule IDA / 65530 Post Open - National 200,000.00 0.00 Canceled 2022-04-04 2022-05-30 2022-11-26 port tions nvelope s pour les pôles SN-PROMOGED-274735-GO- Project Implementation Sup Request for Quota Single Stage - One E RFQ / Acquisition d'équipeme IDA / 65530 Post Limited 20,000.00 0.00 Signed 2022-04-11 2022-07-25 2022-06-06 2022-12-03 port tions nvelope nts pour le SIG SN-PROMOGED-280611-GO- RFB / Achat de Drones dans l Strengthening Sector Gover Single Stage - One E e cadre de la convention ave IDA / 65530 nance and Institutional Capa Post Request for Bids Open - National 300,000.00 0.00 Completed 2022-04-30 2022-06-01 2022-05-05 2022-06-01 2022-06-16 2022-07-05 2022-07-16 2022-08-10 2022-08-20 2023-02-16 2023-01-29 nvelope c la Direction Générale des I city mpôts et des Domaines (DGI D) SN-PROMOGED-280616-GO- RFB / Acquisition d'équipeme Strengthening Sector Gover nts informatiques dans le cad Single Stage - One E IDA / 65530 nance and Institutional Capa Post Request for Bids Open - National 186,000.00 0.00 Completed 2022-04-28 2022-03-23 2022-05-03 2022-03-23 2022-06-14 2022-05-06 2022-07-14 2022-06-27 2022-08-18 2023-02-14 2023-03-05 re de la mise en eouvre de l nvelope city a convention avec la Directio n Générale des Impôts et Do maines (DGID) SN-PROMOGED-280622-GO- RFQ / Achat de véhicules da Strengthening Sector Gover Request for Quota Single Stage - One E ns le cadre de la mise en œu IDA / 65530 nance and Institutional Capa Post Open - National 120,000.00 0.00 Canceled 2022-05-03 2022-06-28 2022-12-25 tions nvelope vre de la convention avec la city Direction Générale des Impôt s et Domaines (DGID) SN-PROMOGED-280999-GO- RFB / Fourniture et Mise en Pl Improving Solid Waste Infras Single Stage - One E ace de Barrières de sécurité IDA / 65530 tructure and Services in Sele Post Request for Bids Open - National 200,000.00 101,832.90 Signed 2022-05-10 2022-03-04 2022-05-15 2022-06-26 2022-04-06 2022-07-26 2022-04-21 2022-08-30 2022-06-09 2023-02-26 nvelope au niveau des accés aux plat cted Agglomerations eformes de la décharge Page 3 SN-PROMOGED-282957-GO- RFQ / Prestations de services Improving Solid Waste Infras Request for Quota Single Stage - One E de conception, réalisation et IDA / 65530 tructure and Services in Sele Post Open - National 98,000.00 0.00 Signed 2022-04-17 2022-06-12 2022-12-09 tions nvelope production de supports multif cted Agglomerations ormats de communication po ur le PAR de Mbeubeuss SN-PROMOGED-289731-GO- RFB / FOURNITURE D’ÉQUIPE Improving Solid Waste Infras Open - Internationa Single Stage - One E Under Imple MENTS ET D’ENGINS LOURDS IDA / 65530 tructure and Services in Sele Post Request for Bids 1,600,000.00 0.00 2022-07-27 2022-11-15 2022-08-01 2022-11-17 2022-09-12 2022-10-12 2022-11-16 2023-05-15 l nvelope mentation POUR L’EXPLOITATION DE LA cted Agglomerations DÉCHARGE DE MBEUBEUSS SN-PROMOGED-295187-GO- Improving Solid Waste Infras Open - Internationa Single Stage - One E Pending Impl RFB / Acquisition Equipement IDA / 65530 tructure and Services in Sele Prior Request for Bids 3,031,600.00 0.00 2023-08-10 2023-08-15 2023-09-26 2023-10-26 2023-11-30 2024-05-28 l nvelope ementation s Roulants pour CTT Mbeube cted Agglomerations us SN-PROMOGED-295189-GO- RFB / Acquisition de mobilier Project Implementation Sup Single Stage - One E s de bureaux et équipements IDA / 65530 Post Request for Bids Open - National 190,000.00 0.00 Signed 2022-12-22 2022-08-12 2022-12-27 2023-02-07 2022-09-20 2023-03-09 2022-11-07 2023-04-13 2023-10-10 port nvelope informatiques pour pôle salo um-centre 8Siège et autres p ôles plus tablettes CTR SN-PROMOGED-295198-GO- Strengthening Sector Gover Request for Quota Single Stage - One E RFQ / Acquisition de KIT EPI p IDA / 65530 nance and Institutional Capa Post Limited 70,000.00 0.00 Completed 2022-12-13 2022-07-25 2023-02-07 2023-08-06 2023-01-03 tions nvelope our Coach et DGID city SN-PROMOGED-308980-GO- Improving Solid Waste Infras Request for Quota Single Stage - One E Pending Impl RFQ / Acquisition d'une ambu IDA / 65520 tructure and Services in Sele Post Limited 90,000.00 0.00 2023-01-02 2023-02-27 2023-08-26 tions nvelope ementation lance médicalisée cted Agglomerations SN-PROMOGED-310089-GO- RFB / Acquisition matériel et l Project Implementation Sup Single Stage - One E Under Imple IDA / 65530 Post Request for Bids Open - National 260,000.00 0.00 2022-12-22 2022-10-20 2022-12-27 2022-10-21 2023-02-07 2022-11-29 2023-03-09 2022-12-02 2023-04-13 2023-10-10 ogiciel Visio conférence / Inst port nvelope mentation allation, Formation et abonne ment SN-PROMOGED-310103-GO- Improving Solid Waste Infras Request for Quota Single Stage - One E RFQ / Fournitures d'équipem IDA / 65530 tructure and Services in Sele Post Limited 96,000.00 0.00 Signed 2023-01-03 2022-08-29 2023-02-28 2023-08-27 tions nvelope ents sportifs cted Agglomerations SN-PROMOGED-310107-GO- RFQ / Fourniture d'EPI pour le Project Implementation Sup Request for Quota Single Stage - One E IDA / 65530 Post Limited 30,000.00 0.00 Signed 2023-01-03 2022-08-29 2023-02-28 2023-08-27 personnel du PROMOGED et l port tions nvelope es visites de chantier SN-PROMOGED-310119-GO- Improving Solid Waste Infras Request for Quota Single Stage - One E RFQ / Fourniture de kits scola IDA / 65530 tructure and Services in Sele Post Limited 97,000.00 0.00 Signed 2023-01-03 2022-08-29 2023-02-28 2023-08-27 tions nvelope ires pour les écoles de Keur cted Agglomerations Massar SN-PROMOGED-323153-GO- RFB / Equipement du Centre des Ressources Educatives d Improving Solid Waste Infras Single Stage - One E Under Imple e Malika (CREM): lot 1 : maté IDA / 65530 tructure and Services in Sele Post Request for Bids Open - National 150,000.00 0.00 2023-06-08 2023-05-03 2023-06-13 2023-07-25 2023-08-24 2023-09-28 2024-03-26 nvelope mentation riels et mobiliers de bureau L cted Agglomerations ot2 : Matériels informatiques et équipements studio d'enre gistrement SN-PROMOGED-323181-GO- RFQ / Acquisition d'équipeme Improving Solid Waste Infras Request for Quota Single Stage - One E nts de transformation de pro IDA / 65530 tructure and Services in Sele Post Limited 24,000.00 0.00 Signed 2023-07-17 2023-01-02 2023-09-11 2024-03-09 tions nvelope duits locaux pour les GIE de f cted Agglomerations emmes de Malika et Keur Ma ssar SN-PROMOGED-323193-GO- Project Implementation Sup Request for Quota Single Stage - One E Pending Impl RFQ / Acquisition de groupes IDA / 65530 Post Limited 34,000.00 0.00 2023-07-10 2023-09-04 2024-03-02 port tions nvelope ementation électrogènes SN-PROMOGED-323229-GO- Project Implementation Sup Request for Quota Single Stage - One E Pending Impl RFQ / Acquisition de TOMPRO IDA / 65530 Post Limited 50,000.00 0.00 2023-06-27 2023-08-22 2024-02-18 port tions nvelope ementation et de TOMPAIE web SN-PROMOGED-323659-GO- Improving Solid Waste Infras RFQ / Réalisation de maquett Request for Quota Single Stage - One E Pending Impl IDA / 65520 tructure and Services in Sele Post Limited 60,000.00 0.00 2023-05-15 2023-07-10 2024-01-06 es pour les infrastructures ( tions nvelope ementation cted Agglomerations Mbeubeuss, CIVD, CTT, Ecop ôle, CRC, PRN, PC) SN-PROMOGED-295193-GO- RFB / Acquisition de véhicule Project Implementation Sup Single Stage - One E IDA / 65530 Post Request for Bids Open - National 460,000.00 0.00 Canceled 2022-11-24 2022-11-29 2023-01-10 2023-02-09 2023-03-16 2023-09-12 s pour DGID- pôles centre - s port nvelope aloum -UGP et 50 motos pour Coach SN-PROMOGED-280624-GO- RFQ / Achat de petits matérie Strengthening Sector Gover Request for Quota Single Stage - One E Pending Impl ls de cadastre dans le cadre IDA / 65530 nance and Institutional Capa Post Limited 21,000.00 0.00 2023-05-01 2023-06-26 2023-12-23 tions nvelope ementation de la convention avec la Dire city ction Générale des Impôts et Domaines (DGID) SN-PROMOGED-260345-GO- Project Implementation Sup Request for Quota Single Stage - One E IDA / 65530 Post Limited 6,000.00 0.00 Canceled 2021-12-04 2021-11-26 2022-01-29 2022-07-28 RFQ / Achat de Motos port tions nvelope SN-PROMOGED-277729-GO- Improving Solid Waste Infras RFB / Acquisition d'équipeme Open - Internationa Single Stage - One E Pending Impl IDA / 65530 tructure and Services in Sele Prior Request for Bids 4,720,000.00 0.00 2025-12-26 2025-12-31 2026-02-11 2026-03-13 2026-04-17 2026-10-14 nts mobiles pour le CTT et la l nvelope ementation cted Agglomerations plateforme de compostage d e Mbeubeuss SN-PROMOGED-339261-GO- Strengthening Sector Gover Request for Quota Single Stage - One E Under Imple RFQ / Conception et fournitur IDA / 65530 nance and Institutional Capa Post Limited 80,000.00 0.00 2023-08-22 2023-03-13 2023-10-17 2024-04-14 tions nvelope mentation e de badges pour les usagers city de Mbeubeuss SN-PROMOGED-339283-GO- RFB / Acquisition de véhicule Strengthening Sector Gover s pour l'UGP, la DGID, la DEF Open - Internationa Single Stage - One E Pending Impl IDA / 65530 nance and Institutional Capa Post Request for Bids 800,000.00 0.00 2023-05-19 2023-05-24 2023-07-05 2023-08-04 2023-09-08 2024-03-06 CCS en deux lots : Lot 1 : 5 v l nvelope ementation city éhicules wagons 4X4 ; Lot 2 : 8 véhicules pick up double ca bine SN-PROMOGED-339285-GO- Strengthening Sector Gover Request for Quota Single Stage - One E Pending Impl RFQ / Acquisition de motos p IDA / 65530 nance and Institutional Capa Post Limited 96,000.00 0.00 2023-05-24 2023-07-19 2024-01-15 tions nvelope ementation our l'UGP , les coachs et DEF city CCS SN-PROMOGED-177970-GO- Improving Solid Waste Infras RFB / Acquisition de tricycles Open - Internationa Single Stage - One E IDA / 65530 tructure and Services in Sele Post Request for Bids 1,078,992.00 0.00 Canceled 2025-08-13 2025-08-18 2025-09-29 2025-10-29 2025-12-03 2026-06-01 et de charettes pour pôles N l nvelope cted Agglomerations ORD -CASAMANCE ET THIES Page 4 SN-PROMOGED-178427-GO- Improving Solid Waste Infras Single Stage - One E RFB / Acquisition de chevaux, IDA / 65530 tructure and Services in Sele Post Request for Bids Open - National 180,929.00 0.00 Canceled 2023-03-09 2023-03-14 2023-04-25 2023-05-25 2023-06-29 2023-12-26 nvelope d'ânes, pour les pôles et Dak cted Agglomerations ar en 2 lots SN-PROMOGED-178423-GO- RFB / Acquisition de poubelle Improving Solid Waste Infras Single Stage - One E s, petits matériels et équipe IDA / 65530 tructure and Services in Sele Post Request for Bids Open - National 592,987.00 0.00 Canceled 2023-02-08 2023-02-13 2023-03-27 2023-04-26 2023-05-31 2023-11-27 nvelope ment de protection pour les cted Agglomerations pôles Nord Casamance et Thi es en 3 lots SN-PROMOGED-359740-GO- Project Implementation Sup Request for Quota Single Stage - One E Pending Impl RFQ / Acquisition de fournitur IDA / 65530 Post Limited 60,000.00 0.00 2023-06-27 2023-08-22 2024-02-18 port tions nvelope ementation es de bureau et consommabl es informatiques SN-PROMOGED-361243-GO- Improving Solid Waste Infras Request for Quota Single Stage - One E Pending Impl RFQ / Equipement des daara IDA / 65530 tructure and Services in Sele Post Limited 16,000.00 0.00 2023-10-03 2023-11-28 2024-05-26 tions nvelope ementation s de Keur Massar cted Agglomerations SN-PROMOGED-361245-GO- Improving Solid Waste Infras RFQ / Acquisition de kits pour Request for Quota Single Stage - One E Pending Impl IDA / 65530 tructure and Services in Sele Post Limited 20,000.00 0.00 2023-09-25 2023-11-20 2024-05-18 les associations villageoises tions nvelope ementation cted Agglomerations d'épargne et de crédit NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SN-PROMOGED-89692-NC-R FQ / recrutement d'un presta Project Implementation Sup Request for Quota Single Stage - One E IDA / V1600 Post Limited 12,000.00 9,867.30 Completed 2018-12-24 2019-01-02 2019-02-18 2019-02-09 2019-08-17 2019-03-26 taire pour la couverture de l' port tions nvelope assurance maladie du person nel du PROMOGED SN-PROMOGED-95110-NC-R FQ / L'objectif général est de mettre à jour le logiciel TOM PRO et de migrer vers sa ver Project Implementation Sup Request for Quota Single Stage - One E IDA / V1600 Post Limited 4,178.00 0.00 Canceled 2019-02-02 2019-02-06 2019-03-30 2019-09-26 sion web pour faciliter une g port tions nvelope estion administrative, financi ère et comptable efficace av ec une synchronisation des d onnées du PROMOGED. SN-PROMOGED-204122-NC- RFQ / Recrutement d'un pres Project Implementation Sup Request for Quota Single Stage - One E IDA / 65530 Post Limited 17,400.00 15,629.29 Signed 2020-11-22 2020-11-11 2021-01-17 2020-12-16 2021-07-16 tataire pour le nettoiement port tions nvelope des locaux du projet SN-PROMOGED-204130-NC- Project Implementation Sup Request for Quota Single Stage - One E RFQ / Recrutement d'une soc IDA / 65530 Post Limited 21,600.00 25,944.49 Signed 2020-11-22 2020-11-11 2021-01-17 2020-12-19 2021-07-16 port tions nvelope iété de gardiennage SN-PROMOGED-227439-GO- Project Implementation Sup Request for Quota Single Stage - One E RFQ / Installation Réseau Tél IDA / 65520 Post Open - National 90,000.00 39,962.97 Completed 2021-12-04 2022-01-29 2022-01-19 2022-07-28 2022-07-08 port tions nvelope éphonie - internet- Visio surv eillance SN-PROMOGED-179838-NC- Improving Solid Waste Infras Single Stage - One E RFB / Prodcution de supports IDA / 65530 tructure and Services in Sele Post Request for Bids Open - National 180,000.00 0.00 Canceled 2022-05-05 2022-05-10 2022-06-21 2022-07-21 2022-08-25 2023-02-21 nvelope de communication cted Agglomerations SN-PROMOGED-262133-NC- RFB / Sélection d'un prestata Project Implementation Sup Request for Quota Single Stage - One E ire pour la réalisation de repo IDA / 65530 Post Open - National 20,000.00 19,243.65 Completed 2021-12-18 2022-02-12 2022-03-01 2022-08-11 2022-07-28 port tions nvelope rtages et de captation de ph otos, vidéos et de la producti on de capsules SN-PROMOGED-265671-NC- RFQ / Recrutement d'une soc Project Implementation Sup Request for Quota Single Stage - One E IDA / 65530 Post Open - National 30,000.00 17,152.17 Signed 2021-12-25 2022-02-19 2022-01-19 2022-08-18 iété pour le gardiennage des port tions nvelope locaux du siège du PROMOG ED SN-PROMOGED-265676-NC- RFQ / Recrutement d'un pres Project Implementation Sup Request for Quota Single Stage - One E IDA / 65530 Post Open - National 24,000.00 13,436.85 Signed 2021-12-27 2022-02-21 2022-01-19 2023-02-21 tataire pour le nettoiement d port tions nvelope es locaux de siège du PROM OGED SN-PROMOGED-272515-GO- RFQ / Recrutement d'un pres Project Implementation Sup Request for Quota Single Stage - One E Pending Impl tataire pour la conception , la IDA / 65520 Post Limited 40,000.00 0.00 2022-03-08 2022-05-03 2022-10-30 port tions nvelope ementation réalisation et l'impression de supports de communication SN-PROMOGED-278412-NC- Project Implementation Sup DIR / Acquisition de logiciels IDA / 65530 Post Direct Selection Direct 30,000.00 20,779.30 Completed 2022-04-11 2022-04-12 2022-04-16 2022-06-03 2022-05-21 2022-07-29 2022-11-17 2022-08-26 port SIG (licences) SN-PROMOGED-295204-NC- RFQ / Prestations de services Improving Solid Waste Infras Request for Quota Single Stage - One E d’entretien, de nettoiement e IDA / 65530 tructure and Services in Sele Post Limited 98,000.00 0.00 Signed 2022-12-13 2022-06-10 2023-02-07 2023-08-06 tions nvelope t de vidange de 30 toilettes cted Agglomerations mobiles à la décharge de Mb eubeuss SN-PROMOGED-323222-NC- Improving Solid Waste Infras RFQ / Conception et impressi Request for Quota Single Stage - One E Pending Impl IDA / 65530 tructure and Services in Sele Post Limited 80,000.00 0.00 2023-07-25 2023-09-19 2024-03-17 on de bâches de présentatio tions nvelope ementation cted Agglomerations n des infrastructures SN-PROMOGED-323226-NC- RFQ / Sélection d'un prestata Strengthening Sector Gover Request for Quota Single Stage - One E Pending Impl ire pour l'organisation d'une IDA / 65520 nance and Institutional Capa Post Open - National 60,000.00 0.00 2023-03-14 2023-05-09 2023-11-05 tions nvelope ementation mission de benchmarking de city s récupérateurs au Maroc SN-PROMOGED-259667-NC- Improving Solid Waste Infras RFB / Prestation de services Open - Internationa Single Stage - One E IDA / 65530 tructure and Services in Sele Prior Request for Bids 2,290,000.00 0.00 Canceled 2021-12-30 2023-05-18 2022-01-04 2022-02-15 2022-03-17 2022-04-21 2022-10-18 de nettoiement pour Dakar e l nvelope cted Agglomerations t les trois (03) pôles en quatr e (04) lots CONSULTING FIRMS Page 5 Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SN-PROMOGED-60946-CS-Q CBS / Sélection d'un cabinet d'Assistance à la Maîtrise d'O Quality And Cost- Open - Internationa Under Implement uvrage pour la l'élaboration d / Post 350,000.00 0.00 2018-04-26 2018-05-08 2018-05-17 2018-05-15 2018-06-10 2018-09-18 2018-07-08 2018-11-05 2018-08-07 2018-11-08 2018-09-11 2018-12-10 2018-10-16 2019-03-15 Based Selection l ation es plans intercommunaux de gestion des déchets pour les Pôles THIES, CASAMANCE et NORD SN-PROMOGED-60948-CS-Q CBS / Sélection d'un Cabinet pour l'appui à la définition du Quality And Cost- Open - Internationa cadre de réforme de la fiscali / Post 200,000.00 145,352.90 Terminated 2018-04-26 2018-05-08 2018-05-17 2018-05-15 2018-06-10 2018-09-18 2018-07-08 2018-11-07 2018-08-07 2018-11-23 2018-09-11 2018-12-10 2018-10-16 2019-03-21 2019-07-13 Based Selection l té directe et l'appui à l'opéra tionnalisation de l'écotaxe po ur le secteur des déchets soli des municipaux au Sénégal SN-PROMOGED-60945-CS-Q CBS / Sélection d'un cabinet pour les études techniques d Strengthening Sector Gover Quality And Cost- Open - Internationa étaillées de l'opération de ré / nance and Institutional Capa Post 550,000.00 467,750.01 Completed 2018-04-26 2018-05-11 2018-05-17 2018-05-15 2018-06-14 2018-09-18 2018-07-12 2018-10-31 2018-08-11 2018-11-19 2018-09-15 2018-12-07 2018-10-20 2019-07-19 2019-06-17 2021-04-10 Based Selection l sorption de la décharge de M city beubeuss et de la constructio n d'infrastructures de traitem ent des déchets solides SN-PROMOGED-62398-CS-C QS / Sélection d'un cabinet p our la réalisation d'une étude Consultant Qualifi d'impact environnemental et / Post Open - National 300,000.00 0.00 Canceled 2018-05-11 2018-05-25 2018-06-23 2018-09-24 2018-07-23 2018-08-27 2018-10-26 cation Selection social, et un plan d'action de réinstallation du nouveau sch éma de gestion des déchets solides a Dakar SN-PROMOGED-66089-CS-Q CBS / SÉLECTION D'UN CABIN ET POUR L'ÉLABORATION DE S DOSSIERS DE CONSULTATI Strengthening Sector Gover ON CONDUISANT A LA SÉLEC Quality And Cost- Open - Internationa Under Implement / nance and Institutional Capa Post 400,000.00 0.00 2018-06-09 2018-06-14 2018-06-30 2018-06-25 2018-08-13 2018-09-27 2018-09-10 2018-11-13 2018-10-10 2018-11-13 2018-11-14 2018-12-11 2018-12-19 2019-06-17 TION DE PARTENAIRES PRIVE Based Selection l ation city S POUR LA CONCEPTION, LA RÉALISATION ET L'EXPLOITAT ION DES INFRASTRUCTURES DE GESTION DES DÉCHETS S OLIDES DE LA RÉGION DE DA KAR SN-PROMOGED-66090-CS-C QS / SÉLECTION D'UN CABIN ET POUR LA RÉALISATION D' Strengthening Sector Gover UNE ETUDE D'IMPACT ENVIR Consultant Qualifi Under Implement / nance and Institutional Capa Post Open - National 300,000.00 0.00 2018-06-09 2018-06-14 2018-06-23 2018-06-25 2018-07-21 2018-08-28 2018-08-05 2018-09-09 2019-03-08 ONNEMENTAL ET SOCIAL, ET cation Selection ation city UN PLAN D'ACTION DE RÉINS TALLATION DU NOUVEAU SC HÉMA DE GESTION DES DÉC HETS SOLIDES A DAKAR SN-PROMOGED-128465-CS- QCBS PRIO / Sélection et em Strengthening Sector Gover ploi d'un consultant firme po Quality And Cost- Open - Internationa IDA / V1600 nance and Institutional Capa Post 450,000.00 366,893.77 Completed 2019-08-21 2019-09-12 2019-09-11 2019-10-25 2019-10-31 2019-11-22 2020-07-09 2019-12-22 2020-07-09 2020-01-26 2020-09-08 2020-03-01 2021-02-05 2021-03-01 2022-05-13 ur l'audit organisationnel du Based Selection l city secteur des déchets et l'acc ompagnement pour la mise e n oeuvre des résultats SN-PROMOGED-178889-CS- QCBS / sélection d’un cabinet pour l’élaboration d’un nouve Improving Solid Waste Infras au mécanisme de financeme Quality And Cost- Open - Internationa IDA / 65530 tructure and Services in Sele Post 400,000.00 0.00 Signed 2020-06-10 2020-06-23 2020-07-01 2020-08-14 2021-08-10 2020-09-11 2021-09-30 2020-10-11 2021-11-06 2020-11-15 2022-02-08 2020-12-20 2021-12-20 nt durable, de la viabilité éco Based Selection l cted Agglomerations nomique et des réformes fisc ales du secteur de la gestion des déchets solides municipa ux au Sénégal SN-PROMOGED-179536-CS- QCBS / Sélection d'un cabine Improving Solid Waste Infras t d'avocats et d'assistance et Quality And Cost- Open - Internationa IDA / 65530 tructure and Services in Sele Post 350,000.00 0.00 Signed 2020-08-13 2020-08-06 2020-09-03 2020-10-17 2020-11-20 2020-11-14 2021-03-08 2020-12-14 2021-03-15 2021-01-18 2021-11-29 2021-02-22 2022-02-22 accompagnement du PROMO Based Selection l cted Agglomerations GED dans la préparation et la mise en œuvre des contrats PPP avec le secteur SN-PROMOGED-182424-CS- Improving Solid Waste Infras CQS / Sélection d'un cabinet Consultant Qualifi IDA / 65530 tructure and Services in Sele Post Limited 44,000.00 32,610.56 Signed 2020-07-30 2020-08-04 2020-08-13 2020-08-05 2020-09-12 2020-09-15 2020-10-17 2020-10-13 2021-04-15 2021-04-20 en charge du recrutement du cation Selection cted Agglomerations personnel complémentaire d e l'UGP SN-PROMOGED-179491-CS- QCBS / Sélection d'un bureau Improving Solid Waste Infras Quality And Cost- Open - Internationa de contrôle des travaux des IDA / 65530 tructure and Services in Sele Prior 2,003,295.00 0.00 Canceled 2021-07-10 2021-07-31 2021-09-13 2021-10-11 2021-11-10 2021-12-15 2022-01-19 2023-01-19 Based Selection l autres infrastructures de Dak cted Agglomerations ar et pour la réception des é quipements en SN-PROMOGED-178431-CS- QCBS / Sélection d'un cabine t pour le suivi des travaux de Improving Solid Waste Infras Quality And Cost- Open - Internationa résorption de la décharge de IDA / 65530 tructure and Services in Sele Prior 2,312,800.00 0.00 Canceled 2022-03-02 2022-03-23 2022-05-06 2022-06-03 2022-07-03 2022-08-07 2022-09-11 2023-09-11 Based Selection l Mbeubeus et des infrastructu cted Agglomerations res de Dakar en 2 missions M beubeus et les autres infrastr uctures de Dakar SN-PROMOGED-240082-CS- QCBS / SELECTION D’UN CON SULTANT (FIRME) EN CHARG Improving Solid Waste Infras Quality And Cost- Open - Internationa Under Implement E DE LA MISSION DE CONTRÔ IDA / 65530 tructure and Services in Sele Prior 2,620,415.00 0.00 2021-06-30 2021-07-30 2021-07-21 2021-08-06 2021-09-03 2022-03-17 2021-10-01 2022-05-24 2021-10-31 2021-12-05 2022-01-09 2023-01-09 Based Selection l ation LE, DE SUIVI ET DE SUPERVIS cted Agglomerations ION DES TRAVAUX DU PROJE T DE RESORPTION DE LA DEC HARGE DE MBEUBEUSS SN-PROMOGED-179505-CS- Improving Solid Waste Infras QCBS / Sélection d'un cabine Quality And Cost- IDA / 65530 tructure and Services in Sele Post Open - National 472,000.00 0.00 Canceled 2022-02-09 2022-03-02 2022-04-15 2022-05-13 2022-06-12 2022-07-17 2022-08-21 2023-08-21 t pour la réalisation d'une EIE Based Selection cted Agglomerations S au niveau du Pôle Casama nce (8 études) SN-PROMOGED-179540-CS- QCBS / Sélection d'un cabine Improving Solid Waste Infras t pour l'évaluation de perfor Quality And Cost- Open - Internationa IDA / 65530 tructure and Services in Sele Post 1,500,000.00 0.00 Canceled 2020-11-19 2020-12-10 2021-01-23 2021-02-20 2021-03-22 2021-04-26 2021-05-31 2022-05-31 mance des acteurs impliqués Based Selection l cted Agglomerations dans la mise en oeuvre -créa tion de données dynamiques sur 6 ans Page 6 SN-PROMOGED-178441-CS- QCBS / Sélection d'un cabine Improving Solid Waste Infras Quality And Cost- t pour l'assistance à l'exploit IDA / 65530 tructure and Services in Sele Post Open - National 908,600.00 0.00 Canceled 2024-02-09 2024-03-01 2024-04-14 2024-05-12 2024-06-11 2024-07-16 2024-08-20 2025-08-20 Based Selection ation des infrastructures à D cted Agglomerations akar (2premières années d'e xploitation) SN-PROMOGED-178917-CS- QCBS / Sélection d'un cabine t pour l'assistance à l'exploit Improving Solid Waste Infras Quality And Cost- Open - Internationa ation des infrastructures au n IDA / 65530 tructure and Services in Sele Post 531,000.00 0.00 Canceled 2024-02-07 2024-02-28 2024-04-12 2024-05-10 2024-06-09 2024-07-14 2024-08-18 2025-08-18 Based Selection l iveau des villes secondaires cted Agglomerations Pôle NORD THIES et CASAMA NCE ( é premières années d' exploitation) SN-PROMOGED-179495-CS- Improving Solid Waste Infras QCBS / Sélection d'un cabine Quality And Cost- IDA / 65530 tructure and Services in Sele Prior Open - National 2,832,000.00 0.00 Canceled 2020-12-18 2021-01-08 2021-02-21 2021-03-21 2021-04-20 2021-05-25 2021-06-29 2022-06-29 t pour le plan d'action et de r Based Selection cted Agglomerations éinstallation PCR au niveau d es Pôles régionaux SN-PROMOGED-179503-CS- Improving Solid Waste Infras QCBS / Sélection d'un cabine Quality And Cost- IDA / 65530 tructure and Services in Sele Post Open - National 236,000.00 0.00 Canceled 2022-05-11 2022-06-01 2022-07-15 2022-08-12 2022-09-11 2022-10-16 2022-11-20 2023-11-20 t pour une EIES au niveau du Based Selection cted Agglomerations Pôle deTHIES (4 études) SN-PROMOGED-179511-CS- QCBS / Sélection d'un cabine Improving Solid Waste Infras Quality And Cost- t pour la réalisation des anal IDA / 65530 tructure and Services in Sele Post Open - National 566,400.00 0.00 Canceled 2022-04-06 2022-04-27 2022-06-10 2022-07-08 2022-08-07 2022-09-11 2022-10-16 2023-10-16 Based Selection yses environnementales et in cted Agglomerations itiales au niveau du Pôle Csa mance SN-PROMOGED-179514-CS- QCBS / Sélection d'un cabine Improving Solid Waste Infras Quality And Cost- Open - Internationa t pour la réalisation d'analyse IDA / 65530 tructure and Services in Sele Post 1,321,600.00 0.00 Canceled 2022-03-11 2022-04-01 2022-05-15 2022-06-12 2022-07-12 2022-08-16 2022-09-20 2023-09-20 Based Selection l s environnementales et initia cted Agglomerations le au niveau du Pôle THIES SN-PROMOGED-195155-CS- QCBS / Sélection et emploi d' Improving Solid Waste Infras Quality And Cost- Open - Internationa un bureau de contrôle des tr IDA / 65530 tructure and Services in Sele Post 945,525.00 0.00 Canceled 2021-07-21 2021-08-11 2021-09-24 2021-10-22 2021-11-21 2021-12-26 2022-01-30 2023-01-30 Based Selection l avaux de Mbeubeus et pour l cted Agglomerations a réception des équipements SN-PROMOGED-262750-CS- QCBS / Sélection d'une firme pour l'Etude de préfaisabilité, de l’évaluation préalable et d Project Implementation Sup Quality And Cost- Open - Internationa IDA / 65520 Prior 800,000.00 0.00 Under Review 2022-02-16 2021-11-30 2022-03-09 2021-12-24 2022-04-22 2022-05-20 2022-06-19 2022-07-24 2022-08-28 2023-08-28 es services de conseil en tran port Based Selection l saction pour la mise en place d’un Partenariat Public Privé (PPP) pour la gestion des déc hets de Dakar SN-PROMOGED-129287-CS- QCBS PRIO / Sélection d'un c abinet d’avocats pour l'élab Project Implementation Sup Quality And Cost- Open - Internationa oration des textes relatifs à IDA / V1600 Post 350,000.00 0.00 Canceled 2021-08-18 2021-09-08 2021-10-22 2021-11-19 2021-12-19 2022-01-23 2022-02-27 2023-02-27 port Based Selection l l'application des PPP pour le secteurs des déchets et acco mpagnement pour la mise en œuvre SN-PROMOGED-323147-CS- QCBS / Recrutement d'une st Improving Solid Waste Infras ructure facilitatrice chargée Quality And Cost- Under Implement IDA / 65530 tructure and Services in Sele Post Open - National 300,000.00 0.00 2023-05-10 2022-12-15 2023-05-31 2023-01-26 2023-07-14 2023-08-11 2023-09-10 2023-10-15 2023-11-19 2024-11-18 de la protection des couches Based Selection ation cted Agglomerations vulnérables et du retrait des enfants de la décharge de M beubeuss SN-PROMOGED-323148-CS- QCBS / Recrutement d'une st ructure facilitatrice chargée Improving Solid Waste Infras de la mise en œuvre du Plan Quality And Cost- Open - Internationa Under Implement IDA / 65530 tructure and Services in Sele Post 800,000.00 0.00 2023-05-12 2022-12-15 2023-06-02 2023-02-16 2023-07-16 2023-08-13 2023-09-12 2023-10-17 2023-11-21 2024-11-20 d'Actions de Réinstallation (P Based Selection l ation cted Agglomerations AR) et du Plan de Restauratio n des moyens de subsistance (PRMS)du projet de résorptio n de la décharge de Mbeube uss SN-PROMOGED-179859-CS- Improving Solid Waste Infras QCBS / Sélection d'un cabine Quality And Cost- IDA / 65530 tructure and Services in Sele Post Open - National 200,000.00 0.00 Canceled 2023-12-13 2024-01-03 2024-02-16 2024-03-15 2024-04-14 2024-05-19 2024-06-23 2025-06-23 t pour l'évaluation à mi-parco Based Selection cted Agglomerations urs et final du Projet SN-PROMOGED-179857-CS- Improving Solid Waste Infras Quality And Cost- QCBS / Sélection d'un cabine IDA / 65530 tructure and Services in Sele Post Open - National 120,000.00 0.00 Canceled 2021-12-09 2021-12-30 2022-02-12 2022-03-12 2022-04-11 2022-05-16 2022-06-20 2023-06-20 Based Selection t pour l'audit des comptes du cted Agglomerations PROMOGED SN-PROMOGED-323195-CS- QCBS / Recrutement d'un Pre Strengthening Sector Gover Quality And Cost- stataire chargé de la coordin IDA / 65530 nance and Institutional Capa Post Open - National 60,000.00 0.00 Canceled 2023-07-11 2022-09-22 2023-08-01 2023-09-14 2023-10-12 2023-11-11 2023-12-16 2024-01-20 2025-01-19 Based Selection ation de la caractérisation de city s déchets solides au niveau d e la région de Dakar SN-PROMOGED-182416-CS- QCBS / Suivi des travaux et r Improving Solid Waste Infras Quality And Cost- Open - Internationa éception des infrastructures IDA / V1600 tructure and Services in Sele Prior 2,268,362.00 0.00 Canceled 2024-12-26 2025-01-16 2025-03-01 2025-03-29 2025-04-28 2025-06-02 2025-07-07 2026-07-07 Based Selection l et équipements au niveau du cted Agglomerations pôle THIES et CASAMANCE SN-PROMOGED-179496-CS- QCBS / Sélection d'un consult Improving Solid Waste Infras ant firme pour la formation d Quality And Cost- IDA / V1600 tructure and Services in Sele Post Open - National 236,000.00 0.00 Canceled 2024-12-26 2025-01-16 2025-03-01 2025-03-29 2025-04-28 2025-06-02 2025-07-07 2026-07-07 es acteurs sur les procédures Based Selection cted Agglomerations de réinstallation , violence ba sée sur le genre et réglemen te des plaintes SN-PROMOGED-178435-CS- Improving Solid Waste Infras QCBS / Sélection d'un cabine Consultant Qualifi IDA / 65530 tructure and Services in Sele Post Open - National 200,000.00 0.00 Canceled 2024-12-28 2025-01-18 2025-03-03 2025-04-02 2025-05-07 2025-11-03 t pour la facilitation de la mis cation Selection cted Agglomerations e en œuvre du PAR de Grand Dakar SN-PROMOGED-248604-CS- Improving Solid Waste Infras QCBS / Sélection d'un cabine Quality And Cost- Open - Internationa IDA / 65530 tructure and Services in Sele Post 236,000.00 0.00 Canceled 2025-09-20 2025-10-11 2025-11-24 2025-12-22 2026-01-21 2026-02-25 2026-04-01 2027-04-01 t pour une EIES au niveau du Based Selection l cted Agglomerations Pôle deTHIES (4 études) Page 7 SN-PROMOGED-248605-CS- Improving Solid Waste Infras QCBS / Sélection d'un cabine Quality And Cost- Open - Internationa IDA / 65530 tructure and Services in Sele Prior 2,832,000.00 0.00 Canceled 2025-11-20 2025-12-11 2026-01-24 2026-02-21 2026-03-23 2026-04-27 2026-06-01 2027-06-01 t pour le plan d'action et de r Based Selection l cted Agglomerations éinstallation PCR au niveau d es Pôles régionaux SN-PROMOGED-248607-CS- Improving Solid Waste Infras QCBS / Sélection d'un cabine Quality And Cost- Open - Internationa IDA / 65530 tructure and Services in Sele Post 472,000.00 0.00 Canceled 2025-12-27 2026-01-17 2026-03-02 2026-03-30 2026-04-29 2026-06-03 2026-07-08 2027-07-08 t pour la réalisation d'une EIE Based Selection l cted Agglomerations S au niveau du Pôle Casama nce (8 études) SN-PROMOGED-248609-CS- QCBS / Sélection d'un cabine Improving Solid Waste Infras Quality And Cost- Open - Internationa t pour la réalisation des anal IDA / 65530 tructure and Services in Sele Prior 566,400.00 0.00 Canceled 2025-08-20 2025-09-10 2025-10-24 2025-11-21 2025-12-21 2026-01-25 2026-03-01 2027-03-01 Based Selection l yses environnementales et in cted Agglomerations itiales au niveau du Pôle Csa mance SN-PROMOGED-248617-CS- Improving Solid Waste Infras QCBS / Sélection d'un cabine Quality And Cost- Open - Internationa IDA / 65530 tructure and Services in Sele Prior 708,000.00 0.00 Canceled 2025-08-21 2025-09-11 2025-10-25 2025-11-22 2025-12-22 2026-01-26 2026-03-02 2027-03-02 t pour la réalisation d'une EIE Based Selection l cted Agglomerations S au niveau du Pôle NORD(3 études) SN-PROMOGED-248620-CS- QCBS / Sélection d'un cabine Improving Solid Waste Infras Quality And Cost- Open - Internationa t pour la réalisation des anal IDA / 65530 tructure and Services in Sele Prior 1,439,600.00 0.00 Canceled 2025-08-20 2025-09-10 2025-10-24 2025-11-21 2025-12-21 2026-01-25 2026-03-01 2027-03-01 Based Selection l yses environnementales et in cted Agglomerations itiales au niveau du Pôle NOR D SN-PROMOGED-248611-CS- QCBS / Sélection d'un cabine Improving Solid Waste Infras Quality And Cost- Open - Internationa t pour la réalisation d'analyse IDA / 65530 tructure and Services in Sele Prior 1,321,600.00 0.00 Canceled 2025-09-27 2025-10-18 2025-12-01 2025-12-29 2026-01-28 2026-03-04 2026-04-08 2027-04-08 Based Selection l s environnementales et initia cted Agglomerations le au niveau du Pôle THIES SN-PROMOGED-179532-CS- QCBS / Sélection d'un cabine Improving Solid Waste Infras t pour l'accompagnement de Consultant Qualifi IDA / 65530 tructure and Services in Sele Post Open - National 100,000.00 0.00 Canceled 2024-12-20 2025-01-10 2025-02-23 2025-03-25 2025-04-29 2025-10-26 la mise en œuvre des résulta cation Selection cted Agglomerations ts:(Modérateurs pour ateliers et processus d'adoption sur l a TEOM,REOM et ECOTAXES) SN-PROMOGED-338887-CS- QCBS / Sélection d’un cabin et pour la réalisation des étu des techniques détaillées des Improving Solid Waste Infras Quality And Cost- Open - Internationa PRN et CRC et l' élaboration IDA / 65530 tructure and Services in Sele Post 400,000.00 0.00 Canceled 2024-12-04 2024-12-25 2025-02-07 2025-03-07 2025-04-06 2025-05-11 2025-06-15 2026-06-15 Based Selection l d’un dossier de consultation cted Agglomerations pour les travaux dans les pôl es Thiès, Nord (St Louis Mata m) et SUD (Ziguinchor Sédhi ou et Kolda) SN-PROMOGED-182406-CS- QCBS / Études techniques de modernisation ,de gestion int Improving Solid Waste Infras Quality And Cost- Open - Internationa ercommunale des déchets so IDA / 65530 tructure and Services in Sele Prior 1,770,000.00 0.00 Canceled 2020-07-06 2020-07-27 2020-09-09 2020-10-07 2020-11-06 2020-12-11 2021-01-15 2022-01-15 Based Selection l lides et du mode de contract cted Agglomerations ualisation des infrastructures avec le secteur privé dans le pôle NORD SN-PROMOGED-248602-CS- QCBS / Sélection d'un cabine Improving Solid Waste Infras t pour l'assistance à l'exploit Quality And Cost- Open - Internationa IDA / 65530 tructure and Services in Sele Prior 531,000.00 0.00 Canceled 2023-05-09 2023-05-30 2023-07-13 2023-08-10 2023-09-09 2023-10-14 2023-11-18 2024-11-17 ation des infrastructures au n Based Selection l cted Agglomerations iveau des villes secondaires Pôle NORD THIES et CASAMA NCE SN-PROMOGED-248600-CS- QCBS / Sélection d'un cabine Improving Solid Waste Infras Quality And Cost- Open - Internationa t pour l'assistance à l'exploit IDA / 65530 tructure and Services in Sele Prior 908,600.00 0.00 Canceled 2023-05-16 2023-06-06 2023-07-20 2023-08-17 2023-09-16 2023-10-21 2023-11-25 2024-11-24 Based Selection l ation des infrastructures à D cted Agglomerations akar (2premières années d'e xploitation) SN-PROMOGED-248612-CS- QCBS / Sélection d'un cabine Improving Solid Waste Infras t pour l'évaluation de perfor Quality And Cost- Open - Internationa IDA / 65530 tructure and Services in Sele Prior 1,500,000.00 0.00 Canceled 2023-05-09 2023-05-30 2023-07-13 2023-08-10 2023-09-09 2023-10-14 2023-11-18 2024-11-17 mance des acteurs impliqués Based Selection l cted Agglomerations dans la mise en oeuvre -créa tion de données dynamiques SN-PROMOGED-128505-CS- QCBS PRIO / Sélection et em ploi d'un cabinet pour les Etu des techniques détaillées des Improving Solid Waste Infras Quality And Cost- Open - Internationa infrastructures au niveau des IDA / V1600 tructure and Services in Sele Prior 1,770,000.00 0.00 Canceled 2022-05-13 2022-06-03 2022-07-17 2022-08-14 2022-09-13 2022-10-18 2022-11-22 2023-11-22 Based Selection l Pôles et mode de contractua cted Agglomerations lisation pour la gestion des in frastructures (1 cabinet en 2 missions : zone Nord :1 et z ones Thiés +Casamance ) SN-PROMOGED-182414-CS- Improving Solid Waste Infras QCBS / Suivi des travaux et r Quality And Cost- Open - Internationa IDA / 65530 tructure and Services in Sele Prior 2,125,864.00 0.00 Canceled 2022-03-10 2022-03-31 2022-05-14 2022-06-11 2022-07-11 2022-08-15 2022-09-19 2023-09-19 éception des infrastructures Based Selection l cted Agglomerations et équipements au niveau du pôle NORD SN-PROMOGED-182411-CS- QCBS / Etudes techniques de modernisation ,de gestion int Improving Solid Waste Infras Quality And Cost- Open - Internationa ercommunale des déchets so IDA / 65530 tructure and Services in Sele Prior 1,770,000.00 0.00 Canceled 2020-08-19 2020-09-09 2020-10-23 2020-11-20 2020-12-20 2021-01-24 2021-02-28 2022-02-28 Based Selection l lides et du mode de contract cted Agglomerations ualisation des infrastructures avec le secteur privé pour le pôle THIES -CASAMANCE SN-PROMOGED-360589-CS- QCBS / Sélection d’un cabin et pour l’étude de préfaisab ilité, de l’évaluation préalabl Improving Solid Waste Infras Quality And Cost- Open - Internationa Pending Impleme e et des services de conseil e IDA / 65530 tructure and Services in Sele Post 500,000.00 0.00 2023-07-26 2023-08-16 2023-09-29 2023-10-27 2023-11-26 2023-12-31 2024-02-04 2025-02-03 Based Selection l ntation n transaction pour la mise en cted Agglomerations place d’un (PPP) pour la con struction et l’exploitation des infrastructures de gestion da ns la région de THIES SN-PROMOGED-360621-CS- QCBS / Sélection d’un cabin Improving Solid Waste Infras Quality And Cost- Open - Internationa Pending Impleme et pour les études technique IDA / 65530 tructure and Services in Sele Post 300,000.00 0.00 2023-08-25 2023-09-15 2023-10-29 2023-11-26 2023-12-26 2024-01-30 2024-03-05 2025-03-05 Based Selection l ntation s détaillées de la réhabilitatio cted Agglomerations n de la décharge de Thiès Page 8 SN-PROMOGED-360628-CS- QCBS / Sélection d’un cabin et pour les études technique Improving Solid Waste Infras s détaillées de la réhabilitatio Quality And Cost- Open - Internationa Pending Impleme IDA / 65530 tructure and Services in Sele Post 300,000.00 0.00 2023-09-22 2023-10-13 2023-11-26 2023-12-24 2024-01-23 2024-02-27 2024-04-02 2025-04-02 n de la décharge de Mamator Based Selection l ntation cted Agglomerations o et l'étude de préfaisabilité pour la mise en place d'un PP P pour la construction et l'ex ploitation des infrastructures de Ziguinchor SN-PROMOGED-360650-CS- QCBS / Sélection d’un cabin et pour l’étude de préfaisabili té, de l’évaluation préalable Improving Solid Waste Infras Quality And Cost- Open - Internationa Pending Impleme et des services de conseil en IDA / 65530 tructure and Services in Sele Post 300,000.00 0.00 2023-09-06 2023-09-27 2023-11-10 2023-12-08 2024-01-07 2024-02-11 2024-03-17 2025-03-17 Based Selection l ntation transaction pour la mise en p cted Agglomerations lace d’un (PPP) pour la constr uction et l’exploitation des in frastructures de gestion de K olda et Sédhiou SN-PROMOGED-360681-CS- QCBS / Sélection d’un cabin et pour les études technique Improving Solid Waste Infras s détaillées de la réhabilitatio Quality And Cost- Open - Internationa Under Implement IDA / 65530 tructure and Services in Sele Post 600,000.00 0.00 2023-09-07 2023-06-23 2023-09-28 2023-06-23 2023-11-11 2023-12-09 2024-01-08 2024-02-12 2024-03-18 2025-03-18 n de la décharge de GANDON Based Selection l ation cted Agglomerations et l'étude de préfaisabilité p our la mise en place d'un PPP pour la construction et l'expl oitation du CIVD SN-PROMOGED-360689-CS- QCBS / Sélection d’un cabin et pour l’étude de préfaisabili té, de l’évaluation préalable Improving Solid Waste Infras Quality And Cost- Open - Internationa Pending Impleme et des services de conseil en IDA / 65530 tructure and Services in Sele Post 500,000.00 0.00 2023-09-14 2023-10-05 2023-11-18 2023-12-16 2024-01-15 2024-02-19 2024-03-25 2025-03-25 Based Selection l ntation transaction pour la mise en p cted Agglomerations lace d’un (PPP) pour la constr uction et l’exploitation des in frastructures dans les région s de St louis et Matam SN-PROMOGED-360692-CS- QCBS / Sélection d’un cabin Improving Solid Waste Infras et pour les études technique Quality And Cost- Open - Internationa Under Implement IDA / 65530 tructure and Services in Sele Post 400,000.00 0.00 2023-09-06 2023-06-23 2023-09-27 2023-06-23 2023-11-10 2023-12-08 2024-01-07 2024-02-11 2024-03-17 2025-03-17 s détaillées pour la construct Based Selection l ation cted Agglomerations ion des PRN et CRC au nivea u des pôles NORD ,THIES et Casamance INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SN-PROMOGED-60935-CS-IN DV / sélection d'un consultan t individuel chargé de la réali Individual Consult Under Implement / Post Open 150,000.00 0.00 2018-04-26 2018-05-08 2018-05-22 2018-10-03 2018-06-12 2018-12-07 2018-07-17 2019-01-13 sation du cadre de gestion e ant Selection ation nvironnementale et sociale ( CGES) et du cadre de politiqu e de réinstallation (CPR) SN-PROMOGED-60964-CS-IN DV / Sélection d'un consultan Individual Consult Under Implement / Post Open 50,000.00 0.00 2018-04-26 2018-05-08 2018-05-25 2018-10-17 2018-06-15 2018-12-07 2018-07-20 2018-08-29 t pour l'élaboration du manu ant Selection ation el des opérations du PROMO GED SN-PROMOGED-60966-CS-C DS / Sélection d'un cabinet c Strengthening Sector Gover hargé de l'élaboration EIES et IDA / 65520 nance and Institutional Capa Post Direct Selection Direct 200,000.00 218,105.80 Completed 2018-04-26 2018-05-06 2018-07-10 2018-10-09 2018-12-07 2019-05-09 PAR pour les travaux de réso city rption du site de Mbeubeuss SN-PROMOGED-62004-CS-IN Individual Consult Under Implement DV / Sélection d'un consultan / Post Open 100,000.00 0.00 2017-11-10 2018-02-13 2018-06-07 2018-03-06 2018-04-10 2019-04-05 ant Selection ation t individuel expert comptable SN-PROMOGED-62005-CS-IN DV / Sélection d'un consultan Individual Consult Under Implement / Post Open 100,000.00 0.00 2017-11-10 2018-02-13 2018-06-07 2018-03-06 2018-04-10 2019-04-05 t individuel expert en sauveg ant Selection ation arde environnemental et soci al SN-PROMOGED-62007-CS-IN DV / Sélection d'un consultan Individual Consult Under Implement / Post Open 100,000.00 0.00 2017-11-10 2018-01-08 2018-06-07 2018-01-29 2018-03-05 2019-02-28 t individuel expert en appui i ant Selection ation nstitutionnel et réforme juridi que SN-PROMOGED-62008-CS-IN DV / Sélection d'un consultan Individual Consult Under Implement t spécialiste en communicati / Post Open 100,000.00 0.00 2018-03-21 2018-05-31 2018-06-21 2018-07-26 2019-07-21 ant Selection ation on, marketing social et dével oppement communautaire SN-PROMOGED-66088-CS-IN DV / SÉLECTION D'UN CONSU Project Implementation Sup Individual Consult Under Implement / Post Open 100,000.00 0.00 2017-11-10 2017-12-04 2018-02-13 2018-05-14 2018-03-06 2018-04-10 2019-04-05 LTANT INDIVIDUEL SPÉCIALIS port ant Selection ation TE EN PASSATION DE MARCH ES SN-PROMOGED-89316-CS-IN DV / sélection d'un consultan t pour la réalisation de l'anal Project Implementation Sup Individual Consult yse économique et financière IDA / V1600 Post Open 60,000.00 0.00 Canceled 2018-12-11 2020-08-24 2019-01-29 2019-02-19 2019-03-26 2019-09-22 port ant Selection du PROMOGED qui fera parti e intégrante du board packa ge relatif à la demande de fi nancement du projet SN-PROMOGED-128532-CS-I NDV PRIO / Sélection et empl Strengthening Sector Gover oi d'un consultant individuel Individual Consult IDA / V1600 nance and Institutional Capa Post Open 100,000.00 92,446.82 Completed 2019-09-11 2019-10-23 2019-10-30 2020-08-07 2019-11-20 2019-11-26 2019-12-25 2020-10-20 2020-06-22 2021-05-13 pour l'élaboration du manuel ant Selection city d'évaluation de performance s des acteurs impliqués dans la mise en œuvre - SN-PROMOGED-128538-CS-I NDV PRIO / Sélection et em Project Implementation Sup Individual Consult IDA / V1600 Post Limited 10,000.00 8,571.05 Signed 2019-09-18 2020-05-28 2019-09-23 2020-09-01 2019-10-14 2020-09-14 2019-11-18 2020-09-30 2020-05-16 ploi d’un consultant individue port ant Selection l pour l’élaboration de la char te graphique du projet Page 9 SN-PROMOGED-135021-CS- CDS / Sélection d'un consulta Strengthening Sector Gover Individual Consult nt pour l'élaboration du plan IDA / V1600 nance and Institutional Capa Post Limited 50,000.00 0.00 Canceled 2019-10-07 2020-12-03 2019-10-12 2019-11-02 2019-12-07 2020-06-04 ant Selection de restauration des moyens city de subsistance des récupérat eurs de Mbeubeus SN-PROMOGED-139855-CS- CDS / sélection de consultant Project Implementation Sup s pour l'élaboration de plan IDA / V1600 Post Direct Selection Direct 120,000.00 320,506.70 Signed 2019-10-18 2019-10-24 2019-10-28 2019-10-03 2020-01-01 2020-04-21 2020-06-29 2020-07-21 port de restauration des moyens de subsistance des récupéra teurs de Mbeubeus SN-PROMOGED-179430-CS-I Improving Solid Waste Infras Individual Consult NDV / Sélection d'un consulta IDA / 65530 tructure and Services in Sele Post Open 112,268.00 0.04 Signed 2020-06-22 2020-07-15 2020-08-10 2021-05-12 2020-08-31 2021-11-08 2020-10-05 2021-12-15 2021-04-03 ant Selection nt pour le poste de Directeur cted Agglomerations de Projet SN-PROMOGED-180545-CS-I Improving Solid Waste Infras Individual Consult NDV / Sélection d'un consulta IDA / 65530 tructure and Services in Sele Post Open 70,307.00 56,559.28 Signed 2020-06-25 2020-08-06 2020-08-13 2021-03-11 2020-09-03 2021-08-05 2020-10-08 2021-08-17 2021-04-06 ant Selection nt individuel Expert en Com cted Agglomerations munication SN-PROMOGED-180551-CS-I Improving Solid Waste Infras Individual Consult NDV / Sélection d'un consulta IDA / 65530 tructure and Services in Sele Post Open 70,307.00 53,724.43 Signed 2020-06-25 2020-08-06 2020-08-13 2021-05-05 2020-09-03 2021-10-18 2020-10-08 2021-11-06 2021-04-06 ant Selection nt Ingénieur génie civil Sénio cted Agglomerations r SN-PROMOGED-180556-CS-I Improving Solid Waste Infras Individual Consult NDV / Sélection d'un consulta IDA / 65530 tructure and Services in Sele Post Open 70,307.00 59,185.23 Signed 2020-06-25 2020-06-23 2020-08-13 2021-06-04 2020-09-03 2021-06-04 2020-10-08 2021-08-17 2021-04-06 ant Selection nt individuel Expert foncier cted Agglomerations SN-PROMOGED-180561-CS-I Improving Solid Waste Infras NDV / Sélection d'un consulta Individual Consult IDA / 65530 tructure and Services in Sele Post Open 52,211.00 43,216.28 Signed 2020-06-25 2020-06-23 2020-08-13 2021-02-25 2020-09-03 2021-06-21 2020-10-08 2021-08-17 2021-04-06 nt individuel Spécialiste en P ant Selection cted Agglomerations assation des Marchés Junior SN-PROMOGED-180564-CS-I Improving Solid Waste Infras Individual Consult NDV / Sélection d'un consulta IDA / 65530 tructure and Services in Sele Post Open 52,211.00 31,831.05 Signed 2020-06-25 2020-06-23 2020-08-13 2021-02-25 2020-09-03 2021-07-23 2020-10-08 2021-09-02 2021-04-06 ant Selection nt individuel Comptable cted Agglomerations SN-PROMOGED-180569-CS-I Improving Solid Waste Infras Individual Consult NDV / Sélection d'un consulta IDA / 65530 tructure and Services in Sele Post Open 52,211.00 46,198.93 Signed 2020-06-25 2020-08-06 2020-08-13 2021-02-23 2020-09-03 2021-07-08 2020-10-08 2021-08-17 2021-04-06 ant Selection nt individuel Facilitateur Soci cted Agglomerations al Pôle Dakar SN-PROMOGED-180575-CS-I Improving Solid Waste Infras Individual Consult NDV / Sélection d'un consulta IDA / 65530 tructure and Services in Sele Post Open 52,211.00 40,897.18 Signed 2020-06-25 2020-08-06 2020-08-13 2020-11-18 2020-09-03 2021-07-23 2020-10-08 2021-08-17 2021-04-06 ant Selection nt individuel Facilitateur soci cted Agglomerations al Pôle Thies SN-PROMOGED-180579-CS-I Improving Solid Waste Infras NDV / Sélection d'un consulta Individual Consult IDA / 65530 tructure and Services in Sele Post Open 52,211.00 2,296.09 Signed 2020-06-25 2020-08-06 2020-08-13 2021-06-04 2020-09-03 2021-07-06 2020-10-08 2021-08-17 2021-04-06 nt individuel facilitateur socia ant Selection cted Agglomerations l Pôle casamance SN-PROMOGED-180581-CS-I Improving Solid Waste Infras Individual Consult NDV / Sélection d'un consulta IDA / 65530 tructure and Services in Sele Post Open 52,211.00 46,209.57 Signed 2020-06-25 2020-08-06 2020-08-13 2021-02-25 2020-09-03 2021-06-04 2020-10-08 2021-08-17 2021-04-06 ant Selection nt individuel facilitateur socia cted Agglomerations l Pôle NORD SN-PROMOGED-180584-CS-I Improving Solid Waste Infras NDV / Sélection d'un consulta Individual Consult IDA / 65530 tructure and Services in Sele Post Open 52,211.00 2,402.84 Signed 2020-06-25 2020-08-06 2020-08-13 2021-02-24 2020-09-03 2021-07-01 2020-10-08 2021-08-17 2021-04-06 nt individuel Environnementa ant Selection cted Agglomerations liste Pôle Dakar SN-PROMOGED-180587-CS-I Improving Solid Waste Infras NDV / Sélection d'un consulta Individual Consult IDA / 65530 tructure and Services in Sele Post Open 52,211.00 2,299.85 Signed 2020-06-25 2020-08-06 2020-08-13 2021-02-24 2020-09-03 2021-06-04 2020-10-08 2021-08-17 2021-04-06 nt individuel Environnementa ant Selection cted Agglomerations liste Pôle Thiés SN-PROMOGED-180591-CS-I Improving Solid Waste Infras NDV / Sélection d'un consulta Individual Consult IDA / 65530 tructure and Services in Sele Post Open 52,211.00 44,882.12 Signed 2020-06-25 2020-08-06 2020-08-13 2021-02-25 2020-09-03 2021-07-23 2020-10-08 2021-08-17 2021-04-06 nt individuel Environnementa ant Selection cted Agglomerations liste Pôle NORD SN-PROMOGED-180594-CS-I Improving Solid Waste Infras NDV / Sélection d'un consulta Individual Consult IDA / 65530 tructure and Services in Sele Post Open 52,211.00 48,001.53 Signed 2020-06-25 2020-08-06 2020-08-13 2021-07-01 2020-09-03 2021-07-08 2020-10-08 2021-08-24 2021-04-06 nt individuel Environnementa ant Selection cted Agglomerations liste Pôle Casamance SN-PROMOGED-180600-CS-I Improving Solid Waste Infras Individual Consult NDV / Sélection d'un consulta IDA / 65530 tructure and Services in Sele Post Open 52,211.00 42,013.31 Signed 2020-06-25 2020-06-23 2020-08-13 2021-06-04 2020-09-03 2021-07-08 2020-10-08 2021-08-17 2021-04-06 ant Selection nt ingénieur génie civil Pôle T cted Agglomerations hies SN-PROMOGED-180603-CS-I Improving Solid Waste Infras Individual Consult NDV / Sélection d'un consulta IDA / 65530 tructure and Services in Sele Post Open 52,211.00 47,937.29 Signed 2020-06-25 2020-06-23 2020-08-13 2021-07-02 2020-09-03 2021-07-23 2020-10-08 2021-08-17 2021-04-06 ant Selection nt individuel ingénieur génie cted Agglomerations civil Pôle Nord SN-PROMOGED-180606-CS-I Improving Solid Waste Infras NDV / Sélection d'un consulta Individual Consult IDA / 65530 tructure and Services in Sele Post Open 52,211.00 43,547.95 Signed 2020-06-25 2020-06-23 2020-08-13 2021-02-18 2020-09-03 2021-08-23 2020-10-08 2021-10-19 2021-04-06 nt individuel ingénieur génie ant Selection cted Agglomerations civil Pôle Casamance SN-PROMOGED-180596-CS-I Improving Solid Waste Infras NDV / Sélection d'un consult Individual Consult IDA / 65530 tructure and Services in Sele Post Open 52,211.00 0.00 Canceled 2020-06-25 2020-06-23 2020-08-13 2020-09-03 2020-10-08 2021-04-06 ant individuel Ingénieur géni ant Selection cted Agglomerations e civil Pôle Dakar SN-PROMOGED-128543-CS-I NDV PRIO / Sélection d’un co Improving Solid Waste Infras Individual Consult nsultant individuel pour l’ap IDA / V1600 tructure and Services in Sele Post Open 101,000.00 0.00 Canceled 2021-11-25 2022-01-13 2022-02-03 2022-03-10 2022-09-06 ant Selection pui à la contractualisation à cted Agglomerations Dakar et au niveau des villes secondaires (PPP et DSP) SN-PROMOGED-247526-CS-I Improving Solid Waste Infras Individual Consult NDV / RECRUTEMENT D’UN A IDA / 65530 tructure and Services in Sele Post Open 120,000.00 108,160.00 Signed 2021-09-07 2021-09-22 2021-10-26 2022-01-05 2021-11-16 2022-02-02 2021-12-21 2022-06-21 2022-06-19 ant Selection GENT VERIFICATEUR INDEPE cted Agglomerations NDANT (AVI) SN-PROMOGED-260356-CS-I NDV / SELECTION ET EMPLOI Project Implementation Sup Individual Consult D’UN CONSULTANT AUDITEU IDA / 65530 Post Limited 20,000.00 9,301.81 Signed 2021-11-23 2021-10-27 2021-11-28 2022-01-26 2021-12-19 2022-02-10 2022-01-23 2022-05-06 2022-07-22 port ant Selection R INTERNE POUR L’UNITE DE GESTION DU PROJET - UGP Page 10 SN-PROMOGED-128541-CS-I NDV PRIO / Sélection d'un Pr estataire chargé de l'Elaborat Project Implementation Sup Individual Consult IDA / 65530 Post Limited 30,000.00 0.00 Signed 2022-01-04 2022-11-08 2022-01-09 2022-01-13 2022-01-30 2022-03-03 2022-03-06 2022-09-02 ion d'une stratégie digitale et port ant Selection de la mise en place du site w eb, d'un intranet et des profil s de réseaux sociaux SN-PROMOGED-262115-CS-I Project Implementation Sup Individual Consult Under Implement NDV / Sélection d'un Consult IDA / 65530 Post Limited 6,000.00 0.00 2022-01-31 2021-11-26 2022-02-05 2022-02-26 2022-04-02 2022-09-29 port ant Selection ation ant chargé de l'infographie d u PROMOGED SN-PROMOGED-262125-CS-I NDV / Sélection d'un Consult Project Implementation Sup Individual Consult IDA / 65530 Post Limited 30,000.00 0.00 Signed 2022-01-16 2021-12-14 2022-01-21 2022-06-02 2022-02-11 2022-07-14 2022-03-18 2022-09-14 ant chargé d'élaborer une str port ant Selection atégie et un plan de commun ication du PROMOGED SN-PROMOGED-262340-CS-I NDV / Sélection d'un Consult Project Implementation Sup Individual Consult ant chargé de la rédaction d IDA / 65530 Post Limited 28,000.00 20,659.05 Signed 2022-02-28 2022-01-20 2022-03-05 2022-01-17 2022-03-26 2022-05-05 2022-04-30 2022-05-28 2022-10-27 port ant Selection u Bulletin d'information et de s contenus médiatiques SN-PROMOGED-180610-CS-I Improving Solid Waste Infras NDV / Sélection d'un consulta Individual Consult IDA / 65530 tructure and Services in Sele Post Open 63,156.00 0.00 Canceled 2020-07-15 2020-08-06 2020-09-02 2021-02-23 2020-09-23 2020-10-28 2021-04-26 nt individuel Responsable d ant Selection cted Agglomerations e l'unité Sociale SN-PROMOGED-194907-CS-I NDV / Sélection et emploi d’u Project Implementation Sup Individual Consult n (e) Expert (e) Social (e) et r IDA / 65530 Post Open 52,211.00 0.00 Canceled 2021-02-25 2020-06-04 2021-04-15 2021-05-06 2021-06-10 2021-12-07 port ant Selection éinstallation au sein de l’Uni té de Gestion de Projet SN-PROMOGED-262770-CS-I NDV / Sélection et emploi d'u Project Implementation Sup Individual Consult IDA / 65530 Post Limited 52,211.00 4,719,140.66 Signed 2021-12-30 2021-10-28 2022-01-04 2021-11-11 2022-01-25 2021-11-17 2022-03-01 2021-12-02 2022-08-28 n(e) Expert(e) Social(e) et réi port ant Selection nstallation au sein de l'Unité de Gestion de Proje SN-PROMOGED-262771-CS-I Project Implementation Sup Individual Consult NDV / Sélection d'un Expert IDA / 65530 Post Limited 63,156.00 58,337.62 Signed 2021-12-30 2022-02-08 2022-01-04 2021-11-11 2022-01-25 2021-11-17 2022-03-01 2021-12-02 2022-08-28 port ant Selection Responsable de l'Unité Social e SN-PROMOGED-128542-CS-I NDV / Sélection d’un consulta Project Implementation Sup Individual Consult nt individuel pour l’élaborati IDA / V1600 Post Open 100,000.00 0.00 Canceled 2022-02-09 2022-03-30 2022-04-20 2024-02-02 2024-07-31 port ant Selection on de bulletins d’information semestrielle (conception et i mpression) SN-PROMOGED-226252-CS-I NDV / Sélection d'un consulta Project Implementation Sup Individual Consult nt individuel pour l'élaboratio IDA / 65520 Post Limited 20,000.00 0.00 Canceled 2021-10-20 2021-10-25 2021-11-15 2021-12-20 2022-06-18 port ant Selection n d'un guide d'exploitation d e la décharge de Mbeubeus SN-PROMOGED-274742-CS-I NDV / Sélection d’un Géomèt re-Expert pour la délimitation et le bornage des sites a infr Project Implementation Sup Individual Consult IDA / 65530 Post Open 30,000.00 29,374.11 Signed 2022-02-17 2022-01-14 2022-04-07 2022-02-10 2022-04-28 2022-02-18 2022-06-02 2022-03-01 2022-11-29 astructures de Dakar : décha port ant Selection rge de Mbeubeuss – CIVD de Bambilor – CIVD de Sébikota ne – CTT de Mbao et CTT de Diamniadio » SN-PROMOGED-278025-CS-I NDV / Recrutement d’un cons ultant individuel chargé d’éta Improving Solid Waste Infras Individual Consult blir une situation de référenc IDA / 65530 tructure and Services in Sele Post Open 200,000.00 0.00 Signed 2022-03-30 2022-02-07 2022-05-18 2022-05-27 2022-06-08 2022-07-15 2022-07-13 2023-01-09 ant Selection e des émissions de gaz à effe cted Agglomerations t de serre (GES) dans le sect eur des déchets solides au S énégal SN-PROMOGED-278953-CS-I NDV / Recrute un Expert tech Project Implementation Sup Individual Consult nique dans le cadre de l'élab IDA / 65530 Post Open 60,000.00 0.00 Signed 2022-04-07 2022-02-08 2022-05-26 2022-06-01 2022-06-16 2022-06-29 2022-07-21 2023-01-17 port ant Selection oration de la loi d'orientation du secteur de la gestion des déchets solides SN-PROMOGED-278956-CS-I NDV / Recrutement d'un juri Project Implementation Sup Individual Consult ste dans le cadre de l'élabora IDA / 65530 Post Open 50,000.00 0.00 Signed 2022-03-25 2022-02-14 2022-05-13 2022-06-07 2022-06-03 2022-06-29 2022-07-08 2023-01-04 port ant Selection tion de la loi d'orientation da ns le secteur des déchets soli des SN-PROMOGED-280702-CS-I NDV / Sélection d'un consulta nt en charge de l'Elaboration Improving Solid Waste Infras Individual Consult Under Implement d’un cahier de charge pour l’ IDA / 65530 tructure and Services in Sele Post Open 120,000.00 0.00 2022-04-20 2021-12-20 2022-06-08 2022-06-29 2022-08-03 2023-01-30 ant Selection ation exploitation des plateformes cted Agglomerations actives de la décharge de Mb eubeuss et d’un règlement in térieur pour les usagers SN-PROMOGED-282282-CS-I NDV / Sélection d'un consulta nt individuel pour la prépara Improving Solid Waste Infras Individual Consult tion des conventions et l'app IDA / 65530 tructure and Services in Sele Post Limited 30,000.00 22,868.81 Signed 2022-04-05 2022-01-21 2022-04-10 2022-06-01 2022-05-01 2022-04-26 2022-06-05 2022-06-03 2022-12-02 ant Selection ui juridique pour la signature cted Agglomerations des protocoles avec les entit és impliquées dans le PROM OGED SN-PROMOGED-247532-CS-I NDV / RECRUTEMENT D’UN E Project Implementation Sup Individual Consult IDA / 65530 Post Open 52,211.00 0.00 Canceled 2021-09-15 2021-11-03 2021-11-24 2021-12-29 2022-06-27 XPERT EN DEVELOPPEMENT I port ant Selection NSTITUTIONNEL JUNIOR 2 SN-PROMOGED-272510-CS-I Project Implementation Sup Individual Consult NDV / Recrutement Expert e IDA / 65530 Post Open 52,211.00 0.00 Canceled 2022-01-19 2022-03-09 2022-03-30 2022-05-04 2022-10-31 port ant Selection n Développement Institution nel SN-PROMOGED-247529-CS-I NDV / RECRUTEMENT D’UN E Project Implementation Sup Individual Consult IDA / 65530 Post Open 52,211.00 0.00 Canceled 2021-09-15 2021-11-03 2021-11-24 2021-12-29 2022-06-27 XPERT EN DEVELOPPEMENT port ant Selection INSTITUTIONNEL JUNIOR 1 Page 11 SN-PROMOGED-288992-CS-I NDV / RECRUTEMENT D’UN E XPERT FINANCIER EN CHARG Improving Solid Waste Infras Individual Consult E D’ELABORER LES COMPTES IDA / 65530 tructure and Services in Sele Post Open 50,000.00 0.00 Signed 2022-06-29 2022-10-07 2022-08-17 2022-08-03 2022-09-07 2022-08-25 2022-10-12 2023-04-10 ant Selection D’EXPLOITATION PREVISIONN cted Agglomerations ELS ET LES PLANS DE FINANC EMENT DES PLANS DE GESTI ON DES DECHETS SOLIDES SN-PROMOGED-295210-CS- CQS / Sélection d’un Consult ant individuel Architecte pou Improving Solid Waste Infras Individual Consult Under Implement r la conception et la modélisa IDA / 65530 tructure and Services in Sele Post Limited 30,000.00 0.00 2022-12-27 2022-04-04 2023-01-01 2022-06-01 2023-01-22 2023-02-26 2023-08-25 ant Selection ation tion 3D des infrastructures pr cted Agglomerations ojetées au niveau du Pôle ur bain de Diamniadio et du lac rose SN-PROMOGED-295212-CS-I NDV / Sélection d’un Consult ant individuel pour l’étude de Improving Solid Waste Infras Individual Consult la cartographie des opportuni IDA / 65530 tructure and Services in Sele Post Open 160,000.00 0.00 Signed 2022-12-21 2022-06-01 2023-02-08 2022-08-03 2023-03-01 2022-09-01 2023-04-05 2023-10-02 ant Selection tés et du mécanisme de renf cted Agglomerations orcement de l’entreprenariat vert dans le secteur des déch ets solides SN-PROMOGED-310106-CS-I Improving Solid Waste Infras NDV / Recrutement de forma Individual Consult Pending Impleme IDA / 65530 tructure and Services in Sele Post Limited 60,000.00 0.00 2022-12-29 2023-01-03 2023-01-24 2023-02-28 2023-08-27 teurs en alphabétisation fonc ant Selection ntation cted Agglomerations tionnelle pour les récupératri ces de Mbeubeuss SN-PROMOGED-286095-CS-I NDV / RECRUTEMENT D’UN C Strengthening Sector Gover ONSULTANT INDIVIDUEL CHA Individual Consult Under Implement IDA / 65530 nance and Institutional Capa Post Limited 60,000.00 0.00 2022-10-20 2022-02-23 2022-10-25 2022-11-15 2022-12-20 2023-06-18 RGE DE L’ELABORATION DU ant Selection ation city PLAN DE GESTION DE LA MAI N D’OEUVRE DU PROMOGED SN-PROMOGED-312608-CS-I NDV / Recrutement de consul tants formateurs pour le renf Strengthening Sector Gover orcement des capacités des Individual Consult Under Implement IDA / 65530 nance and Institutional Capa Post Open - National 34,000.00 0.00 2023-02-23 2022-08-24 2023-04-13 2023-05-04 2023-06-08 2023-12-05 élus et agents municipaux de ant Selection ation city s communes couvertes par le PROMOGED dans le pôle de Dakar en gestion des déchet s solides SN-PROMOGED-312611-CS-I NDV / Recrutement de consul tants formateurs pour le renf Strengthening Sector Gover orcement des capacités des Individual Consult Under Implement IDA / 65530 nance and Institutional Capa Post Open - National 34,000.00 0.00 2023-02-08 2022-08-24 2023-03-29 2023-04-19 2023-05-24 2023-11-20 élus et agents municipaux de ant Selection ation city s communes couvertes par le PROMOGED dans le pôle de NORD(Saint Louis Matam) en gestion des déchets solides SN-PROMOGED-312612-CS-I NDV / Recrutement de consul tants formateurs pour le renf Strengthening Sector Gover orcement des capacités des Individual Consult Under Implement IDA / 65530 nance and Institutional Capa Post Open - National 34,000.00 0.00 2023-02-15 2022-08-24 2023-04-05 2023-04-26 2023-05-31 2023-11-27 élus et agents municipaux de ant Selection ation city s communes couvertes par le PROMOGED dans le pôle de THIES en gestion des déchets solides SN-PROMOGED-312613-CS-I NDV / Recrutement de consul tants formateurs pour le renf Strengthening Sector Gover orcement des capacités des Individual Consult Under Implement IDA / 65530 nance and Institutional Capa Post Open - National 34,000.00 0.00 2023-02-16 2022-08-24 2023-04-06 2023-04-27 2023-06-01 2023-11-28 élus et agents municipaux de ant Selection ation city s communes couvertes par le PROMOGED dans le pôle du SUD et RUFISQUE en gestion des déchets solides SN-PROMOGED-323143-CS-I NDV / Recrutement d'un Con Project Implementation Sup Individual Consult Pending Impleme sultant individuel chargé de l IDA / 65530 Post Limited 20,000.00 0.00 2023-04-12 2023-04-17 2023-05-08 2023-06-12 2023-12-09 port ant Selection ntation a Formation en ARGIS pour l e personnel de l'UGP du PRO MOGED SN-PROMOGED-323144-CS-I NDV / Formation des récupér Improving Solid Waste Infras ateurs de Mbeubeuss et du p Individual Consult Under Implement IDA / 65520 tructure and Services in Sele Post Open - National 60,000.00 0.00 2023-04-28 2022-12-15 2023-06-16 2023-07-07 2023-08-11 2024-02-07 ersonnel de l'UCG et du PRO ant Selection ation cted Agglomerations MOGED sur les questions de l 'Hygiéne, la Sécurité et la Sa nté au travail SN-PROMOGED-323145-CS-I NDV / Formation du personne Improving Solid Waste Infras l du PROMOGED, des agents Individual Consult Under Implement IDA / 65520 tructure and Services in Sele Post Open - National 60,000.00 0.00 2023-04-27 2022-12-15 2023-06-15 2023-07-06 2023-08-10 2024-02-06 de l'UCG et des récupérateur ant Selection ation cted Agglomerations s de la décharge de Mbeube uss sur les gestes de premier s secours SN-PROMOGED-323171-CS-I NDV / Recrutement d'un Con Project Implementation Sup Individual Consult Under Implement IDA / 65530 Post Open - National 50,000.00 0.00 2023-06-23 2023-01-16 2023-08-11 2023-09-10 2023-10-15 2024-10-14 sultant individuel pour la rev port ant Selection ation ue à mi-parcours du PROMO GED SN-PROMOGED-328465-CS-I NDV / Recrutement d'un form Improving Solid Waste Infras Individual Consult Pending Impleme ateur en alphabétisation fonc IDA / 65520 tructure and Services in Sele Post Limited 20,000.00 0.00 2023-01-18 2023-01-23 2023-02-13 2023-03-20 2023-09-16 ant Selection ntation tionnelle pour les récupératri cted Agglomerations ces de la décharge de Mbeub euss en sérére SN-PROMOGED-328473-CS-I NDV / Recrutement d'un form Improving Solid Waste Infras Individual Consult Pending Impleme ateur en alphabétisation fonc IDA / 65520 tructure and Services in Sele Post Limited 20,000.00 0.00 2023-01-19 2023-01-24 2023-02-14 2023-03-21 2023-09-17 ant Selection ntation tionnelle pour les récupératri cted Agglomerations ces de la décharge de Mbeub euss en pular SN-PROMOGED-328476-CS-I NDV / Recrutement d'un For Improving Solid Waste Infras Individual Consult Pending Impleme mateur en genre, VBG, leard IDA / 65520 tructure and Services in Sele Post Limited 10,000.00 0.00 2023-01-25 2023-01-30 2023-02-20 2023-03-27 2023-09-23 ant Selection ntation ership en faveur des récupér cted Agglomerations atrices de la décharge de Mb eubeuss Page 12 SN-PROMOGED-262111-CS-I NDV / Recrutement d'un assi Project Implementation Sup Individual Consult IDA / 65530 Post Open 40,000.00 0.00 Canceled 2022-01-30 2022-03-20 2022-04-10 2022-05-15 2022-11-11 stant en communication et e port ant Selection n Community management d u PROMOGED SN-PROMOGED-96730-CS-IN DV / Recrutement d'un exper t chargé du suivi évaluation Nous avons retenue l'approc Strengthening Sector Gover he d'une contractualisation d IDA / V1600 nance and Institutional Capa Post Direct Selection Direct 100,000.00 0.00 Canceled 2019-01-29 2019-02-08 2019-04-14 2019-10-11 irecte avec Madame Mbicine city Khady SARR qui était le point focal du projet depuis le déb ut de sa formulation en effet elle est la mémoire du projet SN-PROMOGED-180566-CS-I Improving Solid Waste Infras Individual Consult NDV / Sélection d'un consulta IDA / 65530 tructure and Services in Sele Post Open 52,211.00 0.00 Canceled 2020-06-25 2020-08-06 2020-08-13 2021-02-17 2020-09-03 2020-10-08 2021-04-06 ant Selection nt individuel Expert en Genre cted Agglomerations SN-PROMOGED-184360-CS-I Improving Solid Waste Infras Individual Consult NDV / Sélection d'un consulta IDA / 65530 tructure and Services in Sele Post Open 70,307.00 0.00 Canceled 2020-07-16 2020-09-03 2020-09-24 2020-10-29 2021-04-27 ant Selection nt Responsable de l'unité env cted Agglomerations ironnementale SN-PROMOGED-226254-CS-I NDV / Sélection d'un consulta Project Implementation Sup Individual Consult IDA / 65520 Post Limited 30,000.00 0.00 Canceled 2021-10-13 2021-10-18 2021-11-08 2021-12-13 2022-06-11 nt pour la mise en œuvre de port ant Selection mécanisme de gestion des pl aintes SN-PROMOGED-338348-CS-I NDV / SELECTION D’UN CON SULTANT INDIVIDUEL POUR L Strengthening Sector Gover Individual Consult Pending Impleme A FIABILISATION DES DONNE IDA / 65530 nance and Institutional Capa Post Limited 30,000.00 0.00 2023-03-16 2023-03-21 2023-04-11 2023-05-16 2023-11-12 ant Selection ntation ES DU PLAN D’ACTION ET DE city REINSTALLATION DU PROJET DE RESORPTION DE LA DECH ARGE DE MBEUBEUSS SN-PROMOGED-286093-CS-I NDV / Recrutement d’un cons Strengthening Sector Gover Individual Consult ultant individuel pour l’élabor IDA / 65530 nance and Institutional Capa Post Limited 20,000.00 0.00 Canceled 2022-04-27 2022-02-23 2022-05-02 2022-05-23 2022-06-27 2022-12-24 ant Selection ation du Plan de mobilisation city des parties prenantes (PMPP) du PROMOGED SN-PROMOGED-339286-CS-I NDV / Recrutement d'un form Improving Solid Waste Infras ateur en alphabétisation fonc Individual Consult Pending Impleme IDA / 65530 tructure and Services in Sele Post Limited 20,000.00 0.00 2023-05-24 2023-05-29 2023-06-19 2023-07-24 2024-01-20 tionnelle pour les récupératri ant Selection ntation cted Agglomerations ces de la décharge de Mbeub euss en WOLOF pour Groupe n°1 SN-PROMOGED-339292-CS-I NDV / Recrutement d'un form Improving Solid Waste Infras ateur en alphabétisation fonc Individual Consult Pending Impleme IDA / 65530 tructure and Services in Sele Post Limited 20,000.00 0.00 2023-05-30 2023-06-04 2023-06-25 2023-07-30 2024-01-26 tionnelle pour les récupératri ant Selection ntation cted Agglomerations ces de la décharge de Mbeub euss en WOLOF pour Groupe n°2 SN-PROMOGED-178932-CS- QCBS / Sélection d'un consult ant individuel pour la réalisa Project Implementation Sup Individual Consult Under Implement IDA / V1600 Post Open - National 30,000.00 0.00 2023-03-22 2023-06-26 2023-05-10 2023-05-31 2023-07-05 2024-01-01 tion d'une enquête annuelle ( port ant Selection ation mesure des indicateurs de dé veloppement du Projet et en quête de perception ) SN-PROMOGED-346555-CS-I NDV / Recrutement d'un Con Strengthening Sector Gover sultant individuel chargé de l Individual Consult Under Implement IDA / 65530 nance and Institutional Capa Post Open - National 60,000.00 0.00 2023-05-17 2023-06-23 2023-07-05 2023-07-26 2023-08-30 2024-02-26 a coordination de la caractéri ant Selection ation city sation des déchets solides au niveau de la région de Dakar SN-PROMOGED-179842-CS-I NDV / Sélection d'un consulta Improving Solid Waste Infras Individual Consult nt individuel pour la mise en IDA / 65530 tructure and Services in Sele Post Limited 10,000.00 0.00 Canceled 2022-02-03 2022-02-08 2022-03-01 2022-04-05 2022-10-02 ant Selection place et la sécurisation du sit cted Agglomerations e Web et des autres platefor mes du PROMOGED SN-PROMOGED-179851-CS-I NDV / Sélection d'un consulta Improving Solid Waste Infras Individual Consult nt individuel pour l'élaboratio IDA / 65530 tructure and Services in Sele Post Open 100,000.00 0.00 Canceled 2022-02-10 2022-03-31 2022-04-21 2022-05-26 2022-11-22 ant Selection n de guide et supports pour l cted Agglomerations a promotion de bonnes prati que en gestion de déchets SN-PROMOGED-360819-CS-I NDV / Sélection d'un consulta Strengthening Sector Gover Individual Consult Pending Impleme nt individuel expert financier IDA / 65530 nance and Institutional Capa Post Open - National 18,000.00 0.00 2023-08-23 2023-10-11 2023-11-01 2023-12-06 2024-06-03 ant Selection ntation sénior pour l'élaboration des city plans intercommunaux des p ôles Saloum et centre SN-PROMOGED-360835-CS-I NDV / Sélection d'un consulta Strengthening Sector Gover nt individuel Expert sénior e Individual Consult Pending Impleme IDA / 65530 nance and Institutional Capa Post Limited 10,000.00 0.00 2023-07-27 2023-08-01 2023-08-22 2023-09-26 2024-03-24 n gestion des déchets pour l' ant Selection ntation city élaboration des plans interco mmunaux pour les pôles Sal oum et Centre SN-PROMOGED-361251-CS-I NDV / Sélection d'un consult Strengthening Sector Gover Individual Consult Under Implement ant individuel pour l'élaborati IDA / 65530 nance and Institutional Capa Post Open - National 90,000.00 0.00 2023-09-22 2023-06-23 2023-11-10 2023-12-01 2024-01-05 2024-07-03 ant Selection ation on du Plan de mobilisation de city s parties prenantes (PMPP) d u PROMOGED Page 13 AGRO-CLIMATIC RESILIENCE IN SEMI -ARID LANDSCAPES (ACReSAL) PROJECT PROCUREMENT STRATEGY FOR DEVELOPMENT 1 PROJECT OVERVIEW Country: NIGERIA Full Project Name: AGRO-CLIMATIC RESILIENCE IN SEMI -ARID LANDSCAPES (ACReSAL) Total Finance ($): USD 700 MILLION Project Number: P175237 Summary of Project The Project Development Objective (PDO) is to increase the adoption of climate resilient landscape Development Objectives management practices and enhance livelihoods in targeted arid/semi-arid watersheds in Northern Nigeria. PROJECT COST COMPONENTS ESTMATE OBJECTIVES OF EACH (USD) COMPONENT Component A: 299.6m This component aims to prepare and Desertification Control implement investments to arrest and Landscape desertification and improve the Management sustainable productivity of land in targeted watersheds (about 1,000,000 ha area of degraded and desert landscapes out of 4,000,000 (25%) Government program). Component B: 293.4m This component aims to support Community communities with improved capacity Livelihoods and and investments to improve Resilience sustainable livelihoods. Component C: 107.6m This component aims to strengthen Institutional capacities of institutions at various levels (e.g., national, selected states) Strengthening and to modernize their work for the Project Management longer-term on integrated multi- sectoral planning, information management, and building systems for improving land and water management and sustainable agricultural productivity in northern Nigeria. Component D: 0m This will finance a Contingency Contingency Emergency Response Component Emergency Response (CERC) for landscape and community Components (CERC): resilience in response to extreme weather, land movement events and other emergencies. LIST OF PROCUREMENT ACTIVITIES The project is designed as framework project and therefore investments and the participating states (the major investments will be implemented by the participating states) are not fully known yet. In the table below are the activities that already known, and implementation can commence immediately. The PPSD will be updated during implementation as the investments and participating states become more defined. These investments include gully erosion control, rehabilitation of irrigation and dams. S/N ACTIVITIES COST CUMMULATIVE % of ESTIMATE COST TOTAL (USD) ESTIMATE COST (USD) ESTIMATE 1 Technical assistance for 10,000,000 10,000,000 28% landscape restoration services 2 Extension services technical 9,900,000 19,900,000 57% assistance 3 Implementation support 9,500,000 29,400,000 84% consultancy 4 Long-term framework and 2,500,000 31,900,000 91% policy support 5 Development of strategic 1,600,000 33,500,000 95% catchment plan 4 Monitoring Information 600,000 34,100,000 97% System (MIS) and maintenances 5 Others ICT Equipment and 400,000 34,500,000 98% connectivity, cloud services, others general services Desktops & Laptops 300,000 34,800,000 99% Data collection and analysis at 168,000 34,968,000 100% State/federal Level Production of Manuals (PIM ) 90,000 35,058,000 100% Design and hosting of 56,000 35,114,000 100% interactive website TOTAL 35,114,000 Strategic Assessment of Operating Context and Borrower Capability Operational Context Nigeria experiences a diverse climate that ranges from arid in the north to tropical in much of the country and is listed among the countries most exposed to climate risks. The country faces a high water-scarcity hazard level, with droughts expected to occur on average every five years, with potential increased frequency due to climate change. Focusing on drylands management, ACReSAL will be implemented in the states of northern Nigeria. The agricultural sector is the major economic driver of northern Nigeria. Many projects and initiatives have been undertaken in northern Nigeria over the past decades to combat the growing crisis of desertification. The FGN is thus increasingly moving toward an integrated and multisectoral approach to address the challenges of dryland management. (a) Governance Aspects: There are security challenges in almost all the states in the northern Nigeria where the project will be implemented. The Government of Nigeria is making some progress in addressing these security challenges. The security situation may reduce the interest of major players, especially for Component A to participate in the procurement process and those that choose to participate may add a premium to the bid prices to take of the additional security arrangement they want to put in place during contract execution in case of an award. (b) Economic Aspects: Nigeria has just come out of an economic recession because of CIVID 19 pandemic and a fall in crude oil price in the world market. The country is contending with high inflation and exchange rate volatility. The high inflation and exchange rate volatility has made the prices of the major construction materials such as iron rods and cement to be volatile. Substantial proportion of the Component consist of civil works with locally available inputs (labour and materials). The effect of the exchange volatility will be minimal since bidders expecting to incur expenditures in other currencies for inputs to the Works supplied from outside the country can quote for such inputs in up to three different foreign currencies in their bids. Serious bottleneck exists in the main seaport where goods to be imported from abroad will be discharged. This has led to delay in the custom clearance of good from the port with the resulting demurrage payment and delay in contract execution. The government is working on policy that will remove the bottlenecks. (c) Sustainability Aspects: The government environmental and social standards requires that Environmental and Social Impact Assessment be carried on all major works project before the commencement of such works. ESIA will apply to this project and will be reflected in the solicitation documents and contracts for civil works under the project. (d) Technological Aspects: Kaduna, Niger, Kogi, Jigawa, Borno, Kano and Gombe States that will likely participate in the project have an e-Procurement system which is being used in some of the MDAs. Sokoto State is in the final stages of their e- Procurement implementation. The systems so deployed will be used for procurement under the project. This will further improve value for money, transparency, economy, efficiency, effectiveness, integrity, and openness of procurement process under the project. The country is covered substantially by GSM, part of which is through extensive fiber optic cabling leading to increased networking and internet availability. The availability of reasonable internet access will facilitate the use of the World Bank Systematic Tracking of Exchanges in Procurement (STEP) which is mandatory requirement in the processing all procurement activities under the World Bank Procurement Regulations. Key Conclusions: The security challenges in the country especially in the northern states that will participate in the project may reduce the participation of foreign firms and firms from other parts of the in the procurement process for the project. The current high inflation and exchange rate volatility in the country will affect the costing of the various procurement packages in the project. The use of eProcurement for by the participating states and the FPMU will improve value for money, transparency, economy, efficiency, effectiveness, integrity, and openness of procurement process under the project Assessment of Borrower previous Experience, Capability and Project Implementation Unit (PIU) The project will be implemented using the existing NEWMAP PMUs at both Federal and State levels that are implementing NEWMAP and the NEWMAP AF that will close on June 30, 2022. The implementation arrangement is similar to that of NEWMAP. Each state will be responsible for the procurement of its own activities including contract management and administration. The FPMU and the states that are implementing NEWMAP have experience in World Bank Procurement Regulations. The procurement officers have received sufficient training in procurement under World Bank funded project. The gaps that were observed in the implementation of NEWMAP especially in contract management will be addressed under ACReSAL. Training will be provided on contract management, application of price adjustment, contract monitoring and supervision as soon as the project is effective. Market Analysis The summary of the procurement activities under the project are as follows • Civil works: o gully erosion control, o flood and sedimentation control, o construction of firebreaks, o rehabilitation and construction of small dams, o small scale irrigation infrastructure, o small buildings There are several players both national and international in the marketplace for these activities. International open competitive procurement approach will be used for high value, high risk gully erosion control and construction of dams and firebreaks. The other low value, low risk procurement will follow national open competition or limited competition as may be appropriate. • Goods: o fire control equipment, o vehicles, o farm inputs (seeds, fertilizers), o post-production equipment, o computers, furniture They are locally available and be supplied by several suppliers and the procurement approach will be national open/limited completion as may be appropriate. The approach for the procurement of farm inputs (seeds, fertilizer) will limited competition between the well-known producers/suppliers of these goods. • Consulting services: The major consulting services includes engineering design and supervision of the major civil works like gully erosion control and rehabilitation of dams. The firms that offer this service are available in the local and international markets. Due to the criticality of this consulting assignment to the overall delivery of the major works contracts, the procurement will be designed to attract best consulting firms to express interest in this assignment. Procurement Risk Analysis Market Risk Description of Risk Owner /Contract Description Mitigation Title Description Construction of Designs may no A consultant will be State PMU and shovel ready longer be valid by the hired to update the World Bank gully erosion contracts during design before the control site contract execution commencement of the procurement process Expansion of the Provisions for State PMUs gullies between physical bidding and contract contingencies will signature made in the signed contract. Expansion of gullies Proper drainage on Contractor during construction the site must be due to poor drainage maintained during resulting from construction and the construction of the Contractor shall be works held responsible for any flood damage to life and properties due to his work in this Contract. The Contractor shall allow in his rates, inter alia, for all costs to maintain or divert flow in drains, ditches, open channels and watercourses during construction and other drainage work. No claims for additional payment will be considered in this regard. Construction Poor supervision of supervision the works contracts consultancy Procurement of Delay in port All the necessary PMUs goods to be clearance documentation and imported from waivers will be outside the processed speedily country (delfino ploughs, tractors, etc) General (for all High inflation and Price adjustment to PMUs contracts) exchange rate applied to most even volatility if they duration is less than 18 months. Procurement Objective • To a minimum of 8 qualified consultants to participate in the selection process for the engineering design and supervision consultancy for the major works contracts. • To take advantage of the dry season for the construction contracts by aligning the commencement of the works with the dry season in the project areas. • Value for money and integrity in the procurement process using electronic procurement system. • To have not less than six qualified firms submit bids for the major works contracts. • Procurement Approach Options and Recommendation The following will be a draft zero of the procurement approach options and recommendations. This is because the major investments are not yet known. This section will be updated once the investments are finalized. • Contract and Estimated Cost: Landscape investments (many packages)– USD236 million • Procurement Approach Attribute Selected arrangement Justification Summary/Logic Specifications Conformance Details design for shovel- ready investments from NEWMAP are available. Engineering firm will be hired to provide detail designs for other investments. Sustainability No All the safeguard studies Requirements will be carried out separately and cost implications will be included in the bidding document. Contract Type Traditional Pricing and costing Schedule of mechanism Rates/Admeasurement Price Adjustments None/Percentage Form of Contract (Terms and Conditions) Selection Method Request for Bids (RFB) Selection Arrangement N/A Market Approach Open International/National Pre/Post Qualification Post Evaluation Selection Least Cost Based Method Selection (LCS) Evaluation of Costs Adjusted Bid Price Domestic Preference No Rated Criteria N/A • Contract and Estimated Cost: Development of strategic catchment plan – USD1,600,000 • Procurement Approach Attribute Selected arrangement Justification Summary/Logic Sustainability N/A Requirements Contract Type Traditional Pricing and costing Lump Sum mechanism Price Adjustments None Form of Contract (Terms N/A and Conditions) Selection Method Request for Proposals (RFP) Selection Arrangement N/A Market Approach Open International Pre/Post Qualification Pre-Qualification Evaluation Selection Quality Cost Based Method Selection (QCBS) Evaluation of Costs N/A Domestic Preference N/A Rated Criteria Mandatory • Contract and Estimated Cost: Long-term framework and policy support – USD2,500,000 • Procurement Approach Attribute Selected arrangement Justification Summary/Logic Sustainability N/A Requirements Contract Type Traditional Pricing and costing Time and Materials mechanism Price Adjustments ????? Form of Contract (Terms ????? and Conditions) Selection Method Request for Proposals (RFP) Selection Arrangement N/A Market Approach Open International, Two Envelopes Pre/Post Qualification Pre-Qualification Evaluation Selection Quality Cost Based Method Selection (QCBS) Evaluation of Costs Adjusted Bid Price Domestic Preference No Rated Criteria • Specific experience • Methodology and workplan • Qualification and experience of key experts • Contract and Estimated Cost: Implementation support consultancy – USD9,900,000 • Procurement Approach Attribute Selected arrangement Justification Summary/Logic Sustainability N/A Requirements Contract Type Traditional Pricing and costing Lump Sum mechanism Price Adjustments None Form of Contract (Terms N/A and Conditions) Selection Method Request for Proposals (RFP) Selection Arrangement N/A Market Approach Open International Pre/Post Qualification Pre-Qualification Evaluation Selection Quality Cost Based Method Selection (QCBS) Evaluation of Costs N/A Domestic Preference N/A Rated Criteria Mandatory • Contract and Estimated Cost: Development of strategic catchment plan – USD1,600,000 • Procurement Approach Attribute Selected arrangement Justification Summary/Logic Sustainability N/A Requirements Contract Type Traditional Pricing and costing Lump Sum mechanism Price Adjustments None Form of Contract (Terms and Conditions) Selection Method Request for Proposals (RFP) Selection Arrangement N/A Market Approach Open International, Two Envelopes Pre/Post Qualification Pre-Qualification Evaluation Selection Quality Cost Based Method Selection (QCBS) Evaluation of Costs Adjusted Bid Price Domestic Preference No Rated Criteria • Specific experience • Methodology and workplan • Qualification and experience of key experts Preferred arrangement for low value, low activities Contract Category Estimated cost Procurement Arrangement and Method Desktops & Goods 300,000 Open National Laptops Others ICT Goods 400,000 Open National Equipment and connectivity, cloud services, others general services Production of Goods 90,000 Limited RFQ Manuals (PIM Monitoring Consultancy 600,000 Open National Information System (MIS) and maintenances Design and hosting Consultancy 56,000 Limited CQS of interactive website Data collection and Consultancy 168,000 Limited CQS analysis at State/federal Level Summary of PPSD to be inform the Bank’s preparation of the PAD The project is designed as framework project and therefore investments and the participating states (the major investments will be implemented by the participating states) are not fully known yet. The security challenges in the country especially in the northern states that will participate in the project may reduce the participation of foreign firms and firms from other parts of the in the procurement process for the project. The current high inflation and exchange rate volatility in the country will affect the costing of the various procurement packages in the project. The use of eProcurement for by the participating states and the FPMU will improve value for money, transparency, economy, efficiency, effectiveness, integrity, and openness of procurement process under the project. The FPMU and the states that are implementing NEWMAP have experience in World Bank Procurement Regulations. The procurement officers have received sufficient training in procurement under World Bank funded project. The gaps that were observed in the implementation of NEWMAP especially in contract management will be addressed under ACReSAL. A sufficiently large numbers of firms are available locally and international for most of the procurement packages under the project, therefore competitive procurement can readily be used to achieved value for value during procurement implementation. The design of the gully erosion sites already cleared under NEWMAP that will be transferred to project will be updated prior to the launching of the procurement processes for the construction of such sites. The PPSD will be regularly updated as there are clear pictures on the participating states and the procurement activities that will be implemented by the states and the FPMU. Contract Estimat Bank Procurement Selecti Evaluati Title, ed Cost Oversig Approach/Competi on on Description US$ and ht tion Method Method and Risk Category Rating Implementati 9,500,00 Prior International SPD Rated on support0 (RFP) Criteria consultancy Substanti (VfM) al Long-term 2.500,00 Prior International SPD Rated framework 0, (RFP) Criteria and policy Substanti (VfM) support al Development 1,600,00 Prior International SPD Rated of strategic 0, (RFP) Criteria catchment Substanti (VfM) plan al Monitoring 600,000, Post International SPD Rated Information Moderate (RFP) Criteria System (MIS) (VfM) and maintenance s Others ICT 400,000, Post National RFB Lowest Equipment Moderate Evaluated and Cost connectivity, cloud services, others general services Desktops & 300,000, Post National RFB Lowest Laptops Low Evaluated Cost Data 168,000, Post National CQS Negotiati collection Moderate on and analysis at State/federal Level Production of 90,000, Post National RFQ Lowest Manuals Low Evaluated (PIM) Design and 56,000, Post National CQS Negotiati hosting of Moderate on interactive website PROCUREMENT Nigeria : Agro-Climatic Resilience in Semi-Arid Landscapes (ACReSAL) PLAN General Information Country: Nigeria 2022-10-04 Bank’s Approval Date of the Original Procurement Plan: 2023-06-01 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P175237 GPN Date: Project Name: Agro-Climatic Resilience in Semi-Arid Landscapes (ACReSAL) Loan / Credit No: IDA / 70150 Kano State ACReSAL Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned National Procure NG-KANO STATE ACRESAL-3 ment Document - 14021-CW-RFB / Constructio Component A: Dryland Mana Single Stage - One E Pending Imp 2023-05-2 IDA / 70150 Post Request for Bids Open - National 1 Envelope proce 228,000.00 0.00 2022-11-28 2022-12-03 2022-12-24 2023-01-07 2023-01-21 n of 30Km minor drainages in gement nvelope lementation 1 ss (Non Bank-SPD rural and urban communities ) NG-KANO STATE ACRESAL-3 National Procure 14013-CW-RFB / Provision of ment Document - Component B: Community Cl Single Stage - One E Pending Imp 2023-03-2 10no. Solar Powered Borehol IDA / 70150 Post Request for Bids Open - National 1 Envelope proce 238,000.00 0.00 2022-11-28 2022-12-03 2022-12-17 2022-12-24 2023-01-28 imate Resilience nvelope lementation 9 e to the neighbouring comm ss (Non Bank-SPD unities in Falgore game reser ) ve. National Procure NG-KANO STATE ACRESAL-3 Component C: Institutional S Request for Quota Single Stage - One E ment Document - Pending Imp 2023-01-1 14018-CW-RFQ / Office Reno IDA / 70150 trengthening and Project Ma Post Limited 200,000.00 0.00 2022-10-17 2022-11-14 tions nvelope 1 Envelope proce lementation 3 vation nagement ss (Non Bank-SPD ) NG-KANO STATE ACRESAL-3 Request for Bids - Component C: Institutional S 14026-CW-RFB / Constructio Single Stage - One E Small Works SPD 2023-04-1 IDA / 70150 trengthening and Project Ma Post Request for Bids Open - National 240,000.00 0.00 Canceled 2022-12-20 2022-12-25 2023-01-15 2023-01-29 2023-02-12 n of 10 Nos. solar powered b nvelope (1 envelope proce 3 nagement oreholes across the State. ss) KNSPMU-RFQ-CW-C4 / Suppo Component C: Institutional S Request for Quota rt to Ministry of Environment Request for Quota Single Stage - One E Pending Imp 2023-08-0 IDA / 70150 trengthening and Project Ma Post Limited tions (Non Bank-S 195,000.00 0.00 2023-06-23 2023-07-07 to conduct drainage clearanc tions nvelope lementation 6 nagement PD) e within the 8 metropolitant area (Phase I) GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NG-KANO STATE ACRESAL-3 Component C: Institutional S Request for Quota Single Stage - One E Pending Impl 14014-GO-RFQ / Procuremen IDA / 70150 trengthening and Project Ma Post Limited 100,000.00 0.00 2022-10-16 2022-11-13 2023-01-12 tions nvelope ementation t and Installation of Solar Po nagement wer Energy NG-KANO STATE ACRESAL-3 14023-GO-RFQ / Provision of Component B: Community Cl Single Stage - One E Pending Impl IDA / 70150 Post Request for Bids Open - National 120,000.00 0.00 2022-11-28 2022-12-03 2023-01-14 2023-02-13 2023-02-27 2023-04-28 livelihood support to Neighbo imate Resilience nvelope ementation uring communities of Falgore Game Reserve KNSPMU-RFQ-GO-C3 / Procur Component C: Institutional S Request for Quota Single Stage - One E Pending Impl IDA / 70150 Post Limited 70,000.00 0.00 2023-06-29 2023-07-20 2023-08-03 ement of ICT Equipments for trengthening and Project Ma tions nvelope ementation SPMU nagement KNSPMU-RFQ-GO-C5 / Procur Component C: Institutional S ement and Installations of So Request for Quota Single Stage - One E Pending Impl IDA / 70150 trengthening and Project Ma Post Limited 98,500.00 0.00 2023-06-17 2023-07-07 2023-07-28 lar Power, Soil and Water Qu tions nvelope ementation nagement ality Laboratory Equipments in Kano. KNSPMU-RFQ-GO-C6 / Procur Component C: Institutional S Request for Quota Single Stage - One E Pending Impl ement of drone, accessories IDA / 70150 trengthening and Project Ma Post Limited 40,000.00 0.00 2023-06-23 2023-07-10 2023-07-31 tions nvelope ementation and training of staff nagement NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NG-KANO STATE ACRESAL-3 14015-CS-CQS / Stakeholder Mobilization, engagements, a Component B: Community Cl Consultant Qualifi Pending Impleme dvocacy visits and communit IDA / 70150 Post Open - National 100,000.00 0.00 2022-11-01 2022-11-08 2022-11-22 2022-11-29 2022-12-13 2023-04-12 imate Resilience cation Selection ntation y meetings and Training on watershed and Climate Chan ge management in 4 Commu nities NG-KANO STATE ACRESAL-3 14020-CS-CQS / Engagement Component C: Institutional S Consultant Qualifi Pending Impleme of Focal NGO to support the i IDA / 70150 trengthening and Project Ma Post Open - National 150,000.00 0.00 2022-10-03 2022-10-24 2022-11-07 2022-11-28 2022-12-12 2023-04-20 cation Selection ntation mplementation of ACReSAL a nagement ctivities in Kano State. NG-KANO STATE ACRESAL-3 14024-CS-CQS / Consultancy Component B: Community Cl Consultant Qualifi Pending Impleme IDA / 70150 Post Open - National 171,000.00 0.00 2022-10-24 2022-11-07 2022-12-05 2022-12-19 2023-01-09 2023-05-09 for Farmer Led Irrigation Dev imate Resilience cation Selection ntation elopment in 3 Communities u nder CFR NG-KANO STATE ACRESAL-3 14022-CS-INDV / ESMP studie Component B: Community Cl Consultant Qualifi Pending Impleme IDA / 70150 Post Limited 180,000.00 0.00 2022-11-21 2022-11-28 2022-12-19 2023-01-02 2023-07-01 s for 3 sites Rarin, Tudun Ful imate Resilience cation Selection ntation ani and Bulbula/Gayawa Page 1 NG-KANO STATE ACRESAL-3 14012-CS-INDV / RAP studies Component B: Community Cl Consultant Qualifi Pending Impleme IDA / 70150 Post Limited 180,000.00 0.00 2022-11-14 2022-11-28 2022-12-19 2023-01-02 2023-07-01 for 3 sites Rarin, Tudun Fulan imate Resilience cation Selection ntation i and Bulbula/Gayawa NG-KANO STATE ACRESAL-3 14025-CS-CQS / Engagement of Engineening Design and S Component A: Dryland Mana Consultant Qualifi IDA / 70150 Post Open - National 150,000.00 0.00 Canceled 2022-10-31 2022-12-19 2022-11-01 2022-11-15 2022-11-29 2022-12-09 2023-09-05 upervision of Water Conserva gement cation Selection tion Structures and Provision of Minor Irrigation at Getso in Gwarzo LGA, Kano State. NG-KANO STATE ACRESAL-3 14011-CS-CQS / Engagement of Consultant for the implem Component B: Community Cl Consultant Qualifi IDA / 70150 Post Limited 100,000.00 0.00 Canceled 2022-12-05 2022-12-19 2022-12-26 2023-01-09 2023-05-09 entation of Community Smar imate Resilience cation Selection t Agriculture (CSA) and Com munity Revolving Funds (CRF ) NG-KANO STATE ACRESAL-3 14019-CS-CQS / Consultancy for the review of existing eng ineering designs of 1 Water C Component A: Dryland Mana Quality And Cost- IDA / 70150 Post Open - National 405,000.00 0.00 Canceled 2022-10-31 2022-12-19 2022-11-14 2022-12-02 2022-12-30 2023-01-20 2023-02-17 2023-03-03 2024-08-29 onservation Structure and 2 gement Based Selection Erosion control sites and sup ervision for the implementati on of 1 Water Conservation S tructure and 2 Erosion sites INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NG-KANO STATE ACRESAL-3 14017-CS-INDV / Engagemen Component A: Dryland Mana Individual Consult Under Implement IDA / 70150 Post Limited 10,000.00 0.00 2022-10-24 2022-12-19 2022-10-29 2022-11-05 2022-11-19 2022-12-19 t of Consultant for Minor Engi gement ant Selection ation neering Design of 30Km Drai nages NG-KANO STATE ACRESAL-3 14010-CS-INDV / Resource a Component B: Community Cl Individual Consult Pending Impleme nd inventory study of flora an IDA / 70150 Post Limited 30,000.00 0.00 2022-11-07 2022-11-12 2022-11-19 2022-12-03 2023-06-01 imate Resilience ant Selection ntation d fauna for effective conserv ation at Falgore Game reserv e KNSPMU-INDV-CS-C7 / Devel Component C: Institutional S Individual Consult Pending Impleme opment, hosting and mainten IDA / 70150 trengthening and Project Ma Post Limited 25,000.00 0.00 2023-06-26 2023-06-30 2023-07-07 2023-07-14 2023-08-04 ant Selection ntation ance of Kano ACReSAL websi nagement te KNSPMU-CS-INDV-C14 / Revi Component C: Institutional S Individual Consult Pending Impleme ew and update of ESMP studi IDA / 70150 trengthening and Project Ma Post Limited 50,000.00 0.00 2023-06-15 2023-06-16 2023-06-30 2023-07-10 2023-09-08 ant Selection ntation es of 2 sites (Fajewa and Yar nagement Titi) KNSPMU-INDV-CS-C9 / Revie Component C: Institutional S Individual Consult Pending Impleme w and update of RAP studies IDA / 70150 trengthening and Project Ma Post Limited 50,000.00 0.00 2023-06-15 2023-06-18 2023-06-21 2023-06-30 2023-08-01 ant Selection ntation of 2 sites (Fajewa and Yar Titi nagement ) Page 2 PROCUREMENT PLAN (Textual Part) 1. Project information: Country: Central African Republic Project Name: Education Sector Plan Support Project Project Identification: P173103 2. Project Implementation Agency: Ministry of Primary and Secondary School (MEPS) 3. Date of the Procurement Plan: 31st August 2021 4. Period covered by this Procurement Plan: From September 2021 to March 2023 5. Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the Public Procurement Law N° 08-017 of 6th June 2008 of the RCA, such arrangements shall be subject to Commented [AM1]: TBC paragraph 5.4 of the Procurement Regulations. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. “Not Applicable” Procurement of Second-Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: is not applicable Works: is not applicable 6. Other Relevant Procurement Information. The implementation of the Contingency Emergency Response Component (CERC) of the Project will be governed by the Paragraph 12 of Section III of the Investment Project Financing (IPF) Policy and Paragraph 5.7 of the Procurement Regulations - Projects in Situations of Urgent Need of Assistance or Capacity Constraints. Once the CERC is triggered, condensed timeline arrangements and deferred procurement arrangements will be applicable for the procurement activities implementation under the Project as required. This will help the Government improve response times in the event of future situations where urgent assistance is needed; such as the Covid-19 Pandemic situation or other crisis (that is, a natural, climate-related, or man- made disaster or crisis that has caused or is likely to cause a major adverse economic and/or social impact). PROCUREMENT Central African Republic : Central African Republic - Education Sector Plan Support Project PLAN General Information Country: Central African Republic 2021-09-09 Bank’s Approval Date of the Original Procurement Plan: 2023-06-02 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P173103 GPN Date: Project Name: Central African Republic - Education Sector Plan Support Project Loan / Credit No: TF / B5223 CCP PUSEB Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned CF-PAPSE II-238853-CW-RFB National Procure Component 1: Improving acc / Travaux de Construction de ment Document - ess to pre-primary, primary Single Stage - One E Pending Imp 2024-01-2 160 salles de classe niveau d TF / B5223 Post Request for Bids Open - National 1 Envelope proce 2,560,000.00 0.00 2023-04-12 2023-04-17 2023-05-29 2023-06-28 2023-08-02 and lower secondary educati nvelope lementation 9 u fondamental 2 dans l'Inspe ss (Non Bank-SPD on ction Académique de Bangui. ) CF-PUSEB-348381-CW-RFB / National Procure Travaux d'extension, réhabili Component 1: Improving acc ment Document - tation des salles de classe et ess to pre-primary, primary Single Stage - One E Pending Imp 2023-12-2 TF / B5223 Post Request for Bids Open - National 1 Envelope proce 1,165,124.00 0.00 2023-03-09 2023-03-14 2023-04-25 2023-05-25 2023-06-29 construction de latrines au pr and lower secondary educati nvelope lementation 6 ss (Non Bank-SPD éscolaire et au fondamental on ) 1&2 dans la préfecture de la Lobaye CF-PUSEB-348397-CW-RFB / National Procure Travaux d'extension, réhabili Component 1: Improving acc ment Document - tation des salles de classe et ess to pre-primary, primary Single Stage - One E Under Imple 2024-01-1 TF / B5223 Post Request for Bids Open - National 1 Envelope proce 1,038,000.00 0.00 2023-03-24 2023-04-25 2023-03-29 2023-05-10 2023-06-09 2023-07-14 construction de latrines au pr and lower secondary educati nvelope mentation 0 ss (Non Bank-SPD éscolaire et au fondamental on ) 1&2 dans la préfecture de la Kemo CF-PUSEB-348836-CW-RFB / National Procure Component 1: Improving acc Extension des salles de class ment Document - ess to pre-primary, primary Single Stage - One E Under Imple 2024-01-1 e et construction de latrines TF / B5223 Post Request for Bids Open - National 2 Envelope proce 552,000.00 0.00 2023-03-24 2023-05-02 2023-03-29 2023-05-02 2023-05-10 2023-06-09 2023-07-14 and lower secondary educati nvelope mentation 0 au préscolaire et au fondame ss (Non Bank-SPD on ntal 1&2 dans la préfecture d ) e la Nana Gribizi. CF-PUSEB-348779-CW-RFB / National Procure Travaux d’extension, réhabili Component 1: Improving acc ment Document - tation des salles de classe et ess to pre-primary, primary Single Stage - One E Pending Imp 2024-05-0 TF / B5223 Post Request for Bids Open - National 1 Envelope proce 2,915,394.00 0.00 2023-07-19 2023-07-24 2023-09-04 2023-10-04 2023-11-08 construction de latrines au pr and lower secondary educati nvelope lementation 6 ss (Non Bank-SPD éscolaire et au fondamental on ) 1&2 dans la préfecture de l’O uham CF-PUSEB-348783-CW-RFB / National Procure Travaux d’extension, réhabili Component 1: Improving acc ment Document - tation des salles de classe et ess to pre-primary, primary Single Stage - One E Pending Imp 2024-07-0 TF / B5223 Post Request for Bids Open - National 2 Envelope proce 626,177.00 0.00 2023-09-20 2023-09-25 2023-11-06 2023-12-06 2024-01-10 construction de latrines au pr and lower secondary educati nvelope lementation 8 ss (Non Bank-SPD éscolaire et au fondamental on ) 1&2 dans la préfecture de la Sangha Mbaére CF-PUSEB-348840-CW-RFB / National Procure Fourniture et livraison des m Component 1: Improving acc ment Document - obiliers scolaires pour les sall ess to pre-primary, primary Single Stage - One E Pending Imp 2024-04-1 TF / B5223 Post Request for Bids Limited 1 Envelope proce 126,768.00 0.00 2023-06-28 2023-07-03 2023-08-14 2023-09-13 2023-10-18 es de classes construites et r and lower secondary educati nvelope lementation 5 ss (Non Bank-SPD éhabilitées au préscolaire et on ) au fondamental 1&2 dans la préfecture de la Lobaye. National Procure CF-PUSEB-348983-CW-RFB / Component 2: Improving the ment Document - Extension de l’École Normale quality of education and pre- Single Stage - One E Pending Imp 2025-02-0 TF / B5223 Post Request for Bids Open - National 1 Envelope proce 689,710.00 0.00 2024-04-23 2024-04-28 2024-06-09 2024-07-09 2024-08-13 d’Instituteurs de Bambari (EN service and in-service teach nvelope lementation 9 ss (Non Bank-SPD I de Bambari transformée en er training ) ENF) CF-PUSEB-348982-CW-RFB / Construction de points d'eau National Procure standard à Bangui et dans le Component 1: Improving acc ment Document - s préfectures de l'Ombella M ess to pre-primary, primary Single Stage - One E Pending Imp 2025-01-0 TF / B5223 Post Request for Bids Open - National 1 Envelope proce 575,878.00 0.00 2024-03-20 2024-03-25 2024-05-06 2024-06-05 2024-07-10 poko, Lobaye, Kemo, Nana G and lower secondary educati nvelope lementation 6 ss (Non Bank-SPD ribizi,l’Ouham, Ouham Pende on ) , Mbomou, Haut Mbomou, Ha ute Kotto, Sangha Mbaere et Bamingui Bangoran. CF-PAPSE II-238856-CW-RFB National Procure Component 1: Improving acc / Travaux de Réhabilitation d ment Document - ess to pre-primary, primary Single Stage - One E Pending Imp 2024-08-0 e 40 salles de classe au nive TF / B5223 Post Request for Bids Open - National 1 Envelope proce 320,000.00 0.00 2023-10-17 2023-10-22 2023-12-03 2024-01-02 2024-02-06 and lower secondary educati nvelope lementation 4 au du fondamental 2 dans l'I ss (Non Bank-SPD on nspection Académique de Ba ) ngui. CF-PUSEB-352044-CW-RFB / National Procure Travaux d extension des sall Component 1: Improving acc ment Document - es de classe et construction ess to pre-primary, primary Single Stage - One E Pending Imp 2024-04-0 TF / B5223 Post Request for Bids Open - National 1 Envelope proce 1,315,816.00 0.00 2023-06-14 2023-06-19 2023-07-31 2023-08-30 2023-10-04 de latrines aux préscolaires e and lower secondary educati nvelope lementation 1 ss (Non Bank-SPD t au fondamental 1 dans la pr on ) éfecture de l'ombella Mpoko. Request for Quota CF-PUSEB-360440-CW-RFQ / Component 3: Strengthening Request for Quota Single Stage - One E tions - Small Work Pending Imp 2024-01-0 Travaux d'extension de l'Unit TF / B5223 overall education system ma Post Limited 110,000.00 0.00 2023-05-11 2023-07-06 tions nvelope s (Emergency) SP lementation 2 é de Coordination des Projets nagement and resilience D -Competitive Education National Procure CF-PUSEB-364468-CW-RFB / Component 1: Improving acc ment Document - Travaux de construction d'un ess to pre-primary, primary Single Stage - One E Pending Imp 2024-04-0 TF / B5223 Post Request for Bids Open - National 1 Envelope proce 275,908.00 0.00 2023-06-15 2023-06-20 2023-08-01 2023-08-31 2023-10-05 Centre Pédagogique Régional and lower secondary educati nvelope lementation 2 ss (Non Bank-SPD (CPR) à Paoua: Préfecture de on ) l'Ouham-Pendé CF-PUSEB-364470-CW-RFQ / National Procure Travaux de réhabilitation d'u Component 1: Improving acc ment Document - n Centre Pédagogique Régio ess to pre-primary, primary Request for Quota Single Stage - One E Pending Imp 2024-02-1 TF / B5223 Post Limited 1 Envelope proce 45,985.00 0.00 2023-06-20 2023-08-15 nal (CPR) et extension d'une and lower secondary educati tions nvelope lementation 1 ss (Non Bank-SPD salle de classe à Berbérati: Pr on ) éfecture de Mambéré-Kadéï CF-PUSEB-364471-CW-RFQ / National Procure Component 1: Improving acc Travaux de réhabilitation d'u ment Document - ess to pre-primary, primary Request for Quota Single Stage - One E Pending Imp 2024-02-1 n Centre Pédagogique Régio TF / B5223 Post Limited 1 Envelope proce 45,985.00 0.00 2023-06-20 2023-08-15 and lower secondary educati tions nvelope lementation 1 nal (CPR) et extension d'une ss (Non Bank-SPD on salle de classe à KAGA-BAND ) ORO Page 1 CF-PUSEB-364473-CW-RFQ / National Procure Component 1: Improving acc Travaux de réhabilitation d'u ment Document - ess to pre-primary, primary Request for Quota Single Stage - One E Pending Imp 2024-02-1 n Centre Pédagogique Régio TF / B5223 Post Limited 1 Envelope proce 45,985.00 0.00 2023-06-20 2023-08-15 and lower secondary educati tions nvelope lementation 1 nal (CPR) et extension d'une ss (Non Bank-SPD on salle de classe à BANGASSO ) U GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CF-PAPSE II--237980-GO-RF Component 3: Strengthening Request for Quota Single Stage - One E Pending Impl Q / Acquisition d’un (1) Véhic TF / B5223 overall education system ma Post Limited 120,000.00 0.00 2021-11-24 2022-01-19 2022-07-18 tions nvelope ementation ule Pick up pour la CCP. nagement and resilience CF-PAPSE II-237981-GO-RFQ Component 3: Strengthening Request for Quota Single Stage - One E Pending Impl / Acquisition de 2 motos pour TF / B5223 overall education system ma Post Limited 10,000.00 0.00 2021-11-20 2022-01-15 2022-07-14 tions nvelope ementation la CCP. nagement and resilience CF-PUSEB-348644-GO-RFQ / Fourniture et livraison des m Component 1: Improving acc obiliers scolaires pour les sall ess to pre-primary, primary Request for Quota Single Stage - One E Pending Impl TF / B5223 Post Limited 61,304.00 0.00 2023-07-15 2023-09-09 2024-03-07 es de classes construites et r and lower secondary educati tions nvelope ementation éhabilitées au préscolaire et on au fondamental 1&2 dans la préfecture de NANA GRIBIZI CF-PAPSE II-237998-GO-RFQ / Acquisition de mobilier (tabl Component 1: Improving acc e bancs, bureau, chaises ) de ess to pre-primary, primary Request for Quota Single Stage - One E 86 salles au niveau pré-prim TF / B5223 Post Limited 32,700.00 0.00 Canceled 2022-11-23 2023-01-18 2023-07-17 and lower secondary educati tions nvelope aire, de 400 salles de classe on au niveau primaire, de 8 coll èges de proximité et de 160 salles de classe niveau du fo ndamental CF-PUSEB-348960-GO-RFQ / Fourniture et livraison des m Component 1: Improving acc obiliers scolaires pour les sall ess to pre-primary, primary Request for Quota Single Stage - One E Pending Impl es de classes construites et r TF / B5223 Post Limited 25,120.00 0.00 2024-12-23 2025-02-17 2025-08-16 and lower secondary educati tions nvelope ementation éhabilitées au préscolaire et on au fondamental 1&2 dans la préfecture de Bamingui Bang oran. CF-PUSEB-348963-GO-RFQ / Fourniture et livraison des m Component 1: Improving acc obiliers scolaires pour les sall ess to pre-primary, primary Request for Quota Single Stage - One E Pending Impl es de classes construites et r TF / B5223 Post Limited 78,206.00 0.00 2023-12-23 2024-02-17 2024-08-15 and lower secondary educati tions nvelope ementation éhabilitées au préscolaire et on au fondamental 1&2 dans la préfecture de la SANGHA MB AERE. CF-PUSEB-348965-GO-RFQ / Fourniture et livraison des m Component 1: Improving acc obiliers scolaires pour les sall ess to pre-primary, primary Request for Quota Single Stage - One E Pending Impl TF / B5223 Post Limited 62,160.00 0.00 2024-01-01 2024-02-26 2024-08-24 es de classes construites et r and lower secondary educati tions nvelope ementation éhabilitées au préscolaire et on au fondamental 1&2 dans la préfecture de la HAUTE KOTT O. CF-PUSEB-348966-GO-RFQ / Fourniture et livraison des m Component 1: Improving acc obiliers scolaires pour les sall ess to pre-primary, primary Request for Quota Single Stage - One E Pending Impl TF / B5223 Post Limited 94,200.00 0.00 2024-01-30 2024-03-26 2024-09-22 es de classes construites et r and lower secondary educati tions nvelope ementation éhabilitées au préscolaire et on au fondamental 1&2 dans la préfecture de MBOMOU. CF-PUSEB-348968-GO-RFQ / Fourniture et livraison des m Component 1: Improving acc obiliers scolaires pour les sall ess to pre-primary, primary Request for Quota Single Stage - One E Pending Impl TF / B5223 Post Limited 18,840.00 0.00 2024-02-25 2024-04-21 2024-10-18 es de classes construites et r and lower secondary educati tions nvelope ementation éhabilitées au préscolaire et on au fondamental 1&2 dans la préfecture de HAUT MBOMO U. CF-PUSEB-348985-GO-RFQ / Component 2: Improving the Equipements de l’École Norm quality of education and pre- Request for Quota Single Stage - One E Pending Impl TF / B5223 Post Limited 103,465.00 0.00 2024-04-20 2024-06-15 2024-12-12 ale d’Instituteurs de Bambari service and in-service teach tions nvelope ementation (ENI de Bambari transformée er training en ENF) CF-PUSEB-348969-GO-RFQ / Fourniture et livraison des m Component 1: Improving acc obiliers scolaires pour les sall ess to pre-primary, primary Single Stage - One E Pending Impl es de classes construites et r TF / B5223 Post Request for Bids Open - National 710,242.00 0.00 2023-09-19 2023-09-24 2023-11-05 2023-12-05 2024-01-09 2024-07-07 and lower secondary educati nvelope ementation éhabilitées au préscolaire et on au fondamental 1&2 dans les préfectures de l'Ouham et l'O uham Pendé CF-PUSEB-348980-GO-RFQ / Acquisition des mobiliers scol Component 1: Improving acc aires pour les salles de class ess to pre-primary, primary Request for Quota Single Stage - One E Pending Impl TF / B5223 Post Limited 100,000.00 0.00 2023-11-04 2023-12-30 2024-06-27 e construites et réhabilitées and lower secondary educati tions nvelope ementation au Fondamental 2 dans l’Insp on ection Académique de Bangu i. CF-PUSEB-348642-GO-RFQ / Fourniture et livraison des m Component 1: Improving acc obiliers scolaires pour les sall ess to pre-primary, primary Single Stage - One E Pending Impl es de classes construites et r TF / B5223 Post Request for Bids Open - National 177,972.00 0.00 2023-06-20 2023-06-25 2023-08-06 2023-09-05 2023-10-10 2024-04-07 and lower secondary educati nvelope ementation éhabilitées au préscolaire et on au fondamental 1&2 dans les préfectures de l'Ombella Mpo ko. CF-PUSEB-348643-GO-RFQ / Fourniture et livraison des m Component 1: Improving acc obiliers scolaires pour les sall ess to pre-primary, primary Request for Quota Single Stage - One E Pending Impl TF / B5223 Post Limited 100,000.00 0.00 2023-07-15 2023-09-09 2024-03-07 es de classes construites et r and lower secondary educati tions nvelope ementation éhabilitées au préscolaire et on au fondamental 1&2 dans la préfecture de la KEMO CF-PUSEB-298235-GO-RFQ / Component 1: Improving acc Acquisition des mobiliers pou ess to pre-primary, primary Request for Quota Single Stage - One E Pending Impl TF / B5223 Post Limited 10,000.00 0.00 2023-11-22 2024-01-17 2024-07-15 r les 4 centres de formation d and lower secondary educati tions nvelope ementation es enseignants et collèges. on Page 2 CF-PAPSE II-237997-GO-RFQ / Acquisition des équipement Component 1: Improving acc s informatiques pour les Cent ess to pre-primary, primary Request for Quota Single Stage - One E Pending Impl res Pédagogique Régionaux ( TF / B5223 Post Limited 62,079.00 0.00 2023-07-22 2023-09-16 2024-03-14 and lower secondary educati tions nvelope ementation CPR) dans la ville de Paoua, c on hef de la Préfecture de l’Ouh am Pendé de Berberati, Kaga Bandoro et de Bangassou. NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CF-PAPSE II-238863-NC-DIR / Component 3: Strengthening Request for Quota Single Stage - One E Pending Impl Services d'entretien et de ne TF / B5223 overall education system ma Post Limited 12,000.00 0.00 2022-09-26 2022-11-21 2023-05-20 tions nvelope ementation ttoyage des locaux de la CCP nagement and resilience . CF-PAPSE II-238860-NC-DIR / Component 3: Strengthening Entretien et réparation du m Request for Quota Single Stage - One E Pending Impl TF / B5223 overall education system ma Post Limited 20,000.00 0.00 2022-09-26 2022-11-21 2023-05-20 atériel informatique, de bure tions nvelope ementation nagement and resilience au et réseaux au titre de 202 1 CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CF-PAPSE II-243035-CS-LCS / Consultant pour le Suivi-cont Component 1: Improving acc rôle des infrastructures de 40 ess to pre-primary, primary Quality And Cost- Open - Internationa Pending Impleme TF / B5223 Post 636,160.00 0.00 2022-08-31 2022-09-21 2022-11-04 2022-12-02 2023-01-01 2023-02-05 2023-03-12 2024-03-11 0 salles de classes des école and lower secondary educati Based Selection l ntation s primaires, de 8 collèges de on proximité et de 160 salles de classe du fondamental 2. CF-PUSEB-348776-CS-LCS / Mission d’opérateur d’exécuti Component 1: Improving acc on des travaux de constructi ess to pre-primary, primary Quality And Cost- Pending Impleme on et de réhabilitation des sa TF / B5223 Post Open - National 536,939.00 0.00 2024-03-13 2024-04-03 2024-05-17 2024-06-14 2024-07-14 2024-08-18 2024-09-22 2025-09-22 and lower secondary educati Based Selection ntation lles de classe et construction on de latrines au préscolaire et au fondamental 1&2 dans la préfecture de Haute Kotto CF-PUSEB-349132-CS-QCBS / Recrutement des Consultan Component 1: Improving acc ts pour le Suivi et le Contrôle ess to pre-primary, primary Consultant Qualifi Pending Impleme des Travaux de Construction TF / B5223 Post Open - National 197,488.00 0.00 2023-05-29 2023-06-19 2023-08-02 2023-09-01 2023-10-06 2024-04-03 and lower secondary educati cation Selection ntation d’Infrastructures Scolaires da on ns l’Inspection Académique d u Centre(IAC) – Préfecture de la Kemo et de Nana Gribizi. CF-PUSEB-348763-CS-LCS / Mission d’opérateur d’exécuti Component 1: Improving acc on des travaux de constructi ess to pre-primary, primary Quality And Cost- Pending Impleme on et de réhabilitation des sa TF / B5223 Prior Open - National 2,382,062.00 0.00 2024-04-22 2024-05-13 2024-06-26 2024-07-24 2024-08-23 2024-09-27 2024-11-01 2025-11-01 and lower secondary educati Based Selection ntation lles de classe et construction on de latrines au préscolaire et au fondamental 1&2 dans la préfecture de l’Ouham Pendé CF-PUSEB-348771-CS-LCS / Mission d’opérateur d’exécuti Component 1: Improving acc on des travaux de constructi ess to pre-primary, primary Quality And Cost- Pending Impleme on et de réhabilitation des sa TF / B5223 Post Open - National 286,117.00 0.00 2024-04-09 2024-04-30 2024-06-13 2024-07-11 2024-08-10 2024-09-14 2024-10-19 2025-10-19 and lower secondary educati Based Selection ntation lles de classe et construction on de latrines au préscolaire et au fondamental 1&2 dans la préfecture de Bamingui Bang oran CF-PUSEB-348773-CS-LCS / Mission d’opérateur d’exécuti Component 1: Improving acc on des travaux de constructi ess to pre-primary, primary Quality And Cost- Pending Impleme on et de réhabilitation des sa TF / B5223 Post Open - National 207,902.00 0.00 2024-03-18 2024-04-08 2024-05-22 2024-06-19 2024-07-19 2024-08-23 2024-09-27 2025-09-27 and lower secondary educati Based Selection ntation lles de classe et construction on de latrines au préscolaire et au fondamental 1&2 dans la préfecture de Haut Mbomou CF-PUSEB-348772-CS-LCS / Mission d’opérateur d’exécuti Component 1: Improving acc on des travaux de constructi ess to pre-primary, primary Quality And Cost- Pending Impleme on et de réhabilitation des sa TF / B5223 Post Open - National 930,972.00 0.00 2024-04-02 2024-04-23 2024-06-06 2024-07-04 2024-08-03 2024-09-07 2024-10-12 2025-10-12 and lower secondary educati Based Selection ntation lles de classe et construction on de latrines au préscolaire et au fondamental 1&2 dans la préfecture de Mbomou CF-PUSEB-334651-CS-QCBS / Recrutement des Consultan ts pour le Suivi et le Contrôle Component 1: Improving acc des Travaux de Construction ess to pre-primary, primary Quality And Cost- TF / B5223 Post Open - National 514,910.00 0.00 Canceled 2023-01-11 2023-02-01 2023-03-17 2023-04-14 2023-05-14 2023-06-18 2023-07-23 2024-07-22 d’Infrastructures Scolaires da and lower secondary educati Based Selection ns l’ Inspection Académique on du Centre-Sud (IACS) – Préfe cture de la Lobaye et de l’O mbella-Mpoko INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CF-PAPSE II-240507-CS-INDV Component 2: Improving the / Recrutement d’un consulta quality of education and pre- Individual Consult Under Implement TF / B5223 Post Open 12,500.00 0.00 2021-11-22 2021-12-14 2022-01-10 2022-01-31 2022-03-07 2022-06-05 nt pour les études en vue de service and in-service teach ant Selection ation l’introduction du Sango. er training CF-PAPSE II-240508-CS-INDV Component 3: Strengthening / Recrutement Consultant po Individual Consult Pending Impleme TF / B5223 overall education system ma Post Open 20,000.00 0.00 2021-11-29 2022-01-17 2022-02-07 2022-03-14 2022-06-12 ur la réalisation du recensem ant Selection ntation nagement and resilience ent des enseignants du seco ndaire. Page 3 CF-PAPSE II-240512-CS-INDV / Recrutement d'un expert po Component 3: Strengthening Individual Consult Pending Impleme ur mettre en place une base TF / B5223 overall education system ma Post Open 50,000.00 0.00 2022-01-24 2022-03-14 2022-04-04 2022-05-09 2022-08-07 ant Selection ntation de données de gestion RH lié nagement and resilience e au SIGE et à la liste de paie des enseignants. CF-PAPSPE II-240514-CS-IND Component 3: Strengthening V / Recrutement Consultant p Individual Consult Pending Impleme TF / B5223 overall education system ma Post Open 50,000.00 0.00 2022-01-25 2022-03-15 2022-04-05 2022-05-10 2022-11-06 our le renforcement du systè ant Selection ntation nagement and resilience me d'évaluation de l'apprenti ssage. CF-PAPSE II-240516-CS-INDV Component 3: Strengthening Individual Consult Pending Impleme / Recrutement Consultant po TF / B5223 overall education system ma Post Open 50,000.00 0.00 2022-01-25 2022-03-15 2022-04-05 2022-05-10 2023-05-10 ant Selection ntation ur le renforcement de la Cell nagement and resilience ule d'Urgence. CF-PAPSE II-240518-CS-INDV Component 3: Strengthening / Recrutement d'un statisticie Individual Consult Pending Impleme TF / B5223 overall education system ma Post Open 31,200.00 0.00 2022-01-25 2022-03-15 2022-04-05 2022-05-10 2023-05-10 n / planificateur pour souteni ant Selection ntation nagement and resilience r la cellule de coordination E SP (DGESP). CF-PAPSE II-240519-CS-INDV Component 1: Improving acc / Recrutement Consultant po ess to pre-primary, primary Individual Consult Pending Impleme TF / B5223 Post Open 30,000.00 0.00 2022-02-07 2022-03-28 2022-04-18 2022-05-23 2022-08-21 ur l’étude sur l’approche com and lower secondary educati ant Selection ntation munautaire de construction d on es infrastructures. CF-PUSEB-298137-CS-QBS / Recrutement d'un Consultant individuel pour l'élaboration Component 3: Strengthening Pending Impleme de plans de développement TF / B5223 overall education system ma Post Direct Selection Direct - National 4,000.00 0.00 2022-09-06 2022-09-16 2022-11-20 2023-05-19 ntation en faveur des peuples autoch nagement and resilience tones (PPA) dans les zones c ouvertes par le PUSEB et PAP SE II CF-PUSEB-298222-CS-QBS / Recrutement des Consultants individuels / Ingénieurs en G Component 1: Improving acc énie Civil en appui à la Direct ess to pre-primary, primary Pending Impleme TF / B5223 Post Direct Selection Direct - National 15,600.00 0.00 2023-08-15 2023-08-25 2023-10-29 2024-04-26 ion des équipements, de con and lower secondary educati ntation struction des bâtiments scola on ires du MEN pour l'évaluation des infrastructures scolaires des projets PUSEB, PAPSE II e t MAINGO. CF-PUSEB-360436-CS-CQS / Recrutement d'un consultant Component 3: Strengthening Individual Consult Under Implement individuel chargé des opérati TF / B5223 overall education system ma Post Limited 7,200.00 0.00 2023-05-06 2023-05-21 2023-05-11 2023-06-01 2023-07-06 2024-01-02 ant Selection ation ons pour la mie en œuvre de nagement and resilience la Cellule d'appui au Ministèr e de l'Education Nationale. CF-PUSEB-360437-CS-FBS / Recrutement d'un consultant Component 3: Strengthening Individual Consult Under Implement individuel spécialiste Genre d TF / B5223 overall education system ma Post Limited 5,400.00 0.00 2023-05-06 2023-05-22 2023-05-11 2023-06-01 2023-07-06 2024-01-02 ant Selection ation ans la mise en œuvre de la C nagement and resilience ellule d'appui au Ministère de l'Education Nationale. CF-PUSEB-360438-CS-INDV / Recrutement d'un consultant individuel spécialiste en Activ Component 3: Strengthening Individual Consult Under Implement ités Génératrices de Revenu TF / B5223 overall education system ma Post Limited 5,600.00 0.00 2023-05-06 2023-05-22 2023-05-11 2023-06-01 2023-07-06 2024-01-02 ant Selection ation (AGR) dans le cadre de la mis nagement and resilience e en œuvre de la Cellule d'ap pui au Ministère de l'Educatio n Nationale. CF-PUSEB-362808-CS-CDS / Recrutement d'un Cabinet/Co Component 2: Improving the nsultant International pour l' quality of education and pre- Direct - Internation Pending Impleme TF / B5223 Post Direct Selection 71,242.50 0.00 2023-05-21 2023-05-31 2023-08-04 2024-01-31 accompagnement à l'évaluati service and in-service teach al ntation on d'impact de la sous-comp er training osante 2.1 du projet PAPSEII CF-PUSEB-363976-CS-FBS / Recrutement d'in consultant i ndividuel ( Contrôleur Superv Component 1: Improving acc iseur CS1) pour le suivi et le ess to pre-primary, primary Individual Consult Pending Impleme TF / B5223 Post Limited 7,000.00 0.00 2023-05-31 2023-06-05 2023-06-26 2023-07-31 2024-01-27 contrôle des travaux de cons and lower secondary educati ant Selection ntation truction d'infrastructures scol on aires dans la préfecture de la LOBAYE. Inspection Académi que du Centre-Sud CF-PUSEB-363977-CS-FBS / Recrutement d'un consultant individuel ( Contrôleur Super Component 1: Improving acc viseur CS2) pour le suivi et le ess to pre-primary, primary Individual Consult Pending Impleme TF / B5223 Post Limited 7,000.00 0.00 2023-05-31 2023-06-05 2023-06-26 2023-07-31 2024-01-27 contrôle des travaux de cons and lower secondary educati ant Selection ntation truction d'infrastructures scol on aires dans la préfecture de la LOBAYE. Inspection Académi que du Sud CF-PUSEB-363979-CS-FBS / Recrutement d'un consultant Component 1: Improving acc individuel (Contrôleur Superv ess to pre-primary, primary Individual Consult Pending Impleme iseur CS1) pour le suivi et co TF / B5223 Post Limited 7,000.00 0.00 2023-05-31 2023-06-05 2023-06-26 2023-07-31 2024-01-27 and lower secondary educati ant Selection ntation ntrôle des travaux d'infrastru on ctures scolaires dans la préfe cture de l'OMBELLA-MPOKO. I nspection Académique du Ce ntre-Sud CF-PUSEB-363980-CS-FBS7 / Recrutement d'un consultant individuel (Contrôleur Superv Component 1: Improving acc iseur CS2) pour le suivi et co ess to pre-primary, primary Individual Consult Pending Impleme TF / B5223 Post Limited 7,000.00 0.00 2023-05-31 2023-06-05 2023-06-26 2023-07-31 2024-01-27 ntrôle des travaux de constru and lower secondary educati ant Selection ntation ction d'infrastructures scolair on es dans la préfecture de l'OM BELLA-MPOKO Inspection Aca démique du Centre-Sud CF-PUSEB-363981-CS-FBS / Recrutement d'un consultant Component 1: Improving acc individuel ( Contrôleur C1) po ess to pre-primary, primary Individual Consult Pending Impleme ur le suivi et contrôle des tra TF / B5223 Post Limited 4,800.00 0.00 2023-05-31 2023-06-05 2023-06-26 2023-07-31 2024-01-27 and lower secondary educati ant Selection ntation vaux de construction d'infras on tructures scolaires dans la pr éfecture de la LOBAYE. Inspe ction Académique du Centre- Sud Page 4 CF-PUSEB-363984-CS-FBS / Recrutement d'un consultant Component 1: Improving acc individuel ( Contrôleur C2) po ess to pre-primary, primary Individual Consult Pending Impleme ur le suivi et contrôle des tra TF / B5223 Post Limited 4,800.00 0.00 2023-05-31 2023-06-05 2023-06-26 2023-07-31 2024-01-27 and lower secondary educati ant Selection ntation vaux de construction d'infras on tructures scolaires dans la pr éfecture de la LOBAYE. Inspe ction Académique du Centre- Sud CF-PUSEB-364038-CS-INDV / Recrutement d'un consultant Component 1: Improving acc individuel (Contrôleur C1) po ess to pre-primary, primary Individual Consult Pending Impleme ur le suivi et contrôle des tra TF / B5223 Post Limited 4,800.00 0.00 2023-05-31 2023-06-05 2023-06-26 2023-07-31 2024-01-27 and lower secondary educati ant Selection ntation vaux d'infrastructures scolair on es dans l'l'OMBELLA-MPOKO. Inspection Académique du C entre-Sud. CF-PUSEB-364041-CS-INDV / Recrutement d'un consultant Component 1: Improving acc individuel (Contrôleur C2) po ess to pre-primary, primary Individual Consult Pending Impleme ur le suivi et contrôle des tra TF / B5223 Post Limited 4,800.00 0.00 2023-05-31 2023-06-05 2023-06-26 2023-07-31 2024-01-27 and lower secondary educati ant Selection ntation vaux d'infrastructures scolair on es dans l'OMBELLA-MPOKO. I nspection Académique du Ce ntre-Sud. CF-PUSEB-364042-CS-INDV / Recrutement d'un consultant Component 1: Improving acc individuel (Contrôleur C3) ch ess to pre-primary, primary Individual Consult Pending Impleme argé du suivi et contrôle des TF / B5223 Post Limited 4,800.00 0.00 2023-05-31 2023-06-05 2023-06-26 2023-07-31 2024-01-27 and lower secondary educati ant Selection ntation travaux de construction d'infr on astructures scolaires dans l'O MBELLA-MPOKO. Inspection A cadémique du Centre-Sud CF-PUSEB-364043-CS-INDV / Recrutement d'un consultant Component 1: Improving acc (Contrôleur Junior CJ 1) charg ess to pre-primary, primary Individual Consult Pending Impleme é du suivi et contrôle des tra TF / B5223 Post Limited 3,600.00 0.00 2023-05-31 2023-06-05 2023-06-26 2023-07-31 2024-01-27 and lower secondary educati ant Selection ntation vaux de construction d'infras on tructures scolaire dans la LO BAYE. Inspection Académiqu e du Centre-Sud CF-PUSEB-364044-CS-INDV / Recrutement d'un consultant Component 1: Improving acc (Contrôleur Junior CJ 1) charg ess to pre-primary, primary Individual Consult Pending Impleme é du suivi et contrôle des tra TF / B5223 Post Limited 3,600.00 0.00 2023-05-31 2023-06-05 2023-06-26 2023-07-31 2024-01-27 and lower secondary educati ant Selection ntation vaux de construction des infr on astructures scolaires dans l'O MBELLA-MPOKO. Inspection A cadémique du Centre-Sud Page 5 PLAN DE PASSATION DE MARCHÉS (Partie Textuelle) Information sur le Projet : [Nom du pays] [Nom du Projet] [No d’identification du projet] Agence d’exécution du Projet : [Insérer le nom officiel de l’Agence] Date du plan de passation des marchés : [Insérer la date] Période couverte par ce plan de passation des marchés : [Insérer date de début, date de fin] Préambule Conformément au paragraphe 5.9 du “Règlement de Passation des Marchés pour les Emprunteurs sollicitant le Financement de Projets d’Investissement (FPI)” (Juillet 2016) (“Règlement de Passation des Marchés”) l’Emprunteur utilise les outils électroniques de planification et de suivi de la passation des marchés (STEP) pour préparer, valider et actualiser ses plans de passation des marchés et effectuer toutes les transactions liées à la passation des marchés du projet. Cette partie textuelle ainsi que les tableaux du plan de passation des marchés dans STEP constituent le plan de passation des marchés du projet. Les conditions suivantes s'appliquent à toutes les activités de passation de marchés du plan de passation de marchés. Les autres éléments du plan de passation des marchés tels que requis au paragraphe 4.4 du Règlement de passation des marchés sont énoncés dans STEP. Les Dossiers types d’appel d’offres publiés par la Banque devront être utilisés pour tous les contrats soumis à la concurrence internationale ainsi que pour tous les autres contrats spécifiés dans les tableaux du plan de passation des marchés inclus dans STEP. Procédures nationales de passation des marchés : En accord avec le paragraphe 5.3 du Règlement de passation des marchés, au cas où la procédure de passation des marché est retenue (telle que spécifiée dans les tableaux du plan de passation des marchés inclus dans STEP), les procédures de passation de marchés du pays considéré peuvent être appliquées. Si l’Emprunteur utilise ses propres procédures d’appel d’offres national ouvert telles qu’énoncées dans le code des marchés publics [Insérer la référence exacte de la législation nationale], ces arrangements sont soumis aux dispositions du paragraphe 5.4 du Règlement de passation des marchés et aux conditions suivantes : Indiquer la liste des conditions qui s’applique de manière à assurer la cohérence avec le paragraphe 5.4 du Règlement de passation des marchés. Si aucune condition s’applique, supprimer la mention « et aux conditions suivantes ». Lorsque l’Emprunteur utilise d’autres procédures que l’appel d’offres national ouvert, ces procédures devront être en accord avec les dispositions du paragraphe 5.5 du Règlement de passation des marchés. Crédit-bail tel que spécifié au paragraphe 5.10 du Règlement de Passation des marchés : Le crédit-bail peut être utilisé pour les contrats indiqués dans le Plan de passation des marchés. Sinon indiquer « Sans objet » Achat de biens d’occasion tel que spécifié au paragraphe 5.11 du Règlement de Passation des Marchés est autorisé pour les contrats indiqués dans le Plan de passation des marchés. Sinon indiquer « Sans objet » Préférence nationale telle que spécifiée au paragraphe 5.51 du Règlement de Passation des Marchés (Fournitures et Travaux). Fournitures : [ne s’applique pas/s’applique pour les contrats indiqués dans les tableaux du Plan de passation des marchés] Travaux [ne s’applique pas/s’applique pour les contrats indiqués dans les tableaux du Plan de passation des marchés] L’Assistance directe à la mise en œuvre (sigle HEIS en anglais) tel que précisée aux paragraphes 3.10 et 3.11 du Règlement de Passation des marchés s’applique. [Inclure cette mention seulement si la Banque a formellement acceptée de fournir cette assistance directe à l’Emprunteur. Sinon, supprimer cette phrase.] Autres informations pertinentes sur la passation des marchés Indiquer toutes autres informations pertinentes telles que la participation des communautés au développement (CDD), un besoin urgent d’assistance ou se heurte à des problèmes de capacités, etc. PROCUREMENT Guinea : Guinea Commercial Agriculture Development Project PLAN General Information Country: Guinea 2019-10-02 Bank’s Approval Date of the Original Procurement Plan: 2023-06-02 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P164184 GPN Date: Project Name: Guinea Commercial Agriculture Development Project Loan / Credit No: IDA / V2570, IDA / D7130, IDA / 67710 PROJET DE DEVELOPPEMENT DE L'AGRICULTURE COMMERCIALE EN GUINEE Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GN-PDACG-247986-CW-RFQ National Procure / Aménagement de bureaux ment Document - Project Management and Co Request for Quota Single Stage - One E Pending Imp 2022-04-3 pour l'Unité Régionale Opéra IDA / D7130 Post Limited 1 Envelope proce 75,000.00 0.00 2021-09-06 2021-11-01 ordination tions nvelope lementation 0 tionnelle de Boké (y compris ss (Non Bank-SPD la pose des climatiseurs), ) GN-PDACG-247984-CW-RFQ National Procure / Aménagement de bureaux ment Document - Project Management and Co Request for Quota Single Stage - One E Pending Imp 2022-01-3 pour l'Unité Régionale Opéra IDA / 67710 Post Limited 1 Envelope proce 75,000.00 0.00 2021-10-06 2021-12-01 ordination tions nvelope lementation 0 tionnelle (URO) de Kindia (y c ss (Non Bank-SPD ompris la pose des climatise ) urs), National Procure GN-PDACG-247972-CW-RFQ ment Document - / Aménagement des bureaux Project Management and Co Request for Quota Single Stage - One E Pending Imp 2021-12-3 IDA / D7130 Post Limited 1 Envelope proce 90,000.00 0.00 2021-09-06 2021-11-01 de l'Unité de Coordination du ordination tions nvelope lementation 1 ss (Non Bank-SPD Projet (y compris la pose des ) climatiseurs) National Procure GN-PDACG-285133-CW-RFB ment Document - / Travaux de réhabilitation de Project Management and Co Single Stage - One E Under Imple 2023-03-2 IDA / D7130 Post Request for Bids Open - National 1 Envelope proce 3,000,000.00 0.00 2022-05-16 2022-05-21 2022-07-02 2022-08-01 2022-09-30 100 km de routes rurales à Ki ordination nvelope mentation 9 ss (Non Bank-SPD ndia (Mambia) ) GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GN-PDACG-121405-GO-RFQ / Acquisition de fournitures et Request for Quota Single Stage - One E Pending Impl IDA / V2570 Post Limited 50,000.00 0.00 2019-09-10 2019-11-05 2020-05-03 petits matériels de bureau po tions nvelope ementation ur la reprographie des docu ments GN-PDACG-247989-GO-RFQ / Acquisition de fournitures et Project Management and Co Request for Quota Single Stage - One E Pending Impl IDA / D7130 Post Limited 53,000.00 0.00 2021-09-06 2021-10-07 2021-11-06 consommables de bureau po ordination tions nvelope ementation ur l’UCP et ses Antennes de Boké et de Kindia GN-PDACG-248014-GO-RFQ / Acquisition de logiciel de ge stion financière et comptable Project Management and Co Under Imple IDA / D7130 Post Direct Selection Direct 50,000.00 0.00 2021-09-01 2022-03-17 2021-09-06 2022-03-22 2021-10-11 2021-10-17 et formation à l'utilisation (T ordination mentation OM2PRO avec les modules d e Passation des marchés et d e suivi - évaluation) GN-PDACG-248007-GO-RFQ Enabling environment for co Request for Quota Single Stage - One E Pending Impl / Acquisition de logiciel de ca IDA / D7130 Post Limited 10,000.00 0.00 2021-09-06 2021-10-07 2021-12-06 mmercial agriculture tions nvelope ementation rtographies GN-PDACG-248002-GO-RFQ / Acquisition des kits sanitair Project Management and Co Request for Quota Single Stage - One E Pending Impl IDA / D7130 Post Limited 10,000.00 0.00 2021-10-06 2021-12-01 2021-12-31 es contre les risques de cont ordination tions nvelope ementation amination à la COVID-19 GN-PDACG-248019-GO-RFQ / Acquisition de trois (3) géné Project Management and Co Request for Quota Single Stage - One E Pending Impl rateurs d'électricité ( 1 de 20 IDA / D7130 Post Limited 80,000.00 0.00 2021-10-06 2021-11-06 2021-11-12 ordination tions nvelope ementation KVA pour l'UCP et 2 de 10 KV A pour les URO de Kindia et d e Boké) GN-PDACG-248015-GO-RFB / Acquisition de matériels roul ants (12 véhicules 4x4 et 5 Project Management and Co Open - Internationa Single Stage - One E Under Imple motos tout terrain ) pour l'Un IDA / D7130 Post Request for Bids 565,000.00 0.00 2022-03-16 2022-11-09 2022-03-21 2022-11-09 2022-05-02 2022-06-01 2022-07-15 2022-10-13 ordination l nvelope mentation ité de Coordination du Projet (UCP) et les Unités Régionale s Opérationnelles de Kindia e t Boké GN-PDACG-248017-GO-RFQ / Acquisition de matériels inf ormatiques et matériel de bu Project Management and Co Request for Quota Single Stage - One E Pending Impl IDA / D7130 Post Limited 70,000.00 0.00 2022-03-21 2022-04-21 2022-05-21 reau pour l’Unité de Coordina ordination tions nvelope ementation tion du Projet et les Unités R égionales Opérationnelles de Boké et de Kindia GN-PDACG-248018-GO-RFQ / Mobiliers de bureaux pour l’ Project Management and Co Request for Quota Single Stage - One E Pending Impl Unité de Coordination du Proj IDA / D7130 Post Limited 80,000.00 0.00 2022-03-21 2022-04-16 2022-04-26 ordination tions nvelope ementation et (UCP) et les et les Unités R égionales Opérationnelles (IR O) de Kindia et Boké GN-PDACG-296307-GO-RFB / Acquisition d'équipements du laboratoire central de l’ONCQ Enabling environment for co Open - Internationa Single Stage - One E Pending Impl IDA / D7130 Post Request for Bids 300,000.00 0.00 2022-06-06 2022-06-11 2022-07-23 2022-08-22 2022-10-05 2023-01-03 pour le contrôle de conformit mmercial agriculture l nvelope ementation é des aliments (équipements de laboratoire et matériel inf ormatique) GN-PDACG-296309-GO-RFB / Acquisition de kits d’inspecti Enabling environment for co Open - Internationa Single Stage - One E Pending Impl IDA / D7130 Post Request for Bids 140,000.00 0.00 2022-06-06 2022-06-11 2022-07-23 2022-08-22 2022-10-05 2023-01-03 on et de contrôles des produi mmercial agriculture l nvelope ementation ts prioritaires ciblés pour l'O NCQ Page 1 GN-PDACG-296310-GO-RFQ / Acquisition de réactifs et de Enabling environment for co Request for Quota Single Stage - One E Pending Impl IDA / D7130 Post Limited 70,000.00 0.00 2022-06-11 2022-07-12 2022-08-11 milieux de cultures pour les a mmercial agriculture tions nvelope ementation nalyses pour l'ONCQ GN-PDACG-296311-GO-RFQ / Acquisition d’équipements i nformatiques pour les parten aires du projet (ordinateurs fi Enabling environment for co Request for Quota Single Stage - One E Pending Impl xes et portatifs, vidéo-projete IDA / D7130 Post Limited 50,000.00 0.00 2022-06-11 2022-08-06 2023-02-02 mmercial agriculture tions nvelope ementation urs, appareils photo-numériq ue, imprimantes multifonctio ns) pour l’APIP, l'AGUIPEX, la DNGR, la DNAPA, le BSD du Ministère du Commerce GN-PDACG-296312-GO-RFB / Acquisition de 6 véhicules et 6 motos pour les partenaires du projet (1 véhicules pickup Enabling environment for co Single Stage - One E Pending Impl et 2 motos pour l'APIP, 1 véhi IDA / D7130 Post Request for Bids Open - National 250,000.00 0.00 2022-06-06 2022-06-11 2022-07-23 2022-08-22 2022-09-26 2023-03-25 mmercial agriculture nvelope ementation cule pickup et 2 motos pour l 'AGUIPEX, 1 véhicule pickup et 2 motos pour la DNGR, 1 v éhicule pickup pour la DNAPA , 1 véhicule pour le BS GN-PDACG-360847-GO-RFB / Fourniture de 50 lots d'équip ements de gestion post-récol Supporting private investme Single Stage - One E Pending Impl IDA / D7130 Post Request for Bids Open - National 500,000.00 0.00 2023-05-22 2023-05-27 2023-07-08 2023-08-07 2023-09-11 2024-03-09 te de fonio (batteuses, décor nts nvelope ementation tiqueuses, épierreuses, etc.) pour le développement de fili ère en Guinée GN-PDACG-360826-GO-RFQ / Fourniture de 500,000 pous sins d'un jour dans le cadre d Supporting private investme Single Stage - One E Pending Impl IDA / D7130 Post Request for Bids Open - National 1,000,000.00 0.00 2023-06-15 2023-06-20 2023-08-01 2023-08-31 2023-10-05 2024-04-02 e l'appui aux acteurs de la fili nts nvelope ementation ère volaille pour la relance p ost-grippe aviaire, en 5 lots d e 100,000 poussins chaque. GN-PDACG-360830-GO-RFB / Achats de 500 000 poussins et Fourniture 6,7 tonnes d'ali Supporting private investme Open - Internationa Single Stage - One E Pending Impl IDA / D7130 Prior Request for Bids 5,000,000.00 0.00 2023-05-22 2023-05-27 2023-07-08 2023-08-07 2023-09-11 2024-03-09 ment volaille aux acteurs de l nts l nvelope ementation a filière avicole dans le cadre de la relance post-grippe avi aire en Guinée. GN-PDACG-360820-GO-DIR / Acquisition de Pack complet maïs (semences, engrais, pro Supporting private investme Open - Internationa Single Stage - One E Pending Impl IDA / D7130 Prior Request for Bids 1,500,000.00 0.00 2023-05-29 2023-06-03 2023-07-15 2023-08-14 2023-09-18 2024-03-16 duits phyto) dans le cadre du nts l nvelope ementation Sous-projet Intégré de produ ction intensive de maïs (PIM) NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GN-PDACG-247964-CS-INDV Project Management and Co Request for Quota Single Stage - One E Pending Impl / Création et hébergement d IDA / D7130 Post Limited 39,048.00 0.00 2022-04-10 2022-05-30 2022-07-14 ordination tions nvelope ementation u site Web du PDACG CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GN-PDACG-121406-CS-CQS / Recrutement d'un bureau d'é Consultant Qualifi IDA / V2570 Post Limited 240,000.00 0.00 Canceled 2019-07-07 2019-07-21 2019-08-20 2019-09-24 2020-03-22 tudes pour les mesures de sa cation Selection uvegarde environnementales et sociales GN-PDACG-121407-CS-CQS / Recrutement d'un bureau d'é tudes pour la mise en place d Consultant Qualifi Pending Impleme IDA / V2570 Post Limited 100,000.00 0.00 2019-08-05 2019-08-19 2019-09-18 2019-10-23 2020-04-20 'un abattoir moderne à Cona cation Selection ntation kry et les conditions de son b on fonctionnement et pérenn isation de son exploitation GN-PDACG-121409-CS-CQS / Recrutement d'une firme pou Consultant Qualifi Pending Impleme r les études intégrées des inf IDA / V2570 Post Limited 100,000.00 0.00 2019-07-10 2019-07-24 2019-08-23 2019-09-27 2020-03-25 cation Selection ntation rastructures logistiques des c haines de valeur agricoles GN-PDACG-121412-CS-QCBS / Recrutement d'une firme ag Quality And Cost- Open - Internationa IDA / V2570 Prior 300,000.00 0.00 Signed 2019-07-22 2022-04-15 2019-08-12 2022-04-15 2019-10-10 2022-05-05 2019-11-07 2022-05-05 2019-12-07 2022-05-05 2020-01-11 2022-05-06 2020-02-24 2021-02-23 ro business pour l'appui à la Based Selection l préparation du projet GN-PDACG-121413-CS-QCBS / Recrutement d'une firme po Quality And Cost- Open - Internationa Pending Impleme IDA / V2570 Post 300,000.00 0.00 2019-08-18 2019-09-08 2019-11-06 2019-12-04 2020-01-03 2020-02-07 2020-03-22 2021-03-22 ur la préparation des docume Based Selection l ntation nts opérationnels du projet GN-PDACG-205345-CS-CQS / Recrutement d'un cabinet po Project Management and Co Consultant Qualifi Pending Impleme ur le recrutement du personn IDA / V2570 Post Limited 120,000.00 0.00 2020-11-18 2020-12-02 2021-01-01 2021-02-05 2021-08-04 ordination cation Selection ntation el clé de l'UNC du projet PDA CG en deux (2) phases GN-PDACG-121411-CS-CQS / Recrutement d'un cabinet po Project Management and Co Consultant Qualifi Pending Impleme ur l'élaboration du manuel de IDA / V2570 Post Limited 150,000.00 0.00 2019-09-10 2019-09-24 2019-10-24 2019-11-28 2020-05-26 ordination cation Selection ntation procédures fiduciaires, opéra tions, suivi évaluation GN-PDACG-247949-CS-LCS / Project Management and Co Least Cost Selecti Open - Internationa Under Implement Recrutement de l'Auditeur ex IDA / D7130 Post 90,000.00 0.00 2021-09-01 2022-03-20 2021-09-22 2022-03-22 2021-11-05 2021-12-03 2021-12-18 2022-01-22 2022-02-26 2022-08-25 ordination on l ation ternes des comptes du PDAC G Page 2 GN-PDACG-285009-CS-QCBS / Études techniques pour les Enabling environment for co Quality And Cost- Open - Internationa Under Implement IDA / D7130 Post 400,000.00 0.00 2022-03-16 2022-11-22 2022-04-06 2022-05-20 2022-06-17 2022-07-17 2022-08-21 2022-11-19 2023-05-18 travaux de réhabilitation des mmercial agriculture Based Selection l ation 200 km de routes rurales de Kindia GN-PDACG-285108-CS-CQS / Etudes EIES de construction Enabling environment for co Consultant Qualifi Open - Internationa Pending Impleme IDA / D7130 Post 100,000.00 0.00 2022-03-16 2022-04-06 2022-05-20 2022-06-19 2022-09-01 2023-02-28 des abattoirs de volailles à B mmercial agriculture cation Selection l ntation oké et à Kagbelen GN-PDACG-285112-CS-CQS / Etudes techniques (APS/APD/ DAO) pour l'achèvement des Enabling environment for co Consultant Qualifi Open - Internationa Pending Impleme IDA / D7130 Post 251,425.00 0.00 2022-04-04 2022-04-25 2022-06-08 2022-07-08 2022-09-06 2023-03-05 travaux de construction de l' mmercial agriculture cation Selection l ntation abattoir de Conakry (Kagbele n) et les installations complé mentaires GN-PDACG-285126-CS-QCBS / Etudes d'impact environne mental et social des travaux de construction à Conakry (i) Enabling environment for co Quality And Cost- Open - Internationa Pending Impleme de marchés de gros compren IDA / D7130 Post 300,000.00 0.00 2022-04-04 2022-04-25 2022-06-08 2022-07-06 2022-08-05 2022-09-09 2022-11-08 2023-01-07 mmercial agriculture Based Selection l ntation ant les infrastructures et les zones logistiques pertinentes de conditionnement, transbo rdement, stockage, et pour l a création des centres comm er GN-PDACG-285128-CS-CQS / Etudes techniques des trava ux de mise à niveau des loca ux du laboratoire de protecti Enabling environment for co Consultant Qualifi Open - Internationa Pending Impleme IDA / D7130 Post 200,000.00 0.00 2022-04-18 2022-05-09 2022-07-08 2022-08-07 2022-10-06 2023-04-04 on des végétaux de Kindia, d mmercial agriculture cation Selection l ntation u Laboratoire Central Vétérin aire de Diagnostic de Conakr y et du laboratoire CERE pour l'analyse contaminants chimi ques GN-PDACG-285129-CS-CQS / Etudes environnementales d es travaux de mise à niveau des locaux du laboratoire de Enabling environment for co Consultant Qualifi Open - Internationa Pending Impleme protection des végétaux de K IDA / D7130 Post 120,000.00 0.00 2022-04-18 2022-05-09 2022-06-22 2022-07-22 2022-09-20 2023-03-19 mmercial agriculture cation Selection l ntation india, du Laboratoire Central Vétérinaire de Diagnostic de Conakry et du laboratoire CE RE pour l'analyse contamina nts chimiques GN-PDACG-293012- CS-QCB S / Etudes techniques (APS/A PD/DAO) des travaux de cons truction à Conakry (i) de mar Enabling environment for co Quality And Cost- Open - Internationa Pending Impleme chés de gros comprenant les IDA / D7130 Prior 900,000.00 0.00 2022-05-15 2022-06-05 2022-07-19 2022-08-16 2022-09-15 2022-10-20 2022-11-24 2023-11-24 mmercial agriculture Based Selection l ntation infrastructures et les zones lo gistiques pertinentes de con ditionnement, transbordeme nt, stockage, et pour la créati on des centres commerciaux GN-PDACG-247955-CS-QCBS / Études techniques pour les Enabling environment for co Quality And Cost- Open - Internationa Under Implement IDA / D7130 Prior 555,000.00 0.00 2022-05-15 2022-11-22 2022-06-05 2022-11-24 2022-07-19 2022-08-16 2022-09-15 2022-10-20 2023-01-18 2023-07-17 travaux de réhabilitation des mmercial agriculture Based Selection l ation 300 km de routes rurales de Boké GN-PDACG-293013-CS-CQS / Recrutement d’un cabinet po ur l’étude d’impact environn emental et social (EIES) relati Enabling environment for co Consultant Qualifi Open - Internationa Under Implement IDA / D7130 Post 80,000.00 0.00 2022-04-29 2022-04-29 2022-05-20 2022-05-16 2022-07-03 2022-08-02 2022-10-15 2023-04-13 f aux travaux de réhabilitatio mmercial agriculture cation Selection l ation n des 100 km de routes rural es et de ponts moyens dans l a commune rurale de Mambi a – Préfecture de de Kindia GN-PDACG-293014-CS-CQS / Recrutement d’un cabinet po ur le PAR relatif aux travaux Enabling environment for co Consultant Qualifi Open - Internationa Under Implement de réhabilitation des 100 km IDA / D7130 Post 80,000.00 0.00 2022-04-29 2022-05-28 2022-05-20 2022-07-03 2022-08-02 2022-10-15 2023-04-13 mmercial agriculture cation Selection l ation de routes rurales et de ponts moyens dans la commune ru rale de Mambia – Préfecture de de Kindia GN-PDACG-296276-CS-CQS / PAR pour les travaux de réha Enabling environment for co Consultant Qualifi Open - Internationa Under Implement IDA / D7130 Post 80,000.00 0.00 2022-05-23 2022-11-22 2022-06-13 2022-07-27 2022-08-26 2022-11-08 2023-05-07 bilitation des 300 km de rout mmercial agriculture cation Selection l ation es rurales à Boké GN-PDACG-296277-CS-CQS / PAR pour les travaux de réha Enabling environment for co Consultant Qualifi Open - Internationa Under Implement IDA / D7130 Post 75,000.00 0.00 2022-05-23 2022-11-22 2022-06-13 2022-07-27 2022-08-26 2022-10-25 2023-04-23 bilitation des 200 km de rout mmercial agriculture cation Selection l ation es rurales à Kindia GN-PDACG-296278-CS-CQS / EIES pour la construction des Enabling environment for co Consultant Qualifi Open - Internationa Pending Impleme IDA / D7130 Post 50,000.00 0.00 2022-05-23 2022-06-13 2022-07-27 2022-08-26 2022-10-25 2023-04-23 abattoirs de volailles à Boké mmercial agriculture cation Selection l ntation et à Kagbelen GN-PDACG-296280-CS-CQS / PSR (PAR simplifié) pour la co Enabling environment for co Consultant Qualifi Open - Internationa Pending Impleme IDA / D7130 Post 50,000.00 0.00 2022-05-23 2022-06-13 2022-07-27 2022-08-26 2022-10-25 2023-04-23 nstruction des abattoirs de v mmercial agriculture cation Selection l ntation olailles à Boké et à Kagbelen GN-PDACG-296283-CS-CQS / Etudes techniques (APD/DAO Enabling environment for co Consultant Qualifi Open - Internationa Pending Impleme IDA / D7130 Post 150,000.00 0.00 2022-05-30 2022-06-20 2022-08-03 2022-09-02 2022-10-07 2023-04-05 ) pour la construction des ab mmercial agriculture cation Selection l ntation attoirs de volailles à Boké et à Kagbelen GN-PDACG-296293-CS-CQS / Études d'identification des be Enabling environment for co Consultant Qualifi Open - Internationa Pending Impleme IDA / D7130 Post 100,000.00 0.00 2022-05-30 2022-06-20 2022-08-03 2022-09-02 2022-10-07 2023-04-05 soins en installations logistiq mmercial agriculture cation Selection l ntation ues-agro-commerciales à Bo ké et Kindia GN-PDACG-296294-CS-CQS / Études techniques pour la co Enabling environment for co Consultant Qualifi Open - Internationa Pending Impleme nstruction et l'équipement de IDA / D7130 Post 75,000.00 0.00 2022-05-30 2022-06-20 2022-08-03 2022-09-02 2022-10-07 2023-04-05 mmercial agriculture cation Selection l ntation mini-laboratoires de contrôle s sensoriels à Boké, Kamsar et Kindia GN-PDACG-296295-CS-CQS / Enabling environment for co Consultant Qualifi Open - Internationa Pending Impleme Cartographie des chaînes de IDA / D7130 Post 100,000.00 0.00 2022-05-30 2022-06-20 2022-08-03 2022-09-02 2022-10-07 2023-04-05 mmercial agriculture cation Selection l ntation valeur prioritaires Page 3 GN-PDACG-296296-CS-CQS / Diagnostic institutionnel parti Enabling environment for co Consultant Qualifi Open - Internationa Pending Impleme IDA / D7130 Post 200,000.00 0.00 2022-05-30 2022-06-20 2022-08-03 2022-09-02 2022-10-07 2023-04-05 cipatif des organisations prof mmercial agriculture cation Selection l ntation essionnelles des filières cible s GN-PDACG-296297-CS-CQS / Appui à la mise en œuvre de Enabling environment for co Consultant Qualifi Open - Internationa Pending Impleme IDA / D7130 Post 100,000.00 0.00 2022-05-30 2022-06-20 2022-08-03 2022-09-02 2022-10-07 2023-04-05 s plans de renforcement des mmercial agriculture cation Selection l ntation organisations professionnelle s des filières cibles GN-PDACG-296298-CS-CQS / Enabling environment for co Consultant Qualifi Open - Internationa Pending Impleme Étude de la compétitivité-pay IDA / D7130 Post 200,000.00 0.00 2022-05-30 2022-06-20 2022-08-03 2022-09-02 2022-10-07 2023-04-05 mmercial agriculture cation Selection l ntation s des produits cibles du proje t GN-PDACG-296299-CS-QCBS / Élaboration des plans de dé veloppement détaillés pour c Enabling environment for co Quality And Cost- Open - Internationa Pending Impleme IDA / V2570 Post 300,000.00 0.00 2022-05-30 2022-06-20 2022-08-03 2022-08-31 2022-09-30 2022-11-04 2022-12-09 2023-12-09 hacune des chaînes de valeu mmercial agriculture Based Selection l ntation r prioritaires agricoles (Fruits et légume, anacardes et Foni o) et des produits carnés GN-PDACG-285109-CS-CQS / Études EIES des travaux de r Enabling environment for co Consultant Qualifi Open - Internationa Under Implement IDA / D7130 Post 120,000.00 0.00 2022-05-30 2022-11-25 2022-06-20 2022-08-03 2022-09-02 2022-11-15 2023-05-14 éhabilitation des 300 km de r mmercial agriculture cation Selection l ation outes rurales à Boké GN-PDACG-285139-CS-CQS / Études EIES des travaux de r Enabling environment for co Consultant Qualifi Open - Internationa Under Implement IDA / D7130 Post 100,000.00 0.00 2022-05-30 2022-11-25 2022-06-20 2022-08-03 2022-09-02 2022-11-01 2023-04-30 éhabilitation des 200 km de r mmercial agriculture cation Selection l ation outes rurales à Kindia GN-PDACG-364847-CS-CQS / Elaboration Notices d'Impact Supporting private investme Consultant Qualifi Open - Internationa Pending Impleme IDA / D7130 Post 150,000.00 0.00 2023-06-15 2023-07-06 2023-07-28 2023-08-07 2023-09-20 2024-09-19 Environnemental et Social de nts cation Selection l ntation s Sous-projets Matching Gran t du PDACG GN-PDACG-368193-CS-CQS / Recrutement d'un consultant Supporting private investme Consultant Qualifi Pending Impleme pour l'élaboration de NIES po IDA / D7130 Post Limited 100,000.00 0.00 2023-07-03 2023-08-02 2023-08-09 2023-08-26 2023-10-25 nts cation Selection ntation ur neuf (9) sous-projets sélec tionnés dans le cadre du Mat ching Grant. GN-PDACG-285110-CS-QCBS / Mission de contrôle et de su Enabling environment for co Quality And Cost- Open - Internationa pervision des travaux de réh IDA / D7130 Post 300,000.00 0.00 Canceled 2022-04-04 2022-11-22 2022-04-25 2022-06-08 2022-07-06 2022-08-05 2022-09-09 2022-11-08 2023-05-07 mmercial agriculture Based Selection l abilitation de 100 km de rout es rurales à Kindia (Mambia) INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GN-PDACG-121414-CS-INDV / Recrutement d'un consultan Individual Consult Pending Impleme IDA / V2570 Post Limited 100,000.00 0.00 2019-08-27 2019-09-01 2019-09-22 2019-10-27 2020-04-24 t individuel pour la réalisatio ant Selection ntation n des études détaillées sur le genre GN-PDACG-121415-CS-INDV Individual Consult Pending Impleme / Recrutement d'un consultan IDA / V2570 Post Limited 30,000.00 0.00 2019-07-08 2019-07-13 2019-08-03 2019-09-07 2020-03-05 ant Selection ntation t individuel pour l'élaboration du PPSD GN-PDACG-121417-CS-INDV / Recrutement d'un CI pour la Individual Consult Pending Impleme IDA / V2570 Post Limited 50,000.00 0.00 2019-07-10 2019-07-15 2019-08-05 2019-09-09 2020-03-07 collecte des données de référ ant Selection ntation ences du projet GN-PDACG-121418-CS-INDV / Recrutement d'un consultan t individuel pour la réalisatio Individual Consult Pending Impleme IDA / V2570 Post Limited 80,000.00 0.00 2019-07-22 2019-07-27 2019-08-17 2019-09-21 2020-03-19 n des études diagnostic sur l' ant Selection ntation état d'occupation et les droit s applicables aux terres agric oles de l'Etat GN-PDACG-150259-CS-CDS / Improving market access in Pending Impleme Recrutement d'un consultant IDA / V2570 Post Direct Selection Direct 20,000.00 0.00 2019-12-15 2019-12-21 2020-01-05 2020-01-20 targeted areas ntation individuel pour l'élaboration du PPSD GN-PDACG-150264-CS-INDV Enabling environment for co Individual Consult Pending Impleme / Recrutement d'un consultan IDA / V2570 Post Limited 35,000.00 0.00 2019-12-17 2019-12-22 2019-12-27 2020-01-05 2020-02-04 mmercial agriculture ant Selection ntation t individuel pour l'élaboration du COSTAB GN-PDACG-150265-CS-INDV / Recrutement d'un consultan Enabling environment for co Individual Consult IDA / V2570 Post Limited 35,000.00 0.00 Canceled 2020-01-06 2020-01-11 2020-01-16 2020-01-25 2020-02-24 t individuel pour l'élaboration mmercial agriculture ant Selection du screening environnement al et social GN-PDACG-150268-CS-INDV / Recrutement d'un consultan Enabling environment for co Individual Consult Pending Impleme t individuel pour la réalisatio IDA / V2570 Post Limited 45,000.00 0.00 2019-12-13 2019-12-18 2019-12-23 2020-01-01 2020-01-31 mmercial agriculture ant Selection ntation n de l'audit environnemental de l'abattoir de conakry GN-PDACG-150271-CS-INDV / Recrutement d'un consultan Enabling environment for co Individual Consult Pending Impleme IDA / V2570 Post Limited 70,000.00 0.00 2019-12-16 2019-12-21 2019-12-26 2020-01-04 2020-02-03 t individuel pour l'élaboration mmercial agriculture ant Selection ntation du système de suivi évaluati on du PDACG GN-PDACG-150276-CS-INDV / Recrutement d'un consultan Enabling environment for co Individual Consult Pending Impleme t individuel pour la mise en p IDA / V2570 Post Limited 40,000.00 0.00 2020-01-22 2020-02-01 2020-02-06 2020-02-26 2020-03-27 mmercial agriculture ant Selection ntation lace d'un système de gestion des plaintes et réclamations GN-PDACG-150261-CS-CDS / Improving market access in Individual Consult Pending Impleme Recrutement d'un consultant IDA / V2570 Post Direct 45,000.00 0.00 2019-12-24 2020-01-03 2020-01-05 2020-01-20 2020-02-07 targeted areas ant Selection ntation individuel sur l'étude détaillé e sur le genre Page 4 GN-PDACG-151429-CS-INDV / Recrutement d'un Consulta nt individuel pour l'étude d'i Enabling environment for co Individual Consult Pending Impleme IDA / V2570 Post Limited 100,000.00 0.00 2020-11-18 2020-11-23 2020-11-24 2020-12-02 2021-01-01 mpact et de faisabilité techni mmercial agriculture ant Selection ntation que, d'évaluation sociale et e nvironnementale de l'abattoi r GN-PDACG-205346-CS-INDV / Recrutement d'un Consulta Supporting private investme Individual Consult nt individuel pour l'élabiratio IDA / V2570 Post Limited 50,000.00 0.00 Canceled 2020-11-30 2020-12-05 2020-12-06 2020-12-14 2021-01-13 nts ant Selection n du manuel de financement à couts partagés (Matching G rant) GN-PDACG-247684-CS-INDV Project Management and Co Individual Consult / Recrutement de l'Auditeur i IDA / D7130 Post Open 70,000.00 0.00 Canceled 2021-09-01 2021-10-05 2021-10-10 2021-10-20 2022-10-15 ordination ant Selection nterne du projet GN-PDACG-121416-CS-INDV / Recrutement du personnel Individual Consult complémentaire du projet (R IDA / V2570 Post Limited 240,000.00 0.00 Canceled 2019-09-25 2019-09-30 2019-10-21 2019-11-25 2020-05-23 ant Selection AF, SPM, SSE, comptable, sau vegarde (2) et auditeur inter ne GN-PDACG-247941-CS-INDV / Consultant pour la réalisatio Enabling environment for co Individual Consult Pending Impleme IDA / D7130 Post Open 50,000.00 0.00 2021-10-01 2021-11-19 2021-12-10 2022-01-30 2022-07-29 n de l'EIES pour la réhabilitati mmercial agriculture ant Selection ntation on des 100 km de routes rur ales GN-PDACG-247946-CS-INDV / Recrutement Consultant po Project Management and Co Individual Consult Under Implement ur l'élaboration du Plan de M IDA / D7130 Post Open 50,000.00 0.00 2021-09-01 2022-05-18 2021-10-20 2021-11-10 2021-12-15 2022-06-13 ordination ant Selection ation obilisation et d'Engagement des Parties Prenantes (PMEP P) GN-PDACG-247952-CS-INDV / Recrutement Consultant po Enabling environment for co Individual Consult Under Implement IDA / D7130 Post Open 50,000.00 0.00 2021-09-01 2022-05-18 2021-10-20 2021-11-10 2021-12-15 2022-02-13 ur l'Évaluation du genre et d mmercial agriculture ant Selection ation e l'inclusion sociale dans la z one du projet GN-PDACG-247943-CS-INDV / Consultant pour la réalisatio Enabling environment for co Individual Consult Under Implement IDA / D7130 Post Open 70,000.00 0.00 2021-10-01 2022-06-09 2021-11-19 2021-12-10 2022-01-30 2022-07-29 n du PAR pour la réhabilitatio mmercial agriculture ant Selection ation n des 100 km de routes rural es GN-PDACG-285119-CS-INDV / Etudes environnementales pour l'achèvement des trava Enabling environment for co Individual Consult Pending Impleme IDA / D7130 Post Open 19,725.00 0.00 2022-04-04 2022-05-23 2022-06-13 2022-08-03 2023-01-30 ux de construction de l'abatt mmercial agriculture ant Selection ntation oir de Conakry (Kagbelen) et la construction d'installations complémentaires GN-PDACG-285130-CS-INDV / Elaboration du manuel sur l Enabling environment for co Individual Consult Under Implement IDA / D7130 Post Open 50,000.00 0.00 2022-03-16 2022-05-18 2022-05-04 2022-05-25 2022-07-24 2023-01-20 e mécanisme de gestion des mmercial agriculture ant Selection ation plaintes (MGP) du PDACG GN-PDACG-296287-CS-INDV / Etudes EIES de construction Enabling environment for co Individual Consult Pending Impleme IDA / D7130 Post Open 50,000.00 0.00 2022-05-30 2022-07-18 2022-08-08 2022-09-12 2023-03-11 des abattoirs de bovins et pe mmercial agriculture ant Selection ntation tits ruminants de Boké et de Kindia GN-PDACG-296286-CS-INDV / Etudes PSR de construction Enabling environment for co Individual Consult Pending Impleme IDA / D7130 Post Open 30,000.00 0.00 2022-05-30 2022-07-18 2022-08-08 2022-09-12 2023-03-11 des abattoirs de bovins et pe mmercial agriculture ant Selection ntation tits ruminants de Boké et de Kindia GN-PDACG-296288-CS-INDV / Etudes NIES des travaux de mise à niveau des locaux du l aboratoire de protection des Enabling environment for co Individual Consult Pending Impleme IDA / D7130 Post Open 45,000.00 0.00 2022-05-30 2022-07-18 2022-08-08 2022-09-12 2023-03-11 végétaux de Kindia, du Labor mmercial agriculture ant Selection ntation atoire Central Vétérinaire de Diagnostic de Conakry et du l aboratoire CERE pour l'analy se contaminants chimiques GN-PDACG-296290-CS-INDV / Études PSR des travaux de mise à niveau des locaux du l aboratoire de protection des Enabling environment for co Individual Consult Pending Impleme IDA / D7130 Post Open 30,000.00 0.00 2022-05-30 2022-07-18 2022-08-08 2022-09-12 2023-03-11 végétaux de Kindia, du Labor mmercial agriculture ant Selection ntation atoire Central Vétérinaire de Diagnostic de Conakry et du l aboratoire CERE pour l'analy se contaminants chimiques GN-PDACG-296291-CS-INDV / Élaboration des NIES pour l Enabling environment for co Individual Consult Pending Impleme a construction et l'équipeme IDA / D7130 Post Open 45,000.00 0.00 2022-05-30 2022-07-18 2022-08-08 2022-09-12 2023-03-11 mmercial agriculture ant Selection ntation nt de mini-laboratoires de co ntrôles sensoriels à Boké, Ka msar et Kindia GN-PDACG-296292-CS-INDV / Elaboration PSR pour la con Enabling environment for co Individual Consult Pending Impleme struction et l'équipement de IDA / D7130 Post Open 30,000.00 0.00 2022-05-30 2022-07-18 2022-08-08 2022-09-12 2023-03-11 mmercial agriculture ant Selection ntation mini-laboratoires de contrôle s sensoriels à Boké, Kamsar et Kindia GN-PDACG-296300-CS-INDV Enabling environment for co Individual Consult Pending Impleme / Élaboration de la stratégie e IDA / D7130 Post Open 37,000.00 0.00 2022-05-30 2022-07-18 2022-08-08 2022-09-12 2023-03-11 mmercial agriculture ant Selection ntation t du plan de communication du PDACG GN-PDACG-296301-CS-INDV / Formation des partenaires ( APIP, AGUIPEX, ONCQ, BSD/M Enabling environment for co Individual Consult Pending Impleme CIPME, BSD/MAGEL, CONASE IDA / D7130 Post Open 50,000.00 0.00 2022-05-30 2022-07-18 2022-08-08 2022-09-12 2023-03-11 mmercial agriculture ant Selection ntation G, BSD/Ministère Mines et Gé ologie ; etc) sur l'acte unifor me OHADA relatif aux droits des sociétés coopératives et des GIE GN-PDACG-296302-CS-INDV / Mise en place d'une base d Enabling environment for co Individual Consult Pending Impleme IDA / D7130 Post Open 50,000.00 0.00 2022-05-30 2022-07-18 2022-08-08 2022-09-12 2023-03-11 e données commerciales sur mmercial agriculture ant Selection ntation les filières cibles du projet. Page 5 GN-PDACG-296304-CS-INDV / Analyse situationnelle et év Enabling environment for co Individual Consult Pending Impleme aluation des besoins de renfo IDA / D7130 Post Open 20,000.00 0.00 2022-05-30 2022-07-18 2022-08-08 2022-09-12 2023-03-11 mmercial agriculture ant Selection ntation rcement des capacités du Co mité National de gestion des pestes et pesticides GN-PDACG-296305-CS-INDV / Analyse situationnelle et év Enabling environment for co Individual Consult Pending Impleme IDA / D7130 Post Open 15,000.00 0.00 2022-05-30 2022-07-18 2022-08-08 2022-09-12 2023-03-11 aluation des besoins de renfo mmercial agriculture ant Selection ntation rcement des capacités de l'O NCQ GN-PDACG-364850-CS-CDS / Project Management and Co Pending Impleme Assistance temporaire au pro IDA / D7130 Post Direct Selection Direct - National 2,000.00 0.00 2023-06-26 2023-06-28 2023-07-02 2023-08-01 ordination ntation jet en passation de marchés GN-PDACG-360848-CS-INDV / Recrutement d'un consultan Supporting private investme Individual Consult t pour l'élaboration de NIES p IDA / D7130 Post Open - National 100,000.00 0.00 Canceled 2023-05-29 2023-07-17 2023-08-07 2023-09-11 2024-03-09 nts ant Selection our neuf (9) sous-projets séle ctionnés dans le cadre du Ma tching Grant GN-PDACG-368212-CS-INDV / Recrutement d'un Consulta nt individuel pour la mise en Project Management and Co Individual Consult Pending Impleme IDA / D7130 Post Limited 75,000.00 0.00 2023-06-27 2023-07-04 2023-07-07 2023-07-15 2023-12-02 oeuvre des activités prioritair ordination ant Selection ntation es de formation et la sensibil isation sur la gestion des pes tes et pesticides. GN-PDACG-363210-CS-INDV / CONSULTANT POUR LA MIS E EN ŒUVRE DES ACTIVITES PRIORITAIRES DE FORMATIO Project Management and Co Individual Consult IDA / D7130 Post Open - National 75,000.00 0.00 Canceled 2023-06-15 2023-08-11 2023-08-14 2023-09-08 2024-01-26 N ET DE SENSIBILISATION DE ordination ant Selection S ACTEURS LOCAUX, INSCRIT ES DANS LES PLANS DE GEST ION DES PESTES ET PESTICID ES (PGPP) DU PDACG Page 6 18-MONTH PROCUREMENT PLAN Project information: Phase I of Improved Child Survival Program for Human Capital MPA- P167156-- Immunization Plus and Malaria Progress by Accelerating Coverage and Transforming Services (IMPACT) Project Project Implementation Agencies: Federal Ministry of Health (NMEP and NPHCDA) Date of the Procurement Plan: January 1, 2020 Period covered by this Procurement Plan: January 2020 to June 2021 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016), revised on November 1, 2017 and on August 1, 2018 (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the Nigeria Public Procurement Act 2007, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. Not Applicable Procurement of Second-Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables. Not Applicable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: [15% is applicable for those contracts identified in the Procurement Plan tables]; Works: [ 7.5% is applicable for those contracts identified in the Procurement Plan tables] I. Threshold for Prior Review – Goods, Works, Non-Consulting Services and Consulting Services Prior-review Thresholds Thresholds for Procurement Methods High Substanti Moderate Low Risk Goods, IT & Non-Consulting Shortlist of National Procurement Type Risk al Risk Risk Works ($'000) ($'000) ($'000) ($'000) Services Consultants Request Request Engineering Open for for Open Open Open Consultin & Quotatio Quotatio 10,0 15,0 20,0 Internatio National internatio National g Constructio Works n or n or 5,000 00 00 00 nal or ICB or NCB National nal or ICB or NCB National Services n ($'000) ($'000) ($'000) ($'000) ($'000) Supervision Shopping Shopping ($'000) ($'000) ($'000) Goods, IT & Non- 2,0 4,0 6,0 Consulting Services 1,500 00 00 00 ≧ < ≦ ≧ < ≦ < ≦ Consultants 1,0 2,0 4,0 20,0 20,0 5,0 5,0 1 3 5 200 (Firms) 500 00 00 00 00 00 00 00 00 00 00 Post Review: All contracts not subject to prior review shall be subject to post review. Summary of the procurement packages for Goods, Works and Non-Consulting Services (Planned for the first 18 months after project effectiveness): Selec Evaluation Market tion Options Approa Review Meth (Most Expected ch Prequal- Domestic Expected by od Advantageo date of Sr. Contract Estimated (Open- ification Preferenc date of Bank (RFP, us Bid, bid/ No Description Cost (US$) Nation (Yes/ e Contract (Prior/ RFB, BAFO, proposal al/ No) (Yes/No) Signature Post) RFQ, Rated opening Limited DS Criteria etc.) etc.) etc.) Nigeria Malaria Elimination Programme (NMEP) GOODS Procurement of Long Lasting Open- Insecticide Internati Most Treated Nets 45,852,523 3rd Feb 13th July 1 Prior onal RFB Advantageou No Yes (Mass .29 2020 2020 s Bid Campaign & Routine Distribution) Procurement of Artemisinin based Open - Most National 3rd Feb 13th July 2 Combination Post 2,381,472 RFB Advantageou No No 2020 2020 Therapy (ACT)- s Bid (Public and Private) Procurement of Open- Most Rapid National 3rd Feb 13th July 3 Post 1,960,202 RFB Advantageou No No Diagnostics 2020 2020 s Bid Tests (RDTs) Most Artesunate Open- 3rd Feb 13th July 4 Post 420,881.89 RFB Advantageou No No Injection National 2020 2020 s Bid Sulphodoxine/P Most Open - 3rd Feb 13th July 5 yrimethamine_I Post 612,322 RFB Advantageou No No National 2020 2020 PTp s Bid Amodiaquine/Su Most lphodoxine/Pyri 2,990,781. Open - 3rd Feb 13th July 6 Post RFB Advantageou No No methamine 47 National 2020 2020 s Bid (SPAQ) Most Open - 3rd Feb 13th July 7 Sharp Boxes Post 152,122,43 RFB Advantageou No No National 2020 2020 s Bid Most Microscope Open - 3rd Feb 13th July 8 Post 491,031 RFB Advantageou No No commodities National 2020 2020 s Bid NON-CONSULTING SERVICES - NMEP State Malaria Elimination MOU/P Programme erform 10th 2,250,000. 9th July 1 (SMEP) Prior Limited ance Rated Criteria No NA February 00 2020 Performance Contra 2020 Contract and ct Operations National Malaria Elimination MOU/P Programme erform 10th 1,500,000. 9th July 2 (NMEP) Prior Limited ance Rated Criteria No NA February 00 2020 Performance Contra 2020 Contract and ct Operations National Primary Health Care Development Agency (NPHCDA) GOODS Procurement of Most vaccines and 61,380,767 5th Feb 13th July 1 Prior UN RFB Advantageou No No devices for .00 2020 2020 s Bid immunization Procurement and maintenance of Most UN 5th Feb 13th July 2 Generators and Post 900,000.00 RFB Advantageou No No System 2020 2020 Cold Chain s Bid Equipment (CCEs) Procurement and installation of Cold Chain Most 4,500,000. 5th Feb 13th July 3 Hubs (3 Prior UN RFB Advantageou No No 00 2020 2020 walking-in cold s Bid rooms) in Lagos Procurement of Emergency Transport 5th Feb 13th July 4 Service (ETS) Post 45,101.72 Limited RFQ Rated Criteria No No 2020 2020 vouchers, handbooks, and logbooks Procurement of Most Open- 5th Feb 13th July 5 equipment for Post 281,969.00 RFB Advantageou No No National 2020 2020 call centre s Bid Most Procurement of Open- 5th Feb 13th July 6 Post 969,529.00 RFB Advantageou No No 14 vehicles National 2020 2020 s Bid Procurement of 5th Feb 13th July 7 14 computer Post 14,000 Limited RFQ Rated Criteria No No 2020 2020 sets II. Summary of the procurement packages for Consulting Services -Planned for the first 18 months after project effectiveness): Selection Market Method Review Approach Expected Expected Estimate (QCBS, Shortlisti Sr. by Bank (Open - date of bid/ date of Contract Description d Cost FBS, ng No (Prior/ International proposal Contract (US$) LCBS, (Yes/ No) Post) / National/ opening Signature QBS, CQS, etc.) DS etc.) Nigeria Malaria Elimination Programme (NMEP) NGOs Service Contract (for 5 11,525,51 Open 10th Feb 31st Aug 1 Prior QCBS Yes states) 1.00 International 2020 2020 Technical Assistance to SMEP in 5 participating states, 630,000.0 10th Feb 31st July 2 Prior Limited INDV No multiple contracts by 0 2020 2020 different consultants Technical Assistance to NMEP (including procurement 150,000.0 10th Feb 31st July 3 Post Limited INDV No consultant), multiple 0 2020 2020 contracts. Independent Verification 300,000.0 Open- 10th Feb 31st July 4 Post CQS No Agents (IVA) for NGOs 0 National 2020 2020 Social and Behavioral Change 3,000,000. Open 10th Feb 31st Aug 5 Prior QCBS Yes Communication (SBCC) 00 International 2020 2020 Operations research on 2,131,148. Open 10th Feb 31st Aug 6 Prior QCBS Yes disease vector mapping 00 International 2020 2020 Operations research on entomological surveillance by 655,738.0 10th Feb 31st July 7 Prior Direct DS No Nigeria Institute of 0 2020 2020 Medical Research (NIMR) Operations research on therapeutic efficacy by 655,738.0 10th Feb 31st July 8 Prior Direct CDS No Nigeria Institute of 0 2020 2020 Medical Research (NIMR) Consultancy on warehouse 10th Feb 31st July 9 Post 32,131.00 Limited INDV No assessment 2020 2020 Programme Management Training (case management, 2,000,000. 10th Feb 31st July 10 Prior Limited INDV No M&E, IVM etc.) Multiple 00 2020 2020 Contracts National Primary Health Care Development Agency (NPHCDA) Technical assistance support 9,869,000. 10th Feb 31st July 1 to government for polio Prior UN CDS No 00 2020 2020 surveillance Technical assistance support to government for polio 15,301,00 10th Feb 31st July 2 Supplemental Immunization Prior UN CDS No 0.00 2020 2020 Activities (SIAs) surveillance through WHO Technical assistance support to government for polio 4,830,000. 10th Feb 31st July 3 logistics and social Prior UN CDS No 00 2020 2020 mobilization for polio through UNICEF Procurement of consultant for 10th Feb 31st July 4 Post 20,000.00 Limited INDV No landscape survey (SQUATS) 2020 2020 Technical assistance support 837,673.1 10th Feb 31st July 5 Prior Open-National INDV No to 12 SPHCDA PIU 3 2020 2020 Technical assistance support 10th Feb 31st July 6 Post 89,750.63 Limited INDV No to NPHCDA PIU 2020 2020 Procurement of Emergency Transport Services (ETS), MOU with National Union of 530,794.3 10th Feb 31st July 7 Prior Direct CDS No Road Transport Workers 9 2020 2020 (NURTW) and NACTOROMAS Training of ETS service providers, MOU with Federal 207,672.0 10th Feb 31st July 8 Post Direct CDS No Road Safety Commission 0 2020 2020 (FRSC) Conduct PAPA – Lot Quality Assurance Sampling, MOU 2,213,850. 10th Feb 31st July 9 Prior Limited CDS No with National Bureau of 00 2020 2020 Statistics (NBS) Consultancy for RCT research 1,902,356. 10th Feb 31st Aug 10 services with Nigerian Prior Open-National QCBS Yes 00 2020 2020 Universities Procurement of operations 1,689,751. Open- 10th Feb 31st Aug 11 Prior QCBS Yes research services 00 International 2020 2020 Support to Cold Chain Equipment (CCE) 23,000,00 10th Feb 31st July 12 Prior UN CDS No optimization platform 0.00 2020 2020 through UNICEF Technical assistance to 1,553,185. 10th Feb 31st July 13 LGHAs (89 total), multiple Post Open-National INDV No 50 2020 2020 contracts Technical assistance 310,076.0 10th Feb 31st July 14 Post Open-National QCBS Yes management firm 0 2020 2020 10th Feb 31st July 15 IVA for performance contract Post 300,000 Open-National CQS No 2020 2020 Procurement of services 3,203,345 Open- 10th Feb 31st Aug 16 for GIS imagery and Prior QCBS Yes .45 International 2020 2020 microplanning Procurement of Social Behaviour Change Open- 10th Feb 31st Aug 17 Prior 5,000,000 QCBS Yes Communication (SBCC) International 2020 2020 services Contracting of direct 2,000,000. Open- 10th Feb 31st Aug 18 Prior QCBS Yes facility financing firms 00 International 2020 2020 Appendix 1 Letter of Acceptance of the World Bank’s Anti-Corruption Guidelines and Sanctions Framework Date: Invitation of Bids/Proposals No.__________ To: ___________________________________________________________________________ We, along with our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not) consultants and personnel, acknowledge and agree to abide by the World Bank’s policy regarding Fraud and Corruption (corrupt, fraudulent, collusive, coercive, and obstructive practices), as set out and defined in the World Bank’s Anti-Corruption Guidelines1 in connection with the procurement and execution of the contract (in case of award), including any amendments thereto. We declare and warrant that we, along our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not), consultants and personnel, , are not subject to, and are not controlled by any entity or individual that is subject to, a temporary suspension, early temporary suspension, or debarment imposed by a member of the World Bank Group, including, inter alia, a cross-debarment imposed by the World Bank Group as agreed with other international financial institutions (including multilateral development banks), or through the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement. Further, we are not ineligible under the laws or official regulations of [Insert name of Employer as per bidding document] or pursuant to a decision of the United Nations Security Council. We confirm our understanding of the consequences of not complying with the World Bank’s Anti-Corruption Guidelines, which may include the following: a. rejection of our Proposal/Bid for award of contract; b. in the case of award, termination of the contract, without prejudice to any other remedy for breach of contract; and c. sanctions, pursuant to the Bank’s Anti-corruption Guidelines and in accordance with its prevailing sanctions policies and procedures as set forth in the Bank’s Sanctions Framework. This may include a 1Guidelineson Preventing and Combating Fraud and Corruption in Projects Financed by International Bank for Reconstruction and Development Loans and the International Development Agency Credits and Grants, dated October 15, 2006, and revised in January 2011 and July 2016, as they may be revised from time to time. public declaration of ineligibility, either indefinitely or for a stated period of time, (i) to be awarded or otherwise benefit from a Bank-financed contract, financially or in any other manner;2 (ii) to be a nominated3 sub-contractor, consultant, manufacturer or supplier, or service provider of an otherwise eligible firm being awarded a Bank-financed contract; and (iii) to receive the proceeds of any loan made by the Bank or otherwise to participate further in the preparation or implementation of any Bank-financed project. We understand that we may be declared ineligible as set out above upon: a. completion of World Bank Group sanctions proceedings according to its prevailing sanctions procedures; b. cross-debarment as agreed with other international financial institutions (including multilateral development banks); c. the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement; or d. temporary suspension or early temporary suspension in connection with an ongoing World Bank Group sanctions proceeding. For avoidance of doubt, the foregoing effects of ineligibility do not extend to a sanctioned firm’s or individual’s execution of its ongoing Bank-financed contracts (or its ongoing sub-agreements under such contracts) that are not the subject of a material modification, as determined by the Bank. We shall permit, and shall cause our sub-contractors, sub-consultants, agents (whether declared or not), personnel, consultants, service providers or suppliers, to permit the Bank to inspect4 all accounts, records, 2 For the avoidance of doubt, a sanctioned party’s ineligibility to be awarded a contract shall include, without limitation, (i) applying for pre-qualification, expressing interest in a consultancy, and bidding, either directly or as a nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider, in respect of such contract, and (ii) entering into an addendum or amendment introducing a material modification to any existing contract. 3 A nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider (different names are used depending on the particular bidding document) is one which has been: (i) included by the bidder in its pre-qualification application or bid because it brings specific and critical experience and know-how that allow the bidder to meet the qualification requirements for the particular bid; or (ii) appointed by the Borrower. 4 Inspections in this context are usually investigative (i.e., forensic) in nature: they involve fact-finding activities undertaken by the Bank or persons appointed by the Bank to address specific matters related to investigations/audits, such as evaluating the veracity of an allegation of possible Fraud and Corruption, through the appropriate mechanisms. Such activity includes but is not and other documents relating to the procurement process and/or contract execution (in the case of award), and to have them audited by auditors appointed by the Bank. We agree to preserve all accounts, records, and other documents (whether in hard copy or electronic format) related to the procurement and execution of the contract. Name of the Bidder/Consultant: Name of the person duly authorized to sign the Bid/Proposal on behalf of the Bidder/Consultant: Title of the person signing the Letter: limited to accessing and examining a firm's or individual's financial records and information, and making copies thereof as relevant; accessing and examining any other documents, data, and information (whether in hard copy or electronic format) deemed relevant for the investigation/audit, and making copies thereof as relevant; interviewing staff and other relevant individuals; performing physical inspections and site visits; and obtaining third-party verification of information. PROCUREMENT Nigeria : Nigeria Improved Child Survival Program for Human Capital MPA PLAN General Information Country: Nigeria 2022-08-25 Bank’s Approval Date of the Original Procurement Plan: 2023-06-02 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P167156 GPN Date: Project Name: Nigeria Improved Child Survival Program for Human Capital MPA Loan / Credit No: IDA / 65390 Kwara IMPACT Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned NG-KWARA IMPACT-312016- CW-RFQ / 1, Ply wood partitio Request for Quota ning of walls of 6-room office Component 2: Immunization Request for Quota Single Stage - One E tions - Small Work Under Imple 2022-10-0 IDA / 65390 Post Limited 19,218.00 0.00 2022-08-31 2022-09-06 2022-09-19 s 2. Painting 3. Repairs of ceil Plus tions nvelope s (Emergency) SP mentation 3 ing 4. Tiling of 6-room floors D -Competitive 5. Construction of soak away 6. Wiring of the offices GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NG-KWARA IMPACT-312022- GO-RFQ / 1. Executive table with side walk drawer 2. 10 Component 2: Immunization Request for Quota Single Stage - One E Under Imple Medium Executive tables wit IDA / 65390 Post Limited 8,236.00 0.00 2022-09-02 2022-09-21 2022-09-28 Plus tions nvelope mentation h one- side drawer 3. 1 Exec utive rotatable chair 4. 10 r otatable chairs 5. 1-3-Seater Sofa 6. One centre-table NG-KWARA IMPACT-312119- GO-RFQ / 2Nos 4X4WD, doub Component 2: Immunization Request for Quota Single Stage - One E Under Imple IDA / 65390 Post Limited 186,685.00 0.00 2022-09-22 2022-10-05 2022-10-12 le cabin pick up van,2.7 litre Plus tions nvelope mentation engine, shell specification NG-KWARA IMPACT-312139- GO-RFQ / Procurement of Off ice Equipment--14 Nos. Lapto p Computers, 1 No. Desktop Component 2: Immunization Request for Quota Single Stage - One E Under Imple IDA / 65390 Post Limited 25,581.33 0.00 2022-09-11 2022-09-24 2022-10-01 Computer, 1 No. Coloured pri Plus tions nvelope mentation nter, 1NO. Black and White p rinter, 1 No. Photocopier, 1 N o. Projector with screen1 No., Camera Zoom for PIU use NG-KWARA IMPACT-312153- GO-RFQ / Procurement of Ele ctrical Electronics--1 N0. 55 I Component 2: Immunization Request for Quota Single Stage - One E Under Imple IDA / 65390 Post Limited 5,078.94 0.00 2022-09-07 2022-09-14 2022-09-27 2022-10-04 nches coloured television, 4 Plus tions nvelope mentation Nos. 1.5 HP Air- conditioner, 2Nos. Public Address System (PAS) NG-KWARA IMPACT-312160- GO-RFQ / Procurement of Inv Component 2: Immunization Request for Quota Single Stage - One E Pending Impl erter with solar panels and b IDA / 65390 Post Limited 19,080.30 0.00 2022-10-05 2022-10-18 2022-11-01 Plus tions nvelope ementation atteries for PIU office as alter native power source for effec tiveness NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NG-KWARA IMPACT-364290- Component 2: Immunization Request for Quota Single Stage - One E Pending Impl NC-RFQ / Insurance of 2 Toyo IDA / 65390 Post Limited 16,064.00 0.00 2023-06-04 2023-07-30 2024-01-26 Plus tions nvelope ementation ta hilux van CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NG-KWARA IMPACT-331747- CS-INDV / Engagement of In Component 2: Immunization Individual Consult Pending Impleme IDA / 65390 Post Limited 2,353.00 0.00 2022-12-16 2022-12-21 2023-01-11 2023-02-15 2023-08-14 dividual Consultant for Decen Plus ant Selection ntation tralized Facility Financing(DF F) for IMPACT Project NG-KWARA IMPACT-361242- CS-CDS / Request for clearan Component 2: Immunization Pending Impleme ce of Terms of Reference and IDA / 65390 Post Direct Selection Direct - National 3,260.87 0.00 2023-06-05 2023-06-15 2023-08-19 2024-02-15 Plus ntation approval of engagement of E xternal Auditor to audit Kwar a IMPACT finances NG-KWARA IMPACT-361262- CS-INDV / Flexible Accountin Component 2: Immunization Individual Consult Pending Impleme IDA / 65390 Post Limited 10,752.69 0.00 2023-05-16 2023-05-21 2023-06-11 2023-07-16 2024-01-12 g software and installation fo Plus ant Selection ntation r Kwara IMPACT Project Page 1 Procurement Plan I. General 1. Bank’s approval Date of the procurement Plan: May 20, 2017 2. Date of General Procurement Notice: Oct. 10, 2016 3. Period covered by this procurement plan: The whole project period II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Procurement Method Prior Review Comments Threshold US$ 1. ICB and LIB (Goods) 4 million 2. NCB (Goods) 4 million 3. ICB (Works) 15 million 4. NCB (Works) 15 million 5. (Non-Consultant Services) 4 million [Add other methods if necessary] 2. Prequalification. _Not applicable_. 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: Not applicable 4. Reference to (if any) Project Operational/Procurement Manual: Not applicable 5. Any Other Special Procurement Arrangements: Advance procurement and retroactive financing 6. Summary of the Procurement Packages planned during the first 18 months after project effectiveness ( including those that are subject to retroactive financing and advanced procurement) 1 2 3 4 5 6 7 Ref. Descripti Estimat Packages Dome Review Comme No. on ed stic by Bank nts Cost Prefe (Prior / July 9, 2010 US$ rence Post) million (yes/ no) Summary 0 0 N/A N/A of the ICB (Works) Summary 0 0 N/A N/A of the ICB (Goods) Summary 150.47 10 No Prior / of the NCB Post (Works) Summary 50.40 12 No Prior / of the NCB Post (Goods) Summary 0 0 N/A N/A of the ICB (Non- Consultant Services) III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Comments Threshold 1. Competitive Methods (Firms) US$2 million 2. Single Source (Firms) US$1 million 3. Individual US$0.4 million 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $500,000 equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: Not applicable 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 Ref. No. Description Estimat Package Review Comment of ed s by Bank s Assignmen Cost (Prior / t US$ Post) million Summary 0.51 1 Post July 9, 2010 of number of contracts that will be let under QCBS Summary 1.82 12 Post of number of contracts that will be let under other methods July 9, 2010 PROCUREMENT China : Three Gorges Modern Logistics Center Infrastructure Project PLAN General Information Country: China 2018-05-18 Bank’s Approval Date of the Original Procurement Plan: 2023-06-05 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P153473 GPN Date: Project Name: Three Gorges Modern Logistics Center Infrastructure Project Loan / Credit No: IBRD / 87660 Yi Chang PMO Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GK-C2 / Road, architectural, port, electric, communication Baiyang Port and operations Single Stage - One E 27,220,000.0 21,228,646. 2020-12-2 , water supply & drainage, en IBRD / 87660 Prior Request for Bids Open - National Signed 2019-04-25 2019-05-18 2019-04-30 2019-05-30 2019-06-20 2019-06-06 2019-07-18 2019-07-04 2019-07-16 Area nvelope 0 20 5 vironmental protection works and temporary works in Stor age Yard 7#, 12# and 13#. WL-C3 / Intelligent Cargo Dis tributing Center: 1 Building ( 21,000m2) and electric, com Single Stage - One E 15,998,784. 2020-03-2 IBRD / 87660 Baiyang Logistics Park Post Request for Bids Open - National 9,670,000.00 Signed 2019-06-10 2020-09-15 2019-06-15 2019-07-27 2021-03-11 2019-08-26 2021-03-11 2019-09-30 2021-09-02 munications, water supply & nvelope 73 8 drainage, fire-fighting and en vironmental protection, etc i n Building. DJ-C1 / Roadbed (earthwork & foundation treatment), pav ement (carriageway, sidewal Transport Connection Infrast Single Stage - One E 4,655,609.8 2020-06-0 IBRD / 87660 Prior Request for Bids Open - National 7,400,000.00 Signed 2019-08-16 2020-06-29 2019-08-21 2019-10-02 2016-12-27 2019-11-01 2020-08-06 2019-12-06 2017-05-16 k & auxiliaries), traffic, culver ructure nvelope 7 3 ts, lighting, integrated pipe n etwork and drainage in Guih u Road & 2nd Songgang Roa d. WL-C4 / 1. Containing Devan ing & Loading Warehouse: 2 buildings (10,600m2). 2. Foo dstuff Warehouse: 3 building Single Stage - One E 14,940,000.0 12,435,211. 2020-06-0 IBRD / 87660 Baiyang Logistics Park Prior Request for Bids Open - National Signed 2019-08-15 2020-08-14 2019-08-20 2019-10-01 2017-08-08 2019-10-31 2020-08-21 2019-12-05 2017-11-02 s (19,300m2). 3. Processing nvelope 0 33 2 Factory: 2 buildings (4,600m 2). 4. Parking Lot: Road (12,9 00m2). 5.W1 Container Yard. 6. W1~3# Substation(1800m 2). 7.Earthwor DJ-C2 / Roadbed (earthwork & foundation treatment), pav ement (carriageway, sidewal Baiyang Port and operations Single Stage - One E 11,060,000.0 9,665,753.9 2021-06-0 k & auxiliaries), bridge, retai IBRD / 87660 Post Request for Bids Open - National Signed 2020-08-13 2017-06-02 2020-08-18 2020-09-29 2017-07-04 2020-10-29 2017-07-04 2020-12-03 2017-07-29 Area nvelope 0 0 1 ning wall, traffic, culverts, lig hting, integrated pipe networ k and drainage in Shawan Ro ad Overpass. WL-C3-2020 / Intelligent Car go Distributing Center: 1 Bui lding (21,000m2) and electric Single Stage - One E 18,380,000.0 Under Imple 2021-07-0 IBRD / 87660 Baiyang Logistics Park Prior Request for Bids Open - National 0.00 2020-09-15 2020-10-23 2020-09-20 2020-11-01 2021-03-11 2020-12-01 2021-08-04 2021-01-05 , communications, water sup nvelope 0 mentation 4 ply & drainage, fire-fighting a nd environmental protection, etc in Building. WL-C9 / Earthwork excavatio n and backfilling within 890 Request for Bids - mu of area A and B of Comm Single Stage - One E Works (without pr 13,846,153.0 Under Imple 2022-03-0 IBRD / 87660 Baiyang Logistics Park Post Request for Bids Open - National 0.00 2021-05-20 2021-05-27 2021-05-25 2021-07-06 2021-06-30 2021-08-05 2021-06-30 2021-09-09 erce and trade logistics ,unfi nvelope equalification) SP 0 mentation 8 nished subgrade and pavem D ent and supporting works of Guihu road and 2nd Songgan g road. WL-C5 / 1. Si Cheng apartme nt; 2. number 1: comprehens Request for Bids - ive warehouse (1 building); 3 Single Stage - One E Works (without pr 12,500,000.0 Under Imple 2022-04-0 . Building electrical, commun IBRD / 87660 Baiyang Logistics Park Post Request for Bids Open - National 0.00 2021-06-15 2021-08-05 2021-06-20 2021-08-01 2021-09-07 2021-08-31 2021-09-07 2021-10-05 nvelope equalification) SP 0 mentation 3 ication, water supply and dra D inage, fire protection, enviro nmental protection engineeri ng and earthwork Road site. WL-C2 / The scope of this bi dding mainly covers the civil Request for Bids - works of commercial area B Single Stage - One E Works (without pr 37,094,281.0 2022-06-2 of the world bank loan projec IBRD / 87660 Baiyang Logistics Park Prior Request for Bids Open - National 0.00 Signed 2021-09-09 2021-11-17 2021-09-14 2021-10-26 2021-12-20 2021-11-25 2022-09-02 2021-12-30 nvelope equalification) SP 0 8 t, including 2 processing plan D ts, 2 warehouses, 1 office bui lding, 2 power distribution su bstations and 1 fire pump ho use. WL-C1 / 1. Commercial ware house (3 ); 2. Processing plan t (3 ); 3. Exhibition and tradin Request for Bids - g center (1 ); 4. Office buildin Single Stage - One E Works (without pr 38,460,000.0 2022-09-0 IBRD / 87660 Baiyang Logistics Park Prior Request for Bids Open - National 0.00 Signed 2021-11-15 2022-06-14 2021-11-20 2022-01-01 2022-08-02 2022-01-31 2022-09-07 2022-03-07 g (1 ); 5. Substation (2 sets); nvelope equalification) SP 0 3 6. Roads, storage yards and D parking lots; 7. Underground hydropower, pipe network,el ectrical, communication WL-C2-NEW / The scope of t his bidding mainly covers the Request for Bids - civil works of commercial are Single Stage - One E Works (without pr 37,094,281.0 2023-04-2 a B of the world bank loan pr IBRD / 87660 Baiyang Logistics Park Prior Request for Bids Open - National 0.00 Canceled 2022-07-11 2022-07-16 2022-08-27 2022-09-26 2022-10-31 nvelope equalification) SP 0 9 oject, including 2 processing D plants, 2 warehouses, 1 offic e building, 2 power distributi on substations and 1 fire pu mp house. Request for Bids - XX-C1. / Information Center ( Baiyang Logistics Informatio Single Stage - One E Works (without pr Pending Imp 2024-03-2 IBRD / 87660 Post Request for Bids Open - National 1,428,571.00 0.00 2023-06-07 2023-06-12 2023-07-24 2023-08-23 2023-09-27 Decoration and Construction) n Platform and Facilities nvelope equalification) SP lementation 5 D GK-C1 / Construction Works Baiyang Port and operations Single Stage - One E 12,851,093. for 8#-11# Berths and 7#-11 IBRD / 87660 Prior Request for Bids Open - National 0.00 Signed 2017-11-11 2017-12-08 Area nvelope 41 # Land Territories GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 1 GK-G6 / 30 Mobile Belt Conv eyors L=15m; 144m Belt Con Baiyang Port and operations Single Stage - One E veyors IBRD / 87660 Post Request for Bids Open - National 734,200.00 0.00 Canceled 2019-07-30 2019-08-27 2019-08-04 2019-09-03 2019-08-27 2019-10-03 2019-08-27 2019-11-07 2020-05-05 Area nvelope B1200, V2.0m/s, 2 electric wi nches 3T GK-C3 / 1360m windproof an Baiyang Port and operations Request for Quota Single Stage - One E IBRD / 87660 Post Open - National 198,200.00 197,816.75 Signed 2019-08-21 2019-10-16 2019-10-01 2020-04-13 d dust suppression net, 8m h Area tions nvelope igh GK-G4 / Port transfer equipm Baiyang Port and operations Single Stage - One E IBRD / 87660 Prior Request for Bids Open - National 4,540,000.00 5,011,254.40 Signed 2020-05-01 2021-03-04 2020-05-06 2020-06-17 2021-04-16 2020-07-17 2021-04-27 2020-08-21 2021-06-08 2021-02-17 ent (Berths#10-#11) Area nvelope GK-G3 / 8 #9# berth:90 × 1 4 m steel Barges, 2 vessels Baiyang Port and operations Single Stage - One E 600t/h circular track loaders, IBRD / 87660 Prior Request for Bids Open - National 8,249,027.00 6,835,909.10 Signed 2021-05-23 2021-06-01 2021-05-28 2021-07-09 2021-08-24 2021-08-08 2021-11-02 2021-09-12 2021-12-08 2022-03-11 Area nvelope 2 sets; belt conveyors, 7 sets , 1584m; 3T electric hoist, 3 sets. GK-G2 / 2 sets of 40t-30m p ortal cranes, 1 set of 16t-30 m portal crane, 1 set of 45t-2 Baiyang Port and operations Single Stage - One E IBRD / 87660 Prior Request for Bids Open - National 8,093,385.00 7,930,883.30 Terminated 2021-05-23 2021-07-09 2021-05-28 2021-07-09 2021-08-25 2021-08-08 2021-11-17 2021-09-12 2021-12-24 2022-03-11 5m quayside container bridg Area nvelope e crane, 2 sets of 40t-30m R ail Gantry Cranes, 4 sets of 1 6t-22.5m bridge cranes GK-G1 / 1 tire crane 50t, 2 ti re cranes 30t; 2 sets of tire c Baiyang Port and operations Single Stage - One E IBRD / 87660 Prior Request for Bids Open - National 6,800,000.00 0.00 Signed 2021-11-05 2022-02-21 2021-11-10 2021-12-22 2022-07-06 2022-01-21 2022-08-31 2022-02-25 2023-04-12 2022-08-24 ranes 16t; 4 container front c Area nvelope ranes and 4 container straddl e carriers WL-G6 / Rail mounted contai Single Stage - One E ner gantry crane 45t-40m fiv IBRD / 87660 Baiyang Logistics Park Prior Request for Bids Open - National 9,230,000.00 0.00 Signed 2021-11-10 2022-02-21 2021-11-15 2021-12-27 2022-07-04 2022-01-26 2022-08-16 2022-03-02 2022-08-29 nvelope e Rail mounted gantry crane 16t-40m two WL-G5 / Rail mounted contai Single Stage - One E ner gantry crane 45t-40m fiv IBRD / 87660 Baiyang Logistics Park Prior Request for Bids Open - National 9,850,000.00 0.00 Signed 2021-11-10 2022-02-21 2021-11-15 2021-12-27 2022-07-05 2022-01-26 2022-08-16 2022-03-02 2022-08-29 nvelope e Rail mounted gantry crane 40t-40m two WL-G1 / Bridge crane 32t-19 .5m eight 16t-28.5m eight 16t-19.5m eight Electric sin Single Stage - One E Under Imple IBRD / 87660 Baiyang Logistics Park Post Request for Bids Open - National 3,730,000.00 0.00 2021-11-12 2021-12-15 2021-11-17 2021-12-29 2022-07-13 2022-01-28 2022-03-04 2022-08-31 gle beam crane 5t-16.5m two nvelope mentation Embedded boarding axle 1 0t seventy-six Electronic tru ck scale 150t seven WL-G2 / Forklift 5t 10 3t 27 2t ,21 Single bucket loader ZL50 ,14 tractor Q45,18 Fla Single Stage - One E t car PC40 36 tractor Q20 IBRD / 87660 Baiyang Logistics Park Prior Request for Bids Open - National 8,170,000.00 0.00 Signed 2021-11-12 2022-02-21 2021-11-17 2021-12-29 2022-07-12 2022-01-28 2022-08-30 2022-03-04 2022-08-31 nvelope 18 Flat car P20 36 ,Contai ner tractor 40 Container se mitrailer 40 feet 20 Dump truck 55t 24. GK-G9 / Two 40t-30m gantry cranes, two 16t-30m gantry c ranes, one 45t-25m quayside Baiyang Port and operations Single Stage - One E container bridge crane, two 4 IBRD / 87660 Prior Request for Bids Open - National 11,540,000.00 0.00 Canceled 2022-09-20 2022-10-15 2022-11-06 2022-12-06 2023-01-10 2023-07-09 Area nvelope 0t-30m Rail Gantry Cranes, o ne multipurpose gantry cran e (45t-30m), and four 16t-22. 5m bridge cranes GK-G9. / includes the manuf acturing, installation, commis sioning, inspection and final delivery of two 40t-30m port Baiyang Port and operations Open - Internationa Single Stage - One E IBRD / 87660 Prior Request for Bids 10,563,380.00 0.00 Canceled 2022-10-15 2022-11-18 2022-10-20 2022-12-01 2022-12-31 2023-02-04 2023-08-03 al cranes, two 16t-30m portal Area l nvelope cranes, one 45t-25m quaysid e container bridge crane, one 45t-30m multi-purpose portal crane, etc. GK-G9-NEW / includes the m anufacturing, installation, co mmissioning, inspection and Baiyang Port and operations Open - Internationa Single Stage - One E Under Imple final delivery of two 40t-30m IBRD / 87660 Prior Request for Bids 9,285,700.00 0.00 2023-01-17 2023-01-19 2023-01-22 2023-03-05 2023-03-10 2023-04-04 2023-04-27 2023-05-09 2023-11-05 Area l nvelope mentation portal cranes, one 45t-25m q uayside container bridge cra ne, one 45t-30m multi-purpo se portal crane, etc. XX-G1 / Information Center ( Baiyang Logistics Informatio Single Stage - One E Under Imple IBRD / 87660 Prior Request for Bids Open - National 9,285,714.00 0.00 2023-06-01 2023-06-02 2023-06-06 2023-07-18 2023-08-17 2023-09-21 2024-03-19 Information Construction) n Platform and Facilities nvelope mentation XX-C1 / Information Center ( Baiyang Logistics Informatio Single Stage - One E IBRD / 87660 Post Request for Bids Open - National 1,428,571.00 0.00 Canceled 2023-06-05 2023-06-10 2023-07-22 2023-08-21 2023-09-25 2024-03-23 Decoration and Construction) n Platform and Facilities nvelope NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NL-S7 / To develop research about "Business Model & Ope Quality And Cost- Open - Internationa IBRD / 87660 Capacity Building Prior 538,000.00 0.00 Signed 2018-07-19 2018-08-09 2018-07-23 2018-08-30 2019-04-10 2018-09-06 2019-05-15 2018-09-13 2019-08-12 2018-09-30 2023-04-17 2018-10-28 2020-04-20 ration Schedule of Baiyang P Based Selection l ort & Logistics Park" INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 2 NL-S1 / To provide support a bout Architectural Engineerin Individual Consult Pending Impleme IBRD / 87660 Capacity Building Post Open 29,400.00 0.00 2019-06-15 2019-08-03 2019-08-24 2019-09-28 2020-03-26 g to Project Office during imp ant Selection ntation lementation period. NL-S2 / To provide support a bout Port & Harbor Engineeri Individual Consult Pending Impleme IBRD / 87660 Capacity Building Post Open 22,000.00 0.00 2019-06-15 2019-08-03 2019-08-24 2019-09-28 2020-03-26 ng to Project Office during im ant Selection ntation plementation period. Page 3 PROCUREMENT PLAN (Textual Part) Project information: [country] [Project name] [P-number] Project Implementation agency: [insert legal name] Date of the Procurement Plan: [insert date] Period covered by this Procurement Plan: [insert from – to period] Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in [insert appropriate references to the national procurement legislation], such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. List only the applicable conditions required to ensure consistency with paragraph 5.4 of the Procurement Regulations. If no conditions apply, delete the phrase “and the following conditions”. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. Otherwise state “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables Otherwise state “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Specify for each Goods: [is not applicable/is applicable for those contracts identified in the Procurement Plan tables]; Works: [is not applicable/is applicable for those contracts identified in the Procurement Plan tables] Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations is Applicable. [Include this sentence only if the Bank has formally agreed to provide the Borrower with HEIS. Otherwise delete] Other Relevant Procurement Information. Provide any other relevant procurement information such as procedures for CDD components, Procurement in Situations of Urgent Need of Assistance or Capacity Constraints etc. PROCUREMENT Suriname : Saramacca Canal System Rehabilitation Project PLAN General Information Country: Suriname 2019-07-23 Bank’s Approval Date of the Original Procurement Plan: 2023-06-02 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P165973 GPN Date: 2019-08-01 Project Name: Saramacca Canal System Rehabilitation Project Loan / Credit No: IBRD / 89240 Ministry of Public Works Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned MPWTC-WB-SCSRP-CMP1-00 Improving the Drainage Infra Open - Internationa Single Stage - Two E 18,300,000.0 2021-08-0 3 / Rehabilitation of sluices a IBRD / 89240 Prior Request for Bids 0.00 Canceled 2020-09-01 2020-09-06 2020-10-18 2021-02-04 structure l nvelope 0 3 nd locks and canal re-profilin g and clearing MPWTC-WB-SCSRP-CMP1-00 6 / Upgrading of selected criti Improving the Drainage Infra Open - Internationa Single Stage - Two E Pending Imp 2022-06-0 IBRD / 89240 Prior Request for Bids 2,700,000.00 0.00 2021-07-01 2021-07-06 2021-08-17 2021-12-04 cal secondary or tertiary urb structure l nvelope lementation 2 an sub-catchment areas MPWTC-WB-SCSRP-CMP3-00 4 / Emergency Rehabilitation Providing a Contingent Emer Open - Internationa Single Stage - Two E Pending Imp 2020-08-0 IBRD / 89240 Post Request for Bids 300,000.00 0.00 2019-09-05 2019-09-10 2019-10-22 2020-02-08 of critical infrastructure affec gency Response l nvelope lementation 6 ted by a disaster SR-MP-204061-CW-RFB / Re Improving the Drainage Infra Open - Internationa Single Stage - Two E 18,300,000.0 Pending Imp 2021-10-1 habilitation of sluices and loc IBRD / 89240 Post Request for Bids 0.00 2020-11-10 2020-11-15 2020-12-27 2021-03-11 2021-04-15 structure l nvelope 0 lementation 2 ks and canal re-profiling and cleaning MPW\WB\SCSRP\CMP 4-017 / Renovation of an office buildi Supporting Project Managem Request for Quota Single Stage - One E Other (with field f 2022-03-0 IBRD / 89240 Post Limited 80,000.00 191,371.34 Signed 2021-07-10 2021-07-12 2021-09-04 2021-12-16 ng for the SCU unit located a ent and Implementation tions nvelope or explanation) 3 t the Duisburglaan Request for Bids - MPW\WB\SCSRP\CMP1-002 / Improving the Drainage Infra Open - Internationa Single Stage - One E Small Works SPD Under Imple 2024-04-1 IBRD / 89240 Post Request for Bids 2,800,000.00 0.00 2023-03-20 2023-04-05 2023-03-25 2023-04-05 2023-05-06 2023-06-05 2023-07-10 Saramacca Canal Maintenanc structure l nvelope (1 envelope proce mentation 0 e ss) Request for Bids - MPW\WB\SCSRP\CMP1-003 / Improving the Drainage Infra Open - Internationa Single Stage - One E Small Works SPD 11,700,000.0 Under Imple 2024-10-1 Rehabilitation Doorsteek Loc IBRD / 89240 Prior Request for Bids 0.00 2023-06-07 2023-06-12 2023-08-08 2023-09-07 2023-10-12 structure l nvelope (1 envelope proce 0 mentation 1 k and Sluices ss) GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MPWTC-WB-SCSRP-CMP4-01 1 / Support to operating logis Supporting Project Managem Request for Quota Single Stage - One E IBRD / 89240 Post Open - National 25,000.00 0.00 Canceled 2019-06-06 2019-08-01 2020-01-28 tical costs (utilities, small offi ent and Implementation tions nvelope ces services and equipments, etc). MPWTC-WB-SCSRP-CMP4-01 3 / Procurement of equipmen t for the operational manage Supporting Project Managem Single Stage - One E ment and monitoring (such a IBRD / 89240 Post Request for Bids Open - National 270,000.00 0.00 Canceled 2019-07-01 2019-07-06 2019-08-17 2019-09-16 2019-10-21 2020-04-18 ent and Implementation nvelope s vehicles, boat, furniture, an d information and communic ation technology or lab equip ment) MPWTC-WB-SCSRP-CMP4-01 4 / Procurement of ad-hoc se rvice or small goods for impl ementation of Communicatio Supporting Project Managem Request for Quota Single Stage - One E Pending Impl n plan (including support for IBRD / 89240 Post Open - National 60,000.00 0.00 2019-09-06 2019-11-01 2020-04-29 ent and Implementation tions nvelope ementation the development of a commu nications strategy for engagi ng with local communities an d stakeholders, logistic organ ization of events, etc.) MPWTC-WB-SCSRP-CMP4-01 Supporting Project Managem Request for Quota Single Stage - One E IBRD / 89240 Post Open - National 301,000.00 0.00 Canceled 2021-09-06 2021-11-01 2022-04-30 6 / Contingecy ent and Implementation tions nvelope MPWTC-WB-SCSRP-CMP3-00 3 / Procurement of goods for Providing a Contingent Emer Request for Quota Single Stage - One E Pending Impl IBRD / 89240 Post Open - National 50,000.00 0.00 2019-09-09 2019-11-04 2020-05-02 emergency or recovery of aff gency Response tions nvelope ementation ected population after a disa ster MPWTC-WB-SCSRP-CMP2-00 Strengthening the Saramacc Request for Quota Single Stage - One E Pending Impl 3 / Monitoring Instruments fo IBRD / 89240 Post Open - National 20,000.00 0.00 2019-09-06 2019-11-01 2020-04-29 a Canal System tions nvelope ementation r the Saramacca Catchment Area MPWTC-WB-SCSRP-CMP4-01 2 / Procurement Quickbooks and/or similar software for F Supporting Project Managem Request for Quota Open - Internationa Single Stage - One E M management, or flood mo IBRD / 89240 Post 100,000.00 0.00 Canceled 2019-07-06 2019-08-31 2020-02-27 ent and Implementation tions l nvelope deling software, or software r elated to project manageme nt, including training and assi stance for the project MPWTC\WB\SCSRP\CMP4-02 Supporting Project Managem Request for Quota Single Stage - One E Under Imple 2 / Delivery of three (3) vehic IBRD / 89240 Post Limited 170,000.00 0.00 2022-08-30 2022-03-29 2022-10-25 2023-04-23 ent and Implementation tions nvelope mentation les for the SCU. MPWTC\WB\SCSRP\CMP4-02 Supporting Project Managem Request for Quota Single Stage - One E Under Imple 3 / Supply and installation of IBRD / 89240 Post Open - National 9,000.00 0.00 2022-09-06 2022-10-11 2022-11-01 2023-04-30 ent and Implementation tions nvelope mentation Airconditioning (AC) units MPWTC\WB\SCSRP\CMP4-02 4 / Supply and Installation of Supporting Project Managem Request for Quota Single Stage - One E Under Imple IBRD / 89240 Post Open - National 75,000.00 0.00 2022-09-21 2022-11-16 2023-05-15 Office Electronics for the SCU ent and Implementation tions nvelope mentation (Laptops, Monitors, UPS Batt ery Backup) Page 1 MPWTC\WB\SCSRP\CMP4-02 5 / Supply and Installation of Supporting Project Managem Request for Quota Single Stage - One E Under Imple IBRD / 89240 Post Open - National 50,000.00 0.00 2022-09-21 2022-11-16 2023-05-15 Office Electronics for the SCU ent and Implementation tions nvelope mentation (Mobile phones, Beamer, Prin ters, Terastation) MPWTC\WB\SCSRP\CMP4-02 Supporting Project Managem Request for Quota Single Stage - One E Under Imple 1 / Supply and Installation of IBRD / 89240 Post Open - National 60,000.00 0.00 2022-09-25 2022-11-20 2023-05-19 ent and Implementation tions nvelope mentation Office Furniture for the SCU MPWTC\WB\SCSRP\CMP4-02 Supporting Project Managem Request for Quota Single Stage - One E Under Imple 6 / Survey, Supply and Install IBRD / 89240 Post Open - National 35,000.00 0.00 2022-09-25 2022-11-20 2023-05-19 ent and Implementation tions nvelope mentation ation of Window Blinds MPW\WB\SCSRP\CMP4-027 / Supporting Project Managem Request for Quota Single Stage - One E Under Imple Delivery, Installation and Co IBRD / 89240 Post Open - National 70,000.00 0.00 2022-12-05 2023-01-30 2023-07-29 ent and Implementation tions nvelope mentation mmissioning of Network & Se rver Equipment MPW\WB\SCSRP\CMP4-028 / Design, Production, Installati Supporting Project Managem Request for Quota Single Stage - One E Under Imple IBRD / 89240 Post Open - National 12,000.00 0.00 2022-12-05 2023-01-30 2023-07-29 on and Commissioning of Inf ent and Implementation tions nvelope mentation ormation Billboard Services MPW\WB\SCSRP\CMP4-029 / Website Design, Creation, Ho Supporting Project Managem Request for Quota Single Stage - One E Under Imple IBRD / 89240 Post Limited 20,000.00 0.00 2023-01-15 2023-01-17 2023-03-12 2023-09-08 sting including Commissionin ent and Implementation tions nvelope mentation g and Maintenance MPW\WB\SCSRP\CMP4-030 / Supply and Installation of Lap Supporting Project Managem Request for Quota Single Stage - One E top Computers as part of the IBRD / 89240 Post Open - National 55,000.00 0.00 Canceled 2023-04-11 2023-06-06 2023-09-04 ent and Implementation tions nvelope Capacity Building for the Mini stery of Public Works - SCU members. MPW\WB\SCSRP\CMP4-031 / Supply, Delivery and Installat Supporting Project Managem Request for Quota Single Stage - One E Under Imple ion of Laptops and Electronic IBRD / 89240 Post Open - National 85,000.00 0.00 2023-05-02 2023-06-27 2023-12-24 ent and Implementation tions nvelope mentation Equipment for Capacity Build ing of the Ministry of Public Works NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MPWTC-WB-SCSRP-CMP4-01 0 / Ad-hoc training for special ized field related to the proje Supporting Project Managem Request for Quota Open - Internationa Single Stage - One E IBRD / 89240 Post 64,000.00 0.00 Canceled 2019-06-06 2019-08-01 2020-01-28 ct (including technical, procu ent and Implementation tions l nvelope rement, safeguards, monitori ng and evaluation, and finan cial management) MPWTC-WB-SCSRP-CMP4-01 5 / Procurement of ad-hoc se rvice for Monitoring and eval Supporting Project Managem Request for Quota Single Stage - One E IBRD / 89240 Post Open - National 90,000.00 0.00 Canceled 2021-09-06 2021-11-01 2022-04-30 uation (including collecting s ent and Implementation tions nvelope ocioeconomic data during pr oject implementation and bef ore project completion, etc) MPWTC-WB-SCSRP-CMP3-00 2 / Consultant for rapid asses Providing a Contingent Emer Request for Quota Single Stage - One E IBRD / 89240 Post Open - National 50,000.00 0.00 Canceled 2019-09-08 2019-11-03 2020-05-01 sment of emergency rehabilti gency Response tions nvelope ation works or flood impact a ssessment CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MPWTC-WB-SCSRP-CMP2-00 4 / Consulting Services for th Strengthening the Saramacc Consultant Qualifi e feasibility study for the Inst IBRD / 89240 Post Open - National 200,000.00 0.00 Canceled 2019-09-01 2019-09-22 2019-11-05 2019-12-05 2020-01-09 2020-07-07 a Canal System cation Selection itutional support toward a po ssible Saramacca Canal Syst em Platform MPWTC-WB-SCSRP-CMP3-00 1 / Consulting Services for ra Providing a Contingent Emer Consultant Qualifi Pending Impleme IBRD / 89240 Post Open - National 100,000.00 0.00 2019-09-02 2019-09-23 2019-11-06 2019-12-06 2020-01-10 2020-07-08 pid assessment of emergenc gency Response cation Selection ntation y rehabiltiation works or floo d impact assessment MPWTC-WB-SCSRP-CMP1-00 1 / Consulting Services for th e design elaboration of the bi Improving the Drainage Infra Quality And Cost- Open - Internationa IBRD / 89240 Prior 1,700,000.00 1,283,006.90 Signed 2019-06-20 2019-08-01 2019-07-11 2019-08-23 2019-08-24 2020-04-04 2019-09-21 2020-06-10 2019-10-21 2020-10-12 2019-11-25 2021-04-13 2019-12-30 2021-05-31 2020-12-29 dding documents (Lot 1) for t structure Based Selection l he Rehabilitation of sluices a nd locks and canal re-profilin g and clearing MPWTC-WB-SCSRP-CMP1-00 2 / Consulting Services for th Improving the Drainage Infra Quality And Cost- Open - Internationa Pending Impleme e supervision of works (Lot 2) IBRD / 89240 Post 1,500,000.00 0.00 2020-09-01 2020-09-22 2020-11-05 2020-12-03 2021-01-02 2021-02-06 2021-03-13 2022-03-13 structure Based Selection l ntation for the Rehabilitation of sluic es and locks and canal re-pro filing and clearing MPWTC-WB-SCSRP-CMP2-00 1 / Consulting Services for th Strengthening the Saramacc Quality And Cost- Open - Internationa IBRD / 89240 Prior 1,100,000.00 1,510,052.21 Signed 2019-07-01 2019-08-01 2019-07-22 2019-08-28 2019-09-04 2020-04-01 2019-10-02 2020-06-10 2019-11-01 2020-10-30 2019-12-06 2021-06-17 2020-01-10 2021-08-06 2021-01-09 e Updating of norms and gui a Canal System Based Selection l delines for drainage manage ment MPWTC-WB-SCSRP-CMP2-00 2 / Consulting Services for th Strengthening the Saramacc Quality And Cost- Open - Internationa Pending Impleme e Drainage infrastructure ass IBRD / 89240 Post 1,200,000.00 0.00 2019-09-01 2019-09-22 2019-11-05 2019-12-03 2020-01-02 2020-02-06 2020-03-12 2021-03-12 a Canal System Based Selection l ntation et management platform and a flood forecasting system MPWTC-WB-SCSRP-CMP4-00 Supporting Project Managem Quality And Cost- IBRD / 89240 Post Open - National 200,000.00 0.00 Canceled 2019-12-01 2019-12-22 2020-02-04 2020-03-03 2020-04-02 2020-05-07 2020-06-11 2021-06-11 1 / Consulting Services for Pr ent and Implementation Based Selection oject audit Page 2 MPWTC-WB-SCSRP-CMP1-00 4 / Consulting Services for th e design elaboration of the bi Improving the Drainage Infra Consultant Qualifi Open - Internationa Pending Impleme IBRD / 89240 Post 150,000.00 0.00 2021-07-01 2021-07-22 2021-09-04 2021-10-04 2021-11-08 2022-05-07 dding documents (Lot 1) for t structure cation Selection l ntation he Upgrading of selected criti cal secondary or tertiary urb an sub-catchment areas MPWTC-WB-SCSRP-CMP1-00 5 / Consulting Services for th Improving the Drainage Infra Quality And Cost- Open - Internationa Pending Impleme e supervision of works (Lot 2) IBRD / 89240 Post 150,000.00 0.00 2020-01-01 2020-01-22 2020-03-06 2020-04-03 2020-05-03 2020-06-07 2020-07-12 2021-07-12 structure Based Selection l ntation for the Upgrading of selected critical secondary or tertiary urban sub-catchment areas SR-MP-195204-CS-LCS / Exte Supporting Project Managem Least Cost Selecti IBRD / 89240 Post Open - National 90,000.00 40,466.51 Signed 2020-09-18 2020-09-27 2020-10-09 2020-11-22 2020-10-01 2020-12-20 2020-10-30 2021-01-19 2021-05-17 2021-02-23 2021-05-29 2021-03-30 2021-07-01 2021-09-26 rnal Auditing ent and Implementation on SR-MP-268589-CS-LCS / Impl Supporting Project Managem Least Cost Selecti IBRD / 89240 Post Open - National 200,000.00 0.00 Canceled 2021-12-14 2022-01-04 2022-02-17 2022-03-17 2022-04-16 2022-05-21 2022-06-25 2022-12-22 ementation Support SCSRP ent and Implementation on INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MPWTC-WB-SCSRP-CMP4-00 Supporting Project Managem Individual Consult 2 / Individual experts for PIU IBRD / 89240 Prior Open 180,000.00 0.00 Canceled 2019-01-01 2019-08-01 2019-02-19 2019-03-12 2019-04-16 2019-10-13 ent and Implementation ant Selection or specific support: Procurem ent Specialist MPWTC-WB-SCSRP-CMP4-00 3 / Individual experts for PIU Supporting Project Managem Individual Consult IBRD / 89240 Post Open 336,000.00 0.00 Canceled 2019-06-01 2020-12-03 2019-07-20 2019-08-10 2019-09-14 2020-03-12 or specific support: Hydraulic ent and Implementation ant Selection Engineer (national/internatio nal) MPWTC-WB-SCSRP-CMP4-00 4 / Individual experts for PIU Supporting Project Managem Individual Consult IBRD / 89240 Post Open 288,000.00 0.00 Canceled 2019-06-01 2019-07-20 2019-08-10 2019-09-14 2020-03-12 or specific support: Hydrome ent and Implementation ant Selection t/Flood model Engineer (nati onal/international) MPWTC-WB-SCSRP-CMP4-00 5 / Individual experts for PIU Supporting Project Managem Individual Consult IBRD / 89240 Post Open 180,000.00 0.00 Under Review 2019-08-01 2021-11-30 2019-09-19 2019-10-10 2019-11-14 2020-05-12 or specific support: Financial ent and Implementation ant Selection Management Specialist MPWTC-WB-SCSRP-CMP4-00 7 / Individual experts for PIU Supporting Project Managem Individual Consult IBRD / 89240 Post Open 48,000.00 0.00 Canceled 2019-05-01 2020-12-03 2019-06-19 2019-07-10 2019-08-14 2020-02-10 or specific support: Communi ent and Implementation ant Selection cation and Social Specialist MPWTC-WB-SCSRP-CMP4-00 Supporting Project Managem Individual Consult 8 / Individual experts for PIU IBRD / 89240 Post Open 48,000.00 0.00 Canceled 2020-03-01 2020-12-03 2020-04-19 2020-05-10 2020-06-14 2020-12-11 ent and Implementation ant Selection or specific support: Environm ent Specialist MPWTC-WB-SCSRP-CMP4-00 Supporting Project Managem Individual Consult 9 / Individual experts for PIU IBRD / 89240 Post Open 100,000.00 0.00 Canceled 2019-06-01 2019-07-21 2019-08-11 2019-09-15 2020-03-13 ent and Implementation ant Selection or specific support: ad-hoc sp ecialized support MPWTC-WB-SCSRP-CMP4-00 Supporting Project Managem Individual Consult 6 / Individual experts for PIU IBRD / 89240 Post Open 210,000.00 0.00 Canceled 2019-07-01 2019-08-19 2019-09-09 2019-10-14 2020-04-11 ent and Implementation ant Selection or specific support: deputy-pr oject coordinator SCSRP-WB-MPW-CMP04-020 Supporting Project Managem Individual Consult IBRD / 89240 Post Open 200,000.00 0.00 Canceled 2020-12-03 2020-12-07 2021-01-21 2022-04-14 2021-02-11 2021-03-18 2024-12-31 / Procurement Specialist SC ent and Implementation ant Selection U MPW\WB\SCSRP\CMP4-020 / Supporting Project Managem Under Implement Staffing of the SCU for the Sa IBRD / 89240 Prior Direct Selection Direct - National 1,200,000.00 0.00 2022-07-21 2022-10-31 2022-07-31 2022-10-04 2023-04-02 ent and Implementation ation ramacca Canal System Reha bilitation Project MPW\WB\SCSRP\CMP4-032 / Supporting Project Managem Individual Consult Under Implement Staffing of the Saramacca Ca IBRD / 89240 Post Open - National 40,000.00 0.00 2023-05-11 2023-05-08 2023-06-27 2023-07-18 2023-08-22 2024-08-21 ent and Implementation ant Selection ation nal Unit: Financial Manageme nt Specialist Page 3 Procurement Plan Project information: Federated States of Micronesia, Maritime Investment Project (P163922) Project Implementation agency: PPA-Department of Finance and Administration, Department of Transportation, Communication and Infrastructure Date of the Procurement Plan: January 31, 2018 Period covered by this Procurement Plan: February 1, 2018 to July 31, 2019 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the Procurement Code of 1988, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions: 1. The procurement is open to all eligible firms from any country; 2. The request for bids/request for proposals document shall require the Bidders/Proposers submitting Bids/Proposals present a signed acceptance at the time of bidding, to be incorporated in any resulting signed contracts, confirming application of, and compliance with, the Bank's Anti-Corruption Guidelines, including without limitation the Bank's right to sanction and the Bank's inspection and audit rights; 3. Publication of contract award information; 4. Rights for the Bank to review procurement documentation and activities; and 5. An effective complaints mechanism. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Not Applicable Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations: Not Applicable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Work) Goods: is not applicable; Works: is not applicable. PROCUREMENT Micronesia, Federated States of : Federated States of Micronesia Maritime Investment Project PLAN General Information Country: Micronesia, Federated States of 2019-08-06 Bank’s Approval Date of the Original Procurement Plan: 2023-06-06 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P163922 GPN Date: 2018-06-25 Project Name: Federated States of Micronesia Maritime Investment Project Loan / Credit No: IDA / D4500 Department of Transportation, Communications and Infrastructure Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual FM-PIU-MIP, DOTCI-133381- Maritime Safety and Securit Request for Quota Single Stage - One E GO-RFQ / Spill Kits and Conta IDA / D4500 Post Limited 50,000.00 0.00 Canceled 2021-10-08 2021-12-03 2022-06-01 y tions nvelope inment Boom FM-PIU-MIP, DOTCI-133382- Maritime Safety and Securit Open - Internationa Single Stage - One E GO-RFB / SAR Equipment and IDA / D4500 Prior Request for Bids 1,000,000.00 0.00 Canceled 2021-10-03 2021-10-08 2021-11-19 2021-12-19 2022-01-23 2022-01-26 y l nvelope Safety Devices FM-DOTCI-246746-GO-RFQ / Technical Assistance for Port Request for Quota Single Stage - One E IDA / D4500 Post Limited 15,000.00 0.00 Canceled 2021-08-09 2021-10-04 2022-04-02 High Speed Multi-Function Pri Planning and Project Manag tions nvelope nter ement NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual FM-PIU-MIP, DOTCI-126203- CS-CQS / Needs Assessment Technical Assistance for Port Consultant Qualifi Open - Internationa for component one (Maritime IDA / D4500 Planning and Project Manag Prior 500,000.00 337,792.90 Signed 2019-08-16 2019-08-27 2019-09-06 2019-09-11 2019-10-20 2019-11-18 2019-11-19 2020-09-29 2019-12-24 2020-12-16 2020-06-21 cation Selection l Infrastructure) and compone ement nt two (Maritime Safety and Security) activities. FM-PIU-MIP, DOTCI-133385- Technical Assistance for Port Consultant Qualifi Open - Internationa CS-CQS / Review of Institutio IDA / D4500 Planning and Project Manag Post 250,000.00 218,205.50 Signed 2020-06-01 2020-09-01 2020-06-22 2020-10-21 2020-08-05 2020-12-18 2020-09-04 2021-04-30 2020-10-09 2021-05-22 2021-04-07 cation Selection l nal and Governance Arrange ement ments FM-PIU-MIP, DOTCI-133387- Technical Assistance for Port Consultant Qualifi Open - Internationa IDA / D4500 Post 250,000.00 0.00 Canceled 2020-02-01 2020-02-22 2020-04-06 2020-05-06 2020-06-10 2020-12-07 CS-CQS / Chuuk Lagoon Acce Planning and Project Manag cation Selection l ss Study ement FM-PIU-MIP, DOTCI-133386- Technical Assistance for Port Quality And Cost- Open - Internationa CS-QCBS / Individual Ports St IDA / D4500 Planning and Project Manag Post 425,000.00 0.00 Canceled 2019-11-01 2019-11-22 2020-01-05 2020-02-02 2020-03-03 2020-04-07 2020-05-12 2021-05-12 Based Selection l rategic Development Plans ement FM-DOTCI-206001-CS-QCBS Technical Assistance for Port / Individual Ports Strategic D Quality And Cost- Open - Internationa IDA / D4500 Planning and Project Manag Prior 625,000.00 635,963.12 Signed 2020-12-07 2020-12-03 2021-01-22 2020-12-14 2021-02-26 2021-04-28 2021-04-09 2021-07-07 2021-05-09 2021-10-07 2021-06-13 2022-02-23 2021-07-18 2022-05-12 2022-07-18 evelopment Plans and Chuuk Based Selection l ement Lagoon Maritime Access FM-DOTCI-259098-CS-QCBS / Consultancy for the Design Technical Assistance for Port Quality And Cost- Open - Internationa Under Implement and Supervision of Safe, Effic IDA / D4500 Planning and Project Manag Prior 2,350,000.00 0.00 2021-11-02 2021-11-10 2021-11-23 2021-11-17 2022-01-06 2022-09-18 2022-02-03 2022-11-22 2022-03-05 2023-04-13 2022-04-09 2022-05-14 2023-05-14 Based Selection l ation ient and Climate Resilient Ma ement ritime Infrastructure in FSM FM-DOTCI-303022-CS-QCBS Maritime Safety and Securit Quality And Cost- Open - Internationa Under Implement / Gender Capacity Developm IDA / D4500 Prior 570,000.00 0.00 2022-09-30 2022-11-16 2022-10-21 2023-02-12 2022-12-04 2023-01-01 2023-01-31 2023-03-07 2023-04-11 2024-04-10 y Based Selection l ation ent and Training INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PPA-FMIP-03A / Project Mana Technical Assistance for Port Individual Consult IDA / D4500 Prior Open 200,000.00 679,250.00 Signed 2019-01-18 2019-01-18 2019-03-08 2019-05-23 2019-03-29 2019-08-08 2019-05-03 2019-08-23 2019-10-30 ger FMIP Project Planning and Project Manag ant Selection ement FM-PIU-MIP, DOTCI-154700- Technical Assistance for Port Individual Consult IDA / D4500 Post Limited 30,000.00 0.00 Canceled 2020-01-27 2020-01-30 2020-02-01 2020-02-15 2020-03-07 2020-04-12 CS-INDV / Project Officer - FM Planning and Project Manag ant Selection IP ement FM-PIU-MIP, DOTCI-155288- Technical Assistance for Port Individual Consult IDA / D4500 Post Limited 15,000.00 0.00 Canceled 2020-02-14 2020-01-30 2020-02-19 2020-03-04 2020-03-19 2021-03-19 CS-INDV / Project Assistant- F Planning and Project Manag ant Selection MIP ement FM-PIU-MIP, DOTCI-158290- Technical Assistance for Port Individual Consult IDA / D4500 Post Open 30,000.00 113,822.00 Signed 2020-02-11 2020-03-30 2020-02-29 2020-03-23 2020-03-02 2020-06-10 2020-03-13 2020-05-06 2021-03-13 CS-INDV / Project Officer- FMI Planning and Project Manag ant Selection P ement FM-PIU-MIP, DOTCI-158293- Technical Assistance for Port Individual Consult IDA / D4500 Post Open 15,000.00 35,146.00 Signed 2020-03-16 2020-05-14 2020-04-09 2020-11-02 2020-04-14 2020-11-02 2020-04-29 2020-11-07 2020-05-02 CS-INDV / Project Assistant-F Planning and Project Manag ant Selection MIP ement FM-PIU-MIP, DOTCI-133383- Technical Assistance for Port Individual Consult IDA / D4500 Post Limited 50,000.00 0.00 Canceled 2019-10-01 2019-10-06 2019-10-27 2019-12-01 2020-05-29 CS-INDV / GBV Needs Assess Planning and Project Manag ant Selection ment ement Page 1 FM-PIU-MIP, DOTCI-133389- Technical Assistance for Port Individual Consult CS-INDV / Women's Employm IDA / D4500 Planning and Project Manag Post Open 50,000.00 0.00 Canceled 2021-07-25 2021-08-01 2021-09-12 2021-10-03 2021-11-07 2022-05-06 ant Selection ent Specialist ement FM-DOTCI-282140-CS-INDV / Maritime Safety and Securit Individual Consult Under Implement Ports Spill Prevention and Mit IDA / D4500 Post Open 50,000.00 0.00 2022-04-18 2022-06-23 2022-06-06 2023-04-24 2022-06-27 2022-08-01 2023-01-28 y ant Selection ation igation Needs Assessment FM-DOTCI-282142-CS-INDV / Maritime Safety and Securit Individual Consult Under Implement IDA / D4500 Post Open 100,000.00 0.00 2022-05-02 2022-08-11 2022-06-20 2023-05-16 2022-07-11 2022-08-15 2023-02-11 Search and Rescue Needs As y ant Selection ation sessment FM-DOTCI-363283-CS-INDV / Technical Assistance for Port Individual Consult Open - Internationa Pending Impleme Transport Infrastructure Impl IDA / D4500 Planning and Project Manag Prior 200,000.00 0.00 2023-06-06 2023-07-22 2023-08-05 2023-08-31 2024-08-30 ant Selection l ntation ementation Advisor ement FM-DOTCI-364891-CS-CDS / Technical Assistance for Port Under Implement IDA / D4500 Post Direct Selection Direct - National 60,000.00 0.00 2023-06-02 2023-06-07 2023-06-12 2023-06-12 2023-08-16 2024-08-15 Project Administrator FSMIP Planning and Project Manag ation ement Page 2 PROCUREMENT PLAN (Textual Part) Project information: Pakistan Punjab Human Capital Investment Project (HCIP) P164785 Project Implementation agency: (i) Punjab Social Protection Authority; (ii) Secondary Education Department and; (iii) Punjab Health Facilities Management Company (PHFMC) Date of the Procurement Plan: July 22, 2020 Period covered by this Procurement Plan: July 2020- December 2021 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016, Revised November 2017 and August 2018) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in Public Procurement Rules 2004 Revised 2020, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions: 1) The eligibility of bidders shall be as defined under Section III of the Procurement Regulations. Accordingly, no bidder or potential bidder shall be declared ineligible for contracts financed by the Bank for reasons other than those provided in Section III of the Procurement Regulations. 2) For national open competitive procurement, only the model procurement documents acceptable to the World Bank, shall be used. 3) The request for bids/request for proposals document shall require that Bidders/Proposers submitting Bids/Proposals present a signed acceptance (in the form attached) at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights. 4) Procurement Documents include provisions, as agreed with the Bank, intended to adequately mitigate against environmental, social (including sexual exploitation and abuse and gender-based violence), health and safety (“ESHS”) risks and impacts 5) Access to procurement opportunities shall not be restricted to firms that have pre-registered and/or paid a registration fee. 6) No preference of any kind shall be given to national bidders in the bidding process. 7) Procurement methods that use two-envelope process and rated criteria shall be subject to Bank’s prior concurrence When other national procurement arrangements (other than national open competitive procurement) are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed Letter of Acceptance of the World Bank’s Anticorruption Guidelines and Sanctions Framework1 Date: Invitation of Bids/Proposals No.__________ To: ___________________________________________________________________________ We, along with our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not) consultants and personnel, acknowledge and agree to abide by the World Bank’s policy regarding Fraud and Corruption (corrupt, fraudulent, collusive, coercive, and obstructive practices), as set out and defined in the World Bank’s Anti-Corruption Guidelines2 in connection with the procurement and execution of the contract (in case of award), including any amendments thereto. We declare and warrant that we, along our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not), consultants and personnel, are not subject to, and are not controlled by any entity or individual that is subject to, a temporary suspension, early temporary suspension, or debarment imposed by a member of the World Bank Group, including, inter alia, a cross-debarment imposed by the World Bank Group as agreed with other international financial institutions (including multilateral development banks), or through the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement. Further, we are not ineligible under the laws or official regulations of [Insert name of Employer as per bidding document] or pursuant to a decision of the United Nations Security Council. We confirm our understanding of the consequences of not complying with the World Bank’s Anti-Corruption Guidelines, which may include the following: a. rejection of our Proposal/Bid for award of contract; 1[Drafting note: This document shall be signed by bidders/proposers/consultants and submitted as part of their bids/proposals. In addition, this document shall be signed by the winning bidder/consultant and incorporated as part of the contract.] 2Guidelines on Preventing and Combating Fraud and Corruption in Projects Financed by International Bank for Reconstruction and Development Loans and the International Development Agency Credits and Grants, dated October 15, 2006, and revised in January 2011 and July 2016, as they may be revised from time to time. b. in the case of award, termination of the contract, without prejudice to any other remedy for breach of contract; and c. sanctions, pursuant to the Bank’s Anti-Corruption Guidelines and in accordance with its prevailing sanctions policies and procedures as set forth in the Bank’s Sanctions Framework. This may include a public declaration of ineligibility, either indefinitely or for a stated period of time, (i) to be awarded or otherwise benefit from a Bank-financed contract, financially or in any other manner;3 (ii) to be a nominated4 sub-contractor, sub-consultant, consultant, manufacturer or supplier, or service provider of an otherwise eligible firm being awarded a Bank-financed contract; and (iii) to receive the proceeds of any loan made by the Bank or otherwise to participate further in the preparation or implementation of any Bank- financed project. We understand that we may be declared ineligible as set out above upon: a. completion of World Bank Group sanctions proceedings according to its prevailing sanctions procedures; b. cross-debarment as agreed with other international financial institutions (including multilateral development banks); c. the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement; or d. temporary suspension or early temporary suspension in connection with an ongoing World Bank Group sanctions proceeding. For avoidance of doubt, the foregoing effects of ineligibility do not extend to a sanctioned firm’s or individual’s execution of its ongoing Bank-financed contracts (or its ongoing sub-agreements under such contracts) that are not the subject of a material modification, as determined by the Bank. We shall permit, and shall cause our sub-contractors, sub-consultants, agents (whether declared or not), personnel, consultants, service providers or suppliers, to permit the Bank to inspect5 all accounts, records, and other documents relating to 3 For the avoidance of doubt, a sanctioned party’s ineligibility to be awarded a contract shall include, without limitation, (i) applying for pre-qualification or initial selection), expressing interest in a consultancy, and bidding, either directly or as a nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider, in respect of such contract, and (ii) entering into an addendum or amendment introducing a material modification to any existing contract. 4A nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider (different names are used depending on the bidding document) is one which has been: (i) included by the bidder in its pre-qualification or initial selection application or bid because it brings specific and critical experience and know-how that allow the bidder to meet the qualification requirements for the particular bid; or (ii) appointed by the Borrower. 5Inspections in this context are usually investigative (i.e., forensic) in nature: they involve fact- finding activities undertaken by the Bank or persons appointed by the Bank to address specific the procurement process and/or contract execution (in the case of award), and to have them audited by auditors appointed by the Bank. We agree to preserve all accounts, records, and other documents (whether in hard copy or electronic format) related to the procurement and execution of the contract. Name of the Bidder/Proposer/Consultant: Name of the person duly authorized to sign the Bid/Proposal on behalf of the Bidder/Proposer/ Consultant: Title of the person signing the Letter: matters related to investigations/audits, such as evaluating the veracity of an allegation of possible Fraud and Corruption, through the appropriate mechanisms. Such activity includes but is not limited to accessing and examining a firm's or individual's financial records and information, and making copies thereof as relevant; accessing and examining any other documents, data, and information (whether in hard copy or electronic format) deemed relevant for the investigation/audit, and making copies thereof as relevant; interviewing staff and other relevant individuals; performing physical inspections and site visits; and obtaining third-party verification of information. PROCUREMENT Pakistan : Punjab Human Capital Investment Project PLAN General Information Country: Pakistan 2020-07-29 Bank’s Approval Date of the Original Procurement Plan: 2023-06-05 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P164785 GPN Date: 2020-06-25 Project Name: Punjab Human Capital Investment Project Loan / Credit No: IDA / 65480 School Education Department Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PK-SED-185833-GO-RFB / Fo Economic and social inclusio Single Stage - One E r Arranging of Book Shelves i IDA / 65480 Post Request for Bids Open - National 1,648,484.00 0.00 Canceled 2021-04-21 2021-04-23 2021-04-26 2021-04-23 2021-06-07 2021-05-25 2021-07-07 2021-08-11 2022-02-07 n nvelope n Selected Schools PK-SED-185834-GO-RFB / Pr Economic and social inclusio Single Stage - One E IDA / 65480 Post Request for Bids Open - National 2,060,606.00 0.00 Canceled 2021-08-22 2021-08-27 2021-10-08 2021-11-07 2021-12-12 2022-02-20 ocurement of Books for Read n nvelope ing Corners PK-SED-185832-GO-RFB / Pr Economic and social inclusio Single Stage - One E IDA / 65480 Post Request for Bids Open - National 412,121.00 0.00 Canceled 2021-01-12 2021-01-17 2021-02-28 2021-03-30 2021-05-04 2021-10-31 ocurement of Tablets for ECE n nvelope teachers PK-SED-185836-GO-RFQ / Pri Economic and social inclusio Request for Quota Single Stage - One E Pending Impl IDA / 65480 Post Open - National 51,515.00 0.00 2021-04-26 2021-06-24 2021-12-21 nting of Revised ECE Teacher n tions nvelope ementation 's Guide PK-SED-185838-GO-RFB / Pr Economic and social inclusio Request for Quota ocurement of Smart Boards o IDA / 65480 Post 90,909.00 0.00 Canceled 2024-01-20 2024-03-10 2024-10-26 n tions r Pilot Purposes PK-SED-224026-GO-RFQ / Pr Economic and social inclusio Request for Quota Single Stage - One E ocurement of Laptops, Printe IDA / 65480 Post Limited 24,714.00 27,985.44 Signed 2021-03-15 2021-04-08 2021-03-28 2021-05-21 2022-03-28 n tions nvelope rs, Scanner etc. PK-SED-224032-GO-RFQ / Pr Economic and social inclusio Request for Quota Single Stage - One E IDA / 65480 Post Limited 36,445.00 20,296.06 Signed 2021-03-24 2021-06-03 2021-04-20 2021-07-24 2022-04-20 ocurement of Office Furniture n tions nvelope PK-SED-238935-GO-RFB / Pr ocurement of Age-appropriat Economic and social inclusio Single Stage - One E IDA / 65480 Prior Request for Bids Open - National 5,084,716.00 0.00 Canceled 2021-07-01 2021-11-30 2021-07-06 2021-12-01 2021-08-17 2022-01-10 2021-09-16 2021-10-21 2022-04-19 e Furniture and Book Shelves n nvelope for 3400 Schools PK-SED-249103-GO-RFB / Pr Economic and social inclusio Single Stage - One E IDA / 65480 Post Request for Bids Open - National 1,275,000.00 1,160,728.09 Signed 2021-09-10 2021-09-12 2021-09-15 2021-09-16 2021-10-21 2021-10-21 2021-11-11 2021-11-04 2021-12-07 2021-11-30 2022-06-28 ocurement of ECE Kits for sc n nvelope hools PK-SED-255162-GO-RFB / Pr Economic and social inclusio Single Stage - One E IDA / 65480 Post Request for Bids Open - National 1,125,000.00 0.00 Canceled 2021-10-06 2021-10-08 2021-10-11 2021-10-12 2021-11-16 2021-11-30 2021-12-28 2022-06-26 ocurement of Tablets n nvelope PK-SED-265130-GO-RFB / Pr Economic and social inclusio Single Stage - One E Under Imple ocurement of Books (SRM) fo IDA / 65480 Prior Request for Bids Open - National 4,250,000.00 0.00 2021-12-31 2022-03-08 2022-01-05 2022-03-09 2022-02-16 2022-03-18 2022-04-22 2022-10-19 n nvelope mentation r Reading Corners in ECE and Grade 1-3 PK-SED-266093-GO-RFB / Pr Economic and social inclusio Single Stage - One E IDA / 65480 Post Request for Bids Open - National 1,125,000.00 968,193.33 Signed 2021-12-10 2021-12-15 2021-12-15 2021-12-20 2022-01-20 2022-01-19 2022-02-03 2022-02-14 2022-03-03 2022-04-01 2022-06-30 ocurement of Tablets n nvelope PK-SED-282842-GO-RFB / Pr ocurement of Age-Appropriat Economic and social inclusio Single Stage - One E Under Imple IDA / 65480 Prior Request for Bids Open - National 4,750,000.00 0.00 2022-03-21 2022-10-20 2022-03-26 2022-10-21 2022-05-01 2022-12-12 2022-05-22 2023-02-23 2022-06-26 2022-12-23 e Classroom Furniture, Learni n nvelope mentation ng and Reading Corner Shelv es PK-SED-309382-GO-RFQ / Pri Economic and social inclusio Request for Quota Single Stage - One E Under Imple nting of Information Educatio IDA / 65480 Post Open - National 64,000.00 0.00 2022-08-19 2022-08-25 2022-09-13 2022-12-12 n tions nvelope mentation n & Communication (IEC) Mat erial PK-SED-311287-GO-RFB / Pr Economic and social inclusio Single Stage - One E Under Imple IDA / 65480 Post Request for Bids Open - National 950,000.00 0.00 2022-08-30 2022-11-15 2022-09-04 2022-11-16 2022-10-04 2022-12-15 2022-10-25 2022-11-15 2023-05-14 ocurement of Tablets n nvelope mentation PK-SED-332013-GO-RFQ / Pri Economic and social inclusio Request for Quota Single Stage - One E Pending Impl nting Contract under Framew IDA / 65480 Post Limited 100,000.00 0.00 2022-12-26 2023-01-21 2024-07-14 n tions nvelope ementation ork Agreement PK-SED-360557-GO-RFB / Pr Economic and social inclusio Open - Internationa Single Stage - One E Under Imple ocurement of Books (RSM) Fo IDA / 65480 Prior Request for Bids 4,250,000.00 0.00 2023-05-12 2023-05-29 2023-05-17 2023-06-30 2023-07-30 2023-09-03 2024-03-01 n l nvelope mentation r Reading Corners in ECE and Grade 1-3 PK-SED-365614-GO-DIR / Pro Economic and social inclusio Direct - Internation Pending Impl IDA / 65480 Post Direct Selection 1,000,000.00 0.00 2023-06-18 2023-06-23 2023-07-31 2024-01-27 curement of 3900 Tablets for n al ementation PHCIP NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PK-SED-325351-NC-RFB / So Economic and social inclusio Single Stage - One E Under Imple cial Mobilization Firm to Cond IDA / 65480 Post Request for Bids Open - National 480,000.00 0.00 2022-11-21 2022-11-18 2022-11-26 2022-11-28 2022-12-20 2022-12-23 2022-12-30 2023-03-24 2023-01-27 2023-07-26 n nvelope mentation uct Community Awareness S essions CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Page 1 Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PK-SED-185825-CS-CQS / Hir Economic and social inclusio Consultant Qualifi Pending Impleme ing of Media Firm to Develop IDA / 65480 Post Open - National 90,909.00 0.00 2020-12-06 2020-12-27 2021-02-09 2021-03-11 2021-04-15 2021-06-24 n cation Selection ntation Video Contents/Strategies PK-SED-185823-CS-CQS / TA for Content Development of Economic and social inclusio Quality And Cost- Open - Internationa IDA / 65480 Post 848,484.00 0.00 Canceled 2020-09-16 2020-09-19 2020-10-13 2020-11-15 2020-11-20 2020-12-23 2021-01-09 2021-04-19 Teacher's Guide, Lesson Plan n Based Selection l and Children Activity Book PK-SED-185824-CS-CQS / Hir ing of Technical Assistance t Economic and social inclusio Quality And Cost- Open - Internationa IDA / 65480 Post 727,272.00 0.00 Canceled 2020-09-27 2020-09-30 2020-10-24 2020-11-26 2020-12-06 2020-12-21 2021-01-14 2023-10-11 o Develop Training Modules a n Based Selection l nd Train Master Trainers PK-SED-191207-CS-QCBS / H iring of Technical Assistance Economic and social inclusio Quality And Cost- Open - Internationa IDA / 65480 Post 969,696.00 0.00 Canceled 2020-09-27 2021-06-25 2020-09-30 2021-08-25 2020-10-24 2021-11-16 2020-11-25 2021-12-21 2020-12-05 2020-12-22 2021-01-08 2023-10-05 Firm to Develop Training Mod n Based Selection l ules and Train Master Trainer s PK-SED-191211-CS-QCBS / H iring of Technical Assistance Economic and social inclusio Quality And Cost- Open - Internationa for Content Development of IDA / 65480 Post 875,000.00 0.00 Canceled 2020-09-27 2021-06-25 2020-09-30 2021-07-29 2020-11-02 2021-10-11 2020-12-04 2021-11-11 2020-12-14 2021-11-22 2020-12-29 2021-12-10 2021-01-15 2023-10-12 n Based Selection l Teacher's Guide, Lesson Plan and Children Activity Book PK-SED-191213-CS-QCBS / H iring of Technical Assistance Economic and social inclusio Quality And Cost- Open - Internationa IDA / 65480 Post 969,696.00 0.00 Canceled 2020-09-27 2020-09-30 2020-10-24 2020-11-25 2020-12-05 2020-12-22 2021-01-08 2023-10-05 for Content Development of n Based Selection l Digital Interactive Content PK-SED-191217-CS-QCBS / T echnical Assistance for Devel Economic and social inclusio Quality And Cost- Open - Internationa IDA / 65480 Post 969,696.00 0.00 Canceled 2020-09-27 2020-09-30 2020-10-24 2020-11-25 2020-12-05 2020-12-22 2021-01-08 2023-10-05 opment of Student Tracking n Based Selection l Application, Pilot and Trouble Shooting PK-SED-185814-CS-CQS / Hir Economic and social inclusio Consultant Qualifi IDA / 65480 Post Open - National 258,715.00 238,529.13 Signed 2020-08-16 2021-03-05 2020-09-06 2021-03-22 2020-09-26 2021-07-02 2020-10-03 2021-07-23 2020-10-09 2021-09-01 2021-04-07 ing of Firm for Baseline Surve n cation Selection y PK-SED-241917-CS-QCBS / H iring of Technical Assistance Economic and social inclusio Quality And Cost- Open - Internationa Firm to Develop Training Mod IDA / 65480 Post 776,146.00 0.00 Canceled 2021-06-29 2021-06-25 2021-07-02 2021-08-25 2021-07-26 2021-11-08 2021-08-27 2021-12-13 2021-09-06 2021-09-23 2021-10-10 2022-04-08 n Based Selection l ules and Train Master Trainer s (Early Years Trainings) PK-SED-311283-CS-CQS / Hir ing of Firm for Development Economic and social inclusio Consultant Qualifi IDA / 65480 Post Open - National 103,438.00 0.00 Signed 2022-08-25 2022-08-24 2022-09-15 2022-09-14 2022-10-06 2022-11-15 2022-10-13 2022-12-15 2022-11-10 2023-05-09 of Content and Impart Trainin n cation Selection g of Lead Trainers and Social Mobilizers PK-SED-317974-CS-QCBS / H IRING OF CONSULTING SERVI Economic and social inclusio Quality And Cost- CES FOR CONTENT DEVELOP IDA / 65480 Post Open - National 350,000.00 0.00 Signed 2022-09-30 2022-09-27 2022-10-21 2022-10-06 2022-11-19 2022-11-15 2022-12-17 2022-12-06 2022-12-31 2022-12-06 2023-01-28 2023-03-06 2023-03-04 2024-03-03 n Based Selection MENT FOR ECCE TEACHING A ND LEARNING MATERIALS PK-SED-319304-CS-CQS / Hir Economic and social inclusio Consultant Qualifi Under Implement IDA / 65480 Post Open - National 80,000.00 0.00 2022-10-10 2022-12-06 2022-10-31 2022-12-30 2022-11-29 2022-12-20 2023-01-24 2023-07-23 ing of Media Firm n cation Selection ation PK-SED-326070-CS-QCBS / P ROCUREMENT OF CONSULTI NG SERVICES FOR DEVELOP MENT OF HEAD TEACHERS’, Economic and social inclusio Quality And Cost- Under Implement IDA / 65480 Post Open - National 375,000.00 0.00 2022-11-15 2022-11-11 2022-12-06 2022-12-30 2023-01-09 2023-02-06 2023-02-07 2023-03-03 2023-03-31 2023-07-29 ASSISTANT EDUCATION OFFI n Based Selection ation CERS’ (AEOs), AND SCHOOL COUNCIL (SC) MEMBERS’ TR AINING MODULES AND TRAIN ING OF MASTER TRAINERS PK-SED-326069-CS-QCBS / P ROCUREMENT OF CONSULTI NG SERVICES FOR DEVELOP Economic and social inclusio Quality And Cost- Under Implement IDA / 65480 Post Open - National 625,000.00 0.00 2022-11-15 2022-11-14 2022-12-06 2022-12-30 2022-12-30 2023-01-27 2023-02-10 2023-03-10 2023-04-03 2023-09-30 MENT OF ECCE, GRADE 1,2 & n Based Selection ation 3 TEACHERS AND CAREGIVE RS’ TRAINING MODULES AND TRAINING OF MASTER TRAIN ERS INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PK-SED-185809-CS-INDV / Hi Economic and social inclusio Individual Consult ring of Monitoring & Evaluati IDA / 65480 Post Open 111,384.00 3,074.06 Signed 2021-07-01 2020-09-02 2021-07-30 2020-12-21 2021-08-04 2020-12-21 2021-08-10 2020-12-25 2025-08-09 n ant Selection on Specialist PK-SED-185807-CS-INDV / Hi Economic and social inclusio Individual Consult IDA / 65480 Post Open 133,333.00 3,095.84 Completed 2020-08-10 2020-09-02 2020-09-08 2020-12-21 2020-09-13 2020-12-21 2020-09-18 2020-12-25 2025-07-17 2021-07-31 ring of Procurement Specialis n ant Selection t PK-SED-185552-CS-INDV / Hi Economic and social inclusio Individual Consult ring of Financial Managemen IDA / 65480 Post Open 133,333.00 3,333.99 Terminated 2020-10-01 2020-09-02 2020-10-29 2020-12-21 2020-11-03 2020-12-21 2020-11-09 2021-01-05 2025-06-26 n ant Selection t Specialist PK-SED-190129-CS-INDV / Hi ring of Programme Manager f Economic and social inclusio Individual Consult IDA / 65480 Post Open 218,181.00 220,693.19 Completed 2020-08-28 2020-09-02 2020-09-25 2020-12-21 2020-09-30 2020-12-21 2020-10-05 2021-01-26 2025-09-09 2021-04-01 or Foundation Learning Cell u n ant Selection nder PHCIP of SED Compone nt PK-SED-190131-CS-INDV / Hi Economic and social inclusio Individual Consult ring of Education Specialist u IDA / 65480 Post Open 160,000.00 3,086.36 Signed 2020-08-28 2020-09-02 2020-09-25 2020-12-21 2020-09-30 2020-12-21 2020-10-05 2020-12-26 2025-09-09 n ant Selection nder PHCIP SED Component PK-SED-190132-CS-INDV / Hi Economic and social inclusio Individual Consult ring of ECE Curriculum Speci IDA / 65480 Post Open 160,000.00 3,086.36 Signed 2020-08-28 2020-09-02 2020-09-25 2020-12-21 2020-09-30 2020-12-21 2020-10-05 2021-01-12 2025-06-01 n ant Selection alist for PHCIP SED Compone nt PK-SED-190138-CS-INDV / Hi Economic and social inclusio Individual Consult ring of ECE Planning Specialis IDA / 65480 Post Open 130,909.00 3,086.36 Terminated 2021-04-18 2020-09-02 2021-05-16 2020-12-21 2021-05-21 2020-12-21 2021-05-26 2020-12-27 2025-07-04 n ant Selection t under PHCIP SED Compone nt Page 2 PK-SED-190188-CS-INDV / Hi Economic and social inclusio Individual Consult ring of Contract Management IDA / 65480 Post Open 160,000.00 3,333.99 Terminated 2020-08-31 2020-09-02 2020-09-28 2020-12-21 2020-10-05 2020-12-21 2020-10-10 2020-12-25 2025-06-06 n ant Selection Specialist PK-SED-190187-CS-INDV / Hi Economic and social inclusio Individual Consult ring of Database Analyst for IDA / 65480 Post Open 100,000.00 0.00 Canceled 2021-04-22 2020-09-02 2021-05-20 2021-05-25 2021-05-30 2025-05-29 n ant Selection PHCIP SED Component PK-SED-190134-CS-INDV / Hi Economic and social inclusio Individual Consult ring of Social Mobilization Sp IDA / 65480 Post Open 160,000.00 0.00 Canceled 2020-08-28 2020-09-02 2020-09-07 2020-09-12 2020-09-17 2025-07-03 n ant Selection ecialist under PHCIP SED Co mponent PK-SED-220127-CS-INDV / Hi Economic and social inclusio Individual Consult ring of Social Mobilization Sp IDA / 65480 Post Open 160,000.00 2,864.24 Signed 2021-02-17 2021-02-19 2021-04-07 2021-07-28 2021-04-28 2021-07-28 2021-06-02 2021-08-20 2025-06-30 n ant Selection ecialist under PHCIP SED Co mponent PK-SED-220135-CS-INDV / Hi Economic and social inclusio Individual Consult ring of Database Analyst for IDA / 65480 Post Open 100,000.00 0.00 Canceled 2021-02-17 2021-02-19 2021-04-07 2021-07-28 2021-04-28 2021-06-02 2025-06-30 n ant Selection PHCIP SED Component PK-SED-251208-CS-INDV / Hi Economic and social inclusio Individual Consult Under Implement IDA / 65480 Post Open 186,336.00 0.00 2021-09-10 2021-09-06 2021-10-21 2021-10-23 2021-11-13 2025-06-11 ring of Procurement Specialis n ant Selection ation t PK-SED-228608-CS-INDV / Hi ring of Programme Manager f Economic and social inclusio Individual Consult IDA / 65480 Post Open 208,268.00 0.00 Canceled 2021-04-12 2021-05-19 2021-05-27 2021-06-01 2021-06-06 2025-06-30 or Foundation Learning Cell u n ant Selection nder PHCIP of SED Compone nt PK-SED-265127-CS-INDV / Hi Economic and social inclusio Individual Consult ring of Programme Manager f IDA / 65480 Post Open 130,840.00 35,849.08 Signed 2021-12-06 2021-12-02 2022-01-24 2022-03-24 2022-02-14 2022-03-24 2022-03-21 2022-03-29 2025-06-30 n ant Selection or Foundation Learning Cell ( PHCIP - PMIU) PK-SED-299480-CS-INDV / Hi Economic and social inclusio Individual Consult Under Implement ring of Assistant Planning Sp IDA / 65480 Post Open 80,096.00 0.00 2022-06-30 2022-07-19 2022-08-04 2022-08-19 2022-09-17 2025-06-30 n ant Selection ation ecialist for PHCIP-SED PK-SED-301701-CS-INDV / Hi Economic and social inclusio Individual Consult ring of Financial Managemen IDA / 65480 Post Open 80,096.00 0.00 Signed 2022-06-30 2022-07-27 2022-08-04 2022-09-01 2022-08-19 2022-09-03 2022-09-17 2025-06-30 n ant Selection t Specialist for PHCIP-SED PK-SED-301712-CS-INDV / Hi Economic and social inclusio Individual Consult ring of Contract Management IDA / 65480 Post Open 80,096.00 0.00 Canceled 2022-06-30 2022-07-19 2022-08-04 2022-08-19 2022-09-17 2025-06-30 n ant Selection Specialist for PHCIP-SED PK-SED-312543-CS-INDV / Ci Economic and social inclusio Individual Consult Under Implement IDA / 65480 Post Direct - National 9,000.00 0.00 2022-08-29 2022-09-09 2022-09-02 2022-09-09 2022-09-23 2023-03-22 vil Engineer n ant Selection ation PK-SED-319303-CS-INDV / Pr Economic and social inclusio Individual Consult Under Implement IDA / 65480 Post Limited 90,000.00 0.00 2022-10-04 2022-10-04 2022-10-09 2022-10-05 2022-10-16 2022-10-30 2023-10-25 ocurement Management Spe n ant Selection ation cialist PK-SED-320082-CS-INDV / In Economic and social inclusio Individual Consult IDA / 65480 Post Open - National 9,000.00 0.00 Canceled 2022-10-11 2022-11-14 2022-11-06 2022-11-13 2022-11-27 2023-05-26 ternal Auditor n ant Selection PK-SED-327984-CS-INDV / Hi Economic and social inclusio Individual Consult Under Implement ring of Environment Officer S IDA / 65480 Post Limited 9,000.00 0.00 2022-11-25 2022-11-30 2022-11-30 2022-12-07 2023-01-11 2023-07-10 n ant Selection ation ervices for Short term PK-SED-328839-CS-INDV / Ri Economic and social inclusio Individual Consult IDA / 65480 Post Open - National 9,000.00 0.00 Canceled 2022-11-30 2022-11-28 2022-12-19 2022-12-26 2023-01-16 2023-07-15 sk & Compliance Officer n ant Selection PK-SED-333026-CS-INDV / Hi Economic and social inclusio Individual Consult Under Implement ring of Individual Consultant f IDA / 65480 Post Limited 5,400.00 0.00 2022-12-23 2022-12-22 2022-12-28 2023-01-02 2023-01-16 2023-07-15 n ant Selection ation or short term ( for 3 months period only) PK-SED-336412-CS-INDV / Hi Economic and social inclusio Individual Consult IDA / 65480 Post Open - National 75,000.00 0.00 Signed 2023-01-20 2023-01-19 2023-02-15 2023-03-01 2023-02-25 2023-03-01 2023-03-14 2025-06-30 ring of Program Manager n ant Selection PK-SED-338532-CS-INDV / Hi Economic and social inclusio Individual Consult Under Implement ring of Procurement manage IDA / 65480 Prior Open - National 80,000.00 0.00 2023-01-31 2023-02-15 2023-03-01 2023-03-08 2023-03-25 2025-06-30 n ant Selection ation ment Specialist PK-SED-344106-CS-INDV / Hi Economic and social inclusio Individual Consult Under Implement IDA / 65480 Post Open - National 80,000.00 0.00 2023-02-23 2023-02-22 2023-04-13 2023-03-29 2023-05-04 2023-03-30 2023-06-08 2025-06-30 ring of Financial Managemen n ant Selection ation t specialist PK-SED-347963-CS-INDV / Hi Economic and social inclusio Individual Consult Under Implement ring of ECE Planning Specialis IDA / 65480 Post Open - National 78,546.00 0.00 2023-03-08 2023-03-13 2023-04-05 2023-04-10 2023-04-15 2025-06-30 n ant Selection ation t under PHCIP SED Compone nt PK-SED-364085-CS-INDV / Hi Economic and social inclusio Individual Consult ring of Procurement Manage IDA / 65480 Prior Open - National 80,000.00 0.00 Canceled 2023-05-30 2023-07-18 2023-08-08 2023-09-12 2024-03-10 n ant Selection ment Specialist PK-SED-364894-CS-INDV / Hi Economic and social inclusio Individual Consult ring of Procurement Manage IDA / 65480 Prior Limited 50,000.00 0.00 Under Review 2023-06-02 2023-06-13 2023-06-07 2023-06-15 2023-06-28 2023-08-02 2024-01-29 n ant Selection ment Specialist Page 3 PROCUREMENT PLAN (Textual Part) Project information: Country: Nigeria Project Name: Multi-Sectoral Crisis Recovery Project for North East Nigeria (MCRP) P- Number: P157891 Project Implementation Agency: MCRP PCU (Federal and States) Date of the Procurement Plan: Updated -December 22, 2017. Period covered by this Procurement Plan: From 01/12/2018 – 30/06/2019. Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the FGN Public Procurement Act 2007; such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. “Not Applicable” THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables. “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Specify for each: Goods: is not applicable for those contracts identified in the Procurement Plan tables; Works: is not applicable for those contracts identified in the Procurement Plan tables. Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations is Applicable. Other Relevant Procurement Information. 1. Prior Review Threshold for Goods, Works and Non-Consulting Services: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Prior Review Procurement Method Threshold (US$ Comments equivalent) ICB and LIB (Goods and services other than ≥ 5,000,000 ALL consultancy services) NCB (Goods, IT Systems and Non Consulting Services 100,000 < 5,000,000 NONE (NCB) ICB (Works) ≥ 20,000,000 ALL NCB (Works) 150,000 < 20,000,000 NONE Shopping-Goods ≤ 100,000 NONE Shopping-Works ≤ 150,000 NONE Based on Annual Training, Workshops, Study All Values Work Plans & Tours Budgets 2. Prequalification: Bidders for major works shall be prequalified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines, although it is not expected that there will be need for prequalification in the procurement arrangements for the MCRP. MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 2 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT 3. Proposed Procedures for CDD Components (as per paragraph. 6.52 of the Procurement Regulations): Shall apply. 4. Reference to the Project Implementation Manual: Shall apply. 5. Any Other Special Procurement Arrangements: Not Applicable 6. Procurement Packages (Goods and Works) indicating Bank’s Prior and Post Review. MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 3 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT a. Summary of Procurement of Goods: 1 2 3 4 5 6 Review by Estimated Ref. Packag Bank Commen Description Cost (US$ No. es (Prior / ts Million) Post) Total NCB 12.82 43 Post (Goods) Total RfQ (Goods/Non 0.04 1 Post Consulting Services) Procurement of Goods with Selection Methods and Time Schedule (Please see Annex I). b. Summary of Procurement of Civil Works 1 2 3 4 5 6 Review by Estimated Ref. Bank Commen Description Cost (US$ Packages No. (Prior / ts Million) Post) Total NCB 23.59 64 Post (Works) Total RfQ 2.29 20 Post (Works) Procurement of Civil Works with Selection Methods and Time Schedule (Please see Annex II). c. Summary of Procurement of Non- Consulting Services (TBD) 1 2 3 4 5 6 Review by Estimated Ref. Bank Commen Description Cost (US$ Packages No. (Prior / ts Million) Post) Total NCB 0.175 2 Post MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 4 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT 7. Prior Review Threshold for Consultancies: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Prior Review Selection Method Comments Threshold (USD) Consultant Services-QCBS- International 1. Consulting Services ≥ 300,000 ALL 2. Engineering and Construction ≥ 500,000 Supervision Consultant Services-QCBS < 300,000.00 NONE Consultant Services-CQS < 300,000.00 NONE Consultant Services-lC >300,000.00 ALL Consultant Services-lC <300,000.00 NONE Consultant Services- Single Source All Values ALL Selection Note: All ToRs to be prior review QCBS = Quality and Cost Based Selection SSS = Single Source Selection CQ = Consultant Qualification LCS = Least Cost Selection IC = Individual Consultant 8. Short list comprising entirely of National Consultants: Short list of consultants for services, estimated to cost less than $300,000.00 equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. a. Summary of Consultancies 1 2 3 4 5 6 Ref. Description Estimate Package Review by Comment No. d Cost s Bank s (US$ (Prior/Post Million) ) Summary of number of 5.72 7 Prior contracts that will be let under International QCBS Summary of number of 6.45 16 Post contracts that will be let under National QCBS Summary of number of 1.74 30 Post contracts that will be let under CQS Summary of number of 0.35 3 Post contracts that will be let under MOU MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 5 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Summary of number of 0.021 3 Post contracts that will be let under Individual Consultancies MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 6 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Estimated Estimated Prior Number of Amount in Investable or Expected Procureme Pre- USD (Over Amount Post Bid- Description (List of Componen nt Procureme qualificati the Project for 18 Revie Opening Contracts) t/Sector Packages nt Method on Life) months w Date WORKS BORNO Construction Of 18-No Double Classroom Blocks in Ngohi, Biji-Biji, Ngulde, C2/Educati Post Tue-19-Jun- Rumirgo, Chul on 3 NCB No 708,196.72 354,098.36 Review 18 Construction Of 10- No. Double Classroom Block - C2/Educati Post Tue-19-Jun- Bama (Banki Town) on 2 NCB No 393,442.62 314,754.10 Review 18 Reconstruction Of 39- No. Double Classroom Block in C2/Educati Post Damasak, Mobbar on 4 NCB No 575,409.84 71,926.23 Review Tue-24-Jul-18 Construction Of 15- No. Double Classroom Block - C2/Educati Post Gajibo, Logomane (Dikwa) on 2 NCB No 590,163.93 147,540.98 Review Tue-24-Jul-18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 7 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Construction Of 25 No. Double Classroom Block C2/Educati Post GUZAMALA on 2 NCB No 983,606.56 245,901.64 Review Tue-24-Jul-18 Construction Of 20- No. Double Classroom Block - Kukawa Town, Baga, Cross- C2/Educati Post Tue-18-Sep- Kauwa on 2 NCB No 786,885.25 196,721.31 Review 18 Construction Of 10- No. Double Classroom Block - C2/Educati Post Tue-18-Sep- Monguno on 1 NCB No 393,442.62 98,360.66 Review 18 Construction Of 4- No. Double Classroom Block in C2/Educati Post Tue-20-Nov- Ajiri. Mafa on 1 NCB No 157,377.05 39,344.26 Review 18 Renovation Of 20- No. Double Classroom Blockin C2/Educati Post Tue-20-Nov- Damboa Town -Abadam on 2 NCB No 295,081.97 73,770.49 Review 18 Renovation Of 31- No. Double Classroom Block - C2/Educati Post Tue-23-Oct- Bama on 2 NCB No 457,377.05 114,344.26 Review 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 8 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Construction Of 3-No. C2/Educati Post Tue-18-Sep- Educational Office -Kukawa on 1 NCB No 196,721.31 98,360.66 Review 18 Construction Of 2-No. Educational Office - C2/Educati Post Tue-20-Nov- Konduga on 1 NCB No 131,147.54 32,786.89 Review 18 Construction Of 2-No. Educational Office -Hawul C2/Educati Post Tue-23-Oct- Sakwa, Kwajafa on 1 NCB No 131,147.54 32,786.89 Review 18 Construction Of 4-No Vip C2/Educati Post Tue-18-Dec- Toilets -Askira-Uba on 1 RfQ No 59,016.39 47,213.11 Review 18 Construction Of 4-No Vip C2/Educati Post Tue-18-Dec- Toilets -Mafa on 1 RfQ No 59,016.39 47,213.11 Review 18 Construction Of 5-No Vip C2/Educati Post Tue-18-Dec- Toilets -Monguno on 1 RfQ No 73,770.49 59,016.39 Review 18 Renovation Of 1-No. Educational Office - C2/Educati Post Tue-18-Dec- Damboa on 1 RfQ No 18,032.79 4,508.20 Review 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 9 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Renovation Of 1-No. Educational Office and 1- No. Principal's Quarters - Benisheik, Kaga- Benisheik, C2/Educati Post Tue-23-Oct- Kaga on 1 RfQ No 42,622.95 16,803.28 Review 18 Rehabilitation of 66KM C2/Transpo 1,223,144. Prior Tue-27-Feb- Maiduguri to Bama road rt 1 NCB No 9,785,152.68 08 Review 18 Rehabilitation of 1 Ngala C2/Transpo Prior Tue-27-Feb- Bridge rt 1 NCB No 2,295,081.97 483,983.71 Review 18 C2/Transpo Post Tue-27-Feb- Rehabilitation of Biu bridge rt 1 NCB No 902,111.48 73,770.49 Review 18 Construction of galameri- dusuman-zabarmari- C2/Transpo Prior Tue-27-Feb- gongulong feeder road rt 1 NCB No 1,104,625.69 59,016.39 Review 18 RehabilitatIon of 3 General Hospital in ABADAM, ASKIRA UBA, KALA-BALGEe and Rehabilitation of Prior Tue-27-Mar- comprehensive Healthcare C2/Health 3 NCB No 1,555,779.01 986,195.83 Review 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 10 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT center (Civil Works, Solar Borehole, Fence & Security Post) Construction of PHC for 15 2,254,098. Prior Tue-27-Mar- LGAs C2/Health 5 NCB No 3,606,557.38 36 Review 18 Rehabilitation of Borno C2/Educati Post Tue-24-Apr- State Library on 2 NCB No 557,377.05 34,426.23 Review 18 Rehabilitation of Umar Ibn C2/Educati Post Tue-24-Apr- Ibrahim college Bama on 2 NCB No 557,377.05 278,688.52 Review 18 Construction of Solar Powered Boreholes (2Nos) in Umar Ibn Ibrahim college Bama Solar Lighting System to Borno C2/Educati Post Tue-24-Apr- Library on 1 NCB No 196,721.31 98,360.66 Review 18 Rehabilitation of Court Buildings in Bama Gwoza C2/Public Post Tue-22-May- Dikwa Mobbar Buildings 4 RfQ No 393,442.62 49,180.33 Review 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 11 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Rehabilitation of Local Govt Secretariats in Kukawa, Monguno, biu ,Abadam, Kala-Balge, Marte, C2/Public 1,229,508. Post Tue-05-Jun- Magumeri, Guzamala Buildings 8 RfQ No 1,967,213.11 20 Review 18 Rehabilitation of Traditional Rulers' Konduga , Monguno, Kukawa, Nganzai, Baga, Marte, Ngala, Abadam, Guzamala, C2/Public Post Tue-05-Jun- Kwajafa, Kumshe Buildings 6 RfQ No 1,442,622.95 180,327.87 Review 18 Provision of Community Resource Centres in 20 C2/Public Post LGAs Buildings 10 NCB No 2,295,081.97 860,655.74 Review Thu-05-Jul-18 Construction of Handpump Wells in Bama (3) Chibok (5), Biu (5), Mafa(3), Hawul (5), Askira/Uba(5), Konduga(4), Jere(5) Dikwa Post Fri-03-Aug- (3), Gwoza(5), C2/WASH 10 RfQ No 140,983.61 35,245.90 Review 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 12 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Construction of Solar Powered Boreholes in Askira Uba Gwoza(4),Bama(4), Ngala(3), Damboa(3) Jere(4),Kukawa(3), Biu(2),Konduga(3), Gubio(3), Askira/Uba(3), Magumeri(3), Marte(3), Mobbar(3), Monguno(3), Dikwa(2), Mafa(3), Abadam(3), Nganzai(3), Guzamala(3), Kaga(2), Chibok(2), Kala/Balge(3), Hawul(2)(To include 2Nos 5,000lt Plastic water tanks on a 1.5m raised platform , five fetching points/tap gallery, chain link 3,501,639. Post Wed-25-Jul- perimeter fence) C2/WASH 14 NCB No 4,668,852.46 34 Review 18 REHABILITATION OF LOCAL GOVERNMENT LODGES (Marte, Kaga, Chibok, Magumeri, Gwoza, Kala- Balge, Ngala, Guzamala, Abadam, Hawul, C2/Public Post Tue-21-Aug- Askira/Uba, Bama) Buildings 6 NCB No 1,311,475.41 786,885 Review 18 Rehabilitationof Traditional Rulers' Buildings Bama, Konduga, Gwoza ,Kareto, C2/Public Post Damboa , Monguno, Buildings 11 RfQ No 1,442,622.95 180,327.87 Review Thu-26-Jul-18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 13 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Kukawa, Askira-Uba , Dikwa, Baga, Marte REHABILITATION OF MINISTRY BUILDING (Ngala, C2/Public Post Tue-21-Aug- Monguno) Buildings 2 NCB No 276,577 Review 18 CONSTRUCTION OF SANITATION FACILITIES IN 21 LOCAL GOVERNMENT AREAS.ABADAM (6) ASKIRA(6) BAMA(6) BIU(6) CHIBOK(6) DAMBOA(6) DIKWA(6) GUBIO(6) GWOZA(6) JERE(6) KAGA(6) KALA-BALGE(6) KONDUGA(6) KUKAWA(6) MAFA(5) MOBBAR(6) MONGUNO(6) MARTE(6) NGALA(6) NGANZAI(6) Post Wed-19-Sep- MAGUMERI(6) C2/WASH 21 NCB No 781,517 Review 18 REHABILITATION OF EXISTING NON- FUNCTIONAL BOREHOLES ABADAM (1) ASKIRA UBA (2) BIU (2) DIKWA (1) Post Tue-18-Sep- GUBIO (1) GUZAMALA (1) C2/WASH 6 NCB No 258,525 Review 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 14 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT JERE (2) KALA BALGE (1) MAFA (2) MAGUMERI (1) MARTE (2) MOBBAR (1) NGALA (1) NGANZAI (1) Rehabilitation of 8 blocks of Laborataries (Umar Ibn C1/Educati Post Tue-18-Sep- Ibrahim college Bama) on 1 NCB No 262,295 Review 18 ADAMAWA Rehabilitation of Gulak Post Mon-14-May- Water Supply System C2/Water 1 NCB No 179,190.16 134,392.62 Review 18 Rehabilitation of Hong Post Mon-14-May- Water Supply System C2/Water 1 NCB No 116,646.90 87,485.18 Review 18 Rehabilitation of Michika Post Mon-14-May- Water supply system C2/Water 1 NCB No 138,193.44 103,645.08 Review 18 Rehabilitation of Uba Water Post Tue-15-May- Supply system C2/Water 1 NCB No 71,967.21 71,967.21 Review 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 15 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Rehabilitation of exisitng Water Supply sources in Post Tue-15-May- Gombi C2/Water 1 NCB No 30,475.41 30,475.41 Review 18 Construction of Uba New Post Mon-28-May- Water Supply Project C2/Water 1 NCB No 721,222.95 108,183.44 Review 18 Pella New Water Supply Post Mon-28-May- Project C2/Water 1 NCB No 555,289.34 83,293.40 Review 18 Construction of Hong New Post Mon-28-May- Water supply project C2/Water 1 NCB No 1,256,442.62 188,466.39 Review 18 Construction of Michika Post Tue-29-May- New Water supply project C2/Water 1 NCB No 1,189,261.84 178,389.28 Review 18 Construction GOMBI NEW Post Tue-29-May- WATER SUPPLY PROJECT C2/Water 1 NCB No 915,241.80 137,286.27 Review 18 Installation of 12 nos. Solar Boreholes (in secondary schools)- GSS Gombi, GDSS Garkida, GSS Hong, GDSS Pella, GSSS Uba, Post Thu-10-May- GJSS Uba, GDSS Garaha, C2/Water 1 NCB No 377,609.70 75,521.94 Review 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 16 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT GDSS Kwarhi, GDSS Za'ah, GSS Madagli, GSS Shuwa, GSS Gulak, GCSS Shuwa Installation of 37 Nos Solar Boreholes in 37 Health Centers in 7 Local Post Thu-10-May- Governments Areas C2/Water 4 NCB No 1,164,296.59 291,074.15 Review 18 Construction of 295Nos Hand Powered Bore Holes (in 2 primary schools per 35 wards, 35 Markets, 35 Motor parls and 155 Communities across 7 Post Thu-03-May- LGAs) C2/Water 4 NCB No 1,257,377.05 503,483.61 Review 18 Construction of VIP Latrines of 3-Comp (2 Blks Post Tue-14-Aug- in 24 pri sch) C2/WASH 3 RfQ No 212,459.02 79,672.13 Review 18 VIP Latrine of 3-Comp (2 Post Tue-14-Aug- Blks in 26 Markets) C2/WASH 3 RfQ No 230,163.93 92,065.57 Review 18 VIP Latrine of 3-Comp (2 Post Tue-14-Aug- Blks in 26 Motor Parks) C2/WASH 3 RfQ No 230,163.93 92,065.57 Review 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 17 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Rehabilitation of Lokwa C2/Transpo Post Mon-11-Jun- Bridge Mubi rt 1 NCB No 475,143.96 356,357.97 Review 18 Reconstruction of Main Road - Bangshika Road C2/Transpo Prior Mon-11-Jun- 2.5Km rt 1 NCB No 1,019,295.08 127,411.89 Review 18 Rehabilitation of Mubi Bazza Road with a spur to C2/Transpo 1,255,469. Prior Mon-11-Jun- Mayo Bani 45Km rt 1 NCB No 8,369,796.72 51 Review 18 Rehabilitation of PHC, Construction of Perimeter Fence and Staff Quarters (Civil Works, Solar Borehole, Fence & Security C2/Educati Prior Tue-10-Apr- Post) in 7 Communities on 7 NCB No 1,139,130.43 451,779.49 Review 18 Rehabilitation of Cottage Post Tue-10-Apr- Hospital C2/Health 1 NCB No 451,768.85 192,001.76 Review 18 Establishment of Trauma Post Thu-17-May- Center @ general hospital C2/Health 1 RfQ No 65,194.96 65,194.96 Review 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 18 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Renovation of GSS in 10 Towns (Gombi, Hong, Uba, Shuwa, Michika, Bazza, Mubi 1, Maiha, Madagali, C2/Educati Post Mubi North) on 10 NCB No 2,305,292.65 442,327.22 Review Tue-10-Jul-18 Renovation of 25Nos C2/Educati Post Primary School over 7 LGAs on 4 NCB No 865,747.88 324,655.45 Review Tue-10-Jul-18 Rehabilitation of Local Government Secretariat - C2/Public Post Thu-07-Jun- Song Buildings 1 NCB No 288,590.56 144,295.28 Review 18 Rehabilitation of Local Government Secretariat - C2/Public Post Thu-07-Jun- Madagali Buildings 1 NCB No 315,082.89 157,541.44 Review 18 Rehabilitation of District Head's Palace in 5 Communities (Uba, Gella, Gombi, Maiha/Pakka, C2/Public Post Thu-07-Jun- Gulak) Buildings 5 NCB No 422,463.57 158,423.84 Review 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 19 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT YOBE Conversion of Motorised Boreholes (28 Communities in Gulani and Damaturu) into Solar Post Mon-26-Mar- Powered C2/Water 1 NCB No 334,013.66 250,510.24 Review 18 Conversion of existing Motorized powered Borehole without Overhead tank into solar powered (Gujba, Gulani, Yunusari, Damaturu,& Post Mon-26-Mar- Geidam ) C2/Water 1 NCB No 277,532.56 208,149.42 Review 18 Conversion of existing Motorized powered Borehole into solar powered and construction of New Overhead tank (Gujba, Gulani, Yunusari, Post Mon-26-Mar- Damaturu,& Geidam) C2/Water 2 NCB No 542,490.73 406,868.05 Review 18 Drilling of New Solar Powered Boreholes in Gujba, Gulani, Yunusari, Damaturu, Fika, Potiskum, Post Mon-02-Apr- Geidam & Fune C2/Water 2 NCB No 878,917.25 329,593.97 Review 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 20 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Rehabilitation of Solar Powered Boreholes in Gulani, Gujba and Post Mon-02-Apr- Damaturu C2/Water 1 NCB No 244,228.65 183,171.49 Review 18 Construction & Upgrade of Post Wed-24-Oct- 33 nos. PHC Centres C2/Health 5 NCB No 5,386,554.10 538,655.41 Review 18 Reconstruction of Vandalized 3 Nos Post Wed-09-May- Immunization Offices C2/Health 1 RfQ No 68,618.27 68,618.27 Review 18 Renovation of 1No. General Post Mon-03-Sep- Hospital in Buni Yadi C2/Health 1 RfQ No 88,524.59 44,262.30 Review 18 Construction of 1No. Student Hostel each in College of Nursing and Midwifery Damaturu and College of Health Sciences Post Wed-22-Aug- and Technology, Nguru C2/Health 2 NCB No 983,606.56 245,901.64 Review 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 21 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Renovation of Govt Secondary Schools in Goniri,Bara, Bularafa, ,Kananma, Damagum, Buni Yadi, Kukuwa, Gujba and C2/Educati Post Mon-09-Apr- Best Center in Goniri on 5 NCB No 2,001,760.77 800,704.31 Review 18 Renovation of Dokshi C2/Educati Post Mon-09-Apr- Primary school, Gulani on 1 NCB No 168,034.42 67,213.77 Review 18 Rehabilitation of Local Government Office Secretariat in Gujba and C2/Public Post Wed-09-May- Potiskum Buildings 2 NCB No 472,529.40 75,459.62 Review 18 Rehabilitation of Development Offices in Gujba , Gulani, Yunusari & C2/Public Post Wed-09-May- Geidam Buildings 1 RfQ No 62,203.18 15,550.80 Review 18 Provision of Community Resource Centres in all 17 C2/Public Post Wed-23-May- LGAs Buildings 5 NCB No 1,950,819.67 731,557.38 Review 18 Rehabilitation of Audit C2/Public Post Wed-26-Sep- Office Buildings 1 RfQ No 63,078.12 15,769.53 Review 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 22 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Rehabilitation of Zonal C2/Public Post Wed-26-Sep- Statistical Office Buildings 1 RfQ No 50,491.80 25,245.90 Review 18 Rehabilitation ofCultural Buildings (District Head's Palace) in Buni Yadi and C2/Public Post Mon-27-Aug- Damagum Buildings 2 NCB No 446,682.62 111,670.66 Review 18 Rehabilitation of Government Buildings; C2/Public Post Mon-11-Jun- Agency for Mass Literacy Buildings 1 RfQ No 121,445.24 60,722.62 Review 18 Rehabilitation of Government Buildings; C2/Public Post Mon-11-Jun- Town Engineers Office Buildings 1 RfQ No 121,445.24 60,722.62 Review 18 GOODS BORNO Supply of Returnee C1/Transiti Resettlement Kits Bama, onal 2,216,737. Tue-13-Feb- Dikwa, Gwoza, Ngala, Support 4 NCB No 2,216,737.30 30 Post 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 23 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Monguno, Damboa, Gudumbali, Mobbar, Kala Balge) Supply of Agricultural Support kits with Seeds, Fertilizers and Small Work Farm Tools (Bama, Biu, Gwoza, Ngala, Monguno, C1/Transiti Damboa, Askira, Mobbar, onal Tue-13-Feb- Kukawa) Support 3 NCB No 681,729.10 681,729.10 Post 18 Supply of Small Animals (Bama, Mafa, Gwoza, Ngala, Monguno, Damboa, C1/Transiti Chibok, Nganzai, Kala onal Tue-20-Feb- Balge) Support 3 NCB No 788,935.25 788,935.25 Post 18 Supply of Non-agricultural Livelihood Kits (Bama, Dikwa, Gwoza, Ngala, C1/Transiti Monguno, Damboa, Chibok, onal Tue-13-Feb- Mobbar, Hawul Support 2 NCB No 227,377.05 227,377.05 Post 18 C1/Transiti Supply of Skills Acquisition onal Tue-20-Feb- Start up Kits Support 3 NCB No 737,704.92 387,295.08 Post 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 24 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Supply of solar electrification to 3 GENERAL HOSPITALS in ABADAM, GWOZA and KALA-BALGE and five Comprehensive Health Centre in Abadam, 2 in Gwoza, Kala-Balge, Askira - Tue-01-Jan- Uba C2/Health 3 NCB No 670,553.40 516,770.59 Post 19 Supply of Medical Equipment For 3General Hospitals in ABADAM, ASKIRA UBA, and KALA- Tue-15-Jan- BALGE C2/Health 3 NCB No 590,163.93 73,770.49 Post 19 Supply of Essential Drugs/Medical Consumables For 3 General Hospitals in HAWUL, Tue-05-Mar- MOBBAR AND DAMBOA C2/Health 3 NCB No 472,131.15 59,016.39 Post 19 Supply of Medical Equipment for Comprehensive Health Wed-09-Jan- Centers (Gwoza- Izge) C2/Health 1 NCB No 245,901.64 30,737.70 Post 19 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 25 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Supply of Essential Drugs/Medical Consumables for Comprehensive Health Tue-05-Feb- Center (Gwoza-izge) C2/Health 1 NCB No 236,065.57 29,508.20 Post 19 Supply of Medical Equipment to 15 PHCs to (Ngala, Nganzai Kukawa, Biu, Konduga, Gubio, Askira/Uba, Guzamala, Bama, Jere, Marte, Mobbar, Dikwa, Tue-15-Jan- Mafa, Abadam) C2/Health 2 NCB No 983,606.56 122,950.82 Post 19 Supply of Essential Drugs to 15 PHCs (Ngala, Nganzai Kukawa, Biu, Konduga, Gubio, Askira/Uba, Guzamala, Bama, Jere, Marte, Mobbar, Dikwa, Tue-05-Feb- Mafa, Abadam) C2/Health 2 NCB No 786,885.25 98,360.66 Post 19 Supply and Installation of Solar Inverters in 15 PHCs in (Ngala, Nganzai Kukawa, Biu, Konduga, Gubio, Askira/Uba, Guzamala, Bama, Jere, Marte, Mobbar, Tue-06-Mar- Dikwa, Mafa, Abadam) C2/Health 1 NCB No 262,295.08 65,573.77 Post 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 26 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Furniture for Library/ Offices in the Borno State Library and Furniture for 15 blocks of classrooms in Umar Ibn ibrahim college C2/Educati Tue-19-Mar- Bama on 2 NCB No 491,803.28 245,901.64 Post 19 Books and other learning Materials including elibrary C2/Educati Tue-19-Mar- in the Borno State library on 1 NCB No 262,295.08 131,147.54 Post 19 Suppy of Computers and other accessories to the Borno State Library , Maiduguri and Umar Ibn C2/Educati Tue-19-Mar- ibrahim college Bama on 2 RfQ No 81,967.21 40,983.61 Post 19 Supply of Medical Equipment TO 3 Comprehensive Health centers IN HAWUL, MOBBAR AND DAMBOA Tue-06-Mar- (Kwajafa, Kareto, Damboa) C2/Health 1 NCB No 196,721.31 49,180.33 Post 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 27 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Installation of solar inverters for PHC Gwoza( Tue-06-Mar- Izge) C2/Health 1 NCB No 13,114.75 13,114.75 Post 18 ADAMAWA C1/Transiti Supply of Returnee onal Mon-19-Mar- Resettlement Kits Support 2 NCB No 490,780.33 490,780.33 Post 18 Supply of Agricultural Support kits with Seeds, C1/Transiti Fertilizers and Small Work onal 1,496,508. Mon-19-Mar- Farm Tools Support 7 NCB No 1,496,508.20 20 Prior 18 C1/Transiti onal Thu-19-Apr- Supply of Small Animals Support 1 NCB No 182,950.82 182,950.82 Post 18 C1/Transiti Supply of Non-agricultural onal Mon-19-Mar- Livelihood Kits Support 1 NCB No 213,442.62 213,442.62 Post 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 28 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT C1/Transiti Start up kits for quick to onal Mon-19-Mar- market trading Support 1 NCB No 114,754.10 114,754.10 Post 18 Housing Refurbishment Returnee Packs for Voluntary Returnees across C1/Transiti the 7 LGAs being onal Thu-14-Jun- rehabilitated. Support 2 NCB No 390,163.93 331,639.34 Post 18 Supply of Medical Equipment to PHCs in 7 communities and Cottage Hospital in Gulak C2/Health 2 NCB No 344,262.30 43,032.79 Post Thu-19-Jul-18 Supply of Essential Drugs/Medical Consumable to PHCs in 7 Communities and Cottage Hospital in Thu-01-Nov- Gulak C2/Health 2 NCB No 452,459.02 108,196.72 Post 18 Installation of Solar Inverters in 7 Rehabilitated PHCs, Cottage Hospital in Mon-06-Aug- Gulak C2/Health 3 NCB No 268,861.16 18,852.46 Post 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 29 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Equipping of Trauma Center @ Michika General Mon-06-Aug- hospital C2/Health 1 NCB No 214,142.46 80,303.42 Post 18 Supply of Furniture to C2/Educati Thu-29-Mar- Primary Schools in 7 LGAs on 1 NCB No 245,901.64 30,737.70 Post 18 Supply of Books and Teaching/Learning Materials to Primary C2/Educati Thu-29-Mar- Schools in 7 LGAs on 1 NCB No 327,868.85 122,950.82 Post 18 Establishment of spare part supply chain/buffer Mon-16-Apr- stock for Water Facilities C2/WASH 1 NCB No 114,754.10 86,065.57 Post 18 Train the Trainer/User Workshops (i.e. 2 per LGA) for VLOM (Village Level Operation and Maintenance) WASHCOMS, (WASH Committees at LGA Level, WASH Units @ LGAs, VHPs (Voluntary Hygiene Promoters) State/LGA Govt Tue-24-Apr- Officials. C2/WASH 1 NCB No 72,131.15 54,098.36 Post 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 30 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT YOBE C1/Transiti Supply of Non Food Items onal Wed-21-Mar- (NFIs) Kits Support 3 NCB No 559,213.11 559,213.11 Post 18 C1/Transiti Supply of Agricultural kits onal 1,048,940. Wed-21-Mar- with seeds, oil, small tools Support 3 NCB No 1,048,940.98 98 Post 18 C1/Transiti onal Mon-23-Apr- Supply of Small Animals Support 3 NCB No 688,524.59 688,524.59 Post 18 C1/Transiti Non-agricultural Livelihood onal Mon-26-Mar- kits Support 2 NCB No 352,295.08 352,295.08 Post 18 C1/Transiti Supply of Skills Acquisition onal Wed-21-Mar- Start up Kits Support 3 NCB No 786,885.25 550,819.67 Post 18 Procure and distribute Plumpy Nuts for Wed-25-Apr- malnourished children in C2/Health 1 NCB No 215,438.65 32,315.80 Post 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 31 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Gujba, Geidam and Yunusari LGAs Equipping of Trauma Mon-12-Feb- Center C2/Health 1 NCB No 214,147.54 53,536.89 Post 18 Supply of Students Textbooks and Teachers' C2/Educati Mon-17-Sep- Guides on 1 NCB No 284,062.30 71,015.57 Post 18 Supply of Laboratory Equipment Physics. C2/Educati Mon-17-Sep- Chemistry & Biology on 1 NCB No 213,114.75 53,278.69 Post 18 C2/Educati Mon-17-Sep- Supply of School Furniture on 3 NCB No 804,885.25 201,221.31 Post 18 CONSULTING SERVICES BORNO Skills Acquisition Training C1/Transiti (3Nos Consultancies across onal Mon-09-Jul- 10 LGAs) Support 3 QCBS No 491,803.28 258,196.72 Post 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 32 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Specialized psycho-social support responding to C1/Commu needs (3Nos Consultancies nity Wed-28-Mar- across 10 LGAs) Resilience 3 QCBS No 826,229.51 619,672.13 Post 18 Consultancy for the Mobilisation and Organisation of Civic Education with Cultural and Recreational activities at Community Level with programs that respond to needs as prioritized by community based diagnosis (3Nos C1/Commu Consultancies across 10 nity Wed-11-Apr- LGAs) Resilience 3 QCBS No 442,622.95 265,573.77 Post 18 Consultancy for Sensitization, Community Mobilization and formation of peace groups within 7 Communities(establishmen t of community platforms to discuss community needs, grievances; and C1/Commu redress mechanisms. (1No nity Mon-30-Apr- Consultancy) Resilience 1 QCBS No 531,147.54 318,688.52 Prior 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 33 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Consultancy for Post- C1/Commu Conflict Transitional Justice nity Mon-21-May- and Accountability Resilience 1 QCBS No 147,540.98 88,524.59 Post 18 Statewide sponsorship for Radio Programming for Peacebuilding Campaign and Content for dissemination (focusing on deradicalisation, grievance C1/Commu redress and peacebuilding nity Mon-04-Jun- outreach themes) Resilience 1 CQS No 475,409.84 178,278.69 Prior 18 Consultancy for Educational campaigns for the prevention of mine and unexploded ordinance accidents /Mobilisation and Sensitization Campaign on Mine Action (Unexploded C1/Commu Ordnances) (1No nity Mon-04-Jun- Consultancy) Resilience 1 QCBS No 442,622.95 354,098.36 Prior 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 34 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Consultancy for Leadership Accountability and Transparency Training Programme (NELATTP) Targeting 20 LGA Staff and State Ministry Personal per LGA - Development of a transparency and accountability Local Governance Model through community participation C1/Commu (social accountability nity Fri-25-May- mechanisms) Resilience 1 CQS No 88,524.59 55,327.87 Post 18 Consultancy for Registration, Mapping and C1/Strengt Profiling of all local hening government structures and Local existing capacities State Governanc Fri-25-May- Wide e 1 CQS No 49,180.33 30,737.70 Post 18 Consultancy to provide C1/Strengt Capacity building of LG hening Officers for economic Local planning and policy Governanc Fri-25-May- development e CQS No 88,524.59 55,327.87 Post 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 35 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT C1/Strengt hening Capacity building for LG Local officials on programme Governanc Fri-25-May- design and implementation e CQS No 88,524.59 55,327.87 Post 18 Capacity building of LG C1/Strengt Officers for local hening governments on budget Local planning and execution, Governanc Fri-25-May- monitoring and reporting e 1 CQS No 88,524.59 55,327.87 Post 18 Capacity building of LG Officers for strategic communications C1/Strengt (Legislative Advocacy, hening Media relations, Local Stakeholder Management Governanc Fri-25-May- etc). e CQS No 88,524.59 55,327.87 Post 18 Capacity Building for 10 Local Government C1/Strengt Emergency Management hening Responders in Displaced Local and Transitional Local Governanc Fri-25-May- Government Officials e 1 CQS No 203,278.69 152,459.02 Post 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 36 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Sensitization, training (especially on Identification, Documentation, Tracing and Reunification and follow up) and coaching for state and non-state partners on case management of UASC C1/Program (Unaccompanied and Support to Fri-25-May- Separated Children) UASC 1 MOU No 73,770.49 59,016.39 Post 18 Training for officials of relevant State MDAs on C1/Program effective approaches to Support to Thu-28-Jun- UASC UASC 1 IC No 16,393.44 13,114.75 Post 18 Teacher Training and C1/Educati Fri-25-May- Recertification on 1 MOU No 442,622.95 77,459.02 Post 18 Training of Community Health Workers (CHeWs, VHWs, Midwives) to Staff Targeted Health Facilities (3Nos consultancies across the state. Amount Inclusive of Workshop and per diem Mon-29-Apr- payments) C1/Health 3 QCBS No 796,721.31 298,770.49 Post 19 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 37 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Sensitization and Mobilisation for Health (Outreach Programs) in 27 LGAs (Over 10 Fri-25-May- engagements) C1/Health 10 CQS No 708,196.72 265,573.77 Post 18 Identification and training of Village Levels Mechanics and Local Area Mechanics on Operation and Maintenance of existing Hand Pump and Solar powered Borehole for effective utilization and Fri-25-May- management. C2/WASH 1 CQS No 98,360.66 73,770.49 Post 18 ADAMAWA Refresher Training of Existing Extension Workers C1/Transiti to support Livelihoods onal Thu-10-May- Projects Support 1 CQS No 65,573.77 65,573.77 Post 18 Training of affected farmers to apply inputs and access targeted C1/Transiti agricultural value chains onal Thu-21-Jun- and agribusiness skills Support 1 CQS No 167,216.39 167,216.39 Post 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 38 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Establishment of Returnees Resettlement Registry at each LGA for Sensitization, Mobilisation and Logistics support for Safe and C1/Transiti Voluntary returns to 7 onal Thu-24-May- LGAs being rehabilitated Support 1 CQS No 61,565.57 49,252.46 Post 18 Consultancy to provide C1/Transiti Training for Bio Data onal Thu-10-May- Registration Support Support 1 IC No 1,377.05 1,101.64 Post 18 Consultancy for Sensitization, Community Mobilization and formation of peace groups within 7 Communities(establishmen t of community platforms to discuss community C1/Commu needs, grievances; and nity Mon-04-Jun- redress mechanisms Resilience 1 QCBS No 344,262.30 206,557.38 Prior 18 Diagnosis of community- specific reconciliation, peacebuilding and social C1/Commu cohesion needs and nity Thu-03-May- consequent development Resilience 2 QCBS No 344,262.30 206,557.38 Post 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 39 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT of Civil Education Programs using Cultural and Recreational activities at Community Level (2Nos Consultancies) Provision of specialized psycho-social assessment and support responding to needs through group support, recreational, customary and socializing activities, referrals etc C1/Commu (3Nos Consultancies across nity Mon-11-Jun- the affected areas) Resilience 3 QCBS No 642,622.95 481,967.21 Post 18 Sensitization and Mobilisation Programs for Awareness against Stigmatization of Woman and Children associated C1/Commu with armed groups. (1No nity Mon-04-Jun- Consultancy) Resilience 1 QCBS No 413,114.75 247,868.85 Prior 18 Consultancy for Mediation and Alternate Dispute Resolution Capacity C1/Commu Building within the nity Mon-18-Jun- Community Leadership and Resilience 3 QCBS No 425,960.66 255,576.39 Post 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 40 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Governance Structures (3Nos Consultancies acrossthe state) C1/Citizen- Consultancy for Leadership Governmen Accountability and t Transparency Training Relationshi Thu-10-May- Programme p Building 1 CQS No 72,131.15 45,081.97 Post 18 Registration, Mapping and C1/Strengt Profiling of all local hening government structures and Local existing capacities State Governanc Mon-28-May- Wide e 1 CQS No 39,344.26 24,590.16 Post 18 C1/Strengt Capacity building of LG hening Officers for economic Local planning and policy Governanc Mon-28-May- development e 1 CQS No 72,131.15 45,081.97 Post 18 C1/Strengt hening Capacity building for Local programme design and Governanc Mon-28-May- implementation e 1 CQS No 72,131.15 45,081.97 Post 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 41 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Capacity building of LG C1/Strengt Officers for local hening governments on budget Local planning and execution, Governanc Mon-28-May- monitoring and reporting e 1 CQS No 72,131.15 45,081.97 Post 18 Capacity building of LG Officers for strategic communications C1/Strengt (Legislative Advocacy, hening Media relations, Local Stakeholder Management Governanc Thu-21-Jun- etc). e 1 CQS No 72,131.15 45,081.97 Post 18 Hygiene Promotion Mon-17-Sep- Sensitization/Mobilization C2/WASH 1 IC No 9,180.33 6,885.25 Post 18 Hygiene Promotion Mon-12-Nov- Campaign C2/WASH 1 CQS No 85,677.59 64,258.20 Post 18 Training of Community Health Workers (CHeWs) to Staff Targeted Health Thu-13-Dec- Facilities C2/Health 1 CQS No 68,852.46 55,081.97 Post 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 42 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Sensitization and Mobilisation for Health Mon-17-Sep- (Outreach Programs) C2/Health 1 CQS No 183,606.56 146,885.25 Post 18 Mobilization and Sensitization for Children C2/Educati Thu-31-May- Education on 1 CQS No 206,557.38 206,557.38 Post 18 Teacher Training and Recertification ( Primary C2/Educati Thu-13-Dec- and Secondary Schools ) on 1 CQS No 360,655.74 360,656.74 Prior 18 YOBE Skills Acquisition Training C1/Transiti 3 Nos Consultancies across onal Wed-25-Apr- 8 LGAs) Support 3 QCBS No 524,590.16 367,213.11 Post 18 Consultancy for Sensitization, Community Mobilization and formation of peace groups within 15 C1/Peace Wed-23-May- Communities Building 1 QCBS No 491,803.28 319,672.13 Prior 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 43 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Diagnosis of community- specific reconciliation, peacebuilding and social cohesion needs and consequentt development of Civil Education Programs using Cultural and Recreational activities at C1/Peace Mon-04-Jun- Community Level Building 1 CQS No 49,180.33 31,967.21 Post 18 Consultancy for Mediation and Alternate Dispute Resolution Capacity Building within the Community Leadership and C1/Peace Mon-04-Jun- Governance Structures Building 1 CQS No 177,049.18 115,081.97 Post 18 Radio programs on mine awareness, dispute resolution in Hausa, Kanuri C1/Peace Wed-25-Jul- and Fulfulde Building 1 CQS No 280,719.92 105,269.97 Post 18 Provision of specialized psycho-social assessment and support responding to needs (3 Nos Consultancies C1/Peace Wed-20-Jun- across 8 LGAs) Building 3 QCBS No 625,822.95 438,076.07 Post 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 44 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Mapping and profiling of local government C1/Strengt structures and hening communities in places of Local both displacement and Governanc Thu-28-Jun- origin e 1 CQS No 39,344.26 39,344.26 Post 18 Establishment of C1/Strengt community platforms to hening discuss community needs, Local grievances; and building a Governanc Wed-06-Jun- bottom-up planning model e 1 CQS No 74,948.93 59,959.14 Post 18 Development of a transparency and accountability model C1/Strengt through community hening participation (social Local accountability Governanc Wed-06-Jun- mechanisms) e 1 CQS No 47,377.05 37,901.64 Post 18 C1/Strengt Capacity building of LG hening Officers for economic Local planning and policy Governanc Thu-28-Jun- development e 1 CQS No 55,737.70 44,590.16 Post 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 45 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT C1/Strengt hening Capacity building for Local programme design and Governanc Thu-28-Jun- implementation e 1 CQS No 55,737.70 44,590.16 Post 18 Capacity building of LG C1/Strengt Officers for local hening governments on budget Local planning and execution, Governanc Thu-28-Jun- monitoring and reporting e 1 CQS No 55,737.70 44,590.16 Post 18 Capacity building of LG Officers for strategic communications C1/Strengt (Legislative Advocacy, hening Media relations, Local Stakeholder Management Governanc etc). e 1 CQS No 55,737.70 44,590.16 Post Thu-26-Jul-18 Sensitization, training (especially on Identification, Documentation, Tracing and Reunification and follow up) and coaching for state and non-state C1/Program partners on case Support on Thu-07-Jun- management of UASC UASC 1 CQS No 52,459.02 41,967.21 Post 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 46 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Training for officials of C1/Program relevant MDAs on effective Support on Thu-28-Jun- approaches to UASC UASC 1 CQS No 8,196.72 6,557.38 Post 18 Menstrual Hygiene Management to support Women and Girls of productive ages to effectively maintain their Thu-17-May- menstrual hygiene C2/WASH 1 QCBS No 110,163.93 41,311.48 Post 18 Community Led Total Sanitation (CLTS) Implementation in Thu-31-May- communities C2/WASH 1 QCBS No 220,327.87 82,622.95 Post 18 Community Management training of entire Communities in the 8 proposed LGAs to effectively manage their Water, Sanitation and Mon-18-Jun- Hygiene Facilities C2/WASH 3 QCBS No 293,770.49 110,163.93 Post 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 47 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Identification and training of Village Levels Mechanics and Local Area Mechanics on Operation and Maintenance of existing Hand Pump and Solar powered Borehole for effective utilization and Thu-17-May- management. C2/WASH 1 CQS No 98,360.66 61,475.41 Post 18 Water Safety Plan implementation in the entire Communities of the Mon-16-Jul- four LGAs. C2/WASH 1 CQS No 112,459.02 84,344.26 Post 18 Integrated Outreach Services (Up to 5 activities Thu-17-May- envisaged) C2/Health 5 QCBS No 344,262.30 129,098.36 Post 18 Training of Community Health Workers (CHeWs, VHWs, Midwives) to Staff Thu-15-Nov- Targeted Health Facilities C2/Health 1 QCBS No 501,639.34 376,229.51 Prior 18 Teacher Training and C2/Educati Mon-26-Nov- Recertification in all LGAs on 1 MOU No 278,688.52 209,016.39 Post 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 48 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT PCNI NERSP PMC CELL Project Wide Project C3/Technic Management Consultancy al 2,000,000. Wed-11-Apr- Firm Assistance 1 QCBS No 3,000,000.00 00 Prior 18 Consultancy services for immediate- and medium- term implementation capacity building (4 C3/Technic separate Consultancies al Thu-03-May- Envisaged) Assistance 4 CQS No 536,393.44 268,196.72 Prior 18 Consultancy Services for C3/Technic Monitoring and Evaluation al Baseline Study Assistance 1 QCBS No 177,049.18 177,049.18 Post Fri-27-Apr-18 Consultancy services for setting up citizen engagement and third C3/Technic party monitoring al mechanisms Assistance 1 CQS No 177,049.00 59,016.33 Post Fri-06-Apr-18 Consultancy Services for C3/Technic Environmental Impact al Assessment Assistance 1 QCBS No 39,344.26 39,344.26 Post Fri-13-Apr-18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 49 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT NON- CONSULTING SERVICES ADAMAWA Door to Door Collection of Thu-24-May- Solid waste in 7 LGAs C2/WASH 1 NCB No 236,065.57 88,524.59 Post 18 Disposal of Waste from Door to Door Collection in Tue-13-Feb- 7 LGAs C2/WASH 1 NCB No 229,508.20 86,065.57 Post 18 OPERATIONAL COSTS PCNI NERSP PMC CELL PMC Software, Intranet and C3/Operati Tools onal Costs 3 RfQ No 159,240.16 159,240.16 Post Fri-27-Apr-18 Video Conferencing C3/Operati Thu-25-Jan- Equipment onal Costs 1 RfQ No 131,147.54 131,147.54 Post 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 50 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT C3/Operati Tue-27-Mar- Office Vehicles onal Costs 1 RfQ No 344,265.00 344,265.00 Post 18 BORNO STATE Procurement of 12 laptop computers, 12 laserjet printers, 4 photocopiers, 3 desktops, 15 desktops for work stations, 2 deskjet printers, HP Scanjet C3/Operati scanner onal Costs 1 RfQ No 159,240.16 159,240.16 Post Fri-27-Apr-18 Procurement of video conference equipment and C3/Operati internet connectivity onal Costs 1 RfQ No 65,574.00 65,574.00 Post Fri-27-Apr-18 Procurement of Office C3/Operati Tue-27-Mar- Furniture onal Costs 1 NCB No 32,786.89 32,786.89 Post 18 Procurement of 1 Video C3/Operati Wed-28-Mar- Camera, 2 DLSR Cameras, onal Costs 1 RfQ No 7,000.00 7,000.00 Post 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 51 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Procurement of 100KVA sound proof Generator, C3/Operati Sun-20-May- 10KVA Inverter System onal Costs 1 RfQ No 42,623.00 42,623.00 Post 18 Procurement of Office Vehicles - 2 Toyota Prado Jeep, 3 Toyota Hilux, 1 C3/Operati Wed-14-Mar- Toyota Corolla onal Costs 1 NCB No 448,525.00 448,525.00 Post 18 ADAMAWA STATE Procurement of computers, printers and other C3/Operati Wed-28-Mar- accessories onal Costs 1 RfQ No 24,131.15 24,131.15 Post 18 Procurement of video conference equipment and C3/Operati Wed-28-Mar- internet connectivity onal Costs 1 RfQ No 65,574.00 65,574.00 Post 18 Procurement of Office C3/Operati Tue-27-Mar- Furniture onal Costs 1 NCB No 32,786.89 32,786.89 Post 18 Procurement of 1 Video C3/Operati Wed-28-Mar- Camera, 2 DLSR Cameras, onal Costs 1 RfQ No 20,327.87 20,327.87 Post 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 52 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Procurement of 100KVA sound proof Generator, C3/Operati Mon-26-Mar- 10KVA Inverter System onal Costs 1 RfQ No 42,623.00 42,623.00 Post 18 Procurement of Office Vehicles - 2 Toyota Prado Jeep, 3 Toyota Hilux, 1 C3/Operati Tue-27-Mar- Toyota Corolla onal Costs 1 RfQ No 518,033.00 518,033.00 Post 18 YOBE STATE Procurement of computers, printers and other C3/Operati Wed-28-Mar- accessories onal Costs 1 RfQ No 24,131.15 24,131.15 Post 18 Procurement of video conference equipment and C3/Operati Wed-28-Mar- internet connectivity onal Costs 1 RfQ No 65,574.00 65,574.00 Post 18 Procurement of Office C3/Operati Tue-27-Mar- Furniture onal Costs 1 NCB No 32,786.89 32,786.89 Post 18 Procurement of 1 Video C3/Operati Wed-28-Mar- Camera, 2 DLSR Cameras, onal Costs 1 RfQ No 20,327.87 20,327.87 Post 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 53 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Procurement of 100KVA sound proof Generator, C3/Operati Mon-26-Mar- 10KVA Inverter System onal Costs 1 RfQ No 42,623.00 42,623.00 Post 18 Procurement of Office C3/Operati Tue-27-Mar- Vehicles onal Costs 1 RfQ No 468,852.46 468,852.46 Post 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 54 PROCUREMENT Nigeria : Multi-Sectoral Crisis Recovery Project for North Eastern Nigeria PLAN General Information Country: Nigeria 2018-06-05 Bank’s Approval Date of the Original Procurement Plan: 2023-06-05 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P157891 GPN Date: Project Name: Multi-Sectoral Crisis Recovery Project for North Eastern Nigeria Loan / Credit No: IDA / 59880 Borno MCRP Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned NG-BORNO MCRP-57818-CW Infrastructure Rehabilitation Request for Quota Single Stage - One E 2019-01-0 -RFQ / Rehabilitation of Court IDA / 59880 and Service Delivery Restora Post Open - National 393,443.00 80,642.16 Completed 2018-05-12 2021-10-14 2018-07-07 2020-07-25 tions nvelope 3 Buildings in Bama Gwoza Di tion & Improvement kwa Mobbar NG-BORNO MCRP-58804-CW -RFQ / Rehabilitation of Existi ng Non-Functional Boreholes Infrastructure Rehabilitation Request for Quota Single Stage - One E 2019-05-1 Abadam (1) Askira Uba (2) Bi IDA / 59880 and Service Delivery Restora Post Open - National 25,852.46 22,161.59 Completed 2018-09-17 2018-11-12 2019-12-11 tions nvelope 1 u (2) Dikwa (1) Gubio (1) Guz tion & Improvement amala (1) Jere (2) Kala Balge (1) Mafa (2) Magumeri (1) Ma rte (2) Mobbar (1) Ngala (1) Nganzai (1) NG-BORNO MCRP-58797-CW Infrastructure Rehabilitation Request for Quota Single Stage - One E 2019-04-1 -RFQ / Reconstruction of Post IDA / 59880 and Service Delivery Restora Post Open - National 163,934.00 0.00 Canceled 2018-08-20 2018-10-15 tions nvelope 3 Office (Bama) tion & Improvement NG-BORNO MCRP-58769-CW Infrastructure Rehabilitation Request for Quota Single Stage - One E 2019-08-0 -RFQ / Construction Of 5-No IDA / 59880 and Service Delivery Restora Post Open - National 73,770.00 0.00 Canceled 2018-12-08 2019-02-02 tions nvelope 1 Vip Toilets -Monguno tion & Improvement NG-BORNO MCRP-58402-CW Infrastructure Rehabilitation Request for Quota Single Stage - One E 2019-08-0 -RFQ / Renovation Of 1-No. E IDA / 59880 and Service Delivery Restora Post Open - National 18,033.00 0.00 Canceled 2018-12-08 2019-02-02 tions nvelope 1 ducational Office -Damboa tion & Improvement NG-BORNO MCRP-55929-CW -RFQ / Construction of Handp Infrastructure Rehabilitation ump Wells in Bama (3) Chibo Request for Quota Single Stage - One E 2019-03-1 IDA / 59880 and Service Delivery Restora Post Limited 140,984.00 0.00 Canceled 2018-07-24 2018-09-18 k (5), Biu (5), Mafa(3), Hawul tions nvelope 7 tion & Improvement (5), Askira/Uba(5), Konduga( 4), Jere(5) Dikwa (3), Gwoza( 5), NG-BORNO MCRP-58026-CW Infrastructure Rehabilitation Request for Quota Single Stage - One E 2019-07-0 -RFQ / Construction Of 4- No. IDA / 59880 and Service Delivery Restora Post Open - National 157,377.00 0.00 Canceled 2018-11-10 2019-01-05 tions nvelope 4 Double Classroom Block in Aj tion & Improvement iri. Mafa NG-BORNO MCRP-55956-CW Infrastructure Rehabilitation Request for Quota Single Stage - One E 2019-05-0 -RFQ / Construction Of 3-No. IDA / 59880 and Service Delivery Restora Post Limited 196,721.00 0.00 Canceled 2018-09-08 2018-11-03 tions nvelope 2 Educational Office -Kukawa tion & Improvement NG-BORNO MCRP-58801-CW -RFQ / Construction of Solar P Infrastructure Rehabilitation Request for Quota Single Stage - One E 2018-12-0 owered Boreholes (2Nos) in IDA / 59880 and Service Delivery Restora Post Open - National 196,721.00 0.00 Canceled 2018-04-14 2018-06-09 tions nvelope 6 Umar Ibn Ibrahim college Ba tion & Improvement ma Solar Lighting System to Borno Library NG-BORNO MCRP-58893-CW Infrastructure Rehabilitation Request for Quota Single Stage - One E 2019-08-0 -RFQ / Construction Of 4-No IDA / 59880 and Service Delivery Restora Post Open - National 59,016.00 0.00 Canceled 2018-12-08 2019-02-02 tions nvelope 1 Vip Toilets -Mafa tion & Improvement NG-BORNO MCRP-56416-CW Infrastructure Rehabilitation Request for Quota Single Stage - One E 2019-06-0 -RFQ / Construction Of 2-No. IDA / 59880 and Service Delivery Restora Post Limited 131,148.00 0.00 Canceled 2018-10-13 2018-12-08 tions nvelope 6 Educational Office -Hawul Sa tion & Improvement kwa, Kwajafa NG-BORNO MCRP-57851-CW Infrastructure Rehabilitation -RFB / Construction of new S Request for Quota Single Stage - One E 2019-05-1 IDA / 59880 and Service Delivery Restora Post Open - National 3,514,754.00 5,552.31 Completed 2018-09-17 2018-11-12 2019-09-24 olar Powered Boreholes in 27 tions nvelope 1 tion & Improvement Local Government Areas of B orno State NG-BORNO MCRP-58350-CW Infrastructure Rehabilitation -RFB / REHABILITATION OF 1 Request for Quota Single Stage - One E 2019-05-0 IDA / 59880 and Service Delivery Restora Post Open - National 1,311,475.47 257,374.29 Completed 2018-09-12 2018-11-07 2018-10-12 0 LOCAL GOVERNMENT LOD tions nvelope 6 tion & Improvement GES in Borno State NG-BORNO MCRP-56722-CW Infrastructure Rehabilitation -RFQ / Renovation Of 1-No. E Request for Quota Single Stage - One E 2019-08-0 IDA / 59880 and Service Delivery Restora Post Limited 65,674.00 104,759.75 Completed 2018-12-15 2019-06-03 2019-02-09 2019-06-25 ducational Office in Mafa Loc tions nvelope 8 tion & Improvement al Government Area of Borno State NG-BORNO MCRP-58891-CW -RFB / Rehabilitation of Prima Infrastructure Rehabilitation Request for Quota Single Stage - One E 2019-06-1 ry Health Care Center in 15 L IDA / 59880 and Service Delivery Restora Post Open - National 2,459,016.00 106,943.98 Completed 2018-10-21 2021-10-14 2018-12-16 2019-06-28 tions nvelope 4 ocal Government Areas of th tion & Improvement e 3 Senatorial districts of Bor no State NG-BORNO MCRP-58035-CW Infrastructure Rehabilitation Request for Quota Single Stage - One E 2019-05-1 -RFB / Rehabilitation of Borno IDA / 59880 and Service Delivery Restora Post Open - National 131,148.00 287,546.62 Completed 2018-09-22 2018-11-17 2019-07-24 tions nvelope 6 State Library in Maiduguri tion & Improvement NG-BORNO MCRP-58768-CW Infrastructure Rehabilitation -RFQ / Construction Of 18-No. Request for Quota Single Stage - One E 2019-05-1 IDA / 59880 and Service Delivery Restora Post Open - National 708,197.00 133,222.10 Completed 2018-09-24 2018-11-19 2018-10-24 Double Classroom Blocks in tions nvelope 8 tion & Improvement Askira/Uba Local Governmen t Area of Borno State NG-BORNO MCRP-73721-CW Infrastructure Rehabilitation -RFQ / Reconstruction of Loc Request for Quota Single Stage - One E 2019-05-1 IDA / 59880 and Service Delivery Restora Post Open - National 983,607.00 100,066.50 Completed 2018-09-17 2018-11-12 2019-06-27 al Education Authorities Offic tions nvelope 1 tion & Improvement es in 9 Local Governments of Borno State NG-BORNO MCRP-58400-CW Infrastructure Rehabilitation -RFQ / Renovation of 1-No. Pr Request for Quota Single Stage - One E 2019-09-0 IDA / 59880 and Service Delivery Restora Post Open - National 18,291.00 20,565.87 Completed 2019-06-01 2019-07-05 2019-07-05 incipal's Quarters in Kaga Loc tions nvelope 3 tion & Improvement al Government Area of Borno State Page 1 NG-BORNO MCRP-58394-CW Infrastructure Rehabilitation -RFQ / Construction Of 12-No Request for Quota Single Stage - One E 2020-04-0 IDA / 59880 and Service Delivery Restora Post Open - National 133,137.00 59,741.05 Completed 2019-08-11 2019-10-06 2019-07-05 Vip Toilets Mafa (4), Askira-U tions nvelope 3 tion & Improvement ba (4), Monguno (4) (3LOTS) NG-BORNO MCRP-58024-CW -RFQ / Reconstruction Of 18- Infrastructure Rehabilitation Request for Quota Single Stage - One E 2019-05-2 No. Double Classroom Blocks IDA / 59880 and Service Delivery Restora Post Open - National 453,235.00 771,542.71 Completed 2018-10-02 2018-11-27 2019-07-26 tions nvelope 6 in Bama and Mafa Local Gov tion & Improvement ernment Areas of Borno Stat e BOMCRP/RFB/CW/004/019 / Infrastructure Rehabilitation Single Stage - One E 2021-04-0 Rehabilitation of 66KM Maidu IDA / 59880 and Service Delivery Restora Prior Request for Bids Open - National 9,785,153.00 0.00 Canceled 2019-08-05 2020-01-22 2019-08-10 2020-01-29 2019-09-09 2020-03-03 2019-09-23 2019-10-07 nvelope 7 guri to Bama Road tion & Improvement NG-BORNO MCRP-52157-CW Infrastructure Rehabilitation Request for Quota Single Stage - One E 2019-05-1 -RFB / Rehabilitation of Com IDA / 59880 and Service Delivery Restora Post Open - National 2,295,082.00 645,978.75 Completed 2018-09-17 2018-11-12 2019-06-28 tions nvelope 1 munity Resource Centres in tion & Improvement Borno State NG-BORNO MCRP-130217-C Infrastructure Rehabilitation Request for Quota Single Stage - One E 2019-12-1 W-RFQ / Rehabilitation of Libr IDA / 59880 and Service Delivery Restora Post Limited 131,148.00 76,005.59 Completed 2019-09-25 2019-06-03 2019-10-18 2019-06-20 tions nvelope 7 ary at Umar Ibn Ibrahim Colle tion & Improvement ge Bama NG-BORNO MCRP-130225-C Infrastructure Rehabilitation Request for Quota Single Stage - One E 2019-12-2 W-RFQ / Rehabilitation of 1 of IDA / 59880 and Service Delivery Restora Post Limited 492,243.00 422,961.00 Completed 2019-09-29 2019-04-04 2019-10-21 2019-04-25 tions nvelope 0 3 General Hospital tion & Improvement NG-BORNO MCRP-130234-C Infrastructure Rehabilitation Request for Quota Single Stage - One E 2019-11-1 W-RFQ / Supply of Medical Eq IDA / 59880 and Service Delivery Restora Post Limited 590,164.00 521,591.33 Completed 2019-09-19 2019-07-12 2019-10-11 2019-08-01 tions nvelope 0 uipment to 3 General Hospita tion & Improvement ls NG-BORNO MCRP-133224-C Infrastructure Rehabilitation Request for Quota Single Stage - One E 2020-01-2 W-RFQ / Rehabilitation of Cou IDA / 59880 and Service Delivery Restora Post Limited 196,721.00 56,074.13 Completed 2019-11-06 2020-07-03 2019-11-28 2020-07-25 tions nvelope 7 rt Building tion & Improvement NG-BORNO MCRP-133225-C Infrastructure Rehabilitation Request for Quota Single Stage - One E 2020-01-0 W-RFQ / Rehabilitation of Tra IDA / 59880 and Service Delivery Restora Post Limited 721,311.00 264,975.56 Completed 2019-10-13 2019-10-04 2019-11-04 2019-10-24 tions nvelope 3 ditional Rulers Building (11 L tion & Improvement GAs) NG-BORNO MCRP-133227-C Infrastructure Rehabilitation Request for Quota Single Stage - One E 2020-01-0 W-RFQ / Construction of New IDA / 59880 and Service Delivery Restora Post Limited 140,984.00 14,598.54 Completed 2019-10-17 2021-03-01 2019-11-09 2021-03-20 tions nvelope 8 hand Pumps Water Sources tion & Improvement NG-BORNO MCRP-133230-C Infrastructure Rehabilitation Request for Quota Single Stage - One E 2020-01-2 W-RFQ / Rehabilitation of Exi IDA / 59880 and Service Delivery Restora Post Limited 129,262.00 56,840.24 Completed 2019-10-30 2019-12-06 2019-11-21 2019-12-28 tions nvelope 0 sting Non-Functional Borehol tion & Improvement es BORNO/MCRP/CW/RFQ/100/2 Infrastructure Rehabilitation 0 / Construction of Double Cl Request for Quota Single Stage - One E 2020-10-2 IDA / 59880 and Service Delivery Restora Post Limited 175,419.00 145,301.07 Completed 2020-04-07 2019-10-04 2020-04-28 2019-10-25 assroom Blocks at Askira/Uba tions nvelope 5 tion & Improvement Local Government Area of Bo rno State BORNO/MCRP/CW/RFQ/104/2 Infrastructure Rehabilitation 0 / Construction of Double Cl Request for Quota Single Stage - One E 2020-10-2 IDA / 59880 and Service Delivery Restora Post Limited 393,443.00 381,946.31 Signed 2020-04-08 2020-07-27 2020-04-29 2020-08-14 assroom Blocks at Kukawa Lo tions nvelope 6 tion & Improvement cal Government Area of Born o State BORNO/MCRP/CW/RFQ/105/2 Infrastructure Rehabilitation 0 / Construction of Double Cl Request for Quota Single Stage - One E 2020-10-2 IDA / 59880 and Service Delivery Restora Post Limited 78,430.00 57,801.12 Completed 2020-04-11 2019-02-20 2020-05-02 2019-03-12 assroom Blocks at Ajiri Com tions nvelope 9 tion & Improvement munity of Mafa Local Govern ment Area BORNO/MCRP/CW/RFQ/107/2 Infrastructure Rehabilitation 0 / Renovation of Double Clas Request for Quota Single Stage - One E 2020-10-3 IDA / 59880 and Service Delivery Restora Post Limited 132,787.00 58,824.15 Completed 2020-04-12 2019-02-20 2020-05-03 2019-03-12 sroom Blocks at Bama Town, tions nvelope 0 tion & Improvement Bama Local Government Are a of Borno State BORNO/MCRP/CW/RFQ/109 / Infrastructure Rehabilitation Renovation of Educational Of Request for Quota Single Stage - One E 2020-11-0 IDA / 59880 and Service Delivery Restora Post Limited 18,033.00 92,528.54 Completed 2020-04-19 2019-07-17 2020-05-10 2019-06-26 fice at Damboa Local Govern tions nvelope 6 tion & Improvement ment Area of Borno State BORNO/MCRP/CW/RFQ/111 / Infrastructure Rehabilitation Rehabilitation of Primary Hea Request for Quota Single Stage - One E 2020-11-1 IDA / 59880 and Service Delivery Restora Post Limited 1,225,870.00 82,775.24 Completed 2020-04-23 2019-09-02 2020-05-14 2019-09-24 lthcare Centers in selected L tions nvelope 0 tion & Improvement ocal Government Areas of Bo rno State BORNO/MCRP/CW/RFQ/112/2 0 / Rehabilitation of Court Bui Infrastructure Rehabilitation Request for Quota Single Stage - One E 2020-12-1 ldings at Bama, Gwoza, Dikw IDA / 59880 and Service Delivery Restora Post Limited 196,721.00 83,961.86 Completed 2020-05-28 2020-07-06 2020-06-18 2020-07-25 tions nvelope 5 a and Mobbar Local Governm tion & Improvement ent Areas of Borno State BORNO/MCRP/CW/RFQ/113/2 Infrastructure Rehabilitation 0 / Rehabilitation of Tradition Request for Quota Single Stage - One E 2020-12-0 IDA / 59880 and Service Delivery Restora Post Limited 721,312.00 69,919.00 Completed 2020-05-14 2020-02-18 2020-06-04 2020-03-11 al Rulers Building in selected tions nvelope 1 tion & Improvement Local Government Areas of B orno State BORNO/MCRP/CW/RFQ/116/2 Infrastructure Rehabilitation 0 / Rehabilitation of existing Request for Quota Single Stage - One E 2020-09-2 IDA / 59880 and Service Delivery Restora Post Limited 129,262.00 93,386.86 Completed 2020-06-04 2020-09-29 2020-06-25 2020-10-20 Non-Functional Boreholes in tions nvelope 3 tion & Improvement selected Local Government A reas of Borno State BORNO/MCRP/CW/RFQ/118/2 Infrastructure Rehabilitation 0 / Reconstruction of 60 Nos. Request for Quota Single Stage - One E 1,520,034.1 2020-11-2 IDA / 59880 and Service Delivery Restora Post Limited 1,972,386.00 Completed 2020-05-09 2020-12-20 2020-05-30 2020-01-10 Double Classroom Blocks in J tions nvelope 4 6 tion & Improvement ere Local Government Area BORNO/MCRP/CW/RFQ/119/2 Infrastructure Rehabilitation 0 / Reconstruction of 30 Nos. Request for Quota Single Stage - One E 2020-12-0 IDA / 59880 and Service Delivery Restora Post Limited 986,193.00 396,674.96 Completed 2020-05-15 2020-07-07 2020-06-05 2020-07-29 Double Classroom Blocks in P tions nvelope 2 tion & Improvement ulka, Gwoza Local Governme nt Area of Borno State BORNO/MCRP/CW/RFQ/120/2 0 / Reconstruction of Perimet Infrastructure Rehabilitation Request for Quota Single Stage - One E 2020-12-0 er Fence, Gate and Generato IDA / 59880 and Service Delivery Restora Post Limited 821,827.00 761,174.22 Completed 2020-05-17 2020-03-06 2020-06-07 2020-03-28 tions nvelope 4 rs Houses at Borno State Coll tion & Improvement ege of Basic Studies (BOCOB S) Bama Page 2 BORNO/MCRP/CW/RFQ/126/2 Infrastructure Rehabilitation 0 / Establishment of Vocation Request for Quota Single Stage - One E 1,364,155.1 2020-12-1 IDA / 59880 and Service Delivery Restora Post Limited 1,700,000.00 Completed 2020-05-31 2020-01-07 2020-06-21 2020-01-28 al Training Center in Mongun tions nvelope 3 8 tion & Improvement o Local Government Area of Borno State BORNO/MCRP/CW/RFQ/121 / Infrastructure Rehabilitation Establishment of Water Work Request for Quota Single Stage - One E 2020-12-0 IDA / 59880 and Service Delivery Restora Post Limited 842,209.00 353,549.05 Completed 2020-05-21 2019-12-23 2020-06-11 2020-01-14 s Facilities at Pulka, Gwoza L tions nvelope 8 tion & Improvement ocal Government Area of Bor no State BORNO/MCRP/CW/RFQ/108/2 Infrastructure Rehabilitation 0 / Construction of Education Request for Quota Single Stage - One E 2020-11-0 IDA / 59880 and Service Delivery Restora Post Limited 193,259.00 134,120.37 Completed 2020-04-19 2020-07-09 2020-05-10 2020-07-30 al Office at Kukawa, Hawul a tions nvelope 6 tion & Improvement nd Konduga Local Governme nt Areas of Borno State BORNO/MCRP/CW/RFQ/117/2 Infrastructure Rehabilitation 0 / Rehabilitation of Roads in Request for Quota Single Stage - One E 4,745,074.6 2020-11-0 IDA / 59880 and Service Delivery Restora Post Limited 1,981,391.00 Completed 2020-04-15 2020-02-25 2020-05-06 2020-03-14 Jiddari Polo ward of Jere Local tions nvelope 2 2 tion & Improvement Government Area of Borno St ate BORNO/MCRP/CW/RFQ/115,2 0 / Establishment of Sanitatio Infrastructure Rehabilitation Request for Quota Single Stage - One E 2020-12-0 n Facilities across Host Com IDA / 59880 and Service Delivery Restora Post Limited 290,760.00 80,455.59 Completed 2020-05-20 2020-01-07 2020-06-10 2020-01-28 tions nvelope 7 munities in selected Local Go tion & Improvement vernment Areas of Borno Sta te BOMCRP/CW/RFB/05/2020 / Infrastructure Rehabilitation Single Stage - One E 13,442,899.6 2022-09-2 Rehsbilitation of 66Km Maidu IDA / 59880 and Service Delivery Restora Prior Request for Bids Limited 0.00 Canceled 2020-08-17 2020-08-21 2020-08-22 2020-09-21 2020-09-22 2020-10-02 nvelope 0 2 guri - Bama Road tion & Improvement BOMCRP/CW/DIR/001/20 / R Infrastructure Rehabilitation 13,442,899.6 12,717,711. 2023-04-2 ehabilitation of 66km Maidug IDA / 59880 and Service Delivery Restora Prior Direct Selection Direct Signed 2020-10-02 2020-09-30 2020-10-04 2020-10-02 2020-10-17 2020-12-29 0 49 0 uri-Bama Road tion & Improvement BOMCRP/RFB/CW/003/019 / Infrastructure Rehabilitation Single Stage - One E 2020-02-0 Construction of Galameri-Dus IDA / 59880 and Service Delivery Restora Post Request for Bids Open - National 1,104,626.00 0.00 Canceled 2019-08-05 2021-01-13 2019-08-10 2019-09-09 2019-09-23 2019-10-07 nvelope 5 uman-Zabarmari-Gungulong tion & Improvement Feeder Road Request for Quota BOMCRP/CW/DIR/002/2020 / Infrastructure Rehabilitation tions - Small Work REHABILITATION OF 4.17km 2022-11-1 IDA / 59880 and Service Delivery Restora Post Direct Selection Direct s (Emergency) SP 5,215,385.00 0.00 Signed 2021-05-03 2021-08-10 2021-05-05 2022-10-03 2021-05-15 MONGUNO TOWNSHIP ROAD, 3 tion & Improvement D -Non Competiti IN MONGUNO LOCAL GOVER ve NMENT AREA BORNO/MCRP/CW/RFB/122/2 Infrastructure Rehabilitation 0 / Rehabilitation of 4.197k Single Stage - One E 2021-08-0 IDA / 59880 and Service Delivery Restora Prior Request for Bids Limited 5,215,385.00 0.00 Canceled 2020-10-15 2020-10-20 2020-12-01 2020-12-31 2021-02-04 m Monguno Township Roads, nvelope 3 tion & Improvement Monguno Local Government Area of Borno State BORN/MCRP/CW/RFQ/114/20 Infrastructure Rehabilitation / Construction of Sanitation F Request for Quota Single Stage - One E 2020-12-0 IDA / 59880 and Service Delivery Restora Post Limited 543,505.00 0.00 Canceled 2020-05-15 2020-06-05 acilities in selected Local Gov tions nvelope 2 tion & Improvement ernment Areas of Borno Stat e NG-BORNO MCRP-133228-C Infrastructure Rehabilitation Request for Quota Single Stage - One E 2020-01-1 W-RFQ / Construction of Sani IDA / 59880 and Service Delivery Restora Post Limited 390,760.00 0.00 Canceled 2019-10-24 2019-11-15 tions nvelope 4 tation Facilities in 21 LGAs tion & Improvement NG-BORNO MCRP-133229-C Infrastructure Rehabilitation W-RFQ / Establishment of Sa Request for Quota Single Stage - One E 2020-01-2 IDA / 59880 and Service Delivery Restora Post Limited 447,835.00 0.00 Canceled 2019-11-02 2019-11-23 nitation Facilities across Host tions nvelope 2 tion & Improvement Communities in 11 LGAs BORNO/MCRP/CW/RFQ/110/2 Infrastructure Rehabilitation 0 / Renovation of Educational Request for Quota Single Stage - One E 2020-11-0 IDA / 59880 and Service Delivery Restora Post Limited 18,033.00 0.00 Canceled 2020-04-18 2020-05-09 Office Kaga Local Governmen tions nvelope 5 tion & Improvement t Area of Borno State BORNO/MCRP/CW/RFQ/103/2 Infrastructure Rehabilitation 0 / Construction of Double Cl Request for Quota Single Stage - One E 2020-10-2 IDA / 59880 and Service Delivery Restora Post Limited 191,803.00 0.00 Canceled 2020-04-08 2020-04-29 assroom Blocks at Damasak tions nvelope 6 tion & Improvement Town of Mobbar Local Gover nment Area BORNO/MCRP/CW/RFQ/101/2 Infrastructure Rehabilitation 0 / Construction of Double Cl Request for Quota Single Stage - One E 2020-10-2 IDA / 59880 and Service Delivery Restora Post Limited 97,455.00 0.00 Canceled 2020-04-08 2020-04-29 assroom Blocks at Banki Tow tions nvelope 6 tion & Improvement n of Bama Local Government Area BORNO/MCRP/CW/RFQ/106/2 Infrastructure Rehabilitation 0 / Renovation of Double Clas Request for Quota Single Stage - One E 2020-10-2 IDA / 59880 and Service Delivery Restora Post Limited 327,869.00 0.00 Canceled 2020-04-10 2020-05-01 sroom Blocks at Abadam Loc tions nvelope 8 tion & Improvement al Government Area NG-BORNO MCRP-58897-CW Infrastructure Rehabilitation Single Stage - One E 2019-07-2 -RFB / Renovation Of 31- No. IDA / 59880 and Service Delivery Restora Post Request for Bids Open - National 457,377.00 0.00 Canceled 2018-10-08 2018-10-13 2018-11-24 2018-12-24 2019-01-28 nvelope 7 Double Classroom Block -Ba tion & Improvement ma NG-BORNO MCRP-58384-CW Strengthening Peace Buildin Request for Quota Single Stage - One E 2019-04-1 -RFQ / Rehabilitation of Minis IDA / 59880 g, Stability and Social Cohesi Post Open - National 276,578.00 0.00 Canceled 2018-08-20 2018-10-15 tions nvelope 3 try Building (Ngala, Monguno on ) NG-BORNO MCRP-130200-C Infrastructure Rehabilitation Request for Quota Single Stage - One E 2019-12-1 W-RFQ / Construction of 15-N IDA / 59880 and Service Delivery Restora Post Limited 590,164.00 0.00 Canceled 2019-09-20 2019-10-12 tions nvelope 1 o. Double Classroom Block Di tion & Improvement kwa NG-BORNO MCRP-130206-C Infrastructure Rehabilitation Request for Quota Single Stage - One E 2019-12-0 W-RFQ / Renovation of 20-No IDA / 59880 and Service Delivery Restora Post Limited 327,869.00 0.00 Canceled 2019-09-18 2019-10-10 tions nvelope 9 . 20 Double Classroom Block tion & Improvement at Abadam NG-BORNO MCRP-58781-CW Infrastructure Rehabilitation -RFQ / Rehabilitation of Umar Request for Quota Single Stage - One E 2019-05-1 IDA / 59880 and Service Delivery Restora Post Open - National 262,295.00 0.00 Canceled 2018-09-17 2018-11-12 Ibn Ibrahim college Library in tions nvelope 1 tion & Improvement Bama Local Government Are a of Borno State BOMCRP/RFB/CW/001/019 / Infrastructure Rehabilitation Single Stage - One E 2019-08-3 Rehabilitation of 1 Ngala Brid IDA / 59880 and Service Delivery Restora Post Request for Bids Open - National 2,295,081.00 0.00 Canceled 2019-03-05 2019-03-10 2019-04-09 2019-04-19 2019-05-03 nvelope 1 ge tion & Improvement Infrastructure Rehabilitation BOMCRP/RFB/CW/002/019 / Single Stage - One E 2020-03-1 IDA / 59880 and Service Delivery Restora Post Request for Bids Open - National 902,111.00 0.00 Canceled 2019-09-12 2019-09-17 2019-10-17 2019-10-31 2019-11-14 Rehabilitation of Biu bridge nvelope 3 tion & Improvement Page 3 NG-BORNO MCRP-58803-CW Infrastructure Rehabilitation -RFB / RehabilitatIon of 3 Ge Request for Quota Single Stage - One E 2019-06-1 IDA / 59880 and Service Delivery Restora Post Open - National 1,476,727.00 0.00 Canceled 2018-10-17 2018-12-12 neral Hospital in (ABADAM, A tions nvelope 0 tion & Improvement SKIRA UBA & KALA-BALGE) NG-BORNO MCRP-130253-C W-RFQ / Rehabilitation of Co Infrastructure Rehabilitation Request for Quota Single Stage - One E 2019-12-1 mprehensive Health Care Ce IDA / 59880 and Service Delivery Restora Post Limited 79,051.00 0.00 Canceled 2019-09-27 2019-10-20 tions nvelope 9 nter (CivilWorks, Solar Boreh tion & Improvement ole, Fence & Security Post) at CHC Izge, Gwoza NG-BORNO MCRP-57567-CW Infrastructure Rehabilitation -RFQ / Solar Lighting System Request for Quota Single Stage - One E 2019-05-2 IDA / 59880 and Service Delivery Restora Post Limited 98,361.00 0.00 Canceled 2018-10-02 2018-11-27 to Umar Ibrahim College Libr tions nvelope 6 tion & Improvement ary Bama and Borno State Li brary Maiduguri NG-BORNO MCRP-130211-C Infrastructure Rehabilitation W-RFQ / Rehabilitation of 8 Bl Request for Quota Single Stage - One E 2019-12-1 IDA / 59880 and Service Delivery Restora Post Limited 262,295.00 0.00 Canceled 2019-09-21 2019-10-13 ocks of Laboratories at Umar tions nvelope 2 tion & Improvement Ibn Ibrahim College Bama NG-BORNO MCRP-130219-C Infrastructure Rehabilitation W-RFQ / Construction of Sola Request for Quota Single Stage - One E 2019-12-2 IDA / 59880 and Service Delivery Restora Post Limited 98,361.00 0.00 Canceled 2019-09-29 2019-10-21 r Powered Boreholes (2No.) a tions nvelope 0 tion & Improvement t Umar Ibn Ibrahim College B ama NG-BORNO MCRP-130203-C Infrastructure Rehabilitation Request for Quota Single Stage - One E 2019-12-1 W-RFQ / Construction of 20-N IDA / 59880 and Service Delivery Restora Post Limited 393,443.00 0.00 Canceled 2019-09-22 2019-10-14 tions nvelope 3 o.Double Classroom Block at tion & Improvement Kukawa BOMCRP/RFB/CW/035/019 / Infrastructure Rehabilitation Single Stage - One E 2020-01-1 Rehabilitation of Comprehen IDA / 59880 and Service Delivery Restora Post Request for Bids Open - National 2,465,483.00 0.00 Canceled 2019-05-15 2019-05-20 2019-06-19 2019-07-03 2019-07-17 nvelope 3 sive Health Center in (CHC) i tion & Improvement n 15 LGAs NG-BORNO MCRP-58871-CW Infrastructure Rehabilitation -RFB / Rehabilitation of Local Request for Quota Single Stage - One E 2019-05-1 IDA / 59880 and Service Delivery Restora Post Open - National 2,622,951.00 0.00 Canceled 2018-09-17 2018-11-12 Govt Secretariats of 8 Local tions nvelope 1 tion & Improvement Government Areas of Borno State BOMCRP-AF/CW/RFQ/001 / R econstruction of 1 Bedroom s Infrastructure Rehabilitation Request for Quota emi detached staff quarters f Request for Quota Single Stage - One E 2022-08-1 IDA / 59880 and Service Delivery Restora Post Limited tions (Non Bank-S 479,946.00 43,803.64 Signed 2021-12-19 2022-03-15 2022-02-13 2022-04-05 or the 18 PHCs Konduga (2), tions nvelope 2 tion & Improvement PD) Bayo (1), A/Uba (2), MMC (3), Hawul (1), Gwoza (1), Chibok (2), Shani (1) and Marte (1) BOMCRP-AF/CW/RFQ/002 / R econstruction of 2 Bedroom s Request for Quota Infrastructure Rehabilitation emi detached staff quarters f Request for Quota Single Stage - One E tions - Small Work 2022-08-2 IDA / 59880 and Service Delivery Restora Post Limited 627,315.00 59,332.50 Signed 2022-01-04 2022-03-31 2022-03-01 2022-04-06 or the 18 PHCs Konduga (4), tions nvelope s (Emergency) SP 8 tion & Improvement Bayo (1), A/Uba (3), MMC (3), D -Competitive Hawul (1), Gwoza (1), Chibok (2), Shani (1) and Marte (1) BOMCRP-AF/CW/RFQ/003 / R Infrastructure Rehabilitation Request for Quota ehabilitation of Local Govern Request for Quota Single Stage - One E 2022-08-1 IDA / 59880 and Service Delivery Restora Post Limited tions (Non Bank-S 197,642.00 0.00 Completed 2021-12-17 2022-05-27 2022-02-11 emnt Lodges at Kukawa, Guz tions nvelope 0 tion & Improvement PD) amala and Marte Local Gover nment Areas BOMCRP-AF/CW/RFQ/004 / R ehabilitation of Traditional Ru Infrastructure Rehabilitation Request for Quota Request for Quota Single Stage - One E Pending Imp 2022-09-0 lers Buildings Dikwa, Kaga, K IDA / 59880 and Service Delivery Restora Post Limited tions (Non Bank-S 228,849.00 0.00 2022-01-12 2022-03-09 tions nvelope lementation 5 ala Balge, Abadam, Kukawa tion & Improvement PD) and Guzamla Local Governm ent Areas BOMCRP-AF/CW/RFQ/005 / R Infrastructure Rehabilitation Request for Quota ehabilitation of Court Buildin Request for Quota Single Stage - One E Under Imple 2022-07-2 IDA / 59880 and Service Delivery Restora Post Limited tions (Non Bank-S 114,424.00 0.00 2022-01-05 2022-08-01 2022-01-25 gs Ngala, Mobbar, A/Uba, Mo tions nvelope mentation 4 tion & Improvement PD) nguno and konduga Local Go vernment Areas BOMCRP-AF/CW/RFQ/006 / R Infrastructure Rehabilitation Request for Quota ehabilitation of Local Govern Request for Quota Single Stage - One E Pending Imp 2022-07-2 IDA / 59880 and Service Delivery Restora Post Limited tions (Non Bank-S 166,436.00 0.00 2022-01-08 2022-01-28 ment Secretariats Kukawa, G tions nvelope lementation 7 tion & Improvement PD) uzamala and Marte Local Go vernment Areas BOMCRP-AF/CW/RFQ/007 / R Infrastructure Rehabilitation Request for Quota Request for Quota Single Stage - One E Pending Imp 2022-07-1 esuscitation of Damasak Irrig IDA / 59880 and Service Delivery Restora Post Limited tions (Non Bank-S 93,010.00 0.00 2021-12-29 2022-01-18 tions nvelope lementation 7 ation Scheme tion & Improvement PD) BOMCRP-AF/CW/RFQ/008 / R Infrastructure Rehabilitation Request for Quota Request for Quota Single Stage - One E 2022-09-1 esuscitation of Monguno Irrig IDA / 59880 and Service Delivery Restora Post Limited tions (Non Bank-S 237,533.00 205,529.18 Signed 2022-02-22 2021-12-28 2022-03-14 2022-01-18 tions nvelope 0 ation Scheme tion & Improvement PD) BOMCRP-AF/CW/RFQ/009 / E Infrastructure Rehabilitation Request for Quota stablishment of Monguno Liv Request for Quota Single Stage - One E Pending Imp 2022-08-2 IDA / 59880 and Service Delivery Restora Post Limited tions (Non Bank-S 626,907.00 0.00 2022-02-04 2022-02-24 estock Investigation and Bre tions nvelope lementation 3 tion & Improvement PD) eding Center (LIBC) BOMCRP-AF/CW/RFQ/010 / E stablishment of agro-logistic hubs in some selected LGAs Infrastructure Rehabilitation Request for Quota across the state to enhance Request for Quota Single Stage - One E 2022-08-0 IDA / 59880 and Service Delivery Restora Post Limited tions (Non Bank-S 450,000.00 75,498.65 Completed 2022-01-20 2022-03-14 2022-02-09 2022-04-05 production, processing, pack tions nvelope 8 tion & Improvement PD) aging and marketing of farm produce, fruits and vegetable s, livestocks and poultry prod ucts. Dikwa, Kukawa, Gubio a nd Mobbar BOMCRP-AF/CW/RFQ/011 / 5 00,000ltr corrugated overhea d tanks with 25m high steel s Infrastructure Rehabilitation Request for Quota tanchion complete with conn Request for Quota Single Stage - One E Pending Imp 2022-07-2 IDA / 59880 and Service Delivery Restora Post Limited tions (Non Bank-S 216,535.00 0.00 2022-01-06 2022-01-26 ection accessories Monguno ( tions nvelope lementation 5 tion & Improvement PD) 2), Gubio (2), Magumari (2), Marte (2), Guzamala (2), Mob bar (2), Kukawa (2), Abadam (2), Kala Balge (2) and Dikwa (2) BOMCRP-AF/CW/RFQ/012 / R ehabilitation of Double Classr Infrastructure Rehabilitation Request for Quota Request for Quota Single Stage - One E Under Imple 2022-08-1 oom Blocks MMc (10), Jere (1 IDA / 59880 and Service Delivery Restora Post Limited tions (Non Bank-S 839,112.00 0.00 2022-01-28 2022-03-17 2022-02-17 tions nvelope mentation 6 0), Monguno (5), Marte (5), D tion & Improvement PD) ikwa (5), Konduga (10), Kuka wa (5) and Baga (5) Page 4 BOMCRP-AF/CW/RFQ/015 / R Infrastructure Rehabilitation Request for Quota ehabilitation of Laboratory M Request for Quota Single Stage - One E Pending Imp 2022-08-2 IDA / 59880 and Service Delivery Restora Post Limited tions (Non Bank-S 532,594.00 0.00 2022-02-03 2022-02-23 MC (7), Jere (7), Biu (3), Haw tions nvelope lementation 2 tion & Improvement PD) ul (2), A/Uba (2), Bayo (1) an d Dikwa (2) BOMCRP-AF/CW/RFQ/013 / R Request for Quota econstruction of Double Clas Infrastructure Rehabilitation Request for Quota Single Stage - One E tions - Small Work 2022-09-0 sroom Blocks Mafa (5), Guza IDA / 59880 and Service Delivery Restora Post Limited 1,220,527.00 0.00 Completed 2022-01-15 2022-03-21 2022-03-12 tions nvelope s (Emergency) SP 8 mala (5), Kala Balge (5), Dik tion & Improvement D -Competitive wa (5), MMC (8), Jere (7) and Marte (5) BOMCRP-AF/CW/RFQ/014 / R econstruction of VIP Toilets in Infrastructure Rehabilitation Request for Quota Request for Quota Single Stage - One E 2022-08-0 Schools MMC (5), Jere (5), Gu IDA / 59880 and Service Delivery Restora Post Limited tions (Non Bank-S 242,718.00 51,065.87 Completed 2022-01-21 2022-05-20 2022-02-10 2022-06-10 tions nvelope 9 bio (3), Monguno (3), Marte ( tion & Improvement PD) 4), Mafa (4), Dikwa (4), Gwoz a (4) and Konduga (1) GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NG-BORNO MCRP-55919-GO Strengthening Peace Buildin -RFB / Supply of non food ite Request for Quota Single Stage - One E IDA / 59880 g, Stability and Social Cohesi Post Open - National 2,216,691.00 414,196.65 Completed 2018-08-29 2018-10-24 2019-02-05 2019-04-22 2018-10-24 m Kits for household support tions nvelope on for 9 Local Government Area s of Borno State NG-BORNO MCRP-58782-GO -RFB / Supply of Agricultural Strengthening Peace Buildin Request for Quota Single Stage - One E Support kits with Seeds, Ferti IDA / 59880 g, Stability and Social Cohesi Post Open - National 681,729.00 190,176.53 Completed 2018-08-29 2018-10-24 2018-09-05 2019-04-22 2018-09-10 tions nvelope lizers and Small Work Farm T on ools for 9 Local Government Areas of Borno State NG-BORNO MCRP-55925-GO Strengthening Peace Buildin -RFB / Supply of Small Animal Request for Quota Single Stage - One E IDA / 59880 g, Stability and Social Cohesi Post Open - National 788,935.00 352,563.75 Completed 2018-08-29 2018-10-24 2018-10-15 2019-04-22 2018-10-30 s for 9 Local Government Are tions nvelope on as of Borno State NG-BORNO MCRP-58006-GO Strengthening Peace Buildin -RFB / Supply of Non-agricult Request for Quota Single Stage - One E IDA / 59880 g, Stability and Social Cohesi Post Open - National 758,525.00 487,381.13 Completed 2018-08-29 2018-10-24 2018-10-11 2019-04-22 2018-10-17 ural Livelihood Kits to 9 Local tions nvelope on Government Areas of Borno State NG-BORNO MCRP-58404-GO -RFB / Procurement of 2 Toyo Technical Assistance and Pro Single Stage - One E IDA / 59880 Post Request for Bids Open - National 448,525.00 0.00 Canceled 2018-04-16 2019-02-06 2018-04-21 2018-06-02 2018-07-18 2018-07-02 2018-08-06 2019-02-02 ta Prado Jeep, 3 Toyota Hilux, ject Management Support nvelope 1 Toyota Corolla NG-BORNO MCRP-58381-GO -RFQ / Procurement of 100KV Technical Assistance and Pro Request for Quota Single Stage - One E IDA / 59880 Post Open - National 42,623.00 0.00 Canceled 2018-04-14 2018-06-09 2018-12-06 A sound proof Generator, 10 ject Management Support tions nvelope KVA Inverter System NG-BORNO MCRP-58351-GO -RFB / Supply of broadcasting equipment to selected Radio Strengthening Peace Buildin Single Stage - One E Station for content dissemina IDA / 59880 g, Stability and Social Cohesi Post Request for Bids Open - National 262,295.00 0.00 Canceled 2018-04-20 2018-04-25 2018-06-06 2018-07-06 2018-08-10 2019-02-06 nvelope tion towards deradicalisation, on grievance redress and peace building media outreach cam paign to target LGAs. NG-BORNO MCRP-58380-GO Technical Assistance and Pro Request for Quota Single Stage - One E -RFQ / Procurement of 1 Vide IDA / 59880 Post Open - National 7,000.00 0.00 Canceled 2018-04-18 2018-06-13 2018-12-10 ject Management Support tions nvelope o Camera, 2 DLSR Cameras, NG-BORNO MCRP-52708-GO -RFB / Furniture for Library/ O Infrastructure Rehabilitation Single Stage - Two E ffices in the Borno State Libr IDA / 59880 and Service Delivery Restora Post Request for Bids Open - National 491,803.00 0.00 Canceled 2019-07-16 2019-07-21 2019-09-01 2019-11-14 2019-12-19 2020-06-16 nvelope ary and Furniture for 15 bloc tion & Improvement ks of classrooms in Umar Ibn ibrahim college Bama NG-BORNO MCRP-58807-GO -RFQ / Rehabilitation of Comp Infrastructure Rehabilitation rehensive Healthcare Center Request for Quota Single Stage - One E IDA / 59880 and Service Delivery Restora Post Open - National 79,051.00 67,027.47 Completed 2018-11-05 2018-12-31 2019-04-29 2019-06-29 2019-12-05 (Civil Works, Solar Borehole, tions nvelope tion & Improvement Fence & Security Post) in Izg e town of Gwoza Local Gover nment Area of Borno State. NG-BORNO MCRP-58008-GO -RFQ / Statewide sponsorship for Radio Programming for Pe Strengthening Peace Buildin Request for Quota Single Stage - One E acebuilding Campaign/Conte IDA / 59880 g, Stability and Social Cohesi Post Open - National 475,410.00 0.00 Canceled 2018-10-24 2018-12-19 2019-06-17 tions nvelope nt on deradicalisation, grieva on nce redress and cultural/relig ious tolerance in 27 Local Go vernment Areas of Borno Sta te. NG-BORNO MCRP-130187-G Infrastructure Rehabilitation Request for Quota Single Stage - One E O-RFQ / Supply of Teaching IDA / 59880 and Service Delivery Restora Post Limited 1,154,098.00 967,362.59 Completed 2019-09-11 2019-06-04 2019-10-02 2019-06-24 2019-12-31 2019-07-03 tions nvelope Materials (22 Communities) tion & Improvement NG-BORNO MCRP-130192-G Infrastructure Rehabilitation Request for Quota Single Stage - One E O-RFQ / Supply of First aid Kit IDA / 59880 and Service Delivery Restora Post Limited 144,262.00 133,307.89 Completed 2019-09-14 2019-12-27 2019-10-05 2020-01-18 2019-12-04 2020-02-19 tions nvelope s tion & Improvement NG-BORNO MCRP-130193-G Infrastructure Rehabilitation Request for Quota Single Stage - One E O-RFQ / Procurement of Furni IDA / 59880 and Service Delivery Restora Post Limited 442,623.00 401,290.82 Completed 2019-09-18 2019-07-05 2019-10-11 2019-07-27 2019-12-10 2020-02-21 tions nvelope ture tion & Improvement NG-BORNO MCRP-130209-G Infrastructure Rehabilitation O-RFQ / Furniture for 15 Bloc Request for Quota Single Stage - One E IDA / 59880 and Service Delivery Restora Post Limited 245,902.00 479,285.03 Completed 2019-09-22 2020-01-07 2019-10-14 2020-01-30 2019-12-13 2020-03-21 ks of Classrooms at Umar Ibn tions nvelope tion & Improvement Ibrahim College Bama NG-BORNO MCRP-130227-G Infrastructure Rehabilitation Request for Quota Single Stage - One E O-RFQ / Provisions for Solar e IDA / 59880 and Service Delivery Restora Post Limited 604,980.00 544,223.65 Completed 2019-09-26 2019-07-16 2019-10-17 2019-08-06 2019-11-26 2019-08-23 tions nvelope lectrification to 3 General Ho tion & Improvement spitals NG-BORNO MCRP-130243-G Infrastructure Rehabilitation O-RFQ / Supply of Essential D Request for Quota Single Stage - One E IDA / 59880 and Service Delivery Restora Post Limited 472,131.00 405,142.20 Completed 2019-09-28 2019-07-29 2019-10-21 2019-08-15 2019-11-20 2019-09-09 rugs/Medical Consumables to tions nvelope tion & Improvement 3 General Hospitals Page 5 NG-BORNO MCRP-133079-G Infrastructure Rehabilitation Request for Quota Single Stage - One E O-RFQ / Supply of Medical eq IDA / 59880 and Service Delivery Restora Post Limited 49,180.00 48,000.86 Completed 2019-09-29 2020-06-24 2019-10-21 2020-07-14 2019-12-20 2020-08-06 tions nvelope uipment to Izge CHC, Gwoza tion & Improvement LGA NG-BORNO MCRP-133090-G Infrastructure Rehabilitation O-RFQ / Supply Essential Dru Request for Quota Single Stage - One E IDA / 59880 and Service Delivery Restora Post Limited 157,377.00 179,495.82 Completed 2019-10-06 2020-03-04 2019-10-28 2020-03-25 2019-12-12 2020-04-09 gs/Medical Consumables to 3 tions nvelope tion & Improvement Comprehensive Health Cente rs NG-BORNO MCRP-133095-G Infrastructure Rehabilitation Request for Quota Single Stage - One E O-RFQ / Supply of Medical Eq IDA / 59880 and Service Delivery Restora Post Limited 184,426.00 636,589.86 Completed 2019-10-09 2020-07-10 2019-10-31 2020-08-04 2019-12-30 2020-08-21 tions nvelope uipment to 15 PHCs tion & Improvement NG-BORNO MCRP-133221-G Infrastructure Rehabilitation Request for Quota Single Stage - One E O-RFQ / Supply of Essential D IDA / 59880 and Service Delivery Restora Post Limited 147,541.00 94,876.36 Completed 2019-10-13 2020-10-13 2019-11-04 2020-11-03 2020-01-03 2020-11-20 tions nvelope rugs to 15 PHCs tion & Improvement BORNO/MCRP/GO/RFQ/50/20 Infrastructure Rehabilitation Request for Quota Single Stage - One E / Procurement of Furniture fo IDA / 59880 and Service Delivery Restora Post Limited 245,902.00 320,175.05 Completed 2020-04-12 2020-02-20 2020-05-02 2020-03-11 2020-06-01 2020-04-03 tions nvelope r Library/Offices in Maiduguri tion & Improvement BORNO/MCRP/GO/RFQ/55/20 / Supply of Medical Equipmen Infrastructure Rehabilitation Request for Quota Single Stage - One E t to Primary Healthcare Cent IDA / 59880 and Service Delivery Restora Post Limited 231,982.00 284,337.26 Completed 2020-05-02 2020-09-30 2020-05-23 2020-10-21 2020-07-22 2020-11-07 tions nvelope ers in selected Local Govern tion & Improvement ment Areas of Borno State BORNO/MCRP/GO/RFQ/56/20 Infrastructure Rehabilitation / Supply of Essential Drugs to Request for Quota Single Stage - One E IDA / 59880 and Service Delivery Restora Post Limited 132,787.00 427,444.16 Completed 2020-04-30 2019-11-01 2020-05-21 2019-11-23 2020-06-30 2019-12-18 Primary Healthcare Centers i tions nvelope tion & Improvement n selected Local Government Areas of Borno State BORNO/MCRP/GO/RFQ/57/20 / Installation of Solar Inverter Infrastructure Rehabilitation Request for Quota Single Stage - One E s in Primary Healthcare Cent IDA / 59880 and Service Delivery Restora Post Limited 147,541.00 187,371.86 Completed 2020-04-30 2020-02-25 2020-05-20 2020-03-17 2020-06-29 2020-04-03 tions nvelope ers in selected Local Govern tion & Improvement ment Areas of Borno State BORNO/MCRP/GO/RFQ/59/20 Infrastructure Rehabilitation Request for Quota Single Stage - One E / Provision of Instructional Ma IDA / 59880 and Service Delivery Restora Post Limited 493,096.00 782,803.01 Completed 2020-05-28 2020-12-11 2020-06-18 2021-01-01 2020-12-15 2021-01-16 tions nvelope terials to Schools in Borno St tion & Improvement ate BORNO/MCRP/GO/RFQ/61/20 Infrastructure Rehabilitation Request for Quota Single Stage - One E / Provision of Furniture for Sc IDA / 59880 and Service Delivery Restora Post Limited 657,462.00 120,500.42 Completed 2020-05-31 2020-08-11 2020-06-21 2020-09-02 2020-12-18 2020-09-19 tions nvelope hools in Borno State tion & Improvement BORNO/MCRP/GO/RFQ/62/20 Infrastructure Rehabilitation / Provision of Hospital Equip Request for Quota Single Stage - One E IDA / 59880 and Service Delivery Restora Post Limited 987,515.00 941,856.67 Completed 2020-05-28 2021-03-11 2020-06-18 2021-04-01 2020-12-15 2021-04-27 ment for Tertiary Health Cent tions nvelope tion & Improvement er (Borno State University) BORNO/MCRP/GO/RFQ/63/20 Infrastructure Rehabilitation Request for Quota Single Stage - One E / Provision of Furniture to Pri IDA / 59880 and Service Delivery Restora Post Limited 500,000.00 623,855.70 Completed 2020-05-28 2020-05-08 2020-06-18 2020-06-02 2020-12-15 2020-06-24 tions nvelope mary Healthcare Centers in B tion & Improvement orno State BORNO/MCRP/GO/RFQ/58/20 Strengthening Peace Buildin Request for Quota Single Stage - One E IDA / 59880 Post Limited 2,200,000.00 162,792.85 Completed 2020-04-22 2020-10-27 2020-05-14 2020-11-17 2020-08-12 2020-12-08 / Supply of non Food item Kit g, Stability and Social Cohesi tions nvelope s on BORNO/MCRP/GO/RFQ/54/20 Infrastructure Rehabilitation Request for Quota Single Stage - One E / Installation of Solar Lighting IDA / 59880 and Service Delivery Restora Post Limited 12,020.00 0.00 Canceled 2020-04-17 2020-05-08 2020-06-27 tions nvelope System for Library at Maidug tion & Improvement uri Borno State NG-BORNO MCRP-133085-G Infrastructure Rehabilitation O-RFQ / Supply of Essential D Request for Quota Single Stage - One E IDA / 59880 and Service Delivery Restora Post Limited 78,689.00 0.00 Canceled 2019-09-29 2019-10-21 2019-12-20 rugs/Medical Consumables to tions nvelope tion & Improvement CHC Izge,Gwoza LGA NG-BORNO MCRP-133222-G Infrastructure Rehabilitation Request for Quota Single Stage - One E O-RFQ / Installation of Solar I IDA / 59880 and Service Delivery Restora Post Limited 49,180.00 0.00 Canceled 2019-10-02 2019-10-24 2019-12-23 tions nvelope nverters to 15 PHCs tion & Improvement NG-BORNO MCRP-52158-GO -RFQ / Supply and Installation of Solar Inverters in 15 Prima Infrastructure Rehabilitation Request for Quota Single Stage - One E ry Health Cares in (Ngala, Ng IDA / 59880 and Service Delivery Restora Post Open - National 262,295.00 0.00 Canceled 2019-02-24 2019-04-21 2019-10-18 tions nvelope anzai Kukawa, Biu, Konduga, tion & Improvement Gubio, Askira/Uba, Guzamala , Bama, Jere, Marte, Mobbar, Dikwa, Mafa, Abadam) NG-BORNO MCRP-58872-GO Infrastructure Rehabilitation -RFQ / Books and other learni Request for Quota Single Stage - One E IDA / 59880 and Service Delivery Restora Post Open - National 131,147.54 0.00 Canceled 2019-03-09 2019-05-04 2019-10-31 ng Materials including elibrar tions nvelope tion & Improvement y in the Borno State library NG-BORNO MCRP-133078-G Infrastructure Rehabilitation Request for Quota Single Stage - One E O-RFQ / Installation of Solar I IDA / 59880 and Service Delivery Restora Post Limited 13,115.00 0.00 Canceled 2019-10-02 2019-10-24 2019-12-03 tions nvelope nverters at CHC Izge, Gwoza tion & Improvement LGA BORNO/MCRP/GO/RFQ/51/20 Infrastructure Rehabilitation / Procurement of Books and o Request for Quota Single Stage - One E IDA / 59880 and Service Delivery Restora Post Limited 131,148.00 0.00 Canceled 2020-04-08 2020-04-29 2020-05-29 ther learning materials includ tions nvelope tion & Improvement ing E-Library at Maiduguri, B orno State NG-BORNO MCRP-130215-G Infrastructure Rehabilitation O-RFQ / Supply of Computers Request for Quota Single Stage - One E IDA / 59880 and Service Delivery Restora Post Limited 40,984.00 0.00 Canceled 2019-09-25 2019-10-17 2019-11-16 and other accessories to Um tions nvelope tion & Improvement ar Ibn Ibrahim College Bama BORNO/MCRP/GO/RFQ/53/20 Infrastructure Rehabilitation Request for Quota Single Stage - One E / Procurement of Computers IDA / 59880 and Service Delivery Restora Post Limited 40,984.00 0.00 Canceled 2020-04-15 2020-05-06 2020-06-15 tions nvelope and accessories tion & Improvement NG-BORNO MCRP-130189-G Infrastructure Rehabilitation Request for Quota Single Stage - One E O-RFQ / Supply of Laboratory IDA / 59880 and Service Delivery Restora Post Limited 432,787.00 0.00 Canceled 2019-09-14 2019-10-06 2020-01-04 tions nvelope Equipment tion & Improvement BOMCRP/RFQ/CW/034/019 / Infrastructure Rehabilitation Request for Quota Single Stage - One E Supply of Medical equipment IDA / 59880 and Service Delivery Restora Post Limited 591,716.00 0.00 Canceled 2019-03-02 2019-04-06 2019-04-20 tions nvelope to 1 of 3 (Lassa) General Hos tion & Improvement pitals Page 6 NG-BORNO MCRP-133088-G Infrastructure Rehabilitation O-RFQ / Supply of Medical eq Request for Quota Single Stage - One E IDA / 59880 and Service Delivery Restora Post Limited 196,721.00 0.00 Canceled 2019-09-25 2019-10-16 2019-11-30 uipment to 3 Comprehensive tions nvelope tion & Improvement Health Centers (Hawul, Mobb ar and Damboa) NG-BORNO MCRP-58049-GO -RFQ / Suppy of Computers a Infrastructure Rehabilitation Request for Quota Single Stage - One E nd other accessories to the B IDA / 59880 and Service Delivery Restora Post Open - National 81,967.00 0.00 Canceled 2019-03-09 2019-05-04 2019-10-31 tions nvelope orno State Library , Maidugur tion & Improvement i and Umar Ibn ibrahim colle ge Bama BOMCRP-AF/GO/RFQ/001 / S Contingent Emergency Resp Request for Quota Single Stage - One E Pending Impl upply of Medical Equipment t IDA / 59880 Post Limited 368,852.00 0.00 2021-12-15 2022-02-09 2022-08-08 onse tions nvelope ementation o Magumeri and Gubio BOMCRP-AF/GO/RFQ/002 / S Contingent Emergency Resp Request for Quota Single Stage - One E Pending Impl upply of Essential Drugs/Medi IDA / 59880 Post Limited 200,082.00 0.00 2021-12-18 2022-02-12 2022-08-11 onse tions nvelope ementation cal Consumables to Magume ri and Gubio BOMCRP-AF/GO/RFQ/003 / Pr ovision of Vocational Training Infrastructure Rehabilitation Centre Equipments to Mafa, Request for Quota Single Stage - One E IDA / 59880 and Service Delivery Restora Post Limited 884,616.00 996,264.31 Completed 2022-02-03 2022-02-15 2022-02-23 2022-03-08 2022-05-24 2022-03-22 Magumeri, Jere, Gubio, Mong tions nvelope tion & Improvement uno, Ngala, Bama, A/Uba, Dik wa and Gwoza Local Govern ment Areas BOMCRP-AF/GO/RFQ/004 / Pr ovision of Classroom Furnitur Infrastructure Rehabilitation Request for Quota Single Stage - One E Pending Impl es Mafa (4), Gubio (4), Guza IDA / 59880 and Service Delivery Restora Post Limited 293,343.00 0.00 2022-07-24 2022-09-18 2023-03-17 tions nvelope ementation mala (4), Kaga (4), Marte (4), tion & Improvement Kala Balge (4) Magumeri (4) and Dikwa (4) BOMCRP-AF/GO/RFQ/009 / Pr ocurement of Strategic Com Technical Assistance and Pro Request for Quota Single Stage - One E IDA / 59880 Post Limited 12,919.00 13,964.47 Completed 2022-03-09 2022-07-21 2022-03-29 2022-08-11 2022-09-25 2022-08-23 munications Equipment (Cam ject Management Support tions nvelope eras, Vioce Recorders, Camc orders, CUGS etc) BOMCRP-AF/GO/RFQ/010 / Pr Technical Assistance and Pro Request for Quota Single Stage - One E ocurement of Fire Protective IDA / 59880 Post Limited 20,168.00 8,149.51 Completed 2022-03-10 2022-05-09 2022-03-30 2022-05-28 2022-09-26 2022-06-08 ject Management Support tions nvelope & Prevention Equipments BOMCRP-AF/GO/RFQ/011 / Pr Strengthening Peace Buildin Request for Quota Single Stage - One E ovision of Agric kits and Impl IDA / 59880 g, Stability and Social Cohesi Post Limited 800,926.00 786,674.15 Completed 2021-12-23 2021-10-04 2022-01-12 2021-10-23 2022-07-11 2021-11-11 tions nvelope ements (plought, ridgers,pla on nters,sprayers) BOMCRP-AF/GO/RFQ/012 / Pr Strengthening Peace Buildin ovision of Non-Agricultural Li Request for Quota Single Stage - One E Pending Impl IDA / 59880 g, Stability and Social Cohesi Post Limited 437,493.00 0.00 2022-03-17 2022-04-06 2022-10-03 velihood Kits (Knitting Machi tions nvelope ementation on ne, Sewing Machines, Oil Extr action Machines) BOMCRP-AF/GO/RFQ/014 / Pr Strengthening Peace Buildin Request for Quota Single Stage - One E ocurement of Agricultural inp IDA / 59880 g, Stability and Social Cohesi Post Limited 252,171.00 251,566.42 Completed 2022-05-01 2021-10-04 2022-05-21 2021-10-23 2022-06-20 2021-11-10 tions nvelope uts (Seeds, Pesticides etc) on BOMCRP-AF/GO/RFQ/006 / Pr Technical Assistance and Pro Request for Quota Single Stage - One E IDA / 59880 Post Limited 207,588.00 0.00 Canceled 2022-03-10 2022-03-30 2022-09-26 ocurement of Office Utilities ject Management Support tions nvelope BOMCRP-AF/GO/RFQ/50/021 Infrastructure Rehabilitation / PROCUREMENT OF WATER Request for Quota Single Stage - One E IDA / 59880 and Service Delivery Restora Post Limited 974,229.51 0.00 Completed 2022-06-15 2022-03-31 2022-07-05 2022-08-04 2022-05-26 PURIFIERS TO MAIDUGURI W tions nvelope tion & Improvement ATER TREATMENT PLANT BOMCRP-AF/GO/RFQ/030/20 Infrastructure Rehabilitation 22 / PROCUREMENT OF WOR Request for Quota Single Stage - One E IDA / 59880 and Service Delivery Restora Post Limited 320,233.00 0.00 Completed 2022-11-04 2022-11-28 2022-11-13 2023-01-12 2022-12-28 KING TOOLS AND PERSONAL tions nvelope tion & Improvement PROTECTIVE EQUIPMENT (PP E) FOR LIPW BOMCRP-AF/GO/RFQ/030/02 2 / PURCHASE, INTEGRATION Infrastructure Rehabilitation AND INSTALLATION OF COMP Request for Quota Single Stage - One E IDA / 59880 and Service Delivery Restora Post Limited 257,875.97 0.00 Completed 2023-04-30 2023-03-22 2023-05-20 2023-06-19 UTERIZED HOSPITAL MANAG tions nvelope tion & Improvement EMENT SYSTEM FOR MAJOR HOSPITALS IN MAIDUGURI, B ORNO STATE NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BOMCRP-AF/CS/DIR/032/202 2 / ENGAGEMENT OF PAYMEN Strengthening Peace Buildin T SERVICE PROVIDER (PSP) T IDA / 59880 g, Stability and Social Cohesi Post Direct Selection Direct - National 165,517.00 0.00 Signed 2022-10-10 2022-10-07 2022-10-15 2022-11-20 2022-10-21 2023-10-21 O PROVIDE PAYMENY SERVIC on E TO LABOUR- INTEMSIVE PUBLIC WORKS B ENEFICIARIES CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NG-BORNO MCRP-58894-CS- QCBS / Specialized psycho-so Strengthening Peace Buildin cial support responding to ra Consultant Qualifi IDA / 59880 g, Stability and Social Cohesi Post Open - National 825,230.00 374,263.02 Completed 2018-09-21 2019-07-01 2018-10-12 2019-10-17 2018-11-25 2019-07-03 2018-12-25 2019-07-23 2019-01-29 2019-07-29 2019-07-28 2019-10-11 pid assessment needs/gaps a cation Selection on nd pop to intervene in 27 Loc al Government Areas of Born o State. NG-BORNO MCRP-58895-CS- CQS / Consultancy for the Mo Strengthening Peace Buildin bilisation and Organisation of Consultant Qualifi IDA / 59880 g, Stability and Social Cohesi Post Open - National 442,623.00 0.00 Under Review 2018-09-21 2019-08-23 2018-10-12 2018-11-25 2018-12-25 2019-01-29 2019-07-28 Civic Education with Cultural cation Selection on and Recreational activities wi th 27 Local Government Area s of Borno State Page 7 NG-BORNO MCRP-53660-CS- CQS / Consultancy for Sensiti Strengthening Peace Buildin zation, Community Mobilizati Consultant Qualifi Under Implement IDA / 59880 g, Stability and Social Cohesi Post Open - National 531,148.00 0.00 2018-09-21 2018-10-12 2018-11-25 2018-12-25 2019-01-29 2019-07-28 on and formation of peace gr cation Selection ation on oups within affected Commu nities in 7 Local Government Areas of Borno State NG-BORNO MCRP-58889-CS- CQS / Capacity Building for 1 Strengthening Peace Buildin 0 Local Government Emerge Consultant Qualifi IDA / 59880 g, Stability and Social Cohesi Post Open - National 203,279.00 0.00 Canceled 2019-04-18 2019-04-18 2019-04-18 2019-04-18 2019-04-18 2019-04-18 ncy Management Responder cation Selection on s in Displaced and Transition al Local Government Officials NG-BORNO MCRP-58864-CS- Strengthening Peace Buildin CQS / Training for officials of Consultant Qualifi IDA / 59880 g, Stability and Social Cohesi Post Open - National 16,393.00 0.00 Canceled 2018-06-11 2018-07-02 2018-08-15 2018-09-14 2018-10-19 2019-04-17 relevant State MDAs on effec cation Selection on tive approaches to UASC NG-BORNO MCRP-58382-CS- CQS / Consultancy to provide Strengthening Peace Buildin Consultant Qualifi Capacity building of LG Offic IDA / 59880 g, Stability and Social Cohesi Post Open - National 88,525.00 0.00 Canceled 2018-07-02 2018-07-23 2018-09-05 2018-10-05 2018-11-09 2019-05-08 cation Selection ers for economic planning an on d policy development NG-BORNO MCRP-58040-CS- CQS / Capacity building of L Strengthening Peace Buildin Consultant Qualifi G Officers for local governme IDA / 59880 g, Stability and Social Cohesi Post Open - National 88,525.00 0.00 Canceled 2018-05-25 2018-06-15 2018-07-29 2018-08-28 2018-10-02 2019-03-31 cation Selection nts on budget planning and e on xecution, monitoring and rep orting NG-BORNO MCRP-58752-CS- Strengthening Peace Buildin Consultant Qualifi CQS / Consultancy for Post-C IDA / 59880 g, Stability and Social Cohesi Post Open - National 147,541.00 0.00 Canceled 2018-04-02 2018-04-23 2018-06-06 2018-07-06 2018-08-10 2019-02-06 cation Selection onflict Transitional Justice an on d Accountability NG-BORNO MCRP-53657-CS- CQS / Sensitization, training ( especially on Identification, D Strengthening Peace Buildin ocumentation, Tracing and R Consultant Qualifi IDA / 59880 g, Stability and Social Cohesi Post Open - National 73,770.00 0.00 Canceled 2018-06-11 2018-07-02 2018-08-15 2018-09-14 2018-10-19 2019-04-17 eunification and follow up) a cation Selection on nd coaching for state and no n-state partners on case man agement of UASC (Unaccomp anied and Separated Childre n) NG-BORNO MCRP-58439-CS- Infrastructure Rehabilitation Consultant Qualifi Pending Impleme QCBS / Sensitization and Mob IDA / 59880 and Service Delivery Restora Post Open - National 524,590.00 0.00 2018-09-10 2018-10-01 2018-11-14 2018-12-14 2019-01-18 2019-07-17 cation Selection ntation ilisation for Health (Outreach tion & Improvement Programs) NG-BORNO MCRP-53655-CS- QCBS / Training of Communit y Health Workers (CHeWs, V Infrastructure Rehabilitation Quality And Cost- Under Implement HWs, Midwives) to Staff Targ IDA / 59880 and Service Delivery Restora Post Open - National 531,148.00 0.00 2019-03-18 2019-04-08 2019-05-22 2019-06-19 2019-07-19 2019-08-23 2019-09-27 2020-09-26 Based Selection ation eted Health Facilities (3Nos c tion & Improvement onsultancies across the state . Amount Inclusive of Worksh op and per diem payments) NG-BORNO MCRP-57816-CS- CQS / Consultancy for Educat Strengthening Peace Buildin ional Campaigns, Mobilizatio Consultant Qualifi IDA / 59880 g, Stability and Social Cohesi Post Open - National 442,623.00 225,180.00 Completed 2018-09-03 2019-02-12 2018-09-24 2018-11-07 2019-02-12 2018-12-07 2019-02-12 2019-01-11 2018-10-16 2019-07-10 2018-12-24 n and Sensitization on Mine A cation Selection on ctions & Unexploded Ordinan ces in 27 Local Government Areas of Borno State NG-BORNO MCRP-73783-CS- CQS / Consultancy for Mediat Strengthening Peace Buildin ion and Alternate Dispute Re Consultant Qualifi IDA / 59880 g, Stability and Social Cohesi Post Open - National 147,541.00 139,085.49 Completed 2018-11-05 2019-02-12 2018-11-26 2019-01-09 2019-02-12 2019-02-08 2018-10-16 2019-03-15 2018-10-17 2019-09-11 2018-12-03 solution Capacity Building for cation Selection on peace groups in 27 Local Gov enrment Areas of Borno Stat e BOMCRP/CQS/CS/008/019 / Capacity building of LG Offic Strengthening Peace Buildin Consultant Qualifi ers for Strategic Communicat IDA / 59880 g, Stability and Social Cohesi Post Open - National 22,189.00 37,457.33 Completed 2019-04-09 2019-03-19 2019-04-23 2019-05-03 2019-03-26 2019-05-10 2019-04-15 2019-05-24 2019-04-18 2019-06-07 2019-06-07 cation Selection ions (Legislative Advocacy, M on edia relations, Stakeholder M anagement etc) BOMCRP/CQS/CS/007/019 / Strengthening Peace Buildin Capacity building of LG Offic Consultant Qualifi Under Implement IDA / 59880 g, Stability and Social Cohesi Post Open - National 44,379.00 0.00 2019-04-09 2019-02-22 2019-04-23 2019-05-07 2019-05-14 2019-05-28 2019-06-11 ers for budget planning, exec cation Selection ation on ution, monitoring and reporti ng BOMCRP/CQS/CS/009/019 / Capacity building for 10 Loca Strengthening Peace Buildin Consultant Qualifi l Government Emergency Ma IDA / 59880 g, Stability and Social Cohesi Post Open - National 50,953.00 86,180.00 Completed 2019-04-09 2018-09-20 2019-04-23 2019-05-07 2018-10-11 2019-05-14 2018-10-14 2019-05-22 2018-10-17 2019-06-05 2019-01-03 cation Selection nagement Res ponders in Dis on placed and Transitional Local Government Officials BOMCRP/CQS/CS/010/019 / Sensitization, training on ide Strengthening Peace Buildin ntification, Documentation, T Consultant Qualifi IDA / 59880 g, Stability and Social Cohesi Post Open - National 29,586.00 81,257.63 Completed 2019-04-09 2019-08-08 2019-04-23 2019-11-21 2019-05-07 2019-10-14 2019-05-14 2019-09-05 2019-05-28 2019-11-07 2019-06-11 2019-12-09 racing, Reunification, Follow cation Selection on up and coaching for case ma nagement of UASC (Unaccom panied and Separated Childr en) BOMCRP/CQS/CS/033/019 / I dentification and training of Village Levels Mechanics and Infrastructure Rehabilitation Local area Mechanics in 21 L Consultant Qualifi Pending Impleme IDA / 59880 and Service Delivery Restora Post Open - National 73,964.00 0.00 2019-10-10 2019-10-24 2019-11-14 2019-11-21 2019-12-05 2019-12-19 GAs on operation and mainte cation Selection ntation tion & Improvement nance of existing Hand pump and Solar powered Borehole f or effective utilization and m anagement NG-BORNO MCRP-73723-CS- CQS / Statewide sponsorship for Radio Programming for Pe Strengthening Peace Buildin Consultant Qualifi acebuilding Campaign/Conte IDA / 59880 g, Stability and Social Cohesi Post Open - National 360,782.00 97,154.27 Completed 2019-03-18 2019-05-09 2019-04-01 2019-04-22 2019-04-03 2019-04-29 2019-04-22 2019-05-13 2019-04-25 2019-11-09 2020-04-08 cation Selection nt on deradicalization, grieva on nce redress and cultural/relig ious tolerance in 27 Local Go vernment Areas of Borno Sta te BOMCRP/CQS/CS/020/019 / T Infrastructure Rehabilitation Consultant Qualifi eacher Training and Recertifi IDA / 59880 and Service Delivery Restora Post Open - National 177,515.00 0.00 Completed 2019-09-02 2019-10-02 2019-09-16 2019-10-07 2019-10-02 2019-10-14 2019-10-25 2019-10-28 2019-11-27 2021-01-26 cation Selection cation tion & Improvement Page 8 NG-BORNO MCRP-120946-C Infrastructure Rehabilitation S-CQS / Engagement of Cons Consultant Qualifi IDA / 59880 and Service Delivery Restora Post Open - National 310,965.63 261,765.85 Completed 2019-09-02 2019-05-13 2019-09-09 2019-10-16 2019-09-18 2019-05-20 2019-09-19 2019-06-04 2019-09-21 2019-06-05 2019-10-21 2019-08-27 ultant to Design and Supervis cation Selection tion & Improvement e for Borno PCU 66km Maidu guri-Bama Road NG-BORNO MCRP-120952-C S-CQS / Engagement of Safe Infrastructure Rehabilitation Consultant Qualifi Pending Impleme guard Consultant to produce IDA / 59880 and Service Delivery Restora Post Open - National 9,819.97 0.00 2019-09-02 2019-09-09 2019-09-18 2019-09-19 2019-09-21 2019-10-21 cation Selection ntation ESIA for Borno PCU Gongulon tion & Improvement g-Zabarmari-Dusuman-Gala mari-feeder Road NG-BORNO MCRP-120951-C S-CQS / Engagement of Cons Infrastructure Rehabilitation Consultant Qualifi ultant to Design and Supervis IDA / 59880 and Service Delivery Restora Post Open - National 49,099.84 41,510.55 Completed 2019-09-02 2019-05-01 2019-09-09 2019-10-15 2019-09-18 2019-05-14 2019-09-19 2019-06-03 2019-09-21 2019-06-10 2019-10-21 2019-07-08 cation Selection e for Borno PCU Gongulong-Z tion & Improvement abarmari-Duduman-Galamari -feeder Road NG-BORNO MCRP-120950-C S-CQS / Engagement of Safe Infrastructure Rehabilitation Consultant Qualifi guard Consultant to produce IDA / 59880 and Service Delivery Restora Post Open - National 49,099.84 109,131.56 Completed 2019-09-02 2019-08-08 2019-09-09 2019-11-21 2019-09-18 2019-09-26 2019-09-19 2019-10-16 2019-09-21 2019-10-21 2019-10-21 2020-06-08 cation Selection ESIAand RAP for Borno PCU 6 tion & Improvement 6km Maiduguri-Bama Road BORNO/MCRP/CS/CQS/59/20 / Training on Value addition f Strengthening Peace Buildin Consultant Qualifi Pending Impleme or Women drying fish, peppe IDA / 59880 g, Stability and Social Cohesi Post Limited 132,478.00 0.00 2020-05-04 2020-05-14 2020-05-16 2020-05-21 2020-08-19 cation Selection ntation r, tomato, okro and other pro on ducts using solar tent dryer BORNO/MCRP/CS/CQS/50 / T Strengthening Peace Buildin raining of Community Health Consultant Qualifi Pending Impleme IDA / 59880 g, Stability and Social Cohesi Post Limited 164,787.00 0.00 2020-04-20 2020-05-04 2020-05-06 2020-05-11 2020-06-10 Workers (CHeWs, VHWs, Mid cation Selection ntation on wives) of Targeted Health Fa cilities BORN/MCRP/CS/CQS/54/20 / Strengthening Peace Buildin Consultant Qualifi Pending Impleme Silage, Pellet and Concentrat IDA / 59880 g, Stability and Social Cohesi Post Limited 137,248.00 0.00 2020-04-27 2020-05-07 2020-05-09 2020-05-14 2020-08-12 cation Selection ntation e Feed Making Technology on BORNO/MCRP/CS/CQS/55/20 Strengthening Peace Buildin Consultant Qualifi Pending Impleme / Pasture Production and hay IDA / 59880 g, Stability and Social Cohesi Post Limited 143,675.00 0.00 2020-04-27 2020-05-07 2020-05-09 2020-05-14 2020-08-12 cation Selection ntation making technology on BORNO/MCRP/CS/CQS/56/20 Strengthening Peace Buildin Consultant Qualifi Pending Impleme / Artificial Insemination Tech IDA / 59880 g, Stability and Social Cohesi Post Limited 133,957.00 0.00 2020-04-29 2020-05-09 2020-05-11 2020-05-16 2020-08-14 cation Selection ntation nicians Technology on BORNO/MCRP/CS/CQS/57/20 / Training of extension agent Strengthening Peace Buildin s on Climate Smart Agricultur Consultant Qualifi Pending Impleme IDA / 59880 g, Stability and Social Cohesi Post Limited 147,126.00 0.00 2020-04-22 2020-05-02 2020-05-04 2020-05-09 2020-08-07 e (CAS) concept to sustainabl cation Selection ntation on y increase productivity, enha nce resilience and reduce/re move green house gas emiss ion BORNO/MCRP/CS/CQS/54/20 Strengthening Peace Buildin Consultant Qualifi Under Implement / Regenerative Agriculture an IDA / 59880 g, Stability and Social Cohesi Post Limited 131,525.00 0.00 2020-04-24 2019-02-28 2020-05-08 2020-05-10 2020-05-15 2020-08-13 cation Selection ation d Composting Technology on BORNO/MCRP/CS/CQS/60/20 / Provision of Specialized psy Strengthening Peace Buildin Consultant Qualifi Pending Impleme co-social support responding IDA / 59880 g, Stability and Social Cohesi Post Limited 228,904.00 0.00 2020-05-04 2020-05-14 2020-05-16 2020-05-21 2020-08-19 cation Selection ntation to needs (group support, recr on eational, customary and soci alizing activities referrals) BORNO/MCRP/CS/CQS/51/20 Strengthening Peace Buildin / Sensitization for Health (Ou Consultant Qualifi Pending Impleme IDA / 59880 g, Stability and Social Cohesi Post Limited 261,519.00 0.00 2020-05-04 2020-05-18 2020-05-21 2020-05-27 2020-06-26 treach Programs) in 27 Local cation Selection ntation on Government Areas of Borno State BORNO/MCRP/CS/CQS/58/20 Strengthening Peace Buildin / Capacity Building of Smallh Consultant Qualifi Pending Impleme IDA / 59880 g, Stability and Social Cohesi Post Limited 137,264.00 0.00 2020-04-30 2020-05-10 2020-05-12 2020-05-17 2020-08-15 older farmers on Fertilizer an cation Selection ntation on d Pesticides technologies BORNO/MCRP/CS/CQS/52/20 Strengthening Peace Buildin Consultant Qualifi Pending Impleme / Rainwater Harvesting for Dr IDA / 59880 g, Stability and Social Cohesi Post Limited 134,944.00 0.00 2020-04-20 2020-04-22 2020-05-02 2020-05-06 2020-08-04 cation Selection ntation y Season Irrigation Farming on BOMCRP-AF/CS/CQS/005 / C Strengthening Peace Buildin Consultant Qualifi Pending Impleme onsultancy for the Coordinati IDA / 59880 g, Stability and Social Cohesi Post Limited 159,030.00 0.00 2022-03-23 2022-03-28 2022-04-11 2022-04-15 2022-10-12 cation Selection ntation on of Peace Groups activities on and reporting BOMCRP-AF/CS/CQS/004 / Pr Strengthening Peace Buildin Consultant Qualifi IDA / 59880 Post Limited 210,818.00 0.00 Completed 2022-02-01 2023-03-16 2022-02-06 2022-12-22 2022-02-20 2023-01-09 2022-03-27 2022-09-23 2023-03-13 ovision of Psyco social Suppo g, Stability and Social Cohesi cation Selection rt on BOMCRP-AF/CS/CQS/016 / Es Strengthening Peace Buildin Consultant Qualifi Pending Impleme tablishment of cooperative b IDA / 59880 g, Stability and Social Cohesi Post Limited 88,765.00 0.00 2022-01-31 2022-02-14 2022-02-28 2022-03-04 2022-05-03 cation Selection ntation ased pasture development c on enter BOMCRP-AF/CS/CQS/017 / D evelopment of weather infor mation that is easily accessib Strengthening Peace Buildin le to farmers in local languag Consultant Qualifi Under Implement IDA / 59880 g, Stability and Social Cohesi Post Limited 70,478.00 0.00 2022-04-18 2022-05-02 2022-05-05 2022-05-09 2022-11-05 es including leaflets, brochur cation Selection ation on es,short message system, se nsitization on weather and cli mate change through cinema vans, seminars and worksho ps. BOMCRP-AF/CS/CQS/020/21 Technical Assistance and Pro Consultant Qualifi Under Implement / FUNCTIONAL REVIEW OF PC IDA / 59880 Post Limited 16,000.00 0.00 2022-07-22 2022-07-25 2022-08-05 2022-08-07 2022-08-11 2023-02-07 ject Management Support cation Selection ation U CAPACITY AND SYSTEMS BOMCRP-AF/CS/CQS/030 / E Strengthening Peace Buildin NGAGEMENT OF CONSULTIN Consultant Qualifi IDA / 59880 g, Stability and Social Cohesi Post Limited 202,863.00 0.00 Signed 2022-08-01 2022-07-25 2022-08-15 2022-07-26 2022-08-17 2022-08-15 2022-08-21 2022-10-20 G FIRM FOR THE RECRUITME cation Selection on NT OF HUMAN RESOURCE FO R HEALTH BOMCRP-AF/CS/CQS/006 / C apacity Building Training for Strengthening Peace Buildin Local Government and State Consultant Qualifi Under Implement IDA / 59880 g, Stability and Social Cohesi Post 150,000.00 0.00 2022-08-01 2022-08-01 2022-08-15 2021-10-21 2022-08-17 2021-11-12 2022-08-21 2022-09-20 Officials on Restoration and cation Selection ation on Reinforcement of Community Civil Authority in Borno State Page 9 BOCRP-AF/CS/CQS/007 / Cap acity Building Training for Bo Strengthening Peace Buildin Consultant Qualifi rno State officials on Enhanci IDA / 59880 g, Stability and Social Cohesi Post Limited 150,000.00 0.00 Completed 2022-08-01 2022-08-01 2022-08-15 2021-10-22 2022-08-17 2021-11-12 2022-08-21 2022-09-20 2022-02-15 cation Selection ng Public Participation and Ci on vic Engagement for Budgetar y Process BOMCRP-AF/CS/CQS/008 / C apacity Building Training for Strengthening Peace Buildin State Directors of Finance  a Consultant Qualifi IDA / 59880 g, Stability and Social Cohesi Post Limited 150,000.00 0.00 Under Review 2022-08-01 2022-08-01 2022-08-15 2022-08-17 2022-08-21 2022-09-20 nd Auditors on Effective Inter cation Selection on nal Control and Internal Reve nue Generation Oppurtunitie s for Borno State BOMCRP-AF/CS/CQS/009 / C apacity Building Training for Strengthening Peace Buildin Consultant Qualifi State Government Officials o IDA / 59880 g, Stability and Social Cohesi Post Limited 150,000.00 0.00 Completed 2022-08-08 2022-08-01 2022-08-22 2021-11-04 2022-08-24 2021-11-26 2022-08-28 2022-09-27 2022-02-15 cation Selection n Post COVID-19 Economic R on ecovery and Restoration of Li velihoods in Borno State BOMCRP-AF/CS/CQS/010 / C apacity Building Training for Strengthening Peace Buildin LGA Directors of Planning of Consultant Qualifi Under Implement IDA / 59880 g, Stability and Social Cohesi Post Limited 150,000.00 0.00 2022-08-08 2022-08-01 2022-08-22 2022-10-13 2022-08-24 2022-08-28 2022-09-27 Effective Monitoring and Eval cation Selection ation on uation of Projects and Interve ntions for Sustainable Impact in Borno State BOMCRP-AF/CS/RFP/030/022 Strengthening Peace Buildin / ENGAGEMENT OF PAYMENT Consultant Qualifi IDA / 59880 g, Stability and Social Cohesi Post Limited 64,360.00 0.00 Signed 2022-08-31 2022-08-24 2022-09-14 2022-08-23 2022-09-16 2022-09-09 2022-09-20 2023-03-19 SERVICE PROVIDER FOR HUM cation Selection on AN RESOURCE FOR HEALTH BOMCRP-AF/CS/CQS/031/20 22 / ENGAGEMENT OF IMPLE Strengthening Peace Buildin Consultant Qualifi MENTING PARTNER TO UNDE IDA / 59880 g, Stability and Social Cohesi Post Limited 144,812.00 0.00 Signed 2022-10-14 2022-10-07 2022-10-28 2022-11-07 2022-10-30 2022-11-25 2022-11-03 2023-11-03 cation Selection RTAKE THE IMPLEMENTATION on OF LABOUR - INTENSIVE PUB LIC WORKS BOMCRP-AF/CS/CQS/001 / D evelopment, Integration & In Strengthening Peace Buildin Consultant Qualifi Pending Impleme stallation of Computerized H IDA / 59880 g, Stability and Social Cohesi Post Limited 257,875.97 0.00 2023-04-24 2023-05-08 2023-05-10 2023-05-14 2023-06-13 cation Selection ntation ospital Management Systems on for Major Hospitals in Borno S tate BOMCRP-AF/CS/RFP/001/202 3 / CAPACITY BUILDING TRAI Infrastructure Rehabilitation Consultant Qualifi Pending Impleme NINGS FOR STAFF OF MAJOR IDA / 59880 and Service Delivery Restora Post Limited 74,895.98 0.00 2023-04-21 2023-05-05 2023-05-07 2023-05-11 2023-06-10 cation Selection ntation HOSPITALS IN BORNO STATE tion & Improvement ON COMPUTERIZED HOSPITA L MANAGEMENT BOMCRP-AF/CS/RFP/002/202 3 / Identification and training of Village Levels Mechanics a Infrastructure Rehabilitation Consultant Qualifi Pending Impleme nd Local Area Mechanics on IDA / 59880 and Service Delivery Restora Post Limited 194,174.76 0.00 2023-04-24 2023-05-08 2023-05-10 2023-05-14 2023-06-13 cation Selection ntation Operation and Maintenance o tion & Improvement f existing Hand Pump and Sol ar powered Borehole for effe ctive utilization and manage ment. BOMCRP-AF/CS/RFP/003/202 Infrastructure Rehabilitation Consultant Qualifi Pending Impleme 3 / TRAINING AND STRENGTE IDA / 59880 and Service Delivery Restora Post Limited 249,653.26 0.00 2023-04-28 2023-05-12 2023-05-14 2023-05-18 2023-06-17 cation Selection ntation NING OF WASHCOM tion & Improvement BOMCRP-AF/CS/RFP/004/202 Infrastructure Rehabilitation Consultant Qualifi Pending Impleme 3 / TRAINING of LGA SANITAT IDA / 59880 and Service Delivery Restora Post Limited 149,653.26 0.00 2023-05-01 2023-05-15 2023-05-17 2023-05-21 2023-06-20 cation Selection ntation ION AND HYGIENE OFFICERS tion & Improvement INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NG-BORNO MCRP-58865-CS- INDV / Consultancy for Regist Strengthening Peace Buildin ration, Mapping and Profiling Individual Consult IDA / 59880 g, Stability and Social Cohesi Post Open - National 49,180.00 0.00 Completed 2018-11-05 2019-08-12 2018-11-05 2019-09-11 2018-11-05 2019-09-13 2018-11-05 2018-11-05 of all local government struct ant Selection on ures and existing capacities State Wide in 27 Local Gover nment Areas of Borno State BOMCRP-CS-CDS-02-20 / SU Infrastructure Rehabilitation PERVISION OF REHABILITATI IDA / 59880 and Service Delivery Restora Post Direct Selection Direct 260,000.00 257,593.78 Signed 2021-05-03 2021-08-10 2021-05-08 2021-09-02 2021-05-17 2021-09-25 2023-11-03 ON OF 66KM MAIDUGURI-BA tion & Improvement MA ROAD Page 10 PROCUREMENT PLAN (Textual Part) Project information: Country: Nigeria Project Name: Multi-Sectoral Crisis Recovery Project for North East Nigeria (MCRP) P- Number: P157891 Project Implementation Agency: MCRP PCU (Federal and States) Date of the Procurement Plan: Updated -December 22, 2017. Period covered by this Procurement Plan: From 01/12/2018 – 30/06/2019. Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the FGN Public Procurement Act 2007; such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. “Not Applicable” THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables. “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Specify for each: Goods: is not applicable for those contracts identified in the Procurement Plan tables; Works: is not applicable for those contracts identified in the Procurement Plan tables. Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations is Applicable. Other Relevant Procurement Information. 1. Prior Review Threshold for Goods, Works and Non-Consulting Services: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Prior Review Procurement Method Threshold (US$ Comments equivalent) ICB and LIB (Goods and services other than ≥ 5,000,000 ALL consultancy services) NCB (Goods, IT Systems and Non Consulting Services 100,000 < 5,000,000 NONE (NCB) ICB (Works) ≥ 20,000,000 ALL NCB (Works) 150,000 < 20,000,000 NONE Shopping-Goods ≤ 100,000 NONE Shopping-Works ≤ 150,000 NONE Based on Annual Training, Workshops, Study All Values Work Plans & Tours Budgets 2. Prequalification: Bidders for major works shall be prequalified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines, although it is not expected that there will be need for prequalification in the procurement arrangements for the MCRP. MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 2 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT 3. Proposed Procedures for CDD Components (as per paragraph. 6.52 of the Procurement Regulations): Shall apply. 4. Reference to the Project Implementation Manual: Shall apply. 5. Any Other Special Procurement Arrangements: Not Applicable 6. Procurement Packages (Goods and Works) indicating Bank’s Prior and Post Review. MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 3 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT a. Summary of Procurement of Goods: 1 2 3 4 5 6 Review by Estimated Ref. Packag Bank Commen Description Cost (US$ No. es (Prior / ts Million) Post) Total NCB 12.82 43 Post (Goods) Total RfQ (Goods/Non 0.04 1 Post Consulting Services) Procurement of Goods with Selection Methods and Time Schedule (Please see Annex I). b. Summary of Procurement of Civil Works 1 2 3 4 5 6 Review by Estimated Ref. Bank Commen Description Cost (US$ Packages No. (Prior / ts Million) Post) Total NCB 23.59 64 Post (Works) Total RfQ 2.29 20 Post (Works) Procurement of Civil Works with Selection Methods and Time Schedule (Please see Annex II). c. Summary of Procurement of Non- Consulting Services (TBD) 1 2 3 4 5 6 Review by Estimated Ref. Bank Commen Description Cost (US$ Packages No. (Prior / ts Million) Post) Total NCB 0.175 2 Post MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 4 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT 7. Prior Review Threshold for Consultancies: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Prior Review Selection Method Comments Threshold (USD) Consultant Services-QCBS- International 1. Consulting Services ≥ 300,000 ALL 2. Engineering and Construction ≥ 500,000 Supervision Consultant Services-QCBS < 300,000.00 NONE Consultant Services-CQS < 300,000.00 NONE Consultant Services-lC >300,000.00 ALL Consultant Services-lC <300,000.00 NONE Consultant Services- Single Source All Values ALL Selection Note: All ToRs to be prior review QCBS = Quality and Cost Based Selection SSS = Single Source Selection CQ = Consultant Qualification LCS = Least Cost Selection IC = Individual Consultant 8. Short list comprising entirely of National Consultants: Short list of consultants for services, estimated to cost less than $300,000.00 equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. a. Summary of Consultancies 1 2 3 4 5 6 Ref. Description Estimate Package Review by Comment No. d Cost s Bank s (US$ (Prior/Post Million) ) Summary of number of 5.72 7 Prior contracts that will be let under International QCBS Summary of number of 6.45 16 Post contracts that will be let under National QCBS Summary of number of 1.74 30 Post contracts that will be let under CQS Summary of number of 0.35 3 Post contracts that will be let under MOU MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 5 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Summary of number of 0.021 3 Post contracts that will be let under Individual Consultancies MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 6 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Estimated Estimated Prior Number of Amount in Investable or Expected Procureme Pre- USD (Over Amount Post Bid- Description (List of Componen nt Procureme qualificati the Project for 18 Revie Opening Contracts) t/Sector Packages nt Method on Life) months w Date WORKS BORNO Construction Of 18-No Double Classroom Blocks in Ngohi, Biji-Biji, Ngulde, C2/Educati Post Tue-19-Jun- Rumirgo, Chul on 3 NCB No 708,196.72 354,098.36 Review 18 Construction Of 10- No. Double Classroom Block - C2/Educati Post Tue-19-Jun- Bama (Banki Town) on 2 NCB No 393,442.62 314,754.10 Review 18 Reconstruction Of 39- No. Double Classroom Block in C2/Educati Post Damasak, Mobbar on 4 NCB No 575,409.84 71,926.23 Review Tue-24-Jul-18 Construction Of 15- No. Double Classroom Block - C2/Educati Post Gajibo, Logomane (Dikwa) on 2 NCB No 590,163.93 147,540.98 Review Tue-24-Jul-18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 7 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Construction Of 25 No. Double Classroom Block C2/Educati Post GUZAMALA on 2 NCB No 983,606.56 245,901.64 Review Tue-24-Jul-18 Construction Of 20- No. Double Classroom Block - Kukawa Town, Baga, Cross- C2/Educati Post Tue-18-Sep- Kauwa on 2 NCB No 786,885.25 196,721.31 Review 18 Construction Of 10- No. Double Classroom Block - C2/Educati Post Tue-18-Sep- Monguno on 1 NCB No 393,442.62 98,360.66 Review 18 Construction Of 4- No. Double Classroom Block in C2/Educati Post Tue-20-Nov- Ajiri. Mafa on 1 NCB No 157,377.05 39,344.26 Review 18 Renovation Of 20- No. Double Classroom Blockin C2/Educati Post Tue-20-Nov- Damboa Town -Abadam on 2 NCB No 295,081.97 73,770.49 Review 18 Renovation Of 31- No. Double Classroom Block - C2/Educati Post Tue-23-Oct- Bama on 2 NCB No 457,377.05 114,344.26 Review 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 8 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Construction Of 3-No. C2/Educati Post Tue-18-Sep- Educational Office -Kukawa on 1 NCB No 196,721.31 98,360.66 Review 18 Construction Of 2-No. Educational Office - C2/Educati Post Tue-20-Nov- Konduga on 1 NCB No 131,147.54 32,786.89 Review 18 Construction Of 2-No. Educational Office -Hawul C2/Educati Post Tue-23-Oct- Sakwa, Kwajafa on 1 NCB No 131,147.54 32,786.89 Review 18 Construction Of 4-No Vip C2/Educati Post Tue-18-Dec- Toilets -Askira-Uba on 1 RfQ No 59,016.39 47,213.11 Review 18 Construction Of 4-No Vip C2/Educati Post Tue-18-Dec- Toilets -Mafa on 1 RfQ No 59,016.39 47,213.11 Review 18 Construction Of 5-No Vip C2/Educati Post Tue-18-Dec- Toilets -Monguno on 1 RfQ No 73,770.49 59,016.39 Review 18 Renovation Of 1-No. Educational Office - C2/Educati Post Tue-18-Dec- Damboa on 1 RfQ No 18,032.79 4,508.20 Review 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 9 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Renovation Of 1-No. Educational Office and 1- No. Principal's Quarters - Benisheik, Kaga- Benisheik, C2/Educati Post Tue-23-Oct- Kaga on 1 RfQ No 42,622.95 16,803.28 Review 18 Rehabilitation of 66KM C2/Transpo 1,223,144. Prior Tue-27-Feb- Maiduguri to Bama road rt 1 NCB No 9,785,152.68 08 Review 18 Rehabilitation of 1 Ngala C2/Transpo Prior Tue-27-Feb- Bridge rt 1 NCB No 2,295,081.97 483,983.71 Review 18 C2/Transpo Post Tue-27-Feb- Rehabilitation of Biu bridge rt 1 NCB No 902,111.48 73,770.49 Review 18 Construction of galameri- dusuman-zabarmari- C2/Transpo Prior Tue-27-Feb- gongulong feeder road rt 1 NCB No 1,104,625.69 59,016.39 Review 18 RehabilitatIon of 3 General Hospital in ABADAM, ASKIRA UBA, KALA-BALGEe and Rehabilitation of Prior Tue-27-Mar- comprehensive Healthcare C2/Health 3 NCB No 1,555,779.01 986,195.83 Review 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 10 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT center (Civil Works, Solar Borehole, Fence & Security Post) Construction of PHC for 15 2,254,098. Prior Tue-27-Mar- LGAs C2/Health 5 NCB No 3,606,557.38 36 Review 18 Rehabilitation of Borno C2/Educati Post Tue-24-Apr- State Library on 2 NCB No 557,377.05 34,426.23 Review 18 Rehabilitation of Umar Ibn C2/Educati Post Tue-24-Apr- Ibrahim college Bama on 2 NCB No 557,377.05 278,688.52 Review 18 Construction of Solar Powered Boreholes (2Nos) in Umar Ibn Ibrahim college Bama Solar Lighting System to Borno C2/Educati Post Tue-24-Apr- Library on 1 NCB No 196,721.31 98,360.66 Review 18 Rehabilitation of Court Buildings in Bama Gwoza C2/Public Post Tue-22-May- Dikwa Mobbar Buildings 4 RfQ No 393,442.62 49,180.33 Review 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 11 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Rehabilitation of Local Govt Secretariats in Kukawa, Monguno, biu ,Abadam, Kala-Balge, Marte, C2/Public 1,229,508. Post Tue-05-Jun- Magumeri, Guzamala Buildings 8 RfQ No 1,967,213.11 20 Review 18 Rehabilitation of Traditional Rulers' Konduga , Monguno, Kukawa, Nganzai, Baga, Marte, Ngala, Abadam, Guzamala, C2/Public Post Tue-05-Jun- Kwajafa, Kumshe Buildings 6 RfQ No 1,442,622.95 180,327.87 Review 18 Provision of Community Resource Centres in 20 C2/Public Post LGAs Buildings 10 NCB No 2,295,081.97 860,655.74 Review Thu-05-Jul-18 Construction of Handpump Wells in Bama (3) Chibok (5), Biu (5), Mafa(3), Hawul (5), Askira/Uba(5), Konduga(4), Jere(5) Dikwa Post Fri-03-Aug- (3), Gwoza(5), C2/WASH 10 RfQ No 140,983.61 35,245.90 Review 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 12 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Construction of Solar Powered Boreholes in Askira Uba Gwoza(4),Bama(4), Ngala(3), Damboa(3) Jere(4),Kukawa(3), Biu(2),Konduga(3), Gubio(3), Askira/Uba(3), Magumeri(3), Marte(3), Mobbar(3), Monguno(3), Dikwa(2), Mafa(3), Abadam(3), Nganzai(3), Guzamala(3), Kaga(2), Chibok(2), Kala/Balge(3), Hawul(2)(To include 2Nos 5,000lt Plastic water tanks on a 1.5m raised platform , five fetching points/tap gallery, chain link 3,501,639. Post Wed-25-Jul- perimeter fence) C2/WASH 14 NCB No 4,668,852.46 34 Review 18 REHABILITATION OF LOCAL GOVERNMENT LODGES (Marte, Kaga, Chibok, Magumeri, Gwoza, Kala- Balge, Ngala, Guzamala, Abadam, Hawul, C2/Public Post Tue-21-Aug- Askira/Uba, Bama) Buildings 6 NCB No 1,311,475.41 786,885 Review 18 Rehabilitationof Traditional Rulers' Buildings Bama, Konduga, Gwoza ,Kareto, C2/Public Post Damboa , Monguno, Buildings 11 RfQ No 1,442,622.95 180,327.87 Review Thu-26-Jul-18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 13 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Kukawa, Askira-Uba , Dikwa, Baga, Marte REHABILITATION OF MINISTRY BUILDING (Ngala, C2/Public Post Tue-21-Aug- Monguno) Buildings 2 NCB No 276,577 Review 18 CONSTRUCTION OF SANITATION FACILITIES IN 21 LOCAL GOVERNMENT AREAS.ABADAM (6) ASKIRA(6) BAMA(6) BIU(6) CHIBOK(6) DAMBOA(6) DIKWA(6) GUBIO(6) GWOZA(6) JERE(6) KAGA(6) KALA-BALGE(6) KONDUGA(6) KUKAWA(6) MAFA(5) MOBBAR(6) MONGUNO(6) MARTE(6) NGALA(6) NGANZAI(6) Post Wed-19-Sep- MAGUMERI(6) C2/WASH 21 NCB No 781,517 Review 18 REHABILITATION OF EXISTING NON- FUNCTIONAL BOREHOLES ABADAM (1) ASKIRA UBA (2) BIU (2) DIKWA (1) Post Tue-18-Sep- GUBIO (1) GUZAMALA (1) C2/WASH 6 NCB No 258,525 Review 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 14 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT JERE (2) KALA BALGE (1) MAFA (2) MAGUMERI (1) MARTE (2) MOBBAR (1) NGALA (1) NGANZAI (1) Rehabilitation of 8 blocks of Laborataries (Umar Ibn C1/Educati Post Tue-18-Sep- Ibrahim college Bama) on 1 NCB No 262,295 Review 18 ADAMAWA Rehabilitation of Gulak Post Mon-14-May- Water Supply System C2/Water 1 NCB No 179,190.16 134,392.62 Review 18 Rehabilitation of Hong Post Mon-14-May- Water Supply System C2/Water 1 NCB No 116,646.90 87,485.18 Review 18 Rehabilitation of Michika Post Mon-14-May- Water supply system C2/Water 1 NCB No 138,193.44 103,645.08 Review 18 Rehabilitation of Uba Water Post Tue-15-May- Supply system C2/Water 1 NCB No 71,967.21 71,967.21 Review 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 15 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Rehabilitation of exisitng Water Supply sources in Post Tue-15-May- Gombi C2/Water 1 NCB No 30,475.41 30,475.41 Review 18 Construction of Uba New Post Mon-28-May- Water Supply Project C2/Water 1 NCB No 721,222.95 108,183.44 Review 18 Pella New Water Supply Post Mon-28-May- Project C2/Water 1 NCB No 555,289.34 83,293.40 Review 18 Construction of Hong New Post Mon-28-May- Water supply project C2/Water 1 NCB No 1,256,442.62 188,466.39 Review 18 Construction of Michika Post Tue-29-May- New Water supply project C2/Water 1 NCB No 1,189,261.84 178,389.28 Review 18 Construction GOMBI NEW Post Tue-29-May- WATER SUPPLY PROJECT C2/Water 1 NCB No 915,241.80 137,286.27 Review 18 Installation of 12 nos. Solar Boreholes (in secondary schools)- GSS Gombi, GDSS Garkida, GSS Hong, GDSS Pella, GSSS Uba, Post Thu-10-May- GJSS Uba, GDSS Garaha, C2/Water 1 NCB No 377,609.70 75,521.94 Review 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 16 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT GDSS Kwarhi, GDSS Za'ah, GSS Madagli, GSS Shuwa, GSS Gulak, GCSS Shuwa Installation of 37 Nos Solar Boreholes in 37 Health Centers in 7 Local Post Thu-10-May- Governments Areas C2/Water 4 NCB No 1,164,296.59 291,074.15 Review 18 Construction of 295Nos Hand Powered Bore Holes (in 2 primary schools per 35 wards, 35 Markets, 35 Motor parls and 155 Communities across 7 Post Thu-03-May- LGAs) C2/Water 4 NCB No 1,257,377.05 503,483.61 Review 18 Construction of VIP Latrines of 3-Comp (2 Blks Post Tue-14-Aug- in 24 pri sch) C2/WASH 3 RfQ No 212,459.02 79,672.13 Review 18 VIP Latrine of 3-Comp (2 Post Tue-14-Aug- Blks in 26 Markets) C2/WASH 3 RfQ No 230,163.93 92,065.57 Review 18 VIP Latrine of 3-Comp (2 Post Tue-14-Aug- Blks in 26 Motor Parks) C2/WASH 3 RfQ No 230,163.93 92,065.57 Review 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 17 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Rehabilitation of Lokwa C2/Transpo Post Mon-11-Jun- Bridge Mubi rt 1 NCB No 475,143.96 356,357.97 Review 18 Reconstruction of Main Road - Bangshika Road C2/Transpo Prior Mon-11-Jun- 2.5Km rt 1 NCB No 1,019,295.08 127,411.89 Review 18 Rehabilitation of Mubi Bazza Road with a spur to C2/Transpo 1,255,469. Prior Mon-11-Jun- Mayo Bani 45Km rt 1 NCB No 8,369,796.72 51 Review 18 Rehabilitation of PHC, Construction of Perimeter Fence and Staff Quarters (Civil Works, Solar Borehole, Fence & Security C2/Educati Prior Tue-10-Apr- Post) in 7 Communities on 7 NCB No 1,139,130.43 451,779.49 Review 18 Rehabilitation of Cottage Post Tue-10-Apr- Hospital C2/Health 1 NCB No 451,768.85 192,001.76 Review 18 Establishment of Trauma Post Thu-17-May- Center @ general hospital C2/Health 1 RfQ No 65,194.96 65,194.96 Review 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 18 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Renovation of GSS in 10 Towns (Gombi, Hong, Uba, Shuwa, Michika, Bazza, Mubi 1, Maiha, Madagali, C2/Educati Post Mubi North) on 10 NCB No 2,305,292.65 442,327.22 Review Tue-10-Jul-18 Renovation of 25Nos C2/Educati Post Primary School over 7 LGAs on 4 NCB No 865,747.88 324,655.45 Review Tue-10-Jul-18 Rehabilitation of Local Government Secretariat - C2/Public Post Thu-07-Jun- Song Buildings 1 NCB No 288,590.56 144,295.28 Review 18 Rehabilitation of Local Government Secretariat - C2/Public Post Thu-07-Jun- Madagali Buildings 1 NCB No 315,082.89 157,541.44 Review 18 Rehabilitation of District Head's Palace in 5 Communities (Uba, Gella, Gombi, Maiha/Pakka, C2/Public Post Thu-07-Jun- Gulak) Buildings 5 NCB No 422,463.57 158,423.84 Review 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 19 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT YOBE Conversion of Motorised Boreholes (28 Communities in Gulani and Damaturu) into Solar Post Mon-26-Mar- Powered C2/Water 1 NCB No 334,013.66 250,510.24 Review 18 Conversion of existing Motorized powered Borehole without Overhead tank into solar powered (Gujba, Gulani, Yunusari, Damaturu,& Post Mon-26-Mar- Geidam ) C2/Water 1 NCB No 277,532.56 208,149.42 Review 18 Conversion of existing Motorized powered Borehole into solar powered and construction of New Overhead tank (Gujba, Gulani, Yunusari, Post Mon-26-Mar- Damaturu,& Geidam) C2/Water 2 NCB No 542,490.73 406,868.05 Review 18 Drilling of New Solar Powered Boreholes in Gujba, Gulani, Yunusari, Damaturu, Fika, Potiskum, Post Mon-02-Apr- Geidam & Fune C2/Water 2 NCB No 878,917.25 329,593.97 Review 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 20 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Rehabilitation of Solar Powered Boreholes in Gulani, Gujba and Post Mon-02-Apr- Damaturu C2/Water 1 NCB No 244,228.65 183,171.49 Review 18 Construction & Upgrade of Post Wed-24-Oct- 33 nos. PHC Centres C2/Health 5 NCB No 5,386,554.10 538,655.41 Review 18 Reconstruction of Vandalized 3 Nos Post Wed-09-May- Immunization Offices C2/Health 1 RfQ No 68,618.27 68,618.27 Review 18 Renovation of 1No. General Post Mon-03-Sep- Hospital in Buni Yadi C2/Health 1 RfQ No 88,524.59 44,262.30 Review 18 Construction of 1No. Student Hostel each in College of Nursing and Midwifery Damaturu and College of Health Sciences Post Wed-22-Aug- and Technology, Nguru C2/Health 2 NCB No 983,606.56 245,901.64 Review 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 21 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Renovation of Govt Secondary Schools in Goniri,Bara, Bularafa, ,Kananma, Damagum, Buni Yadi, Kukuwa, Gujba and C2/Educati Post Mon-09-Apr- Best Center in Goniri on 5 NCB No 2,001,760.77 800,704.31 Review 18 Renovation of Dokshi C2/Educati Post Mon-09-Apr- Primary school, Gulani on 1 NCB No 168,034.42 67,213.77 Review 18 Rehabilitation of Local Government Office Secretariat in Gujba and C2/Public Post Wed-09-May- Potiskum Buildings 2 NCB No 472,529.40 75,459.62 Review 18 Rehabilitation of Development Offices in Gujba , Gulani, Yunusari & C2/Public Post Wed-09-May- Geidam Buildings 1 RfQ No 62,203.18 15,550.80 Review 18 Provision of Community Resource Centres in all 17 C2/Public Post Wed-23-May- LGAs Buildings 5 NCB No 1,950,819.67 731,557.38 Review 18 Rehabilitation of Audit C2/Public Post Wed-26-Sep- Office Buildings 1 RfQ No 63,078.12 15,769.53 Review 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 22 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Rehabilitation of Zonal C2/Public Post Wed-26-Sep- Statistical Office Buildings 1 RfQ No 50,491.80 25,245.90 Review 18 Rehabilitation ofCultural Buildings (District Head's Palace) in Buni Yadi and C2/Public Post Mon-27-Aug- Damagum Buildings 2 NCB No 446,682.62 111,670.66 Review 18 Rehabilitation of Government Buildings; C2/Public Post Mon-11-Jun- Agency for Mass Literacy Buildings 1 RfQ No 121,445.24 60,722.62 Review 18 Rehabilitation of Government Buildings; C2/Public Post Mon-11-Jun- Town Engineers Office Buildings 1 RfQ No 121,445.24 60,722.62 Review 18 GOODS BORNO Supply of Returnee C1/Transiti Resettlement Kits Bama, onal 2,216,737. Tue-13-Feb- Dikwa, Gwoza, Ngala, Support 4 NCB No 2,216,737.30 30 Post 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 23 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Monguno, Damboa, Gudumbali, Mobbar, Kala Balge) Supply of Agricultural Support kits with Seeds, Fertilizers and Small Work Farm Tools (Bama, Biu, Gwoza, Ngala, Monguno, C1/Transiti Damboa, Askira, Mobbar, onal Tue-13-Feb- Kukawa) Support 3 NCB No 681,729.10 681,729.10 Post 18 Supply of Small Animals (Bama, Mafa, Gwoza, Ngala, Monguno, Damboa, C1/Transiti Chibok, Nganzai, Kala onal Tue-20-Feb- Balge) Support 3 NCB No 788,935.25 788,935.25 Post 18 Supply of Non-agricultural Livelihood Kits (Bama, Dikwa, Gwoza, Ngala, C1/Transiti Monguno, Damboa, Chibok, onal Tue-13-Feb- Mobbar, Hawul Support 2 NCB No 227,377.05 227,377.05 Post 18 C1/Transiti Supply of Skills Acquisition onal Tue-20-Feb- Start up Kits Support 3 NCB No 737,704.92 387,295.08 Post 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 24 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Supply of solar electrification to 3 GENERAL HOSPITALS in ABADAM, GWOZA and KALA-BALGE and five Comprehensive Health Centre in Abadam, 2 in Gwoza, Kala-Balge, Askira - Tue-01-Jan- Uba C2/Health 3 NCB No 670,553.40 516,770.59 Post 19 Supply of Medical Equipment For 3General Hospitals in ABADAM, ASKIRA UBA, and KALA- Tue-15-Jan- BALGE C2/Health 3 NCB No 590,163.93 73,770.49 Post 19 Supply of Essential Drugs/Medical Consumables For 3 General Hospitals in HAWUL, Tue-05-Mar- MOBBAR AND DAMBOA C2/Health 3 NCB No 472,131.15 59,016.39 Post 19 Supply of Medical Equipment for Comprehensive Health Wed-09-Jan- Centers (Gwoza- Izge) C2/Health 1 NCB No 245,901.64 30,737.70 Post 19 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 25 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Supply of Essential Drugs/Medical Consumables for Comprehensive Health Tue-05-Feb- Center (Gwoza-izge) C2/Health 1 NCB No 236,065.57 29,508.20 Post 19 Supply of Medical Equipment to 15 PHCs to (Ngala, Nganzai Kukawa, Biu, Konduga, Gubio, Askira/Uba, Guzamala, Bama, Jere, Marte, Mobbar, Dikwa, Tue-15-Jan- Mafa, Abadam) C2/Health 2 NCB No 983,606.56 122,950.82 Post 19 Supply of Essential Drugs to 15 PHCs (Ngala, Nganzai Kukawa, Biu, Konduga, Gubio, Askira/Uba, Guzamala, Bama, Jere, Marte, Mobbar, Dikwa, Tue-05-Feb- Mafa, Abadam) C2/Health 2 NCB No 786,885.25 98,360.66 Post 19 Supply and Installation of Solar Inverters in 15 PHCs in (Ngala, Nganzai Kukawa, Biu, Konduga, Gubio, Askira/Uba, Guzamala, Bama, Jere, Marte, Mobbar, Tue-06-Mar- Dikwa, Mafa, Abadam) C2/Health 1 NCB No 262,295.08 65,573.77 Post 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 26 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Furniture for Library/ Offices in the Borno State Library and Furniture for 15 blocks of classrooms in Umar Ibn ibrahim college C2/Educati Tue-19-Mar- Bama on 2 NCB No 491,803.28 245,901.64 Post 19 Books and other learning Materials including elibrary C2/Educati Tue-19-Mar- in the Borno State library on 1 NCB No 262,295.08 131,147.54 Post 19 Suppy of Computers and other accessories to the Borno State Library , Maiduguri and Umar Ibn C2/Educati Tue-19-Mar- ibrahim college Bama on 2 RfQ No 81,967.21 40,983.61 Post 19 Supply of Medical Equipment TO 3 Comprehensive Health centers IN HAWUL, MOBBAR AND DAMBOA Tue-06-Mar- (Kwajafa, Kareto, Damboa) C2/Health 1 NCB No 196,721.31 49,180.33 Post 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 27 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Installation of solar inverters for PHC Gwoza( Tue-06-Mar- Izge) C2/Health 1 NCB No 13,114.75 13,114.75 Post 18 ADAMAWA C1/Transiti Supply of Returnee onal Mon-19-Mar- Resettlement Kits Support 2 NCB No 490,780.33 490,780.33 Post 18 Supply of Agricultural Support kits with Seeds, C1/Transiti Fertilizers and Small Work onal 1,496,508. Mon-19-Mar- Farm Tools Support 7 NCB No 1,496,508.20 20 Prior 18 C1/Transiti onal Thu-19-Apr- Supply of Small Animals Support 1 NCB No 182,950.82 182,950.82 Post 18 C1/Transiti Supply of Non-agricultural onal Mon-19-Mar- Livelihood Kits Support 1 NCB No 213,442.62 213,442.62 Post 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 28 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT C1/Transiti Start up kits for quick to onal Mon-19-Mar- market trading Support 1 NCB No 114,754.10 114,754.10 Post 18 Housing Refurbishment Returnee Packs for Voluntary Returnees across C1/Transiti the 7 LGAs being onal Thu-14-Jun- rehabilitated. Support 2 NCB No 390,163.93 331,639.34 Post 18 Supply of Medical Equipment to PHCs in 7 communities and Cottage Hospital in Gulak C2/Health 2 NCB No 344,262.30 43,032.79 Post Thu-19-Jul-18 Supply of Essential Drugs/Medical Consumable to PHCs in 7 Communities and Cottage Hospital in Thu-01-Nov- Gulak C2/Health 2 NCB No 452,459.02 108,196.72 Post 18 Installation of Solar Inverters in 7 Rehabilitated PHCs, Cottage Hospital in Mon-06-Aug- Gulak C2/Health 3 NCB No 268,861.16 18,852.46 Post 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 29 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Equipping of Trauma Center @ Michika General Mon-06-Aug- hospital C2/Health 1 NCB No 214,142.46 80,303.42 Post 18 Supply of Furniture to C2/Educati Thu-29-Mar- Primary Schools in 7 LGAs on 1 NCB No 245,901.64 30,737.70 Post 18 Supply of Books and Teaching/Learning Materials to Primary C2/Educati Thu-29-Mar- Schools in 7 LGAs on 1 NCB No 327,868.85 122,950.82 Post 18 Establishment of spare part supply chain/buffer Mon-16-Apr- stock for Water Facilities C2/WASH 1 NCB No 114,754.10 86,065.57 Post 18 Train the Trainer/User Workshops (i.e. 2 per LGA) for VLOM (Village Level Operation and Maintenance) WASHCOMS, (WASH Committees at LGA Level, WASH Units @ LGAs, VHPs (Voluntary Hygiene Promoters) State/LGA Govt Tue-24-Apr- Officials. C2/WASH 1 NCB No 72,131.15 54,098.36 Post 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 30 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT YOBE C1/Transiti Supply of Non Food Items onal Wed-21-Mar- (NFIs) Kits Support 3 NCB No 559,213.11 559,213.11 Post 18 C1/Transiti Supply of Agricultural kits onal 1,048,940. Wed-21-Mar- with seeds, oil, small tools Support 3 NCB No 1,048,940.98 98 Post 18 C1/Transiti onal Mon-23-Apr- Supply of Small Animals Support 3 NCB No 688,524.59 688,524.59 Post 18 C1/Transiti Non-agricultural Livelihood onal Mon-26-Mar- kits Support 2 NCB No 352,295.08 352,295.08 Post 18 C1/Transiti Supply of Skills Acquisition onal Wed-21-Mar- Start up Kits Support 3 NCB No 786,885.25 550,819.67 Post 18 Procure and distribute Plumpy Nuts for Wed-25-Apr- malnourished children in C2/Health 1 NCB No 215,438.65 32,315.80 Post 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 31 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Gujba, Geidam and Yunusari LGAs Equipping of Trauma Mon-12-Feb- Center C2/Health 1 NCB No 214,147.54 53,536.89 Post 18 Supply of Students Textbooks and Teachers' C2/Educati Mon-17-Sep- Guides on 1 NCB No 284,062.30 71,015.57 Post 18 Supply of Laboratory Equipment Physics. C2/Educati Mon-17-Sep- Chemistry & Biology on 1 NCB No 213,114.75 53,278.69 Post 18 C2/Educati Mon-17-Sep- Supply of School Furniture on 3 NCB No 804,885.25 201,221.31 Post 18 CONSULTING SERVICES BORNO Skills Acquisition Training C1/Transiti (3Nos Consultancies across onal Mon-09-Jul- 10 LGAs) Support 3 QCBS No 491,803.28 258,196.72 Post 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 32 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Specialized psycho-social support responding to C1/Commu needs (3Nos Consultancies nity Wed-28-Mar- across 10 LGAs) Resilience 3 QCBS No 826,229.51 619,672.13 Post 18 Consultancy for the Mobilisation and Organisation of Civic Education with Cultural and Recreational activities at Community Level with programs that respond to needs as prioritized by community based diagnosis (3Nos C1/Commu Consultancies across 10 nity Wed-11-Apr- LGAs) Resilience 3 QCBS No 442,622.95 265,573.77 Post 18 Consultancy for Sensitization, Community Mobilization and formation of peace groups within 7 Communities(establishmen t of community platforms to discuss community needs, grievances; and C1/Commu redress mechanisms. (1No nity Mon-30-Apr- Consultancy) Resilience 1 QCBS No 531,147.54 318,688.52 Prior 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 33 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Consultancy for Post- C1/Commu Conflict Transitional Justice nity Mon-21-May- and Accountability Resilience 1 QCBS No 147,540.98 88,524.59 Post 18 Statewide sponsorship for Radio Programming for Peacebuilding Campaign and Content for dissemination (focusing on deradicalisation, grievance C1/Commu redress and peacebuilding nity Mon-04-Jun- outreach themes) Resilience 1 CQS No 475,409.84 178,278.69 Prior 18 Consultancy for Educational campaigns for the prevention of mine and unexploded ordinance accidents /Mobilisation and Sensitization Campaign on Mine Action (Unexploded C1/Commu Ordnances) (1No nity Mon-04-Jun- Consultancy) Resilience 1 QCBS No 442,622.95 354,098.36 Prior 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 34 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Consultancy for Leadership Accountability and Transparency Training Programme (NELATTP) Targeting 20 LGA Staff and State Ministry Personal per LGA - Development of a transparency and accountability Local Governance Model through community participation C1/Commu (social accountability nity Fri-25-May- mechanisms) Resilience 1 CQS No 88,524.59 55,327.87 Post 18 Consultancy for Registration, Mapping and C1/Strengt Profiling of all local hening government structures and Local existing capacities State Governanc Fri-25-May- Wide e 1 CQS No 49,180.33 30,737.70 Post 18 Consultancy to provide C1/Strengt Capacity building of LG hening Officers for economic Local planning and policy Governanc Fri-25-May- development e CQS No 88,524.59 55,327.87 Post 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 35 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT C1/Strengt hening Capacity building for LG Local officials on programme Governanc Fri-25-May- design and implementation e CQS No 88,524.59 55,327.87 Post 18 Capacity building of LG C1/Strengt Officers for local hening governments on budget Local planning and execution, Governanc Fri-25-May- monitoring and reporting e 1 CQS No 88,524.59 55,327.87 Post 18 Capacity building of LG Officers for strategic communications C1/Strengt (Legislative Advocacy, hening Media relations, Local Stakeholder Management Governanc Fri-25-May- etc). e CQS No 88,524.59 55,327.87 Post 18 Capacity Building for 10 Local Government C1/Strengt Emergency Management hening Responders in Displaced Local and Transitional Local Governanc Fri-25-May- Government Officials e 1 CQS No 203,278.69 152,459.02 Post 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 36 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Sensitization, training (especially on Identification, Documentation, Tracing and Reunification and follow up) and coaching for state and non-state partners on case management of UASC C1/Program (Unaccompanied and Support to Fri-25-May- Separated Children) UASC 1 MOU No 73,770.49 59,016.39 Post 18 Training for officials of relevant State MDAs on C1/Program effective approaches to Support to Thu-28-Jun- UASC UASC 1 IC No 16,393.44 13,114.75 Post 18 Teacher Training and C1/Educati Fri-25-May- Recertification on 1 MOU No 442,622.95 77,459.02 Post 18 Training of Community Health Workers (CHeWs, VHWs, Midwives) to Staff Targeted Health Facilities (3Nos consultancies across the state. Amount Inclusive of Workshop and per diem Mon-29-Apr- payments) C1/Health 3 QCBS No 796,721.31 298,770.49 Post 19 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 37 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Sensitization and Mobilisation for Health (Outreach Programs) in 27 LGAs (Over 10 Fri-25-May- engagements) C1/Health 10 CQS No 708,196.72 265,573.77 Post 18 Identification and training of Village Levels Mechanics and Local Area Mechanics on Operation and Maintenance of existing Hand Pump and Solar powered Borehole for effective utilization and Fri-25-May- management. C2/WASH 1 CQS No 98,360.66 73,770.49 Post 18 ADAMAWA Refresher Training of Existing Extension Workers C1/Transiti to support Livelihoods onal Thu-10-May- Projects Support 1 CQS No 65,573.77 65,573.77 Post 18 Training of affected farmers to apply inputs and access targeted C1/Transiti agricultural value chains onal Thu-21-Jun- and agribusiness skills Support 1 CQS No 167,216.39 167,216.39 Post 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 38 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Establishment of Returnees Resettlement Registry at each LGA for Sensitization, Mobilisation and Logistics support for Safe and C1/Transiti Voluntary returns to 7 onal Thu-24-May- LGAs being rehabilitated Support 1 CQS No 61,565.57 49,252.46 Post 18 Consultancy to provide C1/Transiti Training for Bio Data onal Thu-10-May- Registration Support Support 1 IC No 1,377.05 1,101.64 Post 18 Consultancy for Sensitization, Community Mobilization and formation of peace groups within 7 Communities(establishmen t of community platforms to discuss community C1/Commu needs, grievances; and nity Mon-04-Jun- redress mechanisms Resilience 1 QCBS No 344,262.30 206,557.38 Prior 18 Diagnosis of community- specific reconciliation, peacebuilding and social C1/Commu cohesion needs and nity Thu-03-May- consequent development Resilience 2 QCBS No 344,262.30 206,557.38 Post 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 39 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT of Civil Education Programs using Cultural and Recreational activities at Community Level (2Nos Consultancies) Provision of specialized psycho-social assessment and support responding to needs through group support, recreational, customary and socializing activities, referrals etc C1/Commu (3Nos Consultancies across nity Mon-11-Jun- the affected areas) Resilience 3 QCBS No 642,622.95 481,967.21 Post 18 Sensitization and Mobilisation Programs for Awareness against Stigmatization of Woman and Children associated C1/Commu with armed groups. (1No nity Mon-04-Jun- Consultancy) Resilience 1 QCBS No 413,114.75 247,868.85 Prior 18 Consultancy for Mediation and Alternate Dispute Resolution Capacity C1/Commu Building within the nity Mon-18-Jun- Community Leadership and Resilience 3 QCBS No 425,960.66 255,576.39 Post 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 40 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Governance Structures (3Nos Consultancies acrossthe state) C1/Citizen- Consultancy for Leadership Governmen Accountability and t Transparency Training Relationshi Thu-10-May- Programme p Building 1 CQS No 72,131.15 45,081.97 Post 18 Registration, Mapping and C1/Strengt Profiling of all local hening government structures and Local existing capacities State Governanc Mon-28-May- Wide e 1 CQS No 39,344.26 24,590.16 Post 18 C1/Strengt Capacity building of LG hening Officers for economic Local planning and policy Governanc Mon-28-May- development e 1 CQS No 72,131.15 45,081.97 Post 18 C1/Strengt hening Capacity building for Local programme design and Governanc Mon-28-May- implementation e 1 CQS No 72,131.15 45,081.97 Post 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 41 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Capacity building of LG C1/Strengt Officers for local hening governments on budget Local planning and execution, Governanc Mon-28-May- monitoring and reporting e 1 CQS No 72,131.15 45,081.97 Post 18 Capacity building of LG Officers for strategic communications C1/Strengt (Legislative Advocacy, hening Media relations, Local Stakeholder Management Governanc Thu-21-Jun- etc). e 1 CQS No 72,131.15 45,081.97 Post 18 Hygiene Promotion Mon-17-Sep- Sensitization/Mobilization C2/WASH 1 IC No 9,180.33 6,885.25 Post 18 Hygiene Promotion Mon-12-Nov- Campaign C2/WASH 1 CQS No 85,677.59 64,258.20 Post 18 Training of Community Health Workers (CHeWs) to Staff Targeted Health Thu-13-Dec- Facilities C2/Health 1 CQS No 68,852.46 55,081.97 Post 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 42 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Sensitization and Mobilisation for Health Mon-17-Sep- (Outreach Programs) C2/Health 1 CQS No 183,606.56 146,885.25 Post 18 Mobilization and Sensitization for Children C2/Educati Thu-31-May- Education on 1 CQS No 206,557.38 206,557.38 Post 18 Teacher Training and Recertification ( Primary C2/Educati Thu-13-Dec- and Secondary Schools ) on 1 CQS No 360,655.74 360,656.74 Prior 18 YOBE Skills Acquisition Training C1/Transiti 3 Nos Consultancies across onal Wed-25-Apr- 8 LGAs) Support 3 QCBS No 524,590.16 367,213.11 Post 18 Consultancy for Sensitization, Community Mobilization and formation of peace groups within 15 C1/Peace Wed-23-May- Communities Building 1 QCBS No 491,803.28 319,672.13 Prior 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 43 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Diagnosis of community- specific reconciliation, peacebuilding and social cohesion needs and consequentt development of Civil Education Programs using Cultural and Recreational activities at C1/Peace Mon-04-Jun- Community Level Building 1 CQS No 49,180.33 31,967.21 Post 18 Consultancy for Mediation and Alternate Dispute Resolution Capacity Building within the Community Leadership and C1/Peace Mon-04-Jun- Governance Structures Building 1 CQS No 177,049.18 115,081.97 Post 18 Radio programs on mine awareness, dispute resolution in Hausa, Kanuri C1/Peace Wed-25-Jul- and Fulfulde Building 1 CQS No 280,719.92 105,269.97 Post 18 Provision of specialized psycho-social assessment and support responding to needs (3 Nos Consultancies C1/Peace Wed-20-Jun- across 8 LGAs) Building 3 QCBS No 625,822.95 438,076.07 Post 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 44 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Mapping and profiling of local government C1/Strengt structures and hening communities in places of Local both displacement and Governanc Thu-28-Jun- origin e 1 CQS No 39,344.26 39,344.26 Post 18 Establishment of C1/Strengt community platforms to hening discuss community needs, Local grievances; and building a Governanc Wed-06-Jun- bottom-up planning model e 1 CQS No 74,948.93 59,959.14 Post 18 Development of a transparency and accountability model C1/Strengt through community hening participation (social Local accountability Governanc Wed-06-Jun- mechanisms) e 1 CQS No 47,377.05 37,901.64 Post 18 C1/Strengt Capacity building of LG hening Officers for economic Local planning and policy Governanc Thu-28-Jun- development e 1 CQS No 55,737.70 44,590.16 Post 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 45 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT C1/Strengt hening Capacity building for Local programme design and Governanc Thu-28-Jun- implementation e 1 CQS No 55,737.70 44,590.16 Post 18 Capacity building of LG C1/Strengt Officers for local hening governments on budget Local planning and execution, Governanc Thu-28-Jun- monitoring and reporting e 1 CQS No 55,737.70 44,590.16 Post 18 Capacity building of LG Officers for strategic communications C1/Strengt (Legislative Advocacy, hening Media relations, Local Stakeholder Management Governanc etc). e 1 CQS No 55,737.70 44,590.16 Post Thu-26-Jul-18 Sensitization, training (especially on Identification, Documentation, Tracing and Reunification and follow up) and coaching for state and non-state C1/Program partners on case Support on Thu-07-Jun- management of UASC UASC 1 CQS No 52,459.02 41,967.21 Post 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 46 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Training for officials of C1/Program relevant MDAs on effective Support on Thu-28-Jun- approaches to UASC UASC 1 CQS No 8,196.72 6,557.38 Post 18 Menstrual Hygiene Management to support Women and Girls of productive ages to effectively maintain their Thu-17-May- menstrual hygiene C2/WASH 1 QCBS No 110,163.93 41,311.48 Post 18 Community Led Total Sanitation (CLTS) Implementation in Thu-31-May- communities C2/WASH 1 QCBS No 220,327.87 82,622.95 Post 18 Community Management training of entire Communities in the 8 proposed LGAs to effectively manage their Water, Sanitation and Mon-18-Jun- Hygiene Facilities C2/WASH 3 QCBS No 293,770.49 110,163.93 Post 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 47 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Identification and training of Village Levels Mechanics and Local Area Mechanics on Operation and Maintenance of existing Hand Pump and Solar powered Borehole for effective utilization and Thu-17-May- management. C2/WASH 1 CQS No 98,360.66 61,475.41 Post 18 Water Safety Plan implementation in the entire Communities of the Mon-16-Jul- four LGAs. C2/WASH 1 CQS No 112,459.02 84,344.26 Post 18 Integrated Outreach Services (Up to 5 activities Thu-17-May- envisaged) C2/Health 5 QCBS No 344,262.30 129,098.36 Post 18 Training of Community Health Workers (CHeWs, VHWs, Midwives) to Staff Thu-15-Nov- Targeted Health Facilities C2/Health 1 QCBS No 501,639.34 376,229.51 Prior 18 Teacher Training and C2/Educati Mon-26-Nov- Recertification in all LGAs on 1 MOU No 278,688.52 209,016.39 Post 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 48 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT PCNI NERSP PMC CELL Project Wide Project C3/Technic Management Consultancy al 2,000,000. Wed-11-Apr- Firm Assistance 1 QCBS No 3,000,000.00 00 Prior 18 Consultancy services for immediate- and medium- term implementation capacity building (4 C3/Technic separate Consultancies al Thu-03-May- Envisaged) Assistance 4 CQS No 536,393.44 268,196.72 Prior 18 Consultancy Services for C3/Technic Monitoring and Evaluation al Baseline Study Assistance 1 QCBS No 177,049.18 177,049.18 Post Fri-27-Apr-18 Consultancy services for setting up citizen engagement and third C3/Technic party monitoring al mechanisms Assistance 1 CQS No 177,049.00 59,016.33 Post Fri-06-Apr-18 Consultancy Services for C3/Technic Environmental Impact al Assessment Assistance 1 QCBS No 39,344.26 39,344.26 Post Fri-13-Apr-18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 49 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT NON- CONSULTING SERVICES ADAMAWA Door to Door Collection of Thu-24-May- Solid waste in 7 LGAs C2/WASH 1 NCB No 236,065.57 88,524.59 Post 18 Disposal of Waste from Door to Door Collection in Tue-13-Feb- 7 LGAs C2/WASH 1 NCB No 229,508.20 86,065.57 Post 18 OPERATIONAL COSTS PCNI NERSP PMC CELL PMC Software, Intranet and C3/Operati Tools onal Costs 3 RfQ No 159,240.16 159,240.16 Post Fri-27-Apr-18 Video Conferencing C3/Operati Thu-25-Jan- Equipment onal Costs 1 RfQ No 131,147.54 131,147.54 Post 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 50 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT C3/Operati Tue-27-Mar- Office Vehicles onal Costs 1 RfQ No 344,265.00 344,265.00 Post 18 BORNO STATE Procurement of 12 laptop computers, 12 laserjet printers, 4 photocopiers, 3 desktops, 15 desktops for work stations, 2 deskjet printers, HP Scanjet C3/Operati scanner onal Costs 1 RfQ No 159,240.16 159,240.16 Post Fri-27-Apr-18 Procurement of video conference equipment and C3/Operati internet connectivity onal Costs 1 RfQ No 65,574.00 65,574.00 Post Fri-27-Apr-18 Procurement of Office C3/Operati Tue-27-Mar- Furniture onal Costs 1 NCB No 32,786.89 32,786.89 Post 18 Procurement of 1 Video C3/Operati Wed-28-Mar- Camera, 2 DLSR Cameras, onal Costs 1 RfQ No 7,000.00 7,000.00 Post 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 51 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Procurement of 100KVA sound proof Generator, C3/Operati Sun-20-May- 10KVA Inverter System onal Costs 1 RfQ No 42,623.00 42,623.00 Post 18 Procurement of Office Vehicles - 2 Toyota Prado Jeep, 3 Toyota Hilux, 1 C3/Operati Wed-14-Mar- Toyota Corolla onal Costs 1 NCB No 448,525.00 448,525.00 Post 18 ADAMAWA STATE Procurement of computers, printers and other C3/Operati Wed-28-Mar- accessories onal Costs 1 RfQ No 24,131.15 24,131.15 Post 18 Procurement of video conference equipment and C3/Operati Wed-28-Mar- internet connectivity onal Costs 1 RfQ No 65,574.00 65,574.00 Post 18 Procurement of Office C3/Operati Tue-27-Mar- Furniture onal Costs 1 NCB No 32,786.89 32,786.89 Post 18 Procurement of 1 Video C3/Operati Wed-28-Mar- Camera, 2 DLSR Cameras, onal Costs 1 RfQ No 20,327.87 20,327.87 Post 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 52 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Procurement of 100KVA sound proof Generator, C3/Operati Mon-26-Mar- 10KVA Inverter System onal Costs 1 RfQ No 42,623.00 42,623.00 Post 18 Procurement of Office Vehicles - 2 Toyota Prado Jeep, 3 Toyota Hilux, 1 C3/Operati Tue-27-Mar- Toyota Corolla onal Costs 1 RfQ No 518,033.00 518,033.00 Post 18 YOBE STATE Procurement of computers, printers and other C3/Operati Wed-28-Mar- accessories onal Costs 1 RfQ No 24,131.15 24,131.15 Post 18 Procurement of video conference equipment and C3/Operati Wed-28-Mar- internet connectivity onal Costs 1 RfQ No 65,574.00 65,574.00 Post 18 Procurement of Office C3/Operati Tue-27-Mar- Furniture onal Costs 1 NCB No 32,786.89 32,786.89 Post 18 Procurement of 1 Video C3/Operati Wed-28-Mar- Camera, 2 DLSR Cameras, onal Costs 1 RfQ No 20,327.87 20,327.87 Post 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 53 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Procurement of 100KVA sound proof Generator, C3/Operati Mon-26-Mar- 10KVA Inverter System onal Costs 1 RfQ No 42,623.00 42,623.00 Post 18 Procurement of Office C3/Operati Tue-27-Mar- Vehicles onal Costs 1 RfQ No 468,852.46 468,852.46 Post 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 54 PROCUREMENT Nigeria : Multi-Sectoral Crisis Recovery Project for North Eastern Nigeria PLAN General Information Country: Nigeria 2018-06-06 Bank’s Approval Date of the Original Procurement Plan: 2023-06-02 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P157891 GPN Date: Project Name: Multi-Sectoral Crisis Recovery Project for North Eastern Nigeria Loan / Credit No: IDA / 59880, IDA / 66490 Adamawa MCRP Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned NG-ADAMAWA MCRP-60544- Infrastructure Rehabilitation Single Stage - One E 2019-01-2 CW-RFB / Rehabilitation of G IDA / 59880 and Service Delivery Restora Post Request for Bids Open - National 179,190.16 0.00 Canceled 2018-04-06 2018-04-11 2018-05-23 2018-06-22 2018-07-27 nvelope 3 ulak Water Supply System tion & Improvement NG-ADAMAWA MCRP-60190- Infrastructure Rehabilitation Single Stage - One E 2019-01-2 CW-RFB / Rehabilitation of H IDA / 59880 and Service Delivery Restora Post Request for Bids Open - National 116,646.90 0.00 Canceled 2018-04-06 2018-04-11 2018-05-23 2018-06-22 2018-07-27 nvelope 3 ong Water Supply System tion & Improvement NG-ADAMAWA MCRP-60574- Infrastructure Rehabilitation Single Stage - One E 2019-01-2 CW-RFB / Rehabilitation of Mi IDA / 59880 and Service Delivery Restora Post Request for Bids Open - National 138,193.44 0.00 Canceled 2018-04-06 2018-04-11 2018-05-23 2018-06-22 2018-07-27 nvelope 3 chika Water supply system tion & Improvement NG-ADAMAWA MCRP-60628- Infrastructure Rehabilitation Single Stage - One E 2019-01-2 CW-RFB / Rehabilitation of U IDA / 59880 and Service Delivery Restora Post Request for Bids Open - National 71,967.21 0.00 Canceled 2018-04-06 2018-04-11 2018-05-23 2018-06-22 2018-07-27 nvelope 3 ba Water Supply system tion & Improvement NG-ADAMAWA MCRP-60942- Infrastructure Rehabilitation Single Stage - One E 2019-01-2 CW-RFB / Rehabilitation of e IDA / 59880 and Service Delivery Restora Post Request for Bids Open - National 30,475.41 0.00 Canceled 2018-04-06 2018-04-11 2018-05-23 2018-06-22 2018-07-27 nvelope 3 xisitng Water Supply sources tion & Improvement in Gombi NG-ADAMAWA MCRP-60952- Infrastructure Rehabilitation Request for Quota Single Stage - One E 2019-03-0 CW-RFQ / Construction of VIP IDA / 59880 and Service Delivery Restora Post Open - National 212,459.02 0.00 Canceled 2018-07-11 2018-09-05 tions nvelope 4 Latrines of 3-Comp (2 Blks in tion & Improvement 24 pri sch) NG-ADAMAWA MCRP-60083- Infrastructure Rehabilitation Request for Quota Single Stage - One E 2019-03-0 CW-RFQ / VIP Latrine of 3-Co IDA / 59880 and Service Delivery Restora Post Open - National 230,163.93 0.00 Canceled 2018-07-11 2018-09-05 tions nvelope 4 mp (2 Blks in 26 Markets) tion & Improvement NG-ADAMAWA MCRP-60505- Infrastructure Rehabilitation Request for Quota Single Stage - One E 2019-03-0 CW-RFQ / VIP Latrine of 3-Co IDA / 59880 and Service Delivery Restora Post Open - National 230,163.93 0.00 Canceled 2018-07-11 2018-09-05 tions nvelope 4 mp (2 Blks in 26 Motor Parks) tion & Improvement NG-ADAMAWA MCRP-60940- Infrastructure Rehabilitation CW-RFB / Rehabilitation of M Single Stage - One E 2019-02-2 IDA / 59880 and Service Delivery Restora Prior Request for Bids Open - National 8,369,796.72 0.00 Canceled 2018-05-04 2018-05-09 2018-06-20 2018-07-20 2018-08-24 ubi Bazza Road with a spur t nvelope 0 tion & Improvement o Mayo Bani 45Km NG-ADAMAWA MCRP-60315- Infrastructure Rehabilitation Single Stage - One E 2019-02-1 CW-RFB / Rehabilitation of Lo IDA / 59880 and Service Delivery Restora Post Request for Bids Open - National 315,082.89 0.00 Canceled 2018-04-30 2018-05-05 2018-06-16 2018-07-16 2018-08-20 nvelope 6 cal Government Secretariat - tion & Improvement Madagali NG-ADAMAWA MCRP-69807- Infrastructure Rehabilitation Request for Quota Single Stage - One E Under Imple 2019-03-2 CW-RFQ / Upgrade and Expa IDA / 59880 and Service Delivery Restora Post Limited 721,222.95 0.00 2018-08-05 2019-06-27 2018-09-30 tions nvelope mentation 9 nsion of Uba Water Supply Pr tion & Improvement oject NG-ADAMAWA MCRP-69803- Infrastructure Rehabilitation Request for Quota Single Stage - One E 2019-03-2 CW-RFQ / Upgrade and Expa IDA / 59880 and Service Delivery Restora Post Limited 555,289.34 476,751.54 Signed 2018-08-01 2019-06-27 2018-09-26 2019-09-06 tions nvelope 5 nsion of Pella Water Supply P tion & Improvement roject NG-ADAMAWA MCRP-69714- Infrastructure Rehabilitation Request for Quota Single Stage - One E 1,063,388.5 2019-02-2 CW-RFQ / Upgrade and Expa IDA / 59880 and Service Delivery Restora Post Open - National 1,256,442.62 Completed 2018-07-25 2018-08-29 2019-09-06 tions nvelope 0 5 nsion of Hong Water supply tion & Improvement project NG-ADAMAWA MCRP-69805- Infrastructure Rehabilitation Request for Quota Single Stage - One E Under Imple 2019-03-2 CW-RFQ / Upgrade and Expa IDA / 59880 and Service Delivery Restora Post Limited 915,241.80 0.00 2018-08-01 2019-06-27 2018-09-26 tions nvelope mentation 5 nsion of Gombi Water Supply tion & Improvement Project NG-ADAMAWA MCRP-60578- Infrastructure Rehabilitation Single Stage - One E 2019-02-2 CW-RFB / Rehabilitation of Lo IDA / 59880 and Service Delivery Restora Post Request for Bids Open - National 475,143.96 525,084.68 Signed 2018-05-04 2020-02-05 2018-05-09 2020-02-18 2018-06-20 2020-03-17 2018-07-20 2020-08-06 2018-08-24 2020-09-01 nvelope 0 kwa Bridge Mubi tion & Improvement NG-ADAMAWA MCRP-69818- CW-RFQ / Rehabilitation of P Infrastructure Rehabilitation Request for Quota Single Stage - One E 2019-03-1 HC, Construction of Perimete IDA / 59880 and Service Delivery Restora Post Limited 935,802.00 806,687.09 Completed 2018-08-21 2019-11-08 2018-10-05 2020-07-11 tions nvelope 4 r Fence and Staff Quarters (C tion & Improvement ivil Works, Fence & Security Post) in 7 Communities NG-ADAMAWA MCRP-69810- CW-RFQ / Rehabilitation of Di Infrastructure Rehabilitation Request for Quota Single Stage - One E 2018-12-2 strict Head's Palace and Offic IDA / 59880 and Service Delivery Restora Post Limited 422,463.57 319,349.34 Signed 2018-08-05 2020-06-30 2018-09-30 2020-09-09 tions nvelope 9 es in 5 Communities (Uba, G tion & Improvement ella, Gombi, Maiha/Pakka, Gu lak) NG-ADAMAWA MCRP-69962- CW-RFQ / Remodeling and up Technical Assistance and Pro Request for Quota Single Stage - One E Under Imple 2018-08-0 IDA / 59880 Post Limited 32,840.72 0.00 2018-07-19 2018-07-26 grade of rented office facility ject Management Support tions nvelope mentation 9 to meet the requirements of the PCU. NG-ADAMAWA MCRP-74570- Infrastructure Rehabilitation Request for Quota Single Stage - One E 2019-01-2 CW-RFQ / Rehabilitation of Lo IDA / 59880 and Service Delivery Restora Post Open - National 288,590.56 268,328.76 Completed 2018-08-20 2018-10-18 2020-01-24 tions nvelope 6 cal Government Secretariat - tion & Improvement Song NG-ADAMAWA MCRP-59963- CW-RFB / Installation of 13 n os. Solar Boreholes (in secon Infrastructure Rehabilitation dary schools)- GSS Gombi, G Request for Quota Single Stage - One E 2019-01-0 IDA / 59880 and Service Delivery Restora Post Open - National 544,864.17 0.00 Canceled 2018-08-22 2018-09-30 DSS Garkida, GSS Hong, GDS tions nvelope 8 tion & Improvement S Pella, GSSS Uba, GJSS Uba, GDSS Garaha, GDSS Kwarhi, GDSS Za'ah, GSS Madagli, G SS Shuwa, GSS Gulak, GCSS Shuwa Page 1 NG-ADAMAWA MCRP-60629- Infrastructure Rehabilitation Single Stage - One E 2019-02-2 CW-RFB / Reconstruction of IDA / 59880 and Service Delivery Restora Prior Request for Bids Open - National 1,019,295.08 0.00 Canceled 2018-05-04 2018-05-09 2018-06-20 2018-07-20 2018-08-24 nvelope 0 Main Road - Bangshika Road tion & Improvement 2.5Km NG-ADAMAWA MCRP-72562- Infrastructure Rehabilitation Single Stage - One E 2019-01-3 CW-RFB / Rehabilitation of Mi IDA / 59880 and Service Delivery Restora Prior Request for Bids Open - National 545,138.07 0.00 Canceled 2018-08-02 2018-08-07 2018-08-21 2018-09-11 2018-10-02 nvelope 0 chika Hospital Road tion & Improvement NG-ADAMAWA MCRP-72563- Infrastructure Rehabilitation Single Stage - One E 2019-01-2 CW-RFB / Rehabilitation of ac IDA / 59880 and Service Delivery Restora Prior Request for Bids Open - National 1,235,124.92 0.00 Canceled 2018-08-02 2018-08-07 2018-08-21 2018-09-05 2018-09-23 nvelope 1 cess road to Garkida tion & Improvement NG-ADAMAWA MCRP-74493- Infrastructure Rehabilitation Request for Quota Single Stage - One E Under Imple 2019-02-0 CW-RFQ / Rehabilitation of G IDA / 59880 and Service Delivery Restora Post Open - National 698,530.00 0.00 2018-08-20 2018-10-11 tions nvelope mentation 8 arkida Water Supply System tion & Improvement NG-ADAMAWA MCRP-74494- Infrastructure Rehabilitation Request for Quota Single Stage - One E 2019-02-0 CW-RFQ / Rehabilitation of M IDA / 59880 and Service Delivery Restora Post Open - National 458,241.00 392,382.20 Signed 2018-08-20 2018-10-11 2019-09-05 tions nvelope 8 aiha Water Supply System tion & Improvement NG-ADAMAWA MCRP-74626- Infrastructure Rehabilitation Request for Quota Single Stage - One E 2019-02-0 CW-RFQ / Rehabilitation of G IDA / 59880 and Service Delivery Restora Post Open - National 491,803.00 427,332.84 Completed 2018-08-20 2018-10-11 2020-09-05 tions nvelope 8 eneral Hospital Michika tion & Improvement NG-ADAMAWA MCRP-69765- CW-RFQ / Renovation of GSS Infrastructure Rehabilitation Request for Quota Single Stage - One E Under Imple 2019-02-1 in 10 Towns (Gombi, Hong, U IDA / 59880 and Service Delivery Restora Post Limited 1,650,980.47 0.00 2018-12-08 2018-12-14 tions nvelope mentation 2 ba, Shuwa, Michika, Bazza, M tion & Improvement ubi 1, Maiha, Madagali, Mubi North) NG-ADAMAWA MCRP-69808- Infrastructure Rehabilitation Request for Quota Single Stage - One E 2019-03-2 CW-RFQ / Upgrade and Expa IDA / 59880 and Service Delivery Restora Post Limited 1,189,261.84 991,392.87 Signed 2018-11-20 2019-06-27 2018-12-25 2019-09-05 tions nvelope 5 nsion of Michika Water suppl tion & Improvement y project NG-ADAMAWA MCRP-89273- CW-RFQ / Construction of 5 S Infrastructure Rehabilitation olar Boreholes in 5 Sec. Schs. Request for Quota Single Stage - One E Under Imple 2019-02-2 IDA / 59880 and Service Delivery Restora Post Open - National 1,062,512.28 0.00 2018-12-12 2018-12-23 , 11 in PHCs and 92 HPBH in tions nvelope mentation 1 tion & Improvement communities in Michika and Madagali LGAs of Adamawa State NG-ADAMAWA MCRP-89262- CW-RFQ / Construction of 10 Infrastructure Rehabilitation Solar Powered Boreholes in P Request for Quota Single Stage - One E Under Imple 2019-02-2 IDA / 59880 and Service Delivery Restora Post Open - National 759,971.70 0.00 2018-12-12 2018-12-23 HCs, and 80 HPBH in Commu tions nvelope mentation 1 tion & Improvement nities in Mubi North and Mubi South LGAs of Adamawa Stat e NG-ADAMAWA MCRP-89688- CW-RFQ / Construction of 8 S Infrastructure Rehabilitation Request for Quota Single Stage - One E Under Imple 2019-02-2 olar boreholes in 8 Sec. Schs, IDA / 59880 and Service Delivery Restora Post Open - National 1,529,944.23 0.00 2018-12-12 2018-12-23 tions nvelope mentation 1 16 in PHCs and 123 HPBH in tion & Improvement communities in Gombi, Hong and Maiha LGAs NG-ADAMAWA MCRP-10140 Infrastructure Rehabilitation Request for Quota Single Stage - One E 2018-12-0 9-CW-RFQ / Rehabilitation of IDA / 59880 and Service Delivery Restora Post Limited 30,475.00 25,604.58 Signed 2018-04-11 2019-06-27 2018-06-06 2019-09-05 tions nvelope 3 exisitng Water Supply source tion & Improvement s in Gombi NG-ADAMAWA MCRP-10138 Infrastructure Rehabilitation Request for Quota Single Stage - One E Under Imple 2018-12-0 3-CW-RFQ / Rehabilitation of IDA / 59880 and Service Delivery Restora Post Limited 71,967.00 0.00 2018-04-11 2019-06-27 2018-06-06 tions nvelope mentation 3 Uba Water Supply system tion & Improvement NG-ADAMAWA MCRP-10141 Infrastructure Rehabilitation Request for Quota Single Stage - One E 2018-12-0 3-CW-RFQ / Rehabilitation of IDA / 59880 and Service Delivery Restora Post Limited 138,193.00 114,778.49 Signed 2018-04-11 2019-06-27 2018-06-06 2019-09-05 tions nvelope 3 Michika Water supply system tion & Improvement NG-ADAMAWA MCRP-10141 Infrastructure Rehabilitation Request for Quota Single Stage - One E 2018-12-0 2-CW-RFQ / Rehabilitation of IDA / 59880 and Service Delivery Restora Post Limited 179,190.00 152,854.94 Signed 2018-04-11 2019-06-27 2018-06-06 2019-09-05 tions nvelope 3 Gulak Water Supply System tion & Improvement NG-ADAMAWA MCRP-10141 Infrastructure Rehabilitation Request for Quota Single Stage - One E 2018-12-0 0-CW-RFQ / Rehabilitation of IDA / 59880 and Service Delivery Restora Post Limited 116,646.00 94,375.21 Completed 2018-04-11 2019-06-27 2018-06-06 2019-09-05 tions nvelope 3 Hong Water Supply System tion & Improvement NG-ADAMAWA MCRP-10139 4-CW-RFQ / Construction VIP Infrastructure Rehabilitation Latrine of 3-Compartment (2 Request for Quota Single Stage - One E 2019-03-0 IDA / 59880 and Service Delivery Restora Post Limited 247,705.00 199,279.37 Completed 2018-07-11 2019-02-25 2018-09-05 2019-03-25 Blocks in 7 Primary Schools, tions nvelope 4 tion & Improvement 7 Motor Parks and 8 Markets in Mubi-North & Mubi-South L GAs) NG-ADAMAWA MCRP-10144 3-CW-RFQ / Construction VIP Infrastructure Rehabilitation Latrine of 3-Compartment (2 Request for Quota Single Stage - One E 2019-03-0 IDA / 59880 and Service Delivery Restora Post Limited 377,455.00 326,673.74 Completed 2018-07-11 2019-02-25 2018-09-05 2019-04-16 Blocks in 10 Primary schools, tions nvelope 4 tion & Improvement 12 motor parks and 9 market s in Gombi, Hong & Maiha LG As ) NG-ADAMAWA MCRP-10138 6-CW-RFQ / Construction of V Infrastructure Rehabilitation IP Latrines of 3-Compartment Request for Quota Single Stage - One E 2019-03-0 IDA / 59880 and Service Delivery Restora Post Limited 283,092.00 228,848.59 Completed 2018-07-12 2019-02-25 2018-09-06 2019-03-28 (2 Blocks in 8 Primary School tions nvelope 5 tion & Improvement s, 8 Motor Parks and 8 Marke ts in Michika & Madagali LGA s) NG-ADAMAWA MCRP-14590 7-CW-RFB / Rehabilitation of Infrastructure Rehabilitation Single Stage - One E 10,150,239.7 12,066,531. 2021-07-3 Three (3) Roads in Three (3) IDA / 59880 and Service Delivery Restora Prior Request for Bids Open - National Signed 2019-11-18 2020-02-05 2019-11-23 2020-02-18 2019-12-18 2020-03-17 2020-01-09 2020-08-07 2020-01-30 2020-09-02 nvelope 1 53 0 Local Government Areas of A tion & Improvement damawa State, Mubi, Michika and Gombi. NG-ADAMAWA MCRP-17761 Infrastructure Rehabilitation Request for Quota Single Stage - One E 2021-04-0 0-CW-RFQ / Rehabilitation of IDA / 59880 and Service Delivery Restora Post Limited 800,000.00 416,527.96 Signed 2020-08-23 2021-10-05 2020-10-11 2021-12-21 tions nvelope 9 Male and Female Hostels in tion & Improvement GSS Michika NG-ADAMAWA MCRP-17756 Infrastructure Rehabilitation 4-CW-RFQ / Rehabilitation of Request for Quota Single Stage - One E 2021-04-0 IDA / 59880 and Service Delivery Restora Post Limited 200,000.00 183,055.72 Signed 2020-08-24 2021-10-12 2020-10-08 2021-12-11 Classrooms and Teachers Off tions nvelope 6 tion & Improvement ices at GTC Shuwa Page 2 NG-ADAMAWA MCRP-17756 Infrastructure Rehabilitation Request for Quota Single Stage - One E 2021-03-2 5-CW-RFQ / Construction of 5 IDA / 59880 and Service Delivery Restora Post Limited 217,100.00 175,928.00 Signed 2020-08-09 2021-02-02 2020-09-27 2021-04-01 tions nvelope 6 0 Hand Pump Boreholes in Se tion & Improvement ven LGAs NG-ADAMAWA MCRP-17758 Infrastructure Rehabilitation Request for Quota Single Stage - One E Pending Imp 2021-04-0 2-CW-RFQ / Construction of 3 IDA / 59880 and Service Delivery Restora Post Limited 360,000.00 0.00 2020-08-15 2020-10-03 tions nvelope lementation 1 0 nos VIP Latrines in Seven L tion & Improvement GAs NG-ADAMAWA MCRP-15867 Infrastructure Rehabilitation Request for Quota Single Stage - One E 2021-03-2 5-CW-RFQ / Upgrade and Exp IDA / 59880 and Service Delivery Restora Post Limited 350,000.00 272,410.73 Signed 2020-08-05 2020-07-31 2020-09-23 2020-08-29 tions nvelope 2 ansion of Gulak water supply tion & Improvement scheme NG-ADAMAWA MCRP-16938 Infrastructure Rehabilitation Request for Quota Single Stage - One E 2021-03-2 2-CW-RFQ / Rehabilitation of IDA / 59880 and Service Delivery Restora Post Limited 296,194.00 273,739.87 Signed 2020-07-20 2021-10-12 2020-09-21 2021-12-08 tions nvelope 0 Dermatology Centre, Virgwi tion & Improvement NG-ADAMAWA MCRP-17760 Infrastructure Rehabilitation Request for Quota Single Stage - One E Pending Imp 2021-04-2 8-CW-RFQ / Renovation of 8 IDA / 59880 and Service Delivery Restora Post Limited 1,300,000.00 0.00 2020-09-05 2020-10-24 tions nvelope lementation 2 Secondary Schools in 7 LGAS tion & Improvement NG-ADAMAWA MCRP-17756 Infrastructure Rehabilitation Request for Quota Single Stage - One E Under Imple 2021-03-2 1-CW-RFQ / Rehabilitation of IDA / 59880 and Service Delivery Restora Post Limited 700,000.00 0.00 2020-08-08 2020-09-26 tions nvelope mentation 5 7 nos Primary Schools tion & Improvement NG-ADAMAWA MCRP-17755 Infrastructure Rehabilitation Request for Quota Single Stage - One E Under Imple 2021-04-1 7-CW-RFQ / Rehabilitation of IDA / 59880 and Service Delivery Restora Post Limited 1,000,000.00 0.00 2020-08-31 2020-10-19 tions nvelope mentation 7 7 nos. Primary Health Care C tion & Improvement enter (PHCC) NG-ADAMAWA MCRP-69811- Infrastructure Rehabilitation Request for Quota Single Stage - One E Under Imple 2021-02-1 CW-RFQ / Renovation of 17 IDA / 59880 and Service Delivery Restora Post Limited 1,106,804.87 0.00 2020-07-12 2020-08-14 tions nvelope mentation 0 Nos Primary School over 7 LG tion & Improvement As NG-ADAMAWA MCRP-60939- Infrastructure Rehabilitation Request for Quota Single Stage - One E 2021-02-1 CW-RFQ / Construction of Ne IDA / 59880 and Service Delivery Restora Post Open - National 265,366.00 226,300.17 Signed 2020-07-07 2020-08-18 2020-09-02 tions nvelope 4 w Trauma Center @ General tion & Improvement Hospital mubi NG-ADAMAWA MCRP-15667 Infrastructure Rehabilitation 0-CW-RFQ / Rehabilitation of Request for Quota Single Stage - One E Under Imple 2021-01-2 IDA / 59880 and Service Delivery Restora Post Limited 1,066,944.00 0.00 2020-07-27 2020-09-01 Primary Schools in Michika a tions nvelope mentation 9 tion & Improvement nd Madagali LGAs of Adama wa State NG-ADAMAWA MCRP-15667 Infrastructure Rehabilitation 2-CW-RFQ / Renovation of Go Request for Quota Single Stage - One E Pending Imp 2021-03-0 IDA / 59880 and Service Delivery Restora Post Limited 1,326,768.00 0.00 2020-08-02 2020-09-07 vernment Secondary Schools tions nvelope lementation 6 tion & Improvement in Michika and Madagali LGA s of Adamawa State NG-ADAMAWA MCRP-10143 Infrastructure Rehabilitation Request for Quota Single Stage - One E 2018-12-2 2-CW-RFQ / Rehabilitation of IDA / 59880 and Service Delivery Restora Post Limited 315,082.00 0.00 Canceled 2018-05-05 2018-06-30 tions nvelope 7 Local Government Secretaria tion & Improvement t - Madagali NG-ADAMAWA MCRP-17755 Infrastructure Rehabilitation 2021-06-0 6-CW-DIR / Rehabilitation of IDA / 59880 and Service Delivery Restora Post Direct Selection Direct 1,000,000.00 0.00 Canceled 2020-10-29 2020-11-03 2020-12-08 6 Michika General Hospital Roa tion & Improvement d (additional 2KM) NG-ADAMAWA MCRP-69800- Infrastructure Rehabilitation Request for Quota Single Stage - One E 2019-03-1 CW-RFQ / Rehabilitation of C IDA / 59880 and Service Delivery Restora Post Limited 451,768.85 0.00 Canceled 2018-07-22 2018-09-16 tions nvelope 5 ottage Hospital in Madagali tion & Improvement NG-ADAMAWA MCRP-27780 Infrastructure Rehabilitation Request for Quota 7-CW-RFQ / Rehabilitation of Request for Quota Single Stage - One E Pending Imp 2023-01-2 IDA / 66490 and Service Delivery Restora Post Limited tions (Non Bank-S 500,000.00 0.00 2022-07-05 2022-07-31 General Hospital Garkida, Go tions nvelope lementation 7 tion & Improvement PD) mbi LGA in Adamawa State NG-ADAMAWA MCRP-27803 Infrastructure Rehabilitation Request for Quota 8-CW-RFQ / Rehabilitation of Request for Quota Single Stage - One E Pending Imp 2023-01-2 IDA / 66490 and Service Delivery Restora Post Limited tions (Non Bank-S 228,400.00 0.00 2022-07-05 2022-07-31 Cottage Hospital Maiha, Maih tions nvelope lementation 7 tion & Improvement PD) a LGA in Adamawa State NG-ADAMAWA MCRP-27804 2-CW-RFQ / Provision of Hand Infrastructure Rehabilitation Request for Quota Request for Quota Single Stage - One E Pending Imp 2022-12-0 Pump Boreholes (HPBHs) in V IDA / 66490 and Service Delivery Restora Post Limited tions (Non Bank-S 285,000.00 0.00 2022-04-27 2022-06-10 tions nvelope lementation 7 entiilated Improved Pit (VIP) tion & Improvement PD) Toilets locations in Adamawa State. NG-ADAMAWA MCRP-27773 Infrastructure Rehabilitation Request for Quota 8-CW-RFQ / Rehabilitation of Request for Quota Single Stage - One E Pending Imp 2022-12-1 IDA / 66490 and Service Delivery Restora Post Limited tions (Non Bank-S 125,000.00 0.00 2022-05-17 2022-06-16 Area Social Welfare/ Youth D tions nvelope lementation 3 tion & Improvement PD) evelopment Offices in Adama wa State. NG-ADAMAWA MCRP-27778 Request for Bids - Infrastructure Rehabilitation 7-CW-RFQ / Rehabilitation an Single Stage - One E Small Works SPD 2023-05-0 IDA / 66490 and Service Delivery Restora Post Request for Bids Limited 770,000.00 0.00 Canceled 2022-09-22 2022-09-27 2022-10-18 2022-11-01 2022-11-09 d maintenance of 13 KM Mich nvelope (1 envelope proce 8 tion & Improvement ika ss) - Vi- Rhuro Road with Culvert s NG-ADAMAWA MCRP-17627 Infrastructure Rehabilitation Request for Quota 7-CW-RFQ / Construction of 2 Request for Quota Single Stage - One E 2021-03-2 IDA / 59880 and Service Delivery Restora Post Limited tions (Non Bank-S 852,900.00 743,624.21 Completed 2020-08-08 2021-01-04 2020-09-22 2021-03-04 1 Solar Powered Boreholes in tions nvelope 1 tion & Improvement PD) Michika and Madagali LGAs o f Adamawa State. NG-ADAMAWA MCRP-15626 Infrastructure Rehabilitation Request for Quota 2-CW-RFQ / Construction of S Request for Quota Single Stage - One E 2021-05-0 IDA / 59880 and Service Delivery Restora Post Limited tions (Non Bank-S 560,000.00 544,079.48 Signed 2020-09-09 2021-02-02 2020-11-04 2022-03-19 olar Powered Boreholes in th tions nvelope 3 tion & Improvement PD) e Insurgency affected LGAs o f Adamawa State. NG-ADAMAWA MCRP-26445 Infrastructure Rehabilitation Request for Quota 0-CW-RFQ / Rehabilitation of Request for Quota Single Stage - One E Under Imple 2022-07-1 IDA / 59880 and Service Delivery Restora Post Limited tions (Non Bank-S 451,768.85 0.00 2021-11-27 2022-01-11 Government Secondary Scho tions nvelope mentation 0 tion & Improvement PD) ol (GSS) Madagali NG-ADAMAWA MCRP-28273 Request for Quota 6-CW-NULL / Rehabilitate/Up Infrastructure Rehabilitation Request for Quota Single Stage - One E tions - Small Work 2023-03-0 grade 1 no. International Catt IDA / 66490 and Service Delivery Restora Post Limited 350,000.00 0.00 Canceled 2022-08-07 2022-09-04 tions nvelope s (Emergency) SP 3 le Market including veterinar tion & Improvement D -Competitive y clinics in Adamawa State. NG-ADAMAWA MCRP-27780 Request for Bids - 1-CW-RFQ / Rehabilitation an Infrastructure Rehabilitation Single Stage - One E Small Works SPD 2023-05-0 d maintenance of Michika - Vi IDA / 66490 and Service Delivery Restora Post Request for Bids Limited 710,000.00 0.00 Canceled 2022-09-22 2022-09-27 2022-10-18 2022-11-01 2022-11-09 nvelope (1 envelope proce 8 llekwa - Road tion & Improvement ss) Dzurok farming Community ( 15Km) Page 3 NG-ADAMAWA MCRP-27812 Request for Bids - 7-CW-RFQ / Rehabilitation an Infrastructure Rehabilitation Single Stage - One E Small Works SPD 2023-05-0 d maintenance of 13km Gella IDA / 66490 and Service Delivery Restora Post Request for Bids Limited 750,000.00 0.00 Canceled 2022-09-22 2022-09-27 2022-10-18 2022-11-01 2022-11-08 nvelope (1 envelope proce 7 - tion & Improvement ss) Kwaja - Dumo road with drai nage facilities Request for Bids - NG-ADAMAWA MCRP-27781 Infrastructure Rehabilitation Single Stage - One E Small Works SPD 2023-05-0 0-CW-RFQ / Rehabilitation an IDA / 66490 and Service Delivery Restora Post Request for Bids Limited 700,000.00 0.00 Canceled 2022-09-22 2022-09-27 2022-10-18 2022-11-01 2022-11-08 nvelope (1 envelope proce 7 d maintenance of 13 Km Mub tion & Improvement ss) i-Bahuli Road NG-ADAMAWA MCRP-17761 Infrastructure Rehabilitation Request for Quota Single Stage - One E 2021-05-0 6-CW-RFQ / Rehabilitation of IDA / 59880 and Service Delivery Restora Post Limited 1,000,000.00 0.00 Canceled 2020-09-07 2020-11-02 tions nvelope 1 road network in Madagali To tion & Improvement wnship NG-ADAMAWA MCRP-29712 Infrastructure Rehabilitation Request for Quota 2023-01-1 4-CW-DIR / Rehabilitation of r IDA / 59880 and Service Delivery Restora Post Direct Selection Direct tions (Non Bank-S 1,400,000.00 0.00 Signed 2022-06-22 2022-08-09 2022-06-27 2022-08-10 2022-07-18 4 oad network in Madagali Tow tion & Improvement PD) nship NG-ADAMAWA MCRP-29707 Infrastructure Rehabilitation Request for Quota 9-CW-RFQ / Provision of Solar Request for Quota Single Stage - One E Pending Imp 2023-04-1 IDA / 66490 and Service Delivery Restora Post Limited tions (Non Bank-S 1,435,506.00 0.00 2022-09-18 2022-10-19 Powered Bore Holes (SPBH) i tions nvelope lementation 7 tion & Improvement PD) n Sanitation Centers and sele cted communities NG-ADAMAWA MCRP-29710 Infrastructure Rehabilitation Request for Quota 6-CW-RFQ / Provision of Solar Request for Quota Single Stage - One E Under Imple 2023-04-1 IDA / 66490 and Service Delivery Restora Post Limited tions (Non Bank-S 1,435,506.00 0.00 2022-09-18 2022-08-24 2022-10-19 Powered Bore holes (SPBHs) i tions nvelope mentation 7 tion & Improvement PD) n Primary Health Care Center s (PHCCs) NG-ADAMAWA MCRP-17628 Infrastructure Rehabilitation Request for Quota Single Stage - One E 2021-01-0 1-CW-RFQ / Refencing of Peri IDA / 59880 and Service Delivery Restora Post Limited 400,000.00 0.00 Canceled 2020-08-23 2020-09-30 tions nvelope 9 meter Fence at GSS Gombi ( tion & Improvement Entire School) NG-ADAMAWA MCRP-33310 8-CW-RFQ / Renovation of Go Infrastructure Rehabilitation Request for Quota Request for Quota Single Stage - One E Under Imple 2023-08-1 vernment Day Secondary Sc IDA / 59880 and Service Delivery Restora Post Limited tions (Non Bank-S 400,000.00 0.00 2023-01-17 2023-02-15 tions nvelope mentation 4 hool UBA in Hong Local Gove tion & Improvement PD) rnment Area of Adamawa Sta te. NG-ADAMAWA MCRP-35276 Infrastructure Rehabilitation Request for Quota 5-CW-RFQ / Provision of Solar Request for Quota Single Stage - One E Pending Imp 2023-11-0 IDA / 66490 and Service Delivery Restora Post Limited tions (Non Bank-S 1,435,506.00 0.00 2023-04-05 2023-05-06 Powered Bore Holes (SPBHs) tions nvelope lementation 2 tion & Improvement PD) in public places and in Comm unity based woodlots Request for Bids - NG-ADAMAWA MCRP-35600 Infrastructure Rehabilitation Single Stage - One E Small Works SPD Pending Imp 2023-12-2 5-CW-RFB / Upgrade/Renovat IDA / 66490 and Service Delivery Restora Post Request for Bids Limited 3,987,166.00 0.00 2023-04-25 2023-04-30 2023-05-30 2023-06-20 2023-07-02 nvelope (1 envelope proce lementation 9 ion of 6 nos. Schools in Adam tion & Improvement ss) awa State NG-ADAMAWA MCRP-35598 Request for Bids - Infrastructure Rehabilitation 6-CW-RFB / Rehabilitation of Single Stage - One E Small Works SPD Pending Imp 2023-10-2 IDA / 66490 and Service Delivery Restora Post Request for Bids Limited 1,200,000.00 0.00 2023-04-24 2023-04-29 2023-05-29 2023-06-19 2023-07-01 Primary Health Care Centers nvelope (1 envelope proce lementation 9 tion & Improvement (PHCCs) in Adamawa State. ss) NG-ADAMAWA MCRP-35597 Request for Bids - Infrastructure Rehabilitation 4-CW-RFB / Rehabilitation of Single Stage - One E Works (without pr Under Imple 2024-03-0 IDA / 66490 and Service Delivery Restora Post Request for Bids Limited 7,718,910.00 0.00 2023-04-18 2023-04-27 2023-04-23 2023-05-10 2023-05-28 2023-06-07 2023-06-27 2023-06-29 2023-07-09 (6) Roads in (3) Local Govern nvelope equalification) SP mentation 5 tion & Improvement ment Areas in Adamawa Stat D e. GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NG-ADAMAWA MCRP-59598- Infrastructure Rehabilitation Single Stage - One E GO-RFB / Supply of Furniture IDA / 59880 and Service Delivery Restora Post Request for Bids Open - National 245,901.64 0.00 Canceled 2018-02-23 2018-02-28 2018-04-11 2018-05-11 2018-06-15 2018-12-12 nvelope to Primary Schools in 7 LGAs tion & Improvement NG-ADAMAWA MCRP-59960- Infrastructure Rehabilitation GO-RFB / Supply of Books an Single Stage - One E IDA / 59880 and Service Delivery Restora Post Request for Bids Open - National 327,868.85 0.00 Canceled 2018-02-23 2018-02-28 2018-04-11 2018-05-11 2018-06-15 2018-12-12 d Teaching/Learning Materia nvelope tion & Improvement ls to Primary Schools in 7 LG As NG-ADAMAWA MCRP-60401- Infrastructure Rehabilitation GO-RFB / Establishment of sp Single Stage - One E IDA / 59880 and Service Delivery Restora Post Request for Bids Open - National 114,754.10 0.00 Canceled 2018-03-13 2018-03-18 2018-04-29 2018-05-29 2018-07-03 2018-12-30 are part supply chain/buffer s nvelope tion & Improvement tock for Water Facilities NG-ADAMAWA MCRP-60936- GO-RFB / Train the Trainer/Us er Workshops (i.e. 2 per LGA) Infrastructure Rehabilitation for VLOM (Village Level Oper Single Stage - One E IDA / 59880 and Service Delivery Restora Post Request for Bids Open - National 72,131.15 0.00 Canceled 2018-03-19 2018-03-24 2018-05-05 2018-06-04 2018-07-09 2019-01-05 ation and Maintenance) WAS nvelope tion & Improvement HCOMS, (WASH Committees at LGA Level, WASH Units @ LGAs, VHPs (Voluntary Hygie ne Promoters) State/LGA Gov t Officials. NG-ADAMAWA MCRP-60957- Technical Assistance and Pro Request for Quota Single Stage - One E Under Imple GO-RFQ / Procurement of 1 V IDA / 59880 Post Open - National 20,327.87 0.00 2018-02-18 2018-04-15 2018-10-12 ject Management Support tions nvelope mentation ideo Camera, 2 DLSR Camera s, NG-ADAMAWA MCRP-74572- GO-DIR / Procurement of Vid Technical Assistance and Pro IDA / 59880 Post Direct Selection Direct 85,249.00 67,807.55 Completed 2018-08-20 2018-10-22 2018-08-25 2018-09-18 2018-09-18 2018-11-09 2018-12-17 2019-01-10 eo Conference Equipment an ject Management Support d Internet Connectivity (Dedi cated) for 1 year. NG-ADAMAWA MCRP-69762- GO-RFQ / Procurement of 1 S Technical Assistance and Pro Request for Quota Single Stage - One E Under Imple port Utility Vehicle, 1 Eightee IDA / 59880 Post Limited 548,652.20 0.00 2018-07-21 2018-09-15 2019-03-14 ject Management Support tions nvelope mentation n Seater Bus, 3 Double Cabin Pick Up Vans and 1 Four Doo r Sedan. NG-ADAMAWA MCRP-69822- Strengthening Peace Buildin Request for Quota Single Stage - One E GO-RFQ / Provission of Small IDA / 59880 g, Stability and Social Cohesi Post Limited 183,431.00 171,132.92 Completed 2018-08-23 2020-06-30 2018-09-16 2020-08-15 2018-10-31 2020-09-09 tions nvelope Animals For Livelihood Suppo on rt NG-ADAMAWA MCRP-69753- Strengthening Peace Buildin Request for Quota Single Stage - One E GO-RFQ / Non Agricultural Liv IDA / 59880 g, Stability and Social Cohesi Post Limited 587,131.00 500,323.91 Completed 2018-08-22 2018-11-20 2018-10-17 2018-12-18 2018-12-26 2019-02-28 tions nvelope elihood Kits. on Page 4 NG-ADAMAWA MCRP-69823- Infrastructure Rehabilitation Request for Quota Single Stage - One E GO-RFQ / Equipping of Traum IDA / 59880 and Service Delivery Restora Post Limited 214,142.46 383,168.90 Completed 2018-08-05 2022-03-08 2018-09-30 2022-04-05 2019-03-29 tions nvelope a Center @ Mubi General hos tion & Improvement pital NG-ADAMAWA MCRP-60958- Technical Assistance and Pro Request for Quota Single Stage - One E Under Imple GO-RFQ / Procurement of Offi IDA / 59880 Post Open - National 63,445.10 0.00 2018-08-15 2018-09-19 2018-09-26 ject Management Support tions nvelope mentation ce Furniture NG-ADAMAWA MCRP-74000- GO-RFQ / Supply of Teaching Infrastructure Rehabilitation Request for Quota Single Stage - One E Materials, Labrotary Equipme IDA / 59880 and Service Delivery Restora Post Limited 786,885.00 668,444.08 Completed 2018-08-20 2019-03-07 2018-09-27 2019-04-13 2019-01-05 2019-06-22 tions nvelope nts and First aid Kits to Reha tion & Improvement bilitated Secondary Schools. NG-ADAMAWA MCRP-74210- Strengthening Peace Buildin Request for Quota Single Stage - One E GO-RFQ / Supply of Non-Food IDA / 59880 g, Stability and Social Cohesi Post Limited 492,071.00 379,396.71 Completed 2018-08-21 2018-09-07 2018-09-28 2018-12-10 2018-12-27 2019-01-28 tions nvelope Item Kits For House-hold Sup on port NG-ADAMAWA MCRP-74608- GO-RFQ / Installation of Solar Infrastructure Rehabilitation Request for Quota Single Stage - One E Inverters in 7 Rehabilitated P IDA / 59880 and Service Delivery Restora Post Open - National 249,180.00 243,777.83 Completed 2018-08-20 2018-10-11 2021-12-21 2019-01-19 2022-03-19 tions nvelope HCs, Cottage Hospital in Gula tion & Improvement k and General Hospital Michi ka. NG-ADAMAWA MCRP-74618- GO-RFQ / Supply of Medical E Infrastructure Rehabilitation Request for Quota Single Stage - One E quipment to Rehabilitated P IDA / 59880 and Service Delivery Restora Post Open - National 540,984.00 501,499.87 Completed 2018-08-20 2018-10-11 2020-12-11 2019-01-14 2021-03-25 tions nvelope HCs in 7 communities, Cotta tion & Improvement ge Hospital in Gulak and Gen eral Hospital Michika. NG-ADAMAWA MCRP-74624- Infrastructure Rehabilitation GO-RFQ / Supply of Classroo Request for Quota Single Stage - One E Under Imple IDA / 59880 and Service Delivery Restora Post Open - National 658,643.00 0.00 2018-08-20 2018-10-11 2019-01-19 m Furniture for all Renovated tions nvelope mentation tion & Improvement Secondary Schools. NG-ADAMAWA MCRP-59138- Technical Assistance and Pro Request for Quota Single Stage - One E Under Imple GO-RFQ / Procurement of Co IDA / 59880 Post Open - National 34,131.15 0.00 2018-02-18 2018-04-15 2018-07-14 ject Management Support tions nvelope mentation mputers, Printers and other a ccessories NG-ADAMAWA MCRP-60359- GO-RFQ / Procurement of 60 Technical Assistance and Pro Request for Quota Single Stage - One E IDA / 59880 Post Open - National 42,623.00 28,945.26 Completed 2018-02-18 2018-04-15 2018-09-05 2018-10-12 2018-11-10 KVA sound proof Generator, ject Management Support tions nvelope 10KVA Inverter System NG-ADAMAWA MCRP-69797- Strengthening Peace Buildin GO-RFQ / Provision of Agricul Request for Quota Single Stage - One E IDA / 59880 g, Stability and Social Cohesi Prior Limited 1,733,846.00 0.00 Canceled 2018-11-03 2018-12-01 2019-01-15 tural Support kits with Seeds, tions nvelope on Fertilizers and Small Work Fa rm Tools NG-ADAMAWA MCRP-69802- GO-RFQ / Supply of Essential Infrastructure Rehabilitation Drugs/Medical Consumable t Request for Quota Single Stage - One E IDA / 59880 and Service Delivery Restora Post Open - National 649,180.00 597,201.60 Completed 2018-12-17 2019-02-07 2020-12-11 2019-05-18 2021-01-01 o Rehabilitated PHCs in 7 Co tions nvelope tion & Improvement mmunities, Cottage Hospital in Gulak and General Hospita l Michika. NG-ADAMAWA MCRP-10054 Strengthening Peace Buildin Request for Quota Single Stage - One E 3-GO-RFQ / Supply of Cereals IDA / 59880 g, Stability and Social Cohesi Post Limited 808,082.00 654,880.67 Completed 2018-11-03 2019-02-27 2018-12-29 2019-03-21 2019-06-27 2019-05-28 tions nvelope and Legumes Seeds, on NG-ADAMAWA MCRP-10055 Strengthening Peace Buildin Request for Quota Single Stage - One E 1-GO-RFQ / Supply of Fertiliz IDA / 59880 g, Stability and Social Cohesi Post Limited 624,671.00 504,611.67 Completed 2018-11-03 2019-02-27 2018-12-29 2019-03-13 2019-06-27 2019-05-14 tions nvelope er and Small Work Farm Tool on s NG-ADAMAWA MCRP-10142 Infrastructure Rehabilitation 4-GO-RFQ / Establishment of Request for Quota Single Stage - One E IDA / 59880 and Service Delivery Restora Post Limited 114,754.00 0.00 Completed 2018-03-18 2023-03-08 2018-05-13 2018-11-09 2023-06-05 spare part supply chain/buffe tions nvelope tion & Improvement r stock for Water Facilities NG-ADAMAWA MCRP-10137 Infrastructure Rehabilitation Request for Quota Single Stage - One E Under Imple 9-GO-RFQ / Supply of Furnitu IDA / 59880 and Service Delivery Restora Post Limited 245,901.00 0.00 2018-02-28 2018-04-25 2018-10-22 tions nvelope mentation re to Primary Schools in 7 LG tion & Improvement As NG-ADAMAWA MCRP-10141 Infrastructure Rehabilitation 9-GO-RFQ / Supply of Books Request for Quota Single Stage - One E IDA / 59880 and Service Delivery Restora Post Limited 327,868.00 273,530.41 Completed 2018-02-28 2019-03-07 2018-04-25 2019-04-10 2018-10-22 2019-04-25 and Teaching/Learning Mate tions nvelope tion & Improvement rials to Primary Schools in 7 L GAs NG-ADAMAWA MCRP-10960 0-GO-RFQ / Installation of CC Technical Assistance and Pro Request for Quota Single Stage - One E IDA / 59880 Post Limited 32,000.00 22,640.15 Completed 2019-04-17 2019-09-03 2019-05-06 2019-10-01 2019-05-20 2019-10-04 TV and Intercom System for t ject Management Support tions nvelope he Adamawa MCRP PCU Offic e NG-ADAMAWA MCRP-10969 Infrastructure Rehabilitation 3-GO-RFQ / Networking of Off Request for Quota Single Stage - One E Pending Impl IDA / 59880 and Service Delivery Restora Post Limited 6,800.00 0.00 2019-04-18 2019-05-06 2019-05-20 ice Computer Systems, print tions nvelope ementation tion & Improvement ers and other accessories. NG-ADAMAWA MCRP-13354 Infrastructure Rehabilitation 8-GO-RFQ / Branding and Pac Request for Quota Single Stage - One E IDA / 59880 and Service Delivery Restora Post Limited 24,875.00 20,744.10 Completed 2019-07-28 2019-07-30 2019-08-25 2019-08-31 2019-09-15 2019-09-10 kaging of Books, Instructional tions nvelope tion & Improvement Material, Laboratory Equipme nt and First Aid Kits. NG-ADAMAWA MCRP-15664 4-GO-RFQ / Supply of Solar in Infrastructure Rehabilitation Request for Quota Single Stage - One E frastructure and computers f IDA / 59880 and Service Delivery Restora Post Limited 78,977.88 73,982.97 Completed 2020-08-23 2020-10-12 2020-10-18 2020-12-01 2021-04-16 2021-06-29 tions nvelope or Rehabilitated Local Gover tion & Improvement nments Secretariat, Song an d Madagali. NG-ADAMAWA MCRP-15663 Infrastructure Rehabilitation 6-GO-RFQ / Supply of Office F Request for Quota Single Stage - One E IDA / 59880 and Service Delivery Restora Post Limited 72,338.00 63,368.86 Completed 2020-08-23 2020-10-12 2020-10-02 2020-11-26 2021-01-30 2021-04-16 urnitures for Rehabilitated Lo tions nvelope tion & Improvement cal Governments Secretariat, Song NG-ADAMAWA MCRP-17741 Strengthening Peace Buildin Request for Quota Single Stage - One E 7-GO-RFQ / Provision of Non IDA / 59880 g, Stability and Social Cohesi Post Limited 770,000.00 720,510.32 Completed 2020-06-27 2020-11-11 2020-08-04 2020-12-08 2020-09-23 2020-12-17 tions nvelope Agric Livelihood Kits on NG-ADAMAWA MCRP-17755 Infrastructure Rehabilitation 8-GO-RFQ / Purchase of Furni Request for Quota Single Stage - One E IDA / 59880 and Service Delivery Restora Post Limited 550,000.00 536,094.89 Completed 2020-05-10 2021-03-09 2020-06-28 2021-04-15 2020-12-25 2021-05-15 ture for 8 Sec Schs. Includin tions nvelope tion & Improvement g mattresses for GSS Maiha Page 5 NG-ADAMAWA MCRP-17740 Infrastructure Rehabilitation 6-GO-RFQ / Provision of Solar Request for Quota Single Stage - One E IDA / 59880 and Service Delivery Restora Post Limited 250,000.00 259,629.93 Signed 2020-05-12 2021-11-18 2020-06-23 2021-12-16 2020-09-21 Inverters and Accessories for tions nvelope tion & Improvement Rehabilitated PHCs NG-ADAMAWA MCRP-15666 Technical Assistance and Pro Request for Quota Single Stage - One E Pending Impl 5-GO-RFQ / Purchase of com IDA / 59880 Post Limited 5,000.00 0.00 2020-07-03 2020-08-08 2020-09-07 ject Management Support tions nvelope ementation puters and other accessories for PCU NG-ADAMAWA MCRP-16945 Technical Assistance and Pro Request for Quota Single Stage - One E 7-GO-RFQ / Purchase of AC U IDA / 59880 Post Limited 10,000.00 10,230.28 Completed 2020-07-04 2021-04-22 2020-08-06 2021-05-26 2020-08-27 2021-06-25 ject Management Support tions nvelope nits and Furniture for Office NG-ADAMAWA MCRP-17628 Infrastructure Rehabilitation Request for Quota Single Stage - One E 0-GO-RFQ / Purchase of Book IDA / 59880 and Service Delivery Restora Post Limited 250,000.00 242,339.55 Completed 2020-08-23 2021-02-09 2020-10-07 2021-03-13 2020-11-16 2021-04-01 tions nvelope s and Instructional Materials f tion & Improvement or 8 Sec. Schools NG-ADAMAWA MCRP-17755 Infrastructure Rehabilitation Request for Quota Single Stage - One E 2-GO-RFQ / Purchase of Class IDA / 59880 and Service Delivery Restora Post Limited 300,000.00 290,583.94 Completed 2020-09-22 2020-03-09 2020-11-10 2020-04-15 2021-03-10 2021-06-18 tions nvelope room Furniture for 7 Primary tion & Improvement Schools NG-ADAMAWA MCRP-17741 Infrastructure Rehabilitation 9-GO-RFQ / Purchase of Book Request for Quota Single Stage - One E IDA / 59880 and Service Delivery Restora Post Limited 200,000.00 192,061.45 Completed 2020-09-13 2021-02-09 2020-10-28 2021-03-13 2021-01-26 2021-04-01 s and Instructional Materials f tions nvelope tion & Improvement or 7 Primary. Schools NG-ADAMAWA MCRP-17762 Infrastructure Rehabilitation 0-GO-RFQ / Provision of Drug Request for Quota Single Stage - One E IDA / 59880 and Service Delivery Restora Post Limited 200,000.00 210,000.01 Signed 2020-09-29 2022-03-08 2020-11-17 2022-04-05 2021-02-15 s and Essential Supplies to P tions nvelope tion & Improvement rimary Health Care Centers NG-ADAMAWA MCRP-15663 3-GO-RFQ / Purchase of furni Infrastructure Rehabilitation Request for Quota Single Stage - One E ture for Primary and Second IDA / 59880 and Service Delivery Restora Post Limited 300,000.00 290,632.60 Completed 2020-10-03 2021-03-09 2020-11-28 2021-04-15 2021-03-28 2021-06-19 tions nvelope ary Schools in Michika and M tion & Improvement adagali LGAs of Adamawa St ate NG-ADAMAWA MCRP-15667 3-GO-RFQ / Purchase of Boo Infrastructure Rehabilitation Request for Quota Single Stage - One E ks and Instructional Materials IDA / 59880 and Service Delivery Restora Post Limited 300,000.00 288,756.81 Completed 2020-08-01 2021-02-09 2020-09-19 2021-03-24 2020-12-08 2021-04-24 tions nvelope for Primary and Secondary in tion & Improvement Michika and Madagali LGAs o f Adamawa State NG-ADAMAWA MCRP-15664 Strengthening Peace Buildin 8-GO-RFQ / Supply of basic n Request for Quota Single Stage - One E IDA / 59880 g, Stability and Social Cohesi Post Limited 150,000.00 131,597.00 Completed 2020-07-18 2020-09-29 2020-09-05 2020-10-23 2020-11-04 2020-11-12 ecessity packs for Children (t tions nvelope on o include nutrition packs) NG-ADAMAWA MCRP-15665 Strengthening Peace Buildin Request for Quota Single Stage - One E 0-GO-RFQ / Supply of agricul IDA / 59880 g, Stability and Social Cohesi Post Limited 250,000.00 230,730.26 Completed 2020-07-18 2020-06-29 2020-09-05 2020-07-14 2020-11-04 2020-08-14 tions nvelope tural livelihood support kits t on o include Poultry NG-ADAMAWA MCRP-15627 Infrastructure Rehabilitation Request for Quota Single Stage - One E 9-GO-RFQ / Supply of Basic Li IDA / 59880 and Service Delivery Restora Post Limited 300,000.00 278,829.27 Completed 2020-07-22 2020-11-11 2020-09-09 2020-12-08 2020-11-08 2020-12-08 tions nvelope velihood Kits tion & Improvement NG-ADAMAWA MCRP-10055 Strengthening Peace Buildin Request for Quota Single Stage - One E IDA / 59880 Post Limited 301,092.00 230,129.29 Completed 2018-11-03 2019-02-27 2018-12-29 2019-03-16 2019-06-27 2019-05-15 3-GO-RFQ / Supply of Vegeta g, Stability and Social Cohesi tions nvelope ble Seeds on NG-ADAMAWA MCRP-27780 Infrastructure Rehabilitation 9-GO-RFQ / Procurement of 3 Request for Quota Single Stage - One E IDA / 66490 and Service Delivery Restora Post Limited 525,000.00 564,985.64 Completed 2022-03-30 2022-04-12 2022-04-25 2022-05-11 2022-06-04 2022-06-28 ''inch Solar Powered Water P tions nvelope tion & Improvement umps in Adamawa State. NG-ADAMAWA MCRP-27811 Infrastructure Rehabilitation Request for Quota Single Stage - One E 8-GO-RFQ / Equipping and Fu IDA / 66490 and Service Delivery Restora Post Limited 137,641.00 136,639.09 Completed 2022-03-20 2022-04-27 2022-04-15 2022-06-09 2022-05-25 2022-07-22 tions nvelope rnishing of Gombi Vetinerary tion & Improvement Clinic NG-ADAMAWA MCRP-27778 Strengthening Peace Buildin 3-GO-RFQ / Procurement of l Request for Quota Single Stage - One E Pending Impl IDA / 66490 g, Stability and Social Cohesi Post Limited 350,200.00 0.00 2022-05-03 2022-05-29 2022-07-18 arge ruminant animals (Cattl tions nvelope ementation on e) in Adamawa State. NG-ADAMAWA MCRP-27811 2-GO-RFQ / Procurement of Strengthening Peace Buildin Request for Quota Single Stage - One E Pending Impl Chaff/Fodder Cutting machin IDA / 66490 g, Stability and Social Cohesi Post Limited 100,626.00 0.00 2022-04-17 2022-05-13 2022-06-22 tions nvelope ementation es to support cooperatives in on fodder to boost Animal feed. NG-ADAMAWA MCRP-27772 Strengthening Peace Buildin Request for Quota Single Stage - One E Pending Impl 8-GO-RFQ / Procurement of f IDA / 66490 g, Stability and Social Cohesi Post Limited 50,000.00 0.00 2022-04-17 2022-05-17 2022-06-26 tions nvelope ementation eeds for Large Ruminants. on NG-ADAMAWA MCRP-27780 Strengthening Peace Buildin Request for Quota Single Stage - One E Pending Impl 3-GO-RFQ / Procurement of M IDA / 66490 g, Stability and Social Cohesi Post Limited 50,000.00 0.00 2022-04-17 2022-05-13 2022-06-12 tions nvelope ementation edication for Large Ruminant on s NG-ADAMAWA MCRP-27811 Strengthening Peace Buildin 0-GO-RFQ / Procurement of A Request for Quota Single Stage - One E Pending Impl IDA / 66490 g, Stability and Social Cohesi Post Limited 250,000.00 0.00 2022-04-04 2022-04-30 2022-06-09 ssorted Foundation Seeds to tions nvelope ementation on Community based Seed Prod uction clusters NG-ADAMAWA MCRP-27813 Strengthening Peace Buildin 8-GO-RFQ / Procurement of I Request for Quota Single Stage - One E IDA / 66490 g, Stability and Social Cohesi Post Limited 300,000.00 296,283.62 Completed 2022-06-11 2022-03-08 2022-07-07 2022-04-05 2022-08-16 2022-09-01 nputs tools and Kits to identif tions nvelope on ied Cooperatives. (Dry and R ain Fed Season) NG-ADAMAWA MCRP-27802 8-GO-RFQ / Procurement of M Strengthening Peace Buildin Request for Quota Single Stage - One E Under Imple ini Oil Extraction machines fo IDA / 66490 g, Stability and Social Cohesi Post Limited 150,000.00 0.00 2022-05-09 2022-08-24 2022-06-04 2022-07-14 tions nvelope mentation r Groundnut oil/Soybean and on Sesame Oil processing in Ada mawa State. NG-ADAMAWA MCRP-27833 2-GO-RFQ / Procurement of H Infrastructure Rehabilitation Request for Quota Single Stage - One E Pending Impl and held GIS and IDA / 66490 and Service Delivery Restora Post Limited 9,027.00 0.00 2022-03-27 2022-05-10 2022-06-09 tions nvelope ementation other equipments for collecti tion & Improvement on of Road Data Page 6 NG-ADAMAWA MCRP-27779 3-GO-RFQ / Procurement of F Strengthening Peace Buildin odder seeds (Bracharia, Labl Request for Quota Single Stage - One E Pending Impl IDA / 66490 g, Stability and Social Cohesi Post Limited 100,626.00 0.00 2022-04-25 2022-05-21 2022-06-30 ab, Northern Gamba, Stylosa tions nvelope ementation on nthes) to Animal Husbandry Cooperatives for livestock far ming in Adamawa State. NG-ADAMAWA MCRP-31055 Technical Assistance and Pro Request for Quota Single Stage - One E 9-GO-RFQ / Acs, Computers, IDA / 66490 Post Limited 70,000.00 0.00 Completed 2022-09-02 2022-11-28 2022-09-28 2022-11-07 ject Management Support tions nvelope Laptops, Printers, Photocopie r NG-ADAMAWA MCRP-31055 Technical Assistance and Pro Request for Quota Single Stage - One E Under Imple IDA / 66490 Post Limited 30,000.00 0.00 2022-09-02 2022-09-29 2022-11-08 5-GO-RFQ / Project Staff Furn ject Management Support tions nvelope mentation iture NG-ADAMAWA MCRP-31073 Technical Assistance and Pro Request for Quota Single Stage - One E Pending Impl 5-GO-RFQ / Procurement of E IDA / 66490 Post Limited 25,000.00 0.00 2022-09-07 2022-10-03 2022-12-02 ject Management Support tions nvelope ementation lectronic Document Manage ment System NG-ADAMAWA MCRP-31073 Technical Assistance and Pro Request for Quota Single Stage - One E Under Imple 6-GO-RFQ / Fire Protective & IDA / 66490 Post Limited 25,000.00 0.00 2022-09-07 2022-08-24 2022-10-02 2022-11-11 ject Management Support tions nvelope mentation Prevention Equipments NG-ADAMAWA MCRP-31056 Technical Assistance and Pro Request for Quota Single Stage - One E Under Imple IDA / 66490 Post Limited 40,000.00 0.00 2022-09-13 2022-11-28 2022-10-09 2022-12-08 2-GO-RFQ / Purchase of Powe ject Management Support tions nvelope mentation r Generator NG-ADAMAWA MCRP-31056 Infrastructure Rehabilitation Request for Quota Single Stage - One E 5-GO-RFQ / Furniture Supplie IDA / 66490 and Service Delivery Restora Post Limited 479,278.00 0.00 Signed 2022-09-13 2022-08-24 2022-10-10 2023-01-28 tions nvelope s to 6 Schools (Secondary) Sc tion & Improvement hools NG-ADAMAWA MCRP-31073 Infrastructure Rehabilitation Request for Quota Single Stage - One E 3-GO-RFQ / Furniture Supplie IDA / 66490 and Service Delivery Restora Post Limited 959,278.00 0.00 Signed 2022-09-13 2022-08-24 2022-10-09 2023-02-06 tions nvelope s to 6 Schools (Primary) tion & Improvement NG-ADAMAWA MCRP-32025 Strengthening Peace Buildin Request for Quota Single Stage - One E 8-GO-RFQ / Procurement of S IDA / 66490 g, Stability and Social Cohesi Post Limited 366,364.00 0.00 Completed 2022-10-31 2022-10-12 2022-11-26 2023-01-25 tions nvelope afety kits/work tools for LIPW on beneficiaries NG-ADAMAWA MCRP-32025 Strengthening Peace Buildin 7-GO-RFQ / Provision of equi Request for Quota Single Stage - One E IDA / 66490 g, Stability and Social Cohesi Post Limited 200,000.00 0.00 Completed 2022-10-25 2022-10-12 2022-11-20 2023-01-19 pment and supplies to fish fa tions nvelope on rmer cooperatives NG-ADAMAWA MCRP-32024 Strengthening Peace Buildin 3-GO-RFQ / Procurement of T Request for Quota Single Stage - One E Pending Impl IDA / 66490 g, Stability and Social Cohesi Post Limited 30,000.00 0.00 2022-11-09 2022-12-06 2023-02-04 ube well drilling rigs to youth tions nvelope ementation on farmer cooperative groups. NG-ADAMAWA MCRP-32026 4-GO-RFQ / Procurement of h Strengthening Peace Buildin Request for Quota Single Stage - One E Pending Impl igh volume solar irrigation pu IDA / 66490 g, Stability and Social Cohesi Post Limited 300,000.00 0.00 2022-11-10 2022-12-06 2023-02-04 tions nvelope ementation mps for the rehabilitated Irrig on ation Project sites under 1.02 in 3 LGAs NG-ADAMAWA MCRP-32024 0-GO-RFQ / Procurement and Strengthening Peace Buildin distribution of fodder seeds ( Request for Quota Single Stage - One E Pending Impl IDA / 66490 g, Stability and Social Cohesi Post Limited 100,626.00 0.00 2022-11-11 2022-12-07 2023-02-05 Bracharia, Lablab, Northern tions nvelope ementation on Gamba, Stylosanthes) to Ani mal Husbandry Cooperatives for livestock farming. NG-ADAMAWA MCRP-32024 Strengthening Peace Buildin 4-GO-RFQ / Refurbishing and Request for Quota Single Stage - One E Pending Impl IDA / 66490 g, Stability and Social Cohesi Post Limited 135,000.00 0.00 2022-11-12 2022-12-11 2023-06-09 Upgrade of Fufore Fish Hatch tions nvelope ementation on ery including brood stock an d consumables NG-ADAMAWA MCRP-32026 Technical Assistance and Pro Request for Quota Single Stage - One E 1-GO-RFQ / Purchase of 2 No IDA / 66490 Post Limited 171,000.00 0.00 Completed 2022-11-22 2023-01-10 2022-12-21 2023-02-19 ject Management Support tions nvelope s Hilux Pickup Vans NG-ADAMAWA MCRP-32026 5-GO-RFQ / Strategic Commu Technical Assistance and Pro Request for Quota Single Stage - One E IDA / 66490 Post Limited 60,000.00 0.00 Completed 2022-11-22 2022-11-28 2022-12-18 2023-02-16 nications (Equipment Camer ject Management Support tions nvelope as, lights, Recorders) NG-ADAMAWA MCRP-27774 Infrastructure Rehabilitation Request for Quota Single Stage - One E Under Imple 4-GO-RFQ / Supply of Books f IDA / 66490 and Service Delivery Restora Post Limited 247,235.00 0.00 2022-07-27 2022-11-28 2022-08-24 2022-09-23 tions nvelope mentation or Secondary Schools in Ada tion & Improvement mawa State. NG-ADAMAWA MCRP-34038 Strengthening Peace Buildin 4-GO-RFQ / Provision of Briqu Request for Quota Single Stage - One E Pending Impl IDA / 66490 g, Stability and Social Cohesi Post Limited 64,750.00 0.00 2023-02-21 2023-03-22 2023-05-21 ette Making machines for val tions nvelope ementation on ue addition in agricultural wa ste NG-ADAMAWA MCRP-34307 Strengthening Peace Buildin 1-GO-RFQ / Supply of small r Request for Quota Single Stage - One E Pending Impl IDA / 66490 g, Stability and Social Cohesi Post Limited 177,577.00 0.00 2023-03-21 2023-04-18 2023-06-17 uminants as additional livest tions nvelope ementation on ock support to identified ben eficiary clusters NG-ADAMAWA MCRP-34307 Strengthening Peace Buildin Request for Quota Single Stage - One E Pending Impl 2-GO-RFQ / Procurement of f IDA / 66490 g, Stability and Social Cohesi Post Limited 100,000.00 0.00 2023-03-27 2023-04-24 2023-06-23 tions nvelope ementation eeds and medications for sm on all ruminants NG-ADAMAWA MCRP-34307 Infrastructure Rehabilitation Request for Quota Single Stage - One E 7-GO-RFQ / Purchase of Class IDA / 59880 and Service Delivery Restora Post Limited 495,082.00 0.00 Signed 2023-03-05 2023-02-28 2023-04-02 2023-07-01 tions nvelope room Furniture tion & Improvement NG-ADAMAWA MCRP-34308 Infrastructure Rehabilitation 0-GO-RFQ / Supply of Instruct Request for Quota Single Stage - One E Pending Impl IDA / 66490 and Service Delivery Restora Post Limited 273,853.00 0.00 2023-03-20 2023-04-16 2023-06-15 ional Materials to Primary an tions nvelope ementation tion & Improvement d Secondary Schools NG-ADAMAWA MCRP-34308 Infrastructure Rehabilitation Request for Quota Single Stage - One E Pending Impl 2-GO-RFQ / Supply of Laborat IDA / 66490 and Service Delivery Restora Post Limited 65,277.00 0.00 2023-03-25 2023-04-21 2023-05-21 tions nvelope ementation ory Euipment to Senior Seco tion & Improvement ndary Schools NG-ADAMAWA MCRP-34326 Infrastructure Rehabilitation Request for Quota Single Stage - One E 9-GO-RFQ / Supply of Medical IDA / 66490 and Service Delivery Restora Post Limited 200,000.00 0.00 Completed 2023-03-07 2023-03-08 2023-04-03 2023-06-02 2023-05-13 tions nvelope Equipment to Rehabilitated P tion & Improvement HCs in 7 LGAs Page 7 NG-ADAMAWA MCRP-34327 Infrastructure Rehabilitation Request for Quota Single Stage - One E 7-GO-RFQ / Supply of Furnitu IDA / 66490 and Service Delivery Restora Post Limited 350,000.00 0.00 Completed 2023-03-13 2023-03-08 2023-04-09 2023-07-08 tions nvelope re to rehabilitated Hospitals tion & Improvement and PHCCS NG-ADAMAWA MCRP-34342 Strengthening Peace Buildin 4-GO-RFQ / Rehabilitation of I Request for Quota Single Stage - One E Pending Impl IDA / 66490 g, Stability and Social Cohesi Post Limited 110,446.00 0.00 2023-03-11 2023-04-07 2023-08-05 nfrastructure and Fencing of tions nvelope ementation on Gombi Veterinary Clinic NG-ADAMAWA MCRP-34038 3-GO-RFQ / Provision of Mini Strengthening Peace Buildin Single Stage - One E Pending Impl Mechanized tools to farmer c IDA / 66490 g, Stability and Social Cohesi Post Request for Bids Limited 630,138.00 0.00 2023-03-14 2023-03-19 2023-04-30 2023-05-30 2023-06-05 2023-09-03 nvelope ementation ooperatives/groups (Hand Till on ers, Harrows, Planters, Multi- Crop Threshers etc) NG-ADAMAWA MCRP-34328 Strengthening Peace Buildin 7-GO-RFQ / Procurement of S Request for Quota Single Stage - One E Pending Impl IDA / 66490 g, Stability and Social Cohesi Post Limited 170,833.00 0.00 2023-03-15 2023-04-11 2023-06-10 porting Equipment for the re tions nvelope ementation on habilitated sports centers an d schools NG-ADAMAWA MCRP-34306 Strengthening Peace Buildin 9-GO-RFQ / Provision of Com Single Stage - One E Pending Impl IDA / 66490 g, Stability and Social Cohesi Post Request for Bids Limited 650,000.00 0.00 2023-03-15 2023-03-20 2023-04-10 2023-04-24 2023-05-01 2023-10-28 plete Set of Mini Rice process nvelope ementation on ing equipment to Cooperativ e Clusters/User groups. NG-ADAMAWA MCRP-34327 5-GO-RFQ / Supply of Essenti Infrastructure Rehabilitation al Drugs/Medical consumable Request for Quota Single Stage - One E IDA / 66490 and Service Delivery Restora Post Limited 320,000.00 0.00 Completed 2023-03-07 2023-03-08 2023-04-03 2023-06-02 s to Rehabilitated General Ho tions nvelope tion & Improvement spitals and PHCCs (based on the list of Essential Drugs by the FMoH & NPHCDA) NG-ADAMAWA MCRP-35280 Infrastructure Rehabilitation 4-GO-RFQ / Purchase of addit Request for Quota Single Stage - One E Pending Impl IDA / 66490 and Service Delivery Restora Post Limited 252,459.00 0.00 2023-04-10 2023-05-11 2023-07-10 ional equipment for Trauma tions nvelope ementation tion & Improvement Center at Mubi General Hospi tal NG-ADAMAWA MCRP-35275 Infrastructure Rehabilitation 5-GO-RFB / Supply and Install Single Stage - One E Under Imple IDA / 66490 and Service Delivery Restora Post Request for Bids Open - National 400,000.00 0.00 2023-04-25 2023-06-24 2023-04-30 2023-06-04 2023-07-04 2023-07-18 2024-01-14 ation of Solar Inverter Syste nvelope mentation tion & Improvement ms for Rehabilitated Hospital s and PHCCs NG-ADAMAWA MCRP-36558 Strengthening Peace Buildin 1-GO-RFQ / Procurement of e Request for Quota Single Stage - One E Pending Impl IDA / 66490 g, Stability and Social Cohesi Post Limited 79,565.00 0.00 2023-06-26 2023-07-25 2023-09-03 quipment for upgrade of Ada tions nvelope ementation on mawa state cooperative adm inistration system NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NG-ADAMAWA MCRP-69795- Infrastructure Rehabilitation Request for Quota Single Stage - One E Pending Impl NC-RFQ / Door to Door Collec IDA / 59880 and Service Delivery Restora Post Limited 236,065.57 0.00 2018-08-05 2018-09-30 2019-03-29 tions nvelope ementation tion of Solid waste in 7 LGAs tion & Improvement NG-ADAMAWA MCRP-16947 5-NC-RFQ / Production of Me Technical Assistance and Pro Request for Quota Single Stage - One E Pending Impl IDA / 59880 Post Limited 40,000.00 0.00 2020-07-26 2020-09-09 2020-10-19 dia Materials,Documentaries ject Management Support tions nvelope ementation Jingles,Billboards,Slots,Websi te NG-ADAMAWA MCRP-32025 Strengthening Peace Buildin 9-NC-RFQ / Procurement of P Request for Quota Single Stage - One E Pending Impl IDA / 66490 g, Stability and Social Cohesi Post Limited 155,495.00 0.00 2022-10-29 2022-12-03 2023-12-08 ayment Service Provider (PSP tions nvelope ementation on ) for LIPW Implementation CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NG-ADAMAWA MCRP-59463- Infrastructure Rehabilitation Consultant Qualifi Pending Impleme CS-CQS / Hygiene Promotion IDA / 59880 and Service Delivery Restora Post Open - National 85,677.59 0.00 2018-08-10 2018-08-10 2018-08-10 2018-08-10 2018-08-10 2018-08-10 cation Selection ntation Campaign tion & Improvement NG-ADAMAWA MCRP-69092- CS-CQS / Consultation for Sur Infrastructure Rehabilitation Consultant Qualifi Pending Impleme vey, Design and Supervision IDA / 59880 and Service Delivery Restora Post Open - National 284,494.58 0.00 2018-07-10 2018-07-13 2018-07-19 2018-07-23 2018-07-27 2018-08-11 cation Selection ntation of Health, Education and Publ tion & Improvement ic Buildings Projects under C omponent 2 NG-ADAMAWA MCRP-69097- Infrastructure Rehabilitation CS-CQS / Consultancy for Sur Consultant Qualifi Pending Impleme IDA / 59880 and Service Delivery Restora Post Open - National 494,021.00 0.00 2018-07-11 2018-07-13 2018-07-20 2018-07-23 2018-07-26 2018-08-16 vey, Design and Supervision cation Selection ntation tion & Improvement of Roads Projects under Com ponent 2 NG-ADAMAWA MCRP-62277- Infrastructure Rehabilitation CS-CQS / consultancy for Proj Consultant Qualifi IDA / 59880 and Service Delivery Restora Post Open - National 221,705.04 0.00 Canceled 2018-07-02 2018-07-23 2018-09-05 2018-10-05 2018-11-09 2019-05-08 ect design and Supervision fo cation Selection tion & Improvement r Road Projects Under Compo nent 2. NG-ADAMAWA MCRP-62278- Infrastructure Rehabilitation CS-CQS / Consultancy For Pro Consultant Qualifi IDA / 59880 and Service Delivery Restora Post Open - National 150,787.69 0.00 Canceled 2018-07-30 2018-08-20 2018-10-03 2018-11-02 2018-12-07 2019-06-05 ject Design and Supervision F cation Selection tion & Improvement or Water Projects Under Com ponent 2. NG-ADAMAWA MCRP-62006- CS-CQS / Consultancy for pro Infrastructure Rehabilitation Consultant Qualifi jects design and supervision IDA / 59880 and Service Delivery Restora Post Open - National 162,000.57 0.00 Canceled 2018-06-11 2018-07-02 2018-08-15 2018-09-14 2018-10-19 2019-04-17 cation Selection for Education, Health, and Pu tion & Improvement blic buildings Projects under Component 2. NG-ADAMAWA MCRP-60470- CS-CQS / Training of affecte Strengthening Peace Buildin Consultant Qualifi d farmers to apply inputs and IDA / 59880 g, Stability and Social Cohesi Post Open - National 167,213.00 0.00 Under Review 2018-08-16 2019-08-02 2018-08-23 2018-09-20 2018-10-04 2018-10-21 2018-12-20 cation Selection access targeted agricultural on value chains and agribusine ss skills Page 8 NG-ADAMAWA MCRP-73882- Strengthening Peace Buildin Consultant Qualifi CS-CQS / Provision of Speciali IDA / 59880 g, Stability and Social Cohesi Post Open - National 200,000.00 0.00 Under Review 2018-08-14 2018-10-30 2018-08-28 2018-09-28 2018-10-16 2018-11-13 2019-04-22 cation Selection sed Psycho-social needs ass on essment NG-ADAMAWA MCRP-59454- Strengthening Peace Buildin CS-CQS / Consultancy for Lea Consultant Qualifi Under Implement IDA / 59880 g, Stability and Social Cohesi Post Open - National 108,196.72 0.00 2018-02-05 2021-06-01 2018-02-05 2018-02-05 2018-02-05 2018-02-05 2018-02-05 dership Accountability and cation Selection ation on Transparency Training Progr amme NG-ADAMAWA MCRP-60475- Strengthening Peace Buildin CS-CQS / Capacity building of Consultant Qualifi Under Implement IDA / 59880 g, Stability and Social Cohesi Post Open - National 108,196.72 0.00 2018-02-23 2021-05-05 2018-03-02 2018-03-23 2018-04-13 2018-05-11 2018-09-08 LG Officers for economic plan cation Selection ation on ning and policy development NG-ADAMAWA MCRP-60855- CS-CQS / Capacity building o Strengthening Peace Buildin Consultant Qualifi Under Implement f LG Officers for local govern IDA / 59880 g, Stability and Social Cohesi Post Open - National 108,196.72 0.00 2018-02-23 2021-05-05 2018-03-09 2018-04-13 2018-05-04 2018-06-08 2018-10-06 cation Selection ation ments on budget planning an on d execution, monitoring and reporting NG-ADAMAWA MCRP-60956- CS-CQS / Capacity building o Strengthening Peace Buildin Consultant Qualifi Under Implement f LG Officers for strategic co IDA / 59880 g, Stability and Social Cohesi Post Open - National 108,196.72 0.00 2018-03-19 2021-05-07 2018-04-02 2018-05-07 2018-05-28 2018-07-02 2018-10-30 cation Selection ation mmunications (Legislative Ad on vocacy, Media relations, Stak eholder Management etc). NG-ADAMAWA MCRP-60852- Strengthening Peace Buildin Consultant Qualifi Under Implement CS-CQS / Capacity building fo IDA / 59880 g, Stability and Social Cohesi Post Open - National 108,196.72 0.00 2018-02-23 2021-05-05 2018-03-09 2018-04-13 2018-05-04 2018-06-08 2018-10-06 cation Selection ation r programme design and imp on lementation NG-ADAMAWA MCRP-60513- CS-CQS / Registration, Mappi Strengthening Peace Buildin Consultant Qualifi Under Implement ng and Profiling of all local go IDA / 59880 g, Stability and Social Cohesi Post Open - National 39,448.00 0.00 2018-02-23 2019-01-07 2018-03-16 2018-04-29 2018-05-29 2018-07-03 2018-12-30 cation Selection ation vernment structures and exis on ting capacities State Wide NG-ADAMAWA MCRP-73941- CS-CQS / Soft Skill Training/ r Strengthening Peace Buildin Consultant Qualifi Pending Impleme e-orientation on quick to Mar IDA / 59880 g, Stability and Social Cohesi Post Open - National 225,459.00 0.00 2018-08-19 2018-09-02 2018-09-23 2018-10-03 2018-10-20 2019-01-28 cation Selection ntation ket Trading, Training for Non on agricultural Kits (Refresher Tr aining Skill Upgrade) NG-ADAMAWA MCRP-60997- CS-CQS / Consultancy Servic Strengthening Peace Buildin Consultant Qualifi Under Implement es For Refresher Training of IDA / 59880 g, Stability and Social Cohesi Post Open - National 65,573.00 0.00 2018-08-22 2018-11-16 2018-08-29 2018-09-19 2018-10-03 2018-10-20 2019-01-28 cation Selection ation Existing Extension Workers t on o support Livelihoods Project s NG-ADAMAWA MCRP-69796- CS-CQS / Consultancy for Sen sitization, Community Mobiliz Strengthening Peace Buildin ation and formation of peace Consultant Qualifi IDA / 59880 g, Stability and Social Cohesi Prior Open - National 344,262.00 0.00 Canceled 2018-10-30 2019-06-27 2018-11-13 2018-12-11 2018-12-25 2019-01-11 2019-04-11 groups within 7 Communities cation Selection on (establishment of community platforms to discuss commun ity needs, grievances; and re dress mechanisms NG-ADAMAWA MCRP-69809- Strengthening Peace Buildin CS-CQS / Design and Implem Consultant Qualifi IDA / 59880 g, Stability and Social Cohesi Prior Open - National 344,262.00 0.00 Canceled 2018-10-29 2019-06-27 2018-11-05 2018-11-19 2018-11-26 2018-12-10 2019-04-09 entation of Adamawa State C cation Selection on ivic Education Programe NG-ADAMAWA MCRP-69806- CS-CQS / Sensitization and M Strengthening Peace Buildin obilisation Programs for Awar Consultant Qualifi IDA / 59880 g, Stability and Social Cohesi Prior Open - National 413,115.00 0.00 Canceled 2018-11-12 2018-11-26 2018-12-17 2018-12-31 2019-01-14 2019-05-14 eness against Stigmatization cation Selection on of Woman and Children asso ciated with armed groups. (1 No Consultancy) NG-ADAMAWA MCRP-69804- CS-CQS / Consultancy for Me diation and Alternate Dispute Strengthening Peace Buildin Consultant Qualifi Resolution Capacity Building IDA / 59880 g, Stability and Social Cohesi Prior Open - National 425,961.00 0.00 Canceled 2018-11-26 2018-12-03 2018-12-17 2018-12-24 2019-01-14 2019-04-14 cation Selection within the Community Leader on ship and Governance Structu res (3Nos Consultancies acro ssthe state) NG-ADAMAWA MCRP-73883- CS-CQS / Provision of Speciali sed Psycho-social support t Strengthening Peace Buildin Consultant Qualifi hrough group support, recre IDA / 59880 g, Stability and Social Cohesi Prior Open - National 442,622.95 0.00 Canceled 2018-12-10 2018-12-17 2019-01-03 2019-01-10 2019-01-24 2019-05-04 cation Selection ational , customary and socia on lization activities referrals etc responding to needs identifi ed during the assessment. NG-ADAMAWA MCRP-81646- CS-CQS / Consultancy for Sur Infrastructure Rehabilitation Consultant Qualifi Under Implement vey, Design and Supervision IDA / 59880 and Service Delivery Restora Post Open - National 213,675.22 0.00 2018-10-23 2018-07-03 2018-10-30 2018-11-13 2018-11-20 2018-11-30 2019-01-14 cation Selection ation of boreholes, VIP Latrines an tion & Improvement d Hygiene promotion Campai gn NG-ADAMAWA MCRP-81653- CS-CQS / Consultancy for Sur Infrastructure Rehabilitation Consultant Qualifi Under Implement vey, Design and Supervision IDA / 59880 and Service Delivery Restora Post Open - National 264,879.81 0.00 2018-10-23 2018-11-06 2018-10-30 2018-11-13 2018-11-20 2018-12-02 2019-03-02 cation Selection ation of small towns water project tion & Improvement s Rehabilitation and upgrade . NG-ADAMAWA MCRP-10143 4-CS-CQS / Train the Trainer/ User Workshops (i.e. 2 per L Infrastructure Rehabilitation GA) for VLOM (Village Level Consultant Qualifi Pending Impleme IDA / 59880 and Service Delivery Restora Post Open - National 72,131.00 0.00 2018-03-19 2018-04-09 2018-05-23 2018-06-22 2018-07-27 2019-01-23 Operation and Maintenance) cation Selection ntation tion & Improvement WASHCOMS, (WASH Committ ees at LGA Level, WASH Unit s @ LGAs, VHPs (Voluntary H ygiene Promoters) State/LGA Govt Officials. NG-ADAMAWA MCRP-12489 9-CS-CQS / Consultancy for S ensitization, Community Mob Strengthening Peace Buildin Consultant Qualifi ilization and formation of pea IDA / 59880 g, Stability and Social Cohesi Post Limited 290,000.00 0.00 Under Review 2019-08-05 2019-08-02 2019-08-19 2019-09-02 2019-09-17 2020-03-15 cation Selection ce groups and community pl on atforms to discuss communit y needs, grievances; and red ress mechanisms Page 9 NG-ADAMAWA MCRP-12491 Strengthening Peace Buildin 8-CS-CQS / Design and Imple Consultant Qualifi Under Implement IDA / 59880 g, Stability and Social Cohesi Post Limited 300,000.00 0.00 2019-08-05 2019-08-02 2019-08-19 2019-08-29 2019-09-15 2020-03-13 mentation of Adamawa State cation Selection ation on Civic Education Programe NG-ADAMAWA MCRP-12493 1-CS-CQS / Sensitization and Strengthening Peace Buildin mobilisation programs for aw Consultant Qualifi IDA / 59880 g, Stability and Social Cohesi Post Limited 300,000.00 0.00 Canceled 2019-08-15 2018-11-08 2019-08-29 2019-09-12 2019-10-03 2020-03-31 areness against stigmatizatio cation Selection on n of women and children ass ociated with armed groups. NG-ADAMAWA MCRP-12493 8-CS-CQS / Provision of Speci alised Psycho-social support Strengthening Peace Buildin Consultant Qualifi through group support, recr IDA / 59880 g, Stability and Social Cohesi Post Limited 300,000.00 0.00 Under Review 2019-09-11 2021-06-01 2019-09-25 2019-10-16 2019-11-06 2020-11-05 cation Selection eational , customary and soci on alization activities referrals e tc responding to needs ident ified during the assessment. NG-ADAMAWA MCRP-12494 0-CS-CQS / Consultancy for M Strengthening Peace Buildin ediation and Alternate Disput Consultant Qualifi Under Implement IDA / 59880 g, Stability and Social Cohesi Post Limited 300,000.00 0.00 2019-08-15 2020-09-01 2019-08-29 2019-09-19 2019-10-10 2020-04-07 e Resolution Capacity Buildin cation Selection ation on g within the Community Lead ership and Governance Struc tures NG-ADAMAWA MCRP-17754 Infrastructure Rehabilitation 6-CS-CQS / Capacity Building Consultant Qualifi Under Implement IDA / 59880 and Service Delivery Restora Post Limited 150,000.00 0.00 2020-06-25 2021-05-18 2020-07-09 2020-07-30 2020-08-16 2020-11-14 of Public Sector Personnel on cation Selection ation tion & Improvement Disaster Recovery Planning & Coordination NG-ADAMAWA MCRP-17756 Infrastructure Rehabilitation Consultant Qualifi Pending Impleme 8-CS-CQS / Training of Health IDA / 59880 and Service Delivery Restora Post Limited 100,000.00 0.00 2020-09-10 2020-09-24 2020-10-24 2020-11-28 2021-05-27 cation Selection ntation Workers (50) tion & Improvement NG-ADAMAWA MCRP-15627 1-CS-CQS / Consultancy Servi Infrastructure Rehabilitation Consultant Qualifi Under Implement ce for Survey, design and Su IDA / 59880 and Service Delivery Restora Post Limited 100,000.00 0.00 2020-07-20 2020-08-19 2020-08-03 2020-08-24 2020-09-08 2021-06-05 cation Selection ation pervision of Solar Powered tion & Improvement Boreholes in Adamawa State. (Water Sector) NG-ADAMAWA MCRP-27775 0-CS-CQS / Design and Deplo Strengthening Peace Buildin yment of Platform/Software f Consultant Qualifi Pending Impleme IDA / 66490 g, Stability and Social Cohesi Post Limited 50,000.00 0.00 2022-04-04 2022-04-18 2022-05-18 2022-06-22 2022-12-19 or Monitoring performance of cation Selection ntation on Beneficiaries of Agric. Livelih ood Kits/Small Animals by Ex tension Workers NG-ADAMAWA MCRP-27833 4-CS-CQS / Training of extens Strengthening Peace Buildin Consultant Qualifi Pending Impleme ion workers to support fame IDA / 66490 g, Stability and Social Cohesi Post Limited 180,000.00 0.00 2022-05-14 2022-05-28 2022-06-18 2022-07-23 2023-01-19 cation Selection ntation rs and Agribusiness Coopera on tives in Adamawa State. NG-ADAMAWA MCRP-27833 3-CS-CQS / Monitoring of Part Strengthening Peace Buildin Consultant Qualifi icipants and assessing the im IDA / 66490 g, Stability and Social Cohesi Post Limited 50,000.00 0.00 Under Review 2022-02-28 2022-06-25 2022-03-14 2022-04-04 2022-04-09 2022-06-08 cation Selection pact of Alternative Dispute R on esolution Capacity Building undertaken in 2020/21 NG-ADAMAWA MCRP-27778 9-CS-CQS / Training of Social Strengthening Peace Buildin Welfare & Youth Workers/Co Consultant Qualifi Pending Impleme IDA / 66490 g, Stability and Social Cohesi Post Limited 140,925.00 0.00 2022-05-10 2022-05-24 2022-06-14 2022-06-19 2022-07-29 mmunity/Religious leaders a cation Selection ntation on nd Women groups on Sexual and Gender Based Violence ( SGBV) in Adamawa State. NG-ADAMAWA MCRP-17757 2-CS-CQS / Consultancy Servi Infrastructure Rehabilitation ces for Design of An Impleme Consultant Qualifi Under Implement IDA / 59880 and Service Delivery Restora Post Limited 250,000.00 0.00 2020-07-31 2020-09-10 2020-08-14 2020-09-01 2020-09-22 2021-03-21 ntation Strategy for The Sust cation Selection ation tion & Improvement ainability and Functionality 0f Community Wash Facilities in Adamawa State. NG-ADAMAWA MCRP-27780 Strengthening Peace Buildin 4-CS-CQS / Targeting, Profilin Consultant Qualifi Under Implement IDA / 66490 g, Stability and Social Cohesi Post Limited 125,000.00 0.00 2022-02-28 2022-10-10 2022-03-14 2022-04-04 2022-04-09 2022-06-08 g and Identification of Farme cation Selection ation on r and Agribusiness Cooperati ves in Adamawa State. NG-ADAMAWA MCRP-27802 Strengthening Peace Buildin 2-CS-CQS / Assessment and Consultant Qualifi IDA / 66490 g, Stability and Social Cohesi Post Limited 130,000.00 0.00 Canceled 2022-03-03 2022-03-17 2022-04-07 2022-04-12 2022-05-22 upgrade of Adamawa State C cation Selection on ooperatives Administration S ystem NG-ADAMAWA MCRP-60954- Infrastructure Rehabilitation Consultant Qualifi CS-CQS / Sensitization and M IDA / 59880 and Service Delivery Restora Post Open - National 183,606.56 0.00 Canceled 2018-06-15 2018-06-15 2018-06-15 2018-06-15 2018-06-15 2018-06-15 cation Selection obilisation for Health (Outrea tion & Improvement ch Programs) NG-ADAMAWA MCRP-60983- Infrastructure Rehabilitation Consultant Qualifi CS-CQS / Teacher Training on IDA / 59880 and Service Delivery Restora Post Limited 210,181.65 0.00 Canceled 2020-10-29 2020-11-12 2020-12-03 2020-12-20 2021-04-19 cation Selection Pedagogy ( Primary and Seco tion & Improvement ndary Schools ) NG-ADAMAWA MCRP-60850- Infrastructure Rehabilitation CS-CQS / Training of Commu Consultant Qualifi IDA / 59880 and Service Delivery Restora Post Open - National 68,852.46 0.00 Canceled 2018-09-10 2018-10-01 2018-11-14 2018-12-14 2019-01-18 2019-07-17 nity Health Workers (CHeWs) cation Selection tion & Improvement to Staff Targeted Health Facil ities NG-ADAMAWA MCRP-60949- Infrastructure Rehabilitation Consultant Qualifi CS-CQS / Mobilization and Se IDA / 59880 and Service Delivery Restora Post Limited 111,885.24 0.00 Canceled 2020-10-05 2020-10-19 2020-11-06 2020-11-23 2021-03-15 cation Selection nsitization for Children Educa tion & Improvement tion NG-ADAMAWA MCRP-15664 1-CS-CQS / design and Super Infrastructure Rehabilitation Consultant Qualifi vision for Rehabilitation of P IDA / 59880 and Service Delivery Restora Post Limited 150,000.00 0.00 Canceled 2020-07-03 2020-07-17 2020-08-07 2020-08-24 2021-05-31 cation Selection rimary and Secondary School tion & Improvement s In Adamawa State.(Educati on Sector) NG-ADAMAWA MCRP-73939- CS-CQS / Capacity Building fo Strengthening Peace Buildin r Local Government Emergen Consultant Qualifi IDA / 59880 g, Stability and Social Cohesi Post Open - National 6,885.25 0.00 Canceled 2018-08-15 2018-08-29 2018-09-26 2018-10-10 2018-10-31 2019-02-28 cy Responders among Displa cation Selection on ced and Transitional Local Go vernment Officials per LGA Page 10 NG-ADAMAWA MCRP-29716 0-CS-CQS / CONSULTANCY S ERVICES FOR DESIGN AND S Infrastructure Rehabilitation UPERVISION OF REHABILITAT Consultant Qualifi Pending Impleme IDA / 59880 and Service Delivery Restora Prior Limited 300,000.00 0.00 2020-09-02 2020-09-16 2020-10-07 2020-10-17 2021-11-21 ION/RENOVATION OF PUBLIC cation Selection ntation tion & Improvement BUILDINGS(SCHOOLS AND H EALTH FACILITIES) IN THE SE VEN (7) INSURGENCY AFFECT ED LGAs IN ADAMAWA STATE . NG-ADAMAWA MCRP-31262 9-CS-CQS / Consultancy For F Technical Assistance and Pro Consultant Qualifi Under Implement IDA / 66490 Post Limited 15,000.00 0.00 2022-08-31 2022-10-18 2022-09-07 2022-09-28 2022-10-06 2022-11-15 unctional Review of Capacitie ject Management Support cation Selection ation s and Systems of PCU NG-ADAMAWA MCRP-32022 Strengthening Peace Buildin 5-CS-CQS / Procurement of LI Consultant Qualifi Under Implement IDA / 66490 g, Stability and Social Cohesi Post Limited 400,000.00 0.00 2022-10-25 2022-11-10 2022-11-08 2022-11-29 2022-12-07 2024-01-31 PW Implementing Partner (IP) cation Selection ation on for Beneficiary Targeting and process Management NG-ADAMAWA MCRP-32022 Infrastructure Rehabilitation Consultant Qualifi Under Implement 3-CS-CQS / Consultancy for D IDA / 66490 and Service Delivery Restora Post Limited 100,000.00 0.00 2022-10-27 2022-12-23 2022-11-10 2022-12-01 2022-12-10 2023-09-06 cation Selection ation esign and Supervision of Hea tion & Improvement lth Facilities NG-ADAMAWA MCRP-32025 Infrastructure Rehabilitation 5-CS-CQS / Consultancy for t Consultant Qualifi Under Implement IDA / 66490 and Service Delivery Restora Post Limited 288,525.00 0.00 2022-10-28 2022-12-23 2022-11-11 2022-12-02 2022-12-11 2023-11-06 he Survey, Design and Super cation Selection ation tion & Improvement vision of Schools Projects. NG-ADAMAWA MCRP-32025 2-CS-CQS / Consultancy on st Strengthening Peace Buildin udy to assess and redesign ir Consultant Qualifi Under Implement IDA / 66490 g, Stability and Social Cohesi Post Limited 385,000.00 0.00 2022-11-10 2023-03-31 2022-11-24 2022-12-15 2022-12-24 2023-11-19 rigations and the design and cation Selection ation on supervision of infrastructure f acilities under the livelhood i nfrastructure Components. NG-ADAMAWA MCRP-32141 6-CS-CQS / Consultancy Servi Strengthening Peace Buildin Consultant Qualifi Under Implement ce to assess and upgrade Ad IDA / 66490 g, Stability and Social Cohesi Post Limited 110,000.00 0.00 2022-10-24 2022-10-25 2022-11-07 2022-11-28 2022-12-05 2023-03-05 cation Selection ation amawa State Cooperatives A on dministration System. NG-ADAMAWA MCRP-29715 Infrastructure Rehabilitation 6-CS-CQS / Consultancy for s Consultant Qualifi IDA / 66490 and Service Delivery Restora Post Limited 409,875.00 0.00 Canceled 2022-06-24 2022-07-08 2022-07-29 2022-08-08 2024-01-30 urvey, design and supervisio cation Selection tion & Improvement n of WASH Projects. NG-ADAMAWA MCRP-16939 2-CS-CQS / Design and Deplo Strengthening Peace Buildin yment of Platform/Software f Consultant Qualifi IDA / 59880 g, Stability and Social Cohesi Post Limited 50,000.00 0.00 Canceled 2020-08-12 2020-08-26 2020-09-25 2020-10-30 2021-04-28 or Monitoring performance of cation Selection on Beneficiaries of Agric. Livelih ood Kits/Small Animals by Ex tension Workers NG-ADAMAWA MCRP-34253 Infrastructure Rehabilitation 9-CS-CQS / Consultancy for s Consultant Qualifi Under Implement IDA / 66490 and Service Delivery Restora Post Limited 266,418.75 0.00 2023-02-24 2023-04-26 2023-03-10 2023-03-31 2023-04-08 2024-04-07 urvey, design and supervisio cation Selection ation tion & Improvement n of small towns/urban water supply system NG-ADAMAWA MCRP-34253 Infrastructure Rehabilitation 3-CS-CQS / Consultancy for s Consultant Qualifi Pending Impleme IDA / 66490 and Service Delivery Restora Post Limited 143,456.25 0.00 2023-02-27 2023-03-13 2023-04-03 2023-04-10 2023-10-07 upervision of boreholes (sola cation Selection ntation tion & Improvement r and Handpumps) in Adama wa State NG-ADAMAWA MCRP-35279 8-CS-CQS / Training on Buildi Strengthening Peace Buildin Consultant Qualifi Pending Impleme ng Public Private Partnership IDA / 66490 g, Stability and Social Cohesi Post Limited 150,000.00 0.00 2023-04-03 2023-04-17 2023-05-08 2023-05-18 2023-06-17 cation Selection ntation s and formulation of enabling on policies to drive SME growth i n communities. NG-ADAMAWA MCRP-35334 2-CS-CQS / ENGAGEMENT OF Technical Assistance and Pro Consultant Qualifi Pending Impleme EXTERNAL AUDITOR TO AUDI IDA / 66490 Post Limited 30,000.00 0.00 2023-04-18 2023-05-02 2023-05-23 2023-05-31 2026-05-30 ject Management Support cation Selection ntation T WORLD BANK PROJECTS (M CRP) (FINANCIAL POSITION) NG-ADAMAWA MCRP-36557 Strengthening Peace Buildin 7-CS-CQS / Consultancy Servi Consultant Qualifi Pending Impleme IDA / 66490 g, Stability and Social Cohesi Post Limited 250,250.00 0.00 2023-06-13 2023-06-27 2023-07-18 2023-07-30 2024-04-25 ce for Survey, design and su cation Selection ntation on pervision of C1 Infrastructure Projects. INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NG-ADAMAWA MCRP-74496- Infrastructure Rehabilitation Individual Consult Pending Impleme CS-INDV / Hygiene Promotion IDA / 59880 and Service Delivery Restora Post Limited 9,180.33 0.00 2018-08-20 2018-08-25 2018-09-08 2018-10-02 2019-01-30 ant Selection ntation Sensitization/Mobilization. tion & Improvement NG-ADAMAWA MCRP-60989- CS-CQS / Verification/Validati Strengthening Peace Buildin on of Unified Registry and Be Under Implement IDA / 59880 g, Stability and Social Cohesi Post Direct Selection Direct 35,000.00 0.00 2018-12-10 2019-01-15 2018-12-13 2018-12-18 2019-01-17 neficiary Targeting for distrib ation on ution of interventions in Seve n Local Government Areas of Adamawa State. NG-ADAMAWA MCRP-10949 8-CS-CDS / Procurement of S Infrastructure Rehabilitation Under Implement afeguards Consultants to pro IDA / 59880 and Service Delivery Restora Post Direct Selection Direct 100,000.00 0.00 2019-04-08 2019-07-29 2019-04-16 2019-04-25 2019-05-16 ation duce ESMPs for Adamawa PC tion & Improvement U Infrastructure projects. NG-ADAMAWA MCRP-10950 6-CS-CDS / Procurement of E Infrastructure Rehabilitation nvironmental Safeguards Co IDA / 59880 and Service Delivery Restora Post Direct Selection Direct 50,000.00 0.00 Under Review 2019-04-08 2019-07-29 2019-04-16 2019-04-25 2019-05-16 nsultants to produce ESIAs fo tion & Improvement r Adamawa PCU Infrastructur e projects. NG-ADAMAWA MCRP-10950 Infrastructure Rehabilitation 7-CS-CDS / Procurement of S IDA / 59880 and Service Delivery Restora Post Direct Selection Direct 80,000.00 0.00 Under Review 2019-04-08 2019-07-22 2019-04-16 2019-04-25 2019-05-16 afeguards Consultants to pro tion & Improvement duce RAP for Adamawa PCU I nfrastructure projects. Page 11 NG-ADAMAWA MCRP-13045 5-CS-CDS / consultancy servi Strengthening Peace Buildin ces for beneficiary targeting IDA / 59880 g, Stability and Social Cohesi Post Direct Selection Direct 30,200.00 0.00 Under Review 2019-09-04 2018-10-09 2019-09-14 2019-10-02 2019-11-01 for livelihood support interve on ntions in the seven affected L ocal government Areas of Ad amawa State. NG-ADAMAWA MCRP-16944 0-CS-CDS / Training of Farme Strengthening Peace Buildin rs to apply inputs and access IDA / 59880 g, Stability and Social Cohesi Post Direct Selection Direct 100,000.00 0.00 Under Review 2020-07-22 2021-07-05 2020-08-01 2020-09-08 2021-01-06 targeted argricultural value c on hain and agribusiness skills NG-ADAMAWA MCRP-17755 Infrastructure Rehabilitation 4-CS-CDS / Consultancy for d Under Implement IDA / 59880 and Service Delivery Restora Post Direct Selection Direct 170,000.00 0.00 2020-07-14 2020-09-11 2020-07-24 2020-08-24 2021-07-26 esign and supervision of Roa ation tion & Improvement d and bridge projects NG-ADAMAWA MCRP-15662 Infrastructure Rehabilitation 4-CS-CDS / Consultancy for P Under Implement IDA / 59880 and Service Delivery Restora Post Direct Selection Direct 250,000.00 0.00 2020-07-02 2020-10-05 2020-07-12 2020-08-07 2020-10-06 reparation of Environmental ation tion & Improvement and Social Safeguard Instrum ents NG-ADAMAWA MCRP-17755 Strengthening Peace Buildin 0-CS-CDS / Beneficiary List V IDA / 59880 g, Stability and Social Cohesi Post Direct Selection Direct 20,000.00 0.00 Canceled 2020-06-25 2020-07-05 2020-08-21 2020-10-20 erification and Targeting on NG-ADAMAWA MCRP-17740 9-CS-CDS / Consultancy for P Infrastructure Rehabilitation roduction of Engineering dra IDA / 59880 and Service Delivery Restora Post Direct Selection Direct 150,000.00 0.00 Canceled 2020-07-09 2020-07-19 2020-08-24 2021-05-21 wings design and supervision tion & Improvement of Contracts for Primary & Se condary schools. NG-ADAMAWA MCRP-16943 Strengthening Peace Buildin 7-CS-CDS / Soft skills training IDA / 59880 g, Stability and Social Cohesi Post Direct Selection Direct 100,000.00 0.00 Canceled 2020-09-30 2020-10-10 2020-11-12 2021-03-12 /orientation on Quick to mark on et trading NG-ADAMAWA MCRP-17741 Strengthening Peace Buildin 6-CS-CDS / Softskills Training IDA / 59880 g, Stability and Social Cohesi Post Direct Selection Direct 150,000.00 0.00 Canceled 2020-06-22 2020-07-02 2020-08-09 2020-12-07 on Quick to Market Trades on NG-ADAMAWA MCRP-27780 2-CS-CDS / Design and imple mentation of Mediation and A Strengthening Peace Buildin lternate Dispute Resolution f IDA / 66490 g, Stability and Social Cohesi Post Direct Selection Direct 300,000.00 0.00 Under Review 2022-04-21 2023-05-22 2022-05-01 2022-05-27 2022-07-26 or Community Leaders, Justic on e Officials, Religious Leaders, Community Peace Groups (2 nd Phase) NG-ADAMAWA MCRP-27775 2-CS-CDS / Procurement of C Infrastructure Rehabilitation Under Implement onsultant for Development IDA / 66490 and Service Delivery Restora Post Direct Selection Direct 230,000.00 0.00 2022-03-22 2022-06-27 2022-04-01 2022-07-04 2022-04-16 2022-06-15 ation of Environmental and social tion & Improvement safeguards instruments NG-ADAMAWA MCRP-22356 Strengthening Peace Buildin 7-CS-CDS / Consultancy servi Under Implement IDA / 59880 g, Stability and Social Cohesi Post Direct Selection Direct 250,000.00 0.00 2020-12-02 2020-12-02 2020-12-12 2021-02-06 2021-04-27 ce for soft skill training and r ation on e-orientation on quick to mar ket trading (2020) NG-ADAMAWA MCRP-27814 Infrastructure Rehabilitation 1-CS-CDS / Assessment of th Pending Impleme IDA / 66490 and Service Delivery Restora Post Direct Selection Direct 125,000.00 0.00 2022-03-08 2022-03-18 2022-04-15 2022-06-14 e Adamawa State Hides/Skin/ ntation tion & Improvement Leather Value Chain NG-ADAMAWA MCRP-29715 9-CS-CDS / Procurement of C Infrastructure Rehabilitation onsultant for survey, IDA / 59880 and Service Delivery Restora Post Direct Selection Direct 260,000.00 0.00 Completed 2022-05-31 2022-10-06 2022-06-10 2022-08-09 2022-07-03 2023-08-07 Design and supervision of Ro tion & Improvement ads and Bridges. NG-ADAMAWA MCRP-17754 Infrastructure Rehabilitation 8-CS-CDS / Consultancy for IDA / 59880 and Service Delivery Restora Post Direct Selection Direct 50,000.00 0.00 Canceled 2020-07-20 2020-07-30 2020-09-07 2021-03-06 water projects Design and su tion & Improvement pervision (Solar and Hand Pu mp Boreholes) NG-ADAMAWA MCRP-35612 Infrastructure Rehabilitation 7-CS-CDS / Consultancy for p Pending Impleme IDA / 66490 and Service Delivery Restora Post Direct Selection Direct - National 150,000.00 0.00 2023-04-20 2023-04-30 2023-05-27 2023-07-26 reparation of Safeguards Inst ntation tion & Improvement ruments for Component 1 Inf rastructure activities NG-ADAMAWA MCRP-35614 Infrastructure Rehabilitation 3-CS-CDS / Consultancy for s Pending Impleme IDA / 66490 and Service Delivery Restora Post Direct Selection Direct - National 404,909.90 0.00 2023-04-25 2023-05-05 2023-06-01 2024-05-26 upervision of Roads and brid ntation tion & Improvement ge in Adamawa State (AF) Page 12 Summarized Procurement Plan I. GENERAL Project information: Borrower: Government of Lesotho Project Name: Lesotho Renewable Energy and Electricity Access Project Project ID No: P166936 Grant No.: Project Implementing Agency: Department of Energy Bank’s approval Date of the Procurement Plan: Nov 2019 Date of General Procurement Notice: Period covered by this procurement plan: 18 months II. Goods and Works and Non-Consulting Services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by IDA as stated in the Procurement Regulations for IPF Borrowers: Thresholds for Procurement Methods and Prior Review Goods, Works and Non- Consulting Services Procurement Approaches and Methods (US$ Prior millions) Review Category Open Open Request for (US$ millions) International National Quotation (RfQ) Works ≥ 10 ≥7 <7 ≤ 0.2 Goods, IT, and non- ≥2 ≥1 <1 ≤ 0.1 consulting services 2. Reference to (if any) Project Operational/Procurement Manual: The Procurement Plan also forms part of the Project Implementation Manual approved on Sep 2019. 1 3. Procurement Packages with Methods and Time Schedule Procurement of Goods & Non-consulting Services Summary 1 2 3 4 5 6 7 Ref. Description Estimated Packages Domestic Review Comments No. Cost Preference by Bank US$ million (yes/no) (Prior / Post) Summary of the ICB 8.4 2 NIL Post (Works) Summary of the NCB NIL NIL NIL Nil NIL (Works) Summary of the ICB NIL NIL NIL NIL NIL (Goods) Summary of the NCB NIL NIL NIL NIL NIL (Goods) Summary of the RfQ 0.56 7 NIL Post Nil (Goods & Non- Consulting Services) Summary of the DC 0.065 1 NIL Post (Non-consulting services) III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in the Procurement Regulations for IPF Borrowers: Thresholds for Consultants Selection Methods and Prior Review Thresholds for Consultants Selection Methods and Prior Review for Consulting Services Category Prior Short List of National Consultants (US$ million) 2 Review Consulting Engineering and (US$ Services Construction Supervision millions) Consultants (Firms) ≥1 ≤ 0.1 ≤ 0.3 Individual Consultants ≥ 0.3 NA. NA. 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $ 300,000 equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of the Procurement Regulations for IPF Borrowers. 3. Terms of Reference (TOR) for all consultancy contracts as well as all direction selections, irrespective of the contract value, will be subject to prior review. 4. Any Other Special Selection Arrangements: N/A 5. Consultancy Assignments with Selection Methods and Time Procurement of Consulting Services Summary 1 2 3 4 5 6 Ref. No. Description of Estimated Package Review Comments Assignment Cost s by Bank (Prior / US$ million Post) Summary of 0.55 1 Post contracts through QCBS Summary of 0.35 1 Post NIL contracts through CQS 3 Summary of 1.8 12 Post NIL contracts through IC 4 PROCUREMENT Lesotho : Lesotho Renewable Energy & Energy Access Project PLAN General Information Country: Lesotho 2020-08-24 Bank’s Approval Date of the Original Procurement Plan: 2023-06-04 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P166936 GPN Date: Project Name: Lesotho Renewable Energy & Energy Access Project Loan / Credit No: IDA / 65320, TF / B1683, TF / B1681 Department of Energy Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned LS-DOE-189528-CW-RFB / C onstruction of 60KM, 33 kV li Grid Extension to Peri-Urban Open - Internationa Single Stage - One E 2021-06-2 IDA / 65320 Post Request for Bids 3,498,950.31 0.00 Canceled 2020-09-01 2020-09-06 2020-10-18 2020-11-17 2020-12-22 ne transmission line from Hlo Areas of Lesotho l nvelope 0 tse to Ha Belo and 2x 10MVA Sub station LS-DOE-189529-CW-RFB / R ehabilitation of Semonkong Rural Electrification by Mini- Open - Internationa Single Stage - One E 2021-07-0 TF / B1683 Post Request for Bids 4,950,000.00 0.00 Canceled 2020-09-20 2020-09-25 2020-11-06 2020-12-06 2021-01-10 mini-grid and construction of grids l nvelope 9 1.5 MW Solar PV Plant at Se monkong LS-DOE-303706-CW-RFQ / El Request for Quota ectrification of Khutlo-Peli He Contingent Emergency Resp Request for Quota Single Stage - One E 2023-03-1 IDA / 65320 Post Limited tions (Non Bank-S 200,000.00 0.00 Signed 2022-07-17 2023-01-10 2022-09-11 alth centre and upgrading of onse Component tions nvelope 0 PD) the installed solar systems in health centres. LS-DOE-303741-CW-RFQ / E Request for Quota Contingent Emergency Resp Request for Quota Single Stage - One E 2023-03-3 nergising Education: Solar el IDA / 65320 Post Limited tions (Non Bank-S 30,000.00 0.00 Signed 2022-08-06 2023-04-11 2022-10-01 onse Component tions nvelope 0 ectrification of Maqoala Prim PD) ary Request for Quota LS-DOE-303743-CW-RFQ / E Contingent Emergency Resp Request for Quota Single Stage - One E Under Imple 2023-03-3 IDA / 65320 Post Limited tions (Non Bank-S 70,000.00 0.00 2022-08-07 2023-04-17 2022-10-02 nergising Education: Matelile onse Component tions nvelope mentation 1 PD) Primary LS-DOE-299846-CW-RFQ / In stalling of solar home styste National Procure ms at Maluba-lube Health Ce ment Document - ntre Mokhotlong, A plug and Contingent Emergency Resp Request for Quota Single Stage - One E 2023-05-1 IDA / 65320 Post Limited 1 Envelope proce 95,000.00 0.00 Signed 2022-09-25 2022-07-01 2022-11-20 Play system to be installed to onse Component tions nvelope 9 ss (Non Bank-SPD meet the electricity demand ) for the clinic and nurse hous es in the Health centre, distri bution of electricity LS-DOE-303730-CW-RFQ / Le rotholi Polytechnic Solar stre National Procure et light with WIFI in institutio ment Document - ns of higher learning. Solar st Contingent Emergency Resp Single Stage - One E Pending Imp 2024-03-1 IDA / 65320 Post Request for Bids Open - National 1 Envelope proce 300,000.00 0.00 2023-06-01 2023-06-06 2023-07-18 2023-08-17 2023-09-21 reet lights equipped with free onse Component nvelope lementation 9 ss (Non Bank-SPD Wi-Fi for affected citizen, for ) road safety, for tertiary educ ation hubs. Installation and mounting of solar street light s LS-DOE-303714-CW-RFQ / U pgrading and refurbishment Request for Quota of the installed solar systems Contingent Emergency Resp Request for Quota Single Stage - One E Pending Imp 2024-02-2 IDA / 65320 Post Limited tions (Non Bank-S 90,000.00 0.00 2023-06-30 2023-08-25 in health centres St. Rodrigu onse Component tions nvelope lementation 1 PD) e to meet the electricity dem and of the health centre and nurses houses. LS-DOE-299845-CW-RFQ / E nergising Education National National Procure University of Lesotho, Solar s ment Document - treet light with WIFI in institu Contingent Emergency Resp Single Stage - One E Pending Imp 2024-04-1 IDA / 65320 Post Request for Bids Open - National 1 Envelope proce 350,000.00 0.00 2023-06-27 2023-07-02 2023-08-13 2023-09-12 2023-10-17 tions of higher learning. Solar onse Component nvelope lementation 4 ss (Non Bank-SPD street lights equipped with fr ) ee Wi-Fi for affected citizen, f or road safety, for tertiary ed ucation hubs: LS-DOE-303702-CW-RFQ / in stallation of solar home syste ms for a plug and play syste Request for Quota Contingent Emergency Resp Request for Quota Single Stage - One E Under Imple 2024-01-1 m at Ha Lenkoane Health Ce IDA / 65320 Post Limited tions (Non Bank-S 75,000.00 0.00 2023-05-24 2023-07-19 onse Component tions nvelope mentation 5 ntres. Provision of energy effi PD) cient lighting and appliances to the health centre and nurs e house LS-DOE-303716-CW-RFQ / El Request for Quota Contingent Emergency Resp Request for Quota Single Stage - One E 2023-03-1 ectrification and upgrading o IDA / 65320 Post Limited tions (Non Bank-S 75,000.00 0.00 Canceled 2022-07-17 2022-09-11 onse Component tions nvelope 0 f health centres Sehong-hon PD) g LS-DOE-303720-CW-RFQ / El Request for Quota Contingent Emergency Resp Request for Quota Single Stage - One E 2023-03-1 ectrification of St.Peter Clava IDA / 65320 Post Limited tions (Non Bank-S 120,000.00 0.00 Canceled 2022-07-17 2022-09-11 onse Component tions nvelope 0 Health Centre PD) Request for Quota LS-DOE-303722-CW-RFQ / El Contingent Emergency Resp Request for Quota Single Stage - One E 2023-03-1 IDA / 65320 Post Limited tions (Non Bank-S 130,000.00 0.00 Canceled 2022-07-24 2022-09-18 ectrification of Ha Mafa Healt onse Component tions nvelope 7 PD) h Centre LS-DOE-303736-CW-RFQ / E nergising Education NUL-IEM National Procure S Solar street light with WIFI i ment Document - Contingent Emergency Resp Single Stage - One E Pending Imp 2024-03-1 n institutions of higher learni IDA / 65320 Post Request for Bids Limited 1 Envelope proce 300,000.00 0.00 2023-06-01 2023-06-06 2023-07-18 2023-08-17 2023-09-21 onse Component nvelope lementation 9 ng. Solar street lights equipp ss (Non Bank-SPD ed with free Wi-Fi for affecte ) d citizen, for road safety, for tertiary education hubs LS-DOE-363028-CW-RFP / D Request for Propo esign, Build and Operation Rural Electrification by Mini- Request for Propo Open - Internationa sal Design and Bu Under Imple 2025-10-1 TF / B1683 Prior 5,000,000.00 0.00 2023-05-23 2023-08-08 2023-08-08 2023-05-28 2023-10-17 2024-03-20 2024-04-24 of Solar PV Mini-grids under L grids sals l ild - Works SPD (T mentation 6 REEAP wo-stage) Request for Bids - LS-DOE-364259-CW-RFB / U Contingent Emergency Resp Single Stage - Two E Small Works SPD Pending Imp 2024-05-1 pgrading and installation of s IDA / 65320 Post Request for Bids Open - National 350,000.00 0.00 2023-06-15 2023-06-20 2023-08-01 2023-10-14 2023-11-18 onse Component nvelope (1 envelope proce lementation 6 olar home systems at school ss) s, Page 1 LS-DOE-364258-CW-RFB / En ergising Education Lesotho, S National Procure olar street light with WIFI in i ment Document - Contingent Emergency Resp Single Stage - Two E Pending Imp 2024-05-1 nstitutions of higher learning. IDA / 65320 Post Request for Bids Open - National 1 Envelope proce 300,000.00 0.00 2023-06-15 2023-06-20 2023-08-01 2023-10-14 2023-11-18 onse Component nvelope lementation 6 Solar street lights equipped ss (Non Bank-SPD with free Wi-Fi for affected ci ) tizen, for road safety, for terti ary education hubs LS-DOE-364260-CW-RFB / En ergising Education: Limkokwi Request for Bids - ng University , Solar street li Contingent Emergency Resp Single Stage - Two E Small Works SPD Under Imple 2024-05-1 ght with WIFI in institutions o IDA / 65320 Post Request for Bids Open - National 350,000.00 0.00 2023-06-14 2023-05-30 2023-06-19 2023-07-31 2023-10-13 2023-11-17 onse Component nvelope (2 envelope proce mentation 5 f higher learning. Solar street ss) lights equipped with free Wi- Fi for affected citizen, for roa d safety, for tertiary educatio n hubs LS-DOE-303713-CW-RFQ / El Request for Quota ectrification of Bethel health Contingent Emergency Resp Request for Quota Single Stage - One E Pending Imp 2023-03-1 IDA / 65320 Post Limited tions (Non Bank-S 100,000.00 0.00 2022-07-17 2022-09-11 centers with grid extension b onse Component tions nvelope lementation 0 PD) y Lesotho Electricity Compan y (LEC) LS-DOE-366184-CW-RFQ / In Request for Quota stallation of Home solar syste Contingent Emergency Resp Request for Quota Single Stage - One E tions - Small Work Under Imple 2024-02-0 IDA / 65320 Post Limited 20,000.00 0.00 2023-06-13 2023-08-08 m to Nkokamele-Lifofaneng onse Component tions nvelope s (Emergency) SP mentation 4 Health posts at Mokhotlong D -Competitive LS-DOE-366186-CW-RFQ / In Request for Quota stallation of Solar Home syst Contingent Emergency Resp Request for Quota Single Stage - One E tions - Small Work Under Imple 2024-02-0 IDA / 65320 Post Limited 25,000.00 0.00 2023-06-13 2023-08-08 em to Tloha re bue- Meno He onse Component tions nvelope s (Emergency) SP mentation 4 alth post at Mokhotlong D -Competitive Request for Quota LS-DOE-366187-CW-RFQ / In Contingent Emergency Resp Request for Quota Single Stage - One E tions - Small Work Under Imple 2024-02-0 stallation of home solar syste IDA / 65320 Post Limited 10,000.00 0.00 2023-06-13 2023-08-08 onse Component tions nvelope s (Emergency) SP mentation 4 m to Liqobong Health post at D -Competitive Mokhotlong Request for Quota LS-DOE-366188-CW-RFQ / El Contingent Emergency Resp Request for Quota Single Stage - One E tions - Small Work Pending Imp 2024-02-0 ectricity installation to Chaba IDA / 65320 Post Limited 8,000.00 0.00 2023-06-13 2023-08-08 onse Component tions nvelope s (Emergency) SP lementation 4 -Pokane at Botha-Bothe Healt D -Competitive h posts LS-DOE-366189-CW-RFQ / In Request for Quota stallation of solar home syste Contingent Emergency Resp Request for Quota Single Stage - One E tions - Small Work Under Imple 2024-02-0 IDA / 65320 Post Limited 16,000.00 0.00 2023-06-13 2023-08-08 m to Ramalieletse- Helena H onse Component tions nvelope s (Emergency) SP mentation 4 ealth posts at Botha-Bothe D -Competitive LS-DOE-366192-CW-RFQ / In Request for Quota stallation of solar home syste Contingent Emergency Resp Request for Quota Single Stage - One E tions - Small Work Under Imple 2024-02-0 IDA / 65320 Post Limited 16,000.00 0.00 2023-06-13 2023-08-08 m to Lepatoa -Khatibe Healt onse Component tions nvelope s (Emergency) SP mentation 4 h posts at Botha-Bothe D -Competitive Request for Quota LS-DOE-366193-CW-RFQ / In Contingent Emergency Resp Request for Quota Single Stage - One E tions - Small Work Under Imple 2024-02-0 stallation of solar home syste IDA / 65320 Post Limited 9,000.00 0.00 2023-06-13 2023-08-08 onse Component tions nvelope s (Emergency) SP mentation 4 m at Ha Sello Health Post at D -Competitive Botha-Bothe LS-DOE-366194-CW-RFQ / In Request for Quota stallation of solar home syste Contingent Emergency Resp Request for Quota Single Stage - One E tions - Small Work Under Imple 2024-02-0 IDA / 65320 Post Limited 15,000.00 0.00 2023-06-13 2023-08-08 m to Leboea-Pataka Health P onse Component tions nvelope s (Emergency) SP mentation 4 osts at Botha-Botha D -Competitive Request for Bids - LS-DOE-366195-CW-RFB / D Works (after preq esign and installation of solar Contingent Emergency Resp Single Stage - Two E Pending Imp 2024-05-1 IDA / 65320 Post Request for Bids Open - National ualification) SPD - 850,000.00 0.00 2023-06-16 2023-06-21 2023-08-02 2023-10-15 2023-11-19 power System at Mokhotlong onse Component nvelope lementation 7 Applying contract Hospital or disqualificiatio n GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual LS-DOE-189480-GO-RFQ / Pr ocurement of Office Equipme Technical Assistance and Im Request for Quota Single Stage - One E TF / B1683 Post Open - National 16,546.17 0.00 Canceled 2020-08-25 2020-10-20 2021-04-18 nt for DOE Project Implement plementation Support tions nvelope ation Unit for Start-up LS-DOE-189518-GO-RFQ / Pr Technical Assistance and Im Request for Quota Single Stage - One E ocurement of Office Furniture TF / B1683 Post Open - National 20,000.00 0.00 Canceled 2020-09-25 2020-08-31 2020-11-20 2021-05-19 plementation Support tions nvelope for Project Implementation U nit LS-DOE-189520-GO-RFQ / Pr Technical Assistance and Im Request for Quota Single Stage - One E ocurement of IT Equipment f TF / B1683 Post Open - National 25,000.00 0.00 Canceled 2020-09-05 2020-08-31 2020-10-31 2021-04-29 plementation Support tions nvelope or Project Implementation Un it LS-DOE-189521-GO-RFQ / Pr Technical Assistance and Im Request for Quota Single Stage - One E ocurement of Mobile filing ca TF / B1683 Post Open - National 8,995.80 0.00 Canceled 2020-09-05 2020-10-31 2021-04-29 plementation Support tions nvelope binets for Project Implement ation Unit LS-DOE-189517-GO-RFQ / Pr Technical Assistance and Im Request for Quota Single Stage - One E ocurement of Vehicles for Pro TF / B1681 Post Open - National 291,882.43 137,643.40 Signed 2020-08-25 2020-10-20 2020-10-31 2021-04-18 plementation Support tions nvelope ject Implementation Unit LS-DOE-192449-GO-RFQ / Pr Technical Assistance and Im Request for Quota Single Stage - One E TF / B1681 Post Open - National 18,000.00 19,254.46 Signed 2020-09-13 2020-10-01 2020-11-08 2020-10-16 2021-05-07 ocurement of Office Equipme plementation Support tions nvelope nt for PIU LS-DOE-192451-GO-RFQ / Pr Technical Assistance and Im Request for Quota Single Stage - One E TF / B1681 Post Open - National 291,882.00 46,886.45 Signed 2020-09-19 2020-10-12 2020-11-14 2022-02-04 2021-05-13 ocurement of vehicles for PIU plementation Support tions nvelope LS-DOE-192453-GO-RFQ / Pr Technical Assistance and Im Request for Quota Single Stage - One E TF / B1681 Post Open - National 20,000.00 5,077.51 Signed 2020-09-13 2020-11-08 2022-08-02 2021-05-07 ocurement of Office Furniture plementation Support tions nvelope LS-DOE-192456-GO-RFQ / Pr Technical Assistance and Im Request for Quota Single Stage - One E TF / B1681 Post Open - National 25,000.00 9,913.07 Signed 2020-09-19 2020-10-12 2020-11-14 2020-11-03 2021-05-13 ocurement of IT Equipment f plementation Support tions nvelope or PIU LS-DOE-192459-GO-RFQ / Pr Technical Assistance and Im Request for Quota Single Stage - One E TF / B1681 Post Open - National 8,995.00 0.00 Canceled 2020-09-23 2020-11-18 2021-05-17 ocurement of Mobile filling ca plementation Support tions nvelope binets Page 2 LS-DOE-299851-GO-RFQ / U pgrading of Renewable energ y technologies at Taung Sola r Demonstration Site (Vocatio Contingent Emergency Resp Single Stage - One E Pending Impl nal School): Solar Home Syst IDA / 65320 Post Request for Bids Limited 190,000.00 0.00 2023-06-07 2023-06-12 2023-07-24 2023-08-23 2023-09-27 2024-03-25 onse Component nvelope ementation ems for the tertiary school • Poultry production for inc ome generation o Energy efficient stoves o Solar home systems NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual LS-DOE-189523-NC-RFQ / Fi Grid Extension to Peri-Urban Request for Quota Single Stage - One E bre Connectivity from LEC H IDA / 65320 Post Limited 14,000.00 0.00 Canceled 2020-09-06 2020-11-01 2021-04-30 Areas of Lesotho tions nvelope Qs to LEC Projects Office LS-DOE-189524-NC-DIR / Pro Technical Assistance and Im curement and Installation of TF / B1683 Post Direct Selection Direct 65,000.00 0.00 Canceled 2020-11-02 2020-11-07 2020-12-12 2021-06-10 plementation Support Accounting Management Soft ware LS-DOE-189527-NC-RFQ / Pr Technical Assistance and Im Request for Quota Single Stage - One E TF / B1683 Post Open - National 75,000.00 0.00 Canceled 2020-08-24 2020-08-31 2020-10-19 2021-04-17 ocurement of Office Space fo plementation Support tions nvelope r PIU LS-DOE-192461-NC-RFQ / Pr Technical Assistance and Im Request for Quota Single Stage - One E TF / B1681 Post Open - National 50,000.00 42,773.00 Signed 2020-09-13 2020-10-12 2020-11-08 2021-05-18 2021-05-07 ocurement/leasing of Office S plementation Support tions nvelope pace LS-DOE-192463-NC-DIR / Pro Technical Assistance and Im curement and Installation of TF / B1681 Post Direct Selection Direct 65,000.00 0.00 Signed 2021-02-01 2022-07-15 2021-02-06 2022-05-23 2021-03-13 2021-09-09 plementation Support Accounting Management Soft ware LS-DOE-299875-NC-RFQ / Op Contingent Emergency Resp Request for Quota Single Stage - One E Pending Impl IDA / 65320 Post Limited 80,000.00 0.00 2023-08-02 2023-09-27 2024-03-25 erating costs and UN Urgenc onse Component tions nvelope ementation y fees CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual LS-DOE-189545-CS-CQS / Co Rural Electrification by Mini- Consultant Qualifi Open - Internationa nsultancy Services for design TF / B1683 Post 350,000.00 0.00 Canceled 2020-11-02 2020-11-23 2021-01-06 2021-02-05 2021-03-12 2021-09-08 grids cation Selection l ing subsidy Programme for m ini-grids LS-DOE-192503-CS-CQS / Co nsultancy Services for Feasib Rural Electrification by Mini- Consultant Qualifi Open - Internationa TF / B1683 Post 500,000.00 0.00 Canceled 2020-10-30 2021-02-09 2020-11-20 2021-02-15 2021-01-03 2021-02-02 2021-03-09 2021-09-05 ility Studies, needs assessme grids cation Selection l nt and system sizing for mini -grids LS-DOE-192504-CS-CQS / Co Rural Electrification by Mini- Consultant Qualifi Open - Internationa Pending Impleme nsultancy services for designi TF / B1683 Post 350,000.00 0.00 2021-01-19 2021-02-09 2021-03-25 2021-04-24 2021-05-29 2021-11-25 grids cation Selection l ntation ng subsidy programme for Mi ni-grids LS-DOE-219655-CS-QCBS / C onsultancy Services for Feasi Rural Electrification by Mini- Quality And Cost- Open - Internationa IDA / 65320 Post 500,000.00 245,714.00 Signed 2021-02-15 2021-02-15 2021-03-08 2021-02-17 2021-04-21 2021-06-01 2021-05-19 2021-07-27 2021-06-18 2021-08-04 2021-07-23 2021-08-25 2021-08-27 2022-02-14 2022-08-27 bility studies, needs assessm grids Based Selection l ent and system sizing for min i-grids LS-DOE-339719-CS-QCBS / T ransaction Advisory Firm ser Technical Assistance and Im Quality And Cost- Open - Internationa TF / B1681 Post 250,000.00 0.00 Canceled 2023-02-01 2023-02-22 2023-04-07 2023-05-05 2023-06-04 2023-07-09 2023-08-13 2024-08-12 vices including Development plementation Support Based Selection l of Subsidy policy and fiscal in centive packages. LS-DOE-340210-CS-CQS / Tr ansaction Advisory Firm servi Technical Assistance and Im Consultant Qualifi Open - Internationa Under Implement TF / B1681 Post 290,000.00 0.00 2023-02-06 2023-03-20 2023-02-27 2023-04-17 2023-04-12 2023-05-12 2023-06-16 2023-12-13 ces including Development o plementation Support cation Selection l ation f Subsidy policy and fiscal inc entive packages. LS-DOE-354006-CS-CQS / Co nsultancy Services for the de Technical Assistance and Im Consultant Qualifi Open - Internationa Under Implement TF / B1681 Post 200,000.00 0.00 2023-03-30 2023-06-24 2023-04-20 2023-06-03 2023-07-03 2023-08-07 2024-02-03 velopment of Least Cost Elec plementation Support cation Selection l ation tricity Plan for Lesotho LS-DOE-299865-CS-QBS / Co nduct a countrywide baselin e survey for household energ Contingent Emergency Resp Quality Based Sel Under Implement y consumption trend and nee IDA / 65320 Post Open - National 300,000.00 0.00 2023-07-02 2023-07-23 2023-09-05 2023-10-03 2023-11-02 2023-12-02 2024-01-06 2025-01-05 onse Component ection ation ds; solar home systems. Acceleration of electrification solutions for rural communiti es LS-DOE-299844-CS-QBS / As Contingent Emergency Resp Quality And Cost- sessment of flood impact on IDA / 65320 Post Open - National 150,000.00 0.00 Canceled 2022-09-18 2022-10-09 2022-11-22 2022-12-20 2023-01-19 2023-02-23 2023-03-30 2024-03-29 onse Component Based Selection the energy sector and livelih oods LS-DOE-303727-CS-CDS / He alth Centre needs assessmen t study to inform Energy poli Contingent Emergency Resp Quality And Cost- IDA / 65320 Post Open - National 150,000.00 0.00 Canceled 2022-09-18 2022-10-09 2022-11-22 2022-12-20 2023-01-19 2023-02-23 2023-03-30 2024-03-29 cies and programmes in the onse Component Based Selection Health sector. Consultancy to identify respective energy ne eds in remote health centres LS-DOE-356229-CS-CQS / Pr eparation of Environmental a nd Social Management Plan a Rural Electrification by Mini- Consultant Qualifi Under Implement IDA / 65320 Post Open - National 300,000.00 0.00 2023-06-07 2023-06-03 2023-06-28 2023-08-11 2023-09-10 2023-10-15 2024-04-12 nd Abbreviated Resettlement grids cation Selection ation Action Plan for development of 10 Solar Mini grids in GoL INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 3 LS-DOE-189531-CS-INDV / R Technical Assistance and Im Individual Consult TF / B1683 Post Open 125,000.00 0.00 Canceled 2020-08-19 2020-08-31 2020-10-07 2020-10-28 2020-12-02 2021-05-31 ecruitment of Social Specialis plementation Support ant Selection t DOE LS-DOE-189534-CS-INDV / R Technical Assistance and Im Individual Consult ecruitment of Environmental TF / B1683 Post Open 125,000.00 0.00 Canceled 2020-08-20 2020-08-31 2020-10-08 2020-10-29 2020-12-03 2021-06-01 plementation Support ant Selection Specialist DOE LS-DOE-189536-CS-INDV / R Technical Assistance and Im Individual Consult ecruitment of Procurement S TF / B1683 Post Open 120,000.00 0.00 Canceled 2020-08-20 2020-08-31 2020-10-08 2020-08-20 2020-10-29 2020-12-03 2021-06-01 plementation Support ant Selection pecialist DOE LS-DOE-189538-CS-INDV / R Technical Assistance and Im Individual Consult TF / B1683 Post Open 140,000.00 0.00 Canceled 2020-10-06 2020-11-24 2020-12-15 2021-01-19 2021-07-18 ecruitment of Mini-grids Man plementation Support ant Selection ager DOE LS-DOE-189539-CS-INDV / R Technical Assistance and Im Individual Consult TF / B1683 Post Open 135,000.00 0.00 Canceled 2020-10-05 2020-11-23 2020-12-14 2021-01-18 2021-07-17 ecruitment of Mini-grids Engi plementation Support ant Selection neer DOE LS-DOE-189541-CS-INDV / R Technical Assistance and Im Individual Consult TF / B1683 Post Open 110,000.00 0.00 Canceled 2020-10-05 2020-11-23 2020-12-14 2021-01-18 2021-07-17 ecruitment of CPLO DOE plementation Support ant Selection LS-DOE-189543-CS-INDV / R Technical Assistance and Im Individual Consult TF / B1683 Post Open 130,000.00 0.00 Canceled 2020-10-05 2020-11-23 2020-12-14 2021-01-18 2021-07-17 ecruitment of M&E Specialist plementation Support ant Selection CPU LS-DOE-189547-CS-INDV / R Grid Extension to Peri-Urban Individual Consult ecruitment of PIU Staff: Envir IDA / 65320 Post Open 190,950.00 0.00 Canceled 2020-08-20 2020-10-08 2020-10-29 2020-12-03 2021-06-01 Areas of Lesotho ant Selection onmental Specialist – LEC LS-DOE-189548-CS-INDV / R Grid Extension to Peri-Urban Individual Consult ecruitment of PIU Staff: Socia IDA / 65320 Post Open 190,950.00 0.00 Canceled 2020-08-20 2020-10-08 2020-10-29 2020-12-03 2021-06-01 Areas of Lesotho ant Selection l Specialist – LEC LS-DOE-189516-CS-INDV / R ecruitment of Project Coordin Technical Assistance and Im Individual Consult TF / B1683 Post Open 200,000.00 4,664.37 Signed 2020-09-01 2020-04-30 2020-10-20 2020-03-27 2020-11-10 2020-05-19 2020-12-15 2020-05-20 2021-06-13 ator for 3 years contract com plementation Support ant Selection mencing 1st June 2020 LS-DOE-190353-CS-INDV / R Technical Assistance and Im Individual Consult ecruitment of Transaction Ad TF / B1683 Post Open 250,000.00 0.00 Canceled 2020-10-01 2020-11-19 2020-12-10 2021-01-14 2021-07-13 plementation Support ant Selection visor for the Project LS-DOE-189544-CS-INDV / R Technical Assistance and Im Individual Consult ecruitment of Gender Awaren TF / B1683 Post Open 120,000.00 0.00 Canceled 2020-10-05 2020-11-23 2020-12-14 2021-01-18 2021-07-17 plementation Support ant Selection ess Specialist for Project coor dination unit LS-DOE-189537-CS-INDV / R Technical Assistance and Im Individual Consult TF / B1683 Post Open 120,000.00 0.00 Canceled 2020-08-20 2020-08-31 2020-10-08 2020-10-29 2020-12-03 2021-06-01 ecruitment of Finance Specia plementation Support ant Selection list DOE LS-DOE-192182-CS-INDV / R Technical Assistance and Im Individual Consult ecruitment of Finance Specia TF / B1681 Post Open 120,000.00 33,916.83 Signed 2020-09-08 2020-07-20 2020-10-27 2020-06-26 2020-11-17 2020-07-02 2020-12-22 2020-07-07 2021-06-20 plementation Support ant Selection list for DOE PIU LS-DOE-192447-CS-INDV / R Technical Assistance and Im Individual Consult ecruitment of Procurement S TF / B1681 Post Open 120,000.00 3,588.91 Signed 2020-09-08 2020-10-12 2020-10-27 2020-07-28 2020-11-17 2020-08-18 2020-12-22 2020-09-02 2021-06-20 plementation Support ant Selection pecialist for DOE PIU LS-DOE-192468-CS-INDV / R Technical Assistance and Im Individual Consult ecruitment of Environmental TF / B1681 Post Open 125,000.00 33,994.33 Terminated 2020-09-08 2020-10-12 2020-10-27 2020-07-13 2020-11-17 2020-07-17 2020-12-22 2020-07-27 2021-06-20 plementation Support ant Selection Specialist for DOE PIU LS-DOE-192471-CS-INDV / R Technical Assistance and Im Individual Consult ecruitment of Social Specialis TF / B1681 Post Open 125,000.00 33,868.97 Signed 2020-09-08 2020-10-12 2020-10-27 2020-07-28 2020-11-17 2020-07-31 2020-12-22 2020-07-29 2021-06-20 plementation Support ant Selection t for DOE PIU LS-DOE-192483-CS-INDV / R Technical Assistance and Im Individual Consult TF / B1681 Post Open 135,000.00 33,868.97 Signed 2020-11-02 2021-04-26 2020-12-21 2022-01-28 2021-01-11 2022-01-28 2021-02-15 2022-01-29 2021-08-14 ecruitment of Mini-grids Engi plementation Support ant Selection neer LS-DOE-192494-CS-INDV / R Technical Assistance and Im Individual Consult ecruitment of Monitoring and TF / B1681 Post Open 130,000.00 33,868.97 Signed 2020-10-20 2021-04-26 2020-12-08 2022-01-28 2020-12-29 2022-01-28 2021-02-02 2022-01-29 2021-08-01 plementation Support ant Selection Evaluation Specialist LS-DOE-192495-CS-INDV / R Technical Assistance and Im Individual Consult TF / B1681 Post Open 250,000.00 0.00 Canceled 2020-10-11 2022-12-20 2020-11-29 2020-12-20 2021-01-24 2021-07-23 ecruitment of Transaction Ad plementation Support ant Selection visor LS-DOE-192499-CS-INDV / R Technical Assistance and Im Individual Consult Pending Impleme ecruitment of Gender Awaren TF / B1681 Post Open 120,000.00 0.00 2020-11-01 2020-12-20 2021-01-10 2021-02-14 2021-08-13 plementation Support ant Selection ntation ess Specialist LS-DOE-192478-CS-INDV / R Technical Assistance and Im Individual Consult TF / B1681 Post Open 140,000.00 37,632.19 Signed 2021-03-15 2021-04-26 2021-05-03 2022-01-28 2021-05-24 2022-01-28 2021-06-28 2022-01-29 2021-12-25 ecruitment of Mini-grids Man plementation Support ant Selection ager LS-DOE-298729-CS-INDV / re Technical Assistance and Im Individual Consult TF / B1681 Post Open - National 125,000.00 0.00 Canceled 2022-09-05 2022-10-24 2022-11-14 2022-12-19 2023-06-17 cruitment of finance specialis plementation Support ant Selection t LS-DOE-192467-CS-INDV / R Technical Assistance and Im Individual Consult TF / B1681 Post Open 200,000.00 0.00 Canceled 2020-09-08 2020-05-26 2020-10-27 2020-11-17 2020-12-22 2021-06-20 ecruitment of Project Coordin plementation Support ant Selection ator LS-DOE-192490-CS-INDV / R Technical Assistance and Im Individual Consult TF / B1681 Post Open 110,000.00 0.00 Canceled 2020-10-20 2022-02-22 2020-12-08 2020-12-29 2021-02-02 2021-08-01 ecruitment of CPLO plementation Support ant Selection Page 4 PROCUREMENT PLAN (Textual Part) Project information: Sindh Water and Agriculture Transformation Project (SWAT) (P167596) Project Implementation agency(ies): (i) Sindh Agriculture Department; (ii) Sindh Irrigation and Drainage Authority and (ii) Sindh Planning & Development Department - Project Coordination and Management Unit Date of the Procurement Plan: October 2022 Period covered by this Procurement Plan: October 15, 2022 June 30 2024 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” November 2020 (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in public procurement rules such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions: 1) The eligibility of bidders shall be as defined under Section III of the Procurement Regulations. Accordingly, no bidder or potential bidder shall be declared ineligible for contracts financed by the Bank for reasons other than those provided in Section III of the Procurement Regulations. 2) For national open competitive procurement, only the model procurement documents acceptable to the World Bank, shall be used. 3) The request for bids/request for proposals document shall require that Bidders/Proposers submitting Bids/Proposals present a signed acceptance (in the form attached) at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights. 4) Procurement Documents include provisions, as agreed with the Bank, intended to adequately mitigate against environmental, social (including sexual exploitation and abuse and gender-based violence), health and safety (“ESHS”) risks and impacts 5) Access to procurement opportunities shall not be restricted to firms that have pre-registered and/or paid a registration fee. 6) No preference of any kind shall be given to national bidders in the bidding process. 7) Procurement methods that use two-envelope process and rated criteria shall be subject to Bank’s prior concurrence When other national procurement arrangements (other than national open competitive procurement) are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is not allowed Letter of Acceptance of the World Bank’s Anticorruption Guidelines and Sanctions Framework1 Date: Invitation of Bids/Proposals No.__________ To: ___________________________________________________________________________ We, along with our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not) consultants and personnel, acknowledge and agree to abide by the World Bank’s policy regarding Fraud and Corruption (corrupt, fraudulent, collusive, coercive, and obstructive practices), as set out and defined in the World Bank’s Anti-Corruption Guidelines2 in connection with the procurement and execution of the contract (in case of award), including any amendments thereto. We declare and warrant that we, along our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not), consultants and personnel, are not subject to, and are not controlled by any entity or individual that is subject to, a temporary suspension, early temporary suspension, or debarment imposed by a member of the World Bank Group, including, inter alia, a cross-debarment imposed by the World Bank Group as agreed with other international financial institutions (including multilateral development banks), or through the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement. Further, we are not ineligible under the laws or official regulations of [Insert name of Employer as per bidding document] or pursuant to a decision of the United Nations Security Council. We confirm our understanding of the consequences of not complying with the World Bank’s Anti-Corruption Guidelines, which may include the following: a. rejection of our Proposal/Bid for award of contract; 1[Drafting note: This document shall be signed by bidders/proposers/consultants and submitted as part of their bids/proposals. In addition, this document shall be signed by the winning bidder/consultant and incorporated as part of the contract.] 2Guidelines on Preventing and Combating Fraud and Corruption in Projects Financed by International Bank for Reconstruction and Development Loans and the International Development Agency Credits and Grants, dated October 15, 2006, and revised in January 2011 and July 2016, as they may be revised from time to time. b. in the case of award, termination of the contract, without prejudice to any other remedy for breach of contract; and c. sanctions, pursuant to the Bank’s Anti-Corruption Guidelines and in accordance with its prevailing sanctions policies and procedures as set forth in the Bank’s Sanctions Framework. This may include a public declaration of ineligibility, either indefinitely or for a stated period of time, (i) to be awarded or otherwise benefit from a Bank-financed contract, financially or in any other manner;3 (ii) to be a nominated4 sub-contractor, sub-consultant, consultant, manufacturer or supplier, or service provider of an otherwise eligible firm being awarded a Bank-financed contract; and (iii) to receive the proceeds of any loan made by the Bank or otherwise to participate further in the preparation or implementation of any Bank- financed project. We understand that we may be declared ineligible as set out above upon: a. completion of World Bank Group sanctions proceedings according to its prevailing sanctions procedures; b. cross-debarment as agreed with other international financial institutions (including multilateral development banks); c. the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement; or d. temporary suspension or early temporary suspension in connection with an ongoing World Bank Group sanctions proceeding. For avoidance of doubt, the foregoing effects of ineligibility do not extend to a sanctioned firm’s or individual’s execution of its ongoing Bank-financed contracts (or its ongoing sub-agreements under such contracts) that are not the subject of a material modification, as determined by the Bank. We shall permit, and shall cause our sub-contractors, sub-consultants, agents (whether declared or not), personnel, consultants, service providers or suppliers, to permit the Bank to inspect5 all accounts, records, and other documents relating to 3 For the avoidance of doubt, a sanctioned party’s ineligibility to be awarded a contract shall include, without limitation, (i) applying for pre-qualification or initial selection), expressing interest in a consultancy, and bidding, either directly or as a nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider, in respect of such contract, and (ii) entering into an addendum or amendment introducing a material modification to any existing contract. 4A nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider (different names are used depending on the bidding document) is one which has been: (i) included by the bidder in its pre-qualification or initial selection application or bid because it brings specific and critical experience and know-how that allow the bidder to meet the qualification requirements for the particular bid; or (ii) appointed by the Borrower. 5Inspections in this context are usually investigative (i.e., forensic) in nature: they involve fact- finding activities undertaken by the Bank or persons appointed by the Bank to address specific the procurement process and/or contract execution (in the case of award), and to have them audited by auditors appointed by the Bank. We agree to preserve all accounts, records, and other documents (whether in hard copy or electronic format) related to the procurement and execution of the contract. Name of the Bidder/Proposer/Consultant: Name of the person duly authorized to sign the Bid/Proposal on behalf of the Bidder/Proposer/ Consultant: Title of the person signing the Letter: matters related to investigations/audits, such as evaluating the veracity of an allegation of possible Fraud and Corruption, through the appropriate mechanisms. Such activity includes but is not limited to accessing and examining a firm's or individual's financial records and information, and making copies thereof as relevant; accessing and examining any other documents, data, and information (whether in hard copy or electronic format) deemed relevant for the investigation/audit, and making copies thereof as relevant; interviewing staff and other relevant individuals; performing physical inspections and site visits; and obtaining third-party verification of information. PROCUREMENT Pakistan : Sindh Water and Agriculture Transformation Project (SWAT) PLAN General Information Country: Pakistan 2023-05-23 Bank’s Approval Date of the Original Procurement Plan: 2023-06-05 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P167596 GPN Date: 2022-03-31 Project Name: Sindh Water and Agriculture Transformation Project (SWAT) Loan / Credit No: IDA / 72550, IDA / 72540 Agriculture Supplies and Prices Department Government of Sindh Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PK-SAD-361441-GO-RFQ-009 Component 3: Targeted Agri Request for Quota Single Stage - One E Pending Impl / Procurement of Office Suppl IDA / 72550 cultural Incentives and Inve Post Open - National 100,000.00 0.00 2023-05-27 2023-06-16 2023-07-16 tions nvelope ementation ies & IT Equipment. stments PK-SAD-361444-GO-RFQ-010 Component 3: Targeted Agri Request for Quota Single Stage - One E Pending Impl / Procurement of Office Furni IDA / 72550 cultural Incentives and Inve Post Open - National 100,000.00 0.00 2023-05-29 2023-06-24 2023-07-24 tions nvelope ementation ture & Fixture stments PK-SAD-363038-GO-RFQ-FER C-001 / Development of MIS Component 5: Agricultural Fl Request for Quota Single Stage - One E Pending Impl and associated Systems, app IDA / 72540 ood Emergency Rehabilitatio Post Open - National 50,000.00 0.00 2023-05-30 2023-07-02 2023-12-29 tions nvelope ementation lications, and solutions for Fl n ood Emergency Rehabilitatio n Component. PK-SAD-361645-GO-RFQ-012 Component 3: Targeted Agri / Procurement of Motorcycles Request for Quota Single Stage - One E Pending Impl IDA / 72550 cultural Incentives and Inve Post Open - National 145,000.00 0.00 2023-06-11 2023-07-01 2023-07-15 for all the Project Support Uni tions nvelope ementation stments ts (Extension, CRS, Agri Mark eting, ADU, etc.) PK-SAD-361445-GO-RFQ-011 / Procurement of Project Vehi Component 3: Targeted Agri Request for Quota Single Stage - One E Pending Impl cles for all the ADU - Project IDA / 72550 cultural Incentives and Inve Post Open - National 500,000.00 0.00 2023-06-10 2023-07-11 2023-08-10 tions nvelope ementation Support Units (Wings i.e. Ext stments ension, Research, CSA, CSR, Agri Marketing). NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PK-SAD-361436-CS-CQS-008 / Hiring of Services for Third- Component 6: Contingent E Request for Quota Single Stage - One E Pending Impl Party Validation through the I IDA / 72540 Post Open - National 20,000.00 0.00 2023-06-20 2023-08-15 2023-12-31 mergency Response tions nvelope ementation VR System against wheat se ed cash subsidy distribution. CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PK-SAD-307037-CS-QCBS-00 Component 3: Targeted Agri Quality And Cost- Open - Internationa Under Implement 1 / Hiring of Project Impleme IDA / 72550 cultural Incentives and Inve Post 1,600,000.00 0.00 2023-06-04 2023-06-02 2023-06-25 2023-06-27 2023-07-10 2023-08-07 2023-08-17 2023-09-04 2023-09-17 2028-01-23 Based Selection l ation ntation Support consultant fo stments r ADU SWAT. PK-SAD-367831-CS-CQS / Hir Component 3: Targeted Agri Consultant Qualifi Pending Impleme ing of Design and Supervisio IDA / 72550 cultural Incentives and Inve Post Open - National 300,000.00 0.00 2023-06-30 2023-07-21 2023-09-03 2023-09-08 2023-09-18 2024-03-16 cation Selection ntation n(Architect) Firm stments INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PK-SAD-361430-CS-INDV-00 Component 3: Targeted Agri Individual Consult Under Implement IDA / 72550 Prior Open - National 100,000.00 0.00 2023-06-07 2023-07-11 2023-08-01 2023-09-05 2028-01-10 3 / Hiring of Finance Manager cultural Incentives and Inve ant Selection ation - ADU stments PK-SAD-361177-CS-INDV-00 Component 3: Targeted Agri Individual Consult Under Implement 1 / Hiring of Program Implem IDA / 72550 cultural Incentives and Inve Post Direct - National 192,000.00 0.00 2023-06-04 2023-06-05 2023-06-14 2023-06-19 2023-06-28 2028-01-10 ant Selection ation entation Advisor - ADU stments PK-SAD-361433-CS-INDV-00 Component 3: Targeted Agri Individual Consult Under Implement 6 / Hiring of FFS & Value Chai IDA / 72550 cultural Incentives and Inve Post Open - National 100,000.00 0.00 2023-06-07 2023-06-05 2023-07-26 2023-08-16 2023-09-20 2028-01-10 ant Selection ation n Specialist stments PK-SAD-361434-CS-INDV-00 Component 3: Targeted Agri Individual Consult Under Implement IDA / 72550 Post Open - National 100,000.00 0.00 2023-06-07 2023-06-05 2023-07-26 2023-08-16 2023-09-20 2028-01-10 7 / Hiring of M&E Specialist cultural Incentives and Inve ant Selection ation stments PK-SAD-361431-CS-INDV-00 Component 3: Targeted Agri Individual Consult IDA / 72550 Prior Open - National 100,000.00 0.00 Under Review 2023-06-07 2023-07-26 2023-08-16 2023-09-20 2028-01-10 4 / Hiring of Procurement Spe cultural Incentives and Inve ant Selection cialist stments PK-SAD-361432-CS-INDV-00 Component 3: Targeted Agri Individual Consult Under Implement 5 / Hiring of Social & Gender IDA / 72550 cultural Incentives and Inve Post Open - National 100,000.00 0.00 2023-06-07 2023-06-05 2023-07-26 2023-08-16 2023-09-20 2028-01-10 ant Selection ation Specialist - ADU stments Page 1 PK-SAD-361179-CS-INDV-00 Component 3: Targeted Agri Individual Consult Under Implement 2 / Hiring of Environment Spe IDA / 72550 cultural Incentives and Inve Post Direct - National 100,000.00 0.00 2023-06-08 2023-06-05 2023-06-18 2023-07-09 2023-08-13 2028-01-10 ant Selection ation cialist - ADU stments Page 2 Proyecto de Gestión Integral de los Riesgos en el Sistema Agroindustrial Rural (GIRSAR) Monto – USD150 MILLONES PROCUREMENT Argentina : Integrated Risk Management in the Rural Agroindustrial System PLAN General Information Country: Argentina 2019-03-22 Bank’s Approval Date of the Original Procurement Plan: 2023-06-05 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P162316 GPN Date: Project Name: Integrated Risk Management in the Rural Agroindustrial System Loan / Credit No: IBRD / 88670 Rural Change Unit - Ministry of Agriculture Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned AR-UCAR-216690-CW-RFB / Subproyecto "Reacondiciona Component 2 - Agricultural r Single Stage - One E Under Imple 2022-02-1 IBRD / 88670 Post Request for Bids Open - National 340,028.00 0.00 2021-05-03 2023-01-23 2021-05-08 2021-06-19 2021-07-19 2021-08-23 miento y Mejora del Sistema isk mitigation investments nvelope mentation 9 de Riego de Buta Ranquil". N euquén AR-UCAR-186648-CW-RFB / Subproyecto "Acueducto Gan Component 2 - Agricultural r Single Stage - One E 7,662,149.7 2021-06-1 IBRD / 88670 Post Request for Bids Open - National 5,848,818.00 Signed 2020-08-24 2021-12-29 2020-09-01 2020-10-13 2022-02-24 2020-11-10 2022-04-29 2020-12-15 2022-06-04 adero La Providencia, La Ra isk mitigation investments nvelope 8 5 mada y Santa Ana" - Provinci a de Córdoba AR-UCAR-216712-CW-RFB / Subproyecto "Readecuación Component 2 - Agricultural r Single Stage - One E 2022-05-2 IBRD / 88670 Post Request for Bids Open - National 5,800,000.00 0.00 Signed 2021-08-02 2021-11-17 2021-08-07 2021-09-18 2021-12-17 2021-10-18 2022-04-21 2021-11-22 de Los sistemas de Riego sup isk mitigation investments nvelope 1 erficiales de San Blas de Los Sauces". La Rioja. AR-UCAR-216700-CW-RFB / Subproyecto "Fortalecimient National Procure o de la Cadena Productiva de ment Document - Component 2 - Agricultural r Single Stage - One E Pending Imp 2022-06-2 Pequeños Productores Hortíc IBRD / 88670 Post Request for Bids Open - National 1 Envelope proce 2,470,146.00 0.00 2021-09-06 2021-09-11 2021-10-23 2021-11-22 2021-12-27 isk mitigation investments nvelope lementation 5 olas y Florícolas"- Construcci ss (Non Bank-SPD ón de invernaderos y mejora ) de la comercialización. Provi ncia de Jujuy. AR-UCAR-186653-CW-RFB / Subproyecto "Rehabilitación National Procure de la dinámica hidráulica del ment Document - Component 2 - Agricultural r Single Stage - One E 6,762,382.4 2022-02-1 subsistema de la Cuenca del IBRD / 88670 Post Request for Bids Open - National 1 Envelope proce 9,726,000.00 Signed 2021-05-03 2021-06-23 2021-05-03 2021-06-14 2021-09-06 2021-07-12 2021-12-17 2021-08-16 2022-06-03 isk mitigation investments nvelope 0 4 Arroyo Baí" - Readecuación ss (Non Bank-SPD de los escurrimientos de la C ) uenca del Arroyo Baí - Provin cia de Corrientes AR-UCAR-216698-CW-RFB / National Procure Subproyecto "Desarrollo Gan ment Document - adero de la Provincia de Jujuy Component 2 - Agricultural r Single Stage - One E Pending Imp 2022-05-2 IBRD / 88670 Post Request for Bids Open - National 1 Envelope proce 2,700,000.00 0.00 2021-08-02 2021-08-07 2021-09-18 2021-10-18 2021-11-22 (Etapa I)". Mejoramiento en l isk mitigation investments nvelope lementation 1 ss (Non Bank-SPD os sistemas productivos y la ) generación de nueva estruct ura de faena . Provincia de Ju juy. AR-UCAR-216714-CW-RFB / Subproyecto "Rehabilitación National Procure de la dinámica hídrica de la c ment Document - Component 2 - Agricultural r Single Stage - One E Pending Imp 2022-05-2 uenca alta del Riachuelo: sub IBRD / 88670 Post Request for Bids Open - National 1 Envelope proce 3,100,000.00 0.00 2021-08-02 2021-08-07 2021-09-18 2021-10-18 2021-11-22 isk mitigation investments nvelope lementation 1 sistema de La Palmira" -Cons ss (Non Bank-SPD trucción de un sistema de ve ) rtedero de excedentes hídric os . Provincia de Corrientes. AR-UCAR-253366-CW-RFQ / Mitigación de los Impactos pr oducidos sobre los humedale Request for Quota Component 2 - Agricultural r Request for Quota Single Stage - One E Pending Imp 2022-05-2 s por la deficiencia del escurr IBRD / 88670 Post Open - National tions (Non Bank-S 16,475.00 0.00 2021-10-02 2021-11-27 isk mitigation investments tions nvelope lementation 6 imiento en canales existente PD) s sobre el Estero Las Maloyas – Zona Alcantarillas sobre RP N° 5 AR-UCAR-216686-CW-RFB / Subproyecto "Fortalecimient Component 2 - Agricultural r Single Stage - One E 2022-02-1 IBRD / 88670 Post Request for Bids Open - National 832,160.00 0.00 Canceled 2021-05-03 2021-05-08 2021-06-19 2021-07-19 2021-08-23 o Sanitario del rodeo bovino isk mitigation investments nvelope 9 provincial". Neuquén AR-UCAR-286857-CW-RFB / Licitación de obra de reacond National Procure icionamiento y mejora de sist ment Document - Component 2 - Agricultural r Single Stage - One E Pending Imp 2023-02-1 ema de riego en el marco del IBRD / 88670 Post Request for Bids Open - National 1 Envelope proce 114,270.00 0.00 2022-05-02 2022-05-07 2022-06-18 2022-07-18 2022-08-22 isk mitigation investments nvelope lementation 8 subproyecto "Reacondiciona ss (Non Bank-SPD miento y Mejora del Sistema ) de Riego de Buta Ranquil" de la provincia del Neuquén National Procure AR-UCAR-216721-CW-RFB / ment Document - Component 2 - Agricultural r Single Stage - One E 2022-06-2 Subproyecto "Mejora de la re IBRD / 88670 Post Request for Bids Open - National 1 Envelope proce 2,955,039.00 0.00 Signed 2021-09-06 2022-05-27 2021-09-11 2021-10-23 2022-08-11 2021-11-22 2022-10-24 2021-12-27 isk mitigation investments nvelope 5 d de riego del Valle de Jáchal ss (Non Bank-SPD ". San Juan. ) AR-UCAR-296239-CW-RFB / National Procure Obra civil en el marco del Su ment Document - bproyecto MODERNIZACIÓN Component 2 - Agricultural r Single Stage - One E 10,608,695.0 Under Imple 2023-03-0 IBRD / 88670 Prior Request for Bids Open - National 1 Envelope proce 0.00 2022-05-20 2023-06-01 2022-05-25 2022-07-06 2023-05-11 2022-08-05 2023-06-28 2022-09-09 DEL SISTEMA DE RIEGO RAM isk mitigation investments nvelope 0 mentation 8 ss (Non Bank-SPD A CHIMBA RÍO TUNUYÁN INFE ) RIOR - Provincia de Mendoza AR-UCAR-216723-CW-RFB / Subproyecto "Sistema Provin Component 2 - Agricultural r Single Stage - One E 2022-06-2 IBRD / 88670 Post Request for Bids Open - National 335,000.00 0.00 Canceled 2021-09-06 2021-09-11 2021-10-23 2021-11-22 2021-12-27 cial de Información Para La G isk mitigation investments nvelope 5 estión del Riesgo Agrario". N euquén. National Procure AR-UCAR-305998-CW-RFB / ment Document - Obra correspondiente al sub Component 2 - Agricultural r Single Stage - One E 2023-05-2 IBRD / 88670 Post Request for Bids Open - National 1 Envelope proce 5,287,315.00 0.00 Canceled 2022-08-01 2023-03-02 2022-08-06 2022-09-17 2023-03-30 2022-10-17 2023-04-24 2022-11-21 proyecto "Nueva Nave de Pro isk mitigation investments nvelope 0 ss (Non Bank-SPD ductores Mercado Concentra ) dor de Neuquén" AR-UCAR-311331-CW-RFB / National Procure Obra civil en el marco del Su ment Document - Component 2 - Agricultural r Single Stage - One E Pending Imp 2023-06-2 bproyecto "Modernización y IBRD / 88670 Post Request for Bids Open - National 1 Envelope proce 3,510,607.00 0.00 2022-09-05 2022-09-10 2022-10-22 2022-11-21 2022-12-26 isk mitigation investments nvelope lementation 4 mejoras en el sistema de rieg ss (Non Bank-SPD o del Valle de Viedma" - Prov ) incia de Río Negro Page 1 AR-UCAR-311370-CW-RFB / National Procure Obra en el marco del Subpro ment Document - yecto "Reacondicionamiento Component 2 - Agricultural r Single Stage - One E Pending Imp 2023-07-0 IBRD / 88670 Post Request for Bids Open - National 1 Envelope proce 2,859,000.00 0.00 2022-09-12 2022-09-17 2022-10-29 2022-11-28 2023-01-02 de los “prestamos” de la red isk mitigation investments nvelope lementation 1 ss (Non Bank-SPD vial provincial para el control ) de incendios forestales en la provincia de La Pampa" National Procure AR-UCAR-186659-CW-RFB / ment Document - Obras en el marco del Subpr Component 2 - Agricultural r Single Stage - One E Pending Imp 2023-07-0 IBRD / 88670 Post Request for Bids Open - National 1 Envelope proce 5,000,150.20 0.00 2022-09-09 2022-09-19 2022-10-31 2022-11-28 2023-01-02 oyecto "Prevención y control isk mitigation investments nvelope lementation 3 ss (Non Bank-SPD de incendios forestales de la ) Provincia de Mendoza" AR-UCAR-329253-CW-RFB / National Procure Obras en el marco del Subpr ment Document - oyecto "Sistema Integral de Component 2 - Agricultural r Single Stage - One E Pending Imp 2023-09-3 IBRD / 88670 Post Request for Bids Open - National 1 Envelope proce 4,219,000.00 0.00 2022-12-12 2022-12-17 2023-01-28 2023-02-27 2023-04-03 Mitigación, Prevención y Mon isk mitigation investments nvelope lementation 0 ss (Non Bank-SPD itoreo de incendios en las sie ) rras" de la provincia de Córd oba AR-UCAR-334580-CW-RFB / Licitación de obra de reacond National Procure icionamiento y mejora de sist ment Document - Component 2 - Agricultural r Single Stage - One E Pending Imp 2023-10-2 ema de riego en el marco del IBRD / 88670 Post Request for Bids Open - National 1 Envelope proce 281,100.00 0.00 2023-01-06 2023-01-11 2023-02-22 2023-03-24 2023-04-28 isk mitigation investments nvelope lementation 5 subproyecto "Reacondiciona ss (Non Bank-SPD miento y Mejora del Sistema ) de Riego de Buta Ranquil" de la provincia del Neuquén AR-UCAR-349299-CW-RFB / National Procure Licitación de obra en el marc ment Document - Component 2 - Agricultural r Single Stage - One E Pending Imp 2024-01-0 o del subproyecto "Readecua IBRD / 88670 Post Request for Bids Open - National 1 Envelope proce 4,800,000.00 0.00 2023-03-20 2023-03-25 2023-05-06 2023-06-05 2023-07-10 isk mitigation investments nvelope lementation 6 ción de Los sistemas de Rieg ss (Non Bank-SPD o superficiales Nonogasta, La ) Rioja - Etapa 1" AR-UCAR-216705-CW-RFB / National Procure Obra correspondiente al Sub ment Document - Component 2 - Agricultural r Single Stage - One E 15,882,287.5 Under Imple 2023-05-2 proyecto "Readecuación de c IBRD / 88670 Prior Request for Bids Open - National 1 Envelope proce 0.00 2022-08-05 2023-06-13 2022-08-10 2022-09-21 2023-06-26 2022-10-21 2022-11-25 isk mitigation investments nvelope 0 mentation 6 aminos rurales: RP S/N Tram ss (Non Bank-SPD o RPN 32 (Seguí) – RPN 34". ) Entre Ríos AR-UCAR-366791-CW-RFB / Obra civil en el marco del su National Procure bproyecto "Optimización de l ment Document - Component 2 - Agricultural r Single Stage - One E Pending Imp 2024-11-1 a Infraestructura de Riego de IBRD / 88670 Post Request for Bids Open - National 1 Envelope proce 8,500,000.00 0.00 2023-06-16 2023-06-23 2023-08-04 2023-09-03 2023-10-08 isk mitigation investments nvelope lementation 1 l Valle Bonaerense del Río Co ss (Non Bank-SPD lorado, revestimiento de Can ) ales" de la provincia de Buen os Aires AR-UCAR-311335-CW-RFB / Obra civil en el marco del su National Procure bproyecto "Optimización de l ment Document - Component 2 - Agricultural r Single Stage - One E 10,241,917.0 2023-07-0 a Infraestructura de Riego de IBRD / 88670 Prior Request for Bids Open - National 1 Envelope proce 0.00 Canceled 2022-09-19 2022-09-24 2022-11-05 2022-12-05 2023-01-09 isk mitigation investments nvelope 0 8 l Valle Bonaerense del Río Co ss (Non Bank-SPD lorado, revestimiento de Can ) ales" de la provincia de Buen os Aires GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual AR-UCAR-94920-GO-DIR / Pl Component 1 - Strengthenin ataforma de Integración, Vali IBRD / 88670 g agro-climatic information s Prior Direct Selection Direct 1,800,000.00 1,509,027.90 Signed 2019-04-15 2019-09-02 2019-04-20 2019-09-03 2019-05-25 2019-09-26 2021-05-14 dación y publicación de Infor ystems mación Agrometeorológica AR-UCAR-94928-GO-RFB / A Component 1 - Strengthenin dquisición de instrumentos y Open - Internationa Single Stage - One E IBRD / 88670 g agro-climatic information s Post Request for Bids 240,000.00 0.00 Canceled 2019-05-15 2019-05-20 2019-07-01 2019-07-31 2019-09-04 2020-03-02 emplazamiento de estacione l nvelope ystems s meteorológicas AR-UCAR-94931-GO-RFB / A dquisición y Actualización Te Component 1 - Strengthenin Single Stage - One E cnológica (Hardware - Softwa IBRD / 88670 g agro-climatic information s Post Request for Bids Open - National 150,000.00 141,313.05 Signed 2020-09-10 2021-02-12 2020-09-17 2020-10-29 2021-06-23 2020-11-26 2021-11-15 2020-12-31 2021-12-31 2021-07-01 nvelope re) para Puesta en Producció ystems n. Convenio MFI - SMN - MAG yP AR-UCAR-216754-GO-RFB / Convenio MAGyP - INTA - Adq Component 1 - Strengthenin Single Stage - One E Pending Impl uisición de equipamiento Info IBRD / 88670 g agro-climatic information s Post Request for Bids Open - National 110,000.00 0.00 2021-05-03 2021-05-08 2021-06-19 2021-07-19 2021-08-23 2022-02-19 nvelope ementation rmatico Sistema Back up / st ystems orage / procesamiento (Hard ware y software) AR-UCAR-216771-GO-RFQ / Component 3 - Agricultural E Request for Quota Single Stage - One E Pending Impl Fortalecimiento Informático IBRD / 88670 mergency Response Financi Post Open - National 25,000.00 0.00 2021-11-20 2022-01-15 2022-07-14 tions nvelope ementation MAGYP y Provincias (3.1.1.3) ng and Transfer of Agroclim atic Risks AR-UCAR-226703-GO-RFB / Component 2 - Agricultural r Single Stage - One E Pending Impl ELMI - Adquisición de reservo IBRD / 88670 Post Request for Bids Open - National 212,000.00 0.00 2021-07-01 2021-07-06 2021-08-17 2021-09-16 2021-10-21 2022-04-19 isk mitigation investments nvelope ementation rios y parcelas AR-UCAR-231943-GO-RFQ / Component 1 - Strengthenin Request for Quota Single Stage - One E Placas de telemetría 3G - Bol IBRD / 88670 g agro-climatic information s Post Open - National 49,368.00 49,368.00 Signed 2021-05-15 2021-07-10 2022-03-09 2022-01-06 tions nvelope sa de Cereales Entre Ríos ystems AR-UCAR-216745-GO-RFB / Component 1 - Strengthenin Convenio CONAE - Adquisició Single Stage - One E IBRD / 88670 g agro-climatic information s Post Request for Bids Open - National 614,333.30 0.00 Signed 2021-02-05 2021-11-03 2021-02-10 2021-03-24 2021-12-16 2021-04-23 2022-05-20 2021-05-28 2021-11-24 n de sistema de discos para nvelope ystems almacenamiento de red de al ta AR-UCAR-255413-GO-RFQ / Component 2 - Agricultural r Request for Quota Single Stage - One E Pending Impl Elementos de medición para IBRD / 88670 Post Open - National 29,000.00 0.00 2021-10-09 2021-12-04 2022-06-02 isk mitigation investments tions nvelope ementation parcelas demostrativas ELMI AR-UCAR-255414-GO-RFQ / Component 2 - Agricultural r Request for Quota Single Stage - One E Pending Impl IBRD / 88670 Post Open - National 71,000.00 0.00 2022-06-06 2022-08-01 2023-01-28 Parcelas demostrativas riego isk mitigation investments tions nvelope ementation ELMI AR-UCAR-186660-GO-RFQ / Component 1 - Strengthenin Adquisición de instrumentos Single Stage - One E IBRD / 88670 g agro-climatic information s Post Request for Bids Open - National 506,010.00 0.00 Signed 2021-04-01 2021-11-01 2021-04-06 2021-12-09 2021-12-09 2022-01-08 2022-05-31 2022-02-12 2022-08-11 para estaciones meteorológic nvelope ystems as convencionales - Convenio MAGyP - INTA Page 2 AR-UCAR-286858-GO-RFQ / Equipamiento informático en el marco del subproyecto "Re Component 2 - Agricultural r Request for Quota Single Stage - One E Pending Impl IBRD / 88670 Post Open - National 5,846.00 0.00 2022-05-07 2022-07-02 2022-12-29 acondicionamiento y Mejora isk mitigation investments tions nvelope ementation del Sistema de Riego de Buta Ranquil" de la provincia del N euquén AR-UCAR-287085-GO-RFQ / Adquisición Equipamiento Inf ormático UEP y Consorcio Có Component 2 - Agricultural r Request for Quota Single Stage - One E Pending Impl rdoba - Acueducto Ganadero IBRD / 88670 Post Open - National 17,000.00 0.00 2022-04-16 2022-06-11 2022-12-08 isk mitigation investments tions nvelope ementation "La Providencia, La Ramada y Santa Ana - Departamento Roque Sáenz Peña, Provincia de Córdoba". AR-UCAR-287086-GO-RFQ / Mobiliario UEP y Consorcio - Acueducto Ganadero "La Pro Component 2 - Agricultural r Request for Quota Single Stage - One E Under Imple IBRD / 88670 Post Open - National 3,435.00 0.00 2022-04-16 2022-06-11 2022-12-08 videncia, La Ramada y Santa isk mitigation investments tions nvelope mentation Ana - Departamento Roque S áenz Peña, Provincia de Córd oba". AR-UCAR-295703-GO-RFB / Component 1 - Strengthenin Single Stage - One E Under Imple IBRD / 88670 Prior Request for Bids Open - National 3,000,000.00 0.00 2022-06-06 2022-07-27 2022-06-11 2022-07-23 2022-09-07 2022-08-22 2022-09-26 2023-03-25 Actualización Datacenter MA g agro-climatic information s nvelope mentation GYP ystems AR-UCAR-301414-GO-RFB / 10 camionetas 4x4 en el mar co del subproyecto "Fortaleci Component 2 - Agricultural r Single Stage - One E Pending Impl IBRD / 88670 Post Request for Bids Open - National 700,000.00 0.00 2022-07-04 2022-07-09 2022-08-20 2022-09-19 2022-10-24 2023-04-22 miento del sistema de preve isk mitigation investments nvelope ementation nción y control de Incendios Forestales" de la provincia d e Mendoza AR-UCAR-301415-GO-RFB / Maquinaria pesada en el mar co del subproyecto "Fortaleci Component 2 - Agricultural r Single Stage - One E Pending Impl IBRD / 88670 Post Request for Bids Open - National 1,540,000.00 0.00 2022-07-04 2022-07-09 2022-08-20 2022-09-19 2022-10-24 2023-04-22 miento del sistema de preve isk mitigation investments nvelope ementation nción y control de Incendios Forestales" de la provincia d e Mendoza AR-UCAR-286853-GO-RFQ / Compra de Equipamiento Inf ormático en el marco del sub Component 2 - Agricultural r Request for Quota Single Stage - One E Pending Impl IBRD / 88670 Post Open - National 20,000.00 0.00 2022-07-15 2022-09-09 2022-11-09 proyecto "Fortalecimiento Sa isk mitigation investments tions nvelope ementation nitario del rodeo bovino provi ncial" de la provincia del Neu quén AR-UCAR-301437-GO-RFQ / Equipamiento informático en Component 2 - Agricultural r Request for Quota Single Stage - One E Pending Impl el marco del subproyecto "D IBRD / 88670 Post Open - National 6,600.00 0.00 2022-08-15 2022-10-10 2023-01-08 isk mitigation investments tions nvelope ementation esarrollo Ganadero de la Pro vincia de Jujuy (Etapa I)", pro vincia de Jujuy AR-UCAR-301429-GO-RFB / Maquinaria para siembra y e Component 2 - Agricultural r Single Stage - One E Pending Impl nfardado en el marco del sub IBRD / 88670 Post Request for Bids Open - National 328,000.00 0.00 2022-10-04 2022-10-09 2022-11-20 2022-12-20 2023-01-24 2023-04-24 isk mitigation investments nvelope ementation proyecto "Desarrollo Ganade ro de la Provincia de Jujuy (Et apa I)" de la provincia de Juju y AR-UCAR-301412-GO-RFQ / Equipamiento para Mejorami ento del sistema de comunic Component 2 - Agricultural r Request for Quota Single Stage - One E Pending Impl ación en el marco del subpro IBRD / 88670 Post Open - National 58,000.00 0.00 2022-08-03 2022-09-28 2022-10-28 isk mitigation investments tions nvelope ementation yecto "Fortalecimiento del sis tema de prevención y control de Incendios Forestales" de l a provincia de Mendoza AR-UCAR-301413-GO-RFB / Equipamiento de Combate d e Incendios: motosierras, bo mbas, mochilas, matafuegos, Component 2 - Agricultural r Single Stage - One E Pending Impl IBRD / 88670 Post Request for Bids Open - National 190,000.00 0.00 2022-10-04 2022-10-09 2022-11-20 2022-12-20 2023-01-24 2023-02-23 etc en el marco del subproye isk mitigation investments nvelope ementation cto "Fortalecimiento del siste ma de prevención y control d e Incendios Forestales" de la provincia de Mendoza AR-UCAR-301417-GO-RFQ / Estaciones Meteorológicas en el marco del subproyecto "Fo Component 2 - Agricultural r Request for Quota Single Stage - One E Pending Impl IBRD / 88670 Post Open - National 77,000.00 0.00 2022-12-07 2023-02-01 2023-05-02 rtalecimiento del sistema de isk mitigation investments tions nvelope ementation prevención y control de Ince ndios Forestales" de la provin cia de Mendoza AR-UCAR-301431-GO-RFB / Maquinaria para establecimie nto "El remate" en el marco Component 2 - Agricultural r Single Stage - One E Pending Impl IBRD / 88670 Post Request for Bids Open - National 290,000.00 0.00 2022-10-05 2022-10-10 2022-11-21 2022-12-21 2023-01-25 2023-04-25 del subproyecto "Desarrollo isk mitigation investments nvelope ementation Ganadero de la Provincia de J ujuy (Etapa I", provincia de Ju juy AR-UCAR-301434-GO-RFB / Equipamiento para laboratori o de genética animal en el m Component 2 - Agricultural r Single Stage - One E Pending Impl IBRD / 88670 Post Request for Bids Open - National 109,000.00 0.00 2022-11-02 2022-11-07 2022-12-19 2023-01-18 2023-02-22 2023-05-23 arco del subproyecto "Desarr isk mitigation investments nvelope ementation ollo Ganadero de la Provincia de Jujuy (Etapa I)" provincia de Jujuy AR-UCAR-286851-GO-RFQ / Compra de dos corrales para manejo de Ganado en el mar Component 2 - Agricultural r Single Stage - One E Pending Impl IBRD / 88670 Post Request for Bids Open - National 100,000.00 0.00 2022-07-01 2022-07-06 2022-08-17 2022-09-16 2022-10-21 2023-01-19 co del subproyecto "Fortaleci isk mitigation investments nvelope ementation miento Sanitario del rodeo b ovino provincial" de la Provin cia del Neuquén AR-UCAR-301422-GO-RFB / Compra de 2 camionetas 4x4 Component 2 - Agricultural r Single Stage - One E Pending Impl en el marco del subproyecto IBRD / 88670 Post Request for Bids Open - National 150,000.00 0.00 2022-07-26 2022-07-31 2022-09-11 2022-10-11 2022-11-15 2023-03-15 isk mitigation investments nvelope ementation "Desarrollo Ganadero de la P rovincia de Jujuy (Etapa I)" d e la provincia de Jujuy AR-UCAR-303592-GO-DIR / E staciones agrometeorológica Component 1 - Strengthenin Pending Impl s, sensores y despliegue de t IBRD / 88670 g agro-climatic information s Post Direct Selection Direct - National 60,000.00 0.00 2022-07-18 2022-07-28 2022-10-03 2023-04-01 ementation ecnología en servidor de mo ystems nitoreo provincial en la provi ncia de Chaco Page 3 AR-UCAR-231949-GO-RFB / Component 1 - Strengthenin Single Stage - One E Estaciones Meteorológicas A IBRD / 88670 g agro-climatic information s Post Request for Bids Open - National 118,800.00 0.00 Canceled 2022-01-17 2022-03-17 2022-01-22 2022-03-05 2022-05-06 2022-04-04 2022-05-09 2022-11-05 nvelope utomáticas (EMA) - provincia ystems de Formosa AR-UCAR-309138-GO-RFB / Component 1 - Strengthenin Estaciones Meteorológicas A Single Stage - One E Pending Impl IBRD / 88670 g agro-climatic information s Post Request for Bids Open - National 118,000.00 0.00 2022-08-15 2022-08-20 2022-10-01 2022-10-31 2022-12-05 2023-06-03 utomáticas (EMA) y repuesto nvelope ementation ystems s - provincia de Formosa AR-UCAR-287088-GO-RFQ / Sistema de Ventilación Conso rcio - Acueducto Ganadero "L Component 2 - Agricultural r Request for Quota Single Stage - One E IBRD / 88670 Post Open - National 3,607.00 0.00 Canceled 2022-04-16 2022-06-11 2022-12-08 a Providencia, La Ramada y isk mitigation investments tions nvelope Santa Ana - Departamento R oque Sáenz Peña, Provincia d e Córdoba". AR-UCAR-315643-GO-RFQ / Equipamiento para oficina -C Component 2 - Agricultural r Request for Quota Single Stage - One E Under Imple onsorcio- "Acueducto Ganade IBRD / 88670 Post Open - National 3,607.00 0.00 2022-09-27 2022-11-22 2023-05-21 isk mitigation investments tions nvelope mentation ro La Providencia La Ramada y Santa Ana - Córdoba" AR-UCAR-186688-GO-DIR / A Component 1 - Strengthenin ctualización Antenas. Conven IBRD / 88670 g agro-climatic information s Post Direct Selection Direct 578,334.85 0.00 Canceled 2020-09-09 2021-06-24 2020-09-16 2021-07-24 2021-10-04 2022-05-23 io MAGyP - INTA ystems AR-UCAR-286848-GO-RFB / Dos (2) camionetas 4x4 DC - Component 2 - Agricultural r Single Stage - One E Subproyecto "Fortalecimient IBRD / 88670 Post Request for Bids Open - National 147,000.00 0.00 Canceled 2022-04-04 2022-06-24 2022-07-06 2022-08-17 2022-09-16 2022-10-21 2023-02-01 isk mitigation investments nvelope o Sanitario del rodeo bovino provincial" provincia del Neu quén AR-UCAR-318605-GO-RFB / Compra de heladeras con fre ezer, conservadoras plásticas y centrífugas para conservaci Component 2 - Agricultural r Single Stage - One E Pending Impl IBRD / 88670 Post Request for Bids Open - National 125,000.00 0.00 2022-09-30 2022-10-05 2022-11-02 2022-11-17 2022-12-22 2023-06-20 ón de vacunas e insumos vet isk mitigation investments nvelope ementation erinarios en el marco del sub proyecto "Fortalecimiento Sa nitario del rodeo bovino provi ncial" de la provincia del Neu quén AR-UCAR-287082-GO-RFQ / Adquisición de Vehículo para UEP Córdoba - Acueducto Ga Component 2 - Agricultural r Request for Quota Single Stage - One E IBRD / 88670 Post Open - National 35,800.00 0.00 Canceled 2022-04-16 2022-06-11 2022-12-08 nadero "La Providencia, La R isk mitigation investments tions nvelope amada y Santa Ana - Departa mento Roque Sáenz Peña, Pr ovincia de Córdoba". AR-UCAR-224910-GO-RFB / Component 2 - Agricultural r Single Stage - One E Ocho (8) Camionetas tipo pic IBRD / 88670 Post Request for Bids Open - National 320,000.00 0.00 Canceled 2021-05-03 2022-02-17 2021-05-08 2021-06-19 2022-04-05 2021-07-19 2021-08-23 2022-02-19 isk mitigation investments nvelope k up doble cabina AR-UCAR-320687-GO-RFB / T Component 2 - Agricultural r Single Stage - One E Pending Impl res (3) Camionetas tipo pick IBRD / 88670 Post Request for Bids Open - National 300,000.00 0.00 2022-10-14 2022-10-19 2022-11-03 2022-11-08 2022-11-22 2022-12-22 isk mitigation investments nvelope ementation up doble cabina AR-UCAR-318611-GO-RFQ / Adquisición de Vehículo para UEP Córdoba - Acueducto Ga Component 2 - Agricultural r Request for Quota Single Stage - One E IBRD / 88670 Post Open - National 65,000.00 0.00 Canceled 2022-10-08 2022-12-03 2023-06-01 nadero "La Providencia, La R isk mitigation investments tions nvelope amada y Santa Ana - Departa mento Roque Sáenz Peña, Pr ovincia de Córdoba". AR-UCAR-318601-GO-RFB / Dos (2) camionetas 4x4 DC - Component 2 - Agricultural r Single Stage - One E Pending Impl Subproyecto "Fortalecimient IBRD / 88670 Post Request for Bids Open - National 147,000.00 0.00 2022-09-30 2022-10-05 2022-11-16 2022-12-16 2023-01-20 2023-07-19 isk mitigation investments nvelope ementation o Sanitario del rodeo bovino provincial" provincia del Neu quén AR-UCAR-318824-GO-RFQ / Una (a) camioneta 4x4 - Sub proyecto "Rehabilitación de l Component 2 - Agricultural r Request for Quota Single Stage - One E Pending Impl IBRD / 88670 Post Open - National 88,000.00 0.00 2022-10-10 2022-12-05 2023-06-03 a dinámica hidráulica del sub isk mitigation investments tions nvelope ementation sistema de la Cuenca del Arr oyo Baí – Zona Norte de Corri entes" AR-UCAR-240328-GO-RFQ / Component 1 - Strengthenin Equipamiento informático - F Request for Quota Single Stage - One E IBRD / 88670 g agro-climatic information s Post Open - National 35,155.95 0.00 Canceled 2021-09-25 2021-11-20 2022-05-19 ortalecimiento interno Oficin tions nvelope ystems a de Riesgo Agropecuario AR-UCAR-216747-GO-RFB / Convenio CONAE - Adquisició Component 1 - Strengthenin n de un sistema de antena p Open - Internationa Single Stage - One E IBRD / 88670 g agro-climatic information s Post Request for Bids 570,000.00 0.00 Canceled 2021-12-01 2022-08-26 2021-12-06 2022-08-26 2022-01-17 2022-02-16 2022-03-23 2022-09-19 ara recepción y adquisición d l nvelope ystems e datos satelitales de observac ión de la tierra en banda L y X. AR-UCAR-216747-GO-RFB-2 / Convenio CONAE - Adquisici Component 1 - Strengthenin ón de un sistema de antena Open - Internationa Single Stage - One E Under Imple IBRD / 88670 g agro-climatic information s Post Request for Bids 700,000.00 0.00 2022-11-14 2023-01-23 2022-11-19 2023-01-27 2022-12-31 2023-01-30 2023-03-06 2023-09-02 para recepción y adquisición l nvelope mentation ystems de datos satelitales de obser vación de la tierra en banda L y X. AR-UCAR-326032-GO-DIR / S Component 1 - Strengthenin Pending Impl ensores para estaciones met IBRD / 88670 g agro-climatic information s Post Direct Selection Direct - National 44,852.00 0.00 2022-11-15 2022-11-20 2022-12-26 2023-04-28 ementation eorológicas automáticas - Co ystems nvenio INTA AR-UCAR-326033-GO-DIR / T Component 1 - Strengthenin ermorresistencias de platino Pending Impl IBRD / 88670 g agro-climatic information s Post Direct Selection Direct - National 17,400.00 0.00 2022-11-15 2022-11-20 2022-12-26 2023-04-21 para estaciones meteorológic ementation ystems as automáticas de la Red INT A - Convenio INTA AR-UCAR-326040-GO-DIR / P Component 1 - Strengthenin lacas Electrónicas para Estaci Pending Impl IBRD / 88670 g agro-climatic information s Post Direct Selection Direct - National 25,000.00 0.00 2022-11-15 2022-11-20 2023-01-16 2023-03-03 ones Meteorológicas Automá ementation ystems ticas - Convenio INTA AR-UCAR-302281-GO-RFB / Activación CERC para la Provi Component 5 - Contingency Single Stage - One E ncia de Corrientes. Adquisici IBRD / 88670 Emergency Response Comp Prior Request for Bids Open - National 2,900,000.00 0.00 Canceled 2022-07-07 2022-07-22 2022-08-11 2022-08-16 2022-08-26 2022-12-24 nvelope ón de alambrado perimetral, onent (CERC) postes de acero de alto carb ono y accesorios Page 4 AR-UCAR-326153-GO-RFB / Activación CERC para la Provi Component 2 - Agricultural r Single Stage - One E ncia de Corrientes. Adquisici IBRD / 88670 Post Request for Bids Open - National 4,200,000.00 0.00 Canceled 2022-11-11 2022-11-16 2022-11-26 2022-12-06 2023-01-03 2023-07-02 isk mitigation investments nvelope ón de alambrado perimetral, postes de acero de alto carb ono y accesorios AR-UCAR-186688-GO-DIR-2 / Component 1 - Strengthenin Adquisición de Actualización Direct - Internation Pending Impl IBRD / 88670 g agro-climatic information s Post Direct Selection 580,000.00 0.00 2022-12-02 2022-12-09 2023-02-06 2023-09-25 del Sistema Receptor Satelita al ementation ystems l INTA Castelar AR-UCAR-240328-GO-RFQ-2 Component 1 - Strengthenin / Equipamiento informático - Request for Quota Single Stage - One E Pending Impl IBRD / 88670 g agro-climatic information s Post Open - National 85,000.00 0.00 2023-01-09 2023-03-27 2023-08-28 Fortalecimiento interno Ofici tions nvelope ementation ystems na de Riesgo Agropecuario AR-UCAR-332241-GO-RFB / Compra de Equipamiento Inf ormático en el marco del sub Component 2 - Agricultural r Request for Quota Single Stage - One E Pending Impl proyecto "Reacondicionamie IBRD / 88670 Post Open - National 70,000.00 0.00 2023-01-07 2023-03-04 2023-08-31 isk mitigation investments tions nvelope ementation nto de los préstamos de la re d vial provincial para la prev ención y control de incendios forestales” de La Pampa AR-UCAR-332240-GO-RFB / Una (a) camioneta 4x4 - Sub proyecto "Reacondicionamie Component 2 - Agricultural r Request for Quota Single Stage - One E Pending Impl IBRD / 88670 Post Open - National 80,000.00 0.00 2023-01-07 2023-03-04 2023-08-31 nto de los préstamos de la re isk mitigation investments tions nvelope ementation d vial provincial para la prev ención y control de incendios forestales” La Pampa AR-UCAR-347024-GO-DIR / R Component 1 - Strengthenin Direct - Internation Pending Impl IBRD / 88670 Post Direct Selection 575,000.00 0.00 2023-06-05 2024-06-04 epuestos radares - Convenio g agro-climatic information s al ementation INTA ystems AR-UCAR-347129-GO-RFQ / Equipamiento de Combate d e Incendios: motosierras, Sap a Rastrillo, Pulaski, machetes Component 2 - Agricultural r Request for Quota Single Stage - One E Pending Impl IBRD / 88670 Post Open - National 90,300.00 0.00 2023-03-19 2023-05-14 2023-11-10 , tanque de agua portatil, etc isk mitigation investments tions nvelope ementation en el marco del subproyecto " PREVENCION, CONTROL Y R EMEDIACION DE INCENDIOS FORESTALES - CORDOBA" AR-UCAR-347132-GO-RFB / Maquinaria pesada en el mar Component 2 - Agricultural r Single Stage - One E Pending Impl co del subproyecto "Prevenci IBRD / 88670 Post Request for Bids Open - National 360,000.00 0.00 2023-03-13 2023-03-18 2023-04-29 2023-05-29 2023-07-03 2023-12-30 isk mitigation investments nvelope ementation ón, Control y Remediación de incendios forestales en la Pro vincia de Córdoba" AR-UCAR-347133-GO-RFB / Una (1) Camioneta 4x4 y Cua tro (4) Vehículos utilitarios en Component 2 - Agricultural r Single Stage - One E Pending Impl IBRD / 88670 Post Request for Bids Open - National 300,000.00 0.00 2023-03-13 2023-03-18 2023-04-29 2023-05-29 2023-07-03 2023-12-30 el marco del Subproyecto "Pr isk mitigation investments nvelope ementation evención, Control y Remedia ción de incendios forestales en la Provincia de Córdoba" AR-UCAR-347178-GO-RFB / Cámara de germinación con control de temperatura e ins umos para un banco de germ Component 2 - Agricultural r Single Stage - One E Pending Impl IBRD / 88670 Post Request for Bids Open - National 165,000.00 0.00 2023-03-13 2023-03-18 2023-04-29 2023-05-29 2023-07-03 2023-12-30 oplasma en el marco del Sub isk mitigation investments nvelope ementation proyecto "Prevención, Contro l y Remediación de incendios forestales en la Provincia de Córdoba" AR-UCAR-348011-GO-RFB / Compra de maquinaria vial e n el marco del subproyecto " Component 2 - Agricultural r Single Stage - One E Pending Impl IBRD / 88670 Prior Request for Bids Open - National 4,300,000.00 0.00 2023-03-13 2023-03-18 2023-04-29 2023-05-29 2023-07-03 2023-12-30 Fortalecimiento Provincial de isk mitigation investments nvelope ementation Manejo Agroambiental para l a adaptación y mitigación del riesgo climático" d AR-UCAR-348015-GO-RFB / 4 Camionetas Pick up 4x4 y 3 vehículos utilitarios en el mar co del subproyecto "Fortaleci Component 2 - Agricultural r Single Stage - One E Pending Impl IBRD / 88670 Post Request for Bids Open - National 350,000.00 0.00 2023-03-13 2023-03-18 2023-04-29 2023-05-29 2023-07-03 2023-12-30 miento Provincial de Manejo isk mitigation investments nvelope ementation Agroambiental para la adapt ación y mitigación del riesgo climático" de la provincia de Misiones AR-UCAR-348016-GO-RFB / Equipamiento para combate de Incendios en el marco del Component 2 - Agricultural r Single Stage - One E Pending Impl subproyecto "Fortalecimiento IBRD / 88670 Post Request for Bids Open - National 830,000.00 0.00 2023-03-13 2023-03-18 2023-04-29 2023-05-29 2023-07-03 2023-12-30 isk mitigation investments nvelope ementation Provincial de Manejo Agroam biental para la adaptación y mitigación del riesgo climátic o" provincia de Misiones AR-UCAR-348017-GO-RFB / Maquinaria y equipos para tr abajo de suelos en el marco Component 2 - Agricultural r Single Stage - One E Pending Impl del subproyecto "Fortalecimi IBRD / 88670 Post Request for Bids Open - National 1,420,000.00 0.00 2023-03-13 2023-03-18 2023-04-29 2023-05-29 2023-07-03 2023-12-30 isk mitigation investments nvelope ementation ento Provincial de Manejo Ag roambiental para la adaptaci ón y mitigación del riesgo cli mático" de la provincia de Mi siones AR-UCAR-348162-GO-RFB / Activación CERC para la Provi Component 5 - Contingency Single Stage - One E Pending Impl ncia de Corrientes. Adquisici IBRD / 88670 Emergency Response Comp Post Request for Bids Open - National 2,300,000.00 0.00 2023-03-13 2023-04-02 2023-04-12 2023-04-17 2023-05-08 2023-06-07 nvelope ementation ón de alambrado perimetral, onent (CERC) postes de quebracho y acces orios AR-UCAR-348014-GO-RFB / Vehículos pesados en el mar co del subproyecto "Fortaleci Component 2 - Agricultural r Single Stage - One E Pending Impl miento Provincial de Manejo IBRD / 88670 Post Request for Bids Open - National 1,700,000.00 0.00 2023-03-13 2023-03-18 2023-04-29 2023-05-29 2023-07-03 2023-12-30 isk mitigation investments nvelope ementation Agroambiental para la adapt ación y mitigación del riesgo climático" de la provincia de Misiones AR-UCAR-355816-GO-RFQ / Parcelas demostrativas para Component 2 - Agricultural r Request for Quota Single Stage - One E Pending Impl riego en el marco del subpro IBRD / 88670 Post Open - National 8,000.00 0.00 2023-04-22 2023-06-17 2023-12-14 isk mitigation investments tions nvelope ementation yecto "Mejora de la red de ri ego del Valle de Jáchal – Can al del Alto" en San Juan Page 5 AR-UCAR-355818-GO-RFQ / Compra de Equipamiento Inf ormático en el marco del sub Component 2 - Agricultural r Request for Quota Single Stage - One E Pending Impl IBRD / 88670 Post Open - National 15,000.00 0.00 2023-04-22 2023-06-17 2023-12-14 proyecto "Mejora de la red d isk mitigation investments tions nvelope ementation e riego del Valle de Jáchal – C anal del Alto" provincia de Sa n Juan AR-UCAR-357788-GO-RFB / I Component 1 - Strengthenin nstrumentos para estaciones Single Stage - One E Pending Impl IBRD / 88670 g agro-climatic information s Post Request for Bids Open - National 303,188.00 0.00 2023-05-08 2023-05-15 2023-06-15 2023-07-15 2023-08-31 2023-11-30 meteorológicas convencional nvelope ementation ystems es y automáticas - Convenio I NTA AR-UCAR-357974-GO-RFQ / Compra de heladeras con fre ezer, conservadoras plásticas y centrífugas para conservaci Component 2 - Agricultural r Request for Quota Single Stage - One E Pending Impl IBRD / 88670 Post Open - National 33,000.00 0.00 2023-05-06 2023-07-01 2023-12-28 ón de vacunas e insumos vet isk mitigation investments tions nvelope ementation erinarios en el marco del sub proyecto "Fortalecimiento Sa nitario del rodeo bovino provi ncial" de la provincia del Neu quén AR-UCAR-357976-GO-RFQ / Compra de Equipamiento Inf Component 2 - Agricultural r Request for Quota Single Stage - One E Pending Impl ormático en el marco del sub IBRD / 88670 Post Open - National 27,000.00 0.00 2023-04-29 2023-06-24 2023-12-21 isk mitigation investments tions nvelope ementation proyecto "FORTALECIMIENTO SANITARIO DEL RODEO BOVI NO PROVINCIAL" AR-UCAR-358057-GO-RFQ / Cámaras y equipamiento de prensa para UEP Córdoba - A Component 2 - Agricultural r Request for Quota Single Stage - One E Pending Impl cueducto Ganadero "La Provi IBRD / 88670 Post Open - National 26,000.00 0.00 2023-05-08 2023-07-03 2023-12-30 isk mitigation investments tions nvelope ementation dencia, La Ramada y Santa A na - Departamento Roque Sá enz Peña, Provincia de Córdo ba" AR-UCAR-361848-GO-RFQ / Mobiliario UEP y Consorcio - Acueducto Ganadero "La Pro Component 2 - Agricultural r Request for Quota Single Stage - One E Pending Impl IBRD / 88670 Post Open - National 6,500.00 0.00 2023-05-27 2023-07-22 2024-01-18 videncia, La Ramada y Santa isk mitigation investments tions nvelope ementation Ana - Departamento Roque S áenz Peña, Provincia de Córd oba AR-UCAR-326037-GO-RFQ / Component 1 - Strengthenin Request for Quota Single Stage - One E Pending Impl Notebooks y servidores - Con IBRD / 88670 g agro-climatic information s Post Open - National 89,125.50 0.00 2022-12-05 2023-06-19 2023-10-20 tions nvelope ementation venio INTA ystems AR-UCAR-365932-GO-DIR / S egunda Activación CERC: Co Component 5 - Contingency ntratación de un servicio de Pending Impl IBRD / 88670 Emergency Response Comp Post Direct Selection Direct - National 15,000,000.00 0.00 2023-06-09 2023-06-11 2023-06-22 2023-11-19 disponibilidad de insumos ag ementation onent (CERC) ropecuarios, y entrega a peq ueños y medianos productor es AR-UCAR-257976-GO-RFB / Component 1 - Strengthenin Hardware y Software para “ Single Stage - One E Pending Impl IBRD / 88670 g agro-climatic information s Post Request for Bids Open - National 800,000.00 0.00 2023-06-26 2023-07-01 2023-08-12 2023-09-11 2023-10-16 2024-04-13 Sistemas de Información de nvelope ementation ystems Operaciones (SIO)” AR-UCAR-367631-GO-RFB / Modernización de la Red de Component 1 - Strengthenin Open - Internationa Single Stage - Two E Pending Impl Referencia Meteorológica de IBRD / 88670 g agro-climatic information s Prior Request for Bids 5,000,000.00 0.00 2023-06-20 2023-06-30 2023-08-11 2023-10-24 2023-11-28 2024-05-26 l nvelope ementation Superficie del Servicio Meteo ystems rológico Nacional (SMN) AR-UCAR-289777-GO-RFB / Modernización de la Red de Component 1 - Strengthenin Open - Internationa Single Stage - One E Referencia Meteorológica de IBRD / 88670 g agro-climatic information s Prior Request for Bids 4,764,700.00 0.00 Canceled 2022-04-25 2022-04-30 2022-06-11 2022-07-11 2022-08-15 2023-02-11 l nvelope Superficie del Servicio Meteo ystems rológico Nacional (SMN) NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual AR-UCAR-247569-CS-CQS / Component 3 - Agricultural E Single Stage - One E Adquisición piloto de seguro IBRD / 88670 mergency Response Financi Post Request for Bids Open - National 800,000.00 0.00 Signed 2021-09-30 2021-11-30 2021-10-18 2021-11-29 2022-01-10 2021-12-29 2022-03-27 2022-02-02 2022-08-01 nvelope hortícola. Provincia de Bueno ng and Transfer of Agroclim s Aires atic Risks AR-UCAR-302275-NC-RFB / A Component 3 - Agricultural E dquisición piloto de seguro h mergency Response Financi Single Stage - One E Pending Impl IBRD / 88670 Post Request for Bids Open - National 300,000.00 0.00 2022-06-30 2022-07-07 2022-08-06 2022-08-21 2022-09-25 2023-05-23 ortícola (complementario). Pr ng and Transfer of Agroclim nvelope ementation ovincia de Buenos Aires atic Risks AR-UCAR-304449-NC-RFQ / Servicio de cátering para Jorn Component 1 - Strengthenin adas de capacitación en el “ Request for Quota Single Stage - One E Pending Impl IBRD / 88670 g agro-climatic information s Post Open - National 1,200.00 0.00 2022-07-20 2022-09-01 2023-02-28 USO DE INFORMACIÓN AGRO tions nvelope ementation ystems CLIMÁTICA EN LA TOMA DE D ECISIONES FRENTE AL RIESG O AGROPECUARIO” CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual AR-UCAR-216769-CS-CQS / Contratación de firma consul Component 3 - Agricultural E tora /universidad especialista mergency Response Financi Consultant Qualifi Pending Impleme IBRD / 88670 Post Open - National 21,500.00 0.00 2021-04-01 2021-04-22 2021-06-05 2021-07-05 2021-08-09 2022-02-05 en programación web para p ng and Transfer of Agroclim cation Selection ntation lataforma de carga y consult atic Risks a base histórica de Emergenc ia Agropecuaria.3.1.1.1 y 3.1. 1.2 Page 6 AR-UCAR-216775-CS-CQS / Contratación de firma consul tora especialista en program Component 3 - Agricultural E ación de sistemas para la pu mergency Response Financi Consultant Qualifi Pending Impleme blicación web de herramient IBRD / 88670 Post Open - National 40,000.00 0.00 2021-04-05 2021-04-26 2021-06-09 2021-07-09 2021-08-13 2022-02-09 ng and Transfer of Agroclim cation Selection ntation as de monitoreo y gestión de atic Risks riesgos, desarrollo y publicac ión de Índices climáticos e inf ormes de estudios técnicos. 3.1.6.1 y 3.1.6.2. AR-UCAR-226701-CS-CQS / E Component 2 - Agricultural r Consultant Qualifi Pending Impleme LMI - Desarrollo de una app e IBRD / 88670 Post Open - National 10,000.00 0.00 2021-05-03 2021-05-24 2021-07-07 2021-08-06 2021-09-10 2022-03-09 isk mitigation investments cation Selection ntation n gestión del conocimiento AR-UCAR-247570-CS-QCBS / Contratación de Auditoría Co Component 4 - Project coord Quality And Cost- Under Implement ncurrente de los subproyecto IBRD / 88670 ination, monitoring and eval Post Open - National 240,000.00 0.00 2021-08-30 2022-01-18 2021-09-20 2021-11-03 2021-12-01 2021-12-31 2022-02-04 2022-03-11 2023-03-11 Based Selection ation s de inversión pública en el uation marco del subcomponente 2. 2 AR-UCAR-318668-CS-QCBS / Component 3 - Agricultural E Contratación de firma consul mergency Response Financi Quality And Cost- Open - Internationa Pending Impleme IBRD / 88670 Post 180,000.00 0.00 2022-10-03 2022-10-24 2022-12-07 2023-01-04 2023-02-03 2023-03-10 2023-04-14 2024-04-13 tora para diseño de estrategi ng and Transfer of Agroclim Based Selection l ntation a de financiamiento de riesg atic Risks os AR-UCAR-216770-CS-CQS / Component 3 - Agricultural E Contratación de firma consul mergency Response Financi Consultant Qualifi IBRD / 88670 Post Open - National 70,000.00 0.00 Canceled 2021-04-06 2022-03-15 2021-04-27 2021-06-10 2021-07-10 2021-08-14 2022-02-10 tora/universidad para diseño ng and Transfer of Agroclim cation Selection de estrategia de financiamie atic Risks nto de riesgos. 3.1.5.1 INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual AR-UCAR-186662-CS-INDV / Contratación Consultor/a Esp Component 2 - Agricultural r Individual Consult Pending Impleme IBRD / 88670 Post Open 9,285.70 0.00 2020-08-17 2020-10-05 2020-10-26 2020-11-30 2021-05-29 ecialista en Ingeniería Civil p isk mitigation investments ant Selection ntation ara Formulación de Proyecto s AR-UCAR-186673-CS-INDV / Contratación Consultor/a Esp Component 2 - Agricultural r Individual Consult Pending Impleme IBRD / 88670 Post Open 7,000.00 0.00 2020-08-17 2020-10-05 2020-10-26 2020-11-30 2021-05-29 ecialista en Formulación y Ev isk mitigation investments ant Selection ntation aluación Económica de Proye ctos AR-UCAR-186678-CS-INDV / Contratación Consultor/a esp Component 2 - Agricultural r Individual Consult Pending Impleme IBRD / 88670 Post Open 9,285.70 0.00 2020-08-17 2020-10-05 2020-10-26 2020-11-30 2021-05-29 ecialista ambiental para form isk mitigation investments ant Selection ntation ulación de proyectos AR-UCAR-186680-CS-INDV / Contratación Consultor/a esp Component 2 - Agricultural r Individual Consult Pending Impleme IBRD / 88670 Post Open 6,964.30 0.00 2020-08-17 2020-10-05 2020-10-26 2020-11-30 2021-05-29 ecialista en afectación de act isk mitigation investments ant Selection ntation ivos para formulación de pro yecto AR-UCAR-186681-CS-INDV / Contratación Consultor/a esp Component 2 - Agricultural r Individual Consult Pending Impleme IBRD / 88670 Post Open 6,964.30 0.00 2020-08-17 2020-10-05 2020-10-26 2020-11-30 2021-05-29 ecialista en pueblos indígena isk mitigation investments ant Selection ntation s para formulación de proyec to Component 3 - Agricultural E AR-UCAR-186683-CS-INDV / Individual Consult IBRD / 88670 mergency Response Financi Post Open 5,285.70 0.00 Canceled 2020-08-17 2020-10-05 2020-10-26 2020-11-30 2021-05-29 Contratración de Data Entry ant Selection ng and Transfer of Agroclim atic Risks AR-UCAR-186685-CS-INDV / Component 3 - Agricultural E Contratación de 4 Especialist mergency Response Financi Individual Consult as, Master o Doctor en econo IBRD / 88670 Post Open 59,214.30 0.00 Canceled 2020-08-17 2020-10-05 2020-10-26 2020-11-30 2021-05-29 ng and Transfer of Agroclim ant Selection mía agropecuaria y finanzas atic Risks públicas.- Buenos Aires AR-UCAR-186687-CS-CDS / B uenos Aires- Comité Técnico Component 2 - Agricultural r IBRD / 88670 Post Direct Selection Direct 74,000.00 0.00 Signed 2021-04-01 2021-07-21 2021-04-11 2021-07-08 2021-06-15 2021-12-12 de Evaluación de Subproyect isk mitigation investments os - Contrato Servicios de Co nsultoría IICA AR-UCAR-216774-CS-INDV / Component 3 - Agricultural E Especialista en economía agr mergency Response Financi Individual Consult Pending Impleme IBRD / 88670 Post Open 6,224.00 0.00 2021-05-03 2021-06-21 2021-07-12 2021-08-16 2022-02-12 aria para estudio de prefactib ng and Transfer of Agroclim ant Selection ntation ilidad para seguro en Ganade atic Risks ría AR-UCAR-216778-CS-INDV / Component 3 - Agricultural E Contratación de un consultor mergency Response Financi Individual Consult Pending Impleme IBRD / 88670 Post Open 15,000.00 0.00 2021-04-01 2021-05-20 2021-06-10 2021-07-15 2022-01-11 /ra especialista en seguros p ng and Transfer of Agroclim ant Selection ntation ara adecuación póliza seguro atic Risks horticola. 3.2.2.2. AR-UCAR-216761-CS-INDV / Convenio INTA - Contratación Component 1 - Strengthenin Individual Consult Pending Impleme de 1 Especialista, Master o D IBRD / 88670 g agro-climatic information s Post Open 27,000.00 0.00 2021-04-30 2021-06-18 2021-07-09 2021-08-13 2022-02-09 ant Selection ntation octor en agronomia, SIG, Tel ystems edetección.- Buenos Aires AR-UCAR-216756-CS-INDV / Component 1 - Strengthenin Individual Consult Pending Impleme Convenio INTA - Contratració IBRD / 88670 g agro-climatic information s Post Open 72,000.00 0.00 2021-04-30 2021-06-18 2021-07-09 2021-08-13 2022-02-09 ant Selection ntation n de 2 Programadores ystems AR-UCAR-216760-CS-INDV / Component 1 - Strengthenin Individual Consult Pending Impleme Convenio INTA - Contratració IBRD / 88670 g agro-climatic information s Post Open 36,000.00 0.00 2021-04-30 2021-06-18 2021-07-09 2021-08-13 2022-02-09 ant Selection ntation n de 1 Ing. Electrónico ystems AR-UCAR-186682-CS-INDV / Component 3 - Agricultural E Individual Consult Pending Impleme Contratración de 2 Programa IBRD / 88670 mergency Response Financi Post Open 14,857.10 0.00 2021-04-01 2021-05-20 2021-06-10 2021-07-15 2022-01-11 ant Selection ntation dor web Symfony SENIOR (Fr ng and Transfer of Agroclim ont-Backend) atic Risks AR-UCAR-216772-CS-INDV / Component 3 - Agricultural E Individual Consult Pending Impleme Especialista en economía agr IBRD / 88670 mergency Response Financi Post Open 7,780.00 0.00 2021-05-03 2021-06-21 2021-07-12 2021-08-16 2022-02-12 ant Selection ntation aria/seguros ng and Transfer of Agroclim atic Risks AR-UCAR-216776-CS-INDV / Component 3 - Agricultural E Individual Consult Pending Impleme Contratación de un actuario. IBRD / 88670 mergency Response Financi Post Open 15,000.00 0.00 2021-06-01 2021-07-20 2021-08-10 2021-09-14 2022-03-13 ant Selection ntation 3.2.1.1 ng and Transfer of Agroclim atic Risks Page 7 AR-UCAR-225069-CS-INDV / Component 2 - Agricultural r Individual Consult Pending Impleme Contratación de cuatro (4) C IBRD / 88670 Post Open 29,045.00 0.00 2021-04-01 2021-05-20 2021-06-10 2021-07-15 2022-01-11 isk mitigation investments ant Selection ntation onsultores Especialistas en Ri ego AR-UCAR-226535-CS-INDV / ELMI - 6 consultores/as en In Component 2 - Agricultural r Individual Consult Pending Impleme geniería Agrónoma o Técnico IBRD / 88670 Post Open 37,000.00 0.00 2021-04-01 2021-05-20 2021-06-10 2021-07-15 2022-01-11 isk mitigation investments ant Selection ntation s/as Universitarios/as en Sist emas de Riego o carreras afi nes AR-UCAR-227311-CS-INDV / Component 1 - Strengthenin Individual Consult Especialista en Ciencias Amb IBRD / 88670 g agro-climatic information s Post Open 8,714.00 0.00 Signed 2021-06-01 2021-08-02 2021-07-20 2021-08-24 2021-08-10 2021-08-25 2021-09-14 2022-03-13 ant Selection ientales-Cambio climático ystems AR-UCAR-227312-CS-INDV / Component 1 - Strengthenin Individual Consult Pending Impleme Especialista en hidrología par IBRD / 88670 g agro-climatic information s Post Open 3,112.00 0.00 2021-04-01 2021-05-20 2021-06-10 2021-07-15 2022-01-11 ant Selection ntation a cálculo de precipitación por ystems satélites AR-UCAR-227313-CS-INDV / Especialista informático con Component 1 - Strengthenin Individual Consult Pending Impleme conocimiento agropecuario p IBRD / 88670 g agro-climatic information s Post Open 6,224.00 0.00 2021-06-01 2021-07-20 2021-08-10 2021-09-14 2022-03-13 ant Selection ntation ara estudio de prefactibilidad ystems de Sistema de datos de daño s y pérdidas AR-UCAR-227314-CS-INDV / Component 2 - Agricultural r Individual Consult Cuatro (4) Consultores Espec IBRD / 88670 Post Open 29,045.00 0.00 Signed 2021-05-03 2021-04-01 2021-06-21 2021-05-20 2021-07-12 2021-06-07 2021-08-16 2022-02-12 isk mitigation investments ant Selection ialistas en Riego AR-UCAR-227315-CS-INDV / Dos (2) Consultores/as Econo Component 2 - Agricultural r Individual Consult IBRD / 88670 Post Open 19,087.00 0.00 Signed 2021-04-01 2021-04-01 2021-05-20 2021-05-20 2021-06-10 2021-06-10 2021-07-15 2022-01-11 mistas o idóneos especialista isk mitigation investments ant Selection s en evaluación económica d e proyectos AR-UCAR-227320-CS-INDV / Dos (2) Consultores/as en Ing Component 2 - Agricultural r Individual Consult IBRD / 88670 Post Open 19,087.00 0.00 Signed 2021-04-01 2021-04-01 2021-05-20 2021-05-20 2021-06-10 2021-05-24 2021-07-15 2022-01-11 eniaría Agrónoma o especiali isk mitigation investments ant Selection stas idóneos en producción r ural AR-UCAR-216777-CS-INDV / Component 3 - Agricultural E Contratación de dos consulto mergency Response Financi Individual Consult Pending Impleme res/as agronomos especialist IBRD / 88670 Post Open 20,000.00 0.00 2021-05-01 2021-06-19 2021-07-10 2021-08-14 2022-02-10 ng and Transfer of Agroclim ant Selection ntation as en horticultura para relev atic Risks amiento sector horticola BsA s (3.2.2.1) AR-UCAR-226536-NC-DIR / E Component 2 - Agricultural r Under Implement LMI - Diplomatura en Riego y IBRD / 88670 Post Direct Selection Direct 30,000.00 0.00 2021-05-03 2021-09-07 2021-05-13 2021-07-17 2022-01-13 isk mitigation investments ation Drenaje. Universidad Nacion al de Cuyo AR-UCAR-226709-CS-CDS / C Component 1 - Strengthenin onvenio CONAE - Contratació Under Implement IBRD / 88670 g agro-climatic information s Prior Direct Selection Direct 1,325,000.00 0.00 2021-06-14 2022-07-11 2021-06-24 2021-08-28 2022-02-24 n de firma consultora para d ation ystems esarrollo de productos, distri bución y capacitación AR-UCAR-240331-CS-INDV / Contratación de Analista Fun Component 1 - Strengthenin Individual Consult cional para los sistemas exist IBRD / 88670 g agro-climatic information s Post Open 7,000.00 0.00 Signed 2021-06-28 2021-05-03 2021-08-16 2021-07-23 2021-09-06 2021-07-27 2021-10-11 2022-04-09 ant Selection entes en sitio web de la Ofici ystems na de Riesgo Agropecuario ( ORA) AR-UCAR-247572-CS-INDV / ELMI - Contratación de 4 con Component 2 - Agricultural r Individual Consult Pending Impleme IBRD / 88670 Post Open 16,000.00 0.00 2021-08-11 2021-09-29 2021-10-20 2021-11-24 2022-05-23 sultores especialistas en pro isk mitigation investments ant Selection ntation gramación y/o desarrollo de aplicaciones AR-UCAR-255415-CS-INDV / Dos (2) Consultores/as Espec Component 2 - Agricultural r Individual Consult Pending Impleme ialistas Socio-ambientales pa IBRD / 88670 Post Open 16,000.00 0.00 2021-10-01 2021-11-19 2021-12-10 2022-01-14 2022-07-13 isk mitigation investments ant Selection ntation ra la Formulación de Proyect os con financiamiento intern acional AR-UCAR-255416-CS-INDV / Un (1) Consultor/a Especialist Component 2 - Agricultural r Individual Consult IBRD / 88670 Post Open 10,000.00 0.00 Signed 2021-10-01 2021-10-01 2021-11-19 2021-11-15 2021-12-10 2021-11-23 2022-01-14 2022-07-13 as en Ingeniería Civil para Fo isk mitigation investments ant Selection rmulación de Proyectos AR-UCAR-280638-CS-INDV / Un (1) consultor para Prepara ción de Plan Evaluación de I Component 4 - Project coord Individual Consult mpacto Subproyecto GIRSAR: IBRD / 88670 ination, monitoring and eval Post Open 1,700.00 0.00 Canceled 2022-03-31 2022-05-19 2022-06-09 2022-07-14 2022-09-12 ant Selection Rehabilitación de la dinámica uation hídrica del subsistema del Ar royo Baí - Zona Norte de Corr ientes AR-UCAR-286181-CS-INDV / Un (1) consultor para la prep aración del plan de evaluació Component 4 - Project coord Individual Consult n de Impacto del subproyect IBRD / 88670 ination, monitoring and eval Post Open 1,700.00 0.00 Canceled 2022-03-31 2022-05-19 2022-06-09 2022-07-14 2022-09-12 ant Selection o GIRSAR "Prevención y Cont uation rol de Incendios Forestales d e la Provincia de Mendoza" S ubcomponente 2.2 AR-UCAR-295695-CS-INDV / Component 4 - Project coord Individual Consult Under Implement Consultor para Evaluación de IBRD / 88670 ination, monitoring and eval Post Open 4,700.00 0.00 2022-06-01 2022-07-01 2022-07-20 2022-08-10 2022-09-14 2022-11-30 ant Selection ation medio término del programa uation AR-UCAR-286182-CS-INDV / Component 4 - Project coord Un (1) consultor para la prep Individual Consult Pending Impleme IBRD / 88670 ination, monitoring and eval Post Open 6,000.00 0.00 2022-03-31 2022-05-19 2022-06-01 2022-07-01 2022-10-31 aración de Plan Evaluación d ant Selection ntation uation e Impacto Subproyecto GIRS AR AR-UCAR-286856-CS-CDS / C ontratación INTA para Monito reo y muestras en el marco d Component 2 - Agricultural r Pending Impleme IBRD / 88670 Post Direct Selection Direct 334,301.00 0.00 2022-06-27 2022-07-07 2022-09-10 2023-03-09 el Subproyecto "Fortalecimie isk mitigation investments ntation nto Sanitario del rodeo bovin o provincial" de la provincia del Neuquén AR-UCAR-227319-CS-INDV / Cuatro (4) Consultores/as Es Component 2 - Agricultural r Individual Consult pecialistas Socio-ambientales IBRD / 88670 Post Open 58,174.00 0.00 Signed 2021-04-01 2021-04-01 2021-05-20 2021-05-19 2021-06-10 2021-06-09 2021-07-15 2023-03-31 isk mitigation investments ant Selection para la Formulación de Proye ctos con financiamiento inter nacional Page 8 AR-UCAR-227318-CS-INDV / Cuatro (4) Consultores/as Es Component 2 - Agricultural r Individual Consult IBRD / 88670 Post Open 38,174.00 0.00 Signed 2021-04-01 2021-04-01 2021-05-20 2021-05-20 2021-06-10 2021-06-10 2021-07-15 2022-11-30 pecialistas en Ingeniería Civil isk mitigation investments ant Selection para Formulación de Proyect os AR-UCAR-186676-CS-INDV / Contratación 3 Consultores/a Component 2 - Agricultural r Individual Consult s especialistas en conectivid IBRD / 88670 Post Open 78,000.00 0.00 Signed 2020-08-17 2021-10-01 2020-10-05 2020-11-14 2020-10-26 2020-12-04 2020-11-30 2024-12-31 isk mitigation investments ant Selection ad rural y sistemas de inform ación para formulación de pr oyectos AR-UCAR-216779-CS-INDV / Component 3 - Agricultural E Contratación de un consultor mergency Response Financi Individual Consult Pending Impleme /ra especialista en abogacía IBRD / 88670 Post Open 15,000.00 0.00 2021-04-01 2021-05-20 2021-06-10 2021-07-15 2022-01-11 ng and Transfer of Agroclim ant Selection ntation y/o administración publica pa atic Risks ra proceso de adquisición se guro. 3.2.2.3 AR-UCAR-216780-CS-INDV / Contratación de 2 consultore Component 3 - Agricultural E s/as profesionales en agrono mergency Response Financi Individual Consult mía, economía agraria o para IBRD / 88670 Post Open - National 35,000.00 0.00 Signed 2022-07-15 2021-07-15 2022-09-02 2021-09-02 2022-09-23 2021-09-23 2022-10-28 2023-04-26 ng and Transfer of Agroclim ant Selection registro de productores para atic Risks Plan Piloto de seguro Hortícol a y Florícola en la provincia d e Buenos Aires AR-UCAR-216763-CS-INDV / Component 1 - Strengthenin Individual Consult Convenio INTA - Contratració IBRD / 88670 g agro-climatic information s Post Open - National 24,000.00 0.00 Signed 2022-07-15 2021-06-01 2022-09-02 2021-07-12 2022-09-23 2021-03-16 2022-10-28 2023-04-26 ant Selection n de Administrador datos - D ystems ata Entry AR-UCAR-227316-CS-INDV / Dos (2) Consultores/as Espec Component 2 - Agricultural r Individual Consult IBRD / 88670 Post Open 19,087.00 0.00 Canceled 2021-04-01 2021-05-20 2021-06-10 2021-07-15 2022-01-11 ialistas en Formulación de pr isk mitigation investments ant Selection oyectos con financiamiento i nternacional AR-UCAR-216781-CS-INDV- / Contratación de 1 consultor E Component 1 - Strengthenin Individual Consult specialista en Comunicación IBRD / 88670 g agro-climatic information s Post Limited 20,000.00 0.00 Signed 2021-06-01 2021-05-14 2021-06-06 2021-06-09 2021-06-27 2021-06-30 2021-08-01 2022-12-31 ant Selection para difusión de acciones y a ystems lcances del Programa AR-UCAR-216762-CS-INDV- / 2 Consultores Especialistas S Component 1 - Strengthenin IG- Teledetección con formac Individual Consult IBRD / 88670 g agro-climatic information s Post Limited 14,000.00 0.00 Signed 2021-06-01 2021-08-13 2021-06-06 2021-08-18 2021-06-27 2021-08-25 2021-08-01 2022-12-30 ión en geografía o ciencias a ant Selection ystems mbientales/sociales para mo nitoreo de eventos extremos con impacto agroproductivo AR-UCAR-216762-CS-INDV / Especialista SIG- Teledetecci Component 1 - Strengthenin ón con formación en geografí Individual Consult IBRD / 88670 g agro-climatic information s Post Open 6,224.00 0.00 Canceled 2021-06-01 2021-08-02 2021-07-20 2021-08-10 2021-09-14 2022-03-13 a o ciencias ambientales/soci ant Selection ystems ales para monitoreo de event os extremos con impacto agr oproductivo AR-UCAR-227316-CS-INDV- / Cuatro (4) Consultores/as Es Component 2 - Agricultural r Individual Consult IBRD / 88670 Post Open - National 60,000.00 0.00 Signed 2022-10-14 2021-04-16 2022-12-02 2021-05-05 2022-12-23 2021-05-18 2023-01-27 2024-12-31 pecialistas en Formulación d isk mitigation investments ant Selection e proyectos con financiamien to internacional AR-UCAR-332218-CS-QCBS / Contratación directa del Insti tuto Interamericano de Coop Component 4 - Project coord eración para la Agricultura (II Pending Impleme IBRD / 88670 ination, monitoring and eval Post Direct Selection Direct - National 260,000.00 0.00 2023-01-02 2023-01-12 2023-03-18 2023-09-14 CA) para actualización del es ntation uation tudio “Las explotaciones agr opecuarias familiares en la R epública Argentina” en base a datos censales 2018 AR-UCAR-360918-CS-INDV / Component 1 - Strengthenin Contratación de un consultor Individual Consult Pending Impleme IBRD / 88670 g agro-climatic information s Post Open - National 5,000.00 0.00 2023-07-01 2023-08-19 2023-09-09 2023-10-14 2024-04-11 para el Desarrollo de una apli ant Selection ntation ystems cación móvil de agrometeoro logía para INTA AR-UCAR-368710-CS-INDV / Component 4 - Project coord Individual Consult Pending Impleme Consultor/a técnica en gestió IBRD / 88670 ination, monitoring and eval Post Limited 6,530.00 0.00 2023-06-22 2023-06-27 2023-07-18 2023-08-22 2024-02-18 ant Selection ntation n financiera uation AR-UCAR-368893-CS-INDV / Component 4 - Project coord Individual Consult Pending Impleme IBRD / 88670 Post Limited 6,560.00 0.00 2023-06-23 2023-06-28 2023-07-19 2023-08-23 2024-02-19 Consultor/a técnica en derec ination, monitoring and eval ant Selection ntation ho uation AR-UCAR-368900-CS-INDV / Component 4 - Project coord 3 Consultores/as técnicos/as Individual Consult Pending Impleme IBRD / 88670 ination, monitoring and eval Post Limited 17,400.00 0.00 2023-06-23 2023-06-28 2023-07-19 2023-08-23 2024-02-19 en procesos de contratacione ant Selection ntation uation s y gestiones administrativas AR-UCAR-368935-CS-INDV / Component 4 - Project coord Individual Consult Pending Impleme Consultor/a especialista en G IBRD / 88670 ination, monitoring and eval Post Limited 15,370.00 0.00 2023-06-23 2023-06-28 2023-07-19 2023-08-23 2024-02-19 ant Selection ntation estión presupuestaria uation AR-UCAR-368940-CS-INDV / Component 4 - Project coord Individual Consult Pending Impleme 2 Consultores/as técnicas en IBRD / 88670 ination, monitoring and eval Post Limited 10,870.00 0.00 2023-06-23 2023-06-28 2023-07-19 2023-08-23 2024-02-19 ant Selection ntation gestión presupuestaria uation AR-UCAR-368941-CS-INDV / Component 4 - Project coord Individual Consult Pending Impleme Consultor/a técnica en gestió IBRD / 88670 ination, monitoring and eval Post Limited 4,900.00 0.00 2023-06-23 2023-06-28 2023-07-19 2023-08-23 2024-02-19 ant Selection ntation n de desembolsos y subejecu uation ciones AR-UCAR-368944-CS-INDV / Component 4 - Project coord Individual Consult Pending Impleme Consultor/a técnico en Comu IBRD / 88670 ination, monitoring and eval Post Limited 6,000.00 0.00 2023-06-23 2023-06-28 2023-07-19 2023-08-23 2024-02-19 ant Selection ntation nicación y Difusión de proyec uation tos AR-UCAR-368946-CS-INDV / Component 4 - Project coord Individual Consult Pending Impleme 3 Consultores/as técnicos/as IBRD / 88670 ination, monitoring and eval Post Limited 19,610.00 0.00 2023-06-23 2023-06-28 2023-07-19 2023-08-23 2024-02-19 ant Selection ntation en procesos de adquisiciones uation Page 9 Sustainable Recovery of Landscapes (P175669) Requesting Unit: LCC7C, Responsible Unit: SLCEN/LCRVP Lending Instrument: Investment Project Financing Net commitment: 60 M PROCUREMENT Argentina : Sustainable Recovery of Landscapes and Livelihoods in Argentina Project PLAN General Information Country: Argentina 2022-03-28 Bank’s Approval Date of the Original Procurement Plan: 2023-06-06 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P175669 GPN Date: 2022-05-03 Project Name: Sustainable Recovery of Landscapes and Livelihoods in Argentina Project Loan / Credit No: IBRD / 93350 Administración de Parques Nacionales Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned AR-APN-283682-CW-RFB / R Component 1: Improved Cli National Procure econstruccion ex Hostería pa mate Resilience and Manage ment Document - Single Stage - One E Pending Imp 2024-03-2 ra transformarla en un Centr IBRD / 93350 ment of Selected Conservati Post Request for Bids Open - National 1 Envelope proce 450,000.00 0.00 2023-06-10 2023-06-15 2023-07-27 2023-08-26 2023-09-30 nvelope lementation 8 o de Capacitación e investiga on and Production Landscap ss (Non Bank-SPD ción. Parque Nacional El Rey, es and Seascapes ) Provincia de Salta National Procure AR-APN-284345-CW-RFB / C Component 1: Improved Cli ment Document - onstruccion de Centro de Visi mate Resilience and Manage Single Stage - One E Pending Imp 2024-06-0 IBRD / 93350 Post Request for Bids Open - National 1 Envelope proce 1,200,000.00 0.00 2023-02-10 2023-02-15 2023-03-29 2023-04-28 2023-06-02 tantes. Parque Nacional Tala ment of Selected Conservati nvelope lementation 3 ss (Non Bank-SPD mpaya, Provincia de La Rioja on and Production Landscap ) es and Seascapes National Procure AR-APN-284081-CW-RFB / C Component 1: Improved Cli ment Document - onstruccion Puente Arroyo lo mate Resilience and Manage Single Stage - One E Pending Imp 2024-10-3 IBRD / 93350 Post Request for Bids Open - National 1 Envelope proce 1,800,000.00 0.00 2023-06-13 2023-06-18 2023-07-30 2023-08-29 2023-10-03 s Naranjos en ruta provincial ment of Selected Conservati nvelope lementation 1 ss (Non Bank-SPD N°20. Parque Nacional El Rey on and Production Landscap ) , Provincia de Salta es and Seascapes National Procure AR-APN-284084-CW-RFB / 2 Component 1: Improved Cli ment Document - Viviendas. (240 m2). (Obra n mate Resilience and Manage Single Stage - One E Pending Imp 2023-07-0 IBRD / 93350 Post Request for Bids Open - National 1 Envelope proce 360,000.00 0.00 2022-09-12 2022-09-17 2022-10-29 2022-11-28 2023-01-02 ueva destinada a vivienda. R ment of Selected Conservati nvelope lementation 1 ss (Non Bank-SPD eserva Nacional Pizarro on and Production Landscap ) es and Seascapes National Procure AR-APN-284336-CW-RFB / In Component 1: Improved Cli ment Document - tendencia y galpón en Ing. Ju mate Resilience and Manage Single Stage - One E Pending Imp 2024-03-0 IBRD / 93350 Post Request for Bids Open - National 1 Envelope proce 375,000.00 0.00 2022-11-15 2022-11-20 2023-01-01 2023-01-31 2023-03-07 arez. (250 m2). (Obra nueva ment of Selected Conservati nvelope lementation 8 ss (Non Bank-SPD destinada a sede administrat on and Production Landscap ) iva. es and Seascapes National Procure Component 1: Improved Cli AR-APN-284337-CW-RFB / 2 ment Document - mate Resilience and Manage Single Stage - One E Pending Imp 2024-03-2 Seccionales. (240 m2) Parqu IBRD / 93350 Post Request for Bids Open - National 1 Envelope proce 360,000.00 0.00 2022-11-14 2022-11-19 2022-12-31 2023-01-30 2023-03-06 ment of Selected Conservati nvelope lementation 9 e Nacional Calilegua ss (Non Bank-SPD on and Production Landscap ) es and Seascapes National Procure AR-APN-284339-CW-RFB / C Component 1: Improved Cli ment Document - onstrucción Complejo (Centr mate Resilience and Manage Single Stage - One E Pending Imp 2024-10-3 IBRD / 93350 Post Request for Bids Open - National 1 Envelope proce 400,000.00 0.00 2023-07-01 2023-07-06 2023-08-17 2023-09-16 2023-10-21 o de Visitantes Seccionales y ment of Selected Conservati nvelope lementation 1 ss (Non Bank-SPD sanitarios) en PN Traslasierra on and Production Landscap ) es and Seascapes National Procure AR-APN-284207-CW-RFB / C Component 1: Improved Cli ment Document - onstrucción Complejo (Centr mate Resilience and Manage Single Stage - One E Pending Imp 2024-10-2 IBRD / 93350 Post Request for Bids Open - National 1 Envelope proce 400,000.00 0.00 2023-07-01 2023-07-06 2023-08-17 2023-09-16 2023-10-21 o de Visitantes Seccionales y ment of Selected Conservati nvelope lementation 1 ss (Non Bank-SPD sanitarios) en PN Aconquija on and Production Landscap ) es and Seascapes AR-APN-284165-CW-RFB / C Component 1: Improved Cli National Procure onstruccion de galpón de apo mate Resilience and Manage ment Document - Single Stage - One E Pending Imp 2024-06-1 yo a emergencias forestales ( IBRD / 93350 ment of Selected Conservati Post Request for Bids Open - National 1 Envelope proce 480,000.00 0.00 2023-02-18 2023-02-23 2023-04-06 2023-05-06 2023-06-10 nvelope lementation 0 ICE).(400 m2). Parque Nacion on and Production Landscap ss (Non Bank-SPD al Tierra del Fuego, Provincia es and Seascapes ) de Tierra del Fuego AR-APN-284346-CW-RFB / Ac Component 1: Improved Cli National Procure cesibilidad y puesta en valor mate Resilience and Manage ment Document - Single Stage - One E Pending Imp 2023-08-2 del complejo sanitario en Isla IBRD / 93350 ment of Selected Conservati Post Request for Bids Open - National 1 Envelope proce 400,000.00 0.00 2022-05-02 2022-05-07 2022-06-18 2022-07-18 2022-08-22 nvelope lementation 2 Victoria en el Parque Naciona on and Production Landscap ss (Non Bank-SPD l Nahuel Huapi.(80 m2) es and Seascapes ) AR-APN-283692-CW-RFB / R Component 1: Improved Cli National Procure eparación y puesta en valor mate Resilience and Manage ment Document - Single Stage - One E Pending Imp 2024-11-0 Palacio Haedo, como Centro IBRD / 93350 ment of Selected Conservati Post Request for Bids Open - National 1 Envelope proce 2,200,000.00 0.00 2023-07-08 2023-07-13 2023-08-24 2023-09-23 2023-10-28 nvelope lementation 4 de Visitantes Multimedia. Ciu on and Production Landscap ss (Non Bank-SPD dad Autónoma de Buenos Air es and Seascapes ) es AR-APN-283685-CW-RFB / R Component 1: Improved Cli National Procure efacción y puesta en valor de mate Resilience and Manage ment Document - Single Stage - One E Pending Imp 2023-03-2 2 Destacamentos: El Aibal y IBRD / 93350 ment of Selected Conservati Post Request for Bids Open - National 1 Envelope proce 300,000.00 0.00 2022-06-03 2022-06-08 2022-07-20 2022-08-19 2022-09-23 nvelope lementation 2 La Portada. Parque Nacional on and Production Landscap ss (Non Bank-SPD Copo, Provincia de Santiago es and Seascapes ) del Estero National Procure AR-APN-303251-CW-RFB / C Component 1: Improved Cli ment Document - onstrucción de Galpón de Ser mate Resilience and Manage Single Stage - One E Pending Imp 2023-07-0 IBRD / 93350 Post Request for Bids Open - National 1 Envelope proce 380,000.00 0.00 2022-07-22 2022-07-27 2022-09-07 2022-10-07 2022-11-11 vicios Generales para el Parq ment of Selected Conservati nvelope lementation 9 ss (Non Bank-SPD ue Nacional Ciervo de los Pa on and Production Landscap ) ntanos es and Seascapes AR-APN-284341-CW-RFB - 2 Component 1: Improved Cli National Procure / Construcción de galpón de mate Resilience and Manage ment Document - Single Stage - One E 2023-12-1 apoyo a emergencias foresta IBRD / 93350 ment of Selected Conservati Post Request for Bids Open - National 1 Envelope proce 1,874,000.00 0.00 Canceled 2022-11-25 2022-12-06 2022-12-09 2023-01-09 2023-02-08 2023-03-15 nvelope 2 les (ICE) El Chaltén. Parque N on and Production Landscap ss (Non Bank-SPD acional Los Glaciares, Provinc es and Seascapes ) ia de Santa Cruz, AR-APN-284341-CW-RFB / C Component 1: Improved Cli National Procure onstruccion de galpón de apo mate Resilience and Manage ment Document - Single Stage - One E 2023-09-1 yo a emergencias forestales ( IBRD / 93350 ment of Selected Conservati Post Request for Bids Open - National 1 Envelope proce 1,500,000.00 0.00 Canceled 2022-05-16 2022-05-21 2022-07-02 2022-08-01 2022-09-05 nvelope 1 ICE) El Chaltén. Parque Nacio on and Production Landscap ss (Non Bank-SPD nal Los Glaciares, Provincia d es and Seascapes ) e Santa Cruz AR-APN-284341-CW-RFB – 3 Component 1: Improved Cli National Procure / Construcción de galpón de mate Resilience and Manage ment Document - Single Stage - One E Under Imple 2024-02-0 apoyo a emergencias foresta IBRD / 93350 ment of Selected Conservati Post Request for Bids Open - National 1 Envelope proce 1,874,000.00 0.00 2023-01-05 2022-11-11 2023-02-04 2023-03-06 2023-03-23 2023-04-05 2023-05-10 nvelope mentation 4 les (ICE) El Chaltén. Parque N on and Production Landscap ss (Non Bank-SPD acional Los Glaciares, Provinc es and Seascapes ) ia de Santa Cruz AR-APN-284343-CW-RFB / C Component 1: Improved Cli National Procure onstruccion de muelle cabec mate Resilience and Manage ment Document - Single Stage - One E Pending Imp 2024-07-0 era norte (60 m2). (Refacción IBRD / 93350 ment of Selected Conservati Post Request for Bids Open - National 1 Envelope proce 3,500,000.00 0.00 2023-04-03 2023-04-08 2023-05-08 2023-06-07 2023-07-12 nvelope lementation 6 de obra de uso público.Lago on and Production Landscap ss (Non Bank-SPD Puelo, Provincia de Chubut es and Seascapes ) Page 1 GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 1: Improved Cli AR-APN-284335-GO-RFB / Es mate Resilience and Manage Single Stage - One E Pending Impl taciones meteorológicas para IBRD / 93350 Post Request for Bids Open - National 140,000.00 0.00 2023-04-10 2023-04-15 2023-05-27 2023-06-26 2023-07-31 2023-12-29 ment of Selected Conservati nvelope ementation áreas protegidas on and Production Landscap es and Seascapes Component 1: Improved Cli AR-APN-284330-GO-RFB / La mate Resilience and Manage Single Stage - One E IBRD / 93350 Post Request for Bids Open - National 900,000.00 0.00 Canceled 2022-05-30 2022-10-21 2022-06-04 2022-07-16 2022-12-02 2022-08-15 2022-12-22 2022-09-19 2023-02-28 nchas ment of Selected Conservati nvelope on and Production Landscap es and Seascapes AR-APN-284215-GO-RFB / Ta Component 1: Improved Cli nques cisterna, kits de fuego mate Resilience and Manage Single Stage - One E IBRD / 93350 Post Request for Bids Open - National 400,000.00 0.00 Signed 2022-08-13 2022-11-01 2022-08-18 2022-09-29 2022-12-26 2022-10-29 2023-02-04 2022-12-03 2023-04-04 , Indumentaria, calzado y mo ment of Selected Conservati nvelope chilas para incendios forestal on and Production Landscap es es and Seascapes AR-APN-284062-GO-RFB / M Component 1: Improved Cli ódulos habitacionales/oficina/ mate Resilience and Manage Single Stage - One E Pending Impl IBRD / 93350 Post Request for Bids Open - National 1,200,000.00 0.00 2022-07-20 2022-07-25 2022-09-05 2022-10-05 2022-11-09 2023-03-09 otros usos para áreas protegi ment of Selected Conservati nvelope ementation das on and Production Landscap es and Seascapes AR-APN-284327-GO-RFQ / So Component 3: Project Manag Request for Quota Single Stage - One E Pending Impl IBRD / 93350 Post Open - National 50,000.00 0.00 2022-08-27 2022-10-22 2023-01-23 ftware para monitoreo ement, Monitoring, Evaluatio tions nvelope ementation n Component 1: Improved Cli AR-APN-284340-GO-RFB / Eq mate Resilience and Manage Single Stage - One E IBRD / 93350 Post Request for Bids Open - National 384,652.00 0.00 Signed 2022-05-10 2022-06-16 2022-05-15 2022-06-26 2022-10-11 2022-07-26 2022-11-24 2022-08-30 2022-12-30 uipamiento informático ment of Selected Conservati nvelope on and Production Landscap es and Seascapes AR-APN-284182-GO-RFQ / M Component 3: Project Manag Request for Quota Single Stage - One E Under Imple obiliario Coordinación Genera IBRD / 93350 ement, Monitoring, Evaluatio Post Open - National 41,000.00 0.00 2022-09-26 2022-11-21 2023-03-21 tions nvelope mentation l del Proyecto n AR-APN-283718-GO-RFB / Ve hículos para fortalecimiento Component 2: Promoting Su de la APN. Vehículos asignad Single Stage - One E IBRD / 93350 stainable Livelihoods Across Prior Request for Bids Open - National 4,200,000.00 0.00 Signed 2022-09-19 2022-10-31 2022-09-24 2022-10-24 2022-12-16 2022-11-13 2023-02-23 2022-12-18 2023-05-31 2023-05-17 os a la implementación del C nvelope Selected Landscapes omponente 2, Monitoreo y Ev aluación y aplicación de Está ndares Ambientales y Sociale s AR-APN-331918-GO-RFB / Eq uipos de Comunicación y de Component 1: Improved Cli Herramientas p/ combatir Inc mate Resilience and Manage Single Stage - One E Under Imple endios (Kit Repetidoras, Kit B IBRD / 93350 ment of Selected Conservati Post Request for Bids Open - National 615,000.00 0.00 2023-01-10 2022-12-16 2023-01-15 2023-02-26 2023-02-27 2023-03-28 2023-05-02 2023-10-29 nvelope mentation ases, Handys y Pecheras par on and Production Landscap a Handys. Motosierra,Desmal es and Seascapes ezadora,Podadoras de Altura, Sopladora) AR-APN-346413-GO-RFQ / In Component 2: Promoting Su sumos de Comunicación a tr Request for Quota Single Stage - One E IBRD / 93350 stainable Livelihoods Across Post Limited 9,900.00 0.00 Signed 2023-03-06 2023-03-13 2023-03-14 2023-03-17 avés de materiales gráficos p tions nvelope Selected Landscapes ara representar la identidad del Proyecto AR-APN-284182-GO-RFQ-2 / Component 3: Project Manag Request for Quota Single Stage - One E Mobiliario Coordinación Gene IBRD / 93350 ement, Monitoring, Evaluatio Post Open - National 41,000.00 0.00 Signed 2022-05-15 2022-07-10 2022-11-07 tions nvelope ral del Proyecto n Component 1: Improved Cli AR-APN-356809-GO-RFB / Tr mate Resilience and Manage Single Stage - One E Under Imple actor e Implementos (Hoja Ni IBRD / 93350 Post Request for Bids Open - National 195,900.00 0.00 2023-04-24 2023-04-12 2023-04-29 2023-05-29 2023-06-22 2023-06-28 2023-08-02 2023-11-30 ment of Selected Conservati nvelope mentation veladora y Rastra de Arado) on and Production Landscap es and Seascapes Component 1: Improved Cli AR-APN-358215-GO-RFB / E mate Resilience and Manage Single Stage - One E Under Imple mbarcaciones Fluviales - Lan IBRD / 93350 Post Request for Bids Open - National 1,400,000.00 0.00 2023-04-28 2023-04-21 2023-05-03 2023-06-02 2023-07-02 2023-08-06 2023-12-04 ment of Selected Conservati nvelope mentation chas on and Production Landscap es and Seascapes Component 1: Improved Cli AR-APN-322544-GO-RFB / Ad mate Resilience and Manage Single Stage - One E Under Imple quisición de drones (vehículo IBRD / 93350 Post Request for Bids Open - National 800,000.00 0.00 2023-06-02 2023-05-17 2023-06-07 2023-07-07 2023-08-07 2023-09-11 2023-11-10 ment of Selected Conservati nvelope mentation s aéreos no tripulados) on and Production Landscap es and Seascapes NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual AR-APN-345389-NC-RFQ / Ac Component 2: Promoting Su Request for Quota Single Stage - One E Pending Impl tividad territorial Paisaje Mon IBRD / 93350 stainable Livelihoods Across Post Limited 9,900.00 0.00 2023-03-13 2023-03-22 2023-04-03 tions nvelope ementation te de Sierras y Bolsones - La Selected Landscapes Rioja CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual AR-APN-283650-CS-LCS / Ela Component 1: Improved Cli boración de Proyecto Ejecuti mate Resilience and Manage Least Cost Selecti Pending Impleme vo Complejos (Centro de Visit IBRD / 93350 ment of Selected Conservati Post Open - National 105,000.00 0.00 2022-06-30 2022-07-15 2022-08-08 2022-09-05 2022-09-06 2022-10-11 2022-11-09 2023-03-09 on ntation antes Seccionales y sanitario on and Production Landscap s) en PN Traslasierra y PN Ac es and Seascapes onquija Component 1: Improved Cli AR-APN-284348-CS-CQS / Di mate Resilience and Manage Consultant Qualifi Pending Impleme seño de Pasafauna a diversa IBRD / 93350 Post Open - National 25,000.00 0.00 2022-06-01 2022-06-22 2022-08-05 2022-09-04 2022-10-09 2023-10-09 ment of Selected Conservati cation Selection ntation s escalas on and Production Landscap es and Seascapes AR-APN-284256-CS-CQS / El Component 1: Improved Cli aboración de Proyecto Ejecut mate Resilience and Manage Least Cost Selecti Pending Impleme ivo del Centro de Visitantes y IBRD / 93350 ment of Selected Conservati Post Open - National 88,000.00 0.00 2022-05-23 2022-06-13 2022-07-27 2022-08-24 2022-09-23 2022-10-28 2022-12-02 2023-05-01 on ntation Estacionamienmto. Parque N on and Production Landscap acional Talampaya, Provincia es and Seascapes de La Rioja Page 2 Component 1: Improved Cli AR-APN-283698-CS-CQS / Pl mate Resilience and Manage Consultant Qualifi Pending Impleme an de Gestión Islas de Santa IBRD / 93350 Post Open - National 40,000.00 0.00 2022-08-29 2022-09-19 2022-11-02 2022-12-02 2022-12-17 2024-01-16 ment of Selected Conservati cation Selection ntation Fe, Provincia de Santa Fe on and Production Landscap es and Seascapes AR-APN-283649-CS-CQS / Pl Component 1: Improved Cli an de Gestión Parque Nacion mate Resilience and Manage Consultant Qualifi Pending Impleme IBRD / 93350 Post Open - National 40,000.00 0.00 2022-08-29 2022-09-19 2022-11-02 2022-12-02 2023-01-06 2024-01-01 al Aconquija de la Provincia d ment of Selected Conservati cation Selection ntation e Tucumán on and Production Landscap es and Seascapes AR-APN-346422-CS-CQS / Pl Component 1: Improved Cli an de Manejo del Fuego Parq mate Resilience and Manage Consultant Qualifi Pending Impleme ue Nacional de Pre Delta, Par IBRD / 93350 ment of Selected Conservati Post Open - National 45,000.00 0.00 2023-05-02 2023-05-23 2023-07-06 2023-08-05 2023-09-01 2024-08-31 cation Selection ntation que Nacional de Islas de Sant on and Production Landscap a Fe y Parque Nacional Cierv es and Seascapes o de los Pantanos AR-APN-284344-CS-CQS / Pl Component 1: Improved Cli an de Manejo del Fuego Parq mate Resilience and Manage Consultant Qualifi ue Nacional de Pre Delta, Par IBRD / 93350 ment of Selected Conservati Post Open - National 40,000.00 0.00 Canceled 2022-06-25 2022-07-16 2022-08-29 2022-09-28 2022-11-02 2023-11-02 cation Selection que Nacional de Islas de Sant on and Production Landscap a Fe y Parque Nacional Cierv es and Seascapes o de los Pantanos AR-APN-346423-CS-CQS / Pl Component 1: Improved Cli an de Gestión Área Marina Pr mate Resilience and Manage Consultant Qualifi Pending Impleme IBRD / 93350 Post Open - National 40,000.00 0.00 2023-04-17 2023-05-08 2023-06-01 2023-06-21 2023-07-01 2024-06-30 otegida Yaganes - Tierra del ment of Selected Conservati cation Selection ntation Fuego on and Production Landscap es and Seascapes AR-APN-346424-CS-CQS / Pl Component 1: Improved Cli an de Gestión Parque Nacion mate Resilience and Manage Consultant Qualifi Pending Impleme IBRD / 93350 Post Open - National 30,000.00 0.00 2023-04-03 2023-04-24 2023-06-07 2023-06-30 2023-08-01 2024-07-31 al Islote Lobos, Provincia de ment of Selected Conservati cation Selection ntation Río Negro on and Production Landscap es and Seascapes AR-APN-364439-CS-CQS / Pr Component 3: Project Manag Least Cost Selecti Pending Impleme oducción de Contenidos y Ac IBRD / 93350 ement, Monitoring, Evaluatio Post Open - National 164,000.00 0.00 2023-06-06 2023-06-27 2023-07-27 2023-08-24 2023-09-13 2023-10-18 2023-11-02 2024-11-01 on ntation ciones Comunicacionales p/ e n l Proyecto INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 1: Improved Cli AR-APN-283648-CS-CQS / Pl mate Resilience and Manage Individual Consult Pending Impleme an de Gestión RN Pizarro, Pro IBRD / 93350 Post Open 30,000.00 0.00 2022-06-15 2022-08-03 2022-08-24 2022-09-28 2023-09-28 ment of Selected Conservati ant Selection ntation vincia de Salta on and Production Landscap es and Seascapes AR-APN-283699-CS-INDV / Pl Component 1: Improved Cli an de Uso Público Parque Na mate Resilience and Manage Individual Consult Pending Impleme IBRD / 93350 Post Open 30,000.00 0.00 2022-06-21 2022-08-09 2022-08-30 2022-09-23 2023-10-31 cional Talampaya, Provincia ment of Selected Conservati ant Selection ntation de La Rioja on and Production Landscap es and Seascapes AR-APN-284063-CS-INDV / Pl Component 1: Improved Cli an de Uso Público Parque Na mate Resilience and Manage Individual Consult Pending Impleme IBRD / 93350 Post Open 30,000.00 0.00 2023-06-22 2023-08-10 2023-08-31 2023-09-30 2024-10-31 cional Los Alerces, Provincia ment of Selected Conservati ant Selection ntation de Chubut on and Production Landscap es and Seascapes AR-APN-283658-CS-INDV / Pl Component 1: Improved Cli an de Manejo del Fuego Rese mate Resilience and Manage Individual Consult Pending Impleme IBRD / 93350 Post Open 30,000.00 0.00 2022-06-26 2022-08-14 2022-09-04 2022-10-09 2023-10-31 rva de Biósfera Andino Nor P ment of Selected Conservati ant Selection ntation atagónica (RBANP) on and Production Landscap es and Seascapes AR-APN-283659-CS-INDV / Pl Component 1: Improved Cli an de Gestión Corredor Interj mate Resilience and Manage Individual Consult Pending Impleme urisdiccional Parque Nacional IBRD / 93350 ment of Selected Conservati Post Open 30,000.00 0.00 2022-04-13 2022-06-01 2022-06-16 2022-07-21 2023-07-25 ant Selection ntation Lago Puelo, Parque Provincial on and Production Landscap y Reserva de Usos Múltiples es and Seascapes Río Turbio (PRPRT) AR-APN-284142-CS-INDV / A Component 1: Improved Cli nálisis de la cadena de valor mate Resilience and Manage Individual Consult Pending Impleme IBRD / 93350 Post Open 10,000.00 0.00 2022-05-31 2022-07-19 2022-08-09 2022-09-01 2022-12-31 de turismo comunitario y de ment of Selected Conservati ant Selection ntation naturaleza on and Production Landscap es and Seascapes AR-APN-284204-CS-INDV / A Component 1: Improved Cli nálisis de la cadena de valor mate Resilience and Manage Individual Consult Pending Impleme IBRD / 93350 Post Open 10,000.00 0.00 2022-05-31 2022-07-19 2022-08-09 2022-09-30 2022-12-31 de apicultura y meliponicultu ment of Selected Conservati ant Selection ntation ra on and Production Landscap es and Seascapes Component 1: Improved Cli AR-APN-284195-CS-INDV / A mate Resilience and Manage Individual Consult Pending Impleme nálisis de la cadena de valor IBRD / 93350 Post Open 10,000.00 0.00 2022-05-31 2022-07-19 2022-08-09 2022-09-01 2023-02-28 ment of Selected Conservati ant Selection ntation ganadería sustentable on and Production Landscap es and Seascapes AR-APN-283717-CS-INDV / A Component 3: Project Manag nálisis de la cadena de valor Individual Consult Pending Impleme IBRD / 93350 ement, Monitoring, Evaluatio Post Open 10,000.00 0.00 2022-05-31 2022-07-19 2022-08-09 2022-09-01 2023-02-28 de pesquería artesanal en el ant Selection ntation n Delta del Paraná AR-APN-283702-CS-CDS / Re Component 3: Project Manag IBRD / 93350 Post Direct Selection Direct 26,250.00 0.00 Signed 2022-04-08 2022-08-02 2022-04-18 2022-09-07 2022-06-01 2027-05-31 sponsable área financiera ement, Monitoring, Evaluatio n AR-APN-284307-CS-CDS / Re Component 3: Project Manag IBRD / 93350 Post Direct Selection Direct 26,250.00 0.00 Signed 2022-04-08 2022-08-02 2022-04-18 2022-09-07 2022-06-12 2027-06-30 sponsable área adquisiciones ement, Monitoring, Evaluatio n AR-APN-284326-CS-CDS / Re Component 3: Project Manag IBRD / 93350 Post Direct Selection Direct 26,250.00 0.00 Signed 2022-04-04 2022-08-02 2022-04-14 2022-09-07 2022-06-08 2027-05-31 sponsable Monitoreo y Evalu ement, Monitoring, Evaluatio ación n AR-APN-283674-CS-INDV / Di Component 2: Promoting Su Individual Consult ecinueve Promotores territori IBRD / 93350 stainable Livelihoods Across Post Open 342,000.00 0.00 Canceled 2022-06-01 2022-07-20 2022-08-10 2022-09-01 2027-05-31 ant Selection ales para distintos Paisajes y Selected Landscapes Corredores AR-APN-284318-CS-CDS / Re Component 3: Project Manag IBRD / 93350 Post Direct Selection Direct 26,250.00 0.00 Canceled 2022-04-08 2022-04-18 2022-06-12 2027-05-31 sponsable Gestión Ambiental ement, Monitoring, Evaluatio n AR-APN-284240-CS-INDV / E Component 3: Project Manag Individual Consult IBRD / 93350 Post Open 22,500.00 0.00 Canceled 2022-03-31 2022-05-19 2022-06-09 2022-07-29 2027-05-31 specialista contable ement, Monitoring, Evaluatio ant Selection n AR-APN-284155-CS-INDV / E Component 3: Project Manag Individual Consult IBRD / 93350 Post Open 22,500.00 0.00 Canceled 2022-04-29 2022-06-17 2022-07-08 2022-08-01 2027-05-31 specialista en gestión ambie ement, Monitoring, Evaluatio ant Selection ntal n Page 3 AR-APN-283706-CS-INDV / E Component 3: Project Manag Individual Consult specialista en comunicación IBRD / 93350 ement, Monitoring, Evaluatio Post Open 22,500.00 0.00 Canceled 2022-04-29 2022-06-17 2022-07-08 2022-08-12 2027-05-31 ant Selection y manejo de quejas n AR-APN-284303-CS-INDV / S Component 3: Project Manag Individual Consult ubcoordinador a cargo del ta IBRD / 93350 ement, Monitoring, Evaluatio Post Open 28,500.00 0.00 Canceled 2022-03-31 2022-05-19 2022-06-09 2022-07-01 2027-05-31 ant Selection blero de control n AR-APN-283704-CS-INDV / E Component 3: Project Manag Individual Consult IBRD / 93350 Post Open 22,500.00 0.00 Canceled 2022-03-28 2022-05-16 2022-06-06 2022-07-01 2027-05-31 specialista en RRNAT ement, Monitoring, Evaluatio ant Selection n AR-APN-284135-CS-INDV / Ci nco Referentes de Salvaguar Component 3: Project Manag das Sociales y Subproyectos: Individual Consult IBRD / 93350 ement, Monitoring, Evaluatio Post Open 95,000.00 0.00 Canceled 2022-04-29 2022-06-17 2022-07-08 2022-08-01 2027-05-31 Uno para el Centro, Uno para ant Selection n la Patagonia Norte; Uno para la Patagonia Austral; Uno par a el NEA y Uno para el NOA AR-APN-283711-CS-INDV / Ci nco Referentes Salvaguardas Ambientales, Planes de Gesti Component 3: Project Manag ón y Proyectos de Control de Individual Consult IBRD / 93350 ement, Monitoring, Evaluatio Post Open 95,000.00 0.00 Canceled 2022-04-29 2022-06-17 2022-07-08 2022-08-01 2027-05-31 Especies Exóticas Invasoras: ant Selection n uno para el NOA, uno para el Centro, uno para el NEA, uno para la Patagonia Austral y u no para la Patagonia Norte AR-APN-309136-CS-INDV / S Component 3: Project Manag Individual Consult IBRD / 93350 Post Limited 28,500.00 0.00 Signed 2022-08-25 2022-08-02 2022-08-30 2022-11-01 2022-09-20 2022-11-03 2022-10-25 2027-05-31 ubcoordinador General del Pr ement, Monitoring, Evaluatio ant Selection oyecto n AR-APN-309092-CS-INDV / E Component 3: Project Manag Individual Consult IBRD / 93350 Post Limited 22,500.00 0.00 Signed 2022-08-25 2022-07-27 2022-08-30 2022-09-06 2022-09-20 2022-09-09 2022-10-25 2027-05-31 specialista en Evaluación Am ement, Monitoring, Evaluatio ant Selection biental n AR-APN-309135-CS-INDV / E Component 3: Project Manag Individual Consult Pending Impleme IBRD / 93350 Post Limited 22,500.00 0.00 2022-08-11 2022-08-16 2022-09-06 2022-10-11 2027-05-31 specialista en Contabilidad ement, Monitoring, Evaluatio ant Selection ntation n AR-APN-309143-CS-INDV / R Component 3: Project Manag Individual Consult Under Implement esponsable de Gestión de Rie IBRD / 93350 ement, Monitoring, Evaluatio Post Limited 26,250.00 0.00 2022-08-25 2022-08-02 2022-08-30 2022-09-20 2022-10-25 2027-05-31 ant Selection ation sgos e Impactos Ambientales n AR-APN-309132-CS-INDV / E Component 2: Promoting Su Individual Consult specialista en Apoyo de Com IBRD / 93350 stainable Livelihoods Across Post Limited 25,500.00 0.00 Canceled 2022-08-31 2022-09-05 2022-09-26 2022-10-31 2027-06-06 ant Selection petencia. Selected Landscapes AR-APN-309124-CS-INDV / Ci Component 3: Project Manag Individual Consult nco Especialistas Ambientale IBRD / 93350 ement, Monitoring, Evaluatio Post Limited 95,000.00 0.00 Under Review 2022-08-25 2022-10-03 2022-08-30 2022-09-20 2022-10-25 2027-05-31 ant Selection s Regionales n AR-APN-309134-CS-INDV / E Component 3: Project Manag specialista en Manejo y Apro Individual Consult Under Implement IBRD / 93350 ement, Monitoring, Evaluatio Post Limited 22,500.00 0.00 2022-08-25 2023-01-26 2022-08-30 2023-03-14 2022-09-20 2023-06-14 2022-10-25 2027-05-31 vechamiento Sostenible de R ant Selection ation n ecursos Naturales AR-APN-309131-CS-INDV / E Component 3: Project Manag Individual Consult specialista en Comunicación IBRD / 93350 ement, Monitoring, Evaluatio Post Limited 22,500.00 0.00 Under Review 2022-08-25 2022-08-02 2022-08-30 2022-09-20 2022-10-25 2027-05-31 ant Selection y Manejo de Reclamos. n AR-APN-309081-CS-INDV / Ci Component 3: Project Manag Individual Consult IBRD / 93350 Post Limited 95,000.00 0.00 Under Review 2022-08-25 2022-10-03 2022-08-30 2022-09-20 2022-10-25 2027-05-31 nco Especialistas Sociales Re ement, Monitoring, Evaluatio ant Selection gionales n AR-APN-312214-CS-INDV / E Component 3: Project Manag Individual Consult specialista en Comunicación IBRD / 93350 ement, Monitoring, Evaluatio Post Limited 22,500.00 0.00 Signed 2022-08-25 2022-07-27 2022-08-30 2022-09-26 2022-09-20 2022-09-29 2022-10-25 2027-05-31 ant Selection Estratégica n AR-APN-283701-CS-INDV / E Component 3: Project Manag Individual Consult IBRD / 93350 Post Open 22,500.00 0.00 Canceled 2022-04-29 2022-06-07 2022-06-28 2022-08-01 2027-05-31 specialista en comunicación ement, Monitoring, Evaluatio ant Selection n AR-APN-284277-CS-INDV / C Component 3: Project Manag Individual Consult IBRD / 93350 Post Open 30,000.00 0.00 Canceled 2022-03-21 2022-05-04 2022-05-09 2022-05-30 2022-06-08 2027-06-07 oordinador/Responsable del ement, Monitoring, Evaluatio ant Selection Proyecto n AR-APN-312235-CS-INDV / R Component 2: Promoting Su Individual Consult esponsable Técnico del Com IBRD / 93350 stainable Livelihoods Across Post Limited 27,000.00 0.00 Signed 2022-08-25 2022-09-16 2022-08-30 2022-09-21 2022-09-20 2022-09-27 2022-10-25 2027-05-31 ant Selection ponente 2 Selected Landscapes Component 2: Promoting Su AR-APN-284272-CS-INDV / R Individual Consult IBRD / 93350 stainable Livelihoods Across Post Open 27,000.00 0.00 Canceled 2022-03-28 2022-08-08 2022-05-16 2022-06-06 2022-07-15 2027-05-31 esponsable Componente 2 ant Selection Selected Landscapes AR-APN-312237-CS-INDV / A Component 3: Project Manag Individual Consult IBRD / 93350 Post Limited 18,000.00 0.00 Signed 2022-08-25 2022-08-09 2022-08-30 2022-09-05 2022-09-20 2022-09-09 2022-10-25 2027-05-31 sistente de Contrataciones ement, Monitoring, Evaluatio ant Selection n AR-APN-283666-CS-INDV / A Component 3: Project Manag Individual Consult IBRD / 93350 Post Open 18,000.00 0.00 Canceled 2022-03-31 2022-04-29 2022-05-09 2022-06-01 2027-05-31 sistente contrataciones ement, Monitoring, Evaluatio ant Selection n AR-APN-312241-CS-INDV / E Component 3: Project Manag Individual Consult IBRD / 93350 Post Limited 22,500.00 0.00 Signed 2022-08-25 2022-06-15 2022-08-30 2022-09-05 2022-09-20 2022-09-13 2022-10-25 2027-05-31 specialista en Monitoreo y Ev ement, Monitoring, Evaluatio ant Selection aluación n AR-APN-284333-CS-INDV / E Component 3: Project Manag Individual Consult IBRD / 93350 Post Open 22,500.00 0.00 Canceled 2022-03-28 2022-07-20 2022-05-16 2022-06-06 2022-07-01 2027-05-31 specialista Monitoreo y Evalu ement, Monitoring, Evaluatio ant Selection ación n AR-APN-312251-CS-INDV / A Component 3: Project Manag Individual Consult Pending Impleme IBRD / 93350 Post Limited 18,000.00 0.00 2022-08-25 2022-08-30 2022-09-20 2022-10-25 2027-05-31 sistente de Tesorería ement, Monitoring, Evaluatio ant Selection ntation n AR-APN-284075-CS-INDV / D Component 3: Project Manag Individual Consult IBRD / 93350 Post Open 36,000.00 0.00 Canceled 2022-04-08 2022-08-05 2022-05-27 2022-06-17 2022-07-01 2027-05-31 os Asistentes de Tesorería pa ement, Monitoring, Evaluatio ant Selection ra la CGP n Component 1: Improved Cli AR-APN-312256-CS-INDV / D mate Resilience and Manage Individual Consult Under Implement os Asistente Administrativos IBRD / 93350 Post Limited 30,000.00 0.00 2022-08-25 2022-07-07 2022-08-30 2022-09-20 2022-10-25 2027-05-31 ment of Selected Conservati ant Selection ation Subcomponente 1.3 on and Production Landscap es and Seascapes AR-APN-312258-CS-INDV / T Component 3: Project Manag Individual Consult IBRD / 93350 Post Limited 22,500.00 0.00 Signed 2022-08-31 2022-08-02 2022-09-05 2022-09-06 2022-09-26 2022-09-14 2022-10-31 2027-05-31 esorero ement, Monitoring, Evaluatio ant Selection n AR-APN-284159-CS-INDV / T Component 3: Project Manag Individual Consult IBRD / 93350 Post Open 22,500.00 0.00 Canceled 2022-03-31 2022-08-05 2022-05-19 2022-06-09 2022-07-01 2027-05-31 esorero ement, Monitoring, Evaluatio ant Selection n Page 4 AR-APN-312259-CS-INDV / E Component 3: Project Manag Individual Consult specialista en Adquisiciones IBRD / 93350 ement, Monitoring, Evaluatio Post Limited 22,500.00 0.00 Signed 2022-08-25 2022-06-15 2022-08-30 2022-09-01 2022-09-20 2022-09-12 2022-10-25 2027-05-31 ant Selection y Contrataciones n AR-APN-283703-CS-INDV / E Component 3: Project Manag Individual Consult specialista adquisiciones y co IBRD / 93350 ement, Monitoring, Evaluatio Post Open 22,500.00 0.00 Canceled 2022-03-21 2022-07-20 2022-04-29 2022-05-20 2022-06-08 2027-05-31 ant Selection ntrataciones n AR-APN-312260-CS-INDV / A Component 3: Project Manag Individual Consult IBRD / 93350 Post Limited 18,000.00 0.00 Signed 2022-08-25 2022-08-09 2022-08-30 2022-09-06 2022-09-20 2022-09-13 2022-10-25 2027-05-31 sistente de Contabilidad ement, Monitoring, Evaluatio ant Selection n AR-APN-284168-CS-INDV / D Component 3: Project Manag Individual Consult IBRD / 93350 Post Open 36,000.00 0.00 Canceled 2022-04-08 2022-05-27 2022-06-17 2022-07-15 2027-05-31 os Asistentes Contables para ement, Monitoring, Evaluatio ant Selection la CGP n AR-APN-312261-CS-INDV / E Component 3: Project Manag Individual Consult IBRD / 93350 Post Limited 22,500.00 0.00 Signed 2022-08-25 2022-06-15 2022-08-30 2022-09-05 2022-09-20 2022-09-12 2022-10-25 2027-05-31 specialista Financiero de Sub ement, Monitoring, Evaluatio ant Selection proyectos n AR-APN-284297-CS-INDV / E Component 3: Project Manag Individual Consult IBRD / 93350 Post Open 22,500.00 0.00 Canceled 2022-03-31 2022-07-20 2022-05-19 2022-06-09 2022-07-18 2027-05-31 specialista financiero subpro ement, Monitoring, Evaluatio ant Selection yectos n AR-APN-312262-CS-INDV / E Component 3: Project Manag Individual Consult ncargado de Planificación y S IBRD / 93350 ement, Monitoring, Evaluatio Post Limited 22,500.00 0.00 Signed 2022-08-25 2022-06-15 2022-08-30 2022-09-01 2022-09-20 2022-09-14 2022-10-25 2027-05-31 ant Selection istema STEP n AR-APN-284299-CS-INDV / E Component 3: Project Manag Individual Consult ncargado planificación y sist IBRD / 93350 ement, Monitoring, Evaluatio Post Open 22,500.00 0.00 Canceled 2022-03-28 2022-07-20 2022-05-01 2022-05-16 2022-06-01 2027-06-08 ant Selection emas STEP y Comprar n AR-APN-312268-CS-INDV / A Component 3: Project Manag Individual Consult Under Implement IBRD / 93350 Post Limited 15,000.00 0.00 2022-08-25 2022-06-15 2022-08-30 2022-11-18 2022-09-20 2022-11-25 2022-10-25 2027-05-31 sistente de Mesa de Entradas ement, Monitoring, Evaluatio ant Selection ation n AR-APN-284316-CS-INDV / D Component 3: Project Manag Individual Consult os consultores para la Mesa IBRD / 93350 ement, Monitoring, Evaluatio Post Open 30,000.00 0.00 Canceled 2022-04-04 2022-07-20 2022-05-23 2022-06-13 2022-08-05 2027-05-31 ant Selection de entradas de la CGP n AR-APN-312270-CS-INDV / A Component 3: Project Manag Individual Consult IBRD / 93350 Post Limited 18,000.00 0.00 Signed 2022-08-25 2022-08-09 2022-08-30 2022-09-21 2022-09-20 2022-09-28 2022-10-25 2027-05-31 sistente Legal ement, Monitoring, Evaluatio ant Selection n AR-APN-284304-CS-INDV / A Component 3: Project Manag Individual Consult IBRD / 93350 Post Open 18,000.00 0.00 Canceled 2022-03-31 2022-05-19 2022-06-09 2022-08-01 2027-05-31 sistente legal ement, Monitoring, Evaluatio ant Selection n AR-APN-312272-CS-INDV / A Component 3: Project Manag Individual Consult IBRD / 93350 Post Limited 18,000.00 0.00 Signed 2022-08-25 2022-08-09 2022-08-30 2022-09-05 2022-09-20 2022-09-09 2022-10-25 2027-05-31 sistente de Adquisiciones ement, Monitoring, Evaluatio ant Selection n AR-APN-284109-CS-INDV / A Component 3: Project Manag Individual Consult IBRD / 93350 Post Open 18,000.00 0.00 Canceled 2022-03-31 2022-05-19 2022-06-09 2022-07-01 2027-05-31 sistente adquisiciones ement, Monitoring, Evaluatio ant Selection n AR-APN-312275-CS-INDV / D Component 3: Project Manag Individual Consult IBRD / 93350 Post Limited 30,000.00 0.00 Signed 2022-08-25 2022-06-15 2022-08-30 2022-09-05 2022-09-20 2022-09-13 2022-10-25 2027-05-31 os Asistentes Administrativos ement, Monitoring, Evaluatio ant Selection n AR-APN-284266-CS-INDV / D Component 3: Project Manag Individual Consult os Asistentes administrativos IBRD / 93350 ement, Monitoring, Evaluatio Post Open 30,000.00 0.00 Canceled 2022-04-29 2022-07-20 2022-06-17 2022-07-08 2022-09-01 2027-05-31 ant Selection para el área de Coordinación n de Proyecto Component 1: Improved Cli AR-APN-312277-CS-INDV / R mate Resilience and Manage Individual Consult Pending Impleme esponsable Técnico Subcomp IBRD / 93350 Post Limited 27,000.00 0.00 2022-08-25 2022-08-30 2022-09-20 2022-10-25 2027-05-31 ment of Selected Conservati ant Selection ntation onente 1.2 on and Production Landscap es and Seascapes Component 1: Improved Cli AR-APN-284311-CS-INDV / R mate Resilience and Manage Individual Consult esponsable Subcomponente IBRD / 93350 Post Open 27,000.00 0.00 Canceled 2022-03-28 2022-05-16 2022-06-06 2022-07-01 2027-05-31 ment of Selected Conservati ant Selection 1.2 on and Production Landscap es and Seascapes AR-APN-312278-CS-INDV / A Component 2: Promoting Su Individual Consult sistente Administrativo Comp IBRD / 93350 stainable Livelihoods Across Post Limited 15,000.00 0.00 Signed 2022-08-25 2022-07-07 2022-08-30 2022-12-29 2022-09-20 2022-12-29 2022-10-25 2027-05-31 ant Selection onente 2 Selected Landscapes AR-APN-284098-CS-INDV / A Component 2: Promoting Su Individual Consult sistente administrativo Comp IBRD / 93350 stainable Livelihoods Across Post Open 15,000.00 0.00 Canceled 2022-05-31 2022-07-20 2022-07-19 2022-08-09 2022-09-01 2027-05-31 ant Selection onente 2 Selected Landscapes AR-APN-312282-CS-INDV / A Component 3: Project Manag Individual Consult IBRD / 93350 Post Limited 18,000.00 0.00 Signed 2022-08-25 2022-08-02 2022-08-30 2022-09-05 2022-09-20 2022-09-13 2022-10-25 2027-05-31 sistente de Despacho ement, Monitoring, Evaluatio ant Selection n AR-APN-284317-CS-INDV / A Component 3: Project Manag Individual Consult IBRD / 93350 Post Open 18,000.00 0.00 Canceled 2022-05-31 2022-08-05 2022-07-19 2022-08-09 2022-09-30 2027-05-31 sistente despacho ement, Monitoring, Evaluatio ant Selection n AR-APN-312284-CS-INDV / E Component 3: Project Manag Individual Consult specialista en salud y segurid IBRD / 93350 ement, Monitoring, Evaluatio Post Limited 22,500.00 0.00 Signed 2022-08-25 2022-09-15 2022-08-30 2022-11-02 2022-09-20 2022-11-04 2022-10-25 2027-05-31 ant Selection ad ocupacional n AR-APN-284331-CS-INDV / E Component 3: Project Manag Individual Consult specialista en salud y segurid IBRD / 93350 ement, Monitoring, Evaluatio Post Open 22,500.00 0.00 Canceled 2022-04-29 2022-06-17 2022-07-08 2022-09-01 2027-05-31 ant Selection ad ocupacional n AR-APN-312285-CS-INDV / E Component 3: Project Manag Individual Consult IBRD / 93350 Post Limited 22,500.00 0.00 Signed 2022-08-31 2022-09-15 2022-09-05 2022-09-21 2022-09-26 2022-09-29 2022-10-31 2027-05-31 specialista en Reasentamient ement, Monitoring, Evaluatio ant Selection o n Component 1: Improved Cli AR-APN-312286-CS-INDV / Tr mate Resilience and Manage Individual Consult Pending Impleme IBRD / 93350 Post Limited 72,000.00 0.00 2022-08-31 2022-09-05 2022-09-26 2022-10-31 2027-05-31 es Proyectistas ment of Selected Conservati ant Selection ntation on and Production Landscap es and Seascapes Component 1: Improved Cli AR-APN-287343-CS-CQS / Tr mate Resilience and Manage Individual Consult IBRD / 93350 Post Open 72,000.00 0.00 Canceled 2022-05-31 2022-07-19 2022-08-09 2022-09-13 2027-05-31 es Proyectistas ment of Selected Conservati ant Selection on and Production Landscap es and Seascapes Component 1: Improved Cli AR-APN-312287-CS-INDV / D mate Resilience and Manage Individual Consult Pending Impleme os Especialistas en Obras de IBRD / 93350 Post Limited 42,000.00 0.00 2022-08-31 2022-09-05 2022-09-26 2022-10-31 2027-05-31 ment of Selected Conservati ant Selection ntation Ingeniería on and Production Landscap es and Seascapes AR-APN-283700-CS-INDV / D Component 1: Improved Cli os Ingenieros para el Compo mate Resilience and Manage Individual Consult IBRD / 93350 Post Open 42,000.00 0.00 Canceled 2022-04-29 2022-08-05 2022-05-28 2022-06-18 2022-07-23 2027-05-31 nente 1.3 que fortalezcan téc ment of Selected Conservati ant Selection nicamente el área on and Production Landscap es and Seascapes Page 5 AR-APN-284237-CS-INDV / R Component 2: Promoting Su Individual Consult eferente capacitación y apoy IBRD / 93350 stainable Livelihoods Across Post Open 25,500.00 0.00 Canceled 2022-05-31 2022-07-19 2022-08-09 2022-09-30 2027-05-31 ant Selection o competencias Selected Landscapes AR-APN-284306-CS-INDV / E Component 3: Project Manag Individual Consult IBRD / 93350 Post Open 22,500.00 0.00 Canceled 2022-03-28 2022-05-16 2022-06-06 2022-07-01 2027-05-31 specialista en gestión social ement, Monitoring, Evaluatio ant Selection n AR-APN-312288-CS-INDV / E Component 3: Project Manag Individual Consult Under Implement specialista en Sistemas de In IBRD / 93350 ement, Monitoring, Evaluatio Post Limited 22,500.00 0.00 2022-08-25 2022-10-24 2022-08-30 2022-11-01 2022-09-20 2022-10-25 2027-05-31 ant Selection ation formación Geográfica n AR-APN-284329-CS-INDV / E Component 3: Project Manag Individual Consult IBRD / 93350 Post Open 22,500.00 0.00 Canceled 2022-05-02 2022-07-20 2022-06-20 2022-07-11 2022-09-01 2027-05-31 specialista GIS ement, Monitoring, Evaluatio ant Selection n AR-APN-312289-CS-INDV / E Component 3: Project Manag Individual Consult Under Implement IBRD / 93350 Post Limited 22,500.00 0.00 2022-08-31 2022-10-03 2022-09-05 2022-09-26 2022-10-31 2027-05-31 specialista en Patrimonio Cul ement, Monitoring, Evaluatio ant Selection ation tural n AR-APN-283669-CS-INDV / E Component 3: Project Manag Individual Consult IBRD / 93350 Post Open 22,500.00 0.00 Canceled 2022-04-29 2022-05-28 2022-06-12 2022-07-01 2027-05-31 specialista en Patrimonio Cul ement, Monitoring, Evaluatio ant Selection tural n AR-APN-312291-CS-INDV / E Component 3: Project Manag Individual Consult Under Implement IBRD / 93350 Post Limited 22,500.00 0.00 2022-08-31 2022-07-15 2022-09-05 2022-11-22 2022-09-26 2022-11-24 2022-10-31 2027-05-31 specialista en Presupuesto ement, Monitoring, Evaluatio ant Selection ation n AR-APN-284298-CS-INDV / E Component 3: Project Manag Individual Consult IBRD / 93350 Post Open 22,500.00 0.00 Canceled 2022-03-31 2022-07-20 2022-05-19 2022-06-09 2022-08-01 2027-05-31 specialista presupuesto ement, Monitoring, Evaluatio ant Selection n AR-APN-312292-CS-INDV / E Component 3: Project Manag Individual Consult Under Implement IBRD / 93350 Post Limited 22,500.00 0.00 2022-08-31 2022-10-24 2022-09-05 2022-09-26 2022-10-31 2027-05-31 specialista en Género ement, Monitoring, Evaluatio ant Selection ation n AR-APN-284334-CS-INDV / E Component 3: Project Manag Individual Consult IBRD / 93350 Post Open 22,500.00 0.00 Canceled 2022-04-29 2022-06-17 2022-07-08 2022-09-01 2027-05-31 specialista de género ement, Monitoring, Evaluatio ant Selection n Component 1: Improved Cli AR-APN-287344-CS-INDV / S mate Resilience and Manage Individual Consult IBRD / 93350 Post Open 24,000.00 0.00 Canceled 2022-05-31 2022-07-19 2022-08-09 2022-09-13 2027-05-31 upervisor de Obras ment of Selected Conservati ant Selection on and Production Landscap es and Seascapes Component 1: Improved Cli AR-APN-312293-CS-INDV / R mate Resilience and Manage Individual Consult Under Implement esponsable Técnico Subcomp IBRD / 93350 Post Limited 27,000.00 0.00 2022-08-25 2022-08-02 2022-08-30 2022-09-20 2022-10-25 2027-05-31 ment of Selected Conservati ant Selection ation onente 1.1 on and Production Landscap es and Seascapes Component 1: Improved Cli AR-APN-284296-CS-INDV / R mate Resilience and Manage Individual Consult esponsable subcomponente IBRD / 93350 Post Open 27,000.00 0.00 Canceled 2022-04-10 2022-05-29 2022-06-19 2022-08-01 2027-05-31 ment of Selected Conservati ant Selection 1.1 on and Production Landscap es and Seascapes Component 1: Improved Cli AR-APN-312294-CS-INDV / A mate Resilience and Manage Individual Consult Under Implement sistente Administrativo Subc IBRD / 93350 Post Limited 15,000.00 0.00 2022-08-31 2022-07-07 2022-09-05 2022-09-26 2022-10-31 2027-05-31 ment of Selected Conservati ant Selection ation omponente 1.2 on and Production Landscap es and Seascapes Component 1: Improved Cli AR-APN-284090-CS-INDV / A mate Resilience and Manage Individual Consult sistente administrativo Subc IBRD / 93350 Post Open 15,000.00 0.00 Canceled 2022-05-27 2022-07-20 2022-07-15 2022-08-05 2022-09-09 2027-05-31 ment of Selected Conservati ant Selection omponente 1.2 on and Production Landscap es and Seascapes Component 1: Improved Cli AR-APN-312295-CS-INDV / R mate Resilience and Manage Individual Consult Under Implement esponsable Técnico Subcomp IBRD / 93350 Post Limited 27,000.00 0.00 2022-08-25 2022-08-02 2022-08-30 2022-09-20 2022-10-25 2027-05-31 ment of Selected Conservati ant Selection ation onente 1.3 on and Production Landscap es and Seascapes Component 1: Improved Cli AR-APN-283660-CS-INDV / R mate Resilience and Manage Individual Consult esponsable subcomponente IBRD / 93350 Post Open 27,000.00 0.00 Canceled 2022-03-31 2022-05-19 2022-06-09 2022-07-14 2027-05-31 ment of Selected Conservati ant Selection 1.3 (y pliegos) on and Production Landscap es and Seascapes Component 1: Improved Cli AR-APN-312296-CS-INDV / Ci mate Resilience and Manage Individual Consult Under Implement nco Especialistas de Obras d IBRD / 93350 Post Limited 112,500.00 0.00 2022-08-25 2022-08-02 2022-08-30 2022-09-20 2022-10-25 2027-05-31 ment of Selected Conservati ant Selection ation e Infraestructura on and Production Landscap es and Seascapes Component 1: Improved Cli AR-APN-284073-CS-INDV / E mate Resilience and Manage Individual Consult specialista de Obras de Infra IBRD / 93350 Post Open 22,500.00 0.00 Canceled 2022-03-28 2022-08-05 2022-05-16 2022-06-06 2022-07-01 2027-05-31 ment of Selected Conservati ant Selection estructura. on and Production Landscap es and Seascapes Component 1: Improved Cli AR-APN-284095-CS-INDV / E mate Resilience and Manage Individual Consult IBRD / 93350 Post Open 25,500.00 0.00 Canceled 2022-08-01 2022-09-19 2022-10-10 2022-11-01 2027-05-31 ncargado redeterminaciones ment of Selected Conservati ant Selection on and Production Landscap es and Seascapes AR-APN-312298-CS-INDV / E Component 2: Promoting Su Individual Consult Under Implement specialista en Cadena de Val IBRD / 93350 stainable Livelihoods Across Post Limited 22,500.00 0.00 2022-08-31 2022-11-11 2022-09-05 2022-12-12 2022-09-26 2022-12-29 2022-10-31 2027-05-31 ant Selection ation or Selected Landscapes AR-APN-312300-CS-INDV / E Component 2: Promoting Su Individual Consult specialista en Acceso a Merc IBRD / 93350 stainable Livelihoods Across Post Limited 22,500.00 0.00 Canceled 2022-08-31 2022-09-05 2022-09-26 2022-10-31 2027-05-31 ant Selection ados Selected Landscapes Component 1: Improved Cli AR-APN-312301-CS-INDV / A mate Resilience and Manage Individual Consult Pending Impleme sistente Administrativo Subc IBRD / 93350 Post Limited 15,000.00 0.00 2022-08-25 2022-08-30 2022-09-20 2022-10-25 2027-05-31 ment of Selected Conservati ant Selection ntation omponente 1.1 on and Production Landscap es and Seascapes Component 1: Improved Cli AR-APN-284069-CS-INDV / A mate Resilience and Manage Individual Consult sistente administrativo Subc IBRD / 93350 Post Open 15,000.00 0.00 Canceled 2022-06-30 2022-07-20 2022-08-18 2022-09-08 2022-09-30 2027-05-31 ment of Selected Conservati ant Selection omponente 1.1 on and Production Landscap es and Seascapes Component 1: Improved Cli AR-APN-283664-CS-INDV / A mate Resilience and Manage Individual Consult sistente administrativo 1 Sub IBRD / 93350 Post Open 15,000.00 0.00 Canceled 2022-04-29 2022-07-20 2022-06-17 2022-07-08 2022-08-12 2027-05-31 ment of Selected Conservati ant Selection componente 1.3 on and Production Landscap es and Seascapes Component 1: Improved Cli AR-APN-312302-CS-INDV / A mate Resilience and Manage Individual Consult sistente Técnico Subcompon IBRD / 93350 Post Limited 18,000.00 0.00 Under Review 2022-08-31 2022-08-25 2022-09-05 2022-09-26 2022-10-31 2027-05-31 ment of Selected Conservati ant Selection ente 1.1 on and Production Landscap es and Seascapes Page 6 Component 1: Improved Cli AR-APN-312303-CS-INDV / A mate Resilience and Manage Individual Consult sistente Técnico Subcompon IBRD / 93350 Post Limited 18,000.00 0.00 Signed 2022-08-31 2022-08-25 2022-09-05 2023-02-14 2022-09-26 2023-02-28 2022-10-31 2027-05-31 ment of Selected Conservati ant Selection ente 1.2 on and Production Landscap es and Seascapes Component 1: Improved Cli AR-APN-284259-CS-INDV / A mate Resilience and Manage Individual Consult IBRD / 93350 Post Open 18,000.00 0.00 Canceled 2022-04-29 2022-06-17 2022-07-08 2022-09-01 2027-05-31 sistente técnico ment of Selected Conservati ant Selection on and Production Landscap es and Seascapes Component 1: Improved Cli AR-APN-283665-CS-INDV / A mate Resilience and Manage Individual Consult sistente administrativo 2 Sub IBRD / 93350 Post Open 15,000.00 0.00 Canceled 2022-05-31 2022-07-19 2022-08-09 2022-09-13 2027-05-31 ment of Selected Conservati ant Selection componente 1.3 on and Production Landscap es and Seascapes AR-APN-312304-CS-INDV / R eferentes fiduciarios: Uno par Component 3: Project Manag Individual Consult a el NOA, Uno para la Patago IBRD / 93350 ement, Monitoring, Evaluatio Post Limited 95,000.00 0.00 Signed 2022-08-31 2023-02-03 2022-09-05 2023-02-15 2022-09-26 2023-02-27 2022-10-31 2027-05-31 ant Selection nia Austral, Uno para la Pata n gonia Norte, Uno para el Cen tro y Uno para el NEA AR-APN-284113-CS-INDV / R eferentes fiduciarios: Uno par Component 3: Project Manag Individual Consult a el NOA, Uno para la Patago IBRD / 93350 ement, Monitoring, Evaluatio Post Open 95,000.00 0.00 Canceled 2022-04-29 2022-06-17 2022-07-08 2022-08-01 2027-05-31 ant Selection nia Austral, Uno para la Pata n gonia Norte, Uno para el Cen tro y Uno para el NEA Component 1: Improved Cli AR-APN-284176-CS-INDV / E mate Resilience and Manage Individual Consult IBRD / 93350 Post Open 24,000.00 0.00 Canceled 2022-05-02 2022-06-20 2022-07-11 2022-08-01 2027-05-31 specialista en Obras ment of Selected Conservati ant Selection on and Production Landscap es and Seascapes Component 1: Improved Cli AR-APN-312297-CS-INDV / E mate Resilience and Manage Individual Consult Pending Impleme ncargado de Redeterminacio IBRD / 93350 Post Limited 25,500.00 0.00 2022-08-31 2022-09-05 2022-09-26 2022-10-31 2027-05-31 ment of Selected Conservati ant Selection ntation nes on and Production Landscap es and Seascapes AR-APN-312290-CS-INDV / Di Component 2: Promoting Su Individual Consult Under Implement ecinueve Promotores territori IBRD / 93350 stainable Livelihoods Across Post Limited 342,000.00 0.00 2022-08-31 2022-09-29 2022-09-05 2022-09-26 2022-10-31 2027-05-31 ant Selection ation ales para distintos Paisajes y Selected Landscapes Corredores AR-APN-312232-CS-INDV / C Component 3: Project Manag Individual Consult IBRD / 93350 Post Direct - National 30,000.00 0.00 Signed 2022-08-25 2022-08-02 2022-09-04 2022-12-29 2022-09-25 2023-01-02 2022-10-30 2027-05-31 oordinador General del Proye ement, Monitoring, Evaluatio ant Selection cto n AR-APN-309150-CS-INDV / R Component 3: Project Manag Individual Consult esponsable de Gestión de Rie IBRD / 93350 ement, Monitoring, Evaluatio Post Limited 26,250.00 0.00 Signed 2022-08-11 2022-08-02 2022-08-16 2022-09-26 2022-09-06 2022-09-29 2022-10-01 2027-05-21 ant Selection sgos e Impactos Sociales n AR-APN-333285-CS-INDV / E Component 2: Promoting Su specialista en Desarrollo y Fo Individual Consult IBRD / 93350 stainable Livelihoods Across Post Limited 25,500.00 0.00 Signed 2022-12-21 2022-11-28 2022-12-26 2022-12-27 2023-01-16 2022-12-29 2023-02-20 2027-09-26 rtalecimiento de Capacidade ant Selection Selected Landscapes s y Competencias Laborales p/ el empleo verde AR-APN-346420-CS-INDV / Pl Component 1: Improved Cli an de Gestión Parque Nacion mate Resilience and Manage Individual Consult Pending Impleme IBRD / 93350 Post Limited 30,000.00 0.00 2023-05-02 2023-05-07 2023-05-28 2023-07-01 2024-06-30 al Traslasierra - Provincia de ment of Selected Conservati ant Selection ntation Córdoba on and Production Landscap es and Seascapes AR-APN-284323-CS-INDV / Pl Component 1: Improved Cli an de Gestión Parque Nacion mate Resilience and Manage Individual Consult IBRD / 93350 Post Open 30,000.00 0.00 Canceled 2022-04-13 2022-06-01 2022-06-22 2022-07-27 2023-08-01 al Traslasierra, Provincia de ment of Selected Conservati ant Selection Córdoba on and Production Landscap es and Seascapes AR-APN-283657-CS-INDV / Pl Component 1: Improved Cli an de Gestión área Marina Pr mate Resilience and Manage Individual Consult IBRD / 93350 Post Open 30,000.00 0.00 Canceled 2022-04-13 2022-06-01 2022-06-22 2022-07-27 2023-07-31 otegida Yaganes, Tierra del F ment of Selected Conservati ant Selection uego on and Production Landscap es and Seascapes AR-APN-284293-CS-INDV / Pl Component 1: Improved Cli an de Gestión Parque Nacion mate Resilience and Manage Individual Consult IBRD / 93350 Post Open 30,000.00 0.00 Canceled 2022-06-15 2022-08-03 2022-08-24 2022-09-28 2023-10-02 al Islote Lobos, Provincia de ment of Selected Conservati ant Selection Río Negro on and Production Landscap es and Seascapes AR-APN-355186-CS-INDV / E Component 2: Promoting Su Individual Consult Under Implement specialista en Acceso a Merc IBRD / 93350 stainable Livelihoods Across Post Open - National 22,500.00 0.00 2023-05-01 2022-10-24 2023-06-01 2023-06-22 2023-07-27 2027-05-31 ant Selection ation ados Selected Landscapes Page 7 PROCUREMENT PLAN (Textual Part) Project information: Democratic Republic Democratic of Congo – DRC Electricity and Water Access and Governance Project - P173506 Project Implementation agency: Unité de Coordination et Management des projets du Ministère de l’Energie et des Ressources Hydrauliques(UCM) Date of the Procurement Plan: March 2021 Period covered by this Procurement Plan: March 2021 – December 2021 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016 and revised November 2017) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the Borrower’s Public Procurement Law No 10/010 of April 27, 2010 (PPL) and the Manual of Procedures of the PPL as per Borrower’s Decree No 10/22 of June 2, 2010, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. (a) Standard Bidding Documents: All standard bidding documents to be used for the Project under NCB shall be found acceptable to the World Bank before their use during the implementation of Project; (b) Eligibility: Eligibility of bidders and acceptability of their goods and services shall not be based on their nationality and/or their origin; and association with a national firm shall not be a condition for participation in a bidding process. Therefore, except for the ineligibility situations referred to in paragraphs 1.10(a) (i) and 1.10(a) (ii) of the Procurement Guidelines, the eligibility of bidders must be based solely on their qualification, experience and capacity to carry out the contract related to the specific bidding process; (c) Advertising and Bid Preparation Time: Bidding opportunities shall be advertised at least in a national newspaper of wide circulation and on the website of the Recipient’s Procurement Regulator (Autorité de Régulation des Marchés Publics) and bidders should be given at least 30 days from the date of invitation to bid or the date of availability of the bidding documents, whichever is later; (d) Criteria for Qualification of Bidders: Qualification criteria shall only concern the bidder’s capability and resources to perform the contract taking into account objective and measurable factors. Such criteria for qualification of bidders shall be clearly specified in the bidding documents; (e) Bid Evaluation and Contract Award: A contract shall be awarded to the substantially responsive and lowest evaluated bidder provided that such bidder meets the qualification criteria specified in the bidding documents. No scoring system shall be allowed for the evaluation of bids, and no “blanket” limitation to the number of lots which can be awarded to a bidder shall apply. The criteria for bid evaluation and the contract award conditions shall be clearly specified in the bidding documents; (f) Preferences: No preference shall be given to domestic/regional bidders; to domestically/regionally manufactured goods; and to bidders forming a joint venture with a national firm or proposing national sub-contractors or carrying out economic activities in the territory of the Recipient; (g) Publication of Contract Award: Information on all contract awards shall be published in at least a national newspaper of wide circulation or in the Recipient’s Procurement Regulator (Autorité de Régulation des Marchés Publics) web-site; (h) Fraud and Corruption: In accordance with the Procurement Guidelines, each bidding document and contract shall include provisions stating the World Bank’s policy to sanction firms or individuals found to have engaged in fraud and corruption as set forth in the Procurement Guidelines; (i) Inspection and Audit Rights: In accordance with the Procurement Guidelines, each bidding document and contract shall include provisions stating the World Bank’s policy with respect to inspection and audit of accounts, records and other documents relating to the bid submission and contract performance; (j) Requirement for administrative documents and/or tax clearance certificate: The bidding documents shall not require foreign bidders to produce any administrative or tax related certificates prior to confirmation of awarding a contract; and (k) Modifications of a Signed Contract: Any change in the contract amount which, singly or combined with all previous changes, increases the original contract amount by fifteen (15) percent or more must be done through an amendment to the signed contract instead of signing a new contract. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables. “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: is applicable for those contracts identified in the Procurement Plan tables; Other Relevant Procurement Information. “Not Applicable” PROCUREMENT Congo, Democratic Republic of : Access Governance & Reform for the Electricity and Water Sectors Project PLAN General Information Country: Congo, Democratic Republic of 2021-04-05 Bank’s Approval Date of the Original Procurement Plan: 2023-06-07 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P173506 GPN Date: Project Name: Access Governance & Reform for the Electricity and Water Sectors Project Loan / Credit No: IDA / V4140, IDA / 70660, / UNITE DE COORDINATION ET MANAGEMENT DES PROJETS DU MINISTERE Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned ZR-UCM-329855-CW-RFB / T Component 4: Public Sector- Request for Bids - ravaux additionnels pour par Open - Internationa Single Stage - One E Pending Imp 2025-07-0 IDA / 70660 based Access Expansion wit Prior Request for Bids Plant SPD (withou 9,000,000.00 0.00 2023-01-16 2023-01-21 2023-03-04 2023-04-03 2023-05-08 achever la réhabilitation de l l nvelope lementation 4 h Private Sector Involvement t prequalification) a CHE de Mobayi-Mbongo GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ZR-UCM-283112-GO-DIR / Mi Component 2: Institutional S gration de TOM2PRO vers TO IDA / V4140 trengthening and Developm Post Direct Selection Direct 60,000.00 0.00 Signed 2022-04-04 2022-03-09 2022-04-09 2022-01-28 2022-05-14 2022-11-10 MWEB et acquisition de TOM ent Support CONSO ZR-UCM-301416-GO-DIR / Ac quisition de la plateforme OD Component 3: Private Sector Pending Impl IDA / V4140 Post Direct Selection Direct 500,000.00 0.00 2022-07-18 2022-07-23 2022-08-27 2023-02-23 YSSEY pour la gestion des tra -based Access Expansion ementation nsactions du secteur de l'éle ctricité NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ZR-UCM-226936-CS-CQS / St ructuration technique, institu tionnelle et financière en vue de la mise en place de PPP (i Component 4: Public Sector- Consultant Qualifi Open - Internationa ncluant concessions) pour (i) IDA / V4140 based Access Expansion wit Post 300,000.00 0.00 Under Review 2021-05-23 2022-04-20 2021-06-13 2021-07-27 2021-08-26 2021-09-30 2022-03-29 cation Selection l réseaux de Kinshasa, (ii) rése h Private Sector Involvement aux non concédés de Goma et NYIRAGONGO, et (iii) Centr ale de MOBAYI et réseau ass ocié de Gbadolite ZR-UCM-226938-CS-CQS / A ctualisation APD et élaboratio Component 4: Public Sector- Consultant Qualifi Open - Internationa Under Implement n des DAO pour DKC & DKO ( IDA / V4140 based Access Expansion wit Post 400,000.00 0.00 2021-05-23 2022-05-19 2021-06-13 2021-07-27 2021-08-26 2021-09-30 2022-03-29 cation Selection l ation en partant de l'APD disponibl h Private Sector Involvement e) y compris les mesures en réseau ZR-UCM-226943-CS-CQS / C onsultant (firme) en charge d Component 1: Power and W ’effectuer l’état des lieux des Consultant Qualifi Open - Internationa Pending Impleme / ater Utility Governance and Post 300,000.00 0.00 2021-05-23 2021-06-13 2021-07-27 2021-08-26 2021-09-30 2022-03-29 systèmes d’information de la cation Selection l ntation Performance SNEL et de préparer un DAO pour l’implantation d’un prog iciel de gestion intégré ZR-UCM-226947-CS-CQS / C Component 1: Power and W onsultant (firme) chargé des Consultant Qualifi Open - Internationa Pending Impleme IDA / V4140 ater Utility Governance and Post 300,000.00 0.00 2021-05-24 2021-06-14 2021-07-28 2021-08-27 2021-10-01 2022-03-30 études d'un plan directeur de cation Selection l ntation Performance la desserte en eau potable d ans la ville de Goma ZR-UCM-226952-CS-CQS / S ervices de consultant pour u n diagnostic au sein de la SN Component 1: Power and W Consultant Qualifi Open - Internationa Under Implement EL, la préparation d'un plan a IDA / 70660 ater Utility Governance and Post 300,000.00 0.00 2021-05-28 2022-06-21 2021-06-18 2022-07-21 2021-08-01 2021-08-31 2021-10-05 2022-04-03 cation Selection l ation ctualisé d'amélioration de la Performance performance (sur la base du plan de redressement) et la préparation du contrat de pe rformance ZR-UCM-226954-CS-CQS / Et Component 1: Power and W ude de faisabilité de la délég Consultant Qualifi Open - Internationa Under Implement IDA / V4140 ater Utility Governance and Post 300,000.00 0.00 2021-06-08 2022-12-26 2021-06-29 2021-08-12 2021-09-11 2021-10-16 2022-04-14 ation de service public de l'e cation Selection l ation Performance au à Kananga et Goma ZR-UCM-226956-CS-CQS / Et ude de faisabilité de l'électrifi Component 4: Public Sector- cation et la fourniture d'eau Consultant Qualifi Open - Internationa Under Implement IDA / 70660 based Access Expansion wit Post 350,000.00 0.00 2021-05-28 2022-06-17 2021-06-18 2021-08-01 2021-08-31 2021-10-05 2022-04-03 des centres de santé, écoles cation Selection l ation h Private Sector Involvement et usages productifs et prépa ration de DAO dans les villes ciblées ZR-UCM-226959-CS-CQS / C abinet pour mener des enqu Component 2: Institutional S Consultant Qualifi Open - Internationa Under Implement êtes afin de déterminer la sit IDA / V4140 trengthening and Developm Post 300,000.00 0.00 2021-05-28 2022-04-20 2021-06-18 2022-06-28 2021-08-01 2021-08-31 2021-10-05 2022-04-03 cation Selection l ation uation (valeur des indicateur ent Support s) de référence pour le cadre de résultats du projet ZR-UCM-283114-CS-CQS / R Component 2: Institutional S ecrutement d'un Consultant f Consultant Qualifi IDA / V4140 trengthening and Developm Post Open - National 60,000.00 0.00 Under Review 2022-04-25 2023-05-15 2022-05-16 2022-06-29 2022-07-29 2022-09-02 2023-03-01 irme chargé de l'élaboration cation Selection ent Support du plan de communication Page 1 ZR-UCM-226948-CS-CQS / C onsultant (firme) chargé des Component 4: Public Sector- études (APS, APD et DAO) po Consultant Qualifi Open - Internationa Under Implement IDA / V4140 based Access Expansion wit Post 300,000.00 0.00 2022-04-25 2022-03-23 2022-05-16 2022-06-29 2022-07-29 2022-09-02 2023-03-01 ur la construction et la gestio cation Selection l ation h Private Sector Involvement n de 2 stations de traitement de boues de vidange à Bukav u et à Goma ZR-UCM-283122-CS-CQS / C onsultant firme en charge de l'élaboration de la cartograph Component 2: Institutional S ie des services disponibles e Consultant Qualifi Under Implement IDA / V4140 trengthening and Developm Post Open - National 250,000.00 0.00 2022-04-25 2022-03-23 2022-05-16 2022-06-29 2022-07-29 2022-09-02 2023-03-01 n cas de violences basées su cation Selection ation ent Support r le genre à Kananga, Mbuji- Mayi, Kenge, Goma, Tshikapa , Bandundu-ville, Bunia et Ka binda et 5 autres agglomérat ions ZR-UCM-287039-CS-QCBS / Recrutement d'un Consultant Component 2: Institutional S Quality And Cost- firme chargé de l'audit exter IDA / V4140 trengthening and Developm Post Open - National 50,000.00 0.00 Under Review 2022-07-11 2023-06-12 2022-08-01 2022-09-14 2022-10-12 2022-11-11 2022-12-16 2023-01-20 2024-01-20 Based Selection ne du PPA du projet AGREE e ent Support t de 2 premiers exercices du projet AGREE ZR-UCM-283125-CS-CQS / C Component 4: Public Sector- onsultant firme pour mener l' Consultant Qualifi Pending Impleme IDA / V4140 based Access Expansion wit Post Open - National 200,000.00 0.00 2023-02-20 2023-03-13 2023-04-26 2023-05-26 2023-06-30 2023-08-05 EIES et élaborer le PAR pour l cation Selection ntation h Private Sector Involvement 'Alimentation en Eau Potable de Kananga ZR-UCM-299684-CS-QCBS / Conseiller en transaction pou Component 3: Private Sector Quality And Cost- Open - Internationa Under Implement r la mise en œuvre du progra IDA / 70660 Prior 800,000.00 0.00 2022-06-27 2022-06-16 2022-07-18 2022-06-16 2022-08-31 2023-01-23 2022-09-28 2022-10-28 2022-12-02 2023-01-06 2024-01-06 -based Access Expansion Based Selection l ation mme de mini-réseaux verts d ans les villes de Kananga et Mbuji-Mayi ZR-UCM-311064-CS-QCBS / Recrutement d’un Consultant (firme) chargé de (i) l’élabora tion des études techniques p Component 4: Public Sector- Quality And Cost- Open - Internationa our la poursuite des travaux IDA / 70660 based Access Expansion wit Prior 3,500,000.00 0.00 Under Review 2022-10-31 2022-11-17 2022-11-21 2023-01-20 2023-01-04 2023-02-01 2023-03-03 2023-04-07 2023-05-12 2025-04-11 Based Selection l de réhabilitation, assainisse h Private Sector Involvement ment et extension des résea ux dans les villes de Kinshas a et Gbadolite et (ii) la super vision desdits travaux ZR-UCM-329784-CS-CQS / C onsultant (firme) chargé d'id entifier les besoins en format Component 4: Public Sector- Consultant Qualifi Pending Impleme ion des jeunes, principaleme IDA / V4140 based Access Expansion wit Post Open - National 250,000.00 0.00 2023-01-16 2023-02-06 2023-03-22 2023-04-21 2023-05-26 2023-11-22 cation Selection ntation nt les femmes, dans les zone h Private Sector Involvement s d'intervention du projet AG REE, dans les métiers des se cteurs de l'électricité et de l' eau ZR-UCM-329786-CS-CQS / C onsultant (firme) chargé de (i ) l'élaboration des APS, APD Component 4: Public Sector- Consultant Qualifi et DAO pour les travaux d’int IDA / 70660 based Access Expansion wit Post Open - National 250,000.00 0.00 Under Review 2023-01-16 2023-04-20 2023-02-06 2023-03-22 2023-04-21 2023-05-26 2024-06-29 cation Selection erconnexion des différents ré h Private Sector Involvement seaux de Goma (ii) la supervi sion des travaux d'interconn exion ZR-UCM-330752-CS-QCBS / I ngénieur-conseil pour la supe Component 4: Public Sector- rvision des travaux additionn Quality And Cost- Open - Internationa Pending Impleme IDA / 70660 based Access Expansion wit Prior 1,500,000.00 0.00 2023-01-23 2023-02-13 2023-03-29 2023-04-26 2023-05-26 2023-06-30 2023-08-04 2025-11-28 els pour parachever la réhabi Based Selection l ntation h Private Sector Involvement litation de la Centrale Hydroé lectrique de Mobayi-Mbongo ZR-UCM-362023-CS-QCBS / Component 2: Institutional S Recrutement d'un consultant Quality And Cost- IDA / V4140 trengthening and Developm Post Open - National 240,000.00 0.00 Under Review 2023-06-19 2023-06-12 2023-07-10 2023-08-23 2023-09-20 2023-10-20 2023-11-24 2023-12-29 2027-05-02 firme chargé de réaliser un a Based Selection ent Support udit interne périodique du pr ojet AGREE ZR-UCM-226955-CS-CQS / C abinet (Gestionnaire internati Component 3: Private Sector Consultant Qualifi Open - Internationa IDA / V4140 Post 450,000.00 0.00 Canceled 2021-05-28 2021-06-18 2021-08-01 2021-08-31 2021-10-05 2022-04-03 onal de fonds) en charge de l -based Access Expansion cation Selection l a conception et la gestion du Fonds Mwinda ZR-UCM-334438-CS-QCBS / Cabinet (Gestionnaire interna Component 3: Private Sector Quality And Cost- Open - Internationa IDA / 70660 Prior 5,000,000.00 0.00 Canceled 2023-05-25 2027-07-03 tional de fonds) en charge de -based Access Expansion Based Selection l la conception et la gestion du Fonds Mwinda ZR-UCM-365541-CS-QCBS / Assistance technique à l'ARE pour (A) finaliser et diffuser l Component 2: Institutional S es décrets d'application de la Quality And Cost- Pending Impleme IDA / 70660 trengthening and Developm Post Open - National 500,000.00 0.00 2023-07-24 2023-08-14 2023-09-27 2023-10-25 2023-11-24 2023-12-29 2024-02-02 2025-02-01 loi sur l'électricité, élaborer d Based Selection ntation ent Support es contrats et des procédure s PPP standard, (B) compiler et publier les contrats PPP ap prouvés  ; (C) aider à traiter l es plaintes INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ZR-UCM-226928-CS-INDV / C Component 2: Institutional S Individual Consult Pending Impleme onsultant individuel chargé d IDA / V4140 trengthening and Developm Post Direct 40,000.00 0.00 2021-04-18 2021-04-28 2021-05-19 2021-06-23 2021-12-20 ant Selection ntation e l'amélioration du PPSD ent Support ZR-UCM-226929-CS-INDV / C Component 2: Institutional S onsultant individuel chargé d Individual Consult IDA / V4140 trengthening and Developm Post Limited 40,000.00 0.00 Signed 2021-04-18 2022-03-10 2021-04-23 2022-07-13 2021-05-14 2022-12-02 2021-06-18 2021-12-15 e l'élaboration du manuel de ant Selection ent Support s opérations du projet ZR-UCM-226939-CS-CDS / St ructuration technique, institu tionnelle et financière en vue Component 3: Private Sector IDA / 70660 Post Direct Selection Direct 800,000.00 0.00 Canceled 2021-05-23 2021-06-02 2021-08-06 2022-02-02 de la mise en concession en -based Access Expansion PPP de l'ensemble des projet s du PIP / Conseiller en trans actions Page 2 ZR-UCM-226941-CS-CDS / El aboration (i) des études de fa isabilité, (ii) des études d'ava nt projets détaillés, (iii) des d Component 3: Private Sector / Post Direct Selection Direct 600,000.00 0.00 Canceled 2021-05-23 2021-06-02 2021-08-06 2022-02-02 ossiers d’appels d’offre pour l -based Access Expansion 'électrification de 5 autres ag glomérations par mini-réseau x au moyen d'énergie renouv elable dont KANANGA, MBUJI MAYI ZR-UCM-226946-CS-CDS / C onsultant (firme) chargé des Component 4: Public Sector- études détaillées et élaborati IDA / V4140 based Access Expansion wit Post Direct Selection Direct 350,000.00 0.00 Signed 2021-05-23 2022-12-02 2021-06-02 2023-02-08 2021-08-06 2022-02-02 on DAO pour la construction h Private Sector Involvement de la station d'eau et réseau x associés de la ville de Kana nga ZR-UCM-226957-CS-INDV / C Component 4: Public Sector- onsultant individuel pour me Individual Consult IDA / V4140 based Access Expansion wit Post Limited 200,000.00 0.00 Canceled 2021-05-28 2021-06-02 2021-06-23 2021-07-28 2022-01-24 ner l'EIES et élaborer le PAR ant Selection h Private Sector Involvement pour l'Alimentation en Eau Po table de Kananga ZR-UCM-226961-CS-INDV / C onsultant individuel en charg e de la réalisation d'une Etud e d’impacts environnementa Component 3: Private Sector Individual Consult / Post Limited 200,000.00 0.00 Canceled 2021-06-04 2021-06-09 2021-06-30 2021-08-04 2022-01-31 ux et sociaux (EIES) et d'un P -based Access Expansion ant Selection lan d’action de réinstallation (PAR) dans le cadre des trava ux d'électrification à réaliser dans les villes de KANANGA e t MBUJIMAYI ZR-UCM-283110-CS-INDV / R ecrutement d'un consultant i Component 2: Institutional S Individual Consult Under Implement ndividuel spécialiste en prév IDA / V4140 trengthening and Developm Post Open 51,600.00 0.00 2022-04-18 2022-03-23 2022-06-06 2022-06-27 2022-08-01 2023-08-01 ant Selection ation ention des violences basées ent Support sur le genre au sein d'UCM ZR-UCM-283111-CS-INDV / R Component 2: Institutional S ecrutement d'un Consultant i Individual Consult IDA / V4140 trengthening and Developm Post Open 51,600.00 0.00 Under Review 2022-04-18 2023-05-15 2022-06-06 2022-06-27 2022-08-01 2023-08-01 ndividuel spécialiste en com ant Selection ent Support munication au sein d'UCM ZR-UCM-287040-CS-CDS / C onsultant (firme) chargé des études détaillées et élaborati Component 4: Public Sector- Under Implement on DAO pour la fourniture et IDA / V4140 based Access Expansion wit Post Direct Selection Direct 350,000.00 0.00 2022-05-30 2022-06-10 2022-06-09 2022-08-13 2023-02-09 ation montage de deux unités com h Private Sector Involvement pactes de traitement d’eau e t réseaux associés des villes de BUTEMBO et BENI ZR-UCM-287049-CS-INDV / R ecrutement d'un consultant i Component 2: Institutional S ndividuel assumant la fonctio Individual Consult Under Implement IDA / V4140 trengthening and Developm Post Open 60,000.00 0.00 2022-06-27 2022-05-24 2022-08-15 2022-09-05 2022-10-10 2023-10-11 n d'ingénieur en transport et ant Selection ation ent Support distribution d'électricité au s ein d'UCM et basé à Kananga ZR-UCM-299681-CS-INDV / R ecrutement d'un consultant i Component 2: Institutional S Individual Consult Pending Impleme ndividuel, Ingénieur spécialis IDA / V4140 trengthening and Developm Post Open 60,000.00 0.00 2023-03-27 2023-05-15 2023-06-05 2023-07-10 2024-07-10 ant Selection ntation te en eau et assainissement ent Support pour CEP-O et basé à Goma ZR-UCM-301430-CS-INDV / C onsultant individuel chargé d e l'élaboration des dispositio ns institutionnelles, des besoi Component 2: Institutional S Individual Consult Under Implement ns et des capacités de gestio IDA / V4140 trengthening and Developm Post Open 100,000.00 0.00 2022-09-08 2022-09-20 2022-10-27 2022-11-17 2022-12-22 2023-06-20 ant Selection ation n des risques et impacts E&S ent Support des entités chargées de la mi se en oeuvre du projet et éla boration du plan de renforce ment des capacités ZR-UCM-301420-CS-INDV / C onsultant individuel chargé p our une assistance technique Component 1: Power and W Individual Consult Under Implement pour la préparation et le suivi IDA / V4140 ater Utility Governance and Prior Direct 200,000.00 0.00 2022-07-18 2022-07-06 2022-07-28 2022-07-12 2022-08-18 2022-09-22 2023-10-27 ant Selection ation du projet d’implémentation d Performance ’un progiciel de gestion intég ré (PGI) à la Société national e d’Electricité (SNEL) ZR-UCM-329782-CS-INDV / C onsultant individuel chargé d e l'audit, de l'assistance et d e la rédaction du manuel de Component 2: Institutional S Individual Consult Under Implement procédures de gestion des re IDA / V4140 trengthening and Developm Post Direct - National 30,000.00 0.00 2023-01-16 2023-04-07 2023-01-26 2023-02-16 2023-03-23 2023-09-19 ant Selection ation ssources humaines y compris ent Support les outils afférents pour le pe rsonnel affecté au projet AGR EE au sein d'UCM, CEPO, ANS ER, ARE et COPIREP ZR-UCM-343366-CS-CDS / R ecrutement d’un Consultant ( Component 1: Power and W Firme) chargé de l’étude sur l Direct - Internation Under Implement IDA / 70660 ater Utility Governance and Prior Direct Selection 650,000.00 0.00 2023-06-26 2023-06-14 2023-07-06 2023-09-09 2024-03-07 es modalités de régionalisati al ation Performance on des activités et de filialisa tion des Directions Régionale s de la REGODESO SA ZR-UCM-362014-CS-INDV / R Component 2: Institutional S ecrutement d'un consultant i Individual Consult Under Implement IDA / 70660 trengthening and Developm Post Open - National 48,000.00 0.00 2023-06-19 2023-06-12 2023-08-07 2023-08-28 2023-10-02 2024-10-01 ndividuel devant assumer la f ant Selection ation ent Support onction de chef comptable a u sein d'UCM ZR-UCM-362016-CS-INDV / R Component 2: Institutional S ecrutement d'un consultant i Individual Consult IDA / 70660 trengthening and Developm Post Open - National 42,000.00 0.00 Under Review 2023-06-19 2023-06-12 2023-08-07 2023-08-28 2023-10-02 2024-10-01 ndividuel devant assumer la f ant Selection ent Support onction de comptable au sein d'UCM Page 3 PLAN DE PASSATION DE MARCHÉS (Texte) Information sur le Projet : [Nom du pays] [Nom du Projet] [No d’identification du projet] Agence d’exécution du Projet : [Insérer le nom officiel de l’Agence] Date du plan de passation des marchés : [Insérer la date] Période couverte par ce plan de passation des marchés : [Insérer date de début, date de fin] Préambule Conformément au paragraphe 5.9 du “Règlement de Passation des Marchés pour les Emprunteurs sollicitant le Financement de Projets d’Investissement (FPI)” (Juillet 2016) (“Règlement de Passation des Marchés”) le Système électronique de la Banque de suivi systématique des transactions de marchés publics (STEP) sera utilisé pour préparer, valider et actualiser les plans de passation des marchés et effectuer toutes les transactions liées à la passation des marchés du projet. Ce texte ainsi que les tableaux du plan de passation des marchés présents dans STEP constituent le plan de passation des marchés du projet. Les conditions suivantes s'appliquent à toutes les activités de passation de marchés du plan de passation de marchés. Les autres éléments du plan de passation des marchés tels que requis au paragraphe 4.4 du Règlement de passation des marchés sont énoncés dans STEP. Les Dossiers types de passation des marchés publics de la Banque devront être utilisés pour tous les contrats soumis à la concurrence internationale, ainsi que pour tous les autres contrats soumis à cette obligation telle que spécifiée dans les tableaux du plan de passation des marchés de STEP. Procédures nationales de passation des marchés : En accord avec le paragraphe 5.3 du Règlement de passation des marchés, dans le cas où la procédure de passation des marché se fera au niveau national (telle que spécifiée dans les tableaux du plan de passation des marchés inclus de STEP), les procédures nationales de passation des marchés du pays considéré pourront être utilisées. Si l’Emprunteur utilise ses propres procédures d’appel d’offres national ouvert telles qu’énoncées [Insérer la référence exacte de la législation nationale], ces arrangements sont soumis aux dispositions du paragraphe 5.4 du Règlement de passation des marchés et aux conditions suivantes : Indiquer la liste des conditions requises pour assurer la cohérence avec le paragraphe 5.4 du Règlement de passation des marchés. Si aucune condition s’applique, supprimer la mention « et aux conditions suivantes ». Lorsque l’Emprunteur utilise d’autres procédures que l’appel d’offres national ouvert, ces procédures devront être en accord avec les dispositions du paragraphe 5.5 du Règlement de passation des marchés. Crédit-bail tel que spécifié au paragraphe 5.10 du Règlement de Passation des marchés : Le crédit-bail peut être utilisé pour les contrats indiqués comme tel dans le Plan de passation des marchés. Sinon indiquer « Sans objet » Achat de biens d’occasion tel que spécifié au paragraphe 5.11 du Règlement de Passation des Marchés est autorisé pour les contrats indiqués comme tel dans le Plan de passation des marchés. Sinon indiquer « Sans objet » Préférence nationale telle que spécifiée au paragraphe 5.51 du Règlement de Passation des Marchés (Fournitures et Travaux). Fournitures : [ne s’applique pas/s’applique pour les contrats indiqués dans les tableaux du Plan de passation des marchés] Travaux [ne s’applique pas/s’applique pour les contrats indiqués dans les tableaux du Plan de passation des marchés] L’Assistance directe à la mise en œuvre (sigle HEIS en anglais) tel que précisée aux paragraphes 3.10 et 3.11 du Règlement de Passation des marchés s’applique. [Inclure cette mention seulement si la Banque a formellement acceptée de fournir cette assistance directe à l’Emprunteur. Sinon, supprimer cette phrase.] Autres informations pertinentes sur la passation des marchés Indiquer toute autre information pertinente relative aux procédures de passation, telle que par exemple l’utilisation de procédures de participation communautaire au développement (CDD), de l’utilisation de procédures pour un besoin urgent d’assistance ou de faible capacité, etc. PROCUREMENT Mali : Mali Improving Education Quality and Results for All Project (MIQRA) PLAN General Information Country: Mali 2021-08-24 Bank’s Approval Date of the Original Procurement Plan: 2023-06-07 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P164032 GPN Date: Project Name: Mali Improving Education Quality and Results for All Project (MIQRA) Loan / Credit No: IDA / D7730, IDA / 68300, TF / B3129, TF / B4948, TF / B4949 Ministry of Education Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned National Procure ML-MEN-249622-CW-RFB / T ment Document - Building Stronger Pathways f Single Stage - One E Pending Imp 2023-04-2 ravaux d'extension de salles IDA / D7730 Post Request for Bids Open - National 1 Envelope proce 1,000,000.00 0.00 2022-07-04 2022-07-09 2022-08-20 2022-09-19 2022-10-24 or Girls Education Success nvelope lementation 2 de classe dans les lycées ss (Non Bank-SPD ) National Procure ML-MEN-249625-CW-RFB / T Strengthening the Governan ment Document - Single Stage - One E Pending Imp 2023-04-0 ravaux de construction de sal IDA / 68300 ce and Resilience of the Edu Post Request for Bids Open - National 1 Envelope proce 5,525,000.00 0.00 2022-06-20 2022-06-25 2022-08-06 2022-09-05 2022-10-10 nvelope lementation 8 les de classe au fondamental cation System ss (Non Bank-SPD 2 ) National Procure ML-MEN-263202-CW-RFB / T ment Document - Building Stronger Pathways f Single Stage - One E Pending Imp 2023-09-2 ravaux de réalisation de poin TF / B3129 Post Request for Bids Open - National 1 Envelope proce 240,000.00 0.00 2022-12-05 2022-12-10 2023-01-21 2023-02-20 2023-03-27 or Girls Education Success nvelope lementation 3 ts d'eau (forages) au fondam ss (Non Bank-SPD ental 2 ) ML-MEN-362896-CW-RFB / T Request for Bids - ravaux de construction de 19 Building Stronger Pathways f Single Stage - One E Small Works SPD Pending Imp 2024-04-0 Kits (3 salles de classe ,Bure TF / B3129 Post Request for Bids Open - National 1,235,000.00 0.00 2023-06-16 2023-06-21 2023-08-02 2023-09-01 2023-10-06 or Girls Education Success nvelope (1 envelope proce lementation 3 au+magasin et bloc latrine) ss) école pour le fondamental 2 dans la région de Bougouni ML-MEN-362909-CW-RFB / T Request for Bids - ravaux de construction de 6 Building Stronger Pathways f Single Stage - One E Small Works SPD Pending Imp 2024-02-1 Kits (3 salles de classe ,Bure IDA / D7730 Post Request for Bids Open - National 390,000.00 0.00 2023-06-23 2023-06-28 2023-08-09 2023-09-08 2023-10-13 or Girls Education Success nvelope (1 envelope proce lementation 0 au+magasin et bloc latrine) ss) école pour le fondamental 2 dans la région de San ML-MEN-362922-CW-RFQ / T Request for Quota ravaux de construction de 3 Building Stronger Pathways f Request for Quota Single Stage - One E tions - Small Work Pending Imp 2023-12-2 Kits (3 salles de classe ,Bure IDA / D7730 Post Limited 195,000.00 0.00 2023-06-28 2023-08-23 or Girls Education Success tions nvelope s (Emergency) SP lementation 1 au+magasin et bloc latrine) D -Competitive école pour le fondamental 2 dans la région de Kidal Request for Bids - ML-MEN-362955-CW-RFB / T Building Stronger Pathways f Single Stage - One E Small Works SPD Pending Imp 2024-06-0 ravaux de construction d'un l IDA / 68300 Post Request for Bids Open - National 1,277,400.00 0.00 2023-08-21 2023-08-26 2023-10-07 2023-11-06 2023-12-11 or Girls Education Success nvelope (1 envelope proce lementation 8 ycée dans l'AE de Kati (Morib ss) abougou) Request for Bids - ML-MEN-362959-CW-RFB / T Building Stronger Pathways f Single Stage - One E Small Works SPD Pending Imp 2024-06-0 ravaux de construction d'un l IDA / 68300 Post Request for Bids Open - National 1,277,400.00 0.00 2023-08-21 2023-08-26 2023-10-07 2023-11-06 2023-12-11 or Girls Education Success nvelope (1 envelope proce lementation 8 ycée dans l'AE de Ségou (Far ss) ako) Request for Bids - ML-MEN-362961-CW-RFB / T Building Stronger Pathways f Single Stage - One E Small Works SPD Pending Imp 2024-06-0 ravaux de construction d'un l IDA / 68300 Post Request for Bids Open - National 1,277,400.00 0.00 2023-08-21 2023-08-26 2023-10-07 2023-11-06 2023-12-11 or Girls Education Success nvelope (1 envelope proce lementation 8 ycée dans l'AE de Ségou (Sa ss) nando) Request for Bids - ML-MEN-362965-CW-RFB / T Building Stronger Pathways f Single Stage - One E Small Works SPD Pending Imp 2024-08-0 ravaux de construction d'un l IDA / 68300 Post Request for Bids Open - National 1,277,400.00 0.00 2023-10-16 2023-10-21 2023-12-02 2024-01-01 2024-02-05 or Girls Education Success nvelope (1 envelope proce lementation 3 ycée dans l'AE de Bandiagar ss) a (Nigari) ML-MEN-367029-CW-RFB / T ravaux d'extension de salles de classe dans 10 Lycées pu Request for Bids - blics ( Yanfolila, Yacouba TRA Building Stronger Pathways f Single Stage - One E Small Works SPD Pending Imp 2024-04-1 IDA / D7730 Post Request for Bids Open - National 1,000,000.00 0.00 2023-06-30 2023-07-05 2023-08-16 2023-09-15 2023-10-20 ORE de San,Diéma,Kita,Kalab or Girls Education Success nvelope (1 envelope proce lementation 7 ancoro,Fayçal Ibn Abdel A de ss) Banamba,Kalilou Fofana de B ougouni,Hamadoun DICKO d e Sevaré,Mopti,Diéma ML-MEN-362908-CW-RFQ / T Request for Quota ravaux de construction de 2 Building Stronger Pathways f Request for Quota Single Stage - One E tions - Small Work Pending Imp 2023-12-2 Kits (3 salles de classe ,Bure IDA / D7730 Post Limited 130,000.00 0.00 2023-06-28 2023-08-23 or Girls Education Success tions nvelope s (Emergency) SP lementation 1 au+magasin et bloc latrine) D -Competitive école pour le fondamental 2 dans la région de Nara ML-MEN-362921-CW-RFQ / T ravaux de construction d'un Request for Quota kit (3 salles de classe ,Burea Building Stronger Pathways f Request for Quota Single Stage - One E tions - Small Work Pending Imp 2023-12-2 IDA / D7730 Post Limited 65,000.00 0.00 2023-06-28 2023-08-23 u+magasin et bloc latrine) éc or Girls Education Success tions nvelope s (Emergency) SP lementation 1 ole pour le fondamental 2 da D -Competitive ns la région de Gourma Rhar ous Request for Bids - ML-MEN-362964-CW-RFB / T Building Stronger Pathways f Single Stage - One E Small Works SPD Pending Imp 2024-09-0 ravaux de construction d'un l IDA / 68300 Post Request for Bids Open - National 1,277,400.00 0.00 2023-11-20 2023-11-25 2024-01-06 2024-02-05 2024-03-11 or Girls Education Success nvelope (1 envelope proce lementation 7 ycée dans l'AE de Douentza ( ss) Bamba) Request for Bids - ML-MEN-362953-CW-RFB / T Building Stronger Pathways f Single Stage - One E Small Works SPD Pending Imp 2024-06-0 ravaux de construction d'un l IDA / 68300 Post Request for Bids Open - National 1,277,400.00 0.00 2023-08-21 2023-08-26 2023-10-07 2023-11-06 2023-12-11 or Girls Education Success nvelope (1 envelope proce lementation 8 ycée dans l'AE de Kalaban Co ss) ro (Kouralé) ML-MEN-362907-CW-RFB / T Request for Bids - ravaux de construction de 9 Building Stronger Pathways f Single Stage - One E Small Works SPD Pending Imp 2024-02-1 Kits (3 salles de classe ,Bure IDA / D7730 Post Request for Bids Open - National 585,000.00 0.00 2023-06-23 2023-06-28 2023-08-09 2023-09-08 2023-10-13 or Girls Education Success nvelope (1 envelope proce lementation 0 au+magasin et bloc latrine) ss) école pour le fondamental 2 dans la région de Mopti Request for Bids - ML-MEN-362962-CW-RFB / T Building Stronger Pathways f Single Stage - One E Small Works SPD Pending Imp 2024-08-0 ravaux de construction d'un l IDA / 68300 Post Request for Bids Open - National 1,277,400.00 0.00 2023-10-16 2023-10-21 2023-12-02 2024-01-01 2024-02-05 or Girls Education Success nvelope (1 envelope proce lementation 3 ycée dans l'AE de Mopti (Kon ss) na) ML-MEN-362902-CW-RFB / T Request for Bids - ravaux de construction de 23 Building Stronger Pathways f Single Stage - One E Small Works SPD Pending Imp 2024-02-1 Kits (3 salles de classe ,Bure TF / B3129 Post Request for Bids Open - National 1,495,000.00 0.00 2023-06-23 2023-06-28 2023-08-09 2023-09-08 2023-10-13 or Girls Education Success nvelope (1 envelope proce lementation 0 au+magasin et bloc latrine) ss) école pour le fondamental 2 dans la région de Koulikoro Page 1 Request for Bids - ML-MEN-249621-CW-RFB / T Building Stronger Pathways f Single Stage - One E Small Works SPD Pending Imp 2024-06-0 ravaux de construction d'un l IDA / 68300 Post Request for Bids Open - National 1,277,400.00 0.00 2023-08-21 2023-08-26 2023-10-07 2023-11-06 2023-12-11 or Girls Education Success nvelope (1 envelope proce lementation 8 ycée dans l'AE de Bamako R ss) D (Sénou) ML-MEN-362901-CW-RFB / T ravaux de construction de 12 Building Stronger Pathways f Pending Imp 2024-02-1 Kits de (3 salles de classe ,Bu TF / B3129 Post Request for Bids 780,000.00 0.00 2023-06-23 2023-06-28 2023-08-09 2023-09-08 2023-10-13 or Girls Education Success lementation 0 reau+magasin et bloc latrine ) école pour le fondamental 2 dans la région de Kita ML-MEN-362899-CW-RFQ / T Request for Quota ravaux de construction d'un Building Stronger Pathways f Request for Quota Single Stage - One E tions - Small Work Pending Imp 2024-02-1 KIT de (3 salles de classe ,Bu TF / B3129 Post Limited 65,000.00 0.00 2023-06-28 2023-08-23 or Girls Education Success tions nvelope s (Emergency) SP lementation 9 reau+magasin et bloc latrine D -Competitive ) école pour le fondamental 2 dans la région de Nioro ML-MEN-362904-CW-RFB / T Request for Bids - ravaux de construction de 7 Building Stronger Pathways f Single Stage - One E Small Works SPD Pending Imp 2024-02-1 Kits (3 salles de classe ,Bure IDA / D7730 Post Request for Bids Open - National 455,000.00 0.00 2023-06-23 2023-06-28 2023-08-09 2023-09-08 2023-10-13 or Girls Education Success nvelope (1 envelope proce lementation 0 au+magasin et bloc latrine) ss) école pour le fondamental 2 dans la région de Dioïla ML-MEN-362906-CW-RFB / T Request for Bids - ravaux de construction de 11 Building Stronger Pathways f Single Stage - One E Small Works SPD Pending Imp 2024-02-1 Kits (3 salles de classe ,Bure IDA / D7730 Post Request for Bids Open - National 715,000.00 0.00 2023-06-23 2023-06-28 2023-08-09 2023-09-08 2023-10-13 or Girls Education Success nvelope (1 envelope proce lementation 0 au+magasin et bloc latrine) ss) école pour le fondamental 2 dans la région de Koutiala ML-MEN-362915-CW-RFQ / T ravaux de construction de 2 Kits (3 salles de classe ,Bure Building Stronger Pathways f Request for Quota Pending Imp 2023-12-2 IDA / D7730 Post 130,000.00 0.00 2023-06-28 2023-08-23 au+magasin et bloc latrine) or Girls Education Success tions lementation 1 école pour le fondamental 2 dans la région de Tomboucto u ML-MEN-362912-CW-RFB / T Request for Bids - ravaux de construction de 6 Building Stronger Pathways f Single Stage - One E Small Works SPD Pending Imp 2024-02-1 Kits (3 salles de classe ,Bure IDA / D7730 Post Request for Bids Open - National 390,000.00 0.00 2023-06-23 2023-06-28 2023-08-09 2023-09-08 2023-10-13 or Girls Education Success nvelope (1 envelope proce lementation 0 au+magasin et bloc latrine)é ss) cole pour le fondamental 2 d ans la région de Ségou ML-MEN-362918-CW-RFB / T Request for Bids - ravaux de construction de 11 Building Stronger Pathways f Single Stage - One E Small Works SPD Pending Imp 2024-02-1 Kits (3 salles de classe ,Bure IDA / D7730 Post Request for Bids Open - National 715,000.00 0.00 2023-06-23 2023-06-28 2023-08-09 2023-09-08 2023-10-13 or Girls Education Success nvelope (1 envelope proce lementation 0 au+magasin et bloc latrine) ss) école pour le fondamental 2 dans la région de Douentza ML-MEN-362920-CW-RFB / T Request for Bids - ravaux de construction de 11 Building Stronger Pathways f Single Stage - One E Small Works SPD Pending Imp 2024-02-1 KITS (3 salles de classe ,Bure IDA / D7730 Post Request for Bids Open - National 715,000.00 0.00 2023-06-23 2023-06-28 2023-08-09 2023-09-08 2023-10-13 or Girls Education Success nvelope (1 envelope proce lementation 0 au+magasin et bloc latrine) ss) école pour le fondamental 2 dans la région de Gao Request for Bids - ML-MEN-362956-CW-RFB / T Building Stronger Pathways f Single Stage - One E Small Works SPD Pending Imp 2024-06-0 ravaux de construction d'un l IDA / 68300 Post Request for Bids Open - National 1,277,400.00 0.00 2023-08-21 2023-08-26 2023-10-07 2023-11-06 2023-12-11 or Girls Education Success nvelope (1 envelope proce lementation 8 ycée dans l'AE de Dioïla (Bél ss) éko) Request for Bids - ML-MEN-362957-CW-RFB / T Building Stronger Pathways f Single Stage - One E Small Works SPD Pending Imp 2024-09-0 ravaux de construction d'un l IDA / 68300 Post Request for Bids Open - National 1,277,400.00 0.00 2023-11-20 2023-11-25 2024-01-06 2024-02-05 2024-03-11 or Girls Education Success nvelope (1 envelope proce lementation 7 ycée dans l'AE de Sikasso (Ki ss) gnan) Request for Bids - ML-MEN-362985-CW-RFB / T Building Stronger Pathways f Single Stage - One E Small Works SPD Pending Imp 2025-08-1 ravaux de construction d'un l IDA / 68300 Post Request for Bids Open - National 1,500,000.00 0.00 2024-08-30 2024-09-04 2024-10-16 2024-11-15 2024-12-20 or Girls Education Success nvelope (1 envelope proce lementation 7 ycée d'excellence à Ségou ss) ML-MEN-249623-CW-RFB / T Request for Bids - ravaux de construction d'un l Building Stronger Pathways f Single Stage - One E Small Works SPD Pending Imp 2025-06-2 IDA / 68300 Post Request for Bids Open - National 1,500,000.00 0.00 2024-09-02 2024-09-07 2024-10-19 2024-11-18 2024-12-23 ycée d'excellence dans la co or Girls Education Success nvelope (1 envelope proce lementation 1 mmune du Mandé ss) ML-MEN-362916-CW-RFB / T Request for Bids - ravaux de construction de 5 Building Stronger Pathways f Single Stage - One E Small Works SPD Pending Imp 2024-02-1 Kits (3 salles de classe ,Bure IDA / D7730 Post Request for Bids Open - National 325,000.00 0.00 2023-06-23 2023-06-28 2023-08-09 2023-09-08 2023-10-13 or Girls Education Success nvelope (1 envelope proce lementation 0 au+magasin et bloc latrine)é ss) cole pour le fondamental 2 d ans la région de Bandiagara Request for Bids - ML-MEN-362958-CW-RFB / T Building Stronger Pathways f Single Stage - One E Small Works SPD Pending Imp 2024-08-0 ravaux de construction d'un l IDA / 68300 Post Request for Bids Open - National 1,277,400.00 0.00 2023-10-16 2023-10-21 2023-12-02 2024-01-01 2024-02-05 or Girls Education Success nvelope (1 envelope proce lementation 3 ycée dans l'AE de Koutiala (M ss) olobala) ML-MEN-362900-CW-RFB / T Request for Bids - ravaux de construction de 7 Building Stronger Pathways f Single Stage - One E Small Works SPD Pending Imp 2024-02-1 Kits (3 salles de classe ,Bure TF / B3129 Post Request for Bids Open - National 455,000.00 0.00 2023-06-23 2023-06-28 2023-08-09 2023-09-08 2023-10-13 or Girls Education Success nvelope (1 envelope proce lementation 0 au+magasin et bloc latrine) ss) école pour le fondamental 2 dans la région de Kayes ML-MEN-362913-CW-RFB / T Request for Bids - ravaux de construction de 11 Building Stronger Pathways f Single Stage - One E Small Works SPD Pending Imp 2024-02-1 Kits(3 salles de classe ,Burea IDA / D7730 Post Request for Bids Open - National 715,000.00 0.00 2023-06-23 2023-06-28 2023-08-09 2023-09-08 2023-10-13 or Girls Education Success nvelope (1 envelope proce lementation 0 u+magasin et bloc latrine) éc ss) ole pour le fondamental 2 da ns la région de Sikasso ML-MEN-263200-CW-RFB / T Request for Bids - ravaux de construction 20 Kit Building Stronger Pathways f Single Stage - One E Small Works SPD Pending Imp 2024-04-0 s (3 salles de classe ,Bureau TF / B3129 Post Request for Bids Open - National 1,300,000.00 0.00 2023-06-16 2023-06-21 2023-08-02 2023-09-01 2023-10-06 or Girls Education Success nvelope (1 envelope proce lementation 3 +magasin et bloc latrine) éco ss) le pour le fondamental 2 dan s le district de Bamako GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ML-MEN-249613-GO-RFB / A cquisition de matériels pour l' Accelerating Learning throu Open - Internationa Single Stage - One E Pending Impl extension du Progiciel de Ges IDA / D7730 Prior Request for Bids 5,746,992.00 0.00 2021-11-29 2021-12-04 2022-01-15 2022-02-14 2022-03-21 2022-09-17 gh Improved Quality l nvelope ementation tion Intégrée (PGI) aux ensei gnements fondamental et se condaire Page 2 ML-MEN-249624-GO-RFB / A Building Stronger Pathways f Single Stage - One E Pending Impl cquisition de mobiliers pour s IDA / 68300 Prior Request for Bids Open - National 2,190,893.00 0.00 2022-08-15 2022-08-20 2022-10-01 2022-10-31 2022-12-05 2023-06-03 or Girls Education Success nvelope ementation alles de classe aux lycées ML-MEN-263053-GO-RFB / A Strengthening Monitoring an Single Stage - One E Under Imple cquisition de véhicules pour l TF / B3129 d Evaluation and Supporting Post Request for Bids Open - National 280,000.00 0.00 2021-11-29 2022-08-04 2021-12-04 2022-08-19 2022-01-15 2022-09-26 2022-02-14 2022-11-14 2022-03-21 2022-07-19 nvelope mentation 'unité de facilitation de projet Project Management ML-MEN-263054-GO-RFB / A Strengthening Monitoring an cquisition de matériels et mo Single Stage - One E Under Imple TF / B3129 d Evaluation and Supporting Post Request for Bids Open - National 104,140.00 0.00 2021-11-30 2022-08-04 2021-12-05 2022-08-19 2022-01-16 2022-09-27 2022-02-15 2022-11-14 2022-03-22 2022-07-20 biliers de bureau pour l'unité nvelope mentation Project Management de facilitation de projet ML-MEN-263187-GO-RFB / A Strengthening Monitoring an cquisition de matériels pour l Single Stage - One E Pending Impl TF / B3129 d Evaluation and Supporting Post Request for Bids Open - National 160,000.00 0.00 2022-01-31 2022-02-05 2022-03-19 2022-04-18 2022-05-23 2022-11-19 e système de suivi automatis nvelope ementation Project Management é des cantines scolaires ML-MEN-263190-GO-RFQ / A Strengthening the Governan cquisition de matériels de pr Request for Quota Single Stage - One E Pending Impl TF / B4948 ce and Resilience of the Edu Post Open - National 20,000.00 0.00 2022-02-19 2022-04-16 2022-10-13 évention du COVID 19 pour l tions nvelope ementation cation System es comités pédagogiques ML-MEN-263192-GO-RFB / A Strengthening the Governan Single Stage - One E Pending Impl cquisition de matériels pour l TF / B4948 ce and Resilience of the Edu Post Request for Bids Open - National 124,900.00 0.00 2022-02-08 2022-02-13 2022-03-27 2022-04-26 2022-05-31 2022-11-27 nvelope ementation e studio d'enregistrement cation System ML-MEN-263196-GO-RFB / A Accelerating Learning throu Single Stage - One E Pending Impl cquisition de matériels pour l TF / B3129 Post Request for Bids Open - National 964,792.00 0.00 2022-03-21 2022-03-26 2022-05-07 2022-06-06 2022-07-11 2023-01-07 gh Improved Quality nvelope ementation a robotique au profit de 02 cl ubs régionaux ML-MEN-263197-GO-RFB / A Accelerating Learning throu Single Stage - One E Pending Impl cquisition de matériels pour l TF / B3129 Post Request for Bids Open - National 310,000.00 0.00 2022-03-25 2022-03-30 2022-05-11 2022-06-10 2022-07-15 2023-01-11 gh Improved Quality nvelope ementation es évaluations et études ML-MEN-249618-GO-RFB / A Accelerating Learning throu Single Stage - One E Pending Impl cquisition de manuels scolair IDA / D7730 Post Request for Bids Open - National 1,550,520.00 0.00 2023-06-30 2023-07-05 2023-08-16 2023-09-15 2023-10-20 2024-04-17 gh Improved Quality nvelope ementation es pour les lycées ML-MEN-249620-GO-RFB / A Accelerating Learning throu Single Stage - One E Pending Impl cquisition de tableaux intera IDA / D7730 Post Request for Bids Open - National 1,944,000.00 0.00 2023-10-09 2023-10-14 2023-11-25 2023-12-25 2024-01-29 2024-07-27 gh Improved Quality nvelope ementation ctifs dans les lycées ML-MEN-249619-GO-RFB / A Accelerating Learning throu Single Stage - One E Pending Impl cquisition de matériels de lab IDA / D7730 Post Request for Bids Open - National 1,185,000.00 0.00 2023-06-20 2023-06-25 2023-08-06 2023-09-05 2023-10-10 2024-04-07 gh Improved Quality nvelope ementation oratoires pour les lycées ML-MEN-249616-GO-RFB / A Strengthening the Governan cquisition de matériels pour l Single Stage - One E Pending Impl IDA / D7730 ce and Resilience of the Edu Post Request for Bids Open - National 130,000.00 0.00 2023-07-17 2023-07-22 2023-09-02 2023-10-02 2023-11-06 2024-05-04 es systèmes de suivi à distan nvelope ementation cation System ce (KoBo Toolbox) et itératif des bénéficiaires ML-MEN-362987-GO-RFB / A Accelerating Learning throu Single Stage - One E Pending Impl cquisition de manuels scolair TF / B3129 Prior Request for Bids Open - National 3,811,641.00 0.00 2023-06-30 2023-07-05 2023-08-16 2023-09-15 2023-10-20 2024-04-17 gh Improved Quality nvelope ementation es pour le fondamental 1 ML-MEN-362988-GO-RFB / A Accelerating Learning throu Single Stage - One E Pending Impl cquisition de manuels scolair TF / B3129 Post Request for Bids Open - National 1,094,812.00 0.00 2023-06-30 2023-07-05 2023-08-16 2023-09-15 2023-10-20 2024-04-17 gh Improved Quality nvelope ementation es pour le fondamental 2 ML-MEN-362990-GO-RFQ / A Accelerating Learning throu Request for Quota Single Stage - One E Pending Impl cquisition de matériels pédag TF / B3129 Post Limited 96,200.00 0.00 2023-07-12 2023-09-06 2024-01-04 gh Improved Quality tions nvelope ementation ogiques pour l'ENSup ML-MEN-362991-GO-RFQ / A Accelerating Learning throu Request for Quota Single Stage - One E Pending Impl cquisition de matériels et mo TF / B3129 Post Limited 66,700.00 0.00 2023-07-12 2023-09-06 2023-12-05 gh Improved Quality tions nvelope ementation biliers de bureau pour l'ENSU P ML-MEN-363019-GO-RFB / A Strengthening the Governan Open - Internationa Single Stage - One E Pending Impl cquisition de kits scolaires po TF / B4949 ce and Resilience of the Edu Prior Request for Bids 4,709,496.00 0.00 2023-06-27 2023-07-02 2023-08-16 2023-09-15 2023-10-20 2024-04-17 l nvelope ementation ur le fondamental cation System ML-MEN-362925-GO-RFB / A cquisition de mobiliers pour l Building Stronger Pathways f Single Stage - One E Pending Impl IDA / D7730 Post Request for Bids Open - National 187,740.00 0.00 2023-08-01 2023-08-06 2023-09-17 2023-10-17 2023-11-21 2024-01-20 es kits écoles au fondamenta or Girls Education Success nvelope ementation l 2 dans les régions de Dioïla , Nara, San et Ségou ML-MEN-362924-GO-RFB / A cquisition de mobiliers pour l Building Stronger Pathways f Single Stage - One E Pending Impl TF / B3129 Post Request for Bids Open - National 375,480.00 0.00 2023-08-01 2023-08-06 2023-09-17 2023-10-17 2023-11-21 2024-01-20 es kits écoles au fondamenta or Girls Education Success nvelope ementation l 2 dans les régions de Bougo uni et Koulikoro ML-MEN-263210-GO-RFB / A cquisition de mobiliers pour l Building Stronger Pathways f Single Stage - One E Pending Impl es kits écoles au fondamenta TF / B3129 Post Request for Bids Open - National 357,600.00 0.00 2022-10-25 2022-10-30 2022-12-11 2023-01-10 2023-02-14 2023-08-13 or Girls Education Success nvelope ementation l 2 dans les régions de Kayes , Kita, Nioro et le district de B amako ML-MEN-362930-GO-RFB / A cquisition de mobiliers pour l Building Stronger Pathways f Single Stage - One E Pending Impl es kits écoles au fondamenta IDA / D7730 Post Request for Bids Open - National 223,500.00 0.00 2023-08-01 2023-08-06 2023-09-17 2023-10-17 2023-11-21 2024-01-20 or Girls Education Success nvelope ementation l 2 dans les régions de Bandi agara, Douentza et Mopti ML-MEN-362927-GO-RFB / A cquisition de mobiliers pour l Building Stronger Pathways f Single Stage - One E Pending Impl IDA / D7730 Post Request for Bids Open - National 196,680.00 0.00 2023-08-01 2023-08-06 2023-09-17 2023-10-17 2023-11-21 2024-01-20 es kits écoles au fondamenta or Girls Education Success nvelope ementation l 2 dans les régions de Kouti ala et Sikasso ML-MEN-362947-GO-RFQ / A Building Stronger Pathways f Request for Quota Single Stage - One E Pending Impl cquisition de mobiliers scolai IDA / D7730 Post Limited 91,440.00 0.00 2023-10-07 2023-12-02 2024-01-31 or Girls Education Success tions nvelope ementation res pour les lycées des AE de Dioïla et Ségou ML-MEN-362940-GO-RFQ / A cquisition de mobiliers scolai Building Stronger Pathways f Request for Quota Pending Impl IDA / D7730 Post 91,440.00 0.00 2023-10-07 2023-12-02 2024-01-31 res pour les lycées des AE de or Girls Education Success tions ementation Bamako RD, Kalaban Coro et Kati Page 3 ML-MEN-362948-GO-RFQ / A cquisition de mobiliers scolai Building Stronger Pathways f Request for Quota Pending Impl IDA / D7730 Post 60,960.00 0.00 2023-10-07 2023-12-02 2024-01-31 res pour les lycées des AE de or Girls Education Success tions ementation Koutiala et Sikasso ML-MEN-362949-GO-RFQ / A cquisition de mobiliers scolai Building Stronger Pathways f Request for Quota Single Stage - One E Pending Impl IDA / D7730 Post Limited 91,440.00 0.00 2023-10-07 2023-12-02 2024-01-31 res pour les lycées des AE de or Girls Education Success tions nvelope ementation Bandiagara, Douentza et Mo pti ML-MEN-362931-GO-RFQ / A cquisition de mobiliers pour l Building Stronger Pathways f Request for Quota Single Stage - One E Pending Impl es kits écoles au fondamenta IDA / D7730 Post Limited 151,980.00 0.00 2023-08-06 2023-10-01 2024-03-29 or Girls Education Success tions nvelope ementation l 2 dans la région de Gao, Go urma Rharous, Kidal et Tomb ouctou NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ML-MEN-245939-NC-RFQ / Mi Strengthening Monitoring an Request for Quota Single Stage - One E gration et paramétrage du lo IDA / D7730 d Evaluation and Supporting Post Open - National 31,200.00 0.00 Canceled 2021-09-05 2022-06-27 2021-10-31 2021-12-30 tions nvelope giciel de gestion comptable e Project Management t financière ML-MEN-316867-NC-DIR / Mi Strengthening Monitoring an Under Imple gration et paramétrage du lo IDA / D7730 d Evaluation and Supporting Post Direct Selection Direct - National 56,000.00 0.00 2022-09-19 2022-09-29 2022-09-24 2022-10-28 2022-10-29 2023-05-17 mentation giciel de gestion comptable e Project Management t financière ML-MEN-363002-NC-RFQ / Cr Strengthening Monitoring an Request for Quota Single Stage - One E Pending Impl éation et animation du site in IDA / D7730 d Evaluation and Supporting Post Limited 10,000.00 0.00 2023-07-05 2023-08-30 2023-10-29 tions nvelope ementation ternet du projet MIQRA Project Management CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ML-MEN-245945-CS-CQS / R ecrutement d’un bureau pour les études et le contrôle des Building Stronger Pathways f Consultant Qualifi Pending Impleme IDA / 68300 Post Open - National 152,203.00 0.00 2021-10-04 2021-10-25 2021-12-08 2022-01-07 2022-02-11 2022-11-08 travaux de construction et d’ or Girls Education Success cation Selection ntation extension des lycées des AE de Ségou, San, Mopti et Dou entza ML-MEN-245943-CS-CQS / R ecrutement d'une ONG pour l Strengthening the Governan Quality And Cost- Open - Internationa Under Implement e suivi des activités des écol IDA / 68300 ce and Resilience of the Edu Post 532,589.00 0.00 2021-11-30 2023-06-27 2021-12-21 2022-02-03 2022-03-03 2022-04-02 2022-05-07 2022-06-11 2023-06-11 Based Selection l ation es fondamentales dans les zo cation System nes difficiles d'accès dû à l'in sécurité ML-MEN-245942-CS-CQS / R ecrutement d'une assistance Accelerating Learning throu Quality And Cost- Open - Internationa Under Implement technique aux CGS pour l'ap IDA / 68300 Prior 1,000,000.00 0.00 2021-11-30 2021-12-21 2022-02-03 2022-03-03 2022-04-02 2022-05-07 2022-06-11 2023-06-11 gh Improved Quality Based Selection l ation pui à la préparation et la mis e en œuvre de plans d'améli oration d'école (PAE). ML-MEN-259798-CS-CQS / R Strengthening Monitoring an Consultant Qualifi Under Implement ecrutement d'un cabinet pou IDA / D7730 d Evaluation and Supporting Post Open - National 158,400.00 0.00 2021-11-19 2021-11-16 2021-12-10 2022-06-27 2022-01-23 2022-08-03 2022-02-22 2022-10-05 2022-03-29 2023-03-24 cation Selection ation r l'audit interne Project Management ML-MEN-263051-CS-QCBS / Strengthening Monitoring an Recrutement d'un cabinet po Quality And Cost- Under Implement TF / B3129 d Evaluation and Supporting Post Open - National 53,650.00 0.00 2021-11-22 2021-12-05 2021-12-13 2022-06-27 2022-01-26 2022-08-22 2022-02-23 2022-09-01 2022-03-25 2022-10-03 2022-04-29 2022-11-08 2022-06-03 2023-06-03 ur l'audit externe du projet p Based Selection ation Project Management our les exercices 2021, 2022 et 2023 ML-MEN-263056-CS-QCBS / Strengthening the Governan Recrutement d'un bureau d'é Quality And Cost- Pending Impleme TF / B4948 ce and Resilience of the Edu Post Open - National 90,000.00 0.00 2021-12-27 2022-01-17 2022-03-02 2022-03-30 2022-04-29 2022-06-03 2022-07-08 2023-01-04 tudes pour l'Inventaire des re Based Selection ntation cation System ssources pédagogiques ML-MEN-263150-CS-QCBS / Strengthening Monitoring an Recrutement d'un consultant Quality And Cost- Pending Impleme TF / B3129 d Evaluation and Supporting Post Open - National 20,000.00 0.00 2021-12-30 2022-01-20 2022-03-05 2022-04-02 2022-05-02 2022-06-06 2022-07-11 2022-11-08 pour l'élaboration d'un manu Based Selection ntation Project Management el de réponse aux crises ML-MEN-263183-CS-QCBS / Recrutement d'une assistanc Accelerating Learning throu Quality And Cost- Under Implement e technique aux structures e TF / B3129 Post Open - National 350,000.00 0.00 2022-01-24 2022-11-06 2022-02-14 2022-03-30 2022-04-27 2022-05-27 2022-07-01 2022-08-05 2023-08-05 gh Improved Quality Based Selection ation n charge des examens et l'év aluation des apprentissages ML-MEN-362875-CS-CQS / E valuation indépendante des Strengthening Monitoring an Consultant Qualifi Pending Impleme décaissements liés aux condi IDA / D7730 d Evaluation and Supporting Post Open - National 200,000.00 0.00 2023-06-15 2023-07-06 2023-08-19 2023-09-18 2023-10-23 2025-10-12 cation Selection ntation tions basées sur la performa Project Management nce (CBP) au titre des exercic es 2023 et 2024 ML-MEN-245950-CS-CQS / R ecrutement d'un bureau d'ét Strengthening Monitoring an Quality And Cost- udes pour les évaluations ind IDA / 68300 d Evaluation and Supporting Post Open - National 500,000.00 0.00 Canceled 2021-12-28 2023-04-12 2022-01-18 2022-03-03 2022-03-31 2022-04-30 2022-06-04 2022-07-09 2023-07-09 Based Selection épendantes des Décaisseme Project Management nts Liés aux Résultats (DLR) ML-MEN-362886-CS-CQS / El aboration de la stratégie de f Accelerating Learning throu Consultant Qualifi Pending Impleme IDA / D7730 Post Open - National 160,000.00 0.00 2023-06-15 2023-07-06 2023-08-19 2023-09-18 2023-10-23 2024-01-21 ormation continue des ensei gh Improved Quality cation Selection ntation gnants du secondaire généra l ML-MEN-249612-CS-CQS / R ecrutement d'un bureau d'ét Contingent Emergency Resp Consultant Qualifi IDA / D7730 Post Open - National 120,000.00 0.00 Canceled 2021-11-30 2023-04-12 2021-12-21 2022-02-03 2022-03-05 2022-04-09 2022-10-06 udes pour l'évaluation des be onse cation Selection soins de formation continue dans les lycées Page 4 ML-MEN-245947-CS-CQS / R ecrutement d’un bureau pour Building Stronger Pathways f Consultant Qualifi les études et le contrôle des IDA / 68300 Post Open - National 149,034.00 0.00 Canceled 2021-11-26 2021-12-17 2022-01-30 2022-03-01 2022-04-05 2023-04-05 or Girls Education Success cation Selection travaux de construction de 0 2 lycées d'excellence ML-MEN-362992-CS-CQS / Et ude sur le renforcement des Accelerating Learning throu Consultant Qualifi dispositifs de formations initi TF / B3129 Post Open - National 193,500.00 0.00 Under Review 2023-06-30 2023-06-27 2023-07-21 2023-09-03 2023-10-03 2023-11-07 2024-03-06 gh Improved Quality cation Selection ale et continue dans les Instit uts de Formation des Maîtres (IFM) ML-MEN-362994-CS-CQS / El Accelerating Learning throu Consultant Qualifi aboration des normes éducat IDA / D7730 Post Open - National 160,000.00 0.00 Under Review 2023-06-30 2023-06-27 2023-07-21 2023-09-03 2023-10-03 2023-11-07 2024-03-06 gh Improved Quality cation Selection ives de qualité pour le public et le privé ML-MEN-362997-CS-CQS / S Strengthening the Governan uivi des activités des établiss Consultant Qualifi Pending Impleme TF / B3129 ce and Resilience of the Edu Post Open - National 116,853.00 0.00 2023-09-04 2023-09-25 2023-11-08 2023-12-08 2024-01-12 2025-01-06 ements d'enseignement seco cation Selection ntation cation System ndaire général et les IFM dan s la région de Ségou ML-MEN-362998-CS-CQS / S Strengthening the Governan uivi des activités des établiss Consultant Qualifi Pending Impleme TF / B3129 ce and Resilience of the Edu Post 116,853.00 0.00 2023-09-04 2023-09-25 2023-11-08 2023-12-08 2024-01-12 2025-01-06 ements d'enseignement seco cation Selection ntation cation System ndaire général et les IFM dan s la région de Mopti ML-MEN-363000-CS-CQS / S uivi des activités des établiss Strengthening the Governan Consultant Qualifi Pending Impleme ements d'enseignement seco TF / B3129 ce and Resilience of the Edu Post Open - National 116,853.00 0.00 2023-09-04 2023-09-25 2023-11-08 2023-12-08 2024-01-12 2025-01-06 cation Selection ntation ndaire général et les IFM dan cation System s la région de Tombouctou ML-MEN-363001-CS-CQS / S uivi des activités des établiss Strengthening the Governan Consultant Qualifi Pending Impleme ements d'enseignement seco TF / B3129 ce and Resilience of the Edu Post Open - National 116,853.00 0.00 2023-09-04 2023-09-25 2023-11-08 2023-12-08 2024-01-12 2025-01-06 cation Selection ntation ndaire général et les IFM dan cation System s les régions de Gao, Kidal et Ménaka ML-MEN-362889-CS-CQS / S uivi et contrôle contrôle des Building Stronger Pathways f Consultant Qualifi Pending Impleme travaux de construction des TF / B3129 Post Open - National 77,350.00 0.00 2023-06-16 2023-07-07 2023-08-20 2023-09-19 2023-10-24 2024-03-22 or Girls Education Success cation Selection ntation écoles fondamentales des AE de Gao, Gourma Rharous, Kid al et Tombouctou ML-MEN-363010-CS-CQS / Ét udes complémentaires, Suivi Building Stronger Pathways f Consultant Qualifi Pending Impleme et contrôle des travaux de co IDA / D7730 Post Open - National 357,672.00 0.00 2023-06-30 2023-07-21 2023-09-03 2023-10-03 2023-11-07 2024-06-04 or Girls Education Success cation Selection ntation nstruction des nouveaux lycé es des AE de Bamako RD,Kal aban Coro,Kati et Dioila ML-MEN-266870-CS-CQS / S uivi et contrôle des travaux d Building Stronger Pathways f Consultant Qualifi Pending Impleme e construction des écoles fon TF / B3129 Post Open - National 91,000.00 0.00 2023-06-16 2023-07-07 2023-08-20 2023-09-19 2023-10-24 2024-03-22 or Girls Education Success cation Selection ntation damentales des AE de Kayes, Kéniéba, Kita et Nioro ML-MEN-362892-CS-CQS / S uivi et contrôle des travaux d Building Stronger Pathways f Consultant Qualifi Pending Impleme TF / B3129 Post Open - National 86,450.00 0.00 2023-07-17 2023-08-07 2023-09-20 2023-10-20 2023-11-24 2024-04-22 e construction des écoles fon or Girls Education Success cation Selection ntation damentales des AE de Dioïla, San et Ségou ML-MEN-266869-CS-CQS / S uivi et contrôle des travaux d Building Stronger Pathways f Consultant Qualifi Pending Impleme e construction des écoles fon TF / B3129 Post Open - National 204,750.00 0.00 2023-06-16 2023-07-07 2023-08-20 2023-09-19 2023-10-24 2024-03-22 or Girls Education Success cation Selection ntation damentales des AE de Bama ko RG, Bamako RD, Kalabanc oro, Kati, Koulikoro et Nara ML-MEN-363015-CS-CQS / S uivi et contrôle des travaux d Building Stronger Pathways f Consultant Qualifi Pending Impleme IDA / D7730 Post Open - National 268,254.00 0.00 2023-06-30 2023-07-21 2023-09-03 2023-10-03 2023-11-07 2024-06-04 e construction des nouveaux or Girls Education Success cation Selection ntation lycées des AE de Mopti ,Band iagara et Douentza ML-MEN-266867-CS-CQS / S uivi et contrôle des travaux d Building Stronger Pathways f Consultant Qualifi Pending Impleme e construction des écoles fon TF / B3129 Post Open - National 186,550.00 0.00 2023-06-16 2023-07-07 2023-08-20 2023-09-19 2023-10-24 2024-03-22 or Girls Education Success cation Selection ntation damentales des AE de Bougo uni, Koutiala et Sikasso ML-MEN-266868-CS-CQS / S Building Stronger Pathways f Consultant Qualifi Pending Impleme uivi et contrôle des travaux d TF / B3129 Post Open - National 100,000.00 0.00 2023-06-16 2023-07-07 2023-08-20 2023-09-19 2023-10-24 2024-03-22 or Girls Education Success cation Selection ntation ’extension de salles de class e dans les lycées ML-MEN-363012-CS-CQS / Ét udes complémentaires, Suivi Building Stronger Pathways f Consultant Qualifi Pending Impleme et contrôle des travaux de co IDA / D7730 Post Open - National 357,672.00 0.00 2023-06-30 2023-07-21 2023-09-03 2023-10-03 2023-11-07 2024-06-04 or Girls Education Success cation Selection ntation nstruction des nouveaux lycé es des AE de Sikasso ,Koutial a et Ségou ML-MEN-266866-CS-CQS / S uivi et contrôle des travaux d Building Stronger Pathways f Consultant Qualifi Pending Impleme e construction des écoles fon TF / B3129 Post Open - National 113,750.00 0.00 2023-07-17 2023-08-07 2023-09-20 2023-10-20 2023-11-24 2024-04-22 or Girls Education Success cation Selection ntation damentales des AE de Bandi agara, Douentza, Mopti et Té nenkou ML-MEN-362935-CS-QCBS / Building Stronger Pathways f Quality And Cost- Pending Impleme Etudes et contrôle des travau IDA / D7730 Post Open - National 600,000.00 0.00 2023-07-10 2023-07-31 2023-09-13 2023-10-11 2023-11-10 2023-12-15 2024-01-19 2025-04-13 or Girls Education Success Based Selection ntation x de construction de 02 lycée s d'excellence INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ML-MEN-245915-CS-INDV / R Strengthening Monitoring an Individual Consult ecrutement de l'auditeur inte IDA / D7730 d Evaluation and Supporting Post Open 158,400.00 0.00 Canceled 2021-09-01 2021-10-20 2021-11-10 2021-12-15 2022-12-15 ant Selection rne Project Management ML-MEN-245920-CS-INDV / R Strengthening Monitoring an Individual Consult Under Implement ecrutement du spécialiste en IDA / D7730 d Evaluation and Supporting Post Open 216,000.00 0.00 2021-09-01 2021-10-25 2021-10-20 2021-11-10 2021-12-15 2022-12-15 ant Selection ation passation de marché Project Management Page 5 ML-MEN-245929-CS-INDV / R Strengthening Monitoring an Individual Consult ecrutement de l'environnem IDA / D7730 d Evaluation and Supporting Post Open 177,984.00 27,399.60 Signed 2021-09-01 2021-08-30 2021-10-20 2022-06-27 2021-11-10 2022-06-27 2021-12-15 2022-06-02 2022-12-15 ant Selection entaliste Project Management Strengthening Monitoring an ML-MEN-245931-CS-INDV / R Individual Consult IDA / D7730 d Evaluation and Supporting Post Open 177,984.00 139,281.30 Signed 2021-09-01 2021-08-30 2021-10-20 2022-06-27 2021-11-10 2022-06-27 2021-12-15 2022-06-08 2022-12-15 ecrutement du sociologue ant Selection Project Management Strengthening Monitoring an ML-MEN-245934-CS-INDV / R Individual Consult Under Implement IDA / D7730 d Evaluation and Supporting Post Open 172,800.00 0.00 2021-09-01 2021-10-25 2021-10-20 2022-09-29 2021-11-10 2023-01-23 2021-12-15 2022-12-15 ecrutement du comptable 1 ant Selection ation Project Management Strengthening Monitoring an ML-MEN-245935-CS-INDV / R Individual Consult Under Implement IDA / D7730 d Evaluation and Supporting Post Open 172,800.00 0.00 2021-09-01 2021-10-25 2021-10-20 2022-09-29 2021-11-10 2023-01-23 2021-12-15 2022-12-15 ecrutement du comptable 2 ant Selection ation Project Management ML-MEN-245910-CS-CDS / R Strengthening Monitoring an ecrutement de l’expert 2 en IDA / D7730 d Evaluation and Supporting Post Direct Selection Direct 115,200.00 87,678.72 Signed 2021-08-31 2021-08-27 2021-09-10 2022-06-27 2021-11-14 2021-09-02 2022-11-14 qualité Project Management ML-MEN-245901-CS-CDS / R Strengthening Monitoring an ecrutement du coordinateur t IDA / D7730 d Evaluation and Supporting Post Direct Selection Direct 151,200.00 115,182.65 Signed 2021-08-31 2021-08-27 2021-09-10 2022-06-27 2021-11-14 2021-09-02 2022-11-14 echnique Project Management ML-MEN-245908-CS-CDS / R Strengthening Monitoring an ecrutement de l’expert 1 en IDA / D7730 d Evaluation and Supporting Post Direct Selection Direct 115,200.00 87,678.72 Signed 2021-08-31 2021-08-27 2021-09-10 2022-06-27 2021-11-14 2021-09-02 2022-11-14 qualité Project Management ML-MEN-245913-CS-CDS / R Strengthening Monitoring an ecrutement de l'expert en ac IDA / D7730 d Evaluation and Supporting Post Direct Selection Direct 115,200.00 87,758.21 Signed 2021-08-31 2021-08-27 2021-09-10 2022-06-27 2021-11-14 2021-09-02 2022-11-14 cès Project Management ML-MEN-299252-CS-CDS / « Recrutement de l'UNICEF pou r la mise en œuvre d’activité s des sous composante 3.1. I Contingent Emergency Resp nnovations communautaires TF / B4948 Prior Direct Selection Direct 7,609,100.00 7,533,040.00 Signed 2022-06-11 2022-06-27 2022-06-21 2022-07-27 2022-08-25 2021-06-03 2023-05-22 onse pour une meilleure résilience et une meilleure prestation d e services éducatifs et 3.2. Ri poste du secteur de l'éducati on au COVID-19 » ML-MEN-297834-CS-INDV / R Strengthening Monitoring an Individual Consult ecrutement d'un expert en Vi IDA / D7730 d Evaluation and Supporting Post Open 216,000.00 0.00 Canceled 2022-06-15 2022-06-05 2022-08-03 2022-08-24 2022-09-28 2023-09-23 ant Selection olences basées sur le Genre ( Project Management VBG) ML-MEN-318856-CS-INDV / R Strengthening Monitoring an Individual Consult Under Implement ecrutement d’un expert en Vi IDA / D7730 d Evaluation and Supporting Post Open - National 216,000.00 0.00 2022-10-14 2022-10-21 2022-12-02 2022-12-23 2023-01-27 2028-12-26 ant Selection ation olences basées sur le Genre ( Project Management VBG) ML-MEN-245933-CS-INDV / R Strengthening Monitoring an Individual Consult ecrutement du spécialiste en IDA / D7730 d Evaluation and Supporting Post Open 216,000.00 0.00 Canceled 2021-09-01 2021-10-20 2021-11-10 2021-12-15 2022-12-15 ant Selection gestion financière Project Management ML-MEN-330746-CS-CDS / R Strengthening Monitoring an ecrutement d'un expert Spéc Under Implement IDA / D7730 d Evaluation and Supporting Post Direct Selection Direct - National 46,000.00 0.00 2022-12-12 2022-12-21 2022-12-22 2022-12-28 2023-02-25 2023-04-16 ialiste en Passation de March ation Project Management és en appui au projet ML-MEN-331313-CS-CDS / R ecrutement d'un consultant p Strengthening Monitoring an our l'évaluation indépendant Under Implement IDA / D7730 d Evaluation and Supporting Post Direct Selection Direct - National 42,000.00 0.00 2022-12-16 2022-12-23 2022-12-26 2022-12-28 2023-03-01 2023-04-20 e des décaissements liés aux ation Project Management conditions basées sur la perf ormance (CBP) au titre de l'a n 1 du projet ML-MEN-354828-CS-INDV / R Strengthening Monitoring an ecrutement d’un consultant i Individual Consult Direct - Internation Under Implement TF / B3129 d Evaluation and Supporting Post 65,812.00 0.00 2023-04-07 2023-04-12 2023-04-17 2023-05-08 2023-06-12 2024-01-08 nternational pour l’assistanc ant Selection al ation Project Management e à l’élaboration du Pacte de partenariat ML-MEN-354843-CS-INDV / R Strengthening Monitoring an ecrutement d’un consultant Individual Consult TF / B3129 d Evaluation and Supporting Post Direct - National 47,010.00 0.00 Under Review 2023-04-07 2023-04-12 2023-04-17 2023-05-08 2023-06-12 2024-01-08 national pour l’assistance à l’ ant Selection Project Management élaboration du Pacte de part enariat Strengthening Monitoring an ML-MEN-363004-CS-INDV / C Individual Consult Under Implement IDA / D7730 d Evaluation and Supporting Post Open - National 55,163.00 0.00 2023-06-16 2023-06-26 2023-08-04 2023-08-25 2023-09-29 2024-01-27 onsultant en sécurité ant Selection ation Project Management Page 6 REPUBLIQUE DE COTE D’IVOIRE UNION-DISCIPLINE-TRAVAIL PROJET D’AMELIORATION ET DE MISE EN ŒUVRE DE LA POLITIQUE FONCIERE RURALE Plan de Passation des Marchés I. GÉNÉRALITÉS 1.1. Information générale sur le Projet Pays : République de Côte d’Ivoire Emprunteur : Gouvernement de Côte d’Ivoire ; Nom du Projet : Projet d’Amélioration et de Mise en Œuvre de la Politique Foncière Rurale Numéros du Crédit : IDA-6190 Montant du Crédit : 50 000 000 $ US Unité de Gestion du Projet : Agence Foncière Rurale (AFOR) 1.2 Date d’approbation du Plan de Passation de Marchés : Plan original : ……………………………. 1.3 Date de publication de l’avis général de passation de marchés : ………………… 1.4 Période couverte par le Plan de passation des marchés : 18 premiers mois II. Fournitures, Travaux et Services Assimilés 2.1. Seuils d’examen préalable Marchés qui seront soumis à l'examen préalable de la banque conformément aux nouveaux seuils de revue en fonction des risques attribués au projet après le dernier PPR : Niveau de risque du projet Risque Catégorie de marché Risque Risque Risque Substanti élevé modéré Bas el Travaux (incluant clé à main, $10,000,0 $15,000,0 $20,000,0 fourniture et installation, et les $5,000,000 00 00 00 partenariats Public-Privé-PPP) Biens, Systèmes d’information et de $2,000,00 $4,000,00 $6,000,00 services autres que les services $1,500,000 0 0 0 intellectuels 2.2. Pré qualification : Les soumissionnaires pour (Nature des Acquisitions) devront être pré-qualifiés : N/A 2.3. Procédures applicables aux Composantes relatives au Développement Conduit par les Communautés : N/A 2.4. Référence (si nécessaire) au Manuel opérationnel/de passation de marchés : N/A 2.5. Autres arrangements spécifiques pour la passation de marchés : N/A 6. Marchés, Planning et Méthode de Passation : Marchés de Travaux Montant Méthode Pré- Préférenc Exam. par Ouverture Estimatif de qualificati e N Banque plis Description des Contrats Bailleur passation on nationale Commentaires ° (Milliers de A priori/A marchés (oui/non) (oui/non) Date Prévue $EU) posteriori Spécifications Travaux d’aménagement des bureaux 1 190 CF NON NON A posteriori 20 janv. 2019 techniques en cours complémentaires au siège de l’AFOR d’élaboration Spécification Travaux de réhabilitation d’un amphithéâtre à 2 180 CF Non Non A posteriori 1 févr. 2019 techniques en cours l’INPHB d’élaboration Spécification Travaux d'aménagement de 6 bureaux 3 190 CF NON NON A posteriori 19 févr. 2019 techniques en cours Régionaux de l’AFOR d’élaboration Spécification Travaux d'aménagement d'un local pour 4 150 CF NON NON A posteriori 19 févr. 2019 techniques en cours l'Observatoire du foncier d’élaboration Travaux d'aménagement de stations pour la 5 180 CF NON NON A posteriori 19 févr. 2019 Non échu gestion du CORS Identification et Travaux d'aménagement de locaux pour les 6 90 CF Non Non A postériori 19 févr. 2019 évaluation des sites en secrétariats villageois cours Identification et Travaux de réhabilitation des instituts de 7 180 CF Non Non A postériori 25 janv. 2019 évaluation des sites en formation agricoles cours TOTAL TRAVAUX 1 160 $EU 3 Marchés de Fournitures Montant Méthode Pré- Préférenc Exam. par Ouverture Estimatif de qualificati e N Banque plis prévue Description des Contrats Bailleur passation on nationale Commentaires ° de A priori/A (Milliers $EU) (oui/non) (oui/non) Date Prévue marchés posteriori Recrutement d’un Prestataire pour la fourniture d’un ED avec Contrat en cours 1 130 NON NON A Posteriori N/A logiciel de Gestion Financière et Comptable pour l'AFOR AGOSOFT d’élaboration Spécifications Fourniture et Installation de matériels informatiques pour 2 95 CF NON NON A Posteriori 6 Déc. 2018 techniques en cours l'AFOR d'élaboration Spécifications Fourniture et Installation de Matériels de Bureau pour 3 90 CF NON NON A Posteriori 6 Déc.2018 techniques en cours l’AFOR d'élaboration Spécifications Acquisition de consommables informatiques pour l'AFOR 20 no6 Déc. 4 50 CF NON NON A Posteriori techniques en cours et ses structures partenaires (INPHB, INFPA,) 2018 d'élaboration Spécifications Fourniture et installation de mobiliers de bureaux pour 5 90 CF NON NON A Posteriori 29 Nov. 2018 techniques en cours l'AFOR d'élaboration Spécifications Acquisition de matériel techniques (GPS, drones, 6 116 CF NON NON A posteriori 6 Déc. 2018 techniques en cours Théodolite, station à INPHB etc...) d'élaboration Spécifications Acquisition de mobilier de bureau et de matériels 7 688,5 AON NON NON A posteriori 6 Déc. 2018 techniques en cours pédagogiques pour la DFR, l'INPHB, l'INFPA d'élaboration Spécifications Acquisition d’équipements techniques de terrain pour 8 605 AON NON NON A posteriori 7 Jan. 2019 techniques en cours l'AFOR et ses structures partenaires (INFPA etc.) d'élaboration Spécifications Acquisition de 07 véhicules pour les besoins de l'AFOR, 9 490 CF NON NON A posteriori 22 Jan. 2018 techniques en cours l’ESA/INPHB et l’INPFA d'élaboration 1 ED avec Contrat en cours Acquisition de carburant pour les besoins des activités 450 NON NON A Posteriori N/A 0 TOTAL d'élaboration Spécifications 1 Fourniture et installation d’infrastructures géodésiques 1 420 AOI NON NON A posteriori 23 Mars 2019 techniques en cours 1 d'élaboration Spécifications 1 Fourniture et installation d'équipements pour le SIF 1 118 AOI NON NON A posteriori 16 Juil. 2019 techniques en cours 2 d'élaboration 4 Spécifications 1 Acquisition de deux (02) groupes électrogènes pour les 70 CF NON NON A posteriori 4 Déc. 2018 techniques en cours 3 locaux de l'AFOR d'élaboration Spécifications 1 Acquisition d’équipements techniques et petits 40 CF NON NON A posteriori 26 nov. 2018 techniques en cours 4 équipements de bureau pour l’AFOR (relieuses etc.) d'élaboration TOTAL FOURNITURES 5 452,5 Marchés de Services Assimilés Préféren Montant Méthode Pré- ce Exam. par Ouverture Estimatif de qualificati national Banque plis N° Description des Contrats Bailleur passation on Commentaires e de (Milliers A priori/A marchés (oui/non) (oui/non) Date Prévue $EU) posteriori Recrutement d’un Prestataire pour la fourniture de Police Spécifications d’Assurances (tous risques véhicules, Multirisque 1 90 CF NON NON A posteriori 22 Nov. 2018 techniques en cours Professionnelle, Maladie et individuelle accident) pour d'élaboration l'AFOR Recrutement d’un Prestataire pour la fourniture de ED avec Contrat en Cours 2 40 NON NON A Posteriori N/A connexion internet mobile pour l’AFOR AVISO d’élaboration Recrutement d’un Prestataire pour la fourniture de services Spécification techniques 3 24 CF NON NON A Posteriori 20 Nov. 2018 d'entretien des locaux de l'AFOR en cours de finalisation Spécifications Recrutement d’un Prestataire pour la fourniture de services 4 24 CF NON NON A posteriori 20 Nov. 2018 techniques en cours de de gardiennage des locaux de l'AFOR finalisation Spécifications Recrutement d’un Prestataire pour le service de 5 15 CF NON NON A posteriori 14 Déc. 2018 techniques en cours géolocalisation de la flotte automobile de l'AFOR d'élaboration Recrutement d’un Prestataire pour la maintenance des Spécifications 6 équipements informatiques, bureautiques et téléphoniques 15 CF NON NON A posteriori 14 Déc. 2018 techniques en cours de l’AFOR d'élaboration Spécifications Recrutement d’un Prestataire pour la maintenance des 7 10 CF NON NON A posteriori 14 Déc. 2018 techniques en cours splits de l’AFOR d'élaboration 5 TOTAL SERVICES ASSIMILES 218 6 II. Sélection de Consultants 3.1. Seuil d’examen préalable Marchés qui seront soumis à l'examen préalable de la banque conformément aux nouveaux seuils de revue en fonction des risques attribués au projet après le dernier PPR : Catégorie de marché Niveau de risque du projet Risque Risque Risque Risque Substanti élevé modéré Bas el Services Consultant (Firmes) $1,000,00 $2,000,00 $4,000, $500,000 0 0 000 Consultant Individuel $200,000 $300,000 $400,000 $500,000 Tous les TDRs, quelle que soit la valeur du contrat, sont soumis à examen préalable. 3.2. Liste restreinte composée entièrement de Consultants Nationaux : Liste restreinte de consultants pour prestations de services, d’un coût estimatif inférieur à 300 000$ US ou équivalent par contrat, peut être entièrement composée de Consultants nationaux conformément aux dispositions du paragraphe 2.7 des Directives de Sélection et Emploi de Consultants 3.3. Autres arrangements spécifiques pour la sélection : Non Applicable Marchés de Consultants Montan t Préféren Date Méthode Examen préalable de Estimat Pré- ce prévue de la Banque if qualificati nationale pour N° Description des Contrats passatio Commentaires Bailleur on l’ouvertu n de (oui/non) re des (Millier marchés offres (oui/non) (a priori / a posteriori) s $EU) Sélection d'un cabinet, pour l’audit financier et comptable des 4 Déc. TDR en cours 1 90 SFQC NON NON A priori trois premiers exercices du projet 2018 d'élaboration Sélection d'un consultant individuel pour la réalisation d’une 25 Déc. TDR en cours 2 étude de mise en place d’un système de suivi-évaluation pour 80 QC (AMI) NON NON A posteriori 2018 d'élaboration le projet ED avec Commented [MS1]: Vu du niveau de risque du 3 Convention avec l'INPHB 2 914 NON NON A Priori N/A Non Echu projet (Substantiel), ce montant (> $1,000,000) INPHB demande une revue a priori. ED avec 4 Convention avec l'INFPA 2 725 NON NON A Priori N/A Non Echu Commented [MS2]: Vu du niveau de risque du INFPA projet (Substantiel), ce montant (> $1,000,000) Recrutement d’un cabinet pour la réalisation de l’étude 2 Aout. Evaluation desdemande une revue a priori. 5 120 QC (AMI) NON NON A posteriori d’évaluation sociale du Projet 2018 Offres en Cours Recrutement d’un cabinet pour l’étude de Renforcement du 1 Sept. Négociations en 6 80 QC(AMI) NON NON A posteriori système d'Informations Foncières 2018 Cours Recrutement d’un cabinet pour une assistance technique à 01-août- Analyse des 7 l’installation, au fonctionnement et à la maintenance du 80 QC (AMI) NON NON A posteriori 18 Offres en Cours réseau CORS ED avec Contrat en Recrutement d’un Cabinet pour le recrutement de spécialistes 8 30,8 Raynal & NON NON A Posteriori N/A cours de pour l’AFOR Fadika finalisation Recrutement du Spécialiste en ressources humaines pour 3 Déc. TDR en cours 9 31,2 CI (AMI) NON NON A Posteriori l'AFOR 2018 d'élaboration Réception des Recrutement d’un Spécialiste en programmation des travaux 8 Oct. 10 39 CI (AMI) NON NON A Posteriori Candidatures et supervision des services déconcentrés 2018 en Cours Recrutement d’un Spécialiste en Communication interne et 22 Nov. TDR en cours 11 54,6 CI (AMI) NON NON A Posteriori externe 2018 d'élaboration Recrutement d’un Spécialiste en Vérification des projets 3 Déc. TDR en cours 12 54,6 CI (AMI) NON NON A Posteriori d'actes administratifs 2018 d'élaboration 8 Evaluation en Recrutement d’un Spécialiste en Environnement et 24 Sept. 13 54,6 CI (AMI) NON NON A Posteriori cours des Sauvegarde Sociale 2018 candidatures Evaluation en 25 Sept. 14 Recrutement du Chef Comptable de l’AFOR 54,6 CI (AMI) NON NON A Posteriori cours des 2018 candidatures Recrutement d’un Spécialiste en Système d'informations 3 Dec. TDR en cours 15 54,6 CI (AMI) NON NON A Posteriori foncières 2018 d'élaboration Recrutement d’un consultant pour l’assistance de l’équipe 15 Janv. TDR en cours 16 technique dans l’analyse des offres et des rapports des 20 CI (3CV) NON NON A posteriori 2018 d'élaboration études du SIF Recrutement d’un consultant pour l’assistance de l’équipe 15 Janv. TDR en cours 17 technique dans l’analyse des offres et des rapports des 20 CI (3CV) NON NON A posteriori 2018 d'élaboration Commented [AT3]: Vous évoquiez l’idée de études du CORS distinguer l’expertise necessaire pour ces deux Recrutement d'un consultant individuel international pour le 7 Janv. TDR en cours themes ? 18 162 CI (AMI) NON NON A posteriori renforcement des capacités à l'INPHB 2019 d'élaboration Recrutement d'un consultant individuel international expert 15 Oct. TDR en cours 19 125 CI (3CV) NON NON A posteriori en foncier rural 2018 d'élaboration Contrat en ED avec 14 Févr. 20 Réalisation de l’étude sur le plan de formation en foncier rural 80 NON NON A posteriori cours FIEF 2019 d'élaboration Recrutement d'une entreprise pour les travaux de 04-mars- TDR en cours 21 7 800 SFQ NON NON A priori sécurisation foncière (Exécution de la composante II) 19 d'élaboration Recrutement d'une entreprise pour les travaux de 04-mars- TDR en cours 22 7 800 SFQ NON NON A priori sécurisation foncière (Exécution de la composante II) 19 d'élaboration Recrutement d'une entreprise pour les travaux de 04-mars- TDR en cours 23 7 800 SFQ NON NON A priori sécurisation foncière (Exécution de la composante II) 19 d'élaboration Recrutement d'un bureau d'études pour l'élaboration du DQE 10 Janv. TDR en cours 24 relatif à l'aménagement de stations CORS, ainsi que le suivi et 35 QC NON NON A posteriori 2019 d'élaboration le contrôle des travaux Recrutement d'un cabinet pour assurer le suivi et le contrôle 15 Nov. TDR en cours 25 30 QC NON NON A Posteriori des travaux de réhabilitation de l'INPHB 2018 d'élaboration Recrutement d’un Cabinet pour la conception et le 17 Mars TDR en cours 26 80 QC(AMI) NON NON A posteriori développement d’un nouveau SIF 2019 d'élaboration Recrutement d'un Responsable de la documentation et de 14 Déc. TDR en cours 27 54,6 CI (AMI) NON NON A posteriori l'archivage à l'AFOR 2019 d'élaboration Recrutement d'un Responsable de l'information, des études et 14 Fév. TDR en cours 28 54,6 CI (AMI) NON NON A Posteriori de la politique foncière à l'AFOR 2019 d'élaboration 9 14 Janv. TDR en cours 29 Recrutement d'un Responsable informatique à l'AFOR 54,6 CI (AMI) NON NON A Posteriori 2019 d'élaboration 14 Janv. TDR en cours 30 Recrutement d'un Responsable Réseaux à l'AFOR 54,6 CI (AMI) NON NON A posteriori 2019 d'élaboration 14 Déc. TDR en cours 31 Recrutement d'un Chargé de la formation à l'AFOR 54,6 CI (AMI) NON NON A posteriori 2019 d'élaboration 14 Janv. TDR en cours 32 Recrutement d'un Chargé des moyens généraux à l'AFOR 54,6 CI (AMI) NON NON A posteriori 2019 d'élaboration Recrutement d'un consultant individuel pour la réalisation des 14 Janv. TDR en cours 33 études techniques des travaux d'aménagement des bureaux 12 CI (3 CV) NON NON A posteriori 2019 d'élaboration complémentaires à l’AFOR Recrutement d'un bureau d'études pour les études techniques 14 Janv. TDR en cours 34 40 QC NON NON A posteriori et le suivi et contrôle des travaux de réhabilitation de l'INFPA 2019 d'élaboration Recrutement d'un bureau d'études pour l'élaboration du DQE 14 Janv. TDR en cours 35 relatif à l'aménagement des bureaux régionaux de l'AFOR 50 QC NON NON A posteriori 2019 d'élaboration ainsi que le suivi et le contrôle des travaux Commented [MS4]: Le recrutement d’un TOTAL CONSULTANTS 30 795 responsible de suivi-evaluation et l’ Etude de mise en place d'un système de suivi & Evaluation sont toujours manquants. 10 Montant Date estimatif ATELIERS PNSFR Durée prévisionnelle de (Milliers début $EU) 1 Atelier visant à présenter et à valider la Révision et la mise à jour des modes opératoires de la SFR et la mise au point d'un modèle 20 2 jours 06/02/2019 économique de la SFR 2 Atelier relatif à l’étude de Renforcement du système 10 1 jour 26/02/2019 d'Informations Foncières 3 Atelier visant à présenter et à valider le Plan de formation aux 10 1 jour 22/02/2019 métiers du Foncier rural 4 Atelier de formation sur le manuel de procédures de l'Agence du 20 2 jours 10/09/2018 Foncier Rural (AFOR) 5 Atelier visant à présenter et à valider l’étude de mise en place Commented [MS5]: Cette etude ne figure pas dans 10 1 jour 28/01/2019 la liste des consultants. Comme nous avons convenu, d'un système de suivi & Evaluation cette etude rapport a la mise en place d’un systeme de suivi-evaluation seulement, et pas d’une etude de 6 reference du project. Conférence de présentation du projet d'amélioration et de mise 30 2 jours 28/09/2018 en œuvre de la politique foncière 7 Atelier sur le renforcement des capacités de la DFR 60 3 jours 15/01/2019 Commented [AT6]: En milliers de $ aussi ? TOTAL ATELIERS 160 Montant Date VOYAGES PNSFR estimatif Durée prévisionnelle en $EU de départ Voyage d'études des étudiants de l’INPHB sur le premier 10 jours 1 8 113 semestriel semestre Voyage d'études des étudiants de l’INPHB sur le second 10 jours 2 8 113 semestriel semestre Voyage d'études des professeurs accompagnateurs de 10 jours 3 15 000 semestriel l’INPHB 4 Voyage d'études des étudiants de l’INFPA 30 000 10 jours annuel 5 Voyage d'études pour la formation continue 112 000 10 jours annuel Voyage de capitalisation pour l'élaboration du mode 6 80 000 10 jours nov-18 opératoire 253 226$E TOTAL VOYAGES U PROCUREMENT Cote d'Ivoire : Cote d'Ivoire Land Policy Improvement and Implementation Project PLAN General Information Country: Cote d'Ivoire Bank’s Approval Date of the Original Procurement Plan:2019-01-22 2023-06-05 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P157206 GPN Date: 2019-01-06 Project Name: Cote d'Ivoire Land Policy Improvement and Implementation Project Loan / Credit No: IDA / 61900, IDA / V1170 Rural Land Agency Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process S Draft Pre-qualificatio Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Comple Description Component Review Type Method Amount (U ount (US$ and Recommendatio Signed Contract o. h cess (Y/N) isk ocument Type tatus n Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes tion S$) ) n for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned CI-AFOR-89700-CW-RFQ / Tr Component 1 – Strengtheni Request for Quot Single Stage - One 2019-05-1 avaux d'aménagement des IDA / 61900 Post Limited 195,000.00 0.00 Canceled 2019-01-24 2019-03-19 ng Rural Land Institutions ations Envelope 8 bureaux au siège de l'AFOR CI-AFOR-89708-CW-RFQ / Tr Component 3 – Training for Request for Quot Single Stage - One 2019-07-1 avaux de réhabilitation des i IDA / 61900 Post Limited 180,000.00 0.00 Canceled 2019-03-14 2019-04-17 Land Tenure Professionals ations Envelope 6 nstituts de formation agricol es CI-AFOR-89703-CW-RFQ / Tr Component 3 – Training for Request for Quot Single Stage - One 2019-12-0 avaux de réhabilitation d'un IDA / 61900 Post Limited 200,000.00 0.00 Canceled 2019-07-03 2019-08-10 Land Tenure Professionals ations Envelope 8 amphithéâtre à l'ESA (INPH B) CI-AFOR-89706-CW-RFQ / Tr Component 1 – Strengtheni Request for Quot Single Stage - One 2019-11-2 avaux d'aménagement de s IDA / 61900 Post Limited 195,000.00 0.00 Canceled 2019-08-20 2019-09-24 ng Rural Land Institutions ations Envelope 3 tations pour la gestion du C ORS CI-AFOR-109033-CW-RFQ / Component 1 – Strengtheni Request for Quot Single Stage - One 2019-11-2 Travaux de Réhabilitation de IDA / 61900 Post Limited 150,000.00 0.00 Canceled 2019-07-27 2019-09-21 ng Rural Land Institutions ations Envelope 0 Secrétariats Villageois CI-AFOR-109045-CW-RFQ / Réhabilitation de trois (03) B Component 1 – Strengtheni Request for Quot Single Stage - One 2019-12-0 IDA / 61900 Post Limited 165,000.00 0.00 Canceled 2019-07-09 2019-09-03 âtiments à usage de Bureau ng Rural Land Institutions ations Envelope 2 pour les Antennes Déconcen trés de l'AFOR CI-AFOR-122829-CW-RFQ / Pending Im Travaux de réhabilitation de Component 1 – Strengtheni Request for Quot Single Stage - One 2020-05-0 IDA / 61900 Post Limited 160,000.00 0.00 plementatio 2019-09-16 2019-11-11 19 Bâtiments pour les anten ng Rural Land Institutions ations Envelope 9 n nes déconcentrés de l'AFOR CI-AFOR-122852-CW-DIR / C Component 1 – Strengtheni 2020-03-2 onvention pour les Travaux IDA / 61900 Post Direct Selection Direct 200,000.00 0.00 Canceled 2019-08-28 2019-08-28 2019-09-22 ng Rural Land Institutions 0 de Réhabilitation des CORS CI-AFOR-122831-CW-RFQ / Component 2 – Support Imp Request for Quot Single Stage - One 2020-03-0 Travaux de réhabilitation de IDA / 61900 lementation of the National Post Limited 100,000.00 0.00 Canceled 2019-11-10 2020-01-05 ations Envelope 5 s Secrétariats Villageois (20 Rural Land Tenure Security SV) Program CI-AFOR-122830-CW-RFQ / Réhabilitation de six (06) Bâ Component 1 – Strengtheni Request for Quot Single Stage - One Under Impl 2020-07-1 IDA / 61900 Post Limited 190,000.00 0.00 2019-11-17 2019-12-24 2020-01-12 timents à usage de Bureau p ng Rural Land Institutions ations Envelope ementation 0 our les Bureaux Régionaux d e l'AFOR CI-AFOR-153251-CW-RFQ / Component 4 – Program Co Request for Quot Single Stage - One 2020-06-1 Travaux de Réhabilitation d' IDA / 61900 ordination, Monitoring and Post Limited 100,000.00 0.00 Canceled 2020-03-17 2020-05-01 ations Envelope 5 antennes départementales p Knowledge Management our l'AFOR CI-AFOR-153247-CW-RFQ / Travaux de Construction de Pending Im Component 3 – Training for Request for Quot Single Stage - One 2020-08-0 salles de cours pour la form IDA / 61900 Post Limited 200,000.00 0.00 plementatio 2020-05-05 2020-06-05 Land Tenure Professionals ations Envelope 4 ation au Foncier au sein de l' n Université Alassane Ouatarr a de BOUAKE CI-AFOR-174137-CW-RFB / Travaux de Construction de Component 1 – Strengtheni Single Stage - One 2020-12-2 IDA / 61900 Post Request for Bids Open - National 960,000.00 581,823.13 Signed 2020-06-09 2020-08-04 2020-06-14 2020-08-04 2020-07-26 2020-09-25 2020-08-25 2020-12-10 2020-09-29 2021-02-24 quarante (40) Secrétariats V ng Rural Land Institutions Envelope 8 illageois dans les zones d'int ervention du PAMOFOR CI-AFOR-122839-CW-RFQ / Component 4 – Program Co Request for Quot Single Stage - One 2020-01-2 Travaux de construction de IDA / 61900 ordination, Monitoring and Post Limited 200,000.00 257,049.90 Signed 2019-09-16 2020-02-25 2019-10-26 2020-07-01 ations Envelope 4 Douze secrétariats villageois Knowledge Management CI-AFOR-153249-CW-RFQ / Component 2 – Support Imp Request for Quot Single Stage - One 2020-12-0 Travaux de Construction de IDA / 61900 lementation of the National Post Limited 150,000.00 0.00 Canceled 2020-04-20 2020-06-11 ations Envelope 8 15 Secrétariats Villageois Rural Land Tenure Security Program CI-AFOR-215906-CW-RFQ- / Pending Im Component 1 – Strengtheni Request for Quot Single Stage - One 2021-11-0 Travaux de réhabilitation de IDA / 61900 Post Open - National 81,670.00 0.00 plementatio 2021-03-16 2021-05-11 ng Rural Land Institutions ations Envelope 7 13 bâtiments publics à usag n e de bureaux CI-AFOR-215917-CW-DIR-21 Component 1 – Strengtheni 2021-10-0 / Réhabilitation et observatio IDA / 61900 Post Direct Selection Direct 390,840.00 382,129.78 Completed 2021-02-25 2021-06-11 2021-03-02 2021-06-11 2021-04-06 2021-09-22 ng Rural Land Institutions 3 n du RGIR et du RGIO CI-AFOR-217471-CW-RFQ-2 Pending Im 1 / Travaux de réhabilitation Component 3 – Training for Request for Quot Single Stage - One 2021-12-0 IDA / 61900 Post Open - National 250,450.00 0.00 plementatio 2021-04-17 2021-06-12 et aménagement du Laborat Land Tenure Professionals ations Envelope 9 n oire Juridique du Foncier CI-AFOR-217572-CW-RFB-2 1 / TRAVAUX DE CONSTRUC Pending Im Component 1 – Strengtheni Single Stage - One 1,042,110.0 2022-07-0 TION DE BATIMENTS A USAG IDA / 61900 Post Request for Bids Open - National 0.00 plementatio 2021-09-13 2021-09-18 2021-10-30 2021-11-29 2022-01-03 ng Rural Land Institutions Envelope 0 2 E DE BUREAU POUR 58 BUR n EAUX FONCIERS VILLAGEOIS (BFV) CI-AFOR-217575-CW-RFQ-2 Pending Im 1 / TRAVAUX ET REHABILITA Component 1 – Strengtheni Request for Quot Single Stage - One 2022-07-1 IDA / 61900 Post Open - National 81,670.00 0.00 plementatio 2021-11-22 2022-01-17 TION DES 13 BATIMENTS PU ng Rural Land Institutions ations Envelope 6 n BLICS A USAGE DE BUREAU DES COTIF CI-AFOR-215919-CW-RFB-2 Pending Im Component 3 – Training for Single Stage - One 2023-04-2 1 / Travaux de réhabilitation IDA / 61900 Post Request for Bids Open - National 123,500.00 0.00 plementatio 2021-03-30 2021-06-15 2021-06-15 2021-04-04 2021-08-24 2021-09-23 2021-10-28 Land Tenure Professionals Envelope 1 de l'amphithéâtre de l'ESA n CI-AFOR-215850-CW-RFB-2 Pending Im 1 / Travaux de construction Component 1 – Strengtheni Single Stage - One 1,042,110.0 2023-03-2 IDA / 61900 Post Request for Bids Open - National 0.00 plementatio 2021-03-03 2021-05-19 2021-05-19 2021-03-08 2021-07-28 2021-08-27 2021-10-01 de bâtiments à usage de bur ng Rural Land Institutions Envelope 0 5 n eau pour 58 Bureaux Foncie rs Villageois (BFV) CI-AFOR-225585-CW-RFQ-K Pending Im K-21 / TRAVAUX DE REHABIL Component 1 – Strengtheni Request for Quot Single Stage - One 2022-03-1 IDA / 61900 Post Open - National 19,000.00 0.00 plementatio 2021-07-25 2021-09-19 ITATION DES TROIS (03) BAT ng Rural Land Institutions ations Envelope 8 n IMENTS PUBLICS A USAGE D E BUREAU DES ROT CI-AFOR-226263-CW-RFQ-2 1 / Travaux de réhabilitation Pending Im Component 1 – Strengtheni Request for Quot Single Stage - One 2021-12-0 de trois (3) bâtiments public IDA / 61900 Post Open - National 19,000.00 0.00 plementatio 2021-04-14 2021-06-09 ng Rural Land Institutions ations Envelope 6 s à usage de bureaux pour l n es Responsables des Opérati ons Techniques Page 1 CI-AFOR-293843-CW-RFQ / National Procure Travaux de construction d'u ment Document - Pending Im Component 1 – Strengtheni Request for Quot Single Stage - One 2023-01-1 ne clôture de sécurisation d IDA / 61900 Post Limited 1 Envelope proce 69,352.00 0.00 plementatio 2022-05-21 2022-07-16 ng Rural Land Institutions ations Envelope 2 u site de la préfecture d'Aboi ss (Non Bank-SP n sso pour la sécurisation fonc D) ière GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualificatio Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendatio Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus n Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes n for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CI-AFOR-89712-GO-DIR / Ac Component 4 – Program Co quisition de carburant pour l IDA / 61900 ordination, Monitoring and Post Direct Selection Direct 490,000.00 101,448.60 Signed 2019-01-10 2018-12-05 2019-01-15 2018-12-11 2019-02-19 2018-12-26 2023-02-18 es besoins des activités du P Knowledge Management AMOFOR CI-AFOR-89718-GO-RFQ / Ac Component 2 – Support Imp Request for Quot Single Stage - One Pending Impl quisition de 08 véhicules po IDA / 61900 lementation of the National Post Limited 495,000.00 0.00 2019-01-11 2019-02-12 2019-03-29 ations Envelope ementation ur les besoins de l'AFOR, l'IN Rural Land Tenure Security PHB et l'INPFA Program CI-AFOR-89731-GO-RFQ / Fo Component 1 – Strengtheni Request for Quot Single Stage - One urniture et Installation de m IDA / 61900 Post Limited 95,000.00 93,533.85 Completed 2019-01-15 2018-12-19 2019-03-12 2019-02-09 2019-04-26 2019-03-22 ng Rural Land Institutions ations Envelope atériels informatiques pour l 'AFOR CI-AFOR-89732-GO-RFQ / Fo Component 2 – Support Imp Open - Internation Single Stage - One urniture et installation d'équ IDA / 61900 lementation of the National Post Request for Bids 1,120,000.00 0.00 Canceled 2019-03-27 2019-04-01 2019-05-13 2019-06-12 2019-07-17 2019-10-15 al Envelope ipements pour le SIF Rural Land Tenure Security Program CI-AFOR-89737-GO-RFQ / Fo Component 4 – Program Co urniture et Installation de M Request for Quot Single Stage - One IDA / 61900 ordination, Monitoring and Post Limited 50,000.00 0.00 Canceled 2019-01-15 2019-03-12 2019-03-27 atériels de Bureau et de Mat ations Envelope Knowledge Management ériels Techniques pour l'AFO R CI-AFOR-89740-GO-RFQ / Ac quisition de mobilier de bure Component 3 – Training for Single Stage - One IDA / 61900 Post Request for Bids Open - National 700,000.00 0.00 Canceled 2019-01-30 2019-02-04 2019-03-18 2019-04-17 2019-05-22 2019-08-20 au et de matériels pédagogi Land Tenure Professionals Envelope ques, l'INPHB, l'INFPA CI-AFOR-108564-GO-RFQ / Acquisition de Fournitures d Component 3 – Training for Request for Quot Single Stage - One IDA / 61900 Post Limited 60,000.00 33,597.47 Signed 2019-04-20 2019-10-07 2019-06-15 2019-11-19 2020-06-14 e Bureau pour l'Agence Fonc Land Tenure Professionals ations Envelope ière Rurale (AFOR) et pour le s besoins de l'ESA et l'INFPA CI-AFOR-89727-GO-RFQ / Fo Component 1 – Strengtheni Request for Quot Single Stage - One Pending Impl urniture et installation de Mo IDA / 61900 Post Limited 40,000.00 0.00 2019-05-08 2019-06-22 2019-07-22 ng Rural Land Institutions ations Envelope ementation biliers de bureaux pour l'AF OR CI-AFOR-89735-GO-RFB / Fo Component 2 – Support Imp urniture, installation, mise e lementation of the National Open - Internation Single Stage - One IDA / 61900 Post Request for Bids 850,000.00 0.00 Canceled 2019-07-25 2019-07-30 2019-09-10 2019-10-10 2019-11-14 2020-03-13 n service d'infrastructures g Rural Land Tenure Security al Envelope éodésiques (équipements po Program ur le CORS) CI-AFOR-89717-GO-RFQ / Ac quisition d'équipements tec Component 4 – Program Co Request for Quot Single Stage - One hniques, de communication IDA / 61900 ordination, Monitoring and Post Limited 30,000.00 0.00 Canceled 2019-06-17 2019-07-16 2019-07-31 ations Envelope et petits équipements de bu Knowledge Management reau pour l'AFOR (relieuses, calculettes, Téléphones etc.) CI-AFOR-109064-GO-RFQ / Acquisition de trois (03) Véhi Component 4 – Program Co Request for Quot Single Stage - One cules pour les besoins des a IDA / 61900 ordination, Monitoring and Post Limited 150,000.00 0.00 Canceled 2019-09-23 2019-12-05 2020-01-19 ations Envelope ntennes déconcentrées de l' Knowledge Management Agence Foncière Rurale (AF OR) CI-AFOR-109065-GO-RFQ / Component 2 – Support Imp Request for Quot Single Stage - One Acquisition d'Images Satelitt IDA / 61900 lementation of the National Post Limited 400.00 0.00 Canceled 2019-07-08 2019-09-02 2019-11-01 ations Envelope es Géoréférencés Rural Land Tenure Security Program CI-AFOR-109067-GO-RFQ / F ourniture et Installation de Component 4 – Program Co Request for Quot Single Stage - One Pending Impl Matériels Informatiques et d IDA / 61900 ordination, Monitoring and Post Limited 60,000.00 0.00 2019-06-24 2019-08-28 2020-02-24 ations Envelope ementation e Matériels de Bureau pour l Knowledge Management es antennes déconcentrées de l'AFOR CI-AFOR-109071-GO-RFQ / F Component 2 – Support Imp ourniture de Mobiliers de Bu lementation of the National Request for Quot Single Stage - One Pending Impl reau (Meubles de rangemen IDA / 61900 Post Limited 60,000.00 0.00 2019-06-10 2019-08-05 2020-02-01 Rural Land Tenure Security ations Envelope ementation t, Tables, Chaises etc.) pour Program les antennes régionales de l' AFOR CI-AFOR-122767-GO-RFQ / Component 4 – Program Co Acquisition d'Appareils de M Request for Quot Single Stage - One IDA / 61900 ordination, Monitoring and Post Limited 90,000.00 0.00 Canceled 2019-09-09 2019-11-04 2020-05-02 esure pour l'Agence Foncièr ations Envelope Knowledge Management e Rurale (Station Totale, Thé odolite) CI-AFOR-122775-GO-RFB / A Component 2 – Support Imp Open - Internation Single Stage - Two cquisition d'images satellites IDA / 61900 lementation of the National Post Request for Bids 900,000.00 587,703.06 Signed 2019-08-22 2019-07-30 2019-08-27 2019-07-30 2019-10-08 2019-09-26 2019-12-21 2019-10-02 2020-01-25 2019-10-17 2020-07-23 al Envelope géo référencées pour l'AFOR Rural Land Tenure Security Program CI-AFOR-122777-GO-RFQ / Acquisition d'imprimés et de Component 4 – Program Co gadgets (Kakémonos, Banfer Request for Quot Single Stage - One IDA / 61900 ordination, Monitoring and Post Limited 95,000.00 36,284.20 Signed 2019-08-20 2019-09-09 2019-10-15 2019-10-17 2020-04-12 oles, tee shirt etc.) pour la p ations Envelope Knowledge Management romotion de la sécuridation f oncière dans le cadre du PA MOFOR CI-AFOR-122779-GO-RFQ / Acquisition de 20 Motocyclet Component 1 – Strengtheni Request for Quot Single Stage - One tes et accessoires (casques) IDA / 61900 Post Limited 85,000.00 38,550.05 Signed 2019-09-09 2019-09-18 2019-11-04 2019-11-13 2020-05-02 ng Rural Land Institutions ations Envelope pour les antennes départem entales de l'AFOR et le GIL CI-AFOR-122784-GO-RFQ / F ourniture et Installation de Component 1 – Strengtheni Request for Quot Single Stage - One IDA / 61900 Post Limited 95,000.00 80,495.94 Completed 2019-09-16 2019-09-05 2019-11-11 2019-10-17 2020-05-09 2019-11-23 Matériels Informatiques pour ng Rural Land Institutions ations Envelope les antennes régionales de l' AFOR CI-AFOR-122786-GO-RFQ / F Component 3 – Training for Request for Quot Single Stage - One Pending Impl ourniture et installation de M IDA / 61900 Post Limited 95,000.00 0.00 2019-09-17 2019-11-12 2020-05-10 Land Tenure Professionals ations Envelope ementation obiliers dans l'amphitéatre d e l'ESA CI-AFOR-122788-GO-RFQ / Acquisition de Matériels de Component 1 – Strengtheni Request for Quot Single Stage - One Pending Impl IDA / 61900 Post Limited 90,000.00 0.00 2019-09-16 2019-11-11 2020-05-09 Bureau pour les antennes ré ng Rural Land Institutions ations Envelope ementation gionales et départementales de l'AFOR CI-AFOR-122789-GO-RFQ / F ourniture, livraison et install ation de Mobiliers de bureau Component 1 – Strengtheni Request for Quot Single Stage - One IDA / 61900 Post Limited 95,000.00 0.00 Canceled 2019-08-20 2019-09-29 2019-10-29 (meubles de rangement, tab ng Rural Land Institutions ations Envelope le, chaises) pour les antenne s régionnales et départemen tales CI-AFOR-122791-GO-RFQ / Acquisition de six (06) Véhic Component 1 – Strengtheni Request for Quot Single Stage - One IDA / 61900 Post Limited 400,000.00 354,313.12 Signed 2019-09-23 2019-09-24 2019-11-18 2020-11-13 2020-05-16 ules pour les représentation ng Rural Land Institutions ations Envelope s régionales de l'AFOR Page 2 CI-AFOR-122802-GO-RFQ / F ourniture, livraison et install Component 1 – Strengtheni Request for Quot Single Stage - One ation de Mobiliers de Bureau IDA / 61900 Post Limited 40,000.00 0.00 Canceled 2019-09-02 2019-10-28 2020-04-25 ng Rural Land Institutions ations Envelope pour les Secrétariats Village ois (meubles de rangement, table, chaises etc…) CI-AFOR-122873-GO-RFQ / F ourniture et Installation de Component 3 – Training for Request for Quot Single Stage - One Pending Impl Mobiliers (Tables bancs) pou IDA / 61900 Post Limited 95,000.00 0.00 2019-08-20 2019-10-15 2020-04-12 Land Tenure Professionals ations Envelope ementation r l'Amphitéatre de l'Ecole Su périeure d'Agrnomie (ESA) CI-AFOR-141693-GO-DIR / A Component 4 – Program Co cquissition d'un logiciel de g IDA / 61900 ordination, Monitoring and Post Direct Selection Direct 10,000.00 0.00 Canceled 2019-11-15 2019-11-20 2019-12-09 2020-12-08 estion de base de données d Knowledge Management e fournisseurs de l'AFOR CI-AFOR-141695-GO-RFQ / Acquisition de matériels info Component 2 – Support Imp rmatiques pour les opérateu lementation of the National Request for Quot Single Stage - One rs fonciers dans le cadre de l IDA / 61900 Post Limited 95,000.00 83,733.98 Completed 2019-11-07 2019-11-18 2019-12-17 2019-12-25 2020-01-16 2020-01-21 Rural Land Tenure Security ations Envelope a mise en oeuvre des opérat Program ions de sécurisation foncière dans les régions de la Mé et de l'Agnéby Tiassa CI-AFOR-141705-GO-RFQ / Component 2 – Support Imp Acquisition de Neuf (09) véh lementation of the National Request for Quot Single Stage - One icules pour les opérateurs fo IDA / 61900 Post Limited 500,000.00 267,327.82 Signed 2019-11-12 2019-12-26 2020-01-05 2020-02-29 2020-02-04 Rural Land Tenure Security ations Envelope nciers dans le cadre des opé Program rations de sécurisation fonci ère dans le cadre du PAMOF OR CI-AFOR-141707-GO-RFQ / Component 2 – Support Imp Acquisition d'imprimés et ga lementation of the National Request for Quot Single Stage - One Pending Impl dgets promotionnels des act IDA / 61900 Post Limited 95,000.00 0.00 2020-02-04 2020-03-31 2021-03-31 Rural Land Tenure Security ations Envelope ementation ivités de securisation foncier Program e dans le cadre des activités du PAMOFOR CI-AFOR-141711-GO-RFQ / Component 2 – Support Imp Request for Quot Single Stage - One Acquisition de Matériels Info IDA / 61900 lementation of the National Post Open - National 90,000.00 82,544.30 Completed 2019-11-05 2020-01-03 2019-10-18 2020-02-02 2019-11-17 ations Envelope rmatiques pour l'ESA et l'INF Rural Land Tenure Security PA Program CI-AFOR-141714-GO-RFQ / Acquisition de consommable Component 4 – Program Co Request for Quot Single Stage - One s informatiques (encres, ton IDA / 61900 ordination, Monitoring and Post Limited 95,000.00 55,439.08 Signed 2019-11-20 2019-11-11 2019-12-30 2019-12-25 2020-02-04 ations Envelope ers) pour les besoins de l'AF Knowledge Management OR et des antennes régional es CI-AFOR-141715-GO-RFQ / Recrutement d'un Prestatair Component 2 – Support Imp e pour la Confection de moul lementation of the National IDA / 61900 Post Direct Selection Direct 5,000.00 0.00 Canceled 2019-11-11 2019-11-16 2019-12-05 2019-12-20 e de précision de 12,5 kg à Rural Land Tenure Security mettre à la disposition des O Program pérateurs Fonciers (18 écha ntillons à dupliquer) CI-AFOR-108563-GO-RFQ / Component 2 – Support Imp Acquisition de quatre (04) V lementation of the National Request for Quot Single Stage - One IDA / 61900 Post Limited 300,000.00 343,930.72 Terminated 2019-11-05 2019-09-24 2019-12-31 2019-11-13 2020-02-29 éhicules pour l'ESA et l'INFP Rural Land Tenure Security ations Envelope A (Minibus et Véhicule 4X4) Program CI-AFOR-153022-GO-RFQ / Component 2 – Support Imp Acquisition de douze (12) Vé lementation of the National Request for Quot Single Stage - One hicules pour les Opérateurs f IDA / 61900 Post Limited 600,000.00 0.00 Canceled 2020-02-08 2020-03-21 2020-05-05 Rural Land Tenure Security ations Envelope onciers du Sud Come et de l' Program Indénnie, du BAFING-N'ZI et l'observatoire du Foncier CI-AFOR-153254-GO-RFQ / F ourniture et installation de M obiliers de Bureau et équipe Component 3 – Training for Request for Quot Single Stage - One Pending Impl IDA / 61900 Post Limited 70,000.00 0.00 2020-05-05 2020-06-30 2020-12-27 ments de laboratoire pour la Land Tenure Professionals ations Envelope ementation salle de cours sur le foncier de l'université Allassane Oua ttara CI-AFOR-153287-GO-RFQ / F Component 2 – Support Imp ourniture de Mobiliers pour l lementation of the National Request for Quot Single Stage - One Pending Impl IDA / 61900 Post Limited 80,000.00 0.00 2020-04-28 2020-06-23 2020-08-22 es 70 Secretariats Villageois Rural Land Tenure Security ations Envelope ementation à construire dans le cadre d Program u PAMOFOR CI-AFOR-153292-GO-RFQ / F ournitures d'Equipements po Component 3 – Training for Request for Quot Single Stage - One Pending Impl IDA / 61900 Post Limited 85,000.00 0.00 2020-03-07 2020-05-02 2020-10-29 ur le laboratoire et la bibliot Land Tenure Professionals ations Envelope ementation hèque de l'Université Alassa ne OUATATRRA CI-AFOR-122796-GO-RFB / F ourniture, Installation, Mise en Service, formation des uti Component 1 – Strengtheni Open - Internation Single Stage - Two IDA / 61900 Post Request for Bids 2,000,000.00 1,268,243.62 Signed 2019-09-16 2020-05-01 2019-09-21 2020-05-01 2019-11-02 2020-07-24 2020-01-15 2020-08-25 2020-02-19 2021-05-26 2020-08-17 lisateurs et Maintenance de ng Rural Land Institutions al Envelope cinq (05) Stations GNSS per manentes et d'un Centre de Contrôle CI-AFOR-89730-GO-RFQ / Ac Component 2 – Support Imp quisition de consommables i lementation of the National Request for Quot Single Stage - One IDA / 61900 Post Limited 70,000.00 65,677.52 Completed 2019-03-11 2019-01-08 2019-05-06 2019-02-10 2019-06-05 2020-02-09 nformatiques pour l'AFOR et Rural Land Tenure Security ations Envelope ses structures partenaires (I Program NPHB, INFPA,) CI-AFOR-141692-GO-RFQ / Component 2 – Support Imp Acquisition de motocyclettes lementation of the National Request for Quot Single Stage - One (90), de tricycles et de vélos IDA / 61900 Post Limited 250,000.00 185,625.19 Signed 2019-11-10 2020-01-08 2019-12-20 2020-02-22 2020-02-03 Rural Land Tenure Security ations Envelope pour les opérateurs fonciers Program dans le cadre de la composa nte 2 du PAMOFOR CI-AFOR-165401-GO-RFB / A cquisition de douze (12) Véh Component 1 – Strengtheni Single Stage - One icules pour les Opérateurs fo IDA / 61900 Post Request for Bids Open - National 850,000.00 726,732.94 Signed 2020-04-30 2020-04-10 2020-05-05 2020-04-10 2020-06-16 2020-05-27 2020-07-16 2020-07-07 2020-08-20 2020-08-21 2021-02-16 ng Rural Land Institutions Envelope nciers du Sud Come et de l'I ndénnie, du BAFING-N'ZI et l 'observatoire du Foncier CI-AFOR-174140-GO-RFQ / Component 4 – Program Co Acquisition de Mobiliers pour Request for Quot Single Stage - One Pending Impl IDA / 61900 ordination, Monitoring and Post Limited 80,000.00 0.00 2020-06-16 2020-07-21 2020-08-05 les Bâtiments des Directions ations Envelope ementation Knowledge Management Techniques de l'Agence Fon cière Rurale (AFOR) CI-AFOR-174141-GO-RFQ / Component 2 – Support Imp Acquisition de trois (03) Véhi lementation of the National Request for Quot Single Stage - One Pending Impl cules pour les besoins de l'A IDA / 61900 Post Limited 300,000.00 0.00 2020-07-12 2020-08-18 2020-10-17 Rural Land Tenure Security ations Envelope ementation gence Foncière Rurale (AFO Program R) et des opérateurs Foncier s du PAMOFOR CI-AFOR-174155-GO-RFQ / Component 2 – Support Imp Acquisition de Motos de type lementation of the National Request for Quot Single Stage - One Tout Terrain et trycycles pou IDA / 61900 Post Limited 95,000.00 94,709.09 Completed 2020-06-13 2020-07-16 2020-07-16 2020-09-05 2020-08-15 2020-09-05 Rural Land Tenure Security ations Envelope r les opérateurs fonciers des Program régions du SUD COMOE et d e l'Indénnié-Djuablin CI-AFOR-174160-GO-RFQ / Acquisition et mise en servic Component 4 – Program Co Request for Quot Single Stage - One Pending Impl e d'un logiciel de base de do IDA / 61900 ordination, Monitoring and Post Limited 15,000.00 0.00 2020-06-16 2020-07-31 2020-09-29 ations Envelope ementation nnées fournisseurs pour l'Ag Knowledge Management ence Foncière Rurale (AFOR) Page 3 CI-AFOR-165402-GO-RFQ / Recrutement d'un Prestatair e pour la Fourniture de moul Component 1 – Strengtheni Request for Quot Single Stage - One Under Imple IDA / 61900 Post Limited 10,000.00 0.00 2020-06-06 2020-05-28 2020-07-10 2020-07-20 e de précision de 12,5 kg à ng Rural Land Institutions ations Envelope mentation mettre à la disposition des O pérateurs Fonciers (70 écha ntillons à dupliquer) CI-AFOR-153023-GO-RFQ / Component 2 – Support Imp Acqusition de Matériels infor lementation of the National Request for Quot Single Stage - One IDA / 61900 Post Limited 100,000.00 91,244.81 Signed 2020-06-07 2020-07-17 2020-07-19 2020-08-21 2020-08-09 matiques pour les Opérateur Rural Land Tenure Security ations Envelope s fonciers du BAFING-N'ZI Program CI-AFOR-141696-GO-RFQ / Component 2 – Support Imp Acquisition de Matériels info lementation of the National Request for Quot Single Stage - One rmatiques (Ordinateurs, sca IDA / 61900 Post Limited 120,000.00 0.00 Canceled 2019-11-05 2019-12-13 2020-06-10 Rural Land Tenure Security ations Envelope nners etc.) pour les opérate Program urs fonciers et les besoins d e l'AFOR CI-AFOR-174157-GO-RFQ / Acquisition de Motos de Typ Component 2 – Support Imp e Tout Terrain (4X4) pour les lementation of the National Request for Quot Single Stage - One opérateurs fonciers des régi IDA / 61900 Post Limited 150,000.00 0.00 Canceled 2020-07-05 2020-08-07 2020-09-06 Rural Land Tenure Security ations Envelope ons du BAFING, du N'ZI de l' Program AGNEBY-TIASSA et de la ME dans le cadre de la mise en oeuvre du PAMOFOR CI-AFOR-141704-GO-RFQ / F Component 2 – Support Imp ourniture de Matériels infor lementation of the National Request for Quot Single Stage - One IDA / 61900 Post Limited 95,000.00 90,727.91 Signed 2020-08-08 2020-07-17 2020-09-11 2020-10-03 2020-10-11 matiques pour les Opérateur Rural Land Tenure Security ations Envelope s fonciers du Sud Comoé et l Program 'Indennie DJUABLIN CI-AFOR-187435-GO-DIR / A cquisition de produits d'hygi Component 4 – Program Co ène (Masques de protection, Pending Impl IDA / 61900 ordination, Monitoring and Post Direct Selection Direct 10,000.00 0.00 2020-08-12 2020-08-13 2020-08-18 2021-08-13 gels main etc.) pour la prote ementation Knowledge Management ction des agents de l'AFOR d ans le cadre des activités de l'AFOR CI-AFOR-141702-GO-RFQ / Acquisition de matériels top Component 2 – Support Imp ographiques pour les opérat lementation of the National Request for Quot Single Stage - One IDA / 61900 Post Limited 80,000.00 0.00 Canceled 2019-11-10 2019-12-25 2020-01-24 eurs fonciers dans le cadre d Rural Land Tenure Security ations Envelope e la mise en oeuvre de la sé Program curisation foncière dans le c adre du PAMOFOR CI-AFOR-89726-GO-RFQ / Ac Component 2 – Support Imp quisition de matériel techniq lementation of the National Request for Quot Single Stage - One IDA / 61900 Post Limited 95,000.00 90,307.87 Signed 2020-08-09 2020-07-16 2020-09-06 2021-01-08 2020-10-06 ues (GPS, Drones, Théodolit Rural Land Tenure Security ations Envelope e etc.) pour l'AFOR, l'INPHB Program et l'INFPA CI-AFOR-153286-GO-RFQ / F Component 4 – Program Co ourniture et installation de s Request for Quot Single Stage - One Under Imple IDA / 61900 ordination, Monitoring and Post Limited 95,000.00 0.00 2020-02-18 2020-05-28 2020-04-03 2021-03-29 ystème de sécurité informati ations Envelope mentation Knowledge Management que pour l'AFOR (Parefeus, a ntivirus) CI-AFOR-141709-GO-RFQ / Acquisition de Liasses pour l Component 2 – Support Imp es Délimitation de Territoire lementation of the National Request for Quot Single Stage - One IDA / 61900 Post Limited 95,000.00 93,296.49 Completed 2019-12-03 2020-07-15 2020-01-28 2020-09-04 2020-02-03 2020-09-05 s de Villages et de Certificat Rural Land Tenure Security ations Envelope s Fonciers et impression d'o Program utils, guides et kits dans le cadre du PAMOFOR CI-AFOR-122806-GO-RFQ / Acquisition d’équipements t echniques et petits équipem Component 4 – Program Co Request for Quot Single Stage - One ents de bureau pour les ante IDA / 61900 ordination, Monitoring and Post Limited 65,000.00 54,579.61 Signed 2019-09-30 2020-07-17 2019-11-09 2020-11-17 2019-12-09 ations Envelope nns régionales de l'AFOR (rel Knowledge Management ieuses, Portables, Matériels de sonorisation, Bottes, Imp erméable etc. CI-AFOR-187462-GO-RFB / F Component 2 – Support Imp ourniture de Matériels infor lementation of the National Single Stage - One Pending Impl IDA / 61900 Post Request for Bids Open - National 350,000.00 0.00 2020-09-30 2020-10-05 2020-11-16 2020-12-16 2021-01-20 2022-01-15 matiques et Bureautiques p Rural Land Tenure Security Envelope ementation our l'Agence Foncière Rurale Program (AFOR) CI-AFOR-153411-GO-RFQ / Acquisition de Matériels Info Component 4 – Program Co Request for Quot Single Stage - One rmatiques et Bureautiques p IDA / 61900 ordination, Monitoring and Post Limited 60,000.00 0.00 Canceled 2020-02-11 2020-03-22 2020-04-21 ations Envelope our le Master Foncier Rural d Knowledge Management e l'Université Allassane Ouat tara CI-AFOR-216009-GO-RFQ-2 Component 1 – Strengtheni Request for Quot Single Stage - One 1 / Acquisition de mobilier d IDA / 61900 Post Open - National 24,790.00 23,809.70 Completed 2021-02-27 2021-04-24 2021-10-09 2021-10-21 2021-12-11 ng Rural Land Institutions ations Envelope e bureau pour la Direction d u Foncier Rural CI-AFOR-216010-GO-RFQ-2 1 / Fourniture de bureau pou Component 1 – Strengtheni Request for Quot Single Stage - One IDA / 61900 Post Open - National 24,810.00 26,218.19 Signed 2021-05-19 2021-07-14 2021-06-04 2022-01-10 r la Direction du foncier Rura ng Rural Land Institutions ations Envelope l, des COTIF et des ROT CI-AFOR-216063-GO-RFQ-2 Component 1 – Strengtheni Request for Quot Single Stage - One 1 / Acquisition de consomma IDA / 61900 Post Open - National 10,890.00 25,124.25 Signed 2021-05-15 2021-07-10 2021-08-20 2022-01-06 ng Rural Land Institutions ations Envelope bles informatiques pour la D FR et l'ESA CI-AFOR-216106-GO-RFQ-2 Component 1 – Strengtheni Request for Quot Single Stage - One Pending Impl 1 / Acquisition de matériels IDA / 61900 Post Open - National 43,100.00 0.00 2021-05-11 2021-07-06 2022-01-02 ng Rural Land Institutions ations Envelope ementation médiatiques au profit des O NG CI-AFOR-216161-GO-RFQ-2 1 / Acquisition d'équipement Component 3 – Training for Request for Quot Single Stage - One IDA / 61900 Post Open - National 36,300.00 36,492.94 Signed 2021-04-20 2021-06-15 2021-08-10 2021-12-12 pédagogique pour l'Ecole Su Land Tenure Professionals ations Envelope périeure d'Agronomie (ESA) CI-AFOR-216307-GO-RFQ-2 1 / Acquisition de matériels i Component 1 – Strengtheni Request for Quot Single Stage - One Pending Impl IDA / 61900 Post Open - National 27,220.00 0.00 2021-03-01 2021-04-26 2021-10-23 nformatiques et bureautique ng Rural Land Institutions ations Envelope ementation s pour le siège de l'AFOR CI-AFOR-216646-GO-RFQ-2 Component 2 – Support Imp Request for Quot Single Stage - One 1 / Acquisition de liasses DT IDA / 61900 lementation of the National Post Open - National 217,790.00 104,401.66 Signed 2021-03-03 2021-04-28 2021-02-26 2021-10-25 ations Envelope V et CF Rural Land Tenure Security Program CI-AFOR-217508-GO-RFQ-2 1 / Acquisition de matériels i Component 1 – Strengtheni Request for Quot Single Stage - One IDA / 61900 Post Open - National 27,220.00 26,106.13 Completed 2021-03-13 2021-05-08 2021-06-10 2021-11-04 2021-07-06 nformatiques et bureautique ng Rural Land Institutions ations Envelope s pour le siège de l'AFOR CI-AFOR-217510-GO-RFQ-2 Component 1 – Strengtheni Request for Quot Single Stage - One 1 / Acquisition de mobilier d IDA / 61900 Post Open - National 30,490.00 12,868.61 Completed 2021-06-14 2021-08-09 2021-10-05 2022-02-05 2021-11-27 ng Rural Land Institutions ations Envelope e bureau pour le siège de l'A FOR CI-AFOR-217513-GO-RFB-21 Component 1 – Strengtheni Single Stage - One Pending Impl / Acquisition d'équipement i IDA / 61900 Post Request for Bids Open - National 544,460.00 0.00 2021-06-17 2021-06-22 2021-08-03 2021-09-02 2021-10-07 2022-04-05 ng Rural Land Institutions Envelope ementation nformatique pour les utilisat eurs du SIFOR CI-AFOR-217514-GO-RFQ-2 1 / Acquisition de mobilier p Component 1 – Strengtheni Request for Quot Single Stage - One Pending Impl IDA / 61900 Post Open - National 80,000.00 0.00 2021-06-15 2021-08-10 2022-02-06 our les bâtiments à usage d ng Rural Land Institutions ations Envelope ementation e Bureau Foncier Villageois ( BFV) Page 4 CI-AFOR-217516-GO-RFQ-2 1 / Acquisition de fourniture Component 1 – Strengtheni Request for Quot Single Stage - One IDA / 61900 Post Open - National 20,260.00 18,984.76 Signed 2021-07-24 2021-09-18 2021-09-04 2022-03-17 de Bureau pour les bâtimen ng Rural Land Institutions ations Envelope t à usage de Bureau Foncier Villageois (BFV) CI-AFOR-217517-GO-RFQ-2 Component 1 – Strengtheni Request for Quot Single Stage - One 1 / Acquisition de consomma IDA / 61900 Post Open - National 90,000.00 91,041.89 Signed 2021-03-29 2021-05-24 2021-04-20 2021-11-20 ng Rural Land Institutions ations Envelope bles informatiques pour l'AF OR CI-AFOR-217536-GO-RFQ-2 Component 3 – Training for Request for Quot Single Stage - One Pending Impl 1 / ACQUISITION DU MATERI IDA / 61900 Post Open - National 172,410.00 0.00 2021-07-21 2021-09-15 2022-03-14 Land Tenure Professionals ations Envelope ementation ELS ROULANTS POUR L'ESA CI-AFOR-217542-GO-RFQ-2 Component 3 – Training for Request for Quot Single Stage - One Pending Impl 1 / ACQUISITION DE BUS ET IDA / 61900 Post Open - National 125,000.00 0.00 2021-06-23 2021-08-18 2022-02-14 Land Tenure Professionals ations Envelope ementation DE CAMIONNETTE POUR TRA VAUX DE TERRAIN CI-AFOR-217600-GO-RFQ-2 1 / ACQUISITION DE MATERI Component 1 – Strengtheni Request for Quot Single Stage - One IDA / 61900 Post Open - National 294,010.00 347,832.62 Signed 2021-09-21 2021-11-16 2021-04-15 2022-05-15 EL ROULANT POUR LES ANT ng Rural Land Institutions ations Envelope ENNES REGIONALES CI-AFOR-217662-CS-INDV-2 1 / ACQUISITION D'EQUIPEM Component 1 – Strengtheni Request for Quot Single Stage - One Pending Impl IDA / 61900 Post Open - National 272,230.00 0.00 2021-10-05 2021-11-30 2022-05-29 ENT DE TRAVAIL POUR LES ng Rural Land Institutions ations Envelope ementation ORGANISATION DE LA SOCIE TE CIVILE CI-AFOR-218016-GO-RFQ-2 Component 1 – Strengtheni Request for Quot Single Stage - One Pending Impl 1 / Acquisition de matériels t IDA / 61900 Post Open - National 217,800.00 0.00 2021-05-04 2021-06-29 2021-12-26 ng Rural Land Institutions ations Envelope ementation éléphoniques pour le siège d e l'AFOR CI-AFOR-218037-GO-RFQ-2 Component 1 – Strengtheni Request for Quot Single Stage - One Pending Impl 1 / Acquisition de logiciel po IDA / 61900 Post Open - National 23,560.00 0.00 2021-07-18 2021-09-12 2022-03-11 ng Rural Land Institutions ations Envelope ementation ur le siège de l'AFOR CI-AFOR-218187-GO-RFQ-2 Component 1 – Strengtheni Request for Quot Single Stage - One Pending Impl 1 / Acquisition d'équipement IDA / 61900 Post Open - National 5,000.00 0.00 2021-05-02 2021-06-27 2021-12-24 ng Rural Land Institutions ations Envelope ementation pédagogique pour l'INFPA CI-AFOR-225521-GO-RFQ-K Component 1 – Strengtheni Request for Quot Single Stage - One K-21 / ACQUISITION D'IMPRI IDA / 61900 Post Open - National 4,000.00 3,841.74 Completed 2021-04-05 2021-05-31 2021-08-31 2021-11-27 2021-09-25 ng Rural Land Institutions ations Envelope MANTES MULTIFONCTIONS P OUR LES 6 ROT CI-AFOR-225572-GO-RFQ-K Component 1 – Strengtheni Request for Quot Single Stage - One Pending Impl K-21 / ACHAT DE PETITS REF IDA / 61900 Post Open - National 1,000.00 0.00 2021-06-21 2021-08-16 2022-02-12 ng Rural Land Institutions ations Envelope ementation RIGERATEURS POUR SIX (06) ROT CI-AFOR-225579-GO-RFQ-K K-21 / ACQUISITION D'EQUIP Component 1 – Strengtheni Request for Quot Single Stage - One Pending Impl IDA / 61900 Post Open - National 1,000.00 0.00 2021-06-20 2021-08-15 2022-02-11 EMENT EN BOITE DE PHARM ng Rural Land Institutions ations Envelope ementation ACIE POUR LES SIX (06) ROT CI-AFOR-225592-GO-RFQ-K Component 1 – Strengtheni Request for Quot Single Stage - One IDA / 61900 Post Open - National 64,000.00 52,963.20 Signed 2021-05-31 2021-07-26 2021-06-25 2022-01-22 K-21 / ACQUISITION DU LOGI ng Rural Land Institutions ations Envelope CIEL GED CI-AFOR-225605-GO-RFQ-K Component 1 – Strengtheni Request for Quot Single Stage - One Pending Impl IDA / 61900 Post Open - National 27,000.00 0.00 2021-05-24 2021-07-19 2022-01-15 K-21 / MAINTENANCE INFOR ng Rural Land Institutions ations Envelope ementation MATIQUE CI-AFOR-225607-GO-RFQ-K Component 1 – Strengtheni Request for Quot Single Stage - One Under Imple IDA / 61900 Post Open - National 54,000.00 0.00 2021-09-21 2021-11-16 2022-05-15 K-21 / CONSOMMABLES INF ng Rural Land Institutions ations Envelope mentation ORMATIQUES CI-AFOR-225612-GO-RFB-KK -21 / ACQUISITION D'EQUIPE Component 1 – Strengtheni Single Stage - One Pending Impl IDA / 61900 Post Request for Bids Open - National 849,000.00 0.00 2021-06-24 2021-06-29 2021-08-10 2021-09-09 2021-10-14 2022-04-12 MENT CORS, EQUIPEMENT E ng Rural Land Institutions Envelope ementation T MISE EN ROUTE DES EQUI PEMENTS CI-AFOR-225620-GO-RFQ-K Component 2 – Support Imp Request for Quot Single Stage - One Pending Impl K-21 / ACQUISITION DU LOGI IDA / 61900 lementation of the National Post Open - National 45,000.00 0.00 2021-09-27 2021-11-22 2022-05-21 ations Envelope ementation CIEL (ARCGIS). Rural Land Tenure Security Program CI-AFOR-225622-GO-RFQ-K Component 3 – Training for Request for Quot Single Stage - One Pending Impl K-21 / CARBURANT POUR SU IDA / 61900 Post Open - National 100.00 0.00 2021-06-22 2021-08-17 2022-02-13 Land Tenure Professionals ations Envelope ementation IVI DE TERRAIN DES STAGIAI RES CI-AFOR-226061-GO-RFQ-2 Component 1 – Strengtheni Request for Quot Single Stage - One Pending Impl 1 / Achat de véhicules Pick u IDA / 61900 Post Open - National 66,000.00 0.00 2021-03-31 2021-05-26 2021-11-22 ng Rural Land Institutions ations Envelope ementation p pour les ROT ( 6 véhicules) CI-AFOR-226438-GO-RFQ-2 1 / Contrat avec le Cabinet Component 1 – Strengtheni Under Imple Map Application Building po IDA / 61900 Post Direct Selection 35,607.00 0.00 2021-04-06 2021-07-21 2021-04-11 2021-05-16 2021-11-12 ng Rural Land Institutions mentation ur l'acquisition de base de d onnées cartographiques des forets déclassées CI-AFOR-226450-GO-RFQ-2 Component 1 – Strengtheni Request for Quot Single Stage - One 1 / Acquisition de mobiliers IDA / 61900 Post Open - National 36,297.00 33,713.69 Completed 2021-04-14 2021-06-09 2021-08-12 2021-12-06 2021-09-21 ng Rural Land Institutions ations Envelope de bureau pour la salle d'arc hivage CI-AFOR-242691-GO-RFQ-2 1 / Acquisition de consomma Component 1 – Strengtheni Request for Quot Single Stage - One Under Imple IDA / 61900 Post Limited 54,450.00 0.00 2021-07-20 2021-10-06 2021-09-14 2022-03-13 bles informatiques pour les ng Rural Land Institutions ations Envelope mentation antennes déconcentrées de l'AFOR CI-AFOR-279302-GO-RFQ-K K-22 / Fourniture de carbura Component 1 – Strengtheni Request for Quot Single Stage - One Pending Impl nt pour la réalisation des act IDA / 61900 Post Open - National 26,134.00 0.00 2022-04-13 2022-06-08 2022-12-05 ng Rural Land Institutions ations Envelope ementation ions de suivi et de contrôle p our l'AFOR/ représentations l ocales de l'AFOR CI-AFOR-279303-GO-RFQ-K Component 2 – Support Imp Request for Quot Single Stage - One Pending Impl K-22 / Acquisition GPS BI FR IDA / 61900 lementation of the National Post Open - National 41,742.00 0.00 2022-04-01 2022-05-27 2022-11-23 ations Envelope ementation EQUENCE et d'un carnet Rural Land Tenure Security Program CI-AFOR-281526-GO-RFQ-K Component 1 – Strengtheni Request for Quot Single Stage - One Pending Impl K-22 / Fournitures et consom IDA / 61900 Post Open - National 10,900.00 0.00 2022-04-13 2022-06-08 2022-12-05 ng Rural Land Institutions ations Envelope ementation mables informatiques pour l a DFR CI-AFOR-281531-GO-RFQ-K Component 1 – Strengtheni Request for Quot Single Stage - One Pending Impl K-22 / Matériel informatique IDA / 61900 Post Open - National 90,745.00 0.00 2022-04-03 2022-05-29 2022-11-25 ng Rural Land Institutions ations Envelope ementation pour équiper la DFR CI-AFOR-281530-GO-RFQ-K Component 1 – Strengtheni Request for Quot Single Stage - One K-22 / Consommables inform IDA / 61900 Post Open - National 90,745.00 0.00 Canceled 2022-05-05 2022-06-30 2022-12-27 ng Rural Land Institutions ations Envelope atiques pour les COTIF CI-AFOR-281529-GO-RFQ-K Component 1 – Strengtheni Request for Quot Single Stage - One K-22 / Consommables inform IDA / 61900 Post Open - National 99,820.00 0.00 Canceled 2022-04-30 2022-06-25 2022-12-22 ng Rural Land Institutions ations Envelope atiques pour les ROT CI-AFOR-281528-GO-RFQ-K Component 4 – Program Co Request for Quot Single Stage - One K-22 / Consommables inform IDA / 61900 ordination, Monitoring and Post Open - National 99,820.00 0.00 Canceled 2022-04-11 2022-06-06 2022-12-03 ations Envelope atiques pour l’AFOR Knowledge Management CI-AFOR-279299-GO-RFB-KK Component 1 – Strengtheni Single Stage - One IDA / 61900 Post Request for Bids Open - National 272,232.00 0.00 Canceled 2022-04-08 2022-04-13 2022-05-25 2022-06-24 2022-07-29 2023-01-25 -22 / Acquisition de liasse DT ng Rural Land Institutions Envelope V et CF Page 5 CI-AFOR-284219-GO-RFB-KK Component 1 – Strengtheni Single Stage - One -22 / Acquisition de matériel IDA / 61900 Post Request for Bids Open - National 136,117.00 0.00 Canceled 2022-03-23 2022-03-28 2022-05-09 2022-06-08 2022-07-13 2023-01-09 ng Rural Land Institutions Envelope s informatiques pour les opé rateurs fonciers CI-AFOR-363452-GO-RFQ-2 Component 1 – Strengtheni Request for Quot Single Stage - One Pending Impl IDA / 61900 Post Limited 1,459.00 0.00 2023-06-06 2023-08-01 2024-01-28 3 / Acquisition de mobilier d ng Rural Land Institutions ations Envelope ementation e bureau CI-AFOR-363468-GO-RFQ-2 Component 1 – Strengtheni Request for Quot Single Stage - One Pending Impl 3 / ACQUISITION DE MATERI IDA / 61900 Post Limited 1,626.00 0.00 2023-06-11 2023-08-06 2024-02-02 ng Rural Land Institutions ations Envelope ementation EL INFORMATIQUE POUR L'A FOR CI-AFOR-364398-GO-RFQ / Acquisition de liasses pour l Component 1 – Strengtheni Request for Quot Single Stage - One Pending Impl IDA / 61900 Post Limited 90,744.00 0.00 2023-06-18 2023-08-13 2024-02-09 a Délimitation des Territoire ng Rural Land Institutions ations Envelope ementation s des Villages (DTV) et des C ERTIFICATS FONCIERS (CF). NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualificatio Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendatio Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus n Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes n for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CI-AFOR-89760-NC-RFQ / Re crutement d'un Prestataire p Component 4 – Program Co our la fourniture de Police d' Request for Quot Single Stage - One IDA / 61900 ordination, Monitoring and Post Limited 40,000.00 11,405.83 Signed 2019-03-23 2019-12-10 2019-05-18 2019-03-07 2020-05-17 Assurances (tous risques vé ations Envelope Knowledge Management hicules, Multirisque Professio nnelle et individuelle accide nt) pour l'AFOR CI-AFOR-89761-NC-RFQ / Re Component 4 – Program Co crutement d'un Prestataire p IDA / 61900 ordination, Monitoring and Post Direct Selection Direct 40,000.00 0.00 Canceled 2019-01-21 2019-01-26 2019-03-02 2020-03-01 our la fourniture de connexi Knowledge Management on internet mobile pour l'AF OR CI-AFOR-89762-NC-RFQ / Re Component 4 – Program Co crutement d'un Prestataire p Request for Quot Single Stage - One IDA / 61900 ordination, Monitoring and Post Limited 24,000.00 0.00 Canceled 2019-01-25 2019-03-22 2020-03-21 our la fourniture de services ations Envelope Knowledge Management d'entretien des locaux de l'A FOR CI-AFOR-89763-NC-RFQ / Re Component 4 – Program Co crutement d'un Prestataire p Request for Quot Single Stage - One IDA / 61900 ordination, Monitoring and Post Limited 24,000.00 0.00 Canceled 2019-02-04 2019-04-01 2020-03-31 our la fourniture de services ations Envelope Knowledge Management de gardiennage des locaux d e l'AFOR CI-AFOR-89767-NC-RFQ / Re Component 4 – Program Co crutement d'un Prestataire p Request for Quot Single Stage - One Pending Impl IDA / 61900 ordination, Monitoring and Post Limited 5,000.00 0.00 2019-03-25 2019-05-20 2020-05-19 our le service de géolocalisa ations Envelope ementation Knowledge Management tion de la flotte automobile de l'AFOR CI-AFOR-89770-NC-RFQ / Re crutement d'un Prestataire p Component 4 – Program Co Request for Quot Single Stage - One our la maintenance des équi IDA / 61900 ordination, Monitoring and Post Limited 15,000.00 0.00 Canceled 2018-12-25 2019-02-19 2020-02-19 ations Envelope pements informatiques, bur Knowledge Management eautiques et téléphoniques de l'AFOR CI-AFOR-89773-NC-RFQ / Re Component 4 – Program Co crutement d'un Prestataire p Request for Quot Single Stage - One IDA / 61900 ordination, Monitoring and Post Limited 30,000.00 0.00 Canceled 2019-02-15 2019-04-12 2019-05-12 our le Cablage réseau, infor ations Envelope Knowledge Management matique et téléphonique des locaux de l'AFOR CI-AFOR-90380-NC-RFQ / Re crutement d'un Prestataire p Component 4 – Program Co our la reprographie de docu Request for Quot Single Stage - One IDA / 61900 ordination, Monitoring and Post Limited 15,000.00 0.00 Canceled 2019-03-25 2019-05-20 2020-05-19 ments, outils de gestion et d ations Envelope Knowledge Management 'administration (Registre, Ca rnets de bord véhicule, carte de visite etc.) pour le PAMOF OR CI-AFOR-109061-NC-RFQ / R ecrutement d'un Prestataire Component 4 – Program Co Request for Quot Single Stage - One pour le Câblage réseaux, inf IDA / 61900 ordination, Monitoring and Post Limited 80,000.00 10,364.50 Completed 2019-07-08 2019-06-06 2019-09-02 2019-08-13 2019-10-02 2019-09-18 ations Envelope ormatique et téléphonique d Knowledge Management es locaux de l'Agence Fonciè re Rurale (AFOR) CI-AFOR-109062-NC-DIR / R ecrutement d'un Prestataire Component 4 – Program Co Pending Impl pour la fourniture de connex IDA / 61900 ordination, Monitoring and Post Direct Selection Direct 5,000.00 0.00 2019-05-06 2019-05-11 2019-06-15 2020-06-14 ementation ion internet mobile pour l'Ag Knowledge Management ence Foncière Rurale (AFOR) CI-AFOR-122823-NC-RFQ / R ecrutement d’un Prestataire Component 4 – Program Co Request for Quot Single Stage - One Under Imple pour la réalisation du Câblag IDA / 61900 ordination, Monitoring and Post Limited 40,000.00 0.00 2019-09-23 2019-11-18 2020-05-16 ations Envelope mentation e réseaux, internet et téléph Knowledge Management onique de la Direction Techn ique de l'AFOR CI-AFOR-122824-NC-DIR / R ecrutement d’un Prestataire Component 3 – Training for Pending Impl IDA / 61900 Post Direct Selection Direct 10,000.00 0.00 2019-09-05 2019-09-10 2019-10-15 2020-04-12 pour la fourniture de connex Land Tenure Professionals ementation ion internet mobile pour l’AF OR et l'ESA CI-AFOR-122825-NC-DIR / R Component 4 – Program Co ecrutement d'un Prestataire IDA / 61900 ordination, Monitoring and Post Direct Selection Direct 90,000.00 0.00 Canceled 2019-09-12 2019-09-17 2019-10-22 2020-04-19 pour l'entretien des Véhicule Knowledge Management s Pick-Up du PAMOFOR CI-AFOR-122827-NC-DIR / R Component 4 – Program Co ecrutement d'un Prestataire IDA / 61900 ordination, Monitoring and Post Direct Selection Direct 20,000.00 0.00 Canceled 2019-08-08 2019-08-08 2019-09-17 2020-09-16 pour l'entretien du véhicule Knowledge Management de liaison du PAMOFOR CI-AFOR-122828-NC-RFQ / R ecrutement d'un Prestataire Component 4 – Program Co Request for Quot Single Stage - One pour la fourniture de polices IDA / 61900 ordination, Monitoring and Post Limited 40,000.00 52,958.58 Signed 2019-09-16 2019-12-10 2019-11-11 2020-02-27 2020-05-09 ations Envelope d'assurances pour les Véhic Knowledge Management ules et motos acquis dans le cadre du PAMOFOR CI-AFOR-122871-NC-RFQ / R Component 2 – Support Imp ecrutement d'un Prestataire lementation of the National Request for Quot Single Stage - One pour l'organisation de cérém IDA / 61900 Post Limited 95,000.00 0.00 Canceled 2019-09-17 2019-10-27 2020-04-24 Rural Land Tenure Security ations Envelope onies d'information et de se Program nsibilisation sur l'approche 4 en 1 CI-AFOR-141770-NC-RFQ / R ecrutement d'un Prestataire Component 4 – Program Co Request for Quot Single Stage - One pour les travaux de câblage IDA / 61900 ordination, Monitoring and Post Limited 15,000.00 0.00 Canceled 2019-12-15 2020-02-09 2020-02-12 ations Envelope réseaux et informatiques de Knowledge Management s antennes régionales de l'A FOR CI-AFOR-153258-NC-RFB / R ecrutement d'un Prestataire Component 3 – Training for Single Stage - One pour l'organisation de forma IDA / 61900 Post Request for Bids Open - National 800,000.00 0.00 Canceled 2020-02-03 2020-02-08 2020-03-21 2020-04-10 2020-05-04 2020-10-31 Land Tenure Professionals Envelope tions au profit des acteurs d u PAMOFOR (Magistrats, Cor ps préfectoral, DR, DD etc) CI-AFOR-153264-NC-RFQ / R ecrutement d'un Prestataire Component 2 – Support Imp pour la location de Véhicules lementation of the National Request for Quot Single Stage - One Under Imple IDA / 61900 Post Limited 50,000.00 0.00 2020-02-08 2020-03-24 2020-09-20 pour la mise en œuvre des t Rural Land Tenure Security ations Envelope mentation ravaux de sécurisation fonci Program ère dans le cadre du PAMOF OR Page 6 CI-AFOR-165585-NC-RFQ / R ecrutement d'un Prestataire Component 1 – Strengtheni Request for Quot Single Stage - One Pending Impl pour l'organisation et la gest IDA / 61900 Post Limited 90,000.00 0.00 2020-05-27 2020-07-22 2021-01-18 ng Rural Land Institutions ations Envelope ementation ion complète des lancement du PAMOFOR dans les sous préfecture CI-AFOR-187461-GO-DIR / R Component 4 – Program Co enouvellement des licences IDA / 61900 ordination, Monitoring and Post Direct Selection Direct 22,000.00 18,384.57 Signed 2020-08-20 2020-08-12 2020-08-25 2020-08-06 2020-09-13 2020-08-18 2021-09-14 office des ordinateurs de l'A Knowledge Management gence Foncière Rurale (AFO R) CI-AFOR-216536-NC-RFQ-21 / Entretien et réparation des Component 1 – Strengtheni Request for Quot Single Stage - One Pending Impl véhicules et pneumatiques e IDA / 61900 Post Open - National 15,250.00 0.00 2021-03-31 2021-05-26 2021-11-22 ng Rural Land Institutions ations Envelope ementation t des motos des ROT, des an tennes régionales et des pos tes départementaux CI-AFOR-217545-NC-RFQ-21 / Entretien et réparation des Component 1 – Strengtheni Request for Quot Single Stage - One Pending Impl véhicules et pneumatique et IDA / 61900 Post Open - National 15,250.00 0.00 2021-04-24 2021-06-19 2021-12-16 ng Rural Land Institutions ations Envelope ementation des motos des ROT, des ant ennes régionales et des post es départementaux CI-AFOR-217546-NC-RFQ-21 / Entretien et réparation des Component 1 – Strengtheni Request for Quot Single Stage - One IDA / 61900 Post Open - National 32,280.00 28,711.78 Signed 2021-03-30 2021-05-25 2021-08-14 2021-11-21 véhicules et motos acquis d ng Rural Land Institutions ations Envelope ans le cadre du PAMOFOR CI-AFOR-217548-NC-RFQ-21 / RECRUTEMENT D'UN CONS Component 1 – Strengtheni Request for Quot Single Stage - One IDA / 61900 Post Open - National 37,000.00 36,126.39 Signed 2021-08-17 2021-10-12 2021-03-20 2022-04-10 ULTANT POUR LA MAINTENA ng Rural Land Institutions ations Envelope NCE DU RESEAU INFORMATI QUE DE L'AFOR CI-AFOR-217552-NC-RFQ-21 Component 2 – Support Imp / Recrutement d'un prestatai lementation of the National Request for Quot Single Stage - One re pour l'assurance des véhi IDA / 61900 Post Open - National 79,900.00 71,235.44 Signed 2021-04-27 2021-06-22 2021-03-12 2021-12-19 Rural Land Tenure Security ations Envelope cules, des motos et des tricy Program cles acquis dans le cadre du PAMOFOR CI-AFOR-218193-NC-RFQ-21 / Recrutement d'un prestatai Component 3 – Training for Request for Quot Single Stage - One Pending Impl re pour la fourniture de conn IDA / 61900 Post Open - National 16,530.00 0.00 2021-04-28 2021-06-23 2021-12-20 Land Tenure Professionals ations Envelope ementation exion internet téléphone et de communication pour l'INF PA CI-AFOR-225625-NC-RFQ-KK Component 3 – Training for Request for Quot Single Stage - One Pending Impl -21 / COUVERTURE ASSURA IDA / V1170 Post Open - National 51,000.00 0.00 2021-09-06 2021-11-01 2022-04-30 Land Tenure Professionals ations Envelope ementation NCE DES ETUDIANTS CI-AFOR-226506-NC-DIR-21 / Contrat avec ORANGE COT E D'IVOIRE pour la fournitur Component 1 – Strengtheni Pending Impl IDA / 61900 Post Direct Selection Direct 284,000.00 0.00 2021-04-09 2021-04-14 2021-05-19 2021-11-15 e de connexion internet et l'i ng Rural Land Institutions ementation nstallation de ligne spécialis ée pour 19 sites départemen taux et 6 sites régionaux CI-AFOR-226521-GO-RFQ-2 Component 1 – Strengtheni Request for Quot Single Stage - One Pending Impl 1 / Acquisition d'un système IDA / 61900 Post Open - National 56,000.00 0.00 2021-04-18 2021-06-13 2021-12-10 ng Rural Land Institutions ations Envelope ementation de vidéoconférence CI-AFOR-226524-NC-RFQ-21 / Acquisition d'un système d' Component 1 – Strengtheni Request for Quot Single Stage - One Pending Impl IDA / 61900 Post Open - National 20,000.00 0.00 2021-04-26 2021-06-21 2021-12-18 identification et d'inventaire ng Rural Land Institutions ations Envelope ementation électronique du patrimoine de l'AFOR CI-AFOR-226596-NC-DIR-21 Component 4 – Program Co / Convention avec la RTI pou Pending Impl IDA / 61900 ordination, Monitoring and Post Direct Selection Direct 72,595.00 0.00 2021-05-14 2021-05-19 2021-06-23 2021-12-20 r la diffusion de Prêt-A-Diffus ementation Knowledge Management er ( PAD), de spots et de co mmuniqués de l'AFOR CI-AFOR-242688-NC-RFQ-21 / Recrutement d'un prestatai Component 1 – Strengtheni Request for Quot Single Stage - One Pending Impl IDA / 61900 Post Limited 16,250.00 0.00 2021-07-17 2021-09-11 2022-03-10 re pour l'interconnexion des ng Rural Land Institutions ations Envelope ementation locaux du siège de l'AFOR CI-AFOR-242689-NC-RFQ-21 / Acquisition de logiciel 365 Component 1 – Strengtheni Request for Quot Single Stage - One IDA / 61900 Post Limited 51,200.00 47,111.28 Signed 2021-07-25 2021-08-09 2021-09-19 2021-08-24 2022-03-18 BUSINESS PREMIUM, Licence ng Rural Land Institutions ations Envelope s MS PROJECT, Licence ADO BE ACROBAT, Antivirus CI-AFOR-242694-NC-RFQ-21 / Recrutement d'un prestatai Component 1 – Strengtheni Request for Quot Single Stage - One Pending Impl IDA / 61900 Post Limited 1,815.00 0.00 2021-07-25 2021-09-19 2022-03-18 re pour la dématérialisation ng Rural Land Institutions ations Envelope ementation des dossiers de concessions CI-AFOR-242695-NC-RFQ-21 Component 1 – Strengtheni Request for Quot Single Stage - One Pending Impl / Recrutement d'un consulta IDA / 61900 Post Limited 23,590.00 0.00 2021-07-21 2021-09-15 2022-03-14 ng Rural Land Institutions ations Envelope ementation nt pour le développement d u site Web CI-AFOR-242700-NC-RFQ-21 / Recrutement d'un prestatai Component 1 – Strengtheni Request for Quot Single Stage - One Pending Impl re pour la maintenance du IDA / 61900 Post Limited 27,220.00 0.00 2021-07-24 2021-09-18 2022-03-17 ng Rural Land Institutions ations Envelope ementation matériel informatique dues antennes deconcentrées CI-AFOR-279304-NC-RFQ-KK Component 1 – Strengtheni Request for Quot Single Stage - One -22 / Entretien et réparation IDA / 61900 Post Open - National 5,450.00 0.00 Canceled 2022-06-04 2022-07-30 2023-01-26 ng Rural Land Institutions ations Envelope de véhicules et pneumatiqu e pour la DFR CI-AFOR-279309-NC-RFQ-KK Component 1 – Strengtheni Request for Quot Single Stage - One -22 / Abonnement et conso IDA / 61900 Post Open - National 2,000.00 0.00 Canceled 2022-04-23 2022-06-18 2022-12-15 ng Rural Land Institutions ations Envelope mmation internet pour la DF R CI-AFOR-363720-NC-RFQ-23 Component 1 – Strengtheni Request for Quot Single Stage - One Pending Impl / ENTRETIEN ET REPARATIO IDA / 61900 Post Limited 1,270.00 0.00 2023-06-21 2023-08-16 2024-02-12 ng Rural Land Institutions ations Envelope ementation N DES VEHICULES DE L'AFO R CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amoun Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Techni Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) t (US$) Notice equest for Proposals as Issued Proposals / Minutes cal Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CI-AFOR-89774-CS-QCBS / S Component 4 – Program Co élection d'un cabinet, pour l' Quality And Cost- IDA / 61900 ordination, Monitoring and Post Open - National 90,000.00 33,356.65 Signed 2019-01-08 2019-01-09 2019-01-29 2019-02-25 2019-03-07 2019-03-25 2019-05-08 2019-04-04 2019-05-29 2019-05-04 2019-07-31 2019-06-02 2019-11-07 2022-02-26 audit financier et comptable Based Selection Knowledge Management des trois premiers exercices du projet CI-AFOR-89776-CS-QCBS / S élection d'un Consultant Indi Component 4 – Program Co Consultant Qualifi viduel pour la réalisation d'u IDA / 61900 ordination, Monitoring and Post Open - National 90,000.00 0.00 Canceled 2019-01-15 2019-01-25 2019-02-21 2019-03-23 2019-04-27 2019-07-26 cation Selection ne étude pour la mise en pla Knowledge Management ce d'un système de suivi-év aluation pour le Projet CI-AFOR-89787-CS-QBS / Re Component 2 – Support Imp crutement d'une entreprise lementation of the National Quality Based Sel Open - Internation pour les travaux de sécurisa IDA / 61900 Prior 8,000,000.00 4,865,027.56 Signed 2018-12-24 2019-01-14 2019-02-27 2019-04-26 2019-03-27 2019-07-03 2019-04-26 2019-08-05 2019-05-26 2020-02-10 2019-06-30 2020-03-16 2022-12-11 Rural Land Tenure Security ection al tion foncière dans les région Program s du SUD COMOE et de l'IND ENIE DJUABLIN Page 7 CI-AFOR-89789-CS-QBS / Re Component 2 – Support Imp crutement d'une entreprise lementation of the National Quality Based Sel Open - Internation pour les travaux de sécurisa IDA / 61900 Prior 8,000,000.00 4,829,608.03 Signed 2018-12-23 2019-01-13 2019-02-26 2019-04-26 2019-03-26 2019-07-03 2019-04-25 2019-08-05 2019-05-25 2019-11-27 2019-06-29 2019-12-13 2022-12-10 Rural Land Tenure Security ection al tion foncière dans les région Program s de la ME et de l'AGNEBY TI ASSA CI-AFOR-89791-CS-QBS / Re Component 2 – Support Imp crutement d'une entreprise lementation of the National Quality Based Sel Open - Internation pour les travaux de sécurisa IDA / 61900 Prior 8,000,000.00 3,963,891.01 Signed 2018-12-23 2019-01-13 2019-02-26 2019-04-26 2019-03-26 2019-07-03 2019-04-25 2019-08-05 2019-05-25 2020-02-18 2019-06-29 2020-03-17 2022-12-10 Rural Land Tenure Security ection al tion foncière dans les région Program s du BAFING et du N'ZI COM OE CI-AFOR-89792-CS-CQS / Re Component 2 – Support Imp crutement d'un Cabinet pour lementation of the National Consultant Qualifi IDA / 61900 Post Open - National 90,000.00 0.00 Canceled 2019-03-20 2019-04-10 2019-05-24 2019-06-23 2019-07-28 2020-01-24 la conception et le développ Rural Land Tenure Security cation Selection ement d'un nouveau SIF Program CI-AFOR-109052-CS-QCBS / Recrutement d'un Cabinet p Component 1 – Strengtheni Quality And Cost- IDA / 61900 Post Open - National 100,000.00 48,828.98 Signed 2019-07-01 2019-06-06 2019-07-22 2019-09-04 2019-08-27 2019-10-02 2019-11-08 2019-11-01 2019-12-10 2019-12-06 2020-01-28 2020-01-10 2020-02-28 2020-04-09 our l'élaboration d'un Plan st ng Rural Land Institutions Based Selection ratégique sur les Droits Fonc iers CI-AFOR-109055-CS-CQS / R ecrutement d'une entreprise pour l'organisation de la Con Component 3 – Training for Consultant Qualifi IDA / 61900 Post Limited 150,000.00 314,854.29 Completed 2019-05-06 2019-06-06 2019-05-20 2019-06-13 2019-06-04 2019-10-10 2019-06-28 2019-11-05 2019-09-26 2019-12-14 férence sur le renforcement Land Tenure Professionals cation Selection des capacités des ressource s humaines, dans le domain e du foncier CI-AFOR-109060-CS-QCBS / Recrutement d'un Cabinet p Component 2 – Support Imp our la conception, le dévélop lementation of the National Quality And Cost- Open - Internation IDA / 61900 Prior 500,000.00 2,722,922.80 Signed 2019-05-07 2019-05-13 2019-05-28 2019-05-20 2019-07-11 2019-08-29 2019-08-08 2019-11-29 2019-09-07 2019-12-31 2019-10-12 2020-07-07 2019-11-16 2020-07-24 2020-05-14 pement et la mise en place Rural Land Tenure Security Based Selection al d'un nouveau système d'info Program rmation foncière (SIF) pour l' AFOR CI-AFOR-122835-CS-CQS / R Component 2 – Support Imp ecrutement d'un Ingénieur C lementation of the National Consultant Qualifi Under Implement IDA / 61900 Post Limited 100,000.00 0.00 2019-09-03 2019-09-27 2019-09-17 2020-06-10 2019-10-17 2020-10-23 2019-11-21 2020-05-19 onseil pour l'accompagneme Rural Land Tenure Security cation Selection ation nt de l'AFOR dans la mise en Program place du SIF CI-AFOR-122872-CS-CQS / R Component 1 – Strengtheni Consultant Qualifi ecrutement d'un Prestataire IDA / 61900 Post Limited 250,000.00 0.00 Canceled 2019-09-25 2019-10-09 2019-11-08 2019-12-13 2020-06-10 ng Rural Land Institutions cation Selection pour la formation des Acteur s CI-AFOR-141786-CS-CQS / R Component 2 – Support Imp ecrutement d'un Consultant lementation of the National Consultant Qualifi pour la mise en place d'un a IDA / 61900 Post Limited 30,000.00 0.00 Canceled 2019-10-31 2019-10-25 2019-11-14 2019-11-19 2019-12-13 2020-01-12 Rural Land Tenure Security cation Selection pplicatif informatique de sui Program vi des opérations de sécuris ation foncière CI-AFOR-141805-CS-CQS / R Component 4 – Program Co Consultant Qualifi Open - Internation ecrutement d'une firme pour IDA / 61900 ordination, Monitoring and Post 30,000.00 36,371.29 Signed 2019-10-30 2019-10-25 2019-11-01 2019-10-30 2019-11-29 2019-12-03 2019-12-09 2019-12-20 2019-12-28 2020-01-28 2020-02-26 cation Selection al le contrôle qualité des imag Knowledge Management es satellitaires CI-AFOR-141813-CS-CQS / R Component 2 – Support Imp ecrutement d'une firme pour lementation of the National Consultant Qualifi IDA / 61900 Post Limited 30,000.00 0.00 Canceled 2019-11-29 2019-12-13 2019-12-23 2020-01-27 2020-02-02 le suivi et contrôle des trava Rural Land Tenure Security cation Selection ux de construction de secret Program ariats villageois CI-AFOR-141819-CS-CQS / R ecrutement d'un Consultant Component 3 – Training for Consultant Qualifi Open - Internation Pending Impleme IDA / 61900 Post 50,000.00 0.00 2019-11-01 2019-11-22 2020-01-05 2020-02-04 2020-03-10 2020-09-06 pour réaliser l'Etude relative Land Tenure Professionals cation Selection al ntation au plan de formation aux m étiers du foncier rural CI-AFOR-142210-CS-CQS / R ecrutement d'un Cabinet po Component 2 – Support Imp ur la conception et la diffusi lementation of the National Consultant Qualifi IDA / 61900 Post Limited 50,000.00 255,913.53 Signed 2019-11-14 2019-10-30 2019-11-28 2020-02-10 2019-12-08 2020-06-09 2019-12-27 2020-10-03 2020-06-24 on de messages de sensibili Rural Land Tenure Security cation Selection sation sur les radios rurales Program des zones du PAMOFOR sur l 'approche 4 en 1. CI-AFOR-142213-CS-CQS / R ecrutement d'une firme pour Component 4 – Program Co Consultant Qualifi Under Implement la réalisation d'un système d IDA / V1170 ordination, Monitoring and Post Limited 50,000.00 0.00 2019-11-15 2019-10-30 2019-11-29 2019-12-09 2020-01-13 2021-01-12 cation Selection ation 'archivage électronique de P Knowledge Management assation des Marchés pour l' AFOR CI-AFOR-153413-CS-CQS / R ecrutement d'une Firme pou r une Assistance a la Maîtris Component 1 – Strengtheni Consultant Qualifi Open - Internation e d'ouvrage dans le cadre d IDA / 61900 Post 150,000.00 0.00 Under Review 2020-01-23 2020-02-17 2020-02-13 2020-03-28 2020-04-27 2020-05-21 2021-05-21 ng Rural Land Institutions cation Selection al e la mise en oeuvre du Cont rat de conception détaillée, de développement et de mis e en place du SIFOR CI-AFOR-159966-CS-CQS / R ecrutement d'un Prestataire Component 3 – Training for Consultant Qualifi Under Implement pour l'organisation de forma IDA / 61900 Post Open - National 600,000.00 0.00 2020-02-24 2020-03-11 2020-03-16 2020-03-13 2020-04-29 2020-05-29 2020-06-17 2020-12-14 Land Tenure Professionals cation Selection ation tions au profit des acteurs d u PAMOFOR (Magistrats, Cor ps préfectoral, DR, DD etc). CI-AFOR-165398-CS-QCBS / Recrutement d'une Agence Component 1 – Strengtheni Quality And Cost- Under Implement IDA / 61900 Post Open - National 150,000.00 0.00 2020-06-30 2020-04-10 2020-07-21 2020-07-13 2020-09-03 2020-07-11 2020-10-01 2020-04-23 2020-10-31 2020-03-19 2020-12-05 2021-01-09 2022-01-09 de Communication pour la M ng Rural Land Institutions Based Selection ation ise en œuvre du plan stratég ique de communication CI-AFOR-153268-CS-CQS / R ecrutement d'une Firme pou Component 1 – Strengtheni Consultant Qualifi Open - Internation r la conception, les études t IDA / 61900 Post 250,000.00 0.00 Canceled 2020-02-03 2020-02-24 2020-04-08 2020-05-08 2020-06-01 2021-06-02 ng Rural Land Institutions cation Selection al echniques et la supervision du Contrat de fourniture et i nstallation de Stations CORS CI-AFOR-217390-CS-CQS-21 / Recrutement d'un consulta nt pour l'élaboration d'un re Component 1 – Strengtheni Consultant Qualifi Pending Impleme IDA / 61900 Post Open - National 16,330.00 0.00 2021-03-31 2021-04-21 2021-06-04 2021-07-04 2021-08-08 2022-02-04 cueil des tests juridiques et r ng Rural Land Institutions cation Selection ntation èglementaire relatif au fonci er Rural ( conception et repr ographie ) CI-AFOR-217392-CS-CQS-21 / Recrutement d'un consulta Component 1 – Strengtheni Consultant Qualifi Pending Impleme IDA / 61900 Post Open - National 42,110.00 0.00 2021-03-18 2021-04-08 2021-05-22 2021-06-21 2021-07-26 2022-01-22 nt individuel pour le contrôle ng Rural Land Institutions cation Selection ntation et suivi des travaux CI-AFOR-218000-CS-CQS-21 / recrutement de consultant Component 1 – Strengtheni Consultant Qualifi Under Implement IDA / 61900 Post Open - National 272,230.00 0.00 2021-05-24 2021-05-18 2021-06-14 2021-07-28 2021-08-27 2021-10-01 2022-03-30 s pour le suivi et l'observatio ng Rural Land Institutions cation Selection ation n des opérations de sécurisa tion foncière rurale CI-AFOR-218189-CS-CQS-21 / RECRUTEMENT D'UN CONS ULTANT POUR LA CONCEPTI Component 3 – Training for Consultant Qualifi Under Implement IDA / 61900 Post Open - National 12,704.00 0.00 2021-04-26 2021-06-25 2021-05-17 2021-06-30 2021-07-30 2021-09-03 2022-03-02 ON DE MODULES POUR L'EN Land Tenure Professionals cation Selection ation A, L'ECOLE DE MAGISTRATU RE ET L'ECOLE DE GENDAR MERIE Page 8 CI-AFOR-212205-CS-QBS-21 / RECRUTEMENT D'UNE AGE NCE DE COMMUNICATION P Component 4 – Program Co Quality Based Sel OUR L'EXECUTION DE LA ST IDA / 61900 ordination, Monitoring and Post Open - National 544,480.00 308,952.00 Signed 2021-01-13 2021-03-30 2021-02-03 2021-10-21 2021-03-19 2021-08-10 2021-04-16 2021-08-10 2021-05-16 2021-08-10 2021-06-15 2021-08-12 2021-07-20 2021-10-02 2022-07-20 ection RATEGIE DE COMMUNICATIO Knowledge Management N DU PROGRAMME NATIONA L DE LA SECURISATION FON CIERE RURALE CI-AFOR-226058-CS-INDV-2 1 / Recrutement d'une agen Component 4 – Program Co ce de communication pour l Quality Based Sel IDA / 61900 ordination, Monitoring and Post Open - National 91,000.00 106,653.60 Completed 2021-04-02 2021-03-30 2021-04-23 2021-10-12 2021-06-06 2021-08-10 2021-07-04 2021-08-10 2021-08-03 2021-08-10 2021-09-02 2021-08-10 2021-10-07 2021-08-13 2022-10-07 2021-10-07 a réalisation et la diffusion d ection Knowledge Management 'un publi-reportage sur les o pérations intégrées du PAM OFOR CI-AFOR-226234-CS-CQS-21 / Recrutement d'un consulta Component 1 – Strengtheni Consultant Qualifi Pending Impleme IDA / 61900 Post Open - National 54,000.00 0.00 2021-04-08 2021-04-29 2021-06-12 2021-07-12 2021-08-16 2022-02-12 nt pour l'assistance techniqu ng Rural Land Institutions cation Selection ntation e en appui à la Direction du Foncier Rural CI-AFOR-226525-CS-QBS-21 / Recrutement d'un cabinet Component 1 – Strengtheni Quality Based Sel Under Implement IDA / 61900 Post Open - National 36,000.00 0.00 2021-04-15 2021-09-30 2021-05-06 2021-06-19 2021-07-17 2021-08-16 2021-09-15 2021-10-20 2022-10-20 d'avocat pour une assistanc ng Rural Land Institutions ection ation e juridique et judiciaire CI-AFOR-228035-CS-QBS-21 / Recrutement d'organisatio n de la société civile en vue Component 1 – Strengtheni Quality Based Sel Under Implement IDA / 61900 Post Open - National 272,232.00 0.00 2021-04-09 2021-04-20 2021-04-30 2021-06-13 2021-07-11 2021-08-10 2021-09-09 2021-10-14 2022-10-14 d'assurer le suivi, l'observati ng Rural Land Institutions ection ation on et l'évaluation des opérat ions foncière rurale dans le c adre du PAMOFOR CI-AFOR-363545-CS-CQS-23 / RECRUTEMENT D'UN CABIN Component 4 – Program Co ET POUR LA REALISATION D Quality Based Sel Pending Impleme IDA / 61900 ordination, Monitoring and Post Open - National 181,489.00 0.00 2023-06-16 2023-07-07 2023-08-20 2023-09-17 2023-10-17 2023-11-16 2023-12-21 2024-12-20 E L'ETUDE DE LA FAISABILIT ection ntation Knowledge Management E DE L'ARCHITECTURE D'HE BERGEMENT DU SIFOR ET D E SDI CI-AFOR-363880-CS-QBS-23 Component 4 – Program Co / RECRUTEMENT DE CABINE Consultant Qualifi Pending Impleme IDA / 61900 ordination, Monitoring and Post Limited 106,000.00 0.00 2023-07-03 2023-07-17 2023-08-16 2023-09-20 2024-03-18 T POUR LES ETUDES PREPAR cation Selection ntation Knowledge Management ATOIRES AU FINANCEMENT ADDITIONNEL CI-AFOR-363885-CS-CQS-23 Component 4 – Program Co / RECRUTEMENT DE CABINE Consultant Qualifi Pending Impleme IDA / 61900 ordination, Monitoring and Post Limited 120,000.00 0.00 2023-06-20 2023-07-04 2023-08-03 2023-09-07 2024-03-05 T POUR L'ETUDE DE L'EVALU cation Selection ntation Knowledge Management ATION FINALE DU PAMOFOR CI-AFOR-363515-CS-CQS-23 Component 4 – Program Co / RECRUTEMENT D'UN CABIN Quality Based Sel Pending Impleme IDA / 61900 ordination, Monitoring and Post Open - National 5,444.00 0.00 2023-06-06 2023-06-27 2023-08-10 2023-09-07 2023-10-07 2023-11-06 2023-12-11 2024-12-10 ET POUR L'AUDIT DES COMP ection ntation Knowledge Management TES DU PAMOFOR INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Identifie Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amoun Draft Negotiated Con Description Component Review Type Method Process Status Terms of Reference d/Selected Consultan Signed Contract Contract Completion o. h unt (US$) t (US$) tract t Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CI-AFOR-89779-CS-INDV / R ecrutement d'un Spécialiste Component 1 – Strengtheni Individual Consult Pending Impleme IDA / 61900 Post Open 31,200.00 0.00 2019-01-15 2019-03-05 2019-03-26 2019-04-30 2020-04-29 en programmation des trava ng Rural Land Institutions ant Selection ntation ux et supervision des servic es déconcentrés CI-AFOR-89781-CS-INDV / R Component 1 – Strengtheni Individual Consult ecrutement d'un Spécialiste IDA / 61900 Post Open 31,200.00 0.00 Canceled 2019-01-15 2019-03-05 2019-03-26 2019-04-30 2020-04-29 ng Rural Land Institutions ant Selection en Communication interne e t externe CI-AFOR-89784-CS-INDV / R ecrutement d'un Spécialiste Component 1 – Strengtheni Individual Consult IDA / 61900 Post Open 31,200.00 0.00 Canceled 2019-01-21 2019-03-11 2019-04-01 2019-05-06 2020-05-05 en Vérification des projets d' ng Rural Land Institutions ant Selection actes administratifs CI-AFOR-89785-CS-INDV / R Component 1 – Strengtheni Individual Consult ecrutement d'un Spécialiste IDA / 61900 Post Open 31,200.00 0.00 Canceled 2019-01-31 2019-03-21 2019-04-11 2019-05-16 2020-05-15 ng Rural Land Institutions ant Selection en Système d'informations f oncières CI-AFOR-89797-CS-INDV / R ecrutement d'un Responsabl Component 1 – Strengtheni Individual Consult Pending Impleme IDA / 61900 Post Open 31,200.00 0.00 2019-01-21 2019-03-11 2019-04-01 2019-05-06 2020-05-05 e de la documentation et de ng Rural Land Institutions ant Selection ntation l'archivage à l'AFOR CI-AFOR-89799-CS-INDV / R ecrutement d'un Responsabl Component 1 – Strengtheni Individual Consult Pending Impleme IDA / 61900 Post Open 31,200.00 0.00 2019-01-28 2019-03-18 2019-04-08 2019-05-13 2020-05-12 e de l'information, des étude ng Rural Land Institutions ant Selection ntation s et de la politique foncière à l'AFOR CI-AFOR-89800-CS-INDV / R Component 1 – Strengtheni Individual Consult ecrutement d'un Responsabl IDA / 61900 Post Open 31,200.00 0.00 Canceled 2019-01-15 2019-03-05 2019-03-26 2019-04-30 2020-04-29 ng Rural Land Institutions ant Selection e informatique à l'AFOR CI-AFOR-89801-CS-INDV / R Component 1 – Strengtheni Individual Consult ecrutement d'un Responsabl IDA / 61900 Post Open 31,200.00 0.00 Canceled 2019-01-20 2019-03-10 2019-03-31 2019-05-05 2020-05-04 ng Rural Land Institutions ant Selection e Réseaux à l'AFOR CI-AFOR-89803-CS-INDV / R Component 1 – Strengtheni Individual Consult ecrutement d'un Chargé de l IDA / 61900 Post Open 31,200.00 1,744.09 Signed 2019-01-21 2019-09-27 2019-03-11 2020-05-07 2019-04-01 2020-05-29 2019-05-06 2020-06-11 2020-05-05 ng Rural Land Institutions ant Selection a formation à l'AFOR CI-AFOR-89805-CS-INDV / R Component 1 – Strengtheni Individual Consult ecrutement d'un Chargé des IDA / 61900 Post Open 31,200.00 0.00 Canceled 2019-01-21 2019-03-11 2019-04-01 2019-05-06 2020-05-05 ng Rural Land Institutions ant Selection moyens généraux à l'AFOR CI-AFOR-89806-CS-INDV / R Component 2 – Support Imp Individual Consult Under Implement ecrutement d'un consultant i IDA / 61900 lementation of the National Post Limited 125,000.00 0.00 2018-12-30 2019-01-04 2019-01-25 2019-03-01 2020-02-29 ant Selection ation ndividuel international exper Rural Land Tenure Security t en foncier rural Program CI-AFOR-89808-CS-INDV / R ecrutement d'un consultant i Component 3 – Training for Individual Consult IDA / 61900 Post Limited 120,000.00 0.00 Canceled 2018-12-24 2018-12-29 2019-01-19 2019-02-23 2020-02-23 ndividuel international pour l Land Tenure Professionals ant Selection e renforcement des capacité s à l'INPHB CI-AFOR-89809-CS-INDV / R Component 1 – Strengtheni Individual Consult Pending Impleme ecrutement d'un Spécialiste IDA / 61900 Post Limited 36,000.00 0.00 2018-12-23 2018-12-28 2019-01-18 2019-02-22 2020-02-22 ng Rural Land Institutions ant Selection ntation en environnement et sauveg arde sociale CI-AFOR-89810-CS-INDV / R Component 1 – Strengtheni Individual Consult Pending Impleme ecrutement du Chef Compta IDA / 61900 Post Open 31,200.00 0.00 2018-12-23 2019-02-10 2019-03-03 2019-04-07 2020-04-06 ng Rural Land Institutions ant Selection ntation ble de l'AFOR CI-AFOR-89844-CS-INDV / R ecrutement d'un Consultant Component 4 – Program Co Individual Consult individuel pour la réalisation IDA / 61900 ordination, Monitoring and Post Limited 15,000.00 0.00 Canceled 2019-01-15 2019-01-20 2019-02-10 2019-03-17 2019-09-13 ant Selection d'une étude sur la cartograp Knowledge Management hie du secteur privé du Fonc ier en Côte d'Ivoire Page 9 CI-AFOR-108560-CS-INDV / Recrutement d'un Consultan Component 4 – Program Co t Individuel pour la réalisatio Individual Consult IDA / 61900 ordination, Monitoring and Post Open 90,000.00 49,075.76 Signed 2019-04-15 2019-04-09 2019-06-03 2019-10-28 2019-06-24 2019-10-30 2019-07-29 2019-12-02 2020-01-25 n d'une étude de référence ant Selection Knowledge Management et de Mise en Place d'un Sys tème de Suivi Evaluation po ur le Projet CI-AFOR-108561-CS-CDS / R Component 4 – Program Co Individual Consult Under Implement ecrutement d'un Assistant e IDA / 61900 ordination, Monitoring and Post Limited 24,000.00 0.00 2019-04-15 2019-04-20 2019-05-11 2019-06-15 2019-12-12 ant Selection ation n Passation des Marchés Knowledge Management CI-AFOR-108562-CS-INDV / Recrutement d'un Consultan t Individuel en Ingénierie de Component 4 – Program Co la formation pour l'appui à l' Individual Consult IDA / 61900 ordination, Monitoring and Post Limited 40,000.00 17,759.97 Completed 2019-04-15 2019-04-12 2019-04-20 2019-08-02 2019-05-11 2019-08-16 2019-06-15 2019-08-24 2019-09-13 2019-11-29 atelier de « Renforcement d ant Selection Knowledge Management es ressources humaines pou r la conception et la mise à échelle des réformes foncièr es en Afrique francophone CI-AFOR-108565-CS-INDV / Recrutement d'un Consultan t individuel pour l'élaboratio Component 3 – Training for Individual Consult IDA / 61900 Post Limited 10,000.00 0.00 Canceled 2019-05-19 2019-05-24 2019-06-14 2019-07-19 2019-08-18 n des études techniques pou Land Tenure Professionals ant Selection r les travaux de réhabilitatio n d'un bâtiment de cours au sein de l'ESA CI-AFOR-89778-CS-INDV / R Component 1 – Strengtheni Individual Consult ecrutement du Spécialiste e IDA / 61900 Post Open 31,200.00 0.00 Canceled 2019-05-02 2019-06-20 2019-07-11 2019-08-15 2020-08-14 ng Rural Land Institutions ant Selection n Ressources Humaines pou r l'AFOR CI-AFOR-108566-CS-INDV / Component 4 – Program Co Recrutement d'un Responsa Individual Consult Under Implement IDA / 61900 ordination, Monitoring and Post Open 40,000.00 0.00 2019-04-01 2019-02-06 2019-05-20 2019-06-10 2019-07-15 2020-07-14 ble Suivi Evaluation pour l'A ant Selection ation Knowledge Management gence Foncière Rurale (AFO R) CI-AFOR-109050-CS-CDS / R ecrutement d'un Cabinet po Component 1 – Strengtheni ur une assistance technique IDA / 61900 Post Direct Selection Direct 40,000.00 0.00 Canceled 2019-07-24 2019-08-03 2019-10-07 2020-04-04 ng Rural Land Institutions pour le recrutement du Pers onnel de l'Agence Foncière Rurale (AFOR) CI-AFOR-109056-CS-INDV / Recrutement d'un Consultan Component 1 – Strengtheni Individual Consult t Individuel pour l'élaboratio IDA / 61900 Post Limited 20,000.00 0.00 Canceled 2019-07-24 2019-07-29 2019-08-19 2019-09-23 2019-11-07 ng Rural Land Institutions ant Selection n des devis pour les travaux de réhabilitation des antenn es déconcentrées de l'AFOR CI-AFOR-109058-CS-INDV / Recrutement d'un Consultan Component 2 – Support Imp t individuel pour l'élaboratio lementation of the National Individual Consult IDA / 61900 Post Limited 25,000.00 0.00 Canceled 2019-07-17 2019-07-22 2019-08-12 2019-09-16 2020-03-14 n des devis et le suivi et con Rural Land Tenure Security ant Selection trôle des Travaux de Réhabil Program itation d'un Amphithéâtre po ur le compte de l'ESA CI-AFOR-109059-CS-INDV / Recrutement d'un Consultan Component 1 – Strengtheni Individual Consult t pour l'élaboration des devi IDA / 61900 Post Limited 20,000.00 6,260.66 Signed 2019-07-17 2019-10-03 2019-07-22 2019-10-21 2019-08-12 2019-10-04 2019-09-16 2019-11-05 2020-03-14 ng Rural Land Institutions ant Selection s et le suivi des travaux de r éhabilitation des Secrétariat s Villageois CI-AFOR-122807-CS-CDS / C Component 2 – Support Imp onvention avec le BNETD po lementation of the National IDA / 61900 Post Direct Selection Direct 300.00 0.00 Canceled 2019-09-11 2019-09-16 2019-09-26 2019-09-29 ur le contrôle des Opération Rural Land Tenure Security s de DTV réalisés dans le ca Program dre du PAMOFOR CI-AFOR-122808-CS-INDV / Recrutement d'un Consulta Component 3 – Training for Individual Consult Pending Impleme nt individuel pour la Concept IDA / 61900 Post Limited 20,000.00 0.00 2019-08-06 2019-08-16 2019-09-15 2019-10-09 2019-12-08 Land Tenure Professionals ant Selection ntation ion de Modules de formation au Foncier rural pour les Ma gistrats CI-AFOR-122809-CS-INDV / Recrutement d'un Consultan t Individuel pour la concepti Component 3 – Training for Individual Consult IDA / 61900 Post Open 20,000.00 50,561.19 Signed 2019-09-04 2019-09-27 2019-10-23 2019-12-24 2019-11-13 2020-01-08 2019-12-18 2020-03-04 2020-06-15 on d'un film didactique et d' Land Tenure Professionals ant Selection un Prêt à diffuser (PAD) sur l 'approche 4 en 1 dans le cad re du PAMOFOR CI-AFOR-122819-CS-INDV / Component 2 – Support Imp Recrutement d'un Consultan lementation of the National Individual Consult t Individuel pour la rédaction IDA / 61900 Post Open 20,000.00 0.00 Canceled 2019-09-04 2019-10-23 2019-11-13 2019-12-18 2020-06-15 Rural Land Tenure Security ant Selection d'un Mécanisme de Gestion Program des Plaintes dans le cadre d u PAMOFOR CI-AFOR-122832-CS-INDV / Component 4 – Program Co Individual Consult Recrutement du Spécialiste IDA / 61900 ordination, Monitoring and Post Open 32,000.00 2,267.32 Signed 2019-11-29 2019-10-14 2020-01-18 2020-05-02 2020-01-28 2020-06-08 2020-03-03 2020-06-17 2021-03-03 ant Selection en ressources humaines pou Knowledge Management r l'AFOR CI-AFOR-122854-CS-INDV / Component 4 – Program Co Recrutement d'un Responsa Individual Consult IDA / 61900 ordination, Monitoring and Post Open 20,000.00 866.75 Signed 2019-07-31 2019-08-28 2019-10-03 2019-09-03 2019-10-13 2019-12-19 2019-11-01 2019-12-25 2020-10-31 ble des Opérations Techniqu ant Selection Knowledge Management es pour la Région de la ME CI-AFOR-122856-CS-INDV / Recrutement d'un Responsa Component 1 – Strengtheni Individual Consult IDA / 61900 Post Open 20,000.00 887.10 Signed 2019-08-13 2019-08-28 2019-09-29 2019-12-19 2019-10-09 2019-12-19 2019-11-02 2019-12-17 2020-04-30 ble des Opérations Techniqu ng Rural Land Institutions ant Selection e pour la Région de BAFING CI-AFOR-122859-CS-INDV / Recrutement d'un Responsa Component 1 – Strengtheni Individual Consult IDA / 61900 Post Open 20,000.00 1,167.24 Signed 2019-07-31 2019-08-08 2019-09-01 2019-10-24 2019-09-06 2019-12-09 2019-09-21 2019-12-17 2020-09-20 ble des Opérations Techniqu ng Rural Land Institutions ant Selection es pour la Région de l'AGNE BY-TIASSA CI-AFOR-122861-CS-INDV / Recrutement d'un Responsa Component 1 – Strengtheni Individual Consult Under Implement IDA / 61900 Post Open 20,000.00 0.00 2019-08-14 2019-08-28 2019-09-03 2019-10-24 2019-09-13 2019-09-28 2020-09-27 ble des Opérations Techniqu ng Rural Land Institutions ant Selection ation es pour la Région du N'ZI CI-AFOR-122864-CS-INDV / Recrutement d'un Responsa Component 1 – Strengtheni Individual Consult Under Implement IDA / 61900 Post Open 20,000.00 0.00 2019-08-13 2019-08-28 2019-09-02 2019-09-12 2019-10-01 2020-09-30 ble des Opérations Techniqu ng Rural Land Institutions ant Selection ation es pour la région du SUD CO MOE CI-AFOR-122868-CS-INDV / Recrutement d'un Responsa Component 1 – Strengtheni Individual Consult Under Implement IDA / 61900 Post Open 20,000.00 0.00 2019-07-30 2019-08-28 2019-08-19 2019-08-29 2019-09-17 2020-09-16 ble des Opérations Techniqu ng Rural Land Institutions ant Selection ation es pour la région de l'INDEN NIE DJUABLIN CI-AFOR-141798-CS-CQS / R Component 4 – Program Co Individual Consult ecrurement d'un assistant e IDA / 61900 ordination, Monitoring and Post Limited 24,000.00 21,465.12 Signed 2020-02-03 2019-07-01 2020-02-08 2019-07-19 2020-02-29 2019-08-29 2020-04-04 2019-09-24 2021-04-04 ant Selection n Passation des Marchés po Knowledge Management ur l'AFOR CI-AFOR-141816-CS-CDS / R Component 2 – Support Imp ecrutement d'une firme pour lementation of the National la mise en place d'un mécan IDA / 61900 Post Direct Selection Direct 30,000.00 0.00 Canceled 2019-12-02 2019-12-12 2020-01-16 2020-03-16 Rural Land Tenure Security isme de gestion des plaintes Program dans le cadre du PAMOFOR CI-AFOR-142106-CS-INDV / Component 4 – Program Co Individual Consult Recrutement d'un Assistant IDA / 61900 ordination, Monitoring and Post Limited 24,000.00 19,829.64 Signed 2019-12-13 2019-11-13 2019-12-18 2019-12-23 2020-01-08 2020-01-08 2020-02-12 2020-01-28 2021-02-11 ant Selection Suivi Evaluation pour l'AFOR Knowledge Management Page 10 CI-AFOR-142200-CS-INDV / Recrutement d'un Consultan Component 4 – Program Co Individual Consult t pour la mise en place d'un IDA / 61900 ordination, Monitoring and Post Limited 30,000.00 0.00 Canceled 2019-11-08 2019-11-13 2019-12-04 2020-01-08 2020-07-06 ant Selection système d'archivage électro Knowledge Management nique des Documents de Pas sation des Marchés CI-AFOR-122820-CS-CDS / C onvention avec le LBTP pour Component 4 – Program Co Pending Impleme la réalisation d'une étude su IDA / 61900 ordination, Monitoring and Post Direct Selection Direct 15,000.00 0.00 2019-07-30 2019-08-04 2019-08-09 2022-01-25 ntation r la formulation du béton po Knowledge Management ur la réduction des tailles de s bornes topographiques CI-AFOR-153270-CS-INDV / Component 4 – Program Co Recrutement d'un Assistant Individual Consult Pending Impleme IDA / 61900 ordination, Monitoring and Post Direct 90,000.00 0.00 2020-02-15 2020-02-25 2020-03-17 2020-04-21 2021-04-21 Technique International aupr ant Selection ntation Knowledge Management ès de l'AFOR (Renouvelleme nt Contrat Pascal Thinon) CI-AFOR-153275-CS-CDS / C Component 2 – Support Imp onvention avec le BNETD po lementation of the National Pending Impleme IDA / 61900 Post Direct Selection Direct 70,000.00 0.00 2020-02-20 2020-03-01 2020-05-05 2020-11-01 ur le Contrôle des opération Rural Land Tenure Security ntation s de DTV dans le cadre du P Program AMOFOR CI-AFOR-153277-CS-CDS / C Component 2 – Support Imp onvention avec le BNETD po lementation of the National IDA / 61900 Post Direct Selection Direct 50,000.00 36,875.87 Completed 2020-02-03 2020-04-06 2020-02-13 2020-05-27 2020-04-18 2020-06-30 2020-07-17 2020-09-19 ur la réalisation de l'Etat des Rural Land Tenure Security lieux du RGIR et du RGIO (zo Program ne PAMOFOR) CI-AFOR-153279-CS-CDS / C Component 2 – Support Imp onvention avec le BNETD po lementation of the National Pending Impleme IDA / 61900 Post Direct Selection Direct 50,000.00 0.00 2020-02-06 2020-02-16 2020-04-21 2020-10-18 ur la Réhabilitation/observati Rural Land Tenure Security ntation ons de bornes (RGIR+RGIO) Program suite à l’Etat des lieux CI-AFOR-153281-CS-INDV / Recrutement d'un Consultan Component 3 – Training for Individual Consult Pending Impleme t pour une étude de faisabilit IDA / 61900 Post Open 40,000.00 0.00 2020-04-02 2020-05-21 2020-06-11 2020-07-16 2021-01-12 Land Tenure Professionals ant Selection ntation é sur la formation en ligne d ans le secteur du Foncier Ru ral CI-AFOR-153289-CS-INDV / Recrutement d'un Assistant Component 3 – Training for Individual Consult Technique International aupr IDA / 61900 Post Direct 80,000.00 0.00 Canceled 2020-02-12 2020-02-22 2020-03-14 2020-04-18 2020-10-15 Land Tenure Professionals ant Selection ès de l'Université Allassane Ouattara pour la formation a u Foncier Rural CI-AFOR-153290-CS-INDV / Recrutement d'un Expert en Component 3 – Training for Individual Consult Formation pour aadministrat IDA / 61900 Post Direct 50,000.00 0.00 Canceled 2020-02-12 2020-02-22 2020-03-14 2020-04-18 2020-10-15 Land Tenure Professionals ant Selection ion de cours sur le Foncier à l'Université Allassane Ouatta ra de BOUAKE CI-AFOR-153407-CS-INDV / Recrutement d'un Consultan Component 2 – Support Imp t individuel en Appui à l'AFO lementation of the National Individual Consult IDA / 61900 Post Limited 60,000.00 0.00 Canceled 2020-03-02 2020-03-07 2020-03-28 2020-04-21 2021-10-13 R pour le suivi de la mise en Rural Land Tenure Security ant Selection oeuvre des opérations integr Program ees de la phase pilote de la Composante 2 CI-AFOR-153408-CS-INDV / Recrutement d'un Assistant Component 3 – Training for Individual Consult IDA / 61900 Post Open 90,000.00 84,462.46 Signed 2020-02-20 2020-03-09 2020-04-09 2020-07-03 2020-04-30 2020-05-11 2020-05-19 2020-09-08 2021-10-01 Technique pour l'Appui à la Land Tenure Professionals ant Selection Composante 3 du PAMOFOR CI-AFOR-153409-CS-INDV / Component 4 – Program Co Recrutement d'un Chef de S Individual Consult IDA / 61900 ordination, Monitoring and Post Limited 38,000.00 1,750.01 Signed 2020-02-06 2020-03-18 2020-02-11 2020-04-06 2020-03-03 2020-07-17 2020-03-27 2020-07-21 2021-03-27 ervice de Vérification des Pr ant Selection Knowledge Management ojets d'Actes Administratifs CI-AFOR-159975-CS-CDS / R Component 4 – Program Co ecrutement d'un Chef de Ser IDA / 61900 ordination, Monitoring and Post Direct Selection Direct 29,000.00 0.00 Canceled 2020-03-16 2020-03-26 2020-05-14 2021-05-14 vice pour la vérification et le Knowledge Management contrôle des Actes Administr atifs CI-AFOR-159978-CS-INDV / Recrutement d'un Expert en Component 1 – Strengtheni Individual Consult Bâtiment pour le suivi et Co IDA / 61900 Post Limited 20,000.00 0.00 Canceled 2020-03-10 2020-03-15 2020-04-05 2020-05-10 2020-09-07 ng Rural Land Institutions ant Selection ntrôle des travaux de constr uction de secrétariats village ois CI-AFOR-159986-CS-INDV / Component 2 – Support Imp Individual Consult Recrutement d'un Spécialist IDA / 61900 lementation of the National Post Limited 38,000.00 67,635.16 Signed 2020-03-05 2020-03-09 2020-03-10 2020-04-08 2020-03-31 2020-05-06 2020-05-05 2020-05-13 2021-05-05 ant Selection e Genre pour l'Agence Fonci Rural Land Tenure Security ère Rurale (AFOR) Program CI-AFOR-159989-CS-INDV / Component 4 – Program Co Individual Consult Under Implement Recrutement d'un Spécialist IDA / 61900 ordination, Monitoring and Post Limited 30,000.00 0.00 2020-03-03 2020-03-23 2020-03-08 2020-04-10 2020-03-29 2020-05-03 2021-05-03 ant Selection ation e environnemental pour l'AF Knowledge Management OR CI-AFOR-164126-CS-INDV / Recrutement d’un consultan Component 1 – Strengtheni Individual Consult Pending Impleme t pour la réalisation d’une ét IDA / 61900 Post Open 40,000.00 0.00 2020-03-26 2020-05-14 2020-06-04 2020-07-09 2020-10-07 ng Rural Land Institutions ant Selection ntation ude sur le plan de pérennisa tion budgétaire de l’Agence Foncière Rurale (AFOR), CI-AFOR-164129-CS-INDV / Recrutement d’un Consultan Component 1 – Strengtheni Individual Consult t spécialiste en Géodésie en IDA / 61900 Post Open 70,000.00 94,199.37 Signed 2020-03-24 2020-03-26 2020-05-12 2020-07-09 2020-06-02 2020-07-09 2020-07-07 2020-07-18 2021-07-07 ng Rural Land Institutions ant Selection appui au BNETD CIGN pour l’ amélioration du Réseau Géo désique Ivoirien CI-AFOR-165264-CS-INDV / Recrutement de dix-neuf (19 ) Chargé départemental des Component 1 – Strengtheni Individual Consult Under Implement IDA / 61900 Post Open 150,000.00 0.00 2020-03-25 2020-04-01 2020-05-13 2020-04-08 2020-06-03 2020-07-08 2021-01-04 Opérations Techniques et de ng Rural Land Institutions ant Selection ation l’Information Foncière de l’A gence Foncière Rurale (COTI F) CI-AFOR-153274-CS-INDV / RECRUTEMENT D’UN CONSU Component 2 – Support Imp LTANT INDIVIDUEL SPECIALI lementation of the National Individual Consult IDA / 61900 Post Limited 15,000.00 0.00 Canceled 2020-02-03 2020-02-08 2020-02-29 2020-04-04 2020-10-01 STE EN GEODESIE EN APPUI Rural Land Tenure Security ant Selection AU BNETD-CIGN POUR L’AM Program ELIORATION DU RESEAU GE ODESIQUE IVOIRIEN CI-AFOR-165403-CS-INDV / Recrutement d'un Consultan Component 1 – Strengtheni Individual Consult Under Implement t Individuel pour le suivi et l IDA / 61900 Post Limited 20,000.00 0.00 2020-03-31 2020-10-27 2020-04-05 2020-04-26 2020-05-31 2020-07-30 ng Rural Land Institutions ant Selection ation e contrôle des travaux de co nstruction de secrétariats vil lageois CI-AFOR-153267-CS-INDV / Recrutement d'un Consultan t idividuel pour les études te Component 3 – Training for Individual Consult chniques et le suivi et contrô IDA / 61900 Post Limited 20,000.00 42,942.96 Signed 2020-02-05 2020-05-18 2020-02-10 2020-05-14 2020-02-11 2020-05-14 2020-03-06 2020-08-06 2020-06-04 Land Tenure Professionals ant Selection le des travaux de constructi on de salles de cours pour la formation au Foncier au sein de l'Université A. Ouatarra CI-AFOR-153407-CS-INDV-2 / Recrutement d’un expert in Component 1 – Strengtheni Individual Consult Under Implement ternational Spécialiste en sé IDA / 61900 Post Limited 70,000.00 0.00 2020-08-20 2020-08-14 2020-08-25 2020-09-15 2020-10-09 2021-10-09 ng Rural Land Institutions ant Selection ation curisation foncière rurale po ur le renforcement des capa cités de l'AFOR Page 11 CI-AFOR-187439-CS-INDV / Recrutement d'un Assistant Technique auprès de la Dire Component 1 – Strengtheni Individual Consult IDA / 61900 Post Open 80,000.00 24,948.25 Signed 2020-09-04 2020-08-14 2020-10-08 2020-12-15 2020-10-29 2020-12-16 2020-11-29 2021-01-13 2021-11-24 ction du Foncier Rural (DFR) ng Rural Land Institutions ant Selection pour un appui dans la mise en œuvre de la stratégie de politique foncière rurale CI-AFOR-187464-CS-INDV / Recrutement d'un Consultan Component 4 – Program Co Individual Consult t individuel pour la réalisatio IDA / 61900 ordination, Monitoring and Post Direct 44,000.00 0.00 Canceled 2020-08-13 2020-08-23 2020-08-28 2020-09-16 2020-10-26 ant Selection n d'une Etude pour la mise e Knowledge Management n place d'un système de Sui vi Evaluation pour l'AFOR CI-AFOR-187511-CS-INDV / Component 4 – Program Co Recrutement d'un Assistant Individual Consult Under Implement IDA / 61900 ordination, Monitoring and Post Limited 30,000.00 0.00 2020-08-27 2020-09-01 2020-09-11 2020-09-25 2021-09-20 Technique en Appui à la Dire ant Selection ation Knowledge Management ction Générale de l'AFOR CI-AFOR-184781-CS-CDS / Component 2 – Support Imp Mise en œuvre et support de lementation of the National données pour les interventio IDA / 61900 Post Direct Selection Direct 128,000.00 246,441.00 Signed 2020-08-24 2020-07-16 2020-08-28 2020-07-22 2020-09-12 2020-09-05 2020-12-11 Rural Land Tenure Security ns en matière de droits de p Program ropriété des femmes en côte d'ivoire CI-AFOR-184780-CS-CDS / E Component 2 – Support Imp tude de base pour l’évaluati lementation of the National on d’impact sur la certificati IDA / 61900 Post Direct Selection Direct 250,000.00 0.00 Under Review 2020-08-21 2020-07-16 2020-08-31 2020-11-04 2021-05-03 Rural Land Tenure Security on des terres et les droits de Program propriété des femmes en côt e d’ivoire CI-AFOR-164122-CS-INDV / Recrutement de Chef de ser Component 1 – Strengtheni Individual Consult vice en charge de la sécuris IDA / 61900 Post Open 36,000.00 0.00 Canceled 2020-03-25 2020-03-26 2020-05-13 2020-06-03 2020-07-08 2021-07-03 ng Rural Land Institutions ant Selection ation du patrimoine foncier r ural de l’Etat et de l’instructi on à l’immatriculation CI-AFOR-217527-CS-INDV-2 1 / Recrutement d'un consul tant pour la fourniture et l'in Component 1 – Strengtheni Individual Consult Pending Impleme stallation d'un logiciel pour s IDA / 61900 Post Open 165,000.00 0.00 2021-08-12 2021-09-30 2021-10-21 2021-11-25 2022-05-24 ng Rural Land Institutions ant Selection ntation outenir le développement d u SIFOR( Logiciel de cartogr aphie, AGL, SGBDR, OS, Logi ciel de sécurité...) CI-AFOR-217532-CS-INDV-2 1 / RECRUTEMENT D'UN CO Component 1 – Strengtheni Individual Consult Pending Impleme NSULTANT POUR LA MISE EN IDA / 61900 Post Open 63,520.00 0.00 2021-02-26 2021-04-16 2021-05-07 2021-06-11 2021-12-08 ng Rural Land Institutions ant Selection ntation PLACE D'UN SYSTEME DE GE STION ELECTRONIQUE DES DOCUMENTS ( GED) CI-AFOR-217558-CS-INDV-2 1 / RECRUTEMENT D'UN CO NSULTANT POUR LE SUIVI ET Component 1 – Strengtheni Individual Consult Pending Impleme IDA / 61900 Post Open 94,400.00 0.00 2021-09-01 2021-10-20 2021-11-10 2021-12-15 2022-06-13 LE CONTRÔLE DES TRAVAUX ng Rural Land Institutions ant Selection ntation DE REHABILITATION DES 13 BATIMENTS PUBLICS A USAG E DE BUREAU DES COTIF CI-AFOR-217564-CS-INDV-2 1 / RECRUTEMENT D'UNE ST RUCTURE POUR LA CONFEC Component 1 – Strengtheni Individual Consult Pending Impleme IDA / 61900 Post Open 48,000.00 0.00 2021-03-31 2021-05-19 2021-06-09 2021-07-14 2022-01-10 TION DE SECURISATION "AC ng Rural Land Institutions ant Selection ntation CES BADGE" AFOR (Accès e ntrée principale, salle de do nnées, bureaux etc) CI-AFOR-217567-CS-INDV-2 1 / RECRUTEMENT D'UN CO Component 1 – Strengtheni Individual Consult Pending Impleme NSULTANT INDIVIDUEL POU IDA / 61900 Post Open 42,110.00 0.00 2021-10-01 2021-11-19 2021-12-10 2022-01-14 2022-07-13 ng Rural Land Institutions ant Selection ntation R LE CONTRÔLE ET LE SUIVI DES TRAVAUX DE 58 BUREA U FONCIER RURAL (BFR) CI-AFOR-217569-CS-INDV-2 1 / RECRUEMENT D'UN CON Component 1 – Strengtheni Individual Consult Pending Impleme SULTANT POUR L'ELABORATI IDA / 61900 Post Open 80,000.00 0.00 2021-09-08 2021-10-27 2021-11-17 2021-12-22 2022-06-20 ng Rural Land Institutions ant Selection ntation ON DES CURRICULA VITAE D ES STRUTURES ESA, INFPA, UAO CI-AFOR-217606-CS-INDV-2 1 / RECRUTEMENT D'ASSIST Component 1 – Strengtheni Individual Consult Pending Impleme IDA / 61900 Post Open 49,360.00 0.00 2021-11-18 2022-01-06 2022-01-27 2022-03-03 2022-08-30 ANT TECHNIQUE INTERNATI ng Rural Land Institutions ant Selection ntation ONALE AUPRES DU CIGN/BE NETD CI-AFOR-217613-CS-INDV-2 1 / RECRUTEMENT ASSISTAN Component 1 – Strengtheni Individual Consult Pending Impleme IDA / 61900 Post Open 43,560.00 0.00 2021-09-23 2021-11-11 2021-12-02 2022-01-06 2022-07-05 T TECHNIQUE NATIONAL AU ng Rural Land Institutions ant Selection ntation PRES DE LA DG ET DE LA DO T CI-AFOR-217617-CS-INDV-2 1 / RECRUTEMENT D'ASSIST Component 1 – Strengtheni Individual Consult Pending Impleme ANT TECHNIQUE INTERNATI IDA / 61900 Post Open 83,480.00 0.00 2021-11-18 2022-01-06 2022-01-27 2022-03-03 2022-08-30 ng Rural Land Institutions ant Selection ntation ONELE AUPRES DE LA DIRCO M (APPUI A LA COMPOSANTE FORMATION) CI-AFOR-217621-CS-CDS-21 / RECRUTEMENT COURT TER Component 1 – Strengtheni Individual Consult Under Implement IDA / 61900 Post Open 54,400.00 0.00 2021-06-23 2021-10-20 2021-08-11 2021-09-01 2021-10-06 2022-04-04 ME D'UN CONSULTANT POU ng Rural Land Institutions ant Selection ation R L'AUTONOMISATION DE L' AFOR CI-AFOR-217631-CS-INDV-2 Component 1 – Strengtheni Individual Consult Under Implement 1 / RECRUTEMENT D'UN EXP IDA / 61900 Post Open 12,000.00 0.00 2021-09-23 2021-03-02 2021-11-11 2021-12-02 2022-01-06 2022-07-05 ng Rural Land Institutions ant Selection ation ERT GEODESIQUE CI-AFOR-217634-CS-INDV-2 1 / RECRUTEMENT D'UN CO Component 3 – Training for Individual Consult Under Implement IDA / 61900 Post Open 39,930.00 0.00 2021-09-27 2021-06-25 2021-11-15 2021-12-06 2022-01-10 2022-07-09 NSULTANT POUR L'ETUDE D Land Tenure Professionals ant Selection ation E FAISABILITE DE FORMATIO N EN LIGNE CI-AFOR-217642-CS-INDV-2 1 / RECRUTEMENT D'UN CO Component 3 – Training for Individual Consult Pending Impleme NSULTANT POUR L'EDITION IDA / 61900 Post Open 45,380.00 0.00 2021-11-28 2022-01-16 2022-02-06 2022-03-13 2022-09-09 Land Tenure Professionals ant Selection ntation ET LA DISTRIBUTION D'UN M AGAZINE TRIMESTRIEL DE L' AFOR CI-AFOR-217650-CS-INDV-2 1 / SELECTION D'UN CONSUL Component 3 – Training for Individual Consult Pending Impleme TANT POUR LA MISE EN OEU IDA / 61900 Post Open 54,500.00 0.00 2021-09-24 2021-11-12 2021-12-03 2022-01-07 2022-07-06 Land Tenure Professionals ant Selection ntation VRE DU PLAN STRATEGIQUE DE COMMUNICATION SUR LE S DROITS FONCIERS CI-AFOR-217654-CS-INDV-2 1 / RECRUTEMENT D'UN ASS Component 1 – Strengtheni Individual Consult Under Implement IDA / 61900 Post Open 94,290.00 0.00 2021-10-15 2021-04-19 2021-12-03 2021-12-24 2022-01-28 2022-07-27 ISTANT TECHNIQUE INTERNA ng Rural Land Institutions ant Selection ation TIONAL POUR DIRECTION TE CHNIQUE DE L'AFOR CI-AFOR-217657-CS-INDV / Component 1 – Strengtheni Pending Impleme CONTRAT AVEC COMAFRIQU IDA / 61900 Post Direct Selection Direct 90,000.00 0.00 2021-11-23 2021-12-03 2022-02-06 2022-08-05 ng Rural Land Institutions ntation E POUR L'ACQUISITION DU L OGICIEL (ARCGIS) CI-AFOR-218024-CS-CDS-21 Component 4 – Program Co / Convention avec la Télévisi Pending Impleme IDA / 61900 ordination, Monitoring and Post Direct Selection Direct 7,260.00 0.00 2021-04-15 2021-04-25 2021-06-29 2021-12-26 on Ivoirienne (RTI1) pour la ntation Knowledge Management diffusion de PAD, spots et co mmuniqués de l'AFOR Page 12 CI-AFOR-218277-CS-INDV-2 1 / Recrutement d'assistant Component 1 – Strengtheni Individual Consult Pending Impleme IDA / 61900 Post Open 54,450.00 0.00 2021-03-10 2021-04-28 2021-05-19 2021-06-23 2021-12-20 technique en appui à la DFR ng Rural Land Institutions ant Selection ntation pour conduire la reforme juri dique et réglementaire CI-AFOR-217571-CS-INDV-2 Component 4 – Program Co Individual Consult Pending Impleme 1 / RECRUTEMENT D'UNE FIR IDA / 61900 ordination, Monitoring and Post Open 108,890.00 0.00 2021-06-07 2021-07-26 2021-08-16 2021-09-20 2022-03-19 ant Selection ntation ME POUR L'EVALUATION DU Knowledge Management PAMOFOR CI-AFOR-220615-CS-INDV-2 Component 1 – Strengtheni Individual Consult 1 / Recrutement d'un Spécia IDA / 61900 Prior Open 100.00 0.00 Under Review 2021-02-22 2021-03-01 2021-04-12 2021-06-08 2021-05-03 2021-06-07 2021-12-04 ng Rural Land Institutions ant Selection liste en Passation des March és pour l'AFOR CI-AFOR-220631-CS-INDV-2 Component 1 – Strengtheni Individual Consult 1 / Recrutement d'un Spécia IDA / 61900 Post Open 2,540.00 2,120.45 Signed 2021-02-22 2021-02-24 2021-04-12 2021-05-11 2021-05-03 2021-05-28 2021-06-07 2021-07-02 2021-12-04 ng Rural Land Institutions ant Selection liste Sauvegarde Environne mentale CI-AFOR-220640-CS-INDV-2 Component 1 – Strengtheni Individual Consult Under Implement IDA / 61900 Post Open 2,540.00 0.00 2021-03-02 2021-02-24 2021-04-20 2021-05-11 2021-06-15 2021-12-12 1 / Recrutement d'un Spécia ng Rural Land Institutions ant Selection ation liste Genre CI-AFOR-225511-CS-INDV-K K-21 / RECRUTEMENT D'UN Component 1 – Strengtheni Individual Consult Pending Impleme IDA / 61900 Post Open 26,000.00 0.00 2021-04-14 2021-06-02 2021-06-23 2021-07-28 2022-01-24 RESPONSABLE DE LA DOCU ng Rural Land Institutions ant Selection ntation MENTATION ET DE L'ARCHIV AGE A L'AFOR CI-AFOR-225513-CS-INDV-K Component 1 – Strengtheni Individual Consult Pending Impleme K-21 / RECRUTEMENT DE SIX IDA / 61900 Post Open 30,000.00 0.00 2021-05-13 2021-07-01 2021-07-22 2021-08-26 2022-02-22 ng Rural Land Institutions ant Selection ntation (06) CHAUFFEURS DES ROT CI-AFOR-225514-CS-INDV-K Component 1 – Strengtheni Individual Consult Pending Impleme K-21 / RECRUTEMENT DE SIX IDA / V1170 Post Open 46,000.00 0.00 2021-06-24 2021-08-12 2021-09-02 2021-10-07 2022-04-05 ng Rural Land Institutions ant Selection ntation (06) ASSISTANTS DE ROT CI-AFOR-225517-CS-INDV-B V-21 / RECRUTEMENT D'UN/ Component 1 – Strengtheni Individual Consult Pending Impleme IDA / V1170 Post Open 22,000.00 0.00 2021-07-13 2021-08-31 2021-09-21 2021-10-26 2022-04-24 E ASSISTANT/E AU CHEF DE ng Rural Land Institutions ant Selection ntation SERVICE COMPTABILITE ET F INANCE CI-AFOR-225518-CS-INDV-B V-21 / RECRUTEMENT D'UNE FIRME POUR LA REALISATIO Component 1 – Strengtheni Individual Consult Pending Impleme IDA / 61900 Post Open 50,000.00 0.00 2021-05-20 2021-07-08 2021-07-29 2021-09-02 2022-03-01 N D'UN SYSTEME D'ARCHIVA ng Rural Land Institutions ant Selection ntation GE ELECTRONIQUE DE PASS ATION DE PASSATION DES M ARCHES POUR L'AFOR CI-AFOR-225653-CS-INDV-K K-21 / RECRUTEMENT D'EXP Component 3 – Training for Individual Consult Under Implement IDA / 61900 Post Open 29,000.00 0.00 2021-08-13 2021-05-14 2021-10-01 2021-10-22 2021-11-26 2022-05-25 ERT FORMATEURS SPECIALIS Land Tenure Professionals ant Selection ation TES NON FONCTIONNAIRES CI-AFOR-225658-CS-INDV-K K-21 / RECRUTEMENT D'UN Component 3 – Training for Individual Consult Pending Impleme IDA / 61900 Post Open 40,000.00 0.00 2021-09-24 2021-11-12 2021-12-03 2022-01-07 2022-07-06 CONSULTANT POUR L'ETUDE Land Tenure Professionals ant Selection ntation DE FAISABILITE DE FORMATI ON EN LIGNE CI-AFOR-225660-CS-INDV-K K-21 / RECRUTEMENT D'UN Component 4 – Program Co Individual Consult PRESTATAIRE POUR LA PRO IDA / 61900 ordination, Monitoring and Post Open 25,000.00 0.00 Under Review 2021-08-12 2021-06-01 2021-09-30 2021-10-21 2021-11-25 2022-05-24 ant Selection DUCTION DES OUTILS DU M Knowledge Management ECANISME DE GESTION DES PLAINTES. CI-AFOR-226056-CS-INDV-2 1 / Recrutement d'un Spécia Component 1 – Strengtheni Individual Consult Under Implement IDA / 61900 Prior Open 43,560.00 0.00 2021-03-26 2021-03-31 2021-05-14 2021-06-04 2021-07-09 2022-01-05 liste en Passation des March ng Rural Land Institutions ant Selection ation és pour l'Agence Foncière R urale (AFOR) CI-AFOR-226258-CS-INDV-2 1 / Recrutement d'un Expert Component 1 – Strengtheni Individual Consult Under Implement IDA / 61900 Post Open 1,900.00 0.00 2021-04-12 2021-04-02 2021-05-31 2021-06-21 2021-07-26 2022-01-22 international spécialiste en s ng Rural Land Institutions ant Selection ation écurisation foncière rurale CI-AFOR-226260-CS-INDV-2 1 / Recrutement d'un consul Component 1 – Strengtheni Individual Consult Pending Impleme IDA / 61900 Post Open 54,000.00 0.00 2021-04-12 2021-05-31 2021-06-21 2021-07-26 2022-01-22 tant à court terme pour l'aut ng Rural Land Institutions ant Selection ntation onomisation de l'AFOR CI-AFOR-226464-CS-CDS-21 Component 4 – Program Co / Contrat avec le Cabinet SDI Under Implement IDA / 61900 ordination, Monitoring and Post Direct Selection Direct 52,813.00 0.00 2021-03-31 2021-04-01 2021-04-10 2021-06-14 2021-12-11 pour la mise en place du sys ation Knowledge Management tème de suivi-évaluation CI-AFOR-226059-CS-QBS-21 Component 4 – Program Co / Contrat avec le Cabinet SDI Under Implement IDA / 61900 ordination, Monitoring and Post Direct Selection Direct 109,000.00 0.00 2021-04-06 2021-04-06 2021-04-16 2021-06-20 2021-12-17 pour l'évaluation à mi-parco ation Knowledge Management urs du PAMOFOR CI-AFOR-242703-CS-INDV-2 1 / Recrutement d'un assista Component 1 – Strengtheni Individual Consult Pending Impleme IDA / 61900 Post Limited 16,334.00 0.00 2021-07-23 2021-07-28 2021-08-18 2021-09-22 2022-03-21 nt national , Spécialiste du p ng Rural Land Institutions ant Selection ntation atrimoine foncier rural CI-AFOR-242714-CS-INDV-2 1 / Recrutement d'un consul Component 1 – Strengtheni Individual Consult Pending Impleme IDA / 61900 Post Open 171,506.00 0.00 2021-07-26 2021-09-13 2021-10-04 2021-11-08 2022-05-07 tant pour la formation contin ng Rural Land Institutions ant Selection ntation ue des agents de l'AFOR. CI-AFOR-279323-CS-INDV-K K-22 / Recrutement d'un cab Component 1 – Strengtheni Individual Consult inet pour la réalisation de l'é IDA / 61900 Post Open 90,745.00 0.00 Under Review 2022-05-13 2022-11-09 2022-07-01 2022-07-22 2022-08-26 2023-02-22 ng Rural Land Institutions ant Selection tude de faisabilité de l'archit ecture d'hébergement du SI FOR et SDI CI-AFOR-281426-CS-INDV-K Component 2 – Support Imp K-22 / Recrutement d'un cab lementation of the National Individual Consult Pending Impleme IDA / 61900 Post Open 120,000.00 0.00 2022-03-27 2022-05-15 2022-06-05 2022-07-10 2023-01-06 inet pour l'étude de l'évaluat Rural Land Tenure Security ant Selection ntation ion finale du PAMOFOR Program CI-AFOR-281432-CS-INDV-K Component 4 – Program Co Individual Consult Pending Impleme K-22 / Recrutement d' un ca IDA / 61900 ordination, Monitoring and Post Open 12,068.00 0.00 2022-06-04 2022-07-23 2022-08-13 2022-09-17 2023-03-16 ant Selection ntation binet pour l'audit des compt Knowledge Management es du PAMOFOR CI-AFOR-284283-CS-INDV-K Component 1 – Strengtheni Individual Consult Pending Impleme K-22 / Recrutement d'un ATI IDA / 61900 Post Open 54,500.00 0.00 2022-03-30 2022-05-18 2022-06-08 2022-07-13 2023-01-09 ng Rural Land Institutions ant Selection ntation auprès de la DOT CI-AFOR-284292-CS-INDV-K Component 4 – Program Co Individual Consult Pending Impleme K-22 / Recrutement d'un cab IDA / 61900 ordination, Monitoring and Post Open 12,068.00 0.00 2022-06-06 2022-07-25 2022-08-15 2022-09-19 2023-03-18 ant Selection ntation inet d'audit des comptes du Knowledge Management PAMOFOR CI-AFOR-293847-CS-CDS / R ecrutement du Groupement Component 2 – Support Imp GEOFIT EXPERT-CETIF-CABIN lementation of the National Under Implement ET KOUAMELAN pour la mise IDA / 61900 Prior Direct Selection Direct 3,988,345.00 0.00 2022-05-06 2022-05-16 2022-07-20 2023-01-16 Rural Land Tenure Security ation en œuvre des opérations de Program sécurisation foncière dans le s regions de l'Agnéby Tiassa et de la Mé. Page 13 CI-AFOR-293814-CS-CDS / R ecrutement du Groupement CGEDS-ETAFAT-TERRABO IN Component 2 – Support Imp GENIEURS CONSEILS pour la lementation of the National Under Implement IDA / 61900 Prior Direct Selection Direct 5,267,183.00 0.00 2022-05-10 2022-06-28 2022-05-10 2022-08-19 2022-06-16 2023-09-09 mise des opérations de sécu Rural Land Tenure Security ation risation foncière rurale dans Program les régions du Sud Comoé et de l'Indénié Djuablin- Phase d'extension CI-AFOR-293815-CS-CDS / R ecrutement du groupement CGEDS-ETAFAT-TERRABO- I Component 2 – Support Imp NGENIEURS CONSEILS pour l lementation of the National Under Implement IDA / 61900 Prior Direct Selection Direct 3,223,811.00 0.00 2022-05-10 2022-06-28 2022-05-10 2022-07-28 2022-06-16 2023-09-09 a mise en œuvre des opérati Rural Land Tenure Security ation ons de sécurisation foncière Program rurale dans les régions du B afing et du Nzi dans le cadre du PAMOFOR-Phase d'extens ion CI-AFOR-279312-CS-INDV-K K-22 / Recrutement de l'assi Component 1 – Strengtheni Individual Consult IDA / 61900 Post Open 25,408.00 0.00 Canceled 2022-04-18 2022-06-06 2022-06-27 2022-08-01 2023-01-28 stant technique à la DFR po ng Rural Land Institutions ant Selection ur conduire la reforme juridi que et règlementaire CI-AFOR-284239-CS-INDV-K K-22 / Recrutement d'un con sultant pour la formation d'a Component 1 – Strengtheni Individual Consult IDA / 61900 Post Open 16,000.00 0.00 Canceled 2022-03-30 2022-05-18 2022-06-08 2022-07-13 2023-01-09 ppropriation des agents de l ng Rural Land Institutions ant Selection a DFR sur les nouvelles proc édures de sécurisation fonci ère rurale. CI-AFOR-217604-CS-INDV-2 1 / RECRUTEMENT D'ASSIST Component 1 – Strengtheni Individual Consult IDA / 61900 Post Open 54,450.00 0.00 Canceled 2021-10-21 2021-12-09 2021-12-30 2022-02-03 2022-08-02 ANT TECHNIQUE INTERNATI ng Rural Land Institutions ant Selection ONALE AUPRES DE LA DOT CI-AFOR-284289-CS-INDV-K Component 1 – Strengtheni Individual Consult K-22 / Recrutement d'un ATI IDA / 61900 Post Open 58,077.00 0.00 Canceled 2022-04-15 2022-06-03 2022-06-24 2022-07-29 2023-01-25 ng Rural Land Institutions ant Selection auprès du CIGN/BNETD CI-AFOR-279336-CS-INDV-K Component 2 – Support Imp K-22 / Recrutement d'un con lementation of the National Individual Consult IDA / 61900 Post Open 181,489.00 0.00 Canceled 2022-05-18 2022-07-06 2022-07-27 2022-08-31 2023-02-27 sultant Contrôle des opérati Rural Land Tenure Security ant Selection ons de CF (BNETD ou autres Program ) CI-AFOR-281436-CS-INDV-K Component 4 – Program Co Individual Consult K-22 / Recrutement d'un con IDA / 61900 ordination, Monitoring and Post Open 27,223.00 0.00 Canceled 2022-04-17 2022-06-05 2022-06-26 2022-07-31 2023-01-27 ant Selection sultant pour l'actualisation d Knowledge Management u CGES du projet CI-AFOR-281439-CS-INDV-K Component 4 – Program Co Individual Consult K-22 / recrutement d'un con IDA / 61900 ordination, Monitoring and Post Open 27,223.00 0.00 Canceled 2022-07-07 2022-08-25 2022-09-15 2022-10-20 2023-04-18 ant Selection sultant pour l'actualisation d Knowledge Management u CPR du PNSFR CI-AFOR-281427-CS-INDV-K Component 4 – Program Co K-22 / Recrutement d'un cab Individual Consult IDA / 61900 ordination, Monitoring and Prior Open 500,000.00 0.00 Canceled 2022-04-15 2022-06-03 2022-06-24 2022-07-29 2023-01-25 inet pour les études prépara ant Selection Knowledge Management toires au financement additi onnel CI-AFOR-279328-CS-INDV-K Component 2 – Support Imp K-22 / Recrutement d'un con lementation of the National Individual Consult IDA / 61900 Post Open 181,489.00 0.00 Canceled 2022-05-05 2022-06-23 2022-07-14 2022-08-18 2023-02-14 sultant contrôle des opératio Rural Land Tenure Security ant Selection ns de DTV (BNETD/CIGN) Program CI-AFOR-363864-CS-CDS-23 Component 4 – Program Co / CONTROLE DES OPERATIO Pending Impleme IDA / 61900 ordination, Monitoring and Post Direct Selection Direct - National 181,489.00 0.00 2023-06-16 2023-06-26 2023-08-30 2024-02-26 NS DE CERTIFICATS FONCIE ntation Knowledge Management RS ET DE DTV AVEC LE BNET D CI-AFOR-363709-CS-QBS-23 / RECRUTEMENT DE L'ASSIS Component 1 – Strengtheni Individual Consult Pending Impleme TANT TECHNIQUE A LA DFR IDA / 61900 Post Open - National 2,540.00 0.00 2023-06-07 2023-07-26 2023-08-16 2023-09-20 2024-03-18 ng Rural Land Institutions ant Selection ntation POUR CONDUIRE LA REFOR ME JURIDIQUE ET REGLEMEN TAIRE CI-AFOR-364408-CS-INDV-2 3 / RECRUTEMENT D'UN CO NSULTANT INDIVIDUEL POU R L'EVALUATION SOCIALE ET Component 4 – Program Co FORMATION DU PERSONNEL Individual Consult IDA / 61900 ordination, Monitoring and Post Limited 1,814.00 0.00 Under Review 2023-06-12 2023-06-07 2023-06-17 2023-07-08 2023-08-12 2024-02-08 DE L'AFOR, DES OPERATEUR ant Selection Knowledge Management S FONCIERS ET LES PRESTAT AIRES DES SERVICES DE VIO LENCES BASE SUR LE GENR E , L'EXPLOITATION ET ABUS SEXUELS ET L'HARCELEMEN T SEXUEL CI-AFOR-367896-CS-INDV / Component 4 – Program Co Individual Consult Pending Impleme Recrutement d'un assistant IDA / 61900 ordination, Monitoring and Post Limited 28,400.00 0.00 2023-06-26 2023-07-01 2023-07-22 2023-08-26 2024-08-25 ant Selection ntation en suivi évaluation pour l'AF Knowledge Management OR CI-AFOR-367897-CS-INDV / Component 1 – Strengtheni Individual Consult Pending Impleme Recrutement d'un spécialist IDA / 61900 Post Open - National 36,000.00 0.00 2023-06-30 2023-08-18 2023-09-08 2023-10-13 2024-04-10 ng Rural Land Institutions ant Selection ntation e en sauvegarde sociale pou r l'AFOR CI-AFOR-367898-CS-INDV / Component 1 – Strengtheni Individual Consult Pending Impleme Recrutement d'un Chef com IDA / 61900 Post Open - National 24,000.00 0.00 2023-06-30 2023-08-18 2023-09-08 2023-10-13 2024-04-10 ng Rural Land Institutions ant Selection ntation ptable pour l'AFOR CI-AFOR-367900-CS-INDV / Component 1 – Strengtheni Individual Consult Pending Impleme Recrutement d'un Responsa IDA / 61900 Post Open - National 50,000.00 0.00 2023-06-30 2023-08-18 2023-09-08 2023-10-13 2024-04-10 ng Rural Land Institutions ant Selection ntation ble de l'Audit et Contrôle Int erne de l'AFOR Page 14 PROCUREMENT PLAN (Textual Part) Project information: Sindh Water and Agriculture Transformation Project (SWAT) (P167596) Project Implementation agency(ies): (i) Sindh Agriculture Department; (ii) Sindh Irrigation and Drainage Authority and (ii) Sindh Planning & Development Department - Project Coordination and Management Unit Date of the Procurement Plan: October 2022 Period covered by this Procurement Plan: October 15, 2022 June 30 2024 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” November 2020 (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in public procurement rules such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions: 1) The eligibility of bidders shall be as defined under Section III of the Procurement Regulations. Accordingly, no bidder or potential bidder shall be declared ineligible for contracts financed by the Bank for reasons other than those provided in Section III of the Procurement Regulations. 2) For national open competitive procurement, only the model procurement documents acceptable to the World Bank, shall be used. 3) The request for bids/request for proposals document shall require that Bidders/Proposers submitting Bids/Proposals present a signed acceptance (in the form attached) at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights. 4) Procurement Documents include provisions, as agreed with the Bank, intended to adequately mitigate against environmental, social (including sexual exploitation and abuse and gender-based violence), health and safety (“ESHS”) risks and impacts 5) Access to procurement opportunities shall not be restricted to firms that have pre-registered and/or paid a registration fee. 6) No preference of any kind shall be given to national bidders in the bidding process. 7) Procurement methods that use two-envelope process and rated criteria shall be subject to Bank’s prior concurrence When other national procurement arrangements (other than national open competitive procurement) are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is not allowed Letter of Acceptance of the World Bank’s Anticorruption Guidelines and Sanctions Framework1 Date: Invitation of Bids/Proposals No.__________ To: ___________________________________________________________________________ We, along with our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not) consultants and personnel, acknowledge and agree to abide by the World Bank’s policy regarding Fraud and Corruption (corrupt, fraudulent, collusive, coercive, and obstructive practices), as set out and defined in the World Bank’s Anti-Corruption Guidelines2 in connection with the procurement and execution of the contract (in case of award), including any amendments thereto. We declare and warrant that we, along our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not), consultants and personnel, are not subject to, and are not controlled by any entity or individual that is subject to, a temporary suspension, early temporary suspension, or debarment imposed by a member of the World Bank Group, including, inter alia, a cross-debarment imposed by the World Bank Group as agreed with other international financial institutions (including multilateral development banks), or through the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement. Further, we are not ineligible under the laws or official regulations of [Insert name of Employer as per bidding document] or pursuant to a decision of the United Nations Security Council. We confirm our understanding of the consequences of not complying with the World Bank’s Anti-Corruption Guidelines, which may include the following: a. rejection of our Proposal/Bid for award of contract; 1[Drafting note: This document shall be signed by bidders/proposers/consultants and submitted as part of their bids/proposals. In addition, this document shall be signed by the winning bidder/consultant and incorporated as part of the contract.] 2Guidelines on Preventing and Combating Fraud and Corruption in Projects Financed by International Bank for Reconstruction and Development Loans and the International Development Agency Credits and Grants, dated October 15, 2006, and revised in January 2011 and July 2016, as they may be revised from time to time. b. in the case of award, termination of the contract, without prejudice to any other remedy for breach of contract; and c. sanctions, pursuant to the Bank’s Anti-Corruption Guidelines and in accordance with its prevailing sanctions policies and procedures as set forth in the Bank’s Sanctions Framework. This may include a public declaration of ineligibility, either indefinitely or for a stated period of time, (i) to be awarded or otherwise benefit from a Bank-financed contract, financially or in any other manner;3 (ii) to be a nominated4 sub-contractor, sub-consultant, consultant, manufacturer or supplier, or service provider of an otherwise eligible firm being awarded a Bank-financed contract; and (iii) to receive the proceeds of any loan made by the Bank or otherwise to participate further in the preparation or implementation of any Bank- financed project. We understand that we may be declared ineligible as set out above upon: a. completion of World Bank Group sanctions proceedings according to its prevailing sanctions procedures; b. cross-debarment as agreed with other international financial institutions (including multilateral development banks); c. the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement; or d. temporary suspension or early temporary suspension in connection with an ongoing World Bank Group sanctions proceeding. For avoidance of doubt, the foregoing effects of ineligibility do not extend to a sanctioned firm’s or individual’s execution of its ongoing Bank-financed contracts (or its ongoing sub-agreements under such contracts) that are not the subject of a material modification, as determined by the Bank. We shall permit, and shall cause our sub-contractors, sub-consultants, agents (whether declared or not), personnel, consultants, service providers or suppliers, to permit the Bank to inspect5 all accounts, records, and other documents relating to 3 For the avoidance of doubt, a sanctioned party’s ineligibility to be awarded a contract shall include, without limitation, (i) applying for pre-qualification or initial selection), expressing interest in a consultancy, and bidding, either directly or as a nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider, in respect of such contract, and (ii) entering into an addendum or amendment introducing a material modification to any existing contract. 4A nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider (different names are used depending on the bidding document) is one which has been: (i) included by the bidder in its pre-qualification or initial selection application or bid because it brings specific and critical experience and know-how that allow the bidder to meet the qualification requirements for the particular bid; or (ii) appointed by the Borrower. 5Inspections in this context are usually investigative (i.e., forensic) in nature: they involve fact- finding activities undertaken by the Bank or persons appointed by the Bank to address specific the procurement process and/or contract execution (in the case of award), and to have them audited by auditors appointed by the Bank. We agree to preserve all accounts, records, and other documents (whether in hard copy or electronic format) related to the procurement and execution of the contract. Name of the Bidder/Proposer/Consultant: Name of the person duly authorized to sign the Bid/Proposal on behalf of the Bidder/Proposer/ Consultant: Title of the person signing the Letter: matters related to investigations/audits, such as evaluating the veracity of an allegation of possible Fraud and Corruption, through the appropriate mechanisms. Such activity includes but is not limited to accessing and examining a firm's or individual's financial records and information, and making copies thereof as relevant; accessing and examining any other documents, data, and information (whether in hard copy or electronic format) deemed relevant for the investigation/audit, and making copies thereof as relevant; interviewing staff and other relevant individuals; performing physical inspections and site visits; and obtaining third-party verification of information. PROCUREMENT Pakistan : Sindh Water and Agriculture Transformation Project (SWAT) PLAN General Information Country: Pakistan 2022-10-26 Bank’s Approval Date of the Original Procurement Plan: 2023-06-07 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P167596 GPN Date: 2022-03-31 Project Name: Sindh Water and Agriculture Transformation Project (SWAT) Loan / Credit No: / , IDA / 72550 Project Coordination and Management Unit Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Request for Quota PK-PCMU-360998-CW-RFQ / Component 4: Project Coordi Request for Quota Single Stage - One E Pending Imp 2023-10-3 IDA / 72550 Post Open - National tions (Non Bank-S 30,000.00 0.00 2023-05-20 2023-07-15 Renovation of PCMU Office b nation and Monitoring tions nvelope lementation 0 PD) uilding GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PK-PCMU-365693-GO-RFQ / Component 4: Project Coordi Request for Quota Single Stage - One E Pending Impl Procurement of Electronic Eq IDA / 72550 Post Limited 30,000.00 0.00 2023-06-14 2023-07-17 2023-08-16 nation and Monitoring tions nvelope ementation uipments for PCMU Office PK-PCMU-365694-GO-RFQ / Component 4: Project Coordi Request for Quota Single Stage - One E Pending Impl IDA / 72550 Post Limited 25,000.00 0.00 2023-06-17 2023-07-30 2023-09-28 Procurement of PCMU office f nation and Monitoring tions nvelope ementation urniture PK-PCMU-367643-GO-RFQ / Component 4: Project Coordi Request for Quota Single Stage - One E Pending Impl IDA / 72550 Post Open - National 200,000.00 0.00 2023-07-08 2023-08-08 2023-11-30 Procurement of Vehicles for P nation and Monitoring tions nvelope ementation CMU NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PK-PCMU-307039-CS-QCBS / Project Management Consult Component 4: Project Coordi Quality And Cost- Open - Internationa Under Implement ant (PMC) under component / Prior 2,640,000.00 0.00 2022-11-01 2023-01-05 2022-11-22 2023-03-16 2022-12-11 2023-01-08 2023-01-15 2023-02-13 2023-03-06 2028-02-03 nation and Monitoring Based Selection l ation 4.1 of Sindh Water and Agric ulture Transformation (SWA T) Project, PK-PCMU-360991-CS-CQS / P rocurement of Consulting fir m for preparation of “Basic S Component 4: Project Coordi Consultant Qualifi Pending Impleme chedule of Rates (BSR) 2023 IDA / 72550 Post Limited 100,000.00 0.00 2023-05-10 2023-05-25 2023-06-05 2023-06-26 2025-06-30 nation and Monitoring cation Selection ntation ” and “Composite Schedule o f Rates (CSR) 2023” for all ex ecuting agencies of the Gove rnment of Sindh. INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 1 PROCUREMENT PLAN (Textual Part) Project information: Republic of Tajikistan Project name: Tajikistan Preparedness and Resilience to Disasters Project Project ID: P177779 Project Implementation agency: MoF, MoT, CoESCD Date of the Procurement Plan: May 14, 2023 Period covered by this Procurement Plan: Only two packages were provided by MoT, not the full plan Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (November 2020) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the Tendering with Unlimited Participation procurement method may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the Law of the Republic of Tajikistan “Оn Public Procurement of Goods, Works and Services”, # 1955 dated March 15, 2023 such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions: a. The request for bids/request for proposals document shall require that bidders/proposers submitting bids/proposals present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, Bank Anti- Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights. b. The request for bids/request for proposals document, including contract forms, acceptable to the Bank shall be used. c. The request for bids/request for proposals document and contract shall provide the right to the Bank to review procurement documentation and activities. d. Borrower shall put in place an effective complaints review mechanism and shall disclose the details in all the bidding documents. All complaints shall be recorded by the Borrower in the appropriate tracking and monitoring system, as agreed between the Bank and the Borrower. e. No preference shall be applied under competitive bidding following national market approach. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables “Not Applicable”. Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables. “Not Applicable”. Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Specify for each Goods: [is not applicable/is applicable for those contracts identified in the Procurement Plan tables] “Not Applicable”. Works: [is not applicable/is applicable for those contracts identified in the Procurement Plan tables] “Not Applicable”. Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations is Applicable. “Not Applicable” Other Relevant Procurement Information. No CDC activities are envisaged under the project. The MoF will implement Contingent Emergency Response Component, with technical inputs and supervision from relevant agencies such as the CoESCD, IGEES and relevant departments within the MoF. PROCUREMENT Tajikistan : Tajikistan Preparedness and Resilience to Disasters Project PLAN General Information Country: Tajikistan 2023-05-31 Bank’s Approval Date of the Original Procurement Plan: 2023-06-07 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P177779 GPN Date: Project Name: Tajikistan Preparedness and Resilience to Disasters Project Loan / Credit No: IDA / D9780 Committee of Emergency Situation and Civil Defense Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Request for Quota COE/TPRDP/W-RFQ-01 / Rep Component 3: Project Manag Request for Quota Single Stage - One E Pending Imp 2023-08-2 IDA / D9780 Post Open - National tions (Non Bank-S 80,000.00 0.00 2023-05-20 2023-06-24 air of the office of PIG CoESC ement tions nvelope lementation 3 PD) D COE/TPRDP/W-RFQ-02 / Rep Component 2: Strengthening Request for Quota Request for Quota Single Stage - One E Pending Imp 2024-01-1 air of classrooms of the depa IDA / D9780 Disaster Risk Management C Post Open - National tions (Non Bank-S 150,000.00 0.00 2023-09-09 2023-10-14 tions nvelope lementation 2 rtment of anti-hail service in apacity PD) the city of Gissar COE/TPRDP/W-RFB-01 / Cons Request for Bids - Component 2: Strengthening truction of a diving training c Single Stage - One E Small Works SPD Pending Imp 2025-06-2 IDA / D9780 Disaster Risk Management C Post Request for Bids Open - National 1,300,000.00 0.00 2024-03-11 2024-03-16 2024-04-27 2024-05-27 2024-06-24 enter on the basis of the resc nvelope (1 envelope proce lementation 3 apacity ue training center in Karatag ss) Request for Bids - COE/TPRDP/W-RFB-02 / Crea Component 2: Strengthening Single Stage - One E Small Works SPD Pending Imp 2025-06-3 IDA / D9780 Post Request for Bids Open - National 600,000.00 0.00 2024-03-18 2024-03-23 2024-05-04 2024-06-03 2024-07-01 tion (construction) of a canin Disaster Risk Management C nvelope (1 envelope proce lementation 0 e center apacity ss) GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual COE/TPRDP/G-RFQ-03 / Proc Component 3: Project Manag Request for Quota Single Stage - One E Pending Impl IDA / D9780 Post Open - National 80,000.00 0.00 2023-06-03 2023-07-08 2023-09-06 urement of a vehicle for PIG ement tions nvelope ementation CoESCD COE/TPRDP/G-RFQ-10 / Proc Component 2: Strengthening Request for Quota Single Stage - One E Pending Impl urement of a modern multifu IDA / D9780 Disaster Risk Management C Post Open - National 20,000.00 0.00 2024-03-30 2024-05-04 2024-08-02 tions nvelope ementation nctional plotter apacity COE/TPRDP/G-RFQ-01 / Proc Component 3: Project Manag Request for Quota Single Stage - One E Pending Impl urement of office equipment IDA / D9780 Post Open - National 20,000.00 0.00 2023-06-17 2023-07-22 2023-08-21 ement tions nvelope ementation for PIG CoESCD COE/TPRDP/G-RFQ-02 / Proc Component 3: Project Manag Request for Quota Single Stage - One E Pending Impl IDA / D9780 Post Open - National 20,000.00 0.00 2023-06-20 2023-07-25 2023-08-24 urement of office furniture fo ement tions nvelope ementation r PIG CoESCD COE/TPRDP/G-RFQ-04 / Proc Component 3: Project Manag Pending Impl urement of 1C Accounting So IDA / D9780 Post Direct Selection Direct - National 10,000.00 0.00 2023-06-20 2023-06-25 2023-07-09 2023-10-07 ement ementation ftware for PIG CoESCD NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual COE/TPRDP/CQS-01 / Designi ng a robust and resilient tele Component 2: Strengthening Consultant Qualifi Pending Impleme communications architecture IDA / D9780 Disaster Risk Management C Post Open - National 127,000.00 0.00 2023-09-18 2023-10-09 2023-11-13 2023-11-20 2023-12-04 2024-06-01 cation Selection ntation also implements a long-term apacity strategy and action plan for data storage COE/TPRDP/CQS-02 / Improv Component 2: Strengthening ements to the OpenStreetMa Consultant Qualifi Pending Impleme IDA / D9780 Disaster Risk Management C Post Open - National 130,000.00 0.00 2023-09-11 2023-10-02 2023-11-15 2023-12-06 2023-12-20 2024-06-17 p database also support time cation Selection ntation apacity ly access to special satellite i magery COE/TPRDP/CQS-03 / Condu cting consultancy services to enhance coordination, strea Component 2: Strengthening Consultant Qualifi Pending Impleme mline processes, interoperabi IDA / D9780 Disaster Risk Management C Post Open - National 294,000.00 0.00 2023-09-18 2023-10-09 2023-11-22 2023-12-13 2023-12-27 2024-06-24 cation Selection ntation lity, including uploading and apacity accessing options of relevant data to the existing GIS base d platforms (i.e. OpenCenter, NSDI, etc) COE/TPRDP/CQS-04 / Develo Component 2: Strengthening Consultant Qualifi Pending Impleme pment of a mobile app to rais IDA / D9780 Disaster Risk Management C Post Open - National 80,000.00 0.00 2023-10-02 2023-10-23 2023-12-06 2023-12-27 2024-01-10 2024-05-09 cation Selection ntation e public awareness of existin apacity g disasters COE/TPRDP/CQS-05 / Comm unity-based disaster awarene Component 2: Strengthening ss, community preparedness, Consultant Qualifi Pending Impleme IDA / D9780 Disaster Risk Management C Post Open - National 100,000.00 0.00 2023-10-09 2023-10-30 2023-12-13 2024-01-03 2024-01-17 2024-07-15 stakeholder training also har cation Selection ntation apacity dware, software and training on GIS, hazard mapping and DRR COE/TPRDP/CQS-06 / Comm unity-based disaster prepare Component 2: Strengthening dness trainings, including aw Consultant Qualifi Pending Impleme IDA / D9780 Disaster Risk Management C Post Open - National 130,000.00 0.00 2023-10-16 2023-11-06 2023-12-20 2024-01-10 2024-01-24 2024-07-22 areness raising on climate ch cation Selection ntation apacity ange and DRR and training in hazard, risk and vulnerability mapping Page 1 COE/TPRDP/QCBS-02 / Devel opment of design and estima te documentations (costs, Bo Component 2: Strengthening Quality And Cost- Open - Internationa Pending Impleme Qs, etc), as well as E&S ass IDA / D9780 Disaster Risk Management C Post 300,000.00 0.00 2023-08-07 2023-08-28 2023-10-11 2023-11-10 2023-12-10 2024-01-14 2024-02-18 2024-08-16 Based Selection l ntation essments/requirements for t apacity he diving training center and, canine center at Karatag an d author's supervision COE/TPRDP/CQS-07 / Develo Component 2: Strengthening pment of hazard, risk, and vu Consultant Qualifi Pending Impleme IDA / D9780 Disaster Risk Management C Post Open - National 60,000.00 0.00 2023-09-25 2023-10-16 2023-11-29 2023-12-01 2023-12-15 2024-06-12 lnerability maps for the entir cation Selection ntation apacity e territory of Tajikistan INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 2 MINISTERE DE L’AGRICULTURE REPUBLIQUE DU MALI -=-=-=-=-=-=-=- Un Peuple – Un But – Une Foi SECRETARIAT GENERAL DE AGENCE D’AMENAGEMENT DES TERRES ET FOURNITURE DE L’EAU D’IRRIGATION PLAN DE PASSATION DE MARCHES Projet de Développement de la productivité et diversification Agricole dans les Zones Arides du Mali (PDAZAM) I. INFORMATION SUR LE PROJET 1.1. Information générale sur le projet • Pays : Mali • Emprunteur : Mali • Nom du Projet : Projet de Développement de la productivité et diversification Agricole dans les Zones Arides du Mali (PDAZAM) • Numéro d’identification du projet : P164052 • Agence d’Exécution de l’Avance de Préparation du Projet (AEP) : Unité de Coordination du Projet d’Amélioration de la Compétitivité Agro-Industrielle du Mali • Date du plan de passation des marchés : 14 mai 2018 • Période couverte par ce plan de passation des marchés : Octobre 2018 à Mars 2020 Préambule Conformément au paragraphe 5.9 du “Règlement de Passation des Marchés pour les Emprunteurs sollicitant le Financement de Projets d’Investissement (FPI)” (Juillet 2016) (“Règlement de Passation des Marchés”) le Système électronique de la Banque de suivi systématique des transactions de marchés publics (STEP) sera utilisé pour préparer, valider et actualiser les plans de passation des marchés et effectuer toutes les transactions liées à la passation des marchés du projet. Ce texte ainsi que les tableaux du plan de passation des marchés présents dans STEP constituent le plan de passation des marchés du projet. Les conditions suivantes s'appliquent à toutes les activités de passation de marchés du plan de passation de marchés. Les autres éléments du plan de passation des marchés tels que requis au paragraphe 4.4 du Règlement de passation des marchés sont énoncés dans STEP. Les Dossiers types de passation des marchés publics de la Banque devront être utilisés pour tous les contrats soumis à la concurrence internationale, ainsi que pour tous les autres contrats soumis à cette obligation telle que spécifiée dans les tableaux du plan de passation des marchés de STEP. Procédures nationales de passation des marchés : En accord avec le paragraphe 5.3 du Règlement de passation des marchés, dans le cas où la procédure de passation des marchés se fera au niveau national (telle que spécifiée dans les tableaux du plan de passation des marchés inclus de STEP), les procédures nationales de passation des marchés du pays considéré pourront être utilisées. Si l’Emprunteur utilise ses propres procédures d’appel d’offres national ouvert telles qu’énoncées dans le Décret N° 2015-604/P-RM du 25 Septembre 2015 et le Décret N° 2016-0920 du 6 Décembre 2016, ces arrangements sont soumis aux dispositions du paragraphe 5.4 du Règlement de passation des marchés et aux conditions suivantes : -Publicité ouverte de l'opportunité de marché au niveau national, quel que soit le coût estimé du marché. - Le dossier d'appel d'offres/ la demande de propositions devra exiger que les soumissionnaires présentant une offre/ proposition soumette une acceptation signée au moment de l'appel d'offres et devant être incorporée dans tout contrat subséquent, confirmant ainsi l'application et le respect des Directives Anti-Corruption de la Banque, y compris, sans s'y limiter, le droit de la Banque de sanctionner et les droits d'inspection et d'audit de la Banque. -Les contrats doivent inclure une répartition appropriée des responsabilités, des risques et des passifs jugés acceptables par la Banque (notamment pour renforcer la performance environnementale et sociale, la santé et la sécurité). -La publication des informations sur l'attribution du contrat, quel que soit le coût estimé du marché. -Les droits pour la Banque d'examiner la documentation et les activités de passation des marchés. -La conservation des dossiers de passation des marchés (l'exigence doit être incluse dans les documents d'appel d'offres. Lorsque l’Emprunteur utilise d’autres procédures que l’appel d’offres national ouvert, ces procédures devront être en accord avec les dispositions du paragraphe 5.5 du Règlement de passation des marchés. Crédit-bail tel que spécifié au paragraphe 5.10 du Règlement de Passation des marchés : Le crédit-bail peut être utilisé pour les contrats indiqués comme tel dans le Plan de passation des marchés. « Sans objet » 2 Achat de biens d’occasion tel que spécifié au paragraphe 5.11 du Règlement de Passation des Marchés est autorisé pour les contrats indiqués comme tel dans le Plan de passation des marchés. « Sans objet » Préférence nationale telle que spécifiée au paragraphe 5.51 du Règlement de Passation des Marchés (Fournitures et Travaux). Fournitures : ne s’applique pour les contrats indiqués dans les tableaux du Plan de passation des marchés Autres informations pertinentes sur la passation des marchés. « Sans objet » 3 Approche du % Catégo Montant Date de Numéro marché/ finan rie de Méthode de estimé Type de démarrage de Compétition cé Description passati passation de (Dollars revue prévue Référenc par la on de marché US) (jj/mm/aaaa) e Banq marché ue Fournitures Acquisition de moyens Nationale/ logistique (2 véhicules Go-Ref Appel A 15 Janvier GO Ouverte 540 000 100 station wagon, 8 véhicules 1 d’offres posteriori 2019 pick up et 30 motos) Acquisition de matériels informatiques (ordinateurs et accessoires, imprimantes, Go-Ref Nationale/ Demande de A 02 Décembre GO 65 000 100 photocopieuses, scanners et 2 Restreinte Cotation posteriori 2018 divers) pour la gestion du projet Acquisition d’équipements (tablettes, puces, clé Go-Ref Nationale/ Demande de A 15 Décembre internet et divers) pour GO 50 000 100 3 Restreinte Cotation posteriori 2018 l’identification des ménages vulnérables Acquisition de mobiliers de Go-Ref Nationale/ Demande de A 05 Janvier GO 57 000 100 bureau 4 Restreinte Cotation posteriori 2019 Achats de logiciels pour la Go-Ref Nationale/ Demande de A 25 Janvier GO 51 000 100 gestion du projet 5 Restreinte Cotation posteriori 2019 Achats d'intrants et de matériels agricoles pour les Go-Ref Nationale/ Demande de A GO 70 000 100 15 Avril 2019 plateformes d'innovation/ 6 Restreinte Cotation posteriori champs écoles Approche du % Catégo Montant Date de Numéro marché/ finan rie de Méthode de estimé Type de démarrage de Compétition cé Description passati passation de (Dollars revue prévue Référenc par la on de marché US) (jj/mm/aaaa) e Banq marché ue Services de consultants Prestation Agences de Sélection Nationale/ paiements des transferts CS-Ref fondée sur la A CS Ouverte 461 000 100 10 Mars 2019 monétaires aux ménages 1 Qualité et le posteriori vulnérables Coût (SFQC) Services de consultants pour CS Internationale/ Sélection la réalisation des études de Ouverte fondée sur la CS-Ref 1 000 10 Octobre faisabilité APD/DAO Qualité et le 100 A priori 2 000 2019 d'aménagement de la vallée Coût (SFQC) du serpent CS Nationale/ Sélection Ouverte Fondée sur Réalisations d’études sur les l'impact du changement CS-Ref A 15 novembre qualifications 180 000 100 climatique sur l'agriculture 3 posteriori 2019 des malienne consultants (SQC) CS Nationale/ Sélection Ouverte Fondée sur Réalisation des études des les filières traditionnelles ou CS-Ref A qualifications 174 000 100 31 juillet 2019 émergentes dans la zone 4 posteriori des aride consultants (SQC) Contrats de performance CS-Ref CS Nationale/ Sélection A 200 000 100 15 mars 2019 ONG pour l'appui à la mise 5 Ouverte fondée sur la posteriori 5 Approche du % Catégo Montant Date de Numéro marché/ finan rie de Méthode de estimé Type de démarrage de Compétition cé Description passati passation de (Dollars revue prévue Référenc par la on de marché US) (jj/mm/aaaa) e Banq marché ue en œuvre des transferts Qualité et le monétaires et microprojets Coût (SFQC) de la région de Kayes CS Nationale/ Sélection A Contrats de performance Ouverte Fondée sur posteriori ONG pour l'appui à la mise les CS-Ref en œuvre des transferts qualifications 180 000 100 15 avril 2019 6 monétaires et microprojets des de la région de Koulikoro consultants (SQC) CS Nationale/ Sélection A Contrats de performance Ouverte Fondée sur posteriori ONG / opérateurs pour les l'appui à la réalisation des CS-Ref 25 février qualifications 170 000 100 infrastructures 7 2019 des communautaires (opérateur consultants de Kayes) (SQC) CS Nationale/ Sélection Contrats de performance Ouverte Fondée sur ONG / opérateurs pour les l'appui à la réalisation des CS-Ref A 15 février qualifications 170 000 100 infrastructures 8 posteriori 2019 des communautaires (opérateur consultants de Koulikoro) (SQC) Elaboration de plans CS Nationale/ Sélection CS-Ref A d'adaptation aux Ouverte Fondée sur 140 000 100 15 août 2019 9 posteriori changements climatiques les 6 Approche du % Catégo Montant Date de Numéro marché/ finan rie de Méthode de estimé Type de démarrage de Compétition cé Description passati passation de (Dollars revue prévue Référenc par la on de marché US) (jj/mm/aaaa) e Banq marché ue qualifications des consultants (SQC) CS Nationale/ Sélection Ouverte Fondée sur Analyse de l’efficience et les l’efficacité des politiques sur CS-Ref A 05 décembre qualifications 110 000 100 les engrais, les semences et 10 posteriori 2019 des la mécanisation consultants (SQC) CS Nationale/ Sélection Ouverte Fondée sur Réalisation des études et les contrôle des Tavaux CS-Ref A qualifications 120 000 100 12 mars 2019 d'aménagement de cinq (5) 11 posteriori des bas-fonds consultants (SQC) CS Nationale/ Sélection Réalisation des études et le Ouverte Fondée sur contrôle des travaux de les CS-Ref A construction de sept (7) qualifications 40 000 100 14 mai 2019 12 posteriori magasins de stockage et de des Banque de céréales. consultants (SQC) Réalisation des études et le CS-Ref CS Nationale/ Sélection A 19 000 100 20 mai 2019 contrôle des travaux de 13 Ouverte Fondée sur posteriori 7 Approche du % Catégo Montant Date de Numéro marché/ finan rie de Méthode de estimé Type de démarrage de Compétition cé Description passati passation de (Dollars revue prévue Référenc par la on de marché US) (jj/mm/aaaa) e Banq marché ue construction de cinq (5) de les Banque de céréales. qualifications des consultants (SQC) CS Nationale/ Sélection Réalisation des études et le Ouverte Fondée sur contrôle des travaux de les CS-Ref A construction de cinq (5) qualifications 15 000 100 15 mai 2019 14 posteriori boutiques d'intrants des agricoles. consultants (SQC) CS Nationale/ Sélection Ouverte Fondée sur Réalisation des études et les contrôle des Travaux CS-Ref A qualifications 50 000 100 15 avril 2019 d'aménagement de dix (10) 15 posteriori des petits périmètres maraichers consultants (SQC) CS Nationale/ Sélection Ouverte Fondée sur Réalisation des études et le les contrôle des travaux CS-Ref A qualifications 19 000 100 30 avril 2019 d'aménagement de deux (2) 16 posteriori des mares consultants (SQC) 8 Approche du % Catégo Montant Date de Numéro marché/ finan rie de Méthode de estimé Type de démarrage de Compétition cé Description passati passation de (Dollars revue prévue Référenc par la on de marché US) (jj/mm/aaaa) e Banq marché ue CS Nationale/ Sélection Elaboration des manuels de Ouverte Fondée sur procédures SE, procédure les administrative, comptable et CS-Ref A 15 octobre qualifications 88 000 100 financière, exécution, 17 posteriori 2018 des gestion micro-projets, consultants gestion alliances productives (SQC) CS Nationale/ Sélection Appui à l'enrôlement des Ouverte Fondée sur bénéficiaires (actualisation les situation démographique, CS-Ref A 15 novembre qualifications 200 000 100 collectes de données; 18 posteriori 2018 des enquête sociale, carte des consultants bénéficiaires) (SQC) Elaboration du plan de CS Nationale/ Sélection de contingence et du plan de CS-Ref Ouverte Consultants A 10 décembre 18 000 100 passation des marchés 19 individuels posteriori 2018 d'urgence et validations (SCI) CS Nationale/ Sélection de Elaboration du manuel de CS-Ref Ouverte Consultants A 10 novembre gestion des crises et 18 000 100 20 individuels posteriori 2018 validation (SCI) CS Nationale/ Sélection Etude Diagnostic des Ouverte Fondée sur processus et procédures de CS-Ref A 30 décembre les 60 000 100 planification, de mise en 21 posteriori 2019 qualifications œuvre et de suivi des des 9 Approche du % Catégo Montant Date de Numéro marché/ finan rie de Méthode de estimé Type de démarrage de Compétition cé Description passati passation de (Dollars revue prévue Référenc par la on de marché US) (jj/mm/aaaa) e Banq marché ue politiques agricoles et consultants élaboration de plan d'action (SQC) CS Nationale/ Sélection de Elaboration d'un plan de CS-Ref Ouverte Consultants A 20 décembre 14 000 100 communication 22 individuels posteriori 2018 (SCI) CS Nationale/ Sélection de Elaboration du plan action CS-Ref Ouverte Consultants A 15 janvier 18 000 100 genre 23 individuels posteriori 2019 (SCI) Réalisation de l’étude de la CS Nationale/ Sélection de A situation référence des CS-Ref Ouverte Consultants posteriori 31 janvier 35 000 100 indicateurs du cadre de 24 individuels 2019 résultats (SCI) CS Nationale/ Sélection A Ouverte Fondée sur posteriori Etude sur le système de S&E les CS-Ref 05 octobre et de gestion des qualifications 150 000 100 25 2018 connaissances des consultants (SQC) CS Nationale/ Sélection de A Recrutement du Directeur CS-Ref Ouverte Consultants posteriori 01 octobre 227 000 100 technique 26 individuels 2018 (SCI) 10 Approche du % Catégo Montant Date de Numéro marché/ finan rie de Méthode de estimé Type de démarrage de Compétition cé Description passati passation de (Dollars revue prévue Référenc par la on de marché US) (jj/mm/aaaa) e Banq marché ue CS Nationale/ Sélection de A Recrutement du Spécialiste CS-Ref Ouverte Consultants posteriori 15 septembre 147 200 100 en gestion financière 27 individuels 2018 (SCI) CS Nationale/ Sélection de A Recrutement du CS-Ref Ouverte Consultants posteriori 01 octobre Responsable suivi-évaluation 147 200 100 28 individuels 2018 (RSE) (SCI) CS Nationale/ Sélection de A Recrutement du Spécialiste CS-Ref Ouverte Consultants posteriori 01 octobre 147 200 100 passation des marchés (SPM) 29 individuels 2018 (SCI) CS Nationale/ Sélection de A Recrutement du Spécialiste CS-Ref Ouverte Consultants posteriori 01 novembre 147 200 100 Infrastructures rurales 30 individuels 2018 (SCI) CS Nationale/ Sélection de A Recrutement du Spécialiste CS-Ref Ouverte Consultants posteriori 01 novembre 147 200 100 Environnementaliste 31 individuels 2018 (SCI) CS Nationale/ Sélection de A Recrutement du Spécialiste CS-Ref Ouverte Consultants posteriori 15 janvier 113 200 100 TIC 32 individuels 2019 (SCI) 11 Approche du % Catégo Montant Date de Numéro marché/ finan rie de Méthode de estimé Type de démarrage de Compétition cé Description passati passation de (Dollars revue prévue Référenc par la on de marché US) (jj/mm/aaaa) e Banq marché ue CS Nationale/ Sélection de A Recrutement du Spécialiste CS-Ref Ouverte Consultants posteriori 15 janvier en gestion des ressources 113 200 100 33 individuels 2019 naturelles (SCI) CS Nationale/ Sélection de A Recrutement du Spécialiste CS-Ref Ouverte Consultants posteriori 15 janvier mise en valeur agricole 147 200 100 34 individuels 2019 (agronome) (SCI) CS Nationale/ Sélection de A Recrutement du Spécialiste CS-Ref Ouverte Consultants posteriori 1 novembre 113 200 100 en Développement Sociale 35 individuels 2018 (SCI) CS Nationale/ Sélection de A Recrutement du Spécialiste CS-Ref Ouverte Consultants posteriori 15 janvier 113 200 100 en protection sociale 36 individuels 2019 (SCI) CS Nationale/ Sélection de A CS-Ref Ouverte Consultants posteriori 1 novembre Recrutement du Comptable 113 200 100 37 individuels 2018 (SCI) Travaux Tavaux d'aménagement de CW-Ref CW Nationale/ Ouve Appel 100 A 05 janvier 485 000 cinq (5) bas-fonds 1 rte d’offres posteriori 2020 Travaux d'aménagement et CW-Ref CW Nationale/ Ouve Appel 100 A 10 février 227 000 d'équipement (y compris 2 rte d’offres posteriori 2020 12 Approche du % Catégo Montant Date de Numéro marché/ finan rie de Méthode de estimé Type de démarrage de Compétition cé Description passati passation de (Dollars revue prévue Référenc par la on de marché US) (jj/mm/aaaa) e Banq marché ue système de pompage solaires, forage/puits à grand diamètre, réseau de distribution, clôture, etc.) de dix (10) Petits Périmètres Maraichers Travaux de construction de CW Nationale/ Ouve 100 A sept (7) magasins de CW-Ref rte Appel posteriori 15 janvier 160 000 stockage et de conservation 3 d’offres 2020 de produits Agricoles Travaux de construction de CW Nationale/ 100 A CW-Ref Demande de 20 février cinq (5) Boutiques d'intrants Restreinte 60 000 posteriori 4 Cotation 2020 agricoles Travaux de construction de CW-Ref CW Nationale/ Demande de 100 A 76 500 05 mars 2020 cinq (5) Banques de céréales 5 Restreinte Cotation posteriori Travaux d'aménagement de CW-Ref CW Nationale/ Demande de 100 A 77 000 10 mars 2020 deux (2) mares 6 Restreinte Cotation posteriori Travaux de réhabilitation des CW-Ref CW Nationale/ Demande de 100 A 05 décembre 75 500 bureaux pour Antennes 7 Restreinte Cotation posteriori 2018 13 Annexe 1 : Déclaration d’acceptation des Directives de la Banque Mondiale en matière de lutte contre la corruption, et de son régime de sanctions Date:_________________________________ ___ Appel d’Offres / à Propositions No._____________ À: Nous, ainsi que nos sous-traitants, consultants sous-traitants, prestataires de services, fournisseurs, agents (déclarés ou non), consultants et personnel, reconnaissons et conviennent de respecter la politique de la Banque Mondiale en matière de lutte contre la fraude et la corruption (applicable aux faits de corruption, de fraude, de manœuvres collusives, coercitives et obstructives), telle que précisée et définie dans les Directives de la Banque Mondiale1 en matière de lutte contre la fraude et la corruption, dans la passation et l’exécution du contrat (en cas d’attribution de ce dernier), y compris les amendements y afférent. Nous déclarons et garantissons que, avec nos sous-traitants, consultants sous-traitants, prestataires de service, fournisseurs, agents (déclarés ou non), consultants et personnel, ne sommes ni soumis ni contrôlés par aucune entité ou individu qui est sous le coup d’une mesure de suspension temporaire, suspension temporaire anticipée, ou d’exclusion prononcée par une institution du groupe Banque Mondiale, y compris toute mesure d’exclusion croisé prononcé par le groupe Banque Mondiale en vertu de l’accord conclu avec d’autres institutions financières internationales (inclus les Banques de développement multilatérales), ou en vertu d’une décision d’exclusion prononcée par le département des achats du groupe Banque Mondiale pour des faits de fraude et corruption. De plus, nous ne sommes pas inéligibles en vertu des lois ou règlements officiels de {insérer le nom du Maitre d’Ouvrage tel qu’indiqué dans le dossier d’appel d’offres} ou suite à une décision du Conseil de Sécurité des Nations Unies. Nous confirmons que nous comprenons les conséquences à ne pas se conformer aux Directives en matière de lutte contre la fraude et la corruption de la Banque Mondiale, conséquences qui peuvent consister dans les mesures suivantes : a. Rejet de notre Proposition/Offre pour l’attribution du contrat ; b. Dans le cas de l’attribution du contrat, résiliation du contrat, sans préjudice d’autres recours pour rupture du contrat ; et c. Sanctions, en vertu des directives de la Banque en matière de lutte contre la fraude et la corruption et en conformité avec la politique et les procédures applicables dans le cadre du régime de sanctions de 1 Directives sur la Prévention et la Lutte contre la Fraude et la Corruption des Projets Financés par les prêts de la Banque Internationale pour la Reconstruction et le Développement, et Crédits et Dons de l’Agence Internationale pour le Développement, datés du 15 octobre 2006, révisés en Janvier 2011 et juillet 2016, et leurs révisions régulières successives. la Banque. Cela peut consister en une décision publique d’exclusion, permanente ou pour une période déterminée, (i) de se voir attribuer un marché financé par la Banque ou de pouvoir en bénéficier financièrement ou de toute autre manière;2 (ii) d’être choisi comme sous-traitant, consultant, fabricant ou fournisseur, ou encore prestataire de services retenu3 d’une entreprise elle-même éligible à se voir attribuer un contrat financé par la Banque ; et (iii) de recevoir le produit d’un quelconque prêt octroyé par la Banque ou encore de participer à toute préparation ou mise en œuvre d’un projet financé par la Banque. Nous comprenons que nous pouvons être déclarés inéligible tels que décrits plus haut à l’issue: a. du résultat de la procédure de sanctions du Groupe Banque Mondiale en vertu du régime applicable en matière de procédures de sanctions ; b. de l’exclusion croisée telle que prévue avec les autres institutions financières internationales (y compris les banques de développement multilatérales) ; c. de l’application par le groupe Banque Mondiale d’une mesure d’exclusion pour faits de fraude et corruption en relation avec des marchés passés par le département achats du Groupe Banque Mondiale ; ou d. d’une suspension temporaire ou suspension temporaire anticipée prise dans le cadre d’une procédure de sanctions en cours conduite par le Groupe Banque Mondiale. A toute fin d’éclaircissement, les mesures d’inéligibilité décrites plus haut ne s’appliquent pas à une entreprise ou individu pour ses contrats en cours d’exécution financés par la Banque Mondiale (ou accords subsidiaires en cours de ces mêmes contrats) qui ne sont pas sujets à une modification substantielle, telle que déterminée par la Banque. Nous reconnaissons notre obligation, et ferons respecter cette obligation à nos sous-traitants, consultants sous-traitants, agents (déclarés ou pas), personnel, consultants, prestataires de service ou 2 À des fins d’éclaircissement, l’inéligibilité d’une partie sanctionnée à se voir attribuer un contrat, l’empêche obligatoirement de pouvoir, entre autres, (i) être candidat à une procédure de pré-qualification ou de sélection initiale, de manifester son intérêt à une procédure de sélection de consultant, ou de soumissionner directement ou comme sous- traitant, consultant, fabricant, fournisseur, ou prestataire de services retenu pour ce même contrat, et (ii) conclure un addenda ou amendement au contrat consistant en une modification substantielle de celui-ci. 3 Un sous-traitant, consultant, fabricant ou fournisseur ou prestataire de services (plusieurs terminologies sont utilisées selon les différents dossiers d’appel d’offres) retenu est celui qui a été soit: i) inclu par le soumissionnaire lors de sa candidature à la pré-qualification ou sélection initiale ou encore dans son offre en raison de l’expérience particulière et essentielle et du savoir-faire qu'il apporte et qui ont permis au soumissionnaire de satisfaire aux conditions de sélection d’un appel d’offres ; ou soit ii) désigné par l’Emprunteur. 15 fournisseurs, de permettre à la Banque d’examiner4 l’ensemble des pièces comptables, registres, fichiers et autre document relatif à la passation et/ou exécution du contrat (en cas d’attribution), et de les soumettre pour vérification à des auditeurs désignés par la Banque. Nous nous engageons à préserver l’ensemble des pièces comptables, registres, fichiers, ou tout autre document (que ce soit en version papier ou électronique) relatifs à la passation et l’exécution du contrat. Nom du Soumissionnaire/Consultant:__________________________________________ Nom de la personne dument autorisée à signer l’Offre/la Proposition au nom du Soumissionnaire/Consultant : Titre de la personne signant la Déclaration:_______________________________________ 4 Les examens, dans ce cadre, sont revêtent par nature la forme d’enquêtes (de nature judiciaire) : ils comprennent des activités de recherche documentaire et factuelle entreprises par la Banque, ou des personnes désignées par elle, afin de vérifier des aspects spécifiques relevant d’une enquête ou d’un audit, tel que l’évaluation de la véracité d’une accusation éventuelle de Fraude et Corruption, par le moyen de dispositif approprié. De telles activités peuvent inclure, entre autres, d’avoir accès à des pièces financières et comptables d’une entreprise ou d’une personne et les examiner, faire des copies de ces documents selon les besoins, d’avoir accès à tout autre document, donnée et information (sous forme imprimée ou en format électronique) jugés pertinents aux fins de l’enquête ou de l’audit et les examiner, faire des copies de ces documents selon les besoins ; avoir des entretiens avec le personnel et toute autre personne ; mener des inspections physiques et des visites de site ; et obtenir la vérification des informations par une tierce partie. 16 PROCUREMENT Mali : Mali Drylands Development Project PLAN General Information Country: Mali 2019-02-28 Bank’s Approval Date of the Original Procurement Plan: 2023-06-07 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P164052 GPN Date: Project Name: Mali Drylands Development Project Loan / Credit No: IDA / 62830, IDA / D3400 Mali Drylands Development Project Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned ML-PDAZAM-124533-CW-RF Institutional Support, Crisis Q / Travaux de réhabilitation Request for Quota Single Stage - One E 2020-01-3 IDA / D3400 Management and Project Co Post Limited 36,036.00 0.00 Signed 2019-09-07 2023-02-10 2019-11-02 des bureaux des antennes de tions nvelope 1 ordination Ségou et de Kayes ML-PDAZAM-160696-CW-RF Productive Infrastructure at Single Stage - One E Pending Imp 2021-01-1 B / Travaux de réalisation de IDA / 62830 Post Request for Bids Open - National 146,847.00 0.00 2020-04-01 2020-04-06 2020-05-18 2020-06-17 2020-07-22 Community Level nvelope lementation 8 (3) sous-projets dans le cercl e de Macina ML-PDAZAM-160679-CW-RF B / Travaux de réalisation de Productive Infrastructure at Single Stage - One E Pending Imp 2021-02-1 (85) sous-projets d'infrastruc IDA / 62830 Post Request for Bids Open - National 2,181,982.00 0.00 2020-05-01 2020-05-06 2020-06-17 2020-07-17 2020-08-21 Community Level nvelope lementation 7 tures de commercialisation d ans les régions de Kayes, Ko ulikoro et Ségou ML-PDAZAM-105060-CW-RF B / Travaux de construction d Productive Infrastructure at Request for Quota Single Stage - One E 2020-04-0 IDA / 62830 Post Limited 160,000.00 0.00 Canceled 2019-08-16 2019-10-11 e sept magasin de stockage Community Level tions nvelope 8 et de conservation de produit s agricoles ML-PDAZAM-105061-CW-RF Productive Infrastructure at Request for Quota Single Stage - One E 2020-03-1 B / Travaux de construction d IDA / 62830 Post Limited 60,000.00 0.00 Canceled 2019-07-26 2019-09-20 Community Level tions nvelope 8 e cinq (5) Boutiques d'intrant s agricoles ML-PDAZAM-105062-CW-RF Productive Infrastructure at Request for Quota Single Stage - One E 2020-03-1 B / Travaux de construction d IDA / 62830 Post Limited 76,500.00 0.00 Canceled 2019-07-26 2019-09-20 Community Level tions nvelope 8 e cinq (5) banques de céréal es ML-PDAZAM-105064-CW-RF Productive Infrastructure at Request for Quota Single Stage - One E 2020-02-0 Q / Travaux d'aménagement IDA / 62830 Post Limited 77,000.00 0.00 Canceled 2019-06-15 2019-08-10 Community Level tions nvelope 6 de deux (02) mares ML-PDAZAM-105058-CW-RF B / Travaux d'aménagement et équipement (y compris sy Productive Infrastructure at Single Stage - One E 2020-07-0 stème de pompage solaire, f IDA / 62830 Post Request for Bids Open - National 227,000.00 0.00 Canceled 2019-09-15 2019-09-20 2019-11-01 2019-12-01 2020-01-05 Community Level nvelope 3 orage/puits à grands diamètr es, réseau de distribution, clô ture etc.) de dix (10) petits p érimètres maraichers ML-PDAZAM-104310-CW-RF Productive Infrastructure at Single Stage - One E 2020-07-0 B / Travaux d'aménagement IDA / 62830 Post Request for Bids Open - National 485,000.00 0.00 Canceled 2019-09-15 2019-09-20 2019-11-01 2019-12-01 2020-01-05 Community Level nvelope 3 de cinq (05) bas fonds ML-PDAZAM-160653-CW-RF B / Travaux de réalisation de (23) sous-projets d'infrastruc Request for Bids - tures de production dans les Productive Infrastructure at Single Stage - One E Small Works SPD Under Imple 2021-02-1 IDA / 62830 Post Request for Bids Open - National 3,063,064.00 0.00 2020-05-01 2021-11-10 2020-05-06 2022-02-03 2020-06-17 2020-07-17 2020-08-21 régions de Kayes, Koulikoro e Community Level nvelope (1 envelope proce mentation 7 t Ségou (1ère tranche des lo ss) ts des sous-projets d’infrastr uctures de production de la r égion de Koulikoro) en cinq ( 05) lots distincts ML-PDAZAM-267552-CW-RF Request for Bids - B / Travaux d'aménagement Productive Infrastructure at Single Stage - One E Small Works SPD Under Imple 2022-06-2 de dix-sept (17) sous-projets IDA / 62830 Post Request for Bids Open - National 3,037,297.00 0.00 2021-12-08 2022-01-28 2021-12-13 2022-06-14 2022-01-24 2022-03-22 2022-02-23 2022-03-30 Community Level nvelope (1 envelope proce mentation 8 d'infrastructures de producti ss) on dans la région de Kayes - (IP région de Kayes) ML-PDAZAM-267554-CW-RF Request for Bids - B / Travaux d'aménagement Productive Infrastructure at Single Stage - One E Small Works SPD Under Imple 2022-06-2 de quatorze (14) sous-projets IDA / 62830 Post Request for Bids Open - National 1,432,432.00 0.00 2021-12-08 2022-02-18 2021-12-13 2022-01-24 2022-02-23 2022-03-30 Community Level nvelope (1 envelope proce mentation 8 d'infrastructures de producti ss) on dans la région de Ségou - (IP région de Ségou) ML-PDAZAM-267556-CW-RF Request for Bids - B / Travaux d'aménagement Productive Infrastructure at Single Stage - One E Small Works SPD Pending Imp 2022-07-1 de (45) sous-projets d'infrast IDA / 62830 Post Request for Bids Open - National 1,621,622.00 0.00 2021-12-20 2021-12-25 2022-02-05 2022-03-07 2022-04-11 Community Level nvelope (1 envelope proce lementation 0 ructures de production dans ( ss) 4) cercles de la région de Mo pti ML-PDAZAM-267557-CW-RF Request for Bids - B / Travaux de construction d Productive Infrastructure at Single Stage - One E Small Works SPD Under Imple 2022-07-0 e vingt-deux (22) sous-proje IDA / 62830 Post Request for Bids Open - National 1,576,577.00 0.00 2021-12-13 2022-01-31 2021-12-18 2022-02-03 2022-01-29 2022-02-28 2022-04-04 Community Level nvelope (1 envelope proce mentation 3 ts d'infrastructures de comm ss) ercialisation dans la région d e Kayes. ML-PDAZAM-267572-CW-RF Request for Bids - B / Travaux de construction d Productive Infrastructure at Single Stage - One E Small Works SPD Under Imple 2022-07-0 e trente-sept (37) sous-projet IDA / 62830 Post Request for Bids Open - National 1,855,856.00 0.00 2021-12-13 2022-01-31 2021-12-18 2022-02-03 2022-01-29 2022-02-28 2022-04-04 Community Level nvelope (1 envelope proce mentation 3 s d’infrastructures de comme ss) rcialisation dans la région de Koulikoro. ML-PDAZAM-267574-CW-RF Request for Bids - B / Travaux de réalisation trei Productive Infrastructure at Single Stage - One E Small Works SPD Under Imple 2022-07-1 ze (13) sous-projets d’infrastr IDA / 62830 Post Request for Bids Open - National 886,486.00 0.00 2021-12-20 2022-01-31 2021-12-25 2022-02-03 2022-02-05 2022-03-07 2022-04-11 Community Level nvelope (1 envelope proce mentation 0 uctures de commercialisation ss) dans la région de Ségou. ML-PDAZAM-267576-CW-RF Request for Bids - B / Travaux de construction d Productive Infrastructure at Single Stage - One E Small Works SPD Pending Imp 2022-07-1 e (58) sous-projets d'infrastr IDA / 62830 Post Request for Bids Open - National 810,811.00 0.00 2021-12-20 2021-12-25 2022-02-05 2022-03-07 2022-04-11 Community Level nvelope (1 envelope proce lementation 0 uctures de commercialisation ss) dans (4) cercles de la région de Mopti Page 1 GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ML-PDAZAM-99415-GO-RFQ / Acquisition de matériels inf Institutional Support, Crisis Single Stage - One E Under Imple ormatiques (ordinateurs et a IDA / 62830 Management and Project Co Post Request for Bids Limited 65,000.00 0.00 2019-02-26 2023-02-13 2019-03-03 2023-02-13 2019-04-14 2019-08-05 2019-05-14 2023-02-13 2019-06-18 2019-12-15 nvelope mentation ccessoires, imprimantes phot ordination ocopieuses, scanners) ML-PDAZAM-99428-GO-RFQ Institutional Support, Crisis Request for Quota Single Stage - One E Under Imple IDA / 62830 Post Limited 57,000.00 0.00 2019-03-11 2023-02-13 2019-05-06 2019-11-02 / Acquisition de mobiliers de Management and Project Co tions nvelope mentation bureau ordination ML-PDAZAM-99434-GO-RFQ Improving the productivity a / Achats d'intrants et de mat Request for Quota Single Stage - One E Pending Impl IDA / 62830 nd resilience of beneficiary p Post Limited 70,000.00 0.00 2019-03-29 2019-05-24 2019-11-20 ériels agricoles pour les plate tions nvelope ementation opulations formes d'innovation / champ s écoles ML-PDAZAM-99159-GO-RFB / Improving the productivity a Acquisition de moyen logistiq Single Stage - One E IDA / 62830 nd resilience of beneficiary p Post Request for Bids Open - National 540,400.00 0.00 Canceled 2019-02-26 2019-03-03 2019-04-14 2019-05-14 2019-06-18 2019-12-15 ue (2 véhicules Station wago nvelope opulations n, 8 Véhicules Pick up, 30 mo tos) ML-PDAZAM-124499-GO-RF Institutional Support, Crisis Request for Quota Single Stage - One E Under Imple Q / Acquisition d'un groupe él IDA / D3400 Management and Project Co Post Limited 36,063.00 0.00 2019-08-10 2023-02-13 2019-10-05 2019-11-04 tions nvelope mentation ectrogène de 90 KVA pour l'U ordination GP ML-PDAZAM-124502-GO-RF Institutional Support, Crisis Request for Quota Single Stage - One E Under Imple Q / Acquisition de matériel et IDA / D3400 Management and Project Co Post Limited 32,432.00 0.00 2019-08-10 2019-10-05 2019-11-04 tions nvelope mentation d'équipements de communic ordination ation ML-PDAZAM-124518-GO-RF Institutional Support, Crisis Request for Quota Single Stage - One E Under Imple Q / Acquisition matériels et é IDA / D3400 Management and Project Co Post Limited 34,054.00 0.00 2019-08-10 2019-10-05 2020-04-02 tions nvelope mentation quipements de bureau ordination ML-PDAZAM-124528-GO-RF Institutional Support, Crisis Q / Fourniture et installation Request for Quota Single Stage - One E Under Imple IDA / D3400 Management and Project Co Post Limited 27,027.00 0.00 2019-08-10 2023-02-14 2019-10-05 2019-12-04 de réseaux informatique, télé tions nvelope mentation ordination phonique et de vidéo surveill ance au siège de l'UGP ML-PDAZAM-99159-GO-RFB- Institutional Support, Crisis 2 / Acquisition de moyens log Single Stage - One E Under Imple IDA / 62830 Management and Project Co Post Request for Bids Open - National 522,523.00 0.00 2019-08-05 2019-10-31 2019-08-10 2022-06-14 2019-09-21 2019-12-03 2019-10-21 2023-02-17 2019-11-25 2020-01-24 istiques (2 véhicules stations nvelope mentation ordination wagon, 8 véhicules Pick up) ML-PDAZAM-124482-GO-RF Productive Infrastructure at Request for Quota Single Stage - One E Under Imple IDA / 62830 Post Limited 66,667.00 0.00 2019-08-10 2023-02-09 2019-10-05 2019-11-19 Q / Acquisition de 19 motos Community Level tions nvelope mentation ML-PDAZAM-160699-GO-RF Q / Acquisition et livraison de Productive Infrastructure at Request for Quota Single Stage - One E Pending Impl joint watersop pour des fins IDA / 62830 Post Limited 29,000.00 0.00 2020-06-06 2020-08-01 2020-08-31 Community Level tions nvelope ementation des travaux des sous-projets de Bas-fonds (1200 ml) soit 8 0 rouleaux de 15 mètres ML-PDAZAM-160806-GO-RF Institutional Support, Crisis Q / L'acquisition des équipem Request for Quota Single Stage - One E Under Imple IDA / 62830 Management and Project Co Post Limited 10,811.00 0.00 2020-02-06 2023-02-09 2020-04-02 2020-09-29 ents (téléphone) pour la colle tions nvelope mentation ordination cte des données ML-PDAZAM-160799-GO-RF Q / L'acquisition d'un logiciel Institutional Support, Crisis Request for Quota Single Stage - One E Pending Impl d'archivage électronique des IDA / 62830 Management and Project Co Post Limited 10,811.00 0.00 2020-05-06 2020-07-01 2020-12-28 tions nvelope ementation documents du projet (courrie ordination r/passation marché/finance) ML-PDAZAM-140836-GO-RF Improving the productivity a Request for Quota Single Stage - One E Q / Acquisition de motos pour IDA / 62830 nd resilience of beneficiary p Post Limited 12,613.00 0.00 Canceled 2019-11-15 2020-01-10 2020-07-08 tions nvelope les ASL PDAZAM opulations ML-PDAZAM-140847-GO-RF Improving the productivity a Q / Acquisition de 2 kits RSU Request for Quota Single Stage - One E IDA / 62830 nd resilience of beneficiary p Post Limited 38,288.00 0.00 Canceled 2019-10-29 2019-12-24 2020-06-21 (equipements nécessaires po tions nvelope opulations ur le déploiement du RSU au niveau local ML-PDAZAM-140858-GO-RF Q / Acquisition d'équipement Improving the productivity a Request for Quota Single Stage - One E s et logiciels pour la producti IDA / 62830 nd resilience of beneficiary p Post Limited 18,018.00 0.00 Canceled 2019-10-29 2019-12-24 2020-06-21 tions nvelope on des cartes bénéficiaires p opulations our les nouveaux ménages d u projet PDAZAM. ML-PDAZAM-140829-GO-RF Improving the productivity a Request for Quota Single Stage - One E Q / Acquisition d'ordinateurs IDA / 62830 nd resilience of beneficiary p Post Limited 9,009.00 0.00 Canceled 2019-11-15 2020-01-10 2020-07-08 tions nvelope portables et accessoires pou opulations r les ASL PDAZAM ML-PDAZAM-99427-GO-RFQ Improving the productivity a / Acquisition d'équipements ( Request for Quota Single Stage - One E IDA / 62830 nd resilience of beneficiary p Post Limited 50,000.00 0.00 Canceled 2019-03-03 2019-04-28 2019-10-25 tablettes, puces, clés interne tions nvelope opulations t et divers) pour l'identificatio n des ménages ML-PDAZAM-231126-GO-RF Q / Acquisition matériels cha Productive Infrastructure at Request for Quota Single Stage - One E Under Imple IDA / 62830 Post Limited 35,320.00 0.00 2021-05-08 2023-02-08 2021-07-03 2021-12-30 ntier pour les mesures de CE Community Level tions nvelope mentation S/DRS et de kit de petits mat ériels pour la RNA ML-PDAZAM-231155-GO-RF Productive Infrastructure at Request for Quota Single Stage - One E Under Imple Q / Acquisition des semences IDA / 62830 Post Limited 32,430.00 0.00 2021-05-08 2023-02-08 2021-07-03 2021-12-30 Community Level tions nvelope mentation améliorées de céréales et he rbacées ML-PDAZAM-231164-GO-RF Institutional Support, Crisis Q / Équipement des comités Request for Quota Single Stage - One E Under Imple IDA / 62830 Management and Project Co Post Limited 14,410.00 0.00 2021-05-08 2023-02-10 2021-07-03 2021-12-30 de gestion de plainte (registr tions nvelope mentation ordination es, carnets de reçu, commun ication) ML-PDAZAM-231165-GO-RF Productive Infrastructure at Request for Quota Single Stage - One E Q / Confection / livraison de p IDA / 62830 Post Limited 24,320.00 0.00 Canceled 2021-05-08 2021-07-03 2021-12-30 Community Level tions nvelope anneau signalisation Page 2 ML-PDAZAM-282602-GO-RF Q / Acquisition et transport d Improving the productivity a Request for Quota Single Stage - One E Under Imple es semences de céréales am IDA / 62830 nd resilience of beneficiary p Post Limited 27,027.00 0.00 2022-03-19 2023-01-23 2022-05-14 2022-11-10 tions nvelope mentation éliorées resistantes face aux opulations climats pour les (500) produc teurs ML-PDAZAM-282603-GO-RF Q / Acquisition d'un kit de pet Productive Infrastructure at Request for Quota Single Stage - One E Under Imple IDA / 62830 Post Limited 54,054.00 0.00 2022-03-26 2023-01-23 2022-05-21 2022-11-17 its materiels pour la mise en Community Level tions nvelope mentation œuvre des activités GDTE. ML-PDAZAM-285803-GO-RF Institutional Support, Crisis Q / Acquisition de matériel (5 Request for Quota Single Stage - One E Under Imple IDA / 62830 Management and Project Co Post Limited 21,171.00 0.00 2022-04-04 2023-01-23 2022-05-30 2022-06-29 ordinateurs portables, 2 phot tions nvelope mentation ordination ocopieurs et 20 tablettes sm atphones) ML-PDAZAM-285810-GO-RF Institutional Support, Crisis Q / Acquisition de Matériels p Request for Quota Single Stage - One E Under Imple IDA / 62830 Management and Project Co Post Limited 27,030.00 0.00 2022-04-04 2022-10-27 2022-05-30 2022-06-29 our l'installation et le fonctio tions nvelope mentation ordination nnement de l'UAPA ML-PDAZAM-285813-GO-RF Institutional Support, Crisis Q / Equipement de la Salle d Request for Quota Single Stage - One E Under Imple IDA / 62830 Management and Project Co Post Limited 14,010.00 0.00 2022-04-03 2022-10-12 2022-05-29 2022-06-28 e Formation Virtuelle pour le tions nvelope mentation ordination s politiiques Agricoles ML-PDAZAM-342781-GO-RF Q / Confection des plaques d Improving the productivity a Request for Quota Single Stage - One E Pending Impl e signalisation pour les villag IDA / 62830 nd resilience of beneficiary p Post Limited 30,270.00 0.00 2023-04-17 2023-06-12 2023-09-10 tions nvelope ementation es partenaires des Microproje opulations t (Fonio, Sésame, Niébé, éch alotte) ML-PDAZAM-342783-GO-RFB / Acquisition et transport des Improving the productivity a Single Stage - One E semences de céréales amélio IDA / 62830 nd resilience of beneficiary p Post Request for Bids Open - National 126,126.00 0.00 Canceled 2023-03-13 2023-03-18 2023-04-29 2023-05-29 2023-07-03 2023-10-01 nvelope rées resistantes face aux cli opulations mats pour les (2000) product eurs ML-PDAZAM-342786-GO-RF Q / Acquisition d'un kit de pet Productive Infrastructure at Request for Quota Single Stage - One E Pending Impl IDA / 62830 Post Limited 63,063.00 0.00 2023-03-05 2023-04-30 2023-06-29 its materiels pour la mise en Community Level tions nvelope ementation œuvre des activités GDTE (sa ison 2023) ML-PDAZAM-342787-GO-RF Q / Fourniture de petits maté riels et de semences maraich Productive Infrastructure at Request for Quota Single Stage - One E Pending Impl IDA / 62830 Post Limited 45,045.00 0.00 2023-03-05 2023-04-30 2023-06-29 ères aux Cinq (5) Petits Péri Community Level tions nvelope ementation mètre Maraichers (PPM) de Nara dans le cadre de la mis e en valeur Agricole ML-PDAZAM-342802-GO-RF Q / L'acquisition de matériel i nformatique : 15 Ordinateurs Institutional Support, Crisis portables core I17, capacité Request for Quota Single Stage - One E Pending Impl IDA / 62830 Management and Project Co Post Limited 29,189.00 0.00 2023-04-08 2023-06-03 2023-11-30 1To, 13 à 15 pouces, 16 Go d tions nvelope ementation ordination e RAM avec licence windows 11 professionnel, office profe ssionnel et antivirus et 3 Imp rimantes couleur Multi foncti onnelle ML-PDAZAM-342804-GO-RF Institutional Support, Crisis Q / L'acquisition des équipem Request for Quota Single Stage - One E Pending Impl IDA / 62830 Management and Project Co Post Limited 10,811.00 0.00 2023-04-05 2023-05-31 2023-06-30 ents de communication (tabl tions nvelope ementation ordination ette smatphone) pour la colle cte des données ML-PDAZAM-365918-GO-RF Q / Acquisition et transport d Productive Infrastructure at Request for Quota Single Stage - One E Pending Impl es semences de céréales am IDA / 62830 Post Limited 90,090.00 0.00 2023-06-17 2023-08-12 2023-09-11 Community Level tions nvelope ementation éliorées resistantes face aux climats pour les (1500) produ cteurs NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ML-PDAZAM-104214-NC-RFQ Institutional Support, Crisis Request for Quota Single Stage - One E Pending Impl / Achats de logiciels pour la g IDA / 62830 Management and Project Co Post Limited 51,000.00 0.00 2019-03-29 2019-05-24 2019-11-20 tions nvelope ementation estion du projet ordination ML-PDAZAM-176418-NC-UN / Composante de réponse à l’u Improving the productivity a rgence (CERC) du PDAZAM / UN Agencies (Dire Under Imple IDA / D3400 nd resilience of beneficiary p Prior Direct 12,500,000.00 0.00 2020-05-31 2020-05-15 2020-06-05 2020-06-02 2020-07-10 2021-01-06 Assistance alimentaire d’urg ct) mentation opulations ence du Gouvernement du M ali avec le Programme Alime ntaire Mondial (PAM) ML-PDAZAM-285800-NC-RFQ / Impression/Edition des note Institutional Support, Crisis s produites sur la capitalisati Request for Quota Single Stage - One E Under Imple IDA / 62830 Management and Project Co Post Limited 18,020.00 0.00 2022-04-03 2023-01-23 2022-05-29 2022-11-25 on en matière de politique A tions nvelope mentation ordination gricole et les subventions de s intrants et équipements Ag ricoles CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ML-PDAZAM-104824-CS-QCB S / Réalisation d'études sur l'i Productive Infrastructure at Quality And Cost- Pending Impleme IDA / 62830 Post Open - National 180,000.00 0.00 2019-04-30 2019-05-21 2019-07-04 2019-08-01 2019-08-31 2019-10-05 2019-11-09 2020-05-07 mpact du changement climat Community Level Based Selection ntation ique sur l'agriculture malienn e ML-PDAZAM-104826-CS-QCB S / Réalisation des études de Productive Infrastructure at Quality And Cost- Pending Impleme IDA / 62830 Post Open - National 174,000.00 0.00 2019-04-21 2019-05-12 2019-06-25 2019-07-23 2019-08-22 2019-09-26 2019-10-31 2020-01-29 filières traditionnelles ou ém Community Level Based Selection ntation ergente dans la zone aride Page 3 ML-PDAZAM-104896-CS-CQS / Analyse de l'efficience et de Productive Infrastructure at Consultant Qualifi Pending Impleme IDA / 62830 Post Open - National 110,000.00 0.00 2019-05-26 2019-06-16 2019-07-30 2019-08-29 2019-10-03 2020-03-31 l'efficacité des politiques sur Community Level cation Selection ntation les engrais, les semences et l a mécanisation ML-PDAZAM-105040-CS-CQS / Études diagnostic des proce Institutional Support, Crisis ssus et procédures de planifi Consultant Qualifi Pending Impleme IDA / 62830 Management and Project Co Post Open - National 60,000.00 0.00 2019-04-14 2019-05-05 2019-06-18 2019-07-18 2019-08-22 2020-02-18 cation, de mise en œuvre et cation Selection ntation ordination de suivi des politiques agricol es et élaboration de plan d'a ction ML-PDAZAM-105053-CS-CQS Institutional Support, Crisis / Étude sur le système de sui Consultant Qualifi IDA / 62830 Management and Project Co Post Open - National 150,000.00 0.00 Canceled 2019-04-29 2019-05-20 2019-07-03 2019-08-02 2019-09-06 2019-11-05 vi évaluation et de gestion d cation Selection ordination e connaissance ML-PDAZAM-124531-CS-QCB Institutional Support, Crisis Quality And Cost- S / Audit financier et compta IDA / D3400 Management and Project Co Post Open - National 54,054.00 16,656.99 Signed 2019-08-05 2019-07-09 2019-08-26 2022-06-15 2019-10-09 2019-10-16 2019-11-06 2019-11-18 2019-12-06 2020-01-30 2020-01-10 2020-02-14 2020-02-14 2020-04-11 2021-02-13 Based Selection ble pour les exercices 2019, ordination 2020 et 2021 ML-PDAZAM-104830-CS-QCB Productive Infrastructure at Consultant Qualifi Under Implement S / Élaboration de plans d'ad IDA / 62830 Post Open - National 180,000.00 0.00 2019-05-12 2023-02-24 2019-06-02 2019-07-16 2019-08-15 2019-09-19 2020-03-17 Community Level cation Selection ation aptation aux changements cl imatiques ML-PDAZAM-140196-CS-QBS Productive Infrastructure at Consultant Qualifi Under Implement / Informatisation du système IDA / 62830 Post Open - National 25,000.00 0.00 2020-02-23 2023-02-23 2020-03-15 2020-04-28 2020-05-28 2020-07-02 2020-12-29 Community Level cation Selection ation de suivi évaluation ML-PDAZAM-160792-CS-CQS / Services de consultants dan s le cadre de la préparation d Improving the productivity a Consultant Qualifi Pending Impleme e 90 Plans d'Affaires des micr IDA / 62830 nd resilience of beneficiary p Post Open - National 37,840.00 0.00 2020-06-01 2020-06-22 2020-08-05 2020-09-04 2020-10-09 2021-04-07 cation Selection ntation oprojets sélectionnés dans le opulations s filières horticoles porteuse s identifiées dans la zone du projet ML-PDAZAM-160692-CS-QCB S / Services de Consultants c hargés des études technique Productive Infrastructure at Quality And Cost- s, élaboration du DAO et suiv IDA / 62830 Post Open - National 500,720.00 0.00 Under Review 2020-02-01 2023-02-21 2020-02-22 2020-04-06 2020-05-04 2020-06-03 2020-07-08 2020-08-12 2021-02-08 Community Level Based Selection i-contrôles des travaux de (7 6) sous-projets d'infrastructu res de production dans les ré gions de Kayes, Koulikoro et Ségou. ML-PDAZAM-160677-CS-CQS / Services de Consultants cha rgés des études techniques, élaboration du DAO et suivi-c Productive Infrastructure at Consultant Qualifi Pending Impleme IDA / 62830 Post Open - National 227,027.00 0.00 2020-02-01 2020-02-22 2020-04-06 2020-05-06 2020-06-10 2020-08-09 ontrôles des travaux de (85) Community Level cation Selection ntation sous-projets d'infrastructures de commercialisation dans le s régions de Kayes, Koulikoro et Ségou. ML-PDAZAM-160809-CS-CQS / Services de Consultants cha Productive Infrastructure at Consultant Qualifi Pending Impleme rgés des études environnem IDA / 62830 Post Open - National 171,171.00 0.00 2020-03-01 2020-03-22 2020-05-05 2020-06-04 2020-07-09 2020-09-07 Community Level cation Selection ntation entales et sociales dans les r égions de Kayes et Ségou ML-PDAZAM-160795-CS-CQS / Services de Consultants cha Productive Infrastructure at Consultant Qualifi Under Implement rgés des études environnem IDA / 62830 Post Open - National 162,162.00 0.00 2020-03-01 2023-02-21 2020-03-22 2020-05-05 2020-06-04 2020-07-09 2021-01-05 Community Level cation Selection ation entales et sociales dans les r égions de Koulikoro ML-PDAZAM-160794-CS-CQS / Services de Consultants cha rgés des études environnem Productive Infrastructure at Consultant Qualifi Pending Impleme entales et sociales de quatr IDA / 62830 Post Open - National 162,162.00 0.00 2020-03-01 2020-03-22 2020-05-05 2020-06-04 2020-07-09 2020-09-07 Community Level cation Selection ntation e vingt cinq (85) sous-projets d'infrastructures de commerc ialisation dans les régions de Kayes, Koulikoro et Ségou ML-PDAZAM-160657-CS-CQS / Services de Consultants po ur la capitalisation de toutes Institutional Support, Crisis les expériences en matière d Consultant Qualifi IDA / 62830 Management and Project Co Post Open - National 90,090.00 0.00 Canceled 2020-04-01 2020-04-22 2020-06-05 2020-07-05 2020-08-09 2021-02-05 e politique agricole : Étude s cation Selection ordination ynthétique (retro active et pr ospective) sur la préparation, la mise en œuvre et l’évaluat ion des politiques agricoles a u Mali ML-PDAZAM-140844-CS-QCB Improving the productivity a Quality And Cost- S / Agence de paiement pour IDA / 62830 nd resilience of beneficiary p Post Open - National 424,115.00 0.00 Canceled 2019-11-04 2019-11-25 2020-01-08 2020-02-05 2020-03-06 2020-04-10 2020-05-15 2021-05-15 Based Selection les TM et AGR dans la région opulations de Koulikoro ML-PDAZAM-140856-CS-QCB Improving the productivity a Quality And Cost- S / Agence de paiement pour IDA / 62830 nd resilience of beneficiary p Post Open - National 368,154.00 0.00 Canceled 2019-11-03 2019-11-24 2020-01-07 2020-02-04 2020-03-05 2020-04-09 2020-05-14 2021-05-14 Based Selection les TM et AGR dans la région opulations de Kayes ML-PDAZAM-104816-CS-QCB S / Service de consultants po Productive Infrastructure at Quality And Cost- ur la réalisation des études d IDA / 62830 Prior Open - National 1,000,000.00 0.00 Canceled 2019-04-07 2019-04-28 2019-06-11 2019-07-09 2019-08-08 2019-09-12 2019-10-17 2020-10-16 Community Level Based Selection e faisabilité APD/DAO d'amén agement de la vallée du serp ent ML-PDAZAM-104820-CS-QCB Improving the productivity a S / Prestation d'Agence de pa Quality And Cost- IDA / 62830 nd resilience of beneficiary p Post Open - National 461,000.00 0.00 Canceled 2019-04-14 2019-05-05 2019-06-18 2019-07-16 2019-08-15 2019-09-19 2019-10-24 2020-10-23 iement des transferts monét Based Selection opulations aires aux ménages vulnérabl es ML-PDAZAM-104875-CS-CQS / Contrats de performance O Improving the productivity a Consultant Qualifi NG pour l'appui à la mise en IDA / 62830 nd resilience of beneficiary p Post Open - National 180,000.00 0.00 Canceled 2019-04-21 2019-05-12 2019-06-25 2019-07-25 2019-08-29 2020-02-25 cation Selection œuvre des transferts monéta opulations ires et microprojets de la Rég ion de Koulikoro ML-PDAZAM-104831-CS-QCB S / Contrat de performance O Improving the productivity a Quality And Cost- NG pour l'appui à la mise en IDA / 62830 nd resilience of beneficiary p Post Open - National 200,000.00 0.00 Canceled 2019-04-21 2019-05-12 2019-06-25 2019-07-23 2019-08-22 2019-09-26 2019-10-31 2020-10-30 Based Selection œuvre des transferts monéta opulations ires et microprojets de la régi on de Kayes Page 4 ML-PDAZAM-104901-CS-CQS / Réalisation des études et le Productive Infrastructure at Consultant Qualifi IDA / 62830 Post Open - National 120,000.00 0.00 Canceled 2019-04-14 2019-05-05 2019-06-18 2019-07-18 2019-08-22 2020-02-18 contrôle des travaux d'amén Community Level cation Selection agement de cinq (05) bas-fo nds ML-PDAZAM-104902-CS-CQS / Réalisation des études et le Productive Infrastructure at Consultant Qualifi contrôle des travaux de cons IDA / 62830 Post Open - National 40,000.00 0.00 Canceled 2019-05-19 2019-06-09 2019-07-23 2019-08-22 2019-09-26 2020-03-24 Community Level cation Selection truction de sept (07) magasi ns de stockage et de Banque de céréales. ML-PDAZAM-104904-CS-CQS / Réalisation des études et co Productive Infrastructure at Consultant Qualifi IDA / 62830 Post Open - National 15,000.00 0.00 Canceled 2019-04-30 2019-05-21 2019-07-04 2019-08-03 2019-09-07 2020-03-05 ntrôle des travaux de constru Community Level cation Selection ction de cinq (5) boutiques d' intrants agricoles ML-PDAZAM-105028-CS-CQS / Appui à l'enrôlement des bé Improving the productivity a néficiaires (actualisation situ Quality And Cost- IDA / 62830 nd resilience of beneficiary p Post Open - National 200,000.00 0.00 Canceled 2019-04-30 2019-05-21 2019-07-04 2019-08-01 2019-08-31 2019-10-05 2019-11-09 2020-11-08 ation démographique, collect Based Selection opulations e des données, enquête soci ale, carte des bénéficiaires) ML-PDAZAM-105022-CS-CQS / Réalisation des études et co Productive Infrastructure at Consultant Qualifi IDA / 62830 Post Open - National 19,000.00 0.00 Canceled 2019-05-05 2019-05-26 2019-07-09 2019-08-08 2019-09-12 2020-03-10 ntrôle des travaux d'aménag Community Level cation Selection ement de deux (02) mares ML-PDAZAM-104906-CS-CQS / Réalisation des études et co Productive Infrastructure at Consultant Qualifi ntrôle des travaux d'aménag IDA / 62830 Post Open - National 50,000.00 0.00 Canceled 2019-05-12 2019-06-02 2019-07-16 2019-08-15 2019-09-19 2020-03-17 Community Level cation Selection ement de dix (10) petits péri mètres maraîchers ML-PDAZAM-104877-CS-CQS / Contrat de performance ON Productive Infrastructure at Consultant Qualifi G opérateur pou l'appui à la r IDA / 62830 Post Open - National 170,000.00 0.00 Canceled 2019-04-28 2019-05-19 2019-07-02 2019-08-01 2019-09-05 2020-03-03 Community Level cation Selection éalisation des infrastructures communautaires (opérateurs de Kayes) ML-PDAZAM-104893-CS-CQS / Contrat de performance ON Productive Infrastructure at Consultant Qualifi G opérateur pou l'appui à la r IDA / 62830 Post Open - National 170,000.00 0.00 Canceled 2019-04-21 2019-05-12 2019-06-25 2019-07-25 2019-08-29 2020-02-25 Community Level cation Selection éalisation des infrastructures communautaires (opérateurs de Koulikoro) ML-PDAZAM-160689-CS-CQS / Services de Consultants cha rgés des études techniques, Productive Infrastructure at Consultant Qualifi Under Implement IDA / 62830 Post Limited 24,324.00 0.00 2020-01-01 2020-02-09 2020-01-15 2020-03-24 2020-02-14 2020-03-20 2020-05-19 élaboration du DAO et suivi-c Community Level cation Selection ation ontrôles des travaux de réali sation de trois (3) sous-projet s dans le cercle de Macina ML-PDAZAM-157986-CS-CQS / Le service d’un consultant c hargé des études techniques, élaboration du DAO et suivi-c Productive Infrastructure at Consultant Qualifi IDA / 62830 Post Open 227,027.00 0.00 Signed 2020-03-16 2023-01-31 2020-04-06 2023-02-07 2020-05-20 2023-02-07 2020-06-19 2023-02-08 2020-07-24 2020-10-22 ontrôles des travaux de (85) Community Level cation Selection sous-projets d'infrastructres de commercialisation dans le s régions de Kayes, Koulikoro et Ségou. ML-PDAZAM-206646-CS-CQS / Recrutement d'un bureau d' étude pour l'élaboration du p Institutional Support, Crisis Consultant Qualifi lan de Gestion de la Biodiver IDA / 62830 Management and Project Co Post Limited 52,265.00 0.00 Canceled 2020-11-26 2020-12-10 2021-01-09 2021-02-13 2021-03-15 cation Selection sité du Programme d’appui à ordination la Résilience des Systèmes Al imentaires de l’Afrique de l’O uest (PRSA-Mali) ML-PDAZAM-207465-CS-CQS / Recrutement d’une ONG po Institutional Support, Crisis Consultant Qualifi Pending Impleme ur la mise en place des comit IDA / 62830 Management and Project Co Post Open - National 36,036.00 0.00 2020-12-21 2021-01-11 2021-02-24 2021-03-26 2021-04-30 2021-05-30 cation Selection ntation és de gestion des plaintes da ordination ns la région de Kayes ML-PDAZAM-207470-CS-CQS / Recrutement d’une ONG po Institutional Support, Crisis Consultant Qualifi Pending Impleme ur la mise en place des comit IDA / 62830 Management and Project Co Post Open - National 36,036.00 0.00 2020-12-21 2021-01-11 2021-02-24 2021-03-26 2021-04-30 2021-05-30 cation Selection ntation és de gestion des plaintes da ordination ns la région de Koulikoro ML-PDAZAM-207476-CS-CQS / Recrutement d’une ONG po Institutional Support, Crisis Consultant Qualifi Pending Impleme ur la mise en place des comit IDA / 62830 Management and Project Co Post Open - National 36,036.00 0.00 2020-12-21 2021-01-11 2021-02-24 2021-03-26 2021-04-30 2021-05-30 cation Selection ntation és de gestion des plaintes da ordination ns la région de Ségou ML-PDAZAM-207477-CS-CQS / Recrutement d’une ONG po Institutional Support, Crisis Consultant Qualifi Pending Impleme ur la mise en place des comit IDA / 62830 Management and Project Co Post Open - National 36,036.00 0.00 2020-12-21 2021-01-11 2021-02-24 2021-03-26 2021-04-30 2021-05-30 cation Selection ntation és de gestion des plaintes da ordination ns la région de Mopti ML-PDAZAM-219607-CS-CQS / Le service d'un consultant c hargé des études environne Productive Infrastructure at Consultant Qualifi IDA / 62830 Post Open - National 144,140.00 0.00 Under Review 2021-02-15 2023-02-21 2021-03-08 2021-04-21 2021-05-21 2021-06-25 2021-06-29 mentales et sociales des trav Community Level cation Selection aux de vingt-huit (28) sous-p rojets d'infrastructures de pr oduction dans la région de K ayes ML-PDAZAM-219612-CS-CQS / Le service d'un consultant c hargé des études environne Productive Infrastructure at Consultant Qualifi mentales et sociales des trav IDA / 62830 Post Open - National 90,090.00 0.00 Under Review 2021-02-15 2023-02-21 2021-03-08 2021-04-21 2021-05-21 2021-06-25 2021-08-09 Community Level cation Selection aux de quatorze (14) sous-pr ojets d'infrastructures de pr oduction dans la région de S égou. ML-PDAZAM-219619-CS-CQS / Le service de consultant ch argé des EIES des travaux de Productive Infrastructure at Consultant Qualifi IDA / 62830 Post Open - National 108,110.00 0.00 Under Review 2021-02-15 2023-02-21 2021-03-08 2021-04-21 2021-05-21 2021-06-25 2021-08-09 vingt-quatre (24) sous-projet Community Level cation Selection s d'infrastructures de comme rcialisation dans la région de Kayes Page 5 ML-PDAZAM-219624-CS-CQS / Le service de consultant ch argé des EIES des travaux de Productive Infrastructure at Consultant Qualifi IDA / 62830 Post Open - National 162,162.00 0.00 Under Review 2021-02-15 2023-02-21 2021-03-08 2021-04-21 2021-05-21 2021-06-25 2021-08-09 quarante-six (46) sous-projet Community Level cation Selection s d'infrastructures de comme rcialisation dans la région de Koulikoro ML-PDAZAM-219627-CS-CQS / Le service de consultant ch argé des EIES des travaux de Productive Infrastructure at Consultant Qualifi IDA / 62830 Post Open - National 72,072.00 0.00 Under Review 2021-02-15 2023-02-21 2021-03-08 2021-04-21 2021-05-21 2021-06-25 2021-08-09 seize (16) sous-projets d'infra Community Level cation Selection structures de commercialisat ion dans la région de Ségou. ML-PDAZAM-221749-CS-CQS / Service de consultant pour l a conception et création de l a base de données, le dévelo Institutional Support, Crisis Consultant Qualifi Pending Impleme ppement de la plateforme we IDA / 62830 Management and Project Co Post Open - National 47,910.00 0.00 2021-02-25 2021-03-18 2021-05-01 2021-05-31 2021-07-05 2022-01-01 cation Selection ntation b et des applications mobiles ordination androïdes (pour le recensem ent et pour la distribution éle ctronique avec l’utilisation de s cartes à puce NFC RFID ML-PDAZAM-246307-CS-CQS / Service d’un consultant cha rgé des études techniques (A PS, APD), élaboration du doss Productive Infrastructure at Consultant Qualifi IDA / 62830 Post Limited 175,680.00 0.00 Signed 2021-08-31 2021-07-28 2021-09-14 2023-01-12 2021-10-14 2022-02-21 2021-11-18 2022-05-17 ier d'appel d'offres (DAO) et Community Level cation Selection contrôles des travaux de (58 ) sous-projets d'infrastructur es de commercialisation dan s (4) cercles de la région de Mopti ML-PDAZAM-246316-CS-QCB S / Le service d’un consultant chargé des études technique s (APS, APD), élaboration du Productive Infrastructure at Quality And Cost- Under Implement IDA / 62830 Post Open - National 414,410.00 0.00 2021-08-31 2021-07-28 2021-09-21 2023-01-10 2021-11-04 2023-01-18 2021-12-02 2022-01-01 2022-02-05 2022-03-12 2023-03-12 dossier d'appel d'offres (DAO Community Level Based Selection ation ) et contrôles des travaux de (45) sous-projets d'infrastruc tures de production dans (4) cercles de la région de Mopti ML-PDAZAM-251317-CS-CQS / Recrutement d’un consulta nt charge de l’étude d’impac Productive Infrastructure at Consultant Qualifi Under Implement t environnementale et social IDA / 62830 Post Open - National 162,162.00 0.00 2021-08-31 2021-08-03 2021-09-21 2023-02-03 2021-11-04 2023-02-03 2021-12-04 2023-02-03 2022-01-08 2022-07-07 Community Level cation Selection ation e (EIES) des travaux de const ruction des infrastructures de commercialisation dans la ré gion de Mopti ML-PDAZAM-251326-CS-CQS / Recrutement d’un consulta nt charge des évaluations en Productive Infrastructure at Consultant Qualifi vironnementales et sociales ( IDA / 62830 Post Limited 162,162.00 0.00 Under Review 2021-08-31 2023-02-21 2021-09-14 2021-10-14 2021-11-18 2022-05-17 Community Level cation Selection EES) des travaux de construc tion des infrastructures de pr oduction dans la région de M opti ML-PDAZAM-285766-CS-CQS / Recrutement d'une ONG ch argée des activités de préve Institutional Support, Crisis ntion et réponse aux Violenc Consultant Qualifi Pending Impleme IDA / 62830 Management and Project Co Post Limited 36,036.00 0.00 2022-04-01 2022-04-15 2022-05-15 2022-06-19 2022-12-16 es Basées sur le Genre (VBG) cation Selection ntation ordination , y compris l’Exploitation et l es Abus Sexuels (EAS) et le H arcèlement Sexuel (HS) dans la région de Kayes ML-PDAZAM-285767-CS-CQS / Recrutement d'une ONG ch argée des activités de préve Institutional Support, Crisis ntion et réponse aux Violenc Consultant Qualifi Pending Impleme IDA / 62830 Management and Project Co Post Limited 36,036.00 0.00 2022-04-01 2022-04-15 2022-05-15 2022-06-19 2022-12-16 es Basées sur le Genre (VBG) cation Selection ntation ordination , y compris l’Exploitation et l es Abus Sexuels (EAS) et le H arcèlement Sexuel (HS) dans la région de Koulikoro ML-PDAZAM-285769-CS-CQS / Recrutement d'une ONG ch argée des activités de préve Institutional Support, Crisis ntion et réponse aux Violenc Consultant Qualifi Pending Impleme IDA / 62830 Management and Project Co Post Limited 36,036.00 0.00 2022-04-01 2022-04-15 2022-05-15 2022-06-19 2022-12-16 es Basées sur le Genre (VBG) cation Selection ntation ordination , y compris l’Exploitation et l es Abus Sexuels (EAS) et le H arcèlement Sexuel (HS) dans la région de Ségou ML-PDAZAM-285770-CS-CQS / Recrutement d'une ONG ch argée des activités de préve Institutional Support, Crisis ntion et réponse aux Violenc Consultant Qualifi Pending Impleme IDA / 62830 Management and Project Co Post Limited 36,036.00 0.00 2022-04-01 2022-04-15 2022-05-15 2022-06-19 2022-12-16 es Basées sur le Genre (VBG) cation Selection ntation ordination , y compris l’Exploitation et l es Abus Sexuels (EAS) et le H arcèlement Sexuel (HS) dans la région de Mopti ML-PDAZAM-285791-CS-CQS Institutional Support, Crisis Consultant Qualifi Under Implement / Service d'un consultant pou IDA / 62830 Management and Project Co Post Open - National 36,036.00 0.00 2022-03-29 2022-03-29 2022-04-19 2022-06-02 2022-07-02 2022-08-06 2023-02-02 cation Selection ation r l'audit du projet des années ordination 2022 et 2023 ML-PDAZAM-285798-CS-CQS / Service d'une Agence pour l Institutional Support, Crisis a conception, l'impression et Consultant Qualifi IDA / 62830 Management and Project Co Post Limited 34,595.00 0.00 Signed 2022-03-30 2022-04-08 2022-04-13 2023-01-20 2022-05-13 2023-01-20 2022-06-17 2022-12-14 la diffusion de 04 Bulletins d’i cation Selection ordination nformation du PDAZAM quad ri chromé, format A4 de 20 p ages ML-PDAZAM-285836-CS-CQS Institutional Support, Crisis / Etude des effets du projet p Consultant Qualifi Under Implement IDA / 62830 Management and Project Co Post Limited 54,054.00 0.00 2022-03-29 2022-11-23 2022-04-12 2022-05-12 2022-06-16 2022-12-13 ar un consultant/bureau pour cation Selection ation ordination les années 2022 et 2023 ML-PDAZAM-316842-CS-CQS / Service d'un consultant cha Institutional Support, Crisis Consultant Qualifi rgé de la revision du cadre d IDA / 62830 Management and Project Co Post Limited 12,613.00 0.00 Under Review 2022-09-19 2023-02-24 2022-10-03 2022-11-02 2022-12-07 2023-07-05 cation Selection e resultats du système de sui ordination vi évaluation informatisé suit e à la RNP Page 6 ML-PDAZAM-342797-CS-CQS / Recrutement d'une firme po ur la diffusion des résultats d Institutional Support, Crisis Consultant Qualifi Pending Impleme ’évaluation du 3ème Rapport IDA / 62830 Management and Project Co Post Limited 27,027.00 0.00 2023-03-15 2023-03-29 2023-04-28 2023-06-02 2023-08-01 cation Selection ntation du Mali de la revue biennale ordination de Malabo sur la transformati on de l'Agriculture Africaine a u niveau national (Bamako) ML-PDAZAM-342805-CS-CQS / Service d'une Agence pour l a conception, l'impression et Institutional Support, Crisis Consultant Qualifi la diffusion de Bulletins d’info IDA / 62830 Management and Project Co Post Limited 103,784.00 0.00 Under Review 2023-02-28 2023-04-18 2023-03-14 2023-04-13 2023-05-18 2023-11-14 cation Selection rmation trimestriels du PDAZ ordination AM quadri chromé, format A4 de 20 pages pour les années 2023, 2024 et 2025 ML-PDAZAM-342807-CS-CQS / Service d’une agence pour l Institutional Support, Crisis a réalisation de 03 films de c Consultant Qualifi Under Implement IDA / 62830 Management and Project Co Post Limited 37,838.00 0.00 2023-02-28 2023-04-20 2023-03-14 2023-04-13 2023-05-18 2023-11-14 apitalisation (un film par com cation Selection ation ordination posante) sur l’ensemble des acquis du Projet sur l’ensemb le de la zone d’intervention ML-PDAZAM-342808-CS-CQS / Service d’une agence pour l Institutional Support, Crisis Consultant Qualifi Under Implement a réalisation de l’infographie IDA / 62830 Management and Project Co Post Limited 27,027.00 0.00 2023-03-15 2023-04-20 2023-03-29 2023-04-28 2023-06-02 2023-08-01 cation Selection ation multimédia sur l’impact du pr ordination ojet (web documentaire) ML-PDAZAM-357888-CS-CQS Institutional Support, Crisis / Service d’une agence pour l Consultant Qualifi Under Implement IDA / 62830 Management and Project Co Post Limited 19,820.00 0.00 2023-04-24 2023-04-25 2023-05-08 2023-06-07 2023-07-12 2023-08-11 a production de supports de cation Selection ation ordination communication INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ML-PDAZAM-99145-CS-INDV Institutional Support, Crisis Individual Consult Pending Impleme IDA / 62830 Post Open 227,000.00 0.00 2019-02-05 2019-03-26 2019-04-16 2019-05-21 2019-11-17 / Contrat du Directeur Techni Management and Project Co ant Selection ntation que ordination ML-PDAZAM-99147-CS-INDV Institutional Support, Crisis Individual Consult Pending Impleme / Contrat du Spécialiste en G IDA / 62830 Management and Project Co Post Open 147,200.00 0.00 2019-02-05 2019-03-26 2019-04-16 2019-05-21 2019-11-17 ant Selection ntation estion Financière ordination ML-PDAZAM-99149-CS-INDV Institutional Support, Crisis Individual Consult Pending Impleme / Contrat du Spécialiste en Pa IDA / 62830 Management and Project Co Post Open 147,200.00 0.00 2019-02-05 2019-03-26 2019-04-16 2019-05-21 2019-11-17 ant Selection ntation ssation de marché ordination ML-PDAZAM-99150-CS-INDV Institutional Support, Crisis Individual Consult Pending Impleme / Contrat du Spécialiste en In IDA / 62830 Management and Project Co Post Open 147,200.00 0.00 2019-02-19 2019-04-09 2019-04-30 2019-06-04 2019-12-01 ant Selection ntation frastructures rurales ordination ML-PDAZAM-99154-CS-INDV Institutional Support, Crisis Individual Consult Pending Impleme / Contrat du Spécialiste en D IDA / 62830 Management and Project Co Post Open 113,200.00 0.00 2019-02-19 2019-04-09 2019-04-30 2019-06-04 2019-12-01 ant Selection ntation éveloppement Social ordination ML-PDAZAM-99156-CS-INDV Institutional Support, Crisis Individual Consult Pending Impleme / Contrat du Spécialiste en pr IDA / 62830 Management and Project Co Post Open 113,200.00 0.00 2019-02-19 2019-04-09 2019-04-30 2019-06-04 2019-12-01 ant Selection ntation otection sociale ordination ML-PDAZAM-99158-CS-INDV Institutional Support, Crisis Individual Consult Pending Impleme IDA / 62830 Post Open 113,200.00 0.00 2019-02-05 2019-03-26 2019-04-16 2019-05-21 2019-11-17 / Contrat du Comptable Management and Project Co ant Selection ntation ordination ML-PDAZAM-99148-CS-INDV Institutional Support, Crisis Individual Consult Pending Impleme / Contrat du Spécialiste en Su IDA / 62830 Management and Project Co Post Open 147,200.00 0.00 2019-02-05 2019-03-26 2019-04-16 2019-05-21 2019-11-17 ant Selection ntation ivi évaluation ordination ML-PDAZAM-99152-CS-INDV Institutional Support, Crisis Individual Consult Pending Impleme / Contrat du Spécialiste envir IDA / 62830 Management and Project Co Post Open 147,200.00 0.00 2019-02-19 2019-04-09 2019-04-30 2019-06-04 2019-12-01 ant Selection ntation onnementaliste ordination ML-PDAZAM-99439-CS-INDV Institutional Support, Crisis Individual Consult Pending Impleme IDA / 62830 Post Direct 47,695.00 0.00 2019-02-12 2019-02-22 2019-03-15 2019-04-19 2019-10-16 / Contrat du Consultant E-VO Management and Project Co ant Selection ntation UCHER ordination ML-PDAZAM-99441-CS-INDV Institutional Support, Crisis Individual Consult Under Implement / Contrat du Responsable Tec IDA / 62830 Management and Project Co Post Direct 30,525.00 0.00 2019-02-12 2020-03-04 2019-02-22 2020-03-05 2019-03-15 2020-03-19 2019-04-19 2019-10-16 ant Selection ation hnique E-VOUCHER ordination ML-PDAZAM-105033-CS-IND Institutional Support, Crisis V / Élaboration du plan de co Individual Consult Pending Impleme IDA / 62830 Management and Project Co Post Limited 18,000.00 0.00 2019-04-07 2019-04-12 2019-05-03 2019-06-07 2019-12-04 ntingence et du plan de pass ant Selection ntation ordination ation des marchés d'urgenc e et validation ML-PDAZAM-105038-CS-IND Institutional Support, Crisis Individual Consult Pending Impleme V / Manuel de gestion des cri IDA / 62830 Management and Project Co Post Open 18,000.00 0.00 2019-05-12 2019-06-30 2019-07-21 2019-08-25 2020-02-21 ant Selection ntation ses et validation ordination ML-PDAZAM-105043-CS-IND Institutional Support, Crisis Individual Consult Pending Impleme V / Élaboration d'un plan de c IDA / 62830 Management and Project Co Post Open 14,000.00 0.00 2019-04-14 2019-06-02 2019-06-23 2019-07-28 2020-01-24 ant Selection ntation ommunication ordination ML-PDAZAM-105045-CS-IND Institutional Support, Crisis Individual Consult Pending Impleme IDA / 62830 Post Open 18,000.00 0.00 2019-05-27 2019-07-15 2019-08-05 2019-09-09 2020-03-07 V / Élaboration du plan d'acti Management and Project Co ant Selection ntation on Genre ordination ML-PDAZAM-105050-CS-IND Institutional Support, Crisis V / Réalisation de l'étude de l Individual Consult Under Implement IDA / 62830 Management and Project Co Post Open 35,000.00 0.00 2019-04-18 2020-03-24 2019-06-06 2019-06-27 2019-08-01 2020-01-28 a situation de référence des i ant Selection ation ordination ndicateurs du cadre de résult ats ML-PDAZAM-99436-CS-INDV Institutional Support, Crisis Individual Consult Under Implement / Contrat de l'Assistant infor IDA / 62830 Management and Project Co Post Direct 6,360.00 0.00 2019-02-12 2020-03-16 2019-02-22 2020-03-05 2019-03-15 2023-01-28 2019-04-19 2019-10-16 ant Selection ation maticien -E VOUCHER ordination ML-PDAZAM-105025-CS-CQS Institutional Support, Crisis Individual Consult / Élaboration des manuels de IDA / 62830 Management and Project Co Post Limited 30,631.00 0.00 Under Review 2019-06-09 2023-02-24 2019-06-14 2019-07-05 2019-08-09 2020-02-05 ant Selection procédure de Suivi évaluatio ordination n Page 7 ML-PDAZAM-99442-CS-INDV Institutional Support, Crisis Individual Consult Pending Impleme / Contrat du Spécialiste en G IDA / 62830 Management and Project Co Post Direct 25,438.00 0.00 2019-02-12 2019-02-22 2019-03-15 2019-04-19 2019-10-16 ant Selection ntation enre et Développement Soci ordination al E-VOUCHER ML-PDAZAM-108129-CS-IND Institutional Support, Crisis V / Manuel de procédure de g Individual Consult Pending Impleme IDA / 62830 Management and Project Co Post Limited 26,739.00 0.00 2019-05-20 2019-05-25 2019-06-15 2019-07-20 2020-01-16 estion des micro projets et d ant Selection ntation ordination es alliances productives ML-PDAZAM-133565-CS-IND Institutional Support, Crisis Individual Consult Under Implement V / Contrat du Coordinateur R IDA / D3400 Management and Project Co Post Open 140,541.00 0.00 2019-09-09 2019-07-16 2019-10-28 2019-11-18 2019-12-23 2023-12-22 ant Selection ation égional des Régions de Mopti ordination et de Ségou ML-PDAZAM-133569-CS-IND Institutional Support, Crisis V / Contrat du Coordinateur R Individual Consult Under Implement IDA / D3400 Management and Project Co Post Open 140,541.00 0.00 2019-09-09 2019-07-16 2019-10-28 2019-11-18 2019-12-23 2023-12-22 égional des régions de Koulik ant Selection ation ordination oro et de Kayes ML-PDAZAM-133572-CS-IND Institutional Support, Crisis V / Contrat du Spécialiste en Individual Consult Under Implement IDA / D3400 Management and Project Co Post Open 108,108.00 0.00 2019-09-09 2019-10-28 2019-11-18 2019-12-23 2023-12-22 sauvegarde environnemental ant Selection ation ordination e de l'URCP de Ségou ML-PDAZAM-133573-CS-IND Institutional Support, Crisis V / Contrat du Spécialiste en Individual Consult Pending Impleme IDA / D3400 Management and Project Co Post Open 108,108.00 0.00 2019-09-09 2019-10-28 2019-11-18 2019-12-23 2023-12-22 Sauvegarde environnemental ant Selection ntation ordination e de l'URCP de Koulikoro ML-PDAZAM-133574-CS-IND Institutional Support, Crisis Individual Consult Pending Impleme V / Contrat du Spécialiste en IDA / D3400 Management and Project Co Post Open 108,108.00 0.00 2019-09-09 2019-10-28 2019-11-18 2019-12-23 2023-12-22 ant Selection ntation développement social de l'U ordination RCP de Ségou ML-PDAZAM-133575-CS-IND Institutional Support, Crisis Individual Consult Pending Impleme V / Contrat du Spécialiste en IDA / D3400 Management and Project Co Post Open 108,108.00 0.00 2019-09-09 2019-10-28 2019-11-18 2019-12-23 2023-12-22 ant Selection ntation développement social de Kou ordination likoro ML-PDAZAM-139949-CS-IND Improving the productivity a Individual Consult Under Implement V / Étude de la situation de r IDA / 62830 nd resilience of beneficiary p Post Limited 25,225.00 0.00 2019-10-28 2019-10-01 2019-11-02 2019-11-21 2019-11-23 2023-02-02 2019-12-28 2020-01-27 ant Selection ation éférence du fonio au Mali opulations ML-PDAZAM-139971-CS-QBS / Service de consultant pour l Productive Infrastructure at Individual Consult Pending Impleme e cadre stratégique,  instituti IDA / 62830 Post Limited 15,000.00 0.00 2020-04-01 2020-04-06 2020-04-27 2020-06-01 2020-07-31 Community Level ant Selection ntation onnel  et opérationnel de l'un ité d'analyse des politiques ML-PDAZAM-139956-CS-QBS Improving the productivity a / Recrutement d'un bureau d' Individual Consult Pending Impleme IDA / 62830 nd resilience of beneficiary p Post Limited 15,000.00 0.00 2019-11-28 2019-12-03 2019-12-24 2020-01-28 2020-07-26 études pour l'élaboration de ant Selection ntation opulations 50 micro projets sur le Karité ML-PDAZAM-139968-CS-QBS Improving the productivity a / Service de consultant pour l Individual Consult IDA / 62830 nd resilience of beneficiary p Post Limited 20,000.00 0.00 Under Review 2019-12-31 2023-03-16 2020-01-05 2020-01-26 2020-03-01 2020-08-28 'élaboration de 30 micro-proj ant Selection opulations ets sur le fonio ML-PDAZAM-160701-CS-IND V / Services de Consultants p Improving the productivity a Individual Consult our l'élaboration de Business IDA / 62830 nd resilience of beneficiary p Post Limited 12,613.00 0.00 Under Review 2020-02-01 2023-03-16 2020-02-06 2020-02-27 2020-04-02 2020-09-29 ant Selection Plan de 30 de micro projets d opulations ans la filière karité dans les z ones du projet ML-PDAZAM-160684-CS-IND V / Services de Consultants p Improving the productivity a Individual Consult our l'élaboration de Business IDA / 62830 nd resilience of beneficiary p Post Limited 12,613.00 0.00 Under Review 2020-02-01 2023-03-16 2020-02-06 2020-02-27 2020-04-02 2020-09-29 ant Selection Plan de 30 microprojets dan opulations s la filière sésame dans les z ones du projet ML-PDAZAM-160691-CS-IND V / Services de Consultants p Improving the productivity a Individual Consult our l'élaboration de Business IDA / 62830 nd resilience of beneficiary p Post Limited 12,613.00 0.00 Under Review 2020-02-01 2023-03-16 2020-02-06 2020-02-27 2020-04-02 2020-06-01 ant Selection Plan de 30 microprojets dan opulations s la filière niébé dans les zon es du projet ML-PDAZAM-160700-CS-IND V / Services de Consultants p Improving the productivity a Individual Consult our l'élaboration de Business IDA / 62830 nd resilience of beneficiary p Post Limited 12,613.00 0.00 Under Review 2020-02-01 2023-03-16 2020-02-06 2020-02-27 2020-04-02 2020-06-01 ant Selection Plan de 30 microprojets dan opulations s la filière manioc dans les zo nes du projet ML-PDAZAM-160650-CS-IND V / Services de Consultants p Improving the productivity a Individual Consult our l'élaboration de Business IDA / 62830 nd resilience of beneficiary p Post Limited 12,613.00 0.00 Under Review 2020-02-01 2023-03-16 2020-02-06 2020-02-27 2020-04-02 2020-09-29 ant Selection Plan de 30 microprojets dan opulations s la filière oseille dans les zo nes du projet ML-PDAZAM-160676-CS-IND V / Services de Consultants i Improving the productivity a ndividuels pour l'actualisatio Individual Consult Pending Impleme IDA / 62830 nd resilience of beneficiary p Post Limited 25,225.00 0.00 2020-02-01 2020-02-06 2020-02-27 2020-04-02 2020-06-01 n des connaissances sur les c ant Selection ntation opulations haînes de valeur prometteus es à forte valeur ajoutée dan s la région de Ségou et Mopti ML-PDAZAM-160687-CS-IND V / Services de Consultants c Productive Infrastructure at Individual Consult Under Implement hargés des études environne IDA / 62830 Post Limited 9,009.00 0.00 2020-03-01 2023-02-28 2020-03-06 2020-03-27 2020-05-01 2020-05-01 Community Level ant Selection ation mentales et sociales pour le projet d'urgence de Macina ML-PDAZAM-160698-CS-IND V / Services de Consultants c Productive Infrastructure at Individual Consult Pending Impleme IDA / 62830 Post Limited 25,225.00 0.00 2020-10-01 2020-10-06 2020-10-27 2020-12-01 2021-01-30 hargés des études environne Community Level ant Selection ntation mentales et sociales dans la région de Mopti ML-PDAZAM-160796-CS-IND Institutional Support, Crisis V / Service de consultant pou Individual Consult Pending Impleme IDA / 62830 Management and Project Co Post Limited 25,225.00 0.00 2020-09-01 2020-09-06 2020-09-27 2020-11-01 2020-12-31 r le montage stratégique, ins ant Selection ntation ordination titutionnel et opérationnel de l’UAPA ML-PDAZAM-160801-CS-QBS / L'évaluation de la politique Institutional Support, Crisis Individual Consult Pending Impleme de la subvention (intrants, m IDA / 62830 Management and Project Co Post Limited 36,036.00 0.00 2020-07-01 2020-07-06 2020-07-27 2020-08-31 2021-02-27 ant Selection ntation atériels et équipements agric ordination oles de 2008 à nos jours) Page 8 ML-PDAZAM-160790-CS-IND Improving the productivity a V / L'Analyse de la distributio Individual Consult Pending Impleme IDA / 62830 nd resilience of beneficiary p Post Direct 25,225.00 0.00 2020-08-01 2020-08-11 2020-09-01 2020-10-06 2021-04-04 n électronique des intrants a ant Selection ntation opulations gricoles au Mali (E voucher) ML-PDAZAM-160812-CS-IND Institutional Support, Crisis Individual Consult Under Implement V / Services de Consultant po IDA / 62830 Management and Project Co Post Limited 27,027.00 0.00 2020-05-01 2020-05-01 2020-05-06 2023-02-02 2020-05-27 2023-02-02 2020-07-01 2020-07-31 ant Selection ation ur l'élaboration du plan d'acti ordination on genre ML-PDAZAM-160823-CS-IND V / Services de Consultants i ndividuels pour l'actualisatio Improving the productivity a Individual Consult Pending Impleme n des connaissances sur les c IDA / 62830 nd resilience of beneficiary p Post Limited 25,225.00 0.00 2020-03-02 2020-03-07 2020-03-28 2020-05-02 2020-10-29 ant Selection ntation haînes de valeur prometteus opulations es à forte valeur ajoutée dan s les régions de Kayes et Kou likoro ML-PDAZAM-99155-CS-INDV Institutional Support, Crisis Individual Consult IDA / 62830 Post Open 147,200.00 0.00 Canceled 2019-02-26 2019-04-16 2019-05-07 2019-06-11 2019-12-08 / Contrat du Spécialiste TIC Management and Project Co ant Selection ordination ML-PDAZAM-99157-CS-INDV Institutional Support, Crisis Individual Consult / Contrat du Spécialiste en re IDA / 62830 Management and Project Co Post Open 113,200.00 0.00 Canceled 2019-02-19 2019-04-09 2019-04-30 2019-06-04 2019-12-01 ant Selection ssources naturelles ordination ML-PDAZAM-99153-CS-INDV Institutional Support, Crisis Individual Consult / Contrat du Spécialiste en mi IDA / 62830 Management and Project Co Post Open 113,200.00 0.00 Canceled 2019-02-19 2019-04-09 2019-04-30 2019-06-04 2019-12-01 ant Selection se en valeur agricole ordination ML-PDAZAM-171502-CS-IND Institutional Support, Crisis Individual Consult Pending Impleme V / Service de consultant cha IDA / 62830 Management and Project Co Post Limited 3,600.00 0.00 2020-04-29 2020-05-04 2020-05-25 2020-06-29 2020-12-26 ant Selection ntation rgé de la traduction du PAD e ordination n français ML-PDAZAM-174341-CS-IND V / Services de Consultant in dividuel pour la capitalisation de toutes les expériences en Institutional Support, Crisis Individual Consult matière de politique agricole IDA / 62830 Management and Project Co Post Open 27,027.00 0.00 Under Review 2020-05-19 2023-02-23 2020-07-07 2020-07-28 2020-09-01 2021-02-28 ant Selection : Étude synthétique (retro act ordination ive et prospective) sur la pré paration, la mise en œuvre e t l’évaluation des politiques a gricoles au Mali ML-PDAZAM-204042-CS-CDS / Assistance technique de la plateforme E-voucher et le d éploiement d'un système éle Productive Infrastructure at Pending Impleme IDA / 62830 Post Direct Selection Direct 64,865.00 0.00 2020-11-26 2020-12-06 2021-02-09 2021-08-08 ctronique de gestion de la dis Community Level ntation tribution de subvention à Kou tiala, Yanfolila, Niono, San, B araouli, Bla, Segou, Tominian , Bougouni et Kadiolo ML-PDAZAM-206631-CS-IND V / Recrutement d'un consult ant individuel pour l'élaborati Institutional Support, Crisis on du Plan de Gestion des Pe Individual Consult IDA / 62830 Management and Project Co Post Limited 25,261.00 0.00 Canceled 2020-11-26 2020-12-01 2020-12-22 2021-01-26 2021-02-25 stes et Pesticides (PGPP) du ant Selection ordination Programme d’appui à la Résil ience des Systèmes Alimenta ires de l’Afrique de l’Ouest (P RSA-Mali) ML-PDAZAM-206634-CS-IND V / Recrutement d'un consult ant individuel pour l'élaborati Institutional Support, Crisis Individual Consult on du Plan de Gestion de la IDA / 62830 Management and Project Co Post Limited 25,261.00 0.00 Canceled 2020-11-26 2020-12-01 2020-12-22 2021-01-26 2021-02-25 ant Selection Main d’œuvre du Programme ordination d’appui à la Résilience des S ystèmes Alimentaires de l’Afr ique de l’Ouest (PRSA-Mali) ML-PDAZAM-206639-CS-IND V / Recrutement d'un consult ant individuel pour l'élaborati Institutional Support, Crisis Individual Consult on du Plan de Mobilisation de IDA / 62830 Management and Project Co Post Limited 25,261.00 0.00 Canceled 2020-11-26 2020-12-01 2020-12-22 2021-01-26 2021-02-25 ant Selection s Parties Prenantes du Progra ordination mme d’appui à la Résilience des Systèmes Alimentaires d e l’Afrique de l’Ouest (PRSA- Mali) ML-PDAZAM-206640-CS-IND V / Recrutement d'un consult ant individuel pour l'élaborati Institutional Support, Crisis Individual Consult on du Cadre de Gestion Envir IDA / 62830 Management and Project Co Post Limited 25,261.00 0.00 Canceled 2020-11-26 2020-12-01 2020-12-22 2021-01-26 2021-02-25 ant Selection onnemental et Social du Prog ordination ramme d’appui à la Résilienc e des Systèmes Alimentaires de l’Afrique de l’Ouest (PRSA -Mali) ML-PDAZAM-206644-CS-IND V / Recrutement d'un consult ant individuel pour l'élaborati Institutional Support, Crisis on du Cadre de Politique de Individual Consult IDA / 62830 Management and Project Co Post Limited 25,261.00 0.00 Canceled 2020-11-26 2020-12-01 2020-12-22 2021-01-26 2021-02-25 Réinstallation des population ant Selection ordination s du Programme d’appui à la Résilience des Systèmes Ali mentaires de l’Afrique de l’O uest (PRSA-Mali) ML-PDAZAM-206650-CS-IND V / Recrutement d'un consult ant individuel pour l'appui à l Institutional Support, Crisis a préparation de la stratégie Individual Consult Pending Impleme IDA / 62830 Management and Project Co Post Limited 24,390.00 0.00 2020-11-30 2020-12-05 2020-12-26 2021-01-30 2021-02-19 de passation de marchés et d ant Selection ntation ordination u PPM initiale de 18 mois du Programme d’appui à la Résil ience des Systèmes Alimenta ires de l’Afrique de l’Ouest (P RSA-Mali) ML-PDAZAM-209400-CS-IND V / Service d'un(e) Consultan t(e) environnementaliste cha Institutional Support, Crisis Individual Consult rgé d’élaborer (i) le Cadre de IDA / 62830 Management and Project Co Post Limited 27,027.00 0.00 Under Review 2020-12-14 2023-02-22 2020-12-19 2021-01-09 2021-02-13 2021-03-25 ant Selection Gestion Environnementale et ordination Sociale (CGES) du PRSA ; et ( ii) le Plan d'Engagement Envi ronnemental et Social (PEES) ML-PDAZAM-209401-CS-IND V / Service d'un(e) Consultan Institutional Support, Crisis Individual Consult t(e) chargé de l'élaboration d IDA / 62830 Management and Project Co Post Limited 14,414.00 0.00 Under Review 2020-12-14 2023-02-22 2020-12-19 2021-01-09 2021-02-13 2021-03-15 ant Selection u plan de gestion intégrée de ordination s pestes et pesticides (PGIPP) du PRSA Page 9 ML-PDAZAM-209402-CS-IND V / recrutement d'un(e) Cons ultant(e) chargé(e) de la réali Institutional Support, Crisis sation du Plan de Gestion de Individual Consult IDA / 62830 Management and Project Co Post Limited 27,027.00 0.00 Under Review 2020-12-14 2023-02-22 2020-12-19 2021-01-09 2021-02-13 2021-02-17 la Main D’Œuvre (PGMO) ; (ii) ant Selection ordination du Cadre de Politique de Réi nstallation (CPR) , (iii) du Pla n de Mobilisation des Parties Prenantes (PMPP) ML-PDAZAM-209403-CS-IND V / Recrutement d'un(e) Cons ultant(e) pour l'élaboration d Institutional Support, Crisis es Codes de Conduite et le Pl Individual Consult IDA / 62830 Management and Project Co Post Limited 14,414.00 0.00 Under Review 2020-12-14 2023-02-22 2020-12-19 2021-01-09 2021-02-13 2021-03-15 an d’Action d’Atténuation de ant Selection ordination s Risques et Réponses d’expl oitation et abus sexuels (EAS ), harcèlement sexuel (HS), e t les violences contre les enf ants (VCE) ML-PDAZAM-209405-CS-IND V / Recrutement d'un(e) cons Institutional Support, Crisis ultant(e) senior pour la super Individual Consult Pending Impleme IDA / 62830 Management and Project Co Post Limited 25,225.00 0.00 2020-12-14 2020-12-19 2021-01-09 2021-02-13 2021-03-15 vision de l'ONG lors de la mis ant Selection ntation ordination e en place des comités de ge stion des plaintes dans la rég ion de Kayes ML-PDAZAM-209406-CS-IND V / Recrutement d’un(e) cons Institutional Support, Crisis ultant(e) senior pour la super Individual Consult Pending Impleme IDA / 62830 Management and Project Co Post Limited 25,225.00 0.00 2020-12-14 2020-12-19 2021-01-09 2021-02-13 2021-03-15 vision des ONG lors de la mis ant Selection ntation ordination e en place des comités de ge stion des plaintes dans la rég ion de Koulikoro ML-PDAZAM-209407-CS-IND V / Recrutement d’un(e) cons Institutional Support, Crisis ultant(e) senior pour la super Individual Consult Pending Impleme IDA / 62830 Management and Project Co Post Limited 25,225.00 0.00 2020-12-14 2020-12-19 2021-01-09 2021-02-13 2021-03-15 vision des ONG lors de la mis ant Selection ntation ordination e en place des comités de ge stion des plaintes dans la rég ion de Ségou ML-PDAZAM-209408-CS-IND V / Recrutement d’un(e) cons Institutional Support, Crisis ultant(e) senior pour la super Individual Consult Pending Impleme IDA / 62830 Management and Project Co Post Limited 100.00 0.00 2020-12-14 2020-12-19 2021-01-09 2021-02-13 2021-03-15 vision des ONG lors de la mis ant Selection ntation ordination e en place des comités de ge stion des plaintes dans la rég ion de Mopti ML-PDAZAM-221754-CS-IND V / Le service d'un (1) consul Improving the productivity a Individual Consult tant pour l’élaboration de 30 IDA / 62830 nd resilience of beneficiary p Post Limited 16,220.00 0.00 Under Review 2021-02-25 2023-03-16 2021-03-02 2021-03-23 2021-04-27 2021-05-27 ant Selection business plans des micro proj opulations ets sur la filière fonio (2ème génération) ML-PDAZAM-221811-CS-IND V / Le service de deux consul Improving the productivity a Individual Consult tants pour l’élaboration de 3 IDA / 62830 nd resilience of beneficiary p Post Limited 16,220.00 0.00 Under Review 2021-02-25 2023-03-16 2021-03-02 2021-03-23 2021-04-27 2021-05-27 ant Selection 0 business plans de micro pr opulations ojets sur la filière Niébé (2èm e génération) ML-PDAZAM-221813-CS-IND V / Services de Consultants p Improving the productivity a our l'élaboration de Business Individual Consult IDA / 62830 nd resilience of beneficiary p Post Limited 16,220.00 0.00 Under Review 2021-03-01 2023-03-16 2021-03-06 2021-03-27 2021-05-01 2021-05-31 Plan de 30 micro-projets dan ant Selection opulations s la filière oseille dans les zo nes du projet (2ème générati on) ML-PDAZAM-221814-CS-IND V / Le service d'un consultant Improving the productivity a Individual Consult pour l’élaboration de 30 busi IDA / 62830 nd resilience of beneficiary p Post Limited 16,220.00 0.00 Under Review 2021-02-25 2023-03-16 2021-03-02 2021-03-23 2021-04-27 2021-04-30 ant Selection ness plans des micro projets opulations sur la filière manioc (2ème g énération) ML-PDAZAM-221815-CS-IND V / Le service d'un consultant Improving the productivity a Individual Consult pour l’élaboration de 30 busi IDA / 62830 nd resilience of beneficiary p Post Limited 16,220.00 0.00 Under Review 2021-02-25 2023-03-16 2021-03-02 2021-03-23 2021-04-27 2021-05-27 ant Selection ness plans des micro projets opulations sur la filière sésame (2ème g énération) ML-PDAZAM-221816-CS-IND V / Le service d'un consultant Improving the productivity a Individual Consult pour l’élaboration de 30 busi IDA / 62830 nd resilience of beneficiary p Post Limited 16,220.00 0.00 Under Review 2021-02-25 2023-03-16 2021-03-02 2021-03-23 2021-04-27 2021-05-27 ant Selection ness plans de micro projets s opulations ur la filière karité (2ème gén ération) ML-PDAZAM-219550-CS-CDS Institutional Support, Crisis Pending Impleme / Contrat du Spécialiste infor IDA / 62830 Management and Project Co Post Direct Selection Direct 16,960.00 0.00 2021-02-15 2021-02-25 2021-05-01 2022-02-24 ntation maticien E-Voucher 2021 ordination ML-PDAZAM-219547-CS-CDS Institutional Support, Crisis Pending Impleme / Contrat du Consultant princi IDA / 62830 Management and Project Co Post Direct Selection Direct 42,400.00 0.00 2021-04-22 2021-05-02 2021-07-06 2022-01-02 ntation pal E-Voucher 2021 ordination ML-PDAZAM-251328-CS-IND V / Service d'un consultant p Improving the productivity a our la formation des membre Individual Consult IDA / 62830 nd resilience of beneficiary p Post Limited 26,126.00 0.00 Signed 2021-08-31 2021-10-13 2021-09-05 2023-01-20 2021-09-26 2023-01-20 2021-10-31 2022-04-29 s des coopératives sur les as ant Selection opulations pects de qualité (HACCP) dan s la transformation des produ its alimentaires ML-PDAZAM-266950-CS-IND Institutional Support, Crisis V / Service d'un consultant p Individual Consult IDA / 62830 Management and Project Co Post Limited 18,020.00 0.00 Under Review 2021-12-13 2021-12-01 2021-12-18 2022-01-08 2022-02-12 2022-03-29 our l'élaboration de la straté ant Selection ordination gie globale et d'un plan de co mmunication ML-PDAZAM-266956-CS-IND Institutional Support, Crisis V / Service d'un consultant p Individual Consult Pending Impleme IDA / 62830 Management and Project Co Post Limited 9,010.00 0.00 2021-12-13 2021-12-18 2022-01-08 2022-02-12 2022-03-29 our l'élaboration d'une straté ant Selection ntation ordination gie de communication en te mps de COVID-19 ML-PDAZAM-275433-CS-IND Institutional Support, Crisis V / Recrutement d'un consult Individual Consult Pending Impleme IDA / 62830 Management and Project Co Post Limited 25,225.00 0.00 2022-01-28 2022-02-02 2022-02-23 2022-03-30 2022-04-29 ant individuel pour l'élaborati ant Selection ntation ordination on du manuel de mise en œu vre du PRSA Page 10 ML-PDAZAM-281692-CS-IND Improving the productivity a V / Service d'un consultant p Individual Consult Pending Impleme IDA / 62830 nd resilience of beneficiary p Post Limited 25,230.00 0.00 2022-03-15 2022-03-20 2022-04-10 2022-05-15 2022-08-13 our la formation des coopéra ant Selection ntation opulations tives dans la gestion des déc hets ML-PDAZAM-281701-CS-IND V / Service d'un Consultant p our le renforcement des capa Improving the productivity a Individual Consult Pending Impleme cités des partenaires des PAP IDA / 62830 nd resilience of beneficiary p Post Limited 14,414.00 0.00 2022-03-15 2022-03-20 2022-04-10 2022-05-15 2022-11-11 ant Selection ntation en entreprenariat, gestion fin opulations ancière, technique commerci ales/marketing/recherche de marchés ML-PDAZAM-281706-CS-IND V / Service d'un consultant p Improving the productivity a our la formation sur la lutte i Individual Consult IDA / 62830 nd resilience of beneficiary p Post Limited 14,410.00 0.00 Canceled 2022-03-15 2022-03-20 2022-04-10 2022-05-15 2022-11-11 ntégrée contre les pestes/rav ant Selection opulations ageurs et les techniques de g estion intégrée de la fertilité des sols à Bamako ML-PDAZAM-281713-CS-IND V / Service d'un Consultant p Improving the productivity a our l'élaboration de 30 Busin Individual Consult IDA / 62830 nd resilience of beneficiary p Post Limited 16,220.00 0.00 Under Review 2022-03-15 2022-09-27 2022-03-20 2022-04-10 2022-05-15 2022-11-11 ess Plans de microprojets da ant Selection opulations ns la filière fonio dans les zon es du projet (3ème génératio n) ML-PDAZAM-281720-CS-IND V / Services d'un Consultant Improving the productivity a pour l'élaboration 30 Busines Individual Consult IDA / 62830 nd resilience of beneficiary p Post Limited 16,220.00 0.00 Under Review 2022-03-15 2022-09-27 2022-03-20 2022-04-10 2022-05-15 2022-11-11 s Plans de micro-projets dans ant Selection opulations la filière sésame dans les zon es du projet (3ème génératio n) ML-PDAZAM-282591-CS-IND V / Services d'un Consultant Improving the productivity a pour assistance à elaboration Individual Consult IDA / 62830 nd resilience of beneficiary p Post Limited 16,220.00 0.00 Under Review 2022-03-14 2022-09-27 2022-03-19 2022-04-09 2022-05-14 2022-11-10 de 30 Business Plans de micr ant Selection opulations o-projets dans la filière niébé dans les zones du projet (3è me génération) ML-PDAZAM-282592-CS-IND V / Services d'un Consultant Improving the productivity a pour l'assistance à l'élaborati Individual Consult IDA / 62830 nd resilience of beneficiary p Post Limited 16,220.00 0.00 Under Review 2022-03-14 2022-09-27 2022-03-19 2022-04-09 2022-05-14 2022-11-10 on de 30 Business Plans de ant Selection opulations micro-projets dans la filière manioc dans les zones du pr ojet (3ème génération) ML-PDAZAM-282593-CS-IND V / Services d'un Consultant Improving the productivity a pour l'assistance à l'élaborati Individual Consult IDA / 62830 nd resilience of beneficiary p Post Limited 16,220.00 0.00 Under Review 2022-03-14 2022-09-27 2022-03-19 2022-04-09 2022-05-14 2022-11-10 on de 30 Business Plans de ant Selection opulations microprojets dans la filière os eille dans les zones du projet (3ème génération) ML-PDAZAM-282594-CS-IND V / Services d'un Consultant Improving the productivity a pour l'assistance à l'élaborati Individual Consult IDA / 62830 nd resilience of beneficiary p Post Limited 16,220.00 0.00 Under Review 2022-03-14 2023-02-17 2022-03-19 2022-04-09 2022-05-14 2022-11-10 on de 30 Plans d'affaires de ant Selection opulations micro-projets dans la filière é chalote/oignon d'hivernage d ans les zones du projet ML-PDAZAM-282595-CS-IND V / Services d'un Consultant Improving the productivity a pour l'assistance à l'élaborati Individual Consult Pending Impleme IDA / 62830 nd resilience of beneficiary p Post Limited 16,220.00 0.00 2022-03-14 2022-03-19 2022-04-09 2022-05-14 2022-11-10 on de Plans d'affaires de 30 ant Selection ntation opulations microprojets dans la filière Pi ment dans les zones du proje t ML-PDAZAM-282596-CS-IND V / Services d'un Consultant Improving the productivity a pour l'assistance à l'élaborati Individual Consult Pending Impleme IDA / 62830 nd resilience of beneficiary p Post Limited 16,220.00 0.00 2022-03-14 2022-03-19 2022-04-09 2022-05-14 2022-11-10 on de 30 Business Plans de ant Selection ntation opulations microprojets dans la filière P omme de terre dans les zone s du projet ML-PDAZAM-282597-CS-IND V / Services d'un Consultant Improving the productivity a pour l'assistance à l'élaborati Individual Consult Pending Impleme IDA / 62830 nd resilience of beneficiary p Post Limited 16,220.00 0.00 2022-03-14 2022-03-19 2022-04-09 2022-05-14 2022-11-10 on de 30 Business Plans de ant Selection ntation opulations microprojets dans la filière H aricot vert dans les zones du projet ML-PDAZAM-282598-CS-IND V / Services d'un Consultant Improving the productivity a pour l'assistance à l'élaborati Individual Consult Pending Impleme IDA / 62830 nd resilience of beneficiary p Post Limited 16,220.00 0.00 2022-03-14 2022-03-19 2022-04-09 2022-05-14 2022-11-10 on de 30 Business Plans de ant Selection ntation opulations microprojets dans la filière G omme arabique dans les zon es du projet ML-PDAZAM-282599-CS-IND V / Services d'un Consultant Improving the productivity a Individual Consult Pending Impleme pour la formation sur les tech IDA / 62830 nd resilience of beneficiary p Post Limited 27,027.00 0.00 2022-07-07 2022-07-12 2022-08-02 2022-09-06 2023-03-05 ant Selection ntation niques post-récolte (conserv opulations ation, stockage, conditionne ment, contrôle de qualité) ML-PDAZAM-282600-CS-IND V / Services d'un Consultant Improving the productivity a sur la structuration d’une offr Individual Consult Pending Impleme IDA / 62830 nd resilience of beneficiary p Post Limited 27,027.00 0.00 2022-06-03 2022-06-08 2022-06-29 2022-08-03 2023-01-30 e de produits paysans de qua ant Selection ntation opulations lité et sur l’exploitation d’un système d’information sur le s marchés ML-PDAZAM-282601-CS-IND Improving the productivity a V / Services d'un Consultant Individual Consult Pending Impleme IDA / 62830 nd resilience of beneficiary p Post Limited 27,027.00 0.00 2022-06-01 2022-06-06 2022-06-27 2022-08-01 2023-01-28 pour sur l’approche M4P (Ma ant Selection ntation opulations rkets For the Poor) ML-PDAZAM-285772-CS-IND V / Service de consultant pou r la tenue de l'atelier sur la S Institutional Support, Crisis Individual Consult Pending Impleme ensibilisation des responsabl IDA / 62830 Management and Project Co Post Limited 9,009.00 0.00 2022-03-30 2022-04-04 2022-04-25 2022-05-30 2022-11-26 ant Selection ntation es des OP et des leaders ho ordination mmes sur le dispositif de la l oi sur le genre et la LOA et la session de formation en genr e Page 11 ML-PDAZAM-285774-CS-IND V / Service de consultant po ur la formation en genre (ana Institutional Support, Crisis lyse et intégration) dans les c Individual Consult Pending Impleme IDA / 62830 Management and Project Co Post Limited 9,009.00 0.00 2022-03-29 2022-04-03 2022-04-24 2022-05-29 2022-11-25 ommunes partenaires en vue ant Selection ntation ordination de l’intégration et/ou promoti on féminine dans leur PDESC , à l’intention des autorités c ommunales et communautair es. ML-PDAZAM-285778-CS-IND V / Service d'un consultant c Institutional Support, Crisis Individual Consult Under Implement hargé de la formation sur la IDA / 62830 Management and Project Co Post Limited 9,009.00 0.00 2022-04-01 2022-04-11 2022-04-06 2023-01-20 2022-04-27 2023-01-20 2022-06-01 2022-11-28 ant Selection ation Gestion Axée sur les Résultat ordination s (GAR) et les méthodes de c ollecte des données ML-PDAZAM-285780-CS-IND V / Service d'un consultant c Institutional Support, Crisis Individual Consult hargé de la revision du cadre IDA / 62830 Management and Project Co Post Limited 12,613.00 0.00 Canceled 2022-03-28 2022-04-29 2022-04-02 2022-04-23 2022-05-28 2022-11-24 ant Selection de resultats du système de s ordination uivi évaluation informatisé su ite à la RNP ML-PDAZAM-285816-CS-IND V / Service d'un consultant p our l'étude relative à la ratio Institutional Support, Crisis nnalisation des investisseme Individual Consult Pending Impleme IDA / 62830 Management and Project Co Post Limited 18,020.00 0.00 2022-03-29 2022-04-03 2022-04-24 2022-05-29 2022-11-25 nts Agricoles (intrants, équip ant Selection ntation ordination ements, aménagements, etc) dans les zones arides et sem i arides cas des régions de K ayes, Koulikoro, Ségou……) ML-PDAZAM-285821-CS-IND V / Service d’un consultant in dividuel pour la mise à jour d Institutional Support, Crisis u Cadre de Politique de Réins Individual Consult IDA / 62830 Management and Project Co Post Limited 27,027.00 0.00 Under Review 2022-03-30 2023-02-23 2022-04-04 2022-04-25 2022-05-30 2022-06-03 tallation des Populations (CP ant Selection ordination RP) et l’élaboration d’un Plan de Mobilisation des Parties Pr enantes (PMPP) du financem ent additionnel du PDAZAM ML-PDAZAM-285828-CS-IND V / Service d’un consultant p our la mise à jour du CGES et Institutional Support, Crisis l’élaboration du Plan de Gesti Individual Consult IDA / 62830 Management and Project Co Post Limited 45,045.00 0.00 Under Review 2022-03-21 2022-06-01 2022-03-26 2022-04-16 2022-05-21 2022-05-25 on de la Main-d'œuvre (PGM ant Selection ordination O), Plan de Gestion des Nuisi bles (PGN), Évaluation des Ri sques Sécuritaires (ERS) du fi nancement additionnel ML-PDAZAM-285879-CS-IND Institutional Support, Crisis V / Recrutement d’un consult Individual Consult Under Implement IDA / 62830 Management and Project Co Post Limited 15,000.00 0.00 2022-03-28 2022-04-01 2022-04-02 2022-04-19 2022-04-23 2023-01-20 2022-05-28 2022-11-24 ant court terme en appui au ant Selection ation ordination spécialiste en passation des marches ML-PDAZAM-315288-CS-IND V / Recrutement d'un spéciali Institutional Support, Crisis Individual Consult ste Agronome, pour l'appui à IDA / 62830 Management and Project Co Post Limited 36,850.00 0.00 Under Review 2022-09-12 2023-03-07 2022-09-17 2022-10-08 2022-11-12 2023-01-01 ant Selection la mise en œuvre du PDAZA ordination M et la préparation du financ ement additionnel ML-PDAZAM-315289-CS-IND V / Recrutement d'un spéciali Institutional Support, Crisis ste en Agroéconomie, pour l' Individual Consult IDA / 62830 Management and Project Co Post Limited 37,300.00 0.00 Under Review 2022-09-12 2023-03-07 2022-09-17 2022-10-08 2022-11-12 2023-01-01 appui à la mise en œuvre du ant Selection ordination PDAZAM et la préparation du financement additionnel ML-PDAZAM-315290-CS-IND V / Recrutement d'un Econo Institutional Support, Crisis Individual Consult Pending Impleme miste-financier, pour l'appui IDA / 62830 Management and Project Co Post Limited 30,400.00 0.00 2022-09-12 2022-09-17 2022-10-08 2022-11-12 2022-11-16 ant Selection ntation à la mise en œuvre du PDAZ ordination AM et la préparation du finan cement additionnel ML-PDAZAM-315291-CS-IND V / Service d'un Consultant p Improving the productivity a our l'élaboration de 30 Busin Individual Consult IDA / 62830 nd resilience of beneficiary p Post Limited 16,220.00 0.00 Under Review 2022-09-12 2022-09-27 2022-09-17 2022-10-08 2022-11-12 2023-05-11 ess Plans de microprojets da ant Selection opulations ns la filière Karité dans les zo nes du projet (3ème générati on) ML-PDAZAM-316216-CS-IND Institutional Support, Crisis V / Recrutement d'un Spécial Individual Consult Pending Impleme IDA / 62830 Management and Project Co Post Limited 10,810.00 0.00 2022-09-19 2022-09-24 2022-10-15 2022-11-19 2022-11-22 iste Genre pour l'élaboration ant Selection ntation ordination de la stratégie Genre du fina ncement additionnel ML-PDAZAM-342765-CS-IND Improving the productivity a V / Service d'un consultant p Individual Consult Pending Impleme IDA / 62830 nd resilience of beneficiary p Post Limited 14,141.00 0.00 2023-02-28 2023-03-05 2023-03-26 2023-04-30 2023-06-29 our la formation sur la lutte i ant Selection ntation opulations ntégrée contre les pestes / ra vageurs ML-PDAZAM-342772-CS-IND V / Service d'un consultant p Improving the productivity a Individual Consult Pending Impleme our la formation des membre IDA / 62830 nd resilience of beneficiary p Post Limited 18,018.00 0.00 2023-04-03 2023-04-08 2023-04-29 2023-06-03 2023-08-02 ant Selection ntation s des coopératives sur les tec opulations hniques de production hivern ale de l'échalote/oignon ML-PDAZAM-342775-CS-IND V / Service d'un consultant p Improving the productivity a our le renforcement des capa Individual Consult IDA / 62830 nd resilience of beneficiary p Post Limited 18,018.00 0.00 Under Review 2023-03-06 2023-04-18 2023-03-11 2023-04-01 2023-05-06 2023-07-05 cités sur le zaï, l'utilisation de ant Selection opulations la technologie de microdoses d'engrais/fumure organique ML-PDAZAM-342776-CS-IND V / Service d'un consultant p our le renforcement des capa Improving the productivity a Individual Consult Pending Impleme cités des partenaires des PAP IDA / 62830 nd resilience of beneficiary p Post Limited 18,018.00 0.00 2023-03-01 2023-03-06 2023-03-27 2023-05-01 2023-06-30 ant Selection ntation et introduction d’outils simpl opulations e de gestion comptable, fina ncière et contrôle interne des groupements ML-PDAZAM-342777-CS-IND V / Service d'un consultant p our le renforcement des capa Improving the productivity a Individual Consult Pending Impleme cités des partenaires des PAP IDA / 62830 nd resilience of beneficiary p Post Limited 18,018.00 0.00 2023-03-15 2023-03-20 2023-04-10 2023-05-15 2023-07-14 ant Selection ntation et introduction d’outils simpl opulations e de gestion comptable, fina ncière et contrôle interne des groupements Page 12 ML-PDAZAM-342778-CS-IND V / Service d'un consultant p our la formation des membre Improving the productivity a Individual Consult Pending Impleme s des coopératives et les age IDA / 62830 nd resilience of beneficiary p Post Limited 14,414.00 0.00 2023-05-02 2023-05-07 2023-05-28 2023-07-02 2023-08-31 ant Selection ntation nts des services de l'agricult opulations ure sur les techniques de po se du carré de rendement/de nsité et calcul du revenu agri cole ML-PDAZAM-342790-CS-IND V / Service de consultant pou r la Formation des membres Productive Infrastructure at Individual Consult Pending Impleme du comité de développement IDA / 62830 Post Limited 14,414.00 0.00 2023-04-03 2023-04-08 2023-04-29 2023-06-03 2023-08-02 Community Level ant Selection ntation communautaires(CDC) dans le cadre de la bonne gestion des infrastructures de Produc tion dans les 13 cercles du pr ojet ML-PDAZAM-342791-CS-IND V / Service d'un consultant p Productive Infrastructure at Individual Consult Pending Impleme IDA / 62830 Post Limited 18,018.00 0.00 2023-03-23 2023-03-28 2023-04-18 2023-05-23 2023-07-22 our la mise en place un plan Community Level ant Selection ntation d’alerte multi-niveau ML-PDAZAM-342792-CS-IND V / Service de consultant pou r la Formation des membres du comité de developpement Productive Infrastructure at Individual Consult Pending Impleme IDA / 62830 Post Limited 14,414.00 0.00 2023-04-10 2023-04-15 2023-05-06 2023-06-10 2023-08-09 communautaires(CDC) dans Community Level ant Selection ntation le cadre de la bonne gestion des insfrastructures de Com mercialisation dans les 13 ce rcles du projet ML-PDAZAM-342795-CS-IND V / Service de consultant pou r la tenue de l'atelier sur la S Institutional Support, Crisis ensibilisation des OP et des l Individual Consult Pending Impleme IDA / 62830 Management and Project Co Post Limited 14,414.00 0.00 2023-04-04 2023-04-09 2023-04-30 2023-06-04 2023-08-03 eaders sur le dispositif de la l ant Selection ntation ordination oi sur le genre et la LOA dans les communes partenaires en vue de l’intégration de la pro motion féminine dans leur PD ESC ML-PDAZAM-342796-CS-IND V / Service de consultant po ur la formation en genre (ana Institutional Support, Crisis lyse et intégration) dans les c Individual Consult Pending Impleme IDA / 62830 Management and Project Co Post Limited 14,414.00 0.00 2023-04-12 2023-04-17 2023-05-08 2023-06-12 2023-08-11 ommunes partenaires en vue ant Selection ntation ordination de l’intégration et/ou promoti on féminine dans leur PDESC , à l’intention des autorités c ommunales et communautair es. ML-PDAZAM-357594-CS-IND V / Service d'un consultant p our le renforcement des capa Improving the productivity a cités des groupements de col Individual Consult Pending Impleme IDA / 62830 nd resilience of beneficiary p Post Limited 18,018.00 0.00 2023-04-19 2023-04-24 2023-05-15 2023-06-19 2023-07-19 lecte des amendes et de pro ant Selection ntation opulations duction de beurre de karité s ur les cahiers de charge et d es projets de normes des am endes et du beurre de karité Page 13 REPUBLIQUE DE COTE D'IVOIRE Union - Discipline - Travail -------- MINISTERE DE L’EQUIPEMENT ET DE L’ENTRETIEN ROUTIER -- -- PROJET D’INTEGRATION PORT VILLE DU GRAND ABIDJAN (PACOGA) -------- FONDS DE PREPARATION DU PROJET D’ASSAINISSEMENT ET DE RESILIENCE URBAINE (PARU) CC-PRICI 1 Février 2020 2 PLAN DE PASSATION SIMPLIFIE Plan de passation des marchés – PART BAILLEUR-PPF DU PARU Le présent plan de passation de marchés initial couvre la période de préparation du projet I. Généralités 1.1. Information générale sur le projet Pays: République de Côte d’Ivoire Emprunteur : Gouvernement de Côte d’Ivoire Nom du Projet : Projet d’Assainissement et de résilience urbaine Numéros du Don et du Crédit : Financement de préparation de projet Additionnel Montant du fonds Don et du Crédit : 6 millions de dollars Unité de Gestion du Projet : Ministère de l’Assainissement et de la Salubrité 1.2 Date d’approbation du plan de passation de marchés Plan original : Septembre 2019 1.3 Date de publication de l’avis général de passation de marchés : ………….. 1.4 Période couverte par le Plan de passation des marchés initial : Juillet à décembre 2019 II. Fourniture, Travaux et Services Assimilés 2.1. Seuils d’examen préalable Les marchés qui seront soumis à l'examen préalable de la banque conformément aux dispositions de l'Annexe 1 des Directives de passation de marchés de janvier 2011, révisé en juillet 2014 : Nouveaux seuils de revue de la Banque élaborés en décembre 2012 et proposés au Gouvernement le 05 décembre 2012, révisés en juillet 2016 et liés au niveau de risque du projet. Nature des Méthode de passation de Valeur seuil du Contrats soumis à dépenses marchés marché $EU examen préalable de l’IDA 1. Travaux AOI ≥ 10,000,000 (y compris clés en AON < 10,000,000 Tous les contrats de main, Fourniture et Demande de cotation – 15.000.000 $EU et plus montage < 200,000 au moins 3 offres d’installations et PPP) Entente Directe (*) Pas de seuil 2. Fournitures, AOI ≥ 1,000,000 Systèmes AON < 1,000,000 d’Informations et Services autres que Consultation de Fournisseurs à les services de l’échelle Nationale - Au moins 3 < 100,000 Tous les contrats de Consultants offres 4.000.000 $EU et plus Consultation de Fournisseurs à l’échelle Nationale - Au moins 3 < 500 000 offres pour les véhicules et le carburant Entente directe (*) Pas de seuil (*) Le justificatif de toute entente directe dont le coût estimatif n’atteint pas le seuil de revue préalable de la Banque doit être transmis avec le PPM 3 3.2.1 Type de marchés : Fournitures et travaux Métho Préférenc de Coût e Exam. Ouvertur passati Commentair estimé en P-Q fournisse par e plis on e Liste des ensembles de marchés millier de urs Banque prévue Marché locaux s BAILLEURS Montan t A estimé OUI/NO priori/A Date N° Description OUI/NON En N posterior prévue millier i $ US Coordination et Gestion du 455 projet Aucun équipement n’étant encore A déterminé. Acquisition de biens et 10/11/20 1 455 AON N/A N/A posterior Nous d'équipement 19 i proposons de lancer un AO pour les acquisitions. TOTAL 455 Taux de change utilisé : 550 F CFA=1 $ EU 4 Sélection de Consultants Sélection de Consultants 1. Seuil d’examen préalable Les contrats qui seront soumis à l'examen préalable de la Banque conformément aux dispositions de l'Annexe 1 Les marchés qui seront soumis à l'examen préalable de la banque conformément aux dispositions de l'Annexe 1 des Règlements de Passation de marchés pour les Emprunteurs sollicitant le Financement de projets de juillet 2016 : Nouveaux seuils de revue de la Banque élaborés en décembre 2012 et proposés au Gouvernement le 05 décembre 2012, révisés en juillet 2016 et liés au niveau de risque du projet. Nature Méthode de passation Valeur Contrats soumis de de marchés seuil du à examen dépenses contrat préalable $EU Consultan SFQC1, SFQ2, SMC3, ≥ 300.000 Tout contrat de ts SCBD4, 2.000.000 $EU Firmes SFQC, SFQ, SMC, SCBD, < 300.000 ou plus QC5 Contrat ≥ Sélection par Entente Pas de 100,000$EU Directe (*) seuil Et Audit financier Consultan Consultant Individuel (AMI) ≥ 100.000 Tout contrat de ts 400.000 $ EU ou Individuel Consultant Individuel (3 plus et Contrat du < 100.000 s CV) CAP, SPM et RAF. 1 SFQC : Sélection Fondée sur la Qualité et le Coût 2 SFQ : Sélection Fondée sur la Qualité; SFQ 2 Sélection Fondée sur la Qualité (double enveloppes) 3 SMC : Sélection au Moindre Coût 4 SCBD : Sélection dans le Cadre d’un Budget Déterminé 5 QC : Sélection basée sur les Qualifications des Consultants SCI : Sélection de Consultant Individuel - AMI : Avis à Manifestation d’Intérêt 5 Contrat ≥ Sélection par Entente 100,000 $EU et Pas seuil Directe (*) plus Tous les TDRs, quelle que soit la valeur du contrat, sont de soumis à examen préalable. (*) Le justificatif de toute sélection par entente directe dont le coût estimatif n’atteint pas le seuil de revue préalable de la Banque doit être transmis avec le PPM 2. Liste restreinte composée entièrement de Consultants Nationaux : Liste restreinte de consultants pour prestations de services, d’un coût estimatif inférieur à 300 000$ US ou équivalent par contrat, peut être entièrement composée de Consultants nationaux conformément aux dispositions du paragraphe 2.7 des Directives de Sélection et Emploi de Consultants 6 PROJET D’ASSAINISSEMENT ET DE RESILIENCE URBAINE Montant Ouvertur estimé Exam. par N° Description Méthode de e plis En millier $ Banque Passation prévue Commentaires US Marchés A priori/A Date prévue posteriori Composante 1 : Infrastructures I grises et vertes pour la réduction du 1 546 risque d’inondation Etudes de faisabilité et études techniques pour les En attente des TDR de 1 travaux de drainage et travaux routiers associés 1 152 SFQ A postériori 29/03/2020 l’ONAD Etude pour la mise en place d’une stratégie En attente des TDR de 2 d’entretien des ouvrages 50 SFQ A postériori 29/03/2020 l’ONAD (O&M) Recrutement d’un Consultant Individuel pour Contrat attribué au l’actualisation des études APD pour les travaux Consultant COULIBALY 3 de drainage des eaux pluviales et préparation 69,09 CI (AMI) A posteriori 25/11/2019 Seydou (38 000 000 du DAO de la ville de Bouaké FCFA), et en cours d’exécution Recrutement d’un Consultant Individuel pour 4 CV en cours l’actualisation des études APD pour les travaux 4 69,09 CI (AMI) A posteriori 25/11/2019 d’évaluation par la de drainage des eaux pluviales et préparation COJO. du DAO de la ville de Grand-Bassam Recrutement d’un Consultant Individuel pour Contrat attribué au l’actualisation des études APD pour les travaux 25/11/2019 Consultant OGA 5 69,09 CI (AMI) A posteriori de drainage des eaux pluviales et préparation Dominique (38 000 000), du DAO à Anonkoi Kouté/commune d’Abobo et en cours d’exécution 7 Recrutement d’une firme pour l’actualisation Contrat attribué au des études APD pour les travaux de drainage cabinet STUDI 6 des eaux pluviales et préparation du DAO à 184,43 QC A posteriori 20/01/2020 International Gesco dans la commune de Yopougon (101 435 455 FCFA) et en cours d’exécution TDR transmis 24/10/2019 et en attente Recrutement d’une firme pour l’Etude d’Impact de l’ANO de la Banque. Environnementale et Sociale (EIES) du projet 7 51,00 QC A posteriori 10/10/2019 L’activité ne fait plus d’aménagement de la cuvette de la GESCO et parti de celles devant Port-Bouet II passer au CA de Banque mondiale. Contrat exécuté par le Recrutement d’une firme pour l’Etude d’Impact cabinet SEM Environnementale et Sociale (EIES) du projet de INTERNATIONAL 8 36,85 QC A posteriori 17/10/2019 construction des ouvrages de drainage des eaux (20 270 000 FCFA) et le pluviales à Anonkoua, Abobo. CIES transmis à la Banque pour ANO. Contrat exécuté par le Recrutement d’une firme pour l’Etude d’Impact cabinet SERF BURKINA Environnementale et Sociale (EIES) du projet de 9 70,73 QC A posteriori 10/11/2019 (38 900 000 FCFA) et construction des ouvrages de drainage des eaux l’EIES transmis à la pluviales de Grand-Bassam Banque pour ANO Contrat exécuté par le Recrutement d’une firme pour l’Etude d’Impact cabinet NATRA Environnementale et Sociale (EIES) du projet de CONSULTANT 10 46,72 QC A posteriori 17/10/2019 construction des ouvrages de drainage des eaux (25 694 600 FCFA) et pluviales de Bouaké l’EIES transmis à la Banque pour ANO A la demande de la Banque, la procédure a Recrutement d’un Consultant Individuel pour CI été suspendue car l’élaboration du Plan d’Action et de Réinstallation des 11 18 A posteriori 25/11/2019 l’activité ne fait plus personnes affectée par le projet d’aménagement de la parti de celles devant cuvette de GESCO passer au CA de la Banque mondiale. Contrat exécuté Recrutement d’un Consultant Individuel pour (29 500 000 FCFA) par le l’élaboration du Plan d’Action et de Consultant LOMPO 12 Réinstallation des personnes affectée par de 53,64 CI A posteriori 18/11/2019 Gabriel et le Rapport du construction des ouvrages de drainage des eaux PAR transmis à l’ANO de pluviales de Grand-Bassam la Banque 8 Contrat exécuté Recrutement d’un Consultant Individuel pour (26 610 000 FCFA) par le l’élaboration du Plan d’Action et de Consultant KOUASSI 13 Réinstallation des personnes affectée par le 48,38 CI A posteriori 18/11/2019 N’Guesssan Pierre et le projet de construction des ouvrages de drainage Rapport du PAR transmis des eaux pluviales à Anonkoua Kouté, Abobo à l’ANO de la Banque. Contrat exécuté Recrutement d’un Consultant Individuel pour (25 200 000 Fcfa) par le l’élaboration du Plan d’Action et de Consultant KOFFI 14 Réinstallation des personnes affectée par projet 45,82 CI A posteriori 18/11/2019 Harouna et le Rapport du de construction des ouvrages de drainage des PAR transmis à l’ANO de eaux pluviales de Bouaké la Banque Recrutement d’une ONG pour l’accompagnement du QC TDR retransmis à la 15 PAR du projet d’aménagement de la cuvette de GESCO 4 A posteriori 25/02/2020 Banque pour ANO dans la commune de Yopougon Recrutement d’une ONG pour l’accompagnement des 16 PAR du projet d’aménagement de la cuvette 4 QC A posteriori 27/02/2020 En attente des TDR. d’Anonkoua Kouté dans la commune de d’Abobo. Recrutement d’une ONG pour l’accompagnement des 17 PAR du projet d’aménagement des ouvrages de 4 QC A posteriori 27/02/2020 En attente des TDR drainage des eaux pluviales de Bouaké Recrutement d’une ONG pour l’accompagnement des 18 PAR du projet d’aménagement des ouvrages de 4 QC A posteriori 27/02/2020 En attente des TDR drainage des eaux pluviales de Grand Bassam Composante 2 : Amélioration du II système de gestion et de 2 850 valorisation des déchets solides 26/03/2020 TDR validé le 4/12/2019 par la Banque. Equipe STEP transmis depuis le Etude de faisabilité technique du projet d’optimisation 20/12/2019 à la Banque. et de gestion des déchets solides dans le district En attente du 19 750 SFQ A priori autonome d’Abidjan et du mode de contractualisation paramétrage du STEP du des infrastructures dans le cadre d’un PPP. PARU pour permettre la publication des AMI sur UNBD et sur le site de la Banque 9 26/03/2020 TDR validé le 4/12/2019 par la Banque. Equipe Etude de faisabilité technique du projet de STEP transmis depuis le modernisation et de gestion intercommunale des 20/12/2019 à la Banque. déchets solides des villes de Toumodi, En attente du 20 650 SFQ A posteriori Yamoussoukrou, Tiebissou, Djebonoua, Bouaké et du paramétrage du STEP du mode de contractualisation des infrastructures avec le PARU pour permettre la secteur privé. publication des AMI sur UNBD et sur le site de la Banque 26/03/2020 TDR validé le 4/12/2019 par la Banque. Equipe Etude de faisabilité technique du projet de STEP transmis depuis le modernisation et de gestion intercommunale des 20/12/2019 à la Banque. déchets solides des villes de Korhogo, Sinematiali, En attente du 21 600 SFQ A posteriori Ferkessedougou et Ouangolodougou, et du mode de paramétrage du STEP du contractualisation des infrastructures avec le secteur PARU pour permettre la privé. publication des AMI sur UNBD et sur le site de la Banque 26/03/2020 TDR validé le 4/12/2019 par la Banque. Equipe STEP transmis depuis le Etude de faisabilité de gestion intercommunale des 20/12/2019 à la Banque. En attente du 22 déchets solides des villes de Blolequin, Guiglo et 200 SFQC A posteriori paramétrage du STEP du Duékoue. PARU pour permettre la publication des AMI sur UNBD et sur le site de la Banque Etude sur le développement des filières de recyclage TDR transmis le 23 et de valorisation de déchets dans le district autonome 300 SFQ2 A posteriori 26/03/2020 21/01/2020 à la Banque d’abidjan pour ANO TDR validé par la banque, AMI en cours de Etude du financement durable, de la viabilité publication sur UNBD et 24 économique et des réformes fiscales de la gestion des 350 SFQ2 A posteriori 27/02/2020 sur le site de la Banque. déchets solides en Côte d’Ivoire Ouverture des plis fixée au 27/02/2020 à 10h30mn Composante 3 : Renforcement des III capacités et technologies numériques 400 pour la résilience urbaines 10 Etats des lieux sur les capacités. cadres institutionnels. données et systèmes disponibles sur les technologies digitales pour la résilience urbaine et 10/04/2020 25 200,00 SFQ2 A priori En attente des TDR délivrer une feuille de route et étude de faisabilité et conception pour la préparation des DAO pour les systèmes numériques Recrutement d’un Consultant/Firme pour les études de faisabilité et conception détaillée y compris la 26 200,00 SFQ2 A priori 10/04/2020 En attente des TDR préparation des DAO pour le système d'alerte précoce aux inondations IV Composante 4 : Gestion du projet 713 Contrat exécuté Recrutement d’un Consultant Individuel pour (28 690 000 FCFA) par 27 l’élaboration du CGES du Projet 52,16 CI A posteriori 15/10/2019 Monsieur ZARE Adama et le d’Assainissement et de Résilience Urbaine CGES validé en cours de publication au plan national Contrat exécuté Recrutement d’un consultant individuel pour (21 910 000 FCFA) par 28 l’élaboration du CPR du Projet de Résilience 39,84 CI A posteriori 05/10/2019 Monsieur LOMPO Gabriel et Urbaine le CPR transmis le à la Banque pour ANO Recrutement d’un Consultant Individuel pour En attente des TDR. l’élaboration des Mécanismes de Gestion des Plaintes 29 20 CI A posteriori 29/03/2020 Activité à élaborer en (GRM) du Projet d’Assainissement et de Résilience régie par la CC-PRICI Urbaine Recrutement d’un Consultant individuel pour l’appui à Reprise du processus de 30 la Task-Force pour l’élaboration du PPSD du PARU 19 CI A posteriori 130/02/2020 recrutement du CI après objection sur le 1er recrutement 24 dossiers de candidatures reçus. En 31 Appui à la gestion du projet – Chef de projet 60 CI (AMI) A priori 31/01/2020 cours d’évaluation par le panel MINASS 14 dossiers de Appui à la gestion du projet – Spécialiste en candidatures reçus. En 32 50 CI(AMI) A priori 17/01/2020 sauvegarde environnementale cours d’évaluation par le panel MINASS 06 dossiers de Appui à la gestion du projet – Spécialiste en candidatures reçus. En 33 50 CI(AMI) A priori 17/01/2020 sauvegarde sociale et genre cours d’évaluation par le panel MINASS 11 Appui à la gestion du projet – Spécialiste en En attente des TDR du 34 50 CI(AMI) A priori 15/05/2020 numérique MINASS 37 dossiers de Appui à la gestion du projet – Spécialiste en gestion candidatures reçus. En 35 50 CI(AMI) A priori 21/01/2020 financière cours d’évaluation par le panel MINASS 101 dossiers de candidatures reçus. En 36 Appui à la gestion du projet – Comptable 50 CI(AMI) A posteriori 21/01/2020 cours d’évaluation par le panel MINASS 11 dossiers de Appui à la gestion du projet – Spécialiste en passation candidatures reçus. En 37 50 CI(AMI) A priori 17/01/2020 de marchés cours d’évaluation par le panel MINASS Appui à la gestion du projet – Ingénieur de drainage En attente des TDR de 38 50 CI(AMI) A priori 08/04/2020 urbain l’ONAD En attente des TDR du 39 Appui à la gestion du projet – Spécialiste déchets 50 CI(AMI) A priori 08/04/2020 MINASS Appui à la gestion du projet – Spécialiste en 08/04/2020 En attente des TDR de la 40 communication/ marketing social et développement 50 CI(AMI) A posteriori CC-PRICI communautaire Appui à la gestion du projet - élaboration manuel 08/04/2020 En attente des TDR du 41 30 CI (AMI) A Postériori d'opérations MINASS TOTAL CONSULTANTS 5 509 N.B : Taux de change utilisé : 550 F CFA=1 $ EU 12 IV : RENFORCEMENT DE CAPACITE Dans cette section, lister les activités de renforcement de capacités approuvées et leur planning Réf. Montant Durée Date No Description estimatif estimée de Commentaires du contrat en millier (jours) début de $EU Atelier Atelier de Mars regroupement la 1 validation du 5 7 task force pour la PPSD du 2020 validation du projet PARU PPSD Atelier regroupant Atelier de Février toutes les parties 2 validation des 11 5 prenantes pour 2020 CGES et CPR la validation des documents cadres Atelier regroupant Atelier de Mars 3 6 toutes les parties validation des 18 2020 prenantes pour PAR la validation des PAR TOTAL 36 NB: 1$ USD =550 FCFA 13 V. RECAPITULATION V.1. Financement PPF du PARU_BAILLEUR Commenta Nombre Montant estimatif N° ires Composante/ Catégories ordre en millier F en milier Contrats CFA de $ EU Composante 1 : Infrastructures grises 1 et vertes pour la 18 850 300 1 546 réduction du risque d’inondation Travaux et fournitures par AOI 0 0 0 Travaux et fournitures par AON 0 0 0 Consultants 18 850 300 1 546 Composante 2 : Amélioration du 2 système de gestion 6 1 567 500 2 850 et de valorisation des déchets solides Travaux et fournitures par AOI 0 0 0 Travaux et fournitures par AON 0 0 0 Consultation de fournisseur 0 0 0 Consultants 6 1 567 500 2 850 Composante 3 : Renforcement des 3 capacités et 2 220 000 400 technologies numériques pour la résilience urbaines Travaux et fournitures par AOI 0 0 0 Travaux et fournitures par AON 0 0 0 Consultants 2 220 000 400 4 Composante 4 : 19 662 200 1 204 Gestion du Projet Travaux et fournitures par AOI 0 0 0 Travaux et fournitures par AON 1 250 250 455 Consultants 18 411 950 749 TOTAL 45 3 300 000 6 000 14 15 PROCUREMENT Cote d'Ivoire : Urban Resilience and Solid Waste Management Project PLAN General Information Country: Cote d'Ivoire 2020-02-11 Bank’s Approval Date of the Original Procurement Plan: Revised Plan Date(s): (comma delineated, leave blank2023-06-06 if none) Project ID: P168308 GPN Date: 2021-01-05 Project Name: Urban Resilience and Solid Waste Management Project Loan / Credit No: / , IDA / V2850, IDA / 66860 URBAN SANITATION AND RESILIENCE PROJECT Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process S Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Comple Description Component Review Type Method Amount (U ount (US$ and Recommendatio Signed Contract o. h cess (Y/N) isk ocument Type tatus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes tion S$) ) n for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned CI-PARU-205845-CW-RFQ / Component 3: Project mana Request for Quot Single Stage - One 2021-02-2 Travaux d'aménagement de IDA / 66860 Post Limited 18,340.00 11,923.41 Signed 2020-12-02 2020-12-22 2021-01-27 2021-07-01 gement ations Envelope 6 s locaux de l'UGP/PARU CI-PARU-213153-CW-RFB / Recrutement d'une entrepris Component 1: Flood risk mi Open - Internation Single Stage - One 35,106,710. 2021-11-2 e pour la réalisation des trav IDA / 66860 tigation infrastructure and s Prior Request for Bids 0.00 Canceled 2021-02-01 2021-02-06 2021-03-20 2021-04-19 2021-05-24 al Envelope 00 0 aux de construction des ouv ervices rages de drainages des eau x pluviales de Grand-Bassa m CI-PARU-213918-CW-RFQ / Recrutement d'une entrepris e pour l'Implantation d'emp Component 1: Flood risk mi Pending Im Request for Quot Single Stage - One 2021-09-1 rises de collecteurs dans le IDA / 66860 tigation infrastructure and s Post Limited 32,000.00 0.00 plementatio 2021-01-26 2021-03-23 ations Envelope 9 cadre des travaux de constr ervices n uctions d'ouvrages de drain ages dans les zones de BAS SAM et ABOBO CI-PARU-231675-CW-RFB / Recrutement d'une entrepris Request for Bids Component 1: Flood risk mi e pour la réalisation des trav Open - Internation Single Stage - One - Works (without 24,800,000. 13,587,429. 2022-02-2 IDA / 66860 tigation infrastructure and s Prior Request for Bids Signed 2021-05-04 2021-05-03 2021-05-09 2021-08-03 2021-06-20 2021-09-20 2021-07-20 2022-05-09 2021-08-24 2022-04-16 aux de construction des ouv al Envelope prequalification) 00 78 0 ervices rages de drainage des eaux SPD pluviales de Anonkoua-kout é commune d'Abobo CI-PARU-236812-CW-RFB / Recrutement d'entreprise po Request for Bids Component 1: Flood risk mi Pending Im ur l'exécution des travaux d' Open - Internation Single Stage - One - Works (without 13,277,311. 2022-04-0 IDA / 66860 tigation infrastructure and s Post Request for Bids 0.00 plementatio 2021-06-15 2021-06-20 2021-08-01 2021-08-31 2021-10-05 aménagement des deux cuv al Envelope prequalification) 00 3 ervices n ettes d'Anonkoua et Agouett SPD o et travaux routiers associé s d'Abobo CI-PARU-283899-CW-RFB / Request for Bids Travaux de construction d'o Component 1: Flood risk mi Open - Internation Single Stage - One - Works French Ci 14,943,552. Under Impl 2023-01-1 uvrages de drainages des e IDA / 66860 tigation infrastructure and s Post Request for Bids 0.00 2022-03-30 2022-04-12 2022-04-04 2022-04-12 2022-05-16 2022-05-31 2022-06-15 2022-06-21 2022-07-20 al Envelope vil Law (French) 00 ementation 6 aux pluviales à Gesco, route ervices SPD de Dabou dans la commune de Yopougon CI-PARU-213154-CW-RFB / Recrutement d'une entrepris Component 1: Flood risk mi e pour la réalisation des trav Open - Internation Single Stage - One 30,195,917. 2021-11-2 IDA / 66860 tigation infrastructure and s Prior Request for Bids 0.00 Canceled 2021-02-01 2021-02-06 2021-03-20 2021-04-19 2021-05-24 aux de construction des ouv al Envelope 00 0 ervices rages de drainage des eaux pluviales de Anonkoua-kout é commune d'Abobo CI-PARU-312006-CW-RFB / Request for Bids Recrutement d'une entrepris Component 1: Flood risk mi Open - Internation Single Stage - One - Works (without 19,500,000. Under Impl 2023-07-0 e pour la construction des o IDA / 66860 tigation infrastructure and s Post Request for Bids 0.00 2022-09-12 2022-09-05 2022-09-17 2022-09-05 2022-10-29 2022-10-27 2022-11-28 2023-02-06 2023-01-02 al Envelope prequalification) 00 ementation 1 uvrages de drainages des e ervices SPD aux pluviales dans la comm une de Grand-Bassam CI-PARU-348029-CW-RFB / Recrutement d'entreprise po Request for Bids ur l'exécution des travaux d' Component 1: Flood risk mi Pending Im Open - Internation Single Stage - One - Works French Ci 13,610,570. 2024-01-2 aménagement d'ouvrages d IDA / 66860 tigation infrastructure and s Post Request for Bids 0.00 plementatio 2023-04-03 2023-04-08 2023-05-20 2023-06-19 2023-07-24 al Envelope vil Law (French) 00 0 e drainage des eaux pluviale ervices n SPD s dans le bassin versant de M'pouto dans la commune d e Cocody CI-PARU-348047-CW-RFB / Request for Bids Recrutement d'une entrepris Component 1: Flood risk mi Pending Im Open - Internation Single Stage - One - Works French Ci 14,000,000. 2024-03-1 e pour l'exécution des trava IDA / 66860 tigation infrastructure and s Post Request for Bids 0.00 plementatio 2023-06-01 2023-06-06 2023-07-18 2023-08-17 2023-09-21 al Envelope vil Law (French) 00 9 ux d'aménagement du bassi ervices n SPD n versant des rosiers a Coco dy CI-PARU-348066-CW-RFB / Recrutement d'une entrepris Request for Bids Component 1: Flood risk mi Pending Im e pour l'exécution des trava Open - Internation Single Stage - One - Works French Ci 10,000,000. 2024-08-1 IDA / 66860 tigation infrastructure and s Post Request for Bids 0.00 plementatio 2023-11-01 2023-11-06 2023-12-18 2024-01-17 2024-02-21 ux de protection et de végét al Envelope vil Law (French) 00 9 ervices n alisation des talus des quarti SPD ers Gbebouto et Bidjantè da ns la commune d'Attécoubé CI-PARU-350140-CW-RFQ / Recrutement d'une entrepris Component 1: Flood risk mi Request for Quot e pour la réalisation des trav Request for Quot Single Stage - One Under Impl 2023-12-0 IDA / 66860 tigation infrastructure and s Post Limited ations (Non Bank 12,000.00 0.00 2023-04-17 2022-09-23 2023-06-12 aux d'implantation des empr ations Envelope ementation 9 ervices -SPD) ises des travaux de construc tion d'ouvrages de drainage s dans la commune de Yopo ugon CI-PARU-348053-CW-RFB / Recrutement d'une entrepris Request for Bids Component 1: Flood risk mi Pending Im e pour les travaux de constr Open - Internation Single Stage - One - Works French Ci 30,906,031. 2024-07-0 IDA / 66860 tigation infrastructure and s Prior Request for Bids 0.00 plementatio 2023-09-20 2023-09-25 2023-11-06 2023-12-06 2024-01-10 uction des ouvrages de drai al Envelope vil Law (French) 00 8 ervices n nage des eaux pluviales de SPD Bonoumin dans la commune de Cocody GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendatio Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes n for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CI-PARU-195859-GO-RFQ / Component 3: Project mana Request for Quot Single Stage - One Acquisition de fourniture de IDA / 66860 Post Limited 9,100.00 13,536.88 Signed 2020-10-10 2021-01-19 2020-12-05 2021-09-23 2021-06-03 gement ations Envelope bureau pour la CC-PARU CI-PARU-195865-GO-DIR / M arché par Entente Directe a Component 3: Project mana Under Imple vec AGOSOFT pour la fournit IDA / 66860 Post Direct Selection Direct 51,421.00 0.00 2020-10-01 2021-01-21 2020-10-06 2020-11-10 2021-05-09 gement mentation ure de logiciels TOM PRO; T OM PAIE et TOM MARCHE po ur la CC-PARU. CI-PARU-205208-GO-RFQ / Component 3: Project mana Request for Quot Single Stage - One Acquisition de matériels roul IDA / 66860 Post Limited 100,000.00 77,234.50 Signed 2020-11-29 2021-01-18 2021-01-24 2021-04-15 2021-07-23 gement ations Envelope ant pour le PARU Page 1 CI-PARU-205832-GO-RFQ / Component 3: Project mana Request for Quot Single Stage - One Acquisition de matériels info IDA / 66860 Post Limited 29,091.00 40,712.34 Signed 2020-12-05 2020-12-02 2021-01-30 2021-04-24 2021-03-01 gement ations Envelope rmatiques pour l'UCP CI-PARU-205833-GO-RFQ / Component 3: Project mana Request for Quot Single Stage - One Acquisition de fourniture et IDA / 66860 Post Limited 9,680.00 10,258.71 Signed 2020-12-02 2020-12-02 2021-01-27 2021-04-15 2021-02-26 gement ations Envelope petits matériels techniques pour l'UCP CI-PARU-205834-GO-RFQ / Component 3: Project mana Request for Quot Single Stage - One Acquisition de mobilier de b IDA / 66860 Post Limited 44,810.00 39,352.72 Completed 2020-12-02 2020-12-10 2021-01-27 2021-04-15 2021-02-26 2021-07-14 gement ations Envelope ureau pour l'UCP CI-PARU-205835-GO-RFQ / F Component 3: Project mana Request for Quot Single Stage - One ournitures de consommable IDA / 66860 Post Limited 7,260.00 32,656.34 Signed 2020-12-05 2021-03-04 2021-01-30 2021-05-21 2021-03-01 gement ations Envelope s informatiques pour l'UCP CI-PARU-205836-GO-RFQ / Component 3: Project mana Request for Quot Single Stage - One Pending Impl Acquisition de matériel de b IDA / 66860 Post Limited 6,040.00 0.00 2020-12-05 2021-01-30 2021-03-01 gement ations Envelope ementation ureau pour l'UCP CI-PARU-213965-GO-RFQ / Component 3: Project mana Request for Quot Single Stage - One Under Imple Acquisition des autocoms nu IDA / 66860 Post Limited 6,515.00 0.00 2021-02-01 2022-10-28 2021-03-29 2021-09-25 gement ations Envelope mentation mériques et postes téléphon iques pour l'UCP CI-PARU-213968-GO-RFQ / Component 3: Project mana Request for Quot Single Stage - One Pending Impl Acquisition de matériels d'ét IDA / 66860 Post Limited 2,000.00 0.00 2021-02-03 2021-03-31 2021-09-27 gement ations Envelope ementation iquetages des immobilisatio ns CI-PARU-213969-GO-RFQ / F Component 3: Project mana Request for Quot Single Stage - One IDA / 66860 Post Limited 21,000.00 18,787.55 Signed 2021-02-03 2021-02-09 2021-03-31 2021-05-12 2021-09-27 ourniture de carburant gement ations Envelope CI-PARU-217852-GO-RFQ / Equipement de la salle de ré Component 3: Project mana Request for Quot Single Stage - One IDA / 66860 Post Limited 60,000.00 64,467.13 Signed 2021-02-22 2021-03-04 2021-04-19 2021-09-22 2021-05-19 union du PARU en appareil gement ations Envelope multimédia média et de visi oconférence CI-PARU-236683-GO-RFQ / Component 3: Project mana Request for Quot Single Stage - One Acquisition de logiciels tech IDA / 66860 Post Limited 14,080.00 0.00 Canceled 2021-06-19 2021-08-14 2022-02-10 gement ations Envelope niques (Géomensura, Autoc ad 2020) CI-PARU-236691-GO-RFQ / Acquisition de matériels aud Component 3: Project mana Request for Quot Single Stage - One Under Imple iovisuels pour le Projet (app IDA / 66860 Post Limited 5,000.00 0.00 2021-06-26 2022-10-17 2021-08-21 2022-02-17 gement ations Envelope mentation areil photo, caméra, kit lumi ère, trépieds micro-cravate, dictaphone, Camlight…) CI-PARU-246689-GO-RFQ / Component 3: Project mana Request for Quot Single Stage - One Acquisition d'un groupe élec IDA / 66860 Post Limited 30,000.00 0.00 Signed 2021-08-16 2021-06-07 2021-10-11 2022-04-09 gement ations Envelope trogène pour le PARU CI-PARU-252855-GO-RFQ / Component 3: Project mana Request for Quot Single Stage - One Acquisition de fournitures de IDA / 66860 Post Limited 10,000.00 12,425.20 Signed 2021-11-03 2021-01-19 2021-12-29 2021-09-23 2022-06-27 gement ations Envelope bureau pour le PARU CI-PARU-252863-GO-RFQ / Component 3: Project mana Request for Quot Single Stage - One Under Imple Acquisition de consommable IDA / 66860 Post Limited 10,000.00 0.00 2021-11-30 2022-09-09 2022-01-25 2022-07-24 gement ations Envelope mentation s informatiques pour le PAR U CI-PARU-290522-GO-RFQ / Component 3: Project mana Request for Quot Single Stage - One Acquisition de matériels roul IDA / 66860 Post Limited 100,000.00 15,511.70 Signed 2022-06-13 2022-01-12 2022-08-08 2022-05-26 2023-02-04 gement ations Envelope ants au titre de la gestion 2 022 CI-PARU-290526-GO-RFQ / Component 3: Project mana Request for Quot Single Stage - One Under Imple Acquisition de carburant po IDA / 66860 Post Limited 20,000.00 0.00 2022-05-17 2022-01-11 2022-07-12 2023-01-08 gement ations Envelope mentation ur l'UC-PARU au titre de la g estion 2022 CI-PARU-290528-GO-RFQ / Component 3: Project mana Request for Quot Single Stage - One Acquisition de consommable IDA / 66860 Post Limited 14,000.00 7,663.18 Signed 2022-06-20 2022-04-29 2022-08-15 2022-06-23 2023-02-11 gement ations Envelope s informatiques au titre de l a gestion 2022 CI-PARU-290610-GO-RFQ / Acquisition de fourniture de Component 3: Project mana Request for Quot Single Stage - One Under Imple IDA / 66860 Post Limited 10,000.00 0.00 2022-05-30 2022-06-28 2022-07-25 2023-01-21 bureau pour le compte de l' gement ations Envelope mentation UC-PARU au titre de la gesti on 2022 CI-PARU-290663-GO-RFQ / Component 3: Project mana Request for Quot Single Stage - One Acquisition de fournitures et IDA / 66860 Post Limited 5,000.00 8,721.78 Signed 2022-05-21 2020-12-02 2022-07-16 2021-09-16 2023-01-12 gement ations Envelope petits matériels techniques CI-PARU-290767-GO-RFQ / Component 3: Project mana Request for Quot Single Stage - One Pending Impl IDA / 66860 Post Limited 24,000.00 0.00 2022-07-04 2022-08-29 2023-02-25 Acquisition d'un drone RTK gement ations Envelope ementation CI-PARU-348506-GO-RFQ / Component 3: Project mana Request for Quot Single Stage - One Pending Impl Acquisition de carburant au IDA / 66860 Post Limited 40,000.00 0.00 2023-04-24 2023-06-19 2023-12-16 gement ations Envelope ementation titre de la gestion 2023 CI-PARU-350072-GO-RFQ / Component 3: Project mana Request for Quot Single Stage - One Pending Impl Acquisition de consommable IDA / 66860 Post Limited 60,000.00 0.00 2023-05-07 2023-07-02 2023-12-29 gement ations Envelope ementation s informatiques au titre de l a gestion 2023 CI-PARU-350083-GO-RFQ / Acquisition de fournitures de Component 3: Project mana Request for Quot Single Stage - One Pending Impl IDA / 66860 Post Limited 60,000.00 0.00 2023-06-06 2023-08-01 2024-01-28 bureau pour l'UC-PARU au ti gement ations Envelope ementation tre de la gestion 2023 CI-PARU-350092-GO-RFQ / Acquisition de matériel de b Component 3: Project mana Request for Quot Single Stage - One Pending Impl IDA / 66860 Post Limited 20,000.00 0.00 2023-05-07 2023-07-02 2023-12-29 ureau pour l'UC-PARU au titr gement ations Envelope ementation e de la gestion 2023 CI-PARU-350100-GO-RFQ / Production des outils et sup ports de communication pou Component 3: Project mana Request for Quot Single Stage - One Under Imple IDA / 66860 Post Limited 40,000.00 0.00 2023-04-08 2023-03-29 2023-06-03 2023-11-30 r les campagnes de commu gement ations Envelope mentation nication et de sensibilisation du PARU au titre de la gestio n 2023 CI-PARU-350118-GO-RFQ / Acquisition de matériels info Component 3: Project mana Request for Quot Single Stage - One Pending Impl IDA / 66860 Post Limited 20,000.00 0.00 2023-06-06 2023-08-01 2024-01-28 rmatiques pour les agences gement ations Envelope ementation d'exécution de l'UC-PARU au titre de la gestion 2023 CI-PARU-350125-GO-RFQ / Acquisition de matériels info Component 3: Project mana Request for Quot Single Stage - One Pending Impl rmatiques pour le renforcem IDA / 66860 Post Limited 20,000.00 0.00 2023-07-08 2023-09-02 2024-02-29 gement ations Envelope ementation ent des capacités de l'ANAG ED et de l'ONAD au titre de l a gestion 2023 CI-PARU-350128-GO-RFQ / Acquisition des équipements Component 3: Project mana Request for Quot Single Stage - One Pending Impl informatiques pour la salle s IDA / 66860 Post Limited 100,000.00 0.00 2023-05-07 2023-07-02 2023-12-29 gement ations Envelope ementation erveur du PARU (Rack, Serv eurs, onduleurs, switch, câbl age) au titre de la gestion 2 023 Page 2 CI-PARU-350130-GO-RFQ / Acquisition d'un switch infor Component 3: Project mana Request for Quot Single Stage - One Pending Impl matique pour la connexion fi IDA / 66860 Post Limited 5,000.00 0.00 2023-07-08 2023-09-02 2024-02-29 gement ations Envelope ementation laires dans les bureaux de l' UC-PARU au titre de la gesti on 2023 CI-PARU-350132-GO-RFQ / Acquisition d'un écran intera ctif et des outils multimédia Component 3: Project mana Request for Quot Single Stage - One Pending Impl IDA / 66860 Post Limited 50,000.00 0.00 2023-07-08 2023-09-02 2024-02-29 (sonorisation+camera pour l gement ations Envelope ementation es web conférence) pour la seconde salle de réunion du PARU au titre de la gestion 2 023 CI-PARU-350134-GO-RFQ / Acquisition des équipements de sécurité incendie du bâti Component 3: Project mana Request for Quot Single Stage - One Pending Impl IDA / 66860 Post Limited 10,000.00 0.00 2023-05-07 2023-07-02 2023-12-29 ment (Extincteurs, détecteur gement ations Envelope ementation s dans les salles spécifiques) de l'UC-PARU au titre de la g estion 2023 CI-PARU-350135-GO-RFQ / Acquisition des EPI complém Component 3: Project mana Request for Quot Single Stage - One Pending Impl IDA / 66860 Post Limited 10,000.00 0.00 2023-05-07 2023-07-02 2023-12-29 entaires pour l'UC-PARU au t gement ations Envelope ementation itre de la gestion 2023 CI-PARU-348502-GO-RFQ / Component 3: Project mana Request for Quot Single Stage - One Pending Impl Acquisition de véhicules pou IDA / 66860 Post Limited 120,000.00 0.00 2023-09-18 2023-11-13 2024-05-11 gement ations Envelope ementation r le compte du PARU au titre de l'année 2023 CI-PARU-363276-GO-RFP / A cquisition d'un bus interactif Component 2: Improvemen d'éducation aux bonnes prat t of solid waste manageme Request for Propo Single Stage - Two Pending Impl iques d'assainissement et d IDA / 66860 Post Limited 240,000.00 0.00 2023-06-12 2023-06-17 2023-07-29 2023-10-11 2023-11-15 2024-05-13 nt infrastructure and servic sals Envelope ementation e Gestion durable des déche es ts dans toutes les écoles des régions bénéficiaires du proj et dans le DAA d'Abidjan NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendatio Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes n for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CI-PARU-195872-NC-RFQ / F Component 3: Project mana Request for Quot Single Stage - One ourniture des services d'ass IDA / 66860 Post Limited 15,200.00 0.00 Canceled 2020-12-02 2021-01-27 2021-07-26 gement ations Envelope urance maladie du personne l de la CC-PARU CI-PARU-195878-NC-RFQ / F ourniture d'assurance multi Component 3: Project mana Request for Quot Single Stage - One Pending Impl IDA / 66860 Post Limited 10,000.00 0.00 2020-11-01 2020-12-27 2021-06-25 risque professionnel pour le gement ations Envelope ementation s locaux de la CC-PARU CI-PARU-195882-NC-RFQ / S Component 3: Project mana Request for Quot Single Stage - One ervice de gardiennage des l IDA / 66860 Post Limited 13,000.00 10,009.60 Signed 2020-12-05 2020-12-08 2021-01-30 2021-06-17 2021-07-29 gement ations Envelope ocaux de la CC-PARU CI-PARU-196009-NC-DIR / C Component 3: Project mana Pending Impl ontrat de bail pour les locau IDA / 66860 Post Direct Selection Direct 72,000.00 0.00 2020-09-30 2020-10-05 2020-11-09 2021-05-08 gement ementation x de la Cellule de Coordinati on du PARU CI-PARU-205837-NC-RFQ / A ssurance maladie du person Component 3: Project mana Request for Quot Single Stage - One IDA / 66860 Post Limited 40,000.00 29,114.81 Completed 2020-12-02 2021-01-18 2021-01-27 2021-04-24 2021-02-26 2022-03-31 nel pour un an pour un effec gement ations Envelope tif de 18 personnes (et famil le) CI-PARU-205838-NC-RFQ / A Component 3: Project mana Request for Quot Single Stage - One ssurances tous risques du m IDA / 66860 Post Limited 8,400.00 25,249.79 Signed 2020-12-02 2021-01-18 2021-01-27 2021-02-24 2021-02-26 gement ations Envelope atériel roulant pour un an CI-PARU-205840-NC-RFQ / C Component 3: Project mana Request for Quot Single Stage - One Pending Impl IDA / 66860 Post Limited 4,000.00 0.00 2021-01-10 2021-03-07 2021-03-27 ontrat d'entretien du matéri gement ations Envelope ementation el roulant CI-PARU-205841-NC-RFQ / E ntretien et reparation des sp Component 3: Project mana Request for Quot Single Stage - One Pending Impl IDA / 66860 Post Limited 15,000.00 0.00 2020-12-06 2021-01-31 2021-03-02 lits du PARU y compris les p gement ations Envelope ementation etits travaux de plomberie e t d´électricité CI-PARU-205842-NC-RFQ / S Component 3: Project mana Request for Quot Single Stage - One élection d'un prestataire po IDA / 66860 Post Limited 30,000.00 11,387.49 Signed 2020-12-05 2021-03-11 2021-01-30 2021-06-02 2021-03-01 gement ations Envelope ur l'entretien des locaux de l 'UCP/PARU CI-PARU-205844-NC-RFQ / E Component 3: Project mana Request for Quot Single Stage - One IDA / 66860 Post Limited 15,000.00 9,300.26 Signed 2020-12-20 2021-06-25 2021-02-14 2021-12-29 2021-02-17 ntretien du matériel informa gement ations Envelope tique CI-PARU-213972-NC-RFQ / S Component 3: Project mana Request for Quot Single Stage - One Under Imple élection d'un prestataire po IDA / 66860 Post Limited 44,000.00 0.00 2021-02-02 2021-06-09 2021-03-30 2021-09-26 gement ations Envelope mentation ur la création et hébergeme nt du site internet CI-PARU-236452-NC-RFQ / A Component 3: Project mana Request for Quot Single Stage - One bonnement et câblage résea IDA / 66860 Post Limited 30,200.00 54,562.90 Signed 2021-06-06 2021-08-05 2021-08-01 2021-08-24 2022-01-28 gement ations Envelope u (internet et téléphone) CI-PARU-236454-NC-RFQ / P roduction des supports d’ide Component 3: Project mana Request for Quot Single Stage - One Pending Impl ntification du siège du PARU IDA / 66860 Post Limited 13,400.00 0.00 2021-06-06 2021-08-01 2022-01-28 gement ations Envelope ementation (totem, panneaux de directi on, plaque, plaque de porte, kakémonos…) CI-PARU-236693-NC-RFQ / P roduction des supports de c Component 3: Project mana Request for Quot Single Stage - One Pending Impl ommunication et des gadget IDA / 66860 Post Limited 25,720.00 0.00 2021-06-26 2021-08-21 2022-02-17 gement ations Envelope ementation s personnalisés (Plaquettes de présentation, bloc-notes, stylos, tee shirts, Polos etc… ) CI-PARU-290832-NC-DIR / R Component 3: Project mana Under Imple enouvellement du contrat d IDA / 66860 Post Direct Selection Direct 14,000.00 0.00 2022-06-30 2022-10-04 2022-07-05 2022-08-09 2023-02-05 gement mentation e gardiennage des locaux d e l'UC-PARU CI-PARU-290834-NC-DIR / R Component 3: Project mana Pending Impl enouvellement du contrat d' IDA / 66860 Post Direct Selection Direct 16,000.00 0.00 2022-05-31 2022-06-05 2022-07-10 2023-01-06 gement ementation entretien des locaux du PAR U CI-PARU-290597-NC-RFQ / S élection d'un prestataire po Component 3: Project mana Request for Quot Single Stage - One Under Imple ur la fourniture d'assurance IDA / 66860 Post Limited 16,000.00 0.00 2022-05-31 2022-02-11 2022-07-26 2023-01-22 gement ations Envelope mentation multirisque professionnelle pour les locaux au titre de la gestion 2022 CI-PARU-290600-NC-RFQ / S élection d'un prestataire po Component 3: Project mana Request for Quot Single Stage - One Under Imple ur assurer la couverture mal IDA / 66860 Post Limited 50,000.00 0.00 2022-07-18 2022-02-11 2022-09-12 2023-03-11 gement ations Envelope mentation adie du personnel de l'UC-P ARU au titre de la gestion 20 22 Page 3 CI-PARU-290618-NC-RFQ / S élection d'un prestataire po Component 3: Project mana Request for Quot Single Stage - One IDA / 66860 Post Limited 4,000.00 0.00 Canceled 2022-06-01 2022-07-27 2023-01-23 ur l'entretien des véhicules gement ations Envelope au titre de la gestion 2022 CI-PARU-290661-NC-RFQ / S élection d'un prestataire po Component 3: Project mana Request for Quot Single Stage - One Pending Impl IDA / 66860 Post Limited 11,000.00 0.00 2022-06-28 2022-08-23 2023-02-19 ur assurer l'entretien du mat gement ations Envelope ementation ériel informatique au titre d e la gestion 2022 CI-PARU-290664-NC-RFQ / S élection d'un prestataire po Component 3: Project mana Request for Quot Single Stage - One Pending Impl IDA / 66860 Post Limited 5,000.00 0.00 2022-06-05 2022-07-31 2023-01-27 ur la fourniture d'assurance gement ations Envelope ementation tous risques du matériel roul ant CI-PARU-290665-NC-RFQ / S élection d'un prestataire po ur assurer l'entretien et la ré Component 3: Project mana Request for Quot Single Stage - One Pending Impl IDA / 66860 Post Limited 15,000.00 0.00 2022-06-05 2022-07-31 2023-01-27 paration des splits du PARU gement ations Envelope ementation y compris les petits travaux de plomberie et d'électricité au titre de la gestion 2022 CI-PARU-290666-NC-RFQ / S élection d'un prestataire po Component 3: Project mana Request for Quot Single Stage - One Pending Impl IDA / 66860 Post Limited 30,000.00 0.00 2022-06-05 2022-07-31 2023-01-27 ur la fourniture de service in gement ations Envelope ementation ternet et téléphonique au PA RU CI-PARU-290671-NC-DIR / S Component 3: Project mana Pending Impl élection par Entente Directe IDA / 66860 Post Direct Selection Direct 10,000.00 0.00 2022-05-31 2022-06-05 2022-07-10 2023-01-06 gement ementation pour l'hébergement du site i nternet du PARU CI-PARU-350073-NC-RFQ / S élection d'un prestataire po Component 3: Project mana Request for Quot Single Stage - One Pending Impl IDA / 66860 Post Limited 16,000.00 0.00 2023-04-15 2023-06-10 2023-12-07 ur le gardiennage des locau gement ations Envelope ementation x de l'UC PARU au titre de la gestion 2023 CI-PARU-350079-NC-RFQ / S élection d'un prestataire po Component 3: Project mana Request for Quot Single Stage - One Pending Impl IDA / 66860 Post Limited 24,000.00 0.00 2023-04-10 2023-06-05 2023-12-02 ur l'entretien des locaux du gement ations Envelope ementation de l'UC-PARU au titre de la g estion 2023 CI-PARU-350086-NC-RFQ / S élection d'un prestataire po Component 3: Project mana Request for Quot Single Stage - One Pending Impl IDA / 66860 Post Limited 30,000.00 0.00 2023-04-08 2023-06-03 2023-11-30 ur l'entretien des véhicules gement ations Envelope ementation de l'UC-PARU au titre de la g estion 2023 CI-PARU-350088-NC-RFQ / S élection d'un prestataire po Component 3: Project mana Request for Quot Single Stage - One Pending Impl IDA / 66860 Post Limited 20,000.00 0.00 2023-04-08 2023-06-03 2023-11-30 ur l'entretien du matériel inf gement ations Envelope ementation ormatique de l'UC-PARU au t itre de la gestion 2023 CI-PARU-350097-NC-RFQ / S élection d'un prestataire po ur l'entretien et la réparatio Component 3: Project mana Request for Quot Single Stage - One Pending Impl IDA / 66860 Post Limited 20,000.00 0.00 2023-04-08 2023-06-03 2023-11-30 n des splits de l'UC-PARU y c gement ations Envelope ementation ompris les petits travaux de plomberie et d'électricité au titre de la gestion 2023 CI-PARU-350098-NC-RFQ / S élection d'un prestataire po Component 3: Project mana Request for Quot Single Stage - One Under Imple ur la fourniture d'internet et IDA / 66860 Post Limited 40,000.00 0.00 2023-04-08 2022-10-28 2023-06-03 2023-11-30 gement ations Envelope mentation abonnement téléphonique d e l'UC-PARU au titre de la ge stion 202" CI-PARU-350105-NC-RFQ / S élection d'un prestataire po ur la production d'une émiss Component 3: Project mana Request for Quot Single Stage - One Pending Impl IDA / 66860 Post Limited 60,000.00 0.00 2023-05-07 2023-07-02 2023-12-29 ion TV de sensibilisation et d gement ations Envelope ementation 'information des usagers po ur l'UC-PARU au titre de la g estion 2023 CI-PARU-350110-NC-RFQ / S élection d'un prestataire po ur l'organisation des campa Component 3: Project mana Request for Quot Single Stage - One Pending Impl IDA / 66860 Post Limited 70,000.00 0.00 2023-04-08 2023-06-03 2023-11-30 gnes d'information et de sen gement ations Envelope ementation sibilisation dans les zones d' exécution des travaux pour l 'UC-PARU au titre de la gesti on 2023 CI-PARU-350113-NC-RFQ / S élection d'un prestataire po Component 3: Project mana Request for Quot Single Stage - One Pending Impl IDA / 66860 Post Limited 10,000.00 0.00 2023-12-06 2024-01-31 2024-07-29 ur la production d'un publi-r gement ations Envelope ementation eportage annuel sur l'état d' avancement du PARU CI-PARU-350116-NC-RFQ / S élection d'un prestataire po Component 3: Project mana Request for Quot Single Stage - One Pending Impl ur la maintenance du group IDA / 66860 Post Limited 6,000.00 0.00 2023-04-08 2023-06-03 2023-11-30 gement ations Envelope ementation e électrogène de l'UC-PARU au titre de la gestion 2023 CI-PARU-350129-NC-RFQ / S élection d'un prestataire po Component 3: Project mana Request for Quot Single Stage - One Pending Impl IDA / 66860 Post Limited 100,000.00 0.00 2023-06-06 2023-08-01 2024-01-28 ur l'aménagement des locau gement ations Envelope ementation x de l'UC-PARU au titre de la gestion 2023 CI-PARU-350137-NC-RFQ / S élection d'un prestataire po Component 3: Project mana Request for Quot Single Stage - One Pending Impl IDA / 66860 Post Limited 2,000.00 0.00 2023-07-08 2023-09-02 2024-02-29 ur la réalisation des plans d' gement ations Envelope ementation évacuation de l'UC-PARU au titre de la gestion 2023 CI-PARU-350139-NC-RFQ / S élection d'un prestataire po Component 3: Project mana Request for Quot Single Stage - One Pending Impl ur la production des capsule IDA / 66860 Post Limited 60,000.00 0.00 2023-04-08 2023-06-03 2023-11-30 gement ations Envelope ementation s vidéo de sensibilisation de l'UC-PARU au titre de la gest ion 2023 CI-PARU-290763-NC-RFQ / S élection d'un prestataire po Component 3: Project mana Request for Quot Single Stage - One Pending Impl IDA / 66860 Post Limited 6,000.00 0.00 2022-06-05 2022-07-31 2023-01-27 ur assurer la maintenance d gement ations Envelope ementation u groupe électrogène CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amoun Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Techni Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) t (US$) Notice equest for Proposals as Issued Proposals / Minutes cal Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CI-PARU-155134-CS-QBS / E tude pour la mise en place d Quality Based Sel Open - Internation / Post 50,000.00 0.00 Canceled 2020-03-18 2020-04-08 2020-05-22 2020-06-19 2020-07-19 2020-08-18 2020-09-22 2021-09-22 'une stratégie d'entretien de ection al s ouvrages (O&M) Page 4 CI-PARU-155137-CS-CQS / R ecrutement d'une firme pou r les études d'Impact Enviro nnementale et Sociale (EIES Consultant Qualifi Under Implement / Post Limited 18,000.00 0.00 2020-03-26 2021-05-26 2020-04-09 2020-05-09 2020-06-13 2020-12-10 ) du projet d'aménagement cation Selection ation des ouvrages de drainage d es eaux pluviales de Gesco et Port-Boût II dans la comm une de Yopougon. CI-PARU-155227-CS-QBS / E tude de faisabilité technique du projet de modernisation et de gestion intercommuna Quality Based Sel Open - Internation Under Implement le des déchets solides des vi / Post 650,000.00 0.00 2020-01-27 2020-02-11 2020-02-17 2020-02-18 2020-04-01 2020-04-08 2020-04-29 2020-05-29 2020-06-28 2020-08-02 2021-08-02 ection al ation lles de Toumodi, Yamoussou krou, Tiebissou, Djebonoua, Bouaké et du mode de contr actualisation des infrastruct ures avec le secteur privé. CI-PARU-155231-CS-QBS / E tude de faisabilité technique du projet de modernisation et de gestion intercommuna Quality Based Sel Open - Internation Under Implement le des déchets solides des vi / Post 600,000.00 0.00 2020-01-27 2020-02-11 2020-02-17 2020-02-19 2020-04-01 2020-07-18 2020-04-29 2020-09-16 2020-05-29 2020-06-28 2020-08-02 2021-08-02 ection al ation lles de Korhogo, Sinematiali, Ferkessedougou et Ouangol odougou, et du mode de con tractualisation des infrastruc tures avec le secteur privé. CI-PARU-155232-CS-QCBS / Etude de faisabilité techniqu Quality And Cost- Open - Internation Under Implement e de gestion intercommunal / Post 200,000.00 0.00 2020-02-05 2020-02-11 2020-02-26 2020-02-18 2020-04-10 2020-05-08 2020-06-07 2020-07-12 2020-08-16 2021-08-16 Based Selection al ation e des déchets solides des vil les de Bloléquin, Guiglo et D uékoué. CI-PARU-155241-CS-QBS / E tude sur le développement Quality Based Sel Open - Internation Under Implement des filières de recyclage et d / Post 300,000.00 0.00 2020-01-28 2020-02-11 2020-02-18 2020-03-04 2020-04-02 2020-04-30 2020-05-30 2020-06-29 2020-08-03 2021-08-03 ection al ation e valorisation de déchets da ns le district autonome d’Abi djan CI-PARU-155219-CS-QBS / E tude de faisabilité technique Component 2: Improvemen du projet d’optimisation et d t of solid waste manageme Quality Based Sel Open - Internation Under Implement e gestion des déchets solide IDA / V2850 Post 750,000.00 0.00 2020-05-27 2020-12-16 2020-06-17 2021-02-02 2020-07-31 2020-08-28 2020-09-27 2020-10-27 2020-12-01 2021-12-01 nt infrastructure and servic ection al ation s dans le district autonome es d’Abidjan et du mode de con tractualisation des infrastruc tures dans le cadre d’un PPP . CI-PARU-155242-CS-QBS / E tats des lieux sur les capacit és des cadres institutionnels , données et systèmes disp Component 3: Project mana Quality Based Sel Open - Internation IDA / V2850 Post 200,000.00 0.00 Canceled 2020-05-20 2020-06-10 2020-07-24 2020-08-21 2020-09-20 2020-10-20 2020-11-24 2021-11-24 o sur les technologies digital gement ection al es pour la résilience urbaine et délivrer feuille de route e t étude de faisabilité et conc eption pour la préparation d es DAO pour les SN. CI-PARU-168277-CS-CQS / R ecrutement d'un consultant/ Firme pour l'actualisation de Component 1: Flood risk mi Consultant Qualifi Under Implement s études APD pour les trava IDA / V2850 tigation infrastructure and s Post Open - National 184,428.10 0.00 2020-04-28 2019-11-01 2020-05-19 2020-07-02 2020-08-01 2020-09-05 2021-03-04 cation Selection ation ux de drainage des eaux plu ervices viales et préparation du DA Oà Gesco dans la commune de Yopougon. CI-PARU-205866-CS-LCS / R ecrutement d'un Cabinet po Component 3: Project mana Least Cost Selecti IDA / 66860 Post Open - National 40,000.00 18,560.49 Signed 2020-12-04 2020-12-18 2020-12-25 2021-02-02 2021-02-07 2021-10-04 2021-03-07 2021-10-27 2021-04-06 2021-11-09 2021-05-11 2021-11-30 2021-06-15 2021-12-11 2021-12-12 ur l'Audit comptable et finan gement on cier du projet - Exercice 202 1-2023 CI-PARU-205868-CS-CQS / E tude de faisabilité technico- Component 2: Improvemen économique de gestion inté t of solid waste manageme Consultant Qualifi Under Implement grée des déchets solides sa IDA / 66860 Post Open - National 300,000.00 0.00 2020-12-15 2020-12-16 2021-01-05 2021-02-02 2021-02-18 2021-03-20 2021-04-24 2021-10-21 nt infrastructure and servic cation Selection ation nitaires dans le district auto es nome d'Abidjan et du mode de contractualisation avec l e secteur privé CI-PARU-213152-CS-QCBS / Selection d'une entreprise p Component 1: Flood risk mi our le suivi et le contrôle de Quality And Cost- Open - Internation Under Implement IDA / 66860 tigation infrastructure and s Post 500,000.00 0.00 2021-01-25 2021-01-31 2021-02-15 2021-03-31 2021-04-28 2021-05-28 2021-07-02 2021-08-06 2022-08-06 s travaux de construction de Based Selection al ation ervices s ouvrages de drainages des eaux pluviales de Grand-Bas sam CI-PARU-213155-CS-QCBS / Selection d'une entreprise p Component 1: Flood risk mi our le suivi et le contrôle de Quality And Cost- Open - Internation IDA / 66860 tigation infrastructure and s Post 500,000.00 818,365.35 Signed 2021-01-25 2021-01-31 2021-02-15 2022-03-28 2021-03-31 2021-10-27 2021-04-28 2022-01-20 2021-05-28 2022-02-07 2021-07-02 2022-02-09 2021-08-06 2022-03-29 2022-08-06 s travaux de construction de Based Selection al ervices s ouvrages de drainage des eaux pluviales de Anonkoua- kouté commune d'Abobo CI-PARU-213216-CS-CQS / S election d'une ONG pour acc ompagner la préparation et l Component 1: Flood risk mi a mise en œuvre du PAR da Consultant Qualifi Pending Impleme IDA / 66860 tigation infrastructure and s Post Open - National 6,000.00 0.00 2021-01-25 2021-02-15 2021-03-31 2021-04-30 2021-06-04 2021-12-01 ns le cadre de la réalisation cation Selection ntation ervices des travaux de construction des ouvrages de drainage d es eaux pluviales de Anonko ua-kouté commune d'Abobo CI-PARU-213932-CS-CQS / s élection d'un Consultant pou r la réalisation de l'EIES des Component 1: Flood risk mi Consultant Qualifi Open - Internation Pending Impleme travaux de construction des IDA / 66860 tigation infrastructure and s Post 100,000.00 0.00 2021-02-11 2021-03-04 2021-04-17 2021-05-17 2021-06-21 2021-12-18 cation Selection al ntation ouvrages de drainage des e ervices aux pluviales de GESCO, rou te de Dabou, Commune de Y opougon. CI-PARU-213935-CS-QCBS / Sélection d'un consultant p our le contrôle et le suivi de Component 1: Flood risk mi Quality And Cost- Open - Internation Under Implement s travaux des travaux de co IDA / 66860 tigation infrastructure and s Post 500,000.00 0.00 2021-05-05 2022-03-16 2021-05-26 2022-04-05 2021-07-09 2022-07-19 2021-08-06 2022-08-26 2021-09-05 2022-09-02 2021-10-10 2022-10-28 2021-11-14 2022-11-14 Based Selection al ation nstruction des ouvrages de ervices drainage des eaux pluviales de GESCO, route de Dabou, Commune de Yopougon. CI-PARU-213938-CS-CQS / S élection de Consultant pour Component 1: Flood risk mi Consultant Qualifi Pending Impleme la réalisation des études tec IDA / 66860 tigation infrastructure and s Post Open - National 200,000.00 0.00 2021-03-03 2021-03-24 2021-05-07 2021-06-06 2021-07-11 2022-01-07 cation Selection ntation hniques et élaboration des D ervices AO pour les travaux de révé gétalisation CI-PARU-213949-CS-QCBS / Sélection d'un Consultant po Component 1: Flood risk mi ur la réalisation de l'étude fo Quality And Cost- Open - Internation Under Implement IDA / 66860 tigation infrastructure and s Post 500,000.00 0.00 2021-02-28 2021-08-30 2021-03-21 2021-10-21 2021-05-04 2022-04-19 2021-06-01 2022-05-25 2021-07-01 2022-06-01 2021-08-05 2022-07-14 2021-09-09 2022-09-09 nctionnelle (schema directe Based Selection al ation ervices ur) pour l'extention du SIGF U dans les villes secondaires identifiées. Page 5 CI-PARU-213951-CS-CQS / S élection d'un consultant pou Component 1: Flood risk mi r l'élaboration de plans d'urb Consultant Qualifi Open - Internation IDA / 66860 tigation infrastructure and s Post 226,000.00 0.00 Canceled 2021-03-25 2021-04-15 2021-05-29 2021-06-28 2021-08-02 2022-01-29 anisme détaillé de cinq (5) u cation Selection al ervices nités urbaines du schéma di recteur d'urbanisme du Gra nd-Abidjan (SDUGA) CI-PARU-213953-CS-QCBS / Sélection d'un Consultant po Component 2: Improvemen ur la réalisation de l'EIES po t of solid waste manageme Quality And Cost- Open - Internation Under Implement IDA / 66860 Post 450,000.00 0.00 2021-02-17 2022-10-10 2021-03-10 2022-10-27 2021-04-23 2021-05-21 2021-06-20 2021-07-25 2021-08-29 2022-08-29 ur les travaux de constructio nt infrastructure and servic Based Selection al ation ns des infrastructures du pr es ojet d'optimisation de la ges tion des déchets solides dan s le DAA CI-PARU-213957-CS-QCBS / Sélection d'un Consultant po Component 2: Improvemen ur la réalisation de l'EIES po t of solid waste manageme Quality And Cost- Open - Internation Under Implement ur les travaux de constructio IDA / 66860 Post 850,000.00 0.00 2021-01-27 2022-06-28 2021-02-17 2021-04-02 2021-04-30 2021-05-30 2021-07-04 2021-08-08 2022-08-08 nt infrastructure and servic Based Selection al ation ns des infrastructures du pr es ojet de gestion des déchets solides dans l'intercommuna lité de Yamoussoukro, Boua ké CI-PARU-213959-CS-QCBS / Sélection d'un Consultant po Component 2: Improvemen ur la réalisation de l'EIES po t of solid waste manageme Quality And Cost- Open - Internation Under Implement ur les travaux de constructio IDA / 66860 Post 600,000.00 0.00 2021-01-28 2022-06-28 2021-02-18 2021-04-03 2021-05-01 2021-05-31 2021-07-05 2021-08-09 2022-08-09 nt infrastructure and servic Based Selection al ation ns des infrastructures du pr es ojet de gestion des déchets solides dans l'intercommuna lité de Korhogo_Ferké CI-PARU-213964-CS-CQS / S élection d'un Consultant pou Component 2: Improvemen r la réalisation de l'étude du t of solid waste manageme Consultant Qualifi Open - Internation Under Implement financement durable, de la v IDA / 66860 Post 350,000.00 0.00 2021-01-27 2020-01-10 2021-02-17 2022-04-07 2021-04-02 2020-07-30 2021-05-02 2021-06-06 2021-12-03 nt infrastructure and servic cation Selection al ation iabilité économique et des r es éformes fiscales de la gestio n des déchets solides en Côt e d’Ivoire CI-PARU-216414-CS-QCBS / Component 1: Flood risk mi ETUDE DES FILIERES DE VAL Quality And Cost- Under Implement IDA / 66860 tigation infrastructure and s Post Open - National 300,000.00 0.00 2021-01-31 2021-03-15 2021-02-21 2021-04-08 2021-04-06 2020-11-25 2021-05-04 2021-06-03 2021-07-08 2021-08-12 2022-08-12 ORISATION DES DECHETS S Based Selection ation ervices OLIDES DU DISTRICT AUTON OME D’ABIDJAN CI-PARU-216416-CS-QBS / E Component 2: Improvemen tude de faisabilité technique t of solid waste manageme Quality Based Sel Pending Impleme de gestion intercommunale IDA / 66860 Post Open - National 200,000.00 0.00 2021-01-27 2021-02-17 2021-04-02 2021-04-30 2021-05-30 2021-06-29 2021-08-03 2022-08-03 nt infrastructure and servic ection ntation des déchets solides des ville es s de Bloléquin, Guiglo et Du ékoué. CI-PARU-226465-CS-CQS / É laboration du Constat d’Imp act Environnemental et Soci Component 1: Flood risk mi al (CIES) du projet d’aménag Consultant Qualifi Under Implement IDA / 66860 tigation infrastructure and s Post Limited 36,850.00 0.00 2021-03-29 2019-09-05 2021-04-12 2021-05-12 2021-06-16 2021-12-13 ement de la cuvette d’Anon cation Selection ation ervices koua dans la commune d’Ab obo, dans cadre du fond de préparation du Projet d’Assa inissement et de la Résilienc e Urbaine (PARU) CI-PARU-236502-CS-CQS / R ecrutement d'une ONG pour la mise en œuvre du Plan d' Component 1: Flood risk mi Consultant Qualifi Pending Impleme Action de Réinstallation (PA IDA / 66860 tigation infrastructure and s Post Limited 6,000.00 0.00 2021-06-07 2021-06-21 2021-07-21 2021-08-25 2022-02-21 cation Selection ntation R) des travaux de constructi ervices on des ouvrages de drainag e des eaux pluviales de Gra nd-Bassam CI-PARU-236505-CS-CQS / S élection d'une ONG pour l'ac compagnement à la mise en Component 1: Flood risk mi Consultant Qualifi Pending Impleme œuvre du PAR des travaux d IDA / 66860 tigation infrastructure and s Post Limited 3,700.00 0.00 2021-06-01 2021-06-15 2021-07-15 2021-08-19 2022-02-15 cation Selection ntation ''aménagement des deux cu ervices vettes d'Anonkoua et Agoue tto et travaux routiers assoc iés d'Abobo CI-PARU-236569-CS-CQS / S élection d'un cabinet pour la Component 1: Flood risk mi réalisation de l'EIES des trav Consultant Qualifi Under Implement IDA / 66860 tigation infrastructure and s Post Open - National 100,000.00 0.00 2021-06-02 2022-09-05 2021-06-23 2022-09-12 2021-08-06 2021-09-05 2021-10-10 2022-04-08 aux de construction des ouv cation Selection ation ervices rages de drainage des eaux pluviales de Bonoumin dans la commune de Cocody CI-PARU-236639-CS-QCBS / Sélection d'un consultant po Component 2: Improvemen ur la réalisation de l'étude d t of solid waste manageme Quality And Cost- Open - Internation Under Implement e faisabilité pour les travaux IDA / 66860 Post 300,000.00 0.00 2021-06-14 2021-07-05 2021-08-18 2021-09-15 2021-10-15 2021-11-19 2021-12-24 2022-12-24 nt infrastructure and servic Based Selection al ation de constructions des infrastr es uctures du projet d'optimisa tion de la gestion des déche ts solides dans le DAA CI-PARU-236642-CS-CQS / R ecrutement d'une ONG pour l'accompagnement du Projet Component 2: Improvemen dans la mise en œuvre du P t of solid waste manageme Consultant Qualifi Pending Impleme AR pour les travaux de cons IDA / 66860 Post Limited 5,000.00 0.00 2021-06-07 2021-06-21 2021-07-21 2021-08-25 2022-02-21 nt infrastructure and servic cation Selection ntation truction des infrastructures es du projet d'optimisation de l a gestion des déchets solide s dans l'intercommunalité d e Yamoussoukro-Bouaké CI-PARU-236706-CS-QCBS / Recrutement d'un bureau de Component 1: Flood risk mi contrôle et de suivi des trav Quality And Cost- Pending Impleme IDA / 66860 tigation infrastructure and s Post Open - National 500,000.00 0.00 2021-06-15 2021-07-06 2021-08-19 2021-09-16 2021-10-16 2021-11-20 2021-12-25 2022-12-25 aux d''aménagement des de Based Selection ntation ervices ux cuvettes d'Anonkoua et A gouetto et travaux routiers associés d'Abobo CI-PARU-236884-CS-CQS / S élection d'un consultant pou Component 1: Flood risk mi r l'élaboration de plans d'urb Consultant Qualifi IDA / 66860 tigation infrastructure and s Post Open - National 45,200.00 0.00 Canceled 2021-07-05 2021-07-26 2021-09-08 2021-10-08 2021-11-12 2022-05-11 anisme détaillé d'une unité cation Selection ervices urbaine du schéma directeu r d'urbanisme du Grand-Abi djan (SDUGA) Unité N°2 CI-PARU-236886-CS-CQS / S élection d'un consultant pou Component 1: Flood risk mi r l'élaboration de plans d'urb Consultant Qualifi IDA / 66860 tigation infrastructure and s Post Open - National 45,200.00 0.00 Canceled 2021-07-05 2021-07-26 2021-09-08 2021-10-08 2021-11-12 2022-05-11 anisme détaillé d'une unité cation Selection ervices urbaine du schéma directeu r d'urbanisme du Grand-Abi djan (SDUGA) Unité N°8 CI-PARU-236890-CS-CQS / S élection d'un consultant pou Component 1: Flood risk mi r l'élaboration de plans d'urb Consultant Qualifi IDA / 66860 tigation infrastructure and s Post Open - National 45,200.00 0.00 Canceled 2021-07-05 2021-07-26 2021-09-08 2021-10-08 2021-11-12 2022-05-11 anisme détaillé d'une unité cation Selection ervices urbaine du schéma directeu r d'urbanisme du Grand-Abi djan (SDUGA) Unité N°10 Page 6 CI-PARU-236881-CS-CQS / S élection d'un consultant pou Component 1: Flood risk mi r l'élaboration de plans d'urb Consultant Qualifi IDA / 66860 tigation infrastructure and s Post Open - National 45,200.00 0.00 Canceled 2021-07-05 2021-07-26 2021-09-08 2021-10-08 2021-11-12 2022-05-11 anisme détaillé d'une unité cation Selection ervices urbaine du schéma directeu r d'urbanisme du Grand-Abi djan (SDUGA) Unité N°1 CI-PARU-213950-CS-CQS / S Component 1: Flood risk mi élection d'un consultant et r Consultant Qualifi Open - Internation IDA / 66860 tigation infrastructure and s Post 88,000.00 0.00 Canceled 2021-02-28 2021-05-26 2021-03-21 2021-05-04 2021-06-03 2021-07-08 2022-01-04 éalisation de l'étude de profi cation Selection al ervices lage des quartiers précaires d’Abidjan CI-PARU-244977-CS-QCBS / Sélection de consultant pour Component 1: Flood risk mi Quality And Cost- Open - Internation Under Implement la réalisation de l'étude de s IDA / 66860 tigation infrastructure and s Post 1,000,000.00 0.00 2021-12-30 2021-10-07 2022-01-20 2021-10-27 2022-03-05 2022-06-21 2022-04-02 2022-08-03 2022-05-02 2022-08-18 2022-06-06 2022-11-25 2022-07-11 2023-07-11 Based Selection al ation chéma directeur d'assainiss ervices ement des villes de Bouaflé et Katiola CI-PARU-244975-CS-QCBS / Sélection de consultant pour Component 1: Flood risk mi Quality And Cost- Open - Internation Under Implement la réalisation de l'étude du s IDA / 66860 tigation infrastructure and s Post 950,000.00 0.00 2021-11-26 2021-10-07 2021-12-17 2021-10-27 2022-01-30 2020-07-18 2022-02-27 2020-09-16 2022-03-29 2020-11-20 2022-05-03 2022-06-07 2023-06-07 Based Selection al ation chéma directeur d'assainiss ervices ement des villes de Guiglo_ Duékoué CI-PARU-244970-CS-QCBS / Sélection de consultant pour Component 1: Flood risk mi Quality And Cost- Open - Internation Under Implement la réalisation de l'étude de s IDA / 66860 tigation infrastructure and s Post 600,000.00 0.00 2021-11-25 2021-10-07 2021-12-16 2021-10-27 2022-01-29 2022-06-17 2022-02-26 2022-08-03 2022-03-28 2022-10-04 2022-05-02 2022-11-16 2022-06-06 2023-06-06 Based Selection al ation chéma directeur d'assainiss ervices ement de la ville de Divo CI-PARU-252903-CS-QCBS / Sélection d'un consultant po Component 1: Flood risk mi ur l'élaboration de plans d'ur Quality And Cost- Open - Internation Under Implement IDA / 66860 tigation infrastructure and s Post 1,028,167.00 0.00 2021-11-24 2021-10-07 2021-12-15 2021-10-26 2022-01-28 2022-02-25 2022-03-27 2022-05-01 2022-06-05 2023-06-05 banisme détaillé d'une unité Based Selection al ation ervices urbaine de schéma directeu r du Grand-Abidjan (Unité Ur baine 09 : Alépé et Bonoua) CI-PARU-252904-CS-QCBS / Sélection d'un consultant po ur l'élaboration de plans d'ur Component 1: Flood risk mi banisme détaillé d'une unité Quality And Cost- Open - Internation Under Implement IDA / 66860 tigation infrastructure and s Post 1,033,029.00 0.00 2021-12-06 2021-10-07 2021-12-27 2021-10-26 2022-02-09 2022-03-09 2022-04-08 2022-05-13 2022-06-17 2023-06-17 urbaine de schéma directeu Based Selection al ation ervices r du Grand-Abidjan (Unités U rbaines 01 et 10 : Adjamé, A ttécoubé, Plateau, Dabou et Jacqueville) CI-PARU-252905-CS-QCBS / Sélection d'un consultant po ur l'élaboration de plans d'ur Component 1: Flood risk mi Quality And Cost- Open - Internation Under Implement banisme détaillé d'une unité IDA / 66860 tigation infrastructure and s Post 1,033,029.00 0.00 2021-12-14 2021-10-07 2022-01-04 2021-10-27 2022-02-17 2022-03-17 2022-04-16 2022-05-21 2022-06-25 2023-06-25 Based Selection al ation urbaine de schéma directeu ervices r du Grand-Abidjan (Unités U rbaines 02 et 08 : Port-bouet - Grand-Bassam et Azaguié ) CI-PARU-252873-CS-QCBS / Définition d’une stratégie nu Component 1: Flood risk mi mérique pour le renforceme Quality And Cost- Open - Internation Under Implement IDA / 66860 tigation infrastructure and s Post 369,434.00 0.00 2021-11-01 2021-10-07 2021-11-22 2021-10-26 2022-01-05 2022-02-02 2022-03-04 2022-04-08 2022-05-13 2023-05-13 nt de l’innovation au service Based Selection al ation ervices de la résilience urbaine dans le cadre des activités du pro jet PARU CI-PARU-236453-CS-CQS / R ecrutement d'un consultant Component 3: Project mana Consultant Qualifi IDA / 66860 Post Open - National 160,000.00 0.00 Canceled 2021-06-07 2021-06-28 2021-08-11 2021-09-10 2021-10-15 2022-04-13 firme pour réaliser l'étude d gement cation Selection e référence du PARU CI-PARU-236451-CS-CQS / R ecrutement d'un consultant Component 1: Flood risk mi pour la réalisation de l’EIES Consultant Qualifi Open - Internation Under Implement IDA / 66860 tigation infrastructure and s Post 70,000.00 0.00 2022-04-30 2022-09-05 2022-05-21 2022-09-12 2022-07-04 2022-08-03 2022-09-07 2023-03-06 des travaux d''aménagemen cation Selection al ation ervices t des deux cuvettes d'Anonk oua et Agouetto et travaux r outiers associés d'Abobo CI-PARU-213948-CS-QCBS / Sélection d'un Consultant po Component 1: Flood risk mi ur la réalisation du déploiem Quality And Cost- Open - Internation IDA / 66860 tigation infrastructure and s Post 1,300,391.00 0.00 Canceled 2021-02-18 2021-05-26 2021-03-11 2021-04-24 2021-05-22 2021-06-21 2021-07-26 2021-08-30 2022-08-30 ent de quatre (4) stations pe Based Selection al ervices rmanentes et d'un (1) centr e de calcul sur le Grand- Abi djan (Reférentiel géodésiqu e) CI-PARU-155129-CS-QBS / E tudes de faisabilité et étude Quality Based Sel Open - Internation / Post 1,152,000.00 0.00 Canceled 2020-04-07 2020-04-28 2020-06-11 2020-07-09 2020-08-08 2020-09-07 2020-10-12 2021-10-12 s techniques pour les travau ection al x de drainage et travaux rou tiers associés CI-PARU-155246-CS-QBS / R ecrutement d’un Consultant/ Firme pour les études de fai Quality Based Sel Open - Internation / Post 200,000.00 0.00 Canceled 2020-03-30 2020-04-20 2020-06-03 2020-07-01 2020-07-31 2020-08-30 2020-10-04 2021-10-04 sabilité et conception détaill ection al ée y compris la préparation des DAO pour le système d' alerte précoce aux inondatio ns. CI-PARU-236589-CS-CQS / S élection d'un consultant pou Component 2: Improvemen r l'accompagnement du Proj t of solid waste manageme Consultant Qualifi et dans la mise en œuvre du IDA / 66860 Post Limited 5,000.00 0.00 Canceled 2021-09-06 2021-09-20 2021-10-20 2021-11-24 2022-05-23 nt infrastructure and servic cation Selection PAR pour les travaux de con es struction des infrastructures du projet d'optimisation de l a gestion des déchets solide s dans le DAA CI-PARU-236581-CS-CQS / S élection d'une ONG pour l'ac Component 1: Flood risk mi Consultant Qualifi compagnement le Projet da IDA / 66860 tigation infrastructure and s Post Limited 5,000.00 0.00 Canceled 2021-06-02 2021-06-16 2021-07-16 2021-08-20 2022-02-16 cation Selection ns la mise en œuvre du PAR ervices des travaux de lutte contre l 'érosion CI-PARU-236583-CS-CQS / S élection d'un consultant pou r la réalisation de l'étude d'é Component 1: Flood risk mi Consultant Qualifi tat des lieux sur les capacité IDA / 66860 tigation infrastructure and s Post Open - National 200,000.00 0.00 Canceled 2021-05-31 2021-06-21 2021-08-04 2021-09-03 2021-10-08 2022-04-06 cation Selection s, cadres institutionnels, don ervices nées et système disponible sur les technologies digitale s pour la résilience urbaine CI-PARU-236666-CS-CQS / R Component 2: Improvemen ecrutement d'un consultant t of solid waste manageme Consultant Qualifi pour la réalisation de l'EIES IDA / 66860 Post Open - National 100,000.00 0.00 Canceled 2021-07-19 2021-08-09 2021-09-22 2021-10-22 2021-11-26 2022-05-25 nt infrastructure and servic cation Selection pour les travaux de construc es tions de la déchetterie de Bi ngerville CI-PARU-236559-CS-CQS / S élection d'un consultant pou Component 1: Flood risk mi Consultant Qualifi r la réalisation de l'EIES de p IDA / 66860 tigation infrastructure and s Post Open - National 100,000.00 0.00 Canceled 2021-06-07 2021-06-28 2021-08-11 2021-09-10 2021-10-15 2022-04-13 cation Selection ose des collecteurs EU et EP ervices dans les communes de Marc ory et Koumassi Page 7 CI-PARU-236560-CS-CQS / S élection d'une ONG pour l'ac Component 1: Flood risk mi compagnement à la mise en Consultant Qualifi IDA / 66860 tigation infrastructure and s Post Limited 4,000.00 0.00 Canceled 2021-06-07 2021-06-21 2021-07-21 2021-08-25 2022-02-21 œuvre du PAR de pose des c cation Selection ervices ollecteurs EU et EP dans les communes de Marcory et Ko umassi CI-PARU-236580-CS-CQS / S élection d'un consultant pou Component 1: Flood risk mi Consultant Qualifi r l'accompagnement du Proj IDA / 66860 tigation infrastructure and s Post Limited 5,000.00 0.00 Canceled 2021-06-01 2021-06-15 2021-07-15 2021-08-19 2022-02-15 cation Selection et dans la mise en œuvre du ervices PAR des travaux de revégét alisation CI-PARU-236538-CS-CQS / R ecrutement d'un consultant Component 1: Flood risk mi Consultant Qualifi pour la réalisation des APS/A IDA / 66860 tigation infrastructure and s Post Limited 18,100.00 0.00 Canceled 2021-07-05 2021-07-19 2021-08-18 2021-09-22 2022-03-21 cation Selection PD de pose des collecteurs E ervices U et EP dans les communes de Marcory et Koumassi CI-PARU-236575-CS-CQS / S élection d'un consultant pou r l'accompagnement du Proj Component 1: Flood risk mi Consultant Qualifi et dans la mise en œuvre du IDA / 66860 tigation infrastructure and s Post Limited 5,000.00 0.00 Canceled 2021-06-01 2021-06-15 2021-07-15 2021-08-19 2022-02-15 cation Selection PAR des travaux de sécurisa ervices tion et de valorisation des b erges du canal Anoumabo à Koumassi – Marcory CI-PARU-236520-CS-CQS / S élection d'un consultant pou r l'accompagnement du Proj Component 1: Flood risk mi et dans la mise en œuvre du Consultant Qualifi IDA / 66860 tigation infrastructure and s Post Limited 5,000.00 0.00 Canceled 2021-06-01 2021-06-15 2021-07-15 2021-08-19 2022-02-15 PAR des travaux de construc cation Selection ervices tion des ouvrages de draina ge des eaux pluviales de GE SCO, route de Dabou, Comm une de Yopougon CI-PARU-213942-CS-CQS / S Component 1: Flood risk mi élection d'un Consultant pou Consultant Qualifi Open - Internation IDA / 66860 tigation infrastructure and s Post 100,000.00 0.00 Canceled 2021-03-18 2021-04-08 2021-05-22 2021-06-21 2021-07-26 2022-01-22 r la réalisation de l'EIES pou cation Selection al ervices r les travaux de lutte contre l'érosion CI-PARU-213945-CS-CQS / S élection d'un Consultant pou Component 1: Flood risk mi Consultant Qualifi Open - Internation r la réalisation des études et IDA / 66860 tigation infrastructure and s Post 140,000.00 0.00 Canceled 2021-02-18 2021-03-11 2021-04-24 2021-05-24 2021-06-28 2021-12-25 cation Selection al élaboration des DAO pour le ervices système d'alerte précoce au x inondations CI-PARU-213920-CS-QCBS / Recrutement d'un Consultan Component 1: Flood risk mi Quality And Cost- Open - Internation t pour la réalisation des étud IDA / 66860 tigation infrastructure and s Post 1,152,000.00 0.00 Canceled 2021-03-01 2021-03-22 2021-05-05 2021-06-02 2021-07-02 2021-08-06 2021-09-10 2022-09-10 Based Selection al es APS/APD et l'élaboration ervices des DAO pour les travaux ro utiers associés CI-PARU-213929-CS-QCBS / Component 1: Flood risk mi Sélections de Consultants p Quality And Cost- Open - Internation IDA / 66860 tigation infrastructure and s Post 454,000.00 0.00 Canceled 2021-04-01 2021-04-22 2021-06-05 2021-07-03 2021-08-02 2021-09-06 2021-10-11 2022-10-11 our la réalisation des PAR de Based Selection al ervices s travaux routiers associés CI-PARU-213941-CS-CQS / S élection de Consultants pour Component 1: Flood risk mi Consultant Qualifi Open - Internation la réalisation des études tec IDA / 66860 tigation infrastructure and s Post 200,000.00 0.00 Canceled 2021-02-10 2021-03-03 2021-04-16 2021-05-16 2021-06-20 2021-12-17 cation Selection al hniques et élaboration des D ervices AO pour les travaux de lutte contre l'érosion CI-PARU-213963-CS-CQS / S élection d'un Consultant pou Component 2: Improvemen r la réalisation des études te t of solid waste manageme Consultant Qualifi Open - Internation IDA / 66860 Post 100,000.00 0.00 Canceled 2021-03-23 2021-04-13 2021-05-27 2021-06-26 2021-07-31 2022-01-27 chniques et études de sauve nt infrastructure and servic cation Selection al gardes pour les travaux de c es onstructions de la déchetteri e de Bingerville CI-PARU-213922-CS-CQS / S élection d'un Consultant pou Component 1: Flood risk mi Consultant Qualifi r la réalisation de l’Etude d’I IDA / 66860 tigation infrastructure and s Post Open - National 300,000.00 0.00 Canceled 2021-04-01 2021-04-22 2021-06-05 2021-07-05 2021-08-09 2022-02-05 cation Selection mpact Environnementale et ervices Sociale (EIES) des travaux ro utiers associés CI-PARU-213944-CS-CQS / S élection d' un Consultant po Component 1: Flood risk mi Consultant Qualifi Open - Internation ur la réalisation des études IDA / 66860 tigation infrastructure and s Post 140,000.00 0.00 Canceled 2021-02-10 2021-03-03 2021-04-16 2021-05-16 2021-06-20 2021-12-17 cation Selection al et élaboration des DAO pour ervices les systèmes numériques CI-PARU-213939-CS-CQS / S élection de Consultant pour Component 1: Flood risk mi Consultant Qualifi la réalisation de l'EIES et éla IDA / 66860 tigation infrastructure and s Post Open - National 100,000.00 0.00 Canceled 2021-02-19 2021-03-12 2021-04-25 2021-05-25 2021-06-29 2021-12-26 cation Selection boration des DAO pour les tr ervices avaux de révégétalisation CI-PARU-213936-CS-QCBS / Sélection d'un Consultant po ur la réalisation des études t Component 1: Flood risk mi Quality And Cost- Open - Internation echniques, EIES et élaborati IDA / 66860 tigation infrastructure and s Post 400,000.00 0.00 Canceled 2021-02-26 2021-03-19 2021-05-02 2021-05-30 2021-06-29 2021-08-03 2021-09-07 2022-09-07 Based Selection al on des DAO pour les travaux ervices de sécurisation et de valoris ation des berges du canal A noumabo à Koumassi – Marc ory CI-PARU-213931-CS-QCBS / Sélection de Consultant pou Component 1: Flood risk mi r la réalisation des études d Quality And Cost- Open - Internation IDA / 66860 tigation infrastructure and s Post 420,168.00 0.00 Canceled 2021-03-18 2021-04-08 2021-05-22 2021-06-19 2021-07-19 2021-08-23 2021-09-27 2022-09-27 e schémas directeurs d'assa Based Selection al ervices inissement de cinq (5) Chefs lieux de Région (Divo, Duék oué, Bouaflé, Guiglo, Katiola ) CI-PARU-288653-CS-CQS / R ecrutement d'une ONG pour accompagner la mise en œu Component 1: Flood risk mi Consultant Qualifi Pending Impleme vre du PAR des travaux de c IDA / 66860 tigation infrastructure and s Post Limited 10,000.00 0.00 2022-04-30 2022-05-14 2022-06-13 2022-07-18 2023-01-14 cation Selection ntation onstruction des ouvrages de ervices drainage des eaux pluviales de GESCO, route de Dabou, Commune de Yopougon CI-PARU-288830-CS-CQS / R ecrutement d'un consultant pour la réalisation des étude Component 1: Flood risk mi Consultant Qualifi Under Implement s APS/APD et du DAO pour le IDA / 66860 tigation infrastructure and s Post Open - National 300,000.00 0.00 2022-07-05 2022-06-08 2022-07-26 2023-05-11 2022-09-08 2022-12-05 2022-10-08 2022-11-12 2023-05-11 cation Selection ation s travaux de protection et d ervices e végétalisation des talus de s quartiers Gbébouto et Bidj éké dans la commune d'Atté coubé CI-PARU-288831-CS-CQS / R ecrutement d'un consultant pour la réalisation de l'EIES Component 1: Flood risk mi Consultant Qualifi Under Implement des travaux de protection et IDA / 66860 tigation infrastructure and s Post Limited 60,000.00 0.00 2022-05-25 2022-09-05 2022-06-08 2022-10-06 2022-07-08 2022-08-12 2023-02-08 cation Selection ation de végétalisation des talus d ervices es quartiers Gbébouto et Bid jéké dans la commune d'Att écoubé Page 8 CI-PARU-288902-CS-CQS / S élection d'une ONG pour l'ac compagnement à la mise en Component 1: Flood risk mi Consultant Qualifi Pending Impleme oeuvre du PAR des travaux IDA / 66860 tigation infrastructure and s Post Limited 6,000.00 0.00 2022-07-05 2022-07-19 2022-08-18 2022-09-22 2023-03-21 cation Selection ntation de protection et de végétalis ervices ation des talus des quartiers Gbébouto et Bidjeke dans la commune d'Attécoubé CI-PARU-290390-CS-QCBS / Recrutement d'un consultan t pour la réalisation de l'EIES Component 2: Improvemen pour les travaux du projet d t of solid waste manageme Quality And Cost- Pending Impleme IDA / 66860 Post Open - National 300,000.00 0.00 2022-09-06 2022-09-27 2022-11-10 2022-12-08 2023-01-07 2023-02-11 2023-03-18 2024-03-17 e modernisation et de gestio nt infrastructure and servic Based Selection ntation n intercommunale des déch es ets solides des villes de Kor hogo, Sinématiali, Ferké et Ouangolodougou CI-PARU-290841-CS-CQS / R ecrutement d'un consultant Component 1: Flood risk mi pour la réalisation de l'EIES Consultant Qualifi Under Implement IDA / 66860 tigation infrastructure and s Post Limited 70,000.00 0.00 2022-06-28 2022-09-05 2022-07-12 2022-08-11 2022-09-15 2023-03-14 des travaux d'aménagemen cation Selection ation ervices t des ouvrages de drainages dans le bassin versant de M' pouto à Cocody CI-PARU-267739-CS-QCBS / Sélection d'un cabinet pour l Component 1: Flood risk mi Quality And Cost- Open - Internation a réalisation de l'étude de pr IDA / 66860 tigation infrastructure and s Post 988,020.00 0.00 Canceled 2021-12-24 2022-01-13 2022-01-14 2022-02-27 2022-03-27 2022-04-26 2022-05-31 2022-07-05 2023-07-05 Based Selection al ofilage des quartiers précair ervices es du District Autonome d'A bidjan CI-PARU-295947-CS-QBS / S élection d'un consultant firm Component 1: Flood risk mi Quality Based Sel Open - Internation Under Implement e pour la réalisation de l'étu IDA / 66860 tigation infrastructure and s Post 750,000.00 0.00 2022-06-30 2022-05-26 2022-07-21 2022-09-03 2022-10-01 2022-10-31 2022-11-30 2023-01-04 2024-01-04 ection al ation de de profilage des quartier ervices s précaires dans le District A utonome d'Abidjan CI-PARU-302156-CS-QBS / S élection de consultant pour l a réalisation de la mission d' Component 2: Improvemen assistance pour la mise en p t of solid waste manageme Quality Based Sel Open - Internation Under Implement lace de contrats de délégati IDA / 66860 Post 800,000.00 0.00 2022-07-15 2022-07-13 2022-08-05 2022-10-07 2022-09-18 2022-10-16 2022-11-15 2022-12-15 2023-01-19 2024-01-19 nt infrastructure and servic ection al ation on de services publics de pr es opreté dans le District Auton ome d'Abidjan et dans les In tercommunalités du Centre et du Nord à travers des PPP CI-PARU-303094-CS-QBS / R ecrutement d'un consultant Component 1: Flood risk mi pour la Conception, le déploi Quality Based Sel Open - Internation Under Implement IDA / 66860 tigation infrastructure and s Post 3,790,899.00 0.00 2022-07-30 2022-07-13 2022-08-20 2022-10-18 2022-10-03 2022-10-31 2022-11-30 2022-12-30 2023-02-03 2024-02-03 ement du Système de prévis ection al ation ervices ion et d'alerte précoce (SPA P) des inondations dans le D istrict Autonome d'Abidjan CI-PARU-304283-CS-QBS / R ecrutement de consultant p our la réalisation de l'étude t Component 1: Flood risk mi echnique détaillée des trava Quality Based Sel Under Implement IDA / 66860 tigation infrastructure and s Post Open - National 269,352.00 0.00 2022-07-28 2022-07-15 2022-08-18 2022-08-09 2022-10-01 2022-10-29 2022-11-28 2022-12-28 2023-02-01 2024-02-01 ux d'aménagement des ouvr ection ation ervices ages de drainage des eaux pluviales dans le Bassin vers ant de M’pouto (CITE SYNAC ASCI) dans la commune de Cocody CI-PARU-304286-CS-QBS / R ecrutement de consultants p our la réalisation de l'étude t echnique détaillé des travau Component 1: Flood risk mi Quality Based Sel Open - Internation Under Implement x d'aménagement des ouvra IDA / 66860 tigation infrastructure and s Post 400,000.00 0.00 2022-07-28 2022-07-15 2022-08-18 2022-08-09 2022-10-01 2022-10-29 2022-11-28 2022-12-28 2023-02-01 2024-02-01 ection al ation ges de drainage des eaux pl ervices uviales pluviales dans le Bas sin versant de la Riviera (Tal weg de Bonoumin) dans la c ommune de Cocody CI-PARU-304287-CS-QBS / R ecrutement d'un consultant pour la réalisation de l'Etude Component 1: Flood risk mi Technique détaillée des trav Quality Based Sel Open - Internation Under Implement IDA / 66860 tigation infrastructure and s Post 297,172.00 0.00 2022-07-28 2022-07-15 2022-08-18 2022-08-09 2022-10-01 2022-10-29 2022-11-28 2022-12-28 2023-02-01 2024-02-01 aux d'aménagement des cu ection al ation ervices vettes de PK-18 et N’dotré et des voies associées aux o uvrages de drainage d'Anon koua kouté dans la commun e d'Abobo CI-PARU-304453-CS-QCBS / Recrutement d'un consultan Component 1: Flood risk mi t pour la conception et la mi Quality And Cost- Open - Internation Under Implement IDA / 66860 tigation infrastructure and s Post 2,174,151.00 0.00 2022-07-30 2022-08-12 2022-08-20 2022-10-18 2022-10-03 2022-10-31 2022-11-30 2023-01-04 2023-02-08 2024-02-08 se en œuvre d'un dispositif Based Selection al ation ervices de réponse aux urgences da ns le District Autonome d'Ab idjan CI-PARU-205867-CS-CQS / R Component 1: Flood risk mi ecrutement de consultant p Consultant Qualifi IDA / 66860 tigation infrastructure and s Post Open - National 50,000.00 0.00 Canceled 2020-12-15 2021-01-05 2021-02-18 2021-03-20 2021-04-24 2021-10-21 our la mis en place d'une str cation Selection ervices atégie d'entretien des ouvra ges CI-PARU-236585-CS-CQS / S Component 1: Flood risk mi élection d'un consultant pou Consultant Qualifi IDA / 66860 tigation infrastructure and s Post Open - National 20,000.00 0.00 Canceled 2021-06-02 2021-06-23 2021-08-06 2021-09-05 2021-10-10 2022-04-08 r la réalisation de la politiqu cation Selection ervices e d'alerte précoce en Côte d 'Ivoire CI-PARU-331200-CS-CQS / E laboration du Plan d'Action d e Réinstallation (PAR) des tr Component 2: Improvemen avaux de Construction d'un t of solid waste manageme Consultant Qualifi Pending Impleme IDA / 66860 Post Open - National 200,000.00 0.00 2023-01-13 2023-02-03 2023-03-19 2023-04-18 2023-05-23 2023-11-19 centre de valorisation et d'e nt infrastructure and servic cation Selection ntation nfouissement technique (CV es ET) et de quatre (04) centre s de transferts dans l'Interco mmunalité du Nord CI-PARU-236450-CS-CQS / R ecrutement d'un consultant pour la réalisation des étude Component 1: Flood risk mi Consultant Qualifi s APS/APD et DAO des trava IDA / 66860 tigation infrastructure and s Post Open - National 240,000.00 0.00 Canceled 2021-06-01 2021-06-22 2021-08-05 2021-09-04 2021-10-09 2022-04-07 cation Selection ux d'aménagement des deu ervices x cuvettes d'Anonkoua-Kout é et Agouetto et travaux rou tiers associés d'Abobo CI-PARU-288763-CS-CQS / R ecrutement d'un consultant pour l'actualisation des étud Component 1: Flood risk mi Consultant Qualifi es APS/APD et la préparation IDA / 66860 tigation infrastructure and s Post Limited 80,000.00 0.00 Canceled 2022-06-30 2022-07-14 2022-08-13 2022-09-17 2023-03-16 cation Selection du DAO des travaux d'amén ervices agement des ouvrages de dr ainage dans le bassin versa nt de M'POUTO à Cocody CI-PARU-236563-CS-QCBS / Sélection d'un consultant po ur la réalisation de l'étude A Component 1: Flood risk mi Quality And Cost- Open - Internation PS/APD des travaux de cons IDA / 66860 tigation infrastructure and s Post 540,000.00 0.00 Canceled 2021-06-30 2021-07-21 2021-09-03 2021-10-01 2021-10-31 2021-12-05 2022-01-09 2023-01-09 Based Selection al truction des ouvrages de dr ervices ainage des eaux pluviales d e Bonoumin dans la commu ne de Cocody Page 9 CI-PARU-288821-CS-QBS / R ecrutement d'un consultant Component 1: Flood risk mi pour la réalisation de l'EIES Quality Based Sel Open - Internation IDA / 66860 tigation infrastructure and s Post 80,000.00 0.00 Canceled 2022-05-12 2022-06-02 2022-07-16 2022-08-13 2022-09-12 2022-10-12 2022-11-16 2023-11-16 des travaux de construction ection al ervices des ouvrages de drainage d es eaux pluviales de Bonou min dans la commune de Co cody CI-PARU-347879-CS-QCBS / Recrutement de consultant Component 1: Flood risk mi Quality And Cost- Open - Internation Pending Impleme pour la réalisation des APS/A IDA / 66860 tigation infrastructure and s Post 960,000.00 0.00 2023-05-31 2023-06-21 2023-08-04 2023-09-01 2023-10-01 2023-11-05 2023-12-10 2024-12-09 Based Selection al ntation PD de pose des collecteurs E ervices U et EP dans les communes de Marcory et Koumassi CI-PARU-347885-CS-CQS / R ecrutement de consultant p Component 1: Flood risk mi Consultant Qualifi Pending Impleme our la réalisation de l'EIES d IDA / 66860 tigation infrastructure and s Post Open - National 100,000.00 0.00 2023-07-26 2023-08-16 2023-09-29 2023-10-29 2023-12-03 2024-05-31 cation Selection ntation e pose des collecteurs EU et ervices EP dans les communes de M arcory et Koumassi CI-PARU-347898-CS-QCBS / Recrutement d'un consultan Component 1: Flood risk mi Quality And Cost- Open - Internation Pending Impleme t pour la réalisation des étud IDA / 66860 tigation infrastructure and s Post 960,000.00 0.00 2023-04-29 2023-05-20 2023-07-03 2023-07-31 2023-08-30 2023-10-04 2023-11-08 2024-11-07 Based Selection al ntation es APS/APD des travaux de ervices drainage des eaux pluviales dans la ville de Bouaké CI-PARU-347905-CS-CQS / R ecrutement de consultant p Component 1: Flood risk mi Consultant Qualifi Pending Impleme our la réalisation de l'EIES p IDA / 66860 tigation infrastructure and s Post Open - National 100,000.00 0.00 2023-05-15 2023-06-05 2023-07-19 2023-08-18 2023-09-22 2024-03-20 cation Selection ntation our les travaux d'aménagem ervices ent du bassin versant des ro siers à Cocody CI-PARU-348028-CS-QCBS / Recrutement d'un bureau de Component 1: Flood risk mi contrôle et de suivi des trav Quality And Cost- Open - Internation Pending Impleme IDA / 66860 tigation infrastructure and s Post 700,000.00 0.00 2023-04-17 2023-05-08 2023-06-21 2023-07-19 2023-08-18 2023-09-22 2023-10-27 2024-10-26 aux d'aménagement des ou Based Selection al ntation ervices vrages de drainage dans le bassin versant de M'POUTO dans la commune de Cocod y CI-PARU-348042-CS-QCBS / Recrutement de consultant Component 1: Flood risk mi pour le contrôle et le suivi d Quality And Cost- Open - Internation Pending Impleme IDA / 66860 tigation infrastructure and s Post 700,000.00 0.00 2023-07-03 2023-07-24 2023-09-06 2023-10-04 2023-11-03 2023-12-08 2024-01-12 2025-01-11 es travaux de construction d Based Selection al ntation ervices es ouvrages de drainage de s eaux pluviales de Bonoumi n dans la commune de Coco dy CI-PARU-348167-CS-QCBS / Component 1: Flood risk mi Recrutement d'un consultan Quality And Cost- Open - Internation Pending Impleme IDA / 66860 tigation infrastructure and s Post 400,000.00 0.00 2023-10-18 2023-11-08 2023-12-22 2024-01-19 2024-02-18 2024-03-24 2024-04-28 2025-04-28 t pour la réalisation du systè Based Selection al ntation ervices me d'information de gestion du drainage CI-PARU-236660-CS-QCBS / Component 2: Improvemen Quality And Cost- Recrutement d'un consultan IDA / 66860 t of solid waste manageme Post Open - National 640,000.00 0.00 Canceled 2021-06-03 2021-06-24 2021-08-07 2021-09-04 2021-10-04 2021-11-08 2021-12-13 2022-12-13 Based Selection t pour l'assistance technique nt infrastructure and servic en PPP es CI-PARU-350127-CS-CQS / R Component 2: Improvemen ecrutement de consultant p t of solid waste manageme Consultant Qualifi Open - Internation Pending Impleme our la réalisation des études IDA / 66860 Post 150,000.00 0.00 2023-05-17 2023-06-07 2023-07-21 2023-08-20 2023-09-24 2024-03-22 nt infrastructure and servic cation Selection al ntation techniques pour les travaux es de construction de la déchet terie de Bingerville CI-PARU-350131-CS-CQS / R Component 2: Improvemen ecrutement de consultants p t of solid waste manageme Consultant Qualifi Pending Impleme our la réalisation de l'EIES p IDA / 66860 Post Open - National 50,000.00 0.00 2023-05-26 2023-06-16 2023-07-30 2023-08-29 2023-10-03 2024-03-31 nt infrastructure and servic cation Selection ntation our les travaux de constructi es on de la déchetterie de Bing erville CI-PARU-348106-CS-CQS / R ecrutement d'un consultant Component 1: Flood risk mi pour la réalisation de l'EIES Consultant Qualifi Pending Impleme IDA / 66860 tigation infrastructure and s Post Open - National 100,000.00 0.00 2023-09-20 2023-10-11 2023-11-24 2023-12-24 2024-01-28 2024-07-26 pour les travaux de sécurisa cation Selection ntation ervices tion et de valorisation des b erges du canal Anoumabo à Marcory-Koumassi CI-PARU-348088-CS-CQS / R ecrutement d'une ONG pour accompagner le projet dans Component 1: Flood risk mi Consultant Qualifi Pending Impleme la mise en oeuvre du PAR po IDA / 66860 tigation infrastructure and s Post Limited 50,000.00 0.00 2023-08-24 2023-09-07 2023-10-07 2023-11-11 2024-05-09 cation Selection ntation ur les travaux de sécurisatio ervices n et de valorisation des berg es du canal d'Anoumabo à K oumassi - Marcory CI-PARU-347902-CS-CQS / R ecrutement d'ONG pour l'ac compagnement du Projet da Component 1: Flood risk mi Consultant Qualifi Pending Impleme ns la mise en œuvre du PAR IDA / 66860 tigation infrastructure and s Post Limited 40,000.00 0.00 2023-08-23 2023-09-06 2023-10-06 2023-11-10 2024-05-08 cation Selection ntation des travaux de construction ervices d'ouvrages de drainages de s eaux pluviales dans la ville de BOUAKE CI-PARU-288785-CS-CQS / R ecrutement d'une ONG pour accompagner la mise en oe Component 1: Flood risk mi Consultant Qualifi Pending Impleme uvre du PAR des travaux d'a IDA / 66860 tigation infrastructure and s Post Limited 40,000.00 0.00 2023-08-03 2023-08-17 2023-09-16 2023-10-21 2024-04-18 cation Selection ntation ménagement d'ouvrages de ervices drainage des eaux pluviales dans le bassin versant de M' pouto dans la commune de Cocody CI-PARU-348059-CS-QCBS / Recrutement d'un bureau de Component 1: Flood risk mi contrôle et de suivi des trav Quality And Cost- Open - Internation Pending Impleme IDA / 66860 tigation infrastructure and s Post 500,000.00 0.00 2023-08-01 2023-08-22 2023-10-05 2023-11-02 2023-12-02 2024-01-06 2024-02-10 2025-02-09 aux de protection et de vég Based Selection al ntation ervices étalisation des talus des qua rtiers Gbebouto et Bidjeke d ans la commune d'Attécoub é CI-PARU-348044-CS-QCBS / Recrutement d'un bureau de Component 1: Flood risk mi Quality And Cost- Open - Internation Pending Impleme contrôle et de suivi des trav IDA / 66860 tigation infrastructure and s Post 700,000.00 0.00 2023-08-22 2023-09-12 2023-10-26 2023-11-23 2023-12-23 2024-01-27 2024-03-02 2025-03-02 Based Selection al ntation aux d'aménagement du bas ervices sin versant des rosiers à Coc ody CI-PARU-331286-CS-CQS / E laboration du Plan d'Action d Component 2: Improvemen e Réinstallation (PAR) des tr t of solid waste manageme Consultant Qualifi Pending Impleme avaux de construction d'un IDA / 66860 Post Open - National 200,000.00 0.00 2023-04-12 2023-05-03 2023-06-16 2023-07-16 2023-08-20 2024-02-16 nt infrastructure and servic cation Selection ntation centre de valorisation et d'e es nfouissement technique (CV ET) et de cinq (05) centres d e transfert dans l'Intercomm unalité du centre CI-PARU-359907-CS-CQS / E tude de profilage et d'incorp oration dans le schéma opér Component 2: Improvemen ationnel de gestion des déch t of solid waste manageme Consultant Qualifi Under Implement IDA / 66860 Post Limited 290,000.00 0.00 2023-07-03 2023-06-07 2023-07-17 2023-08-16 2023-09-20 2024-03-18 ets solides des acteurs infor nt infrastructure and servic cation Selection ation mels de la filière et assimilé es s dans le DAA et dans les int ercommunalités du Centre e t du Nord de la Côte d'Ivoire Page 10 CI-PARU-363322-CS-CQS / R ecrutement d'un consultant pour la Réalisation de l'étud Component 2: Improvemen e de faisabilité de la valorisa t of solid waste manageme Consultant Qualifi Pending Impleme IDA / 66860 Post Open - National 60,000.00 0.00 2023-11-06 2023-11-27 2024-01-10 2024-02-09 2024-03-15 2024-09-11 tion énergétique et organiqu nt infrastructure and servic cation Selection ntation e (biodigesteurs) des déchet es s solides ménagers et assimi lés et des déchets agricoles dans les intercommunalités du projet CI-PARU-363324-CS-CQS / R ecrutement d'un consultant pour la réalisation de l'étude Component 2: Improvemen des comportements des act t of solid waste manageme Quality Based Sel Pending Impleme IDA / 66860 Post Open - National 100,000.00 0.00 2023-07-10 2023-07-31 2023-09-13 2023-10-11 2023-11-10 2023-12-10 2024-01-14 2025-01-13 eurs des déchets (ménages, nt infrastructure and servic ection ntation récupérateurs…) et la défini es tion des différents canaux d e diffusion des messages au x acteurs dans la commune d'Abobo CI-PARU-363326-CS-CQS / R Component 2: Improvemen ecrutement d'un consultant t of solid waste manageme Consultant Qualifi Open - Internation Pending Impleme IDA / 66860 Post 136,000.00 0.00 2023-07-06 2023-07-27 2023-09-09 2023-10-09 2023-11-13 2024-05-11 pour la réalisation de l'étude nt infrastructure and servic cation Selection al ntation de profilage des acteurs info es rmels CI-PARU-365148-CS-CQS / R ECRUTEMENT D'ONG OU OS C POUR LA MISE EN ŒUVRE DU PLAN DE RESTAURATION Component 1: Flood risk mi Consultant Qualifi Pending Impleme DES MOYENS DE SUBSISTAN IDA / 66860 tigation infrastructure and s Post Open - National 300,000.00 0.00 2023-06-30 2023-07-21 2023-09-03 2023-10-03 2023-11-07 2024-05-05 cation Selection ntation CE DES SOUS-PROJETS D’AM ervices ENAGEMENT D’OUVRAGES D E DRAINAGE DES EAUX PLU VIALES DANS LES COMMUNE S DE GRAND-BASSAM ET DE YOPOUGON CI-PARU-365150-CS-QCBS / Recrutement d'un consultan Component 1: Flood risk mi t pour la revue des études t Quality And Cost- Pending Impleme IDA / 66860 tigation infrastructure and s Post Open - National 300,000.00 0.00 2023-08-03 2023-08-24 2023-10-07 2023-11-04 2023-12-04 2024-01-08 2024-02-12 2024-04-12 echniques APS/APD pour les Based Selection ntation ervices travaux d'aménagement du bassin versant des rosiers à Cocody CI-PARU-365151-CS-QCBS / Recrutement d'un consultan t pour la revue des études t Component 1: Flood risk mi Quality And Cost- Pending Impleme echniques APS/APD des trav IDA / 66860 tigation infrastructure and s Post Open - National 300,000.00 0.00 2023-08-03 2023-08-24 2023-10-07 2023-11-04 2023-12-04 2024-01-08 2024-02-12 2025-02-11 Based Selection ntation aux d'aménagement d'ouvra ervices ges de drainage des eaux pl uviales (2ème cuvette de Bo cabo) dans la commune d'A bobo CI-PARU-365152-CS-QCBS / Recrutement d'un bureau de contrôle pour le suivi et le c Component 1: Flood risk mi ontrôle des travaux d'ouvra Quality And Cost- Open - Internation Pending Impleme IDA / 66860 tigation infrastructure and s Post 1,400,000.00 0.00 2023-08-23 2023-09-13 2023-10-27 2023-11-24 2023-12-24 2024-01-28 2024-03-03 2025-03-03 ges de drainages des eaux p Based Selection al ntation ervices luviales dans les bassins ver sants de la riviera Bonoumin et de M'pouto_SYNACASCI d ans la commune de Cocody CI-PARU-366830-CS-QCBS / Sélection d'un consultant po Component 1: Flood risk mi ur la mise en place de quatr Quality And Cost- Open - Internation Under Implement IDA / 66860 tigation infrastructure and s Post 1,200,000.00 0.00 2023-07-15 2023-06-20 2023-08-05 2023-09-18 2023-10-16 2023-11-15 2023-12-20 2024-01-24 2025-01-23 e (4) stations permanentes Based Selection al ation ervices GNSS (Global Navigation Sa tellite System) pour le Gran d Abidjan et Assinie INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Identifie Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amoun Draft Negotiated Con Description Component Review Type Method Process Status Terms of Reference d/Selected Consultan Signed Contract Contract Completion o. h unt (US$) t (US$) tract t Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CI-PARU-155213-CS-INDV / Recrutement d'un Consultan t Individuel pour l'élaboratio n du Plan d'action et de Réin Individual Consult Under Implement stallation des personnes affe / Post Limited 18,000.00 0.00 2020-03-23 2021-05-14 2020-03-28 2020-04-18 2020-05-23 2020-11-19 ant Selection ation ctée par le projet d'aménag ement des ouvrages de drai nage des eaux pluviales de Gesco et Port-Boût II dans la commune de Yopougon. CI-PARU-155251-CS-INDV / Recrutement d'un Consultan Individual Consult Pending Impleme / Post Limited 30,000.00 0.00 2020-02-28 2020-03-04 2020-03-25 2020-04-29 2020-10-26 t Individuel pour l'élaboratio ant Selection ntation n du manuel d'opérations d u PARU. CI-PARU-205846-CS-INDV / Component 3: Project mana Individual Consult Under Implement IDA / 66860 Prior Open 72,000.00 0.00 2020-11-21 2021-01-09 2021-01-30 2021-03-06 2022-03-01 Recrutement du Coordonnat gement ant Selection ation eur CI-PARU-205847-CS-INDV / Component 3: Project mana Individual Consult Under Implement Recrutement d'un Responsa IDA / 66860 Post Open 57,600.00 0.00 2020-11-27 2019-11-11 2021-01-15 2021-02-05 2021-03-12 2022-03-07 gement ant Selection ation ble Administratif et Financie r (chef de cellule) CI-PARU-205853-CS-INDV / Component 3: Project mana Individual Consult Under Implement Recrutement d'un Spécialist IDA / 66860 Post Open 54,000.00 0.00 2020-11-27 2020-12-08 2021-01-15 2021-02-05 2021-03-12 2022-03-07 gement ant Selection ation e en Passation des Marchés (chef de cellule) CI-PARU-205854-CS-INDV / Component 3: Project mana Individual Consult Pending Impleme IDA / 66860 Post Open 24,000.00 0.00 2020-11-27 2021-01-15 2021-02-05 2021-03-12 2022-03-07 Recrutement du Chef Compt gement ant Selection ntation able CI-PARU-205855-CS-INDV / Component 3: Project mana Individual Consult Pending Impleme Recrutement du Spécialiste IDA / 66860 Post Open 39,600.00 0.00 2020-11-27 2021-01-15 2021-02-05 2021-03-12 2022-03-07 gement ant Selection ntation en sauvegarde environneme ntale CI-PARU-205856-CS-INDV / Component 3: Project mana Individual Consult Recrutement du Spécialiste IDA / 66860 Post Open 63,600.00 0.00 Canceled 2020-11-27 2020-05-15 2021-01-15 2021-02-05 2021-03-12 2022-03-07 gement ant Selection en sauvegarde sociale CI-PARU-205857-CS-INDV / Component 3: Project mana Individual Consult Recrutement de deux (2) Se IDA / 66860 Post Open 36,000.00 28,060.92 Signed 2020-11-27 2020-12-09 2021-01-15 2021-02-10 2021-02-05 2021-02-25 2021-03-12 2021-04-03 2022-03-07 gement ant Selection cretaires de Direction CI-PARU-205858-CS-INDV / Component 3: Project mana Individual Consult Under Implement IDA / 66860 Post Open 13,200.00 0.00 2020-11-27 2020-11-25 2021-01-15 2021-02-05 2021-03-12 2022-03-07 Recrutement de deux (2) Ch gement ant Selection ation auffeurs CI-PARU-205860-CS-INDV / Component 3: Project mana Individual Consult Recrutement d'un Spécialist IDA / 66860 Post Open 43,200.00 38,783.66 Completed 2020-11-30 2020-11-25 2021-01-18 2021-02-15 2021-02-08 2021-02-26 2021-03-15 2021-03-02 2022-03-10 2022-03-16 gement ant Selection e Suivi-Evaluation CI-PARU-205861-CS-INDV / Component 3: Project mana Individual Consult Recrutement d'un Spécialist IDA / 66860 Post Open 43,200.00 36,549.58 Signed 2020-11-30 2020-11-25 2021-01-18 2021-02-15 2021-02-08 2021-03-15 2021-03-15 2021-03-16 2022-03-10 gement ant Selection e des déchets solides CI-PARU-205863-CS-INDV / Recrutement d'un Spécialist Component 3: Project mana Individual Consult Under Implement IDA / 66860 Post Open 43,200.00 0.00 2020-11-30 2020-12-03 2021-01-18 2021-02-08 2021-03-15 2022-03-10 e en Technologie Numérique gement ant Selection ation et Géospacial (système d'al erte précoce) Page 11 CI-PARU-205864-CS-INDV / Component 3: Project mana Individual Consult Under Implement Recrutement d'un Ingénieur IDA / 66860 Post Open 43,200.00 0.00 2020-11-30 2020-11-25 2021-01-18 2021-02-08 2021-03-15 2022-03-10 gement ant Selection ation drainage urbain CI-PARU-205865-CS-INDV / Recrutement d'un (1) Spécia Component 3: Project mana Individual Consult IDA / 66860 Post Open 43,200.00 38,783.66 Signed 2020-12-02 2020-11-25 2021-01-20 2021-02-15 2021-02-10 2021-02-26 2021-03-17 2021-03-02 2022-03-17 liste en Communication/Mar gement ant Selection keting Social et Développem ent Communautaire CI-PARU-213934-CS-INDV / Sélection d'un Consultant po ur la réalisation du PAR des Component 1: Flood risk mi Individual Consult Under Implement travaux de construction des IDA / 66860 tigation infrastructure and s Post Open 100,000.00 0.00 2021-02-04 2021-05-01 2021-03-25 2021-04-15 2021-05-20 2021-11-16 ant Selection ation ouvrages de drainage des e ervices aux pluviales de GESCO, rou te de Dabou, Commune de Y opougon. CI-PARU-213940-CS-INDV / Sélection d'un Consultants fi Component 1: Flood risk mi Individual Consult Pending Impleme rmes pour l’élaboration des IDA / 66860 tigation infrastructure and s Post Open 100,000.00 0.00 2021-02-26 2021-04-16 2021-05-07 2021-06-11 2021-12-08 ant Selection ntation (PAR) des personnes affecté ervices es par les travaux de revégé talisation CI-PARU-213955-CS-INDV / Sélectionu d'un Consultant I Component 2: Improvemen ndividuel pour la réalisation t of solid waste manageme Individual Consult Pending Impleme du PAR pour les travaux de IDA / 66860 Post Open 100,000.00 0.00 2021-01-28 2021-03-18 2021-04-08 2021-05-13 2021-11-09 nt infrastructure and servic ant Selection ntation constructions des infrastruct es ures du projet d'optimisatio n de la gestion des déchets solides dans le DAA CI-PARU-213958-CS-INDV / Sélection d'un Consultant po Component 2: Improvemen ur la réalisation du PAR pour t of solid waste manageme Individual Consult Pending Impleme les travaux de constructions IDA / 66860 Post Open 100,000.00 0.00 2021-01-27 2021-03-17 2021-04-07 2021-05-12 2021-11-08 nt infrastructure and servic ant Selection ntation des infrastructures du projet es de gestion des déchets solid es dans l'intercommunalité de Yamoussoukro, Bouaké CI-PARU-213961-CS-INDV / Sélection d'un Consultant In Component 2: Improvemen dividuel pour la réalisation d t of solid waste manageme Individual Consult Pending Impleme u PAR pour les travaux de c IDA / 66860 Post Open 100,000.00 0.00 2021-01-26 2021-03-16 2021-04-06 2021-05-11 2021-11-07 nt infrastructure and servic ant Selection ntation onstructions des infrastructu es res du projet de gestion des déchets solides dans l'interc ommunalité de Korhogo_Fer ké CI-PARU-213971-CS-INDV / Component 3: Project mana Individual Consult Pending Impleme Sélection d'un prestataire p IDA / 66860 Post Limited 400.00 0.00 2021-01-27 2021-02-01 2021-02-22 2021-03-29 2021-09-25 gement ant Selection ntation our la conception du LOGO d u PARU CI-PARU-213974-CS-INDV / Sélection d'un(e) Consultant (e) pour l'élaboration du Pla Component 3: Project mana Individual Consult IDA / 66860 Post Open 14,000.00 15,190.07 Signed 2021-04-14 2021-03-15 2021-06-02 2021-06-08 2021-06-23 2021-06-17 2021-07-28 2021-06-19 2022-01-24 n d'actions de prévention et gement ant Selection de lutte contre les VBG/VCE et la formation des Parties p renantes CI-PARU-226496-CS-INDV / Recrutement d’un Consultan t Individuel pour l’actualisati Component 1: Flood risk mi Individual Consult Under Implement on du Plan d’Action et de Ré IDA / 66860 tigation infrastructure and s Post Limited 53,640.00 0.00 2021-04-23 2021-04-29 2021-04-28 2021-05-19 2021-06-23 2021-12-20 ant Selection ation installation (PAR) des person ervices nes affectées par la constru ction des ouvrages de drain age des eaux pluviales de G rand-Bassam CI-PARU-236696-CS-INDV / Recrutement d'un consultan Component 1: Flood risk mi t pour l'élaboration du PAR d Individual Consult Under Implement IDA / 66860 tigation infrastructure and s Post Open 100,000.00 0.00 2021-06-28 2022-09-13 2021-08-16 2021-09-06 2021-10-11 2022-04-09 es travaux d''aménagement ant Selection ation ervices des deux cuvettes d'Anonko ua et Agouetto et travaux ro utiers associés d'Abobo CI-PARU-236727-CS-INDV / Recrutement de consultants Component 1: Flood risk mi pour l'élaboration des PAR d Individual Consult Under Implement IDA / 66860 tigation infrastructure and s Post Open 100,000.00 0.00 2021-07-05 2022-10-27 2021-08-23 2021-09-13 2021-10-18 2022-04-16 es travaux de construction d ant Selection ation ervices es ouvrages de drainage de s eaux pluviales de Bonoumi n dans la commune de Coco dy CI-PARU-244988-CS-INDV / Component 3: Project mana Individual Consult Under Implement IDA / 66860 Post Open 36,000.00 0.00 2021-08-02 2021-08-11 2021-09-20 2021-10-11 2021-11-15 2022-05-14 Recrutement d'un comptabl gement ant Selection ation e principal CI-PARU-236873-CS-INDV / Sélection d'un consultant po Component 1: Flood risk mi ur la réalisation de l'extensi Individual Consult IDA / 66860 tigation infrastructure and s Post Limited 6,030.00 0.00 Canceled 2021-09-06 2021-09-11 2021-10-02 2021-11-06 2022-05-05 on du système intégré de ge ant Selection ervices stion du foncier urbain dans les villes secondaires identifi ées (Bouaflé et Katiola) CI-PARU-236876-CS-INDV / Sélection de consultant pour Component 1: Flood risk mi Individual Consult la réalisation de l'extension IDA / 66860 tigation infrastructure and s Post Limited 6,030.00 0.00 Canceled 2021-09-06 2021-09-11 2021-10-02 2021-11-06 2022-05-05 ant Selection du système intégré de gesti ervices on du foncier urbain dans la ville secondaire de Divo CI-PARU-236878-CS-INDV / Sélection d'un consultant po Component 1: Flood risk mi ur la réalisation de l'extensi Individual Consult IDA / 66860 tigation infrastructure and s Post Limited 6,030.00 0.00 Canceled 2021-09-06 2021-09-11 2021-10-02 2021-11-06 2022-05-05 on du système intégré de ge ant Selection ervices stion du foncier urbain dans les villes secondaires identifi ées (Duékoué et Guiglo) CI-PARU-257256-CS-CDS / S ELECTION DIRECTE POUR LA CONCEPTION, LE DEPLOIEM ENT DU SYSTEME DE PREVIS Component 1: Flood risk mi Under Implement ION ET D'ALERTE PRECOCE ( IDA / 66860 tigation infrastructure and s Post Direct Selection Direct 607,245.00 0.00 2021-12-01 2021-09-08 2021-12-11 2022-02-14 2022-08-13 ation SPAP) DES INONDATIONS ET ervices LA MISE EN PLACE D'UN DIS POSITIF DE MISE EN OEUVRE DES MESURES D'URGENCE DANS LE DISTRICT AU CI-PARU-267921-CS-INDV / Recrutement d'un consultan Component 1: Flood risk mi t individuel pour l'actualisati Individual Consult Pending Impleme IDA / 66860 tigation infrastructure and s Post Limited 76,000.00 0.00 2020-01-20 2020-01-25 2020-02-15 2020-03-21 2020-09-17 on des études APD pour les ant Selection ntation ervices travaux de drainage des eau x pluviales et préparation du DAO de la ville de Bouaké CI-PARU-267922-CS-INDV / Recrutement d'un consultan t individuel pour l'actualisati Component 1: Flood risk mi Individual Consult ondes études APD pour les t IDA / 66860 tigation infrastructure and s Post Limited 76,000.00 0.00 Signed 2020-02-06 2020-01-20 2020-02-11 2019-11-14 2020-03-03 2019-12-11 2020-04-07 2020-10-04 ant Selection ravaux de drainage des eau ervices x pluviales des eaux pluviale s et préparation du DAO À A nonkoi Kouté:Commune d'A bobo Page 12 CI-PARU-267920-CS-INDV / Recrutement d'un consultan t individuel pour l'élaboartio Component 1: Flood risk mi n du Plan d'Action et de Rei Individual Consult Pending Impleme IDA / 66860 tigation infrastructure and s Post Limited 53,200.00 0.00 2020-01-14 2020-01-19 2020-02-09 2020-03-15 2020-09-11 nstallation des personnes af ant Selection ntation ervices fectée par le projet de const ruction des ouvrages de drai nage des eaux pluviales à A nonkoua kouté, Abobo CI-PARU-236449-CS-INDV / Recruter un consultant pour Component 1: Flood risk mi l'évaluation de la mise en œ Individual Consult IDA / 66860 tigation infrastructure and s Post Limited 3,500.00 0.00 Canceled 2021-11-15 2021-11-20 2021-12-11 2022-01-15 2022-07-14 uvre du PAR des travaux de ant Selection ervices construction des ouvrages d e drainage des eaux pluviale s de Grand Bassam CI-PARU-244992-CS-INDV / Recrutement d'un consultan Component 1: Flood risk mi t pour la réalisation du PAR Individual Consult IDA / 66860 tigation infrastructure and s Post Limited 100,000.00 0.00 Canceled 2021-10-05 2021-10-10 2021-10-31 2021-12-05 2022-06-03 pour les travaux de pose de ant Selection ervices collecteurs EU et EP dans les communes de Marcory et Ko umassi CI-PARU-205859-CS-INDV / Component 3: Project mana Individual Consult IDA / 66860 Post Open 8,400.00 0.00 Canceled 2020-11-27 2021-09-19 2021-01-15 2021-02-05 2021-03-12 2022-03-07 Recrutement d'un (1) Agent gement ant Selection de liaison CI-PARU-155249-CS-INDV / Recrutement d’un Consultan t Individuel pour l’élaboratio Individual Consult / Post Limited 18,000.00 0.00 Canceled 2020-03-31 2020-04-05 2020-04-26 2020-05-31 2020-11-27 n des Mécanismes de Gestio ant Selection n des Plaintes (GRM) du Proj et d’Assainissement et de R ésilience Urbaine. CI-PARU-236486-CS-INDV / Recrutement d'un consultan Component 1: Flood risk mi t pour la mise en œuvre du Individual Consult IDA / 66860 tigation infrastructure and s Post Limited 3,090.00 0.00 Canceled 2021-12-01 2021-12-06 2021-12-27 2022-01-31 2022-07-30 PAR des travaux de construc ant Selection ervices tion des ouvrages de draina ge des eaux pluviales d'Ano nkoua Kouté CI-PARU-236584-CS-INDV / Component 1: Flood risk mi Individual Consult Recrutement des opérateurs IDA / 66860 tigation infrastructure and s Post Limited 18,090.00 0.00 Canceled 2021-12-01 2021-12-06 2021-12-27 2022-01-31 2022-07-30 ant Selection pour la mise en place du SA ervices P CI-PARU-236680-CS-INDV / Recrutement de consultants Component 2: Improvemen pour l'élaboration des Plans t of solid waste manageme Individual Consult d’Action et de Réinstallation IDA / 66860 Post Limited 100,000.00 0.00 Canceled 2021-06-28 2021-07-03 2021-07-24 2021-08-28 2022-02-24 nt infrastructure and servic ant Selection (PAR) des personnes affecté es es par les travaux de constr uctions de la déchetterie de Bingerville CI-PARU-236526-CS-INDV / Recrutement d'un consultan t individuel pour l'évaluation Component 1: Flood risk mi de la mise en œuvre du PAR Individual Consult IDA / 66860 tigation infrastructure and s Post Limited 3,090.00 0.00 Canceled 2021-12-01 2021-12-06 2021-12-27 2022-01-31 2022-07-30 des travaux de construction ant Selection ervices des ouvrages de drainage d es eaux pluviales de GESCO, route de Dabou, Commune de Yopougon CI-PARU-236495-CS-INDV / Recrutement d'un consultan t pour l'évaluation de la mis Component 1: Flood risk mi Individual Consult e en œuvre du PAR des trav IDA / 66860 tigation infrastructure and s Post Limited 3,090.00 0.00 Canceled 2021-12-01 2021-12-06 2021-12-27 2022-01-31 2022-07-30 ant Selection aux d''aménagement des de ervices ux cuvettes d'Anonkoua et A gouetto et travaux routiers associés d'Abobo CI-PARU-213937-CS-INDV / Sélection d'une firme pour l’ élaboration du Plan d’Action Component 1: Flood risk mi Individual Consult et de Réinstallation (PAR) de IDA / 66860 tigation infrastructure and s Post Open 100,000.00 0.00 Canceled 2021-02-26 2021-04-16 2021-05-07 2021-06-11 2021-12-08 ant Selection s personnes affectées par le ervices s travaux de sécurisation et de valorisation des berges d u canal Anoumabo à Kouma ssi – Marcory CI-PARU-213975-CS-INDV / Sélection d'un consultant in Component 3: Project mana Individual Consult dividuel pour la mise en plac IDA / 66860 Post Open 17,500.00 0.00 Canceled 2021-03-16 2021-05-04 2021-05-25 2021-06-29 2021-12-26 gement ant Selection e et former les parties sur le mécanisme de gestion des p laintes CI-PARU-213943-CS-INDV / Sélection d'un Consultant In Component 1: Flood risk mi dividuel pour l’élaboration d Individual Consult IDA / 66860 tigation infrastructure and s Post Open 100,000.00 0.00 Canceled 2021-03-18 2021-05-06 2021-05-27 2021-07-01 2021-12-28 u Plan d’Action et de Réinsta ant Selection ervices llation (PAR) des personnes affectées par les travaux de lutte contre l'érosion CI-PARU-288826-CS-INDV / Recrutement d'une ONG pou r accompagner la mise en o Component 1: Flood risk mi Individual Consult Pending Impleme euvre du PAR des travaux d IDA / 66860 tigation infrastructure and s Post Limited 6,000.00 0.00 2022-05-18 2022-05-23 2022-06-13 2022-07-18 2023-01-14 ant Selection ntation e construction des ouvrages ervices de drainage des eaux pluvia les de Bonoumin dans la co mmune de Cocody CI-PARU-290398-CS-INDV / Recrutement d'un consultan t pour la réalisation du PAR Component 2: Improvemen des personnes affectées pou t of solid waste manageme Individual Consult Pending Impleme IDA / 66860 Post Limited 130,000.00 0.00 2022-10-12 2022-10-17 2022-11-07 2022-12-12 2023-06-10 r les travaux du projet de m nt infrastructure and servic ant Selection ntation odernisation et de gestion in es tercommunale des déchets solides des villes de Korhog o, Sinématiali, Ferké et Oua ngolodougou CI-PARU-290769-CS-INDV / Sélection d'un consultant in dividuel pour l'élaboration d Component 3: Project mana Individual Consult Pending Impleme IDA / 66860 Post Limited 40,000.00 0.00 2022-05-31 2022-06-05 2022-06-26 2022-07-31 2023-01-27 u Cadre de Politique de Réin gement ant Selection ntation stallation (CPR) du Projet de Développement Durable et I nclusif des Villes du Nord (P DVN) CI-PARU-290770-CS-INDV / Sélection d'un consultant in dividuel pour l'élaboration d Component 3: Project mana Individual Consult Pending Impleme u Cadre de Gestion Environn IDA / 66860 Post Limited 41,000.00 0.00 2022-05-31 2022-06-05 2022-06-26 2022-07-31 2023-01-27 gement ant Selection ntation ementale et Sociale (CGES) du Projet de Développement Durable et Inclusif des Villes du Nord (PDVN) CI-PARU-290771-CS-INDV / Sélection d'un consultant in Component 3: Project mana Individual Consult Pending Impleme dividuel pour l'élaboration d IDA / 66860 Post Limited 33,000.00 0.00 2022-05-31 2022-06-05 2022-06-26 2022-07-31 2023-01-27 gement ant Selection ntation u PPSD du Projet de Dévelop pement Durable et Inclusif d es Villes du Nord (PDVN) Page 13 CI-PARU-290815-CS-INDV / Recrutement d'un Assistant Component 3: Project mana Individual Consult Under Implement IDA / 66860 Post Limited 24,000.00 0.00 2022-05-31 2022-05-10 2022-06-05 2022-05-13 2022-06-26 2022-05-27 2022-07-31 2023-01-27 en Passation des Marchés p gement ant Selection ation our le compte du PARU CI-PARU-290816-CS-INDV / Component 3: Project mana Individual Consult Under Implement Recrutement d'un Assistant IDA / 66860 Post Limited 24,000.00 0.00 2022-05-31 2022-07-06 2022-06-05 2022-06-26 2022-07-31 2023-01-27 gement ant Selection ation Comptable pour le compte d u PARU CI-PARU-236587-CS-INDV / Recruter un consultant pour Component 1: Flood risk mi Individual Consult l'élaboration du texte du Co IDA / 66860 tigation infrastructure and s Post Limited 50,000.00 0.00 Canceled 2021-08-02 2021-08-07 2021-08-28 2021-10-02 2022-03-31 ant Selection de d’Alerte National, y comp ervices ris des protocoles d'alertes CI-PARU-320438-CS-INDV / Recrutement d'un consultan t pour l'élaboration du Plan Component 1: Flood risk mi Individual Consult Under Implement d'Action de Réinstallation (P IDA / 66860 tigation infrastructure and s Post Limited 80,000.00 0.00 2022-10-30 2022-10-27 2022-11-04 2022-11-03 2022-11-25 2023-02-09 2022-12-30 2023-06-28 ant Selection ation AR) des travaux de protectio ervices n et de végétalisation des ta lus des quartiers Gbébouto et Bidjiké dans la commune d'Attécoubé. CI-PARU-213947-CS-INDV / Sélection d'un Consultant po Component 1: Flood risk mi Individual Consult ur animer un seminaire sur l IDA / 66860 tigation infrastructure and s Post Open 10,000.00 0.00 Canceled 2021-03-16 2021-05-04 2021-05-25 2021-06-29 2021-12-26 ant Selection es rôles, responsabilités et p ervices rérogatives des acteurs du s ystème d'alerte précoce CI-PARU-168279-CS-CDS / C ontrat de service avec le ca binet ANVIPUR, pour effectu Component 1: Flood risk mi er des prélèvements et des IDA / V2850 tigation infrastructure and s Post Direct Selection Direct 12,708.55 0.00 Canceled 2020-04-30 2020-05-10 2020-07-14 2021-01-10 analyses de cinq (5) échantil ervices lons de sols et de trois (3) é chantillons d'eaux usées da ns le cadre des activités du PARU. CI-PARU-168278-CS-CDS / C ontrat de services avec le ca binet ACG-CI pour l'implanta Component 1: Flood risk mi tion de l'emprise de collecte IDA / V2850 tigation infrastructure and s Post Direct Selection Direct 12,727.27 0.00 Canceled 2020-04-30 2020-05-10 2020-07-14 2021-01-10 ur dans le cadre de l'actualis ervices ation des études APD pour tr avaux de drainage des EP et préparation des DAO dans le s zones d'Abobo et Grand-B assam CI-PARU-267919-CS-CDS / S élection par entente directe Component 1: Flood risk mi du Cabinet ENVIPUR pour eff IDA / 66860 tigation infrastructure and s Post Direct Selection Direct 16,495.00 0.00 Canceled 2020-01-15 2020-01-25 2020-03-30 2020-09-26 ectuer des prélèvements et ervices des analyses de cinq (5) éch antillons d'eaux usées dans l e cadre des activités du PAR U CI-PARU-213946-CS-INDV / Component 1: Flood risk mi Sélection d'un Consultant po Individual Consult IDA / 66860 tigation infrastructure and s Post Open 40,000.00 0.00 Canceled 2021-02-17 2021-04-07 2021-04-28 2021-06-02 2021-11-29 ur la réalisation des projets ant Selection ervices de textes juridiques sur le sy stème d'alerte précoce CI-PARU-323860-CS-INDV / Recrutement d'un consultan t pour l'élaboration du Plan d'Action de Réinstallation (P Component 1: Flood risk mi Individual Consult Under Implement AR) des travaux d'aménage IDA / 66860 tigation infrastructure and s Post Limited 80,000.00 0.00 2022-11-30 2022-11-26 2022-12-05 2022-12-07 2022-12-26 2023-02-09 2023-01-30 2023-07-29 ant Selection ation ment des ouvrages de drain ervices age des eaux pluviales dans le bassin versant de la rivier a (talweg de m'pouto) dans l a commune de Cocody CI-PARU-339627-CS-INDV / Recrutement d'un consultan t pour l'évaluation de la mis Component 1: Flood risk mi e en œuvre du Plan d'Action Individual Consult Pending Impleme IDA / 66860 tigation infrastructure and s Post Limited 30,000.00 0.00 2023-04-03 2023-04-08 2023-04-29 2023-06-03 2023-11-30 et de Réinstallation (PAR) de ant Selection ntation ervices s travaux de construction de s ouvrages de drainage des eaux pluviales d'Anonkoua K outé dans la commune d'Ab obo CI-PARU-350133-CS-INDV / Component 2: Improvemen Recrutement de consultant i t of solid waste manageme Individual Consult Pending Impleme ndividuel pour la réalisation IDA / 66860 Post Limited 50,000.00 0.00 2023-04-28 2023-05-03 2023-05-24 2023-06-28 2023-12-25 nt infrastructure and servic ant Selection ntation du PAR des travaux de const es ruction de la déchetterie de Bingerville CI-PARU-347887-CS-INDV / Recrutement d'un consultan Component 1: Flood risk mi Individual Consult Pending Impleme t pour la réalisation du PAR IDA / 66860 tigation infrastructure and s Post Limited 100,000.00 0.00 2023-08-30 2023-09-04 2023-09-25 2023-10-30 2024-04-27 ant Selection ntation de pose des collecteurs EU e ervices t EP dans les communes de Marcory et Koumassi CI-PARU-348041-CS-INDV / Recrutement de consultant i Component 1: Flood risk mi Individual Consult Pending Impleme ndividuel pour la réalisation IDA / 66860 tigation infrastructure and s Post Open - National 100,000.00 0.00 2023-09-06 2023-10-25 2023-11-15 2023-12-20 2024-06-17 ant Selection ntation du PAR des travaux d'amén ervices agement du bassin versant des rosiers à Cocody Page 14 REPUBLIC OF GUINEA BISSAU, REPUBLIC OF MALI, REPUBLIC OF THE GAMBIIA AND ECOWAS COMMISSION ECOWAS REGIONAL ELECTRICITY ACCESS PROJECT – P164044 I. General  Project: ECOWAS Regional Electricity Access Project (IDA CREDIT No. XXX  Project Implementation agency: Regional Coordination Unit - Directorate of Energy of ECOWAS COMMISSION  Project ID No: P164044  Date of General Procurement Notice: MM/DD/YYYY 1. Period covered by this Procurement Plan: August 2018 to February 2020 2. Preamble: In accordance with paragraph 5.9 of the “ World Bank Procurement Regulations for IPF Borrowers” (July 2016 revised November 2017) (“Procurement Regulations”) the Bank’ s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plan and conduct all procurement transactions for the Project. II. Goods, Works and Non-Consulting Services 1. List of contract packages to be procured: Prior review thresholds: Method Levels Comments 1. Goods >=US$1,500,000 Prior review 3. Works >= US$5,000,000 Prior review 1 2 3 4 5 6 7 Revie Estimate Expected w Ref Description d Selectio Proposals by Comment . of Cost n Submissio Bank s No. Assignment (USD Method n (Prior / Million) Date Post) Design, supply, install Supply 1 188 Prior 01-Sept-19 distribution install infrastructur e 2. Consulting Services Prior review thresholds: Selection method Prior review Comments level 1. Selection of firms >= US$500,000 Prior review 2. Selection of individual consultants >= US$200,000 Prior review 1 2 3 4 5 6 7 Review Estimated Expected by Ref. Description of Cost Selection Proposals Bank Comments No. Assignment (USD Method Submission (Prior / Million) Date Post) Owner’s 1 6 QCBS Prior 01-Aug-19 engineer PROCUREMENT Western and Central Africa : ECOWAS-Regional Electricity Access Project PLAN General Information Country: Western and Central Africa 2019-02-04 Bank’s Approval Date of the Original Procurement Plan: 2023-06-01 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P164044 GPN Date: 2018-10-08 Project Name: ECOWAS-Regional Electricity Access Project Loan / Credit No: IDA / 63520 Projet d Urgence pour l Amelioration des Services de l eau et l' Electricite Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PRAE 1 FOUR CF 2019 / Acq Program coordination and te Request for Quota Single Stage - One E uisition d'équipement de bur IDA / 63520 Post Limited 2,200.00 1,971.55 Completed 2019-08-05 2019-08-01 2019-09-30 2019-07-14 2020-03-28 2019-07-26 chnical assistance tions nvelope eau pour l'ingénieur électrici en. PRAE 2 FOUR CF 2019 / Acq Program coordination and te Request for Quota Single Stage - One E uisition de matériel informati IDA / 63520 Post Limited 2,350.00 3,243.24 Completed 2019-08-05 2019-08-08 2019-09-30 2019-07-14 2020-03-28 2019-08-01 chnical assistance tions nvelope que pour ingénieur électricie n. PRAE 1 FOUR AON/2019 / Ac Supervision of the constructi Single Stage - One E quisition de deux (2) véhicule IDA / 63520 Post Request for Bids Open - National 112,000.00 0.00 Canceled 2019-10-30 2019-09-05 2019-11-04 2019-09-20 2019-12-16 2019-10-08 2020-01-15 2020-02-19 2020-08-17 on and technical advisory nvelope s double cabines pour le proj et. 3 PRAE ED 2019 / ACQUISITI Program coordination and te ON DE DEUX (2) véhicules do IDA / 63520 Post Direct Selection Direct 112,000.00 69,839.08 Completed 2020-02-26 2020-04-02 2020-03-02 2020-03-12 2020-04-06 2020-03-16 2020-10-03 2020-10-15 chnical assistance uble cabines pour le projet P RAE. 1 CF PRAE 2020 / Acquisition Design, supply and installati de cinq (5) ordinateurs porta Request for Quota Single Stage - One E IDA / 63520 on of electricity distribution i Post Limited 15,500.00 5,975.34 Completed 2020-08-18 2020-11-09 2020-10-13 2020-08-24 2021-04-11 2020-10-01 bles pour le teletravail, pour f tions nvelope nfrastructure aire face a COVID-19 pendan t la quarentaine. PRAE 1 /DC/2022 / Acquisitio n de materiels informatiques Program coordination and te Request for Quota Single Stage - One E IDA / 63520 Post Limited 6,100.00 11,229.24 Completed 2022-06-05 2022-01-26 2022-07-31 2022-05-01 2023-01-27 2022-07-08 pour les deux Ingemieurs ele chnical assistance tions nvelope ctriciens qui seront recrutés au projet PRAE-GB. PRAE 2 /CD/2022 / Acquisitio n de materiel de bureau pour Program coordination and te Request for Quota Single Stage - One E IDA / 63520 Post Limited 4,000.00 3,225.58 Completed 2022-04-05 2022-04-21 2022-05-31 2022-05-01 2022-11-27 2022-05-01 les deux autres Ingenieurs el chnical assistance tions nvelope ectriciens pour le PRAE-GB NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PRAE 1 SQC/2019 / Etudes d Design, supply and installati ’Impact Environnemental et Consultant Qualifi Open - Internationa IDA / 63520 on of electricity distribution i Post 100,000.00 0.00 Canceled 2019-09-24 2019-07-29 2019-10-15 2019-08-06 2019-11-28 2019-10-11 2019-12-28 2020-02-01 2020-07-30 Social – EIES et Plans de Gest cation Selection l nfrastructure ion Environnemental et Socia l – PGES PRAE 2 SQC/2019 / Étude d’I Design, supply and installati Consultant Qualifi Open - Internationa mpact Social et Economique IDA / 63520 on of electricity distribution i Post 100,000.00 0.00 Canceled 2019-09-20 2019-07-23 2019-10-11 2019-07-31 2019-11-24 2019-10-11 2019-12-24 2020-01-28 2020-07-26 cation Selection l (EISE) et Plan d’Action de Réi nfrastructure nstallation (PAR) 1 PRAE SBQC/2019 / Realisat ion de l´audit externe des et Program coordination and te Consultant Qualifi Open - Internationa IDA / 63520 Post 80,000.00 44,090.79 Completed 2020-02-13 2020-01-07 2020-03-05 2020-01-21 2020-04-18 2020-03-26 2020-05-18 2020-05-01 2020-06-22 2020-06-12 2020-12-19 2022-01-09 ets comptables et financiers chnical assistance cation Selection l 2019, 2020 et 2021 du PRAE. 1 PRAE 2019 / Elaboration d es Plans d’Action de Réinstall Design, supply and installati ation des personnes affectée Quality And Cost- Open - Internationa IDA / 63520 on of electricity distribution i Prior 300,000.00 0.00 Canceled 2020-01-31 2020-01-23 2020-02-21 2020-02-05 2020-04-05 2020-05-03 2020-06-02 2020-07-07 2020-08-11 2021-08-11 s par la construction et/ou le Based Selection l nfrastructure renforcement des lignes de tr ansport d’électricité et leurs composantes 2 PRAE 2019 / Etude d’Impa ct Environnemental et Social Design, supply and installati (EIES) en Guinée-Bissau pou Quality And Cost- Open - Internationa IDA / 63520 on of electricity distribution i Post 250,000.00 367,552.79 Signed 2020-01-23 2020-01-22 2020-02-13 2020-01-28 2020-03-28 2020-06-03 2020-04-25 2020-05-11 2020-05-25 2020-06-03 2020-06-29 2020-06-10 2020-08-03 2020-08-04 2021-08-03 r la CONCEPTION, FOURNITU Based Selection l nfrastructure RE ET INSTALLATION D’INFRA STRUCTURES DE DISTRIBUTI ON D’ELECTRICITE. 1 SFQC PRAE 2019 / Elabora tion des Plans d’Action de Réi Design, supply and installati nstallation des personnes aff Quality And Cost- Open - Internationa IDA / 63520 on of electricity distribution i Post 300,000.00 299,516.86 Terminated 2020-05-29 2020-06-03 2020-06-19 2020-06-03 2020-08-02 2020-05-12 2020-08-30 2020-06-22 2020-09-29 2020-07-06 2020-11-03 2020-07-16 2020-12-08 2020-10-11 2021-12-08 ectées par la construction et/ Based Selection l nfrastructure ou le renforcement des ligne s de transport d’électricité et leurs composantes Page 1 FA 1 SFQC/2022 / Recrutem ent d´un bureau pour l´audit financier et comptable du pro Program coordination and te Quality And Cost- Open - Internationa IDA / 63520 Post 80,000.00 0.00 Canceled 2023-05-26 2023-01-27 2023-06-16 2023-07-30 2023-08-27 2023-09-26 2023-10-31 2023-12-05 2024-12-04 jet Regional d´Accès à l´Élect chnical assistance Based Selection l ricité- Guiné-Bissau (PRAE-G B) de la CEDEAO pour l´exerc ice fiscal 2022, 2023 et 2024 1/SQC/PRAE/2023 / Recrute ment d´un bureau pour l´aud it financier et comptable du p Program coordination and te Consultant Qualifi Open - Internationa IDA / 63520 Post 80,000.00 0.00 Signed 2023-04-27 2023-03-20 2023-05-18 2023-03-20 2023-07-01 2023-04-24 2023-07-31 2023-05-11 2023-09-04 2024-03-02 rojet Regional d´Accès à l´Él chnical assistance cation Selection l ectricité- Guiné-Bissau (PRAE -GB) de la CEDEAO pour l´ex ercice fiscal 2022, 2023 et 2 024. INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 01 PRAE/CI/2019 / Recrutem Supervision of the constructi Individual Consult ent d´un Assiatant Technique IDA / 63520 Post Open 150,000.00 1,877.67 Completed 2019-04-15 2019-02-04 2019-06-03 2019-08-05 2019-06-24 2019-08-05 2019-07-29 2019-05-16 2020-01-25 on and technical advisory ant Selection en Electricité. 01 PRAE/CI/2020 / Recrutem Design, supply and installati Individual Consult ent d´un Assiatant Technique IDA / 63520 on of electricity distribution i Post Open 150,000.00 0.00 Canceled 2020-11-30 2020-12-10 2021-01-18 2021-02-08 2021-03-15 2021-09-11 ant Selection en Electricité. nfrastructure 01 PRAE/CI/2020/ / Recrute Design, supply and installati Individual Consult ment d'un ingenieur electrici IDA / 63520 on of electricity distribution i Post Open 150,000.00 0.00 Canceled 2021-01-20 2020-12-23 2021-03-10 2021-03-31 2021-05-05 2021-11-01 ant Selection en. nfrastructure 01/PRAE/ED/2021 / Recrute ment d´un consultant pour u ne contre-expertise des PAR Design, supply and installati de Mansoa et de Bissau visan IDA / 63520 on of electricity distribution i Post Direct Selection Direct 30,000.00 40,867.47 Signed 2021-09-23 2021-07-29 2021-10-03 2021-08-06 2021-12-07 2021-08-16 2022-06-05 t à effectuer des évaluations nfrastructure contradictoires des propriété s, biens et services impactés par le projet. 01/CI/PRAE/2021 / Recrutem Program coordination and te Individual Consult IDA / 63520 Post Open 150,000.00 4,366.69 Signed 2021-11-26 2021-09-22 2022-01-14 2021-11-17 2022-02-04 2021-11-25 2022-03-11 2021-11-26 2022-09-07 ent d´un Ingenieur Electricie chnical assistance ant Selection n. 02 PRAE/ED/2021 / Réalisati Design, supply and installati on de l’étude du PAR pour l IDA / 63520 on of electricity distribution i Post Direct Selection Direct 150,000.00 142,334.69 Signed 2021-11-30 2021-10-23 2021-12-10 2021-09-17 2022-02-13 2021-11-06 2022-08-12 a sous-station de Bambadinc nfrastructure a et Saltinho. PRAE 1 CONS. IND. 2023 / R Design, supply and installati Individual Consult Under Implement ecrutement d´un assistant In IDA / 63520 on of electricity distribution i Post Open - National 150,000.00 0.00 2023-04-29 2023-02-10 2023-06-17 2023-07-08 2023-08-12 2024-02-08 ant Selection ation génieur spécialiste en Energi nfrastructure e electrique PRAE-GB 1 ED 2023 / Recrut ement d´une firme pour la se Program coordination and te Pending Impleme IDA / 63520 Post Direct Selection Direct - National 6,500.00 0.00 2023-12-29 2024-01-08 2024-03-13 2024-09-09 nsibilisation et visuslisation d chnical assistance ntation u projet PRAE-GB PRAE-GB 2 ED 2023 / Signat ure d´une convention avev l´ Autorité Compétente pour l'É Program coordination and te Under Implement IDA / 63520 Post Direct Selection Direct - National 25,000.00 0.00 2024-02-29 2023-05-19 2024-03-10 2023-06-23 2024-05-14 2024-11-10 valuation Environnementale ( chnical assistance ation AAAC) pour suivre les travau x du PRAE-GB dans le domai ne environnemental. PRAE-GB 3 ED 2023 / Signat ure d´une convention avec l'I nstitut de la Biodiversité et d Supervision of the constructi Under Implement IDA / 63520 Post Direct Selection Direct - National 20,000.00 0.00 2023-11-30 2023-05-19 2023-12-10 2023-06-23 2024-02-13 2024-08-11 es Aires Protégées (IBAP) pou on and technical advisory ation r gérer la biodiversité et les A ires Protégées (AP) pendant l e travaux du PRAE-GB. PRAE-GB 4 ED 2023 / Signat ure d´une convention avec le Réseau National de Lutte con tre les Violences Basées sur l Supervision of the constructi Pending Impleme e Genre et les Enfants en Gui IDA / 63520 Post Direct Selection Direct - National 25,000.00 0.00 2024-02-29 2024-03-10 2024-05-14 2024-11-10 on and technical advisory ntation née-Bissau (RENLUV-GC/GB) l utte contre les violences bas ées sur le genre et favorise l' accès à la justice pour suivre travauxPRAE-GB. PRAE-GB 5 ED 2023 / Signat ure d´une convention avec la Direction générale des forêts Supervision of the constructi Under Implement IDA / 63520 Post Direct Selection Direct - National 20,000.00 0.00 2024-03-29 2023-05-19 2024-04-08 2023-06-23 2024-06-12 2024-12-09 et faune le seul service publi on and technical advisory ation c de gestion forestière du pa ys pour suivre le travaux du PRAE-GB.. PRAE-GB 2 CONS IND 2023 / Prolongation du délais du con Program coordination and te Individual Consult Under Implement IDA / 63520 Post Direct - National 74,200.00 0.00 2023-09-28 2023-06-02 2023-10-08 2023-06-15 2023-10-29 2023-12-03 2024-05-31 trat d´un ans avec le Coordo chnical assistance ant Selection ation nnateur du projet PRAE - Gui née-Bissau. PRAE 3 CONS IND 2023 / Pro Program coordination and te Individual Consult Under Implement longation du contrat avec l´a IDA / 63520 Post Direct - National 50,800.00 0.00 2023-11-30 2023-06-02 2023-12-10 2023-06-15 2023-12-31 2024-02-04 2024-08-02 chnical assistance ant Selection ation ssistant en suivi et evaluatio n des projets. PRAE-GB 4 CONS IND 2023 / Prolongation du contrat avec Program coordination and te Individual Consult Under Implement IDA / 63520 Post Direct - National 50,800.00 0.00 2023-10-25 2023-06-02 2023-11-04 2023-06-15 2023-11-25 2023-12-30 2024-06-27 l´assistant tecnique administ chnical assistance ant Selection ation ratif et financiere PRAE GB 5 CONS IND 2023 / Prolongation du contrat avec Program coordination and te Individual Consult Under Implement IDA / 63520 Post Direct - National 50,800.00 0.00 2023-10-10 2023-06-02 2023-10-20 2023-06-15 2023-11-10 2023-12-15 2024-06-12 l´assistant tecnique en Passa chnical assistance ant Selection ation tion des Marchés. PRAE-GB 6 CONS IND 2023 / Program coordination and te Individual Consult Under Implement Prolongation du contrat avec IDA / 63520 Post Direct - National 50,800.00 0.00 2023-08-31 2023-06-02 2023-09-10 2023-06-15 2023-10-01 2023-11-05 2024-05-03 chnical assistance ant Selection ation l´assistant tecnique environn ementaliste. PRAE GB 7 CONS IND 2023 / Program coordination and te Individual Consult Under Implement Prolongation du contrat avec IDA / 63520 Post Direct - National 40,420.00 0.00 2023-11-30 2023-06-02 2023-12-10 2023-06-15 2023-12-31 2024-02-04 2024-08-02 chnical assistance ant Selection ation le tecnicien en PAR. Page 2 PRAE GB 8 CONS IND 2023 / Program coordination and te Individual Consult Under Implement Prolongation du contrat avec IDA / 63520 Post Direct - National 40,420.00 0.00 2023-11-30 2023-06-02 2023-12-10 2023-06-15 2023-12-31 2024-02-04 2024-08-02 chnical assistance ant Selection ation l´assistant spécialiste en ene rgie electrique. Page 3 PROCUREMENT PLAN (Textual Part) Project information: Guyana-Additional Financing-Flood Risk Management Project- Additional Financing - CREDIT NUMBER - 6786- GY, Amendment: CREDIT AGREEMENT – 5474-GY Project Implementation agency: Agriculture Sector Development Unit, Ministry of Agriculture Date of the Procurement Plan: January 30, 2021 Period covered by this Procurement Plan: December 15, 2020 to December 30, 2024 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in Guyana’s Procurement Act 2003 such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Specify for each Goods manufactured in the Borrower’s country, compared with Goods manufactured abroad. The preference is fifteen percent (15%) added to the Carriage and Insurance Paid (CIP) price of the Goods manufactured abroad; and Works in member countries below a specified threshold of per capita gross national income (as defined annually by the Bank), when comparing Bids/Proposals from eligible domestic firms with those from foreign firms. The preference is seven and a half percent (7.5%) added to the price offered by the foreign firms. Other Relevant Procurement Information. Not Applicable. PROCUREMENT Guyana : GY Flood Risk Management PLAN General Information Country: Guyana 2021-02-25 Bank’s Approval Date of the Original Procurement Plan: 2023-06-02 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P147250 GPN Date: Project Name: GY Flood Risk Management Loan / Credit No: IDA / 67860, IDA / 54740 GY FLOOD RISK MNGMT Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GY-GY FRM-224545-CW-RFB / Rehabilitation of existing Irri Priority Works for Flood Risk Single Stage - One E 2022-07-1 IDA / 67860 Post Request for Bids Open - National 2,000,000.00 0.00 Signed 2021-09-27 2021-07-11 2021-10-02 2021-08-12 2021-11-13 2021-08-10 2021-12-13 2021-11-15 2022-01-17 gation Structures on the Nort Reduction nvelope 6 h Eastern Dam of the EDWC GY/AF/IDA/FRMP-CP1-W-DS-0 1 / Variation/Additional/Rema Priority Works for Flood Risk Single Stage - One E 2021-10-2 ining Works on the Constructi IDA / 67860 Post Request for Bids Open - National 600,000.00 0.00 Canceled 2021-01-01 2021-01-06 2021-02-17 2021-03-19 2021-04-23 Reduction nvelope 0 on of North Eastern Dams inc luding the maintenance of Eq uipment etc GY/AF/IDA/FRMP-CP1-W-ICB- 05 / Drainage Intervention at Priority Works for Flood Risk Open - Internationa Single Stage - One E 2022-09-0 Liliendaal & Ogle basins, Gre IDA / 67860 Prior Request for Bids 7,000,000.00 0.00 Canceled 2021-11-20 2021-11-25 2022-01-06 2022-02-05 2022-03-12 Reduction l nvelope 8 ater Georgetown and East Co ast of Demerara, Region No. 4 GY/AF/IDA/FRMP-CP1-W-NCB Request for Bids - -04 / Rehabilitation of existin Priority Works for Flood Risk Single Stage - One E Works (without pr 2023-04-0 g irrigation structures on the IDA / 67860 Post Request for Bids Open - National 1,500,000.00 0.00 Signed 2022-09-26 2022-09-26 2022-10-01 2022-09-27 2022-10-29 2022-10-20 2022-11-05 2022-10-24 2022-12-10 Reduction nvelope equalification) SP 9 North Eastern Dam of the ED D WC Lot 4 Nabaclis and Lot 5 Anns Grove GY/AF/IDA/FRMP-CP1-W-ICB- Request for Bids - 06 / Phase 1 - Drainage Inter Priority Works for Flood Risk Open - Internationa Single Stage - One E Works (without pr Under Imple 2023-11-2 IDA / 67860 Prior Request for Bids 4,000,000.00 0.00 2022-09-22 2022-10-05 2022-09-27 2022-10-05 2022-11-01 2022-11-17 2022-11-08 2022-12-02 2022-11-29 vention - Rehabilitation of Og Reduction l nvelope equalification) SP mentation 9 le and Liliendaal Drainage Ca D tchment Areas GY/AF/IDA/FRMP-CP1-W-ICB- Request for Bids - 02 / Reconstruction of North Priority Works for Flood Risk Open - Internationa Single Stage - One E Small Works SPD Pending Imp 2022-09-0 IDA / 67860 Prior Request for Bids 7,000,000.00 0.00 2021-11-20 2021-11-25 2022-01-06 2022-02-05 2022-03-12 Eastern Dam (from Nabaclis t Reduction l nvelope (1 envelope proce lementation 8 o Buxton/Annadale area). ss) GY/AF/IDA/FRMP-CP1-W-ICB- Request for Bids - 07 / Phase 2 - New Works - D Priority Works for Flood Risk Open - Internationa Single Stage - One E Works (without pr 2024-08-1 rainage Intervention - New W IDA / 67860 Post Request for Bids 3,500,000.00 0.00 Canceled 2022-11-01 2022-11-06 2022-12-21 2023-01-04 2023-01-18 Reduction l nvelope equalification) SP 7 orks at Ogle and Liliendaal Dr D ainage Catchment Areas GY/AF/IDA/FRMP-CP2-W-NCB Request for Bids - -05 / Lots 6,7 & 8 - Rehabilita Priority Works for Flood Risk Single Stage - One E Works (without pr Pending Imp 2024-02-0 IDA / 67860 Post Request for Bids Open - National 2,195,000.00 0.00 2023-06-06 2023-06-11 2023-07-02 2023-07-16 2023-08-06 tion of Existing Structures on Reduction nvelope equalification) SP lementation 2 North Eastern Dam of EDWC D FRMP/NCB/01/2016 / Recons truction of the North Eastern Priority Works for Flood Risk Single Stage - One E 390,920,220. 1,887,409.7 IDA / 54740 Prior Request for Bids Open - National Signed 2016-12-12 2016-07-19 Dam of the East Demerara W Reduction nvelope 00 3 ater Conservancy (EDWC)-Re tender FRMP/ICB/01/2016 / Supply, Delivery and Testing of Earth Priority Works for Flood Risk Open - Internationa Single Stage - One E 1,988,816.6 IDA / 54740 Prior Request for Bids 2,060,000.00 Signed 2016-12-12 2016-07-27 Moving Equipment for East D Reduction l nvelope 7 emerara Water Conservancy (EDWC) (Lots 1 to 3) GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GY/AF/IDA/FRMP-CP2-GO-NC Priority Works for Flood Risk Single Stage - One E Pending Impl B-01 / Purchase of Earth Movi IDA / 67860 Post Request for Bids Open - National 3,000,000.00 0.00 2021-03-28 2021-04-02 2021-05-14 2021-06-13 2021-07-18 2022-01-14 Reduction nvelope ementation ng Equipment GY/AF/IDA/FRMP-CP2-GO-NC Project Management and Im Single Stage - One E IDA / 67860 Post Request for Bids Open - National 120,000.00 0.00 Canceled 2021-04-09 2021-01-18 2021-04-14 2021-05-26 2021-06-25 2021-07-30 2022-01-26 B-02 / Purchase of Vehicles f plementation Support nvelope or ASDU GY/AF/IDA/FRMP-CP2-GO-NC B-07 / Purchase of Earth Harv Priority Works for Flood Risk Single Stage - One E Pending Impl IDA / 67860 Post Request for Bids Open - National 1,000,000.00 0.00 2022-08-08 2022-09-05 2022-10-03 2022-10-31 2022-12-05 2023-06-03 esting Equipment (Mud Bins Reduction nvelope ementation with Pontoons and Crawler ty pe Draglines) GY/AF/IDA/FRMP-CP2-GO-NC B-06 / Purchase of Earth Movi Priority Works for Flood Risk Single Stage - One E ng Equipment (Lot 1 only) (2 IDA / 67860 Prior Request for Bids Open - National 2,000,000.00 0.00 Canceled 2021-07-12 2021-07-14 2021-08-24 2021-09-23 2021-10-28 2022-04-26 Reduction nvelope Amphibious Excavators & 6 S uper Long Reach Excavators) GY/AF/IDA/FRMP-CP2-GO-NC B-08 / Supply, Delivery & Tes ting of Earth Moving Equipme Priority Works for Flood Risk Open - Internationa Single Stage - One E IDA / 67860 Prior Request for Bids 2,000,000.00 0.00 Signed 2021-11-09 2021-11-11 2021-11-30 2021-11-12 2021-12-01 2021-12-10 2021-12-08 2022-01-03 2021-12-29 2022-06-27 nt for the East Demerara Wat Reduction l nvelope er Conservancy (3 Amphibiou s excavator and additional ac cessories) GY/AF/IDA/FRMP-CP2-GO-DIR Project Management and Im Pending Impl -03 / Purchase of Motor Vehic IDA / 67860 Post Direct Selection Direct 63,450.00 0.00 2021-11-17 2021-11-22 2021-12-18 2022-02-16 plementation Support ementation le (4*4) for ASDU GY/AF/IDA/FRMP-CP2-GO-DIR -04 / Supply and Delivery of Project Management and Im Under Imple IDA / 67860 Post Direct Selection Direct 56,550.00 0.00 2021-11-17 2022-01-05 2021-11-22 2021-12-13 2022-02-11 One New Mini-Bus for use to plementation Support mentation transport staff from Project si te to Office. Page 1 NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GY/AF/IDA/FRMP-CP2-NCS-RF Q-01 / Geology Study within t Institutional Strengthening f Request for Quota Single Stage - One E Pending Impl IDA / 67860 Post Limited 75,000.00 0.00 2023-01-11 2023-02-23 2024-04-23 he EDWC for Construction of or Flood Risk Reduction tions nvelope ementation 12 KM of Earthen Embankme nt CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GY/AF/IDA/FRMP-CP1-CS-QC BS-02 / Supervision of Works: Priority Works for Flood Risk Quality And Cost- Pending Impleme IDA / 67860 Post Open - National 100,000.00 0.00 2022-03-20 2022-04-10 2022-05-24 2022-06-21 2022-07-21 2022-08-25 2022-09-29 2023-09-29 Additional/Remaining Work o Reduction Based Selection ntation n the Construction of North E astern Dams GY/AF/IDA/FRMP-CP2-CS-IC-0 7 / Development and Implem Institutional Strengthening f Consultant Qualifi entation of an Emergency Pr IDA / 67860 Post Open - National 50,000.00 0.00 Canceled 2021-11-15 2022-02-04 2021-12-04 2022-01-17 2022-02-16 2022-03-23 2022-09-19 or Flood Risk Reduction cation Selection eparedness Plan (EPP) for the East Coast of Demerara GY/AF/IDA/FRMP-CP3-CS-IC-1 8 / Capacity building activitie s for MoA staff focusing on th Institutional Strengthening f Quality And Cost- Pending Impleme IDA / 67860 Post Open - National 120,000.00 0.00 2022-03-07 2022-03-28 2022-05-11 2022-06-08 2022-07-08 2022-08-12 2022-09-16 2023-09-16 ree major directions: a) hydr or Flood Risk Reduction Based Selection ntation aulic engineering and modelli ng; b) structural engineering; and c) geotechnical engineer ing GY/AF/IDA/FRMP-CP3-CS-LCS Project Management and Im Least Cost Selecti Pending Impleme -15 / Audit Services (Support IDA / 67860 Post Open - National 25,000.00 0.00 2022-06-06 2022-06-27 2022-08-10 2022-09-07 2022-10-07 2022-11-11 2022-12-16 2023-06-14 plementation Support on ntation to Audit Office of Guyana) GY/AF/IDA/FRMP-CP1-CS-QC BS-05 / Supervision of Works: Priority Works for Flood Risk Quality And Cost- Open - Internationa Under Implement IDA / 67860 Post 600,000.00 0.00 2022-07-04 2022-10-04 2022-07-25 2022-09-07 2022-12-16 2022-10-05 2023-01-05 2022-11-04 2023-01-19 2022-12-09 2023-02-14 2023-01-13 2024-01-13 Drainage Interventions at Lili Reduction Based Selection l ation endaal & Ogle basin, ECD GY/AF/IDA/FRMP-CP1-CS-QC BS-04 / Additional Study for Priority Works for Flood Risk Quality And Cost- Open - Internationa IDA / 67860 Post 350,000.00 343,415.38 Signed 2021-10-05 2021-11-01 2021-10-12 2021-11-02 2020-04-14 2021-11-09 2020-06-30 2021-11-16 2020-08-18 2021-12-07 2021-09-10 2021-12-28 2021-12-18 2022-04-28 Drainage Intervention at Lilie Reduction Based Selection l ndaal and Ogle basins GY/AF/IDA/FRMP-CP1-CS-CQ Priority Works for Flood Risk Consultant Qualifi S-01 / Optimization study an IDA / 67860 Post Open - National 40,000.00 0.00 Canceled 2021-10-06 2021-11-08 2021-10-27 2021-12-10 2022-01-09 2022-02-13 2022-08-12 Reduction cation Selection d updating of CSQAP for Nab acalis to Annadale GY/AF/IDA/FRMP-CP1-CS-QC BS-03 / Supervision of Works: Priority Works for Flood Risk Quality And Cost- Open - Internationa IDA / 67860 Post 900,000.00 0.00 Canceled 2021-10-24 2021-11-14 2021-12-28 2022-01-25 2022-02-24 2022-03-31 2022-05-05 2023-05-05 Reconstruction of North East Reduction Based Selection l ern Dam (from Nabaclis to B uxton/Annadale area). GY/AF/IDA/FRMP-CP2-CS-IC-1 7 / Development and Implem Institutional Strengthening f Consultant Qualifi Open - Internationa entation of an Emergency Pr IDA / 67860 Post 50,000.00 0.00 Canceled 2022-06-10 2022-07-06 2022-07-01 2022-07-06 2022-07-22 2022-08-05 2022-09-09 2022-12-08 or Flood Risk Reduction cation Selection l eparedness Plan (EPP) for the East Coast of Demerara GY/AF/IDA/FRMP-CP2-CS-IC-0 9 / Geology Survey and Detai Priority Works for Flood Risk Consultant Qualifi Open - Internationa IDA / 67860 Post 300,000.00 0.00 Canceled 2022-06-16 2023-01-04 2022-07-07 2022-08-20 2022-09-10 2022-10-22 2022-12-21 led Design of EDWC Embank Reduction cation Selection l ment, Region # 4 GY/AF/IDA/FRMP-CP2-QCBS- 10 / Consulting Services: Det ailed Design & Supervision of Institutional Strengthening f Quality And Cost- Open - Internationa East Demerara Water Conser IDA / 67860 Prior 1,175,000.00 0.00 Canceled 2023-01-13 2023-01-19 2023-01-13 2023-01-26 2023-01-20 2023-05-03 2023-02-17 2023-02-24 2023-03-17 2023-04-14 2024-06-12 or Flood Risk Reduction Based Selection l vancy Dam and Preparation of an Emergency Preparedne ss and Response Plan (EPRP) in Region # 4 GY/AF/IDA/FRMP-CP1-CS-QC BS-06 / Supervision of Works: Priority Works for Flood Risk Quality And Cost- Open - Internationa Under Implement Reconstruction of North East IDA / 67860 Post 700,000.00 0.00 2023-06-07 2023-06-12 2023-06-28 2023-08-11 2023-09-08 2023-10-08 2023-11-12 2023-12-17 2024-12-16 Reduction Based Selection l ation ern Dam (between Nabaclis t o Buxton/Annadale area). GY/AF/IDA/FRMP-CP2-CS-CQ S-02 / Optimization study, de Priority Works for Flood Risk Consultant Qualifi Open - Internationa Pending Impleme IDA / 67860 Post 300,000.00 0.00 2023-06-07 2023-06-28 2023-08-11 2023-09-10 2023-10-15 2024-04-12 sign and updated constructio Reduction cation Selection l ntation n methodology (CSQAP) for EDWC Dam GY/IDA/FRMP-CP2-CS-QCBS- 01 (Re-tender) / Supervision Priority Works for Flood Risk Quality And Cost- Open - Internationa of the Reconstruction of the IDA / 54740 Prior 0.00 502,204.94 Signed 2016-12-27 2017-02-14 Reduction Based Selection l North Eastern Dam of the Ea st Demerara Water Conserva ncy (EDWC) GY/IDA/FRMP-CP3-CS-IC-04 / Priority Works for Flood Risk Consultant Qualifi Open - Internationa Hiring of Project Engineer Ms. IDA / 54740 Prior 38,465.00 38,465.00 Signed 2016-12-13 2017-01-02 Reduction cation Selection l Melisa Melinder October GY/IDA/FRMP-CP1-CS-QCBS- 02 / Supervision of Pump Sta Priority Works for Flood Risk Quality And Cost- Open - Internationa IDA / 54740 Prior 0.00 278,207.71 Signed 2017-01-18 2017-02-28 tions at Lusignan, Buxton/Vig Reduction Based Selection l ilance and Hope/Enmore, Eas t Coast Demerara INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 2 GY/AF/IDA/FRMP-CP1-CS-IC-1 Institutional Strengthening f Individual Consult Pending Impleme IDA / 67860 Post Open 60,000.00 0.00 2021-11-20 2022-01-08 2022-01-29 2022-03-05 2022-09-01 9 / Dam Safety Specialist-Pha or Flood Risk Reduction ant Selection ntation se 2 GY/AF/IDA/FRMP-CP3-CS-DC- Priority Works for Flood Risk 21 / Biodiversity study for sel IDA / 67860 Post Direct Selection Direct 160,000.00 0.00 Signed 2021-04-04 2021-06-01 2021-04-14 2021-04-20 2021-06-18 2021-12-15 Reduction ected sections of the EDWC GY/AF/IDA/FRMP-CP3-CS-IC-1 Project Management and Im Individual Consult Under Implement IDA / 67860 Post Open 275,000.00 0.00 2021-04-04 2021-09-09 2021-05-23 2021-10-10 2021-06-13 2021-07-18 2022-01-14 2 / Project Engineer plementation Support ant Selection ation GY/AF/IDA/FRMP-CP2-CS-IC-0 8 / Updating and Training of t Priority Works for Flood Risk Individual Consult Pending Impleme IDA / 67860 Post Open 20,000.00 0.00 2022-06-06 2022-07-25 2022-08-15 2022-09-19 2023-03-18 he Operations and Maintenan Reduction ant Selection ntation ce System (OMS) Plan for the EDWC GY-GY FRM-256517-CS-INDV Project Management and Im Individual Consult IDA / 67860 Post Open 275,000.00 0.00 Under Review 2021-05-25 2022-01-14 2021-07-13 2021-08-03 2021-09-07 2022-09-07 / Senior Procurement Officer plementation Support ant Selection GY/AF/IDA/FRMP-CP1-CS-IC-2 Project Management and Im Individual Consult Under Implement 0 / Hiring of Environmental & IDA / 67860 Post Open 100,000.00 0.00 2021-05-25 2019-10-08 2021-07-13 2019-11-29 2021-08-03 2021-01-02 2021-09-07 2024-03-07 plementation Support ant Selection ation Social Specialist GY/AF/IDA/FRMP-CP3-CS-IC-1 Project Management and Im IDA / 67860 Post Direct Selection Direct 325,000.00 0.00 Under Review 2021-01-01 2022-01-14 2021-01-11 2021-02-01 2022-02-01 0 / Project Coordinator plementation Support GY/AF/IDA/FRMP-CP3-CS-IC-1 Project Management and Im Individual Consult Pending Impleme IDA / 67860 Post Open 200,000.00 0.00 2021-12-15 2022-02-02 2022-02-23 2022-03-30 2022-09-26 4 / Personnel/Administrative plementation Support ant Selection ntation Officer GY/AF/IDA/FRMP-CP3-CS-IC-1 Project Management and Im Individual Consult Pending Impleme IDA / 67860 Post Open 225,000.00 0.00 2021-10-14 2021-12-02 2021-12-23 2022-01-27 2023-01-27 3 / Project Accountant plementation Support ant Selection ntation GY/AF/IDA/FRMP-CP1-CS-DIR -02 / Geology Survey and Det Priority Works for Flood Risk Under Implement IDA / 67860 Post Direct Selection Direct 75,000.00 0.00 2021-11-17 2021-12-01 2021-11-27 2022-01-06 2021-12-28 2022-02-26 ailed Design of EDWC Emban Reduction ation kment, Region # 4 GY/AF/IDA/FRMP-CP3-CS-CD Project Management and Im IDA / 67860 Post Direct Selection Direct 62,800.00 58,875.00 Signed 2022-02-01 2022-02-01 2022-02-01 2022-01-01 2022-02-01 2022-02-02 2023-01-31 S-04 / Project Coordinator Yr plementation Support 2 GY/AF/IDA/FRMP-CP3-CS-CD Project Management and Im IDA / 67860 Post Direct Selection Direct 47,100.00 47,100.00 Signed 2022-02-15 2022-02-15 2022-02-15 2022-01-01 2022-02-15 2022-02-16 2023-02-14 S-05 / Senior Procurement Of plementation Support ficer Yr2 GY/AF/IDA/FRMP-CP3-CS-CD Project Management and Im IDA / 67860 Post Direct Selection Direct 62,800.00 0.00 Signed 2022-11-18 2023-01-02 2022-11-28 2023-01-31 2023-02-01 2024-01-31 S-18 / Project Coordinator Yr plementation Support 3 GY/AF/IDA/FRMP-CP3-CS-CD Project Management and Im IDA / 67860 Post Direct Selection Direct 47,100.00 0.00 Signed 2022-12-28 2023-02-09 2023-01-25 2023-02-01 2023-02-15 2024-02-14 S-19 / Senior Procurement Of plementation Support ficer Yr 3 GY/AF/IDA/FRMP-CP2-CS-IC-1 0 / Development and Implem Institutional Strengthening f Individual Consult IDA / 67860 Post Limited 80,000.00 0.00 Canceled 2023-06-07 2023-06-02 2023-06-12 2023-07-03 2023-07-24 2023-09-22 entation of an Emergency Pr or Flood Risk Reduction ant Selection eparedness Plan (EPP) for ED WC GY/AF/IDA/FRMP-CP1-CS-IC-1 1 / Development and Implem Institutional Strengthening f Individual Consult Open - Internationa Under Implement IDA / 67860 Post 80,000.00 0.00 2023-06-23 2023-06-25 2023-08-04 2023-08-11 2023-08-25 2023-10-24 entation of an Emergency Pr or Flood Risk Reduction ant Selection l ation eparedness Plan (EPP) for ED WC GY/IDA/FRMP-CP2-CS-SS-01 and 02 / Engineering Service s for Dam Design Optimizatio Priority Works for Flood Risk n, Construction Quality Assur IDA / 54740 Prior Direct Selection Direct 0.00 51,741.62 Signed 2015-07-17 Reduction ance System and Dam Safety Monitoring Program Develop ment including an Instrument ation Plan GY/IDA/DRMP-CP3-CS-IC-03 / Priority Works for Flood Risk Individual Consult Hiring of Project Coordinator IDA / 54740 Prior Open 0.00 47,100.00 Signed 2014-12-12 2014-12-02 Reduction ant Selection for the Flood Risk Manageme nt Project GY/IDA/FRMPCP3-CS-IC-03 / Priority Works for Flood Risk Individual Consult IDA / 54740 Prior Open 47,100.00 94,200.00 Signed 2015-11-24 2015-12-02 Contract Renewal for Project Reduction ant Selection Coordinator GY/IDA/FRMP-CP3-CS-IC-06 / Priority Works for Flood Risk Individual Consult IDA / 54740 Prior Open 0.00 51,810.00 Signed 2015-02-20 2015-05-02 HIRING OF PROCUREMENT O Reduction ant Selection FFICER Page 3 18-MONTH PROCUREMENT PLAN Project information: Phase I of Improved Child Survival Program for Human Capital MPA- P167156-- Immunization Plus and Malaria Progress by Accelerating Coverage and Transforming Services (IMPACT) Project Project Implementation Agencies: Federal Ministry of Health (NMEP and NPHCDA) Date of the Procurement Plan: January 1, 2020 Period covered by this Procurement Plan: January 2020 to June 2021 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016), revised on November 1, 2017 and on August 1, 2018 (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the Nigeria Public Procurement Act 2007, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. Not Applicable Procurement of Second-Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables. Not Applicable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: [15% is applicable for those contracts identified in the Procurement Plan tables]; Works: [ 7.5% is applicable for those contracts identified in the Procurement Plan tables] I. Threshold for Prior Review – Goods, Works, Non-Consulting Services and Consulting Services Prior-review Thresholds Thresholds for Procurement Methods High Substanti Moderate Low Risk Goods, IT & Non-Consulting Shortlist of National Procurement Type Risk al Risk Risk Works ($'000) ($'000) ($'000) ($'000) Services Consultants Request Request Engineering Open for for Open Open Open Consultin & Quotatio Quotatio 10,0 15,0 20,0 Internatio National internatio National g Constructio Works n or n or 5,000 00 00 00 nal or ICB or NCB National nal or ICB or NCB National Services n ($'000) ($'000) ($'000) ($'000) ($'000) Supervision Shopping Shopping ($'000) ($'000) ($'000) Goods, IT & Non- 2,0 4,0 6,0 Consulting Services 1,500 00 00 00 ≧ < ≦ ≧ < ≦ < ≦ Consultants 1,0 2,0 4,0 20,0 20,0 5,0 5,0 1 3 5 200 (Firms) 500 00 00 00 00 00 00 00 00 00 00 Post Review: All contracts not subject to prior review shall be subject to post review. Summary of the procurement packages for Goods, Works and Non-Consulting Services (Planned for the first 18 months after project effectiveness): Selec Evaluation Market tion Options Approa Review Meth (Most Expected ch Prequal- Domestic Expected by od Advantageo date of Sr. Contract Estimated (Open- ification Preferenc date of Bank (RFP, us Bid, bid/ No Description Cost (US$) Nation (Yes/ e Contract (Prior/ RFB, BAFO, proposal al/ No) (Yes/No) Signature Post) RFQ, Rated opening Limited DS Criteria etc.) etc.) etc.) Nigeria Malaria Elimination Programme (NMEP) GOODS Procurement of Long Lasting Open- Insecticide Internati Most Treated Nets 45,852,523 3rd Feb 13th July 1 Prior onal RFB Advantageou No Yes (Mass .29 2020 2020 s Bid Campaign & Routine Distribution) Procurement of Artemisinin based Open - Most National 3rd Feb 13th July 2 Combination Post 2,381,472 RFB Advantageou No No 2020 2020 Therapy (ACT)- s Bid (Public and Private) Procurement of Open- Most Rapid National 3rd Feb 13th July 3 Post 1,960,202 RFB Advantageou No No Diagnostics 2020 2020 s Bid Tests (RDTs) Most Artesunate Open- 3rd Feb 13th July 4 Post 420,881.89 RFB Advantageou No No Injection National 2020 2020 s Bid Sulphodoxine/P Most Open - 3rd Feb 13th July 5 yrimethamine_I Post 612,322 RFB Advantageou No No National 2020 2020 PTp s Bid Amodiaquine/Su Most lphodoxine/Pyri 2,990,781. Open - 3rd Feb 13th July 6 Post RFB Advantageou No No methamine 47 National 2020 2020 s Bid (SPAQ) Most Open - 3rd Feb 13th July 7 Sharp Boxes Post 152,122,43 RFB Advantageou No No National 2020 2020 s Bid Most Microscope Open - 3rd Feb 13th July 8 Post 491,031 RFB Advantageou No No commodities National 2020 2020 s Bid NON-CONSULTING SERVICES - NMEP State Malaria Elimination MOU/P Programme erform 10th 2,250,000. 9th July 1 (SMEP) Prior Limited ance Rated Criteria No NA February 00 2020 Performance Contra 2020 Contract and ct Operations National Malaria Elimination MOU/P Programme erform 10th 1,500,000. 9th July 2 (NMEP) Prior Limited ance Rated Criteria No NA February 00 2020 Performance Contra 2020 Contract and ct Operations National Primary Health Care Development Agency (NPHCDA) GOODS Procurement of Most vaccines and 61,380,767 5th Feb 13th July 1 Prior UN RFB Advantageou No No devices for .00 2020 2020 s Bid immunization Procurement and maintenance of Most UN 5th Feb 13th July 2 Generators and Post 900,000.00 RFB Advantageou No No System 2020 2020 Cold Chain s Bid Equipment (CCEs) Procurement and installation of Cold Chain Most 4,500,000. 5th Feb 13th July 3 Hubs (3 Prior UN RFB Advantageou No No 00 2020 2020 walking-in cold s Bid rooms) in Lagos Procurement of Emergency Transport 5th Feb 13th July 4 Service (ETS) Post 45,101.72 Limited RFQ Rated Criteria No No 2020 2020 vouchers, handbooks, and logbooks Procurement of Most Open- 5th Feb 13th July 5 equipment for Post 281,969.00 RFB Advantageou No No National 2020 2020 call centre s Bid Most Procurement of Open- 5th Feb 13th July 6 Post 969,529.00 RFB Advantageou No No 14 vehicles National 2020 2020 s Bid Procurement of 5th Feb 13th July 7 14 computer Post 14,000 Limited RFQ Rated Criteria No No 2020 2020 sets II. Summary of the procurement packages for Consulting Services -Planned for the first 18 months after project effectiveness): Selection Market Method Review Approach Expected Expected Estimate (QCBS, Shortlisti Sr. by Bank (Open - date of bid/ date of Contract Description d Cost FBS, ng No (Prior/ International proposal Contract (US$) LCBS, (Yes/ No) Post) / National/ opening Signature QBS, CQS, etc.) DS etc.) Nigeria Malaria Elimination Programme (NMEP) NGOs Service Contract (for 5 11,525,51 Open 10th Feb 31st Aug 1 Prior QCBS Yes states) 1.00 International 2020 2020 Technical Assistance to SMEP in 5 participating states, 630,000.0 10th Feb 31st July 2 Prior Limited INDV No multiple contracts by 0 2020 2020 different consultants Technical Assistance to NMEP (including procurement 150,000.0 10th Feb 31st July 3 Post Limited INDV No consultant), multiple 0 2020 2020 contracts. Independent Verification 300,000.0 Open- 10th Feb 31st July 4 Post CQS No Agents (IVA) for NGOs 0 National 2020 2020 Social and Behavioral Change 3,000,000. Open 10th Feb 31st Aug 5 Prior QCBS Yes Communication (SBCC) 00 International 2020 2020 Operations research on 2,131,148. Open 10th Feb 31st Aug 6 Prior QCBS Yes disease vector mapping 00 International 2020 2020 Operations research on entomological surveillance by 655,738.0 10th Feb 31st July 7 Prior Direct DS No Nigeria Institute of 0 2020 2020 Medical Research (NIMR) Operations research on therapeutic efficacy by 655,738.0 10th Feb 31st July 8 Prior Direct CDS No Nigeria Institute of 0 2020 2020 Medical Research (NIMR) Consultancy on warehouse 10th Feb 31st July 9 Post 32,131.00 Limited INDV No assessment 2020 2020 Programme Management Training (case management, 2,000,000. 10th Feb 31st July 10 Prior Limited INDV No M&E, IVM etc.) Multiple 00 2020 2020 Contracts National Primary Health Care Development Agency (NPHCDA) Technical assistance support 9,869,000. 10th Feb 31st July 1 to government for polio Prior UN CDS No 00 2020 2020 surveillance Technical assistance support to government for polio 15,301,00 10th Feb 31st July 2 Supplemental Immunization Prior UN CDS No 0.00 2020 2020 Activities (SIAs) surveillance through WHO Technical assistance support to government for polio 4,830,000. 10th Feb 31st July 3 logistics and social Prior UN CDS No 00 2020 2020 mobilization for polio through UNICEF Procurement of consultant for 10th Feb 31st July 4 Post 20,000.00 Limited INDV No landscape survey (SQUATS) 2020 2020 Technical assistance support 837,673.1 10th Feb 31st July 5 Prior Open-National INDV No to 12 SPHCDA PIU 3 2020 2020 Technical assistance support 10th Feb 31st July 6 Post 89,750.63 Limited INDV No to NPHCDA PIU 2020 2020 Procurement of Emergency Transport Services (ETS), MOU with National Union of 530,794.3 10th Feb 31st July 7 Prior Direct CDS No Road Transport Workers 9 2020 2020 (NURTW) and NACTOROMAS Training of ETS service providers, MOU with Federal 207,672.0 10th Feb 31st July 8 Post Direct CDS No Road Safety Commission 0 2020 2020 (FRSC) Conduct PAPA – Lot Quality Assurance Sampling, MOU 2,213,850. 10th Feb 31st July 9 Prior Limited CDS No with National Bureau of 00 2020 2020 Statistics (NBS) Consultancy for RCT research 1,902,356. 10th Feb 31st Aug 10 services with Nigerian Prior Open-National QCBS Yes 00 2020 2020 Universities Procurement of operations 1,689,751. Open- 10th Feb 31st Aug 11 Prior QCBS Yes research services 00 International 2020 2020 Support to Cold Chain Equipment (CCE) 23,000,00 10th Feb 31st July 12 Prior UN CDS No optimization platform 0.00 2020 2020 through UNICEF Technical assistance to 1,553,185. 10th Feb 31st July 13 LGHAs (89 total), multiple Post Open-National INDV No 50 2020 2020 contracts Technical assistance 310,076.0 10th Feb 31st July 14 Post Open-National QCBS Yes management firm 0 2020 2020 10th Feb 31st July 15 IVA for performance contract Post 300,000 Open-National CQS No 2020 2020 Procurement of services 3,203,345 Open- 10th Feb 31st Aug 16 for GIS imagery and Prior QCBS Yes .45 International 2020 2020 microplanning Procurement of Social Behaviour Change Open- 10th Feb 31st Aug 17 Prior 5,000,000 QCBS Yes Communication (SBCC) International 2020 2020 services Contracting of direct 2,000,000. Open- 10th Feb 31st Aug 18 Prior QCBS Yes facility financing firms 00 International 2020 2020 Appendix 1 Letter of Acceptance of the World Bank’s Anti-Corruption Guidelines and Sanctions Framework Date: Invitation of Bids/Proposals No.__________ To: ___________________________________________________________________________ We, along with our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not) consultants and personnel, acknowledge and agree to abide by the World Bank’s policy regarding Fraud and Corruption (corrupt, fraudulent, collusive, coercive, and obstructive practices), as set out and defined in the World Bank’s Anti-Corruption Guidelines1 in connection with the procurement and execution of the contract (in case of award), including any amendments thereto. We declare and warrant that we, along our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not), consultants and personnel, , are not subject to, and are not controlled by any entity or individual that is subject to, a temporary suspension, early temporary suspension, or debarment imposed by a member of the World Bank Group, including, inter alia, a cross-debarment imposed by the World Bank Group as agreed with other international financial institutions (including multilateral development banks), or through the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement. Further, we are not ineligible under the laws or official regulations of [Insert name of Employer as per bidding document] or pursuant to a decision of the United Nations Security Council. We confirm our understanding of the consequences of not complying with the World Bank’s Anti-Corruption Guidelines, which may include the following: a. rejection of our Proposal/Bid for award of contract; b. in the case of award, termination of the contract, without prejudice to any other remedy for breach of contract; and c. sanctions, pursuant to the Bank’s Anti-corruption Guidelines and in accordance with its prevailing sanctions policies and procedures as set forth in the Bank’s Sanctions Framework. This may include a 1Guidelineson Preventing and Combating Fraud and Corruption in Projects Financed by International Bank for Reconstruction and Development Loans and the International Development Agency Credits and Grants, dated October 15, 2006, and revised in January 2011 and July 2016, as they may be revised from time to time. public declaration of ineligibility, either indefinitely or for a stated period of time, (i) to be awarded or otherwise benefit from a Bank-financed contract, financially or in any other manner;2 (ii) to be a nominated3 sub-contractor, consultant, manufacturer or supplier, or service provider of an otherwise eligible firm being awarded a Bank-financed contract; and (iii) to receive the proceeds of any loan made by the Bank or otherwise to participate further in the preparation or implementation of any Bank-financed project. We understand that we may be declared ineligible as set out above upon: a. completion of World Bank Group sanctions proceedings according to its prevailing sanctions procedures; b. cross-debarment as agreed with other international financial institutions (including multilateral development banks); c. the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement; or d. temporary suspension or early temporary suspension in connection with an ongoing World Bank Group sanctions proceeding. For avoidance of doubt, the foregoing effects of ineligibility do not extend to a sanctioned firm’s or individual’s execution of its ongoing Bank-financed contracts (or its ongoing sub-agreements under such contracts) that are not the subject of a material modification, as determined by the Bank. We shall permit, and shall cause our sub-contractors, sub-consultants, agents (whether declared or not), personnel, consultants, service providers or suppliers, to permit the Bank to inspect4 all accounts, records, 2 For the avoidance of doubt, a sanctioned party’s ineligibility to be awarded a contract shall include, without limitation, (i) applying for pre-qualification, expressing interest in a consultancy, and bidding, either directly or as a nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider, in respect of such contract, and (ii) entering into an addendum or amendment introducing a material modification to any existing contract. 3 A nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider (different names are used depending on the particular bidding document) is one which has been: (i) included by the bidder in its pre-qualification application or bid because it brings specific and critical experience and know-how that allow the bidder to meet the qualification requirements for the particular bid; or (ii) appointed by the Borrower. 4 Inspections in this context are usually investigative (i.e., forensic) in nature: they involve fact-finding activities undertaken by the Bank or persons appointed by the Bank to address specific matters related to investigations/audits, such as evaluating the veracity of an allegation of possible Fraud and Corruption, through the appropriate mechanisms. Such activity includes but is not and other documents relating to the procurement process and/or contract execution (in the case of award), and to have them audited by auditors appointed by the Bank. We agree to preserve all accounts, records, and other documents (whether in hard copy or electronic format) related to the procurement and execution of the contract. Name of the Bidder/Consultant: Name of the person duly authorized to sign the Bid/Proposal on behalf of the Bidder/Consultant: Title of the person signing the Letter: limited to accessing and examining a firm's or individual's financial records and information, and making copies thereof as relevant; accessing and examining any other documents, data, and information (whether in hard copy or electronic format) deemed relevant for the investigation/audit, and making copies thereof as relevant; interviewing staff and other relevant individuals; performing physical inspections and site visits; and obtaining third-party verification of information. PROCUREMENT Nigeria : Nigeria Improved Child Survival Program for Human Capital MPA PLAN General Information Country: Nigeria 2022-02-15 Bank’s Approval Date of the Original Procurement Plan: 2023-06-02 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P167156 GPN Date: Project Name: Nigeria Improved Child Survival Program for Human Capital MPA Loan / Credit No: IDA / 65390 Borno MPA Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BOSMEP/GO/RFQ/001/22 / Pr Component 1:Malaria Contro Request for Quota Single Stage - One E IDA / 65390 Post Limited 57,831.00 77,510.33 Completed 2022-03-02 2022-05-19 2022-03-22 2022-06-09 2022-05-21 2022-06-25 ocurement of 1No. Double Ca l tions nvelope bin Hilux BOSMEP/GO/RFQ/003/22 / P Component 1:Malaria Contro Request for Quota Single Stage - One E ROCUREMENT OF OFFICE EQ IDA / 65390 Post Limited 6,260.00 5,302.65 Completed 2022-02-23 2022-05-31 2022-03-15 2022-06-21 2022-05-14 2022-07-02 l tions nvelope UIPMENT AND FURNITURE BOSMEP/GO/RFQ/004/22 / P ROCUREMENT OF OFFICE CO Component 1:Malaria Contro Request for Quota Single Stage - One E IDA / 65390 Post Limited 12,318.00 12,007.07 Completed 2022-03-02 2022-05-25 2022-03-22 2022-06-16 2022-05-21 2022-06-28 MPUTER LAPTOPS, DESK TOP l tions nvelope , PRINTERS AND ACCESORIES BOSMEP/GO/RFQ/005/22 / P ROCUREMENT OF TV SET, RE Component 1:Malaria Contro Request for Quota Single Stage - One E IDA / 65390 Post Limited 1,462.00 1,425.09 Completed 2022-03-12 2022-05-31 2022-04-01 2022-06-21 2022-05-31 2022-07-01 FRIGERATOR DSTV RECEIVER l tions nvelope AND ACCESSORIES NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BO-IMPACT/NC/RFQ/002/202 Component 1:Malaria Contro Request for Quota Single Stage - One E 2 / INSURANCE COVER AND R IDA / 65390 Post Limited 6,939.00 5,580.75 Completed 2022-08-17 2022-07-08 2022-09-15 2022-07-16 2022-09-29 2022-07-23 l tions nvelope EGISTRATION OF VEHICLE CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BOSMEP/CS/RFP/002/22 / IN Component 1:Malaria Contro Consultant Qualifi SURANCE COVER AND REGIS IDA / 65390 Post Limited 6,939.00 0.00 Canceled 2022-03-07 2022-03-09 2022-03-11 2022-03-17 2022-04-16 l cation Selection TRATION OF THE VEHICLE BO-IMPACT/CS/RFP/011/22 / Component 1:Malaria Contro Quality And Cost- Engagement of NGOs/NSAs f IDA / 65390 Prior Open - National 1,552,991.00 0.00 Canceled 2022-05-20 2022-06-10 2022-07-24 2022-08-21 2022-09-20 2022-10-25 2022-11-29 2023-11-29 l Based Selection or the Provision of Malaria Se rvices BO-IMPACT/CS/RFP/001/23 / ENGAGEMENT OF NSAs/NGOs Component 1:Malaria Contro Quality And Cost- IDA / 65390 Post Open - National 1,401,068.00 0.00 Canceled 2023-05-08 2023-05-31 2023-05-12 2023-06-01 2023-05-19 2023-06-02 2023-06-02 2023-06-05 2023-06-16 2024-06-15 FOR THE PROVISION OF MAL l Based Selection ARIA SERVICES IN BORNO ST ATE BO-IMPACT/CS/RFP/003/23 / ENGAGEMENT OF 1 TA TO SU Component 1:Malaria Contro Consultant Qualifi Pending Impleme IDA / 65390 Post Limited 4,826.00 0.00 2023-05-08 2023-05-22 2023-06-21 2023-07-26 2024-05-30 PPORT PIU STAFF ON ENVIRO l cation Selection ntation NMENTAL SAFEGUARD BO-IMPACT/CS/RFP/001/202 3 / ENGAGEMENT OF NSA/NG Component 1:Malaria Contro Quality And Cost- Under Implement IDA / 65390 Prior Open - National 1,401,068.00 0.00 2023-06-05 2023-06-02 2023-06-07 2023-06-08 2023-06-13 2023-06-19 2023-07-04 2023-07-04 2023-07-11 2023-08-01 2024-07-31 O FOR THE PROVISION OF MA l Based Selection ation LARIA SERVICES IN BORNO S TATE INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BO-IMPACT/CS/RFP/007/22 / Engagement of 1 TA Consult Component 1:Malaria Contro Individual Consult ant to support PIU Staff on Pr IDA / 65390 Post Limited 5,349.00 0.00 Canceled 2022-05-25 2022-05-30 2022-06-20 2022-07-25 2023-01-21 l ant Selection ocurement of LLINS and othe r antimalarial Commodities BO-IMPACT/CS/RFP/008/22 / Engagement of 1 TA Consult Component 1:Malaria Contro Individual Consult IDA / 65390 Post Limited 5,349.00 0.00 Canceled 2022-05-16 2022-05-21 2022-06-11 2022-07-16 2023-01-12 ant to support PIU Staff on En l ant Selection vironmental safeguard BO-IMPACT/CS/RFP/009/22 / Engagement of 1 TA Consult Component 1:Malaria Contro Individual Consult IDA / 65390 Post Limited 5,349.00 0.00 Canceled 2022-05-18 2022-05-23 2022-06-13 2022-07-18 2023-01-14 ant to support PIU Staff on In l ant Selection tegrated Vector Management Page 1 BO-IMPACT/CS/RFP/010/22 / Engagement of 1 TA Consult Component 1:Malaria Contro Individual Consult IDA / 65390 Post Limited 5,349.00 0.00 Canceled 2022-05-19 2022-05-24 2022-06-14 2022-07-19 2023-01-15 ant to support PIU Staff on B l ant Selection ehaviour Change Communica tion BO-IMPACT/CS/RFP/006/202 Component 1:Malaria Contro 2 / Development of Flexible A IDA / 65390 Post Direct Selection Direct - National 10,672.00 0.00 Completed 2022-10-31 2022-10-31 2022-11-06 2022-11-08 2022-12-03 2023-01-02 2023-01-04 l ccounting Software (Installati on and Training) BO-IMPACT/CS/RFP/002/23 / Component 1:Malaria Contro Pending Impleme ENGAGEMENT OF EXTERNAL IDA / 65390 Post Direct Selection Direct - National 7,608.00 0.00 2023-05-09 2023-05-11 2023-05-24 2023-05-27 l ntation AUDITOR'S FIRM Page 2 Procurement Plan for TRANSIP (P151819) I. General 1. Bank’s approval Date of the procurement Plan: Original: March 25, 2015: Revision V1 of Updated Procurement Plan, April 24, 2017 2. Date of General Procurement Notice: October 22, 2015 3. Period covered by this procurement plan: The procurement period of project covered from year 2016-2017 II. Goods and Works and non-consulting services 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Procurement Method Prior Review Comments Threshold US$ 1. ICB / NCB (Goods) Above US$ 1.0/0.5m All 2. ICB / NCB (Works) Above US$ 5.0/7.0 m All 3. Non-Consultant Services NA 2. Pre-qualification. Bidders for not identified shall be prequalified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines. 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: Not Applicable 4. Reference to (if any) Project Operational/Procurement Manual: Project Implementation Manual for World Bank Loan Project: Transport Systems Improvement Project, February 2015 issued by AARTB 5. Summary of the Procurement Packages planned during the first 18 months after project effectiveness 1 2 3 4 5 6 7 Ref. Descripti Estimat Packages Domes Review Comme No. on ed tic by Bank nts Cost Prefere (Prior / US$ nce Post) million (yes/no ) April 27, 2017 Summary 20.7 3 No Prior of the ICB (Works) Summary 66.8 4 No Prior ITS and of the ICB other (Goods) Goods Summary 5.0 1 NA Prior of the NCB (Works) Summary 0.45 1 NA Post of the NCB (Goods) Summary 0 0 NA NA of the ICB (Non- Consultant Services) III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Comment Threshold 1. Competitive Methods (Firms) Above US$ 200,000 2. Single Source (Firms) na 3. Individual Above US$ 100,000 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_300,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 Ref. No. Description Estimat Package Review Comment of ed s by Bank s Assignmen Cost (Prior / t US$ Post) million Summary 39.0 22 Prior of number of contracts April 27, 2017 that will be let under QCBS Summary 1.93 5 Post IC of number of contracts that will be let under other methods April 27, 2017 PROCUREMENT Ethiopia : Ethiopia: Transport Systems Improvement Project (TRANSIP) PLAN General Information Country: Ethiopia 2016-07-26 Bank’s Approval Date of the Original Procurement Plan: 2023-06-05 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P151819 GPN Date: Project Name: Ethiopia: Transport Systems Improvement Project (TRANSIP) Loan / Credit No: IDA / 58160, IDA / Q9810 Addis Ababa Road & Transport Bureau Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned ET-AARTB-356-CW-RFB / Con Component A: Traffic Manag Single Stage - One E 2018-11-0 structing A Building for the Tr IDA / 58160 ement and Road Safety in th Prior Request for Bids Open - National 5,000,000.00 0.00 Canceled 2018-01-16 2018-01-21 2018-03-04 2018-04-03 2018-05-08 nvelope 4 affic Control Center e City of Addis Ababa ET-AARTB-199944-CW-RFB / Procurement of Geotechnical Component A: Traffic Manag Investigation Works (investig Single Stage - One E Under Imple 2021-05-1 IDA / 58160 ement and Road Safety in th Post Request for Bids Limited 80,000.00 0.00 2020-10-19 2020-03-27 2020-10-24 2020-03-30 2020-12-05 2020-05-07 2021-01-04 2021-02-08 ation of Subgrade soil, constr nvelope mentation 9 e City of Addis Ababa uction materials and bridge f oundation) for the Main-ITS C onsultancy Service ET-AARTB-242640-CW-RFB / Construction Works of Corrid Request for Bids - Component A: Traffic Manag or 1: Africa Avenue - Bole Me Open - Internationa Single Stage - One E Works (without pr 24,800,000.0 23,956,587. 2023-12-2 IDA / 58160 ement and Road Safety in th Prior Request for Bids Signed 2021-08-09 2021-12-22 2021-08-14 2021-12-30 2021-10-28 2022-05-10 2021-11-27 2022-06-24 2021-12-26 2022-08-30 dhanialem Square - Traffic Po l nvelope equalification) SP 0 04 6 e City of Addis Ababa lice - Misrak Atekalay - British D Embassy Urban Road Project ET-AARTB-358-CW-RFB / Anb Component A: Traffic Manag Open - Internationa Single Stage - One E 10,700,000.0 2019-08-0 essa's operational facilities i IDA / 58160 ement and Road Safety in th Prior Request for Bids 0.00 Canceled 2018-10-16 2018-10-21 2018-12-02 2019-01-01 2019-02-05 l nvelope 0 4 mprovement e City of Addis Ababa ET-AARTB-357-CW-RFB / Con Component A: Traffic Manag Open - Internationa Single Stage - One E 10,000,000.0 2018-12-0 struction of Pedestrian Footb IDA / 58160 ement and Road Safety in th Prior Request for Bids 0.00 Canceled 2018-02-13 2018-02-18 2018-04-01 2018-05-01 2018-06-05 l nvelope 0 2 ridges e City of Addis Ababa GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ET-AARTB-351-GO-RFQ / Pro curement of 4 units four whe Component A: Traffic Manag Request for Quota Single Stage - One E el drive pick up double cabin IDA / Q9810 ement and Road Safety in th Post Limited 350,000.00 259,698.99 Completed 2016-07-18 2016-03-29 2016-09-12 2016-05-17 2017-03-11 2016-06-09 tions nvelope field vehicles (3 for Addis Ab e City of Addis Ababa aba PIU and 1 for FTA PIU) ET-AARTB-5968-GO-RFB / Su Component A: Traffic Manag Open - Internationa Single Stage - One E pply and Installation of Com IDA / 58160 ement and Road Safety in th Prior Request for Bids 10,000,000.00 7,247,035.40 Signed 2017-02-21 2018-06-22 2017-02-26 2018-07-16 2017-04-09 2018-10-02 2017-05-09 2019-05-08 2017-06-13 2019-07-04 2017-12-10 l nvelope munication System for Traffic e City of Addis Ababa Enforcement ET-AARTB-5967-GO-RFB / Pr Component A: Traffic Manag UN Agencies (Dire ocurement of Vehicles and M IDA / 58160 ement and Road Safety in th Prior Direct 4,500,000.00 4,406,580.98 Completed 2017-04-03 2017-06-07 2017-04-08 2017-06-27 2017-05-13 2017-06-14 2017-11-09 2019-03-05 ct) otor cycles for Traffic Police E e City of Addis Ababa nforcement ET-AARTB-40074-RFQ / Proc Component A: Traffic Manag Request for Quota Single Stage - One E Pending Impl urement of IT Equipment for IDA / 58160 ement and Road Safety in th Post Limited 70,000.00 0.00 2018-01-23 2018-03-20 2018-09-16 tions nvelope ementation PIU and AACRA e City of Addis Ababa ET-AARTB-42977-GO-UN / Pr Component A: Traffic Manag UN Agencies (Dire ocurement of Vehicles for An IDA / 58160 ement and Road Safety in th Prior Direct 1,000,000.00 602,208.66 Completed 2018-01-16 2018-02-22 2018-01-21 2018-04-18 2018-02-25 2018-03-26 2018-08-24 2019-06-06 ct) bessa City Bus Service Enter e City of Addis Ababa prise(ACBSE) ET-AARTB-40073-RFQ / Proc Component A: Traffic Manag Request for Quota Single Stage - One E urement of Office furniture fo IDA / 58160 ement and Road Safety in th Post Limited 45,000.00 8,602.75 Signed 2018-01-23 2015-12-18 2018-03-20 2015-12-28 2018-09-16 tions nvelope r PIU and AACRA e City of Addis Ababa ET-AARTB-36632-GO-RFB / P Component A: Traffic Manag rocurement of Light Detectio Open - Internationa Single Stage - One E IDA / 58160 ement and Road Safety in th Prior Request for Bids 1,300,000.00 0.00 Canceled 2018-02-07 2018-02-28 2018-02-12 2018-04-18 2018-03-26 2018-04-25 2018-05-30 2018-11-26 n and Ranging (LIDAR) Spee l nvelope e City of Addis Ababa d Measuring Devices for AAP C ET-AARTB-49178-GO-RFB / T Component A: Traffic Manag Open - Internationa Single Stage - One E raffic enforcement uniforms f IDA / 58160 ement and Road Safety in th Post Request for Bids 550,000.00 0.00 Canceled 2018-11-05 2019-02-12 2018-11-10 2018-12-22 2019-04-10 2019-01-21 2019-08-22 2019-02-25 2019-08-24 l nvelope or traffic police e City of Addis Ababa ET-AARTB-122486-GO-UN / P Component A: Traffic Manag UN Agencies (Dire rocurement of 17 units of ve IDA / 58160 ement and Road Safety in th Prior Direct 2,100,000.00 613,286.33 Signed 2019-07-23 2019-07-30 2019-07-28 2019-08-06 2019-09-23 2019-09-20 2020-03-21 ct) hicles for Addis Ababa Traffic e City of Addis Ababa police ET-AARTB-126997-GO-RFB / Component A: Traffic Manag Procurement of Light Detecti Open - Internationa Single Stage - One E IDA / 58160 ement and Road Safety in th Prior Request for Bids 1,300,000.00 0.00 Canceled 2019-08-13 2019-08-18 2019-09-29 2019-10-29 2019-12-03 2020-05-31 on Ranging (LIDAR) Speed M l nvelope e City of Addis Ababa easuring Device for AAPC ET-AARTB-133497-GO-RFB / Component A: Traffic Manag procurement of Light Detecti Open - Internationa Single Stage - One E IDA / 58160 ement and Road Safety in th Post Request for Bids 1,300,000.00 0.00 Canceled 2019-09-11 2019-09-19 2019-09-16 2019-10-28 2019-10-15 2019-11-27 2019-12-20 2020-01-01 2020-06-29 on and Ranging ( LIDAR) spe l nvelope e City of Addis Ababa ed measuring device ET-AARTB-135746-GO-RFB / Component A: Traffic Manag Procurement of (Traffic Enfor Single Stage - One E IDA / 58160 ement and Road Safety in th Post Request for Bids Open - National 550,000.00 0.00 Canceled 2019-09-26 2019-10-01 2019-10-01 2019-11-12 2019-10-23 2019-12-12 2019-12-22 2020-01-16 2020-07-14 cement) Traffic Police Unifor nvelope e City of Addis Ababa m,Traffic Police Vest,Color Ch alks and LED lencer M3R. ET-AARTB-170834-GO-RFQ / Procurement of COVID 19 pre Component A: Traffic Manag Request for Quota Single Stage - One E Pending Impl vention materials suchas 50, IDA / 58160 ement and Road Safety in th Post Limited 325,000.00 0.00 2020-04-27 2020-05-13 2020-05-28 tions nvelope ementation 000 liters of Hand sanitizer a e City of Addis Ababa nd 50,000 liters of 96% Alcoh ol. Page 1 ET-AARTB-170839-GO-RFQ / Procurement of Covid19 prev Component A: Traffic Manag Request for Quota Single Stage - One E Pending Impl ention materials such as 50,0 IDA / 58160 ement and Road Safety in th Post Limited 325,000.00 0.00 2020-04-27 2020-05-13 2020-05-28 tions nvelope ementation 00 pcs of high quality face m e City of Addis Ababa ask and 60,000 pcs of plastic gloves. ET-AARTB-170858-GO-RFQ / Component A: Traffic Manag Procuerment of COVID 19 pre Request for Quota Single Stage - One E Pending Impl IDA / 58160 ement and Road Safety in th Post Limited 50,000.00 0.00 2020-04-27 2020-05-15 2020-05-30 vention material such as 10, tions nvelope ementation e City of Addis Ababa 000 liters of Bus cleaning che micals (Bleach). ET-AARTB-170861-GO-RFQ / Procuerment of COVID19 pre vention materials such as 50 Component A: Traffic Manag Request for Quota Single Stage - One E Pending Impl pcs of disinfectant back pack IDA / 58160 ement and Road Safety in th Post Limited 50,000.00 0.00 2020-04-27 2020-05-15 2020-05-30 tions nvelope ementation -chemical sprayer,50 pcs of d e City of Addis Ababa isposable long sleeve water r esistant gown and 50 pcs of f ull face shield safety. ET-AARTB-170846-GO-RFQ / Component A: Traffic Manag Procurement of COVID19 pre Request for Quota Single Stage - One E Pending Impl IDA / 58160 ement and Road Safety in th Post Limited 90,000.00 0.00 2020-04-27 2020-05-15 2020-05-30 vention materials such as 30 tions nvelope ementation e City of Addis Ababa 0 pcs of Inferared Thermome ters. ET-AARTB-197329-GO-RFB / Supply, Installation, Operatio Component A: Traffic Manag Open - Internationa Single Stage - Two E n and Maintenance of ITS-ICT IDA / 58160 ement and Road Safety in th Prior Request for Bids 28,100,000.00 0.00 Canceled 2020-10-26 2020-10-31 2021-02-28 2021-06-12 2021-07-17 2023-04-08 l nvelope system for Anbesa City Bus S e City of Addis Ababa ervice Enterprise(ACBSE) ET-AARTB-214155-GO-RFB / Supply, Installation, Operatio Component A: Traffic Manag Open - Internationa Single Stage - One E n and Maintenance of ITS-ICT IDA / 58160 ement and Road Safety in th Prior Request for Bids 28,100,000.00 14,285,385.45 Signed 2021-01-18 2021-02-10 2021-02-02 2021-03-05 2021-06-02 2021-08-24 2021-08-16 2021-10-26 2021-09-20 2021-12-17 2023-06-12 l nvelope system for Anbesa City Bus S e City of Addis Ababa ervice Enterprise(ACBSE) ET-AARTB-222814-GO-RFB / Component A: Traffic Manag Procurement of Low Entry Cit Open - Internationa Single Stage - One E IDA / 58160 ement and Road Safety in th Prior Request for Bids 20,000,000.00 18,358,046.85 Signed 2021-03-31 2021-06-05 2021-04-15 2021-06-15 2021-07-14 2021-10-07 2021-09-12 2022-02-17 2021-10-12 2022-02-19 2022-07-13 y Buses for Anbessa City Bus l nvelope e City of Addis Ababa Service Enterprise (ACBSE) ET-AARTB-228102-GO-RFB / Procurement of the Supply, I Component A: Traffic Manag nstallation and Commissionin Open - Internationa Single Stage - One E IDA / 58160 ement and Road Safety in th Prior Request for Bids 10,000,000.00 0.00 Canceled 2021-04-15 2021-06-05 2021-04-30 2021-06-15 2021-07-29 2021-09-21 2021-09-27 2021-11-25 2021-10-27 2023-07-28 g of Workshop Equipment an l nvelope e City of Addis Ababa d Machineries for Anbessa Ci ty Bus Service Enterprise (AC BSE) ET-AARTB-228107-GO-RFB / Component A: Traffic Manag Open - Internationa Single Stage - One E Procurement of Parking Mana IDA / 58160 ement and Road Safety in th Prior Request for Bids 1,500,000.00 0.00 Canceled 2021-04-15 2021-10-24 2021-04-30 2021-11-24 2021-07-29 2022-01-25 2021-09-27 2022-04-05 2021-10-27 2021-12-20 l nvelope gement Equipment e City of Addis Ababa ET-AARTB-228101-GO-RFB / Procurement of IT Infrastruct ure including Supply, installa Component A: Traffic Manag Open - Internationa Single Stage - One E tion, commissioning, and mai IDA / 58160 ement and Road Safety in th Prior Request for Bids 2,700,000.00 0.00 Canceled 2021-04-30 2021-10-04 2021-05-15 2021-10-09 2021-08-13 2022-01-25 2021-10-12 2022-04-13 2021-11-11 2025-04-27 l nvelope ntenance for the Transport In e City of Addis Ababa frastructure Asset Manageme nt System (TIAMS) of Addis A baba City Roads Authority ET-AARTB-262291-GO-RFB / Supply, Installation, Operatio ns and Maintenance of Traffi Component A: Traffic Manag Open - Internationa Single Stage - One E c Management Centre (TMC) IDA / 58160 ement and Road Safety in th Prior Request for Bids 45,660,000.00 0.00 Signed 2021-11-19 2022-02-17 2021-11-24 2022-08-26 2022-02-22 2022-10-20 2022-04-08 2023-03-17 2022-05-20 2023-12-29 l nvelope Hardware and Software, Traff e City of Addis Ababa ic Signals on Corridor No. 1 a nd ITS Systems on Existing T raffic Signals in Addis Ababa ET-AARTB-267526-GO-RFB / Procurement of the Supply, I Component A: Traffic Manag nstallation and Commissionin Open - Internationa Single Stage - One E IDA / 58160 ement and Road Safety in th Prior Request for Bids 10,000,000.00 0.00 Canceled 2022-01-10 2022-05-26 2022-01-25 2022-06-02 2022-04-25 2022-12-15 2022-06-09 2023-02-03 2022-07-01 2023-05-02 g of Workshop Equipment an l nvelope e City of Addis Ababa d Machineries for Anbessa Ci ty Bus Service Enterprise (AC BSE) ET-AARTB-228107-GO-RFB-2 Component A: Traffic Manag Open - Internationa Single Stage - One E Pending Impl / Procurement of Parking Ma IDA / 58160 ement and Road Safety in th Prior Request for Bids 1,500,000.00 0.00 2022-07-15 2022-07-18 2022-07-24 2022-09-07 2022-10-07 2023-04-08 l nvelope ementation nagement Equipment e City of Addis Ababa ET-AARTB-228101-GO-RFB-2 / Procurement of IT Infrastruc ture including Supply, Install Component A: Traffic Manag Open - Internationa Single Stage - One E Under Imple ation, Commissioning, and M IDA / 58160 ement and Road Safety in th Prior Request for Bids 2,700,000.00 0.00 2022-06-17 2022-08-08 2022-07-02 2022-08-10 2022-09-10 2023-01-12 2022-10-25 2023-04-16 2022-11-24 2026-05-10 l nvelope mentation aintenance for the Transport e City of Addis Ababa Infrastructure Asset Manage ment System (TIAMS) of Addi s Ababa City Roads Authority ET-AARTB-332658-GO-DIR / Component A: Traffic Manag Direct - Internation Procurement of Additional Lo IDA / 58160 ement and Road Safety in th Prior Direct Selection 9,752,000.00 0.00 Signed 2022-12-23 2022-12-20 2022-12-28 2022-12-30 2023-02-01 2023-04-25 2023-07-31 al w Entry City Buses for Anbes e City of Addis Ababa a ET-AARTB-364545-GO-RFQ / Component A: Traffic Manag Request for Quota Single Stage - One E Pending Impl Procurement of Desktops an IDA / 58160 ement and Road Safety in th Post Limited 99,000.00 0.00 2023-06-20 2023-08-15 2024-02-11 tions nvelope ementation d All in one desktop compute e City of Addis Ababa r ET-AARTB-364549-GO-RFQ / Component A: Traffic Manag Request for Quota Single Stage - One E Pending Impl Procurement of Laptop Com IDA / 58160 ement and Road Safety in th Post Limited 50,000.00 0.00 2023-06-20 2023-08-15 2024-02-11 tions nvelope ementation puters e City of Addis Ababa ET-AARTB-364554-GO-RFQ / Component A: Traffic Manag Single Stage - One E Pending Impl Procurement of office Tables IDA / 58160 ement and Road Safety in th Post Request for Bids Open - National 200,000.00 0.00 2023-06-22 2023-06-27 2023-08-08 2023-09-07 2023-10-12 2024-04-09 nvelope ementation and chairs e City of Addis Ababa ET-AARTB-267526-GO-RFB-2 / Procurement of the Supply, Component A: Traffic Manag Installation and Commissioni Open - Internationa Single Stage - One E Under Revie IDA / 58160 ement and Road Safety in th Prior Request for Bids 10,000,000.00 0.00 2023-06-09 2023-06-24 2023-09-22 2023-11-06 2023-11-28 2024-06-25 ng of Workshop Equipment a l nvelope w e City of Addis Ababa nd Machineries for Addis Aba ba City Bus Service Enterpris e (AACBSE) ET-AARTB-359952-GO-DIR / Component A: Traffic Manag Direct - Internation Pending Impl procurement of 4WD pickup IDA / 58160 ement and Road Safety in th Post Direct Selection 1,000,000.00 0.00 2023-06-22 2023-06-27 2023-08-01 2024-01-28 al ementation vehicles and electric automo e City of Addis Ababa biles, Page 2 ET-AARTB-348-GO-RFQ / Pro curement of Office furniture f Component A: Traffic Manag Request for Quota Single Stage - One E Pending Impl or FTA and PIU (Executive off IDA / Q9810 ement and Road Safety in th Post Limited 9,000.00 0.00 2016-07-18 2016-09-12 2017-03-11 tions nvelope ementation ice table, Woden shelf, execu e City of Addis Ababa tive chaires, conference tabl e, and conference chaires ) Component A: Traffic Manag ET-AARTB-409-GO-RFB / Traf Open - Internationa Single Stage - One E IDA / 58160 ement and Road Safety in th Prior Request for Bids 19,000,000.00 0.00 Canceled 2016-10-11 2016-10-16 2016-11-27 2016-12-27 2017-01-31 2017-07-30 fic Enforcement Equipments l nvelope e City of Addis Ababa Component A: Traffic Manag ET-AARTB-352-GO-RFQ / Pro Request for Quota Single Stage - One E IDA / Q9810 ement and Road Safety in th Post Limited 5,000.00 0.00 Canceled 2016-08-20 2016-10-15 2017-04-13 curement of Books tions nvelope e City of Addis Ababa ET-AARTB-345-GO-RFQ / Offi Component A: Traffic Manag Request for Quota Single Stage - One E Pending Impl ce furniture (coffee table,gue IDA / Q9810 ement and Road Safety in th Post Limited 11,000.00 0.00 2016-07-17 2016-09-11 2017-03-10 tions nvelope ementation st chair, Metal shelf, water di e City of Addis Ababa stiller, table coffee) ET-AARTB-344-GO-RFQ / Offi Component A: Traffic Manag Request for Quota Single Stage - One E Pending Impl ce furnitures, (executive tabl IDA / Q9810 ement and Road Safety in th Post Limited 57,000.00 0.00 2016-07-11 2016-07-19 2016-07-24 tions nvelope ementation e and wooden shelf) e City of Addis Ababa Component A: Traffic Manag ET-AARTB-412-GO-RFB / Pro Single Stage - One E IDA / 58160 ement and Road Safety in th Post Request for Bids Open - National 150,000.00 0.00 Canceled 2016-10-25 2016-10-30 2016-12-11 2017-01-10 2017-02-14 2017-08-13 curement of software nvelope e City of Addis Ababa ET-AARTB-414-GO-RFB / Pro Component A: Traffic Manag curement of Office Equipmen Single Stage - One E Pending Impl IDA / 58160 ement and Road Safety in th Post Request for Bids Open - National 150,000.00 0.00 2017-10-03 2017-10-08 2017-11-19 2017-12-19 2018-01-23 2018-07-22 t (Computers and Related ac nvelope ementation e City of Addis Ababa cessories) for TMA ET-AARTB-346-GO-RFQ / Pro Component A: Traffic Manag Request for Quota Single Stage - One E curement of IT equipments ( IDA / Q9810 ement and Road Safety in th Post Limited 5,000.00 44,203.62 Completed 2016-07-17 2015-12-14 2016-09-11 2016-02-18 2017-03-10 2016-05-12 tions nvelope Server, LCD Projector, UPS, T e City of Addis Ababa ablets) ET-AARTB-342-GO-RFB / Sup Component A: Traffic Manag Open - Internationa Single Stage - One E ply & Install Traffic Signal Sys IDA / 58160 ement and Road Safety in th Prior Request for Bids 35,000,000.00 0.00 Canceled 2020-08-25 2020-08-30 2020-10-11 2020-11-10 2020-12-15 2021-06-13 l nvelope tem including traffic control e City of Addis Ababa center system ET-AARTB-349-GO-RFQ / Pro curement of IT equipments fo Component A: Traffic Manag r FTA PIU ( Desk top comp, la Request for Quota Single Stage - One E Pending Impl IDA / Q9810 ement and Road Safety in th Post Limited 18,000.00 0.00 2016-07-25 2016-09-19 2017-03-18 ptop computer, LCD projecto tions nvelope ementation e City of Addis Ababa r, Color printer, All in one pri nter and other computer peri pherals) ET-AARTB-350-GO-RFQ / Pro Component A: Traffic Manag Request for Quota Single Stage - One E curement of application Soft IDA / Q9810 ement and Road Safety in th Post Limited 18,000.00 0.00 Canceled 2016-09-04 2016-10-30 2017-04-28 tions nvelope ware's e City of Addis Ababa Component A: Traffic Manag ET-AARTB-413-GO-RFB / Pro Single Stage - One E IDA / 58160 ement and Road Safety in th Post Request for Bids Open - National 150,000.00 0.00 Canceled 2017-04-04 2017-04-09 2017-05-21 2017-06-20 2017-07-25 2018-01-21 curement of Documents nvelope e City of Addis Ababa ET-AARTB-341-GO-RFB / Sup ply and installation of Equip Component A: Traffic Manag ment and Software for electr Open - Internationa Single Stage - One E IDA / 58160 ement and Road Safety in th Prior Request for Bids 12,300,000.00 0.00 Canceled 2018-07-30 2018-08-04 2018-09-15 2018-10-15 2018-11-19 2019-05-18 onic fare collection and ITS t l nvelope e City of Addis Ababa o support Anbessa Operatio ns and Management Anbessa City Bus Enterprise ET-AARTB-347-GO-RFQ / Pro curement of IT equipments ( Component A: Traffic Manag Request for Quota Single Stage - One E Pending Impl Desk top comp, laptop comp IDA / Q9810 ement and Road Safety in th Post Limited 29,000.00 0.00 2016-07-17 2016-09-11 2017-03-10 tions nvelope ementation uter, Printer, External hard di e City of Addis Ababa sc and other computer perip herals) NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ET-AARTB-316934-NC-DIR / Component A: Traffic Manag Pending Impl Procurement of Conference C IDA / 58160 ement and Road Safety in th Post Direct Selection Direct - National 55,000.00 0.00 2022-09-20 2022-09-25 2022-10-30 2022-11-29 ementation entre for a Capacity Building e City of Addis Ababa Program. CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ET-AARTB-360-CS-QCBS / Pr Component A: Traffic Manag Quality And Cost- Open - Internationa epare Parking Strategy and I IDA / 58160 ement and Road Safety in th Prior 750,000.00 766,245.00 Signed 2016-07-17 2016-08-05 2016-08-07 2016-09-20 2017-02-16 2016-12-18 2017-04-26 2017-01-17 2017-12-05 2017-02-21 2018-05-11 2017-03-28 2018-06-04 2018-03-28 Based Selection l mplementation Program e City of Addis Ababa ET-AARTB-399-CS-QCBS / De Component A: Traffic Manag Quality And Cost- Open - Internationa velopment of Strategic trans IDA / 58160 ement and Road Safety in th Prior 4,000,000.00 4,182,747.51 Signed 2017-02-06 2017-12-22 2017-02-27 2018-01-31 2017-04-12 2018-06-27 2017-07-12 2017-08-11 2018-12-31 2017-09-15 2019-04-15 2017-10-20 2019-05-03 2018-10-20 Based Selection l port master plan for the city e City of Addis Ababa of Addis Ababa ET-AARTB-359-CS-QCBS / Tr Component A: Traffic Manag Quality And Cost- Open - Internationa affic study, design and constr IDA / 58160 ement and Road Safety in th Prior 6,000,000.00 22,233,705.94 Signed 2016-10-18 2016-11-08 2017-01-17 2016-12-22 2018-02-28 2017-02-28 2018-07-19 2017-03-30 2018-10-18 2017-05-04 2018-12-31 2017-06-08 2019-02-05 2017-07-25 Based Selection l uction supervision e City of Addis Ababa ET-AARTB-5966-CS-QCBS / S tudy, Design, and Constructi Component A: Traffic Manag Quality And Cost- Open - Internationa on Supervision of Comprehen IDA / 58160 ement and Road Safety in th Prior 2,500,000.00 3,990,092.03 Signed 2017-02-14 2017-05-05 2017-03-07 2017-05-11 2017-04-20 2018-02-15 2017-06-07 2018-05-22 2017-07-07 2018-09-18 2017-08-11 2019-02-12 2017-09-15 2019-02-27 2018-09-15 Based Selection l sive Transport and Traffic Im e City of Addis Ababa provement Measures for Mer kato Area ET-AARTB-16763-CS-CDS / C onsultancy Service to Provide Component A: Traffic Manag Training on Public Transport Non-Profit Organiz Pending Impleme IDA / 58160 ement and Road Safety in th Post Direct 120,000.00 0.00 2017-06-04 2017-07-14 2017-08-18 2018-02-14 Development and Capacity B ations ntation e City of Addis Ababa uilding Programme using Inte rnational Association of Publi c Transportation /UITP/ Page 3 ET-AARTB-23388-CS-NPO / C onsultancy Service to provid Component A: Traffic Manag e training on Ticketing and F Non-Profit Organiz Pending Impleme IDA / 58160 ement and Road Safety in th Post Direct 32,000.00 0.00 2017-08-10 2017-09-19 2017-10-24 2018-04-22 are Management and Asset ations ntation e City of Addis Ababa Management ( by Internation al Association of Public Trans port (UITP) ET-AARTB-80356-GO-RFB / P Component A: Traffic Manag Quality And Cost- Open - Internationa edestrians Crossing Facility P IDA / 58160 ement and Road Safety in th Prior 750,000.00 523,176.50 Signed 2018-10-15 2018-11-01 2018-11-05 2018-12-04 2018-12-19 2020-01-02 2019-02-17 2020-06-18 2019-03-10 2020-09-01 2019-04-14 2020-10-28 2019-05-19 2020-11-15 2020-05-18 Based Selection l lanning and Detailed Enginee e City of Addis Ababa ring Design ET-AARTB-81969-CS-INDV / Component A: Traffic Manag Consultant Qualifi ESIA and RAP consultant for IDA / 58160 ement and Road Safety in th Post Open - National 77,500.00 70,877.51 Signed 2018-10-22 2018-08-01 2018-11-12 2018-12-26 2019-02-21 2019-01-25 2019-10-10 2019-03-01 2020-10-19 2019-08-28 cation Selection main ITS e City of Addis Ababa ET-AARTB-81971-CS-INDV / Component A: Traffic Manag ESIA and RAP consultant for Consultant Qualifi IDA / 58160 ement and Road Safety in th Post Open - National 45,000.00 87,143.18 Signed 2018-10-22 2018-10-22 2018-11-12 2018-12-26 2019-02-20 2019-01-25 2020-07-03 2019-03-01 2019-08-31 2019-08-28 Comprehensive Transport an cation Selection e City of Addis Ababa d Traffic Improvement Measu res for Merkato Area ET-AARTB-104745-CS-CQS / Component A: Traffic Manag Strategic Environmental and Consultant Qualifi Under Implement IDA / 58160 ement and Road Safety in th Post Open - National 25,000.00 0.00 2019-03-07 2019-03-13 2019-03-28 2019-05-11 2019-06-10 2019-07-15 2020-01-11 Social Assessment (SESA) for cation Selection ation e City of Addis Ababa Drainage Master Plan for Add is Ababa ET-AARTB-104750-CS-CQS / Strategic Environmental and Component A: Traffic Manag Social Assessment (SESA) for Consultant Qualifi IDA / 58160 ement and Road Safety in th Post Open - National 35,000.00 89,833.28 Signed 2019-03-14 2019-03-13 2019-04-04 2019-05-18 2019-08-22 2019-06-17 2020-01-23 2019-07-22 2020-02-19 2020-01-18 Strategic Comprehensive Tra cation Selection e City of Addis Ababa nsport Development Plan (SC TDP) for the City of Addis Ab aba ET-AARTB-106550-CS-LCS / Component A: Traffic Manag Consultancy Service for TRA Least Cost Selecti IDA / 58160 ement and Road Safety in th Post Open - National 25,000.00 15,810.60 Signed 2019-04-02 2019-04-16 2019-04-23 2019-06-16 2019-06-28 2019-07-14 2019-08-01 2019-08-13 2019-09-11 2019-09-17 2019-10-07 2019-10-22 2019-10-12 2020-04-19 NSIP External Audit for 2018/ on e City of Addis Ababa 19 and 2019/20 EFY ET-AARTB-110998-CS-QCBS / Consultancy Service for Adv Component A: Traffic Manag isory Service on Developing Quality And Cost- Open - Internationa IDA / 58160 ement and Road Safety in th Prior 780,000.00 0.00 Canceled 2019-06-30 2019-07-21 2019-09-03 2019-10-01 2019-10-31 2019-12-05 2020-01-09 2021-01-08 an Improved Road Maintenan Based Selection l e City of Addis Ababa ce and Associated Funding St rategy for Addis Ababa city R oad authority ET-AARTB-129212-CS-QCBS / Consultancy Services for Te Component A: Traffic Manag Quality And Cost- Open - Internationa chnical Assistance and Revie IDA / 58160 ement and Road Safety in th Prior 2,136,450.00 0.00 Canceled 2019-09-09 2019-09-02 2019-09-18 2019-09-04 2019-11-01 2020-01-03 2019-11-29 2020-03-12 2019-12-29 2020-09-02 2020-02-02 2020-03-08 2021-03-08 Based Selection l w of Outputs from TRANSIP S e City of Addis Ababa ub-Projects/Activities ET-AARTB-135393-CS-CQS / Component A: Traffic Manag Consultancy Service for TRA Consultant Qualifi IDA / 58160 ement and Road Safety in th Post Open - National 80,000.00 0.00 Canceled 2019-10-16 2019-09-16 2019-11-06 2019-12-20 2020-01-19 2020-02-23 2020-05-23 NSIP Gender Based Violence cation Selection e City of Addis Ababa (GBV) Assessment ET-AARTB-162082-CS-QCBS Component A: Traffic Manag / Consultancy Service for Urb Quality And Cost- Open - Internationa IDA / 58160 ement and Road Safety in th Prior 670,000.00 0.00 Canceled 2020-03-09 2020-03-07 2020-03-30 2020-05-18 2020-05-13 2020-09-06 2020-06-10 2021-01-28 2020-07-10 2020-08-14 2020-09-18 2022-01-11 an Transport Human Capital Based Selection l e City of Addis Ababa Development Framework Pro ject (UT-HCDP) ET-AARTB-162742-CS-CQS / Component A: Traffic Manag Consultant Qualifi Consultancy Service for Gend IDA / 58160 ement and Road Safety in th Post Open - National 80,000.00 0.00 Canceled 2020-03-09 2020-03-06 2020-03-30 2020-05-13 2020-06-12 2020-07-17 2020-10-15 cation Selection er Based Violence assessmen e City of Addis Ababa t for TRANSIP ET-AARTB-163884-CS-QCBS Component B: Improvement Quality And Cost- Open - Internationa Under Implement / Consultancy Service for Tra IDA / 58160 of Integrated Urban Planning Prior 1,500,000.00 0.00 2020-03-18 2020-09-01 2020-04-08 2021-07-10 2020-06-06 2021-11-16 2020-07-21 2022-04-05 2020-09-04 2023-02-28 2020-10-09 2020-11-13 2021-11-13 Based Selection l ation nsit-Oriented Development ( and Transport System TOD) Project ET-AARTB-166326-CS-QCBS Component A: Traffic Manag / Consultancy Service for TRA Quality And Cost- Under Implement IDA / 58160 ement and Road Safety in th Post Open - National 80,000.00 0.00 2020-03-31 2020-03-31 2020-04-21 2020-06-04 2020-07-02 2020-08-01 2020-09-05 2020-10-10 2021-10-10 NSIP Gender Based Violence Based Selection ation e City of Addis Ababa (GBV) Assessment ET-AARTB-178373-CS-QCBS Component A: Traffic Manag / Consultancy Service for Pre Quality And Cost- Open - Internationa IDA / 58160 ement and Road Safety in th Prior 1,800,000.00 0.00 Signed 2020-06-15 2020-08-05 2020-07-06 2020-08-25 2020-08-29 2021-01-31 2020-10-13 2021-04-27 2020-11-22 2021-11-06 2020-12-27 2022-12-29 2021-01-31 2022-09-23 paration of BRT Development Based Selection l e City of Addis Ababa Strategy in the City of Addis Ababa ET-AARTB-244463-CS-QCBS / Consultancy Service for Env Component A: Traffic Manag Quality And Cost- Under Implement ironmental and Social Impact IDA / 58160 ement and Road Safety in th Post Open - National 75,000.00 0.00 2021-07-26 2022-09-14 2021-08-10 2021-09-01 2021-09-29 2021-10-14 2021-11-12 2021-11-29 2022-03-29 Based Selection ation Assessment for the study of e City of Addis Ababa Pedestrian Crossings. ET-AARTB-267530-CS-LCS / Consultancy Service for Selec Component A: Traffic Manag Least Cost Selecti Under Implement tion of TRANSIP External Audi IDA / 58160 ement and Road Safety in th Post Open - National 35,000.00 0.00 2022-01-15 2021-12-24 2022-01-29 2022-02-19 2022-03-19 2022-04-18 2022-05-23 2022-06-27 2024-02-17 on ation tor for a period covering July e City of Addis Ababa 2021 till December 2023. Component A: Traffic Manag ET-AARTB-361-CS-QCBS / Fu Quality And Cost- Open - Internationa IDA / 58160 ement and Road Safety in th Prior 700,000.00 0.00 Canceled 2017-06-19 2017-07-10 2017-08-23 2017-11-20 2017-12-20 2018-01-24 2018-02-28 2019-02-28 ture Traffic Planning Studies Based Selection l e City of Addis Ababa ET-AARTB-408-CS-QCBS / Ad Component B: Improvement visory Assistance in Improvin Quality And Cost- Open - Internationa IDA / 58160 of Integrated Urban Planning Prior 1,000,000.00 0.00 Canceled 2017-03-19 2017-04-09 2017-05-23 2017-07-06 2017-08-05 2017-09-09 2017-10-14 2018-10-14 g Metro Area Master Plan and Based Selection l and Transport System preparing Local Development Plans ET-AARTB-375-CS-QCBS / As Component A: Traffic Manag sistance in planning /establis Quality And Cost- Open - Internationa IDA / 58160 ement and Road Safety in th Prior 2,500,000.00 0.00 Canceled 2016-12-14 2017-01-04 2017-02-17 2017-05-08 2017-06-07 2017-07-12 2017-08-16 2018-08-16 hing an integrated Public Tra Based Selection l e City of Addis Ababa nsport Systems for all modes . ET-AARTB-370-CS-QCBS / De Component A: Traffic Manag Quality And Cost- Open - Internationa velopment of a drainage mas IDA / 58160 ement and Road Safety in th Prior 800,000.00 1,572,736.60 Signed 2016-11-15 2018-03-09 2016-12-06 2018-03-30 2017-01-19 2018-10-26 2017-04-25 2019-07-04 2017-05-25 2019-09-24 2017-06-29 2020-02-27 2017-08-03 2020-05-16 2018-08-03 Based Selection l ter plan for Addis Ababa e City of Addis Ababa ET-AARTB-369-CS-QCBS / Ad Component A: Traffic Manag visory assistance on restruct Quality And Cost- Open - Internationa IDA / 58160 ement and Road Safety in th Prior 500,000.00 0.00 Canceled 2017-01-24 2017-02-14 2017-03-30 2017-06-27 2017-07-27 2017-08-31 2017-10-05 2018-10-05 uring of AACRA and re-establi Based Selection l e City of Addis Ababa shing its functional units Page 4 ET-AARTB-373-CS-QCBS / Ad Component A: Traffic Manag visory Assistance in Establish Quality And Cost- Open - Internationa IDA / 58160 ement and Road Safety in th Prior 1,000,000.00 0.00 Canceled 2017-01-31 2017-02-21 2017-04-06 2017-07-11 2017-08-10 2017-09-14 2017-10-19 2018-10-19 ing and Operating the Public Based Selection l e City of Addis Ababa and Freight Transport Authori ty (PFTA) ET-AARTB-366-CS-QCBS / Co Component A: Traffic Manag mprehensive road asset man Quality And Cost- Open - Internationa IDA / 58160 ement and Road Safety in th Prior 2,500,000.00 3,293,627.43 Signed 2016-11-29 2016-11-24 2016-12-20 2017-01-17 2017-02-02 2018-02-15 2017-05-02 2018-05-29 2017-06-01 2018-12-01 2017-07-06 2019-01-14 2017-08-10 2019-02-04 2018-08-10 agement system and develo Based Selection l e City of Addis Ababa ping a road maintenance ma nual Component A: Traffic Manag ET-AARTB-405-CS-LCS / Ann Least Cost Selecti Under Implement IDA / Q9810 ement and Road Safety in th Post Open - National 15,000.00 0.00 2016-07-20 2016-08-10 2016-09-23 2016-10-21 2016-11-20 2016-12-25 2017-01-29 2017-07-28 ual Audit on ation e City of Addis Ababa ET-AARTB-367-CS-QCBS / Up Component A: Traffic Manag dating road design manual, i Quality And Cost- Open - Internationa IDA / 58160 ement and Road Safety in th Prior 1,000,000.00 0.00 Signed 2016-11-15 2016-12-06 2020-10-11 2017-01-19 2021-08-11 2017-04-18 2022-01-27 2017-05-18 2022-04-14 2017-06-22 2022-09-22 2017-07-27 2018-07-27 mproving contract managem Based Selection l e City of Addis Ababa ent and associated capacity building ET-AARTB-407-CS-QCBS / De Component A: Traffic Manag velopment of transit oriented Quality And Cost- Open - Internationa IDA / 58160 ement and Road Safety in th Prior 500,000.00 0.00 Canceled 2016-08-30 2016-09-20 2016-11-03 2016-12-01 2016-12-31 2017-02-04 2017-03-11 2018-03-11 development (TOD) program Based Selection l e City of Addis Ababa for the city of AA. ET-AARTB-379-CS-QCBS / De Component A: Traffic Manag Quality And Cost- Open - Internationa sign on improving Anbessa's IDA / 58160 ement and Road Safety in th Prior 500,000.00 0.00 Canceled 2017-03-17 2017-04-07 2017-05-21 2017-08-15 2017-09-14 2017-10-19 2017-11-23 2018-11-23 Based Selection l operational facilities e City of Addis Ababa ET-AARTB-374-CS-QCBS / Su Component A: Traffic Manag pport the implementation of I Quality And Cost- Open - Internationa IDA / 58160 ement and Road Safety in th Prior 1,000,000.00 1,108,178.54 Signed 2016-12-27 2018-10-26 2017-01-17 2018-10-23 2017-03-02 2019-03-02 2017-05-30 2019-05-16 2017-06-29 2019-09-06 2017-08-03 2019-12-02 2017-09-07 2019-12-13 2018-09-07 nstitutional and Policy reform Based Selection l e City of Addis Ababa in the Provision of public Tra nsport Service. ET-AARTB-377-CS-QCBS / Ad Component A: Traffic Manag Quality And Cost- Open - Internationa vice on Optimization of Anbe IDA / 58160 ement and Road Safety in th Prior 1,000,000.00 1,406,572.44 Signed 2016-11-15 2017-07-27 2016-12-06 2017-12-22 2017-01-19 2018-05-16 2017-04-11 2018-09-06 2017-05-11 2018-10-26 2017-06-15 2019-02-12 2017-07-20 2019-02-22 2018-07-20 Based Selection l ssa Bus Management e City of Addis Ababa ET-AARTB-365-CS-QCBS / De Component A: Traffic Manag Quality And Cost- Open - Internationa sign and supervision of Pede IDA / 58160 ement and Road Safety in th Prior 750,000.00 0.00 Canceled 2016-07-18 2016-09-05 2016-08-08 2016-09-21 2016-10-30 2016-11-29 2017-01-27 2016-12-29 2017-02-02 2017-03-09 2018-03-09 Based Selection l strian footbridges constructio e City of Addis Ababa n ET-AARTB-382-CS-CQS / Fina Component A: Traffic Manag Consultant Qualifi nce Receivable and Payable IDA / 58160 ement and Road Safety in th Post Open - National 30,000.00 0.00 Canceled 2016-10-27 2016-11-17 2016-12-31 2017-01-30 2017-03-06 2017-09-02 cation Selection clearance of AACRA e City of Addis Ababa ET-AARTB-376-CS-QCBS / De Component A: Traffic Manag sign and supervision of the in Quality And Cost- Open - Internationa IDA / 58160 ement and Road Safety in th Prior 2,000,000.00 1,943,386.57 Signed 2016-07-21 2016-08-17 2016-08-11 2016-09-29 2016-09-24 2017-02-16 2016-12-27 2017-01-26 2017-12-06 2017-03-02 2018-05-18 2017-04-06 2018-06-13 2018-04-06 stallation of the IT infrastruct Based Selection l e City of Addis Ababa ure and systems for Anbessa bus operation. ET-AARTB-362-CS-QCBS / Ro Component A: Traffic Manag Quality And Cost- Open - Internationa ad Safety Awareness and Pu IDA / 58160 ement and Road Safety in th Post 190,000.00 0.00 Canceled 2016-10-27 2016-11-17 2016-12-31 2017-01-28 2017-02-27 2017-04-03 2017-05-08 2018-05-08 Based Selection l blic Education e City of Addis Ababa INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component A: Traffic Manag ET-AARTB-371-CS-INDV / Tec Individual Consult IDA / 58160 ement and Road Safety in th Prior Open - National 500,000.00 0.00 Canceled 2017-02-14 2017-04-04 2017-04-25 2017-05-30 2017-11-26 hnical Assistance to ACCRA ant Selection e City of Addis Ababa ET-AARTB-390-CS-INDV / Se Component A: Traffic Manag Individual Consult nior Procurement specialist f IDA / Q9810 ement and Road Safety in th Prior Open - National 50,000.00 15,586.78 Signed 2016-07-19 2018-09-24 2016-08-07 2016-07-04 2016-08-08 2018-09-24 2016-07-30 2016-07-08 2017-07-30 ant Selection or AA PIU e City of Addis Ababa ET-AARTB-19423-CS-CDS / C apacity Building in Road Con Component A: Traffic Manag struction Management by Eth IDA / 58160 ement and Road Safety in th Post Direct Selection Direct 130,434.00 108,456.54 Signed 2017-09-11 2017-09-21 2017-11-25 2017-09-25 2018-05-24 iopian Institute of Architectur e City of Addis Ababa e, Building Construction and City Development (EiABC) ET-AARTB-21812-CS-INDV / Component A: Traffic Manag Project Supervisor for Transp Individual Consult IDA / 58160 ement and Road Safety in th Post Open 50,000.00 1,880.11 Signed 2017-08-01 2017-10-05 2017-09-19 2018-02-09 2017-10-10 2018-04-06 2017-11-14 2018-04-16 2018-05-13 ort Infrastructure Asset Mana ant Selection e City of Addis Ababa gement System Consultancy Service ET-AARTB-40493-CS-CDS / E Component A: Traffic Manag xternal audit service for FY20 IDA / 58160 ement and Road Safety in th Post Direct Selection Direct 8,500.00 8,415.72 Completed 2018-01-18 2018-01-28 2018-04-03 2018-07-26 2018-09-30 2018-09-10 17/18 by A.W. Thomas LP Ch e City of Addis Ababa artered Certified Accountants ET-AARTB-36648-CS-INDV / Component A: Traffic Manag Senior Procurement Specialis Individual Consult IDA / 58160 ement and Road Safety in th Post Open 50,000.00 32,811.83 Signed 2018-01-17 2018-02-14 2018-03-07 2018-04-27 2018-03-28 2018-07-03 2018-05-02 2018-08-27 2018-10-29 t to enhance AACRA's Interna ant Selection e City of Addis Ababa l Procurement Capacity Component A: Traffic Manag ET-AARTB-36622-CS-INDV / Individual Consult IDA / 58160 ement and Road Safety in th Post Open 40,000.00 1,668.31 Signed 2018-01-30 2018-03-20 2018-04-27 2018-04-10 2018-06-08 2018-05-15 2018-06-16 2018-11-11 Gender Specialist for AA PIU ant Selection e City of Addis Ababa ET-AARTB-49169-CS-INDV / Component A: Traffic Manag Capacity building expert for r Individual Consult IDA / 58160 ement and Road Safety in th Post Open 30,000.00 0.00 Canceled 2018-03-08 2018-04-26 2018-05-17 2018-06-21 2018-12-18 esearch and technology tran ant Selection e City of Addis Ababa sfer ( AACRA's Capacity Build ing) ET-AARTB-81978-CS-CDS / T raining program on the revis Component B: Improvement Under Implement ed city master plan for 720 C IDA / 58160 of Integrated Urban Planning Prior Direct Selection Direct 200,000.00 0.00 2018-10-17 2018-02-15 2018-10-27 2018-08-09 2018-12-31 2019-06-29 ation ity Management Executives a and Transport System nd Line Managers ( Level II a nd III Training Program) Component A: Traffic Manag ET-AARTB-106033-CS-INDV / Individual Consult IDA / 58160 ement and Road Safety in th Post Open 25,000.00 12,210.76 Signed 2019-03-26 2019-06-10 2019-05-14 2019-05-10 2019-06-13 2019-06-25 2019-07-18 2019-08-27 2020-07-17 Senior Finance Expert ant Selection e City of Addis Ababa Component A: Traffic Manag ET-AARTB-39687-CS-INDV / Individual Consult IDA / 58160 ement and Road Safety in th Post Open 30,000.00 0.00 Canceled 2018-01-25 2018-03-15 2018-04-05 2018-05-10 2018-11-06 Finance Expert for AACRA ant Selection e City of Addis Ababa Page 5 Component A: Traffic Manag ET-AARTB-39686-CS-INDV / Individual Consult IDA / 58160 ement and Road Safety in th Post Open 50,000.00 0.00 Canceled 2018-01-30 2018-03-20 2018-04-10 2018-05-15 2018-11-11 Project Manager for AA PIU ant Selection e City of Addis Ababa Component A: Traffic Manag ET-AARTB-106099-CS-INDV / Individual Consult Under Implement IDA / 58160 ement and Road Safety in th Prior Open 30,000.00 0.00 2019-06-15 2019-07-19 2019-08-03 2019-09-02 2019-10-07 2021-09-26 Procurement Expert ant Selection ation e City of Addis Ababa ET-AARTB-106102-CS-INDV / Component A: Traffic Manag Individual Consult Senior Procurement Specialis IDA / 58160 ement and Road Safety in th Prior Open 54,000.00 0.00 Canceled 2019-06-30 2019-07-19 2019-08-18 2019-09-17 2019-10-22 2021-10-11 ant Selection t e City of Addis Ababa Component A: Traffic Manag ET-AARTB-106055-CS-INDV / Individual Consult IDA / 58160 ement and Road Safety in th Post Open 54,000.00 23,856.46 Signed 2019-05-15 2019-03-14 2019-07-03 2019-07-24 2019-08-02 2019-09-11 2019-09-06 2019-09-25 2021-08-26 Contract and Claim Expert ant Selection e City of Addis Ababa ET-AARTB-106036-CS-INDV / Component A: Traffic Manag Individual Consult Project Supervisor for Transp IDA / 58160 ement and Road Safety in th Post Open 54,000.00 0.00 Canceled 2019-05-31 2019-11-06 2019-07-19 2019-08-18 2019-09-22 2021-09-11 ant Selection ort Infrastructure Asset Mana e City of Addis Ababa gement ET-AARTB-106039-CS-INDV / Component A: Traffic Manag Individual Consult Senior Pavement/Material En IDA / 58160 ement and Road Safety in th Post Open 64,000.00 22,254.11 Signed 2019-05-31 2019-03-21 2019-07-19 2019-07-20 2019-08-18 2019-06-18 2019-09-22 2019-08-22 2021-09-11 ant Selection gineer e City of Addis Ababa ET-AARTB-106041-CS-INDV / Component A: Traffic Manag Individual Consult Senior Transport Planner/ Tra IDA / 58160 ement and Road Safety in th Post Open 64,000.00 0.00 Canceled 2019-05-31 2019-03-13 2019-07-19 2019-08-18 2019-09-22 2021-09-11 ant Selection ffic Engineer e City of Addis Ababa ET-AARTB-106042-CS-INDV / Component A: Traffic Manag Individual Consult Project Manager for Project I IDA / 58160 ement and Road Safety in th Post Open 70,000.00 0.00 Canceled 2019-05-31 2019-02-13 2019-07-19 2019-08-18 2019-09-22 2021-09-11 ant Selection mplementation Unit (PIU) e City of Addis Ababa Component A: Traffic Manag ET-AARTB-106050-CS-INDV / Individual Consult IDA / 58160 ement and Road Safety in th Post Open 54,000.00 0.00 Canceled 2019-05-31 2019-03-01 2019-07-19 2019-08-18 2019-09-22 2021-09-11 Contract and Claim Expert ant Selection e City of Addis Ababa ET-AARTB-106057-CS-INDV / Component A: Traffic Manag Individual Consult Senior Hydrologist/Hydraulic IDA / 58160 ement and Road Safety in th Post Open 54,000.00 17,929.83 Signed 2019-05-31 2019-01-15 2019-07-19 2019-05-25 2019-08-18 2019-07-01 2021-08-28 2019-07-31 2023-08-18 ant Selection Engineer e City of Addis Ababa Component A: Traffic Manag ET-AARTB-106059-CS-INDV / Individual Consult IDA / 58160 ement and Road Safety in th Post Open 64,000.00 23,795.24 Signed 2019-05-31 2019-03-14 2019-07-19 2019-11-22 2019-08-18 2020-02-06 2019-09-22 2020-05-14 2021-09-11 Senior Structural Engineer ant Selection e City of Addis Ababa Component A: Traffic Manag ET-AARTB-106060-CS-INDV / Individual Consult IDA / 58160 ement and Road Safety in th Post Open 54,000.00 0.00 Canceled 2019-05-31 2019-06-03 2019-07-19 2019-08-18 2019-09-22 2021-09-11 Senior Highway Engineer ant Selection e City of Addis Ababa Component A: Traffic Manag ET-AARTB-106048-CS-INDV / Individual Consult IDA / 58160 ement and Road Safety in th Post Open 70,000.00 23,356.37 Signed 2019-05-31 2019-02-13 2019-07-19 2019-05-25 2019-08-18 2019-11-15 2019-09-22 2019-12-10 2021-10-11 Project Manager for AACRA ant Selection e City of Addis Ababa ET-AARTB-36623-CS-INDV / Component A: Traffic Manag Senior Procurement Specialis Individual Consult IDA / 58160 ement and Road Safety in th Post Open 50,000.00 0.00 Canceled 2018-01-17 2017-12-20 2018-03-07 2018-04-27 2018-03-28 2018-05-02 2018-10-29 t to enhance AACRA's Interna ant Selection e City of Addis Ababa l Procurement Capacity Component A: Traffic Manag ET-AARTB-122352-CS-INDV / Individual Consult IDA / Q9810 ement and Road Safety in th Post Open - National 50,000.00 16,799.67 Signed 2019-07-18 2019-07-31 2019-08-19 2019-08-20 2019-08-27 2020-02-06 2019-09-12 2020-02-15 2020-09-11 Social Safeguard Specialist ant Selection e City of Addis Ababa ET-AARTB-111296-CS-CDS / Component A: Traffic Manag Training on Transport Infrastr IDA / 58160 ement and Road Safety in th Post Direct Selection Direct 150,000.00 45,500.00 Signed 2019-07-24 2019-07-21 2019-08-03 2019-06-21 2019-10-07 2019-10-15 2020-04-04 ucture Asset Management Sy e City of Addis Ababa stems ET-AARTB-145086-CS-INDV / Component A: Traffic Manag Transport Infrastructure Asse Individual Consult IDA / 58160 ement and Road Safety in th Post Open 30,000.00 0.00 Canceled 2019-11-21 2019-11-15 2020-01-09 2020-01-30 2020-03-05 2021-03-05 t Management System (TIAM ant Selection e City of Addis Ababa S) project supervisor ET-AARTB-146340-CS-INDV / Component A: Traffic Manag Individual Consult International Consultant for IDA / 58160 ement and Road Safety in th Post Limited 20,000.00 38,000.00 Signed 2019-11-25 2019-11-01 2019-11-30 2019-12-10 2019-12-21 2020-01-30 2020-01-25 2020-02-22 2020-03-25 ant Selection Mid Term Review of TRANSIP e City of Addis Ababa ET-AARTB-146341-CS-INDV / Component A: Traffic Manag Individual Consult Local Consultant for Mid-Ter IDA / 58160 ement and Road Safety in th Post Limited 5,000.00 10,764.60 Signed 2019-11-25 2019-11-01 2019-11-30 2020-01-02 2019-12-21 2020-03-05 2020-01-25 2020-03-18 2020-03-25 ant Selection m Review of TRANSIP e City of Addis Ababa ET-AARTB-149650-CS-CDS / Component A: Traffic Manag Experience Sharing and Train IDA / 58160 ement and Road Safety in th Post Direct Selection Direct 78,000.00 77,979.00 Signed 2019-12-16 2019-12-11 2019-12-26 2020-01-03 2020-02-29 2020-01-05 2020-03-10 ing of Public Transport Best P e City of Addis Ababa ractices in Korea ET-AARTB-152487-CS-INDV / Component A: Traffic Manag Individual Consult Intelligent Transport System( IDA / 58160 ement and Road Safety in th Post Direct 35,000.00 25,963.12 Signed 2020-01-06 2020-01-03 2020-01-16 2020-02-11 2020-02-06 2020-05-19 2020-03-12 2020-05-29 2021-03-12 ant Selection ITS) Expert e City of Addis Ababa ET-AARTB-182064-CS-INDV / Component A: Traffic Manag Transport Infrastructure Asse Individual Consult IDA / 58160 ement and Road Safety in th Post Direct 30,000.00 26,117.28 Signed 2020-09-09 2020-09-02 2020-09-19 2020-09-07 2020-10-10 2020-11-10 2020-11-14 2020-11-25 2021-11-14 t Management System (TIAM ant Selection e City of Addis Ababa S) Project Supervisor ET-AARTB-199336-CS-INDV / Component A: Traffic Manag Individual Consult SENIOR LEGAL EXPERT for M IDA / 58160 ement and Road Safety in th Post Limited 7,000.00 0.00 Canceled 2020-10-15 2020-10-20 2020-11-10 2020-12-15 2021-03-15 ant Selection ain ITS and Merkato projects e City of Addis Ababa ET-AARTB-202946-CS-INDV / Component A: Traffic Manag Individual Consult SENIOR LEGAL EXPERT for M IDA / 58160 ement and Road Safety in th Post Direct 7,000.00 6,665.20 Signed 2020-11-11 2020-11-05 2020-11-21 2020-11-05 2020-12-12 2020-11-11 2021-01-16 2020-11-20 2021-04-16 ant Selection ain ITS and Merkato projects e City of Addis Ababa ET-AARTB-205554-CS-INDV / Component A: Traffic Manag Individual Consultancy Servic Individual Consult IDA / 58160 ement and Road Safety in th Post Direct 20,000.00 20,056.92 Signed 2020-11-20 2020-11-18 2020-11-30 2020-11-24 2020-12-21 2020-12-28 2021-01-25 2021-01-29 2021-03-06 e for Technical Assistance on ant Selection e City of Addis Ababa Anbessa Bus Procurement. ET-AARTB-247527-CS-INDV / Component A: Traffic Manag Individual Consult Under Implement Individual Consultancy Servic IDA / Q9810 ement and Road Safety in th Post Open 50,000.00 0.00 2021-08-18 2021-09-01 2021-09-09 2021-09-30 2021-11-04 2022-11-04 ant Selection ation e of Contract and Claim Expe e City of Addis Ababa rt Page 6 ET-AARTB-283601-CS-INDV / Individual Consultancy Servic Component A: Traffic Manag Individual Consult Pending Impleme e for Dispute Avoidance/Adju IDA / 58160 ement and Road Safety in th Post Limited 40,000.00 0.00 2022-03-25 2022-03-30 2022-04-20 2022-05-25 2024-05-14 ant Selection ntation dication Board (DAAB) Memb e City of Addis Ababa er for Corridor 1 Civil Work ET-AARTB-316935-CS-INDV / Component A: Traffic Manag Employment of an Advisor in Individual Consult Under Implement IDA / 58160 ement and Road Safety in th Post Limited 40,000.00 0.00 2022-09-27 2022-09-13 2022-10-02 2022-10-23 2022-11-27 2023-01-02 Intersectoral Coordination for ant Selection ation e City of Addis Ababa the Mayor of Addis Ababa Cit y ET-AARTB-316932-CS-CDS / Component A: Traffic Manag Direct - Internation Pending Impleme Capacity Building Program: T IDA / 58160 ement and Road Safety in th Post Direct Selection 50,000.00 0.00 2022-09-20 2022-09-30 2022-12-04 2023-01-03 al ntation raining on FIDIC Modules e City of Addis Ababa ET-AARTB-106060-CS-INDV- Component A: Traffic Manag Individual Consult Under Implement 2 / Individual Consultancy Se IDA / 58160 ement and Road Safety in th Post Open - National 30,000.00 0.00 2022-11-15 2022-12-13 2023-01-03 2023-02-02 2023-03-09 2024-03-08 ant Selection ation rvices of Highway Engineer e City of Addis Ababa ET-AARTB-323170-CS-INDV / Component A: Traffic Manag Individual Consult Open - Internationa Under Implement Individual Consultancy Servic IDA / 58160 ement and Road Safety in th Post 40,000.00 0.00 2022-11-10 2022-12-13 2022-12-29 2023-01-28 2023-03-04 2024-03-03 ant Selection l ation e of Intelligent Transport Syst e City of Addis Ababa em Expert ET-AARTB-323173-CS-INDV / Component A: Traffic Manag Individual Consult Under Implement Individual Consultancy Servic IDA / 58160 ement and Road Safety in th Post Open - National 30,000.00 0.00 2022-11-10 2022-12-13 2022-12-29 2023-01-28 2023-03-04 2024-03-03 ant Selection ation e of Traffic Engineer e City of Addis Ababa ET-AARTB-323174-CS-INDV / Component A: Traffic Manag Individual Consult Under Implement Individual Consultancy Servic IDA / 58160 ement and Road Safety in th Post Open - National 30,000.00 0.00 2022-11-10 2022-12-13 2022-12-29 2023-01-28 2023-03-04 2024-03-03 ant Selection ation e of Contract and Claim Expe e City of Addis Ababa rt ET-AARTB-331480-CS-INDV / Component A: Traffic Manag Individual Consult Under Implement Individual Consultancy Servic IDA / 58160 ement and Road Safety in th Post Open - National 35,000.00 0.00 2022-12-22 2022-12-21 2023-02-09 2023-03-11 2023-04-15 2024-04-14 ant Selection ation es of Urban Planner and Arch e City of Addis Ababa itect ET-AARTB-331482-CS-INDV / Component A: Traffic Manag Individual Consult Under Implement Individual Consultancy Servic IDA / 58160 ement and Road Safety in th Post Open - National 25,000.00 0.00 2022-12-21 2022-12-21 2023-02-08 2023-03-10 2023-04-14 2024-04-13 ant Selection ation es of Finance Expert e City of Addis Ababa Component A: Traffic Manag ET-AARTB-394-CS-INDV / Fin Individual Consult IDA / Q9810 ement and Road Safety in th Post Open - National 50,000.00 11,686.41 Signed 2016-07-19 2015-08-28 2016-08-07 2015-12-15 2016-08-18 2016-04-18 2016-08-02 2016-04-18 2017-08-02 ancial management expert ant Selection e City of Addis Ababa Component A: Traffic Manag ET-AARTB-404-CS-CDS / Proj IDA / 58160 ement and Road Safety in th Post Direct Selection Direct 20,000.00 0.00 Canceled 2016-11-10 2016-11-20 2017-01-24 2017-03-25 ect Staff Training (Abroad) e City of Addis Ababa ET-AARTB-363-CS-INDV / Ad Component A: Traffic Manag visory Assistance in Establish Individual Consult IDA / 58160 ement and Road Safety in th Prior Open - National 500,000.00 0.00 Canceled 2016-07-21 2016-09-19 2016-08-08 2016-08-15 2016-09-20 2017-08-29 ing and Operating the Trafic ant Selection e City of Addis Ababa Management Agency ( TMA ) Component A: Traffic Manag ET-AARTB-402-CS-CDS / Proj IDA / Q9810 ement and Road Safety in th Post Direct Selection Direct 10,000.00 151,209.74 Signed 2016-08-25 2018-03-26 2016-09-04 2017-12-17 2016-11-08 2018-04-05 2016-11-08 ect Staff Training (Local) e City of Addis Ababa ET-AARTB-384-CS-INDV / Fin Component A: Traffic Manag Individual Consult ancial Specialist for Preparati IDA / Q9810 ement and Road Safety in th Prior Open - National 10,000.00 0.00 Canceled 2016-07-19 2016-09-06 2016-09-27 2016-11-01 2017-04-30 ant Selection on of Finance Management G e City of Addis Ababa uideline Component A: Traffic Manag ET-AARTB-386-CS-INDV / Pro Individual Consult IDA / 58160 ement and Road Safety in th Post Open - National 80,000.00 0.00 Canceled 2016-10-25 2016-12-13 2017-01-03 2017-02-07 2017-08-06 ject Officer ant Selection e City of Addis Ababa ET-AARTB-385-CS-INDV / Pro Component A: Traffic Manag Individual Consult ject Implementation Manual IDA / Q9810 ement and Road Safety in th Post Open - National 10,000.00 0.00 Canceled 2016-10-04 2016-11-22 2016-12-13 2017-01-17 2017-03-18 ant Selection Preparation e City of Addis Ababa ET-AARTB-5965-CS-INDV / In Component A: Traffic Manag Individual Consult telligent Transport System Ex IDA / 58160 ement and Road Safety in th Post Open 20,000.00 35,348.61 Signed 2017-02-14 2017-12-25 2017-04-04 2018-08-03 2017-04-25 2018-11-16 2017-05-30 2018-12-31 2017-11-26 ant Selection pert for Addis Ababa PIU e City of Addis Ababa ET-AARTB-5961-CS-INDV / Pr Component A: Traffic Manag Individual Consult oject Supervisor for Transpor IDA / 58160 ement and Road Safety in th Post Open 30,000.00 0.00 Canceled 2017-02-03 2017-03-24 2017-04-14 2017-05-19 2017-11-15 ant Selection t Infrastructure Asset Manag e City of Addis Ababa ement System ET-AARTB-5963-CS-INDV / Tr Component A: Traffic Manag Individual Consult affic Engineer for Addis Abab IDA / 58160 ement and Road Safety in th Post Open 20,000.00 2,349.89 Signed 2017-02-10 2017-03-31 2017-08-15 2017-04-21 2017-11-23 2017-05-26 2017-12-01 2017-11-22 ant Selection a PIU e City of Addis Ababa Component C: Road Safety I ET-AARTB-700-CS-INDV / Se nterventions and Institutiona Individual Consult nior Procurement specialist f IDA / Q9810 Prior Open - National 50,000.00 15,581.89 Signed 2016-07-27 2018-09-26 2016-09-14 2016-03-04 2016-10-05 2018-09-29 2016-11-09 2016-07-08 2017-11-09 l Strengthening of Selected ant Selection or FTA PIU Federal Transport Institution s Component A: Traffic Manag ET-AARTB-391-CS-INDV / Pro Individual Consult IDA / Q9810 ement and Road Safety in th Post Open - National 50,000.00 12,984.90 Signed 2016-07-19 2016-07-12 2016-08-03 2016-01-25 2016-08-19 2016-02-18 2016-08-25 2016-02-18 2016-12-29 curement Experts ant Selection e City of Addis Ababa ET-AARTB-392-CS-INDV / Se Component A: Traffic Manag Individual Consult nior Financial management s IDA / Q9810 ement and Road Safety in th Prior Open - National 11,000.00 0.00 Canceled 2016-07-19 2016-08-01 2016-08-14 2016-08-18 2016-09-15 2017-09-15 ant Selection pecialist (one for FTA PIU and e City of Addis Ababa One for AA PIU) Component A: Traffic Manag ET-AARTB-398-CS-INDV / Fin Individual Consult IDA / Q9810 ement and Road Safety in th Post Open - National 50,000.00 0.00 Canceled 2016-08-30 2017-01-31 2017-02-21 2017-03-28 2018-03-28 ance Expert for FTA ant Selection e City of Addis Ababa ET-AARTB-5962-CS-INDV / Tr Component A: Traffic Manag Individual Consult ansport Planner for Addis Ab IDA / 58160 ement and Road Safety in th Post Open 20,000.00 25,809.82 Signed 2017-02-09 2017-03-30 2017-10-13 2017-04-20 2017-11-20 2017-05-25 2017-12-01 2017-11-21 ant Selection aba PIU e City of Addis Ababa Component A: Traffic Manag ET-AARTB-381-CS-INDV / Saf Individual Consult IDA / Q9810 ement and Road Safety in th Post Open - National 40,000.00 24,288.69 Signed 2016-07-19 2015-10-27 2016-09-06 2015-11-20 2016-09-27 2015-12-04 2016-11-01 2015-11-30 2017-04-30 eguard Consultancy ant Selection e City of Addis Ababa Component A: Traffic Manag ET-AARTB-395-CS-INDV / Soc Individual Consult IDA / Q9810 ement and Road Safety in th Post Open - National 50,000.00 1,527.91 Signed 2016-07-19 2016-07-19 2016-08-07 2018-02-09 2016-08-15 2018-03-01 2016-08-31 2018-03-01 2017-08-31 ial Safeguard specialist ant Selection e City of Addis Ababa Page 7 ET-AARTB-396-CS-INDV / En Component A: Traffic Manag Individual Consult vironmental Safeguard Speci IDA / Q9810 ement and Road Safety in th Post Open - National 50,000.00 27,958.82 Signed 2016-07-19 2016-07-28 2016-08-08 2017-08-15 2016-08-10 2017-08-21 2016-08-09 2017-12-01 2017-08-09 ant Selection alist(One for FTA PIU & One f e City of Addis Ababa or AA PIU) ET-AARTB-5964-CS-INDV / R Component A: Traffic Manag Individual Consult oad and Material Engineer fo IDA / 58160 ement and Road Safety in th Post Open 20,000.00 33,373.28 Signed 2017-02-13 2017-04-03 2018-04-27 2017-04-24 2018-07-05 2017-05-29 2018-07-17 2017-11-25 ant Selection r Addis Ababa PIU e City of Addis Ababa Page 8 PROCUREMENT PLAN (Textual Part) Project information: EL Salvador Growing Up and Learning Together: Comprehensive Early Childhood Development P171316 Project Implementation agency: Ministerio de Educación, Ciencia y Tecnología Date of the Procurement Plan: December 6, 2021 Period covered by this Procurement Plan: December 6, 2021 – December 31, 2022 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. PROCUREMENT El Salvador : Growing Up and Learning Together: Comprehensive Early Childhood Development in El Salvador PLAN General Information Country: El Salvador Bank’s Approval Date of the Original Procurement Plan: 2023-05-22 Revised Plan Date(s): (comma delineated, leave blank if 2023-06-05 none) Project ID: P171316 GPN Date: Project Name: Growing Up and Learning Together: Comprehensive Early Childhood Development in El Salvador Loan / Credit No: IBRD / 90670 Ministry of Public Works and Transport Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned SDO 006/2023 / “REHABILIT Request for Bids - ACIÓN DE CENTROS EDUCATI Contingency Emergency Res Single Stage - One E Small Works SPD Pending Imp 2024-03-3 IBRD / 90670 Post Request for Bids Open - National 5,620,424.00 0.00 2023-06-12 2023-06-17 2023-07-29 2023-08-28 2023-10-02 VOS AFECTADOS POR LA TOR ponse nvelope (1 envelope proce lementation 0 MENTA TROPICAL JULIA EN L ss) A REGIÓN CENTRAL” SDO 007/2023 / “REHABILIT Request for Bids - ACIÓN DE CENTROS EDUCATI Contingency Emergency Res Single Stage - One E Small Works SPD Pending Imp 2024-03-3 VOS AFECTADOS POR LA TOR IBRD / 90670 Post Request for Bids Open - National 1,941,175.18 0.00 2023-06-12 2023-06-17 2023-07-29 2023-08-28 2023-10-02 ponse nvelope (1 envelope proce lementation 0 MENTA TROPICAL JULIA EN L ss) A REGIÓN OCCIDENTAL” SDO 008/2023 / “REHABILIT Request for Bids - ACIÓN DE CENTROS EDUCATI Contingency Emergency Res Single Stage - One E Small Works SPD Pending Imp 2024-03-3 IBRD / 90670 Post Request for Bids Open - National 7,929,632.81 0.00 2023-06-12 2023-06-17 2023-07-29 2023-08-28 2023-10-02 VOS AFECTADOS POR LA TOR ponse nvelope (1 envelope proce lementation 0 MENTA TROPICAL JULIA EN L ss) A REGIÓN ORIENTAL” GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SDP-SCC 009/2023 / SUPERV ISIÓN DE “REHABILITACIÓN D Contingency Emergency Res Consultant Qualifi Pending Impleme E CENTROS EDUCATIVOS AFE IBRD / 90670 Post Open - National 155,294.02 0.00 2023-06-02 2023-06-23 2023-08-06 2023-09-05 2023-10-10 2024-04-07 ponse cation Selection ntation CTADOS POR LA TORMENTA TROPICAL JULIA EN LA REGIÓ N OCCIDENTAL” SDP-SCC 008/2023 / SUPERV ISIÓN DE “REHABILITACIÓN D Contingency Emergency Res Consultant Qualifi Pending Impleme E CENTROS EDUCATIVOS AFE IBRD / 90670 Post Open - National 449,633.92 0.00 2023-06-05 2023-06-26 2023-08-09 2023-09-08 2023-10-13 2024-04-10 ponse cation Selection ntation CTADOS POR LA TORMENTA TROPICAL JULIA EN LA REGIÓ N CENTRAL”. SDP-SCC 010/2023 / SUPERV ISIÓN DE“REHABILITACIÓN D Contingency Emergency Res Consultant Qualifi Pending Impleme E CENTROS EDUCATIVOS AFE IBRD / 90670 Post Open - National 634,370.63 0.00 2023-06-05 2023-06-26 2023-08-09 2023-09-08 2023-10-13 2024-04-10 ponse cation Selection ntation CTADOS POR LA TORMENTA TROPICAL JULIA EN LA REGIÓ N ORIENTAL” INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 1 PROCUREMENT PLAN (Textual Part) Project information: Burkina Faso- Strengthening Climate Resilience in Burkina Faso- P164078 Project Implementation agency: Permeant Secretariat of Transports (PST) Date of the Procurement Plan: January 8th,2019 Period covered by this Procurement Plan: from January– to December 2019 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in [Décret N°2017-00049/PRES/PM/MINEFID du 01/02/2017 portant procédures de passation, d’exécution et de règlement des marchés publics et des délégations de service publics au Burkina Faso], such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. The National Bidding Document clause allowed to reject all bid when arithmetic error is 15% on + or – of original bid is not applied to the project. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: [is not applicable]; Works: [is not applicable] PROCUREMENT Burkina Faso : Strengthening Climate Resilience in Burkina Faso PLAN General Information Country: Burkina Faso 2019-01-09 Bank’s Approval Date of the Original Procurement Plan: 2023-06-06 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P164078 GPN Date: Project Name: Strengthening Climate Resilience in Burkina Faso Loan / Credit No: IDA / V2230, IDA / D3740 Burkina Faso Hydromet PIU Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned BF-PST2-127041-CW-RFQ / A Request for Quota Single Stage - One E 2019-11-3 ménagement des locaux de L IDA / D3740 Project Management Post Limited 18,000.00 12,951.92 Completed 2019-10-01 2020-01-10 2019-10-31 2020-01-31 tions nvelope 0 ’UGP/HYDROMET BF-PST2-126457-CW-DIR / R éalisation des travaux d'exte Contingent Emergency Resp 2020-08-2 nsion (R+2 et R+3) du centr IDA / D3740 Post Direct Selection Direct 944,000.00 811,250.92 Completed 2019-10-01 2019-10-01 2019-10-06 2019-08-07 2019-10-31 2019-11-08 onse Component 6 e national de veille et d’alert e précoce au profit de l’ANA M BF-HYDROMET-306643-CW- Request for Quota RFQ / Travaux de réfection d Improvement of hydromet a Request for Quota Single Stage - One E tions - Small Work Pending Imp 2022-11-0 e l'etancheite de la dalle du IDA / D3740 nd early warning infrastruct Post Limited 94,545.00 0.00 2022-08-21 2022-09-23 tions nvelope s (Emergency) SP lementation 7 bâtiment R+3 de l'agence Na ure D -Competitive tionale de la Météorologie (A NAM). BF-HYDROMET-225124-CW- Request for Bids - Improvement of hydromet a RFB / Travaux de constructio Single Stage - One E Small Works SPD Under Imple 2023-12-1 IDA / D3740 nd early warning infrastruct Post Request for Bids Open - National 558,182.00 0.00 2023-04-28 2023-06-05 2023-05-08 2023-06-07 2023-06-21 2023-07-22 n du bâtiment R+1 extensibl nvelope (1 envelope proce mentation 9 ure e en R+2 de la DEIE ss) GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BF-PST2-93958-GO-RFB / Ac quisition de matériels inform Capacity building and institu Single Stage - One E IDA / V2230 Post Request for Bids Open - National 98,000.00 81,665.57 Completed 2019-01-20 2019-01-24 2019-01-25 2019-03-08 2019-02-07 2019-04-07 2019-03-08 2019-05-12 2019-05-10 2019-07-11 2019-07-11 atiques et de consommables tional development nvelope au profit du projet HYDROME T BF-PST2-93961-GO-RFQ / Ac Capacity building and institu Request for Quota Single Stage - One E quisition de mobiliers de bur IDA / V2230 Post Open - National 23,636.00 13,092.17 Completed 2019-01-25 2019-03-22 2019-06-01 2019-05-21 2020-08-13 tional development tions nvelope eau au profit de DMP, DAF et DCMEF, DGESS BF-PST2-93967-GO-RFQ / Ac quisition de téléphones porta Capacity building and institu Request for Quota Single Stage - One E bles cellulaires avec forfait d IDA / V2230 Post Open - National 10,200.00 9,777.15 Completed 2019-01-27 2019-03-24 2019-06-06 2019-09-20 2019-09-21 tional development tions nvelope e connexion 3G + RP et de d e deux routers de connexion BF-PST2-99399-GO-RFQ / Ac Request for Quota Single Stage - One E quisition véhicule au profit d IDA / V2230 Project Management Post Limited 50,000.00 41,800.32 Completed 2019-02-20 2019-02-21 2019-04-03 2019-06-20 2019-05-18 2020-08-03 tions nvelope u projet HYDROMET BF-PST2-126800-GO-RFQ / A cquisition de fournitures de b Request for Quota Single Stage - One E IDA / D3740 Project Management Post Limited 12,000.00 5,087.79 Completed 2019-09-03 2019-10-18 2019-10-29 2019-12-31 2019-11-13 2020-01-31 ureau et de de produits d’ent tions nvelope retien au profit de l’UGP/HYD ROMET (2 lots) BF-PST2-127014-GO-RFQ / A Request for Quota Single Stage - One E cquisition d'un groupe électr IDA / D3740 Project Management Post Limited 16,000.00 13,596.49 Completed 2019-09-21 2019-10-18 2019-10-23 2019-11-30 2019-11-22 2021-02-05 tions nvelope ogène au profit de l'UGP/HYD ROMET BF-PST2-127039-GO-RFQ / A Request for Quota Single Stage - One E cquisition de coffres forts au IDA / D3740 Project Management Post Limited 3,000.00 2,561.79 Completed 2019-09-21 2019-12-10 2019-10-26 2019-12-31 2019-11-25 2021-04-28 tions nvelope profit de l'UGP/HYDROMET BF-PST2-127044-GO-RFQ / A cquisition d'un véhicule pick- Request for Quota Single Stage - One E IDA / D3740 Project Management Post Limited 50,000.00 0.00 Canceled 2019-10-06 2019-02-21 2019-11-01 2020-01-30 up (Double cabine 4X4) au pr tions nvelope ofit de l'UGP/HYDROMET BF-PST2-126826-GO-RFQ / A Request for Quota Single Stage - One E cquisition de mobiliers de bur IDA / D3740 Project Management Post Limited 20,000.00 14,719.97 Completed 2019-10-06 2019-01-22 2019-11-03 2019-05-31 2019-12-03 2019-07-05 tions nvelope eau au profit de l’UGP/HYDR OMET BF-PST2-126831-GO-RFQ / T Request for Quota Single Stage - One E ravaux câblage du réseau inf IDA / D3740 Project Management Post Limited 16,000.00 0.00 Canceled 2019-10-19 2019-11-14 2019-12-14 tions nvelope ormatique du bâtiment de l’U GP/HYDROMET BF-PST2-134929-GO-RFQ / P Request for Quota Single Stage - One E restation de service de gardi IDA / D3740 Project Management Post Limited 6,300.00 5,212.60 Completed 2019-09-26 2019-04-15 2019-10-20 2019-05-01 2020-06-16 2020-01-01 tions nvelope ennage au profit de l’UGP/HY DROMET BF-PST2-126832-GO-RFQ / C onnexion du bâtiment de l’U IDA / D3740 Project Management Post Direct Selection Direct 5,600.00 4,682.24 Completed 2019-10-03 2019-12-16 2019-10-08 2019-12-16 2019-10-31 2020-01-07 2019-11-30 2020-03-07 GP/HYDROMET au RESINA BF-PST2-126323-GO-RFQ / A cquisition et paramétrage d’ un logiciel de gestion financi IDA / D3740 Project Management Post Direct Selection Direct 39,500.00 33,315.06 Completed 2020-02-03 2020-02-13 2020-02-08 2019-11-08 2020-03-06 2020-03-13 2020-05-05 2020-06-23 er et comptable TOM2PRO au profit de l'UGP/HYDROMET BF-PST2-143146-GO-RFQ / A cquisition et installation d'un Request for Quota Single Stage - One E IDA / D3740 Project Management Post Limited 30,000.00 27,140.51 Completed 2020-02-22 2020-03-30 2020-03-21 2020-05-27 2020-05-05 2022-01-19 kit de vidéo conférence au se tions nvelope in de l’UGP/HYDROMET Page 1 BF-PST2-156791-GO-RFB / A cquisition d’équipements (ca pteurs de température, capte urs d’humidité relative, capte Capacity building and institu Single Stage - One E IDA / D3740 Post Request for Bids Open - National 407,450.00 371,088.72 Completed 2020-05-18 2020-09-14 2020-05-23 2020-10-12 2020-07-04 2020-10-26 2020-08-03 2020-10-26 2020-09-07 2021-02-27 2021-03-06 2021-11-20 urs de vitesse et direction du tional development nvelope vent et capteurs d’insolation) pour les stations météorologi ques automatiques au profit de l'ANAM BF-PST2-156793-GO-RFQ / A cquisition de grilles métalliqu Capacity building and institu Request for Quota Single Stage - One E IDA / D3740 Post Limited 32,000.00 30,656.17 Completed 2020-03-21 2020-04-27 2020-04-29 2020-06-02 2020-06-28 2020-09-12 es pour la protection des stat tional development tions nvelope ions agrométéorologiques au profit de l'ANAM BF-PST2-134571-GO-RFQ / A Enhancement of service deli cquisition de soixante un (61 Request for Quota Single Stage - One E IDA / D3740 very and warnings to users a Post Limited 80,026.00 0.00 Canceled 2019-10-15 2019-11-19 2020-01-18 ) capteurs pour les mesures tions nvelope nd communities de l’insolation au profit au pr ofit de l’ANAM BF-PST2-156985-GO-RFQ / A Improvement of hydromet a cquisition de mobiliers de bur Request for Quota Single Stage - One E IDA / D3740 nd early warning infrastruct Post Limited 56,400.00 53,774.33 Completed 2020-03-31 2020-06-30 2020-05-09 2019-12-31 2020-07-08 2020-02-01 eaux au profit du SP/CONASU tions nvelope ure R et du SAP (2 lots) BF-PST2-156992-GO-RFQ / A Request for Quota Single Stage - One E cquisition d’une motocyclette IDA / D3740 Project Management Post Limited 1,700.00 1,391.50 Completed 2020-03-17 2020-04-10 2020-04-12 2020-05-30 2020-06-11 2020-06-24 tions nvelope au profit de l’UGP/HYDROME T BF-PST2-126664-GO-RFQ / A cquisition de matériels et con Request for Quota Single Stage - One E IDA / D3740 Project Management Post Limited 16,000.00 0.00 Canceled 2019-10-05 2019-11-04 2019-11-07 sommables informatiques au tions nvelope profit de l’UUGP/HYDROMET. BF-PST2-156986-GO-RFQ / A Improvement of hydromet a cquisition de téléphones por Request for Quota Single Stage - One E IDA / D3740 nd early warning infrastruct Post Limited 27,300.00 26,212.80 Completed 2020-03-31 2020-03-30 2020-05-09 2020-04-21 2020-07-08 2020-05-16 tables au profit de l’UGP/HYD tions nvelope ure ROMET et du SP/CONASUR. BF-PST2-156988-GO-RFQ / A Improvement of hydromet a cquisition de matériels infor Single Stage - One E IDA / D3740 nd early warning infrastruct Post Request for Bids Open - National 373,000.00 356,939.00 Completed 2020-04-09 2020-04-07 2020-04-14 2020-05-14 2020-05-20 2020-05-28 2020-05-28 2020-07-02 2020-07-01 2020-09-30 2021-06-16 matiques au profit du SAP, d nvelope ure u SP/CONASUR et de l'UGP/H YDROMET (03 lots) BF-PST2-161324-GO-RFQ / A Request for Quota Single Stage - One E cquisition de consommable i IDA / D3740 Project Management Post Limited 4,545.00 4,239.63 Completed 2020-03-24 2020-05-06 2020-04-30 2020-06-03 2020-05-30 2020-07-25 tions nvelope nformatiques au profit de l'U GP/HYDROMET BF-PST2-156801-GO-RFB / A cquisition du matériels roula nts : -lot 1 :Véhicules tout terrain ( Improvement of hydromet a Open - Internationa Single Stage - One E pick-up) au profit des Agence IDA / D3740 nd early warning infrastruct Post Request for Bids 1,593,000.00 0.00 Canceled 2020-04-03 2020-04-08 2020-05-20 2020-06-19 2020-07-24 2020-11-21 l nvelope s d'exécution et de l'UGP/HY ure DROMET (12) -lot 2 :Gros porteurs de 40T a vec têtes et wagons au profit du SP/CONASUR (2) -lot 3: Ambulances (04) BF-PST2-156804-GO-RFB / A cquisition de matériel de sec ours, d'intervention et de sau Improvement of hydromet a vetage de victimes au profit Open - Internationa Single Stage - One E IDA / D3740 nd early warning infrastruct Post Request for Bids 1,036,365.00 0.00 Canceled 2020-04-03 2020-04-08 2020-05-20 2020-06-19 2020-07-24 2020-11-21 de la DGPC. l nvelope ure lot 1 :Engins-pompes (02) et moto pompes remarquables (02) lot 2 : Embarcations motorisé es (06) BF-HYDROMET-172279-GO- Improvement of hydromet a DIR / Acquisition du matériels IDA / D3740 nd early warning infrastruct Post Direct Selection Direct 1,150,000.00 15,156,242.75 Completed 2020-05-14 2020-05-14 2020-05-19 2020-05-14 2020-06-23 2020-06-12 2020-09-21 2021-04-28 roulants au profit de l'UGP/H ure YDROMET et des Agences d'e xécution. BF-HYDROMET-173321-GO- Improvement of hydromet a DIR / Acquisition de matériel Request for Quota Single Stage - One E IDA / D3740 nd early warning infrastruct Post Limited 1,000,000.00 1,052,375.65 Completed 2020-05-25 2020-07-20 2020-07-07 2021-08-20 2020-11-04 2022-06-25 de secours, d'intervention et tions nvelope ure de sauvetage de victimes au profit de la DGPC. BF-HYDROMET-224803-GO-R Improvement of hydromet a Request for Quota Single Stage - One E FQ / Groupe électrogène de 2 IDA / D3740 nd early warning infrastruct Post Limited 80,000.00 67,433.71 Signed 2021-06-26 2022-01-31 2021-08-06 2022-07-09 2021-10-05 tions nvelope 50 KVA au profit du SP-CONA ure SUR BF-PST2-156788-GO-RFB / A cquisition de package d’obse rvation et de prévision (maté Capacity building and institu Single Stage - One E riel de détection d’orage, d’i IDA / D3740 Post Request for Bids Open - National 327,300.00 0.00 Canceled 2020-03-02 2020-03-07 2020-04-18 2020-04-19 2020-06-02 2020-11-29 tional development nvelope mpact de foudre, de suivi de phénomènes météo extrême s et d’alertes météo) au profi t de l'ANAM BF-PST2-156984-GO-RFB / A cquisition d'équipements (uni Improvement of hydromet a tés de stockage, unités centr Single Stage - One E IDA / D3740 nd early warning infrastruct Post Request for Bids Open - National 200,000.00 0.00 Canceled 2020-04-06 2020-04-11 2020-05-11 2020-05-16 2020-06-25 2020-12-22 ales rackables, RAM, baies, s nvelope ure erveur) pour l'augmentation de la capacité du supercalcu lateur HPC au profit de l’ANA M BF-HYDROMET-225133-GO-R Pending Impl IDA / D3740 Project Management Post Direct Selection Direct 28,910.00 0.00 2021-12-05 2022-01-30 2022-03-31 FQ / Logiciel delta suivi évalu ementation ation BF-HYDROMET-232007-GO-R FB / ACQUISITION ET INSTALL Improvement of hydromet a ATION D’EQUIPEMENTS DES Single Stage - One E Pending Impl IDA / D3740 nd early warning infrastruct Post Request for Bids Open - National 131,190.00 0.00 2021-11-24 2021-11-29 2021-12-13 2022-01-12 2022-02-16 2022-05-17 ATELIERS DE MAINTENANCE nvelope ementation ure AU PROFIT DE L’AGENCE NAT IONALE DE LA METEOROLOGI E (ANAM) BF-HYDROMET-259685-GO-R FQ / Acquisition de fourniture Request for Quota Single Stage - One E s de bureau et de produits d' IDA / D3740 Project Management Post Limited 9,090.00 7,596.86 Completed 2021-11-18 2021-01-05 2021-12-18 2021-11-20 2021-12-28 2022-01-01 tions nvelope entretien au profit de l'Unité de Gestion du Projet HYDRO MET BF-HYDROMET-276489-GO-R Improvement of hydromet a FB / Acquisition de moyens r Single Stage - One E Under Imple IDA / D3740 nd early warning infrastruct Post Request for Bids Open - National 714,308.00 0.00 2022-02-28 2022-07-28 2022-03-05 2022-04-04 2022-04-19 2022-05-14 2022-10-11 oulants spécialisés au profit nvelope mentation ure de la DGPC et du SP-CONASU R (02 lots) Page 2 BF-HYDROMET-225125-GO-R FB / Matériel informatique et Improvement of hydromet a Single Stage - One E Under Imple péri-informatique au profit d IDA / D3740 nd early warning infrastruct Post Request for Bids Open - National 689,510.00 0.00 2022-02-18 2022-04-04 2022-02-23 2022-03-25 2022-04-08 2022-05-03 2022-08-01 nvelope mentation u centre de veille et d'alerte l ure 'ANAM, de la DGRE et de la D GPC (03 lots) BF-PST2-156990-GO-RFQ / R eproduction du guide des ris Enhancement of service deli Request for Quota Single Stage - One E Pending Impl ques et des menaces au profi IDA / D3740 very and warnings to users a Post Limited 45,455.00 0.00 2022-05-11 2022-06-04 2022-08-03 tions nvelope ementation t des élus et des représentan nd communities ts de l’Etat au profit de la DG PC BF-HYDROMET-173331-GO-R FQ / Serveur pour abriter les Request for Quota Single Stage - One E Pending Impl IDA / D3740 Project Management Post Limited 9,090.00 0.00 2020-05-30 2020-07-05 2020-08-19 systèmes des bases de donn tions nvelope ementation ées au profit de l'UGP/HYDRO MET BF-HYDROMET-276582-GO- DIR / Acquisition de matériel Improvement of hydromet a Single Stage - One E Pending Impl s d’épuisement et d'interven IDA / D3740 nd early warning infrastruct Post Request for Bids Limited 218,182.00 0.00 2022-02-25 2022-03-02 2022-04-01 2022-04-16 2022-05-15 2022-09-12 nvelope ementation tion pour renforcer les capaci ure tés de la DGPC en cas d'inno ndation BF-HYDROMET-276596-GO-R Improvement of hydromet a FB / Acquisition et installatio Single Stage - One E Pending Impl IDA / D3740 nd early warning infrastruct Post Request for Bids Open - National 150,000.00 0.00 2022-03-21 2022-03-26 2022-05-07 2022-06-06 2022-07-11 2022-11-08 n des équipements pour le c nvelope ementation ure hamp solaire au profit de l'A NAM BF-HYDROMET-225121-GO-R FB / Système de gestion de b ase de données (logiciel CLID Improvement of hydromet a ATA) pour la collecte, l’archiv Pending Impl IDA / D3740 nd early warning infrastruct Post Direct Selection Direct 524,800.00 0.00 2022-05-10 2022-05-15 2022-06-19 2022-10-17 age et le traitement de Donn ementation ure ées (système de collecte, d’a rchivage, de traitement de d onnées météo) au profit de l' AANAM. BF-HYDROMET-225123-GO-R Improvement of hydromet a FB / Acquisition de Mobiliers Single Stage - One E Pending Impl IDA / D3740 nd early warning infrastruct Post Request for Bids Open - National 297,300.00 0.00 2022-02-28 2022-03-05 2022-04-04 2022-04-18 2022-05-12 2022-08-10 de bureau au profit du centre nvelope ementation ure de veille et d’alerte/ANAM et de la DGRE BF-HYDROMET-225128-GO-R FB / Acquisition et installatio Improvement of hydromet a n de 200 éléments d'échelle Request for Quota Single Stage - One E Pending Impl IDA / D3740 nd early warning infrastruct Post Limited 87,564.00 0.00 2021-06-08 2021-08-03 2021-10-02 pour les station à télé transm tions nvelope ementation ure ission et de 200 supports d'é chelle IPN-180 au profit de la DGRE BF-HYDROMET-277823-GO-R Enhancement of service deli Request for Quota Single Stage - One E FQ / Acquisition de pluviomè IDA / D3740 very and warnings to users a Post Limited 8,582.00 7,187.41 Completed 2022-03-05 2022-04-21 2022-04-30 2022-06-15 2022-06-29 2022-08-26 tions nvelope tres paysans au profit de l'AN nd communities AM BF-HYDROMET-225020-GO-R FB / Postes de travail intégré s pour les unités de producti Improvement of hydromet a Single Stage - One E on (système ou plateforme in IDA / D3740 nd early warning infrastruct Post Request for Bids Open - National 670,000.00 0.00 Canceled 2021-12-07 2021-12-12 2022-01-11 2022-01-25 2022-03-01 2022-06-29 nvelope tégré de collecte, de traitem ure ent, de visualisation et de pr évision météorologique) au p rofit de l’ANAM BF-HYDROMET-225673-GO-R FB / Equipements pour l'aug Improvement of hydromet a mentation de la capacité du Open - Internationa Single Stage - One E IDA / D3740 nd early warning infrastruct Post Request for Bids 200,000.00 0.00 Canceled 2021-07-01 2021-07-06 2021-08-17 2021-08-31 2021-10-05 2022-02-02 supercalculateur HPC (unités l nvelope ure de stockage, unités centrales rackables, RAM, baies, serve ur) au profit de l’ANAM. BF-HYDROMET-225122-GO-R FB / Acquisition et installatio n d’un studio complet d’équi Enhancement of service deli Single Stage - One E pement audio visuels (captur IDA / D3740 very and warnings to users a Post Request for Bids Open - National 262,400.00 0.00 Canceled 2021-11-22 2021-11-27 2021-12-27 2022-01-10 2022-02-10 2022-05-11 nvelope e, montage, mixage, …) pour nd communities la production de bulletins mé téorologiques à l’endroit du p ublic au profit de l'ANAM. BF-HYDROMET-224813-GO-R FB / Stations automatiques P Capacity building and institu Single Stage - One E Under Imple TH (mesure de Précipitation, IDA / D3740 Post Request for Bids Open - National 95,418.00 0.00 2021-11-29 2022-07-20 2021-12-04 2022-01-03 2022-01-17 2022-02-17 2022-05-18 tional development nvelope mentation de Température et d’Humidit é) au profit de l’ANAM BF-PST2-156991-GO-RFQ / A Request for Quota Single Stage - One E cquisition de petits matériels IDA / D3740 Project Management Post Limited 8,909.00 0.00 Signed 2022-08-10 2022-09-01 2022-09-09 2022-10-24 tions nvelope de bureau au profit de l’UGP/ HYDROMET BF-HYDROMET-225669-GO-R FB / Acquisition de matériels météorologiques d'observati ons et de prévision (matériel Capacity building and institu Open - Internationa Single Stage - One E IDA / D3740 Post Request for Bids 400,000.00 0.00 Canceled 2021-12-10 2021-12-22 2021-12-15 2021-12-22 2022-01-26 2022-02-10 2022-02-09 2022-03-16 2022-07-14 s de détection d'orages, d'im tional development l nvelope pacts de foudre, de suivi de phénomènes météorologique s extrêmes et d'alerte météo rologique) au profit de l'ANA M BF-HYDROMET-306614-GO-R FB / Acquisition de matériels météorologiques d'observati ons et de prévision (matériel Capacity building and institu Open - Internationa Single Stage - One E Under Imple IDA / D3740 Post Request for Bids 400,000.00 0.00 2022-08-22 2022-10-20 2022-08-27 2022-10-20 2022-10-08 2022-10-28 2022-11-22 2023-02-20 s de détection d'orages, d'im tional development l nvelope mentation pacts de foudre, de suivi de phénomènes météorologique s extrêmes et d'alerte météo rologique) au profit de l'ANA M BF-PST2-156795-GO-RFQ / A cquisition et installation de p ostes pluviométriques autom Capacity building and institu Request for Quota Single Stage - One E IDA / D3740 Post Limited 35,800.00 29,745.28 Completed 2020-04-06 2020-08-25 2020-05-15 2020-10-09 2020-08-13 2021-11-20 atiques pour accroître la den tional development tions nvelope sité du réseau dans les zones à fort risque d’inondation au profit de l’ANAM BF-HYDROMET-276601-GO-R FB / Acquisition de moyens d Improvement of hydromet a Request for Quota Single Stage - One E Pending Impl e transmission au profit du S IDA / D3740 nd early warning infrastruct Post Limited 70,000.00 0.00 2022-08-25 2022-10-20 2022-12-19 tions nvelope ementation P/CONASUR (drones, GPS, lic ure ence d'exploitation SIG) Page 3 BF-HYDROMET-317466-GO-R FB / Acquisition de matériels informatiques et péri-informa Improvement of hydromet a Single Stage - One E tiques au profit de l'Agence N IDA / D3740 nd early warning infrastruct Post Request for Bids Open - National 590,909.00 0.00 Signed 2022-10-07 2022-10-11 2022-10-12 2022-11-11 2022-11-03 2022-11-26 2022-11-11 2022-12-11 2023-02-09 nvelope ationale de la météorologie ( ure ANAM) et de la Direction Gén érale de la Protection Civile ( DGPC) BF-HYDROMET-318354-GO-R FB / Acquisition et installatio n d'équipements pour les sta Enhancement of service deli tions hydrométriques et pour Open - Internationa Single Stage - One E Pending Impl IDA / D3740 very and warnings to users a Post Request for Bids 1,000,000.00 0.00 2022-12-15 2022-12-20 2023-01-31 2023-02-20 2023-03-27 2023-09-23 l’infrastructure informatique l nvelope ementation nd communities de transfert/gestion de donn ées au profit de la Direction des Études et de l'Informatio n sur l'Eau (DEIE). BF-HYDROMET-276578-GO-R Improvement of hydromet a Open - Internationa Single Stage - One E Pending Impl FB / Acquisition des moyens IDA / D3740 nd early warning infrastruct Prior Request for Bids 2,110,833.00 0.00 2022-12-30 2023-01-04 2023-02-18 2023-03-20 2023-04-17 2024-10-08 l nvelope ementation de télécommunication au pro ure fit de la DGPC BF-PST2-156989-GO-RFQ / A Improvement of hydromet a Request for Quota Single Stage - One E Pending Impl cquisition de fonds document IDA / D3740 nd early warning infrastruct Post Limited 27,273.00 0.00 2023-05-15 2023-06-14 2023-08-13 tions nvelope ementation aire pour la salle de docume ure ntation du SAP. BF-HYDROMET-350635-GO-R Improvement of hydromet a Request for Quota Single Stage - One E Pending Impl FQ / Acquisition de 55 téléph IDA / D3740 nd early warning infrastruct Post Limited 32,727.00 0.00 2023-05-24 2023-07-04 2023-08-18 tions nvelope ementation ones GSM Smartphones au p ure rofit de la DGRE BF-HYDROMET-350619-GO-R FQ / Acquisition d'un Kit de r Improvement of hydromet a Request for Quota Single Stage - One E Pending Impl eprographie constitué d'une i IDA / D3740 nd early warning infrastruct Post Limited 38,182.00 0.00 2023-05-27 2023-07-15 2023-08-14 tions nvelope ementation mprimante multifonction A3 ure et d'un ordinateur de traitem ent des images BF-HYDROMET-350626-GO-R FB / Acquisition de moyens r Improvement of hydromet a Single Stage - One E Pending Impl oulants spécialisés (3 camion IDA / D3740 nd early warning infrastruct Post Request for Bids Limited 350,671.00 0.00 2023-05-26 2023-05-31 2023-06-30 2023-07-15 2023-08-09 2024-02-05 nvelope ementation s de 20T et 1 plateau équipé ure de citerne) au profit du SP/C ONASUR BF-HYDROMET-362319-GO-R Improvement of hydromet a FB / Acquisition et installatio Single Stage - One E Pending Impl IDA / D3740 nd early warning infrastruct Post Request for Bids Open - National 753,756.00 0.00 2023-06-12 2023-06-17 2023-07-29 2023-08-28 2023-10-02 2024-03-30 n des moyens de communica nvelope ementation ure tion au profit de la DGPC NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BF-PST2-134931-NC-RFQ / E Request for Quota Single Stage - One E ntretien et nettoyage des loc IDA / D3740 Project Management Post Limited 5,000.00 4,151.92 Completed 2019-09-26 2019-04-15 2019-10-20 2019-05-01 2020-06-16 2020-01-01 tions nvelope aux de l’UGP/HYDROMET BF-HYDROMET-259681-NC-R Request for Quota Single Stage - One E FQ / Entretien et maintenanc IDA / D3740 Project Management Post Limited 3,636.00 2,878.88 Completed 2021-11-21 2021-01-05 2022-01-01 2021-11-04 2022-01-11 2021-11-17 tions nvelope e du groupe électrogène BF-HYDROMET-225231-NC-D IR / Accord de partenariat av Enhancement of service deli ec les médias (radios rurales, Pending Impl IDA / D3740 very and warnings to users a Post Direct Selection Direct 10,000.00 0.00 2021-04-27 2021-05-02 2021-06-06 2021-12-03 télévision) pour la diffusion d ementation nd communities e l’information climatique en différentes langues au profit de l'ANAM BF-PST2-126659-NC-DIR / As surance maladie au profit du Request for Quota Single Stage - One E IDA / D3740 Project Management Post Limited 20,000.00 0.00 Canceled 2020-02-02 2020-02-28 2021-02-22 personnel de l'UGP/HYDROM tions nvelope ET pour le compte de l'année 2020. BF-HYDROMET-278008-NC-D IR / Développement de la pre Enhancement of service deli station de service directe au Pending Impl IDA / D3740 very and warnings to users a Post Direct Selection Direct 20,000.00 0.00 2022-05-31 2022-06-05 2022-07-11 2023-01-07 x bénéficiaires par le pilotage ementation nd communities de la diffusion d'avertisseme nts avec des prestataires de service de téléphonie portabl e BF-HYDROMET-278252-NC-R FQ / Acquisition et installatio Improvement of hydromet a Request for Quota Single Stage - One E Under Imple n de réseau informatique et r IDA / D3740 nd early warning infrastruct Post Open - National 90,000.00 0.00 2022-03-05 2022-04-30 2022-06-29 tions nvelope mentation éseau au profit de l'Agence N ure ationale de la Météorologie ( ANAM) BF-HYDROMET-317469-NC-R Enhancement of service deli FQ / Reproduction de prospe Request for Quota Single Stage - One E IDA / D3740 very and warnings to users a Post Limited 9,091.00 0.00 Completed 2022-10-12 2022-11-17 2022-11-02 2022-11-16 2023-01-23 ctus de sensibilisation sur les tions nvelope nd communities risques d'inondation au profit des communautés CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BF-PST2-93979-CS-CQS / Ela Improvement of hydromet a boration des études Architect Consultant Qualifi IDA / D3740 nd early warning infrastruct Post Open - National 60,000.00 56,240.50 Signed 2019-01-28 2020-02-25 2019-02-18 2020-04-02 2019-04-03 2020-05-08 2019-05-03 2020-05-04 2019-06-07 2020-07-01 2019-12-04 urale et technique de constru cation Selection ure ction du bâtiment de la DEIE BF-PST2-93972-CS-CQS / Etu Capacity building and institu Consultant Qualifi Under Implement des de travaux de réhabilitati IDA / D3740 Post Open - National 40,000.00 0.00 2020-02-06 2020-10-27 2020-02-27 2021-02-01 2020-04-11 2020-05-11 2020-06-24 2020-09-22 tional development cation Selection ation on des stations synoptiques de l'ANAM BF-PST2-134936-CS-CQS / R éalisation d’une étude de fais Improvement of hydromet a Consultant Qualifi abilité en vue de la dotation IDA / D3740 nd early warning infrastruct Post Open - National 30,000.00 35,760.21 Completed 2020-03-26 2020-10-27 2020-04-25 2021-02-01 2020-06-15 2021-04-02 2020-07-06 2021-04-21 2020-08-10 2021-08-20 2020-12-08 2022-04-26 cation Selection d’un champ solaire pour la fo ure urniture d’électricité de l’ANA M. Page 4 BF-PST2-157010-CS-CQS / R Improvement of hydromet a ecrutement d'un cabinet pou Consultant Qualifi Under Implement IDA / D3740 nd early warning infrastruct Post Open - National 50,000.00 0.00 2020-07-30 2021-11-16 2020-08-20 2020-10-03 2020-11-02 2020-12-07 2021-08-04 r le suivi-contrôle des travau cation Selection ation ure x de construction du bâtimen t de la DEIE BF-PST2-157357-CS-CQS / R ecrutement d'un cabinet pou Least Cost Selecti r l’audit externe des comptes IDA / D3740 Project Management Post Open - National 44,000.00 18,432.39 Completed 2020-03-02 2020-03-02 2020-03-23 2020-04-03 2020-05-06 2020-05-12 2020-06-05 2020-06-03 2020-06-19 2020-06-08 2020-07-13 2020-07-09 2020-08-08 2020-09-09 2020-09-07 2020-10-01 on des exercices 2019, 2020 et 2021 du projet HYDROMET. BF-HYDROMET-225512-CS-C QS / Mise en place d’un plan Capacity building and institu Consultant Qualifi Open - Internationa Under Implement IDA / D3740 Post 120,000.00 0.00 2021-07-15 2021-12-22 2021-07-29 2023-03-17 2021-09-04 2021-09-14 2021-10-19 2022-01-17 de qualité (certification) ISO tional development cation Selection l ation au profit de l'ANAM. BF-HYDROMET-225516-CS-C QS / Mise en place d’un plan Capacity building and institu Consultant Qualifi Open - Internationa Under Implement de recouvrement des coûts e IDA / D3740 Post 90,600.00 0.00 2021-07-06 2021-12-23 2021-07-20 2023-03-16 2021-08-26 2021-08-27 2021-10-01 2021-12-30 tional development cation Selection l ation t de mobilisation des ressour ces au profit de l'ANAM BF-PST2-134934-CS-QCBS / Enhancement of service deli Réalisation d'une étude de c Consultant Qualifi IDA / D3740 very and warnings to users a Post Open - National 140,000.00 0.00 Canceled 2019-11-04 2019-11-25 2019-12-19 2020-01-18 2020-02-22 2020-06-21 artographie des zones inond cation Selection nd communities ables au profit de la DGRE BF-HYDROMET-225507-CS-C Enhancement of service deli Consultant Qualifi Under Implement QS / Etude sur l'impact socio- IDA / D3740 very and warnings to users a Post Open - National 60,000.00 0.00 2021-06-21 2021-12-22 2021-07-05 2021-08-18 2021-08-28 2021-10-02 2021-12-01 cation Selection ation économique de l’ANAM nd communities BF-HYDROMET-225698-CS-Q CBS / Etude d'identification d es secteurs prioritaires rurau x et urbains (zones inondable Enhancement of service deli Quality And Cost- Open - Internationa Under Implement s, SAP urbains et ruraux), co IDA / D3740 very and warnings to users a Prior 1,775,900.00 0.00 2022-03-15 2022-04-13 2022-04-05 2022-05-19 2022-06-16 2022-07-16 2022-08-20 2022-09-24 2023-09-24 Based Selection l ation nception, calage et mise en nd communities œuvre des modèles hydrolog iques et hydrauliques qui ser ont utilisés pour l'alerte préc oce sur les bassins versants BF-HYDROMET-277506-CS-C QS / Recrutement d’un (01) c Enhancement of service deli onsultant pour l'élaboration d Consultant Qualifi Pending Impleme IDA / D3740 very and warnings to users a Post Open - National 20,000.00 0.00 2022-08-29 2022-09-13 2022-10-12 2022-10-27 2022-11-20 2023-01-19 e la politique nationale huma cation Selection ntation nd communities nitaire et de la relecture de l oi sur la prévention et la gest ion des catastrophes BF-HYDROMET-277512-CS-C QS / Recrutement d’un (01) c Enhancement of service deli Consultant Qualifi Pending Impleme onsultant pour l'élaboration d IDA / D3740 very and warnings to users a Post Open - National 49,091.00 0.00 2022-08-22 2022-09-12 2022-10-11 2022-10-26 2022-11-19 2023-01-18 cation Selection ntation es plans de contingence régi nd communities onaux (Hauts-Bassins, Centre -Est, Centre-Sud) BF-HYDROMET-277514-CS-C QS / Recrutement d’un (01) c onsultant pour l’élaboration Enhancement of service deli Consultant Qualifi Pending Impleme des projets de textes statuta IDA / D3740 very and warnings to users a Post Open - National 20,000.00 0.00 2022-03-10 2022-03-31 2022-05-14 2022-06-13 2022-07-07 2022-09-05 cation Selection ntation ires pour la mise en place de nd communities l’Agence Unique de gestion d es catastrophes tel que reco mmandé par la CEDEAO BF-HYDROMET-277518-CS-C QS / Mise en place d'une plat Enhancement of service deli Consultant Qualifi Pending Impleme e-forme interactive de partag IDA / D3740 very and warnings to users a Post Open - National 90,909.00 0.00 2022-05-13 2022-06-03 2022-07-17 2022-08-16 2022-09-09 2023-01-07 cation Selection ntation e de l'information avec les au nd communities tres membres du dispositif n ational SAP BF-HYDROMET-277555-CS-C Improvement of hydromet a QS / Étude technique de réali Consultant Qualifi Pending Impleme IDA / D3740 nd early warning infrastruct Post Open - National 39,091.00 0.00 2022-05-23 2022-06-13 2022-07-27 2022-08-26 2022-09-30 2022-11-29 sation d'un champ solaire au cation Selection ntation ure profit de l'ANAM BF-HYDROMET-277746-CS-C QS / Recrutement d'un consu Capacity building and institu Consultant Qualifi Pending Impleme ltant pour l'actualisation et la IDA / D3740 Post Open - National 90,900.00 0.00 2022-04-20 2022-05-11 2022-06-24 2022-07-24 2022-08-18 2022-10-17 tional development cation Selection ntation validation du plan stratégiqu e 2022-2026 de modernisatio n de l’ANAM BF-HYDROMET-277749-CS-L CS / Recrutement d'un cabin Least Cost Selecti Under Implement IDA / D3740 Project Management Post Open - National 27,273.00 0.00 2022-04-28 2022-07-08 2022-05-19 2022-07-02 2022-07-30 2022-08-29 2022-10-03 2022-11-07 2022-12-07 et pour l'audit externe des co on ation mptes de 2022,2023 et 2024 BF-HYDROMET-225510-CS-C QS / Elaboration d’un manuel d’audit interne, de la cartogr Consultant Qualifi IDA / D3740 Project Management Post Open - National 30,000.00 0.00 Canceled 2021-07-15 2021-07-29 2021-09-11 2021-09-21 2021-10-22 2021-12-21 aphie des risques, d’une polit cation Selection ique de gestion des risques e t d’un plan d’audit interne pl uriannuel du Projet HYDROM ET BF-HYDROMET-350675-CS-C QS / Recrutement d'un cabin Improvement of hydromet a Consultant Qualifi Under Implement et pour le suivi-contrôle des t IDA / D3740 nd early warning infrastruct Post Open - National 51,818.00 0.00 2023-04-20 2023-06-26 2023-04-30 2023-05-25 2023-06-24 2023-07-16 2023-12-13 cation Selection ation ravaux de construction du bâ ure timent R+1 extensible en R+ 2 de la DEIE. BF-HYDROMET-350685-CS-C Improvement of hydromet a QS / Etude architecturale pou Consultant Qualifi Under Implement IDA / D3740 nd early warning infrastruct Post Open - National 60,000.00 0.00 2023-04-10 2023-03-30 2023-04-20 2023-05-15 2023-05-30 2023-06-27 2023-08-26 r la construction de stations cation Selection ation ure d'observations synoptiques a u profit de l'ANAM. BF-HYDROMET-350691-CS-C QS / Recrutement d'un consu Improvement of hydromet a ltant pour le suivi et le contrô Consultant Qualifi Pending Impleme IDA / D3740 nd early warning infrastruct Post Open - National 127,273.00 0.00 2023-06-12 2023-07-03 2023-08-16 2023-09-15 2023-10-20 2024-10-19 le de l'installation des équipe cation Selection ntation ure ments de télécommunication au profit de la DGPC (reseau PS-LTE) Page 5 BF-HYDROMET-364185-CS-C QS / Recrutement d’un consu ltant pour la réalisation de l’é Enhancement of service deli tude de faisabilité et de supe Consultant Qualifi Open - Internationa Under Implement IDA / D3740 very and warnings to users a Post 45,455.00 0.00 2023-06-05 2023-06-08 2023-06-26 2023-06-15 2023-07-25 2023-08-24 2023-09-28 2023-11-27 rvision de la plateforme uniq cation Selection l ation nd communities ue de gestion de l'informatio n et de l'alerte précoce des d ifférents systèmes d'informat ion sectoriel INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BF-PST2-93522-CS-INDV / El aboration du manuel d'exécu Individual Consult IDA / V2230 Project Management Post Limited 50,000.00 0.00 Under Review 2019-01-15 2019-01-09 2019-01-20 2019-02-10 2019-03-17 2019-04-16 tion et de suivi et évaluation ant Selection du projet HYDROMET BF-PST2-93983-CS-INDV / Fo rmation des acteurs sur la rè Individual Consult IDA / V2230 Project Management Post Open 40,000.00 35,978.45 Completed 2019-01-28 2019-02-04 2019-03-18 2019-04-01 2019-04-08 2019-05-22 2019-05-27 2019-06-21 2019-06-06 2019-08-02 glementation de la Banque ant Selection mondiale en matière de pass ation des marchés BF-PST2-93984-CS-INDV / Re crutement d'un expert en pro Individual Consult IDA / V2230 Project Management Post Open 5,600.00 0.00 Canceled 2019-01-30 2019-01-28 2019-03-20 2019-04-10 2019-05-29 2019-09-26 tection sociale et environne ant Selection mentale (04 mois) BF-PST2-93988-CS-INDV / Re Individual Consult crutement d'un expert en sui IDA / V2230 Project Management Post Open 5,600.00 0.00 Canceled 2019-01-29 2019-03-19 2019-04-09 2019-05-28 2019-09-25 ant Selection vi et évaluation BF-PST2-99405-CS-INDV / Re Individual Consult crutement d'un expert en sui IDA / V2230 Project Management Post Open 16,800.00 0.00 Under Review 2019-02-13 2019-06-11 2019-02-27 2019-03-01 2019-03-05 2020-03-04 ant Selection vi et évaluation BF-PST2-113041-CS-INDV / r Individual Consult Under Implement ecrutement d'un Auditeur int IDA / V2230 Project Management Post Open 16,800.00 0.00 2019-05-09 2021-11-16 2019-05-23 2019-05-25 2019-06-09 2020-06-08 ant Selection ation erne au profit du projet HYDR OMET BF-PST2-127046-CS-INDV / R ecrutement d'un consultant p Individual Consult IDA / D3740 Project Management Post Limited 20,000.00 0.00 Canceled 2019-10-28 2019-12-02 2019-11-02 2019-11-23 2019-12-28 2020-01-27 our l’audit externe des comp ant Selection tes de l’exercice 2019 du pro jet HYDROMET BF-PST2-126653-CS-CDS / S uivi contrôle des travaux d'e Contingent Emergency Resp IDA / D3740 Post Direct Selection Direct 100,000.00 85,211.97 Completed 2019-10-01 2019-12-10 2019-10-11 2019-10-08 2019-11-12 2020-01-01 2020-09-07 2020-10-03 xtension du centre national d onse Component e veille et d’alerte précoce a u profit de l’ANAM BF-PST2-134935-CS-INDV / R ecrutement d’un consultant Capacity building and institu Individual Consult IDA / D3740 Post Limited 16,000.00 5,855.37 Completed 2019-10-28 2020-06-18 2019-11-02 2020-08-10 2019-11-07 2020-10-09 2019-11-29 2020-10-28 2019-12-29 2021-01-10 pour la formation des cadres tional development ant Selection du SAP en analyse de l'écono mie des ménages BF-PST2-150251-CS-INDV / R ecrutement d’un consultant pour la réalisation d’une étud Capacity building and institu Individual Consult IDA / D3740 Post Limited 20,000.00 19,091.66 Completed 2020-02-17 2020-06-24 2020-02-22 2020-08-28 2020-03-14 2020-10-07 2020-04-18 2020-11-28 2020-07-17 2021-08-21 e des lieux des structures de tional development ant Selection réduction des risques des cat astrophes et crises humanitai res au profit de la DGPC. BF-PST2-157002-CS-INDV / R ecrutement d'un consultant p Capacity building and institu Individual Consult our l'élaboration de la straté IDA / D3740 Post Limited 33,000.00 20,027.08 Completed 2020-03-24 2020-06-18 2020-03-29 2020-08-25 2020-04-19 2020-10-15 2020-05-24 2020-12-31 2020-08-22 2022-04-02 tional development ant Selection gie de communication du SA P à l'endroit des communaut és au profit du SAP BF-PST2-127050-CS-INDV / R ecrutement d’un consultant pour la formation des cadres Capacity building and institu Individual Consult IDA / D3740 Post Limited 24,000.00 22,714.42 Completed 2020-04-02 2020-03-02 2020-04-07 2020-05-11 2020-04-28 2020-06-08 2020-06-11 2020-07-15 2020-07-01 2021-09-17 du dispositif SAP central et d tional development ant Selection éconcentré en logiciel SIG et télédétection et de 20 agents en SIG au profit de la DGRE BF-PST2-157005-CS-INDV / R ecrutement d'un consultant p Capacity building and institu Individual Consult our la formation des cadres d IDA / D3740 Post Limited 9,100.00 7,378.87 Completed 2020-04-30 2020-06-17 2020-05-05 2020-09-17 2020-05-26 2020-12-10 2020-06-30 2021-02-09 2020-08-29 2021-06-02 tional development ant Selection u dispositif SAP central sur le s modèles de prévision des p rix BF-PST2-157006-CS-INDV / R ecrutement d'un consultant p our la formation des cadres d Capacity building and institu Individual Consult IDA / D3740 Post Limited 14,545.00 10,183.26 Completed 2020-06-15 2020-06-17 2020-06-20 2020-09-03 2020-07-11 2020-10-05 2020-08-15 2020-12-31 2020-09-14 2021-06-17 u dispositif SAP central et dé tional development ant Selection concentré en rédaction des a rticles et montage de bulletin s BF-PST2-157008-CS-INDV / R ecrutement d'un consultant p our l'assistance technique inf ormatique en vue de la mode Capacity building and institu Individual Consult Under Implement IDA / D3740 Post Limited 19,100.00 0.00 2020-07-27 2020-06-17 2020-08-01 2020-08-22 2020-09-26 2020-11-25 rnisation de la salle de docu tional development ant Selection ation mentation du SAP et la forma tion des cadres chargés du g uichet unique en archivage n umérique des données (2 lot s) BF-PST2-157009-CS-INDV / R ecrutement d'un consultant p our la formation des cadres c Capacity building and institu Individual Consult IDA / D3740 Post Limited 8,182.00 7,470.65 Completed 2020-05-14 2020-06-17 2020-05-19 2020-08-10 2020-06-09 2020-10-09 2020-07-14 2020-10-28 2020-08-13 2021-06-05 entraux (formateurs) sur les tional development ant Selection concepts de sécurité aliment aire, la nutrition et l’alerte pr écoce au profit du SAP BF-PST2-157011-CS-INDV / R ecrutement d'un consultant p Enhancement of service deli our l'élaboration d'un guide d Individual Consult IDA / D3740 very and warnings to users a Post Limited 14,545.00 13,713.31 Signed 2020-07-20 2020-06-24 2020-07-25 2021-11-03 2020-08-15 2021-12-01 2020-09-19 2022-01-21 2020-11-18 es risques et des menaces a ant Selection nd communities u profit des élus et des repré sentants de l'Etat au profit d e la DGPC Page 6 BF-PST2-157012-CS-INDV / R ecrutement d'un consultant p our la mise en place d’une st ratégie de communication et Enhancement of service deli Individual Consult Pending Impleme un Protocole Standard d’opér IDA / D3740 very and warnings to users a Post Limited 36,365.00 0.00 2020-04-30 2020-05-05 2020-05-26 2020-06-30 2020-10-28 ant Selection ntation ation (SOP) pour la transmiss nd communities ion de l’information climatiqu e, en partenariat avec le SAP , la DGPC, le CONASUR et la DGRE au profit de l'ANAM BF-PST2-157013-CS-INDV / R ecrutement d'un consultant p our l'appui technique pour l’é Enhancement of service deli laboration et la mise en plac Individual Consult IDA / D3740 very and warnings to users a Post Limited 40,000.00 34,198.78 Completed 2020-06-11 2020-09-18 2020-06-16 2020-11-20 2020-07-07 2021-03-12 2020-08-11 2021-04-17 2020-12-09 2021-10-11 e du SOP et de la stratégie d ant Selection nd communities e communication pour les au tres partenaires (Energie, Infr astructures, Mines, Transport s) au profit de l'ANAM) BF-PST2-157014-CS-INDV / R ecrutement d'un consultant p Individual Consult IDA / D3740 Project Management Post Limited 9,090.00 8,538.64 Completed 2020-04-16 2020-04-16 2020-04-21 2020-05-06 2020-05-12 2020-06-10 2020-06-16 2020-06-23 2020-08-15 2020-09-08 our la mise en place le site w ant Selection eb du Projet HYDROMET BF-PST2-157015-CS-INDV / R ecrutement d'un consultant p Individual Consult our d'un consultant pour l'éta IDA / D3740 Project Management Post Limited 16,365.00 15,473.42 Completed 2020-06-18 2020-05-12 2020-06-23 2020-05-19 2020-07-14 2020-06-10 2020-08-18 2020-07-15 2020-12-16 2020-09-26 ant Selection blissement de la situation de référence du Projet HYDROM ET BF-PST2-93978-CS-INDV / Et Capacity building and institu Individual Consult ude technique des moyens d IDA / D3740 Post Limited 30,000.00 28,659.33 Completed 2020-04-06 2020-06-24 2020-04-11 2020-10-01 2020-05-02 2021-02-25 2020-06-06 2021-09-11 2020-08-05 2021-12-01 tional development ant Selection e communication de la Prote ction civile BF-HYDROMET-167523-CS-I Enhancement of service deli Individual Consult NDV / Mise à jour du site web IDA / D3740 very and warnings to users a Post Limited 7,273.00 6,791.91 Completed 2020-05-20 2020-06-26 2020-05-25 2020-08-10 2020-06-15 2020-06-16 2020-07-20 2020-10-28 2020-09-18 2021-09-14 ant Selection du SAP/DGESS/MAAH nd communities BF-HYDROMET-225509-CS-I Individual Consult NDV / Production d'un film do IDA / D3740 Project Management Post Limited 17,273.00 0.00 Signed 2021-08-17 2021-11-23 2021-08-22 2022-03-16 2021-09-12 2022-04-01 2021-10-17 2021-12-16 ant Selection cumentaire sur le projet HYD ROMET BF-PST2-126829-CS-INDV / R ecrutement d'un consultant i ndividuel pour l'élaboration d Individual Consult IDA / D3740 Project Management Post Limited 58,182.00 54,112.51 Completed 2021-06-15 2021-11-16 2021-06-20 2021-08-13 2021-07-11 2021-09-07 2021-08-15 2021-12-14 2021-10-14 2022-01-08 e huit (08) Notices d'Impacts ant Selection Environnemental et social de s stations synoptiques de l'A NAM. BF-HYDROMET-277550-CS-C DS / Recrutement d’un consu ltant pour la réalisation de l’é tude de faisabilité et de supe Enhancement of service deli Pending Impleme rvision de la plateforme uniq IDA / D3740 very and warnings to users a Post Direct Selection Direct 45,455.00 0.00 2022-03-10 2022-03-20 2022-05-13 2022-07-12 ntation ue de gestion de l'informatio nd communities n et de l'alerte précoce des d ifférents systèmes d'informat ion sectoriel (plateforme glob ale intégrateur) BF-PST2-157003-CS-INDV / R ecrutement d'un consultant p Capacity building and institu Individual Consult Pending Impleme IDA / D3740 Post Limited 28,365.00 0.00 2022-05-16 2022-05-21 2022-06-11 2022-07-05 2022-10-03 our l'étude diagnostique sur tional development ant Selection ntation la modernisation du SAP Nati onal BF-PST2-157001-CS-INDV / R ecrutement d'un consultant p our l'étude sur l'automatisati on du contrôle-qualité des do Capacity building and institu Individual Consult IDA / D3740 Post Limited 24,000.00 0.00 Canceled 2020-03-10 2020-03-15 2020-04-05 2020-05-10 2020-08-08 nnées et leur acheminement tional development ant Selection du réseau vers le centre d’ar chivage et la Prévision Numé rique du Temps (PNT et HPC) au profit de l'ANAM BF-HYDROMET-277733-CS-I NDV / Recrutement d'un cons Individual Consult Under Implement ultant individuel pour la réali IDA / D3740 Project Management Post Open 36,364.00 0.00 2022-02-28 2022-03-28 2022-04-18 2022-05-09 2022-06-13 2022-08-12 ant Selection ation sation de la revue à mi-parco urs du projet HYDROMET. BF-HYDROMET-225520-CS-I NDV / Formation du dispositif SAP sur le genre et sa prise e Capacity building and institu Individual Consult IDA / D3740 Post Limited 8,182.00 0.00 Completed 2022-02-28 2022-03-31 2022-03-05 2022-04-05 2022-03-26 2022-05-11 2022-04-30 2022-05-30 2022-09-09 n compte dans les analyses d tional development ant Selection e la sécurité alimentaire et d e l’alerte précoce au profit d u SAP BF-HYDROMET-259658-CS-C DS / Recrutement d'un consu Capacity building and institu Pending Impleme IDA / D3740 Post Direct Selection Direct 24,888.00 0.00 2022-03-14 2022-03-18 2022-04-04 2022-04-18 ltant pour la formation des d tional development ntation écideurs en gestion des crise s et des catastrophes BF-PST2-157016-CS-INDV / R ecrutement d'un consultant c Individual Consult hargé de l'élaboration d'un pl IDA / D3740 Project Management Post Limited 9,090.00 0.00 Canceled 2020-06-22 2020-06-27 2020-07-18 2020-08-22 2020-11-20 ant Selection an de prise en compte du ge nre pour le projet HYDROMET . BF-PST2-162324-CS-INDV / R ecrutement d'un spécialiste e Individual Consult n sauvegarde environnement IDA / D3740 Project Management Post Open 20,750.00 0.00 Canceled 2020-03-02 2020-03-02 2020-03-26 2020-03-27 2020-04-22 2021-04-17 ant Selection ales et sociales pour le comp te du projet HYDROMET. BF-PST2-99402-CS-INDV / Re Individual Consult crutement d'un expert en pro IDA / V2230 Project Management Post Open 16,800.00 0.00 Canceled 2019-02-06 2019-02-15 2019-02-16 2019-02-19 2020-02-19 ant Selection tection sociale et environne mentale BF-PST2-118681-CS-INDV / r Individual Consult ecrutement d’un communica IDA / V2230 Project Management Post Open 16,800.00 0.00 Canceled 2019-06-30 2019-08-06 2019-07-17 2019-07-19 2019-08-03 2020-08-02 ant Selection teur au profit du projet HYDR OMET Page 7 BF-HYDROMET-317649-CS-C DS / Assistance technique po ur la conception, le développ Enhancement of service deli Direct - Internation Under Implement ement et la mise en œuvre d IDA / D3740 very and warnings to users a Prior Direct Selection 2,092,004.00 0.00 2022-10-07 2022-11-08 2022-10-17 2022-11-24 2022-12-21 2024-12-10 al ation ’un Système d’Alerte Précoce nd communities des Crues et Inondations ; a mélioration des produits et s ervice de prévision d’inondati ons. BF-HYDROMET-306180-CS-C DS / Formation des cadres en Enhancement of service deli élaboration de plans d'urgen Under Implement IDA / D3740 very and warnings to users a Post Direct Selection Direct - National 49,776.00 0.00 2022-10-15 2022-11-04 2022-10-25 2022-11-25 2022-11-28 ce ( EDD/POI/PPI/PCS......) et ation nd communities des acteurs de protection civi le en gestion des crises et ca tastrophes BF-HYDROMET-322632-CS-I NDV / Formation des cadres de l'UGP, de la cellule genre Individual Consult Under Implement du MTMUSR et des points foc IDA / D3740 Project Management Post Limited 9,091.00 0.00 2022-11-07 2022-11-04 2022-11-12 2022-11-27 2022-12-05 2022-12-15 ant Selection ation aux genre sur les outils et les techniques pratiques d'intégr ation du genre dans les proje ts et programmes de dévelop pement BF-HYDROMET-323880-CS-C DS / Assistance technique po ur le renforcement et l'intégr ation des capacités de prévis Capacity building and institu Direct - Internation Under Implement IDA / D3740 Prior Direct Selection 2,982,715.00 0.00 2022-11-14 2022-11-09 2022-11-24 2022-11-24 2023-01-09 2024-10-30 ion et de développement de tional development al ation services et informations agro -météorologiques et climatiq ues au profit des utilisateurs finaux de l'ANAM. BF-HYDROMET-323883-CS-I NDV / Recrutement d'un cons Enhancement of service deli ultant individuel en vue d'ass Individual Consult Under Implement IDA / D3740 very and warnings to users a Post Open - National 20,000.00 0.00 2022-11-14 2023-03-16 2022-12-18 2023-01-02 2023-01-24 2023-02-07 urer la formation d’agents en ant Selection ation nd communities Prévision Numérique du Tem ps (PNT) et assimilation des données BF-HYDROMET-323981-CS-C DS / Recrutement d'un consu Improvement of hydromet a ltant pour le suivi contrôle d Direct - Internation Pending Impleme IDA / D3740 nd early warning infrastruct Post Direct Selection 81,818.00 0.00 2022-12-30 2023-01-09 2023-02-28 2024-10-20 es installations des équipem al ntation ure ents de communication au pr ofit de la Direction Générale de la Protection Civile (DGPC ) BF-HYDROMET-325993-CS-I NDV / Recrutement d'un cons ultant individuel pour la form Individual Consult Under Implement ation des acteurs impliqués d IDA / D3740 Project Management Post Limited 36,364.00 0.00 2022-11-21 2023-01-25 2022-11-26 2022-12-17 2023-01-21 2023-07-20 ant Selection ation ans le processus de passatio n des marchés publics du pro jet de renforcement de la rés ilience climatique (HYDROME T). BF-HYDROMET-350689-CS-C Capacity building and institu Pending Impleme DS / Formation des cadres de IDA / D3740 Post Direct Selection Direct - National 54,545.00 0.00 2023-06-05 2023-06-15 2023-08-19 2024-02-15 tional development ntation la protection civile en SIG Page 8 PROCUREMENT PLAN (Mandatory Requirement) Project information: Country: Bhutan Project Name: COVID-19 Emergency Response and Health Systems Preparedness Project P-number: P173787 Project Implementation agency: Ministry of Health (MoH) Period covered by this Procurement Plan: Entire Project Period Preamble In accordance with paragraph 5.9 of the World Bank Procurement Regulations for IPF Borrowers, July 2016, revised November 2017 and August 2018 (“Procurement Regulations”), the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to record all procurement actions for the Project, including preparing, updating and clearing its Procurement Plan, and seeking and receiving the Bank’s review and No-objection to procurement actions as required. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: The Bank’s Standard Procurement Documents (SPDs) shall be used for all contracts subject to international competitive procurement and those contract as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the World Bank Procurement Regulations, when approaching the national market, as agreed in the Procurement Plan, the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in Procurement Rules and Regulations, 2019, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions: 1) At the Borrower’s request, the Bank may agree to the Borrower’s use, in whole or in part, of its electronic procurement system, provided that the Bank is satisfied with the adequacy of such system. 2) Procurement shall be open to eligible bidders as defined under Section III of the Procurement Regulations. Accordingly, no bidder or potential bidder shall be declared ineligible for contracts financed by the Bank for reasons other than those provided in Section III of the Procurement Regulations. 3) The request for bids/request for proposals document shall require that Bidders/Proposers submitting Bids/Proposals present a signed acceptance (in the form attached) at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights. 4) Procurement Documents include provisions, as agreed with the Bank, intended to adequately mitigate against environmental, social (including sexual exploitation and abuse and gender-based violence), health and safety (“ESHS”) risks and impacts. 5) The Bank shall have the right to review procurement documentation and activities. When other national procurement arrangements (other than national open competitive procurement) are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. As per paragraph 5.4 of the Procurement Regulations, the “Letter of Acceptance of the World Bank’s Anticorruption Guidelines and Sanctions Framework” as attached to this document shall form part of the Model Bidding Documents. Leased Assets: Not Applicable. Procurement of Second-Hand Goods: as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables – Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Specify for each Goods: [is not applicable/is applicable for those contracts identified in the Procurement Plan tables]; Works: [is not applicable/is applicable for those contracts identified in the Procurement Plan tables] Hands-on Expanded Implementation Support (HEIS): as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations is Applicable. Bank’s Procurement Prior Review Thresholds: As this is an emergency response project, there will be no prior review for all procurement during the immediate response period. The project will also have increased threshold for Request for Quotations (RFQ) and national procurement, as applicable in emergency projects. Procurement under Retroactive Financing: Contracts that were procured during the period January 1, 2020 and prior to signing of the Financing Agreement will be eligible for the World Bank’s retroactive financing, if: (i) the procurement procedures, including advertising, are consistent with Sections I, II and III of the Procurement Regulations; and (ii) the contractor/supplier/consultant has explicitly agreed to comply with the relevant provisions of the World Bank’s Anti-Corruption Guidelines, including the World Bank’s right to inspect and audit all accounts, records, and other documents relating to the project that are required to be maintained pursuant to the Financing Agreement. However, there are practical limits to the application of the Anti-Corruption Guidelines in the case of unsuccessful bidders for these retroactively financed contracts. Accordingly, the waiver of paragraph 6 (requiring that the Anti-Corruption Guidelines be applied to all procurement) and paragraphs 9(d) and 10 (requiring agreement by bidders and contractors to comply with the Anti- Corruption Guidelines) of the Anti-Corruption Guidelines, as requested by the Global MPA, will apply to the project. Letter of Acceptance of the World Bank’s Anticorruption Guidelines and Sanctions Framework1 Date: Invitation of Bids/Proposals No.__________ To: ___________________________________________________________________________ We, along with our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not) consultants and personnel, acknowledge and agree to abide by the World Bank’s policy regarding Fraud and Corruption (corrupt, fraudulent, collusive, coercive, and obstructive practices), as set out and defined in the World Bank’s Anti-Corruption Guidelines2 in connection with the procurement and execution of the contract (in case of award), including any amendments thereto. 1[Drafting note: This document shall be signed by bidders/proposers/consultants and submitted as part of their bids/proposals. In addition, this document shall be signed by the winning bidder/consultant and incorporated as part of the contract.] 2Guidelines on Preventing and Combating Fraud and Corruption in Projects Financed by International Bank for Reconstruction and Development Loans and the International Development Agency Credits and Grants, dated October 15, 2006, and revised in January 2011 and July 2016, as they may be revised from time to time. We declare and warrant that we, along our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not), consultants and personnel, are not subject to, and are not controlled by any entity or individual that is subject to, a temporary suspension, early temporary suspension, or debarment imposed by a member of the World Bank Group, including, inter alia, a cross-debarment imposed by the World Bank Group as agreed with other international financial institutions (including multilateral development banks), or through the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement. Further, we are not ineligible under the laws or official regulations of [Insert name of Employer as per bidding document] or pursuant to a decision of the United Nations Security Council. We confirm our understanding of the consequences of not complying with the World Bank’s Anti-Corruption Guidelines, which may include the following: a. rejection of our Proposal/Bid for award of contract; b. in the case of award, termination of the contract, without prejudice to any other remedy for breach of contract; and c. sanctions, pursuant to the Bank’s Anti-Corruption Guidelines and in accordance with its prevailing sanctions policies and procedures as set forth in the Bank’s Sanctions Framework. This may include a public declaration of ineligibility, either indefinitely or for a stated period of time, (i) to be awarded or otherwise benefit from a Bank-financed contract, financially or in any other manner;3 (ii) to be a nominated4 sub-contractor, sub-consultant, consultant, manufacturer or supplier, or service provider of an otherwise eligible firm being awarded a Bank-financed contract; and (iii) to receive the proceeds of any loan made by the Bank or otherwise to participate further in the preparation or implementation of any Bank-financed project. We understand that we may be declared ineligible as set out above upon: a. completion of World Bank Group sanctions proceedings according to its prevailing sanctions procedures; b. cross-debarment as agreed with other international financial institutions (including multilateral development banks); 3For the avoidance of doubt, a sanctioned party’s ineligibility to be awarded a contract shall include, without limitation, (i) applying for pre-qualification or initial selection), expressing interest in a consultancy, and bidding, either directly or as a nominated sub- contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider, in respect of such contract, and (ii) entering into an addendum or amendment introducing a material modification to any existing contract. 4A nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider (different names are used depending on the bidding document) is one which has been: (i) included by the bidder in its pre-qualification or initial selection application or bid because it brings specific and critical experience and know- how that allow the bidder to meet the qualification requirements for the particular bid; or (ii) appointed by the Borrower. c. the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement; or d. temporary suspension or early temporary suspension in connection with an ongoing World Bank Group sanctions proceeding. For avoidance of doubt, the foregoing effects of ineligibility do not extend to a sanctioned firm’s or individual’s execution of its ongoing Bank-financed contracts (or its ongoing sub-agreements under such contracts) that are not the subject of a material modification, as determined by the Bank. We shall permit, and shall cause our sub-contractors, sub-consultants, agents (whether declared or not), personnel, consultants, service providers or suppliers, to permit the Bank to inspect5 all accounts, records, and other documents relating to the procurement process and/or contract execution (in the case of award), and to have them audited by auditors appointed by the Bank. We agree to preserve all accounts, records, and other documents (whether in hard copy or electronic format) related to the procurement and execution of the contract. Name of the Bidder/Proposer/Consultant: Name of the person duly authorized to sign the Bid/Proposal on behalf of the Bidder/Proposer/ Consultant: Title of the person signing the Letter: 5Inspections in this context are usually investigative (i.e., forensic) in nature: they involve fact-finding activities undertaken by the Bank or persons appointed by the Bank to address specific matters related to investigations/audits, such as evaluating the veracity of an allegation of possible Fraud and Corruption, through the appropriate mechanisms. Such activity includes but is not limited to accessing and examining a firm's or individual's financial records and information, and making copies thereof as relevant; accessing and examining any other documents, data, and information (whether in hard copy or electronic format) deemed relevant for the investigation/audit, and making copies thereof as relevant; interviewing staff and other relevant individuals; performing physical inspections and site visits; and obtaining third-party verification of information. PROCUREMENT Bhutan : Bhutan: COVID-19 Emergency Response and Health Systems Preparedness Project PLAN General Information Country: Bhutan 2020-05-18 Bank’s Approval Date of the Original Procurement Plan: 2023-06-05 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P173787 GPN Date: 2020-07-21 Project Name: Bhutan: COVID-19 Emergency Response and Health Systems Preparedness Project Loan / Credit No: IDA / 66270, IDA / 70980 Ministry of Health, RGoB Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned MOH-PPD/WB-WORKS/2020/ 01 / Civil and electrical works for the extension and modific Emergency COVID-19 Respo Request for Quota Single Stage - One E 2021-03-3 ation of loading/unloading ar IDA / 66270 Post Limited 24,200.00 22,380.86 Completed 2020-11-08 2020-11-20 2020-12-09 2020-12-03 nse tions nvelope 1 ea into Walk-in cooler room a nd construction of pre-casual ty unit at Mongar Regional R eferral Hospital. W1-RFQ-LIMITED / Office ref urbishment including electric Community Engagement an Request for Quota Single Stage - One E 2020-08-0 al works, partition, , working IDA / 66270 Post Limited 15,000.00 0.00 Canceled 2020-06-20 2020-07-12 d Risk Communication tions nvelope 9 table and chair, for the three consultants and officers depu ted from the MoH. MOH-PPD/WB-WORKS/2021/ Emergency COVID-19 Respo Other (with field f 2021-12-2 03 / Civil and electrical works IDA / 66270 Post Direct Selection Direct 70,000.00 54,277.19 Completed 2021-05-17 2021-06-08 2021-05-22 2021-06-09 2021-06-26 2021-06-12 nse or explanation) 3 for the construction of Flu Cli nic at Thimphu. MOH-PPD/WB-WORKS/2021/ 4 / Civil and electrical works f Request for Quota or the construction of semi-p Emergency COVID-19 Respo Request for Quota Single Stage - One E tions - Small Work 2022-03-1 IDA / 66270 Post Limited 40,000.00 0.00 Canceled 2021-07-17 2021-09-11 ermanent Structure for Covid nse tions nvelope s (Emergency) SP 0 -19 Screening at Eastern Reg D -Competitive ional Referral Hospital, Mong ar. MOH-PPD/WB-WORKS/2021/ Emergency COVID-19 Respo Request for Quota Single Stage - One E Other (with field f 2022-05-3 05 / Construction of the Retai IDA / 66270 Post Open - National 23,000.00 0.00 Canceled 2021-12-05 2022-01-30 nse tions nvelope or explanation) 0 ning wall for the MDR-TB war d at ERRH, Mongar MOH-PPD/WB-WORKS/2022/ 02 / Refurbishment of old hos Emergency COVID-19 Respo Request for Quota Single Stage - One E Other (with field f 2022-09-1 IDA / 66270 Post Open - National 33,400.00 0.00 Canceled 2022-01-19 2022-02-01 2022-03-21 pital structure at CRRH, Gele nse tions nvelope or explanation) 7 phu to convert as Flu Clinic. MOH-PPD/WB-WORKS/2022/ Emergency COVID-19 Respo Request for Quota Single Stage - One E Other (with field f 2022-09-0 01 / Construction of the Retai IDA / 66270 Post Limited 23,000.00 0.00 Canceled 2022-01-12 2022-03-09 nse tions nvelope or explanation) 5 ning wall for the MDR-TB war d at ERRH, Mongar. MOH-PPD/WB-WORKS/2022/ Emergency COVID-19 Respo Other (with field f 2022-09-0 03 / Construction of the Retai IDA / 66270 Post Direct Selection Direct 23,000.00 17,117.68 Completed 2022-01-28 2022-01-17 2022-02-02 2022-01-28 2022-03-09 2022-02-05 nse or explanation) 5 ning wall for the MDR-TB war d at ERRH, Mongar. MOH-PPD/WB-WORKS/2022/ Emergency COVID-19 Respo Other (with field f 2023-03-1 04 / Renovation of Flu Clinic IDA / 66270 Post Direct Selection Direct 34,700.00 24,552.18 Completed 2022-05-06 2022-04-16 2022-05-11 2022-04-22 2022-06-15 2022-04-30 nse or explanation) 2 at CRRH, Gelephu MOH-PPD/WB-WORKS/2020/ 02 / Civil and electrical works Emergency COVID-19 Respo Request for Quota Single Stage - One E 2021-12-2 IDA / 66270 Post Limited 28,000.00 0.00 Canceled 2021-05-06 2022-03-26 2021-07-01 for the construction of Dialysi nse tions nvelope 8 s unit at Wangdiphodrang Ho spital. National Procure MOH-PPD/WB-WORKS/2022/ ment Document - Emergency COVID-19 Respo Single Stage - One E 2023-11-1 06 / Construction of PSA oxy IDA / 70980 Post Request for Bids Open - National 1 Envelope proce 148,500.00 0.00 Canceled 2022-11-07 2022-11-17 2022-12-29 2023-01-28 2023-03-04 nse nvelope 4 gen shed at JDWNRH & ERRH ss (Non Bank-SPD . ) National Procure MOH-PPD/WB-WORKS/2022/ ment Document - Emergency COVID-19 Respo Single Stage - One E 2023-11-1 07 / Construction of PSA oxy IDA / 70980 Post Request for Bids Open - National 1 Envelope proce 64,535.00 0.00 Signed 2022-11-30 2022-09-01 2022-12-05 2023-01-16 2022-09-18 2023-02-15 2022-09-19 2023-03-22 nse nvelope 7 gen Plant at JDWNRH ss (Non Bank-SPD ) National Procure MOH-PPD/WB-WORKS/2022/ ment Document - Emergency COVID-19 Respo Single Stage - One E Pending Imp 2023-11-1 08 / Construction (Refurbish IDA / 70980 Post Request for Bids Open - National 1 Envelope proce 83,965.00 0.00 2022-11-30 2022-12-05 2023-01-16 2023-02-15 2023-03-22 nse nvelope lementation 7 ment) of PSA oxygen plant at ss (Non Bank-SPD ERRH ) Request for Quota MOH-PPD/WB-WORKS/2022/ Emergency COVID-19 Respo Request for Quota Single Stage - One E tions - Small Work 2023-02-0 09 / Modification of the prost IDA / 70980 Post Open - National 10,335.00 0.00 Completed 2022-12-05 2023-01-30 nse tions nvelope s (Emergency) SP 8 hodontic and orthodontic ser D -Competitive vices at MRRH National Procure MOH-PPD/WB-WORKS/2022/ ment Document - Emergency COVID-19 Respo Single Stage - One E 2023-10-1 11 / Construction of water tre IDA / 70980 Post Request for Bids Open - National 1 Envelope proce 61,390.00 0.00 Signed 2022-11-30 2022-11-23 2022-12-05 2023-01-16 2022-12-12 2023-02-15 2022-12-20 2023-03-22 nse nvelope 8 atment plant at ERRH ss (Non Bank-SPD ) MOH-PPD/WB-WORKS/2022/ Emergency COVID-19 Respo Request for Quota Single Stage - One E Other (with field f 2023-08-1 10 / Construction of Deep Bu IDA / 70980 Post Limited 8,340.00 0.00 Completed 2022-12-05 2022-12-06 2023-01-30 nse tions nvelope or explanation) 8 rial Pit at Gidakom Hospital MOH-PPD/WB-WORKS/2022/ 05 / Construction of Dialysis Emergency COVID-19 Respo Request for Quota Single Stage - One E Other (with field f 2023-11-0 unit and Re-modeling of exist IDA / 66270 Post Limited 47,000.00 0.00 Canceled 2023-01-05 2023-03-02 nse tions nvelope or explanation) 7 ing mortuary into histopathol ogy lab at Wangdiphodrang Hospital MOH-PPD/WB-WORKS/2022- Request for Quota 2023/12 / Construction of dia Emergency COVID-19 Respo Request for Quota Single Stage - One E tions - Small Work 2023-09-0 lysis unit and re-modelling of IDA / 66270 Post Open - National 47,000.00 0.00 Signed 2023-01-05 2023-03-13 nse tions nvelope s (Emergency) SP 9 existing mortuary into histop D -Competitive athology lab at Wandiphodra ng hospital. MOH-PPD/WB-WORKS/2022- Emergency COVID-19 Respo Request for Quota Single Stage - One E Other (with field f 2023-07-0 2023/13 / Maintenance (Civil IDA / 70980 Post Limited 14,350.00 0.00 Signed 2023-01-19 2023-01-09 2023-03-29 nse tions nvelope or explanation) 7 Works) of Phuntsholing Hosp ital Page 1 Request for Quota MOH-PPD/WB-WORKS/2022- Emergency COVID-19 Respo Request for Quota Single Stage - One E tions - Small Work Under Imple 2023-11-2 2023/14 / Construction of Flu IDA / 66270 Post Open - National 50,000.00 0.00 2023-02-05 2023-04-02 nse tions nvelope s (Emergency) SP mentation 8 Clinic at Samtse D -Competitive GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MOH/DMSHI/COVID-19/2020 Emergency COVID-19 Respo Request for Quota Single Stage - One E IDA / 66270 Post Open - National 10,000.00 10,589.51 Completed 2020-06-09 2020-08-04 2020-06-25 2021-01-31 2020-10-17 / ICU Beds nse tions nvelope MOH-PPD/WB-PROCUREMEN Implementation Managemen T/2020 / procurement of des Request for Quota Single Stage - One E IDA / 66270 t and Monitoring and Evaluat Post Limited 7,000.00 0.00 Canceled 2020-07-06 2020-08-31 2021-02-27 ktop, laptop and printers for tions nvelope ion project staff and project offic e. MOH-PPD/WB- PROCUREMEN T/2020/02 / Surgical N95 res pirator mask, good breathabi Emergency COVID-19 Respo IDA / 66270 Post Direct Selection Direct 500,000.00 459,684.00 Completed 2020-07-24 2020-06-21 2022-07-25 2020-07-13 2022-08-29 2020-07-17 2023-02-25 2020-11-24 lity with the design that does nse not collapse against mouth. No valve Quantity : 90,000 number. MSPD/COVID-19/2020/2230 / Supply of medicines: Emergency COVID-19 Respo Lopinavir + Ritonavir : Qty. ( IDA / 66270 Post Direct Selection Direct 14,000.00 13,641.88 Completed 2020-08-03 2020-01-30 2020-08-08 2020-01-30 2020-09-12 2020-03-28 2021-03-11 2020-04-14 nse 20010) Azithromycin: Qty. (1500) MSPD/COVID-19/2020/2128 / Emergency COVID-19 Respo IDA / 66270 Post Direct Selection Direct 11,000.00 10,648.00 Completed 2020-08-03 2020-01-30 2020-08-08 2020-01-30 2020-09-12 2020-03-18 2021-03-11 2020-04-22 Supply of medicines Qty. (50 nse 000) MOH/DMSHI/MSPD/NCORON Emergency COVID-19 Respo O/2020/2167 / Supply of face IDA / 66270 Post Direct Selection Direct 11,666.67 11,677.09 Completed 2020-08-03 2020-01-30 2020-08-08 2020-01-30 2020-09-12 2020-03-15 2021-03-11 2020-04-03 nse masks: Qty: (50000) MOH/DMSHI/MSPD/NCORON Emergency COVID-19 Respo O/2020/2087 / Supply of blan IDA / 66270 Post Direct Selection Direct 7,541.33 0.00 Canceled 2020-08-03 2020-01-30 2020-08-08 2020-01-30 2020-09-12 2021-03-11 nse kets and pillows: Qty. (334) MOH/DMSHI/MSPD/NCORON Emergency COVID-19 Respo O/2020/1953 / Supply of face IDA / 66270 Post Direct Selection Direct 58,500.00 58,931.03 Completed 2020-08-03 2020-01-30 2020-08-08 2020-01-30 2020-09-12 2020-02-20 2021-03-11 2020-03-11 nse mask. Qty. (150000) MOH/DMSHI/MSPD/NCORON O/2020/2093 / procurement Emergency COVID-19 Respo IDA / 66270 Post Direct Selection Direct 3,000.00 3,003.51 Completed 2020-08-03 2020-01-30 2020-08-08 2020-01-30 2020-09-12 2020-03-18 2021-03-11 2020-04-10 of Suction machine. nse Qty: (10) MSPD/COVID-19/2020/2229 / Emergency COVID-19 Respo Procurement of Azithromycin IDA / 66270 Post Direct Selection Direct 150.00 109.22 Completed 2020-08-03 2020-01-30 2020-08-08 2020-01-30 2020-09-12 2020-03-28 2021-03-11 2020-04-10 nse , 500mg. Qty:(500) MOH/COVID-19/2019-20/119 Emergency COVID-19 Respo 61 / Procurement of 1200 tes IDA / 66270 Post Direct Selection Direct 130,000.00 120,000.00 Completed 2020-08-03 2020-04-03 2020-08-08 2020-04-03 2020-09-12 2020-04-04 2021-03-11 2020-04-15 nse ts/pkts (10 packets ) MOH/DMSHI/MSPD/NCORON O/2020/2041 / Procurement Emergency COVID-19 Respo IDA / 66270 Post Direct Selection Direct 10,000.00 9,867.23 Completed 2020-08-03 2020-01-30 2020-08-08 2020-01-30 2020-09-12 2020-02-21 2021-03-11 2020-04-03 of GC-Alcohol based hand ru nse b of 150ml: Qty.(2450) MOH/DMSHI/MSPD/NCORON Emergency COVID-19 Respo O/2020/1951 / Supply of GC IDA / 66270 Post Direct Selection Direct 250,000.00 223,889.84 Completed 2020-08-03 2020-01-30 2020-08-08 2020-01-30 2020-09-12 2020-02-02 2021-03-11 2020-03-14 nse General Consumables) : Qty: (48800) MOH/DMSHI/MSPD/NCORON Emergency COVID-19 Respo O/2020/2145 / Procurement IDA / 66270 Post Direct Selection Direct 7,000.00 7,099.22 Completed 2020-08-03 2020-01-30 2020-08-08 2020-01-30 2020-09-12 2020-03-19 2021-03-11 2020-04-03 nse of Disinfectants (Qty: 1300) MOH/COVID-19/2019-20/121 Emergency COVID-19 Respo 96 / Procurement of masks N IDA / 66270 Post Direct Selection Direct 17,000.00 16,880.88 Completed 2020-08-03 2020-04-15 2020-08-08 2020-04-15 2020-09-12 2020-04-16 2021-03-11 2020-04-24 nse 95; approved by NIOSH. Qty ( 3,200) MOH/DMSHI/MSPD/NCORON O/2020/1896 / Procurement of GC & PPEs: 1.Supply of N95/ V410 : Qty. (1600) Emergency COVID-19 Respo IDA / 66270 Post Direct Selection Direct 290,000.00 288,226.84 Completed 2020-08-03 2020-01-30 2020-08-08 2020-01-30 2020-09-12 2020-01-31 2021-03-11 2020-03-27 2. Googles : Qty. (2000) nse 3. Plastic apron disposable: Qty.(2000) 4.Coverall size S: Qty.(7500) 5.Coverall size M: Qty.(7500) MOH/DMSHI/MSPD/NCORON O/2020/1950 / Procurement of GC: 1.oxygen flow meter and pul Emergency COVID-19 Respo IDA / 66270 Post Direct Selection Direct 26,000.00 19,424.41 Completed 2020-08-03 2020-01-30 2020-08-08 2020-01-30 2020-09-12 2020-01-31 2021-03-11 2020-04-03 se oximeter: Qty. (30 each) nse 2.Hydrogen Peroxide & glyce rin: Qty.(1350 and 940 each) 3. Hand rub & Gloves Qty. (1 050 and 69000 each) MOH/DMSHI/MSPD/NCORON Emergency COVID-19 Respo O/2020/2144 / Procurement IDA / 66270 Post Direct Selection Direct 90,000.00 145,118.91 Completed 2020-08-03 2020-01-30 2020-08-08 2020-01-30 2020-09-12 2020-03-19 2021-03-11 2020-03-31 nse of PPEs: coverall size L&M (Q ty: 5275) MOH/DMSHI/MSPD/NCORON Emergency COVID-19 Respo O/2020/2196 / Procurement IDA / 66270 Post Direct Selection Direct 4,500.00 4,647.26 Completed 2020-08-03 2020-01-30 2020-08-08 2020-03-07 2020-09-12 2020-03-08 2021-03-11 2020-04-03 nse of GE; bed rail. Qt:(23) MOH/DMSHI/MSPD/NCORON O/2020/2021 / Procurement Emergency COVID-19 Respo IDA / 66270 Post Direct Selection Direct 12,000.00 10,887.74 Completed 2020-08-03 2020-01-30 2020-08-08 2020-01-30 2020-09-12 2020-03-09 2021-03-11 2020-04-07 of PPEs and GC; (glycerine). nse Qty: (2900) Page 2 MOH/DMSHI/MSPD/NCORON Emergency COVID-19 Respo O/2020/2224 / Procurement IDA / 66270 Post Direct Selection Direct 7,800.00 7,618.01 Completed 2020-08-03 2020-01-30 2020-08-08 2020-01-30 2020-09-12 2020-03-26 2021-03-11 2020-04-08 nse of oxygen concentrator Qty. ( 12) MOH/DMSHI/MSPD/NCORON O/2020/2211 / Procurement of PPEs and Consumables; (s Emergency COVID-19 Respo IDA / 66270 Post Direct Selection Direct 25,000.00 24,646.91 Completed 2020-08-03 2020-01-30 2020-08-08 2020-01-30 2020-09-12 2020-03-15 2021-03-11 2020-04-14 urgical gowns disposable nse Size: L & M) Quantity: (24071) MOH/DMSHI/MSPD/NCORON Emergency COVID-19 Respo A/2020/2087 / Procurement o IDA / 66270 Post Direct Selection Direct 7,541.33 7,722.58 Completed 2020-09-06 2020-01-30 2020-09-11 2020-03-14 2020-10-16 2020-03-15 2021-04-14 2020-04-03 nse f equipments (blankets and p illow) MOH-PPD/WB-PROCUREMEN Implementation Managemen T/2020/1 / Procurement of La IDA / 66270 t and Monitoring and Evaluat Post Direct Selection Direct 4,000.00 3,599.05 Completed 2020-10-11 2020-08-06 2020-10-16 2020-08-07 2020-11-20 2020-10-06 2021-05-19 2020-12-16 ptops for PMU staffs ion Qty: 3 MOH/DMSHI/MSPD/COVID-19 /2020/2057 / Procurement of Emergency COVID-19 Respo Request for Quota Single Stage - One E IDA / 66270 Post Open - National 100,600.00 0.00 Canceled 2020-11-05 2020-12-31 2021-06-29 equipments & consumables- nse tions nvelope Portable Ventilators, Astral 1 50 (QTY: 13) MOH/DMSHI/MSPD/NCORON Emergency COVID-19 Respo Request for Quota Single Stage - One E A/2020/2097 / Procurement o IDA / 66270 Post Open - National 145,000.00 0.00 Canceled 2020-11-05 2020-12-31 2021-06-29 nse tions nvelope f PPEs: Surgical Face Mask (Q TY: 598,700) MOH/DMSHI/MSPD/COVID-19 /2020/2433 / supply of PPEs Emergency COVID-19 Respo Request for Quota Single Stage - One E & consumables IDA / 66270 Post Open - National 93,000.00 0.00 Canceled 2020-11-05 2020-12-31 2021-06-29 nse tions nvelope -Surgical Face Mask (QTY: 30 0,000 nos) MOH/DMSHI/MSPD/COVID-19 /2020/2458 / Supply of Consu Emergency COVID-19 Respo Request for Quota Single Stage - One E IDA / 66270 Post Open - National 30.00 0.00 Canceled 2020-11-05 2020-12-31 2021-06-29 mables nse tions nvelope -Breathing circuit, Anesthesia , adult 22 mm (QTY: 5 sets) MOH/DMSHI/MSPD/COVID-19 /2020/2143 / Supply of PPEs Emergency COVID-19 Respo Request for Quota Single Stage - One E IDA / 66270 Post Open - National 200.00 0.00 Canceled 2020-11-05 2020-12-31 2021-06-29 -Operation cap, size medium nse tions nvelope (50cm) (QTY: 14,000 nos) MOH/DMSHI/MSPD/COVID-19 /2020/2446 / Supply of PPEs Emergency COVID-19 Respo Request for Quota Single Stage - One E IDA / 66270 Post Open - National 1,500.00 0.00 Canceled 2020-11-05 2020-12-31 2021-06-29 -surgical cap, non woven, dis nse tions nvelope posable (QTY:126,900) MOH/DMSHI/MSPD/COVID-19 /2020/2500 / Supply of consu Emergency COVID-19 Respo Request for Quota Single Stage - One E IDA / 66270 Post Open - National 6,000.00 0.00 Canceled 2020-11-05 2020-12-31 2021-06-29 mables nse tions nvelope -Disposable gloves , Size M & L (QTY: 100,000) MOH/DMSHI/MSPD/COVID-19 Emergency COVID-19 Respo Request for Quota Single Stage - One E /2020/2418 / Supply of Equip IDA / 66270 Post Open - National 5,000.00 0.00 Canceled 2020-11-05 2020-12-31 2021-06-29 nse tions nvelope ment-Foam mattress (QTY: 1 28) MOH/DMSHI/MSPD/COVID-19 /2020/2144 / Supply of PPEs & consumables Emergency COVID-19 Respo Request for Quota Single Stage - One E -Coverall size S, White tyvek IDA / 66270 Post Open - National 150,000.00 0.00 Canceled 2020-11-05 2020-12-31 2021-06-29 nse tions nvelope (QTY: 4300) -Coverall size M, White Tyve k (QTY: 4300) MOH/DMSHI/MSPD/COVID-19 /2020/2194 / Supply of GC & Consumables-Oxygen Cylind Emergency COVID-19 Respo Request for Quota Single Stage - One E er D type (QTY: 100 nos) IDA / 66270 Post Open - National 23,000.00 0.00 Canceled 2020-11-05 2020-12-31 2021-06-29 nse tions nvelope Supply of GC & Consumables -Oxygen Stand B type (QTY: 10 nos) MOH/DMSHI/MSPD/COVID-19 /2020/2092 / Supply of Equip Emergency COVID-19 Respo Request for Quota Single Stage - One E IDA / 66270 Post Open - National 26,000.00 0.00 Canceled 2020-11-05 2020-12-31 2021-06-29 ment nse tions nvelope -Defibrillator(Pediatric paddle ) (QTY: 4) MOH/DMSHI/MSPD/COVID-19 Emergency COVID-19 Respo Request for Quota Single Stage - One E /2020/2191 / Supply of Equip IDA / 66270 Post Open - National 24,000.00 0.00 Canceled 2020-11-05 2020-12-31 2021-06-29 nse tions nvelope ment-Reverse Osmosis syste m (QTY: 1) MSDD/MED.GAS/2019-2020/ 2065 / Filled Medical Oxygen Gas cylinders (QTY: 99 ) Emergency COVID-19 Respo IDA / 66270 Post Direct Selection Direct 170.00 154.22 Completed 2020-10-31 2020-05-27 2020-11-05 2020-05-27 2020-12-10 2020-05-28 2021-06-08 2020-06-16 [ Empty oxygen 'B' Type- 80 nse nos and Empty Oxygen 'D' ty pe- 19 nos ] MSDD/MED.GAS/2019-2020/ 2072 / Filled Medical Oxygen Emergency COVID-19 Respo IDA / 66270 Post Direct Selection Direct 260.00 262.83 Completed 2020-10-31 2020-05-28 2020-11-05 2020-05-28 2020-12-10 2020-05-29 2021-06-08 2020-06-16 Gas cylinders [Empty Oxygen nse 'B' type] (QTY: 193) MSDD/MED.GAS/2019-2020/ 2105 / Filled Medical Oxygen Emergency COVID-19 Respo IDA / 66270 Post Direct Selection Direct 120.00 106.22 Completed 2020-10-31 2020-05-29 2020-11-05 2020-05-29 2020-12-10 2020-05-30 2021-06-08 2020-06-16 Gas cylinders[ Empty Oxygen nse 'B' type] (QTY: 78 nos) MSDD/MED.GAS/2019-2020/ 2047 / Filled Medical Oxygen Emergency COVID-19 Respo Gas cylinders (QTY: 600 ) IDA / 66270 Post Direct Selection Direct 1,500.00 1,429.88 Completed 2020-10-31 2020-05-22 2020-11-05 2020-05-22 2020-12-10 2020-05-23 2021-06-08 2020-06-16 nse [ Empty Oxygen 'D' type-300 nos & purging ang blowing-3 00 nos] MSDD/MED.GAS/2019-2020/ 2104 / Filled Medical Oxygen Emergency COVID-19 Respo Gas cylinders (QTY: 89) IDA / 66270 Post Direct Selection Direct 170.00 156.95 Completed 2020-10-31 2020-06-01 2020-11-05 2020-06-01 2020-12-10 2020-06-02 2021-06-08 2020-06-16 nse [Empty Oxygen 'B' type-54 n os & Empty Oxygen 'D' type- 35 nos] Page 3 MSDD/MED.GAS/2019-2020/ 2103 / Filled Medical Oxygen Emergency COVID-19 Respo IDA / 66270 Post Direct Selection Direct 160.00 142.99 Completed 2020-10-31 2020-06-02 2020-11-05 2020-06-02 2020-12-10 2020-06-03 2021-06-08 2020-06-16 Gas cylinders [ Empty Oxyge nse n 'D' type] (QTY: 60 ) MSDD/MED.GAS/2019-2020/ 2111 / Filled Medical Oxygen Gas cylinders (QTY: 136 nos) Emergency COVID-19 Respo IDA / 66270 Post Direct Selection Direct 300.00 250.57 Completed 2020-10-31 2020-06-03 2020-11-05 2020-06-03 2020-12-10 2020-06-04 2021-06-08 2020-06-16 [ Empty Oxygen 'B' type- 72 nse nos & Empty Oxygen 'D' type - 64 nos ] MOH/DMSHI/MSPD/COVID-19 Emergency COVID-19 Respo Request for Quota Single Stage - One E /2020/2170 / Supply of Equip IDA / 66270 Post Open - National 1,000.00 0.00 Canceled 2020-11-05 2020-12-31 2021-06-29 nse tions nvelope ment- Trolley (QTY) : 3 sets MOH/DMSHI/MSPD/COVID-19 Emergency COVID-19 Respo Request for Quota Single Stage - One E /2020/2055 / Supply of Equip IDA / 66270 Post Open - National 1,000.00 0.00 Canceled 2020-11-05 2020-12-31 2021-06-29 nse tions nvelope ment -Semi fowler's bed (QT Y: 8 nos) MOH/DMSHI/MSPD/NCORON A/2020/2086 / Procurement o f Equipments: Emergency COVID-19 Respo Request for Quota Single Stage - One E 1. Arterial Blood Gas unit (QT IDA / 66270 Post Open - National 64,000.00 0.00 Canceled 2020-11-05 2020-12-31 2021-06-29 nse tions nvelope Y: 6 nos) 2. Infusion Pump (QTY: 15 no s) 3. Bed ICU (QTY: 18 nos) MOH/DMSHI/MSPD/NCORON Emergency COVID-19 Respo Request for Quota Single Stage - One E O/2020/2078 / Supply of PPE IDA / 66270 Post Open - National 1,400.00 0.00 Canceled 2020-11-05 2020-12-31 2021-06-29 nse tions nvelope s and GC-Glycerin (QTY: 115 0 nos) BT-MOH-173319-GO-RFQ / S Emergency COVID-19 Respo Request for Quota Single Stage - One E IDA / 66270 Post Limited 44,836.90 0.00 Canceled 2020-05-22 2020-06-09 2020-08-08 upply of PPEs for COVID-19 nse tions nvelope MOH/DMSHI/MSPD/NCORON Emergency COVID-19 Respo Request for Quota Single Stage - One E A/2020/2076 / Supply of Equi IDA / 66270 Post Open - National 61,500.00 0.00 Canceled 2020-11-05 2020-12-31 2021-06-29 nse tions nvelope pment-Infrared Thermometer (QTY: 95) MOH/DMSHI/MSPD/COVID-19 /2020/2174 / Supply of Equip Emergency COVID-19 Respo Request for Quota Single Stage - One E IDA / 66270 Post Open - National 1,200.00 0.00 Canceled 2020-11-05 2020-12-31 2021-06-29 ment & Consumable: nse tions nvelope -Electrocardiograph (QTY: 1) MOH/DMSHI/MSPD/NCORON Emergency COVID-19 Respo Request for Quota Single Stage - One E A/2020/2059 / Supply of Equi IDA / 66270 Post Open - National 4,800.00 0.00 Canceled 2020-11-05 2020-12-31 2021-06-29 nse tions nvelope pment: -Infusion Pump (QTY: 13 sets ) MOH/DMSHI/MSPD/COVID-19 Emergency COVID-19 Respo Request for Quota Single Stage - One E /2020/2190 / Supply of Equip IDA / 66270 Post Open - National 11,500.00 0.00 Canceled 2020-11-05 2020-12-31 2021-06-29 nse tions nvelope ment: -Cartridge (test card) (QTY: 3 0) MOH/DMSHI/MSPD/COVID-19 /2020/2077 / Procurement of Emergency COVID-19 Respo Request for Quota Single Stage - One E PPEs and GC: IDA / 66270 Post Open - National 1,600.00 0.00 Canceled 2020-11-05 2020-12-31 2021-06-29 nse tions nvelope - Glutaraldehyde, 5 ltr (QTY: 305 nos.) MOH/DMSHI/MSPD/COVID-19 /2020/2140 / Supply of PPEs -Clean gloves /non sterile m Emergency COVID-19 Respo Request for Quota Single Stage - One E IDA / 66270 Post Open - National 49,500.00 0.00 Canceled 2020-11-05 2020-12-31 2021-06-29 edium (QTY: 216,000) nse tions nvelope -Clean gloves/ non sterile lar ge (QTY: 90,000) MOH/DMSHI/MSPD/NCORON O/2020/2895 / Supply of Equi pment & GC: Emergency COVID-19 Respo Request for Quota Single Stage - One E IDA / 66270 Post Open - National 4,000.00 0.00 Canceled 2020-11-05 2020-12-31 2021-06-29 - Mattress Foam with waterpr nse tions nvelope oof synthetic cover, Size 78* 37*4" (QTY: 94 ) MOH/DMSHI/MSPD/COVID-19 /2020/2453 / Supply of PPEs & Consumables Emergency COVID-19 Respo Request for Quota Single Stage - One E -Coverall size L, white Tyvek IDA / 66270 Post Open - National 660,000.00 0.00 Canceled 2020-11-05 2020-12-31 2021-06-29 nse tions nvelope (QTY: 3600) -Coverall size M, White Tyve k (QTY: 3600) MOH/DMSHI/MSPD/COVID-19 /2020/2216 / Supply of Equip Emergency COVID-19 Respo Request for Quota Single Stage - One E IDA / 66270 Post Open - National 54,000.00 0.00 Canceled 2020-11-05 2020-12-31 2021-06-29 ment -Infrared Thermometer, nse tions nvelope Digital, Forehead (sensor) Ba ttery (QTY: 400) 13(02)DMS/HCDD/MSQU/201 9-2020/2910 / Procurement o Emergency COVID-19 Respo f reagents and consumables IDA / 66270 Post Direct Selection Direct 94,200.00 88,366.13 Completed 2021-01-14 2020-11-21 2021-01-19 2020-12-01 2021-02-23 2021-01-09 2021-08-22 2021-12-07 nse for Biochemistry and Haemat ology analyzers. (QTY: 1416 nos.) MOH-PPD/WB-PROCUREMEN Emergency COVID-19 Respo Request for Quota Single Stage - One E T/2020/03 / Ultra Refrigerator IDA / 66270 Post Limited 25,000.00 0.00 Canceled 2021-03-05 2021-04-30 2021-10-27 nse tions nvelope -70, 900 litres (QTY:2) MOH-PPD/WB-PROCUREMEN T/2020/04 / Auto- Disable Syr Emergency COVID-19 Respo Request for Quota Single Stage - One E IDA / 66270 Post Limited 1,000.00 0.00 Canceled 2021-03-05 2021-04-30 2021-10-27 inges, 0.3 ML or 1 ML Needle nse tions nvelope with 23 Gauge (QTY:22000) MOH-PPD/WB-PROCUREMEN Emergency COVID-19 Respo Request for Quota Single Stage - One E T/2020/05 / AD syringes, 2 Ml IDA / 66270 Post Limited 1,000.00 0.00 Canceled 2021-03-05 2021-04-30 2021-10-27 nse tions nvelope with 21 gauge needle (QTY: 22,000) MOH-PPD/WB-PROCUREMEN T/2020/06 / Diluent, 0.9% so Emergency COVID-19 Respo Request for Quota Single Stage - One E IDA / 66270 Post Limited 25,000.00 0.00 Canceled 2021-03-05 2021-04-30 2021-10-27 dium chloride solution for inj nse tions nvelope ection 2ml USP( QTY: 22,000) MOH-PPD/WB-PROCUREMEN Emergency COVID-19 Respo Request for Quota Single Stage - One E T/2020/07 / Adrenaline 1mg/ IDA / 66270 Post Limited 500.00 0.00 Canceled 2021-03-05 2021-04-30 2021-10-27 nse tions nvelope m Injection(1ml) (QTY:4000) Page 4 MOH-PPD/WB-PROCUREMEN Emergency COVID-19 Respo Request for Quota Single Stage - One E T/2020/08 / Hydrocortisone 1 IDA / 66270 Post Limited 1,800.00 0.00 Canceled 2021-03-05 2021-04-30 2021-10-27 nse tions nvelope 00mg/ml Injection(2ml) (QTY: 4000) MOH-PPD/WB-PROCUREMEN Emergency COVID-19 Respo Request for Quota Single Stage - One E T/2020/09 / Promethazine 25 IDA / 66270 Post Limited 500.00 0.00 Canceled 2021-03-05 2021-04-30 2021-10-27 nse tions nvelope mg/ml Injection(2ml) (QTY:40 00) MOH-PPD/WB-PROCUREMEN T/2020/10 / "0.5 ML AD syrin Emergency COVID-19 Respo Request for Quota Single Stage - One E IDA / 66270 Post Limited 50,000.00 0.00 Canceled 2021-03-05 2021-04-30 2021-10-27 ges (with 23x1” Gauze needl nse tions nvelope e size) (0.6x25mm)" (QTY:919,800) MOH-PPD/WB-PROCUREMEN T/2020/11 / Biohazard Safety Emergency COVID-19 Respo Request for Quota Single Stage - One E IDA / 66270 Post Limited 6,000.00 0.00 Canceled 2021-03-05 2021-04-30 2021-10-27 Box 5 litres, WHO/PSO/E-10/S nse tions nvelope B01.1 Code PQS E10/04 9QT Y: 9,200) RBC/HEALTH/09/2020-21/64 2 / procurement of: 1. Hydrocortisone 100mg/ml Emergency COVID-19 Respo IDA / 66270 Post Direct Selection Direct 1,500.00 0.00 Canceled 2021-03-07 2020-11-21 2021-03-12 2020-11-25 2021-04-16 2021-10-13 injection(2ml)- (QTY:4000) nse 2. Promethazine 25mg/ml Inj ection ( 2ml)- (QTY-4000) MOH/DMSHI/MSPD/VPDP PR OGRAM/2021/1342 / Procure Emergency COVID-19 Respo ment of consumables- Auto IDA / 66270 Post Direct Selection Direct 5,000.00 0.00 Canceled 2021-03-07 2021-03-12 2021-04-16 2021-10-13 nse Disable syringes, 0.3 ML or 1 ML Needle with 23 gauge (QT Y:110,000). MOH/DMSHI/MSPD/VPDP PR OGRAM/2021/1316 / Procure Emergency COVID-19 Respo IDA / 66270 Post Direct Selection Direct 23,000.00 22,709.67 Completed 2021-02-26 2020-11-21 2021-03-03 2021-01-22 2021-03-16 2021-02-16 2021-03-30 2021-06-23 ment of Equipment; Ultra Ref nse rigerator, -70 degree Celcius, 900 liters (QTY-2) RBC/HEALTH/09/2020-21/64 Emergency COVID-19 Respo Request for Quota Single Stage - One E 1 / Procurement of Adrenalin IDA / 66270 Post Limited 400.00 0.00 Canceled 2021-03-05 2021-04-12 2021-05-18 nse tions nvelope e 1mg/ml Injection(1ml) (QTY :4000) MOH/DMSHI/MSPD/VPDP PR OGRAM/2021/1317 / Procure Emergency COVID-19 Respo Request for Quota Single Stage - One E ment of Biohazard Safety Bo IDA / 66270 Post Limited 6,000.00 0.00 Canceled 2021-03-05 2021-04-23 2021-05-26 nse tions nvelope x 5 litres, WHO/PSO/E-10/SB0 1.1 Code PQS E10/04 (QTY:9 200) BT-MOH-225373-GO-DIR / Pr Emergency COVID-19 Respo ocurement of 0.5ml AD Syrin IDA / 66270 Post Direct Selection Direct 15,000.00 0.00 Canceled 2021-03-22 2021-03-23 2021-04-28 2021-10-25 nse ges (23GX1") QTY:363,600 R1-MOH/DMSHI/MSPD/COVID Emergency COVID-19 Respo Request for Quota Single Stage - One E -19/2020/2055 / Supply of Eq IDA / 66270 Post Limited 1,000.00 992.03 Completed 2021-04-16 2020-03-09 2021-06-11 2020-03-20 2021-12-08 2020-06-23 nse tions nvelope uipment -Semi fowler's bed ( QTY: 8 nos) R2-MOH/DMSHI/MSPD/COVID -19/2020/2077 / Procurement Emergency COVID-19 Respo Request for Quota Single Stage - One E IDA / 66270 Post Limited 1,600.00 1,622.19 Completed 2021-04-16 2020-03-09 2021-06-11 2020-03-14 2021-12-08 2020-06-11 of PPEs and General Consum nse tions nvelope able: - Glutaraldehyde, 5 ltr ( QTY: 305 nos.) R3-MOH/DMSHI/MSPD/NCOR Emergency COVID-19 Respo Request for Quota Single Stage - One E ONA/2020/2059 / Supply of E IDA / 66270 Post Limited 4,800.00 4,760.74 Completed 2021-04-16 2020-03-09 2021-06-11 2020-03-20 2021-12-08 2020-06-11 nse tions nvelope quipment: -Infusion Pump (Q TY: 13 sets) R4-MOH/DMSHI/MSPD/COVID -19/2020/2140 / Supply of PP Es Emergency COVID-19 Respo Request for Quota Single Stage - One E IDA / 66270 Post Limited 49,500.00 20,713.32 Completed 2021-04-16 2020-03-09 2021-06-11 2020-03-19 2021-12-08 2020-06-23 -Clean gloves /non sterile me nse tions nvelope dium (QTY: 216,000) -Clean gloves/ non sterile lar ge (QTY: 90,000) R5-MOH/DMSHI/MSPD/NCOR ONO/2020/2895 / Supply of E Emergency COVID-19 Respo Request for Quota Single Stage - One E quipment & GC: - Mattress Fo IDA / 66270 Post Limited 4,000.00 3,596.16 Completed 2021-04-16 2020-03-09 2021-06-11 2020-03-15 2021-12-08 2020-06-11 nse tions nvelope am with waterproof synthetic cover, Size 78*37*4" (QTY: 9 4) R6-MOH/DMSHI/MSPD/COVID -19/2020/2216 / Supply of Eq Emergency COVID-19 Respo Request for Quota Single Stage - One E IDA / 66270 Post Limited 54,000.00 21,825.12 Completed 2021-04-16 2020-03-09 2021-06-11 2020-03-26 2021-12-08 2020-06-11 uipment -Infrared Thermome nse tions nvelope ter, Digital, Forehead (sensor ) Battery (QTY: 400) R7-MOH/DMSHI/MSPD/NCOR Emergency COVID-19 Respo Request for Quota Single Stage - One E ONA/2020/2076 / Supply of E IDA / 66270 Post Limited 61,500.00 2,958.08 Completed 2021-04-16 2020-03-09 2021-06-11 2020-03-14 2021-12-08 2020-06-23 nse tions nvelope quipment-Infrared Thermom eter (QTY: 95) R8-MOH/DMSHI/MSPD/COVID Emergency COVID-19 Respo Request for Quota Single Stage - One E -19/2020/2190 / Supply of Eq IDA / 66270 Post Limited 11,500.00 0.00 Canceled 2021-04-16 2021-06-11 2021-12-08 nse tions nvelope uipment: -Cartridge (test car d) (QTY: 30) R9-MOH/DMSHI/MSPD/COVID -19/2020/2174 / Supply of Eq Emergency COVID-19 Respo Request for Quota Single Stage - One E IDA / 66270 Post Limited 1,200.00 1,116.69 Completed 2021-04-16 2020-03-09 2021-06-11 2020-03-21 2021-12-08 2020-06-25 uipment & Consumable: -Ele nse tions nvelope ctrocardiograph (QTY: 1) R10-MOH/DMSHI/MSPD/COVI D-19/2020/2453 / Supply of P PEs & Consumables: Emergency COVID-19 Respo Request for Quota Single Stage - One E -Coverall size L, white Tyvek IDA / 66270 Post Limited 660,000.00 120,964.78 Completed 2021-04-16 2020-03-09 2021-06-11 2020-04-21 2021-12-08 2020-06-11 nse tions nvelope (QTY: 3600) -Coverall size M, White Tyvek (QTY: 3600) R11-MOH/DMSHI/MSPD/COVI D-19/2020/2446 / Supply of P Emergency COVID-19 Respo Request for Quota Single Stage - One E IDA / 66270 Post Limited 1,500.00 1,504.66 Completed 2021-04-16 2020-03-09 2021-06-11 2020-04-21 2021-12-08 2020-06-27 PEs -surgical cap, non woven nse tions nvelope , disposable (QTY:126,900) R12-MOH/DMSHI/MSPD/NCO RONA/2020/2086 / Procurem ent of Equipment: Emergency COVID-19 Respo Request for Quota Single Stage - One E 1. Arterial Blood Gas unit (QT IDA / 66270 Post Limited 64,000.00 64,064.63 Completed 2021-04-16 2020-03-09 2021-06-11 2020-03-15 2021-12-08 2020-06-11 nse tions nvelope Y: 6 nos) 2. Infusion Pump (QTY: 15 no s) 3. Bed ICU (QTY: 18 nos) Page 5 R13-MOH/DMSHI/MSPD/NCO Emergency COVID-19 Respo Request for Quota Single Stage - One E RONO/2020/2078 / Supply of IDA / 66270 Post Limited 1,400.00 1,409.49 Completed 2021-04-16 2020-03-09 2021-06-11 2020-03-14 2021-12-08 2020-06-11 nse tions nvelope PPEs and GC-Glycerin (QTY: 1 150 nos) R14-MOH/DMSHI/MSPD/NCO Emergency COVID-19 Respo Request for Quota Single Stage - One E RONA/2020/2097 / Procurem IDA / 66270 Post Limited 145,000.00 143,973.11 Completed 2021-04-16 2020-03-09 2021-06-11 2020-03-17 2021-12-08 2020-06-11 nse tions nvelope ent of PPEs: Surgical Face Ma sk (QTY: 598,700) R15-MOH/DMSHI/MSPD/COVI D-19/2020/2144 / Supply of P PEs & consumables: Emergency COVID-19 Respo Request for Quota Single Stage - One E -Coverall size S, White tyvek IDA / 66270 Post Limited 150,000.00 70,727.29 Completed 2021-04-16 2020-03-09 2021-06-11 2020-03-19 2021-12-08 2020-06-11 nse tions nvelope (QTY: 4300) -Coverall size M, White Tyvek (QTY: 4300) R16-MOH/DMSHI/MSPD/COVI D-19/2020/2194 / Supply of GC & Consumables: Emergency COVID-19 Respo Request for Quota Single Stage - One E -Oxygen Cylinder D type (QT IDA / 66270 Post Limited 23,000.00 22,837.64 Completed 2021-04-16 2020-03-20 2021-06-11 2020-03-24 2021-12-08 2020-06-11 nse tions nvelope Y: 100 nos) -Oxygen Stand B type (QTY: 10 nos) R17-MOH/DMSHI/MSPD/COVI Emergency COVID-19 Respo D-19/2020/2170 / Supply of E IDA / 66270 Post Direct Selection Direct 1,000.00 956.24 Completed 2021-04-11 2020-03-17 2021-04-16 2020-03-20 2021-05-21 2020-03-21 2021-11-17 2020-06-23 nse quipment- Trolley (QTY) : 3 s ets R18-MOH/DMSHI/MSPD/COVI D-19/2020/2092 / Supply of E Emergency COVID-19 Respo Request for Quota Single Stage - One E IDA / 66270 Post Open - National 26,000.00 26,456.83 Completed 2021-04-16 2021-06-11 2020-03-15 2021-12-08 2020-06-23 quipment -Defibrillator(Pedia nse tions nvelope tric paddle) (QTY: 4) R19-MOH/DMSHI/MSPD/COVI Emergency COVID-19 Respo Request for Quota Single Stage - One E D-19/2020/2191 / Supply of E IDA / 66270 Post Limited 24,000.00 0.00 Canceled 2021-04-16 2021-06-11 2021-12-08 nse tions nvelope quipment-Reverse Osmosis s ystem (QTY: 1) R20-MOH/DMSHI/MSPD/COVI D-19/2020/2143 / Supply of P Emergency COVID-19 Respo Request for Quota Single Stage - One E IDA / 66270 Post Limited 200.00 162.06 Completed 2021-04-16 2020-03-09 2021-06-11 2020-03-19 2021-12-08 2020-06-23 PEs -Operation cap, size med nse tions nvelope ium (50cm) (QTY: 14,000 nos ) R21-MOH/DMSHI/MSPD/COVI D-19/2020/2458 / Supply of C Emergency COVID-19 Respo IDA / 66270 Post Direct Selection Direct 30.00 28.00 Completed 2021-04-11 2020-04-15 2021-04-16 2020-04-15 2021-05-21 2020-04-18 2021-11-17 2020-06-25 onsumables -Breathing circui nse t, Anesthesia, adult 22 mm ( QTY: 5 sets) R22-MOH/DMSHI/MSPD/COVI D-19/2020/2433 / supply of P Emergency COVID-19 Respo Request for Quota Single Stage - One E IDA / 66270 Post Limited 93,000.00 93,448.43 Completed 2021-04-16 2020-03-09 2021-06-11 2020-04-22 2021-12-08 2020-06-11 PEs & consumables -Surgical nse tions nvelope Face Mask (QTY: 300,000 nos ) R23-MOH/DMSHI/MSPD/COVI D-19/2020/2500 / Supply of c Emergency COVID-19 Respo Request for Quota Single Stage - One E IDA / 66270 Post Limited 6,000.00 5,940.76 Completed 2021-04-16 2020-03-09 2021-06-11 2020-04-26 2021-12-08 2020-06-23 onsumables -Disposable glov nse tions nvelope es , Size M & L (QTY: 100,000 ) R24-MOH/DMSHI/MSPD/COVI D-19/2020/2057 / Procureme Emergency COVID-19 Respo Request for Quota Single Stage - One E IDA / 66270 Post Limited 100,600.00 100,732.82 Completed 2021-04-16 2020-03-09 2021-06-11 2020-03-20 2021-12-08 2020-06-12 nt of equipment & consumab nse tions nvelope les-Portable Ventilators, Astr al 150 (QTY: 13) R25-MOH/DMSHI/MSPD/COVI Emergency COVID-19 Respo Request for Quota Single Stage - One E D-19/2020/2418 / Supply of E IDA / 66270 Post Limited 5,000.00 4,903.40 Completed 2021-04-16 2020-03-09 2021-06-11 2020-04-18 2021-12-08 2020-06-25 nse tions nvelope quipment-Foam mattress (QT Y: 128) DMSHI/MSPD/VACCINATION/ Emergency COVID-19 Respo Request for Quota Single Stage - One E 2020-21 / Procurement of 0.5 IDA / 66270 Post Limited 20,000.00 0.00 Canceled 2021-04-06 2021-06-01 2021-11-28 nse tions nvelope ml AD Syringes (23GX1") QT Y:363,600 R1-DMSHI/MSPD/VACCINATI Emergency COVID-19 Respo ON/2020-21 / Procurement of IDA / 66270 Post Direct Selection Direct 20,000.00 17,599.23 Completed 2021-04-25 2021-03-19 2021-04-30 2021-04-06 2021-06-04 2021-04-21 2021-12-01 2021-06-23 nse 0.5ml AD Syringes (23GX1") QTY:363,600 R-MOH/DMSHI/MSPD/COVID- Emergency COVID-19 Respo 19/2020/2190 / Supply of Eq IDA / 66270 Post Direct Selection Direct 11,500.00 11,654.11 Completed 2021-05-27 2020-03-17 2021-06-01 2020-03-20 2021-07-06 2020-03-24 2022-01-02 2020-06-11 nse uipment: -Cartridge (test car d) (QTY: 30) R-MOH/DMSHI/MSPD/COVID- Emergency COVID-19 Respo 19/2020/2191 / Supply of Eq IDA / 66270 Post Direct Selection Direct 24,000.00 23,672.20 Completed 2021-05-27 2020-03-17 2021-06-01 2020-03-20 2021-07-06 2020-03-24 2022-01-02 2020-06-23 nse uipment-Reverse Osmosis sy stem (QTY: 1) MOH-PPD/WB-PROCUREMEN T/2021/01 / Procurement of P Emergency COVID-19 Respo aracetamol (PCM) tablets for IDA / 66270 Post Direct Selection Direct 21,000.00 5,225.05 Completed 2021-07-16 2021-07-12 2021-07-21 2021-07-13 2021-08-25 2021-07-21 2022-02-21 2021-11-20 nse the 2nd dose COVID-19 vacci nation campaign. (QTY:996,776 tabs) MOH-PPD/WB-PROCUREMEN T/2021/02 / Procurement of: 1. A.D Syringes 0.3ml w/need Emergency COVID-19 Respo IDA / 66270 Post Direct Selection Direct 47,000.00 45,377.28 Completed 2021-08-04 2021-07-23 2021-08-09 2021-07-23 2021-09-13 2021-08-03 2022-03-12 2021-08-27 le/Box-100 (Qty. 2,200 boxes nse syringes) 2. Syringes reconstitute 2ml( Qty: 450 Boxes(45,000 Nos.)) MOH-PPD/WB-PROCUREMEN T/2021/03 / Procurement of Emergency COVID-19 Respo IDA / 66270 Post Direct Selection Direct 5,000.00 4,704.97 Completed 2021-08-15 2021-08-09 2021-08-20 2021-08-09 2021-09-24 2021-08-14 2022-03-23 2021-11-23 Diluents 0.9% Sodium Chlori nse de, 2ml USP/IPS in bottle (Qt y: 100,000 vials) MOH-PPD/WB-PROCUREMEN Emergency COVID-19 Respo T/2021/04 / Procurement of IDA / 66270 Post Direct Selection Direct 25,000.00 16,859.23 Completed 2021-08-15 2021-08-03 2021-08-20 2021-08-06 2021-09-24 2021-08-10 2022-03-23 2021-11-11 nse Diesel Generator 125 KVA (Q ty:1) MOH-PPD/WB-PROCUREMEN Emergency COVID-19 Respo IDA / 66270 Prior Direct Selection Direct 5,600,000.00 5,562,000.00 Completed 2021-11-02 2021-11-07 2021-11-07 2021-11-11 2021-12-12 2021-10-01 2022-06-10 2022-02-15 T/2021/07 / Supply of Modern nse a Vaccine Page 6 MOH-PPD/WB-PROCUREMEN T/2021/08 / Furniture require ment for JDWNRH Flu Clinic, Thimphu. 1. Manager's Table Art No 11 0(qty: 5) Emergency COVID-19 Respo Request for Quota Single Stage - One E IDA / 66270 Post Limited 1,300.00 0.00 Canceled 2021-11-12 2022-01-07 2022-07-06 2. Visitor's Chair with Cushio nse tions nvelope n(Qty: 6) 3. Executive Visitor's Chair K S 3003 (Qty: 1) 4. Half secretariat table with drawers (Qty:2) 5. Armed Chair (wood) (Qty: 3) MOH-PPD/WB-PROCUREMEN T/2021/09 / Procurement of l Emergency COVID-19 Respo IDA / 66270 Post Direct Selection Direct 5,600.00 5,558.05 Completed 2021-11-19 2021-11-04 2021-11-24 2021-11-18 2021-12-29 2021-12-04 2022-06-27 2022-03-26 aser imaging films for portabl nse e digital x-rays machines. (Qt y: 49 packets). R1-MOH-PPD/WB-PROCUREM ENT/2021/08 / Furniture requ irement for JDWNRH Flu Clini c, Thimphu. 1. Manager's Tab Emergency COVID-19 Respo le Art No 110(qty: 5) 2. Visito IDA / 66270 Post Direct Selection Direct 1,300.00 1,226.33 Completed 2021-11-29 2021-12-20 2021-12-04 2021-12-23 2022-01-08 2021-12-29 2022-07-07 2022-01-12 nse r's Chair with Cushion(Qty: 6) 3. Executive Visitor's Chair K S 3003 (Qty: 1) 4. Half secret ariat table with drawers (Qty: 2) 5. Armed Chair (wood) (Qt y: 3) MOH-PPD/WB-PROCUREMEN T/2022/01 / Procurement of Diagnostic test kits: 1.Standard Transport mediu m and swab-200,000 tests 2.Standard M Spin-X Viral RN Emergency COVID-19 Respo IDA / 70980 Prior Direct Selection Direct 1,700,000.00 1,558,728.00 Completed 2022-05-20 2022-05-18 2022-05-25 2022-05-18 2022-06-29 2022-01-23 2022-12-26 2022-01-26 A Extraction kit-100,000 test nse s 3.RT-PCR-100,000 tests 4.Standard F rapid antigen-2 00,000 tests 5.Standard Q rapid antigen-1 00,000 tests MOH-PPD/WB-PROCUREMEN T/2022/02 / Procurement of; Emergency COVID-19 Respo 1. RTPCR (1042 nos. of packs IDA / 70980 Prior Direct Selection Direct 410,000.00 408,628.00 Completed 2022-06-17 2022-06-14 2022-06-22 2022-06-19 2022-07-27 2022-03-08 2023-01-23 2022-03-11 nse ) 2. Cold chain box(Qty: 12) H/C & Shipping: US$ 4,000 MOH-PPD/WB-PROCUREMEN T/2022/03 / Procurement of; 1. Clinical Virus Transport Me Emergency COVID-19 Respo IDA / 70980 Prior Direct Selection Direct 120,000.00 114,070.00 Completed 2022-06-17 2022-06-14 2022-06-22 2022-06-19 2022-07-27 2022-03-01 2023-01-23 2022-03-08 dium (CTM) with Nasalpharyn nse geal and Oropharyngeal swa b (Qty: 100,000) Freight Charges: US$ 14,070 MOH-PPD/WB-PROCUREMEN T/2022/04 / Procurement of medicines for COVID-19 1. Multivitamin containing vit amin D3 (Qty: 300,000) Emergency COVID-19 Respo Request for Quota Single Stage - One E IDA / 70980 Post Limited 23,000.00 21,195.60 Completed 2022-06-22 2022-03-25 2022-08-17 2022-03-30 2023-02-13 2022-06-21 2. Multivitamin syrup contain nse tions nvelope ing vitamin D3 (Qty: 30,000) 3. Sodium Chloride 0.9% nas al drop (Qty: 3,000) 4. Sinarest syrup (Qty: 53,00 0) MOH-PPD/WB-PROCUREMEN T/2022/05 / Procurement of f urniture and other items for CRRH; half secretariat table, Emergency COVID-19 Respo Request for Quota Single Stage - One E dispensing chair, half back re IDA / 66270 Post Limited 4,000.00 4,719.54 Completed 2022-08-03 2022-07-25 2022-09-28 2022-08-19 2023-03-27 2022-11-01 nse tions nvelope volving chair, steel almirah w ith four shelves, airport waiti ng chair, patient examination stool, wooden diwan, water fi lter, TV, wooden cabinet tabl e MOH-PPD/WB-PROCUREMEN T/2022/06 / Procurement of n Emergency COVID-19 Respo Open - Internationa Single Stage - One E Under Imple eurosurgical equipment. IDA / 70980 Prior Request for Bids 300,000.00 0.00 2022-11-30 2023-02-19 2022-12-05 2023-04-05 2023-01-16 2023-05-05 2023-02-15 2023-03-22 2023-09-18 nse l nvelope mentation 1. Neuro-drill system 2. Neurosurgical microscope NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual VPDP(12)DOPH/2020/ / Tran sportation of vaccine to differ Emergency COVID-19 Respo IDA / 66270 Post Direct Selection Direct 20,000.00 17,973.81 Completed 2021-03-24 2021-03-18 2021-03-24 2021-03-24 2021-04-13 2021-03-25 2021-05-15 2021-06-04 ent districts in Bhutan (using nse helicopter services) MOH-PPD/WB-PROCUREMEN T/2021/05 / Maintenance of Emergency COVID-19 Respo IDA / 66270 Post Direct Selection Direct 10,000.00 8,958.49 Completed 2021-08-22 2021-08-17 2021-08-27 2021-08-20 2021-10-01 2021-08-28 2022-03-30 2021-10-30 walk-in cooler at Mongar Hos nse pital for COVID-19 patient's k itchen. CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 7 PPD/WB(COVID-10)PROC/20 20 / Hiring of Procurement Of Emergency COVID-19 Respo Individual Consult ficer/Consultant for COVID-19 IDA / 66270 Post Limited 46,500.00 38,590.12 Terminated 2020-05-19 2020-05-23 2020-05-24 2020-05-27 2020-06-14 2020-06-15 2020-07-19 2020-06-17 2021-01-15 nse ant Selection Emergency Response and He alth Systems Preparedness P roject. PPD/WB(COVID-19)M&E2020 / Hiring of M&E Officer/Consu Emergency COVID-19 Respo Individual Consult ltant for COVID-19 Emergenc IDA / 66270 Post Limited 55,800.00 38,759.83 Terminated 2020-05-19 2020-05-23 2020-05-24 2020-05-27 2020-06-14 2020-06-15 2020-07-19 2020-06-19 2021-01-15 nse ant Selection y Response and Health Syste ms Preparedness Project PPD/WB(COVID-19)CIVIL/202 0 / Hiring of Civil Engineer/Co Emergency COVID-19 Respo Individual Consult nsultant for COVID-19 Emerg IDA / 66270 Post Limited 49,600.00 38,540.75 Signed 2020-05-19 2020-05-23 2020-05-24 2020-05-27 2020-06-14 2020-06-18 2020-07-19 2020-06-19 2021-01-15 nse ant Selection ency Response and Health S ystems Preparedness Project. PPD/WB(COVID-19)M&E2023 / Hiring of M&E Officer/Consu Implementation Managemen Individual Consult ltant for COVID-19 Emergenc IDA / 66270 t and Monitoring and Evaluat Post Limited 15,000.00 0.00 Signed 2023-04-09 2023-03-30 2023-04-14 2023-03-30 2023-05-05 2023-04-19 2023-06-09 2023-12-06 ant Selection y Response and Health Syste ion ms Preparedness Project PPD/WB(COVID-19)PROCURE MENT2023 / Hiring of Procure Emergency COVID-19 Respo Individual Consult Under Implement ment officer /Consultant for C IDA / 66270 Post Open - National 15,000.00 0.00 2023-06-30 2023-06-06 2023-08-18 2023-09-08 2023-10-13 2024-06-30 nse ant Selection ation OVID-19 Emergency Respons e and Health Systems Prepar edness Project Page 8 Procurement Plan WASIS II Credit No.: IDA-57830 I. General 1. Bank’s approval Date of the procurement Plan [Original: December 2007]: Revision 15 of Updated Procurement Plan, June 2010] 2. Date of General Procurement Notice: Dec 24, 2006 3. Period covered by this procurement plan: June 2017 to December 2018 II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Procurement Method Prior Review Comments Threshold US$ 1. ICB and LIB (Goods) Above US$ 1,500,000 All 2. NCB (Goods) Below US$ 1,500,000 None 3. ICB (Works) Above US$ 5 million All 4. NCB (Works) Below US$ 5 million None 2. Prequalification. Bidders for _Not applicable_ shall be prequalified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines. 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: Not Applicable 4. Reference to (if any) Project Operational/Procurement Manual: Project Implementation Manual for World Bank Loan Project XYZ 04/01/2010 issued by 5. Any Other Special Procurement Arrangements: [including advance procurement and retroactive financing, if applicable] 5 ICB works packages will be financed under retroactive financing 6. Summary of the Procurement Packages planned during the first 18 months after project effectiveness ( including those that are subject to retroactive financing and advanced procurement) 1 2 3 4 5 6 7 Ref. No. Description Estimated Package Domestic Review Comments Cost s Preference by Bank US$ (yes/no) (Prior / million Post) FIPAG Summary of the ICB (Works) 22.43 2 No Prior FIPAG Summary of the NCB (Works) 8.90 2 No Post CRA/WASIS II/G 04/17, CRA/WASIS II/G 05/17, Summary of the NCB CRA/WASIS II/G-04/17 & (Goods) 0.295 4 Yes Post CRA/WASIS II/G 06/17 III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Comments Threshold 1. Competitive Methods (Firms) Above US$ 500,000 2. Individual Above US$ 200,000 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_300,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: None 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 Estimated Review Ref. No. Description of Assignment Cost Package by Bank Comments US$ million s (Prior / Post) FIPAG Summary of QCBS 9.42 6 Prior QCBS FIPAG Summary ICS 0.38 2 Prior and IND Post CRA/WASIS II/CON 03/17 Summary of QCBS 0.2 1 Prior QCBS CRA/WASIS II/CON 04/17 Summary of CQS 0.5 1 Prior CQS CRA/WASIS II/CON 07/17 CRA/WASIS II/CON 06/17 Summary ICS 0.20 3 Prior ICS CRA/WASIS II/ CON 05/17 PROCUREMENT Mozambique : Water Services & Institutional Support II PLAN General Information Country: Mozambique 2016-10-18 Bank’s Approval Date of the Original Procurement Plan: 2023-06-06 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P149377 GPN Date: Project Name: Water Services & Institutional Support II Loan / Credit No: IDA / D1100, IDA / 57830, IDA / D4910 Water Supply Asset Holding and Investment Fund Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Component 1: Rehabilitation FIPAG/WASISII/W-8/18 / Drili Single Stage - One E 2019-02-0 IDA / 57830 and Expansion of Water Sup Post Request for Bids Open - National 1,323,000.00 789,850.46 Signed 2018-04-27 2018-04-13 2018-05-02 2018-04-13 2018-06-15 2018-05-25 2018-07-30 2018-07-10 2018-11-11 2018-09-26 ng boreholes, Tete nvelope 9 ply Production and Distributi on FIPAG/WASISII/W-12/18 / Des Component 1: Rehabilitation ign and build for rehabilitatio and Expansion of Water Sup Request for Quota Single Stage - One E 2,188,687.6 2018-12-2 IDA / 57830 Post Limited 1,500,000.00 Signed 2018-05-02 2018-10-16 2018-06-27 2019-01-29 n of the Mutua pumping stati ply Production and Distributi tions nvelope 6 4 on, Beira (emergency) on FIPAG/WASISII/W-3/19 / Elect Component 1: Rehabilitation romechanical equipment of b and Expansion of Water Sup Open - Internationa Single Stage - One E 19,600,000.0 13,724,398. 2021-10-1 oreholes, rehabilitation and c IDA / 57830 Prior Request for Bids Signed 2019-10-31 2020-04-23 2019-11-15 2020-05-05 2020-02-13 2020-07-15 2020-05-13 2020-09-23 2020-07-18 2020-12-08 ply Production and Distributi l nvelope 0 50 1 onstruction of Water Treatme on nt Plant and Pumping Station in Pemba FIPAG/WASISII/W-5/19 / Refu Component 1: Rehabilitation rbishment of existing treatm and Expansion of Water Sup Open - Internationa Single Stage - One E 18,100,000.0 12,986,588. 2022-08-3 ent system, including pre-tre IDA / 57830 Prior Request for Bids Signed 2019-11-20 2020-12-06 2019-12-05 2020-12-21 2020-03-04 2021-02-16 2020-06-02 2021-08-24 2020-08-31 2021-12-14 ply Production and Distributi l nvelope 0 47 1 atment canal, and rehabilitat on ion of the Dingue Dingue wat er intake in Beira FIPAG/WASISII/W-4/19 / Reh Component 1: Rehabilitation Open - Internationa Single Stage - One E 10,793,000.0 9,173,096.4 2022-07-3 abilitation and construction o IDA / 57830 and Expansion of Water Sup Prior Request for Bids Signed 2020-03-27 2020-07-17 2020-04-11 2020-07-24 2020-07-10 2020-09-22 2020-10-08 2021-01-26 2021-03-07 2021-04-02 l nvelope 0 0 0 f distribution centres and net ply Production and Distributi work in Pemba on FIPAG/DRIVE/W-1/19 / Desig Component 1: Rehabilitation n, rehabilitation and construc and Expansion of Water Sup Open - Internationa Single Stage - One E 25,050,000.0 2022-08-0 tion of intake, water treatme IDA / D4910 Prior Request for Bids 0.00 Canceled 2020-06-18 2020-07-03 2020-09-01 2020-11-30 2021-02-13 ply Production and Distributi l nvelope 0 7 nt, transmission main and pu on mping stations in Nacala FIPAG/DRIVE/W-2/19 / Desig Component 1: Rehabilitation n, Rehabilitation and Constru and Expansion of Water Sup Open - Internationa Single Stage - One E 17,550,000.0 2022-10-1 IDA / D4910 Prior Request for Bids 0.00 Canceled 2020-07-30 2020-08-14 2020-10-13 2021-01-11 2021-04-26 ction of Distribution Centers ply Production and Distributi l nvelope 0 8 and Network in Nacala on FIPAG/WASISII/EMERGENCY/ W-13/20 / Borehole equipme Component 4: Contingent E Open - Internationa Single Stage - One E 2021-03-1 IDA / 57830 Post Request for Bids 835,000.00 0.00 Canceled 2020-05-28 2020-06-02 2020-07-14 2020-08-13 2020-09-17 nt and construction of trans mergency Response l nvelope 6 mission mains in Moatize FIPAG/WASISII/EMERGENCY/ Component 1: Rehabilitation Single Stage - One E 2021-03-0 W-7A/20 / Rehabilitation of n IDA / 57830 and Expansion of Water Sup Post Request for Bids Open - National 837,885.00 0.00 Canceled 2020-05-13 2020-05-18 2020-06-29 2020-07-29 2020-09-02 nvelope 1 etwork in Beira and Dondo ply Production and Distributi on FIPAG/WASISII/W-10/22 / Exp Component 1: Rehabilitation Request for Bids - ansion of the wellfields, reha and Expansion of Water Sup Open - Internationa Single Stage - One E Works (without pr 15,000,000.0 Under Imple 2023-01-1 bilitation and expansion of th IDA / D4910 Prior Request for Bids 0.00 2022-04-01 2022-08-12 2022-04-06 2022-08-16 2022-05-18 2022-10-10 2022-06-17 2023-01-03 2022-07-22 ply Production and Distributi l nvelope equalification) SP 0 mentation 8 e water treatment plant and on D pumping stations, Tete and Moatize Request for Bids - FIPAG/WASISII/W-14/22 / Co Component 1: Rehabilitation Open - Internationa Single Stage - One E Works (without pr 10,000,000.0 Under Imple 2023-06-2 nstruction of new Distributio IDA / D4910 and Expansion of Water Sup Prior Request for Bids 0.00 2022-09-01 2022-10-31 2022-09-06 2022-11-01 2022-10-18 2022-12-19 2022-11-17 2023-04-13 2022-12-22 l nvelope equalification) SP 0 mentation 0 n Center, Beira ply Production and Distributi D on FIPAG/WASISII/W-11/22 / Re Component 1: Rehabilitation Request for Bids - habilitation and Construction and Expansion of Water Sup Open - Internationa Single Stage - One E Works (without pr 20,000,000.0 2023-07-0 IDA / D4910 Prior Request for Bids 0.00 Canceled 2022-09-15 2022-09-20 2022-11-01 2022-12-01 2023-01-05 of Distribution Centers and N ply Production and Distributi l nvelope equalification) SP 0 4 etwork, Tete and Moatize on D FIPAG/DRIVE/W-15/23 / Reha Component 1: Rehabilitation Request for Bids - bilitation and construction of and Expansion of Water Sup Open - Internationa Single Stage - One E Works (without pr 21,500,000.0 Under Imple 2024-01-0 IDA / D4910 Prior Request for Bids 0.00 2023-03-16 2023-04-21 2023-03-21 2023-04-26 2023-05-02 2023-06-01 2023-07-06 intake, water treatment, tran ply Production and Distributi l nvelope equalification) SP 0 mentation 2 smission main and pumping on D stations in Nacala Request for Bids - FIPAG/DRIVE/W-16/23 / Reha Component 1: Rehabilitation Open - Internationa Single Stage - One E Works (without pr 16,500,000.0 Under Imple 2024-01-0 bilitation and construction of IDA / D4910 and Expansion of Water Sup Prior Request for Bids 0.00 2023-03-16 2023-04-21 2023-03-21 2023-04-26 2023-05-02 2023-06-01 2023-07-06 l nvelope equalification) SP 0 mentation 2 distribution centers and netw ply Production and Distributi D ork in Nacala on FIPAG/WASISII/W-11A/23 / R Component 1: Rehabilitation Request for Bids - ehabilitation and Constructio and Expansion of Water Sup Open - Internationa Single Stage - One E Works (without pr 11,180,000.0 Under Imple 2024-09-0 IDA / D4910 Prior Request for Bids 0.00 2023-03-14 2023-03-24 2023-03-19 2023-03-27 2023-04-30 2023-05-30 2023-07-04 n of Distribution Centers and ply Production and Distributi l nvelope equalification) SP 0 mentation 4 Network, Tete and Moatize on D FIPAG/WASISII/W-2/15 / Desi Component 1: Rehabilitation gn and build for rehabilitatio and Expansion of Water Sup Open - Internationa Single Stage - One E 22,416,000.0 13,747,363. 2019-05-0 n of existing transmission ma IDA / 57830 Prior Request for Bids Signed 2016-10-17 2016-10-19 2016-10-17 2016-10-27 2016-10-17 2016-12-15 2016-10-17 2017-04-24 2017-04-03 2017-05-22 2017-07-06 2017-10-13 2017-10-31 ply Production and Distributi l nvelope 0 87 4 in and construction of 50 km on of transmission main DN 500 mm, Pemba FIPAG/WASISII/W-9/16 / Desi gn and build of 25km transmi Component 1: Rehabilitation ssion main, DN 350 mm to co and Expansion of Water Sup Open - Internationa Single Stage - One E 10,000,000.0 9,315,309.5 2019-11-0 IDA / 57830 Prior Request for Bids Signed 2017-01-10 2017-01-20 2017-05-29 2017-10-27 2017-07-12 2018-09-04 2017-02-14 2017-04-25 2017-10-09 2018-11-22 2017-11-24 2019-04-09 2018-04-12 2019-05-31 nnect Moatize to Tete system ply Production and Distributi l nvelope 0 1 1 and new pipeline from Nhart on anda to WTP, 1km, DN 500 m m, Tete FIPAG/WASISII/W-7/15 / Desi Component 1: Rehabilitation Single Stage - One E 6,185,997.9 2018-08-2 gn and construction of netwo IDA / 57830 and Expansion of Water Sup Post Request for Bids Open - National 7,763,000.00 Signed 2017-05-08 2017-07-24 2017-05-29 2017-07-24 2017-08-05 2017-10-06 2017-09-19 2017-12-19 2018-02-03 2018-03-14 nvelope 3 5 rk, Beira and Dondo ply Production and Distributi on Component 1: Rehabilitation FIPAG/WASISII/W-1/15 / Drilli Single Stage - One E 2018-01-0 IDA / 57830 and Expansion of Water Sup Post Request for Bids Open - National 1,134,000.00 722,843.63 Signed 2016-12-05 2017-04-25 2016-12-26 2017-05-10 2017-02-16 2017-07-05 2017-03-20 2017-08-29 2017-06-05 2017-12-13 ng Boreholes, Pemba nvelope 2 ply Production and Distributi on Page 1 GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual FIPAG/IGP/G-2/17 / Supply of Component 2: Institutional S Request for Quota Single Stage - One E IDA / D1100 Post Limited 65,000.00 82,081.84 Signed 2017-08-27 2017-09-26 2017-11-23 2018-01-30 2017-12-23 IT equipment upport tions nvelope FIPAG/IGP/G-1/17 / Supply of Component 2: Institutional S Request for Quota Single Stage - One E IDA / D1100 Post Limited 35,000.00 46,398.49 Signed 2018-04-09 2018-06-04 2018-07-06 2019-04-16 2018-08-05 office furniture upport tions nvelope FIPAG/WASISII/G-3/18 / Purc Component 2: Institutional S Request for Quota Single Stage - One E IDA / D1100 Post Limited 65,000.00 0.00 Canceled 2018-11-05 2019-02-26 2019-08-25 hase of motorcycles for Tete upport tions nvelope and Moatize FIPAG/EMERGENCY/G-5/19 / Component 4: Contingent E Request for Quota Single Stage - One E Supply of sand for SSFs in Be IDA / 57830 Post Limited 136,750.00 654,353.83 Signed 2019-10-22 2019-09-09 2019-12-17 2019-11-29 2020-06-14 mergency Response tions nvelope ira, Quelimane, Manica and N ampula FIPAG/EMERGENCY/G-2/19 / Supply of electrical and mec Component 4: Contingent E Request for Quota Single Stage - One E Under Imple IDA / 57830 Post Limited 1,237,110.00 0.00 2019-10-19 2019-08-26 2019-12-22 2020-06-19 hanical equipament for Beira mergency Response tions nvelope mentation and Dondo, Manica, FIPAG/EMERGENCY/G-4/19 / Component 4: Contingent E Request for Quota Single Stage - One E Supply of Chemicals (HTH, All IDA / 57830 Post Limited 310,000.00 276,357.72 Signed 2020-03-13 2019-07-22 2020-05-08 2019-10-13 2020-11-04 mergency Response tions nvelope uminium Sulphate and Lime) for Beira FIPAG/EMERGENCY/G-1/19 / Supply of Pipes and Fittings f Component 4: Contingent E Request for Quota Single Stage - One E IDA / 57830 Post Limited 1,006,820.00 259,651.56 Signed 2019-10-08 2019-08-15 2019-12-03 2019-11-14 2020-05-31 or Beira, Dondo, Manica, Tet mergency Response tions nvelope e, Moatize, Nampula and Moc uba FIPAG/WASISII/EMERGENCY/ G-6/20 / Supply of electrical a nd mechanical equipament f Component 4: Contingent E Request for Quota Single Stage - One E IDA / 57830 Post Limited 1,230,000.00 1,096,934.08 Signed 2020-05-23 2020-05-27 2020-07-18 2021-01-01 2021-01-14 or Beira, Dondo, Manica, Chi mergency Response tions nvelope moio, Gondola, Tete and Moa tize and Supply of pipes and fittings FIPAG/WASISII/EMERGENCY/ Component 4: Contingent E Request for Quota Single Stage - One E G-8/20 / Supply of Chemicals IDA / 57830 Post Limited 1,510,000.00 1,246,974.16 Signed 2020-05-17 2020-05-27 2020-07-12 2020-08-29 2021-01-08 mergency Response tions nvelope (HTH, Alluminium Sulphate a nd Lime) for Beira FIPAG/WASISII/EMERGENCY/ Component 4: Contingent E Pending Impl G-10/20 / Supply of Electricit IDA / 57830 Post Direct Selection Direct 550,967.74 0.00 2020-05-12 2020-05-17 2020-06-21 2020-12-18 mergency Response ementation y to Beira by EDM FIPAG/WASISII/EMERGENCY/ Component 4: Contingent E Request for Quota Single Stage - One E G-9/20 / Supply of Sand to Be IDA / 57830 Post Limited 636,707.00 528,158.71 Signed 2020-05-25 2020-05-27 2020-07-20 2020-08-29 2021-01-16 mergency Response tions nvelope ira, Quelimane, Manica and N ampula FIPAG/WAISIS II/G-15/20 / Su Component 2: Institutional S Single Stage - One E Pending Impl pply of equipment and goods IDA / D1100 Post Request for Bids Open - National 300,000.00 0.00 2020-09-21 2020-10-06 2020-12-05 2021-02-03 2021-05-04 2021-12-30 upport nvelope ementation for Nacala dam safety manag ement FIPAG/WASIS II/G-04/20 / Su Component 1: Rehabilitation pply of water meters & fitting and Expansion of Water Sup Open - Internationa Single Stage - One E IDA / 57830 Prior Request for Bids 2,650,000.00 2,904,085.26 Signed 2020-12-01 2021-02-12 2020-12-06 2021-02-17 2021-01-17 2021-04-30 2021-02-16 2021-11-10 2021-03-23 2022-06-30 2021-09-19 s for connections for Pemba, ply Production and Distributi l nvelope Nacala, Tete, Moatize, Beira on and Dondo Component 1: Rehabilitation FIPAG/WASISII/G-6/21 / Upgr Open - Internationa Single Stage - One E IDA / 57830 and Expansion of Water Sup Post Request for Bids 315,000.00 0.00 Signed 2021-04-30 2022-02-18 2021-05-05 2022-02-19 2021-06-16 2022-04-06 2021-07-16 2022-12-27 2021-08-20 2022-02-16 ade of Regional Laboratories l nvelope ply Production and Distributi on FIPAG/WASISII/G-7/21 / Asset Component 1: Rehabilitation Single Stage - One E Pending Impl Management: Software, Mate IDA / 57830 and Expansion of Water Sup Post Request for Bids Limited 350,000.00 0.00 2021-06-24 2021-06-29 2021-08-10 2021-09-09 2021-10-14 2022-04-12 nvelope ementation rials and Equipment ply Production and Distributi on FIPAG/WASISII/G-8/21 / Supp Component 2: Institutional S Request for Quota Single Stage - One E Pending Impl IDA / D1100 Post Limited 50,000.00 0.00 2021-08-13 2022-01-16 2022-07-15 ly of IT Equipment upport tions nvelope ementation NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual FIPAG/WASISII/CON-3/17 / D Component 2: Institutional S Request for Quota Single Stage - One E IDA / D1100 Post Limited 150,000.00 64,350.68 Signed 2017-08-19 2017-08-23 2017-10-23 2017-10-30 2019-10-23 ocuments Translation Service upport tions nvelope s FIPAG/WASISII/CON-26/18 / Component 2: Institutional S Request for Quota Single Stage - One E IDA / D1100 Post Open - National 150,000.00 72,247.06 Signed 2018-10-20 2018-12-17 2018-12-14 2020-12-23 Document translation service upport tions nvelope s FIPAG/WASIS II/CON-36/20 / I mplementation of COVID-19 Component 2: Institutional S mitigation measures in the P IDA / D1100 Post Direct Selection Direct 624,774.00 715,004.07 Signed 2020-09-14 2020-09-14 2020-09-19 2020-09-16 2020-12-01 2020-10-29 2022-12-01 upport HC commercial management system by 2-Business FIPAG/WASISII/G-5/21 / Docu Component 2: Institutional S Request for Quota Single Stage - One E IDA / D1100 Post Limited 80,000.00 46,646.33 Signed 2021-04-13 2021-05-06 2021-06-08 2022-02-01 2021-12-05 ment translation services upport tions nvelope FIPAG/WASISII/ G-8/21 / Com Component 2: Institutional S Request for Quota Single Stage - One E munication and Logistics for IDA / D1100 Post Limited 150,000.00 121,781.19 Signed 2021-06-02 2021-05-25 2021-07-28 2021-09-04 2022-01-24 upport tions nvelope Financiers Conference FIPAG/WASISII/CON-39/20 / Dam Safety Technical Assista Component 2: Institutional S nce Service Provider for ARA- IDA / D1100 Post Direct Selection Direct 120,000.00 0.00 Canceled 2020-11-16 2022-01-01 2020-12-16 2022-03-10 2021-04-15 2023-04-15 upport Norte - Portuguese Laborator y of Civil Engineering (LNEC) FIPAG/WASISII/G-9/23 / Train Component 3: Output-Based Request for Quota Single Stage - One E Pending Impl ing in GEMS under OBA Progr IDA / D4910 Payments for Low-Income-H Post Limited 4,200.00 0.00 2023-03-01 2023-04-26 2023-10-23 tions nvelope ementation am ousehold Connections Page 2 CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual FIPAG/WASISII/CON-7/15 / D esign and supervision of elec tromechanical equipment of Component 2: Institutional S Quality And Cost- Open - Internationa IDA / D1100 Prior 2,300,000.00 798,480.34 Signed 2016-10-17 2016-10-19 2016-10-17 2016-12-22 2016-11-08 2017-03-06 2017-01-10 2017-04-09 2017-03-24 2017-09-20 2017-08-01 2018-01-09 2018-03-16 2021-02-21 boreholes, rehabilitation and upport Based Selection l construction of treatment pla nt and pumping stations, Pe mba FIPAG/WASISII/CON-15/18 / Design and supervision of ele ctro-mechanical equipment o Component 2: Institutional S Quality And Cost- Open - Internationa IDA / D1100 Prior 3,000,000.00 2,017,083.27 Signed 2018-05-21 2018-10-10 2018-07-05 2018-10-16 2018-08-18 2019-07-29 2018-09-22 2019-09-24 2018-10-22 2020-05-14 2018-12-05 2020-10-29 2019-03-19 2020-12-27 2021-09-04 f boreholes, rehabilitation an upport Based Selection l d construction of treatment p lant and pumping stations, T ete FIPAG/WASISII/CON-16/18 / Design and Supervision for re Component 2: Institutional S Quality And Cost- Open - Internationa IDA / D1100 Prior 2,100,000.00 872,120.31 Signed 2018-05-11 2018-07-17 2018-06-01 2018-07-19 2018-07-15 2019-07-30 2018-08-20 2019-09-26 2018-09-19 2019-12-23 2018-11-02 2020-04-01 2019-02-14 2020-08-13 2021-08-02 habilitation and construction upport Based Selection l of distribution centres and ne twork, Tete and Moatize FIPAG/WASISII/CON-13A/18 / Component 2: Institutional S Consultant Qualifi IDA / D1100 Post Open - National 110,000.00 91,401.88 Signed 2018-09-21 2018-07-24 2018-09-28 2018-11-11 2018-11-05 2018-11-25 2019-01-29 2018-12-16 2019-02-08 2019-05-15 Supervision for drilling boreh upport cation Selection oles in Tete FIPAG/WASISII/CON-24/18 / Component 2: Institutional S Quality And Cost- Open - Internationa Design and supervision of co IDA / D1100 Prior 1,000,000.00 1,301,234.04 Signed 2018-11-30 2019-12-20 2018-12-14 2020-01-03 2019-04-13 2020-05-31 2019-06-27 2020-08-12 2019-08-11 2020-10-28 2019-10-09 2021-01-21 2019-12-22 2021-03-30 2021-07-12 upport Based Selection l nstruction of distribution cent er in Beira FIPAG/WASISII/CON-19/18 / Development of information and communication technolo Component 2: Institutional S Quality And Cost- Open - Internationa IDA / D1100 Post 650,000.00 677,082.81 Signed 2018-10-28 2018-11-14 2018-12-09 2018-12-17 2019-01-22 2020-06-04 2019-02-19 2020-07-21 2019-03-21 2021-03-10 2019-04-25 2021-04-19 2019-05-30 2021-12-13 2020-05-29 gy master plan and assistanc upport Based Selection l e in the identification of appli cation management solution s FIPAG/WASISII/CON-23A/18- 2 / Design check and supervi Component 2: Institutional S Consultant Qualifi IDA / D1100 Post Open - National 200,000.00 291,710.00 Signed 2018-11-30 2018-12-06 2018-12-30 2019-04-11 2019-02-27 2019-11-05 2019-03-29 2019-12-30 2019-05-03 2020-01-28 2019-12-29 sion of construction of Mutua upport cation Selection emergency pumping station, Beira FIPAG/DRIVE/CON-1/19 / Des ign check and supervision of Component 2: Institutional S Quality And Cost- Open - Internationa IDA / D4910 Prior 2,500,000.00 1,772,419.07 Signed 2020-04-05 2020-05-13 2020-05-05 2020-05-16 2020-10-17 2021-12-19 2021-01-15 2021-10-25 2021-03-16 2021-12-31 2021-06-14 2022-04-04 2021-12-11 2022-05-30 2024-05-29 rehabilitation and expansion upport Based Selection l of Nacala water supply syste m FIPAG/WASISII/CON-27/20 / F Component 2: Institutional S Least Cost Selecti IDA / D1100 Post Open 450,000.00 238,954.91 Signed 2020-03-12 2021-01-18 2020-04-02 2020-11-05 2020-05-16 2021-02-05 2020-06-13 2021-03-04 2020-07-13 2021-04-15 2020-08-17 2021-06-08 2020-09-21 2021-05-25 2021-03-20 inancial Audit for 2020, 2021 upport on and 2022 FIPAG/WASISII/CON-34/20 / F Component 2: Institutional S Quality And Cost- Open - Internationa Under Implement easibility Study and Detailed IDA / D1100 Prior 600,000.00 0.00 2020-08-30 2021-08-31 2020-10-14 2021-09-22 2021-02-11 2022-08-09 2021-05-12 2022-10-17 2021-07-11 2023-04-18 2021-10-09 2022-01-28 2022-11-24 upport Based Selection l ation Design for Nampula FIPAG/WASISII/CON-33/20 / P Component 2: Institutional S Quality And Cost- Open - Internationa Under Implement reparation of Master Plan for IDA / D1100 Prior 1,500,000.00 0.00 2020-11-16 2021-05-03 2020-12-31 2021-05-21 2021-04-30 2022-02-10 2021-07-29 2022-04-08 2021-09-27 2022-08-10 2021-12-26 2023-03-01 2022-04-16 2023-04-16 upport Based Selection l ation Pemba and Nacala FIPAG/WASISII/CON-31/20 / P Component 2: Institutional S Consultant Qualifi reparation of Project Manage IDA / D1100 Post Open - National 250,000.00 243,018.57 Signed 2020-09-04 2020-09-28 2020-09-25 2020-11-06 2020-12-24 2021-03-29 2021-01-23 2021-06-21 2021-04-08 2022-04-04 2022-03-10 upport cation Selection ment Platform for FIPAG FIPAG/WASISII/CON-25/18 / Component 2: Institutional S Quality And Cost- Open - Internationa Groundwater management pl IDA / D1100 Post 500,000.00 0.00 Canceled 2018-12-12 2019-01-02 2019-04-02 2019-06-16 2019-07-31 2019-09-13 2019-11-26 2021-06-18 upport Based Selection l an for Tete and Pemba FIPAG/WASISII/CON-12/15 / I Component 3: Output-Based Consultant Qualifi ndependent monitoring verifi IDA / D1100 Payments for Low-Income-H Post Open - National 300,000.00 0.00 Canceled 2018-07-26 2021-08-27 2018-09-15 2018-12-19 2019-06-08 2019-08-13 2025-09-09 cation Selection cation agent for Maputo ousehold Connections FIPAG/WASISII/CON-46/21 / T Component 2: Institutional S Quality And Cost- Open - Internationa echnical Assistance to Centra IDA / D1100 Post 450,000.00 0.00 Canceled 2021-05-28 2021-06-18 2021-08-01 2021-08-29 2021-09-28 2021-11-02 2021-12-07 2022-12-07 upport Based Selection l l Regional Water Utilily FIPAG/WASISII/CON-48/21 / Consultancy for the Refining Component 2: Institutional S Consultant Qualifi Open - Internationa Under Implement IDA / D1100 Post 150,000.00 0.00 2021-04-30 2022-08-27 2021-05-21 2022-11-18 2021-07-04 2021-08-03 2021-09-07 2022-03-06 and Implementation of Asset upport cation Selection l ation Management strategy FIPAG/WASISII/CON-42/21 / L eagal advisory services for e Component 2: Institutional S Consultant Qualifi Under Implement stablishment of Regional Co IDA / D1100 Prior Open - National 120,000.00 0.00 2021-05-30 2021-12-21 2021-06-20 2022-01-24 2021-08-03 2021-09-02 2021-10-07 2022-04-05 upport cation Selection ation mpanies, and legal assistanc e for PPP Studies up until the transactions FIPAG/WASISII/CON-49/21 / Component 2: Institutional S Consultant Qualifi Pending Impleme Utility Regional Office Project IDA / D1100 Post Open - National 150,000.00 0.00 2021-05-28 2021-06-18 2021-08-01 2021-08-31 2021-10-05 2022-04-03 upport cation Selection ntation Design and supervision FIPAG/WASISII/CON-43/21 / Developing Innovative Fit-for Component 2: Institutional S Consultant Qualifi Open - Internationa IDA / D1100 Post 300,000.00 0.00 Canceled 2021-04-19 2021-08-09 2021-05-10 2021-06-23 2021-07-23 2021-08-27 2022-02-23 -Purpose Public Private Partn upport cation Selection l erships for Four Regional Wat er Utilities FIPAG/WASISII/CON-58/21 / Developing Innovative Fit-for Component 2: Institutional S Quality And Cost- Open - Internationa IDA / D1100 Prior 400,000.00 0.00 Signed 2021-08-24 2021-11-15 2021-09-14 2021-09-13 2021-10-28 2021-11-26 2021-11-25 2022-01-27 2021-12-25 2022-03-15 2022-01-29 2022-08-03 2022-03-05 2024-02-29 -PurposePublic Private Partne upport Based Selection l rship for Four Regional Water Utilities FIPAG/WASISII/CON-59/21 / T Component 2: Institutional S Quality And Cost- Open - Internationa Under Implement echnical Assistance to Northe IDA / D1100 Prior 1,000,000.00 0.00 2021-09-03 2021-09-10 2021-09-24 2021-09-10 2021-11-07 2022-02-07 2021-12-05 2022-03-23 2022-01-04 2022-10-04 2022-02-08 2023-04-03 2022-03-15 2024-03-15 upport Based Selection l ation rn and Central Regional Wate r Utility FIPAG/WASISII/CON-60/21 / T echnical Assistance to South Component 2: Institutional S Quality And Cost- Open - Internationa IDA / D1100 Prior 1,000,000.00 0.00 Signed 2021-09-03 2021-09-11 2021-09-24 2021-09-12 2021-11-07 2022-02-07 2021-12-05 2022-03-24 2022-01-04 2022-10-05 2022-02-08 2023-04-03 2022-03-15 2023-06-21 2024-03-15 ern and Maputo Metropolitan upport Based Selection l Regional Water Utility Page 3 FIPAG/WASISII/CON-47/21 / T Component 2: Institutional S Quality And Cost- Open - Internationa echnical Assistance to Northe IDA / D1100 Post 400,000.00 0.00 Canceled 2021-05-28 2021-08-17 2021-06-18 2021-08-01 2021-08-29 2021-09-28 2021-11-02 2021-12-07 2022-12-07 upport Based Selection l rn Regional Water Utitily FIPAG/WASISII/CON-44/21 / T Component 2: Institutional S Quality And Cost- Open - Internationa echnical Assistance to Maput IDA / D1100 Post 500,000.00 0.00 Canceled 2021-05-28 2021-08-19 2021-06-18 2021-08-01 2021-08-29 2021-09-28 2021-11-02 2021-12-07 2022-12-07 upport Based Selection l o Metropolitan Water Utility FIPAG/WASISII/CON-41/21 / Consultancy services for pre Component 2: Institutional S Consultant Qualifi Open - Internationa paration and installation the IDA / D1100 Post 40,000.00 0.00 Canceled 2021-06-10 2021-07-14 2021-07-01 2021-08-14 2021-09-13 2021-10-18 2022-04-16 upport cation Selection l platform for manage the Grie vance Redress Mechanism (G RM) FIPAG/WASISII/CON-67/22 / F easibility Study and Detailed Component 2: Institutional S Quality And Cost- Open - Internationa Under Implement Design of Additional Intake, IDA / D4910 Post 400,000.00 0.00 2022-01-12 2022-01-26 2022-02-02 2022-03-17 2022-03-18 2022-08-30 2022-04-15 2022-11-04 2022-05-15 2023-03-16 2022-06-19 2023-05-09 2022-07-24 2023-07-24 upport Based Selection l ation Water Treatment Plant, Trans mission Main and Distribution System for Tete and Moatize. FIPAG/WASISII/CON-70/22 / Component 2: Institutional S Consultant Qualifi Open - Internationa Under Implement Dam Safety Technical Assista IDA / D1100 Post 120,000.00 0.00 2022-07-21 2022-07-27 2022-08-11 2022-08-26 2022-09-24 2022-11-24 2022-10-24 2022-11-28 2023-05-27 upport cation Selection l ation nce Service Provider for ARA- Norte FIPAG/WASISII/CON-69/22 / Detailed Hydrogeological Stu Component 2: Institutional S Quality And Cost- Open - Internationa Under Implement dies and Monitoring Systems IDA / D1100 Post 600,000.00 0.00 2022-08-05 2022-08-04 2022-08-26 2022-10-09 2022-11-06 2022-12-06 2023-01-10 2023-02-14 2024-02-14 upport Based Selection l ation Installation in the Aquifers of Pemba, Tete and Moatize FIPAG/WASISII/CON-75/23 / I mplementation of Regional D Component 2: Institutional S Quality And Cost- Open - Internationa Pending Impleme IDA / D1100 Post 300,000.00 0.00 2023-05-10 2023-05-31 2023-07-14 2023-08-11 2023-09-10 2023-10-15 2023-11-19 2024-11-18 atabase in the context of Cre upport Based Selection l ntation ation of Water Utilities FIPAG/WASISII/CON-9/15 / D esign and Supervision for ref urbishment of existing treat Component 2: Institutional S Quality And Cost- Open - Internationa IDA / D1100 Prior 1,500,000.00 786,012.94 Signed 2016-10-17 2016-10-19 2016-10-17 2017-01-03 2016-12-18 2017-03-17 2017-03-24 2017-06-09 2017-05-31 2017-10-06 2018-01-04 2017-12-11 2018-06-10 2021-02-26 ment system, including pre-t upport Based Selection l reatment canal & rehabilitati on of the Dingue Dingue Wat er Intake, Beira FIPAG/WASISII/CON-8/16 / D esign and supervision for Re Component 2: Institutional S Quality And Cost- Open - Internationa IDA / D1100 Prior 1,900,000.00 1,356,578.66 Signed 2016-10-17 2016-10-19 2016-10-17 2016-12-22 2016-12-21 2017-03-10 2017-03-09 2017-04-13 2017-05-03 2017-09-26 2017-12-05 2018-01-15 2018-03-19 2021-09-28 habilitation and Construction upport Based Selection l of Distribution Centre and Ne twork, Pemba FIPAG/WASISII/CON-14/16 / Design check and supervisio Component 2: Institutional S Quality And Cost- Open - Internationa IDA / D1100 Prior 1,000,000.00 599,575.00 Signed 2017-01-05 2017-05-22 2017-02-27 2017-07-26 2017-05-31 2018-10-15 2017-08-16 2018-12-04 2017-09-20 2019-04-09 2018-01-31 2019-07-19 2018-04-09 2019-10-10 2020-11-30 n of rehabilitation and constr upport Based Selection l uction of transmission mains, Tete FIPAG/WASISII/CON-11/15 / Component 2: Institutional S Quality And Cost- Open - Internationa Design check and supervisio IDA / D1100 Prior 1,500,000.00 771,254.25 Signed 2016-11-10 2016-12-15 2017-02-03 2016-12-21 2017-04-05 2017-05-10 2017-06-21 2017-07-26 2017-12-04 2017-12-06 2018-05-14 2018-02-12 2018-07-08 2020-09-02 upport Based Selection l n of network, Beira and Dond o FIPAG/WASISII/CON-6/15 / D esign check and supervision Component 2: Institutional S Quality And Cost- Open - Internationa IDA / D1100 Prior 1,215,000.00 665,133.53 Signed 2016-10-17 2016-10-19 2016-10-17 2016-12-12 2016-10-26 2017-02-27 2017-01-26 2017-04-03 2017-04-19 2017-08-29 2017-08-23 2017-11-03 2017-11-03 2020-11-16 of rehabilitation and construc upport Based Selection l tion of transmission mains, P emba INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual FIPAG/WASISII/CON-2/17 / Pl Component 2: Institutional S Individual Consult IDA / D1100 Prior Open 400,000.00 549,000.00 Signed 2017-08-10 2017-09-13 2017-09-22 2018-01-09 2017-10-07 2018-02-21 2017-12-10 2018-04-12 2019-12-10 anning and Investment Advis upport ant Selection or FIPAG/WASISII/CON-1/17 / Pr Component 2: Institutional S Individual Consult IDA / D1100 Prior Open 400,000.00 993,225.00 Signed 2017-08-11 2017-08-22 2017-10-14 2018-01-23 2017-11-04 2018-02-21 2018-01-07 2018-05-14 2020-01-07 ocurement Advisor upport ant Selection FIPAG/WASISII/CON-4/18 / El Component 2: Institutional S Individual Consult IDA / D1100 Prior Open 300,000.00 0.00 Canceled 2018-06-08 2018-07-27 2018-08-17 2018-11-06 2020-06-01 ectromechanical advisor upport ant Selection FIPAG/WASISII/CON-17/18 / Component 2: Institutional S Individual Consult IDA / D1100 Prior Open 400,000.00 268,032.00 Signed 2018-05-31 2019-12-12 2018-08-03 2020-03-13 2018-09-06 2020-04-22 2018-12-19 2020-05-22 2020-12-18 Contract management advis upport ant Selection or FIPAG/WASISII/CON-21/18 / Component 2: Institutional S Individual Consult IDA / D1100 Post Limited 50,000.00 37,830.00 Signed 2018-04-02 2018-05-02 2018-04-09 2018-06-05 2018-04-30 2018-11-13 2018-07-23 2018-12-02 2018-08-22 Dam safety inspection servic upport ant Selection es FIPAG/WASISII/CON-4/17 / U Component 2: Institutional S Individual Consult pdate of FIPAG generic Envir IDA / D1100 Post Open 100,000.00 0.00 Canceled 2018-04-18 2018-06-23 2018-07-25 2018-10-01 2019-03-30 upport ant Selection onmental Management Plan FIPAG/WASISII/CON-10/18 / Component 2: Institutional S Individual Consult Under Implement IDA / D1100 Post Open 150,000.00 0.00 2018-06-15 2021-03-12 2018-08-03 2018-08-31 2018-11-13 2020-06-08 Water treatment process spe upport ant Selection ation cialist FIPAG/WASISII/CON-22/18 / Component 2: Institutional S Individual Consult IDA / D1100 Post Direct 50,000.00 40,775.00 Signed 2018-04-06 2018-05-18 2018-04-16 2018-06-07 2018-05-07 2018-07-06 2018-06-11 2018-08-04 2018-12-08 Update of the RPF upport ant Selection FIPAG/WASISII/CON-20/18 / Component 2: Institutional S Individual Consult IDA / D1100 Post Direct 70,000.00 50,373.75 Signed 2018-04-09 2018-05-28 2018-04-19 2018-07-16 2018-05-10 2018-08-17 2018-07-23 2018-09-04 2018-09-06 Update of the ESMF upport ant Selection FIPAG/WASISII/CON-23/18 / Design check and supervisio Component 2: Institutional S Individual Consult IDA / D1100 Post Open 150,000.00 0.00 Canceled 2018-05-10 2018-06-28 2018-07-28 2018-08-24 2019-04-21 n of rehabilitation of Mutua p upport ant Selection umping station (emergency) FIPAG/WASISII/CON-19/15 / Component 2: Institutional S Individual Consult Pending Impleme Acquisition of commercial sof IDA / D1100 Post Open 300,000.00 0.00 2018-09-15 2019-02-10 2019-04-13 2019-06-19 2021-07-16 upport ant Selection ntation tware and technical assistanc e FIPAG/WASISII/CON-13/18 / S Component 2: Institutional S Individual Consult upervision for construction of IDA / D1100 Post Open 80,000.00 0.00 Canceled 2018-05-30 2018-07-24 2018-07-18 2018-08-21 2018-12-03 2019-03-03 upport ant Selection boreholes in Tete Page 4 FIPAG/WASISII/CON-27/19 / Component 2: Institutional S IDA / D1100 Post Direct Selection Direct 60,000.00 55,656.00 Signed 2019-05-31 2019-06-20 2019-06-12 2019-09-09 2019-07-29 2020-03-07 Review and update of ESIA fo upport r Nacala FIPAG/WASISII/CON-29/20 / I Component 2: Institutional S Individual Consult IDA / D1100 Post Limited 200,000.00 239,040.00 Signed 2020-07-08 2020-07-31 2020-07-13 2020-08-07 2020-08-03 2020-09-03 2020-09-07 2020-10-02 2021-03-06 nstitutional Advisor upport ant Selection FIPAG/WASIS II/CON-30/20 / Component 2: Institutional S Individual Consult Monitoring and Evaluation Sp IDA / D1100 Post Open 250,000.00 173,484.00 Signed 2020-07-15 2020-11-05 2020-09-02 2021-04-20 2020-09-23 2021-05-07 2020-10-28 2021-05-24 2021-04-26 upport ant Selection ecialist services FIPAG/WASISII/CON-32/20 / P Component 2: Institutional S Individual Consult IDA / D1100 Prior Open 400,000.00 150,422.40 Signed 2020-08-17 2020-11-03 2020-10-16 2021-04-14 2020-10-31 2021-06-10 2021-01-04 2021-06-29 2023-01-04 lanning and Investment Advi upport ant Selection sor FIPAG/WASISII/W-38/20 / Hy Component 2: Institutional S Individual Consult IDA / D1100 Post Open 200,000.00 299,800.00 Signed 2020-08-17 2020-08-13 2020-11-29 2021-01-07 2020-12-29 2021-01-29 2021-03-14 2021-03-05 2023-03-14 dro-mechanical Advisor upport ant Selection FIPAG/WASISII/CON-37/20 / Component 2: Institutional S Individual Consult IDA / D1100 Post Direct 60,000.00 141,493.75 Signed 2020-09-08 2020-10-22 2020-09-18 2020-12-03 2020-10-09 2021-02-26 2021-01-22 2021-04-02 2021-07-21 Dam safety inspection servic upport ant Selection es FIPAG/WASIS II/CON-35/20 / Component 2: Institutional S Individual Consult Groundwater management S IDA / D1100 Post Open 200,000.00 264,101.27 Signed 2020-08-31 2020-12-02 2020-11-13 2021-03-31 2020-12-13 2021-06-04 2021-02-26 2021-06-11 2023-02-26 upport ant Selection pecialist for Tete and Moatize FIPAG/WASIS II/CON 40/20 / Component 1: Rehabilitation Preparation and Implementat and Expansion of Water Sup Individual Consult IDA / D1100 Post Open 200,000.00 96,787.50 Signed 2020-11-06 2021-02-17 2020-12-25 2021-06-23 2021-01-15 2021-08-24 2021-02-19 2021-07-29 2021-08-18 ion of the Abbreviated Resett ply Production and Distributi ant Selection lement Action Plan (ARAP) in on Pemba FIPAG/WASISII/CON-50/21 / Component 1: Rehabilitation Individual Consult Pending Impleme Mapping of services for survi IDA / D1100 and Expansion of Water Sup Post Open 75,000.00 0.00 2021-05-30 2021-08-28 2021-09-18 2021-10-12 2022-04-10 ant Selection ntation vors of GBV /SEA for WASIS II ply Production and Distributi project on FIPAG/WASISII/CON-51/21 / Component 2: Institutional S Individual Consult IDA / D1100 Prior Open 350,000.00 397,495.00 Terminated 2021-05-26 2021-06-07 2021-07-14 2021-09-15 2021-08-04 2021-10-15 2021-09-08 2021-12-02 2022-03-07 Contract Management Adviso upport ant Selection r FIPAG/WASIS/CON-56/21 / Pr Component 2: Institutional S Individual Consult IDA / D1100 Prior Open 200,000.00 0.00 Canceled 2021-08-06 2021-07-24 2021-11-16 2022-01-13 2021-12-31 2022-02-21 2022-03-22 2023-09-13 ocurement Assistant upport ant Selection FIPAG/WASISII/CON-53/21 / Component 2: Institutional S Individual Consult IDA / D1100 Post Open 250,000.00 186,931.38 Signed 2021-08-24 2021-07-13 2021-11-19 2021-12-06 2021-12-19 2022-01-18 2022-03-10 2022-03-03 2024-03-09 Business Management Advis upport ant Selection or FIPAG/WASISII/CON-54/21 / T echnical Assistance for Imple Component 2: Institutional S Individual Consult IDA / D1100 Post Open 150,000.00 181,280.00 Signed 2021-07-16 2021-07-12 2021-10-26 2022-04-14 2021-12-10 2022-05-31 2022-03-10 2022-06-09 2024-03-09 mentation of the Environmen upport ant Selection tal and Social Safeguards FIPAG/WASISII/CON-52/21 / Component 2: Institutional S Individual Consult IDA / D1100 Post Open 150,000.00 148,210.48 Signed 2021-07-20 2021-07-13 2021-10-15 2022-02-02 2021-11-29 2022-03-21 2022-02-27 2022-03-27 2023-09-23 Communication Assistant upport ant Selection FIPAG/WASISII/CON-57/21 / P Component 2: Institutional S Individual Consult IDA / D1100 Prior Open 400,000.00 0.00 Canceled 2021-08-25 2021-09-08 2021-10-13 2021-11-03 2021-12-08 2023-11-30 rocurement Advisor upport ant Selection FIPEG/WASISII/CON-55/21 / T Component 2: Institutional S Pending Impleme echnical Assistance for Hous IDA / D1100 Post Direct Selection Direct 300,000.00 0.00 2021-08-30 2021-09-14 2022-01-03 2024-01-03 upport ntation ehold Connection program in Nacala FIPAG/WASISII/CON-64/21 / Consultancy services for pre Component 2: Institutional S Individual Consult paration and installation the IDA / D1100 Post Limited 40,000.00 59,100.00 Signed 2021-09-16 2021-06-14 2021-09-21 2021-07-14 2021-10-12 2021-09-10 2021-11-16 2021-12-01 2022-05-15 upport ant Selection platform for manage the Grie vance Redress Mechanism (G RM) FIPAG/WASISII/CON-61/21 / I Component 3: Output-Based Individual Consult ndependent Monitoring and IDA / D1100 Payments for Low-Income-H Post Open 100,000.00 0.00 Canceled 2021-09-28 2021-12-15 2021-11-16 2022-07-06 2021-12-07 2022-09-30 2022-01-11 2024-06-21 ant Selection Verification Agent – Pemba a ousehold Connections nd Nacala /FIPAG/WASISII/CON-62/21 / I Component 3: Output-Based Individual Consult ndependent Monitoring and IDA / D1100 Payments for Low-Income-H Post Open 100,000.00 0.00 Signed 2021-09-28 2021-12-17 2021-11-16 2022-07-06 2021-12-07 2022-09-29 2022-01-11 2024-06-21 ant Selection Verification Agent – Tete and ousehold Connections Moatize FIPAG/WASISII/CON-63/21 / I Component 3: Output-Based Individual Consult ndependent Monitoring and IDA / D1100 Payments for Low-Income-H Post Open 100,000.00 0.00 Signed 2021-09-28 2021-12-17 2021-11-16 2022-07-04 2021-12-07 2022-08-23 2022-01-11 2024-06-21 ant Selection Verification Agent – Beira an ousehold Connections d Dondo FIPAG/WASISII/CON-65/21 / Annual Independent Environ Component 2: Institutional S Individual Consult IDA / D1100 Post Open 160,000.00 198,100.00 Signed 2021-12-10 2021-12-24 2022-01-28 2022-03-07 2022-02-18 2022-04-21 2022-03-25 2022-06-26 2022-09-21 mental and Social Audit for upport ant Selection WASIS II Project (2022-2024). FIPAG/WASISII/CON-66/21 / Component 2: Institutional S Individual Consult Under Implement IDA / D1100 Prior Open 350,000.00 0.00 2021-12-31 2022-01-09 2022-02-18 2022-07-04 2022-03-11 2022-08-03 2022-04-15 2024-04-15 Contract Management Adviso upport ant Selection ation r FIPAG/WASISII/CON-68/22 / P Component 2: Institutional S Individual Consult IDA / D1100 Prior Direct 90,000.00 78,300.00 Signed 2022-03-14 2022-03-15 2022-03-24 2022-04-20 2022-04-14 2022-04-29 2022-05-19 2022-05-13 2022-11-15 rocurement Assistant upport ant Selection FIPAG/WASISII/CON-71/22 / P REPARATION AND IMPLEMEN Component 2: Institutional S Individual Consult Open - Internationa IDA / D1100 Post 120,000.00 0.00 Signed 2022-08-05 2022-09-19 2022-09-23 2023-01-19 2022-10-14 2023-03-08 2022-11-18 2023-05-17 TATION OF THE ABBREVIATE upport ant Selection l D RESETTLEMENT ACTION PL AN (ARAP) IN NACALA FIPAG/WASISII/CON-72/22 / S Component 2: Institutional S Individual Consult Open - Internationa IDA / D1100 Post 100,000.00 0.00 Signed 2022-09-09 2022-09-09 2022-10-28 2022-11-04 2022-11-18 2022-11-22 2022-12-23 2023-04-14 ecurity Risk Assessment Con upport ant Selection l sultant FIPAG/WASISII/CON-73/22 / S Component 2: Institutional S Individual Consult Open - Internationa ecurity Risk Assessment Man IDA / D1100 Post 100,000.00 0.00 Signed 2022-09-09 2022-09-09 2022-10-28 2023-01-23 2022-11-18 2023-01-26 2022-12-23 2023-12-21 upport ant Selection l agement Specialist FIPAG/WASISII/CON-74/23 / I Component 3: Output-Based Individual Consult Under Implement ndependent Monitoring and IDA / D1100 Payments for Low-Income-H Post Open - National 100,000.00 0.00 2023-02-06 2023-02-05 2023-03-27 2023-04-17 2023-05-22 2023-11-18 ant Selection ation Verification Agent – Pemba a ousehold Connections nd Nacala FIPAG/WASISII/CON-76/23 / I ndependent Verification Age Component 3: Output-Based nt (IVA) for Auditing the Impl Individual Consult Under Implement IDA / D1100 Payments for Low-Income-H Post Limited 60,000.00 0.00 2023-06-01 2023-06-23 2023-06-06 2023-06-27 2023-08-01 2024-01-28 ementation of Performance-B ant Selection ation ousehold Connections ased Grants Program (PBGP) at Northern and Centre Regio nal Utilities. Page 5 FIPAG/WASISII/CON-77/23 / I ndependent Verification Age Component 3: Output-Based nt (IVA) for Auditing the Impl Individual Consult Under Implement IDA / D1100 Payments for Low-Income-H Post Limited 40,000.00 0.00 2023-06-01 2023-06-23 2023-06-06 2023-06-27 2023-08-01 2024-01-28 ementation of Performance-B ant Selection ation ousehold Connections ased Grants Program (PBGP) at Southern and Great Maput o Regional Utilities FIPAG/WASISII/CON-5/15 / Su Component 2: Institutional S Individual Consult pervision for construction of IDA / D1100 Post Open 80,000.00 51,420.00 Signed 2017-01-16 2017-05-17 2017-04-24 2017-08-02 2017-06-12 2017-12-06 2017-08-02 2018-01-22 2019-02-26 upport ant Selection boreholes in Pemba Page 6 Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_500,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of Procurement Regulations. Other Conditions: 1. Irrespective of the contract value, the following procurement activities are subject to the Bank’s procurement prior review: a. procurement processes involving contract negotiations as, described in paragraphs 6.34-36 of Section VI of the Procurement Regulation for Borrowers; b. competitive dialogue; c. sustainable procurement; and d. best and final offer. 2. Use of Standard Procurement Documents: For all procurements under the project, the Bank’s Standard Procurement Documents (or other Model Procurement Documents agreed with the Bank) shall be used. 3. Request for Bids (Open-National), if allowed in the Procurement Plan, will be carried out under the Bank’s Procurement Regulations following procedures for Open Tendering Method (OTM) of the People’s Republic of Bangladesh (Public Procurement Act 2006 - PPA, 1st amendment to PPA (2009) and The Public Procurement Rules 2008, as amended in August 2009) using standard/model bidding documents satisfactory to the Bank. For the purpose of Request for Bids (Open-National) the following shall apply: a. Post bidding negotiations shall not be allowed with the lowest evaluated or any other bidder; b. Bids should be submitted and opened in public in one location immediately after the deadline for submission; c. Lottery in award of contracts shall not be allowed; d. Bidders’ qualification/experience requirement shall be mandatory; e. Bids shall not be invited or rejected on the basis of percentage above or below the estimated cost. PROCUREMENT Bangladesh : Rural Electrification and Renewable Energy Development II (RERED II) Project PLAN General Information Country: Bangladesh 2017-07-28 Bank’s Approval Date of the Original Procurement Plan: 2023-06-07 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P131263 GPN Date: Project Name: Rural Electrification and Renewable Energy Development II (RERED II) Project Loan / Credit No: IDA / 51580, IDA / 55140, TF / 15034, IDA / 62020 Infrastructure Development Company Limited Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned W-01 UNDER REREDII-AFII / Single Stage - One E Pending Imp 2021-03-0 Civil Work Construction of th IDA / 62020 Sector Technical Assistance Post Request for Bids Open - National 4,000,000.00 0.00 2019-06-13 2019-06-16 2019-07-16 2019-08-15 2019-09-12 nvelope lementation 5 e New Office Building of IDC OL W-01 UNDER REREDP-II AF / Single Stage - One E 2020-05-1 Shore Piling work of the New IDA / 55140 Sector Technical Assistance Post Request for Bids Open - National 551,250.00 401,298.26 Terminated 2019-08-01 2019-10-07 2019-08-06 2021-02-07 2019-09-17 2019-10-28 2019-10-17 2019-12-01 2019-11-21 2020-01-03 nvelope 9 Office Building of IDCOL GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual G-16 UNDER GPOBA-II FOR R EREDPII / Procurement of 1,0 Request for Quota Single Stage - One E 00 Pcs of Construction Manu IDA / 51580 Household Energy Post Limited 1,200.00 619.86 Completed 2017-10-18 2017-09-21 2017-10-25 2017-09-26 2017-11-06 2017-10-08 tions nvelope als under IDCOL Biogas progr am (Package No.: G-16 under GPOBAII) G-08 UNDER REREDP-II AF / Procurement of 2 Pcs of Onli Request for Quota Single Stage - One E IDA / 55140 Access to Electricity Post Limited 2,565.00 2,127.79 Completed 2017-10-31 2017-10-24 2017-11-09 2017-10-31 2017-11-16 2017-11-28 ne Energy Meters under IDC tions nvelope OL Other RE program G-09-REREDII-AF AND G-57- Single Stage - One E REREDII / Procurement of 22 IDA / 51580 Access to Electricity Post Request for Bids Open - National 55,000.00 46,716.39 Completed 2017-11-28 2017-12-19 2017-11-29 2017-12-21 2017-12-20 2018-01-11 2018-01-19 2018-02-04 2018-02-04 2018-03-01 2018-03-06 2018-04-04 nvelope units of Motorcycles for IDCO L G-18 UNDER GPOBA-II FOR R Request for Quota Single Stage - One E EREDPII / Procurement of 6 u IDA / 51580 Household Energy Post Limited 75.00 0.00 Canceled 2017-12-29 2018-01-08 2018-01-23 tions nvelope nits of toolkit for IDCOL Bio-g as Program G-56 UNDER REREDP-II / Prin Single Stage - One E ting and Supply of 100,000 P IDA / 51580 Household Energy Post Request for Bids Open - National 25,000.00 22,809.43 Completed 2017-11-28 2017-11-29 2017-12-21 2017-12-20 2018-01-11 2018-01-19 2018-01-31 2018-02-04 2018-02-25 2018-03-06 2018-03-20 nvelope cs Calendar for IDCOL ICS Pr ogram. G-11 UNDER REREDP-II AF / Procurement of 10 units of C Request for Quota Single Stage - One E IDA / 55140 Access to Electricity Post Limited 6,282.01 5,911.85 Completed 2018-01-10 2018-01-28 2018-01-21 2018-02-04 2018-01-28 2018-02-08 PU and 13 units of monitor fo tions nvelope r IDCOL HO and RE office G-19 UNDER GPOBA-II / Sup Request for Quota Single Stage - One E ply of Biogas stoves for IDCO IDA / 51580 Household Energy Post Limited 28,750.00 25,032.78 Completed 2018-05-24 2018-05-27 2018-05-31 2018-06-03 2018-06-30 2018-06-28 tions nvelope L Biogas & Bio-fertilizer Progr am. G-20 UNDER GPOBA-II / Sup Request for Quota Single Stage - One E ply of equipment for the Tec IDA / 51580 Household Energy Post Open - National 8,250.00 7,782.60 Completed 2018-06-05 2018-06-13 2018-06-14 2018-06-25 2018-06-28 tions nvelope hnical Monitoring Facility of I DCOL. G-21 UNDER GPOBA-II / Sup ply and fixation of furniture, f Request for Quota Single Stage - One E IDA / 51580 Household Energy Post Limited 36,880.00 25,588.37 Terminated 2018-07-12 2018-06-14 2018-07-19 2018-06-21 2018-07-26 ixture and equipment for IDC tions nvelope OL (17th floor-North). G-22 UNDER GPOBA-II / Sup Request for Quota Single Stage - One E ply of refrigerator for the Tec IDA / 51580 Household Energy Post Limited 1,880.00 990.77 Completed 2018-07-12 2018-05-24 2018-07-20 2018-06-03 2018-07-27 2018-06-06 tions nvelope hnical Monitoring Facilty of I DCOL G-05 UNDER USAID / Procure ment of 30 unit IP Phones, 10 Request for Quota Single Stage - One E TF / 15034 Access to Electricity Post Limited 2,812.00 2,602.48 Completed 2018-09-24 2018-09-25 2018-10-02 2018-10-01 2018-10-09 2018-10-04 unit network switch and 1 bo tions nvelope x CAT6 UTP cable for new reg ional offices of IDCOL G-06 UNDER USAID / Procure Request for Quota Single Stage - One E ment of 5 unit of LASER print TF / 15034 Access to Electricity Post Limited 4,687.00 3,006.91 Completed 2018-09-24 2018-09-25 2018-10-03 2018-09-30 2018-10-10 2018-09-30 tions nvelope ers for new regional offices o f IDCOL G-13 UNDER REREDII-AF / Su Request for Quota Single Stage - One E IDA / 55140 Access to Electricity Post Limited 5,250.00 3,433.07 Completed 2018-07-12 2018-07-12 2018-07-19 2018-07-19 2018-07-26 2018-07-25 pply of 3 unit of laser printer tions nvelope s for IDCOL G-14 UNDER REREDII-AF / Su Request for Quota Single Stage - One E pply of Batteries for Online U IDA / 55140 Access to Electricity Post Limited 5,750.00 4,985.58 Completed 2018-07-12 2018-07-26 2018-07-19 2018-08-02 2018-07-26 2018-08-11 tions nvelope PS and IPS of IDCOL G-09 UNDER REREDII-AFII / S upply of furniture, fixture and Single Stage - One E Pending Impl IDA / 55140 Sector Technical Assistance Post Request for Bids Open - National 1,262,500.00 0.00 2020-08-24 2020-08-29 2020-09-26 2020-10-26 2020-11-23 2021-05-22 office equipment for the new nvelope ementation office building of IDCOL G-15 UNDER REREDII-AF / Su Request for Quota Single Stage - One E pply and installation of Docu IDA / 55140 Access to Electricity Post Limited 6,875.00 5,545.59 Completed 2018-11-01 2018-11-09 2018-10-23 2018-11-16 2018-11-07 tions nvelope Dex server for IDCOL G-24 UNDER GPOBA-II / Sup Request for Quota Single Stage - One E ply of furniture, fixture and of IDA / 51580 Access to Electricity Post Limited 6,125.00 5,736.87 Completed 2018-11-01 2018-05-08 2018-11-11 2018-05-17 2018-11-18 2018-05-27 tions nvelope fice equipment in IDCOL Dha ka RO G-16 UNDER REREDP-II AF / Single Stage - One E Supply of thirty (30) units De IDA / 55140 Access to Electricity Post Request for Bids Open - National 18,750.00 19,016.42 Completed 2018-12-09 2019-01-10 2018-12-10 2019-01-09 2019-01-24 2019-02-04 2019-02-11 2019-03-07 2019-02-27 2019-03-22 2019-03-08 nvelope sktop Computer for IDCOL e mployees Page 1 G-06 UNDER REREDP-II AFII / Single Stage - One E Supply of Equipment (Phase- IDA / 62020 Access to Electricity Post Request for Bids Open - National 220,000.00 102,954.20 Completed 2018-12-09 2019-11-26 2018-12-10 2019-01-09 2019-12-10 2019-02-10 2020-02-18 2019-03-17 2020-06-16 2019-05-16 2021-01-12 nvelope 02) for IDCOL Technical Moni toring Facilities G-17 UNDER REREDP-II AF / Request for Quota Single Stage - One E Supply of two (02) units PoE IDA / 55140 Access to Electricity Post Limited 2,375.00 1,786.53 Completed 2018-12-10 2018-12-13 2018-12-19 2018-12-24 2018-12-26 2018-12-28 tions nvelope Switch & two (02) units Laser Printer for IDCOL G-23 UNDER GPOBA-II / Sup Request for Quota Single Stage - One E IDA / 51580 Household Energy Post Limited 875.00 643.70 Completed 2018-07-12 2018-06-05 2018-07-19 2018-06-14 2018-07-26 2018-06-24 ply of rechargeable table fan tions nvelope s for IDCOL. G-10 UNDER REREDP-II AF II / Framework Agreement for S Single Stage - One E IDA / 62020 Access to Electricity Post Request for Bids Open - National 71,822.63 0.00 Canceled 2018-12-26 2018-12-27 2019-01-17 2019-02-17 2019-03-19 2020-03-18 upply of Toners and Mainten nvelope ance Kit for printers of IDCOL G-11 UNDER REREDP-II AF II Single Stage - One E / Framework Agreement for S IDA / 62020 Access to Electricity Post Request for Bids Open - National 14,908.25 0.00 Canceled 2018-12-26 2018-12-27 2019-01-17 2019-02-17 2019-03-19 2020-03-18 nvelope upply of Stationary for IDCOL G-12 UNDER REREDII-AF-II / Supply of 190 units of Micros Request for Quota Single Stage - One E oft Exchange Online Plan-1 ( IDA / 62020 Access to Electricity Post Limited 10,000.00 8,410.98 Completed 2019-01-15 2019-01-13 2019-01-21 2019-01-22 2019-01-29 2019-02-01 tions nvelope EOP-1) & Office 365 Enterpris e E1 subscription license for I DCOL G-18 UNDER REREDP-II AF / Selection of Firm for Printing Request for Quota Single Stage - One E IDA / 55140 Household Energy Post Limited 1,062.50 0.00 Canceled 2019-04-04 2019-04-10 2019-04-30 Leaflet & Manuals for IDCOL tions nvelope Biogas & Bio-fertilizer progra m G-12 UNDER REREDP-II AF-II Single Stage - One E / Printing and Supply of 240, IDA / 62020 Household Energy Post Request for Bids Open - National 60,000.00 50,768.69 Completed 2019-03-04 2019-03-20 2019-03-09 2019-03-31 2019-04-04 2019-04-09 2019-04-21 2019-05-14 2019-05-19 2019-06-13 2019-06-10 nvelope 000 pcs of Calender for IDCO L ICS Program G-19 UNDER REREDP-II AF / Supply of Arsenic Kit for testi Request for Quota Single Stage - One E ng the arsenic level in potent IDA / 55140 Access to Electricity Post Limited 2,812.50 2,464.07 Completed 2019-03-26 2019-03-28 2019-04-21 2019-04-08 2019-05-02 2019-04-22 tions nvelope ial Solar Irrigation Pump Proj ect sites by IDCOL inspectors G-13 UNDER REREDP-II AF-II / Supply of thirty paper licens e of MS Office 2019 (standar Request for Quota Single Stage - One E IDA / 62020 Access to Electricity Post Limited 28,750.00 21,726.40 Completed 2019-03-29 2019-04-04 2019-04-18 2019-04-17 2019-04-30 2019-07-22 d), thirty paper license of Wi tions nvelope ndows 10 pro and Security fir ewall with UTM for 300 users of IDCOL HO & RE office G-14 UNDER REREDP-II AF-II / Supply of 120 SFT Roller Bli Request for Quota Single Stage - One E IDA / 62020 Access to Electricity Post Limited 6,125.00 2,860.00 Completed 2019-04-02 2019-04-02 2019-04-11 2019-04-11 2019-04-18 2019-04-19 nds Fabrics & 22 pcs Executi tions nvelope ve Chair for IDCOL HO 17 Flo or G-20 UNDER REREDP-II AF / Supply of 30 television and 3 0 refrigerators for disseminat IDA / 55140 Access to Electricity Post Direct Selection Direct 18,750.00 0.00 Canceled 2019-04-01 2019-04-02 2019-04-07 2019-04-11 ion in different solar mini-gri d project sites for demonstra tion of energy efficient applia nces G-15 UNDER REREDP-II AF-II Request for Quota Single Stage - One E / Supply of Attendance Devic IDA / 62020 Access to Electricity Post Limited 7,437.50 5,163.34 Completed 2019-05-05 2019-05-06 2019-05-13 2019-05-28 2019-05-20 2019-06-28 tions nvelope e for IDCOL Regional Offices G-21 UNDER REREDP-II AF / Supply of 02 units Hard Disk IDA / 55140 Access to Electricity Post Direct Selection Direct 875.00 862.91 Completed 2019-05-29 2019-02-25 2019-05-30 2019-02-26 2019-06-09 2019-03-04 2019-06-11 2019-03-08 for IBA system X3650 M4 Ser ver G-16 UNDER REREDP II AF II Request for Quota Single Stage - One E / Supply of 01 unit 6KVA onli IDA / 62020 Access to Electricity Post Limited 4,375.00 2,907.70 Completed 2019-06-09 2019-06-17 2019-06-20 2019-06-28 2019-06-30 2019-07-08 tions nvelope ne UPS for server room of ID COL Dhaka RO G-17 UNDER RERED-II-AF-II / Request for Quota Single Stage - One E Printing and Supply of Biogas IDA / 62020 Household Energy Post Limited 6,875.00 3,473.42 Completed 2019-06-24 2019-06-18 2019-07-02 2019-07-16 2019-07-09 2019-09-05 tions nvelope Manuals for IDCOL G-18 UNDER REREDP-II AFII / Single Stage - One E Supply of 20 Motorcycles for IDA / 62020 Access to Electricity Post Request for Bids Open - National 45,000.00 0.00 Canceled 2019-08-29 2019-09-03 2019-09-24 2019-11-07 2019-11-28 2019-12-29 nvelope new regional managers G-19 UNDER REREDP-II AFII / Request for Quota Single Stage - One E IDA / 62020 Access to Electricity Post Limited 2,406.25 1,609.76 Completed 2019-08-22 2019-08-19 2019-09-02 2019-08-27 2019-09-09 2019-08-30 Supply of 35 units IP Phones tions nvelope G-20 UNDER REREDP-II AFII / Request for Quota Single Stage - One E IDA / 62020 Access to Electricity Post Limited 9,225.00 6,720.92 Completed 2019-08-04 2019-10-13 2019-08-19 2019-10-18 2019-08-26 2019-11-01 Supply of 41 units IPS Batter tions nvelope y G-21 UNDER REREDP-II AFII / Request for Quota Single Stage - One E Supply of 254 units of mobile IDA / 62020 Access to Electricity Post Limited 41,275.00 0.00 Canceled 2019-08-05 2019-08-27 2019-09-03 tions nvelope phones for field staffs G-22 UNDER REREDP-II AFII / Request for Quota Single Stage - One E Supply of 7 units Laptops for IDA / 62020 Access to Electricity Post Limited 6,125.00 5,671.33 Completed 2019-08-08 2019-08-22 2019-08-24 2019-08-28 2019-08-31 2019-08-31 tions nvelope IDCOL HO employees G-23 UNDER REREDP-II AFII / Request for Quota Single Stage - One E IDA / 62020 Access to Electricity Post Limited 1,875.00 1,400.44 Completed 2019-08-19 2019-09-29 2019-08-27 2019-10-06 2019-09-03 2019-10-10 Supply of 25 units IP Camera tions nvelope G-24 UNDER REREDP-II AFII / Request for Quota Single Stage - One E IDA / 62020 Access to Electricity Post Limited 312.50 0.00 Canceled 2019-08-26 2019-09-03 2019-09-10 Supply of 10 pcs Analog Hydr tions nvelope ometer G-25 UNDER REREDP-II AFII / Request for Quota Single Stage - One E IDA / 62020 Access to Electricity Post Limited 6,250.00 0.00 Canceled 2019-09-09 2019-09-17 2019-09-24 Supply of 2 pcs Digital Batter tions nvelope y Tester G-22 UNDER REREDP-II / Sup Request for Quota Single Stage - One E ply of 40 units Tablet for tech IDA / 62020 Access to Electricity Post Limited 7,500.00 0.00 Canceled 2019-10-03 2019-10-14 2019-10-21 tions nvelope nical inspectors G-23 UNDER REREDP-II AF / Request for Quota Single Stage - One E IDA / 55140 Access to Electricity Post Limited 10,275.00 0.00 Canceled 2019-09-02 2019-09-10 2019-09-18 Supply of 137 units Multimet tions nvelope er Page 2 G-24 UNDER REREDP-II AF / Supply of 05 units Printers, 1 Request for Quota Single Stage - One E IDA / 55140 Access to Electricity Post Limited 16,500.00 12,689.43 Completed 2019-08-04 2019-08-25 2019-08-19 2019-09-02 2019-08-29 2019-09-04 unit Photocopier Machine an tions nvelope d 03 units Projectors G-25 UNDER REREDP-II AF / Request for Quota Single Stage - One E Supply of 01 unit attendance IDA / 55140 Access to Electricity Post Limited 875.00 706.40 Completed 2019-08-04 2019-08-05 2019-08-08 2019-08-22 2019-08-18 2019-09-01 tions nvelope device for IDCOL office space G-28 UNDER REREDP-II AF / Single Stage - One E Selection of firm for Supply & IDA / 55140 Access to Electricity Post Request for Bids Open - National 60,625.00 47,843.34 Completed 2019-10-24 2019-11-26 2019-10-29 2019-11-19 2019-12-18 2019-12-19 2020-02-18 2020-01-23 2020-06-18 2020-02-22 2020-10-12 nvelope Installation of VRF AC G-26 UNDER REREDP-II AF / Request for Quota Single Stage - One E Supply of 07 (seven) units La IDA / 55140 Access to Electricity Post Limited 4,500.00 4,220.95 Completed 2019-10-03 2018-07-31 2019-10-09 2018-08-03 2019-10-16 2018-08-07 tions nvelope ptop for IDCOL officials G-27 UNDER REREDP-II AF / Request for Quota Single Stage - One E Supply and Installation of 03 IDA / 55140 Access to Electricity Post Limited 4,250.00 2,942.91 Completed 2019-10-03 2018-07-31 2019-10-09 2018-08-06 2019-10-16 2018-08-09 tions nvelope units IPS with Batteries for ID COL G-29 UNDER REREDP II AF / Supply of nine units 2KVA IPS Request for Quota Single Stage - One E IDA / 55140 Access to Electricity Post Limited 7,875.00 7,058.20 Completed 2019-11-28 2020-02-19 2019-12-05 2020-03-02 2019-12-15 2020-03-11 with maintenance-free batter tions nvelope y for new IDCOL Regional Offi ces G-26 UNDER REREDP-II AF II Request for Quota Single Stage - One E / Printing of 30,000 pcs New IDA / 62020 Household Energy Post Limited 6,125.00 6,619.67 Completed 2019-12-12 2019-12-08 2019-12-20 2019-12-13 2019-12-27 2019-12-30 tions nvelope Year Calendars for IDCOL Bio gas Program G-27 UNDER REREDP-II AF II Request for Quota Single Stage - One E / Printing of 200,000 pcs of le IDA / 62020 Household Energy Post Limited 3,750.00 4,033.26 Completed 2019-12-16 2019-12-23 2019-12-24 2019-12-30 2020-01-03 2020-01-10 tions nvelope aflets for IDCOL Biogas Progr am G-28 UNDER REREDP-II-AF-II Request for Quota Single Stage - One E / Printing and Supply of 5000 IDA / 62020 Access to Electricity Post Limited 1,875.00 0.00 Canceled 2020-03-02 2020-03-09 2020-03-16 tions nvelope Pcs of Brochures for SIP G-29 UNDER REREDII-AFII / S upply and Installation of 1 un IDA / 62020 Access to Electricity Post Direct Selection Direct 288.00 0.00 Canceled 2020-03-05 2020-03-08 2020-03-11 2020-03-18 it of Attendance Device for ID COL G-30 UNDER REREDII-AFII / P Single Stage - One E rinting & Supply of 300000 P IDA / 62020 Household Energy Post Request for Bids Open - National 75,000.00 0.00 Canceled 2020-03-08 2020-03-08 2020-03-22 2020-04-21 2020-05-26 2020-06-25 nvelope cs of Calendars for IDCOL ICS Program G-31 UNDER REREDII-AFII / P Single Stage - One E rinting and Supply of Books o IDA / 62020 Household Energy Post Request for Bids Open - National 31,250.00 0.00 Canceled 2020-04-15 2020-04-16 2020-05-07 2020-06-06 2020-07-11 2020-08-20 nvelope n R&D Activities of Renewabl e Energy of IDCOL G-30 UNDER REREDII-AF / Su Request for Quota Single Stage - One E IDA / 55140 Access to Electricity Post Limited 9,125.00 7,573.94 Completed 2020-08-17 2020-08-18 2020-08-22 2020-08-27 2020-08-27 2020-09-03 pply of 10 units of Laptop for tions nvelope IDCOL G-32 UNDER REREDP-II AF-II Request for Quota Single Stage - One E / Supply of Video Conferencin IDA / 62020 Access to Electricity Post Limited 10,000.00 0.00 Canceled 2020-09-06 2020-11-01 2020-12-01 tions nvelope g Equipment G-33 UNDER REREDP-II AF II Single Stage - One E / Supply of 2,790 pcs signage IDA / 62020 Household Energy Post Request for Bids Open - National 89,063.00 97,449.34 Signed 2020-09-27 2020-10-04 2020-10-04 2021-09-13 2020-10-18 2020-10-25 2020-11-17 2021-01-11 2020-12-22 2021-03-01 2021-06-20 nvelope for IDCOL ICS Program (3 Lot s) G-34 UNDER REREDP-II AF II Single Stage - One E Pending Impl / Printing of 300,000 pcs Cale IDA / 62020 Household Energy Post Request for Bids Open - National 62,500.00 0.00 2020-09-27 2020-10-04 2020-10-18 2020-11-17 2020-12-22 2021-01-06 nvelope ementation ndars for IDCOL ICS Program G-35 UNDER REREDP-II AF II Request for Quota Single Stage - One E / Supply of 2,500 pcs cap for IDA / 62020 Household Energy Post Limited 2,344.00 0.00 Canceled 2020-10-06 2020-10-18 2020-11-02 tions nvelope IDCOL ICS Program G-36 UNDER REREDP-II AF II Request for Quota Single Stage - One E / Supply of 750 pcs bag for ID IDA / 62020 Household Energy Post Limited 7,031.00 4,342.72 Completed 2020-10-09 2021-02-15 2020-10-21 2021-02-26 2020-11-05 2021-03-01 tions nvelope COL ICS Program G-37 UNDER REREDP-II AF II Request for Quota Single Stage - One E / Supply of 2,500 pcs T-shirt f IDA / 62020 Household Energy Post Limited 7,813.00 4,021.16 Completed 2020-10-23 2020-12-27 2020-11-03 2021-01-12 2020-12-03 2021-02-10 tions nvelope or IDCOL ICS Program G-39 UNDER REREDP-II AF II Single Stage - One E IDA / 62020 Access to Electricity Post Request for Bids Open - National 64,375.00 0.00 Canceled 2020-11-18 2020-11-23 2020-12-07 2021-01-06 2021-02-10 2021-03-12 / Supply of 93 units Desktop nvelope Computer G-31 UNDER REREDP-II AF / Request for Quota Single Stage - One E Supply of 40 units IP phones IDA / 55140 Access to Electricity Post Limited 11,125.00 0.00 Canceled 2020-10-06 2020-10-20 2020-11-04 tions nvelope & 7 units switch G-32 UNDER REREDP-II AF / Request for Quota Single Stage - One E Supply of 2 units projector & IDA / 55140 Access to Electricity Post Limited 9,000.00 3,939.73 Completed 2020-11-23 2021-03-23 2020-12-06 2021-03-30 2020-12-21 2021-04-05 tions nvelope 7 units scanner G-41 UNDER REREDP-II AF II Request for Quota Single Stage - One E Pending Impl IDA / 62020 Access to Electricity Post Limited 10,500.00 0.00 2020-11-06 2020-11-19 2020-12-04 / Supply of 200 units MS Exc tions nvelope ementation hange online G-33 UNDER REREDP-II AF / Request for Quota Single Stage - One E Pending Impl IDA / 55140 Access to Electricity Post Limited 20,000.00 0.00 2020-10-11 2020-10-24 2020-11-23 Supply of 2 units server tions nvelope ementation G-44 UNDER REREDP-II AF-II Request for Quota Single Stage - One E / Supply of 180 units MS EOP- IDA / 62020 Access to Electricity Post Limited 10,625.00 8,576.57 Completed 2021-02-01 2020-01-09 2021-02-07 2020-01-16 2021-02-22 2020-01-29 tions nvelope 1 License and 10 units MS Of fice 365 E-1 G-45 UNDER REREDII-AFII / P Request for Quota Single Stage - One E rinting and Supply of Books o IDA / 62020 Household Energy Post Open - National 12,500.00 3,009.97 Completed 2021-06-10 2021-06-19 2021-08-27 2021-07-01 2021-11-04 tions nvelope n R&D Activities of Renewabl e Energy of IDCOL G-46 UNDER REREDP-II AF-II / Supply of 6KVA online UPS, Request for Quota Single Stage - One E IDA / 62020 Access to Electricity Post Limited 5,750.00 5,387.36 Completed 2021-08-23 2021-09-15 2021-09-16 2021-09-21 2021-09-26 2021-09-24 battery, cabinet, installation tions nvelope with all related accessories Page 3 G-47 UNDER REREDP-II AF-II Request for Quota Single Stage - One E Pending Impl / Supply of 20 Desktop PC for IDA / 62020 Access to Electricity Post Open - National 15,125.00 0.00 2021-09-06 2021-10-05 2021-10-20 tions nvelope ementation IDCOL HO & RE G-48 UNDER REREDP-II AF-II Request for Quota Single Stage - One E IDA / 62020 Access to Electricity Post Limited 10,000.00 7,114.88 Completed 2021-08-27 2021-08-29 2021-09-11 2021-09-08 2021-09-18 2021-09-22 / Supply of 07 printers for ID tions nvelope COL G-49 UNDER REREDP-II AF-II Request for Quota Single Stage - One E IDA / 62020 Access to Electricity Post Limited 15,000.00 9,337.49 Completed 2021-08-31 2021-08-29 2021-09-27 2021-09-08 2021-10-27 2021-09-09 / Supply of 02 units photocop tions nvelope ier machine G-50 UNDER REREDP-II AF II Request for Quota Single Stage - One E IDA / 62020 Household Energy Post Limited 5,500.00 3,860.66 Completed 2021-10-08 2021-10-14 2021-10-18 2021-10-20 2021-11-17 2021-10-25 / Supply of Kaspersky Antivir tions nvelope us Licenses G-38 UNDER REREDP-II AF II Single Stage - One E Under Imple / Supply of Leaflets and User IDA / 62020 Household Energy Post Request for Bids Open - National 72,500.00 0.00 2020-11-05 2022-04-13 2020-11-10 2022-09-01 2020-12-22 2022-05-09 2021-01-21 2022-07-26 2021-02-25 2021-03-27 nvelope mentation Manuals for IDCOL ICS Progra m G-51 UNDER REREDP-II AF II Request for Quota Single Stage - One E / Supply of umbrellas for IDC IDA / 62020 Household Energy Post Limited 11,250.00 7,059.03 Completed 2021-11-05 2021-12-12 2021-11-17 2022-01-07 2021-12-02 2022-02-01 tions nvelope OL ICS Program G-52 UNDER REREDP-II AF II Single Stage - One E Under Imple / Supply of Mic with Amplifier IDA / 62020 Household Energy Post Request for Bids Open - National 40,500.00 0.00 2021-11-01 2022-04-13 2021-11-06 2022-05-10 2021-11-20 2021-12-20 2022-01-13 2022-02-12 nvelope mentation for IDCOL ICS Program G-53 UNDER REREDP-II AF II Request for Quota Single Stage - One E Pending Impl / Supply of Laptop for IDCOL IDA / 62020 Access to Electricity Post Limited 3,000.00 0.00 2021-12-06 2021-12-26 2022-01-10 tions nvelope ementation Regional Offices G-54 UNDER REREDP-II AF II Request for Quota Single Stage - One E Pending Impl IDA / 62020 Access to Electricity Post Limited 5,250.00 0.00 2021-10-31 2021-11-18 2021-11-25 / Supply of attendance devic tions nvelope ementation es for IDCOL G-42 UNDER REREDP-II AF II Request for Quota Single Stage - One E IDA / 62020 Access to Electricity Post Limited 5,400.00 3,181.69 Completed 2020-11-30 2021-12-22 2020-12-13 2022-01-07 2020-12-28 2022-01-13 / Supply of MS Office 365 lice tions nvelope nses G-40 UNDER REREDP-II AF II Request for Quota Single Stage - One E Under Imple IDA / 62020 Access to Electricity Post Limited 48,750.00 0.00 2020-11-09 2022-10-24 2020-11-22 2020-12-07 / Supply of Windows 11 for ID tions nvelope mentation COL G-43 UNDER REREDP-II AF II / Lot 1: Supply of 01 unit MS Request for Quota Single Stage - One E Under Imple windows server 2019 standar IDA / 62020 Household Energy Post Limited 36,250.00 0.00 2020-11-16 2021-12-30 2020-11-29 2020-12-14 tions nvelope mentation d Lot 2: Supply of 02 units MS SQL Server 2019 enterprise G-55 UNDER REREDP-II AF-II Request for Quota Single Stage - One E IDA / 62020 Household Energy Post Limited 8,200.00 5,969.68 Completed 2021-12-12 2022-01-26 2022-01-02 2022-02-09 2022-01-17 2022-02-28 / Supply of batteries for IPS tions nvelope G-56 UNDER REREDP-II AF II Request for Quota Single Stage - One E / Supply of PoE Switch for ID IDA / 62020 Household Energy Post Limited 1,500.00 1,290.71 Completed 2021-12-12 2021-12-26 2021-12-27 2022-01-07 2022-01-11 2022-01-25 tions nvelope COL Regional Offices G-57 UNDER REREDP-II AF II / Supply of 210 users MS 365 Request for Quota Single Stage - One E Business Basic, 10 users Offi IDA / 62020 Household Energy Post Limited 8,750.00 6,562.49 Completed 2022-01-16 2022-01-12 2022-01-28 2022-01-21 2022-02-04 2022-01-25 tions nvelope ce 365 EI & 10 users license of Exchange Online Archiving for IDCOL HO, RE & RO G-58 UNDER REREDP-II AF II / Supply of 6KVA Online UPS i Request for Quota Single Stage - One E Under Imple IDA / 62020 Access to Electricity Post Limited 4,375.00 0.00 2022-04-15 2022-05-08 2022-05-03 2022-06-02 ncluding battery for IDCOL D tions nvelope mentation haka Regional Office G-59 UNDER REREDP-II AF II Request for Quota Single Stage - One E Under Imple / Procurement of 02 (two) uni IDA / 62020 Household Energy Post Limited 13,000.00 0.00 2022-07-23 2022-08-03 2022-08-04 2023-01-31 tions nvelope mentation ts of 6KVA online ups with Ba ttery G-60 UNDER REREDP-II AF II Request for Quota Single Stage - One E Pending Impl IDA / 62020 Household Energy Post Limited 5,500.00 0.00 2022-08-26 2022-09-10 2023-03-09 / Supply of 10 (ten) units CIS tions nvelope ementation CO IP Phone G-61 UNDER REREDP-II AF II Request for Quota Single Stage - One E Under Imple IDA / 62020 Household Energy Post Limited 350.00 0.00 2022-08-29 2022-11-07 2022-09-18 2023-03-17 / Supply of IP Camera tions nvelope mentation G-62 UNDER REREDP-II AF II Request for Quota Single Stage - One E Under Imple / Supply of Physical server wi IDA / 62020 Household Energy Post Limited 16,250.00 0.00 2022-09-02 2022-11-03 2022-09-16 2023-03-15 tions nvelope mentation th Windows Server 2022 Sta ndard G-63 UNDER REREDP-II AF II Request for Quota Single Stage - One E Under Imple IDA / 62020 Household Energy Post Limited 6,000.00 0.00 2022-10-11 2022-10-10 2022-10-23 2022-10-31 / Renewal of Antivirus Licens tions nvelope mentation e 2022-23 G-64 UNDER REREDP-II AF II Request for Quota Single Stage - One E IDA / 62020 Household Energy Post Limited 4,500.00 0.00 Signed 2022-11-05 2022-11-09 2022-12-02 2023-05-31 / Procurement of Monitor tions nvelope G-65 UNDER REREDP II (AF II ) / Supply & Installation of 01 Request for Quota Single Stage - One E Pending Impl IDA / 55140 Sector Technical Assistance Post Limited 1,125.00 0.00 2023-01-05 2023-01-15 2024-01-15 (one) Unit Access Controller tions nvelope ementation and 05 (five) Units of IP Cam era for IDCOL Head Office G-66 UNDER REREDP II (AF II Request for Quota Single Stage - One E Pending Impl ) / Supply of 220 Units of Offi IDA / 62020 Household Energy Post Limited 31,250.00 0.00 2023-01-05 2023-01-11 2024-01-11 tions nvelope ementation ce 365 License for IDCOL G-67 UNDER REREDP II AF II / Supply of Arsenic Kits for te Request for Quota Single Stage - One E Pending Impl IDA / 62020 Access to Electricity Post Limited 2,400.00 0.00 2023-03-19 2023-03-28 2023-04-06 sting the arsenic level in the tions nvelope ementation potential solar irrigation proj ects of IDCOL NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NS-03 UNDER REREDPII-AF / Selection of Firm for Battery IDA / 55140 Access to Electricity Post Direct Selection Direct 20,000.00 38,145.18 Signed 2018-02-22 2018-01-10 2018-02-27 2018-01-16 2018-03-22 2018-02-01 2018-12-31 Testing under IDCOL Other R E Program (Package No.: NS- 03 under REREDPII-AF) Page 4 NS-05 UNDER REREDII-AFII / Selection of Firm for Collectin g Power Quality Data of Tran IDA / 62020 Access to Electricity Post Direct Selection Direct 5,000.00 4,768.15 Completed 2018-11-05 2018-11-05 2018-11-08 2018-11-08 2018-11-16 2018-12-04 2018-12-11 2019-01-03 smission Line of Two Power P lants of SEBL SMG Project-2 NS-06 UNDER REREDPII-AFII / Selection of Firm for providi IDA / 62020 Access to Electricity Post Direct Selection Direct 57,500.00 0.00 Canceled 2018-11-08 2018-11-12 2018-11-27 2019-11-27 ng Billboard Display Service t o promote IDCOL Programs a nd Projects CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual S-16 UNDER RERED-II-AF-II / Selection of firm for developi Consultant Qualifi ng the communication strate IDA / 62020 Household Energy Post Open - National 43,750.00 26,442.51 Completed 2018-06-24 2018-06-04 2018-07-09 2018-07-20 2018-08-16 2018-07-27 2018-10-24 2018-08-06 2018-11-20 2018-11-04 2019-10-29 cation Selection gy for IDCOL ICS program (pr ocurement method: CQS with Limited Market approach) S-06 UNDER USAID / Audit s ervices for solar Irrigation Pu Consultant Qualifi TF / 15034 Access to Electricity Post Open - National 50,000.00 44,992.22 Completed 2018-10-31 2018-10-07 2018-11-14 2021-10-05 2018-12-13 2019-01-03 2018-12-18 2019-01-31 2018-12-20 2019-02-11 2019-04-30 2022-03-17 mp (SIP) and solar Mini-Grid ( cation Selection SMG) sponsors of IDCOL S-21 UNDER REREDII-AFII / C onsulting firm for the interior Consultant Qualifi Pending Impleme IDA / 62020 Sector Technical Assistance Post Open - National 125,000.00 0.00 2020-04-05 2020-04-26 2020-06-14 2020-07-09 2020-07-29 2021-01-25 design and supervision of de cation Selection ntation coration of new office buildin g of IDCOL S-20 UNDER REREDII-AFII / A consulting firm for Architectu Consultant Qualifi IDA / 62020 Sector Technical Assistance Post Open - National 250,000.00 335,869.54 Signed 2018-11-20 2018-08-31 2018-12-10 2018-12-17 2019-01-09 2019-01-16 2019-05-15 2019-02-16 2019-06-24 2021-05-13 ral and Structural design and cation Selection work supervision of IDCOL's new office building S-24 UNDER REREDP-II AFII / Quality And Cost- Pending Impleme Selection of a firm for designi IDA / 62020 Access to Electricity Post Open - National 25,000.00 0.00 2019-10-01 2019-10-22 2019-11-26 2019-12-24 2020-01-08 2020-01-26 2020-03-01 2020-05-31 Based Selection ntation ng process flow automation o f IDCOL S-29 UNDER REREDP-II AF II Quality And Cost- / Selection of consultant for p IDA / 62020 Household Energy Post Open - National 250,000.00 0.00 Canceled 2021-12-15 2021-12-22 2022-01-05 2022-02-18 2022-03-18 2022-04-17 2022-05-22 2022-06-26 2024-06-25 Based Selection romoting IDCOL ICS Program S-31 UNDER REREDP-II AF II Quality And Cost- Open - Internationa Under Implement / Selection of Consultant for IDA / 62020 Household Energy Post 500,000.00 0.00 2022-10-11 2022-10-31 2022-10-16 2022-11-13 2022-12-25 2023-01-22 2023-02-21 2023-03-28 2023-05-02 2023-12-31 Based Selection l ation promoting IDCOL ICS Progra m S-32 UNDER REREDP-II AF II / Selection of consultant for fi Quality And Cost- Under Implement IDA / 62020 Household Energy Post Open - National 250,000.00 0.00 2022-10-12 2022-10-31 2022-11-02 2022-11-13 2022-12-16 2023-01-13 2023-02-12 2023-03-19 2023-04-23 2023-12-31 eld-level sales campaign und Based Selection ation er IDCOL ICS Program INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual S-11 UNDER GPOBA-II FOR R EREDPII / Selection of Individ Individual Consult ual Consultant for developme IDA / 51580 Household Energy Post Open 2,560.00 2,248.94 Completed 2017-12-10 2018-01-22 2018-01-04 2018-02-05 2018-01-11 2018-02-07 2018-01-28 2018-02-11 2018-02-27 2018-09-04 ant Selection nt of PO Module software und er IDCOL Biogas program S-09 UNDER GPOBA-II FOR R EREDPII / Selection of Individ ual Consultant for Developm Individual Consult IDA / 51580 Access to Electricity Post Open 24,400.00 23,840.74 Completed 2017-11-30 2018-01-23 2017-12-18 2018-02-28 2017-12-25 2018-03-01 2018-01-17 2018-03-05 2018-06-16 2018-09-27 ent and Publication of Press ant Selection News about IDCOL Programs & Project (Package No.: S-09 under GPOBA-II) S-12 UNDER GPOBA-II / Sele ction of Individual Consultant for the Design of Low-cost Bri Individual Consult IDA / 51580 Household Energy Post Open 11,000.00 10,768.00 Completed 2018-02-20 2018-02-18 2018-03-05 2018-02-19 2018-03-12 2018-03-08 2018-04-03 2018-03-11 2018-04-23 2018-04-20 ck-cement Based Biogas Plan ant Selection t under IDCOL Biogas & Bio-f ertilizer Program (Package N o.: S-12 under GPOBA-II) S-24 UNDER REREDPII-AF / S election of firm for conductin g impact assessment of solar IDA / 55140 Access to Electricity Post Direct Selection Direct 108,000.00 126,115.99 Completed 2018-02-22 2018-02-25 2017-10-30 2018-03-10 2018-02-22 2018-12-31 2019-11-24 irrigation, solar mini-grid and ICS Projects of IDCOL (Packa ge No.: S-24 under REREDPII- AF) S-13 UNDER GPOBA-II / Sele ction of Individual Consultant Individual Consult for development of 'Construc IDA / 51580 Household Energy Post Open 3,500.00 3,046.31 Completed 2018-03-01 2018-04-08 2018-03-09 2018-04-15 2018-03-14 2018-04-26 2018-03-22 2018-04-26 2018-05-06 2018-06-27 ant Selection tion Manual' and 'User Manu al' under IDCOL Biogas & Bio -fertilizer Program. S-14 UNDER GPOBA-II / Sele ction of Individual Consultant for the development of onlin Individual Consult IDA / 51580 Household Energy Post Direct 1,400.00 1,218.52 Completed 2018-04-05 2018-03-12 2018-04-10 2018-04-10 2018-04-20 2018-04-22 2018-05-08 2018-04-22 2018-11-04 2018-10-21 e-based PO Data Entry Softw ant Selection are for larger plants under ID COL Biogas & Bio-fertilizer pr ogram. S-17 UNDER RERED-II-AF-II / Selection of individual consul Individual Consult tant for development of a soc IDA / 62020 Household Energy Post Limited 4,380.00 3,814.52 Terminated 2018-10-08 2018-10-04 2018-10-23 2018-10-10 2018-10-28 2018-10-17 2018-11-05 2018-10-24 2019-01-19 ant Selection iocultural program to promot e woodlot plantation under I DCOL ICS Program. Page 5 S-18 UNDER RERED-II-AF-II / Selection of Individual Consul Individual Consult tant for the Development of IDA / 62020 Household Energy Post Limited 5,625.00 5,483.37 Completed 2018-10-15 2018-10-15 2018-10-30 2018-10-25 2018-11-04 2018-10-28 2018-11-08 2018-11-12 2019-02-06 2019-08-04 ant Selection Mobile Application Based Ins pection system under IDCOL ICS Program. S-22 UNDER REREDP-II AF / Selection of Technical Consul Individual Consult IDA / 55140 Access to Electricity Post Limited 6,250.00 0.00 Canceled 2018-01-15 2018-01-20 2018-02-10 2018-02-25 2018-05-26 tant under IDCOL Biomass pr ant Selection ogram (under Renewable En ergy Project) S-19 UNDER REREDII-AFII / Fi rm for arranging a design co mpetition to select a firm for IDA / 62020 Sector Technical Assistance Post Direct Selection Direct 37,500.00 7,004.44 Completed 2018-10-31 2018-05-15 2018-11-06 2018-05-15 2018-11-20 2018-05-16 2019-11-20 2018-12-21 architectural and structural d esign work of new office buil ding of IDCOL S-26 UNDER REREDP-II AF / Selection of Individual Consul Individual Consult IDA / 55140 Household Energy Post Limited 937.50 882.92 Completed 2019-01-14 2018-12-10 2019-01-16 2019-01-27 2019-01-20 2019-02-04 2019-01-23 2019-02-08 2019-03-30 2019-02-28 tant for Designing Leaflet & ant Selection Manuals for IDCOL Biogas & Bio-fertilizer program S-22 UNDER REREDP-II AF-II Individual Consult / Individual Consultant to dev IDA / 62020 Household Energy Post Direct 56,250.00 58,364.55 Signed 2019-03-04 2019-04-07 2019-03-11 2019-05-05 2019-03-25 2019-05-22 2019-03-31 2019-05-30 2020-02-29 ant Selection elop domestic and commerci al stoves S-23 UNDER REREDP-II AF-II IDA / 62020 Household Energy Post Direct Selection Direct 312.50 294.31 Completed 2019-03-05 2019-03-17 2019-03-08 2019-03-14 2019-03-21 2019-03-20 2019-03-31 2019-03-31 / Design of Biogas Manual S-27 UNDER REREDP-II AF / Selection of Individual Consul tant for developing mobile ap Individual Consult plication for inspection of Sol IDA / 55140 Access to Electricity Post Limited 12,500.00 0.00 Canceled 2019-09-01 2019-09-05 2019-09-08 2019-09-12 2019-10-13 ant Selection ar Irrigation & Solar-Minigrid with web service and option f or integrating other project-r elated inspection templates S-25 UNDER REREDP-II AFII / Selection of Firm to measure personal exposure to Househ IDA / 62020 Household Energy Post Direct Selection Direct 220,502.00 220,477.00 Signed 2019-10-06 2020-07-02 2019-10-16 2020-07-13 2019-11-12 2020-07-15 2020-05-10 old Air Pollution (HAP) and st ove usage patterns associate d with transition to ICS under IDCOL ICS Program S-26 UNDER REREDII-AFII / S election of Consultant for Do IDA / 62020 Household Energy Post Direct Selection Direct 15,000.00 13,573.32 Completed 2020-03-15 2020-02-04 2020-03-19 2020-02-05 2020-04-14 2020-06-22 2020-07-13 2020-11-06 cumenting R&D Activities on Renewable Energy of IDCOL S-27 UNDER REREDP-II AF II / Developing a web-based sof Individual Consult tware for online enlistment of IDA / 62020 Access to Electricity Post Limited 15,000.00 0.00 Canceled 2020-09-23 2020-09-24 2020-09-29 2020-10-06 2021-04-04 ant Selection solar products under IDCOL r enewable energy programs S-28 UNDER REREDP-II AF II / Selection of consultant for I Individual Consult IDA / 62020 Household Energy Post Limited 5,625.00 5,071.73 Signed 2020-10-22 2021-03-07 2020-10-29 2021-03-01 2020-11-08 2021-03-15 2020-12-13 2021-03-25 2021-06-11 DCOL ICS program inspection ant Selection app improvement S-30 UNDER REREDP-II AF II Individual Consult Under Implement / Selection of consultant for a IDA / 62020 Household Energy Post Limited 10,000.00 0.00 2022-07-24 2022-10-10 2022-07-29 2022-08-19 2022-09-23 2023-09-23 ant Selection ation chieving gender targets unde r ICS Program S-33 UNDER REREDP-II AF II / Selection of an Individual C Individual Consult Under Implement IDA / 62020 Access to Electricity Post Limited 3,000.00 0.00 2022-10-12 2022-10-31 2022-10-17 2022-10-24 2022-11-05 2023-05-04 onsultant to inspect the upda ant Selection ation ted technical standard for SIP projects S-35 UNDER REREDP II AF II / Individual Consult Pending Impleme Selection of Individual Consul IDA / 55140 Sector Technical Assistance Post Limited 5,000.00 0.00 2023-03-20 2023-03-29 2023-04-02 2023-04-10 2023-05-31 ant Selection ntation tant for Interior Decoration IDCOL S-13 / Technical Cons ultant for Biogas Based Capti IDA / 51580 Access to Electricity Prior Direct Selection Direct 0.00 155,946.05 Canceled ve Plant - Draft Negotiated C ontract Page 6 PROCUREMENT PLAN (Textual Part) Project information: Pakistan Punjab Human Capital Investment Project (HCIP) P164785 Project Implementation agency: (i) Punjab Social Protection Authority; (ii) Secondary Education Department and; (iii) Punjab Health Facilities Management Company (PHFMC) Date of the Procurement Plan: July 22, 2020 Period covered by this Procurement Plan: July 2020- December 2021 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016, Revised November 2017 and August 2018) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in Public Procurement Rules 2004 Revised 2020, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions: 1) The eligibility of bidders shall be as defined under Section III of the Procurement Regulations. Accordingly, no bidder or potential bidder shall be declared ineligible for contracts financed by the Bank for reasons other than those provided in Section III of the Procurement Regulations. 2) For national open competitive procurement, only the model procurement documents acceptable to the World Bank, shall be used. 3) The request for bids/request for proposals document shall require that Bidders/Proposers submitting Bids/Proposals present a signed acceptance (in the form attached) at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights. 4) Procurement Documents include provisions, as agreed with the Bank, intended to adequately mitigate against environmental, social (including sexual exploitation and abuse and gender-based violence), health and safety (“ESHS”) risks and impacts 5) Access to procurement opportunities shall not be restricted to firms that have pre-registered and/or paid a registration fee. 6) No preference of any kind shall be given to national bidders in the bidding process. 7) Procurement methods that use two-envelope process and rated criteria shall be subject to Bank’s prior concurrence When other national procurement arrangements (other than national open competitive procurement) are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed Letter of Acceptance of the World Bank’s Anticorruption Guidelines and Sanctions Framework1 Date: Invitation of Bids/Proposals No.__________ To: ___________________________________________________________________________ We, along with our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not) consultants and personnel, acknowledge and agree to abide by the World Bank’s policy regarding Fraud and Corruption (corrupt, fraudulent, collusive, coercive, and obstructive practices), as set out and defined in the World Bank’s Anti-Corruption Guidelines2 in connection with the procurement and execution of the contract (in case of award), including any amendments thereto. We declare and warrant that we, along our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not), consultants and personnel, are not subject to, and are not controlled by any entity or individual that is subject to, a temporary suspension, early temporary suspension, or debarment imposed by a member of the World Bank Group, including, inter alia, a cross-debarment imposed by the World Bank Group as agreed with other international financial institutions (including multilateral development banks), or through the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement. Further, we are not ineligible under the laws or official regulations of [Insert name of Employer as per bidding document] or pursuant to a decision of the United Nations Security Council. We confirm our understanding of the consequences of not complying with the World Bank’s Anti-Corruption Guidelines, which may include the following: a. rejection of our Proposal/Bid for award of contract; 1[Drafting note: This document shall be signed by bidders/proposers/consultants and submitted as part of their bids/proposals. In addition, this document shall be signed by the winning bidder/consultant and incorporated as part of the contract.] 2Guidelines on Preventing and Combating Fraud and Corruption in Projects Financed by International Bank for Reconstruction and Development Loans and the International Development Agency Credits and Grants, dated October 15, 2006, and revised in January 2011 and July 2016, as they may be revised from time to time. b. in the case of award, termination of the contract, without prejudice to any other remedy for breach of contract; and c. sanctions, pursuant to the Bank’s Anti-Corruption Guidelines and in accordance with its prevailing sanctions policies and procedures as set forth in the Bank’s Sanctions Framework. This may include a public declaration of ineligibility, either indefinitely or for a stated period of time, (i) to be awarded or otherwise benefit from a Bank-financed contract, financially or in any other manner;3 (ii) to be a nominated4 sub-contractor, sub-consultant, consultant, manufacturer or supplier, or service provider of an otherwise eligible firm being awarded a Bank-financed contract; and (iii) to receive the proceeds of any loan made by the Bank or otherwise to participate further in the preparation or implementation of any Bank- financed project. We understand that we may be declared ineligible as set out above upon: a. completion of World Bank Group sanctions proceedings according to its prevailing sanctions procedures; b. cross-debarment as agreed with other international financial institutions (including multilateral development banks); c. the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement; or d. temporary suspension or early temporary suspension in connection with an ongoing World Bank Group sanctions proceeding. For avoidance of doubt, the foregoing effects of ineligibility do not extend to a sanctioned firm’s or individual’s execution of its ongoing Bank-financed contracts (or its ongoing sub-agreements under such contracts) that are not the subject of a material modification, as determined by the Bank. We shall permit, and shall cause our sub-contractors, sub-consultants, agents (whether declared or not), personnel, consultants, service providers or suppliers, to permit the Bank to inspect5 all accounts, records, and other documents relating to 3 For the avoidance of doubt, a sanctioned party’s ineligibility to be awarded a contract shall include, without limitation, (i) applying for pre-qualification or initial selection), expressing interest in a consultancy, and bidding, either directly or as a nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider, in respect of such contract, and (ii) entering into an addendum or amendment introducing a material modification to any existing contract. 4A nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider (different names are used depending on the bidding document) is one which has been: (i) included by the bidder in its pre-qualification or initial selection application or bid because it brings specific and critical experience and know-how that allow the bidder to meet the qualification requirements for the particular bid; or (ii) appointed by the Borrower. 5Inspections in this context are usually investigative (i.e., forensic) in nature: they involve fact- finding activities undertaken by the Bank or persons appointed by the Bank to address specific the procurement process and/or contract execution (in the case of award), and to have them audited by auditors appointed by the Bank. We agree to preserve all accounts, records, and other documents (whether in hard copy or electronic format) related to the procurement and execution of the contract. Name of the Bidder/Proposer/Consultant: Name of the person duly authorized to sign the Bid/Proposal on behalf of the Bidder/Proposer/ Consultant: Title of the person signing the Letter: matters related to investigations/audits, such as evaluating the veracity of an allegation of possible Fraud and Corruption, through the appropriate mechanisms. Such activity includes but is not limited to accessing and examining a firm's or individual's financial records and information, and making copies thereof as relevant; accessing and examining any other documents, data, and information (whether in hard copy or electronic format) deemed relevant for the investigation/audit, and making copies thereof as relevant; interviewing staff and other relevant individuals; performing physical inspections and site visits; and obtaining third-party verification of information. PROCUREMENT Pakistan : Punjab Human Capital Investment Project PLAN General Information Country: Pakistan 2020-07-29 Bank’s Approval Date of the Original Procurement Plan: 2023-06-01 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P164785 GPN Date: 2020-06-25 Project Name: Punjab Human Capital Investment Project Loan / Credit No: IDA / 65480 School Education Department Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PK-SED-185833-GO-RFB / Fo Economic and social inclusio Single Stage - One E r Arranging of Book Shelves i IDA / 65480 Post Request for Bids Open - National 1,648,484.00 0.00 Canceled 2021-04-21 2021-04-23 2021-04-26 2021-04-23 2021-06-07 2021-05-25 2021-07-07 2021-08-11 2022-02-07 n nvelope n Selected Schools PK-SED-185834-GO-RFB / Pr Economic and social inclusio Single Stage - One E IDA / 65480 Post Request for Bids Open - National 2,060,606.00 0.00 Canceled 2021-08-22 2021-08-27 2021-10-08 2021-11-07 2021-12-12 2022-02-20 ocurement of Books for Read n nvelope ing Corners PK-SED-185832-GO-RFB / Pr Economic and social inclusio Single Stage - One E IDA / 65480 Post Request for Bids Open - National 412,121.00 0.00 Canceled 2021-01-12 2021-01-17 2021-02-28 2021-03-30 2021-05-04 2021-10-31 ocurement of Tablets for ECE n nvelope teachers PK-SED-185836-GO-RFQ / Pri Economic and social inclusio Request for Quota Single Stage - One E Pending Impl IDA / 65480 Post Open - National 51,515.00 0.00 2021-04-26 2021-06-24 2021-12-21 nting of Revised ECE Teacher n tions nvelope ementation 's Guide PK-SED-185838-GO-RFB / Pr Economic and social inclusio Request for Quota ocurement of Smart Boards o IDA / 65480 Post 90,909.00 0.00 Canceled 2024-01-20 2024-03-10 2024-10-26 n tions r Pilot Purposes PK-SED-224026-GO-RFQ / Pr Economic and social inclusio Request for Quota Single Stage - One E ocurement of Laptops, Printe IDA / 65480 Post Limited 24,714.00 27,985.44 Signed 2021-03-15 2021-04-08 2021-03-28 2021-05-21 2022-03-28 n tions nvelope rs, Scanner etc. PK-SED-224032-GO-RFQ / Pr Economic and social inclusio Request for Quota Single Stage - One E IDA / 65480 Post Limited 36,445.00 20,296.06 Signed 2021-03-24 2021-06-03 2021-04-20 2021-07-24 2022-04-20 ocurement of Office Furniture n tions nvelope PK-SED-238935-GO-RFB / Pr ocurement of Age-appropriat Economic and social inclusio Single Stage - One E IDA / 65480 Prior Request for Bids Open - National 5,084,716.00 0.00 Canceled 2021-07-01 2021-11-30 2021-07-06 2021-12-01 2021-08-17 2022-01-10 2021-09-16 2021-10-21 2022-04-19 e Furniture and Book Shelves n nvelope for 3400 Schools PK-SED-249103-GO-RFB / Pr Economic and social inclusio Single Stage - One E IDA / 65480 Post Request for Bids Open - National 1,275,000.00 1,160,728.09 Signed 2021-09-10 2021-09-12 2021-09-15 2021-09-16 2021-10-21 2021-10-21 2021-11-11 2021-11-04 2021-12-07 2021-11-30 2022-06-28 ocurement of ECE Kits for sc n nvelope hools PK-SED-255162-GO-RFB / Pr Economic and social inclusio Single Stage - One E IDA / 65480 Post Request for Bids Open - National 1,125,000.00 0.00 Canceled 2021-10-06 2021-10-08 2021-10-11 2021-10-12 2021-11-16 2021-11-30 2021-12-28 2022-06-26 ocurement of Tablets n nvelope PK-SED-265130-GO-RFB / Pr Economic and social inclusio Single Stage - One E Under Imple ocurement of Books (SRM) fo IDA / 65480 Prior Request for Bids Open - National 4,250,000.00 0.00 2021-12-31 2022-03-08 2022-01-05 2022-03-09 2022-02-16 2022-03-18 2022-04-22 2022-10-19 n nvelope mentation r Reading Corners in ECE and Grade 1-3 PK-SED-266093-GO-RFB / Pr Economic and social inclusio Single Stage - One E IDA / 65480 Post Request for Bids Open - National 1,125,000.00 968,193.33 Signed 2021-12-10 2021-12-15 2021-12-15 2021-12-20 2022-01-20 2022-01-19 2022-02-03 2022-02-14 2022-03-03 2022-04-01 2022-06-30 ocurement of Tablets n nvelope PK-SED-282842-GO-RFB / Pr ocurement of Age-Appropriat Economic and social inclusio Single Stage - One E Under Imple IDA / 65480 Prior Request for Bids Open - National 4,750,000.00 0.00 2022-03-21 2022-10-20 2022-03-26 2022-10-21 2022-05-01 2022-12-12 2022-05-22 2023-02-23 2022-06-26 2022-12-23 e Classroom Furniture, Learni n nvelope mentation ng and Reading Corner Shelv es PK-SED-309382-GO-RFQ / Pri Economic and social inclusio Request for Quota Single Stage - One E Under Imple nting of Information Educatio IDA / 65480 Post Open - National 64,000.00 0.00 2022-08-19 2022-08-25 2022-09-13 2022-12-12 n tions nvelope mentation n & Communication (IEC) Mat erial PK-SED-311287-GO-RFB / Pr Economic and social inclusio Single Stage - One E Under Imple IDA / 65480 Post Request for Bids Open - National 950,000.00 0.00 2022-08-30 2022-11-15 2022-09-04 2022-11-16 2022-10-04 2022-12-15 2022-10-25 2022-11-15 2023-05-14 ocurement of Tablets n nvelope mentation PK-SED-332013-GO-RFQ / Pri Economic and social inclusio Request for Quota Single Stage - One E Pending Impl nting Contract under Framew IDA / 65480 Post Limited 100,000.00 0.00 2022-12-26 2023-01-21 2024-07-14 n tions nvelope ementation ork Agreement PK-SED-360557-GO-RFB / Pr Economic and social inclusio Open - Internationa Single Stage - One E Under Imple ocurement of Books (RSM) Fo IDA / 65480 Prior Request for Bids 4,250,000.00 0.00 2023-05-12 2023-05-29 2023-05-17 2023-06-30 2023-07-30 2023-09-03 2024-03-01 n l nvelope mentation r Reading Corners in ECE and Grade 1-3 PK-SED-365614-GO-DIR / Pro Economic and social inclusio Direct - Internation Pending Impl IDA / 65480 Post Direct Selection 1,000,000.00 0.00 2023-06-18 2023-06-23 2023-07-31 2024-01-27 curement of 3900 Tablets for n al ementation PHCIP NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PK-SED-325351-NC-RFB / So Economic and social inclusio Single Stage - One E Under Imple cial Mobilization Firm to Cond IDA / 65480 Post Request for Bids Open - National 480,000.00 0.00 2022-11-21 2022-11-18 2022-11-26 2022-11-28 2022-12-20 2022-12-23 2022-12-30 2023-03-24 2023-01-27 2023-07-26 n nvelope mentation uct Community Awareness S essions CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Page 1 Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PK-SED-185825-CS-CQS / Hir Economic and social inclusio Consultant Qualifi Pending Impleme ing of Media Firm to Develop IDA / 65480 Post Open - National 90,909.00 0.00 2020-12-06 2020-12-27 2021-02-09 2021-03-11 2021-04-15 2021-06-24 n cation Selection ntation Video Contents/Strategies PK-SED-185823-CS-CQS / TA for Content Development of Economic and social inclusio Quality And Cost- Open - Internationa IDA / 65480 Post 848,484.00 0.00 Canceled 2020-09-16 2020-09-19 2020-10-13 2020-11-15 2020-11-20 2020-12-23 2021-01-09 2021-04-19 Teacher's Guide, Lesson Plan n Based Selection l and Children Activity Book PK-SED-185824-CS-CQS / Hir ing of Technical Assistance t Economic and social inclusio Quality And Cost- Open - Internationa IDA / 65480 Post 727,272.00 0.00 Canceled 2020-09-27 2020-09-30 2020-10-24 2020-11-26 2020-12-06 2020-12-21 2021-01-14 2023-10-11 o Develop Training Modules a n Based Selection l nd Train Master Trainers PK-SED-191207-CS-QCBS / H iring of Technical Assistance Economic and social inclusio Quality And Cost- Open - Internationa IDA / 65480 Post 969,696.00 0.00 Canceled 2020-09-27 2021-06-25 2020-09-30 2021-08-25 2020-10-24 2021-11-16 2020-11-25 2021-12-21 2020-12-05 2020-12-22 2021-01-08 2023-10-05 Firm to Develop Training Mod n Based Selection l ules and Train Master Trainer s PK-SED-191211-CS-QCBS / H iring of Technical Assistance Economic and social inclusio Quality And Cost- Open - Internationa for Content Development of IDA / 65480 Post 875,000.00 0.00 Canceled 2020-09-27 2021-06-25 2020-09-30 2021-07-29 2020-11-02 2021-10-11 2020-12-04 2021-11-11 2020-12-14 2021-11-22 2020-12-29 2021-12-10 2021-01-15 2023-10-12 n Based Selection l Teacher's Guide, Lesson Plan and Children Activity Book PK-SED-191213-CS-QCBS / H iring of Technical Assistance Economic and social inclusio Quality And Cost- Open - Internationa IDA / 65480 Post 969,696.00 0.00 Canceled 2020-09-27 2020-09-30 2020-10-24 2020-11-25 2020-12-05 2020-12-22 2021-01-08 2023-10-05 for Content Development of n Based Selection l Digital Interactive Content PK-SED-191217-CS-QCBS / T echnical Assistance for Devel Economic and social inclusio Quality And Cost- Open - Internationa IDA / 65480 Post 969,696.00 0.00 Canceled 2020-09-27 2020-09-30 2020-10-24 2020-11-25 2020-12-05 2020-12-22 2021-01-08 2023-10-05 opment of Student Tracking n Based Selection l Application, Pilot and Trouble Shooting PK-SED-185814-CS-CQS / Hir Economic and social inclusio Consultant Qualifi IDA / 65480 Post Open - National 258,715.00 238,529.13 Signed 2020-08-16 2021-03-05 2020-09-06 2021-03-22 2020-09-26 2021-07-02 2020-10-03 2021-07-23 2020-10-09 2021-09-01 2021-04-07 ing of Firm for Baseline Surve n cation Selection y PK-SED-241917-CS-QCBS / H iring of Technical Assistance Economic and social inclusio Quality And Cost- Open - Internationa Firm to Develop Training Mod IDA / 65480 Post 776,146.00 0.00 Canceled 2021-06-29 2021-06-25 2021-07-02 2021-08-25 2021-07-26 2021-11-08 2021-08-27 2021-12-13 2021-09-06 2021-09-23 2021-10-10 2022-04-08 n Based Selection l ules and Train Master Trainer s (Early Years Trainings) PK-SED-311283-CS-CQS / Hir ing of Firm for Development Economic and social inclusio Consultant Qualifi IDA / 65480 Post Open - National 103,438.00 0.00 Signed 2022-08-25 2022-08-24 2022-09-15 2022-09-14 2022-10-06 2022-11-15 2022-10-13 2022-12-15 2022-11-10 2023-05-09 of Content and Impart Trainin n cation Selection g of Lead Trainers and Social Mobilizers PK-SED-317974-CS-QCBS / H IRING OF CONSULTING SERVI Economic and social inclusio Quality And Cost- CES FOR CONTENT DEVELOP IDA / 65480 Post Open - National 350,000.00 0.00 Signed 2022-09-30 2022-09-27 2022-10-21 2022-10-06 2022-11-19 2022-11-15 2022-12-17 2022-12-06 2022-12-31 2022-12-06 2023-01-28 2023-03-06 2023-03-04 2024-03-03 n Based Selection MENT FOR ECCE TEACHING A ND LEARNING MATERIALS PK-SED-319304-CS-CQS / Hir Economic and social inclusio Consultant Qualifi Under Implement IDA / 65480 Post Open - National 80,000.00 0.00 2022-10-10 2022-12-06 2022-10-31 2022-12-30 2022-11-29 2022-12-20 2023-01-24 2023-07-23 ing of Media Firm n cation Selection ation PK-SED-326070-CS-QCBS / P ROCUREMENT OF CONSULTI NG SERVICES FOR DEVELOP MENT OF HEAD TEACHERS’, Economic and social inclusio Quality And Cost- Under Implement IDA / 65480 Post Open - National 375,000.00 0.00 2022-11-15 2022-11-11 2022-12-06 2022-12-30 2023-01-09 2023-02-06 2023-02-07 2023-03-03 2023-03-31 2023-07-29 ASSISTANT EDUCATION OFFI n Based Selection ation CERS’ (AEOs), AND SCHOOL COUNCIL (SC) MEMBERS’ TR AINING MODULES AND TRAIN ING OF MASTER TRAINERS PK-SED-326069-CS-QCBS / P ROCUREMENT OF CONSULTI NG SERVICES FOR DEVELOP Economic and social inclusio Quality And Cost- Under Implement IDA / 65480 Post Open - National 625,000.00 0.00 2022-11-15 2022-11-14 2022-12-06 2022-12-30 2022-12-30 2023-01-27 2023-02-10 2023-03-10 2023-04-03 2023-09-30 MENT OF ECCE, GRADE 1,2 & n Based Selection ation 3 TEACHERS AND CAREGIVE RS’ TRAINING MODULES AND TRAINING OF MASTER TRAIN ERS INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PK-SED-185809-CS-INDV / Hi Economic and social inclusio Individual Consult ring of Monitoring & Evaluati IDA / 65480 Post Open 111,384.00 3,074.06 Signed 2021-07-01 2020-09-02 2021-07-30 2020-12-21 2021-08-04 2020-12-21 2021-08-10 2020-12-25 2025-08-09 n ant Selection on Specialist PK-SED-185807-CS-INDV / Hi Economic and social inclusio Individual Consult IDA / 65480 Post Open 133,333.00 3,095.84 Completed 2020-08-10 2020-09-02 2020-09-08 2020-12-21 2020-09-13 2020-12-21 2020-09-18 2020-12-25 2025-07-17 2021-07-31 ring of Procurement Specialis n ant Selection t PK-SED-185552-CS-INDV / Hi Economic and social inclusio Individual Consult ring of Financial Managemen IDA / 65480 Post Open 133,333.00 3,333.99 Terminated 2020-10-01 2020-09-02 2020-10-29 2020-12-21 2020-11-03 2020-12-21 2020-11-09 2021-01-05 2025-06-26 n ant Selection t Specialist PK-SED-190129-CS-INDV / Hi ring of Programme Manager f Economic and social inclusio Individual Consult IDA / 65480 Post Open 218,181.00 220,693.19 Completed 2020-08-28 2020-09-02 2020-09-25 2020-12-21 2020-09-30 2020-12-21 2020-10-05 2021-01-26 2025-09-09 2021-04-01 or Foundation Learning Cell u n ant Selection nder PHCIP of SED Compone nt PK-SED-190131-CS-INDV / Hi Economic and social inclusio Individual Consult ring of Education Specialist u IDA / 65480 Post Open 160,000.00 3,086.36 Signed 2020-08-28 2020-09-02 2020-09-25 2020-12-21 2020-09-30 2020-12-21 2020-10-05 2020-12-26 2025-09-09 n ant Selection nder PHCIP SED Component PK-SED-190132-CS-INDV / Hi Economic and social inclusio Individual Consult ring of ECE Curriculum Speci IDA / 65480 Post Open 160,000.00 3,086.36 Signed 2020-08-28 2020-09-02 2020-09-25 2020-12-21 2020-09-30 2020-12-21 2020-10-05 2021-01-12 2025-06-01 n ant Selection alist for PHCIP SED Compone nt PK-SED-190138-CS-INDV / Hi Economic and social inclusio Individual Consult ring of ECE Planning Specialis IDA / 65480 Post Open 130,909.00 3,086.36 Terminated 2021-04-18 2020-09-02 2021-05-16 2020-12-21 2021-05-21 2020-12-21 2021-05-26 2020-12-27 2025-07-04 n ant Selection t under PHCIP SED Compone nt Page 2 PK-SED-190188-CS-INDV / Hi Economic and social inclusio Individual Consult ring of Contract Management IDA / 65480 Post Open 160,000.00 3,333.99 Terminated 2020-08-31 2020-09-02 2020-09-28 2020-12-21 2020-10-05 2020-12-21 2020-10-10 2020-12-25 2025-06-06 n ant Selection Specialist PK-SED-190187-CS-INDV / Hi Economic and social inclusio Individual Consult ring of Database Analyst for IDA / 65480 Post Open 100,000.00 0.00 Canceled 2021-04-22 2020-09-02 2021-05-20 2021-05-25 2021-05-30 2025-05-29 n ant Selection PHCIP SED Component PK-SED-190134-CS-INDV / Hi Economic and social inclusio Individual Consult ring of Social Mobilization Sp IDA / 65480 Post Open 160,000.00 0.00 Canceled 2020-08-28 2020-09-02 2020-09-07 2020-09-12 2020-09-17 2025-07-03 n ant Selection ecialist under PHCIP SED Co mponent PK-SED-220127-CS-INDV / Hi Economic and social inclusio Individual Consult ring of Social Mobilization Sp IDA / 65480 Post Open 160,000.00 2,864.24 Signed 2021-02-17 2021-02-19 2021-04-07 2021-07-28 2021-04-28 2021-07-28 2021-06-02 2021-08-20 2025-06-30 n ant Selection ecialist under PHCIP SED Co mponent PK-SED-220135-CS-INDV / Hi Economic and social inclusio Individual Consult ring of Database Analyst for IDA / 65480 Post Open 100,000.00 0.00 Canceled 2021-02-17 2021-02-19 2021-04-07 2021-07-28 2021-04-28 2021-06-02 2025-06-30 n ant Selection PHCIP SED Component PK-SED-251208-CS-INDV / Hi Economic and social inclusio Individual Consult Under Implement IDA / 65480 Post Open 186,336.00 0.00 2021-09-10 2021-09-06 2021-10-21 2021-10-23 2021-11-13 2025-06-11 ring of Procurement Specialis n ant Selection ation t PK-SED-228608-CS-INDV / Hi ring of Programme Manager f Economic and social inclusio Individual Consult IDA / 65480 Post Open 208,268.00 0.00 Canceled 2021-04-12 2021-05-19 2021-05-27 2021-06-01 2021-06-06 2025-06-30 or Foundation Learning Cell u n ant Selection nder PHCIP of SED Compone nt PK-SED-265127-CS-INDV / Hi Economic and social inclusio Individual Consult ring of Programme Manager f IDA / 65480 Post Open 130,840.00 35,849.08 Signed 2021-12-06 2021-12-02 2022-01-24 2022-03-24 2022-02-14 2022-03-24 2022-03-21 2022-03-29 2025-06-30 n ant Selection or Foundation Learning Cell ( PHCIP - PMIU) PK-SED-299480-CS-INDV / Hi Economic and social inclusio Individual Consult Under Implement ring of Assistant Planning Sp IDA / 65480 Post Open 80,096.00 0.00 2022-06-30 2022-07-19 2022-08-04 2022-08-19 2022-09-17 2025-06-30 n ant Selection ation ecialist for PHCIP-SED PK-SED-301701-CS-INDV / Hi Economic and social inclusio Individual Consult ring of Financial Managemen IDA / 65480 Post Open 80,096.00 0.00 Signed 2022-06-30 2022-07-27 2022-08-04 2022-09-01 2022-08-19 2022-09-03 2022-09-17 2025-06-30 n ant Selection t Specialist for PHCIP-SED PK-SED-301712-CS-INDV / Hi Economic and social inclusio Individual Consult ring of Contract Management IDA / 65480 Post Open 80,096.00 0.00 Canceled 2022-06-30 2022-07-19 2022-08-04 2022-08-19 2022-09-17 2025-06-30 n ant Selection Specialist for PHCIP-SED PK-SED-312543-CS-INDV / Ci Economic and social inclusio Individual Consult Under Implement IDA / 65480 Post Direct - National 9,000.00 0.00 2022-08-29 2022-09-09 2022-09-02 2022-09-09 2022-09-23 2023-03-22 vil Engineer n ant Selection ation PK-SED-319303-CS-INDV / Pr Economic and social inclusio Individual Consult Under Implement IDA / 65480 Post Limited 90,000.00 0.00 2022-10-04 2022-10-04 2022-10-09 2022-10-05 2022-10-16 2022-10-30 2023-10-25 ocurement Management Spe n ant Selection ation cialist PK-SED-320082-CS-INDV / In Economic and social inclusio Individual Consult IDA / 65480 Post Open - National 9,000.00 0.00 Canceled 2022-10-11 2022-11-14 2022-11-06 2022-11-13 2022-11-27 2023-05-26 ternal Auditor n ant Selection PK-SED-327984-CS-INDV / Hi Economic and social inclusio Individual Consult Under Implement ring of Environment Officer S IDA / 65480 Post Limited 9,000.00 0.00 2022-11-25 2022-11-30 2022-11-30 2022-12-07 2023-01-11 2023-07-10 n ant Selection ation ervices for Short term PK-SED-328839-CS-INDV / Ri Economic and social inclusio Individual Consult IDA / 65480 Post Open - National 9,000.00 0.00 Canceled 2022-11-30 2022-11-28 2022-12-19 2022-12-26 2023-01-16 2023-07-15 sk & Compliance Officer n ant Selection PK-SED-333026-CS-INDV / Hi Economic and social inclusio Individual Consult Under Implement ring of Individual Consultant f IDA / 65480 Post Limited 5,400.00 0.00 2022-12-23 2022-12-22 2022-12-28 2023-01-02 2023-01-16 2023-07-15 n ant Selection ation or short term ( for 3 months period only) PK-SED-336412-CS-INDV / Hi Economic and social inclusio Individual Consult IDA / 65480 Post Open - National 75,000.00 0.00 Signed 2023-01-20 2023-01-19 2023-02-15 2023-03-01 2023-02-25 2023-03-01 2023-03-14 2025-06-30 ring of Program Manager n ant Selection PK-SED-338532-CS-INDV / Hi Economic and social inclusio Individual Consult Under Implement ring of Procurement manage IDA / 65480 Prior Open - National 80,000.00 0.00 2023-01-31 2023-02-15 2023-03-01 2023-03-08 2023-03-25 2025-06-30 n ant Selection ation ment Specialist PK-SED-344106-CS-INDV / Hi Economic and social inclusio Individual Consult Under Implement IDA / 65480 Post Open - National 80,000.00 0.00 2023-02-23 2023-02-22 2023-04-13 2023-03-29 2023-05-04 2023-03-30 2023-06-08 2025-06-30 ring of Financial Managemen n ant Selection ation t specialist PK-SED-347963-CS-INDV / Hi Economic and social inclusio Individual Consult Under Implement ring of ECE Planning Specialis IDA / 65480 Post Open - National 78,546.00 0.00 2023-03-08 2023-03-13 2023-04-05 2023-04-10 2023-04-15 2025-06-30 n ant Selection ation t under PHCIP SED Compone nt PK-SED-364085-CS-INDV / Hi Economic and social inclusio Individual Consult ring of Procurement Manage IDA / 65480 Prior Open - National 80,000.00 0.00 Canceled 2023-05-30 2023-07-18 2023-08-08 2023-09-12 2024-03-10 n ant Selection ment Specialist PK-SED-364894-CS-INDV / Hi Economic and social inclusio Individual Consult ring of Procurement Manage IDA / 65480 Prior Limited 50,000.00 0.00 Under Review 2023-06-02 2023-06-13 2023-06-07 2023-06-15 2023-06-28 2023-08-02 2024-01-29 n ant Selection ment Specialist Page 3 Procurement Plan (Text in italic font is meant for instruction to staff and should be deleted in the final version of the PP) (This is only a sample with the minimum content that is required to be included in the PAD. The detailed procurement plan is still mandatory for disclosure on the Bank’s website in accordance with the guidelines. The initial procurement plan will cover the first 18 months of the project and then updated annually or earlier as necessary). General 1. Bank’s approval Date of the procurement Plan March 28, 2019: [N/A] 2. Date of General Procurement Notice: February 26, 2019 3. Period covered by this procurement plan: March to December, 2019 II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: [Thresholds for applicable procurement methods (not limited to the list below) will be determined by the Procurement Specialist /Procurement Accredited Staff based on the assessment of the implementing agency’s capacity.] No. Procurement Method Prior Review Threshold Comments US$ 1. NCB (Consultancy) Above US$ 1,350,000 N/A 2. Requalification. Bidders N/A_ shall be prequalified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines. 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: Not applicable 4. Reference to (if any) Project Operational/Procurement Manual: Project no. P166539 5. Any Other Special Procurement Arrangements: Not Applicable 6. Summary of the Procurement Packages planned during the first 18 months after project effectiveness (including those that are subject to retroactive financing and advanced procurement) July 9, 2010 1 2 3 4 5 6 7 Estimate Domesti Review Ref Description d Packag c by Bank Comments . Cost es Prefere (Prior / No. US$ nce Post) million (yes/no) Summary of the 1 NCB (Consulting 1.35 12 None Prior services) 2 Summary of the 0.378 9 None Post NCB (Consulting services) Summary of the 3 NCB (Goods) 0.2 1 No Post Summary of the 4 Shopping (Goods) 0.22 4 None Post Summary of the 5 NCB (Non- 0.05 1 None Post Consultant Services) III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Threshold Comments 1. Competitive Methods US$ 620,000.00 (Firms) 2. Single Source (Firms) N/A 3. Individual US$ 730,000.00 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_300,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 Ref Description of Estimated Review . Assignment Cost Packag by Bank Commen No. US$ es (Prior / ts million Post) July 9, 2010 Summary of 1 number of 0.15 2 Post contracts that will be let under CQS Summary of 2 number of 0.62 4 Prior contracts that will be let under CQS Summary of 0.228 7 number of Post contracts that will be let under IC Summary of 0.73 8 number of Prior contracts that will be let under IC July 9, 2010 PROCUREMENT Ghana : Ghana Economic Transformation Project PLAN General Information Country: Ghana 2019-03-18 Bank’s Approval Date of the Original Procurement Plan: 2023-06-06 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P166539 GPN Date: Project Name: Ghana Economic Transformation Project Loan / Credit No: / , IDA / 64650 Ministry of Finance - Economic Transformation Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GH-MOFEP-148797-CW-RFQ Project management and ev Request for Quota Single Stage - One E 2020-03-1 / Refurbishment of Project C IDA / 64650 Post Limited 70,000.00 65,220.79 Completed 2019-12-23 2020-02-06 2020-02-17 2020-04-07 aluation tions nvelope 8 oordinating Unit at Shippers Council GH-MOFEP-225302-CW-RFQ Crowding-in investments: Pr Request for Quota Single Stage - One E 2021-09-0 / Construction of 120 meter P IDA / 64650 omoting spatial and industri Post Limited 123,000.00 0.00 Canceled 2021-05-12 2021-07-07 tions nvelope 5 erimeter Fence Wall at GFZA al planning and developmen t GH-MOFEP-225305-CW-RFB / Crowding-in investments: Pr Single Stage - One E 2021-11-1 Rehabilitation of the 0.3km N IDA / 64650 omoting spatial and industri Post Request for Bids Open - National 377,000.00 914,330.47 Signed 2021-06-15 2022-01-14 2021-06-20 2022-01-20 2021-08-01 2022-02-14 2021-08-31 2022-03-23 2021-10-05 2022-06-04 nvelope 9 iche-Melcom Road al planning and developmen t GH-MOFEP-225306-CW-RFB / Crowding-in investments: Pr Rehabilitation of 1.6km Acce omoting spatial and industri Single Stage - One E 2,477,080.7 2021-12-0 IDA / 64650 Post Request for Bids Open - National 1,201,400.00 Signed 2021-06-15 2022-01-14 2021-06-20 2022-01-20 2021-08-01 2022-02-15 2021-08-31 2022-03-23 2021-10-05 2022-06-04 ss Road to AMP Logistics and al planning and developmen nvelope 0 4 Cocoa Touton TEPZ for GFZA t GH-MOFEP-225307-CW-RFB / Crowding-in investments: Pr Single Stage - One E 2,107,758.0 2021-11-1 Rehabilitation of existing mai IDA / 64650 omoting spatial and industri Post Request for Bids Open - National 300,000.00 Signed 2021-06-15 2022-01-14 2021-06-20 2022-01-20 2021-08-01 2022-02-16 2021-08-31 2022-03-23 2021-10-05 2022-06-04 nvelope 4 9 n Access Road al planning and developmen t National Procure GH-MOFEP-253837-CW-RFQ Project management and ev Request for Quota Single Stage - One E ment Document - 2021-12-2 / Partitioning of New Office B IDA / 64650 Post Limited 150,000.00 223,848.23 Completed 2021-09-27 2021-10-22 2021-11-08 2021-12-25 aluation tions nvelope 1 Envelope proce 3 uilding ss (Non Bank-SPD ) National Procure GH-MOFEP-268519-CW-RFB / Crowding-in investments: Pr ment Document - Construction of 295-meter Pe omoting spatial and industri Single Stage - One E 2022-05-2 IDA / 64650 Post Request for Bids Open - National 1 Envelope proce 270,000.00 194,380.09 Signed 2021-12-23 2022-01-14 2021-12-28 2022-01-20 2022-01-27 2022-02-14 2022-02-26 2022-03-23 2022-03-27 2022-06-04 rimeter Fence Wall at Tema al planning and developmen nvelope 6 ss (Non Bank-SPD Export Processing Zone t ) National Procure GH-MOFEP-253850-CW-RFB / Accelerating entrepreneursh Single Stage - One E ment Document - Under Imple 2023-11-2 Renovation of GEA Office Buil IDA / 64650 Post Request for Bids Open - National 1,800,000.00 0.00 2022-09-05 2022-09-12 2022-09-10 2022-09-12 2022-10-10 2022-10-12 2022-10-24 2022-12-09 2022-11-28 ip and MSME growth nvelope 1 Envelope proce mentation 3 ding ss (Non Bank-SPD ) Request for Propo GH-MOFEP-313585-CW-RFP / sal Engineering Pr Construction of Offsite Infrast Crowding-in investments: Pr ocurement and C ructure for the Greater Kuma omoting spatial and industri Request for Propo Open - Internationa 30,000,000.0 Under Imple 2024-11-0 IDA / 64650 Prior onstruction/Turnk 0.00 2022-09-09 2022-11-01 2022-11-25 2023-02-22 2022-11-25 2023-04-14 2022-09-14 2022-11-01 2023-02-03 2023-05-16 2023-07-08 2023-08-12 si industrial City and Special al planning and developmen sals l 0 mentation 4 ey - Works SPD (T Economic Zone (Engineer, Pr t wo-Stage)- Applyi ocure and Construct (EPC) ng contractor disq ualificiation GH-MOFEP-323225-CW-RFQ Request for Quota Accelerating entrepreneursh Request for Quota Single Stage - One E 2023-02-1 / Partitioning of Office for Ve IDA / 64650 Post Limited tions (Non Bank-S 30,000.00 0.00 Canceled 2022-11-09 2023-01-04 ip and MSME growth tions nvelope 8 nture Capital Trust Fund's An PD) alyst Program GH-MOFEP-351275-CW-RFQ Request for Quota Request for Quota Single Stage - One E Under Imple 2023-08-2 / Renovation of office space a IDA / 64650 Enabling investments Post Limited tions (Non Bank-S 200,000.00 0.00 2023-04-01 2023-05-27 tions nvelope mentation 5 llocated by MOTI to GhaNAS PD) GH-MOFEP-365667-CW-RFQ Request for Quota Request for Quota Single Stage - One E Pending Imp 2023-10-1 / Renovation of Business Reg IDA / 64650 Enabling investments Post Limited tions (Non Bank-S 50,000.00 0.00 2023-06-18 2023-08-13 tions nvelope lementation 2 ulatory Reforms (BRR) Office PD) GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GH-MOFEP-183234-GO-RFQ / Project management and ev Request for Quota Single Stage - One E IDA / 64650 Post Open - National 90,000.00 90,568.53 Completed 2020-07-13 2020-09-07 2021-08-28 2021-03-06 2022-07-07 Supply of Computers and Acc aluation tions nvelope essories GH-MOFEP-183247-GO-RFQ / Project management and ev Request for Quota Single Stage - One E IDA / 64650 Post Open - National 100,000.00 98,404.83 Completed 2020-07-13 2020-09-07 2020-07-30 2021-03-06 2020-09-15 Procurement of Office Equip aluation tions nvelope ment GH-MOFEP-183256-GO-RFQ / Project management and ev Request for Quota Single Stage - One E IDA / 64650 Post Open - National 50,000.00 3,147.42 Completed 2020-07-13 2020-09-07 2020-09-30 2021-03-06 2020-10-15 Procurement of Stationery aluation tions nvelope GH-MOFEP-194767-GO-RFB / Project management and ev Single Stage - One E Procurement of Vehicles for P IDA / 64650 Post Request for Bids Open - National 260,000.00 0.00 Canceled 2020-10-05 2020-10-10 2020-11-21 2020-12-21 2021-01-25 2021-07-24 aluation nvelope roject Coordination Unit GH-MOFEP-200002-GO-RFQ / Procurement of Computers a nd Printers (32No. Desktop P Request for Quota Single Stage - One E IDA / 64650 Enabling investments Post Limited 100,000.00 184,849.60 Completed 2020-10-27 2020-11-03 2020-11-22 2021-03-18 2020-12-22 2021-10-06 C, 21No. Laptop, 10No. All-in- tions nvelope PC, 10No. Multi-Functional Pri nter, 2No. Scanners (High En d) ) for GIPC and NBSSI GH-MOFEP-200004-GO-RFQ / Procurement of Networking A ccessories (8No.Hand held d evices (Smart devices/iPad/tr Request for Quota Single Stage - One E IDA / 64650 Enabling investments Post Limited 60,500.00 132,170.18 Completed 2020-10-27 2020-11-03 2020-11-22 2021-03-18 2020-12-22 2021-10-06 acking),10No. Network Switc tions nvelope hes,12No. Access Points, 16N o. Security Camera, 150No. I P Phones, 1No. USPS and cab le wiring) GH-MOFEP-200006-GO-RFQ / Procurement of 2No. Automa Request for Quota Single Stage - One E ted Voltage Regulator (AVR) IDA / 64650 Enabling investments Post Limited 77,000.00 73,867.60 Completed 2020-10-27 2020-11-03 2020-12-01 2021-03-18 2020-12-31 2021-05-29 tions nvelope &2No. Uninterruptible Power Supply (UPS) for GIPC Page 1 GH-MOFEP-200007-GO-RFQ / Procurement of HYBRID PABX System and Storage Devices (1No. Hybrid PABX System, 1 Request for Quota Single Stage - One E No. Video conference Facility IDA / 64650 Enabling investments Post Limited 77,000.00 222,932.20 Completed 2020-10-27 2020-11-03 2020-12-01 2021-03-18 2020-12-31 2021-10-13 tions nvelope , 1No. Storage Appliance syst em, 2No. Server, 1No. Firepr oof Media Storage, 10No. Ext ernal HDD Drives for Backup s) for GIPC and NBSSI GH-MOFEP-200008-GO-RFQ / Procurement of Office Furnitu re (130 No. Conference Chair s, 35No. Trapezoidal Chrome Request for Quota Single Stage - One E IDA / 64650 Enabling investments Post Limited 60,000.00 0.00 Canceled 2020-10-27 2020-11-03 2020-11-29 2020-12-29 Meeting Tables s, 15 No. File tions nvelope Cabinet, 4 No. works stations including chairs, 2No. detach ed desks and 2No. Chairs) for NBSSI and GIPC GH-MOFEP-200013-GO-RFQ / Procurement of TV Screens ( Request for Quota Single Stage - One E 1No. 40-inch, 1No. 42-inch, 5 IDA / 64650 Enabling investments Post Limited 98,000.00 191,940.90 Completed 2020-10-27 2020-11-03 2020-12-06 2021-03-18 2021-01-05 2021-10-07 tions nvelope No. 65-inch) and 8No. Confe rencing Equipment for GIPC GH-MOFEP-200204-GO-RFQ / Procurement of 6No. 4x4 Do Accelerating entrepreneursh Request for Quota Single Stage - One E uble Cabin Pick-Up Vehicles f IDA / 64650 Post Limited 500,000.00 305,542.19 Completed 2020-11-29 2020-11-18 2021-01-10 2021-03-18 2021-03-11 2021-10-14 ip and MSME growth tions nvelope or and 1No. 4x4 Cross Count ry Vehicle for NEIP and NBSSI GH-MOFEP-200206-GO-RFB / Procurement of ICT devices ( 10No. Projectors and project Accelerating entrepreneursh Single Stage - One E or screens, 20No. computers IDA / 64650 Post Request for Bids Open - National 270,000.00 53,203.49 Completed 2020-10-28 2020-10-29 2020-11-02 2020-12-02 2020-12-03 2020-12-16 2021-01-20 2021-01-13 2021-03-20 2021-03-14 2021-07-06 ip and MSME growth nvelope and 14No, multipurpose print ers & scanners and 1No. Hea vy duty Photocopier) for NEIP and 20 Incubation Hubs GH-MOFEP-200629-GO-RFQ / Project management and ev Request for Quota Single Stage - One E Procurement of 2 Cross Coun IDA / 64650 Post Limited 260,000.00 254,141.79 Completed 2020-10-26 2020-10-20 2020-12-07 2021-01-30 2021-01-06 2021-04-16 aluation tions nvelope try Vehicles and 2 Saloon Car s for PCU GH-MOFEP-205403-GO-RFB / Supply and Installation of Eq uipment (1 No. Inductively C oupled Plasma Mass Spectros Single Stage - One E copy, 1 No. High Performanc IDA / 64650 Enabling investments Post Request for Bids Open - National 670,000.00 946,937.58 Completed 2020-11-26 2021-02-24 2020-12-01 2021-03-05 2020-12-31 2021-03-26 2021-01-14 2021-03-30 2021-02-18 2021-07-27 2021-05-19 2022-04-28 nvelope e Liquid Chromatograph, 1 N o. Automatic Distillation Anal yzer, 1No.Fuel Analyzer,1 No. Automatic Pensky-Martens Cl osed Cup Flash Point Analyze r) GH-MOFEP-205413-GO-RFQ / Procurement of 2 No. 4x4 Cr Accelerating entrepreneursh Request for Quota Single Stage - One E IDA / 64650 Post Limited 200,000.00 189,342.20 Signed 2020-12-05 2021-11-26 2021-01-23 2022-05-24 2021-02-22 oss Country Vehicles and 1N ip and MSME growth tions nvelope o. Saloon Car for VCTF GH-MOFEP-205414-GO-RFQ / Procurement of Office Equip Accelerating entrepreneursh Request for Quota Single Stage - One E ment (15 laptops, 2 photocop IDA / 64650 Post Limited 70,000.00 62,075.11 Completed 2020-12-02 2021-05-27 2021-01-20 2021-08-28 2021-02-19 2022-06-01 ip and MSME growth tions nvelope iers, 4 printers, 3 shredder, 2 scanner, 2 colour printer, and IT accessories) GH-MOFEP-229088-GO-RFQ / Project management and ev Request for Quota Single Stage - One E Procurement of stationery, T IDA / 64650 Post Limited 50,000.00 43,405.83 Completed 2021-04-24 2021-05-27 2021-06-05 2021-08-28 2021-06-19 2021-10-30 aluation tions nvelope oners and Office Supplies for PCU GH-MOFEP-229095-GO-RFQ / Procurement of Office Equip ment (5no. Cabinets, 2no. GP Project management and ev Request for Quota Single Stage - One E IDA / 64650 Post Limited 100,000.00 2,578.93 Completed 2021-04-24 2021-05-27 2021-06-05 2021-08-28 2021-06-19 2021-10-30 S, 2no. Digital Camera, 15no aluation tions nvelope . External Hard Drives, 100no . Pendrives, 1no. Video Confe rencing Facility for PCU GH-MOFEP-229170-GO-RFQ / Project management and ev Request for Quota Single Stage - One E Procurement of 3no. Cross C IDA / 64650 Post Limited 250,000.00 361,539.45 Signed 2021-05-02 2021-11-26 2021-06-27 2022-05-27 2021-08-26 aluation tions nvelope ountry Vehicles and 1no. 4x4 Pickup for PCU GH-MOFEP-229171-GO-RFQ / Request for Quota Single Stage - One E Procurement of Multi-Media E IDA / 64650 Enabling investments Post Limited 70,000.00 97,157.77 Completed 2021-04-24 2021-08-09 2021-06-19 2021-12-07 2021-07-19 2022-05-25 tions nvelope quipment and Accessories fo r GIPC GH-MOFEP-229173-GO-RFQ / Procurement of 15No. File Ca Accelerating entrepreneursh Request for Quota Single Stage - One E binet, Office Desk and Chairs IDA / 64650 Post Limited 35,000.00 32,617.22 Completed 2021-04-24 2021-07-22 2021-06-19 2021-10-30 2021-07-19 2022-02-16 ip and MSME growth tions nvelope (4 works stations including c hairs, 2 detached desks, and 2 Chairs) GH-MOFEP-240322-GO-RFQ / Project management and ev Request for Quota Single Stage - One E Procurement of Microsoft Offi IDA / 64650 Post Limited 30,000.00 15,925.67 Completed 2021-07-14 2021-07-22 2021-09-08 2021-11-20 2021-10-08 2022-06-19 aluation tions nvelope ce and Anti Virus for 50 users GH-MOFEP-240323-GO-RFQ / Procure 1no. 4x4 Pick up and Request for Quota Single Stage - One E IDA / 64650 Enabling investments Post Limited 360,000.00 290,923.60 Signed 2021-07-14 2021-11-26 2021-09-08 2022-06-01 2021-11-07 three (3) cross country vehic tions nvelope les for MoTI and GFZA GH-MOFEP-253835-GO-RFQ / Refurbishment of GETP/GJSP Project management and ev Request for Quota Single Stage - One E IDA / 64650 Post Limited 70,000.00 77,007.29 Completed 2021-09-27 2021-10-22 2021-11-08 2021-12-25 2021-11-22 2022-03-02 New Office Building (Furnitur aluation tions nvelope e, Equipment etc.) GH-MOFEP-259207-GO-RFQ / Procurement of Furniture, Fix Request for Quota Single Stage - One E IDA / 64650 Enabling investments Post Limited 50,000.00 0.00 Canceled 2021-11-03 2021-12-22 2022-01-21 tures, and Equipment to Refu tions nvelope rbish the offices of BRR Secre tariat (DLI) GH-MOFEP-259209-GO-RFB / Procurement and Installation Single Stage - One E IDA / 64650 Enabling investments Post Request for Bids Open - National 240,000.00 0.00 Canceled 2021-11-15 2021-12-09 2021-11-20 2021-12-14 2021-12-20 2022-01-19 2022-02-23 2022-04-24 of IT Equipment to support B nvelope RR Programmes Page 2 GH-MOFEP-264225-GO-RFQ / Supply and Installation of Lab Request for Quota Single Stage - One E oratory Equipment (1no. Aut IDA / 64650 Enabling investments Post Limited 100,000.00 88,637.88 Completed 2021-12-05 2022-01-12 2022-01-23 2022-05-01 2022-03-24 2022-10-14 tions nvelope omatic Closed Cup Flash Anal yzer and 1no. Automatic Disti llation Analyzer) GH-MOFEP-161042-GO-RFQ / Accelerating entrepreneursh Request for Quota Single Stage - One E Designing and Printing of Poli IDA / 64650 Post Open - National 35,300.00 0.00 Canceled 2020-02-29 2020-04-14 2020-07-13 ip and MSME growth tions nvelope cy, Leaflets and Banner (ba ckdrop, pull-ups) GH-MOFEP-200195-GO-RFQ / Procurement of Office Equip Project management and ev Request for Quota Single Stage - One E ment and supplies ( 6 Laptop IDA / 64650 Post Limited 30,000.00 0.00 Canceled 2020-10-28 2022-01-20 2020-12-02 2021-01-01 aluation tions nvelope s,1 photocopier, 2 Printer ) fo r Economic Transformation U nits (MoF) GH-MOFEP-293690-GO-RFB / Design, Supply, Installation a Open - Internationa Single Stage - One E Under Revie nd configuration of a Busines IDA / 64650 Enabling investments Prior Request for Bids 6,700,000.00 0.00 2022-08-12 2022-09-20 2022-08-17 2022-09-22 2022-09-28 2023-01-20 2022-10-28 2022-12-02 2025-12-01 l nvelope w s Registry Software and data Centre for the Office of the R egistrar of Companies GH-MOFEP-310948-GO-RFB / Procurement of a Weighbridg Single Stage - One E IDA / 64650 Enabling investments Post Request for Bids Open - National 500,000.00 0.00 Signed 2022-09-01 2022-08-30 2022-09-06 2022-09-26 2022-10-06 2022-09-30 2022-10-27 2022-10-31 2022-12-01 2023-03-01 e Truck with Crane for the Gh nvelope ana Standards Authority GH-MOFEP-310958-GO-RFB / Printing 2000 copies of the G Single Stage - One E IDA / 64650 Enabling investments Post Request for Bids Open - National 250,000.00 0.00 Signed 2022-09-05 2022-09-12 2022-09-10 2022-09-12 2022-10-10 2022-10-12 2022-10-31 2022-11-16 2022-12-05 2023-02-03 hana Standards Authority Act nvelope and 5000 copies of the Natio nal Quality Policy. GH-MOFEP-312177-GO-RFB / Procurement of 95No. Laptop Single Stage - One E s,137 No. Computers, 6No.Pri IDA / 64650 Enabling investments Post Request for Bids Open - National 290,000.00 0.00 Signed 2022-09-05 2022-09-20 2022-09-10 2022-09-22 2022-09-24 2022-10-24 2022-10-15 2022-11-22 2022-11-12 2022-12-27 nvelope nters, 15No. Toners, and Acc essories for GSA, GEA and G HaNAS GH-MOFEP-315969-GO-RFB / Procurement of IT Equipment to support selected Reforms under BRR (70No. Desktop,3 Single Stage - One E IDA / 64650 Enabling investments Post Request for Bids Open - National 300,000.00 0.00 Signed 2022-09-26 2022-09-23 2022-10-01 2022-09-26 2022-10-31 2022-10-26 2022-11-30 2022-12-08 2023-01-04 2023-03-05 0No. Laptops, 50No. Router, nvelope 20No. Scanners, 70No. Table ts, 8No. Printers, 70No. UPS, 4No. Heavy Duty Photocopier s, 60No. External Hard Drives ) GH-MOFEP-319777-GO-RFQ / Accelerating entrepreneursh Request for Quota Single Stage - One E Procurement of Fund Reporti IDA / 64650 Post Limited 25,000.00 0.00 Canceled 2022-10-22 2022-12-17 2023-01-16 ip and MSME growth tions nvelope ng Software for VCTF GH-MOFEP-323209-GO-RFQ / Accelerating entrepreneursh Request for Quota Single Stage - One E Procurement of 2No.Servers IDA / 64650 Post Limited 90,000.00 0.00 Canceled 2022-11-09 2023-01-04 2023-03-05 ip and MSME growth tions nvelope and Accessories for VCTF GH-MOFEP-323217-GO-RFQ / Supply and Installation of Vid Accelerating entrepreneursh Request for Quota Single Stage - One E IDA / 64650 Post Limited 100,000.00 0.00 Canceled 2022-11-09 2023-01-04 2023-03-05 eo and Audio Reproduction, a ip and MSME growth tions nvelope nd Networking Accessories fo r VCTF GH-MOFEP-328645-GO-RFQ / Printing of 7,500 copies of Tri fold-Brochures, 12 copies of Request for Quota Single Stage - One E Under Imple Publicity Materials, 4,675 cop IDA / 64650 Enabling investments Post Open - National 83,000.00 0.00 2022-12-19 2023-02-13 2023-04-14 tions nvelope mentation ies of Branded Conferencing Material, and 4,500 copies of Policy Framework for Trade Support GH-MOFEP-323197-GO-RFQ / Procurement of Office Equip ment ( Lot 1- 6 Desktop com puters, 14.Laptops, 1 shredd Accelerating entrepreneursh Request for Quota Single Stage - One E IDA / 64650 Post Limited 85,000.00 0.00 Canceled 2023-01-31 2023-03-21 2023-05-05 er, 6 Printers,14 UPS,15 Micr ip and MSME growth tions nvelope osoft Office and 40. Antivirus , Lot 2- 10. Tables 2. 4 in 1 w orkstation and 21. Chairs, 1 K ettle, 2 water dispensers, an d 2 Fridges) for VCTF GH-MOFEP-347759-GO-RFQ / Procurement of 4 pick-up veh Request for Quota Single Stage - One E IDA / 64650 Enabling investments Post Limited 400,000.00 0.00 Signed 2023-04-01 2023-03-29 2023-05-27 2023-08-25 icles and 1 Cross Country ve tions nvelope hicle for GIPC and GhaNAS. GH-MOFEP-355125-GO-RFB / Accelerating entrepreneursh Single Stage - One E Under Imple Procurement of IT Equipment IDA / 64650 Post Request for Bids Open - National 100,000.00 0.00 2023-04-13 2023-04-11 2023-04-18 2023-04-13 2023-05-09 2023-05-23 2023-06-20 2023-08-04 ip and MSME growth nvelope mentation to support VCTF Analyst prog ram GH-MOFEP-347732-GO-RFQ / Procurement of Office Equip ment for MoTI and GEA (3 Pri Crowding-in investments: Pr nters, 15 Dock station, 4 swiv omoting spatial and industri Request for Quota Single Stage - One E Under Imple IDA / 64650 Post Limited 90,000.00 0.00 2023-04-25 2023-05-16 2023-06-20 2023-08-19 el chairs, 2 cabinets,4mobile al planning and developmen tions nvelope mentation phones,1 camera, 1 tripod, 3 t office tables, 1 Drone,2 SD C ards, 10 Reflective jackets, 1 0 Safety Boots, 10 Helmets) GH-MOFEP-365291-GO-RFQ / Procurement of Networking A ccessories (2No.Networking t Request for Quota Single Stage - One E Under Imple IDA / 64650 Enabling investments Post Limited 55,000.00 0.00 2023-06-17 2023-08-12 2023-10-11 ool kits, 2,000 Nos CAT 6 Pat tions nvelope mentation ch cables, 20pck pass-throug h RJ45 Connectors,10No swit ches,1No Hub, etc.) for GIPC GH-MOFEP-365303-GO-RFQ / Procurement of IT Equipment and Accessories (40No Deskt Request for Quota Single Stage - One E Pending Impl IDA / 64650 Enabling investments Post Limited 100,000.00 0.00 2023-06-17 2023-08-12 2023-10-11 op Computer, 30No Laptop, 3 tions nvelope ementation No Tablet, 3No Amplifier, 40 No. Headphones etc. ) for GIP C Page 3 GH-MOFEP-365450-GO-RFB / Procurement of IT Equipment for NEIP ( 1No Television, 30 No Laptops, 2No Shredder, C Accelerating entrepreneursh Single Stage - One E Under Imple CTV Camera, 10No Mobile Ph IDA / 64650 Post Request for Bids Open - National 187,000.00 0.00 2023-06-12 2023-06-12 2023-06-17 2023-06-15 2023-07-17 2023-08-16 2023-09-20 2023-11-19 ip and MSME growth nvelope mentation ones, 20No Desktops Compu ters, 20No UPS, 10No Cables, 25No Phone Jack, 3No Rack, 3No Mobile workstation, 4No switches, 1No Phone server) NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GH-MOFEP-240321-NC-RFQ / Project management and ev Request for Quota Single Stage - One E Procure record, document m IDA / 64650 Post Limited 50,000.00 0.00 Canceled 2021-07-14 2021-09-08 2021-10-08 aluation tions nvelope anagement & Develop Websi te GH-MOFEP-365286-NC-RFQ / Request for Quota Single Stage - One E Pending Impl Recruit a service provider to IDA / 64650 Enabling investments Post Limited 100,000.00 0.00 2023-06-17 2023-08-12 2023-10-11 tions nvelope ementation scan and store 10,000 files fo r GIPC GH-MOFEP-365453-NC-RFQ / Accelerating entrepreneursh Request for Quota Single Stage - One E Pending Impl Recruit a Consultant to devel IDA / 64650 Post Limited 17,000.00 0.00 2023-06-17 2023-08-12 2023-10-11 ip and MSME growth tions nvelope ementation op a website for NEIP CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GH-MOFEP-106990-CS-CQS / Restructuring of National Ent Accelerating entrepreneursh Consultant Qualifi / Post Open - National 100,000.00 0.00 Canceled 2019-04-30 2019-05-21 2019-06-18 2019-07-02 2019-08-06 2019-12-04 repreneurship and Innovation ip and MSME growth cation Selection Plan (NEIP) Secretariat GH-MOFEP-106994-CS-CQS / Stakeholder Engagements an Consultant Qualifi d activities relating to the de / Enabling investments Post Open - National 100,000.00 0.00 Canceled 2019-05-14 2019-06-04 2019-07-18 2019-08-17 2019-09-21 2020-03-19 cation Selection velopment and finalization of the National Entrepreneurshi p Policy GH-MOFEP-134074-CS-CQS / CONSULTANCY SERVICES FO Accelerating entrepreneursh Consultant Qualifi IDA / 64650 Post Open - National 100,000.00 0.00 Canceled 2019-09-18 2019-10-02 2019-10-30 2019-11-20 2019-12-25 2020-02-23 R A STRATEGIC REVIEW OF V ip and MSME growth cation Selection ENTURE CAPITAL TRUST FUN D (VCTF) GH-MOFEP-144544-CS-CQS / Consultancy Services for the Feasibility study for the esta Accelerating entrepreneursh Consultant Qualifi Open - Internationa IDA / 64650 Post 100,000.00 48,375.00 Signed 2019-11-25 2019-12-13 2019-12-16 2020-01-13 2020-02-14 2020-02-03 2020-02-21 2020-03-09 2020-03-31 2020-05-08 blishment of two new funds ip and MSME growth cation Selection l of the Ghana Venture Capita l Trust Fund GH-MOFEP-144547-CS-CQS / Consultancy services for the I nstitutional Review and Prep Accelerating entrepreneursh Consultant Qualifi Open - Internationa IDA / 64650 Post 100,000.00 0.00 Canceled 2019-11-25 2019-12-16 2020-01-13 2020-02-03 2020-03-09 2020-08-06 aration and Implementation ip and MSME growth cation Selection l Support for a Reform Roadmap for Gh ana’s Venture Capital Trust F und GH-MOFEP-158150-CS-QBS / Consultancy services for the I nstitutional Review and Prep Accelerating entrepreneursh Quality Based Sel IDA / 64650 Post Open - National 100,000.00 420,000.00 Completed 2020-02-07 2020-04-01 2020-02-28 2020-04-12 2020-04-28 2020-05-10 2020-06-19 2020-06-09 2020-07-28 2020-07-09 2020-08-13 2020-08-13 2020-12-16 2021-08-13 2022-06-09 aration and Implementation ip and MSME growth ection Support for a Reform Roadm ap for Ghana’s Venture Capit al Trust Fund GH-MOFEP-183261-CS-QCBS Crowding-in investments: Pr / Procurement of Consultancy omoting spatial and industri Quality And Cost- Open - Internationa IDA / 64650 Post 205,000.00 191,982.00 Signed 2020-08-02 2021-03-03 2020-08-23 2021-03-16 2020-10-06 2021-06-18 2020-11-03 2021-10-08 2020-12-03 2021-10-21 2021-01-07 2022-01-19 2021-02-11 2022-05-11 2022-02-11 Services for Benchmarking a al planning and developmen Based Selection l nd Value Proposition Exercise t GH-MOFEP-200018-CS-CQS / Consultancy Services to Dev Accelerating entrepreneursh Consultant Qualifi IDA / 64650 Post Open - National 300,000.00 637,956.93 Signed 2020-10-23 2020-10-23 2020-11-06 2020-11-03 2020-11-27 2021-02-25 2020-12-18 2021-06-03 2021-01-15 2021-07-24 2024-12-25 elop Technology Platform for ip and MSME growth cation Selection Management of Funds for SM Es GH-MOFEP-200020-CS-CQS / Recruit a Firm to undertake T Accelerating entrepreneursh Consultant Qualifi echnical Assistance for SMEs IDA / 64650 Post Open - National 250,000.00 0.00 Canceled 2020-10-23 2020-10-23 2020-11-06 2020-11-27 2021-03-25 2020-12-18 2021-01-15 2024-12-25 ip and MSME growth cation Selection and Strengthening of NBSSI Support system for SMEs GH-MOFEP-200022-CS-CQS / Recruitment of a consultant f Accelerating entrepreneursh Consultant Qualifi or Outreach & Communicatio IDA / 64650 Post Open - National 200,000.00 134,984.16 Signed 2020-10-23 2020-10-23 2020-11-13 2020-11-03 2020-12-18 2021-02-25 2021-01-17 2021-09-21 2021-02-21 2021-11-23 2021-08-20 ip and MSME growth cation Selection ns of GET support for SMEs & the Call for Applications for N BSSI GH-MOFEP-133825-CS-CQS / CONSULTANCY SERVICES TO Consultant Qualifi IDA / 64650 Enabling investments Post Open - National 100,000.00 0.00 Canceled 2019-09-19 2019-10-03 2019-10-31 2019-11-21 2019-12-26 2020-06-23 DEVELOP A STRATEGY AND cation Selection BUSINESS PLAN FOR GIPC GH-MOFEP-204933-CS-QCBS / Recruitment of a Consultant Quality And Cost- Open - Internationa to Develop Business Strategy IDA / 64650 Enabling investments Post 200,000.00 182,972.75 Completed 2020-11-20 2020-11-20 2020-12-11 2020-11-25 2021-01-15 2021-06-14 2021-02-05 2021-07-14 2021-02-19 2021-08-20 2021-03-26 2021-12-14 2021-04-30 2022-01-18 2021-11-08 2023-01-03 Based Selection l and Plan for Ghana Investme nt Promotion Centre (GIPC) GH-MOFEP-204945-CS-CQS / Recruitment of a Consultant t Accelerating entrepreneursh Consultant Qualifi IDA / 64650 Post Open - National 50,000.00 65,773.30 Signed 2020-11-20 2021-03-24 2020-12-11 2021-04-01 2021-01-15 2021-07-29 2021-02-05 2021-10-07 2021-03-12 2021-11-23 2021-09-08 o Develop communication str ip and MSME growth cation Selection ategy and plan for rebrandin g of VCTF Page 4 GH-MOFEP-204948-CS-CQS / Consultancy Service to Cond uct Hr/Staff Skills Audit and D Accelerating entrepreneursh Least Cost Selecti IDA / 64650 Post Open - National 30,000.00 58,679.41 Completed 2020-11-20 2021-03-24 2020-12-11 2021-04-01 2021-01-15 2021-07-29 2021-02-05 2021-08-20 2021-02-26 2021-09-03 2021-04-02 2021-09-30 2021-05-07 2021-11-27 2021-06-21 2022-07-06 evelop a Multi-Year Capacity ip and MSME growth on Building Plan for Venture Cap ital Trust Fund GH-MOFEP-204953-CS-LCS / Recruitment of a Consultant t Accelerating entrepreneursh Least Cost Selecti o Conduct Information Comm IDA / 64650 Post Open - National 30,000.00 38,008.63 Completed 2020-11-20 2021-03-24 2020-12-11 2021-04-01 2021-01-15 2021-07-29 2021-02-12 2021-08-20 2021-03-05 2021-09-30 2021-04-09 2021-12-06 2021-05-14 2022-01-15 2021-06-14 2022-07-06 ip and MSME growth on unication Technology GAP An alysis for Venture Capital Tru st Fund GH-MOFEP-205379-CS-QCBS Crowding-in investments: Pr / Recruitment of a Consultant omoting spatial and industri Quality And Cost- Open - Internationa to Provide Technical Assistan IDA / 64650 Post 200,000.00 0.00 Canceled 2020-11-23 2021-03-23 2020-12-07 2021-04-01 2021-01-04 2021-06-18 2021-02-01 2021-07-16 2021-02-15 2021-08-13 2021-03-22 2021-04-26 2021-08-19 al planning and developmen Based Selection l ce for the formulation of the t Ghana Special Economic Zon es Policy GH-MOFEP-205397-CS-QCBS Crowding-in investments: Pr / Recruit a Consultant to und omoting spatial and industri Quality And Cost- Open - Internationa ertake Site Assessment and IDA / 64650 Prior 1,200,000.00 217,200.00 Completed 2020-11-23 2021-03-23 2020-12-14 2021-03-24 2021-01-11 2021-06-30 2021-02-08 2021-07-30 2021-02-22 2021-09-23 2021-03-29 2021-12-10 2021-05-03 2021-12-29 2021-07-14 2023-03-14 al planning and developmen Based Selection l Selection Exercise on Ghana’ t s Special Economic Zones & I ndustrial Park Program GH-MOFEP-225295-CS-CQS / Recruit Consultant to Undert Project management and ev Consultant Qualifi ake Environmental and Socia IDA / 64650 Post Limited 45,000.00 62,054.14 Signed 2021-04-30 2021-04-16 2021-05-14 2021-06-14 2021-06-13 2021-10-07 2021-07-18 2021-11-23 2021-09-16 aluation cation Selection l Safeguards Audit and ESMP for Tema Export Processing Z one GH-MOFEP-225297-CS-CQS / Crowding-in investments: Pr Recruit Consultant to Prepare omoting spatial and industri Consultant Qualifi IDA / 64650 Post Limited 180,000.00 328,179.84 Signed 2021-03-24 2021-03-24 2021-04-07 2021-04-09 2021-04-28 2021-06-08 2021-05-26 2021-07-24 2022-01-31 Bill of Quantities (BOQs) and al planning and developmen cation Selection Supervise Pre and Post Const t ruction Activities GH-MOFEP-227638-CS-CQS / RECRUITMENT OF A CONSUL TANT TO DEVELOP CORPORA TE STRATEGIC DOCUMENTS AND ORGANISATIONAL MANU Consultant Qualifi IDA / 64650 Enabling investments Post Open - National 150,000.00 294,000.00 Signed 2021-04-20 2021-06-18 2021-05-11 2021-06-28 2021-06-24 2022-02-17 2021-07-15 2022-05-06 2021-08-19 2022-07-08 2021-11-17 ALS FOR THE OFFICE OF THE cation Selection REGISTRAR OF COMPANIES ( ORC) AND THE REGISTRAR-G ENERAL’S DEPARTMENT (RG D) AND FACILITATE THE DEC OUPLING OF ORC FROM THE RGD GH-MOFEP-227641-CS-CQS / Recruitment of a Consultanc Accelerating entrepreneursh Consultant Qualifi y firm to Carry out Institution IDA / 64650 Post Open - National 100,000.00 100,000.00 Completed 2021-04-19 2021-05-06 2021-05-10 2021-06-28 2021-06-23 2021-08-26 2021-07-14 2021-11-12 2021-08-19 2021-12-27 2021-11-27 2023-01-01 ip and MSME growth cation Selection al Strengthening Assessment and Delivery of a Strategic Pl an Framework for NEIP GH-MOFEP-229081-CS-CQS / Recruit a Consultancy Firm f Consultant Qualifi IDA / 64650 Enabling investments Post Limited 150,000.00 0.00 Canceled 2021-04-30 2021-06-18 2021-05-14 2021-07-12 2021-06-13 2021-07-18 2022-01-14 or digitisation of Ghana Stan cation Selection dards Authority (GSA) proce ss and workflows GH-MOFEP-229174-CS-CQS / Recruit a Local Consultant for Consultant Qualifi IDA / 64650 Enabling investments Post Limited 60,000.00 0.00 Canceled 2021-04-30 2022-03-29 2021-05-14 2022-05-11 2021-06-13 2021-07-18 2022-04-14 preparatory activities for ISO cation Selection 9001 Certification GH-MOFEP-240297-CS-CQS / Recruit Consultant to design Accelerating entrepreneursh Consultant Qualifi a comprehensive Technical A IDA / 64650 Post Limited 50,000.00 0.00 Canceled 2021-06-28 2021-07-12 2021-08-11 2021-09-15 2021-11-14 ip and MSME growth cation Selection ssistance program for the ec osystem of Venture Capital T rust Fund. GH-MOFEP-240301-CS-CQS / Recruit Consultant to Prepare Crowding-in investments: Pr Environmental and Social Im omoting spatial and industri Consultant Qualifi IDA / 64650 Post Open - National 100,000.00 86,158.76 Signed 2021-06-28 2021-06-28 2021-07-12 2021-06-30 2021-08-16 2021-10-27 2021-09-06 2021-12-10 2021-10-11 2022-01-14 2022-01-09 pact Assessment (ESIA) for t al planning and developmen cation Selection he Greater Kumasi Industrial t City and Special Economic Zo nes Project GH-MOFEP-240304-CS-CQS / Crowding-in investments: Pr Recruit Consultant to Prepare omoting spatial and industri Consultant Qualifi Resettlement Action Plan (RA IDA / 64650 Post Open - National 150,000.00 119,542.35 Signed 2021-06-28 2021-06-28 2021-07-19 2021-06-30 2021-08-23 2021-10-27 2021-09-13 2021-12-10 2021-10-18 2022-01-12 2022-01-16 al planning and developmen cation Selection P) for the Greater Kumasi Ind t ustrial City and Special Econ omic Zones Project GH-MOFEP-240306-CS-LCS / Recruit Consultant to develo Accelerating entrepreneursh Least Cost Selecti IDA / 64650 Post Open - National 50,000.00 59,540.85 Signed 2021-06-28 2021-06-28 2021-07-12 2021-06-30 2021-08-16 2021-10-21 2021-09-13 2021-11-12 2021-10-04 2021-12-22 2021-11-08 2022-02-21 2021-12-13 2022-03-24 2022-03-13 p Standard Operating Proced ip and MSME growth on ures for Ghana Enterprises A gency (GEA) GH-MOFEP-240308-CS-LCS / Recruit Consultant to underta ke HR Assessment for the tra Accelerating entrepreneursh Least Cost Selecti IDA / 64650 Post Open - National 80,000.00 68,898.57 Signed 2021-06-28 2021-06-28 2021-07-19 2021-06-30 2021-08-23 2021-10-21 2021-09-20 2021-11-12 2021-10-11 2021-12-22 2021-11-15 2022-02-21 2021-12-20 2022-03-24 2022-04-19 nsitioning of the National Boa ip and MSME growth on rd for Small Scale Industries ( NBSSI) to Ghana Enterprises Agency (GEA). GH-MOFEP-240309-CS-LCS / Recruit Consultant to underta ke Communication and Bran Accelerating entrepreneursh Least Cost Selecti ding support services for the IDA / 64650 Post Open - National 65,000.00 44,778.88 Signed 2021-06-28 2021-06-28 2021-07-19 2021-06-30 2021-08-23 2021-10-21 2021-09-20 2021-11-12 2021-10-11 2021-12-22 2021-11-15 2022-02-21 2021-12-20 2022-03-24 2022-06-18 ip and MSME growth on transitioning of the National Board for Small Scale Industri es (NBSSI) to Ghana Enterpri ses Agency (GEA). GH-MOFEP-240320-CS-CQS / Recruit Consultant to Undert Project management and ev Consultant Qualifi IDA / 64650 Post Limited 70,000.00 80,000.00 Signed 2021-06-28 2021-06-28 2021-07-12 2021-07-12 2021-08-11 2021-10-13 2021-09-15 2021-11-23 2021-12-14 ake Baseline Assessment of t aluation cation Selection he Ghana Economic Transfor mation (GET) Project GH-MOFEP-242106-CS-QBS / Recruit Consultancy Service t Accelerating entrepreneursh Quality Based Sel Open - Internationa o undertake Technical Assist IDA / 64650 Prior 4,000,000.00 4,411,477.10 Signed 2021-06-30 2021-08-02 2021-07-21 2021-08-11 2021-09-03 2021-12-20 2021-10-01 2022-01-21 2021-10-31 2022-02-28 2021-11-30 2022-04-25 2022-01-04 2022-05-13 2026-01-03 ip and MSME growth ection l ance for High Growth SMEs a nd Strengthening of GEA Sup port System for SMEs Page 5 GH-MOFEP-253839-CS-CQS / Recruit Consultant to Review Accelerating entrepreneursh Consultant Qualifi IDA / 64650 Post Limited 65,000.00 68,852.46 Signed 2021-09-30 2021-12-17 2021-10-14 2021-12-21 2021-11-13 2022-03-03 2021-12-18 2022-04-15 2023-06-11 Bill of Quantities (BOQs), desi ip and MSME growth cation Selection gns and Supervision GH-MOFEP-263193-CS-CQS / Crowding-in investments: Pr Recruitment of Consultant to omoting spatial and industri Consultant Qualifi IDA / 64650 Post Open - National 100,000.00 0.00 Canceled 2021-11-30 2021-12-21 2022-02-03 2022-03-05 2022-04-09 2022-07-08 develop a Five-Year Corporat al planning and developmen cation Selection e Strategic Plan for Ghana Fr t ee Zone Authority GH-MOFEP-264701-CS-QBS / Recruitment of a Consultant t Accelerating entrepreneursh Quality Based Sel o develop Entrepreneurship IDA / 64650 Prior 1,700,000.00 0.00 Signed 2021-11-29 2021-11-29 2021-12-20 2021-12-13 2022-02-02 2022-03-17 2022-03-02 2022-04-29 2022-03-23 2022-08-25 2022-04-22 2022-10-19 2022-05-27 2024-05-26 ip and MSME growth ection Ecosystem, hubs Benchmarki ng and Capacity developmen t for NEIP GH-MOFEP-240319-CS-CQS / Crowding-in investments: Pr Consultant Qualifi Recruitment of Consultant to IDA / 64650 omoting spatial and industri Post Open - National 50,000.00 0.00 Canceled 2021-06-28 2021-06-28 2021-07-19 2021-08-23 2021-09-13 2021-10-18 2022-01-16 cation Selection facilitate Investment Promoti al planning and developmen on Events t GH-MOFEP-225290-CS-INDV Project management and ev Consultant Qualifi / Recruit a Consultant to Dev IDA / 64650 Post Open - National 50,000.00 0.00 Canceled 2021-04-19 2021-05-10 2021-06-23 2021-07-14 2021-08-18 2021-09-17 aluation cation Selection elop GETP Communication St rategy GH-MOFEP-290602-CS-CQS / Consultant Qualifi Engage a consultant to Desig IDA / 64650 Enabling investments Post Limited 100,000.00 0.00 Canceled 2022-04-25 2022-04-28 2022-05-09 2022-05-13 2022-06-08 2022-07-13 2022-10-11 cation Selection n the new ORC Office Buildin g GH-MOFEP-205401-CS-QCBS Crowding-in investments: Pr / Recruitment of a Consultant omoting spatial and industri Quality And Cost- IDA / 64650 Post Open - National 120,000.00 0.00 Canceled 2020-11-23 2021-04-16 2020-12-07 2021-05-14 2021-01-04 2021-02-01 2021-02-15 2021-03-22 2021-04-26 2021-08-19 to Design and Manage the Vi al planning and developmen Based Selection ability Gap Fund t GH-MOFEP-205412-CS-CQS / Consultancy services for Inde pendent Verification Agent to Project management and ev Consultant Qualifi IDA / 64650 Post Open - National 80,000.00 0.00 Canceled 2020-11-23 2021-03-03 2020-12-07 2021-03-16 2021-01-04 2021-01-18 2021-02-22 2021-05-05 verify the Disbursement Link aluation cation Selection ed Indicators (DLIs) of the Gh ana Economic Transformatio n Project GH-MOFEP-293924-CS-CQS / Recruitment of Consultant to Consultant Qualifi IDA / 64650 Enabling investments Post Limited 300,000.00 0.00 Signed 2022-05-22 2022-08-03 2022-06-05 2022-08-19 2022-06-26 2022-11-19 2022-07-31 2023-01-27 Migrate current ORC System cation Selection and Data to iCloud GH-MOFEP-302605-CS-CQS / Crowding-in investments: Pr Recruitment of a Consultant t omoting spatial and industri Consultant Qualifi o Provide Technical Assistanc IDA / 64650 Post Limited 300,000.00 0.00 Signed 2022-07-08 2022-07-18 2022-07-22 2022-07-27 2022-08-21 2022-08-31 2022-09-25 2022-12-24 al planning and developmen cation Selection e for the formulation of the G t hana Special Economic Zone s Policy GH-MOFEP-302607-CS-CQS / Consultant Qualifi Under Implement Procure and Deploy Custome IDA / 64650 Enabling investments Post Open - National 160,000.00 0.00 2022-07-08 2022-07-18 2022-07-29 2022-09-28 2022-09-11 2022-11-04 2022-10-11 2023-04-11 2022-11-15 2023-05-14 cation Selection ation r Relationship Management ( CRM) for GIPC GH-MOFEP-302611-CS-QCBS / Recruitment of Consultant t o Develop GSA Core process Quality And Cost- IDA / 64650 Enabling investments Prior Open - National 630,000.00 0.00 Signed 2022-07-08 2022-07-19 2022-07-29 2022-08-01 2022-09-11 2022-12-14 2022-10-09 2023-01-13 2022-10-30 2023-03-02 2022-12-04 2023-05-02 2023-01-08 2024-01-08 es, Customer Relationship M Based Selection anagement Software and Hu man Resource Management Software GH-MOFEP-312197-CS-QCBS Crowding-in investments: Pr / Consultancy Services for th omoting spatial and industri Quality And Cost- Open - Internationa e Development of a Master Pl IDA / 64650 Prior 1,200,000.00 0.00 Canceled 2022-09-01 2022-09-13 2022-10-01 2022-11-05 2022-12-03 2022-12-24 2023-01-28 2023-03-04 2023-07-02 al planning and developmen Based Selection l an and Feasibility Studies for t the Proposed Greater Kumasi Industrial City GH-MOFEP-312198-CS-CQS / Consultancy Services to Prep are Environmental and Social Management Systems for Ve Accelerating entrepreneursh Consultant Qualifi Under Implement IDA / 64650 Post Open - National 60,000.00 0.00 2022-09-01 2022-09-20 2022-09-22 2022-09-26 2022-10-27 2022-11-17 2022-12-22 2023-03-22 nture Capital Trust Fund (VC ip and MSME growth cation Selection ation TF), Ghana Enterprise Agenc y (GEA) and National Entrepr eneurship and Innovation Pr ogramme (NEIP) GH-MOFEP-312199-CS-CQS / Recruitment of a Communica Project management and ev Consultant Qualifi Under Implement tions Firm to Support the Gh IDA / 64650 Post Open - National 200,000.00 0.00 2022-09-05 2022-09-20 2022-09-26 2022-09-26 2022-10-31 2022-11-30 2023-01-04 2024-06-27 aluation cation Selection ation ana Economic Transformatio n Project Coordinating Unit GH-MOFEP-313512-CS-QCBS Crowding-in investments: Pr / Recruitment of Project Man omoting spatial and industri Quality And Cost- Open - Internationa Under Implement agement Consultant for Cons IDA / 64650 Prior 3,000,000.00 0.00 2022-09-08 2022-09-23 2022-09-29 2022-09-23 2022-11-12 2022-12-19 2022-12-10 2023-01-27 2023-01-09 2023-03-20 2023-02-13 2023-03-20 2025-03-19 al planning and developmen Based Selection l ation truction works for Greater Ku t masi Industrial City Project GH-MOFEP-313541-CS-QCBS / Recruitment of a Consultant Crowding-in investments: Pr for the Development, Installa omoting spatial and industri Quality And Cost- Under Implement IDA / 64650 Prior Open - National 500,000.00 0.00 2022-09-08 2022-09-23 2022-09-29 2022-09-26 2022-11-12 2023-01-13 2022-12-10 2023-03-01 2023-01-09 2023-05-08 2023-02-13 2023-06-09 2023-03-20 2024-03-19 tion, Management and Maint al planning and developmen Based Selection ation enance of a Single Window S t ystem for the Ghana Free Zo nes Authority GH-MOFEP-315989-CS-LCS / Recruitment of Consultant to Least Cost Selecti Under Implement conduct a Survey on Investor IDA / 64650 Enabling investments Post Open - National 100,000.00 0.00 2022-09-26 2022-09-22 2022-10-17 2022-10-05 2022-11-21 2022-12-20 2022-12-19 2023-01-18 2023-01-09 2023-02-24 2023-02-13 2023-03-20 2023-07-18 on ation Perceptions of Ghana's Inves tment Climate and Investme nt Promotion GH-MOFEP-316040-CS-LCS / Consultancy Service for the Development of a Web-Base Least Cost Selecti Under Implement IDA / 64650 Enabling investments Post Open - National 80,000.00 0.00 2022-09-26 2022-09-22 2022-10-17 2022-10-05 2022-11-21 2022-12-20 2022-12-19 2023-01-30 2023-01-09 2023-02-24 2023-02-13 2023-03-20 2023-09-16 d Monitoring and Evaluation on ation System for the Ghana Invest ment Promotion Centre (GIPC ) GH-MOFEP-316793-CS-QCBS Crowding-in investments: Pr / Consultancy Services for th omoting spatial and industri Quality And Cost- Open - Internationa Under Implement IDA / 64650 Prior 1,200,000.00 0.00 2022-09-26 2022-09-23 2022-10-17 2022-09-26 2022-11-21 2023-01-13 2022-12-19 2023-02-13 2023-01-09 2023-03-16 2023-02-13 2023-03-20 2023-06-18 e Development of a Master Pl al planning and developmen Based Selection l ation an for the Proposed Greater t Kumasi Industrial City Page 6 GH-MOFEP-318139-CS-QCBS / Recruitment of Consultant t Accelerating entrepreneursh Quality And Cost- o Conduct Feasibility Study, IDA / 64650 Post Open - National 250,000.00 0.00 Canceled 2022-10-05 2022-10-26 2022-11-30 2022-12-28 2023-01-18 2023-02-22 2023-03-29 2023-08-26 ip and MSME growth Based Selection Design and Set-up of the Mic ro, Small and Medium Enterp rises (MSME) Fund GH-MOFEP-319728-CS-QCBS / Recruitment of a Consultant Accelerating entrepreneursh Quality And Cost- to undertake feasibility study IDA / 64650 Post Open - National 250,000.00 0.00 Canceled 2022-10-17 2022-12-12 2022-11-07 2022-12-12 2023-01-09 2023-02-08 2023-03-15 2023-04-19 2023-09-16 ip and MSME growth Based Selection , design and set-up of the Mi cro Small and Medium Enterp rises (MSME) Fund GH-MOFEP-320385-CS-CQS / Recruitment of a Consultant t Accelerating entrepreneursh Consultant Qualifi Under Implement IDA / 64650 Post Limited 100,000.00 0.00 2022-10-17 2022-10-30 2022-10-31 2022-11-30 2023-01-04 2023-06-03 o develop a Web-Based M&E ip and MSME growth cation Selection ation system to support the NEIP GH-MOFEP-323384-CS-QCBS / Recruitment of a Program M anager for the Implementatio Accelerating entrepreneursh Quality And Cost- Open - Internationa Under Implement IDA / 64650 Prior 1,200,000.00 0.00 2022-11-04 2022-11-25 2022-12-30 2023-01-27 2023-02-17 2023-03-24 2023-04-28 2025-04-27 n of the Fund Manager Devel ip and MSME growth Based Selection l ation opment Program for the Vent ure Capital Trust Fund (VCTF) GH-MOFEP-328649-CS-CQS / Recruitment of Consultant to determine, develop, host, Pro Consultant Qualifi vide maintenance and Opera IDA / 64650 Enabling investments Post Open - National 100,000.00 0.00 Canceled 2022-12-14 2023-01-19 2023-01-04 2023-02-17 2023-03-19 2023-04-25 2023-10-24 cation Selection tional Support to the Ghana National Accreditation Servic e Information and Communic ation Technology Infrastructu re. GH-MOFEP-347747-CS-CQS / Recruitment of a Consultant t o Develop an Investor Grieva Consultant Qualifi Under Implement IDA / 64650 Enabling investments Post Open - National 150,000.00 0.00 2023-03-20 2023-03-17 2023-04-10 2023-04-04 2023-05-15 2023-06-14 2023-07-19 2023-12-16 nce Management Mechanism cation Selection ation (IGM) for the Ghana Investm ent Promotion Centre (GIPC) GH-MOFEP-347751-CS-CQS / Recruitment of a Consultant t o Conduct Training on Invest Consultant Qualifi Under Implement IDA / 64650 Enabling investments Post Open - National 200,000.00 0.00 2023-03-20 2023-05-22 2023-04-10 2023-05-15 2023-06-14 2023-07-19 2023-11-16 or Deal Making for the Busine cation Selection ation ss Development Team at the Ghana Investment Promotion Centre (GIPC) GH-MOFEP-347767-CS-CQS / Recruit a Consultant to under Consultant Qualifi Under Implement take preparatory activities to IDA / 64650 Enabling investments Post Open - National 90,000.00 0.00 2023-03-21 2023-05-22 2023-04-11 2023-05-25 2023-06-24 2023-07-29 2024-07-28 cation Selection ation wards ISO 9001:2015 certific ation of GSA procedures and processes GH-MOFEP-348100-CS-CQS / Recruitment of Consultant to Provide Training in ISO 1518 Consultant Qualifi Under Implement IDA / 64650 Enabling investments Post Open - National 200,000.00 0.00 2023-03-22 2023-03-17 2023-04-12 2023-04-04 2023-05-17 2023-06-07 2023-07-12 2023-10-24 9 and ISO/IEC 17025 to Supp cation Selection ation ort the Operationalization of the Ghana National Accredita tion Service (GhaNAS) GH-MOFEP-348108-CS-CQS / Recruitment of a Consultant t o Develop an ICT Manageme Consultant Qualifi Under Implement IDA / 64650 Enabling investments Post Open - National 170,000.00 0.00 2023-03-22 2023-03-27 2023-04-12 2023-04-25 2023-05-17 2023-06-07 2023-07-12 2024-02-07 nt System including a Databa cation Selection ation se, Automation of GhaNAS Pr ocedures/ Processes and Trai ning. GH-MOFEP-359008-CS-CQS / Recruitment of an Event Man Consultant Qualifi Under Implement IDA / 64650 Enabling investments Post Limited 50,000.00 0.00 2023-05-01 2023-04-28 2023-05-11 2023-05-21 2023-06-14 2023-09-12 agement Firm to Manage the cation Selection ation Market Expedition in Kenya GH-MOFEP-365282-CS-CQS / Consultancy services for Inde pendent Verification Agent to Project management and ev Consultant Qualifi Under Implement IDA / 64650 Post Open - National 100,000.00 0.00 2023-06-12 2023-07-03 2023-08-16 2023-09-15 2023-10-20 2025-10-19 verify the Disbursement Link aluation cation Selection ation ed Indicators (DLIs) of the Gh ana Economic Transformatio n Project INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GH-MOFEP-103063-CS-INDV / Consultancy for the Prepara Project management and ev Individual Consult Under Implement tion of Environmental and So / Prior Limited 40,000.00 0.00 2019-02-26 2019-03-03 2019-01-08 2019-03-24 2021-09-29 2019-04-28 2019-06-27 aluation ant Selection ation cial Management Framework (ESMF) and Resettlement Poli cy Framework (RPF) GH-MOFEP-106986-CS-INDV / Review of National Board f or Small Scale Industry (NBS Accelerating entrepreneursh Individual Consult / Post Limited 50,000.00 0.00 Canceled 2019-04-25 2019-04-30 2019-05-21 2019-06-25 2019-10-23 SI) ACT ip and MSME growth ant Selection To tailor the functions and ob jects of the ACT to the vision of conversion of NBSSI into a n Authority GH-MOFEP-106989-CS-INDV / Project Management Trainin Accelerating entrepreneursh Individual Consult / Post Limited 20,000.00 0.00 Canceled 2019-04-25 2019-04-30 2019-05-21 2019-06-25 2019-12-22 g of the core team that will ip and MSME growth ant Selection manage and report on the ac tivities. GH-MOFEP-106993-CS-INDV / Review of NEIP and NBSS C urrent training manuals, oper Individual Consult ating procedures for busines / Enabling investments Post Open 130,000.00 0.00 Canceled 2019-05-06 2019-06-24 2019-07-15 2019-08-19 2020-02-15 ant Selection s advisory centres and busin ess resource centres and dev elopment of revised curriculu m and training content GH-MOFEP-106995-CS-INDV / Implementation Plan and Ro Individual Consult / Enabling investments Post Limited 50,000.00 0.00 Canceled 2019-05-07 2019-05-12 2019-06-02 2019-07-07 2020-01-03 ad Map for the National Entre ant Selection preneurship policy Page 7 GH-MOFEP-106996-CS-INDV / Review of National Enterpre Individual Consult neurship and Innovation Plan / Enabling investments Post Limited 60,000.00 0.00 Canceled 2019-05-13 2019-05-18 2019-06-08 2019-07-13 2020-01-09 ant Selection (NEIP) and National Board for Small Scale Industry (NBSSI) M&E systems GH-MOFEP-106999-CS-INDV / Review of Service Delivery Individual Consult Processes of core Service De / Enabling investments Post Open 15,000.00 0.00 Canceled 2019-05-21 2019-07-09 2019-07-30 2019-09-03 2020-03-01 ant Selection partments and develop revis ed Processes to enhance effi ciency. GH-MOFEP-133800-CS-INDV / Consultancy Services to Pro vide Technical Support for Pr oject Component One: Enabli Accelerating entrepreneursh Individual Consult IDA / 64650 Post Open 120,000.00 1,170.66 Signed 2019-09-19 2020-10-16 2019-10-14 2021-03-02 2019-10-28 2021-03-15 2019-12-02 2021-03-30 2021-11-21 ng Investment- Improving th ip and MSME growth ant Selection e enabling business environ ment, investment promotion capacity and quality infrastru cture support system. GH-MOFEP-133813-CS-INDV / Consultancy Service to Prov Crowding-in investments: Pr ide Technical Support for Proj omoting spatial and industri Individual Consult IDA / 64650 Post Open 120,000.00 4,000.00 Signed 2019-09-19 2020-10-16 2019-10-22 2021-02-11 2019-11-12 2021-03-15 2019-12-10 2021-03-31 2021-11-29 ect Component Two: Crowdin al planning and developmen ant Selection g-in Investments- Promoting t spatial and industrial plannin g and development. GH-MOFEP-133819-CS-INDV / Consultancy Services to Pro Individual Consult vide Technical Support for Pr IDA / 64650 Enabling investments Post Open 120,000.00 4,000.00 Signed 2019-09-19 2020-04-07 2019-10-22 2020-06-12 2019-11-05 2020-07-06 2019-12-10 2020-08-28 2021-11-29 ant Selection oject Component Three: Acce lerating Entrepreneurship an d SME Growth. GH-MOFEP-128155-CS-INDV / Consultancy Services for th Project management and ev Individual Consult e development of Project Imp IDA / 64650 Post Limited 52,250.00 25,000.00 Completed 2019-09-19 2019-06-19 2019-09-24 2019-07-03 2019-10-15 2019-12-03 2019-11-19 2020-02-04 2020-05-17 2020-07-07 aluation ant Selection lementation Manual (PIM) of t he Ghana Economic Transfor mation (GET) Project GH-MOFEP-144585-CS-INDV / Consultancy Services for th Accelerating entrepreneursh Individual Consult e Revision of the Strategic Pl IDA / 64650 Post Open 100,000.00 50,000.00 Signed 2019-11-06 2019-11-06 2019-12-09 2020-02-18 2020-07-10 2020-02-20 2020-08-14 2020-04-04 2020-11-12 ip and MSME growth ant Selection an for the National Board for Small Scale Industries (NBSSI ) 2018 - 2023 GH-MOFEP-160140-CS-INDV Project management and ev Individual Consult / Consultancy services for th IDA / 64650 Post Open 120,000.00 4,700.00 Signed 2020-02-19 2020-04-07 2020-03-23 2020-06-12 2020-04-13 2020-07-06 2020-05-18 2020-08-28 2022-05-18 aluation ant Selection e recruitment of Procuremen t Specialist GH-MOFEP-160141-CS-INDV / Consultancy services for th Project management and ev Individual Consult IDA / 64650 Post Open 120,000.00 4,000.00 Signed 2020-02-19 2020-04-07 2020-03-30 2020-06-12 2020-04-20 2020-07-06 2020-05-25 2020-08-28 2022-05-25 e recruitment for Environmen aluation ant Selection tal and Social Risk Managem ent Specialist GH-MOFEP-167851-CS-INDV Project management and ev Individual Consult / RECRUITMENT OF PROJECT IDA / 64650 Post Open 120,000.00 6,500.00 Completed 2020-04-07 2020-04-07 2020-05-17 2020-07-23 2020-06-07 2020-08-19 2020-07-12 2020-08-31 2022-07-02 2022-09-09 aluation ant Selection COORDINATOR GH-MOFEP-172005-CS-INDV Accelerating entrepreneursh Individual Consult / Procurement of Individual C IDA / 64650 Prior Open 40,000.00 4,100.00 Signed 2020-05-13 2021-03-12 2020-07-01 2021-03-19 2020-07-22 2021-03-19 2020-08-26 2021-04-02 2021-02-22 ip and MSME growth ant Selection onsultant as Grant Manager GH-MOFEP-172009-CS-INDV Accelerating entrepreneursh Individual Consult IDA / 64650 Post Open 12,000.00 2,800.00 Signed 2020-05-13 2020-05-01 2020-07-01 2020-10-07 2020-07-22 2020-11-20 2020-08-26 2021-03-11 2021-02-22 / Procurement of Grant Acco ip and MSME growth ant Selection untant GH-MOFEP-172011-CS-INDV Accelerating entrepreneursh Individual Consult IDA / 64650 Post Open 30,000.00 1,220.58 Signed 2020-05-13 2020-05-01 2020-07-01 2020-10-07 2020-07-22 2020-11-20 2020-08-26 2021-03-11 2021-02-22 / Procurement of two Grant O ip and MSME growth ant Selection fficers GH-MOFEP-172013-CS-INDV Accelerating entrepreneursh Individual Consult / Procurement of Monitoring IDA / 64650 Post Open 20,000.00 0.00 Canceled 2020-05-27 2020-07-15 2020-08-05 2020-09-09 2021-03-08 ip and MSME growth ant Selection and Evaluation Specialist GH-MOFEP-186397-CS-INDV Crowding-in investments: Pr / Procurement of Individual C omoting spatial and industri Individual Consult onsultant for the Developme IDA / 64650 Post Open 50,000.00 34,460.00 Completed 2020-07-29 2020-08-03 2020-09-16 2020-11-18 2020-10-07 2021-03-15 2020-11-11 2021-05-16 2021-05-10 2022-09-26 al planning and developmen ant Selection nt of the Ghana National Accr t editation Service Strategic Pl an GH-MOFEP-197534-CS-INDV Project management and ev Individual Consult / Procurement of Monitoring IDA / 64650 Post Open 40,000.00 4,500.00 Signed 2020-10-01 2020-09-16 2020-11-19 2021-02-11 2020-12-10 2021-03-15 2021-01-14 2021-03-31 2021-07-13 aluation ant Selection and Evaluation Specialist GH-MOFEP-197535-CS-INDV Project management and ev Individual Consult / Procurement of Procuremen IDA / 64650 Post Open 15,000.00 2,700.00 Signed 2020-10-01 2020-10-02 2020-11-19 2021-02-11 2020-12-10 2021-03-15 2021-01-14 2021-03-31 2021-07-13 aluation ant Selection t Assistant GH-MOFEP-225275-CS-INDV Project management and ev Individual Consult IDA / 64650 Post Limited 24,000.00 2,500.00 Signed 2021-03-31 2021-03-23 2021-04-05 2021-06-03 2021-04-26 2021-06-30 2021-05-31 2021-08-07 2023-05-31 / Recruitment of Office Mana aluation ant Selection ger GH-MOFEP-225279-CS-INDV Project management and ev Individual Consult IDA / 64650 Post Limited 18,000.00 1,621.62 Signed 2021-03-31 2021-03-23 2021-04-05 2021-06-03 2021-04-26 2021-06-30 2021-05-31 2021-08-07 2023-05-31 / Recruitment of Project Offic aluation ant Selection er for PCU GH-MOFEP-225281-CS-INDV Project management and ev Individual Consult IDA / 64650 Post Limited 18,000.00 1,621.62 Signed 2021-03-31 2021-03-22 2021-04-05 2021-06-03 2021-04-26 2021-06-30 2021-05-31 2021-08-14 2023-05-31 / Recruitment of Safeguard A aluation ant Selection ssistant GH-MOFEP-225284-CS-INDV Project management and ev Individual Consult IDA / 64650 Post Limited 18,000.00 2,500.00 Signed 2021-03-31 2021-03-23 2021-04-05 2021-06-03 2021-04-26 2021-06-30 2021-05-31 2021-08-14 2023-05-31 / Recruitment of M & E Assist aluation ant Selection ant GH-MOFEP-225285-CS-INDV Project management and ev Individual Consult IDA / 64650 Post Limited 12,000.00 0.00 Canceled 2021-03-31 2021-04-05 2021-04-26 2021-05-31 2023-05-31 / Recruitment of 2 Project Dri aluation ant Selection vers GH-MOFEP-225287-CS-INDV / Recruit a Consultant to Dev Project management and ev Individual Consult IDA / 64650 Post Limited 85,000.00 85,192.20 Signed 2021-03-24 2021-03-23 2021-03-29 2021-04-27 2021-04-19 2021-08-27 2021-05-24 2021-11-09 2021-07-23 elop and Setup an IT Based G aluation ant Selection rievance Redress Mechanism Platform GH-MOFEP-225289-CS-INDV Project management and ev Individual Consult / Recruit a Consultant to Und IDA / 64650 Post Limited 50,000.00 45,930.00 Signed 2021-04-19 2021-03-22 2021-04-24 2021-04-27 2021-05-15 2021-08-27 2021-06-19 2021-11-09 2021-08-03 aluation ant Selection ertake Gender Gap Analysis Page 8 GH-MOFEP-225292-CS-INDV Project management and ev Individual Consult / Recruit Consultant to Devel IDA / 64650 Post Direct 30,000.00 0.00 Canceled 2021-03-24 2021-03-26 2021-04-03 2021-04-24 2021-05-29 2021-06-28 aluation ant Selection op Independent Verification Manual GH-MOFEP-229073-CS-INDV / Recruitment of a Consultant Accelerating entrepreneursh Individual Consult IDA / 64650 Post Open 50,000.00 0.00 Canceled 2021-04-19 2021-06-07 2021-06-28 2021-08-02 2021-10-01 to design Technical Assistant ip and MSME growth ant Selection program for the Venture Cap ital Trust Fund (VCTF) GH-MOFEP-107004-CS-INDV / Consultancy services for th Project management and ev Individual Consult e Setting up of the Economic / Post Limited 25,000.00 0.00 Canceled 2019-06-11 2019-06-16 2019-07-07 2019-08-11 2019-11-09 aluation ant Selection Transformation Project (ETP) Project Cordinating Unit (PCU ) GH-MOFEP-107003-CS-INDV Project management and ev Individual Consult / Consultancy services for th / Post Open 18,000.00 0.00 Canceled 2019-04-16 2019-06-04 2019-06-25 2019-07-30 2020-01-26 aluation ant Selection e Procurement of M&E Expert GH-MOFEP-259204-CS-INDV Individual Consult / Recruitment of IT Expert to IDA / 64650 Enabling investments Post Limited 42,000.00 3,200.00 Signed 2021-11-29 2021-12-17 2021-12-04 2021-12-20 2021-12-25 2022-02-18 2022-01-29 2022-04-30 2023-01-29 ant Selection support Business Regulatory Reform (BRR) GH-MOFEP-262871-CS-INDV Accelerating entrepreneursh Individual Consult IDA / 64650 Post Limited 20,000.00 1,600.00 Signed 2021-11-29 2022-01-26 2021-12-04 2022-02-01 2021-12-25 2022-03-28 2022-01-29 2022-05-05 2024-01-29 / Recruitment of M & E Office ip and MSME growth ant Selection r for GEA GH-MOFEP-262872-CS-INDV Accelerating entrepreneursh Individual Consult IDA / 64650 Post Limited 15,000.00 2,000.00 Signed 2021-11-29 2021-11-24 2021-12-04 2022-01-26 2021-12-25 2022-03-28 2022-01-29 2022-05-05 2024-01-29 / Recruitment of Grant Office ip and MSME growth ant Selection r for GEA GH-MOFEP-263208-CS-INDV / Recruitment of Research As Individual Consult IDA / 64650 Enabling investments Post Limited 24,000.00 1,800.00 Signed 2021-11-29 2021-12-17 2021-12-04 2021-12-20 2021-12-25 2022-02-18 2022-01-29 2022-04-30 2023-01-29 sistant to support the Busine ant Selection ss Regulatory Reform (BRR) unit. GH-MOFEP-259202-CS-INDV Accelerating entrepreneursh Individual Consult / Recruitment of Project Offic IDA / 64650 Post Limited 20,000.00 1,600.00 Signed 2021-11-29 2021-12-01 2021-12-04 2022-01-26 2021-12-25 2022-03-28 2022-01-29 2022-05-05 2024-01-29 ip and MSME growth ant Selection er for GEA - 2 GH-MOFEP-263201-CS-INDV Accelerating entrepreneursh Individual Consult / Recruitment of Project Offic IDA / 64650 Post Limited 20,000.00 1,600.00 Signed 2021-11-29 2021-12-01 2021-12-04 2022-01-26 2021-12-25 2022-03-28 2022-01-29 2022-05-05 2024-01-29 ip and MSME growth ant Selection er for GEA - 3 GH-MOFEP-264224-CS-INDV Accelerating entrepreneursh Individual Consult / Recruitment of Project Offic IDA / 64650 Post Limited 20,000.00 1,600.00 Signed 2021-11-29 2021-11-23 2021-12-04 2022-01-26 2021-12-25 2022-03-28 2022-01-29 2022-05-05 2024-01-29 ip and MSME growth ant Selection er for GEA - 1 GH-MOFEP-161038-CS-INDV Accelerating entrepreneursh Individual Consult / Consultant services to dev IDA / 64650 Post Limited 3,000.00 0.00 Canceled 2020-02-27 2020-03-03 2020-03-10 2020-03-31 2020-06-29 ip and MSME growth ant Selection elop creative materials and c ontent GH-MOFEP-263211-CS-INDV Individual Consult / Recruitment of Office Assist IDA / 64650 Enabling investments Post Limited 18,000.00 0.00 Canceled 2021-11-29 2021-12-17 2021-12-04 2021-12-20 2021-12-25 2022-01-29 2023-01-29 ant Selection ant to support BRR GH-MOFEP-312345-CS-INDV / Recruitment of Senior Oper Project management and ev Individual Consult IDA / 64650 Post Limited 48,000.00 0.00 Signed 2022-09-05 2022-09-08 2022-09-10 2022-09-26 2022-10-01 2022-11-21 2022-11-05 2023-11-05 ations Officer for Project Coor aluation ant Selection dination Unit (PCU) GH-MOFEP-262870-CS-INDV Individual Consult / Recruitment of a Legal Advi IDA / 64650 Enabling investments Post Limited 54,000.00 0.00 Canceled 2021-11-29 2021-12-17 2021-12-04 2021-12-20 2021-12-25 2022-01-29 2023-01-29 ant Selection ser to MoTI -BRR GH-MOFEP-259199-CS-INDV Project management and ev Individual Consult / Recruitment of M & E Speci IDA / 64650 Post Limited 54,000.00 0.00 Canceled 2021-10-29 2021-11-23 2021-11-03 2021-12-13 2021-11-24 2021-12-29 2022-12-29 aluation ant Selection alist for Economic Transform ation Unit (ETU) GH-MOFEP-319462-CS-INDV / Recruitment of Consultant t Accelerating entrepreneursh Individual Consult Under Implement IDA / 64650 Post Limited 60,000.00 0.00 2022-10-17 2022-10-26 2022-10-22 2022-11-12 2022-12-17 2023-12-17 o Design and Implement VCT ip and MSME growth ant Selection ation F Analyst Program GH-MOFEP-320377-CS-INDV / Recruitment of a Consultant Accelerating entrepreneursh Individual Consult Under Implement to commence the Process to IDA / 64650 Post Limited 100,000.00 0.00 2022-10-17 2023-06-22 2022-10-22 2022-11-21 2022-12-26 2024-12-25 ip and MSME growth ant Selection ation wards the Development of a Limited Partnership Act for V CTF GH-MOFEP-319756-CS-INDV Individual Consult Under Implement / Recruitment of a Legal Advi IDA / 64650 Enabling investments Post Limited 108,000.00 0.00 2022-10-17 2023-01-19 2022-10-22 2022-11-12 2022-12-17 2024-12-16 ant Selection ation ser for Business Regulatory R eforms GH-MOFEP-319774-CS-INDV Individual Consult / Engage a Consultant to Des IDA / 64650 Enabling investments Post Limited 100,000.00 0.00 Canceled 2022-10-17 2022-10-22 2022-11-12 2022-12-17 2023-06-15 ant Selection ign the new ORC Office Buildi ng GH-MOFEP-347776-CS-INDV Crowding-in investments: Pr / Recruitment of a Special Ec omoting spatial and industri Individual Consult Under Implement onomic Zones (SEZ) Expert t IDA / 64650 Post Open - National 70,000.00 0.00 2023-03-22 2023-03-17 2023-05-10 2023-05-31 2023-07-05 2025-07-04 al planning and developmen ant Selection ation o Coordinate Industrial Parks t and other related activities fo r MoTI. Page 9 Procurement Plan General 1. Bank’s approval Date of the procurement Plan January 28, 2022 2. Date of General Procurement Notice: February 22, 2022 3. Period covered by this procurement plan: 18 Months (January 2022 to August, 2023) II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Annex II to the Regulation for Procurement: No. Procurement Method Prior Review Threshold Comments US$ 1. ICB and LIB (Goods) Above US$ 2,000,000 All 2. NCB (Goods) Above US$ 2,000,000 All 3. ICB (Works) Above US$ 10,000,000 All 4. NCB (Works) Above US$ 10,000,000 All 5. (Non-Consultant Services) Above US$ 2,000,000 All 2. Prequalification. Bidders when applicable_ shall be prequalified in accordance with the provisions of paragraphs 6.23 and 6.24 of the Regulation. 3. Proposed Procedures for CDD Components (as per paragraph. 6.9 of the Regulations: Not applicable 4. Reference to (if any) Project Operational/Procurement Manual: Project Implementation Manual for World Bank Loan Project 5. Any Other Special Procurement Arrangements: Not Applicable 6. Summary of the Procurement Packages planned during the first 18 months after project effectiveness (including those that are subject to retroactive financing and advanced procurement) 1 2 3 4 5 6 7 Estimate Domesti Review Ref d Packag c by Bank . Description Cost es Prefere (Prior / Comments No. US$ nce Post) million (yes/no) January 17, 2022 Summary of the 1 RFB- 8.200 2 No Prior International/DIR. (Goods) Summary of the 2 RFB-National/RFQ 7.584 12 No Post (Goods) 3 Summary of the RFB-International, 9.000 1 No Prior Dir/Limited (Works) 4 Summary of the RFB-National/RFQ 13.049 9 No Post (Works) III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Annex II to the Regulation Selection and Employment of Consultants: Selection Method Prior Review Threshold Comments 1. Competitive Methods Above US$ 1,000,000 (Firms) 2. Single Source (Firms) All 3. Individual Above US$ 300,000 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $300,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of the Consultant Regulations 3. Any Other Special Selection Arrangements: Not Applicable 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 Ref Description of Estimated Review . Assignment Cost Packag by Bank Commen No. US$ es (Prior / ts million Post) Summary of 2.000 3 Prior 1number of contracts that will be let under QCBS Summary of 26 2 number of 2.488 Post contracts that will January 17, 2022 be let under other methods January 17, 2022 PROCUREMENT Western and Central Africa : West Africa Food System Resilience Program (FSRP) Phase 2 PLAN General Information Country: Western and Central Africa 2022-05-24 Bank’s Approval Date of the Original Procurement Plan: 2023-06-06 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P178132 GPN Date: 2023-06-27 Project Name: West Africa Food System Resilience Program (FSRP) Phase 2 Loan / Credit No: IDA / V4240, IDA / 71950 Ministry of Food and Agriculture - Phase 2 Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GH-FSRP PHASE 2-312496-N Request for Quota Single Stage - One E Pending Impl C-RFQ / Supply and Installati IDA / 71950 Project Management Post Limited 10,000.00 0.00 2022-09-26 2022-11-21 2023-01-20 tions nvelope ementation on of Accounting Software CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GH-FSRP PHASE 2-295997-C S-CQS / Consultancy services Sustainability and Adaptive for Feasibility studies of Lot 1 Consultant Qualifi Under Implement IDA / V4240 Capacity of the Food System Post Limited 100,000.00 0.00 2022-06-07 2022-10-05 2022-06-21 2022-11-15 2022-07-05 2022-08-02 2022-09-21 : Development of inland valle cation Selection ation 's Productive Base ys at Jeduako, Asare Nkwant a rice valley (Skere Central), and Agona (Skyere South) GH-FSRP PHASE 2-296002-C S-CQS / Consultancy services Sustainability and Adaptive for Feasibility studies of Lot 2 Consultant Qualifi Under Implement IDA / V4240 Capacity of the Food System Post Limited 100,000.00 0.00 2022-06-08 2022-10-05 2022-06-22 2022-11-11 2022-07-07 2022-08-04 2022-09-23 : Development of inland valle cation Selection ation 's Productive Base ys at Barekese (Atwima Nwa biagya), Juaben (Juaben), an d Donuaso (Ejusu) GH-FSRP PHASE 2-299185-C Consultant Qualifi Under Implement S-CQS / Consultancy Service IDA / V4240 Project Management Post Limited 80,000.00 0.00 2022-06-15 2022-06-09 2022-06-29 2022-06-27 2022-07-14 2022-08-07 2022-09-26 cation Selection ation for the baseline survey for FS RP GH-FSRP PHASE 2-323066-C S-CQS / CONSULTANCY FOR THE PREPARATION OF ENVIR Sustainability and Adaptive ONMENTAL AND SOCIAL IMP Consultant Qualifi Under Implement IDA / 71950 Capacity of the Food System Post Limited 80,000.00 0.00 2022-11-17 2022-11-15 2022-12-01 2022-12-31 2023-02-04 2023-08-03 ACTS ASSESSMENT (ESIA) AN cation Selection ation 's Productive Base D ENVIRONMENTAL AND SOC IAL MANAGEMENT PLANS (ES MPs) FOR SELECTED INLAND VALLEYS IN THE ASHANTI RE GION- LOT 1 GH-FSRP PHASE 2-323065-C S-CQS / CONSULTANCY FOR THE PREPARATION OF ENVIR Sustainability and Adaptive ONMENTAL AND SOCIAL IMP Consultant Qualifi Under Implement IDA / 71950 Capacity of the Food System Post Limited 80,000.00 0.00 2022-11-17 2022-11-15 2022-12-01 2022-12-31 2023-02-04 2023-08-03 ACTS ASSESSMENT (ESIA) AN cation Selection ation 's Productive Base D ENVIRONMENTAL AND SOC IAL MANAGEMENT PLANS (ES MPs) FOR SELECTED INLAND VALLEYS IN THE ASHANTI RE GION- LOT 2 GH-FSRP PHASE 2-323064-C S-CQS / CONSULTANCY FOR THE PREPARATION OF ENVIR Sustainability and Adaptive ONMENTAL AND SOCIAL IMP Consultant Qualifi Under Implement IDA / 71950 Capacity of the Food System Post Limited 80,000.00 0.00 2022-11-17 2022-11-15 2022-12-01 2022-12-31 2023-02-04 2023-08-03 ACTS ASSESSMENT (ESIA) AN cation Selection ation 's Productive Base D ENVIRONMENTAL AND SOC IAL MANAGEMENT PLANS (ES MPs) FOR SELECTED INLAND VALLEYS IN THE ASHANTI RE GION- LOT 3 GH-FSRP PHASE 2-323063-C S-CQS / CONSULTANCY FOR THE PREPARATION OF ENVIR Sustainability and Adaptive ONMENTAL AND SOCIAL IMP Consultant Qualifi Under Implement IDA / 71950 Capacity of the Food System Post Limited 150,000.00 0.00 2022-11-17 2022-11-11 2022-12-01 2022-12-31 2023-02-04 2023-08-03 ACTS ASSESSMENT (ESIA) AN cation Selection ation 's Productive Base D ENVIRONMENTAL AND SOC IAL MANAGEMENT PLANS (ES MPs) FOR SELECTED INLAND VALLEYS IN THE BONO EAST REGION GH-FSRP PHASE 2-323067-C S-CQS / Consultancy for the f Sustainability and Adaptive easibility Studies for develop Consultant Qualifi Under Implement IDA / 71950 Capacity of the Food System Post Limited 200,000.00 0.00 2022-11-30 2022-11-11 2022-12-14 2023-01-13 2023-02-17 2023-08-16 ment of selected Inland Valle cation Selection ation 's Productive Base ys for improved Rainfed Agri cultural Production Bono East -LOT 3 GH-FSRP PHASE 2-323068-C S-CQS / Consultancy for the f Sustainability and Adaptive easibility Studies for develop Consultant Qualifi Under Implement IDA / 71950 Capacity of the Food System Post Limited 200,000.00 0.00 2022-11-30 2022-11-11 2022-12-14 2023-01-13 2023-02-17 2023-08-16 ment of selected Inland Valle cation Selection ation 's Productive Base ys for improved Rainfed Agri cultural Production Bono East -LOT 4 Page 1 GH-FSRP PHASE 2-312497-C S-CQS / Consultancy Service Consultant Qualifi IDA / 71950 Project Management Post Limited 25,000.00 0.00 Canceled 2022-10-05 2022-10-19 2022-11-18 2022-12-23 2023-06-21 for Updating of National Irrig cation Selection ation Policy and Strategic Pla n for GIDA GH-FSRP PHASE 2-343254-C Digital Advisory Services for S-CQS / Consultancy Service Consultant Qualifi Pending Impleme IDA / V4240 Agriculture and Food Crisis P Post Limited 80,000.00 0.00 2023-02-22 2023-03-08 2023-04-07 2023-05-12 2023-11-08 for the assessment of the Hy cation Selection ntation reventionand Management dromet, Agrimet, and Agro-a dvisory Systems GH-FSRP PHASE 2-347906-C S-CQS / Consultancy Service Sustainability and Adaptive for Update of Engineering De Consultant Qualifi Under Implement IDA / V4240 Capacity of the Food System Post Limited 80,000.00 0.00 2023-05-16 2023-05-03 2023-05-30 2023-06-29 2023-08-03 2024-01-30 sign and Construction Superv cation Selection ation 's Productive Base ision for the rehabilitation of the Tanoso Irrigation Scheme (TIS) GH-FSRP PHASE 2-365051-C Consultant Qualifi Pending Impleme S-CQS / Recruitment of Cons IDA / 71950 Project Management Post Limited 30,000.00 0.00 2023-06-12 2023-06-26 2023-07-26 2023-08-30 2023-11-28 cation Selection ntation ultant to develop Project We bsite GH-FSRP PHASE 2-343156-C Least Cost Selecti Under Implement S-LCS / Consultancy for Finan IDA / V4240 Project Management Post Open - National 90,000.00 0.00 2023-06-16 2023-06-15 2023-06-30 2023-07-20 2023-07-25 2023-08-04 2023-08-22 2023-09-08 2023-10-08 on ation cial Audit for FSRP (FISCAL Ye ar 2022-2025) INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GH-FSRP PHASE 2-296005-C S-INDV / Consultancy service Individual Consult IDA / V4240 Project Management Post Direct 40,000.00 0.00 Canceled 2022-06-06 2022-07-20 2022-06-16 2022-07-07 2022-08-11 2022-09-10 to prepare ESIA Lot 1: Wheta ant Selection & Tanoso Irrigation Schemes GH-FSRP PHASE 2-296009-C S-INDV / Consultancy service Individual Consult to prepare ESIA Lot 2: Jeduak IDA / V4240 Project Management Post Direct 40,000.00 0.00 Canceled 2022-06-09 2022-07-22 2022-06-19 2022-07-10 2022-08-14 2022-09-13 ant Selection o, Asare Nkwanta, Barekese, Agona, Juaben, and Donuaso Inland Valleys GH-FSRP PHASE 2-296019-C S-CDS / Consultancy service f Sustainability and Adaptive Under Implement or the preparation of the da IDA / V4240 Capacity of the Food System Post Direct Selection Direct 80,000.00 0.00 2022-05-31 2022-06-21 2022-06-10 2022-08-14 2022-09-13 ation m safety assessment ( Tanos 's Productive Base o, Wheta and affected Inland valleys) GH-FSRP PHASE 2-296338-C S-INDV / Consultancy service Individual Consult for Identification of appropria IDA / V4240 Project Management Post Limited 25,000.00 0.00 Signed 2022-06-08 2022-06-21 2022-06-13 2022-07-05 2022-07-04 2022-08-26 2022-08-08 2022-09-07 ant Selection te grant model to support th e youth, women and SMEs GH-FSRP PHASE 2-296339-C S-INDV / Recruitment of Cons Individual Consult IDA / V4240 Project Management Post Limited 80,000.00 0.00 Signed 2022-06-10 2022-06-01 2022-06-15 2022-07-13 2022-07-06 2022-07-19 2022-08-10 2022-09-29 ultant to develop Project Impl ant Selection ementation Manual GH-FSRP PHASE 2-296340-C S-INDV / Recruitment of Cons Individual Consult Under Implement IDA / V4240 Project Management Post Limited 30,000.00 0.00 2022-06-15 2022-08-30 2022-06-20 2022-07-11 2022-08-15 2022-09-24 ultant to develop Project Co ant Selection ation mmunications Strategy GH-FSRP PHASE 2-296342-C Individual Consult S-INDV / Recruitment of Cons IDA / V4240 Project Management Post Limited 50,000.00 0.00 Signed 2022-06-08 2022-06-07 2022-06-13 2022-06-09 2022-07-04 2022-07-25 2022-08-08 2022-09-27 ant Selection ultant to develop project M& E manuals MOFA/FSRP/PPA/IC/2022/07 / Recruitment of Social Safegu IDA / V4240 Project Management Post Direct Selection Direct 45,000.00 54,000.00 Signed 2022-01-03 2022-01-03 2022-01-13 2021-12-30 2022-03-19 2022-01-29 2022-09-15 ard Specialist for FSRP MOFA/FSRP/PPA/IC/2022/04 / Recruitment of Procurement IDA / V4240 Project Management Post Direct Selection Direct 25,000.00 35,000.00 Signed 2022-01-03 2022-01-03 2022-01-13 2021-12-30 2022-03-19 2022-01-18 2022-09-15 Specialist for FSRP MOFA/FSRP/PPA/IC/2022/05 / Recruitment of Financial Ma IDA / V4240 Project Management Post Direct Selection Direct 55,000.00 66,000.00 Signed 2022-01-03 2022-01-03 2022-01-13 2021-12-30 2022-03-19 2022-01-29 2022-09-15 nagement Specialist for FSRP MOFA/FSRP/PPA/IC/2022/10 / IDA / V4240 Project Management Post Direct Selection Direct 45,000.00 54,000.00 Signed 2022-01-03 2022-01-03 2022-01-13 2021-12-30 2022-03-19 2022-01-29 2022-09-15 Recruitment of Agric Econom ist for FSRP MOFA/FSRP/PPA/IC/2022/06 / Recruitment of Agribusiness IDA / V4240 Project Management Post Direct Selection Direct 50,000.00 60,000.00 Signed 2022-01-03 2022-01-03 2022-01-13 2021-12-30 2022-03-19 2022-01-29 2022-09-15 Specialist for FSRP MOFA/FSRP/PPA/IC/2022/09 / Recruitment of Environment IDA / V4240 Project Management Post Direct Selection Direct 45,000.00 54,000.00 Signed 2022-01-03 2022-01-03 2022-01-13 2021-12-30 2022-03-19 2022-01-29 2022-09-15 al Safeguard Specialist for FS RP MOFA/FSRP/PPA/IC/2022/03 / Recruitment of Snr. Rural Inf IDA / V4240 Project Management Post Direct Selection Direct 50,000.00 60,000.00 Signed 2022-01-03 2022-01-03 2022-01-13 2021-12-30 2022-03-19 2022-01-18 2022-09-15 rastructure Engineer for FSRP MOFA/FSRP/PPA/IC/2022/01 / Recruitment of Project Coord IDA / V4240 Project Management Post Direct Selection Direct 65,000.00 78,000.00 Signed 2022-01-03 2022-01-03 2022-01-13 2021-12-30 2022-03-19 2022-01-29 2022-09-15 inator for FSRP MOFA/FSRP/PPA/IC/2022/08 / IDA / V4240 Project Management Post Direct Selection Direct 45,000.00 54,000.00 Signed 2022-01-03 2022-01-03 2022-01-13 2021-12-30 2022-03-19 2022-01-29 2022-09-15 Recruitment of M & E Specia list for FSRP MOFA/FSRP/PPA/IC/2022/02 / Recruitment of Opration Ma IDA / V4240 Project Management Post Direct Selection Direct 55,000.00 66,000.00 Signed 2022-01-03 2022-01-03 2022-01-13 2021-12-30 2022-03-19 2022-01-29 2022-09-15 nager for FSRP GH-FSRP PHASE 2-298765-C S-INDV / Consultancy service Individual Consult IDA / V4240 Project Management Post Direct 40,000.00 0.00 Signed 2022-06-20 2022-06-09 2022-06-30 2022-09-28 2022-07-21 2022-09-29 2022-08-11 2022-09-20 to Update ESIA for KIS and V ant Selection EA Irrigation Schemes Page 2 GH-FSRP PHASE 2-295995-C S-CDS / Consultancy services Sustainability and Adaptive Under Implement to Update, Review UPDATE O IDA / V4240 Capacity of the Food System Post Direct Selection Direct 80,000.00 0.00 2022-07-20 2022-07-26 2022-07-30 2022-10-26 2022-10-03 2022-11-12 ation F DAM SAFETY ASSESSMENT 's Productive Base OF VEA DAM Irrigation Sche me GH-FSRP PHASE 2-312495-C Individual Consult Under Implement S-INDV / Recruitment of Proc IDA / 71950 Project Management Prior Open - National 60,000.00 0.00 2022-09-13 2022-09-14 2022-11-01 2023-01-06 2022-11-22 2023-02-21 2022-12-27 2023-12-22 ant Selection ation urement Specialist GH-FSRP PHASE 2-323069-C S-INDV / CONSULTANCY FOR Individual Consult Pending Impleme IDA / 71950 Project Management Post Limited 10,000.00 0.00 2022-11-30 2022-12-05 2022-12-26 2023-01-30 2023-07-29 THE PREPARATION OF Emerg ant Selection ntation ency Response Manual (ERM) GH-FSRP PHASE 2-296020-C Digital Advisory Services for S-INDV / Consultancy service Individual Consult IDA / V4240 Agriculture and Food Crisis P Post Limited 80,000.00 0.00 Canceled 2022-06-30 2022-07-05 2022-07-26 2022-08-30 2022-09-29 for the assessment of the hy ant Selection reventionand Management dromet, agrimet and agro-ad visory systems GH-FSRP PHASE 2-343716-C Individual Consult Under Implement S-INDV / Recruitment of Com IDA / 71950 Project Management Post Open - National 60,000.00 0.00 2023-03-01 2023-06-17 2023-04-19 2023-05-10 2023-06-14 2024-06-08 ant Selection ation munications & Outreach Spe cialist GH-FSRP PHASE 2-343250-C S-INDV / Consultancy Service to prepare Environmental an Individual Consult Pending Impleme d Social Impact Assessment ( IDA / V4240 Project Management Post Limited 80,000.00 0.00 2023-02-20 2023-02-25 2023-03-18 2023-04-22 2023-10-19 ant Selection ntation ESIA) and Environmental and Social Management Plan (ES MP) for Lot 2: Weta Irrigation Scheme GH-FSRP PHASE 2-296015-C S-INDV / Consultancy service Individual Consult Pending Impleme IDA / V4240 Project Management Post Limited 40,000.00 0.00 2023-06-26 2023-07-01 2023-07-22 2023-08-26 2024-02-22 to prepare RAP Lot 1: Weta ant Selection ntation & Tanoso Irrigation Schemes GH-FSRP PHASE 2-295996-C S-CDS / Consultancy services Sustainability and Adaptive for Update, Review and Engi IDA / V4240 Capacity of the Food System Post Direct Selection Direct 40,000.00 0.00 Canceled 2022-05-31 2023-02-21 2022-06-10 2022-08-14 2022-09-23 neering Design for selected ir 's Productive Base rigation systems/schemes -L ot 2: Completion of Tanoso Ir rigation Scheme Page 3 PROCUREMENT Tunisia : TN-Road Transport Corridors PLAN General Information Country: Tunisia 2017-03-03 Bank’s Approval Date of the Original Procurement Plan: 2023-06-05 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P146502 GPN Date: Project Name: TN-Road Transport Corridors Loan / Credit No: IBRD / 85190 Direction General des ponts et chaussees Executing Agency(ies): WORKS Activity Reference No. / Procureme Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH Ri Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method nt Docume ount (US$ and Recommendation Signed Contract o. h cess (Y/N) sk atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion nt Type ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual D2015-3 / Liaison de Tataoui ne avec l'Autoroute A1-lot3 : Open - Internationa Single Stage - One E 2020-02-2 IBRD / 85190 Road Corridor Improvement Prior Request for Bids 0.00 Canceled 2017-10-09 2017-11-01 2017-12-01 2018-02-02 2018-02-23 Liaison de Tataouine (L=12.1 l nvelope 3 96Km) dans le gouvernorat d e Medenine D2015-2 / Liaison de Tataoui ne avec l'Autoroute A1-lot2 : Liaison de Tataouine (L=17.9 Open - Internationa Single Stage - One E 2020-08-2 IBRD / 85190 Road Corridor Improvement Prior Request for Bids 0.00 Canceled 2017-10-09 2017-11-01 2017-12-01 2018-02-02 2018-02-23 87Km) & Route de rétablisse l nvelope 3 ment de Bir Lahmar (L=7.30 6Km) dans le gouvernorat de Tataouine. D2015 / Liaison de Tataouin Open - Internationa Single Stage - One E 40,333,162. 2020-09-0 e avec l'Autoroute A1 dans le IBRD / 85190 Road Corridor Improvement Prior Request for Bids Signed 2017-11-07 2018-01-09 2017-11-14 2017-12-14 2018-02-12 2019-01-17 2018-03-05 2019-04-03 l nvelope 00 2 s Gouvernorats de Medenine et Tataouine D2015-1 / Liaison de Tataoui ne avec l'Autoroute A1 - lot1 : Déviation de Tataouine nou Open - Internationa Single Stage - One E 2020-08-2 IBRD / 85190 Road Corridor Improvement Prior Request for Bids 0.00 Canceled 2017-10-06 2017-11-01 2017-12-01 2018-02-02 2018-02-23 velle (L=3.716Km) et liaison l nvelope 3 de Tataouine (L=13.5Km) da ns le gouvernorat de Tataoui ne A2015-1 / Modernisation et Open - Internationa Single Stage - One E 16,919,381. 2018-04-1 mise en 2x2 voies de la RN1 IBRD / 85190 Road Corridor Improvement Prior Request for Bids Signed 2015-07-02 2015-11-30 2016-02-02 2016-05-17 2017-03-29 2016-07-20 2016-09-22 l nvelope 61 6 2 du pk 5 au pk 54 - Lot 1 A2015-3 / Modernisation et Open - Internationa Single Stage - One E 15,344,574. 2017-06-1 mise en 2x2 voies de la RN1 IBRD / 85190 Road Corridor Improvement Prior Request for Bids Signed 2015-07-02 2015-11-30 2016-02-02 2016-12-08 2017-12-06 2016-12-16 2016-12-16 l nvelope 15 4 2 du pk 5 au pk 54 - Lot 3 A2015-4 / Modernisation et Open - Internationa Single Stage - One E 9,968,837.9 2018-04-1 mise en 2x2 voies de la RN1 IBRD / 85190 Road Corridor Improvement Prior Request for Bids Signed 2015-07-02 2015-11-30 2016-02-02 2016-05-17 2017-03-29 2016-07-12 2016-07-12 l nvelope 5 6 2 du pk 5 au pk 54 - Lot 4 A2015-5 / Modernisation et Open - Internationa Single Stage - One E 4,330,461.1 2018-04-1 mise en 2x2 voies de la RN1 IBRD / 85190 Road Corridor Improvement Prior Request for Bids Signed 2015-07-02 2015-11-30 2016-02-02 2016-05-17 2017-03-29 2016-07-12 2016-07-15 l nvelope 1 6 2 du pk 5 au pk 54 - Lot 5 C2015-1 / Modernisation et Open - Internationa Single Stage - One E 17,571,633. 2018-06-1 mise en 2x2 voies de la RN4 IBRD / 85190 Road Corridor Improvement Prior Request for Bids Signed 2015-08-03 2016-03-22 2016-05-24 2016-07-18 2017-03-29 2016-09-22 2016-07-20 l nvelope 86 4 du pk 0 au pk 65 - lot 1 A2015-2 / Modernisation et Open - Internationa Single Stage - One E 22,565,221. 2018-04-1 mise en 2x2 voies de la RN1 IBRD / 85190 Road Corridor Improvement Prior Request for Bids Signed 2015-12-01 2015-12-06 2016-01-17 2016-02-16 2017-03-28 2016-07-20 2016-07-20 l nvelope 10 6 2 du pk 5 au pk 54 - Lot 2 B2015-1-2 / Mise en 2x2 voi Open - Internationa Single Stage - One E 27,173,865. 2018-04-1 es de la RR133 du pk 0 au pk IBRD / 85190 Road Corridor Improvement Prior Request for Bids Signed 2015-06-26 2015-12-15 2016-02-16 2016-05-04 2017-03-29 2016-07-20 2016-07-20 l nvelope 74 3 22+500 - Lots 1 et 2 C2015-3 / Modernisation et Open - Internationa Single Stage - One E 14,109,442. Under Revie 2018-06-1 mise en 2x2 voies de la RN4 IBRD / 85190 Road Corridor Improvement Prior Request for Bids 2015-08-03 2016-03-22 2016-05-24 2016-07-18 2017-03-29 2016-09-22 2016-09-22 l nvelope 33 w 4 du pk 0 au pk 65 - lot 3 C2015-2 / Modernisation et Open - Internationa Single Stage - One E 15,619,624. 2018-06-1 mise en 2x2 voies de la RN4 IBRD / 85190 Road Corridor Improvement Prior Request for Bids Signed 2015-08-03 2016-03-22 2016-05-24 2016-07-18 2017-03-29 2016-09-22 2016-09-22 l nvelope 30 4 du pk 0 au pk 65 - lot 2 C2015-4 / Modernisation et Open - Internationa Single Stage - One E 16,096,566. Under Revie 2018-06-1 mise en 2x2 voies de la RN4 IBRD / 85190 Road Corridor Improvement Prior Request for Bids 2015-08-03 2016-03-22 2016-05-24 2016-07-18 2017-03-29 2016-10-12 2016-10-12 l nvelope 53 w 4 du pk 0 au pk 65 - lot 4 GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual A2/2015 / Contrats de Perfor Quality And Cost- Open - Internationa IBRD / 85190 Road Corridor Improvement Post 285,662.45 Signed 2016-05-27 2016-05-31 2016-10-03 2016-11-15 2017-01-31 2017-03-30 2017-07-07 2017-07-07 2018-01-16 mance (CP) Based Selection l E2015 / Assistance au Maître Consultant Qualifi Under Implement IBRD / 85190 Road Corridor Improvement Post Open - National 0.00 2023-06-05 2023-06-15 2023-07-13 2023-07-27 2023-08-24 2024-08-18 d’Ouvrage (AMO) cation Selection ation Page 1 A1/2015 / Base de Données Quality And Cost- Open - Internationa IBRD / 85190 Road Corridor Improvement Post 724,590.41 Signed 2016-05-27 2016-05-31 2016-10-21 2016-11-25 2017-03-30 2017-04-25 2017-08-02 2017-05-30 2017-08-02 2018-05-30 Routières (BDR) Based Selection l INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Actual Amount Invitation to Identifie Draft Negotiated Cont Component Review Type Method Contract Type Process Status Teams of Reference Signed Contract Contract Completion Description o. h (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 2 Procurement Plan I. General 1. Bank’s approval Date of the procurement Plan: Mat negotiations May 28, 2019. 2. Date of General Procurement Notice: to be published I Aug/Sep 2019 3. Period covered by this procurement plan: The procurement period of project covered from year Aug 2019-Sep 2020 II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement for Moderate Risk Projects: Procurement Method Prior Review Comments Threshold US$ 1. ICB and LIB (Goods) US$ 4 million All 2. NCB (Goods) US$ 4 million All 3. ICB (Works) US$ 15 million All 4. NCB (Works) US$ 15 million All 5. (Non-Consultant Services) US$ 4 million All 2. Prequalification. Bidders for _Not applicable_ shall be prequalified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines. 3. Reference to (if any) Project Operational/Procurement Manual: Procurement Manual is being prepared and shall be discussed in Aug 17 2019 mission. 4. Any Other Special Procurement Arrangements: Not Applicable 5. Summary of the Procurement Packages planned during the first 18 months after project effectiveness The main contract include three works contracts and one IT contract. The procurement activity table is annexed. Aug 8, 2017 III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Comments Threshold 1. Competitive Methods (Firms) Above US$ 2 m 2. Single Source (Firms) Above US $ 2 m Justification alongwith identification of SSS in procurement plan 3. Individual Above US$ 400, 000 In addition the selection of procurement staff 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_500,000_equivalent per contract, may comprise entirely of national consultants in accordance with the OPCS guidance. 3. Any Other Special Selection Arrangements: [including advance procurement and retroactive financing, if applicable or delete if not applicable] 4. Consultancy Assignments with Selection Methods and Time Schedule: There are a number of activities for consultancy contracts. The procurement activity table is annexed which indicted the identified activities. Aug 8, 2017 Procurement Activities S Ref Activity Est Procuremen Risk Review N No cost t Approach Type USD m Component 1 1 1a Design of and HR plan 1.5 Consultancy Substantial Prior &1b and trainings to KWSB QCBS staff, Software and hardware of HR system 2 2a, b Design and impl. of 1.2 Consultancy Moderate Post communication and QCBS customer relation strategy programs 3 2c Construction of six 0.65 Works NCB Low Post service centers 4 2b Design and Superv. 0.05 Consultancy Low Post Firm for above CQS 5 3a Development of a GIS 0.95 IT contract Moderate Post 6 3b Design and 1 Consultancy Moderate Post Implementation of an QCBS Asset Management Program 7 4a & Customer survey, tariff 1 Consultancy Moderate Post 4b review, revised billing QCBS system 8 5a & Design of NRW 1.5 Consultancy Substantial Prior 5b program and metering QCBS system 9 6a & Strategy for Katchi 1.1 Consultancy Substantial Prior 6b abadi cell and gender QCBS action program 10 7a Monitoring industrial 0.7 Consultancy Substantial Post discharge into QCBS sewerage and storm water; Drafting of indirect (industrial) discharge regulations into the sewerage; Priority sewer lines condition survey and rehabilitation design (incl. trenchless) 11 8 Study on FM best 0.3 Consultancy Moderate Post practices CQS Component 2 12 1 Rehabilitating water 5 Works NCB low Post supply and/or sewerage in three low income communities Aug 8, 2017 S Ref Activity Est Procuremen Risk Review N No cost t Approach Type USD m 13 2 Priority sewer network 16 Works NCB Moderate Prior rehabilitation 14 3 Priority Water Network 20 Works NCB Moderate Prior Rehabilitation including meters & DMAs to reduce NRW 15 4 Reducing energy 19 Supply & Moderate Prior consumption install ICB 16 5 Sewage Suction and 10 Goods ICB Moderate Prior Jetting Trucks Component 3 17 1 Preparing specific 2.5 Consultancy Moderate Prior safeguard documents QCBS for SOP 2 18 2 Project Management 3 Consultancy Substantial Prior Consultants QCBS 19 3 Design & Tender 2 Consultancy Moderate Prior Documents and QCBS supervision for SOP-1 19 4 Conduct Energy Audit 0.5 Consultancy Substantial Post QCBS 20 5, 6 PPP Options Study for 2.0 Consultancy Substantial Prior NRW Reduction; QCBS Options Study and/or transaction advice for PPP operation and investment for desalination and/or wastewater reuse 21 7 Rapid Groundwater 0.5 Consultancy Moderate Post Protection Assessment QCBS 22 8 Updating of KWSB’s 4.0 Consultancy Moderate Prior Masterplan QCBS 23 9 Feasibility & Tender 4.0 Consultancy Substantial Prior Documents for QCBS selected investments under SOP 2 24 PIU staff for FM; 1.5 Individual Moderate Post procurement and Consultants contract management; technical support; social env; communications Aug 8, 2017 PROCUREMENT Pakistan : Karachi Water and Sewerage Services Improvement Project (KWSSIP) PLAN General Information Country: Pakistan 2019-11-16 Bank’s Approval Date of the Original Procurement Plan: 2023-06-01 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P164704 GPN Date: 2019-10-30 Project Name: Karachi Water and Sewerage Services Improvement Project (KWSSIP) Loan / Credit No: IBRD / 89940 Karachi Water and Sewerage Board Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned PK-KWSB-200911-CW-RFQ / Operational & Enabling Envir Request for Quota Single Stage - One E Under Imple 2021-04-1 Rehabilitation & Refurbishme IBRD / 89940 Post Open - National 90,000.00 0.00 2020-12-15 2020-11-23 2021-02-09 onment Reform tions nvelope mentation 0 nt of Project Implementation Unit PIU Office PK-KWSB-200902-CW-RFB / Priority Water Network Reha Operational & Enabling Envir Single Stage - One E Pending Imp 2021-11-2 IBRD / 89940 Post Request for Bids Open - National 5,000,000.00 0.00 2021-02-01 2021-02-06 2021-03-20 2021-04-19 2021-05-24 bilitation ( Supply& Install Wa onment Reform nvelope lementation 0 ter Meters to Bulk Customer s) PK-KWSB-309204-CW-RFB / Request for Bids - Package KA-1 Rehabilitating Operational & Enabling Envir Single Stage - One E Small Works SPD 11,020,000.0 2023-06-1 Water Supply and Sewerage i IBRD / 89940 Post Request for Bids Open - National 0.00 Canceled 2022-08-28 2022-09-02 2022-10-14 2022-11-13 2022-12-18 onment Reform nvelope (1 envelope proce 0 6 n Tekri Village under LOT-1 w ss) orks and Soba Nagar, Gohara bad under LOT-2 works. Request for Bids - PK-KWSB-309246-CW-RFB / Operational & Enabling Envir Single Stage - One E Small Works SPD Pending Imp 2024-01-0 IBRD / 89940 Post Request for Bids Open - National 700,000.00 0.00 2023-03-15 2023-03-20 2023-05-01 2023-05-31 2023-07-05 Construction of Six Service C onment Reform nvelope (1 envelope proce lementation 1 enters. ss) PK-KWSB-316201-CW-RFB / Request for Bids - Package KA-1 Rehabilitating Single Stage - One E Small Works SPD 11,020,000.0 2024-03-1 Water Supply and Sewerage i IBRD / 89940 Infrastructure Investments Prior Request for Bids Open - National 0.00 Canceled 2022-09-19 2022-09-24 2022-11-05 2022-12-05 2023-01-09 nvelope (1 envelope proce 0 9 n Tekri Village under LOT-1 w ss) orks and Soba Nagar, Gohara bad under LOT-2 works. PK-KWSB-320941-CW-RFQ / Request for Quota Package-I: Repair/Replaceme Request for Quota Single Stage - One E tions - Small Work 2022-12-2 nt of Damaged Sections of W IBRD / 89940 Infrastructure Investments Post Open - National 6,000,000.00 0.00 Canceled 2022-10-14 2022-10-26 tions nvelope s (Emergency) SP 5 ater Lines and Sewers on Peo D -Competitive ples Bus Service Routes in Di fferent Districts of Karachi PK-KWSB-320972-CW-RFQ / Request for Quota Package-II: Repair/Replacem Request for Quota Single Stage - One E tions - Small Work 2023-01-0 ent of Damaged Sections of IBRD / 89940 Infrastructure Investments Post Open - National 4,000,000.00 0.00 Signed 2022-10-25 2022-11-10 2022-11-07 tions nvelope s (Emergency) SP 6 Water Lines and Sewers in Di D -Competitive fferent Districts of Karachi PK-KWSB-323866-CW-RFQ / Package-I: Repair/Replaceme nt of Damaged Sections of W Request for Quota ater Lines and Sewers on Peo Request for Quota Single Stage - One E tions - Small Work 2023-01-2 IBRD / 89940 Infrastructure Investments Post Open - National 6,000,000.00 0.00 Signed 2022-10-28 2022-10-31 2022-11-26 ples Bus Service Routes in Di tions nvelope s (Emergency) SP 5 fferent Districts of Karachi D -Competitive Lot-1 [District East] Lot-2 [District Korangi & Malir ] Lot-3 [District Central & Kem PK-KWSB-325427-GO-RFB / ari] Contract Package G-1 Request for Bids - Open - Internationa Single Stage - One E 10,550,000.0 Under Imple 2025-06-3 Supply and Installation of Bul IBRD / 89940 Infrastructure Investments Prior Request for Bids Plant SPD (withou 0.00 2022-11-09 2022-11-27 2022-11-10 2022-12-01 2022-12-22 2023-03-07 2023-01-21 2023-02-25 l nvelope 0 mentation 0 k Flow Meters t prequalification) under Component-2, SOP-I PK-KWSB-320984-CW-RFQ / Package-III: Repair/Replacem ent of Damaged Sections of Water Lines and Sewers in Di Request for Quota fferent Districts of Karachi Request for Quota Single Stage - One E tions - Small Work 2023-01-1 IBRD / 89940 Infrastructure Investments Post Open - National 2,500,000.00 0.00 Canceled 2022-11-04 2022-11-23 2022-11-16 Lot-1 [District West] tions nvelope s (Emergency) SP 5 Lot-2 [District South] D -Competitive Lot-3 [District Keamari] Lot-4 [Manhole Cover with Ri ng Slab] PK-KWSB-321023-CW-RFB / Construction and Protection/ Request for Bids - Rehabilitation work for G.K C Single Stage - One E Small Works SPD 10,920,000.0 Under Imple 2023-08-0 IBRD / 89940 Infrastructure Investments Post Request for Bids Open - National 0.00 2022-12-05 2023-02-17 2022-12-10 2023-02-17 2023-01-09 2023-03-31 2023-02-08 2023-06-15 2023-03-15 onduit, K-11, K-11I, 84" diam nvelope (1 envelope proce 0 mentation 2 eter Balance Convince and 3 ss) 6" diameter Malir main at Ma lir River Bed Phase-I and Pha se-Ill PK-KWSB-320993-CW-RFB / REPLACEMENT OF RISING MA Request for Bids - IN NO: 05 WITH X-42 GRADE Single Stage - One E Small Works SPD Under Imple 2024-07-1 IBRD / 89940 Infrastructure Investments Post Request for Bids Open - National 7,000,000.00 0.00 2023-03-16 2023-03-15 2023-03-21 2023-03-24 2023-04-20 2023-05-09 2023-05-20 2023-06-24 STEEL 72” (1800MM) DIA MS nvelope (1 envelope proce mentation 7 RISING MAIN FROM DHABEJI ss) PUMPING COMPLEX TO FORE BAY HIGH POINT. PK-KWSB-351424-CW-RFQ / Package-III: Repair/Replacem ent of Damaged Sections of Water Lines and Sewers in Di Request for Quota fferent Districts of Karachi Request for Quota Single Stage - One E tions - Small Work 2023-11-1 IBRD / 89940 Infrastructure Investments Post Open - National 2,500,000.00 0.00 Signed 2023-03-26 2023-05-21 Lot-1 [District West] tions nvelope s (Emergency) SP 7 Lot-2 [District South] D -Competitive Lot-3 [District Keamari] Lot-4 [Manhole Cover with Ri ng Slab] PK-KWSB-200906-CW-RFB / Request for Bids - Contract Package G-2: Suppl Operational & Enabling Envir Open - Internationa Single Stage - One E Under Imple 2024-09-2 IBRD / 89940 Post Request for Bids Plant SPD (withou 1,114,341.00 0.00 2023-06-01 2023-06-05 2023-06-06 2023-06-05 2023-07-18 2023-08-17 2023-09-21 y and Installation of Intermitt onment Reform l nvelope mentation 0 t prequalification) ent Chlorination Stations und er Component-2, SoP-I Request for Bids - PK-KWSB-366239-CW-RFB / Single Stage - One E Small Works SPD Pending Imp 2024-10-0 Package KA-1: Rehabilitating IBRD / 89940 Infrastructure Investments Post Request for Bids Open - National 1,260,000.00 0.00 2023-06-12 2023-06-17 2023-07-29 2023-08-28 2023-10-02 nvelope (1 envelope proce lementation 1 Water Supply and Sewerage i ss) n Soba Nagar Page 1 Request for Bids - PK-KWSB-309186-CW-RFB / Single Stage - One E Small Works SPD Pending Imp 2024-09-2 Contract Package S-1-Priority IBRD / 89940 Infrastructure Investments Post Request for Bids Open - National 1,600,000.00 0.00 2023-06-20 2023-06-25 2023-07-25 2023-08-24 2023-09-28 nvelope (1 envelope proce lementation 7 Sewer Network Rehabilitation ss) of Teen Hatti PK-KWSB-368997-CW-RFB / Request for Bids - Construction of Center of Ref Operational & Enabling Envir Single Stage - One E Small Works SPD Pending Imp 2024-10-1 IBRD / 89940 Post Request for Bids Open - National 3,000,000.00 0.00 2023-06-26 2023-07-01 2023-08-12 2023-09-11 2023-10-16 orm, Research and Innovatio onment Reform nvelope (1 envelope proce lementation 5 n (CERRI) Building at Shahra ss) h-e-Faisal, Karachi Request for Bids - PK-KWSB-369067-CW-RFB / Single Stage - One E Small Works SPD Pending Imp 2024-10-2 Package KA-2: Rehabilitating IBRD / 89940 Infrastructure Investments Post Request for Bids Open - National 2,300,000.00 0.00 2023-07-13 2023-07-18 2023-08-17 2023-09-16 2023-10-21 nvelope (1 envelope proce lementation 0 Water Supply and Sewerage i ss) n Essa Nagri Request for Bids - PK-KWSB-309250-CW-RFB / Single Stage - One E Small Works SPD Pending Imp 2024-07-1 Priority Water Network Reha IBRD / 89940 Infrastructure Investments Post Request for Bids Open - National 2,400,000.00 0.00 2023-10-01 2023-10-06 2023-11-17 2023-12-17 2024-01-21 nvelope (1 envelope proce lementation 9 bilitation - 3 DMAs ss) Request for Bids - PK-KWSB-369068-CW-RFB / Operational & Enabling Envir Single Stage - One E Small Works SPD Pending Imp 2024-04-0 Construction of Six Customer IBRD / 89940 Post Request for Bids Open - National 1,000,000.00 0.00 2023-06-30 2023-07-05 2023-08-04 2023-09-03 2023-10-08 onment Reform nvelope (1 envelope proce lementation 5 Service Centers ss) GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PK-KWSB-142705-CS-QCBS / Operational & Enabling Envir Single Stage - One E Procurement of 14 Pairs of S IBRD / 89940 Prior Request for Bids Open - National 5,000,000.00 4,126,718.96 Signed 2019-12-10 2020-01-17 2019-12-15 2020-05-13 2020-01-26 2020-06-16 2020-02-25 2020-09-13 2020-03-31 2020-12-04 2020-09-27 onment Reform nvelope ewage Suction and Jetting Tr ucks PK-KWSB-200916-GO-RFQ / Procurement of Furniture and Operational & Enabling Envir Request for Quota Single Stage - One E Under Imple IBRD / 89940 Post Open - National 25,000.00 0.00 2020-12-15 2021-02-15 2021-02-09 2021-02-15 Fixtures for Project Impleme onment Reform tions nvelope mentation ntation Unit PIU Office PK-KWSB-200925-GO-RFB / F or Asset Management Progra Operational & Enabling Envir Single Stage - One E Pending Impl m conduct Gap Analysis, pre IBRD / 89940 Post Request for Bids Open - National 400,000.00 0.00 2020-12-20 2020-12-25 2021-02-05 2021-03-07 2021-04-11 2021-10-08 onment Reform nvelope ementation pare Development Strategy & Design Priority Data Collec tion. PK-KWSB-200869-GO-RFB / Operational & Enabling Envir Open - Internationa Single Stage - One E Procurement of Sewage Sucti IBRD / 89940 Prior Request for Bids 6,000,000.00 5,049,573.35 Signed 2020-12-30 2021-05-19 2021-01-04 2021-05-31 2021-02-15 2021-07-15 2021-03-17 2021-11-24 2021-04-21 2022-01-29 2021-10-18 onment Reform l nvelope on and Jetting Trucks (2nd St age) PK-KWSB-200927-GO-RFB / I Operational & Enabling Envir Single Stage - One E Pending Impl IBRD / 89940 Post Request for Bids Open - National 1,000,000.00 0.00 2021-01-10 2021-01-15 2021-02-26 2021-03-28 2021-05-02 2022-05-02 mprovement of the GIS onment Reform nvelope ementation PK-KWSB-200930-GO-RFQ / Procurement of Transport fo Operational & Enabling Envir Request for Quota Single Stage - One E Under Imple IBRD / 89940 Post Open - National 180,000.00 0.00 2020-11-06 2021-03-09 2021-01-01 2021-06-30 r PIU Staff will be procured u onment Reform tions nvelope mentation nder separate contracts in tw o different LOTS. PK-KWSB-217362-GO-RFQ / Procurement and Installation Operational & Enabling Envir Request for Quota Single Stage - One E Pending Impl IBRD / 89940 Post Limited 6,000.00 0.00 2021-10-05 2021-11-30 2022-05-29 of Photocopier Machine for K onment Reform tions nvelope ementation WSSIP Project Implementatio n Unit (PIU Office). PK-KWSB-200921-GO-RFQ / Operational & Enabling Envir Request for Quota Single Stage - One E Procurement of IT Equipmen IBRD / 89940 Post Limited 26,000.00 25,773.42 Signed 2021-09-29 2021-10-13 2021-11-24 2021-11-03 2022-05-23 onment Reform tions nvelope t for Project Implementation Unit (PIU Office). PK-KWSB-217357-GO-RFQ / Procurement and Installation Operational & Enabling Envir Request for Quota Single Stage - One E IBRD / 89940 Post Limited 8,000.00 7,794.81 Signed 2021-10-02 2021-10-08 2021-11-27 2021-10-26 2022-05-26 of Air Conditioners (AC's) at K onment Reform tions nvelope WSSIP Project Implementatio n Unit (PIU Office). PK-KWSB-309252-GO-RFB / Operational & Enabling Envir Open - Internationa Single Stage - One E Pending Impl IBRD / 89940 Prior Request for Bids 10,000,000.00 0.00 2023-02-15 2023-02-20 2023-04-03 2023-05-03 2023-06-07 2023-12-04 Reducing energy consumptio onment Reform l nvelope ementation n PK-KWSB-311899-GO-RFQ / Procurement of Office Equip Operational & Enabling Envir Request for Quota Single Stage - One E Pending Impl IBRD / 89940 Post Open - National 24,000.00 0.00 2022-11-20 2023-01-15 2023-07-14 ment & upgrade Multimedia onment Reform tions nvelope ementation & Communication facilities K WSSIP PIU PK-KWSB-297897-GO-RFB / CONTRACT PACKAGE G-1: PR Operational & Enabling Envir Open - Internationa Single Stage - One E IBRD / 89940 Prior Request for Bids 10,550,000.00 0.00 Canceled 2022-08-03 2022-10-18 2022-08-08 2022-09-19 2022-10-19 2022-11-23 2023-05-22 OVISION OF BULK FLOW MET onment Reform l nvelope ERS UNDER COMPONENT-2, SOP-I PK-KWSB-368074-GO-RFQ / Procurement and Implement ation of Grievance Redressal Project Management and Stu Request for Quota Single Stage - One E Pending Impl IBRD / 89940 Post Open - National 50,000.00 0.00 2023-07-01 2023-08-26 2024-08-25 Mechanism (GRM) Software a dies tions nvelope ementation nd Digitization of Hydrant Inf ormation with One Year Oper ation and Maintenance NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PK-KWSB-142714-CS-QCBS / Operational & Enabling Envir Quality And Cost- Design, Tender Documents IBRD / 89940 Prior Open - National 3,500,000.00 2,682,670.30 Signed 2020-02-20 2020-07-30 2020-03-12 2020-08-29 2020-04-25 2021-01-04 2020-05-23 2021-03-03 2020-06-22 2021-06-17 2020-07-27 2021-08-30 2020-08-31 2021-09-27 2024-02-29 onment Reform Based Selection and Supervision for SOP-1 Page 2 PK-KWSB-200842-CS-QCBS / Operational & Enabling Envir Quality And Cost- Pending Impleme Rapid Groundwater Protectio IBRD / 89940 Post Open - National 500,000.00 0.00 2021-01-25 2021-02-15 2021-03-31 2021-04-28 2021-05-28 2021-07-02 2021-08-06 2022-08-06 onment Reform Based Selection ntation n Assessment PK-KWSB-146130-CS-CQS / T Operational & Enabling Envir Consultant Qualifi IBRD / 89940 Post Open - National 250,000.00 0.00 Canceled 2020-01-10 2020-01-31 2020-03-15 2020-04-14 2020-05-19 2020-11-15 ariff Review onment Reform cation Selection PK-KWSB-201024-CS-QCBS / Operational & Enabling Envir Quality And Cost- Under Implement Conduct Energy Audit for Wa IBRD / 89940 Post Open - National 500,000.00 0.00 2020-12-02 2020-12-07 2020-12-23 2020-12-08 2021-02-05 2022-05-31 2021-03-05 2022-08-05 2021-04-04 2021-05-09 2021-06-13 2022-02-08 onment Reform Based Selection ation ter / Sewerage Installations PK-KWSB-142743-CS-QCBS / Operational & Enabling Envir Quality And Cost- Conduct Energy Audit for Wa IBRD / 89940 Post Open - National 500,000.00 0.00 Canceled 2019-12-26 2019-11-21 2020-01-16 2020-01-03 2020-02-29 2020-03-28 2020-04-18 2020-05-23 2020-06-27 2020-12-26 onment Reform Based Selection ter / Sewerage Installations PK-KWSB-203987-CS-CQS / Operational & Enabling Envir Consultant Qualifi Under Implement Head Hunting Firm for the hir IBRD / 89940 Post Open - National 30,000.00 0.00 2021-01-01 2021-10-28 2021-01-22 2021-11-10 2021-03-07 2022-02-07 2021-04-06 2021-05-11 2022-05-11 onment Reform cation Selection ation ing of new KW&SB CEO and Reform Managers. PK-KWSB-200846-CS-QCBS / Operational & Enabling Envir Quality And Cost- Open - Internationa IBRD / 89940 Prior 4,000,000.00 0.00 Under Review 2020-12-15 2021-10-18 2021-01-05 2021-11-30 2021-02-18 2022-08-25 2021-03-18 2022-11-14 2021-04-17 2021-05-22 2021-06-26 2023-12-25 Updating of KWSB's Masterpl onment Reform Based Selection l an PK-KWSB-142664-CS-QCBS / Design of NRW Program and Operational & Enabling Envir Quality And Cost- Under Implement IBRD / 89940 Post Open - National 1,250,000.00 0.00 2021-03-01 2023-05-05 2021-03-22 2023-05-08 2021-05-05 2021-06-02 2021-07-02 2021-08-06 2021-09-10 2023-03-11 Metering System including P onment Reform Based Selection ation reparation of PB NRW Contra cts. PK-KWSB-142822-CS-CQS / Operational & Enabling Envir Consultant Qualifi Under Implement Design and Supervision Firm IBRD / 89940 Post Open - National 100,000.00 0.00 2021-02-25 2022-06-08 2021-03-18 2022-06-14 2021-05-01 2022-12-09 2021-05-29 2021-06-28 2021-08-02 2021-09-06 2022-09-06 onment Reform cation Selection ation for Construction of Six Servic e Centers PK-KWSB-142673-CS-QCBS / Priority Sewer Lines Conditio Operational & Enabling Envir Quality And Cost- Pending Impleme IBRD / 89940 Post Open - National 200,000.00 0.00 2021-04-01 2021-04-22 2021-06-05 2021-07-03 2021-08-02 2021-09-06 2021-10-11 2022-04-11 n Survey and Rehabilitation onment Reform Based Selection ntation Design (incl. Trenchless) PK-KWSB-200850-CS-QCBS / Operational & Enabling Envir Consultant Qualifi Open - Internationa Pending Impleme Implementation Support for IBRD / 89940 Post 100,000.00 0.00 2021-12-30 2022-01-20 2022-03-05 2022-04-04 2022-05-09 2022-11-05 onment Reform cation Selection l ntation Gender Action Plan PK-KWSB-249688-CS-QCBS / Operational & Enabling Envir Quality And Cost- Open - Internationa Under Implement IBRD / 89940 Prior 2,250,000.00 0.00 2021-09-20 2021-10-18 2021-10-11 2021-12-02 2021-11-24 2022-05-24 2021-12-22 2022-07-18 2022-01-21 2023-02-08 2022-02-25 2023-06-11 2022-04-01 2023-04-01 Institutional Reform Studies onment Reform Based Selection l ation of KW&SB PK-KWSB-142659-CS-QCBS / Customer Survey &Identificat Operational & Enabling Envir Quality And Cost- ion (Bulk & Retail) IBRD / 89940 Post Open - National 500,000.00 0.00 Canceled 2019-12-31 2020-10-27 2020-01-21 2020-10-27 2020-03-05 2020-04-02 2020-05-02 2020-06-06 2020-07-11 2021-07-11 onment Reform Based Selection Improved Revised Billing & C ollection System PK-KWSB-142562-CS-QCBS / Design of a HR Plan & trainin Operational & Enabling Envir Quality And Cost- gs to KWSB staff/ new KWSB IBRD / 89940 Post Open - National 1,100,000.00 0.00 Canceled 2019-12-24 2020-11-03 2020-01-14 2020-11-07 2020-02-27 2020-03-26 2020-04-25 2020-05-30 2020-07-04 2021-07-04 onment Reform Based Selection Board Software & Hardware of HR s ystem. PK-KWSB-142800-CS-CQS / S Operational & Enabling Envir Consultant Qualifi IBRD / 89940 Post Open - National 100,000.00 0.00 Canceled 2020-12-03 2020-12-10 2020-12-24 2020-12-10 2021-02-06 2021-03-06 2021-04-05 2021-05-10 2021-06-14 2021-12-13 tudy on FM Best Practices onment Reform cation Selection PK-KWSB-146132-CS-CQS / Design and implementation s Operational & Enabling Envir Consultant Qualifi IBRD / 89940 Post Open - National 200,000.00 0.00 Canceled 2021-01-15 2021-02-05 2021-03-21 2021-04-20 2021-05-25 2021-11-21 upport for communication an onment Reform cation Selection d customer relation strategy programs PK-KWSB-309223-CS-QCBS / Strategy for Strengthening of Operational & Enabling Envir Quality And Cost- IBRD / 89940 Post Open - National 400,000.00 0.00 Canceled 2022-08-28 2022-08-30 2022-09-18 2022-09-02 2022-11-01 2022-11-29 2022-12-29 2023-02-02 2023-03-09 2024-03-08 the Katchi Abadis Cell and N onment Reform Based Selection GOs/CBOs working in Katchi Abadis PK-KWSB-309256-CS-QCBS / Operational & Enabling Envir Quality And Cost- Pending Impleme Monitoring Industrial Dischar IBRD / 89940 Post Open - National 100,000.00 0.00 2022-09-15 2022-10-06 2022-11-19 2022-12-17 2023-01-16 2023-02-20 2023-03-27 2024-03-26 onment Reform Based Selection ntation ge into Sewerage and Storm Water System. PK-KWSB-309292-CS-QCBS / Operational & Enabling Envir Quality And Cost- Pending Impleme Design and Implementation o IBRD / 89940 Post Open - National 250,000.00 0.00 2023-01-23 2023-02-13 2023-03-29 2023-04-26 2023-05-26 2023-06-30 2023-08-04 2024-08-03 onment Reform Based Selection ntation f a Meter Maintenance Progra m PK-KWSB-309286-CS-QCBS / PPP Options Study for NRW R Operational & Enabling Envir Quality And Cost- Open - Internationa Pending Impleme IBRD / 89940 Post 1,000,000.00 0.00 2022-12-15 2023-01-05 2023-02-18 2023-03-18 2023-04-17 2023-05-22 2023-06-26 2024-06-25 eduction, Desalination and/or onment Reform Based Selection l ntation Wastewater reuse. PK-KWSB-200832-CS-QCBS / Operational & Enabling Envir Quality And Cost- Open - Internationa IBRD / 89940 Post 1,500,000.00 0.00 Canceled 2020-12-04 2020-12-23 2020-12-25 2020-12-23 2021-02-07 2022-06-27 2021-03-07 2022-08-22 2021-04-06 2022-11-08 2021-05-11 2021-06-15 2023-06-15 Project Management Consult onment Reform Based Selection l ant PK-KWSB-366301-CS-CQS / S trengthening of Katchi Abadi Operational & Enabling Envir Consultant Qualifi Under Implement IBRD / 89940 Post Open - National 300,000.00 0.00 2023-06-12 2023-06-21 2023-07-03 2023-08-16 2023-09-15 2023-10-20 2025-06-30 Cell and Engagement of Com onment Reform cation Selection ation munity Based Organizations ( CBOs) PK-KWSB-368044-CS-CQS / I nvestment Grade Energy Aud Operational & Enabling Envir Consultant Qualifi Pending Impleme IBRD / 89940 Post Open - National 300,000.00 0.00 2023-06-22 2023-07-13 2023-08-26 2023-09-25 2023-10-30 2024-08-30 it for Pumping Stations at Th onment Reform cation Selection ntation e Dhabeji Pumping Complex PK-KWSB-368069-CS-CQS / I ndependent Monitoring of En Project Management and Stu Consultant Qualifi Pending Impleme vironmental and Social Mana IBRD / 89940 Post Open - National 200,000.00 0.00 2023-06-22 2023-07-13 2023-08-26 2023-09-25 2023-10-30 2024-10-29 dies cation Selection ntation gement Aspects by an Enviro nmental and Social Consulta ncy Firm PK-KWSB-309281-CS-QCBS / Drafting of Regulations for In direct (Industrial) Discharge i Operational & Enabling Envir Quality And Cost- Pending Impleme IBRD / 89940 Post Open - National 200,000.00 0.00 2023-07-05 2023-07-26 2023-09-08 2023-10-06 2023-11-05 2023-12-10 2024-01-14 2025-01-13 nto Sewerage and Monitoring onment Reform Based Selection ntation Industrial Discharge into Sew erage and Storm Water Syste m INDIVIDUAL CONSULTANTS Page 3 Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PK-KWSB-142755-CS-INDV / Operational & Enabling Envir Individual Consult Under Implement IBRD / 89940 Post Open 126,000.00 0.00 2019-11-05 2019-11-19 2019-12-24 2020-01-14 2020-02-18 2023-02-17 PIU staff for Procurement onment Reform ant Selection ation PK-KWSB-142759-CS-INDV / Operational & Enabling Envir Individual Consult Under Implement IBRD / 89940 Post Open 126,000.00 0.00 2019-11-05 2019-11-19 2019-12-24 2020-01-14 2020-02-18 2023-02-17 PIU staff for Financial Manag onment Reform ant Selection ation ement PK-KWSB-142761-CS-INDV / Operational & Enabling Envir Individual Consult Under Implement IBRD / 89940 Post Open 126,000.00 0.00 2019-11-05 2019-11-19 2019-12-24 2020-01-14 2020-02-18 2023-02-17 PIU staff for Communication onment Reform ant Selection ation PK-KWSB-142798-CS-INDV / Operational & Enabling Envir Individual Consult Under Implement IBRD / 89940 Post Open 126,000.00 0.00 2019-11-05 2019-11-19 2019-12-24 2020-01-14 2020-02-18 2023-02-17 PIU staff for Social Developm onment Reform ant Selection ation ent PK-KWSB-200882-CS-INDV / Operational & Enabling Envir Individual Consult Under Implement Procurement and Contract M IBRD / 89940 Post Open 126,000.00 0.00 2020-10-28 2020-11-07 2020-12-16 2021-01-06 2021-02-10 2024-02-10 onment Reform ant Selection ation anagement Specialist 1 (Addi tional PIU Staff) PK-KWSB-200886-CS-INDV / Operational & Enabling Envir Individual Consult Under Implement IBRD / 89940 Post Open 126,000.00 0.00 2020-10-25 2020-11-13 2020-12-13 2021-01-03 2021-02-07 2024-02-07 GIS Specialist (Additional PIU onment Reform ant Selection ation Staff) PK-KWSB-200894-CS-INDV / Operational & Enabling Envir Individual Consult Pending Impleme Technical Specialist (Addition IBRD / 89940 Post Open 126,000.00 0.00 2020-10-30 2020-12-18 2021-01-08 2021-02-12 2021-08-11 onment Reform ant Selection ntation al PIU Staff) PK-KWSB-200901-CS-INDV / Operational & Enabling Envir Individual Consult Under Implement IBRD / 89940 Post Open 126,000.00 0.00 2020-11-15 2020-11-07 2021-01-03 2021-01-24 2021-02-28 2024-02-28 Gender Specialist (Additional onment Reform ant Selection ation PIU Staff) PK-KWSB-201033-CS-INDV / Operational & Enabling Envir Individual Consult Under Implement IBRD / 89940 Post Open 126,000.00 0.00 2020-11-05 2020-11-07 2020-12-24 2021-01-14 2021-02-18 2024-02-18 PIU staff for Environment onment Reform ant Selection ation PK-KWSB-201561-CS-INDV / Operational & Enabling Envir Individual Consult Under Implement Procurement and Contract M IBRD / 89940 Post Open 126,000.00 0.00 2020-10-28 2020-11-07 2020-12-16 2021-01-06 2021-02-10 2024-02-10 onment Reform ant Selection ation anagement Specialist 2 (Addi tional PIU Staff) PK-KWSB-142787-CS-INDV / Operational & Enabling Envir Individual Consult IBRD / 89940 Post Open 126,000.00 0.00 Canceled 2019-11-05 2019-11-19 2019-12-24 2020-01-14 2020-02-18 2023-02-17 PIU staff for Environment onment Reform ant Selection PK-KWSB-335687-CS-INDV / Project Management and Stu Individual Consult Under Implement IBRD / 89940 Post Open - National 126,000.00 0.00 2023-01-11 2023-01-18 2023-03-01 2023-03-22 2023-04-26 2023-10-23 Monitoring & Evaluation Spec dies ant Selection ation ialist PK-KWSB-357391-CS-INDV / Project Management and Stu Individual Consult Under Implement IBRD / 89940 Post Open - National 84,000.00 0.00 2023-04-20 2023-05-09 2023-05-26 2023-06-16 2023-07-21 2025-06-30 Financial Specialist (PIU) dies ant Selection ation PK-KWSB-357613-CS-INDV / Project Management and Stu Individual Consult Under Implement Procurement and Contract M IBRD / 89940 Post Open - National 84,000.00 0.00 2023-04-20 2023-05-09 2023-05-26 2023-06-16 2023-07-21 2025-06-30 dies ant Selection ation anagement Specialist (PIU) PK-KWSB-368848-CS-INDV / Project Management and Stu Individual Consult Pending Impleme IBRD / 89940 Post Open - National 84,000.00 0.00 2023-07-03 2023-08-21 2023-09-11 2023-10-16 2025-06-30 Internal Auditor (PIU) dies ant Selection ntation PK-KWSB-368849-CS-INDV / Project Management and Stu Individual Consult Pending Impleme IBRD / 89940 Post Open - National 84,000.00 0.00 2023-07-03 2023-08-21 2023-09-11 2023-10-16 2024-07-02 Legal Expert for PPP Node-K dies ant Selection ntation W&SB Page 4 PROCUREMENT PLAN (Textual Part) Project information: P173518 - Rural and Small Towns Water Security Project Project Implementation agencies: National Directorate for Water Supply and Sanitation (DNAAS) Water and Sanitation Infrastructures Administration (AIAS) Date of the Procurement Plan: 1/11/2021 Period covered by this Procurement Plan: 1/11/2021 – 12/31/2023 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (November 2020) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in Decree 5/2016 of March 8, 2016, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Not Applicable Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – Not Applicable PROCUREMENT Mozambique : Rural and Small Towns Water Security Project PLAN General Information Country: Mozambique 2021-11-10 Bank’s Approval Date of the Original Procurement Plan: 2023-06-02 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P173518 GPN Date: 2021-10-29 Project Name: Rural and Small Towns Water Security Project Loan / Credit No: / , IDA / D9410 National Directorate of Water Supply and Sanitation Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned MZ-DNAAS-CERC-RSTWSP- National Procure W001 / Restoration of Water Component 4: Contingent E ment Document - Pending Imp 2024-01-1 Supply Systems including 1 d IDA / D9410 mergency Response Compo Post Direct Selection Direct - National 1 Envelope proce 156,000.00 0.00 2023-06-05 2023-06-10 2023-07-15 lementation 1 esalination plant in Luabo in nent (CERC) ss (Non Bank-SPD Zambezia Province (2 units) ) National Procure MZ-DNAAS-CERC-RSTWSP- Component 4: Contingent E ment Document - W002 / Restoration of Water Single Stage - One E Pending Imp 2024-05-2 IDA / D9410 mergency Response Compo Post Request for Bids Open - National 1 Envelope proce 4,374,000.00 0.00 2023-08-15 2023-08-29 2023-09-19 2023-10-19 2023-11-23 Supply Systems in Zambézia, nvelope lementation 1 nent (CERC) ss (Non Bank-SPD Sofala, Tete and Inhambane ) Provinces (7 Lots) National Procure MZ-DNAAS-CERC-RSTWSP- Component 4: Contingent E ment Document - W003 / Replacement of Bore Single Stage - One E Pending Imp 2024-03-1 IDA / D9410 mergency Response Compo Post Request for Bids Open - National 1 Envelope proce 1,394,000.00 0.00 2023-06-05 2023-06-19 2023-07-10 2023-08-09 2023-09-13 holes in Zambezia, Sofala, Te nvelope lementation 1 nent (CERC) ss (Non Bank-SPD te, and Inhambane Provinces ) (5 Lots) MZ-DNGRH-CERC-RSTWSP - National Procure W005 / Replacement of the H Component 4: Contingent E ment Document - Single Stage - One E Pending Imp 2024-03-1 ydrological Monitoring Netwo IDA / D9410 mergency Response Compo Post Request for Bids Open - National 1 Envelope proce 675,000.00 0.00 2023-06-06 2023-06-20 2023-07-11 2023-08-10 2023-09-14 nvelope lementation 2 rk dragged by the high flows nent (CERC) ss (Non Bank-SPD in the Southern, Central and ) Northern Regions (3 Lots) MZ-DNGRH-CERC-RSTWSP- National Procure W004 / Restoration of normal Component 4: Contingent E ment Document - Single Stage - One E Pending Imp 2024-03-1 operation of the Corumana D IDA / D9410 mergency Response Compo Post Request for Bids Open - National 1 Envelope proce 900,000.00 0.00 2023-06-05 2023-06-19 2023-07-10 2023-08-09 2023-09-13 nvelope lementation 1 am affected by the floods, in nent (CERC) ss (Non Bank-SPD cluding the monitoring syste ) m. GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MZ-DNAAS-PPA018-RFQ/ OF Component 3: Institutional a Request for Quota Single Stage - One E FICE FURNITURE / Office Furn / nd Project Management Sup Post Limited 10,000.00 0.00 Signed 2021-11-15 2023-01-11 2022-01-10 2022-07-09 tions nvelope iture for DPOP port MZ-DNAAS-PPA011-RFQ- OF Component 3: Institutional a Request for Quota Single Stage - One E FICE IT EQUIP / Office IT Equi / nd Project Management Sup Post Limited 30,000.00 0.00 Signed 2021-11-20 2022-08-30 2022-01-15 2022-07-14 tions nvelope pment for DNAAS and AURA port MZ-DNAAS-PPA012-RFQ/ FIE Component 3: Institutional a Request for Quota Single Stage - One E LD VEHICLES / 2 Field Vehicle / nd Project Management Sup Post Limited 70,000.00 0.00 Signed 2021-11-20 2022-01-19 2022-01-15 2022-07-14 tions nvelope s for DPOP Nampula and Za port mbezia MZ-DNAAS-P033-RFQ-2022 / Component 3: Institutional a Request for Quota Single Stage - One E Under Imple IDA / D9410 Post Limited 60,000.00 0.00 2022-12-14 2023-02-08 2023-05-09 Supply of two small office ve nd Project Management Sup tions nvelope mentation hicles port MZ-DNAAS-CERC-RSTWSP-G 001 / Supply of Concrete Sla bs and Rolls of Plastic Sheets Component 4: Contingent E Single Stage - One E Under Imple and Technical Assistance in t IDA / D9410 mergency Response Compo Post Request for Bids Open - National 1,476,000.00 0.00 2023-06-02 2023-06-14 2023-06-16 2023-06-16 2023-07-07 2023-08-06 2023-09-10 2024-03-08 nvelope mentation he Installation of the Concret nent (CERC) e Slabs in Zambezia, Sofala, and Inhambane Provinces (3 Lots) MZ-DNAAS-CERC-RSTWSP-G 004 / Description: Supply of Component 4: Contingent E Single Stage - One E Under Imple Buckets of Chlorine and Wate IDA / D9410 mergency Response Compo Post Request for Bids Open - National 880,000.00 0.00 2023-06-06 2023-06-12 2023-06-20 2023-06-13 2023-07-11 2023-08-10 2023-09-14 2024-03-12 nvelope mentation r Purify Units in Zambezia, So nent (CERC) fala, Tete, Inhambane and M anica Provinces (5 Lots) MZ-DNAAS-CERC-RSTWSP- G 002 / Supply of Concrete Sla Component 4: Contingent E bs and Rolls of Plastic Sheets Single Stage - One E Under Imple IDA / D9410 mergency Response Compo Post Request for Bids Open - National 1,477,000.00 0.00 2023-06-05 2023-06-14 2023-06-19 2023-06-16 2023-07-10 2023-08-09 2023-09-13 2024-03-11 and Technical Assistance in t nvelope mentation nent (CERC) he Installation of the Concret e Slabs in Tete Province (3 Lo ts) MZ-DNAAS-CERC-RSTWSP- G 003 / Supply of Concrete Sla Component 4: Contingent E bs and Rolls of Plastic Sheets Single Stage - One E Under Imple IDA / D9410 mergency Response Compo Post Request for Bids Open - National 1,169,000.00 0.00 2023-06-06 2023-06-14 2023-06-20 2023-06-16 2023-07-11 2023-08-10 2023-09-14 2024-03-12 and Technical Assistance in t nvelope mentation nent (CERC) he Installation of the Concret e Slabs in Manica Province (2 Lots) MZ-DNAA-RSTWSP-G048 / S Component 3: Institutional a upply of 2 units 4x4 Vehicles Request for Quota Single Stage - One E Under Imple IDA / D9410 nd Project Management Sup Post Limited 100,000.00 0.00 2023-06-30 2023-06-20 2023-08-25 2024-02-21 to the National Directorate of tions nvelope mentation port Water Supply and Sanitation NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MZ-DNAAS-PPA014-ICS-INDV Component 3: Institutional a /TNSLOFDOC / Translation of / nd Project Management Sup Post Direct Selection Direct 15,000.00 0.00 Signed 2021-11-19 2022-06-22 2021-11-24 2022-06-15 2021-12-29 2022-06-27 Project Documents port Page 1 MZ-DNAAS-312400-NC-RFQ / Component 3: Institutional a Request for Quota Single Stage - One E Provision of Healthcare Servi IDA / D9410 nd Project Management Sup Post Limited 30,000.00 0.00 Signed 2022-09-05 2022-12-23 2022-10-31 2023-04-29 tions nvelope ces to DNAAS for 2 years port CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MZ-DNAAS-PRPPA002-CS-QC Component 3: Institutional a BS / TA PNGRH / Preparation Quality And Cost- / nd Project Management Sup Prior Open - National 500,000.00 0.00 Canceled 2021-10-29 2021-11-19 2022-01-02 2022-01-30 2022-03-01 2022-04-05 2022-05-10 2023-05-10 of the National Water Resour Based Selection port ces Management Program D NGRH) MZ-DNAAS-PRPPA005-CS-QC BS / DNGRH / Dam Safety As Component 2: Enhancement sessment and Management / Quality And Cost- / of Water Supply and Sanitati Prior Open - National 800,000.00 0.00 Canceled 2021-11-30 2021-12-21 2022-02-03 2022-03-03 2022-04-02 2022-05-07 2022-06-11 2023-06-11 implementation of dam safet Based Selection on Services in Rural Areas y support program, incl. train ing and capacity building (DN GRH) MZ-DNAAS-PRPPA004-CS-QC Component 3: Institutional a BS / DNGRH / Preparation of Quality And Cost- Pending Impleme / nd Project Management Sup Prior Open - National 500,000.00 0.00 2021-11-23 2021-12-14 2022-01-27 2022-02-24 2022-03-26 2022-04-30 2022-06-04 2023-06-04 social and environmental stu Based Selection ntation port dies for 2 final designs for DN GRH MZ-DNAAS-PPA017-CS-CQS- Component 3: Institutional a Consultant Qualifi Under Implement DES&S / Design and Supervis / nd Project Management Sup Post Open - National 120,000.00 0.00 2021-11-30 2022-01-18 2021-12-21 2022-02-12 2022-02-03 2022-03-05 2022-04-09 2022-10-06 cation Selection ation ion of AURA Offices in Nampu port la MZ-DNAAS-PPA015-CS-QCBS ADJ / Adjustment of the Regu Component 3: Institutional a Quality And Cost- Pending Impleme latory Framework for the rura / nd Project Management Sup Prior Open - National 250,000.00 0.00 2021-11-30 2021-12-21 2022-02-03 2022-03-03 2022-04-02 2022-05-07 2022-06-11 2023-06-11 Based Selection ntation l space covering water suppl port y and sanitation and decentr alization issues MZ-DNAAS-PPA016-CS-QCBS /DISM / Development of Ince Component 3: Institutional a Quality And Cost- ntive and Sanctions mechani / nd Project Management Sup Post Open - National 150,000.00 0.00 Canceled 2021-11-19 2022-01-18 2021-12-10 2022-01-23 2022-02-20 2022-03-22 2022-04-26 2022-05-31 2023-05-31 Based Selection sm applicable to the Regulat port ed Entities under the Regulat ion of public WSS service MZ-DNAAS-PPA016-CS-CQS - 2022 / Development of Incen Component 3: Institutional a tive and Sanctions mechanis Consultant Qualifi Under Implement IDA / D9410 nd Project Management Sup Post Open - National 150,000.00 0.00 2022-02-02 2022-02-13 2022-02-23 2022-04-08 2022-05-08 2022-06-12 2022-12-09 m applicable to the Regulate cation Selection ation port d Entities under the Regulati on of public Water Supply an d Sanitation Service FIPAG/GMWSP/CON-06/13 / Component 3: Institutional a CONSULTANCY SERVICES FO Quality And Cost- Open - Internationa Under Implement IDA / D9410 nd Project Management Sup Prior 1,300,000.00 0.00 2022-02-28 2022-03-08 2022-03-14 2022-04-11 2022-03-24 2022-04-16 2022-03-29 2022-04-30 2022-10-23 2022-06-04 2023-04-17 2022-07-09 2023-07-09 R PREPARATION OF PHASE II Based Selection l ation port OF THE GREATER MAPUTO W ATER SUPPLY PROJECT MZ-DNAAS-PRPPA003-CS-QC Component 3: Institutional a BS / DNGRH / Review of feasi Quality And Cost- Open - Internationa / nd Project Management Sup Prior 2,500,000.00 0.00 Canceled 2021-11-23 2021-12-14 2022-01-27 2022-02-24 2022-03-26 2022-04-30 2022-06-04 2023-06-04 bility studies and preparation Based Selection l port of 2 final designs (DNGRH) MZ-DNAAS-CERC-RSTWSP-C S001-CQS / Needs Assessme Component 4: Contingent E nt and Supervision of Works f Consultant Qualifi IDA / D9410 mergency Response Compo Post Open - National 452,000.00 0.00 Under Review 2023-06-05 2023-06-27 2023-06-19 2023-08-02 2023-09-01 2023-10-06 2024-04-03 or Water Supply Systems Rec cation Selection nent (CERC) overy in Zambezia, Sofala, T ete, and Inhambane Province s MZ-DNAAS-CERC-RSTWSP-C S002-CQS / Supervision of W Component 4: Contingent E Consultant Qualifi orks for Replacement of Bore IDA / D9410 mergency Response Compo Post Open - National 138,000.00 0.00 Under Review 2023-06-05 2023-06-27 2023-06-19 2023-08-02 2023-09-01 2023-10-06 2024-04-03 cation Selection holes in Zambezia, Sofala, Te nent (CERC) te, and Inhambane Provinces MZ-DNAA-RSTWSP-CS-047-C Component 2: Enhancement Consultant Qualifi Under Implement QS / Independent Verification IDA / D9410 of Water Supply and Sanitati Post Open - National 205,000.00 0.00 2023-06-19 2023-06-16 2023-07-03 2023-08-16 2023-09-15 2023-10-20 2024-04-17 cation Selection ation Agent on Services in Rural Areas MZ-DNGRH-CERC-RSTWSP-C Component 4: Contingent E Consultant Qualifi Pending Impleme S003-CQS / Supervision of Re IDA / D9410 mergency Response Compo Post Open - National 307,000.00 0.00 2023-06-18 2023-07-02 2023-08-15 2023-09-14 2023-10-19 2024-04-16 cation Selection ntation pair of Dikes in the Southern nent (CERC) Region INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MZ-DNAAS-PRPPA001-ICS-IN DV/TA DNGRH / Recruitment Component 3: Institutional a Individual Consult of an individual consultant to / nd Project Management Sup Prior Open 200,000.00 0.00 Signed 2021-10-29 2021-12-08 2021-12-17 2022-04-01 2022-01-07 2022-05-24 2022-02-11 2022-08-10 ant Selection provide Technical Assistance port for the Management of the Pr PPA at DNGRH level MZ-DNAAS-PPA006-ICS-INDV Component 3: Institutional a / PBG MANUAL / Developmen Individual Consult Under Implement / nd Project Management Sup Post Limited 30,000.00 0.00 2021-10-27 2021-11-30 2021-11-01 2022-01-06 2021-11-22 2022-03-08 2021-12-27 2022-06-25 t of the Implementation Man ant Selection ation port ual for the DPOP Performanc e Based Grants MZ-DNAAS-PPA008-ICS-INDV Component 3: Institutional a Individual Consult Pending Impleme / ON-SITE SANIT / On-Site Sa / nd Project Management Sup Post Open 160,000.00 0.00 2021-11-20 2022-01-08 2022-01-29 2022-03-05 2022-09-01 ant Selection ntation nitation Specialist for DNAAS port (2 years) MZ-DNAAS-PPA009-ICS-INDV Component 3: Institutional a /M&E SPECIALIST / Monitorin Individual Consult / nd Project Management Sup Post Open 160,000.00 0.00 Signed 2021-11-20 2021-12-13 2022-01-08 2022-07-19 2022-01-29 2022-08-01 2022-03-05 2022-09-01 g and Evaluation Specialist fo ant Selection port r DNAAS (2 years) MZ-DNAAS-PPA019-ICS-INDV Component 3: Institutional a Individual Consult / GRANT& FIN SP / Grant and / nd Project Management Sup Post Open 180,000.00 0.00 Signed 2021-11-29 2022-01-30 2022-01-17 2022-05-09 2022-02-07 2022-05-25 2022-03-14 2022-09-10 ant Selection Financial Specialist for DNAA port S (2 years) Page 2 MZ-DNAAS-PPA010-ICS-INDV Component 3: Institutional a Individual Consult / PROC-SP / Procurement Spe / nd Project Management Sup Prior Open 200,000.00 0.00 Signed 2021-11-30 2021-12-05 2022-01-18 2022-03-18 2022-02-08 2022-05-08 2022-03-15 2022-09-11 ant Selection cialist for DNAAS (2 years) port MZ-DNAAS-PPA007-ICS-INDV Component 3: Institutional a Individual Consult Under Implement / PROJECT COORD / Project C / nd Project Management Sup Prior Open 240,000.00 0.00 2021-11-30 2022-02-22 2022-01-18 2022-07-04 2022-02-08 2022-08-12 2022-03-15 2022-09-11 ant Selection ation oordinator for DNAAS (2 year port s) MZ-DNAAS-PPA020-ICS-INDV Component 3: Institutional a Individual Consult / WAT&SAN SPEC / Water and IDA / D9410 nd Project Management Sup Post Direct 168,000.00 175,200.00 Signed 2022-03-28 2022-04-04 2022-04-07 2022-04-19 2022-04-17 2022-04-22 2022-05-22 2022-07-18 2022-11-18 ant Selection Sanitation Specialist port MZ-DNAAS-PPA021-ICS-INDV Component 3: Institutional a / ENVIRON SPEC / ENVIRONM Individual Consult IDA / D9410 nd Project Management Sup Post 160,000.00 0.00 Signed 2022-03-31 2022-03-29 2022-04-30 2022-07-22 2022-05-10 2022-07-25 2022-06-14 2022-12-11 ENTAL AND SOCIAL SPECIALI ant Selection port ST FOR DNAAS MZ-DNAAS-PPA021-ICS-INDV Component 3: Institutional a Individual Consult -PROC. OFFICER / PROCUREM IDA / D9410 nd Project Management Sup Prior Open 72,000.00 0.00 Signed 2022-04-25 2022-06-03 2022-05-25 2022-10-24 2022-06-04 2022-11-18 2022-07-09 2023-04-24 2024-06-28 ant Selection ENT OFFICER port MZ-DNAAS-P022-ICS-INDIV-A Component 3: Institutional a Individual Consult Pending Impleme DMIN ASSISTANT / Financial IDA / D9410 nd Project Management Sup Post Open 36,000.00 0.00 2022-05-04 2022-06-07 2022-06-28 2022-08-02 2024-07-22 ant Selection ntation and Administrative Assistant port MZ-DNAAS-P028-ICS-INDV-2 Component 3: Institutional a Individual Consult Pending Impleme IDA / D9410 Post Open - National 25,000.00 0.00 2022-12-15 2023-01-14 2023-01-24 2023-02-28 2023-08-27 022 / Independent Verificatio nd Project Management Sup ant Selection ntation n Agent port MZ-DNAAS-PPA042-ICS-INDV Component 3: Institutional a Individual Consult Open - Internationa Under Implement / PROC-SP / International Pro IDA / D9410 nd Project Management Sup Prior 100,000.00 0.00 2023-02-03 2023-02-08 2023-03-24 2023-04-14 2023-05-19 2023-11-15 ant Selection l ation curement Specialist port MZ-DNAAS-PRPPA043-CS-IN Component 3: Institutional a Individual Consult Under Implement DV / Dam Monitoring System IDA / D9410 nd Project Management Sup Post Limited 50,000.00 0.00 2023-05-05 2023-05-12 2023-05-10 2023-05-08 2023-05-31 2023-05-08 2023-07-05 2024-01-01 ant Selection ation Consultant port MZ-DNAAS-PRPPA044-CS-IN Component 3: Institutional a Individual Consult Direct - Internation Under Implement DV / Panel of Expert 1 – Dam IDA / D9410 nd Project Management Sup Post 50,000.00 0.00 2023-05-05 2023-05-04 2023-05-15 2023-06-05 2023-07-10 2024-01-06 ant Selection al ation Safety Expert port MZ-DNAAS PRPPA045-CS-IN Component 3: Institutional a Individual Consult Direct - Internation Under Implement DV / Panel of Expert 2 – Hydr IDA / D9410 nd Project Management Sup Post 50,000.00 0.00 2023-05-05 2023-05-12 2023-05-15 2023-05-22 2023-06-05 2023-05-22 2023-07-10 2024-01-06 ant Selection al ation o-Mechanical Equipment Spe port cialist MZ-DNAAS-PRPPA046-CS-IN Component 3: Institutional a Individual Consult Direct - Internation Under Implement DV / Panel of Expert 3 – Hydr IDA / D9410 nd Project Management Sup Post 50,000.00 0.00 2023-05-05 2023-05-12 2023-05-15 2023-05-22 2023-06-05 2023-05-25 2023-07-10 2024-01-06 ant Selection al ation aulics Specialist port MZ-DNGRH-CERC-RSTWSP- Component 4: Contingent E CS004-INDV / Supervision of Individual Consult Pending Impleme IDA / D9410 mergency Response Compo Post Limited 27,000.00 0.00 2023-06-02 2023-06-09 2023-06-23 2023-08-04 2024-01-31 replacement of the foof of Ca ant Selection ntation nent (CERC) ia's office, damaged by extre me events. MZ-DNGRH-CERC-RSTWSP-C Component 4: Contingent E Individual Consult Pending Impleme S005-INDV / Supervision of R IDA / D9410 mergency Response Compo Post Limited 28,000.00 0.00 2023-06-19 2023-06-24 2023-07-15 2023-08-19 2024-02-15 ant Selection ntation epair of Dikes in the Central nent (CERC) Region Page 3 PROCUREMENT PLAN Project information: Higher Education for Economic Transformation Project P166415 Project Implementation agency: ARU, COSTECH, DUCE, HESLB, MJNUAT,MOCU, MUCE, MUHAS,MUST, MZUMBE, MoEST, OUT, SUA, SUZ, TCU, UDOM, UDSM Date of the Procurement Plan: Sep 28, 2021 Period covered by this Procurement Plan: Oct 2021- Oct 2022 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international and national competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: When approaching the national market, as agreed in the Procurement Plan, the country’s own procurement procedures may be used. These procurement procedures shall be consistent with the Bank’s Core Procurement Principles and ensure that the Bank’s Anti- Corruption Guidelines and Sanctions Framework and contractual remedies set out in its Legal Agreement apply. For national open competitive procurement the requirements as per National Procurement Procedure (5.4) of Bank’s Procurement Regulations will apply Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Not Applicable Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations –Not Applicable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Not applicable Other Relevant Procurement Information. None PROCUREMENT Tanzania : Higher Education for Economic Transformation Project PLAN General Information Country: Tanzania 2023-01-19 Bank’s Approval Date of the Original Procurement Plan: 2023-06-02 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P166415 GPN Date: 2021-11-28 Project Name: Higher Education for Economic Transformation Project Loan / Credit No: IDA / 68870 Tanzania Commission for Science and Technology Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TZ-COSTECH-327349-GO-RF Q / Supply of Working Tools f Strengthening the Managem Request for Quota Single Stage - One E Under Imple or Project Team (7-Laptops; IDA / 68870 ent of the Higher Education Post Limited 20,000.00 0.00 2022-12-20 2023-03-24 2023-02-06 2023-05-07 tions nvelope mentation 1-Projector; 1-Printer; 2-HDMI System Cable; 1-IPAD and 1-UPS) TZ-COSTECH-327350-GO-RF B / Supply of two (2) Motor V ehicles (Station Wagon and P Strengthening the Managem ick-up Double cabin) for proj Single Stage - One E Under Imple IDA / 68870 ent of the Higher Education Post Request for Bids Open - National 149,500.00 0.00 2022-12-15 2022-12-31 2022-12-18 2023-02-18 2023-01-31 2023-02-17 2023-02-20 2023-04-28 2023-03-10 2023-06-08 ect monitoring and facilitatin nvelope mentation System g the construction of STI Com plex in Dodoma and to stren gthening and expansion of H ERIN in Seven (7) Regions NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TZ-COSTECH-363868-NC-DI Strengthening the Managem R / Conference package for S Under Imple IDA / 68870 ent of the Higher Education Post Direct Selection Direct - National 49,248.00 0.00 2023-05-26 2023-06-01 2023-05-31 2023-06-01 2023-06-10 2023-06-15 cience, Technology and Inno mentation System vation Conference and Exhibi tion (STICE) TZ-COSTECH-363902-NC-DI R / Supply the Branded Confe rence bags, Trophy Awards, c Strengthening the Managem Under Imple onference stationaries and pr IDA / 68870 ent of the Higher Education Post Direct Selection Direct - National 10,870.00 0.00 2023-06-02 2023-06-01 2023-06-06 2023-06-01 2023-06-11 2023-06-26 mentation inting Books of Abstracts, for System the Annual National Science, Technology, and Innovation Conference and Exhibition TZ-COSTECH-363896-NC-DI Strengthening the Managem R / Journal publishing for Scie Pending Impl IDA / 68870 ent of the Higher Education Post Direct Selection Direct - National 3,913.00 0.00 2023-06-02 2023-06-05 2023-06-09 2023-06-29 nce, Technology Innovation C ementation System onference and Exhibition (STI CE) CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TZ-COSTECH-327514-CS-CQ S / Consultancy service to co Strengthening the Managem nduct Environmental Social I Consultant Qualifi Under Implement IDA / 68870 ent of the Higher Education Post Limited 30,000.00 0.00 2023-02-03 2023-05-25 2023-02-17 2023-06-02 2023-03-19 2023-04-23 2023-07-22 mpact Assessment (ESIA) for cation Selection ation System construction of Science, Tech nology and Innovation (STI) C omplex in Dodoma TZ-COSTECH-339914-CS-QC BS / Consultancy Services for Design, Preparation of Biddin Strengthening the Managem Quality And Cost- Under Implement g, Documents, Cost Estimate IDA / 68870 ent of the Higher Education Post Open - National 360,000.00 0.00 2023-05-16 2023-05-30 2023-06-06 2023-05-31 2023-07-20 2023-08-17 2023-09-16 2023-10-21 2023-11-25 2024-11-24 Based Selection ation , and Supervision of Construc System tion of the Science, Technolo gy, and Innovation (STI) Com plex in Dodoma. INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 1 PROCUREMENT PLAN (Textual Part) Project information: Saint Lucia Renewable Sector Development Project P161316 Project Implementation agency: Department of Infrastructure, Ports and Transport Date of the Procurement Plan: June 7, 2021 Period covered by this Procurement Plan: June 7, 2021– June 7 2025 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: NA. Leased Assets Not Applicable Procurement of Second Hand Goods Not Applicable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). NA Other Relevant Procurement Information: Not applicable PROCUREMENT St. Lucia : Renewable Energy Sector Development Project PLAN General Information Country: St. Lucia Bank’s Approval Date of the Original Procurement Plan: 2018-11-27 Revised Plan Date(s): (comma delineated, leave blank if 2023-06-02 none) Project ID: P161316 GPN Date: 2023-05-25 Project Name: Renewable Energy Sector Development Project Loan / Credit No: / PCU - Department of Planning and National Development, Ministry of Finance, Economic Affairs Plannin Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SLU-RESDP-NCS-RQ-PPAR-01 2. Capacity Building, Technic Request for Quota Single Stage - One E / Post Open - National 10,000.00 0.00 Canceled 2019-01-27 2019-03-24 2019-09-20 -18 / Printing of Paraphenilia al Assistance and Market En tions nvelope gagement CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SLU-RESDP-CS-QCBS-EMC-0 2. Capacity Building, Technic 1-18 / Procurement of Servic Quality And Cost- Open - Internationa / al Assistance and Market En Post 3,500,000.00 0.00 Canceled 2019-02-01 2019-02-22 2019-04-07 2019-05-05 2019-06-04 2019-07-09 2019-08-13 2020-08-12 es of an Exploration Manage Based Selection l gagement ment Consultant (EMC) SLU-RESDP-CS-CQS -02-18 / 2. Capacity Building, Technic Consultant Qualifi / Post Limited 125,000.00 0.00 Canceled 2018-11-30 2018-12-04 2018-12-14 2019-01-13 2019-02-17 2019-08-16 Legal Advisory Services al Assistance and Market En cation Selection gagement INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SLU-RESDP-CS-IC-PA-01-18 / Project management support 2. Capacity Building, Technic Individual Consult – incremental support to adm / al Assistance and Market En Post Limited 26,000.00 0.00 Under Review 2019-02-01 2020-07-22 2019-02-06 2019-02-27 2019-04-03 2019-09-30 ant Selection inister overall project: Procur gagement ement and Contract Manage ment Analyst SLU RESDP FA 01 19 / Admi 2. Capacity Building, Technic Pending Impleme / Post Direct Selection Direct 20,000.00 0.00 2019-03-15 2019-03-25 2019-05-29 2019-11-25 nistrative Assistant (Fiduciary al Assistance and Market En ntation ) gagement SLU-RESDP-CS-SSS-PACO-01 2. Capacity Building, Technic -18 / Public Awareness Camp / al Assistance and Market En Post Direct Selection Direct 37,000.00 0.00 Canceled 2018-08-01 2018-08-11 2018-10-15 2019-04-13 aign and Investor's Outreach gagement SLU-RESDP-CS-IC-FO-01-18 / 2. Capacity Building, Technic Project management support Individual Consult / al Assistance and Market En Post Direct 25,000.00 0.00 Canceled 2019-03-28 2019-04-07 2019-04-28 2019-06-02 2019-11-29 – incremental support to adm ant Selection gagement inister overall project: Financ e Officer SLU-RESDP-CS-IC-PM-01-18 / 2. Capacity Building, Technic Project management support Individual Consult / al Assistance and Market En Prior Open 450,000.00 0.00 Canceled 2018-11-22 2019-01-09 2019-01-10 2019-01-31 2019-03-07 2019-09-03 - incremental support to adm ant Selection gagement inister overall project: Project Manager SLU-RESDP-CS-IC-CLSSO-01- 18 / Project management sup 2. Capacity Building, Technic Individual Consult port - incremental support to / al Assistance and Market En Post Open 35,000.00 0.00 Canceled 2019-01-15 2019-03-05 2019-03-26 2019-04-30 2019-10-27 ant Selection administer overall project: Co gagement mmunications/Liaison and So cial Safeguards Officer SLU-RESDP-CS-IC-AA-01-18 / 2. Capacity Building, Technic Project management support Individual Consult / al Assistance and Market En Post Open 20,000.00 0.00 Canceled 2019-01-15 2019-03-05 2019-03-26 2019-04-30 2019-10-27 - incremental support to adm ant Selection gagement inister overall project: Admini strative Assistant SLU-RESDP-CS-IC-PPIM-01-1 2. Capacity Building, Technic 8 / Technical Advisor for Proj / al Assistance and Market En Post Direct Selection Direct 30,000.00 0.00 Canceled 2019-01-08 2019-01-18 2019-03-24 2019-09-20 ect Preparation and Impleme gagement ntation SLU-RESDP-CS-SSS-TC-01-18 2. Capacity Building, Technic / Project management suppo / al Assistance and Market En Post Direct Selection Direct 40,000.00 0.00 Canceled 2019-01-08 2019-03-11 2019-01-18 2019-03-24 2019-09-20 rt - incremental support to ad gagement minister overall project: Tech nical Coordinator Page 1 PROCUREMENT PLAN General 1. Project Information a. Country: Federal Republic of Somalia b. Project Name: Somalia Recurrent Cost and Reform Financing Project – Phase III c. Project Number: P173731 d. Total Finance: USD 68,000,000 2. Project Implementation Agency: Ministry of Finance, Federal Government of Somalia 3. Date of Project Plan: 7 June 2021 4. Period Covered by this Procurement: June 2021 – December 2022 I. Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016 revised November 2017, August 2018 and November 2020) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. II. Bank’s Standard Procurement Document: The Bank’s standard Procurement Documents shall be used for all contracts subject to international competitive procurement and those contracts as specified into Procurement Plan tables in STEP III. National Procurement Arrangements: Not applicable IV. Prequalification: Not applicable V. Leased Assets: Not Applicable VI. Procurement of Second-hand Goods: Not Applicable VII. Domestic Preference: Not Applicable 1 VIII. Hands on Expanded Implementation Support (HEIS): Not applicable IX. Other Relevant Procurement Information: Not Applicable X. Thresholds for Procurement Approaches and Method (US$ millions) Based on the risks identified above, the following procurement arrangements are proposed: a) Approach to Market: Based on previous experience and available local market, the following threshold will be used of open national/international and RFQ bidding (all figures in million USD) Table 1.2: Thresholds for procurement approaches and methods Procurement Methods (US$ millions)–Goods, Works, and Non- Consulting Services Open Open Request for Direct Category Internatio National Quotation Selection nal (RfQ) Works ≥ 5.0 <5.0 ≤ 0.2 All Values Goods, IT, and non- ≥ 0.5 <0.5 ≤ 0.1 All Values consultin g services Thresholds for Procurement Approaches and Methods (US$, millions) – Consulting Services Category Short List of National Consultants Consulting Engineering and Services Construction Supervision Consultants (Firms) ≤ 0.1 ≤ 0.2 Individual Consultants N.A. N.A. Direct Selection Consultants (Firms) All Values All Values Individual Consultants All Values All Values 2 3 XI. Table Packages for Goods, Works and Non-Consulting Services (At Negotiations – to be entered in STEP) Market Selecti Procurem Revi Approa on Evaluatio ent ew Expected Expected ch Metho n Options Process Contract Estimat by date of date of Ref. (Open- d (BAFO (Single Descripti ed Cost Bank bid/ Contract No Nation (RFP, Rated stage- on (US$) (Prio proposal Signatur al/ RFB, Criteria single r/ opening e Limited RFQ etc.) envelope Post) etc.) etc.) etc.) Goods Supply of Single Smart Most stage One- Open 02/July/20 30/July/20 G1 Phones 300,000. Prior RFB advantage Envelop National 21 21 with Solar 00 ous Bid System Office Furniture Most Single 28/June/2 25/July/20 Limited G2 for RCRF 22,000.0 Prior RFQ advantage stage One- 021 21 National PIU 0 ous Bid Envelop Offices 322,00 Subtotal (Goods) 0.00 Non-Consulting Services Provision of Most Single 20/June/2 01/July/20 12,000.0 Limited NC1 WhatsApp Prior DS advantage stage One- 021 21 0 National Messagin ous Bid Envelop g Services Translatio Most 50,000.0 Limited Single 20/June/2 10/July/20 NC2 n, Voice Prior RFP advantage 0 National stage One- 021 21 Over ous Bid Envelop 1 Market Selecti Procurem Revi Approa on Evaluatio ent ew Expected Expected ch Metho n Options Process Contract Estimat by date of date of Ref. (Open- d (BAFO (Single Descripti ed Cost Bank bid/ Contract No Nation (RFP, Rated stage- on (US$) (Prio proposal Signatur al/ RFB, Criteria single r/ opening e Limited RFQ etc.) envelope Post) etc.) etc.) etc.) Recording Service Event Most Managem 60,000.0 Limited Single 20/June/2 10/July/20 NC3 Prior RFP advantage ent 0 National stage One- 021 21 ous Bid Services Envelop Subtotal 122,00 (Non-consulting) 0.00 Consulting Services. Market Expected Method Expected Contract Estimate Review by Approach Date of Ref (QCBS, Date of Descriptio d Cost Bank (Open- Bid No. LCBCS, Contract n (US$) (Prior/Post) National/ Proposal QBS, DS Signature Limited etc.) Opening Health 4,300,000. C1 Technical Prior Direct DS 01/March/2 30/March/20 00 Partner 021 21 ICT based Community Engagement 20/June/202 10/July/2021 150,000.0 Limited C2 and Prior CQS 1 0 National Feedback (Call Centre) Service 2 Consulting Services. Market Expected Method Expected Contract Estimate Review by Approach Date of Ref (QCBS, Date of Descriptio d Cost Bank (Open- Bid No. LCBCS, Contract n (US$) (Prior/Post) National/ Proposal QBS, DS Signature Limited etc.) Opening Mass Media Activity for 27/June/202 01/August/2 C3 100,000.0 Prior Open National CQS Citizen 1 021 0 Engagement Community Mobilization 100,000.0 27/June/202 01/August/2 C4 Prior Open National CQS for Citizen 0 1 021 Engagement Procuremen DS 01/March/2 01/April/202 C5 t Specialist 180,000 Prior Direct 021 1 MoH Financial Managemen 14/June/202 1/July/2021 C6 180,000 Prior Direct t Specialist DS 1 MoH HR 20/June/202 15/July/2021 Limited C7 Governance 60,000.00 Prior INDV 1 National Advisor Communicat ion and Open 20/June/202 01/August/2 C8 60,000.00 Prior INDV Reporting International 1 021 Specialist Health 28/June/202 01/August/2 Limited C9 Program 70,000.00 Prior INDV 1 021 National Coordinator Subtotal 5,200,00 Consulting service 0.00 3 Consulting Services. Market Expected Method Expected Contract Estimate Review by Approach Date of Ref (QCBS, Date of Descriptio d Cost Bank (Open- Bid No. LCBCS, Contract n (US$) (Prior/Post) National/ Proposal QBS, DS Signature Limited etc.) Opening Grand Total (Goods+ 5,644,00 Non-consulting + 0.00 Consulting Services) 4 PROCUREMENT Somalia : Somalia Recurrent Cost & Reform Financing Project - Phase 3 PLAN General Information Country: Somalia 2021-06-15 Bank’s Approval Date of the Original Procurement Plan: 2023-06-05 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P173731 GPN Date: 2021-06-14 Project Name: Somalia Recurrent Cost & Reform Financing Project - Phase 3 Loan / Credit No: IDA / D6580 Federal Government of Somalia Ministry of Finance Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SO-MOF-239594-GO-RFQ / O Component 5: Project Manag Request for Quota Single Stage - One E IDA / D6580 Prior Limited 22,000.00 23,840.00 Signed 2021-06-22 2021-07-28 2021-07-27 2021-08-15 2021-09-10 ffice Equipment for RCRF PIU ement tions nvelope Offices Component 3: Transfers for SO-MOF-238764-GO-RFB / Pr core government functions a Single Stage - One E ocurement of Android Smart IDA / D6580 nd foundational education h Prior Request for Bids Open - National 300,000.00 213,350.00 Signed 2021-06-16 2021-06-16 2021-06-18 2021-06-17 2021-07-16 2021-07-25 2021-08-05 2021-09-07 2021-08-24 2021-09-30 2021-10-08 nvelope Phones with Solar System ealth service delivery mecha nisms in elig ible Federal Me mber States (FMS) Component 3: Transfers for SO-MOF-240070-GO-RFQ / P core government functions a Request for Quota Single Stage - One E urchase of Vehicle (4x4 Doub IDA / D6580 nd foundational education h Prior Limited 40,000.00 0.00 Canceled 2021-07-01 2021-08-19 2021-10-18 tions nvelope le Cabin Pick Up) for MOH PIU ealth service delivery mecha nisms in elig ible Federal Me mber States (FMS) Component 3: Transfers for SO-MOF-240071-GO-RFQ / P core government functions a Request for Quota Single Stage - One E urchase of Office Furniture fo IDA / D6580 nd foundational education h Prior Limited 40,000.00 0.00 Canceled 2021-07-03 2021-08-21 2021-10-05 tions nvelope r MoH PIU ealth service delivery mecha nisms in elig ible Federal Me mber States (FMS) Component 3: Transfers for SO-MOF-243680-GO-RFQ / P core government functions a Request for Quota Single Stage - One E urchase of Vehicle for MoH PI IDA / D6580 nd foundational education h Prior Limited 40,000.00 40,000.00 Signed 2021-07-22 2021-10-06 2021-09-09 2021-10-22 2021-10-24 tions nvelope U ealth service delivery mecha nisms in elig ible Federal Me mber States (FMS) Component 3: Transfers for SO-MOF-244019-GO-RFQ / P core government functions a Request for Quota Single Stage - One E urchase of Office Furniture fo IDA / D6580 nd foundational education h Prior Limited 28,000.00 27,880.00 Signed 2021-07-21 2021-10-13 2021-08-19 2021-10-25 2021-09-09 tions nvelope r MoH PIU ealth service delivery mecha nisms in elig ible Federal Me mber States (FMS) Component 3: Transfers for SO-MOF-244027-GO-RFQ / Pr core government functions a ocurement of Supply and Del Request for Quota Single Stage - One E IDA / D6580 nd foundational education h Prior Limited 13,000.00 24,050.00 Signed 2021-07-22 2021-10-14 2021-08-20 2021-12-21 2021-09-10 ivery of IT Equipment’s for M tions nvelope ealth service delivery mecha oH PIU nisms in elig ible Federal Me mber States (FMS) Component 3: Transfers for SO-MOF-253188-GO-RFQ / O core government functions a Request for Quota Single Stage - One E ffice Equipment for Hirshabel IDA / D6580 nd foundational education h Prior Limited 17,300.00 0.00 Canceled 2021-09-20 2021-10-23 2021-11-22 tions nvelope le MoH ealth service delivery mecha nisms in elig ible Federal Me mber States (FMS) Component 3: Transfers for SO-MOF-255298-GO-RFQ / S core government functions a Request for Quota Single Stage - One E upply of ICT and Office Equip IDA / D6580 nd foundational education h Prior Limited 9,050.00 9,740.00 Signed 2021-10-06 2022-01-02 2021-11-02 2022-01-26 2022-05-01 tions nvelope ment for HSS - MoH. ealth service delivery mecha nisms in elig ible Federal Me mber States (FMS) Component 3: Transfers for SO-MOF-255302-GO-RFQ / S core government functions a Request for Quota Single Stage - One E upply of Office Furniture for IDA / D6580 nd foundational education h Prior Limited 8,250.00 8,400.00 Signed 2021-10-07 2022-01-02 2021-11-03 2022-01-26 2022-05-02 tions nvelope Hirshabelle State - MoH. ealth service delivery mecha nisms in elig ible Federal Me mber States (FMS) SO-MOF-258810-GO-RFQ / S Component 3: Transfers for upply of Office furniture and core government functions a Request for Quota Single Stage - One E Equipment for GSS External IDA / D6580 nd foundational education h Prior Limited 18,890.00 17,890.00 Signed 2021-10-29 2022-01-02 2021-11-23 2022-02-27 2021-12-23 tions nvelope Assistance Fiduciary Section ealth service delivery mecha (EAFS) and the GSS - MOH PI nisms in elig ible Federal Me U offices. mber States (FMS) SO-MOF-258815-GO-RFQ / S Component 3: Transfers for upply of ICT for the GSS MoF core government functions a Request for Quota Single Stage - One E External Assistance Fiduciary IDA / D6580 nd foundational education h Prior Limited 16,090.00 16,250.00 Signed 2021-10-29 2022-01-02 2021-11-25 2022-02-25 2021-12-25 tions nvelope Section (EAFS) and the ealth service delivery mecha MOH PIU offices. nisms in elig ible Federal Me mber States (FMS) Component 3: Transfers for SO-MOF-268882-GO-RFQ / P core government functions a urchase of 4x4 Seven Seater Request for Quota Single Stage - One E IDA / D6580 nd foundational education h Prior Limited 40,000.00 36,500.00 Signed 2021-12-28 2022-03-28 2022-02-11 2022-05-23 2022-03-28 Station Wagon (Toyota Prado tions nvelope ealth service delivery mecha or Equivalent) nisms in elig ible Federal Me mber States (FMS) Component 3: Transfers for SO-MOF-274468-GO-RFQ / S core government functions a upply of office furniture and Request for Quota Single Stage - One E IDA / D6580 nd foundational education h Prior Limited 25,000.00 24,930.00 Signed 2022-01-31 2022-04-25 2022-02-18 2022-07-27 2022-08-17 equipment for Ministry of Ed tions nvelope ealth service delivery mecha ucation nisms in elig ible Federal Me mber States (FMS) Component 3: Transfers for SO-MOF-324962-GO-RFQ / S core government functions a upply of Office Furniture and Request for Quota Single Stage - One E Under Imple IDA / D6580 nd foundational education h Prior Limited 21,000.00 0.00 2022-11-13 2022-12-15 2022-12-01 2023-01-15 Equipment for MoF - South W tions nvelope mentation ealth service delivery mecha est nisms in elig ible Federal Me mber States (FMS) Page 1 SO-MOF-332532-GO-RFQ / S Component 5: Project Manag Request for Quota Single Stage - One E Pending Impl upply of Office Furniture and IDA / D6580 Prior Limited 50,000.00 0.00 2022-12-26 2023-02-03 2023-03-20 ement tions nvelope ementation Equipment for RCRF - PIU Offi ce Component 3: Transfers for SO-MOF-354692-GO-RFB / S core government functions a upply and Delivery of Mobile Single Stage - One E Under Imple IDA / D6580 nd foundational education h Prior Request for Bids Open - National 180,000.00 0.00 2023-04-10 2023-05-09 2023-04-15 2023-06-07 2023-05-27 2023-06-11 2023-06-25 2023-08-09 devices, Tablets and Solar Ch nvelope mentation ealth service delivery mecha arging Solutions nisms in elig ible Federal Me mber States (FMS) SO-MOF-362174-GO-RFQ / O Component 5: Project Manag Request for Quota Single Stage - One E ffice Furniture and renovatio IDA / D6580 Prior Limited 20,000.00 0.00 Canceled 2023-05-25 2023-06-16 2023-07-31 ement tions nvelope n for RCRF Office - FGS Component 3: Transfers for SO-MOF-364142-GO-RFQ / S core government functions a Request for Quota Single Stage - One E Pending Impl upply of ICT and equipment f IDA / D6580 nd foundational education h Prior Limited 10,000.00 0.00 2023-06-05 2023-07-11 2023-08-25 tions nvelope ementation or MOECHE - FGS ealth service delivery mecha nisms in elig ible Federal Me mber States (FMS) SO-MOF-364505-GO-RFQ / P Component 5: Project Manag Request for Quota Single Stage - One E Under Imple urchase of Office Furniture a IDA / D6580 Prior Limited 5,200.00 0.00 2023-06-08 2023-07-14 2023-08-28 ement tions nvelope mentation nd Equipment for RCRF Offic e NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SO-MOF-238775-NC-DIR / W Component 4: Citizen Engag IDA / D6580 Prior Direct Selection Direct 12,000.00 14,652.00 Signed 2021-06-16 2021-06-16 2021-06-19 2021-06-17 2021-07-02 2021-12-13 2022-07-02 hatsApp Messaging Services ement and Feedback SO-MOF-238778-NC-RFQ / Tr Component 4: Citizen Engag Request for Quota Single Stage - One E IDA / D6580 Prior Limited 50,000.00 35,595.00 Signed 2021-06-20 2021-06-29 2021-07-23 2021-08-02 2022-07-23 anslation Voice over Recordi ement and Feedback tions nvelope ng Services SO-MOF-238779-NC-RFQ / E Component 5: Project Manag Request for Quota Single Stage - One E IDA / D6580 Prior Limited 60,000.00 69,125.00 Signed 2021-06-19 2021-06-29 2021-07-20 2021-08-08 2021-08-25 vents Management Services ement tions nvelope Component 3: Transfers for SO-MOF-268864-NC-DIR / Ad core government functions a ditional Work on English-Som IDA / D6580 nd foundational education h Prior Direct Selection Direct 135,000.00 131,980.00 Signed 2021-12-18 2022-01-26 2021-12-23 2022-02-17 2022-01-04 2022-03-30 2022-07-03 ali Somali-English Translation ealth service delivery mecha , Voice -Over Recording nisms in elig ible Federal Me mber States (FMS) SO-MOF-299401-NC-RFQ / W Component 4: Citizen Engag Request for Quota Single Stage - One E Pending Impl ritten Translation of Budget R IDA / D6580 Prior Limited 50,000.00 0.00 2022-06-27 2022-08-11 2023-08-11 ement and Feedback tions nvelope ementation eports and Related Documen ts SO-MOF-362638-NC-DIR / Pr Component 3: Transfers for ocurement of Non Consultin core government functions a g Services for a Health Tech nd foundational education h Direct - Internation Under Imple nical Partner (HTP) to Suppor IDA / D6580 Prior Direct Selection 10,746,208.00 0.00 2023-05-22 2023-06-07 2023-05-27 2023-06-15 2023-07-01 2023-12-28 ealth service delivery mecha al mentation t Implementation of Somalia’ nisms in elig ible Federal Me s Female Health Worker Prog mber States (FMS) ram and Capacity Developm ent in Ministries of Health CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SO-MOF-238785-CS-CQS / C Component 4: Citizen Engag Consultant Qualifi all Centre Service for Citizen IDA / D6580 Prior Limited 150,000.00 156,513.65 Signed 2021-06-17 2021-06-16 2021-07-01 2021-07-23 2021-07-22 2021-10-28 2021-08-19 2021-11-14 2021-09-24 ement and Feedback cation Selection Engagement SO-MOF-238789-CS-CQS / C Component 4: Citizen Engag Consultant Qualifi ommunity Mobilization for Cit IDA / D6580 Prior Open - National 100,000.00 0.00 Canceled 2021-06-18 2021-07-02 2021-08-06 2021-08-07 2021-09-04 2022-09-04 ement and Feedback cation Selection izen Engagement SO-MOF-239596-CS-CQS / M Component 4: Citizen Engag Consultant Qualifi ass Media Activity for Citizen IDA / D6580 Prior Open - National 100,000.00 102,824.90 Signed 2021-06-17 2021-08-18 2021-07-05 2021-08-26 2021-08-08 2021-11-11 2021-09-07 2022-01-10 2021-09-28 2022-01-24 2022-09-28 ement and Feedback cation Selection Engagement SO-MOF-246715-CS-CQS / C Component 4: Citizen Engag Consultant Qualifi ommunity Mobilization for Cit IDA / D6580 Prior Open - National 200,000.00 167,070.12 Signed 2021-08-09 2021-08-16 2021-08-23 2021-08-26 2021-09-27 2021-11-03 2021-10-18 2022-01-04 2021-11-15 2022-01-24 2022-11-15 ement and Feedback cation Selection izen Engagement SO-MOF-290903-CS-LCS / In Component 5: Project Manag Least Cost Selecti Open - Internationa Under Implement dependent Verification Agent IDA / D6580 Prior 100,000.00 0.00 2022-04-24 2022-04-29 2022-05-08 2022-05-03 2022-06-19 2022-11-24 2022-06-20 2023-01-18 2022-07-04 2023-04-18 2022-07-12 2023-06-09 2022-07-26 2023-04-22 ement on l ation for RCRF Expenditure Progra m - 2022/2023 SO-MOF-284926-CS-QCBS / Component 4: Citizen Engag Quality And Cost- Open - Internationa Consultant Services for Impr IDA / D6580 Prior 500,000.00 0.00 Canceled 2022-03-21 2022-04-04 2022-04-21 2022-05-21 2022-06-04 2022-06-18 2022-07-09 2023-12-31 ement and Feedback Based Selection l oving Budget Transparency SO-MOF-299399-CS-CQS / T hink Tank for Policy Briefs on Component 4: Citizen Engag Consultant Qualifi Under Implement IDA / D6580 Prior Open - National 100,000.00 0.00 2022-06-16 2022-06-15 2022-07-07 2022-06-20 2022-08-11 2022-12-24 2022-08-18 2022-09-08 2023-09-08 Budget Cycle: Citizen Engage ement and Feedback cation Selection ation ment and Feedback SO-MOF-299400-CS-CQS / S Component 4: Citizen Engag Consultant Qualifi Under Implement upport for Budget Transpare IDA / D6580 Prior Open - National 200,000.00 0.00 2022-06-16 2022-06-15 2022-06-30 2022-06-20 2022-08-04 2022-10-11 2022-08-25 2023-02-16 2022-09-18 2023-09-18 ement and Feedback cation Selection ation ncy under Citizen Engageme nt and Feedback SO-MOF-348226-CS-LCS / Pr Component 5: Project Manag Least Cost Selecti Open - Internationa Under Implement ojects Audit for WB funded Pr IDA / D6580 Prior 250,000.00 0.00 2023-03-20 2023-04-03 2023-03-22 2023-04-12 2023-04-15 2023-04-22 2023-04-28 2023-05-18 2023-06-02 2024-06-01 ement on l ation ojects for 2022 INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 2 SO-MOF-238781-CS-CDS / H Component 3: Transfers for EALTH TECHNICAL PARTNER core government functions a (HTP) TO SUPPORT IMPLEME nd foundational education h NTATION OF SOMALIA FEMAL IDA / D6580 Prior Direct Selection Direct 4,300,000.00 4,268,149.12 Signed 2021-06-16 2021-06-16 2021-06-22 2021-06-24 2021-07-16 2021-07-01 2022-07-16 ealth service delivery mecha E HEALTH WORKER PROGRA nisms in elig ible Federal Me M & CAPACITY DEVELOPMEN mber States (FMS) T IN MINISTRIES OF HEALTH Component 3: Transfers for SO-MOF-238791-CS-CDS / Pr core government functions a ocurement Specialist Consult IDA / D6580 nd foundational education h Prior Direct Selection Direct 180,000.00 254,400.00 Signed 2021-06-16 2021-06-16 2021-06-24 2021-07-11 2021-07-14 2021-08-02 2021-08-19 ing Services ealth service delivery mecha nisms in elig ible Federal Me mber States (FMS) Component 3: Transfers for SO-MOF-238800-CS-INDV / I core government functions a ndependent Verification Age Individual Consult IDA / D6580 nd foundational education h Prior Limited 15,000.00 14,900.00 Signed 2021-06-16 2021-07-23 2021-06-21 2021-08-22 2021-07-01 2021-08-26 2021-07-15 2021-08-29 2021-08-26 nt for RCRF II Expenditure Pr ant Selection ealth service delivery mecha ogram - Individual Consultant nisms in elig ible Federal Me mber States (FMS) SO-MOF-239592-CS-INDV / H Component 2: Strengthen in uman Resource Governance Individual Consult IDA / D6580 ter-governmental fiscal relat Prior Limited 70,000.00 129,360.00 Signed 2021-06-16 2021-06-16 2021-06-21 2021-07-29 2021-07-05 2021-08-04 2021-07-19 2021-08-06 2022-07-19 Advisor for National Civil Ser ant Selection ions vice Commission Component 3: Transfers for SO-MOF-239593-CS-CDS / Fi core government functions a nancial Management Speciali IDA / D6580 nd foundational education h Prior Direct Selection Direct 200,000.00 0.00 Canceled 2021-06-16 2021-06-16 2021-06-21 2021-07-12 2021-07-12 2022-07-12 st for Ministry of Health ealth service delivery mecha nisms in elig ible Federal Me mber States (FMS) SO-MOF-240056-CS-CDS / PF Component 5: Project Manag MRCU Financial Management IDA / D6580 Prior Direct Selection Direct 55,000.00 0.00 Canceled 2021-06-19 2021-06-29 2021-08-12 2022-08-12 ement Specialist Services SO-MOF-240057-CS-CDS / S Component 5: Project Manag IDA / D6580 Prior Direct Selection Direct 85,000.00 0.00 Canceled 2021-06-19 2021-06-29 2021-07-20 2022-07-20 enior Financial Management ement Consultant Component 3: Transfers for SO-MOF-240062-CS-INDV / S core government functions a Individual Consult enior RCRF Health Focal Poin IDA / D6580 nd foundational education h Prior Open 70,000.00 76,800.00 Signed 2021-06-22 2021-06-29 2021-08-09 2021-11-14 2021-08-23 2022-02-02 2021-09-20 2022-02-23 2022-09-20 ant Selection t ealth service delivery mecha nisms in elig ible Federal Me mber States (FMS) Component 3: Transfers for SO-MOF-240064-CS-INDV / S core government functions a Individual Consult enior Monitoring and Evaluati IDA / D6580 nd foundational education h Prior Open 70,000.00 67,440.00 Signed 2021-06-26 2021-06-28 2021-08-05 2021-10-28 2021-08-26 2021-11-11 2021-09-23 2021-11-29 2022-09-23 ant Selection on Specialist ealth service delivery mecha nisms in elig ible Federal Me mber States (FMS) SO-MOF-240067-CS-CDS / G Component 5: Project Manag IDA / D6580 Prior Direct Selection Direct 55,000.00 121,880.00 Signed 2021-06-20 2021-06-28 2021-06-30 2021-07-20 2021-07-21 2021-08-03 2022-07-21 almudug RCRF Project Manag ement er SO-MOF-240068-CS-CDS / Ex Component 5: Project Manag ternal Financing Coordination IDA / D6580 Prior Direct Selection Direct 50,000.00 104,400.00 Signed 2021-06-19 2021-07-13 2021-06-29 2021-07-20 2021-07-20 2021-07-29 2022-07-20 ement Specialist SO-MOF-241523-CS-CDS / H Component 5: Project Manag IDA / D6580 Prior Direct Selection Direct 31,800.00 60,480.00 Signed 2021-06-30 2021-06-30 2021-07-06 2021-07-20 2021-07-28 2021-07-23 2022-07-28 SS Community Health Coordi ement nator SO-MOF-241524-CS-CDS / H Component 5: Project Manag SS Contracts Management a IDA / D6580 Prior Direct Selection Direct 31,800.00 60,480.00 Signed 2021-06-30 2021-06-30 2021-07-10 2021-07-20 2021-07-25 2021-07-20 2022-07-25 ement nd M&E Specialist SO-MOF-244091-CS-CDS / E Component 5: Project Manag IDA / D6580 Prior Direct Selection Direct 55,000.00 117,220.00 Signed 2021-07-17 2021-07-28 2021-07-27 2021-08-03 2021-08-18 2021-08-09 2022-08-18 AFS Financial Management C ement onsultant SO-MOF-244094-CS-CDS / R Component 5: Project Manag IDA / D6580 Prior Direct Selection Direct 85,000.00 171,960.00 Signed 2021-07-17 2021-07-28 2021-07-27 2021-08-02 2021-08-15 2021-09-03 2021-09-20 CRF Financial Management C ement onsultant SO-MOF-245179-CS-CDS / R Component 5: Project Manag IDA / D6580 Prior Direct Selection Direct 88,000.00 174,960.00 Signed 2021-07-27 2021-08-19 2021-08-06 2021-09-06 2021-09-01 2021-09-12 2022-09-01 CRF Project Coordinator ement SO-MOF-246702-CS-CDS / R Component 5: Project Manag IDA / D6580 Prior Direct Selection Direct 50,000.00 102,120.00 Signed 2021-08-07 2021-08-17 2021-08-17 2021-08-22 2021-09-12 2021-09-12 2022-09-12 CRF Program Officer ement Component 3: Transfers for SO-MOF-246709-CS-INDV / F core government functions a Individual Consult Under Implement inancial and Accounting Tech IDA / D6580 nd foundational education h Prior Open 50,000.00 0.00 2021-08-09 2021-08-17 2021-09-27 2021-10-11 2021-11-08 2021-12-14 ant Selection ation nical Assistant ealth service delivery mecha nisms in elig ible Federal Me mber States (FMS) Component 3: Transfers for SO-MOF-246711-CS-INDV / H core government functions a Individual Consult R and Administration Technic IDA / D6580 nd foundational education h Prior Open 50,000.00 0.00 Canceled 2021-08-09 2021-08-25 2021-08-30 2021-09-20 2021-10-18 2022-10-18 ant Selection al Assistant ealth service delivery mecha nisms in elig ible Federal Me mber States (FMS) Component 3: Transfers for SO-MOF-246712-CS-INDV / P core government functions a Individual Consult rocurement Technical Assista IDA / D6580 nd foundational education h Prior Open 50,000.00 60,280.00 Signed 2021-08-09 2021-08-17 2021-09-18 2022-01-25 2021-10-09 2022-02-02 2021-11-06 2022-02-07 2022-11-06 ant Selection nt ealth service delivery mecha nisms in elig ible Federal Me mber States (FMS) Component 3: Transfers for SO-MOF-248385-CS-CDS / C core government functions a ommunity Health Coordinato IDA / D6580 nd foundational education h Prior Direct Selection Direct 30,240.00 60,480.00 Signed 2021-08-18 2021-08-19 2021-08-28 2021-08-23 2021-09-19 2021-08-31 2022-09-19 r for Jubbaland State ealth service delivery mecha nisms in elig ible Federal Me mber States (FMS) Component 3: Transfers for SO-MOF-253451-CS-CDS / M core government functions a OH Financial Management Sp IDA / D6580 nd foundational education h Prior Direct Selection Direct 200,000.00 216,000.00 Signed 2021-09-17 2021-10-06 2021-09-25 2021-10-08 2021-10-23 2021-10-28 2022-10-23 ecialist ealth service delivery mecha nisms in elig ible Federal Me mber States (FMS) SO-MOF-257038-CS-CDS / E Component 5: Project Manag IDA / D6580 Prior Direct Selection Direct 55,000.00 110,880.00 Signed 2021-10-11 2021-10-20 2021-10-21 2021-10-27 2021-11-07 2021-11-02 2022-11-07 AFS Financial Management S ement pecialist 1 SO-MOF-257049-CS-CDS / E Component 5: Project Manag Under Implement IDA / D6580 Prior Direct Selection Direct 62,000.00 0.00 2021-10-11 2021-10-20 2021-10-21 2021-11-16 2022-11-16 AFS Financial Management S ement ation pecialist 2 Page 3 Component 3: Transfers for SO-MOF-259508-CS-CDS / Ju core government functions a bbaland Contract Manageme IDA / D6580 nd foundational education h Prior Direct Selection Direct 35,000.00 34,200.00 Signed 2021-10-24 2021-11-01 2021-11-03 2021-11-02 2021-11-24 2021-11-08 2022-11-24 nt, Monitoring & Evaluation S ealth service delivery mecha pecialist nisms in elig ible Federal Me mber States (FMS) SO-MOF-263366-CS-INDV / S Component 5: Project Manag Individual Consult IDA / D6580 Prior Limited 40,000.00 0.00 Canceled 2021-11-22 2021-11-19 2021-11-27 2021-12-11 2022-01-08 2022-07-07 ecurity Risk Management Co ement ant Selection nsultant SO-MOF-264788-CS-CDS / PF Component 5: Project Manag IDA / D6580 Prior Direct Selection Direct 80,000.00 73,420.00 Signed 2021-11-30 2021-11-29 2021-12-08 2021-12-07 2021-12-27 2022-01-20 2022-12-27 MRCU Office Secretary ement SO-MOF-264796-CS-CDS / G Component 5: Project Manag IDA / D6580 Prior Direct Selection Direct 61,000.00 65,880.00 Signed 2021-11-27 2021-12-22 2021-12-07 2021-12-25 2021-12-24 2022-01-26 2022-12-24 ender Based Violence (GBV) ement Expert SO-MOF-264800-CS-CDS / Fi Component 2: Strengthen in IDA / D6580 Prior Direct Selection Direct 98,980.00 98,980.00 Signed 2021-11-27 2021-12-06 2021-12-07 2022-02-16 2021-12-27 2022-03-08 2022-12-27 scal Federalism Expert ter-governmental fiscal relat ions SO-MOF-264804-CS-CDS / As Component 2: Strengthen in sistant to Extended Credit Fa IDA / D6580 ter-governmental fiscal relat Prior Direct Selection Direct 74,000.00 73,420.00 Signed 2021-11-27 2021-11-29 2021-12-08 2021-12-11 2021-12-26 2022-01-10 2022-12-26 cility Coordinator ions SO-MOF-264807-CS-CDS / S Component 2: Strengthen in ecretary 3 Intergovernmental IDA / D6580 ter-governmental fiscal relat Prior Direct Selection Direct 40,000.00 39,840.00 Signed 2021-11-27 2021-12-01 2021-12-07 2021-12-11 2021-12-27 2022-01-12 2022-12-27 Fiscal Federalism Secretariat ions SO-MOF-264808-CS-CDS / S Component 2: Strengthen in ecretary 1 Intergovernmental IDA / D6580 ter-governmental fiscal relat Prior Direct Selection Direct 40,000.00 39,840.00 Signed 2021-11-27 2021-12-01 2021-12-05 2021-12-11 2021-12-26 2022-01-12 2022-12-26 Fiscal Federalism Secretariat ions SO-MOF-265944-CS-CDS / S Component 5: Project Manag ocial Safeguarding Specialist, IDA / D6580 Prior Direct Selection Direct 15,780.00 18,600.00 Signed 2021-12-04 2021-12-07 2021-12-12 2021-12-08 2021-12-31 2022-01-09 2022-12-31 ement for Jubbaland SO-MOF-266896-CS-CDS / S Component 5: Project Manag ocial Safeguarding Specialist, IDA / D6580 Prior Direct Selection Direct 18,000.00 18,000.00 Signed 2021-12-08 2021-12-07 2021-12-17 2021-12-08 2021-12-31 2021-12-25 2022-12-31 ement for Galnudug State SO-MOF-267657-CS-CDS / S Component 5: Project Manag ocial Safeguard Specialist -So IDA / D6580 Prior Direct Selection Direct 24,000.00 24,000.00 Signed 2021-12-12 2021-12-16 2021-12-20 2021-12-19 2021-12-31 2021-12-24 2022-12-31 ement uthwest State, Somalia Component 3: Transfers for core government functions a SO-MOF-268873-CS-INDV / E Individual Consult IDA / D6580 nd foundational education h Prior Open 65,000.00 61,920.00 Signed 2021-12-20 2022-01-14 2022-02-07 2022-04-14 2022-02-21 2022-04-21 2022-03-17 2022-04-24 2023-03-17 MIS Data Analyst/Specialist ant Selection ealth service delivery mecha nisms in elig ible Federal Me mber States (FMS) SO-MOF-270404-CS-CDS / S Component 5: Project Manag ocial Safeguards Specialists- IDA / D6580 Prior Direct Selection Direct 18,000.00 18,000.00 Signed 2021-12-23 2021-12-25 2021-12-27 2021-12-28 2022-01-02 2021-12-29 2023-01-02 ement Hirshabelle State of Somalia SO-MOF-272465-CS-CDS / S Component 5: Project Manag IDA / D6580 Prior Direct Selection Direct 56,000.00 57,700.00 Signed 2022-01-12 2022-01-11 2022-01-18 2022-01-27 2022-01-31 2022-02-06 2023-01-31 WSS RCRF III Project Manage ement r Component 3: Transfers for SO-MOF-275267-CS-INDV / H core government functions a uman Resource/Civil Service Individual Consult IDA / D6580 nd foundational education h Prior Direct 55,000.00 26,160.00 Signed 2022-02-03 2022-03-02 2022-02-09 2022-03-15 2022-02-14 2022-03-21 2022-02-24 2022-04-18 2023-02-24 Advisor for Civil Service Com ant Selection ealth service delivery mecha mission of FMSs nisms in elig ible Federal Me mber States (FMS) SO-MOF-276050-CS-CDS / Hi Component 5: Project Manag IDA / D6580 Prior Direct Selection Direct 55,000.00 51,630.00 Under Review 2022-02-03 2022-02-15 2022-02-08 2022-02-16 2022-02-21 2022-03-05 2023-02-21 rshabelle RCRF III Project Ma ement nager SO-MOF-276052-CS-INDV / S Component 5: Project Manag Individual Consult IDA / D6580 Prior Open 40,000.00 54,700.00 Signed 2022-02-03 2022-02-15 2022-02-27 2022-05-14 2022-03-09 2022-05-20 2022-03-19 2022-06-02 2022-09-15 ecurity Risk Management Co ement ant Selection nsultant SO-MOF-279657-CS-INDV / S Component 5: Project Manag Individual Consult IDA / D6580 Prior Limited 50,000.00 49,920.00 Signed 2022-02-21 2022-03-07 2022-02-26 2022-04-20 2022-03-19 2022-04-29 2022-04-12 2022-05-22 2023-04-12 ocial Safeguard Specialist ement ant Selection SO-MOF-281899-CS-CDS / Ju bbaland RCRF III Project Man ager. The Consultant was co Component 5: Project Manag IDA / D6580 Prior Direct Selection Direct 90,480.00 90,480.00 Signed 2022-03-05 2022-03-17 2022-03-10 2022-03-21 2022-03-19 2022-05-18 2023-03-19 ntracted for this position und ement er RCRF II and is being move d to RCRF III under same ter ms and conditions. SO-MOF-284568-CS-CDS / R Component 5: Project Manag IDA / D6580 Prior Direct Selection Direct 74,000.00 73,380.00 Signed 2022-03-19 2022-04-13 2022-03-23 2022-04-21 2022-03-30 2022-05-08 2023-03-30 CRF Education Coordinator ement SO-MOF-284574-CS-CDS / S Component 5: Project Manag enior Adviser - Intergovernm IDA / D6580 Prior Direct Selection Direct 72,000.00 71,600.00 Signed 2022-03-19 2022-03-29 2022-03-24 2022-04-03 2022-03-31 2022-04-24 2023-03-31 ement ental Education Forum Com mittee) (IGEFC) SO-MOF-284579-CS-CDS / Pr Component 5: Project Manag IDA / D6580 Prior Direct Selection Direct 59,000.00 58,900.00 Signed 2022-03-19 2022-03-21 2022-03-24 2022-04-06 2022-04-04 2022-04-22 2023-04-04 oject Administrative Assistan ement t SO-MOF-284835-CS-CDS / S Component 5: Project Manag ecretary 4, Inter-Government IDA / D6580 Prior Direct Selection Direct 39,840.00 39,840.00 Signed 2022-03-19 2022-03-21 2022-03-29 2022-03-22 2022-04-09 2022-05-15 2023-04-09 ement al Federalism SO-MOF-284840-CS-CDS / E Component 5: Project Manag IDA / D6580 Prior Direct Selection Direct 62,800.00 63,240.00 Signed 2022-03-19 2022-03-28 2022-03-25 2022-03-29 2022-04-07 2022-04-22 2022-04-10 AFS Financial Management S ement pecialist SO-MOF-284894-CS-CDS / H Component 3: Transfers for uman Resource and Civil Ser core government functions a vant Advisor for Hirshabelle S IDA / D6580 nd foundational education h Prior Direct Selection Direct 30,000.00 26,160.00 Signed 2022-03-20 2022-03-28 2022-03-30 2022-03-31 2022-04-12 2022-04-17 2022-10-09 tate Civil Service Commissio ealth service delivery mecha n. nisms in elig ible Federal Me mber States (FMS) Component 3: Transfers for SO-MOF-284921-CS-CDS / H core government functions a ealth Technical Partner for Fe IDA / D6580 nd foundational education h Prior Direct Selection Direct 5,000,000.00 4,700,000.00 Signed 2022-03-21 2022-04-06 2022-03-31 2022-04-13 2022-04-13 2022-06-02 2023-01-08 male Health Worker Program ealth service delivery mecha . nisms in elig ible Federal Me mber States (FMS) SO-MOF-284562-CS-CDS / N Component 5: Project Manag IDA / D6580 Prior Direct Selection Direct 67,800.00 65,020.00 Signed 2022-03-19 2022-03-30 2022-03-25 2022-04-03 2022-04-06 2022-04-22 2023-04-06 ational Procurement Speciali ement st Page 4 SO-MOF-284853-CS-CDS / R Component 5: Project Manag IDA / D6580 Post Direct Selection Direct 87,720.00 0.00 Canceled 2022-03-19 2022-03-27 2022-04-09 2022-05-15 CRF Financial Management C ement onsultant Component 3: Transfers for SO-MOF-287023-CS-INDV / C core government functions a Individual Consult ommunity Health Coordinato IDA / D6580 nd foundational education h Prior Direct 30,240.00 30,240.00 Signed 2022-04-02 2022-04-20 2022-04-09 2022-04-26 2022-04-14 2022-05-02 2022-04-22 2022-05-22 2023-04-22 ant Selection r Southwest ealth service delivery mecha nisms in elig ible Federal Me mber States (FMS) Component 3: Transfers for SO-MOF-287027-CS-CDS / C core government functions a ontracts Management and M IDA / D6580 nd foundational education h Prior Direct Selection Direct 30,240.00 30,240.00 Signed 2022-04-02 2022-04-20 2022-04-09 2022-04-26 2022-04-22 2022-05-20 2023-04-22 &E Specialist –MoH SWSS ealth service delivery mecha nisms in elig ible Federal Me mber States (FMS) Component 3: Transfers for SO-MOF-287034-CS-CDS / C core government functions a ommunity Health Coordinato IDA / D6580 nd foundational education h Prior Direct Selection Direct 56,000.00 56,520.00 Signed 2022-04-02 2022-04-20 2022-04-12 2022-04-27 2022-04-25 2022-05-21 2023-04-25 r, MoH – FGS ealth service delivery mecha nisms in elig ible Federal Me mber States (FMS) Component 3: Transfers for SO-MOF-287219-CS-INDV / A core government functions a Individual Consult Under Implement ssessment of Female particip IDA / D6580 nd foundational education h Prior Limited 15,000.00 0.00 2022-04-02 2022-04-08 2022-04-07 2022-11-14 2022-04-28 2022-11-29 2022-05-26 2022-07-25 ant Selection ation ation in Teaching. ealth service delivery mecha nisms in elig ible Federal Me mber States (FMS) Component 3: Transfers for core government functions a SO-MOF-288270-CS-CDS / D IDA / D6580 nd foundational education h Prior Direct Selection Direct 43,440.00 43,440.00 Signed 2022-04-06 2022-04-20 2022-04-12 2022-04-27 2022-04-25 2022-05-21 2023-04-25 ata Analyst – MoH – FGS ealth service delivery mecha nisms in elig ible Federal Me mber States (FMS) Component 3: Transfers for SO-MOF-288274-CS-CDS / C core government functions a ommunity Health Coordinato IDA / D6580 nd foundational education h Prior Direct Selection Direct 30,240.00 30,240.00 Signed 2022-04-06 2022-04-20 2022-04-12 2022-05-04 2022-04-27 2022-05-26 2023-04-27 r -GSS ealth service delivery mecha nisms in elig ible Federal Me mber States (FMS) SO-MOF-288420-CS-CDS / C Component 5: Project Manag ustoms Automated System L IDA / D6580 Prior Direct Selection Direct 50,000.00 49,970.00 Signed 2022-04-07 2022-04-08 2022-04-13 2022-04-21 2022-04-26 2022-05-23 2022-06-10 ement ead Consultant SO-MOF-288421-CS-CDS / Pu Component 2: Strengthen in blic Financial Management (P IDA / D6580 ter-governmental fiscal relat Prior Direct Selection Direct 55,000.00 50,900.00 Signed 2022-04-07 2022-04-19 2022-04-13 2022-05-05 2022-04-28 2022-06-08 2022-10-25 FM) Reform Expert ions SO-MOF-288422-CS-CDS / Ac Component 2: Strengthen in counting and Financial Mana IDA / D6580 ter-governmental fiscal relat Prior Direct Selection Direct 90,000.00 86,640.00 Signed 2022-04-07 2022-04-12 2022-04-13 2022-04-23 2022-04-28 2022-05-17 2023-04-28 gement Technical Assistant ions Component 3: Transfers for SO-MOF-290902-CS-INDV / H core government functions a uman Resource & Administra Individual Consult IDA / D6580 nd foundational education h Prior Open 50,000.00 0.00 Signed 2022-04-23 2022-04-26 2022-06-07 2022-10-03 2022-06-17 2022-10-11 2022-07-11 2023-06-07 2023-07-11 tion Technical Assistant, Mini ant Selection ealth service delivery mecha stry of Education nisms in elig ible Federal Me mber States (FMS) Component 3: Transfers for SO-MOF-292062-CS-INDV / C core government functions a ontract Management and M& Individual Consult IDA / D6580 nd foundational education h Prior Open 30,240.00 30,240.00 Signed 2022-04-28 2022-04-29 2022-05-22 2022-08-28 2022-05-23 2022-09-05 2022-06-07 2022-09-02 2023-06-07 E Specialist - Galmudug Stat ant Selection ealth service delivery mecha e of Somalia nisms in elig ible Federal Me mber States (FMS) SO-MOF-284871-CS-CDS / Ac counting and Financial Mana Component 5: Project Manag IDA / D6580 Post Direct Selection Direct 86,640.00 0.00 Canceled 2022-03-20 2022-03-26 2022-04-08 2023-04-08 gement Technical Advisor - O ement ffice of the Accountant Gener al. Component 3: Transfers for SO-MOF-299395-CS-INDV / I core government functions a Individual Consult Under Implement nternal Audit Technical Assist IDA / D6580 nd foundational education h Prior Open 55,000.00 0.00 2022-06-16 2022-06-15 2022-08-04 2022-08-11 2022-09-01 2023-09-01 ant Selection ation ant for MoH - FGS ealth service delivery mecha nisms in elig ible Federal Me mber States (FMS) Component 3: Transfers for SO-MOF-299397-CS-INDV / D core government functions a Individual Consult Under Implement igital Health Coordinator for IDA / D6580 nd foundational education h Prior Open 55,000.00 0.00 2022-06-16 2022-06-14 2022-08-04 2022-08-11 2022-09-01 2023-09-01 ant Selection ation MoH, FGS ealth service delivery mecha nisms in elig ible Federal Me mber States (FMS) SO-MOF-257051-CS-INDV / E Component 5: Project Manag Individual Consult IDA / D6580 Prior Open 50,000.00 0.00 Canceled 2021-10-11 2021-10-20 2021-11-20 2021-12-04 2021-12-25 2022-12-25 AFS Risk Management Specia ement ant Selection list SO-MOF-301510-CS-CDS / Pr Component 5: Project Manag ocurement Specialist/Technic IDA / D6580 Post Direct Selection Direct 100,000.00 0.00 Canceled 2022-06-28 2022-07-19 2022-07-06 2022-07-19 2023-07-19 ement al Assistant SO-MOF-312477-CS-INDV / P Component 5: Project Manag Individual Consult Open - Internationa rocurement Specialist/Techni IDA / D6580 Prior 180,000.00 0.00 Signed 2022-09-03 2022-09-23 2022-10-07 2023-02-22 2022-10-12 2023-03-01 2022-10-25 2023-06-07 2023-10-25 ement ant Selection l cal Assistant SO-MOF-299402-CS-INDV / C Component 5: Project Manag Individual Consult Under Implement ommunications Specialist for IDA / D6580 Prior Limited 50,000.00 0.00 2022-09-13 2022-10-24 2022-09-19 2022-09-29 2022-10-14 2023-10-14 ement ant Selection ation RCRF Project SO-MOF-325518-CS-INDV / F Component 2: Strengthen in Individual Consult IDA / D6580 Prior Open - National 70,000.00 0.00 Signed 2022-11-13 2022-11-21 2022-12-12 2023-02-26 2022-12-22 2023-03-01 2023-01-06 2023-06-07 2024-01-06 ederalism Adviser ter-governmental fiscal relat ant Selection ions Component 3: Transfers for SO-MOF-330993-CS-INDV / J core government functions a Individual Consult Under Implement ubbaland Community Health IDA / D6580 nd foundational education h Prior Open - National 30,240.00 0.00 2022-12-14 2022-12-24 2023-01-12 2023-04-13 2023-01-22 2023-04-17 2023-02-04 2024-02-04 ant Selection ation Coordinator ealth service delivery mecha nisms in elig ible Federal Me mber States (FMS) SO-MOF-330988-CS-INDV / T Component 5: Project Manag Individual Consult Under Implement IDA / D6580 Prior Limited 59,000.00 0.00 2022-12-15 2022-12-14 2022-12-20 2023-02-04 2022-12-30 2023-02-09 2023-01-14 2024-01-14 echnical Administrative Assis ement ant Selection ation tant SO-MOF-330991-CS-INDV / R Component 5: Project Manag Individual Consult eform Reporting and Perform IDA / D6580 Prior Direct - National 74,000.00 0.00 Signed 2022-12-15 2022-12-15 2022-12-25 2022-12-21 2023-01-04 2023-01-11 2023-01-19 2023-06-07 2024-01-19 ement ant Selection ance Specialist Page 5 Component 3: Transfers for SO-MOF-337754-CS-CDS / Hi core government functions a Under Implement rshabelle Social Safeguards S IDA / D6580 nd foundational education h Prior Direct Selection Direct - National 18,000.00 0.00 2023-01-25 2023-01-30 2023-01-29 2023-02-02 2023-02-06 2024-02-06 ation pecialist ealth service delivery mecha nisms in elig ible Federal Me mber States (FMS) Component 3: Transfers for SO-MOF-337757-CS-CDS / S core government functions a Under Implement ocial Safeguards Specialist -S IDA / D6580 nd foundational education h Prior Direct Selection Direct - National 24,000.00 0.00 2023-01-25 2023-01-31 2023-01-29 2023-02-04 2023-02-05 2024-02-05 ation outh West State ealth service delivery mecha nisms in elig ible Federal Me mber States (FMS) SO-MOF-346749-CS-CDS / IC Component 4: Citizen Engag Under Implement T-Based Call Center Services IDA / D6580 Prior Direct Selection Direct - National 450,000.00 0.00 2023-03-04 2023-03-25 2023-03-11 2023-04-24 2023-04-05 2024-09-26 ement and Feedback ation for Citizen Engagement and Feedback SO-MOF-354687-CS-INDV / S Component 5: Project Manag Individual Consult Under Implement enior Social and Gender Bas IDA / D6580 Prior Open - National 61,000.00 0.00 2023-04-06 2023-04-17 2023-05-01 2023-05-11 2023-05-26 2024-05-25 ement ant Selection ation ed Violence Specialist Component 3: Transfers for SO-MOF-356886-CS-INDV / A core government functions a dmin and Finance Specialist - IDA / D6580 nd foundational education h Prior Direct Selection Direct - National 36,000.00 0.00 Signed 2023-04-27 2023-05-18 2023-05-05 2023-05-27 2023-05-30 2023-06-20 2024-05-29 MoH ealth service delivery mecha nisms in elig ible Federal Me mber States (FMS) SO-MOF-369294-CS-INDV / P Component 5: Project Manag Individual Consult Under Implement rocurement of Individual Con IDA / D6580 Prior Open - National 60,000.00 0.00 2023-06-30 2023-06-29 2023-08-18 2023-09-08 2023-10-13 2024-04-10 ement ant Selection ation sultant: Security Specialist Page 6 GOVERNMENT OF THE KINGDOM OF ESWATINI GENERAL PROCUREMENT NOTICE Country: Kingdom of Eswatini Project: Health System Strengthening for Human Capital Development Project Sector: Health Project ID No.: P168564 The Ministry of Health has received financing in the amount of US$20 Million amount equivalent from the World Bank toward the cost of the ESWATINI MINISTRY OF HEALTH SYSTEMS STRENGTHENING FOR HUMAN CAPITAL DEVELOPMENT PROJECT and it intends to apply part of the proceeds to payments for goods, works, related services and consulting services to be procured under this project. The project aims to to improve the coverage and quality of key reproductive, maternal, neonatal, child and adolescent health (RMNCAH), nutrition and NCD services (hypertension and diabetes) in Eswatini and will include the following components. Component 1: Improve health service delivery to increase the coverage and quality of health services to build human capital. Component 2. Increase community demand for RMNCAH, nutrition and NCD services. Component 3. Strengthen the MOH’s stewardship capacity to manage essential health and nutrition services and project activities. The project will broadly support the procurement of the following categories of items under the open international approach to market: Technical assistance and procurement of tablets/technology to develop, test and scale-up provider digital decision support tools for RMNCAH, International specialist neonatal nurses, procurement of commodities and equipment for nutrition and NCDs including micronutrient supplements and therapeutic foods, procurement of biomedical equipment and supplies including patient monitors, ICU beds, oxygen concentrators, waste skips, and disinfectant. Technical assistance to strengthen supportive supervision and mentorship for RMNCAH, nutrition and NCDs. Procurement of contracts financed by the proceeds of the proposed IBRD loan will be conducted through the procedures as specified in the World Bank’s Procurement Regulations for IPF Borrowers (July 2016) (Procurement Regulations), as amended from time to time, and is open to all eligible firms and individuals as defined in the Procurement Regulations. Specific procurement notices for contracts to be bid under the World Bank’s open international approach to market procedures and for contracts for consultancy services will be announced, as they become available, in UN Development Business and dgMarket, local and regional newspapers. Address of the Project Implementing Unit Ministry of Health Headquarters P. O. Box 5 Mbabane Telephone number: +268 2404 3757 Fax number: +268 2404 2092 E-mail address: smz1157@gmail.com PROCUREMENT Eswatini : Health System Strengthening for Human Capital Development in Eswatini PLAN General Information Country: Eswatini 2021-03-09 Bank’s Approval Date of the Original Procurement Plan: 2023-06-02 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P168564 GPN Date: 2021-03-03 Project Name: Health System Strengthening for Human Capital Development in Eswatini Loan / Credit No: IBRD / 91260 Ministry of Health Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Component 1: Improve healt Request for Bids - SZ-MOH-251848-CW-RFB / L h service delivery to increas Single Stage - One E Works (without pr 1,003,856.3 2022-07-1 ot No 1. Construction of Oper IBRD / 91260 Post Request for Bids Open - National 1,154,574.00 Signed 2021-09-24 2021-09-28 2021-09-29 2021-10-05 2021-11-10 2021-11-12 2021-12-10 2021-11-24 2022-01-14 2022-02-09 e the coverage and quality o nvelope equalification) SP 0 3 ation Centre f health services to build hu D man capita l SZ-MOH-254269-CW-RFB / L Component 1: Improve healt Request for Bids - ot No 2 Construction of Office h service delivery to increas Single Stage - One E Works (without pr 1,967,625.4 2022-07-1 IBRD / 91260 Post Request for Bids Open - National 670,272.00 Signed 2021-09-27 2021-09-28 2021-10-02 2021-10-05 2021-11-13 2021-11-12 2021-12-13 2021-11-24 2022-01-17 2022-06-22 s & Workshops for Biomed an e the coverage and quality o nvelope equalification) SP 9 6 d HMIS f health services to build hu D man capita l GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 1: Improve healt SZ-MOH-225077-GO-RFB / Pr h service delivery to increas Open - Internationa Single Stage - One E ocurement of Primary Health IBRD / 91260 Post Request for Bids 1,162,080.00 387,875.71 Signed 2021-04-01 2021-04-06 2021-04-06 2021-04-16 2021-05-18 2021-05-31 2021-06-17 2021-06-09 2021-07-22 2021-10-28 2022-01-18 2022-03-17 e the coverage and quality o l nvelope Care goods f health services to build hu man capita l Component 1: Improve healt SZ-MOH-225079-GO-RFB / S h service delivery to increas Open - Internationa Single Stage - One E upply and Delivery of Vehicle IBRD / 91260 Post Request for Bids 759,000.00 572,881.09 Completed 2021-04-01 2021-04-06 2021-04-06 2021-04-16 2021-05-18 2021-06-01 2021-06-17 2021-06-10 2021-07-22 2021-09-23 2022-01-18 2022-02-19 e the coverage and quality o l nvelope s and Waste kips f health services to build hu man capita l Component 3. Strengthen th SZ-MOH-228885-GO-RFQ / O e MOH’s stewardship capacit Request for Quota Single Stage - One E ffice Equipment & Supplies fo IBRD / 91260 Post Limited 20,000.00 4,233.91 Signed 2021-04-24 2021-05-06 2021-06-19 2021-07-29 2021-12-16 y to manage essential healt tions nvelope r PIU h and nutrition services and project activ ities Component 3. Strengthen th SZ-MOH-229665-GO-RFQ / S e MOH’s stewardship capacit Request for Quota Single Stage - One E upply and Delivery of Office F IBRD / 91260 Post Limited 7,000.00 7,495.09 Completed 2021-04-25 2021-04-28 2021-06-20 2021-08-24 2021-12-17 2021-12-04 y to manage essential healt tions nvelope urniture h and nutrition services and project activ ities Component 1: Improve healt SZ-MOH-234158-GO-RFB / S h service delivery to increas Single Stage - One E upply and delivery of comput IBRD / 91260 Post Request for Bids Open - National 990,000.00 976,081.22 Completed 2021-05-18 2021-05-19 2021-05-23 2021-05-20 2021-07-04 2021-07-28 2021-08-03 2021-08-09 2021-09-07 2021-10-08 2022-03-06 2021-12-18 e the coverage and quality o nvelope ers and IT Equipment f health services to build hu man capita l Component 3. Strengthen th SZ-MOH-254277-GO-RFQ / A e MOH’s stewardship capacit Request for Quota Single Stage - One E dditional Office Equipment fo IBRD / 91260 Post Limited 5,000.00 6,255.63 Completed 2021-09-27 2021-09-28 2021-11-22 2021-11-24 2022-05-21 2022-02-16 y to manage essential healt tions nvelope r PIU h and nutrition services and project activ ities Component 1: Improve healt SZ-MOH-254276-GO-RFQ / P h service delivery to increas Request for Quota Single Stage - One E rocurement of 4x4 Double Ca IBRD / 91260 Post Limited 48,000.00 50,584.96 Signed 2021-09-29 2021-09-28 2021-11-24 2021-11-30 2022-05-23 e the coverage and quality o tions nvelope bin Vehicle f health services to build hu man capita l Component 1: Improve healt SZ-MOH-259788-GO-RFB / W h service delivery to increas Single Stage - One E ater, Sanitation and Hygiene IBRD / 91260 Post Request for Bids Open - National 41,835.00 10,458.24 Completed 2021-10-29 2021-10-29 2021-11-03 2021-11-03 2021-12-15 2021-12-15 2022-01-14 2022-02-04 2022-02-18 2022-05-29 2022-08-17 2022-06-24 e the coverage and quality o nvelope Goods (WASH) f health services to build hu man capita l SZ-MOH-262229-GO-RFQ / P Component 1: Improve healt rinting of Chronic Care Files; h service delivery to increas Request for Quota Single Stage - One E IBRD / 91260 Post Limited 15,593.00 26,139.03 Completed 2021-11-16 2021-11-11 2022-01-11 2022-02-26 2022-07-10 2022-04-08 LMIS Tool; Patient Health Car e the coverage and quality o tions nvelope d and Primary Health Care g f health services to build hu uidelines man capita l SZ-MOH-276478-GO-RFQ / F Component 2. Increase com Request for Quota Single Stage - One E acility Tablets; Table Stands IBRD / 91260 munity demand for RMNCAH Post Limited 18,531.00 1,449.51 Signed 2022-02-14 2022-02-15 2022-04-11 2022-04-23 2022-10-08 tions nvelope and Cell Phones , nutrition and NCD services Component 1: Improve healt SZ-MOH-276483-GO-DIR / Mi h service delivery to increas IBRD / 91260 Post Direct Selection Direct 292,634.00 222,663.77 Signed 2022-02-11 2022-02-09 2022-02-16 2022-02-25 2022-03-23 2022-06-25 2022-09-19 cronutrients e the coverage and quality o f health services to build hu man capita l Component 1: Improve healt SZ-MOH-293047-GO-RFQ / P h service delivery to increas Request for Quota Single Stage - One E rocurement of 4x4 Double Ca IBRD / 91260 Post Limited 60,000.00 41,212.44 Signed 2022-05-08 2022-05-05 2022-07-03 2022-06-30 2022-12-30 e the coverage and quality o tions nvelope bin Vehicle f health services to build hu man capita l Component 1: Improve healt SZ-MOH-295780-GO-RFB / E h service delivery to increas Single Stage - One E quipment for Last-mile Sites IBRD / 91260 Post Request for Bids Open - National 120,000.00 0.00 Signed 2022-05-25 2022-06-06 2022-05-30 2022-06-06 2022-07-11 2022-07-08 2022-08-10 2022-08-17 2022-09-14 2023-03-13 e the coverage and quality o nvelope Connectivity f health services to build hu man capita l Component 1: Improve healt SZ-MOH-299927-GO-RFQ / P h service delivery to increas Request for Quota Single Stage - One E rocurement of Oxytocin Injec IBRD / 91260 Post Limited 7,950.00 0.00 Canceled 2022-06-25 2022-06-23 2022-08-20 2023-02-16 e the coverage and quality o tions nvelope tion f health services to build hu man capita l Component 3. Strengthen th SZ-MOH-288513-GO-RFQ / P e MOH’s stewardship capacit Request for Quota Single Stage - One E IBRD / 91260 Post Limited 2,260.00 0.00 Canceled 2022-04-13 2022-04-08 2022-06-08 2022-12-05 rocurement of Printer y to manage essential healt tions nvelope h and nutrition services and project activ ities Component 2. Increase com SZ-MOH-314787-GO-RFQ / P Request for Quota Single Stage - One E IBRD / 91260 munity demand for RMNCAH Post Limited 6,847.00 0.00 Signed 2022-09-18 2022-09-09 2022-11-13 2023-05-12 rocurement of cellphones tions nvelope , nutrition and NCD services Page 1 Component 2. Increase com SZ-MOH-314789-GO-RFQ / B Request for Quota Single Stage - One E IBRD / 91260 munity demand for RMNCAH Post Limited 1,200.00 0.00 Signed 2022-09-18 2022-09-09 2022-11-13 2023-05-12 randing of SAM Champions tions nvelope , nutrition and NCD services Component 2. Increase com SZ-MOH-319159-GO-RFQ / F Request for Quota Single Stage - One E IBRD / 91260 munity demand for RMNCAH Post Limited 8,000.00 0.00 Completed 2022-10-11 2022-10-05 2022-12-06 2023-06-04 acility Tablet Stand tions nvelope , nutrition and NCD services Component 1: Improve healt SZ-MOH-327802-GO-RFQ / In h service delivery to increas Request for Quota Single Stage - One E fantometer and Weighing Sc IBRD / 91260 Post Limited 101,450.00 0.00 Signed 2022-11-30 2022-11-25 2023-01-25 2023-07-24 e the coverage and quality o tions nvelope ales f health services to build hu man capita l Component 1: Improve healt SZ-MOH-327825-GO-RFQ / U h service delivery to increas Request for Quota Single Stage - One E IBRD / 91260 Post Limited 62,500.00 0.00 Completed 2022-11-30 2022-11-25 2023-01-25 2023-07-24 nder 5 Card e the coverage and quality o tions nvelope f health services to build hu man capita l Component 3. Strengthen th SZ-MOH-327832-GO-RFQ / R e MOH’s stewardship capacit Request for Quota Single Stage - One E IBRD / 91260 Post Limited 10,200.00 0.00 Canceled 2022-11-30 2022-11-25 2023-01-25 2023-07-24 eference Material y to manage essential healt tions nvelope h and nutrition services and project activ ities Component 3. Strengthen th SZ-MOH-336745-GO-RFQ / L e MOH’s stewardship capacit Request for Quota Single Stage - One E IBRD / 91260 Post Limited 2,260.00 0.00 Completed 2023-01-25 2023-01-23 2023-03-22 2023-09-18 aser Printer y to manage essential healt tions nvelope h and nutrition services and project activ ities Component 1: Improve healt SZ-MOH-364836-GO-DIR / Mi h service delivery to increas Direct - Internation Under Imple IBRD / 91260 Post Direct Selection 252,462.00 0.00 2023-06-07 2023-06-14 2023-06-12 2023-06-26 2023-07-17 2024-01-13 cronutrients Supplements e the coverage and quality o al mentation f health services to build hu man capita l NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 2. Increase com SZ-MOH-276491-NC-RFQ / M Request for Quota Single Stage - One E IBRD / 91260 munity demand for RMNCAH Post Limited 1,168.00 3,560.41 Completed 2022-02-14 2022-02-15 2022-04-11 2022-05-07 2022-10-08 2022-07-28 ural Wall Painting tions nvelope , nutrition and NCD services Component 2. Increase com SZ-MOH-276498-NC-RFQ / Br Request for Quota Single Stage - One E IBRD / 91260 munity demand for RMNCAH Post Limited 600.00 0.00 Canceled 2022-02-14 2022-04-11 2022-10-08 anding of SAM Champions tions nvelope , nutrition and NCD services SZ-MOH-276507-NC-RFQ / Pr Component 2. Increase com Request for Quota Single Stage - One E inting of Job Aids (Booklets) B IBRD / 91260 munity demand for RMNCAH Post Limited 50,000.00 18,041.22 Completed 2022-02-14 2022-02-15 2022-04-11 2022-04-15 2022-10-08 2022-06-08 tions nvelope uild capacity of CHV/ RHM pr , nutrition and NCD services ogram Component 3. Strengthen th SZ-MOH-279345-NC-DIR / M e MOH’s stewardship capacit edicines and Regulatory Unit IBRD / 91260 Post Direct Selection Direct 1,200.00 0.00 Canceled 2022-02-22 2022-02-22 2022-02-27 2022-03-15 2022-04-03 2022-09-30 y to manage essential healt Reference Material h and nutrition services and project activ ities Component 2. Increase com SZ-MOH-336751-NC-RFQ / M Request for Quota Single Stage - One E IBRD / 91260 munity demand for RMNCAH Post Limited 1,230.00 0.00 Signed 2023-01-25 2023-01-20 2023-03-22 2023-09-18 ural Painting tions nvelope , nutrition and NCD services Component 2. Increase com SZ-MOH-336757-NC-RFQ / Si Request for Quota Single Stage - One E IBRD / 91260 munity demand for RMNCAH Post Limited 1,401.00 0.00 Signed 2023-01-25 2023-01-20 2023-03-22 2023-09-18 te Visibility Signage tions nvelope , nutrition and NCD services Component 2. Increase com SZ-MOH-345026-NC-RFQ / Jo Request for Quota Single Stage - One E Under Imple IBRD / 91260 munity demand for RMNCAH Post Limited 50,000.00 0.00 2023-03-05 2023-02-24 2023-04-30 2023-10-27 b Aids tions nvelope mentation , nutrition and NCD services Component 1: Improve healt SZ-MOH-346824-NC-RFQ / Pr h service delivery to increas Request for Quota Single Stage - One E Under Imple inting of Nutrition and Cancer IBRD / 91260 Post Limited 5,000.00 0.00 2023-03-13 2023-03-08 2023-05-08 2023-11-04 e the coverage and quality o tions nvelope mentation Guidelines f health services to build hu man capita l Component 3. Strengthen th SZ-MOH-357224-NC-RFQ / In e MOH’s stewardship capacit Request for Quota Single Stage - One E Under Imple ternet Connection for Medici IBRD / 91260 Post Limited 10,155.00 0.00 2023-04-25 2023-04-20 2023-06-20 2023-12-17 y to manage essential healt tions nvelope mentation nes Regulatory Unit h and nutrition services and project activ ities Component 3. Strengthen th SZ-MOH-364841-NC-RFQ / Fi e MOH’s stewardship capacit Request for Quota Single Stage - One E Under Imple IBRD / 91260 Post Limited 30,000.00 0.00 2023-06-11 2023-06-07 2023-08-06 2024-02-02 nancial Management System y to manage essential healt tions nvelope mentation h and nutrition services and project activ ities Component 1: Improve healt SZ-MOH-369643-NC-RFQ / Pr h service delivery to increas Request for Quota Single Stage - One E Pending Impl inting of Registers and Recor IBRD / 91260 Post Limited 15,000.00 0.00 2023-07-09 2023-09-03 2024-03-01 e the coverage and quality o tions nvelope ementation d Card Packs for NCD f health services to build hu man capita l CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 1: Improve healt SZ-MOH-229232-CS-CQS / E h service delivery to increas Consultant Qualifi nvironmental and Social man IBRD / 91260 Post Open - National 20,000.00 21,105.71 Signed 2021-04-14 2021-04-15 2021-05-05 2021-04-16 2021-06-18 2021-05-17 2021-07-18 2021-06-07 2021-08-22 2021-06-16 2022-02-18 e the coverage and quality o cation Selection agement plan Consultancy f health services to build hu man capita l Component 3. Strengthen th SZ-MOH-229365-CS-INDV / C e MOH’s stewardship capacit Consultant Qualifi Open - Internationa onsultancy for Procurement S IBRD / 91260 Post 100,000.00 127,200.00 Signed 2021-04-16 2021-04-28 2021-05-07 2021-05-04 2021-06-20 2021-06-17 2021-07-20 2021-08-06 2021-08-24 2021-09-14 2022-02-20 y to manage essential healt cation Selection l trategy h and nutrition services and project activ ities Component 1: Improve healt SZ-MOH-239240-CS-QCBS / h service delivery to increas Quality And Cost- Open - Internationa Consultancy Services for Qua IBRD / 91260 Post 400,000.00 0.00 Canceled 2021-07-20 2021-07-21 2021-08-10 2021-07-22 2021-09-23 2021-08-31 2021-10-21 2021-11-20 2021-12-25 2022-01-29 2023-01-29 e the coverage and quality o Based Selection l lity of Care f health services to build hu man capita l Page 2 SZ-MOH-245202-CS-CQS / Bi Component 1: Improve healt omed equipment assessment h service delivery to increas Consultant Qualifi IBRD / 91260 Post Open - National 100,000.00 130,985.00 Signed 2021-07-27 2021-07-27 2021-08-17 2021-08-18 2021-09-30 2021-09-17 2021-10-30 2022-03-23 2021-12-04 2022-03-29 2022-06-02 and production of strategy pl e the coverage and quality o cation Selection an f health services to build hu man capita l SZ-MOH-245539-CS-CQS / T Component 3. Strengthen th echnical Study for the Rehabi e MOH’s stewardship capacit Consultant Qualifi Open - Internationa IBRD / 91260 Post 100,000.00 128,960.00 Completed 2021-07-29 2021-07-29 2021-08-19 2021-08-18 2021-10-02 2021-11-04 2021-11-01 2022-02-21 2021-12-06 2022-03-04 2022-06-04 litation of Sanitation Systems y to manage essential healt cation Selection l at two Health Facilities h and nutrition services and project activ ities Component 1: Improve healt SZ-MOH-261042-CS-QCBS / h service delivery to increas Quality And Cost- Open - Internationa IBRD / 91260 Post 400,000.00 374,735.00 Signed 2021-11-04 2021-11-05 2021-11-25 2021-11-08 2022-01-08 2022-01-19 2022-02-05 2022-03-22 2022-03-07 2022-03-22 2022-04-11 2022-06-20 2022-05-16 2022-06-30 2023-05-16 Quality of Care Consultancy e the coverage and quality o Based Selection l f health services to build hu man capita l SZ-MOH-276464-CS-CQS / C Component 1: Improve healt onsultant to Support Establis h service delivery to increas Consultant Qualifi IBRD / 91260 Post Open - National 150,000.00 0.00 Completed 2022-02-11 2022-02-14 2022-03-04 2022-04-13 2022-04-17 2022-06-08 2022-05-17 2022-09-28 2022-06-21 2022-12-18 hment of Eswatini Midwives e the coverage and quality o cation Selection Community of Practice Platfo f health services to build hu rm man capita l SZ-MOH-278123-CS-CQS / T Component 1: Improve healt echnical Assistance to train E h service delivery to increas Consultant Qualifi IBRD / 91260 Post Open - National 20,000.00 0.00 Canceled 2022-02-11 2022-02-14 2022-03-04 2022-04-17 2022-05-17 2022-06-21 2022-12-18 nvironmental Health Officers e the coverage and quality o cation Selection on Following Management Sy f health services to build hu stems Standards man capita l SZ-MOH-276471-CS-QCBS / Component 1: Improve healt Technical Assistance for a Co h service delivery to increas Quality And Cost- Open - Internationa nsulting Firm to provide a Ne IBRD / 91260 e the coverage and quality o Post 400,000.00 0.00 Canceled 2022-02-08 2022-02-09 2022-03-01 2022-03-03 2022-04-14 2022-05-12 2022-06-11 2022-07-16 2022-08-20 2023-08-20 Based Selection l onatologist and Specialist NI f health services to build hu CU Nurses to provide on goin man capita l g trainings and mentorship SZ-MOH-292691-CS-CQS / C ONSULTANCY FIRM TO DESIG Component 1: Improve healt N AND DEVELOP DIGITAL APP h service delivery to increas Quality And Cost- Open - Internationa LICATIONS (INPATIENT, SURV IBRD / 91260 e the coverage and quality o Post 429,800.00 0.00 Canceled 2022-04-29 2022-04-29 2022-05-20 2022-05-09 2022-07-03 2022-06-28 2022-07-31 2022-08-23 2022-08-30 2022-08-23 2022-10-04 2022-11-08 2023-11-08 Based Selection l EILLANCE, MATERNAL AND N f health services to build hu EONATAL, MOM-CONNECT A man capita l ND COMMUNITY HEALTH DIGI TAL TOOL) SZ-MOH-324012-CS-CQS / C Component 3. Strengthen th onsultancy to Develop Block e MOH’s stewardship capacit Contracting at 2 Mission Hos Consultant Qualifi Open - Internationa Under Implement IBRD / 91260 y to manage essential healt Post 120,000.00 0.00 2022-11-02 2022-11-02 2022-11-23 2022-11-15 2023-01-06 2023-01-30 2023-02-05 2023-03-12 2023-09-08 pitals ( Technical Design, Sup cation Selection l ation h and nutrition services and port Policy Process, Negotiati project activ ities on, Contract Adjustment and Evaluation) SZ-MOH-313005-CS-CQS / T Component 1: Improve healt echnical Assistance for the tr h service delivery to increas Consultant Qualifi aining of environmental healt IBRD / 91260 e the coverage and quality o Post Limited 20,000.00 0.00 Canceled 2022-09-07 2022-09-07 2022-09-21 2022-11-25 2022-10-21 2022-11-25 2023-05-24 cation Selection h officers in environmental h f health services to build hu ealth and safety system stan man capita l dards SZ-MOH-340790-CS-QCBS / Hire a consultant to perform Component 1: Improve healt background research and de h service delivery to increas sign the provider digital decis Quality And Cost- Open - Internationa Under Implement IBRD / 91260 e the coverage and quality o Post 429,800.00 0.00 2023-02-10 2023-02-08 2023-03-03 2023-04-16 2023-02-13 2023-05-14 2023-04-14 2023-06-13 2023-04-14 2023-07-18 2023-08-22 2024-08-21 ion support tools as well as u Based Selection l ation f health services to build hu ser experience workshops for man capita l field testing and engagement s with professional bodies an d ministries SZ-MOH-365373-CS-QCBS / Consultancy to Conduct Orga Component 1: Improve healt nizational Assessment of the h service delivery to increas Central Medical Stores and to Quality And Cost- Open - Internationa Under Implement IBRD / 91260 e the coverage and quality o Post 400,000.00 0.00 2023-06-09 2023-06-21 2023-06-30 2023-06-27 2023-08-13 2023-09-10 2023-10-10 2023-11-14 2023-12-19 2024-12-18 Strengthen its Capacity to De Based Selection l ation f health services to build hu liver on its mandate includin man capita l g Procurement, Warehousing and Distribution of Health Su pplies. INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 1: Improve healt SZ-MOH-215198-CS-INDV / H h service delivery to increas Individual Consult IBRD / 91260 Post Open 90,000.00 0.00 Canceled 2021-01-20 2020-06-30 2021-03-10 2021-03-31 2021-05-05 2021-11-01 uman Capital Liaison e the coverage and quality o ant Selection f health services to build hu man capita l Component 1: Improve healt SZ-MOH-223867-CS-INDV / H h service delivery to increas Individual Consult IBRD / 91260 Post Open 90,000.00 103,040.00 Signed 2021-03-09 2021-03-10 2021-04-27 2021-02-09 2021-05-18 2021-03-01 2021-06-22 2021-03-02 2021-12-19 iring of Project Engineer e the coverage and quality o ant Selection f health services to build hu man capita l SZ-MOH-225070-CS-INDV / R Component 1: Improve healt E-ADVERTISEMENT FOR HU h service delivery to increas Individual Consult IBRD / 91260 Post Open 90,000.00 2,426.09 Terminated 2021-03-19 2021-03-18 2021-05-07 2021-04-28 2021-05-28 2021-08-31 2021-07-02 2021-06-11 2021-12-29 MAN CAPITAL LIAISON OFFIC e the coverage and quality o ant Selection ER f health services to build hu man capita l SZ-MOH-228097-CS-INDV / E Component 1: Improve healt nvironmental and Social imp h service delivery to increas Individual Consult IBRD / 91260 Post Open 20,000.00 0.00 Canceled 2021-04-12 2021-04-08 2021-05-31 2021-06-21 2021-07-26 2022-01-22 act assessment for Central M e the coverage and quality o ant Selection edical Stores operation centr f health services to build hu e man capita l Component 1: Improve healt SZ-MOH-234589-CS-INDV / C h service delivery to increas Individual Consult IBRD / 91260 Post Open 255,000.00 5,877.62 Terminated 2021-05-17 2021-05-17 2021-07-05 2021-07-30 2021-07-26 2021-08-31 2021-08-30 2022-01-21 2022-02-26 linical Technical Advisor e the coverage and quality o ant Selection f health services to build hu man capita l SZ-MOH-235046-CS-INDV / R Component 2. Increase com Individual Consult eginal Health Management P IBRD / 91260 munity demand for RMNCAH Post Open 180,000.00 180,000.00 Signed 2021-05-18 2021-06-11 2021-07-06 2021-09-21 2021-07-27 2022-01-27 2021-08-31 2022-02-10 2022-02-27 ant Selection rogramme Advisor , nutrition and NCD services Component 3. Strengthen th SZ-MOH-244630-CS-INDV / H e MOH’s stewardship capacit Individual Consult ealth Care waste manageme IBRD / 91260 Post Open 50,000.00 29,567.33 Completed 2021-07-21 2021-07-20 2021-09-08 2021-09-16 2021-09-29 2021-11-12 2021-11-03 2021-12-05 2022-05-02 2022-08-17 y to manage essential healt ant Selection nt Strategic Plan h and nutrition services and project activ ities Component 3. Strengthen th SZ-MOH-248522-CS-INDV / N e MOH’s stewardship capacit Individual Consult utrition Strategy and costed IBRD / 91260 Post Open 90,000.00 0.00 Canceled 2021-08-19 2021-08-19 2021-10-07 2021-10-28 2021-12-02 2022-05-31 y to manage essential healt ant Selection action plan h and nutrition services and project activ ities Page 3 Component 1: Improve healt SZ-MOH-250073-CS-INDV / N h service delivery to increas Individual Consult CD Monitoring & Evaluation A IBRD / 91260 Post Open 84,000.00 82,766.78 Signed 2021-08-26 2021-08-26 2021-10-14 2021-11-10 2021-11-04 2021-12-07 2021-12-09 2021-12-16 2022-06-07 e the coverage and quality o ant Selection nalyst f health services to build hu man capita l Component 1: Improve healt SZ-MOH-250075-CS-INDV / N h service delivery to increas Individual Consult IBRD / 91260 Post Open 84,000.00 0.00 Canceled 2021-08-26 2021-08-26 2021-10-14 2021-11-04 2021-12-09 2022-06-07 CD Supply Chain Analyst e the coverage and quality o ant Selection f health services to build hu man capita l Component 1: Improve healt SZ-MOH-248551-CS-INDV / D h service delivery to increas Individual Consult IBRD / 91260 Post Open 39,600.00 0.00 Canceled 2021-08-23 2021-08-26 2021-10-11 2021-11-01 2021-12-06 2022-06-04 atabase Administrator e the coverage and quality o ant Selection f health services to build hu man capita l Component 1: Improve healt SZ-MOH-248554-CS-INDV / N h service delivery to increas Individual Consult IBRD / 91260 Post Open 53,484.00 0.00 Canceled 2021-08-24 2021-08-26 2021-10-12 2021-11-02 2021-12-07 2022-06-05 etwork Engineer e the coverage and quality o ant Selection f health services to build hu man capita l Component 1: Improve healt SZ-MOH-248540-CS-INDV / H h service delivery to increas Individual Consult IBRD / 91260 Post Open 45,000.00 0.00 Canceled 2021-08-19 2021-09-03 2021-10-07 2021-10-28 2021-12-02 2022-05-31 MIS Analyst e the coverage and quality o ant Selection f health services to build hu man capita l SZ-MOH-275538-CS-INDV / T Component 1: Improve healt echnical Assistance to condu h service delivery to increas Individual Consult ct a comprehensive Gap Anal IBRD / 91260 e the coverage and quality o Post Open 13,200.00 12,613.59 Completed 2022-02-08 2022-02-09 2022-03-29 2022-04-27 2022-04-19 2022-05-23 2022-05-24 2022-06-04 2022-11-20 ant Selection ysis for the Environmental He f health services to build hu alth and Infection Prevention man capita l Control Standards Component 1: Improve healt SZ-MOH-234871-CS-INDV / N h service delivery to increas Individual Consult CD Decentralization Coordina IBRD / 91260 Post Open 225,000.00 0.00 Canceled 2021-05-18 2021-05-18 2021-07-06 2021-07-30 2021-07-27 2021-08-31 2022-02-27 e the coverage and quality o ant Selection tor f health services to build hu man capita l Component 3. Strengthen th SZ-MOH-279819-CS-INDV / T e MOH’s stewardship capacit Individual Consult echnical Assistance - Progra IBRD / 91260 Post Open 110,700.00 97,102.48 Signed 2022-02-22 2022-03-03 2022-04-12 2022-05-20 2022-05-03 2022-06-06 2022-06-07 2022-06-14 2022-12-04 y to manage essential healt ant Selection m Officer h and nutrition services and project activ ities Component 1: Improve healt SZ-MOH-282197-CS-INDV / H h service delivery to increas Individual Consult IBRD / 91260 Post Open 45,000.00 52,221.45 Signed 2022-03-15 2022-03-14 2022-05-03 2022-06-08 2022-05-24 2022-06-14 2022-06-28 2022-06-22 2022-12-25 MIS Analyst e the coverage and quality o ant Selection f health services to build hu man capita l Component 1: Improve healt SZ-MOH-282199-CS-INDV / D h service delivery to increas Individual Consult IBRD / 91260 Post Open 39,600.00 38,484.51 Signed 2022-03-15 2022-03-14 2022-05-03 2022-06-08 2022-05-24 2022-06-14 2022-06-28 2022-06-18 2022-12-25 atabase Administrator e the coverage and quality o ant Selection f health services to build hu man capita l Component 1: Improve healt SZ-MOH-282200-CS-INDV / N h service delivery to increas Individual Consult IBRD / 91260 Post Open 53,484.00 52,972.80 Signed 2022-03-15 2022-03-14 2022-05-03 2022-06-07 2022-05-24 2022-06-14 2022-06-28 2022-06-18 2022-12-25 etwork Engineer e the coverage and quality o ant Selection f health services to build hu man capita l Component 1: Improve healt SZ-MOH-282202-CS-INDV / h service delivery to increas Individual Consult IBRD / 91260 Post Open 44,862.00 24,786.40 Signed 2022-03-15 2022-03-14 2022-05-03 2022-05-24 2022-05-24 2022-06-13 2022-06-28 2022-06-21 2022-12-25 Maintenance Technician e the coverage and quality o ant Selection f health services to build hu man capita l Component 1: Improve healt SZ-MOH-285544-CS-INDV / D h service delivery to increas Individual Consult IBRD / 91260 Post Open 240,000.00 91,649.88 Signed 2022-03-23 2022-04-06 2022-05-11 2022-08-24 2022-06-01 2022-08-30 2022-07-06 2022-09-13 2023-01-02 ecentralization Coordinator e the coverage and quality o ant Selection f health services to build hu man capita l Component 1: Improve healt SZ-MOH-285545-CS-INDV / N h service delivery to increas Individual Consult IBRD / 91260 Prior Open 432,000.00 0.00 Signed 2022-04-08 2022-04-13 2022-05-27 2022-08-30 2022-06-17 2022-11-16 2022-07-22 2023-03-20 2023-01-18 CD Technical Advisor e the coverage and quality o ant Selection f health services to build hu man capita l Component 3. Strengthen th SZ-MOH-261040-CS-INDV / N e MOH’s stewardship capacit Individual Consult utrition Strategy and costed IBRD / 91260 Post Open 90,000.00 0.00 Canceled 2021-11-04 2021-11-04 2021-12-23 2022-01-24 2022-01-13 2022-02-17 2022-08-16 y to manage essential healt ant Selection action plan h and nutrition services and project activ ities Component 1: Improve healt SZ-MOH-292698-CS-INDV / N h service delivery to increas Individual Consult CD Monitoring and Evaluatio IBRD / 91260 Post Open 84,000.00 74,832.96 Signed 2022-04-29 2022-04-29 2022-06-17 2022-07-11 2022-07-08 2022-08-17 2022-08-12 2022-09-09 2023-02-08 e the coverage and quality o ant Selection n Officer f health services to build hu man capita l SZ-MOH-293042-CS-INDV / T Component 3. Strengthen th A for Health Care Waste Man e MOH’s stewardship capacit Individual Consult IBRD / 91260 Post Open 30,000.00 21,672.92 Completed 2022-05-03 2022-05-04 2022-06-21 2022-08-16 2022-07-12 2022-08-23 2022-08-16 2022-09-04 2023-02-12 agement Regulations Draftin y to manage essential healt ant Selection g and Finalization h and nutrition services and project activ ities SZ-MOH-293044-CS-INDV / T Component 3. Strengthen th A for Feasibility Study for Ce e MOH’s stewardship capacit Individual Consult IBRD / 91260 Post Open 30,000.00 0.00 Signed 2022-05-03 2022-05-04 2022-06-21 2022-06-20 2022-07-12 2022-10-20 2022-08-16 2023-02-12 ntralized Health Care Waste y to manage essential healt ant Selection Management h and nutrition services and project activ ities SZ-MOH-295779-CS-INDV / C Component 2. Increase com onsultant to Develop RMNCA Individual Consult IBRD / 91260 munity demand for RMNCAH Post Open 10,000.00 0.00 Signed 2022-05-23 2022-05-23 2022-07-11 2022-07-27 2022-08-01 2022-11-18 2022-09-05 2023-03-04 H, Nutrition and NCD Social B ant Selection , nutrition and NCD services ehavior Change Communicati on (SBCC) SZ-MOH-301012-CS-INDV / L Component 3. Strengthen th eadership and Management e MOH’s stewardship capacit Individual Consult IBRD / 91260 Post Open 20,000.00 0.00 Signed 2022-06-28 2022-06-29 2022-08-16 2022-10-14 2022-09-06 2022-12-16 2022-10-11 2023-04-09 Training Needs Assessment f y to manage essential healt ant Selection or Ministry Health Manageme h and nutrition services and nt Team project activ ities SZ-MOH-301013-CS-INDV / C Component 1: Improve healt onsultant to Review the Baby h service delivery to increas Individual Consult Open - Internationa IBRD / 91260 Post 50,000.00 0.00 Signed 2022-08-04 2022-08-01 2022-09-22 2022-10-13 2022-10-13 2022-11-28 2022-11-17 2023-05-16 Friendly Hospital Initiative gu e the coverage and quality o ant Selection l idelines and training package f health services to build hu man capita l Component 3. Strengthen th SZ-MOH-306565-CS-INDV / C e MOH’s stewardship capacit Individual Consult onsultant in Human Resource IBRD / 91260 Post Open - National 30,000.00 0.00 Signed 2022-08-04 2022-08-01 2022-09-22 2022-10-13 2022-10-13 2022-12-05 2022-11-17 2023-05-16 y to manage essential healt ant Selection s Health Analyst h and nutrition services and project activ ities Component 1: Improve healt SZ-MOH-315911-CS-INDV / A h service delivery to increas Individual Consult Under Implement IBRD / 91260 Post Open - National 144,000.00 0.00 2022-09-19 2022-09-19 2022-11-07 2023-02-01 2022-11-28 2023-01-02 2023-07-01 ssistant HMIS Analyst e the coverage and quality o ant Selection ation f health services to build hu man capita l Page 4 Component 1: Improve healt SZ-MOH-316814-CS-INDV / F h service delivery to increas Individual Consult IBRD / 91260 Post Open - National 78,420.00 0.00 Signed 2022-09-22 2022-09-21 2022-11-10 2022-12-05 2022-12-01 2022-12-12 2023-01-05 2023-07-04 leet Management Officer e the coverage and quality o ant Selection f health services to build hu man capita l Component 3. Strengthen th SZ-MOH-316815-CS-INDV / C e MOH’s stewardship capacit Individual Consult onsultant to review staffing n IBRD / 91260 Post Open - National 20,000.00 0.00 Signed 2022-09-22 2022-09-21 2022-11-10 2023-01-31 2022-12-01 2023-03-17 2023-01-05 2023-07-04 y to manage essential healt ant Selection orms h and nutrition services and project activ ities SZ-MOH-324754-CS-INDV / C Component 3. Strengthen th onsultancy to Review Eswati e MOH’s stewardship capacit Individual Consult Open - Internationa Under Implement IBRD / 91260 Post 50,000.00 0.00 2022-11-08 2022-11-23 2022-12-27 2023-05-19 2023-01-17 2023-06-27 2023-02-21 2023-08-20 ni Medical and Dental Counci y to manage essential healt ant Selection l ation l Legal Framework h and nutrition services and project activ ities Component 3. Strengthen th SZ-MOH-314961-CS-INDV / C e MOH’s stewardship capacit Individual Consult onsultancy to develop a Nutri IBRD / 91260 Post Limited 87,000.00 0.00 Canceled 2022-09-14 2022-09-12 2022-09-19 2022-10-10 2022-11-14 2023-05-13 y to manage essential healt ant Selection tion Strategy h and nutrition services and project activ ities SZ-MOH-338817-CS-CDS / T Component 1: Improve healt echnical assistance (specialis h service delivery to increas Direct - Internation Under Implement IBRD / 91260 Post Direct Selection 396,000.00 0.00 2023-02-03 2023-02-02 2023-02-13 2023-02-16 2023-04-19 2023-10-16 t NICU nurses to provide on-g e the coverage and quality o al ation oing training and mentorship f health services to build hu ) man capita l Component 3. Strengthen th SZ-MOH-336761-CS-INDV / S e MOH’s stewardship capacit Individual Consult Under Implement IBRD / 91260 Post Open - National 80,000.00 0.00 2023-02-03 2023-02-02 2023-03-24 2023-06-16 2023-04-14 2023-05-19 2023-11-15 ID Program Technical Advisor y to manage essential healt ant Selection ation h and nutrition services and project activ ities Component 3. Strengthen th SZ-MOH-336764-CS-INDV / T e MOH’s stewardship capacit Individual Consult Open - Internationa Under Implement A to Develop Health Financin IBRD / 91260 Post 70,000.00 0.00 2023-02-03 2023-02-02 2023-03-24 2023-06-13 2023-04-14 2023-05-19 2023-11-15 y to manage essential healt ant Selection l ation g Strategy h and nutrition services and project activ ities SZ-MOH-342698-CS-INDV / T Component 3. Strengthen th echnical Assistance for Devel e MOH’s stewardship capacit Individual Consult Under Implement IBRD / 91260 Post Limited 85,600.00 0.00 2023-02-17 2023-02-15 2023-02-22 2023-05-22 2023-03-15 2023-04-19 2023-10-16 opment of Nutrition Strategy y to manage essential healt ant Selection ation and Costed Action Plan h and nutrition services and project activ ities SZ-MOH-356309-CS-INDV / T Component 1: Improve healt A to Design and Implement E h service delivery to increas Individual Consult Open - Internationa Under Implement IBRD / 91260 Post 50,000.00 0.00 2023-04-18 2023-04-13 2023-06-06 2023-06-27 2023-08-01 2024-01-28 fficient Referrals within Healt e the coverage and quality o ant Selection l ation h Facilities f health services to build hu man capita l Component 1: Improve healt SZ-MOH-359969-CS-INDV / E h service delivery to increas Individual Consult Under Implement ngage a consultant to train E IBRD / 91260 Post Direct - National 5,647.06 0.00 2023-05-17 2023-05-16 2023-05-27 2023-06-26 2023-06-17 2023-07-22 2024-01-18 e the coverage and quality o ant Selection ation nvironmental Health Officers f health services to build hu man capita l SZ-MOH-361954-CS-INDV / T Component 3. Strengthen th A to support the developmen e MOH’s stewardship capacit Individual Consult Open - Internationa Under Implement IBRD / 91260 Post 25,000.00 0.00 2023-05-22 2023-05-16 2023-07-10 2023-07-31 2023-09-04 2024-03-02 t of a Public Private Partnersh y to manage essential healt ant Selection l ation ip Guidelines for Health h and nutrition services and project activ ities Page 5 P175143 - Innovation Program for Smart Growth (PINCRI) PROCUREMENT Argentina : Innovation Program for Smart Growth (PINCRI) PLAN General Information Country: Argentina 2023-04-17 Bank’s Approval Date of the Original Procurement Plan: 2023-06-05 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P175143 GPN Date: 2023-04-03 Project Name: Innovation Program for Smart Growth (PINCRI) Loan / Credit No: IBRD / 94340 Ministry of Science, Technology and Productive Innovation Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual AR-MINCYT-357274-NC-RFB / Adecuación de espacio para i Foster innovation-led private Single Stage - One E Pending Impl IBRD / 94340 Post Request for Bids Open - National 1,700,000.00 0.00 2023-04-18 2023-04-19 2023-05-14 2023-05-17 2023-05-21 2023-08-19 nstalar y equipar una Tecnot sector growth nvelope ementation eca en el Parque Tecnópolis AR-MINCYT-361384-NC-RFQ / Servicio de adecuación de l Foster innovation-led private Request for Quota Single Stage - One E Pending Impl IBRD / 94340 Post Limited 46,000.00 0.00 2023-05-23 2023-07-18 2023-11-15 a plataforma de formación d sector growth tions nvelope ementation el programa TIP.AR CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual AR-MINCYT-354022-CS-INDV / Contratación de consultor p Promote entrepreneurship a ara conformar el equipo de A Individual Consult Under Implement IBRD / 94340 nd innovation financing ecos Post Open - National 27,000.00 0.00 2023-04-04 2023-04-17 2023-05-23 2023-06-13 2023-07-18 2024-07-17 sesoría Técnica y Legal (ATL) ant Selection ation ystems para la ejecución del compon ente de Capital de Riesgo - E CONOMISTA EXPERTO. AR-MINCYT-354026-CS-INDV / Contratación de consultor p Promote entrepreneurship a ara conformar el equipo de A Individual Consult Under Implement IBRD / 94340 nd innovation financing ecos Post Open - National 24,000.00 0.00 2023-04-04 2023-04-17 2023-05-23 2023-06-13 2023-07-18 2024-07-17 sesoría Técnica y Legal (ATL) ant Selection ation ystems para la ejecución del compon ente de Capital de Riesgo - E XPERTO LEGAL. AR-MINCYT-354031-CS-INDV / Contratación de consultor p Promote entrepreneurship a ara conformar el equipo de A Individual Consult Under Implement IBRD / 94340 nd innovation financing ecos Post Open - National 21,000.00 0.00 2023-04-04 2023-04-17 2023-05-23 2023-06-13 2023-07-18 2024-07-17 sesoría Técnica y Legal (ATL) ant Selection ation ystems para la ejecución del compon ente de Capital de Riesgo - E XPERTO AMBIENTALISTA. AR-MINCYT-354032-CS-INDV / Contratación de consultor p ara conformar el equipo de A Promote entrepreneurship a Individual Consult Under Implement sesoría Técnica y Legal (ATL) IBRD / 94340 nd innovation financing ecos Post Open - National 21,000.00 0.00 2023-04-04 2023-04-17 2023-05-23 2023-06-13 2023-07-18 2024-07-17 ant Selection ation para la ejecución del compon ystems ente de Capital de Riesgo - E XPERTO EN DESARROLLO TE CNOLÓGICO E INNOVACIÓN. AR-MINCYT-354034-CS-INDV / Contratación de consultor p ara conformar el equipo de A Promote entrepreneurship a Individual Consult Under Implement sesoría Técnica y Legal (ATL) IBRD / 94340 nd innovation financing ecos Post Open - National 10,500.00 0.00 2023-04-04 2023-04-17 2023-05-23 2023-06-13 2023-07-18 2024-07-17 ant Selection ation para la ejecución del compon ystems ente de Capital de Riesgo - P ROFESIONAL EXPERTO EN EV ALUACIÓN DE PROYECTOS (2 ). AR-MINCYT-354035-CS-INDV / Contratación de consultor p ara conformar el equipo de A Promote entrepreneurship a Individual Consult Under Implement sesoría Técnica y Legal (ATL) IBRD / 94340 nd innovation financing ecos Post Open - National 10,500.00 0.00 2023-04-04 2023-04-17 2023-05-23 2023-06-13 2023-07-18 2024-07-17 ant Selection ation para la ejecución del compon ystems ente de Capital de Riesgo - P ROFESIONAL EXPERTO EN EV ALUACIÓN DE PROYECTOS (1 ) Page 1 AGRO-CLIMATIC RESILIENCE IN SEMI -ARID LANDSCAPES (ACReSAL) PROJECT PROCUREMENT STRATEGY FOR DEVELOPMENT 1 PROJECT OVERVIEW Country: NIGERIA Full Project Name: AGRO-CLIMATIC RESILIENCE IN SEMI -ARID LANDSCAPES (ACReSAL) Total Finance ($): USD 700 MILLION Project Number: P175237 Summary of Project The Project Development Objective (PDO) is to increase the adoption of climate resilient landscape Development Objectives management practices and enhance livelihoods in targeted arid/semi-arid watersheds in Northern Nigeria. PROJECT COST COMPONENTS ESTMATE OBJECTIVES OF EACH (USD) COMPONENT Component A: 299.6m This component aims to prepare and Desertification Control implement investments to arrest and Landscape desertification and improve the Management sustainable productivity of land in targeted watersheds (about 1,000,000 ha area of degraded and desert landscapes out of 4,000,000 (25%) Government program). Component B: 293.4m This component aims to support Community communities with improved capacity Livelihoods and and investments to improve Resilience sustainable livelihoods. Component C: 107.6m This component aims to strengthen Institutional capacities of institutions at various levels (e.g., national, selected states) Strengthening and to modernize their work for the Project Management longer-term on integrated multi- sectoral planning, information management, and building systems for improving land and water management and sustainable agricultural productivity in northern Nigeria. Component D: 0m This will finance a Contingency Contingency Emergency Response Component Emergency Response (CERC) for landscape and community Components (CERC): resilience in response to extreme weather, land movement events and other emergencies. LIST OF PROCUREMENT ACTIVITIES The project is designed as framework project and therefore investments and the participating states (the major investments will be implemented by the participating states) are not fully known yet. In the table below are the activities that already known, and implementation can commence immediately. The PPSD will be updated during implementation as the investments and participating states become more defined. These investments include gully erosion control, rehabilitation of irrigation and dams. S/N ACTIVITIES COST CUMMULATIVE % of ESTIMATE COST TOTAL (USD) ESTIMATE COST (USD) ESTIMATE 1 Technical assistance for 10,000,000 10,000,000 28% landscape restoration services 2 Extension services technical 9,900,000 19,900,000 57% assistance 3 Implementation support 9,500,000 29,400,000 84% consultancy 4 Long-term framework and 2,500,000 31,900,000 91% policy support 5 Development of strategic 1,600,000 33,500,000 95% catchment plan 4 Monitoring Information 600,000 34,100,000 97% System (MIS) and maintenances 5 Others ICT Equipment and 400,000 34,500,000 98% connectivity, cloud services, others general services Desktops & Laptops 300,000 34,800,000 99% Data collection and analysis at 168,000 34,968,000 100% State/federal Level Production of Manuals (PIM ) 90,000 35,058,000 100% Design and hosting of 56,000 35,114,000 100% interactive website TOTAL 35,114,000 Strategic Assessment of Operating Context and Borrower Capability Operational Context Nigeria experiences a diverse climate that ranges from arid in the north to tropical in much of the country and is listed among the countries most exposed to climate risks. The country faces a high water-scarcity hazard level, with droughts expected to occur on average every five years, with potential increased frequency due to climate change. Focusing on drylands management, ACReSAL will be implemented in the states of northern Nigeria. The agricultural sector is the major economic driver of northern Nigeria. Many projects and initiatives have been undertaken in northern Nigeria over the past decades to combat the growing crisis of desertification. The FGN is thus increasingly moving toward an integrated and multisectoral approach to address the challenges of dryland management. (a) Governance Aspects: There are security challenges in almost all the states in the northern Nigeria where the project will be implemented. The Government of Nigeria is making some progress in addressing these security challenges. The security situation may reduce the interest of major players, especially for Component A to participate in the procurement process and those that choose to participate may add a premium to the bid prices to take of the additional security arrangement they want to put in place during contract execution in case of an award. (b) Economic Aspects: Nigeria has just come out of an economic recession because of CIVID 19 pandemic and a fall in crude oil price in the world market. The country is contending with high inflation and exchange rate volatility. The high inflation and exchange rate volatility has made the prices of the major construction materials such as iron rods and cement to be volatile. Substantial proportion of the Component consist of civil works with locally available inputs (labour and materials). The effect of the exchange volatility will be minimal since bidders expecting to incur expenditures in other currencies for inputs to the Works supplied from outside the country can quote for such inputs in up to three different foreign currencies in their bids. Serious bottleneck exists in the main seaport where goods to be imported from abroad will be discharged. This has led to delay in the custom clearance of good from the port with the resulting demurrage payment and delay in contract execution. The government is working on policy that will remove the bottlenecks. (c) Sustainability Aspects: The government environmental and social standards requires that Environmental and Social Impact Assessment be carried on all major works project before the commencement of such works. ESIA will apply to this project and will be reflected in the solicitation documents and contracts for civil works under the project. (d) Technological Aspects: Kaduna, Niger, Kogi, Jigawa, Borno, Kano and Gombe States that will likely participate in the project have an e-Procurement system which is being used in some of the MDAs. Sokoto State is in the final stages of their e- Procurement implementation. The systems so deployed will be used for procurement under the project. This will further improve value for money, transparency, economy, efficiency, effectiveness, integrity, and openness of procurement process under the project. The country is covered substantially by GSM, part of which is through extensive fiber optic cabling leading to increased networking and internet availability. The availability of reasonable internet access will facilitate the use of the World Bank Systematic Tracking of Exchanges in Procurement (STEP) which is mandatory requirement in the processing all procurement activities under the World Bank Procurement Regulations. Key Conclusions: The security challenges in the country especially in the northern states that will participate in the project may reduce the participation of foreign firms and firms from other parts of the in the procurement process for the project. The current high inflation and exchange rate volatility in the country will affect the costing of the various procurement packages in the project. The use of eProcurement for by the participating states and the FPMU will improve value for money, transparency, economy, efficiency, effectiveness, integrity, and openness of procurement process under the project Assessment of Borrower previous Experience, Capability and Project Implementation Unit (PIU) The project will be implemented using the existing NEWMAP PMUs at both Federal and State levels that are implementing NEWMAP and the NEWMAP AF that will close on June 30, 2022. The implementation arrangement is similar to that of NEWMAP. Each state will be responsible for the procurement of its own activities including contract management and administration. The FPMU and the states that are implementing NEWMAP have experience in World Bank Procurement Regulations. The procurement officers have received sufficient training in procurement under World Bank funded project. The gaps that were observed in the implementation of NEWMAP especially in contract management will be addressed under ACReSAL. Training will be provided on contract management, application of price adjustment, contract monitoring and supervision as soon as the project is effective. Market Analysis The summary of the procurement activities under the project are as follows • Civil works: o gully erosion control, o flood and sedimentation control, o construction of firebreaks, o rehabilitation and construction of small dams, o small scale irrigation infrastructure, o small buildings There are several players both national and international in the marketplace for these activities. International open competitive procurement approach will be used for high value, high risk gully erosion control and construction of dams and firebreaks. The other low value, low risk procurement will follow national open competition or limited competition as may be appropriate. • Goods: o fire control equipment, o vehicles, o farm inputs (seeds, fertilizers), o post-production equipment, o computers, furniture They are locally available and be supplied by several suppliers and the procurement approach will be national open/limited completion as may be appropriate. The approach for the procurement of farm inputs (seeds, fertilizer) will limited competition between the well-known producers/suppliers of these goods. • Consulting services: The major consulting services includes engineering design and supervision of the major civil works like gully erosion control and rehabilitation of dams. The firms that offer this service are available in the local and international markets. Due to the criticality of this consulting assignment to the overall delivery of the major works contracts, the procurement will be designed to attract best consulting firms to express interest in this assignment. Procurement Risk Analysis Market Risk Description of Risk Owner /Contract Description Mitigation Title Description Construction of Designs may no A consultant will be State PMU and shovel ready longer be valid by the hired to update the World Bank gully erosion contracts during design before the control site contract execution commencement of the procurement process Expansion of the Provisions for State PMUs gullies between physical bidding and contract contingencies will signature made in the signed contract. Expansion of gullies Proper drainage on Contractor during construction the site must be due to poor drainage maintained during resulting from construction and the construction of the Contractor shall be works held responsible for any flood damage to life and properties due to his work in this Contract. The Contractor shall allow in his rates, inter alia, for all costs to maintain or divert flow in drains, ditches, open channels and watercourses during construction and other drainage work. No claims for additional payment will be considered in this regard. Construction Poor supervision of supervision the works contracts consultancy Procurement of Delay in port All the necessary PMUs goods to be clearance documentation and imported from waivers will be outside the processed speedily country (delfino ploughs, tractors, etc) General (for all High inflation and Price adjustment to PMUs contracts) exchange rate applied to most even volatility if they duration is less than 18 months. Procurement Objective • To a minimum of 8 qualified consultants to participate in the selection process for the engineering design and supervision consultancy for the major works contracts. • To take advantage of the dry season for the construction contracts by aligning the commencement of the works with the dry season in the project areas. • Value for money and integrity in the procurement process using electronic procurement system. • To have not less than six qualified firms submit bids for the major works contracts. • Procurement Approach Options and Recommendation The following will be a draft zero of the procurement approach options and recommendations. This is because the major investments are not yet known. This section will be updated once the investments are finalized. • Contract and Estimated Cost: Landscape investments (many packages)– USD236 million • Procurement Approach Attribute Selected arrangement Justification Summary/Logic Specifications Conformance Details design for shovel- ready investments from NEWMAP are available. Engineering firm will be hired to provide detail designs for other investments. Sustainability No All the safeguard studies Requirements will be carried out separately and cost implications will be included in the bidding document. Contract Type Traditional Pricing and costing Schedule of mechanism Rates/Admeasurement Price Adjustments None/Percentage Form of Contract (Terms and Conditions) Selection Method Request for Bids (RFB) Selection Arrangement N/A Market Approach Open International/National Pre/Post Qualification Post Evaluation Selection Least Cost Based Method Selection (LCS) Evaluation of Costs Adjusted Bid Price Domestic Preference No Rated Criteria N/A • Contract and Estimated Cost: Development of strategic catchment plan – USD1,600,000 • Procurement Approach Attribute Selected arrangement Justification Summary/Logic Sustainability N/A Requirements Contract Type Traditional Pricing and costing Lump Sum mechanism Price Adjustments None Form of Contract (Terms N/A and Conditions) Selection Method Request for Proposals (RFP) Selection Arrangement N/A Market Approach Open International Pre/Post Qualification Pre-Qualification Evaluation Selection Quality Cost Based Method Selection (QCBS) Evaluation of Costs N/A Domestic Preference N/A Rated Criteria Mandatory • Contract and Estimated Cost: Long-term framework and policy support – USD2,500,000 • Procurement Approach Attribute Selected arrangement Justification Summary/Logic Sustainability N/A Requirements Contract Type Traditional Pricing and costing Time and Materials mechanism Price Adjustments ????? Form of Contract (Terms ????? and Conditions) Selection Method Request for Proposals (RFP) Selection Arrangement N/A Market Approach Open International, Two Envelopes Pre/Post Qualification Pre-Qualification Evaluation Selection Quality Cost Based Method Selection (QCBS) Evaluation of Costs Adjusted Bid Price Domestic Preference No Rated Criteria • Specific experience • Methodology and workplan • Qualification and experience of key experts • Contract and Estimated Cost: Implementation support consultancy – USD9,900,000 • Procurement Approach Attribute Selected arrangement Justification Summary/Logic Sustainability N/A Requirements Contract Type Traditional Pricing and costing Lump Sum mechanism Price Adjustments None Form of Contract (Terms N/A and Conditions) Selection Method Request for Proposals (RFP) Selection Arrangement N/A Market Approach Open International Pre/Post Qualification Pre-Qualification Evaluation Selection Quality Cost Based Method Selection (QCBS) Evaluation of Costs N/A Domestic Preference N/A Rated Criteria Mandatory • Contract and Estimated Cost: Development of strategic catchment plan – USD1,600,000 • Procurement Approach Attribute Selected arrangement Justification Summary/Logic Sustainability N/A Requirements Contract Type Traditional Pricing and costing Lump Sum mechanism Price Adjustments None Form of Contract (Terms and Conditions) Selection Method Request for Proposals (RFP) Selection Arrangement N/A Market Approach Open International, Two Envelopes Pre/Post Qualification Pre-Qualification Evaluation Selection Quality Cost Based Method Selection (QCBS) Evaluation of Costs Adjusted Bid Price Domestic Preference No Rated Criteria • Specific experience • Methodology and workplan • Qualification and experience of key experts Preferred arrangement for low value, low activities Contract Category Estimated cost Procurement Arrangement and Method Desktops & Goods 300,000 Open National Laptops Others ICT Goods 400,000 Open National Equipment and connectivity, cloud services, others general services Production of Goods 90,000 Limited RFQ Manuals (PIM Monitoring Consultancy 600,000 Open National Information System (MIS) and maintenances Design and hosting Consultancy 56,000 Limited CQS of interactive website Data collection and Consultancy 168,000 Limited CQS analysis at State/federal Level Summary of PPSD to be inform the Bank’s preparation of the PAD The project is designed as framework project and therefore investments and the participating states (the major investments will be implemented by the participating states) are not fully known yet. The security challenges in the country especially in the northern states that will participate in the project may reduce the participation of foreign firms and firms from other parts of the in the procurement process for the project. The current high inflation and exchange rate volatility in the country will affect the costing of the various procurement packages in the project. The use of eProcurement for by the participating states and the FPMU will improve value for money, transparency, economy, efficiency, effectiveness, integrity, and openness of procurement process under the project. The FPMU and the states that are implementing NEWMAP have experience in World Bank Procurement Regulations. The procurement officers have received sufficient training in procurement under World Bank funded project. The gaps that were observed in the implementation of NEWMAP especially in contract management will be addressed under ACReSAL. A sufficiently large numbers of firms are available locally and international for most of the procurement packages under the project, therefore competitive procurement can readily be used to achieved value for value during procurement implementation. The design of the gully erosion sites already cleared under NEWMAP that will be transferred to project will be updated prior to the launching of the procurement processes for the construction of such sites. The PPSD will be regularly updated as there are clear pictures on the participating states and the procurement activities that will be implemented by the states and the FPMU. Contract Estimat Bank Procurement Selecti Evaluati Title, ed Cost Oversig Approach/Competi on on Description US$ and ht tion Method Method and Risk Category Rating Implementati 9,500,00 Prior International SPD Rated on support0 (RFP) Criteria consultancy Substanti (VfM) al Long-term 2.500,00 Prior International SPD Rated framework 0, (RFP) Criteria and policy Substanti (VfM) support al Development 1,600,00 Prior International SPD Rated of strategic 0, (RFP) Criteria catchment Substanti (VfM) plan al Monitoring 600,000, Post International SPD Rated Information Moderate (RFP) Criteria System (MIS) (VfM) and maintenance s Others ICT 400,000, Post National RFB Lowest Equipment Moderate Evaluated and Cost connectivity, cloud services, others general services Desktops & 300,000, Post National RFB Lowest Laptops Low Evaluated Cost Data 168,000, Post National CQS Negotiati collection Moderate on and analysis at State/federal Level Production of 90,000, Post National RFQ Lowest Manuals Low Evaluated (PIM) Design and 56,000, Post National CQS Negotiati hosting of Moderate on interactive website PROCUREMENT Nigeria : Agro-Climatic Resilience in Semi-Arid Landscapes (ACReSAL) PLAN General Information Country: Nigeria 2022-11-21 Bank’s Approval Date of the Original Procurement Plan: 2023-06-06 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P175237 GPN Date: Project Name: Agro-Climatic Resilience in Semi-Arid Landscapes (ACReSAL) Loan / Credit No: IDA / 70150 Jigawa State ACReSAL Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Request for Quota JGS-ACRESAL/GO/22/017 / Of Component C: Institutional S Request for Quota Single Stage - One E Under Imple 2023-05-1 IDA / 70150 Post Limited tions (Non Bank-S 90,000.00 0.00 2023-01-28 2023-01-30 2023-02-11 fice Renovation trengthening and Project Ma tions nvelope mentation 2 PD) nagement JGS-ACRESAL/RFQ/01 / Const ruction of 5no. solar powere Request for Quota Component A: Dryland Mana Request for Quota Single Stage - One E 2023-09-0 d boreholes and fencing peri IDA / 70150 Post Limited tions (Non Bank-S 70,000.00 0.00 Canceled 2023-01-15 2023-03-12 gement tions nvelope 8 meter for community nursery PD) for selected agroforestry spe cies. NG-JIGAWA STATE ACRESAL- 338998-CW-RFB / Drilling of Request for Bids - 5no. Solar powered borehole Component A: Dryland Mana Single Stage - One E Small Works SPD Pending Imp 2024-01-2 s and fencing perimeter for c IDA / 70150 Post Request for Bids Open - National 410,000.00 0.00 2023-04-09 2023-04-14 2023-05-26 2023-06-25 2023-07-30 gement nvelope (1 envelope proce lementation 6 ommunity nursery for select ss) ed agroforestry species. At: ( Sule Tankarkar, Kanya Babba ,Kirri Kassama, Jahun and Ma jeri) NG-JIGAWA STATE ACRESAL- 364970-CW-RFQ / Establishm Request for Quota Component B: Community Cl Request for Quota Single Stage - One E Under Imple 2023-09-0 ent of 15 hecters of datepal IDA / 70150 Post Limited tions (Non Bank-S 150,000.00 0.00 2023-06-12 2023-06-29 imate Resilience tions nvelope mentation 7 m plantation at three senator PD) ial zone(Dutse, Hadejia & Gu mel). NG-JIGAWA STATE ACRESAL- Request for Quota 364953-CW-RFQ / establishm Component B: Community Cl Request for Quota Single Stage - One E Pending Imp 2023-07-0 IDA / 70150 Post Limited tions (Non Bank-S 120,000.00 0.00 2023-06-16 2023-07-01 ent of 15km sheltebelt at fro imate Resilience tions nvelope lementation 2 PD) nt line in 3 senotorial zone NG-JIGAWA STATE ACRESAL- Request for Quota Component B: Community Cl Request for Quota Single Stage - One E Pending Imp 2023-09-1 364963-CW-RFQ / Sand dune IDA / 70150 Post Limited tions (Non Bank-S 120,000.00 0.00 2023-06-17 2023-07-12 imate Resilience tions nvelope lementation 0 stabilization 20km at Jahun PD) and Miga LGAs GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual JGS-ACRESAL/GO/22/018 / S Component C: Institutional S Request for Quota Single Stage - One E Under Imple IDA / 70150 Post Limited 60,000.00 0.00 2023-01-28 2023-01-17 2023-03-25 2023-09-21 upply of Furnitures trengthening and Project Ma tions nvelope mentation nagement JGS-ACRESAL/IRFQ/22/011 / Component C: Institutional S Request for Quota Single Stage - One E Under Imple procurment of 2no project v IDA / 70150 trengthening and Project Ma Post Limited 240,000.00 0.00 2023-02-14 2023-01-30 2023-03-12 2023-06-10 tions nvelope mentation ehicles (1no-Bus & 1no Hilux) nagement JGS-ACRESAL/IRFQ/22/010 / Component C: Institutional S Procurement of ICT Eequipm Single Stage - One E IDA / 70150 trengthening and Project Ma Post Request for Bids Open - National 250,000.00 0.00 Canceled 2023-02-10 2023-02-15 2023-03-17 2023-03-24 2023-04-03 2023-07-02 ent GIS, MIS and communica nvelope nagement tion equipment (Laptop, Des ktop etc) JGS-ACRESAL/RFQ/010 / Proc Component C: Institutional S Request for Quota Single Stage - One E Under Imple urement of ICT Equipments ( IDA / 70150 trengthening and Project Ma Post Limited 100,000.00 0.00 2023-04-24 2023-03-27 2023-05-11 2023-05-14 tions nvelope mentation Lasptops, Printers & photoco nagement piers) NG-JIGAWA STATE ACRESAL- 367806-GO-RFB / Supply of f arm inputs for the production Component B: Community Cl Single Stage - One E Pending Impl IDA / 70150 Post Request for Bids Open - National 400,000.00 0.00 2023-07-03 2023-07-08 2023-08-07 2023-08-14 2023-08-26 2023-10-25 of 300hectres rainfed crops ( imate Resilience nvelope ementation Rice, wheet, sorghum and m aize) using standard agrono my practice In cluster system JGS-ACRESAL/IRFQ/23/29 / Pr Component C: Institutional S Single Stage - One E Pending Impl IDA / 70150 Post Request for Bids Open - National 150,000.00 0.00 2023-06-25 2023-06-30 2023-08-11 2023-09-10 2023-10-15 2024-04-12 ocurement GIS & MIS Equip trengthening and Project Ma nvelope ementation ment nagement NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual JGS-ACRESAL/ICS/22/014 / E Component C: Institutional S ngagement of consultant for Consultant Qualifi Under Implement IDA / 70150 trengthening and Project Ma Post Limited 70,000.00 0.00 2023-09-05 2023-05-02 2023-09-16 2023-10-07 2023-10-15 2024-02-12 Enviromental and Social Man cation Selection ation nagement agement Plan (ESMP) JGS-ACRESAL/CS/23/04 / Eng agement of focal NGOs to co nduct communities awarenes Component B: Community Cl Consultant Qualifi Under Implement IDA / 70150 Post Limited 100,000.00 0.00 2023-04-20 2023-03-15 2023-05-04 2023-05-02 2023-05-09 2023-05-15 2023-11-11 s creation, stakeholders sen imate Resilience cation Selection ation sitization and community par ticipation on the impact of cli mate change. Page 1 JGS-ACRESAL/RFP/03 / Enga gement of engineering desig Component A: Dryland Mana Consultant Qualifi IDA / 70150 Post Limited 120,000.00 0.00 Canceled 2023-02-08 2023-01-13 2023-02-22 2023-03-24 2023-04-28 2023-10-25 n for erosion control in Danm gement cation Selection asara & Yalwawa Dutse local government INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NG-JIGAWA STATE ACRESAL- 364961-CS-INDV / Training of Component B: Community Cl Individual Consult Pending Impleme seed producers on seed prod IDA / 70150 Post Limited 30,000.00 0.00 2023-04-19 2023-04-24 2023-04-29 2023-05-18 2023-07-17 imate Resilience ant Selection ntation uction techniques and seed b usiness model in front line L GAs Page 2 PROCUREMENT PLAN (Textual Part) Project information: Nigeria [SPESSE ][P169405] Project Implementation agency: National University Commission Date of the Procurement Plan: August 9, 2019 Period covered by this Procurement Plan: [August 9, 2019 – Jan 31, 2019] Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in Nigeria 2017 Procurement Act, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. None When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Not Applicable Goods: is not applicable Works: is not applicable Other Relevant Procurement Information. None PROCUREMENT Nigeria : Sustainable Procurement, Environmental and Social Standards Enhancement Project (SPESSE) PLAN General Information Country: Nigeria Bank’s Approval Date of the Original Procurement Plan:2019-12-02 2023-06-05 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P169405 GPN Date: Project Name: Sustainable Procurement, Environmental and Social Standards Enhancement Project (SPESSE) Loan / Credit No: IDA / V2820, IDA / 65250 Federal Ministry of Environment-SPESSE Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned NG-EA-CW-RFQ-01-21 / Cons truction of 40ft Containers fo r the project store, conferenc Component I: Technical assi Request for Quota Request for Quota Single Stage - One E Under Imple 2022-06-2 e room, drivers office& toilet IDA / 65250 stance and Support to imple Post Limited tions (Non Bank-S 22,060.00 0.00 2021-10-30 2021-12-25 tions nvelope mentation 3 (including electrical, carpent menting agencies PD) ry & joinery roof work, suppo rt for roof site clearing &foun dation base, window, burglar y &floor tiles) GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NG-EA-GO-RFQ-01-21 / Proc Component I: Technical assi urement of communications Request for Quota Single Stage - One E Pending Impl IDA / 65250 stance and Support to imple Post Limited 9,210.00 0.00 2021-11-20 2022-01-03 2022-07-02 management support equip tions nvelope ementation menting agencies ment (portable audio visual a nd voice equipment) NG-FMENV_SPESSE-140460- Component I: Technical assi Request for Quota Single Stage - One E GO-RFQ / Procurement of Offi IDA / V2820 stance and Support to imple Post Limited 30,000.00 25,429.89 Signed 2020-01-25 2022-03-25 2020-03-21 2022-05-14 2020-09-17 tions nvelope ce furniture menting agencies NG-FMENV_SPESSE-243451- Component I: Technical assi Request for Quota Single Stage - One E Pending Impl GO-RFQ / Procurement of Pro IDA / 65250 stance and Support to imple Post Limited 113,090.00 0.00 2021-10-26 2021-12-21 2022-06-19 tions nvelope ementation ject vehicle menting agencies NG-FMENV_SPESSE-257081- Component I: Technical assi GO-RFQ / Procurement and In Request for Quota Single Stage - One E Pending Impl IDA / 65250 stance and Support to imple Post Limited 18,420.00 0.00 2021-11-08 2022-01-03 2022-07-02 stallation of 10KVA Solar Inv tions nvelope ementation menting agencies erter for Environment Node NG-FMENV_SPESSE-243441- Component I: Technical assi Request for Quota Single Stage - One E Pending Impl GO-RFQ / Procurement of Sec IDA / 65250 stance and Support to imple Post Limited 2,460.00 0.00 2021-11-02 2021-12-28 2022-06-26 tions nvelope ementation urity Systems for Environme menting agencies nt Node Office NG-FMENV_SPESSE-257120- Component I: Technical assi Request for Quota Single Stage - One E GO-RFQ / Procurement of ICT IDA / 65250 stance and Support to imple Post Limited 110,530.00 0.00 Canceled 2021-11-27 2022-01-22 2022-07-21 tions nvelope Infrastructure for the Central menting agencies Agencies Component I: Technical assi NG-EA-GO-RFQ-06-21 / Offic Request for Quota Single Stage - One E Under Imple IDA / 65250 stance and Support to imple Post Limited 25,420.00 0.00 2021-11-13 2022-03-28 2022-01-08 2022-07-07 e Equipments tions nvelope mentation menting agencies NG-FMENV_SPESSE-243375- Component I: Technical assi GO-RFQ / Procurement/Install Request for Quota Single Stage - One E Pending Impl IDA / 65250 stance and Support to imple Post Limited 45,210.00 0.00 2021-11-01 2021-12-27 2022-06-25 ation of Video Conferencing F tions nvelope ementation menting agencies acilities for Environment Nod e NG-EA-GO-RFQ-02-21 / Proc Component I: Technical assi urement and Installation of P Request for Quota Single Stage - One E Pending Impl IDA / 65250 stance and Support to imple Post Limited 73,680.00 0.00 2021-11-03 2021-12-29 2022-06-27 ower Systems for Environme tions nvelope ementation menting agencies nt Node (2 nos.) 50KVA Gene rating Set NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NG-EA-NC-RFQ-03-21 / Procu rement and installation of Ce Component I: Technical assi rtification Management web Request for Quota Single Stage - One E IDA / V2820 stance and Support to imple Post Limited 65,790.00 0.00 Canceled 2021-05-15 2021-07-10 2022-01-06 Portal, E-mail and E-learning tions nvelope menting agencies systems, High End Servers ( Online Infrastructure/Service s and Backup) NG-EA-NC-RFQ-04-21 / Procu rement and Installation of Lo Component I: Technical assi Request for Quota Single Stage - One E cal Area Network Infrastructu IDA / V2820 stance and Support to imple Post Limited 33,420.00 0.00 Canceled 2021-03-20 2021-05-15 2021-11-11 tions nvelope re and 50mbps Internet Band menting agencies width Subscription for Enviro nment Node NG-FMENV_SPESSE-257124- Component I: Technical assi Request for Quota Single Stage - One E Pending Impl NC-RFQ / Renewal of Office S IDA / 65250 stance and Support to imple Post Limited 1,550.00 0.00 2021-11-21 2022-01-16 2022-07-15 tions nvelope ementation uite and Antivirus Subscriptio menting agencies ns NG-EA-NC-RFQ-07-21 / Procu Component I: Technical assi Request for Quota Single Stage - One E Pending Impl rement of Accounting Softwa IDA / 65250 stance and Support to imple Post Limited 18,420.00 0.00 2021-11-23 2022-01-18 2022-07-17 tions nvelope ementation re menting agencies NG-FMENV_SPESSE-257100- Component I: Technical assi Request for Quota Single Stage - One E GO-RFQ / Printing of Financial IDA / 65250 stance and Support to imple Post Limited 8,680.00 8,220.76 Signed 2021-10-31 2022-04-11 2021-12-26 2022-05-01 2022-06-24 tions nvelope Management Security/ Office menting agencies Documents CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 1 NG-FMENV_SPESSE-257119- Component I: Technical assi Least Cost Selecti Under Implement CS-LCS / Auditing of Annual F IDA / 65250 stance and Support to imple Post Open - National 11,050.00 0.00 2021-12-13 2023-03-03 2022-01-03 2022-02-16 2022-03-16 2022-04-15 2022-05-20 2022-06-24 2022-12-21 on ation inancial Accounts menting agencies NG-FMENV_SPESSE-322638- Component I: Technical assi CS-CQS / Consultancy on the Consultant Qualifi Pending Impleme IDA / 65250 stance and Support to imple Post Limited 300,530.00 0.00 2022-10-27 2022-11-10 2022-12-10 2023-01-14 2023-07-13 Development of Certification cation Selection ntation menting agencies management Portal INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NG-EA-CS-INDV-02-21 / Cons ultancy on ICT Support to Ce Component I: Technical assi ntral Agencies on Procureme Individual Consult IDA / V2820 stance and Support to imple Post Limited 26,320.00 0.00 Canceled 2021-04-06 2021-04-11 2021-05-02 2021-06-06 2021-12-03 nt of communications manag ant Selection menting agencies ement support equipment (p ortable audio visual and voic e equipment) NG-EA-CS-INDV-04-21 / Cons ultancy service for the devel Component I: Technical assi opment of Environmental Sta Individual Consult IDA / V2820 stance and Support to imple Post Limited 26,320.00 0.00 Canceled 2021-04-14 2021-04-19 2021-05-10 2021-06-14 2021-12-11 ndards Training Strategies & ant Selection menting agencies Certification Schemes for Co mmunity of Professionals wit h online tools NG-FMENV_SPESSE-140456- Component I: Technical assi CS-INDV / Consultancy sercic Individual Consult Under Implement IDA / V2820 stance and Support to imple Post Limited 35,000.00 0.00 2019-12-31 2022-02-25 2020-01-05 2022-04-19 2020-01-26 2022-04-28 2020-03-01 2020-08-28 e for the Engagement of Proc ant Selection ation menting agencies urement officer NG-FMENV_SPESSE-243413- Component I: Technical assi CS-INDV / Consultancy Servic Individual Consult Under Implement IDA / 65250 stance and Support to imple Post Limited 55,260.00 0.00 2021-11-26 2022-02-17 2021-12-01 2021-12-22 2022-01-26 2022-07-25 e for the Establishment of ES ant Selection ation menting agencies Certification Scheme NG-FMENV_SPESSE-243444- Component I: Technical assi CS-INDV / Consultancy for th Individual Consult Under Implement IDA / 65250 stance and Support to imple Post Limited 12,086.00 0.00 2021-11-29 2022-02-17 2021-12-04 2021-12-25 2022-01-29 2022-07-28 e Review and Validation of ro ant Selection ation menting agencies admap/framework for ES Cer tification Scheme. NG-FMENV_SPESSE-243425- CS-INDV / Consultancy on the requirements for FMENV (EA Component I: Technical assi Individual Consult D) to use online platforms to IDA / 65250 stance and Support to imple Post Limited 5,952.00 0.00 Canceled 2021-11-29 2021-12-04 2021-12-25 2022-01-29 2022-07-28 ant Selection develop capacities to inform menting agencies and manage environmental s tandards activities. (PDO indi cator 1) NG-EA-CS-INDV-05-21 / Cons Component I: Technical assi ultancy Services on Develop Individual Consult IDA / 65250 stance and Support to imple Post Limited 18,420.00 0.00 Canceled 2021-11-30 2021-12-05 2021-12-26 2022-01-30 2022-07-29 ment of Strategies to upscale ant Selection menting agencies Social and Health Standards Assessment NG-FMENV_SPESSE-243418- CS-INDV / Consultancy for St Component I: Technical assi akeholder's Engagement incl Individual Consult Under Implement IDA / 65250 stance and Support to imple Post Limited 55,260.00 0.00 2021-11-17 2022-08-25 2021-11-22 2021-12-13 2022-01-17 2022-07-16 uding Development of Comm ant Selection ation menting agencies unication Strategy for Enviro nmental Standards Sector NG-EA-CS-INDV-01-21 / Cons Component I: Technical assi Individual Consult ultancy on the development IDA / V2820 stance and Support to imple Post Limited 13,160.00 0.00 Canceled 2021-03-22 2021-03-27 2021-04-17 2021-05-22 2021-11-18 ant Selection of communications strategy menting agencies NG-FMENV_SPESSE-312831- CS-INDV / Consultancy for th Component I: Technical assi Individual Consult Pending Impleme e development of Environme IDA / 65250 stance and Support to imple Post Limited 64,189.51 0.00 2022-08-31 2022-09-05 2022-09-26 2022-10-31 2023-04-29 ant Selection ntation ntal Standards capacity build menting agencies ing strategies and plan NG-FMENV_SPESSE-312836- Component I: Technical assi CS-INDV / E&S Instrument Pr Individual Consult Pending Impleme IDA / 65250 stance and Support to imple Post Limited 14,028.54 0.00 2022-12-29 2023-01-03 2023-01-24 2023-02-28 2023-08-27 eparation - GRM, GBV and SE ant Selection ntation menting agencies A Plans for Environment Nod e NG-FMENV_SPESSE-363414- Component I: Technical assi CS-INDV / CONSULTANCY FO Individual Consult Pending Impleme IDA / 65250 stance and Support to imple Post Limited 3,675.00 0.00 2023-06-14 2023-06-19 2023-07-10 2023-08-14 2024-02-10 R THE ENGAGEMENT OF IT C ant Selection ntation menting agencies ONSULTANT FOR THE ENVIR ONMENT NODE Page 2 PLAN DE PASSATION DE MARCHÉS (Texte) Information sur le Projet : République de Djibouti- Projet de Riposte au COVID-19- P173807 Agence d’exécution du Projet : Ministère de la Santé Date du plan de passation des marchés : 13 Avril 2020 Période couverte par ce plan de passation des marchés : Avril 2020 – Juin 2020 Préambule Conformément au paragraphe 5.9 du “Règlement de Passation des Marchés pour les Emprunteurs sollicitant le Financement de Projets d’Investissement (FPI)” (Juillet 2016, révisé en Novembre 2107 et Août 2018) (“Règlement de Passation des Marchés”) le Système électronique de la Banque de suivi systématique des transactions de marchés publics (STEP) sera utilisé pour préparer, valider et actualiser les plans de passation des marchés et effectuer toutes les transactions liées à la passation des marchés du projet. Ce texte ainsi que les tableaux du plan de passation des marchés présents dans STEP constituent le plan de passation des marchés du projet. Les conditions suivantes s'appliquent à toutes les activités de passation de marchés du plan de passation de marchés. Les autres éléments du plan de passation des marchés tels que requis au paragraphe 4.4 du Règlement de passation des marchés sont énoncés dans STEP. Les Dossiers types de passation des marchés publics de la Banque devront être utilisés pour tous les contrats soumis à la concurrence internationale, ainsi que pour tous les autres contrats soumis à cette obligation telle que spécifiée dans les tableaux du plan de passation des marchés de STEP. Procédures nationales de passation des marchés : En accord avec le paragraphe 5.3 du Règlement de passation des marchés, dans le cas où la procédure de passation des marché se fera au niveau national (telle que spécifiée dans les tableaux du plan de passation des marchés inclus de STEP), les procédures nationales de passation des marchés du pays considéré pourront être utilisées. Si l’Emprunteur utilise ses propres procédures d’appel d’offres national ouvert telles qu’énoncées dans la Loi n°53/AN/09/6ème L portant Nouveau Code des Marchés Publics, ces arrangements sont soumis aux dispositions du paragraphe 5.4 du Règlement de passation des marchés Lorsque l’Emprunteur utilise d’autres procédures que l’appel d’offres national ouvert, ces procédures devront être en accord avec les dispositions du paragraphe 5.5 du Règlement de passation des marchés. Crédit-bail tel que spécifié au paragraphe 5.10 du Règlement de Passation des marchés : Le crédit-bail peut être utilisé pour les contrats indiqués comme tel dans le Plan de passation des marchés. « Sans objet » Achat de biens d’occasion tel que spécifié au paragraphe 5.11 du Règlement de Passation des Marchés est autorisé pour les contrats indiqués comme tel dans le Plan de passation des marchés. « Sans objet » Préférence nationale telle que spécifiée au paragraphe 5.51 du Règlement de Passation des Marchés (Fournitures et Travaux). Fournitures : ne s’applique pas/ Travaux ne s’applique pas/ L’Assistance directe à la mise en œuvre (sigle HEIS en anglais) tel que précisée aux paragraphes 3.10 et 3.11 du Règlement de Passation des marchés s’applique. Autres informations pertinentes sur la passation des marchés Utilisation de procédures pour un besoin urgent d’assistance ou de faible capacité PROCUREMENT Djibouti : Djibouti COVID-19 Response PLAN General Information Country: Djibouti 2020-05-03 Bank’s Approval Date of the Original Procurement Plan: 2023-06-02 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P173807 GPN Date: 2020-05-12 Project Name: Djibouti COVID-19 Response Loan / Credit No: IDA / 66000 Ministere de la Sante Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual DJ-MOS-168492-GO-DIR / Ac quisition des fournitures, mé Emergency COVID-19 Respo dicaments , consommables, IDA / 66000 Post Direct Selection Direct 1,900,000.00 1,875,000.00 Completed 2020-04-19 2020-04-30 2020-04-21 2020-04-30 2020-05-10 2020-05-06 2020-08-08 2021-02-15 nse kit de diagnostic et équipem ents médicaux pour le site d e quarantaine. DON PEF TF0B4364 / FOURN Emergency COVID-19 Respo ITURE DES CONSOMMABLES IDA / 66000 Post Direct Selection Direct 942,856.60 942,856.60 Completed 2021-01-21 2021-02-01 2021-01-24 2021-02-03 2021-01-30 2021-02-07 2021-02-24 2022-01-21 nse ET EQUIPEMENTS MEDICAUX DJ-MOS-234856-GO-RFQ / Co nception et impression d’ima Emergency COVID-19 Respo Request for Quota Single Stage - One E IDA / 66000 Post Limited 25,000.00 24,856.07 Completed 2020-11-06 2020-12-02 2021-01-01 2021-01-04 2021-06-30 2021-01-04 ge sur la prévention de la pa nse tions nvelope ndémie de la COVID-19 à Dji bouti DJ-MOS-292879-GO-DIR / Ac Strengthening Overall Healt hat de medicament et conso IDA / 66000 hcare Services and Clinical C Post Direct Selection Direct 1,746,511.10 0.00 Completed 2022-01-01 2022-01-23 2022-01-06 2022-01-23 2022-02-10 2022-08-09 2023-01-13 mmable medicaux apacity for Emergency COVI D-19 Response DJ-MOS-220948-GO-RFQ / Ac Emergency COVID-19 Respo Request for Quota Single Stage - One E quisition des kits et matériel IDA / 66000 Post Limited 27,000.00 0.00 Completed 2021-03-03 2022-05-22 2021-04-03 2021-07-02 2022-06-25 nse tions nvelope s pour le lavage des mains DJ-MOS-298583-GO-DIR / Ac Implementation Managemen quisition d'un Scanner CT po IDA / 66000 t and Monitoring and Evaluat Post Direct Selection Direct - National 655,000.00 0.00 Completed 2022-07-31 2022-10-27 2022-08-05 2022-10-27 2022-09-09 2023-03-08 ur l'hôpital d'Ali-Sabieh. ion DJ-MOS-298584-GO-DIR / Ac Implementation Managemen Under Imple quisition de 02 chambre froid IDA / 66000 t and Monitoring and Evaluat Post Direct Selection Direct - National 80,000.00 0.00 2022-07-31 2022-09-01 2022-08-05 2022-09-01 2022-09-09 2023-03-08 mentation es morgues (6-8 corps). ion DJ-MOS-305782-GO-RFQ / Ac Strengthening Overall Healt Request for Quota Single Stage - One E quisition des fournitures des IDA / 66000 hcare Services and Clinical C Post Limited 27,696.33 0.00 Completed 2020-01-06 2020-01-07 2020-03-02 2020-08-29 2020-01-21 tions nvelope matériels tels que peintures, apacity for Emergency COVI ciments etc D-19 Response DJ-MOS-305781-GO-RFQ / Ac Strengthening Overall Healt Request for Quota Single Stage - One E quisition des lits d'hôpital po IDA / 66000 hcare Services and Clinical C Post Limited 24,927.61 0.00 Completed 2020-01-06 2020-02-20 2020-03-02 2020-08-29 2020-04-01 tions nvelope ur l'hôpital d'Ali-sabieh. apacity for Emergency COVI D-19 Response DJ-MOS-305777-GO-RFQ / Ac Strengthening Overall Healt quisition des fournitures, équ hcare Services and Clinical C Request for Quota Single Stage - One E IDA / 66000 Post Limited 25,937.28 0.00 Completed 2020-01-06 2020-01-16 2020-03-02 2020-08-29 2020-03-02 ipements de plomberie et de apacity for Emergency COVI tions nvelope s petits outillages. D-19 Response DJ-MOS-305778-GO-RFQ / Ac Strengthening Overall Healt Request for Quota Single Stage - One E quisition des lits d'hôpital po IDA / 66000 hcare Services and Clinical C Post Limited 24,927.61 0.00 Completed 2020-01-06 2020-02-20 2020-03-02 2020-08-29 2020-04-01 tions nvelope ur le site de PK13. apacity for Emergency COVI D-19 Response DJ-MOS-306572-GO-DIR / Sy Implementation Managemen stème de visualisation pour l IDA / 66000 t and Monitoring and Evaluat Post Direct Selection Direct - National 27,000.00 0.00 Canceled 2022-08-10 2022-08-15 2022-09-19 2023-03-18 e scanner de l'hôpital Cheiko. ion DJ-MOS-306573-GO-DIR / Ac quisition d'un injecteur pour l Implementation Managemen e scanner de l'hôpital Cheiko IDA / 66000 t and Monitoring and Evaluat Post Direct Selection Direct - National 31,000.00 0.00 Canceled 2022-08-10 2022-08-15 2022-09-19 2023-03-18 et un nouveau onduleur pour ion l'hôpital d'Ali-SABIEH (toujour s avec la CAMME). DJ-MOS-315525-GO-RFQ / Ac quisition des matériels adéqu ats pour la gestion des déche Emergency COVID-19 Respo Request for Quota Single Stage - One E IDA / 66000 Post Limited 17,500.00 0.00 Completed 2022-09-25 2022-10-13 2022-11-20 2023-05-19 2022-12-18 ts sanitaires en termes ( sacs nse tions nvelope plastiques codifiés, corbeilles et boites de sécurité à aiguill es etc.) DJ-MOS-364536-GO-DIR / Ac Implementation Managemen quisition de 4 appareils d'éch Direct - Internation Pending Impl IDA / 66000 t and Monitoring and Evaluat Post Direct Selection 154,980.00 0.00 2023-06-14 2023-06-17 2023-06-18 2023-06-30 ographies fixes et 5 échogra al ementation ion phies mobiles pour les forma tions sanitaires. NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual DJ-MOS-291207-NC-RFQ / Pr oduire des outils de communi Emergency COVID-19 Respo Request for Quota Single Stage - One E cation sur la prévention contr IDA / 66000 Post Limited 24,000.00 0.00 Canceled 2022-06-04 2022-07-30 2023-01-26 nse tions nvelope e la COVID-19 et l'importanc e de la vaccination contre le covid-19 Page 1 DJ-MOS-291203-NC-RFQ / Co nception et production des af Emergency COVID-19 Respo Request for Quota Single Stage - One E IDA / 66000 Post Limited 25,000.00 0.00 Canceled 2022-06-03 2022-07-29 2023-01-25 fiches de communication pou nse tions nvelope r promouvoir la vaccination c ontre le covid-19 CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual DJ-MOS-182922-CS-QCBS / R Implementation Managemen Consultant Qualifi Open - Internationa ecrutement d'une agence po IDA / 66000 t and Monitoring and Evaluat Post 40,000.00 0.00 Canceled 2020-08-25 2020-09-15 2020-10-29 2020-11-28 2021-01-02 2021-07-01 cation Selection l ur l'audit technique et des pe ion rformances DJ-MOS-182925-CS-LCS / Re Implementation Managemen Least Cost Selecti crutement d’un cabinet char IDA / 66000 t and Monitoring and Evaluat Post Open - National 10,000.00 0.00 Canceled 2020-08-25 2020-12-10 2020-09-15 2020-10-07 2020-10-17 2020-11-01 2020-11-23 2020-12-10 2021-01-29 on gé de l’audit des comptes du ion nouveau projet DJ-MOS-241365-CS-LCS / Re Implementation Managemen Least Cost Selecti Under Implement crutement d'un consultant en IDA / 66000 t and Monitoring and Evaluat Post Open - National 10,000.00 0.00 2021-08-09 2021-07-22 2021-08-30 2021-10-13 2021-11-10 2021-12-10 2022-01-14 2022-02-18 2022-08-17 on ation audit externe ion DJ-MOS-306569-CS-CQS / Re Implementation Managemen crutement d'un cabinet pour Consultant Qualifi Open - Internationa Under Implement IDA / 66000 t and Monitoring and Evaluat Post 130,000.00 0.00 2022-08-03 2022-08-07 2022-08-24 2022-10-07 2022-11-06 2022-12-11 2023-06-09 l'élaboration d'une stratégie cation Selection l ation ion de digitalisation. DJ-MOS-352712-CS-CQS / Re Implementation Managemen crutement d’un cabinet médi Consultant Qualifi Open - Internationa IDA / 66000 t and Monitoring and Evaluat Post 60,000.00 0.00 Canceled 2023-03-30 2023-04-20 2023-06-03 2023-07-03 2023-08-07 2024-02-03 cal chargé de services de tél cation Selection l ion é radiologie et de formation en radiologie. INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual DJ-MOS-291137-CS-INDV / R ecrutement d'un consultant p Implementation Managemen Individual Consult our élaborer le document de IDA / 66000 t and Monitoring and Evaluat Post Open 20,000.00 0.00 Canceled 2022-04-28 2022-06-16 2022-07-07 2022-08-11 2023-02-07 ant Selection PLIGD et sa mise en œuvre d ion ans la cadre du projet DJ-MOS-306571-CS-CDS / Co ntrat de maintenance préven Implementation Managemen tive pour le scanner de l'hôpi IDA / 66000 t and Monitoring and Evaluat Post Direct Selection Direct - National 60,000.00 0.00 Canceled 2022-08-10 2022-08-20 2022-10-24 2023-04-22 tal cheiko et formation des b ion énéficiaires (toujours avec la CAMME). DJ-MOS-361196-NC-DIR / Re Implementation Managemen crutement d’un cabinet médi Direct - Internation Under Implement IDA / 66000 t and Monitoring and Evaluat Post Direct Selection 60,000.00 0.00 2023-05-11 2023-05-16 2023-05-14 2023-05-18 2023-06-30 cal chargé des services de té al ation ion lé radiologie et des formation s en radiologie. DJ-MOS-362017-CS-CDS / Re Implementation Managemen crutement d'un cabinet pour Direct - Internation Under Implement IDA / 66000 t and Monitoring and Evaluat Post Direct Selection 45,000.00 0.00 2023-05-21 2023-06-04 2023-05-24 2023-06-20 2023-06-30 l'Installation, la Formation et al ation ion la maintenance des incinérat eurs Page 2 AGRO-CLIMATIC RESILIENCE IN SEMI -ARID LANDSCAPES (ACReSAL) PROJECT PROCUREMENT STRATEGY FOR DEVELOPMENT 1 PROJECT OVERVIEW Country: NIGERIA Full Project Name: AGRO-CLIMATIC RESILIENCE IN SEMI -ARID LANDSCAPES (ACReSAL) Total Finance ($): USD 700 MILLION Project Number: P175237 Summary of Project The Project Development Objective (PDO) is to increase the adoption of climate resilient landscape Development Objectives management practices and enhance livelihoods in targeted arid/semi-arid watersheds in Northern Nigeria. PROJECT COST COMPONENTS ESTMATE OBJECTIVES OF EACH (USD) COMPONENT Component A: 299.6m This component aims to prepare and Desertification Control implement investments to arrest and Landscape desertification and improve the Management sustainable productivity of land in targeted watersheds (about 1,000,000 ha area of degraded and desert landscapes out of 4,000,000 (25%) Government program). Component B: 293.4m This component aims to support Community communities with improved capacity Livelihoods and and investments to improve Resilience sustainable livelihoods. Component C: 107.6m This component aims to strengthen Institutional capacities of institutions at various levels (e.g., national, selected states) Strengthening and to modernize their work for the Project Management longer-term on integrated multi- sectoral planning, information management, and building systems for improving land and water management and sustainable agricultural productivity in northern Nigeria. Component D: 0m This will finance a Contingency Contingency Emergency Response Component Emergency Response (CERC) for landscape and community Components (CERC): resilience in response to extreme weather, land movement events and other emergencies. LIST OF PROCUREMENT ACTIVITIES The project is designed as framework project and therefore investments and the participating states (the major investments will be implemented by the participating states) are not fully known yet. In the table below are the activities that already known, and implementation can commence immediately. The PPSD will be updated during implementation as the investments and participating states become more defined. These investments include gully erosion control, rehabilitation of irrigation and dams. S/N ACTIVITIES COST CUMMULATIVE % of ESTIMATE COST TOTAL (USD) ESTIMATE COST (USD) ESTIMATE 1 Technical assistance for 10,000,000 10,000,000 28% landscape restoration services 2 Extension services technical 9,900,000 19,900,000 57% assistance 3 Implementation support 9,500,000 29,400,000 84% consultancy 4 Long-term framework and 2,500,000 31,900,000 91% policy support 5 Development of strategic 1,600,000 33,500,000 95% catchment plan 4 Monitoring Information 600,000 34,100,000 97% System (MIS) and maintenances 5 Others ICT Equipment and 400,000 34,500,000 98% connectivity, cloud services, others general services Desktops & Laptops 300,000 34,800,000 99% Data collection and analysis at 168,000 34,968,000 100% State/federal Level Production of Manuals (PIM ) 90,000 35,058,000 100% Design and hosting of 56,000 35,114,000 100% interactive website TOTAL 35,114,000 Strategic Assessment of Operating Context and Borrower Capability Operational Context Nigeria experiences a diverse climate that ranges from arid in the north to tropical in much of the country and is listed among the countries most exposed to climate risks. The country faces a high water-scarcity hazard level, with droughts expected to occur on average every five years, with potential increased frequency due to climate change. Focusing on drylands management, ACReSAL will be implemented in the states of northern Nigeria. The agricultural sector is the major economic driver of northern Nigeria. Many projects and initiatives have been undertaken in northern Nigeria over the past decades to combat the growing crisis of desertification. The FGN is thus increasingly moving toward an integrated and multisectoral approach to address the challenges of dryland management. (a) Governance Aspects: There are security challenges in almost all the states in the northern Nigeria where the project will be implemented. The Government of Nigeria is making some progress in addressing these security challenges. The security situation may reduce the interest of major players, especially for Component A to participate in the procurement process and those that choose to participate may add a premium to the bid prices to take of the additional security arrangement they want to put in place during contract execution in case of an award. (b) Economic Aspects: Nigeria has just come out of an economic recession because of CIVID 19 pandemic and a fall in crude oil price in the world market. The country is contending with high inflation and exchange rate volatility. The high inflation and exchange rate volatility has made the prices of the major construction materials such as iron rods and cement to be volatile. Substantial proportion of the Component consist of civil works with locally available inputs (labour and materials). The effect of the exchange volatility will be minimal since bidders expecting to incur expenditures in other currencies for inputs to the Works supplied from outside the country can quote for such inputs in up to three different foreign currencies in their bids. Serious bottleneck exists in the main seaport where goods to be imported from abroad will be discharged. This has led to delay in the custom clearance of good from the port with the resulting demurrage payment and delay in contract execution. The government is working on policy that will remove the bottlenecks. (c) Sustainability Aspects: The government environmental and social standards requires that Environmental and Social Impact Assessment be carried on all major works project before the commencement of such works. ESIA will apply to this project and will be reflected in the solicitation documents and contracts for civil works under the project. (d) Technological Aspects: Kaduna, Niger, Kogi, Jigawa, Borno, Kano and Gombe States that will likely participate in the project have an e-Procurement system which is being used in some of the MDAs. Sokoto State is in the final stages of their e- Procurement implementation. The systems so deployed will be used for procurement under the project. This will further improve value for money, transparency, economy, efficiency, effectiveness, integrity, and openness of procurement process under the project. The country is covered substantially by GSM, part of which is through extensive fiber optic cabling leading to increased networking and internet availability. The availability of reasonable internet access will facilitate the use of the World Bank Systematic Tracking of Exchanges in Procurement (STEP) which is mandatory requirement in the processing all procurement activities under the World Bank Procurement Regulations. Key Conclusions: The security challenges in the country especially in the northern states that will participate in the project may reduce the participation of foreign firms and firms from other parts of the in the procurement process for the project. The current high inflation and exchange rate volatility in the country will affect the costing of the various procurement packages in the project. The use of eProcurement for by the participating states and the FPMU will improve value for money, transparency, economy, efficiency, effectiveness, integrity, and openness of procurement process under the project Assessment of Borrower previous Experience, Capability and Project Implementation Unit (PIU) The project will be implemented using the existing NEWMAP PMUs at both Federal and State levels that are implementing NEWMAP and the NEWMAP AF that will close on June 30, 2022. The implementation arrangement is similar to that of NEWMAP. Each state will be responsible for the procurement of its own activities including contract management and administration. The FPMU and the states that are implementing NEWMAP have experience in World Bank Procurement Regulations. The procurement officers have received sufficient training in procurement under World Bank funded project. The gaps that were observed in the implementation of NEWMAP especially in contract management will be addressed under ACReSAL. Training will be provided on contract management, application of price adjustment, contract monitoring and supervision as soon as the project is effective. Market Analysis The summary of the procurement activities under the project are as follows • Civil works: o gully erosion control, o flood and sedimentation control, o construction of firebreaks, o rehabilitation and construction of small dams, o small scale irrigation infrastructure, o small buildings There are several players both national and international in the marketplace for these activities. International open competitive procurement approach will be used for high value, high risk gully erosion control and construction of dams and firebreaks. The other low value, low risk procurement will follow national open competition or limited competition as may be appropriate. • Goods: o fire control equipment, o vehicles, o farm inputs (seeds, fertilizers), o post-production equipment, o computers, furniture They are locally available and be supplied by several suppliers and the procurement approach will be national open/limited completion as may be appropriate. The approach for the procurement of farm inputs (seeds, fertilizer) will limited competition between the well-known producers/suppliers of these goods. • Consulting services: The major consulting services includes engineering design and supervision of the major civil works like gully erosion control and rehabilitation of dams. The firms that offer this service are available in the local and international markets. Due to the criticality of this consulting assignment to the overall delivery of the major works contracts, the procurement will be designed to attract best consulting firms to express interest in this assignment. Procurement Risk Analysis Market Risk Description of Risk Owner /Contract Description Mitigation Title Description Construction of Designs may no A consultant will be State PMU and shovel ready longer be valid by the hired to update the World Bank gully erosion contracts during design before the control site contract execution commencement of the procurement process Expansion of the Provisions for State PMUs gullies between physical bidding and contract contingencies will signature made in the signed contract. Expansion of gullies Proper drainage on Contractor during construction the site must be due to poor drainage maintained during resulting from construction and the construction of the Contractor shall be works held responsible for any flood damage to life and properties due to his work in this Contract. The Contractor shall allow in his rates, inter alia, for all costs to maintain or divert flow in drains, ditches, open channels and watercourses during construction and other drainage work. No claims for additional payment will be considered in this regard. Construction Poor supervision of supervision the works contracts consultancy Procurement of Delay in port All the necessary PMUs goods to be clearance documentation and imported from waivers will be outside the processed speedily country (delfino ploughs, tractors, etc) General (for all High inflation and Price adjustment to PMUs contracts) exchange rate applied to most even volatility if they duration is less than 18 months. Procurement Objective • To a minimum of 8 qualified consultants to participate in the selection process for the engineering design and supervision consultancy for the major works contracts. • To take advantage of the dry season for the construction contracts by aligning the commencement of the works with the dry season in the project areas. • Value for money and integrity in the procurement process using electronic procurement system. • To have not less than six qualified firms submit bids for the major works contracts. • Procurement Approach Options and Recommendation The following will be a draft zero of the procurement approach options and recommendations. This is because the major investments are not yet known. This section will be updated once the investments are finalized. • Contract and Estimated Cost: Landscape investments (many packages)– USD236 million • Procurement Approach Attribute Selected arrangement Justification Summary/Logic Specifications Conformance Details design for shovel- ready investments from NEWMAP are available. Engineering firm will be hired to provide detail designs for other investments. Sustainability No All the safeguard studies Requirements will be carried out separately and cost implications will be included in the bidding document. Contract Type Traditional Pricing and costing Schedule of mechanism Rates/Admeasurement Price Adjustments None/Percentage Form of Contract (Terms and Conditions) Selection Method Request for Bids (RFB) Selection Arrangement N/A Market Approach Open International/National Pre/Post Qualification Post Evaluation Selection Least Cost Based Method Selection (LCS) Evaluation of Costs Adjusted Bid Price Domestic Preference No Rated Criteria N/A • Contract and Estimated Cost: Development of strategic catchment plan – USD1,600,000 • Procurement Approach Attribute Selected arrangement Justification Summary/Logic Sustainability N/A Requirements Contract Type Traditional Pricing and costing Lump Sum mechanism Price Adjustments None Form of Contract (Terms N/A and Conditions) Selection Method Request for Proposals (RFP) Selection Arrangement N/A Market Approach Open International Pre/Post Qualification Pre-Qualification Evaluation Selection Quality Cost Based Method Selection (QCBS) Evaluation of Costs N/A Domestic Preference N/A Rated Criteria Mandatory • Contract and Estimated Cost: Long-term framework and policy support – USD2,500,000 • Procurement Approach Attribute Selected arrangement Justification Summary/Logic Sustainability N/A Requirements Contract Type Traditional Pricing and costing Time and Materials mechanism Price Adjustments ????? Form of Contract (Terms ????? and Conditions) Selection Method Request for Proposals (RFP) Selection Arrangement N/A Market Approach Open International, Two Envelopes Pre/Post Qualification Pre-Qualification Evaluation Selection Quality Cost Based Method Selection (QCBS) Evaluation of Costs Adjusted Bid Price Domestic Preference No Rated Criteria • Specific experience • Methodology and workplan • Qualification and experience of key experts • Contract and Estimated Cost: Implementation support consultancy – USD9,900,000 • Procurement Approach Attribute Selected arrangement Justification Summary/Logic Sustainability N/A Requirements Contract Type Traditional Pricing and costing Lump Sum mechanism Price Adjustments None Form of Contract (Terms N/A and Conditions) Selection Method Request for Proposals (RFP) Selection Arrangement N/A Market Approach Open International Pre/Post Qualification Pre-Qualification Evaluation Selection Quality Cost Based Method Selection (QCBS) Evaluation of Costs N/A Domestic Preference N/A Rated Criteria Mandatory • Contract and Estimated Cost: Development of strategic catchment plan – USD1,600,000 • Procurement Approach Attribute Selected arrangement Justification Summary/Logic Sustainability N/A Requirements Contract Type Traditional Pricing and costing Lump Sum mechanism Price Adjustments None Form of Contract (Terms and Conditions) Selection Method Request for Proposals (RFP) Selection Arrangement N/A Market Approach Open International, Two Envelopes Pre/Post Qualification Pre-Qualification Evaluation Selection Quality Cost Based Method Selection (QCBS) Evaluation of Costs Adjusted Bid Price Domestic Preference No Rated Criteria • Specific experience • Methodology and workplan • Qualification and experience of key experts Preferred arrangement for low value, low activities Contract Category Estimated cost Procurement Arrangement and Method Desktops & Goods 300,000 Open National Laptops Others ICT Goods 400,000 Open National Equipment and connectivity, cloud services, others general services Production of Goods 90,000 Limited RFQ Manuals (PIM Monitoring Consultancy 600,000 Open National Information System (MIS) and maintenances Design and hosting Consultancy 56,000 Limited CQS of interactive website Data collection and Consultancy 168,000 Limited CQS analysis at State/federal Level Summary of PPSD to be inform the Bank’s preparation of the PAD The project is designed as framework project and therefore investments and the participating states (the major investments will be implemented by the participating states) are not fully known yet. The security challenges in the country especially in the northern states that will participate in the project may reduce the participation of foreign firms and firms from other parts of the in the procurement process for the project. The current high inflation and exchange rate volatility in the country will affect the costing of the various procurement packages in the project. The use of eProcurement for by the participating states and the FPMU will improve value for money, transparency, economy, efficiency, effectiveness, integrity, and openness of procurement process under the project. The FPMU and the states that are implementing NEWMAP have experience in World Bank Procurement Regulations. The procurement officers have received sufficient training in procurement under World Bank funded project. The gaps that were observed in the implementation of NEWMAP especially in contract management will be addressed under ACReSAL. A sufficiently large numbers of firms are available locally and international for most of the procurement packages under the project, therefore competitive procurement can readily be used to achieved value for value during procurement implementation. The design of the gully erosion sites already cleared under NEWMAP that will be transferred to project will be updated prior to the launching of the procurement processes for the construction of such sites. The PPSD will be regularly updated as there are clear pictures on the participating states and the procurement activities that will be implemented by the states and the FPMU. Contract Estimat Bank Procurement Selecti Evaluati Title, ed Cost Oversig Approach/Competi on on Description US$ and ht tion Method Method and Risk Category Rating Implementati 9,500,00 Prior International SPD Rated on support0 (RFP) Criteria consultancy Substanti (VfM) al Long-term 2.500,00 Prior International SPD Rated framework 0, (RFP) Criteria and policy Substanti (VfM) support al Development 1,600,00 Prior International SPD Rated of strategic 0, (RFP) Criteria catchment Substanti (VfM) plan al Monitoring 600,000, Post International SPD Rated Information Moderate (RFP) Criteria System (MIS) (VfM) and maintenance s Others ICT 400,000, Post National RFB Lowest Equipment Moderate Evaluated and Cost connectivity, cloud services, others general services Desktops & 300,000, Post National RFB Lowest Laptops Low Evaluated Cost Data 168,000, Post National CQS Negotiati collection Moderate on and analysis at State/federal Level Production of 90,000, Post National RFQ Lowest Manuals Low Evaluated (PIM) Design and 56,000, Post National CQS Negotiati hosting of Moderate on interactive website PROCUREMENT Nigeria : Agro-Climatic Resilience in Semi-Arid Landscapes (ACReSAL) PLAN General Information Country: Nigeria 2022-11-21 Bank’s Approval Date of the Original Procurement Plan: 2023-06-06 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P175237 GPN Date: Project Name: Agro-Climatic Resilience in Semi-Arid Landscapes (ACReSAL) Loan / Credit No: IDA / 70150 Zamfara State ACReSAL Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned NG-ZAMFARA STATE ACRES Request for Bids - A-335426-CW-RFB / Construc Component A: Dryland Mana Single Stage - One E Small Works SPD Pending Imp 2023-08-1 IDA / 70150 Post Request for Bids Open - National 260,000.00 0.00 2023-01-20 2023-01-25 2023-03-08 2023-04-07 2023-05-12 tion of 6Nos Solar Powered B gement nvelope (1 envelope proce lementation 0 orehole for Domestic use Cho ss) lera Hot spot Areas NG-ZAMFARA STATE ACRES Request for Bids - A-335442-CW-RFB / Establish Component A: Dryland Mana Single Stage - One E Small Works SPD 2023-11-2 ment of 280 Ha Nurseries in IDA / 70150 Post Request for Bids Open - National 490,000.00 0.00 Canceled 2023-02-06 2023-02-13 2023-03-27 2023-04-26 2023-05-31 gement nvelope (1 envelope proce 7 14 LGAs for the Communities ss) to support Farmer Led Agro- Afforestation NG-ZAMFARA STATE ACRES Request for Quota A-327978-CW-RFQ / Construc Component A: Dryland Mana Request for Quota Single Stage - One E tions - Small Work 2023-05-2 IDA / 70150 Post Limited 260,000.00 0.00 Canceled 2023-01-16 2023-02-27 tion of 6Nos solar powered b gement tions nvelope s (Emergency) SP 9 orehole for domestic use in C D -Competitive holera Hot spot areas NG-ZAMFARA STATE ACRES Request for Bids - A-309553-CW-RFB / Establish Component A: Dryland Mana Single Stage - One E Small Works SPD 2023-08-2 ment of 280ha Nurseries in IDA / 70150 Post Request for Bids Limited 490,000.00 0.00 Canceled 2022-11-22 2022-12-06 2023-01-05 2023-02-04 2023-02-25 gement nvelope (1 envelope proce 4 14 LGAs for the Communities ss) to support farnmers led Agro Afforestation. NG-ZAMFARA STATE ACRES Request for Bids - A-338365-CW-RFB / Establish Component A: Dryland Mana Single Stage - One E Small Works SPD Pending Imp 2023-10-0 ment of 280 Ha Nurseries in1 IDA / 70150 Post Request for Bids Limited 916,309.52 0.00 2023-02-13 2023-02-18 2023-04-01 2023-05-01 2023-06-05 gement nvelope (1 envelope proce lementation 3 4LGAs for the Communities t ss) o support farmer led Agro Aff orestation GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NG-ZAMFARA STATE ACRES Component C: Institutional S A-309590-GO-RFQ / Supply of Request for Quota Single Stage - One E Pending Impl IDA / 70150 trengthening and Project Ma Post Limited 35,000.00 0.00 2023-01-16 2023-02-04 2023-02-25 Information, Education and c tions nvelope ementation nagement ommunicvation (IEC) Materia ls NG-ZAMFARA STATE ACRES Component C: Institutional S Request for Quota Single Stage - One E A-310868-GO-RFQ / Supply a IDA / 70150 trengthening and Project Ma Post Limited 75,000.00 0.00 Canceled 2022-12-09 2023-01-12 2023-02-09 tions nvelope nd insatllation of Solar Power nagement for Office NG-ZAMFARA STATE ACRES Component C: Institutional S Request for Quota Single Stage - One E Pending Impl A-309952-GO-RFQ / Supply of IDA / 70150 trengthening and Project Ma Post Limited 50,000.00 0.00 2023-05-03 2023-06-14 2023-07-14 tions nvelope ementation Office furniture & Fittings nagement NG-ZAMFARA STATE ACRES Component C: Institutional S Request for Quota Single Stage - One E Pending Impl A-335422-GO-RFQ / Supply a IDA / 70150 trengthening and Project Ma Post Limited 135,000.00 0.00 2023-05-27 2023-06-27 2023-07-25 tions nvelope ementation nd Installation of Solar Power nagement for Office NG-ZAMFARA STATE ACRES Component C: Institutional S Request for Quota Single Stage - One E Pending Impl A-309514-GO-RFQ / Supply of IDA / 70150 trengthening and Project Ma Post Limited 10,000.00 0.00 2023-05-21 2023-06-08 2023-06-22 tions nvelope ementation Photocopiers & Printers nagement NG-ZAMFARA STATE ACRES Component C: Institutional S A-310837-GO-RFQ / Supply of Request for Quota Single Stage - One E Pending Impl IDA / 70150 trengthening and Project Ma Post Limited 130,000.00 0.00 2022-10-19 2022-11-23 2022-12-23 Multispectral drone, RGB dro tions nvelope ementation nagement ne and Lidar scanner NG-ZAMFARA STATE ACRES Component C: Institutional S A-309568-GO-RFQ / Supply of Request for Quota Single Stage - One E Under Imple IDA / 70150 trengthening and Project Ma Post Limited 220,000.00 0.00 2023-06-12 2023-06-25 2023-07-02 (1 No) 18 seater Bus and (1 tions nvelope mentation nagement Nos) 4x4 Pick up for the Proje ct NG-ZAMFARA STATE ACRES A-340564-GO-RFQ / Supply a Component B: Community Cl Single Stage - One E IDA / 70150 Post Request for Bids Open - National 895,000.00 0.00 Canceled 2023-04-26 2023-05-01 2023-05-06 2023-05-20 2023-06-03 2023-11-30 nd Distribution of 5,000 Goat imate Resilience nvelope s to 2,500 women to support livelihood NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NG-ZAMFARA STATE ACRES Component C: Institutional S Consultant Qualifi Pending Impleme A-310864-CS-CQS / GIS Basel IDA / 70150 trengthening and Project Ma Post Open - National 80,000.00 0.00 2022-10-20 2022-11-10 2022-12-08 2022-12-15 2022-12-29 2023-06-27 cation Selection ntation ine Survey nagement Page 1 NG-ZAMFARA STATE ACRES Component C: Institutional S Consultant Qualifi Pending Impleme A-310832-CS-CQS / M&E Bas IDA / 70150 trengthening and Project Ma Post Limited 300,000.00 0.00 2022-10-21 2022-11-04 2022-12-04 2022-12-18 2023-03-18 cation Selection ntation eline Survey nagement NG-ZAMFARA STATE ACRES A-309598-CS-CQS / Develop Component B: Community Cl Consultant Qualifi Pending Impleme IDA / 70150 Post Open - National 95,000.00 0.00 2023-01-12 2023-01-26 2023-03-02 2023-03-16 2023-04-03 2023-06-02 ment of Business plan for Ide imate Resilience cation Selection ntation ntified Communities NG-ZAMFARA STATE ACRES Component C: Institutional S Consultant Qualifi Pending Impleme A-310371-CS-CQS / Engagem IDA / 70150 trengthening and Project Ma Post Limited 91,000.00 0.00 2023-01-19 2023-02-03 2023-02-10 2023-02-20 2023-04-21 cation Selection ntation ent of ESMP consultant nagement NG-ZAMFARA STATE ACRES A-310857-CS-CQS / Engagem Component B: Community Cl Consultant Qualifi IDA / 70150 Post Open - National 50,000.00 0.00 Canceled 2022-12-12 2022-12-19 2023-01-16 2023-01-30 2023-02-20 2023-05-22 ent of Consultant for Implem imate Resilience cation Selection entation of Climate Smart Ag riculture/CRF NG-ZAMFARA STATE ACRES A-310828-CS-QCBS / Designs of Flood control site for the Component A: Dryland Mana Quality And Cost- Open - Internationa Under Implement reclaimation of 3000 Ha at 5 IDA / 70150 Post 400,000.00 0.00 2023-01-26 2023-02-09 2023-03-03 2023-04-14 2023-05-12 2023-06-23 2023-07-21 2024-01-17 gement Based Selection l ation sites in Bardoki, Maradun, Ka ura Namoda Gusau and Asa ko to Gidan Dangwari of Bun gudu and Kaura Namoda LGA s NG-ZAMFARA STATE ACRES A-310861-CS-QCBS / Studies and Designs for Six number ( Component A: Dryland Mana Quality And Cost- Open - Internationa Pending Impleme 6Nos) Earth Dams with irriga IDA / 70150 Prior 500,000.00 0.00 2023-02-13 2023-03-06 2023-03-27 2023-05-08 2023-06-05 2023-07-17 2023-08-14 2024-02-12 gement Based Selection l ntation tion facilities for 50 hectres + Studies in Bakura, Birnin M agaji, Kaura Namoda, Bungu du, Gusau, and Gummi LGAs NG-ZAMFARA STATE ACRES A-337855-CS-CQS / Develop Component C: Institutional S Consultant Qualifi Under Implement ment of Zamfara ACReSAL W IDA / 70150 trengthening and Project Ma Post Limited 50,000.00 0.00 2023-02-20 2023-02-10 2023-03-06 2023-03-20 2023-04-03 2023-06-02 cation Selection ation ebsite with Portal and other S nagement ocial Media Platforms INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NG-ZAMFARA STATE ACRES A-310842-CS-INDV / Develop Component C: Institutional S Individual Consult Under Implement ment of Zamfara ACReSAL W IDA / 70150 trengthening and Project Ma Post Limited 50,000.00 0.00 2022-12-20 2023-01-02 2023-01-16 2023-02-02 2023-04-04 ant Selection ation ebsite with portal and other nagement Social Media Platforms Page 2 Procurement Plan I. General 1. Project Information Country : Bhutan Borrower : Project Name : Sustainable Hydropower Development Project Loan Credit No. : P 174327 2. Bank’s Approval Date of the Procurement Plan : June 2021 In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (November 2020) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. II. Goods, Works and Non consulting Services 1. Prior Review Threshold Method of Thresholds for Method Prior Review Procurement (USD equivalent) Threshold (USD) RFB (Intl) (Goods) > 200,000 USD All contract above RFB (National) ( > USD 30,000 and up to USD 100,000 Goods) USD 200,000 RFQ (Goods) Up to USD 30,000 RFB Intl (Works) > 1.5 million All contract above USD 300,000 RFB National > 50,000 and up to USD 1.5 (Works) million RFQ (Works) Up to USD 50,000 ICB (Non- > 200,000 USD All contract above Consulting USD 100,000 Services) NCB (Non- < 200,000 USD Consulting Services) Direct Contracting No Threshold; meet paragraph 6.8, 6.9 and 6.10 of regulations Note: The Prior Review Thresholds will be reviewed during the implementation of the project and modified depending on the risk assessment and implementation of mitigation measures. In the case of contracts subject to prior review, before granting / agreeing to (a) a material extension of the stipulated time for performance of a contract; or (b) any substantial modification or waiver of the scope of services or other significant changes to the terms and conditions of such that the contract, including issuing; or (c) any change variation order or orders under such contract amendment (except in cases of extreme urgency) which would in aggregate, singly or combined with all variation orders or amendments previously issued, increase the original contract amount of the contract by more than 15% (fifteen percent); or (d) the proposed termination of the original price contract, the Borrower shall seek the Bank’s no objection to the proposed extension, modification, or change order. A copy of all amendments to the contract shall be furnished to the Bank for its record. 2. Prequalification Not Applicable 3. Reference to Project operational/Procurement Manual Standard Procurement Documents agreed between Project and Bank will be used for all works, consultancy and goods procurements. 4. Any Other Special Procurement Arrangements: National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. Requirements for national open competitive procurement include the following: a. open advertising of the procurement opportunity at the national level; b. the procurement is open to eligible firms from any country; c. the request for bids/request for proposals document shall require that Bidders/Proposers submitting Bids/Proposals present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights; d. contracts with an appropriate allocation of responsibilities, risks, and liabilities; e. publication of contract award information; f. rights for the Bank to review procurement documentation and activities; g. an effective complaints mechanism; and h. maintenance of records of the Procurement Process. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. II. Domestic Preference. Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: is applicable for those contracts identified in the Procurement Plan tables; Works: is not applicable The bid evaluation will be carried out as per agreed timeline in the Procurement Activity Schedule III. Selection of Consultant 1. Prior Review Threshold Method of Threshold (USD Prior Review Threshold Procurement Equivalent) (a) Quality and Cost No threshold All Contracts above USD Based Selection 70,000 for Consultant (b) Quality Based No threshold Firms Selection (c) Selection Made No threshold All contracts above USD Under a Fixed Budget 50,000 for Individual (d) Least Cost Selection No threshold Consultants. (e) Selection Based on < 100,000 Consultant’s Qualifications (f) Single Source As per Consultant Selection of firms Guidelines Para 3.9 (g) Selection of No threshold Individual Consultants Note: The Prior Review Thresholds will be reviewed during the implementation of the project and modified. In the case of contracts subject to prior review, before agreeing to: (a) an extension of the stipulated time for performance of a contract; (b) any substantial modification of the scope of services, substitutions of key experts, or other significant changes to the terms and conditions of the contract; or (c) the proposed termination of the contract, the Borrower shall seek the Bank’s no objection. A copy of all amendments to the contract shall be furnished to the Bank for its record. 2. Short List comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than USD 200,000 equivalent per contract, may comprise entirely of national consultants. PROCUREMENT Bhutan : Sustainable Hydropower Development Project PLAN General Information Country: Bhutan 2021-06-17 Bank’s Approval Date of the Original Procurement Plan: 2023-06-04 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P174327 GPN Date: 2021-06-24 Project Name: Sustainable Hydropower Development Project Loan / Credit No: / , TF / B8007, TF / B8049 DRUK GREEN POWER CORPORATION LIMITED Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BT-DGPCL-364477-GO-RFQ / Purchase of : Preparation Studies/Technic i. High-end desktop (16 core) al Assistance for Hydropowe Single Stage - One E Under Imple ii. High-end desktop (32 core TF / B8007 Post Request for Bids Open - National 69,809.68 0.00 2023-06-18 2023-06-16 2023-06-23 2023-08-04 2023-09-03 2023-10-08 2024-04-05 r Plant and Transmission Lin nvelope mentation ) for flow 3D software e Projects iii. High-end laptop iv. Heavy-duty printer BT-DGPCL-365489-GO-DIR / Preparation Studies/Technic Under Imple Purchase of Laptop (MacBook TF / B8007 al Assistance for Hydropowe Post Direct Selection Direct - National 10,127.69 0.00 2023-06-06 2023-02-20 2023-06-13 2023-07-18 2024-01-14 mentation ) r Plant and Transmission Lin e Projects BT-DGPCL-367286-GO-DIR / Preparation Studies/Technic Direct - Internation Under Imple Procurement of updated DTM TF / B8007 al Assistance for Hydropowe Post Direct Selection 19,797.00 0.00 2023-06-15 2023-06-15 2023-06-16 2023-06-16 2023-06-16 2023-07-29 al mentation images (AW3D Enhanced DT r Plant and Transmission Lin M 50cm) e Projects BT-DGPCL-367287-GO-DIR / Procurement of Flow-3D Hyd ro Software Capacity Building for the Sus 1. A permanent license with Direct - Internation Under Imple TF / B8049 tainable Development of Hy Prior Direct Selection 124,000.00 0.00 2023-06-16 2023-06-18 2023-06-16 2023-06-16 2023-07-07 1 (one) 32-core solver instan al mentation dropower ce token(s) and a total of 32 core tokens 2. A permanent license with 1 (one) 16-core solver instan ce token (s) and a total of 16 core tokens NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BT-DGPCL-236241-CS-QCBS Preparation Studies/Technic / Hiring of Consultancy firm f al Assistance for Hydropowe Quality And Cost- Open - Internationa or providing technical adviso / Post 870,000.00 0.00 Canceled 2021-08-05 2021-06-21 2021-08-26 2021-10-09 2021-11-23 2021-12-23 2022-01-27 2022-03-03 2023-03-03 r Plant and Transmission Lin Based Selection l ry services for the update of e Projects the DPR for Dorjilung Hydrop ower Project BT-DGPCL-241886-CS-QCBS / Hiring of consultancy firm fo r updating and completing en Preparation Studies/Technic vironmental and social impac al Assistance for Hydropowe Quality And Cost- Open - Internationa TF / B8007 Prior 710,000.00 0.00 Signed 2021-08-15 2022-02-03 2021-09-19 2022-03-01 2021-11-23 2022-06-23 2021-12-28 2022-08-11 2022-01-27 2022-09-19 2022-03-09 2022-12-09 2022-04-13 2023-04-13 t assessment including envir r Plant and Transmission Lin Based Selection l onmental management plan e Projects and resettlement plan for Bh utan proposed 1125 MW Dorj ilung Hydropower Project BT-DGPCL-241894-CS-QCBS / Hiring of consultancy firm fo Preparation Studies/Technic r conducting an Aquatic Biodi al Assistance for Hydropowe Quality And Cost- Open - Internationa / Prior 160,000.00 0.00 Canceled 2021-08-15 2021-09-19 2021-11-23 2021-12-28 2022-01-27 2022-03-09 2022-04-13 2023-04-13 versity Assessment r Plant and Transmission Lin Based Selection l of the proposed Bhutan 1125 e Projects MW Dorjilung Hydropower Pr oject BT-DGPCL-241896-CS-QCBS / Hiring of consultancy firm fo Preparation Studies/Technic r conducting a Terrestrial Bio al Assistance for Hydropowe Quality And Cost- Open - Internationa / Prior 100,000.00 0.00 Canceled 2021-08-15 2021-09-19 2021-11-23 2021-12-28 2022-01-27 2022-03-09 2022-04-13 2023-04-13 diversity Assessment r Plant and Transmission Lin Based Selection l of the proposed Bhutan 1125 e Projects MW Dorjilung Hydropower Pr oject BT-DGPCL-266609-CS-QCBS Preparation Studies/Technic / Hiring of consultancy firm fo al Assistance for Hydropowe Quality And Cost- Open - Internationa r providing technical advisory TF / B8007 Prior 870,000.00 0.00 Signed 2021-12-20 2022-01-11 2021-12-30 2022-03-02 2022-02-12 2022-06-10 2022-03-12 2022-08-04 2022-04-11 2022-10-02 2022-05-16 2022-12-14 2022-06-13 2022-12-10 r Plant and Transmission Lin Based Selection l services for the update of the e Projects DPR for Dorjilung Hydropowe r Project INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 1 BT-DGPCL-238665-CS-INDV / Hiring of engineering and da Preparation Studies/Technic m safety review panel (indivi al Assistance for Hydropowe Individual Consult / Post Open 85,000.00 0.00 Canceled 2021-08-15 2021-06-21 2021-10-03 2021-10-24 2021-11-28 2022-05-27 dual consultant) related to d r Plant and Transmission Lin ant Selection am and hydraulic structures f e Projects or Dorjilung Hydropower Proj ect. BT-DGPCL-238688-CS-INDV / Hiring of engineering and da Preparation Studies/Technic m safety review panel (indivi al Assistance for Hydropowe Individual Consult / Post Open 85,000.00 0.00 Canceled 2021-08-15 2021-06-21 2021-10-03 2021-10-24 2021-11-28 2022-05-27 dual consultant) related to hy r Plant and Transmission Lin ant Selection drology/sediment manageme e Projects nt/GLOF for Dorjilung Hydrop ower Project. BT-DGPCL-238689-CS-INDV / Hiring of engineering and da Preparation Studies/Technic m safety review panel (indivi al Assistance for Hydropowe Individual Consult / Post Open 85,000.00 0.00 Canceled 2021-08-15 2021-06-21 2021-10-03 2021-10-24 2021-11-28 2022-05-27 dual consultant) related to se r Plant and Transmission Lin ant Selection ismic hazard assessment and e Projects seismic structural design for Dorjilung Hydropower Project . BT-DGPCL-241900-CS-INDV / Hiring of environmental expe Preparation Studies/Technic rt (individual consultant) of t al Assistance for Hydropowe Individual Consult Under Implement / Prior Limited 50,000.00 0.00 2021-08-15 2022-06-02 2021-09-04 2023-04-07 2021-10-04 2023-05-20 2021-11-14 2022-05-13 he Environmental and Social r Plant and Transmission Lin ant Selection ation Panel of Experts for the prop e Projects osed Bhutan 1125 MW Dorjil ung Hydropower Project BT-DGPCL-241901-CS-INDV / Hiring of Social Expert (indivi Preparation Studies/Technic dual consultant) of the Enviro al Assistance for Hydropowe Individual Consult / Post Limited 40,000.00 0.00 Signed 2021-08-15 2022-06-22 2021-09-04 2023-04-07 2021-10-04 2023-05-24 2021-11-14 2022-05-13 nmental and Social Panel of r Plant and Transmission Lin ant Selection Experts for proposed Bhutan e Projects 1125 MW Dorjilung Hydropo wer Project BT-DGPCL-238686-CS-INDV / Hiring of engineering and da Preparation Studies/Technic m safety review panel (indivi al Assistance for Hydropowe Individual Consult dual consultant) related to e / Prior Open 85,000.00 0.00 Canceled 2021-08-15 2021-06-21 2021-10-03 2021-10-24 2021-11-28 2022-05-27 r Plant and Transmission Lin ant Selection ngineering geology/ geotech e Projects nics/ rock mechanics and des ign of underground works for Dorjilung Hydropower Project . BT-DGPCL-288429-CS-INDV / Hiring of engineering and da Preparation Studies/Technic m safety review panel (indivi al Assistance for Hydropowe Individual Consult dual consultant) related to e / Prior Limited 85,000.00 0.00 Signed 2022-08-14 2022-08-22 2022-08-19 2023-04-07 2022-09-09 2023-05-20 2022-09-23 2023-06-13 2024-03-16 r Plant and Transmission Lin ant Selection ngineering geology/ geotech e Projects nics/ rock mechanics and des ign of underground works for Dorjilung Hydropower Project . BT-DGPCL-290513-CS-INDV / Hiring of engineering and da Preparation Studies/Technic m safety review panel (indivi al Assistance for Hydropowe Individual Consult / Prior Limited 85,000.00 0.00 Signed 2022-08-14 2022-08-22 2022-08-19 2023-04-07 2022-09-09 2023-05-20 2022-10-04 2024-03-27 dual consultant) related to d r Plant and Transmission Lin ant Selection am and hydraulic structures f e Projects or Dorjilung Hydropower Proj ect. BT-DGPCL-290518-CS-INDV / Hiring of engineering and da Preparation Studies/Technic m safety review panel (indivi al Assistance for Hydropowe Individual Consult Under Implement / Prior Limited 85,000.00 0.00 2022-08-14 2022-08-22 2022-08-19 2023-04-07 2022-09-09 2023-05-20 2022-10-04 2024-03-27 dual consultant) related to hy r Plant and Transmission Lin ant Selection ation drology/sediment manageme e Projects nt/GLOF for Dorjilung Hydrop ower Project. BT-DGPCL-290520-CS-INDV / Hiring of engineering and da Preparation Studies/Technic m safety review panel (indivi al Assistance for Hydropowe Individual Consult Under Implement / Prior Limited 85,000.00 0.00 2022-08-14 2022-08-22 2022-08-19 2023-04-07 2022-09-09 2023-05-20 2022-10-04 2024-03-27 dual consultant) related to se r Plant and Transmission Lin ant Selection ation ismic hazard assessment and e Projects seismic structural design for Dorjilung Hydropower Project . Page 2 PROCUREMENT PLAN (Textual Part) Project information: ETHIOPIA, LIVESTOCK AND FISHERIES SECTOR DEVELOPMENT PROJECT, P159382 Project Implementation agency: MINISTRY OF LIVESTOCK AND FISHERIES Date of the Procurement Plan: 31 October 2017 Period covered by this Procurement Plan: October 2017-April 2019 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in Sections 33(1)(a) and 35-48 of the Proclamation No. 649/2009, The Ethiopian Federal Government Procurement and Property Administration Proclamation, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Specify for each Goods: is applicable for those contracts identified in the Procurement Plan tables; Works: is applicable for those contracts identified in the Procurement Plan tables Other Relevant Procurement Information. Procurement of Vehicles and Motor Cycles will be carried out by UNOPS considering the urgency that the vehicles and motor cycles are critically needed for project start up and the need to use UNOPS’s expertise on having long-term relationships with suppliers. PROCUREMENT Ethiopia : Livestock and Fisheries Sector Development Project PLAN General Information Country: Ethiopia 2019-04-11 Bank’s Approval Date of the Original Procurement Plan: 2023-06-06 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P159382 GPN Date: 2018-02-26 Project Name: Livestock and Fisheries Sector Development Project Loan / Credit No: IDA / 61650 Southern Region Livestock and Foshery Sector Development Project Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned ET-SR LFSDP-160651-GO-DI Strengthening National Instit Request for Quota Single Stage - One E 2020-05-2 R / procurement of works to IDA / 61650 Post Limited 3,700.00 5,293.06 Completed 2020-03-06 2020-11-10 2020-04-07 2020-12-08 utions and Programs tions nvelope 2 maintain existing fish bonds ET-SR LFSDP-220435-CW-RF Strengthening National Instit Request for Quota Single Stage - One E Under Imple 2021-04-2 Q / Drilling of a deep well for IDA / 61650 Post Limited 64,500.00 0.00 2021-02-28 2021-08-10 2021-03-26 utions and Programs tions nvelope mentation 5 Arba Minch Fish Hatchery Ce nter ET-SR LFSDP-341744-CW-RF Request for Quota Q / to procure poultry grower Linking More Productive Far Request for Quota Single Stage - One E Pending Imp 2023-10-0 IDA / 61650 Post Limited tions (Non Bank-S 190,000.00 0.00 2023-02-14 2023-04-11 houses work(Lot-1) and to pr mers to Markets tions nvelope lementation 8 PD) ocure a poultry feed house w ork(Lot 2). ET-SR LFSDP-341751-CW-RF Request for Quota Linking More Productive Far Request for Quota Single Stage - One E Pending Imp 2023-10-0 Q / to procure work for the co IDA / 61650 Post Limited tions (Non Bank-S 112,600.00 0.00 2023-02-14 2023-04-11 mers to Markets tions nvelope lementation 8 nstruction of poultry houses. PD) GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ET-SR LFSDP-109415-GO-RF Project Coordination, Monito Request for Quota Single Stage - One E Q / Purchase of IT equipment IDA / 61650 ring and Evaluation, and Kno Post Limited 12,000.00 10,069.25 Completed 2019-04-15 2019-09-29 2019-05-18 2019-04-04 2019-05-28 2019-04-17 tions nvelope s for RCU wledge Management ET-SR LFSDP-109461-GO-RF B / trocar and canula,burdizo ,forceps,apron ,teat cnnula,h oof trimmer, icebox,treatmen Strengthening National Instit Single Stage - One E t syringe, sterilizer,automatic IDA / 61650 Post Request for Bids Open - National 116,364.00 81,298.29 Completed 2019-04-06 2019-04-26 2019-04-11 2019-05-11 2019-05-27 2019-05-21 2019-05-27 2019-06-09 2019-06-27 2019-06-19 2019-07-24 utions and Programs nvelope vaccination syringe 20ml, tre atment needle , vaccination needle ,stethoscope,thermo meter, drenching gun,balling gun, stove,vaginal speculum ET-SR LFSDP-109466-GO-RF Project Coordination, Monito Request for Quota Single Stage - One E Q / Procurement of office fur IDA / 61650 ring and Evaluation, and Kno Post Limited 16,400.00 11,853.81 Completed 2019-04-15 2019-09-29 2019-05-18 2018-11-29 2019-05-28 2018-12-14 tions nvelope niture for regional CU and wo wledge Management reda ET-SR LFSDP-111214-GO-RF B / regional forage seed varie ties & demand: desho grass, Strengthening National Instit Single Stage - One E IDA / 61650 Post Request for Bids Open - National 187,400.00 137,902.40 Completed 2019-04-18 2019-06-02 2019-04-23 2019-06-04 2019-06-02 2019-06-14 2019-07-01 2019-07-02 2019-08-14 2019-07-07 2019-10-11 elephant grass, rhodess gras utions and Programs nvelope s, panicum, cowpea,lablab,d esmodium,pigeon pea, vatch ET-SR LFSDP-111251-GO-RF Q / feed improvement and fe Strengthening National Instit Request for Quota Single Stage - One E ed technologies such as chop IDA / 61650 Post Limited 32,600.00 34,380.27 Completed 2019-04-30 2021-05-19 2019-06-09 2021-07-06 2019-06-19 2021-10-21 utions and Programs tions nvelope per, molasses tanker, urea m olasses block molder. ET-SR LFSDP-146849-GO-RF B / procurement of medical fi eld equipment and laborator y equipment: incubator ,wat Strengthening National Instit Single Stage - One E er bath, air conditioning mac IDA / 61650 Post Request for Bids Open - National 120,000.00 50,126.18 Completed 2019-12-01 2020-08-03 2019-12-06 2020-01-05 2020-01-21 2020-01-15 2020-02-11 2020-01-24 2020-05-01 2020-02-20 2020-05-01 utions and Programs nvelope hine,laboratory deep refriger atorprotective stethoscope, t racor cannula, veterinary spe culums,needle sterilise, castr ation instruments,er, ET-SR LFSDP-146966-GO-RF Project Coordination, Monito Request for Quota Single Stage - One E Q / to procure laptops and de IDA / 61650 ring and Evaluation, and Kno Post Limited 12,000.00 4,226.91 Completed 2019-12-06 2020-01-01 2019-12-18 2020-03-10 2020-01-07 2020-03-10 tions nvelope sk tops for newly procured sp wledge Management ecialists . ET-SR LFSDP-147103-GO-RF B / regional forage seed varie ties & demand: desho grass, Strengthening National Instit Single Stage - One E IDA / 61650 Post Request for Bids Open - National 209,000.00 39,564.05 Completed 2020-03-15 2021-02-23 2020-03-25 2020-04-24 2021-04-05 2020-05-09 2021-04-13 2020-05-22 2021-10-15 2020-06-21 2021-10-15 elephant grass, rhodess gras utions and Programs nvelope s, panicum, cowpea,lablab,d esmodium,pigeon pea, vatc ET-SR LFSDP-158340-GO-DI Strengthening National Instit R / to procure fish feed which IDA / 61650 Post Direct Selection Direct 6,258.35 3,861.08 Completed 2020-02-12 2020-02-07 2020-02-17 2020-03-01 2020-03-16 2020-03-25 2020-04-16 2020-03-28 utions and Programs contains 40% crud protein ET-SR LFSDP-158597-GO-RF Strengthening National Instit Request for Quota Single Stage - One E IDA / 61650 Post Limited 1,200.00 2,331.67 Completed 2020-02-23 2021-06-30 2020-03-20 2021-07-22 2020-04-20 2021-08-18 Q / to procure water pump utions and Programs tions nvelope ET-SR LFSDP-158603-GO-RF Strengthening National Instit Request for Quota Single Stage - One E Q / to procure tables for newl IDA / 61650 Post Limited 5,000.00 2,090.83 Completed 2020-02-20 2020-02-28 2020-03-15 2020-03-16 2020-04-10 2020-03-31 utions and Programs tions nvelope y employed staffs and shelve s ET-SR LFSDP-160601-GO-DI Linking More Productive Far IDA / 61650 Post Direct Selection Direct 84,000.00 14,421.30 Completed 2020-02-24 2020-01-14 2020-03-10 2020-05-29 2020-04-15 2020-01-13 2020-05-15 2020-03-06 R / procurement of a day old mers to Markets chicken ET-SR LFSDP-160621-GO-DI Linking More Productive Far R / procurement of layer and IDA / 61650 Post Direct Selection Direct 136,572.00 3,120.51 Completed 2020-02-24 2020-07-02 2020-03-10 2020-05-01 2020-04-13 2020-07-08 2020-05-13 2020-07-08 mers to Markets broiler chicken Page 1 ET-SR LFSDP-160643-GO-DI Linking More Productive Far R / to procure concentrated f IDA / 61650 Post Direct Selection Direct 153,000.00 30,274.43 Completed 2020-02-24 2020-05-19 2020-03-10 2020-05-22 2020-04-03 2020-06-22 2020-05-03 2020-06-30 mers to Markets eed for livestocks ET-SR LFSDP-160644-GO-DI Linking More Productive Far R / to procure concentrated f IDA / 61650 Post Direct Selection Direct 101,000.00 41,989.90 Completed 2020-02-24 2020-05-30 2020-03-10 2020-06-06 2020-03-30 2020-06-07 2020-04-30 2020-07-06 mers to Markets eed for chickens ET-SR LFSDP-171554-GO-RF Q / to procure deep refrigerat Strengthening National Instit Request for Quota Single Stage - One E IDA / 61650 Post Limited 33,000.00 11,258.45 Completed 2020-05-20 2020-06-08 2020-06-19 2020-07-14 2020-06-25 2020-07-15 or, incubator and liquid nitro utions and Programs tions nvelope gen container 2 liter ET-SR LFSDP-171560-GO-RF B / to procure milk cans, butt er churner, pullet and chicke n transportation coop,egg co Strengthening National Instit Single Stage - One E IDA / 61650 Post Request for Bids Open - National 157,000.00 31,151.50 Completed 2020-05-03 2020-11-27 2020-05-08 2020-06-07 2021-01-04 2020-06-12 2021-02-02 2020-06-23 2021-04-05 2020-07-07 2021-05-27 llection tray,weighting balanc utions and Programs nvelope e, strainer,overall,boots,weig hting scale, heart girth, ear t ag applicator, stew pot, plate , bowl,fish transportation cou p,cream separator. ET-SR LFSDP-171729-GO-RF Q / to procure tablet for RPC Project Coordination, Monito U coordinator and ME special Request for Quota Single Stage - One E IDA / 61650 ring and Evaluation, and Kno Post Limited 33,000.00 384.19 Completed 2020-05-13 2020-06-25 2020-05-26 2020-07-30 2020-06-07 2020-08-13 ist, colour printer and printer tions nvelope wledge Management for RPCU , laptop for woreda project finance officers , LCD for woredas, ET-SR LFSDP-181010-GO-DI R / to procure basic and pre- basic forage seeds of Desmo Strengthening National Instit Pending Impl dium intortum(green leaf), D IDA / 61650 Post Direct Selection Direct 26,000.00 0.00 2020-06-20 2020-06-24 2020-07-03 2020-07-19 utions and Programs ementation esmodium uncinatum(silverl eaf), Rhodes,Sesbania, Alfaal fa (Medicago Sative), Vetch, Punicum(guinea grass). ET-SR LFSDP-199573-GO-RF Linking More Productive Far Request for Quota Single Stage - One E IDA / 61650 Post Limited 16,500.00 7,763.44 Completed 2020-10-19 2020-12-07 2020-11-27 2020-12-19 2020-12-01 2020-12-22 Q / to procure field bags mers to Markets tions nvelope ET-SR LFSDP-201436-GO-RF B / To procure veterinary fiel d equipment and laboratory materials by lot: Lot1- field e Strengthening National Instit Single Stage - One E quipment: glove, vaccination IDA / 61650 Post Request for Bids Open - National 106,000.00 71,353.63 Completed 2020-10-29 2020-11-26 2020-11-03 2020-12-03 2020-11-26 2020-12-10 2021-01-25 2020-12-24 2021-04-03 2021-01-24 2021-04-20 utions and Programs nvelope needle, AI gun, alcohol, syrin ge, CMT kit reagent, cannula; and Lot-2 -Lab equip: incubat or, water bath, Deep freezer, Deionizer, disposal can ET-SR LFSDP-207164-GO-RF Q / to procure fishery develo pment materials: Lot1: PH m Strengthening National Instit Request for Quota Single Stage - One E eter, DO meter, fishing twine IDA / 61650 Post Limited 25,000.00 10,460.13 Completed 2020-12-05 2021-06-24 2020-12-21 2021-07-22 2021-01-20 2021-07-29 utions and Programs tions nvelope , polyethylene bags, Ice box, weighing scale. Lot 2: beach seine net, life jackets, fibre b oat,scoop net, out board engi ne ET-SR LFSDP-207166-GO-DI Strengthening National Instit R / to procure fish feed which IDA / 61650 Post Direct Selection Direct 4,250.00 4,843.28 Completed 2020-11-30 2020-11-01 2020-12-04 2021-05-18 2020-12-20 2021-06-10 2020-12-25 2021-06-11 utions and Programs contains 40% crud protein. ET-SR LFSDP-211326-GO-RF Q / to procure forage develop Strengthening National Instit Request for Quota Single Stage - One E ment materials spade, hoe wi IDA / 61650 Post Limited 7,500.00 3,542.74 Completed 2020-12-27 2021-02-03 2021-01-11 2021-02-23 2021-01-31 2021-04-14 utions and Programs tions nvelope th three fingers, garden rake, wheelbarrow, plastic water c an, tape measure ET-SR LFSDP-237318-GO-RF Strengthening National Instit Request for Quota Single Stage - One E Under Imple IDA / 61650 Post Limited 32,500.00 0.00 2021-06-05 2021-11-19 2021-06-22 2021-07-07 Q / to procure animal forage utions and Programs tions nvelope mentation hay bell ET-SR LFSDP-238731-GO-RF Q / Insemination gun, univers Strengthening National Instit Request for Quota Single Stage - One E IDA / 61650 Post Limited 82,000.00 54,395.03 Completed 2021-06-14 2021-07-05 2021-07-05 2021-08-14 2021-08-04 2021-08-20 al sheath, arm length glove, t utions and Programs tions nvelope hermos flask, denature 70%, savalon, rubber boat ET-SR LFSDP-261449-GO-RF Strengthening National Instit Request for Quota Single Stage - One E Under Imple IDA / 61650 Post Limited 66,000.00 0.00 2021-11-19 2021-12-01 2021-12-08 2022-01-07 Q / to procure heifer utions and Programs tions nvelope mentation ET-SR LFSDP-261451-GO-RF Strengthening National Instit Request for Quota Single Stage - One E Pending Impl IDA / 61650 Post Limited 9,500.00 0.00 2021-11-20 2021-12-08 2022-01-07 Q / to procure bale of hays utions and Programs tions nvelope ementation ET-SR LFSDP-261453-GO-RF Strengthening National Instit Request for Quota Single Stage - One E Under Imple Q / to procure concentrated IDA / 61650 Post Limited 22,200.00 0.00 2021-11-20 2022-10-04 2021-12-08 2022-01-07 utions and Programs tions nvelope mentation feed for animals ET-SR LFSDP-261496-GO-RF B / To procure veterinary fiel d equipment and laboratory materials by lot: Lot1- field e Strengthening National Instit Single Stage - One E Pending Impl quipment: glove, vaccination IDA / 61650 Post Request for Bids Open - National 105,500.00 0.00 2021-11-17 2021-12-02 2022-01-01 2022-01-06 2022-01-16 2022-01-31 utions and Programs nvelope ementation needle, AI gun, alcohol, syrin ge, CMT kit reagent, cannula; and Lot-2 -Lab equip: incubat or, water bath, Deep freezer, Deionizer, disposal can ET-SR LFSDP-262088-GO-RF Project Coordination, Monito Request for Quota Single Stage - One E Under Imple Q / to procure laptop,tablet, IDA / 61650 ring and Evaluation, and Kno Post Limited 4,100.00 0.00 2021-11-23 2021-12-22 2021-12-13 2022-01-02 tions nvelope mentation printer wledge Management ET-SR LFSDP-262212-GO-RF Project Coordination, Monito Request for Quota Single Stage - One E Under Imple Q / to procure chair, table, fil IDA / 61650 ring and Evaluation, and Kno Post Limited 2,500.00 0.00 2021-11-24 2021-12-30 2021-12-14 2022-01-03 tions nvelope mentation e cabinet, cash safe wledge Management ET-SR LFSDP-265001-GO-RF Q / to procure animal veterin ary drugs such as Penestrep 20/20, Oxytetracycline 20%, Strengthening National Instit Request for Quota Single Stage - One E Pending Impl IDA / 61650 Post Limited 3,700.00 0.00 2021-12-08 2021-12-24 2022-01-13 Oxytetracycline 10%, Albend utions and Programs tions nvelope ementation azole, Tetraclozan, Levamiza n, Indigestion powder, Sulfad imidine Sodium, Diminazene diaceturate + Phenazone, Io dine tincture ET-SR LFSDP-265016-GO-RF Strengthening National Instit Request for Quota Single Stage - One E Pending Impl IDA / 61650 Post Limited 8,100.00 0.00 2021-12-05 2021-12-25 2022-01-14 Q / to procure chairs and tabl utions and Programs tions nvelope ementation es Page 2 ET-SR LFSDP-265022-GO-RF Strengthening National Instit Request for Quota Single Stage - One E Pending Impl IDA / 61650 Post Limited 10,600.00 0.00 2021-12-05 2021-12-24 2022-01-13 Q / to procure boat utions and Programs tions nvelope ementation ET-SR LFSDP-265049-GO-RF Strengthening National Instit Request for Quota Single Stage - One E Pending Impl Q / to procure chopper and U IDA / 61650 Post Limited 32,300.00 0.00 2021-12-05 2021-12-22 2022-01-11 utions and Programs tions nvelope ementation rea molasses moulder ET-SR LFSDP-265057-GO-RF Strengthening National Instit Request for Quota Single Stage - One E Under Imple IDA / 61650 Post Limited 4,000.00 0.00 2021-12-05 2022-04-13 2021-12-23 2022-01-11 Q / to procure pumps utions and Programs tions nvelope mentation ET-SR LFSDP-265076-GO-RF Q / to procure spade, wheelb Strengthening National Instit Request for Quota Single Stage - One E Pending Impl IDA / 61650 Post Limited 6,600.00 0.00 2021-12-05 2021-12-23 2022-01-12 arrows, garden rake, plastic utions and Programs tions nvelope ementation water can, tape measure ET-SR LFSDP-269041-GO-RF Linking More Productive Far Request for Quota Single Stage - One E Pending Impl Q / procurement of chopper a IDA / 61650 Post Limited 14,210.00 0.00 2021-12-28 2022-01-17 2022-02-16 mers to Markets tions nvelope ementation nd urea molasses moulder ET-SR LFSDP-269052-GO-RF Q / procurement of hanging Linking More Productive Far Request for Quota Single Stage - One E Pending Impl IDA / 61650 Post Limited 3,200.00 0.00 2021-12-28 2022-01-17 2022-02-16 weight scale, hearth girth, kn mers to Markets tions nvelope ementation apsack spray, overcoat ET-SR LFSDP-269055-GO-RF Linking More Productive Far Request for Quota Single Stage - One E Pending Impl IDA / 61650 Post Limited 3,200.00 0.00 2021-12-28 2022-01-17 2022-02-17 Q / procurement of water tan mers to Markets tions nvelope ementation ker ET-SR LFSDP-269056-GO-RF Linking More Productive Far Request for Quota Single Stage - One E Pending Impl Q / procurement of wheelbarr IDA / 61650 Post Limited 1,800.00 0.00 2021-12-23 2021-12-28 2022-01-02 2022-01-17 2022-01-25 2022-02-24 mers to Markets tions nvelope ementation ow, sickle,rake, spade,hoe ET-SR LFSDP-269070-GO-RF Linking More Productive Far Request for Quota Single Stage - One E Pending Impl IDA / 61650 Post Limited 15,600.00 0.00 2021-12-28 2022-01-17 2022-07-16 Q / procurement of concentra mers to Markets tions nvelope ementation ted feed ET-SR LFSDP-269185-GO-RF Linking More Productive Far Request for Quota Single Stage - One E Pending Impl IDA / 61650 Post Limited 6,400.00 0.00 2021-12-28 2022-01-17 2022-02-16 Q / procurement of baled hay mers to Markets tions nvelope ementation ET-SR LFSDP-269186-GO-RF Linking More Productive Far Request for Quota Single Stage - One E Pending Impl IDA / 61650 Post Limited 2,700.00 0.00 2021-12-28 2022-01-17 2022-02-16 Q / to procure water tankers mers to Markets tions nvelope ementation ET-SR LFSDP-269187-GO-RF Linking More Productive Far Request for Quota Single Stage - One E Pending Impl IDA / 61650 Post Limited 9,500.00 0.00 2021-12-28 2022-01-17 2022-02-16 Q / to procure chopper and U mers to Markets tions nvelope ementation MB ET-SR LFSDP-269191-GO-RF Linking More Productive Far Request for Quota Single Stage - One E Pending Impl Q / to procure wheelbarrow,si IDA / 61650 Post Limited 1,500.00 0.00 2021-12-28 2022-01-17 2022-02-16 mers to Markets tions nvelope ementation ckle,rake,spade,hoe ET-SR LFSDP-269192-GO-RF Linking More Productive Far Request for Quota Single Stage - One E Under Imple IDA / 61650 Post Limited 10,700.00 0.00 2021-12-28 2022-06-27 2022-01-17 2022-02-16 Q / to procure concentrated f mers to Markets tions nvelope mentation eed ET-SR LFSDP-269194-GO-RF Q / to procure hanging weigh Linking More Productive Far Request for Quota Single Stage - One E Pending Impl IDA / 61650 Post Limited 2,600.00 0.00 2021-12-28 2022-01-17 2022-02-16 t balance, hearth girth,knaps mers to Markets tions nvelope ementation ack spray,overcoat ET-SR LFSDP-269195-GO-RF Linking More Productive Far Request for Quota Single Stage - One E Pending Impl IDA / 61650 Post Limited 4,500.00 0.00 2021-12-28 2022-01-17 2022-02-16 Q / to procure baled hay mers to Markets tions nvelope ementation ET-SR LFSDP-269203-GO-RF Linking More Productive Far Request for Quota Single Stage - One E Pending Impl IDA / 61650 Post Limited 3,157.00 0.00 2021-12-28 2022-01-17 2022-02-16 Q / to procure water tanker mers to Markets tions nvelope ementation ET-SR LFSDP-269204-GO-RF Linking More Productive Far Request for Quota Single Stage - One E Pending Impl Q / to procure chooper and u IDA / 61650 Post Limited 9,500.00 0.00 2021-12-28 2022-01-17 2022-02-16 mers to Markets tions nvelope ementation rea molasses moulder ET-SR LFSDP-269205-GO-RF Linking More Productive Far Request for Quota Single Stage - One E Pending Impl Q / to procure wheelbarrow,si IDA / 61650 Post Limited 1,400.00 0.00 2021-12-28 2022-01-17 2022-02-16 mers to Markets tions nvelope ementation ckle,rake,spade,hoe ET-SR LFSDP-269206-GO-RF Linking More Productive Far Request for Quota Single Stage - One E Pending Impl IDA / 61650 Post Limited 10,700.00 0.00 2021-12-28 2022-01-17 2022-02-16 Q / to procure concentrated f mers to Markets tions nvelope ementation eed ET-SR LFSDP-269207-GO-RF Linking More Productive Far Request for Quota Single Stage - One E Pending Impl Q / to procure hanging weigh IDA / 61650 Post Limited 5,100.00 0.00 2021-12-28 2022-01-17 2022-02-16 mers to Markets tions nvelope ementation t scale,hearth girth,knaspack spray, overcoat ET-SR LFSDP-269556-GO-RF Linking More Productive Far Request for Quota Single Stage - One E Pending Impl IDA / 61650 Post Limited 4,300.00 0.00 2021-12-28 2022-01-17 2022-02-16 Q / to procure baled hay mers to Markets tions nvelope ementation ET-SR LFSDP-269568-GO-RF Q / to procure milk canes, ch Linking More Productive Far Request for Quota Single Stage - One E Pending Impl urner,casserole, chiller,chees IDA / 61650 Post Limited 23,200.00 0.00 2021-12-28 2022-01-17 2022-02-16 mers to Markets tions nvelope ementation e maker, sieve, graduate cyli nder,aluminium dishes,bucke t,plastic jar ET-SR LFSDP-269570-GO-RF Linking More Productive Far Request for Quota Single Stage - One E Pending Impl IDA / 61650 Post Limited 3,200.00 0.00 2021-12-28 2022-01-17 2022-02-16 Q / to procure deep refrigerat mers to Markets tions nvelope ementation or ET-SR LFSDP-269572-GO-RF Q / to procure aluminium mil k cane,chiller, casserole, chu Linking More Productive Far Request for Quota Single Stage - One E Pending Impl IDA / 61650 Post Limited 23,200.00 0.00 2021-12-28 2022-01-17 2022-02-16 rner, chiller, graduate cylinde mers to Markets tions nvelope ementation r, cheese maker, sieve, alumi nium dish, plastic jar, bucket ET-SR LFSDP-269573-GO-RF Linking More Productive Far Request for Quota Single Stage - One E Pending Impl IDA / 61650 Post Limited 3,200.00 0.00 2021-12-28 2022-01-17 2022-02-16 Q / to procure deep refrigerat mers to Markets tions nvelope ementation or ET-SR LFSDP-269581-GO-RF Q / to procurement aluminiu Linking More Productive Far Request for Quota Single Stage - One E Pending Impl m milk cane, aluminium, chill IDA / 61650 Post Limited 8,700.00 0.00 2021-12-28 2022-01-17 2022-02-16 mers to Markets tions nvelope ementation er, churner, aluminium dish, graduate cylinder, cheese m aker, plastic jar, bucket ET-SR LFSDP-269585-GO-RF Linking More Productive Far Request for Quota Single Stage - One E Pending Impl IDA / 61650 Post Limited 1,500.00 0.00 2021-12-28 2022-01-17 2022-02-16 Q / to procurement deep refri mers to Markets tions nvelope ementation gerator Page 3 ET-SR LFSDP-269602-GO-RF Linking More Productive Far Request for Quota Single Stage - One E Pending Impl IDA / 61650 Post Limited 1,500.00 0.00 2021-12-28 2022-01-17 2022-02-16 Q / to procure deep refrigerat mers to Markets tions nvelope ementation or ET-SR LFSDP-269620-GO-RF Q / to procure aluminium mil Linking More Productive Far Request for Quota Single Stage - One E Under Imple IDA / 61650 Post Limited 8,800.00 0.00 2021-12-28 2022-04-14 2022-01-17 2022-02-16 k cane, chiller,churner, chees mers to Markets tions nvelope mentation e maker, sieve, graduate cyli nder, plastic jar,bucket ET-SR LFSDP-269622-GO-RF Linking More Productive Far Request for Quota Single Stage - One E Pending Impl IDA / 61650 Post Limited 1,500.00 0.00 2021-12-28 2022-01-17 2022-02-16 Q / to procure refrigerator mers to Markets tions nvelope ementation ET-SR LFSDP-269623-GO-RF Q / to procure aluminium mil Linking More Productive Far Request for Quota Single Stage - One E Pending Impl k cane, chiller, churner, sieve IDA / 61650 Post Limited 8,800.00 0.00 2021-12-28 2022-01-17 2022-02-16 mers to Markets tions nvelope ementation , casserole, water bucket, pla stic jar, cheese maker, gradu ate cylinder ET-SR LFSDP-269625-GO-RF Q / to procure feeder,grower Linking More Productive Far Request for Quota Single Stage - One E Pending Impl IDA / 61650 Post Limited 4,800.00 0.00 2021-12-28 2022-01-17 2022-02-16 feeder, waterer, chicken gare mers to Markets tions nvelope ementation d, water barrel, coup, spraye r for disinfection ET-SR LFSDP-269628-GO-RF Q / to procure feeder,grower Linking More Productive Far Request for Quota Single Stage - One E Pending Impl IDA / 61650 Post Limited 4,800.00 0.00 2021-12-28 2022-01-17 2022-02-16 feeder, waterer, chicken gare mers to Markets tions nvelope ementation d, water barrel, coup, spraye r for disinfection ET-SR LFSDP-269629-GO-RF Q / to procure feeder,grower Linking More Productive Far Request for Quota Single Stage - One E Pending Impl IDA / 61650 Post Limited 4,800.00 0.00 2021-12-28 2022-01-17 2022-02-16 feeder, waterer, chicken gare mers to Markets tions nvelope ementation d, water barrel, coup, spraye r for disinfection ET-SR LFSDP-269635-GO-RF Linking More Productive Far Request for Quota Single Stage - One E Pending Impl IDA / 61650 Post Limited 3,200.00 0.00 2021-12-28 2022-01-17 2022-02-16 Q / to procure water tanker mers to Markets tions nvelope ementation ET-SR LFSDP-269641-GO-RF Linking More Productive Far Request for Quota Single Stage - One E Pending Impl Q / to procure chopper, urea IDA / 61650 Post Limited 9,500.00 0.00 2021-12-28 2022-01-17 2022-02-16 mers to Markets tions nvelope ementation molasses moulder ET-SR LFSDP-269642-GO-RF Linking More Productive Far Request for Quota Single Stage - One E Pending Impl Q / to procure wheelbarrow, IDA / 61650 Post Limited 1,400.00 0.00 2021-12-28 2022-01-17 2022-02-16 mers to Markets tions nvelope ementation sickle, rake,hoe, spade ET-SR LFSDP-269644-GO-RF Linking More Productive Far Request for Quota Single Stage - One E Pending Impl IDA / 61650 Post Limited 10,700.00 0.00 2021-12-28 2022-01-17 2022-02-16 Q / to procure concentrated f mers to Markets tions nvelope ementation ood ET-SR LFSDP-269645-GO-RF Linking More Productive Far Request for Quota Single Stage - One E Pending Impl IDA / 61650 Post Limited 4,300.00 0.00 2021-12-28 2022-01-17 2022-02-16 Q / to procure baled hay mers to Markets tions nvelope ementation ET-SR LFSDP-269646-GO-RF Linking More Productive Far Request for Quota Single Stage - One E Pending Impl Q / to procure weight scale, h IDA / 61650 Post Limited 5,100.00 0.00 2021-12-28 2022-01-17 2022-02-16 mers to Markets tions nvelope ementation earth girth, knapsack spray, overcoat ET-SR LFSDP-269647-GO-RF Linking More Productive Far Request for Quota Single Stage - One E Pending Impl IDA / 61650 Post Limited 2,700.00 0.00 2021-12-28 2022-01-17 2022-02-16 Q / to procure water tanker mers to Markets tions nvelope ementation ET-SR LFSDP-269648-GO-RF Linking More Productive Far Request for Quota Single Stage - One E Pending Impl IDA / 61650 Post Limited 4,800.00 0.00 2021-12-28 2022-01-17 2022-02-16 Q / to procure chopper, urea mers to Markets tions nvelope ementation molasses ET-SR LFSDP-269649-GO-RF Linking More Productive Far Request for Quota Single Stage - One E Pending Impl Q / to procure wheelbarrow, IDA / 61650 Post Limited 3,300.00 0.00 2021-12-28 2022-01-17 2022-02-16 mers to Markets tions nvelope ementation sickle, rake, spade,hoe ET-SR LFSDP-269650-GO-RF Linking More Productive Far Request for Quota Single Stage - One E Under Imple IDA / 61650 Post Limited 5,400.00 0.00 2021-12-28 2022-06-30 2022-01-17 2022-02-16 Q / to procure concentrated f mers to Markets tions nvelope mentation eed ET-SR LFSDP-269652-GO-RF Linking More Productive Far Request for Quota Single Stage - One E Pending Impl IDA / 61650 Post Limited 2,200.00 0.00 2021-12-28 2022-01-17 2022-02-16 Q / to procure baled hay mers to Markets tions nvelope ementation ET-SR LFSDP-269653-GO-RF Linking More Productive Far Request for Quota Single Stage - One E Pending Impl Q / to procure weight scale, h IDA / 61650 Post Limited 2,000.00 0.00 2021-12-28 2022-01-17 2022-02-16 mers to Markets tions nvelope ementation earth girth, knapsack spray, overcoat ET-SR LFSDP-269655-GO-RF Linking More Productive Far Request for Quota Single Stage - One E Pending Impl IDA / 61650 Post Limited 3,700.00 0.00 2021-12-28 2022-01-17 2022-02-16 Q / to procure water tanker mers to Markets tions nvelope ementation ET-SR LFSDP-269662-GO-RF Linking More Productive Far Request for Quota Single Stage - One E Pending Impl IDA / 61650 Post Limited 9,500.00 0.00 2021-12-28 2022-01-17 2022-02-16 Q / to procure chopper, urea mers to Markets tions nvelope ementation molasses ET-SR LFSDP-269664-GO-RF Linking More Productive Far Request for Quota Single Stage - One E Pending Impl Q / to procure wheelbarrow, IDA / 61650 Post Limited 1,200.00 0.00 2021-12-28 2022-01-17 2022-02-16 mers to Markets tions nvelope ementation sickle,rake,spade,hoe ET-SR LFSDP-269665-GO-RF Linking More Productive Far Request for Quota Single Stage - One E Pending Impl IDA / 61650 Post Limited 10,700.00 0.00 2021-12-28 2022-01-17 2022-02-16 Q / to procure concentrated f mers to Markets tions nvelope ementation eed ET-SR LFSDP-269666-GO-RF Linking More Productive Far Request for Quota Single Stage - One E Pending Impl IDA / 61650 Post Limited 4,300.00 0.00 2021-12-28 2022-01-17 2022-02-16 Q / to procure baled hay mers to Markets tions nvelope ementation ET-SR LFSDP-269667-GO-RF Linking More Productive Far Request for Quota Single Stage - One E Pending Impl Q / to procure weight balanc IDA / 61650 Post Limited 2,600.00 0.00 2021-12-28 2022-01-17 2022-02-16 mers to Markets tions nvelope ementation e, hearth, knapsack spray ET-SR LFSDP-269668-GO-RF Linking More Productive Far Request for Quota Single Stage - One E Under Imple IDA / 61650 Post Limited 2,200.00 0.00 2021-12-28 2022-06-10 2022-01-17 2022-02-16 Q / to procure water tanker mers to Markets tions nvelope mentation ET-SR LFSDP-269669-GO-RF Linking More Productive Far Request for Quota Single Stage - One E Pending Impl Q / to procure chopper, urea IDA / 61650 Post Limited 9,500.00 0.00 2021-12-28 2022-01-17 2022-02-16 mers to Markets tions nvelope ementation molasses moulder ET-SR LFSDP-269670-GO-RF Linking More Productive Far Request for Quota Single Stage - One E Pending Impl Q / to procure wheelbarrow, IDA / 61650 Post Limited 1,200.00 0.00 2021-12-28 2022-01-17 2022-02-16 mers to Markets tions nvelope ementation sickle, rake,hoe, spade ET-SR LFSDP-269671-GO-RF Linking More Productive Far Request for Quota Single Stage - One E Under Imple IDA / 61650 Post Limited 10,700.00 0.00 2021-12-28 2022-06-28 2022-01-17 2022-02-16 Q / to procure concentrated f mers to Markets tions nvelope mentation eed Page 4 ET-SR LFSDP-269672-GO-RF Linking More Productive Far Request for Quota Single Stage - One E Pending Impl IDA / 61650 Post Limited 4,300.00 0.00 2021-12-28 2022-01-17 2022-02-16 Q / to procure baled hay mers to Markets tions nvelope ementation ET-SR LFSDP-269673-GO-RF Linking More Productive Far Request for Quota Single Stage - One E Pending Impl Q / to procure weight scale, h IDA / 61650 Post Limited 2,100.00 0.00 2021-12-28 2022-01-17 2022-02-16 mers to Markets tions nvelope ementation earth girth, knapsack spray, overcoat ET-SR LFSDP-269674-GO-RF Linking More Productive Far Request for Quota Single Stage - One E Pending Impl IDA / 61650 Post Limited 3,200.00 0.00 2021-12-28 2022-01-17 2022-02-16 Q / to procure water tanker mers to Markets tions nvelope ementation ET-SR LFSDP-269675-GO-RF Linking More Productive Far Request for Quota Single Stage - One E Pending Impl Q / to procure chopper, urea IDA / 61650 Post Limited 14,300.00 0.00 2021-12-28 2022-01-17 2022-02-16 mers to Markets tions nvelope ementation molasses moulder ET-SR LFSDP-269683-GO-RF Linking More Productive Far Request for Quota Single Stage - One E Pending Impl Q / to procure wheelbarrow, IDA / 61650 Post Limited 1,800.00 0.00 2021-12-28 2022-01-17 2022-02-16 mers to Markets tions nvelope ementation sickle,rake,spade,hoe ET-SR LFSDP-269684-GO-RF Linking More Productive Far Request for Quota Single Stage - One E Pending Impl IDA / 61650 Post Limited 16,000.00 0.00 2021-12-28 2022-01-17 2022-02-16 Q / to procure concentrated f mers to Markets tions nvelope ementation eed ET-SR LFSDP-269685-GO-RF Linking More Productive Far Request for Quota Single Stage - One E Pending Impl IDA / 61650 Post Limited 6,400.00 0.00 2021-12-28 2022-01-17 2022-02-16 Q / to procure baled hay mers to Markets tions nvelope ementation ET-SR LFSDP-269686-GO-RF Linking More Productive Far Request for Quota Single Stage - One E Pending Impl Q / to procure hanging weigh IDA / 61650 Post Limited 3,200.00 0.00 2021-12-28 2022-01-17 2022-02-16 mers to Markets tions nvelope ementation t scale, hearth, knapsack spr ay, overcoat ET-SR LFSDP-269687-GO-RF Linking More Productive Far Request for Quota Single Stage - One E Pending Impl IDA / 61650 Post Limited 2,700.00 0.00 2021-12-28 2022-01-17 2022-02-16 Q / to procure water tanker mers to Markets tions nvelope ementation ET-SR LFSDP-269688-GO-RF Linking More Productive Far Request for Quota Single Stage - One E Pending Impl Q / to procure chopper, urea IDA / 61650 Post Limited 9,500.00 0.00 2021-12-28 2022-01-17 2022-02-16 mers to Markets tions nvelope ementation molasses moulder ET-SR LFSDP-269689-GO-RF Linking More Productive Far Request for Quota Single Stage - One E Pending Impl Q / to procure wheelbarrow,si IDA / 61650 Post Limited 1,400.00 0.00 2021-12-28 2022-01-17 2022-02-16 mers to Markets tions nvelope ementation ckle,rake,spade,hoe, ET-SR LFSDP-269690-GO-RF Linking More Productive Far Request for Quota Single Stage - One E Pending Impl IDA / 61650 Post Limited 10,700.00 0.00 2021-12-28 2022-01-17 2022-02-16 Q / to procure concentrated f mers to Markets tions nvelope ementation eed ET-SR LFSDP-269691-GO-RF Linking More Productive Far Request for Quota Single Stage - One E Pending Impl IDA / 61650 Post Limited 4,300.00 0.00 2021-12-28 2022-01-17 2022-02-16 Q / to procure baled hay mers to Markets tions nvelope ementation ET-SR LFSDP-269692-GO-RF Linking More Productive Far Request for Quota Single Stage - One E Pending Impl Q / to procure hanging weigh IDA / 61650 Post Limited 2,200.00 0.00 2021-12-28 2022-01-17 2022-02-16 mers to Markets tions nvelope ementation t scale, hearth girth, knapsac k spray, overcoat ET-SR LFSDP-269776-GO-RF Q / to procure deep refrigerat Linking More Productive Far Request for Quota Single Stage - One E Under Imple IDA / 61650 Post Limited 7,800.00 0.00 2021-12-28 2022-06-27 2022-01-17 2022-02-16 or,ice maker machine, ice bo mers to Markets tions nvelope mentation x, packing machine, coup ET-SR LFSDP-269779-GO-RF Linking More Productive Far Request for Quota Single Stage - One E Pending Impl IDA / 61650 Post Limited 1,100.00 0.00 2021-12-28 2022-01-17 2022-02-16 Q / to procure life jacket mers to Markets tions nvelope ementation ET-SR LFSDP-269781-GO-RF Linking More Productive Far Request for Quota Single Stage - One E Pending Impl IDA / 61650 Post Limited 5,300.00 0.00 2021-12-28 2022-01-17 2022-02-16 Q / to procure threads mers to Markets tions nvelope ementation ET-SR LFSDP-270366-GO-RF Q / to procure cement, nails, Linking More Productive Far Request for Quota Single Stage - One E Pending Impl corrugated iron sheet, paints IDA / 61650 Post Limited 3,500.00 0.00 2021-12-28 2022-01-17 2022-02-16 mers to Markets tions nvelope ementation ,gypsum, electric materials li ke plug, switcher,meshes ET-SR LFSDP-270371-GO-RF Q / to procure cement,nails, Linking More Productive Far Request for Quota Single Stage - One E Under Imple mesh wire, corrugated iron s IDA / 61650 Post Limited 3,500.00 0.00 2021-12-28 2022-01-03 2022-01-17 2022-02-16 mers to Markets tions nvelope mentation heets, paints, gypsum, electr ic materials like wire,plug. ET-SR LFSDP-270372-GO-RF Q / to procure cement,nails, Linking More Productive Far Request for Quota Single Stage - One E Pending Impl mesh wire, corrugated iron s IDA / 61650 Post Limited 3,600.00 0.00 2021-12-28 2022-01-17 2022-02-16 mers to Markets tions nvelope ementation heets, paints, gypsum, electr ic materials like wire,plug. ET-SR LFSDP-270373-GO-RF Q / to procure cement,nails, Linking More Productive Far Request for Quota Single Stage - One E Pending Impl mesh wire, corrugated iron s IDA / 61650 Post Limited 3,200.00 0.00 2021-12-28 2022-01-17 2022-02-16 mers to Markets tions nvelope ementation heets, paints, gypsum, electr ic materials like wire,plug. ET-SR LFSDP-270374-GO-RF Q / to procure cement,nails, Linking More Productive Far Request for Quota Single Stage - One E Under Imple mesh wire, corrugated iron s IDA / 61650 Post Limited 3,300.00 0.00 2021-12-28 2022-06-21 2022-01-17 2022-02-16 mers to Markets tions nvelope mentation heets, paints, gypsum, electr ic materials like wire,plug. ET-SR LFSDP-270376-GO-RF Q / to procure cement,nails, Linking More Productive Far Request for Quota Single Stage - One E Pending Impl mesh wire, corrugated iron s IDA / 61650 Post Limited 3,300.00 0.00 2021-12-28 2022-01-17 2022-02-16 mers to Markets tions nvelope ementation heets, paints, gypsum, electr ic materials like wire,plug. ET-SR LFSDP-270378-GO-RF Q / to procure cement,nails, Linking More Productive Far Request for Quota Single Stage - One E Pending Impl mesh wire, corrugated iron s IDA / 61650 Post Limited 3,200.00 0.00 2021-12-28 2022-01-17 2022-02-16 mers to Markets tions nvelope ementation heets, paints, gypsum, electr ic materials like wire,plug. ET-SR LFSDP-270380-GO-RF Q / to procure cement,nails, Linking More Productive Far Request for Quota Single Stage - One E Pending Impl mesh wire, corrugated iron s IDA / 61650 Post Limited 3,100.00 0.00 2021-12-28 2022-01-17 2022-02-16 mers to Markets tions nvelope ementation heets, paints, gypsum, electr ic materials like wire,plug. Page 5 ET-SR LFSDP-270458-GO-RF Q / to procure cement,nails,p Linking More Productive Far Request for Quota Single Stage - One E Under Imple IDA / 61650 Post Limited 3,400.00 0.00 2021-12-28 2022-06-27 2022-01-17 2022-02-16 aints,wire mesh, gypsum,ele mers to Markets tions nvelope mentation ctric materials like plug, swit cher. ET-SR LFSDP-270459-GO-RF Q / to procure cement,nails, Linking More Productive Far Request for Quota Single Stage - One E Pending Impl mesh wire, corrugated iron s IDA / 61650 Post Limited 3,000.00 0.00 2021-12-28 2022-01-17 2022-02-16 mers to Markets tions nvelope ementation heets, paints, gypsum, electr ic materials like wire,plug. ET-SR LFSDP-270467-GO-RF Q / to procure cement, mesh Linking More Productive Far Request for Quota Single Stage - One E Pending Impl IDA / 61650 Post Limited 3,400.00 0.00 2021-12-28 2022-01-17 2022-02-16 wire, nails, gypsum, electric mers to Markets tions nvelope ementation materials like plug, conduce, switcher. ET-SR LFSDP-275707-GO-RF Strengthening National Instit Single Stage - One E Pending Impl B / to procure forage seeds li IDA / 61650 Post Request for Bids Open - National 101,500.00 0.00 2022-02-02 2022-02-07 2022-03-09 2022-03-16 2022-03-28 2022-04-27 utions and Programs nvelope ementation ke panicum, cowpea, desmo dium, pea ET-SR LFSDP-275709-GO-RF B / to procure milk cans, butt er churner, pullet and chicke n transportation coop,egg col Strengthening National Instit Single Stage - One E Pending Impl IDA / 61650 Post Request for Bids Open - National 103,000.00 0.00 2022-02-01 2022-02-06 2022-03-08 2022-03-13 2022-03-23 2022-04-22 lection tray,weighting balanc utions and Programs nvelope ementation e, strainer,overall,boots,weig hting scale, heart girth, ear t ag applicator, stew pot, plate , bowl,fish transportation cou p,cream separator. ET-SR LFSDP-275984-GO-RF Linking More Productive Far Request for Quota Single Stage - One E Pending Impl Q / to procure desk computer IDA / 61650 Post Limited 11,486.00 0.00 2022-02-06 2022-02-26 2022-03-28 mers to Markets tions nvelope ementation , printer and scanner ET-SR LFSDP-282320-GO-RF Q / to procure cement, corru Linking More Productive Far Request for Quota Single Stage - One E Under Imple IDA / 61650 Post Limited 41,600.00 0.00 2022-03-12 2022-04-08 2022-04-01 2022-05-01 gated sheet, nails, mesh wire mers to Markets tions nvelope mentation , electric materials etc... ET-SR LFSDP-282321-GO-RF Q / to procure cream separat Linking More Productive Far Request for Quota Single Stage - One E Under Imple IDA / 61650 Post Limited 41,500.00 0.00 2022-03-12 2022-06-16 2022-04-01 2022-05-01 or, churner, weighting scale, mers to Markets tions nvelope mentation cooking pan, hand sprayers ET-SR LFSDP-282372-GO-RF Q / to procure cement, corru Linking More Productive Far Request for Quota Single Stage - One E Under Imple IDA / 61650 Post Limited 423,718.00 0.00 2022-03-12 2022-03-21 2022-04-01 2022-05-01 gated iron sheet, nails, electr mers to Markets tions nvelope mentation ic materials, mesh wire ET-SR LFSDP-282375-GO-RF Linking More Productive Far Request for Quota Single Stage - One E Pending Impl Q / to procure wheelbarrow, IDA / 61650 Post Limited 1,200.00 0.00 2022-03-12 2022-04-01 2022-05-01 mers to Markets tions nvelope ementation sickle, rake, hoe, spade ET-SR LFSDP-292613-CW-RF Strengthening National Instit Request for Quota Single Stage - One E Pending Impl Q / to procure water pump wi IDA / 61650 Post Limited 40,000.00 0.00 2022-05-15 2022-06-05 2022-07-05 utions and Programs tions nvelope ementation th installation. ET-SR LFSDP-297850-GO-RF Strengthening National Instit Request for Quota Single Stage - One E Under Imple Q / to procure Spectro photo IDA / 61650 Post Limited 8,200.00 0.00 2022-06-06 2022-06-07 2022-06-27 2022-07-27 utions and Programs tions nvelope mentation meter , nets, cylinder gage ET-SR LFSDP-297851-GO-RF Strengthening National Instit Request for Quota Single Stage - One E Under Imple IDA / 61650 Post Limited 5,100.00 0.00 2022-06-06 2022-06-10 2022-06-27 2022-07-27 Q / to procure fishing boat utions and Programs tions nvelope mentation ET-SR LFSDP-297852-GO-RF Strengthening National Instit Request for Quota Single Stage - One E Under Imple IDA / 61650 Post Limited 6,000.00 0.00 2022-06-06 2022-06-02 2022-06-27 2022-07-27 Q / to procure boat propeller utions and Programs tions nvelope mentation ET-SR LFSDP-297853-GO-DI Strengthening National Instit Pending Impl IDA / 61650 Post Direct Selection Direct 4,100.00 0.00 2022-06-05 2022-06-10 2022-07-04 2022-08-03 R / to procure concentrated f utions and Programs ementation eed for fish ET-SR LFSDP-298424-GO-RF Strengthening National Instit Request for Quota Single Stage - One E Pending Impl IDA / 61650 Post Limited 2,800.00 0.00 2022-06-11 2022-07-01 2022-07-30 Q / to procure Doyogena ram utions and Programs tions nvelope ementation ET-SR LFSDP-298426-GO-RF Strengthening National Instit Request for Quota Single Stage - One E Pending Impl IDA / 61650 Post Limited 3,800.00 0.00 2022-06-11 2022-07-01 2022-07-31 Q / to procure Bonga sheep utions and Programs tions nvelope ementation ET-SR LFSDP-298428-GO-RF Strengthening National Instit Request for Quota Single Stage - One E Pending Impl IDA / 61650 Post Limited 5,900.00 0.00 2022-06-11 2022-07-01 2022-07-31 Q / to procure Abera sheep utions and Programs tions nvelope ementation ET-SR LFSDP-308143-GO-RF B / To procure veterinary fiel d equipment and laboratory materials such as field equip Strengthening National Instit Single Stage - One E Pending Impl IDA / 61650 Post Request for Bids Open - National 101,000.00 0.00 2022-08-24 2022-08-29 2022-09-03 2022-09-08 2022-09-18 2022-10-18 ment: glove, vaccination nee utions and Programs nvelope ementation dle, AI gun, alcohol, syringe, CMT kit reagent, cannula; bu rdizo, Rx syringe ,vaccination needle, iodin. ET-SR LFSDP-311846-GO-RF Q / to procure hormone sync Strengthening National Instit Request for Quota Single Stage - One E Pending Impl hrumate, plastic apron, plasti IDA / 61650 Post Limited 10,200.00 0.00 2022-08-29 2022-09-18 2022-10-18 utions and Programs tions nvelope ementation c funnel, sheath, permanent ear tag, thermos flask, alcoh ol ET-SR LFSDP-325864-GO-RF Q / to procure feeding trough Linking More Productive Far Request for Quota Single Stage - One E Pending Impl , watering trough, eggs colle IDA / 61650 Post Limited 30,100.00 0.00 2022-11-14 2022-12-04 2023-01-03 mers to Markets tions nvelope ementation ction tree, chicken transport crate, spray for disinfection ET-SR LFSDP-325865-GO-RF Linking More Productive Far Request for Quota Single Stage - One E Pending Impl IDA / 61650 Post Limited 16,000.00 0.00 2022-11-14 2022-12-06 2023-01-05 Q / to procure generator, sola mers to Markets tions nvelope ementation r ET-SR LFSDP-325670-GO-RF Linking More Productive Far Request for Quota Single Stage - One E Pending Impl IDA / 61650 Post Limited 3,000.00 0.00 2022-11-14 2022-12-04 2023-01-03 Q / to procure water tanker mers to Markets tions nvelope ementation ET-SR LFSDP-325680-GO-RF Strengthening National Instit Request for Quota Single Stage - One E Pending Impl Q / to procure computers,pri IDA / 61650 Post Limited 38,600.00 0.00 2022-11-14 2022-12-04 2023-01-03 utions and Programs tions nvelope ementation nters and LCD projectors Page 6 ET-SR LFSDP-325825-GO-RF Linking More Productive Far Request for Quota Single Stage - One E Pending Impl Q / to procure lacto scan, lact IDA / 61650 Post Limited 12,140.00 0.00 2022-11-15 2022-12-05 2023-01-04 mers to Markets tions nvelope ementation o meter, milk canes ET-SR LFSDP-325829-GO-RF Linking More Productive Far Request for Quota Single Stage - One E Pending Impl IDA / 61650 Post Limited 14,000.00 0.00 2022-11-15 2022-12-05 2023-01-04 Q / to procure deep refrigerat mers to Markets tions nvelope ementation ors ET-SR LFSDP-325834-GO-RF Linking More Productive Far Request for Quota Single Stage - One E Pending Impl Q / to procure detergent, glo IDA / 61650 Post Limited 11,600.00 0.00 2022-11-15 2022-12-05 2023-01-04 mers to Markets tions nvelope ementation ves, alcohol, boots, overalls ET-SR LFSDP-326050-GO-RF Q / to procure cement blocks, Linking More Productive Far Request for Quota Single Stage - One E Pending Impl cement, iron, galvanized iron IDA / 61650 Post Limited 149,450.00 0.00 2022-11-16 2022-12-08 2023-01-07 mers to Markets tions nvelope ementation sheet, nails, mesh wire, cond uit, electric wire, cables ET-SR LFSDP-326055-GO-RF Q / to procure cement, metal, Linking More Productive Far Request for Quota Single Stage - One E Pending Impl IDA / 61650 Post Limited 66,388.00 0.00 2022-11-16 2022-12-06 2023-01-05 metal pipe, PVC, valves, corr mers to Markets tions nvelope ementation ugated sheet, nails, mesh wir e ET-SR LFSDP-340705-GO-RF Linking More Productive Far Single Stage - One E Pending Impl IDA / 61650 Post Request for Bids Open - National 192,000.00 0.00 2023-02-07 2023-02-12 2023-03-14 2023-03-21 2023-03-31 2023-06-14 B / to procure trucks mers to Markets nvelope ementation ET-SR LFSDP-358139-GO-RF Linking More Productive Far Request for Quota Single Stage - One E Pending Impl Q / to procure cement, nails, IDA / 61650 Post Limited 46,400.00 0.00 2023-04-29 2023-05-19 2023-06-18 mers to Markets tions nvelope ementation mesh wire, PVC ET-SR LFSDP-358142-GO-RF Linking More Productive Far Request for Quota Single Stage - One E Pending Impl Q / to procure cement,nails, IDA / 61650 Post Limited 178,000.00 0.00 2023-04-29 2023-05-19 2023-06-18 mers to Markets tions nvelope ementation mesh wire, pipe, pvc ET-SR LFSDP-360562-GO-RF Linking More Productive Far Request for Quota Single Stage - One E Pending Impl IDA / 61650 Post Limited 46,000.00 0.00 2023-05-13 2023-06-22 2023-09-19 Q / to procure chiller mers to Markets tions nvelope ementation NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 7 Sample Procurement Plan Regional Disease Surveillance Systems Enhancement (REDISSE)(P154807) I. General 1. Bank’s approval Date of the procurement Plan [Original: July 2016]: Revision 1of Updated Procurement Plan, January 5th 2017 2. Date of General Procurement Notice: Dec 27, 2016 3. Period covered by this procurement plan: The procurement period of project covered from year March to December 2017 II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Prior Review Type of procurement Threshold US$ Works (including turnkey, supply & US$ 10 million installation of plant and equipment, and PPP) Goods, information technology and non- US$ 2 million consulting services 2. Prequalification. Bidders for _Not applicable_ shall be prequalified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines. 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: not applicable 4. Reference to (if any) Project Operational/Procurement Manual: Project Implementation Manual for World Bank Loan Project issued by WAHO 5. Any Other Special Procurement Arrangements: Not applicable 6. Summary of the Procurement Packages planned during the first 18 months after project effectiveness ( including those that are subject to retroactive financing and advanced procurement) [List the Packages which require Bank’s prior review first and then the other packages] 1 2 3 4 5 6 7 4/4/2017 Ref. Descripti Estimat Packages Dome Review Comme No. on ed stic by Bank nts Cost Prefe (Prior / US$ rence Post) million (yes/ no) Summary 0.14 1 No Post of the NCB (Goods) III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Type of procurement Prior Review Threshold US$ Consultants: firms US$ 1 million Consultants: individuals US$ 0.3 million 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_200,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: not applicable 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 Ref. No. Description Estimat Package Review Comments of ed s by Bank Assignmen Cost (Prior / t US$ Post) million Summary 3.995 2 Prior of number of contracts that will be let under QCB Summary 0.22 2 Post Market of number approach: of Open 4/4/2017 contracts Internatio that will nal be let under CQS 4/4/2017 PROCUREMENT Western and Central Africa : Regional Disease Surveillance Systems Enhancement (REDISSE) PLAN General Information Country: Western and Central Africa 2017-11-30 Bank’s Approval Date of the Original Procurement Plan: 2023-06-02 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P154807 GPN Date: Project Name: Regional Disease Surveillance Systems Enhancement (REDISSE) Loan / Credit No: IDA / 58830, IDA / D1300 MoH-GUI - PROJET D'AMELIORATION DES SERVICES DE SANTE PRIMAIRES Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GN-PASSP-28085-CW-RFB / Rénovation des locaux des la Component 2: Strengthening Single Stage - One E 2019-03-3 IDA / 58830 Post Request for Bids Open - National 228,000.00 208,518.20 Signed 2018-06-12 2018-12-10 2018-06-17 2018-12-13 2018-07-29 2019-01-06 2018-08-28 2019-04-01 2018-10-02 2019-05-31 boratoires de Fièvres Hémor of Laboratory Capacity nvelope 1 agique et INSP/LNR GN-PASSP-28113-CW-RFB / Component 2: Strengthening Open - Internationa Single Stage - One E Under Imple 2019-08-2 Construction d'un Laboratoir IDA / 58830 Post Request for Bids 1,400,000.00 0.00 2018-05-10 2019-05-09 2018-05-15 2019-05-13 2018-06-26 2018-07-26 2018-08-30 of Laboratory Capacity l nvelope mentation 6 e natioal de diagnostic vétéri naire niveau P2 GN-PASSP-28114-CW-RFQ / Component 2: Strengthening Request for Quota Single Stage - One E 2018-11-1 Construction de cinq (5) Post IDA / 58830 Post Limited 150,000.00 93,205.36 Signed 2018-06-17 2018-12-06 2018-08-12 2019-03-26 of Laboratory Capacity tions nvelope 2 es d'Inspection Frontaliers (PI F) GN-PASSP-42811-CW-RFB / Component 5: Institutional C Recrutement d'une entrepris apacity Building, Project Ma Single Stage - One E Under Imple 2019-02-2 e pour la construction du bâti IDA / 58830 Post Request for Bids Open - National 220,000.00 0.00 2018-04-29 2018-11-20 2018-05-04 2018-11-26 2018-06-15 2018-07-15 2018-08-28 nagement, Coordination, an nvelope mentation 4 ment administratif R+2 pour d Advocacy abriter le siège de l'UGP REDI SSE et PASSP GN-MOH-GUI-172593-CW-RF Q / Travaux de rénovation de Component 2: Strengthening Request for Quota Single Stage - One E 2021-02-2 s locaux du laboratoire de l'I IDA / 58830 Post Limited 65,000.00 55,214.54 Signed 2020-09-29 2020-07-14 2020-11-24 2020-11-13 of Laboratory Capacity tions nvelope 2 NSP (remise en état de la plo mberie sanitaire, de l'électric ité, la peinture, etc. ) GN-MOH-GUI-326595-CW-RF Q / Aménagement et mise à niveau des Postes d'Inspectio Request for Quota n Frontalier (PIF) des Service Component 1: Surveillance a Request for Quota Single Stage - One E Pending Imp 2023-05-1 IDA / 58830 Post Limited tions (Non Bank-S 87,500.00 0.00 2022-12-24 2023-02-18 s Vétérinaire en deux lots : lo nd Information Systems tions nvelope lementation 9 PD) t 1 : Installation de 4 forages solaires et Lot 2 : Installation de 5 latrines de deux blocs c hacun pour les PIF. GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GN-PASSP-28033-GO-RFB / A Component 1: Surveillance a Single Stage - One E Under Imple cquisition de neuf (9) véhicul IDA / 58830 Prior Request for Bids Open - National 270,000.00 0.00 2017-10-17 2017-10-22 2017-12-03 2018-01-02 2018-02-15 2018-05-16 nd Information Systems nvelope mentation es 4x4 Pick-up double cabine s GN-PASSP-28034-GO-RFB / A cquisition de quatre-vingt-dix Component 1: Surveillance a Single Stage - One E IDA / 58830 Post Request for Bids Open - National 450,000.00 166,038.69 Completed 2017-10-17 2018-01-08 2017-10-22 2018-02-01 2017-12-03 2018-02-15 2018-01-02 2018-03-02 2018-02-15 2018-05-15 2018-05-16 2018-10-01 (90) motos tout terrain en fa nd Information Systems nvelope veur des Agents du REMAGUI GN-PASSP-28035-GO-RFQ / Component 4: Human Resou Acquisition de matériel infor rce Management for Effectiv Request for Quota Single Stage - One E matique et de reprographie e IDA / 58830 Post Limited 98,000.00 96,595.73 Completed 2017-10-28 2017-12-18 2017-12-23 2018-01-29 2018-01-22 2018-11-23 e Disease Surveillance and E tions nvelope n faveur du personnel de l'U pidemic Preparedness. GP et de la Santé Animale GN-PASSP-28036-GO-RFQ / Component 4: Human Resou Acquisition et installation de rce Management for Effectiv Request for Quota Single Stage - One E IDA / 58830 Post Limited 98,500.00 97,497.48 Completed 2017-10-28 2017-12-18 2017-12-23 2018-01-23 2018-01-22 2017-09-27 mobilier de bureau en faveur e Disease Surveillance and E tions nvelope de l'UGP et la santé animale pidemic Preparedness. GN-PASSP-28043-GO-RFQ / E quipement du Laboratoire pé Component 2: Strengthening Request for Quota Single Stage - One E IDA / 58830 Post Limited 45,000.00 16,750.89 Signed 2017-12-02 2018-04-03 2018-01-27 2018-05-08 2018-02-26 dagogique en matériel de lab of Laboratory Capacity tions nvelope o pour l'Institut vétérinaire d e Dalaba GN-PASSP-28065-GO-RFB / A cquisition du matériel de dia gnostic des maladies à poten Component 2: Strengthening Request for Quota Single Stage - One E Under Imple tiel épimédique d'origine bac IDA / 58830 Post Limited 84,100.00 0.00 2017-12-01 2018-06-21 2018-01-26 2018-03-27 of Laboratory Capacity tions nvelope mentation térienne et virale ainsi que d es consommables et réactif p our les 2 laboratoires de réfé rence (INSP/LNR et LFH GN-PASSP-28081-GO-RFQ / Acquisition de matériels, con Component 2: Strengthening Single Stage - One E sommables et réactif de diag IDA / 58830 Post Request for Bids Open - National 354,400.00 921,516.93 Signed 2017-11-22 2018-10-25 2017-11-27 2018-10-29 2018-01-08 2019-01-25 2018-02-07 2019-03-11 2018-03-14 2019-06-03 2018-06-12 of Laboratory Capacity nvelope nostic pour les laboratoires a u niveau régional, préfectoral et communautaires GN-PASSP-28467-GO-RFQ / P roduction et édition des outil s de gestion pour les centres de surveillance animale et en Component 1: Surveillance a Request for Quota Single Stage - One E IDA / 58830 Post Limited 35,000.00 21,853.48 Completed 2017-12-23 2018-03-25 2018-02-17 2018-06-27 2018-03-19 2018-08-28 vironnementale en (registres nd Information Systems tions nvelope et notification, fiches de notif ication, fiches d'investigation , fiches de suivi, fiches de col lecte des informations/déclar ation, etc.) GN-PASSP-28472-GO-RFB / A cquisition et instalation de h Component 1: Surveillance a Single Stage - One E uit (8) incinérateurs pour les IDA / 58830 Post Request for Bids Open - National 320,000.00 449,180.26 Signed 2018-04-16 2018-09-18 2018-04-21 2018-09-24 2018-06-02 2018-10-30 2018-07-02 2018-12-24 2018-08-15 2019-05-10 2019-02-11 nd Information Systems nvelope établissements de soins (cen tres de santé et hopitaux) Page 1 GN-PASSP-28500-GO-RFB / A chat, transport et installation de 456 kits solaires dont : Component 1: Surveillance a Open - Internationa Single Stage - One E Under Imple IDA / D1300 Prior Request for Bids 1,620,000.00 0.00 2018-08-13 2019-10-08 2018-08-18 2018-09-29 2018-10-29 2018-12-03 2019-06-01 - 410 pour les Centre de sa nd Information Systems l nvelope mentation ntés - 38 pour les DPS et - 8 pour les DRS GN-PASSP-28570-GO-RFB / A cquisition de VSAT pour les b Component 1: Surveillance a Single Stage - One E IDA / 58830 Post Request for Bids Open - National 399,000.00 188,833.15 Completed 2018-05-21 2019-01-21 2018-05-26 2019-01-22 2018-07-07 2019-02-26 2018-08-06 2019-03-07 2018-09-10 2019-07-17 2018-12-09 2020-09-15 ureaux de la Division Prévent nd Information Systems nvelope ion et Lutte contre la Maladie ainsi que les DRS GN-PASSP-28462-GO-RFQ / Achat de kit de surveillance Component 1: Surveillance a Request for Quota Single Stage - One E (vélos, bottes, imperméables IDA / 58830 Post Limited 42,000.00 36,810.15 Signed 2018-05-26 2019-12-20 2018-07-21 2020-03-03 2018-08-20 nd Information Systems tions nvelope , stylos, sac à dos, etc.) pour les Agents Communautaires GN-PASSP-28040-GO-RFQ / Contrat avec VDC Télécom p our la fourniture et l'installati on de connexion Internet et l' Component 1: Surveillance a IDA / 58830 Post Direct Selection Direct 48,000.00 17,099.10 Signed 2018-03-26 2018-03-05 2018-03-31 2018-03-12 2018-05-07 2018-03-26 2018-06-06 assistance technique pour la nd Information Systems Direction Nationale des Servi ces Vétérinaires. VDC est re cruté par le PASSP pour la fo urniture de la connexion Inte rnet de l'UGP. MOF-REF-02 / Acquisition de 9 véhicules 4x4 Pick-up doub le cabines Tout Terrain dont Component 1: Surveillance a Single Stage - One E IDA / 58830 Post Request for Bids Open - National 270,000.00 229,313.12 Completed 2017-12-17 2018-01-08 2017-12-22 2018-02-02 2018-02-15 2018-03-04 2018-03-02 2018-04-08 2018-05-15 2018-07-07 2018-10-01 1 véhicule pour la santé hum nd Information Systems nvelope aine, 7 pour la santé animale et 1 véhicule pour le SE/Unité de Gestion du Projet GN-PASSP-28048-GO-RFB / A chat de 410 tablettes pour l Component 1: Surveillance a Request for Quota Single Stage - One E a suveillance au niveau com IDA / 58830 Post Limited 85,000.00 81,736.20 Signed 2019-01-27 2019-08-06 2019-03-24 2019-10-03 2019-05-23 nd Information Systems tions nvelope munautaire pour la Direction Nationale des Services Vétéri naires (santé animale) GN-PASSP-28108-GO-RFB / A chat de chaîne de froid (solai re) et matériel de prélèveme Component 1: Surveillance a Single Stage - One E Pending Impl IDA / 58830 Post Request for Bids Open - National 250,000.00 0.00 2019-03-26 2019-03-31 2019-05-12 2019-06-11 2019-07-16 2019-09-14 nt pour le renforcement des nd Information Systems nvelope ementation unités mobiles de santé anim ale de Kankan et de Labé, Ki ndia et N'Zérékoré GN-PASSP-65629-GO-RFQ / Acquisition de 4 véhicules Pic k-up double cabines 4x4 dont : 1 véhicule pour le laboratoir Component 1: Surveillance a Single Stage - One E Under Imple IDA / 58830 Post Request for Bids Open - National 120,000.00 0.00 2019-02-14 2019-04-22 2019-02-19 2019-04-30 2019-04-02 2019-05-02 2019-06-06 2019-12-03 e central de diagnostic (sant nd Information Systems nvelope mentation é animale), 2 véhicules pour l a Direction de l'Environneme nt et 1 véhicule pour la super vision des laboratoires du rés eau (INSP). GN-PASSP-79450-GO-RFB / A chat de 410 tablettes en fave Component 1: Surveillance a Single Stage - One E Pending Impl ur des structures déconcentr IDA / 58830 Post Request for Bids Open - National 460,000.00 0.00 2019-03-27 2019-04-01 2019-05-13 2019-06-12 2019-07-17 2020-01-13 nd Information Systems nvelope ementation ées de la Direction Nationale des Services Vétérinaires GN-PASSP-92792-GO-DIR / C ontrat avec MERIAL France p our la fourniture 7000 flacon s de vaccins Aftovax O A SAT Component 1: Surveillance a IDA / 58830 Prior Direct Selection Direct 700,000.00 724,000.00 Signed 2019-01-28 2019-02-07 2019-02-02 2019-04-10 2019-03-09 2019-05-02 2019-09-05 1 SAT2 (souches O manisa, O nd Information Systems 3039, A Saudi 95, SAT1 et SA T2 Eri) en flacons de 50 dose s, soit l'équivalent de 350 00 0 doses pour la fièvre aphteu se GN-PASSP-92796-GO-RFQ / Acquisition de huit (8) chaine Component 1: Surveillance a Request for Quota Single Stage - One E IDA / 58830 Post Limited 65,000.00 50,579.12 Signed 2019-01-27 2019-02-04 2019-03-24 2019-04-25 2019-05-08 s de froids solaires (Réfrigéra nd Information Systems tions nvelope teur-congélateur) pour la fièv re aphteuse GN-PASSP-92949-GO-RFQ / Acquisition de produits vétéri naire dont : 160 Portes vacci Component 1: Surveillance a Request for Quota Single Stage - One E IDA / 58830 Post Limited 55,000.00 52,361.08 Completed 2019-01-27 2019-02-04 2019-03-24 2019-03-29 2019-05-08 2019-06-06 ns genre UNICEF, 165 Sering nd Information Systems tions nvelope ues automatiques, 4 kits de diagnostic 1 kit de 250 tests pour la fièvre aphteuse GN-PASSP-94044-GO-RFQ / P Component 5: Institutional C restataire de service pour l'a apacity Building, Project Ma Request for Quota Single Stage - One E IDA / 58830 Post Limited 40,000.00 2,021.80 Signed 2019-04-05 2018-11-05 2019-05-31 2018-12-24 2021-05-30 cquisition de fournitures de nagement, Coordination, an tions nvelope bureau par marché à comma d Advocacy nde GN-PASSP-115253-GO-RFB / Acquisition de 100 motocycle Component 1: Surveillance a Single Stage - One E Pending Impl IDA / 58830 Post Request for Bids Open - National 230,000.00 0.00 2019-12-23 2019-12-28 2020-02-08 2020-03-09 2020-04-13 2020-06-12 ttes complémentaires pour l nd Information Systems nvelope ementation es Agents du REMAGUI GN-PASSP-115258-GO-RFQ / Acquisition du matériel infor Component 5: Institutional C matique en faveur de la direc apacity Building, Project Ma Request for Quota Single Stage - One E tion de l'OGUIPAR, des 4 UMS IDA / 58830 Post Limited 75,000.00 60,185.82 Terminated 2019-10-05 2020-08-05 2019-11-30 2020-03-28 2020-01-14 nagement, Coordination, an tions nvelope A, de la DNGELM et de la D d Advocacy NSV ainsi que l'acquisition d' un photocopieur grand modè le et une imprimante pour l'U GP GN-PASSP-115277-GO-RFQ / Acquisition de mobilier de bu reau pour de la direction de l' Component 1: Surveillance a Request for Quota Single Stage - One E IDA / 58830 Post Limited 45,000.00 57,124.84 Signed 2019-10-29 2019-09-05 2019-12-24 2019-10-26 2020-01-23 Office Guinéen des Parcs et nd Information Systems tions nvelope Réserves (OGUIPAR), des 4 U nités Mobiles de Santé Anima le (UMSA) GN-PASSP-118159-GO-RFQ / Achat de chaîne de froid (sol aire) et matériel de prélèvem Component 1: Surveillance a Request for Quota Single Stage - One E IDA / 58830 Post Limited 85,000.00 67,872.75 Signed 2019-11-03 2019-10-03 2019-12-29 2019-12-11 2020-02-27 ent pour le renforcement des nd Information Systems tions nvelope unités mobiles de santé anim ale de Kankan et de Labé, Ki ndia et N'Zérékoré Page 2 GN-PASSP-119939-GO-RFQ / Achat de matériel de commu Component 1: Surveillance a Request for Quota Single Stage - One E nication : 300 smartphones p IDA / 58830 Post Limited 95,000.00 85,464.60 Signed 2020-02-17 2019-08-06 2020-04-13 2019-09-30 2020-06-12 nd Information Systems tions nvelope our les Agents du niveau co mmunautaire de la santé ani male GN-PASSP-120478-GO-RFB / Acquisition des kits d'urgenc Component 1: Surveillance a Open - Internationa Single Stage - One E Under Imple e et de riposte dans les quinz IDA / 58830 Prior Request for Bids 575,000.00 0.00 2020-01-23 2019-10-28 2020-01-28 2019-11-04 2020-03-10 2020-04-09 2020-05-14 2020-08-12 nd Information Systems l nvelope mentation e (15) districts sanitaires pou r la santé humaine, animale et environnementale GN-MOH-GUI-141032-GO-DI R / Acquisition d'un véhicule Component 1: Surveillance a IDA / 58830 Post Direct Selection Direct 25,000.00 24,097.19 Signed 2019-11-20 2019-11-11 2019-11-25 2019-11-11 2020-01-04 2019-11-26 2020-02-03 Pick-up double cabines 4x4 t nd Information Systems out terrain en faveur du Mini stère de l'Elevage GN-MOH-GUI-141978-GO-DI R / Accord avec UNOPS pour l Component 1: Surveillance a 'achat de 102 motocyclettes IDA / 58830 Post Direct Selection Direct 305,727.00 305,727.00 Completed 2019-12-10 2019-11-08 2019-12-15 2019-07-19 2020-01-19 2020-02-21 2020-08-08 2021-09-15 nd Information Systems YAMAHA AG 100 complémen taires pour les Agents du RE MAGUI GN-MOH-GUI-165522-GO-UN / Acquisition des équipement Component 1: Surveillance a UN Agencies (Dire s de protection individuelle e IDA / 58830 Prior Direct 1,550,000.00 1,947,962.00 Signed 2020-04-10 2020-03-24 2020-04-15 2020-03-31 2020-05-20 2020-04-08 2020-11-16 nd Information Systems ct) t des kits d'hygiène avec UNI CEF pour l'urgence sanitaire du COVID 19 GN-MOH-GUI-165546-GO-UN / Acquisition de logiciel GO D ATA, du matériel de réanimat Component 2: Strengthening UN Agencies (Dire IDA / 58830 Prior Direct 1,900,000.00 1,600,792.00 Signed 2020-04-13 2020-03-26 2020-04-18 2020-03-30 2020-05-23 2020-04-08 2020-11-19 ion, matériel et intrant de lab of Laboratory Capacity ct) oratoire avec OMS pour l'Urg ence sanitaire du COVID 19 GN-MOH-GUI-167247-GO-UN / Convention pour la fournitur e du matériel roulant (véhicul Component 1: Surveillance a UN Agencies (Dire IDA / 58830 Post Direct 600,000.00 735,197.00 Signed 2020-04-28 2020-04-03 2020-05-03 2020-04-03 2020-06-07 2020-05-06 2020-12-04 es et Ambulances) pour la ré nd Information Systems ct) ponse à la Pandémie de COVI D-19 En République de Guiné e avec UNICEF GN-MOH-GUI-171668-GO-DI R / Acquisition des matériels et consommables pour l'exte Component 1: Surveillance a nsion de deux (2) CT-EPI (Ke IDA / 58830 Post Direct Selection Direct 375,000.00 512,805.31 Completed 2020-05-20 2020-05-04 2020-05-25 2020-05-04 2020-06-29 2020-05-20 2020-08-28 2020-06-09 nd Information Systems nien et Gbessia) de Conakry pour la riposte au COVID 19 en entente directe avec la So ciété 2HK Equipements et Se rvices GN-MOH-GUI-172561-GO-RF Q / Acquisition de kits de sur veillance (registres de notific Component 1: Surveillance a Request for Quota Single Stage - One E ation, Bottes, Imperméables, IDA / 58830 Post Limited 45,000.00 33,157.09 Completed 2020-09-26 2020-06-18 2020-11-21 2020-08-05 2020-12-21 2020-09-03 nd Information Systems tions nvelope Stylos, Sac à dos et torches) pour les 270 conservateurs de la nature pour l'Environne ment GN-MOH-GUI-172563-GO-RF Q / Acquisition et installation de 8 chaînes de froid solaire Component 1: Surveillance a Request for Quota Single Stage - One E en faveur des 3 Direction Pré IDA / 58830 Post Limited 98,000.00 91,960.31 Completed 2020-10-03 2020-07-10 2020-11-28 2020-09-22 2021-01-27 2021-04-21 nd Information Systems tions nvelope fectorales de l'Elevage et Postes d'Inspections Frontali ers (PIFs) GN-MOH-GUI-172567-GO-RF Q / Acquisition de kits de prél èvement dans le cadre de la Component 2: Strengthening Request for Quota Single Stage - One E IDA / 58830 Post Limited 30,000.00 29,555.43 Completed 2020-10-10 2021-01-25 2020-12-05 2021-03-20 2021-03-05 2021-06-23 surveillance des maladies Zo of Laboratory Capacity tions nvelope onotiques par le REMAGUI po ur les 33 Directions Préfector ales de l’Élevage GN-MOH-GUI-172568-GO-RF Q / Acquisition et installation du matériel informatique (34 Component 1: Surveillance a Request for Quota Single Stage - One E IDA / 58830 Post Limited 95,000.00 54,405.30 Completed 2020-10-17 2020-07-02 2020-12-12 2020-09-03 2021-02-10 2020-10-08 ordinateurs fixes et 38 impri nd Information Systems tions nvelope mantes multifonction) pour l es 34 services vétérinaires pr éfectoraux GN-MOH-GUI-172570-GO-UN / Acquisition des équipement s, consommables et réactifs Component 2: Strengthening UN Agencies (Dire Pending Impl pour les laboratoires de l'INS IDA / 58830 Post Direct 686,239.00 0.00 2020-10-20 2020-10-25 2020-11-29 2021-11-29 of Laboratory Capacity ct) ementation P, de LFH, du LCVD, des 3 hô pitaux Nationaux, régionaux, préfectoraux et Centres de s anté en entente directe avec UNICEF GN-MOH-GUI-172573-GO-RF Q / Acquisition de 3 motocyc Component 2: Strengthening Request for Quota Single Stage - One E lettes tout terrain de liaison IDA / 58830 Post Limited 12,000.00 7,890.21 Completed 2020-07-18 2020-05-11 2020-09-12 2020-06-12 2020-10-12 2020-07-22 of Laboratory Capacity tions nvelope pour le transport des échantil lons en faveur du laboratoire de l'INSP GN-MOH-GUI-172581-GO-RF Q / Achat de 13 Ordinateurs portables pour le personnel d Component 5: Institutional C 'Appui dont : 1 Assistante CN apacity Building, Project Ma Request for Quota Single Stage - One E , 3 Secrétaires, 1 APM, 5 Com IDA / 58830 Post Limited 36,000.00 20,943.15 Completed 2020-06-30 2020-05-15 2020-08-25 2020-06-05 2020-10-24 2021-06-16 nagement, Coordination, an tions nvelope ptables, 1 Auditeur Interne, 1 d Advocacy Consultant Communication, 1 Sauvegarde Sociale) et ac cessoires (6 Disque Externe de 1 Téra, 6 Casques, 6 Pack sT GN-MOH-GUI-172584-GO-RF Q / Achat de Kits de Lavage d es Mains et Savons pour la s anté humaine, animale et en Component 1: Surveillance a Request for Quota Single Stage - One E IDA / 58830 Post Limited 10,000.00 10,549.21 Completed 2020-06-30 2020-07-28 2020-08-25 2020-09-10 2020-09-24 2020-11-03 vironnementale (10 000 Kits nd Information Systems tions nvelope 30 000 morceaux de Savons) , Kit de protection individuell e (masque, gel Hydroalcooliq ue) et 50 Thermoflash Page 3 GN-MOH-GUI-172609-GO-RF Q / Acquisition et installation de 2 chambres froides 1 à te Component 2: Strengthening Request for Quota Single Stage - One E IDA / 58830 Post Limited 95,000.00 93,915.12 Completed 2020-11-10 2020-06-22 2021-01-05 2020-08-27 2021-03-06 2021-05-18 mpérature positive et l'autre of Laboratory Capacity tions nvelope à température négative pour le laboratoire de la Direction Nationale de l'Elevage (DNSV ) GN-MOH-GUI-174571-GO-DI R / acquisition des écouvillon s avec milieux de transport e Component 2: Strengthening IDA / 58830 Post Direct Selection Direct 105,000.00 105,000.00 Terminated 2020-06-30 2020-05-25 2020-07-05 2020-05-26 2020-08-09 2020-07-02 2020-09-23 n Turquie avec la Société SE of Laboratory Capacity NTROMER DNA TEKNOLOLEJI LERI Ltd. Sti pour l'urgence s anitaire du COVID 19 GN-MOH-GUI-174841-GO-DI R / Acquisition du matériel ro ulant dont 10 Pick-up 4x4 do uble cabines et 10 Minibus 1 Component 1: Surveillance a IDA / 58830 Post Direct Selection Direct 620,000.00 648,781.95 Terminated 2020-06-07 2020-05-27 2020-06-12 2020-05-28 2020-07-17 2020-07-09 2020-08-16 5 places en faveur de l'Agenc nd Information Systems e Nationale de Sécurité Sanit aire (ANSS) avec ETOILE MOT ORS GUINÉE pour la riposte d u COVID 19 GN-MOH-GUI-190064-GO-DI R / Acquisition des équipeme Component 1: Surveillance a nts de protection individuelle IDA / 58830 Post Direct Selection Direct 1,160,000.00 915,811.30 Completed 2020-09-30 2020-09-04 2020-10-05 2020-09-14 2020-11-09 2020-11-20 2020-12-24 2021-02-25 nd Information Systems et matériels sanitaires en fav eur des CTEPI avec AFRICA H EALTH CARE PHARMA Sarl GN-MOH-GUI-190072-GO-DI R / Acquisition des médicame Component 1: Surveillance a nts, kits d'hygiène et kits de IDA / 58830 Prior Direct Selection Direct 4,300,000.00 3,836,726.37 Signed 2020-09-28 2020-10-14 2020-10-03 2020-11-23 2020-11-07 2021-02-25 2021-02-05 nd Information Systems protection individuelle en fav eur des CTEPI avec la SOGUI PREM GN-MOH-GUI-189601-GO-DI R / Fourniture et installation Component 1: Surveillance a de deux (2) Chapiteaux avec IDA / 58830 Post Direct Selection Direct 509,129.00 497,125.60 Completed 2020-10-19 2020-09-24 2020-10-24 2020-09-24 2020-11-28 2020-11-18 2021-01-27 2021-01-12 nd Information Systems la Pâtisserie 2 Octobre pour l a lutte contre la pandémie de coronavirus en Guinée GN-MOH-GUI-189603-GO-DI R / Achat de 80.000 tests rap Component 1: Surveillance a ides COVID-19 avec le fourni IDA / 58830 Post Direct Selection Direct 879,200.00 899,671.42 Completed 2020-10-19 2020-09-24 2020-10-24 2020-09-30 2020-11-28 2020-11-18 2021-01-12 2021-02-05 nd Information Systems sseur LAMART MD/TT, sis au Quartier Dixinn, Conakry, Ré publique de Guinée GN-PASSP-120447-GO-RFQ / Acquisition des réactifs et co nsommables pour les apparei Component 2: Strengthening Request for Quota Single Stage - One E Under Imple IDA / 58830 Post Limited 85,000.00 0.00 2021-09-29 2022-07-07 2021-11-24 2022-01-08 ls VIDAS des 7 HR dans le ca of Laboratory Capacity tions nvelope mentation dre de la surveillances des M aladies à potentiel épidémiqu e GN-PASSP-28110-GO-RFQ / Acquisition des kits de diagn ostic moléculaire (amorces) d es maladies prioritaires y co Component 2: Strengthening Request for Quota Single Stage - One E IDA / 58830 Post Limited 95,800.00 108,584.46 Signed 2021-10-30 2021-06-07 2021-12-25 2021-12-23 2022-03-25 mpris les zoonoses et équipe of Laboratory Capacity tions nvelope ments (3 chaines Elisa) et ré actifs pour les laboratoires ré gionaux et central vétérinair e et des Kits PCR pour l'ISSM V GN-PASSP-28083-GO-RFQ / Acquisition de deux (2) incin Component 2: Strengthening Request for Quota Single Stage - One E Pending Impl érateurs solaires en faveur d IDA / 58830 Post Limited 45,600.00 0.00 2021-10-05 2021-11-30 2022-01-14 of Laboratory Capacity tions nvelope ementation es hôpitaux préfectoraux de Dalaba et de Macenta é GN-PASSP-28561-GO-RFQ / Achat, transport et installatio n de chaines de froid solaire 8 zones d'élevage: Ditinn (Da Component 1: Surveillance a Request for Quota Single Stage - One E IDA / 58830 Post Limited 98,500.00 106,407.31 Signed 2018-08-25 2021-06-01 2018-10-20 2021-07-17 2019-01-18 laba), Banora (Dinguiraye), K nd Information Systems tions nvelope akony (Gaoual), Sangareya ( Pita), Dabola Centre, Senko ( Beyla), Donghol Sigon (Mali), Macenta Centre GN-PASSP-28580-GO-RFB / A cquisition et installation de m obilier de bureau pour les bur Component 1: Surveillance a Single Stage - One E eaux de tous les niveaux (co IDA / 58830 Post Request for Bids Open - National 663,000.00 0.00 Canceled 2017-12-18 2017-12-23 2018-02-03 2018-03-05 2018-04-09 2018-07-08 nd Information Systems nvelope mmunautaire, sous/préfector al, préfectoral et régional ) e n faveur de la Santé Humain e et de la Santé Animale GN-PASSP-115251-GO-RFQ / Acquisition de kit de surveilla nce (registres de notification, Component 1: Surveillance a Request for Quota Single Stage - One E IDA / 58830 Post Limited 75,000.00 70,618.75 Completed 2019-11-22 2021-05-26 2020-01-17 2021-07-01 2020-02-16 2021-07-20 Bottes, Imperméables, Stylos nd Information Systems tions nvelope , Sac à dos, etc,) en faveur d e 1000 AC de la santé animal e GN-MOH-GUI-227270-GO-RF Q / Achat et installation de 2 2 ordinateurs dont 15 portabl Component 1: Surveillance a Request for Quota Single Stage - One E es et 7 fixes ainsi que l'acqui IDA / 58830 Post Limited 75,000.00 60,834.49 Completed 2021-06-30 2021-05-27 2021-08-25 2021-07-02 2021-10-24 2022-03-04 nd Information Systems tions nvelope sition d'un photocopieur gran d modèle et vidéoprojecteurs en faveur de la DNGE-LM, l' OGUIPAR et de la DNSV GN-MOH-GUI-227273-GO-RF Q / Acquisition de kits d'éner Component 1: Surveillance a Request for Quota Single Stage - One E gie solaire pour le fonctionne IDA / 58830 Post Limited 98,000.00 105,661.41 Signed 2021-06-20 2021-05-28 2021-08-15 2021-08-03 2021-11-13 nd Information Systems tions nvelope ment du matériel informatiqu e en faveur des 33 Directions Préfectorales de l'Elevage GN-MOH-GUI-227274-GO-RF Q / Acquisition de deux (2) vé Component 2: Strengthening Request for Quota Single Stage - One E hicules Pick Up 4 x 4 en fave IDA / 58830 Post Limited 78,500.00 89,927.96 Completed 2021-08-23 2021-05-31 2021-09-29 2021-07-31 2021-12-28 2022-03-09 of Laboratory Capacity tions nvelope ur des laboratoires vétérinair es régionaux de Kankan et L abé GN-MOH-GUI-227277-GO-DI R / Acquisition d'un séquence Component 1: Surveillance a Pending Impl ur de coronavirus en faveur d IDA / 58830 Post Direct Selection Direct 250,000.00 0.00 2021-06-14 2021-06-19 2021-07-24 2021-09-22 nd Information Systems ementation e l'ANSS avec la Maison du M édecin et du Paramédical Page 4 GN-MOH-GUI-297927-GO-RF Q / Doter les 450 AC de la sa nté animale et 205 Conserva Component 1: Surveillance a Request for Quota Single Stage - One E teurs de la nature en kit de s IDA / 58830 Post Limited 85,000.00 0.00 Completed 2022-09-04 2022-07-06 2022-10-30 2022-12-29 nd Information Systems tions nvelope urveillance (registres de notif ication, Bottes, Imperméable s, Stylos, Sac à dos, torches, boites médicales, gants, jum elles) GN-MOH-GUI-297934-GO-RF Q / Acquisition des réactifs et matériel pour l'évaluation ext erne de la qualité des laborat Component 2: Strengthening Request for Quota Single Stage - One E Pending Impl IDA / 58830 Post Limited 98,500.00 0.00 2022-07-27 2022-09-21 2022-12-20 oires (méningite et Choléra), of Laboratory Capacity tions nvelope ementation de l'étude pour la prévalence de l'arbovirose, la surveillanc e de la RAM et des équipeme nts pour le laboratoire nation al GN-MOH-GUI-326585-GO-RF Q / Fourniture des Kits EPI (m asque de protection, respirat oire de type FFP, gants (M; L; Component 1: Surveillance a Request for Quota Single Stage - One E IDA / 58830 Post Limited 95,000.00 0.00 Completed 2022-12-20 2022-12-12 2023-02-14 2023-04-15 XL et XLL), blouse tyvek, calo nd Information Systems tions nvelope tte, imperméables, bottes et couvre botte) pour la surveill ance active et passive dans l es fermes infestées GN-MOH-GUI-326593-GO-RF B / Acquisition de matériel ro ulant dont :: 390 motos pour la surveillance active en fave Component 1: Surveillance a Direct - Internation Under Imple IDA / 58830 Post Direct Selection 1,300,000.00 0.00 2022-12-27 2022-11-22 2023-01-01 2022-12-01 2023-02-05 2023-08-04 ur des chefs de Poste d'éleva nd Information Systems al mentation ge et conservateurs des sites RAMSAR et 4 véhicules Pick Up TT pour la coordination in tervention avec UNOPS GN-MOH-GUI-326601-GO-RF Q / Acquisition et installation du matériel informatique pou Component 1: Surveillance a Request for Quota Single Stage - One E Pending Impl IDA / 58830 Post Limited 98,500.00 0.00 2023-01-25 2023-03-22 2023-05-21 r la Direction Nationale des S nd Information Systems tions nvelope ementation ervices Vétérinaires , la Direc tion Nationale des Epidémies et l'UGP GN-MOH-GUI-326602-GO-RF Q / Acquisition du matériel d e communication téléphones Component 1: Surveillance a Request for Quota Single Stage - One E Pending Impl IDA / 58830 Post Limited 25,000.00 0.00 2023-01-25 2023-03-22 2023-05-06 et tablettes pour le Service N nd Information Systems tions nvelope ementation ational de la Promotion de la Santé, la Direction National d es Epidémies et l'UGP. GN-MOH-GUI-326605-GO-RF Q / Acquisition et installation de mobiliers de bureaux pour Component 1: Surveillance a Request for Quota Single Stage - One E Pending Impl 28 points focaux de la promo IDA / 58830 Post Limited 75,000.00 0.00 2023-02-28 2023-04-25 2023-10-22 nd Information Systems tions nvelope ementation tion de la santé-communicati on (PFPS) des districts des ré gions de Boké, Conakry, Fara nah, N'Zérékoré, Mamou et L abé. GN-MOH-GUI-326609-GO-RF Q / Acquisition de matériels, Component 2: Strengthening Request for Quota Single Stage - One E Pending Impl IDA / 58830 Post Limited 62,550.00 0.00 2023-03-04 2023-04-29 2023-07-28 consommables et réactifs de of Laboratory Capacity tions nvelope ementation laboratoire pour le LCVD et l'I NSP GN-MOH-GUI-326612-GO-RF Q / Acquisition des kits de pr Component 2: Strengthening Request for Quota Single Stage - One E Pending Impl IDA / 58830 Post Limited 70,019.00 0.00 2023-03-26 2023-05-21 2023-07-20 élèvements pour les Unités M of Laboratory Capacity tions nvelope ementation obiles de Surveillance Animal e GN-MOH-GUI-326614-GO-DI R / Acquisition des vaccins an tirabiques et des équipement Component 3: Preparedness Direct - Internation Pending Impl IDA / 58830 Post Direct Selection 525,141.00 0.00 2023-01-06 2023-01-11 2023-02-15 2023-08-14 s connexes pour la santé hu and Emergency Response al ementation maine et animale en entente directe avec une Institution s pécialisée GN-MOH-GUI-349960-GO-DI R / Contrat avec TANE CORP Component 1: Surveillance a Under Imple IDA / 58830 Post Direct Selection Direct - National 72,600.00 0.00 2023-05-10 2023-05-28 2023-05-15 2023-06-09 2023-08-08 ORATION pour l'acquisition d nd Information Systems mentation e 2 véhicules Pick-up Double Cabines Tout Terrain GN-MOH-GUI-364040-GO-DI R / Acquisition de 390 motos pour la surveillance active en Component 1: Surveillance a Pending Impl faveur des chefs de Poste d'é IDA / 58830 Post Direct Selection Direct - National 695,000.00 0.00 2023-06-05 2023-06-07 2023-06-27 2023-08-26 nd Information Systems ementation levage des Communes rurale s et urbaines du pays et les 1 2 conservateurs des sites RA MSAR avec les Ets ABB. GN-MOH-GUI-364792-GO-DI R / Convention avec OMS pou Component 1: Surveillance a Pending Impl r l'achat de vaccins antirabiq IDA / 58830 Post Direct Selection Direct - National 91,782.00 0.00 2023-06-15 2023-06-20 2023-06-30 2023-08-29 nd Information Systems ementation ues humaines en faveur du M inistère de la Santé et de l'Hy giène Publique NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GN-PASSP-28605-NC-DIR / R Component 5: Institutional C ecrutement d'un Prestataire apacity Building, Project Ma Request for Quota Single Stage - One E de Services pour l'entretien e IDA / 58830 Post Limited 15,000.00 14,828.75 Completed 2018-03-18 2018-06-04 2018-05-13 2018-08-09 2018-06-12 2019-01-07 nagement, Coordination, an tions nvelope t la réparation des équipeme d Advocacy nts informatiques de REDISS E et du PASSP GN-PASSP-28609-NC-DIR / C ontrat avec DK Courtage pou r l'assurance du personnel co Component 5: Institutional C ntractuel et le matériel roula apacity Building, Project Ma IDA / 58830 Post Direct Selection Direct 30,000.00 24,463.56 Completed 2018-04-18 2018-04-30 2018-04-23 2018-05-28 2018-09-26 2018-06-27 2018-09-28 nt du REDISSE. DK courtage nagement, Coordination, an est recruté par le PASSP et fo d Advocacy urnira les mêmes services au REDISSE sur la base des mê mes prix unitaires. Page 5 GN-PASSP-115282-NC-RFQ / Edition et production des ma gazines/affiches/spots publici taires sur les maladies à pote Component 1: Surveillance a Request for Quota Single Stage - One E Pending Impl IDA / 58830 Post Limited 62,000.00 0.00 2019-12-03 2020-01-28 2020-03-13 ntiel épidémique pour la sant nd Information Systems tions nvelope ementation é humaine, animale et enviro nnementale et édition des ou tils de gestion pour les centr es de surveillance de la faun e sauvage GN-PASSP-115298-NC-RFQ / Component 5: Institutional C Request for Quota Single Stage - One E Confection des Agendas, Cal IDA / 58830 apacity Building, Project Ma Post Limited 30,000.00 27,320.89 Signed 2019-10-12 2019-11-11 2019-12-07 2019-12-20 2020-01-21 tions nvelope endriers et Cartes de meilleu nagement, Coordination, an rs vœux 2020 d Advocacy GN-PASSP-119934-NC-RFQ / Edition et impression des out Component 5: Institutional C ils de gestion financière pour apacity Building, Project Ma Request for Quota Single Stage - One E Pending Impl les Directions Préfectorales e IDA / 58830 Post Limited 15,000.00 0.00 2020-01-22 2020-03-18 2020-04-17 nagement, Coordination, an tions nvelope ementation t les Directions Régionales d d Advocacy e la Santé (fiche pour la tenu e de la comptabilité des struc tures) GN-MOH-GUI-172571-NC-RF Q / Elaborer des messages cl Component 4: Human Resou és, des outils et des supports rce Management for Effectiv Request for Quota Single Stage - One E Pending Impl IDA / 58830 Post Limited 95,000.00 0.00 2020-09-05 2020-10-31 2020-12-15 de communication accessible e Disease Surveillance and E tions nvelope ementation s aux communautés sur les pidemic Preparedness. maladies à potentiel épidémi ques GN-MOH-GUI-172576-NC-RF Q / Produire des matériels d e communication et d'outils d'engagement communautai Component 1: Surveillance a Request for Quota Single Stage - One E IDA / 58830 Post Limited 85,000.00 37,830.01 Signed 2020-11-21 2021-08-24 2021-01-16 2022-02-08 2021-03-17 res sur les événements de sa nd Information Systems tions nvelope nté humaine, animale et envi ronnementale pour le Chang ement Social et Comporteme nt (CSC) des populations GN-MOH-GUI-172578-NC-RF Component 5: Institutional C Q / Edition et Confection des apacity Building, Project Ma Request for Quota Single Stage - One E IDA / 58830 Post Limited 28,500.00 26,987.36 Completed 2020-09-20 2019-11-11 2020-11-15 2019-12-20 2021-01-14 2021-02-09 Agendas, Calendriers et Cart nagement, Coordination, an tions nvelope es de meilleurs vœux 2021 d Advocacy GN-MOH-GUI-172583-NC-RF Q / Produire des matériels d e Visibilité sur la réponse au COVID 19 en Santé humaine, Component 1: Surveillance a Request for Quota Single Stage - One E Pending Impl IDA / 58830 Post Limited 65,000.00 0.00 2020-11-21 2021-01-16 2021-03-17 animale et environnementale nd Information Systems tions nvelope ementation pour le Bénéficiaire (MS) (Pa nneaux, Affiches, dépliants, Cartable, Kakemono, etc.) po ur renforcer la communicatio n et la visibilité GN-MOH-GUI-172619-NC-DIR / Location de tentes et acces soires (électricité, système d e ventilation et assainisseme Component 1: Surveillance a IDA / 58830 Post Direct Selection Direct 35,000.00 172,380.30 Completed 2020-06-05 2020-05-08 2020-06-10 2020-05-11 2020-07-15 2020-07-07 2020-10-13 2020-07-24 nt) pour servir de sites de pri nd Information Systems se en charge des cas COVID 19 au Centre Pénitencier de Conakry avec ISSA Tapisserie pour 3 mois de location GN-MOH-GUI-297932-NC-RF Q / Prestataire de service po ur la reproduction du Guide S Component 1: Surveillance a Request for Quota Single Stage - One E IMR (Système Intégré des Ma IDA / 58830 Post Limited 25,000.00 0.00 Completed 2022-08-30 2022-09-08 2022-10-25 2022-12-24 nd Information Systems tions nvelope ladies et Riposte) révisé au ni veau du Centre de Santé pou r les régions de Boké, Kindia et Conakry GN-MOH-GUI-297939-CS-IND Component 5: Institutional C V / Recrutement d'un Prestat apacity Building, Project Ma Request for Quota Single Stage - One E Pending Impl aire pour la réalisation d'un fi IDA / 58830 Post Limited 18,000.00 0.00 2022-09-20 2022-11-15 2023-01-14 nagement, Coordination, an tions nvelope ementation lm documentaire de 20 minu d Advocacy tes sur le Projet REDISSE CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GN-PASSP-28115-CS-QCBS / Recrutement d'un bureau d'é tudes d'ingénierie civil pour l Component 1: Surveillance a Quality And Cost- IDA / 58830 Post Open - National 80,000.00 162,233.89 Signed 2017-09-27 2018-01-15 2017-10-18 2018-02-01 2017-12-01 2018-03-05 2017-12-29 2018-04-12 2018-01-28 2018-04-12 2018-03-04 2018-05-09 2018-04-08 2018-06-21 2019-04-08 es études et le contrôle des t nd Information Systems Based Selection ravaux de construction et la r énovation de laboratoires et PIF GN-MOH-GUI-145099-CS-QC BS / Recrutement d'un Cabin Component 5: Institutional C et/Bureau pour l'Audit extern apacity Building, Project Ma Quality And Cost- Open - Internationa e des comptes du Projet Régi IDA / 58830 Post 45,000.00 18,000.00 Signed 2019-12-20 2019-12-04 2020-01-09 2020-01-20 2020-02-12 2020-03-03 2020-03-03 2020-04-14 2020-03-23 2020-04-14 2020-04-21 2020-06-02 2020-05-15 2020-07-29 2022-06-30 nagement, Coordination, an Based Selection l onal d'Amélioration des Syst d Advocacy èmes de Surveillance des Ma ladies en Afrique de l'Ouest ( REDISSE) GN-MOH-GUI-165564-CS-UN / Assistance Technique avec UNICEF pour le recrutement Component 1: Surveillance a UN Agencies (Dire Pending Impleme IDA / 58830 Post Direct 85,000.00 0.00 2020-06-01 2020-11-28 de : 2 Spécialistes Socio Ant nd Information Systems ct) ntation hropologue et 1 Spécialiste e n Communication pour l'urge nce sanitaire du COVID 19 GN-MOH-GUI-165558-GO-UN / Assistance technique avec OMS pour recrutement de six (6) spécialistes : 1 statisticie Component 1: Surveillance a UN Agencies (Dire n, 1 informaticien, 1 technici IDA / 58830 Post Direct 185,000.00 193,670.00 Signed 2020-05-18 2020-05-07 2020-11-14 nd Information Systems ct) en de laboratoire, 1 pneumol ogue, 1 Spécialiste en Réani mation et 1 Expert en Logisti que dans le cadre de l'urgenc e sanitaire du COVID 19 Page 6 GN-MOH-GUI-171996-CS-UN / Assistance Technique en Co mmunication Pour le Dévelop Component 1: Surveillance a UN Agencies (Dire IDA / 58830 Post Direct 409,336.00 409,336.00 Signed 2020-07-04 2020-05-15 2021-07-04 pement et en Socio-Anthropo nd Information Systems ct) logie avec l'UNICEF dans le c adre de l'urgence sanitaire d u COVID 19 GN-MOH-GUI-278076-CS-CQ S / Recrutement d’un Cabinet pour l’élaboration de la Notic e d’Impact Environnemental Component 2: Strengthening Consultant Qualifi Open - Internationa Pending Impleme IDA / 58830 Post 75,000.00 0.00 2022-02-28 2022-03-21 2022-05-04 2022-06-03 2022-07-08 2022-08-07 et Social( NIES) du projet de of Laboratory Capacity cation Selection l ntation construction du laboratoire v étérinaire P2+ dans la Sous- préfecture de Kouriyah (Préfe cture de Coyah) GN-MOH-GUI-297936-CS-QC Component 5: Institutional C BS / Recrutement d'un Cabin apacity Building, Project Ma Quality And Cost- IDA / 58830 Post Open - National 15,000.00 0.00 Canceled 2022-07-15 2022-08-05 2022-09-18 2022-10-16 2022-11-15 2022-12-20 2023-01-24 2024-01-24 et pour l'audit externe des co nagement, Coordination, an Based Selection mptes du REDISSE exercice 2 d Advocacy 022 INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GN-PASSP-28094-CS-INDV / Recrutement d'un Consultant National pour l'élaboration d' Component 2: Strengthening Individual Consult IDA / 58830 Post Limited 40,000.00 13,786.64 Signed 2017-11-20 2019-06-24 2017-11-25 2019-07-01 2017-12-16 2020-03-03 2018-01-20 2020-03-31 2018-02-19 un manuel de procédures sta of Laboratory Capacity ant Selection ndads des différentes unités du laboratoire dans l'approch e One Health GN-PASSP-28112-CS-INDV / Recrutement d'un Consultant pour déterminer les caractéri Component 2: Strengthening Individual Consult Under Implement IDA / 58830 Post Open 60,000.00 0.00 2017-10-30 2018-02-01 2017-12-18 2018-01-08 2018-02-12 2018-04-13 stiques techniquqes pour le n of Laboratory Capacity ant Selection ation ouveau laobratoire national d e diagnostic véterinaire nive au P2 GN-PASSP-28493-CS-INDV / Recrutement d'un Consultant Component 1: Surveillance a Individual Consult pour l'actualisation du manu IDA / 58830 Post Limited 20,000.00 13,722.70 Completed 2018-05-21 2019-05-16 2018-05-26 2019-05-05 2018-06-16 2019-07-22 2018-07-21 2019-07-22 2018-08-20 2020-02-05 nd Information Systems ant Selection el de protocole de surveillanc e au niveau des abattoirs des maladies prioritaires GN-PASSP-28496-CS-INDV / Component 5: Institutional C Recrutement d'un Consultant apacity Building, Project Ma Individual Consult International pour l'élaborati IDA / 58830 Post Limited 60,000.00 45,176.00 Completed 2018-06-06 2018-03-27 2018-06-11 2018-04-02 2018-07-02 2018-05-29 2018-08-06 2018-06-21 2018-09-05 2018-09-28 nagement, Coordination, an ant Selection on d'une stratégie de commu d Advocacy nication en santé humaine et animale GN-PASSP-28497-CS-INDV / Recrutement d'un Consultant Component 5: Institutional C National pour appuyer le Co apacity Building, Project Ma Individual Consult IDA / 58830 Post Open 15,000.00 7,390.50 Completed 2018-06-06 2018-05-14 2018-07-25 2018-06-22 2018-08-15 2018-07-10 2018-09-19 2018-07-30 2018-10-19 2019-02-11 nsultant International dans l' nagement, Coordination, an ant Selection élaboration d'une stratégie d d Advocacy e communication en santé h umaine et animale GN-PASSP-71189-CS-INDV / Recrutement d'un Consultant Component 1: Surveillance a Individual Consult IDA / 58830 Post Open 18,000.00 24,000.00 Signed 2019-02-26 2018-12-17 2019-04-16 2019-05-17 2019-05-07 2019-05-22 2019-06-11 2019-06-13 2020-06-05 Conseiller technique (Assista nd Information Systems ant Selection nt à la Coordination Une Seul e Santé) GN-PASSP-82468-CS-INDV / Recrutement d'un Consultant International pour le renforce Component 2: Strengthening Individual Consult ment des capacités des labor IDA / 58830 Post Open 100,000.00 115,350.00 Signed 2018-12-16 2019-06-14 2019-02-03 2019-07-30 2019-02-24 2019-09-11 2019-03-31 2019-09-11 2020-03-31 of Laboratory Capacity ant Selection atoires de Guinée dans le ca dre de la surveillance et de la riposte (plan directeur 2018- 2022) GN-PASSP-119926-CS-CDS / Recruter AFNET (Réseau Afri Component 4: Human Resou cain d’Epidémiologie de Terr rce Management for Effectiv IDA / 58830 Post Direct Selection Direct 148,000.00 148,000.00 Completed 2019-11-20 2019-07-09 2019-11-30 2019-09-04 2020-02-03 2020-02-21 2021-02-02 2021-05-08 ain (African Field Epidemiolo e Disease Surveillance and E gy Network) pour former des pidemic Preparedness. cadres du Ministère de la San té en Épidémiologie de Terrai n GN-MOH-GUI-180928-CS-IND V / Recrutement d'un Consult Component 5: Institutional C ant pour l'évaluation à mi-pa apacity Building, Project Ma Individual Consult IDA / 58830 Post Open 10,000.00 10,586.73 Completed 2020-07-16 2020-07-27 2020-09-03 2020-09-02 2020-09-24 2020-09-08 2020-10-29 2020-09-09 2020-11-28 2020-12-19 rcours du Projet Régional d'A nagement, Coordination, an ant Selection mélioration des Systèmes de d Advocacy Surveillance des Maladies en Afrique de l'Ouest (REDISSE) GN-PASSP-115303-CS-INDV / Recrutement d'un Consultant Component 5: Institutional C National pour Formation en g apacity Building, Project Ma Individual Consult estion de Projet de 20 cadres IDA / 58830 Post Open 10,000.00 0.00 Canceled 2020-01-28 2020-03-17 2020-04-07 2020-05-12 2020-06-11 nagement, Coordination, an ant Selection des 3 ministères (8 Santé, 7 d Advocacy Élevage et 5 Environnement) impliqués dans la mise en oe uvre du Projet GN-PASSP-115304-CS-INDV / Recrutement d'un consultant Component 5: Institutional C National pour l'élaboration d' apacity Building, Project Ma Individual Consult Under Implement IDA / 58830 Post Open 25,000.00 0.00 2021-12-21 2022-04-27 2022-02-08 2022-03-01 2022-04-05 2022-05-05 un manuel de procédures sta nagement, Coordination, an ant Selection ation ndards des différentes unités d Advocacy des laboratoires vétérinaire GN-PASSP-71328-CS-INDV / Recruter un Consultant Natio Component 5: Institutional C nal pour évaluer les impacts apacity Building, Project Ma Individual Consult Under Implement de la communication des risq IDA / 58830 Post Open 45,000.00 0.00 2019-02-26 2022-08-03 2019-04-16 2019-05-07 2019-06-11 2019-07-11 nagement, Coordination, an ant Selection ation ues et d'engagement commu d Advocacy nautaire sur le changement d e comportement en lien avec le coronavirus GN-MOH-GUI-172603-CS-IND Component 5: Institutional C V / Recrutement d'un consult apacity Building, Project Ma Individual Consult Under Implement IDA / 58830 Post Open 30,000.00 0.00 2020-12-28 2021-02-15 2021-03-08 2021-04-12 2021-06-11 ant national pour la réalisatio nagement, Coordination, an ant Selection ation n d'une étude entomologique d Advocacy sur la Fièvre Jaune Page 7 GN-MOH-GUI-227275-CS-IND V / Recrutement d'un consult Component 2: Strengthening Individual Consult Under Implement ant pour élaborer les normes IDA / 58830 Post Open 25,000.00 0.00 2021-11-18 2022-04-27 2022-01-06 2022-01-27 2022-03-03 2022-04-17 of Laboratory Capacity ant Selection ation et procédures de gestion des déchets générés par les activ ités d'élevage GN-MOH-GUI-227276-CS-IND V / Recrutement d'un consult Component 5: Institutional C ant national pour créer une i apacity Building, Project Ma Individual Consult Under Implement nterface entre la Plateforme IDA / 58830 Post Open 35,000.00 0.00 2021-11-30 2022-08-03 2022-01-18 2022-02-08 2022-03-15 2022-05-14 nagement, Coordination, an ant Selection ation DHIS2 et la Plateforme EMPR d Advocacy ES-i utilisée par les services v étérinaires et la formation du personnel GN-MOH-GUI-300112-CS-IND V / Recrutement d'un Consult ant international dans le cadr Component 2: Strengthening Individual Consult Pending Impleme e de l'assurance qualité et de IDA / 58830 Post Open 150,000.00 0.00 2022-09-05 2022-10-24 2022-11-14 2022-12-19 2023-06-17 of Laboratory Capacity ant Selection ntation l'accréditation pour assurer u ne assistance technique à l'In stitut National de Santé Publi que (INSP) GN-PASSP-28499-CS-CDS / C ontrat avec le Cabinet Fiduci Component 5: Institutional C aire de Guinée membre Pwc apacity Building, Project Ma pour l'audit externe des com IDA / 58830 Post Direct Selection Direct 45,000.00 0.00 Canceled 2018-02-12 2018-02-22 2018-04-28 2018-08-26 nagement, Coordination, an ptes du REDISSE. Le Cabinet d Advocacy Pwc est recruté par la PASSP pour l'audit des Projets PASS P, REDISSE et PSRM GN-MOH-GUI-327538-CS-CD S / Recrutement du Groupem ent d’Expertise Comptable & Component 5: Institutional C Conseils (CE2C) et Panafricai apacity Building, Project Ma Direct - Internation IDA / 58830 Post Direct Selection 12,000.00 0.00 Signed 2023-01-16 2023-01-11 2023-01-26 2023-02-22 2023-04-01 2023-05-31 ne nagement, Coordination, an al d’Audit du Burkina (PANAUDI d Advocacy T – BURKINA) pour l'Audit ext erne des comptes du REDISS E (exercices 2022 et 2023) GN-MOH-GUI-349223-CS-IND V / Recrutement de d’un Con Component 4: Human Resou sultants National pour l’évalu rce Management for Effectiv Individual Consult Under Implement ation finale du Projet Régiona IDA / 58830 Post Open - National 25,000.00 0.00 2023-04-21 2023-03-23 2023-06-19 2023-07-10 2023-08-14 2023-09-28 e Disease Surveillance and E ant Selection ation l d'Amélioration des Système pidemic Preparedness. s de Surveillance des Maladie s en Afrique de l'Ouest (REDI SSE) Page 8 Sample Procurement Plan I. General 1. Bank’s approval Date of the procurement Plan [Original: February 1,2017]: Revision 1 of Updated Procurement Plan, June 21,2017] 2. Date of General Procurement Notice: Dec 24, 2006 3. Period covered by this procurement plan: The procurement period of project covered from year June 2010 to December 2012 II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: [Thresholds for applicable procurement methods (not limited to the list below) will be determined by the Procurement Specialist /Procurement Accredited Staff based on the assessment of the implementing agency’s capacity.] Procurement Method Prior Review Comments Threshold US$ 1. ICB and LIB (Goods) Above US$ 500,000 All 2. NCB (Goods) Above US$ 100,000 First contract 3. ICB (Works) Above US$ 15 million All 4. NCB (Works) Above US$ 5 million All 5. (Non-Consultant Services) Below US$ 100,000 First contract [Add other methods if necessary] 2. Prequalification. Bidders for _Not applicable_ shall be prequalified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines. 4. Reference to (if any) Project Operational/Procurement Manual: Project Operations Manual for World Bank Loan Project P158099 5. Summary of the Procurement Packages planned during the first 18 months after project effectiveness ( including those that are subject to retroactive financing and advanced procurement) [List the Packages which require Bank’s prior review first and then the other packages] July 9, 2010 1 2 3 4 5 6 7 Ref. Descripti Estimat Packages Dome Review Comme No. on ed stic by Bank nts Cost Prefe (Prior / US$ rence Post) million (yes/ no) Summary 82 5 No Prior of the ICB (Works) Summary 43.77 15 No Prior of the ICB (Goods) Summary 64.53 18 No Post 1st of the NCB contrac (Works) t for Prior Review Summary 1.86 4 No Post 1st of the NCB contrac (Goods) t for Prior Review Summary 0.45 1 No Prior of the ICB (Non- Consultant Services) III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Comments Threshold 1. Competitive Methods (Firms) Above US$ 100,000 2. Single Source (Firms) All 3. Individual Above US$ 110,000 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_300,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. July 9, 2010 3. Any Other Special Selection Arrangements: [including advance procurement and retroactive financing, if applicable or delete if not applicable] 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 Ref. No. Description Estimat Package Review Comment of ed s by Bank s Assignmen Cost (Prior / t US$ Post) million Summary 4.17 7 Prior of number of contracts that will be let under QCBS Summary 0.83 1 Prior CQS of number of contracts that will be let under other methods July 9, 2010 PROCUREMENT Pakistan : PK: Punjab Tourism for Economic Growth Project PLAN General Information Country: Pakistan 2017-12-21 Bank’s Approval Date of the Original Procurement Plan: 2023-06-06 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P158099 GPN Date: 2020-08-11 Project Name: PK: Punjab Tourism for Economic Growth Project Loan / Credit No: IDA / 59820 Punjab Tourism for Economic Growth Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned PK-PTEG-40086-CW-RFB / Fa 3. Public Investment Facilit Open - Internationa Single Stage - One E 11,386,666.0 2021-09-3 IDA / 59820 Prior Request for Bids 0.00 Canceled 2018-08-31 2018-09-05 2018-10-17 2018-11-01 2018-11-22 cilities & Amenities up-gradat y l nvelope 0 0 ion at sites PK-PTEG-40077-CW-RFB / Da 3. Public Investment Facilit Single Stage - One E 2019-04-1 rbar sahib road Kartarpur - R IDA / 59820 Prior Request for Bids Open - National 588,219.00 0.00 Canceled 2018-08-06 2018-08-11 2018-09-22 2018-10-07 2018-10-21 y nvelope 9 ehabilitation of secondary & t ertiary roads PK-PTEG-40079-CW-RFB / Ta 3. Public Investment Facilit Single Stage - One E 2019-04-2 xila- Toap Mankila- Mohra - R IDA / 59820 Post Request for Bids Open - National 1,437,133.00 0.00 Canceled 2018-08-13 2018-08-18 2018-09-29 2018-10-14 2018-10-28 y nvelope 6 ehabilitation of roads PK-PTEG-40080-CW-RFB / Na 3. Public Investment Facilit Open - Internationa Single Stage - One E 2019-03-2 nkana Sahib-Farooqabad roa IDA / 59820 Post Request for Bids 5,262,066.00 0.00 Canceled 2018-07-16 2018-07-21 2018-09-01 2018-09-16 2018-09-30 y l nvelope 9 d - Rehabilitation of road PK-PTEG-40081-CW-RFB / E 3. Public Investment Facilit Single Stage - One E 2018-12-1 minabad - Rori roads - Rehab IDA / 59820 Post Request for Bids Open - National 399,228.00 0.00 Canceled 2018-04-04 2018-04-09 2018-05-21 2018-06-05 2018-06-19 y nvelope 6 ilitation of roads PK-PTEG-40084-CW-RFB / Uc 3. Public Investment Facilit Single Stage - One E 2019-04-1 IDA / 59820 Post Request for Bids Open - National 1,199,457.00 0.00 Canceled 2018-08-06 2018-08-11 2018-09-20 2018-10-04 2018-10-18 h Sharif road - Rehabilitation y nvelope 6 of roads PK-PTEG-40085-CW-RFB / Gh 3. Public Investment Facilit Single Stage - One E 2019-03-2 ulam Farid Mithan Kot Rajanp IDA / 59820 Post Request for Bids Open - National 1,024,428.00 0.00 Canceled 2018-07-09 2018-07-14 2018-08-25 2018-09-09 2018-09-23 y nvelope 2 ur - Rehabilitation of roads PK-PTEG-194132-CW-RFB / R 3. Public Investment Facilit Single Stage - One E 4,346,514.4 2021-11-2 oads Rehabilitation in Punjab IDA / 59820 Post Request for Bids Open - National 6,000,000.00 Signed 2020-09-16 2020-09-17 2020-09-18 2020-09-17 2020-10-20 2020-10-20 2020-10-30 2020-11-10 2020-11-20 2020-12-10 y nvelope 3 0 (4 Packages, 6 Roads) PK-PTEG-238517-CW-RFB / R 3. Public Investment Facilit Single Stage - One E Other (with field f Under Imple 2022-08-1 ehabilitation of Roads - Uch S IDA / 59820 Post Request for Bids Open - National 3,300,000.00 0.00 2021-06-08 2021-06-30 2021-06-10 2021-07-14 2021-07-10 2021-08-03 2021-07-25 2021-08-22 y nvelope or explanation) mentation 7 harif & Channan Pir PK-PTEG-269512-CW-RFQ / T Request for Quota 3. Public Investment Facilit Request for Quota Single Stage - One E 2022-08-0 axila Museum - Design & Con IDA / 59820 Post Open - National tions (Non Bank-S 95,000.00 20,833.57 Signed 2021-12-31 2022-03-25 2022-02-04 2022-04-27 y tions nvelope 3 struction of Entrance Gate PD) Request for Bids - PK-PTEG-279723-CW-RFB / C 3. Public Investment Facilit Single Stage - One E Small Works SPD 2023-04-2 onstruction/Rehabilitation of IDA / 59820 Post Request for Bids Open - National 1,950,000.00 0.00 Canceled 2022-02-22 2022-03-25 2022-02-27 2022-03-29 2022-03-29 2022-04-13 2022-04-27 y nvelope (2 envelope proce 2 Toilet facilities at Heritage & ss) Tourist Sites Request for Bids - PK-PTEG-314721-CW-RFB / C 3. Public Investment Facilit Single Stage - One E Small Works SPD 2023-11-1 onstruction/Rehabilitation of IDA / 59820 Post Request for Bids Open - National 1,950,000.00 0.00 Canceled 2022-09-19 2022-09-24 2022-10-24 2022-11-08 2022-11-22 y nvelope (1 envelope proce 7 Toilet Blocks at Tourist sites - ss) Punjab PK-PTEG-330987-CW-RFB / R ehabilitation / Improvement 3. Public Investment Facilit Single Stage - One E Other (with field f Under Imple 2024-02-1 of Metaled Road from Lahore IDA / 59820 Post Request for Bids Open - National 1,000,000.00 0.00 2022-12-12 2023-02-20 2022-12-12 2023-02-24 2023-01-16 2023-03-27 2023-01-26 2023-04-12 2023-02-19 y nvelope or explanation) mentation 9 -Sheikhupura-Sargodha Road to Gurdwara Sucha Soda Dist rict Sheikhupura. PK-PTEG-331277-CW-RFB / R ehabilitation / Improvement 3. Public Investment Facilit Single Stage - One E Other (with field f 2024-02-1 of Metalled Road from Lahore IDA / 59820 Post Request for Bids Open - National 950,000.00 0.00 Canceled 2022-12-12 2023-02-20 2022-12-12 2023-02-24 2023-01-16 2023-01-26 2023-02-19 y nvelope or explanation) 9 -Sheikhupura-Sargodha Road to Mariumabad (Right Side of canal) District Sheikhupura PK-PTEG-331281-CW-RFB / R ehabilitation / Improvement 3. Public Investment Facilit Single Stage - One E Other (with field f 2024-08-1 IDA / 59820 Post Request for Bids Open - National 8,250,000.00 0.00 Signed 2022-12-12 2023-02-20 2022-12-12 2023-02-24 2023-01-16 2023-03-27 2023-01-26 2023-04-10 2023-02-19 of Road from Kallar Kahar to y nvelope or explanation) 7 Manara District Boundary Ch akwal District Chakwal PK-PTEG-331284-CW-RFB / C 3. Public Investment Facilit Single Stage - One E Other (with field f Pending Imp 2024-08-1 onstruction of Rohtas Fort By IDA / 59820 Post Request for Bids Open - National 8,700,000.00 0.00 2022-12-12 2022-12-12 2023-01-16 2023-01-26 2023-02-19 y nvelope or explanation) lementation 7 pass Road District Jhelum. Request for Bids - PK-PTEG-333401-CW-RFB / C 3. Public Investment Facilit Single Stage - One E Small Works SPD Under Imple 2024-03-1 onstruction/Rehabilitation of IDA / 59820 Post Request for Bids Open - National 1,950,000.00 0.00 2022-12-23 2023-03-20 2022-12-28 2023-04-02 2023-02-01 2023-02-11 2023-03-19 y nvelope (1 envelope proce mentation 8 Toilet Blocks at Tourist sites - ss) Punjab Request for Bids - PK-PTEG-360704-CW-RFB / C 2. Private Investment and Single Stage - One E Small Works SPD Under Imple 2024-07-1 onservation & Rehabilitation IDA / 59820 Post Request for Bids Open - National 610,000.00 0.00 2023-05-09 2023-05-17 2023-05-09 2023-05-17 2023-06-03 2023-06-10 2023-06-22 Entrepreneurship Promotion nvelope (1 envelope proce mentation 5 of Buildings/Façade Work on ss) West Side Request for Bids - PK-PTEG-360710-CW-RFB / C 2. Private Investment and Single Stage - One E Small Works SPD Under Imple 2024-07-1 onservation & Rehabilitation IDA / 59820 Post Request for Bids Open - National 780,000.00 0.00 2023-05-09 2023-05-17 2023-05-09 2023-05-17 2023-06-03 2023-06-10 2023-06-22 Entrepreneurship Promotion nvelope (1 envelope proce mentation 5 of Buildings/Façade Work on ss) East Side-1 Request for Bids - PK-PTEG-360711-CW-RFB / C 2. Private Investment and Single Stage - One E Small Works SPD Under Imple 2024-07-1 onservation & Rehabilitation IDA / 59820 Post Request for Bids Open - National 780,000.00 0.00 2023-05-09 2023-05-17 2023-05-09 2023-05-17 2023-06-03 2023-06-10 2023-06-22 Entrepreneurship Promotion nvelope (1 envelope proce mentation 5 of Buildings/Façade Work On ss) East Side-2 PK-PTEG-360715-CW-RFB / C Request for Bids - onservation of Bhatti Gate: 2. Private Investment and Single Stage - One E Small Works SPD Under Imple 2024-07-1 Façade Rehabilitation of Main IDA / 59820 Post Request for Bids Open - National 545,000.00 0.00 2023-05-09 2023-05-17 2023-05-09 2023-05-17 2023-06-03 2023-06-10 2023-06-22 Entrepreneurship Promotion nvelope (1 envelope proce mentation 5 Trail, Relocation of Water Filt ss) ration Plant and Establishme nt of Parking Area Page 1 PK-PTEG-363215-CW-RFB / R ehabilitation / Improvement of Metaled Road from Lahore 2. Private Investment and Single Stage - One E Other (with field f Pending Imp 2024-07-1 IDA / 59820 Post Request for Bids Open - National 950,000.00 0.00 2023-05-23 2023-05-25 2023-06-15 2023-06-25 2023-07-15 -Sheikhupura-Sargodha Road Entrepreneurship Promotion nvelope or explanation) lementation 4 to Mariumabad Length 4.10K M (Right Side of canal) Distri ct Sheikhupura GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PK-PTEG-32430-GO-RFQ / Ve 4. Project Management, M Request for Quota Single Stage - One E IDA / 59820 Post Open - National 40,000.00 0.00 Canceled 2018-02-05 2018-04-02 2018-09-29 hicles Procurement onitoring and Evaluation tions nvelope PK-PTEG-32431-GO-RFQ / Of 4. Project Management, M Request for Quota Single Stage - One E IDA / 59820 Post Open - National 58,650.00 23,294.21 Signed 2018-02-04 2018-04-01 2018-05-18 2018-09-28 fice Furniture onitoring and Evaluation tions nvelope PK-PTEG-40059-GO-RFQ / Po 4. Project Management, M Request for Quota Single Stage - One E IDA / 59820 Post Open - National 9,600.00 6,930.48 Signed 2018-03-03 2018-04-28 2018-06-01 2018-10-25 wer Generator onitoring and Evaluation tions nvelope PK-PTEG-40060-GO-RFQ / Of fice Equipment 4. Project Management, M Request for Quota Single Stage - One E IDA / 59820 Post Open - National 17,000.00 5,280.80 Signed 2018-01-13 2018-06-30 2018-03-10 2018-06-01 2018-09-06 (Telephone Exchange, CCTV, onitoring and Evaluation tions nvelope Air conditioners, refrigerators etc.) PK-PTEG-40065-GO-RFQ / M 4. Project Management, M Request for Quota Single Stage - One E IDA / 59820 Post Open - National 600.00 0.00 Canceled 2018-01-24 2018-03-21 2018-09-17 otor Bike onitoring and Evaluation tions nvelope PK-PTEG-40054-GO-RFQ / IT Equipment 4. Project Management, M Request for Quota Single Stage - One E (Laptops, Desktops, Server, P IDA / 59820 Post Open - National 39,000.00 22,115.80 Signed 2017-12-30 2018-02-14 2018-02-24 2018-06-01 2018-08-23 onitoring and Evaluation tions nvelope rinters, Scanner, Multimedia Projector etc.) PK-PTEG-40058-GO-RFQ / Ne 4. Project Management, M Request for Quota Single Stage - One E tworking for IT connectivity & IDA / 59820 Post Open - National 7,000.00 2,693.07 Signed 2018-02-25 2018-04-22 2018-06-01 2018-10-19 onitoring and Evaluation tions nvelope Telephone Exchange PK-PTEG-40067-GO-RFB / Hu 1. Policy, Institutions and Open - Internationa Single Stage - One E IDA / 59820 Post Request for Bids 200,000.00 0.00 Canceled 2018-04-16 2018-04-21 2018-06-02 2018-06-18 2018-07-02 2018-12-29 man Resource Information Sy Governance for Tourism Dev l nvelope stem elopment PK-PTEG-93484-GO-RFB / To 1. Policy, Institutions and Open - Internationa Single Stage - One E IDA / 59820 Prior Request for Bids 3,500,000.00 0.00 Canceled 2019-02-04 2019-02-09 2019-03-23 2019-04-22 2019-05-27 2019-11-23 urism Mobile Application Governance for Tourism Dev l nvelope elopment PK-PTEG-151606-GO-RFQ / P urchase of new IT Equipment and software for project staf 4. Project Management, M Request for Quota Single Stage - One E Pending Impl f. IDA / 59820 Post Open - National 15,000.00 0.00 2019-12-24 2019-12-28 2020-01-31 onitoring and Evaluation tions nvelope ementation 7 Laptops Core i-5 8GB ram 1 3.3" Screen size 256/512 GB HDD Windows 10 + MS Office 1 Tablet PK-PTEG-161181-GO-RFQ / I 4. Project Management, M Request for Quota Single Stage - One E Pending Impl IDA / 59820 Post Open - National 17,300.00 0.00 2020-03-14 2020-05-09 2020-11-05 T Equipment onitoring and Evaluation tions nvelope ementation PK-PTEG-161189-GO-RFQ / O 4. Project Management, M Request for Quota Single Stage - One E Pending Impl IDA / 59820 Post Open - National 11,800.00 0.00 2020-03-14 2020-05-09 2020-11-05 ffice Equipment onitoring and Evaluation tions nvelope ementation PK-PTEG-161192-GO-RFQ / O 4. Project Management, M Request for Quota Single Stage - One E IDA / 59820 Post Open - National 16,000.00 10,960.00 Signed 2020-03-14 2020-03-17 2020-05-09 2020-03-21 2020-11-05 ffice Furniture onitoring and Evaluation tions nvelope PK-PTEG-186934-GO-RFB / Si 3. Public Investment Facilit Single Stage - One E Under Imple IDA / 59820 Post Request for Bids Open - National 1,000,000.00 0.00 2020-08-13 2020-08-31 2020-08-18 2020-09-03 2020-09-29 2020-10-05 2020-10-14 2020-11-04 2023-10-20 gnboards - Supply and Install y nvelope mentation ation (FA) PK-PTEG-200114-GO-RFQ / P 3. Public Investment Facilit Request for Quota Single Stage - One E IDA / 59820 Post Limited 2,500.00 2,580.69 Signed 2020-10-20 2020-10-26 2020-11-05 2020-10-31 2020-11-12 rofessional Camera y tions nvelope PK-PTEG-200602-GO-RFQ / O 4. Project Management, M Request for Quota Single Stage - One E IDA / 59820 Post Open - National 36,000.00 19,551.99 Signed 2020-10-27 2020-10-28 2020-11-26 2020-11-12 2021-02-24 ffice Furniture - Tourism Dep onitoring and Evaluation tions nvelope artment PK-PTEG-200605-GO-RFQ / I 4. Project Management, M Request for Quota Single Stage - One E Under Imple IDA / 59820 Post Open - National 25,200.00 0.00 2020-10-30 2020-10-28 2020-12-11 2021-02-09 T Equipment - Tourism Depar onitoring and Evaluation tions nvelope mentation tment PK-PTEG-200606-GO-RFQ / O 4. Project Management, M Request for Quota Single Stage - One E IDA / 59820 Post Open - National 15,000.00 12,992.20 Signed 2020-10-31 2020-11-19 2020-12-15 2020-12-11 2021-02-13 ffice Equipment - Tourism De onitoring and Evaluation tions nvelope partment PK-PTEG-230268-GO-RFQ / G 3. Public Investment Facilit Request for Quota Single Stage - One E IDA / 59820 Post Open - National 150,000.00 163,734.37 Signed 2021-04-30 2021-05-07 2021-06-04 2021-06-10 2021-12-01 olf Carts for Heritage Sites y tions nvelope PK-PTEG-230269-GO-RFQ / H 3. Public Investment Facilit Request for Quota Single Stage - One E IDA / 59820 Post Open - National 70,000.00 34,537.37 Signed 2021-05-01 2021-05-07 2021-06-05 2021-06-23 2021-12-02 eritage Rikshaws y tions nvelope PK-PTEG-230271-GO-RFQ / C 3. Public Investment Facilit Request for Quota Single Stage - One E IDA / 59820 Post Open - National 100,000.00 80,079.55 Signed 2021-05-01 2021-05-07 2021-06-05 2021-06-08 2021-12-02 oaster - Shuttle Bus y tions nvelope PK-PTEG-228308-GO-RFQ / S 3. Public Investment Facilit Request for Quota Single Stage - One E IDA / 59820 Post Open - National 95,000.00 38,012.80 Signed 2021-05-01 2021-09-03 2021-06-05 2021-10-29 2021-12-02 MD for Taxila Museum y tions nvelope PK-PTEG-231715-GO-RFB / S 3. Public Investment Facilit Single Stage - One E IDA / 59820 Post Request for Bids Open - National 700,000.00 207,024.82 Terminated 2021-05-05 2021-08-04 2021-05-10 2021-08-05 2021-06-09 2021-09-02 2021-06-23 2021-09-23 2021-07-14 2022-01-02 2022-01-10 olid Waste Management Equi y nvelope pment PK-PTEG-256404-GO-RFQ / O 4. Project Management, M Request for Quota Single Stage - One E IDA / 59820 Post Open - National 35,000.00 34,327.89 Signed 2021-10-15 2021-10-07 2021-11-16 2021-10-27 2022-05-15 ffice Furniture - Tourism Dep onitoring and Evaluation tions nvelope artment PK-PTEG-256408-GO-RFQ / O ffice Equipment - Tourism De 4. Project Management, M Request for Quota Single Stage - One E Pending Impl IDA / 59820 Post Open - National 24,000.00 0.00 2021-10-15 2021-11-19 2022-05-18 partment onitoring and Evaluation tions nvelope ementation DSLR, AC, Generator 15 KV, Refrigirator, Fax Machine PK-PTEG-256411-GO-RFQ / I T Equipment - Tourism Depar 4. Project Management, M Request for Quota Single Stage - One E IDA / 59820 Post Open - National 25,000.00 8,175.37 Signed 2021-10-15 2021-10-11 2021-11-19 2021-10-29 2022-05-18 tment onitoring and Evaluation tions nvelope LEDs, Printers, Smart Phones , Video Conferencing System Page 2 PK-PTEG-271627-GO-RFB / S olid Waste Management Equi 3. Public Investment Facilit Single Stage - One E pment IDA / 59820 Post Request for Bids Open - National 200,000.00 148,710.58 Signed 2022-01-05 2022-01-10 2022-01-07 2022-01-13 2022-02-06 2022-02-11 2022-02-13 2022-02-22 2022-02-27 2022-03-25 2022-08-26 y nvelope 10 Mini Tippers 05 Mechanical Sweepers (Tra ctor driven) PK-PTEG-222318-GO-RFB / G 3. Public Investment Facilit Single Stage - One E IDA / 59820 Post Request for Bids Open - National 165,000.00 0.00 Canceled 2021-03-10 2021-03-15 2021-04-14 2021-04-24 2021-05-15 2021-11-11 olf Carts & Heritage Rikshaw y nvelope s PK-PTEG-227444-GO-RFB / S 3. Public Investment Facilit Single Stage - One E olar Power Energy System for IDA / 59820 Post Request for Bids Open - National 410,000.00 0.00 Canceled 2021-04-02 2021-04-06 2021-04-04 2021-04-08 2021-05-06 2021-05-21 2021-06-16 2022-06-11 y nvelope Heritage Sites PK-PTEG-275532-GO-RFB / D 3. Public Investment Facilit Open - Internationa Single Stage - One E IDA / 59820 Prior Request for Bids 3,000,000.00 0.00 Canceled 2022-02-11 2022-05-06 2022-02-16 2022-05-07 2022-04-02 2022-06-20 2022-04-16 2022-08-25 2022-05-21 2022-11-17 ouble Decker Buses - 9 buses y l nvelope PK-PTEG-283628-GO-RFB / P 3. Public Investment Facilit Single Stage - One E re-fabricated Containers for IDA / 59820 Post Request for Bids Open - National 240,000.00 0.00 Canceled 2022-03-18 2022-03-23 2022-04-22 2022-04-29 2022-05-20 2022-11-16 y nvelope Rescue Services - Murree Im plementation Plan PK-PTEG-283630-GO-RFB / R 3. Public Investment Facilit Single Stage - One E ecovery Vehicles for Rescue IDA / 59820 Post Request for Bids Open - National 400,000.00 0.00 Canceled 2022-03-18 2022-03-23 2022-04-22 2022-04-29 2022-05-20 2022-11-16 y nvelope Services - Murree Implement ation Plan PK-PTEG-283631-GO-RFB / A 3. Public Investment Facilit Single Stage - One E mbulances with fabrication R IDA / 59820 Post Request for Bids Open - National 600,000.00 0.00 Canceled 2022-03-18 2022-03-23 2022-04-22 2022-05-06 2022-05-27 2022-11-23 y nvelope escue Services - Murree Impl ementation Plan PK-PTEG-283632-GO-RFB / R 3. Public Investment Facilit Single Stage - One E escue Equipment for Rescue IDA / 59820 Post Request for Bids Open - National 300,000.00 0.00 Canceled 2022-03-18 2022-03-23 2022-04-22 2022-05-06 2022-05-27 2022-11-23 y nvelope Services - Murree Implement ation Plan PK-PTEG-283634-GO-RFQ / R 3. Public Investment Facilit Request for Quota Single Stage - One E ehabilitation of Takht-e-Babri IDA / 59820 Post Open - National 100,000.00 32,388.30 Signed 2022-03-16 2022-03-16 2022-04-16 2022-03-30 2022-06-15 y tions nvelope , Kalar Kahar PK-PTEG-286749-GO-RFQ / A 3. Public Investment Facilit Request for Quota Single Stage - One E rcheological Laboratory Equi IDA / 59820 Post Open - National 68,000.00 47,017.08 Signed 2022-03-30 2022-05-16 2022-05-05 2022-06-21 2022-11-01 y tions nvelope pment - Directorate of Arche ology PK-PTEG-293035-GO-RFB / V 4. Project Management, M Single Stage - One E Pending Impl ehicles for PTEGP (PMU-Touri IDA / 59820 Post Request for Bids Open - National 750,000.00 0.00 2022-05-09 2022-05-14 2022-06-11 2022-06-18 2022-07-02 2023-06-27 onitoring and Evaluation nvelope ementation sm Department and C&W) & IDAP PK-PTEG-295160-GO-RFB / P 3. Public Investment Facilit Single Stage - One E rocurement of Architectural a IDA / 59820 Post Request for Bids Open - National 725,000.00 0.00 Canceled 2022-06-26 2022-07-01 2022-07-31 2022-08-14 2022-09-11 2023-03-10 y nvelope nd Civil Engineering related S oftware PK-PTEG-295161-GO-RFB / P rocurement of Computer Equ 3. Public Investment Facilit Single Stage - One E Pending Impl IDA / 59820 Post Request for Bids Open - National 795,000.00 0.00 2022-06-27 2022-07-02 2022-08-01 2022-08-15 2022-09-19 2023-03-18 ip. Drones, Terrestrial Laser y nvelope ementation Scanner & Total Station for I DAP PK-PTEG-302801-GO-RFQ / S upply of Uniforms and relate 3. Public Investment Facilit Request for Quota Single Stage - One E IDA / 59820 Post Open - National 70,000.00 0.00 Signed 2022-07-18 2022-07-18 2022-08-20 2023-02-16 d accessories for Tourism Sq y tions nvelope uad - Tourism Department PK-PTEG-302808-GO-RFB / S upply & Installation of Revers 3. Public Investment Facilit Single Stage - One E IDA / 59820 Post Request for Bids Open - National 500,000.00 0.00 Canceled 2022-07-25 2022-08-31 2022-07-30 2022-09-02 2022-08-29 2022-09-12 2022-10-10 2023-04-08 ible Tuck shops & Washroom y nvelope s - Tourist sites Punjab PK-PTEG-302810-GO-RFQ / S 3. Public Investment Facilit Request for Quota Single Stage - One E Pending Impl upply of Garbage Collection IDA / 59820 Post Open - National 72,000.00 0.00 2022-07-23 2022-09-17 2023-03-16 y tions nvelope ementation Carts - Tourist Sites Punjab PK-PTEG-303027-GO-RFQ / S 3. Public Investment Facilit Request for Quota Single Stage - One E Under Imple upply & Installation of SMD S IDA / 59820 Post Open - National 50,000.00 0.00 2022-07-20 2022-07-15 2022-08-17 2022-10-16 y tions nvelope mentation creens - Murree District PK-PTEG-317860-GO-RFQ / P unjab Tourism Squad - Procur 3. Public Investment Facilit Request for Quota Single Stage - One E IDA / 59820 Post Open - National 96,000.00 0.00 Signed 2022-10-05 2022-11-01 2023-01-30 ement of equipment for cap y tions nvelope acity building of PTS PK-PTEG-319157-GO-RFB / S upply & Installation of Solar P ower System (Jahangir Tomb, Lahore, Shal 3. Public Investment Facilit Single Stage - One E amar Gardens, Lahore, Hiran IDA / 59820 Post Request for Bids Open - National 430,000.00 0.00 Canceled 2022-10-03 2022-11-10 2022-10-08 2022-11-11 2022-11-19 2022-12-19 2023-01-23 2023-07-22 y nvelope Minar, Sheikhupura, Rohtas F ort, Jhelum, Taxila Museum, Taxila Rawalpindi, Wah Gard ens Wah Rawalpindi & Harap pa Museum & Site, Sahiwal ) PK-PTEG-324234-GO-RFB / S upply & Installation of Revers 3. Public Investment Facilit Single Stage - One E IDA / 59820 Post Request for Bids Open - National 550,000.00 0.00 Signed 2022-11-01 2022-11-10 2022-11-02 2022-11-11 2022-12-02 2022-12-13 2022-12-05 2022-12-20 2022-12-11 2023-03-11 ible Tuck shops & Washroom y nvelope s - Tourist sites Punjab PK-PTEG-335666-GO-RFB / S 3. Public Investment Facilit Single Stage - One E Under Imple upply & Installation of Solar P IDA / 59820 Post Request for Bids Open - National 500,000.00 0.00 2023-01-16 2023-01-17 2023-01-21 2023-03-04 2023-02-27 2023-04-03 2023-05-08 2023-08-06 y nvelope mentation ower System PK-PTEG-351380-GO-RFB / P 3. Public Investment Facilit Open - Internationa Single Stage - One E Under Imple rocurement of 06-Double De IDA / 59820 Post Request for Bids 2,000,000.00 0.00 2023-03-27 2023-05-01 2023-04-01 2023-05-20 2023-05-13 2023-05-28 2023-06-03 2023-11-30 y l nvelope mentation cker Bus (Diesel Hybrid) PK-PTEG-351387-GO-RFQ / P 3. Public Investment Facilit Request for Quota Single Stage - One E Under Imple IDA / 59820 Post Open - National 575,000.00 0.00 2023-03-31 2023-04-28 2023-07-27 rocurement of 05-Coasters ( y tions nvelope mentation Diesel) PK-PTEG-351403-GO-RFQ / P 3. Public Investment Facilit Request for Quota Single Stage - One E Under Imple IDA / 59820 Post Open - National 400,000.00 0.00 2023-03-31 2023-04-30 2023-07-29 rocurement of 07-VANS y tions nvelope mentation PK-PTEG-351418-GO-RFQ / F 3. Public Investment Facilit Request for Quota Single Stage - One E Under Imple urniture and Inverter Floor St IDA / 59820 Post Open - National 53,000.00 0.00 2023-03-31 2023-04-16 2023-06-15 y tions nvelope mentation anding Cabinet A.C for Lahor e Museum Page 3 PK-PTEG-351405-GO-RFQ / P rocurement of I.T. Equipment for Lahore Museum Lot-1: Desktop Computer, est 3. Public Investment Facilit Request for Quota Single Stage - One E Under Imple imated budget=USD$=15,00 IDA / 59820 Post Open - National 50,000.00 0.00 2023-03-31 2023-04-27 2023-07-26 y tions nvelope mentation 0/- Lot-2: Laptop, estimated bud get=USD$=12,00/- Lot-3: Server 96TB storage, e stimated budget=USD$=33, 800/- PK-PTEG-353673-GO-RFQ / P 3. Public Investment Facilit Request for Quota Single Stage - One E Under Imple rocurement of Office Equipm IDA / 59820 Post Open - National 15,000.00 0.00 2023-03-29 2023-05-02 2023-07-31 y tions nvelope mentation ent for Lahore Museum PK-PTEG-355575-GO-RFQ / P ROCUREMENT OF EQUIPMEN T FOR AUDIO-VIDEOGRAPHY 3. Public Investment Facilit Request for Quota Single Stage - One E Pending Impl IDA / 59820 Post Open - National 90,000.00 0.00 2023-04-15 2023-05-10 2023-08-08 STUDIO, PORTABLE PUBLIC A y tions nvelope ementation DDRESS SYSTEM AND WEBIN AR ROOM FOR LAHORE MUSE UM PK-PTEG-363800-GO-RFQ / E QUIPMENT (LED) LIGHTS FOR 2. Private Investment and Request for Quota Single Stage - One E Pending Impl IDA / 59820 Post Open - National 16,000.00 0.00 2023-05-29 2023-06-29 2023-09-27 ILLUMINATION OF FRONT ELE Entrepreneurship Promotion tions nvelope ementation VATION FOR LAHORE MUSEU M BUILDING PK-PTEG-363804-GO-RFQ / P ROCUREMENT OF GOLF CART 2. Private Investment and Request for Quota Single Stage - One E Pending Impl IDA / 59820 Post Open - National 95,000.00 0.00 2023-05-29 2023-06-21 2023-09-19 FOR TDCP AT CHANGA MANG Entrepreneurship Promotion tions nvelope ementation A RESORT, LAHORE PK-PTEG-365225-GO-RFB / P 1. Policy, Institutions and rocurement of 11-Seater Golf Single Stage - One E Pending Impl IDA / 59820 Governance for Tourism Dev Post Request for Bids Open - National 300,000.00 0.00 2023-06-05 2023-06-07 2023-07-03 2023-07-08 2023-07-19 2024-01-15 Carts for Walled City Lahore nvelope ementation elopment Authority (WCLA) PK-PTEG-365229-GO-RFQ / P 1. Policy, Institutions and Request for Quota Single Stage - One E Pending Impl rocurement of Coaster for W IDA / 59820 Governance for Tourism Dev Post Open - National 120,000.00 0.00 2023-06-10 2023-07-03 2023-12-30 tions nvelope ementation alled City Lahore Authority ( elopment WCLA) PK-PTEG-365231-GO-RFQ / P 1. Policy, Institutions and Request for Quota Single Stage - One E Pending Impl rocurement of High Roof-VAN IDA / 59820 Governance for Tourism Dev Post Open - National 120,000.00 0.00 2023-06-07 2023-07-01 2023-12-28 tions nvelope ementation S for Walled City Lahore Auth elopment ority (WCLA) NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PK-PTEG-48673-NC-RFQ / Ev 4. Project Management, M Request for Quota Single Stage - One E IDA / 59820 Post Open - National 30,000.00 27,702.75 Signed 2018-02-14 2018-02-15 2018-02-26 2018-02-13 2018-03-08 ent Management Firm - Proje onitoring and Evaluation tions nvelope ct Launch PK-PTEG-91147-NC-RFQ / Su 4. Project Management, M Request for Quota Single Stage - One E IDA / 59820 Post Open - National 35,000.00 10,591.35 Signed 2019-01-12 2019-02-13 2019-03-09 2019-04-22 2019-09-05 rvey Firm for Data collection onitoring and Evaluation tions nvelope PK-PTEG-103229-NC-RFQ / T 4. Project Management, M Request for Quota Single Stage - One E ourism Sector regulation and IDA / 59820 Post Open - National 20,000.00 0.00 Canceled 2019-03-04 2019-04-29 2019-06-30 onitoring and Evaluation tions nvelope Inspection Mapping Exercise -4 Months PK-PTEG-103234-NC-RFQ / D ocumentary Preparation of K 4. Project Management, M Request for Quota Single Stage - One E IDA / 59820 Post Open - National 100,000.00 0.00 Canceled 2019-03-10 2019-05-05 2019-06-30 artarpur site (Non Consultanc onitoring and Evaluation tions nvelope y Services) 2-Months PK-PTEG-103260-NC-RFQ / T 4. Project Management, M Request for Quota Single Stage - One E raining need assessment of S IDA / 59820 Post Open - National 100,000.00 0.00 Canceled 2019-03-04 2019-04-29 2019-06-30 onitoring and Evaluation tions nvelope kill training 4-Months PK-PTEG-141301-NC-DIR / Pr 4. Project Management, M Pending Impl ocurement of Planning & Mon IDA / 59820 Post Direct Selection Direct 1,260.00 0.00 2019-10-21 2019-10-26 2019-11-08 2019-11-18 onitoring and Evaluation ementation itoring Software (SMARTSHEE T) PK-PTEG-140344-NC-DIR / H all and Auditorium facility ch 1. Policy, Institutions and arges for conduct of Lahore I IDA / 59820 Governance for Tourism Dev Post Direct Selection Direct 50,000.00 0.00 Canceled 2019-10-23 2019-10-28 2019-12-07 2019-12-28 nternational Tourism Expo (LI elopment TE) at Expo center Lahore PK-PTEG-134818-NC-RFQ / H 4. Project Management, M Request for Quota Single Stage - One E IDA / 59820 Post Open - National 20,000.00 0.00 Canceled 2019-09-19 2019-09-24 2019-09-27 iring of Firm for Event Manag onitoring and Evaluation tions nvelope ement PK-PTEG-159994-NC-RFQ / E 3. Public Investment Facilit Request for Quota Single Stage - One E IDA / 59820 Post Open - National 12,000.00 4,442.20 Signed 2020-02-24 2020-02-25 2020-03-18 2020-03-18 2022-03-08 nvironment Laboratory y tions nvelope PK-PTEG-300757-NC-RFQ / T 3. Public Investment Facilit Request for Quota Single Stage - One E Under Imple opographic Survey of Archeol IDA / 59820 Post Open - National 100,000.00 0.00 2022-07-01 2022-07-18 2022-08-05 2023-02-01 y tions nvelope mentation ogical Sites PK-PTEG-306845-NC-RFB / Hi 1. Policy, Institutions and ring of Training Service Provi Single Stage - One E IDA / 59820 Governance for Tourism Dev Post Request for Bids Open - National 2,000,000.00 0.00 Canceled 2022-08-04 2022-10-03 2022-08-09 2022-09-08 2022-09-28 2022-10-26 2023-04-24 ders (TSPs) for Skills Develop nvelope elopment ment - Tourism Sector Punja b CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PK-PTEG-32421-CS-QCBS / H 3. Public Investment Facilit UN Agencies (Dire iring of Heritage Firm IDA / 59820 Prior Direct 500,000.00 2,834,843.00 Signed 2018-01-27 2018-02-19 2021-01-29 y ct) UNESCO PK-PTEG-32423-CS-QCBS / H 1. Policy, Institutions and Quality And Cost- Open - Internationa Under Implement iring of firm for Legal & Regul IDA / 59820 Governance for Tourism Dev Prior 750,000.00 0.00 2017-12-25 2018-07-24 2018-01-15 2018-02-28 2018-03-28 2018-04-27 2018-06-01 2018-07-06 2019-07-06 Based Selection l ation atory Review elopment Page 4 PK-PTEG-32425-CS-CQS / Int 4. Project Management, M Least Cost Selecti ernal Audit Firm IDA / 59820 Post Open - National 150,000.00 0.00 Canceled 2017-12-18 2018-01-08 2018-02-21 2018-03-21 2018-04-20 2018-05-25 2018-06-29 2022-12-30 onitoring and Evaluation on Estimated cost for 5 years PK-PTEG-32422-CS-QCBS / Fi 2. Private Investment and Quality And Cost- Open - Internationa IDA / 59820 Post 1,500,000.00 0.00 Canceled 2018-01-31 2018-12-28 2018-02-16 2018-03-09 2018-04-23 2018-05-08 2018-05-22 2018-06-05 2020-10-13 rm Hiring for Skills Developm Entrepreneurship Promotion Based Selection l ent PK-PTEG-32418-CS-QCBS / S 3. Public Investment Facilit Quality And Cost- Open - Internationa upervision & Quality Assuran IDA / 59820 Prior 952,380.00 94,799.46 Signed 2018-01-15 2019-02-11 2018-01-30 2019-02-11 2018-02-27 2020-05-08 2018-04-01 2020-04-15 2018-04-17 2020-05-09 2018-05-08 2020-07-17 2018-05-22 2020-07-09 2020-09-29 y Based Selection l ce Firm Civil Works consultant firm - PISC PK-PTEG-32427-CS-CQS / Up 1. Policy, Institutions and Quality And Cost- Open - Internationa gradation of Existing Institute IDA / 59820 Governance for Tourism Dev Prior 750,000.00 0.00 Canceled 2018-02-01 2018-02-16 2018-03-12 2018-04-24 2018-05-09 2018-05-23 2018-06-06 2019-06-06 Based Selection l s - Hiring of firm elopment PK-PTEG-51948-CS-CQS / Int 4. Project Management, M Consultant Qualifi IDA / 59820 Post Open - National 150,000.00 0.00 Canceled 2018-03-06 2018-05-01 2018-03-26 2018-05-10 2018-05-17 2018-06-14 2023-04-30 ernal Audit Firm - 5 Years Co onitoring and Evaluation cation Selection ntract PK-PTEG-64589-CS-CQS / Up 1. Policy, Institutions and Consultant Qualifi gradation of Existing Institute IDA / 59820 Governance for Tourism Dev Post Open - National 400,000.00 0.00 Canceled 2018-06-11 2018-06-19 2018-07-02 2018-08-15 2018-09-14 2018-10-19 2019-06-28 cation Selection s - Restructuring of TDCP elopment PK-PTEG-93553-CS-QCBS / R 1. Policy, Institutions and Quality And Cost- IDA / 59820 Post Open - National 500,000.00 0.00 Canceled 2019-01-14 2019-01-08 2019-02-04 2019-02-13 2019-03-20 2019-04-17 2019-05-17 2019-06-21 2019-07-26 2020-07-25 e-structuring of TDCP Governance for Tourism Dev Based Selection elopment PK-PTEG-110939-CS-CQS / D 4. Project Management, M Consultant Qualifi Under Implement ocumentary Preparation of K IDA / 59820 Post Open - National 100,000.00 0.00 2019-04-22 2019-05-10 2019-05-13 2019-07-08 2019-06-26 2019-08-21 2019-07-26 2019-08-30 2020-04-30 onitoring and Evaluation cation Selection ation artarpur site PK-PTEG-110942-CS-CQS / T 4. Project Management, M Consultant Qualifi Under Implement IDA / 59820 Post Open - National 100,000.00 0.00 2019-04-22 2019-05-10 2019-05-13 2019-07-08 2019-06-26 2019-07-26 2019-08-30 2020-04-30 raining need assessment of S onitoring and Evaluation cation Selection ation kill training PK-PTEG-128723-CS-LCS / Hi 4. Project Management, M Least Cost Selecti IDA / 59820 Post Open - National 250,000.00 0.00 Canceled 2019-08-25 2020-03-09 2019-09-15 2019-10-29 2019-11-26 2019-12-26 2020-01-30 2020-03-05 2023-03-05 ring of Media Firm onitoring and Evaluation on PK-PTEG-103226-CS-LCS / Hi 4. Project Management, M Least Cost Selecti IDA / 59820 Post Open - National 150,000.00 0.00 Canceled 2019-02-27 2019-03-08 2019-03-20 2019-03-11 2019-05-03 2019-07-19 2019-05-31 2019-08-23 2019-06-30 2019-08-04 2019-09-08 2022-06-30 ring of Internal Audit Firm 5- onitoring and Evaluation on Years PK-PTEG-32414-CS-CQS / Me 2. Private Investment and Consultant Qualifi IDA / 59820 Prior Open - National 2,500,000.00 0.00 Canceled 2017-11-20 2018-09-20 2017-12-11 2018-01-24 2018-02-23 2018-03-30 2020-11-23 dia Firm hiring Entrepreneurship Promotion cation Selection PK-PTEG-163250-CS-QCBS / I 1. Policy, Institutions and Quality And Cost- IDA / 59820 Post Open - National 300,000.00 188,305.86 Signed 2020-03-13 2020-03-09 2020-04-02 2020-03-13 2020-04-19 2020-07-29 2020-05-19 2020-08-31 2020-05-29 2020-09-17 2020-06-15 2020-10-20 2020-07-06 2020-12-17 2021-07-01 SMP Qila Kohna Qasim Bagh Governance for Tourism Dev Based Selection elopment PK-PTEG-164014-CS-QCBS / 1. Policy, Institutions and Quality And Cost- IDA / 59820 Post Open - National 250,000.00 544,997.13 Signed 2020-03-12 2020-03-11 2020-04-02 2020-03-13 2020-05-16 2020-07-13 2020-06-13 2020-08-25 2020-07-13 2020-09-16 2020-08-17 2020-10-05 2020-09-21 2021-02-04 2023-09-06 Media Firm Hiring Governance for Tourism Dev Based Selection elopment PK-PTEG-183974-CS-QCBS / Destination Investment & Ma 1. Policy, Institutions and Quality And Cost- Open - Internationa nagement Plans (DIMPs) Con IDA / 59820 Governance for Tourism Dev Prior 3,000,000.00 614,175.00 Signed 2020-07-16 2020-07-24 2020-07-26 2020-08-28 2020-08-30 2020-11-26 2020-09-27 2021-01-11 2020-10-12 2021-03-03 2020-11-02 2021-03-16 2020-12-07 2021-05-15 2022-12-07 Based Selection l sultancy Services - elopment IDC (Framework contract) PK-PTEG-206682-CS-CQS / E 3. Public Investment Facilit Consultant Qualifi Under Implement nvironment Impact Assessme IDA / 59820 Post Open - National 100,000.00 0.00 2020-12-01 2020-12-15 2020-12-16 2020-12-30 2021-01-06 2021-02-11 2021-01-13 2021-01-25 2022-01-25 y cation Selection ation nt Services PK-PTEG-223666-CS-QCBS / 3. Public Investment Facilit Quality And Cost- Open - Internationa Pending Impleme Taxila Museum Upgradation - IDA / 59820 Post 450,000.00 0.00 2021-03-19 2021-04-03 2021-04-20 2021-05-18 2021-06-01 2021-06-22 2021-07-13 2022-07-13 y Based Selection l ntation Consulting Firm PK-PTEG-228305-CS-CQS / A 3. Public Investment Facilit Consultant Qualifi Pending Impleme rchitectural Firm for Design o IDA / 59820 Post Open - National 100,000.00 0.00 2021-04-11 2021-04-26 2021-05-17 2021-05-24 2021-06-07 2021-12-04 y cation Selection ntation f New Museum at Harappa PK-PTEG-246068-CS-QCBS / 3. Public Investment Facilit Quality And Cost- Under Implement Design Review and Supervisi IDA / 59820 Post Open - National 550,000.00 0.00 2021-08-02 2021-08-02 2021-08-17 2021-09-07 2021-10-05 2021-10-19 2021-11-02 2021-11-23 2022-11-23 y Based Selection ation on Firm (Roads & Buildings) PK-PTEG-267389-CS-CQS / S 3. Public Investment Facilit Consultant Qualifi Under Implement olar Energy - Design & Super IDA / 59820 Post Open - National 45,000.00 0.00 2021-12-13 2021-12-14 2021-12-28 2022-01-20 2022-01-26 2022-04-05 2022-02-09 2022-02-23 2023-02-18 y cation Selection ation vision Firm PK-PTEG-295159-CS-CQS / T 3. Public Investment Facilit Consultant Qualifi Under Implement opographic & Utilities Survey IDA / 59820 Post Open - National 100,000.00 0.00 2022-05-20 2022-05-30 2022-06-04 2022-07-03 2022-07-17 2022-08-14 2023-02-10 y cation Selection ation - IDAP Hiran Minar PK-PTEG-295158-CS-QCBS / Services for Preparation of As 3. Public Investment Facilit Consultant Qualifi Pending Impleme -Built Drawings & Scan-Base IDA / 59820 Post Open - National 175,000.00 0.00 2022-06-26 2022-07-17 2022-08-14 2022-08-28 2022-09-11 2023-03-10 y cation Selection ntation d 3D Models - IDAP Hiran Minar, Rohtas Fort & Ta xila PK-PTEG-320789-CS-CQS / D ESIGN AND RESIDENT SUPER 3. Public Investment Facilit Consultant Qualifi Under Implement VISION OF URBAN REHABILIT IDA / 59820 Post Open - National 150,000.00 0.00 2022-10-12 2022-11-10 2022-10-22 2022-12-28 2022-11-16 2022-12-01 2023-01-05 2024-10-31 y cation Selection ation ATION OF FAÇADE AND ESTA BLISHMENT OF PARKING ARE A - BHATTI GATE PK-PTEG-320794-CS-CQS / D ESIGN AND RESIDENT SUPER 3. Public Investment Facilit Consultant Qualifi Under Implement VISION OF URBAN REHABILIT IDA / 59820 Post Open - National 250,000.00 0.00 2022-10-12 2022-11-10 2022-10-27 2022-12-28 2022-11-20 2022-12-05 2023-01-09 2024-10-31 y cation Selection ation ATION OF INFRASTRUCTURE I MPROVEMENT - BHATTI GATE PK-PTEG-320797-CS-CQS / D ESIGN AND RESIDENT SUPER 3. Public Investment Facilit Consultant Qualifi IDA / 59820 Post Open - National 200,000.00 0.00 Under Review 2022-10-12 2022-11-10 2022-10-27 2022-11-20 2022-12-05 2022-12-25 2024-10-31 VISION FIRM FOR QILA KOHN y cation Selection A QASIM BAGH PROJECT PK-PTEG-330668-CS-QCBS / 3. Public Investment Facilit Quality And Cost- Under Implement Hiring of Firm for Digital Cura IDA / 59820 Post Open - National 600,000.00 0.00 2022-12-13 2022-12-06 2023-01-17 2023-01-02 2023-01-28 2023-03-04 2023-03-14 2023-03-27 2023-04-20 2024-04-19 y Based Selection ation tion of Lahore and Taxila Mus eum INDIVIDUAL CONSULTANTS Page 5 Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PK-PTEG-32377-CS-INDV / So 4. Project Management, M Individual Consult cial Gender Specialist IDA / 59820 Post Open 189,450.00 26,773.76 Signed 2017-10-17 2017-08-01 2017-12-05 2018-01-02 2017-12-26 2018-01-01 2018-01-30 2018-02-01 2018-12-20 onitoring and Evaluation ant Selection Estimated amount for 5 year s PK-PTEG-32381-CS-INDV / E 4. Project Management, M Individual Consult nvironmental Specialist IDA / 59820 Post Open 189,450.00 24,361.53 Signed 2017-10-17 2017-07-17 2017-12-05 2017-12-26 2017-12-11 2018-01-30 2018-01-11 2019-01-10 onitoring and Evaluation ant Selection Estimated amount for 5 year s PK-PTEG-32410-CS-INDV / C 4. Project Management, M Individual Consult oordinator DC Bahawalpur IDA / 59820 Post Open 85,714.00 0.00 Canceled 2017-11-06 2018-09-18 2017-12-25 2018-01-15 2018-02-19 2019-01-30 onitoring and Evaluation ant Selection Estimated cost for 5 years PK-PTEG-32411-CS-INDV / C 4. Project Management, M Individual Consult oordinator DC Rajanpur IDA / 59820 Post Open 85,714.00 0.00 Canceled 2017-11-06 2018-09-18 2017-12-25 2018-01-15 2018-02-19 2019-01-30 onitoring and Evaluation ant Selection Estimated cost for 5 years PK-PTEG-40044-CS-INDV / R 4. Project Management, M Individual Consult IDA / 59820 Post Open 85,714.00 5,361.93 Signed 2017-12-18 2017-10-02 2018-02-05 2017-10-27 2018-02-26 2017-11-27 2018-04-02 2017-10-27 2018-09-28 esearch Associate onitoring and Evaluation ant Selection PK-PTEG-40046-CS-INDV / R 4. Project Management, M Individual Consult esearch Associate IDA / 59820 Post Open 85,714.00 5,361.93 Signed 2017-12-18 2017-12-04 2018-02-05 2018-01-03 2018-02-26 2018-01-02 2018-04-02 2018-01-08 2019-04-30 onitoring and Evaluation ant Selection Estimated cost for 5 years PK-PTEG-32376-CS-INDV / Fi 4. Project Management, M Individual Consult nancial Management Speciali IDA / 59820 Post Open 189,450.00 21,440.76 Signed 2017-10-17 2017-12-05 2017-09-11 2017-12-26 2017-09-13 2018-01-30 2017-09-26 2018-10-10 onitoring and Evaluation ant Selection st Estimated amount for 5 year s PK-PTEG-32398-CS-INDV / M 4. Project Management, M Individual Consult & E Specialist IDA / 59820 Post Open 225,000.00 29,233.84 Signed 2017-10-17 2017-07-01 2017-12-05 2017-09-11 2017-12-26 2017-09-25 2018-01-30 2017-09-26 2018-10-01 onitoring and Evaluation ant Selection Estimated cost for 5 years PK-PTEG-32389-CS-INDV / Pr 4. Project Management, M Individual Consult oject Director IDA / 59820 Prior Open 600,000.00 0.00 Canceled 2017-10-17 2018-08-16 2017-12-05 2017-12-26 2018-02-19 2019-02-19 onitoring and Evaluation ant Selection Estimated amount for 5 year s PK-PTEG-32391-CS-INDV / D 4. Project Management, M Individual Consult eputy Project Director IDA / 59820 Prior Open 370,000.00 0.00 Canceled 2017-10-17 2017-12-05 2017-12-26 2018-01-30 2018-10-25 onitoring and Evaluation ant Selection Estimated cost for 5 years PK-PTEG-40047-CS-INDV / R 4. Project Management, M Individual Consult esearch Associate - Account/ IDA / 59820 Post Open 85,714.00 14,616.92 Signed 2017-12-18 2017-09-11 2018-01-21 2017-12-08 2018-01-28 2017-12-11 2018-02-19 2017-12-12 2019-01-02 onitoring and Evaluation ant Selection Admin Estimated cost for 5 years PK-PTEG-68956-CS-INDV / Pu 4. Project Management, M Individual Consult IDA / 59820 Post Open 47,000.00 0.00 Canceled 2018-07-16 2018-09-03 2018-09-24 2018-10-29 2019-04-27 blic Sector Development Spe onitoring and Evaluation ant Selection cialist PK-PTEG-73991-CS-INDV / Pr 4. Project Management, M Individual Consult IDA / 59820 Post Open 47,000.00 17,457.63 Signed 2018-08-16 2019-01-14 2018-10-04 2019-09-20 2018-10-25 2019-09-24 2018-11-29 2019-09-24 2019-05-28 ivate Sector Development Sp onitoring and Evaluation ant Selection ecialist PK-PTEG-93482-CS-INDV / To 4. Project Management, M Individual Consult urism Expert IDA / 59820 Post Open 40,000.00 25,119.61 Signed 2019-01-11 2019-09-30 2019-03-01 2020-02-27 2019-03-22 2019-04-26 2020-04-09 2019-10-23 onitoring and Evaluation ant Selection (One year estimated cost) PK-PTEG-103221-CS-INDV / 4. Project Management, M Individual Consult Monitoring & Evaluation Spec IDA / 59820 Post Open 150,000.00 21,524.65 Signed 2019-02-27 2019-05-04 2019-04-17 2019-11-20 2019-05-08 2019-06-12 2019-11-26 2022-06-30 onitoring and Evaluation ant Selection ialist 3-Years and 4 Months PK-PTEG-103232-CS-INDV / P 4. Project Management, M Individual Consult rocurement & Contract Admi IDA / 59820 Post Open 16,000.00 0.00 Canceled 2019-02-27 2019-04-17 2019-05-08 2019-06-12 2020-04-30 onitoring and Evaluation ant Selection nistration Support 1-Year PK-PTEG-32401-CS-INDV / C 4. Project Management, M Individual Consult oordinator DC Rawalpindi IDA / 59820 Post Open 85,714.00 0.00 Canceled 2017-11-06 2018-09-18 2017-12-25 2018-01-15 2018-02-19 2019-01-30 onitoring and Evaluation ant Selection Estimated amount for 5 year s PK-PTEG-32405-CS-INDV / C 4. Project Management, M Individual Consult oordinator DC Gujranwala IDA / 59820 Post Open 85,714.00 0.00 Canceled 2017-11-06 2018-09-18 2017-12-25 2018-01-15 2018-02-19 2019-01-30 onitoring and Evaluation ant Selection Estimated amount for 5 year s PK-PTEG-32407-CS-INDV / C 4. Project Management, M Individual Consult oordinator DC Sheikhupura IDA / 59820 Post Open 85,714.00 0.00 Canceled 2017-11-06 2018-09-18 2017-12-25 2018-01-15 2018-02-19 2019-01-30 onitoring and Evaluation ant Selection Estimated cost for 5 years PK-PTEG-136467-CS-INDV / 4. Project Management, M Individual Consult IDA / 59820 Post Open 170,000.00 0.00 Canceled 2019-10-02 2019-10-03 2019-10-28 2019-11-04 2019-11-18 2022-11-16 Hiring of Sr. Procurement Sp onitoring and Evaluation ant Selection ecialist PK-PTEG-136466-CS-INDV / 4. Project Management, M Individual Consult Pending Impleme IDA / 59820 Post Open 4,260.00 0.00 2019-10-03 2019-10-12 2019-10-14 2019-10-19 2020-02-16 Hiring of Graphic Designer onitoring and Evaluation ant Selection ntation PK-PTEG-138460-CS-INDV / 4. Project Management, M Individual Consult Hiring of Monitoring & Evalua IDA / 59820 Post Open 76,600.00 0.00 Canceled 2019-10-03 2019-10-29 2019-11-05 2019-11-13 2022-10-31 onitoring and Evaluation ant Selection tion (M&E) Specialist PK-PTEG-139666-CS-INDV / 4. Project Management, M Individual Consult IDA / 59820 Post Open 170,000.00 0.00 Canceled 2019-10-14 2019-11-16 2019-11-26 2019-12-10 2023-10-31 Hiring of Sr. Communication onitoring and Evaluation ant Selection Specialist PK-PTEG-139667-CS-INDV / 4. Project Management, M Individual Consult IDA / 59820 Post Open 87,500.00 8,612.44 Signed 2019-10-14 2019-12-02 2019-11-09 2020-01-22 2019-11-16 2020-01-23 2019-11-30 2020-01-24 2023-10-30 Hiring of Research Associate onitoring and Evaluation ant Selection PK-PTEG-103217-CS-INDV / 4. Project Management, M Individual Consult Senior Communication Speci IDA / 59820 Prior Open 168,000.00 0.00 Canceled 2019-02-27 2019-03-07 2019-04-17 2019-05-08 2019-06-12 2022-06-30 onitoring and Evaluation ant Selection alist 3-Years and 4 Months PK-PTEG-145106-CS-INDV / P 4. Project Management, M Individual Consult IDA / 59820 Post Limited 150,000.00 26,016.25 Signed 2019-11-11 2019-11-08 2019-11-12 2019-11-08 2019-11-13 2019-11-19 2019-11-14 2019-11-20 2022-09-14 roject Manager onitoring and Evaluation ant Selection PK-PTEG-145603-CS-INDV / P 4. Project Management, M Individual Consult rocurement and Contract Ad IDA / 59820 Post Limited 12,000.00 8,863.64 Signed 2019-11-14 2019-10-15 2019-11-15 2021-02-24 2019-11-15 2021-03-22 2019-11-15 2021-03-23 2020-11-14 onitoring and Evaluation ant Selection ministration Support Assistan t PK-PTEG-145698-CS-INDV / 4. Project Management, M Individual Consult IDA / 59820 Post Limited 12,000.00 0.00 Canceled 2019-11-14 2019-11-15 2019-11-15 2019-11-15 2020-02-16 Short Term Media Advisor for onitoring and Evaluation ant Selection YASAT Page 6 PK-PTEG-32372-CS-INDV / Se 4. Project Management, M Individual Consult nior Procurement Specialist IDA / 59820 Prior Open 255,000.00 0.00 Canceled 2017-10-17 2017-12-05 2017-12-26 2018-01-30 2018-10-08 onitoring and Evaluation ant Selection Estimated amount for 5 year s PK-PTEG-103202-CS-INDV / 4. Project Management, M Individual Consult Senior Procurement Specialis IDA / 59820 Prior Open 170,000.00 0.00 Canceled 2019-02-27 2019-02-28 2019-04-17 2019-05-08 2019-06-12 2022-06-30 onitoring and Evaluation ant Selection t-3 Years & 4-Months PK-PTEG-145723-CS-INDV / 1. Policy, Institutions and Individual Consult Pending Impleme Short Term Media Consultant IDA / 59820 Governance for Tourism Dev Post Limited 12,000.00 0.00 2019-11-14 2019-11-15 2019-11-15 2019-11-15 2019-11-24 ant Selection ntation for YASA&T. Demand Driven elopment PK-PTEG-151717-CS-INDV / Estimated cost for Project Off icer -1 for 3 years 4. Project Management, M Individual Consult IDA / 59820 Post Limited 45,000.00 10,762.33 Signed 2019-12-24 2019-12-02 2019-12-29 2020-01-02 2019-12-30 2020-01-03 2020-01-07 2021-01-02 We will use limited competiti onitoring and Evaluation ant Selection on as we will select a candid ate from existing pool of can didates. PK-PTEG-151720-CS-INDV / P roject Officer -2 . Estimated cost for 3 years USD 45,000. 4. Project Management, M Individual Consult IDA / 59820 Post Limited 45,000.00 12,197.30 Signed 2019-12-24 2019-12-02 2019-12-29 2020-01-06 2020-01-03 2020-01-10 2020-01-07 2021-01-09 We will use limited competiti onitoring and Evaluation ant Selection on since we have existing po ol of consultants to select fro m. PK-PTEG-32404-CS-INDV / C 4. Project Management, M Individual Consult oordinator DC Chakwal IDA / 59820 Post Open 85,714.00 0.00 Canceled 2017-11-06 2018-09-18 2017-12-25 2018-01-15 2018-02-19 2019-01-30 onitoring and Evaluation ant Selection Estimated cost for 5 years PK-PTEG-32385-CS-INDV / Se 4. Project Management, M Individual Consult nior Communication Specialis IDA / 59820 Prior Open 252,000.00 0.00 Canceled 2017-10-17 2018-08-31 2017-12-05 2017-12-26 2018-01-30 2019-01-30 onitoring and Evaluation ant Selection t Estimated amount for 5 year s PK-PTEG-153682-CS-INDV / 4. Project Management, M Individual Consult Hiring of Procurement Specia IDA / 59820 Post Limited 170,000.00 22,959.63 Signed 2020-01-14 2020-01-01 2020-01-17 2020-01-10 2020-01-18 2020-02-10 2020-01-20 2020-02-11 2023-01-19 onitoring and Evaluation ant Selection list PTEGP- cost for 3 years PK-PTEG-115815-CS-INDV / 4. Project Management, M Individual Consult IDA / 59820 Post Open 168,000.00 0.00 Canceled 2019-05-21 2019-07-09 2019-07-30 2019-09-03 2022-06-30 Senior Communication Speci onitoring and Evaluation ant Selection alist PK-PTEG-32387-CS-INDV / In 4. Project Management, M Individual Consult frastructure Development Sp IDA / 59820 Post Open 189,450.00 0.00 Canceled 2017-10-17 2019-01-21 2017-12-05 2017-12-26 2018-01-30 2019-03-29 onitoring and Evaluation ant Selection ecialist Estimated amount for 5 year s PK-PTEG-162559-CS-INDV / 4. Project Management, M Individual Consult IDA / 59820 Post Limited 100,000.00 18,126.90 Signed 2020-03-09 2020-03-09 2020-03-14 2020-03-06 2020-04-04 2020-03-16 2020-05-09 2020-03-21 2022-04-29 Civil Engineer onitoring and Evaluation ant Selection PK-PTEG-163247-CS-INDV / 4. Project Management, M Individual Consult IDA / 59820 Post Limited 15,000.00 11,229.64 Signed 2020-03-10 2020-03-24 2020-03-15 2020-10-03 2020-04-05 2020-12-11 2020-05-10 2020-12-18 2021-05-10 Assistant Civil Engineer onitoring and Evaluation ant Selection PK-PTEG-190459-CS-INDV / 4. Project Management, M Individual Consult IDA / 59820 Post Open 75,000.00 14,972.86 Signed 2020-09-02 2020-09-01 2020-10-21 2020-11-12 2020-11-11 2020-12-03 2020-12-16 2020-12-08 2021-06-14 Social Safeguard & Gender S onitoring and Evaluation ant Selection pecialist PK-PTEG-196847-CS-INDV / 3. Public Investment Facilit Individual Consult IDA / 59820 Post Limited 20,000.00 12,496.10 Signed 2020-10-05 2020-10-09 2020-10-10 2020-10-16 2020-10-24 2020-11-15 2020-11-17 2020-11-17 2022-11-17 Content Writer - Informative y ant Selection Signboards PK-PTEG-197173-CS-INDV / 3. Public Investment Facilit Individual Consult Under Implement IDA / 59820 Post Limited 20,000.00 0.00 2020-10-09 2022-07-19 2020-10-14 2020-11-04 2020-12-09 2021-12-04 Conservation Architect - PCR y ant Selection ation MP PK-PTEG-228307-CS-INDV / P 4. Project Management, M Individual Consult IDA / 59820 Post Open 20,000.00 12,954.55 Signed 2021-04-26 2021-04-26 2021-05-29 2021-06-04 2021-06-05 2021-06-04 2021-06-19 2021-07-08 2022-06-14 roject Officer - 1 onitoring and Evaluation ant Selection PK-PTEG-228310-CS-INDV / 4. Project Management, M Individual Consult Under Implement IDA / 59820 Post Open 30,000.00 0.00 2021-04-26 2021-09-23 2021-05-29 2021-06-12 2021-06-26 2022-06-21 Architect onitoring and Evaluation ant Selection ation PK-PTEG-232086-CS-INDV / L 4. Project Management, M Individual Consult Under Implement egal Consultant for Tourism IDA / 59820 Post Open 9,500.00 0.00 2021-05-03 2021-04-30 2021-06-05 2021-06-12 2021-06-26 2021-09-24 onitoring and Evaluation ant Selection ation Department PK-PTEG-243329-CS-INDV / 4. Project Management, M Individual Consult Under Implement IDA / 59820 Post Open 45,000.00 0.00 2021-07-16 2021-07-07 2021-08-18 2021-09-01 2021-09-18 2023-04-30 Environment Specialist onitoring and Evaluation ant Selection ation PK-PTEG-256619-CS-INDV / 4. Project Management, M Individual Consult Under Implement IDA / 59820 Post Limited 23,500.00 0.00 2021-11-21 2022-03-25 2021-11-26 2021-12-03 2021-12-17 2022-06-15 Consultant for Integrated Tou onitoring and Evaluation ant Selection ation rism Plan PK-PTEG-264216-CS-INDV / 4. Project Management, M Individual Consult Under Implement IDA / 59820 Post Open 20,000.00 0.00 2021-11-28 2021-12-14 2021-12-24 2021-12-31 2022-01-14 2023-01-09 Research Associate - I onitoring and Evaluation ant Selection ation PK-PTEG-264217-CS-INDV / 4. Project Management, M Individual Consult Under Implement IDA / 59820 Post Open 20,000.00 0.00 2021-11-28 2021-12-14 2021-12-24 2021-12-31 2022-01-14 2023-01-09 Research Associate - II onitoring and Evaluation ant Selection ation PK-PTEG-267380-CS-INDV / P 4. Project Management, M Individual Consult Under Implement IDA / 59820 Post Open 100,000.00 0.00 2021-12-17 2021-12-16 2022-01-26 2022-02-09 2022-02-23 2023-04-30 roject Director onitoring and Evaluation ant Selection ation PK-PTEG-274905-CS-INDV / 4. Project Management, M Individual Consult Under Implement Coordination Officer for Touri IDA / 59820 Post Open 21,000.00 0.00 2022-01-31 2022-01-28 2022-02-26 2022-03-05 2022-03-19 2023-03-14 onitoring and Evaluation ant Selection ation sm Department PK-PTEG-274909-CS-INDV / 4. Project Management, M Individual Consult Under Implement IDA / 59820 Post Open 14,000.00 0.00 2022-01-31 2022-01-28 2022-02-26 2022-03-05 2022-03-19 2023-03-14 Data Analyst for Tourism Dep onitoring and Evaluation ant Selection ation artment PK-PTEG-274911-CS-INDV / 4. Project Management, M Individual Consult Under Implement IDA / 59820 Post Open 14,000.00 0.00 2022-01-31 2022-01-28 2022-02-26 2022-03-05 2022-03-19 2023-03-14 Analyst for Tourism Departm onitoring and Evaluation ant Selection ation ent PK-PTEG-279726-CS-INDV / 4. Project Management, M Individual Consult IDA / 59820 Post Limited 28,000.00 0.00 Signed 2022-02-22 2022-02-18 2022-02-27 2022-07-21 2022-03-13 2022-08-04 2022-03-27 2023-03-22 Environment Specialist onitoring and Evaluation ant Selection PK-PTEG-279729-CS-INDV / L 4. Project Management, M Individual Consult Under Implement IDA / 59820 Post Limited 20,000.00 0.00 2022-02-21 2022-02-18 2022-02-24 2022-03-03 2022-03-17 2023-03-12 iaison Officer onitoring and Evaluation ant Selection ation PK-PTEG-279736-CS-INDV / 4. Project Management, M Individual Consult Under Implement IDA / 59820 Post Open 21,000.00 0.00 2022-02-21 2022-02-18 2022-03-19 2022-04-02 2022-04-16 2023-04-11 Coordination Officer onitoring and Evaluation ant Selection ation PK-PTEG-286751-CS-INDV / 1. Policy, Institutions and Individual Consult Under Implement Economist - Assessment of e IDA / 59820 Governance for Tourism Dev Post Open 16,000.00 0.00 2022-04-25 2022-04-21 2022-05-21 2022-05-28 2022-06-11 2022-09-09 ant Selection ation conomic impact of the PTEGP elopment Page 7 PK-PTEG-293040-CS-INDV / 3. Public Investment Facilit Individual Consult Pending Impleme IDA / 59820 Post Open 26,000.00 0.00 2022-05-09 2022-06-04 2022-06-11 2022-06-25 2023-06-20 Conservation Specialist y ant Selection ntation PK-PTEG-302813-CS-INDV / P 4. Project Management, M Individual Consult Under Implement rocurement and Contract Ad IDA / 59820 Post Open 12,000.00 0.00 2022-07-18 2023-03-20 2022-08-20 2022-08-27 2022-09-10 2023-04-29 onitoring and Evaluation ant Selection ation ministration Officer PK-PTEG-305507-CS-INDV / P 4. Project Management, M Individual Consult IDA / 59820 Prior Open - National 20,000.00 0.00 Signed 2022-07-25 2022-07-26 2022-08-27 2022-10-21 2022-09-10 2023-05-25 2022-10-01 2023-06-01 2023-04-29 rocurement Specialist onitoring and Evaluation ant Selection PK-PTEG-321724-CS-INDV / 4. Project Management, M Individual Consult Under Implement Hiring of Financial Managem IDA / 59820 Post Open - National 15,000.00 0.00 2022-10-17 2022-10-31 2022-11-07 2023-01-05 2022-11-09 2022-11-12 2023-05-11 onitoring and Evaluation ant Selection ation ent Specialist PK-PTEG-332494-CS-INDV / 4. Project Management, M Individual Consult Under Implement IDA / 59820 Post Open - National 12,000.00 0.00 2022-12-19 2022-12-12 2023-01-10 2023-01-15 2023-01-26 2023-04-30 Hiring of Electrical Engineer onitoring and Evaluation ant Selection ation PK-PTEG-347113-CS-INDV / 4. Project Management, M Individual Consult Under Implement Hiring of Digital Media & Com IDA / 59820 Post Open - National 25,000.00 0.00 2023-03-07 2023-03-20 2023-04-11 2023-04-16 2023-04-22 2024-04-21 onitoring and Evaluation ant Selection ation munication Expert PK-PTEG-347155-CS-INDV / 1. Policy, Institutions and Individual Consult Hiring of Museum Educator a IDA / 59820 Governance for Tourism Dev Post Open - National 5,000.00 0.00 Canceled 2023-03-10 2023-03-20 2023-04-08 2023-04-13 2023-04-23 2023-10-20 ant Selection t Lahore Museum elopment PK-PTEG-347167-CS-INDV / 4. Project Management, M Individual Consult Under Implement Hiring of Social Safeguard & IDA / 59820 Post Open - National 31,000.00 0.00 2023-03-10 2023-03-06 2023-04-13 2023-04-18 2023-04-28 2024-04-27 onitoring and Evaluation ant Selection ation Gender Specialist Page 8 CAMEROUN – MINISTERE DE L’ECONOMIE DE LA PLANIFICATION ET DE L’AMENAGEMENT DU TERRITOIRE (MINEPAT) PROJET DES INFRASTRUCTURES HYDRAULIQUES DANS LA VALLEE DE LA BENOUE – REGION DU NORD CAMEROUN / AVANCE DE PREPARATION DU PROJET (PN66072) PLAN DE PASSATION DES MARCHES (PPM) SIMPLIFIE – PPA (DATE DE MISE A JOUR FEVRIER 2018) I. GENERAL 1. Informations sur le Projet Emprunteur : République du Cameroun Ministère Responsable: Ministère de l’Economie, de la Planification et de l’Aménagement du territoire (MINEPAT) Nom du Projet : Projet des infrastructures hydrauliques dans la vallée de la Bénoué Identification : PN66072 CREDIT IDA N° : CR __________ Agence d’exécution du Projet : Unité de Coordination du PULCI, agence fiduciaire 2. Date d’approbation par la Banque du Plan de Passation des Marchés : (1) __________ 3. Date de publication de l’Avis Général de Passation des Marchés : _________________ 4. Période couverte par le Plan de Passation des Marchés : 24 Mois II. TRAVAUX, FOURNITURES ET SERVICES AUTRE QUE SERVICES DE CONSULTANTS 1. Dispositions relatives aux seuils de revue préalable : Risque Substantiel Seuils requis pour les décisions de marchés soumis à la revue préalable de la Banque, tel que prévu dans l’annexe 1 des "Directives de Passation des Marchés de fournitures, de travaux et de services (autres que les services de consultants) par les Emprunteurs de la Banque mondiale dans le cadre des prêts de la BIRD et des crédits de l’AID". Catégories de marchés Seuils de revue a Observations priori Montants estimatifs des contrats en millions de dollars américains Travaux, Contrats clé en main et Contrats de Fourniture et Montage >= 10 d’Installations Fournitures, Système d’information, et Services autres que les services de >= 2 Pour les contrats par consultants entente directe, la 1 Travaux, Contrats clé justification devra être en main et Contrats préalablement approuvée de Fourniture et >= 10 par la Banque. Cette Montage approbation pourrait se Contrats à d’Installations passer par faire lors de l’approbation Fournitures, Système entente directe d’information, et du PPM Services autres que >= 2 les services de consultants 2. Pré qualification : En cas de nécessité, les soumissionnaires seront pré qualifiées en accord avec les dispositions des paragraphes 2.9 et 2.10 3. Seuils pour les méthodes de passation des marchés : Les seuils de passation des marchés se présentent comme suit au vu des conditions du marché : FOURNITURES (US$ TRAVAUX (US$ équivalent) équivalent) AOI AON CF AOI AON CF ≥10.000.0 <10.000.0 <200.0 ≥1.000.0 <1.000.0 <100.0 00 00 00 00 00 00 4. Dispositions spéciales sur les marchés : Concernant les acquisitions de véhicules et de carburant, en fonction des circonstances et des besoins spécifiques du pays, le seuil pour la consultation de fournisseurs pourrait être porté à la contre-valeur de : USD 500,000 (en prenant soin de consulter tous les principaux concessionnaires de marque ou distributeurs de produits pétroliers). 5. Liste des marchés avec les méthodes de passation et les dates de mise en œuvre TRAVAUX : 1 2 3 4 5 6 7 8 9 Montant Préfé Méthod Pré Observati Estimatif - Revue Date e qualific on Date (USD) renc Banque prévue N° Description passati a-tion fin des e (Prior/ ouvertu on du (oui/no prestatio Natio Post) re offres marché n) ns -nale Réhabilitation, aménagement et Avril 1 extension des bureaux de 100 000 CF N/A N/A Post 2018 déc/2019 la MEADEN à Garoua et à Lagdo TOTAL EN USD 100 000 FOURNITURES DE BIENS & SERVICES AUTRES QUE LES SERVICES DE CONSULTANTS 1 2 3 4 5 6 7 8 9 Montant Préfé Méthod Pré Observati Estimatif - Revue Date e qualific on Date (USD) renc Banque prévue N° Description passati a-tion fin des e (Prior/ ouvertu on du (oui/no prestatio Natio Post) re offres marché n) ns -nale 2 Acquisition de mobilier et autre équipement de bureau pour l’Unité de Avril 1 40 000 CF N/A N/A Post Gestion du projet : 2018 meubles réfrigérateurs, splits, … Achat en 03 lots de Fourniture et matériel de bureau (lot1), de matériel Avril 2 60 000 CF N/A N/A Post et consommables 2018 informatiques (lot2) pour l’UCP Acquisition et paramétrage du logiciel Avril 3 comptable TOMPRO 2 y 25 000 CF N/A N/A Post 2018 compris formation du personnel Achat de quatre (04) Avril 4 200 000 CF N/A N/A Post véhicules pour l’UCP 2018 Fourniture du signal Avril 5 10 000 CF N/A N/A Post Internet à l’UCP 2018 Acquisition d’une flotte de téléphone mobile Avril 6 20 000 CF N/A N/A Post (appareils et crédit) pour 2018 le personnel de l’UCP Assurances véhicule et du Avril 7 25 000 CF N/A N/A Post matériel de l’UCP, 2018 Assurance annuel du Avril 8 personnel (maladie et 10 000 CF N/A N/A Post 2018 individuelle accident) TOTAL EN USD 390 000 N/A N/A III. Sélection des Consultants 1. Dispositions relatives aux seuils de revue préalable des marchés : Décisions de sélection sujet à la revue préalable de la Banquet comme indiqué dans l’annexe 1 du Guide de Sélection et d’Emploi des Consultants par les Emprunteurs de la Banque Mondiale dans le cadre des Prêts de la BIRD et des Crédits et Dons de l’AID Catégories de marchés Seuils de revue a Observations priori Montants estimatifs des contrats en millions de dollars américains Le contrat d’audit financier et comptable sera néanmoins Services de consultants – Firmes >= 1 soumis à la revue préalable de la banque Tous les contrats à passer par Pour tout contrat par entente entente directe avec les firmes >= 1 directe, la justification devra de consultants être au préalable approuvée Sélection de Consultants par la banque. Ceci pourra >= 0.3 être joint et approuvée avec individuel par entente directe le PPM. Les contrats du personnel. Le Sélection de Consultants contrat du personnel cadre >= 0.3 individuels par comparaison de de l’UGP devra néanmoins CVs être revu a priori de la banque 3 2. Liste restreinte composée entièrement de firmes nationales: La liste restreinte de consultants pour les prestations d’études d’ingénierie, de contrôle et de surveillance estimées à moins de 300,000 US$ par contrat, et pour tout autre type de prestations, estimées à moins de 100 000 US$ par contrat, peut comporter entièrement de consultants nationaux selon les dispositions du paragraphe 2.7 des Directives de Sélection et d’Emploi des Consultants, et l’Emprunteur ne procède pas à une publication dans UNDB. 3. Autre arrangement spécial de Sélection de consultants : Le seuil pour l’utilisation de la méthode de sélection de consultant fondée sur les qualifications des consultants est déterminé au cas par cas en tenant compte de la nature et de la complexité de la mission; cependant, ce seuil ne devrait pas dépasser la contre- valeur de USD 300,000 sauf dans des cas exceptionnels prévus au paragraphe 3.7 des directives pour la sélection et l’emploi des consultants par les emprunteurs de la Banque Mondiale dans le cadre des Prêts de la BIRD et des Crédits et Dons de l’AID. 4. Liste des Consultations, avec les méthodes de sélection et le calendrier de mise œuvre CONSULTANTS 1 2 3 4 5 6 8 Coûts Date Observa Méthod Ré Estimatifs Revue prévue tions/ e de f Description (USD) par la de Date fin sélecti Banque l'ouvertu prestati on re ons Réalisation de l’étude sur le Cadre de Gestion 1 Environnemental et social du 40 000 CI Post Avril 2018 Projet (CGES) Plan de Gestion des Nuisibles Avril 2 10 000 CI Post (PGN) 2018 Étude d’Impact Environnemental et Social (EIES) détaillée des périmètres Lagdo rive droite - réhabilitation (1 000 ha), rive droite extension (5 000 100 000 Avril 3 SQC Post ha) et rive gauche – 2018 extension (5 000 ha). Les coûts de l’étude incluent la validation des TDR, les consultations publiques et la validation du Rapport Réalisation de l’Etude Pendant la Avant d’Impacts Environnementales 300 000 mise en 4 SQC Post présentat et Sociales régionale (zone œuvre du ion au CA ABN) projet Etude de Plan Directeur d’Aménagement et de Gestion du bassin versant de 180 000 Avril 5 Lagdo SQC Post 2018 et Plan de Gestion des ZICs 7, 8, 8bis et 9 4 Étude hydraulique et hydrologique, sureté du barrage et des installations, système 900 000 Avril 6 d’informations hydrométriques SFQC Prior 2018 (Flood and dam operation studies) Études détaillées (APD) et dossier d’appel d’offre (DAO) pour l’irrigation et le 1 800 000 Avril 7 drainage de 11000 ha de SFQC Prior 2018 périmètres agricoles à Lagdo (Re-design of irrigation scheme studies) - Réalisation de l'étude sur le Cadre de politique de réinstallation (CPR) - Évaluation sociale - Plan d’Action de Recasement (PAR) du Périmètre Lagdo rive droite - réhabilitation (1 000 ha) 100 000 Avril 8 CI Post 2018 - Rapport de l’Évaluation du processus de finalisation de recasement des personnes affectées sur les Périmètres Lagdo rive droite - réhabilitation (1 000 ha), rive droite extension (5 000 ha) et rive gauche – extension (5 000 ha) Après les Plan de gestion des afflux 9 15 000 CI Post résultats sociaux (PGAS) des EIES Après les Plan d’engagement des 10 15 000 CI Post résultats parties prenantes (PEPP) des EIES Définition de de la situation de référence (baseline) des indicateurs du Cadre de 60 000 Avril 11 Résultats du Projet et CI Post 2018 élaboration de la section de suivi-évaluation du manuel de mise en œuvre. Elaboration du Manuel de 20 000 Avril 12 Procédures Administratives, CI Post 2018 Financières et Comptables Elaboration du Manuel 20 000 Avril 13 CI Post d’exécution du projet 2018 Audit institutionnel et 14 organisationnel de la 150 000 SQC Post Juin 2018 MEADEN 5 Recrutement d’un (e) Responsable /planificateur Avril 15 90 000 CI Post (trice) pour la phase de 2018 préparation projet Recrutement d’un (e) Expert (e) des questions Environnementales, Avril 16 40 000 CI Post d’Hygiène et de Sécurité 2018 (ESHS) à l’Unité de Coordination du Projet Recrutement d’un (e) Expert (e) des questions Sociales, à Avril 17 40 000 CI Post 2018 l’Unité de Coordination du Projet Recrutement d’un (e) Expert (e) en suivi-évaluation à Février 18 24 000 CI Post l’Unité de Coordination du 2019 Projet Recrutement d’un (e) Expert (e) en ingénierie de la Février 19 24 000 CI Post formation à l’Unité de 2019 Coordination du Projet Recrutement d’un (e) Responsable des affaires Février 20 administratives et financières 36 000 CI Post 2019 (RAF) à l’Unité de Coordination du Projet Recrutement d’un (e) Expert (e) en passation des marchés Avril 21 36 000 CI Post (SPM), l’Unité de 2018 Coordination du Projet Recrutement d’un (e) Avril 22 Comptable à l’Unité de 24 000 CI Post 2018 Coordination du Projet Recrutement d’un (e) assistants (es) de Direction à Avril 23 l’Unité de Coordination du 20 000 CI Post 2018 Projet, à la phase de préparation Recrutement de 02 chauffeurs, 01 agent de Avril 24 liaison, 02 agents d'entretien, 20 000 CI Post 2018 03 gardiens dont 01 de jour et 02 de nuit Assistance technique pour la Février 25 gestion des périmètres 50 000 SQC Post 2019 irrigués Assistance technique pour Février 26 50 000 SQC Post appui conseil 2019 TOTAL en USD 3 964 000 6 IV. Activité de renforcement des capacités de l’Agence d’exécution du Projet 1.Liste des activités de renforcement des capacités et Séminaires 1 2 3 4 5 6 Montant Estimatif Durée Date de Commentaires et (USD) Estimé N° Description démarra Résultats (Impacts) e ge attendus (Jour) Prise en charge du Mai 1 groupe de préparation 120 000 2018 du Projet (six réunions) Séminaire de formation en développement des 2 compétences à 10 000 05 Juil. 2018 destination de l'équipe nationale élargie. Résultats attendus: Séminaire de formation maîtrise du cycle des en gestion financière et projets et des procédures en passation des Mai de passation des marchés 3 10 000 05 marchés de projet 2018 et de gestion financières suivant les procédures des projets de la Banque mondiale. de la Banque mondiale (20taine de participants) Effectuer des voyages d'études dans les pays Voyage d'études pour ayant mis en place les appropriation des projets similaires avec la Banque mondiale, à l'effet bonnes pratiques de 4 30 000 15 Juil. 2018 de s'approprier des bonnes projets de pratiques y ayant cours développement en Résultats attendus: Afrique renforcement des connaissances des personnels TOTAL en USD 170 000 TOTAL GENERAL 4 524 000 II+II+IV/USD (*) : Contrat bien que soumis à la Revue à posteriori, seront soumis à l’Avis Technique de l’IDA Lexique des Sigles et Abréviations AOI : Appel d’Offres International SFQC : Sélection Fondée sur la Qualité et le Coût AON : Appel d’Offres National SQC : Sélection fondée sur les Qualifications des Consultants CFEN : Consultation des Fournisseurs SFQ : Sélection Fondée sur la Qualité Au Niveau National SMC : Sélection au Moindre Coût ED : Entente Directe (Gré à Gré) SCBD : Sélection dans le Cadre d’un Budget Déterminé 7 PROCUREMENT Cameroon : Valorization of Investments in the Valley of the Benue PLAN General Information Country: Cameroon 2022-02-14 Bank’s Approval Date of the Original Procurement Plan: 2023-06-07 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P166072 GPN Date: 2022-03-09 Project Name: Valorization of Investments in the Valley of the Benue Loan / Credit No: IDA / 67700 MISSION D'ETUDES POUR L'AMENAGEMENT ET LE DEVELOPPEMENT DE LA REGION DU NORD Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned CM-MEADEN-276963-CW-RF B / Réhabilitation de : (i) 100 0 ha et aménagement de 50 Request for Bids - 00 ha rive droite y compris tr Improvement of Infrastructu Open - Internationa Single Stage - One E Works French Civi 129,456,000. 2026-07-0 avaux de construction de la IDA / 67700 Prior Request for Bids 0.00 Canceled 2022-02-18 2022-02-25 2022-05-06 2022-05-26 2022-06-24 re and Water Management l nvelope l Law (French) SP 00 1 digue de la Bénoué (15km) e D t de : (ii) 5000 ha rive gauch e y com-pris travaux de cons truction de la digue de la Bén oué (15km), en deux lots CM-MEADEN-282133-CW-RF B / Réhabilitation de : (i) 100 0 ha et aménagement de 50 Request for Bids - 00 ha rive droite y compris tr Improvement of Infrastructu Open - Internationa Single Stage - One E Works French Civi 129,456,000. 2026-06-3 avaux de construction de la IDA / 67700 Prior Request for Bids 0.00 Canceled 2022-03-04 2022-03-14 2022-05-31 2022-06-21 2022-07-21 re and Water Management l nvelope l Law (French) SP 00 0 digue de la Bénoué (15km) e D t de : (ii) 5000 ha rive gauch e y compris travaux de const ruction de la digue de la Bén oué (15km), en deux lots CM-MEADEN-294155-CW-RF B / Réhabilitation de 1122 ha et aménagement de 3065 ha Request for Bids - rive droite y compris travaux Improvement of Infrastructu Open - Internationa Single Stage - One E Works (without pr 130,481,565. Under Revie 2026-06-3 de construction de 15,7 km d IDA / 67700 Prior Request for Bids 0.00 2022-05-23 2022-06-22 2022-05-31 2022-09-09 2022-08-26 2022-07-14 2022-09-15 2023-05-22 2022-11-09 re and Water Management l nvelope equalification) SP 00 w 0 igue le long de la Bénoué (Lo D t1) -Aménagement de 2944 h a rive gauche y compris trav aux de construction de 18,1 km digue le long de Bénoué (Lot2) CM-MEADEN-277003-CW-RF Request for Bids - B / Mise en place du réseau h Improvement of Infrastructu Open - Internationa Single Stage - One E Works French Civi 2023-03-2 ydrométéorologique, sécurité IDA / 67700 Post Request for Bids 5,000,000.00 0.00 Canceled 2022-05-31 2022-06-15 2022-07-27 2022-08-26 2022-09-30 re and Water Management l nvelope l Law (French) SP 9 du barrage de Lagdo et systè D me d’alerte précoce dans la vallée de la Bénoué Request for Bids - CM-MEADEN-299333-CW-RF Improvement of Infrastructu Single Stage - One E Small Works SPD Pending Imp 2023-12-2 B / Travaux de réhabilitation IDA / 67700 Post Request for Bids Open - National 68,259.00 0.00 2023-06-26 2023-07-03 2023-07-31 2023-08-04 2023-08-22 re and Water Management nvelope (1 envelope proce lementation 0 des locaux abritant la MEADE ss) N. CM-MEADEN-277008-CW-RF B / Travaux de Construction des bâtiments : i) de 02 cent Request for Bids - res locaux du CGER dont un ( Improvement of Infrastructu Single Stage - One E Small Works SPD 2023-11-1 IDA / 67700 Post Request for Bids Open - National 167,891.00 0.00 Canceled 2023-05-30 2023-06-13 2023-07-28 2023-08-04 2023-08-18 01) à Garoua et l'autre à Lag re and Water Management nvelope (1 envelope proce 6 do (lot1), et ii) du Centre d’I ss) nnovation Technologique Y c ompris un magasin pour la c onservation des semences à Lagdo (lot2) . CM-MEADEN-348423-CW-RF Request for Bids - B / Travaux de construction d Capacity Building and Imple Single Stage - One E Works (without pr Pending Imp 2024-02-2 IDA / 67700 Post Request for Bids Open - National 170,648.00 0.00 2023-05-31 2023-06-05 2023-07-20 2023-08-19 2023-09-23 es deux (02) bâtiments de C mentation nvelope equalification) SP lementation 0 GER à Lagdo et à Garoua D Request for Bids - CM-MEADEN-348424-CW-RF Capacity Building and Imple Single Stage - One E Works (without pr Pending Imp 2024-03-2 B / Travaux de construction d IDA / 67700 Post Request for Bids Open - National 153,584.00 0.00 2023-05-31 2023-06-05 2023-07-20 2023-08-19 2023-09-23 mentation nvelope equalification) SP lementation 1 u Centre d’Innovation Techno D logique (CIT) CM-MEADEN-366966-CW-RF Request for Bids - B / Travaux de construction d Capacity Building and Imple Single Stage - One E Small Works SPD Pending Imp 2024-06-0 es bureaux pour l'Unité de C IDA / 67700 Post Request for Bids Open - National 211,638.00 0.00 2023-08-14 2023-08-28 2023-10-12 2023-11-11 2023-12-09 mentation nvelope (1 envelope proce lementation 6 oordination du Projet (UCP), ss) y compris mini adduction d'e au potable GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CM-MEADEN-277229-GO-RF Capacity Building and Imple Single Stage - One E IDA / 67700 Post Request for Bids Open - National 300,000.00 293,924.54 Signed 2022-02-28 2022-03-02 2022-03-08 2022-03-02 2022-04-07 2022-04-04 2022-04-14 2022-04-06 2022-05-11 2022-06-04 2022-06-10 B / 05 véhicules automobiles mentation nvelope CM-MEADEN-277241-GO-RF Q / Achat de 02 groupes élec Capacity Building and Imple Request for Quota Single Stage - One E IDA / 67700 Post Limited 80,000.00 0.00 Canceled 2022-03-28 2022-04-26 2022-05-25 2022-06-24 trogènes de 15 KVA avec inv mentation tions nvelope erseur automatique, y compr is les abris CM-MEADEN-277236-GO-RF Q / Achat de Fournitures de b Capacity Building and Imple Request for Quota Single Stage - One E IDA / 67700 Post Limited 25,597.00 0.00 Signed 2022-08-24 2022-09-09 2022-10-10 2022-11-09 ureau et de Consommables i mentation tions nvelope nformatiques pour l'UCP rep artis en deux (02) lots. CM-MEADEN-300421-GO-RF Q / Achat de 02 groupes élec Capacity Building and Imple Request for Quota Single Stage - One E Under Imple IDA / 67700 Post Limited 89,543.00 0.00 2022-07-26 2022-08-12 2022-09-13 2022-10-13 trogènes de 15 KVA avec inv mentation tions nvelope mentation erseur automatique, y compr is les abris CM-MEADEN-277233-GO-RF Q / Matériel informatique co mplet pour l’UCP (ordinateur s, imprimantes, copieurs, sca Capacity Building and Imple Request for Quota Single Stage - One E Under Imple IDA / 67700 Post Limited 111,928.00 0.00 2022-07-29 2022-10-05 2022-09-16 2022-10-19 nners, onduleurs, parasurten mentation tions nvelope mentation seurs, logiciels) (Lot1) et Equ ipements informatiques dans le cadre de l’appui institution nel à la MEADEN (Lot2) Page 1 CM-MEADEN-294030-GO-RF Capacity Building and Imple Request for Quota Single Stage - One E IDA / 67700 Post Limited 12,799.00 0.00 Canceled 2022-06-14 2022-08-18 2022-09-07 Q / Acquisition des pneus po mentation tions nvelope ur véhicules CM-MEADEN-277224-GO-RF Improvement of Infrastructu Request for Quota Single Stage - One E Q / Mise en place d’un Systè IDA / 67700 Post Limited 100,000.00 0.00 Canceled 2022-10-31 2022-12-21 2023-01-10 re and Water Management tions nvelope me d’Informations Géograph iques (SIG) CM-MEADEN-303566-GO-RF Q / Fourniture et installation Improvement of Infrastructu Request for Quota Single Stage - One E Pending Impl du matériel de télécommunic IDA / 67700 Post Limited 60,000.00 0.00 2023-05-06 2023-07-22 2024-01-18 re and Water Management tions nvelope ementation ations, mise en service" et d e formation du personnel à l' utilisation CM-MEADEN-277239-GO-RF Q / Acquisition du matériel p our communications : (01 drô ne, 01 Kit Visioconférence, 0 Capacity Building and Imple Request for Quota Single Stage - One E Pending Impl IDA / 67700 Post Limited 61,433.00 0.00 2023-04-21 2023-05-24 2023-06-24 1 Camera Professionnel, 30 T mentation tions nvelope ementation éléphones Portables, 01 App areil Photographique, 04 Még aphones et 01 Magnétophon e) pour le Projet VIVA-BENOU E CM-MEADEN-277231-GO-RF Capacity Building and Imple Request for Quota Single Stage - One E Under Imple Q / Mobilier et autres équipe IDA / 67700 Post Limited 93,857.00 0.00 2023-06-09 2023-07-06 2023-08-10 mentation tions nvelope mentation ments du bureau pour l’UCP CM-MEADEN-277227-GO-RF Q / Achat des Équipements d es ateliers/laboratoires pour l Capacity Building and Imple Request for Quota Single Stage - One E Pending Impl e renforcement des institutio IDA / 67700 Post Limited 80,000.00 0.00 2023-07-31 2023-10-09 2024-01-07 mentation tions nvelope ementation ns en trois lots: Lot 1: Lycée Agricole de Lagdo, Lot 2: ETA Garoua et Lot 3: l'Université de Maroua CM-MEADEN-348280-GO-RF Q / Acquisition de deux (02) Improvement of Infrastructu Request for Quota Single Stage - One E Pending Impl IDA / 67700 Post Open - National 119,454.00 0.00 2023-08-30 2023-11-01 2023-12-31 pick-up 4 x 4 pour le déplace re and Water Management tions nvelope ementation ment de l'Assistance Techniq ue AUE CM-MEADEN-348286-GO-RF Support Services for Agricult Request for Quota Single Stage - One E Pending Impl Q / Acquisition des mobiliers IDA / 67700 Post Open - National 17,065.00 0.00 2023-08-30 2023-10-18 2023-11-17 ural Production tions nvelope ementation de bureau pour les CGER CM-MEADEN-348293-GO-RF Q / Acquisition du matériel in formatique et de bureau pou Support Services for Agricult Request for Quota Single Stage - One E Pending Impl r les CGER (4 ordinateurs des IDA / 67700 Post Open - National 25,597.00 0.00 2023-08-29 2023-10-17 2023-11-16 ural Production tions nvelope ementation ktop, 4 ordinateurs portables , 4 imprimantes, 2 copieurs, 2 vidéoprojecteurs, matériels de reprographie) CM-MEADEN-348303-GO-RF Q / Acquisition de quatre (04) Support Services for Agricult Request for Quota Single Stage - One E Pending Impl motocyclettes (Lot 1) tout ter IDA / 67700 Post Open - National 68,259.00 0.00 2023-08-02 2023-10-11 2023-12-10 ural Production tions nvelope ementation rain pour les CGER et de six ( 06) pour le MINADER (Lot 2) CM-MEADEN-348316-GO-RF Q / Acquisition des équipeme nts et matériels de productio Capacity Building and Imple Request for Quota Single Stage - One E Pending Impl IDA / 67700 Post Open - National 85,324.00 0.00 2023-09-04 2023-10-30 2024-04-27 n pour le CIT (02 Motoculteur mentation tions nvelope ementation s, 02 sarcleurs manuels, 02 b atteuses, 02 mini-rizerie et é quipement de vitrine) CM-MEADEN-348326-GO-RF Q / Achats de fournitures de Capacity Building and Imple Request for Quota Single Stage - One E Under Imple IDA / 67700 Post Open - National 42,662.00 0.00 2023-06-20 2023-08-15 2023-09-14 bureau et des Consommable mentation tions nvelope mentation s informatiques complément aires de l'UGP CM-MEADEN-348340-GO-RF Q / Achat de quatre (04) impr imantes portatifs, un (01) Ser Capacity Building and Imple Request for Quota Single Stage - One E Pending Impl veur, quatre (04) scanners p IDA / 67700 Post Open - National 59,898.00 0.00 2023-06-04 2023-07-30 2023-09-28 mentation tions nvelope ementation ortatifs et quatre (04) vidéo projecteurs portatifs et 03 or dinateurs complet pour struc ture VBG en convention avec le Projet CM-MEADEN-348370-GO-RF Q / Acquisition du matériel p our communications : (01 drô ne, 01 Kit Visioconférence, 0 Capacity Building and Imple Request for Quota Single Stage - One E Under Imple IDA / 67700 Post Open - National 61,433.00 0.00 2023-04-19 2023-06-14 2023-12-11 1 Camera Professionnel, 30 T mentation tions nvelope mentation éléphones Portables, 01 App areil Photographique, 04 Még aphones et 01 Magnétophon e) pour le Projet VIVA-BENOU E CM-MEADEN-348375-GO-RF Q / Matériel de formation et d Capacity Building and Imple Request for Quota Single Stage - One E Pending Impl IDA / 67700 Post Open - National 17,065.00 0.00 2023-04-25 2023-06-20 2023-12-17 e sensibilisation (Tableau ZO mentation tions nvelope ementation PP, Ecran projection, flirt cha rt, nattes, Trépieds) CM-MEADEN-352913-GO-RF Q / Production d'outils et sup ports de communication (Affi ches, Affichettes, Flyers, Dép Capacity Building and Imple Request for Quota Single Stage - One E Pending Impl liants, Plaquettes, Roll-Up, Br IDA / 67700 Post Open - National 82,935.00 0.00 2023-05-15 2023-07-24 2024-01-20 mentation tions nvelope ementation ochures, Autocollants) – Lot 1 et Production d'outils et supp orts de promotion (Tee-Shirt, Casquettes, Banderoles, Clé USB, Polos, Pagnes, G NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CM-MEADEN-277243-NC-RF Q / Recrutement d’un prestat Capacity Building and Imple Request for Quota Single Stage - One E aire pour la souscription à de IDA / 67700 Post Limited 70,000.00 0.00 Signed 2022-03-23 2022-04-26 2022-05-25 2023-05-31 mentation tions nvelope s polices d’assurance automo biles, bâtiments et maladie Page 2 CM-MEADEN-294029-NC-DIR Capacity Building and Imple Pending Impl IDA / 67700 Post Direct Selection Direct - National 42,662.00 0.00 2022-05-31 2022-06-15 2022-08-12 2022-09-16 / Extension de la fibre optiqu mentation ementation e CM-MEADEN-277242-NC-RF Capacity Building and Imple Request for Quota Single Stage - One E Pending Impl Q / Services d’une entreprise IDA / 67700 Post Limited 16,773.00 0.00 2022-05-10 2022-07-11 2022-08-11 mentation tions nvelope ementation pour la fourniture d’un signal internet CM-MEADEN-348391-NC-RF Capacity Building and Imple Request for Quota Single Stage - One E Pending Impl Q / Souscription d'une Police IDA / 67700 Post Open - National 33,788.00 0.00 2023-06-05 2023-07-31 2023-08-30 mentation tions nvelope ementation d'Assurances automobile tou t risque vie CM-MEADEN-348396-NC-RF Q / Souscription d'une Police Capacity Building and Imple Request for Quota Single Stage - One E Pending Impl IDA / 67700 Post Open - National 51,195.00 0.00 2023-06-05 2023-07-31 2023-08-30 d'Assurances Maladie pour le mentation tions nvelope ementation personnel du Projet et de leu rs ayants droits CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CM-MEADEN-277238-GO-RF Q / Contrat d’Assistance tech Capacity Building and Imple Consultant Qualifi nique pour le paramétrage et IDA / 67700 Post Limited 5,000.00 9,010.94 Signed 2022-02-22 2022-02-27 2022-03-15 2022-04-09 2022-03-22 2022-05-09 2022-04-07 2022-05-11 2023-04-07 mentation cation Selection la formation à l’utilisation de s logiciels TOMATE (TOMPRO) CM-MEADEN-277519-CS-QC BS / Services consultant pour contrôle et surveillance trava ux, Réhabilitation de 1122 h Improvement of Infrastructu Quality And Cost- Open - Internationa Under Implement a, aménagement de 3494 ha IDA / 67700 Prior 6,823,000.00 0.00 2022-02-21 2022-03-09 2022-02-28 2022-03-14 2022-04-13 2022-09-15 2022-05-11 2022-11-30 2022-05-31 2023-02-08 2022-06-22 2023-05-22 2022-07-11 2026-12-09 re and Water Management Based Selection l ation rive droite, construction 15,7 km de digue (Lot 1) et Amén agement de 4953 ha rive ga uche et construction 18,1 k m de digue le long Bénoué (l ot2) CM-MEADEN-277554-CS-QC BS / Assistance technique po Improvement of Infrastructu Quality And Cost- Open - Internationa Under Implement IDA / 67700 Prior 4,000,000.00 0.00 2022-03-23 2022-05-12 2022-04-04 2022-06-03 2022-05-18 2023-04-11 2022-06-17 2022-07-04 2022-07-27 2022-08-17 2027-06-30 ur la mise en place des sous- re and Water Management Based Selection l ation composantes 1.3, 2.1 et 3.2 CM-MEADEN-277556-CS-QC BS / Assistance Technique po ur la mise en place des sous- Support Services for Agricult Quality And Cost- Open - Internationa IDA / 67700 Prior 2,000,000.00 0.00 Under Review 2022-03-16 2022-05-12 2022-03-28 2022-06-03 2022-05-16 2023-04-11 2022-06-15 2023-06-06 2022-07-04 2022-07-28 2022-08-25 2027-06-30 composantes 2.2 et 2.3.(prép ural Production Based Selection l aration, formation et suivi de s dossiers de cofinancement et structuration du CGER). CM-MEADEN-277541-CS-QC BS / Service d'une firme de c onsultants pour la réalisation Improvement of Infrastructu Quality And Cost- Open - Internationa Under Implement de l’Etude hydraulique et hyd IDA / 67700 Post 500,000.00 0.00 2022-09-13 2022-12-20 2022-09-23 2023-03-23 2022-11-08 2023-05-31 2022-12-08 2022-12-22 2023-01-13 2023-02-06 2024-02-05 re and Water Management Based Selection l ation rologique de la vallée de la B énoué (y compris élaboration APS/APD/DAO sécurité de bar rage) CM-MEADEN-327361-CS-LCS / Services d’un Consultant po Improvement of Infrastructu Least Cost Selecti Under Implement IDA / 67700 Post Open - National 40,000.00 0.00 2023-02-13 2023-03-06 2023-02-23 2023-03-09 2023-03-07 2023-03-31 2023-03-14 2023-04-27 2023-03-21 2023-04-28 2023-04-04 2023-05-24 2023-04-14 2023-05-29 ur la réalisation de l’audit co re and Water Management on ation mptable et financier externe CM-MEADEN-277551-CS-QC BS / Service d'une firme de c onsultants pour le contrôle e t la surveillance de la mise e Improvement of Infrastructu Quality And Cost- Open - Internationa IDA / 67700 Post 750,000.00 0.00 Canceled 2023-04-25 2023-05-25 2023-06-08 2023-06-22 2023-07-06 2023-08-11 2023-08-25 2024-02-21 n place du réseau hydromété re and Water Management Based Selection l orologique, sécurité du barra ge de Lagdo et système d’ale rte précoce de la vallée de la Bénoué CM-MEADEN-348240-CS-CQ S / Service d'un Consultant Fi rme Organisme Spécialisé (O Capacity Building and Imple Consultant Qualifi IDA / 67700 Post Open - National 42,662.00 0.00 Under Review 2023-05-26 2023-06-02 2023-06-16 2023-07-30 2023-08-29 2023-10-03 2024-03-31 NG) dans la sensibilisation en mentation cation Selection vironnementale, l'accompag nement des jeunes, la lutte c ontre les IST/VIH-SIDA CM-MEADEN-348261-CS-CQ S / Service de Consultant pou r la mise en place d'un Systè Capacity Building and Imple Consultant Qualifi Under Implement IDA / 67700 Post Open - National 91,297.00 0.00 2023-05-26 2023-04-13 2023-06-16 2023-06-25 2023-07-30 2023-08-29 2023-10-03 2023-12-02 me Intégré de Gestion de Sui mentation cation Selection ation vi-Evaluation, Planification, R apportage et Archivage du Pr ojet CM-MEADEN-348266-CS-CQ S / Service d'un Consultant d' une ONG Spécialisée dans le Capacity Building and Imple Consultant Qualifi s Violences Basées sur le Ge IDA / 67700 Post Open - National 32,743.00 0.00 Under Review 2023-04-14 2023-06-02 2023-05-05 2023-06-18 2023-07-18 2023-08-22 2024-02-18 mentation cation Selection nre (VBG) pour la sensibilisat ion des acteurs, l'assistance psycho-sociale et juridique a ux survivants INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CM-MEADEN-277565-CS-IND Improvement of Infrastructu Individual Consult V / Service d’un Consultant In IDA / 67700 Post Open 100,000.00 0.00 Signed 2022-03-21 2022-05-05 2022-05-09 2022-10-07 2022-05-30 2022-11-11 2022-07-04 2022-12-31 re and Water Management ant Selection dividuel Expert Barragiste CM-MEADEN-277570-CS-IND Improvement of Infrastructu Individual Consult V / Service d’un consultant i IDA / 67700 Post Open 100,000.00 0.00 Signed 2022-03-21 2022-05-05 2022-05-12 2022-10-10 2022-05-30 2022-11-10 2022-06-13 2022-09-12 re and Water Management ant Selection ndividuel Expert Hydrologue CM-MEADEN-277573-CS-IND Improvement of Infrastructu Individual Consult V / Service d’un Consultant In IDA / 67700 Post Open 100,000.00 0.00 Signed 2022-03-21 2022-05-05 2022-05-09 2022-09-08 2022-05-30 2022-11-11 2022-07-04 2022-12-30 re and Water Management ant Selection dividuel Expert Electromécan icien Page 3 CM-MEADEN-294027-CS-IND V / Services d’un Consultant i ndividuel pour préparer les d Improvement of Infrastructu Individual Consult Under Implement esigns (plans), APS et APD de IDA / 67700 Post Limited 16,955.00 0.00 2022-05-17 2022-08-05 2022-06-07 2022-10-12 2022-06-21 2022-12-15 2022-07-13 2022-08-12 re and Water Management ant Selection ation s travaux des infrastructures à construire ou à réhabiliter au cours de l’exécution du PT BA 2022, répartie en deux lot s. CM-MEADEN-294031-CS-IND V / Service d'un Consultant In dividuel pour l'élaboration du Plan d’Engagement des Parti Support Services for Agricult Individual Consult IDA / 67700 Post Limited 36,689.00 0.00 Canceled 2022-06-02 2022-05-25 2022-06-17 2022-07-14 2022-08-11 2022-09-15 es Prenantes (PEPP) et d'un ural Production ant Selection Consultant Individuel pour l'é laboration du Plan de Gestion des Afflux Sociaux (PGAS) re parti en deux lots. CM-MEADEN-299314-CS-IND V / Service d'un Consultant In Capacity Building and Imple Individual Consult IDA / 67700 Post Limited 17,918.00 0.00 Signed 2022-07-20 2022-07-30 2022-07-27 2022-10-27 2022-08-17 2022-12-21 2022-09-14 2022-10-31 dividuel pour l'élaboration du mentation ant Selection Plan d'Engagement des Parti es Prenantes (PEPP) CM-MEADEN-299322-CS-IND V / Service d'un Consultant In Capacity Building and Imple Individual Consult IDA / 67700 Post Limited 18,771.00 0.00 Signed 2022-07-25 2022-07-30 2022-08-01 2022-10-28 2022-08-22 2022-12-21 2022-09-19 2022-11-03 dividuel pour l'élaboration du mentation ant Selection Plan de Gestion des Afflux So ciaux (PGAS) . CM-MEADEN-277558-CS-IND V / Service de consultants po Capacity Building and Imple Individual Consult ur la réalisation des notices e IDA / 67700 Post Open 17,065.00 0.00 Signed 2022-07-14 2022-08-04 2022-08-26 2022-11-10 2022-09-02 2022-12-12 2022-09-16 2022-10-17 mentation ant Selection nvironnementales et sociales liées aux travaux de construc tions des bâtiments CM-MEADEN-304456-CS-IND V / Services d'un Consultant I ndividuel pour la surveillance Improvement of Infrastructu Individual Consult Under Implement et du contrôle des travaux de IDA / 67700 Post Limited 11,945.00 0.00 2023-03-20 2023-04-12 2023-04-10 2023-05-25 2023-06-22 2023-12-19 re and Water Management ant Selection ation construction des bâtiments p our abriter les 02 centres loc aux du CGER (Garoua et Lag do) CM-MEADEN-304461-CS-IND V / Service d’un consultant in Improvement of Infrastructu Individual Consult Pending Impleme dividuel pour la surveillance IDA / 67700 Post Limited 3,412.00 0.00 2023-04-20 2023-04-28 2023-05-19 2023-06-16 2023-12-13 re and Water Management ant Selection ntation et le contrôle des travaux de réhabilitation des bâtiments de la MEADEN CM-MEADEN-277536-CS-IND V / Service d’un consultant in dividuel pour la surveillance Improvement of Infrastructu Individual Consult Under Implement IDA / 67700 Post Limited 8,532.00 0.00 2023-04-10 2023-04-12 2023-04-17 2023-05-08 2023-06-05 2023-12-02 et le contrôle des travaux de re and Water Management ant Selection ation Construction des bureaux et de base vie de l' Unité de Co ordination Projet VIVA BENO UE. CM-MEADEN-304460-CS-IND V / Service d’un consultant in dividuel pour la surveillance Improvement of Infrastructu Individual Consult Under Implement IDA / 67700 Post Limited 4,266.00 0.00 2023-06-20 2023-04-12 2023-06-28 2023-07-19 2023-08-16 2024-02-12 et le contrôle des travaux de re and Water Management ant Selection ation Construction des bâtiments d u CIT et magasin semences à Lagdo. CM-MEADEN-294028-CS-IND V / Service d'un consultant d' Capacity Building and Imple Individual Consult un Spécialiste pour la mise e IDA / 67700 Post Limited 10,239.00 0.00 Canceled 2023-06-27 2023-07-12 2023-08-01 2023-08-18 2023-09-17 mentation ant Selection n conformité de la sécurité in cendie au sein de la MEADEN à Garoua CM-MEADEN-347450-CS-IND V / Services d'un Consultant Capacity Building and Imple Individual Consult IDA / 67700 Post Open - National 42,662.00 0.00 Under Review 2023-05-25 2023-03-23 2023-07-13 2023-08-03 2023-09-07 2024-03-05 pour l'étude sur la petite irrig mentation ant Selection ation hors périmètre CM-MEADEN-348245-CS-IND V / Services d’un consultant Capacity Building and Imple Individual Consult Pending Impleme pour la Réalisation des notice IDA / 67700 Post Open - National 13,652.00 0.00 2023-04-28 2023-06-16 2023-07-07 2023-08-11 2023-09-10 mentation ant Selection ntation s d'impact environnementale s sur les gites d'emprunt des matériaux CM-MEADEN-348250-CS-CD S / Services d'un Cabinet pou Capacity Building and Imple r l'Ajustement du Plan d'Actio IDA / 67700 Post Direct Selection Direct - National 51,195.00 0.00 Canceled 2023-04-21 2023-05-01 2023-07-05 2024-01-01 mentation n de Recasement (PAR) de 1 0 000 ha à aménager (rive dr oite et rive gauche) CM-MEADEN-348264-CS-IND V / Service de Consultant Indi viduel pour la réalisation des Capacity Building and Imple Individual Consult IDA / 67700 Post Limited 6,485.00 0.00 Canceled 2023-04-28 2023-03-23 2023-05-03 2023-05-24 2023-06-28 2023-07-01 Tableaux de Bords pour le su mentation ant Selection ivi physico-financier et temp orel des indicateurs du cadre des résultats Page 4 PROCUREMENT PLAN (Textual Part) Turkey Emergency COVID-19 Health Project Project information: (P173988) Project Implementation Ministry of Health (MoH) Agency: Date of the Procurement 17 April 2020 Plan: Period covered by this 17 April 2020- 31 December 2022 Procurement Plan: Date of General TBD Procurement Notice: I. Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016 and revised August 2018) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. Any procurement activity under the Project shall not be initiated before it is approved by the Bank through STEP. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. II. Goods, Works and Non-Consulting Services Procurement Method Procurement Method Threshold RFB/Open Default Method (No procurement method threshold) International Goods and Non-consulting Services RFB/Open National No procurement threshold (shall require Bank’s approval through STEP) Goods, Non-Consulting Services RFQ No procurement threshold (shall require Bank’s approval through STEP) No threshold (shall require Bank’s approval through Direct Selection STEP) Framework No threshold Agreement III. Selection of Consultants Selection Method Selection Method Threshold Quality and Cost Based No selection method threshold Selection (QCBS) 1/2 Least Cost Selection No selection method threshold (LCS) Quality Based Selection No selection method threshold (QBS) Selection Based on No selection method threshold (shall require Bank’s Consultants approval through STEP) Qualification (CQS) Individual Consultants No selection method threshold (IC) No selection method threshold (shall require Bank’s Direct Selection approval through STEP) The terms of references of any audit, procurement or legal consultants financed by the project shall be sent to the Bank for its comments. IV. Special Arrangements 1. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. For the procurements not subject to international competitive selection the procurement documents agreed by the Bank shall be used. 2. Review Procedure: All the procurements under the project are subject to the Bank’s ex-post review unless otherwise specified in the procurement schedule given below in Section V. 3. Procurement of Second-Hand Goods: may be considered under the Project, where justified and needed to respond to emergency. 4. Domestic preference (as specified under paragraph 5.51 of the Procurement Regulations): Not applicable. 5. Operational costs. will not be considered under procurement implementation which could be the incremental expenses, including office supplies, office rental, publication of procurement notices, vehicle operation, office and equipment maintenance and repair, communication, translation and interpretation, travel and supervision costs, subscription to publications and databases, publication fees, and ownership of intellectual property rights, but excluding salaries of officials and employees of the MoH. V. Procurement Packages with Methods and Time Schedule The estimated costs in the attached tables (sheets) (including VAT). Due to emergency nature of the project the procurement plan will be completed during the implementation. 2/2 PROCUREMENT Turkiye : Turkey Emergency COVID-19 Health Project PLAN General Information Country: Turkiye 2020-05-30 Bank’s Approval Date of the Original Procurement Plan: 2023-06-05 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P173988 GPN Date: 2020-04-30 Project Name: Turkey Emergency COVID-19 Health Project Loan / Credit No: IBRD / 91030, COFN / C2110 Ministry of Health Executing Agency(ies): WORKS Activity Reference No. / Procureme Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH Ri Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method nt Docume ount (US$ and Recommendation Signed Contract o. h cess (Y/N) sk atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion nt Type ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SADP-COVID19/KHGM/2021/ Component 1: Emergency C G/ÇA/RFQ/1 / Medical Equipm IBRD / 91030 Post Direct Selection Direct 0.00 Canceled 2021-03-15 2021-03-20 2021-04-24 2021-09-21 OVID-19 Response ent and supplies (Monitors) SADP-COVID19/HSGM/2020/ Component 1: Emergency C G/ÇA/RFQ/1 / Medical equipm IBRD / 91030 Post Direct Selection Direct 0.00 Canceled 2020-07-06 2020-07-11 2020-08-15 2021-01-04 OVID-19 Response ent and supplies SADP-COVID19/HSGM/2021/ Component 1: Emergency C G/ÇA/RFQ/1 / Medical equipm IBRD / 91030 Post Direct Selection Direct 0.00 Canceled 2021-03-30 2021-04-04 2021-05-09 2021-09-14 OVID-19 Response ent and supplies SADP-COVID19/KHGM/2020/ Component 1: Emergency C G/ÇA/RFQ/2 / Medical Equipm IBRD / 91030 Post Direct Selection Direct 0.00 Canceled 2020-07-15 2020-07-20 2020-08-24 2020-12-30 OVID-19 Response ent and Supplies (Monitors) SADP-COVID19/KHGM/2020/ Component 1: Emergency C G/ÇA/RFQ/3 / Medical Equipm IBRD / 91030 Post Direct Selection Direct 0.00 Canceled 2020-08-15 2020-08-20 2020-09-24 2020-12-31 OVID-19 Response ent and Supplies (Monitors) SADP-COVID19/KHGM/2020/ Component 1: Emergency C G/ÇA/RFQ/4 / Medical Equipm IBRD / 91030 Post Direct Selection Direct 0.00 Canceled 2020-06-25 2020-07-01 2020-08-05 2020-12-30 OVID-19 Response ent and Supplies (Computed Tomography) SADP-COVID19/KHGM/2020/ G/ÇA/RFQ/5 / Medical Equipm Component 1: Emergency C IBRD / 91030 Post Direct Selection Direct 0.00 Canceled 2020-07-01 2020-07-06 2020-08-10 2020-12-30 ent and Supplies (Mobile x-ra OVID-19 Response y and digital x-ray equipment ) SADP-COVID19/KHGM/2020/ Component 1: Emergency C G/ÇA/RFQ/1 / Medical Equipm IBRD / 91030 Post Direct Selection Direct 10,395,000.00 Completed 2020-06-15 2020-06-22 2020-06-20 2020-07-06 2020-07-25 2020-09-02 2020-12-30 2021-01-01 OVID-19 Response ent and Supplies (Ventilators ) SADP-COVID19/KHGM/2021/ Component 1: Emergency C G/ÇA/RFQ/2 / Medical Equipm IBRD / 91030 Post Direct Selection Direct 0.00 Canceled 2021-04-15 2021-04-20 2021-05-25 2021-10-22 OVID-19 Response ent and Supplies (Computed Tomography) SADP-COVID19/KHGM/2021/ G/ÇA/RFQ/3 / Medical Equipm Component 1: Emergency C IBRD / 91030 Post Direct Selection Direct 0.00 Canceled 2021-05-15 2021-05-20 2021-06-24 2021-11-21 ent and Supplies (Mobile and OVID-19 Response Digital X-Ray Equipment) SADP-COVID19/HSGM/2020/ Component 1: Emergency C Request for Quota Single Stage - One E G/RFQ/2 / Procurement of Me IBRD / 91030 Post Open - National 0.00 Canceled 2020-10-31 2020-11-27 2020-12-27 OVID-19 Response tions nvelope dical Consumables SADP-COVID19/HSGM/2020/ Component 1: Emergency C Request for Quota Single Stage - One E IBRD / 91030 Post Open - National 0.00 Canceled 2020-10-31 2020-11-27 2020-12-27 G/RFQ/3 / Procurement of Me OVID-19 Response tions nvelope dical Kits SADP-COVID19/HSGM/2020/ Component 1: Emergency C Request for Quota Single Stage - One E G/RFQ/1 / Procurement of Me IBRD / 91030 Post Open - National 0.00 Canceled 2020-11-08 2020-12-01 2020-12-31 OVID-19 Response tions nvelope dical Devices SADP-COVID19/HSGM/2020/ Component 1: Emergency C Request for Quota Single Stage - One E G/RFQ/4 / Procurement of Per IBRD / 91030 Post Open - National 0.00 Canceled 2020-11-13 2020-11-30 2020-12-30 OVID-19 Response tions nvelope sonal Protective Equipment SADP-COVID19/HSGM/2020/ Component 1: Emergency C IBRD / 91030 Post Direct Selection Direct 5,775,000.00 Completed 2020-11-12 2020-11-12 2020-11-17 2020-11-19 2020-12-22 2020-12-04 2021-05-29 2020-12-04 G/ÇA/RFQ/2 / Procurement of OVID-19 Response Ventilators SADP-COVID19/HSGM/2020/ Component 1: Emergency C G/ÇA/RFQ/4 / Procurement of IBRD / 91030 Post Direct Selection Direct 1,026,083.13 Signed 2020-12-02 2020-05-05 2020-12-07 2020-12-03 2020-12-09 2020-12-15 2020-12-24 OVID-19 Response Medical Devices SADP-COVID19/HSGM/2020/ Component 1: Emergency C G/ÇA/RFQ/6 / Procurement of IBRD / 91030 Post Direct Selection Direct 391,973.89 Signed 2020-12-02 2020-05-05 2020-12-07 2020-12-04 2020-12-09 2020-12-23 2020-12-24 OVID-19 Response Medical Consumables SADP-COVID19/HSGM/2020/ Component 1: Emergency C IBRD / 91030 Post Direct Selection Direct 26,629,000.00 Completed 2020-12-02 2020-05-05 2020-12-07 2020-12-04 2020-12-09 2020-12-15 2020-12-24 2020-12-15 G/ÇA/RFQ/5 / Procurement of OVID-19 Response Medical Kits SADP-COVID19/HSGM/2020/ Component 1: Emergency C G/ÇA/RFQ/3 / Procurement of IBRD / 91030 Post Direct Selection Direct 3,054,717.28 Signed 2020-12-02 2020-05-05 2020-12-07 2020-12-03 2020-12-09 2020-12-22 2020-12-24 OVID-19 Response Personal Protective Equipme nt SADP-COVID19/HSGM/2020/ Component 1: Emergency C G/ÇA/RFQ/7 / Procurement of IBRD / 91030 Post Direct Selection Direct 12,833,145.00 Completed 2020-12-02 2020-05-05 2020-12-07 2020-12-04 2020-12-09 2020-12-20 2020-12-24 2020-12-23 OVID-19 Response Ventilators and Humidifiers f or Ventilators SADP-COVID19/HSGM/2021/ G/ÇA/RFQ/2 / Procurement of Component 1: Emergency C IBRD / 91030 Post Direct Selection Direct 452,000.00 Completed 2021-03-01 2021-02-16 2021-03-06 2021-03-05 2021-03-08 2021-04-03 2021-03-23 2021-04-08 Next Generation Sequencing OVID-19 Response Device and its Kits Page 1 SADP-COVID19/KHGM/2021/ Component 1: Emergency C IBRD / 91030 Post Direct Selection Direct 3,040,620.09 Signed 2021-09-06 2021-09-01 2021-09-11 2021-10-15 2021-10-16 2021-09-28 2021-12-31 G/ÇA/RFQ/4 / Procurement of OVID-19 Response Ventilators SADP-COVID19/HSGM/2021/ Component 1: Emergency C IBRD / 91030 Post Direct Selection Direct 2,699,400.00 Signed 2021-10-07 2021-10-19 2021-10-12 2021-11-08 2021-10-14 2021-11-27 2021-10-29 G/DC/1 / Whole genome sequ OVID-19 Response encing kit SADP-COVID19/HSGM/2021/ Component 1: Emergency C Request for Quota Single Stage - One E G/RFQ/1 / Fluorometric meas IBRD / 91030 Post Open - National 0.00 Canceled 2021-12-05 2022-01-30 2022-07-29 OVID-19 Response tions nvelope urement kit for NGS studies SADP-COVID19/HSGM/2021/ Component 1: Emergency C Request for Quota Single Stage - One E IBRD / 91030 Post Limited 584,269.96 Completed 2021-12-05 2021-12-06 2022-01-23 2022-01-01 2022-07-22 2022-01-13 G/RFQ/2 / Real Time PCR OVID-19 Response tions nvelope SADP-COVID19/HSGM/2021/ Component 1: Emergency C Request for Quota Single Stage - One E G/RFQ/3 / Neutralizing antibo IBRD / 91030 Post Limited 0.00 Canceled 2021-12-05 2021-12-07 2022-01-23 2022-07-22 OVID-19 Response tions nvelope dy serological diagnostic kit SADP-COVID19/HSGM/2021/ Component 1: Emergency C Request for Quota Single Stage - One E IBRD / 91030 Post Limited 246,000.00 Signed 2021-12-05 2021-12-07 2022-01-23 2021-12-30 2022-07-22 G/RFQ/4 / Extraction Kit OVID-19 Response tions nvelope SADP-COVID19/HSGM/2021/ Component 1: Emergency C Request for Quota Single Stage - One E G/RFQ/5 / Viral nucleic acid tr IBRD / 91030 Post Limited 756,000.00 Signed 2021-12-05 2021-12-07 2022-01-23 2021-12-23 2022-07-22 OVID-19 Response tions nvelope ansport and extraction medi um SADP-COVID19/HSGM/2021/ Component 1: Emergency C Request for Quota Single Stage - One E G/RFQ/6 / Artic primer set for IBRD / 91030 Post Limited 1,477,980.00 Completed 2021-12-05 2021-12-07 2022-01-23 2021-12-30 2022-07-22 2022-01-08 OVID-19 Response tions nvelope whole genom analysis SADP-COVID19/HSGM/2021/ Component 1: Emergency C Request for Quota Single Stage - One E G/RFQ/7 / Viral Transport Me IBRD / 91030 Post Limited 118,800.00 Completed 2021-12-05 2021-12-07 2022-01-23 2021-12-23 2022-07-22 2022-03-10 OVID-19 Response tions nvelope dium (for cell culture with sw ab) SADP-COVID19/HSGM/2021/ G/RFQ/8 / Bovine serum albu Component 1: Emergency C Request for Quota Single Stage - One E IBRD / 91030 Post Limited 0.00 Canceled 2021-12-05 2021-12-08 2022-01-23 2022-07-22 min fraction V 7.5% for cell c OVID-19 Response tions nvelope ulture (100 ml/vial) SADP-COVID19/HSGM/2021/ Component 1: Emergency C Request for Quota Single Stage - One E G/RFQ/9 / Fetal bovine serum IBRD / 91030 Post Limited 0.00 Canceled 2021-12-05 2021-12-10 2022-01-23 2022-07-22 OVID-19 Response tions nvelope (500 ml) for cell culture SADP-COVID19/HSGM/2021/ Component 1: Emergency C Request for Quota Single Stage - One E IBRD / 91030 Post Limited 423.90 Signed 2021-12-05 2021-12-07 2022-01-23 2021-12-31 2022-07-22 G/RFQ/10 / Antibiotic for cell OVID-19 Response tions nvelope culture SADP-COVID19/HSGM/2021/ Component 1: Emergency C Request for Quota Single Stage - One E G/RFQ/11 / DMEM medium fo IBRD / 91030 Post Limited 313,200.00 Signed 2021-12-05 2021-12-17 2022-01-23 2022-01-13 2022-07-22 OVID-19 Response tions nvelope r cell culture SADP-COVID19/HSGM/2021/ Component 1: Emergency C Request for Quota Single Stage - One E G/RFQ/12 / MEM medium for IBRD / 91030 Post Limited 0.00 Canceled 2021-12-05 2021-12-08 2022-01-23 2022-07-22 OVID-19 Response tions nvelope cell culture 10x1 liter SADP-COVID19/HSGM/2021/ Component 1: Emergency C Request for Quota Single Stage - One E G/RFQ/13 / MEM medium for IBRD / 91030 Post Limited 382.75 Signed 2021-12-05 2021-12-08 2022-01-23 2022-01-13 2022-07-22 OVID-19 Response tions nvelope cell culture (500 ml/bottle) SADP-COVID19/HSGM/2021/ Component 1: Emergency C Request for Quota Single Stage - One E IBRD / 91030 Post Limited 34,456.00 Completed 2021-12-05 2021-12-08 2022-01-23 2022-01-04 2022-07-22 2022-03-10 G/RFQ/14 / Spore (plastic) OVID-19 Response tions nvelope SADP-COVID19/HSGM/2021/ Component 1: Emergency C Request for Quota Single Stage - One E IBRD / 91030 Post Limited 95,580.00 Signed 2021-12-05 2021-12-08 2022-01-23 2022-01-20 2022-07-22 G/RFQ/15 / Criotube (2 ml) OVID-19 Response tions nvelope SADP-COVID19/HSGM/2021/ Component 1: Emergency C Request for Quota Single Stage - One E IBRD / 91030 Post Limited 21,004.00 Completed 2021-12-05 2021-12-08 2022-01-23 2022-01-05 2022-07-22 2022-03-08 G/RFQ/16 / Criotube (5 ml) OVID-19 Response tions nvelope SADP-COVID19/HSGM/2021/ Component 1: Emergency C Request for Quota Single Stage - One E IBRD / 91030 Post Limited 59,000.00 Signed 2021-12-05 2021-12-08 2022-01-23 2022-01-19 2022-07-22 G/RFQ/17 / Criotube box OVID-19 Response tions nvelope SADP-COVID19/HSGM/2021/ Component 1: Emergency C Request for Quota Single Stage - One E IBRD / 91030 Post Limited 12,862.00 Completed 2021-12-05 2021-12-09 2022-01-23 2021-12-28 2022-07-22 2022-02-10 G/RFQ/18 / Falcon tube (15 OVID-19 Response tions nvelope ml) SADP-COVID19/HSGM/2021/ Component 1: Emergency C Request for Quota Single Stage - One E IBRD / 91030 Post Limited 8,201.00 Completed 2021-12-05 2021-12-09 2022-01-23 2021-12-28 2022-07-22 2022-02-10 G/RFQ/19 / Falcon tube (50 OVID-19 Response tions nvelope ml) SADP-COVID19/HSGM/2021/ Component 1: Emergency C Request for Quota Single Stage - One E G/RFQ/21 / Cell culture plate IBRD / 91030 Post Limited 11,016.48 Signed 2021-12-05 2021-12-09 2022-01-23 2022-01-19 2022-07-22 OVID-19 Response tions nvelope (24 dishes - flat bottom) SADP-COVID19/HSGM/2021/ Component 1: Emergency C Request for Quota Single Stage - One E IBRD / 91030 Post Limited 2,690.40 Completed 2021-12-05 2021-12-09 2022-01-23 2022-01-13 2022-07-22 2022-01-25 G/RFQ/22 / Flask (75 cm2) OVID-19 Response tions nvelope SADP-COVID19/HSGM/2021/ Component 1: Emergency C Request for Quota Single Stage - One E IBRD / 91030 Post Limited 8,814.60 Signed 2021-12-05 2022-05-09 2022-01-23 2022-01-11 2022-07-22 G/RFQ/23 / Flask (25 cm2) OVID-19 Response tions nvelope SADP-COVID19/HSGM/2021/ Component 1: Emergency C Request for Quota Single Stage - One E IBRD / 91030 Post Limited 0.00 Canceled 2021-12-05 2021-12-07 2022-01-23 2022-07-22 G/RFQ/24 / Flask (12.5 cm2) OVID-19 Response tions nvelope SADP-COVID19/HSGM/2021/ Component 1: Emergency C Request for Quota Single Stage - One E IBRD / 91030 Post Limited 7,080.00 Signed 2021-12-05 2021-12-22 2022-01-23 2022-01-19 2022-07-22 G/RFQ/26 / Pipette tip OVID-19 Response tions nvelope SADP-COVID19/HSGM/2021/ Component 1: Emergency C Request for Quota Single Stage - One E IBRD / 91030 Post Limited 58,441.72 Signed 2021-12-05 2021-12-23 2022-01-23 2022-02-01 2022-07-22 G/RFQ/27 / Automatic pipette OVID-19 Response tions nvelope tip SADP-COVID19/HSGM/2021/ Component 1: Emergency C Request for Quota Single Stage - One E IBRD / 91030 Post Limited 28,320.00 Signed 2021-12-05 2021-12-24 2022-01-23 2022-03-01 2022-07-22 G/RFQ/29 / PCR plate and sea OVID-19 Response tions nvelope ler SADP-COVID19/HSGM/2021/ Component 1: Emergency C Request for Quota Single Stage - One E IBRD / 91030 Post Limited 0.00 Canceled 2021-12-05 2021-12-30 2022-01-23 2022-07-22 G/RFQ/31 / Glove OVID-19 Response tions nvelope SADP-COVID19/HSGM/2021/ Component 1: Emergency C Request for Quota Single Stage - One E IBRD / 91030 Post Limited 0.00 Canceled 2021-12-05 2021-12-30 2022-01-23 2022-07-22 G/RFQ/32 / Glove latex OVID-19 Response tions nvelope SADP-COVID19/HSGM/2021/ Component 1: Emergency C Request for Quota Single Stage - One E IBRD / 91030 Post Limited 0.00 Canceled 2021-12-05 2022-01-05 2022-01-23 2022-07-22 G/RFQ/35 / Protective gloves OVID-19 Response tions nvelope Page 2 SADP-COVID19/HSGM/2021/ Component 1: Emergency C Request for Quota Single Stage - One E IBRD / 91030 Post Limited 0.00 Canceled 2021-12-05 2021-12-30 2022-01-23 2022-07-22 G/RFQ/36 / Surgical mask OVID-19 Response tions nvelope SADP-COVID19/HSGM/2021/ Component 1: Emergency C Request for Quota Single Stage - One E G/RFQ/37 / PCR reagents (on IBRD / 91030 Post Limited 0.00 Canceled 2021-12-06 2021-12-29 2022-01-24 2022-07-23 OVID-19 Response tions nvelope e step RT-PCr enzyme-rxn) SADP-COVID19/HSGM/2021/ Component 1: Emergency C Request for Quota Single Stage - One E Pending Impl G/RFQ/39 / Exanthematous di IBRD / 91030 Post Limited 0.00 2021-12-06 2022-01-24 2022-07-23 OVID-19 Response tions nvelope ementation seases multiplex PCR kit SADP-COVID19/HSGM/2021/ Component 1: Emergency C Request for Quota Single Stage - One E G/RFQ/40 / Gastrointestinal s IBRD / 91030 Post Limited 0.00 Canceled 2021-12-06 2022-03-24 2022-01-24 2022-07-23 OVID-19 Response tions nvelope ystem infections multiplex P CR kit SADP-COVID19/HSGM/2021/ Component 1: Emergency C Request for Quota Single Stage - One E G/RFQ/41 / Central nervous s IBRD / 91030 Post Limited 0.00 Canceled 2021-12-06 2022-03-28 2022-01-24 2022-07-23 OVID-19 Response tions nvelope ystem infections multiplex P CR kit SADP-COVID19/HSGM/2021/ Component 1: Emergency C Request for Quota Single Stage - One E Pending Impl G/RFQ/42 / Respiratory factor IBRD / 91030 Post Limited 0.00 2021-12-06 2022-01-24 2022-07-23 OVID-19 Response tions nvelope ementation s multiplex PCR SADP-COVID19/HSGM/2021/ Component 1: Emergency C Request for Quota Single Stage - One E Pending Impl IBRD / 91030 Post Limited 0.00 2021-12-06 2022-01-24 2022-07-23 G/RFQ/43 / Automatic pipette OVID-19 Response tions nvelope ementation set SADP-COVID19/HSGM/2021/ Component 1: Emergency C Request for Quota Single Stage - One E Under Imple G/RFQ/44 / Automatic pipette IBRD / 91030 Post Limited 0.00 2021-12-06 2022-01-17 2022-01-24 2022-07-23 OVID-19 Response tions nvelope mentation single channel (multi-shot) SADP-COVID19/HSGM/2021/ Component 1: Emergency C Request for Quota Single Stage - One E G/RFQ/45 / Automatic pipette IBRD / 91030 Post Limited 0.00 Canceled 2021-12-06 2022-01-13 2022-01-24 2022-07-23 OVID-19 Response tions nvelope multi-channel (multi-shot) SADP-COVID19/HSGM/2021/ Component 1: Emergency C Request for Quota Single Stage - One E Pending Impl IBRD / 91030 Post Limited 0.00 2021-12-05 2022-01-23 2022-07-22 G/RFQ/30 / Laboratry coat OVID-19 Response tions nvelope ementation SADP-COVID19/HSGM/2021/ Component 1: Emergency C Request for Quota Single Stage - One E G/RFQ/20 / Cell culture plate IBRD / 91030 Post Limited 50,504.00 Completed 2021-12-07 2021-12-14 2022-01-25 2021-12-31 2022-07-24 2022-01-25 OVID-19 Response tions nvelope (96 well - flat bottom) SADP-COVID19/HSGM/2021/ Component 1: Emergency C Request for Quota Single Stage - One E IBRD / 91030 Post Limited 66,729.00 Completed 2021-12-07 2021-12-22 2022-01-25 2022-01-11 2022-07-24 2022-02-10 G/RFQ/25 / Autoclave pouch OVID-19 Response tions nvelope SADP-COVID19/PYDB/2021/ Component 1: Emergency C Request for Quota Single Stage - One E Pending Impl IBRD / 91030 Post Limited 0.00 2022-01-09 2022-03-06 2022-12-31 G/RFQ/1 / High-speed Separa OVID-19 Response tions nvelope ementation tor SADP-COVID19/HSGM/2021/ Component 1: Emergency C Pending Impl G/DC/2 / Combined Rapid Mol IBRD / 91030 Post Direct Selection Direct 0.00 2022-01-10 2022-01-15 2022-01-17 2022-12-31 OVID-19 Response ementation ecular Diagnostic Kits for Infe ctious Diseases SADP-COVID19/HSGM/2021/ Component 1: Emergency C Request for Quota Single Stage - One E Pending Impl G/RFQ/47 / Deep-Freezer - U IBRD / 91030 Post Limited 0.00 2022-01-30 2022-03-20 2022-09-16 OVID-19 Response tions nvelope ementation pright – 80 C (510-600 L) SADP-COVID19/HSGM/2021/ Component 1: Emergency C Request for Quota Single Stage - One E Under Imple IBRD / 91030 Post Limited 0.00 2022-01-30 2022-03-30 2022-03-20 2022-09-16 G/RFQ/50 / PCR Cabinet OVID-19 Response tions nvelope mentation SADP-COVID19/HSGM/2022/ Component 1: Emergency C IBRD / 91030 Post Direct Selection Direct 0.00 Canceled 2022-02-09 2022-02-15 2022-03-01 2024-01-17 G/DC/1 / Cell Factory Device OVID-19 Response SADP-COVID19/HSGM/2021/ G/RFQ/28 / PCR consumables Component 1: Emergency C Request for Quota Single Stage - One E IBRD / 91030 Post Limited 0.00 Canceled 2021-12-07 2021-12-28 2022-01-25 2022-07-24 (0.2 ml) (strip, in two separat OVID-19 Response tions nvelope e volumes of 0.1 and 0.2 ul) SADP-COVID19/HSGM/2021/ Component 1: Emergency C Request for Quota Single Stage - One E G/RFQ/38 / PCR reagents (pri IBRD / 91030 Post Limited 0.00 Canceled 2021-12-06 2022-01-13 2022-01-24 2022-07-23 OVID-19 Response tions nvelope mary, probe -bp) SADP-COVID19/HSGM/2021/ Component 1: Emergency C Request for Quota Single Stage - One E G/RFQ/48 / Deep-Freezer - U IBRD / 91030 Post Limited 0.00 Canceled 2022-01-30 2022-02-15 2022-03-20 2022-09-16 OVID-19 Response tions nvelope pright – 20 C (min. 400 L) SADP-COVID19/HSGM/2021/ Component 1: Emergency C Request for Quota Single Stage - One E G/RFQ/49 / Under-counter 4 IBRD / 91030 Post Limited 0.00 Canceled 2022-01-30 2022-03-20 2022-09-16 OVID-19 Response tions nvelope C Refrigerator (Min. 90 L) SADP-COVID19/HSGM/2022/ Component 1: Emergency C Request for Quota Single Stage - One E Pending Impl G/RFQ/1 / Refrigerator (labor IBRD / 91030 Post Limited 0.00 2022-03-20 2022-05-08 2022-11-04 OVID-19 Response tions nvelope ementation atory type at least 250 liters) SADP-COVID19/HSGM/2021/ Component 1: Emergency C Request for Quota Single Stage - One E G/RFQ/33 / Shoe covers (for t IBRD / 91030 Post Limited 0.00 Canceled 2022-01-30 2022-03-20 2022-09-16 OVID-19 Response tions nvelope he machine) SADP-COVID19/HSGM/2021/ Component 1: Emergency C Request for Quota Single Stage - One E G/RFQ/34 / Shoe covers (not IBRD / 91030 Post Limited 0.00 Canceled 2022-01-30 2022-03-20 2022-09-16 OVID-19 Response tions nvelope for the machine) SADP-COVID19/KHGM/2022/ Component 1: Emergency C Open - Internationa Single Stage - One E G/RFB/1 / Procurement of Dig IBRD / 91030 Post Request for Bids 0.00 Signed 2022-08-15 2022-09-08 2022-09-26 2022-09-13 2022-10-26 2022-09-09 2022-11-25 2022-12-09 2022-12-30 2023-06-28 OVID-19 Response l nvelope ital X-Ray Device GO-DS-AF-01 / COVID-19 Va Component 1: Emergency C Direct - Internation Under Imple COFN / C2110 Prior Direct Selection 0.00 2020-11-02 2022-11-29 2020-11-07 2022-11-29 2020-12-25 2021-11-15 ccine Procurement from BioN OVID-19 Response al mentation Tech1 No.1 GO-DS-AF-02 / COVID-19 Va Component 1: Emergency C Direct - Internation Under Imple COFN / C2110 Prior Direct Selection 0.00 2021-04-05 2022-11-29 2021-04-10 2022-11-29 2021-05-17 2023-05-31 ccine Procurement from BioN OVID-19 Response al mentation Tech1 No.2 SADP-COVID19/HSGM/2023/ G/ÇA/RFQ/1 / SARS CoV-2 Re Component 1: Emergency C Pending Impl al Time PCR Diagnostic Kit an IBRD / 91030 Post Direct Selection Direct - National 0.00 2023-01-03 2023-01-08 2023-01-11 2023-12-31 OVID-19 Response ementation d Respiratory Multiplex PCR Diagnostic (Inf A+B+COVID+ RSV) Kits Page 3 SADP-COVID19/HSGM/2023/ Component 1: Emergency C Pending Impl IBRD / 91030 Post Direct Selection Direct - National 0.00 2023-01-03 2023-01-08 2023-01-11 2023-12-31 G/ÇA/RFQ/2 / Nucleic Acid Ex OVID-19 Response ementation traction Kit SADP-COVID19/KHGM/2023/ Component 1: Emergency C Request for Quota Single Stage - One E Pending Impl G/RFQ/1 / Transurethral Rese IBRD / 91030 Post Limited 0.00 2023-05-15 2023-06-07 2023-07-22 OVID-19 Response tions nvelope ementation ction Motor (Brain Surgery) SADP-COVID19/KHGM/2023/ Component 1: Emergency C Request for Quota Single Stage - One E Pending Impl G/RFQ/2 / Endovision System IBRD / 91030 Post Limited 0.00 2023-05-15 2023-05-29 2023-07-13 OVID-19 Response tions nvelope ementation (Ent Polyclinic Type) SADP-COVID19/KHGM/2023/ Component 1: Emergency C Request for Quota Single Stage - One E Pending Impl G/RFQ/3 / Transurethral Rese IBRD / 91030 Post Limited 0.00 2023-05-15 2023-05-29 2023-07-13 OVID-19 Response tions nvelope ementation ction Motor (Ent) SADP-COVID19/KHGM/2023/ Component 1: Emergency C Request for Quota Single Stage - One E Pending Impl G/RFQ/4 / Intermediate Magn IBRD / 91030 Post Limited 0.00 2023-05-15 2023-05-29 2023-07-13 OVID-19 Response tions nvelope ementation etic Resonance Imaging Devi ce SADP-COVID19/KHGM/2023/ Component 1: Emergency C Request for Quota Single Stage - One E Pending Impl G/RFQ/5 / Procurement of Dig IBRD / 91030 Post Limited 0.00 2023-06-10 2023-06-24 2023-07-14 OVID-19 Response tions nvelope ementation ital X-Ray Device (C-Arm Sco py) SADP-COVID19/KHGM/2023/ Component 1: Emergency C Request for Quota Single Stage - One E Pending Impl G/RFQ/6 / Procurement of Dig IBRD / 91030 Post Limited 0.00 2023-06-10 2023-06-24 2023-07-14 OVID-19 Response tions nvelope ementation ital Mobile X-Ray System NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Actual Amount Invitation to Identifie Draft Negotiated Cont Component Review Type Method Contract Type Process Status Teams of Reference Signed Contract Contract Completion Description o. h (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SADP-COVID19/PYDB/2022/C Component 1: Emergency C Individual Consult Pending Impleme IBRD / 91030 Post Limited 0.00 2022-08-15 2022-08-22 2022-08-27 2022-09-20 2023-12-31 S/IC/1 / Environmental Specia OVID-19 Response ant Selection ntation list SADP-COVID19/PYDB/2022/C Component 1: Emergency C Individual Consult Pending Impleme IBRD / 91030 Post Limited 0.00 2022-08-15 2022-08-22 2022-08-27 2022-09-20 2023-12-31 S/IC/2 / Social Specialist OVID-19 Response ant Selection ntation Page 4 PROCUREMENT PLAN (Textual Part) Project information: P173076 – Moldova Water Security and Sanitation Project – Project Preparation Grant Project Implementation agency: Ministry of Agriculture, Regional Development and Environment through its Public Institution “Environmental Projects Implementation Unit” Date of the Procurement Plan: November 11, 2020 Period covered by this Procurement Plan: November 2020 – July 2021 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016, revised November 2017 and August 2018) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. Under the proposed project the country’s procurement procedures will not be used. When approaching the national market, the Implementation Agency will use the documents agreed with the Bank. However, these arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. Not Applicable Procurement of Second-Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables. Not Applicable PROCUREMENT Moldova : Moldova Water Security and Sanitation Project PLAN General Information Country: Moldova 2022-05-25 Bank’s Approval Date of the Original Procurement Plan: 2023-06-07 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P173076 GPN Date: 2020-11-09 Project Name: Moldova Water Security and Sanitation Project Loan / Credit No: IDA / 70270 National Office for Regional and Local Development Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Request for Bids - MD-PIU-NORLD-346164-CW- Strengthening institutional c Open - Internationa Single Stage - One E Small Works SPD Pending Imp 2025-08-2 RFB / Improvement of Water IDA / 70270 apacity at national and local Post Request for Bids 8,000,000.00 0.00 2023-11-01 2023-11-15 2023-12-27 2024-01-26 2024-03-01 l nvelope (1 envelope proce lementation 3 Supply Services in Riscani Di levels for WSS service delive ss) strict ry Request for Bids - MD-PIU-NORLD-346191-CW- Strengthening institutional c Open - Internationa Single Stage - One E Works (without pr 15,265,000.0 Pending Imp 2025-08-2 RFB / Improvement of Water IDA / 70270 apacity at national and local Prior Request for Bids 0.00 2023-11-01 2023-11-16 2023-12-28 2024-01-27 2024-03-02 l nvelope equalification) SP 0 lementation 4 Supply Services in Cahul Dist levels for WSS service delive D rict ry Request for Bids - MD-PIU-NORLD-346197-CW- Strengthening institutional c Open - Internationa Single Stage - One E Small Works SPD Pending Imp 2026-05-2 RFB / Improvement of Sanitat IDA / 70270 apacity at national and local Post Request for Bids 9,805,000.00 0.00 2024-04-01 2024-04-15 2024-05-27 2024-06-26 2024-07-31 l nvelope (1 envelope proce lementation 2 ion Services in Comrat Distric levels for WSS service delive ss) t ry GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MD-PIU-NORLD-346199-GO- Strengthening institutional c RFB / Procurement of Septic t apacity at national and local Single Stage - One E Pending Impl IDA / 70270 Post Request for Bids Open - National 192,000.00 0.00 2025-07-01 2025-07-15 2025-08-26 2025-09-25 2025-10-30 2026-04-28 ruck and Bobcat Skid-steer L levels for WSS service delive nvelope ementation oader for Comrat Subproject ry MD-PIU-NORLD-346206-GO- Strengthening institutional c RFB / Procurement of Septic t apacity at national and local Single Stage - One E Pending Impl IDA / 70270 Post Request for Bids Open - National 192,000.00 0.00 2025-01-01 2025-01-15 2025-02-26 2025-03-28 2025-05-02 2025-10-29 ruck and Bobcat Skid-steer L levels for WSS service delive nvelope ementation oader for Soroca Subproject ry NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Strengthening institutional c MD-PIU-NORLD-346141-CS-C Consultant Qualifi Pending Impleme IDA / 70270 apacity at national and local Post Open - National 75,000.00 0.00 2023-04-01 2023-04-03 2023-04-24 2023-05-08 2023-05-29 2023-10-26 QS / ESIA for Riscani District cation Selection ntation levels for WSS service delive ry MD-PIU-NORLD-346153-CS-C Strengthening institutional c Quality And Cost- Open - Internationa Pending Impleme QS / Technical Supervision C IDA / 70270 apacity at national and local Post 160,000.00 0.00 2023-09-01 2023-09-20 2023-11-03 2023-12-01 2023-12-22 2024-01-26 2024-03-01 2025-08-23 Based Selection l ntation ompany Selection for Riscani levels for WSS service delive District ry Strengthening institutional c MD-PIU-NORLD-346176-CS-C Consultant Qualifi Under Implement IDA / 70270 apacity at national and local Post Open - National 75,000.00 0.00 2023-03-01 2023-03-09 2023-03-03 2023-03-24 2023-04-07 2023-04-28 2023-09-25 QS / ESIA for Cahul District cation Selection ation levels for WSS service delive ry MD-PIU-NORLD-346186-CS- Strengthening institutional c Quality And Cost- Open - Internationa Pending Impleme QCBS / Technical Supervision IDA / 70270 apacity at national and local Post 306,000.00 0.00 2023-09-07 2023-09-28 2023-11-10 2023-12-08 2023-12-26 2024-01-27 2024-03-02 2025-08-24 Based Selection l ntation Company Selection for Cahul levels for WSS service delive District ry MD-PIU-NORLD-346194-CS- Strengthening institutional c Quality And Cost- Open - Internationa Under Implement QCBS / Feasibility study and IDA / 70270 apacity at national and local Post 318,000.00 0.00 2023-03-09 2023-03-14 2023-03-30 2023-03-20 2023-05-04 2023-05-25 2023-06-24 2023-07-22 2023-08-26 2024-03-13 Based Selection l ation ESIA for Comrat Subproject levels for WSS service delive ry MD-PIU-NORLD-346195-CS-C Strengthening institutional c QS / Topographical and geolo apacity at national and local Consultant Qualifi Pending Impleme gical survey, expertise of exi IDA / 70270 Post Open - National 11,000.00 0.00 2024-04-01 2024-04-19 2024-05-24 2024-06-14 2024-07-19 2024-11-26 levels for WSS service delive cation Selection ntation sting pumping station buildin ry gs in Comrat subproject MD-PIU-NORLD-346198-CS- Strengthening institutional c Quality And Cost- Open - Internationa Pending Impleme QCBS / Technical Supervision IDA / 70270 apacity at national and local Post 200,000.00 0.00 2024-11-15 2024-12-06 2025-01-11 2025-02-08 2025-03-06 2025-04-17 2025-05-22 2026-05-22 Based Selection l ntation Company Selection for Comr levels for WSS service delive at Subproject ry MD-PIU-NORLD-346201-CS-C Strengthening institutional c QS / Topographical and geolo apacity at national and local Consultant Qualifi Under Implement gical survey, expertise of exi IDA / 70270 Post Open - National 6,600.00 0.00 2023-03-20 2023-06-14 2023-04-03 2023-05-08 2023-05-22 2023-06-26 2023-09-24 levels for WSS service delive cation Selection ation sting pumping station buildin ry gs in Soroca subproject MD-PIU-NORLD-346202-CS- Strengthening institutional c Quality And Cost- Open - Internationa Pending Impleme QCBS / Technical Supervision IDA / 70270 apacity at national and local Post 190,500.00 0.00 2023-08-01 2023-08-22 2023-10-05 2023-11-02 2023-12-02 2024-01-06 2024-02-10 2025-02-09 Based Selection l ntation Company Selection for Soroc levels for WSS service delive a Subproject ry MD-PIU-NORLD-346209-CS- Strengthening institutional c Quality And Cost- Open - Internationa Pending Impleme QCBS / National Water Suppl IDA / 70270 apacity at national and local Post 1,375,000.00 0.00 2023-05-01 2023-05-22 2023-07-05 2023-08-02 2023-09-01 2023-10-06 2023-11-10 2025-05-03 Based Selection l ntation y and Sanitation Sectoral De levels for WSS service delive velopment Plan ry MD-PIU-NORLD-365353-CS-C Project management and co Consultant Qualifi Under Implement QS / Video spot promoting W IDA / 70270 Post Open - National 3,000.00 0.00 2023-06-16 2023-06-07 2023-07-07 2023-08-20 2023-09-19 2023-10-24 2023-11-23 ordination cation Selection ation SS program, TUM Page 1 MD-PIU-NORLD-368215-CS-C QS / Elaboration of the Emplo Strengthening institutional c yer’s Requirements chapters apacity at national and local Consultant Qualifi Under Implement for the project "Construction IDA / 70270 Post Open - National 50,000.00 0.00 2023-06-21 2023-06-22 2023-07-12 2023-08-25 2023-09-24 2023-10-29 2024-01-07 levels for WSS service delive cation Selection ation of the wastewater treatment ry plant and the sewerage infra structure in the municipality of Soroca" INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MD-PIU-NORLD-296455-CS-I Project management and co Individual Consult IDA / 70270 Post Open 238,392.00 3,080.00 Signed 2022-05-24 2022-05-26 2022-07-12 2022-07-14 2022-08-02 2022-07-22 2022-09-06 2022-07-27 2027-01-31 NDV / Project manager ordination ant Selection MD-PIU-NORLD-296461-CS-I Project management and co Individual Consult IDA / 70270 Post Open 170,280.00 0.00 Canceled 2022-05-24 2022-05-26 2022-07-12 2022-08-02 2022-09-06 2027-01-31 NDV / Financial Management ordination ant Selection Officer MD-PIU-NORLD-296462-CS-I Project management and co Individual Consult IDA / 70270 Prior Open 170,280.00 26,974.08 Signed 2022-05-24 2022-05-31 2022-07-12 2022-08-01 2022-08-02 2022-08-04 2022-09-06 2022-08-06 2027-01-31 NDV / Procurement Specialist ordination ant Selection MD-PIU-NORLD-296463-CS-I Project management and co Individual Consult IDA / 70270 Post Open 127,682.00 1,649.61 Signed 2022-05-24 2022-05-26 2022-07-12 2022-07-14 2022-08-02 2022-07-22 2022-09-06 2022-07-27 2027-01-31 NDV / Chief WWS Engineer ordination ant Selection MD-PIU-NORLD-296464-CS-I Project management and co Individual Consult IDA / 70270 Post Open 122,602.00 3,055.00 Signed 2022-05-24 2022-05-26 2022-07-12 2022-07-14 2022-08-02 2022-07-22 2022-09-06 2022-07-27 2027-01-31 NDV / Environmental Speciali ordination ant Selection st MD-PIU-NORLD-296465-CS-I Project management and co Individual Consult IDA / 70270 Post Open 122,602.00 1,583.72 Signed 2022-05-24 2022-05-26 2022-07-12 2022-07-14 2022-08-02 2022-07-22 2022-09-06 2022-07-27 2027-01-31 NDV / Social Specialist ordination ant Selection MD-PIU-NORLD-303355-CS-I Project management and co Individual Consult IDA / 70270 Post Open 170,280.00 2,150.00 Signed 2022-07-11 2022-07-14 2022-08-29 2022-08-01 2022-09-19 2022-08-02 2022-10-24 2022-08-04 2027-03-20 NDV / Financial Management ordination ant Selection officer MD-PIU-NORLD-318444-CS-I Project management and co Individual Consult Under Implement IDA / 70270 Post Open - National 110,000.00 0.00 2022-10-13 2022-11-18 2022-12-05 2022-12-26 2023-01-30 2024-01-29 NDV / Administrative Assista ordination ant Selection ation nt MD-PIU-NORLD-318718-CS-I Project management and co Individual Consult Under Implement IDA / 70270 Post Open - National 117,000.00 0.00 2022-10-20 2022-11-17 2022-12-08 2022-12-29 2023-02-02 2024-02-01 NDV / WWS Engineer ordination ant Selection ation MD-PIU-NORLD-320076-CS-I Project management and co Individual Consult Under Implement NDV / Monitoring and Evaluat IDA / 70270 Post Open - National 81,000.00 0.00 2022-10-21 2022-11-17 2022-12-09 2022-12-30 2023-02-03 2024-01-29 ordination ant Selection ation ion Specialist MD-PIU-NORLD-327325-CS-I Project management and co Individual Consult Under Implement NDV / Driver Vehicles/Logisti IDA / 70270 Post Open - National 55,000.00 0.00 2022-11-30 2022-12-01 2023-01-20 2023-02-10 2023-03-17 2024-03-11 ordination ant Selection ation cs Specialist MD-PIU-NORLD-328118-CS-I Project management and co Individual Consult Under Implement NDV / Communication Specia IDA / 70270 Post Open - National 63,000.00 0.00 2022-12-07 2022-11-23 2023-01-25 2023-02-15 2023-03-22 2024-03-16 ordination ant Selection ation list (Part – Time Assignment) MD-PIU-NORLD-339411-CS-I NDV / Technical consultant fo Project management and co Individual Consult Under Implement r the development of a techn IDA / 70270 Post Open - National 4,500.00 0.00 2023-01-30 2023-02-09 2023-03-17 2023-04-07 2023-05-12 2023-06-11 ordination ant Selection ation ical market study regarding o n-site sanitation systems (se ptic tanks) MD-PIU-NORLD-339413-CS-I NDV / Legal consultant for th e elaboration of the draft Go vernment Decision regarding Project management and co Individual Consult Under Implement approval of criteria for author IDA / 70270 Post Open - National 6,600.00 0.00 2023-01-30 2023-02-09 2023-03-31 2023-04-21 2023-05-26 2023-07-10 ordination ant Selection ation ization, construction, registra tion, control, operation and maintenance of appropriate i ndividual wastewater collecti on and treatment systems MD-PIU-NORLD-339414-CS-I NDV / Legal consultant for th e elaboration of the required Project management and co Individual Consult Under Implement IDA / 70270 Post Open - National 9,500.00 0.00 2023-01-30 2023-02-09 2023-03-31 2023-04-21 2023-05-26 2023-07-25 amendments for Law no. 303 ordination ant Selection ation /2013 regarding the public w ater supply and sewerage ser vice MD-PIU-NORLD-339416-CS-I NDV / Technical consultant to Project management and co Individual Consult Under Implement IDA / 70270 Post Open - National 72,000.00 0.00 2023-01-30 2023-02-09 2023-03-31 2023-04-21 2023-05-26 2024-12-06 provide support to the MIRD i ordination ant Selection ation n the implementation of the Subcomponent 1.1. MD-PIU-NORLD-339417-CS-I NDV / Strategic planning con Project management and co Individual Consult Under Implement sultant to provide support to IDA / 70270 Post Open - National 72,000.00 0.00 2023-01-30 2023-02-09 2023-03-31 2023-04-21 2023-05-26 2024-12-06 ordination ant Selection ation MIRD in the implementation of the Subcomponent 2.1. MD-PIU-NORLD-346083-CS-C Strengthening institutional c DS / Review and up-date of D apacity at national and local Pending Impleme IDA / 70270 Post Direct Selection Direct - National 145,500.00 0.00 2023-03-01 2023-03-11 2023-05-15 2023-11-11 etailed Design technical docu levels for WSS service delive ntation ments in Riscani district ry MD-PIU-NORLD-346170-CS-C Strengthening institutional c QS / Review and up-date of D apacity at national and local Under Implement IDA / 70270 Post Direct Selection Direct - National 218,000.00 0.00 2023-03-01 2023-03-11 2023-03-15 2023-05-19 2023-11-15 etailed Design technical docu levels for WSS service delive ation ments in Cahul district ry MD-PIU-NORLD-358033-CS-I Project management and co Individual Consult Under Implement IDA / 70270 Post Open - National 50,000.00 0.00 2023-04-21 2023-04-25 2023-06-09 2023-06-30 2023-08-04 2026-08-04 NDV / WASH Engineer ordination ant Selection ation MD-PIU-NORLD-358043-CS-I Project management and co Individual Consult IDA / 70270 Post Open - National 32,000.00 0.00 Canceled 2023-05-05 2023-05-06 2023-06-23 2023-07-14 2023-08-18 2025-08-18 NDV / Procurement Assistant ordination ant Selection MD-PIU-NORLD-355433-CS-I Project management and co Individual Consult Under Implement IDA / 70270 Post Open - National 115,000.00 0.00 2023-04-10 2023-05-06 2023-05-16 2023-06-06 2023-07-11 2027-08-05 NDV / Chief WWS Engineer-2 ordination ant Selection ation MD-PIU-NORLD-365351-CS-I Project management and co Individual Consult Under Implement IDA / 70270 Prior Open - National 85,140.00 0.00 2023-06-16 2023-06-07 2023-08-04 2023-08-25 2023-09-29 2026-06-25 NDV / Procurement Specialist ordination ant Selection ation 2 Page 2 MD-PIU-NORLD-369172-CS-I NDV / International individual consultant for assessment of Increasing access to safely Individual Consult Open - Internationa Under Implement the need to update/adjust th IDA / 70270 managed WSS services in se Post 15,000.00 0.00 2023-06-30 2023-06-28 2023-08-18 2023-09-08 2023-10-13 2023-11-12 ant Selection l ation e Moldovan Construction Nor lected rural areas and towns mative G.03.02:2015, and Moldovan Construction Norm ative NCM G.03.01:2017 MD-PIU-NORLD-369411-CS-I Strengthening institutional c NDV / Individual consultant f apacity at national and local Individual Consult Under Implement or development of the Imple IDA / 70270 Post Open - National 6,500.00 0.00 2023-06-30 2023-06-28 2023-08-18 2023-09-08 2023-10-13 2023-11-22 levels for WSS service delive ant Selection ation mentation Plan of Directive 9 ry 1/271/CEE on urban wastewa ter treatment Page 3 UNITED REPUBLIC OF TANZANIA Procurement Plan General 1. Project Information Country: Tanzania Project Name: Roads to Inclusion and Social Economic Opportunities (RISE) Project ID: P164920 2. Project Implementation Agency: TARURA 3. Date of the Procurement Plan: TBD 4. Period Covered by this procurement plan: I. Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitutes the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. II. Bank’s Standard Procurement Documents: The Bank’s Standard Procurement Documents shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. III. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in The Public Procurement Act, 2011, The Public Procurement (Amendment) Act, 2016 and the Regulations, 2016, such 1 arrangements shall be subject to paragraph 5.3 and 5.4 of the Procurement Regulations and the following conditions: o There should be no mandatory requirements for inclusion of local experts and firms for the consulting assignments; o There should be no exclusive preference based on threshold prescribed in PPA and its Regulations; o Negotiations with the lowest evaluated bidder to reduce price in the case of goods, works and non-consulting services where competitive methods have been used shall not be allowed; o The fixed budget method shall not be used for goods, works and non- consulting services; o Established and approved procurement standards by the government may be used, provided that they are not restrictive When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. In accordance with paragraph 5.4(c) and 5.5 of the Procurement Regulations, the request for bids/request for proposals/request for quotations document shall require that Bidders/Proposers submitting Bids/Proposals/quotations present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights. The form of the Letter of Acceptance is attached in Appendix 1. IV. Prequalification: Not Applicable V. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Not Applicable VI. Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations: Not Applicable VII. Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Not Applicable Domestic preference is not applicable for National Open Competitive Procurement VIII. Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations is Applicable. Not Applicable IX. Other Relevant Procurement Information Not Applicable 2 3 X. Threshold for Prior Review, Procurement Approaches and Methods – Good, Works and Non- Consulting Services Procurement Approaches and Methods (US$ millions) Prior Review Category (US$ millions) Open Open National Request for Quotation International (RfQ) Works ≥5 ≥ 15 < 15 ≤ 0.2 Goods, IT, and non-consulting ≥ 1.5 ≥5 <5 ≤ 0.1 services Post Review: All contracts not subject to prior review shall be subject to post review. Summary of the procurement packages for Good, Works and Non-Consulting Services (Planned for the first 18 months after project effectiveness): Evaluation Market Procurem Expect Selecti Options Expect Approac ent ed Revie on (Most Domesti ed date h Process date of Estimat w by Method Advantage Prequalifica c of Sr. Contract (Open- (Single bid/ ed Cost Bank (RFP, ous Bid, tion Prefere Contra No Description National stage- propos (US$) (Prior/ RFB, BAFO, (Yes/ No) nce ct / single al Post) RFQ, Rated (Yes/No) Signat Commented [RJM1]: Dates will be updated when Limited envelope openin finalizing the PP. DS etc.) Criteria ure etc.) etc.) g etc.) GOODS Component 2: Institutional Strengthening, Technical Assistance and Project Management and monitoring Procurement of Vehicles (Lot 1) Most and Odometer Single Open - Advantageo 20 Feb 8 April 1. and GPS for 280,000 Post National RFB us Bid stage One- No No 2019 2019 Inventory and Envelope (MAB) Condition Survey (Lot 2). Procurement of Desktop Computers and Single Laptops (Lot 1) Open - 20 Feb 8 April 2. and heavy duty 160,000 Post National RFB MAB stage One- No No 2019 2019 Envelope photocopy/printi ng machine (Lot 2) 4 Procurement of Single Limited - 13 Feb 1 April 3. Survey 30,000 Post National RFQ MAB stage One- No No 2019 2019 Equipment Envelope Tender for the Single Supply of Video Limited - 13 Feb 1 April 4. 100,000 Post RFQ MAB stage One- No No Conferencing National 2019 2019 Envelope Facilities 570,00 Total Goods 0 XI. Thresholds for Prior Review, Selection Approaches and Methods – Consulting Services Category Prior Review Short List of National Consultants (US$ millions) Consulting Engineering and Construction Supervision Services Consultants (Firms) ≥ 0.5 ≤ 0.3 ≤ 0.3 Individual Consultants ≥ 0.2 n.a. n.a. Note: Consultancy services estimated to cost equivalent to US $ 300,000 and above per contract shall be advertised in the United Nations Development Business (UNDB) online in addition to advertising in national newspaper(s) of wide circulation and/or regional newspaper. XII. Summary of the procurement packages for Consulting Services -Planned for the first 18 months after project effectiveness): Market Selection Expecte Revie Approach Method d date Expected Durati Estimat w by (Open - (QCBS, Shortlisti Sr. of bid/ date of on Contract Description ed Cost Bank Internatio FBS, ng No proposa Contract (month (US$) (Prior/ nal/ LCBS, (Yes/ No) l Signature s) Post) National/ QBS, CQS, opening etc.) DS etc.) Component 1: Rural Road Development and Maintenance Consulting Services for Road Safety Specialist to (i) Carry out Road Safety audit of pilot studies and (ii) Capacity Building Open - 11 Feb 13 March 1 180,000 Post IC No 12 for Road Safety Engineering National 19 2019 (including vulnerable groups) and Road Safety Audits; (iii) Preparation of Road Safety 5 Design Manuals/Guideline; (iv) Preparation of Road Safety Audit Manual Component 2: Institutional Strengthening, Human Capital and Project Management and monitoring Consulting Services for Procurement and Contract Management Specialist to (i) Advise TARURA on Procurement and contract management Open - 6 March 2 matters (ii) Capacity Building in 200,000 Post National IC No 4 Feb 19 2019 12 Procurement and Contracts Management (iii) Preparation of Procurement and (iv) Preparation of Contracts Management Manual/ Guideline Consulting Services for (i) Review of TARURA Strategic Plan, Organization Structure and Job Analysis, (ii) Preparation of Human Open - 18 Feb 20 March 3 Resources Plan and Training 200,000 Post National CQS No 2019 2019 12 Strategy (iii) Assessment of facilities required for efficient functioning of TARURA Consulting Services for Communications Specialist for (i) Open - 18 Feb 20 March 4 Preparing TARURA Communication 80,000 Post National CQS No 2019 2019 6 Policy and Strategy and (ii) Capacity building of TARURA Staff Consulting Services for Open - 11 Feb 13 March 5 Preparation Quality Control 40,000 Post National IC No 19 2019 6 Manuals/Guideline Consulting Services for Updating of Low Volume Design Manual Open - 18 Feb 20 March 6 60,000 Post IC No 6 and Maintenance Manual + National 2019 2019 Training Consulting Services of Financial Management Expert to (i) Open - 18 Feb 20 March 7 Prepare Financial Management 90,000 Post National IC No 2019 2019 6 Manual) –(ii) Capacity building in Financial Management and 6 Auditing Consulting Services for Open - 18 Feb 20 March 8 90,000 Post IC No 12 Transport Economist expert National 2019 2019 Consulting Services for Open - 18 Feb 20 March 9 Preparation of Project 30,000 Post National IC No 2019 2019 6 Operations Manual Consulting Services for Monitoring and Evaluation Open - 18 Feb 20 March 10 80,000 Post IC No 6 Specialist to Prepare Baseline for National 2019 2019 M&E, and Impact Evaluation Consulting Services to Update defect identification and data Open - 18 Feb 20 March 11 50,000 Post IC No 6 collection manual 2005- National 2019 2019 DROMAS Component 3: Community Engagement, Inclusion and Protection Consulting Services for Developing and Advising on Open - 11 Feb 13 March 12 90,000 Post IC No 12 Labor Based Road Maintenance National 19 2019 Model for TARURA Consulting Services for Environmental and Social safeguard specialist for (i) Preparation of Community Engagement Policy and 150,000 Open - 6 March 13. Plan (ii) capacity Building in Gender Post National IC No 4 Feb 19 2019 12 Mainstreaming Approaches including Review of Gender, Sexual Harassment, HIV-AIDS, OHS policies. 1,340.0 Total Consultancy Services 0 GRAND TOTAL (Goods +Consultancy 1,910.0 Services) 0 7 Appendix 1 Letter of Acceptance of the World Bank’s Anti-Corruption Guidelines and Sanctions Framework Date: Invitation of Bids/Proposals No.__________ To: ___________________________________________________________________________ We, along with our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not) consultants and personnel, acknowledge and agree to abide by the World Bank’s policy regarding Fraud and Corruption (corrupt, fraudulent, collusive, coercive, and obstructive practices), as set out and defined in the World Bank’s Anti-Corruption Guidelines1 in connection with the procurement and execution of the contract (in case of award), including any amendments thereto. We declare and warrant that we, along our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not), consultants and personnel, , are not subject to, and are not controlled by any entity or individual that is subject to, a temporary suspension, early temporary suspension, or debarment imposed by a member of the World Bank Group, including, inter alia, a cross-debarment imposed by the World Bank Group as agreed with other international financial institutions (including multilateral development banks), or through the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement. Further, we are not ineligible under the laws or official regulations of [Insert name of Employer as per bidding document] or pursuant to a decision of the United Nations Security Council. We confirm our understanding of the consequences of not complying with the World Bank’s Anti- Corruption Guidelines, which may include the following: a. rejection of our Proposal/Bid for award of contract; b. in the case of award, termination of the contract, without prejudice to any other remedy for breach of contract; and c. sanctions, pursuant to the Bank’s Anti-corruption Guidelines and in accordance with its prevailing sanctions policies and procedures as set forth in the Bank’s Sanctions Framework. This may include a public declaration of ineligibility, either indefinitely or for a stated period of time, (i) to be awarded or otherwise benefit from a Bank-financed contract, financially or in any other manner;2 (ii) to be a nominated3 sub-contractor, consultant, manufacturer or 1Guidelines on Preventing and Combating Fraud and Corruption in Projects Financed by International Bank for Reconstruction and Development Loans and the International Development Agency Credits and Grants, dated October 15, 2006, and revised in January 2011 and July 2016, as they may be revised from time to time. 2 For the avoidance of doubt, a sanctioned party’s ineligibility to be awarded a contract shall include, without limitation, (i) applying for pre-qualification, expressing interest in a consultancy, and bidding, either directly or as a nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider, in respect of such contract, and (ii) entering into an addendum or amendment introducing a material modification to any existing contract. 3 A nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider (different names are used depending on the particular bidding document) is one which has been: (i) included by the bidder in its pre-qualification application or bid because it brings specific and critical experience and know-how that allow the bidder to meet the qualification requirements for the particular bid; or (ii) appointed by the Borrower. 8 supplier, or service provider of an otherwise eligible firm being awarded a Bank-financed contract; and (iii) to receive the proceeds of any loan made by the Bank or otherwise to participate further in the preparation or implementation of any Bank-financed project. We understand that we may be declared ineligible as set out above upon: a. completion of World Bank Group sanctions proceedings according to its prevailing sanctions procedures; b. cross-debarment as agreed with other international financial institutions (including multilateral development banks); c. the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement; or d. temporary suspension or early temporary suspension in connection with an ongoing World Bank Group sanctions proceeding. For avoidance of doubt, the foregoing effects of ineligibility do not extend to a sanctioned firm’s or individual’s execution of its ongoing Bank-financed contracts (or its ongoing sub-agreements under such contracts) that are not the subject of a material modification, as determined by the Bank. We shall permit, and shall cause our sub-contractors, sub-consultants, agents (whether declared or not), personnel, consultants, service providers or suppliers, to permit the Bank to inspect4 all accounts, records, and other documents relating to the procurement process and/or contract execution (in the case of award), and to have them audited by auditors appointed by the Bank. We agree to preserve all accounts, records, and other documents (whether in hard copy or electronic format) related to the procurement and execution of the contract. Name of the Bidder/Consultant: Name of the person duly authorized to sign the Bid/Proposal on behalf of the Bidder/Consultant: Title of the person signing the Letter: 4 Inspections in this context are usually investigative (i.e., forensic) in nature: they involve fact-finding activities undertaken by the Bank or persons appointed by the Bank to address specific matters related to investigations/audits, such as evaluating the veracity of an allegation of possible Fraud and Corruption, through the appropriate mechanisms. Such activity includes but is not limited to accessing and examining a firm's or individual's financial records and information, and making copies thereof as relevant; accessing and examining any other documents, data, and information (whether in hard copy or electronic format) deemed relevant for the investigation/audit, and making copies thereof as relevant; interviewing staff and other relevant individuals; performing physical inspections and site visits; and obtaining third-party verification of information. 9 PROCUREMENT Tanzania : Tanzania Roads to Inclusion and Socioeconomic Opportunities (RISE) Project PLAN General Information Country: Tanzania 2022-03-08 Bank’s Approval Date of the Original Procurement Plan: 2023-06-07 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P164920 GPN Date: 2021-12-07 Project Name: Tanzania Roads to Inclusion and Socioeconomic Opportunities (RISE) Project Loan / Credit No: IDA / 68670 Tanzania National Roads Agency Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned TZ-TANROADS-271376-CW-R Request for Bids - FB / Upgrading of Iringa (Ipog Rural Roads Development a Open - Internationa Single Stage - One E Works (without pr 26,100,000.0 Under Imple 2023-09-1 IDA / 68670 Prior Request for Bids 0.00 2022-03-03 2023-03-24 2022-03-08 2023-04-04 2022-04-22 2023-05-31 2022-05-22 2022-06-26 olo) - Kilolo Road to Bitumen nd Maintenance l nvelope equalification) SP 0 mentation 9 Standard (33.61 Km) D GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TZ-TANROADS-327281-GO-R Project Management, Monito Open - Internationa Single Stage - One E Under Imple FB / Supply of Automatic Dist IDA / 68670 Post Request for Bids 600,000.00 0.00 2022-12-27 2023-01-11 2023-01-01 2023-01-11 2023-02-12 2023-03-14 2023-04-18 2023-08-16 ring and Evaluation l nvelope mentation ress Measurement Equipmen t System NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TZ-TANROADS-271375-CS-Q CBS / Consultancy Services f Rural Roads Development a Quality And Cost- Open - Internationa Under Implement or Supervision of Upgrading IDA / 68670 Post 1,000,000.00 0.00 2022-02-08 2022-10-13 2022-03-01 2023-01-15 2022-04-14 2023-04-05 2022-05-12 2022-06-11 2022-07-16 2022-08-20 2024-11-12 nd Maintenance Based Selection l ation of Iringa (Ipogolo) - Kilolo Roa d to Bitumen Standard (33.6 1 Km) in Iringa Region TZ-TANROADS-365648-CS-Q CBS / CONSULTANCY SERVIC ES FOR FEASIBILITY STUDY, E CONOMIC EVALUATION, PREL IMINARY DESIGN, PRELIMINA Rural Roads Development a Quality And Cost- Open - Internationa Under Implement IDA / 68670 Prior 1,460,539.00 0.00 2023-06-08 2023-06-07 2023-06-29 2023-06-12 2023-09-07 2023-10-05 2023-11-14 2023-12-19 2024-01-23 2026-12-12 RY ENVIRONMENTAL AND SO nd Maintenance Based Selection l ation CIAL IMPACT ASSESSMENT, D ETAILED ENGINEERING DESI GN, PREPARATION OF BIDDIN G DOCUMENTS AND SUPERVI SION OF WORKS FOR UPGRA DING OF MKATA TZ-TANROADS-358097-CS-Q CBS / Consultancy Services f or Economic Evaluation, Deta iled Engineering Design, Prep Rural Roads Development a Quality And Cost- Open - Internationa IDA / 68670 Prior 1,126,874.46 0.00 Canceled 2023-04-30 2023-05-21 2023-07-04 2023-08-01 2023-08-31 2023-10-05 2023-11-09 2026-05-27 aration of Tender Documents nd Maintenance Based Selection l and Supervision of Works for Upgrading of Mkata – Kwamsi si Regional Road (38km) to Bi tumen Standard TZ-TANROADS-365786-CS-C QS / RAPs AND ESIA FOR UPG RADING OF KWAMSISI - MKAT A ROAD (38KM) IN TANGA; N AMICHIGA-RUANGWA ROAD ( Rural Roads Development a Quality And Cost- IDA / 68670 Post Open - National 413,500.00 0.00 Under Review 2023-07-03 2023-06-27 2023-07-24 2023-09-06 2023-09-11 2023-10-11 2023-10-29 2023-12-03 2024-05-06 20.60KM) IN LINDI, AND NYIK nd Maintenance Based Selection ONGA BRIDGE – KASHELO JCt (10.48 KM); KASHELO JCT – IL OLANGULU (15KM) AND USHI ROMBO – KILIMAHEWA - NAN DA (15.57KM) IN GEITA REGI ON INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TZ-TANROADS-271372-CS-IN Institutional Strengthening a DV / Procurement of Individu Individual Consult Under Implement IDA / 68670 nd Human Capital Developm Post Open 150,000.00 0.00 2022-04-04 2022-04-21 2022-06-08 2022-06-23 2022-06-29 2022-07-27 2022-08-03 2025-07-18 al Consultants for capacity st ant Selection ation ent rengthening - Procurement S pecialist No. 2 TZ-TANROADS-271387-CS-Q BS / Procurement of Individu Project Management, Monito Individual Consult Under Implement IDA / 68670 Post Open 150,000.00 0.00 2022-04-22 2022-12-19 2022-06-17 2022-07-02 2022-08-06 2024-08-05 al Consultants for capacity st ring and Evaluation ant Selection ation rengthening - Project Accoun tant No. 1 TZ-TANROADS-288095-CS-IN DV / Procurement of Individu Project Management, Monito Individual Consult Under Implement IDA / 68670 Post Open 150,000.00 0.00 2022-04-22 2022-04-21 2022-06-17 2022-08-04 2022-07-02 2022-08-06 2024-08-05 al Consultants for capacity st ring and Evaluation ant Selection ation rengthening - Procurement S pecialist No. 1 TZ-TANROADS-326121-CS-IN Institutional Strengthening a DV / Procurement of Individu Individual Consult Under Implement IDA / 68670 nd Human Capital Developm Post Open - National 150,000.00 0.00 2022-11-22 2023-06-02 2023-01-26 2023-02-16 2023-03-23 2026-03-07 al Consultant for Capacity Str ant Selection ation ent engthening -Highway Engine er Page 1 TZ-TANROADS-326123-CS-IN Institutional Strengthening a DV / Procurement of Individu Individual Consult Under Implement IDA / 68670 nd Human Capital Developm Post Open - National 150,000.00 0.00 2022-11-22 2023-05-29 2023-01-26 2023-02-16 2023-03-23 2026-03-07 al Consultant for Capacity Str ant Selection ation ent engthening --Social Expert TZ-TANROADS-326126-CS-IN Institutional Strengthening a DV / Procurement of Individu Individual Consult Under Implement IDA / 68670 nd Human Capital Developm Post Open - National 150,000.00 0.00 2022-11-22 2023-05-28 2023-01-26 2023-02-16 2023-03-23 2026-03-07 al Consultants for Capacity St ant Selection ation ent rengthen - Environmental Ex pert TZ-TANROADS-336243-CS-IN DV / Consultancy Services for Project Management, Monito Individual Consult TANROADS’ Capacity Strengt IDA / 68670 Post Open - National 16,000.00 0.00 Canceled 2023-01-22 2023-01-19 2023-03-12 2023-03-27 2023-05-01 2024-04-30 ring and Evaluation ant Selection hening – Engagement of Proj ect Accountant No. 2 - re-adv ertisement TZ-TANROADS-288089-CS-IN DV / Procurement of Individu Project Management, Monito Individual Consult IDA / 68670 Post Open 150,000.00 0.00 Canceled 2022-04-22 2022-12-19 2022-06-17 2022-07-02 2022-08-06 2024-08-05 al Consultants for capacity st ring and Evaluation ant Selection rengthening - Project Accoun tant No. 2 TZ-TANROADS-336242-CS-IN DV / Consultancy Services for Project Management, Monito Individual Consult TANROADS’ Capacity Strengt IDA / 68670 Post Open - National 16,000.00 0.00 Canceled 2023-01-22 2023-01-19 2023-03-12 2023-04-01 2023-05-06 2024-05-05 ring and Evaluation ant Selection hening – Engagement of Proj ect Accountant No. 1 - re-adv ertisement Page 2 PROJET DE DEVELOPPEMENT LOCAL ET D’ADAPTATION AUX CHANGEMENTS CLIMATIQUES (ALBIA) ___________________________________________________________ PLAN SIMPLIFIE DE PASSATION DES MARCHES (PPM) – SEPTEMBRE 2019 Information sur le Projet : Pays : République du Tchad; Nom du Projet : Projet de Développement Local et d’Adaptation aux changements climatiques (ALBIA) Numéro d’Identification du projet : P171611 Agence d’exécution du Projet : Projet de Renforcement de la Résilience Climatique et de la Productivité Agricole Durable (ProPAD) Date du plan de passation des marchés : Septembre 2019 Période couverte par ce plan de passation des marchés : Octobre 2019- Septembre 2020 Préambule Conformément au paragraphe 5.9 du “Règlement de Passation des Marchés pour les Emprunteurs sollicitant le Financement de Projets d’Investissement (FPI)” (Juillet 2016) (“Règlement de Passation des Marchés”) le Système électronique de la Banque de suivi systématique des transactions de marchés publics (STEP) sera utilisé pour préparer, valider et actualiser les plans de passation des marchés et effectuer toutes les transactions liées à la passation des marchés du projet. Ce texte ainsi que les tableaux du plan de passation des marchés présents dans STEP constituent le plan de passation des marchés du projet. Les conditions suivantes s'appliquent à toutes les activités de passation de marchés du plan de passation de marchés. Les autres éléments du plan de passation des marchés tels que requis au paragraphe 4.4 du Règlement de passation des marchés sont énoncés dans STEP. Les Dossiers types de passation des marchés publics de la Banque devront être utilisés pour tous les contrats soumis à la concurrence internationale, ainsi que pour tous les autres contrats soumis à cette obligation telle que spécifiée dans les tableaux du plan de passation des marchés de STEP. Procédures nationales de passation des marchés : En accord avec le paragraphe 5.3 du Règlement de passation des marchés, dans le cas où la procédure de passation des marchés se fera au niveau national (telle que spécifiée dans les tableaux du plan de passation des marchés inclus de STEP), les procédures nationales de passation des marchés du pays considéré pourront être utilisées. Si l’Emprunteur utilise ses propres procédures d’appel d’offres national ouvert telles qu’énoncées dans le Décret No 2417/PR/PM/2015 du 17 Décembre 2015 portant Code des Marches Publics au Tchad, ces arrangements sont soumis aux dispositions du paragraphe 5.4 du Règlement de passation des marchés et aux conditions suivantes : 1 a) Les entreprises éligibles de tout pays peuvent concourir ; b) Le dossier d’appel d’offres/a propositions oblige le Soumissionnaire/Proposant présentant une Offre/Proposition à déposer un agreement signe, qui sera joint à tout contrat éventuel, pour confirmer qu’il applique et respecte les Directives de la Banque pour la lutte contre la corruption, y compris sans limitation, le droit de la Banque de sanctionner et les droits de la Banque pour l’inspection et l’audit ; c) Les marchés doivent comporter une répartition appropriée des attributions, risques et responsabilités ; d) Les documents de passation des marchés incluent des dispositions, convenues avec la Banque, destinées à atténuer de manière adéquate les risques et impacts environnementales, sociaux (y compris l’exploitation et les abus sexuels et la violence basée sur le genre), l’hygiène et la sécurité (« EHS ») e) La publication des informations relatives à l’attribution du marché ; f) Le droit de la Banque d’examiner le dossier et les activités de passation des marchés ; g) L’existence d’un mécanisme efficace d’examen des plaintes ; et h) La gestion et l’archivage des dossiers relatifs au Processus de passation des marchés. Lorsque l’Emprunteur utilise d’autres procédures que l’appel d’offres national ouvert, ces procédures devront être en accord avec les dispositions du paragraphe 5.5 du Règlement de passation des marchés. Crédit-bail tel que spécifié au paragraphe 5.10 du Règlement de Passation des marchés : Le crédit-bail peut être utilisé pour les contrats indiqués comme tel dans le Plan de passation des marchés : « Sans objet » Achat de biens d’occasion tel que spécifié au paragraphe 5.11du Règlement de Passation des Marchés est autorisé pour les contrats indiqués comme tel dans le Plan de passation des marchés. « Sans objet » Préférence nationale telle que spécifiée au paragraphe 5.51 du Règlement de Passation des Marchés (Fournitures et Travaux). Fournitures : ne s’applique pas Travaux ne s’applique pas Autres informations pertinentes sur la passation des marchés : « Sans Objet » Les seuils pour les méthodes de passation des marchés : Les seuils de passation des marchés se présentent comme suit au vu des conditions du marché : 2 PROCUREMENT Chad : Chad Local Development and Adaptation Project PLAN General Information Country: Chad 2020-04-14 Bank’s Approval Date of the Original Procurement Plan: 2023-06-07 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P171611 GPN Date: 2021-01-14 Project Name: Chad Local Development and Adaptation Project Loan / Credit No: IDA / V2990, IDA / D6730 Chad Local Development and Adaptation Project Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned TD-CLDAP-167605-CW-RFQ / Component 3: Project Manag Request for Quota Single Stage - One E Pending Imp 2020-12-2 IDA / V2990 Post Limited 5,300.00 0.00 2020-04-29 2020-06-24 réhabilitation de bureau du A ement, Coordination, and M tions nvelope lementation 1 L-BIA onitoring TD-CLDAP-341728-CW-RFQ / Component 1. Sustainable N Request for Quota Réfection de bureau de la Dir Request for Quota Single Stage - One E Pending Imp 2023-11-2 IDA / D6730 atural Resources Manageme Post Limited tions (Non Bank-S 27,273.00 0.00 2023-04-03 2023-05-29 ection des Affaires Juridiques tions nvelope lementation 5 nt and Protected Areas PD) et du Contentieux TD-CLDAP-341730-CW-RFQ / Component 1. Sustainable N Request for Quota Réfection de bureau de la Dir Request for Quota Single Stage - One E Pending Imp 2023-11-2 IDA / D6730 atural Resources Manageme Post Limited tions (Non Bank-S 27,273.00 0.00 2023-04-04 2023-05-30 ection des Affaires Juridiques tions nvelope lementation 6 nt and Protected Areas PD) et du Contentieux TD-CLDAP-341731-CW-RFQ / Component 3: Project Manag Request for Quota Construction d'un château d' Request for Quota Single Stage - One E Pending Imp 2023-11-2 IDA / D6730 ement, Coordination, and M Post Limited tions (Non Bank-S 72,727.00 0.00 2023-04-04 2023-05-30 eau et installation des panne tions nvelope lementation 6 onitoring PD) aux solaires pour son exploit ations TD-CLDAP-341735-CW-RFQ / Component 3: Project Manag Request for Quota Request for Quota Single Stage - One E Pending Imp 2023-11-1 Clôture en grillage du siège d IDA / D6730 ement, Coordination, and M Post Limited tions (Non Bank-S 29,091.00 0.00 2023-03-20 2023-05-15 tions nvelope lementation 1 u projet (Djedda) onitoring PD) TD-CLDAP-365275-CW-RFB / Request for Bids - Component 3: Project Manag Travaux de construction du si Single Stage - One E Small Works SPD Under Imple 2024-04-0 IDA / D6730 ement, Coordination, and M Post Request for Bids Open - National 488,909.00 0.00 2023-06-20 2023-03-20 2023-06-25 2023-06-21 2023-08-06 2023-05-10 2023-09-05 2023-10-10 ège du Projet a Djedda dans l nvelope (1 envelope proce mentation 7 onitoring a Province de BATHA ss) GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TD-CLDAP-167603-GO-RFQ / Component 3: Project Manag Request for Quota Single Stage - One E achat de consommable infor IDA / V2990 ement, Coordination, and M Post Limited 3,529.00 35,211.19 Completed 2020-04-20 2021-02-09 2020-06-15 2020-01-11 2020-12-12 2020-03-07 tions nvelope matique et bureautique onitoring TD-CLDAP-167601-GO-RFQ / Component 3: Project Manag Request for Quota Single Stage - One E Acquisition de deux groupes IDA / V2990 ement, Coordination, and M Post Limited 22,000.00 22,909.00 Completed 2020-07-01 2020-07-14 2020-08-26 2020-02-20 2020-09-08 2020-03-03 tions nvelope électrogènes onitoring TD-CLDAP-167602-GO-RFQ / Component 3: Project Manag Request for Quota Single Stage - One E IDA / V2990 Post Limited 18,000.00 18,000.00 Signed 2020-06-27 2021-03-18 2020-08-22 2020-04-23 2020-09-15 acquisition de mobilier de bu ement, Coordination, and M tions nvelope reau onitoring TD-CLDAP-167508-GO-RFQ / Component 3: Project Manag Request for Quota Single Stage - One E IDA / V2990 Post Limited 47,300.00 37,959.39 Completed 2020-07-04 2020-06-15 2020-08-29 2020-03-26 2020-10-30 2020-06-27 acquisition d'un véhicule4x4 ement, Coordination, and M tions nvelope onitoring TD-CLDAP-167599-GO-RFQ / Component 4: Contingency Request for Quota Single Stage - One E IDA / V2990 Post Limited 37,279.00 25,814.19 Completed 2020-08-25 2020-06-08 2020-10-20 2020-01-19 2021-04-18 2020-03-12 Acquisition de matériel infor Emergency Response Comp tions nvelope matique onent TD-CLDAP-264235-GO-RFQ / Component 3: Project Manag Request for Quota Single Stage - One E IDA / D6730 Post Limited 26,545.00 24,396.53 Completed 2021-12-01 2022-01-04 2022-01-11 2022-02-24 2022-01-18 2022-05-28 Acquisition des mobiliers de ement, Coordination, and M tions nvelope bureaux onitoring TD-CLDAP-264248-GO-RFQ / Component 3: Project Manag Achat des équipements infor Request for Quota Single Stage - One E IDA / D6730 ement, Coordination, and M Post Limited 19,727.00 0.00 Canceled 2021-12-22 2022-02-01 2022-02-08 matiques (Desktop, laptop, i tions nvelope onitoring mprimantes, scanner et stabi lisateurs, etc.) TD-CLDAP-264747-GO-RFQ / Component 3: Project Manag Request for Quota Single Stage - One E Acquisition de deux groupes IDA / D6730 ement, Coordination, and M Post Limited 24,546.00 22,577.00 Completed 2021-12-08 2022-01-04 2022-01-18 2022-02-25 2022-01-25 2022-03-19 tions nvelope électrogènes de 30 KVA onitoring TD-CLDAP-264253-GO-RFQ / Component 1. Sustainable N Request for Quota Single Stage - One E Acquisition d'outils de comm IDA / D6730 atural Resources Manageme Post Limited 12,800.00 0.00 Canceled 2021-12-29 2022-02-08 2022-02-15 tions nvelope unication et de matériels de nt and Protected Areas visibilité TD-CLDAP-264250-GO-RFQ / Component 3: Project Manag Fourniture et installation d'un Request for Quota Single Stage - One E IDA / D6730 ement, Coordination, and M Post Limited 40,000.00 19,747.41 Completed 2021-12-15 2022-03-28 2022-01-25 2022-06-22 2022-02-01 2022-08-13 VSAT et d'une connexion inte tions nvelope onitoring rnet au bureau de l'UCP TD-CLDAP-276096-GO-RFQ / Component 3: Project Manag Request for Quota Single Stage - One E Acquisition d'un véhicule 4x4 IDA / D6730 ement, Coordination, and M Post Limited 50,900.00 36,995.33 Completed 2022-02-06 2022-02-21 2022-03-04 2022-05-29 2022-03-11 2022-08-07 tions nvelope pour l'Unité de Gestion du Pr onitoring ojet TD-CLDAP-310087-GO-RFB / Component 3: Project Manag Single Stage - One E Under Imple Acquisition de quatre (04) vé IDA / D6730 ement, Coordination, and M Post Request for Bids Open - National 181,818.00 0.00 2022-08-24 2022-08-25 2022-08-29 2022-08-31 2022-10-10 2022-09-30 2022-11-09 2022-10-04 2022-12-14 2023-06-12 nvelope mentation hicules 4x4 au profit de l'UCP onitoring TD-CLDAP-307981-GO-RFQ / Component 3: Project Manag Achat des équipements infor Request for Quota Single Stage - One E IDA / D6730 ement, Coordination, and M Post Limited 53,637.00 44,829.23 Terminated 2022-09-19 2022-09-05 2022-11-14 2022-09-25 2023-05-13 matiques (Desktop, laptop, i tions nvelope onitoring mprimantes, scanneur etc.) TD-CLDAP-316238-GO-RFQ / Component 3: Project Manag Acquisition d'un serveur pour Request for Quota Single Stage - One E IDA / D6730 ement, Coordination, and M Post Limited 54,545.00 0.00 Completed 2022-10-05 2022-10-07 2022-11-30 2023-05-29 2022-11-27 stockage des données + acc tions nvelope onitoring essoires (Data Center) Page 1 TD-CLDAP-324844-GO-RFQ / Acquisition des fournitures d Component 3: Project Manag Request for Quota Single Stage - One E e bureau au profit du Ministè IDA / D6730 ement, Coordination, and M Post Limited 4,190.00 0.00 Completed 2022-11-19 2022-10-07 2023-01-14 2023-07-13 2022-12-03 tions nvelope re de l'Environnement de la P onitoring êche et du Développement D urable TD-CLDAP-323882-GO-RFQ / Component 1. Sustainable N Request for Quota Single Stage - One E Acquisition des mobiliers de IDA / D6730 atural Resources Manageme Post Limited 5,450.00 0.00 Completed 2022-11-12 2022-10-31 2023-01-07 2023-07-06 2022-12-04 tions nvelope bureau au profit de l'UCP nt and Protected Areas TD-CLDAP-323877-GO-RFQ / Acquisition des équipements Component 1. Sustainable N informatique et visioconféren Request for Quota Single Stage - One E IDA / D6730 atural Resources Manageme Post Limited 36,000.00 0.00 Completed 2022-11-12 2022-11-01 2023-01-07 2023-07-06 2022-12-11 ce au profit du Ministère de l' tions nvelope nt and Protected Areas Environnement, de la Pêche et du Développement Durabl e et l'UCP. TD-CLDAP-328340-GO-RFQ / Component 3: Project Manag Request for Quota Single Stage - One E Acquisitions des équipement IDA / D6730 ement, Coordination, and M Post Limited 53,637.00 0.00 Completed 2022-12-04 2022-12-12 2023-01-29 2023-07-28 2023-01-10 tions nvelope s informatiques au profit de l' onitoring UCP. TD-CLDAP-340801-GO-RFQ / Component 1. Sustainable N Request for Quota Single Stage - One E Pending Impl Acquisition des mobiliers de IDA / D6730 atural Resources Manageme Post Limited 9,091.00 0.00 2023-05-06 2023-07-01 2023-12-28 tions nvelope ementation bureau au profit de la DAJC nt and Protected Areas TD-CLDAP-340841-GO-RFQ / Acquisition des Matériels info rmatiques au profit de la Dire Component 1. Sustainable N Request for Quota Single Stage - One E ction des Affaires Juridiques IDA / D6730 atural Resources Manageme Post Limited 9,091.00 0.00 Completed 2023-05-06 2023-02-14 2023-07-01 2023-12-28 2023-05-02 tions nvelope et du Contentieux (DAJC) du nt and Protected Areas Ministère de l'Environnement , de la pêche et du Développ ement Durable. TD-CLDAP-340843-GO-RFQ / Component 1. Sustainable N Acquisition d'un véhicule 4x4 Request for Quota Single Stage - One E Pending Impl IDA / D6730 atural Resources Manageme Post Limited 45,455.00 0.00 2023-02-25 2023-04-22 2023-10-19 au profit de la Direction des tions nvelope ementation nt and Protected Areas Affaires Juridiques et du Cont entieux (DACJ). TD-CLDAP-340847-GO-RFQ / Acquisition de deux motos au Component 1. Sustainable N profit de la Direction des Affa Request for Quota Single Stage - One E Under Imple IDA / D6730 atural Resources Manageme Post Limited 3,636.00 0.00 2023-03-02 2023-02-14 2023-04-27 2023-10-24 ires Juridiques et du Contenti tions nvelope mentation nt and Protected Areas eux du Ministère de l'Environ nement, de la Pêche et du D éveloppement Durable. TD-CLDAP-340856-GO-RFQ / Component 3: Project Manag Acquisition des mobiliers de Request for Quota Single Stage - One E Pending Impl IDA / D6730 ement, Coordination, and M Post Limited 10,909.00 0.00 2023-03-01 2023-04-26 2023-10-23 bureau (deux tables de réuni tions nvelope ementation onitoring on et des chaises) au profit d e l'UCP TD-CLDAP-340860-GO-RFQ / Component 3: Project Manag Acquisition d’un kit solaire du Request for Quota Single Stage - One E Pending Impl IDA / D6730 ement, Coordination, and M Post Limited 29,091.00 0.00 2023-03-05 2023-04-30 2023-10-27 bureau de l’UCP d’ATI (fourni tions nvelope ementation onitoring tures et installations) TD-CLDAP-340863-GO-RFQ / Component 3: Project Manag Request for Quota Single Stage - One E Under Imple Acquisition des climatiseurs IDA / D6730 ement, Coordination, and M Post Limited 8,182.00 0.00 2023-03-05 2023-02-14 2023-04-30 2023-10-27 tions nvelope mentation au profit de l’UCP d’ATI onitoring TD-CLDAP-364179-GO-RFQ / Component 3: Project Manag ACQUISITION ET INSTALLATI Request for Quota Single Stage - One E Pending Impl IDA / D6730 ement, Coordination, and M Post Limited 30,545.00 0.00 2023-06-25 2023-08-20 2024-02-16 ON DE LA CONNEXION INTER tions nvelope ementation onitoring NET POUR LE BUREAU DE N' DJAMENA TD-CLDAP-369150-GO-RFQ / Acquisition de mobilier de bu reau additionnel au profit de Component 3: Project Manag Request for Quota Single Stage - One E Pending Impl la Direction des Affaires Juridi IDA / D6730 ement, Coordination, and M Post Limited 36,364.00 0.00 2023-07-25 2023-09-19 2024-03-17 tions nvelope ementation ques et du Contentieux du Mi onitoring nistère de l’Environnement, d e la Pêche et du Développem ent Durable. NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TD-CLDAP-167604-NC-DIR / Component 3: Project Manag IDA / V2990 Post Direct Selection Direct 56,000.00 38,000.00 Signed 2020-09-04 2020-12-10 2020-09-09 2020-12-10 2020-10-14 2021-03-18 2020-12-19 achat de logiciel de gestion c ement, Coordination, and M omptabilité onitoring TD-CLDAP-264746-NC-RFQ / Component 3: Project Manag Request for Quota Single Stage - One E Assurance maladie pour le p IDA / D6730 ement, Coordination, and M Post Limited 57,273.00 48,275.65 Completed 2021-12-12 2021-12-09 2022-01-10 2022-01-06 2023-01-10 2022-01-19 tions nvelope ersonnel du Projet onitoring TD-CLDAP-346359-NC-DIR / Component 3: Project Manag IDA / D6730 Post Direct Selection Direct - National 50,745.00 0.00 Signed 2023-03-20 2023-03-02 2023-03-25 2023-03-02 2023-04-29 2023-10-26 Assurance maladie du person ement, Coordination, and M nel onitoring CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TD-CLDAP-183687-CS-INDV / Component 3: Project Manag Consultant Qualifi Open - Internationa Under Implement Étude sur la planification de l IDA / D6730 ement, Coordination, and M Post 1,200,000.00 0.00 2020-08-28 2020-07-21 2020-09-18 2020-11-01 2020-12-01 2021-01-05 2021-07-04 cation Selection l ation ’utilisation des ressources en onitoring eau TD-CLDAP-185615-CS-CQS / Études techniques et réalisat ions des APD, DAO des infras Component 3: Project Manag Quality And Cost- Open - Internationa Under Implement tructures en eau potable, d'a IDA / D6730 ement, Coordination, and M Post 1,200,000.00 0.00 2020-07-31 2020-08-04 2020-08-21 2020-08-12 2020-10-04 2021-04-07 2020-11-01 2021-05-10 2020-12-01 2022-01-25 2021-01-05 2022-03-04 2021-02-09 2022-02-09 Based Selection l ation ssainissement et d'hygiène - onitoring surveillance et contrôle des t ravaux dans la zone du proje t ALBIA TD-CLDAP-185631-CS-QCBS Component 3: Project Manag / Étude sur la planification su Quality And Cost- Open - Internationa IDA / D6730 ement, Coordination, and M Post 1,200,000.00 0.00 Canceled 2020-07-31 2020-07-28 2020-08-21 2020-08-12 2020-10-04 2021-04-07 2020-11-01 2021-05-10 2020-12-01 2022-03-09 2021-01-05 2021-02-09 2022-02-09 r l'utilisation des ressources Based Selection l onitoring en eau du Projet ALBIA Page 2 TD-CLDAP-203173-CS-LCS / Recrutement d'un cabinet ch Component 3: Project Manag Least Cost Selecti Open - Internationa Under Implement argé de la réalisation de l'au IDA / D6730 ement, Coordination, and M Post 45,500.00 0.00 2020-12-15 2020-11-18 2021-01-05 2020-12-09 2021-02-18 2021-05-19 2021-03-18 2022-04-12 2021-04-17 2022-05-05 2021-05-22 2022-05-23 2021-06-26 2021-12-23 on l ation dit externe des comptes des onitoring exercices 2020 et 2021 du Pr ojet ALBIA TD-CLDAP-205312-CS-CQS / Recrutement d'un cabinet d' Component 3: Project Manag étude chargé de réaliser la m Consultant Qualifi IDA / D6730 ement, Coordination, and M Post Limited 145,500.00 0.00 Canceled 2020-11-30 2020-12-08 2020-12-14 2021-01-13 2021-02-17 2021-08-16 aquette, cadre de devis, DAO cation Selection onitoring , contrôle et supervision des travaux de construction des bureaux de l'UCP ALBIA TD-CLDAP-229055-CS-CQS / Component 3: Project Manag Réalisation de la maquette et Consultant Qualifi Under Implement IDA / D6730 ement, Coordination, and M Post Limited 85,454.00 0.00 2021-04-19 2021-05-04 2021-05-03 2021-05-23 2021-06-27 2021-12-24 DAO pour la construction du cation Selection ation onitoring Local du Projet ALBIA à Djedd a TD-CLDAP-229058-CS-CQS / Component 3: Project Manag Surveillance et contrôle de la Consultant Qualifi IDA / D6730 ement, Coordination, and M Post Limited 36,363.00 0.00 Canceled 2021-04-19 2021-05-04 2021-05-03 2021-05-18 2021-06-22 2021-12-19 Construction du Local du Proj cation Selection onitoring et ALBIA à Djedda TD-CLDAP-240983-CS-CQS / RECRUTEMENT DE CONSULT Component 1. Sustainable N Consultant Qualifi ANTS POUR FAIRE L’ETAT DE IDA / D6730 atural Resources Manageme Post Open - National 45,527.00 37,689.69 Signed 2021-07-05 2021-12-29 2021-07-26 2022-02-01 2021-09-08 2022-03-28 2021-10-08 2022-05-05 2021-11-12 2022-05-10 2022-05-11 cation Selection S LIEUX DU CORPUS JURIDIQ nt and Protected Areas UE DE L’ENVIRONNEMENT TD-CLDAP-240987-CS-CQS / Recrutement des ONG pour l’ Component 1. Sustainable N Consultant Qualifi appui à la participation citoy IDA / D6730 atural Resources Manageme Post Open - National 227,272.00 0.00 Canceled 2021-07-05 2021-06-29 2021-07-26 2021-09-08 2021-10-08 2021-11-12 2022-05-11 cation Selection enne (Information, communic nt and Protected Areas ation et sensibilisation de pro ximité) TD-CLDAP-244738-CS-CQS / Recrutement d'un consultant Component 1. Sustainable N Consultant Qualifi pour le Renforcement de cap IDA / D6730 atural Resources Manageme Post Limited 54,545.00 45,165.63 Completed 2021-07-26 2021-08-02 2021-08-09 2022-03-14 2021-09-01 2022-06-09 2021-10-06 2022-06-25 2022-04-04 2022-11-26 cation Selection acité, l'information et la sensi nt and Protected Areas bilisation à la protection de l' Environnement TD-CLDAP-246566-CS-CQS / Recrutement des ONG pour l’ Component 1. Sustainable N appui à la participation citoy Consultant Qualifi Under Implement IDA / D6730 atural Resources Manageme Post Limited 45,455.00 0.00 2021-08-02 2021-08-02 2021-08-16 2021-09-15 2021-10-20 2022-04-18 enne (Information, communic cation Selection ation nt and Protected Areas ation et sensibilisation de pro ximité) dans la zone de Djed da TD-CLDAP-246567-CS-CQS / Recrutement des ONG pour l’ Component 1. Sustainable N appui à la participation citoy Consultant Qualifi Under Implement IDA / D6730 atural Resources Manageme Post Limited 45,455.00 0.00 2021-08-02 2021-08-02 2021-08-16 2021-09-15 2021-10-20 2022-04-18 enne (Information, communic cation Selection ation nt and Protected Areas ation et sensibilisation de pro ximité) dans la zone de Koub a Olanga TD-CLDAP-246568-CS-CQS / Recrutement des ONG pour l’ Component 1. Sustainable N appui à la participation citoy Consultant Qualifi Under Implement IDA / D6730 atural Resources Manageme Post Limited 45,455.00 0.00 2021-08-02 2021-08-02 2021-08-16 2021-09-15 2021-10-20 2022-04-18 enne (Information, communic cation Selection ation nt and Protected Areas ation et sensibilisation de pro ximité) dans la zone de Salal TD-CLDAP-246569-CS-CQS / Recrutement des ONG pour l’ Component 1. Sustainable N appui à la participation citoy Consultant Qualifi Under Implement IDA / D6730 atural Resources Manageme Post Limited 45,455.00 0.00 2021-08-02 2021-08-02 2021-08-16 2021-09-15 2021-10-20 2022-04-18 enne (Information, communic cation Selection ation nt and Protected Areas ation et sensibilisation de pro ximité) dans la zone de Arad a TD-CLDAP-246570-CS-CQS / Recrutement des ONG pour l’ Component 1. Sustainable N appui à la participation citoy Consultant Qualifi Under Implement IDA / D6730 atural Resources Manageme Post Limited 45,455.00 0.00 2021-08-02 2021-08-02 2021-08-16 2021-09-15 2021-10-20 2022-04-18 enne (Information, communic cation Selection ation nt and Protected Areas ation et sensibilisation de pro ximité) dans la zone de Kalait TD-CLDAP-296569-CS-QCBS / Recrutement d'une firme po Component 2. Promoting Div Quality And Cost- Open - Internationa Under Implement ur la réalisation d'une étude IDA / D6730 ersified, Resilient, Sustainabl Prior 1,200,000.00 0.00 2022-06-06 2022-08-15 2022-06-20 2022-10-04 2022-07-25 2022-11-17 2022-09-05 2023-01-20 2022-10-05 2022-11-09 2022-12-23 2024-12-22 Based Selection l ation sur la planification de l'utilisa e Livelihoods tion des ressources en eau TD-CLDAP-313463-CS-CQS / Réalisation d’une Notice d’Im Component 3: Project Manag Consultant Qualifi pact Environnemental et Soci IDA / D6730 ement, Coordination, and M Post Limited 14,546.00 0.00 Completed 2022-09-15 2022-09-08 2022-09-29 2022-10-04 2022-10-29 2022-11-07 2022-12-03 2023-06-01 2023-03-27 cation Selection al relative à la construction d onitoring u siège du projet ALBIA à Dje daa TD-CLDAP-241049-CS-CQS / Component 1. Sustainable N Recrutement d'une ONG pour Quality And Cost- IDA / D6730 atural Resources Manageme Post Open - National 390,909.00 0.00 Canceled 2021-06-30 2021-08-02 2021-07-21 2021-09-03 2021-10-01 2021-10-31 2021-12-05 2022-01-09 2023-01-09 la structuration communauta Based Selection nt and Protected Areas ire et renforcement des capa cités TD-CLDAP-318067-CS-QCBS / Recrutement d’une organis ation pour soutenir la mise e n œuvre des activités de stru Component 1. Sustainable N Quality And Cost- Open - Internationa Under Implement cturation et de renforcement IDA / D6730 atural Resources Manageme Post 390,909.00 0.00 2022-10-24 2022-10-11 2022-11-14 2022-10-17 2022-12-28 2023-01-25 2023-02-24 2023-03-31 2023-05-05 2024-05-04 Based Selection l ation des capacités dans la zone d’ nt and Protected Areas intervention du Projet de Dév eloppement Local et d’Adapt ation aux Changements Clim atique (ALBIÄ). TD-CLDAP-336701-CS-CQS / Component 3: Project Manag Recrutement d’un cabinet po Consultant Qualifi Under Implement IDA / D6730 ement, Coordination, and M Post Limited 14,545.00 0.00 2023-02-15 2023-02-04 2023-03-01 2023-03-31 2023-05-05 2023-11-01 ur la création d’un Datacente cation Selection ation onitoring r ainsi que la conception du s ite internet . TD-CLDAP-341641-CS-CQS / Recrutement d’un bureau d’é Component 1. Sustainable N Consultant Qualifi Under Implement tude pour l’appui à la révisio IDA / D6730 atural Resources Manageme Post Limited 61,818.00 0.00 2023-03-02 2023-02-15 2023-03-16 2023-04-15 2023-05-20 2023-11-16 cation Selection ation n de la loi 14/98 intégrant les nt and Protected Areas recommandations de l’étude sur le corpus juridique Page 3 TD-CLDAP-341659-CS-CQS / Recrutement d’un bureau d’é Component 1. Sustainable N tude pour l’élaboration du dé Consultant Qualifi Under Implement IDA / D6730 atural Resources Manageme Post Limited 89,091.00 0.00 2023-08-07 2023-02-15 2023-08-21 2023-09-20 2023-10-25 2024-04-22 cret d’application de la loi 14 cation Selection ation nt and Protected Areas /2008 modifiée portant régim e de forêts, de la faune et de s ressources halieutiques TD-CLDAP-341677-CS-CQS / Recrutement de cabinet char gé de la mise à jour du décre Component 1. Sustainable N t 2014 portant promotion de Consultant Qualifi Under Implement IDA / D6730 atural Resources Manageme Post Limited 61,818.00 0.00 2023-03-20 2023-02-14 2023-04-03 2023-05-03 2023-06-07 2023-12-04 l’éducation environnemental cation Selection ation nt and Protected Areas e et de l'élaboration du text e d’application mettant en pl ace le Haut Comité National pour l’Environnement TD-CLDAP-341683-CS-CQS / Recrutement d'un cabinet ch argé d'élaborer les modules Component 1. Sustainable N Consultant Qualifi Under Implement de formation et la mise en œ IDA / D6730 atural Resources Manageme Post Limited 90,000.00 0.00 2023-03-20 2023-02-14 2023-04-03 2023-05-03 2023-06-07 2023-12-04 cation Selection ation uvre du plan de renforcemen nt and Protected Areas t de capacité à la protection de la faune et de la flore au T chad TD-CLDAP-341690-CS-CQS / Recrutement d’un cabinet po Component 1. Sustainable N Consultant Qualifi Pending Impleme ur faire la Notice d’Impacte E IDA / D6730 atural Resources Manageme Post Limited 9,091.00 0.00 2023-03-20 2023-04-03 2023-05-03 2023-06-07 2023-12-04 cation Selection ntation nvironnementale et sociale d nt and Protected Areas u bâtiment de la DAJC TD-CLDAP-341692-CS-CQS / Recrutement d’un cabinet ch argés de la conception et pro Component 1. Sustainable N duction de documents didact Consultant Qualifi Pending Impleme IDA / D6730 atural Resources Manageme Post Limited 72,727.00 0.00 2023-03-30 2023-04-13 2023-05-13 2023-06-17 2023-12-14 iques et de manuels à l’inten cation Selection ntation nt and Protected Areas tion des acteurs cibles clefs (l es communautés de la ZIP, le s écoles de la ZIP, la Justice, l a DAJC, la DFAP, la GFF TD-CLDAP-341699-CS-CQS / Recrutement d’un consultant individuel pour Compléter et Component 1. Sustainable N vérifier le suivi des risques d Consultant Qualifi Pending Impleme IDA / D6730 atural Resources Manageme Post Limited 12,727.00 0.00 2023-04-20 2023-05-04 2023-06-03 2023-07-08 2024-01-04 e violences basées sur le gen cation Selection ntation nt and Protected Areas re dans le cadre du Projet et faire la cartographie des pres tataires de services VBG à pr oximité des sous projets TD-CLDAP-341709-CS-CQS / Recrutement d’un consultant individuel en vue de renforce Component 1. Sustainable N Consultant Qualifi Under Implement r les capacités des parties pr IDA / D6730 atural Resources Manageme Post Limited 10,909.00 0.00 2023-08-15 2023-03-14 2023-08-29 2023-09-28 2023-11-02 2024-04-30 cation Selection ation enantes sur les Violences Se nt and Protected Areas xuelles Basée sur le Genre (V SBG) et Mécanisme de gestio n des VSBG/Genre Leadershi p TD-CLDAP-341716-CS-CQS / Recrutement d’un cabinet en vue de conduire les études e Component 1. Sustainable N Consultant Qualifi Pending Impleme nvironnementales et sociales IDA / D6730 atural Resources Manageme Post Limited 81,818.00 0.00 2023-06-20 2023-07-04 2023-08-03 2023-09-07 2024-03-05 cation Selection ntation relative aux Adductions d'Ea nt and Protected Areas u Potable dans le cinq Hotsp ots (Kouba-Oulanga, Salal et Djadda) TD-CLDAP-341719-CS-CQS / Recrutement d’un cabinet en Component 1. Sustainable N vue de conduire les études e Consultant Qualifi Pending Impleme IDA / D6730 atural Resources Manageme Post Limited 45,545.00 0.00 2023-06-25 2023-07-09 2023-08-08 2023-09-12 2024-03-10 nvironnementales et sociales cation Selection ntation nt and Protected Areas relative aux Adductions d'Ea u Potable dans le cinq Hotsp ots (Kalait et Arada) TD-CLDAP-355954-CS-CQS / Recrutement d'un bureau de Component 3: Project Manag Consultant Qualifi Pending Impleme surveillance et de contrôle p IDA / D6730 ement, Coordination, and M Post Limited 54,545.00 0.00 2023-06-15 2023-06-29 2023-07-14 2023-08-18 2024-02-14 cation Selection ntation our la construction du siège onitoring du Projet ALBIA a Djedda dan s la Province du Batha. INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TD-CLDAP-167606-CS-INDV / Component 3: Project Manag Individual Consult étude de référence sur la situ IDA / V2990 ement, Coordination, and M Post Limited 28,000.00 27,075.07 Signed 2020-05-14 2020-07-09 2020-05-19 2020-12-01 2020-06-09 2021-03-18 2020-07-14 2021-03-19 2021-01-10 ant Selection ation de base en agriculture onitoring TD-CLDAP-167607-CS-INDV / Component 3: Project Manag étude de référence sur l'iden Individual Consult IDA / V2990 ement, Coordination, and M Post Limited 52,700.00 51,545.00 Signed 2020-05-22 2020-07-09 2020-05-27 2021-03-01 2020-06-17 2021-03-08 2020-07-22 2020-12-24 2021-01-18 tification et la faisabilité tech ant Selection onitoring nique des ouvrages en eau p otable TD-CLDAP-167617-CS-INDV / Component 2. Promoting Div Etude de reference sur la situ Individual Consult IDA / V2990 ersified, Resilient, Sustainabl Post Limited 36,000.00 34,545.00 Signed 2020-04-05 2020-07-08 2020-04-10 2021-03-01 2020-05-01 2021-03-08 2020-06-05 2019-12-24 2020-12-02 ation de base sur le développ ant Selection e Livelihoods ement local et l'engagement des citoyens TD-CLDAP-167632-CS-INDV / recrutement d'un assistant e n passation des marchés. il est chargé d'assister l'spécia Component 3: Project Manag Individual Consult liste en passation des marc IDA / V2990 ement, Coordination, and M Post Open 14,118.00 0.00 Canceled 2020-04-20 2020-07-08 2020-06-08 2020-06-29 2020-08-03 2022-08-03 ant Selection hés des travaux, des fournitu onitoring res et des prestations intellec tuelles. il doit tout implément er dans STEP et suivre cha que activités. TD-CLDAP-167635-CS-INDV / Component 3: Project Manag Individual Consult recrutement d'un spécialiste IDA / V2990 ement, Coordination, and M Post Open 42,360.00 39,272.00 Signed 2020-04-13 2020-07-08 2020-06-01 2020-10-05 2020-06-22 2020-10-12 2020-07-27 2020-09-16 2022-07-27 ant Selection en passation des marchés onitoring TD-CLDAP-167636-CS-INDV / Component 2. Promoting Div Individual Consult recrutement d'un responsabl IDA / V2990 ersified, Resilient, Sustainabl Post Open 42,360.00 39,272.00 Signed 2020-04-13 2020-07-08 2020-06-01 2020-09-14 2020-06-22 2020-09-14 2020-07-21 2020-09-18 2022-07-21 ant Selection e administratif et financier e Livelihoods Page 4 TD-CLDAP-167637-CS-INDV / Component 2. Promoting Div Individual Consult recrutement d'un auditeur in IDA / V2990 ersified, Resilient, Sustainabl Post Open 40,584.00 0.00 Canceled 2020-04-13 2020-07-07 2020-06-01 2020-06-22 2020-07-27 2022-07-27 ant Selection terne e Livelihoods TD-CLDAP-167638-CS-INDV / Component 3: Project Manag Individual Consult recrutement d'un spécialiste IDA / V2990 ement, Coordination, and M Post Open 42,360.00 39,272.00 Signed 2020-04-13 2020-07-08 2020-06-01 2020-09-08 2020-06-22 2020-09-15 2020-07-27 2020-09-18 2022-07-27 ant Selection en suivi et évaluation onitoring TD-CLDAP-167649-CS-INDV / Le recrutement d'un coordon nateur en vue de la coordinat Component 3: Project Manag ion des activités fiduciaires e Individual Consult IDA / V2990 ement, Coordination, and M Post Open 52,944.00 52,363.00 Signed 2020-04-13 2020-07-08 2020-06-01 2020-09-14 2020-06-22 2020-09-15 2020-07-27 2020-09-18 2022-07-17 t techniques du projet, à ce ti ant Selection onitoring tre il est aussi d'assurer les r elations entre le bailleur et le projet d'une part et les relati ons entre le projet le ministèr e du tutel TD-CLDAP-167659-CS-INDV / Component 3: Project Manag Individual Consult Recrutement d'un spécialiste IDA / V2990 ement, Coordination, and M Post Open 42,360.00 39,272.00 Signed 2020-04-13 2020-07-08 2020-06-01 2020-09-07 2020-06-22 2020-09-15 2020-07-27 2020-09-18 2022-07-27 ant Selection en environnement onitoring TD-CLDAP-167660-CS-INDV / Component 3: Project Manag Individual Consult Recrutement d'un spécialiste IDA / V2990 ement, Coordination, and M Post Open 42,360.00 39,272.00 Signed 2020-04-13 2020-07-08 2020-06-01 2021-03-12 2020-06-22 2020-09-11 2020-07-27 2020-09-18 2022-07-27 ant Selection Développement social et gen onitoring re TD-CLDAP-168017-CS-INDV / Component 3: Project Manag Recrutement d'un specialiste Individual Consult IDA / V2990 ement, Coordination, and M Post Open 42,360.00 39,272.00 Signed 2020-04-13 2020-07-08 2020-06-01 2020-09-10 2020-06-22 2020-09-11 2020-07-27 2020-09-18 2021-01-23 en conservation dans le cadr ant Selection onitoring e de la gestion du projet TD-CLDAP-168018-CS-INDV / Component 3: Project Manag Individual Consult Recrutement d'un spécialiste IDA / V2990 ement, Coordination, and M Post Open 42,360.00 0.00 Canceled 2020-04-13 2020-07-08 2020-06-01 2020-06-22 2020-07-27 2022-07-27 ant Selection en eau dans le cadre du proj onitoring et TD-CLDAP-168019-CS-INDV / Component 3: Project Manag Recrutement d'un spécialiste Individual Consult IDA / V2990 ement, Coordination, and M Post Open 28,224.00 0.00 Under Review 2020-04-13 2020-07-07 2020-06-01 2020-06-22 2020-07-27 2022-07-27 chargé de communication et ant Selection onitoring de l'engagement citoyen TD-CLDAP-168021-CS-INDV / Component 3: Project Manag Individual Consult Recrutement d'un comptable IDA / V2990 ement, Coordination, and M Post Open 28,224.00 28,363.00 Signed 2020-04-13 2020-07-08 2020-06-01 2020-09-07 2020-06-22 2020-09-07 2020-07-27 2020-06-18 2022-07-27 ant Selection dans le cadre du projet onitoring TD-CLDAP-167616-CS-INDV / Component 3: Project Manag Individual Consult Etude de référence sur la bas IDA / V2990 ement, Coordination, and M Post Open 19,500.00 29,045.00 Signed 2020-06-25 2020-07-08 2020-08-13 2021-03-08 2020-09-03 2021-03-15 2020-10-08 2020-12-24 2021-04-06 ant Selection e sur le changement climatiq onitoring ue TD-CLDAP-167609-CS-INDV / Etude de référence sur la situ ation de base pour les besoi ns de renforcements des ca Component 3: Project Manag Individual Consult pacités. le consultant doit év IDA / V2990 ement, Coordination, and M Post Open 38,000.00 0.00 Under Review 2020-06-25 2020-07-09 2020-08-13 2020-09-03 2020-10-08 2020-11-06 ant Selection aluer les besoins en renforce onitoring ment des capacités par com posante et par personne a fin de répondre de manière exhaustif aux besoins TD-CLDAP-167619-CS-INDV / Component 3: Project Manag étude complémentaire d'élab Individual Consult IDA / V2990 ement, Coordination, and M Post Limited 27,000.00 27,909.00 Signed 2020-07-07 2020-07-07 2020-07-12 2021-03-01 2020-08-02 2021-03-15 2020-08-25 2019-12-20 2020-08-27 oration de cartographie des r ant Selection onitoring essource en eau de surface TD-CLDAP-167613-CS-INDV / Component 3: Project Manag Individual Consult Under Implement Etude de référence sur la situ IDA / V2990 ement, Coordination, and M Post Limited 33,000.00 0.00 2020-07-07 2020-07-08 2020-07-12 2020-08-02 2020-09-06 2020-10-02 ant Selection ation ation de base écosystémique onitoring TD-CLDAP-167631-CS-INDV / Component 3: Project Manag Individual Consult IDA / V2990 Post Open 10,588.00 0.00 Canceled 2020-06-27 2020-07-08 2020-08-15 2020-09-05 2020-10-10 2021-04-08 recrutement d'un assistant c ement, Coordination, and M ant Selection omptable onitoring TD-CLDAP-167618-CS-INDV / Component 3: Project Manag Individual Consult Under Implement Etude de reference sur la situ IDA / V2990 ement, Coordination, and M Post Limited 30,000.00 0.00 2020-06-26 2020-07-08 2020-07-02 2020-07-23 2020-08-27 2021-02-23 ant Selection ation ation de base sur le genre onitoring TD-CLDAP-167630-CS-INDV / Component 3: Project Manag recrutement d'un consultant Individual Consult Under Implement IDA / V2990 ement, Coordination, and M Post Limited 9,559.00 0.00 2020-06-26 2020-07-07 2020-07-01 2020-07-22 2020-08-26 2020-09-24 pour l'élaboration d'un plan d ant Selection ation onitoring e communication TD-CLDAP-167621-CS-INDV / Component 3: Project Manag Individual Consult IDA / V2990 Post Limited 32,500.00 32,177.75 Signed 2020-06-29 2020-07-07 2020-07-04 2020-08-13 2020-07-25 2020-08-13 2020-08-29 2021-03-19 2020-10-15 recrutement du cartogaphe ement, Coordination, and M ant Selection onitoring TD-CLDAP-167622-CS-INDV / Component 2. Promoting Div recrutement d'un consultant Individual Consult Under Implement IDA / V2990 ersified, Resilient, Sustainabl Post Limited 54,500.00 0.00 2020-07-15 2020-07-08 2020-07-20 2020-08-10 2020-09-14 2021-03-13 principal en charge de la coo ant Selection ation e Livelihoods rdination des études de référ ences TD-CLDAP-167614-CS-INDV / Component 3: Project Manag étude de référence sur la situ Individual Consult Pending Impleme IDA / V2990 ement, Coordination, and M Post Limited 53,500.00 0.00 2020-07-24 2020-07-29 2020-08-19 2020-09-23 2020-11-02 ation de base sur les change ant Selection ntation onitoring ments climatiques TD-CLDAP-168022-CS-CDS / Component 3: Project Manag Pending Impleme Convention avec le PROPAD IDA / V2990 ement, Coordination, and M Post Direct Selection Direct 20,000.00 0.00 2020-07-29 2020-08-08 2020-10-12 2021-04-10 ntation pour la gestion PPA onitoring TD-CLDAP-167610-CS-INDV / Component 3: Project Manag Individual Consult Pending Impleme Etude de référence sur la situ IDA / V2990 ement, Coordination, and M Post Open 25,000.00 0.00 2020-08-18 2020-10-06 2020-10-27 2020-12-01 2021-05-30 ant Selection ntation ation de base sur la biodivers onitoring ité TD-CLDAP-167624-CS-INDV / Component 3: Project Manag recrutement d'un consultant Individual Consult IDA / V2990 ement, Coordination, and M Post Open 53,500.00 0.00 Canceled 2020-09-03 2020-07-09 2020-10-22 2020-11-12 2020-12-17 2021-06-15 chargé de coordonner les act ant Selection onitoring ivités environnementales et s ociales TD-CLDAP-167626-CS-INDV / Component 3: Project Manag recrutement d'un consultant Individual Consult Pending Impleme IDA / V2990 ement, Coordination, and M Post Open 53,500.00 0.00 2020-07-24 2020-09-11 2020-10-02 2020-11-06 2021-05-05 en environnement pour l'élab ant Selection ntation onitoring oration du cadre de gestion e t sociale Page 5 TD-CLDAP-167620-CS-INDV / Component 3: Project Manag Etude complémentaire d'élab Individual Consult Pending Impleme IDA / V2990 ement, Coordination, and M Post Limited 28,000.00 0.00 2020-08-18 2020-08-23 2020-09-13 2020-10-18 2020-11-01 oration de cartographie des r ant Selection ntation onitoring essources en eau de surface TD-CLDAP-167612-CS-INDV / Component 3: Project Manag Individual Consult Under Implement Etude de référence sur la situ IDA / V2990 ement, Coordination, and M Post Open 15,500.00 0.00 2020-07-05 2020-07-08 2020-08-23 2020-09-13 2020-10-18 2021-04-16 ant Selection ation ation de base sur la biodivers onitoring ité TD-CLDAP-167608-CS-INDV / Component 3: Project Manag Individual Consult Etude de référence sur la situ IDA / V2990 ement, Coordination, and M Post Open 28,000.00 27,247.00 Completed 2020-09-03 2020-07-09 2020-10-22 2021-03-02 2020-11-12 2021-03-08 2020-12-17 2020-01-04 2021-06-15 2022-04-30 ant Selection ation de base sur le foncier onitoring TD-CLDAP-167628-CS-INDV / Component 3: Project Manag recrutement d'un consultant Individual Consult IDA / V2990 ement, Coordination, and M Post Open 12,000.00 0.00 Canceled 2020-08-19 2020-06-20 2020-10-07 2020-10-28 2020-12-02 2021-05-31 pour l'élaboration du manuel ant Selection onitoring de suivi et évaluation TD-CLDAP-167627-CS-INDV / Component 3: Project Manag recrutement d'un consultant Individual Consult IDA / V2990 ement, Coordination, and M Post Open 38,000.00 0.00 Canceled 2020-07-23 2020-06-20 2020-09-10 2020-10-01 2020-11-05 2021-05-04 pour l'élaboration du manuel ant Selection onitoring s d'exécution du projet TD-CLDAP-183190-CS-INDV / recrutement d'un consultant en charge de l'élaboration du manuel d’exécution, de suivi Component 3: Project Manag Individual Consult et évaluation et l'Appui au gr IDA / D6730 ement, Coordination, and M Post Open 50,000.00 0.00 Canceled 2020-08-15 2020-10-03 2020-10-24 2020-11-28 2021-05-27 ant Selection oupe de travail interministéri onitoring el pour l'adaptation du manu el de procédures administrati ves , financières et comptabl es harmonise . TD-CLDAP-183214-CS-INDV / Component 3: Project Manag recrutement d'un consultant Individual Consult IDA / D6730 ement, Coordination, and M Post Limited 38,000.00 40,000.00 Signed 2020-08-12 2020-07-09 2020-08-17 2020-11-01 2020-09-07 2020-11-19 2020-10-12 2021-03-19 2021-04-10 chargé de l'élaboration de m ant Selection onitoring anuel d’exécution du projet TD-CLDAP-183218-CS-INDV / recrutement d'un consultant assistant chargé d'adapter le Component 3: Project Manag Individual Consult Under Implement manuel de procédures , admi IDA / V2990 ement, Coordination, and M Post Limited 12,000.00 0.00 2020-08-14 2020-07-09 2020-08-19 2020-09-09 2020-10-14 2021-04-12 ant Selection ation nistratives, financières et co onitoring mptables harmonisés de la Banque Mondiale au context e d'ALBIA. TD-CLDAP-183230-CS-INDV / Component 3: Project Manag Individual Consult recrutement d'un assistant a IDA / V2990 ement, Coordination, and M Post Open 21,168.00 15,272.00 Signed 2020-09-18 2020-07-09 2020-11-06 2020-10-05 2020-11-27 2020-10-14 2021-01-01 2020-10-16 2021-06-30 ant Selection dministratif et comptable onitoring TD-CLDAP-183693-CS-INDV / Études techniques et réalisat ion APD et du dossier d’appel Component 3: Project Manag d’offres (DAO) des infrastruct Individual Consult IDA / D6730 ement, Coordination, and M Prior Open 1,200,000.00 0.00 Canceled 2020-08-28 2020-07-17 2020-10-16 2020-11-06 2020-12-11 2021-06-09 ures d’Alimentation en Eau P ant Selection onitoring otable, d’Assainissement et d ’Hygiène - surveillance et co ntrôle des travaux dans la zo ne du projet ALBIA au Tchad TD-CLDAP-168020-CS-INDV / Component 3: Project Manag Individual Consult Recrutement d'un assistant A IDA / V2990 ement, Coordination, and M Post Open 28,224.00 0.00 Canceled 2020-04-13 2020-07-08 2020-06-01 2020-06-22 2020-07-27 2022-07-27 ant Selection dministratif dans le cadre du onitoring projet TD-CLDAP-206474-CS-CDS / Component 1. Sustainable N Convention MOD SCF pour la IDA / D6730 atural Resources Manageme Post Direct Selection Direct 669,544.00 600,000.00 Signed 2020-11-25 2020-12-02 2020-12-05 2021-02-08 2021-02-08 2021-04-21 2021-08-07 gestion de la sous-composan nt and Protected Areas te 1.1. TD-CLDAP-206477-CS-CDS / Component 2. Promoting Div Convention MOD SOSSIF pou IDA / D6730 ersified, Resilient, Sustainabl Post Direct Selection Direct 1,762,500.00 1,762,500.00 Signed 2020-11-25 2021-02-12 2020-12-05 2021-02-18 2021-02-08 2021-04-21 2021-08-07 r la gestion de la sous-compo e Livelihoods sante 2.2. TD-CLDAP-267864-CS-CDS / Component 3: Project Manag Sélection d'une firme pour le IDA / D6730 ement, Coordination, and M Post Direct Selection Direct 4,330.00 3,995.70 Completed 2021-12-10 2021-12-21 2021-12-12 2022-01-10 2021-12-18 2022-01-28 2022-01-02 2022-06-07 recrutement du Spécialiste e onitoring n Passation des Marchés du P rojet ALBIA TD-CLDAP-310063-CS-INDV / Réalisation d’une Notice d’Im Component 3: Project Manag Individual Consult pact Environnemental et Soci IDA / D6730 ement, Coordination, and M Post Limited 14,500.00 0.00 Canceled 2022-08-17 2022-08-22 2022-08-22 2022-09-12 2022-10-17 2023-04-15 ant Selection al relative à la construction d onitoring u siège du projet ALBIA à Dje daa TD-CLDAP-316227-CS-INDV / Recrutement d'un consultant pour la Configuration du Dat Component 3: Project Manag Individual Consult a center (rédaction du manu IDA / D6730 ement, Coordination, and M Post Limited 14,545.00 0.00 Canceled 2022-11-14 2022-12-08 2022-11-19 2022-12-10 2023-01-14 2023-07-13 ant Selection el d’utilisation, spécification t onitoring echniques des équipements et conception de data center ) conception du site internet TD-CLDAP-349917-CS-CDS / Component 3: Project Manag Recrutement d'un auditeur e Direct - Internation IDA / D6730 ement, Coordination, and M Post Direct Selection 18,182.00 0.00 Signed 2023-04-03 2023-03-23 2023-04-13 2023-04-03 2023-06-17 2023-12-14 xterne pour l'audit annuel de al onitoring s comptes et états financiers de l'exercice 2022 Page 6 PROCUREMENT PLAN (Textual Part) Project information: Burkina Faso-Solar Energy and Access Project- P166785 Project Implementation agency: Ministry of Energy, Mines and Quarries Date of the Procurement Plan: March 21, 2023 Period covered by this Procurement Plan: April 2023-December 2023 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in Law No. 039/2016/AN of 2 December 2016 "on the General regulation of public procurement" and its implementing texts including Decree 2017-0049/PRES/PM/MINEFID of 1 February 2017 regulating public procurement and delegation of public services, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: “Not Applicable” Procurement of Second-Hand Goods as specified under paragraph 5.11 of the Procurement Regulations “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: is not applicable; Works: is not applicable. Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations is Applicable. Other Relevant Procurement Information. Depending on the evolution of the security situation in the country, the PPSD could be updated for efficient market procurement management. PROCUREMENT Burkina Faso : Solar Energy and Access Project PLAN General Information Country: Burkina Faso 2023-03-21 Bank’s Approval Date of the Original Procurement Plan: 2023-06-07 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P166785 GPN Date: 2023-03-08 Project Name: Solar Energy and Access Project Loan / Credit No: TF / B5744, TF / B5738 Coordination Unit of Solar Energy and Access Project Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BF-UGP/SOLEER -352978-GO -RFQ / Acquisition de matérie Component 3: Private Sector Request for Quota Single Stage - One E Pending Impl l et équipement de Visio conf TF / B5744 Mobilization for Large-Scale Post Limited 29,412.00 0.00 2023-04-25 2023-06-20 2023-12-17 tions nvelope ementation érence et vidéo surveillance Solar au profit de l'UGP SOLEER BF-UGP/SOLEER -352985-GO Component 3: Private Sector Request for Quota Single Stage - One E Pending Impl -RFQ / Acquisition de matérie TF / B5744 Mobilization for Large-Scale Post Limited 9,191.00 0.00 2023-04-25 2023-06-20 2023-12-17 tions nvelope ementation l électroménager et équipem Solar ents divers BF-UGP/SOLEER -352990-GO -RFQ / Acquisition de fournitu Component 3: Private Sector Request for Quota Single Stage - One E Pending Impl res de bureau, de consomma TF / B5744 Mobilization for Large-Scale Post Limited 11,029.00 0.00 2023-04-24 2023-06-19 2023-12-16 tions nvelope ementation bles informatiques et de prod Solar uits d'entretien au profit de l' UGP SOLEER BF-UGP/SOLEER -352995-GO Component 3: Private Sector Request for Quota Single Stage - One E Pending Impl -RFQ / Acquisition de matérie TF / B5744 Mobilization for Large-Scale Post Limited 386,029.00 0.00 2023-04-23 2023-06-18 2023-12-15 tions nvelope ementation l roulant au profit de l'UGP S Solar OLEER BF-UGP/SOLEER -352997-GO Component 3: Private Sector -RFQ / Acquisition de matérie Request for Quota Single Stage - One E Pending Impl TF / B5744 Mobilization for Large-Scale Post Limited 58,824.00 0.00 2023-04-23 2023-06-18 2023-12-15 l et mobilier de bureau au pr tions nvelope ementation Solar ofit de l'UGP SOLEER BF-UGP/SOLEER -353004-GO Component 3: Private Sector -RFQ / Acquisition de matérie Request for Quota Single Stage - One E Pending Impl TF / B5744 Mobilization for Large-Scale Post Limited 91,912.00 0.00 2023-05-22 2023-07-17 2024-01-13 l et équipement informatique tions nvelope ementation Solar au profit de l'UGP SOLEER NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BF-UGP/SOLEER -347820-NC -RFQ / Acquisition, installatio Component 3: Private Sector Request for Quota Single Stage - One E Under Imple n, formation des utilisateurs TF / B5744 Mobilization for Large-Scale Post Limited 64,338.00 0.00 2023-03-25 2023-03-31 2023-05-20 2023-11-16 tions nvelope mentation du logiciel de gestion financi Solar ère et comptable (TOM 2 PR O) de l'UGP SOLEER BF-UGP/SOLEER -352969-NC -RFQ / Recrutement d'une ag Component 3: Private Sector Request for Quota Single Stage - One E Pending Impl ence chargée des prestations TF / B5744 Mobilization for Large-Scale Post Limited 47,794.00 0.00 2023-04-26 2023-06-21 2023-12-18 tions nvelope ementation de service d'assurance mala Solar die au profit du personnel de l'UGP SOLEER CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BF-UGP/SOLEER -352962-CS- LCS / Recrutement d'un cabi Component 3: Private Sector Least Cost Selecti Pending Impleme net chargé de l'audit des co TF / B5744 Mobilization for Large-Scale Post Open - National 50,000.00 0.00 2023-04-27 2023-05-18 2023-07-01 2023-07-29 2023-08-28 2023-10-02 2023-11-06 2024-05-04 on ntation mptes du projet SOLEER pou Solar r les exercices 2023, 2024 et 2025 BF-UGP/SOLEER -352963-CS- Component 3: Private Sector CQS / Recrutement d'un cabi Consultant Qualifi Pending Impleme TF / B5744 Mobilization for Large-Scale Post Limited 18,382.00 0.00 2023-04-24 2023-05-08 2023-06-07 2023-07-12 2024-01-08 net en charge du recrutemen cation Selection ntation Solar t du personnel complémentai re de l'UGP BF-UGP/SOLEER -364659-CS- QCBS / Recrutement de l’ing énieur conseil chargé du cont Component 2: Utility-Scale S rôle et de la supervision des t Quality And Cost- Open - Internationa TF / B5744 olar with Storage and VRE In Post 800,000.00 0.00 Under Review 2023-06-30 2023-06-08 2023-07-21 2023-09-03 2023-10-01 2023-10-31 2023-12-05 2024-01-09 2025-01-08 ravaux dans le cadre de la co Based Selection l tegration nstruction des infrastructures d’évacuation de la productio n d’énergie des parcs solaire s régionaux au Burkina Faso. INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 1 BF-UGP/SOLEER -360611-CS- CDS / Recrutement d'un Con Component 3: Private Sector seil en transaction pour orga Direct - Internation TF / B5738 Mobilization for Large-Scale Prior Direct Selection 1,665,000.00 0.00 Under Review 2023-05-22 2023-06-01 2023-08-05 2024-02-01 niser une enchère (phase 2) al Solar dans le cadre du Parc Solaire à Vocation Régionale au Burk ina Faso Page 2 Project Procurement Strategy for Development April 18, 2022 I. Project overview Country: The Republic of Tajikistan Full Project Name: Technical Assistance for Financing Framework for Rogun Hydropower Project Total Finance ($): US$15,000,000 Project number: P178819 Project Development The development objective is to improve the Objective readiness of Rogun hydropower project to raise a financing package required for completion of construction II. Project Description The TA Project will help to: (a) strengthen technical, environmental and social aspects of the Rogun hydropower plant construction project (Rogun HPP Project); (b) develop the commercial framework of the Rogun HPP Project; and (c) strengthen the institutional capacity of the Project Management Group for Energy Facilities Construction under the President of the Republic of Tajikistan Rogun (Rogun PMG), which is the implementing entity for Rogun HPP Project. The TA Project would be implemented during the period of April 2022 and April 2031. The TA Project will have the following key components: Component 1: Improvement of the dam safety of Rogun HPP Project (estimated cost of about US$6.3 million). This component will finance: (a) the panel of experts (POE) for the dam safety, which will carry out due diligence and ensure international quality standards in the design and construction of Rogun HPP Project; provide high level and professional independent advice and guidance to support objectivity and credibility in the development and implementation of designs and in the construction of the project; share technical expertise and knowledge and so contribute to dialogue amongst the various stakeholders; and (b) technical and engineering studies that may be required for improvement of technical aspects of the Project. Component 2: Strengthening of environmental and social (E&S) performance of Rogun HPP Project (estimated cost of about US$5.2 million). This component will finance the following: (a) update of E&S instruments for Rogun HPP Project to align them with the requirements of the World Bank’s Environmental and Social Framework (ESF); assistance to Rogun PMG in developing a Contractor Management Plan that will include the details of how Rogun PMG will supervise the E&S performance of its contractors; recommendations on modification of existing contractors, to 1 include relevant E&S requirements to comply with the applicable E&S standards and requirements; (d) E&S panel of experts; and (e) design of local community benefit-sharing program. Component 3: Development of the commercial framework for Rogun HPP Project (estimated cost of US$2 million). This component will finance: (a) preparation of a macroeconomically sustainable Project construction completion schedule taking into account the existing and projected macro-fiscal framework of the country; (b) prepare a Project financing plan taking into account the updated Project construction completion schedule; (c) transaction advisory service to help the Government draft, negotiate, and sign long-term PPAs for sale of Rogun electricity; and (d) technical and engineering studies that may be required for strengthening o Component 4: Strengthening of institutional capacity of Rogun PMG and other technical assistance (estimated cost of US$1.5 million). This component will finance: (a) strengthening of Rogun PMG team to implement the TA Project; (b) capacity building for Rogun PMG and Rogun JSC staff in dam safety, operation and management of hydro facilities, and project management; (c) Purchase of Information and Communication Technologies (ITC) and office equipment for Rogun PMG; (d) TA Project audits; and (e) incremental operating costs of Rogun PMG. III. Strategic Assessment of Country, Borrower and Marketplace a. Operational context Governance aspects. Government of the Republic of Tajikistan established the Rogun Open Joint Stock Company to own and operate the Rogun Hydropower Project (HPP). By the executive order of the President (No. 1361, dated October 26, 2012), Rogun PMG was established. It is the implementing entity for the construction of the Project. The HPP is being constructed on the Vakhsh River about 110 kilometers east of Dushanbe and about 70 kilometers upstream of the Nurek HPP. The dam will be 335 meters high and the facility will have generation capacity of 3,780 MW. This large hydropower project of 3,780 MW located on the Vakhsh cascade has the potential to generate a multitude of benefits for Tajikistan and the broader Central Asia (CA) region. For Tajikistan, the project could provide reliable electricity to meet growing domestic electricity demand at affordable costs. The legal and regulatory framework to be applicable to the key aspects of the TA Project is clear and well-defined. The World Bank Procurement Regulations applicable to the project take precedence over any conflicting regulations from the national public procurement laws. This has been enabled in the Constitution of the Republic of Tajikistan. The current Law on Public Procurement of Goods, Works and Services was adopted in March 2006 and was amended on April 16, 2012. The Government is working on preparation of a new PPL based on the UNCITRAL Model Law 2011 and the principles of the WTO GPA, and, in parallel, on the development of secondary legislation and standard bidding documents to be in line with the new draft 2 PPL. The licensing framework for provision of technical consulting services is clear. In addition, the consultants will be required to comply with the requirements of the World Bank’s relevant Environmental and Social Standards (ESS) as detailed in the relevant E&S documents prepared as well as the requirements of the local legislation related to labor policies. Economic aspects. In 2021, Tajikistan’s per capita income (GNI, Atlas method) was about US$1,100, which is slightly above the lower-middle- income threshold. The poverty rate fell from 17.8 percent in 2015 to about 13.9 percent in 2021. Tajikistan's economy relies heavily on primary commodity production and exports, with limited economic diversification. Domestic investment and consumption depend heavily on migrant remittances, which are about a third of GDP, thus leaving the economy highly vulnerable to external shocks. Sanctions on the Russian economy have exposed this vulnerability since Russia is the largest employer of Tajik migrant workers and is among the largest trading partners. Reforms aimed at private sector growth, public sector efficiency, and greater inclusion are vital to further economic development. Sustainability aspects. There are no issues with the sustainability aspects of the TA Project-financed activities since they only include advisory services and technical assistance for the needs of PMG. The proposed TA Project would contribute to strengthening the sustainability of the Rogun HPP Project by introducing requirements for good-practice E&S standards; robust criteria for E&S performance of the existing and new contractors; and design of community benefit sharing program that would contribute to equitable development and sustainable socio-economic growth at the local and national levels. Technological aspects. The assessments and studies under the TA Project will be relying on methodologies (such as hydropower planning, probable maximum flood modelling, least-cost system planning with economic optimization), which are considered to be standard for the hydropower sector and overall electricity industry. Therefore, there are no issues or risks to the grant-financed activities from technology-driven change or deployment of untested methods for technical studies. Key Conclusion. No major issues expected given that the grant would be financing primarily consulting services. b. Client Capability and PMG Assessment Experience. Rogun PMG will be responsible for the implementation of the Project. PMG staff consists of 34 persons. In its procurement activities, it is guided by the developed regulations, instructions, the Public Procurement Law of the Republic of Tajikistan, and the Rules for International Tender for Construction of Rogun Project. Rogun PMG has significant experience in implementing projects funded by the state budget including preparation of bidding documents for works and goods contracts, evaluation of bids, contract negotiations, and contract management. Rogun HPP team and the Resettlement Unit will be involved in reviewing the relevant documents, 3 reports, and outputs to be produced by the consultants to be hired by Rogun PMG. They would be involved in reviewing and approving the contractual, technical, environmental and social recommendations and advice to be provided by the consultants that would be hired by Rogun PMG , con. In addition to its primary function, Rogun PMG is also responsible for coordination of the activities with various ministries, departments and international financial organizations in the implementation of the state policy of the Republic of Tajikistan related to issues related to the construction of energy facilities and their upgrade in accordance with the programs of socio- economic development of the Republic of Tajikistan. The activities of the Rogun PMG related to procurement process include, among other things, the following: • Coordination of activities with ministries and departments, enterprises, institutions of Tajikistan and other international financial organizations related to the construction of energy facilities. • Ensuring, together with the authorized state bodies, the organization of the work of tender commissions related to the construction of power facilities. • Development and preparation of documentation for procurement of goods, works, consulting and non-consulting services for the construction of power facilities. • Monitoring the use of funds attracted and allocated by the Government of the Republic of Tajikistan for the implementation of projects for the construction of energy facilities. • Coordination and provision of working conditions for international and domestic specialists, consultants, experts in the preparation and implementation of projects. • Together with the authorized state bodies, organizing meetings with representatives of international organizations and, based on their results, providing information to the President of the Republic of Tajikistan. However, Rogun PMG does not have experience in implementation of projects financed by IFIs including the World Bank. It currently has one procurement consultant with experience in procurement in World Bank financed projects – CASA-1000 and Rural Electrification Project. The consultant will continue providing support to the Rogun PMG under her current financing until Rogun PMG selects a procurement specialist funded by the TA Project to carry out the required functions till the end of the TA Project. Her performance to date has been satisfactory. The procurement specialist will receive the required training to further strengthen the capacity in World Bank’s procurement rules and policies. Contract management capacity. Contract management is the responsibility of the relevant staff (director, manager, technical experts, etc.). Rogun PMG maintains an Excel file to track key contract dates. PMG has experience in managing contracts for similar projects such as pre- contract works on Rogun HPP Project that involved management of several 4 civil works contractors, construction of electricity transmission line projects for evacuation of electricity from Rogun HPP Project. In general, Rogun PMG will benefit from further training in contract management. Complaint management and dispute resolution systems. Rogun PMG will follow the requirements of The World Bank Procurement Regulations for IPF Borrowers (Nov 2020) in handling the complaints under consulting and goods contracts. Specifically, if a complaint is received, consistent with the requirements of an RFP or a request for bids, then Rogun PMG will respond to the complaint by ensuring the following minimum information is provided: (a) statement of issues; (b) facts and evidence; (c) decision and reference to the basis for the decision; and (d) analysis. Rogun PMG will act consistent with the roles and responsibilities of the Borrower/Recipient as specified in the World Bank Procurement Regulations Conclusions on PMG capacity. PMG has experience in implementing projects financed by the Government. However, it has no experience with the World Bank procurement procedures; have limited monitoring and contract management skills, as this function was mainly assigned to external consultants. The existing capacity is not sufficient to manage the growing volume of procurement activities across multiple projects running in parallel. Therefore, this will require further strengthening of PMG’s capacity to meet the TA Project needs. c. Market analysis Market sector dynamics. There are many specialized consulting firms that provide technical, economic analysis, environmental and social advisory, as well as financial and legal advisory services related to various aspects of hydropower projects and that have been very active in Tajikistan. These firms have been contracted to perform various large consulting assignments for new investment projects in the hydropower as well as rehabilitation projects; technical and economic assessments of new investments; feasibility studies; preparation of tender documentation; and preparation of environmental and social instruments/documents as required by various financial institutions; and financial and legal advisory for various project-level needs. Additionally, there have been strong interest from global individual experts to assume roles under the POE for dam safety and E&S issues. This has been demonstrated during implementation of techno-economic assessment studies (TEAS) for the Project as well as engagement of those experts for the needs of Nurek Hydropower Rehabilitation Project. Procurement risk analysis Keeping in view the nature of the consulting contracts to be procured under the TA Project, the main risks associated with the implementation of the TA Project and the proposed mitigation measures are described hereunder. Risk Description A B Overal Description of Risk l Risk proposed owner 5 Likelihood Impact Rating mitigation Rating Rating (A*B) through the procurement process Lack of interest 2 3 6 Procurement Rogun from reputable activities related to PMG international Rogun HPP that is a consultants. very large and complex project. Therefore, it is expected to generate significant interest from reputable international consultant. Moreover, competitive procurement is expected to be the main approach. Issues with 2 4 8 The TA Project Rogun contract would finance PMG management due capacity building to limited and training of the familiarity of relevant staff in Rogun PMG staff procurement and with Procurement contract Regulations of the management. World Bank. IV. Procurement objectives The main procurement objectives to be achieved are: • Advance preparation of TOR to avoid delays in procurement; • Monitoring of the procurement process so that the timing of each tender does not exceed the planned deadlines. V. Recommended Procurement Approach for a Grant Activity 1: Panel of Experts (POE) on Dam Safety Selection method for all nine POE members: International Competitive Selection. Individual consultant contracts (time-based). The POE will be comprised of various experts and those will need to be hired under individual contracts because POE members will need to be internationally renowned experts in their respective fields and the experience and qualifications of the individuals are of paramount requirement. This cannot be achieved through hiring of a firm. We will invite those individual consultants that we deem 6 qualified to provide the required consulting services. The complete TOR will be sent with the invitation. Estimated cost: The estimated cost of each POE member contract is presented in the Procurement Plan (PP) and is expected to range from US$142,000 to US$770,000 Duration of contract: The POE members will provide services during the period of May 2022 – April 2031. Level of risk: Low. Activity 2: Update of the environmental and social instruments of the Rogun HPP Project Selection method: Quality and Cost Based Solution (QCBS). International Competitive. Estimated cost: US$4,000,000. Duration of contract: June 2022 – June 2026. Risk level: Medium. Activity 3: POE on Social and Environmental Issues Selection method for all three POE members: International Competitive Selection. Individual consultant contracts (time-based). The POE will be comprised of various experts and those will need to be hired under individual contracts because POE members will need to be internationally renowned experts in their respective fields and the experience and qualifications of the individuals are of paramount requirement. This cannot be achieved through hiring of a firm. We will invite those individual consultants that we deem qualified to provide the required consulting services. The complete TOR will be sent with the invitation. Estimated cost: The estimated cost of each POE member contract is presented in the Procurement Plan (PP) and is expected to range from US$300,000 to US$574,000. Duration of contract: The POE members will provide services during the period of May 2022 – May 2031. Level of risk: Low. Activity 4: Update of the Project implementation completion schedule Selection method: Direct contract with joint venture of Tractebel-ELC (France-Italy). The direct contracting is justified for the following reasons: 7 a. The JV of Tractebel-ELC was selected in 2018 using international competitive process. The contract is financed by the Government. The consultant was hired to carry out update of the project implementation schedule, technical supervision of some construction activities and manage the interface among existing civil works contractors under Rogun HPP Project. The contract is still ongoing with the focus on technical supervision of construction works. b. The engagement of JV of Tractebel-ELC is justified because this assignment is related to ongoing services under the existing contract. The procurement is of both very low value and low risk. Estimated cost: US$100,000. Duration of contract: May 2022 – July 2022. Risk level: Low. Activity 5: Preparation of a financing plan to complete construction of the Project Selection method: Quality and Cost Based Solution (QCBS). International Competitive. Estimated cost: US$474,000. Duration of contract: July 2022 – September 2022. Risk level: Medium. Activity 6: Financial and legal advisor to negotiate and sign long- term power purchase agreements Selection method: Quality and Cost Based Solution (QCBS). International Competitive. Estimated cost: US$1,100,000. Duration of contract: August 2022 – June 2023. Risk level: Medium. Activity 7: Update of economic analysis of the Project Selection method: Direct contract with Poweren Consulting (UAE). This method is justified given that the Consultant has knowledge of the Project of exceptional worth to the needs of the assignment. The proposed consultant has previously completed a similar contract with the Borrower for detailed modelling of electricity sector, dispatch simulation, and valuation of economic costs and benefits of large hydro rehabilitation projects. The contract was under Nurek Hydropower Rehabilitation Project financed by the World Bank. Therefore, the Consultant can perform the task with much 8 greater speed and precision, which is of critical importance for the Rogun HPP. Without detailed and very rigorous updated economic analysis, based on the updated implementation schedule, it will be impossible to secure financing for the completion of the Rogun HPP. This, in turn, will create technical and safety risks. The performance of this consultant was satisfactory under the previous contract. Estimated cost: US$ 200,000. Duration of contract: July 2022 – October 2022. Risk level: Low. Activity 8: Purchase of IT and office equipment for Rogun PIG Selection method: Request for Quotation. Estimated cost: US$50,000. Duration of contract: September 2022. Risk level: Low. Activity 9: Audit of the annual financial statements of the grant Selection method: LCS. The audit firms will be selected from the World Bank’s list of auditors eligible to carry out Project audits. Estimated cost: US$20,000 per year (needs to be carried out for each year during 10-year implementation period of the TA) Duration of contract: Recurring. Risk level: Low. 9 Procurement plan Sl. Activity Estimated Procureme Contract Prior/pos N cost nt method signing date t review o in US$ (including taxes) 1 Dam Safety POE Dam engineering expert/POE 767,700 IC May 16, 2022 Post Chair Hydrology and sediment 108,300 IC May 16, 2022 Post management expert Engineering geology and 171,200 IC May 16, 2022 Post hydrogeology expert Geotechnical engineering expert 672,400 IC May 16, 2022 Post Hydraulics expert 672,400 IC May 16, 2022 Post Seismology and seismic design 142,300 IC May 16, 2022 Post expert 10 Sl. Activity Estimated Procureme Contract Prior/pos N cost nt method signing date t review o in US$ (including taxes) Electro-mechanical expert 672,400 IC May 16, 2022 Post Hydromechanical expert 199,510 IC May 16, 2022 Post Hydropower construction 409,800 IC May 16, 2022 Post management expert 2 E&S POE Hydrology and water resources 574,000 IC June 10, 2022 Post expert/POE Chair Environmental and planning 300,500 IC June 10, 2022 Post expert Social and resettlement expert 425,500 IC June 10, 2022 Post 3 Update of the environmental 4,000,000 QCBS July 20, 2022 Prior and social instruments of the Rogun HPP Project 4 Update of the Project 100,000 DS May 16, 2022 Post implementation completion schedule 5 Preparation of a financing plan 400,000 QCBS July 30, 2022 Post to complete construction of the Project 6 Financial and legal advisor to 1,100,000 QCBS July 30, 2022 Post negotiate and sign long-term power purchase agreements 7 Update of economic analysis of 200,000 DS July 20, 2022 Post the Project 8 Purchase of ICT and office 50,000 RFQ September 30, Post equipment for Rogun PIG 2022 9 Audit 200,000 LCS Annually Post 11 PROCUREMENT Tajikistan : Technical Assistance for Financing Framework for Rogun Hydropower Project PLAN General Information Country: Tajikistan Bank’s Approval Date of the Original Procurement Plan:2022-04-29 2023-06-01 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P178819 GPN Date: Project Name: Technical Assistance for Financing Framework for Rogun Hydropower Project Loan / Credit No: / , IDA / E1460 Project Management Group for Energy Facilities Construction under the President of the RT Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual RHPP/SH/G/01 / Purchase of I Request for Quota Single Stage - One E Pending Impl / Post Open - National 50,000.00 0.00 2022-07-06 2022-08-31 2022-09-30 CT and office equipment for tions nvelope ementation Rogun PIG NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual RHPP/CS/CQBS/03 / Financial and legal advisor to negotiat Quality And Cost- Open - Internationa / Post 1,100,000.00 0.00 Canceled 2022-07-01 2022-07-15 2022-08-19 2022-09-18 2022-10-09 2022-11-13 2022-12-11 2023-11-06 e and sign long-term power p Based Selection l urchase agreements RHPP/CS/CQBS/01 / Update Quality And Cost- Open - Internationa of the environmental and soc / Prior 4,000,000.00 0.00 Signed 2022-06-01 2022-05-04 2022-06-15 2022-05-31 2022-07-20 2022-07-16 2022-08-19 2022-08-24 2022-09-09 2022-09-11 2022-10-14 2022-11-17 2022-11-11 2026-11-10 Based Selection l ial instruments of the Rogun HPP Project RHPP/CS/CQBS/02 / Preparat Quality And Cost- Open - Internationa ion of a financing plan to co / Post 400,000.00 0.00 Canceled 2022-07-01 2022-07-15 2022-08-19 2022-09-18 2022-10-09 2022-11-13 2022-12-11 2023-03-11 Based Selection l mplete construction of the Pr oject Component 1: Development RHPP/CS/CQS/01 / Independ of macroeconomically sustai Consultant Qualifi Open - Internationa ent assessment of Lot 3 Cont / Post 180,000.00 0.00 Signed 2022-08-14 2022-08-02 2022-09-04 2022-08-19 2022-10-18 2022-09-05 2022-11-17 2022-11-04 2022-12-22 2023-02-20 nable financing plan and a c cation Selection l ract ommercial framework for Ro gun HPP project RHPP/CS/QCBS/02 / Preparat Component 1: Development ion of Rogun HPP Project Fina of macroeconomically sustai Quality And Cost- Open - Internationa Under Implement / Prior 1,500,000.00 0.00 2022-09-15 2022-09-01 2022-09-29 2022-09-09 2022-11-03 2022-12-28 2022-12-03 2023-02-02 2022-12-24 2023-03-15 2023-01-28 2023-06-01 2023-03-04 2023-10-30 ncing Plan and Development nable financing plan and a c Based Selection l ation of Power Purchase Agreemen ommercial framework for Ro ts for Rogun HPP gun HPP project RHPP/CS/QCBS/3 / Design an Component 3: Strengthening d Implementation Support for of E&S framework and benef Quality And Cost- Open - Internationa Under Implement IDA / E1460 Post 600,000.00 0.00 2023-02-23 2023-03-17 2023-03-09 2023-05-08 2023-04-13 2023-05-13 2023-06-03 2023-07-08 2023-08-12 2025-06-12 Benefit Sharing Program for it sharing aspects of Rogun Based Selection l ation Rogun HPP Project HPP Project RHPP/CS/QCBS/03 / Design o Component 3: Strengthening Quality And Cost- Open - Internationa f Benefit Sharing Program for / of E&S framework and benef Post 600,000.00 0.00 Canceled 2022-11-15 2022-12-30 2022-11-29 2023-01-17 2023-01-03 2023-02-02 2023-02-23 2023-03-30 2023-05-04 2024-05-03 Based Selection l Rogun HPP it sharing aspects of Rogun HPP Project RHPP/CS/CQS/02 / Audit of t he Quality Assurance and Qu Component 2: Improvement Consultant Qualifi Open - Internationa Under Implement IDA / E1460 Post 200,000.00 0.00 2023-03-31 2023-04-05 2023-04-14 2023-05-03 2023-05-19 2023-05-23 2023-06-02 2023-07-07 2023-09-05 ality Control Systems and As of the dam safety cation Selection l ation sociated Procedures followed for construction works RHPP/CS/CQS/03 / Seismic H Component 2: Improvement Consultant Qualifi Open - Internationa Pending Impleme IDA / E1460 Post 300,000.00 0.00 2023-06-30 2023-07-14 2023-08-18 2023-09-01 2023-10-06 2024-04-03 azard Update Study of the dam safety cation Selection l ntation RHPP/CS/CQS/04 / Sediment Component 2: Improvement Consultant Qualifi Open - Internationa Pending Impleme IDA / E1460 Post 300,000.00 0.00 2023-07-02 2023-07-16 2023-08-20 2023-09-03 2023-10-08 2024-04-05 ation Study of the dam safety cation Selection l ntation RHPP/CS/QCBS/05 / Hydrolo Component 2: Improvement Quality And Cost- Open - Internationa Pending Impleme IDA / E1460 Prior 1,000,000.00 0.00 2023-07-04 2023-07-18 2023-08-22 2023-09-21 2023-10-12 2023-11-16 2023-12-21 2024-12-20 gy and Climate Change Stud of the dam safety Based Selection l ntation y Component 1: Development RHPP/CS/ QCBS/04 / Electrici of macroeconomically sustai Quality And Cost- Open - Internationa Pending Impleme ty Sector Cost of Service Stu IDA / E1460 Post 350,000.00 0.00 2023-07-31 2023-08-14 2023-09-18 2023-10-18 2023-11-08 2023-12-13 2024-01-17 2024-07-21 nable financing plan and a c Based Selection l ntation dy ommercial framework for Ro gun HPP project RHPP/CS/CQS/05 / Support w Component 2: Improvement Consultant Qualifi Open - Internationa Pending Impleme ith Negotiation of Amendmen IDA / E1460 Post 295,000.00 0.00 2023-06-30 2023-07-14 2023-08-18 2023-09-01 2023-10-06 2024-02-08 of the dam safety cation Selection l ntation ts to Existing Contracts INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual RHPP/CS/IC/02 / Hydraulics e Individual Consult / Prior Limited 672,400.00 765,280.00 Signed 2022-05-04 2022-05-16 2022-05-09 2022-07-25 2022-05-19 2022-08-26 2022-06-12 2022-08-27 2031-06-10 xpert ant Selection Page 1 RHPP/CS/IC/03 / Geotechnica Individual Consult / Prior Limited 672,400.00 631,100.00 Signed 2022-05-04 2022-05-16 2022-05-09 2022-07-25 2022-05-19 2022-08-25 2022-06-12 2022-08-26 2031-06-10 l engineering expert ant Selection RHPP/CS/IC/04 / Electro-mec Individual Consult / Prior Limited 672,400.00 619,900.00 Signed 2022-05-04 2022-05-16 2022-05-09 2022-07-25 2022-05-19 2022-08-26 2022-06-12 2022-09-05 2031-06-10 hanical expert ant Selection RHPP/CS/DC/01 / Update of e Pending Impleme / Post Direct Selection Direct 200,000.00 0.00 2022-06-01 2022-06-07 2022-07-02 2022-09-30 conomic analysis of the Proje ntation ct RHPP/CS/DC/02 / Update of t Pending Impleme he Project implementation co / Post Direct Selection Direct 100,000.00 0.00 2022-06-01 2022-06-07 2022-07-02 2022-09-30 ntation mpletion schedule RHPP/CS/IC/01 / Dam engine Individual Consult / Prior Limited 767,700.00 554,750.00 Signed 2022-05-05 2022-05-16 2022-05-10 2022-07-25 2022-05-20 2022-08-23 2022-06-13 2022-08-25 2031-06-11 ering expert/POE Chair ant Selection RHPP/CS/IC/7 / Seismology a Component 2: Improvement Individual Consult / Post Open 142,300.00 431,640.00 Signed 2022-05-30 2022-07-26 2022-07-09 2022-08-17 2022-07-30 2022-08-24 2022-08-13 2022-08-26 2031-08-11 nd Seismic Design Expert of the dam safety ant Selection RHPP/CS/IC/6 / Engineering g Component 2: Improvement Individual Consult / Post Open 171,200.00 509,000.00 Signed 2022-05-30 2022-06-17 2022-07-09 2022-08-01 2022-07-30 2022-08-24 2022-08-13 2022-08-26 2031-08-11 eology and hydrogeology ex of the dam safety ant Selection pert RHPP/CS/IC/06 / Engineering Individual Consult / Post Limited 171,200.00 0.00 Canceled 2022-05-04 2022-05-09 2022-05-19 2022-06-12 2031-06-10 geology and hydrogeology e ant Selection xpert RHPP/CS/IC/07 / Seismology Individual Consult / Post Limited 142,300.00 0.00 Canceled 2022-05-04 2022-05-09 2022-05-19 2022-06-12 2031-06-10 and seismic design expert ant Selection RHPP/CS/IC/5 / Hydrology an Component 2: Improvement Individual Consult / Post Open 108,300.00 395,330.00 Signed 2022-05-30 2022-08-22 2022-07-09 2022-09-08 2022-07-30 2022-09-08 2022-08-13 2022-09-10 2031-08-11 d Sediment Management Exp of the dam safety ant Selection ert RHPP/CS/IC/05 / Hydrology a Individual Consult / Post Limited 108,300.00 0.00 Canceled 2022-05-04 2022-05-09 2022-05-19 2022-06-12 2031-06-10 nd sediment management ex ant Selection pert RHPP/CS/IC/8 / Hydromecha Component 2: Improvement Individual Consult / Post Open 199,510.00 287,960.00 Signed 2022-05-30 2022-05-25 2022-07-09 2022-07-25 2022-07-30 2022-08-24 2022-08-13 2022-08-26 2031-08-11 nical Expert of the dam safety ant Selection RHPP/CS/IC/08 / Hydromech Individual Consult / Post Limited 199,510.00 0.00 Canceled 2022-05-04 2022-05-09 2022-05-19 2022-06-12 2031-06-10 anical expert ant Selection RHPP/CS/IC/09 / Hydropower Individual Consult / Prior Limited 409,800.00 0.00 Canceled 2022-05-04 2022-05-09 2022-05-19 2022-06-12 2031-06-10 construction management ex ant Selection pert RHPP/CS/IC/10 / Hydrology a Individual Consult / Prior Limited 574,000.00 0.00 Canceled 2022-06-01 2022-06-06 2022-06-16 2022-07-10 2031-07-08 nd water resources expert/P ant Selection OE Chair RHPP/CS/IC/11 / Environmen Individual Consult / Prior Limited 300,500.00 0.00 Canceled 2022-06-01 2022-06-06 2022-06-16 2022-07-10 2031-07-08 tal and planning expert ant Selection RHPP/CS/IC/12 / Social and r Individual Consult / Prior Limited 425,500.00 0.00 Canceled 2022-06-01 2022-06-06 2022-06-16 2022-07-10 2031-07-08 esettlement expert ant Selection Component 3: Strengthening RHPP/CS/IC_12 / Social and r Individual Consult / of E&S framework and benef Prior Open 425,500.00 0.00 Signed 2022-06-20 2022-09-01 2022-07-30 2022-09-29 2022-08-20 2022-10-10 2022-09-03 2031-09-01 esettlement expert ant Selection it sharing aspects of Rogun HPP Project RHPP/CS/IC/9 / Hydropower Component 2: Improvement Individual Consult Open - Internationa / Prior 409,800.00 524,800.00 Signed 2022-08-14 2022-08-02 2022-10-02 2022-08-26 2022-10-23 2022-09-07 2022-11-27 2022-09-08 2023-05-26 Construction Management Ex of the dam safety ant Selection l pert Component 3: Strengthening RHPP/CS/IC_11 / Environmen Individual Consult Open - Internationa / of E&S framework and benef Prior 300,500.00 0.00 Signed 2022-08-08 2022-09-01 2022-09-26 2022-09-22 2022-10-17 2022-10-13 2022-11-21 2023-05-20 tal and planning expert ant Selection l it sharing aspects of Rogun HPP Project Component 1: Development RHHP/CS/DC/02 / Update of t of macroeconomically sustai Direct - Internation he Project implementation co / Post Direct Selection 150,000.00 0.00 Signed 2022-07-31 2022-08-02 2022-08-10 2022-08-05 2022-10-14 2023-04-12 nable financing plan and a c al mpletion schedule ommercial framework for Ro gun HPP project RHPP/CS/IC/13 / Senior Envir Component 3: Strengthening Individual Consult Open - Internationa onmental and Social Advisor / of E&S framework and benef Prior 430,000.00 0.00 Signed 2022-11-08 2022-10-31 2022-12-18 2022-11-16 2023-01-08 2022-11-17 2023-02-12 2024-03-18 ant Selection l for Rogun Project Manageme it sharing aspects of Rogun nt Group HPP Project RHHP/CS/DC/03 / Preparatio Component 2: Improvement Direct - Internation Under Implement n of Lot 4 bidding documents IDA / E1460 Post Direct Selection 565,000.00 0.00 2023-02-23 2023-03-10 2023-03-05 2023-05-09 2024-05-08 of the dam safety al ation and assistance during tender ing RHPP/CS/IC/10/ / Occupation Component 3: Strengthening Individual Consult Pending Impleme al Health and Safety Speciali IDA / E1460 of E&S framework and benef Post Limited 100,000.00 0.00 2023-06-29 2023-07-04 2023-07-14 2023-08-07 2025-02-04 ant Selection ntation st for Rogun PMG it sharing aspects of Rogun HPP Project RHPP/CS/IC_10 / Hydrology a Component 3: Strengthening Individual Consult nd water resources expert/P / of E&S framework and benef Prior Open 574,000.00 0.00 Canceled 2022-06-20 2022-09-01 2022-07-30 2022-08-20 2022-09-03 2031-09-01 ant Selection OE Chair it sharing aspects of Rogun HPP Project RHPP/ CS/IC/14 / Probity Adv Component 2: Improvement Individual Consult Open - Internationa Pending Impleme IDA / E1460 Post 65,000.00 0.00 2023-06-04 2023-07-14 2023-08-04 2023-09-08 2024-05-05 iser of the dam safety ant Selection l ntation RHPP/CS/DC/05 / Summary o Component 1: Development f existing capacity of hydrog of macroeconomically sustai en and ammonia production i Direct - Internation Pending Impleme IDA / E1460 nable financing plan and a c Post Direct Selection 30,000.00 0.00 2023-07-27 2023-08-06 2023-08-31 2023-10-30 n Tajikistan and overview of al ntation ommercial framework for Ro main existing global projects gun HPP project in advanced stages of develo pment RHPP/CS/DC/04 / Preliminary Component 1: Development evaluation of competitivenes of macroeconomically sustai Direct - Internation Pending Impleme s of green hydrogen and gre IDA / E1460 nable financing plan and a c Post Direct Selection 80,000.00 0.00 2023-07-31 2023-08-10 2023-09-04 2023-11-03 al ntation en ammonia production and ommercial framework for Ro exports from Tajikistan gun HPP project Page 2 Procurement Plan I. General 1. Bank’s approval Date of the procurement Plan [Original: February 2020] 2. Period covered by this procurement plan: The procurement period of project covered from year February 2020 till June 2020. II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: [Thresholds for applicable procurement methods (not limited to the list below) will be determined by the Procurement Specialist /Procurement Accredited Staff based on the assessment of the implementing agency’s capacity.] Procurement Method Prior Review Comments Threshold US$ 1. ICB and LIB (Goods) Above US$ 1.5 All million 2. NCB (Goods) Above US$ 1.5 All million 3. ICB (Works) Above US$ 5 million All 4. NCB (Works) Above US$ 5 million All 2. Prequalification. Bidders for works activities shall be prequalified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines. 4. Summary of the Procurement Packages planned during the first 18 months after project effectiveness (including those that are subject to retroactive financing and advanced procurement) Refer to PP. III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Comments Threshold 1. Competitive Methods (Firms) Above US$ 0.5 million 2. Single Source (Firms) All 3. Individual Above US$ 0.2 million 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_300,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Consultancy Assignments with Selection Methods and Time Schedule Refer to PP PROCUREMENT Lebanon : Lebanon Health Resilience Project PLAN General Information Country: Lebanon 2020-02-15 Bank’s Approval Date of the Original Procurement Plan: 2023-06-07 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P163476 GPN Date: 2020-06-08 Project Name: Lebanon Health Resilience Project Loan / Credit No: IBRD / 87710 Ministry of Public Health Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MOPH-RFQ-COVID19-001 / Pr Strengthen the Government’ Request for Quota IBRD / 87710 Prior 1,500,000.00 68,815.00 Signed 2019-03-18 2019-03-18 2020-04-28 2019-03-18 ocurement of PPEs s capacity to respond to CO tions VID-19 MOPH-RFQ-COVID19-002 / Pr Strengthen the Government’ Request for Quota IBRD / 87710 Prior 2,000,000.00 1,638,696.38 Signed 2019-03-18 2019-03-18 2020-04-16 2019-03-18 ocurement of Ventilators s capacity to respond to CO tions VID-19 MOPH-DS-COVID19-004 / PR Strengthen the Government’ IBRD / 87710 Post Direct Selection Direct 400,000.00 0.00 Canceled 2020-04-16 2020-04-15 2020-04-21 2020-05-26 2020-11-22 OCUREMEMT OF RAPID TEST s capacity to respond to CO KITS VID-19 LB-MOPH-RFQ005 / Procure Strengthen the Government’ Request for Quota Single Stage - One E ment of Goods for Negative P IBRD / 87710 s capacity to respond to CO Post Open - National 60,000.00 45,065.00 Signed 2020-12-19 2020-12-18 2021-02-13 2021-01-15 2021-08-12 tions nvelope ressure Rooms VID-19 LB-MOPH-RFQ003 / Procure Strengthen the Government’ Request for Quota Single Stage - One E IBRD / 87710 Post Limited 450,000.00 151,766.00 Signed 2020-12-19 2020-12-24 2021-02-13 2020-12-29 2021-08-12 ment of COVID-19 Related Eq s capacity to respond to CO tions nvelope uipment VID-19 LB-MOPH-RFQ004 / Procure Strengthen the Government’ Request for Quota Single Stage - One E IBRD / 87710 Post Limited 450,000.00 74,551.00 Signed 2020-12-19 2021-01-19 2021-02-13 2021-04-15 2021-08-12 ment of COVID-19 Related Eq s capacity to respond to CO tions nvelope uipment VID-19 LB-MOPH-DS001 / Procurem Strengthen the Government’ ent of a UPS system for COVI IBRD / 87710 s capacity to respond to CO Post Direct Selection Direct 20,000.00 79,464.81 Signed 2021-01-08 2021-03-23 2021-01-13 2021-03-23 2021-02-17 2021-04-30 2021-08-16 D-19 unit at Qana Hospital VID-19 LB-MOPH-NP004 / Installatio Strengthen the Government’ n of a Negative Pressure syst IBRD / 87710 s capacity to respond to CO Post Direct Selection Direct 40,000.00 0.00 Canceled 2021-01-19 2021-01-24 2021-02-28 2021-08-27 em at Al Bouwar hospital VID-19 LB-MOPH-PFIZER / Procurem Strengthen the Government’ IBRD / 87710 Prior Direct Selection Direct 18,000,000.00 39,012,960.00 Signed 2021-01-19 2021-02-12 2021-01-24 2021-02-12 2021-02-28 2021-01-18 2021-08-27 ent of COVID-19 Vaccine s capacity to respond to CO VID-19 LB-MOPH-NP001 / Installatio Strengthen the Government’ Request for Quota Single Stage - One E n of a Negative Pressure Syst IBRD / 87710 s capacity to respond to CO Post Limited 40,000.00 185,987.81 Signed 2021-02-01 2021-02-09 2021-03-29 2021-01-28 2021-09-25 tions nvelope em at Baabda Public Hospital VID-19 LB-MOPH-NP002 / Installatio Strengthen the Government’ Request for Quota Single Stage - One E n of a Negative Pressure Syst IBRD / 87710 s capacity to respond to CO Post Limited 20,000.00 178,831.00 Signed 2021-02-01 2021-02-09 2021-03-29 2021-01-29 2021-09-25 tions nvelope em at Jezzin Hospital VID-19 LB-MOPH-SD001 / Rehabilita Strengthen the Government’ Request for Quota Single Stage - One E tion of COVID-19 ICU Unit at IBRD / 87710 s capacity to respond to CO Post Limited 40,000.00 190,890.62 Signed 2021-02-06 2021-03-23 2021-04-03 2021-02-02 2021-09-30 tions nvelope Sir El Donnieh Public Hospital VID-19 LB-MOPH-NP003 / Installatio Strengthen the Government’ Request for Quota Single Stage - One E n of Negative Pressure at Bat IBRD / 87710 s capacity to respond to CO Post Limited 20,000.00 143,216.24 Signed 2021-02-11 2021-02-09 2021-04-08 2021-01-30 2021-10-05 tions nvelope roun Hospital VID-19 LB-MOPH-NP0010 / Installati Strengthen the Government’ Request for Quota Single Stage - One E on of Negative Pressure Syst IBRD / 87710 s capacity to respond to CO Post Limited 40,000.00 145,769.34 Signed 2021-02-11 2021-04-25 2021-04-08 2021-01-29 2021-10-05 tions nvelope em at Mays Al Jabal Hospital VID-19 LB-MOPH-NP005 / Installatio Strengthen the Government’ Request for Quota Single Stage - One E n of Negative Pressure Syste IBRD / 87710 s capacity to respond to CO Post Limited 40,000.00 209,447.08 Signed 2021-02-11 2021-02-09 2021-04-08 2021-01-29 2021-10-05 tions nvelope m at Marjeyoun Hospital VID-19 LB-MOPH-NP006 / Installatio Strengthen the Government’ Request for Quota Single Stage - One E n of Negative Pressure Syste IBRD / 87710 s capacity to respond to CO Post Limited 40,000.00 136,490.26 Signed 2021-02-11 2021-02-16 2021-04-08 2021-02-17 2021-10-05 tions nvelope m at Saida Hospital VID-19 LB-MOPH-NP007 / Installatio Strengthen the Government’ Request for Quota Single Stage - One E n of Negative Pressure Syste IBRD / 87710 s capacity to respond to CO Post Limited 30,000.00 163,133.63 Signed 2021-02-11 2021-02-09 2021-04-08 2021-01-29 2021-10-05 tions nvelope m at Al Chahhar Al Gharbi VID-19 LB-MOPH-NP008 / Installatio Strengthen the Government’ Request for Quota Single Stage - One E n of Negative Pressure Syste IBRD / 87710 s capacity to respond to CO Post Limited 30,000.00 122,087.36 Signed 2021-02-11 2021-02-10 2021-04-08 2021-01-30 2021-10-05 tions nvelope m at Bcharri Hospital VID-19 LB-MOPH-NP009 / Installatio Strengthen the Government’ Request for Quota Single Stage - One E n of Negative Pressure Syste IBRD / 87710 s capacity to respond to CO Post Limited 20,000.00 94,908.03 Signed 2021-02-11 2021-04-25 2021-04-08 2021-02-18 2021-10-05 tions nvelope m at Nabatiye Hospital VID-19 LB-MOPH-RFQ006 / Procure Strengthen the Government’ Request for Quota Open - Internationa Single Stage - One E ment of Pfizer Vaccine Relate IBRD / 87710 s capacity to respond to CO Post 1,000,000.00 675,350.00 Signed 2021-02-22 2021-02-24 2021-04-19 2021-04-28 2021-10-16 tions l nvelope d Accessories VID-19 LB-MOPH-RFQ007 / Procure Strengthen the Government’ Request for Quota Single Stage - One E IBRD / 87710 Post Open - National 500,000.00 520,111.61 Signed 2021-03-07 2021-03-03 2021-05-02 2021-07-27 2021-10-29 ment of Spare Parts for CT Sc s capacity to respond to CO tions nvelope an VID-19 LB-MOPH-RFQ008 / Procure Strengthen the Government’ Request for Quota Single Stage - One E IBRD / 87710 Post Open - National 350,000.00 356,270.00 Signed 2021-03-24 2021-04-06 2021-05-19 2021-06-09 2021-11-15 ment of Oxygen Related Equi s capacity to respond to CO tions nvelope pment VID-19 Page 1 LB-MOPH-RFQ009 / Procure Strengthen the Government’ Request for Quota Open - Internationa Single Stage - One E IBRD / 87710 Post 500,000.00 405,000.00 Signed 2021-04-10 2021-04-06 2021-06-05 2021-05-13 2021-12-02 ment of Accessories for Vacci s capacity to respond to CO tions l nvelope nes VID-19 LB-MOPH-RFQ010 / Installati Strengthen the Government’ Request for Quota Single Stage - One E Under Imple IBRD / 87710 Post Open - National 300,000.00 0.00 2021-04-14 2021-04-12 2021-06-09 2021-12-06 on of Negative Pressure Syst s capacity to respond to CO tions nvelope mentation ems VID-19 LB-MOPH-RFQ011 / Procure Strengthen the Government’ Request for Quota Open - Internationa Single Stage - One E Under Imple ment of CT Scan Spare Parts IBRD / 87710 s capacity to respond to CO Post 50,000.00 0.00 2021-04-30 2021-05-18 2021-06-25 2021-12-22 tions l nvelope mentation for Al Menyeh and Chebaa Pu VID-19 blic Hospitals LB-MOPH-SD002 / Installatio Strengthen the Government’ Request for Quota Single Stage - One E IBRD / 87710 Post Limited 30,000.00 14,740.00 Signed 2021-05-25 2021-02-01 2021-07-20 2021-02-16 2022-01-16 n of Oxygen Related Equipm s capacity to respond to CO tions nvelope ent VID-19 LB-MOPH-DS002 / Procurem Strengthen the Government’ ent of syringes for the vaccin IBRD / 87710 s capacity to respond to CO Post Direct Selection Direct 60,000.00 60,000.00 Signed 2021-08-05 2021-08-09 2021-08-10 2021-08-10 2021-09-14 2021-08-11 2022-03-13 ation process VID-19 LB-MOPH-RFQ012 / Procure Strengthening project mana Request for Quota Open - Internationa Single Stage - One E IBRD / 87710 Post 180,000.00 25,047.74 Signed 2021-09-26 2021-09-20 2021-11-21 2022-04-05 2022-05-20 ment of an accounting softw gement and monitoring tions l nvelope are LB-MOPH-RFQ014 / Procure Strengthening project mana Request for Quota Single Stage - One E Under Imple IBRD / 87710 Post Limited 2,000.00 0.00 2021-11-03 2021-11-23 2021-12-29 2022-06-27 ment of Office Equipment (La gement and monitoring tions nvelope mentation ptops) LB-MOPH-RFQ013 / Procure Strengthen the Government’ Request for Quota Single Stage - One E IBRD / 87710 Post Open - National 100,000.00 43,000.00 Signed 2021-11-03 2021-11-18 2021-12-29 2021-12-08 2022-06-27 ment of Vaccine Accessories s capacity to respond to CO tions nvelope VID-19 LB-MOPH-DS003 / Procurem Strengthen the Government’ IBRD / 87710 Post Direct Selection Direct 40,000.00 22,780.00 Signed 2022-01-31 2022-01-27 2022-02-05 2022-02-21 2022-03-12 2022-03-01 2022-09-08 ent of Spare Parts for Tebnin s capacity to respond to CO e Hospital VID-19 LB-MOPH-RFQ015 / Procure Strengthening project mana Request for Quota Single Stage - One E Pending Impl IBRD / 87710 Post Open - National 2,000.00 0.00 2022-11-06 2023-01-01 2023-06-30 ment of office equipment (La gement and monitoring tions nvelope ementation ptops) LB-MOPH-RFQ016 / Procure Strengthen the Government’ Request for Quota Single Stage - One E Under Imple IBRD / 87710 Post Open - National 30,000.00 0.00 2023-02-06 2023-02-07 2023-04-03 2023-09-30 ment of IT Equipment s capacity to respond to CO tions nvelope mentation VID-19 LB-MOPH-RFQ017 / Procure Strengthening project mana Request for Quota Single Stage - One E Under Imple IBRD / 87710 Post Open - National 25,000.00 0.00 2023-02-06 2023-02-07 2023-04-03 2023-09-30 ment of Helium Tanks gement and monitoring tions nvelope mentation LB-MOPH-RFQ018 / Procure Strengthen the Government’ Request for Quota Single Stage - One E Under Imple ment of Spare Parts for the El IBRD / 87710 s capacity to respond to CO Post Open - National 75,000.00 0.00 2023-03-15 2023-03-15 2023-05-10 2023-11-06 tions nvelope mentation evators at Al Nabatieh Public VID-19 Hospital NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual LB-MOPH-164381-NC-UN / Pr Strengthen the Government’ UN Agencies (Dire ocurement of equipment and IBRD / 87710 s capacity to respond to CO Prior Direct 20,000,000.00 0.00 Canceled 2020-03-14 2020-03-19 2020-04-23 2020-10-20 ct) tools to respond to COVID-19 VID-19 LB-MOPH-164382-NC-WHO / Strengthen the Government’ UN Agencies (Dire Procurement of goods in resp IBRD / 87710 s capacity to respond to CO Prior Direct 6,000,000.00 5,562,071.99 Signed 2020-03-31 2020-04-01 2020-04-05 2020-04-01 2020-05-10 2020-04-04 2020-11-06 ct) onse to COVID19 VID-19 LB-MOPH-164385-NC-UNOPS Strengthen the Government’ UN Agencies (Dire / Procurement of PPEs and Eq IBRD / 87710 s capacity to respond to CO Prior Direct 9,500,000.00 5,742,367.72 Signed 2020-03-15 2020-04-01 2020-03-15 2020-04-03 2020-03-15 2020-04-03 2020-03-15 ct) uipments VID-19 LB-MOPH-RFQ019 / Procure Strengthening project mana Request for Quota Single Stage - One E Under Imple IBRD / 87710 Post Open - National 15,000.00 0.00 2023-04-15 2023-04-11 2023-06-10 2023-12-07 ment of an Antivirus Softwar gement and monitoring tions nvelope mentation e LB-MOPH-RFQ020 / Maintena Strengthening project mana Request for Quota Single Stage - One E Under Imple nce, Support and Update of t IBRD / 87710 Post Open - National 30,000.00 0.00 2023-05-27 2023-06-05 2023-07-22 2024-01-18 gement and monitoring tions nvelope mentation he Ministry Mobile Applicatio n LB-MOPH-RFQ021 / Provision Strengthening project mana Request for Quota Single Stage - One E Under Imple IBRD / 87710 Post Open - National 10,000.00 0.00 2023-06-06 2023-06-12 2023-08-01 2024-01-28 of SMS Services gement and monitoring tions nvelope mentation LB-MOPH-RFQ022 / Provision Strengthening project mana Request for Quota Single Stage - One E Pending Impl IBRD / 87710 Post Open - National 20,000.00 0.00 2023-06-12 2023-08-07 2024-02-03 of Landline Internet Services gement and monitoring tions nvelope ementation CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual LB-MOPH-159410-CS-QCBS / Strengthening project mana Quality And Cost- Open - Internationa IBRD / 87710 Prior 540,000.00 990,766.00 Signed 2020-02-14 2020-02-17 2020-03-06 2020-02-18 2020-04-19 2020-08-11 2020-05-17 2020-10-28 2020-06-16 2020-11-05 2020-07-21 2021-01-04 2020-08-25 2020-12-30 2021-08-25 Third-party agent gement and monitoring Based Selection l LB-MOPH-197566-CS-LCS / F Strengthening project mana Least Cost Selecti Open - Internationa IBRD / 87710 Post 36,000.00 50,870.00 Signed 2020-10-03 2020-10-02 2020-10-24 2020-10-07 2020-12-07 2021-03-31 2021-01-04 2021-07-02 2021-02-03 2021-06-05 2021-03-10 2021-06-23 2021-04-14 2021-08-13 2021-10-11 inancial Auditor gement and monitoring on l LB-MOPH-ICS-004 / Hiring of Strengthening project mana Consultant Qualifi Under Implement an Environmental and Social IBRD / 87710 Post Limited 18,000.00 0.00 2022-11-01 2022-11-08 2022-11-15 2023-02-01 2022-12-15 2023-01-19 2023-07-18 gement and monitoring cation Selection ation Specialist and Grievance Mec hanism Officer INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual HR-001-PROJECT MANAGER / Strengthening project mana IBRD / 87710 Post Direct Selection Direct 42,000.00 42,000.00 Signed 2020-05-14 2020-06-30 2020-05-24 2020-07-14 2020-07-28 2020-07-02 2021-01-24 Project Manager gement and monitoring HR-003-MONITORING AND E Strengthening project mana Individual Consult Under Implement IBRD / 87710 Post Limited 26,400.00 0.00 2020-06-12 2020-07-13 2020-06-17 2020-08-28 2020-07-08 2020-08-28 2020-08-12 2021-02-08 VALUATION / Monitoring and gement and monitoring ant Selection ation evaluation Page 2 HR-004-FINANCIAL OFFICER Strengthening project mana IBRD / 87710 Post Direct Selection Direct 26,400.00 55,440.00 Signed 2020-05-16 2020-07-13 2020-05-26 2020-07-14 2020-07-30 2020-07-02 2021-01-26 / Financial officer gement and monitoring HR-005-TRAINING AND COM Strengthening project mana Individual Consult Under Implement MUNICATION / Training and c IBRD / 87710 Post Limited 21,600.00 0.00 2020-06-12 2020-07-13 2020-06-17 2020-07-08 2020-08-12 2021-02-08 gement and monitoring ant Selection ation ommunication coordinator HR-006-OPERATIONS ASSIST Strengthening project mana Individual Consult IBRD / 87710 Post Limited 21,600.00 43,380.00 Signed 2020-06-12 2020-07-13 2020-06-17 2020-08-04 2020-07-08 2020-08-04 2020-08-12 2020-08-02 2021-02-08 ANT / Operations assistant gement and monitoring ant Selection LB-MOPH-188195-CS-CDS / T Strengthen the Government’ IBRD / 87710 Post Direct Selection Direct 10,000.00 204,620.70 Signed 2020-08-19 2020-09-02 2020-08-29 2020-09-03 2020-11-02 2020-08-27 2021-05-01 echnical audit for covid-19 co s capacity to respond to CO verage VID-19 LB-MOPH-191340-CS-INDV / Strengthening project mana Individual Consult IBRD / 87710 Post Limited 15,600.00 29,900.00 Signed 2020-09-02 2020-09-02 2020-09-07 2020-09-03 2020-09-28 2020-09-03 2020-11-02 2020-09-02 2021-05-01 Administrative Assistant gement and monitoring ant Selection LB-MOPH-191343-CS-INDV / Strengthening project mana Individual Consult IBRD / 87710 Post Limited 20,400.00 20,400.00 Signed 2020-09-02 2020-09-03 2020-09-07 2020-09-03 2020-09-28 2020-09-03 2020-11-02 2020-09-02 2021-05-01 Monitoring and Evaluation gement and monitoring ant Selection LB-MOPH-201928-CS-INDV / Strengthening project mana Individual Consult IBRD / 87710 Post Limited 18,000.00 0.00 Canceled 2020-10-28 2020-11-02 2020-11-02 2020-11-23 2020-12-28 2021-06-26 IT Analyst gement and monitoring ant Selection LB-MOPH-202741-CS-INDV / Strengthening project mana Individual Consult IBRD / 87710 Post Open 18,000.00 0.00 Canceled 2020-11-04 2020-11-05 2020-12-23 2021-01-13 2021-02-17 2021-08-16 IT Analyst gement and monitoring ant Selection LB-MOPH-ICM-001 / Selectio Strengthen the Government’ Pending Impleme IBRD / 87710 Post Direct Selection Direct 2,250.00 0.00 2020-11-27 2020-12-07 2021-02-10 2021-08-09 n of Isolation Center Manager s capacity to respond to CO ntation VID-19 LB-MOPH-ICM-002 / Selectio Strengthen the Government’ Pending Impleme IBRD / 87710 Post Direct Selection Direct 2,250.00 0.00 2020-11-30 2020-12-10 2021-02-13 2021-08-12 n of Isolation Center Manager s capacity to respond to CO ntation VID-19 LB-MOPH-ICM-003 / Selectio Strengthen the Government’ Pending Impleme IBRD / 87710 Post Direct Selection Direct 2,250.00 0.00 2020-11-30 2020-12-10 2021-02-13 2021-08-12 n of Isolation Center Manager s capacity to respond to CO ntation VID-19 LB-MOPH-ICM-004 / Selectio Strengthen the Government’ Pending Impleme IBRD / 87710 Post Direct Selection Direct 2,250.00 0.00 2020-11-30 2020-12-10 2021-02-13 2021-08-12 n of isolation center manager s capacity to respond to CO ntation VID-19 LB-MOPH-ICM-005 / Selectio Strengthen the Government’ Pending Impleme IBRD / 87710 Post Direct Selection Direct 2,250.00 0.00 2020-11-30 2020-12-10 2021-02-13 2021-08-12 n of Isolation Center Manager s capacity to respond to CO ntation VID-19 LB-MOPH-ICM-006 / Selectio Strengthen the Government’ Pending Impleme IBRD / 87710 Post Direct Selection Direct 2,250.00 0.00 2020-11-30 2020-12-10 2021-02-13 2021-08-12 n of Isolation Center Manager s capacity to respond to CO ntation VID-19 LB-MOPH-ICM-007 / Selectio Strengthen the Government’ Pending Impleme IBRD / 87710 Post Direct Selection Direct 2,250.00 0.00 2020-11-30 2020-12-10 2021-02-13 2021-08-12 n of Isolation Center s capacity to respond to CO ntation VID-19 LB-MOPH-ICM-008 / Selectio Strengthen the Government’ Pending Impleme IBRD / 87710 Post Direct Selection Direct 3,000.00 0.00 2020-11-30 2020-12-10 2021-02-13 2021-08-12 n of Isolation Center Manager s capacity to respond to CO ntation VID-19 LB-MOPH-ICS-001 / Selection Strengthening project mana Individual Consult Under Implement IBRD / 87710 Post Open 18,000.00 0.00 2021-01-11 2021-01-11 2021-03-01 2021-03-22 2021-04-26 2021-10-23 of an IT Analyst gement and monitoring ant Selection ation LB-MOPH-ICS-002 / Selection Strengthening project mana Individual Consult IBRD / 87710 Post Open 16,800.00 0.00 Signed 2021-06-08 2021-06-17 2021-07-27 2021-10-11 2021-08-17 2021-10-09 2021-09-21 2022-03-20 of a Financial Assistant gement and monitoring ant Selection HR-007-SENIOR CLINICAL M Strengthen the Government’ ANAGER / Hiring of a Senior T IBRD / 87710 s capacity to respond to CO Post Direct Selection Direct 9,600.00 19,200.00 Signed 2021-09-07 2021-09-14 2021-09-17 2021-10-07 2021-11-21 2021-09-09 2022-05-20 echnical and Clinical Manage VID-19 r for the Pharmacovigilance p rogram HR-008-CLINICAL PV OFFICE Strengthen the Government’ R / Hiring of a Clinical Pharm IBRD / 87710 s capacity to respond to CO Post Direct Selection Direct 8,400.00 16,800.00 Signed 2021-09-07 2021-09-14 2021-09-17 2021-10-07 2021-11-21 2021-09-09 2022-05-20 acovigilance Officer VID-19 HR-009-CLINICAL PV OFFICE Strengthen the Government’ Under Implement R / Hiring of a Clinical Pharm IBRD / 87710 s capacity to respond to CO Post Direct Selection Direct 8,400.00 0.00 2021-09-07 2021-09-14 2021-09-17 2021-11-21 2022-05-20 ation acovigilance Officer VID-19 HR-010-DATA OPERATOR / H Strengthen the Government’ iring of a Data Operator for t IBRD / 87710 s capacity to respond to CO Post Direct Selection Direct 4,800.00 9,600.00 Signed 2021-09-07 2021-09-14 2021-09-17 2021-10-07 2021-11-21 2021-09-09 2022-05-20 he Pharmacovigilance Progra VID-19 m HR-011-DATA OPERATOR / H Strengthen the Government’ iring of a Data Operator for t IBRD / 87710 s capacity to respond to CO Post Direct Selection Direct 4,800.00 9,600.00 Signed 2021-09-07 2021-09-14 2021-09-17 2021-10-07 2021-11-21 2021-09-09 2022-05-20 he Pharmacovigilance Progra VID-19 m LB-MOPH-ICS-003 / Hiring of Strengthening project mana Individual Consult Under Implement an Environmental and Social IBRD / 87710 Post Open 18,000.00 0.00 2022-03-17 2022-03-21 2022-05-05 2022-05-26 2022-06-30 2022-12-27 gement and monitoring ant Selection ation Specialist and Grievance Mec hanism Officer LB-MOPH-DS004 / Provision Strengthen the Government’ Under Implement IBRD / 87710 Post Direct Selection Direct - National 30,000.00 0.00 2022-09-23 2022-09-28 2022-10-03 2022-09-29 2022-12-07 2023-06-05 of Information Security Servi s capacity to respond to CO ation ces VID-19 LB-MOPH-ICS-005 / Hiring of Strengthening project mana Individual Consult Under Implement a Primary Health Care Techni IBRD / 87710 Post Open - National 20,400.00 0.00 2023-05-15 2023-05-16 2023-07-03 2023-07-24 2023-08-28 2024-02-24 gement and monitoring ant Selection ation cal Coordinator Page 3 REPUBLIC OF GUINEA BISSAU, REPUBLIC OF MALI, REPUBLIC OF THE GAMBIIA AND ECOWAS COMMISSION ECOWAS REGIONAL ELECTRICITY ACCESS PROJECT – P164044 I. General  Project: ECOWAS Regional Electricity Access Project (IDA CREDIT No. XXX  Project Implementation agency: Regional Coordination Unit - Directorate of Energy of ECOWAS COMMISSION  Project ID No: P164044  Date of General Procurement Notice: MM/DD/YYYY 1. Period covered by this Procurement Plan: August 2018 to February 2020 2. Preamble: In accordance with paragraph 5.9 of the “ World Bank Procurement Regulations for IPF Borrowers” (July 2016 revised November 2017) (“Procurement Regulations”) the Bank’ s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plan and conduct all procurement transactions for the Project. II. Goods, Works and Non-Consulting Services 1. List of contract packages to be procured: Prior review thresholds: Method Levels Comments 1. Goods >=US$1,500,000 Prior review 3. Works >= US$5,000,000 Prior review 1 2 3 4 5 6 7 Revie Estimate Expected w Ref Description d Selectio Proposals by Comment . of Cost n Submissio Bank s No. Assignment (USD Method n (Prior / Million) Date Post) Design, supply, install Supply 1 188 Prior 01-Sept-19 distribution install infrastructur e 2. Consulting Services Prior review thresholds: Selection method Prior review Comments level 1. Selection of firms >= US$500,000 Prior review 2. Selection of individual consultants >= US$200,000 Prior review 1 2 3 4 5 6 7 Review Estimated Expected by Ref. Description of Cost Selection Proposals Bank Comments No. Assignment (USD Method Submission (Prior / Million) Date Post) Owner’s 1 6 QCBS Prior 01-Aug-19 engineer PROCUREMENT Western and Central Africa : ECOWAS-Regional Electricity Access Project PLAN General Information Country: Western and Central Africa 2019-02-19 Bank’s Approval Date of the Original Procurement Plan: 2023-06-01 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P164044 GPN Date: 2018-10-08 Project Name: ECOWAS-Regional Electricity Access Project Loan / Credit No: IDA / D4070, IDA / D4080 NATIONAL WATER AND ELECTRICITY COMPANY Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GM-NAWEC-102784-CW-RFB Program coordination and te Single Stage - One E 2020-04-1 / Rehabilitation and Extensio IDA / D4070 Post Request for Bids Open - National 100,000.00 0.00 Canceled 2019-06-27 2019-07-02 2019-08-13 2019-09-12 2019-10-17 chnical assistance nvelope 4 n of Office Space for NAWEC Project GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GM-NAWEC-102791-GO-RFQ / Procurement and Supply of Program coordination and te Request for Quota Single Stage - One E IDA / D4070 Post Limited 30,000.00 0.00 Canceled 2019-06-29 2019-08-24 2020-02-20 office equipment for the Proj chnical assistance tions nvelope ect Implementation Unit GM-NAWEC-102787-GO-RFB / Procurement and Supply of Program coordination and te Request for Quota Single Stage - One E Under Imple IDA / D4070 Post Limited 50,000.00 0.00 2019-06-17 2019-07-15 2019-08-12 2020-02-08 one(1) motor vehicles for Pro chnical assistance tions nvelope mentation ject Implementation Unit NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GM-NAWEC-158928-NC-DIR / Program coordination and te Procurement of PSSE Softwar IDA / D4070 Post Direct Selection Direct 41,819.77 37,131.79 Signed 2020-02-16 2020-02-11 2020-02-21 2020-02-24 2020-03-27 2020-07-07 2020-09-23 chnical assistance e and Training CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GM-NAWEC-124909-CS-CQS / Environmental and Social I Program coordination and te Consultant Qualifi IDA / D4070 Post Limited 80,000.00 75,470.69 Signed 2019-07-31 2019-07-31 2019-08-14 2019-10-02 2019-09-13 2020-01-20 2019-10-18 2020-02-01 2020-04-15 mpact Assessment/ Environ chnical assistance cation Selection mental and Social Manageme nt Plan GM-NAWEC-124953-CS-CQS Supervision of the constructi Consultant Qualifi IDA / D4070 Post Limited 50,000.00 48,703.26 Signed 2019-07-31 2019-07-31 2019-08-14 2019-10-02 2019-09-13 2020-01-20 2019-10-18 2020-02-01 2020-04-15 / Resettlement Action Plan on and technical advisory cation Selection GM-NAWEC-153220-CS-LCS / Supervision of the constructi Least Cost Selecti Open - Internationa External Auditor for ECOWAS IDA / D4070 Post 150,000.00 0.00 Canceled 2020-01-09 2020-02-04 2020-01-30 2020-03-14 2020-06-29 2020-04-11 2020-09-01 2020-05-11 2020-09-29 2020-06-15 2020-10-14 2020-07-20 2021-01-16 on and technical advisory on l Regional Electricity Access Pr oject GM-NAWEC-153220-CS-LCS- Supervision of the constructi Least Cost Selecti Open - Internationa BIS / External Auditor for ECO IDA / D4070 Post 150,000.00 32,771.09 Signed 2020-12-11 2020-12-14 2021-01-01 2021-02-14 2021-02-15 2021-03-14 2021-03-25 2021-04-13 2021-03-30 2021-05-18 2021-04-19 2021-06-22 2021-05-18 2021-12-19 on and technical advisory on l WAS Regional Electricity Acc ess Project GM-NAWEC-217659-CS-CQS / Consultancy Service for the Supervision of the constructi Consultant Qualifi IDA / D4070 Post Open - National 40,000.00 0.00 Canceled 2021-02-17 2021-09-01 2021-03-10 2021-11-02 2021-04-23 2022-02-10 2021-05-23 2021-06-27 2021-12-24 Design and Supervision for th on and technical advisory cation Selection e Construction of Project Offi ce GM-NAWEC-311925-CS-LCS / Consultancy Service for the Supervision of the constructi Least Cost Selecti Open - Internationa IDA / D4070 Post 80,000.00 0.00 Canceled 2022-08-31 2022-09-21 2022-11-04 2022-12-02 2023-01-01 2023-02-05 2023-03-12 2023-09-08 Design and Supervision for th on and technical advisory on l e Construction of Project Offi ce GM-NAWEC-315674-CS-LCS / DESIGN, PREPARATION OF T HE TENDER DOCUMENTS PLU Supervision of the constructi Least Cost Selecti Open - Internationa Under Implement IDA / D4070 Post 80,000.00 0.00 2022-09-27 2022-09-27 2022-10-18 2022-11-07 2022-12-01 2022-12-29 2023-01-28 2023-03-04 2023-04-08 2023-10-05 S SUPERVISION OF THE WOR on and technical advisory on l ation KS FOR THE PROPOSED EDG E-CERTIFIED PROJECT OFFICE BUILDING AT KOTU GM-NAWEC-348394-CS-CQS / Develop a plan to Implemen Supervision of the constructi Consultant Qualifi Open - Internationa Under Implement IDA / D4080 Post 75,000.00 0.00 2023-03-23 2023-04-06 2023-04-13 2023-05-23 2023-05-27 2023-06-26 2023-07-31 2024-01-27 t the Resettlement Action Pla on and technical advisory cation Selection l ation n (RAP) for Additional Village s - (ECO-REAP) GM-NAWEC-364342-CS-CQS Design, supply and installati / Detailed Design and Suppor Consultant Qualifi Open - Internationa Under Implement IDA / D4080 on of electricity distribution i Post 200,000.00 0.00 2023-06-15 2023-06-12 2023-07-06 2023-08-19 2023-09-18 2023-10-23 2024-04-20 t through Bidding Process for cation Selection l ation nfrastructure Additional Villages INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 1 GAM-PIU/EREAP/SERVICES/C Program coordination and te Individual Consult 2/04 / Recruitment of an Envi IDA / D4070 Post Open 120,000.00 1,966.32 Terminated 2019-01-31 2019-03-22 2019-03-21 2019-04-09 2019-04-11 2019-05-16 2019-05-16 2019-05-17 2019-11-12 chnical assistance ant Selection ronmental Specialist GAM-PIU/EREAP/SERVICES/C Program coordination and te Individual Consult IDA / D4070 Post Limited 120,000.00 1,966.32 Terminated 2019-02-27 2019-03-22 2019-03-04 2019-04-01 2019-03-25 2019-04-11 2019-04-29 2019-04-26 2019-10-26 2/06 / Recruitment of a Powe chnical assistance ant Selection r Engineer GAM-PIU/EREAP/SERVICES/C Program coordination and te Individual Consult IDA / D4070 Post Open 120,000.00 0.00 Canceled 2019-01-31 2019-04-18 2019-03-21 2019-04-11 2019-05-16 2019-11-12 2/05 / Recruitment of a Socia chnical assistance ant Selection l Specialist GM-NAWEC-119405-CS-INDV Supervision of the constructi Individual Consult IDA / D4070 Post Limited 50,000.00 0.00 Canceled 2019-06-28 2019-07-18 2019-07-03 2019-10-01 2019-07-24 2019-08-28 2020-02-24 / Resettlement Action Plan on and technical advisory ant Selection GM-NAWEC-97517-CS-INDV / Supervision of the constructi Individual Consult IDA / D4070 Prior Limited 120,000.00 0.00 Canceled 2019-02-28 2019-03-05 2019-03-26 2019-04-30 2019-10-27 Procurement Officer on and technical advisory ant Selection GM-NAWEC-102800-CS-INDV / Environmental and Social I Program coordination and te Individual Consult IDA / D4070 Post Limited 80,000.00 0.00 Canceled 2019-06-19 2019-07-25 2019-06-24 2019-07-15 2019-08-19 2020-02-15 mpact Assessment/ Environ chnical assistance ant Selection mental and Social Manageme nt Plan GM-NAWEC-124973-CS-INDV Supervision of the constructi Individual Consult IDA / D4070 Prior Open 50,000.00 26,395.42 Signed 2019-08-02 2019-09-10 2019-09-20 2020-04-21 2019-10-11 2020-06-19 2019-11-15 2020-06-01 2020-05-13 / Procurement Officer on and technical advisory ant Selection GM-NAWEC-155108-CS-INDV Program coordination and te Individual Consult IDA / D4080 Post Open 50,000.00 974.83 Signed 2020-02-28 2020-02-24 2020-04-17 2020-05-04 2020-05-08 2020-05-18 2020-06-12 2020-07-02 2020-12-09 / Project Accountant chnical assistance ant Selection GM-NAWEC-166067-CS-INDV Program coordination and te Individual Consult IDA / D4070 Post Open 108,314.00 25,504.00 Completed 2020-03-31 2020-05-18 2020-05-19 2020-10-14 2020-06-09 2020-10-19 2020-07-14 2020-11-04 2021-01-10 2021-12-01 / Environmental Specialist chnical assistance ant Selection GM-NAWEC-191894-CS-CDS Program coordination and te Individual Consult IDA / D4070 Post Open 125,000.00 369,617.75 Signed 2020-09-17 2020-09-14 2020-11-05 2020-10-15 2020-11-26 2020-10-20 2020-12-31 2020-10-24 2021-06-29 / Senior Power Engineer for P chnical assistance ant Selection IU GM-NAWEC-230911-CS-INDV Program coordination and te Individual Consult / Recruitment of a Junior Pow IDA / D4080 Post Open 1,500.00 0.00 Canceled 2021-04-30 2021-04-26 2021-06-18 2021-07-09 2021-08-13 2022-02-09 chnical assistance ant Selection er Engineer for PIU GM-NAWEC-254819-CS-INDV Program coordination and te Individual Consult / Recruitment of a Junior Pow IDA / D4080 Post Open 80,000.00 37,967.07 Signed 2021-09-30 2021-10-11 2021-11-18 2022-01-20 2021-12-09 2022-03-24 2022-01-13 2022-04-01 2022-07-12 chnical assistance ant Selection er Engineer for Project Imple mentation Unit GM-NAWEC-275370-CS-INDV Program coordination and te Individual Consult IDA / D4070 Post Open 95,850.00 0.00 Signed 2022-02-09 2022-05-18 2022-03-30 2022-09-20 2022-04-20 2022-10-10 2022-05-25 2022-11-21 / Environmental Safeguard S chnical assistance ant Selection pecialist GM-NAWEC-275376-CS-INDV Program coordination and te Individual Consult IDA / D4070 Post Open 95,850.00 0.00 Signed 2022-02-09 2022-04-29 2022-03-30 2022-09-29 2022-04-20 2022-10-06 2022-05-25 2022-11-21 / Social Safeguard Specialist chnical assistance ant Selection GM-NAWEC-306109-CS-INDV Supervision of the constructi Direct - Internation / Project and Contract Manag IDA / D4070 Post Direct Selection 65,000.00 65,000.00 Signed 2022-08-05 2022-08-30 2022-08-15 2022-09-05 2022-10-19 2022-09-24 2023-04-17 on and technical advisory al ement Advisor Page 2 1. Procurement Plan. Textual part Preamble 1. In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (Fourth Edition, November 2020) (“Procurement Regulations”), the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. 2. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. 3. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements 4. In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), procurement under World Bank financed operations may be carried out in accordance with “Tendering with Unlimited Participation” method set forth in the Law of the Republic of Tajikistan “Оn Public Procurement of Goods, Works and Services”, # 168 dated March 3, 2006 (as amended by Law #815, the “Law of the Republic of Tajikistan on “Introduction of Amendments and Additions to the Law of the Republic of Tajikistan on ‘Public Procurement of Goods, Works and Services’” dated April 16, 2012), provided that such arrangements continue to meet requirements of the paragraph 5.4 of the Procurement Regulations and the following conditions: • The request for bids/request for proposals document shall require that bidders/proposers submitting bids/proposals present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, World Bank Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights; • The request for bids/request for proposals document, including contract forms, acceptable to the Bank shall be used. • The request for bids/request for proposals document and contract shall provide the right to the Bank to review procurement documentation and activities. • Borrower shall put in place an effective complaints review mechanism with procurement related complaints and shall disclose the details in all the bidding documents. All complaints shall be recorded by the Borrower in the appropriate tracking and monitoring system, as agreed between the Bank and the Borrower. • No preference shall be applied under competitive bidding following national market approach. 5. Other national procurement arrangements such as tendering with limited participation, request for quotations, direct contracting, may be used on the above stated conditions. 6. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: “Not Applicable.” 7. Procurement of Second-Hand Goods as specified under paragraph 5.11 of the Procurement Regulations “Not Applicable.” 8. Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works): “Not Applicable.” 2. Procurement Plan for the project duration Start Comp-onent Contract title, Estimat Bank Procurem Selecti Evaluation date Description and ed cost over ent on method: s(Pre Category (US$) sight approach metho limin / ds ary): Competiti on Goods &NCS Equipment in support of plant breeding and variety evaluation programs including irrigation Substantially equipment, farming machinery for the responsive and C1 Tajik Academy of Agricultural 470,000.00 Post National, Open RFB 2023 lowest evaluated Sciences (TAAS) institutes: Pamir cost Institute, Institute of Horticulture, Viticulture and Vegetable Growing, Farming Institute Equipment in support of the storage and maintenance of germplasm Substantially including freezers for long-term responsive and C1 germplasm storage, irrigation 80,000.00 Post National, Open RFQ 2023 lowest evaluated equipment, farm machinery for cost National Republican Center for Genetic Resources C1 Equipment in support of plant 100,000.00 Post National, Open RFQ Substantially 2023 breeding and variety evaluation responsive and programs including irrigation lowest evaluated equipment, farming machinery for cost Center for Innovation and Mechanization of Agriculture Equipment in support of plant breeding, in vitro laboratory Substantially equipment, irrigation equipment, responsive and C1 680,000.00 Post National, Open RFB 2023 farming machinery for Scientific lowest evaluated Research Institute of Biotechnology cost of Tajik Agrarian University (TAU) Equipment in support of seed, seedling and planting material propagation, including cleaning, Substantially processing, packaging, quality responsive and C1 780,000.00 Post National, Open RFB 2023 monitoring for institutes of the TAAS: lowest evaluated Pamir Institute, Institute of cost Horticulture, Viticulture and Vegetable Growing, Farming Institute Equipment in support of seed, seedling and planting material quality control including laboratory Substantially equipment, field and greenhouse responsive and C1 equipment and field equipment for 280,000.00 Post National, Open RFB 2023 lowest evaluated use in surveillance of material cost produced in the field and sold into the market for Central Seed Laboratory of TAAS Equipment in support of seed, seedling and planting material quality control including laboratory Substantially equipment, field and greenhouse responsive and C1 equipment and field equipment for 540,000.00 Post National, Open RFB 2022 lowest evaluated use in surveillance of material cost produced in the field and sold into the market for Regional Quality Control Facilities Office and IT equipment for TAAS institutes: Pamir Institute, Institute of Horticulture, Viticulture and Vegetable Growing, Farming Substantially Institute, National Republican Center responsive and C1 430,000.00 Post National, Open RFB 2023 for Genetic Resources, Center for lowest evaluated Innovation and Mechanization of cost Agriculture, Central Seed Laboratory of TAAS, Regional Quality Control Facilities Procurement of cotton seeds of the Substantially elite and super elite categories for Prior International, responsive and C1 5,200,000.00 RFB 2022 production of categories and for Open lowest evaluated reproduction in seed farms cost Procurement of potato seeds of the Substantially elite and super elite categories for Prior International, responsive and C1 5,200,000.00 RFB 2022 production of categories and for Open lowest evaluated reproduction in seed farms cost Procurement of wheat seeds of the Substantially elite and super elite categories for Prior International, responsive and C1 5,155,000.00 RFB 2022 production of categories and for Open lowest evaluated reproduction in seed farms cost Procurement of corn seeds of the Substantially elite and super elite categories for International, responsive and C1 200,000 Post RFB 2022 production of categories and for Open lowest evaluated reproduction in seed farms cost Substantially Equipment (Pre-cooling, sorting, International, responsive and C2 grading, packing lines, cold storage) 1,280,000.00 Post RFB 2023 Open lowest evaluated for ALCs cost Substantially ALCs Operational Management responsive and C2 99,000.00 Post National, Open RFQ 2023 software lowest evaluated cost Purchase of satellite images for soil Substantially remote sensing responsive and C3 250,000.00 Post National, Open RFB 2022 lowest evaluated cost Digital data processing, creation of Substantially agricultural and thematic maps for responsive and C3 633,000.00 Post National, Open RFB 2023 forecasting lowest evaluated cost C3 Equipment for Data Center for MOA 150,000.00 Post National, Open RFB Substantially 2023 (Digital archive SDW) responsive and lowest evaluated cost Software (GIS Server, 3D GIS, GIS and Substantially 3 D GIS editing tools, SUBDD) responsive and C3 200,000.00 Post National, Open RFB 2023 lowest evaluated cost Hardware (Server, Web APP, storage, Substantially Plotter, Scanner, Printers, Notebooks, responsive and C3 450,000.00 Post National, Open RFB 2022 Displays, switchers, brandmauer, lowest evaluated network equipment, computers) cost Drones for aero photography and Substantially monitoring responsive and C3 200,000.00 Post National, Open RFB 2022 lowest evaluated cost Diesel generator (1) Substantially responsive and C3 20,000.00 Post National, Open RFQ 2022 lowest evaluated cost Mobile agrometeorological stations Substantially (12) responsive and C3 60,000.00 Post National, Open RFQ 2022 lowest evaluated cost Equipment for MOA to support Substantially monitoring and planning of responsive and C3 500,000.00 Post National, Open RFB 2022 agriculture lowest evaluated cost Office and computer equipment for Substantially TAAS and TAU responsive and C3 200,000.00 Post National, Open RFB 2023 lowest evaluated cost Vehicles (5 for PMU AED, 6 for Center Substantially for Digital Development of responsive and C3 Agriculture (1), for Soil Management 401,550.00 Post National, Open RFB 2022 lowest evaluated Research Institute (1), for Crop cost Protection Unit (1) for Agrokhims (3)) Laboratory equipment for Agrokhim Substantially soil laboratories: (3), Laboratory responsive and C3 equipment, Mobile soil testing 1,010,000.00 Post National, Open RFB 2023 lowest evaluated laboratory (2), Soil Doctor kits for Soil cost Management Research Institute Laboratory materials for Agrokhim Substantially soil laboratories, Soil Management responsive and C3 430,000.00 Post National, Open RFB 2023 Research Institute, and Crop lowest evaluated Protection Unit cost Equipment for Technical Substantially modernization of Agrokhim soil responsive and C3 400,000.00 Post National, Open RFB 2022 laboratories (Establishment of digital lowest evaluated soil testing database) cost Office &IT equipment for Crop Substantially Protection Unit responsive and C3 200,000.00 Post National, Open RFB 2023 lowest evaluated cost Equipment for Crop protection Substantially laboratories in 4 regions and Special International, responsive and C3 1,600,000.00 Post RFB 2022 safety equipment/tools for Crop Open lowest evaluated Protection Unit cost Import of plant protection products Substantially for control and prevention of diseases responsive and C3 200,000.00 Post National, Open RFB 2022 lowest evaluated cost Equipment for mechanical and Substantially manual control of locust, equipment responsive and C3 800,000.00 Post National, Open RFB 2022 and tools for staff engaged in locust lowest evaluated control cost Chemicals for locust control Substantially responsive and C3 1,050,000.00 Post National, Open RFB 2022 lowest evaluated cost Utilization of remaining chemicals Substantially and materials responsive and C3 60,000.00 Post National, Open RFQ 2022 lowest evaluated cost Substantially Office Equipment and furniture (for responsive and C4 133,850.00 Post National, Open RFB 2022 PMU AED & two regional offices) lowest evaluated cost TBA 1,886,600.00 31,329,000. Sub-Total 00 Works Renovation/construction of buildings, structures and facilities in support of plant breeding and variety evaluation Substantially programs, storage facilities, and responsive and C1 660,000.00 Post National, Open RFB 2022 greenhouses of institutes of the lowest evaluated TAAS: Pamir Institute, Institute of cost Horticulture, Viticulture and Vegetable Growing, Farming Institute Renovation/construction of buildings, structures and facilities in support of Substantially the storage and maintenance of responsive and C1 germplasm including specialized seed 210,000.00 Post National, Open RFB 2022 lowest evaluated room and greenhouse for germplasm cost maintenance of National Republican Center for Genetic Resources Renovation/construction of buildings, structures and facilities in support of Substantially plant breeding and variety evaluation responsive and C1 40,000.00 Post National, Open RFQ 2022 programs including storage facilities lowest evaluated of Center for Innovation and cost Mechanization of Agriculture Renovation/construction of buildings, structures and facilities in support of Substantially plant breeding and variety evaluation responsive and C1 930,000.00 Post National, Open RFB 2022 programs including storage facilities lowest evaluated of Center for Innovation and cost Mechanization of Agriculture Renovation/construction of buildings, structures and facilities in support of seed, seedling and plant material multiplication including for cleaning, Substantially processing, packaging and storage, responsive and C1 including upgrade of existing facilities 600,00.00 Post National, Open RFB 2022 lowest evaluated in addition to the construction of cold cost storage facilities of institutes of the TAAS: Pamir Institute, Institute of Horticulture, Viticulture and Vegetable Growing, Farming Institute Renovation/construction of buildings, Substantially structures and facilities in support of responsive and C1 350,000.00 Post National, Open RFB 2022 seed, seedling and plant material lowest evaluated quality control. cost Construction of Regional Quality Substantially Control Facilities (3) responsive and C1 1,300,000.00 Post National, Open RFB 2022 lowest evaluated cost Construction of ALC near Dushanbe Substantially responsive and C2 4,700,000.00 Post National, Open RFB 2023 lowest evaluated cost Construction of ALC in Khatlon Substantially responsive and C2 4,600,000.00 Post National, Open RFB 2023 lowest evaluated cost Construction of ALC in Sughd Substantially responsive and C2 4,700,000.00 Post National, Open RFB 2023 lowest evaluated cost Renovation of the Center for Digital Substantially Development of Agriculture responsive and C3 400,000.00 Post National, Open RFB 2022 lowest evaluated cost Repair of Agrokhim soil laboratories Substantially (3) responsive and C3 300,000.00 Post National, Open RFB 2023 lowest evaluated cost Repair of building of Soil Substantially Management Research Institute responsive and C3 100,000.00 Post National, Open RFQ 2023 lowest evaluated cost Repair of buildings of the crop Substantially protection unit responsive and C3 125,000.00 Post National, Open RFQ 2023 lowest evaluated cost Substantially Renovation of AED PMU office responsive and C4 20,000.00 Post National, Open RFQ 2022 lowest evaluated cost TBA 89,000.00 19,124,000. Sub-Total 00 Consultants Technical support and capacity Based on C1 building on plant breeding, crop 72,000.00 Post National, Open CQS 2023 qualification propagation, plant diseases, irrigation Strategic contract covering the following areas: (i) support for improving seed policies and legislation; (ii) update the seed quality standards, aligning them with international standards; (iii) training MOA and Food Security Committee staff on seed quality assurance; (iv) support to introduce best practices for multiplication of seed, seedling and planting material on seed farms and nurseries; (v) supervision and monitoring of seed production on seed multiplication farms; (vi) awareness raising campaign with farmers on improved seeds; (vi) design and establishment of the C1 database for real-time agricultural 2,500,000.00 Prior Direct (UNFAO) DS Direct Selection 2023 sector monitoring and agricultural production forecasting; (vii) development of information products using agrometeorological information and development of mechanisms to disseminate it to farmers; (viii) supporting the improvement of quality of soil tests, preparation of agro-technological maps, and methodologies for testing various soil types; (ix) capacity building on crop protection and locust control; and (x) preparation of technical specifications for specialized equipment on seeds, real-time monitoring, soil testing, and crop protection. Needs assessment for renovation work and development of design and detailed cost estimates: Based on C1 170,000.00 Post National, Open CQS 2022 1. Research institutes of TAAS qualification 2. TAU 3. Centers and agencies of the MoA Preparation of the list and technical specifications of equipment for technical modernization: Based on C1 70,000.00 Post National, Open CQS 2022 1. Research institutes of TAAS qualification 2. TAU 3. Centers and agencies of the MoA Feasibility study - business plan - Based on C2 213,000.00 Post National, Open CQS 2022 ESIA / qualification Detailed design/cost estimate for International, Based on C2 489,000.00 Post QCBS 2022 three ALCs and supervision of works Open qualification On-site specialized training of the Based on C2 104,000.00 Post National, Open CQS 2025 staff operating the ALCs qualification Lawyer to prepare documents on legal changes of the SOE "Center for Individual C3 Staff Capacity Building" under MOA 10,000.00 Post National, Open IC 2022 Consultant into the Center for Digital Development of Agriculture C3 Forecasting the yield of agricultural 750,000.00 Post International, QCBS Most 2022 production through the introduction Open advantageous of digital technologies Proposal Detailed design of the Center for Based on C3 300,000.00 Post National, Open CQS 2022 Digital Development of Agriculture qualification Baseline study of the project Based on C4 90,000.00 Post National, Open CQS 2022 qualification Mid-term review Based on C4 70,000.00 Post National, Open CQS 2024 qualification Final review Based on C4 60,000.00 Post National, Open CQS 2027 qualification Grievance Redress Mechanism Based on C4 90,000.00 Post National, Open CQS 2022 qualification International Audit (Block audit. To be International, Based on the C4 conducted by State Investment 66,000.00 Post LCS 2023 Open lowest cost Committee) Individual Consultants 46,000.00 Sub-Total 5,100,000.0 0 Total 55,553,000. 00 PROCUREMENT Tajikistan : Strengthening Resilience of the Agriculture Sector Project PLAN General Information Country: Tajikistan Bank’s Approval Date of the Original Procurement Plan: 2022-02-24 Revised Plan Date(s): (comma delineated, leave blank if 2023-06-05 none) Project ID: P175952 GPN Date: Project Name: Strengthening Resilience of the Agriculture Sector Project Loan / Credit No: IDA / D8600, IDA / E1450 Project Implementation Unit under the Ministry of Agriculture of the Republic of Tajikistan Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned National Procure TJ-SRASP-RFB-CW02 / Renov Strengthening seed, seedlin ment Document - ation/construction of building Pending Imp 2023-11-1 IDA / D8600 g and planting material syst Post Request for Bids 1 Envelope proce 210,000.00 0.00 2022-07-21 2022-07-26 2022-09-06 2022-10-06 2022-11-10 s, structures of National Rep lementation 6 ems ss (Non Bank-SPD ublican Center for Genetic Re ) sources TJ-SRASP-RFB-CW03 / Renov National Procure ation/construction of building Strengthening seed, seedlin ment Document - Single Stage - One E Pending Imp 2024-02-0 s, structures of Tajik Agrarian IDA / D8600 g and planting material syst Post Request for Bids Open - National 1 Envelope proce 930,000.00 0.00 2022-09-10 2022-09-10 2022-10-22 2022-11-21 2022-11-27 nvelope lementation 9 University, Scientific Researc ems ss (Non Bank-SPD h Institute of Biotechnology ) National Procure TJ-SRASP-RFB-CW06 / Constr Strengthening seed, seedlin ment Document - Single Stage - One E Pending Imp 2023-07-0 uction Regional Quality Contr IDA / D8600 g and planting material syst Post Request for Bids Open - National 1 Envelope proce 1,300,000.00 0.00 2022-10-22 2022-10-22 2022-11-22 2022-12-22 2023-01-03 nvelope lementation 2 ol Facilities (3) ems ss (Non Bank-SPD ) TJ-SRASP-RFQ-CW02 / Repair Strengthen public capacity f Request for Quota Request for Quota Single Stage - One E Pending Imp 2024-01-2 of building of Soil Manageme IDA / D8600 or crises prevention and ma Post Open - National tions (Non Bank-S 100,000.00 0.00 2023-03-13 2023-05-02 tions nvelope lementation 7 nt Research Institute nagement PD) Request for Quota TJ-SRASP-RFQ-CW03 / Repair Strengthen public capacity f Request for Quota Single Stage - One E Pending Imp 2023-11-2 IDA / D8600 Post Open - National tions (Non Bank-S 125,000.00 0.00 2023-04-05 2023-05-30 of buildings of the crop prote or crises prevention and ma tions nvelope lementation 6 PD) ction unit nagement Request for Quota TJ-AED PIU-303693-CW-RFQ Strengthen public capacity f Request for Quota Single Stage - One E Under Imple 2022-11-0 IDA / D8600 Post Open - National tions (Non Bank-S 96,000.00 0.00 2022-08-28 2022-10-02 / Construction of "Garden of or crises prevention and ma tions nvelope mentation 1 PD) Friendship" nagement TJ-SRASP-RFB-CW04 / Renov National Procure ation/construction of building Strengthening seed, seedlin ment Document - s, structures including upgr Single Stage - One E Pending Imp 2024-04-0 IDA / D8600 g and planting material syst Post Request for Bids Open - National 1 Envelope proce 600,000.00 0.00 2022-10-21 2022-10-21 2022-11-20 2022-12-04 2023-01-08 ade of existing facilities in ad nvelope lementation 2 ems ss (Non Bank-SPD dition to the construction of c ) old storage facilities of institu tes of the TAAS National Procure TJ-SRASP-RFB-CW11 / Repair Strengthen public capacity f Single Stage - One E ment Document - Pending Imp 2024-02-1 e of Agrokhim soil laboratorie IDA / D8600 or crises prevention and ma Post Request for Bids Open - National 300,000.00 0.00 2023-05-30 2023-06-04 2023-07-04 2023-08-03 2023-08-17 nvelope 1 Envelope proce lementation 3 s (3) nagement ss (Non Bank-SPD ) TJ-SRASP-RFQ-CW01 / Renov Strengthening seed, seedlin Request for Quota ation/construction of building Request for Quota Single Stage - One E Pending Imp 2023-09-2 IDA / D8600 g and planting material syst Post Open - National tions (Non Bank-S 40,000.00 0.00 2023-05-20 2023-07-01 s, structures of Center for Inn tions nvelope lementation 9 ems PD) ovation and Mechanization of Agriculture National Procure TJ-SRASP-RFB-CW09 / Constr Support investments in Agri- ment Document - Single Stage - One E Pending Imp 2024-01-1 uction of agro-logistics cente IDA / D8600 Logistical Centers (ALCs) for Post Request for Bids Open - National 1 Envelope proce 3,770,000.00 0.00 2023-03-31 2023-04-05 2023-05-17 2023-06-16 2023-07-21 nvelope lementation 7 r in Sughd horticulture value chains ss (Non Bank-SPD ) National Procure TJ-SRASP-RFB-CW10 / Renov Strengthen public capacity f ment Document - Single Stage - One E Pending Imp 2023-11-0 ation of the Center for Digital IDA / D8600 or crises prevention and ma Post Request for Bids Open - National 1 Envelope proce 400,000.00 0.00 2023-05-10 2023-05-15 2023-06-14 2023-07-14 2023-08-04 nvelope lementation 2 Development of Agriculture nagement ss (Non Bank-SPD ) TJ-SRASP-RFB-CW05 / Renov National Procure ation/construction of building Strengthening seed, seedlin ment Document - Single Stage - One E Pending Imp 2023-04-0 s, structures and facilities in IDA / D8600 g and planting material syst Post Request for Bids Open - National 1 Envelope proce 350,000.00 0.00 2022-06-20 2022-06-25 2022-08-06 2022-09-05 2022-10-10 nvelope lementation 8 support of seed, seedling and ems ss (Non Bank-SPD plant material quality control ) . National Procure TJ-SRASP-RFB-CW08 / Constr Support investments in Agri- ment Document - Single Stage - One E Pending Imp 2023-11-1 uction of agro-logistics cente IDA / D8600 Logistical Centers (ALCs) for Post Request for Bids Open - National 1 Envelope proce 3,770,000.00 0.00 2023-01-31 2023-02-05 2023-03-19 2023-04-18 2023-05-23 nvelope lementation 9 r in Khatlon horticulture value chains ss (Non Bank-SPD ) National Procure TJ-SRASP-RFB-CW01 / Recon Strengthening seed, seedlin ment Document - struction / construction of str Single Stage - One E Pending Imp 2024-02-1 IDA / D8600 g and planting material syst Post Request for Bids Open - National 1 Envelope proce 660,000.00 0.00 2023-05-19 2023-05-24 2023-07-05 2023-08-04 2023-08-18 uctures, institutes of the Taji nvelope lementation 4 ems ss (Non Bank-SPD k Academy of Agricultural Sci ) ences (TAAS) . National Procure TJ-SRASP-RFB-CW07 / Constr Support investments in Agri- ment Document - Single Stage - One E Pending Imp 2024-05-0 uction of agro-logistics cente IDA / D8600 Logistical Centers (ALCs) for Post Request for Bids Open - National 1 Envelope proce 3,841,000.00 0.00 2023-07-21 2023-07-26 2023-09-06 2023-10-06 2023-11-10 nvelope lementation 8 r near Dushanbe horticulture value chains ss (Non Bank-SPD ) TJ-AED PIU-358146-CW-RFB / National Procure Construction of overhaul war Strengthening seed, seedlin ment Document - Single Stage - One E Under Imple 2023-12-2 ehouses and renovation of b IDA / D8600 g and planting material syst Post Request for Bids Open - National 1 Envelope proce 990,000.00 0.00 2023-06-12 2023-05-19 2023-06-17 2023-05-20 2023-07-29 2023-08-28 2023-09-25 nvelope mentation 4 uildings for project beneficiar ems ss (Non Bank-SPD ies (research institutions und ) er TAAS and MoA) Request for Quota TJ-SRASP-RFQ-CW04 / Renov Project management and co Request for Quota Single Stage - One E Pending Imp 2023-09-2 IDA / D8600 Post Open - National tions (Non Bank-S 20,000.00 0.00 2023-06-10 2023-07-30 ation of SRASP PMU office ordination tions nvelope lementation 9 PD) GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TJ-SRASP-PIU-RFB-01 / Procu rement of cotton seeds of th Strengthening seed, seedlin Single Stage - One E e Flesh, Karisma and BA 440 IDA / D8600 g and planting material syst Post Request for Bids Open - National 400,000.00 0.00 Canceled 2022-02-04 2022-02-04 2022-02-09 2022-03-18 2022-02-18 2022-03-22 2022-04-26 2022-05-23 nvelope for production of categories a ems nd for reproduction in seed f arms TJ-SRASP-RFQ-G03 / ALCs Op Support investments in Agri- Request for Quota Single Stage - One E Pending Impl erational Management softw IDA / D8600 Logistical Centers (ALCs) for Post Open - National 99,000.00 0.00 2023-11-05 2023-12-31 2024-06-28 tions nvelope ementation are horticulture value chains Page 1 TJ-SRASP-RFQ-G04 / Diesel g Strengthen public capacity f Request for Quota Single Stage - One E Pending Impl IDA / D8600 Post Open - National 20,000.00 0.00 2022-07-16 2022-09-10 2023-01-08 enerator (1) or crises prevention and ma tions nvelope ementation nagement TJ-SRASP-RFB-G22 / Labotar atory materials for Agrokhim Strengthen public capacity f Single Stage - One E Pending Impl soil laboratories, for Soil Man IDA / D8600 or crises prevention and ma Post Request for Bids Open - National 430,000.00 0.00 2023-07-31 2023-08-05 2023-09-16 2023-10-16 2023-11-20 2024-05-18 nvelope ementation agement Research Institute, nagement and for Crop Protection Unit TJ-SRASP-PIU-RFB-02 / Procu rement of potato seeds of th Strengthening seed, seedlin Single Stage - One E e Romance, Bigroza and Cro IDA / D8600 g and planting material syst Post Request for Bids Open - National 560,000.00 540,880.00 Signed 2022-02-04 2022-02-04 2022-02-09 2022-02-18 2022-02-18 2022-02-25 2022-03-15 2022-03-07 2022-04-15 2022-04-05 nvelope ne for production of categori ems es and for reproduction in se ed farms TJ-SRASP-RFB-G02 / Equipm ent in support of plant breedi ng, in vitro laboratory equip Strengthening seed, seedlin Single Stage - One E Pending Impl ment, irrigation equipment, f IDA / D8600 g and planting material syst Post Request for Bids Open - National 680,000.00 0.00 2023-05-31 2023-05-31 2023-06-30 2023-07-30 2023-08-10 2024-02-06 nvelope ementation arming machinery for Scienti ems fic Research Institute of Biote chnology of Tajik Agrarian Un iversity TJ-SRASP-RFB-G14 / Equipm Strengthen public capacity f Single Stage - One E Pending Impl ent for Data Center for MOA ( IDA / D8600 or crises prevention and ma Post Request for Bids Open - National 150,000.00 0.00 2023-06-22 2023-06-22 2023-07-22 2023-08-21 2023-09-25 2024-03-23 nvelope ementation Digital archive SDW) nagement TJ-SRASP-RFB-G15 / Softwar Strengthen public capacity f Single Stage - One E Pending Impl es (GIS Server, 3D GIS, GIS a IDA / D8600 or crises prevention and ma Post Request for Bids Open - National 200,000.00 0.00 2023-06-22 2023-06-27 2023-07-27 2023-08-26 2023-09-07 2024-03-05 nvelope ementation nd 3 D GIS editing tools, SUB nagement DD) TJ-SRASP-RFB-G17 / Drones f Strengthen public capacity f Single Stage - One E Pending Impl IDA / D8600 Post Request for Bids Open - National 200,000.00 0.00 2022-07-16 2022-07-16 2022-08-15 2022-09-14 2022-09-26 2023-03-25 or aerophotography and mon or crises prevention and ma nvelope ementation itoring nagement TJ-SRASP-RFQ-G05 / Mobile a Strengthen public capacity f Request for Quota Single Stage - One E Pending Impl IDA / D8600 Post Open - National 60,000.00 0.00 2022-07-16 2022-08-21 2023-02-17 grometeorological stations (1 or crises prevention and ma tions nvelope ementation 2) nagement TJ-SRASP-RFB-G24 / Office a Strengthen public capacity f Single Stage - One E Pending Impl IDA / D8600 Post Request for Bids Open - National 200,000.00 0.00 2023-02-07 2023-02-12 2023-03-26 2023-04-25 2023-05-30 2024-05-29 nd IT for Crop Protection Unit or crises prevention and ma nvelope ementation nagement TJ-SRASP-RFB-G20 / Procure Project management and co Single Stage - One E IDA / D8600 Post Request for Bids Open - National 254,460.00 249,600.00 Completed 2022-04-28 2022-04-28 2022-05-03 2022-04-29 2022-06-14 2022-05-31 2022-07-14 2022-06-10 2022-08-18 2022-07-14 2022-08-27 2023-01-10 ment of 8 vehicles for AED P ordination nvelope MU TJ-AED PIU-291011-GO-RFB / Strengthen public capacity f Single Stage - One E IDA / D8600 Post Request for Bids Open - National 240,000.00 0.00 Completed 2022-08-01 2022-07-25 2022-08-06 2022-07-26 2022-09-17 2022-08-26 2022-10-17 2022-09-14 2022-11-21 2023-05-20 2022-12-27 Procurement of 6 Field cars. or crises prevention and ma nvelope nagement TJ-SRASP-RFB-G29 / Office E quipment and Office Furnitur Project management and co Single Stage - One E IDA / D8600 Post Request for Bids Open - National 133,850.00 0.00 Canceled 2022-02-28 2022-03-05 2022-04-16 2022-05-16 2022-06-20 2022-12-17 e (for PMU & two regional off ordination nvelope ices in North and South) TJ-SRASP-295742-GO-RFQ / Project management and co Request for Quota Single Stage - One E Procurement of office equip IDA / D8600 Post Open - National 80,000.00 79,340.00 Completed 2022-06-06 2022-06-06 2022-07-16 2022-07-17 2022-10-14 2022-09-20 ordination tions nvelope ment for PMU AED & two regi onal offices TJ-SRASP-296890-GO-RFB / P Strengthening seed, seedlin Single Stage - One E rocurement of cotton seeds o IDA / D8600 g and planting material syst Post Request for Bids Open - National 900,000.00 0.00 Canceled 2022-08-01 2022-07-22 2022-08-06 2022-07-22 2022-09-05 2022-08-24 2022-10-05 2022-10-20 2022-10-26 2023-01-24 nvelope f the elite and super elite cat ems egories TJ-SRASP-296894-GO-RFB / P Strengthening seed, seedlin Single Stage - One E rocurement of potato seeds o IDA / D8600 g and planting material syst Post Request for Bids Open - National 800,000.00 0.00 Canceled 2022-09-05 2022-08-19 2022-09-10 2022-08-19 2022-09-13 2022-09-19 2022-10-13 2022-10-17 2022-11-17 2023-02-15 nvelope f the elite and super elite cat ems egories TJ-SRASP- 96900-GO-RFB / P Strengthening seed, seedlin rocurement of wheat seeds o Single Stage - One E IDA / D8600 g and planting material syst Post Request for Bids Open - National 700,000.00 713,212.50 Completed 2022-06-08 2022-06-03 2022-06-13 2022-06-03 2022-07-13 2022-07-05 2022-07-27 2022-07-12 2022-08-02 2022-08-08 2022-09-01 2022-09-28 f the elite and super elite cat nvelope ems egories and fertilizers TJ-SRASP-RFB-G21 / Laborat ory equipment for Agrokhim Strengthen public capacity f Single Stage - One E Pending Impl soil laboratories: (3), Laborat IDA / D8600 or crises prevention and ma Post Request for Bids Open - National 810,000.00 0.00 2023-08-08 2023-08-13 2023-09-24 2023-10-24 2023-11-28 2024-05-26 nvelope ementation ory equipment, Soil Doctor ki nagement ts for Soil Management Rese arch Institute TJ-SRASP-300076-GO-RFB / P Strengthen public capacity f Single Stage - One E Under Imple rocurement of two (2) mobile IDA / D8600 or crises prevention and ma Post Request for Bids Open - National 200,000.00 0.00 2022-06-23 2022-07-22 2022-06-28 2022-07-22 2022-07-28 2022-08-27 2022-08-31 2022-11-29 nvelope mentation soil testing laboratories nagement TJ-AED PIU-304795-GO-RFQ / Project management and co Request for Quota Single Stage - One E Under Imple Supply and installation of 1C IDA / D8600 Post Open - National 15,000.00 0.00 2022-07-26 2022-08-13 2022-09-12 ordination tions nvelope mentation Accounting Software TJ-SRASP-307221-GO-RFB / P rocurement of seeds, seedlin Strengthening seed, seedlin Single Stage - One E Under Imple gs and planting material to cr IDA / D8600 g and planting material syst Post Request for Bids Open - National 150,000.00 0.00 2022-08-08 2022-08-12 2022-08-10 2022-08-15 2022-09-09 2022-10-09 2022-10-16 2022-11-15 nvelope mentation eate intensive gardens for SU ems E “Tojikniholparvar” for 2022 . TJ-SRASP-307269-GO-RFB / P Strengthen public capacity f Single Stage - One E rocurement of means and ch IDA / D8600 or crises prevention and ma Post Request for Bids Open - National 400,000.00 0.00 Signed 2022-08-08 2022-08-12 2022-08-13 2022-08-15 2022-09-12 2022-09-08 2022-10-12 2022-09-30 2022-10-21 2023-01-19 nvelope emicals for locust control for nagement 2022 TJ-SRASP-307211-GO-RFB / P Strengthening seed, seedlin Open - Internationa Single Stage - One E rocurement of fertilisers for c IDA / D8600 g and planting material syst Post Request for Bids 2,700,000.00 0.00 Signed 2022-08-15 2022-08-19 2022-08-20 2022-08-19 2022-09-19 2022-09-19 2022-10-19 2022-10-02 2022-11-23 2023-02-21 l nvelope otton seeds and potato seeds ems TJ-SRASP-RFB-G07 / Procure Strengthening seed, seedlin Open - Internationa Single Stage - One E ment of cotton seeds of the e IDA / D8600 g and planting material syst Post Request for Bids 1,750,000.00 0.00 Signed 2022-08-22 2022-08-29 2022-08-27 2022-09-27 2022-10-08 2022-10-10 2022-11-07 2022-10-21 2022-12-12 2023-06-10 l nvelope lite and super elite categorie ems s and fertilizers TJ-SRASP-RFB-G18 / Equipm Strengthen public capacity f Single Stage - One E Under Imple ent for MOA to support monit IDA / D8600 or crises prevention and ma Post Request for Bids Open - National 350,000.00 0.00 2022-09-22 2022-12-01 2022-09-27 2022-12-01 2022-10-27 2022-12-30 2022-11-26 2022-12-08 2023-04-07 nvelope mentation oring and planning of agricult nagement ure TJ-SRASP-331090-GO-RFB / P Strengthening seed, seedlin Open - Internationa Single Stage - One E rocurement of cotton seeds o IDA / D8600 g and planting material syst Post Request for Bids 900,000.00 0.00 Completed 2022-12-14 2022-12-14 2022-12-19 2022-12-15 2023-01-30 2023-01-13 2023-03-01 2023-01-19 2023-03-13 2023-04-12 2023-04-03 l nvelope f elite and super elite categor ems ies Page 2 TJ-AED PIU-332924-GO-RFB / Procurement of tractors and Strengthening seed, seedlin Open - Internationa Single Stage - One E agricultural equipment for St IDA / D8600 g and planting material syst Post Request for Bids 2,700,000.00 0.00 Signed 2022-12-30 2022-12-30 2023-01-04 2022-12-29 2023-01-14 2023-02-08 2023-02-03 2023-03-20 2023-03-06 2023-07-04 l nvelope ate Unitary Republican Enter ems prise “Tojikniholparvar” and seed production farms TJ-AED PIU-336407-GO-RFB / Strengthening seed, seedlin Single Stage - One E Procurement of potato seeds IDA / D8600 g and planting material syst Post Request for Bids Open - National 950,000.00 0.00 Completed 2023-01-17 2023-01-18 2023-01-18 2023-01-17 2023-02-08 2023-02-08 2023-02-13 2023-02-17 2023-02-24 2023-04-25 2023-05-03 nvelope of elite category for 2023 ems TJ-SRASP-RFB-G01 / Equipm ent in support of plant breedi Strengthening seed, seedlin ng and variety evaluation pro Single Stage - One E Pending Impl IDA / D8600 g and planting material syst Post Request for Bids Open - National 730,000.00 0.00 2023-01-31 2023-02-05 2023-03-19 2023-04-18 2023-04-28 2023-10-25 grams including irrigation eq nvelope ementation ems uipment, farming machinery for the Tajik Academy of Agri cultural Sciences (TAAS) insti tutes. TJ-SRASP-311034-GO-RFQ / Strengthening seed, seedlin Procurement of wheat, barle Request for Quota Single Stage - One E Pending Impl IDA / D8600 g and planting material syst Post Open - National 10,000.00 0.00 2023-09-06 2023-10-11 2023-11-10 y, cotton, corn, potato, alfalf tions nvelope ementation ems a, rape seeds of elite categor ies for seed farms TJ-SRASP-RFB-G10 / Procure ment of corn seeds of the elit Strengthening seed, seedlin Single Stage - One E Pending Impl e and super elite categories f IDA / D8600 g and planting material syst Post Request for Bids Open - National 190,000.00 0.00 2024-05-15 2024-05-20 2024-07-01 2024-07-31 2024-08-04 2024-09-03 nvelope ementation or the production of categori ems es and for reproduction in se ed farms TJ-SRASP-RFB-G08 / Procure ment of potato seeds of the e Strengthening seed, seedlin Open - Internationa Single Stage - One E Pending Impl lite and super elite categorie IDA / D8600 g and planting material syst Post Request for Bids 3,850,000.00 0.00 2023-12-01 2023-12-06 2024-01-05 2024-02-04 2024-02-08 2024-04-08 l nvelope ementation s for production of categories ems and for reproduction in seed farms TJ-SRASP-RFB-G28 / Procure Strengthen public capacity f Single Stage - One E Pending Impl ment of means and chemical IDA / D8600 or crises prevention and ma Post Request for Bids Open - National 650,000.00 0.00 2023-05-30 2023-06-04 2023-07-04 2023-08-03 2023-08-31 2023-10-30 nvelope ementation s for locust control nagement TJ-SRASP-RFB-G27 / Equipm Strengthen public capacity f ent for mechanical and manu Single Stage - One E Pending Impl IDA / D8600 or crises prevention and ma Post Request for Bids Open - National 800,000.00 0.00 2023-06-30 2023-06-30 2023-07-30 2023-08-29 2023-09-17 2023-09-23 al control of locust, equipme nvelope ementation nagement nt and tools for staff engage d in locust control TJ-SRASP-RFB-G12 / Purchas Strengthen public capacity f Single Stage - One E Pending Impl e of satellite images for soil r IDA / D8600 or crises prevention and ma Post Request for Bids Open - National 250,000.00 0.00 2023-07-10 2023-07-10 2023-08-09 2023-09-08 2023-09-21 2024-03-19 nvelope ementation emote sensing nagement TJ-SRASP-RFB-G16 / Hardwar e, (Server, Web APP, storage, Strengthen public capacity f Single Stage - One E Pending Impl Plotter, Scanner, Printers, No IDA / D8600 or crises prevention and ma Post Request for Bids Open - National 450,000.00 0.00 2024-03-03 2024-03-08 2024-04-07 2024-05-07 2024-05-21 2024-11-17 nvelope ementation tebooks, Displays, switchers, nagement brandmauer, network equip ment, computers) TJ-SRASP-RFB-G11 / Equipm ent (Pre-cooling, sorting, gra Support investments in Agri- Open - Internationa Single Stage - One E Pending Impl ding, packing lines, cold stor IDA / D8600 Logistical Centers (ALCs) for Post Request for Bids 1,280,000.00 0.00 2024-05-10 2024-05-15 2024-06-26 2024-07-26 2024-08-30 2025-02-26 l nvelope ementation age) for agro-logistics center horticulture value chains s in Dushanbe, Khatlon and Sughd TJ-SRASP-RFB-G23 / Equipm Strengthen public capacity f ent for Techjical modernizati Single Stage - One E Pending Impl IDA / D8600 or crises prevention and ma Post Request for Bids Open - National 400,000.00 0.00 2023-07-03 2023-07-08 2023-08-19 2023-09-18 2023-10-23 2024-04-20 on of Agrokhim soil laboratori nvelope ementation nagement es (Establishment of digital s oil testing database) TJ-SRASP-RFQ-G01 / Equipm ent in support of the storage and maintenance of germpla Strengthening seed, seedlin Request for Quota Single Stage - One E Pending Impl sm including freezers for lon IDA / D8600 g and planting material syst Post Open - National 200,000.00 0.00 2023-02-25 2023-04-22 2023-10-19 tions nvelope ementation g-term germplasm storage, ir ems rigation equipment, farm ma chinery for National Republic an Center for Genetic Resour ces TJ-SRASP-RFB-G26 / Procure Strengthen public capacity f ment of chemical means (pes Single Stage - One E Under Imple IDA / D8600 or crises prevention and ma Post Request for Bids Open - National 200,000.00 0.00 2023-06-02 2023-05-19 2023-06-07 2023-05-20 2023-07-07 2023-06-16 2023-08-06 2023-08-20 2023-11-18 ticides) for SI “Plant protectio nvelope mentation nagement n and Agricultural Chemicals ” TJ-SRASP-RFB-G25 / Equipm Strengthen public capacity f Open - Internationa Single Stage - One E Pending Impl ent for Crop protection labor IDA / D8600 or crises prevention and ma Post Request for Bids 815,000.00 0.00 2022-04-05 2022-04-10 2022-05-22 2022-06-21 2022-07-26 2023-01-22 l nvelope ementation atories in 4 regions nagement TJ-SRASP-RFQ-G06 / Utilizati Strengthen public capacity f Request for Quota Single Stage - One E Pending Impl IDA / D8600 Post Open - National 60,000.00 0.00 2024-07-15 2024-08-29 2025-02-25 on of remaining chemicals an or crises prevention and ma tions nvelope ementation d materials nagement TJ-SRASP-RFB-G03 / Equipm ent in support of seed, seedli Strengthening seed, seedlin ng and planting material pro Single Stage - One E IDA / D8600 g and planting material syst Post Request for Bids Open - National 780,000.00 0.00 Canceled 2023-12-22 2023-12-27 2024-02-07 2024-03-08 2024-04-12 2024-10-09 pagation, including cleaning, nvelope ems processing, packaging, qualit y monitoring for institutes of the TAAS TJ-SRASP-357808-GO-RFB / P Strengthen public capacity f Single Stage - One E Under Imple rocurement of sprayers for SI IDA / D8600 or crises prevention and ma Post Request for Bids Open - National 300,000.00 0.00 2023-05-10 2023-05-19 2023-05-15 2023-05-22 2023-06-14 2023-06-16 2023-07-14 2023-08-04 2023-10-03 nvelope mentation “Plant protection and Agricult nagement ural Chemicals” TJ-SRASP-RFB-G002 / Equip ment in support of plant bree Strengthening seed, seedlin ding and variety evaluation p Request for Quota Single Stage - One E Pending Impl IDA / D8600 g and planting material syst Post Open - National 230,000.00 0.00 2022-12-21 2023-02-06 2023-08-05 rograms including irrigation e tions nvelope ementation ems quipment, farming machiner y for Center for Innovation an d Mechanisation of Agricultur e TJ-SRASP-RFB-G05 / laborato ry and field Quality control a Strengthening seed, seedlin Single Stage - One E Pending Impl nd surveillance equipment fo IDA / D8600 g and planting material syst Post Request for Bids Open - National 820,000.00 0.00 2023-07-03 2023-07-10 2023-08-09 2023-09-08 2023-09-20 2024-01-18 nvelope ementation r Regional Quality Control Fa ems cilities and Central Seed Lab oratory TAAS TJ-SRASP-314986-GO-RFB / P Strengthen public capacity f rocurement of furniture for th Single Stage - One E Pending Impl IDA / D8600 or crises prevention and ma Post Request for Bids Open - National 190,000.00 0.00 2023-07-28 2023-08-02 2023-09-01 2023-10-01 2023-10-07 2024-01-05 e Ministry of Agriculture and nvelope ementation nagement PMU office and two regional offices Page 3 TJ-SRASP-RFB-G06 / Office a nd IT equipment for the Tajik Strengthening seed, seedlin Single Stage - One E Pending Impl Academy of Agricultural Scie IDA / D8600 g and planting material syst Post Request for Bids Open - National 240,000.00 0.00 2023-06-15 2023-06-15 2023-07-27 2023-08-26 2023-09-11 2023-12-10 nvelope ementation nces (TAAS) institutes and SI ems “Plant protection and Agricult ural Chemicals” TJ-SRASP-361656-GO-RFB / P Strengthening seed, seedlin Single Stage - One E Under Imple rocurement of wheat seeds o IDA / D8600 g and planting material syst Post Request for Bids Open - National 500,000.00 0.00 2023-05-18 2023-05-24 2023-05-23 2023-05-24 2023-06-22 2023-07-22 2023-07-31 2023-09-29 nvelope mentation f the elite and super elite cat ems egories TJ-SRASP-361657-GO-RFB / P Strengthening seed, seedlin Open - Internationa Single Stage - One E Under Imple rocurement of mineral fertiliz IDA / D8600 g and planting material syst Post Request for Bids 1,250,000.00 0.00 2023-05-23 2023-05-24 2023-05-28 2023-05-25 2023-07-09 2023-08-08 2023-08-22 2023-10-06 l nvelope mentation ers for wheat seeds ems TJ-SRASP-RFB-G09 / Procure ment of wheat seeds of the Strengthening seed, seedlin Single Stage - One E Pending Impl elite and super elite categori IDA / D8600 g and planting material syst Post Request for Bids Open - National 2,550,000.00 0.00 2022-03-28 2022-03-28 2022-04-27 2022-06-11 2022-07-16 2027-08-12 nvelope ementation es for the production of cate ems gories and for reproduction i n seed farms TJ-SRASP-358144-GO-RFB / P rocurement of tractors for SI “Plant protection and Agricult Strengthening seed, seedlin ural Chemicals” and SI "State Open - Internationa Single Stage - One E Pending Impl IDA / D8600 g and planting material syst Post Request for Bids 2,469,750.00 0.00 2023-06-01 2023-06-06 2023-07-18 2023-08-17 2023-09-07 2024-01-05 Commission for Variety Testi l nvelope ementation ems ng of Agricultural Crops and Protection of Varieties and tr actors and trailers for SUE “T ojikniholparvar” and seed pro duction farms" SRASP AF/G/RFB-2023/11 / P Project management and co Single Stage - One E Pending Impl IDA / E1450 Post Request for Bids Open - National 135,000.00 0.00 2023-06-30 2023-07-05 2023-08-04 2023-08-24 2023-09-09 2023-11-08 rocurement of vehicles for P ordination nvelope ementation MU SRASP AF/G/RFB-2023/09 / P Strengthening seed, seedlin rocurement of mineral fertiliz Single Stage - One E Pending Impl IDA / E1450 g and planting material syst Post Request for Bids Open - National 1,072,778.00 0.00 2023-07-10 2023-07-15 2023-08-14 2023-09-13 2023-09-29 2023-11-28 ers for pea and flax seeds for nvelope ementation ems vulnerable farmers SRASP AF/G/RFB-2023/01 / P Strengthening seed, seedlin Single Stage - One E Under Imple rocurement of wheat seeds f IDA / E1450 g and planting material syst Post Request for Bids Open - National 480,000.00 0.00 2023-06-05 2023-06-19 2023-06-10 2023-06-22 2023-07-10 2023-08-09 2023-08-25 2023-10-24 nvelope mentation or vulnerable farmers ems SRASP AF/G/RFB-2023/03 / P Strengthening seed, seedlin Single Stage - One E Under Imple rocurement of onion, tomato IDA / E1450 g and planting material syst Post Request for Bids Open - National 800,000.00 0.00 2023-06-05 2023-06-12 2023-06-10 2023-06-13 2023-07-10 2023-08-09 2023-08-25 2023-11-23 nvelope mentation and cucumber seeds for vuln ems erable farmers SRASP AF/G/RFB-2023/08 / P Strengthening seed, seedlin Open - Internationa Single Stage - One E Pending Impl rocurement of mineral fetiliz IDA / E1450 g and planting material syst Post Request for Bids 1,613,200.00 0.00 2023-06-27 2023-07-02 2023-08-13 2023-08-28 2023-09-13 2023-11-12 l nvelope ementation er for corn seeds for vulnera ems ble farmers SRASP AF/G/RFB-2023/04 / P Strengthening seed, seedlin Pending Impl rocurement of corn seeds for IDA / E1450 g and planting material syst Post Request for Bids 460,000.00 0.00 2023-06-19 2023-06-20 2023-07-20 2023-08-19 2023-09-04 2023-12-03 ementation vulnerable farmers ems SRASP AF/G/RFB-2023/07 / P Strengthening seed, seedlin rocurement of mineral fertiliz Single Stage - One E Under Imple IDA / E1450 g and planting material syst Post Request for Bids Open - National 436,000.00 0.00 2023-06-12 2023-06-16 2023-06-17 2023-06-16 2023-07-17 2023-08-16 2023-09-01 2023-10-31 ers for onion, tomato and cuc nvelope mentation ems umbers seeds for vulnerable farmers SRASP AF/G/RFB-2023/10 / P Strengthening seed, seedlin Open - Internationa Single Stage - One E Pending Impl rocurement of small agricultu IDA / E1450 g and planting material syst Post Request for Bids 3,500,000.00 0.00 2023-06-19 2023-06-24 2023-08-05 2023-08-25 2023-09-10 2023-12-09 l nvelope ementation ral machineries for vulnerabl ems e farmers SRASP AF/G/RFB-2023/02 / P Strengthening seed, seedlin Single Stage - One E Pending Impl rocurement of potato seeds f IDA / E1450 g and planting material syst Post Request for Bids Open - National 970,000.00 0.00 2023-06-05 2023-06-10 2023-07-10 2023-08-09 2023-08-25 2023-10-24 nvelope ementation or vulnerable farmers ems SRASP AF/G/RFB-2023/05 / P Strengthening seed, seedlin Pending Impl rocurement of pea and flax s IDA / E1450 g and planting material syst Post Request for Bids 550,180.00 0.00 2023-06-20 2023-06-25 2023-07-25 2023-08-24 2023-09-09 2023-11-08 ementation eeds for vulnerable farmers ems SRASP AF/G/RFB-2023/06 / P Strengthening seed, seedlin rocurement of mineral fertiliz Open - Internationa Single Stage - One E Pending Impl IDA / E1450 g and planting material syst Post Request for Bids 1,129,240.00 0.00 2023-06-09 2023-06-10 2023-07-10 2023-08-09 2023-08-25 2023-10-09 er for wheat and potato seed l nvelope ementation ems s for vulnerable farmers NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TJ-SRASP-CQS-CS05 / On-site Support investments in Agri- Consultant Qualifi Pending Impleme specialized training of the sta IDA / D8600 Logistical Centers (ALCs) for Post Open - National 104,000.00 0.00 2024-11-01 2024-11-22 2025-01-05 2025-02-04 2025-03-11 2025-09-07 cation Selection ntation ff operating the ALCs horticulture value chains TJ-SRASP-CQS-CS08 / Mid-ter Project management and co Consultant Qualifi Pending Impleme IDA / D8600 Post Open - National 70,000.00 0.00 2024-03-10 2024-03-31 2024-05-14 2024-06-13 2024-07-18 2025-01-14 m review ordination cation Selection ntation TJ-SRASP-CQS-CS09 / Final r Project management and co Consultant Qualifi Pending Impleme IDA / D8600 Post Open - National 60,000.00 0.00 2027-01-15 2027-02-05 2027-03-21 2027-04-20 2027-05-25 2027-11-21 eview ordination cation Selection ntation TJ-SRASP-CQS-CS10 / Grieva Project management and co Consultant Qualifi Under Implement IDA / D8600 Post Open - National 90,000.00 0.00 2022-03-15 2023-02-27 2022-04-05 2022-05-19 2022-06-18 2022-07-23 2023-01-19 nce Redress Mechanism ordination cation Selection ation TJ-SRASP-QCBS-CS01 / Feas Support investments in Agri- ability Study -business plan-E Quality And Cost- Open - Internationa Under Implement IDA / D8600 Logistical Centers (ALCs) for Post 702,000.00 0.00 2022-04-11 2022-04-08 2022-04-18 2022-05-19 2022-06-01 2022-07-28 2022-06-29 2022-07-29 2022-09-02 2022-10-07 2023-10-07 SIA/ Detailed design /cost est Based Selection l ation horticulture value chains imate for three ALCs and Sup ervision of works Page 4 TJ-SRASP-CQS-CS04 / Feasibi Support investments in Agri- Consultant Qualifi lity study - business plan - ES IDA / D8600 Logistical Centers (ALCs) for Post Open - National 213,000.00 0.00 Canceled 2022-03-10 2022-03-31 2022-05-14 2022-06-13 2022-07-18 2022-11-15 cation Selection IA horticulture value chains TJ-SRASP-CQS-CS07 / Baseli Project management and co Consultant Qualifi Under Implement IDA / D8600 Post Open - National 25,000.00 0.00 2022-07-01 2022-08-09 2022-07-06 2022-09-14 2022-08-19 2022-09-18 2022-10-23 2023-04-21 ne study of the project ordination cation Selection ation TJ-SRASP-CQS-CS02 / Need a ssessment of renovation wor k and for development of des Strengthening seed, seedlin ign and detailed cost estimat Consultant Qualifi IDA / D8600 g and planting material syst Post Open - National 170,000.00 0.00 Canceled 2022-04-22 2022-05-13 2022-06-26 2022-07-26 2022-08-30 2022-12-28 es cation Selection ems for Research institutes of TA AS, Tajik Agrarian University and Centers and agencies of the Ministry of Agriculture TJ-SRASP-296837-CS-CQS / P Strengthening seed, seedlin reparation of design and esti Consultant Qualifi Under Implement IDA / D8600 g and planting material syst Post Open - National 250,000.00 0.00 2022-08-22 2022-12-08 2022-09-05 2022-10-20 2022-11-03 2022-11-17 2023-05-16 mate documentation and sup cation Selection ation ems ervision of works for 7 sites. TJ-SRASP-296158-CS-CQS / P Strengthening seed, seedlin reparation of design and esti Consultant Qualifi Under Implement IDA / D8600 g and planting material syst Post Open - National 136,000.00 0.00 2022-07-20 2022-08-02 2022-08-03 2022-08-11 2022-08-19 2022-08-26 2022-09-09 2023-03-08 mate documentation and fiel cation Selection ation ems d supervision for 10 sites. TJ-SRASP-296164-CS-CQS / P Strengthening seed, seedlin reparation of design and esti Consultant Qualifi IDA / D8600 g and planting material syst Post Open - National 75,000.00 0.00 Signed 2022-05-31 2022-07-07 2022-06-10 2022-07-14 2022-07-08 2022-08-16 2022-07-15 2022-08-31 2022-07-29 2023-01-25 mate documentation and fiel cation Selection ems d supervision for 4 sites. TJ-SRASP-CQS-CS01 / Techni Strengthening seed, seedlin cal support and capacity buil Consultant Qualifi Pending Impleme IDA / D8600 g and planting material syst Post Open - National 72,000.00 0.00 2024-01-01 2024-01-01 2024-02-14 2024-02-28 2024-03-30 2024-08-08 ding on plant breeding, crop cation Selection ntation ems propagation, plant diseases, i rrigation TJ-SRASP-CQS-CS03 / Prepar ation of the list and technical specifications of equipment f Strengthening seed, seedlin Consultant Qualifi or technical modernization fo IDA / D8600 g and planting material syst Post Open - National 70,000.00 0.00 Canceled 2022-04-22 2022-05-13 2022-06-26 2022-07-26 2022-08-30 2022-12-28 cation Selection r Research institutes of TAAS ems , Tajik Agrarian University an d Centers and agencies of th e Ministry of Agriculture; SRASP AF/CS/CQS-2023/01 / Strengthening seed, seedlin Conduction of survey for iden Consultant Qualifi Pending Impleme IDA / E1450 g and planting material syst Post Open - National 200,000.00 0.00 2023-06-23 2023-07-07 2023-08-04 2023-08-05 2023-08-21 2023-10-20 tification of the availability of cation Selection ntation ems irrigation pumps of the vulne rable farmers TJ-SRASP-CQS-CS06 / Detaile Strengthen public capacity f Consultant Qualifi d design of the Center for Di IDA / D8600 or crises prevention and ma Post Open - National 300,000.00 0.00 Canceled 2022-05-20 2022-06-10 2022-07-24 2022-08-23 2022-09-27 2023-03-26 cation Selection gital Development of Agricult nagement ure TJ-SRASP-QCBS-CS02 / Devel Strengthen public capacity f Quality And Cost- Open - Internationa opment of Agriculture & Live IDA / D8600 or crises prevention and ma Post 3,400,000.00 0.00 Under Review 2023-06-20 2023-06-29 2023-07-11 2023-08-24 2023-09-21 2023-10-21 2023-11-25 2023-12-30 2024-12-29 Based Selection l stock Management Informati nagement on System INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TJ-SRASP-DS-CS01 / A strate gic contract covering all aspe cts of the project activities su Strengthening seed, seedlin Under Implement ch as. IDA / D8600 g and planting material syst Prior Direct Selection Direct 2,500,000.00 0.00 2022-02-28 2022-04-08 2022-03-10 2022-04-15 2022-04-23 2026-12-23 ation Component 1; including (Sub ems components 1.1- 1.4) Component 3: including (Sub -components 3.1-3.3) TJ-AED PIU-291019-CS-INDV Project management and co Individual Consult / Individual Consultant for Ba IDA / D8600 Post Open 40,000.00 36,918.00 Signed 2022-04-25 2022-04-25 2022-06-13 2022-06-22 2022-07-04 2022-07-01 2022-08-08 2022-07-08 2023-02-04 ordination ant Selection seline study of the project TJ-SRASP-321733-CS-CDS / Strengthening seed, seedlin National Consultant for proje IDA / D8600 g and planting material syst Post Direct Selection Direct - National 14,000.00 0.00 Signed 2022-11-04 2022-11-04 2022-11-06 2022-10-21 2022-11-08 2023-02-28 ct development to rise additi ems onal financial resources for C RW ERF within SRASP TJ-SRASP-325596-CS-INDV / Lawyer to prepare document s on legal changes of the Sta te Unitary Enterprise "Center Strengthen public capacity f Individual Consult Under Implement for Agricultural Staff Professi IDA / D8600 or crises prevention and ma Post Open - National 10,000.00 0.00 2022-11-15 2022-11-23 2023-01-03 2023-01-08 2023-01-14 2023-06-13 ant Selection ation onal Development" under the nagement Ministry of Agriculture into th e State Unitary Enterprise "C enter for Digital Developmen t and Agricultural Staf TJ-SRASP-361675-CS-INDV / National consultant for techni Strengthening seed, seedlin Individual Consult Under Implement cal support of laboratories of IDA / D8600 g and planting material syst Post Open - National 3,450.00 0.00 2023-05-15 2023-05-23 2023-06-06 2023-06-08 2023-06-12 2023-07-07 ant Selection ation Institute of seed production o ems f the Academy of Agricultural Sciences of Tajikistan TJ-SRASP-361677-CS-INDV / National consultant for techni Strengthening seed, seedlin cal support of laboratories of Individual Consult Under Implement IDA / D8600 g and planting material syst Post Open - National 3,450.00 0.00 2023-05-15 2023-05-23 2023-06-06 2023-06-08 2023-06-12 2023-07-07 Institute of Soil Science and ant Selection ation ems Agrochemistry of the Acade my of Agricultural Sciences o f Tajikistan TJ-AED PIU-361689-CS-INDV / National consultant for tech Strengthening seed, seedlin Individual Consult Under Implement nical support of laboratories IDA / D8600 g and planting material syst Post Open - National 3,450.00 0.00 2023-05-15 2023-05-23 2023-06-06 2023-06-08 2023-06-12 2023-07-07 ant Selection ation of State Institute «Plant prote ems ction and agrochemistry» SRASP AF/CS/DS-2023/01 / C Strengthening seed, seedlin Under Implement onduction of survey for identi IDA / E1450 g and planting material syst Post Direct Selection Direct - National 150,000.00 0.00 2023-06-06 2023-06-15 2023-06-16 2023-06-28 2023-08-12 ation fication of the vulnerable far ems mers Page 5 PROCUREMENT PLAN (Textual Part) Project information: Nepal, Second Bridge Improvement and Maintenance Program (P161929) Project Implementation agency: Department of Roads, within Ministry of Physical Infrastructure and Transport. Date of the Procurement Plan: May 31, 2019. Period covered by this Procurement Plan: From May 2019 covering first 18 months. Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. National Procurement Procedures: These procedures are applicable for the procurement of goods, works and non-consulting services only. In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market, as agreed in the Procurement Plan tables in STEP, the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in Nepal’s Public Procurement Act, 2007, as amended by Amendment 2073 (2016) - (1st Amendment) and the Public Procurement Regulation, 2007, as amended by Amendment 2073 (2017) - (5th Amendment) made thereunder, such arrangements shall be subject to paragraph 5.4 of the Bank’s Procurement Regulations and the following conditions: 1) Model bidding documents, including contract conditions agreed with the Bank (as amended from time to time), shall be used. Bidding documents shall be made available, by mail or in person, or through e-GP portal to all who are willing to pay the required fee. 2) The eligibility of bidders shall be as defined under Section III of the Procurement Regulations. Accordingly, no bidder or potential bidder shall be declared ineligible for contracts financed by the Bank for reasons other than those provided in Section III of the Procurement Regulations; 3) The request for bids/request for proposals document shall require that Bidders/Proposers submitting Bids/Proposals present a signed acceptance (in the form attached) at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights. 4) Qualification criteria (in case pre-qualifications were not carried out) shall be stated in the bidding documents for all contracts, irrespective of the value, and if a registration process is required, a foreign firm declared as the lowest evaluated bidder shall be given a reasonable opportunity to register, without let or hindrance. 5) Procurement Documents include provisions, as agreed with the Bank, intended to adequately mitigate against environmental, social (including sexual exploitation and abuse and gender-based violence), health and safety (“ESHS”) risks and impacts. 6) Performance security should be an amount of five (5) to ten (10) percent of the contract price and shall not be increased merely based on comparison of the bid price of awarded bidders with the pre-bid cost estimate. 7) If a contract is terminated because of fundamental breach of contract by the contractor, the amount to be recovered from the contractor representing the employer’s additional costs for completing the contract shall be provisioned as agreed with the Bank in model bidding documents. When other national procurement arrangements (other than national open competitive procurement) are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Not Applicable. Procurement of Second-Hand Goods as specified under paragraph 5.11 of the Procurement Regulations: Not Applicable. Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works), if any: • Goods: is applicable for those contracts identified in the Procurement Plan tables; • Works: is applicable for those contracts identified in the Procurement Plan tables. Other Relevant Procurement Information: As mentioned in the procurement section of the Project Operation/ Implementation Manual, if any. 5.3 Consultancy/Services Procurement Arrangements Selection of consulting firms will follow QCBS, CQS, LCS or Direct Selection methods as appropriate. For selecting individual consultants, open competitive, limited competitive or direct selection methods will be adopted. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. PROCUREMENT Nepal : Second Bridges Improvement and Maintenance Program PLAN General Information Country: Nepal 2019-06-25 Bank’s Approval Date of the Original Procurement Plan: 2023-06-01 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P161929 GPN Date: Project Name: Second Bridges Improvement and Maintenance Program Loan / Credit No: IDA / 63170 Department of Roads Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NP-DOR-BIMP-GOODS-2 / Pro curement of Laptops,desktop computers, printer cum phot IDA / 63170 Post Direct Selection Direct 60,000.00 44,309.14 Completed 2019-06-03 2019-07-11 2019-06-08 2020-02-23 2019-07-13 2020-03-07 2020-01-09 2020-05-31 ocopy machines A3 size,Colo r printer,Video Conferencing system(e.g Web ex) for DATC . NP-DOR-BIMP-GOODS-1 / Pro curement of Bridge Design S IDA / 63170 Post Direct Selection Direct 100,000.00 61,246.58 Completed 2019-06-27 2019-07-09 2019-06-30 2019-07-28 2019-08-09 2019-08-20 2020-02-05 2019-08-31 oftware(MIDAS). NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NP-DOR-126175-CS-QBS-PD K02 / Environmental and soci Quality Based Sel al impact assessment of Path IDA / 63170 Post Open - National 100,000.00 0.00 Canceled 2019-08-15 2019-09-05 2019-10-19 2019-11-23 2019-12-23 2020-01-22 2020-02-26 2021-02-25 ection laiya-Dhalkebar Road section of Mahendra Highway. NP-DOR-126160-CS-QBS-PD K01 / Detailed Engineering s Quality Based Sel IDA / 63170 Prior 3,600,000.00 0.00 Canceled 2019-08-15 2019-09-05 2019-10-19 2019-12-03 2020-01-02 2020-02-01 2020-03-07 2021-03-07 urvey and design of Patlaiya- ection Dhalkebar-Kamala Roads and Bridges. NP-DOR-128701-CS-QCBS-P DK01 / Detailed Engineering Quality And Cost- Open - Internationa IDA / 63170 Post 3,600,000.00 0.00 Canceled 2019-09-05 2019-09-12 2019-10-22 2019-12-06 2020-01-05 2020-02-16 2020-03-29 2021-03-29 survey and design of Patlaiya Based Selection l -Dhalkebar-Kamala Roads an d Bridges. NP-DOR-142208-CS-CQS-TA- 1 / Cosnsulting services for T Consultant Qualifi Open - Internationa ransaction Advisory Service f IDA / 63170 Post 300,000.00 0.00 Canceled 2019-11-21 2019-11-28 2020-01-02 2020-02-16 2020-04-09 2021-03-09 cation Selection l or the Improvement of Nagd hunga - Naubise - Mugling Ro ad. NP-DOR-163013-CS-QCBS-E Quality And Cost- Under Implement SMF-01 / Consulting Service f IDA / 63170 Post Open - National 200,000.00 0.00 2020-04-27 2020-09-08 2020-05-18 2020-10-16 2020-07-01 2021-02-17 2020-07-29 2021-03-22 2020-08-28 2021-07-11 2020-10-02 2020-11-06 2021-08-03 Based Selection ation or ESMF Update. NP-DOR-166310-CS-CQS-SIG B-01 / Hiring Consulting firm Consultant Qualifi Pending Impleme IDA / 63170 Post Limited 100,000.00 0.00 2020-04-30 2020-05-15 2020-07-04 2020-07-28 2020-09-26 for Conceptual design of ten cation Selection ntation approved Signature Bridges. NP-DOR-193085-CS-QCBS-IE Quality And Cost- Open - Internationa -01 / Baseline and Endline Su IDA / 63170 Post 474,947.71 0.00 Signed 2021-05-10 2021-06-22 2021-05-31 2021-06-28 2021-07-31 2022-02-07 2021-08-28 2022-04-04 2021-09-30 2022-11-07 2021-11-08 2022-12-13 2021-12-13 2023-06-15 Based Selection l rvey- for BIMP II Impact Evalu ation NP-DOR-BIMPII-CS-QCBS-PP- 01 / Feasibility Study for the Upgradation of Gorusinghe-G Quality And Cost- Open - Internationa Under Implement IDA / 63170 Prior 2,400,000.00 0.00 2021-12-15 2022-02-09 2021-12-28 2022-03-10 2022-02-10 2023-03-03 2022-03-10 2023-05-07 2022-04-09 2022-05-24 2022-06-15 2023-06-15 addachauki Section of East Based Selection l ation West Highway (Mahendra Hig hway and Detailed Design of Priority sub-section NP-DOR-BIMPII-CS-QCBS-PP- 02 / Environmental and Socia l Assessment of four laning of Gorusinghe-Gaddachauki and Quality And Cost- Open - Internationa IDA / 63170 Post 500,000.00 0.00 Canceled 2021-12-15 2021-12-22 2021-12-22 2022-01-27 2022-02-24 2022-03-16 2022-04-10 2022-05-15 2023-06-15 Bridges of East-West Highwa Based Selection l y (Mahendra Highway) and E nvironmental and Social Imp act Assessment (ESIA) of prio rity sub-section/s NP-DOR-BIMPII-CS-QCBS-PP- Quality And Cost- Open - Internationa 03 / Design of Major Mainten IDA / 63170 Post 193,000.00 0.00 Canceled 2021-12-21 2021-12-22 2022-01-11 2022-02-18 2022-02-24 2022-03-24 2022-04-23 2022-05-28 2022-07-02 2022-10-30 Based Selection l ance/Rehabilitation Works of SRN Bridges NP-DOR-BIMPII-CS-QCBS-PP- Quality And Cost- Open - Internationa 03-2 / Design of Major Mainte IDA / 63170 Post 193,000.00 0.00 Canceled 2022-09-30 2022-11-13 2022-10-27 2022-12-02 2022-12-27 2023-01-26 2023-02-25 2023-04-01 2023-05-06 2023-09-03 Based Selection l nace/Rehabilitation works of SRN Bridges. Page 1 NP-DOR-BIMPII-CS-QCBS-BM Quality And Cost- S-04 / Updating the Bridge In IDA / 63170 Post Open - National 225,085.00 0.00 Canceled 2022-11-22 2022-11-16 2022-12-07 2023-02-20 2023-03-22 2023-04-21 2023-05-16 2023-06-15 2024-05-10 Based Selection ventory in Bridge Manageme nt System. NP-DOR-BIMPII-CS-QCBS-BM Quality And Cost- Under Implement S-04-02 / Updating the Bridg IDA / 63170 Post Open - National 225,085.00 0.00 2022-12-01 2022-11-27 2022-12-16 2022-12-02 2023-03-01 2023-04-09 2023-03-31 2023-04-30 2023-05-30 2023-07-14 2024-06-08 Based Selection ation e Inventory in Bridge Manage ment System. NP-DOR-BIMPII-CS-QCBS-ESI A-01 / Environmental and So cial Screening of Chanauta - Gaddachauki Road section in Quality And Cost- Open - Internationa cluding Bridges of East-West IDA / 63170 Post 462,600.00 0.00 Canceled 2023-02-01 2023-02-03 2023-02-08 2023-03-09 2023-04-08 2023-04-22 2023-05-13 2023-06-17 2024-07-11 Based Selection l Highway (Mahendra Highway ) and Environmental and Soc ial Impact Assessment (ESIA) of selected priority subsectio n/s within Chanauta - Gaddac hauki Road NP-DOR-BIMPII-CS-QCBS-CM A-05 / Consulting Service for Quality And Cost- IDA / 63170 Post Open - National 73,998.00 0.00 Canceled 2022-11-23 2022-11-28 2022-12-14 2022-11-30 2023-02-12 2023-03-14 2023-04-13 2023-05-18 2023-06-22 2023-12-19 Contractor's Market Assessm Based Selection ent Study (CMAs) of the Brid ge works. NP-DOR-BIMPII-CS-QCBS-ESI A-02 / Environmental and So cial Screening of Chandrauta - Gaddachauki Road section i Quality And Cost- Open - Internationa Under Implement ncluding Bridges of East-Wes IDA / 63170 Post 433,130.58 0.00 2023-03-12 2023-03-23 2023-03-19 2023-04-17 2023-06-04 2023-05-29 2023-06-15 2023-07-06 2023-08-10 2024-06-05 Based Selection l ation t Highway (Mahendra Highwa y) and Environmental and So cial Impact Assessment (ESIA ) of selected priority subsecti on/s within Chandrauta - Gad dachauki INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NP-DOR-BIMP-CS-IND-2 / Sel ection of International Individ Individual Consult Under Implement IDA / 63170 Post Limited 80,000.00 0.00 2019-07-21 2019-09-27 2019-07-26 2019-08-16 2019-09-20 2020-03-18 ual Consultant for Road Safet ant Selection ation y Support(Road Safety Exper t). NP-DOR-151734-CS-INDV-03 / Selection of consultant for Individual Consult IDA / 63170 Post Limited 54,600.00 50,483.44 Completed 2019-12-30 2020-01-14 2020-01-04 2020-02-02 2020-01-11 2020-03-27 2020-01-25 2020-04-15 2023-07-08 2020-04-15 bridge design check and brid ant Selection ge design review and trainin g to new Engineers. NP-DOR-BIMPII-CS-IC-04 / In dividual Consultant for Revie wing and Updating Environm ental and Social Impact Asse Individual Consult IDA / 63170 Post Limited 61,000.00 0.00 Signed 2021-12-23 2021-12-24 2021-12-25 2022-09-28 2021-12-26 2022-09-28 2021-12-27 2022-07-15 ssment (ESIA) and Preparatio ant Selection n of Environmental and Socia l Management Framework (E SMF) of Nepal East West Hig hway (Butwal-Gorusinghe Se ction), BBIN MPA NP-DOR-BIMPII-CS-INDV-CDE / Consulting Services for Hirin Individual Consult Under Implement IDA / 63170 Post Limited 15,000.00 0.00 2023-06-02 2023-06-02 2023-06-07 2023-06-28 2023-08-02 2024-08-02 g of Capacity Development E ant Selection ation xpert (Individual Consultant) NP-DOR-BIMPII-CS-INDV-PE / Consulting Services for hiring Individual Consult Under Implement IDA / 63170 Prior Limited 15,000.00 0.00 2023-06-04 2023-06-02 2023-06-09 2023-06-30 2023-08-04 2024-08-05 of Procurement and Contract ant Selection ation Management Expert (Individu al Consultant) NP-DOR-126177-CS-INDV-01 / Selection of international in dividual consultant for bridge Individual Consult Direct - Internation Under Implement design support (Bridge desig IDA / 63170 Post 80,000.00 0.00 2019-08-30 2023-06-25 2019-09-11 2019-10-02 2019-11-06 2021-11-05 ant Selection al ation n Expert) ,his/her net input w ill be 180 days over a gross p eriod of 12 months and the s election method is direct. Page 2 PROCUREMENT PLAN (Textual Part) Project information: Republic of Serbia, Montenegro, Bosnia and Herzegovina – Sava and Drina Rivers Corridors Integrated Development Program – P168862 Date of the Procurement Plan: October 6, 2020 Period covered by this Procurement Plan: 2020 – 2023 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Not Applicable Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – Not Applicable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Not Applicable PROCUREMENT Western Balkans : Sava and Drina Rivers Corridors Integrated Development Program PLAN General Information Country: Western Balkans 2021-10-25 Bank’s Approval Date of the Original Procurement Plan: 2023-06-05 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P168862 GPN Date: 2021-04-20 Project Name: Sava and Drina Rivers Corridors Integrated Development Program Loan / Credit No: IBRD / 91290 Agriculture Project Coordination Unit Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned National Procure BA-RS-SDIP-W-SSS-21-011 / Integrated Management and ment Document - Reforestation in torrent creek Under Imple 2023-01-1 IBRD / 91290 Development of the Sava Ri Post Direct Selection Direct 1 Envelope proce 540,827.00 0.00 2021-10-25 2021-09-22 2021-10-25 2021-10-25 2021-12-02 s basins - the Vrbanja and Vr mentation 3 ver Corridor ss (Non Bank-SPD bas River tributaries ) BA-RS-SDIP-W- SSS -21-013 / National Procure Estblishment of energy plant Integrated Management and ment Document - Under Imple 2023-01-1 ations and poplar plantations IBRD / 91290 Development of the Sava Ri Post Direct Selection Direct 1 Envelope proce 145,135.00 0.00 2021-10-26 2021-11-11 2021-10-26 2021-10-25 2021-12-12 mentation 1 in the Sava and Vrbas River v ver Corridor ss (Non Bank-SPD alleys inundation area in RS, ) 14.2 ha BA-RS-SDIP-G-RFQ-22-016 / Integrated Management and Request for Quota Request for Quota Single Stage - One E Under Imple 2022-10-3 Reconstruction of exsisting c IBRD / 91290 Development of the Sava Ri Post Open - National tions (Non Bank-S 45,000.00 0.00 2022-03-08 2022-05-03 tions nvelope mentation 0 old store ver Corridor PD) BA-RS-SDIP-D&W-ISD-22-00 9 / Main Circumferential Cha Request for Bids - nnel (GOK) between the mou Integrated Management and Open - Internationa Single Stage - One E Works (without pr 2023-01-1 ths of the Sava river and the IBRD / 91290 Development of the Sava Ri Post Request for Bids 5,700,831.00 0.00 Canceled 2022-03-30 2022-04-04 2022-05-16 2022-06-15 2022-07-20 l nvelope equalification) SP 6 Majevica peripheral canal - D ver Corridor D esign (incl Environmental & S ocial Impact Assesment) and Construction National Procure BA-RS-SDIP-W-RFB-22-025 / Integrated Management and ment Document - Construction of the bridge in Single Stage - One E Under Imple 2023-06-0 IBRD / 91290 Development of the Sava Ri Post Request for Bids Open - National 1 Envelope proce 662,545.00 0.00 2022-08-15 2022-09-27 2022-08-20 2023-03-07 2022-10-01 2022-10-31 2022-12-05 municipality Čelinac over riv nvelope mentation 3 ver Corridor ss (Non Bank-SPD er Vrbanja and access road ) BA-RS-SDIP-D&W-ISD-22-00 Request for Bids - 9.1 / Main Circumferential Ch Integrated Management and Single Stage - One E Works (without pr 2023-06-1 annel (GOK) between the mo IBRD / 91290 Development of the Sava Ri Post Request for Bids Open - National 4,386,267.00 0.00 Canceled 2022-08-29 2022-09-03 2022-10-15 2022-11-14 2022-12-19 nvelope equalification) SP 7 uths of the Sava river and th ver Corridor D e Majevica peripheral canal - Design & Construction BA-RS-SDIP-W-RFQ-22-028 / Integrated Management and Request for Quota Facility for drying and finishin Request for Quota Single Stage - One E 2023-06-2 IBRD / 91290 Development of the Sava Ri Post Open - National tions (Non Bank-S 35,356.00 0.00 Canceled 2022-10-31 2022-12-26 g cones and fruits, Distributiv tions nvelope 4 ver Corridor PD) e / sales facility, Shading sys tem BA-RS-SDIP-D&W-ISD-22-00 National Procure 9.2 / Main Circumferential Ch Integrated Management and ment Document - Open - Internationa Single Stage - Two E Under Imple 2024-02-2 annel (GOK) between the mo IBRD / 91290 Development of the Sava Ri Post Request for Bids 2 Envelope proce 4,604,053.00 0.00 2023-03-29 2023-05-29 2023-04-03 2023-05-29 2023-05-15 2023-07-28 2023-09-01 l nvelope mentation 8 uths of the Sava river and th ver Corridor ss (Non Bank-SPD e Majevica peripheral canal - ) Design & Construction BA-RS-SDIP-W-RFQ-22-030 / Facility for drying and finishin g cones and fruits, Distributiv Integrated Management and Request for Quota Request for Quota Single Stage - One E Pending Imp 2023-12-2 e / sales facility, Shading syst IBRD / 91290 Development of the Sava Ri Post Open - National tions (Non Bank-S 109,555.00 0.00 2023-05-02 2023-06-27 tions nvelope lementation 4 em with Heaters for greenho ver Corridor PD) use heating and Constructio n of an accumulation within t he irrigation system Request for Bids - Integrated Management and BA-RS-SDIP-W-RFB-23-031 / Open - Internationa Single Stage - One E Works (without pr 17,506,937.5 Pending Imp 2024-03-2 IBRD / 91290 Development of the Sava Ri Prior Request for Bids 0.00 2023-06-08 2023-06-13 2023-07-25 2023-08-24 2023-09-28 Turjanica river regulation l nvelope equalification) SP 0 lementation 6 ver Corridor D GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BA-RS-SDIP-G-RFQ-21-014 / Integrated Management and Tractor vith double traction ( Request for Quota Single Stage - One E Under Imple IBRD / 91290 Development of the Sava Ri Post Open - National 62,124.00 0.00 2021-12-25 2022-02-19 2022-02-20 >100 hp) with vibrating plow tions nvelope mentation ver Corridor for removing seedlings BA-RS-SDIP-G-RFQ-21-015 / Integrated Management and Request for Quota Single Stage - One E Forklift (Load Capacity 2-2.5 IBRD / 91290 Development of the Sava Ri Post Open - National 79,000.00 0.00 Canceled 2021-12-28 2022-02-22 2022-02-22 tions nvelope t), Mini excavator (with conn ver Corridor ectors) BA-RS-SDIP-G-RFQ-22-017 / Integrated Management and Request for Quota Single Stage - One E Pending Impl Enlargement of parent tree c IBRD / 91290 Development of the Sava Ri Post Open - National 16,332.00 0.00 2022-03-19 2022-05-14 2022-11-10 tions nvelope ementation ollection ver Corridor BA-RS-SDIP-G-RFQ-22-019 / Forklift for PFE "Sume Republ Integrated Management and Request for Quota Single Stage - One E Pending Impl ike Srpske" Seeds and Seedli IBRD / 91290 Development of the Sava Ri Post Open - National 18,464.00 0.00 2022-05-11 2022-07-05 2023-01-01 tions nvelope ementation ngs Center - nursery producti ver Corridor on under the B&H SDIP Proje ct BA-RS-SDIP-G-RFQ-22-020 / Integrated Management and Request for Quota Single Stage - One E Under Imple Cargo wehicle for seedling an IBRD / 91290 Development of the Sava Ri Post Open - National 21,100.00 0.00 2022-05-11 2022-07-05 2023-01-01 tions nvelope mentation d equipemet transportation ver Corridor BA-RS-SDIP-G-RFQ-22-021 / I rrigation pump for PFE "Sum Integrated Management and Request for Quota Single Stage - One E e Republike Srpske" Seeds a IBRD / 91290 Development of the Sava Ri Post Open - National 4,200.00 0.00 Canceled 2022-05-11 2022-07-05 2023-01-01 tions nvelope nd Seedlings Center - nurser ver Corridor y production under the B&H SDIP Project Page 1 BA-RS-SDIP-G-RFQ-22-026 / Integrated Management and Request for Quota Single Stage - One E Heaters for greenhouse heati IBRD / 91290 Development of the Sava Ri Post Open - National 8,920.00 0.00 Canceled 2022-10-04 2022-10-14 2022-11-29 2023-05-28 tions nvelope ng ver Corridor BA-RS-SDIP-G-RFQ-22-027 / I Integrated Management and Request for Quota Single Stage - One E Under Imple rrigation pump (P> 5 bar) wit IBRD / 91290 Development of the Sava Ri Post Open - National 15,900.00 0.00 2022-10-04 2022-10-14 2022-11-29 2023-05-28 tions nvelope mentation h dispensers ver Corridor BA-RS-SDIP-G-RFQ-22-022 / Integrated Management and Request for Quota Single Stage - One E Pending Impl Procurement of boat for the IBRD / 91290 Development of the Sava Ri Post Open - National 39,300.00 0.00 2022-10-31 2022-12-26 2023-06-24 tions nvelope ementation needs of RS MoT&C / Captain ver Corridor cy in Brcko NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BA-RS-SDIP-NCS-RFB-22-024 Integrated Management and / Examination of status of the Open - Internationa Single Stage - One E Under Imple IBRD / 91290 Development of the Sava Ri Post Request for Bids 1,834,740.00 0.00 2022-08-24 2023-03-09 2022-08-29 2023-03-08 2022-10-10 2022-11-09 2022-12-14 2023-06-12 Sava dyke and a portion of th l nvelope mentation ver Corridor e Una dyke in Republika Srps ka CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BA-RS-SDIP- CS-QCBS-22-01 2 / developing a set of docu ments for the flow regime co Integrated Management and ntrol and regulation of the Tu Quality And Cost- IBRD / 91290 Development of the Sava Ri Post Open - National 260,000.00 198,997.75 Signed 2022-02-10 2022-02-18 2022-03-03 2022-04-16 2022-04-19 2022-05-14 2022-06-01 2022-06-13 2022-06-15 2022-07-18 2022-07-06 2022-08-22 2022-07-27 2023-08-22 rjanica channel in the Munici Based Selection ver Corridor pality of Laktasi from the con fluence with the Vrbas upstre am to the intersection with M -16-1 trunk road (total length : 8km) BA-RS-SDIP- CS-QCBS-22-02 3 / Environmental & Social Im Integrated Management and pact Assesment for Main Circ Quality And Cost- IBRD / 91290 Development of the Sava Ri Post Open - National 255,000.00 0.00 Canceled 2022-08-22 2022-09-12 2022-10-26 2022-11-23 2022-12-23 2023-01-27 2023-03-03 2024-03-02 umferential Channel (GOK) b Based Selection ver Corridor etween the mouths of the Sa va river and the Majevica per ipheral BA-RS-SDIP- CS-QCBS-22-02 3.1 / Development of Environ mental and Social Manageme nt Plan (ESMP) for Project of Integrated Management and Quality And Cost- Under Implement rehabilitation of the Main Peri IBRD / 91290 Development of the Sava Ri Post Open - National 744,000.00 0.00 2023-02-23 2023-02-28 2023-03-16 2023-04-29 2023-05-27 2023-06-26 2023-07-31 2023-09-04 2024-09-03 Based Selection ation pheral Canal (GOK) in Sembe ver Corridor rija, Bijeljina municipality; Pr oject of Turjanica flow regim e control and water course re gulation in territory of La INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BA-APCU-231849-CS-INDV / Project Preparation and Man Individual Consult Pending Impleme ENVIRONMENTAL AND SOCIA IBRD / 91290 Post Open 9,000.00 0.00 2021-04-29 2021-05-06 2021-05-07 2021-05-10 2021-11-06 agement ant Selection ntation L SAFEGUARDS EXPERT BA-RS-SDIP-IC-DC-22-029 / B A-RS-SDIP-IC-DC-23-029.1 Pr Project Preparation and Man Individual Consult Under Implement oject Manager for the Sava a IBRD / 91290 Post Open - National 108,236.00 0.00 2023-02-20 2023-02-08 2023-04-10 2023-04-25 2023-05-01 2023-06-05 2024-06-03 agement ant Selection ation nd Drina Rivers Corridors Int egrated Development Projec Page 2 PROCUREMENT PLAN (Textual Part) Project information: Papua New Guinea (PNG), PNG Agriculture Commercialization and Diversification Strategy, P-166222 Project Implementation agency: Department of Agriculture and Livestock (DAL); Cocoa Board (CB); and Coffee Industry Corporation (CIC) Date of the Procurement Plan: February 13, 2020 Period covered by this Procurement Plan: February 2020 – to August 2021 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016, revised November 2017 and August 2018) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the National Procurement Act 2018, No. 12 of 2018, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. National preferences Eligibility: Eligibility to participate in a procurement process for and to be awarded a Bank financed contract shall be as defined under paragraphs 3.21-3.23 of the Procurement Regulations; accordingly, no bidder or potential bidder shall be declared ineligible for contracts financed by the Bank for reasons other than those provided in the said paragraphs. Foreign bidders shall be eligible to participate in bidding under the same conditions as national bidders. No domestic preference shall be granted in bid evaluation on the basis of bidder’s nationality, origin of goods or services, and/or preferential programs. Registration of bidders as Registration of bidders: condition for bidding Registration shall not be used to assess bidders’ qualifications. A foreign bidder shall not be required to register as a condition for submitting its bid, and a foreign bidder recommended for contract award shall be given a reasonable opportunity to register, with the reasonable cooperation of the Recipient, prior to contract signing. Procurement documents Procurement Documents: Templates of procurement documents, including contract forms, acceptable to the Association shall be used for all procurement financed by the Project. Document Fees Bidding Document Fees: A fee for bidding documents if applied must be reasonable and is to be used to offset the actual costs associated with reproduction of large bidding documents and associated plans and drawings. It is not to be used to generate revenue, or to limit or restrict participation in procurement processes. Bidding document fees are not to be charged for the procurement of consulting services (firms and individual), non-consulting services, or goods. Fraud and Corruption Fraud and Corruption: The procurement documents shall require that bidders submitting bids present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights. Negotiations and Cancellation of all bids: cancellation of All bids (or the sole bid if only one bid is procurement process received) shall not be rejected, the procurement process shall not be cancelled, and new bids shall not be solicited without the Bank’s prior written concurrence. Complaints Handling Complaints Review Mechanism: The Recipient shall establish and implement an effective, fair and timely complaints review mechanism allowing bidders to complain and to have their complaints handled in a timely manner. Until an adequate complaints review mechanism (as assessed by the Bank) is established the Bank’s review mechanism as set out in the Procurement Regulations will apply. Contract Award Notice Publication of Contract Award Notice: For purposes of Article 36(5) of the Act, within one month from award, a notice of all procurement contract awards shall include, at a minimum as relevant and applicable for each procurement method (a) the name of each bidder that submitted a bid; (b) bid prices as read out at bid opening; (c) evaluated prices of each bid that was evaluated; (d) the names of bidders whose bids were either rejected as nonresponsive or not meeting qualification criteria, or not evaluated, with the reasons thereof; and (e) the name of the winning bidder, the final total contract price, as well as the duration and a summary of the scope of the contract. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. The above captioned conditions also apply when approaching the international market. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Not Applicable Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations: Not Applicable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: Not Applicable; Works: Not Applicable PROCUREMENT Papua New Guinea : PNG Agriculture Commercialization and Diversification Project PLAN General Information Country: Papua New Guinea 2021-07-23 Bank’s Approval Date of the Original Procurement Plan: 2023-06-04 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P166222 GPN Date: 2020-12-12 Project Name: PNG Agriculture Commercialization and Diversification Project Loan / Credit No: IDA / 64660 Cocoa Board Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned National Procure PG-CB-365240-CW-RFQ / Co Institutional Capacity Buildin Request for Quota Single Stage - One E ment Document - Pending Imp 2024-02-2 IDA / 64660 Post Open - National 800,000.00 0.00 2023-07-08 2023-09-02 coa Board Office Extension g tions nvelope 1 Envelope proce lementation 9 ss (Non Bank-SPD ) Request for Bids - PG-CB-365241-CW-RFB / RE Single Stage - One E Small Works SPD Pending Imp 2024-04-1 HABILITATION OF TEHOBUIN- IDA / 64660 Agriculture Feeder Roads Post Request for Bids Open - National 1,400,000.00 0.00 2023-06-26 2023-07-01 2023-08-12 2023-09-11 2023-10-16 nvelope (1 envelope proce lementation 3 SIPOTAVAI FEEDER ROAD ss) GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PG-CB-236465-CS-INDV / Se Project Management and Mo Individual Consult IDA / 64660 Post Open 180,000.00 95,473.98 Signed 2021-06-01 2021-12-03 2021-07-20 2022-03-09 2021-08-10 2022-04-03 2021-09-14 2022-04-06 2022-03-13 nior Procurement Officer, Coc nitoring and Evaluation ant Selection oa PMU PG-CB-236457-CS-INDV / Pro Project Management and Mo Individual Consult IDA / 64660 Prior Open 1,200,000.00 0.00 Canceled 2021-06-01 2021-07-20 2021-08-10 2021-09-14 2022-03-13 ject Manager, Cocoa PMU nitoring and Evaluation ant Selection PG-CB-236483-CS-INDV / Mo Project Management and Mo Individual Consult nitoring, Evaluation and Surv IDA / 64660 Post Open 220,000.00 0.00 Signed 2021-06-01 2021-12-02 2021-07-20 2022-04-21 2021-08-10 2022-04-25 2021-09-14 2022-03-13 nitoring and Evaluation ant Selection ey Officer (MESO) PG-CB-236466-CS-INDV / Pro Individual Consult ductive Partnership Coordina IDA / 64660 Productive Partnerships Prior Open 360,000.00 162,547.92 Signed 2021-06-01 2021-12-02 2021-07-20 2022-07-13 2021-08-10 2022-08-09 2021-09-14 2022-09-06 2022-03-13 ant Selection tor, Cocoa PMU PG-CB-248924-CS-INDV / En Project Management and Mo Individual Consult IDA / 64660 Post Open 210,000.00 102,862.53 Terminated 2021-08-18 2021-12-03 2021-10-06 2022-03-10 2021-10-27 2022-03-10 2021-12-01 2022-03-15 2022-05-30 vironmental and Social Office nitoring and Evaluation ant Selection r PG-CB-255259-CS-INDV / Pro Project Management and Mo Individual Consult ject Manager, Cocoa Project IDA / 64660 Prior Open 540,000.00 0.00 Canceled 2021-09-28 2021-11-16 2021-12-07 2022-01-11 2022-07-10 nitoring and Evaluation ant Selection Management Unit PG-CB-260469-CS-INDV / Pro Project Management and Mo Individual Consult ject Manager, Cocoa Project IDA / 64660 Prior Open 424,000.00 0.00 Signed 2021-10-29 2021-11-10 2021-12-17 2022-08-16 2022-01-07 2022-09-07 2022-02-11 2023-05-21 2022-08-10 nitoring and Evaluation ant Selection Management Unit PG-CB-236464-CS-INDV / Se Project Management and Mo Individual Consult IDA / 64660 Prior Open 420,000.00 0.00 Canceled 2021-08-05 2021-09-23 2021-10-14 2021-11-18 2022-05-17 nior Finance Officer, Cocoa P nitoring and Evaluation ant Selection MU PG-CB-266764-CS-INDV / Se Project Management and Mo Individual Consult IDA / 64660 Post Open 240,000.00 105,303.92 Signed 2021-12-07 2021-12-07 2022-01-25 2022-03-01 2022-02-15 2022-02-28 2022-03-22 2022-03-01 2025-12-01 nior Finance Officer, Cocoa P nitoring and Evaluation ant Selection MU PG-CB-236467-CS-INDV / Se Individual Consult IDA / 64660 Agriculture Feeder Roads Prior Open 377,000.00 0.00 Canceled 2021-08-05 2021-09-23 2021-10-14 2021-11-18 2022-05-17 nior Engineer, Cocoa PMU ant Selection PG-CB-266765-CS-INDV / Co Individual Consult Under Implement IDA / 64660 Agriculture Feeder Roads Post Open 295,000.00 0.00 2021-12-08 2022-11-21 2022-01-26 2022-02-16 2022-03-23 2025-12-02 coa PMU Senior Engineer ant Selection ation PG-CB-300445-CS-INDV / Pro Project Management and Mo Individual Consult ductive Partnerships Officer- IDA / 64660 Post Open - National 120,000.00 0.00 Signed 2022-08-01 2022-07-31 2022-09-19 2023-01-17 2022-10-10 2023-02-28 2022-11-14 2024-11-03 nitoring and Evaluation ant Selection PMU Madang PG-CB-300446-CS-INDV / Par Project Management and Mo Individual Consult IDA / 64660 Post Open - National 90,000.00 0.00 Canceled 2022-08-01 2022-09-19 2022-10-10 2022-11-14 2024-11-03 tnership Finance Officer nitoring and Evaluation ant Selection PG-CB-300447-CS-INDV / MI Project Management and Mo Individual Consult IDA / 64660 Post Open - National 167,000.00 0.00 Signed 2022-08-01 2022-08-02 2022-09-19 2023-02-14 2022-10-10 2023-02-28 2022-11-14 2024-11-03 S Officer PMU Kokopo nitoring and Evaluation ant Selection PG-CB-300227-CS-INDV / Ad Project Management and Mo Individual Consult IDA / 64660 Post Open - National 49,308.00 0.00 Signed 2022-08-01 2022-08-17 2022-09-19 2023-01-17 2022-10-10 2023-02-02 2022-11-14 2024-11-03 ministrative Assistant nitoring and Evaluation ant Selection Page 1 PG-CB-300444-CS-INDV / Pro ductive Partnership Officer-E Project Management and Mo Individual Consult IDA / 64660 Post Open - National 143,000.00 0.00 Signed 2022-08-01 2022-08-17 2022-09-19 2023-01-17 2022-10-10 2023-02-28 2022-11-14 2024-11-03 ast New Britain Province (EN nitoring and Evaluation ant Selection B), Autonomous Region of Bo ugainville (ARoB) PG-CB-317954-CS-INDV / En Project Management and Mo Individual Consult vironmental and Social Office IDA / 64660 Post Open - National 200,000.00 0.00 Signed 2022-09-30 2022-11-20 2022-11-18 2023-05-15 2022-12-09 2023-05-30 2023-01-13 2025-01-02 nitoring and Evaluation ant Selection r Cocoa PMU PG-CB-330713-CS-INDV / Fin Project Management and Mo Individual Consult IDA / 64660 Post Open - National 86,614.00 0.00 Canceled 2022-12-08 2023-01-26 2023-02-16 2023-03-23 2023-09-19 ance Assistant nitoring and Evaluation ant Selection PG-CB-344966-CS-INDV / MS Individual Consult Under Implement IDA / 64660 Productive Partnerships Post Open - National 143,136.00 0.00 2023-02-23 2023-03-31 2023-04-13 2023-05-04 2023-06-08 2023-12-05 ME Development Officer ant Selection ation PG-CB-344968-CS-INDV / Inf Project Management and Mo Individual Consult IDA / 64660 Post Open - National 240,000.00 0.00 Canceled 2023-02-23 2023-03-30 2023-04-13 2023-05-04 2023-06-08 2023-12-05 ormation Communications Of nitoring and Evaluation ant Selection ficer PG-CB-363608-CS-INDV / Inf Project Management and Mo Individual Consult Pending Impleme IDA / 64660 Post Limited 240,000.00 0.00 2023-05-29 2023-06-03 2023-06-24 2023-07-29 2024-01-25 ormation Communications Of nitoring and Evaluation ant Selection ntation ficer PG-CB-363610-CS-INDV / Fin Project Management and Mo Individual Consult Pending Impleme IDA / 64660 Post Limited 86,614.00 0.00 2023-06-30 2023-07-05 2023-07-26 2023-08-30 2024-02-26 ance Assistant nitoring and Evaluation ant Selection ntation PG-CB-363611-CS-INDV / Par Individual Consult Pending Impleme IDA / 64660 Productive Partnerships Post Limited 90,000.00 0.00 2023-08-01 2023-08-06 2023-08-27 2023-10-01 2024-03-29 tnership Finance Officer ant Selection ntation Page 2 PROCUREMENT PLAN (Textual Part) Project information: Brazil: Integrated Landscape Management in the Cerrado Biome Project – P164602 Project Implementation agency: DEUTSCHE GESELLSCHAFT FÜR INTERNATIONALE ZUSAMMENARBEIT GmbH (GIZ) Date of the Procurement Plan: August 21, 2018 Period covered by this Procurement Plan: October 2018- March 2020 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in [insert appropriate references to the national procurement legislation], such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. List only the applicable conditions required to ensure consistency with paragraph 5.4 of the Procurement Regulations. If no conditions apply, delete the phrase “and the following conditions”. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. Otherwise state “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables Otherwise state “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Specify for each Goods: [is not applicable/is applicable for those contracts identified in the Procurement Plan tables]; Works: [is not applicable/is applicable for those contracts identified in the Procurement Plan tables] Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations is Applicable. [Include this sentence only if the Bank has formally agreed to provide the Borrower with HEIS. Otherwise delete] Other Relevant Procurement Information. Provide any other relevant procurement information such as procedures for CDD components, Procurement in Situations of Urgent Need of Assistance or Capacity Constraints etc. PROCUREMENT Brazil : Integrated Landscape Management in the Cerrado Biome Project PLAN General Information Country: Brazil 2018-09-03 Bank’s Approval Date of the Original Procurement Plan: Revised Plan Date(s): (comma delineated, leave blank2023-06-02 if none) Project ID: P164602 GPN Date: Project Name: Integrated Landscape Management in the Cerrado Biome Project Loan / Credit No: / , TF / A8532 German Society for International Cooperation Executing Agency(ies): WORKS Activity Reference No. / Procureme Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH Ri Process S Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Comple Description Component Review Type Method nt Docume ount (US$ and Recommendatio Signed Contract o. h cess (Y/N) sk tatus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes tion nt Type ) n for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual EMBRAPA 2 BR-GIZ-76279- CW-APA / Contratação de e Mainstreaning Landscape Pr Alternative Procur Single Stage - One 2019-05-2 mpresa da área de construç / actices into Selected Water Post ement Arrangem Open - National 0.00 Canceled 2018-10-01 2018-10-06 2018-10-27 2018-11-03 2018-11-24 Envelope 3 ão civil para execução de ref sheds ent orma do auditório e salas de aula da EMBRAPA Cerrados. EMBRAPA 2 BR-GIZ-76268- CW-APA / Contratação de e mpresa da área de construç Mainstreaning Landscape Pr Alternative Procur Single Stage - One 2019-05-2 ão civil para reforma e adeq / actices into Selected Water Post ement Arrangem Open - National 0.00 Canceled 2018-10-01 2018-10-06 2018-10-27 2018-11-03 2018-11-24 Envelope 3 uação do Viveiro de P&D da sheds ent Embrapa Cerrados para ope rar também como Unidade de Aprendizagem EMBRAPA 2 BR-GIZ-76209- CW-APA / Contratação de e mpresa da área de construç Mainstreaning Landscape Pr Alternative Procur Single Stage - One 2019-05-2 ão civil para reforma e adeq / actices into Selected Water Post ement Arrangem Open - National 0.00 Canceled 2018-10-01 2018-10-06 2018-10-27 2018-11-03 2018-11-24 Envelope 3 uação e manutenção do Stu sheds ent dio para produção/gravação de vídeos para TT, inclusive EAD, da Embrapa Cerrados EMBRAPA BR-GIZ-242453-C W-RFQ / Contratação de em Institutional Development a Other (with f Request for Quot Single Stage - One 2022-06-0 presa da área de construção TF / A8532 nd Capacity Building for Lan Post Open - National ield for expla 0.00 Canceled 2021-10-09 2021-12-04 ations Envelope 2 civil para reforma e adequaç dscape Management nation) ão do Viveiro de Mudas da E mbrapa Cerrados. EMBRAPA BR-GIZ-161546-C W-RFQ / Contratação de em Institutional Development a Other (with f Request for Quot Single Stage - One Under Impl 2023-07-2 presa para obra de reforma TF / A8532 nd Capacity Building for Lan Post Open - National ield for expla 0.00 2022-12-05 2023-01-30 ations Envelope ementation 9 de construção civil de auditó dscape Management nation) rio para capacitação na Emb rapa Cerrados.... GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendatio Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes n for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual EMBRAPA 1 BR-GIZ-76233- GO-APA / Aquisição de equip amentos de informatica com Institutional Development a Alternative Procur Single Stage - One putadores etc.. Para a equip / nd Capacity Building for Lan Post ement Arrangem Open - National 0.00 Canceled 2018-10-10 2018-10-15 2018-11-05 2018-11-12 2018-12-03 2019-06-01 Envelope e de processamento e siste dscape Management ent matização da informação te cnológica da paisagem da E mbrapa Cerrados. EMBRAPA 2 BR-GIZ-76255- GO-APA / Aquisição de equip Mainstreaning Landscape Pr Alternative Procur Single Stage - One amentos de informatica com / actices into Selected Water Post ement Arrangem Open - National 0.00 Canceled 2018-10-10 2018-10-15 2018-11-05 2018-11-12 2018-12-03 2019-06-01 Envelope putadores, etc.. para a sala sheds ent de treinamento (EAD) da Em brapa Cerrados. EMBRAPA 1 BR-GIZ-76272- GO-APA / Aquisição de maqu inas e equipamentos tecnico Institutional Development a Alternative Procur Single Stage - One s para analises de campo pa / nd Capacity Building for Lan Post ement Arrangem Open - National 0.00 Canceled 2018-10-10 2018-10-15 2018-11-05 2018-11-12 2018-12-03 2019-06-01 Envelope ra avaliar o processamento dscape Management ent e sistematização da informa ção tecnológica da paisage m da Embrapa Cerrados. EMBRAPA 2 BR-GIZ-76207- Mainstreaning Landscape Pr Alternative Procur GO-APA / Aquisição de mobil Single Stage - One / actices into Selected Water Post ement Arrangem Open - National 0.00 Canceled 2018-10-10 2018-10-15 2018-11-05 2018-11-12 2018-12-03 2019-06-01 iário para auditorio e sala de Envelope sheds ent treinamento (EAD) da Embr apa Cerrados. EMBRAPA 2 BR-GIZ-76257- GO-APA / Aquisição de mate Mainstreaning Landscape Pr Alternative Procur Single Stage - One rial didatico impresso para d / actices into Selected Water Post ement Arrangem Open - National 0.00 Canceled 2019-03-10 2019-03-15 2019-04-05 2019-04-12 2019-05-03 2019-10-30 Envelope istribuição nos cursos de co sheds ent nservação para os diferente s atores/públicos. EMBRAPA 1 BR-GIZ-76283- GO-APA / Aquisição de equip Institutional Development a Alternative Procur Single Stage - One amentos eletroeletronicos p / nd Capacity Building for Lan Post ement Arrangem Open - National 0.00 Canceled 2019-01-20 2019-01-25 2019-02-15 2019-02-22 2019-03-15 2019-09-11 Envelope ara o auditorio e as salas de dscape Management ent treinamento da Embrapa C errados. EMBRAPA 2 BR-GIZ-76256- GO-APA / Aquisição de mate Mainstreaning Landscape Pr Alternative Procur rial (toner, tinta, papel etc..) Single Stage - One / actices into Selected Water Post ement Arrangem Open - National 0.00 Canceled 2018-10-01 2018-10-06 2018-10-27 2018-11-03 2018-11-24 2019-05-23 para impressao de material Envelope sheds ent didatico (audiovisual) para o s cursos de conservação par a os diferentes atores/públic os. EMBRAPA 1 BR-GIZ-76250- GO-APA / Aquisição de equip Institutional Development a Alternative Procur Single Stage - One amentos de audio visual etc / nd Capacity Building for Lan Post ement Arrangem Open - National 0.00 Canceled 2019-02-10 2019-02-15 2019-03-08 2019-03-15 2019-04-05 2019-10-02 Envelope .. para auditorio e sala de tr dscape Management ent einamento (EAD) da Embrap a Cerrados. EMBRAPA 1 BR-GIZ-76258- GO-APA / Aquisição de mate rial de consumo para estudo Institutional Development a Alternative Procur s prospectivos de cenários d Single Stage - One / nd Capacity Building for Lan Post ement Arrangem Open - National 0.00 Canceled 2019-01-20 2019-01-25 2019-02-15 2019-02-22 2019-03-15 2019-09-11 e conservação e produção c Envelope dscape Management ent om tecnologias disponíveis s obre o CAR, PRA, tecnologia s do ABC, BPAs, RAD, Legisl ação de Proteção da Vegeta ção Nativa EMBRAPA 2 BR-GIZ-76291- GO-APA / Aquisição de mate rial de consumo para a reali zação do componente de co Mainstreaning Landscape Pr Alternative Procur Single Stage - One nservação da paisagem nos / actices into Selected Water Post ement Arrangem Open - National 0.00 Canceled 2019-01-20 2019-01-25 2019-02-15 2019-02-22 2019-03-15 2019-09-11 Envelope cursos, treinamentos, dias d sheds ent e campo etc.sobre o CAR, P RA, tecnologias do ABC, BPA s, RAD, Legislação de Proteç ão da Vegetação Nativa Page 1 EMBRAPA 1 BR-GIZ-76269- GO-APA / Aquisição de comb ustível para a realização do s estudos prospectivos de c Institutional Development a Alternative Procur Single Stage - One enários e paisagens de cons / nd Capacity Building for Lan Post ement Arrangem Open - National 0.00 Canceled 2019-01-20 2019-01-25 2019-02-15 2019-02-22 2019-03-15 2019-09-11 Envelope ervação e produção com te dscape Management ent cnologias disponíveis sobre o CAR, PRA, tecnologias do ABC, BPAs, RAD, Legislação de Proteção da Vegetação N ativa EMBRAPA 2 BR-GIZ-76208- GO-APA / Aquisição de comb ustível para a realização do Mainstreaning Landscape Pr Alternative Procur s cursos e estudos de conse Single Stage - One / actices into Selected Water Post ement Arrangem Open - National 0.00 Canceled 2019-01-20 2019-01-25 2019-02-15 2019-02-22 2019-03-15 2019-09-11 rvação da paisagem nos cur Envelope sheds ent sos, treinamentos, dias de c ampo etc.sobre o CAR, PRA, tecnologias do ABC, BPAs, R AD, Legislação de Proteção da Vegetação Nativa SFB 2 BR-GIZ-76245-GO-AP Mainstreaning Landscape Pr Alternative Procur Single Stage - One A / Aquisicao de Kits promoc / actices into Selected Water Post ement Arrangem Open - National 0.00 Canceled 2019-03-15 2019-03-20 2019-04-10 2019-04-17 2019-05-08 2019-11-04 Envelope ionais de comunicacao e inf sheds ent ormativos INPE 1 BR-GIZ-76271-GO-A Institutional Development a Alternative Procur PA / Aquisição de material d Single Stage - One / nd Capacity Building for Lan Post ement Arrangem Open - National 0.00 Canceled 2018-10-15 2018-10-20 2018-11-10 2018-11-17 2018-12-08 2019-06-06 e Campo (mapeamento orbi Envelope dscape Management ent tal e análise da paisagem) INPE 1 BR-GIZ-76287-GO-A Institutional Development a Alternative Procur PA / Aquisição de Material d Single Stage - One / nd Capacity Building for Lan Post ement Arrangem Open - National 0.00 Canceled 2018-10-15 2018-10-20 2018-11-10 2018-11-17 2018-12-08 2019-06-06 e Escritório (mapeamento or Envelope dscape Management ent bital e análise da paisagem) INPE 1 BR-GIZ-76192-GO-A Institutional Development a Alternative Procur PA / Aquisição de equipame Single Stage - One / nd Capacity Building for Lan Post ement Arrangem Open - National 0.00 Canceled 2018-10-15 2018-10-20 2018-11-10 2018-11-17 2018-12-08 2019-06-06 ntos de Informática (mapea Envelope dscape Management ent mento orbital e análise da p aisagem) INPE 1 BR-GIZ-76218-GO-A Institutional Development a Alternative Procur Single Stage - One PA / Aquisição de equipame / nd Capacity Building for Lan Post ement Arrangem Open - National 0.00 Canceled 2018-10-15 2018-10-20 2018-11-10 2018-11-17 2018-12-08 2019-06-06 Envelope nto Fotográfico (mapeament dscape Management ent o orbital) GIZ 3 BR-GIZ-76225-GO-AP Project Management, Monit Alternative Procur Single Stage - One A / Aquisição de equipament / oring, Evaluation and Com Post ement Arrangem Open - National 0.00 Canceled 2018-10-15 2018-10-20 2018-11-10 2018-11-17 2018-12-08 2019-06-06 Envelope os de informática para equip munication ent e base da GIZ INPE BR-GIZ-109966-GO-RF Institutional Development a Q / Aquisição de equipamen Request for Quot Single Stage - One TF / A8532 nd Capacity Building for Lan Post Open - National 9,464.01 Signed 2019-06-08 2019-08-03 2019-07-09 2020-01-30 tos de Informática (mapeam ations Envelope dscape Management ento orbital e análise da pai sagem) INPE BR-GIZ-109967-GO-RF Institutional Development a Request for Quot Single Stage - One Q / Aquisição de equipamen TF / A8532 nd Capacity Building for Lan Post Open - National 3,003.44 Signed 2019-08-10 2019-10-05 2019-08-28 2020-04-02 ations Envelope to Fotográfico (mapeamento dscape Management orbital) GIZ BR-GIZ-109985-GO-RFQ Project Management, Monit Request for Quot Single Stage - One / Aquisição de equipamento TF / A8532 oring, Evaluation and Com Post Open - National 0.00 Canceled 2019-04-15 2019-06-10 2019-12-07 ations Envelope s de informática para equipe munication base da GIZ EMBRAPA BR-GIZ-123501-G O-RFQ / Adquirir equipamen Institutional Development a tos para edicao de videos pa Request for Quot Single Stage - One TF / A8532 nd Capacity Building for Lan Post Open - National 8,053.30 Signed 2019-08-06 2019-10-01 2019-11-12 2020-03-29 ra a Embrapa/Cerrados que ations Envelope dscape Management atenderao demandas do trei namento dos tecnicos do SE NAR GIZ-BR-GIZ-143344-GO-RFQ Project Management, Monit Request for Quot Single Stage - One / Aquisicao de uma licenca d TF / A8532 oring, Evaluation and Com Post Open - National 369.85 Signed 2019-11-16 2020-01-11 2019-11-27 2020-07-09 ations Envelope e software para gerenciame munication nto de projeto INPE BR-GIZ-161547-GO-RF Institutional Development a Request for Quot Single Stage - One Q / Equipamentos de escritó TF / A8532 nd Capacity Building for Lan Post Open - National 592.74 Signed 2020-04-06 2020-06-01 2020-04-14 2020-11-28 ations Envelope rio (ar-condicionado, cadeira dscape Management s, etc.) INPE BR-GIZ-162147-GO-RF Institutional Development a Request for Quot Single Stage - One Q / Equipamentos de inform TF / A8532 nd Capacity Building for Lan Post Open - National 1,915.01 Terminated 2020-07-10 2020-09-04 2020-03-20 2021-03-03 ations Envelope ática dscape Management EMBRAPA BR-GIZ-109842-G O-RFQ / Aquisição de combu stível para a realização dos estudos prospectivos de cen Institutional Development a Request for Quot Single Stage - One ários e paisagens de conser TF / A8532 nd Capacity Building for Lan Post Open - National 0.00 Canceled 2019-07-13 2019-09-07 2020-03-05 ations Envelope vação e produção com tecn dscape Management ologias disponíveis sobre o CAR, PRA, tecnologias do AB C, BPAs, RAD, Legislação de Proteção da Vegetação Nati va. INPE BR-GIZ-109958-GO-AP Institutional Development a A / Aquisição de Material de Request for Quot Single Stage - One TF / A8532 nd Capacity Building for Lan Post Open - National 0.00 Canceled 2019-09-07 2019-11-02 2020-04-30 Escritório (mapeamento orbi ations Envelope dscape Management tal e análise da paisagem) INPE BR-GIZ-109957-GO-RF Institutional Development a Q / Aquisição de material de Request for Quot Single Stage - One TF / A8532 nd Capacity Building for Lan Post Open - National 0.00 Canceled 2019-09-07 2019-11-02 2020-04-30 Campo (mapeamento orbital ations Envelope dscape Management e análise da paisagem) INPE BR-GIZ-201636-GO-RF Institutional Development a Request for Quot Single Stage - One Q / Aquisição de equipamen TF / A8532 nd Capacity Building for Lan Post Open - National 8,018.21 Completed 2020-11-03 2020-12-29 2021-01-28 2021-06-27 2021-01-29 ations Envelope tos de informática dscape Management EMBRAPA BR-GIZ-240326-G O-RFQ / Aquisição de Softwa re Adobe EDU Named Acrob Institutional Development a Request for Quot Single Stage - One at Pro DC for Teams - Multipl TF / A8532 nd Capacity Building for Lan Post Open - National 542.67 Completed 2021-07-03 2021-08-28 2021-07-13 2022-02-24 2021-08-12 ations Envelope ataforma ML para a Embrap dscape Management a Cerrados, parceira do Proj eto Paisagens Rurais (FIP-Pa isagens) INPE BR-GIZ-240327-GO-RF Q / Aquisição de HDs extern Institutional Development a Request for Quot Single Stage - One os portáteis para a Embrapa TF / A8532 nd Capacity Building for Lan Post Open - National 848.97 Signed 2021-07-03 2021-08-28 2021-07-30 2022-02-24 ations Envelope Informática Agropecuária, p dscape Management arceira do Projeto Paisagens Rurais SFB BR-GIZ-109849-GO-RF Mainstreaning Landscape Pr Request for Quot Single Stage - One Q / Aquisicao de Kits promoc TF / A8532 actices into Selected Water Post Open - National 0.00 Canceled 2021-10-08 2021-12-03 2022-06-01 ations Envelope ionais de comunicacao e inf sheds ormativos EMBRAPA BR-GIZ-162133-G O-RFQ / Compra de materiai s, insumos e equipamentos Institutional Development a Request for Quot Single Stage - One para manutenção da Unidad TF / A8532 nd Capacity Building for Lan Post Open - National 0.00 Canceled 2021-08-07 2021-10-02 2022-03-31 ations Envelope es Demonstrativas na Embr dscape Management apa Cerrados. (ILP - Experim ento longa duração-Chapad ao + ILPF e pastagem solteir a) Page 2 EMBRAPA BR-GIZ-204510-G O-RFQ / Aquisição de semen tes forrageiras para plantio nas Unidades de Referencia Institutional Development a Request for Quot Single Stage - One Tecnológica (URT) utilizada TF / A8532 nd Capacity Building for Lan Post Open - National 0.00 Canceled 2020-11-20 2021-01-15 2021-07-14 ations Envelope nos treinamentos sobre recu dscape Management peração de vegetação nativ a e pastagens para os 230 t écnicos de ATeG que atende rão os 4 mil proprietários rur ais EMBRAPA BR-GIZ-161606-G O-RFQ / Aquisição de bens e Mainstreaning Landscape Pr equipamentos para o audito Request for Quot Single Stage - One TF / A8532 actices into Selected Water Post Open - National 0.00 Canceled 2021-08-07 2021-10-02 2022-03-31 rio para capacitação na Emb ations Envelope sheds rapa Cerrados. (Som + Imag em + piso + ar condicionad o + cadeiras) EMBRAPA BR-GIZ-109840-G O-RFQ / Aquisição de materi Mainstreaning Landscape Pr Request for Quot Single Stage - One al didático impresso para dis TF / A8532 actices into Selected Water Post Open - National 0.00 Canceled 2021-01-04 2021-03-01 2021-08-28 ations Envelope tribuição nos cursos de cons sheds ervação para os diferentes a tores/públicos. EMBRAPA BR-GIZ-162145-G O-RFQ / Compra de materiai Institutional Development a Request for Quot Single Stage - One s e insumos (gesso) para ma TF / A8532 nd Capacity Building for Lan Post Open - National 0.00 Canceled 2021-08-07 2021-10-02 2022-03-31 ations Envelope nutenção da URT na Fazend dscape Management a Entre Rios PA-DF (BPA + RAD + Guzerá ). EMBRAPA BR-GIZ-162144-G O-RFQ / Compra de materiai Institutional Development a s, insumos e equipamentos Request for Quot Single Stage - One TF / A8532 nd Capacity Building for Lan Post Open - National 3,551.04 Completed 2021-10-09 2021-12-04 2022-03-04 2022-06-02 2022-03-04 para manutenção da URT na ations Envelope dscape Management Embrapa Cerrados (CTZL - C entro de Tecnologias de Raç as Zebuínas Leiteiras). EMBRAPA BR-GIZ-242450-G O-RFQ / Aquisição de bens e Institutional Development a Request for Quot Single Stage - One equipamentos para estúdio TF / A8532 nd Capacity Building for Lan Post Open - National 0.00 Canceled 2021-10-09 2021-12-04 2022-06-02 ations Envelope para produção/gravação de dscape Management vídeos para TT, inclusive EA D, da Embrapa Cerrados. EMBRAPA BR-GIZ-242454-G O-RFQ / Compra de materiai Institutional Development a s, insumos e equipamentos Request for Quot Single Stage - One TF / A8532 nd Capacity Building for Lan Post Open - National 0.00 Canceled 2021-10-09 2021-12-04 2022-06-02 para manutenção da URT da ations Envelope dscape Management Embrapa Cerrados na Fazen da Experimental da ABCZ, U beraba-MG EMBRAPA BR-GIZ-109835-G Institutional Development a O-RFQ / Aquisição de equipa Request for Quot Single Stage - One Under Imple TF / A8532 nd Capacity Building for Lan Post Open - National 0.00 2019-05-11 2019-07-06 2020-01-02 mentos de informática comp ations Envelope mentation dscape Management utadores, softwares, imagen s, equipamentos, etc.. EMBRAPA BR-GIZ-162146-G O-RFQ / Compra de materiai Institutional Development a Request for Quot Single Stage - One s e insumos para manutenç TF / A8532 nd Capacity Building for Lan Post Open - National 0.00 Canceled 2021-10-16 2021-12-11 2022-06-09 ations Envelope ão da URT na Fazenda Entre dscape Management Rios PA-DF (BPA + RAD + Guzerá ). EMBRAPA BR-GIZ-254481-G Institutional Development a O-RFQ / Compra de insumos Request for Quot Single Stage - One TF / A8532 nd Capacity Building for Lan Post Open - National 0.00 Canceled 2021-10-15 2021-12-10 2022-06-08 (SULFATO DE AMÔNIO) para ations Envelope dscape Management manutenção da URT EMBRAPA BR-GIZ-254483-G Institutional Development a O-RFQ / Aquisição de agroqu Request for Quot Single Stage - One TF / A8532 nd Capacity Building for Lan Post Open - National 15,725.72 Completed 2021-10-29 2021-12-24 2021-12-15 2022-06-22 2021-12-15 ímicos para Unidades de Ref ations Envelope dscape Management erência Tecnológica (URTs) EMBRAPA BR-GIZ-263852-G O-RFQ / Aquisição de Drone Institutional Development a Request for Quot Single Stage - One para Unidade de Referência TF / A8532 nd Capacity Building for Lan Post Open - National 17,132.65 Completed 2021-11-27 2022-01-22 2022-02-08 2022-07-21 2022-02-08 ations Envelope Tecnológica (URTs) mantida dscape Management pela Embrapa Cerrados SFB BR-GIZ-269451-GO-RF Institutional Development a Q / Aquisição de brindes par Request for Quot Single Stage - One TF / A8532 nd Capacity Building for Lan Post Open - National 0.00 Signed 2021-12-27 2022-02-21 2022-08-20 a distribuição em eventos pr ations Envelope dscape Management esenciais promovidos EMBRAPA BR-GIZ-283623-G O-RFQ / Aquisição de equipa Institutional Development a mento de ultrassom veterin Request for Quot Single Stage - One TF / A8532 nd Capacity Building for Lan Post Open - National 0.00 Signed 2022-03-16 2022-05-11 2022-11-07 ário para Unidades de Refer ations Envelope dscape Management ência Tecnológica (URTs) m antidas pela Embrapa Cerra dos EMBRAPA BR-GIZ-283624-G Institutional Development a Request for Quot Single Stage - One O-RFQ / Aquisição de equipa TF / A8532 nd Capacity Building for Lan Post Open - National 0.00 Signed 2022-03-16 2022-05-11 2022-11-07 ations Envelope mentos informática dscape Management SFB BR-GIZ-291096-GO-RF Q / Aquisição de fitas de pes Institutional Development a Request for Quot Single Stage - One agem para gado para distrib TF / A8532 nd Capacity Building for Lan Post Open - National 0.00 Signed 2022-04-23 2022-06-18 2022-12-15 ations Envelope uição em eventos presenciai dscape Management s promovidos no âmbito do Projeto EMBRAPA BR-GIZ-305644-G O-RFQ / Aquisição de equipa Institutional Development a Request for Quot Single Stage - One mentos audiovisuais para ati TF / A8532 nd Capacity Building for Lan Post Open - National 0.00 Signed 2022-07-30 2022-09-24 2023-03-23 ations Envelope vidades de EAD promovidas dscape Management pela Embrapa Cerrados EMBRAPA BR-GIZ-305645-G Institutional Development a Request for Quot Single Stage - One O-RFQ / Equipamentos de in TF / A8532 nd Capacity Building for Lan Post Open - National 0.00 Completed 2022-08-06 2022-10-01 2023-03-30 2022-12-23 ations Envelope formática para atividades de dscape Management EAD EMBRAPA BR-GIZ-305649-G Institutional Development a Request for Quot Single Stage - One O-RFQ / Móveis para o estúd TF / A8532 nd Capacity Building for Lan Post Open - National 0.00 Signed 2022-08-06 2022-10-01 2023-03-30 ations Envelope io dscape Management SFB BR-GIZ-322193-GO-RF Q / Aquisição de equipamen Institutional Development a Request for Quot Single Stage - One tos informática para a execu TF / A8532 nd Capacity Building for Lan Post Open - National 0.00 Canceled 2022-11-12 2023-01-07 2023-07-06 ations Envelope ção das atividades de asses dscape Management soria e coordenação técnica do Serviço Florestal Brasileir o EMBRAPA BR-GIZ-327286-G Institutional Development a O-RFQ / Aquisição de fertiliz Request for Quot Single Stage - One TF / A8532 nd Capacity Building for Lan Post Open - National 0.00 Canceled 2022-12-03 2023-01-28 2023-07-27 antes para Unidades de Ref ations Envelope dscape Management erência Tecnológica (URTs) EMBRAPA BR-GIZ-361072-G O-RFQ / Aquisição de fertiliz Institutional Development a antes para manutenção de e Request for Quot Single Stage - One Pending Impl TF / A8532 nd Capacity Building for Lan Post Open - National 0.00 2023-05-15 2023-07-10 2024-01-06 xperimentos de pesquisa na ations Envelope ementation dscape Management Unidades de Referência Tec nológica (URT) mantidas pel a Embrapa Page 3 NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendatio Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes n for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual EMBRAPA 2 BR-GIZ-76293- NC-APA / Fornecimento de c offee break e/ou almoço par a todas as capacitações do c Mainstreaning Landscape Pr Alternative Procur Single Stage - One omp de conserv da paisage / actices into Selected Water Post ement Arrangem Open - National 0.00 Canceled 2019-01-20 2019-01-25 2019-02-15 2019-02-22 2019-03-15 2019-09-11 Envelope m em cursos, dias de campo sheds ent etc dos técnicos rurais e/ou produtores durante todos o s cursos, seminarios regiona is, excursoes tecnicas EMBRAPA 1 BR-GIZ-76234- NC-APA / Loc. de veiculos pa ra a realização de estudos p Institutional Development a Alternative Procur rospectivos de cenários de c Single Stage - One / nd Capacity Building for Lan Post ement Arrangem Open - National 0.00 Canceled 2019-01-20 2019-01-25 2019-02-15 2019-02-22 2019-03-15 2019-09-11 onservação e produção co Envelope dscape Management ent m tecnologias disponíveis so bre o CAR, PRA, tecnologias do ABC, BPAs, RAD, Legislaç ão de Proteção da Vegetaçã o Nativa EMBRAPA 2 BR-GIZ-76262- NC-APA / Loc de veic para a realização do comp de estud os e cursos de conserv da p Mainstreaning Landscape Pr Alternative Procur Single Stage - One aisagem nos cursos, treinam / actices into Selected Water Post ement Arrangem Open - National 0.00 Canceled 2019-01-20 2019-01-25 2019-02-15 2019-02-22 2019-03-15 2019-09-11 Envelope , dias de campo etc com te sheds ent cnol disponíveis sobre o CAR , PRA, tecnologias do ABC, B PAs, RAD, Legislação de Prot eção da Vegetação Nativa EMBRAPA 2 BR-GIZ-76236- NC-APA / Contratação de em Mainstreaning Landscape Pr Alternative Procur presa gráfica para a impress Single Stage - One / actices into Selected Water Post ement Arrangem Open - National 0.00 Canceled 2019-01-20 2019-01-25 2019-02-15 2019-02-22 2019-03-15 2019-09-11 ao de material didatico para Envelope sheds ent os cursos de conservação p ara os diferentes atores/púb licos. SFB 1 BR-GIZ-76238-NC-AP A / Contratação de empresa para realização de eventos, Institutional Development a Alternative Procur Single Stage - One cursos, oficinas e reuniões d / nd Capacity Building for Lan Post ement Arrangem Open - National 0.00 Canceled 2018-10-15 2018-10-20 2018-11-10 2018-11-17 2018-12-08 2019-06-06 Envelope e promoção do empoderam dscape Management ent ento local e integração multi -institucional por Bacia selec ionada SFB 2 BR-GIZ-76275-NC-AP A / Contratação de pessoa ju rídica para realizar 10 oficin Mainstreaning Landscape Pr Alternative Procur Single Stage - One as participativas de elaboraç / actices into Selected Water Post ement Arrangem Open - National 0.00 Canceled 2018-10-15 2018-10-20 2018-11-10 2018-11-17 2018-12-08 2019-06-06 Envelope ão e pactuação do plano, pa sheds ent ra o lançamento e a difusão do plano de ação de cada u ma das bacias SFB 2 BR-GIZ-76286-NC-AP Mainstreaning Landscape Pr Alternative Procur Single Stage - One / Post Open - National 0.00 Canceled 2019-01-15 2019-01-20 2019-02-10 2019-02-17 2019-03-10 2019-09-06 A / Aluguel de veiculos do S actices into Selected Water ement Arrangem Envelope FB sheds ent INPE 1 BR-GIZ-76273-NC-AP Institutional Development a Alternative Procur A / Serviços de organização Single Stage - One / nd Capacity Building for Lan Post ement Arrangem Open - National 0.00 Canceled 2018-10-15 2018-10-20 2018-11-10 2018-11-17 2018-12-08 2019-06-06 de eventos, publicação e div Envelope dscape Management ent ulgação de resultados (map eamento orbital) INPE 1 BR-GIZ-76292-NC-AP Institutional Development a Alternative Procur Single Stage - One A / Locação de Veículo (map / nd Capacity Building for Lan Post ement Arrangem Open - National 0.00 Canceled 2018-10-15 2018-10-20 2018-11-10 2018-11-17 2018-12-08 2019-06-06 Envelope eamento orbital e análise da dscape Management ent paisagem) GIZ 3 BR-GIZ-76290-NC-AP Project Management, Monit Alternative Procur A / Contratação de serviços Single Stage - One / oring, Evaluation and Com Post ement Arrangem Open - National 0.00 Canceled 2018-10-15 2018-10-20 2018-11-10 2018-11-17 2018-12-08 2019-06-06 para produção dos materiais Envelope munication ent e peças de comunicação do Projeto GIZ 3 BR-GIZ-76276-NC-AP Project Management, Monit Alternative Procur Single Stage - One A / Auditorias Externas Inde / oring, Evaluation and Com Post ement Arrangem Open - National 0.00 Canceled 2018-10-15 2018-10-20 2018-11-10 2018-11-17 2018-12-08 2019-06-06 Envelope pendentes do projeto munication ent SFB BR-GIZ-109851-NC-RFQ Mainstreaning Landscape Pr Request for Quot Single Stage - One TF / A8532 Post Open - National 0.00 Canceled 2019-08-10 2019-10-05 2020-04-02 / Aluguel de veículos do SFB actices into Selected Water ations Envelope sheds INPE BR-GIZ-109968-NC-RF Institutional Development a Request for Quot Single Stage - One Q / Aluguel de sala comercia TF / A8532 nd Capacity Building for Lan Post Open - National 17,449.76 Signed 2019-05-11 2019-07-06 2019-06-24 2020-01-02 ations Envelope l para equipe de técnicos e dscape Management m Campinas/SP GIZ BR-GIZ-109987-NC-RFQ Project Management, Monit / Contratação de serviços pa Request for Quot Single Stage - One TF / A8532 oring, Evaluation and Com Post Open - National 0.00 Canceled 2019-12-07 2020-02-01 2020-07-30 ra produção dos materiais e ations Envelope munication peças de comunicação do Pr ojeto GIZ BR-GIZ-109989-NC-RFQ Project Management, Monit Request for Quot Single Stage - One / Auditorias Externas Indepe TF / A8532 oring, Evaluation and Com Post Open - National 4,214.35 Signed 2019-11-23 2020-01-18 2020-01-16 2020-07-16 ations Envelope ndentes do projeto munication EMBRAPA BR-GIZ-109841-N C-RFQ / Contratação de serv iço de locação de veiculos p ara a realização de estudos Institutional Development a Request for Quot Single Stage - One prospectivos de cenários de TF / A8532 nd Capacity Building for Lan Post Open - National 0.00 Canceled 2019-08-10 2019-10-05 2020-04-02 ations Envelope conservação e produção co dscape Management m tecnologias disponíveis so bre o CAR, PRA, tecnologias do ABC, BPAs, RAD, Legislaç ão de Proteção da Vegetaçã o Nativa INPE BR-GIZ-162154-NC-RF Institutional Development a Q / Contrato ferramentas TI Request for Quot Single Stage - One TF / A8532 nd Capacity Building for Lan Post Open - National 0.00 Canceled 2020-04-10 2020-06-05 2020-12-02 para armazenamento de da ations Envelope dscape Management dos e comunicação INPE BR-GIZ-109960-NC-RF Institutional Development a Q / Serviços de organização Request for Quot Single Stage - One TF / A8532 nd Capacity Building for Lan Post Open - National 0.00 Canceled 2019-11-09 2020-01-04 2020-07-02 de eventos, publicação e div ations Envelope dscape Management ulgação de resultados (map eamento orbital) INPE BR-GIZ-109964-NC-RF Institutional Development a Request for Quot Single Stage - One Q / Locação de Veículo (map TF / A8532 nd Capacity Building for Lan Post Open - National 0.00 Canceled 2019-11-09 2020-01-04 2020-07-02 ations Envelope eamento orbital e análise da dscape Management paisagem) BR-GIZ-207801-NC-RFQ / A Project Management, Monit Request for Quot Single Stage - One uditorias Externas Independ TF / A8532 oring, Evaluation and Com Post Open - National 14,745.42 Signed 2020-12-07 2021-02-01 2021-01-06 2021-07-31 ations Envelope entes do projeto Exercícios munication 2020/2021 SFB BR-GIZ-161627-NC-RFQ Institutional Development a Request for Quot Single Stage - One / Aquisicao de Kits promocio TF / A8532 nd Capacity Building for Lan Post Open - National 0.00 Canceled 2020-06-07 2020-08-02 2021-01-29 ations Envelope nais de comunicacao e infor dscape Management mativos Page 4 SFB BR-GIZ-161619-NC-RFQ / Produção de material infor Institutional Development a Request for Quot Single Stage - One mativo e vídeo para divulga TF / A8532 nd Capacity Building for Lan Post Open - National 0.00 Canceled 2021-10-08 2021-12-03 2022-06-01 ations Envelope ção das atuações do SFB inc dscape Management luindo o projeto FIP Paisage m. EMBRAPA BR-GIZ-161972-N Institutional Development a C-RFQ / Alimentação  para o Request for Quot Single Stage - One TF / A8532 nd Capacity Building for Lan Post Open - National 0.00 Canceled 2020-04-10 2020-06-05 2020-12-02 s dois cursos presenciais de ations Envelope dscape Management capacitação BPA e RAD. EMBRAPA BR-GIZ-161975-N Institutional Development a C-RFQ / Material de apoio pa Request for Quot Single Stage - One TF / A8532 nd Capacity Building for Lan Post Open - National 0.00 Canceled 2021-07-05 2021-08-30 2022-02-26 ra os dois cursos presenciais ations Envelope dscape Management de capacitação BPA e RAD. EMBRAPA BR-GIZ-242452-N C-RFQ / Contratação de emp resa da área de construção Institutional Development a Request for Quot Single Stage - One civil para reforma e adequaç TF / A8532 nd Capacity Building for Lan Post Open - National 0.00 Canceled 2021-10-09 2021-12-04 2022-06-02 ations Envelope ão e manutenção do estúdio dscape Management para produção/gravação de vídeos para TT, inclusive EA D, da Embrapa Cerrados. EMBRAPA BR-GIZ-164514-C W-RFQ / Contratação de em Institutional Development a Request for Quot Single Stage - One presa para instalações de eq TF / A8532 nd Capacity Building for Lan Post Open - National 0.00 Canceled 2021-10-09 2021-12-04 2022-06-02 ations Envelope uipamentos de Som + Imag dscape Management em + piso + ar condicionad o + cadeiras SFB BR-GIZ-270583-NC-RFQ Institutional Development a / Almoços e coffe-breaks par Request for Quot Single Stage - One Pending Impl TF / A8532 nd Capacity Building for Lan Post Open - National 0.00 2022-01-08 2022-03-05 2022-09-01 a oficina que ocorrerá na Ba ations Envelope ementation dscape Management hia entre os dias 24 e 25 de janeiro. SFB BR-GIZ-280725-CS-QCB S / Contratação de empresa para realização de retificaçã o (e/ou atendimentos de not Institutional Development a Single Stage - One ificações) dos imóveis rurais TF / A8532 nd Capacity Building for Lan Post Request for Bids Open - National 0.00 Signed 2022-03-09 2022-03-02 2022-03-14 2022-04-25 2022-03-04 2022-05-25 2022-03-16 2022-06-29 2022-12-26 Envelope já cadastrados na Base do SI dscape Management CAR, bem como a inscrição de imóveis rurais que ainda não possuam o Cadastro Am biental Rural (CAR) SFB BR-GIZ-290637-NC-RFB / Contratação de empresa p Institutional Development a ara produção de pacote de Single Stage - One TF / A8532 nd Capacity Building for Lan Post Request for Bids Open - National 0.00 Signed 2022-04-14 2022-04-20 2022-04-19 2022-05-31 2022-04-20 2022-06-30 2022-07-20 2022-08-04 2023-01-31 quatro vídeos educativos cu Envelope dscape Management rtos com temas de conserva ção e regularização ambient al de imóveis rurais. SFB BR-GIZ-298269-NC-RFQ / Contratação de serviços de infraestrutura e alimentação necessários para a realizaçã Institutional Development a Request for Quot Single Stage - One o de eventos da “Agenda da TF / A8532 nd Capacity Building for Lan Post Open - National 0.00 Canceled 2022-06-11 2022-08-06 2023-02-02 ations Envelope Regularização Ambiental” n dscape Management o âmbito do Projeto “Gestão Integrada de Paisagens no b ioma Cerrado – Paisagens R urais” na Bahia SDI BR-GIZ-312279-NC-RFQ / Realizar a diagramação e r evisão gramatical da publica ção dos resultados de uma d Institutional Development a Request for Quot Single Stage - One Under Imple écada de implementação do TF / A8532 nd Capacity Building for Lan Post Open - National 0.00 2022-09-03 2022-10-29 2023-04-27 ations Envelope mentation Plano Setorial de Mitigação dscape Management e de Adaptação às Mudança s Climáticas para a Consolid ação de uma Economia de B aixa Emissão de Carbono na Agricultura - GIZ BR-GIZ-322194-NC-RFQ Project Management, Monit Request for Quot Single Stage - One Under Imple / Auditorias Externas Indepe TF / A8532 oring, Evaluation and Com Post Open - National 0.00 2022-12-03 2023-01-28 2023-07-27 ations Envelope mentation ndentes do projeto Exercício munication s 2022/2023 EMBRAPA BR-GIZ-357696-N C-RFQ / impressão de 500 e Institutional Development a Request for Quot Single Stage - One Pending Impl xemplares da publicação Gu TF / A8532 nd Capacity Building for Lan Post Open - National 0.00 2023-04-29 2023-06-24 2023-12-21 ations Envelope ementation ia de plantas do Cerrado par dscape Management a recomposição da vegetaçã o nativa EMBRAPA BR-GIZ-361378-N C-RFQ / Serviços de reabilita Institutional Development a ção e modernização das cen Request for Quot Single Stage - One Under Imple TF / A8532 nd Capacity Building for Lan Post Open - National 0.00 2023-05-20 2023-07-15 2024-01-11 trais de ar-condicionado do ations Envelope mentation dscape Management prédio do auditório e salas a djacentes da Embrapa Cerra dos, situada em Planaltina/D F CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Techni Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h (US$) Notice equest for Proposals as Issued Proposals / Minutes cal Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual EMBRAPA 1 BR-GIZ-76228- CS-CAPA / CI na area de eng Institutional Development a Alternative Procur enharia para elaboracao de / nd Capacity Building for Lan Post ement Arrangem Direct 0.00 Canceled 2018-10-30 2018-12-09 2018-12-30 2019-06-28 projeto basico e executivo p dscape Management ent ara as reformas do auditori o, salas de aula, salas de vid eo e viveiro da EMBRAPA Ce rrados. EMBRAPA 1 BR-GIZ-76229- CS-CAPA / CI para o process amento e sistem da informa Institutional Development a Alternative Procur ção tecnol para a caracteriz / nd Capacity Building for Lan Post ement Arrangem Open - National 0.00 Canceled 2018-10-30 2018-11-20 2019-01-03 2019-01-31 2019-03-02 2019-04-06 2019-04-27 2020-04-26 ação e análise da estrutura dscape Management ent e da dinâmica das unidades de paisagem para replicabili dade das intervenções de B PA e RAD em diferentes esc alas EMBRAPA 2 BR-GIZ-76270- CS-CAPA / CI para coord, ela boração de cont e apresenta ção de cursos presenciais e Mainstreaning Landscape Pr Alternative Procur a distância no tema conserv / actices into Selected Water Post ement Arrangem Open - National 0.00 Canceled 2018-11-15 2018-12-06 2019-01-19 2019-02-16 2019-03-18 2019-04-22 2019-05-13 2020-05-12 dos rec nat em temas como sheds ent tecnol de manejo e uso cont rolado do fogo, estrat de rec omp da vegetação nativas e boas praticas agropecuárias EMBRAPA 2 BR-GIZ-76204- CS-CAPA / Contratação de C Mainstreaning Landscape Pr Alternative Procur onsultoria Individual para ap / actices into Selected Water Post ement Arrangem Open - National 0.00 Canceled 2018-11-15 2018-12-06 2019-01-19 2019-02-16 2019-03-18 2019-04-22 2019-05-13 2020-05-12 resentação de cursos prese sheds ent nciais e a distância no tema conservação dos recursos n aturais (instrutores/equipe d e apoio). Page 5 EMBRAPA 2 BR-GIZ-76254- CS-CAPA / CI para coordenaç ão da coleta de dados na im Mainstreaning Landscape Pr Alternative Procur plantação de tecnologias de / actices into Selected Water Post ement Arrangem Open - National 0.00 Canceled 2018-11-15 2018-12-06 2019-01-19 2019-02-16 2019-03-18 2019-04-22 2019-05-13 2020-05-12 manejo e uso controlado do sheds ent fogo; estratégias de recomp osição da vegetação nativa e boas praticas agropecuári as, em imoveis rurais assisti dos pelo Projeto EMBRAPA 2 BR-GIZ-76205- CS-CAPA / CI para execução Mainstreaning Landscape Pr Alternative Procur da coleta de dados na impla / actices into Selected Water Post ement Arrangem Open - National 0.00 Canceled 2018-11-15 2018-12-06 2019-01-19 2019-02-16 2019-03-18 2019-04-22 2019-05-13 2020-05-12 nt de tecnologias de manejo sheds ent e uso controlado do fogo; es tratégias de recomp da veg. nativa e boas praticas agrop ecuárias EMBRAPA 2 BR-GIZ-76277- CS-CAPA / 3 CIs para apoio n a coleta de dados na implan Mainstreaning Landscape Pr Alternative Procur tação de tecnologias de ma / actices into Selected Water Post ement Arrangem Open - National 0.00 Canceled 2018-10-10 2018-10-31 2018-12-14 2019-01-11 2019-02-10 2019-03-17 2019-04-07 2020-04-06 nejo e uso controlado do fog sheds ent o, estratégias de recomposi ção da vegetação nativa e b oas praticas agropecuárias. EMBRAPA 2 BR-GIZ-76232- Mainstreaning Landscape Pr Alternative Procur CS-CAPA / CI para levantar s / actices into Selected Water Post ement Arrangem Open - National 0.00 Canceled 2018-10-10 2018-10-31 2018-12-14 2019-01-11 2019-02-10 2019-03-17 2019-04-07 2020-04-06 ubsidios para incentivar à ca sheds ent deia produtiva da restauraç ão SFB 1 BR-GIZ-76252-CS-CA PA / Serviços de Consultoria Institutional Development a Alternative Procur jurídica para Classificações / nd Capacity Building for Lan Post ement Arrangem Open - National 0.00 Canceled 2018-10-15 2018-11-05 2018-12-19 2019-01-16 2019-02-15 2019-03-22 2019-04-12 2020-04-11 para o SICAR no Cerrado, SE dscape Management ent NTINEL ou Sensor Compatív el 1:10.000 - 2016, 2017, 2 018, 2019 SFB 1 BR-GIZ-76264-CS-CA PA / CPJ para realizar diag, mapeam e elaborar portif de Institutional Development a Alternative Procur divulgação da sistematiz de / nd Capacity Building for Lan Post ement Arrangem Open - National 0.00 Canceled 2018-10-15 2018-11-05 2018-12-19 2019-01-16 2019-02-15 2019-03-22 2019-04-12 2020-04-11 exp de imóveis rurais públ e dscape Management ent priv qto às ativ e empreend de recuperação/recomposiç ão de áreas degradadas, silv icultura e soluções tecnol BP A SFB 1 BR-GIZ-76213-CS-CA PA / CPJ para promoção de u ma melhor comunicacao e Institutional Development a Alternative Procur melhoria institucional das or / nd Capacity Building for Lan Post ement Arrangem Open - National 0.00 Canceled 2018-10-15 2018-11-05 2018-12-19 2019-01-16 2019-02-15 2019-03-22 2019-04-12 2020-04-11 ganizações (Compatibilizaçã dscape Management ent o de informações sobre o Ce rrado entre o SFB (Inventári o Florestal), INPE (Prodes), E MBRAPA (TerraClass), SENA R, MAPA e MMA) SFB 1 BR-GIZ-76266-CS-CA PA / Contratacao de pessoa j Institutional Development a Alternative Procur uridica para Elaboracao e di / nd Capacity Building for Lan Post ement Arrangem Open - National 0.00 Canceled 2018-10-15 2018-11-05 2018-12-19 2019-01-16 2019-02-15 2019-03-22 2019-04-12 2020-04-11 sponibilizacao na plataforma dscape Management ent Saberes da Floresta de 10 c ursos com tematica relativa as acoes do projeto SFB 1 BR-GIZ-76237-CS-CA PA / Consultoria pessoa juríd Institutional Development a Alternative Procur ica (OS) para mobilização e / nd Capacity Building for Lan Post ement Arrangem Open - National 0.00 Canceled 2018-10-15 2018-11-05 2018-12-19 2019-01-16 2019-02-15 2019-03-22 2019-04-12 2020-04-11 apoio à instalação e fortaleci dscape Management ent mento de Comitês de Bacia Hidrográfica SFB 2 BR-GIZ-76243-CS-CA PA / Contratação de Pessoa J Mainstreaning Landscape Pr Alternative Procur urídica (OS) para instalar viv / actices into Selected Water Post ement Arrangem Open - National 0.00 Canceled 2018-10-15 2018-11-05 2018-12-19 2019-01-16 2019-02-15 2019-03-22 2019-04-12 2020-04-11 eiros permanentes e tempor sheds ent arios, casa de sementes, pro dução e comercialização de sementes e mudas. SFB 2 BR-GIZ-76249-CS-CA PA / Contratação de pessoa j urídica para desenvolver me Mainstreaning Landscape Pr Alternative Procur todologia de monitoramento / actices into Selected Water Post ement Arrangem Open - National 0.00 Canceled 2018-10-15 2018-11-05 2018-12-19 2019-01-16 2019-02-15 2019-03-22 2019-04-12 2020-04-11 de áreas restauradas (fortal sheds ent ecer a oferta de serviços de monitoramento) e aplicação por dois ciclos de monitora mento (T.0, T.1 e T.2). SFB 1 BR-GIZ-76274-CS-CA PA / CI para a elaboração de método, treinamento e apoi Institutional Development a Alternative Procur o à execução da Análise téc / nd Capacity Building for Lan Post ement Arrangem Open - National 0.00 Canceled 2018-10-15 2018-11-05 2018-12-19 2019-01-16 2019-02-15 2019-03-22 2019-04-12 2020-04-11 nica sobre o CAR e PRAs na dscape Management ent área de abrangência do proj eto no SICAR e elaboração d e materiais específicos da ár ea de abrangência do Projet o. SFB 1 BR-GIZ-76280-CS-CA PA / CI pra a sistematização de informações sobre a área Institutional Development a Alternative Procur selecionada, com a definiçã / nd Capacity Building for Lan Post ement Arrangem Open - National 0.00 Canceled 2018-10-15 2018-11-05 2018-12-19 2019-01-16 2019-02-15 2019-03-22 2019-04-12 2020-04-11 o da área de abrangência do dscape Management ent projeto, considerando passiv os florestais em APP, RL, áre as passíveis de restauração e análise multicritérios. SFB 2 BR-GIZ-76288-CS-CA PA / Consultoria Individual p Mainstreaning Landscape Pr Alternative Procur ara a definição da estrutura / actices into Selected Water Post ement Arrangem Open - National 0.00 Canceled 2018-10-15 2018-11-05 2018-12-19 2019-01-16 2019-02-15 2019-03-22 2019-04-12 2020-04-11 e escopo do plano de ação n sheds ent as 10 bacias selecionadas. SFB 2 BR-GIZ-76244-CS-CA PA / CI para apoiar os treina mento para funcionários pú Mainstreaning Landscape Pr Alternative Procur blicos em legislação ambien / actices into Selected Water Post ement Arrangem Open - National 0.00 Canceled 2018-10-15 2018-11-05 2018-12-19 2019-01-16 2019-02-15 2019-03-22 2019-04-12 2020-04-11 tal, especialmente Código Fl sheds ent orestal e as relativas ao CAR , PRA e licenciamento ambie ntal, bem como sobre as eta pas e procedimentos para re alização de CAR e PRA INPE 1 BR-GIZ-76253-CS-CA PA / Contratação de 04 (qua Institutional Development a Alternative Procur tro) consultorias individuais / nd Capacity Building for Lan Post ement Arrangem Open - National 0.00 Canceled 2018-10-15 2018-11-05 2018-12-19 2019-01-16 2019-02-15 2019-03-22 2019-04-12 2020-04-11 - Serviços de Geoprocessam dscape Management ent ento (mapeamento orbital) INPE 1 BR-GIZ-76241-CS-CA Institutional Development a Alternative Procur PA / Contratação de Consult / nd Capacity Building for Lan Post ement Arrangem Open - National 0.00 Canceled 2018-10-15 2018-11-05 2018-12-19 2019-01-16 2019-02-15 2019-03-22 2019-04-12 2020-04-11 or individual - Assistente Ge dscape Management ent oprocessamento júnior (anál ise da paisagem) INPE 1 BR-GIZ-76289-CS-CA Institutional Development a Alternative Procur PA / Contratação de Consult / nd Capacity Building for Lan Post ement Arrangem Open - National 0.00 Canceled 2018-10-15 2018-11-05 2018-12-19 2019-01-16 2019-02-15 2019-03-22 2019-04-12 2020-04-11 or individual - Serviços de G dscape Management ent eoprocessamento (análise d a paisagem) Page 6 INPE 3 BR-GIZ-76278-CS-CA PA / Contratação de Consult oria pessoa jurídica para a d Project Management, Monit Alternative Procur ifusão e comunicação dos re / oring, Evaluation and Com Post ement Arrangem Open - National 0.00 Canceled 2018-10-15 2018-11-05 2018-12-19 2019-01-16 2019-02-15 2019-03-22 2019-04-12 2020-04-11 sultados do projeto em even munication ent tos e reuniões nacionais ou i nternacionais técnicos, acad êmicos e políticos GIZ 3 BR-GIZ-76242-CS-CAP Project Management, Monit Alternative Procur A / Consultoria Individual pa / oring, Evaluation and Com Post ement Arrangem Open - National 0.00 Canceled 2018-10-15 2018-11-05 2018-12-19 2019-01-16 2019-02-15 2019-03-22 2019-04-12 2020-04-11 ra elaborar Relatório Final d munication ent e Revisão de Meio Termo GIZ 3 BR-GIZ-76246-CS-CAP Project Management, Monit Alternative Procur A / Consultorias para Suport / oring, Evaluation and Com Post ement Arrangem Open - National 0.00 Canceled 2018-10-15 2018-11-05 2018-12-19 2019-01-16 2019-02-15 2019-03-22 2019-04-12 2020-04-11 e Administrativo e de Aquisi munication ent ções ao Projeto (equipe bas e GIZ) GIZ 3 BR-GIZ-76247-CS-CAP Project Management, Monit Alternative Procur A / Consultorias para Suport / oring, Evaluation and Com Post ement Arrangem Open - National 0.00 Canceled 2019-01-15 2019-02-05 2019-03-21 2019-04-18 2019-05-18 2019-06-22 2019-07-13 2020-07-12 e Técnico ao Projeto (equipe munication ent base GIZ) GIZ 3 BR-GIZ-76203-CS-CAP Project Management, Monit Alternative Procur A / Elaboração do Plano de c / oring, Evaluation and Com Post ement Arrangem Open - National 0.00 Canceled 2018-10-15 2018-11-05 2018-12-19 2019-01-16 2019-02-15 2019-03-22 2019-04-12 2020-04-11 omunicação do projeto - co munication ent muncação geral do Projeto GIZ BR-GIZ-109973-CS-CQS / Contratação de Consultoria pessoa jurídica para a difusã Project Management, Monit Consultant Qualifi o e comunicação dos resulta TF / A8532 oring, Evaluation and Com Post Open - National 0.00 Canceled 2019-12-02 2019-12-23 2020-02-05 2020-03-06 2020-04-10 2020-10-07 cation Selection dos do projeto em eventos e munication reuniões nacionais ou intern acionais técnicos, acadêmic os e políticos SFB BR-GIZ-201637-CS-IND V / Contratação de consultor ia pessoa jurídica para mape Institutional Development a amento da cobertura do uso Consultant Qualifi TF / A8532 nd Capacity Building for Lan Post Open - National 25,525.40 Signed 2020-11-04 2021-06-18 2020-11-25 2021-01-08 2021-09-14 2021-02-07 2021-09-17 2021-03-14 2021-10-02 2021-09-10 do solo, hidrografia, relevo e cation Selection dscape Management servidões administrativas da s Bacias Hidrográficas, nos e stados do Tocantins, Maranh ão, Bahia, Minas Gerais, Goi ás e Mato Grosso SFB BR-GIZ-223586-CS-CQS / Contratação de empresa p ara realização de retificação (e/ou atendimentos de notifi Institutional Development a Quality And Cost- cações) dos imóveis rurais j TF / A8532 nd Capacity Building for Lan Post Open - National 169,149.12 Signed 2021-03-14 2021-03-17 2021-04-04 2021-05-18 2021-04-23 2021-06-15 2021-06-24 2021-07-15 2021-08-03 2021-08-19 2021-08-18 2021-09-23 2021-09-02 2022-09-23 Based Selection á cadastrados na Base do SI dscape Management CAR, bem como a inscrição de imóveis rurais que ainda não possuam o Cadastro Am biental Rural (CAR) INPE BR-GIZ-239970-CS-QC Institutional Development a BS / Reformulação do "layou Consultant Qualifi TF / A8532 nd Capacity Building for Lan Post Open - National 29,344.75 Signed 2021-07-25 2021-07-14 2021-08-15 2021-09-28 2021-08-27 2021-10-28 2021-09-10 2021-12-02 2021-09-25 2022-05-31 t" e codificação da nova inte cation Selection dscape Management rface do geoportal e do Web GIS TerraClass SFB BR-GIZ-201638-CS-IND V / Contratação de consultor ia pessoa jurídica para mape Institutional Development a Consultant Qualifi amento da cobertura do uso TF / A8532 nd Capacity Building for Lan Post Open - National 0.00 Canceled 2020-11-04 2020-12-17 2020-11-25 2021-01-08 2021-02-07 2021-03-14 2021-09-10 cation Selection do solo, hidrografia, relevo e dscape Management servidões administrativas da Bacia Hidrográfica 8652, no estado de Mato Grosso do S ul. SFB BR-GIZ-204513-CS-CQS / Contratação de pessoa jurí Institutional Development a dica para mapeamento de c Consultant Qualifi TF / A8532 nd Capacity Building for Lan Post Open - National 0.00 Canceled 2020-11-15 2020-12-17 2020-12-06 2021-01-19 2021-02-18 2021-03-25 2021-09-21 obertura do solo, hidrografia cation Selection dscape Management , relevo e servidões administ rativas das áreas de Cerrad o nos estados do Maranhão e Piauí EMBRAPA BR-GIZ-242457-C S-CQS / Contratação de em presa na área de engenhari Institutional Development a Consultant Qualifi a para elaboração de projet TF / A8532 nd Capacity Building for Lan Post Open - National 0.00 Canceled 2021-10-04 2021-10-25 2021-12-08 2022-01-07 2022-02-11 2022-08-10 cation Selection o básico e executivo para as dscape Management reformas do auditório, salas de aula, salas de video e viv eiro da Embrapa Cerrados GIZ BR-GIZ-245677-CS-CQS / Contratação de consultoria Project Management, Monit Consultant Qualifi PJ para o desenvolvimento d TF / A8532 oring, Evaluation and Com Post Open - National 0.00 Canceled 2021-10-04 2021-08-12 2021-10-25 2021-12-08 2022-01-07 2022-02-11 2022-08-10 cation Selection o Painel Estratégico de Moni munication toramento do Projeto FIP Pai sagens Rurais SFB BR-GIZ-290638-NC-RFQ Institutional Development a / Contratar uma empresa ou Consultant Qualifi TF / A8532 nd Capacity Building for Lan Post Open - National 0.00 Canceled 2022-04-20 2022-05-11 2022-06-24 2022-07-24 2022-08-28 2023-02-24 agência de comunicação par cation Selection dscape Management a realizar 4 palestras presen ciais SFB BR-GIZ-305651-CS-CQS / Contratação de empresa p Institutional Development a Consultant Qualifi ara elaborar e realizar pales TF / A8532 nd Capacity Building for Lan Post Open - National 0.00 Signed 2022-08-01 2022-07-25 2022-08-22 2022-10-05 2022-08-09 2022-11-04 2022-10-03 2022-12-09 2023-06-07 cation Selection tras sobre Comunicação e E dscape Management stratégia de Narrativa sobre Regularização Ambiental SDI BR-GIZ-316609-CS-CQS / Consultoria para elaboraçã o dos artefatos para implant ação do Sistema de Governa Institutional Development a Consultant Qualifi Under Implement nça do ABC+ (SIGABC) na e TF / A8532 nd Capacity Building for Lan Post Open - National 0.00 2022-09-16 2022-09-29 2022-10-07 2022-11-20 2022-12-20 2023-01-24 2023-07-23 cation Selection ation strutura de TI do MAPA e de dscape Management senvolvimento de painéis de inteligência de negócios (pai néis gerenciais) para o moni toramento e acompanhame nto da execução SFB BR-GIZ-312283-CS-CQS / Prestação de serviços espe Institutional Development a Consultant Qualifi cializados para o desenvolvi TF / A8532 nd Capacity Building for Lan Post Open - National 0.00 Canceled 2022-10-31 2022-11-21 2023-01-04 2023-02-03 2023-03-10 2023-09-06 cation Selection mento de Plataforma de Mo dscape Management nitoramento do Projeto Pais agens Rurais | FIP Paisagem SFB BR-GIZ-312280-CS-CQS Institutional Development a / Contratação de empresa e Consultant Qualifi TF / A8532 nd Capacity Building for Lan Post Open - National 0.00 Signed 2022-10-31 2022-10-19 2022-11-21 2023-01-04 2022-12-12 2023-02-03 2023-03-22 2023-03-10 2023-09-06 specializada para o desenvo cation Selection dscape Management lvimento de cursos na moda lidade EAD SDI BR-GIZ-320196-CS-CQS Institutional Development a / Contratação de consultoria Consultant Qualifi Under Implement TF / A8532 nd Capacity Building for Lan Post Open - National 0.00 2022-11-28 2022-11-18 2022-12-19 2023-02-01 2023-03-03 2023-04-07 2023-10-04 para apoiar elaboração de p cation Selection ation dscape Management rojeto denominado ABC+Fa miliar SDI BR-GIZ-320198-CS-CQS / Contratação de consultoria Institutional Development a Consultant Qualifi para identificar desafios e o TF / A8532 nd Capacity Building for Lan Post Open - National 0.00 Signed 2022-11-14 2022-12-07 2022-12-05 2023-01-18 2023-02-27 2023-02-17 2023-04-05 2023-03-24 2023-09-20 cation Selection portunidades para o manejo dscape Management de resíduos da produção ani mal, no âmbito do ABC+. Page 7 SDI BR-GIZ-320199-CS-CQS / Contratação de consultoria para apoiar no aprimoramen Institutional Development a to de questões referentes à Consultant Qualifi Pending Impleme TF / A8532 nd Capacity Building for Lan Post Open - National 0.00 2022-11-28 2022-12-19 2023-02-01 2023-03-03 2023-04-07 2023-10-04 valorização das ações do AB cation Selection ntation dscape Management C+ junto ao Inventário Nacio nal de emissões e remoções de GEE relacionadas aos set ores agropecuário e LULUCF INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Actual Amount Invitation to Identifie Draft Negotiated Con Component Review Type Method Contract Type Process Status Teams of Reference Signed Contract Contract Completion Description o. h (US$) d/Selected Consultan tract Planned Actual Planned t Actual Planned Actual Planned Actual Planned Actual INPE 1 BR-GIZ-76216-CS-CA PA / Contratação de 01 (um a) consultoria individual - Es Institutional Development a pecialista em Geoprocessam Individual Consult TF / A8532 nd Capacity Building for Lan Post Open 107,512.82 Signed 2019-04-22 2019-04-12 2019-06-10 2019-05-14 2019-07-01 2019-06-02 2019-08-05 2019-06-25 2020-02-01 ento Pleno I (mapeamento o ant Selection dscape Management rbital) - Pelas regras da GIZ, trata-se de contrato CLT con forme acordado com o Banc o Mundial na documentação do Projeto. INPE 1 BR-GIZ-76239-CS-CA PA / Contratação de 01 (um a) consultoria individual - A Institutional Development a ssistente em Geoprocessam Individual Consult TF / A8532 nd Capacity Building for Lan Post Open 62,476.22 Terminated 2019-04-22 2019-04-10 2019-06-10 2019-05-14 2019-07-01 2019-05-14 2019-08-05 2019-06-25 2020-02-01 ento Júnior (mapeamento or ant Selection dscape Management bital) - Pelas regras da GIZ, t rata-se de contrato CLT conf orme acordado com o Banco Mundial na documentação d o Projeto. GIZ 3 BR-GIZ-76281-CS-CAP A / Consultoria para Gerenci amento e Monitoramento Ge Project Management, Monit Individual Consult ral do Projeto (equipe base TF / A8532 oring, Evaluation and Com Post Open 339,274.24 Signed 2019-04-04 2019-09-01 2019-05-23 2018-12-05 2019-06-13 2019-01-02 2019-07-18 2019-01-11 2020-01-14 ant Selection GIZ) - Pelas regras da GIZ, tr munication ata-se de contrato CLT conf orme acordado com o Banco Mundial na documentação d o Projeto. INPE BR-GIZ-105361-CS-CA PA / Contratação de 01 (um a) consultoria individual - Es Institutional Development a pecialista em Geoprocessam Individual Consult TF / A8532 nd Capacity Building for Lan Post Open 107,970.17 Signed 2019-04-22 2019-04-22 2019-06-10 2019-06-09 2019-07-01 2019-06-09 2019-08-05 2019-06-25 2020-02-01 ento Pleno I (mapeamento o ant Selection dscape Management rbital) - Pelas regras da GIZ, trata-se de contrato CLT con forme acordado com o Banc o Mundial na documentação do Projeto. INPE BR-GIZ-105364-CS-CA PA / Contratação de 01 (um a) consultoria individual - Es Institutional Development a pecialista em Geoprocessam Individual Consult TF / A8532 nd Capacity Building for Lan Post Open 108,502.36 Terminated 2019-04-22 2019-04-18 2019-06-10 2019-06-05 2019-07-01 2019-06-09 2019-08-05 2019-06-25 2020-02-01 ento Pleno I (mapeamento o ant Selection dscape Management rbital) - Pelas regras da GIZ, trata-se de contrato CLT con forme acordado com o Banc o Mundial na documentação do Projeto. INPE BR-GIZ-105365-CS-CA PA / Contratação de 01 (um a) consultoria individual - Es Institutional Development a pecialista em Geoprocessam Individual Consult TF / A8532 nd Capacity Building for Lan Post Open 176,929.50 Terminated 2019-04-22 2019-04-12 2019-06-10 2019-06-09 2019-07-01 2019-06-09 2019-08-05 2019-06-25 2020-02-01 ento Pleno I (mapeamento o ant Selection dscape Management rbital) - Pelas regras da GIZ, trata-se de contrato CLT con forme acordado com o Banc o Mundial na documentação do Projeto. INPE BR-GIZ-105366-CS-CA PA / Contratação de 01 (um a) consultoria individual - Es Institutional Development a pecialista em Geoprocessam Individual Consult TF / A8532 nd Capacity Building for Lan Post Open 107,970.17 Signed 2019-04-30 2019-03-06 2019-06-18 2019-06-09 2019-07-09 2019-06-09 2019-08-13 2019-06-24 2020-02-09 ento Pleno I (mapeamento o ant Selection dscape Management rbital) - Pelas regras da GIZ, trata-se de contrato CLT con forme acordado com o Banc o Mundial na documentação do Projeto. INPE BR-GIZ-105367-CS-CA PA / Contratação de 01 (um a) consultoria individual - Es Institutional Development a pecialista em Geoprocessam Individual Consult TF / A8532 nd Capacity Building for Lan Post Open 107,970.17 Terminated 2019-04-22 2019-04-10 2019-06-10 2019-05-14 2019-07-01 2019-06-02 2019-08-05 2019-06-24 2020-02-01 ento Pleno I (mapeamento o ant Selection dscape Management rbital) - Pelas regras da GIZ, trata-se de contrato CLT con forme acordado com o Banc o Mundial na documentação do Projeto. INPE BR-GIZ-105369-CS-CA PA / Contratação de 01 (um a) consultoria individual - A Institutional Development a ssistente em Geoprocessam Individual Consult TF / A8532 nd Capacity Building for Lan Post Open 62,476.22 Signed 2019-04-22 2019-04-10 2019-06-10 2019-05-14 2019-07-01 2019-06-09 2019-08-05 2019-06-24 2020-02-01 ento Júnior (mapeamento or ant Selection dscape Management bital) - Pelas regras da GIZ, t rata-se de contrato CLT conf orme acordado com o Banco Mundial na documentação d o Projeto. EMBRAPA BR-GIZ-109805-C S-INDV / Contratação de Con sultoria Individual para siste matização de informações s Mainstreaning Landscape Pr Individual Consult obre recuperação de vegeta TF / A8532 actices into Selected Water Post Open 15,617.86 Completed 2019-06-03 2019-04-22 2019-07-22 2019-07-29 2019-08-12 2019-05-02 2019-09-16 2019-05-07 2020-03-14 2019-11-27 ant Selection ção nativa - Pelas regras da sheds GIZ, trata-se de contrato de consultoria conforme acorda do com o Banco Mundial na documentação do Projeto EMBRAPA BR-GIZ-109831-C S-INDV / Contratação de Con sultoria Individual para siste matização de informações s Mainstreaning Landscape Pr Individual Consult obre ILPF, BPA e recuperaçã TF / A8532 actices into Selected Water Post Open 15,710.01 Completed 2019-05-20 2019-05-08 2019-07-08 2019-06-28 2019-07-29 2019-09-03 2019-09-02 2019-07-06 2020-02-29 2020-09-16 ant Selection o de áreas produtivas degra sheds dadas - Pelas regras da GIZ, trata-se de contrato CLT con forme acordado com o Banc o Mundial na documentação do Projeto SFB BR-GIZ-109844-CS-IND V / Contratação de Consultir a Individual para elaborar di agnóstico e caracterização p Mainstreaning Landscape Pr Individual Consult or sensoriamento remoto da TF / A8532 actices into Selected Water Post Open 6,161.37 Completed 2019-08-05 2019-04-25 2019-09-23 2019-05-02 2019-10-14 2019-05-06 2019-11-18 2019-05-07 2020-05-16 2020-01-02 ant Selection s 53 bacias hidrográficas e o sheds DF do Projeto FIP/Paisagem. Pelas regras da GIZ, trata-se de contrato de consultoria c onforme acordado com o BM SFB BR-GIZ-109845-CS-IND V / Contratação de Consultir a Individual para elaborar di agnóstico socio economico a Mainstreaning Landscape Pr Individual Consult mbiental das 53 bacias hidr TF / A8532 actices into Selected Water Post Open 6,198.71 Completed 2019-08-05 2019-04-11 2019-09-23 2019-07-05 2019-10-14 2019-05-02 2019-11-18 2019-05-03 2020-05-16 2020-01-02 ant Selection ográficas e o DF do Projeto F sheds IP/Paisagem. - Pelas regras da GIZ, trata-se de contrato de consultoria conforme aco rdado com o Banco Mundial Page 8 INPE BR-GIZ-109862-CS-IND V / Contratação de Consulto r individual - Assistente Geo Institutional Development a processamento júnior (análi Individual Consult TF / A8532 nd Capacity Building for Lan Post Open 68,160.53 Signed 2019-08-05 2020-09-28 2019-09-23 2020-11-27 2019-10-14 2020-12-02 2019-11-18 2021-01-19 2020-05-16 se da paisagem) - Pelas regr ant Selection dscape Management as da GIZ, trata-se de contra to CLT conforme acordado c om o Banco Mundial na doc umentação do Projeto. GIZ BR-GIZ-109979-CS-IND V / Consultorias para Suport e Administrativo e de Aquisi Project Management, Monit ções ao Projeto (equipe bas Individual Consult TF / A8532 oring, Evaluation and Com Post Open 149,828.12 Signed 2019-04-10 2018-09-14 2019-05-29 2019-02-18 2019-06-19 2019-01-18 2019-07-24 2019-01-22 2020-01-20 e GIZ) - Consultoria Individu ant Selection munication al. Pelas regras da GIZ, trata -se de contrato CLT conform e acordado com o Banco Mu ndial na documentação do P rojeto. GIZ BR-GIZ-109980-CS-IND V / Consultorias para Suport e Técnico ao Projeto (equipe Project Management, Monit Individual Consult base GIZ) - Consultoria Indiv TF / A8532 oring, Evaluation and Com Post Open 67,462.18 Signed 2019-11-04 2020-07-23 2019-12-23 2020-09-17 2020-01-13 2020-09-17 2020-02-17 2020-10-14 2020-08-15 ant Selection idual. Pelas regras da GIZ, tr munication ata-se de contrato CLT conf orme acordado com o Banco Mundial na documentação d o Projeto. GIZ BR-GIZ-109986-CS-IND Project Management, Monit V / Elaboração do Plano de c Individual Consult TF / A8532 oring, Evaluation and Com Post Open 0.00 Canceled 2019-08-05 2019-09-23 2019-10-14 2019-11-18 2020-05-16 omunicação do projeto - co ant Selection munication muncicação geral do Projeto SFB BR-GIZ-109990-CS-IND V / Cont de Cons de Pessoa Física para analisar as infor m cartográficas de inscriçõe Institutional Development a Individual Consult s de imóveis rurais com até TF / A8532 nd Capacity Building for Lan Post Open 15,295.68 Signed 2019-04-22 2019-05-19 2019-06-10 2019-05-15 2019-07-01 2019-06-06 2019-08-05 2019-05-24 2020-02-01 ant Selection 4 módulos fiscais no Cadastr dscape Management o Ambiental Rural do estado do Maranhão (sub lote 1, 2 e 3) para subsídio da qualifica ção da cobertura do uso do solo SFB BR-GIZ-109991-CS-IND V / Cont de Consultoria de P essoa Física para analisar as informações cartográficas d Institutional Development a Individual Consult e inscrições de imóveis rurai TF / A8532 nd Capacity Building for Lan Post Open 4,592.07 Completed 2019-04-15 2019-05-03 2019-06-03 2019-05-15 2019-06-24 2019-05-15 2019-07-29 2019-05-23 2020-01-25 2020-06-09 ant Selection s com até 4 módulos fiscais dscape Management no Cadastro Ambiental Rural do estado do Minas Gerais ( sub-lote 1,2 e 3)o para subsí dio da qualificação da cob d o sol SFB BR-GIZ-109992-CS-IND V / Cont de Consultoria de P essoa Física para analisar as informações cartográficas d Institutional Development a Individual Consult e inscrições de imóveis rurai TF / A8532 nd Capacity Building for Lan Post Open 3,365.43 Completed 2019-04-22 2019-05-02 2019-06-10 2019-05-15 2019-07-01 2019-05-20 2019-08-05 2019-05-21 2020-02-01 2020-06-09 ant Selection s com até 4 módulos fiscais dscape Management no Cadastro Ambiental Rural do estado do Minas Gerais ( sub-lote 4,5 e 6)o para subsí dio da qualificação da cob d o sol SFB BR-GIZ-109993-CS-IND V / Consultoria de Pessoa Fís ica para analisar as informa ções documentais de inscriç Institutional Development a Individual Consult ões de imóveis rurais com at TF / A8532 nd Capacity Building for Lan Post Open 14,413.97 Signed 2019-04-22 2019-04-25 2019-06-10 2019-05-15 2019-07-01 2019-05-16 2019-08-05 2019-05-17 2020-02-01 ant Selection é 4 módulos fiscais no Cada dscape Management stro Ambiental Rural do esta do do Maranhão (sub lote 1, 2 e 3) para subsídio da quali ficação da cobertura do uso do solo SFB BR-GIZ-109996-CS-IND V / Consultoria de Pessoa Fís ica para analisar as informa ções documentais de inscriç Institutional Development a Individual Consult ões de imóveis rurais com at TF / A8532 nd Capacity Building for Lan Post Open 4,751.27 Completed 2019-04-22 2019-04-25 2019-06-10 2019-05-10 2019-07-01 2019-05-15 2019-08-05 2019-05-20 2020-02-01 2020-06-08 ant Selection é 4 módulos fiscais no Cada dscape Management stro Ambiental Rural do esta do de Minas Gerais (sub lote 1 e 2) para subsídio da quali ficação da cobertura do uso do sol SFB BR-GIZ-109997-CS-IND V / Consultoria de Pessoa Fís ica para analisar as informa ções documentais de inscriç Institutional Development a Individual Consult ões de imóveis rurais com at TF / A8532 nd Capacity Building for Lan Post Open 4,003.88 Completed 2019-04-22 2019-04-25 2019-06-10 2019-05-10 2019-07-01 2019-05-20 2019-08-05 2019-05-20 2020-02-01 2020-06-08 ant Selection é 4 módulos fiscais no Cada dscape Management stro Ambiental Rural do esta do de Minas Gerais (sub lote 3 e 4) para subsídio da quali ficação da cobertura do uso do sol SFB BR-GIZ-109998-CS-IND V / Consultoria de Pessoa Fís ica para analisar as informa ções documentais de inscriç Institutional Development a Individual Consult ões de imóveis rurais com at TF / A8532 nd Capacity Building for Lan Post Open 4,009.84 Completed 2019-04-22 2019-04-22 2019-06-10 2019-05-15 2019-07-01 2019-05-20 2019-08-05 2019-05-30 2020-02-01 2020-06-02 ant Selection é 4 módulos fiscais no Cada dscape Management stro Ambiental Rural do esta do de Minas Gerais (sub lote 5 e 6) para subsídio da quali ficação da cobertura do uso do sol SFB BR-GIZ-112004-CS-IND V / Cont de Consultoria de P essoa Física para analisar as informações cartográficas d Institutional Development a Individual Consult e inscrições de imóveis rurai TF / A8532 nd Capacity Building for Lan Post Open 2,024.44 Completed 2019-05-29 2019-05-02 2019-07-17 2019-05-09 2019-08-07 2019-05-14 2019-09-11 2019-05-20 2020-03-09 2020-06-09 ant Selection s com até 4 módulos fiscais dscape Management no Cadastro Ambiental Rural do estado do Minas Gerais ( sub-lote 6)o para subsídio d a qualificação da cob do sol EMBRAPA CERRADO BR-GIZ -150287-CS-INDV / Contrata ção de assessor técnico par Institutional Development a a monitoramento nas áreas Individual Consult TF / A8532 nd Capacity Building for Lan Post Open 50,523.58 Signed 2019-12-16 2020-02-18 2020-02-03 2020-02-19 2020-02-24 2020-02-20 2020-03-30 2020-03-04 2020-09-26 de referência do Projeto Pais ant Selection dscape Management agens Rurais – Gestão Integr ada da Paisagem, na Embra pa Cerrado e em outras Uni dades de Referência Tecnol ógica definidas. SFB BR-GIZ-152976-CS-IND V / Contratação de Assessor Institutional Development a (a) Técnico(a) para apoio à i Individual Consult TF / A8532 nd Capacity Building for Lan Post Open 54,122.00 Signed 2020-01-12 2020-01-08 2020-03-01 2020-02-21 2020-03-22 2020-02-21 2020-04-26 2020-03-03 2020-10-23 mplementação da Regulariz ant Selection dscape Management ação Ambiental nas bacias p rioritárias do projeto Paisage ns Rurais SFB BR-GIZ-160378-CS-IND Institutional Development a V / Elaborar o Plano de Conti Individual Consult TF / A8532 nd Capacity Building for Lan Post Open 0.00 Canceled 2020-02-21 2020-02-20 2020-04-10 2020-05-01 2020-06-05 2020-12-02 nuidade de Negócio do CAR, ant Selection dscape Management suas integrações e o SICAR. Page 9 SFB BR-GIZ-160383-CS-IND V / Contratar consultor para revisar a topologia, configur Institutional Development a ação e desenho da rede de Individual Consult TF / A8532 nd Capacity Building for Lan Post Open 0.00 Canceled 2020-02-21 2020-02-20 2020-04-10 2020-05-01 2020-06-05 2020-12-02 dados atual do SICAR, com o ant Selection dscape Management objetivo de ampliar, agilizar e maximizar o tráfego de da dos internamente dentro da rede dados dos servidores. SFB BR-GIZ-160389-CS-IND Institutional Development a V / Contratar consultor para Individual Consult TF / A8532 nd Capacity Building for Lan Post Open 0.00 Canceled 2020-02-21 2020-02-20 2020-04-10 2020-05-01 2020-06-05 2020-12-02 redesenhar a arquitetura do ant Selection dscape Management ambiente de hardware de se rvidores para o CAR SFB BR-GIZ-164470-CS-IND V / Consultoria para redesen Institutional Development a har todo ambiente de TI que Individual Consult TF / A8532 nd Capacity Building for Lan Post Open 17,130.78 Completed 2020-03-15 2020-03-26 2020-05-03 2020-05-27 2020-05-24 2020-06-12 2020-06-28 2020-06-13 2020-12-25 2021-02-01 sustenta todos os componen ant Selection dscape Management tes do SICAR através do Proj eto Paisagens Rurais (FIP/Pai sagem). EMBRAPA BR-GIZ-166991-C S-INDV / Contratação de Con sultoria CLT para organizar Institutional Development a e elaborar conteúdo técnico Individual Consult TF / A8532 nd Capacity Building for Lan Post Open 59,650.48 Signed 2020-03-31 2020-03-30 2020-05-19 2020-05-14 2020-06-09 2020-05-18 2020-07-14 2020-06-02 2021-01-10 para cursos de capacitação ant Selection dscape Management de multiplicadores sobre rec uperação de áreas com veg etação nativa degradada em paisagem rural no Bioma Ce rrado BR-GIZ-179870-CS-INDV SF B / Contratação de Assessor Project Management, Monit Individual Consult (a) Técnico(a) para apoio à i TF / A8532 oring, Evaluation and Com Post Open 44,613.36 Signed 2020-06-14 2020-06-24 2020-08-02 2020-09-10 2020-08-23 2020-10-02 2020-09-27 2020-10-21 2021-03-26 ant Selection mplementação do Plano de munication Comunicação do projeto Pai sagens Rurais SFB BR-GIZ-181728-CS-IND V / Consultoria para realizar a organização e compilação Institutional Development a das ações realizadas, result Individual Consult TF / A8532 nd Capacity Building for Lan Post Open 21,463.72 Signed 2020-06-28 2020-11-20 2020-08-16 2021-01-05 2020-09-06 2021-01-11 2020-10-11 2021-01-22 2021-04-09 ados alcançados e impactos ant Selection dscape Management observados na implementaç ão do Plano ABC que podem ser estratégicos para o Proje to Paisagens Rurais (FIP/Pais agem). SFB BR-GIZ-182522-CS-IND V / Consultor 04 – Realizar o levantamento, análise e co mpilação dos resultados de Institutional Development a Individual Consult execução de metas, das exp TF / A8532 nd Capacity Building for Lan Post Open 19,883.06 Signed 2020-06-30 2020-07-08 2020-08-18 2020-09-15 2020-09-08 2020-10-02 2020-10-13 2020-10-14 2021-04-11 ant Selection eriencias, perspectivas e co dscape Management mpromissos em nível estadu al no âmbito do Plano ABC e xecutadas pelos Grupos Ges tores Estaduais na região No rdeste SFB BR-GIZ-183115-CS-IND V / Consultor 02 – Organizar Institutional Development a Individual Consult e compilar as propostas par TF / A8532 nd Capacity Building for Lan Post Open 20,472.81 Signed 2020-07-12 2020-12-08 2020-08-30 2021-01-29 2020-09-20 2021-02-04 2020-10-25 2021-02-16 2021-04-23 ant Selection a o desenvolvimento e impl dscape Management ementação do Plano ABC 20 20-2030 SFB BR-GIZ-183116-CS-IND V / Consultor 03 – Realizar o levantamento, análise e co Institutional Development a Individual Consult mpilação das experiências, TF / A8532 nd Capacity Building for Lan Post Open 15,836.01 Completed 2020-07-12 2020-07-16 2020-08-30 2020-09-15 2020-09-20 2020-09-17 2020-10-25 2020-10-02 2021-04-23 2021-09-11 ant Selection perspectivas e compromisso dscape Management s de instituições públicas e p rivadas parceiras na implem entação do Plano ABC SFB BR-GIZ-183117-CS-IND V / Consultor 05 – Realizar o levantamento, análise e co mpilação dos resultados de Institutional Development a Individual Consult execução de metas, das exp TF / A8532 nd Capacity Building for Lan Post Open 20,270.09 Completed 2020-07-12 2020-07-08 2020-08-30 2020-09-17 2020-09-20 2020-09-21 2020-10-25 2020-10-10 2021-04-23 2021-09-11 ant Selection eriencias, perspectivas e co dscape Management mpromissos em nível estadu al no âmbito do Plano ABC e xecutadas pelos Grupos Ges tores Estaduais nas regiões Norte e Cent SFB BR-GIZ-183119-CS-IND V / Consultor 06 – Realizar o levantamento, análise e co mpilação dos resultados de Institutional Development a Individual Consult execução de metas, das exp TF / A8532 nd Capacity Building for Lan Post Open 14,589.57 Signed 2020-07-12 2021-02-08 2020-08-30 2021-04-06 2020-09-20 2021-04-06 2020-10-25 2021-04-09 2021-04-23 ant Selection eriencias, perspectivas e co dscape Management mpromissos em nível estadu al no âmbito do ABC execut adas pelos Grupos Gestores Estaduais nas regiões Sul e Sudeste EMBRAPA BR-GIZ-183568-C S-INDV / Contratação de Con Institutional Development a Individual Consult sultoria Pessoa Física para e TF / A8532 nd Capacity Building for Lan Post Open 0.00 Canceled 2020-07-10 2020-07-10 2020-08-28 2020-09-18 2020-10-23 2021-04-21 ant Selection laborar o logotipo do Projeto dscape Management Paisagens Rurais projeto Pai sagens Rurais SFB BR-GIZ-184435-CS-IND V / Técnico 3 - Contratação de Assessor(a) Técnico(a) p Institutional Development a Individual Consult ara apoio na compilação de TF / A8532 nd Capacity Building for Lan Post Open 67,462.18 Signed 2020-07-17 2020-07-22 2020-09-04 2020-10-02 2020-09-25 2020-10-02 2020-10-30 2020-10-21 2021-04-28 ant Selection dados do CAR e em soluçõe dscape Management s de geoprocessamento / se nsoriamento remoto no âmb ito do projeto Paisagens Rur ais SFB BR-GIZ-184442-CS-IND V / Contratação de Assessor Institutional Development a Individual Consult (a) Técnico(a) para apoio ao TF / A8532 nd Capacity Building for Lan Post Open 72,080.70 Signed 2020-07-17 2020-07-22 2020-09-04 2020-09-14 2020-09-25 2020-09-14 2020-10-30 2020-10-02 2021-04-28 ant Selection desenvolvimento de soluçõe dscape Management s para Regularização Ambie ntal INPE BR-GIZ-137983-CS-IND Institutional Development a V / Assistente Administrativo Individual Consult TF / A8532 nd Capacity Building for Lan Post Open 0.00 Canceled 2019-10-18 2019-12-06 2019-12-27 2020-01-31 2020-07-29 para apoiar as atividades rel ant Selection dscape Management acionadas ao mapeamento do projeto INPE BR-GIZ-109857-CS-IND V / Contratação de consultor ia individual - Serviços de G Institutional Development a eoprocessamento (mapeam Individual Consult TF / A8532 nd Capacity Building for Lan Post Open 0.00 Canceled 2019-08-05 2019-09-23 2019-10-14 2019-11-18 2020-05-16 ento orbital) - Pelas regras d ant Selection dscape Management a GIZ, trata-se de contrato d e consultoria conforme acor dado com o Banco Mundial na documentação do Projeto . INPE BR-GIZ-109854-CS-IND Institutional Development a V / Contratação consultoria i Individual Consult TF / A8532 nd Capacity Building for Lan Post Open 0.00 Canceled 2019-08-05 2019-09-23 2019-10-14 2019-11-18 2020-05-16 ndividual - Serviços de Geo ant Selection dscape Management processamento (mapeamen to orbital) Page 10 INPE BR-GIZ-109859-CS-IND V / Contratação de consultor ia individual - Serviços de G Institutional Development a eoprocessamento (mapeam Individual Consult TF / A8532 nd Capacity Building for Lan Post Open 0.00 Canceled 2019-08-05 2019-09-23 2019-10-14 2019-11-18 2020-05-16 ento orbital) - Pelas regras d ant Selection dscape Management a GIZ, trata-se de contrato d e consultoria conforme acor dado com o Banco Mundial na documentação do Projeto . INPE BR-GIZ-109950-CS-IND V / Contratação de Consulto r individual - Serviços de Ge Institutional Development a oprocessamento (análise da Individual Consult TF / A8532 nd Capacity Building for Lan Post Open 0.00 Canceled 2019-09-02 2019-10-21 2019-11-11 2019-12-16 2020-06-13 paisagem) - Pelas regras da ant Selection dscape Management GIZ, trata-se de contrato de consultoria conforme acorda do com o Banco Mundial na documentação do Projeto INPE BR-GIZ-109860-CS-IND V / Contratação de consultor ia individual - Serviços de G Institutional Development a eoprocessamento (mapeam Individual Consult TF / A8532 nd Capacity Building for Lan Post Open 0.00 Canceled 2019-08-05 2019-09-23 2019-10-14 2019-11-18 2020-05-16 ento orbital) - Pelas regras d ant Selection dscape Management a GIZ, trata-se de contrato d e consultoria conforme acor dado com o Banco Mundial na documentação do Projeto . INPE BR-GIZ-196031-CS-IND V / Contratação de 01 (uma) consultoria individual - Assis Institutional Development a tente em Geoprocessament Individual Consult TF / A8532 nd Capacity Building for Lan Post Open 36,584.88 Signed 2020-09-28 2020-09-30 2020-11-16 2021-01-06 2020-12-07 2021-01-06 2021-01-11 2021-01-26 2021-07-10 o Júnior (mapeamento orbita ant Selection dscape Management l) - Pelas regras da GIZ, trat a-se de contrato CLT confor me acordado com o Banco Mundial na documentação d o Projeto. INPE EMB BR-GIZ-198052-C S-INDV / Assessor (a) Técnic Institutional Development a o (a) / Analista Junior (a) de Individual Consult TF / A8532 nd Capacity Building for Lan Post Open 36,584.88 Signed 2020-10-13 2020-10-07 2020-12-01 2020-11-23 2020-12-22 2020-11-23 2021-01-26 2021-01-19 2021-07-25 geoprocessamento para ativ ant Selection dscape Management idades de mapeamento do p rojeto FIP Paisagem – “MAPE AMENTO TERRACLASS INPE EMBR BR-GIZ-198053- CS-INDV / Assessor (a) Técni Institutional Development a co (a) / Analista Junior (a) de Individual Consult TF / A8532 nd Capacity Building for Lan Post Open 0.00 Canceled 2020-10-13 2021-02-24 2020-12-01 2020-12-22 2021-01-26 2021-07-25 sistemas para atividades de ant Selection dscape Management apoio ao mapeamento do pr ojeto FIP Paisagem – “MAPE AMENTO TERRACLASS”. INPE BR-GIZ-213289-CS-IND V / Contratação de 01 (uma) consultoria individual - Espe Institutional Development a cialista em Geoprocessamen Individual Consult TF / A8532 nd Capacity Building for Lan Post Open 80,735.91 Terminated 2021-01-25 2021-01-12 2021-03-15 2021-03-01 2021-04-05 2021-03-03 2021-05-10 2021-04-06 2021-11-06 to Pleno I (mapeamento orbi ant Selection dscape Management tal) - Pelas regras da GIZ, tr ata-se de contrato CLT conf orme acordado com o Banco Mundial na documentação d o Projeto. SFB BR-GIZ-228499-CS-IND V / Contratação de Assessor/ a Técnico/a para análise de CAR e desenvolvimento de s Institutional Development a Individual Consult oluções de geoprocessamen TF / A8532 nd Capacity Building for Lan Post Open 66,898.04 Signed 2021-04-12 2021-04-13 2021-05-31 2021-06-22 2021-06-21 2021-06-22 2021-07-26 2021-07-06 2022-01-22 ant Selection to / sensoriamento remoto - dscape Management Pelas regras da GIZ, trata-se de contrato CLT conforme a cordado com o Banco Mundi al na documentação do Proj eto. SFB BR-GIZ-228500-CS-IND V / Contratação de Assessor (a) Técnico(a) para análise d Institutional Development a e documentação de imóveis Individual Consult TF / A8532 nd Capacity Building for Lan Post Open 40,884.49 Signed 2021-04-12 2021-04-13 2021-05-31 2021-06-11 2021-06-21 2021-06-17 2021-07-26 2021-07-06 2022-01-22 rurais inscritos e retificados ant Selection dscape Management no CAR - Pelas regras da GIZ , trata-se de contrato CLT co nforme acordado com o Ban co Mundial na documentaçã o do Projeto. GIZ 3.2 BR-GIZ-238979-CS-I NDV / Contratação de consul Project Management, Monit Individual Consult tor individual para elaborar TF / A8532 oring, Evaluation and Com Post Open 17,699.17 Signed 2021-06-14 2021-06-24 2021-08-02 2021-07-16 2021-08-23 2021-07-21 2021-09-27 2021-08-10 2022-03-26 ant Selection o Relatório de Avaliação par munication a a Revisão de Meio Termo do Projeto FIP Paisagens Rur ais SFB BR-GIZ-161952-CS-IND Institutional Development a Individual Consult V / Retificação dos CARs de i TF / A8532 nd Capacity Building for Lan Post Open 0.00 Canceled 2020-10-04 2020-11-22 2020-12-13 2021-01-17 2021-07-16 ant Selection móveis rurais contemplados dscape Management pelo Projeto SFB BR-GIZ-161969-CS-IND V / Contratação de consultor individual para realizar ofici Institutional Development a nas participativas de elabor Individual Consult TF / A8532 nd Capacity Building for Lan Post Open 0.00 Canceled 2020-06-01 2020-07-20 2020-08-10 2020-09-14 2021-03-13 ação e pactuação do plano, ant Selection dscape Management para o lançamento e a difus ão do plano de ação de cada uma das bacias e mobilizaçã o dos Comitês de Bacias SFB BR-GIZ-161951-CS-IND V / Desenvolvimento de met odologia de monitoramento Institutional Development a Individual Consult de áreas restauradas (fortal TF / A8532 nd Capacity Building for Lan Post Open 0.00 Canceled 2020-06-01 2020-07-20 2020-08-10 2020-09-14 2021-03-13 ant Selection ecer a oferta de serviços de dscape Management monitoramento) e aplicação por dois ciclos de monitora mento (T.0, T.1 e T.2). SFB BR-GIZ-110007-CS-IND V / Consultoria Individual pa ra Produção de material info rmativo para divulgação das Institutional Development a Individual Consult atuação do SFB incluindo o TF / A8532 nd Capacity Building for Lan Post Open 0.00 Canceled 2021-10-04 2021-11-22 2021-12-13 2022-01-17 2022-07-16 ant Selection projeto FIP Paisagem - Pelas dscape Management regras da GIZ, trata-se de co ntrato de consultoria confor me acordado com o Banco Mundial na documentação SFB BR-GIZ-110005-CS-IND V / Consultoria Individual pa ra Produção de videos infor Institutional Development a mativos para divulgação do Individual Consult TF / A8532 nd Capacity Building for Lan Post Open 0.00 Canceled 2021-10-04 2021-11-22 2021-12-13 2022-01-17 2022-07-16 SFB, incluindo o projeto FIP ant Selection dscape Management Paisagem - Pelas regras da GIZ, trata-se de contrato de consultoria conforme acorda do com o Banco Mundial na documentação SFB BR-GIZ-161954-CS-IND V / Consultoria Individual pa Institutional Development a Individual Consult ra o levantamento, sistemati TF / A8532 nd Capacity Building for Lan Post Open 0.00 Canceled 2020-07-05 2020-08-23 2020-09-13 2020-10-18 2021-04-16 ant Selection zação e divulgação de dado dscape Management s e informações (incluindo e conômicos); SFB BR-GIZ-161618-CS-IND Institutional Development a Individual Consult V / Apoio o fortalecimento d TF / A8532 nd Capacity Building for Lan Post Open 0.00 Canceled 2020-05-03 2020-06-21 2020-07-12 2020-08-16 2021-02-12 ant Selection e redes de sementes dscape Management Page 11 SFB BR-GIZ-161944-CS-IND V / Diagnósticos, mapeamen to e elaboração de portifólio de divulgação da sistematiz Institutional Development a Individual Consult ação de experiências prática TF / A8532 nd Capacity Building for Lan Post Open 0.00 Canceled 2020-05-03 2020-06-21 2020-07-12 2020-08-16 2021-02-12 ant Selection s de imóveis rurais públicos dscape Management e privados quanto às ativida des e empreendimentos de recuperação/recomposição de áreas degradadas, silvicu ltura, e solu SFB BR-GIZ-161936-CS-IND Institutional Development a V / Monitoramento e avaliaç Individual Consult TF / A8532 nd Capacity Building for Lan Post Open 0.00 Canceled 2021-10-04 2021-11-22 2021-12-13 2022-01-17 2022-07-16 ao das açoes de regularizaç ant Selection dscape Management ao e recuperaçaoambiental EMBRAPA BR-GIZ-161599-C S-INDV / Contratação de Con sultoria Pessoa Física (analis ta) para coordenar a assiste Mainstreaning Landscape Pr Individual Consult ncia tecnica virtual no monit TF / A8532 actices into Selected Water Post Open 0.00 Canceled 2021-07-30 2021-09-17 2021-10-08 2021-11-12 2022-05-11 ant Selection oramento de indicadores tec sheds nicos e socioeconomicos da recuperação das pastagens e de APP e de Reserva Legal das URTs e nas bacias hidro graficas. EMBRAPA BR-GIZ-161526-C S-INDV / Contratação consul tor individual (Pessoa Física - analista) para realizar estu Institutional Development a Individual Consult do prospectivo de análise so TF / A8532 nd Capacity Building for Lan Post Open 31,757.40 Terminated 2021-10-04 2021-11-12 2021-11-22 2022-01-12 2021-12-13 2022-01-27 2022-01-17 2022-01-22 2022-07-16 ant Selection cioeconômica da cadeia da r dscape Management estauração e recomposição da vegetação nativa em APP e ARL nas propriedades rura is e URTs do Distrito Federal e das bacia EMBRAPA BR-GIZ-161529-C S-INDV / Contratação consul tor individual (Pessoa Física - analista) para caracterizaç Institutional Development a Individual Consult ão e análise da estrutura e d TF / A8532 nd Capacity Building for Lan Post Open 31,757.40 Signed 2021-10-04 2021-11-12 2021-11-22 2022-02-03 2021-12-13 2022-02-09 2022-01-17 2022-03-08 2022-07-16 ant Selection a dinâmica das unidades de dscape Management paisagem por meio de levan tamento de campo, process amento e análise de fotogra fias digitais verticais e panor âmicas em pro EMBRAPA BR-GIZ-161602-C S-INDV / Contratação de con sultoria individual (Pessoa Fí sica - analista) para coorden Institutional Development a Individual Consult ação do diagnostico, implant TF / A8532 nd Capacity Building for Lan Post Open 32,524.11 Signed 2021-10-04 2021-10-29 2021-11-22 2022-01-26 2021-12-13 2022-01-27 2022-01-17 2022-02-15 2022-07-16 ant Selection ação e monitoramento das a dscape Management tividades de restauração de vegetação nativa em APP e Reserva Legal em proprieda des rurais e nas URTs do Dis trito Federal e EMBRAPA BR-GIZ-161542-C S-INDV / Contratação de ana lista (CLT) para realização d o diagnostico, implantação e Institutional Development a Individual Consult monitoramento de indicador TF / A8532 nd Capacity Building for Lan Post Open 63,023.14 Signed 2021-10-04 2021-10-29 2021-11-22 2021-12-24 2021-12-13 2022-01-17 2022-01-17 2022-01-25 2022-07-16 ant Selection es tecnicos e socioeconomic dscape Management os de boas práticas e sistem as de produção agropecuári a (recuperação das pastage ns) nas propriedades rurais e URTs do DF e da EMBRAPA BR-GIZ-109839-C S-INDV / Contratação de Con sultoria individual na área d e engenharia para elaboraçã Institutional Development a Individual Consult o de projeto básico e execut TF / A8532 nd Capacity Building for Lan Post Open 0.00 Canceled 2021-04-29 2021-06-17 2021-07-08 2021-08-12 2022-02-08 ant Selection ivo para as reformas do aud dscape Management itório, salas de aula, salas d e video e viveiro da EMBRA PA Cerrados - Pelas regras d a GIZ, trata-se de contrato d e consultor SFB BR-GIZ-242063-CS-IND V / Contratação de consultor Institutional Development a ia individual para apoio no d Individual Consult TF / A8532 nd Capacity Building for Lan Post Open 0.00 Canceled 2021-10-04 2021-11-22 2021-12-13 2022-01-17 2022-07-16 esenvolvimento e analise de ant Selection dscape Management documentos referentes a im plementação e execução da s ações do SFB no Projeto. SFB BR-GIZ-242068-CS-IND V / Contratação de Assessor/ a Técnico/a Sênior para fort Institutional Development a Individual Consult alecimento da agenda de re TF / A8532 nd Capacity Building for Lan Post Open 0.00 Signed 2021-08-24 2021-08-30 2021-10-12 2021-12-02 2021-11-02 2022-03-11 2021-12-07 2022-06-05 ant Selection gularização ambiental e arti dscape Management culação institucional junto a parceiros estratégicos do Pr ojeto FIP Paisagens Rurais INPE BR-GIZ-254480-CS-IND V / Contratação de 01 (uma) consultoria individual - Espe Institutional Development a cialista em Geoprocessamen Individual Consult TF / A8532 nd Capacity Building for Lan Post Open 47,126.13 Signed 2021-09-21 2021-10-01 2021-11-09 2021-09-20 2021-11-30 2021-09-21 2022-01-04 2021-10-14 2022-07-03 to Pleno I (mapeamento orbi ant Selection dscape Management tal) - Pelas regras da GIZ, tr ata-se de contrato CLT conf orme acordado com o Banco Mundial na documentação d o Projeto. GIZ BR-GIZ-109975-CS-IND Project Management, Monit V / Consultoria Individual pa Individual Consult TF / A8532 oring, Evaluation and Com Post Open 0.00 Canceled 2022-01-03 2022-02-21 2022-03-14 2022-04-18 2022-10-15 ra elaborar Relatório Final d ant Selection munication e Revisão de Meio Termo EMBRAPA BR-GIZ-109803-C S-INDV / Contratação de ana lista (CLT) para o processa mento e sistematização da i Institutional Development a Individual Consult nformação tecnológica para TF / A8532 nd Capacity Building for Lan Post Open 0.00 Canceled 2021-10-04 2021-11-22 2021-12-13 2022-01-17 2022-07-16 ant Selection a caracterização da estrutur dscape Management a e da dinâmica das unidade s de paisagem com interven ções técnicas de boas prátic as e sistemas de produção a gropecuária (recupe INPE BR-GIZ-264686-CS-IND Institutional Development a V / Analista Pleno/a de geop Individual Consult TF / A8532 nd Capacity Building for Lan Post Open 0.00 Signed 2021-11-28 2021-11-24 2022-01-16 2022-02-15 2022-02-06 2022-03-21 2022-03-13 2022-09-09 rocessamento para atividad ant Selection dscape Management es de mapeamento GIZ BR-GIZ-269444-CS-IND Project Management, Monit Individual Consult Under Implement V / Consultoria para Suporte TF / A8532 oring, Evaluation and Com Post Open 0.00 2022-01-03 2021-12-22 2022-02-21 2022-03-24 2022-03-14 2022-03-24 2022-04-18 2022-10-15 ant Selection ation Técnico ao Projeto (equipe b munication ase GIZ) INPE BR-GIZ-270564-CS-IND V / Desenvolvedor/a / Geren Mainstreaning Landscape Pr Individual Consult Under Implement ciador/a de Banco de Dados TF / A8532 actices into Selected Water Post Open 0.00 2022-01-03 2022-01-05 2022-02-21 2022-07-07 2022-03-14 2022-02-07 2022-04-18 2022-10-15 ant Selection ation para atividades de Monitora sheds mento do Desmatamento no Cerrado Brasileiro Page 12 INPE BR-GIZ-270566-CS-IND V / Coordenador/a de Projet Mainstreaning Landscape Pr Individual Consult o de geoprocessamento par TF / A8532 actices into Selected Water Post Open 38,755.42 Signed 2022-01-03 2022-01-05 2022-02-21 2022-02-25 2022-03-14 2022-03-02 2022-04-18 2022-03-15 2022-10-15 ant Selection a atividades de Monitorame sheds nto do Desmatamento no Ce rrado Brasileiro INPE BR-GIZ-270570-CS-IND V / Auditores/as Plenos de g Mainstreaning Landscape Pr Individual Consult eoprocessamento para ativi TF / A8532 actices into Selected Water Post Open 27,186.90 Signed 2022-01-03 2022-01-05 2022-02-21 2022-02-23 2022-03-14 2022-02-23 2022-04-18 2022-03-04 2022-10-15 ant Selection dades de Monitoramento do sheds Desmatamento no Cerrado Brasileiro BR-GIZ-270574-CS-INDV / A uditores/as Plenos de geopr Mainstreaning Landscape Pr Individual Consult ocessamento para atividade TF / A8532 actices into Selected Water Post Open 0.00 Signed 2022-01-03 2022-01-05 2022-02-21 2022-02-23 2022-03-14 2022-02-23 2022-04-18 2022-10-15 ant Selection s de Monitoramento do Des sheds matamento no Cerrado Bras ileiro INPE BR-GIZ-270578-CS-IND V / Auditores/as Seniores de Mainstreaning Landscape Pr Individual Consult Under Implement geoprocessamento para ativ TF / A8532 actices into Selected Water Post Open 0.00 2022-01-03 2022-01-05 2022-02-21 2022-02-25 2022-03-14 2022-03-14 2022-04-18 2022-10-15 ant Selection ation idades de Monitoramento do sheds Desmatamento no Cerrado Brasileiro INPE BR-GIZ-270580-CS-IND V / Auditores/as Seniores de Mainstreaning Landscape Pr Individual Consult geoprocessamento para ativ TF / A8532 actices into Selected Water Post Open 0.00 Signed 2022-01-03 2022-01-05 2022-02-21 2022-02-25 2022-03-14 2022-02-14 2022-04-18 2022-10-15 ant Selection idades de Monitoramento do sheds Desmatamento no Cerrado Brasileiro INPE BR-GIZ-277577-CS-IND Institutional Development a V / Analista Pleno/a de geop Individual Consult TF / A8532 nd Capacity Building for Lan Post Open 0.00 Signed 2022-03-07 2022-02-09 2022-04-25 2022-03-24 2022-05-16 2022-04-08 2022-06-20 2022-12-17 rocessamento para atividad ant Selection dscape Management es de mapeamento BR-GIZ-277578-CS-INDV / A Institutional Development a Individual Consult nalista Pleno/a de geoproces TF / A8532 nd Capacity Building for Lan Post Open 0.00 Signed 2022-03-07 2022-02-09 2022-04-25 2022-03-24 2022-05-16 2022-04-08 2022-06-20 2022-12-17 ant Selection samento para atividades de dscape Management mapeamento GIZ BR-GIZ-280764-CS-IND Project Management, Monit Individual Consult Under Implement V / Moderador da Oficina de TF / A8532 oring, Evaluation and Com Post Open 0.00 2022-02-28 2022-03-07 2022-04-18 2023-04-14 2022-05-09 2022-04-20 2022-06-13 2022-12-10 ant Selection ation Revisão de Meio Termo munication SDI BR-GIZ-283625-CS-IND V / Consultoria para apoio à Institutional Development a Individual Consult identificação, seleção, verifi TF / A8532 nd Capacity Building for Lan Post Open 0.00 Signed 2022-03-11 2022-03-21 2022-04-29 2022-08-25 2022-05-20 2022-08-25 2022-06-24 2022-12-21 ant Selection cação e avaliação de novos dscape Management potenciais SPSABC a serem i ncluídos no Plano ABC+ SDI BR-GIZ-283626-CS-IND V / Analisar e propor mecani smos de reconhecimento e Institutional Development a Individual Consult valorização para propriedad TF / A8532 nd Capacity Building for Lan Post Open 0.00 Signed 2022-03-11 2022-03-21 2022-04-29 2023-01-16 2022-05-20 2023-01-26 2022-06-24 2022-12-21 ant Selection es e produtos relacionados a dscape Management os Sistemas, Práticas, Produ tos e Processos de Produção Sustentáveis (SPSABC) SDI BR-GIZ-283705-CS-IND V / apoiar os Grupos Gestore Institutional Development a Individual Consult s Estaduais da região Norde TF / A8532 nd Capacity Building for Lan Post Open 0.00 Signed 2022-03-11 2022-04-27 2022-04-29 2022-06-02 2022-05-20 2022-08-03 2022-06-24 2022-12-21 ant Selection ste para atualização e propo dscape Management sição de Planos de Ação Est aduais alinhados ao ABC+ SDI BR-GIZ-283710-CS-IND V / Consultoria para apoiar o Institutional Development a s Grupos Gestores Estaduais Individual Consult TF / A8532 nd Capacity Building for Lan Post Open 0.00 Signed 2022-03-11 2022-04-27 2022-04-29 2022-07-06 2022-05-20 2022-08-03 2022-06-24 2022-12-21 da região Centro-Oeste para ant Selection dscape Management atualização e proposição de Planos de Ação Estaduais ali nhados ao ABC+ SDI BR-GIZ-283715-CS-IND V / Consultoria para apoiar o Institutional Development a s Grupos Gestores Estaduais Individual Consult Under Implement TF / A8532 nd Capacity Building for Lan Post Open 0.00 2022-03-11 2022-04-27 2022-04-29 2022-08-03 2022-05-20 2022-08-16 2022-06-24 2022-12-21 da região Sudeste para atua ant Selection ation dscape Management lização e proposição de Plan os de Ação Estaduais alinha dos ao ABC+ EMBRAPA BR-GIZ-298267-C S-INDV / Contratação consul tor individual (Pessoa Física - analista) para realizar estu Institutional Development a Individual Consult do prospectivo de análise so TF / A8532 nd Capacity Building for Lan Post Open 0.00 Signed 2022-06-13 2022-06-10 2022-08-01 2022-07-18 2022-08-22 2022-07-18 2022-09-26 2023-03-25 ant Selection cioeconômica da cadeia da r dscape Management estauração e recomposição da vegetação nativa em APP e ARL nas propriedades rura is e URTs do Distrito Federal e das bacia INPE BR-GIZ-298268-CS-IND V / Contratação de Consulto r individual - Assistente Geo Institutional Development a processamento júnior (análi Individual Consult Under Implement TF / A8532 nd Capacity Building for Lan Post Open 0.00 2022-06-06 2022-06-03 2022-07-25 2022-08-15 2022-08-15 2022-08-17 2022-09-19 2023-03-18 se da paisagem) - Pelas regr ant Selection ation dscape Management as da GIZ, trata-se de contra to CLT conforme acordado c om o Banco Mundial na doc umentação do Projeto. COM BR-GIZ-310605-CS-IN DV / Contratação de consult oria pessoa física para exec Project Management, Monit Individual Consult Under Implement ução de serviços especializa TF / A8532 oring, Evaluation and Com Post Open - National 0.00 2022-08-29 2022-08-24 2022-10-17 2022-09-26 2022-11-07 2022-09-30 2022-12-12 2023-06-10 ant Selection ation dos em customização de pai munication néis gerenciais dinâmicos b aseados em solução de Pow er BI (Business Intelligence) SFB BR-GIZ-316624-CS-IND V / Assessor/a Técnico/a par Institutional Development a a apoiar o Serviço Florestal Individual Consult TF / A8532 nd Capacity Building for Lan Post Open - National 0.00 Signed 2022-09-16 2022-09-29 2022-11-04 2022-12-30 2022-11-25 2023-01-04 2022-12-30 2023-06-28 Brasileiro (SFB/MAPA) em aç ant Selection dscape Management ões estratégicas de planeja mento e execução das ativid ades EMBRAPA BR-GIZ-320200-C S-INDV / Contratação de con sultoria individual (Pessoa Fí sica - analista) para coorden Institutional Development a Individual Consult ação do diagnostico, implant TF / A8532 nd Capacity Building for Lan Post Open - National 0.00 Signed 2022-10-31 2022-10-27 2022-12-19 2022-12-28 2023-01-09 2023-01-04 2023-02-13 2023-08-12 ant Selection ação e monitoramento das a dscape Management tividades de restauração de vegetação nativa em APP e Reserva Legal em proprieda des rurais e nas URTs do Dis trito Federal INPE BR-GIZ-320201-CS-IND Institutional Development a V / Analista Pleno/a de geop Individual Consult TF / A8532 nd Capacity Building for Lan Post Open - National 0.00 Signed 2022-11-28 2022-11-03 2023-01-16 2022-09-19 2023-02-06 2022-10-31 2023-03-13 2023-09-09 rocessamento para atividad ant Selection dscape Management es de mapeamento INPE BR-GIZ-327287-CS-IND Institutional Development a V / Analista Pleno/a de geop Individual Consult TF / A8532 nd Capacity Building for Lan Post Open - National 0.00 Signed 2022-11-28 2022-11-25 2023-01-16 2022-12-13 2023-02-06 2023-03-31 2023-03-13 2023-09-09 rocessamento para atividad ant Selection dscape Management es de mapeamento Page 13 SFB BR-GIZ-161615-CS-IND V / Prestação de serviços téc nicos especializados em pro Institutional Development a cessos de educação em am Individual Consult TF / A8532 nd Capacity Building for Lan Post Open - National 0.00 Signed 2022-12-13 2023-01-10 2023-01-31 2023-03-10 2023-02-21 2023-03-13 2023-03-28 2023-09-24 biente virtual de aprendizag ant Selection dscape Management em para realizar a facilitaçã o, moderação, monitoria e g estão do Portal Saberes da F loresta e dos curso INPE BR-GIZ-343766-CS-IND Institutional Development a V / Contratação de Consulto Individual Consult TF / A8532 nd Capacity Building for Lan Post Open - National 0.00 Signed 2023-02-17 2023-02-22 2023-04-07 2023-05-05 2023-04-28 2023-05-05 2023-06-02 2023-11-29 r individual - Assistente Geo ant Selection dscape Management processamento júnior (análi se da paisagem) SFB BR-GIZ-343769-CS-IND Institutional Development a V / Contratação de pessoa fí Individual Consult Under Implement TF / A8532 nd Capacity Building for Lan Post Open - National 0.00 2023-02-27 2023-02-22 2023-04-17 2023-04-19 2023-05-08 2023-06-12 2023-12-09 sica especializada para análi ant Selection ation dscape Management se de Cadastros Ambientais Rurais - CAR em bacias SFB BR-GIZ-350696-CS-IND V / Contratação de consultor ia pessoa física especializad Institutional Development a Individual Consult Under Implement a para análise de Cadastros TF / A8532 nd Capacity Building for Lan Post Open - National 0.00 2023-03-28 2023-03-20 2023-05-16 2023-06-06 2023-07-11 2024-01-07 ant Selection ation Ambientais Rurais - CAR em dscape Management bacias do Projeto Paisagens Rurais (FIP/Paisagem) no est ado de Minas Gerais. SDI BR-GIZ-350698-CS-IND V / Consultoria para aprimor Institutional Development a ar o reporte de ações do AB Individual Consult Pending Impleme TF / A8532 nd Capacity Building for Lan Post Open - National 0.00 2023-03-28 2023-05-16 2023-06-06 2023-07-11 2024-01-07 C+ no âmbito do Inventário ant Selection ntation dscape Management Nacional de emissões e rem oções de GEE relacionadas a os setores agropecuário e L ULUCF GIZ BR-GIZ-357685-CS-IND Project Management, Monit Individual Consult Under Implement V / Consultoria para Suporte TF / A8532 oring, Evaluation and Com Post Open - National 0.00 2023-04-24 2023-05-03 2023-06-12 2023-07-03 2023-08-07 2024-02-03 ant Selection ation Técnico ao Projeto (equipe b munication ase GIZ) SFB BR-GIZ-361336-CS-IND V / Para apoiar o Serviço Flo Institutional Development a restal Brasileiro (SFB/MAPA) Individual Consult Pending Impleme TF / A8532 nd Capacity Building for Lan Post Open - National 0.00 2023-05-22 2023-07-10 2023-07-31 2023-09-04 2024-03-02 em ações estratégicas de pl ant Selection ntation dscape Management anejamento e execução das atividades voltadas à Cadeia do Restauro SFB BR-GIZ-364453-CS-IND V / Para apoiar o Serviço Flo restal Brasileiro (SFB/MMA) quanto ao planejamento e e Institutional Development a Individual Consult Under Implement xecução das atividades estr TF / A8532 nd Capacity Building for Lan Post Open - National 0.00 2023-06-26 2023-06-05 2023-08-14 2023-09-04 2023-10-09 2024-04-06 ant Selection ation atégicas da plataforma EaD dscape Management Portal Saberes da Floresta n o âmbito do Projeto “Gestão Integrada de Paisagens no B ioma Cerrado – FIP Paisagen s Rurais” SFB BR-GIZ-364454-CS-IND V / Contratação de Assessor (a) Técnico(a) Sênior para e Institutional Development a Individual Consult Pending Impleme struturar e coordenar uma e TF / A8532 nd Capacity Building for Lan Post Open - National 0.00 2023-06-26 2023-08-14 2023-09-04 2023-10-09 2024-04-06 ant Selection ntation stratégia de Gestão Integrad dscape Management a da Paisagem (GIP) e uma das áreas de atuação do pro jeto FIP Paisagens Rurais SFB BR-GIZ-364456-CS-IND V / apoiar o Serviço Florestal Brasileiro (SFB/MAPA) em aç Institutional Development a Individual Consult Pending Impleme ões estratégicas de planeja TF / A8532 nd Capacity Building for Lan Post Open - National 0.00 2023-06-26 2023-08-14 2023-09-04 2023-10-09 2024-04-06 ant Selection ntation mento e execução das ativid dscape Management ades relacionadas à Regular ização Ambiental, no âmbito do Projeto FIP Paisagens Rur ais Page 14 AGRICULTURAL PRODUCTIVITY AND NUTRITION IMPROVEMENT PROJECT 1. Procurement for the proposed Project be carried out in accordance with Guidelines: Procurement of Goods, Works and Non-consulting Services under IBRD Loans and IDA Credits and Grants by World Bank Borrowers” dated January 2011 (revised July 2014) and “Guidelines: Selection and Employment of Consultants under IBRD Loans and IDA Credits and Grants by World Bank Borrowers” dated January 2011 (revised July 2014). The various items under different expenditure categories are described in general below. 2. The World Bank Guidelines on Preventing and Combating Fraud and Corruption in Projects Financed by IBRD Loans and IDA Credit and Grants dated October 15, 2006 and revised on January 2011, will also apply. For each contract to be financed by the Bank, the different procurement methods or consultant selection methods, the need for prequalification, estimated costs, prior review requirements, and time frame are agreed between the GoK and the Bank task team in the Procurement Plan. The Procurement Plan will be updated at least annually or as required to reflect the actual project implementation needs and improvements in institutional capacity. 3. Procurement of Works: Works procured under this project would include (i) rehabilitation of existing on- and off-farm I&D systems; (ii) installation of intake structures at on-farm systems. 4. Procurement of Goods: Goods procured under this project would include procurement of maintenance equipment for WUAs and FWUAs, water measuring equipment for WUAs, minor food processing equipment for households, micronutrient supplements, and office equipment and vehicles for PIU. Micronutrients will be procured through UNICEF under the existing procurement agreement with the MoH. 5. Selection of Consultants: Consultancy would include (i) technical assistance in such areas as detailed design, contract administration, construction and supervision; (ii) technical assistance to rehabilitated WUAs in contract management and preparation of TORs, (iii) technical advisory services on improved agricultural production and improved marketing; (iv) technical advisory services for improved cropping patterns towards higher shares of nutritional crops; (v) technical advisory services on improved on-farm water management; (vi) M&E; (vi) international and local technical assistance for preparation of improved irrigated agricultural production and marketing and diversification towards nutritional crops; and (vii) local consultants to support FSC for improved national coordination for food and nutrition security. 6. Short-lists of consultants for services estimated to cost less than U$100,000 equivalent per contract may be composed entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. The Bank's Standard Request for Proposal Document would be used as a base for all procurement of consultancy services to be procured under the project. Some of the PIU staff hired under previous projects would continue working for implementation of the project. 7. Training: Training will cover training to (i) WUAs selected for components 1 and 2 on improved irrigated agricultural production, improved marketing and diversification towards nutritional crops, improved water management and IPM, (ii) raion level health promotion unit staff of MoH under component 3 on health promotion related activities, (iii) vulnerable households and self-help groups under components 3.1 and 3.3 on improved consumption of nutritional food and increased production of nutritional food on household plots, and (iv) PIU staff on procurement, financial management, M&E, IPM and other project management related activities. 8. Operating Costs: The grant will finance incremental operating costs. Operating costs will cover vehicle maintenance for PIU and WUA SUs, fuel, utility and communication costs, translation costs, travel expenses, bank charges, office supplies, advertisement costs, printing, mail, as well as other reasonable expenditures directly associated with the implementation of the project. Such costs would be financed by the project as per an annual budget approved by the Bank and incurred using the implementing agency’s administrative procedures. Operating costs will not include salaries of civil servants. It will also finance the operating costs of the Food Security Council (FSC) for the period of two years. 9. Project will also finance grants to WUAs for: (i) contracting advisory service providers to assist WUAs in the preparation of agricultural development plans, provision of advice and facilitation of development plan implementation; and (ii) procurement of inputs, materials, cultivation equipment, soil and water testing equipment or other equipment, and minor improvements in farm infrastructure required for the training and demonstration aspects of the agricultural development plan. 10. Delegation of the Procurement Function to WUAs. The execution of procurement for grants will be delegated to WUAs. Procurement responsibilities, procedures and sample documentation are described in detail in the Project Implementation Manual (PIM) and in the WUA Procurement Handbook. . The micro-projects will include the procurement of goods, works, consultant services and training. WUA will manage micro-project implementation. These procedures will be harmonized with public procurement procedures to ensure sustainable capacity building. They require local advertisement and public bid opening, using the sample bidding documents and standard contract forms developed for community procurement for micro-projects (and included in the IM and the WUA Procurement Handbook). 11. Each WUA will allocate a part of its public information board for posting information on contract awards, including the name of each vendor who submitted a quotation, prices as read out at public opening, name and evaluated prices of each quotation that was evaluated, name of vendors who were rejected and the reasons for rejection, the name of the winning vendor and the price it offered, as well as duration and summary of the scope of the contract award. All contracts awarded through direct contracting (irrespective of the amount) shall be listed on the information board. 12. Assessment of the agencies’ capacity to implement procurement. The implementation responsibility of the project will lie with the DWRLI through the PIU. The main activities to be procured under the project include civil works for rehabilitation of on-farm irrigation systems for 30 WUAs and FWUAs, technical equipment for WUAs, goods like seeds, agricultural tools, consultant services for design and technical supervision, agricultural advisory and nutrition services, project audit, and training and salaries of PIU staff. Individual consultants for design and technical supervision and asset management can be hired based on single source selection if they have worked for the OIP-2 and AF in the same capacity and their performance was rated satisfactory. The PIU staff hired under the OIP-2 and AF will continue working for implementation of the project activities if their performance was rated satisfactory. 13. A procurement plan has been developed covering the above procurement activities and will be agreed during negotiations. Thereafter, the plan will be updated periodically, at least once per year, and each update will be subject to the Bank’s prior review. The initial procurement plan plus the subsequent updates will be published on the Bank’s external web site in line with the requirements of Bank Guidelines. 14. Procurement Supervision and Ex-post Review: Routine procurement reviews and supervision will be provided by the procurement analyst based in the country office. In addition, two supervision missions are expected to take place per year during which ex-post reviews will be conducted for the contracts that are not subject to Bank prior review on a sample basis (20 percent in terms of number of contracts). One ex-post review report will be prepared per fiscal year, including findings of physical inspections for not less than 10 percent of the contracts awarded during the review period. 15. Procurement Thresholds and Methods of Procurement: The following methods of procurement shall be used for procurement under the project. It has been agreed that if a particular invitation for a bid is comprised of several packages, lots or slices, and invited in the same invitation for bid, then the aggregate value of the whole package determines the applicable threshold amount for procurement and also for the review by the Bank. The national competitive bidding (NCB) conditions will be part of the Grant Agreement. Contract Contracts Subjects to Expenditure Value Procurement Prior Review (Threshold Category Threshold Method in US$) (US$) >=1,000,000 ICB Contracts >=1,500,000 Goods and non- <1,000,000 NCB Not applicable consultancy <100,000 SH Not applicable services N/A DC Contracts >= 1,500,000 >=5,000,000 ICB Contracts >= 5,000,000 Works <5,000,000 NCB Not applicable <200,000 SH Not applicable N/A DC Contracts >=$5,000,000 >=300,000 QCBS/QBS/LCS/FBS In addition to the Consultant above listed Contracts >= 500,000; all <300,000 Services* methods, CQS may TORs (including be used training) N/A SSS Contracts with individuals N/A IC >= 200,000; all TORs *Consultancy: national short list for contracts 2,000,000$ M>500,000 2. AON Néant M<500,000 3. Cotation Néant M<100,000 4. UNOPS >2,000,000 Travaux 4. AOI >10,000,000 M>3,000,000 5. AON Néant M<3,000,000 6. Demande de devis Néant M<200,000 7. Entente directe Même que AOI 2. Préqualification : Les soumissionnaires pour _____________ seront pré- qualifiés selon les dispositions des paragraphes 6.19 à 6.26 du Règlement. 3. Procédures proposées pour les composantes CDD (selon le paragraphe. 6.52 du Règlement : non applicable 4. Référence (s’il y en a) au Manuel d’exécution du projet / Manuel de Passation de marchés : Manuel simplifié à élaborer pour le besoin du PPA 5. Tout autre arrangement spécial en passation de marchés : non applicable 6. Allotissement de fournitures avec méthodes et calendrier : 1 2 3 4 5 6 7 8 9 Pré- Préféren Revue de Date qualificatio ce la prévue Coût Méthode n nationale Banque Réf. d’ouvertur Commentair Description Contrat estimat de (à priori No e des es if (en $) sélection /à Oui / Non Oui / Non soumissio posterior ns i) Acquisition matériel informatique et fournitures de bureau A 11/21/202 Responsabl (imprimante, 100,00 DC Non Non posterior 1 e : MEAH ordinateurs, 0 i consommables informatiques …) A Responsabl Acquisition de matériel 150,00 DC Non Non posterior 12/5/2021 e: roulant 0 i MEAH Frais de logistique (mise en œuvre du Plan de A Responsabl Mobilisation des Parties 110,00 DC Non Oui posterior 11/5/2021 e : MEAH Prenantes - PMPP, frais 0 i de fonctionnement) TOTAL Fournitures et 360,00 Travaux 0 B-SELECTION DE CONSULTANTS 1. Seuil de Revue Préalable : Décisions de sélection sujet à la revue préalable de la Banque comme indiqué dans l'Annexe 1 des Directives Sélection et Emploi de consultants : Méthode de sélection Seuil de revue à Commentaires priori 1. Toute méthode de Sélection de >1,000,000 cabinet y compris par Entente directe 2. Sélection de Consultants individuels >300,000 y compris par entente directe 3. 4. 5. 2. Liste restreinte composée entièrement de consultants nationaux : Liste restreinte de consultants pour prestations de services, estimés à moins de $ 100 000 par contrat, peut comporter entièrement des consultants nationaux selon les dispositions du paragraphe 2.7 des directives de sélection de consultants. 3. Tout autre arrangement spécial de Sélection de consultants : non applicable 4. Tâches de consultation avec des méthodes de sélection et calendrier 1 2 3 4 5 6 7 Date prévue Revue de la Coût Méthode de Banque (à Commentair Réf. No. Description des missions estimatif de soumission priori / à es (en $) sélection des posteriori) propositions Composante 1 – Améliorer la production d’eau dans la région du Grand Antananarivo Etude pour finalisation de la sectorisation en DMA (District Responsabl Metering Area) et matériels 200,000 BE (SQC) A posteriori 12/05/2021 e : JIRAMA divers de détection de fuites pour Antananarivo Composante 2. Amélioration des services d’approvisionnement en eau à Antananarivo et dans les villes secondaires Etude pour divers travaux de renforcement des stations de Responsabl pompage d'Antananarivo, y 200,000 BE (SQC) A posteriori 12/05/2021 e : JIRAMA compris audit d'efficacité énergétique des pompages Consultant pour Appel d'Offres réseaux pour Responsabl Antananarivo, y compris 100,000 BE (SQC) A posteriori 11/21/2021 e : JIRAMA raccordements pour Branchement Sociaux Etude institutionnelle pour intervention WASH dans les Responsabl 50,000 CI A posteriori 11/15/2021 écoles et centres de santé e : MEAH (Antananarivo) Inventaire des écoles et centres de santé pour Responsabl 80,000 CI A posteriori 12/15/2021 intervention WASH e : MEAH (Antananarivo) Etudes Environnementales et Responsabl 180,000 BE (SQC) A posteriori 12/5/2021 Sociales pour Antananarivo e : JIRAMA Etude d'alimentation en Eau potable pour cinq villes BE Responsabl secondaires (Antsirananana, 810,000 A priori 12/21/2021 (SFQC) e : JIRAMA Mahajanga, Antsirabe, Fianarantsoa et Manakara) Etudes Environnementales et Responsabl Sociales pour villes 150,000 BE (SQC) A posteriori 12/21/2021 e : JIRAMA secondaires Composante 3. Renforcement des capacités, études stratégiques et gestion de projet Étude sur les compteurs, y compris les Smart meters et 11/30/2021 Responsabl les compteurs en prépayé en 50,000 CI A posteriori e : JIRAMA vue de définir l'évolution du parc compteurs de la JIRAMA Mise en place d'un 11/1/2021 Responsabl mécanisme de gestion des CI A posteriori e : MEAH plaintes (GRM) 20,000 Manuels d’exécution du 11/1/2021 projet (opérationnel, gestion financière, passation de Responsabl 30,000 CI A posteriori marché, système de suivi e : MEAH évaluation, gestion environnementale et sociale) 11/1/2021 Responsabl Elaboration PPSD 20,000 CI A posteriori e : MEAH Spécialiste Eau et 11/1/2021 Responsabl Assainissement en appui au 50,000 CI A posteriori e : MEAH MEAH Spécialiste Eau et 11/1/2021 Responsabl Assainissement en appui à la 50,000 CI A posteriori e : JIRAMA JIRAMA Spécialiste en passation des 11/1/2021 marchés pour appui à la mise Responsabl 50,000 CI A posteriori en œuvre du PPA et de la e : MEAH préparation du Projet 2,040,00 TOTAL CONSULTANCE 0 C- FORMATION Date Revue de la prévue de Coût Méthode Banque (à soumissio DÉSIGNATION estimat de Commentaires priori / à n des if (en $) sélection posteriori) propositio ns Composante 3. Renforcement des capacités, études stratégiques et gestion de projet Acronymes : AOI : Appel d’Offre International AON : Appel d’Offre National DC : Demande de Cotation SED : Sélection par entente directe SFQC : Sélection Fondée sur la Qualité et le Cout SMC : Sélection au « moindre coût » SQC : Sélection fondée sur les qualifications des consultants SCBD : Sélection dans le cadre d’un budget déterminé PROCUREMENT Madagascar : Madagascar National Water Project PLAN General Information Country: Madagascar 2021-10-31 Bank’s Approval Date of the Original Procurement Plan: 2023-06-06 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P174477 GPN Date: Project Name: Madagascar National Water Project Loan / Credit No: / , IDA / 71210, IDA / V3950, IDA / E0400 Ministry of Water, Sanitation and Hygiene Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned MG-MEAH-358907-CW-RFB / Request for Bids - Component 3 : Resilient infr Travaux de construction, réh Open - Internationa Single Stage - One E Works French Civi Pending Imp 2024-03-1 IDA / E0400 astructure and post-cyclone Post Request for Bids 1,826,000.00 0.00 2023-05-31 2023-06-15 2023-08-02 2023-08-18 2023-09-15 abilitation, extension d'adduc l nvelope l Law (French) SP lementation 3 reconstructions tion d'Eau divisés en quatre ( D 4) lots: GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 3 : Resilient infr MG-MEAH-260103-GO-RFB / Single Stage - One E / astructure and post-cyclone Post Request for Bids Open - National 150,000.00 0.00 Canceled 2021-11-10 2021-11-19 2021-12-06 2021-12-17 2022-01-03 2022-02-02 Acquisition des voitures 4x4 nvelope reconstructions MG-MEAH-273470-GO-DIR / Component 3 : Resilient infr Under Imple Acquisition du logiciel Tompr IDA / V3950 astructure and post-cyclone Post Direct Selection Direct 30,000.00 0.00 2022-01-25 2022-02-08 2022-02-01 2022-11-03 2022-02-18 2022-02-28 mentation o reconstructions Component 3 : Resilient infr MG-MEAH-263404-GO-RFQ / Request for Quota Single Stage - One E / astructure and post-cyclone Post Limited 150,000.00 0.00 Canceled 2021-11-30 2022-01-06 2022-01-21 Acquisition de voitures 4X4 tions nvelope reconstructions MG-MEAH-260112-GO-RFQ / Component 3 : Resilient infr Request for Quota Single Stage - One E Acquisition des matériels info / astructure and post-cyclone Post Limited 100,000.00 0.00 Canceled 2021-11-25 2022-01-04 2022-01-19 tions nvelope rmatiques reconstructions MG-MEAH-324306-GO-RFQ / Component 4 : Sector Institu Request for Quota Single Stage - One E Acquisition des matériels et IDA / 71210 Post Open - National 50,000.00 0.00 Signed 2022-11-25 2022-12-02 2022-12-29 2023-01-13 tional Development tions nvelope mobiliers de bureau MG-MEAH-326530-GO-RFQ / Component 4 : Sector Institu Request for Quota Single Stage - One E Under Imple IDA / 71210 Post Open - National 40,000.00 0.00 2022-11-25 2022-12-02 2022-12-29 2023-01-13 Acquisition de matériels infor tional Development tions nvelope mentation matiques MG-MEAH-343278-GO-RFQ / Component 4 : Sector Institu Request for Quota Single Stage - One E Under Imple Acquisition des produits, peti IDA / 71210 Post Open - National 4,000.00 0.00 2023-03-09 2023-06-02 2023-04-24 2023-05-09 tional Development tions nvelope mentation ts matériels et menues dépe nse d'entretien MG-MEAH-343333-GO-RFQ / Component 4 : Sector Institu Request for Quota Single Stage - One E Under Imple IDA / 71210 Post Open - National 20,000.00 0.00 2023-03-18 2023-06-02 2023-04-28 2023-05-18 Acquisition des téléphones p tional Development tions nvelope mentation ortables MG-MEAH-343267-GO-RFQ / Component 4 : Sector Institu Request for Quota Single Stage - One E Under Imple Acquisition de consomptibles IDA / 71210 Post Open - National 16,000.00 0.00 2023-03-07 2023-06-01 2023-04-19 2023-05-04 tional Development tions nvelope mentation informatiques : encre pour i mprimante MG-MEAH-358901-GO-RFB / Acquisition des matériels de Component 3 : Resilient infr Open - Internationa Single Stage - One E Pending Impl pre-positionnement pour les IDA / E0400 astructure and post-cyclone Prior Request for Bids 4,668,000.00 0.00 2023-05-17 2023-05-25 2023-07-12 2023-07-28 2023-08-23 2023-09-22 l nvelope ementation réponses d'urgences WASH d reconstructions ans les zones à risques divisé e en quatre (4) lots. MG-MEAH-327272-GO-RFB / Component 4 : Sector Institu Single Stage - One E Acquisition des véhicules 4x4 IDA / 71210 Post Request for Bids Open - National 250,000.00 0.00 Canceled 2022-12-07 2023-01-10 2022-12-12 2023-01-11 2023-01-12 2023-01-23 2023-02-09 2023-02-24 tional Development nvelope pour le projet PAAEP. MG-MEAH-359158-GO-RFB / Component 4 : Sector Institu Single Stage - One E Under Imple IDA / E0400 Post Request for Bids Open - National 250,000.00 0.00 2023-05-30 2023-06-07 2023-06-03 2023-06-14 2023-07-11 2023-07-30 2023-08-28 2023-09-27 Acquisition de véhicules 4x4 tional Development nvelope mentation du projet MG-MEAH-343253-GO-RFQ / Acquisition de fournitures et Component 4 : Sector Institu Request for Quota Single Stage - One E IDA / 71210 Post Open - National 8,000.00 0.00 Canceled 2023-02-28 2023-04-14 2023-04-11 2023-04-26 articles de bureau (Papier ph tional Development tions nvelope otocopie A4 et A3, autre que papiers) MG-MEAH-362667-GO-RFQ / Component 4 : Sector Institu Request for Quota Single Stage - One E Under Imple Acquisition de fournitures et IDA / E0400 Post Open - National 16,000.00 0.00 2023-06-05 2023-06-09 2023-08-01 2023-08-22 tional Development tions nvelope mentation articles de bureau. NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MG-MEAH-333245-NC-RFB / Etude topographique de tout e la zone d'intervention du b arrage de retenu, vallée à l'a Component 4 : Sector Institu Single Stage - One E Under Imple IDA / 71210 Post Request for Bids Open - National 250,000.00 0.00 2023-01-04 2023-01-17 2023-01-10 2023-01-18 2023-01-31 2023-02-22 2023-02-15 2023-03-03 2023-02-27 2023-06-27 val par Ebelo et Amboasary d tional Development nvelope mentation u fleuve de Mandrare et péri mètres potentielles à irriguer dans l'Androy et Anosy (26,0 00 ha), à l'échelle 1:5,000. CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 1 MG-MEAH-318255-CS-CQS / Recrutement d'une firme pou Component 2: Improving wa r inventorier les services Eau ter supply services in Greate Consultant Qualifi Under Implement IDA / V3950 Post Open - National 50,000.00 0.00 2022-10-03 2022-11-17 2022-10-20 2022-12-13 2022-11-30 2022-12-15 2022-12-28 2023-03-28 , Assainissement et Hygiène r Antananarivo and secondar cation Selection ation dans les formations sanitaire y towns s et les écoles des quatre Dis tricts du Grand Tana. MG-MEAH-318270-CS-CQS / Recrutement d'une firme pou r la revue de la sécurité et la Component 4 : Sector Institu Quality And Cost- Under Implement mise aux normes des barrag IDA / 71210 Post Open - National 400,000.00 0.00 2022-10-17 2022-10-24 2022-11-04 2022-12-13 2022-12-02 2023-03-06 2022-12-22 2023-04-26 2023-01-06 2023-01-31 2023-02-13 2023-08-12 tional Development Based Selection ation es existants de Mantasoa, Va rahina Sud et Manandriana ai nsi que de leurs ouvrages an nexes MG-MEAH-325369-CS-QCBS / Recrutement d'un cabinet e n vue de l'élaboration d’Avan Component 4 : Sector Institu Quality And Cost- Under Implement t-Projet Sommaire (APS) faisa IDA / 71210 Prior Open - National 1,800,000.00 0.00 2022-11-09 2022-11-18 2022-11-10 2022-12-01 2022-12-28 2023-03-03 2023-01-17 2023-05-04 2023-01-30 2023-06-12 2023-02-23 2023-03-09 2023-11-09 tional Development Based Selection ation bilité de l’aménagement pou r un usage multiple dans l’An droy et l’Anosy par le fleuve Mandrare. MG-MEAH-351492-CS-CQS / Recrutement d'un cabinet de Component 4 : Sector Institu Consultant Qualifi recrutement en vue d’appuy IDA / 71210 Post Open - National 20,000.00 0.00 Under Review 2023-05-10 2023-06-19 2023-05-17 2023-06-30 2023-07-14 2023-07-28 2023-09-26 tional Development cation Selection er l’UGP-MEAH et l’UGP-JIRA MA pour le recrutement de s on personnel. INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MG-MEAH-259674-CS-INDV / Component 3 : Resilient infr Individual Consult Recrutement d'un consultant / astructure and post-cyclone Post Limited 20,000.00 0.00 Canceled 2021-11-04 2021-11-15 2021-11-30 2021-12-13 2022-01-13 ant Selection individuel chargé à l'élaborat reconstructions ion du PPSD MG-MEAH-260147-CS-INDV / Component 3 : Resilient infr Individual Consult Recrutement d'un consultant / astructure and post-cyclone Post Limited 50,000.00 0.00 Canceled 2021-11-11 2021-11-16 2021-11-18 2021-11-25 2021-12-06 2022-06-04 ant Selection individuel pour l'appui du mi reconstructions nistère. MG-MEAH-261454-CS-CDS / Component 3 : Resilient infr Under Implement Recrutement d' un Consultan IDA / 71210 astructure and post-cyclone Post Direct Selection Direct 20,000.00 0.00 2021-11-08 2021-11-08 2021-11-15 2021-11-19 2021-12-07 2022-01-06 ation t Individuel pour l'élaboration reconstructions du PPSD. MG-MEAH-261485-CS-INDV / Component 3 : Resilient infr Recrutement d'un consultant Individual Consult / astructure and post-cyclone Post Limited 30,000.00 0.00 Canceled 2021-11-25 2021-11-23 2021-12-02 2021-12-14 2021-12-28 2022-02-11 individuel en charge de l'élab ant Selection reconstructions oration du Manuels d'Exécuti on du Projet. MG-MEAH-272483-CS-INDV / Recrutement d'un Consultant Component 3 : Resilient infr Individual Consult Individuel pour un poste d'un IDA / V3950 astructure and post-cyclone Post Limited 50,000.00 0.00 Canceled 2022-01-24 2022-02-11 2022-02-03 2022-02-18 2022-03-02 2022-10-31 ant Selection Coordonnateur (trice) de la p reconstructions réparation du nouveau projet du MEAH. MG-MEAH-272848-CS-INDV / Recrutement d'un consultant Component 3 : Resilient infr Individual Consult individuel pour Responsable IDA / V3950 astructure and post-cyclone Post Limited 50,000.00 0.00 Signed 2022-01-24 2022-01-19 2022-02-03 2022-02-28 2022-02-18 2022-10-20 2022-03-02 2022-10-31 ant Selection des Passations des Marchés ( reconstructions RPM) de la préparation du no uveau projet du MEAH. MG-MEAH-291491-CS-INDV / Recrutement d'un Consultant Component 4 : Sector Institu Individual Consult Under Implement IDA / V3950 Post Limited 30,000.00 0.00 2022-04-22 2022-05-25 2022-04-29 2022-05-31 2022-05-19 2022-08-17 2022-06-02 2022-07-18 Individuel en vue de l' élabor tional Development ant Selection ation ation du MEP du projet. MG-MEAH-297225-CS-INDV / Recrutement d'un Consultant Component 4 : Sector Institu Individual Consult IDA / V3950 Post Limited 50,000.00 0.00 Signed 2022-06-01 2022-06-03 2022-06-15 2022-09-01 2022-06-30 2022-11-10 2022-07-14 2023-07-14 Individuel Expert en gestion tional Development ant Selection des risques environnementa ux du projet. MG-MEAH-321738-CS-CDS / MISSION D'ELABORATION DU Component 4 : Sector Institu SCHEMA DIRECTEUR D'ALIME IDA / 71210 Prior Direct Selection Direct - National 3,000,000.00 0.00 Signed 2022-10-20 2022-10-25 2022-11-02 2022-11-15 2022-11-24 2024-05-17 tional Development NTATION EN EAU POTABLE D U GRAND ANTANANARIVO MG-MEAH-327258-CS-INDV / Recrutement d'un consultant Component 4 : Sector Institu Individual Consult Under Implement IDA / 71210 Post Open - National 50,000.00 0.00 2022-12-09 2022-11-30 2023-01-16 2023-01-23 2023-02-08 2024-02-08 individuel expert (e) en suivi tional Development ant Selection ation et évaluation du projet PAAE P. MG-MEAH-327271-CS-INDV / Component 4 : Sector Institu Individual Consult Under Implement Recrutement d'un consultant IDA / 71210 Post Open - National 50,000.00 0.00 2022-12-07 2022-12-05 2023-01-18 2023-01-23 2023-02-13 2024-02-13 tional Development ant Selection ation individuel expert(e) WASH du projet PAAEP. MG-MEAH-327197-CS-CDS / Component 4 : Sector Institu Under Implement Études électriques et sondag IDA / 71210 Post Direct Selection Direct - National 95,000.00 0.00 2022-11-30 2022-11-27 2022-12-15 2023-01-05 2023-03-14 tional Development ation es carottées avec LNTPB. MG-MEAH-340183-CS-INDV / Recrutement d'un consultant individuel chargé d'élaborer l e plan d'engagement environ Component 4 : Sector Institu Under Implement nemental et social (PEES)-le IDA / 71210 Post Direct Selection Direct - National 10,000.00 0.00 2023-02-08 2023-02-07 2023-02-20 2023-02-07 2023-03-13 2023-04-12 tional Development ation plan de mobilisation des part ies prenantes (PMPP)-le docu ment de procédures de gesti on de la main d'œuvre (PGM O)-le plan d'action VBG/EAS- HS MG-MEAH-327263-CS-INDV / Component 4 : Sector Institu Individual Consult Recrutement d'un consultant IDA / 71210 Post Open - National 50,000.00 0.00 Canceled 2022-11-24 2022-12-06 2023-01-05 2023-01-12 2023-01-30 2024-01-30 tional Development ant Selection individuel auditeur interne du projet PAAEP. MG-MEAH-327240-CS-INDV / Component 4 : Sector Institu Individual Consult Recrutement d'un Consultant IDA / 71210 Post Open - National 20,000.00 0.00 Canceled 2022-11-30 2022-11-25 2023-01-09 2023-01-16 2023-02-01 2024-02-01 tional Development ant Selection individuel comptable du Proj et PAAEP. Page 2 MG-MEAH-343045-CS-INDV / Component 4 : Sector Institu Individual Consult Under Implement Recrutement d'un consultant IDA / 71210 Post Open - National 50,000.00 0.00 2023-02-20 2023-03-05 2023-04-03 2023-04-12 2023-04-25 2026-04-24 tional Development ant Selection ation individuel au poste d'un Audi teur interne MG-MEAH-343039-CS-INDV / Component 4 : Sector Institu Individual Consult Under Implement Recrutement d'un consultant IDA / 71210 Post Open - National 20,000.00 0.00 2023-02-27 2023-03-05 2023-04-10 2023-04-17 2023-04-27 2026-04-24 tional Development ant Selection ation individuel pour le poste d'un Comptable. MG-MEAH-344554-CS-INDV / Component 4 : Sector Institu Individual Consult Under Implement Recrutement d'un consultant IDA / 71210 Post Open - National 40,000.00 0.00 2023-02-27 2023-03-05 2023-04-12 2023-04-21 2023-05-03 2026-05-04 tional Development ant Selection ation individuel expert(e) en hydra ulique du projet MG-MEAH-304660-CS-INDV / Recrutement d'un consultant Component 4 : Sector Institu Individual Consult IDA / V3950 Post Open - National 50,000.00 0.00 Canceled 2022-07-25 2022-09-15 2022-08-23 2022-08-30 2022-09-08 2024-09-13 individuel pour un poste d'un tional Development ant Selection Coordonnateur du projet PA AEP Madagascar. MG-MEAH-297228-CS-INDV / Recrutement d'un Consultant Component 4 : Sector Institu Individual Consult IDA / V3950 Post 50,000.00 0.00 Canceled 2022-06-01 2022-08-16 2022-06-15 2022-09-01 2022-06-30 2022-07-14 2023-07-14 Individuel Expert en gestion tional Development ant Selection des risques sociaux du projet . MG-MEAH-330357-CS-CDS / Recrutement d'un consultant Component 4 : Sector Institu individuel en vue de l'élabora IDA / 71210 Post Direct Selection Direct - National 10,000.00 0.00 Canceled 2022-12-26 2023-01-31 2023-01-06 2023-02-06 2023-01-26 2023-02-15 tional Development tion de la mise à jour des doc uments initiaux (PPSD). MG-MEAH-272851-CS-INDV / Recrutement d'un consultant Component 3 : Resilient infr Individual Consult individuel pour un Responsab IDA / V3950 astructure and post-cyclone Post Limited 50,000.00 0.00 Canceled 2022-01-24 2022-01-19 2022-02-03 2022-02-14 2022-02-18 2022-03-02 2022-10-31 ant Selection le Administratif et Financier d reconstructions e la préparation du nouveau projet du MEAH. MG-MEAH-362659-CS-CDS / Recrutement d'un Consultant Component 4 : Sector Institu Under Implement IDA / 71210 Post Direct Selection Direct - National 100,000.00 0.00 2023-05-31 2023-06-07 2023-06-09 2023-06-19 2026-06-18 individuel pour le poste d'un tional Development ation Coordonnateur du projet. MG-MEAH-362673-CS-INDV / Recrutement d'un consultant Component 4 : Sector Institu Individual Consult Under Implement IDA / 71210 Post Open - National 40,000.00 0.00 2023-06-16 2023-06-19 2023-08-02 2023-08-11 2023-09-04 2026-09-03 individuel expert(e) en gestio tional Development ant Selection ation n des risques sociaux. MG-MEAH-358889-CS-INDV / Recrutement d'un consultant Component 4 : Sector Institu Individual Consult IDA / 71210 Post Open - National 50,000.00 0.00 Under Review 2023-06-19 2023-06-19 2023-08-10 2023-08-17 2023-09-05 2026-09-04 individuel Responsable Admi tional Development ant Selection nistratif et Financier du Proje t PAAEP -UGP MEAH MG-MEAH-363148-CS-INDV / Recrutement d'un consultant Component 4 : Sector Institu Individual Consult Pending Impleme IDA / 71210 Post Open - National 40,000.00 0.00 2023-06-22 2023-08-24 2023-08-31 2023-09-19 2026-09-18 individuel Assistant(e) du Co tional Development ant Selection ntation ordonnateur du projet . MG-MEAH-366326-CS-INDV / Recrutement d'un Consultant individuel pour l'appui techni Component 4 : Sector Institu Individual Consult Pending Impleme IDA / 71210 Post Open - National 35,000.00 0.00 2023-06-28 2023-08-24 2023-08-31 2023-09-21 2024-01-04 que et rajout de fonctionnalit tional Development ant Selection ntation és de l’application SESAM du ministère de l’Eau, de l’Assa inissement et de l’Hygiène. Page 3 PLAN DE PASSATION DE MARCHÉS Information sur le Projet : Djibouti – Projet pour l’Entrepreneuriat des Jeunes et des Femmes – P165558 Agence d’exécution du Projet : Centre de Leadership et d’Entrepreneuriat Date du plan de passation des marchés : 12 mars 2019 Période couverte par ce plan de passation des marchés : Mars 2019- Décembre 2020 Préambule Conformément au paragraphe 5.9 du “Règlement de Passation des Marchés pour les Emprunteurs sollicitant le Financement de Projets d’Investissement (FPI)” (Juillet 2016) (“Règlement de Passation des Marchés”) le Système électronique de la Banque de suivi systématique des transactions de marchés publics (STEP) sera utilisé pour préparer, valider et actualiser les plans de passation des marchés et effectuer toutes les transactions liées à la passation des marchés du projet. Ce texte ainsi que les tableaux du plan de passation des marchés présents dans STEP constituent le plan de passation des marchés du projet. Les conditions suivantes s'appliquent à toutes les activités de passation de marchés du plan de passation de marchés. Les autres éléments du plan de passation des marchés tels que requis au paragraphe 4.4 du Règlement de passation des marchés sont énoncés dans STEP. Les Dossiers types de passation des marchés publics de la Banque devront être utilisés pour tous les contrats soumis à la concurrence internationale, ainsi que pour tous les autres contrats soumis à cette obligation telle que spécifiée dans les tableaux du plan de passation des marchés de STEP. Procédures nationales de passation des marchés : En accord avec le paragraphe 5.3 du Règlement de passation des marchés, dans le cas où la procédure de passation des marché se fera au niveau national (telle que spécifiée dans les tableaux du plan de passation des marchés inclus dans STEP), les procédures nationales de passation des marchés du pays considéré pourront être utilisées. Si l’Emprunteur utilise ses propres procédures d’appel d’offres national ouvert telles qu’énoncées [La Loi n°53/AN/09/6ème L portant Nouveau Code de s Marchés Publics], ces arrangements sont soumis aux dispositions du paragraphe 5.4 du Règlement de passation des marchés Lorsque l’Emprunteur utilise d’autres procédures que l’appel d’offres national ouvert, ces procédures devront être en accord avec les dispositions du paragraphe 5.5 du Règlement de passation des marchés. Crédit-bail tel que spécifié au paragraphe 5.10 du Règlement de Passation des marchés : Le crédit-bail peut être utilisé pour les contrats indiqués comme tel dans le Plan de passation des marchés. « Sans objet » Achat de biens d’occasion tel que spécifié au paragraphe 5.11 du Règlement de Passation des Marchés est autorisé pour les contrats indiqués comme tel dans le Plan de passation des marchés. « Sans objet » Préférence nationale telle que spécifiée au paragraphe 5.51 du Règlement de Passation des Marchés (Fournitures et Travaux). Fournitures : ne s’applique pas/ Travaux ne s’applique pas/ PROCUREMENT Djibouti : Djibouti Support for Women and Youth Entrepreneurship PLAN General Information Country: Djibouti 2019-03-28 Bank’s Approval Date of the Original Procurement Plan: 2023-06-01 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P165558 GPN Date: Project Name: Djibouti Support for Women and Youth Entrepreneurship Loan / Credit No: IDA / 62590 Center for Leadership and Entrepreneurship Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual DJ-CEL-107261-GO-RFQ / Pro Improving access to services curement of marketing and c , finance, and competitive v Request for Quota Single Stage - One E IDA / 62590 Post Open - National 3,303.00 0.00 Canceled 2019-03-31 2019-05-26 2019-11-22 ommunication tools for the in alue chains for women and y tions nvelope auguration of the Centre. oung entrepreneurs DJ-CEL-77127-GO-RFQ / ach at d'un seul véhicule de servi Building capacity of women Request for Quota Single Stage - One E IDA / 62590 Post Limited 50,000.00 50,000.00 Signed 2019-05-27 2019-10-27 2019-07-01 2020-01-09 2019-07-10 ce, avec chauffeur, sont utilis and young entrepreneurs tions nvelope ation, le plan de maintenanc e et d'amortisation. DJ-CEL-123429-CS-QBS / Acq Improving access to services uisition et mise en place du s , finance, and competitive v Single Stage - One E IDA / 62590 Post Request for Bids Limited 150,000.00 0.00 Canceled 2019-07-31 2019-08-05 2019-09-16 2019-10-16 2019-11-20 2020-05-18 ystème d'information et de g alue chains for women and y nvelope estion pour le FGPCD oung entrepreneurs DJ-CEL-168791-GO-RFQ / Ac Building capacity of women Request for Quota Single Stage - One E hat de deux vehicules de ser IDA / 62590 Post Limited 120,000.00 120,000.00 Signed 2020-06-15 2020-06-08 2020-08-17 2020-09-02 2021-02-13 and young entrepreneurs tions nvelope vices (y compris son plan de maintenance). Improving access to services DJ-CEL-295554-GO-DIR / Acq , finance, and competitive v uisition des cartes à puces bi IDA / 62590 Post Direct Selection Direct 105,000.00 0.00 Signed 2022-05-23 2022-07-27 2022-05-25 2022-07-31 2022-06-02 2022-11-29 alue chains for women and y ométriques oung entrepreneurs NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Improving access to services DJ-CEL-107219-NC-DIR / Ser , finance, and competitive v vices d'hôtellerie et de resta IDA / 62590 Post Direct Selection Direct 52,162.00 52,162.00 Signed 2019-03-24 2020-04-09 2019-03-24 2020-04-09 2019-03-24 2020-10-16 2019-03-26 alue chains for women and y uration oung entrepreneurs Improving access to services DJ-CEL-107258-NC-DIR / Digi , finance, and competitive v tal Panel rental in several ke IDA / 62590 Post Direct Selection Direct 702.81 703.00 Signed 2019-03-25 2018-11-25 2019-03-25 2019-03-25 2020-10-16 2019-03-27 alue chains for women and y y locations of the city. oung entrepreneurs CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual DJ-CEL-106911-CS-INDV / Re crutement d'une firme pour l Building capacity of women Consultant Qualifi IDA / 62590 Post Limited 45,000.00 0.00 Canceled 2019-04-04 2019-04-11 2019-04-18 2019-05-09 2019-07-08 a stratégie globale du centre and young entrepreneurs cation Selection pour les 5 prochaines années . DJ-CEL-115613-CS-LCS / Rec Support for Project Impleme Least Cost Selecti rutement d'un cabinet pour l' IDA / 62590 Post Open - National 5,000.00 13,225.00 Signed 2019-06-30 2020-01-06 2019-07-14 2020-04-05 2019-08-11 2020-06-01 2019-08-25 2020-07-09 2019-09-08 2020-07-12 2019-09-27 2020-07-25 2019-10-06 2020-08-07 2020-04-03 ntation and Monitoring on audit de mi-année. DJ-CEL-123426-CS-LCS / Rec rutement d’une firme pour le Building capacity of women Least Cost Selecti IDA / 62590 Post Open - National 25,000.00 0.00 Canceled 2019-10-01 2019-10-22 2019-12-05 2020-01-02 2020-02-01 2020-03-07 2020-04-11 2020-10-08 s services de graphisme des and young entrepreneurs on documents de formation DJ-CEL-146531-CS-QCBS / L’ opérationnalisation du FGPC Improving access to services D nécessite la mise en place , finance, and competitive v Quality And Cost- Open - Internationa IDA / 62590 Post 150,000.00 158,332.00 Signed 2019-11-25 2019-11-25 2019-11-27 2019-12-11 2019-12-25 2020-04-07 2020-01-22 2020-06-24 2020-01-29 2020-08-19 2020-02-19 2020-10-07 2020-02-27 2021-06-01 2020-08-25 d’un système d’information q alue chains for women and y Based Selection l ui couvrira ses fonctions prin oung entrepreneurs cipales pour assurer son bon fonctionnement. DJ-CEL-162954-CS-CQS / Rec rutement d'un consultant po Building capacity of women Consultant Qualifi IDA / 62590 Post Limited 45,000.00 24,000.00 Signed 2020-03-08 2020-03-15 2020-03-15 2020-05-10 2020-04-14 2020-05-11 2020-05-19 2020-05-21 2020-11-15 ur la stratégie globale du cen and young entrepreneurs cation Selection tre pour le 5 prochaines anné es. DJ-CEL-178352-CS-QCBS / R Improving access to services ecrutement d'une firme pour , finance, and competitive v Quality And Cost- Open - Internationa IDA / 62590 Post 150,000.00 0.00 Canceled 2020-06-15 2020-06-15 2020-07-06 2020-06-22 2020-08-19 2020-09-16 2020-10-16 2020-11-20 2020-12-25 2022-06-18 le développement de l'activit alue chains for women and y Based Selection l é sectorielle sur le Tourisme oung entrepreneurs à Djibouti DJ-CEL-186892-CS-QCBS / R Improving access to services ecrutement d'une firme pour , finance, and competitive v Quality And Cost- Open - Internationa IDA / 62590 Post 330,000.00 0.00 Canceled 2020-08-04 2020-08-03 2020-08-25 2020-08-03 2020-10-08 2020-12-10 2020-11-05 2021-02-18 2020-12-05 2021-04-21 2021-01-09 2021-02-13 2022-02-13 le développement de l'activit alue chains for women and y Based Selection l é sectorielle sur l'économie b oung entrepreneurs leue à Djibouti. Page 1 DJ-CEL-186893-CS-QCBS / R Improving access to services ecrutement d'une firme pour , finance, and competitive v Quality And Cost- Open - Internationa IDA / 62590 Post 330,000.00 330,000.00 Signed 2020-08-06 2020-08-03 2020-08-27 2020-08-03 2020-10-10 2020-11-28 2020-11-07 2021-02-18 2020-12-07 2021-04-22 2021-01-11 2021-05-19 2021-02-15 2021-08-31 2022-02-15 le développement de l'activit alue chains for women and y Based Selection l é sectorielle sur le tourisme oung entrepreneurs à Djibouti. DJ-CEL-255705-CS-CQS / Rec rutement d'une firme pour la Improving access to services conception, le développemen , finance, and competitive v Consultant Qualifi t et la mise en place d'une st IDA / 62590 Post Limited 150,000.00 0.00 Canceled 2021-10-07 2021-10-07 2021-10-21 2021-11-20 2021-12-25 2022-06-23 alue chains for women and y cation Selection ratégie de communication po oung entrepreneurs ur la promotion de l'entrepre neuriat des jeunes et des fe mmes. DJ-CEL-290313-CS-QCBS / R ecrutement d’une firme pour Improving access to services la réalisation d’une étude de , finance, and competitive v Consultant Qualifi Open - Internationa Under Implement IDA / 62590 Post 75,000.00 0.00 2022-04-16 2022-04-18 2022-04-30 2022-05-09 2022-06-09 2022-08-23 2022-06-19 2022-09-08 2022-06-25 2022-09-23 faisabilité pour le développe alue chains for women and y cation Selection l ation ment d’un centre de services oung entrepreneurs partagés en faveur des MPM Es. DJ-CEL-310547-CS-QCBS / R Improving access to services ecrutement d’un Cabinet pou , finance, and competitive v Quality And Cost- Open - Internationa Under Implement IDA / 62590 Post 200,000.00 0.00 2022-08-31 2022-09-15 2022-09-21 2022-11-06 2022-10-15 2023-03-15 2022-11-05 2022-11-15 2022-12-02 2022-12-23 2023-02-21 r la Mise en Place d’un « Star alue chains for women and y Based Selection l ation t-Up Act » oung entrepreneurs DJ-CEL-310540-CS-QCBS / R ecrutement d’un cabinet d’a Support for Project Impleme Least Cost Selecti Under Implement IDA / 62590 Post Open - National 15,000.00 0.00 2022-10-30 2023-01-05 2022-11-20 2023-02-12 2022-12-25 2023-01-15 2023-02-05 2023-02-25 2023-03-08 2024-06-10 udit pour le projet (PAEFJ) po ntation and Monitoring on ation ur les exercices 2022 et 202 3 du projet DJ-CEL-324794-CS-QCBS / R Improving access to services ecrutement d'une firme pour , finance, and competitive v Quality And Cost- Open - Internationa Pending Impleme IDA / 62590 Post 200,000.00 0.00 2022-11-02 2022-11-23 2023-02-06 2023-03-23 2023-04-22 2023-05-27 2023-07-01 2024-05-18 le développement de pipelin alue chains for women and y Based Selection l ntation e de projet prêts à l'investiss oung entrepreneurs ement. DJ-CEL-324836-CS-QCBS / R Improving access to services ecrutement d'un accélérateu , finance, and competitive v Quality And Cost- Open - Internationa Under Implement r intégré pour la définition et IDA / 62590 Prior 700,000.00 0.00 2022-11-15 2023-01-11 2022-12-06 2023-02-07 2023-02-19 2023-04-05 2023-05-05 2023-06-09 2023-07-14 2024-07-13 alue chains for women and y Based Selection l ation l'implémentation d'un progra oung entrepreneurs mme d'accompagnement de s Startups. DJ-CEL-337603-CS-QCBS / R ecrutement d'un cabinet nati Building capacity of women Quality And Cost- Under Implement onal pour la création et la mi IDA / 62590 Post Open - National 100,000.00 0.00 2023-01-21 2023-01-19 2023-02-11 2023-04-30 2023-03-27 2023-04-24 2023-05-24 2023-06-28 2023-08-02 2024-08-01 and young entrepreneurs Based Selection ation se en ligne d'un portail virtue l pour les entrepreneurs DJ-CEL-344520-CS-CQS / Rec Improving access to services rutement d’un Cabinet pour l , finance, and competitive v Consultant Qualifi Under Implement IDA / 62590 Post Limited 27,000.00 0.00 2023-02-21 2023-02-21 2023-03-07 2023-04-06 2023-05-11 2023-11-07 a réalisation d’un diagnostic alue chains for women and y cation Selection ation des activités règlementées. oung entrepreneurs DJ-CEL-357371-CS-CDS / Rec rutement d'un cabinet spécia Building capacity of women Consultant Qualifi lisé pour la recherche et le re IDA / 62590 Post Limited 18,000.00 0.00 Under Review 2023-05-14 2023-05-14 2023-05-24 2023-05-31 2023-06-14 2023-08-13 and young entrepreneurs cation Selection crutement d'un Directeur Ge neral au sein du CLE. DJ-CEL-364028-CS-INDV / Re Improving access to services crutement d'un Cabinet pour , finance, and competitive v Consultant Qualifi Pending Impleme IDA / 62590 Post Limited 15,000.00 0.00 2023-05-31 2023-06-10 2023-06-15 2023-06-20 2023-09-18 l'établissement du bilan d'ou alue chains for women and y cation Selection ntation verture de CLE oung entrepreneurs DJ-CEL-364029-CS-INDV / Re Improving access to services crutement d'un Cabinet pour , finance, and competitive v Consultant Qualifi Under Implement IDA / 62590 Post Limited 25,000.00 0.00 2023-05-31 2023-06-01 2023-06-05 2023-06-10 2023-06-13 2023-09-11 l'évaluation du patrimoine du alue chains for women and y cation Selection ation CLE oung entrepreneurs DJ-CEL-364190-CS-INDV / Re Improving access to services crutement d’un cabinet pour , finance, and competitive v Consultant Qualifi Under Implement IDA / 62590 Post Limited 12,755.00 0.00 2023-05-31 2023-05-15 2023-06-15 2023-06-20 2023-06-28 2023-12-25 l’appui de l’ANPI dans la gest alue chains for women and y cation Selection ation ion du Foncier à vocation éco oung entrepreneurs nomique INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual DJ-CEL-106795-CS-CQS / Rec Improving access to services rutement d'un consultant ex , finance, and competitive v Individual Consult IDA / 62590 Post Open 50,000.00 0.00 Canceled 2019-03-20 2019-04-15 2019-05-08 2019-05-29 2019-07-03 2019-08-12 pert en programme incubatio alue chains for women and y ant Selection n et services connexes oung entrepreneurs DJ-CEL-106901-CS-CDS / Rec Improving access to services rutement d'une firme pour l' , finance, and competitive v IDA / 62590 Prior Direct Selection Direct 365,925.00 365,000.00 Signed 2019-03-21 2020-10-15 2019-03-31 2019-04-14 2019-05-29 2021-04-13 Assistance technique FabLab alue chains for women and y : gestion, formation, accomp oung entrepreneurs agnement etc... DJ-CEL-106921-CS-INDV / Re Improving access to services crutement d'un consultant po , finance, and competitive v ur l'opérationnalisation du Fo IDA / 62590 Post Direct Selection Direct 25,000.00 24,198.00 Signed 2019-03-21 2019-04-15 2019-03-27 2019-04-24 2019-05-27 2019-05-24 alue chains for women and y nds de Garantie Partielle des oung entrepreneurs Crédits de Djibouti (FGPCD) DJ-CEL-106922-CS-INDV / re crutement d'un administrate Support for Project Impleme IDA / 62590 Post Direct Selection Direct 9,000.00 17,820.00 Signed 2019-03-21 2019-04-25 2019-03-31 2019-04-28 2019-04-09 2019-05-01 2019-10-06 ur réseau à temps partiel po ntation and Monitoring ur 6 premiers mois. DJ-CEL-106925-CS-INDV / Re Support for Project Impleme Individual Consult crutement consultant gestion IDA / 62590 Post Open 36,000.00 42,000.00 Signed 2019-03-24 2019-04-15 2019-04-17 2019-04-28 2019-04-22 2019-05-20 2019-05-02 2019-05-21 2020-05-01 ntation and Monitoring ant Selection financière pour la mise en oe uvre du projet. DJ-CEL-107117-CS-INDV / Re crutement d'un consultant po Support for Project Impleme Individual Consult IDA / 62590 Post Direct 36,000.00 42,000.00 Signed 2019-03-22 2019-04-15 2019-04-01 2019-04-29 2019-04-06 2019-05-02 2019-04-16 2019-05-01 2020-04-15 ur l'assistance technique aux ntation and Monitoring ant Selection opérations du CLE. Page 2 DJ-CEL-107133-CS-INDV / Re crutement consultant métho dologie et programme conco Building capacity of women Individual Consult urs business plan IDA / 62590 Post Limited 25,000.00 0.00 Canceled 2019-03-27 2019-09-01 2019-04-01 2019-04-22 2019-05-27 2019-06-26 and young entrepreneurs ant Selection et la méthode d'évaluation b asés sur les bonnes pratique s internationales. DJ-CEL-109474-CS-INDV / Ap Support for Project Impleme Individual Consult pui technique pour la passati IDA / 62590 Post Limited 3,000.00 0.00 Canceled 2019-04-08 2019-04-13 2019-05-04 2019-06-08 2019-10-06 ntation and Monitoring ant Selection on des marchés. DJ-CEL-107126-CS-INDV / Re crutement d'un consultant po Building capacity of women Individual Consult IDA / 62590 Post Limited 50,000.00 79,096.00 Signed 2019-07-17 2019-07-18 2019-07-22 2020-04-09 2019-08-12 2020-05-05 2019-09-16 2019-10-06 2019-11-15 ur l'élaboration du curricula d and young entrepreneurs ant Selection e formation de niveau 1 et ni veau 2. DJ-CEL-126431-CS-INDV / Re Improving access to services crutement d'un Chargé de pr , finance, and competitive v Individual Consult IDA / 62590 Post Limited 13,800.00 0.00 Canceled 2019-08-18 2019-09-15 2019-09-10 2019-09-15 2019-10-01 2020-09-30 ojets pour les services conne alue chains for women and y ant Selection xes de l'incubateur. oung entrepreneurs DJ-CEL-126350-CS-INDV / Re Improving access to services crutement d'un chargé de pr , finance, and competitive v Individual Consult ojet pour les services connex IDA / 62590 Post Direct 27,600.00 27,600.00 Signed 2019-08-09 2019-08-28 2019-08-19 2019-08-28 2019-08-24 2019-08-28 2019-09-08 2019-09-02 2020-09-07 alue chains for women and y ant Selection es de l'incubateur ( comptabi oung entrepreneurs lité, RH, finance, juridique.) DJ-CEL-141067-CS-CDS / Rec rutement d'un expert pour l'a Support for Project Impleme IDA / 62590 Post Direct Selection Direct 20,964.00 20,964.70 Signed 2019-10-17 2019-10-20 2019-10-19 2019-10-25 2019-11-01 2019-11-08 2020-04-29 ssistance technique pour la t ntation and Monitoring echnologie des informations I TC. DJ-CEL-144113-CS-CDS / Rec rutement d’un Consultant : E xpert en « Public Relation St rategist » dans le cadre de la Building capacity of women Semaine de l’Entrepreneuriat IDA / 62590 Post Direct Selection Direct 8,000.00 8,000.00 Signed 2019-11-05 2020-04-05 2019-11-09 2020-04-09 2019-11-24 2019-11-23 2019-12-01 and young entrepreneurs de l'année 2019 organisé par le Centre de Leadership et d e l’Entrepreneuriat (CLE) A Djibouti, la Semaine de l’en trepreneuriat 2019 DJ-CEL-146912-CS-INDV / L’o bjectif de la formation pour l aquelle le CLE souhaite recru Improving access to services ter des formateurs / formatri , finance, and competitive v Individual Consult ces est de renforcer les capa IDA / 62590 Post Limited 2,000.00 2,000.00 Signed 2019-11-24 2020-04-05 2019-11-29 2020-04-10 2019-12-04 2020-04-30 2019-12-21 2019-12-17 2019-12-31 alue chains for women and y ant Selection cités entrepreneuriales des a oung entrepreneurs pprenants afin de leur perme ttre de mettre en œuvre effic acement le plan de développ ement de leurs projets DJ-CEL-146913-CS-INDV / L’o bjectif de la formation pour l aquelle le CLE souhaite recru Improving access to services ter des formateurs / formatri , finance, and competitive v Individual Consult ces est de renforcer les capa IDA / 62590 Post Limited 2,000.00 2,000.00 Signed 2019-11-24 2020-04-05 2019-11-29 2020-04-10 2019-12-04 2020-04-30 2019-12-21 2019-12-18 2019-12-31 alue chains for women and y ant Selection cités entrepreneuriales des a oung entrepreneurs pprenants afin de leur perme ttre de mettre en œuvre effic acement le plan de développ ement de leurs projets DJ-CEL-146914-CS-INDV / L’o bjectif de la formation pour l aquelle le CLE souhaite recru Improving access to services ter des formateurs / formatri , finance, and competitive v Individual Consult ces est de renforcer les capa IDA / 62590 Post Limited 2,000.00 2,000.00 Signed 2019-11-24 2020-04-05 2019-11-29 2020-04-10 2019-12-04 2020-04-30 2019-12-21 2019-12-18 2019-12-31 alue chains for women and y ant Selection cités entrepreneuriales des a oung entrepreneurs pprenants afin de leur perme ttre de mettre en œuvre effic acement le plan de développ ement de leurs projets DJ-CEL-154165-CS-CDS / Rec Improving access to services rutement d’un Consultant po , finance, and competitive v ur l’élaboration de l’activité s IDA / 62590 Post Direct Selection Direct 25,000.00 25,000.00 Signed 2020-01-18 2020-01-18 2020-01-28 2020-04-15 2020-04-02 2020-01-22 2020-09-29 alue chains for women and y ectorielle sur l’économie bleu oung entrepreneurs e et le secteur halieutique. DJ-CEL-154175-CS-CDS / Rec Improving access to services rutement d’un Consultant po , finance, and competitive v IDA / 62590 Post Direct Selection Direct 25,000.00 25,000.00 Signed 2020-01-17 2020-01-17 2020-01-27 2020-01-16 2020-04-01 2020-01-23 2020-09-28 ur l’élaboration de l’activité s alue chains for women and y ectorielle sur le tourisme oung entrepreneurs DJ-CEL-165243-CS-INDV / Re Building capacity of women Individual Consult crutement d'un chargé pour l IDA / 62590 Post Limited 16,800.00 0.00 Canceled 2020-04-12 2020-04-17 2020-04-22 2020-05-02 2021-05-02 and young entrepreneurs ant Selection es projets de formations DJ-CEL-165315-CS-INDV / Re crutement d'un support en TI Building capacity of women Individual Consult IDA / 62590 Post Direct 14,800.00 14,800.00 Signed 2020-04-02 2020-04-02 2020-04-14 2020-04-27 2020-04-21 2020-04-29 2020-05-01 2020-05-04 2021-05-01 C (Technologie de l'Informati and young entrepreneurs ant Selection on & Communication). Improving access to services DJ-CEL-165326-CS-INDV / Re , finance, and competitive v Individual Consult crutement d'un chargé de pr IDA / 62590 Post Direct 18,200.00 18,120.00 Signed 2020-04-02 2020-04-02 2020-04-12 2020-04-27 2020-04-19 2020-04-29 2020-05-01 2020-05-04 2021-05-01 alue chains for women and y ant Selection ojet 2 oung entrepreneurs Improving access to services DJ-CEL-165328-CS-INDV / Re , finance, and competitive v Individual Consult crutement d'un chargé de pr IDA / 62590 Post Direct 16,000.00 3,977.50 Terminated 2020-04-02 2020-04-02 2020-04-12 2020-04-26 2020-04-19 2020-05-01 2020-05-01 2020-05-04 2021-05-01 alue chains for women and y ant Selection ojet 3 oung entrepreneurs DJ-CEL-165329-CS-INDV / Re Building capacity of women Individual Consult crutement d'un appui techni IDA / 62590 Post Limited 12,000.00 0.00 Canceled 2020-04-05 2020-04-05 2020-04-12 2020-04-19 2020-05-01 2021-05-01 and young entrepreneurs ant Selection que en Communication Improving access to services DJ-CEL-165332-CS-INDV / Re , finance, and competitive v Individual Consult crutement d'un appui techni IDA / 62590 Post Limited 14,200.00 0.00 Canceled 2020-04-09 2020-04-16 2020-04-30 2020-05-21 2021-05-21 alue chains for women and y ant Selection que en graphisme. oung entrepreneurs DJ-CEL-165333-CS-INDV / Re crutement d'une assistante d Support for Project Impleme Individual Consult e Direction pour l'équipe proj IDA / 62590 Post Limited 14,200.00 0.00 Canceled 2020-04-02 2020-04-02 2020-04-09 2020-04-16 2020-05-01 2021-05-01 ntation and Monitoring ant Selection et (Projet d'Appui à l'Entrepre neuriat des Femmes et des J eunes). Page 3 DJ-CEL-165334-CS-INDV / Re Improving access to services crutement d'un consultant po , finance, and competitive v Individual Consult ur la réalisation des ateliers IDA / 62590 Post Direct 15,200.00 17,200.00 Signed 2020-03-26 2020-04-02 2020-04-05 2020-06-17 2020-04-10 2020-06-23 2020-04-20 2020-07-02 2020-09-17 alue chains for women and y ant Selection de formation et d'accompagn oung entrepreneurs ement pour les incubés. DJ-CEL-168784-CS-CDS / Rec rutement consultant gestion Support for Project Impleme IDA / 62590 Post Direct Selection Direct 100,000.00 100,000.00 Signed 2020-05-04 2020-05-05 2020-05-16 2020-05-05 2020-06-01 2020-05-28 2022-06-01 financière pour la mise en ntation and Monitoring oeuvre du projet. DJ-CEL-168787-CS-CDS / Rec rutement d'un consultant po Support for Project Impleme IDA / 62590 Post Direct Selection Direct 100,000.00 100,000.00 Signed 2020-04-20 2020-04-25 2020-04-26 2020-04-27 2020-05-03 2020-05-04 2022-05-03 ur l'assistance technique aux ntation and Monitoring opérations du CLE. DJ-CEL-178347-CS-INDV / Re Improving access to services crutement d'un consultant ju , finance, and competitive v Individual Consult IDA / 62590 Post Limited 25,000.00 24,000.00 Signed 2020-06-30 2020-06-30 2020-07-05 2020-06-30 2020-07-26 2020-07-21 2020-08-30 2020-07-21 2020-10-29 riste pour un appui technique alue chains for women and y ant Selection auprès du CLE. oung entrepreneurs DJ-CEL-178356-CS-INDV / Re Improving access to services crutement d'un consultant po , finance, and competitive v Individual Consult IDA / 62590 Post Limited 50,000.00 0.00 Canceled 2020-06-30 2020-07-05 2020-07-26 2020-08-30 2021-02-26 ur l'élaboration d'une cartagr alue chains for women and y ant Selection aphie du secteur privé de Dji oung entrepreneurs bouti. DJ-CEL-178358-CS-INDV / Re Improving access to services crutement d'un consultant po , finance, and competitive v Individual Consult ur l'élaboration d'une stratég IDA / 62590 Post Limited 50,000.00 0.00 Canceled 2020-06-30 2020-10-14 2020-07-05 2020-07-26 2020-08-30 2021-02-26 alue chains for women and y ant Selection ie de développement de l'éco oung entrepreneurs système entrepreneurial de Djibouti. DJ-CEL-181185-CS-INDV / Re Improving access to services crutement d'un consultant lo , finance, and competitive v Individual Consult cal pour l’accompagnement IDA / 62590 Post Limited 42,360.00 42,360.00 Signed 2020-06-30 2020-06-30 2020-07-14 2020-07-16 2020-07-21 2020-07-23 2020-07-31 2020-08-02 2021-07-31 alue chains for women and y ant Selection et le suivi de la mise en oeuv oung entrepreneurs re des activités sectorielles. DJ-CEL-183409-CS-INDV / Re crutement d'un consultant po Improving access to services ur la mise en place de l'activi , finance, and competitive v Individual Consult IDA / 62590 Post Limited 25,000.00 0.00 Canceled 2020-07-13 2020-10-07 2020-07-18 2020-08-08 2020-09-12 2020-12-11 té finance islamique au sein alue chains for women and y ant Selection du Fonds de Garantie Partiell oung entrepreneurs e des Crédits de Djibouti (FG PCD). DJ-CEL-186928-CS-CDS / Rec rutement d'un consultant po Improving access to services ur l'appui de l'évaluation des , finance, and competitive v IDA / 62590 Post Direct Selection Direct 7,000.00 7,000.00 Signed 2020-08-15 2020-08-25 2020-08-25 2020-09-03 2020-09-13 2020-09-23 2021-01-11 propositions reçues dans le c alue chains for women and y adre du développement de l' oung entrepreneurs activité sectorielle sur le tour sime à Djibouti. DJ-CEL-190182-CS-CDS / Rec Improving access to services rutement d'un chargé de proj , finance, and competitive v IDA / 62590 Post Direct Selection Direct 28,000.00 28,000.00 Signed 2020-08-27 2020-09-01 2020-09-02 2020-09-03 2020-09-07 2020-09-08 2021-09-07 et 1 pour les services connex alue chains for women and y es de l'incubateur (renouvell oung entrepreneurs ement ) Improving access to services DJ-CEL-198420-CS-CDS / Rec , finance, and competitive v rutement d'un chargé de proj IDA / 62590 Post Direct Selection Direct 14,200.00 14,000.00 Signed 2020-10-11 2020-10-11 2020-10-15 2020-10-12 2020-10-21 2020-10-16 2021-10-21 alue chains for women and y et i-LAB (renouvellement) oung entrepreneurs DJ-CEL-198531-CS-CDS / Rec Improving access to services rutement d'un consultant ex , finance, and competitive v IDA / 62590 Post Direct Selection Direct 18,500.00 16,068.52 Signed 2019-04-15 2019-04-15 2019-04-25 2019-10-20 2019-06-29 2020-01-08 2021-04-09 pert en programme incubatio alue chains for women and y n et services et services conn oung entrepreneurs exes. DJ-CEL-109469-CS-INDV / Re Building capacity of women Individual Consult crutement d'un consultant en IDA / 62590 Post Limited 28,000.00 28,000.00 Signed 2020-10-08 2020-10-29 2020-10-13 2021-10-05 2020-11-03 2021-11-01 2020-12-08 2021-11-02 2021-01-07 and young entrepreneurs ant Selection communication. DJ-CEL-203690-CS-CDS / Rec Improving access to services rutement d'un formateur pou , finance, and competitive v IDA / 62590 Post Direct Selection Direct 2,000.00 2,000.00 Signed 2020-11-10 2020-11-10 2020-11-14 2020-11-11 2020-11-20 2020-11-14 2021-05-19 r la formation de l'entreprene alue chains for women and y uriat de niveau 2 (Bootcamp) oung entrepreneurs Improving access to services DJ-CEL-224664-CS-INDV / Re , finance, and competitive v Individual Consult crutement d'un chargé de pr IDA / 62590 Post Direct 15,000.00 15,000.00 Signed 2021-03-15 2021-03-15 2021-03-21 2021-03-16 2021-03-24 2021-03-17 2021-03-31 2021-03-19 2022-03-31 alue chains for women and y ant Selection ojet #3 oung entrepreneurs DJ-CEL-224665-CS-CDS / Rec Improving access to services rutement d'une firme pour la , finance, and competitive v IDA / 62590 Post Direct Selection Direct 150,000.00 155,000.00 Signed 2021-03-17 2021-03-15 2021-03-29 2021-07-14 2021-04-15 2021-10-02 2021-10-12 digitalisation et la mise à jour alue chains for women and y du système SAF. oung entrepreneurs DJ-CEL-231322-CS-INDV / Re Improving access to services crutement d'un consultant po , finance, and competitive v Individual Consult ur la réalisation d'ateliers de IDA / 62590 Post Direct 10,000.00 10,000.00 Signed 2021-04-26 2021-04-26 2021-05-04 2021-05-04 2021-05-07 2021-05-07 2021-05-13 2021-05-14 2022-03-09 alue chains for women and y ant Selection formation et d'accompagnem oung entrepreneurs ent pour les incubés (Renouv ellement). Improving access to services DJ-CEL-231324-CS-INDV / Re , finance, and competitive v Individual Consult crutement d'un chargé de pr IDA / 62590 Post Direct 36,400.00 36,400.00 Signed 2021-04-26 2021-04-26 2021-05-02 2021-05-02 2021-05-05 2021-05-05 2021-05-11 2021-05-12 2023-05-11 alue chains for women and y ant Selection ojet #2 (Renouvellement) oung entrepreneurs DJ-CEL-231462-CS-INDV / Re Building capacity of women Individual Consult crutement d'un support TIC ( IDA / 62590 Post Direct 33,600.00 33,600.00 Signed 2021-04-28 2021-04-28 2021-05-06 2021-05-06 2021-05-09 2021-05-09 2021-05-15 2021-05-16 2023-05-15 and young entrepreneurs ant Selection renouvellement) DJ-CEL-243012-CS-INDV / Re crutement d’un(e) consultant Support for Project Impleme Individual Consult (e) individuel(le) pour la réali IDA / 62590 Post Limited 21,000.00 21,000.00 Signed 2021-07-11 2021-07-11 2021-07-14 2021-07-12 2021-07-17 2021-07-20 2021-07-23 2021-07-24 2021-10-01 ntation and Monitoring ant Selection sation d’une surveillance et d ’une évaluation par une tierc e partie du PAEFJ et du CLE. DJ-CEL-245412-CS-CDS / Rec rutement d'un(e) consultant( Building capacity of women IDA / 62590 Post Direct Selection Direct 13,350.00 13,350.00 Signed 2021-07-26 2021-07-26 2021-07-30 2021-07-30 2021-08-05 2021-08-02 2022-03-15 e) pour la production de cont and young entrepreneurs enus de communication instit utionnelles du CLE. Page 4 DJ-CEL-247332-CS-INDV / Re Improving access to services nouvellement du recrutemen , finance, and competitive v Individual Consult t du consultant local pour l'ac IDA / 62590 Post Direct 85,000.00 85,000.00 Signed 2021-08-09 2021-08-09 2021-08-11 2021-08-11 2021-08-12 2021-08-12 2021-08-15 2021-08-16 2023-08-15 alue chains for women and y ant Selection compagnement et le suivi de oung entrepreneurs la mise en œuvre sectorielles . DJ-CEL-247333-CS-INDV / Re Improving access to services crutement d’un consultant ex , finance, and competitive v Individual Consult pert en idéation et accompag IDA / 62590 Post Limited 20,000.00 20,000.00 Signed 2021-08-12 2021-08-12 2021-08-17 2021-08-17 2021-08-22 2021-08-22 2021-09-01 2021-09-02 2022-06-28 alue chains for women and y ant Selection nement entrepreneurial, char oung entrepreneurs gé de la promotion de la créa tivité et de l’innovation. DJ-CEL-254455-CS-INDV / Re crutement d'une chargé de p Improving access to services rojet senior en charge des se , finance, and competitive v Individual Consult IDA / 62590 Post Direct 63,850.00 63,850.00 Signed 2021-09-23 2021-09-23 2021-09-25 2021-09-25 2021-09-26 2021-09-26 2021-09-28 2021-09-30 2023-09-28 rvices connexes de l'incubati alue chains for women and y ant Selection on et accélération (renouvell oung entrepreneurs ement du contrat+upgrade). DJ-CEL-254452-CS-CDS / Rec rutement d'une firme pour la Improving access to services conception, le développemen , finance, and competitive v IDA / 62590 Post Direct Selection Direct 150,000.00 0.00 Canceled 2021-09-30 2021-10-10 2021-10-25 2022-05-13 t et la mise en place d'une st alue chains for women and y ratégie de communication po oung entrepreneurs ur la promotion de l'entrepre neuriat des jeunes DJ-CEL-254754-CS-CDS / Rec Improving access to services rutement en gré à gré du Ca , finance, and competitive v binet Odyssée pour l'audit P IDA / 62590 Post Direct Selection Direct 9,000.00 9,000.00 Signed 2021-09-30 2021-10-05 2021-10-10 2021-10-18 2021-12-14 2021-11-12 2022-06-12 alue chains for women and y GDSP sur la période d'exten oung entrepreneurs sion supplémentaire du 1er s emestre 2021. DJ-CEL-255710-CS-INDV / Re Improving access to services crutement d’un(e) consultant , finance, and competitive v Individual Consult (e) pour la création, producti IDA / 62590 Post Limited 16,000.00 16,000.00 Signed 2021-10-07 2021-11-13 2021-10-14 2021-12-05 2021-10-21 2021-12-21 2021-10-31 2021-12-24 2022-10-31 alue chains for women and y ant Selection on et l’animation d’une Webr oung entrepreneurs adio pour la promotion de l’e ntrepreneuriat DJ-CEL-257895-CS-CDS / Rec rutement d'un chargé de proj Improving access to services et en charge de la supervisio , finance, and competitive v IDA / 62590 Post Direct Selection Direct 37,600.00 37,600.00 Signed 2021-10-13 2021-10-13 2021-10-16 2021-10-16 2021-10-19 2021-10-20 2023-10-19 n des activités et de l'accom alue chains for women and y pagnement des porteurs de oung entrepreneurs projets à l'innovation center ( iLAB) (renouvellement). DJ-CEL-273150-CS-INDV / Re Improving access to services crutement d'un(e) chargé(e) , finance, and competitive v Individual Consult IDA / 62590 Post Direct 12,020.00 12,020.00 Signed 2022-01-16 2021-12-06 2022-01-20 2022-01-20 2022-01-22 2022-01-22 2022-01-26 2022-01-27 2022-01-28 de projets pour l'accompagn alue chains for women and y ant Selection ement des incubés oung entrepreneurs DJ-CEL-273151-CS-CDS / Rec Improving access to services rutement d'un(e) chargé(e) d , finance, and competitive v e projets pour l'accompagne IDA / 62590 Post Direct Selection Direct 9,015.00 9,015.00 Signed 2022-01-16 2022-01-16 2022-01-20 2022-01-20 2022-01-26 2022-01-27 2022-01-28 alue chains for women and y ment des porteurs de projets oung entrepreneurs à l'Innovation Center (i-Lab) ( N#1) DJ-CEL-273153-CS-CDS / Rec Improving access to services rutement d'un(e) chargé(e) d , finance, and competitive v e projets pour l'accompagne IDA / 62590 Post Direct Selection Direct 9,015.00 9,015.00 Signed 2022-01-16 2021-12-15 2022-01-20 2022-01-20 2022-01-26 2022-01-27 2022-01-28 alue chains for women and y ment des porteurs de projets oung entrepreneurs à l'innovation (N#2). DJ-CEL-291493-CS-CDS / Rec Improving access to services rutement d'un consultant po , finance, and competitive v IDA / 62590 Post Direct Selection Direct 83,350.00 83,350.00 Signed 2022-04-25 2022-05-15 2022-04-29 2022-05-15 2022-05-04 2022-05-18 2024-01-04 ur l'assistance technique aux alue chains for women and y opérations du CLE (Renouvell oung entrepreneurs ement) DJ-CEL-292844-CS-CDS / Rec rutement d'un consultant ges Support for Project Impleme IDA / 62590 Post Direct Selection Direct 79,182.50 79,182.50 Signed 2022-05-10 2022-05-15 2022-05-14 2022-05-15 2022-05-22 2022-05-19 2024-01-03 tion financière pour la mise e ntation and Monitoring n œuvre du projet (Renouvellement) DJ-CEL-302212-CS-CDS / Rec Improving access to services rutement d'un(e) chargé(e) d , finance, and competitive v e projets pour l'accompagne IDA / 62590 Post Direct Selection Direct 23,000.00 0.00 Signed 2022-06-30 2022-06-01 2022-07-04 2022-08-03 2022-07-10 2024-01-01 alue chains for women and y ment des incubés / suivi bud oung entrepreneurs gétaire de l'écosystème DJ-CEL-302215-CS-CDS / Rec Improving access to services rutement d'un(e) chargé(e) d , finance, and competitive v IDA / 62590 Post Direct Selection Direct 35,000.00 0.00 Signed 2022-06-30 2022-06-01 2022-07-04 2022-08-03 2022-07-10 2023-12-31 e projets pour l'accompagne alue chains for women and y ment des incubés / S&E du pr oung entrepreneurs ogramme FORJE DJ-CEL-310515-CS-INDV / Re Building capacity of women crutement d'une chargé de c IDA / 62590 Post Direct Selection Direct - National 22,000.00 0.00 Canceled 2022-08-22 2022-05-06 2022-08-28 2022-09-06 2023-12-31 and young entrepreneurs ommunication affectée à l'éq uipe projet DJ-CEL-310527-CS-CDS / Rec rutement d'une assistante à l Support for Project Impleme IDA / 62590 Post Direct Selection Direct - National 26,300.00 0.00 Signed 2022-08-22 2022-05-06 2022-08-28 2022-08-28 2022-09-06 2023-12-31 a gestion financière affectée ntation and Monitoring à l'équipe projet DJ-CEL-310532-CS-CDS / Rec rutement d'une assistante à l Building capacity of women IDA / 62590 Post Direct Selection Direct - National 26,000.00 0.00 Canceled 2022-08-22 2022-07-06 2022-08-28 2022-09-06 2023-12-31 a gestion administrative et a and young entrepreneurs ux achats affectée à l'équipe projet DJ-CEL-310535-CS-INDV / Re crutement d’un Consultant In Building capacity of women Individual Consult IDA / 62590 Post Limited 25,000.00 0.00 Signed 2022-08-25 2022-08-14 2022-09-01 2022-08-28 2022-09-08 2022-10-27 2022-09-22 2022-11-21 dividuel pour l’Étude d’impac and young entrepreneurs ant Selection t du cycle 1 du programme F ORJE DJ-CEL-320056-CS-CDS / Rec Improving access to services rutement d'un chargé de proj , finance, and competitive v Individual Consult IDA / 62590 Post Limited 17,500.00 0.00 Under Review 2022-10-21 2022-10-21 2022-10-26 2022-11-09 2022-11-23 2023-05-22 et senior en charge des servi alue chains for women and y ant Selection ces connexes de l'incubation oung entrepreneurs et accélération. DJ-CEL-324786-CS-CDS / Rec Improving access to services rutement d'un chargé de proj , finance, and competitive v IDA / 62590 Post Direct Selection Direct - National 24,000.00 0.00 Canceled 2022-11-02 2022-11-12 2022-12-03 2023-12-03 et en communication (renouv alue chains for women and y ellement) oung entrepreneurs DJ-CEL-328899-CS-INDV / Re Building capacity of women Individual Consult crutement d'un consultant in IDA / 62590 Post Limited 25,000.00 0.00 Signed 2022-11-30 2022-12-01 2022-12-05 2022-12-05 2022-12-26 2022-12-07 2023-01-30 2023-07-29 and young entrepreneurs ant Selection dividuel pour l'appui à la for malisation Page 5 DJ-CEL-328981-CS-INDV / Re crutement d’un(e) consultant Building capacity of women Individual Consult Under Implement IDA / 62590 Post Limited 27,500.00 0.00 2022-12-04 2022-12-01 2022-12-09 2022-12-30 2023-02-03 2023-08-02 (e) pour la production de con and young entrepreneurs ant Selection ation tenus de communication insti tutionnelles du CLE. DJ-CEL-328984-CS-INDV / Re Improving access to services crutement d'un(e) chargé(e) , finance, and competitive v Individual Consult IDA / 62590 Post Limited 13,000.00 0.00 Signed 2022-12-01 2022-12-01 2022-12-08 2022-12-03 2022-12-15 2022-11-07 2023-01-01 2023-12-31 de projets junior pour l'acco alue chains for women and y ant Selection mpagnement des incubés oung entrepreneurs DJ-CEL-332593-CS-INDV / Re Improving access to services crutement d'un(e) consultant , finance, and competitive v Individual Consult Under Implement IDA / 62590 Post Limited 27,000.00 0.00 2022-12-19 2022-12-20 2022-12-24 2022-12-26 2023-01-14 2023-02-18 2023-04-19 (e) pour l'élaboration d'un m alue chains for women and y ant Selection ation anuel de procédures de proje oung entrepreneurs ts DJ-CEL-360961-CS-INDV / Re Improving access to services crutement d'un chargé de pr , finance, and competitive v Individual Consult Under Implement ojet senior en charge des ser IDA / 62590 Post Direct - National 27,939.91 0.00 2023-05-10 2023-05-07 2023-05-20 2023-06-10 2023-07-15 2023-12-31 alue chains for women and y ant Selection ation vices connexes de l'incubatio oung entrepreneurs n et de l'accélération (renouv ellement) DJ-CEL-360967-CS-INDV / Re crutement d'un consultant en Building capacity of women Individual Consult Under Implement IDA / 62590 Post Direct - National 13,440.00 0.00 2023-05-10 2023-05-07 2023-05-20 2023-06-10 2023-07-15 2023-12-31 administration des réseaux e and young entrepreneurs ant Selection ation t systèmes (renouvellement) DJ-CEL-360970-CS-INDV / Re Improving access to services crutement d'une chargée de , finance, and competitive v Individual Consult Under Implement IDA / 62590 Post Direct - National 15,166.64 0.00 2023-05-10 2023-05-07 2023-05-20 2023-06-10 2023-07-15 2023-12-31 projet pour l'accompagneme alue chains for women and y ant Selection ation nt des incubés et écosystèm oung entrepreneurs e (renouvellement) DJ-CEL-360973-CS-INDV / Re Improving access to services crutement d'un chargé de pr , finance, and competitive v Individual Consult Under Implement IDA / 62590 Post Direct - National 9,015.00 0.00 2023-05-10 2023-05-07 2023-05-20 2023-06-10 2023-07-15 2023-12-31 ojet pour l'accompagnement alue chains for women and y ant Selection ation des incubés et S&E oung entrepreneurs DJ-CEL-360981-CS-INDV / Re Building capacity of women Individual Consult Under Implement IDA / 62590 Post Direct - National 10,016.00 0.00 2023-05-10 2023-05-07 2023-05-20 2023-06-10 2023-07-15 2023-12-31 crutement d'une assistante a and young entrepreneurs ant Selection ation ux achats Page 6 PROCUREMENT PLAN (Textual Part) Project information: Republic of Congo Education Sector Support Project P152910 Project Implementation agency: [insert legal name] Date of the Procurement Plan: [insert date] Period covered by this Procurement Plan: [insert from – to period] Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in [insert appropriate references to the national procurement legislation], such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. List only the applicable conditions required to ensure consistency with paragraph 5.4 of the Procurement Regulations. If no conditions apply, delete the phrase “and the following conditions”. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. Otherwise state “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables Otherwise state “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Specify for each Goods: [is not applicable/is applicable for those contracts identified in the Procurement Plan tables]; Works: [is not applicable/is applicable for those contracts identified in the Procurement Plan tables] Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations is Applicable. [Include this sentence only if the Bank has formally agreed to provide the Borrower with HEIS. Otherwise delete] Other Relevant Procurement Information. Provide any other relevant procurement information such as procedures for CDD components, Procurement in Situations of Urgent Need of Assistance or Capacity Constraints etc. PROCUREMENT Congo, Republic of : Congo - Education Sector Support Project PLAN General Information Country: Congo, Republic of 2017-09-26 Bank’s Approval Date of the Original Procurement Plan: 2023-06-01 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P152910 GPN Date: Project Name: Congo - Education Sector Support Project Loan / Credit No: IDA / V0020, IDA / 58060 Education Sector Support Project Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PRAASED-001-F-CF / matérie l informatique et mobilier- a Request for Quota Single Stage - One E IDA / V0020 Unallocated Post Limited 80,000.00 0.00 Canceled 2017-03-31 2017-05-26 2017-11-22 cquisition équipement inform tions nvelope atique et mobilier UCP PRAASED-014-F-CF / mobilie Request for Quota Single Stage - One E IDA / V0020 Unallocated Post Limited 80,000.00 0.00 Canceled 2017-04-04 2017-05-30 2017-11-26 r de bureau UCP tions nvelope PRAASED-012-F-CF / vehicul Request for Quota Single Stage - One E IDA / V0020 Unallocated Post Limited 120,000.00 246,318.60 Completed 2017-10-25 2018-02-09 2017-12-20 2018-01-09 2018-06-18 2018-03-30 e UCP tions nvelope PRAASED-002-F-ED / TOMPR IDA / V0020 Unallocated Prior Direct Selection Direct 40,000.00 0.00 Canceled 2017-03-28 2017-04-02 2017-05-07 2017-11-03 O- Acquisition logiciel TOMPR O PRAASED-012-F-ED / cablag IDA / V0020 Unallocated Post Direct Selection Direct 150,000.00 1,244.88 Signed 2017-10-30 2017-11-04 2017-12-09 2018-01-12 2018-06-07 es 4 sites MEPSA CG-PRAASED-065-F-CF-2018 / Fourniture matériel informa Providing quality education f Request for Quota Single Stage - One E tique (tablettes-ordinateurs) IDA / 58060 Post Limited 300,000.00 230,746.50 Completed 2018-04-24 2018-04-18 2018-06-19 2018-04-30 2018-12-16 2018-08-03 or all tions nvelope pour la collectes des donnée s statistiques des 3 ministère s de l'ensignement CG-PRAASED-075-F-CF-2018 / Fourniture, livraison et insta Improving system performa Request for Quota Single Stage - One E IDA / 58060 Post Limited 15,000.00 12,550.32 Completed 2018-07-11 2018-03-21 2018-09-05 2018-04-17 2019-03-04 2018-05-04 llation de l'équipement infor nce tions nvelope matique destiné à l'INS CG-PRAASED-078-F-CF-2018 / Fourniture de la conexion In Improving system performa Request for Quota Single Stage - One E IDA / 58060 Post Limited 12,000.00 10,469.68 Completed 2018-07-16 2018-04-30 2018-09-10 2018-06-04 2019-03-09 2022-06-22 ternet dans les bureaux du P nce tions nvelope RAASED (Abonnement et Equ ipement) CG-PRAASED-048-F-AON-17 Providing quality education f Request for Quota Single Stage - One E / Télephone mobile contrôle IDA / 58060 Post Open - National 10,000.00 0.00 Canceled 2018-11-27 2019-01-22 2019-07-21 or all tions nvelope action au sein des écoles CG-PRAASED-080-F-CF-2018 Improving system performa Request for Quota Single Stage - One E IDA / 58060 Post Limited 40,000.00 22,228.04 Completed 2018-08-04 2018-05-31 2018-09-29 2018-09-07 2019-03-28 2018-09-25 / Acquisition du Groupe élect nce tions nvelope rogène CG-PRAASED-085-AOI-2019 / Appel d'offre international po Improving scope, quality an Open - Internationa Single Stage - Two E ur la fourniture et installation IDA / 58060 d management of human re Post Request for Bids 800,000.00 0.00 Canceled 2019-03-04 2019-03-09 2019-04-20 2019-07-03 2019-08-07 2020-02-03 l nvelope d'un système pour l' enregist sources rement biométrique des ense ignants. CG-PRAASED-085 BIS-AOI-20 19-2 / Fourniture, installation Improving scope, quality an Open - Internationa Single Stage - One E et assistance à la mise en oe IDA / 58060 d management of human re Post Request for Bids 800,000.00 899,030.25 Completed 2019-05-11 2019-05-13 2019-05-16 2019-05-13 2019-06-27 2019-07-12 2019-07-27 2019-09-12 2019-08-31 2019-12-31 2020-02-27 2022-06-22 l nvelope uvre d'un système d'enregist sources rement biometrique des ense ignants du MEPSA. CG-PRAASED-104- F -ED- 20 19 / Internet : Renouvelleme Improving system performa nt du contrat de Fourniture d IDA / 58060 Post Direct Selection Direct 36,000.00 0.00 Canceled 2019-07-10 2019-06-26 2019-07-15 2019-07-16 2019-08-19 2020-02-15 nce e la connexion Internet dans les bureaux du PRAASED CG-PRAASED-099-F-ED-2019 Improving system performa IDA / 58060 Post Direct Selection Direct 2,000.00 3,600.00 Completed 2020-02-27 2019-11-08 2020-03-03 2020-01-13 2020-04-07 2020-01-30 2020-10-04 2020-02-08 / Acquisition du logiciel STAT nce A CG-PRAASED-0120-ASC-CF-2 020 / Production des fascicul Providing quality education f Request for Quota Single Stage - One E IDA / 58060 Post Limited 557,076.00 433,604.47 Completed 2020-06-16 2020-06-05 2020-08-11 2020-06-17 2021-02-07 2020-07-01 es restants destinés aux elev or all tions nvelope es du MEPSA en classes d'ex amen. CG-PRAASED-0121-CF- 2020 / Production des cahiers d’act ivités des classes intermédiai Providing quality education f Request for Quota Single Stage - One E IDA / 58060 Post Limited 853,788.00 1,218,698.85 Completed 2020-09-06 2020-09-18 2020-11-01 2020-10-08 2021-04-30 2020-12-31 res dans le pôle de Pointe-No or all tions nvelope ire (Pointe-Noire, Kouilou, Nia ri, Lekoumou, Bouenza), en d eux lots CG-PRAASED-0122-CF -2020 / Production des cahiers d’act ivités des classes intermédiai Providing quality education f Request for Quota Single Stage - One E IDA / 58060 Post Limited 970,973.00 1,280,761.25 Completed 2020-09-06 2020-09-18 2020-11-01 2020-10-08 2021-04-30 2021-04-27 res dans le pôle de Brazzavill or all tions nvelope e (Brazzaville, Pool, Plateaux Cuvette, Cuvette-Ouest, San gha et Likouala), lot unique. CG-PRAASED-081-F-CF-2018 / Acquisition fourniture de bu Improving system performa Request for Quota Single Stage - One E IDA / 58060 Post Limited 80,000.00 0.00 Canceled 2020-04-21 2020-06-16 2020-12-13 reau et consommables infor nce tions nvelope matiques- contrat cadre Page 1 CG-PRAASED-0149 -F-ED-20 21 / Logiciel AFIS- Acquisition Improving scope, quality an Under Imple d'une licence AFIS pour l'enr IDA / 58060 d management of human re Post Direct Selection Direct 185,981.00 0.00 2021-12-30 2021-12-17 2022-01-04 2022-02-08 2022-08-07 mentation ôlement biométrique de 30 0 sources 00 enseignants (phase génér alisation) CG-PRAASED-0157- / 12 véhi Improving system performa Request for Quota Single Stage - One E cules - Acquisition des 12 vé IDA / 58060 Post Limited 761,421.32 570,110.40 Signed 2022-03-21 2022-03-22 2022-05-16 2022-04-29 2022-11-12 nce tions nvelope hicules destinés aux DDEPSA CG-PRAASED-0158- F -CF-20 22 / PE+ CA du CP1-CP2 -La production et la livraison dan s les 12 Départements des pr Providing quality education f Request for Quota Single Stage - One E IDA / 58060 Post Limited 1,130,355.00 1,429,888.73 Signed 2022-03-23 2022-01-26 2022-05-18 2022-04-14 2022-11-14 ogrammes et guides pédago or all tions nvelope giques ainsi que les cahiers d'activités des nouveaux pro grammes révisés pour les cla sses de CP1, CP2. CG- PRAASED-0159-F- CF-20 22 / PE+ CA de la 6è et 5è -L a production et la livraison d ans les 12 Départements des Providing quality education f Request for Quota Single Stage - One E Under Imple IDA / 58060 Post Limited 752,248.91 0.00 2022-03-30 2022-08-01 2022-05-25 2022-11-21 programmes et guides pédag or all tions nvelope mentation ogiques (PE) ainsi que les ca hiers d'activités (CA) des nou veaux programmes révisés p our les classes de la 6ème et 5ème . CG-PRAASED-0176-F-CF-202 2 / DEP- IGEPSA-DDEPPSA - A Improving system performa Request for Quota Single Stage - One E cquisition du matériel inform IDA / 58060 Post Limited 60,000.00 0.00 Signed 2022-10-16 2022-10-25 2022-12-11 2023-06-09 nce tions nvelope atique destiné à la DEP, l'IGE PSA .et aux DDEPPSA du MEP PSA. CG-PRAASED-0177- F-ED-20 22 / CA 6è et 5è- Production des cahiers d’activités compl Providing quality education f émentaires des classes de 6è IDA / 58060 Post Direct Selection Direct - National 160,500.00 0.00 Signed 2022-10-29 2022-10-05 2022-11-03 2022-10-06 2022-12-08 2023-06-06 or all me et 5ème, issus des nouve aux programmes dans les d eux pôles (Brazzaville et Poin te-Noire). CG-PRAASED-0184-F-CF-202 Improving scope, quality an Request for Quota Single Stage - One E Under Imple 3 / DNEAS - Acquisition des é IDA / 58060 d management of human re Post Limited 16,933.00 0.00 2023-04-06 2023-06-01 2023-11-28 tions nvelope mentation quipements informatiques du sources DNEAS CG-PRAASED-0185-CS-CI-20 23 / Recrutement de 12 vérifi Providing quality education f Request for Quota Single Stage - One E IDA / 58060 Post Limited 70,632.00 0.00 Canceled 2023-04-08 2023-06-03 2023-11-30 cateurs indépendants des su or all tions nvelope pports pédagogiques distribu és CG-PRAASED-0189-F-CF-202 Improving scope, quality an 3 / Impression de 200 annuai Request for Quota Single Stage - One E Pending Impl IDA / 58060 d management of human re Post Limited 3,626.00 0.00 2023-04-19 2023-06-14 2023-12-11 res statistiques du MEPPSA 2 tions nvelope ementation sources 018 -2019 & 2019-2020 (15 j ours) CG-PRAASED-0192-CF-ED-20 23 / Recrutement des imprim eurs pour la Reproduction de Providing quality education f IDA / 58060 Post Direct Selection Direct - National 322,310.00 0.00 Canceled 2023-04-03 2023-04-08 2023-05-13 2023-11-09 s nouveaux programmes édu or all catifs et guides pédagogique s des classes restantes du CE 1 au CM2, 4ème à 3ème CG-PRAASED-0193-F-CF-202 Providing quality education f Request for Quota Single Stage - One E Pending Impl 3 / Impression des instrumen IDA / 58060 Post Limited 65,192.00 0.00 2023-04-08 2023-06-03 2023-11-30 or all tions nvelope ementation ts d’enquête finale du DNEAS CG-PRAASED-0195-F-CF-202 Providing quality education f Request for Quota Single Stage - One E Under Imple 3 / Acquisition de fournitures IDA / 58060 Post Limited 8,724.00 0.00 2023-04-08 2023-06-03 2023-11-30 or all tions nvelope mentation pour le DNEAS CG-PRAASED-0194-CF-ED-20 23 / Recrutement des imprim Providing quality education f eurs pour la Reproduction de IDA / 58060 Post Direct Selection Direct - National 1,205,584.00 0.00 Canceled 2023-04-03 2023-04-08 2023-05-13 2023-11-09 or all s cahiers d'activités des class es restantes du CE1 au CM2, 4ème à 3ème CG-PRAASED-0191-F-CF-202 Providing quality education f Request for Quota Single Stage - One E Pending Impl 3 / Impression des instrumen IDA / 58060 Post Limited 65,192.00 0.00 2023-04-15 2023-06-10 2023-12-07 or all tions nvelope ementation ts d’enquête finale CG-PRAASED-0198-CF-ED-20 23 / Reproduction des nouve aux programmes éducatifs et Providing quality education f Pending Impl IDA / 58060 Post Direct Selection Direct - National 322,311.00 0.00 2023-05-02 2023-05-07 2023-06-11 2023-12-08 guides pédagogiques du pri or all ementation maire (du CP1 au CM2) et col lège (de la 6ème en 3ème) CG-PRAASED-0199-CF-ED-20 23 / Reproduction des Cahier Providing quality education f Pending Impl IDA / 58060 Post Direct Selection Direct - National 974,955.00 0.00 2023-05-02 2023-05-07 2023-06-11 2023-12-08 s d'activités des programme or all ementation s révisés restants (CE1 au C M2, 4e et 3e) CG-PRAASED-0200-CF-ED-20 23 / Reproduction des Cahier Providing quality education f Pending Impl IDA / 58060 Post Direct Selection Direct - National 406,231.00 0.00 2023-05-02 2023-05-07 2023-06-11 2023-12-08 s d’activités des programmes or all ementation révisés restants (CE1 au CM2 , 4e et 3e) CG-PRAASED-0201-CF-ED-20 23 / Reproduction des Cahier Providing quality education f Pending Impl IDA / 58060 Post Direct Selection Direct - National 243,739.00 0.00 2023-05-02 2023-05-07 2023-06-11 2023-12-08 s d'activités des programmes or all ementation révisés restants (CE1 au CM2 , 4e et 3e) CG-PRAASED-0178 -F-AON-2 022 / - Tablettes SIGE- Acquis Improving system performa Single Stage - One E IDA / 58060 Post Request for Bids Open - National 124,000.00 0.00 Canceled 2022-12-23 2023-01-26 2022-12-28 2023-02-08 2023-02-08 2023-03-10 2023-04-14 2023-10-11 ition de 400 tablettes pour la nce nvelope mise en place du SIGE du ME PPSA PRAASED-013-F-AON / appar Single Stage - One E IDA / V0020 Unallocated Post Request for Bids Open - National 120,000.00 0.00 Canceled 2017-04-05 2017-04-10 2017-05-22 2017-06-21 2017-07-26 2018-01-22 eils biométriques nvelope NON CONSULTING SERVICES Page 2 Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CG-PRAASED-074-CF-ED-201 Improving system performa 8 / Contrat de bail à usage d IDA / 58060 Post Direct Selection Direct 122,400.00 0.00 Canceled 2018-06-27 2018-07-02 2018-08-06 2019-02-02 nce es bureaux du PRAASED CG-PRAASED-073-AS-CF-201 8 / Prestation de services pou Improving system performa Request for Quota Single Stage - One E IDA / 58060 Post Limited 12,000.00 4,667.89 Completed 2018-07-11 2018-03-05 2018-09-05 2018-03-15 2019-03-04 2018-03-16 r l'assurance tous risques de nce tions nvelope s véhicules destinés au PRAA SED CG-PRAASED-076-AS-CF-201 Improving system performa Request for Quota Single Stage - One E 8 / Prestation de services pou IDA / 58060 Post Limited 20,000.00 16,899.39 Completed 2018-07-11 2018-04-03 2018-09-05 2018-05-10 2019-03-04 2019-05-09 nce tions nvelope r le gardiennage des bureaux du PRAASED CG-PRAASED-077-AS-CF-201 Improving system performa Request for Quota Single Stage - One E 8 / Prestation de services pou IDA / 58060 Post Limited 10,000.00 7,331.05 Completed 2018-07-11 2018-04-03 2018-09-05 2018-05-10 2019-03-04 2019-05-09 nce tions nvelope r l'entretien des bureau du P RAASED CG-PRAASED-079-AS-CF-201 8 / Prestation de services pou r la restauration des participa nts à la formation sur la colle Improving system performa Request for Quota Single Stage - One E IDA / 58060 Post Limited 150,000.00 172,585.42 Completed 2018-07-16 2018-06-12 2018-09-10 2018-06-30 2019-03-09 2018-06-28 cte des données statistiques nce tions nvelope des ministères en charge de l 'éducation à Brazzaville, Poin te-Noire et Owando (en lots distincts. CG-PRAASED-091-ED-2019 / Contrat de maintenance et e Improving system performa ntretien du groupe electroge IDA / 58060 Post Direct Selection Direct 15,000.00 1,637.82 Completed 2019-04-23 2019-04-28 2019-04-29 2019-06-02 2019-05-10 2019-11-29 2020-08-28 nce ne du PRAASED, avec Grasse t SPORAFRIC- Fournisseur du groupe CG-PRAASED-105- ASC-ED-2 019 / Gardiennage - Renouve Improving system performa llement du contrat de Prestat IDA / 58060 Post Direct Selection Direct 57,600.00 32,554.89 Completed 2019-07-10 2019-07-07 2019-07-15 2019-07-07 2019-08-19 2019-08-20 2020-02-15 2020-12-30 nce ion de services pour le gardie nnage des bureaux du PRAA SED CG-PRAASED-106- ASC-ED-2 019 / Entretien bureaux : Ren Improving system performa ouvellement du contrat de Pr IDA / 58060 Post Direct Selection Direct 25,200.00 14,090.92 Completed 2019-07-10 2019-07-07 2019-07-15 2019-07-07 2019-08-19 2019-08-20 2020-02-15 2020-12-30 nce estation de services pour l'en tretien des bureau du PRAAS ED CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PRAASED-009-C-SFQC / cabi Quality And Cost- Open - Internationa IDA / V0020 Unallocated Post 300,000.00 0.00 Canceled 2017-03-31 2017-04-21 2017-06-04 2017-07-02 2017-08-01 2017-09-05 2017-10-10 2018-10-10 net evalu syst educatif congo Based Selection l lais PRAASED-006-C-QC / cabine Consultant Qualifi Open - Internationa IDA / V0020 Unallocated Prior 40,000.00 0.00 Canceled 2017-03-27 2017-04-17 2017-05-31 2017-06-30 2017-08-04 2018-01-31 t perso clé cation Selection l CG-PRAASED-049-C-SFQC-17 Providing quality education f Quality And Cost- Open - Internationa / Cabinet système biométriqu IDA / 58060 Post 120,000.00 0.00 Canceled 2017-10-20 2017-11-10 2017-12-24 2018-01-21 2018-02-20 2018-03-27 2018-05-01 2019-05-01 or all Based Selection l e recensement enseignant CG-PRAASED-056-C-CI-17 / A Improving system performa Quality And Cost- Open - Internationa IDA / 58060 Prior 40,000.00 48,895.38 Completed 2018-02-05 2018-02-14 2018-02-26 2018-02-16 2018-04-11 2018-04-27 2018-05-09 2018-06-08 2018-06-04 2018-07-13 2018-06-13 2018-08-17 2018-06-13 2019-08-17 2019-08-29 udit externe 2017-2018 nce Based Selection l CG-PRAASED-037-C-SFQC-17 Providing quality education f Quality And Cost- Open - Internationa IDA / 58060 Prior 50,000.00 0.00 Canceled 2018-03-14 2018-04-04 2018-05-18 2018-06-15 2018-07-15 2018-08-19 2018-09-23 2019-09-23 / Audit externe or all Based Selection l CG-PRAASED-032-C-SFQC-17 / Analyse reforme enseignem Improving scope, quality an ent superieur et l'ensembe d Quality And Cost- Open - Internationa IDA / 58060 d management of human re Prior 250,000.00 0.00 Canceled 2019-06-17 2019-07-08 2019-08-21 2019-09-18 2019-10-18 2019-11-22 2019-12-27 2020-12-26 u système portant sur l'adéq Based Selection l sources uation enseignement superie ur et marché du travail , gou vernance du secteur... CG-PRAASED-029-C-SFQC-17 / Eval dispositifs et/ ou meca Providing quality education f Quality And Cost- Open - Internationa IDA / 58060 Post 200,000.00 0.00 Canceled 2018-10-15 2018-11-05 2018-12-19 2019-01-16 2019-02-15 2019-03-22 2019-04-26 2020-04-25 nismes d'évaluation des acqu or all Based Selection l is des élèves/apprentissage CG-PRAASED-026-C-SFQC / Cabinet recensement bénévo Providing quality education f Quality And Cost- Open - Internationa les et autres personnel ensei IDA / 58060 Post 170,000.00 0.00 Canceled 2018-11-05 2018-11-26 2019-01-09 2019-02-06 2019-03-08 2019-04-12 2019-05-17 2020-05-16 or all Based Selection l gnant: directeurs scolaires, c onseillers pédagogiques, insp ecteurs.. PRAASED-011 BIS-C-SFQC-2 018 / Révision des curriculas Improving system performa Quality And Cost- - Recrutement d'un cabinet c IDA / 58060 Prior Open - National 500,000.00 0.00 Canceled 2018-08-10 2018-08-31 2018-10-14 2018-11-11 2018-12-11 2019-01-15 2019-02-19 2020-02-19 nce Based Selection hargé de la révision des curri culas du primaire et secondai re CG-PRAASED-021-C-SFQC-17 Providing quality education f Quality And Cost- Open - Internationa IDA / 58060 Post 234,000.00 0.00 Canceled 2019-02-28 2019-03-21 2019-05-04 2019-06-01 2019-07-01 2019-08-05 2019-09-09 2020-09-08 / Contrôle travaux depart 1 or all Based Selection l CG-PRAASED-027-C-SFQC / c abinet enquête SDI - Recrute Providing quality education f Consultant Qualifi Open - Internationa IDA / 58060 Post 500,000.00 0.00 Canceled 2018-07-30 2018-08-17 2018-08-20 2018-09-03 2018-10-03 2018-11-02 2018-12-07 2019-06-05 ment d'un cabinet chargé de or all cation Selection l réaliser l'enquête SDI CG-PRAASED-030-C-SFQC-17 Providing quality education f Quality And Cost- Open - Internationa / Analyse programme de for IDA / 58060 Prior 700,000.00 0.00 Canceled 2019-02-19 2019-03-12 2019-04-25 2019-05-23 2019-06-22 2019-07-27 2019-08-31 2020-08-30 or all Based Selection l mation et pratiques classe CG-PRAASED-060-C-SQC-18 Improving scope, quality an / Mise en place du système bi Consultant Qualifi Open - Internationa IDA / 58060 d management of human re Post 240,000.00 0.00 Canceled 2018-03-13 2018-04-03 2018-05-17 2018-03-15 2018-06-16 2018-07-21 2019-01-17 ométrique pour l'enregistrem cation Selection l sources ent des enseignants Page 3 CG-PRAASED-089-CS-SFQC-2 019 / Enquete SDI- Recrutem Providing quality education f Quality And Cost- Open - Internationa ent d'un cabinet en charge d IDA / 58060 Prior 750,000.00 919,214.00 Completed 2019-03-12 2019-04-12 2019-04-02 2019-04-18 2019-05-16 2019-07-17 2019-06-13 2019-08-22 2019-07-13 2019-10-09 2019-08-17 2019-12-23 2019-09-21 2019-12-25 2020-09-20 2022-07-15 or all Based Selection l e l'enquete sur les indicateur s de prestation de services e n Republique du Congo CG-PRAASED-108- CS-QC-20 19 / INRAP- Recrutement d’u n consultant International po Improving system performa Consultant Qualifi Open - Internationa IDA / 58060 Post 50,000.00 0.00 Canceled 2019-07-11 2019-08-01 2019-09-14 2019-10-14 2019-11-18 2020-05-16 ur une assistance a l’elaborat nce cation Selection l ion d’une feuille de route et d ’un plan strategique de l’INR AP CG-PRAASED- 107- CS- QC-2 019 / ENI/ENS - Recrutement d’un Consultant International Improving system performa Consultant Qualifi Open - Internationa IDA / 58060 Post 50,000.00 0.00 Canceled 2019-07-11 2019-08-01 2019-09-14 2019-10-14 2019-11-18 2020-05-16 pour une assistance a l’elabo nce cation Selection l ration d’une feuille de route et d’un plan strategique de ENI/ENS CG-PRAASED-0114-CS-SFQC- 2019 / Audit Externe 2019-20 20 : Recrutement d'un cabin Improving system performa Quality And Cost- Open - Internationa IDA / 58060 Post 60,000.00 26,404.83 Completed 2019-10-24 2019-11-20 2019-11-14 2019-11-27 2019-12-28 2020-02-25 2020-01-25 2020-03-25 2020-02-24 2020-06-08 2020-03-30 2020-06-22 2020-05-04 2020-07-02 2021-05-04 2021-07-31 et d'expertise comptable cha nce Based Selection l rgé de l'audit des comptes d u PRAASED (exercices 2019- 2020). CG-PRAASED-125-SFQC-202 1 / Auditeur Interne - Recrute Improving system performa Quality And Cost- Open - Internationa IDA / 58060 Post 50,000.00 67,984.66 Terminated 2021-06-15 2021-01-14 2021-07-06 2021-08-19 2021-05-06 2021-09-16 2021-06-04 2021-10-16 2021-06-28 2021-11-20 2021-07-01 2021-12-25 2021-09-25 2022-12-25 ment d'un cabinet ou firme p nce Based Selection l our assurer la fonction d’audi t interne du PRAASED CG-PRAASED-125-SC-SFQC-2 021-REGULARISATI / Audit Int Improving system performa Quality And Cost- Open - Internationa erne - Recrutement d'un cabi IDA / 58060 Post 50,000.00 70,222.92 Signed 2021-10-08 2021-01-19 2021-10-29 2021-12-12 2021-05-06 2022-01-09 2021-06-04 2022-02-08 2021-06-18 2022-03-15 2021-07-01 2022-04-19 2021-09-25 2023-04-19 nce Based Selection l net ou firme pour assurer la f onction d'audit interne du PR AASED CG-PRAASED-0137-CS-QC-2 021 / Leadership - Recrutem Improving scope, quality an ent d’un cabinet/ Bureau d’ét Consultant Qualifi Open - Internationa Under Implement IDA / 58060 d management of human re Post 150,000.00 0.00 2021-11-04 2022-02-08 2021-11-25 2022-03-08 2022-01-08 2022-02-07 2022-03-14 2022-09-10 ude chargé de la formation d cation Selection l ation sources es Directeurs d’établissemen ts scolaires en leadership et en Management. CG-PRAASED-0148-CS-SFQC- 2021 / Audit externe 2021-20 22- Recrutement d'un cabin Improving system performa Quality And Cost- Open - Internationa et/ Firme d'expertise compta IDA / 58060 Post 60,000.00 13,616.09 Signed 2021-12-29 2022-01-18 2022-01-19 2022-02-02 2022-03-04 2022-03-18 2022-04-01 2022-04-20 2022-05-01 2022-04-26 2022-06-05 2022-05-24 2022-07-10 2022-05-24 2023-07-10 nce Based Selection l ble, chargé de l'audit des co mptes du PRAASED, exercice 2021 et exercice 2022 (clôtur e au 30 juin) INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PRAASED-003-C-CI / CI DFC- Individual Consult IDA / V0020 Unallocated Post Open 50,000.00 0.00 Canceled 2017-03-30 2017-05-18 2017-06-08 2017-07-13 2018-01-09 Evaluation des capacités DFC ant Selection PRAASED-008-C-CI / CI capa Individual Consult IDA / V0020 Unallocated Post Open 70,000.00 0.00 Canceled 2017-03-29 2017-05-17 2017-06-07 2017-07-12 2018-01-08 cité DDPSA ant Selection PRAASED-004-C-CI / CI INRA Individual Consult IDA / V0020 Unallocated Post Open 60,000.00 0.00 Canceled 2017-03-31 2017-05-19 2017-06-09 2017-07-14 2018-01-10 P- evaluation capacités INRA ant Selection P PRAASED-011-C-CI / CI revisi Individual Consult IDA / V0020 Unallocated Post Open 120,000.00 0.00 Canceled 2018-03-07 2018-04-25 2018-05-16 2018-06-20 2018-12-17 on curricula primaire et seco ant Selection ndaire PRAASED-015-C-ED / Elabor IDA / 58060 Unallocated Prior Direct Selection Direct 10,000.00 0.00 Canceled 2017-04-06 2017-04-16 2017-06-20 2017-12-17 ation manuel de procédures PRAASED-005-C-CI / CI ENI e Individual Consult t ENS- evaluation des formati IDA / V0020 Unallocated Post Open 90,000.00 0.00 Canceled 2017-03-31 2017-05-19 2017-06-09 2017-07-14 2018-01-10 ant Selection ons ENI et ENS CG-PRAASED-020-C-CI-17 / A Improving system performa Individual Consult IDA / 58060 Post Open 90,000.00 0.00 Canceled 2018-01-12 2018-01-11 2018-03-02 2018-03-23 2018-04-27 2018-10-24 uditeur interne nce ant Selection CG-PRAASED-038-C-CI-17 / R Improving system performa Individual Consult IDA / 58060 Post Open 90,000.00 0.00 Canceled 2017-11-06 2017-12-01 2017-12-25 2018-01-15 2018-02-19 2018-08-18 ecrut Comptable nce ant Selection CG-PRAASED-028-C-CI-17 / A Providing quality education f Individual Consult IDA / 58060 Prior Open 200,000.00 0.00 Canceled 2018-03-18 2018-01-19 2018-05-06 2018-05-27 2018-07-01 2018-12-28 nalyse inst MEPSA et DDPSA or all ant Selection CG-PRAASED-36-C-ED-17 / Pl Improving scope, quality an ate forme contrôle et verifica IDA / 58060 d management of human re Prior Direct Selection Direct 100,000.00 0.00 Canceled 2018-06-13 2018-06-23 2018-08-27 2019-02-23 tion des actions au sein de l' sources école par BLUE SQUARE CG-PRAASED-051-C-CI-17 / R Improving system performa Individual Consult IDA / 58060 Prior Open 139,200.00 245,144.43 Completed 2017-12-18 2018-02-05 2018-02-26 2018-01-18 2018-04-02 2018-01-15 2018-09-29 2021-01-30 ecrutement coordonnateur P nce ant Selection RAASED CG-PRAASED-052-C-CI-17 / R Improving system performa Individual Consult IDA / 58060 Prior Open 51,600.00 48,273.86 Completed 2017-12-18 2018-02-05 2018-02-26 2018-01-18 2018-04-02 2018-01-15 2018-09-29 2019-01-14 ecrutement RAFC nce ant Selection CG-PRAASED-053-C-CI-17 / R Improving system performa Individual Consult IDA / 58060 Prior Open 51,600.00 48,273.86 Completed 2017-12-18 2018-02-05 2018-02-26 2018-01-18 2018-04-02 2018-01-15 2018-09-29 2019-01-14 ecrutement SPM nce ant Selection CG-PRAASED-055-C-CDS-17 Providing quality education f / Appui INS aux trois ministèr IDA / 58060 Prior Direct Selection Direct 48,000.00 98,518.39 Completed 2018-02-15 2018-02-25 2018-05-01 2018-02-08 2018-10-28 2020-02-28 or all es MEPSA MES METPFQE CG-PRAASED-057-C-CI-18 / R Improving system performa Individual Consult IDA / 58060 Prior Open 228,000.00 0.00 Canceled 2018-02-13 2018-02-14 2018-04-03 2018-12-27 2018-04-24 2018-05-29 2018-11-25 ecrutement Auditeur interne nce ant Selection Page 4 CG-PRAASED-058-C-CI-18 / R Improving system performa Individual Consult IDA / 58060 Prior Open 192,000.00 101,406.72 Completed 2018-02-13 2018-02-14 2018-04-03 2018-04-18 2018-04-24 2018-06-12 2018-05-29 2018-06-12 2018-11-25 2021-01-30 ecrutement Comptable nce ant Selection CG-PRAASED-059-C-ED-18 / Appui au MEPSA pour partici Providing quality education f IDA / 58060 Prior Direct Selection Direct 617,760.00 466,774.66 Completed 2018-02-12 2018-02-22 2018-07-20 2018-04-28 2018-12-11 2018-10-25 2020-12-30 pation à l'évaluation internati or all onale PASEC 2019 CG-PRAASED-060-C-ED-2018 Improving system performa / Analyse institutionnelle MEP IDA / 58060 Prior Direct Selection Direct 200,000.00 56,498.00 Completed 2018-03-02 2018-03-07 2018-03-12 2018-03-13 2018-05-16 2018-06-11 2018-11-12 2018-12-29 nce SA et DDPSA CG-PRAASED-063-C-CI-18 / R Improving system performa Individual Consult ecrutement du Responsable IDA / 58060 Post Open 258,000.00 0.00 Canceled 2018-03-13 2018-03-06 2018-05-01 2018-05-22 2018-06-26 2018-12-23 nce ant Selection de la composante 3 (RC 3) d u PRAASED CG-PRAASED-062-C-CI-18 / R Improving system performa Individual Consult ecrutement du Responsable IDA / 58060 Post Open 258,000.00 0.00 Canceled 2018-03-13 2018-03-06 2018-05-01 2018-05-22 2018-06-26 2018-12-23 nce ant Selection de la composante 2 (RC 2) d u PRAASED CG-PRAASED-061-C-CI-18 / R Improving system performa Individual Consult ecrutement du responsable d IDA / 58060 Post Open 258,000.00 0.00 Canceled 2018-03-13 2018-03-06 2018-05-01 2018-05-22 2018-06-26 2018-12-23 nce ant Selection e la composante 1 (RC 1) du PRAASED CG-PRAASED-064-C-CI-18 / R Improving system performa Individual Consult ecrutement du Responsable IDA / 58060 Post Open 258,000.00 0.00 Canceled 2018-03-13 2018-03-06 2018-05-01 2018-05-22 2018-06-26 2018-12-23 nce ant Selection du Suivi-Evaluation (RSE) du PRAASED CG-PRAASED-063-C-CI-2018 Improving system performa Individual Consult / Recrutement du Responsabl IDA / 58060 Prior Open 258,000.00 87,084.54 Completed 2018-03-30 2018-04-27 2018-05-18 2018-12-07 2018-06-08 2019-02-07 2018-07-13 2019-02-08 2019-01-09 2021-01-30 nce ant Selection e de la composante 3 (RC3) du PRAASED CG-PRAASED-061-C-CI-2018 Improving system performa Individual Consult / Recrutement du Responsabl IDA / 58060 Prior Open 258,000.00 87,027.53 Completed 2018-03-30 2018-05-21 2018-05-18 2018-12-07 2018-06-08 2019-02-12 2018-07-13 2019-02-13 2019-01-09 2021-01-30 nce ant Selection e de la composante 1 (RC1) du PRAASED CG-PRAASED-064-C-CI-2018 Improving system performa Individual Consult / Recrutement du Responsabl IDA / 58060 Prior Open 258,000.00 87,519.28 Completed 2018-03-30 2018-04-27 2018-05-18 2018-12-07 2018-06-08 2019-02-07 2018-07-13 2019-02-08 2019-01-09 2021-01-30 nce ant Selection e Suivi-Évaluation (RSE) du P RAASED CG-PRAASED-066-C-CI-2018 Improving system performa Individual Consult / Recrutement d'un Assistant IDA / 58060 Post Open 168,000.00 0.00 Canceled 2018-05-04 2018-06-30 2018-06-22 2018-07-13 2018-08-17 2019-02-13 nce ant Selection chargé de la communication du PRAASED CG-PRAASED-068-C-CI-2018 Improving system performa Individual Consult / Recrutement d'un Trésorier IDA / 58060 Post Open 144,000.00 0.00 Canceled 2018-05-25 2018-04-25 2018-07-13 2018-08-03 2018-09-07 2019-03-06 nce ant Selection du PRAASED CG-PRAASED-069-C-CI-2018 Improving system performa Individual Consult / Recrutement d'un Assistant IDA / 58060 Post Open 96,000.00 0.00 Canceled 2018-05-25 2018-04-25 2018-07-13 2018-08-03 2018-09-07 2019-03-06 nce ant Selection Administratif du PRAASED CG-PRAASED-070-C-CI-2018 Improving system performa Individual Consult / Recrutement d'une Sécretai IDA / 58060 Post Open 72,000.00 0.00 Canceled 2018-05-25 2018-04-25 2018-07-13 2018-08-03 2018-09-07 2019-03-06 nce ant Selection re de direction du PRAASED CG-PRAASED-071-C-CI-2018 Improving system performa Individual Consult / Recutement de trois Chauff IDA / 58060 Post Open 108,000.00 25,277.93 Completed 2018-05-25 2018-04-25 2018-07-13 2018-08-06 2018-08-03 2018-08-23 2018-09-07 2018-09-03 2019-03-06 2020-09-30 nce ant Selection eurs du PRAASED CG-PRAASED-066-CS-CI-201 Improving system performa Individual Consult 8 / Recrutement d'un Spéciali IDA / 58060 Prior Open 258,000.00 87,556.69 Completed 2018-07-11 2018-08-02 2018-08-29 2019-01-21 2018-09-19 2019-02-27 2018-10-24 2019-03-01 2019-04-22 2021-01-30 nce ant Selection ste en charge de la communi cation CG-PRAASED-018-C-CI-17 / I ngénieur en génie civil - Rec Improving system performa Individual Consult IDA / 58060 Post Open 120,000.00 0.00 Canceled 2019-01-08 2019-02-26 2019-03-19 2019-04-23 2019-10-20 rutement d'un Ingénieur en g nce ant Selection énie civile chargé des constr uctions scolaires CG-PRAASED-050-C-CI-17 / C onsultant banque items pour Providing quality education f Individual Consult IDA / 58060 Post Open 25,000.00 0.00 Canceled 2018-10-22 2018-12-10 2018-12-31 2019-02-04 2019-08-03 évaluation des acquis scolair or all ant Selection e au primaire et secondaire CG-PRAASED-072-CS-CI-201 8 / Recrutement d'un Spéciali Improving system performa Individual Consult IDA / 58060 Post Open 90,000.00 0.00 Canceled 2018-09-04 2018-10-23 2018-11-13 2018-12-18 2019-06-16 ste en Sauvegarde environne nce ant Selection mentale du PRAASED CG-PRAASED-017-BIS-C-CI-2 018 / Sauvegarde sociale - R Improving system performa Individual Consult IDA / 58060 Post Open 90,000.00 0.00 Canceled 2018-09-04 2018-10-23 2018-11-13 2018-12-18 2019-06-16 ecrutement d'un consultant c nce ant Selection hargé d la suvegarde sociale du PRAASED CG-PRAASED-019-C-CI-17 / T Improving system performa Individual Consult IDA / 58060 Post Open 60,000.00 0.00 Canceled 2019-01-08 2019-02-26 2019-03-19 2019-04-23 2019-10-20 echnicien sup en génie civil nce ant Selection CG-PRAASED-082-C-ED-2018 / Consultant FGB - Recrutem ent du consultant Internation Providing quality education f IDA / 58060 Post Direct Selection Direct 60,000.00 0.00 Canceled 2018-08-07 2018-08-17 2018-08-17 2018-10-21 2019-04-19 al, spécialiste en formation g or all estion à la Base, pour la mise en oeuvre du volet communa utaire CG-PRAASED-062-C-CI-2018 Improving system performa Individual Consult / Recrutement du Responsabl IDA / 58060 Prior Open 258,000.00 0.00 Canceled 2018-03-30 2018-06-04 2018-05-18 2018-06-08 2018-07-13 2019-01-09 nce ant Selection e de la composante 2 (RC2) du PRAASED CG-PRAASED-062 BIS-CS-IN Improving system performa Individual Consult DV / Recrutement d'un Respo IDA / 58060 Prior Open 258,000.00 87,871.19 Completed 2019-01-15 2018-12-08 2019-03-05 2019-02-18 2019-03-26 2019-04-25 2019-04-30 2019-04-26 2019-10-27 2021-01-30 nce ant Selection nsable de la Composante 2 ( RC2) CG-PRAASED-017-C-CI-17 / R Improving system performa Individual Consult ecrutement Spécialiste sauve IDA / 58060 Post Open 90,000.00 0.00 Canceled 2018-09-20 2018-11-08 2019-01-17 2018-11-29 2019-01-03 2019-07-02 nce ant Selection garde environnementale et s ociale CG-PRAASED-057-CS-CI-201 Improving system performa Individual Consult 8 / Recrutement d'une Assist IDA / 58060 Post Open 76,800.00 32,760.67 Completed 2019-03-06 2019-04-24 2019-06-12 2019-05-15 2019-06-13 2019-06-19 2019-06-14 2019-12-16 2021-01-30 nce ant Selection ance de direction du PRAASE D Page 5 CG-PRAASED-083-CS-CI-201 9 / Renouvelement du contra Improving system performa Individual Consult IDA / 58060 Prior Direct 206,400.00 88,034.50 Completed 2019-02-22 2019-02-28 2019-03-04 2019-01-14 2019-03-25 2019-03-12 2019-04-29 2019-03-13 2019-10-26 2021-01-30 t de service du Responsable nce ant Selection Administratif et Financier (RA F) du PRAASED CG-PRAASED-086-CS-CI-201 9 / Renouvelement du contra Improving system performa Individual Consult IDA / 58060 Prior Direct 206,400.00 87,053.33 Completed 2019-02-22 2019-02-28 2019-03-04 2019-01-14 2019-03-25 2019-03-12 2019-04-29 2019-03-13 2019-10-26 2021-01-30 t de service de la Spécialiste nce ant Selection en Passation des Marches (S PM) du PRAASED CG-PRAASED-087-CS-CI-201 9 / Recrutement d'un consult ant international pour l'analy Providing quality education f Individual Consult IDA / 58060 Post Open 60,000.00 90,929.39 Completed 2019-02-28 2019-04-30 2019-04-18 2019-07-23 2019-05-09 2019-09-23 2019-06-13 2019-09-24 2019-12-10 2021-04-30 se du dispositif des évaluatio or all ant Selection ns sommatives et examens n ationaux (CEPE, BEPC, BAC) CG-PRAASED-090-CS-CI-201 Improving system performa Individual Consult 9 / Recrutement du 3ème ch IDA / 58060 Post Open 28,800.00 6,081.98 Completed 2019-03-27 2019-04-11 2019-05-15 2019-07-22 2019-06-05 2019-07-23 2019-07-10 2019-07-25 2020-01-06 2020-07-30 nce ant Selection auffeur du PRAASED CG-PRAASED-093-CS-CI-201 Improving system performa Individual Consult 9 / Recrutement d'un Speciali IDA / 58060 Post Open 103,200.00 67,045.43 Completed 2019-04-29 2019-04-29 2019-06-17 2019-08-12 2019-07-08 2019-09-05 2019-08-12 2019-10-09 2020-02-08 2021-01-30 nce ant Selection ste en Sauvegardes Sociales du PRAASED PRAASED-094-CS-CI-2019 / Recrutement d'un consultant national pour l'analyse des e Providing quality education f Individual Consult IDA / 58060 Post Open 12,000.00 0.00 Canceled 2019-05-13 2019-07-01 2019-07-22 2019-08-26 2020-02-22 valuations formatives en situ or all ant Selection ation de classe pour les devo irs departemantaux, examen s blancs et tests. CG PRAASED-095-CS-CI-201 9 / Recrutement d'un consult ant national pour l'analyse d Providing quality education f Individual Consult IDA / 58060 Post Open 12,000.00 0.00 Canceled 2019-05-13 2019-07-01 2019-07-22 2019-08-26 2020-02-22 es évaluations formatives en or all ant Selection situation de classe pour les d evoirs, compositions mensuel les/trimestrielles CG-PRAASED-097-CS-CI-201 9 / Recrutement d'un consult ant pour la redynamisation d Improving system performa Individual Consult IDA / 58060 Post Open 8,000.00 30,960.18 Signed 2019-05-16 2019-08-29 2019-07-04 2019-11-20 2019-07-25 2020-02-18 2019-08-29 2020-05-23 2020-02-25 u site web du MEPSA et mise nce ant Selection en place des sites web de l'IN RAP, IGEPSA, DEC et DGRHA. PRAASED-098-CS-CI-2019 / Recrutement d'un consultant international charge d'appui aux équipe tecniques- à l'ela Improving system performa Individual Consult IDA / 58060 Post Open 40,000.00 0.00 Canceled 2019-05-17 2019-07-05 2019-07-26 2019-08-30 2020-02-26 boration des feuilles de route nce ant Selection et plans strategiques pour la mise en oeuvre des recomm andations des etudes realise es (ENI/ENS, INRAP, MEPSA-D DEPSA. PRAASED-0100-CS-ED-2019 / Contrat de service de consu ltant avec Viticia THAMES, co Providing quality education f nsultante internationale pour IDA / 58060 Post Direct Selection Direct 60,000.00 0.00 Canceled 2019-05-21 2019-07-30 2019-05-31 2019-08-30 2019-08-04 2020-01-31 or all l'élaboration/adaptation du p rotocole/outils CLASS pour l'a melioration de la pedagogie active et de l'apprentissage. CG-PRAASED- 101- CS-ED-20 19 / Evaluations curriculas- R ecrutement du consultant int Providing quality education f ernational pour l'appui techni IDA / 58060 Post Direct Selection Direct 140,000.00 119,210.13 Completed 2019-07-04 2019-07-09 2019-07-14 2019-07-23 2019-09-17 2019-09-25 2020-03-15 2021-12-30 or all que au processus de révision des curricula (évaluation et l a réécriture) des programme s du primaire et du secondair e CG- PRAASED- 102-CS- CI-20 19 / Evaluations Formatives - Recrutement d’un consultant national chargé de l’analyse Providing quality education f Individual Consult du dispositif actuel des evalu IDA / 58060 Post Open 24,000.00 33,076.77 Completed 2019-07-07 2019-07-09 2019-08-21 2019-09-11 2019-09-11 2019-11-21 2019-10-16 2019-12-11 2020-04-13 2021-02-26 or all ant Selection ations formatives (devoirs de classe et departementaux, c ompositions mensuelles, trim estrielles, et examens blancs /tests ) dans le systeme educ CG-PRAASED-103- CS-CI-201 Improving system performa Individual Consult 9 / Auditeur Interne : Recrute IDA / 58060 Prior Open 228,000.00 0.00 Canceled 2019-07-08 2019-08-26 2019-09-16 2019-10-21 2020-04-18 nce ant Selection ment d'un auditeur interne d u PRAASED CG-PRAASED-109-CS-CI-201 9 / SIGE : Schema directeurs Improving system performa Individual Consult Recrutement d'un consultant IDA / 58060 Post Open 80,000.00 112,081.22 Completed 2019-08-12 2019-10-23 2019-09-30 2020-02-04 2019-10-21 2020-03-27 2019-11-25 2020-06-27 2020-05-23 2021-03-31 nce ant Selection international en charge de l'e laboration du schéma directe ur du SIGE. CG-PRAASED-110-CS-CI-201 9 / Carte Scolaire- Recruteme Improving system performa Individual Consult nt d'un consultant internatio IDA / 58060 Post Open 80,000.00 0.00 Canceled 2019-08-13 2019-10-24 2019-10-01 2019-10-22 2019-11-26 2020-05-24 nce ant Selection nal pour l'appui à l'équipe ch argé de l'élaboration de la ca rte scolaire CG-PRAASED-111-CS-CI-201 9 / IGEPSA- Recrutement du consultant international pour Improving system performa Individual Consult le renforcement des capacité IDA / 58060 Post Open 60,000.00 0.00 Canceled 2019-08-15 2019-09-03 2019-10-03 2019-10-24 2019-11-28 2020-05-26 nce ant Selection s de l'IGEPSA: appui à la réda ction du manuel de procédur e d'inspection et d'encadrem ent pédagogique et formatio ns CG-PRAASED- 108 BIS-CS-CI- 2019 / INRAP- Recrutement d ’un consultant International p Improving system performa Individual Consult IDA / 58060 Post Open 20,000.00 30,150.18 Signed 2019-08-16 2019-10-31 2019-10-04 2020-03-27 2019-10-25 2020-08-10 2019-11-29 2020-08-11 2020-05-27 our une assistance a élaborat nce ant Selection ion d’une feuille de route et d ’un plan stratégique de l’INR AP Page 6 CG-PRAASED-107 BIS-CS-ED- 2019 / ENI/ENS - Recrutemen t d’un Consultant Internation Improving system performa Individual Consult IDA / 58060 Post Limited 40,000.00 0.00 Canceled 2019-08-15 2019-10-02 2019-08-20 2019-09-10 2019-10-15 2020-04-12 al pour une assistance a l’ela nce ant Selection boration d’une feuille de rout e et d’un plan strategique de ENI/ENS CG-PRAASED-112-CS-ED-201 9 / DFC - Contrat de service a vec M. BALONGA Moise ,Cons Improving system performa Individual Consult IDA / 58060 Post Direct 20,000.00 0.00 Canceled 2019-09-17 2019-10-01 2019-09-27 2019-10-18 2019-11-22 2020-05-20 ultant national en charge de l nce ant Selection 'assistance a élaboration d’u ne feuille de route et d’un pla n strategique de la DFC CG PRAASED-096-CS-CI-201 9 / Recrutement d'un consult ant international chargé d'ap Improving system performa Individual Consult pui au renforcement des cap IDA / 58060 Post Open 30,000.00 0.00 Canceled 2019-11-17 2020-01-05 2020-01-26 2020-03-01 2020-08-28 nce ant Selection acites des partie prenantes ( cabinet MEPSA, APE, ONGs...) sur la gestion de l'ecole, le m erite et la recevabilite. CG-PRAASED-0115-CS-IND-2 020 / - Contrat Coordo- Reno Improving system performa Individual Consult uvellement du contrat de ser IDA / 58060 Post Direct 174,000.00 0.00 Canceled 2020-01-15 2020-02-12 2020-01-25 2020-02-15 2020-02-15 2020-02-17 2020-03-21 2020-09-17 nce ant Selection vice du Coordonnateur de l'U nité de Coordination du Proje t PRAASED. CG-PRAASED-0113-CS-CI-20 19 / ENI-ENS/DFC : Recrutem ent d'un consultant internati onal chargé d'appuiaux équi Improving system performa Individual Consult IDA / 58060 Post Open 60,000.00 0.00 Canceled 2019-10-24 2019-11-14 2019-12-12 2020-01-02 2020-02-06 2020-08-04 pes techniques, à l'élaboratio nce ant Selection n des feuilles de route pour l a mise en oeuvre des recom mandations des études réalis ées ENI-ENS/DFC. CG-PRAASED-0117-CS-ED-20 20 / Feuille MEPSA-DDEPSA : Recrutement d’un consultant international chargé d’appui Improving system performa Individual Consult aux équipes techniques, à l’é IDA / 58060 Post Direct 40,000.00 0.00 Canceled 2020-03-11 2020-03-19 2020-03-21 2020-03-19 2020-04-11 2020-05-16 2020-11-12 nce ant Selection laboration des feuilles de rou tes et plans stratégiques pou r la mise en œuvre des reco mmandations des études réa lisées MEPSA –DDEPSA CG-PRAASED-0119-CS-CI-20 20 / Elaboration PPA: Recrute ment d'un consultant nationa Providing quality education f Individual Consult IDA / 58060 Post Open 40,000.00 16,613.49 Completed 2020-03-11 2020-03-13 2020-04-29 2020-06-12 2020-05-20 2020-08-10 2020-06-24 2020-08-15 2020-12-21 2021-07-31 l chargé de l’élaboration d’u or all ant Selection n plan d’action en faveur des populations autochtones du PRAAESD CG-PRAASED-0118-CS-ED-20 20 / FGB-COGES: Recruteme nt d'un consultant internatio Providing quality education f Individual Consult nal, spécialiste n formation, e IDA / 58060 Post Direct 50,000.00 113,489.30 Signed 2020-03-20 2020-03-18 2020-03-30 2020-03-19 2020-04-20 2020-09-29 2020-05-25 2020-10-01 2020-11-21 or all ant Selection n gestion à la base (FGB) pou r la mise en place des comité s de Gestion scolaire (COGES ) CG-PRAASED-0116-CS-ED-20 20 / ENI-ENS/DFC- Recruteme nt d’un consultant internatio Improving scope, quality an nal chargé d’appui aux équip Individual Consult IDA / 58060 d management of human re Post Direct 40,000.00 33,199.26 Signed 2020-03-20 2020-03-19 2020-03-30 2020-03-19 2020-04-20 2021-01-07 2020-05-25 2021-01-12 2020-11-21 es techniques, à l’élaboration ant Selection sources des feuilles de routes et plan s stratégiques pour la mise e n œuvre des recommandatio ns des études réalisées ENI-E NS/ DFC CG-PRAASED-103 BIS-CS-CI- Improving system performa Individual Consult 2019 / Auditeur Interne - Rec IDA / 58060 Post Open 122,222.00 0.00 Canceled 2019-08-16 2019-10-24 2019-10-04 2019-12-13 2019-10-25 2019-11-29 2020-05-27 nce ant Selection rutement d'un Auditeur Inter ne du PRAASED PRAASED-092-CS-CI-2019 / Recrutement du consultant i nternational pour l'appui tec Providing quality education f Individual Consult IDA / 58060 Post Open 140,000.00 0.00 Canceled 2019-04-25 2019-06-13 2019-06-13 2019-07-04 2019-08-08 2020-02-04 hnique au processus de révis or all ant Selection ion des curricula (évaluation et la réécriture) des program mes du primaire et du secon daire CG-PRAASED-123-CS-ED-202 1 / Carte scolaire Consul Int - Improving system performa Recrutement d'un consultant IDA / 58060 Post Direct Selection Direct 66,667.00 54,100.00 Completed 2021-06-15 2021-01-14 2021-06-25 2021-03-26 2021-08-29 2021-06-15 2022-02-25 2022-05-03 nce international en charge de l'é laboration de la carte scolair e du MEPSA CG-PRAASED-126-CS-ED-202 1 / Guides pedagogiques- Ac compagnement pour la suite du processus de revision des Providing quality education f curricula pour les classes de IDA / 58060 Post Direct Selection Direct 60,000.00 46,931.85 Signed 2021-06-21 2022-02-01 2021-07-01 2022-03-23 2021-09-04 2022-03-26 2022-03-03 or all ce1, ce2, cm1, cm2, 4eme et 3eme ainsi que la conception des guides et des cahiers d’a ctivites des programmes edu catifs revises pour le primair ee CG-PRAASED- -124-CS-INDV- 2021 / Carte scolaire Consul Nat - Recrutement d'un cons Improving system performa Individual Consult IDA / 58060 Post Open 2,000.00 12,188.88 Completed 2021-06-15 2021-01-14 2021-08-03 2021-04-12 2021-08-24 2021-04-30 2021-09-28 2021-06-15 2022-03-27 2022-05-03 ultant national pour appui au nce ant Selection consultant international en c harge de l'élaboration de la c arte scolaire du MEPSA. CG-PRAASED-0128-CS-INDV- 2021 / Formateurs nationaux . - Recrutement de 5 consult Improving scope, quality an ants nationaux chargés de l’é Individual Consult IDA / 58060 d management of human re Post Limited 20,000.00 0.00 Canceled 2021-08-27 2021-09-10 2021-09-01 2021-09-22 2021-10-27 2022-04-25 laboration du guide et outils ant Selection sources de formation des enseignant s et inspecteurs et de la form ation des formateurs au mani ement des nouveaux progra mmes Page 7 CG-PRAASED-0127-CS-INDV- 2021 / Graphiste - Recrutem ent d’un graphiste pour l’éla Improving system performa Individual Consult boration des guides illustres IDA / 58060 Post Limited 8,000.00 4,657.84 Signed 2021-08-23 2021-09-10 2021-08-28 2021-04-26 2021-09-18 2021-09-13 2021-10-23 2021-09-17 2022-04-21 nce ant Selection des 3 modules de formation en gestion a la base (FGB) du programme d’institutionnalis ation des COGES CG-PRAASED-0133-CS-INDV- 2021 / Formateur Sylvain MB UYAMBA - Recrutement d'un consultant international char Improving scope, quality an Individual Consult gé de l’élaboration du guide IDA / 58060 d management of human re Post Direct 15,000.00 14,193.58 Completed 2021-08-27 2021-09-09 2021-09-06 2021-09-08 2021-09-27 2021-09-13 2021-11-01 2021-09-26 2022-04-30 2022-05-03 ant Selection et outils de formation des en sources seignants et inspecteurs et d e la formation des formateur s au maniement des nouveau x programmes. CG-PRAASED-0131-CS-INDV- 2021 / Formateur KATSUNGA - Recrutement d'un consulta Improving scope, quality an nt international chargé de l’é Individual Consult IDA / 58060 d management of human re Post Direct 15,000.00 14,193.58 Completed 2021-08-27 2021-09-09 2021-09-06 2021-09-16 2021-09-27 2021-09-25 2021-11-01 2021-09-26 2022-04-30 2022-05-03 laboration du guide et outils ant Selection sources de formation des enseignant s et inspecteurs et de la form ation des formateurs au mani ement des nouveaux progra mmes. CG -PRAASED 0129-CS -INDI V-2021 / Formateur IBUTCH - Recrutement d'un consultant Improving scope, quality an international chargé de l’élab Individual Consult IDA / 58060 d management of human re Post Direct 15,000.00 14,193.58 Completed 2021-08-27 2021-09-10 2021-09-06 2021-09-09 2021-09-27 2021-09-13 2021-11-01 2021-09-26 2022-04-30 2022-05-03 oration du guide et outils de f ant Selection sources ormation des enseignants et inspecteurs et de la formatio n des formateurs au maniem ent des nouveaux programm es. CG-PRAASED-0130-CS-INDV- 2021 / Formateur NKONGOL O - Recrutement d'un consult Improving scope, quality an ant international chargé de l’ Individual Consult IDA / 58060 d management of human re Post Direct 15,000.00 14,193.58 Completed 2021-08-27 2021-09-09 2021-09-06 2021-09-08 2021-09-27 2021-09-13 2021-11-01 2021-09-26 2022-04-30 2022-05-03 élaboration du guide et outils ant Selection sources de formation des enseignant s et inspecteurs et de la form ation des formateurs au mani ement des nouveaux progra mmes. CG-PRAASED-0132-CS-INDV- 2021 / Formateur Roger MBO UYAMBA TSIUNZA - Recrutem ent d'un consultant internati Improving scope, quality an Individual Consult onal chargé de l’élaboration IDA / 58060 d management of human re Post Direct 15,000.00 14,193.58 Completed 2021-08-27 2021-09-09 2021-09-06 2021-09-16 2021-09-27 2021-09-13 2021-11-01 2021-09-26 2022-04-30 2022-05-03 ant Selection du guide et outils de formatio sources n des enseignants et inspect eurs et de la formation des fo rmateurs au maniement des nouveaux programmes. CG-PRAASED-0134-CS-INDV- 2021 / Animateurs AGC- FGB : Recrutement de 12 animate Improving system performa Individual Consult Under Implement IDA / 58060 Post Open 40,000.00 0.00 2021-09-14 2021-09-10 2021-11-02 2021-11-23 2021-12-28 2022-06-26 urs en gestion communautair nce ant Selection ation e pour accompagner les com munautés éducatives au nive au primaire. CG-PRAASED-0135-CS-INDV- 2021 / Formateurs FGB : Recr Improving system performa Individual Consult Under Implement IDA / 58060 Post Open 40,000.00 0.00 2021-09-14 2021-09-10 2021-11-02 2021-11-23 2021-12-28 2022-06-26 utement de 12 formateurs F nce ant Selection ation GB du niveau primaire CG-PRAASED-0136-CS-ED-20 21 / Editoriale CA- Recruteme nt d'un consultant pour l'app ui à la mise en conformité éd Providing quality education f itoriale des Cahiers d'activit IDA / 58060 Post Direct Selection Direct 100,000.00 23,924.06 Completed 2021-10-30 2021-11-05 2021-11-09 2021-11-04 2022-01-13 2021-11-11 2022-07-12 2022-02-27 or all és issus des nouveaux progr ammes éducatifs révisés, en deux phases (phase 1: CP1, CP2, 6è et 5è et phase 2 : C E1, CE2, CM1, CM2, 4è et 3è) CG-PRAASED-0138-CS-ED-20 21 / CA - YAZBECK- Recrutem ent d’une Assistance techniq Providing quality education f ue pour la mise en conformit IDA / 58060 Post Direct Selection Direct 6,560.00 5,670.00 Completed 2021-11-10 2021-11-11 2021-11-20 2021-11-09 2022-01-24 2021-11-11 2022-07-23 2022-07-09 or all é éditoriale des cahiers d’acti vités issus des nouveaux pro grammes éducatifs révisés d e CP1, CP2, 6ème et 5ème. CG-PRAASED-0139-CS-ED-20 21 / CA- TARCELIN- Recrutem ent d’une Assistance techniq Providing quality education f ue pour la mise en conformit IDA / 58060 Post Direct Selection Direct 3,570.00 3,395.40 Completed 2021-11-10 2021-11-11 2021-11-20 2021-11-10 2022-01-24 2021-11-11 2022-07-23 2021-12-16 or all é éditoriale des cahiers d’acti vités issus des nouveaux pro grammes éducatifs révisés d e CP1, CP2, 6ème et 5ème CG-PRAASED-0140-CS-ED-20 21 / CA- RENARD - Recrutem ent d’une Assistance techniq Providing quality education f ue pour la mise en conformit IDA / 58060 Post Direct Selection Direct 2,975.00 2,841.75 Completed 2021-11-10 2021-11-11 2021-11-20 2021-11-04 2022-01-24 2021-11-11 2022-07-23 2022-03-01 or all é éditoriale des cahiers d’acti vités issus des nouveaux pro grammes éducatifs révisés d e CP1, CP2, 6ème et 5ème. CG-PRAASED-0141-CS-ED-20 21 / CA- MIOLA- Recrutement d’une Assistance technique p Providing quality education f our la mise en conformité édi IDA / 58060 Post Direct Selection Direct 4,760.00 4,546.80 Completed 2021-11-10 2021-11-11 2021-11-20 2021-11-04 2022-01-24 2021-11-11 2022-07-23 2022-07-09 or all toriale des cahiers d’activités issus des nouveaux program mes éducatifs révisés de CP1 , CP2, 6ème et 5ème CG-PRAASED-0142-CS-ED-20 21 / CA- MILLET : Recruteme nt d’une Assistance techniqu e pour la mise en conformité Providing quality education f IDA / 58060 Post Direct Selection Direct 2,711.00 2,580.50 Completed 2021-11-10 2021-11-11 2021-11-20 2021-12-09 2022-01-24 2021-11-11 2022-07-23 2022-07-09 éditoriale des cahiers d’activi or all tés issus des nouveaux progr ammes éducatifs révisés de CP1, CP2, 6ème et 5ème (Ch ristian MILLET). Page 8 CG-PRAASED-0143- CS-ED-2 021 / CA-Gabrielle Debbas- R ecrutement d’une Assistance technique pour la mise en co Providing quality education f IDA / 58060 Post Direct Selection Direct 1,785.00 1,701.00 Completed 2021-11-10 2021-11-11 2021-11-20 2021-11-09 2022-01-24 2021-11-11 2022-07-23 2022-07-09 nformité éditoriale des cahier or all s d’activités issus des nouve aux programmes éducatifs ré visés de CP1, CP2, 6ème et 5 ème . CG-PRAASED -0144-CS-ED-2 021 / CA- GUGES : Recrutem ent d’une Assistance techniq Providing quality education f ue pour la mise en conformit IDA / 58060 Post Direct Selection Direct 7,615.00 7,250.88 Completed 2021-11-10 2021-11-11 2021-11-20 2021-11-08 2022-01-24 2021-11-11 2022-07-23 2022-07-09 or all é éditoriale des cahiers d’acti vités issus des nouveaux pro grammes éducatifs révisés d e CP1, CP2, 6ème et 5ème. CG-PRAASED-0145- CS-ED-2 021 / CA-DAUBIGNARD : Recr utement d’une Assistance te Providing quality education f chnique pour la mise en conf IDA / 58060 Post Direct Selection Direct 5,946.00 5,659.00 Completed 2021-11-10 2021-11-11 2021-11-20 2021-11-10 2022-01-24 2021-11-11 2022-07-23 2022-07-09 or all ormité éditoriale des cahiers d’activités issus des nouveau x programmes éducatifs révi sés de CP1, CP2, 6ème et 5è me. CG-PRAASED-0146-CS-ED-20 21 / CA-HORRENBERGER- Re crutement d’une Assistance t Providing quality education f echnique pour la mise en con IDA / 58060 Post Direct Selection Direct 3,211.00 3,046.95 Completed 2021-11-10 2021-11-11 2021-11-20 2021-11-10 2022-01-24 2021-11-11 2022-07-23 2022-07-09 or all formité éditoriale des cahiers d’activités issus des nouveau x programmes éducatifs révi sés de CP1, CP2, 6ème et 5è me. CG-PRAASED-0147-CS-ED-20 21 / CA- AYMARD : Recrutem ent d’une Assistance techniq Providing quality education f ue pour la mise en conformit IDA / 58060 Post Direct Selection Direct 7,615.00 6,820.20 Completed 2021-11-10 2021-11-10 2021-11-20 2021-11-04 2022-01-24 2021-11-11 2022-07-23 2022-07-09 or all é éditoriale des cahiers d’acti vités issus des nouveaux pro grammes éducatifs révisés d e CP1, CP2, 6ème et 5ème. CG-PRAASED-0150-CS-INDV- 2022 / IBUTCH Valère Renf. C apacités -Recrutement du co nsultant international du renf Improving scope, quality an Individual Consult orcement pour renforcement IDA / 58060 d management of human re Post Direct 11,581.00 9,212.87 Signed 2022-03-11 2022-03-17 2022-03-21 2022-03-25 2022-04-11 2022-03-25 2022-05-16 2022-04-14 2022-11-12 ant Selection du pool des formateurs et pe sources rsonnel d'encadrement en ch arge de la formation décentr alisée dans le maniement de s nouveau programmes (IBU TCH Valère). CG-PRAASED-0151CS-INDV- 2022 / Roger MBUYAMBA Ren f. Capacités- Recrutement du consultant international pour Improving scope, quality an Individual Consult le renforcement du pool des f IDA / 58060 d management of human re Post Direct 11,581.00 9,220.26 Signed 2022-03-11 2022-03-17 2022-03-21 2022-03-25 2022-04-11 2022-03-30 2022-05-16 2022-04-14 2022-11-12 ant Selection ormateurs et personnel d'enc sources adrement en charge de la for mation décentralisée dans le maniement des nouveau pro grammes éducatifs (MBUYAM BA Roger) ; CG-PRAASED-152-CS-INDV-2 022 / Sylvain MBUYAMBA Re nf. Capacités- Recrutement d u consultant international po Improving scope, quality an Individual Consult ur le renforcement du pool d IDA / 58060 d management of human re Post Direct 11,581.00 9,220.26 Signed 2022-03-11 2022-03-17 2022-03-21 2022-03-24 2022-04-11 2022-03-25 2022-05-16 2022-04-14 2022-11-12 ant Selection es formateurs et personnel d' sources encadrement en charge de la formation décentralisée dans le maniement des nouveau p rogrammes éducatifs (MBUY AMBA Sylvain) CG-PRAASED-0153-CS-INDV- 2022 / KATSUNGA Renf. Capa cités- Recrutement du consul tant international du renforce Improving scope, quality an Individual Consult ment du pool des formateurs IDA / 58060 d management of human re Post Direct 11,581.00 9,212.87 Signed 2022-03-11 2022-03-17 2022-03-21 2022-03-25 2022-04-11 2021-09-13 2022-05-16 2022-04-14 2022-11-12 ant Selection et personnel d'encadrement sources en charge de la formation dé centralisée dans le manieme nt des nouveau programmes éducatifs (KATSUNGA) CG-PRAASED-0154-CS-INDV- 2022 / NKONGOLO Renf. Cap acités - Recrutement du cons ultant international pour le re Improving scope, quality an Individual Consult nforcement du pool des form IDA / 58060 d management of human re Post Direct 11,581.00 9,212.87 Signed 2022-03-11 2022-03-17 2022-03-21 2022-03-25 2022-04-11 2022-03-24 2022-05-16 2022-04-14 2022-11-12 ant Selection ateurs et personnel d'encadr sources ement en charge de la forma tion décentralisée dans le ma niement des nouveau progra mmes éducatifs (NKONGOLO ) CG-PRAASED- 0155-CS-ED-2 022 / SIGE- ACSI - Mise en pl ace des modules 1, 2 et 4 (g estion des établissements, d Improving system performa Under Implement es ressources humaines et e IDA / 58060 Post Direct Selection Direct 350,000.00 0.00 2022-03-16 2022-03-17 2022-03-26 2022-05-30 2022-11-26 nce ation xamen et concours) du SIGE au sein du MEPPSA, avec l'a ppui de l'ACSI : Développeme nt, déploiement et et interfaç age à Stateduc de l’ISU. CG-PRAASED-0156-CS-ED -2 022 / SIGE ISU-Mise en place et opérationnalisation du mo dule 5 (Statistique et Aide à l Improving system performa Pending Impleme a décision) du SIGE-MEPPSA IDA / 58060 Post Direct Selection Direct 313,900.00 0.00 2022-03-21 2022-03-31 2022-06-04 2022-12-01 nce ntation avec l'assistance technique d e l'Institut de l'UNESCO (ISU) : mise en place, utilisation, in terfaçage avec les modules 1 ,2 et et 4 du SIGE, CG - PRAASED- 0160- CS-ED- 2022 / NDOUNGOU - Appui a u consultant international da Providing quality education f ns le cadre de la reecriture d IDA / 58060 Post Direct Selection Direct 12,510.00 11,147.99 Signed 2022-04-12 2022-03-23 2022-04-22 2022-03-07 2022-06-26 2022-04-09 2022-12-23 or all es programmes des classes CE1 àCM2 et 4ème a 3ème ( Consultant NDOUNGOU Jean Pierre) Page 9 CG-PRAASED- 0161-CS-ED-2 022 / NKOMBO - Appui au co nsultant international dans le Providing quality education f IDA / 58060 Post Direct Selection Direct 12,510.00 11,147.99 Signed 2022-04-12 2022-03-23 2022-04-22 2022-03-28 2022-06-26 2022-04-09 2022-12-23 cadre de la reecriture des pr or all ogrammes des classes CE1 a CM2 et 4ème a 3ème.(Cons ultant NKOMBO Edouard) CG-PRAASED-0162-CS-ED-20 22 / NDEBANI- Appui au cons ultant international dans le c Providing quality education f IDA / 58060 Post Direct Selection Direct 12,510.00 11,147.99 Signed 2022-04-12 2022-03-23 2022-04-22 2022-03-28 2022-06-26 2022-04-09 2022-12-23 adre de la reecriture des pro or all grammes des classes CE1 a CM2 et 4ème a 3ème.(Cons ultant NDEBANI François) CG-PRAASED-0163-CS-ED-20 22 / NZENZA- Appui au consu ltant international dans le ca Providing quality education f IDA / 58060 Post Direct Selection Direct 12,510.00 11,147.99 Signed 2022-04-12 2022-03-23 2022-04-22 2022-03-25 2022-06-26 2022-04-09 2022-12-23 dre de la reecriture des progr or all ammes des classes CE1 a CM 2 et 4ème a 3ème.(Consulta nt NZENZA Jacqueline) CG-PRAASED-0164-CS-ED-20 22 / DIANSATOU- Appui au c onsultant international dans l Providing quality education f IDA / 58060 Post Direct Selection Direct 12,510.00 11,139.08 Signed 2022-04-12 2022-03-23 2022-04-22 2022-03-28 2022-06-26 2022-04-09 2022-12-23 e cadre de la reecriture des p or all rogrammes des classes CE1 a CM2 et 4ème a 3ème.(DIA SANTOU Jonas) CG-PRAASED-0165-CS-ED-20 22 / MAZIKOU- Appui au cons ultant international dans le c Providing quality education f IDA / 58060 Post Direct Selection Direct 12,510.00 11,147.99 Signed 2022-04-12 2022-03-23 2022-04-22 2022-03-25 2022-06-26 2022-04-09 2022-12-23 adre de la reecriture des pro or all grammes des classes CE1 a CM2 et 4ème a 3ème.(MAZI KOU Aimé Hubert CG-PRAASED-0166-CS-ED-20 22 / Editoriale PE- Mise en co nformité éditoriale et de mis Providing quality education f IDA / 58060 Post Direct Selection Direct 32,000.00 7,575.12 Signed 2022-06-10 2022-06-23 2022-06-20 2022-06-23 2022-08-24 2022-06-11 2023-02-20 e en pages de 6 guides-progr or all ammes Congo, Français, Mat hs et sciences, CP1-CP2 et 6è me -5ème. CG-PRAASED-0167-CS-ED-20 22 / Editoriale PE Daubignard - Mise en conformité éditorial Providing quality education f IDA / 58060 Post Direct Selection Direct 5,800.00 5,392.01 Signed 2022-06-27 2022-06-27 2022-07-07 2022-06-22 2022-09-10 2022-06-11 2023-03-09 e et de mise en pages de 6 g or all uides-programmes Congo, Fr ançais, Maths et sciences, CP 1-CP2 et 6ème -5ème. CG-PRAASED-0168-CS-ED-20 22 / Editoriale PE Guges- Mis e en conformité éditoriale et Providing quality education f IDA / 58060 Post Direct Selection Direct 4,330.00 4,028.49 Signed 2022-06-27 2022-06-27 2022-07-07 2022-06-22 2022-09-10 2022-06-11 2023-03-09 de mise en pages de 6 guide or all s-programmes Congo, França is, Maths et sciences, CP1-CP 2 et 6ème -5ème. CG-PRAASED-0169-CS-ED-20 22 / Editoriale PE-2 - Assistan ce technique, pour la mise e n conformité éditoriale des n Providing quality education f Direct - Internation ouveaux programmes éducat IDA / 58060 Post Direct Selection 25,000.00 21,738.68 Signed 2022-08-19 2022-08-19 2022-08-29 2022-08-08 2022-11-02 2022-08-21 2023-05-01 or all al ifs et guides pédagogiques d e CP1-CP2 pour le français et les sciences du primaire et le s classes de 6è et 5è pour les SVT de collège (phase 2). CG-PRAASED-0170-CS-ED-20 22 / NDOUNGOU -Phase 2- A ppui au consultant internatio Providing quality education f nal dans le cadre de la reecri IDA / 58060 Post Direct Selection Direct - National 12,000.00 0.00 Signed 2022-10-04 2022-10-07 2022-10-14 2022-07-14 2022-12-18 2023-06-16 or all ture des programmes des cla sses CE1 a CM2 et 4ème a 3 ème.(NDOUNGOU Jean Pierre ), Phase 2. CG-PRAASED-0171-CS-ED-20 22 / NKOMBO- Phase 2 - App ui au consultant international Providing quality education f Under Implement IDA / 58060 Post Direct Selection Direct - National 12,000.00 0.00 2022-10-04 2022-10-07 2022-10-14 2022-07-14 2022-12-18 2023-06-16 dans le cadre de la reecriture or all ation des programmes des classes CE1 a CM2 et 4ème a 3ème. (NKOMBO Edouard), Phase 2 CG-PTAASED-0172-CS-ED-20 22 / NDEBANI-Phase 2- Appui au consultant international d Providing quality education f Under Implement ans le cadre de la reecriture IDA / 58060 Post Direct Selection Direct - National 12,000.00 0.00 2022-10-04 2022-10-07 2022-10-14 2022-08-29 2022-12-18 2023-06-16 or all ation des programmes des classes CE1 a CM2 et 4ème a 3ème (Consultant NDEBANI Françoi s), Phase 2. CG- PRAASED-0173-CS-ED-2 022 / NZENZA- Phase 2- App ui au consultant international Providing quality education f dans le cadre de la reecriture IDA / 58060 Post Direct Selection Direct - National 12,000.00 0.00 Signed 2022-10-04 2022-10-07 2022-10-14 2022-07-14 2022-12-18 2023-06-16 or all des programmes des classes CE1 a CM2 et 4ème a 3ème (NZENZA Jacqueline), Phase 2; CG-PRAASED-0175-SC-ED-20 22 / MAZIKOU- Phase 2- App ui au consultant international Providing quality education f Under Implement dans le cadre de la reecriture IDA / 58060 Post Direct Selection Direct - National 12,000.00 0.00 2022-10-04 2022-10-07 2022-10-14 2022-10-07 2022-12-18 2023-06-16 or all ation des programmes des classes CE1 a CM2 et 4ème a 3ème (MAZIKOU Aimé Hubert), pha se 2. CG-PRAASED-0174-CS-ED-20 22 / DIANSATOU -Phase 2- Ap pui au consultant internation Providing quality education f Under Implement al dans le cadre de la reecrit IDA / 58060 Post Direct Selection Direct - National 12,000.00 0.00 2022-10-04 2022-10-17 2022-10-14 2022-08-29 2022-12-18 2023-06-16 or all ation ure des programmes des clas ses CE1 a CM2 et 4ème a 3è me (DIASANTOU Jonas); Phas e 2; Page 10 CG-PRAASED-0178- CS-ED-2 022 / PNEAS- Convention ave c la CONFEMEN pour la mise Providing quality education f Direct - Internation Under Implement à disposition de 3 consultant IDA / 58060 Post Direct Selection 145,622.00 0.00 2022-11-15 2022-11-09 2022-11-25 2023-01-29 2023-07-28 or all al ation s chargés de l'enquête natio nale sur l'évaluation et le ren forcement des capacités des membres du PNEAS. CG-PRAASED -0179- CS-ED-2 022 / ISU- DEP- Convention a vec ISU (UNESCO), pour la fo Improving system performa Direct - Internation Under Implement rmation des agents de la DEP IDA / 58060 Post Direct Selection 70,632.00 0.00 2022-11-16 2022-11-09 2022-11-26 2023-01-30 2023-07-29 nce al ation dans le calcul des indicateurs requis pour l'analyse de la pe rformance du système éduca tif. CG-PRAASED-0180- CS-CI-20 22 / 12 Vérificateurs - Recrut ement de 12 consultants en Providing quality education f Individual Consult Pending Impleme charge de la vérification des IDA / 58060 Post Limited 70,632.00 0.00 2022-11-15 2022-11-20 2022-12-11 2023-01-15 2023-07-14 or all ant Selection ntation supports pédagogiques et m atériels didactiques distribué s par le PRAASED, dans les d épartements. CG-PRAASED-0181-CS-CI- 20 22 / LMD CI- Recrutement de Improving scope, quality an Individual Consult Open - Internationa Under Implement deux consultants internation IDA / 58060 d management of human re Post 108,200.00 0.00 2022-11-21 2022-11-16 2023-01-09 2023-01-30 2023-03-06 2023-09-02 ant Selection l ation aux en charge des contenus sources de formation en lien avec le s ysteme LMD . CG-PRAASED-0182- CS-CI-20 22 / LMD CN- Recrutement d Improving scope, quality an e deux consultants nationaux Individual Consult Under Implement IDA / 58060 d management of human re Post Open - National 52,500.00 0.00 2022-11-21 2022-11-16 2023-01-09 2023-01-30 2023-03-06 2023-09-02 en appui aux consultants inte ant Selection ation sources rnationaux en charge des co ntenus de formation en lien a vec le système LMD. CG-PRAASED- 0179-CS-ED-2 023 / PE CE1-CM, 4è-3è -Phas e1- Mise en conformité éditor Providing quality education f Direct - Internation iale des programmes éducati IDA / 58060 Post Direct Selection 48,462.00 0.00 Canceled 2023-01-12 2023-01-22 2023-03-28 2023-09-24 or all al fs et guides pédagogiques, Fr ançais, Maths et Sciences, de s classes de CE1-CE2, CM1-C M2, 4è-3è (phase1). CG-PRAASED-0180-CS-ED-20 23 / PE CE-CM,4è-3è- Mise en conformité éditoriale des pro Providing quality education f Direct - Internation grammes éducatifs et guides IDA / 58060 Post Direct Selection 90,000.00 0.00 Canceled 2023-01-31 2023-01-26 2023-02-10 2023-04-16 2023-10-13 or all al pédagogiques, Français, Mat hs et Sciences, des classes d e CE1-CE2, CM1-CM2, 4è-3è ( phase1). CG-PRAASED-0181-CS-ED-20 23 / PE+CA - CE-CM, 4è-3è -- Mise en conformité éditoriale des programmes éducatifs et Providing quality education f Direct - Internation Under Implement IDA / 58060 Post Direct Selection 172,500.00 0.00 2023-02-07 2023-02-07 2023-02-17 2023-01-16 2023-04-23 2023-10-20 guides pédagogiques en Fran or all al ation çais, Maths et Sciences, et de s cahiers d’activités des class es de CE1-CE2, CM1-CM2, 4è -3è (phase1+phase2), CG-PRAASED-0182-SC-ED-20 23 / Etats généraux- Recrute ment d’un consultant interna Improving scope, quality an Direct - Internation Under Implement tional dans le cadre de l’app IDA / 58060 d management of human re Post Direct Selection 17,500.00 0.00 2023-02-22 2023-02-23 2023-03-04 2023-05-08 2023-11-04 al ation ui du PRAASED aux etats gen sources eraux de l’education national e, de la formation et de la re cherche CG-PRAASED-0183-CS-ED-20 23 / Recrutement par entent Improving system performa Under Implement e avec l'ACSI pour le Dévelop IDA / 58060 Post Direct Selection Direct - National 240,276.00 0.00 2023-03-20 2023-03-22 2023-03-30 2023-06-03 2023-11-30 nce ation pement, la mise en place et l e déploiement du SIGE CG-PRAASED-0186-CS-ED-20 23 / Recrutement d’un consul tant international pour l’appu Improving system performa Direct - Internation Under Implement IDA / 58060 Post Direct Selection 5,708.00 0.00 2023-03-31 2023-05-05 2023-04-10 2023-06-14 2023-12-11 i thématique aux états génér nce al ation aux de l’éducation nationale, de la formation et de la rech erche CG-PRAASED-0187-CS-ED-20 23 / Recrutement d’un cabin Improving scope, quality an et d’expertise comptable pou Direct - Internation Under Implement IDA / 58060 d management of human re Post Direct Selection 16,336.00 0.00 2023-03-30 2023-04-06 2023-04-09 2023-06-13 2023-12-10 r l’audit des comptes du PRA al ation sources ASED pour les exercices 202 2 (exercice plein) et 2023 (cl os au 30 juin 2023) CG-PRAASED-0188-CS-ED-20 23 / Recrutement du consult Improving scope, quality an ant international pour le renf Direct - Internation Under Implement IDA / 58060 d management of human re Post Direct Selection 23,709.00 0.00 2023-04-03 2023-04-06 2023-04-13 2023-06-17 2023-12-14 orcement des capacités tech al ation sources nique des membres de l'équi pe du projet "assurance-quali té" CG-PRAASED-0190-CS-ED-20 Improving scope, quality an Direct - Internation Pending Impleme 23 / Convention avec l'ISU su IDA / 58060 d management of human re Post Direct Selection 72,500.00 0.00 2023-04-10 2023-04-20 2023-06-24 2023-12-21 al ntation r le calcul des indicateurs sources CG-PRAASED-0196-CS-ED-20 23 / Recrutement d’une agen ce n° 1 de paiement des part icipants à la formation décen Improving system performa Under Implement IDA / 58060 Post Direct Selection Direct - National 53,042.00 0.00 2023-04-17 2023-04-17 2023-04-27 2023-07-01 2023-12-28 tralisée des enseignants au nce ation maniement des nouveaux pr ogrammes éducatifs de CE1- CM2 et 4ème -3ème : Groupe ment MAOUENE CG-PRAASED-0197-CS-ED-20 23 / Recrutement de l’agenc e 1 de paiement des particip Improving system performa Under Implement ants à la formation décentrali IDA / 58060 Post Direct Selection Direct - National 83,702.00 0.00 2023-04-17 2023-04-17 2023-04-27 2023-07-01 2023-12-28 nce ation sée des enseignants au mani ement des nouveaux progra mmes éducatifs de CE1-CM2 et 4ème -3ème : EXPRESS U NION Page 11 CG-PRAASED-0202-CS-CI-20 23 / Recrutement d'un consul Individual Consult IDA / 58060 Unallocated Post Limited 192,730.00 0.00 Canceled 2023-05-08 2023-05-08 2023-05-13 2023-06-03 2023-07-08 2024-01-04 tant en charge de l'élaboratio ant Selection n du rapport d'achèvement d u PRAASED CG-PRAASED-0185BIS-CS-CI- 2023 / Recrutement de 12 vé Providing quality education f Individual Consult IDA / 58060 Post Limited 70,632.00 0.00 Canceled 2023-04-13 2023-04-18 2023-05-09 2023-06-13 2023-12-10 rificateurs indépendants des or all ant Selection supports pédagogiques distri bués CG-PRAASED-0203-CS-ED-20 23 / Recrutement de 12 vérifi cateurs indépendants de l’eff Providing quality education f Under Implement IDA / 58060 Post Direct Selection Direct - National 70,632.00 0.00 2023-05-24 2023-06-02 2023-06-03 2023-08-07 2024-02-03 ectivité de la distribution et u or all ation tilisation des programmes éd ucatifs et cahiers d’activités dans les 12 départements CG-PRAASED-0202BIS-CS-ED Improving scope, quality an -2023 / Recrutement d'un co Direct - Internation Under Implement IDA / 58060 d management of human re Post Direct Selection 43,772.00 0.00 2023-05-31 2023-05-31 2023-06-10 2023-08-14 2024-02-10 nsultant en charge de l'élabo al ation sources ration du rapport d'achèvem ent du PRAASED CG-PRAASED-0204-CS-ED-20 23 / Recrutement d’une micr ofinance devant assurer la pr Improving system performa Under Implement ise en charge des participant IDA / 58060 Post Direct Selection Direct - National 3,187.00 0.00 2023-06-01 2023-06-01 2023-06-11 2023-08-15 2024-02-11 nce ation s à la formation décentralisé e des directeurs d’établissem ents scolaires au leadership et au management PRAASED-007-C-CI / manuel Individual Consult IDA / V0020 Unallocated Prior Open 22,000.00 0.00 Canceled 2017-03-27 2017-05-15 2017-06-05 2017-07-10 2018-01-06 exécution ant Selection PRAASED-010-C-CI / CI prep Individual Consult IDA / V0020 Unallocated Prior Open 60,000.00 0.00 Canceled 2017-04-20 2017-06-08 2017-06-29 2017-08-03 2018-01-30 ation DAO matériel didactiqu ant Selection e Page 12 MINISTRY OF HEALTH Transforming Health Systems for Universal Care Project Project Procurement Plan Financial Year 2016/2017 IDA CREDIT No. 5836-KE GFF Grant Agreement TF0A2561 PHRD Grant Agreement TF0A2792 General 1. Project information: The Government of Kenya has applied for a Credit from the International Development Association supporting the Transforming Health Systems or Universal Care Project 2. Bank’s approval Date of the procurement Plan [Original::] 3. Date of General Procurement Notice: 4. Period covered by this procurement plan: 1st June, 2016 to 31st December, 2017 II. Goods and Works and Non-Consulting Services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Procurement Method Method Threshold Prior Review Threshold 1 ICB – Works ≥US$15 million ≥US$10 million 2 NCB- Works =USD 2 million; QCBS, QBS, < 300,000 FBS, LCS, Firms: All DS contracts >= Consultant CQS USD 1 million; s Others DS Individual Consultant: All contracts >=400 K; Others IC DS for individual consultant: All contracts>=USD 400 K Notes: QCBS: Quality- and Cost-Based Selection DS: Direct Selection QBS: Quality-Based Selection IC: Individual Consultant selection procedure FBS: Fixed Budget Selection NA: Not Applicable LCS: Least Cost Selection CQS: Consultants’ Qualifications-based Selection Consultancy Assignments with Selection Methods and Time Schedule: Procurement Plan Estimat Expect Expecte Contra ed Cost Review ed Procure d ct contract (USD: by Bank Contra Contract Name Description ment Proposal Period number 10 (Prior / ct Method Submiss (Month thousan Post) Signing ion Date ) d) Date CHONGQING Development of green and low carbon indicator system of Development of green and low carbon CQ- Chongqing and indicator system of Chongqing and Open+ CS- construction plan of construction plan of Chongqing for green 29 Nationa Post 2023.6 12 2023.9 01 Chongqing for green and smart platform based on carbon l+CQS and smart cloud peaking and carbon neutrality platform based on carbon peaking and carbon neutrality Pilot Evaluation of Green and Low CQ- Carbon Indicator Pilot Evaluation of Green and Low Carbon Open+ CS- System of Indicator System of Chongqing in "One 60 Nationa Post 2025.4 12 2025.7 02 Chongqing in "One Area and Two Clusters" l+QCBS Area and Two Clusters" Research on the CQ- Implementation Open+ Research on the Implementation Plan of CS- Plan of Carbon 141 Nationa Prior 2026.4 12 2026.7 Carbon Neutrality in Chongqing 03 Neutrality in l+QCBS Chongqing CQ- Natural capital Manual of natural capital accounting for Open+ CS- accounting and Bishan; empirical study of the natural 60 Nationa Post 2023.05 48 2023.6 04 biodiversity capital accounting for Bishan; baseline l+QCBS 8 Procurement Plan Estimat Expect Expecte Contra ed Cost Review ed Procure d ct contract (USD: by Bank Contra Contract Name Description ment Proposal Period number 10 (Prior / ct Method Submiss (Month thousan Post) Signing ion Date ) d) Date protection for survey of Bishan biodiversity index; Bishan District development of Bishan urban biodiversity index; integration of Bishan urban biodiversity in territorial space planning; urban biodiversity protection strategy for Bishan; and public awareness and outreach of urban biodiversity protection CQ- Open+ Bishan nature-based NBS for water for Bishan; and wind corridor CS- 70 Nationa Post 2023.05 48 2023.5 solutions (NBS) pilot control plan for Bishan 05 l+QCBS Formulation of green project handbook for Chongqing green finance services; CQ- Open+ approaches absorbing social capital to CS- Green finance 50 Nationa Post 2023.5 18 2023.6 participate in investing in green projects; 06 l+QCBS financing models development and implementation for demonstration projects Put forward the specific scheme of low- carbon design and transformation of old community buildings with mountain characteristics; put forward specific plans Pilot of near-zero for building low-carbon public service CQ- Open+ carbon transition of facilities and infrastructure; put forward CS- 80 Nationa Post 2023.5 24 2023.7 old communities - specific schemes to create a beautiful and 07 l+QCBS Yuzhong District livable community environment; put forward specific measures for the classification and recovery of domestic garbage; explore the low-carbon operation and management mode and long-term 9 Procurement Plan Estimat Expect Expecte Contra ed Cost Review ed Procure d ct contract (USD: by Bank Contra Contract Name Description ment Proposal Period number 10 (Prior / ct Method Submiss (Month thousan Post) Signing ion Date ) d) Date mechanism; explore and formulate supporting incentive measures for low- carbon construction investment and behavior guidance; guide the participation and consultation of the private sector Level monitoring indicator system of green and low-carbon synergetic development; capability assessment system of green and Assessment system low-carbon synergetic development; and implementation CQ- optimization of CCEC green and low- Open+ mechanism of CCEC 2023.6 CS- carbon synergetic development; 60 Nationa Post 2023.3 60 green and low- 08 construction of economic system of CCEC l+QCBS carbon synergetic green and low-carbon synergetic development development; integration of factor market for CCEC; and mechanism for value realization of ecological products in CCEC General framework design of net zero/ near-zero industrial park; development of net zero energy system construction CQ- Trans-regional net Open+ scheme for trans-regional net zero CS- zero industrial park 60 Nationa Post 2023.9 60 2023.12 industrial park; design of interconnection 09 construction action l+QCBS of every system in CCEC; design of professional and normalized trans-regional renewable energy recovery system CQ- Trans-regional net Technical supporting platform and Open+ CS- zero urban-rural certification system for green city; net zero Nationa Post 60 2023.9 60 2023.12 10 construction action building standard and certification system; l+QCBS design of general framework of net zero 10 Procurement Plan Estimat Expect Expecte Contra ed Cost Review ed Procure d ct contract (USD: by Bank Contra Contract Name Description ment Proposal Period number 10 (Prior / ct Method Submiss (Month thousan Post) Signing ion Date ) d) Date and near-zero rural areas; and net zero/near-zero carbon industrial planning for rural revitalization Handbook for mountains, river, forest, farmland, lake, grassland ecological Trans-regional CQ- restoration; handbook for trans-regional Open+ ecological CS- watershed pollution synergetic control 40 Nationa Post 2023.3 60 2023.6 environment 11 engineering; standard and guide for l+QCBS protection action contingency plan startup for heavy trans- regional pollution weather Policy toolkits for synergetic green Pilot action on development for central Sichuan and green, low-carbon Chongqing area; design of transformation CQ- and high-quality Open+ development mechanism for South CS- development in 180 Nationa Prior 2023.9 60 2023.12 Sichuan and West Chongqing area; design 12 adjacent areas of l+QCBS of ecological protection and development Sichuan and mechanism for East Chongqing and North Chongqing Sichuan area CQ- Open+ Project CS- 1 policy and planning expert 8 Nationa Post 2022.12 60 2023.2 management 15-1 l+ICS CQ- Open+ Project CS- 1 procurement expert 6 Nationa Post 2022.12 60 2023.2 management 15-2 l+ICS 11 Procurement Plan Estimat Expect Expecte Contra ed Cost Review ed Procure d ct contract (USD: by Bank Contra Contract Name Description ment Proposal Period number 10 (Prior / ct Method Submiss (Month thousan Post) Signing ion Date ) d) Date CQ- Open+ Project CS- 1 financial expert 3 Nationa Post 2022.12 60 2023.2 management 15-3 l+ICS CQ- 1 environmental and social expert Open+ Project CS- 3 Nationa Post 2022.12 60 2023.2 management 15-4 l+ICS CHENGDU 1. Develop green and low-carbon indicators that have the characteristics of a park city and the requirements of new human-centered urbanization, and clarify the source, connotation, Research and standards and boundaries of indicators, piloting for as well as work requirements strengthening high- 2. Formation of indicator guidelines and quality development monitoring and evaluation framework Open CD- frameworks with a for Chengdu's green and low-carbon +Intern development 140 Post 2022.4 48 2022.6 CS1 focus on promoting ational ecological, 3. Mid-term monitoring and evaluation of + QCBS biodiversity Chengdu’s green and low-carbon conservation and development level during the “14th carbon neutrality Five-Year Plan” period using indicator guidelines and evaluation frameworks 4. Suggestions on the preparation and index setting of the "15th Five-Year Plan" 5. Under the requirements of new urbanization, establish a green and low- 12 Procurement Plan Estimat Expect Expecte Contra ed Cost Review ed Procure d ct contract (USD: by Bank Contra Contract Name Description ment Proposal Period number 10 (Prior / ct Method Submiss (Month thousan Post) Signing ion Date ) d) Date carbon indicator system for metropolitan areas with cross-regional characteristics 6. Construct a guide for green and low- carbon development indicators in the Chengdu metropolitan area 7. Use the indicator system and indicator guide to conduct mid-term monitoring and evaluation of the implementation of the Chengdu Metropolitan Area Development Plan and the green and low-carbon development of the Chengdu Metropolitan Area 8. Put forward opinions and suggestions on the green and low-carbon development of Chengdu metropolitan area. 9. Relying on the Chengdu City Smart Management Platform (City Brain) to build a "dual carbon" sharing platform 10.According to the main carbon emission sources in Chengdu, classify and integrate urban management and monitoring data 11.Develop green and low-carbon development indicators comparison, trend analysis, abnormal monitoring and early warning and other functions 12.Standardize the data sharing process and mechanism for green and low- 13 Procurement Plan Estimat Expect Expecte Contra ed Cost Review ed Procure d ct contract (USD: by Bank Contra Contract Name Description ment Proposal Period number 10 (Prior / ct Method Submiss (Month thousan Post) Signing ion Date ) d) Date carbon development, and promote the interconnection and data sharing of information systems of municipal departments and institutions. 13.Based on the development status and trend of Chengdu industrial parks (functional zones), carrying out the construction of green and low-carbon development index of parks (functional zones). 14.Based on index construction, selecting typical parks (functional zone) for evaluation, and regularly publish evaluation results. 15.According to the evaluation report, carrying out the selection and promotion of excellent green and low- carbon development cases of industrial parks (functional zones), and forming a number of typical cases. 16.Carry out research on green, low- carbon and circular development of industrial parks (functional zoness) in metropolitan areas 17.Carry out the research and design of the circular transformation of industrial parks (one industrial park in Deyang, Meishan and Ziyang will be selected as a pilot) 14 Procurement Plan Estimat Expect Expecte Contra ed Cost Review ed Procure d ct contract (USD: by Bank Contra Contract Name Description ment Proposal Period number 10 (Prior / ct Method Submiss (Month thousan Post) Signing ion Date ) d) Date 1. Focusing on Chengdu wetlands, actively carrying out biodiversity surveys and formulating Chengdu wetland biodiversity assessment reports. Chengdu Wetland 2. In response to the problems assessed Biodiversity Survey, in the report, highlight the unique Ecological natural features of Chengdu and the Restoration, ecological barrier characteristics of the Biodiversity upper reaches of the Yangtze River, Management and formulate ecological restoration Open System Research, guidelines based on natural solutions CD- +Intern andTuojiang (NBS). 130 Post 2023.7 48 2023.9 CS2 ational Comprehensive 3. Formulate specific restoration plans for + QCBS Management the Minshan L population and Strategic Daxiangling B population in the Framework and Chengdu metropolitan area of the Giant Method Panda National Park, and make Optimization and professional plans for restoration Improvement Plan methods, restoration areas, and restoration timing. 4. Carry out wetland biodiversity monitoring, and establish a wetland biodiversity management system 15 Procurement Plan Estimat Expect Expecte Contra ed Cost Review ed Procure d ct contract (USD: by Bank Contra Contract Name Description ment Proposal Period number 10 (Prior / ct Method Submiss (Month thousan Post) Signing ion Date ) d) Date 1. Assess the quality of the giant panda habitat in the Chengdu area of the Giant Panda National Park, formulate a systematic ecological restoration plan, and make professional plans for restoration sites, restoration areas, CD- Ecological restoration methods, restoration timing, Open CS3 restoration plan for etc. +Intern 160 Post 2023.10 24 2023.12 Chengdu Giant 2. Formulate specific restoration plans for ational Panda Habitat the Minshan L population and + QCBS Daxiangling B population in the Chengdu metropolitan area of the Giant Panda National Park, and make professional plans for restoration methods, restoration areas, and restoration timing. Wetland Biodiversity Select wetlands to install monitoring CD- facilities. Monitoring 30 RFQ Post 2024.3 6 2024.5 GD1 Equipment 1. In view of the characteristics of Chengdu's large population growth, rapid economic development, low per Research and capita carbon emission level, and Open CD- Piloting for Carbon relatively clean energy structure, +Intern 60 Post 2023.3 36 2023.5 CS4 Neutrality Roadmap dealing with the contradiction between ational and Green Finance development and carbon reduction + QCBS based on overall planning, solving the problem of continuous carbon reduction at lower carbon emission levels, 16 Procurement Plan Estimat Expect Expecte Contra ed Cost Review ed Procure d ct contract (USD: by Bank Contra Contract Name Description ment Proposal Period number 10 (Prior / ct Method Submiss (Month thousan Post) Signing ion Date ) d) Date developing a roadmap to peak carbon neutrality. 2. Analyze different types of green projects, revenue sources and business models in the private sector, and sort out the main products and paths of green finance. 3. According to the characteristics of different projects, select and match appropriate financing models, and carry out green financing model pilot projects in the fields of giant panda national park ecological restoration, green and low-carbon transformation of functional zones, and urban renewal and transformation. 1. Analyze different types of green projects, revenue sources and business models in the private sector, and sort out the main products and paths of Guidelines and green finance. Piloting for Green 2. According to the characteristics of Open CD- and Low-Carbon different projects, select and match +Intern 100 Post 2023.10 24 2023.12 CS5 Transformation of appropriate financing models, and carry ational Communities in out green financing model pilot projects + QCBS Chengdu in the fields of giant panda national park ecological restoration, green and low-carbon transformation of functional zones, and urban renewal and transformation. 17 Procurement Plan Estimat Expect Expecte Contra ed Cost Review ed Procure d ct contract (USD: by Bank Contra Contract Name Description ment Proposal Period number 10 (Prior / ct Method Submiss (Month thousan Post) Signing ion Date ) d) Date Project Management Open CD- Support for project management and and Procurement 10 +Natio Post 2022.12 48 2023.1 IC1 procurement during implementation phase Management Experts nal+ IC Technical Experts Open CD- Technical Support for Carbon Neutralization (Carbon +Natio Post IC2 and Green Development during 5 2022.12 48 2023.1 Neutralization and nal+ IC implementation phase Green Development) Technical Specialist Open CD- Technical Support for Biodiversity and (Biodiversity and 5 +Natio Post 2022.12 48 2023.1 IC3 Wetlands during implementation phase Wetlands) nal+ IC NINGBO 1. To establish green and high-quality development indicators  Theoretical research and policy interpretation  Conduct international case studies and analyze the current situation Open Study on Indicator  Establish indicator system and +Intern NB- system of Green evaluation model ational CS- High-quality 2. To proposing a monitoring and 40 Post 2023.06 46 2023.08 + 1.1 Development in evaluation framework for the green and QCBS/Q Ningbo City low carbon development in Ningbo BS 3. Use the framework to conduct mid-term monitoring and evaluation on the implementation of the 14th five-year plan. 4. To make suggestions on the preparation of the 15th Five-Year Plan 18 Procurement Plan Estimat Expect Expecte Contra ed Cost Review ed Procure d ct contract (USD: by Bank Contra Contract Name Description ment Proposal Period number 10 (Prior / ct Method Submiss (Month thousan Post) Signing ion Date ) d) Date and its indicators setting. 1. To survey the natural assets and analyzing ecosystem services of the natural assets in Ninghai Open Pilot Project of Blue 2. To conduct natural capital accounting +Intern NB- and Green Natural for the County ational CS- 90 Post 2023.08 44 2023.10 Assets Accounting 3. To explore the realization of ecological + 2.1 in Ninghai County product value and the transformation QCBS/Q path from GEP to GDP BS 4. To formulate strategic plans for Ninghai ecological space Study on the 1. To conduct baseline surveys and Open NB- Strategy of assessments of the biodiversity in +Intern CS- Biodiversity Ningbo 100 ational Post 2023.07 45 2023.09 2.2 Conservation in 2. To develop a strategy plan of + Ningbo City biodiversity conservation QCBS/Q 19 Procurement Plan Estimat Expect Expecte Contra ed Cost Review ed Procure d ct contract (USD: by Bank Contra Contract Name Description ment Proposal Period number 10 (Prior / ct Method Submiss (Month thousan Post) Signing ion Date ) d) Date 3. To develop a monitoring framework for BS biodiversity and a biodiversity index. 4. Display the results of biodiversity baseline investigation and dynamic monitoring on the “Beautiful Ningbo” map 1. To undertake studies and modeling Study on the Road Open NB- work to formulate a roadmap for visions Map to Carbon +Intern CS- toward carbon neutrality and timeframe Neutrality in Ningbo 50 ational+ Post 2023.07 30 2023.09 2.3 2. To conduct consultations with various City QCBS/Q agencies as well as public on the BS roadmap 1. To prepare a implementation plan for the platform  Background surveys and policy interpretation  Overall design of the platform  Task breakdown  Investment estimation for the Ningbo Construction Open NB- platform development Industry Double- +Intern CS- 2. To develop the platform, sub-modules Carbon Smart 80 ational+ Post 2023.07 45 2023.09 2.4 and tools. Service Platform QCBS/Q  Special planning sub-module (new) BS  Energy saving evaluation sub-module (upgrade existing system)  Construction Drawing Review Sub- module (Upgrade existing system)  Green Building Identification Sub- Module (Upgrade existing system)  Green Building Materials 20 Procurement Plan Estimat Expect Expecte Contra ed Cost Review ed Procure d ct contract (USD: by Bank Contra Contract Name Description ment Proposal Period number 10 (Prior / ct Method Submiss (Month thousan Post) Signing ion Date ) d) Date Management Sub-module (New)  As-built energy efficiency evaluation sub-module (upgrade existing system)  Energy consumption online monitoring sub-module (upgrade existing system)  Existing Building Renovation Sub- module (New Construction)  Green Finance Sub-module (New)  Social Supervision Sub-module (New)  Supporting function sub-module (new) 3. To compile supporting policies for double-carbon digitalization and intelligent development of the construction industry  To analyze the status of double- carbon digitalization and intelligent development of the construction industry  To propose solutions to the difficulties of double-carbon digitalization and intelligent development in the construction industry  To formulate supporting policies to promote double-carbon digitalization and intelligent development of the construction industry 21 Procurement Plan Estimat Expect Expecte Contra ed Cost Review ed Procure d ct contract (USD: by Bank Contra Contract Name Description ment Proposal Period number 10 (Prior / ct Method Submiss (Month thousan Post) Signing ion Date ) d) Date Conceptual Design 1. To formulate NBS strategy for Ninghai Open NB- water system Project with Nature- +Intern CS- 2. To provide NBS design options for the 40 Post 2023.12 24 2024.02 Based Solutions in ational 2.5 selected site in Ninghai based on a set Ninghai County + QCBS of criteria in annex 1. To Help three local city commercial banks with corporate headquarters in Ningbo (Bank of Ningbo, Ningbo Commerce Bank, Donghai Bank) to establish and improve green financial business, establish due diligence, rating, data collection and analysis mechanisms, effectively improve energy efficiency, decarbonize and Study on Green sequester carbon and the ability to Open NB- Financial Products identify projects such as renewable +Intern CS- and Innovation of energy utilization. 60 ational+ Post 2023.07 24 2023.9 2.6 Green Financial 2. Investigate projects in the fields of QCBS/Q Model carbon reduction and biodiversity in BS Ningbo, and form a list of investment and financing projects to adapt to climate change and promote biodiversity 3. Form independent financial product and financial model evaluation reports for typical demonstration projects, and form investment and financing empirical cases 4. Develop green financial products and 22 Procurement Plan Estimat Expect Expecte Contra ed Cost Review ed Procure d ct contract (USD: by Bank Contra Contract Name Description ment Proposal Period number 10 (Prior / ct Method Submiss (Month thousan Post) Signing ion Date ) d) Date green financial model manuals 1. Design of the low-carbon/net-zero carbon renewal scheme in the pilot area  Investigation on the development status and economic indicators of the pilot area Study and pilot on  Carry out feasibility analysis of key Urban Renewal scene placement in combination with Open NB- Technology based future communities; +Intern CS- 60 Post 2024.01 24 2024.3 on the concept of  Overall design of low-carbon/net-zero ational+ 2.7 low carbon/net zero carbon emission transformation CQS carbon emissions scheme;  Deepening design of special scheme 2. To explore low-carbon/net-zero carbon urban renewal technologies 3. To build a low-carbon/net-zero carbon community evaluation indicator system 23 Procurement Plan Estimat Expect Expecte Contra ed Cost Review ed Procure d ct contract (USD: by Bank Contra Contract Name Description ment Proposal Period number 10 (Prior / ct Method Submiss (Month thousan Post) Signing ion Date ) d) Date Expert of Open+ NB- Environment 5 Nationa Post 2023.02 51 2023.03 IC1 Safeguard l+ICS Open+ NB- Expert of Social 5 Nationa Post 2023.02 51 2023.03 IC2 Safeguard l+ICS Technical Expert of Open+ NB- Low Cabon and 3 Nationa Post / 52 2023.02 IC3 Green Development l+ICS Expert of Project Open+ NB- Management/ 14 Nationa Post / 51 2023.03 IC4 Contract l+ICS Management Open+ NB- Project Translator 1 Nationa Post / 51 2023.03 IC5 l+ICS 24 PROCUREMENT China : GEF7: Green and Carbon Neutral Cities PLAN General Information Country: China 2023-04-03 Bank’s Approval Date of the Original Procurement Plan: 2023-06-01 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P173316 GPN Date: 2022-11-14 Project Name: GEF7: Green and Carbon Neutral Cities Loan / Credit No: TF / B8386 GEF7 Ningbo Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 3. Support knowledge sharin Individual Consult Under Implement NB-IC5 / Project Translator TF / B8386 g, capacity building, and pro Post Open - National 10,000.00 0.00 2023-04-06 2023-04-04 2023-04-24 2023-04-27 2023-05-01 2027-06-30 ant Selection ation ject management 3. Support knowledge sharin NB-IC2 / Expert of Social Saf Individual Consult Under Implement TF / B8386 g, capacity building, and pro Post Open - National 25,000.00 0.00 2023-04-06 2023-04-04 2023-04-24 2023-04-27 2023-05-01 2027-06-30 eguard ant Selection ation ject management 3. Support knowledge sharin NB-IC1 / Expert of Environm Individual Consult Under Implement TF / B8386 g, capacity building, and pro Prior Open - National 25,000.00 0.00 2023-04-06 2023-04-05 2023-04-24 2023-04-27 2023-05-01 2027-06-30 ent Safeguard ant Selection ation ject management 3. Support knowledge sharin NB-IC4 / Expert of Project Ma Individual Consult Under Implement TF / B8386 g, capacity building, and pro Post Open - National 60,000.00 0.00 2023-04-21 2023-05-17 2023-06-06 2023-06-09 2023-06-16 2025-06-15 nagement ant Selection ation ject management NB-IC3 / Technical Expert of 3. Support knowledge sharin Individual Consult Pending Impleme Low Cabon and Green Develo TF / B8386 g, capacity building, and pro Post Open - National 30,000.00 0.00 2023-06-04 2023-06-25 2023-06-30 2023-07-02 2025-06-30 ant Selection ntation pment ject management Page 1 PROCUREMENT PLAN (Textual Part) Project information: Cabo Verde Human Capital Project - P175828 Implementation agency: UGPE (Unidade de Gestão de Projetos Especiais) Date of the Procurement Plan: March 22, 2022 Period covered by this Procurement Plan: March 22, 2022 - August 21, 2023 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. “Not Applicable” Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: is not applicable for those contracts identified in the Procurement Plan tables; Works: is not applicable for those contracts identified in the Procurement Plan tables Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations is Applicable. “Not Applicable” Other Relevant Procurement Information. Retroactive Financing used shall be consistent with Sections I, II and III of these Procurement Regulations and within the limits specified in the Legal Agreement. PROCUREMENT Cabo Verde : Cabo Verde Human Capital Project PLAN General Information Country: Cabo Verde 2022-06-07 Bank’s Approval Date of the Original Procurement Plan: 2023-06-01 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P175828 GPN Date: Project Name: Cabo Verde Human Capital Project Loan / Credit No: IDA / 70780 Unidade de Gestao de Projectos Especiais Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned 19/HCP/UGPE/2023 / Rehabil Strengthen access to basic s itation works on houses in Ca ervices and social and produ Request for Quota Single Stage - One E Other (with field f Under Imple 2023-08-3 IDA / 70780 Post Limited 190,000.00 0.00 2023-01-06 2023-01-23 2023-03-03 labaceira neighbourhood, Pra ctive inclusion of poor and v tions nvelope or explanation) mentation 0 ia - Lot IV and Lot V ulnerable 20/HCP/UGPE/2023 / Rehabil Strengthen access to basic s Request for Quota Single Stage - One E Other (with field f Under Imple 2023-08-3 itation works on houses in Sa IDA / 70780 ervices and social and produ Post Limited 80,000.00 0.00 2023-01-06 2023-01-23 2023-03-03 tions nvelope or explanation) mentation 0 fende neighbourhood, Praia - ctive inclusion of poor and v Lot I ulnerable 21/HCP/UGPE/2023 / Rehabil Strengthen access to basic s Request for Quota Single Stage - One E Other (with field f Under Imple 2023-08-3 itation works on houses in Sa IDA / 70780 ervices and social and produ Post Limited 170,000.00 0.00 2023-01-06 2023-01-23 2023-03-03 tions nvelope or explanation) mentation 0 fende neighbourhood, Praia - ctive inclusion of poor and v Lot II and Lot III ulnerable GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 30/HCP/UGPE/2023 / Purcha se of equipment for 22 Multi media Centres for Distance L Support education system re earning (EAD) in 22 municipa forms to better prepare in-sc Single Stage - One E Pending Impl IDA / 70780 Post Request for Bids Open - National 150,000.00 0.00 2023-07-31 2023-08-05 2023-09-13 2023-10-13 2023-11-17 2024-05-15 lities across the country (Aqu hool youth for future employ nvelope ementation isição de equipamentos mobi ment liários para 22 Centros Multi média de Formação à Distan cia (EAD) nos 22 concelhos d o país) 24/HCP/UGPE/2023 / Equipm Improve access to labor mar Request for Quota Single Stage - One E ent for EMAR courses on boat IDA / 70780 ket relevant professional trai Post Open - National 40,000.00 0.00 Canceled 2023-02-12 2023-04-09 2023-10-06 tions nvelope repair ning for youth and women 16/HCP/UGPE/2022 / Purcha Support education system re Request for Quota Single Stage - One E Pending Impl se of IT equipment for 22 dist IDA / 70780 forms to better prepare in-sc Post Open - National 100,000.00 0.00 2023-09-05 2023-10-31 2024-04-28 tions nvelope ementation ance media training centers i hool youth for future employ n 22 municipalities ment NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 03/HCP/UGPE/2022 / Technic Support education system re al assistance for the elaborat forms to better prepare in-sc Open - Internationa Single Stage - One E Under Imple ion/editing of textbooks and i IDA / 70780 Post Request for Bids 600,000.00 0.00 2022-05-18 2022-08-10 2022-05-23 2022-08-10 2022-07-04 2022-08-03 2022-09-07 2023-03-06 hool youth for future employ l nvelope mentation nteractive resources associat ment ed with all 9th grade second ary school Strengthen access to basic s 09/HCP/UGPE/2022 / Purcha Direct - Internation Under Imple IDA / 70780 ervices and social and produ Post Direct Selection 20,000.00 0.00 2022-09-01 2022-09-16 2022-09-06 2022-09-16 2022-10-11 2023-10-11 se software licenses for CSU al mentation ctive inclusion of poor and v ulnerable 10/HCP/UGPE/2022 / Video r Support education system re Request for Quota Single Stage - One E Under Imple ecording and editing in the cl IDA / 70780 forms to better prepare in-sc Post Open - National 15,000.00 0.00 2022-10-17 2022-12-12 2023-02-10 tions nvelope mentation assroom as part of "TEACH P hool youth for future employ RIMARY ment 17.2/HCP/UGPE/2023 / Seleç Support education system re ão de uma Gráfica para impr forms to better prepare in-sc Request for Quota Single Stage - One E Pending Impl essão de provas para a AVAL IDA / 70780 Post Limited 80,000.00 0.00 2023-07-01 2023-08-26 2024-02-22 hool youth for future employ tions nvelope ementation IAÇÃO AFERIDA 2023 (Selecti ment on of a Printing House to prin t tests) 39/HCP/UGPE/2023 / Assista nce for "Emergency tempora ry accommodation for interv Strengthen access to basic s ention beneficiaries under su ervices and social and produ Under Imple b-component 3.3: partnershi IDA / 70780 Post Direct Selection Direct - National 15,000.00 0.00 2023-07-31 2023-06-16 2023-08-05 2023-09-09 2024-03-07 ctive inclusion of poor and v mentation p with Red Cross CV (Assistê ulnerable ncia para “Alojamento tempo rário de emergência para be neficiários de intervenção no âmbito da subcomponente 3. 3 45/HCP/UGPE/2023 / Recruit Strengthen access to basic s ment of a firm to develop co ervices and social and produ Request for Quota Single Stage - One E Pending Impl mmunication materials (recr IDA / 70780 Post Open - National 88,000.00 0.00 2023-10-04 2023-11-29 2024-05-27 ctive inclusion of poor and v tions nvelope ementation utamento de uma Firma para ulnerable desenvolver materiais de co municação) CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 04/HCP/UGPE/2022 / Develo pment of Financial and Accou nting Audits for the Least Cost Selecti Open - Internationa Under Implement Cabo Verde Human Capital P IDA / 70780 Project Management Post 36,000.00 0.00 2022-05-18 2022-08-22 2022-06-08 2022-09-28 2022-07-22 2022-08-19 2022-09-18 2022-10-23 2022-11-27 2023-05-26 on l ation roject a the Resilient Tourism and Blue Economy Developm ent Project for fiscal years 20 22, 2023 and 2024. Page 1 22/HCP/UGPE/2023 / Consult ancy to support the Ministry Improve access to labor mar of Education in drafting the L Consultant Qualifi Open - Internationa Under Implement IDA / 70780 ket relevant professional trai Post 150,000.00 0.00 2023-02-01 2023-02-22 2023-04-07 2023-05-07 2023-06-11 2023-12-08 aw for Financing Higher Educ cation Selection l ation ning for youth and women ation and in adapting the Hig her Education Legislation in Cabo Verde 28/HCP/UGPE/2023 / Technic Support education system re al Assistance for the preparat forms to better prepare in-sc Consultant Qualifi Open - Internationa Under Implement ion and validation of the Prog IDA / 70780 Post 300,000.00 0.00 2023-02-16 2023-02-20 2023-03-09 2023-03-24 2023-04-22 2023-05-22 2023-06-26 2024-06-25 hool youth for future employ cation Selection l ation rammes for the 11 grade sec ment ondary school subjects/Cabo Verde 26/HCP/UGPE/2023 / Technic al Assistance for the elaborat ion and validation of the Prog Support education system re rammes, associated to 12th forms to better prepare in-sc Quality And Cost- Open - Internationa Under Implement IDA / 70780 Prior 2,800,000.00 0.00 2023-02-15 2023-03-15 2023-03-08 2023-05-04 2023-04-21 2023-05-19 2023-06-18 2023-07-23 2023-08-27 2024-08-26 grade subjects & edition of te hool youth for future employ Based Selection l ation xtbooks and interactive reso ment urces, associated to 10th, 11 th and 12th grade subjects of secondary education/Cabo V erde 07/HCP/UGPE/2022 / Technic Support education system re al assistance for Aferida II an forms to better prepare in-sc Quality And Cost- Open - Internationa IDA / 70780 Post 200,000.00 0.00 Canceled 2022-07-29 2022-08-22 2022-08-19 2022-10-13 2022-10-02 2022-10-30 2022-11-29 2023-01-03 2023-02-07 2024-02-07 d capacity building activities hool youth for future employ Based Selection l for assessment staff ment 34.1/HCP/UGPE/2023 / LOT 1 - Contratação de ONG para a poiar no acompanhamento d Strengthen access to basic s os beneficiários do Programa ervices and social and produ Consultant Qualifi Pending Impleme IDA / 70780 Post Open - National 75,000.00 0.00 2023-07-31 2023-08-21 2023-10-04 2023-11-03 2023-12-08 2024-06-05 de Inclusão Produtiva (S. Vic ctive inclusion of poor and v cation Selection ntation ente, Porto Novo, Ribeira Gra ulnerable nde, Paul)(NGOs to help moni tor the beneficiaries of the Pr oductive Inclusion Programm e) 34.2/HCP/UGPE/2023 / LOT 2 - Contratação de ONG para a poiar no acompanhamento d Strengthen access to basic s os beneficiários do Programa ervices and social and produ Consultant Qualifi Pending Impleme IDA / 70780 Post Open - National 47,000.00 0.00 2023-07-31 2023-08-21 2023-10-04 2023-11-03 2023-12-08 2024-06-05 de Inclusão Produtiva (Sal, Ri ctive inclusion of poor and v cation Selection ntation beira Brava, Tarrafal SN, Boa ulnerable Vista) (NGOs to help monitor the beneficiaries of the Produ ctive Inclusion Programme) 34.3/HCP/UGPE/2023 / LOT 3 - Contratação de ONG para a poiar no acompanhamento d Strengthen access to basic s os beneficiários do Programa ervices and social and produ Consultant Qualifi Pending Impleme IDA / 70780 Post Open - National 67,000.00 0.00 2023-07-31 2023-08-21 2023-10-04 2023-11-03 2023-12-08 2024-06-05 de Inclusão Produtiva (S. Filip ctive inclusion of poor and v cation Selection ntation e, Mosteiros, S. Catarina Fog ulnerable o, Brava) (NGOs to help moni tor the beneficiaries of the Pr oductive Inclusion Programm e) 34.5/HCP/UGPE/2023 / LOT 5 - Contratação de ONG para a poiar no acompanhamento d Strengthen access to basic s os beneficiários do Programa ervices and social and produ Consultant Qualifi Under Implement de Inclusão Produtiva (Santa IDA / 70780 Post Limited 77,000.00 0.00 2023-06-30 2023-06-05 2023-07-14 2023-08-13 2023-09-17 2024-03-15 ctive inclusion of poor and v cation Selection ation Cruz, S. Lourenço dos Órgãos ulnerable , Salvador do Mundo) (NGOs to help monitor the beneficia ries of the Productive Inclusio n Programme) 34.6/HCP/UGPE/2023 / LOT 6 - Contratação de ONG para a poiar no acompanhamento d Strengthen access to basic s os beneficiários do Programa ervices and social and produ Consultant Qualifi Under Implement IDA / 70780 Post Limited 61,000.00 0.00 2023-06-30 2023-06-05 2023-07-14 2023-08-13 2023-09-17 2024-03-15 de Inclusão Produtiva (Tarraf ctive inclusion of poor and v cation Selection ation al, S. Miguel, Santa Catarina) ulnerable (NGOs to help monitor the be neficiaries of the Productive I nclusion Programme) 35.1/HCP/UGPE/2023 / Lote 1 - Contratação Entidades Fo rmadoras para implementaçã Strengthen access to basic s o de formações e atividades ervices and social and produ Consultant Qualifi Pending Impleme IDA / 70780 Post Open - National 75,000.00 0.00 2023-07-31 2023-08-21 2023-10-04 2023-11-03 2023-12-08 2024-06-05 de apoio à Inclusão Produtiva ctive inclusion of poor and v cation Selection ntation (S. Antão, S. Vicente) (Trainin ulnerable g Entities to implement traini ng and support activities for Productive Inclusion) 35.2/HCP/UGPE/2023 / Lote 2 - Contratação Entidades Fo rmadoras para implementaçã Strengthen access to basic s o de formações e atividades ervices and social and produ Consultant Qualifi Pending Impleme IDA / 70780 Post Open - National 47,000.00 0.00 2023-07-31 2023-08-21 2023-10-04 2023-11-03 2023-12-08 2024-06-05 de apoio à Inclusão Produtiva ctive inclusion of poor and v cation Selection ntation (S. Nicolau, Sal, Boa Vista) (T ulnerable raining Entities to implement training and support activitie s for Productive Inclusion) 35.3/HCP/UGPE/2023 / Lote 3 - Contratação de Entidades Formadoras para implement Strengthen access to basic s ação de formações e atividad ervices and social and produ Consultant Qualifi Pending Impleme IDA / 70780 Post Open - National 67,000.00 0.00 2023-07-31 2023-08-21 2023-10-04 2023-11-03 2023-12-08 2024-06-05 es de apoio à Inclusão Produt ctive inclusion of poor and v cation Selection ntation iva (Fogo, Brava) (Training E ulnerable ntities to implement training and support activities for Pro ductive Inclusion) 35.4/HCP/UGPE/2023 / Lote 4 - Contratação Entidades Fo rmadoras para implementaçã Strengthen access to basic s o de formações e atividades ervices and social and produ Consultant Qualifi Under Implement IDA / 70780 Post Open - National 66,000.00 0.00 2023-07-31 2023-06-05 2023-08-21 2023-10-04 2023-11-03 2023-12-08 2024-06-05 de apoio à Inclusão Produtiva ctive inclusion of poor and v cation Selection ation (Praia, S. Domingos, R.G. San ulnerable tiago, Maio) (Training Entities to implement training and su pport activities for Productive Inclusion) 35.5/HCP/UGPE/2023 / Lote 5 - Contratação Entidades Fo rmadoras para implementaçã Strengthen access to basic s o de formações e atividades ervices and social and produ Consultant Qualifi Under Implement IDA / 70780 Post Open - National 78,000.00 0.00 2023-07-31 2023-06-05 2023-08-21 2023-10-04 2023-11-03 2023-12-08 2024-06-05 de apoio à Inclusão Produtiva ctive inclusion of poor and v cation Selection ation (S.Cruz, S.L. Órgãos, S.Salva ulnerable dor Mundo) (Training Entities to implement training and su pport activities for Productive Inclusion) Page 2 35.6/HCP/UGPE/2023 / Lote 6 - Contratação Entidades Fo rmadoras para implementaçã Strengthen access to basic s o de formações e atividades ervices and social and produ Consultant Qualifi Under Implement IDA / 70780 Post Open - National 61,000.00 0.00 2023-07-31 2023-06-05 2023-08-21 2023-10-04 2023-11-03 2023-12-08 2024-06-05 de apoio à Inclusão Produtiva ctive inclusion of poor and v cation Selection ation (Tarrafal, S. Miguel, S. Catari ulnerable na) (Training Entities to impl ement training and support a ctivities for Productive Inclusi on) 34.4/HCP/UGPE/2023 / LOT 4 - Contratação de ONG para a poiar no acompanhamento d Strengthen access to basic s os beneficiários do Programa ervices and social and produ Consultant Qualifi Pending Impleme IDA / 70780 Post Limited 66,000.00 0.00 2023-06-30 2023-07-14 2023-08-13 2023-09-17 2024-03-15 de Inclusão Produtiva (Praia, ctive inclusion of poor and v cation Selection ntation São Domingos, R.G. Santiago ulnerable , Maio) (NGOs to help monito r the beneficiaries of the Pro ductive Inclusion Programme ) INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 02/HCP/UGPE/2022 / Technic Support education system re al Consulting in Curriculum D forms to better prepare in-sc Individual Consult Under Implement evelopment - Institutional Rei IDA / 70780 Prior Open 300,000.00 0.00 2022-05-30 2022-07-11 2022-07-18 2022-08-08 2022-09-12 2023-03-11 hool youth for future employ ant Selection ation nforcement for Curriculum R ment eview of Secondary Educatio n (Cabo Verde) 05/HCP/UGPE/2022 / Recruit Strengthen access to basic s ment of a Programmer for th ervices and social and produ Individual Consult Under Implement e social registry (CSU) [Recru IDA / 70780 Post Open 48,000.00 0.00 2022-06-16 2022-05-31 2022-08-04 2022-08-25 2022-09-29 2024-06-03 ctive inclusion of poor and v ant Selection ation tamento de um Programador ulnerable de Sistema do Cadastro Soci al Único (CSU)] 06/HCP/UGPE/2022 / Recruit ment of a Civil Engineer for U Individual Consult Under Implement IDA / 70780 Project Management Post Open 70,000.00 0.00 2022-06-22 2022-06-22 2022-08-10 2022-08-31 2022-10-05 2023-04-03 GPE (Recrutamento de um(a) ant Selection ation Engenheiro(a) Civil para a U GPE) 08/HCP/UGPE/2022 / TA to u Improve access to labor mar Direct - Internation Under Implement pdate the software for the na IDA / 70780 ket relevant professional trai Post Direct Selection 440,000.00 0.00 2022-08-22 2022-09-16 2022-09-01 2022-09-30 2022-11-05 2023-05-04 al ation vigation simulator ning for youth and women Strengthen access to basic s 11/HCP/UGPE/2022 / Recruit Individual Consult Under Implement IDA / 70780 ervices and social and produ Post Open - National 33,600.00 0.00 2022-09-01 2022-09-12 2022-10-20 2022-11-10 2022-12-15 2024-12-15 ment of a Child Care Expert ant Selection ation ctive inclusion of poor and v ulnerable 12HCP/UGPE/2022 / Recruit Strengthen access to basic s Individual Consult Under Implement ment of a Communication an IDA / 70780 ervices and social and produ Post Open - National 45,000.00 0.00 2022-10-13 2022-08-18 2022-12-01 2022-12-22 2023-01-26 2024-01-26 ant Selection ation d Image Specialist ctive inclusion of poor and v ulnerable 14/HCP/UGPE/2022 / Recruit ment of a Senior Technical a Improve access to labor mar nd Vocational Training Speci Individual Consult Open - Internationa Under Implement IDA / 70780 ket relevant professional trai Post 150,000.00 0.00 2022-11-15 2022-12-07 2023-01-03 2023-01-24 2023-02-28 2024-02-28 alist (TVET) to Support the Im ant Selection l ation ning for youth and women plementation of Component 2 of the Cabo Verde Human Capital Project 15/HCP/UGPE/2022 / Recruit Individual Consult Under Implement ment of a Social Protection E IDA / 70780 Project Management Post Direct - National 120,000.00 0.00 2022-12-22 2023-01-05 2023-01-01 2023-01-22 2023-02-26 2024-02-21 ant Selection ation xpert for UGPE 17/HCP/UGPE/2022 / Technic Support education system re al assistance for Aferida II an forms to better prepare in-sc Direct - Internation Under Implement IDA / 70780 Post Direct Selection 200,000.00 0.00 2022-12-22 2023-01-05 2023-01-01 2023-03-07 2023-09-03 d capacity building activities hool youth for future employ al ation for assessment staff ment 18/HCP/UGPE/2022 / Recruit ment of Consultancy services to design the Resettlement A Individual Consult Under Implement IDA / 70780 Project Management Post Direct - National 5,000.00 0.00 2022-12-22 2023-01-05 2023-01-01 2023-01-22 2023-02-26 2023-08-25 ction Plans for Intervention o ant Selection ation n House Regeneration Progra m in Safende and Calabaceir a Neighborhoods 23/HCP/UGPE/2023 / Social/S Strengthen access to basic s Individual Consult Under Implement ocial Protection Assistant, Co IDA / 70780 ervices and social and produ Post Open - National 86,400.00 0.00 2023-02-01 2023-03-22 2023-04-12 2023-05-17 2023-11-13 ant Selection ation mponent 3 ctive inclusion of poor and v ulnerable 29/HCP/UGPE/2023 / TA for t Support education system re he evaluation of basic educat forms to better prepare in-sc Individual Consult Under Implement ion reform (Assistência Técni IDA / 70780 Post Open - National 50,000.00 0.00 2023-03-02 2023-03-15 2023-04-20 2023-05-11 2023-06-15 2023-08-24 hool youth for future employ ant Selection ation ca para proceder a avaliação ment da revisão curricular implem entada no Ensino Básico) 27/HCP/UGPE/2023 / Procure Individual Consult Pending Impleme IDA / 70780 Project Management Post Direct - National 35,880.00 0.00 2023-07-31 2023-08-10 2023-08-31 2023-10-05 2024-10-04 ment Officer for UGPE ant Selection ntation 25/HCP/UGPE/2023 / Implem Improve access to labor mar Pending Impleme entation of the training cours IDA / 70780 ket relevant professional trai Post Direct Selection Direct - National 100,000.00 0.00 2023-07-31 2023-08-10 2023-10-14 2024-04-11 ntation es (1st phase) ning for youth and women 13/HCP/UGPE/2022 / Recruit ment of a Statistician for the Strengthen access to basic s Social Registry of the Coorde ervices and social and produ Individual Consult Pending Impleme IDA / 70780 Post Open - National 36,000.00 0.00 2023-07-31 2023-09-18 2023-10-09 2023-11-13 2024-05-11 nação Nacional do Cadastro ctive inclusion of poor and v ant Selection ntation Social Único (CSU) in the Mini ulnerable stério da Família, Inclusão e Desenvolvimento Social 01/HCP/UGPE/2021 / Recruit ment of a consultant for the elaboration of the Resettlem Pending Impleme ent Policy Framework (RPF) a IDA / 70780 Project Management Post Direct Selection Direct - National 14,300.00 0.00 2023-06-30 2023-07-10 2023-09-13 2023-12-12 ntation nd the Environmental and So cial Management Framework s (ESMF) for the Human Capit al in Cabo Verde Page 3 37/HCP/UGPE/2023 / Recruta mento de um coordenador p ara a elaboração de qualifica Improve access to labor mar Individual Consult Pending Impleme ções profissionais na área m IDA / 70780 ket relevant professional trai Post Open - National 30,000.00 0.00 2023-07-28 2023-09-15 2023-10-06 2023-11-10 2024-05-08 ant Selection ntation arítima (Recruitment of a coo ning for youth and women rdinator for the development of professional qualifications in the maritime field) 31/HCP/UGPE/2023 / Recruit Individual Consult Pending Impleme ment of an Internal Auditor A IDA / 70780 Project Management Post Direct - National 43,934.00 0.00 2023-07-31 2023-08-10 2023-08-31 2023-10-05 2024-04-02 ant Selection ntation uditor e interno para UGPE 32/HCP/UGPE/2023 / Recruta Strengthen access to basic s mento Analista de Sistema p ervices and social and produ Pending Impleme ara o Ministério da Família, In IDA / 70780 Post Direct Selection Direct - National 79,200.00 0.00 2023-06-30 2023-07-10 2023-09-13 2024-03-11 ctive inclusion of poor and v ntation clusão e Desenvolvimento So ulnerable cial (MFIDS) (Social registry a nalyst for PISP (DGIS)) 33/HCP/UGPE/2023 / Recruta mento de um Especialista em Strengthen access to basic s Inclusão Produtiva para Minis ervices and social and produ Pending Impleme tério da Família, Inclusão e D IDA / 70780 Post Direct Selection Direct - National 50,400.00 0.00 2023-06-30 2023-07-10 2023-09-13 2024-03-11 ctive inclusion of poor and v ntation esenvolvimento Social (MFID ulnerable S) (Recruitment of a technica l expert for Productive Inclusi on ) 38/HCP/UGPE/2023 / Recruit ment of fourteen (14) social Strengthen access to basic s experts for the Câmara Muni ervices and social and produ Individual Consult Pending Impleme IDA / 70780 Post Limited 132,000.00 0.00 2023-08-31 2023-09-05 2023-09-26 2023-10-31 2024-04-28 cpal of Porto Novo, Paúl, R. G ctive inclusion of poor and v ant Selection ntation rande, S. Vicente, Praia, S. C ulnerable atarina, S. Cruz, S. Miguel, S. Filipe, respectively 36/HCP/UGPE/2023 / Especia lista para acompanhar o proc esso de atualização do simul Improve access to labor mar ador de Treinamento e reforç Individual Consult Pending Impleme IDA / 70780 ket relevant professional trai Post Limited 30,000.00 0.00 2023-08-31 2023-09-05 2023-09-26 2023-10-31 2024-04-28 o da capacidade técnica da E ant Selection ntation ning for youth and women MAR (Expert to accompany t he process of upgrading the Training simulator and reinfo rcing the technical capacity o f EMAR) 42/HCP/UGPE/2023 / TA to a Support education system re Individual Consult Pending Impleme dapt TEACH Tools, Training, IDA / 70780 forms to better prepare in-sc Post Limited 50,000.00 0.00 2023-08-31 2023-09-05 2023-09-26 2023-10-31 2024-04-28 ant Selection ntation Observers and conduct Pilot hool youth for future employ ment 43/HCP/UGPE/2023 / Trainer s for the off-board engine ma Improve access to labor mar intenance course in Santiago Individual Consult Pending Impleme IDA / 70780 ket relevant professional trai Post Open - National 15,000.00 0.00 2023-09-29 2023-11-17 2023-12-08 2024-01-12 2024-07-10 and São Nicolau (Formadores ant Selection ntation ning for youth and women para o curso de manutenção de motores fora de bordo em Santiago e São Nicolau) 44/HCP/UGPE/2023 / Recruit ment of a specialist to coordi nate the development of prof Improve access to labor mar essional qualifications in the Individual Consult Pending Impleme IDA / 70780 ket relevant professional trai Post Open - National 50,000.00 0.00 2023-09-29 2023-11-17 2023-12-08 2024-01-12 2024-07-10 area of blue economy (Recru ant Selection ntation ning for youth and women tamento de um especialista para coordenar elaboração d e qualificações profissionais na área de economia azul) Page 4 PROCUREMENT PLAN (Textual Part) Project information: Ukraine, Public Expenditures for Administrative Capacity Endurance (PEACE in Ukraine) Project, P178946 Project Implementation agency: Ministry of Finance of Ukraine Date of the Procurement Plan: May 29, 2023 Period covered by this Procurement Plan: from June 2022 to June 2023 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (Fourth Edition, November 2020) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: Not Applicable. Leased Assets: Not Applicable Procurement of Second Hand Good: Not Applicable Domestic preference: Not Applicable Hands-on Expanded Implementation Support (HEIS) is Applicable. Other Relevant Procurement Information. The Project is implemented in Fragile and Conflict Affected (FCV) context in a situation of Urgent Need of Assistance. The implementing agency’s capacity is also constrained both internally (lack of IFI and WB procurement experience) and externally (FCV), while the Project timeline is tight. The only procurement procedure envisaged within the Project is the selection of an audit firm. The Bank’s team will provide reasonable support and assistance in preparation of required documents. PROCUREMENT Ukraine : Public Expenditures for Administrative Capacity Endurance (PEACE) in Ukraine PLAN General Information Country: Ukraine 2023-06-01 Bank’s Approval Date of the Original Procurement Plan: 2023-06-01 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P178946 GPN Date: 2023-03-29 Project Name: Public Expenditures for Administrative Capacity Endurance (PEACE) in Ukraine Loan / Credit No: IDA / 71530 Ministry of Finance of Ukraine Executing Agency(ies): WORKS Activity Reference No. / Procureme Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH Ri Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method nt Docume ount (US$ and Recommendation Signed Contract o. h cess (Y/N) sk atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion nt Type ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Audit and administrative exp Consultant Qualifi Under Implement PEACE-CQS-1 / Project Audit IDA / 71530 Post Limited 0.00 2023-06-01 2023-06-01 2023-06-12 2023-06-20 2023-06-26 2023-06-30 2023-12-29 enses cation Selection ation INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Actual Amount Invitation to Identifie Draft Negotiated Cont Component Review Type Method Contract Type Process Status Teams of Reference Signed Contract Contract Completion Description o. h (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 1 SUMMARY O F PROCUREMENT PLAN Project Preparation Advancement (PPA) Project information: Harmonizing and Improving Statistics in West Africa Project -P169265 Project Implementation agency: Liberia Institute of Statistics and Geo- Information Services (LISGIS) Date of the Procurement Plan: February 3, 2020 Period covered by this Procurement Plan: 3rd February to 31st July 2020 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 1, 2016), revised in November 2017, and August 2018 (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the Public Procurement and Concessions Act, 2010 of the Republic of Liberia, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations. In accordance with paragraph 5.3 of the Procurement Regulations, the request for bids/request for proposals document shall require that Bidders/Proposers submitting Bids/Proposals present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights. The form of the Letter of Acceptance is attached in Appendix 1. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. Not Applicable Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables. Not Applicable. Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: Not Applicable for those contracts identified in the Procurement Plan tables; Works: Not Applicable for those contracts identified in the Procurement Plan tables. Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations: Not Applicable. Other Relevant Procurement Information: - (a). Prior Procurement Arrangements: The Procurement Arrangements as indicated in the below table and within the thresholds indicated in the below tables will be used. The thresholds for the Bank’s prior review requirements are also provided in the table below: Table: Thresholds*, Procurement Arrangements, and Prior Review (The table below depicts the Thresholds and Procurement Methods to be used under the Regional Project for Statistics Thresholds*, Procurement Methods, and Prior Review Contract (C) Value Expenditure Procurement Contracts Subject to No Threshold* [eq. Category Method Prior Review /[eq. US$] USD] All contracts at or above USD Open Competition 5,000,000 are subject to International Market 1 Works C ≥ 5,000,000 Approach and Direct international advertising and the use of the Bank’s SPDs (or other Contracting documents agreed with the Contract (C) Value Expenditure Procurement Contracts Subject to No Threshold* [eq. Category Method Prior Review /[eq. US$] USD] Bank). Open Competition National Market 200,000 < C < 5,000,000 None Approach C ≤ 200,000 RfQ None All contracts at or above USD Open Competition 500,000 are subject to International Market international advertising and the C ≥ 500,000 Approach and Direct use of the Bank’s SPDs (or other Goods, IT and Contracting documents agreed with the 2 non-consulting Bank). services Open Competition 100,000 < C < 500,000 National Market None Approach C ≤ 100,000 RfQ None All contracts at or above USD 100,000 are subject to for international advertising and the C < 100,000 Consulting Services use of the Bank’s SPDs (or other National documents agreed with the shortlist for Bank). 3 selection of All contracts at or above USD consultant firms for 200,000 are subject to Engineering and international advertising and the C ≤ 200,000 Construction use of the Bank’s SPDs (or other Supervision documents agreed with the Bank). Selection of All values ≥ 100,000 4 Individual All Approaches consultants Training, This line activity is not subject to Workshops, Based on approved Procurement Review However, 5 Study Tours All Values Annual Work Plan & each of the activities will be Budgets (AWPB) by TTL cleared with the TTL prior to its implementation. (Special procurement arrangements like direct contracting, use of SOEs, UN Agencies, third party monitors, local NGOs, Force Account, servants needs, results based arrangements. It is not expected that there will be need for prequalification in the procurement arrangements under this Regional Project *These thresholds are for the purposes of the initial procurement plan for the PPA and for first 18 months. The thresholds will be revised periodically based on re- assessment of risks. All contracts not subject to prior review will be post-reviewed. Prequalification. Not expected for the packages of works/goods packages in the procurement plan. Proposed Procedures for CDD Components: Not Applicable Reference to (if any) Project Operational/Procurement Manual: The LISGIS Project Management Team will prepare Procurement manuals. The Procurement Plan will also form part of the Project Implementation Manual. Any Other Special Procurement Arrangements: None Procurement Packages/PLAN with Procurement Arrangements and Time Schedule: as per the Table below: b) PROCUREMENT PLAN Works There are no works under the Project Preparation Advance Goods and Non-Consulting Services 1 2 3 4 5 6 7 8 9 Ref. Contract Estimated Procurement Prequ Nation Revie Expecte Expecte Comment No. (Description) Cost Method alifica al w d bid d s US$ tion Prefer by opening Contrac (yes/n ence Bank date t o) (yes/n (Prior Signatu o) / Post) re Date 1 Procurement of 4 12,100 laptops, 3 No. all- in-1 printers, Limited, RFQ No No Post 28 Feb 4 Mar office desks, a 20 20 projector, metal filing cabinet, and stationery and supplies for project management Consultancy Services 1 2 3 4 5 6 7 8 9 Ref. Description of Estimate Selection Review Expecte Expected Expected Comments No. Assignment d Method/ by Bank d date Contract Completi Cost in Arrangem (Prior / of Signatur on US$ ent Post) proposal e Date submissi Date on 1. Recruitment of a Consultant to draft and validate 10,000 INDV Post 16 Mar 10 Apr 23 Apr ToR to be curricula of the 20 20 20 submitted to IDA Statistics degree & for Review and No CEST Program at Objection. the UL 2. Recruitment of a ToR, performance Financial evaluation, draft Management contract and Officer for Project DS Prior 10 Feb 21 Feb 31 Aug minutes of Management 20 20 20 contract negotiation to be submitted to IDA for Review and No 15,600 Objection. 3. ToR, performance evaluation, draft Recruitment of a contract and Procurement DS Prior 10 Feb 21 Feb 31 Aug minutes of Specialist for 20 20 20 contract Project 18,000 negotiation to be Management submitted to IDA for Review and No Objection. Training and Workshop (Training & Workshop activities are subject to TTL clearance). Estimat Estimated Expected Ref. Training, workshop and ed Cost Duration Training/workshop No. study tours in (Days) Date (US$) Conduct of validation 54,000 workshop and TOT for the GP Feb. 20 to March 1. on the design of 13 2020 questionnaires and enumeration training manual Workshop for cartographic 150,000 Feb. 24 to March 2. field staff training 16 2020 Workshop for enumeration 113,900 3. mapping training April 15, 2020 Study Tours to regional 32,000 countries for first-hand experience on regional March to April 4. harmonization of data 2020 collection, management and communication Workshops on current 50,000 administrative data across 5. April to July 2020 MACs and LISGIS regional offices Workshop to strengthen and 35,000 6. develop institutional capacity April to July 2020 of NSO Workshops for steering 40,000 7. committee on Administrative April to July 2020 Data Workshop for Project 10,000 Steering/Technical 8. Committees for annual work February 2020 plan preparation, review and validation GENERAL NOTES 1. Training and capacity building: Training workshops (including training material and support), conference attendance and study tours, will be carried out based on approved annual training and allied activities plan by the TTL. The beneficiaries, after the training, will be requested to submit a brief report indicating what skills have been acquired and how these skills will contribute to enhance their performance and contribute to the attainment of the Project’s development objective. 2. Operational Costs: These are expenditures incurred by the Recipient to finance: (i) communication technology (including, without limitation, internet and telephone; (ii) per diem and travel expenses of the operational staff performing their responsibilities under the Project; (iii) fuel and vehicle maintenance; (iv) maintenance of equipment; (v) photocopies and publications; (viii) bank commissions; and (ix) utilities and office supplies as defined in the FA. Appendix 1 Letter of Acceptance of the World Bank’s Anti-Corruption Guidelines and Sanctions Framework Date: Invitation of Bids/Proposals No.__________ To: ___________________________________________________________________________ We, along with our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not) consultants and personnel, acknowledge and agree to abide by the World Bank’s policy regarding Fraud and Corruption (corrupt, fraudulent, collusive, coercive, and obstructive practices), as set out and defined in the World Bank’s Anti-Corruption Guidelines1 in connection with the procurement and execution of the contract (in case of award), including any amendments thereto. We declare and warrant that we, along our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not), consultants and personnel, , are not subject to, and are not controlled by any entity or individual that is subject to, a temporary suspension, early temporary suspension, or debarment imposed by a member of the World Bank Group, including, inter alia, a cross-debarment imposed by the World Bank Group as agreed with other international financial institutions (including multilateral development banks), or through the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement. Further, we are not ineligible under the laws or official regulations of [Insert name of Employer as per bidding document] or pursuant to a decision of the United Nations Security Council. We confirm our understanding of the consequences of not complying with the World Bank’s Anti-Corruption Guidelines, which may include the following: a. rejection of our Proposal/Bid for award of contract; 1Guidelines on Preventing and Combating Fraud and Corruption in Projects Financed by International Bank for Reconstruction and Development Loans and the International Development Agency Credits and Grants, dated October 15, 2006, and revised in January 2011 and July 2016, as they may be revised from time to time. b. in the case of award, termination of the contract, without prejudice to any other remedy for breach of contract; and c. sanctions, pursuant to the Bank’s Anti-corruption Guidelines and in accordance with its prevailing sanctions policies and procedures as set forth in the Bank’s Sanctions Framework. This may include a public declaration of ineligibility, either indefinitely or for a stated period of time, (i) to be awarded or otherwise benefit from a Bank-financed contract, financially or in any other manner;2 (ii) to be a nominated3 sub-contractor, consultant, manufacturer or supplier, or service provider of an otherwise eligible firm being awarded a Bank-financed contract; and (iii) to receive the proceeds of any loan made by the Bank or otherwise to participate further in the preparation or implementation of any Bank-financed project. We understand that we may be declared ineligible as set out above upon: a. completion of World Bank Group sanctions proceedings according to its prevailing sanctions procedures; b. cross-debarment as agreed with other international financial institutions (including multilateral development banks); c. the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement; or d. temporary suspension or early temporary suspension in connection with an ongoing World Bank Group sanctions proceeding. For avoidance of doubt, the foregoing effects of ineligibility do not extend to a sanctioned firm’s or individual’s execution of its ongoing Bank-financed contracts (or its ongoing sub-agreements under such contracts) that are not the subject of a material modification, as determined by the Bank. We shall permit, and shall cause our sub-contractors, sub-consultants, agents (whether declared or not), personnel, consultants, service providers or suppliers, to 2 For the avoidance of doubt, a sanctioned party’s ineligibility to be awarded a contract shall include, without limitation, (i) applying for pre-qualification, expressing interest in a consultancy, and bidding, either directly or as a nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider, in respect of such contract, and (ii) entering into an addendum or amendment introducing a material modification to any existing contract. 3 A nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider (different names are used depending on the particular bidding document) is one which has been: (i) included by the bidder in its pre-qualification application or bid because it brings specific and critical experience and know-how that allow the bidder to meet the qualification requirements for the particular bid; or (ii) appointed by the Borrower. permit the Bank to inspect4 all accounts, records, and other documents relating to the procurement process and/or contract execution (in the case of award), and to have them audited by auditors appointed by the Bank. We agree to preserve all accounts, records, and other documents (whether in hard copy or electronic format) related to the procurement and execution of the contract. Name of the Bidder/Consultant: Name of the person duly authorized to sign the Bid/Proposal on behalf of the Bidder/Consultant: Title of the person signing the Letter: 4 Inspections in this context are usually investigative (i.e., forensic) in nature: they involve fact-finding activities undertaken by the Bank or persons appointed by the Bank to address specific matters related to investigations/audits, such as evaluating the veracity of an allegation of possible Fraud and Corruption, through the appropriate mechanisms. Such activity includes but is not limited to accessing and examining a firm's or individual's financial records and information, and making copies thereof as relevant; accessing and examining any other documents, data, and information (whether in hard copy or electronic format) deemed relevant for the investigation/audit, and making copies thereof as relevant; interviewing staff and other relevant individuals; performing physical inspections and site visits; and obtaining third-party verification of information. PROCUREMENT Western and Central Africa : Harmonizing and Improving Statistics in West Africa PLAN General Information Country: Western and Central Africa 2020-11-27 Bank’s Approval Date of the Original Procurement Plan: 2023-06-02 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P169265 GPN Date: 2021-05-19 Project Name: Harmonizing and Improving Statistics in West Africa Loan / Credit No: IDA / 65730, IDA / 65770, IDA / 65740, IDA / 65760 Institut National de la Statistique et de la Démographie Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned National Procure BF-INSD-338574-CW-RFQ / R Country-Specific Component ment Document - éalisation des travaux d'amé : Improving and modernizing Request for Quota Single Stage - One E Pending Imp 2023-06-2 IDA / 65730 Post Limited 1 Envelope proce 54,545.00 0.00 2023-04-25 2023-05-11 nagement pour la mise en no physical and statistical infra tions nvelope lementation 5 ss (Non Bank-SPD rme de la salle serveur (Réfe structure ) ction) GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BF-INSD-177135-GO-RFB / A Regional component: Harmo cquisition du matériel inform nization, Data Collection, Qu Open - Internationa Single Stage - One E atique au profit des structure IDA / 65730 ality Improvement, Dissemin Post Request for Bids 1,450,000.00 0.00 Canceled 2021-03-01 2021-03-06 2021-04-20 2021-05-20 2021-06-24 2021-09-22 l nvelope s de MEO du Projet et pour l ation and Use of Core Social a mise en œuvre des enquêt and Economic Statistics es. Regional component: Harmo BF-INSD-175419-GO-RFQ / A nization, Data Collection, Qu Request for Quota Single Stage - One E cquisition de Mobiliers de bur IDA / 65730 ality Improvement, Dissemin Post Limited 15,000.00 26,504.55 Completed 2020-06-20 2021-10-06 2020-08-04 2021-11-10 2020-09-03 2022-01-01 tions nvelope eaux pour l'UGP ation and Use of Core Social and Economic Statistics BF-INSD-175423-GO-RFQ / F Project Management and Mo Request for Quota Single Stage - One E ourniture matériels informati IDA / 65730 Post Limited 25,000.00 21,688.49 Completed 2020-06-27 2021-10-22 2020-08-02 2021-12-03 2020-08-23 2022-03-02 nitoring and Evaluation tions nvelope ques pour l'UGP BF-INSD-175426-GO-RFQ / A cquisition de fournitures de b Project Management and Mo Request for Quota Single Stage - One E IDA / 65730 Post Limited 14,000.00 12,667.21 Completed 2020-06-27 2021-09-30 2020-07-22 2021-11-18 2020-08-12 2021-12-22 ureau , consommables infor nitoring and Evaluation tions nvelope matiques et produits d'entre tien pour l'UGP BF-INSD-175443-GO-RFQ / A Project Management and Mo Request for Quota Single Stage - One E chat de logiciel de gestion co IDA / 65730 Post Limited 25,000.00 26,132.24 Completed 2021-05-22 2021-06-15 2021-06-29 2021-08-11 2021-07-29 2021-10-19 nitoring and Evaluation tions nvelope mptable et financière du proj et BF-INSD-175446-GO-RFQ / A Project Management and Mo Request for Quota Single Stage - One E cquisition de logiciel de suivi IDA / 65730 Post Limited 25,000.00 26,509.54 Signed 2021-05-22 2022-04-11 2021-06-28 2022-06-08 2021-07-28 nitoring and Evaluation tions nvelope évaluation pour l'UGP BF-INSD-176330-GO-RFQ / a Project Management and Mo Request for Quota Single Stage - One E cquisition de matériel de prot IDA / 65770 Post Limited 15,265.00 0.00 Canceled 2021-01-30 2021-03-20 2021-04-10 nitoring and Evaluation tions nvelope ection pour l'enquête emploi et rebasage BF-INSD-176333-GO-RFQ / F Project Management and Mo Request for Quota Single Stage - One E ournitures d'imperméables, t IDA / 65770 Post Limited 4,200.00 0.00 Canceled 2021-04-04 2021-05-12 2021-06-02 nitoring and Evaluation tions nvelope orches pour l'enquête ménag es BF-INSD-176335-GO-RFQ / F Project Management and Mo Request for Quota Single Stage - One E ournitures de matériels de co IDA / 65730 Post Limited 12,899.00 0.00 Canceled 2020-08-30 2020-10-25 2020-12-24 nitoring and Evaluation tions nvelope llectes -balances, pesons, etc BF-INSD-215385-GO-RFQ / M Regional component: Harmo atériel de protection (imper nization, Data Collection, Qu Request for Quota Single Stage - One E méables, bottes, torches, la IDA / 65730 ality Improvement, Dissemin Post Open - National 32,400.00 14,777.01 Completed 2021-04-24 2021-06-19 2022-01-21 2021-08-03 2022-02-26 tions nvelope mpes) pour les enquêtes Em ation and Use of Core Social ploi, , Rebasage, ménage et - and Economic Statistics IHPC 12 Regional component: Harmo BF-INSD-177179-GO-RFQ / A nization, Data Collection, Qu chat de enquêteurs et sac po Request for Quota Single Stage - One E Pending Impl IDA / 65730 ality Improvement, Dissemin Post Limited 37,508.00 0.00 2021-04-04 2021-05-30 2021-06-29 ur tablette dans le cadre des tions nvelope ementation ation and Use of Core Social enquêtes. and Economic Statistics Regional component: Harmo BF-INSD-177186-GO-RFB / A nization, Data Collection, Qu Single Stage - One E Pending Impl chat de sac enquêteurs dans IDA / 65730 ality Improvement, Dissemin Post Request for Bids Open - National 177,311.00 0.00 2021-04-21 2021-04-26 2021-07-18 2021-08-17 2021-09-21 2021-11-20 nvelope ementation le cadre de la cartographie ation and Use of Core Social and Economic Statistics BF-INSD-216310-GO-RFB / M Country-Specific Component Single Stage - One E atériel informatique au profit IDA / 65730 : Improving and modernizing Post Request for Bids Open - National 355,000.00 0.00 Canceled 2021-05-10 2021-05-15 2021-06-14 2021-06-29 2021-08-03 2021-12-01 nvelope de l’INSD physical and statistical infra structure BF-INSD-216330-GO-RFQ / E Country-Specific Component quiper l’INSD de kit de vidéo : Improving and modernizing Request for Quota Single Stage - One E IDA / 65730 Post Limited 27,500.00 0.00 Signed 2021-06-07 2022-11-02 2021-08-02 2021-09-16 surveillance pour renforcer la physical and statistical infra tions nvelope sécurité des locaux structure BF-INSD-219691-GO-UN / Fo Regional component: Harmo urniture de matériels roulant nization, Data Collection, Qu UN Agencies (Dire pour l’UGP (3 véhicules et u IDA / 65730 ality Improvement, Dissemin Post Direct 1,917,000.00 1,228,143.37 Completed 2021-03-01 2021-02-25 2021-03-06 2021-07-26 2021-04-10 2021-07-28 2021-08-08 2021-08-13 ct) ne motos) et aux structures ation and Use of Core Social de mise en œuvre. and Economic Statistics BF-INSD-238952-GO-DIR / Sé Regional component: Harmo lection d'un concessionnaire nization, Data Collection, Qu de location de véhicules sous Request for Quota Single Stage - One E IDA / 65730 ality Improvement, Dissemin Post Limited 447,272.00 405,046.38 Completed 2021-06-24 2021-06-24 2021-07-25 2021-08-31 2021-11-25 2021-12-09 forme d'accord cadre pour la tions nvelope ation and Use of Core Social réalisation de la 5ème enquê and Economic Statistics te démographique et de sant é du Burkina Faso (EDS/BF-5) Page 1 BF-INSD-254077-NC-RFQ / A Country-Specific Component Request for Quota Single Stage - One E cquisition d'un logiciel pour l IDA / 65730 : Improving and modernizing Post Limited 7,272.00 6,453.75 Completed 2021-10-06 2022-01-28 2021-11-04 2022-03-12 2021-11-19 2022-04-28 tions nvelope a gestion des dossiers de l'E physical and statistical infra DSBF-V structure Regional component: Harmo BF-INSD-267618-GO-RFQ / A nization, Data Collection, Qu Request for Quota Single Stage - One E cquisition d'equipements aca IDA / 65730 ality Improvement, Dissemin Post Limited 18,181.00 16,023.87 Completed 2021-12-19 2022-01-26 2022-01-04 2022-03-11 2022-01-09 2022-04-12 tions nvelope démiques pour l'ISSP ation and Use of Core Social and Economic Statistics BF-INSD-281151-GO-RFQ / A Regional component: Harmo cquisition d'équipements (m nization, Data Collection, Qu Request for Quota Single Stage - One E atériels informatiques et mat IDA / 65730 ality Improvement, Dissemin Post Limited 90,909.00 74,030.65 Completed 2022-03-15 2022-04-11 2022-04-11 2022-05-25 2022-05-11 2022-08-02 tions nvelope ériels de bureau) au profit du ation and Use of Core Social PHASAO et pour le compte d and Economic Statistics e l'ISSP Regional component: Harmo BF-INSD-283169-GO-RFQ / A nization, Data Collection, Qu cquisition de consommables i Request for Quota Single Stage - One E IDA / 65730 ality Improvement, Dissemin Post Limited 10,409.00 8,818.14 Signed 2022-04-04 2022-06-22 2022-05-30 2022-07-28 2022-06-13 nformatiques (DD, DSCVM et tions nvelope ation and Use of Core Social MENAPLN) and Economic Statistics BF-INSD-283187-GO-RFQ / a Country-Specific Component Request for Quota Single Stage - One E cquisition de matériels de bu IDA / 65730 : Improving and modernizing Post Limited 7,045.00 12,861.46 Signed 2022-03-30 2022-06-28 2022-05-25 2022-09-03 2022-07-09 tions nvelope reau au profit des DR-INSD physical and statistical infra structure BF-INSD-283201-GO-RFQ / a Country-Specific Component Request for Quota Single Stage - One E Under Imple cquisition de mobiliers de bur IDA / 65730 : Improving and modernizing Post Limited 13,600.00 0.00 2022-03-30 2022-06-28 2022-05-25 2022-07-09 tions nvelope mentation eau au profits des DR-INSD physical and statistical infra structure Regional component: Harmo BF-INSD-283207-GO-RFQ / a nization, Data Collection, Qu cquisition de produit pharma Request for Quota Single Stage - One E Under Imple IDA / 65730 ality Improvement, Dissemin Post Limited 10,909.00 0.00 2022-04-25 2023-01-04 2022-06-20 2022-07-20 ceutiques au profit de la DSC tions nvelope mentation ation and Use of Core Social VM and Economic Statistics BF-INSD-283237-GO-RFQ / a Country-Specific Component cquisition de licences Kasper : Improving and modernizing Request for Quota Single Stage - One E IDA / 65730 Post Limited 15,614.00 0.00 Signed 2022-04-16 2022-05-31 2022-05-15 2022-05-18 sky Endpoint Security et Kas physical and statistical infra tions nvelope persky Security for internet G structure ateway Regional component: Harmo BF-INSD-284201-GO-RFQ / A nization, Data Collection, Qu cquisition des matériels d'arc Request for Quota Single Stage - One E IDA / 65730 ality Improvement, Dissemin Post Limited 27,727.00 21,718.10 Signed 2022-05-10 2022-09-13 2022-06-09 2022-10-08 2022-07-24 hivage des questionnaires de tions nvelope ation and Use of Core Social s recensements de 2006 and Economic Statistics BF-INSD-284265-GO-RFQ / A Project Management and Mo Request for Quota Single Stage - One E IDA / 65730 Post Limited 90,909.00 4,867,424.79 Signed 2022-04-20 2022-06-06 2022-05-21 2022-07-28 2022-07-20 cquisition de 25 motos pour l nitoring and Evaluation tions nvelope 'UGP BF-INSD-284288-GO-RFQ / C onfection de gadgets (tee-shi Project Management and Mo Request for Quota Single Stage - One E IDA / 65730 Post Limited 27,272.00 0.00 Signed 2022-04-20 2022-09-20 2022-05-28 2022-07-12 rts, casquettes, calendrier...) nitoring and Evaluation tions nvelope pour la visibilité du Projet BF-INSD-216313-GO-RFB / A Country-Specific Component Open - Internationa Single Stage - One E cquisition de logiciel pour l'IN IDA / 65730 : Improving and modernizing Post Request for Bids 602,000.00 0.00 Canceled 2021-05-17 2021-05-22 2021-07-06 2021-07-21 2021-08-25 2021-10-24 l nvelope SD physical and statistical infra structure BF-INSD-177146-GO-RFB / A Project Management and Mo Open - Internationa Single Stage - One E cquisition de divers équipem IDA / 65730 Post Request for Bids 193,277.00 0.00 Canceled 2021-05-17 2021-05-22 2021-07-06 2021-08-05 2021-09-09 2021-11-08 nitoring and Evaluation l nvelope ents d'imprimerie pour l'INSD Regional component: Harmo nization, Data Collection, Qu BF-INSD-177130-GO-RFB / A Single Stage - One E IDA / 65730 ality Improvement, Dissemin Post Request for Bids Open - National 353,200.00 283,765.63 Signed 2020-06-30 2022-05-17 2020-07-05 2020-08-04 2022-06-21 2020-08-19 2022-07-27 2020-09-16 2022-09-08 2020-11-15 chat de kits solaires nvelope ation and Use of Core Social and Economic Statistics Regional component: Harmo BF-INSD-229234-GO-UN / Ac nization, Data Collection, Qu quisition du matériel informa Under Imple IDA / 65730 ality Improvement, Dissemin Prior Direct Selection Direct 4,545,454.00 0.00 2021-06-01 2022-09-12 2021-06-06 2023-01-19 2021-07-11 2021-11-08 tique au profit pour la mise e mentation ation and Use of Core Social n œuvre du projet and Economic Statistics BF-INSD-295495-GO-RFB / A Country-Specific Component cquisition de matériels péri-i : Improving and modernizing Single Stage - One E IDA / 65730 Post Request for Bids Open - National 403,000.00 0.00 Signed 2022-06-20 2022-09-30 2022-06-25 2022-07-25 2022-11-07 2022-08-01 2022-11-15 2022-08-25 2022-10-24 nformatiques au profit des st physical and statistical infra nvelope ructures de mise en œuvre d structure u PHASAO BF-INSD-312670-GO-RFQ / A Project Management and Mo Request for Quota Single Stage - One E Pending Impl IDA / 65730 Post Limited 9,661.81 0.00 2022-10-15 2022-11-11 2022-12-11 cquisition du logiciel TOM2 P nitoring and Evaluation tions nvelope ementation AIE BF-INSD-318561-GO-RFQ / A Project Management and Mo Request for Quota Single Stage - One E cquisition de consommables i IDA / 65730 Post Limited 18,181.81 0.00 Signed 2022-10-23 2022-10-24 2022-11-08 2022-11-23 nitoring and Evaluation tions nvelope nformatiques au profit de l'U GP BF-INSD-318586-GO-RFQ / A Project Management and Mo Request for Quota Single Stage - One E cquisition de fournitures (con IDA / 65730 Post Limited 45,454.54 0.00 Signed 2022-10-21 2022-10-24 2022-11-06 2022-11-21 nitoring and Evaluation tions nvelope sommables) de bureau BF-INSD-318589-GO-RFQ / A Project Management and Mo Request for Quota Single Stage - One E cquisition de produit d'entreti IDA / 65730 Post Limited 27,272.72 0.00 Signed 2022-10-23 2022-10-24 2022-11-08 2022-11-23 nitoring and Evaluation tions nvelope en pour l'UGP Regional component: Harmo BF-INSD-318608-GO-RFQ / A nization, Data Collection, Qu Request for Quota Single Stage - One E cquisition de matériels infor IDA / 65730 ality Improvement, Dissemin Post Limited 90,909.09 0.00 Signed 2022-10-28 2022-11-02 2022-11-13 2022-12-13 tions nvelope matiques pour l'ISSP ation and Use of Core Social and Economic Statistics BF-INSD-219693-GO-RFQ / F Country-Specific Component Request for Quota Single Stage - One E Pending Impl ournitures de bureau au profi IDA / 65730 : Improving and modernizing Post Limited 45,455.00 0.00 2023-09-30 2023-11-12 2024-11-06 tions nvelope ementation t de l'UGP physical and statistical infra structure Regional component: Harmo BF-INSD-284217-GO-RFQ / a nization, Data Collection, Qu cquisition de fournitures et d Request for Quota Single Stage - One E Pending Impl IDA / 65730 ality Improvement, Dissemin Post Limited 45,454.00 0.00 2023-06-04 2023-07-03 2023-08-02 e matériel pour l'école au pr tions nvelope ementation ation and Use of Core Social ofit de l'ISSP and Economic Statistics Page 2 BF-INSD-284276-GO-RFQ / A cquisition de matériel d'acco Project Management and Mo Request for Quota Single Stage - One E Pending Impl mmodation (frigos, bottes, i IDA / 65730 Post Limited 18,818.00 0.00 2023-06-20 2023-07-14 2023-08-13 nitoring and Evaluation tions nvelope ementation mperméables, chaussures de sécurité, gourdes etc.) BF-INSD-312661-GO-RFQ / A Country-Specific Component Request for Quota Single Stage - One E Pending Impl cquisition de trois (03) conte IDA / 65730 : Improving and modernizing Post Limited 67,272.72 0.00 2023-06-06 2023-06-30 2023-08-14 tions nvelope ementation neurs au profit de l'INSD physical and statistical infra structure BF-INSD-338637-GO-RFQ / A Regional component: Harmo cquisition d'ouvrages didacti nization, Data Collection, Qu ques pour le corps professor Request for Quota Single Stage - One E Under Imple IDA / 65730 ality Improvement, Dissemin Post Limited 72,727.00 0.00 2023-05-06 2023-05-02 2023-05-28 2023-06-27 al et les étudiants des écoles tions nvelope mentation ation and Use of Core Social de statistiques et pour les us and Economic Statistics agers de la salle de lecture d e l'INSD BF-INSD-338645-GO-RFB / A Country-Specific Component ssurer la mise en norme du d : Improving and modernizing Single Stage - One E Pending Impl atacencer et les salles techni IDA / 65730 Post Request for Bids Open - National 363,636.00 0.00 2023-05-01 2023-05-06 2023-06-05 2023-06-19 2023-07-03 2023-10-01 physical and statistical infra nvelope ementation ques (câblage ,sécurité physi structure que, climatiseurs ,urbanisatio n serveur) Regional component: Harmo BF-INSD-338685-GO-RFQ / A nization, Data Collection, Qu cquisition de sacs dans le ca Request for Quota Single Stage - One E Under Imple IDA / 65730 ality Improvement, Dissemin Post Limited 18,182.00 0.00 2023-04-08 2023-03-22 2023-04-30 2023-05-30 dre de recensement des infra tions nvelope mentation ation and Use of Core Social structures éducatives and Economic Statistics BF-INSD-338692-GO-RFQ / A Regional component: Harmo cquisition de matériel inform nization, Data Collection, Qu atique dans le cadre de l'opé Request for Quota Single Stage - One E Pending Impl IDA / 65730 ality Improvement, Dissemin Post Limited 9,091.00 0.00 2023-04-19 2023-05-11 2023-06-10 rationnalisation du dispositif tions nvelope ementation ation and Use of Core Social national de suivi des prix et c and Economic Statistics oût des transports de marcha ndises Regional component: Harmo BF-INSD-338697-GO-RFB / A nization, Data Collection, Qu cquisition de kits solaire au p Single Stage - One E Pending Impl IDA / 65730 ality Improvement, Dissemin Post Request for Bids Open - National 261,818.00 0.00 2023-03-15 2023-03-20 2023-04-19 2023-05-03 2023-05-17 2023-08-15 rofit du Ministère en charge d nvelope ementation ation and Use of Core Social e la santé and Economic Statistics BF-INSD-338699-GO-RFQ / A Regional component: Harmo cquisition et installation d'un nization, Data Collection, Qu Request for Quota Single Stage - One E Pending Impl tableau numérique pour la di IDA / 65730 ality Improvement, Dissemin Post Limited 9,091.00 0.00 2023-05-20 2023-06-11 2023-07-26 tions nvelope ementation ffusion d'informations statisti ation and Use of Core Social ques and Economic Statistics Regional component: Harmo BF-INSD-338701-GO-RFQ / A nization, Data Collection, Qu cquisition d'équipement infor Request for Quota Single Stage - One E Pending Impl IDA / 65730 ality Improvement, Dissemin Post Limited 90,909.00 0.00 2023-07-08 2023-07-30 2023-09-13 matique pour l'école au profit tions nvelope ementation ation and Use of Core Social de l'ISSP and Economic Statistics BF-INSD-338709-GO-RFQ / A Project Management and Mo Request for Quota Single Stage - One E Pending Impl cquisition de produits d'entre IDA / 65730 Post Limited 18,182.00 0.00 2023-09-30 2023-10-22 2023-11-21 nitoring and Evaluation tions nvelope ementation tien au profit de l'UGP BF-INSD-338712-GO-RFQ / C onfection de gadgets (t-shirt, Project Management and Mo Request for Quota Single Stage - One E Pending Impl IDA / 65730 Post Limited 54,545.00 0.00 2023-07-08 2023-07-30 2023-09-13 casquettes, calendriers...) po nitoring and Evaluation tions nvelope ementation ur la visibilité du projet Regional component: Harmo BF-INSD-338716-GO-RFQ / A nization, Data Collection, Qu Request for Quota Single Stage - One E Pending Impl cquisition de mobilier de bur IDA / 65730 ality Improvement, Dissemin Post Limited 36,364.00 0.00 2023-07-25 2023-08-16 2023-09-15 tions nvelope ementation eau au profit de l'ISSP ation and Use of Core Social and Economic Statistics BF-INSD-338720-GO-RFQ / A cquisition de consommables i Project Management and Mo Request for Quota Single Stage - One E Pending Impl IDA / 65730 Post Limited 65,455.00 0.00 2023-09-20 2023-10-12 2023-11-11 nformatique (encres ) pour l'I nitoring and Evaluation tions nvelope ementation HPC ,l' ICC et l'UGP Regional component: Harmo BF-INSD-318610-GO-RFQ / A nization, Data Collection, Qu cquisition d'équipements de Request for Quota Single Stage - One E IDA / 65730 ality Improvement, Dissemin Post Limited 27,272.72 0.00 Canceled 2022-10-28 2022-11-13 2022-11-16 salles de classe au profit de l' tions nvelope ation and Use of Core Social ISSP and Economic Statistics BF-INSD-283228-GO-DIR / Ac Country-Specific Component quisition de CERTIFICAT SSL IDA / 65730 : Improving and modernizing Post Direct Selection Direct 1,964.00 0.00 Canceled 2022-04-05 2022-04-10 2022-05-01 2022-06-15 de type EV physical and statistical infra structure BF-INSD-283145-GO-RFQ / A cquisition de matériels et fou Project Management and Mo Request for Quota Single Stage - One E IDA / 65730 Post Limited 52,313.00 0.00 Canceled 2022-04-25 2022-06-20 2022-07-11 rnitures diverses au profit de nitoring and Evaluation tions nvelope s structures de mise en œuvr e du PHASAO Regional component: Harmo BF-INSD-176141-GO-RFQ / F nization, Data Collection, Qu ourniture de vaccin et de boit Request for Quota Single Stage - One E IDA / 65730 ality Improvement, Dissemin Post Limited 13,445.00 0.00 Canceled 2021-04-05 2021-05-10 2021-06-09 e à pharmacie dans le cadre tions nvelope ation and Use of Core Social des enquêtes ménages and Economic Statistics Regional component: Harmo BF-INSD-215375-GO-RFB / fo nization, Data Collection, Qu urniture de matériels IEC pou Single Stage - One E IDA / 65730 ality Improvement, Dissemin Post Request for Bids Open - National 146,000.00 0.00 Canceled 2021-04-26 2021-05-01 2021-05-31 2021-06-15 2021-07-20 2021-10-18 r les enquêtes emploi , ména nvelope ation and Use of Core Social ges et pour le MAAH and Economic Statistics BF-INSD-284209-GO-RFQ / A Regional component: Harmo cquisition de matériels d'arch nization, Data Collection, Qu Request for Quota Single Stage - One E ivage numérique des actes a IDA / 65730 ality Improvement, Dissemin Post Limited 43,636.00 0.00 Canceled 2022-05-10 2022-06-02 2022-07-17 tions nvelope dministratifs et autres docum ation and Use of Core Social ents administratifs and Economic Statistics Regional component: Harmo BF-INSD-175415-GO-RFQ / fo nization, Data Collection, Qu Request for Quota Single Stage - One E urnitures de matériels de bur IDA / 65730 ality Improvement, Dissemin Post Limited 15,000.00 0.00 Canceled 2021-05-08 2021-06-13 2021-07-13 tions nvelope eau pour l'UGP ation and Use of Core Social and Economic Statistics Page 3 Regional component: Harmo BF-INSD-283163-GO-RFQ / a nization, Data Collection, Qu Request for Quota Single Stage - One E cquisition d'équipement de p IDA / 65730 ality Improvement, Dissemin Post Limited 6,355.00 0.00 Canceled 2022-04-10 2022-06-05 2022-06-26 tions nvelope rotection contre la COVID-19 ation and Use of Core Social and Economic Statistics BF-INSD-216315-GO-RFB / F Country-Specific Component ourniture, installation et mise : Improving and modernizing Single Stage - One E IDA / 65730 Post Request for Bids Open - National 245,000.00 0.00 Canceled 2021-06-01 2021-06-06 2021-07-06 2021-07-21 2021-08-25 2021-12-23 en service des équipements physical and statistical infra nvelope d’interconnexion de l’INSD a structure vec les quatre DR BF-INSD-216319-GO-RFB / M Country-Specific Component ettre en place un centre d’ap : Improving and modernizing Single Stage - One E Under Imple IDA / 65730 Post Request for Bids Open - National 410,000.00 0.00 2023-03-30 2023-06-15 2023-04-04 2023-05-04 2023-05-19 2023-06-23 2023-09-21 pel pour la réalisation des en physical and statistical infra nvelope mentation quêtes par téléphone structure BF-INSD-338713-GO-RFB / E Regional component: Harmo quiper les CEB er les DREPS nization, Data Collection, Qu Open - Internationa Single Stage - One E Under Imple en matériels pour la collecte IDA / 65730 ality Improvement, Dissemin Prior Request for Bids 2,578,955.00 0.00 2023-03-31 2023-04-10 2023-04-05 2023-05-19 2023-05-20 2023-06-03 2023-07-08 2023-11-05 l nvelope mentation et la saisie des données stati ation and Use of Core Social stiques and Economic Statistics Regional component: Harmo BF-INSD-346019-GO-RFQ / A nization, Data Collection, Qu Request for Quota Single Stage - One E Under Imple cquisition de panneaux solair IDA / 65730 ality Improvement, Dissemin Post Limited 98,181.00 0.00 2023-04-05 2023-03-30 2023-05-02 2023-06-16 tions nvelope mentation es portables ation and Use of Core Social and Economic Statistics BF-INSD-353001-GO-RFQ / A Country-Specific Component Request for Quota Single Stage - One E Pending Impl cquisition de certificat de séc IDA / 65730 : Improving and modernizing Post Limited 5,454.55 0.00 2023-05-30 2023-07-01 2023-07-31 tions nvelope ementation urité SSL EV physical and statistical infra structure BF-INSD-360195-GO-RFQ / A Project Management and Mo Request for Quota Single Stage - One E Pending Impl cquisition de matériels d'arch IDA / 65730 Post Limited 27,272.72 0.00 2023-07-15 2023-08-17 2023-10-16 nitoring and Evaluation tions nvelope ementation ivage des questionnaires des RGPH BF-INSD-360207-GO-RFQ / A Country-Specific Component Request for Quota Single Stage - One E Pending Impl cquisition et installation de cl IDA / 65730 : Improving and modernizing Post Limited 63,636.36 0.00 2023-07-25 2023-08-29 2023-10-28 tions nvelope ementation imatiseurs au profit de l'INSD physical and statistical infra structure BF-INSD-360214-GO-RFQ / A Country-Specific Component Request for Quota Single Stage - One E Pending Impl cquisition de fournitures de b IDA / 65730 : Improving and modernizing Post Limited 54,545.45 0.00 2023-07-25 2023-08-29 2023-09-30 tions nvelope ementation ureau au profit de l'INSD physical and statistical infra structure BF-INSD-360220-GO-RFQ / A Country-Specific Component Request for Quota Single Stage - One E Pending Impl cquisition de mobiliers de bur IDA / 65730 : Improving and modernizing Post Limited 45,454.54 0.00 2023-07-25 2023-09-01 2023-10-16 tions nvelope ementation eau au profit de l'INSD physical and statistical infra structure BF-INSD-360232-GO-RFQ / A Country-Specific Component Request for Quota Single Stage - One E Pending Impl cquisition d'antivirus au profi IDA / 65730 : Improving and modernizing Post Limited 12,727.27 0.00 2023-07-15 2023-08-19 2023-09-18 tions nvelope ementation t des Directions régionales d physical and statistical infra e l'INSD structure BF-INSD-360236-GO-RFQ / A Country-Specific Component cquisition de consommables i : Improving and modernizing Request for Quota Single Stage - One E Pending Impl IDA / 65730 Post Limited 54,545.45 0.00 2023-07-25 2023-08-29 2023-10-13 nformatiques et spécifiques physical and statistical infra tions nvelope ementation au profit de l'INSD structure NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Regional component: Harmo BF-INSD-175402-NC-RFQ / L nization, Data Collection, Qu Request for Quota Single Stage - One E Pending Impl ocation de bureau pour l'unit IDA / 65730 ality Improvement, Dissemin Post Limited 30,000.00 0.00 2021-03-06 2021-04-20 2022-04-20 tions nvelope ementation é de gestion du projet. ation and Use of Core Social and Economic Statistics Regional component: Harmo BF-INSD-215338-NC-RFQ / C nization, Data Collection, Qu ontrat d'assurances travail p Request for Quota Single Stage - One E Pending Impl IDA / 65730 ality Improvement, Dissemin Post Limited 75,500.00 0.00 2021-02-13 2021-04-10 2022-04-05 our les-enquêtes emploi, IHP tions nvelope ementation ation and Use of Core Social C et ménage and Economic Statistics BF-INSD-175435-NC-RFQ / S Project Management and Mo Request for Quota Single Stage - One E Pending Impl ociété de gardiennage pour l IDA / 65730 Post Limited 10,000.00 0.00 2021-04-25 2021-05-27 2023-05-27 nitoring and Evaluation tions nvelope ementation a sécurité des bureaux de l'U GP BF-INSD-175440-NC-RFQ / S Project Management and Mo Request for Quota Single Stage - One E Pending Impl ociété d'entretien et de netto IDA / 65730 Post Limited 14,000.00 0.00 2020-06-27 2020-08-03 2022-08-03 nitoring and Evaluation tions nvelope ementation yage des bureaux de l'UGP BF-INSD-177154-NC-RFQ / R Project Management and Mo Request for Quota Single Stage - One E eproduction de rapports pour IDA / 65770 Post Limited 25,210.00 0.00 Canceled 2020-12-20 2021-02-14 2021-03-16 nitoring and Evaluation tions nvelope l’enquête emploi BF-INSD-177175-NC-RFQ / re Project Management and Mo Request for Quota Single Stage - One E IDA / 65770 Post Limited 1,008.00 0.00 Canceled 2020-07-20 2020-09-01 2020-09-16 prographies pour ICC nitoring and Evaluation tions nvelope BF-INSD-216326-NC-DIR / Ex Country-Specific Component Pending Impl ternalisation de la sauvegard IDA / 65730 : Improving and modernizing Post Direct Selection Direct 100,000.00 0.00 2021-06-21 2021-06-26 2021-07-31 2023-07-21 ementation e des données de l’INSD (loc physical and statistical infra ation de serveur) structure Regional component: Harmo BF-INSD-215392-NC-RFB / Lo nization, Data Collection, Qu cation de véhicules - Enquête Open - Internationa Single Stage - One E IDA / 65730 ality Improvement, Dissemin Post Request for Bids 1,038,000.00 0.00 Canceled 2021-04-23 2021-04-28 2021-06-12 2021-06-27 2021-08-01 2022-07-27 Emploi,( DGESS MENAPLN et l nvelope ation and Use of Core Social Carto) et Enquête ménage and Economic Statistics Regional component: Harmo BF-INSD-267619-NC-RFQ / R nization, Data Collection, Qu Request for Quota Single Stage - One E eproduction des publications IDA / 65730 ality Improvement, Dissemin Post Limited 45,455.00 40,109.46 Signed 2021-12-19 2022-01-27 2022-01-06 2022-07-28 2022-01-11 tions nvelope de l'INSD ation and Use of Core Social and Economic Statistics BF-INSD-284285-NC-RFQ / M Project Management and Mo Request for Quota Single Stage - One E Pending Impl aintenance de matériels infor IDA / 65730 Post Limited 10,909.00 0.00 2022-05-15 2022-06-15 2022-12-12 nitoring and Evaluation tions nvelope ementation matiques et péri-informatiqu es Page 4 Regional component: Harmo BF-INSD-284291-NC-RFQ / I nization, Data Collection, Qu Request for Quota Single Stage - One E mpression des documents du IDA / 65730 ality Improvement, Dissemin Post Limited 24,818.00 20,998.52 Signed 2022-07-20 2022-08-03 2022-08-07 2022-09-03 2022-09-06 tions nvelope MSL et du RGA2 ation and Use of Core Social and Economic Statistics BF-INSD-281153-NC-RFQ / C Regional component: Harmo onfection de gadgets pour la nization, Data Collection, Qu Request for Quota Single Stage - One E visibilité de l’INSD dans le ca IDA / 65730 ality Improvement, Dissemin Post Limited 81,818.18 66,549.09 Signed 2022-03-15 2022-08-16 2022-04-11 2022-09-24 2022-05-02 tions nvelope dre de la mise en œuvre du P ation and Use of Core Social HASAO and Economic Statistics BF-INSD-283238-NC-RFQ / C Country-Specific Component Request for Quota Single Stage - One E onnexion internet haut débit IDA / 65730 : Improving and modernizing Post Limited 54,545.45 38,195.58 Signed 2022-04-25 2022-08-17 2022-05-29 2022-09-23 2022-07-13 tions nvelope de l'INSD physical and statistical infra structure BF-INSD-216323-NC-DIR / Co Country-Specific Component nnexion haut débit du siège IDA / 65730 : Improving and modernizing Post Direct Selection Direct 54,545.00 0.00 Canceled 2021-05-26 2021-05-31 2021-07-05 2023-06-25 de l’INSD physical and statistical infra structure BF-INSD-318618-NC-RFQ / L Regional component: Harmo ocation de véhicule dans le c nization, Data Collection, Qu Request for Quota Single Stage - One E adre de l'Enquête de base su IDA / 65730 ality Improvement, Dissemin Post Limited 294,545.45 0.00 Signed 2022-10-21 2022-11-04 2022-11-06 2023-02-04 tions nvelope r l'emploi et le secteur inform ation and Use of Core Social el and Economic Statistics BF-INSD-322171-NC-RFQ / R ecrutement d'une agence de Regional component: Harmo communication pour couvrir l nization, Data Collection, Qu Request for Quota Single Stage - One E es activités de l'enquête emp IDA / 65730 ality Improvement, Dissemin Post Limited 160,418.18 0.00 Signed 2022-10-28 2022-11-02 2022-11-13 2022-12-13 tions nvelope loi, du recensement général ation and Use of Core Social de l'agriculture et des activit and Economic Statistics és du Ministère en charge de l'Education nationale BF-INSD-338595-NC-RFQ / R Regional component: Harmo éalisation et diffusion d'un fil nization, Data Collection, Qu Request for Quota Single Stage - One E Pending Impl m documentaire sur les missi IDA / 65730 ality Improvement, Dissemin Post Limited 18,182.00 0.00 2023-04-20 2023-05-12 2023-07-11 tions nvelope ementation ons et les réalisations de l'IN ation and Use of Core Social SD and Economic Statistics BF-INSD-338608-NC-RFQ / A Country-Specific Component Request for Quota Single Stage - One E Pending Impl cquérir une connexion de typ IDA / 65730 : Improving and modernizing Post Limited 72,727.00 0.00 2023-06-06 2023-06-28 2023-08-12 tions nvelope ementation e dédié pour l'INSD physical and statistical infra structure BF-INSD-338616-NC-RFQ / R Country-Specific Component Request for Quota Single Stage - One E Pending Impl enouveler la licence de l'anti IDA / 65730 : Improving and modernizing Post Limited 21,818.00 0.00 2023-06-20 2023-07-12 2023-08-11 tions nvelope ementation virus réseau de l'INSD physical and statistical infra structure Regional component: Harmo BF-INSD-338650-NC-RFQ / A nization, Data Collection, Qu Request for Quota Single Stage - One E Pending Impl cquisition de serveur pour la IDA / 65730 ality Improvement, Dissemin Post Limited 36,364.00 0.00 2023-05-06 2023-05-28 2023-07-12 tions nvelope ementation digitalisation ation and Use of Core Social and Economic Statistics Regional component: Harmo BF-INSD-338688-NC-RFQ / C nization, Data Collection, Qu onfection de banderoles et c Request for Quota Single Stage - One E Pending Impl IDA / 65730 ality Improvement, Dissemin Post Limited 9,091.00 0.00 2023-04-19 2023-05-11 2023-06-01 ouverture publicitaire (charg tions nvelope ementation ation and Use of Core Social es publicitaires) and Economic Statistics Regional component: Harmo BF-INSD-283209-NC-RFQ / E nization, Data Collection, Qu Request for Quota Single Stage - One E ntretien de véhicules au profi IDA / 65730 ality Improvement, Dissemin Post Limited 7,273.00 0.00 Canceled 2022-04-04 2022-05-30 2022-11-26 tions nvelope t du MENAPLN ation and Use of Core Social and Economic Statistics BF-INSD-234163-NC-DIR / An Regional component: Harmo alyse des prélèvements de s nization, Data Collection, Qu ang de l'enquête démographi IDA / 65730 ality Improvement, Dissemin Post Direct Selection Direct 118,200.00 0.00 Canceled 2021-06-07 2021-06-12 2021-07-17 2021-09-15 que de santé au Burkina Fas ation and Use of Core Social o EDSBF-2021 and Economic Statistics BF-INSD-177147-NC-DIR / Li Project Management and Mo aison internet entre le siège IDA / 65730 Post Direct Selection Direct 244,900.00 0.00 Canceled 2021-04-01 2021-04-06 2021-05-11 2022-05-06 nitoring and Evaluation de l'INSD et ses directions ré gionales Regional component: Harmo BF-INSD-219697-NC-RFQ / R nization, Data Collection, Qu eproduction , impression et é Request for Quota Single Stage - One E Pending Impl IDA / 65730 ality Improvement, Dissemin Post Limited 545,455.00 0.00 2021-04-17 2021-06-12 2022-06-07 dition des documents de l'IN tions nvelope ementation ation and Use of Core Social SD and Economic Statistics BF-INSD-338689-NC-RFQ / R Regional component: Harmo ecrutement d'une agence de nization, Data Collection, Qu Request for Quota Single Stage - One E Pending Impl communication pour la couve IDA / 65730 ality Improvement, Dissemin Post Limited 172,727.27 0.00 2023-02-25 2023-03-26 2023-06-24 tions nvelope ementation rture médiatique de recense ation and Use of Core Social ment général des entreprises and Economic Statistics (RGE) Regional component: Harmo BF-INSD-283204-NC-RFQ / L nization, Data Collection, Qu Request for Quota Single Stage - One E ocation de véhicules au profit IDA / 65730 ality Improvement, Dissemin Post Limited 21,818.18 0.00 Signed 2022-04-20 2023-03-21 2022-06-15 2023-06-10 tions nvelope du MENAPLN ation and Use of Core Social and Economic Statistics CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Country-Specific Component BF-INSD-177236-CS-LCS / Au Least Cost Selecti Pending Impleme IDA / 65730 : Improving and modernizing Post Open - National 50,000.00 0.00 2021-03-26 2021-04-16 2021-05-08 2021-05-23 2021-06-07 2021-06-29 2021-07-21 2021-09-19 dit de l'enquête ménage on ntation physical and statistical infra structure BF-INSD-177237-CS-LCS / Au Regional component: Harmo dit comptable, financier et de nization, Data Collection, Qu Least Cost Selecti passation de marchés du proj IDA / 65730 ality Improvement, Dissemin Post Open - National 50,000.00 16,895.68 Completed 2020-07-15 2021-05-11 2020-08-05 2021-11-11 2020-08-27 2022-03-03 2020-09-11 2022-04-14 2020-09-26 2022-04-25 2020-10-18 2022-05-27 2020-11-09 2022-06-01 2020-12-24 2022-07-19 on et- exercie 2020, 2021 et 20 ation and Use of Core Social 22 and Economic Statistics Page 5 BF-INSD-247466-CS-CQS / S Regional component: Harmo élection d'un consultant pour nization, Data Collection, Qu Consultant Qualifi l'élaboration du statut et de l IDA / 65730 ality Improvement, Dissemin Post Open - National 36,400.00 30,527.83 Signed 2021-08-23 2021-10-07 2021-09-13 2021-10-07 2022-07-26 2021-11-06 2022-09-06 2021-12-11 2022-09-23 2022-01-25 cation Selection a stratégie d'abondement du ation and Use of Core Social fond de développement de la and Economic Statistics statistique (FDS) BF-INSD-240246-CS-CQS / Él Country-Specific Component Consultant Qualifi Under Implement aboration de la politique de s IDA / 65730 : Improving and modernizing Post Limited 25,000.00 0.00 2021-07-14 2021-10-07 2021-07-19 2022-08-22 2021-08-02 2022-10-27 2021-08-30 2021-10-29 cation Selection ation écurité du système d’informa physical and statistical infra tion structure BF-INSD-240235-CS-CQS / R Country-Specific Component ecrutement d’un cabinet pou : Improving and modernizing Consultant Qualifi IDA / 65730 Post Limited 30,000.00 26,255.19 Signed 2021-08-23 2022-04-11 2021-09-06 2022-04-11 2021-09-16 2022-05-31 2021-09-30 2022-06-10 2022-01-28 r l’élaboration du Schéma dir physical and statistical infra cation Selection ecteur de l’informatique (SDI structure -2021-2025) BF-INSD-284664-CS-CQS / R Regional component: Harmo ecrutement d'un consultant p nization, Data Collection, Qu Consultant Qualifi Pending Impleme our la réalisation d'une étude IDA / 65730 ality Improvement, Dissemin Post Open - National 36,363.00 0.00 2022-06-30 2022-07-14 2022-07-26 2022-08-05 2022-08-20 2022-10-04 cation Selection ntation sur la déconcentration de l'IN ation and Use of Core Social SD and Economic Statistics BF-INSD-284945-CS-CQS / re crutement d'un consultant en Project Management and Mo Consultant Qualifi vue de l'élaboration de la car IDA / 65730 Post Open - National 57,272.00 0.00 Canceled 2022-08-10 2022-08-24 2022-09-08 2022-09-15 2022-10-04 2022-11-18 nitoring and Evaluation cation Selection tographie des risques et le pl an de mitigation du PHASAO BF-INSD-216673-CS-CQS / S Regional component: Harmo élection du consultant pour l' nization, Data Collection, Qu Consultant Qualifi élaboration du statut et relec IDA / 65730 ality Improvement, Dissemin Post Open - National 27,300.00 0.00 Canceled 2021-06-01 2021-08-10 2021-06-22 2021-11-11 2021-08-05 2021-09-04 2021-10-09 2021-12-08 cation Selection ture de l'organigramme de l'I ation and Use of Core Social NSD and Economic Statistics BF-INSD-284980-CS-CQS / re Regional component: Harmo crutement d'un consultant po nization, Data Collection, Qu Consultant Qualifi ur la réalisation de la rétrosp IDA / 65730 ality Improvement, Dissemin Post Open - National 49,818.00 0.00 Signed 2022-07-25 2022-06-22 2022-08-08 2022-08-23 2022-10-26 2022-09-02 2022-10-26 2022-09-17 2022-11-16 cation Selection ective macro-économique du ation and Use of Core Social Burkina Faso and Economic Statistics BF-INSD-315083-CS-CQS / R Country-Specific Component ecrutement d'un consultant i : Improving and modernizing Consultant Qualifi Under Implement IDA / 65730 Post Limited 36,363.63 0.00 2022-10-12 2022-12-08 2022-10-19 2022-10-29 2022-11-13 2022-12-28 ndividuel pour l'élaboration d physical and statistical infra cation Selection ation u statut et de l'organigramm structure e de l'INSD BF-INSD-318599-CS-CQS / R Regional component: Harmo ecrutement d'un cabinet pou nization, Data Collection, Qu Consultant Qualifi Under Implement r la relecture de la charte gra IDA / 65730 ality Improvement, Dissemin Post Limited 18,181.81 0.00 2022-10-24 2022-10-26 2022-11-07 2023-02-10 2022-11-22 2023-03-13 2022-12-02 2023-01-01 cation Selection ation phique de l'Institut national d ation and Use of Core Social e la statistique et de la démo and Economic Statistics graphie BF-INSD-338843-CS-CQS / R Regional component: Harmo ecrutement d'un Consultant nization, Data Collection, Qu Consultant Qualifi Pending Impleme pour appuyer l'équipe nation IDA / 65730 ality Improvement, Dissemin Post Limited 32,727.00 0.00 2023-03-01 2023-03-06 2023-03-13 2023-03-27 2023-06-25 cation Selection ntation ale à la réalisation du recens ation and Use of Core Social ement des structures éducati and Economic Statistics ves BF-INSD-284969-CS-CQS / R Regional component: Harmo ecrutement d'un consultant p nization, Data Collection, Qu Consultant Qualifi Pending Impleme our l'élaboration d'un cadre d IDA / 65730 ality Improvement, Dissemin Post Limited 36,363.00 0.00 2023-07-03 2023-07-08 2023-07-15 2023-07-27 2023-07-31 cation Selection ntation 'assurance qualité et d'un ma ation and Use of Core Social nuel de procédures techniqu and Economic Statistics e du SSN BF-INSD-312667-CS-CQS / R Country-Specific Component éalisation d'une étude archit : Improving and modernizing Consultant Qualifi Under Implement ecturale pour la rénovation IDA / 65730 Post Limited 145,455.00 0.00 2023-04-05 2023-03-23 2023-04-10 2023-04-17 2023-05-01 2023-06-15 physical and statistical infra cation Selection ation des locaux de l'Institut Natio structure nal de la Statistique et de la démographie BF-INSD-314785-CS-CQS / R Regional component: Harmo ecrutement d'un consultant e nization, Data Collection, Qu Consultant Qualifi n vue de développer les capa IDA / 65730 ality Improvement, Dissemin Post Limited 36,364.00 0.00 Canceled 2023-05-08 2023-05-13 2023-05-20 2023-06-03 2023-07-18 cation Selection cités de l'INSD à l'utilisation ation and Use of Core Social des méga données dans la pr and Economic Statistics oduction statistique BF-INSD-304863-CS-CQS / R Regional component: Harmo ecrutement d’un cabinet pou nization, Data Collection, Qu r la réalisation d’une étude d Consultant Qualifi Under Implement IDA / 65730 ality Improvement, Dissemin Post Limited 11,454.00 0.00 2023-08-07 2023-04-10 2023-08-12 2023-08-19 2023-09-02 2023-10-02 e faisabilité et de mise en œ cation Selection ation ation and Use of Core Social uvre de l’interconnexion du s and Economic Statistics iège de l’INSD avec ses Direc tions régionales BF-INSD-338866-CS-CQS / R Regional component: Harmo ecrutement d'un cabinet pou nization, Data Collection, Qu Consultant Qualifi Pending Impleme r l'élaboration d'un nouveau IDA / 65730 ality Improvement, Dissemin Post Limited 50,000.00 0.00 2023-05-10 2023-05-15 2023-05-29 2023-06-12 2023-08-11 cation Selection ntation modèle de prévision des rece ation and Use of Core Social ttes and Economic Statistics BF-INSD-240242-CS-CQS / C Country-Specific Component onception de spots publicitair : Improving and modernizing Consultant Qualifi es pour les enquêtes ménage IDA / 65760 Post Limited 15,000.00 0.00 Canceled 2021-08-14 2021-09-13 physical and statistical infra cation Selection s, enquête emploi et enquête structure démographique et de santé ( EDS) BF-INSD-347456-CS-CQS / R Regional component: Harmo ecrutement d'un consultant p nization, Data Collection, Qu Consultant Qualifi Under Implement our l’élaboration du rapport d IDA / 65730 ality Improvement, Dissemin Post Limited 31,091.00 0.00 2023-04-25 2023-04-10 2023-04-30 2023-05-14 2023-05-26 2023-09-23 cation Selection ation e l’étude rétrospective politiq ation and Use of Core Social ue du Burkina Faso and Economic Statistics Regional component: Harmo BF-INSD-351479-CS-CQS / R nization, Data Collection, Qu ecrutement d'un cabinet pou Consultant Qualifi Under Implement IDA / 65730 ality Improvement, Dissemin Post Limited 36,363.63 0.00 2023-04-20 2023-04-10 2023-04-27 2023-05-04 2023-05-16 2023-07-15 r la conception et la mise en cation Selection ation ation and Use of Core Social place d'un WebSIG and Economic Statistics INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BF-INSD-177190-CS-INDV / r Country-Specific Component Individual Consult ecrutement d'un chef de proj IDA / 65730 : Improving and modernizing Post Open 36,000.00 0.00 Canceled 2020-06-30 2020-07-26 2020-08-16 2020-09-10 2020-10-10 ant Selection et physical and statistical infra structure Page 6 Regional component: Harmo BF-INSD-177193-CS-INDV / R nization, Data Collection, Qu Individual Consult ecrutement d'un spécialiste e IDA / 65730 ality Improvement, Dissemin Post Open 21,000.00 0.00 Canceled 2020-06-30 2020-07-26 2020-08-09 2020-08-31 2020-09-30 ant Selection n passation de marchés ation and Use of Core Social and Economic Statistics Regional component: Harmo BF-INSD-177197-CS-INDV / R nization, Data Collection, Qu Individual Consult ecrutement d'un spécialiste e IDA / 65730 ality Improvement, Dissemin Post Open 21,000.00 0.00 Canceled 2020-06-30 2020-08-03 2020-08-18 2020-09-04 2020-10-04 ant Selection n gestion financière ation and Use of Core Social and Economic Statistics Regional component: Harmo BF-INSD-177199-CS-INDV / R nization, Data Collection, Qu Individual Consult ecrutement d'un spécialiste e IDA / 65730 ality Improvement, Dissemin Post Open 21,000.00 0.00 Canceled 2020-06-30 2020-07-29 2020-08-13 2020-09-04 2020-10-04 ant Selection n suivi-évaluation ation and Use of Core Social and Economic Statistics Regional component: Harmo BF-INSD-177203-CS-INDV / r nization, Data Collection, Qu Individual Consult ecrutement d'un Auditeur Int IDA / 65730 ality Improvement, Dissemin Post Open 21,000.00 0.00 Canceled 2020-06-30 2020-08-03 2020-08-18 2020-09-09 2020-10-09 ant Selection erne ation and Use of Core Social and Economic Statistics BF-INSD-177204-CS-INDV / R Country-Specific Component Individual Consult ecrutement d'un comptable IDA / 65730 : Improving and modernizing Post Open 14,000.00 0.00 Canceled 2020-06-30 2020-08-03 2020-08-17 2020-09-08 2020-10-08 ant Selection pour l'UGP physical and statistical infra structure BF-INSD-177206-CS-INDV / R Country-Specific Component Individual Consult ecrutement d'un Assistant Ad IDA / 65730 : Improving and modernizing Post Open 9,500.00 0.00 Canceled 2020-06-30 2020-08-03 2020-08-18 2020-09-09 2020-10-09 ant Selection ministratif physical and statistical infra structure BF-INSD-177207-CS-INDV / R Country-Specific Component Individual Consult ecrutement du personnel d'a IDA / 65730 : Improving and modernizing Post Limited 21,000.00 0.00 Canceled 2020-06-30 2020-07-05 2020-07-26 2020-08-30 2020-09-29 ant Selection ppui pour l'UGP physical and statistical infra structure BF-INSD-177220-CS-INDV / C Country-Specific Component onsultant pour l'évaluation fi : Improving and modernizing Individual Consult IDA / 65770 Post Limited 45,500.00 0.00 Canceled 2020-06-30 2020-07-05 2020-07-20 2020-08-11 2020-09-10 nal du SDS 2016-2020 et éla physical and statistical infra ant Selection boration du SDS 2021-2025 structure Regional component: Harmo BF-INSD-177230-CS-INDV / E nization, Data Collection, Qu Individual Consult laboration du manuel opérati IDA / 65740 ality Improvement, Dissemin Post Open 13,000.00 0.00 Canceled 2020-06-30 2020-08-03 2020-08-18 2020-09-09 2020-10-09 ant Selection onnel du projet ation and Use of Core Social and Economic Statistics BF-INSD-216344-CS-INDV / C onsultant pour la formation e Regional component: Harmo n passation de marchés suiv nization, Data Collection, Qu Individual Consult Under Implement ant le nouveau règlement de IDA / 65730 ality Improvement, Dissemin Post Limited 50,000.00 0.00 2021-04-01 2022-10-28 2021-04-06 2021-04-27 2021-06-01 2021-06-16 ant Selection ation passation de marchés de la B ation and Use of Core Social anque Mondiale au profit des and Economic Statistics acteurs de la chaine de pass ation du projet BF-INSD-216664-CS-INDV / R Regional component: Harmo ecrutement d'un consultant p nization, Data Collection, Qu Individual Consult our l’élaboration d'un manuel IDA / 65730 ality Improvement, Dissemin Post Open 30,250.00 15,765.46 Completed 2021-06-30 2021-06-30 2021-08-18 2022-04-27 2021-09-08 2022-05-10 2021-09-30 2022-05-25 2021-10-30 2022-08-23 ant Selection de suivi évaluation du Projet ation and Use of Core Social et la mise en place d'un disp and Economic Statistics ositif de suivi-évaluation. BF-INSD-219711-CS-INDV / C onsultant individuel pour une Project Management and Mo Individual Consult IDA / 65730 Post Direct 22,500.00 19,689.83 Completed 2021-02-25 2021-03-22 2021-03-07 2021-04-20 2021-03-28 2021-05-05 2021-05-02 2021-07-27 2021-08-30 2021-11-05 assistance technique en pass nitoring and Evaluation ant Selection ation de marchés BF-INSD-216338-CS-INDV / C Country-Specific Component onsultant pour la conception : Improving and modernizing Individual Consult de spot publicitaire pour les IDA / 65730 Post Limited 15,000.00 0.00 Canceled 2021-04-30 2021-05-05 2021-05-26 2021-06-30 2021-08-14 physical and statistical infra ant Selection enquêtes ménages, enquête structure emploi et enquête démograp hique et de santé (EDS) Regional component: Harmo BF-INSD-177235-CS-INDV / A nization, Data Collection, Qu ctualisation de la politique de Individual Consult IDA / 65730 ality Improvement, Dissemin Post Open 10,000.00 0.00 Canceled 2021-03-29 2021-05-02 2021-05-17 2021-06-08 2021-08-07 sécurité du système d'inform ant Selection ation and Use of Core Social ation de l'INSD and Economic Statistics BF-INSD-216674-CS-INDV / S Regional component: Harmo élection d'un consultant pour nization, Data Collection, Qu Individual Consult l'élaboration du statut et de l IDA / 65730 ality Improvement, Dissemin Post Open 36,400.00 0.00 Canceled 2021-06-01 2021-07-20 2021-08-10 2021-09-14 2021-11-13 ant Selection a stratégie d'abondement du ation and Use of Core Social fond de développement de la and Economic Statistics statistique (FDS) BF-INSD-177214-CS-INDV / C onsultants pour réalisation d' Country-Specific Component analyses thématiques approf : Improving and modernizing Individual Consult IDA / 65730 Post Open 25,210.00 0.00 Canceled 2021-06-08 2021-07-12 2021-07-27 2021-08-18 2021-09-17 ondies de données secondair physical and statistical infra ant Selection es pour soutenir la mise en structure œuvre des politiques publiqu es BF-INSD-240207-CS-INDV / R Project Management and Mo Individual Consult Pending Impleme ecrutement d’un spécialiste IDA / 65760 Post Open 21,000.00 0.00 2021-06-30 2021-08-02 2021-08-09 2021-08-23 2022-08-23 nitoring and Evaluation ant Selection ntation en passation des marchés BF-INSD-240209-CS-INDV / R Project Management and Mo Individual Consult Pending Impleme ecrutement d’un spécialiste IDA / 65760 Post Open 21,000.00 0.00 2021-08-24 2021-09-26 2021-10-03 2021-10-17 2022-10-17 nitoring and Evaluation ant Selection ntation en gestion financière BF-INSD-240216-CS-INDV / R Project Management and Mo Individual Consult Pending Impleme IDA / 65760 Post Open 14,000.00 0.00 2021-08-24 2021-09-19 2021-09-26 2021-10-10 2022-10-10 ecrutement d’un comptable nitoring and Evaluation ant Selection ntation BF-INSD-284581-CS-INDV / r Regional component: Harmo ecrutement d'un consultant p nization, Data Collection, Qu our faire la refonte de la plat Individual Consult Under Implement IDA / 65730 ality Improvement, Dissemin Post Limited 4,909.00 0.00 2022-08-10 2022-07-19 2022-08-15 2022-12-01 2022-08-29 2023-02-07 2022-09-17 2022-11-01 eforme de diffusion des micr ant Selection ation ation and Use of Core Social o-données avec l'outil NADA and Economic Statistics et former le personnel de l'IN SD aux techniques d'archiva ge Page 7 BF-INSD-284680-CS-INDV / R ecrutement d'un consultant p our la réalisation d'une étude Regional component: Harmo d'évaluation des performanc nization, Data Collection, Qu Individual Consult es de prévision des sources d IDA / 65730 ality Improvement, Dissemin Post Limited 34,909.00 0.00 Signed 2022-07-15 2022-07-18 2022-07-20 2022-09-09 2022-07-30 2022-10-25 2022-08-14 2022-09-28 ant Selection e données du modèle IAP, dé ation and Use of Core Social velopper un module TCEI de l and Economic Statistics 'IAP et modéliser et construir e un module TOFE consolidé avec l’intégration des sous BF-INSD-284942-CS-INDV / R Regional component: Harmo ecrutement d'un consultant p nization, Data Collection, Qu our la réalisation d'une étude Individual Consult IDA / 65730 ality Improvement, Dissemin Post Limited 11,454.00 0.00 Canceled 2022-08-25 2022-08-30 2022-09-09 2022-09-24 2022-11-23 de faisabilité et de mise en ant Selection ation and Use of Core Social œuvre de l'interconnexion du and Economic Statistics siège de l'INSD avec les DR-I NSD BF-INSD-284965-CS-INDV / R Regional component: Harmo ecrutement d'un consultant i nization, Data Collection, Qu Individual Consult Pending Impleme ndividuel pour la formation d IDA / 65730 ality Improvement, Dissemin Post Limited 7,772.00 0.00 2022-07-15 2022-07-20 2022-07-30 2022-08-14 2022-09-04 ant Selection ntation u personnel du service charg ation and Use of Core Social é de la diffusion en webmast and Economic Statistics er BF-INSD-284977-CS-INDV / R ecrutement d'un consultant i Project Management and Mo Individual Consult Under Implement IDA / 65730 Post Limited 9,090.00 0.00 2022-07-25 2022-09-29 2022-07-30 2022-08-09 2022-08-24 2022-10-08 ndividuel pour l'élaboration d nitoring and Evaluation ant Selection ation e la stratégie de communicat ion du projet BF-INSD-177217-CS-INDV / E Country-Specific Component valuation du plan de formatio : Improving and modernizing Individual Consult n 2015-2020 du personnel du IDA / 65730 Post Open 31,933.00 0.00 Canceled 2021-04-28 2021-08-10 2021-06-01 2021-06-16 2021-07-03 2021-08-02 physical and statistical infra ant Selection système statistique national structure et élaboration du plan de for mation 2021-2025 BF-INSD-177219-CS-INDV / E Country-Specific Component Individual Consult laboration et adoption du sta IDA / 65730 : Improving and modernizing Post Open 25,210.00 0.00 Canceled 2021-07-12 2021-08-15 2021-08-30 2021-09-21 2021-10-21 ant Selection tut particulier du statisticien physical and statistical infra structure BF-INSD-182528-CS-INDV / R Project Management and Mo Individual Consult IDA / 65730 Post Open 9,076.00 0.00 Canceled 2021-05-28 2021-07-01 2021-07-16 2021-08-07 2021-09-06 ecrutement aide comptable. nitoring and Evaluation ant Selection BF-INSD-216670-CS-INDV / R ecrutement d'un consultant i Project Management and Mo Individual Consult nternational pour l'appui à la IDA / 65730 Post Open 27,300.00 0.00 Canceled 2021-06-22 2021-06-16 2021-08-10 2021-11-11 2021-08-31 2021-10-05 2022-02-02 nitoring and Evaluation ant Selection mise en œuvre d'un système permanent d'enquêtes sur l'e mploi BF-INSD-295493-CS-CDS / R ecrutement d'experts interna Country-Specific Component tionaux en vue d’appuyer l’IN : Improving and modernizing Under Implement SD dans la réalisation du RG IDA / 65730 Post Direct Selection Direct 115,729.00 0.00 2022-06-01 2023-01-24 2022-06-11 2022-04-15 2022-08-15 2023-02-11 physical and statistical infra ation E, de ENESI, de l’ICC ? dans l structure a nomenclature de travail de la nouvelle base et du rebas age des comptes nationaux BF-INSD-295497-CS-INDV / R Regional component: Harmo ecrutement d'un consultant i nization, Data Collection, Qu ndividuel pour la formation d Individual Consult Pending Impleme IDA / 65730 ality Improvement, Dissemin Post Limited 9,694.00 0.00 2022-07-25 2022-07-30 2022-08-09 2022-08-26 2022-09-25 es cadres de l'INSD sur les ap ant Selection ntation ation and Use of Core Social proches sécurisées de collect and Economic Statistics e de données et de supervisi on en milieu d'insécurité BF-INSD-216672-CS-INDV / S Regional component: Harmo election d'un consultant pour nization, Data Collection, Qu Individual Consult Under Implement l'élaboration des projets de t IDA / 65730 ality Improvement, Dissemin Post Direct 36,363.00 0.00 2021-06-01 2022-07-19 2021-06-11 2022-11-23 2021-07-02 2021-08-06 2021-10-05 ant Selection ation extes d'application de la nou ation and Use of Core Social velle loi statistique and Economic Statistics BF-INSD-298771-CS-INDV / R ecrutement d'un consultant i Project Management and Mo Individual Consult ndividuel pour l'élaboration d IDA / 65730 Post Limited 20,909.00 0.00 Signed 2022-06-27 2022-06-10 2022-07-02 2022-08-19 2022-07-16 2022-10-25 2022-07-28 2022-09-11 nitoring and Evaluation ant Selection e la cartographie et du plan de mitigation des risques du PHASAO BF-INSD-312671-CS-INDV / S Regional component: Harmo élection d'un consultant indiv nization, Data Collection, Qu iduel pour appuyer le dévelo Individual Consult IDA / 65730 ality Improvement, Dissemin Post Limited 5,000.00 0.00 Canceled 2022-10-10 2022-10-15 2022-10-25 2022-11-11 2022-12-11 ppement des capacités de l'I ant Selection ation and Use of Core Social NSD à l'utilisation des mégad and Economic Statistics onnées dans la production de statistique officielle Regional component: Harmo BF-INSD-284560-CS-INDV / R nization, Data Collection, Qu ecrutement d'un consultant i Individual Consult IDA / 65730 ality Improvement, Dissemin Post Limited 18,181.81 0.00 Canceled 2022-10-20 2022-10-25 2022-11-04 2022-11-23 2023-01-22 ndividuel pour la relecture de ant Selection ation and Use of Core Social la charte graphique de l'INSD and Economic Statistics BF-INSD-318560-CS-INDV / R évision du Manuel de procéd Project Management and Mo Individual Consult Under Implement IDA / 65730 Post Limited 9,090.90 0.00 2022-10-20 2022-12-08 2022-10-25 2022-12-27 2022-10-30 2023-02-10 2022-11-11 2022-12-11 ures administratives, compta nitoring and Evaluation ant Selection ation bles et financiers du PHASAO BF-INSD-322173-CS-INDV / R Regional component: Harmo ecrutement d’un consultant nization, Data Collection, Qu Individual Consult Under Implement pour la conception d’un nouv IDA / 65730 ality Improvement, Dissemin Post Limited 27,272.72 0.00 2022-10-25 2022-10-20 2022-10-28 2022-11-02 2022-11-12 2022-12-12 ant Selection ation eau modèle de prévision de r ation and Use of Core Social ecettes budgétaires and Economic Statistics BF-INSD-325201-CS-INDV / R Regional component: Harmo ecrutement d'un consultant i nization, Data Collection, Qu Individual Consult Under Implement ndividuel en vue de l'élabora IDA / 65730 ality Improvement, Dissemin Post Limited 8,636.36 0.00 2022-11-15 2022-12-08 2022-11-20 2022-11-27 2022-12-07 2022-12-22 ant Selection ation tion du compte satellite du to ation and Use of Core Social urisme Burkinabè and Economic Statistics BF-INSD-284544-CS-INDV / r Regional component: Harmo ecrutement d'un consultant i nization, Data Collection, Qu Individual Consult ndividuel pour la conception IDA / 65730 ality Improvement, Dissemin Post Limited 36,364.00 0.00 Canceled 2023-07-03 2023-07-08 2023-07-15 2023-07-29 2023-09-27 ant Selection et la mise en place d'un web ation and Use of Core Social gis and Economic Statistics BF-INSD-338856-CS-INDV / R Regional component: Harmo ecrutement d'un consultant p nization, Data Collection, Qu our assurer la mise en place Individual Consult Under Implement IDA / 65730 ality Improvement, Dissemin Post Limited 18,182.00 0.00 2023-05-10 2023-04-10 2023-05-15 2023-05-22 2023-06-19 2023-12-16 d'une plateforme IMIS pour la ant Selection ation ation and Use of Core Social diffusion de données du 5èm and Economic Statistics e RGPH et des enquêtes Page 8 Regional component: Harmo BF-INSD-338859-CS-INDV / R nization, Data Collection, Qu ecrutement d'un consultant p Individual Consult Under Implement IDA / 65730 ality Improvement, Dissemin Post Limited 16,727.00 0.00 2023-06-12 2023-03-23 2023-06-17 2023-06-24 2023-07-08 2023-09-06 our améliorer l'ergonomie du ant Selection ation ation and Use of Core Social nouveau IAP and Economic Statistics BF-INSD-338863-CS-INDV / R Regional component: Harmo ecrutement d'un Consultant nization, Data Collection, Qu Individual Consult Under Implement pour développer un modèle d IDA / 65730 ality Improvement, Dissemin Post Limited 24,909.00 0.00 2023-06-12 2023-03-23 2023-06-17 2023-06-24 2023-07-08 2023-09-06 ant Selection ation e prévision macro économétr ation and Use of Core Social ique (moyen terme et long te and Economic Statistics rme) BF-INSD-338869-CS-INDV / R Regional component: Harmo ecrutement d'un assistant te nization, Data Collection, Qu chnique pour l'opérationnalis Individual Consult Under Implement IDA / 65730 ality Improvement, Dissemin Post Limited 23,636.00 0.00 2023-08-10 2023-03-23 2023-08-15 2023-08-22 2023-09-05 2023-10-20 ation du dispositif de suivi de ant Selection ation ation and Use of Core Social s prix et des coûts de transp and Economic Statistics ort de marchandises au Burki na Faso Regional component: Harmo BF-INSD-284959-CS-INDV / R nization, Data Collection, Qu ecrutement d'un consultant p Individual Consult IDA / 65730 ality Improvement, Dissemin Post Limited 18,181.00 0.00 Canceled 2022-07-01 2022-07-06 2022-07-16 2022-07-31 2022-09-14 our l'élaboration du cahier de ant Selection ation and Use of Core Social charge de l'interfaçage and Economic Statistics BF-INSD-284501-CS-CQS / R Regional component: Harmo ecrutement de consultant ind nization, Data Collection, Qu Individual Consult ividuel pour l'élaboration des IDA / 65730 ality Improvement, Dissemin Post Open 36,363.00 0.00 Canceled 2022-04-20 2022-05-23 2022-06-02 2022-06-23 2022-08-22 ant Selection textes d'application de la nou ation and Use of Core Social velle loi statistique and Economic Statistics BF-INSD-284573-CS-INDV / R ecrutement d'un consultant i Regional component: Harmo ndividuel pour former le pers nization, Data Collection, Qu Individual Consult onnel de l'INSD à l'édition de IDA / 65730 ality Improvement, Dissemin Post Limited 8,727.00 0.00 Canceled 2022-07-20 2022-07-25 2022-08-01 2022-08-20 2022-09-10 ant Selection s documents professionnel a ation and Use of Core Social vec l'application InDesign et and Economic Statistics en infographie avec Adobe P hotoshop et Illustrator public ation BF-INSD-284675-CS-INDV / R ecrutement d'un consultant i Regional component: Harmo ndividuel pour la formation d nization, Data Collection, Qu Individual Consult es chauffeur de l'INSD en con IDA / 65730 ality Improvement, Dissemin Post Limited 18,181.00 0.00 Canceled 2022-09-15 2022-09-20 2022-09-30 2022-10-15 2022-11-05 ant Selection duite opérationnelle de perso ation and Use of Core Social nnalité, gestion du risque séc and Economic Statistics uritaire et bonne tenue du vé hicule Regional component: Harmo BF-INSD-284962-CS-INDV / R nization, Data Collection, Qu ecrutement d'un consultant i Individual Consult IDA / 65730 ality Improvement, Dissemin Post Limited 36,363.00 0.00 Canceled 2022-07-01 2022-07-06 2022-07-16 2022-07-31 2022-09-14 ndividuel pour la réalisation ant Selection ation and Use of Core Social de l'interfaçage and Economic Statistics Regional component: Harmo BF-INSD-284547-CS-INDV / R nization, Data Collection, Qu ecrutement d'un consultant i Individual Consult IDA / 65730 ality Improvement, Dissemin Post Limited 27,273.00 0.00 Canceled 2022-07-15 2022-07-20 2022-08-03 2022-08-22 2022-10-21 ndividuel pour la mise en pla ant Selection ation and Use of Core Social ce d'une infrastructure SIG and Economic Statistics BF-INSD-284566-CS-INDV / r Regional component: Harmo ecrutement d'un consultant i nization, Data Collection, Qu Individual Consult ndividuel pour la formation d IDA / 65730 ality Improvement, Dissemin Post Limited 3,818.00 0.00 Canceled 2022-06-01 2022-06-06 2022-06-20 2022-07-09 2022-07-30 ant Selection u personnel du service charg ation and Use of Core Social é de la diffusion en communi and Economic Statistics cation digitale Regional component: Harmo BF-INSD-177233-CS-INDV / A nization, Data Collection, Qu Individual Consult ctualisation du schéma direct IDA / 65730 ality Improvement, Dissemin Post Open 15,000.00 0.00 Canceled 2020-06-30 2020-08-03 2020-08-18 2020-09-09 2020-11-08 ant Selection eur informatique de l'INSD ation and Use of Core Social and Economic Statistics BF-INSD-216671-CS-INDV / C Regional component: Harmo onsultants pour l'élaboration nization, Data Collection, Qu Individual Consult des cahiers de charge de la p IDA / 65730 ality Improvement, Dissemin Post Open 54,500.00 0.00 Canceled 2021-06-16 2021-08-04 2021-08-25 2021-09-29 2021-10-05 ant Selection lateforme de collecte des DS ation and Use of Core Social F and Economic Statistics BF-INSD-177212-CS-INDV / S Regional component: Harmo élection de consultants indivi nization, Data Collection, Qu Individual Consult duels pour la formation conti IDA / 65730 ality Improvement, Dissemin Post Open 28,570.00 0.00 Canceled 2021-06-30 2021-08-03 2021-08-18 2021-09-09 2021-10-09 ant Selection nue sur les nouvelles techniq ation and Use of Core Social ues de production et d'analys and Economic Statistics e des données Regional component: Harmo BF-INSD-340832-CS-CDS / El nization, Data Collection, Qu Direct - Internation Pending Impleme aboration d'une feuille de rou IDA / 65730 ality Improvement, Dissemin Post Direct Selection 36,364.00 0.00 2023-07-25 2023-08-04 2023-08-25 2023-11-23 al ntation te de révolution des données ation and Use of Core Social and Economic Statistics BF-INSD-347451-CS-INDV / R Regional component: Harmo ecrutement d'un assistant te nization, Data Collection, Qu Individual Consult Under Implement chnique pour l'accompagnem IDA / 65730 ality Improvement, Dissemin Post Direct - National 32,727.27 0.00 2023-04-20 2023-04-10 2023-04-30 2023-05-07 2023-05-17 2023-06-16 ant Selection ation ent à la réalisation du recens ation and Use of Core Social ement des structures éducati and Economic Statistics ves du MENAPLN BF-INSD-347458-CS-INDV / R ecrutement d'un consultant i Country-Specific Component ndividuel pour la conception : Improving and modernizing Individual Consult Under Implement de la base de données de sui IDA / 65730 Post Limited 22,545.45 0.00 2023-05-05 2023-04-10 2023-05-10 2023-05-17 2023-05-29 2023-07-28 physical and statistical infra ant Selection ation vi de la conjoncture (BDSC) s structure ous MS Access et renforceme nt des capacités des agents à sa gestion BF-INSD-351473-CS-INDV / R Regional component: Harmo ecrutement d'un consultant i nization, Data Collection, Qu ndividuel en vue de développ Individual Consult Under Implement IDA / 65730 ality Improvement, Dissemin Post Limited 36,363.63 0.00 2023-05-15 2023-04-10 2023-05-20 2023-06-03 2023-06-15 2023-08-14 er les capacités de l'INSD à l' ant Selection ation ation and Use of Core Social utilisation des mégadonnées and Economic Statistics dans la production statistiqu e BF-INSD-351485-CS-INDV / R Regional component: Harmo ecrutement d'un consultant p nization, Data Collection, Qu Individual Consult Direct - Internation Under Implement our l'élaboration d'un nouvea IDA / 65730 ality Improvement, Dissemin Post 49,636.36 0.00 2023-05-15 2023-04-10 2023-05-25 2023-06-08 2023-06-29 2023-09-27 ant Selection al ation u modèle de prévision des re ation and Use of Core Social cettes and Economic Statistics Page 9 BF-INSD-360203-CS-INDV / R Regional component: Harmo ecrutement d'un consultant i nization, Data Collection, Qu Individual Consult Pending Impleme ndividuel pour l'élaborer la c IDA / 65730 ality Improvement, Dissemin Post Limited 36,363.63 0.00 2023-07-20 2023-07-25 2023-08-15 2023-09-05 2023-11-04 ant Selection ntation artographie des risques de l'I ation and Use of Core Social NSD assorti d'un plan de miti and Economic Statistics gation BF-INSD-360357-CS-INDV / R ecrutement d'un consultant i Project Management and Mo Individual Consult Under Implement IDA / 65730 Post Limited 36,363.63 0.00 2023-06-20 2023-06-02 2023-06-25 2023-07-16 2023-08-06 2023-09-20 ndividuel pour réaliser l'évalu nitoring and Evaluation ant Selection ation ation à mi-parcours du PHAS AO Page 10 Procurement Plan Project information: FSM Strategic Climate-Oriented Road Enhancements (P177073) Project Implementation agency: Department of Transport, Communications and Infrastructure (DoTC&I) Date of the Procurement Plan: August 31, 2021 Period covered by this Procurement Plan: September 1, 2021 – August 31, 2021 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the Procurement Code of 1988, as amended, and Financial Management Regulations, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions: 1. The procurement is open to all eligible firms from any country; 2. The request for bids/request for proposals document shall require the Bidders/Proposers submitting Bids/Proposals present a signed acceptance at the time of bidding, to be incorporated in any resulting signed contracts, confirming application of, and compliance with, the Bank's Anti-Corruption Guidelines, including without limitation the Bank's right to sanction and the Bank's inspection and audit rights; 3. Publication of contract award information; 4. Rights for the Bank to review procurement documentation and activities; and 5. An effective complaints mechanism. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Not Applicable Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations: Not Applicable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Work) Goods: is not applicable; Works: is not applicable. PROCUREMENT Micronesia, Federated States of : Federated States of Micronesia Strategic Climate-Oriented Road Enhancements PLAN General Information Country: Micronesia, Federated States of 2022-05-09 Bank’s Approval Date of the Original Procurement Plan: 2023-06-02 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P177073 GPN Date: 2022-10-05 Project Name: Federated States of Micronesia Strategic Climate-Oriented Road Enhancements Loan / Credit No: IDA / D9710 Department of Transportation, Communications and Infrastructure Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual FM-DOTCI-288698-GO-RFB / Component 3: Strengthening Open - Internationa Single Stage - One E Pending Impl IDA / D9710 Prior Request for Bids 500,000.00 0.00 2024-06-03 2024-06-08 2024-07-20 2024-08-19 2024-09-23 2025-03-22 Goods for Materials Testing L the Enabling Environment l nvelope ementation ab NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual FM-DOTCI-293024-CS-CQS / Institutional and Governance Component 3: Strengthening Quality And Cost- Open - Internationa IDA / D9710 Prior 706,665.00 0.00 Canceled 2022-05-31 2022-06-17 2022-06-21 2022-08-30 2022-08-04 2022-09-01 2022-10-01 2022-11-05 2022-12-10 2022-12-28 Review and Sustainable Moto the Enabling Environment Based Selection l rization Management FM-DOTCI-288706-CS-QCBS Component 3: Strengthening Quality And Cost- Open - Internationa Under Implement / Gender Capacity Developm IDA / D9710 Prior 570,000.00 0.00 2022-09-30 2022-11-16 2022-10-21 2023-01-17 2022-12-04 2023-01-01 2023-01-31 2023-03-07 2023-04-11 2024-04-10 the Enabling Environment Based Selection l ation ent and Training FM-DOTCI-292162-CS-QCBS / Design, Environmental and Component 3: Strengthening Quality And Cost- Open - Internationa Social Assessment, and Supe IDA / D9710 Prior 2,700,000.00 0.00 Canceled 2022-05-02 2022-05-23 2022-07-06 2022-08-03 2022-09-02 2022-10-07 2022-11-11 2023-11-11 the Enabling Environment Based Selection l rvision Services for Vulnerabi lity Assessment - identified w orks FM-DOTCI-320297-CS-QCBS / Design, Environmental and Component 2: Climate Resili Quality And Cost- Open - Internationa Under Implement Social Assessment, and Supe IDA / D9710 Prior 7,272,410.00 0.00 2022-11-10 2022-11-18 2022-12-01 2023-02-28 2023-01-14 2023-02-11 2023-03-13 2023-04-17 2023-05-22 2024-05-21 ent Infrastructure Solutions Based Selection l ation rvision Services for Vulnerabi lity Assessment-idenified wor ks FM-DOTCI-327642-CS-QCBS / Sustainable Motorization Ma Component 3: Strengthening Quality And Cost- Open - Internationa Under Implement IDA / D9710 Prior 510,000.00 0.00 2022-12-31 2023-01-09 2023-01-21 2023-02-08 2023-03-06 2023-04-03 2023-05-03 2023-06-07 2023-07-12 2024-07-11 nagement Diagnostic and Im the Enabling Environment Based Selection l ation plementation Plan FM-DOTCI-349011-CS-QCBS / Enhancement of Science, T Component 3: Strengthening Quality And Cost- Open - Internationa Under Implement IDA / D9710 Post 400,000.00 0.00 2023-03-15 2023-05-11 2023-04-05 2023-06-11 2023-05-19 2023-06-16 2023-07-16 2023-08-20 2023-09-24 2024-09-23 echnology, Engineering and the Enabling Environment Based Selection l ation Mathematics (STEM) FM-DOTCI-288693-CS-CQS / Component 1: Spatial and S Consultant Qualifi Open - Internationa Under Implement IDA / D9710 Post 200,000.00 0.00 2023-04-03 2023-04-11 2023-04-24 2023-06-07 2023-07-07 2023-08-11 2024-02-07 Road Crash Database Consul ector Planning Tools cation Selection l ation tant INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual FM-DOTCI-288700-CS-INDV / Component 3: Strengthening Individual Consult IDA / D9710 Prior Open 400,000.00 0.00 Under Review 2022-09-01 2023-05-04 2022-10-20 2022-11-10 2022-12-15 2024-12-14 Transport Data Collection Co the Enabling Environment ant Selection nsultant FM-DOTCI-288701-CS-INDV / Component 3: Strengthening Individual Consult Under Implement IDA / D9710 Post Open - National 120,000.00 0.00 2023-06-05 2023-04-11 2023-07-24 2023-08-14 2023-09-18 2025-09-17 Transport Data Collection - Y the Enabling Environment ant Selection ation ap FM-DOTCI-288702-CS-INDV / Component 3: Strengthening Individual Consult Under Implement IDA / D9710 Post Open - National 120,000.00 0.00 2023-06-05 2023-04-11 2023-07-24 2023-08-14 2023-09-18 2025-09-17 Transport Data Collection - K the Enabling Environment ant Selection ation osrae FM-DOTCI-288703-CS-INDV / Component 3: Strengthening Individual Consult Under Implement IDA / D9710 Post Open - National 120,000.00 0.00 2023-06-05 2023-04-11 2023-07-24 2023-08-14 2023-09-18 2025-09-17 Transport Data Collection - C the Enabling Environment ant Selection ation huuk FM-DOTCI-288704-CS-INDV / Component 3: Strengthening Individual Consult Under Implement Transportation Data Collectio IDA / D9710 Post Open - National 120,000.00 0.00 2023-06-05 2023-04-11 2023-07-24 2023-08-14 2023-09-18 2025-09-17 the Enabling Environment ant Selection ation n - Pohnpei FM-DOTCI-288695-CS-INDV / Component 3: Strengthening Individual Consult Pending Impleme Technical Officer will provide IDA / D9710 Prior Open - National 360,000.00 0.00 2023-12-04 2024-01-22 2024-02-12 2024-03-18 2025-03-18 the Enabling Environment ant Selection ntation technical assistance to PIU. FM-DOTCI-288697-CS-INDV / Component 3: Strengthening Individual Consult Open - Internationa Pending Impleme Consultant to the Establishm IDA / D9710 Post 150,000.00 0.00 2024-02-05 2024-03-25 2024-04-15 2024-05-20 2025-05-20 the Enabling Environment ant Selection l ntation ent of Material Testing Labor atory Page 1 FM-DOTCI-356433-CS-INDV / Component 3: Strengthening Individual Consult Under Implement IDA / D9710 Post Open - National 140,000.00 0.00 2023-04-22 2023-05-22 2023-06-10 2023-07-01 2023-08-05 2024-02-01 Transport Data Deputy Mana the Enabling Environment ant Selection ation ger FM-DOTCI-288696-CS-INDV / Component 3: Strengthening Individual Consult Policy & Law Review Relating IDA / D9710 Post Open 200,000.00 0.00 Canceled 2022-09-01 2022-10-20 2022-11-10 2022-12-15 2023-06-13 the Enabling Environment ant Selection to Land Easement for Works Page 2 Procurement Plan I. General 1. Bank’s approval Date of the procurement Plan: May 20, 2017 2. Date of General Procurement Notice: Oct. 10, 2016 3. Period covered by this procurement plan: The whole project period II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Procurement Method Prior Review Comments Threshold US$ 1. ICB and LIB (Goods) 4 million 2. NCB (Goods) 4 million 3. ICB (Works) 15 million 4. NCB (Works) 15 million 5. (Non-Consultant Services) 4 million [Add other methods if necessary] 2. Prequalification. _Not applicable_. 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: Not applicable 4. Reference to (if any) Project Operational/Procurement Manual: Not applicable 5. Any Other Special Procurement Arrangements: Advance procurement and retroactive financing 6. Summary of the Procurement Packages planned during the first 18 months after project effectiveness ( including those that are subject to retroactive financing and advanced procurement) 1 2 3 4 5 6 7 Ref. Descripti Estimat Packages Dome Review Comme No. on ed stic by Bank nts Cost Prefe (Prior / July 9, 2010 US$ rence Post) million (yes/ no) Summary 0 0 N/A N/A of the ICB (Works) Summary 0 0 N/A N/A of the ICB (Goods) Summary 150.47 10 No Prior / of the NCB Post (Works) Summary 50.40 12 No Prior / of the NCB Post (Goods) Summary 0 0 N/A N/A of the ICB (Non- Consultant Services) III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Comments Threshold 1. Competitive Methods (Firms) US$2 million 2. Single Source (Firms) US$1 million 3. Individual US$0.4 million 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $500,000 equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: Not applicable 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 Ref. No. Description Estimat Package Review Comment of ed s by Bank s Assignmen Cost (Prior / t US$ Post) million Summary 0.51 1 Post July 9, 2010 of number of contracts that will be let under QCBS Summary 1.82 12 Post of number of contracts that will be let under other methods July 9, 2010 PROCUREMENT China : Three Gorges Modern Logistics Center Infrastructure Project PLAN General Information Country: China 2018-05-18 Bank’s Approval Date of the Original Procurement Plan: 2023-06-07 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P153473 GPN Date: Project Name: Three Gorges Modern Logistics Center Infrastructure Project Loan / Credit No: IBRD / 87660 Yi Chang PMO Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GK-C1 / Construction Works Baiyang Port and operations Single Stage - One E 12,851,093. for 8#-11# Berths and 7#-11 IBRD / 87660 Prior Request for Bids Open - National 0.00 Signed 2017-11-11 2017-12-08 Area nvelope 41 # Land Territories GK-C2 / Road, architectural, port, electric, communication Baiyang Port and operations Single Stage - One E 27,220,000.0 21,228,646. 2020-12-2 , water supply & drainage, en IBRD / 87660 Prior Request for Bids Open - National Signed 2019-04-25 2019-05-18 2019-04-30 2019-05-30 2019-06-20 2019-06-06 2019-07-18 2019-07-04 2019-07-16 Area nvelope 0 20 5 vironmental protection works and temporary works in Stor age Yard 7#, 12# and 13#. WL-C3 / Intelligent Cargo Dis tributing Center: 1 Building ( 21,000m2) and electric, com Single Stage - One E 15,998,784. 2020-03-2 IBRD / 87660 Baiyang Logistics Park Post Request for Bids Open - National 9,670,000.00 Signed 2019-06-10 2020-09-15 2019-06-15 2019-07-27 2021-03-11 2019-08-26 2021-03-11 2019-09-30 2021-09-02 munications, water supply & nvelope 73 8 drainage, fire-fighting and en vironmental protection, etc i n Building. DJ-C1 / Roadbed (earthwork & foundation treatment), pav ement (carriageway, sidewal Transport Connection Infrast Single Stage - One E 4,655,609.8 2020-06-0 IBRD / 87660 Prior Request for Bids Open - National 7,400,000.00 Signed 2019-08-16 2020-06-29 2019-08-21 2019-10-02 2016-12-27 2019-11-01 2020-08-06 2019-12-06 2017-05-16 k & auxiliaries), traffic, culver ructure nvelope 7 3 ts, lighting, integrated pipe n etwork and drainage in Guih u Road & 2nd Songgang Roa d. WL-C4 / 1. Containing Devan ing & Loading Warehouse: 2 buildings (10,600m2). 2. Foo dstuff Warehouse: 3 building Single Stage - One E 14,940,000.0 12,435,211. 2020-06-0 IBRD / 87660 Baiyang Logistics Park Prior Request for Bids Open - National Signed 2019-08-15 2020-08-14 2019-08-20 2019-10-01 2017-08-08 2019-10-31 2020-08-21 2019-12-05 2017-11-02 s (19,300m2). 3. Processing nvelope 0 33 2 Factory: 2 buildings (4,600m 2). 4. Parking Lot: Road (12,9 00m2). 5.W1 Container Yard. 6. W1~3# Substation(1800m 2). 7.Earthwor DJ-C2 / Roadbed (earthwork & foundation treatment), pav ement (carriageway, sidewal Baiyang Port and operations Single Stage - One E 11,060,000.0 9,665,753.9 2021-06-0 k & auxiliaries), bridge, retai IBRD / 87660 Post Request for Bids Open - National Signed 2020-08-13 2017-06-02 2020-08-18 2020-09-29 2017-07-04 2020-10-29 2017-07-04 2020-12-03 2017-07-29 Area nvelope 0 0 1 ning wall, traffic, culverts, lig hting, integrated pipe networ k and drainage in Shawan Ro ad Overpass. WL-C3-2020 / Intelligent Car go Distributing Center: 1 Bui lding (21,000m2) and electric Single Stage - One E 18,380,000.0 Under Imple 2021-07-0 IBRD / 87660 Baiyang Logistics Park Prior Request for Bids Open - National 0.00 2020-09-15 2020-10-23 2020-09-20 2020-11-01 2021-03-11 2020-12-01 2021-08-04 2021-01-05 , communications, water sup nvelope 0 mentation 4 ply & drainage, fire-fighting a nd environmental protection, etc in Building. WL-C9 / Earthwork excavatio n and backfilling within 890 Request for Bids - mu of area A and B of Comm Single Stage - One E Works (without pr 13,846,153.0 Under Imple 2022-03-0 IBRD / 87660 Baiyang Logistics Park Post Request for Bids Open - National 0.00 2021-05-20 2021-05-27 2021-05-25 2021-07-06 2021-06-30 2021-08-05 2021-06-30 2021-09-09 erce and trade logistics ,unfi nvelope equalification) SP 0 mentation 8 nished subgrade and pavem D ent and supporting works of Guihu road and 2nd Songgan g road. WL-C5 / 1. Si Cheng apartme nt; 2. number 1: comprehens Request for Bids - ive warehouse (1 building); 3 Single Stage - One E Works (without pr 12,500,000.0 Under Imple 2022-04-0 . Building electrical, commun IBRD / 87660 Baiyang Logistics Park Post Request for Bids Open - National 0.00 2021-06-15 2021-08-05 2021-06-20 2021-08-01 2021-09-07 2021-08-31 2021-09-07 2021-10-05 nvelope equalification) SP 0 mentation 3 ication, water supply and dra D inage, fire protection, enviro nmental protection engineeri ng and earthwork Road site. WL-C2 / The scope of this bi dding mainly covers the civil Request for Bids - works of commercial area B Single Stage - One E Works (without pr 37,094,281.0 2022-06-2 of the world bank loan projec IBRD / 87660 Baiyang Logistics Park Prior Request for Bids Open - National 0.00 Signed 2021-09-09 2021-11-17 2021-09-14 2021-10-26 2021-12-20 2021-11-25 2022-09-02 2021-12-30 nvelope equalification) SP 0 8 t, including 2 processing plan D ts, 2 warehouses, 1 office bui lding, 2 power distribution su bstations and 1 fire pump ho use. WL-C1 / 1. Commercial ware house (3 ); 2. Processing plan t (3 ); 3. Exhibition and tradin Request for Bids - g center (1 ); 4. Office buildin Single Stage - One E Works (without pr 38,460,000.0 2022-09-0 IBRD / 87660 Baiyang Logistics Park Prior Request for Bids Open - National 0.00 Signed 2021-11-15 2022-06-14 2021-11-20 2022-01-01 2022-08-02 2022-01-31 2022-09-07 2022-03-07 g (1 ); 5. Substation (2 sets); nvelope equalification) SP 0 3 6. Roads, storage yards and D parking lots; 7. Underground hydropower, pipe network,el ectrical, communication WL-C2-NEW / The scope of t his bidding mainly covers the Request for Bids - civil works of commercial are Single Stage - One E Works (without pr 37,094,281.0 2023-04-2 a B of the world bank loan pr IBRD / 87660 Baiyang Logistics Park Prior Request for Bids Open - National 0.00 Canceled 2022-07-11 2022-07-16 2022-08-27 2022-09-26 2022-10-31 nvelope equalification) SP 0 9 oject, including 2 processing D plants, 2 warehouses, 1 offic e building, 2 power distributi on substations and 1 fire pu mp house. Request for Bids - XX-C1. / Information Center ( Baiyang Logistics Informatio Single Stage - One E Works (without pr Pending Imp 2024-03-2 IBRD / 87660 Post Request for Bids Open - National 1,428,571.00 0.00 2023-06-07 2023-06-12 2023-07-24 2023-08-23 2023-09-27 Decoration and Construction) n Platform and Facilities nvelope equalification) SP lementation 5 D GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 1 GK-G6 / 30 Mobile Belt Conv eyors L=15m; 144m Belt Con Baiyang Port and operations Single Stage - One E veyors IBRD / 87660 Post Request for Bids Open - National 734,200.00 0.00 Canceled 2019-07-30 2019-08-27 2019-08-04 2019-09-03 2019-08-27 2019-10-03 2019-08-27 2019-11-07 2020-05-05 Area nvelope B1200, V2.0m/s, 2 electric wi nches 3T GK-C3 / 1360m windproof an Baiyang Port and operations Request for Quota Single Stage - One E IBRD / 87660 Post Open - National 198,200.00 197,816.75 Signed 2019-08-21 2019-10-16 2019-10-01 2020-04-13 d dust suppression net, 8m h Area tions nvelope igh GK-G4 / Port transfer equipm Baiyang Port and operations Single Stage - One E IBRD / 87660 Prior Request for Bids Open - National 4,540,000.00 5,011,254.40 Signed 2020-05-01 2021-03-04 2020-05-06 2020-06-17 2021-04-16 2020-07-17 2021-04-27 2020-08-21 2021-06-08 2021-02-17 ent (Berths#10-#11) Area nvelope GK-G3 / 8 #9# berth:90 × 1 4 m steel Barges, 2 vessels Baiyang Port and operations Single Stage - One E 600t/h circular track loaders, IBRD / 87660 Prior Request for Bids Open - National 8,249,027.00 6,835,909.10 Signed 2021-05-23 2021-06-01 2021-05-28 2021-07-09 2021-08-24 2021-08-08 2021-11-02 2021-09-12 2021-12-08 2022-03-11 Area nvelope 2 sets; belt conveyors, 7 sets , 1584m; 3T electric hoist, 3 sets. GK-G2 / 2 sets of 40t-30m p ortal cranes, 1 set of 16t-30 m portal crane, 1 set of 45t-2 Baiyang Port and operations Single Stage - One E IBRD / 87660 Prior Request for Bids Open - National 8,093,385.00 7,930,883.30 Terminated 2021-05-23 2021-07-09 2021-05-28 2021-07-09 2021-08-25 2021-08-08 2021-11-17 2021-09-12 2021-12-24 2022-03-11 5m quayside container bridg Area nvelope e crane, 2 sets of 40t-30m R ail Gantry Cranes, 4 sets of 1 6t-22.5m bridge cranes GK-G1 / 1 tire crane 50t, 2 ti re cranes 30t; 2 sets of tire c Baiyang Port and operations Single Stage - One E IBRD / 87660 Prior Request for Bids Open - National 6,800,000.00 0.00 Signed 2021-11-05 2022-02-21 2021-11-10 2021-12-22 2022-07-06 2022-01-21 2022-08-31 2022-02-25 2023-04-12 2022-08-24 ranes 16t; 4 container front c Area nvelope ranes and 4 container straddl e carriers WL-G6 / Rail mounted contai Single Stage - One E ner gantry crane 45t-40m fiv IBRD / 87660 Baiyang Logistics Park Prior Request for Bids Open - National 9,230,000.00 0.00 Signed 2021-11-10 2022-02-21 2021-11-15 2021-12-27 2022-07-04 2022-01-26 2022-08-16 2022-03-02 2022-08-29 nvelope e Rail mounted gantry crane 16t-40m two WL-G5 / Rail mounted contai Single Stage - One E ner gantry crane 45t-40m fiv IBRD / 87660 Baiyang Logistics Park Prior Request for Bids Open - National 9,850,000.00 0.00 Signed 2021-11-10 2022-02-21 2021-11-15 2021-12-27 2022-07-05 2022-01-26 2022-08-16 2022-03-02 2022-08-29 nvelope e Rail mounted gantry crane 40t-40m two WL-G1 / Bridge crane 32t-19 .5m eight 16t-28.5m eight 16t-19.5m eight Electric sin Single Stage - One E Under Imple IBRD / 87660 Baiyang Logistics Park Post Request for Bids Open - National 3,730,000.00 0.00 2021-11-12 2021-12-15 2021-11-17 2021-12-29 2022-07-13 2022-01-28 2022-03-04 2022-08-31 gle beam crane 5t-16.5m two nvelope mentation Embedded boarding axle 1 0t seventy-six Electronic tru ck scale 150t seven WL-G2 / Forklift 5t 10 3t 27 2t ,21 Single bucket loader ZL50 ,14 tractor Q45,18 Fla Single Stage - One E t car PC40 36 tractor Q20 IBRD / 87660 Baiyang Logistics Park Prior Request for Bids Open - National 8,170,000.00 0.00 Signed 2021-11-12 2022-02-21 2021-11-17 2021-12-29 2022-07-12 2022-01-28 2022-08-30 2022-03-04 2022-08-31 nvelope 18 Flat car P20 36 ,Contai ner tractor 40 Container se mitrailer 40 feet 20 Dump truck 55t 24. GK-G9 / Two 40t-30m gantry cranes, two 16t-30m gantry c ranes, one 45t-25m quayside Baiyang Port and operations Single Stage - One E container bridge crane, two 4 IBRD / 87660 Prior Request for Bids Open - National 11,540,000.00 0.00 Canceled 2022-09-20 2022-10-15 2022-11-06 2022-12-06 2023-01-10 2023-07-09 Area nvelope 0t-30m Rail Gantry Cranes, o ne multipurpose gantry cran e (45t-30m), and four 16t-22. 5m bridge cranes GK-G9. / includes the manuf acturing, installation, commis sioning, inspection and final delivery of two 40t-30m port Baiyang Port and operations Open - Internationa Single Stage - One E IBRD / 87660 Prior Request for Bids 10,563,380.00 0.00 Canceled 2022-10-15 2022-11-18 2022-10-20 2022-12-01 2022-12-31 2023-02-04 2023-08-03 al cranes, two 16t-30m portal Area l nvelope cranes, one 45t-25m quaysid e container bridge crane, one 45t-30m multi-purpose portal crane, etc. GK-G9-NEW / includes the m anufacturing, installation, co mmissioning, inspection and Baiyang Port and operations Open - Internationa Single Stage - One E Under Imple final delivery of two 40t-30m IBRD / 87660 Prior Request for Bids 9,285,700.00 0.00 2023-01-17 2023-01-19 2023-01-22 2023-03-05 2023-03-10 2023-04-04 2023-04-27 2023-05-09 2023-11-05 Area l nvelope mentation portal cranes, one 45t-25m q uayside container bridge cra ne, one 45t-30m multi-purpo se portal crane, etc. XX-G1 / Information Center ( Baiyang Logistics Informatio Single Stage - One E Under Imple IBRD / 87660 Prior Request for Bids Open - National 9,285,714.00 0.00 2023-06-01 2023-06-02 2023-06-06 2023-07-18 2023-08-17 2023-09-21 2024-03-19 Information Construction) n Platform and Facilities nvelope mentation XX-C1 / Information Center ( Baiyang Logistics Informatio Single Stage - One E IBRD / 87660 Post Request for Bids Open - National 1,428,571.00 0.00 Canceled 2023-06-05 2023-06-10 2023-07-22 2023-08-21 2023-09-25 2024-03-23 Decoration and Construction) n Platform and Facilities nvelope NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NL-S7 / To develop research about "Business Model & Ope Quality And Cost- Open - Internationa IBRD / 87660 Capacity Building Prior 538,000.00 0.00 Signed 2018-07-19 2018-08-09 2018-07-23 2018-08-30 2019-04-10 2018-09-06 2019-05-15 2018-09-13 2019-08-12 2018-09-30 2023-04-17 2018-10-28 2020-04-20 ration Schedule of Baiyang P Based Selection l ort & Logistics Park" INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 2 NL-S1 / To provide support a bout Architectural Engineerin Individual Consult Pending Impleme IBRD / 87660 Capacity Building Post Open 29,400.00 0.00 2019-06-15 2019-08-03 2019-08-24 2019-09-28 2020-03-26 g to Project Office during imp ant Selection ntation lementation period. NL-S2 / To provide support a bout Port & Harbor Engineeri Individual Consult Pending Impleme IBRD / 87660 Capacity Building Post Open 22,000.00 0.00 2019-06-15 2019-08-03 2019-08-24 2019-09-28 2020-03-26 ng to Project Office during im ant Selection ntation plementation period. Page 3